2. I move that City Council approve the HSIP Cycle 9 Orange Blossom Trail Phase 3 Crossings Project plans and specifications, and approve the Construction Contract with California Professional Engineering, Inc. for an amount not-to-exceed $259,245; and

3. I move that the City Council approve an additional appropriation in an amount not-to-exceed $48,000 for this project.

4. Redlans Regular Meeting of 09-05-2023
719 of 1115
RECOMMENDATION:

Staff recommends City Council determine acceptance of a grant and approval of a Construction Contract and construction of the Highway Safety Improvement Program (HSIP) Cycle 9 Orange Blossom Trail Phase 3 Crossings Project are exempt from environmental review pursuant to Section 15301(c) of the State's guidelines implementing the California Environmental Quality Act. Staff further recommends City Council accept the California Department of Transportation HSIP Cycle 9 grant of $298,000, approve the Project plans and specifications, and award a Construction Contract to California Professional Engineering, Inc. for an amount not-to-exceed $259,245, and approve an additional appropriation not-to-exceed $48,000 for this project.

DISCUSSION:

In August 2018, staff submitted a $250,000 funding application through the California Department of Transportation (CalTrans) Highway Safety Improvement Program (HSIP) to install enhanced crosswalks at the Orange Blossom Trail (OBT) crossings at Alabama Street and Tennessee Street. The HSIP manages and distributes federal funds to assist local agencies to reduce fatalities and serious injuries on public streets. In December 2018, the City was notified that the Project was selected for full funding. In July 2023, the City received an additional $48,000 in funding through the same program to supplement construction costs.

The enhanced crosswalk features include in-roadway lights, rectangular rapid flashing beacons, striping, and signage. Both locations are currently configured with uncontrolled crosswalks that are used by OBT users to cross these public streets. Pedestrians using these crosswalks are often obscured by oncoming traffic and parked vehicles. These safety enhancements will increase the visibility of pedestrians using the crosswalks.

A portion of the HSIP grant funding was used for preliminary Project engineering, and the remainder will be used for construction and construction engineering. The construction plans, specifications, and cost estimates for the engineering phase of the Project were completed by MUED staff.

In March 2023, CalTrans authorized the City to proceed with Project construction, and staff issued a bid notice. On May 18, 2023, the City Clerk’s office received and opened the following four (4) Project bids:

Redlans Regular Meeting of 09-05-2023
720 of 1115

BID OPENING REPORT SUMMARY
Bidder Bid Amount
Crosstown Electrical & Data, Inc., Irwindale, CA $254,985 California Professional Engineering, Inc., La Puente, CA $259,245 Elecnor Belco Electric, Inc., Chino, CA $272,800
DBX, Inc., Temecula, CA $284,261
MUED staff reviewed the bids and determined that Crosstown Electrical & Data, Inc. (Crosstown) was the apparent lowest bidder. After further review, the City's Risk Management Division determined Crosstown is “Not Qualified”. Crosstown elected not to appeal this decision and their bid was disqualified. Staff reviewed the remaining bids and determined that California Professional Engineering, Inc. was the next lowest responsive and responsible bidder. Staff recommends awarding a Construction Contract to California Professional Engineering, Inc. for an amount not-to-exceed $259,245, and approve an additional appropriation not-to-exceed $48,000 for this project. If approved, it is anticipated that the Project will be completed within 100 calendar days from issuance of a Notice to Proceed.

The Project is categorically exempt from environmental review in accordance with Section 15301(c) of the State's guidelines implementing the California Environmental Quality Act as this project is within the City’s right-of-way on the street and involves negligible or no expansion of use beyond what is existing.

ALTERNATIVES:

City Council may deny the staff recommendation and provide alternate direction.

STRATEGIC PLAN:

N/A
SUBMITTED BY:

John R. Harris, Municipal Utilities and Engineering Director RECOMMENDED BY:

Charles M. Duggan Jr., City Manager
REVIEWED BY:

Yvette M. Abich Garcia, City Attorney
Janice McConnell, Assistant City Manager
Danielle Garcia, Management Services/Finance Director
Goutam K. Dobey, City Engineer
Redlans Regular Meeting of 09-05-2023
721 of 1115
PREPARED BY:

Veronica Medina, Associate Engineer
Fiscal Impact
Fiscal Year: FY 23/24
Appropriation Required Y/N: Y
Amount: $48,000
Budgeted Y/N: Y
Account No.: 200400; 101400
Discussion:

Accepting the HSIP Cycle 9 grant and approving the construction contract requires an additional appropriation of $48,000 from the Governmental Grant Fund (200400). The FY 23/24 Governmental Grant Fund (200400) includes $235,000 for this project, all of which will be reimbursed by the CalTrans HSIP grant program after successful completion of the Project. The remaining balance of $24,245 is included in the FY 23/24 MUED Engineering Budget (101400).

Attachments
HSIP Cycle 9 Award Letter
HSIP Additional Funding Notification Email
A. CPE Public Works Contract
B. Bid Opening
C. Bid Analysis
D. Location Map
Additional Appropriation
Specifications
Plans
CPE - Safety Questionnaire Final
Crosstown - Safety Questionnaire Final
Redlans Regular Meeting of 09-05-2023
722 of 1115

“Provide a safe, sustainable, integrated and efficient transportation system to enhance California’s economy and livability”

STATE OF CALIFORNIA------- CALIFORNIA STATE TRANSPORTATION AGENCY EDMUND G. BROWN Jr., Governor

DEPARTMENT OF TRANSPORTATION

DIVISION OF LOCAL ASSISTANCE
P.O. BOX 942874, MS-1
SACRAMENTO, CA 94274-0001
PHONE (916) 654-1776
FAX (916) 654-7181
TTY 711
www.dot.ca.gov

Serious drought.

Help save water!
December 27, 2018

Mr. Jason Montgomery
Senior Civil Engineer
City of Redlands
35 Cajon Street, PE Box 3005
Redlands, CA 92373

Dear Mr. Montgomery:

Congratulations! The following project you submitted for the Highway Safety Improvement Program (HSIP) Cycle 9 funding has been selected for implementation:

Application ID Location Description of Work Project Cost Federal Funds 08-Redlands-2 Orange Blossom
Trail at Alabama
Street and Tennessee
Street.

Install pedestrian
crossings with
enhanced safety
features.
$ 250,000 $ 250,000

To view the complete statewide project listing, please visit the HSIP website at:
http://www.dot.ca.gov/hq/LocalPrograms/HSIP/prev_cycle_results.htm.

In HSIP Cycle 9, 221 projects were selected from a candidate pool of 351 applications. These projects are selected for funding either based on the statewide Benefit Cost Ratio (BCR), or under the various set-asides (i.e. set-asides for Guardrail Upgrade, Horizontal Curve Signing, Pedestrian Crossing Enhancements, and Tribes). The selected HSIP projects, totaling $182 million, will be programmed in the 2019 Federal Statewide Transportation Improvement Plan (FSTIP).

So what is next?

1. Program new HSIP projects into the FSTIP:

The Metropolitan Planning Organizations (MPOs) will be informed of the projects being approved for funding, and the MPOs will program these projects in their FSTIP. Please note that it is your agency’s responsibility to check with your MPO to confirm when the Federal Highway Administration (FHWA) has approved the programming of your projects. At that Redlans Regular Meeting of 09-05-2023
723 of 1115
Mr. Montgomery
December 27, 2018

Page 2 ends

“Provide a safe, sustainable, integrated and efficient transportation system to enhance California’s economy and livability”

time your agency may submit a request for authorization (RFA) to begin reimbursable work on the project in accordance with federal-aid project implementation procedures.

While waiting for the projects to be programmed into the FSTIP, your agency is encouraged to prepare documents required for your first Request for Authorization to Proceed (E-76) with your first phase of work. For more details regarding project implementation, please review the Local Assistance Procedures Manual (LAPM) at
http://www.dot.ca.gov/hq/LocalPrograms/lam/lapm.htm.

2. Deliver your HSIP projects and meet the delivery milestones per requirements:

For HSIP Cycle 9 projects, the following delivery milestones are required:
• The milestone of E-76 with Preliminary Engineering is met by September 30, 2019; and • The milestone of E-76 with Construction is met by December 31, 2021.

Caltrans will track the delivery of these HSIP projects. For delivery reports, consequence of not meeting the delivery requirements, exceptions, time extensions and other details, please visit http://www.dot.ca.gov/hq/LocalPrograms/HSIP/delivery_status.htm.

Important: Use EPSP to deliver the projects
Key: Local agencies can and should use the Expedited Project Selection Procedures (EPSP) to deliver their HSIP projects in advance of the FSTIP program year.

Given that a HSIP safety project is programmed in the FSTIP as lump-sum (i.e. not programmed by phases), it is quite often that the actual year of one or more phases will be different from the program year in the FSTIP. When this occurs, local agencies are allowed and encouraged to request for E-76s in any year, using the Expedited Project Selection Procedures (EPSP). The fact that a local HSIP project is not programmed in a given year should NOT hinder the local agency from requesting for authorization in that year, if the local agency is ready to start the work for a project phase. This understanding is especially important in meeting the delivery requirements of the local HSIP projects.

For the specifics of using the EPSP, please visit
http://www.dot.ca.gov/hq/LocalPrograms/HSIP/delivery_status.htm.

If you have questions, please feel free to contact Enrique Gonzalez at (909) 806-3960, or at [email protected].

Sincerely,

David Lee
District Local Assistance Planner
Redlans Regular Meeting of 09-05-2023
724 of 1115

STATE OF CALIFORNIA-------CALIFORNIA STATE TRANSPORTATION AGENCY Gavin Newsom, Governor

DEPARTMENT OF TRANSPORTATION

DIVISION OF LOCAL ASSISTANCE
P.O. BOX 942874, MS-1
SACRAMENTO, CA 94274-0001
PHONE (916) 654-1776 Making Conservation
FAX (916) 653-1905 a California Way of Life.

TTY 711
www.dot.ca.gov
March 26, 2021
Highway Safety Improvement Program (HSIP) Cycle 10 Awardee Dear Recipient:

Congratulations! Your HSIP application has been selected for funding.

The complete list of funded projects in HSIP Cycle 10 Call for Projects is available online at https://dot.ca.gov/programs/local-assistance/fed-and-state-programs/highway-safety- improvement-program/approved-project-lists.

The agency’s first step is to contact the appropriate District Local Assistance Engineer (DLAE) who can assist with the funding allocation process and other project management requirements.

The DLAE contact information is available at https://dot.ca.gov/programs/local-assistance/other- important-issues/local-assistance-contacts.

To help in the success of your project, here are some important items to note:

1. All HSIP Cycle 10 projects will be funded with State-only funding.

2. The HSIP is a reimbursement program. Reimbursable work cannot commence on your project until:
a. You receive an allocation from Caltrans Division of Local Assistance (DLA) for this project;
b. You have a State-only Funds Master Agreement for your agency; and c. You have a Program Supplement Agreement (PSA) for this project.

For implementation guidance, allocation request form and other documents, please visit https://dot.ca.gov/programs/local-assistance/fed-and-state-programs/highway-safety- improvement-program/state-funded-hsip.

Please note:
a. the funding allocation process for HSIP projects with State-only Funding is different from projects in other programs such as ATP/STIP and SB1. The funding allocation for HSIP projects is processed through Caltrans DLA, not the CTC.
b. The funding allocation request is Phase specific, i.e. Preliminary Engineering (PE), Right of Way (ROW) or Construction (CON).

3. The delivery of the HSIP Cycle 10 projects must meet the below milestones:
a. The PE phase (if applicable) must be allocated by 12/31/2021; b. The Construction (CON) phase must be allocated by 3/31/2024. c. The project must be completed and closed out by 3/31/2026. “Provide a safe, sustainable, integrated and efficient transportation system to enhance California’s economy and livability” Redlans Regular Meeting of 09-05-2023
725 of 1115

HSIP Cycle 10 Awardee
March 26, 2021

Page 2 ends

You may submit your funding allocation for PE to the DLAE now. Allocation request for CON may be submitted after 3/1/2022.

HSIP project delivery requests and status of the projects are available at https://dot.ca.gov/programs/local-assistance/fed-and-state-programs/highway-safety- improvement-program/delivery-requirements-status-approved-projects.

4. It is the agency’s responsibility to review their project scope throughout the project delivery process and confirm that HSIP funding is used to fund the approved eligible scope as defined in your HSIP application. In case that any scope or cost change is needed, please contact your DLAE.

5. Prior to engaging in any Architectural and Engineering (A&E) contract procurement(s), agencies should reference Chapter 10 (Consultant Selection) of the Local Assistance Procedures Manual (LAPM), located at: https://dot.ca.gov/programs/local- assistance/guidelines-and-procedures/local-assistance-procedures-manual-lapm.

For more guidance on implementing State-funded HSIP projects, please visit https://dot.ca.gov/programs/local-assistance/fed-and-state-programs/highway-safety- improvement-program/state-funded-hsip.

If you have any questions about your project, please contact your DLAE.

Sincerely,

DEE LAM
Division of Local Assistance, Chief
c: DLAEs and HSIP Coordinators, Caltrans Districts
Chiu Liu/Richard Ke, HSIP Managers, Caltrans HQ
Robert Peterson, Chief, Office of Federal Programs, Caltrans HQ Sujaya Kalainesan, Chief, Office of Project Implementation - South, Caltrans HQ Felicia Haslem, Chief, Office of Project Implementation - North, Caltrans HQ “Provide a safe, sustainable, integrated and efficient transportation system to enhance California’s economy and livability”
Redlans Regular Meeting of 09-05-2023
726 of 1115
1 I:\cmo\Agreements\California Professional Engineering, Inc.-FY22-0218.doc-jm

PUBLIC WORK CONSTRUCTION CONTRACT

This Public Work Cons truction contract (“Contract”) is made and entered into this 5th day of September 2023, by and between the City of Redlands, a municipal corporation, organized and existing under the laws of the State of California (hereinafter “City”), and California Professional Engineering, Inc., a California corporation, (hereinafter "Contractor"). City and Contractor are sometimes individually referred to herein as a “Party” and, together, as the “Parties.”

In consideration of the mutual promises contained herein, City and Contractor agree as follows:

1. SCOPE OF WORK: Contractor shall furnish all materials and will perform all of the work for the following: HSIP Cycle 9 Orange Blossom Trail Phase 3 Crossings , complete all items as required by the Contract Documents (as herein defined) and Specifications for City’s HSIP Cycle 9 Orange Blossom Trail Phase 3 Crossings, City Project No. 47033, Federal Project No. HSIPL 5083(024) (the “Work”).

2. CONTRACT SUM: City shall pay Contractor the sum of Two Hundred Fifty-Nine Thousand Two Hundred Forty-Five dollars ($259,245) as consideration for its performance of the Work in accordance with the terms and conditions set forth in the Contract Documents. Pursuant to Public Contract Code Section 22300, Contractor has the option to deposit securities with an escrow agent as a substitute for retention of earnings required to be withheld by City pursuant to an escrow agreement as set forth in Public Contract Code section 22300.

3. TIME FOR COMPLETION: The Work shall be completed within One Hundred (100) calendar days from and after the date of City’s issuance of a Notice to Proceed to Contractor.

4. LIQUIDATED DAMAGES: Contractor’s failure to complete the Work within the time allowed will result in damages being sustained by City. Such damages are, and will continue to be, impracticable and extremely difficult to determine. Accordingly, Contractor shall pay to City, or have withheld from monies due to Contractor, the sum of Five Hundred dollars ($500) for each consecutive calendar day in excess of the specified time for completion of the Work. Execution of this Contract shall constitute agreement by City and Contractor that Five Hundred dollars ($500) per day is the estimated damage to City caused by the failure of Contractor to complete the work within the allowed time. Such sum is liquidated damages and shall not be construed as a penalty, and may be deducted from payments due Contractor if such delay occurs.

5. CONTRACT DOCUMENTS: This Contract incorporates by reference the following: Notice Inviting Bids, Instructions to Bidders, Contractor’s Proposal, Bid Bond, Agreement, Performance Bond, Labor and Material Bond, Plans, General Conditions, Special Provisions and Specifications, and any addenda thereto (collectively, the “Contract Documents”).

6. ATTORNEYS' FEES: In the event any action is commenced to enforce or interpret the terms or conditions of this Contract, or the Contract Documents, the pre vailing Party in suc h action, in addition to any costs and other relief, shall be entitled to recover its reasonable attorneys’ fees, including fees for use of in-house counsel by a Party.

Redlans Regular Meeting of 09-05-2023
727 of 1115
2 I:\cmo\Agreements\California Professional Engineering, Inc.-FY22-0218.doc-jm

7. RESOLUTION OF CONSTRUCTION CLAIMS: Claims by Contractor in the amount of three hundred seventy-five thousand dollars ($375,000) or less shall be made by Contractor and processed by the City pursuant to the provisions of Part 3, Chapter 1 , Article 1.5 of the Public Contract Code (commencing with Section 20104). All claims shall be in writing and include the documents necessary to substantiate the claim. Nothing in subdivision (a) of Public Contract Code Section 20104.2 shall extend the time limit or supersede the notice requirements provided in this case from filing claims by Contractor.

8. ELIGIBILITY OF CONTRACTOR/SUBCONTRACTOR: Contractor and all of its subcontractors shall abide by California Public Contract Code, Section 6109, and California Labor Code Sections 1777.1 and/or 1777.7, and certify that they are not debarred and are eligible to work on this project.

9. ASSIGNMENT OF AGREEMENT: No assignment by a Party of any rights or interests under this Contract shall be binding on another Party without the written consent of the Party sought to be bound.

10. SUCCESSORS AND ASSIGNS: City and Contractor each binds itself and their respective successors and assigns in respect to all covenants, agreements, and obligations contained in the Contract Documents.

11. SEVERABILITY: Any provision or part of the Contract Documents held to be void or unenforceable under any law or regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon City and Contractor.

IN WITNESS WHEREOF, the Parties hereto have executed this Contract the day and year first written above.

CITY OF REDLANDS
(SEAL)

By:____________________________________
Eddie Tejeda, Mayor
ATTEST:

____________________________________
Jeanne Donaldson, City Clerk
(SEAL)

__________________________________________
Van Nguyen, President

_793907_____________________________________
Contractor's License No.

Redlans Regular Meeting of 09-05-2023
728 of 1115
3 I:\cmo\Agreements\California Professional Engineering, Inc.-FY22-0218.doc-jm

WORKER'S COMPENSATION INSURANCE CERTIFICATION

Description of Contract: City of Redlands
Municipal Utilities and Engineering Department
HSIP Cycle 9 Orange Blossom Trail Phase 3 Crossings
City Project No. 47033,
Federal Project No. HSIPL 5083(024)
Every employer, except the Sta te, shall secure the payment of compen sation in one or more of the following ways:

a. By being insured against liability to pay compensation by one or more insurers duly authorized to write compensation insurance in this State. b. By securing from the Director of Industrial Relations, a certificate of consent to self- insure, either as an individual employer, or as one employer in a group of employers, which may be given upon furnishing proof satisfactory to the Director of Industria l Relations of ability to self-insure and to pay any compensation th at may become due to his or her employees.

CHECK ONE

_____I am aware of the provisions of Section 3700 of the Labor Code which requires every employer to be insured against liability fo r Workers’ Compensation or to undertake self-insurance in accordance with the provisions of that Code, and I will comply with such provisions before commencing the performance of the work and activities required or permitted under this Agreement. (Labor Code §1861).

_____I affirm tha t at all t imes, in performing the work and activities required or permitted und er this Agreement, I shall not employ any person in any manner such that I become subject to the workers’ compensation laws of California. However, at any time, if I employ any person such that I become subject to t he workers’ compensation laws of Californ ia, immediately I shall provide the City with a certificate of consent to self -insure, or a certification of workers’ compensation insurance.

I certify under penalty of perjury under the laws of the State of Califo rnia that the information and representations made in this certificate are true and correct.

Dated this day of ___ , 2023.

_____________________________________
Van Nguyen, President

(SEAL)
(Labor Code Section 1861 provides that the above certificate must be signed and filed by the Contractor with the Owner prior to performing the work of the contract.)
Redlans Regular Meeting of 09-05-2023
729 of 1115
4 I:\cmo\Agreements\California Professional Engineering, Inc.-FY22-0218.doc-jm

FAITHFUL PERFORMANCE BOND

Whereas, the City of Redlands (“City”), State of California, and California Professional Engineering, Inc. (hereinafter designated as "Principal") have entered into an agreement dated September 5, 2023 (“Agreement”) whereby Principal agrees to install and complete certain public improvements (the “Work”), which said Agreement is identified as HSIP Cycle 9 Orange Blossom Trail Phase 3 Cross ings, City Project No. 47033, Federal Project No. HSIPL 5083(024 ) and is hereby referred to and made a part hereof; and

Whereas, said Principal is req uired under the terms of the A greement to furnish a bond for the faithf ul performance of the Work, now, therefore, we, the Principal and , _____________________________, as Surety, are held and firmly bound unto the City in the penal sum of Two Hundred Fifty -Nine Thousand Two Hundred Forty-Five dollars ($ 259,245) lawful money of the United States, for the payment of which sum we bind ourselves, and our heirs, successors, executors and administrators, jointly and severally, firmly by these presents.

The condition of th is obligation is such that if the above bounded Principal , his or its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions and provisions in the Ag reement and any alteration thereof made as therein provid ed, on his or its part, to be kept and performed at the time and in the manner therein specified, and in all respects according to their true intent and meaning, and shall faithfully fulfill the one -year guarantee of all material s and workmanship, and sha ll defend, indemnify and save harmless the City and its elected officials, officers, agents and employees, as therein stipulated, then this obligation shall become null and void; otherwise it shall be and remain in full force and effect.

As a part of the obligation secured hereby and in addition to the face amount specified therefor, there shall be i ncluded costs and reasonable expe nses and fees, including reasonable attorneys’ fees, incurred by the City in successfully enforcin g such obligations, all to be taxed as costs and included in the judgment rendered.

As a condition precedent to the satisfac tory completion of the Work, the above obligation shall hold good for a period of one (1) year or lon ger if required by the Agreeme nt after the acceptance of the work by the City, during which time if the Principal shall fail to make full, complete, and satisfactory repair and replacements and totally protect the City from loss or damage made evident duri ng this period from the date o f completion of the Work, a nd resulting from or caused by defective materials or faulty workmanship, the above obligation in penal sum thereof shall remain i n full force and effect. The obligations of Surety hereunder shall c ontinue so long as any obligation of the Principal remains.

Whenever the Principal shall be, and is declared by the City to be, in default under the Agreement, the City having performed the City obligations thereunder, the Surety shall promptly remedy the default, or shall promptly, at the City’s option:

1. Complete the Work in accordance with its terms and conditions; or

Redlans Regular Meeting of 09-05-2023
730 of 1115
5 I:\cmo\Agreements\California Professional Engineering, Inc.-FY22-0218.doc-jm

2. Obtain a bid or bids for c ompleting the Work in accordance with its terms and conditions, and upon determination by Surety of t he lowest responsive and respo nsible bidder, arrange for a contract between such bidder and the City, and make available as work progresses sufficient funds to pay the cost of completion o f the Work less the balance of the Agreement price, but not exceeding, including other costs and damages for which Surety may be liable hereunder, the amount set forth above. The term “balance of the Agreement price,” as us ed in this paragraph, shall mean the total amount payable to the Principal by the City under the Agre ement and any modifications thereto, less the amount previously properly paid by the City to the Principal.

Surety expressly agrees that the City may reject any contractor or subcontr actor which may be proposed by Surety in fulfillment of its obligations in the event of default by the Principal.

Surety shall not utilize the Principal in completing the Work nor shall Surety accept a bid from the Princip al for completion of the Work if the City, when declaring the Principal in default, notifies Surety o f the City’s objection to the Principal’s further partici pation in the completion of the Work.

No right of action shall accrue on the bond to or for the u se of any person or corporation other than the City named herein or the successors or assigns of the City. Any suit under this bon d must be instituted within the applicable statute of limitations period.

The said Surety, for value received, hereby stipu lates and agrees that no change, extension of time, alteration or addition to the terms of the Agreem ent or to the work to be perfo rmed thereunder or the Spec ifications accompanying the same shall in any way affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Agreement or to the work or to the specifications.

No final settlement between the City and the Principal shall abridge the right of any beneficiary hereunder whose claim may be unsatisfied.

The Principal and Surety agree that if the City is required to engage the services of any attorney in connection with the enforcement of this bond, each shall pay the City’s reasonable attorneys’ fees incurred, with or without suit, in addition to the above sum.

In witness whereof, this instrument has been duly executed by the Principal and Surety above named, on , 2023.

(SEAL) (SEAL)

(Contractor) (Surety)
BY:
(Signature) (Signature)

Address:___________________________________
__________________________________________
(Seal and Nota rial Acknowledgment of
Surety)
Telephone ( )___________________________
Redlans Regular Meeting of 09-05-2023
731 of 1115
6 I:\cmo\Agreements\California Professional Engineering, Inc.-FY22-0218.doc-jm

LABOR AND MATERIAL BOND

Whereas, the City C ouncil of the City of Redla nds, State of California, and California Professional Engineering, Inc. (hereinafter designa ted as “Principal”) have enter ed into a n agreement (the “Agreement”) whereby Principal agrees to install and complete certain designated public improvements (the “Work”), which said agreement, dated September 5, 2023, and identified as HSIP Cycle 9 Orange Blossom Trail Phase 3 Crossings, City P roject No. 47033, Federal Project No. HSIPL 5083(024) is hereby referred to and made a part hereof; and

Whereas, under the t erms of the Agre ement, Principal is required before commending the performance of the Work, to file a good and sufficient Labor and Material bond with the City of Redlands to se cure the claims to which refer ence is made in Title 3 (commencing with Section 9550) of Part 6 of Division 4 of the Civil Code of the State of California.

Now, therefore, said Principal and the undersigned as corporate surety, are held firmly bound unto t he City and all contractors, s ubcontractors, laborers, material men and other p ersons employed in the performance of the Agreement and referred to in the aforesaid Code of Civil Procedure in the sum of Two Hund red Fifty -Nine Thousand Two Hundred Forty-Five dollars ($259,245) for materials furnishe d or labor thereon of any kind , or fo r amounts due under the Unemployment Insurance Act with respect to such work or labor, that said surety will pay the same in an amount not exceeding the amount hereinabove set forth, and also in case suit is brought upo n this bond, will pay, in addi tion to the face amount thereof, costs and reasonable expenses and fees, including reasonable attorneys’ fees, incurred by the City in suc cessfully enforcing such obligation, to be awarded and fixed by the court, and to be tax ed as cost s and to be included in the judgment therein rendered.

It is hereby expressly stipulated and agreed that this bond shall insure to the benefit of any and all persons, companies and corporations entitled to file claims under Title 3 (commencing w ith Section 9550) of Part 6 of Division 4 of the Ci vil Code, so as to give a right of action to them or their assigns in any suit brought upon this bond.

Should the condition of this bond be fully performed, then this obligation shall become null and void, otherwise it shall be and remain in full force and effect.

The surety hereby stipulates and agrees that no change, extension of time, alteration or addition to the t erms of the Agreement or the specifications accompanying the same shall in any manner af fect its o bligations on this b ond, an d it does here by waive notice of any such change, extension of time, alteration or addition.

SIGNATURES ON NEXT PAGE
Redlans Regular Meeting of 09-05-2023
732 of 1115
7 I:\cmo\Agreements\California Professional Engineering, Inc.-FY22-0218.doc-jm In witness whereof, this instrument has been duly executed by the Principal and surety above named, on _______________________, 2023.

(SEAL) (SEAL)

(Contractor) (Surety)
BY:
(Signature) (Signature)
Address:_____________________________
(Seal and Notarial Acknowledgement of Surety) ____________________________________ Telephone: ( )___________________

Redlans Regular Meeting of 09-05-2023
733 of 1115
Redlans Regular Meeting of 09-05-2023
734 of 1115
ATTACHMENT "C"
PROJECT NO. 47033; HSIPL-5083(024) BID DATE: 18-May-2023 HSIP-Cycle 9 Orange Blossom Trail Phase 3 Crossings Project EST. START DATE: 24-Jul-2023 Unit Price Item Price Unit Price Item Price Unit Price Item Price 1 Mobilization (Maximum 5% of total bid price) 1 LS $12,500.00 $12,500.00 $5,100.00 $5,100.00 $12,000.00 $12,000.00 2 Traffic Control 1 LS $8,500.00 $8,500.00 $6,000.00 $6,000.00 $9,500.00 $9,500.00 3 In-Roadway Warning Light System 2 EA $68,490.00 $136,980.00 $69,705.00 $139,410.00 $58,000.00 $116,000.00 4 Rectangular Rapid Flashing Beacons (RRFB) with
Pole 5 EA $12,390.00 $61,950.00 $14,460.00 $72,300.00 $19,800.00 $99,000.00 5 Annunciating Pushbuttons 5 EA $2,280.00 $11,400.00 $2,127.00 $10,635.00 $1,860.00 $9,300.00 6 Signage and Striping 1 LS $5,655.00 $5,655.00 $8,000.00 $8,000.00 $5,000.00 $5,000.00 7 Demobilization 1 LS $1,000.00 $1,000.00 $800.00 $800.00 $5,000.00 $5,000.00 8 Unforeseen work not covered within all other bid
items 1 LS $17,000.00 $17,000.00 $17,000.00 $17,000.00 $17,000.00 $17,000.00 Last Minute Additions/Deductions $0.00 $0.00 $0.00
Total Bid Price
License Status
Sub's License Status
Bid Bond Company
Submitted Entire Bid Package
Submitted Sub's Qualification Statement
DIR Status
Error in Bid
$272,800.00$254,985.00
YesYes
Active
Yes
Fidelity and Deposit Company of Maryland
Active
Active
Liberty Mutual Insurance Company
$259,245.00

CITY OF REDLANDS

MUNICIPAL UTILITIES & ENGINEERING DEPARTMENT

BID ANALYSIS
Item
No.

Elecnor Belco Electric,
Inc.Bid Item Quantity Unit
Crosstown Electrical &
Data, Inc.

California Professional
Engineering, Inc.

No
Yes Yes
Active Active
No
Active
No
Active
Active
United States Fire Insurance Company
Yes
N/A
Low Bidders #1, #2 and #3
Sheet 1 of 2
Redlans Regular Meeting of 09-05-2023
735 of 1115
ATTACHMENT "C"
PROJECT NO. 47033; HSIPL-5083(024) BID DATE: 18-May-2023 HSIP-Cycle 9 Orange Blossom Trail Phase 3 Crossings Project EST. START DATE: 24-Jul-2023 Unit Price Item Price Unit Price Item Price Unit Price Item Price 1 Mobilization (Maximum 5% of total bid price) 1 LS $5,000.00 $5,000.00 2 Traffic Control 1 LS $29,920.00 $29,920.00
3 In-Roadway Warning Light System 2 EA $70,250.00 $140,500.00 4 Rectangular Rapid Flashing Beacons (RRFB) with
Pole 5 EA $15,000.00 $75,000.00
5 Annunciating Pushbuttons 5 EA $1,900.00 $9,500.00
6 Signage and Striping 1 LS $4,841.00 $4,841.00
7 Demobilization 1 LS $2,500.00 $2,500.00
8 Unforeseen work not covered within all other bid
items 1 LS $17,000.00 $17,000.00
Last Minute Additions/Deductions $0.00
Total Bid Price
License Status
Sub's License Status
Bid Bond Company
Submitted Entire Bid Package
Submitted Sub's Qualification Statement
DIR Status
Error in Bid
Item
No. Bid Item Quantity Unit DBX, Inc.

CITY OF REDLANDS

MUNICIPAL UTILITIES & ENGINEERING DEPARTMENT

BID ANALYSIS
$284,261.00
No
Yes
Active
The Ohio Casualty Insurance Company
Yes
Active
Active
Low Bidders #4
Sheet 2 of 2
Redlans Regular Meeting of 09-05-2023
736 of 1115

TENNESSEE ST

ALABAMA ST

W REDLANDS BLVD

BUSINESS CENTER CT

MISSOURI CT

KANSAS ST

PINE AVE

STORAGE CT

ORANGE AVE

W CITRUS AVE

W PARK AVE

W STATE ST
Copyrigh t nearmap 2015
HSIP Cycle 9 In-Roadway Lights Project
Alabama and Tennessee St at OBT Crossings
Location Map
^_
^_PROJECT LOCATION

PROJECT LOCATION
Redlans Regular Meeting of 09-05-2023
737 of 1115
Redlans Regular Meeting of 09-05-2023
738 of 1115

CITY OF REDLANDS

MUNICIPAL UTILITIES &

ENGINEERING DEPARTMENT

Bid Proposal, Contract Documents and Specifications

For

HSIP Cycle 9 Orange Blossom Trail Phase 3
Crossings
City Project No. 47033,
Federal Project No. HSIPL 5083(024)

APRIL 2023
Redlans Regular Meeting of 09-05-2023
739 of 1115

THIS PAGE INTENTIONALLY LEFT BLANK
Redlans Regular Meeting of 09-05-2023
740 of 1115

CITY OF REDLANDS

MUNICIPAL UTILITIES & ENGINEERING DEPARTMENT

Bid Proposal, Contract Documents and Specifications

for

HSIP Cycle 9 Orange Blossom Trail Phase 3
Crossings
City Project No. 47033,
Federal Project No. HSIPL 5083(024)

For use in conjunction with specifications entitled: “Standard Specifications for Public Works Construction (Greenbook)” 2021 Edition; “Standard Plans for Public Works Construction” 2021 Edition; Standard Specifications, State of California, Department of Transportation, latest edition, the State of California Department of Transportation Standard Plans 2018 edition unless otherwise specified, and these Special provisions.

