ROCKLIN CITY COUNCIL
City Council Regular Meeting
City Hall - Council Chambers
3970 Rocklin Rd. Rocklin, CA
95677
Website:
www.rocklin.ca.us
May 26, 2026
General Session 6:00 p.m.

Notice of Teleconference Meeting Locations:

DoubleTree - 990 Hilton Heights Road
Charlottesville, VA 22901
AND
Marina Sol - 204 Paseo de Marina
Baja California Norte 23453

DAVID BASS,

Mayor

BILL HALLDIN,

Vice Mayor

KEN BROADWAY,

Council Member

JILL GAYALDO,

Council Member

GREG JANDA,

Council Member

ALY ZIMMERMANN,

City Manager

MATTHEW MCOMBER,

City Attorney

DANIEL CHOE,

City Treasurer

AVINTA SINGH,

City Clerk

HOW TO PARTICIPATE
The City of Rocklin welcomes your interest and involvement in the City's legislative process. The City Council has established a procedure for addressing the Council. Persons wishing to address the City Council are asked to voluntarily complete and submit a speaker identification sheet to the City Clerk.

Speaker identification sheets are available near the entrance of the Council Chambers. For items listed on the agenda, any person may address the City Council at the time the item is considered. Speakers are requested to restrict their comments to the item as it appears on the agenda and stay within the required three-minute time limit. The Brown Act does not permit the City Council to take action on items brought up under Citizens Addressing the City Council.

WRITINGS RECEIVED AFTER AGENDA POSTING
Any writing or documents related to an agenda item for this meeting provided to the City Council, Public Financing Authority or Successor Agency will be made available for public inspection at City Hall, 3970 Rocklin Road, Rocklin, during normal business hours.

AMERICANS WITH DISABILITIES ACT
In compliance with the Americans with Disabilities Act, if you require special assistance to participate in this meeting or other services in conjunction with this meeting, including receiving notices, agendas, and other writings in appropriate alternative formats, please contact our office at (916) 625- 5560 at least 48 hours prior to the meeting or time when services are needed so that we may make every reasonable effort to accommodate you.

LEVINE ACT PROVISIONS
The Levine Act requires a party (or the party’s agent(s)) to a proceeding before the City of Rocklin that
involves any action or consideration to their contract, license, permit, or other entitlement for use, to
disclose any campaign contribution made to a City elected or appointed officer (including Councilmembers, Planning Commissioners, and members of other City boards and commissions) totaling more than $500 within the 12 months before the City decision.

City Council Regular Meeting Agenda of May 26, 2026
1 AUDIO/VISUAL PRESENTATIONS
If making a presentation regarding an agenda item, all audio/visual materials must be submitted to the City Clerk or Secretary at least 72 hours in advance. The City is not responsible for the compatibility or operation of non-city devices or the functionality of non-city presentations.

POSTING OF AGENDA
In accordance with Government Code Section 54954.2(a) this agenda was posted on the City's bulletin board at City Hall, 3970 Rocklin Road, Rocklin, and City of Rocklin website at www.rocklin.ca.us.

AGENDA

MEETING

INSTRUCTIONS
The public may listen to audio or view the meeting via live stream at https://www.rocklin.ca.us/agendas-minutes
. For those that do not plan on attending in person
but wish to make a public comment during the meeting, public comments will be accepted in email form until 3:00 p.m. on the meeting day. Public comments should be submitted to the City Clerk at
[email protected]
. Emailed public comments will be distributed to
City Council and treated as a public record.

Zoom Participation Via Computer Or Smartphone
You can join the meeting from your computer using a web browser or the Zoom software.

You can also join the meeting using the Zoom app on your Apple IOS or Android device.

Click the link below to join the Zoom meeting:

Click here to join this meeting via Zoom
Meeting ID: 851 6290 5205
Meeting password: 996260
Zoom Participation By Telephone (Audio Only Option)

1. Dial (669) 900-6833

2. When asked for the meeting ID, enter 851 6290 5205#

3. When asked for your participant ID, press # to continue

4. When asked for the meeting password, enter 996260#

5. To inform the City Clerk that you would like to make a public comment, dial *9 to “Raise your hand”. The Clerk will unmute you when it is your turn to speak.

CALL TO ORDER

PLEDGE OF ALLEGIANCE

ROLL CALL

AGENDA REVIEW

CITIZENS ADDRESSING THE CITY COUNCIL
This is an opportunity for public comment on matters not listed on the agenda. Public comment on items listed on the agenda will be taken when the agenda item is called.

City Council Regular Meeting Agenda of May 26, 2026
2 C1.

Minutes of the May 12, 2026, Regular Meeting of the City Council C2.

Kennel Ordinance Amendments / Zoning Ordinance Amendment ZOA2025-0002 (Second Reading of Ordinance)
C3.

Accounts Paid List - January to March 2026
C4.

Setting a Public Hearing on Delinquent Nuisance Abatement Charges (Weed Abatement)
C5.

Setting a Public Hearing on Delinquent Refuse Collection Charges C6.

Position Reclassification
C7.

