Project: City of Pleasanton Sewer Capital Implementation Plan Capital Improvement Projects
20-Year Plan -- Scenario 2 Funded By Priority

Capital Improvement Project Notes:

1) Estimated Total Capital Cost is derived from “Table 9: Cost Sharing for Scenario 3 CIP” from the Technical Memorandum dated February 11, 2025 concerning the East Pleasanton Annexation. Costs assume that development of the Kiewit property will contribute $222,275 in payment while balance will be funded by the Arroyo Lago development.

2) Estimated Total Capital Cost is derived from “Table 12: Pro-Rata Cost Sharing Scenario 6 CIP” from the Technical Memorandum dated February 11, 2025 concerning the East Pleasanton Annexation. Costs assume that Project 4B costs will be the Total of all developments (Kiewit North, Site H, East Lakes, Arroyo Lago, and Amazon) minus the Project 4A cost (Kiewit North and Arroyo Lago). The City will seek funding from developments as applications are processed or will seek construction of these projects from the first development with reimbursements made to others on a pro rata share basis as others connect.

3) Priority A Lift Station projects encompass all Criticality 2 and 3 improvements, while Priority B represents Criticality 1 (included in rehabilitation projects), as identified in the 2024 LS Condition Assessment TM.

4) At the time of this project, a redundant siphon will also be installed. Costs include demolition of existing station and assumes full replacement, including cutover costs from the old to new station.

5) Includes all sewer and stormwater generators identified in the TJC Report (2023).

6) Pipeline Replacement includes replacement and repair (R&R) of high priority pipes and an allowance for future R&R work, as well as CCTV inspection and Sewer AI for pipes. This money can also be spent on other high priority assets like force mains, siphons, or large diameter sewers as needed depending on the findings of condition assessment efforts.

7) City funded work to be performed by DSRSD. CIP assumes EALS will be rehabilitated, and the EARS LS and associated piping will be installed to supplement this rehabilitated lift station

8) Estimation of $200,000 for abandonment of Lift Stations currently not in service.

9) Major rehabilitation costs for lift stations were estimated based on the lift station's pump horse power and flow rate. A more refined cost estimate will be developed based on the extent of the rehabilitation required at each station prior to construction.

10) This line item is an allowance for the replacement or rehab of sewer siphons, forcemains, and large diameter sewers that are inspected as part of the Priority A analysis work. This cost will be refined as the analysis is completed

11) LS-14 Rehabilitation will take place under separate CIP funding, and therefore not included in this spreadsheet.

12) The SSMP will make subsequent recommendations about the scope and schedule of future condition assessment work, including CCTV, force main inspection, and manhole inspections.

Page 394 of 408 ends

$0
$2
$4
$6
$8
$10
$12
$14 CIP Cost ($M)
CIP Implementation - Scenario 2
FTE Priority C Priority B Priority A