City Council:

Eddie Tejeda, Mayor
Paul T. Barich, Mayor Pro Tem
Denise Davis, Councilmember
Jenna Guzman-Lowery, Councilmember
Mario Saucedo, Councilmember

City Clerk:

Jeanne Donaldson, City Clerk

City Staff:

Charles M. Duggan Jr., City Manager

APRIL 2023
Redlans Regular Meeting of 09-05-2023
741 of 1115

THIS PAGE INTENTIONALLY LEFT BLANK
Redlans Regular Meeting of 09-05-2023
742 of 1115

TOC 1
HSIP Cycle 9 Orange Blossom Trail Phase 3
Crossings
City Project No. 47033,
Federal Project No. HSIPL 5083(024)

TABLE OF CONTENTS
(XX) REFLECTS PAGE IDENTIFICATION FOOTER ABBREVIATION

NOTICE INVITING SEALED PROPOSALS (NIB)

BID DOCUMENTS (BD)
INSTRUCTIONS TO BIDDERS .......................................................................................... 1 PROPOSAL…. .................................................................................................................... 10 BID CERTIFICATION ........................................................................................................ 13 BID BOND…. ..................................................................................................................... 14 EQUAL EMPLOYMENT OPPORTUNITY CERTIFICATION ....................................... 15 NON-COLLUSION AFFIDAVIT ...................................................................................... 16 STATEMENT BY BIDDER ............................................................................................... 17 OFFICERS OF CORPORATION (Members of Firm) ....................................................... 17 SUB-CONTRACTORS LIST ............................................................................................. 18 QUALIFICATION AND EXPERIENCE STATEMENT .................................................. 19 GENERAL INFORMATION ............................................................................................. 20

CONTRACT DOCUMENTS (CD)
PUBLIC WORK CONSTRUCTION CONTRACT ............................................................. 1 WORKER'S COMPENSATION INSURANCE CERTIFICATION ................................... 4

GENERAL CONDITIONS (GC)
SECTION 1 – GENERAL, TERMS, DEFINITIONS, ABBREVIATIONS, UNITS OF MEASURE, AND SYMBOLS ...................................................................... 1 SECTION 2 - SCOPE OF THE WORK ............................................................................... 2 SECTION 3 - CONTROL OF THE WORK ......................................................................... 3 SECTION 4 - CONTROL OF MATERIALS ....................................................................... 8 SECTION 5 – LEGAL RELATIONS AND RESPONSIBILITES ...................................... 9 SECTION 6 – PROSECUTION AND PROGRESS OF THE WORK .............................. 31 SECTION 7 - MEASUREMENT AND PAYMENT ......................................................... 32 SECTION 8 - FACILITIES FOR AGENCY PERSONNEL .............................................. 34 SECTION 9 - ASSIGNMENT OF UNFAIR BUSINESS PRACTICES CLAIMS ........... 34 SECTION 10 - REMOVAL, RELOCATION OR PROTECTION OF EXISTING UTILITIES ................................................................................................... 35 Redlans Regular Meeting of 09-05-2023
743 of 1115

TOC 2

SPECIAL CONDITIONS (SC)
SECTION 1 – CONSTRUCTION DETAILS ...................................................................... 1 SECTION 2 – REQUIRED CONTRACT PROVISIONS FEDERAL-AID
CONSTRUCTION CONTRACTS ................................................................ 9

GENERAL REQUIREMENTS
SECTION 01110 COORDINATION OF WORK
SECTION 01111 TRAFFIC CONTROL PLAN
SECTION 01112 DESCRIPTION OF WORK
SECTION 01200 MEASUREMENT AND PAYMENT
SECTION 01251 CHANGE ORDER REQUESTS
SECTION 01254 CHANGE ORDERS
SECTION 01298 SCHEDULE OF VALUES
SECTION 01321 CONSTRUCTION SCHEDULE
SECTION 01322 CONSTRUCTION PROGRESS PHOTOGRAPHY
SECTION 01323 CONSTRUCTION STATUS REPORTS
SECTION 01330 SUBMITTALS
SECTION 01581 CONSTRUCTION INFORMATION SIGNS
SECTION 01721 MOBILIZATION
SECTION 01740 DEMOBILIZATION

TECHNICAL SPECIFICATIONS
SECTION 02222 PROTECTING EXISTING UNDERGROUND UTILITIES SECTION 16561 RECTANGULAR RAPID FLASHING BEACONS (RRFB)

APPENDIX

APPENDIX A CHECKLIST OF LABOR LAW REQUIREMENTS

APPENDIX B CITY OF REDLANDS WORKDAY CONSTRUCTION SCHEDULE

APPENDIX C CALIFORNIA DEPARTMENT OF TRANSPORTATION EXHIBITS APPENDIX D FHWA – 1273

APPENDIX E FEDERAL WAGE RATES

APPENDIX F ENVIRONMENTAL COMMITMENTS RECORD

APPENDIX G CONTRACTOR SAFETY PROGRAM

APPENDIX H PERMITS
Redlans Regular Meeting of 09-05-2023
744 of 1115
Redlans Regular Meeting of 09-05-2023
745 of 1115
Redlans Regular Meeting of 09-05-2023
746 of 1115

BID DOCUMENTS
(BD)
Redlans Regular Meeting of 09-05-2023
747 of 1115

THIS PAGE INTENTIONALLY LEFT BLANK
Redlans Regular Meeting of 09-05-2023
748 of 1115

BD 1

INSTRUCTIONS TO BIDDERS
For
HSIP Cycle 9 Orange Blossom Trail Phase 3 Crossings
City Project No. 47033,
Federal Project No. HSIPL 5083(024)

Bids to receive consideration shall be made in accordance with the following instructions:

1. PROPOSALS:

a . Bids shall be made upon the form of proposal furnished by the City. All Bids shall be properly executed with all items filled in; the signatures of all persons signing shall be in longhand. If the unit price and the total amount named by a Bidder for any item are not in agreement, the unit price shall be considered as representing the Bidder's intention, and the totals may be corrected by the Engineer to conform thereto. If the sum of the individual bid item’s and the total amount named by a Bidder are not in agreement, the sum of the bid item’s shall be considered as representing the Bidder’s intention, and the totals may be corrected by the Engineer to conform thereto. If the total price written in words and the total price written in figures are not in agreement, then the total price written in words will be considered as representing the Bidder’s intention, and the totals will be corrected by the Engineer to conform thereto.

b. Proposals may be rejected if they show any alterations of form, additions not called for, conditional or alternative bids, incomplete Bids, erasures, or irregularities of any kind.

Mistakes shall be lined through and the correct amount written above and initialed by the authorized agent of the Bidder.

c. Bids shall be accompanied by a cashier's or a certified check or Bidder's admitted corporate surety bond, in an amount not less than ten percent (10%) of the bid, made payable to the City of Redlands. Said check or bond shall be given as a guarantee that the Bidder will enter into a contract if awarded the work. In the case of refusal or failure to enter into said Contract, within fourteen (14) days after Notice of Award by the City in writing, the security shall be applied by the City to the difference between such bid and next lowest acceptable bid and surplus, if any, shall be returned to Bidder if cash or check is used, or to Surety if bid bond is used.

d. Before submitting a bid, Bidders shall carefully examine the Plans; read the Specifications; read all other Contract documents; shall visit the site of the work; shall fully inform themselves as to all existing conditions and limitations; and include in the bid a sum to cover the cost of all items included in the Contract. No allowance will be made due to lack of examination or knowledge. The submission of a bid shall be conclusive evidence that the bidder has investigated and is satisfied as to the conditions to be encountered as to character, quality and scope of work to be performed; the quantities of materials to be furnished; and as to the requirements of the Bid Proposal, plans and specifications.

Redlans Regular Meeting of 09-05-2023
749 of 1115

BD 2
e. Attention is directed to the Federal minimum wage rate requirements. If there is a difference between the minimum wage rates predetermined by the Secretary of Labor and the general prevailing wage rates determined by the Director of the California Department of Industrial Relations for similar classifications of labor, the Contractor and subcontractors shall pay not less than the higher wage rate. This includes “helper” (or other classifications based on hours of experience) or any other classification not appearing in the Federal wage determinations. Where Federal wage determinations do not contain the State wage rate determination otherwise available for use by the Contractor and subcontractors, the Contractor and subcontractors shall pay not less than the Federal minimum wage rate which most closely approximates the duties of the employee in question.

f. The bid must be submitted on or before the date and time specified in the Notice Inviting Sealed Proposals (Bids). The bid shall be submitted in a sealed envelope marked in the lower left corner as follows:

BID FOR: HSIP Cycle 9 Orange Blossom Trail Phase 3 Crossings City Project No. 47033, Federal Project No. HSIPL 5083(024)

g. Bids will be opened and publicly read aloud at the time set in the Notice Inviting Sealed Proposals (Bids), in the Office of the City Clerk, Civic Center, 35 Cajon Street, Suite 4, Redlands, California.

2. AGREEMENT AND BONDS:

The form of Contract which the successful Bidder, as Contractor, will be required to execute is included in the Contract Documents (CD) of these specifications and should be carefully examined by the Bidder. The Agreement, admitted Corporate Surety Bonds and other documents to be executed by the Contractor shall be executed in original-duplicates stamped according to law, one of which original-duplicates shall be filed with the City Clerk of the City of Redlands. The successful Bidder, simultaneously with the execution of the Agreement, will be required to furnish a faithful performance bond and a labor and material bond, each in an amount equal to one hundred percent (100%) of the Contract price. Said bonds shall provide that if the Contractor or their Subcontractor fails to pay for any materials, provision, provender or other supplies or items used in, upon, for or about the performance of the work contracted to be done, or for any work of labor thereon of any kind, or for amounts due under the Unemployment Insurance Act or Workman's Compensation, with respect to such work or labor, that the surety or sureties will pay for the same. The amount shall not exceed the sum specified in the bond, and also, in case suit is brought upon the bond, a reasonable attorney's fee to be fixed by the court. All bonds shall be secured from surety companies satisfactory to the City of Redlands and whose name is on file with the County Clerk of San Bernardino County, as an approved and financially sound surety company authorized to transact business in this state.

3. WITHDRAWAL OF BIDS:

Redlans Regular Meeting of 09-05-2023
750 of 1115

BD 3
a. Any Bidder may withdraw his Bid, only by written request, at any time prior to the scheduled time for Bid Opening.

b. No Bidder may withdraw his Bid for a period of sixty (60) days after the time of Bid Opening except as allowed by the California Public Contract Code.

4. INSURANCE AND HOLD HARMLESS REQUIREMENTS:

Before entering into a Contract, the Bidder to whom the Contract has been awarded shall furnish satisfactory evidence that they have secured all required insurance from a responsible insurance company authorized to do business in California and satisfactory to the City, and such insurance shall be maintained in full force and effect at the Contractor's own expense during the life of the Contract. Contractor shall furnish the City with the customary Certificates of Insurance for all required insurance listed below. General Liability Insurance shall name the City and the Consultant, as an additional insured and shall be primary and non-contributing to any insurance or self-insurance maintained by the City. All liability insurance policies shall bear an endorsement or shall have attached a rider whereby it is provided that, in the event of expiration or proposed cancellation of such policies for any reason whatsoever, the City shall be notified by registered mail, return receipt requested, giving sufficient time before the date thereof to comply with any applicable law or statute, but in no event less than forty five (45) days before expiration or cancellation is effective.

The coverage shall provide the following minimum limits based on the type of work proposed under this Contract. The Contractor shall determine if the proposed work requires Tier 1 or Tier 2 Insurance Requirements as follows:

CONTRACTED OPERATIONS DESIGNATED AS TIER 1
Air Conditioning (HVAC)
Systems (installation)
Electric Light or Power Line
Construction Pipeline Construction
Airport Runways (paving,
repaving, etc.) Elevator Work Roofing
Blasting Operations Excavation Sandblasting
Bridge or Elevated Highway
Construction
Fire Suppression Systems
(installation)
Sewer and Water Main
Construction
Buildings Structural Work
(including elevators)
Gas Mains or Connections
Construction Sign Erection (streets)
Building Structure (raising or
moving) Geophysical Exploration Solar Energy
Cable Installation in Conduits
and Conduit Construction
(streets)
Grading of Land Street Cleaning
Caisson or Cofferdam Work Hazardous Materials
Contractors Street or Road Construction
Dam or Reservoir Construction Irrigation or Drainage
Construction
Tank Construction, Installation,
Erection or Repair
Demolition (structures) Landscape Construction (street
or street medians)
Telephone or Cable Line
Construction
Drilling Painting (exterior greater than
single story)
Tree Pruning, Dusting,
Spraying or Removal
Redlans Regular Meeting of 09-05-2023
751 of 1115

BD 4
TIER 1 DESIGNATED INSURANCE REQUIREMENTS
a. Commercial General Liability
 $1 Million Per Occurrence/ $2 Million Aggregate
 City listed as an Additional Insured on the coverage
 Coverage is primary and non-contributory
 If scope of work is within 50 feet of any railroad, endorsement citing inclusion of liability associated with this work is required
 If any policy forms of endorsements are cited to grant extension of coverage, they must be included with the Certificate of Insurance submission

b. Business Auto Liability
 $1 Million Combined Single Limit
 City listed as an Additional Insured on the coverage
 Must include liability arising from all owned, leased, hired, and non-owned autos  If any policy forms of endorsements are cited to grant extension of coverage, they must be included with the Certificate of Insurance submission  If Contractor or its subcontractors or suppliers haul hazardous material (including, without limitation, waste), Auto Liability insurance must be applicable to all hazardous waste hauling vehicles, and include MCS 90 and CA9948 Endorsements.

c. Commercial Umbrella/ Excess Liability
 $5 Million Per Occurrence/ Aggregate
 City listed as an Additional Insured on the coverage
 Coverage is primary and non-contributory
 If any policy forms of endorsements are cited to grant extension of coverage, they must be included with the Certificate of Insurance submission

d. Workers Compensation
 $1 Million Per Occurrence for Bodily Injury by Accident  $1 Million Each Employee for Bodily Injury by Disease  $1 Million Policy Limit for Bodily Injury by Accident  Waiver of Subrogation in favor of City
 If any policy forms of endorsements are cited to grant extension of coverage, they must be included with the Certificate of Insurance submission

e. Pollution Policy (Hazardous Materials) [If Applicable]  Required of Projects that involve Demolition and/or Excavation Activities  $1 Million Per Occurrence/ $2 Million Aggregate
 City listed as an Additional Insured on the coverage

Redlans Regular Meeting of 09-05-2023
752 of 1115

BD 5

TIER 2 DESIGNATED INSURANCE REQUIREMENTS
a. Commercial General Liability
 $1 Million Per Occurrence/ $2 Million Aggregate
 City listed as an Additional Insured on the coverage
 Coverage is primary and non-contributory
 If scope of work is within 50 feet of any railroad, endorsement citing inclusion of liability associated with this work is required
 If any policy forms of endorsements are cited to grant extension of coverage, they must be included with the Certificate of Insurance submission

b. Business Auto Liability
 $1 Million Combined Single Limit
 City listed as an Additional Insured on the coverage
 Must include liability arising from all owned, leased, hired, and non-owned autos  If any policy forms of endorsements are cited to grant extension of coverage, they must be included with the Certificate of Insurance submission  If Contractor or its subcontractors or suppliers haul hazardous material (including, without limitation, waste), Auto Liability insurance must be applicable to all hazardous waste hauling vehicles, and include MCS 90 and CA9948 Endorsements.

c. Workers Compensation
 $1 Million Per Occurrence for Bodily Injury by Accident  $1 Million Each Employee for Bodily Injury by Disease  $1 Million Policy Limit for Bodily Injury by Accident  Waiver of Subrogation in favor of City
 If any policy forms of endorsements are cited to grant extension of coverage, they must be included with the Certificate of Insurance submission

d. Pollution Policy (Hazardous Materials) [If Applicable]  Required of Projects that involve Demolition and/or Excavation Activities  $1 Million Per Occurrence/ $2 Million Aggregate
 City listed as an Additional Insured on the coverage

CONTRACTED OPERATIONS DESIGNATED AS TIER 2
Air Conditioning (HVAC)
Systems (service and repair) Carpentry (building interiors) Fire Suppression Systems (service and repair)
Alarms and Alarm Systems Communications Equipment
Installation (interior) Landscape Construction
Building Interior Work (service,
repair and non-structural
remodeling)
Driveway, Parking Area or
Sidewalk (paving or repaving) Painting (exterior)
Cable Installation in Conduits
(buildings) Fence Erection All Other Job Types including Vendors
Redlans Regular Meeting of 09-05-2023
753 of 1115

BD 6

Contractor expressly waives all rights to subrogation against the City, its officers, employees and volunteers for losses arising from work performed by Contractor for City by expressly waiving Contractor’s immunity for injuries to Contractor’s employees and agrees that the obligation to indemnify, defend and hold harmless provided for in this Agreement extend to any claim brought by or on behalf of any employee of Contractor. This waiver is mutually negotiated by the parties. This shall not apply to any damage resulting from the sole negligence of City, its agents and employees. To the extent any of the damages referenced herein were caused by or resulted from the concurrent negligence of City, its agents or employees, the obligations provided herein to indemnify, defend and hold harmless are valid and enforceable only to the extent of the negligence of contractor, its officers, agents and employees.

Subcontractors. The prime contractor shall include all subcontractors as insureds under its policies or shall furnish separate certificates and endorsements from each subcontractor.

The Contractor shall not assign or sublet the contract, in whole or in part, without the written consent of the City, nor shall the contractor assign any monies due to, or to become due to, Contractor hereunder without prior written consent of the City.

The Contractor shall be fully responsible to the City for the acts and omissions of the subcontractor and persons either directly or indirectly employed by the Contractor. Consent to subcontracting part of the work shall, in no way, release the Contractor from responsibility for performance of the work, and Contractor will be held, in all respects, accountable for the same as if no consent had been given. The Contractor shall give personal attention to this work which is sublet. Nothing contained in the contract documents shall create any contractual relation between any subcontractor and the City.

Hold Harmless and Indemnification. Contractor shall indemnify, hold harmless and defend City and its elected officials, agents and employees and the Consultant from and against any and all claims, losses or liability, including attorney’s fees, arising from injury or death to persons or damage to property occasioned by any act, omission or failure to act of Contractor, its subcontractors, and any officers, agents and employees in performing the work required by this Agreement. Contractor’s obligations under this provision shall not be limited in any way by any terms of this Agreement, or the insurance limits.

5. LICENSES AND PERMITS:

No bid will be accepted from a Contractor who is not licensed in accordance with the law under the provisions of Division III, Chapter 9 of the Business and Professions Code of the State of California.

The Contractor shall, at the time of bid opening, possess a valid "Class A" and "Class C-10" Contractor's license, and provide its California State Contractor’s License number to the City.

All subcontractors listed at the time of bid opening shall possess a valid Contractor’s license for the work in which they are specified to complete within the Bid Submittal Package.

Redlans Regular Meeting of 09-05-2023
754 of 1115

BD 7
The Contractor shall, prior to Notice to Proceed, procure all other permits and licenses as stipulated in the GENERAL CONDITIONS.

In addition, no contractor or subcontractor may be listed on a bid proposal for a public works project (submitted on or after March 1, 2015 or awarded on or after April 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5.

Contractors shall submit proof of registration status with their bid submission to the City of Redlands. This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.

6. SUBSTITUTION OF SECURITIES:

In accordance with applicable provisions of State law, the Contractor will be permitted to substitute qualified securities in lieu of retention of withheld progress payments by the Owner.

7. SUBCONTRACTORS:

Pursuant to Section 4105 of the California Public Contract Code, the bidder may not circumvent the requirement to list subcontractors by the device of listing one subcontractor, who in turn sublets portions constituting a majority of the work covered by the contract.

A. Pursuant to California Government Code section 4106, subcontractors who will perform work or labor or render services in an amount in excess of one-half of one percent of the Contractor’s total bid shall be set forth in a list of subcontractors within the bid documents. Such list shall be accompanied by an experienced statement with pertinent information regarding similar projects and other evidence of qualifications for each such subcontractor, supplier, individual, or entity if requested by City. If City or engineer, after doing an investigation, has reasonable objection to any proposed subcontractor, supplier, individual, or entity, City may, before the notice of award is given, request the apparent successful bidder to submit a substitute, without an increase in the bid.

B. If the apparent successful bidder declines to make any such substitution, City may award the contract to the next lowest bidder that proposes to use acceptable subcontractors, suppliers, individuals, or entities declining to make the request and substitutions will not constitute grounds for forfeiture of the bid security of any bidder. Any subcontractor, supplier, individual or entity so listed and against which City makes no written objection prior to the giving of the notice of award will be deemed acceptable by City subject to verification of such assessments after the effective date of the agreement as provided herein.

8. NON DEBARRED CONTRACTORS AND SUBCONTRACTORS

The Contractor and all of its subcontractors shall, at the time of bid opening and for performance of this public works contract, be non-debarred contractors and not be ineligible Contractors pursuant to Public Contract Code section 6109 and Labor Code sections 1777.1 and 1777.7.

Redlans Regular Meeting of 09-05-2023
755 of 1115

BD 8

9. LABOR LAW REQUIREMENTS

Prior to the start of construction, the Contractor and each subcontractor shall submit to the City an executed Checklist of Labor Law Requirements, included within Appendix A, certifying that each Contractor and Subcontractor will comply with the foregoing Labor Law requirements; and fully understands that failure to comply with these requirements will subject it to the penalties cited herein.

By submitting a bid, the prime contractor and subcontractors involved in this project assure that they intend to comply with the labor law requirements noted within Appendix A, fully understanding that failure to comply may subject them to penalties as noted.

10. BID PROTEST PROCEDURES

Any bid protest must be in writing and received by the City Clerk’s Office at 35 Cajon Street, Suite 4, Redlands, CA 92373, before 5:00 p.m. no later than two working days following the bid opening (the “Bid Protest Deadline”) and must comply with the following requirements:

10.1 General. Only a bidder who has actually submitted a Bid Proposal is eligible to submit a bid protest against another bidder. Subcontractors are not eligible to submit bid protests. A bidder may not rely on the bid protest submitted by another bidder, but must timely pursue its own protest. If required by City, the protesting bidder must submit a non- refundable fee in the amount specified by City, based upon City’s reasonable costs to administer the bid protest. Any such fee must be submitted to City no later than the Bid Protest Deadline, unless otherwise specified. For purposes of this Section, a “working day” means a day that City is open for normal business, and excludes weekends and holidays as observed by the City.

10.2 Protest Contents. The bid protest must contain a complete statement of the basis for the protest and all supporting documentation. Material submitted after the Bid Protest Deadline will not be considered. The protest must refer to the specific portion or portions of the Contract Documents upon which the protest is based. The protest must include the name, address, email address, and telephone number of the person representing the protesting bidder if different from the protesting bidder.

10.3 Copy to Protested Bidder. A copy of the protest and all supporting documents must be concurrently transmitted by fax or by email, by or before the Bid Protest Deadline, to the protested bidder and any other bidder who has a reasonable prospect of receiving an award depending on the outcome of the protest.

10.4 Response to Protest. The protested bidder may submit a written response to the protest, provided the response is received by the City Clerk’s Office before 5:00 p.m., within two working days after the Bid Protest Deadline or after actual receipt of the bid protest, whichever is sooner (the “Response Deadline”). The response must include all supporting documentation. Material submitted after the Response Deadline will not be considered. The response must include the name, address, email address, and telephone Redlans Regular Meeting of 09-05-2023
756 of 1115

BD 9
number of the person representing the protested bidder if different from the protested bidder.

10.5 Copy of Protesting Bidder. A copy of the response and all supporting documents must be concurrently transmitted by fax or by email, by or before the Bid Protest Deadline, to the protesting bidder and any other bidder who has a reasonable prospect of receiving an award depending upon the outcome of the protest.

10.6 Exclusive Remedy. The procedure and time limits set forth in this section are mandatory and are the bidder’s sole and exclusive remedy in the event of a bid protest. A bidder’s failure to comply with these procedures will constitute a waiver of any right to further pursue a bid protest, including filing a Government Code Claim or initiation of legal proceedings.

10.7 Right to Award. The City Council reserves the right to award the Contract to the bidder it has determined to be the responsible bidder submitting the lowest responsive bid, and to issue a notice to proceed with the Contract notwithstanding any pending or continuing challenge to its determination.

11. AWARD OF CONTRACT

The Award of Contract shall be to the Lowest Responsible Bidder as prescribed by Public Contract Code Section 20164-20172, inclusive.

12. CONTRACT ASSURANCE

The contractor, sub recipient or subcontractor shall not discriminate on the basis of race, color, national origin, or sex in the performance of this contract. The contractor shall carry out applicable requirements of Title 49 CFR (Code of Federal Regulations) part 26 in the award and administration of US DOT assisted contracts. Failure by the contractor to carry out these requirements is a material breach of this contract, which may result in the termination of this contract or such other remedy, as the recipient deems appropriate. Each subcontract signed by the bidder must include this assurance.

13. BID RIGGING

The U.S. Department of transportation (DOT) provides a toll-free hotline to report bid rigging activities. Use the hot-line to report bid rigging, bidder collusion, and other fraudulent activities. The hotline number is (800) 424-9071. The service is available 24 hours 7 days a week and is confidential and anonymous.. The hotline is part of the DOT’s effort to identify and investigate highway construction contract fraud and abuse and is operated under the direction of the dot Inspector General.

Redlans Regular Meeting of 09-05-2023
757 of 1115

BD 10

PROPOSAL

TO: THE CITY OF REDLANDS, SAN BERNARDINO COUNTY, CALIFORNIA herein called the “City”.

Pursuant to and in compliance with your Notice Inviting Bids, and the other documents relating thereto, the undersigned Bidder, having familiarized themselves with the terms of the Contract, the local conditions affecting the performance of the Contract and the cost of the work at the place where the work is to be done, and with the plans thereto, hereby proposes and agrees to perform within the time stipulated, the Contract, including all of its component parts and everything required to be performed, and to provide and furnish any and all of the labor, materials, tools, equipment and all utility and transportation services necessary to perform the contract, and complete in a workmanlike manner, all of the work covered by the contract in connection with the City’s Project identified as

HSIP Cycle 9 Orange Blossom Trail Phase 3 Crossings
City Project No. 47033,
Federal Project No. HSIPL 5083(024)

NOTE: Bidders must bid each item in this schedule. All entries in the entire PROPOSAL must be made clearly and in ink. Mistakes shall be lined through and the correct amount written above and initialed by the authorized agent of the Bidder.

BID SCHEDULE
(See “Section 01200 – Measurement and Payment” for Bid Item description) Item
No. Brief Description Estimated
Quantity
Unit Price
(If Applicable) Total Price in Figures
1 Mobilization (Maximum 5% of
Total Base Bid Price) LUMP SUM N/A $______________________ 2 Traffic Control LUMP SUM N/A $______________________ 3 In-Roadway Warning Light
System 2 EA $_________/EA $______________________
4 Rectangular Rapid Flashing
Beacons (RRFB) with Pole 5 EA $_________/EA
$______________________
5 Annunciating Pushbuttons 5 EA $_________/EA $______________________ 6 Signage and Striping LUMP SUM N/A $______________________ 7 Demobilization LUMP SUM N/A $______________________
8 Unforeseen work not covered
within all other bid items LUMP SUM N/A $17,000
BID SCHEDULE PRICE $______________________

Redlans Regular Meeting of 09-05-2023
758 of 1115

BD 11
Last Minute Additions/Deductions*__________________________________________ Bid Item No.________ Last Minute Additions/Deductions*__________________________________________ Bid Item No.________ Last Minute Additions/Deductions*__________________________________________ Bid Item No.________

BID SCHEDULE TOTAL PRICE: $_______________________________________________________

BID SCHEDULE TOTAL PRICE WRITTEN IN WORDS: ________________________________ _______________________________________________________________________________________________ _______________________________________________________________________________________________

* Provision is made here for the Bidder to include an addition or deduction in its bid, if it wishes, to reflect any last-minute adjustments in prices. The addition or deduction, if made, will be proportionately applied to the Progress Payments total for the respective item in the Schedule of Prices, the amount being added or deducted for each monthly payment. The unit prices entered in the Schedule of Prices will not be affected.

LOW BID DETERMINATION:

The low bid will be determined pursuant to Public Contract Code Section 20103.8 as the lowest bid price on the Bid Schedule Total Price on page BD 11. A responsible bidder who submits the lowest bid as determined by the above method shall be awarded the contract, if it is awarded, by the City Council of the City of Redlands.

Redlans Regular Meeting of 09-05-2023
759 of 1115

BD 12

ADDENDA

Receipt of the following addenda is hereby acknowledged and the same is included in the Bid Price:

Addendum #1___________ Addendum #2___________ Addendum #3____________ (initials) (initials) (initials)

Addendum #4___________ Addendum #5___________ Addendum #6____________ (initials) (initials) (initials)

ATTEST: (if Corporation)

(Corporation Seal)

___________________________________ _____________________________________ Company Name Signature

____________________________________ _____________________________________ Address Name

____________________________________ _____________________________________ City, State, Zip Title

Redlans Regular Meeting of 09-05-2023
760 of 1115

BD 13

BID CERTIFICATION

The undersigned certifies that they are familiar with the various State and local laws affecting labor, length of working days, employer's liabilities, Sunday work, alien labor, domestic materials, Subcontractors, etc.

It is understood and agreed that the work under the contract will be commenced by the undersigned Bidder, if awarded the contract, within ten (10) calendar days from the date in the Notice to Proceed and will be completed by the Contractor in the time set forth in the CONTRACT.

Enclosed find Bidders bond or certified or cashier's check No. _________________ on the __________________________________ Bank, in the amount of ______________________ _______________________ which is not less than ten percent (10%) of the Bid submitted by the undersigned, made payable to the City of Redlands, California and which is given as a guarantee that the Bidder agrees that in case of their default in executing said contract with necessary bonds, the bond or check accompanying this Bid and the money made payable shall become and remain the property of the City of Redlands.

It is understood and agreed that the City of Redlands has the right to waive defects or irregularities and to accept or reject any or all Bids. No Bidder may withdraw their Bid for a period of sixty (60) days after the time of the Bid Opening except as allowed by the California Public Contract Code.

The following information, required by State law under penalty of perjury, is true and correct. Failure to complete this information renders the bid non-responsive, and the bid must be rejected.

____________________________________ _______________________________________ Company Name Signature

____________________________________ _______________________________________ Address Signatory's Title

____________________________________ _______________________________________ City, State, Zip State License Number and Class

____________________________________ _______________________________________ Telephone Number License Expiration Date

Dated this ________________ day of ___________________, 20___.

Redlans Regular Meeting of 09-05-2023
761 of 1115

BD 14

BID BOND

KNOW ALL PERSONS BY THESE PRESENTS,

That ______________________________________________________________ as Principal, and ______________________________________ as Surety, are held and firmly bound unto the City of Redlands, hereinafter called City, in the sum of ______________________________________ dollars, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors, and assigns, jointly and severally, firmly by these presents.

WHEREAS, said Principal has submitted a bid to said City to perform all work required under the City Project No. 47033, Federal Project No. HSIPL 5083(024).

NOW, THEREFORE, if said Principal is awarded a contract by said City and, within the time and in the manner required under the heading "Instructions to Bidders" bound with said Specifications, enters into a written contract on the form of agreement bound with said Specifications and furnishes the required bonds, one to guarantee faithful performance and the other to guarantee payment for labor and materials; then this obligations shall be null and void, otherwise it shall remain in full force and effect. In the event suit is brought upon this bond by said City and Judgment is recovered, said Surety shall pay all costs incurred by said City in such suit, including a reasonable attorney's fee to be fixed by the court.

SIGNED AND SEALED, this _________ day of _____________________________, 20____.

______________________________(SEAL) _______________________________ (SEAL) (Principal) (Surety)

By:_________________________________ By:__________________________________ (Signature) (Signature)

Address:______________________________
_____________________________________
Telephone (___)________________________
(Seal and Notarial Acknowledgment of Surety)
Redlans Regular Meeting of 09-05-2023
762 of 1115

BD 15

EQUAL EMPLOYMENT OPPORTUNITY CERTIFICATION

The bidder , proposed subcontractor , hereby certifies that he has , has not , participated in a previous contract or subcontract subject to the equal opportunity clauses, as required by Executive Orders 10925, 11114, or 11246, and that, where required, he has filed with the Joint Reporting Committee, the Director of the Office of Federal Contract Compliance, a Federal Government contracting or administering agency, or the former President’s Committee on Equal Employment Opportunity, all reports due under the applicable filing requirements.

Note: The above certification is required by the Equal Employment Opportunity Regulations of the Secretary of Labor (41 CFR 60-1.7(b)(1)), and must be submitted by bidders and proposed subcontractors only in connection with contracts and subcontracts which are subject to the equal opportunity clause. Contracts and subcontracts which are exempt from the equal opportunity clause are set forth in 41 CFR 60-1.5. (Generally only contracts or subcontracts of $10,000 or under are exempt.)

Currently, Standard Form 100 (EEO-1) is the only report required by the Executive Orders or their implementing regulations.

Proposed prime contractors and subcontractors who have participated in a previous contract or subcontract subject to the Executive Orders and have not field the required reports should note that 41 CFR 60-1.7(b)(1) prevents the award of contracts and subcontracts unless such contractor submits a report covering the delinquent period or such other period specified by the Federal Highway Administration or by the Director, Office of Federal Contract Compliance, U.S. Department of Labor.

ACKNOWLEDGED this day of , .

_____________
Contractor’s Signature

_____________
Contractor’s Name

_____________
Address

_____________
City

Redlans Regular Meeting of 09-05-2023
763 of 1115

BD 16

STATEMENT BY BIDDER

NON-COLLUSION AFFIDAVIT

STATE OF )
) ss

COUNTY OF )

, being first duly sworn, deposes and says that

he is
(Sole Owner, a Partner, President, Secretary, etc.)

of
(Contractor)

the party making the foregoing bid on City Project No. 47033, Federal Project No. HSIPL 5083(024). that such bid is not made in the interest of or on behalf of any undisclosed person, partnership, company, association, organization, or corporation; that the bid is genuine and not collusive or sham; that the Bidder has not directly or indirectly induced or solicited any other Bidder to put in a false or sham bid, and has not directly or indirectly colluded, conspired, connived, or agreed with any Bidder or anyone else to put in a sham bid, or that anyone shall refrain from bidding; that the Bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the Bidder or of any other Bidder or to fix any overhead, profit, or cost element of the bid price or of that of another bidder, or to secure any advantage against the public body awarding the Contract of anyone interested in the proposed contract; that all statements contained in such bid are true; and further, that the Bidder has not directly or indirectly, submitted his bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, or paid, and will not pay, any fee to any corporation, partnership, company, association organization, bid depository, or to any member or agent thereof to effectuate a collusive or sham bid.

By: ______________________________ Title: ________________________________

Subscribed and sworn to before me this day of __________________________, 20 .

Signature of Officer Administering Oath
(Notary Public)

Redlans Regular Meeting of 09-05-2023
764 of 1115

BD 17

STATEMENT BY BIDDER
OFFICERS OF CORPORATION (Members of Firm)

The names of all persons interested in the foregoing proposals as principals, are as follows:
(IMPORTANT NOTICE - if Bidder or other interested person is a corporation, state legal name of corporation, also names of the president, secretary, treasurer and manager thereof; if a co-partnership, state true name of firm, also names of all individual co-partners composing firm; if Bidder or other interested person is an individual, state first and last names in full).

_____________________________________ _____________________________________

_____________________________________ _____________________________________

_____________________________________ _____________________________________

Licensed in accordance with an act providing for the Registration of Contractors, License

No. ______________________________________.

Signature of Bidder Dated

NOTE: If Bidder is a corporation, the legal name of the corporation shall be set forth above, together with the signature of the officer(s) authorized to sign contracts on behalf of the corporation; if Bidder is a co-partnership, the true name of the firm shall be set forth above, together with the signature of the partner or partners authorized to sign contracts in behalf of the co-partnership, and if the Bidder is an individual, that signature shall be placed above.

Redlans Regular Meeting of 09-05-2023
765 of 1115

BD 18

STATEMENT BY BIDDER

SUB-CONTRACTORS LIST

Bidder supplies the following information for any Subcontractor who will perform work or labor or render services to the prime contractor, etc. to be used on City Project No. 47033, Federal Project No. HSIPL 5083(024), all in accordance with Section 4104 of the California Public Contract Code.

LICENSED SUBCONTRACTOR’S NAME

AND BUSINESS ADDRESS

LICENSE #

SPECIFIC

DESCRIPTION

OF SUBCONTRACT
& BID ITEM #
% OF BID

ITEM TO BE

PERFORMED

Redlans Regular Meeting of 09-05-2023
766 of 1115

BD 19

STATEMENT BY BIDDER

QUALIFICATION AND EXPERIENCE STATEMENT

The following outline is a record of the undersigned Bidder's experience in construction of three (3) projects of a type similar in magnitude and character to that contemplated under City Project No. 47033, Federal Project No. HSIPL 5083(024), within the past two years. Include the location of each project as well as the name, address, and phone number of the owner, and name of individual to contact.