The Bluffs Subdivision Road Reconstruction Phase II Bid Award

REPORTS FROM CITY COUNCIL AND CITY MANAGER
Reports from the City Council will include any AB1234 Reports.

CONSENT CALENDAR
All items listed under the Consent Calendar are considered and acted upon by one Motion. Anyone may request an item be removed for separate consideration.

Recommendation:

Approve the Minutes of the May 12, 2026, Regular Meeting of the City Council.

Recommendation:

Adopt an Ordinance of the City Council of the City of Rocklin Amending Rocklin Municipal Code Section 17.64.070 - Kennels (Kennel Ordinance / ZOA2025-0002).

Recommendation:

Receive the Accounts Paid List for January 1, 2026 to March 31, 2026.

Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Setting a Public Hearing on Delinquent Nuisance Abatement Charges (Weed Abatement).

Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Setting a Public Hearing on Delinquent Refuse Collection Charges.

Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Approving the Deletion of One Administrative Technician Allocation from the Community Development Department, and the Addition of One Administrative Analyst Allocation to the Community Development Department.

Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Awarding the Contract for the Bluffs Subdivision Road Reconstruction Phase II to All Phase Construction & Engineering, Inc., and Authorizing the City Manager to Execute an Agreement with All Phase Construction & Engineering, Inc.

City Council Regular Meeting Agenda of May 26, 2026
3 C8.

Park Drive Dig Outs Bid Award
C9.

Citywide Facilities Condition Assessment Project
C10.

Johnson-Springview and Twin Oaks ADA Counter Replacement P1.

Recognition of Granite Oaks Middle School Girls Flag Football Team for Two Undefeated Seasons
D1.

Placement of a General Transactions and Use Tax Measure on the November 3, 2026 General Election Ballot

Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Awarding the Contract for the Park Drive Dig Outs Project to JB Bostick Company and Authorizing the City Manager to Execute an Agreement with JB Bostick Company.

Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Approving and Authorizing the City Manager to Execute a Contract with Kitchell/CEM, Inc. for a Facilities Condition Assessment.

Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Approving and Authorizing the City Manager to Execute a Contract with PBM Construction, Inc. for the Johnson-Springview and Twin Oaks ADA Counter Replacement.

PRESENTATIONS

DISCUSSION ITEMS
Discussion Items include oral presentations including those recommending "receive and file".

Recommendation:

Introduce, Waive the Full Reading and Read by Title Only, an Ordinance of the City of Rocklin Amending Rocklin Municipal Code Title 3 – Revenue and Finance By Adding Chapter 3.25 “2026 Transactions and Use Tax” By Imposing a One-Half Percent (0.50%) General Transactions and Use (Sales) Tax Until Repealed By Voters, To Be Collected and Administered by the California Department of Tax and Fee Administration, Subject to Voter Approval.

FUTURE AGENDA ITEMS

ADJOURNMENT
City Council Regular Meeting Agenda of May 26, 2026
4 City Council
Staff Report

Subject:

Minutes of the May 12, 2026, Regular Meeting of the City Council Date:

May 26, 2026
Submitted By:

Avinta Singh, City Clerk
Department:

City Clerk's Office
Recommendation:

Approve the Minutes of the May 12, 2026, Regular Meeting of the City Council.

Item Number C1.

ATTACHMENTS:

1. Draft City Council Meeting Minutes of May 12, 2026
5 DRAFT Meeting Minutes of May 12, 2026 Rocklin City Council 1 | P a g e

ROCKLIN CITY COUNCIL

City Council Regular Meeting
City Hall – Council Chambers
3970 Rocklin Rd. Rocklin, CA 95677
Website: www.rocklin.ca.us

May 12, 2026
Closed Session 5:30 p.m.

General Session 6:00 p.m.

MEETING MINUTES
-DRAFT-

CALL TO ORDER

Mayor Bass called the meeting to order at 5:32 p.m.

ROLL CALL

Present: Councilmembers Ken Broadway, Jill Gayaldo, Bill Halldin Mayor David Bass

Absent: Council Member Greg Janda

PUBLIC COMMENT ON CLOSED SESSION

There were none.

Members of the City Council left the Council Chambers and convened Closed Session at 5:33 p.m.

CLOSED SESSION

Members of the City Council returned to the Council Chambers at 6:00 p.m.

CS1. Pursuant to Government Code Section 54957.6: Conference with Labor Negotiators, Agency Designated Representatives: Mayor Bass, Unrepresented Employee: City Manager

6 DRAFT Meeting Minutes of May 12, 2026 Rocklin City Council 2 | P a g e

CS2. Pursuant to Government Code Section 54957.6: Conference with Labor Negotiators, Agency Designated Representatives: Mayor Bass, Unrepresented Employee: City Attorney

REPORT OUT OF CLOSED SESSION

There was no reportable action.

CALL GENERAL SESSION TO ORDER

Mayor Bass called the meeting to order at 6:00 p.m.

PLEDGE OF ALLEGIANCE

Mayor Bass led the pledge of allegiance.

AGENDA REVIEW

There were no changes to the agenda.