Page 395 of 408 ends

City of Pleasanton Sewer Capital Implementation Plan20-Year Plan -- Scenario 3 Maximum Deferrals Long Term
Capital Projects Notes Estimated Total
Capital Cost FY 25-26 FY 26-27 FY 27-28 FY 28-29 FY 29-30 FY 30-31 FY 31-32 FY 32-33 FY 33-34 FY 34-35 FY 35/36 - FY 44/45
Existing
Customers
Future
Customers
Priority A - Capacity & Reliability Improvement Projects Project 1B: Upsize Sunol Blvd Sewers preferred alt $1,600,000 790,000$ 810,000$ - $ - $ - $ - $ - $ - $ - $ - $ -$ 1,600,000$ -$ Project 2A: Bernal Ave Pipe Bridge preferred alt $3,330,000 - $ 400,000$ 2,930,000$ - $ - $ - $ - $ - $ - $ - $ -$ 3,330,000$ -$ Project 3: Upsize Pipes downstream of Stoneridge Mall $3,660,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ -$ -$ 3,660,000$ Project 4A: East Pleasanton Capacity Project A (Kiewit and Arroyo Lago) Note 1 $2,972,000 - $ - $ - $ - $ 222,275$ - $ - $ - $ - $ - $ -$ 222,275$ 2,749,725$ Project 4B: East Pleasanton Capacity Project B (Amazon, East Lakes, Site H)
Note 2 $4,314,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ -$ -$ 4,314,000$ Priority A - Lift Station Projects
LS-02, -07, -08, -10 Improvements Note 3 $1,420,000 - $ - $ - $ - $ - $ 1,420,000$ - $ - $ - $ - $ -$ 1,420,000$ -$ LS-04, -12, -13, -15 Improvements Note 3 $940,000 - $ - $ - $ - $ - $ 470,000$ 470,000$ - $ - $ - $ -$ 940,000$ -$ LS-05 Full Replacement Project Note 4 $6,120,000 - $ - $ 810,000$ 5,310,000$ - $ - $ - $ - $ - $ - $ -$ 6,120,000$ -$ EARS and EALS Condition Assessment, Capacity Evaluation, and Predesign $500,000 250,000$ 250,000$ - $ - $ - $ - $ - $ - $ - $ - $ -$ 500,000$ -$ Generator Replacement - Sewer and Storm
Note 5 $9,860,000 150,000$ 1,710,000$ - $ 1,000,000$ 3,000,000$ - $ 1,000,000$ 3,000,000$ - $ - $ -$ 9,860,000$ -$ Priority A - Condition Assessment Projects
Pipeline Replacement (1-2 mile of system) Note 6 $6,615,000 - $ 315,000$ 2,100,000$ 2,100,000$ 2,100,000$ - $ - $ - $ - $ - $ -$ 6,615,000$ -$ Amberwood Siphon $3,330,000 - $ - $ - $ 270,000$ 3,060,000$ - $ - $ - $ - $ - $ -$ 3,330,000$ -$ Priority A - Annual Sewer System Improvements for Resurfacing $1,050,000 - $ - $ 350,000$ 350,000$ 350,000$ - $ - $ - $ - $ - $ -$ 1,050,000$ -$ Large Diameter Inspection Study $150,000 - $ 150,000$ - $ - $ - $ - $ - $ - $ - $ - $ -$ 150,000$ -$ Denker Road Sewer Replacement $1,650,000 150,000$ 1,500,000$ - $ - $ - $ - $ - $ - $ - $ - $ -$ 1,650,000$ -$ Cathodic Protection and I&I Studies $150,000 - $ 150,000$ - $ - $ - $ - $ - $ - $ - $ - $ -$ 150,000$ -$ Cathodic Protection Installation $9,000,000 - $ - $ 500,000$ 500,000$ 500,000$ 500,000$ 500,000$ 500,000$ 500,000$ 500,000$ 5,000,000$ 9,000,000$ -$ Force Main Desktop Analysis and Inspections $704,000 104,000$ 300,000$ 300,000$ - $ - $ - $ - $ - $ - $ - $ -$ 704,000$ -$ $57,365,000 1,444,000$ 5,585,000$ 6,990,000$ 9,530,000$ 9,232,275$ 2,390,000$ 1,970,000$ 3,500,000$ 500,000$ 500,000$ 5,000,000$ 46,641,275$ 10,723,725$ Priority B - Lift Station Projects
Health and Safety Signage $10,000 - $ - $ - $ - $ - $ - $ 10,000$ - $ - $ - $ -$ 10,000$ -$ EALS R&R Note 7 $4,000,000 - $ - $ - $ - $ - $ 520,000$ 3,480,000$ - $ - $ - $ -$ 4,000,000$ -$ EARS LS Note 7 $8,412,000 - $ - $ - $ - $ - $ - $ - $ - $ 1,093,560$ 7,318,440$ -$ 8,412,000$ -$ EARS LS Piping Note 7 $1,647,000 - $ - $ - $ - $ - $ - $ - $ 214,110$ 1,432,890$ - $ -$ 1,647,000$ -$ LS-03, -09, 11 Abandonment Note 8 $600,000 - $ - $ - $ - $ - $ - $ 600,000$ - $ - $ - $ -$ 600,000$ -$ LS-06 Major Rehabilitation Note 9 $2,890,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ $2,890,000 2,890,000$ -$ LS-08 Major Rehabilitation Note 9 $3,120,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 3,120,000$ 3,120,000$ -$ LS-07 Major Rehabilitation Note 9 $3,700,000 - $ - $ - $ - $ - $ - $ 481,000$ 3,219,000$ - $ - $ -$ 3,700,000$ -$ Priority B - Condition Assessment Projects