Subcontractors performing in excess of one half of one percent of the prime Contractor’s total bid, or in the construction of streets or highways, one half of one percent of the prime contractor’s total bid or ten thousand dollars ($10,000), whichever is greater shall provide a similar outline.

Additional pages outlining this portion of the Bid may be attached. Failure to provide this statement may result in rejection of the bid by the City of Redlands.

1. Owner's Name:

Contact Person: Phone: ( ) Address of Owner:

Project Description:

Amount of Contract: Completion Date:

2. Owner's Name:

Contact Person: Phone: ( ) Address of Owner:

Project Description:

Amount of Contract: Completion Date:

3. Owner's Name:

Contact Person: Phone: ( ) Address of Owner:

Project Description:

Amount of Contract: Completion Date:

Redlans Regular Meeting of 09-05-2023
767 of 1115

BD 20

STATEMENT BY BIDDER

GENERAL INFORMATION

1. Bidder's Mailing Address

2. Number of years engaged in the contracting business under your present firm or trade name:

3. Have you ever failed to complete any work awarded to you? (Yes or No) . If yes, provide details in the space provided in Item 10.

4. Have you ever defaulted on a contract? (Yes or No) . If yes, provide details in the space provided in Item 10.

5. Have you ever been a party to a lawsuit or gone to arbitration during the last 5 years? (Yes or No) . If yes, provide details in the space provided in Item 10.

6. Has any Stop Notice been filed against you during the last 5 years? (Yes or No) . If yes, provide details in the space provided in Item 10.

7. Has your contractor's license ever been suspended, revoked, or subject to disciplinary action? (Yes or No) . If yes, provide details in the space provided in Item 10.

8. Contracts currently on hand:

Agency Name Amount of Contract Start Date Completion Date

9. Enter the name of person(s) who inspected the site of the proposed work for your firm and the date of said site inspection.

Name: Date:

Redlans Regular Meeting of 09-05-2023
768 of 1115

BD 21

10. In the space provided, the Bidder shall provide details concerning any "Yes" answers provided in this "General Information" section. Details shall include, but not be limited to, the nature of dispute, name of the agency involved and the final outcome. If requested by the City, the Bidder shall supply additional information, sufficiently detailed, to permit evaluation of the Bidder's ability to perform the work.

Question
Number Details

Redlans Regular Meeting of 09-05-2023
769 of 1115

BD 22

DEBARMENT AND SUSPENSION CERTIFICATION

TITLE 49, CODE OF FEDERAL REGULATIONS, PART 29

The bidder, under penalty of perjury, certifies that, except as noted below, he/she or any other person associated therewith in the capacity of owner, partner, director, officer, manager:
• is not currently under suspension, debarment, voluntary exclusion, or determination of ineligibility by any Federal agency;
• has not been suspended, debarred, voluntarily excluded or determined ineligible by any Federal agency within the past 3 years;
• does not have a proposed debarment pending; and
• has not been indicted, convicted, or had a civil judgment rendered against it by a court of competent jurisdiction in any matter involving fraud or official misconduct within the past 3 years.

If there are any exceptions to this certification, insert the exceptions in the following space.

Exceptions will not necessarily result in denial of award, but will be considered in determining bidder responsibility. For any exception noted above, indicate below to whom it applies, initiating agency, and dates of action.

Notes: Providing false information may result in criminal prosecution or administrative sanctions.

The above certification is part of the Proposal. Signing this Proposal on the signature portion thereof shall also constitute signature of this Certification.

Redlans Regular Meeting of 09-05-2023
770 of 1115

BD 23

NONLOBBYING CERTIFICATION

FOR FEDERAL-AID CONTRACTS

The prospective participant certifies, by signing and submitting this bid or proposal, to the best of his or her knowledge and belief, that:

(l) No Federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or attempting to influence an officer or employee of any Federal agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any Federal contract, grant, loan, or cooperative agreement.

(2) If any funds other than Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any Federal agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with this Federal contract, grant, loan, or cooperative agreement, the undersigned shall complete and submit Standard Form-LLL, "Disclosure of Lobbying Activities," in conformance with its instructions.

This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by Sec tion
1352, Title 31, U.S. Code. Any person who fails to file the required certification shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.

The prospective participant also agrees by submitting his or her bid or proposal that he or she shall require that the language of this certification be included in all lower tier subcontracts, which exceed $100,000 and that all such subrecipients shall certify and disclose accordingly.

Redlans Regular Meeting of 09-05-2023
771 of 1115

BD 24

DISCLOSURE OF LOBBYING ACTIVITIES
COMPLETE THIS FORM TO DISCLOSE LOBBYING ACTIVITIES PURSUANT TO 31 U.S.C. 1352

1. Type of Federal Action: 2. Status of Federal Action: 3. Report Type:
a. contract a. bid/offer/application a. initial
b. grant b. initial award b. material change
c. cooperative agreement c. post-award
d. loan For Material Change Only:
e. loan guarantee year _____ quarter ________
f. loan insurance date of last report __________

4. Name and Address of Reporting Entity 5. If Reporting Entity in No. 4 is Subawardee, Enter Name and Address of Prime:

Prime Subawardee
Tier _______ , if known

Congressional District, if known Congressional District, if known

6. Federal Department/Agency: 7. Federal Program Name/Description:

CFDA Number, if applicable ___________________

8. Federal Action Number, if known: 9. Award Amount, if known:

10. a. Name and Address of Lobby Entity b. Individuals Performing Services (including (If individual, last name, first name, MI) address if different from No. 10a) (last name, first name, MI)

(attach Continuation Sheet(s) if necessary)

11. Amount of Payment (check all that apply) 13. Type of Payment (check all that apply)

$ _____________ actual planned a. retainer
b. one-time fee

12. Form of Payment (check all that apply): c. commission a. cash d. contingent fee
b. in-kind; specify: nature ______________ e deferred value ______________ f. other, specify _________________________

14. Brief Description of Services Performed or to be performed and Date(s) of Service, including officer(s), employee(s), or member(s) contacted, for Payment Indicated in Item 11:

(attach Continuation Sheet(s) if necessary)

15. Continuation Sheet(s) attached: Yes No

16. Information requested through this form is authorized by Title 31 U.S.C. Section 1352. This disclosure of lobbying reliance was placed by the tier above when his transaction was made or entered into. This disclosure is required
pursuant to 31 U.S.C. 1352. This information will be
reported to Congress semiannually and will be available for public inspection. Any person who fails to file the required disclosure shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.

Signature: ________________________________________

Print Name: ______________________________________

Title: ____________________________________________

Telephone No.: ____________________ Date: __________

Authorized for Local Reproduction
Federal Use Only: Standard Form - LLL
Redlans Regular Meeting of 09-05-2023
772 of 1115

BD 25

INSTRUCTIONS FOR COMPLETION OF SF-LLL,

DISCLOSURE OF LOBBYING ACTIVITIES

This disclosure form shall be completed by the reporting entity, whether subawardee or prime Federal recipient, at the initiation or receipt of covered Federal action or a material change to previous filing pursuant to title 31 U.S.C. section 1352. The filing of a form is required for such payment or agreement to make payment to lobbying entity for influencing or attempting to influence an officer or employee of any agency, a Member of Congress an officer or employee of Congress or an employee of a Member of Congress in connection with a covered Federal action. Attach a continuation sheet for additional information if the space on the form is inadequate. Complete all items that apply for both the initial filing and material change report. Refer to the implementing guidance published by the Office of Management and Budget for additional information.

1. Identify the type of covered Federal action for which lobbying activity is and/or has been secured to influence, the outcome of a covered Federal action.

2. Identify the status of the covered Federal action.

3. Identify the appropriate classification of this report. If this is a follow-up report caused by a material change to the information previously reported, enter the year and quarter in which the change occurred. Enter the date of the last, previously submitted report by this reporting entity for this covered Federal action.

4. Enter the full name, address, city, state and zip code of the reporting entity. Include Congressional District if known.

Check the appropriate classification of the reporting entity that designates if it is or expects to be a prime or subaward recipient. Identify the tier of the subawardee, e.g., the first subawardee of the prime is the first tier. Subawards include but are not limited to subcontracts, subgrants and contract awards under grants.

5. If the organization filing the report in Item 4 checks "Subawardee" then enter the full name, address, city, state and zip code of the prime Federal recipient. Include Congressional District, if known.

6. Enter the name of the Federal agency making the award or loan commitment. Include at least one organization level below agency name, if known. For example, Department of Transportation, United States Coast Guard.

7. Enter the Federal program name or description for the covered Federal action (item 1). If known, enter the full Catalog of Federal Domestic Assistance (CFDA) number for grants, cooperative agreements, loans and loan commitments.

8. Enter the most appropriate Federal identifying number available for the Federal action identification in item 1 (e.g., Request for Proposal (RFP) number, Invitation for Bid (IFB) number, grant announcement number, the contract grant. or loan award number, the application/proposal control number assigned by the Federal agency). Include prefixes, e.g., "RFP-DE-90-001."

9. For a covered Federal action where there has been an award or loan commitment by the Federal agency, enter the Federal amount of the award/loan commitments for the prime entity identified in item 4 or 5.

10. (a) Enter the full name, address, city, state and zip code of the lobbying entity engaged by the reporting entity identified in item 4 to influenced the covered Federal action.
(b) Enter the full names of the individual(s) performing services and include full address if different from 10 (a). Enter Last Name, First Name and Middle Initial (Ml).

11. Enter the amount of compensation paid or reasonably expected to be paid by the reporting entity (item 4) to the lobbying entity (item 10). Indicate whether the payment has been made (actual) or will be made (planned). Check all boxes that apply. If this is a material change report, enter the cumulative amount of payment made or planned to be made.

12. Check the appropriate box. Check all boxes that apply. If payment is made through an in-kind contribution, specify the nature and value of the in-kind payment.

13. Check the appropriate box. Check all boxes that apply. If other, specify nature.

14. Provide a specific and detailed description of the services that the lobbyist has performed or will be expected to perform and the date(s) of any services rendered. Include all preparatory and related activity not just time spent in actual contact with Federal officials. Identify the Federal officer(s) or employee(s) contacted or the officer(s) employee(s) or Member(s) of Congress that were contacted.

15. Check whether or not a continuation sheet(s) is attached.

16. The certifying official shall sign and date the form, print his/her name title and telephone number.

Public reporting burden for this collection of information is estimated to average 30 minutes per response, including time for reviewing instruction, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding the burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Office of Management and Budget, Paperwork Reduction Project (0348-0046), Washington, D.C. 20503.

SF-LLL-Instructions Rev. 06-04-90«ENDIF»
Redlans Regular Meeting of 09-05-2023
773 of 1115

THIS PAGE INTENTIONALLY LEFT BLANK

Redlans Regular Meeting of 09-05-2023
774 of 1115

CONTRACT DOCUMENTS
(CD)

Redlans Regular Meeting of 09-05-2023
775 of 1115

THIS PAGE INTENTIONALLY LEFT BLANK

Redlans Regular Meeting of 09-05-2023
776 of 1115

CD 1

PUBLIC WORK CONSTRUCTION CONTRACT

This Public Work Construction contract (“Contract”) is made and entered into this ___ day of ____________, 2023, by and between the City of Redlands, a municipal corporation, organized and existing under the laws of the State of California (hereinafter “City”), and __________________ (hereinafter "Contractor"). City and Contractor are sometimes individually referred to herein as a “Party” and, together, as the “Parties.”

In consideration of the mutual promises contained herein, City and Contractor agree as follows:

1. SCOPE OF WORK: Contractor shall furnish all materials and will perform all of the work for the following: HSIP Cycle 9 Orange Blossom Trail Phase 3 Crossings, complete all items as required by the Contract Documents (as herein defined) and Specifications for City’s HSIP Cycle 9 Orange Blossom Trail Phase 3 Crossings, City Project No. 47033, Federal Project No. HSIPL 5083(024) (the “Work”).

2. CONTRACT SUM: City shall pay Contractor the sum of ___________________ dollars ($___________) as consideration for its performance of the Work in accordance with the terms and conditions set forth in the Contract Documents. Pursuant to Public Contract Code Section 22300, Contractor has the option to deposit securities with an escrow agent as a substitute for retention of earnings required to be withheld by City pursuant to an escrow agreement as set forth in Public Contract Code section 22300.

3. TIME FOR COMPLETION: The Work shall be completed within One Hundred (100) calendar days from and after the date of City’s issuance of a Notice to Proceed to Contractor.

4. LIQUIDATED DAMAGES: Contractor’s failure to complete the Work within the time allowed will result in damages being sustained by City. Such damages are, and will continue to be, impracticable and extremely difficult to determine. Accordingly, Contractor shall pay to City, or have withheld from monies due to Contractor, the sum of Five Hundred Dollars ($500) for each consecutive calendar day in excess of the specified time for completion of the Work.

Execution of this Contract shall constitute agreement by City and Contractor that Five Hundred Dollars ($500) per day is the estimated damage to City caused by the failure of the Contractor to complete the work within the allowed time. Such sum is liquidated damages and shall not be construed as a penalty, and may be deducted from payments due the Contractor if such delay occurs.

5. CONTRACT DOCUMENTS: This Contract incorporates by reference the following: Notice Inviting Bids, Instructions to Bidders, Contractor’s Proposal, Bid Bond, Agreement, Performance Bond, Labor and Material Bond, Plans, General Conditions, Special Provisions and Specifications, and any addenda thereto (collectively, the “Contract Documents”).

6. ATTORNEYS' FEES: In the event any action is commenced to enforce or interpret the terms or conditions of this Contract, or the Contract Documents, the prevailing Party in such action, in addition to any costs and other relief, shall be entitled to recover its reasonable attorneys’ fees, including fees for use of in-house counsel by a Party.

Redlans Regular Meeting of 09-05-2023
777 of 1115

CD 2

7. RESOLUTION OF CONSTRUCTION CLAIMS: Claims by Contractor in the amount of three hundred seventy five thousand dollars ($375,000) or less shall be made by Contractor and processed by the City pursuant to the provisions of Part 3, Chapter 1, Article 1.5 of the Public Contract Code (commencing with Section 20104). All claims shall be in writing and include the documents necessary to substantiate the claim. Nothing in subdivision (a) of Public Contract Code Section 20104.2 shall extend the time limit or supersede the notice requirements provided in this case from filing claims by Contractor.

8. ELIGIBILITY OF CONTRACTOR/SUBCONTRACTOR: Contractor and all of its subcontractors shall abide by California Public Contract Code, Section 6109, and California Labor Code Sections 1777.1 and/or 1777.7, and certify that they are not debarred and are eligible to work on this project.

9. ASSIGNMENT OF AGREEMENT: No assignment by a Party of any rights or interests under this Contract shall be binding on another Party without the written consent of the Party sought to be bound.

10. SUCCESSORS AND ASSIGNS: City and Contractor each binds itself and their respective successors and assigns in respect to all covenants, agreements, and obligations contained in the Contract Documents.

11. SEVERABILITY: Any provision or part of the Contract Documents held to be void or unenforceable under any law or regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon City and Contractor.

Redlans Regular Meeting of 09-05-2023
778 of 1115

CD 3

IN WITNESS WHEREOF, the Parties hereto have executed this Contract the day and year first written above.

CITY OF REDLANDS
(SEAL)

By:____________________________________
Eddie Tejeda, Mayor
ATTEST:

____________________________________
Jeanne Donaldson, City Clerk
(SEAL)

__________________________________________
Name of Contractor

By:_______________________________________
Signature of Authorized Agent

__________________________________________
Title

__________________________________________
Signature of Authorized Agent (if necessary)

__________________________________________
Title

__________________________________________
Contractor's License No.

Redlans Regular Meeting of 09-05-2023
779 of 1115

CD 4

WORKER'S COMPENSATION INSURANCE CERTIFICATION

Description of Contract: City of Redlands
Municipal Utilities and Engineering Department
HSIP Cycle 9 Orange Blossom Trail Phase 3 Crossings
City Project No. 47033,
Federal Project No. HSIPL 5083(024)

Every employer, except the State, shall secure the payment of compensation in one or more of the following ways:

a. By being insured against liability to pay compensation by one or more insurers duly authorized to write compensation insurance in this State. b. By securing from the Director of Industrial Relations, a certificate of consent to self-insure, either as an individual employer, or as one employer in a group of employers, which may be given upon furnishing proof satisfactory to the Director of Industrial Relations of ability to self-insure and to pay any compensation that may become due to his or her employees.

CHECK ONE

_____I am aware of the provisions of Section 3700 of the Labor Code which requires every employer to be insured against liability for Workers’ Compensation or to undertake self-insurance in accordance with the provisions of that Code, and I will comply with such provisions before commencing the performance of the work and activities required or permitted under this Agreement. (Labor Code §1861).

_____I affirm that at all times, in performing the work and activities required or permitted under this Agreement, I shall not employ any person in any manner such that I become subject to the workers’ compensation laws of California. However, at any time, if I employ any person such that I become subject to the workers’ compensation laws of California, immediately I shall provide the City with a certificate of consent to self-insure, or a certification of workers’ compensation insurance.

I certify under penalty of perjury under the laws of the State of California that the information and representations made in this certificate are true and correct.

Dated this day of , 2023. _____________________________________
(Contractor)
_____________________________________
(Signature)
_____________________________________
(Official Title)
(SEAL)
(Labor Code Section 1861 provides that the above certificate must be signed and filed by the Contractor with the Owner prior to performing the work of the contract.) Redlans Regular Meeting of 09-05-2023
780 of 1115

CD 5

FAITHFUL PERFORMANCE BOND

Whereas, the City of Redlands (“City”), State of California, and ______________ (hereinafter designated as "Principal") have entered into an agreement dated _____, 2023 (“Agreement”) whereby Principal agrees to install and complete certain public improvements (the “Work”), which said Agreement is identified as _________________ and is hereby referred to and made a part hereof; and

Whereas, said Principal is required under the terms of the Agreement to furnish a bond for the faithful performance of the Work, now, therefore, we, the Principal and, _____________________________, as Surety, are held and firmly bound unto the City in the penal sum of ________________________________ dollars ($_______________) lawful money of the United States, for the payment of which sum we bind ourselves, and our heirs, successors, executors and administrators, jointly and severally, firmly by these presents.

The condition of this obligation is such that if the above bounded Principal, his or its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions and provisions in the Agreement and any alteration thereof made as therein provided, on his or its part, to be kept and performed at the time and in the manner therein specified, and in all respects according to their true intent and meaning, and shall faithfully fulfill the one-year guarantee of all materials and workmanship, and shall defend, indemnify and save harmless the City and its elected officials, officers, agents and employees, as therein stipulated, then this obligation shall become null and void; otherwise it shall be and remain in full force and effect.

As a part of the obligation secured hereby and in addition to the face amount specified therefor, there shall be included costs and reasonable expenses and fees, including reasonable attorneys’ fees, incurred by the City in successfully enforcing such obligations, all to be taxed as costs and included in the judgment rendered.

As a condition precedent to the satisfactory completion of the Work, the above obligation shall hold good for a period of one (1) year or longer if required by the Agreement after the acceptance of the work by the City, during which time if the Principal shall fail to make full, complete, and satisfactory repair and replacements and totally protect the City from loss or damage made evident during this period from the date of completion of the Work, and resulting from or caused by defective materials or faulty workmanship, the above obligation in penal sum thereof shall remain in full force and effect. The obligations of Surety hereunder shall continue so long as any obligation of the Principal remains.

Whenever the Principal shall be, and is declared by the City to be, in default under the Agreement, the City having performed the City obligations thereunder, the Surety shall promptly remedy the default, or shall promptly, at the City’s option:

1. Complete the Work in accordance with its terms and conditions; or

2. Obtain a bid or bids for completing the Work in accordance with its terms and conditions, and upon determination by Surety of the lowest responsive and responsible bidder, Redlans Regular Meeting of 09-05-2023
781 of 1115

CD 6

arrange for a contract between such bidder and the City, and make available as work progresses sufficient funds to pay the cost of completion of the Work less the balance of the Agreement price, but not exceeding, including other costs and damages for which Surety may be liable hereunder, the amount set forth above. The term “balance of the Agreement price,” as used in this paragraph, shall mean the total amount payable to the Principal by the City under the Agreement and any modifications thereto, less the amount previously properly paid by the City to the Principal.

Surety expressly agrees that the City may reject any contractor or subcontractor which may be proposed by Surety in fulfillment of its obligations in the event of default by the Principal.

Surety shall not utilize the Principal in completing the Work nor shall Surety accept a bid from the Principal for completion of the Work if the City, when declaring the Principal in default, notifies Surety of the City’s objection to the Principal’s further participation in the completion of the Work.

No right of action shall accrue on the bond to or for the use of any person or corporation other than the City named herein or the successors or assigns of the City. Any suit under this bond must be instituted within the applicable statute of limitations period.

The said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Agreement or to the work to be performed thereunder or the Specifications accompanying the same shall in any way affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Agreement or to the work or to the specifications.

No final settlement between the City and the Principal shall abridge the right of any beneficiary hereunder whose claim may be unsatisfied.

The Principal and Surety agree that if the City is required to engage the services of any attorney in connection with the enforcement of this bond, each shall pay the City’s reasonable attorneys’ fees incurred, with or without suit, in addition to the above sum.

In witness whereof, this instrument has been duly executed by the Principal and Surety above named, on , 2023.

(SEAL) (SEAL)

(Contractor) (Surety)
BY:
(Signature) (Signature)

Address:___________________________________
__________________________________________
(Seal and Notarial Acknowledgment of
Surety)
Telephone ( )___________________________

Redlans Regular Meeting of 09-05-2023
782 of 1115

CD 7

LABOR AND MATERIAL BOND

Whereas, the City Council of the City of Redlands, State of California, and ________________ (hereinafter designated as “Principal”) have entered into an agreement (the “Agreement”) whereby Principal agrees to install and complete certain designated public improvements (the “Work”), which said agreement, dated ____________, 2023, and identified as __________________________ is hereby referred to and made a part hereof; and

Whereas, under the terms of the Agreement, Principal is required before commending the performance of the Work, to file a good and sufficient Labor and Material bond with the City of Redlands to secure the claims to which reference is made in Title 3 (commencing with Section 9550) of Part 6 of Division 4 of the Civil Code of the State of California.

Now, therefore, said Principal and the undersigned as corporate surety, are held firmly bound unto the City and all contractors, subcontractors, laborers, material men and other persons employed in the performance of the Agreement and referred to in the aforesaid Code of Civil Procedure in the sum of ______________ dollars ($_____) for materials furnished or labor thereon of any kind, or for amounts due under the Unemployment Insurance Act with respect to such work or labor, that said surety will pay the same in an amount not exceeding the amount hereinabove set forth, and also in case suit is brought upon this bond, will pay, in addition to the face amount thereof, costs and reasonable expenses and fees, including reasonable attorneys’ fees, incurred by the City in successfully enforcing such obligation, to be awarded and fixed by the court, and to be taxed as costs and to be included in the judgment therein rendered.

It is hereby expressly stipulated and agreed that this bond shall insure to the benefit of any and all persons, companies and corporations entitled to file claims under Title 3 (commencing with Section 9550) of Part 6 of Division 4 of the Civil Code, so as to give a right of action to them or their assigns in any suit brought upon this bond.

Should the condition of this bond be fully performed, then this obligation shall become null and void, otherwise it shall be and remain in full force and effect.

The surety hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Agreement or the specifications accompanying the same shall in any manner affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition.

Redlans Regular Meeting of 09-05-2023
783 of 1115

CD 8

In witness whereof, this instrument has been duly executed by the Principal and surety above named, on _______________________, 2023.

(SEAL) (SEAL)

(Contractor) (Surety)
BY:
(Signature) (Signature)
Address:_____________________________
(Seal and Notarial Acknowledgement of Surety) ____________________________________ Telephone: ( )___________________
Redlans Regular Meeting of 09-05-2023
784 of 1115

GENERAL CONDITIONS
(GC)
Redlans Regular Meeting of 09-05-2023
785 of 1115

THIS PAGE INTENTIONALLY LEFT BLANK
Redlans Regular Meeting of 09-05-2023
786 of 1115

GC 1

GENERAL CONDITIONS

The Standard Specifications for Public Works Constructions, 2021 Edition (Greenbook), together with supplements as published by Building News, Inc., are modified herein and comprise the Standard Specifications. For convenience, the section and subsection numbering system used in these modifications correspond to those used in the Greenbook. Unless specifically deleted or modified herein, all requirements of the Greenbook shall prevail.

SECTION 1 – GENERAL, TERMS, DEFINITIONS, ABBREVIATIONS,

UNITS OF MEASURE, AND SYMBOLS

1-2 TERMS AND DEFINITIONS.

Agency - Amend as follows:
“The legal entity (City) for which the Work is being performed.”

Bidder - Amend as follows:
“Any individual, firm, partnership, corporation, or combination thereof, licensed in accordance with the provisions of Chapter 9, Division III of the Business and Professions Code, submitting a Bid for the Work, acting directly or through a duly authorized representative.”

City. The City of Redlands, San Bernardino County, California, being the legal entity for which the Work is being performed. Also referred to as Agency or Owner.

City Council. The City Council of the City of Redlands, San Bernardino County, California, being the body authorizing entrance into legal agreements and allowing work in public right-of- way or on public property controlled by the City of Redlands. Also referred to as Board.

Engineer - Amend as follows:
“The Chief Engineer of the Agency, being the Municipal Utilities and Engineering Director, or other person designated by the Board or Chief Engineer, acting either directly or through authorized agents.”

Fabricated. An item specifically assembled or made out of selected materials to meet individual design requirements.

Guarantee. See Warranty.

Laboratory. The designated laboratory authorized by the City of Redlands to test materials and work involved in the Contract.

Manufactured. A standard mass-produced unit or item meeting design requirements.

Owner. The City of Redlands, San Bernardino County, California.

Redlans Regular Meeting of 09-05-2023
787 of 1115

GC 2

Pavement. The uppermost layer of material placed on the traveled way or shoulder. Also referred to as surfacing.

Rain Day. A scheduled working day when you cannot perform work on the controlling activity for at least 50 percent of the day with at least 50 percent of the normal labor and equipment due to adverse weather-related conditions that cause the Contractor to dismiss the crew.

Street - Delete and replace with the following:
“Any road, highway, parkway, freeway, avenue, street, lane, alley, crossing, intersection, court, place, circle, walk, way, or any public right-of-way within the jurisdiction of the Agency.”

Surety - Delete and replace with the following:
“An admitted corporate surety as listed by the United States Department of Treasury and duly licensed to conduct business in the State of California and County of San Bernardino and acceptable to the City of Redlands, bound with and for the Contractor for the acceptable performance, execution, and completion of the Work, and for the satisfaction of all obligations incurred.”

Warranty. An extended insurance by the Contractor, of any product or item of work installed as a part of this project for replacement and/or repair for the time period specified, including but not limited to, all parts, labor, materials, tools, equipment costs, etc. necessary for the product or item of work to be in proper and acceptable working condition after completion of the project. For the purposes of this Contract, the period of coverage shall begin on the date of the Notice of Completion filed by the Owner.

Working Hours. Unless specified otherwise, working hours shall be from 7:00 AM to 4:00 PM, Monday through Friday, inclusive. Saturdays, Sundays, and City Holidays, as shown on the current year Construction Schedule, are excluded unless authorized by the City.

1-7.2 CONTRACT BONDS. - Add the following sentence to paragraph 1:

The warranty provisions set forth in Section 3-13.3 shall be secured by the Contract Performance Bond required under this section and said Bond shall remain in full force and effect for a period of one year from the date of completion as specified in the Notice of Completion.

SECTION 2 - SCOPE OF THE WORK

2-2 PERMITS. - Amend the following:

Amend the first sentence of paragraph 1 as follows:
“The Contractor will obtain all permits necessary to perform the work in streets, highways, railways or other rights-of-way.”

Add the following sentence between the first and second sentences of paragraph 1:

For all work within Caltrans right-of-way, the Contractor shall obtain their own Caltrans Encroachment Permit and pay all necessary permit and inspection fees as required by Caltrans.

Redlans Regular Meeting of 09-05-2023
788 of 1115

GC 3

Add the following paragraph:

The Contractor shall, prior to the start of work, procure all permits and licenses, including but not limited to, a City Business License for itself, subcontractors, and all parties performing actions associated with this contract within the City of Redlands, City Truck Route Permit, City Street/Lane Closure Permit, City Encroachment Permit, USA Verification Number, DOSH Excavation Permit, other permits required by agencies and/or utilities having jurisdiction on the work, pay all charges and fees required by the City, other agencies and utilities, and give all notices necessary and incidental to the due and lawful prosecution of the work. All City permits associated with this project are no fee to the Contractor.

SECTION 3 - CONTROL OF THE WORK

3-7 CONTRACT DOCUMENTS.

3-7.1 General. – Add the following paragraphs:

Contractor’s working drawings or plans for any structure not included in the plans shall be approved by the Engineer before any work is performed. It is mutually agreed that approval by the Engineer of the Contractor’s working plans does not relieve the Contractor of any responsibility for accuracy of dimensions and details, and that the Contractor shall be responsible for agreement and conformity of their working plans with the approved plans and specifications.

Finished surfaces in all cases shall conform with the lines, grades, cross sections, and dimensions shown on the approved plans. Deviations from the approved plans will be determined by the Engineer and approved in writing. In the event of a discrepancy between any drawing and the figures written thereon, the figures shall be taken as correct.

Should it appear that the work to be done or any matter thereto is not sufficiently detailed or explained by the plans and specification, the Contractor shall apply to the Engineer for such further explanation as may be necessary and shall conform to such explanation or interpretation as part of the Contract so far as may be consistent with the intent of the original plans and specifications.

3-7.1.1 Preconstruction Meeting. The Contractor to whom the contract is awarded, and all his major subcontractors, shall attend a pre-construction meeting. The time and location of said meeting will be set by the City. Contractor will be given adequate notice of such meeting. It shall be the Contractor's responsibility to notify his subcontractors of the time and location of the meeting. All submittals as required under the General Requirements shall be submitted by the Contractor at the time of the meeting.

The Contractor will be provided with an electronic (.PDF file) of the conformed plans and specifications for their use throughout the project. Contractor is responsible for all costs of reproduction.

Progress meetings will be scheduled by the City. The Contractor will be given at least five working days notice of the time and location of said meetings. The Contractor has the responsibility of notifying his subcontractors, suppliers, and fabricators of the time and location of said meetings.

Meetings will be held either at the job site, at the offices of the City of Redlands, or at any other Redlans Regular Meeting of 09-05-2023
789 of 1115

GC 4

location approved by the City. The Contractor may request, in writing, that a meeting be held.

The City will schedule a meeting at the Contractor’s request not more than five working days after receiving said written notice.

3-7.2 Precedence of Contract Documents. – Replace paragraph 2 with the following:

The precedence shall be (A. being highest, O. being lowest):

A. Permits from other Agencies as may be required by law.

B. Change Orders.

C. Contract.

D. Addenda.

E. Bid Schedule/Proposal.

F. General Requirements.

G. Technical Specifications.

H. Plans.

I. MUED General Permit Conditions and Trench Specifications.

J. City of Redlands Water & Sewer Systems Standard Specifications.

K. General Conditions.

L. City of Redlands Standard Specifications and Detail Drawings for Design and Construction of Public Improvements and all Supplements
M. Standard Specifications for Public Works Construction (SSPWC), 2021 Edition N. Standard Plans for Public Works Construction, 2021 Edition O. Reference Specifications.

P. Caltrans Standard Specifications, 2018 Edition
Q. Caltrans Standard Plans, 2018 Edition

3-8.7 Record Drawings. The Contractor shall maintain at the job site, a set of record drawings for the work showing: exact location information of all existing underground utilities encountered, final locations determined in the field, any deviations from the plans and specifications and new work performed within the work area; and all differences between the work as drawn and as installed for all concealed work as well as work added which is not shown on the drawings. Concealed work shall mean all work installed underground or in an area which cannot be readily inspected by use of access panels, inspection plates or other removable features.

These record drawings shall be kept current and legible, and shall be available for inspection at all times by the Engineer, Architect and Contractor. All information, changes in the work or work added on these record drawings shall be marked in red. All markings shall use the same legends that are used on the drawings. Indicate locations by exact dimensions and elevations. Give dimensions and elevations from a permanent reference point and prepare all changes to scale.

At the end of construction, the contractor shall prepare one set of marked-up prints of the record drawings indicating any and all revisions and changes to the drawings reflecting As-Built conditions.

The drawings shall also contain a listing of all subcontractors who worked on the construction project.

The As-Built drawings will be submitted to the Municipal Utilities and Engineering Department for review and approval by the City Inspector and Engineer.

Redlans Regular Meeting of 09-05-2023
790 of 1115

GC 5

The design engineer or City staff shall prepare the final As-Built drawings for record purposes in one of the following two ways: (1) Check out the original drawings from the City and manually revise the drawings to reflect the As-Built condition; or (2) Re-plot the original drawings electronically on 4 mil mylars and make revisions electronically to reflect the As-Built conditions. The final As-Built drawings will be reviewed and approved by the City Inspector and Engineer

The construction related bonds will not be released by the City until the As-Built drawings are accepted by the Engineer and all City stipulated conditions for the release of the bonds have been satisfied.

3-12 WORKSITE MAINTENANCE

3-12.4 Storage of Equipment and Materials.

The Contractor shall be required to provide and maintain as necessary, any additional property required for storage of equipment, materials, etc., to perform work on this project. Should the additional property be located within the city limits of the City of Redlands, the Contractor shall obtain written approval from the City of Redlands Development Services Department and comply with all conditions set therein prior to use. When private property is used for a yard area, the Contractor shall also secure written authorization from the private property owner and supply a copy of such to the City before any monthly progress payment is submitted.

The Contractor shall ensure the construction yard adheres to all local, State and Federal regulations, ordinances, codes and maintained in a neat and orderly manner throughout the duration of the project.

The contractor shall include the construction yard in the Erosion Control Plan or SWPPP and shall be inspected and approved prior to use of the yard. If at any time during the project the location of the construction yard changes from the approved site, the City shall be notified prior to relocation for inspection and approval. Should the Contractor fail to comply with these conditions, the Engineer may suspend the work per SSPWC section 6-6 until the condition is corrected.

At the end of the project or as required, the Contractor shall: clean up and remove all trash and debris, including all organic trash and debris; clean up and remove all hazardous and biochemical wastes from the property to the satisfaction of the agency (City, County, State, or Federal) charged with overseeing these items; and provide to the City a written release from the private property owner that they are satisfied with all clean up and removal work.

5-9.1 Storage in Public Streets.

Construction materials and equipment shall not be stored within public streets or right of way without prior approval from the City. In order to seek approval, Contractor shall submit a location map with all equipment or materials identified including size, duration and any BMP’s installed and provide at least 7 days for review by the City.

3-13 COMPLETION, ACCEPTANCE, AND WARRANTY.

3-13.2 Acceptance. - Add the following paragraphs:

Redlans Regular Meeting of 09-05-2023
791 of 1115

GC 6

The Contractor shall submit written assertion that the work has been completed prior to the Engineer making final inspection. The Engineer will have 48 hours to inspect the work. If the Engineer determines that the work is not complete, written notice will be given.