CITIZENS ADDRESSING THE CITY COUNCIL

Ms. Ariya Prakash invited the City Council to the Hindu Education Foundation’s Teacher Appreciation event being held at Ruhkala Elementary School on May 17, 2026.

Placer County Supervisor Anthony DeMattei presented members of the City Council with commemorative challenge coins honoring Placer County’s 175th anniversary.

REPORTS FROM CITY COUNCIL AND CITY MANAGER

Council Member Broadway reported attendance at the Rocklin Police Department’s annual Honors and Awards Ceremony; shared his participation in the Joint City Council and Planning Commission Workshop held on May 5, 2026; attended a South Placer Municipal Utility District Board meeting; and participated in the 9 th annual Rocklin Police and Fire Golf Tournament organized by the Rocklin Public Safety Foundation.

Council Member Gayaldo reported attendance in the California Passenger Rail Summit event; shared that the Rocklin Civic Celebration celebrating the City’s 133 rd anniversary and America’s 250 th birthday was a successful event featuring a fireworks and drone show; participated in the Joint City Council and Planning Commission Workshop held on May 5, 2026; attended the Rocklin Chamber of Commerce ’s monthly Government Relations Committee Meeting; attended a media training held by the Sacramento Area Council of Governments ( SACOG); participated in SACOG’s Policy and Innovation Committee meeting, followed by the Strategic Planning Committee meeting, sharing that the California Department of Housing and Community Development will provide SACOG with its regional housing determination no later than September 15, 2026. 7 DRAFT Meeting Minutes of May 12, 2026 Rocklin City Council 3 | P a g e

Vice Mayor Halldin reported attendance at the Rocklin Police Department’s annual Honors and Awards Ceremony; attended the Rocklin Heritage Street Faire on Front Street organized by the Rocklin Historical Society; attended the Rocklin Civic Celebration; and attended Placer County’s annual State of the C ounty event which included a presentation by County Board of Supervisor’s Shanti Landon.

Mayor Bass thanked City staff for hosting a successful Red, White and Blue Grass Civic Celebration event.

City Manager Zimmermann reported that the City would be reimbursed from the County for the Placer Parkway Project improvements, including the widening of the Whitney Ranch Parkway intersection and for the installation of the traffic signal; expressed her appreciation to the City Council and City staff including the Parks and Recreation, Police, Fire, Public Works and all internal departments for their efforts in organizing the Rocklin Civic Celebration and honoring the nation’s 250th birthday, which included a parade held between the Heritage Street Faire and Civic Celebration ; shared that the City was receiving applications for scheduled vacancies on its Board/Commissions/Committee with the deadline being May 22, 2026; noted that splash pads at City parks would open on May 15, 202 6; shared that City facilities will be closed on Monday, May 25, 2026, in observance of Memorial Day, adding that Memorial Day services will be held on this day at 11 a.m. at the Rocklin Cemetery; invited the public to attend the 3 rd annual Meet the Machines to be held at the Corp Yard; and shared upcoming Concerts at Quarry Park on May 21 and May 23, 2026.

CONSENT CALENDAR

C1. Minutes of the April 28, 2026, Regular Meeting of the City Council Action: Approved the Minutes of the April 28, 2026, Regular Meeting of the City Council.

C2. Proclamation Declaring the Month of May 2026 as Lyme Disease Awareness Month
Action: Approved a Proclamation Declaring the Month of May 2026 as Lyme Disease Awareness Month, and Designated the Mayor to Sign the Proclamation on Behalf of the City Council.

C3. Proclamation Declaring May 10-16, 2026 as National Police Week and May 15 as Peace Officers Memorial Day
Action: Approved a Proclamation Declaring May 10 -16, 2026 as National Police Week and May 15 as Peace Officers Memorial Day, and Designated the Mayor to Sign the Proclamation on Behalf of the City Council.

C4. Proclamation Declaring May 17-23, 2026, as National Public Works Week Action: Approved a Proclamation Declaring May 17-23, 2026, as National Public Works Week, and Designated the Mayor to Sign the Proclamation on Behalf of the City Council.
8 DRAFT Meeting Minutes of May 12, 2026 Rocklin City Council 4 | P a g e

C5. Accessory Dwelling Unit and Junior Accessory Dwel ling Unit Zoning Ordinance Amendments ZOA2026-0001 (Second Reading of Ordinance)
Action: Adopted Ordinance No. 1206 of the City Council of the City of Rocklin Amending Rocklin Municipal Code - Title 17 (Zoning) Specific to Accessory Dwelling Units and Junior Accessory Dwelling Units.

C6. Agreement with Clifford Moss LLC for Continued Public Engagement and Communications Services - Amendment No.1
Action: Adopted Resolution No. 2026-052 of the City Council of the City of Rocklin Authorizing Amendment No. 1 to the Professional Services Agreement with Clifford Moss LLC for Continued Public Engagement and Communication Services.

C7. Public Multi-Purpose Pedestrian and Bicycle Trail Easement and Emergency and Maintenance Vehicle Access Easement - University Avenue Apartments (The Francis)
Action: Adopted Resolution No. 2026 -053 Approving and Accepting a Grant of Public Multi-Purpose Pedestrian and Bicycle Trail Easement and Emergency and Maintenance Vehicle Access Easement Agreement Associated with The Francis Project.