Priority B - Pipeline Replacement (1-2 mile of system) Note 6 $12,500,000 - $ - $ - $ - $ - $ 2,500,000$ 2,500,000$ 2,500,000$ 2,500,000$ 2,500,000$ $0 12,500,000$ -$ Priority B - Large Diameter Pipe and Force Main Rehab Note 10 $6,000,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ $6,000,000 6,000,000$ -$ Priority B - Sewer Siphon Replacement Note 10 $3,330,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ $3,330,000 3,330,000$ -$ Priority B - Annual Sewer System Improvements for Resurfacing Note 10 $1,650,000 - $ - $ - $ - $ - $ 350,000$ 350,000$ 350,000$ 350,000$ 350,000$ -$ 1,650,000$ -$ $47,859,000 - $ - $ - $ - $ - $ 3,370,000$ 7,421,000$ 6,283,110$ 5,376,450$ 10,168,440$ 15,340,000$ 47,859,000$ -$ Priority C - Lift Station Projects11
LS-02 Major Rehabilitation Note 9 $750,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 750,000$ $750,000 -$ LS-04 Major Rehabilitation Note 9 $810,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 810,000$ $810,000 -$ LS-10 Major Rehabilitation Note 9 $880,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 880,000$ $880,000 -$ LS-12 Major Rehabilitation Note 9 $1,230,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 1,230,000$ $1,230,000 -$ LS-13 Major Rehabilitation Note 9 $1,150,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 1,150,000$ $1,150,000 -$ LS-15 Major Rehabilitation Note 9 $710,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 710,000$ $710,000 -$ Priority C - Condition Assessment Projects
Force Main and Large Diameter Desktop Analysis and Inspections Note 12 $750,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 750,000$ $750,000 -$ Priority C - Pipeline Replacement (1-2 mile of system) Note 6 $30,000,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 30,000,000$ $30,000,000 -$ Priority C - Large Diameter Pipe and Force Main Rehab Note 10 $12,000,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 12,000,000$ $12,000,000 -$ Priority C - Sewer Siphon Replacement Note 10 $3,330,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 3,330,000$ $3,330,000 -$ Project Deferral - Unplanned Repair Costs Note 13 $7,600,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 7,600,000$ $7,600,000 -$ Priority C - Annual Sewer System Improvements for Resurfacing Note 10 $3,500,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 3,500,000$ $3,500,000 -$ $62,710,000 - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 62,710,000$ $62,710,000 -$ $1,444,000 $5,585,000 $6,990,000 $9,530,000 $9,232,275 $5,760,000 $9,391,000 $9,783,110 $5,876,450 $10,668,440 $83,050,000 $157,210,275 $10,723,725 Engineering/Administration FTE's Count 1 2 2 3 3 2 3 3 2 3 25 NA NA Engineering/Administration FTE's Cost $300,000 $600,000 $600,000 $900,000 $900,000 $600,000 $900,000 $900,000 $600,000 $900,000 $6,900,000 NA NA Total CIP $1,744,000 $6,185,000 $7,590,000 $10,430,000 $10,132,275 $6,360,000 $10,291,000 $10,683,110 $6,476,450 $11,568,440 $89,950,000 $157,210,275 $10,723,725 Total Priority C Projects
Estimated Total Capital Cost
Cost Sharing
Total Priority A Projects
Priority B Projects
Total Priority B Projects
Priority C Projects
Near Term Mid Term
Priority A Projects