Until final acceptance of work by the Engineer, the Contractor shall have charge and care thereof from damage caused by the action of the elements or from any other cause, whether arising from the execution or from the non-execution of the work. The Contractor shall rebuild, repair, restore, and make good all injuries or damage to any portion of the work occasioned by any of the above causes before final acceptance and shall bear the expense thereof.

All work which has been rejected shall be remedied or removed and replaced by the Contractor at their expense with work conforming to the plans and specifications. Any defective material or workmanship which may be discovered before final acceptance or within one year from the date of final acceptance shall be immediately corrected by the Contractor at their expense, notwithstanding that it may have been overlooked in previous inspections and estimates. Failure to inspect work at any stage shall not relieve the Contractor from any obligation to perform sound and reliable work as herein described. It is the Contractor’s ultimate responsibility to deliver a complete, operational project that complies in all details with these specifications, at the time of final acceptance.

Any omission or failure on the part of the City to discover or notify the Contractor of or to condemn defective work or material at the time of construction shall not be deemed as acceptance, and the Contractor will be required to correct defective work or material prior to final acceptance.

The City will endeavor to locate any errors or defective materials or workmanship and call them to the attention of the Contractor prior to subsequent work being performed. However, the City is under no obligation to do so and shall not be held liable because errors or defective material or workmanship by the Contractor are not discovered prior to subsequent work.

Nothing in this section shall be construed to limit the rights of the City to immediately correct conditions which are unsafe or which pose a public health nuisance. Should said corrections later be found to be caused by defective material and/or workmanship, the Contractor and their surety shall reimburse the City for costs reasonably incurred while attending the situation.

In the event it is necessary for the City to file suit to enforce any liability of the Contractor pursuant to this Section, the City shall be entitled to recover from the Contractor, in addition to all other amounts found due and owing, costs of suit and reasonable expenses and fees including reasonable attorneys’ fees incurred by the City in successfully enforcing the Contractor’s obligation, all to be taxed as costs and included in any judgment rendered.

3-13.3 Warranty. - Amend the following:

Amend the first sentence of the paragraph 3:
“The warranty period for specific items covered under manufacturers’ or suppliers’ warranties shall commence from the date of the final acceptance, except where longer warranty periods are specified.”

Add the following paragraphs:

Redlans Regular Meeting of 09-05-2023
792 of 1115

GC 7

All start-up and testing shall be complete, approved and accepted before final acceptance, substantial completion, or beneficial occupancy.

The warranty provided herein shall not be in lieu of, but shall be in addition to any warranties or other obligations otherwise imposed by the specifications or by law. The remedies provided herein shall not be exclusive and the City shall be entitled to any and all remedies provided by law.

3-13.3.1 Warranty of Work. The Contractor shall guarantee the Work against defective materials or workmanship for a period of (1) year from the date of completion date specified in the Notice of Completion, except where longer warranty periods are specifically stated. As specified in Section 2- 4 in the GENERAL CONDITIONS, the Performance Bond shall remain in full force and effect during the warranty period.

All work which has been rejected, shall be remedied, or removed and replaced, by the Contractor at his own expense, with work conforming to the Plans and Specifications. Any defective material or workmanship which may be discovered before final acceptance or within (1) one year from the completion date specified in the Notice of Completion shall be corrected immediately by the Contractor at his own expense notwithstanding that it may have been overlooked in previous inspections and estimates. Failure to inspect work at any stage shall not relieve the Contractor from any obligation to perform sound and reliable work as herein described. It is the Contractor's ultimate responsibility to deliver at the time of final acceptance a complete project that complies in all details with these Contract Documents. All items shall be ready to operate.

Any omission or failure on the part of the Owner to discover or notify the Contractor of or to condemn defective work or material at the time of construction shall not be deemed an acceptance, and the Contractor will be required to correct defective work or material prior to final acceptance.

The Owner will endeavor to locate any errors or defective materials or workmanship and call them to the attention of the Contractor prior to subsequent work being performed. However, the Owner is under no obligation to do so and shall not be held liable because errors or defective material or workmanship by the Contractor are not discovered prior to subsequent work.

During the (1) one year warranty period, should the Contractor fail to remedy defective material and/or workmanship, or to make replacements within five (5) days after written notice by the Owner, it is agreed that the Owner may make such repairs and replacement and the actual cost of the required labor and materials shall be chargeable to and payable by the Contractor or his Surety.

Nothing in this section shall be construed to limit the rights of the Owner to immediately correct conditions which may be unsafe or which may pose a public health nuisance. Should said conditions later be found to be caused by defective material and/or workmanship, the Contractor and his Surety shall reimburse the Owner for costs reasonably incurred while attending the situation.

In the event it is necessary for the Owner to file suit to enforce any liability of the Contractor pursuant to this sections WARRANTY OF WORK, the Owner shall be entitled to recover from the Contractor, in addition to all other amounts found due and owing, costs of suit and reasonable expenses and fees, Redlans Regular Meeting of 09-05-2023
793 of 1115

GC 8

including reasonable attorneys' fees, incurred by the Owner in successfully enforcing the Contractor's obligations, all to be taxed as costs and included in any judgment rendered.

The warranty provided herein shall not be in lieu of, but shall be in addition to any warranties or other obligations otherwise imposed by the Contract Document or by law. The remedies provided herein shall not be exclusive and the Owner shall be entitled to any and all remedies provided by law.

SECTION 4 - CONTROL OF MATERIALS

4-1 GENERAL. - Delete and replace with the following:

Should any work performed or material furnished under the Contract prove defective or not in accordance with the Plans and Specifications and in the opinion of the Engineer such defect is not of sufficient magnitude or importance to make the work dangerous or unusable, or if the removal of such work is impracticable or will create dangerous or undesirable conditions, the Engineer at his discretion shall have the right and authority to retain such work instead of requiring it to be removed and reconstructed, but he shall make such deductions therefore in the payment due the Contractor as may be just and reasonable.

4-1.1 Warranty of Title. No materials, supplies or equipment for the work under this Contract shall be purchased subject to any chattel mortgage or under a conditional sale contract or other agreement by which an interest therein or any part thereof is retained by the seller or supplier. The Contractor warrants clear and good title to all materials supplied and equipment installed and incorporated in the work and agrees, upon completion of all work, to deliver the premises, together with all improvements and appurtenances constructed or placed thereon by him, to the Owner free from any claims, liens, encumbrances or charges, and further agrees that neither he nor any person, firm, or corporation furnishing any material or labor for work covered by the Contract shall have any right to a lien upon the premises or any improvement or appurtenance thereon, provided that this shall not preclude the Contractor from installing metering devices or other equipment of utility companies the title of which is commonly retained by the utility company. Nothing contained in this article, however, shall defeat or impair the right of such persons furnishing materials or labor under any bond given by the Contractor for their protection, or any right under any law permitting such persons to look to funds due the Contractor, which are in the hands of the Owner.

4-1.2 Clayton Act. In submitting a bid to the City, if the bid is accepted the Contractor agrees it will assign to the City all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C.

Section 15) or under the Cartwright Act (chapter 2 [commencing with Section 16700] of Part 2 Division 7 of the Business and Professionals Code), arising from purchases of goods, materials, or services by the Bidder for sale to the City pursuant to the bid. Such assignment shall be made and become effective at the time the City tenders final payment to the Bidder.

4-3 INSPECTION. - Add the following paragraphs:

“The Contractor shall notify the Engineer at least 24 hours in advance before inspection is required.”

Redlans Regular Meeting of 09-05-2023
794 of 1115

GC 9

Whenever the Contractor varies the period during which work is carried on each day, due notice shall be given to the Engineer so that proper inspection may be provided. Varied working hours may be allowed only upon written authorization from the Engineer.

Work financed in whole or in part with funds from another public entity or performed within the jurisdiction of another public entity shall be subject to inspection at all times by authorized representatives of that entity.

The work shall be ready for inspection, whether by City, other public entities or independent testing laboratories, at the scheduled times arranged by the Contractor. If, in the City’s sole judgment, the work is not ready and the inspection must be rescheduled, the Contractor shall be notified. The Contractor shall reschedule the inspection and provide the proper 24 hour notification for the rescheduled inspection. Any costs incurred by the City for rescheduled inspections shall be reimbursed prior to the release of Bonds.

In order to allow for inspection, the Contractor shall notify the City’s inspector sufficiently in advance of the permanent concealment of any materials or work. The City’s inspector shall make the appropriate notifications to other public entities and independent testing laboratories for inspections.

All inspections required in the specifications for this project shall be coordinated through the City’s inspector.

If any work is concealed or performed without the prior notice specified, the work shall be subject to such tests or exposure as may be necessary to prove to the City, Architect and Engineer, that the materials used and the work performed are in conformity with the drawings and specifications. All labor, tools, materials and equipment necessary for exposing and testing shall be furnished by the Contractor at their expense. The Contractor shall replace at their expense, any materials or work damaged by exposure or testing.

Overtime inspection may be requested by the Contractor. Overtime inspection includes but is not limited to, any hours worked outside of the inspector’s normal working hours including weekends and holidays. Such requests shall be on a case-by-case basis as determined by the Engineer. If the Engineer so determines and approves, overtime inspection shall be paid for by the Contractor at the current City billing rate at the time of request or as billed by other public entities or independent testing laboratories. Any costs incurred by the City for overtime inspection shall be reimbursed prior to the release of Bonds.

SECTION 5 – LEGAL RELATIONS AND RESPONSIBILITES

5-1.1 CONTRACTOR’S EQUIPMENT AND FACILITIES.

A noise level limit of 86 dbA at a distance of 15 m (50 feet) shall apply to all construction equipment on or related to the work whether owned by the Contractor or not. The use of excessively loud warning signals shall be avoided, except in those cases required for the protection of personnel.

5-1.2 General.

Redlans Regular Meeting of 09-05-2023
795 of 1115

GC 10

The enclosed toilets required by this section shall be located within an approved yard, if one is acquired by the Contractor. If a yard is not acquired by the Contractor or the project is not within a City owned property, the toilets must be installed on a trailer and removed from the jobsite each day.

At no times shall toilets be stored within the public right of way outside of working hours.

5-3 LABOR. - Amend the following:

5-3.1 General. - Add the following paragraphs:

Employment of apprentices are required on projects of $30,000 or more. Provisions in Sections 1777.5 of the California Labor Code fixes responsibility of compliance with that section for all apprenticeable occupations with the Contractor. Section 1777.5 provides that the Contractor and every Subcontractor shall submit contract award information to the applicable joint apprenticeship committee. One apprentice hour for every five journeymen hours worked is the minimum State requirement applicable to each apprenticeable trade. Section 1777.7 of said Labor Code provides that the Contractor shall forfeit as a civil penalty the sum of one hundred dollars ($100.00) for each calendar day of noncompliance with provision of said Section 1777.5.

The Contractor will observe all applicable health and safety requirements, including, but not limited to the California and Federal Occupational Safety and Health Acts. The Contractor shall submit for review by the City a Site Specific Health and Safety Plan prior to the commencement of construction activities. This Plan shall meet or exceed the requirements of 29 CFR 1910.120.

5-3.2 Prevailing Wages. - Add the following paragraphs:

Contractors are hereby notified that pursuant to Section 1770 of the Labor Code of the State of California, the City Council of the City of Redlands, California, by Resolution No. 2326, has ascertained the general prevailing rate of hourly wages and rates for legal holidays and overtime work in the locality where this work is to be performed, for each craft or type of workman or mechanic needed to execute the Contract which will be awarded to the successful Bidder. The Contractor shall comply with Sections 1770 to 1780 inclusive of the Labor Code and Master Labor Agreement of Southern California.

The Contractor and each of his subcontractors shall pay each of his employees engaged in work on the project under this Contract in full less legally required deductions and also deductions made pursuant to the regulations prescribed under the so-called “Kick- Back Statute” (48 Sta. 948; U.S.C. 875; 40 U.S.C. 276c).

In accordance with Section 1775 of the California Labor code, Contractor shall forfeit to City, as a penalty, a minimum of $40 for each day, or portion thereof, and a maximum of $200 for each day, or portion thereof, for each worker paid, either by Contractor, or any subcontractor, less than the prevailing rates as determined by the Director of the California Department of Industrial Relations for the work.

Contractor further agrees to fully comply with all applicable provisions of the California Labor Code including but not limited to Sections 1771, 1775, 1776, 1777.5, 1813 and 1815. Failure to abide by prevailing wages and laws by Contractor will be enforced.

Redlans Regular Meeting of 09-05-2023
796 of 1115

GC 11

The Contractor or subcontractor shall, as a penalty, to the State or political subdivision on whose behalf the contract is made or awarded forfeit twenty-five ($25) dollars for each worker employed in the execution of the contract by the respective contractor or subcontractor for each calendar day during which the worker is required or permitted to work more than 8 hours in any calendar day and 40 hours in any calendar work in violation of Labor Code section 1813.

Attention is also directed to the Federal minimum wage rate requirements. If there is a difference between the minimum wage rates predetermined by the Secretary of Labor and the general prevailing wage rates determined by the Director of the California Department of Industrial Relations for similar classifications of labor, the Contractor and subcontractors shall pay not less than the higher wage rate. This includes “helper” (or other classifications based on hours of experience) or any other classification not appearing in the Federal wage determinations. Where Federal wage determinations do not contain the State wage rate determination otherwise available for use by the Contractor and subcontractors, the Contractor and subcontractors shall pay not less than the Federal minimum wage rate which most closely approximates the duties of the employee in question.

5-3.3 Payroll Records. – Delete and replace with the following:

The contractor and subcontractors shall submit electronic certified payroll on a weekly basis to the City of Redlands through LCPtracker. LCPtracker is a web-based labor compliance management system. The Prime Contractor and Subcontractors and lower-tier Subcontractors will receive an email from LCPtracker providing their log-on identification and temporary password. The Contractors will need to follow the instructions in the email to set-up their permanent password and activate their account. Once their account is setup, LCPtracker Inc. provides either computer based or web based training. Training can be accessed via the “Book Now” button located under the “Projects” tab. The prime contractor shall submit their certified payroll, along with any subcontractor who is performing any labor, on a weekly basis. The prime contractor is responsible for all communication with their subcontractors and shall submit their subcontractor’s certified payroll as part of their weekly payroll packet. All labor compliance correspondence and submissions will be made through the LCPtracker software.

All certified payroll shall be submitted no later than 7 days from the close of the pay period. The payroll records shall set out accurately and completely the name, social security number, classification and hourly wage rate of each employee, hours worked by employee during the payroll period and a full weekly wages and the actual weekly wages paid to the employee. Such certified payroll records shall be made available at all time for inspection by the City, the Department of Industrial Relations, the Department of Labor or authorized representatives within ten days of request. The contractor and subcontractor shall preserve weekly payroll records for a period of three (3) years from the date of completion of the Contract. In case on noncompliance with said Section 1776 and after a ten-day period following receipt of written notice, the Contractor shall forfeit to the California Department of Industrial Relations one hundred dollars ($100.00) for each calendar day or portion thereof, for each worker in non-compliance, until compliance is effectuated.

In order to meet labor compliance requirements, all contractors will be required to complete eDocuments which are accessed, submitted and approved through LCPtracker. All eDocuments are required to be signed by an owner/officer or authorized signer. The Prime Contractor and each Redlans Regular Meeting of 09-05-2023
797 of 1115

GC 12

Subcontractor and every lower-tier Subcontractor and any Vendors subject to this provision shall comply with Title 8, Section 16404 of the California Code of Regulations.

A Fringe Benefit Statement shall be submitted with the first payroll and is required for both the prime contractor and any subcontractors. A new Fringe Benefit Statement will be required when general determinations are issued in February and August. Please refer to the DIR website for additional details. Any weeks where no work was performed must be represented by the submittal of a Statement of Non-Performance covering the 7 day pay period where no hours were worked on the site. Final payroll on the project should state “Final” on the certified payroll, and must be marked as such in the LCPtracker system.

Failure by the Contractor to comply with the aforementioned requirements shall result in withheld progress payments until such time certified payroll documents have been received, reviewed, and accepted by the City. The City reserves the right to seek assistance from the State Department of Industrial Relations in determining the acceptability of certified payroll submittals before release of withheld progress payments. Prior to the release of retention monies, all certified payroll must be submitted on the project and any outstanding issues that may have occurred throughout the project must be resolved.

5-4 INSURANCE. - Delete Section 5-4.1, Section 5-4.2 and replace with the following:

Before entering into a Contract, the Bidder to whom the Contract has been awarded shall furnish satisfactory evidence that they have secured all required insurance from a responsible insurance company authorized to do business in California and satisfactory to the City, and such insurance shall be maintained in full force and effect at the Contractor's own expense during the life of the Contract.

Contractor shall furnish the City with the customary Certificates of Insurance for all required insurance listed below. General Liability Insurance shall name the City and the Consultant, as an additional insured and shall be primary and non-contributing to any insurance or self-insurance maintained by the City. All liability insurance policies shall bear an endorsement or shall have attached a rider whereby it is provided that, in the event of expiration or proposed cancellation of such policies for any reason whatsoever, the City shall be notified by registered mail, return receipt requested, giving sufficient time before the date thereof to comply with any applicable law or statute, but in no event less than forty five (45) days before expiration or cancellation is effective.

The coverage shall provide the following minimum limits based on the type of work proposed under this Contract. The Contractor shall determine if the proposed work requires Tier 1 or Tier 2 Designated Insurance Requirements shown below.

Redlans Regular Meeting of 09-05-2023
798 of 1115

GC 13

TIER 1 DESIGNATED INSURANCE REQUIREMENTS
a. Commercial General Liability
 $1 Million Per Occurrence/ $2 Million Aggregate
 City listed as an Additional Insured on the coverage
 Coverage is primary and non-contributory
 If scope of work is within 50 feet of any railroad, endorsement citing inclusion of liability associated with this work is required
 If any policy forms of endorsements are cited to grant extension of coverage, they must be included with the Certificate of Insurance submission

b. Business Auto Liability
 $1 Million Combined Single Limit
 City listed as an Additional Insured on the coverage
 Must include liability arising from all owned, leased, hired, and non-owned autos  If any policy forms of endorsements are cited to grant extension of coverage, they must be included with the Certificate of Insurance submission  If Contractor or its subcontractors or suppliers haul hazardous material (including, without limitation, waste), Auto Liability insurance must be applicable to all hazardous waste hauling vehicles, and include MCS 90 and CA9948 Endorsements.

c. Commercial Umbrella/ Excess Liability
 $5 Million Per Occurrence/ Aggregate
 City listed as an Additional Insured on the coverage
 Coverage is primary and non-contributory
CONTRACTED OPERATIONS DESIGNATED AS TIER 1
Air Conditioning (HVAC)
Systems (installation)
Electric Light or Power Line
Construction Pipeline Construction
Airport Runways (paving,
repaving, etc.) Elevator Work Roofing
Blasting Operations Excavation Sandblasting
Bridge or Elevated Highway
Construction
Fire Suppression Systems
(installation)
Sewer and Water Main
Construction
Buildings Structural Work
(including elevators)
Gas Mains or Connections
Construction Sign Erection (streets)
Building Structure (raising or
moving) Geophysical Exploration Solar Energy
Cable Installation in Conduits and
Conduit Construction (streets) Grading of Land Street Cleaning Caisson or Cofferdam Work Hazardous Materials Contractors Street or Road Construction Dam or Reservoir Construction Irrigation or Drainage
Construction
Tank Construction, Installation,
Erection or Repair
Demolition (structures) Landscape Construction (street or street medians)
Telephone or Cable Line
Construction
Drilling Painting (exterior greater than
single story)
Tree Pruning, Dusting, Spraying
or Removal
Redlans Regular Meeting of 09-05-2023
799 of 1115

GC 14

 If any policy forms of endorsements are cited to grant extension of coverage, they must be included with the Certificate of Insurance submission

d. Workers Compensation
 $1 Million Per Occurrence for Bodily Injury by Accident  $1 Million Each Employee for Bodily Injury by Disease  $1 Million Policy Limit for Bodily Injury by Accident  Waiver of Subrogation in favor of City
 If any policy forms of endorsements are cited to grant extension of coverage, they must be included with the Certificate of Insurance submission

e. Pollution Policy (Hazardous Materials) [If Applicable]  Required of Projects that involve Demolition and/or Excavation Activities  $1 Million Per Occurrence/ $2 Million Aggregate
 City listed as an Additional Insured on the coverage

TIER 2 DESIGNATED INSURANCE REQUIREMENTS
a. Commercial General Liability
 $1 Million Per Occurrence/ $2 Million Aggregate
 City listed as an Additional Insured on the coverage
 Coverage is primary and non-contributory
 If scope of work is within 50 feet of any railroad, endorsement citing inclusion of liability associated with this work is required
 If any policy forms of endorsements are cited to grant extension of coverage, they must be included with the Certificate of Insurance submission

b. Business Auto Liability
 $1 Million Combined Single Limit
 City listed as an Additional Insured on the coverage
 Must include liability arising from all owned, leased, hired, and non-owned autos  If any policy forms of endorsements are cited to grant extension of coverage, they must be included with the Certificate of Insurance submission CONTRACTED OPERATIONS DESIGNATED AS TIER 2
Air Conditioning (HVAC) Systems
(service and repair) Carpentry (building interiors) Fire Suppression Systems (service and repair)
Alarms and Alarm Systems Communications Equipment
Installation (interior) Landscape Construction
Building Interior Work (service,
repair and non-structural
remodeling)
Driveway, Parking Area or
Sidewalk (paving or repaving) Painting (exterior)
Cable Installation in Conduits
(buildings) Fence Erection All Other Job Types including Vendors
Redlans Regular Meeting of 09-05-2023
800 of 1115

GC 15

 If Contractor or its subcontractors or suppliers haul hazardous material (including, without limitation, waste), Auto Liability insurance must be applicable to all hazardous waste hauling vehicles, and include MCS 90 and CA9948 Endorsements.

c. Workers Compensation
 $1 Million Per Occurrence for Bodily Injury by Accident  $1 Million Each Employee for Bodily Injury by Disease  $1 Million Policy Limit for Bodily Injury by Accident  Waiver of Subrogation in favor of City
 If any policy forms of endorsements are cited to grant extension of coverage, they must be included with the Certificate of Insurance submission

d. Pollution Policy (Hazardous Materials) [If Applicable]  Required of Projects that involve Demolition and/or Excavation Activities  $1 Million Per Occurrence/ $2 Million Aggregate
 City listed as an Additional Insured on the coverage
Contractor expressly waives all rights to subrogation against the City, its officers, employees and volunteers for losses arising from work performed by Contractor for City by expressly waiving Contractor’s immunity for injuries to Contractor’s employees and agrees that the obligation to indemnify, defend and hold harmless provided for in this Agreement extend to any claim brought by or on behalf of any employee of Contractor. This waiver is mutually negotiated by the parties. This shall not apply to any damage resulting from the sole negligence of City, its agents and employees.

To the extent any of the damages referenced herein were caused by or resulted from the concurrent negligence of City, its agents or employees, the obligations provided herein to indemnify, defend and hold harmless are valid and enforceable only to the extent of the negligence of contractor, its officers, agents and employees.

Subcontractors. The prime contractor shall include all subcontractors as insureds under its policies or shall furnish separate certificates and endorsements from each subcontractor.

The Contractor shall not assign or sublet the contract, in whole or in part, without the written consent of the City, nor shall the contractor assign any monies due to, or to become due to, Contractor hereunder without prior written consent of the City.

The Contractor shall be fully responsible to the City for the acts and omissions of the subcontractor and persons either directly or indirectly employed by the Contractor. Consent to subcontracting part of the work shall, in no way, release the Contractor from responsibility for performance of the work, and Contractor will be held, in all respects, accountable for the same as if no consent had been given.

The Contractor shall give personal attention to this work which is sublet. Nothing contained in the contract documents shall create any contractual relation between any subcontractor and the City.

Hold Harmless and Indemnification. Contractor shall indemnify, hold harmless and defend City and its elected officials, agents and employees and the Consultant from and against any and all claims, losses or liability, including attorney’s fees, arising from injury or death to persons or damage to property occasioned by any act, omission or failure to act of Contractor, its subcontractors, and any Redlans Regular Meeting of 09-05-2023
801 of 1115

GC 16

officers, agents and employees in performing the work required by this Agreement. Contractor’s obligations under this provision shall not be limited in any way by any terms of this Agreement, or the insurance limits.

5-4.3 Worker’s Compensation Insurance. - Delete and replace with the following:

A. Contractor shall have worker’s compensation and employer’s liability insurance in force throughout the duration of the contract in an amount which meets the statutory requirement with an insurance carrier acceptable to the City. The insurance policy shall include a provision prohibiting cancellation of said policy except upon forty-five (45) days prior written notice to City. Certificates of Insurance shall be delivered to the City at the time of the Contractors’ execution of the agreement.

B. Contractor expressly waives all rights to subrogation against the City, its officers, employees and volunteers for losses arising from work performed by Contractor for City by expressly waiving Contractor’s immunity for injuries to Contractor’s employees and agrees that the obligation to indemnify, defend and hold harmless provided for in this Agreement extend to any claim brought by or on behalf of any employee of Contractor. This waiver is mutually negotiated by the parties. This shall not apply to any damage resulting from the sole negligence of City, its agents and employees. To the extent any of the damages referenced herein were caused by or resulted from the concurrent negligence of City, its agents or employees, the obligations provided herein to indemnify, defend and hold harmless are valid and enforceable only to the extent of the negligence of contractor, its officers, agents and employees.

5-6 PATENT FEES OR ROYALTIES. Delete and replace with the following:

The Contractor shall include in its Bid the patent fees or royalties on any patented article or process which may be furnished or used in the Work. The Contractor shall indemnify and hold the City harmless from any legal action that may be brought for infringement of patents. The Contractor’s attention is directed to “Notice of Patents, Data, and Copyright Regulations” of the Federal Labor Standards.

The Contractor shall bear all costs arising from the use of patented goods and/or processes used on and/or incorporated into the Work. When use of these goods and/or processes is judged to be an infringement and the use is banned, the Contractor, at its own expense, shall, with concurrence of the Engineer, do one of the following:

A. Secure for the City the right to continue using goods and/or processes by suspension of the injunction or by procuring a license(s);

B. Replace said goods and/or processes with non-infringing goods and/or processes;

C. Modify said goods and/or processes so that they become non-infringing; or

D. Remove said goods and/or processes and refund the sum paid therefore without prejudice to any other rights of the City.

Redlans Regular Meeting of 09-05-2023
802 of 1115

GC 17

The preceding shall not apply to any goods manufactured to the detailed design of the City contained in the Contract Documents.

5-7 SAFETY.

5-7.1 Work Site Safety.

5-7.1.1 General. - Amend the following:

Add the following sentences to paragraph 1:

Should watering be the sole method utilized for roadway dust abatement purposes, the maximum time interval that shall elapse between applications thereof shall be no greater than 3 hours during normal working day, supplemented by an additional application thereof immediately prior to the conclusion of the workday and at such other times as may be required, including evenings, weekends and holidays as required by the Engineer. Should the Contractor be unable to furnish dust abatement as specified, the City may perform or cause to be performed the necessary service, the expense of which will be deducted from the payment due the Contractor.

Add the following paragraphs:

To insure the protection of storm drain inlets, Best Management Practices (BMPs) shall be employed during cleanup and dust control operations. Refer to Section 3-12.6.

Compliance with this section is of extreme importance to the City and its citizens. The City may fine the Contractor $1,000 per incident if there are issues with dust, mud, unused equipment or materials and rubbish within the construction area that result in citizen complaints. A 24 hour notice shall be issued to the Contractor and failure to correct the problems will result in the fine being levied. This fine will be in addition to those fines potentially charged for NPDES violations.

5-8 AIR POLLUTION CONTROL.

Dust control shall be performed in accordance with Subsection 7-8 of the Standard Specifications, South Coast Air Quality Management District (SCAQMD) Rule 403, the general Provisions and the following Provision.

Dust resulting from the Contractor’s performance of the work, either inside or outside, the right-of- way shall be controlled by the Contractor. Dust control includes the action necessary to prevent, reduce or control dust within the work area as required to complete the work. The Contractor shall carry out proper and efficient measures to prevent his operations from producing dust in amounts damaging to property or causing a nuisance, or harm to persons living nearby or occupying buildings in the vicinity of the work. The Contractor shall control dust 24 hours a day, seven days a week. The methods to be used for controlling dust in the construction area and along haul roads shall be approved by the Engineer prior to starting any work. The Rule 403 Implementation Handbook published by the SCAQMD, contains a detailed listing of reasonably available dust control measures.

Dust control ordered by the Engineer to be applied on Saturdays, Sundays or holidays will be included in the Contract price for dust control and no additional compensation will be allowed therefore.

Redlans Regular Meeting of 09-05-2023
803 of 1115

GC 18

The full compensation for all direct and indirect costs incurred for work performed or materials used to control dust resulting from the Contractor’s performance of the work and caused by public traffic, either inside or outside the right-of-way shall be considered as included in the Contract prices paid for the various items of work involved and no additional compensation will be allowed therefore.

5-9 STORAGE OF EQUIPMENT AND MATERIALS.

The Contractor shall be required to provide and maintain as necessary, any additional property required for storage of equipment, materials, etc., to perform work on this project. Should the additional property be located within the city limits of the City of Redlands, the Contractor shall obtain written approval from the City of Redlands Development Services Department and comply with all conditions set therein prior to use. When private property is used for a yard area, the Contractor shall also secure written authorization from the private property owner and supply a copy of such to the City before any monthly progress payment is submitted.

The Contractor shall ensure the construction yard adheres to all local, State and Federal regulations, ordinances, codes and maintained in a neat and orderly manner throughout the duration of the project.

The contractor shall include the construction yard in the Erosion Control Plan or SWPPP and shall be inspected and approved prior to use of the yard. If at any time during the project the location of the construction yard changes from the approved site, the City shall be notified prior to relocation for inspection and approval. Should the Contractor fail to comply with these conditions, the Engineer may suspend the work per SSPWC section 6-3 until the condition is corrected.

At the end of the project or as required, the Contractor shall: clean up and remove all trash and debris, including all organic trash and debris; clean up and remove all hazardous and biochemical wastes from the property to the satisfaction of the agency (City, County, State, or Federal) charged with overseeing these items; and provide to the City a written release from the private property owner that they are satisfied with all clean up and removal work.

5-9.1 Storage in Public Streets.

Construction materials and equipment shall not be stored within public streets or right of way without prior approval from the City. In order to seek approval, Contractor shall submit a location map with all equipment or materials identified including size, duration and any BMP’s installed and provide at least 7 days for review by the City.

5-10 WATER POLLUTION CONTROL.

The Contractor shall follow the City's guidelines for Storm Water Pollution Prevention in providing storm water pollution control at the project site, including the implementation of approved Erosion/Sediment Control Plans during construction as well as the implementation of approved Water Quality Management Plans.

Construction activities disturbing 1 acre or more of land shall comply with the State Water Resources Control Board’s NPDES General Construction Storm Water Permit. A copy of the Notice of Intent (NOI) to include the Waste Discharge Identification (WDID) number shall be submitted as part of Redlans Regular Meeting of 09-05-2023
804 of 1115

GC 19

the Storm Water Pollution Prevention Plan (SWPPP) to the Engineer for review. Call (909) 782- 4130 for NOI/WDID information.

All projects requiring grading shall submit to the City for review and approval an Erosion/Sediment Control Plan and a Grading Plan. Permit(s) will not be issued until plans are approved and may be revoked if work required in these specifications are not complied with.

Construction sites shall be maintained by implementation of BMPs in such manner that pollutants are not discharged from the site to the maximum extent practicable. A few references available to help with selection and implementation of applicable BMPs are:

1. California Storm Water Best Management Practice Handbook, American Public Works Association, March 1993;

2. The Construction Site Best Management Practices Manual, November 2000;

3. Storm Water Pollution Prevention Plan and Water Pollution Control Program Preparation Manual, November 2000;

4. California Regional Water Quality Control Board’s San Francisco Bay Region, Guidelines for Construction Projects; and

5. California Regional Water Quality Control Board’s San Francisco Bay Region, Erosion and Sediment Control Field Manual, July 1999.

All discharges into the storm drain system are prohibited except for potable water, properly treated discharge, and those discharges specifically approved by the Engineer. The following are some of the prohibited discharges:

1. Discharges that could have an impact on human health or the environment, cause or threaten to cause pollution, contamination, or nuisance;

2. Discharges that exceed any applicable water quality standard contained in a statewide Water Quality Control Plan or local Basin Plan; and

3. Discharges containing hazardous substances equal to or in excess of a reportable quantity listed in Federal regulations 40 CFR, Parts 117 and 302.

Materials that can cause or contribute to pollution or a violation of any applicable water quality standard include, but are not limited to: sediments; solid or liquid chemical spills; wastes from paints, stains, sealants, glues, limes, pesticides or herbicides and wood preservatives or solvents; asbestos fibers, paint flakes or stucco fragments; fuels, oils, lubricants or hydraulic, radiator and battery fluids; fertilizers; vehicle and equipment wash water or concrete wash water; concrete, detergent or floatable wastes; wastes from any engine and equipment steam cleaning or chemical degreasing; and chlorinated potable water line flushings.

Unless exempted or authorized by an NPDES permit, all non-storm water discharges require prior approval by the Engineer or the State Water Resources Control Board with Engineer approval.

During construction, temporary storage of such materials as identified above, must occur in a designated area physically separated from potential storm water runoff, with ultimate disposal in accordance with local, state and federal requirements.

Redlans Regular Meeting of 09-05-2023
805 of 1115

GC 20

De-watering of contaminated groundwater or discharging contaminated soils via surface erosion is prohibited.

Unless indicated otherwise by the Engineer, all projects, regardless of size, shall submit for review and approval, a Water Quality Management Plan (WQMP). The WQMP shall consist of post construction BMPs which shall remain in effect throughout the life of the facility. Refer to WQMP guidelines.

5-11 TEMPORARY LIGHTS, POWER AND WATER.

Any water drawn from a City fire hydrant shall be via a City owned water meter. Said meter may be obtained from the Municipal Utilities & Engineering Department. Contractor is responsible for payment of a $1200 deposit fee. Said meter shall be returned in a condition like received, less normal wear and tear. All meters are loaned subject to the conditions of the Fire Hydrant Construction Meter Water Service Application. Contractor must provide proposed location of meter and notify Customer Service at (909) 798-7516 each time the meter is relocated during construction. Water reasonably used in connection with the construction contract will be provided at no cost to the Contractor. Water use determined to be wasteful or unreasonable will be charged for at the prevailing rate.

5-12 PROTECTION AND RESTORATION OF EXISTING IMPROVEMENTS.

The Contractor shall relocate, re-establish, repair or replace all existing improvements within the work limits or right-of-way which are not designated for removal (e.g., sprinkler systems, curbs, sidewalks, driveways, fences, walls, signs, utility installations, pavement, structures, etc.) which are damaged or removed as a result of its operations.

Relocations, re-establishments, repairs and replacements shall be at least equal to existing improvements and shall match them in finish and dimension.

All costs to the Contractor for protecting, removing, restoring, relocating, repairing, replacing or re- establishing existing improvements shall be included in the Bid.

The Contractor shall be responsible for the maintenance of the streets and roadways to be used by public and local traffic through and adjacent to the construction zone, from the date of "Notice to Proceed" until the date of acceptance of the completed construction improvements.