C8. Affordable Housing Agreement for The Steven
Action: Adopted Resolution No. 2026-054 of the City Council of the City of Rocklin Approving an Affordable Housing Agreement by and between the City and Rocklin Sierra 703 L.P. Making a Loan in the Amount of $2,230,000 for The Steven Senior Affordable Housing Development and Authorize the City Manager to Execute the Necessary Documents.

C9. Quarterly Treasurer's Report
Action: Received the Treasurer's Report for the Quarter Ending March 31, 2026.

C10. Approving the Fiscal Year 2026/27 Engineer's Reports Action:

A. Action: Adopted Resolution No. 2026-055 of the City Council of the City of Rocklin Approving the Fiscal Year 2026/27 Engineer's Report for the Levy of the Annual Assessment for Lighting Maintenance District No. 1.

B. Action: Adopted Resolution No. 2026-056 of the City Council of the City of Rocklin Declaring Its Intention to Levy and Collect Annual Assessments for Lighting Maintenance District No. 1 and Setting a Time and Place for Public Hearing Thereon.

C. Action: Adopted Resolution No. 2026-057 of the City Council of the City of Rocklin Approving the Fiscal Year 2026/27 Engineer’s Report for the Levy of the Annual Assessment for Landscape and Lighting Maintenance District No. 2.

9 DRAFT Meeting Minutes of May 12, 2026 Rocklin City Council 5 | P a g e

D. Action: Adopted Resolution No. 2026-058 of the City Council of the City of Rocklin Declaring its Intention to Levy and Collect Annual Assessments for Landscape and Lighting Maintenance District No. 2 and Setting a Time and Place for Public Hearing Thereon.

C11. Enterprise Resource Agreement - Amendment No. 1
Action: Adopted Resolution No. 2026-059 of the City Council of the City of Rocklin Approving and Authorizing the City Manager to Execute an Amendment to the Enterprise Resource Planning Solution Maintenance Agreement with Tyler Technologies, Inc.

C12. Various Personnel Updates
Action:

A. Action: Adopted Resolution No. 2026-060 of the City Council of the City of Rocklin Approving the Deletion of the City Engineer/Deputy Director of Community Development Allocation, Addition of One City Engineer Allocation, Addition of One Deputy Director of Community Development Allocation, Deletion of the Planning Manager Allocation, and the Revised Management Salary Schedule.

B. Action: Adopted Resolution No. 2026-061 of the City Council of the City of Rocklin Approving the Deletion of Two Community Services Officer Allocations, the Addition of One Animal Control Officer Allocation, the Addition of One Senior Animal Control Officer Allocation and the Revised RPOA Salary Schedule and Y-Rated Salary Schedule.

C13. Whitney Ranch Parkway Widening Project Notice of Completion Action: Adopted Resolution No. 2026-062 of the City Council of the City of Rocklin Accepting the Public Work Known as the Whitney Ranch Parkway Widening Project, Approving the Notice of Completion, and Authorizing and Directing the Execution and Recordation of Said Notice on Behalf of the City.

C14. Homeland Security Grant Program-Urban Areas Security Initiative (UASI) - Grant Subaward
Action: Adopted Resolution No. 2026 -063 of the Ci ty Council of the City of Rocklin Accepting the Grant Subaward from City of Sacramento for the Homeland Security Grant Program Urban Areas Security Initiative and Authorizing the City Manager to Execute the Subaward Agreement and Purchase Specialized Tools and Equipment.

10 DRAFT Meeting Minutes of May 12, 2026 Rocklin City Council 6 | P a g e

Motion to approve Consent Calendar Item Nos. C1 through C14, by Council Member Broadway, second ed by Council Member Gayaldo . Passed by the following vote:

Ayes: Councilmembers Broadway, Gayaldo, Halldin
Mayor Bass
Noes: None

Absent: Council Member Janda
Abstain: None

PRESENTATIONS

P1. Proclamation Declaring the Month of May 2026 as Lyme Disease Awareness Month

Council Member Broadway read the proclamation and presented it to Melisa Moya, founder and CEO of Lyme Fight Foundation.

Melisa Moya made remarks in support of Lyme Disease advocacy and awareness.

P2. Proclamation Declaring May 10-16, 2026 as National Police Week and May 15 as Peace Officers Memorial Day

Mayor Bass read the proclamation and presented it to Police Chief Rustin Banks.

Chief Banks thanked the City Council for their support and recognition.

P3. Proclamation Declaring the May 17-23, 2026 as National Public Works Week

Mayor Bass read the proclamation and presented it to Public Works Director Justin Nartker, who was joined by Department staff members Michael Broughan and Christian Catalan. Director Nartker shared that the upcoming Meet the Machines event was to be held on May 21, 2026 at the Corp Yard.