Page 396 of 408 ends

Project: City of Pleasanton Sewer Capital Implementation Plan Capital Improvement Projects
20-Year Plan -- Scenario 3 Maximum Deferrals

Capital Improvement Project Notes:

1) Estimated Total Capital Cost is derived from “Table 9: Cost Sharing for Scenario 3 CIP” from the Technical Memorandum dated February 11, 2025 concerning the East Pleasanton Annexation. Costs assume that development of the Kiewit property will contribute $222,275 in payment while balance will be funded by the Arroyo Lago development.

2) Estimated Total Capital Cost is derived from “Table 12: Pro-Rata Cost Sharing Scenario 6 CIP” from the Technical Memorandum dated February 11, 2025 concerning the East Pleasanton Annexation. Costs assume that Project 4B costs will be the Total of all developments (Kiewit North, Site H, East Lakes, Arroyo Lago, and Amazon) minus the Project 4A cost (Kiewit North and Arroyo Lago). The City will seek funding from developments as applications are processed or will seek construction of these projects from the first development with reimbursements made to others on a pro rata share basis as others connect.

3) Priority A Lift Station projects encompass all Criticality 2 and 3 improvements, while Priority B represents Criticality 1 (included in rehabilitation projects), as identified in the 2024 LS Condition Assessment TM.

4) At the time of this project, a redundant siphon will also be installed. Costs include demolition of existing station and assumes full replacement, including cutover costs from the old to new station.

5) Includes all sewer and stormwater generators identified in the TJC Report (2023).

6) Pipeline Replacement includes replacement and repair (R&R) of high priority pipes and an allowance for future R&R work, as well as CCTV inspection and Sewer AI for pipes. This money can also be spent on other high priority assets like force mains, siphons, or large diameter sewers as needed depending on the findings of condition assessment efforts.

7) City funded work to be performed by DSRSD. CIP assumes EALS will be rehabilitated, and the EARS LS and associated piping will be installed to supplement this rehabilitated lift station

8) Estimation of $200,000 for abandonment of Lift Stations currently not in service.

9) Major rehabilitation costs for lift stations were estimated based on the lift station's pump horse power and flow rate. A more refined cost estimate will be developed based on the extent of the rehabilitation required at each station prior to construction.

10) This line item is an allowance for the replacement or rehab of sewer siphons, forcemains, and large diameter sewers that are inspected as part of the Priority A analysis work. This cost will be refined as the analysis is completed

11) LS-14 Rehabilitation will take place under separate CIP funding, and therefore not included in this spreadsheet.

12) The SSMP will make subsequent recommendations about the scope and schedule of future condition assessment work, including CCTV, force main inspection, and manhole inspections. 13) Unplanned repair costs represent the risk associated with deferring capital projects. This cost is intended to account for potential emergency repairs that may arise if assets fail before they can be rehabilitated or replaced. To reflect this risk, a line item equal to 5% of City-funded capital projects is included in priority C, but spending would occur whenever an asset fails unexpectedly (in addition to the City’s O&M budget).

Page 397 of 408 ends

$0
$2
$4
$6
$8
$10
$12
$14 CIP Cost ($M)
CIP Implementation - Scenario 3
FTE Priority C Priority B Priority A

Page 398 of 408 ends

$0
$2
$4
$6
$8
$10
$12
$14 CIP Cost ($M)
CIP Implementation - Scenario Comparison
Scenario 1 - Total Cost Scenario 2 - Total Cost Scenario 3 - Total Cost

Page 399 of 408 ends

10/7/2025
1 2025
Long-Term
Sewer CIP
City Council Meeting
October 21, 2025
Outline
Purpose of Long-Term CIP
Overview of Sewer System Assessments
Prioritization and Scheduling
Questions and discussions
Council Action
1 2

Page 400 of 408 ends

10/7/2025
2 Long-Term CIP Purpose
• Develop a "comprehensive" capital improvement program to ensure "long-term" sustainability of sewer system
• Inform the upcoming sewer rate study
• Comply with new SWRCB General Waste Discharge
Requirements
Long-Term CIP updates Element 8 of City's 2025 SSMP

1. Goals and Introduction

2. Organization

3. Legal Authority

4. Operations & Maintenance Program

5. Design and Performance Provisions

6. Spill Emergency Response Plan

7. Sewer Pipe Blockage Control Plan

8. System Evaluation, Capacity Assurance,
and Capital Improvements

9. Monitoring, Tracking, & Reporting System

10. SSMP Audits

11. Communication Program

Appendices
A. Council Adoption Documents
B. Performance Tracking
C. SSMP Change Log