Street maintenance shall include filling of potholes, grading of subgrade and base, replacing signs, installing interim pavement striping and markers on the project streets and other side streets within the construction zone. Street maintenance shall also include sweeping and washing of streets, adjacent and connected to the construction zone on a weekly, or more frequent schedule, to prevent the accumulation of dust, dirt, gravel or other deleterious materials, all as necessary to maintain the construction roadways and adjacent streets in a safe, clean and drivable condition for use by public and local traffic.

Redlans Regular Meeting of 09-05-2023
806 of 1115

GC 21

Upon request from the City for information pertaining to a claim against the contractor, contractor shall provide a written/email response, including all requested information, within 14 calendar days of City’s request. If a response with all requested information is not provided to the City within 14 calendar days, a penalty of $500 per calendar day will be assessed to the Contractor by the City.

5-13 PUBLIC CONVENIENCE AND SAFETY.

5-13.1 General.

The Contractor may be allowed to close the roadway, or a portion thereof, to traffic during normal work hours upon approval from the Engineer. During any closure, the Contractor shall allow access for residents, schools, trash service trucks, churches and businesses within the affected portion of roadway, except as required for construction for a reasonable period of time. The Contractor shall notify residents as noted within Section 7-19.

The Contractor shall provide and install barricades, delineators, warning devices and construction signs in accordance with the Work Area Traffic Control Handbook (WATCH) prepared by the Southern California Chapter of the American Public Works Association. During adverse weather or unusual traffic or working conditions additional devices shall be placed as directed by the engineer.

All traffic signs and devices shall conform to the current State of California, Department of Transportation (CALTRANS), "Manual of Warning Signs, Lights, and Devices for Use in Performance of Work upon Highways", unless otherwise approved by the Engineer.

Fences, barriers, lights and signs shall be furnished, erected and maintained as necessary to give an adequate warning to the public at all times that the work is under construction and of dangerous conditions to be encountered as a result thereof, and warning and directional signs shall also be erected and maintained as may be required by the City. Should the Contractor fail to furnish a sufficient number of traffic and/or pedestrian safety devices within three (3) hours after being notified, the Owner will place such necessary items and the Contractor shall be liable to the Owner for providing such devices in accordance with the following provisions:

1. For placing of barricades - $15.00 per barricade for each day or part thereof.

For flashers - $15.00 per flasher for each day or part thereof.

For traffic cones - $7.50 per cone for each day or part thereof.

2. In the event that the services of the Owner are required outside the normal working hours and/or days or items not noted above are furnished by the City, all costs incurred by the City shall be the responsibility of the Contractor.

The Contractor shall relocate, preserve and maintain the visibility of all signs within the project limits which affect the flow of traffic, as directed by the engineer. Any signs that are missing or found damaged shall be replaced immediately by the Contractor at his expense.

The Contractor shall provide and maintain Class II barricades along excavation edges parallel to the flow of traffic at a spacing of twenty-five feet (25'). Class II barricades mounted with flashers shall be installed around work areas in parkways. Class II barricades shall have alternating black and Redlans Regular Meeting of 09-05-2023
807 of 1115

GC 22

reflectorized white (or yellow) stripes at an angle of 45 degrees. The stripe with shall be four to six inches.

During paving operations barricades may be supplemented with minimum size eighteen-inch (18") high traffic cones and delineators such that spacing between barricades and/or cones or delineators is no greater than twenty-five feet (25"). At all access points such as intersecting streets, alleys and driveways, barricades and/or cones shall be provided at five-foot (5') intervals so as to prevent vehicular access to the paving area. Where access from an intersecting street is prohibited, a "Road Closed" sign shall be provided. "No Left Turn" sign shall be provided wherever required by the Engineer.

Clearances from traffic lanes shall be 5 feet to the edge of any excavation and 2 feet to the face of any curb, pole, barricade, delineator or other vertical obstruction.

A 4 foot wide pedestrian walkway shall be maintained in the parkway area on each side of all streets, unless otherwise authorized by the Engineer. The minimum clearance from: the edge of pedestrian walkways to any traffic lane shall be 5 feet; the edge of pedestrian walkways to any work zone shall be 3 feet; and the surface of pedestrian walkways to any overhead obstruction shall be 7 feet.

The Contractor shall, at the end of each work day, have backfilled, compacted and placed a temporary drivable roadway surface on all work areas within traveled roadways prior to leaving the job site.

Failure to comply to the satisfaction of the Engineer shall result in immediate correction by City forces, and all costs shall be borne by the Contractor.

Traffic control devices shall be marked with the Contractor’s name as appropriate. At no time shall any traffic control devices marked with companies or agencies other than the Contractor or subcontractors, be utilized within the work area.

All said traffic controls and safety devices shall be maintained in clean condition, with any and all graffiti removed by the end of workday on which the graffiti was first reported to the Contractor.

If the traffic control devices are deemed unacceptable by the Engineer due to being damaged, dirty, or marked incorrectly, the Contractor shall replace the traffic control devices immediately. Should the Contractor fail to furnish traffic control devices within three (3) hours after being notified, the Owner will place such necessary items and the Contractor shall be liable to the Owner for providing such devices in accordance with the provisions above.

5-13.1.1 Vehicular Access.

At such times as driveways are inaccessible due to the Contractor's work they shall be blocked by two (2) Class II barricades or one (1) Class II barricades and two (2) delineators. Driveways that are ramped or planked for temporary access shall be provided with a delineator at each side.

5-13.1.2 Signage. The Contractor shall furnish, erect and maintain all construction traffic signage as required and specified.

All construction traffic signage shall be in place prior to commencing any work, placed as needed during construction, moved as necessary and removed only upon completion of all work.

Redlans Regular Meeting of 09-05-2023
808 of 1115

GC 23

All construction traffic signage and controls shall comply with the State of California Manual of Traffic Controls, Warning Signs, Lights and Devices for use in Performance of Work Upon Highways. All construction traffic signage used in the performance of the work shall be a minimum of the encapsulated lens (high intensity) type. All traffic controls and safety devices, equipment and materials, including but not limited to cones, channelizers, delineators, flashing warning lights, barricades, high level warning devices, telescoping flag trees, flags, signs, markers, portable barriers, flashing arrow signs, changeable message signs, markings and flagging equipment shall be provided and maintained in like new condition.

When a Traffic Signal is constructed as a part of the project, the Contractor shall place and maintain for one calendar month, a message board for each approach leg to a new traffic signal. The message board shall read “CAUTION - NEW TRAFFIC SIGNAL”. The one month period shall begin from the day of activation. This requirement may be lessened or waived, on a case-by-case basis, by the Engineer.

The Contractor shall furnish and properly install, construct, erect, use and continuously inspect and maintain, twenty-four (24) hours per day, seven (7) days per week, including holidays, all said devices, equipment and materials and all temporary and permanent pedestrian and driving surfaces as necessary to provide for the safety and convenience of, and to properly warn, guide, control, regulate, channelize and protect the vehicular traffic, pedestrian traffic, project workers, and the public throughout the entire limits of the work activity and beyond said limits as necessary to include areas affecting or affected by the work, from the date of notice to proceed to the completion and acceptance of the work. Any corrective work required to be performed by City forces shall be charged to the Contractor and paid in full before release of any bonds on the project.

All traffic cones shall be no less than 28 inches in height, except that shorter cones, 12 inches minimum height, may be permitted during striping maintenance operations where the only function of the cone is to separate traffic from the wet paint. All barricades used to delineate traffic at night or placed in or adjacent to the traveled roadway at night, shall be equipped with flashing warning lights.

Channelizers shall be required when lane restrictions, detours or other work conditions need to be maintained for periods longer than normal work hours. Channelizers shall be surface-mounted type and shall be furnished, placed and maintained at the locations shown on the plans or as approved by the Engineer and shall conform to these specifications. Channelizers shall be, at the Contractor’s option, one of the following types, or approved equal: (1) Safe-Hit SH236SMA; (2) Repo “The Replaceable Post”; or (3) Carsonite, “Super Duck” SDF-436.SDF-436.

5-13.2 Traffic Control Plan
The Contractor shall provide a Traffic Control Plan to the agency for approval prior to the scheduled commencement of work. Comments and corrections shall be returned to the Contractor within five (5) working days.

The Contractor shall be required to maintain one lane in each direction when working on the roadway.

Access to schools, businesses, etc. shall be maintained as necessary for their operations. If closures are authorized by the Engineer, all detour signage shall be installed prior to closure of specified portion of roadway(s), and shall be maintained during closure.

Redlans Regular Meeting of 09-05-2023
809 of 1115

GC 24

The Contractor shall make provision to allow pedestrians full access across work areas at existing crosswalks, while working within those areas.

Traffic controls, including but not limited to vehicular and pedestrian traffic controls, maintenance of vehicular and pedestrian access, detours, and street closures shall be in accordance with Subsection 7-1, of the current edition of the "Standard Specifications for Public Works Construction," including all its subsequent amendments, and the current edition of the "Work Area Traffic Control Handbook."

Traffic control and the Traffic Control Plan shall conform to the following:

a. All major streets shall remain open to through-traffic at all times, residential street will be closed to traffic only as long as it takes for material application and drying time.

b. The Traffic Control Plan shall indicate the traffic control requirements for the different types of work to be performed. The Contractor shall be responsible for the preparation of Plans as necessary for specific items of work. These Plans shall be approved by the City's Engineer.

c. All traffic controls and safety devices, equipment and materials, including but not limited to cones, delineators, flashing warning lights, barricades, high level warning devices (flag trees), flags, signs, markers, portable barriers, flashing arrow signs, markings, and flagging equipment shall be provided and maintained in "like new" condition.

d. The Contractor shall furnish and properly install, construct, erect, use, and continuously inspect and maintain, twenty-four (24) hours per day, seven (7) days per week, all said devices, equipment and materials and all temporary and permanent pedestrian and driving surfaces as necessary to provide for the safety and convenience of, and to properly warn, guide, control, regulate, channelize and protect the vehicular traffic, pedestrian traffic, project workers, and the public throughout the entire limits of the work activity and beyond said limits as necessary to include area affecting or affected by the work, from the start of work to the completion of the work.

In the event the slurry and cape seal ravels, a "loose gravel" (C6) sign shall be placed to adequately warn the public.

e. High-level warning devices (flag trees) are required at all times for any work being performed within the roadway unless otherwise specifically authorized by the City's Engineer.

f. All barricades shall be equipped with flashing warning lights, and all traffic cones shall be no less than twenty-eight inches (28") in height, except that shorter cones, twelve inches (12") high or higher, may be used during striping maintenance operations where the only function of the cones is to protect the wet paint from the traffic.

Redlans Regular Meeting of 09-05-2023
810 of 1115

GC 25

g. Type III barricades, no less than six feet (6') in length and equipped with two (2) Type "N" markers each and two (2) flashing warning lights each, shall be used to close streets, except as otherwise specifically authorized in advance by the City's Engineer for minor maintenance work of no more than one (1) working days duration on weekdays, or on holidays only, and between 8:00 a.m. and 3:30 p.m. only. Said barricades shall be placed across the full roadway at each point of closure with the distance between barricades or between barricades and curbs, not exceeding three feet (3'), except that one (1) eleven-foot (11')-wide gap between barricades shall be provided at the center of the street. Barricades to the right of the street's center, facing the inbound vehicular traffic, shall also be equipped with one (1) Type C2 "Road Closed" sign each or one (1) Type C3A "Road Closed to Thru Traffic" sign each.

h. Except for residential streets, as otherwise directed and/or authorized by the City's Engineer, two-way vehicular traffic shall be maintained at all times within two (2) eleven foot (11')-wide lanes on streets, having an effective roadway width of forty-four feet (44') or more with restricted parking, and other streets of lesser widths may be reduced to one (1) twelve-foot (12') wide lane with work activity being limited to one side at a time, and with one-way vehicular traffic being maintained at all times by properly trained and experienced flaggers.

No reduction of the traveled way width shall be permitted on any City street before 8:00 a.m. nor after 3:30 p.m., on weekends or holidays, or when active work is not being done, unless prior authorization to do so is granted by the City's Engineer.

Arrow boards shall be required for all lane closures on major streets.

i. Properly trained and experienced flaggers shall be provided to traffic when said traffic is to be interrupted, when two-way traffic is to be reduced to one-way traffic, and at such other times as is necessary to safely pass the traffic through or around the work area, and when so directed by the City's Engineer.

j. Vehicular access to occupied residential property may be restricted on weekdays other than holidays between the hours of 8:00 a.m. to 3:30 p.m. while essential work activity is taking place, with specific prior written approval from the City's Engineer, providing the Contractor gives the owner and/or resident at least forty-eight (48)-hour advance written and oral notice. See Part 2, "Notification of Residents," herein.

Convenient and safe pedestrian access to occupied residential property shall be maintained at all times. Access to mailboxes must be maintained at all time, such that the postal delivery service is not interrupted.

Access to vacant and unused property may be restricted at the Engineer's discretion.

Both vehicular and pedestrian access shall be maintained at all times to all other property except as otherwise specifically authorized in writing by the City's Engineer.

Redlans Regular Meeting of 09-05-2023
811 of 1115

GC 26

k. Any traffic control and safety devices and equipment being used which becomes damaged, destroyed, faded, soiled, misplaced, worn out, inoperative, lost, or stolen shall be promptly repaired refurbished and/or replaced, and any traffic control and safety devices and equipment being used which are displaced or not in an upright position from any cause, shall be promptly returned or restored to their proper position.

l. An unobstructed view of all signs and warning devices including but not limited to stop signs, stop ahead signs, street names signs, and other regulatory, warning and construction signs, markers, and warning devices shall be maintained at all times. No trucks or other equipment or materials shall be stopped, parked, or otherwise placed so as to obscure said signs, markers, and devices from the view of vehicular and/or pedestrian traffic to which it applies.

m. When entering or leaving roadways carrying public traffic, the Contractor's equipment, whether empty or loaded, shall yield to said public traffic at all times, except where the traffic is being controlled by police officers, fire officers, properly trained and experienced flaggers, or at traffic signalized intersections.

n. Stockpiling and/or storage of materials on any public right-of-way or parking areas will not be allowed without specific permission of the Engineer. Materials spilled along or on said right-of-way or parking areas shall be removed completely and promptly. All stockpile and/or storage areas shall be kept in a safe, neat, clean, and orderly fashion, and shall be restored to equal or better than original condition upon completion of the work.

o. Where vehicular access to abutting property must be restricted, the work shall be so selected, arranged, and scheduled that the person(s) requiring access to said abutting property and/or residents along said streets affected will be able to park within a reasonable distance of not more than five hundred feet (500') from their homes and/or destination. Residents must be supplied written notice of such restrictions a minimum of 48 hours in advance.

p. When work has been completed on a particular street or has been suspended or rescheduled, and said street is to be opened to vehicular traffic, all equipment, "NO PARKING" signs, other obstructions, and unnecessary traffic control devices and equipment shall be promptly removed from that street except as otherwise authorized or directed by the City's Engineer.

q. Should the Contractor be neglectful, negligent, or refuse, fail, or otherwise be unavailable to promptly, satisfactorily, and fully comply with the provisions specified and referred to hereinabove, the City reserves the right to correct and/or mitigate any situation, which in the sole opinion of the City's Engineer constitutes a serious deficiency and/or serious case of noncompliance, by any means at its disposal at the Contractor's and/or permittee's expense, and will deduct the cost therefore from the Contractor's progress and/or final payment. Such corrective action taken by the City shall not reduce or abrogate the Contractor's legal obligations and liability for proper Redlans Regular Meeting of 09-05-2023
812 of 1115

GC 27

traffic control and safety measures, and shall not serve to transfer said obligations and liabilities from the Contractor to the City or the City's agents.

r. Violations of any of the above Provisions and/or Provisions of the referenced publications, unless promptly and completely corrected to the satisfaction of the City's Engineer, shall at the sole discretion of the City, be grounds for termination of the Contract, or shut down or partial shutdown of the work, without compensation to the Contractor and/or permittee, or liability to the City, all as prescribed by Contractual obligation or State law, whichever is applicable.

Full compensation for furnishing all labor, materials, tools, equipment, flaggers, lights, channelizers (surface mounted), temporary striping, barricades, portable flashing lights, flashing arrow signs, traffic control and detour plan, and incidentals required to comply with the provisions specified and referred to herein above, to provide all required traffic and pedestrian control for the duration of this contract, all as shown and as specified, shall be paid as specified in Section 01200 of the General Requirements and no other compensation shall be made therefore.

5-13.3 Edison Energized Conductors. The Contractor hereby promises and agrees that in the performance of the Work, he will employ and utilize only qualified persons, as hereinafter defined, to work in proximity to Edison's secondary, primary and transmission facilities. The term "qualified person" is defined as follows:

"Qualified Person". A person by reason of experience or instruction is familiar with the operation to be performed and hazards involved.

Contractor further promises and agrees that the provisions of this paragraph shall be and are binding upon any Subcontractor or Subcontractors that may be retained by it, and that the Contractor shall take such steps as are necessary to insure compliance by said Subcontractor or Subcontractors with the requirements of this paragraph.

5-14 CONTRACTOR’S RESPONSIBILITY FOR DAMAGE.

5-14.1 Responsibility for Damage. The Contractor agrees to and does hereby indemnify, defend and hold harmless the City, its elected officials and the Consultant and their officers, agents and employees from every claim or demand made, and every liability, loss, damage, or expense of any nature whatsoever, including attorney's fees and costs, which may be incurred by reason of:

(a) Liability for damages for (1) death or bodily injury to persons, (2) injury to loss or theft of property, (3) any other loss, damage or expense arising under either (1) or (2) above, sustained by the Contractor or any person, firm or corporation employed by the contractor upon or in connection with the work called for in this agreement, except for the liability resulting from the sole negligence or willful misconduct of the City, its elected officials and their officers, employees and agents who are directly employed by the City and the Consultant; and

Redlans Regular Meeting of 09-05-2023
813 of 1115

GC 28

(b) any injury to or death of persons or damage to property caused by any fault, neglect, default or omission of the Contractor, or any person, firm or corporation employed by the Contractor, either directly or by independent contract, including all damages due to loss or theft, sustained by any person, firm or corporation, including the City, arising out of, or in any way connected with the work covered by this agreement, whether said injury or damage occurs either on or off City property, provided that any of the foregoing (1) is attributable to personal injury, bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the work itself), including the loss of use resulting there from, and (2) is caused in whole or in part by any act or omission of the Contractor, any subcontractor, any supplier, anyone directly or indirectly employed by any of them or anyone for whose act or omissions any of them may be liable, regardless of whether or not caused in part by any act or omission (active, passive, or comparative negligence included, excepting the active negligence of the District) of a party indemnified hereunder.

(c) The Contractor, at its own expense, cost, and risk shall defend any and all actions, suits or other proceedings that may be brought or instituted against the City, its elected officials, officers, agents and employees and the Consultant, against any such claim, demand or liability, and shall pay or satisfy any judgment that may be rendered against the City, its elected officials, officers, agents or employees, in any such action, suit or other proceedings as a result thereof.

5-15 NO PERSONAL LIABILITY. Neither the City Council, the Engineer, the Consultant, nor any other officer or authorized assistant or agent shall be personally responsible for any liability arising under the contract.

5-16 CONTRACTOR'S RESPONSIBILITY FOR WORK. Except as provided above, until the formal acceptance of the Work by the City, the Contractor shall have the charge and care thereof and shall bear the risk of injury or damage to any part thereof by the action of the elements or from any other cause, whether arising from the execution or from the non-execution of the Work. The Contractor shall rebuild, repair, restore, and make good all injuries or damages to any portion of the work occasioned by any of the above causes before final acceptance and shall bear the expense thereof, except such injuries or damages occasioned by act of the federal government or the public enemy.

The City of Redlands shall not be held responsible for the care or protection of any material or parts of the work prior to final acceptance, except as expressly provided in these specifications.

The City shall not be responsible for security of the Contractors equipment or materials at the site.

The City will not be responsible for theft or damage to any property or materials of the Contractor.

Security for Contractor’s property shall be the responsibility of the Contractor.

5-17 WARRANTY OF WORK. The Contractor shall guarantee the Work against defective materials or workmanship for a period of (1) year from the date of completion date specified in the Notice of Completion, except where longer warranty periods are specifically stated. As specified in Redlans Regular Meeting of 09-05-2023
814 of 1115

GC 29

Section 2-4 in the GENERAL CONDITIONS, the Performance Bond shall remain in full force and effect during the warranty period.

All work which has been rejected, shall be remedied, or removed and replaced, by the Contractor at his own expense, with work conforming to the Plans and Specifications. Any defective material or workmanship which may be discovered before final acceptance or within (1) one year from the completion date specified in the Notice of Completion shall be corrected immediately by the Contractor at his own expense notwithstanding that it may have been overlooked in previous inspections and estimates. Failure to inspect work at any stage shall not relieve the Contractor from any obligation to perform sound and reliable work as herein described. It is the Contractor's ultimate responsibility to deliver at the time of final acceptance a complete project that complies in all details with these Contract Documents. All items shall be ready to operate.

Any omission or failure on the part of the Owner to discover or notify the Contractor of or to condemn defective work or material at the time of construction shall not be deemed an acceptance, and the Contractor will be required to correct defective work or material prior to final acceptance.

The Owner will endeavor to locate any errors or defective materials or workmanship and call them to the attention of the Contractor prior to subsequent work being performed. However, the Owner is under no obligation to do so and shall not be held liable because errors or defective material or workmanship by the Contractor are not discovered prior to subsequent work.

During the (1) one year warranty period, should the Contractor fail to remedy defective material and/or workmanship, or to make replacements within five (5) days after written notice by the Owner, it is agreed that the Owner may make such repairs and replacement and the actual cost of the required labor and materials shall be chargeable to and payable by the Contractor or his Surety.

Nothing in this section shall be construed to limit the rights of the Owner to immediately correct conditions which may be unsafe or which may pose a public health nuisance. Should said conditions later be found to be caused by defective material and/or workmanship, the Contractor and his Surety shall reimburse the Owner for costs reasonably incurred while attending the situation.

In the event it is necessary for the Owner to file suit to enforce any liability of the Contractor pursuant to this sections WARRANTY OF WORK, the Owner shall be entitled to recover from the Contractor, in addition to all other amounts found due and owing, costs of suit and reasonable expenses and fees, including reasonable attorneys' fees, incurred by the Owner in successfully enforcing the Contractor's obligations, all to be taxed as costs and included in any judgment rendered.

The warranty provided herein shall not be in lieu of, but shall be in addition to any warranties or other obligations otherwise imposed by the Contract Document or by law. The remedies provided herein shall not be exclusive and the Owner shall be entitled to any and all remedies provided by law.

5-18 NOTIFICATION OF RESIDENTS/BUSINESSES. The Contractor shall notify all residents, firms, institutions, agencies, and utility companies which may be affected by the work. Notification shall be by hand delivery of an approved notice within the project limits approved by the City. The notification process shall consist of two notifications, one prior to the start of construction for all Redlans Regular Meeting of 09-05-2023
815 of 1115

GC 30

properties within the project area and a second notification at least seven days in advance of any activity which may impact each specific property. In the event of any work within the downtown area, the distribution of the second notification shall be at least fourteen days in advance of any activity. Activities impacting said properties and, therefore, requiring the above said notices include the following: the work itself; closure or partial closure of the street; and disallowance of street parking and disallowance of vehicular ingress to or egress from the property.

Said firms, institutions, agencies, and utility companies which must be notified of proposed work shall include, but are not limited to the following: public schools, private schools, day care centers, postal service, hospitals, governmental services, police department, fire department, ambulance services, Omnitrans, solid waste collection, and City street sweeping.

The proposed notice shall be submitted to the Engineer at least seven calendar days prior to the date of distribution for review and approval. The submittal shall also include a map identifying the limits of the work and proposed limits of distribution. The printed notices shall contain a general description of the work to be done, the name of the street with limits, the day and date of the work and the name and telephone number of the Contractor. The notice shall also include a statement that there will be no disruption of trash collection schedules and that trash should be set out by 6:00 a.m. on the scheduled day of pickup. If on-street parking will be affected the notice shall include a statement that no on-street parking will be allowed between the hours of 7:00 a.m. and 5:00 p.m. on the day of work, and a statement that it will be necessary to tow away parked vehicles at the owner's expense per California Vehicle Code CVC 22651L and CVC 22654D.

The Contractor will provide City with the dates and addresses of when project notifications are delivered to affected properties. City will verify the notification process is completed in compliance with the requirements of the specifications. Work will commence when City approves Contractor’s compliance with the requirements set forth in the specifications.

If on-street parking is affected, the Contractor shall also post pre-approved "NO PARKING-TOW WAY" signs on 1 x 2 wood stakes or barricades at one hundred foot (100’) maximum spacing along the affected areas of the street, 48 hours prior to the start of the work. The "NO PARKING-TOW AWAY" signs shall contain the day, date, and hours that parking will be prohibited on that particular street and a statement that parked vehicles will be towed away at owner's expense per California Vehicle Code CVC 22651L and CVC 22654D. The Contractor shall maintain said signs throughout the day of work, and shall start the removal of said signs by 4:00 p.m. and complete the removal by 6:00 p.m. on said day of work or as otherwise directed by the Engineer.

The Contractor shall document the day, date, and time the signs are installed because the no parking restriction cannot be enforced until the signs have been in place 24 hours. Posting of signs on trees, utility poles, light standards and other existing parkway improvement is strictly forbidden.

In the event of street resurfacing operations, the notices to residents shall contain a statement that the street to be resurfaced will be closed to vehicular traffic, and the suggestion that if they require the use of their vehicles on the day of the resurfacing work, they should consider parking their vehicle on a nearby street which is not scheduled for a resurfacing application.

Redlans Regular Meeting of 09-05-2023
816 of 1115

GC 31

In the event scheduled work is delayed, the Contractor shall immediately remove all "NO PARKING" signs. The contractor must notify all previously notified, in person and with printed notices, that the work will be rescheduled and that they will be re-notified 48 hours in advance. The Contractor shall have an adequate supply of approved notifications for distribution to residents.

Full compensation for conforming to these requirements shall be considered as included in the various Contract items of work involved, and no additional compensation will be allowed therefore.

Failure to comply with this section shall result in a penalty assessment imposed of up to $10,000 per violation at the City’s discretion.

SECTION 6 – PROSECUTION AND PROGRESS OF THE WORK

6-1 CONSTRUCTION SCHEDULE AND COMMENCEMENT OF WORK. - Add the following paragraph:

Contractor shall notify Underground Service Alert (USA) at 1 (800) 227-2600, two working days prior to starting work, and must submit verification number to the City prior to starting work.

6-1.2 Commencement of the Work. - Amend the second sentence as follows:
“The work shall start within 10 days thereafter, and be diligently prosecuted to completion within the Contract Time.”

6-3 TIME OF COMPLETION.

6-3.1 General. - Add the following sentence:

The time of completion of the Contract shall be expressed in consecutive calendar days.

6-9 LIQUIDATED DAMAGES. The value of liquidated damages noted in this section is amended to five hundred dollars ($500) per calendar day.

6-10 NOTICE AND SERVICE THEREOF. Any notice required or given by one party to the other under the Contract shall be in writing and shall be dated and signed by the party giving such notice or by duly authorized representative of such party. Any such notice shall not be effective for any purpose whatever unless served in the following manner:

Notice shall be given to the Contractor by personal delivery thereof to said Contractor or to his authorized representative at the project site, or by deposing the same in the United States Mail enclosed in a sealed envelope addressed to said Contractor at the address established for the conduct of work under this Contract, certified and with postage prepaid.

Notice shall be given to the Surety, or any other person, by personal delivery to said Surety or other person, or by depositing the same in the United States Mail, enclosed in a sealed envelope addressed to such Surety or persons at the address of said Surety or persons last communicated by him to the party giving the notice, certified and with postage prepaid.

Redlans Regular Meeting of 09-05-2023
817 of 1115

GC 32

Notice shall be given to the Owner by personal delivery thereof or by depositing the same in the United States Mail enclosed in a sealed envelope, certified and with postage prepaid. The address of record for the owner is:

City of Redlands
Municipal Utilities & Engineering Department
P.O. Box 3005
35 Cajon Street, Suite 15A
Redlands, CA 92373

6-11 PUBLIC RECORDS ACT. All documents, Plans, specifications and all other information relating to the conduct of the City’s business, including information submitted by the Contractor, shall become the exclusive property of the City and except as provided by law shall be deemed public records. Said information shall be subject to the provisions of the California Public Records Act (Government Code Sections 6250 et seq.).

Under no circumstances will the City be responsible or liable to the Contractor, submitter or any other party for the disclosure of any records or information submitted to the City, regardless of whether such records or information are labeled “Trade Secret”, “Confidential”, or “Proprietary” (or words to similar effect) and regardless of whether the disclosure is required by law or a court order or occurs through inadvertence, mistake, or negligence on the part of the City or its officers, employees, and/or Contractors.

The City will not advise as to the nature or content of documents entitled to protection from disclosure under the California Public Records Act, including interpretations of the Act or the definition of “Trade Secret”. The submitting party shall be solely responsible for all determinations made under the Act, and where appropriate for clearly and prominently marking each and every page or sheet of information with “Trade Secret”, “Confidential”, or “Proprietary”. Each submitting party is advised to contact its own legal counsel concerning the California Public Records Act and its applicability to the submitting party’s own circumstances.

In the event of litigation concerning the disclosure of any information submitted by the submitting party, the City’s sole involvement will be as a stakeholder, retaining the information until otherwise ordered by a court. The submitting party, at its sole expense and risk, shall be responsible for any and all fees and costs for prosecuting or defending any action concerning the information, and shall indemnify and hold the City harmless from all costs and expenses including attorneys’ fees, in connection with such action.

SECTION 7 - MEASUREMENT AND PAYMENT

7-3 PAYMENT.

7-3.2 Partial and Final Payment. - Delete and replace with the following:

The closure date for the purpose of making monthly progress payments shall be assigned by the Engineer during the pre-construction meeting. Payment, less deductions, unearned work and retention, will be made within 30 days of the closure date. If a dispute exists between the City and Redlans Regular Meeting of 09-05-2023
818 of 1115

GC 33

the Contractor regarding an item included in the Contractor's Monthly Progress Payment Request, progress payments will be withheld until said dispute is resolved, in which case longer period of time will be required to make such payment. No such payment shall be required to be made, when in the judgment of the Engineer, the total value of the work since the last estimate amounts to less than $500.

If, in the opinion of the Engineer, work is not progressing according to the approved schedule, payments may be withheld until the Contractor returns to the approved schedule.

Deductions will be made for: (1) amounts due the Owner for equipment or material furnished or services rendered; (2) amounts due the Owner under the terms of the Contract; (3) amounts of any claims of lien filed with the Owner; (4) accrued amounts of liquidated damages; (5) amounts required to be deducted by Federal, State or local governmental authorities. From the balance thus determined will be deducted the amounts of all previous payments, and the remainder shall constitute the monthly payment due the Contractor.

A retention of five percent (5%) will be withheld from each and every progress payment to the Contractor. This percentage will remain constant throughout the duration of the Contract. The City shall make a progress payment within thirty (30) days after receipt of an undisputed and properly submitted payment request from Contractor pursuant to Public Contract Code section 20104.50.

After completion of the work to the satisfaction of the Engineer, the Engineer shall make a final estimate of the amount of work done. The City shall pay the entire sum so found to be due after deducting there from all previous payments and all amounts to be retained under the provisions of the Contract. All prior partial estimates and payments shall be subject to correction in the final estimate and payment. The final payment shall not be due and payable until the expiration of thirty-five (35) days from and after the recordation of the Notice of Completion filed by the City.

As provided by paragraph 22300 of the California Public Contract Code, the Contractor may substitute securities for any monies withheld by the City to ensure performance under the Contract.

Substitute securities shall be deposited in a financial institution in a form acceptable to the City of Redlands. The financial institution shall be located within the City limits of the City of Redlands.

The Escrow Agreement to be used is set forth in Public Contract Code section 22300.

7-3.3 Delivered Materials. - Delete and replace with the following:

No payment will be made for materials or equipment delivered but not yet incorporated in the work.

7-4.2.6 Extras. Without invalidating the Contract, the City may order extra work or make changes by altering, adding or deducting from the work, the Contract sum being adjusted accordingly and the consent of the Surety being first obtained where necessary or desirable. All the Work of the kind bid upon shall be paid for at the price stipulated on the proposal, and no claims for any extra work or material shall be allowed unless the work is ordered in writing by the engineer and the price is stated in such order.

7-4.2.7 Claims for Extra Costs. No claim for extra work or cost shall be allowed unless the same was done in pursuance of a written order by the Engineer, as aforesaid, and the claim presented with the first estimate after the changed or extra work is done. When work is performed under the terms of the General Conditions, the Contractor shall furnish satisfactory bills, payrolls, and vouchers Redlans Regular Meeting of 09-05-2023
819 of 1115

GC 34

covering all items of cost and when requested by the City, give the City access to accounts relating thereto.

After completion of the work to the satisfaction of the Engineer, the Engineer shall make a final estimate of the amount of work done. The City shall pay the entire sum so found to be due after deducting there from all previous payments and all amounts to be retained under the provisions of the Contract. All prior partial estimates and payments shall be subject to correction in the final estimate and payment. The final payment shall not be due and payable until the expiration of the thirty-five (35) days from and after the recordation of the Notice of Completion filed by the City.

SECTION 8 - FACILITIES FOR AGENCY PERSONNEL

This section is deleted in its entirety.

SECTION 9 - ASSIGNMENT OF UNFAIR BUSINESS PRACTICES
CLAIMS

9-1. In entering into a public works contract or a subcontract to supply goods, services, or materials pursuant to a public works contract, the Contractor or subcontractor offers and agrees to assign to the City all rights, title and interest and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. 15) or under the Cartwright Act (Chapter 2, commencing with section 16700 of part 2 of division 7 of the Business and Professions Code), arising from the purchase of goods, services, or materials pursuant to this public works agreement. This assignment shall be made and become effective at the time the City tenders final payment to the Contractor, without further acknowledgment by the Parties.

SECTION 10 - TRENCHING AND EXCAVATION

10-1. If this contract involves digging trenches or other excavations that extend deeper than (4) feet below the surface, the following shall be done pursuant to California Public Contract Code Section 7104:

A. That the Contractor shall promptly and before the following conditions are disturbed, notify the City in writing, of any:

(1) Material that the Contractor believes may be material that is hazardous waste, as defined in Section 25117 of the Health and Safety Code, that is required to be removed to a Class I, Class II or Class III disposal site in accordance with provisions of existing law.

(2) Subsurface or latent physical conditions differing from those indicated.

(3) Unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the contract.

Redlans Regular Meeting of 09-05-2023
820 of 1115

GC 35

B. That the City shall promptly investigate the conditions, and if it finds that the conditions do materially so differ, or do involve hazardous waste, and cause a decrease or increase in the Contractor’s cost of, or the time required for, performance of any part of work shall issue a change order under the procedures described in the contract.

C. That, in the event that a dispute arises between the City and the Contractor whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the Contractor cost of, or time required for, performance of any part of the work, the Contractor shall not be excused from any scheduled completion date provided for by the contract, but shall proceed with all work to be performed under the contract. The Contractor shall retain any and all rights provided either by contract or by law which pertains to the resolution of disputes and protests between the contracting parties.