P4. Recognition of Past Presidents of the Rocklin Public Safety Foundation

The City Council recognized the following past presidents of the Rocklin Public Safety Foundation and presented them with certificates:

Ms. Rebecca Kanowsky (Years served: 2012 – 2014)
Mr. Rich Vallone (Years served: 2015-2018)
Mr. Stu Lehman (Years served: 2019-2021)
Mr. Scott Yuill (Year served: 2022)
Ms. Mariella Platner (Year served: 2023
Mr. Jeremy Cappalo (Year served: 2024
11 DRAFT Meeting Minutes of May 12, 2026 Rocklin City Council 7 | P a g e

Mr. Braden Moulton (Year served: 2025)

P5. Rocklin Public Safety Foundation Presentation

Council Member Broadway presented the item to the City Council, indicating that it was an honor for him to serve as a Foundation Board Member . Councilmembers expressed their appreciation to the Foundation for its contributions to public safety benefitting the community.

The City Council recessed at 6:52 p.m. and reconvened at 7:01 p.m.

PUBLIC HEARINGS

PH1. Kennel Ordinance Amendments / Zoning Ordinance Amendment, ZOA2025- 0002, and Environmental, ENV2026-0007
Action: Conducted a Public Hearing and Considered the Following Actions:

A. Action: Adopted Resolution No. 2026-064 of the City Council of the City of Rocklin Approving a Notice of Exemption (Kennel Ordinance Amendments / ENV2026-0007).

B. Introduced, Waived the Full Reading and Read by Title Only, an Ordinance of the City Council of the City of Rocklin Amending Rocklin Municipal Code Section 17.64.070 - Kennels (Kennel Ordinance / ZOA2025-0002).

Mayor Bass opened the public hearing for item PH1.

Senior Planner Smithhart presented the item to the City Council.

Members of the City Council asked questions, which were responded to by City Manager Zimmermann.

PUBLIC COMMENT

There were none.

Motion to approve Public Hearing Item No. PH1.A by Council Member Broadway, seconded by Vice Mayor Halldin. Motion passed by the following vote:

Ayes: Councilmembers Broadway, Gayaldo, Halldin
Mayor Bass
Noes: None

Absent: Council Member Janda
Abstain: None

12 DRAFT Meeting Minutes of May 12, 2026 Rocklin City Council 8 | P a g e

Motion to approve Public Hearing Item No. PH1.B by Council Member Broadway, seconded by Vice Mayor Halldin. Motion passed by the following vote:

Ayes: Councilmembers Broadway, Gayaldo, Halldin
Mayor Bass
Noes: None

Absent: Council Member Janda
Abstain: None

Mayor Bass stated that in accordance with the Audio/ Visual P resentation rules listed on the meeting agenda, audiovisual materials must be submitted to City staff 72 hours in advance to be displayed at a City Council meeting. Since the presentation submitted for the public hearing was received at 1:00 p.m. on the day of the meeting, it could not be displayed.

PH2. Sierra Wilds Apartments / Design Review, DR2025-0005, and Environmental, ENV2025-0008
Action: Conducted a Public Hearing and Considered the Following Actions:

A. Resolution of the City Council of the City of Rocklin Approving a Notice of Exemption (Sierra Wilds Apartments / ENV2025-0008).

B. Resolution No. 2026-066 of the City Council of the City of Rocklin Approving a Design Review (Sierra Wilds Apartments / DR2025-0005).

Mayor Bass opened the public hearing for item PH2.

Principal Planner Nathan Anderson presented the item to the City Council.

Members of the City Council asked questions, which were responded to by Senior Planner Anderson, City Manager Zimmermann, City Attorney Matthew McOmber and Community Development Director David Mohlenbrok.

The City Council recessed at 8:43 p.m. and the public hearing reconvened at 8:51 p.m.

On behalf of the project applicant Pacific West Communities, Inc., the following individuals addressed City Council questions:

Lauren Alexander, Project Manager
Sam Bacal-Graves, Attorney with Stoel Rives
Jackie Winkel, Senior Air Quality Scientist with First Carbon Solutions Mary Bean, with First Carbon Solutions

Mayor Bass requested a brief regulatory recess to confer with the City Manager and City Attorney regarding how to proceed with the public hearing, as there were still questions remaining for the project applicant as well as the public comment period.

13 DRAFT Meeting Minutes of May 12, 2026 Rocklin City Council 9 | P a g e

The City Council recessed at 9:52 p.m. and the public hearing reconvened at 10:05 p.m.

Mayor Bass indicated that the City Council had additional questions pending for the applicant, which would likely require a continuation of the public hearing to a future meeting date.

Reverend Anny Gelato , and Director of St. Augustine Episcopal Church, addressed the City Council in support of the project, noting the church had financial obligations requiring the sale of the land.

City Clerk Avinta Singh noted there were 45 public comment cards submitted for the public hearing.

Mayor Bass requested a motion from the City Council to continue the public hearing to the August 11, 2026 City Council meeting.

City Manager Zimmermann indicated that per the City Council Procedural Rules, the time of adjournment for City Council meetings was 11:00 p.m., a motion would be required to waive the normal time of adjournment. She added that if any members of the public who offer public comment s at the present meeting would not be able to offer additional public comments if the public hearing is continued to a future date certain.