3 4

Page 401 of 408 ends

10/7/2025
3 Long-Term CIP - Approach
Step 1
Identify CIP Needs
Long-Term CIP
Report
Step 2
Select Implementation Timing
Sewer Rate
Study
Step 3
Update SSMP
SWRCB
Change Log Process
Sewer System
Description
• 21,000 service
connections
• ADWF– 6 mgd
• 253 miles of gravity
pipe
• 8 siphons
• 11 lift stations
• 5 miles of force main
5 6

Page 402 of 408 ends

10/7/2025
4 Projects Are Based on Various Assessments
Capacity Assessment
2022/2023 Flow Monitoring
Model Calibration
Future Development
Design Storm Results
7 8

Page 403 of 408 ends

10/7/2025
5 Gravity System Condition Assessment
Rehab and
repair decisions
are based on
defect codes
During CCTV, every
defect is given a
standardized code
30% of system
had CCTV
data available
Gravity System Condition Assessment
Risk Priority
Rating
Cost of Pipe R/R Decisions1
Total Cost
Replace Line Point Repair
and Line
Defect Point
Repair
Estimated CCTV
Cost2
High $ 230,000 - $ 298,000 $ 298,000 $ 119,000 $ 945,000 Medium $ 202,000 $ 462,000 $ 448,000 $ 3,527,000 $ 366,000 $ 5,005,000 Low - - - $ 488,000 $ 707,000 $ 1,195,000 Very Low - - - $ 244,000 $ 4,962,000 $ 5,206,000 Total Pipes $ 432,000 $ 462,000 $ 757,000 $ 4,557,000 $ 6,154,000 $ 12,362,000 Risk
Priority
Rating
Number of Pipes
Total
Length
(LF)1Replace Line
Point
Repair and
Line
Defect
Point
Repair
Pipes that
Require
CCTV Data
Normal PM Total
High 2 - 2 3 57 10 74 18,800
Medium 2 8 5 39 274 74 402 77,600
Low - - - 5 424 19 448 100,700
Very Low - - - 3 4,081 1,655 5,739 1,138,000
Total Pipes 4 8 7 50 4,836 1,758 6,663 1,334,300
Total
Length
(LF)1
600 1,700 1,800 14,800 910,800 404,900 1,334,300
9 10

Page 404 of 408 ends

10/7/2025
6 Lift Station Assessments
Visited every site
• LS 5 – Full
Replacement
• Generators at
many stations
11 12

Page 405 of 408 ends

10/7/2025
7 • Near-term
rehab/replacement
• Assumed high risk
rehab/replacement
needs after inspection
• Health & Safety Risks
• Criteria Violations
• High Risk of Failure
• Inspection of Critical
Assets
Capital improvement projects were grouped by
prioritization categories
• Equipment nearing end
of life, but in good
condition
• Anticipated work based
on ongoing inspection
work
• Preventative
maintenance
Priority Grouping A
Priority Grouping B
Priority Grouping C
Summary of Projects – Scenario 1 (Maintain)
Project Type Project Priority
Priority A Priority B Priority C
Capacity Projects $ 15,876,000 $ - $ - Lift Station Projects $ 8,980,000 $ 24,379,000 $ 5,530,000 Condition Assessment Projects $ 25,180,000 $ 26,830,000 $ 53,380,000 Total Project Cost by Priority $ 50,036,000 $ 51,209,000 $ 58,910,000 13 14

Page 406 of 408 ends

10/7/2025
8 Three Scenarios with Varying Spend Levels
Priority A
Priority B
Priority C
FTE
Legend
Next Steps
• Today – Approve the Long-term Sewer CIP
• November 2025 thru June 2026 - Sewer Rate Study
• July 1, 2026 – Effective date for updated Sewer Rate and Connection Fees

15 16

Page 407 of 408 ends

10/7/2025
9 Questions?
In Combination with the SSMP, the Long-Term CIP provides a sustainable approach to managing the City’s Sewer System System Reliability
Capacity Management
Regulatory Compliance
17 18

Page 408 of 408 ends