SECTION 11 - REMOVAL, RELOCATION OR PROTECTION OF

EXISTING UTILITIES

11-1. Pursuant to Government Code Section 4215 et seq, the City shall assume the responsibility between the parties to this contract, for the timely removal, relocation, or protection of existing main or trunk line utility facilities located on the site of the construction project for this contract, if such utilities are not identified by the public agency in the plans and specifications made a part of the invitation for bids.

11-2. The Contractor shall be compensated for the costs of locating, repairing damage not due to the failure of the Contractor to exercise reasonable care, and removing or relocating such utility facilities not identified in the plans and specifications with reasonable accuracy and for equipment on the project necessarily identified during such work.

11-3. The Contractor shall not be assessed liquidated damages for delay in completion of the project, when such delay was caused by the failure of the City, or the owner of the utility to provide for removal or relocation of such utility facilities.

11-4. The City shall not be required to indicate the presence of existing service laterals or appurtenances whenever the presence of such utilities on the site of the construction project can be inferred from the presence of other visible facilities, such as buildings, meter and junction boxes, on adjacent to the site of construction, provided, however, nothing herein shall relieve the City from identifying main or trunk lines in the plans and specifications.

11-5. Nothing herein shall preclude the City from pursuing appropriate remedy against the utility for delays which are the responsibility of the utility.

11-6. If the Contractor, while performing the contract, discovers utility facilities not identified by the City in the contract plans or specifications, Contractor shall immediately notify the City and the utility in writing.

11-7. The public utility, when it is the owner, shall have the sole discretion to perform repairs or relocation work or permit the Contractor to do such repairs or relocation work at a reasonable price.

Redlans Regular Meeting of 09-05-2023
821 of 1115

GC 36

11-8. Contractor shall comply with Government Code Section 4216 through 4216.9.

11-9. Conduits from existing street light and traffic signal systems may be encountered during construction of this project. All removals, relocations, and/or replacements of existing conduit systems shall be performed in accordance with these specifications and City standards, by a qualified electrical contractor. All costs for said work shall be borne by the Contractor and paid as a part of the various items of work requiring such removals, relocations, and/or replacements, and no other compensation shall be made therefore.

SECTION 201 - CONCRETE, MORTAR AND RELATED MATERIALS

201-1 PORTLAND CEMENT CONCRETE.

201-1.1.1 General - Add the following paragraph:

The Contractor shall furnish the Engineer in the field with a copy of the mix design to be used, and with a legible certified weighmaster's certificate for each load of PCC delivered to the project.

PCC delivered to the project site having a water content and/or slump greater than that specified in the mix design, shall be rejected and removed from the project site.

201-1.1.2 Concrete Specified by Class and Alternate Class - Amend Table 201-1.1.2.(A) as follows:

Street Surface Improvements section -
All concrete in this section shall have a minimum compressive strength at 28 days of 22,410 kPa (3,250 pounds per square inch), and meet the requirements of class 330-C-23 (560-C-3250) concrete.

Sewer & Storm Drain Facilities section, Sidehill Surface Drainage Facilities subsection - All concrete in this subsection shall have a minimum compressive strength at 28 days of 22,410 kPa (3,250 pounds per square inch), and meet the requirements of class 330-C-23 (560-C-3250) concrete.

201-1.4.3 Transit Mixers. - Replace the first sentence in paragraph 6 with the following:

The total elapsed time between addition of water at the batch plant and the completion of the discharge of the PCC from the mixer, shall not exceed ninety (90) minutes. All PCC remaining in the mixer, after said ninety (90) minutes time limit, shall be rejected and removed from the project site.

SECTION 206 - MISCELLANEOUS METAL ITEMS

206-7 TRAFFIC SIGNS.

206-7.1 General. The Contractor shall furnish or relocate and erect all traffic signage as required and specified.

Redlans Regular Meeting of 09-05-2023
822 of 1115

GC 37

All new traffic signage shall be a minimum of the encapsulated lens (high intensity) type, have an anti-graffiti protective covering and be installed on new posts. All traffic signage to be relocated shall be installed on new posts.

206-7.2 Protective Covering. Anti-graffiti protective covering shall be Type 1150-POF, manufactured by 3M Company, or approved equal.

206-7.3 Post and Base. New posts and bases shall be Ultimate Sign Support System as manufactured by Western Highway, or approved equal.

SECTION 211 - MATERIAL TESTS

211-1 COMPACTION TESTS.

211-1.4 General. The Contractor shall be responsible for all quality control for all work. The Contractor shall complete all necessary testing to ensure the quality requirements within the specifications are achieved.

The City will complete assurance testing throughout the project by an independent testing firm.

The City will perform the first compaction test required at any location. If such test does not meet the required specifications, the City will make additional tests until the required compaction is obtained and withhold from the final payment due the Contractor, the cost of all such additional tests. To be acceptable, tests must be ordered and witnessed by the City. Tests will be ordered by the City and performed at a location and depth as directed by the City. The Contractor shall assist the City in performing these tests as necessary. The Contractor shall provide to the City the maximum dry density and the optimum moisture content results of backfill and bedding material when requested by the City.

SECTION 214 - TRAFFIC STRIPING, CURB AND PAVEMENT

MARKINGS, AND PAVEMENT MARKERS

214-4 PAINT FOR STRIPING AND MARKINGS.

214-4.1 General. - Amend the first sentence in paragraph 4 as follows:
“Glass beads conforming to 214-3 shall be mechanically applied at a rate of 0.6 to 0.8 kg of beads per liter (5 to 7 pounds of beads per gallon).”

SECTION 300 - EARTHWORK

300-1 CLEARING AND GRUBBING.

300-1.1 General. - Amend as follows:

Amend paragraph 3 as follows:
“The natural ground surface shall be cleared of all vegetable growth, such as trees, logs, upturned stumps, roots of downed trees, brush, grass, weeds, shrubs, ground cover, tree stumps, decorative Redlans Regular Meeting of 09-05-2023
823 of 1115

GC 38

landscape rocks, edging, railroad ties, other decorative landscape treatments, boulders, rock, portland cement concrete, and all other objectionable materials, within the limits of construction.”

Add the following paragraphs:

Grubbing and removal of organic debris shall include the repair and/or replacement of all parkway irrigation piping and systems necessary to perform work on this Contract and capping pipelines until such time that permanent repairs and/or replacements have been made.

All debris removed from the project site under this item shall be disposed of at an approved dump site. All transportation costs and dump fees shall be borne by the Contractor.

Clearing and Grubbing shall include, but is not limited to, the following:

1. Removal of existing AC berms.

2. Removal of all curb and gutter, cross gutters, and spandrels shall be replaced within three (3) calendar days. The Asphalt Concrete patch for areas with curbs and gutters removed and replaced shall be placed within two (2) working days after the curb and gutter, cross gutters, and spandrels are replaced. Removal of all sidewalks shall be replaced within three (3) calendar days.

3. Saw cut and removal of poles, posts, PCC pavements, curb, gutter, and sidewalk. Holes resulting from removal of existing poles and posts from existing PCC, AC pavements and curbs and gutters, shall be filled or patched with like materials. Self-propelled drop hammers will not be allowed for removals.

4. Removal of all raised pavement markers not conforming to the approved plan or conflicting with the proposed striping as shown on the plans in accordance with Subsection 312-3, Removal, of the Standard Specifications.

5. Removal and disposal of boulders, rock or PCC.

6. All trees and shrubs less than 3m (9 ft) directly above the entire sidewalk surface shall be trimmed and removed by the contractor to allow a clear path of travel for pedestrians.

7. Irrigation system relocation:

Any irrigation systems in conflict with the proposed improvements that are removed, damaged, disturbed, or broken shall be modified, repaired, and/or replaced to be operable and provide full irrigation coverage to the areas requiring irrigation using new materials, equal or better than the original materials, with 20 mm (3/4 in) Schedule 40 PVC being the minimum acceptable for underground lines and 13 mm (1/2 in) Schedule 80 being minimum acceptable for risers and with the systems not being out of operation for more than two (2) days. No payment for work associated with the irrigation repair will be released, until all irrigation is complete, operable and accepted by the City.

Redlans Regular Meeting of 09-05-2023
824 of 1115

GC 39

All trees, shrubbery and lawns deprived of normal irrigation watering due to a disruption of service caused by the Contractor’s operations shall be regularly and thoroughly irrigated by the Contractor so that said plantings will not be damaged. If any trees, shrubbery or lawns die or suffer unacceptable damage as a result of or precipitated by the Contractor’s operations the Contractor shall replace same with the same plant species and size. Existing grass lawns within areas that must be excavated and/or re-graded shall be cut into approximate 305 mm (1 ft) squares, removed, protected, cared for and replaced as soon as possible. Dead, dying, and unacceptably damaged grass shall be replaced with new grass sod.

8. Existing inlets, slotted drains, drainage pipes, concrete gutters, drainage pipes, where any portion of such structure is within 1m of the grading plane in the excavation areas, or within 300 mm (1 ft) of original ground in embankment areas, or where shown on the plans to be removed, shall be completely removed and disposed of accordingly.

9. Removal and disposal of existing drainage inlet structure and PCC or AC apron.

10. The Contractor shall dispose all materials not being salvaged outside of the right-of-way and shall pay for all costs for disposal.

11.Removal and disposal of any abandoned utilities that may interfere with the improvements.

12.Self-propelled drop hammers will not be allowed for removals.

300-1.3.1 General. - Add the following paragraphs:

The Contractor shall dispose portland cement concrete, stone rubble, and brick at an approved dump site.

All reprocessed asphaltic cement concrete may be placed as the lower course of crushed aggregate base material. If the Contractor chooses not to reprocess the material, disposal at an approved dump site shall be required. All costs for disposal shall be borne by the Contractor. If the Contractor chooses to reprocess material, it shall be protected and remain contaminate-free, otherwise disposal at an approved dump site will be required with all costs borne by the Contractor.

All reprocessed asphaltic cement concrete to be used as crushed aggregate base shall be ground to conform to Section 200-2.2.

300-1.3.2 (a) Bituminous Pavement. - Amend the following:

Amend the second sentence as follows:
“Saw cutting of edges to be joined shall be with a power-driven saw. The groove shall be cut to a minimum depth of 4 inches (102 mm).”

Amend the third sentence as follows:

Redlans Regular Meeting of 09-05-2023
825 of 1115

GC 40

“Where bituminous pavement is to be removed, a cold mill header cut of maximum 6 feet (1.8 m) in width perpendicular to the join line shall be made, and a minimum laying depth of 1 inch (25mm) of new pavement material shall be provided at the join line.”

Amend the fourth sentence as follows:
“The edges of existing concrete pavement adjacent to the trench shall be saw cut to neat straight lines for the purpose of removing the damaged pavement areas.”

Add the following sentence:

Work under this item shall include asphalt concrete berms.

300-1.3.2 (b) Concrete Pavement. - Amend the following:

Amend the second sentence as follows:
“Saw cuts shall be made to a minimum depth of 4 inches (102 mm).”

Amend the third sentence as follows:
“If a saw cut in concrete pavement falls within 5 feet (1.5 m) of a construction joint, cold joint, expansion joint, or edge, the concrete shall be removed to the joint or edge.”

300-1.3.2 (c) Concrete Curb, Walk, Gutters, Cross Gutters, Driveways and Alley Intersections. - Amend the following:

Amend the first sentence as follows:
“Concrete shall be removed to neatly sawed edges with saw cuts made to a minimum depth of 4 inches (102 mm).”

Amend the third sentence as follows:
“No section to be replaced shall be smaller than 36 inches (1 m) in either length or width.”

Amend the fourth sentence as follows:
“If the saw cut in sidewalk or driveway would fall within 36 inches (914 mm) of a construction joint, expansion joint, or edge, the concrete shall be removed to the joint or edge, except that where the saw cut would fall within 12 inches (300mm) of a score mark, the saw cut shall be made in and along the score mark.”

Amend the fifth sentence as follows:
“curb and gutter shall be sawed to a depth of 4 inches (102 mm) on a neat line at right angles to the curb face.”

300-1.3.2 (d) Striping and Markings. All existing striping, markings and raised pavement markers shown to be removed or necessary to be removed from paving areas. This item includes removal in compliance with applicable laws and cleanup of residue from the operation.

All striping, markings and raised pavement markers removed beyond the limits shown on the plans for and/or at the convenience of the Contractor shall be replaced at the Contractor’s expense.

Redlans Regular Meeting of 09-05-2023
826 of 1115

GC 41

300-1.3.2 (e) Structures. All existing concrete structures (reinforced or non-reinforced) as shown on the plans to be removed or abandoned, including but not limited to, undersidewalk drains, manholes, headwalls, bulkheads, drop inlet structures, energy dissipaters, catch basins, vaults and pipelines. Abandonment shall include all cuts and concrete plugs necessary to seal ends or openings of abandoned pipes or structures.

300-1.3.2 (f) Rock Curbs. All rock from rock curb removals, as shown on the plans or required for construction of the project, shall be transported, delivered and unloaded at a storage site as directed by the Engineer.

300-1.3.2 (g) Miscellaneous Removals. All other removals of facilities, as shown on the plans but not covered under separate bid items, and any underground facilities found during the work and not shown on the plans shall be performed. The City has endeavored to show all known underground facilities but is not responsible for unknown or abandoned facilities. Unknown underground facilities shall be paid as extra work.

300-1.3.2 (h) Miscellaneous Relocations. All relocation work as shown on the plans or required for construction of the project, but not covered under separate bid items, shall be included as a part of Subsection 300-1 Clearing and Grubbing. All relocation work performed as a part of clearing and grubbing work shall conform to the requirements and specifications of the agency or utility having jurisdiction over the item to be relocated.

300-1.4 Payment. - Add the following sentence to paragraph 1:

Payment for work on this item shall be made as a percentage of the work completed at each monthly payment.

300-2 UNCLASSIFIED EXCAVATION.

300-2.2.2 Wet Material. - Amend the second sentence of the paragraph:
“If such high moisture content is not the result of any action on the part of the Contractor, or inaction in protecting the work during the course of the contract, the work involved will be paid for in the following manner: Over-excavation and disposal work shall be considered “extra work,” with backfill and compaction of crushed aggregate base paid under the appropriate bid item in these specifications.”

300-12 MISCELLAENOUS GRADING. The parkway, whether landscaping exists or not, shall be graded and compacted to achieve drainage towards the street at a slope of 2%. Grading shall be coordinated such that it is the last item of work to be completed, prior to site clean-up. Loose material and dirt shall be raked, compacted and distributed throughout the parkway area. Areas adjacent to installed improvements must be graded to a level within one inch from the finished surface. Extra dirt/fill shall be removed from the project in accordance with Specifications.

The Contractor, at his expense shall photo-document pre-construction conditions prior to starting excavating. After construction is completed, the Contractor shall photo-document the finished grade. The Contractor shall provide the City with said photos with addresses identifying each property location, the direction the photograph was taken (facing North, South etc). The Redlans Regular Meeting of 09-05-2023
827 of 1115

GC 42

Contractor shall keep a copy of the photos (either electronically or hard copy) and provide the City with electronic copies of the photos.

SECTION 301 - TREATED SOIL, SUBGRADE PREPARATION AND

PLACEMENT OF BASE MATERIALS

301-1 SUBGRADE PREPARATION.

301-1.3 Relative Compaction. - Amend the second sentence of paragraph 1 as follows:
“When base material, curb, gutter, alley pavement, driveways, or sidewalks are to be placed on the subgrade material, the top 6 inches (150mm) of such subgrade material shall be compacted to a relative compaction of 95 percent.”

301-2.1 General. – Add the following paragraphs:

The contractor shall use ‘crushed aggregate base’ or ‘crushed miscellaneous base, fine graded’ as the base material. The use of ‘processed miscellaneous base,’ ‘select subbase,’ or ‘disintegrated granite’ shall not be used as base material.

The contractor may use ‘pulverized miscellaneous base’ (grindings) as part of the crushed base material. Said grindings shall be uncontaminated and placed in an even thickness as the lower course of crushed base material. Spreading and compacting shall comply with Sections 301-2.2 and 301-2.3.

301-2.3 Compacting. – Amend the second sentence of paragraph 3 as follows:
“Compaction in the excepted areas shall be as specified in 211-1 with each layer of compacted base material having a minimum relative compaction of 95 percent.”

301-2.4 Measurement and Payment. – Add the following paragraph:

Payment shall be made for cold-planing, storing, placing, and compacting reprocessed asphalt concrete pavement (grindings) as part of the crushed aggregate base (CAB) material. The volume of grindings placed shall be figured and a tonnage figure computed using 9.35 kg/m^3 (150 pounds per cubic foot). This tonnage figure shall be paid as part of the crushed aggregate base tonnage for this project.

301-6 FULL DEPTH RECLAMATION WITH MECHANICAL STABILIZATION (FDR- 25)

301-6.1 Description. This rehabilitation alternative consists of pulverizing the existing asphalt concrete (AC) layer along with the underlying unbound material to a depth of 6, 9 or 12 inches per plan and specifications. The properties of this layer are considered to be similar to an Aggregate Subbase material with a modulus of at least 25 ksi.

The manufacture of the recycled base course shall be done in-place by pulverizing and blending the existing AC layer and base materials, if present. The process shall be accomplished in accordance with these specifications and conform to the lines and grades shown in the plans or as established by the engineer.

Redlans Regular Meeting of 09-05-2023
828 of 1115

GC 43

301-6.2 Construction . The asphalt concrete surfacing and underlying base materials shall be pulverized such that 100 percent of the material will pass a two-inch sieve and a minimum of 90 percent will pass a one and one-half inch sieve. All materials other than rock and pulverized asphalt concrete shall be broken up such that these materials will pass a one inch sieve. The pulverized materials shall be free of roots, weeds, wood, and construction debris. All grass and other vegetation shall be removed from the edge of the exiting pavement or lip of gutter pan to prevent contamination of the pulverized bituminous material during the milling operation.

Trimming and disposal of excess material, if required, will be performed on the intimate mixture of pulverized asphalt concrete, base materials and subgrade soil. Excess pulverized material is the surplus that results after trimming and grading the pulverized pavement section to the lines and grades matching existing and/or per plans and specifications.

Do not start pulverized roadbed activities if the ambient air temperature is below 40F. If the ambient air temperature falls below 40F, you may only compact and finish pulverized roadbed.

Before starting daily pulverized roadbed activities, sweep the pulverized roadbed area constructed the previous day to remove loose material.

301-6.3 Surface Preparation. Before pulverized roadbed activities start, prepare the existing roadway surface by:

1. Clearing foreign matter including vegetation

2. Removing standing water

3. Referencing the profile and cross slope

4. Marking the proposed longitudinal cut lines on the existing pavement as follows:

4.1. Cut lines must coincide with points where the existing cross slope changes, approximately at the centerline and edge of traveled way

4.2. Cut lines must indicate the sequence of the cuts

5. Referencing existing lane lines and striping layout

Final subgrade surface shall slope away from the street centerline to a maximum of 3% grade.

Pulverized asphalt material must be used as base material to meet new cross slope requirements.

Native sub-grade material may need to be hauled off to allow for the use of all pulverized base material. No additional compensation will be allowed for any sub-grade removal and haul-off if required. Any contaminated material will be removed and disposed of by the contractor off site at his expense. Any shortage of material, caused by premature disposal of the indicated surplus material by the contractor, shall be replaced by it and no additional compensation will be allowed for such replacement.

301-6.4 Spreading, Mixing, and Compacting. Do not use a heating device to soften the pavement. Remove any visible oversized materials in the pulverized roadbed mixture prior to shaping and compacting. If you encounter unstable subgrade or rocks greater than 4 inches in the roadway section, notify the Engineer. The Engineer determines the extent of the unsuitable material and the corrective measures to be taken.

Redlans Regular Meeting of 09-05-2023
829 of 1115

GC 44

According to the Section 301-2.3, the compaction shall always be commenced along the edge of the area to be compacted and the roller shall gradually advance toward the center of the area to be compacted. Rollers shall be operated along lines parallel or concentric with the centerline of the road being constructed, and no material variation therefrom will be permitted. All rollers must be maintained in good mechanical and working condition.

The relative compaction of each layer of compacted base material shall not be less than 95 percent.

ASTM D2922, Methods of Density of Soil and Soil Aggregate in Place by Nuclear Methods, (or ASTM D1556). After compaction, the sub-grade shall be firm, and unyielding.

301-6.5 Finishing. The finished pulverized roadbed surface must not vary more than 0.05 foot from the lower edge of a 12-foot straight edge laid in directions parallel and perpendicular to the centerline. Variations within the above specified tolerances shall be compensating so that the average grade and cross section specified are met. The finished surface must be free from segregation, tearing, and scarring, and have a uniform surface texture throughout the work limits.

301-7 FULL DEPTH RECLAMATION WITH CEMENT STABILIZATION (FDR-200)

301-7.1 Description. This rehabilitation alternative consists of pulverizing the existing asphalt concrete (AC) layer along with the underlying unbound material to a depth of 6, 9 or 12 inches per plan and specifications. The properties of this layer are considered to be similar to an Aggregate Subbase material with a modulus of at least 200 ksi.

The manufacture of the recycled base course shall be done in-place by pulverizing and blending the existing AC layer and base materials, if present, and adding cement. Micro-cracking of the completed cement stabilized surface is required before HMA is to be placed directly on top of the cement treated surface, regardless of the AC thickness. The process shall be accomplished in accordance with these specifications and conform to the lines and grades shown in the plans or as established by the engineer.

The cement content must be 2% by dry weight of FDR with cement with a dry unit weight of 130 lb/cu ft for 6” FDR section. The cement content must be 3% by dry weight of FDR with cement with a dry unit weight of 130 lb/cu ft for 9” FDR section. The cement content must be 4% by dry weight of FDR with cement with a dry unit weight of 130 lb/cu ft for 12” FDR section. Cement must be Type II or Type V Portland cement specified in ASTM C 150/150M.

301-7.2 Construction . The asphalt concrete surfacing and underlying base materials shall be pulverized such that 100 percent of the material will pass a two-inch sieve and a minimum of 90 percent will pass a one and one-half inch sieve. All materials other than rock and pulverized asphalt concrete shall be broken up such that these materials will pass a one inch sieve. The pulverized materials shall be free of grass and vegetation, and construction debris to prevent contamination of the pulverized materials. Mixing shall continue until, and at the speed of the recycling unit adjusted to ensure, a homogenous mixture of the above materials and pulverized materials are achieved.

Redlans Regular Meeting of 09-05-2023
830 of 1115

GC 45

Trimming and disposal of excess material, if required, will be performed on the intimate mixture of pulverized asphalt concrete, base materials and subgrade soil. Excess pulverized material is the surplus that results after trimming and grading the pulverized pavement section to the lines and grades matching existing and/or per plans and specifications. Excess pulverized material shall consist of non-treated well mixed pulverized AC pavement and subgrade.

Do not start pulverized roadbed activities if the ambient air temperature is below 40F. If the ambient air temperature falls below 40F, you may only compact and finish pulverized roadbed.

Before starting daily pulverized roadbed activities, sweep the pulverized roadbed area constructed the previous day to remove loose material.

301-7.3 Surface Preparation. Before pulverized roadbed activities start, prepare the existing roadway surface by:

1. Clearing foreign matter including vegetation

2. Removing standing water

3. Referencing the profile and cross slope

4. Marking the proposed longitudinal cut lines on the existing pavement as follows:

4.1. Cut lines must coincide with points where the existing cross slope changes, approximately at the centerline and edge of traveled way

4.2. Cut lines must indicate the sequence of the cuts

5. Referencing existing lane lines and striping layout

Final pavement surface shall slope away from the street centerline to a maximum of 3% grade.

Pulverized material must be used as base material to meet new cross slope requirements. Native sub-grade material may need to be hauled off to allow for the use of all the pulverized base material. No additional compensation will be allowed for any sub-grade removal and haul-off if required. Any contaminated material will be removed and disposed of by the contractor off site at his expense. Any shortage of material, caused by premature disposal of the indicated surplus material by the contractor, shall be replaced by it and no additional compensation will be allowed for such replacement.

301-7.4 Spreading, Mixing, and Compacting. Do not use a heating device to soften the pavement. Remove any visible oversized materials in the pulverized roadbed mixture before shaping and compacting. If you encounter unstable subgrade or rocks greater than 4 inches in the roadway section, notify the Engineer. The Engineer determines the extent of the unsuitable material and the corrective measures to be taken.

Recycling shall be performed to the depth provided in the plans, while incorporating stabilizing agents, mineral filler, additional aggregate and water. Mixing shall continue until, and the speed of the recycling unit adjusted to ensure, a homogenous mixture of the above materials and pulverized materials is achieved. Pre-cutting, grading and light compacting of the recycled material shall be performed prior to incorporation of the stabilizing. Spread cement uniformly over the full roadway surface width. Do not spread cement more than 30 minutes before mixing. Do not apply dry cement in windy conditions that will result in dust outside the FDR with cement area. The application rate must be the mix design rate or the ordered application rate in lb/sq yd ± Redlans Regular Meeting of 09-05-2023
831 of 1115

GC 46

0.5 percent. The application rate of all stabilizing agents shall be continuously monitored. If the measured application rate falls outside the above tolerance, then the recycling operations shall be stopped and corrected before proceeding. Do not spread cement and aggregate before pulverizing.

Water must be injected through the pulverizing machine. The injection rate of mixing water must be sufficient to produce the FDR with cement material mixing moisture content. The water content of the stabilized material shall be monitored closely to ensure proper compaction. Mark where the center of the pulverizing drum stops. Start the following cut on this alignment at least 2 feet behind the mark. Before compacting, remove solids larger than 3 inches in any dimension by hand.

Immediately after pulverizing and mixing, compact FDR with cement to the minimum relative compaction. Do not allow more than 2 hours between final mixing of the pulverized material with cement and completion of initial compaction before trimming. During grading and final compaction add water to maintain the mixing moisture content as described in the mix design. Do not allow more than 2 hours to elapse from the time water is added to the aggregate and cement to completion of final compaction after trimming.

Longitudinal joints between adjacent stabilization passes shall be overlapped at least 4 inches.

Transverse joints between the recycling process shall be saw-cut, if necessary, to provide a vertical clean face to ensure proper compaction. Compaction of cementitious stabilizer begins within 20 minutes after mixing and achieving gradation and moisture requirements.

According to the Section 301-2.3, the compaction shall always be commenced along the edge of the area to be compacted and the roller shall gradually advance toward the center of the area to be compacted. Rollers shall be operated along lines parallel or concentric with the centerline of the road being constructed, and no material variation therefrom will be permitted. All rollers must be maintained in good mechanical and working condition.

The relative compaction of each layer of compacted base material shall not be less than 95 percent.

ASTM D2922, Methods of Density of Soil and Soil Aggregate in Place by Nuclear Methods, (or ASTM D1556). After compaction, the sub-grade shall be firm, and unyielding.

Construction joints shall have vertical faces and shall be made in thoroughly compacted material.

Additional mixture shall not be placed against the construction joint until the joint has been approved by the Engineer. The face of the cut joint shall be lean and free of deleterious material and shall be kept moist until the placing of the adjacent FDR with cement.

301-7.5 Finishing. Once the entire working width (full lane width plus effected shoulder width) has been stabilized, and only after primary compaction has been completed, the entire working width shall be graded to the required profile and cross-slope. Disturbance to the stabilized and primary compacted material shall be kept to a minimum during this grading and shaping operation.

The finished pulverized roadbed surface must not vary more than 0.05 foot from the lower edge of a 12-foot straight edge laid in directions parallel and perpendicular to the centerline. Variations within the above specified tolerances shall be compensating so that the average grade and cross Redlans Regular Meeting of 09-05-2023
832 of 1115

GC 47

section specified are met. The finished surface must be free from segregation, tearing, and scarring, and have a uniform surface texture throughout the work limits.

Immediately after compaction, apply water and roll with no vibration. The finished surface must be free of ruts, bump, indentations, segregation, raveling, and any loose material.

The completed cement treated subgrade shall be moist cured continuously until it is in a firm and unyielding condition. The cement treated subgrade shall be kept free from heavy traffic during the curing period or until the asphalt concrete surfacing is placed whichever is less, unless otherwise directed by the Engineer. Moisture curing shall be the only method of curing prior to micro- cracking.

Micro-cracking shall be performed with several vibratory roller passes 48 to 72 hours after finish grading to prevent severe, wide cracks from forming thus reduces the potential for reflective cracking through the HMA layer. Micro-cracking shall be performed before the application of asphaltic emulsion curing seal. After micro-cracking is complete additional moisture curing may be used. Any additional water required to achieve maximum density shall be applied by spraying the surface of the stabilized material with light applications. Care shall be taken so as not to over- apply additional water to any areas of the stabilized material.

While open to traffic and before placing HMA, maintain the FDR with cement surface free of ruts, bumps, indentations, raveling, and segregation. If FDR with cement material is damaged, it shall be repaired by removing and replacing the entire depth of affected layers in the damaged area.

Feathering will not be permitted for repair of low areas.

Asphaltic emulsion curing seal must be applied on the completed cement treated base immediately before placing HMA. Asphaltic emulsion curing seal must comply with Caltrans Standard Section 94, Grade SS1 or CSS1. Dilute and thoroughly mix asphaltic emulsion for curing seal at a ratio of 1 part water to 1-part asphaltic emulsion. The water must no cause premature separation of the emulsion. Uniformly apply the diluted curing seal at a rate of 0.1 gal/yd2 of cement treated base surface.

SECTION 302 - ROADWAY SURFACING

302-4 SLURRY SEAL SURFACING.

302-4.3.1 General. – Add the following paragraphs:

All slurry mixing machines shall be equipped with a Fines Feeder for the adding of cement or granular Aluminum Sulfate.

Prior to the beginning of slurry operations, the Contractor shall furnish, at no cost to the City, current licensed weigh master’s certificates indicating the net weight capacity of the aggregate bin.

The Contractor shall provide a drive upon scale at the project site or an alternate site approved by the City. The drive on scale shall show the net weight of the aggregate bin on each slurry machine before the machine and product will be approved for applying slurry on the project.

Redlans Regular Meeting of 09-05-2023
833 of 1115

GC 48

All slurry machines are to carry, at all times, a calibrated emulsion measuring stick. The emulsion measuring stick is to be calibrated in 10-gallon increments to the slurry machine it is used on.

Emulsion measuring sticks from other slurry machines will not be allowed to measure the gallons of emulsions on the slurry machines they were not calibrated to. The emulsion measuring stick is to have the slurry machine number or identification permanently marked on the stick. The gallons of emulsion are to be measured with a calibrated emulsion measuring stick and recorded before leaving and after returning to materials site. Use of a slurry machine will not be allowed if it does not have a calibrated emulsion measuring stick.

The Contractor shall furnish prior commencing work, a calibrated stick in 10-gallon increments to measure the oil in the trailer storage tanks in gallons. The measuring stick shall be calibrated to the trailer storage tank it is used on. The inspector shall check the oil in each load “in and out” and in the storage tanks at the beginning and end of each day to determine the amount of emulsion used for that day. Emulsion is not to be transferred from delivery tank to on-site storage tank before the City performs the sieve analysis on the emulsion. Aggregate used in the slurry shall not exceed a moisture content of four percent (4%) by weight of dry aggregate.

Contractor may not schedule more than 150 tons of slurry to be placed per day. Slurry may not be applied at more than 150 feet per minute.

The Contractor shall provide a self-propelled 10 ton pneumatic roller with a tire pressure of 50 PSI and equipped with a water spray system. The Contractor shall roll the required streets the same day they are slurried. The Contractor will be responsible for proper scheduling of the work such that the rolling can be properly done within the given time constraint. Failure to comply shall result in a $250.00/calendar day liquidated damage being assessed per incident. The cost of furnishing the roller and operator shall be included in the price paid for slurry seal.

The Contractor is hereby advised that City streets, parking lots, or other City-approved property will not be allowed as a site for stockpiling and batching. Arrangements for an acceptable site shall be the sole responsibility of the Contractor.

The Contractor shall sweep any raveled material on the street one (1) week after the initial placement. If the Engineer determines the raveling is excessive, the frequency of sweeping shall be adjusted to the field conditions of the raveling. If raveling continues within two (2) weeks of the initial placement, the street shall be swept and reslurried with a Type I mixtures (Local Streets) or a Type II (Arterial/Collector Streets) at no cost to the City. Raveling can be identified by the presence of “black pebbles” in the gutter.

The Contractor shall remove any and all weeds that are growing through cracks from the project street located within the pavement or growing between the concrete gutter and the pavement and spray a herbicide mixture of either Hyvar mixed with Roundup or Pramatol mixed with Roundup, or approved equal, at least fourteen (14) calendar days prior to slurrying. The herbicide mixture shall contain Blazon, or approved equal, a purple dye to easily confirm the herbicide has been applied. The work shall be approved by the Engineer or his representative prior to slurrying. Full compensation for plant removal and herbicide treatment shall be considered as included in the unit cost for slurry seal.

Redlans Regular Meeting of 09-05-2023
834 of 1115

GC 49

Longitudinal joints must correspond with lane lines. You may request other longitudinal joint patterns if they do not adversely affect the slurry seal. Spread slurry seal in full lane widths. Do not overlap slurry seal between adjacent lanes more than 3 inches. Use a material, such as building paper at transverse joints and over previously placed slurry seal to prevent double placement.

Remove the material after use. Use hand tools to remove spillage.

Full compensation for developing a water supply, for furnishing and placing all water required for work done in the Contract, including extra work shall be included in the prices paid for the various items of work requiring water; and no separate payment will be made therefore. The Contractor shall supply the City with licensed weighmaster’s certificates of weight for all delivered aggregates to the job during the course of each day. Aggregate shall be delivered to the project only in the presence of a City representative. The Contractor shall also present weighmaster certificates for the amount of such aggregate remaining at the completion of the project at no cost to the City.

Payment shall be determined by the amount that is physically placed, which cannot exceed the amount that is delivered to the job site with the certified weighmaster tickets. There shall be not outside work done utilizing materials from the tanks or stockpiles stored for the City’s Contract.

Prior to storing aggregate on private property, the Contractor shall submit to the Engineer written permission from the property owner for such stockpiling.

Precautions shall be taken to ensure that stockpiles do not become contaminated with oversized rock, clay, silt, or excessive amounts of moisture. The stockpiles shall be kept in areas that drain readily. Segregation of the aggregate will not be permitted.

The Contactor shall protect the wet slurry from traffic at all times and if damaged or defaced, the Contractor shall repair said damage at no additional cost to the City.

The placement of slurry seal may be suspended with the concurrence of the Engineer due to unsuitable weather, temperature conditions, or other conditions that are considered unfavorable for the prosecution of the work. The Contractor shall immediately comply with the order of suspension by the Engineer, and work shall not be resumed until authorized by the Engineer.

302-4.8 Spreading and Application. - Add the following paragraphs:

Prior to applying slurry seal, the Contractor shall clean, to the satisfaction of the Engineer, the street surface with a power sweeper, remove all R.P.M.’s, abrasive grind or sandblast completely all lane lines, street legends, crosswalks or other painted or thermoplastic surfaces. This is necessary to provide a good bonding surface for the slurry seal, as well as eliminate “ghosting” of the old striping and markings as the new slurry wears off over time.

It is anticipated that nuisance water, such as storm water runoff and irrigation water, will run in and across the right-of-way at various time throughout the period of construction. It shall be the responsibility of the Contractor, at their own expense, to provide for and protect the work from such water. In addition, the Contactor’s responsibility shall include handling nuisance waters such that their operations do not cause them to damage existing improvements or properties adjacent to or near the site of work.