The City council requested further information on the following topics of concern as related to the proposed project: air quality, noise, traffic circulation, and student safety.

Motion to continue Public Hearing Item No. PH2 to the August 11, 2026 City Council Meeting to be held in the Rocklin City Council Chambers at 6:00 p.m. by Council Member Broadway, seconded by Council Member Gayaldo. Motion passed by the following vote:

Ayes: Councilmembers Broadway, Gayaldo, Halldin
Mayor Bass
Noes: None

Absent: Council Member Janda
Abstain: None

FUTURE AGENDA ITEMS

Mayor Bass requested a future agenda i tem on what other Council of Governments are doing to address upcoming changes to RHNA numbers.

14 DRAFT Meeting Minutes of May 12, 2026 Rocklin City Council 10 | P a g e

ADJOURNMENT

Mayor Bass adjourned the meeting at 10:29 p.m.

_____________________________
David Bass, Mayor

This is to certify that the foregoing is a true and
correct copy of the minutes of May 12 , 2026 as
approved by the Rocklin City Council.

_______________________________
Avinta Singh, City Clerk

15 City Council
Staff Report

Subject:

Kennel Ordinance Amendments / Zoning Ordinance Amendment ZOA2025-0002 (Second Reading of Ordinance)
Date:

May 26, 2026
Submitted By:

Avinta Singh, City Clerk
Department:

City Clerk's Office
Recommendation:

Adopt an Ordinance of the City Council of the City of Rocklin Amending Rocklin Municipal
Code Section 17.64.070 - Kennels (Kennel Ordinance / ZOA2025-0002).

Background:

On May 12, 2026, the City Council introduced, waived the full reading, and read by title only the following: A
n
Ordinance of the City Council of the City of Rocklin
Amending Rocklin
Municipal Code Section 17.64.070 - Kennels (Kennel Ordinance / ZOA2025-0002).

The background materials for this item are contained in the May 12, 2026 City Council
Meeting Staff Report,

located on the City's website.

Item Number C2.

ATTACHMENTS:

1. Ordinance

2. Rocklin Municipal Code Section 17.64.070 redlined
16

Page 1 of 5 ends

Ordinance No. XXXX
ORDINANCE NO. XXXX

ORDINANCE OF THE CITY COUNCIL OF THE CITY OF ROCKLIN
AMENDING ROCKLIN MUNICIPAL CODE SECTION 17.64.070 –
KENNELS (Kennel Ordinance / ZOA2025-0002)

The City Council of the City of Rocklin finds as follows:

A. Purpose. The purpose of this Ordinance is to amend Section 17.64.070 of Title 17 of the Rocklin Municipal Code (RMC) to clarify regulations governing the operation of kennels within the City of Rocklin. This Ordinance is intended to further assist in protecting public health, safety, and welfare, promote responsible kennel management, and ensure appropriate conditions for the animals housed within these facilities. These kennel regulation ame ndments have been further designed to ensure compatibility with surrounding development and adjacent tenants. Staff has received concerns regarding the placement of kennel operations, particularly near office -type uses, as dog vocalizations, while not exceeding applicable noise standards, may still be audible and impact neighboring tenants. Rocklin’s zoning code currently lacks a mechanism to regulate the compatibility of kennels with various individual business operations, such as offices, that may be quie ter than other tenants within the land use zone district. To address this, the ordinanc e amendment requires applicants to submit adjacent tenant floor plans and business descriptions for review as part of the Conditional Use Permit review process, allowing for case-by-case evaluation.

B. The proposed amendments to the RMC are consistent with and implement the policies of the City of Rocklin's General Plan.

C. The proposed amendments to the RMC are not likely to create serious health problems or create nuisances on or near affected properties.

D. Authority. The City Council enacts this or dinance under the authority granted to cities by Article XI, Section 7 of the California Constitution and Government Code section 37100.

NOW THEREFORE, THE CITY COUNCIL OF THE CITY OF ROCKLIN DOES ORDAIN AS FOLLOWS:

Section 1. Findings. The findings an d recitals set forth above are true and correct.

Section 2. Amendment to Code . The Rocklin Municipal Code Section

17.64.070 “Kennels” is hereby amended to read as follows:

17

Page 2 of 5 ends

Ordinance No. XXXX
Chapter 17.64 - SPECIAL AND PROHIBITED USES

17.64.070 – Kennels
A. Kennels, for b oarding of animals for commercial or noncommercial purposes, except those prohibited by Section 17.64.030.A, are permitted in the following zone districts subject to issuance of a conditional use permit and compliance with the criteria set forth in Sections 17.64.070.B and C below:

1. C-2: retail business zone;

2. C-3: general and service commercial zone;

3. C-4: limited general retail and service commercial zone;

4. C-H: highway commercial zone;

5. M-1: manufacturing zone;

6. M-2: heavy industrial zone;

7. Planned development zone districts equivalent to the above.

B. Application Submittal. Applications for a Conditional Use Permit for a Kennel shall include the items specified in Section 17.70.030 – Application, and shall also include, but not be limited to the following:

1. Design plans for any exterior modifications related to the outdoor dog enclosure, such as walls, fencing, lighting, hardscape, and plantings;

2. A written statement of compatibility, including all relevant details of the proposed use, such as abutting business operations (if located in a multi - tenant building or adjacent to other surrounding uses), type of use, operating hours, number of employees, parking, traffic impacts, and other pertinent information; and

3. When proposed w ithin an existing multi -tenant building, the applicant shall provide a floor plan of their entire tenant space, as well as all adjacent tenant space; and

4. If any component of the kennel is proposed to be outdoors, a noise study (prepared by a qualified n oise professional) is required to demonstrate compliance with the noise standards of the General Plan Noise Element and Noise Standards Ordinance.