Redlans Regular Meeting of 09-05-2023
835 of 1115

GC 50

Slurry shall not be applied when the atmospheric temperature is less than 65oF (18oC).

The application of slurry shall not commence until after 8:00 a.m., and shall conclude at 1:30 p.m. unless other authorized by the Engineer. The slurry shall be sufficiently cured to be open to traffic by 4:00 p.m. The portions of streets to be slurried shall be closed from the time the application begins until the mixture as achieved sufficient set to be opened to traffic.

The slurry shall be applied in such a manner that no ripples or waves exist. If ripples or waves occur in the slurry during the application, the work shall cease and the Contractor shall correct the situation. The Contractor may use a drag to knock down ridges. If ripples or waves are not corrected to the Engineer’s satisfaction, the street shall be reslurried at the Contractor’s expense.

The Contractor shall, at the direction of the Engineer, repair the reseal to the entire street, or complete section thereof, as determined by the Engineer, which have not been sealed properly (includes areas that have failed to meet yield and mix design specifications) and completely. No compensation will be provided for slurry seal used in repair and reseal work.

Each slurry crew shall be composed, at a minimum, of a coordinator at the project site at all times, a competent quick-set mixing man, a competent driver, two squeegee men, and sufficient laborers for any handiwork and cleanup.

Surface oil and grease shall be removed or sealed with shellac or an equivalent material approved by the City before the application of the slurry seal. Full compensation for surface oil and grease removal shall be considered as included in the unit cost for slurry seal.

The Contractor shall roll all cul-de-sacs (the last 250’ minimum), the last 250’ of dead-end streets and knuckle curves. Full compensation for rolling the slurry shall be considered as include in the unit cost for slurry seal.

During slurry seal operations, it shall be the Contractor’s responsibility to place protective covering over, or to otherwise avoid slurry seal coating of manholes, utility covers, pavement markers (reflective and non-reflective), concrete gutters, concrete cross gutters, and drainage facilities, survey monuments and remove said covering and/for slurry seal coating after slurry sealing has been completed.

The start and finish of slurry application shall be a straight line which, unless otherwise approved by the Engineer, shall be obtained by laying a strip of building paper or other material approved by the Engineer on the pavement surface. After application of slurry, the paper is to be removed leaving a straight edge. The entire street surface area shall be sealed the same day.

302-4.8.1 Crack Sealing and Filling. Crack sealing shall be performed prior to the Slurry Seal application. Pavement cracks 1/4" wide and larger shall be sealed. Pavement cracks 1/8" to 1" wide shall be cleared of all loose particles of dust, dirt and laitance with oil-free compressed air immediately preceding the sealing operation. Cracks shall be routed out as necessary to provide a reservoir for the sealer that will have a depth of l" to 1 1/2".

Redlans Regular Meeting of 09-05-2023
836 of 1115

GC 51

The crack sealing material shall be a hot-applied asphalt (Crafco Polyflex or approved equivalent).

The crack sealing material must not be modified or diluted in any way. Pavement cracks larger than 1” wide shall be filled with the mixtures per Specification Section 203-6.4 Type E (Extra Fine).

A wand and nozzle type application shall be used to fill all cracks with crack sealing material.

Crack sealing material shall be applied in two applications with the possibility of additional applications to fill the crack within the allowable tolerance. The cracks must be filled to the surface and not overfilled or applied to the top of adjoining pavement or concrete surfaces. The cracks shall be squeegee immediately after the sealant has been applied to insure conformity with the pavement surface.

The crack sealing material shall then be allowed to penetrate and sink into the crack area for a minimum of one hour. Each crack must then have a second application of crack sealer material applied in the crack area only to within + 0.01' of the adjoining pavement surface. If the material is a cold-applied, polymer modified petroleum emulsion, sand will be applied over the crack sealing material after the second application, covering a minimum of 1 1/2 inches each side of the crack and not more than 3/4 inch higher than the top of the pavement. The contractor shall be responsible for the removal of all excess sand which shall be removed within three hours after being applied.

302-5 ASPHALT CONCRETE PAVEMENT.

302-5.1 General. - Add the following paragraphs:

Asphalt concrete pavement structural sections equal to or greater than 3 inches (76 mm) in thickness shall be installed in two lifts. Base course aggregate material size shall be ¾ inch (19 mm) and cap course aggregate material size shall be ½ inch (13 mm). All pavement shall be placed over 4 inches of crushed aggregate base, unless compacted to 95% relative compaction.

All valves within project limits in the public right-of-way shall be raised to finish grade as a part of this work. The Contractor shall furnish and install new can or slip can materials as necessary.

If new water valve lids are necessary, they shall be supplied by the Municipal Utilities and Engineering Department. All valve can lids within the project limits in the public right-of-way shall be painted the appropriate color for the utility they represent (ie. Water - Blue, Gas - Yellow, Fire – Red, etc.).

302-5.2 Timeline of Paving Operations.

All paving operations shall follow the timeline and requirements shown below unless otherwise approved by the City:

PAVING TIMELINE

DESCRIPTION OF WORK

TIME PERIOD
WEEK 1
(DAY 1-7)
WEEK 2
(DAY 8-14)
WEEK 3
(DAY 15-21)
WEEK 4
(DAY 22-28)
Redlans Regular Meeting of 09-05-2023
837 of 1115

GC 52

PAVING (START TO FINISH) (1)
CURE PERIOD (2)
MANHOLE ADJUST TO GRADE (3)
STRIPING & PAVEMENT MARKINGS (4)
TRAFFIC LOOPS (5)
NO PARKING SIGNS ALLOWED (6)
Note: All time periods shown above are the maximum amount of allowable time for each activity.

This timeline does not apply to the installation or repair of curb and gutter, ac dikes, sidewalks, cross gutters, curb ramps, driveway approaches or truncated domes.

(1) In no case shall any street segment remain unpaved longer than three calendar days if no other work activity is being performed on that street segment. Any deviation from the timeline shall result in a penalty assessment of $1,000 per calendar day. (2) No work except cat tracking of proposed striping is allowed during this period; therefore “No Parking Signs” shall not be installed during this activity. (3) Once each manhole is exposed, all associated work to adjust it to grade must be completed within 48 hours. This shall include all adjustments of manholes, vaults, valve cans, etc. as required by the Contract.
(4) All cat tracking and approval of proposed striping shall occur during the cure period. (5) Traffic loops must be installed after the approval of striping layout and prior to the installation of thermoplastic striping and pavement markings. (6) “No Parking Signs” shall be installed per Section 7-19 of these specifications.

302-5.4 Tack Coat. – Delete and replace with the following:

If the asphalt concrete pavement is being constructed directly upon an existing hard-surfaced pavement, a tack coat of High Performance Seal (HPS) No-Track Tack at an approximate rate of

0.05 gallon per square yard shall be uniformly applied upon the existing pavement preceding the placement of asphalt concrete. The surface shall be free of water, foreign material, or dust when the tack coat is applied. To minimize public inconvenience, no greater area shall be treated in any one day than is planned to be covered by asphalt concrete during the same day, unless otherwise approved by the Engineer.

302-5.5 Distribution and Spreading. – Add the following:

Unless otherwise permitted by the Engineer, the top layer of asphalt concrete for shoulders, tapers, transitions, road connections, private drives, curve widening, turnouts, left-turn pockets, and other such areas, shall not be spread before the top layer of asphalt concrete for the adjoining through lane has been spread and compacted. At locations where the number of lanes are changed, the top layer for the through lanes shall be paved first. Tracks or wheels of spreading equipment shall not be operated on the top layer of asphalt concrete in any area until final compaction has been completed or unless directed by the Engineer.

Redlans Regular Meeting of 09-05-2023
838 of 1115

GC 53

All screed extensions for paving machines shall be provided with a tamper, roller, or other suitable compacting devices.

Asphalt pavers shall be equipped with automatic screed controls and a sensing device or devices.

Automatic grade and slope control shall be used for overlays.

All joints shall be sealed after rolling.

When placing asphalt concrete to the lines and grades noted in the plans or as approved by the Engineer, the automatic screed controls shall control the longitudinal grade and transverse slope of the screed. Grade and slope references shall be furnished, installed, and maintained by the Contractor. The Contractor shall use a ski device, the minimum length of the ski device shall be 30 ft. The ski device shall be a rigid one-piece unit and the entire length shall be utilized in activating the sensor. The Contractor may use a laser to control the screed.

When placing the initial mat of asphalt concrete on existing pavement, the end of the screed nearest the center line shall be controlled by a sensor activated by a ski device not less than 30 ft long.

The end of the screed farthest from center line shall be controlled by an automatic transverse slope device set to reproduce the cross slope approved by the Engineer.

When paving contiguously with previously placed mats, the end of the screed adjacent to the previously placed mat shall be controlled by a sensor that responds to the grade of the previously placed mat and will reproduce the grade in the new mat within a 0.01 ft. tolerance. The end of the screed farthest from the previously placed mat shall be controlled in the same manner as when placing the initial mat.

Should the automatic screed controls fail to operate properly during any day's work, the Contractor may use manual control of the spreading equipment for the remainder of that day; however, the equipment shall be corrected or replaced with alternative automatically controlled equipment conforming to the requirements in this section before starting the next day's work.

Should the methods and equipment furnished by the Contractor fail to produce a layer of asphalt concrete conforming to the requirements, including straightedge tolerance, of Subsection 302-

5.6.2 - Density and Smoothness, of the Standard Specifications, the paving operation shall be discontinued and the Contractor shall modify his equipment or furnish substitute equipment. A drop-off of more than 0.15 ft will not be allowed at anytime between adjacent lanes open to public traffic.

The Contractor shall schedule his paving operations such that each layer of asphalt concrete is placed on all contiguous lanes of a traveled way each work shift. At the end of each work shift, the distance between the ends of the layers of asphalt concrete on adjacent lanes shall not be greater than 10 ft. nor less than 5 ft. Additional asphalt concrete shall be placed along the transverse edge at the end of each lane and along the exposed longitudinal edges between adjacent lanes, hand raked, and compacted to form temporary conforms. Kraft paper, or other approved bond breaker, may be placed under the conform tapers to facilitate the removal of the taper when paving operations resume.

Redlans Regular Meeting of 09-05-2023
839 of 1115

GC 54

302-5.6.1 General. - Add the following paragraph:

All asphalt concrete pavement abutting portland cement concrete gutters shall match and be flush with the gutter lip when finish rolling is complete.

302-5.6.2 – Density and Smoothness. – Delete and replace with the following:

The completed surfacing shall be thoroughly compacted, smooth and free from ruts, humps, depressions or irregularities. Any ridges, indentations or other objectionable marks left in the surface of the asphalt concrete shall be eliminated by rolling or other means. The use of any equipment that leaves humps, ridges, irregularities or other objectionable marks in the asphalt concrete shall be discontinued, and acceptable equipment shall be furnished by the Contractor.

The finished surface shall meet the following smoothness criteria:
 When a 12 foot long straightedge is laid on the finished surface parallel to the centerline of the roadway, the finished surface shall not vary from the edge of the straightedge more than 0.05 feet, except at changes in grade,
 When a 12 foot long straightedge is laid on the finished surface perpendicular to the centerline of the roadway and extends from edge to edge of a traffic lane, the finished surface shall not vary from the edge of the straightedge more than 0.05 feet, except at changes in grade.

If the top layer of pavement does not comply with the smoothness specifications shown, remove and replace the entire section or complete a grind and overlay of 1.5 inches or 3 times the aggregate size, whichever is greater. Grind and overlay will be considered as a repair method only when the thickness of the asphalt pavement section is greater than 1.5 inches following the required grinding. Corrected section shall be rectangular to the nearest pavement edge or lane line and to a crosswalk, concrete spandrel or other limits approved by the City. Do not begin corrective actions until the method and limit of correction is authorized by the City. If the tolerances cannot be achieved by the methods described above, the contractor must re-pave the street section, in kind, at their own expenses.

The compaction after rolling shall be a minimum of 91 percent and a maximum of 97 percent of the density obtained on samples compacted with the California Kneading Compactor per California Test 304. Cores will be taken randomly by the City for laboratory testing per California Test 308, Method A at a frequency of three per lot. A lot shall consist of a maximum of 3,000 square yards of asphalt concrete and will be identified in the field by the City. The cores will be averaged to determine the percent of maximum theoretical density, as determined by ASTM D- 2041, per lot to the nearest tenth of a percent.

Reduced payment factors for percent of maximum theoretical density will be per the following table, and will be applied to the entire lot sampled.

Reduced Payment Factors for Percent of Maximum Theoretical Density Asphalt Concrete
percent of maximum
theoretical density
Reduced payment
factor
Asphalt Concrete
percent of maximum
theoretical density
Reduced payment
factor

91.0 0.0000 97.0 0.0000
Redlans Regular Meeting of 09-05-2023
840 of 1115

GC 55

90.9 0.0125 97.1 0.0125

90.8 0.0250 97.2 0.0250

90.7 0.0375 97.3 0.0375

90.6 0.0500 97.4 0.0500

90.5 0.0625 97.5 0.0625

90.4 0.0750 97.6 0.0750

90.3 0.0875 97.7 0.0875

90.2 0.1000 97.8 0.1000

90.1 0.1125 97.9 0.1125

90.0 0.1250 98.0 0.1250

89.9 0.1375 98.1 0.1375

89.8 0.1500 98.2 0.1500

89.7 0.1625 98.3 0.1625

89.6 0.1750 98.4 0.1750

89.5 0.1875 98.5 0.1875

89.4 0.2000 98.6 0.2000

89.3 0.2125 98.7 0.2125

89.2 0.2250 98.8 0.2250

89.1 0.2375 98.9 0.2375

89.0 0.2500 99.0 0.2500
< 89.0 Remove and replace > 99.0 Remove and replace

In addition to the reduced payment factors below, all costs associated with the testing of the lot which resulted in values outside of the 91-97 percent range, will be withheld from the final payment due to the Contractor.

Following completion of the testing by the City, the core locations within the asphalt pavement shall be repaired by the Contractor.

302-5.6.3 Tracking. All areas receiving asphalt pavement shall be protected from tracking onto adjacent areas. Do not allow traffic on new asphalt pavement until its mid-depth temperature is below 140º Fahrenheit to minimize the tracking.

A rock dust blotter coat per Section 302-9.7 or a sand coat at a rate of 1-2 pounds per square yard shall be applied to the compacted surface for all areas where tracking is a concern. The application of tracking prevention measures shall be determined by the Contractor.

A haul route for all paving operations shall be reviewed and approved by the City prior to the start of any construction activity. No deviations from the approved haul route shall occur unless approved in writing from the City.

All tracking onto adjacent streets, striping or pavement markings shall be the responsibility of the Contractor. All striping and pavement markings shall be removed and replaced in kind by sandblasting. All tracking onto roadway surfaces may require the use of a street sweeper to the satisfaction of the City.

302-5.7 Joints. – Add the following:

Redlans Regular Meeting of 09-05-2023
841 of 1115

GC 56

Longitudinal joints shall be trimmed to a vertical face and to a neat line if the edges of the previously laid surfacing are, in the opinion of the Engineer, in such condition that the quality of the completed joint will be affected. Longitudinal and transverse joints shall be tested with a 12’ straightedge and shall be cut back as required to conform to the provisions in Subsection 302-5.6.2 Density and Smoothness for surface smoothness. Connections to existing surfacing shall be feathered to conform to the provisions for smoothness.

Longitudinal joints in the top layer shall correspond with the edges of proposed lane striping.

Longitudinal joints in all other layers shall be offset not less than 0.5' alternately each side of the edges of traffic lanes.

All feathered joints shall be sealed after rolling.

302-5.9 Measurement and Payment. – Add the following:

Reduced payment factors per 302-5.6.2 will be applied to the Contract Unit Price for lots with a Maximum Theoretical Density less than 91.0 and greater than 97.0 percent.

302-5.10 Hot Asphalt Leveling Course. Areas to receive the Hot Asphalt Concrete Leveling Course shall be determined and defined by the project manager and inspector, and identified to the Contractor in the field. Mix for hot Asphalt Concrete Leveling Course shall be 1/2 inch aggregate, C2, as defined in Section 203-6.4.3.

Areas to receive hot asphalt concrete leveling course shall be areas located near or adjacent to existing curbs and/or gutters that are potholed, or have the lip of gutter higher than the adjacent roadway. Potholes, large cracks, or ruts shall be filled to the surrounding grade elevation and compacted. Hot Asphalt Concrete Leveling Course shall be completed prior to the placement of Type II Slurry Seal, ARAM or resurfacing.

Prior to placement of asphalt concrete, the surface shall be cleaned and all debris and deleterious materials shall be removed. A tack coat meeting the material and application requirements of Section 302-5.4 Tack Coat, shall be applied prior to placement of hot mix asphalt concrete.

302-5.11 Asphalt Pavement Crack Sealing and Filling. Crack sealing shall only be performed as a repair method for conventional hot mix asphalt pavement (HMA) and not installed at project locations which will have asphalt rubber hot mix (ARHM) used as the overlay material. Crack sealing shall be performed after milling of existing asphalt surface and prior to any leveling course, if necessary.

Right after milling of existing asphalt and before crack sealing or filling, Contractor shall remove any and all weeds that are growing through cracks from the project street located within the pavement or growing between the concrete gutter and the pavement and spray a herbicide mixture of either Hyvar mixed with Roundup or Pramatol mixed with Roundup, or approved equal, at least seven (7) calendar days prior to paving. The herbicide mixture shall contain Blazon, or approved equal, a purple dye to easily confirm the herbicide has been applied. The work shall be approved by the Engineer or his representative prior to paving. Full compensation for plant removal and herbicide treatment shall be considered as included in the unit cost for paving.

Redlans Regular Meeting of 09-05-2023
842 of 1115

GC 57

The crack sealing material shall be a hot-applied asphalt (Crafco Polyflex or approved equivalent).

The crack sealing material must not be modified or diluted in any way. Pavement cracks larger than 1” wide shall be filled with the mixtures per Specification Section 203-6.4 Type E (Extra Fine).

A wand and nozzle type application shall be used to fill all cracks with crack sealing material.

Crack sealing material shall be applied in two applications with the possibility of additional applications to fill the crack within the allowable tolerance. The cracks must be filled to the surface and not overfilled or applied to the top of adjoining pavement or concrete surfaces. The cracks shall be squeegee immediately after the sealant has been applied to insure conformity with the pavement surface.

The crack sealing material shall then be allowed to penetrate and sink into the crack area for a minimum of one hour. Each crack must then have a second application of crack sealer material applied in the crack area only to within + 0.01' of the adjoining pavement surface. If the material is a cold-applied, polymer modified petroleum emulsion, sand will be applied over the crack sealing material after the second application, covering a minimum of 1 1/2 inches each side of the crack and not more than 3/4 inch higher than the top of the pavement. The contractor shall be responsible for the removal of all excess sand which shall be removed within three hours after being applied.

SECTION 303 - CONCRETE AND MASONRY CONSTRUCTION

303-1 CONCRETE STRUCTURES.

303-1.1 General. - Delete the first sentence of paragraph 1 and replace with the following:
“Concrete bridges, culverts, catch basins, retaining walls, abutments, piers, footings, foundations, drainage inlets, head walls, end walls, wing walls, junction structures, transition structures, manholes, and other similar types of portland cement concrete structures shall be constructed to the lines and grades in conformity with the Plans and Specifications.

303-5 CONCRETE CURBS, WALKS, GUTTERS, CROSS GUTTERS, ALLEY INTERSECTIONS, ACCESS RAMPS, AND DRIVEWAYS.

303-5.1.1 General. - Replace the last paragraph with the following:

No PCC shall be ordered and/or placed until the forms and subgrade have been inspected and approved by the Engineer in the field.

All pull boxes, water meter boxes, and water valve covers shall be adjusted to proposed finish grade and approved by the Engineer in the field prior to placement of the PCC.

The Contractor shall barricade and protect placed PCC from all damage, marks, mars, and/or graffiti. Any PCC damaged, defaced, discolored, or defective shall be replaced at the Contractor's expense.

When removals of curb and/or sidewalk are located at curb return, the Contractor shall install access ramps. The Contractor is to construct all access ramps in accordance with American Redlans Regular Meeting of 09-05-2023
843 of 1115

GC 58

Disability Act (ADA) Standards/California Code of Regulations Title 24 – Accessibility Regulations. If the ramps constructed by the Contractor are found to be in non-compliance with ADA Standards, the Contractor will be required to remove and replace the ramps to ADA Standards at the Contractor's expense.

303-5.1.2 Drainage Outlets Through Curb. - Add the following paragraph:

Coring shall be required for all drains through existing curbs.

303-5.1.3 Driveway Entrances. – Replace the last paragraph with the following:

Driveway approaches where required, shall be 150 mm (6") thick for single-family residential area, and 200 mm (8") thick for commercial driveway approaches.

303-5.1.4 Walk. The back of sidewalk shall be 2 inches from the street Right-of-Way line unless otherwise specified by the Engineer.

Included in the price of sidewalk construction are retaining curbs. Retaining curbs are needed to retain soils from sloughing and eroding onto the finished sidewalk surface, as a result of grade differentials from existing ground surface to proposed sidewalk surface. Retaining curbs shall be installed when the finished surface is lower than the surrounding grade by 3 inches vertically within 6 inches horizontally. If the vertical difference in elevation is less than 3 inches, the surrounding grade shall be sloped, maximum 2:1 slope, to match the finished elevation. The height of the retaining curb shall be to the height of the existing grade it is retaining. Retaining curbs shall be located within the City’s right-of-way at all times.

303-5.1.5 Access Ramps. Construction of curb ramps shall conform to the Type and Case appropriate for the condition, as specified on the plans and as shown within the 2012 Standard Plans for Public Works Construction, Plan 111-5. The Contractor shall be responsible to layout the proposed access ramp to comply with the maximum slope indicated on the plans or Standard Plan 111-5. The maximum slope for the ramp shall not be exceeded unless otherwise approved in writing by the Engineer. The Contractor shall remove and replace access ramps deemed non- compliant with the plans or Standard Plan 111-5.

For proposed locations adjacent to a cross gutter spandrel, sawcuts along the radius of the curb will not be allowed. The spandrel shall be replaced from expansion joint to expansion joint to the extents of the curb removal. For proposed locations adjacent to curb and gutter, sawcuts along the flowline of the curb will not be allowed. The entire curb and gutter shall be replaced from expansion joint to expansion joint as required. Sawcuts at locations other than the expansion joint will not be allowed unless approved by the Engineer. Curb cuts of the existing curb will not be permitted for installation of proposed ramp. Any deviation from these requirements will result in rejection of all work at this location and shall not be included in progress payment requests until corrected, per direction from the Engineer.

The Contractor shall verify the extents of sawcut and removal for each access ramp taking into account the maximum slope and transition area required. It shall be the Contractor’s responsibility to identify required removal limits, set concrete forms and verify maximum slopes are not exceeded. The Engineer shall be present to verify the concrete forms prior to the placement of the concrete at each location, however this does not alleviate the responsibility of the accuracy of forms or slopes of the access ramp from the Contractor.

Redlans Regular Meeting of 09-05-2023
844 of 1115

GC 59

Included in the price of access ramps are retaining curbs. Retaining curbs are needed to retain soils from sloughing and eroding onto the finished ramp surface, as a result of grade differentials from existing ground surface to proposed ramp surface. Retaining curbs shall be installed when the finished surface is lower than the surrounding grade by 3 inches vertically within 6 inches horizontally. If the vertical difference in elevation is less than 3 inches, the surrounding grade shall be sloped, maximum 2:1 slope, to match the finished elevation. The height of the retaining curb shall be to the height of the existing grade it is retaining. Retaining curbs shall be located within the City’s right-of-way at all times.

Access Ramps shall have truncated domes installed in accordance with standard plans and specifications. Truncated domes on new access ramps shall be Armor-Tile, Cast in Place System, or approved equal. Truncated domes installed on existing surfaces shall be Safety Sted TD, or approved equal. Truncated dome panels shall be 36”x48”, inline configuration, with a spacing of

2.35” on center, and Federal Yellow in color.

The access ramp work shall include all related adjustments of pull boxes, pull box covers, signs, and protection of any underground utilities within the work area. The removal and replacement of up to 5 linear feet of sidewalk on each side of the access ramp shall be included within the cost of the access ramp. The removal and replacement of the sidewalk will allow for transition from the top of ramp to adjacent sidewalk and will be utilized as necessary.

303-5.4.3 Weakened Plane Joints, (a) General. - Add the following paragraph:

All weakened plane joints shall be spaced at a maximum of 3.05 m (10') feet for curbs, gutters, and sidewalks. Scoring lines shall conform to those prevailing in the area and be uniform in spacing.

303-5.5.2 Curb. - Replace the first paragraph with the following:

PCC for curb and gutter shall be placed within three working days from removal of the existing PCC curb and gutter. The curb and gutter surface shall not vary more than 3 mm (0.01') from a 3 m (10') straightedge except at the grade changes. Prior to the removal of the forms, the surface shall be finished true to grade by means of a straightedge float of not less than 3 m (10') in length, and operated longitudinally over the surface of the concrete. Form clamps shall be constructed so as not to interfere with the operation of the float. The form on the front of the curbs shall not be removed less than one (1) hour, nor more than six (6) hours after the concrete has been placed. In no event shall forms be removed while the concrete is sufficiently plastic to slump. The top and face of the finished curb shall be true and straight, and top surface of curbs shall be of uniform width, free from humps, sags, blemishes, or other irregularities.

303-5.5.3 Walk. - Add the following paragraphs:

The sidewalk surface shall not vary more than 5 mm (0.02') from the 3m (10') straightedge except at grade changes, and the finished surface shall be free from humps, sags, blemishes or other irregularities. All sidewalks shall be a minimum of 100 mm (4") thick, except at driveways where the sidewalks shall be a minimum of 150 mm (6") thick for single family residential areas and 200 mm (8") thick for all other areas.

303-5.6 Curing. - Add the following paragraph:

Redlans Regular Meeting of 09-05-2023
845 of 1115

GC 60

Curing compound shall be translucent with red fugitive dye, Type 1, in accordance with Section 201-4 Concrete Curing Compound, of the Standard Specifications.

303-5.7 Repairs and Replacements. - Add the following paragraphs:

In order to minimize vandalism damage to the finished PCC surfaces, the Contractor shall plan his work so that no PCC is poured after 1:00 p.m., unless otherwise authorized by the Engineer in the field.

The Contractor shall barricade and protect placed Portland Cement Concrete from all damages, marks, mars, and/or graffiti. Any Portland Cement Concrete damaged, defaced, discolored, or defective shall be replaced to the satisfaction of the Engineer at the Contractor's expense, and no additional time will be allowed.

Grading, patching, or other remedies to correct the situation will not be accepted unless in the opinion of the Engineer the vandalized area is so small that it does not warrant replacement.

Concrete replacement areas shall be from score mark or control joint to score mark or control joint, and full width of the sidewalk. All replacement areas shall be saw cut.

303-5.8 Backfilling and Cleanup. - Add the following paragraph:

A minimum of 300mm (12”) wide full depth asphalt concrete pavement repair patch and an 450mm (18”) wide 1-1/2” deep grind outside of the trench width is required when cross gutter, spandrel, driveways, curb and gutter is placed adjacent to existing asphalt concrete pavement. The asphalt concrete pavement repair patch shall be placed within two (2) working days after the cross gutters, spandrels, driveways, curb and gutter are replaced. The asphalt concrete pavement shall be sawcut. All work shall be in accordance with the General Permit Conditions and Trench Specifications, latest edition.

SECTION 304 - METAL FABRICATION AND CONSTRUCTION

304-3 CHAIN LINK FENCE.

304-3.4 Measurement and Payment. - Delete paragraph 1 and replace with:

Chain link fence will be measured along the horizontal projection line of the completed fence, deducting the widths of gates and openings.

SECTION 306 - UNDERGROUND CONDUIT CONSTRUCTION

306-1 OPEN TRENCH OPERATIONS.

306-1.1.3 Maximum and Minimum Width of Trench. - Amend as follows:

Add the following sentence to paragraph 4:

If additional payment is to be requested, the Contractor shall make written request and receive approval from the Engineer before any excavation is begun.

Add the following sentence to paragraph 5:

Redlans Regular Meeting of 09-05-2023
846 of 1115

GC 61

If additional payment is to be requested, the Contractor shall make written request and receive approval from the Engineer before any excavation is begun.

306-1.1.6 Bracing Excavations. - Add the following paragraphs:

The Contractor shall submit a bracing plan, prepared by a registered engineer authorized to perform this type of work, as allowed by state statute. The bracing plan shall be stamped and signed by the engineer, and submitted as specified.

The bracing plan shall be submitted for review and acceptance by the Engineer prior to the start of any excavation work requiring bracing and shall include plate data as specified in 306-1.1.7.

306-1.1.7 Plate Installation. - Add this subsection:

When plating across an open trench is required or necessary due to the Contractor’s operations, the trench shall be adequately and properly braced to stabilize trench edges to support a minimum H20 load rating. Plates shall be installed with a minimum clearance from the trench edge on each side as shown on the bracing plan. The maximum plate span across a trench shall be shown on the bracing plan.

Plate contact area shall be cold milled to a depth equal to the plate thickness, allowing a smooth transition from plate surface to existing roadway pavement surface. The cold mill area shall not exceed the plate edge by more than 1 inch (25 mm) maximum.

All costs for plate use, including cold milling, shall be borne by the Contractor, and no additional compensation shall be made therefore.

306-1.2 Installation of Pipe. - Add the following paragraphs:

Before installation of pipelines, the Contractor shall have constructed curb and gutter, and cut street to the appropriate subgrade depth. This requirement shall be waived for the installation of storm drain and sewer piping, which shall be installed prior to the curb and gutter construction.

“Pipelines” as referred to in the previous paragraph shall include potable water mains, non-potable water mains, irrigation mains, electrical conduits, telephone conduits, television conduits, gas mains, and any other underground pipeline or conduit, except storm drain and sewer. This shall include all laterals, services, and other appurtenances for the “pipelines”.

306-1.2.1.2 Bedding for Narrow Trenches. - Amend paragraph 1 as follows:
“Narrow trenches are defined as 12 inches (305 mm) or less in width.”

306-1.2.2 Pipe Laying. - Add the following paragraph:

Concrete collars, plugs, anchors, thrust blocks, stabilizers and bulkheads shall be included as work under this item.

306-1.3.1 General. - Amend the following:

Amend paragraph 4 as follows:

Redlans Regular Meeting of 09-05-2023
847 of 1115

GC 62

“When the depth of cover of the top pipe or cable is less than 30 inches (760mm), the top 24 inches (600mm) of backfill, measured from the surface, shall be compacted to 95 percent relative compaction.”

Add the following paragraph:

All trench backfill shall be compacted to a minimum 95 percent relative compaction, unless otherwise specified by the Engineer.

306-1.5.1 Temporary Resurfacing. - Delete the last 2 paragraphs, replace with the following:

The price bid for underground conduit construction shall include full compensation for furnishing, placing, maintaining, removing and disposing of temporary resurfacing materials.

306-1.6 Basis of Payment for Open Trench Installations. - Amend the following:

Amend the first sentence of paragraph 1:
“Pipe and conduit shall be measured along the horizontal axis between the ends as laid and shall include the actual pipe in place and shall not include the inside dimensions of structures.”

Amend the first sentence of paragraph 2:
“The Contract Unit Price per linear foot (meter) for pipe and conduit in place shall be considered full compensation for all wyes, tees, bends, monolithic catch basin connections, concrete collars, plugs, bulkheads and specials shown on the Plans; the removal of interfering portions of existing sewers, storm drains, and improvements; the closing or removing of abandoned conduit and structures; the excavations of the trench; the control of ground and surface waters; the preparation of subgrade; placing and joining pipe; backfilling the trench; permanent resurfacing; and all other work (excluding temporary resurfacing) necessary to install the pipe or conduit, complete in place.”

Add the following paragraph:

In all items involving pipelines, 90 percent of the pipe item unit price will be included in progress estimates when all work except testing and clean up has been completed. An additional 5 percent will be included in progress estimates when a section of pipeline has satisfactorily met all test requirements and the remaining 5 percent will be included in progress estimates when clean up of a section of pipeline, including permanent trench resurfacing, has been completed.

306-2 JACKING OPERATIONS.

306-2.6 Payment. - Add the following sentence to paragraph 1:

If rocks, boulders, or debris of any type are encountered during operations, all removal, repair and correction costs including delay time and costs shall be borne by the Contractor and no additional compensations shall be made therefore.

SECTION 307 - STREET LIGHTING AND TRAFFIC SIGNAL SYSTEMS

307-1 GENERAL. - Amend the following:

Redlans Regular Meeting of 09-05-2023
848 of 1115

GC 63

Add the following paragraphs:

Any person performing electrical work subject to the certification requirements of Labor Code sections 3099 et seq. shall be certified, as required by law, prior to, and throughout, the performance of such work.

Add the following paragraphs:

Inspection shall be required at the following stages: (1) prior to pouring foundation concrete, excavation dimensions shall be verified; (2) prior to placement of a standard, foundation and anchor bolts shall be verified; and (3) prior to pouring the cap, connections, ground bond and luminary shall be verified.

There shall be no structure(s) encased in foundation concrete. Foundation concrete shall be held 4 inches to 5 inches (102 mm to 127 mm) below top of curb grade.

Anchor bolts shall be held by a template with the top of each bolt a maximum 1/2 inch (13 mm) below top of curb or a maximum ½ inch (13 mm) below top of sidewalk if set behind sidewalk.

The top of foundation concrete shall be cleaned of all foreign objects before foundation cap is poured. Standard shall be plumb and tightened prior to foundation cap placement.

Foundation cap shall be formed to a minimum dimension of 32 inches (813 mm) wide, centered to the light standard and from the back of curb to a point 9 inches (229 mm) beyond the back of the light standard. The cap slope shall be equivalent to adjacent sidewalk or shall be 2 percent from the top of curb in parkway. Cap shall be poured to encase anchor bolts and flow under street light standard so that the pole butt is encased.

307-8 FOUNDATIONS, FOUNDATION CAPS AND SLABS.

307-8.2 Foundations. - Amend the following:

Amend the first sentence of paragraph 2 as follows:
“Foundations shall cure for 72 hours before erecting standards and 72 hours before erecting mast arms.”

Amend the second sentence of paragraph 2 as follows:
“Pile foundations shall cure for 72 hours before erecting standards and 7 days before erecting mast arms.”

Add the following paragraphs:

Minimum foundation dimensions shall be 32 inches x 32 inches x 46 inches (813 mm x 813 mm x 1,168 mm) or when bored with an auger shall be 32 inches x 60 inches (813 mm x 1,524 mm).

Foundation and cap concrete shall be as specified in Section 201-1. Cap concrete shall have a light broom finish.

Redlans Regular Meeting of 09-05-2023
849 of 1115

GC 64

There shall be an 8 foot x 5/8 inch (2.4 m x 16 mm) copper-clad ground rod placed in the center of the base and extended 3 inches (76 mm) above curb level with a ground clamp installed at the top.

307-8.3 Foundation Caps. - Amend the first sentence of paragraph 1 as follows:
“Foundation caps shall be the same color, finish, and material as the adjacent sidewalk, and be a minimum thickness of 4 inches (102mm) thick or unless otherwise specified in the Special Provisions.”

307-8.4 Concrete Slabs. - Amend the first sentence of paragraph 1 as follows:
“Wherever the edge of a concrete foundation extends within 18 inches (450mm) of any existing concrete improvement, a concrete slab with a minimum thickness of 4 inches (102mm) or as specified in the Special Provisions shall be extended to meet the existing improvement.”

307-10 STANDARDS, PEDESTALS AND MAST ARMS. - Add the following paragraphs:

Standard shall be set square with the street or as directed by the Engineer. Standard shall be centered 24 inches (610 mm) behind curb face or as shown on the plan.

The access door at the base of the standard shall be a minimum ½ inch (13 mm) to a maximum 2 inches (51 mm) above the top of adjacent curb or sidewalk.

Anchor bolts shall have no threads exposed above top of nut when final tightening is completed.

307-11 PULL BOXES. - Amend the following:

Amend (b) of paragraph 3 as follows:
“150 feet for street lighting systems, and”

Add the following sentence to paragraph 4:

Conduit entering a pull box shall extend a minimum 3 inches (76 mm) above the rock base.

Add the following paragraph:

Double depth pull boxes shall be grouted on the inside, as specified. Pull boxes shall be located as shown on the plans and installed at either sidewalk or curb grade.

307-12 CONDUIT. - Amend the following:

Amend the first sentence of paragraph 6 as follows:
“Detector, telephone interconnect, or street lighting conduit shall be 1-1/4 inch (32 mm) nominal size unless otherwise specified in the Special Provisions.”

Delete the second sentence of paragraph 6 and replace with the following:
“Direct interconnect and utility service conduit shall be 2 inch (51 mm) nominal size unless otherwise specified or required by agency or utility.”

Add the following sentence to paragraph 6:

Redlans Regular Meeting of 09-05-2023
850 of 1115

GC 65

Traffic Signal conduit size shall be as specified in Section 209-2.3.

Amend the second sentence of paragraph 2 as follows:
“Conduit placed behind a curb shall not be less than 18 inches (457 mm) nor more than 36 inches (900mm) below the top of the curb.”

Add the following sentence to paragraph 9:

There shall be no more than 2 conduits in each foundation.

Amend the first sentence of paragraph 7 as follows:
“ not be less than 3 inches (76 mm) above the bottom of the box.”

Add the following paragraph:

Contractor shall be required to install traffic signal interconnect conduit, with pull rope, between new traffic signal controller and any existing traffic signal controller located within 1,500 feet (457 m).

307-13 WIRES, CONDUCTORS AND CABLES.

307-13.1 General. - Add the following paragraph:

All conductors shall be new and in their original packaging.

307-14 SERVICES.

307-14.1 General. - Add the following paragraph:

When a service pedestal is installed in an unpaved area, a slab shall be constructed per Section 307-4.11.

307-17 TRAFFIC SIGNAL CONSTRUCTION.

307-17.2.2 Controller Cabinet Wiring Diagrams. - Amend the following:

Add the following sentence to paragraph 1:

Traffic signal Phase 4 shall face north, for southbound traffic.

Add the following paragraphs:

A representative from the traffic controller manufacturer shall be onsite at the time of signal activation and shall install timing and coordination provided by the Engineer.

All software and current upgrades, at the time of installation, for the controller and conflict monitor shall be provided to the City.

307-17.3 Pull Box Covers. - Amend the following:

Amend the first sentence as follows:

Redlans Regular Meeting of 09-05-2023
851 of 1115

GC 66

“Pull box covers to be installed in traffic signal systems or combined traffic signal and multiple circuit street lighting systems conforming to 209-4.2.3, shall conform to 209-3.7 and shall be inscribed “STREET LIGHTING”.”

Add the following sentence to paragraph 1:

Lid shall have two 1 inch (10 mm) brass bolts for fastening.

307-17.5.1 General. - Add the following paragraph:

Tape color codes for traffic signal phases shall be as follows: 0 - black; 1 - brown; 2 - red; 3 - orange; 4 - yellow; 5 - green; 6 - blue; 7 - violet; 8 - gray; 9 - white.

All cables shall be phase taped to match signal phasing. Cable splicing shall not be allowed in pull boxes.

307-17.6.1 General. - Amend the following:

Delete the first two sentences of paragraph 2 and replace with the following:

All signal and arrow indications shall be 12 inches (305 mm).

Add the following paragraph:

Traffic heads, pedestrian heads and shields shall be aluminum. Heads, hardware, etc. shall be flat black. Vehicle faces shall be 12 inches (305 mm). All red, yellow, green and “hand man” indicators shall be LED type. Pedestrian lenses shall be mechanically connected to the visor “egg crate.” Silicone glue shall not be allowed. Lamp sockets shall not be plastic and shall not be held to the lens by use of a clip. The Contractor shall furnish per traffic signal installed, one of each color and type, spare vehicle and pedestrian LED’s to the City.

307-17.7.3.1 General. - Add the following paragraphs:

If allowed by the Engineer, approach and advance loops shall each have a lead-in cable. Cables shall have the appropriate color phase tape and advance loop cables shall have two bands of the appropriate color phase tape. Loops shall be in series. Advance loops shall be connected to the top detector.

Loops are to be installed as shown and/or dimensioned on the plans. When lane width is greater than 15 feet (4.6 m), excluding parking lane, a second loop shall be installed perpendicular to each loop shown on the plans for said lane. Loops shall be installed in the center of each lane, or equally spaced for lanes greater than 15 feet (4.6 m) in width.

Loop detector wires may be spliced in pull boxes if necessary. Permanent splices shall be crimped and soldered. Contractor may substitute shrink tubing, as specified in Section 209-5.3.1 of these specifications, in lieu of crimping and soldering. Wire nuts may be used for temporary connections only.

307-17.8.2 Pedestrian Push Buttons. - Add the following sentence:

Pedestrian push buttons shall be de-isolated with no cabinet logic ground leaving the controller cabinet.

Redlans Regular Meeting of 09-05-2023
852 of 1115

GC 67

307-17.10 Controller Foundation. Traffic signal controller foundations shall extend a minimum 18 inches (457 mm) and a maximum of 20 inches (508 mm) above finish grade, and be sized as necessary to fit the controller cabinet with a 1 inch (25 mm) lip, including the 1/2 inch (13 mm) chamfer, beyond outside cabinet dimensions. Cabinet shall be sealed on the concrete foundation with a silicon bead placed under the cabinet edge as it is set in place.

307-17.11 Reflectorized Street Name Sign Placement and Mounting. Top of sign frame shall have two free swinging mounting brackets manufactured from aluminum, bronze and stainless steel, as specified. 8 inch (203 mm) stainless steel bolts shall allow for fine adjustment.

Dampening springs shall be used. Each swing bracket shall be adjusted vertically for leveling of the sign to fit mast arm angles. The bracket assembly shall permit the S.S.G. unit to swing perpendicular to the support hardware.

Hardware used to attach the sign and swing assembly to the mast arm shall by “Y-brackets,” “EZ- L brackets” or approved equal.

EZ-L brackets shall be a three piece telescoping design to adjust from 12 inches (305 mm) to 28 inches (711 mm) in 1 inch (25 mm) increments without additional adapters. The outside tube shall be 1-3/4 inches x 1-1/2 inches (44 mm x 38 mm) with a wall thickness of 5/32 inch (4 mm). The middle tube shall be 1-1/2 inches x 1-1/4 inches (38 mm x 32 mm) with wall thickness of 5/32 inch (4 mm) and one wall having a thickness of  inch (10 mm) and threaded for two  inch (10 mm) stainless steel holding bolts with external tooth lock washers. The inside tubes shall fit firmly within each other and slide smoothly. Safety tabs shall be located on the ends of each tube and will not allow the tubes to completely separate from each other during shipping and installation procedures. When installing EZ-L bracket, the middle tube should be extended first, then the inside tube.

The Y-bracket shall be one piece solid aluminum extrusion construction. There shall be four slots in the bracket to accommodate two 3/4 inch (19 mm) wide stainless steel straps side by side.

Strapping shall have a minimum thickness of 0.020 inches (½ mm). The EZ-L bracket shall attach to the Y-bracket with a ½ inch (13 mm) stainless steel bolt, lock washer and ny-lock nut.

When installation of the S.S.G. sign to the mast arm is complete, the S.S.G. sign shall swing freely in both directions when moved by the installer without any binding or hindrance being felt, allowing the sign to move freely under normal weather conditions.

307-18 TESTING.

307-18.1 General. - Add the following paragraph:

Luminares shall be in operation for 5 days prior to final acceptance.

SECTION 314 - TRAFFIC STRIPING, CURB AND PAVEMENT

MARKINGS, AND PAVEMENT MARKERS

314-1 GENERAL. - Add the following paragraphs:

Redlans Regular Meeting of 09-05-2023
853 of 1115

GC 68

To insure the protection of storm drain inlets, Best Management Practices (BMPs) shall be employed during all striping operations. Refer to Section 7-8.6.

Each storm drain catch basin or storm drain inlet box shall be marked “NO DUMPING - FLOWS TO CREEK.” Two coats of paint are required. Stencil shall match City’s stencil. Paint and painting shall comply with the specifications.

All street resurfacing work shall include installing fire hydrant pavement markers at all fire hydrant location, whether the pavement markers were existing or not. The pavement markers shall be Type I – Two-Way Blue Retroreflective per Section 214-6 of the Specifications and installed per City’s detail drawing No. 102-0. All work associated with the installation of all new, or replacement of existing, fire hydrant pavement markers shall be included as noted within the specifications.

314-4 APPLICATION OF TRAFFIC STRIPING AND CURB AND PAVEMENT MARKINGS.

314-4.1 General. – Add the following paragraphs:

During construction, if traffic legends or lane striping are removed or paved-over for any reason, they shall be replaced immediately with temporary traffic legends or lane striping as directed by the City, and the Contractor shall place permanent traffic legends or lane striping at the end of the job or on completion of final paving. When permanent items are placed, they shall be complete markings, legends, or striping i.e.: if limit lines are disturbed, they shall be replaced to centerline or from curb to curb, whichever was existing; if a letter in a word is removed or covered, the entire word shall be replaced; and lane striping shall extend 75 feet beyond construction limits. All replacement markings, legends, or striping required to be replaced beyond the contract limits shown shall be at the cost of the Contractor and shall meet City standards. If existing striping or legends are to be removed on existing surfaces, they shall be sandblasted. Painting over striping or legends in lieu of removal will not be permitted. Pavement striping shall comply with the applicable provisions of Sections 214 and 314 of the Standard Specifications.

Where side streets with existing striping, markings and markers are encountered, striping, markings and markers shall be repainted and replaced for a minimum distance of 15 m (50 feet) from the crosswalk, stop bar or limit line.

314-4.2 Control of Alignment and Layout.

314-4.2.1 General. - Delete and replace with the following:

The Contractor will be responsible for all layout of all striping. All striping, markings and markers shall be reinstalled in their existing locations unless otherwise shown on the plans. The Contractor shall be responsible to take appropriate measures and record the existing locations.

The Contractor shall verify all dimensions in the field prior to installation of pavement striping/marking layout (Cat-Track). Should field measurements differ from the plan, the Contractor shall immediately notify City staff. No Cat-Track marks shall be placed until discrepancies are resolved.

Redlans Regular Meeting of 09-05-2023
854 of 1115

GC 69

Cat-Track must be approved by City staff prior to the installation of permanent pavement striping/marking. Contractor shall notify City staff a minimum of 24 hours prior to installation of permanent pavement striping/marking to allow for inspection and approval. If approval of Cat- Track is not obtained by the Contractor, all work required to correct the striping/marking will be at the expense of the Contractor

Cat-Track marks shall be made in chalk. Paint for the purpose of Cat-Track is prohibited. If paint is used, the Contractor must remove the paint without damaging or visually deforming the pavement surface. If damage or visual deformity within the removal area occurs, in the opinion of City staff, the Contractor shall grind and overlay the entire segment with no additional compensation. The area of the grind and overlay shall be as required by City staff and shall be a minimum of 0.10’ thickness.

All visible Cat-Track markings after the installation of the permanent striping/marking shall be removed without damage or visual deformity to the pavement surface. Any damage or visual deformity to the pavement shall be remedied as noted above.

314-4.3.5 Application. - Amend the first sentence in paragraph 8 as follows:
“Glass beads shall be applied at a rate of 0.6 to 0.8 kg of beads per liter (5 to 7 pounds of beads per gallon).”

314-6 GREEN BIKE LANE. Green bike lanes shall be installed per plan and conform to the technical specifications included within the contract documents and shall be Streetbond CL or approved equal.

SECTION 400 - PROTECTION AND RESTORATION

400-1.1 General. The Contractor shall relocate, re-establish, repair or replace all existing improvements within the work limits or right-of-way which are not designated for removal (e.g., sprinkler systems, curbs, sidewalks, driveways, fences, walls, signs, utility installations, pavement, structures, etc.) which are damaged or removed as a result of its operations.

Relocations, re-establishments, repairs and replacements shall be at least equal to existing improvements and shall match them in finish and dimension.

All costs to the Contractor for protecting, removing, restoring, relocating, repairing, replacing or re- establishing existing improvements shall be included in the Bid.

The Contractor shall be responsible for the maintenance of the streets and roadways to be used by public and local traffic through and adjacent to the construction zone, from the date of "Notice to Proceed" until the date of acceptance of the completed construction improvements.

Street maintenance shall include filling of potholes, grading of subgrade and base, replacing signs, installing interim pavement striping and markers on the project streets and other side streets within the construction zone. Street maintenance shall also include sweeping and washing of streets, adjacent and connected to the construction zone on a weekly, or more frequent schedule, to prevent Redlans Regular Meeting of 09-05-2023
855 of 1115

GC 70

the accumulation of dust, dirt, gravel or other deleterious materials, all as necessary to maintain the construction roadways and adjacent streets in a safe, clean and drivable condition for use by public and local traffic.

Upon request from the City for information pertaining to a claim against the contractor, contractor shall provide a written/email response, including all requested information, within 14 calendar days of City’s request. If a response with all requested information is not provided to the City within 14 calendar days, a penalty of $500 per calendar day will be assessed to the Contractor by the City.

Redlans Regular Meeting of 09-05-2023
856 of 1115

SPECIAL CONDITIONS (SC)
Redlans Regular Meeting of 09-05-2023
857 of 1115

THIS PAGE INTENTIONALLY LEFT BLANK
Redlans Regular Meeting of 09-05-2023
858 of 1115

SC 1

SPECIAL CONDITIONS

SECTION 1 – CONSTRUCTION DETAILS

1.01 SPECIFICATIONS. The Standard Specifications, State of California, Department of Transportation, 2018 Edition (Standard Specifications), are modified herein and comprise the Standard Specifications. For convenience, the section and subsection numbering system used in these modifications correspond to those used in the Standard Specifications. Unless specifically deleted or modified herein, all requirements of the Standard Specifications shall prevail.

1.02 DESCRIPTION. The work to be done shall be performed or executed in accordance with these Special Conditions, the General Conditions, the Caltrans Standard Specifications 2018 Edition and latest revisions, the Greenbook Specifications 2021 Edition, and the State of California Department of Transportation Standard Plans 2018 Edition. Under the terms of the Contract, the work shall consist of furnishing all labor, materials, tools, equipment, appurtenances and incidentals for the installation of new enhanced crosswalk systems and related work in accordance with the Plans and Specifications for HSIP Cycle 9 Orange Blossom Trail Phase 3 Crossings , City Project No. 47033, Federal Project No. HSIPL 5083(024).

1.03 FEDERAL LOBBYING RESTRICTIONS . Section 1352, Title 1352, Title 31, United States Code prohibits Federal funds from being expended by the recipient or any lower tier sub- recipient of a Federal-aid contract to pay for any person for influencing or attempting to influence a Federal agency or Congress in connection with the awarding of any Federal-aid contract, the making of any Federal grant or loan, or the entering into of any cooperative agreement.

If any funds other than Federal funds have been paid for the same purposes in connection with this Federal-aid contract, the recipient shall submit an executed certification and, if required, submit a completed disclosure form as part of the bid documents.

A certification for Federal-aid contracts regarding payment of funds to lobby Congress or a Federal agency is included in the Proposal. Standard Form - LLL, “Disclosure of Lobbying Activities,” with instructions for completion of the Standard Form is also included in the Proposal. Signing the Proposal shall constitute signature of the Certification.

The above referenced certification and disclosure of lobbying activities shall be included in each subcontract and any lower-tier contracts exceeding $100,000. All disclosure forms, but not certifications, shall be forwarded from tier to tier until received by the Engineer.

The Contractor, subcontractors and any lower-tier contractors shall file a disclosure form at the end of each calendar quarter in which there occurs any event that requires disclosure or that materially affects the accuracy of the information contained in any disclosure form previously filed by the Contractor, subcontractors and any lower-tier contractors. An event that materially affects the accuracy of the information reported includes:

1. A cumulative increase if $25,000 or more in the amount paid or expected to be paid for influencing or attempting to influence a covered Federal action; or

2. A change in the person(s) or individual(s) influencing or attempting to influence a covered Redlans Regular Meeting of 09-05-2023
859 of 1115

SC 2

Federal action; or

3. A change in the officer(s), employees(s), or Member(s) contacted to influence or attempt to influence a covered Federal Action.

1.04 DISADVANTAGED BUSINESS ENTERPRISE (DBE) REQUIREMENTS:

Under 49 CFR 26.13(b):

The contractor, subrecipient or subcontractor shall not discriminate on the basis of race, color, national origin, or sex in the performance of this contract. The contractor shall carry out applicable requirements of 49 CFR part 26 in the award and administration of DOT-assisted contracts. Failure by the contractor to carry out these requirements is a material breach of this contract, which may result in the termination of this contract or such other remedy as the recipient deems appropriate.

Take necessary and reasonable steps to ensure that DBEs have opportunity to participate in the contract (49 CFR 26).

To ensure equal participation of DBEs provided in 49 CFR 26.5, the Agency shows a goal for DBEs.

Make work available to DBEs and select work parts consistent with available DBE subcontractors and suppliers.

Meet the DBE goal shown elsewhere in these special provisions or demonstrate that you made adequate good faith efforts to meet this goal.

It is your responsibility to verify that the DBE firm is certified as DBE at date of bid opening. For a list of DBEs certified by the California Unified Certification Program, go to:
http://www.dot.ca.gov/hq/bep/find_certified.htm.

All DBE participation will count toward the California Department of Transportation’s federally mandated statewide overall DBE goal.

Credit for materials or supplies you purchase from DBEs counts towards the goal in the following manner:

• 100 percent counts if the materials or supplies are obtained from a DBE manufacturer. • 60 percent counts if the materials or supplies are obtained from a DBE regular dealer. • Only fees, commissions, and charges for assistance in the procurement and delivery of materials or supplies count if obtained from a DBE that is neither a manufacturer nor regular dealer. 49 CFR 26.55 defines "manufacturer" and "regular dealer."

You receive credit towards the goal if you employ a DBE trucking company that performs a commercially useful function as defined in 49 CFR 26.55(d)(1) through (4) and (6).

a. DBE Commitment Submittal
Redlans Regular Meeting of 09-05-2023
860 of 1115

SC 3

Submit the Exhibit 15-G Local Agency Bidder DBE Commitment (Construction Contracts) form, included in Appendix D. If the form is not submitted with the bid, remove the form from the Bid book before submitting your bid.

If the DBE Commitment form is not submitted with the bid, the apparent low bidder, the 2nd low bidder, and the 3rd low bidder must complete and submit the DBE Commitment form to the Agency. DBE Commitment form must be received by the Agency no later than 4:00 p.m. on the 4th business day after bid opening.

Other bidders do not need to submit the DBE Commitment form unless the Agency requests it. If the Agency requests you to submit a DBE Commitment form, submit the completed form within 4 business days of the request.

Submit written confirmation from each DBE stating that it is participating in the contract. Include confirmation with the DBE Commitment form. A copy of a DBE's quote will serve as written confirmation that the DBE is participating in the contract.

If you do not submit the DBE Commitment from within the specified time, the Agency will find your bid nonresponsive.

b. Good Faith Efforts Submittal

If you have not met the DBE goal, complete and submit the DBE Information - Good Faith Efforts, Exhibit 15-H, form with the bid showing that you made adequate good faith efforts to meet the goal. Only good faith efforts directed towards obtaining participation by DBEs will be considered.

If good faith efforts documentation is not submitted with the bid, it must be received by the Agency no later than 4:00 p.m. on the 4th business day after bid opening.

If your DBE Commitment form shows that you have met the DBE goal or if you are required to submit the DBE Commitment form, you must also submit good faith efforts documentation within the specified time to protect your eligibility for award of the contract in the event the Agency finds that the DBE goal has not been met.

Good faith efforts documentation must include the following information and supporting documents, as necessary

1. Items of work you have made available to DBE firms. Identify those items of work you might otherwise perform with your own forces and those items that have been broken down into economically feasible units to facilitate DBE participation. For each item listed, show the dollar value and percentage of the total contract. It is your responsibility to demonstrate that sufficient work to meet the goal was made available to DBE firms.

2. Names of certified DBEs and dates on which they were solicited to bid on the project.

Include the items of work offered. Describe the methods used for following up initial solicitations to determine with certainty if the DBEs were interested, and the dates of the Redlans Regular Meeting of 09-05-2023
861 of 1115

SC 4

follow-up. Attach supporting documents such as copies of letters, memos, facsimiles sent, telephone logs, telephone billing statements, and other evidence of solicitation. You are reminded to solicit certified DBEs through all reasonable and available means and provide sufficient time to allow DBEs to respond.

3. Name of selected firm and its status as a DBE for each item of work made available. Include name, address, and telephone number of each DBE that provided a quote and their price quote. If the firm selected for the item is not a DBE, provide the reasons for the selection.

4. Name and date of each publication in which you requested DBE participation for the project. Attach copies of the published advertisements.

5. Names of agencies and dates on which they were contacted to provide assistance in contacting, recruiting, and using DBE firms. If the agencies were contacted in writing, provide copies of supporting documents.

6. List of efforts made to provide interested DBEs with adequate information about the plans, specifications, and requirements of the contract to assist them in responding to a solicitation. If you have provided information, identify the name of the DBE assisted, the nature of the information provided, and date of contact. Provide copies of supporting documents, as appropriate.

7. List of efforts made to assist interested DBEs in obtaining bonding, lines of credit, insurance, necessary equipment, supplies, and materials, excluding supplies and equipment that the DBE subcontractor purchases or leases from the prime contractor or its affiliate. If such assistance is provided by you, identify the name of the DBE assisted, nature of the assistance offered, and date assistance was provided. Provide copies of supporting documents, as appropriate.

8. Any additional data to support demonstration of good faith efforts.

The Agency may consider DBE commitments of the 2nd and 3rd bidders when determining whether the low bidder made good faith efforts to meet the DBE goal.

c. Exhibit 15-G - Local Agency Bidder DBE Information (Construction Contracts)

Complete and sign Exhibit 15-G Local Agency Bidder DBE Commitment (Construction Contracts) included in the contract documents regardless of whether DBE participation is reported.

Provide written confirmation from each DBE that the DBE is participating in the Contract. A copy of a DBE's quote serves as written confirmation. If a DBE is participating as a joint venture partner, the Agency encourages you to submit a copy of the joint venture agreement.)

d. Subcontractor and Disadvantaged Business Enterprise Records

Redlans Regular Meeting of 09-05-2023
862 of 1115

SC 5

Use each DBE subcontractor as listed on Exhibit 12-B Bidder’s List of Subcontractors (DBE and Non-DBE) and Exhibit 15-G Local Agency Bidder DBE Commitment (Construction Contracts) form unless you receive authorization for a substitution.

The Agency requests the Contractor to:

1. Notify the Engineer of any changes to its anticipated DBE participation

2. Provide this notification before starting the affected work

3. Maintain records including:
 Name and business address of each 1st-tier subcontractor  Name and business address of each DBE subcontractor, DBE vendor, and DBE trucking company, regardless of tier
 Date of payment and total amount paid to each business

If you are a DBE contractor, include the date of work performed by your own forces and the corresponding value of the work.

Before the 15th of each month, submit a Monthly DBE Trucking Verification form.

If a DBE is decertified before completing its work, the DBE must notify you in writing of the decertification date. If a business becomes a certified DBE before completing its work, the business must notify you in writing of the certification date. Submit the notifications. On work completion, complete a Disadvantaged Business Enterprises (DBE) Certification Status Change, Exhibit 17-O, form. Submit the form within 30 days of contract acceptance.

Upon work completion, complete Exhibit 17-F Final Report – Utilization of Disadvantaged Business Enterprises (DBE), First-Tier Subcontractors. Submit it within 90 days of contract acceptance. The Agency will withhold $10,000 until the form is submitted. The Agency releases the withhold upon submission of the completed form.

e. Performance of Disadvantaged Business Enterprises

DBEs must perform work or supply materials as listed in the Exhibit 15-G Local Agency Bidder DBE Commitment (Construction Contracts) form, included in the Bid.

Do not terminate or substitute a listed DBE for convenience and perform the work with your own forces or obtain materials from other sources without authorization from the Agency.

The Agency authorizes a request to use other forces or sources of materials if it shows any of the following justifications:

1. Listed DBE fails or refuses to execute a written contract based on plans and specifications for the project.

2. You stipulated that a bond is a condition of executing the subcontract and the listed DBE fails to meet your bond requirements.

3. Work requires a contractor's license and listed DBE does not have a valid license under Redlans Regular Meeting of 09-05-2023
863 of 1115

SC 6

Contractors License Law.

4. Listed DBE fails or refuses to perform the work or furnish the listed materials.

5. Listed DBE's work is unsatisfactory and not in compliance with the contract.

6. Listed DBE is ineligible to work on the project because of suspension or debarment.

7. Listed DBE becomes bankrupt or insolvent.

8. Listed DBE voluntarily withdraws with written notice from the Contract

9. Listed DBE is ineligible to receive credit for the type of work required.

10. Listed DBE owner dies or becomes disabled resulting in the inability to perform the work on the Contract.

11. Agency determines other documented good cause.

Notify the original DBE of your intent to use other forces or material sources and provide the reasons. Provide the DBE with 5 days to respond to your notice and advise you and the Agency of the reasons why the use of other forces or sources of materials should not occur. Your request to use other forces or material sources must include:

1. One or more of the reasons listed in the preceding paragraph

2. Notices from you to the DBE regarding the request

3. Notices from the DBEs to you regarding the request

If a listed DBE is terminated or substituted, you must make good faith efforts to find another DBE to substitute for the original DBE. The substitute DBE must perform at least the same amount of work as the original DBE under the contract to the extent needed to meet the DBE goal.

The substitute DBE must be certified as a DBE at the time of request for substitution.

Unless the Agency authorizes (1) a request to use other forces or sources of materials or (2) a good faith effort for a substitution of a terminated DBE, the Agency does not pay for work listed on the Exhibit 15-G Local Agency Bidder DBE Commitment (Construction Contracts) form unless it is performed or supplied by the listed DBE or an authorized substitute.

1.05 FEDERAL WAGE RATES. Attention is directed to the Federal wage rates in Section 5-3.2 of the General Conditions within these Specifications. The federal prevailing wage rates are available directly from the department of Labor home page under https://sam.gov/wage- determination/CA20220026/3.

1.06 LABOR NONDISCRIMINATION. Attention is directed to the following Notice that is required by Chapter 5 of Division 4 of Title 2, California Code of Regulations.

Redlans Regular Meeting of 09-05-2023
864 of 1115

SC 7

NOTICE OF REQUIREMENT FOR NONDISCRIMINATION PROGRAM
(GOV. CODE, SECTION 12990)

Your attention is called to the “Nondiscrimination Clause,” set forth in Section 7-1.01A(4), “Labor Nondiscrimination,” of the Standard Specifications, which is applicable to all nonexempt state contracts and subcontracts, and to the “Standard California Nondiscrimination Construction Contract Specifications” set forth therein. The Specifications are applicable to all nonexempt state construction contracts and subcontracts of $5000 or more.

S-1.07 SUBCONTRACTING - Attention is directed to the provisions in Section 8-1.01, “Subcontracting,” of the Standard Specifications, Section 2, “Proposal Requirements and Conditions,” of the Standard Specifications and Section 3, ”Award and Execution of Contract,” of the Standard Specifications elsewhere in these special provisions and these special provisions.

The requirement in the third paragraph of Section 8-1.01 that the Contractor shall perform with the Contractor’s own organization contract work amounting to no less than 50 percent of the original contract price is not changed by the Federal Aid requirement specified under ”Required Contract Provisions Federal-Aid Construction Contracts” in S-5 of the Special Provisions (Section 14 in the Caltrans special provisions) that the Contractor perform not less than 30 percent of the original contract work with the Contractor’s own organization.

Each subcontract and any lower tier subcontract that may in turn be made shall include the "Required Contract Provisions Federal-Aid Construction Contracts" in Section S-5 of these special provisions (Section 14 in the Caltrans special provisions). Noncompliance shall be corrected.

Payment for subcontracted work involved will be withheld from progress payments due, or to become due, until correction is made. Failure to comply may result in termination of the contract.

Pursuant to the provisions in Section 1777.1 of the Labor Code, the Labor Commissioner publishes and distributes a list of contractors ineligible to perform work as a subcontractor on a public works project. This list of debarred contractors is available from the Department of Industrial Relations web site at: http://www.dir.ca.gov/DLSE/Debar.html.

1.08 PROMPT PAYMENT CLAUSES

Prompt Progress Payment to Subcontractors. A prime contractor or subcontractor shall pay any subcontractor not later than 10 days of receipt of each progress payment in accordance with the provision in Section 7108.5 of the California Business and Professions Code concerning prompt payment to subcontractors. The 10 days is applicable unless a longer period is agreed to in writing.

Any delay or postponement of payment over 30 days may take place only for good cause and with the agency’s prior written approval. Any violation shall subject the violating contractor or subcontractor to the penalties, sanction and other remedies of that section. This requirement shall not be construed to limit or impair any contractual, administrative, or judicial remedies otherwise available to the contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the prime contractor, deficient subcontract performance, or noncompliance by a subcontractor. This provision applies to both DBE and non-DBE subcontractors.

Redlans Regular Meeting of 09-05-2023
865 of 1115

SC 8

Prompt Payment of Fund Withheld to Subcontractors. The agency shall hold retainage from the prime contractor and shall make prompt and regular incremental acceptances of portions, as determined by the agency, of the contract work, and pay retainage to the prime contractor based on these acceptances. The prime contractor, or subcontractor, shall return all monies withheld in retention from a subcontractor within 30 days after receiving payment for work satisfactorily completed and accepted including incremental acceptances of portions of the contract work by the agency. Federal law (49CFR26.29) requires that any delay or postponement of payment over 30 days may take place only for good cause and with the agency postponement of payment over violation of this provision shall subject the violating prime contractor or subcontractor to the penalties, sanctions and other remedies specified in Section 7108.5 of the Business and Professions Code. These requirements shall not be construed to limit or impair any contractual, administrative, or judicial remedies otherwise available to the prime contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the prime contractor, deficient subcontract performance, or noncompliance by a subcontractor.

1.09 BUY AMERICA REQUIREMENTS . Attention is directed to the “Buy America” requirements of the Surface Transportation Assistance Act of 1982 (Section 165) and the Intermodal Surface Transportation Efficiency Act of 1991 (ISTEA) Sections 1041(a) and 1048(a), and the regulations adopted pursuant thereto. In accordance with said law and regulations, all manufacturing processes for steel and iron materials furnished for incorporation into the work on this project shall occur in the United States; with the exception that pig iron and processed, pelletized and reduced iron ore manufactured outside the United States may be used in the domestic manufacturing process for such steel and iron materials. The application of coatings, such as epoxy coating, galvanizing, painting, and any other coating that protects or enhances the value of such steel or iron materials shall be considered a manufacturing process subject to the “Buy America” requirements.

A Certificate of Compliance, conforming to the provisions in Section 6-2.03C, “Certificates of Compliance, “of the Standard Specifications, shall be furnished for steel and iron materials. The certificates, in addition to certifying that the materials comply with the specifications, shall also specifically certify that all manufacturing processes for the materials occurred in the United States, except for the exceptions allowed herein.

The requirements imposed by said law and regulations do not prevent a minimal use of foreign steel and iron materials if the total combined cost of such materials used does not exceed one-tenth of one percent (0.1%) of the total contract cost or $2500, whichever is greater. The Contractor shall furnish the Engineer acceptable documentation of the quantity and value of any foreign steel and iron prior to incorporating such materials into the work.

Redlans Regular Meeting of 09-05-2023
866 of 1115

SC 9

SECTION 2 – REQUIRED CONTRACT PROVISIONS FEDERAL-AID

CONSTRUCTION CONTRACTS

Redlans Regular Meeting of 09-05-2023
867 of 1115

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
EXHIBIT 12-G REQUIRED FEDERAL-AID CONTRACT LANGUAGE
(For Local Assistance Construction Projects)
The following language must be incorporated into all Local Assistance Federal-aid construction contracts.

The following language, with minor edits, was taken from the Code of Federal Regulations.

MAINTAIN RECORDS AND SUBMIT REPORTS DOCUMENTING YOUR PERFORMANCE UNDER THIS

SECTION

1. DISADVANTAGED BUSINESS ENTERPRISES (DBE) ................................................................................ 2 A. NONDISCRIMINATION STATEMENT.............................................................................................. 2 B. CONTRACT ASSURANCE............................................................................................................... 3 C. PROMPT PROGRESS PAYMENT ................................................................................................... 3 D. PROMPT PAYMENT OF WITHHELD FUNDS TO SUBCONTRACTORS ...................................... 3 E. TERMINATION AND SUBSTITUTION OF DBE SUBCONTRACTORS.......................................... 4 F. COMMITMENT AND UTILIZATION ................................................................................................. 5 G. DBE RUNNING TALLY OF ATTAINMENTS ................................................................................... 6

2. BID OPENING ................................................................................................................................................ 6

3. BID RIGGING ................................................................................................................................................. 6

4. CONTRACT AWARD ..................................................................................................................................... 6

5. CONTRACTOR LICENSE.............................................................................................................................. 6

6. CHANGED CONDITIONS .............................................................................................................................. 6 A. DIFFERING SITE CONDITIONS....................................................................................................... 6 B. SUSPENSIONS OF WORK ORDERED BY THE ENGINEER ......................................................... 6 C. SIGNIFICANT CHANGES IN THE CHARACTER OF WORK.......................................................... 7

7. BEGINNING OF WORK, TIME OF COMPLETION AND LIQUIDATED DAMAGES...................................... 7

8. BUY AMERICA...............................................................................................................................................7

9. QUALITY ASSURANCE................................................................................................................................. 8

10. PROMPT PAYMENT FROM THE AGENCY TO THE CONTRACTORS........................................................ 8

11. FORM FHWA-1273 REQUIRED CONTRACT PROVISIONS FEDERAL-AID CONTRACTS....................... 8

12. FEMALE AND MINORITY GOALS .............................................................................................................. 21

13. TITLE VI ASSURANCES.............................................................................................................................. 22

14. USE OF UNITED STATES-FLAG VESSELS (CARGO PREFERENCE ACT)............................................. 23

15. FEDERAL TRAINEE PROGRAM................................................................................................................. 23