5. In addition to the standard noticing requirements, any kennel application that includes an outdoor enclosu re shall require an early notice to be mailed to surrounding properties. The early notice constitutes the final administrative action prior to the City’s determination t hat an application submittal is complete. The notice shall be provided to all property owners 18

Page 3 of 5 ends

Ordinance No. XXXX
of record and to mailing addresses within 300 feet of the subject property, advising that an application has been received, providing a summary of the application , and the location where project documents can be reviewed. This notice shall be mailed no fewer than thirty (30) days prior to the date of the Planning Commission hearing.

C. All kennels shall comply with the following criteria:

1. The kennel use facilit y, premises, and surrounding area shall be regularly cleaned and maintenance shall be c onducted in accordance with applicable health and sanitation standards.

2. All animals housed in the facility shall be cared for in accordance with Chapter 11 (Pet Boarding Facilities) of the California Health and Safety Code (Sections 122380-122388).

3. The building or tenant space in which the kennel is located shall be improved and maintained such that animals housed there do not cause regular annoyance and disturbanc e to persons in the surrounding area, including but not limited to noise, odor, waste d isposal, etc. A medical - grade filtration system shall be installed to prevent the spread of noxious odors.

4. The kennel use shall be conducted entirely within a building with no outside activities or storage, except:
(a) When a noise study is submitted a nd approved with the project application demonstrating compliance with applicable noise regulations;
(b) When the hours for any outdoor kennel operations are restricted to between the hours of 8:00 AM to 8:00 PM;
(c) When located more than 200 feet from the boundary of any residentially zoned parcel;
(d) When located on parcels that directly abut a State Highway, Interstate Highway, or Arterial Road, as designated in the General Plan Circulation Element, and the noise from the roadway facilities is the predominant noise source at the kennel location; and (e) When a sign is installed and maintained at the edge of the public right-of-way that clearly displays the name and telephone number of a designated business representative responsible for addressing noise or odor complaints.
19

Page 4 of 5 ends

Ordinance No. XXXX

5. The operations of the kennel shall comply with all applicable regulations and requirements of county and state agencies. All health and safety permits shall be posted in a public location

Section 3. Environmental. The proposed a mendments to the Rocklin Municipal Code will not result in a direct or reasonably foreseeable indirect physical change to the environment under CEQA, and are therefore e xempt under sections 15060(c)(2) and 15061(b)(3) of the State CEQA Guidelines.

Section 4. Severability. If any section, sub -section, sentence, clause, phrase or portion of this Ordinance is for any reason held to be invalid or unconstitutional by the decision of any court of competent jurisdiction, such decision shall not affect the validit y of the remaining portions of the Ordinance. The City Council hereby declares that it would have adopted the Ordinance and each section, sub -section, sentence, clause, phrase or portion thereof, irrespective of the fact that any one or more sections, sub - sections, sentences, clauses, phrases or portions be declared invalid or unconstitutional.

Section 5. Effective Date. This ordinance shall take effect thirty (30) days after the day of its adoption.

Section 6. Publication. Within 15 days of the passage o f this ordinance, the City Clerk shall cause the full text of the ordinance, with the names of those City Council members voting for and against the ordinance, to be pub lished in the Placer Herald. In lieu of publishing the full text of the ordinance, the City Clerk, if so directed by the City Attorney and within 15 days, shall cause a summary of the ordinance, prepared by the City Attorney and with the names of the City Council members voting for and against the ordinance, to be published in the Placer Her ald, and shall post in the office of the City Clerk a certified copy of the full text of the ordinance, along with the names of those City Council members voting for and against the ordinance. The publication of a summary of the ordinance in lieu of the f ull text of the ordinance is authorized only where the requirements of Government Code section 36933(c)(1) are met. 20

Page 5 of 5 ends

Ordinance No. XXXX

INTRODUCED at a regular meeting of the City Council of the City of Rocklin held on May 12, 2026, by the following vote:

AYES: Councilmembers: Bass, Broadway, Gayaldo, Halldin NOES: None
ABSENT: Councilmember Janda
ABSTAIN: None

PASSED AND ADOPTED at a regular meeting of the City Council of the City of Rocklin held on May 26, 2026, by the following vote:

AYES: Councilmembers:

NOES: Councilmembers:

ABSENT: Councilmembers:

ABSTAIN: Councilmembers:

____________________________________
David Bass, Mayor

ATTEST:

___________________________
Avinta Singh, City Clerk

First Reading: 05.12.2026
Second Reading: 05.26.2026
Effective Date: 06.25.2026

21 ATTACHMENT 1

Proposed revisions to Rocklin Municipal Code (RMC) Section 17.64.070. Deletions to this section appear in red strike through and additions to this section are in blue underline.

Chapter 17.64 - SPECIAL AND PROHIBITED USES

17.64.070 – Kennels
A. Kennels, for boarding of animals for comm ercial or noncommercial purposes, except as specified in Section 17. 64.030.A, are permitted in the following zone districts subject to issuance of a n administrative permit conditional use permit by the economic and community development director and compliance with the criteria set forth in Sections 17.64.070.B and C below:

1. C-1: neighborhood commercial zone;

2.1. C-2: retail business zone;

3.2. C-3: general and service commercial zone;

4.3. C-4: limited general retail and service commercial zone;

5.4. C-H: highway commercial zone;

6.5. M-1: manufacturing zone;

7.6. M-2: heavy industrial zone;

8.7. Planned development zone districts equivalent to the above.

B. Permit Approval/Modification/Revocation.

1. Consistent with the provisions of th is chapter, the economic and community development director shall issue an administrative permit to operate a kennel if, in the opinion of the economic and co mmunity development director, the premises on which the k ennel will be located has been improved and is of sufficient size to accommodate the number of animals which the owner of such kennel anticipates will be on the premises, without c ausing any disturbance or annoyance to persons in the surrounding area subject to ongoing compliance with the criteria set forth in this chapter and any special conditions of approval deemed necessary by the economic and community development director.

2. A permit to operate a kennel may be m odified or revoked by the economic and community development director when he/she determines any of the following:
(a) That the animals in the kennel are causing continual annoyance and disturbance to persons in the surrounding area;
(b) That the animals within the kennel are not being given proper care; (c) That circumstances have changed sinc e the issuance of the kennel license, and in view of such circumstances, the premises are no longer suitable for the operation of a kennel.
22 3. Any person whose license to operate a k ennel is denied, modified or revoked by the economic and community develop ment director may appeal such determination, in accordance with the procedures specified in Chapter 17.86 of this title.

C. All kennels shall comply with the following criteria:

1. The premises and surroundings are mainta ined in a clean and sanitary state;

2. All animals housed in the facility are k ept in good health, well fed, watered, and receive adequate care and exercise;

3. The building or t enant space in which the kennel is located shall be improved and maintained such that animals housed therein do not cause regular annoyance and disturbance to persons in the surrounding area, including but not limited to noise, odor, waste disposal, etc.;

4. The use shall be conduct ed entirely within a building with no outside activities or storage;

5. The facility shall comply with all applicable regulations and requirements of county and state agencies;

6. The economic and community developmen t director may place such conditions on the permit as may be necessary to pr otecting the public health, safety and welfare.

B. Application Submittal. Applications for a Conditional Use Permi t for a Kennel shall include the items specified in Section 17.70.030 – Application, and shall also include, but not be limited to the following:

1. Design plans for any exterior modifica tions related to the outdoor dog enclosure, such as walls, fencing, lighting, hardscape, and plantings; and

2. A written statement of compatibility, including all relevant details of the proposed use, such as abutting business operations (if located in a multi-tenant building or adjacent to other surrounding uses), type of use, operating hours, number of employees, parking, traffic impacts, and other pertinent information; and

3. When proposed within an existing multi- tenant building, the applicant shall provide a floor plan of thei r entire tenant space, as we ll as all adjacent tenant space; and

4. If any component of the kennel is proposed to be outdoors, a noise study (prepared by a qualified noise profe ssional) is required to demonstrate compliance with applicable no ise standards (i.e., General Plan Noise Element and Noise Standards Ordinance).

5. In addition to the sta ndard noticing requirements, any kennel application that includes an outdoor enclosure shall r equire an early notice to be mailed to surrounding properties. The early notice c onstitutes the final administrative action prior to the City’s determination that an application submittal is complete.

The notice shall be provided to all proper ty owners of record and to mailing addresses within 300 feet of the subject property, advis ing that an application 23 has been received, providing a summary of the application, and the location where project documents can be reviewed. This notice shall be mailed no fewer than thirty (30) days prior to the date of the Planning Commission hearing.

C. All kennels shall comply with the following criteria:

1. The kennel use facility, premises, and surrounding area shall be regularly cleaned and maintenance shall be condu cted in accordance with applicable health and sanitation standards;

2. All animals housed in the facility sha ll be cared for in accordance with Chapter 11 (Pet Boarding Facilities) of the Califo rnia Health and Safety Code (Sections 122380-122388).

3. The building or t enant space in which the kennel is located shall be improved and maintained such that animals housed there do not cause regular annoyance and disturbance to persons in the surroundi ng area, including but not limited to noise, odor, waste disposal, etc. A medi cal-grade filtration system shall be installed to prevent the spread of noxious odors;

4. The kennel use shall be conducted entir ely within a building with no outside activities or storage, except:
(a) When a noise study is submitted and approved with the project application demonstrating compliance with applicable noise regulations; and (b) When the hours for any outdoor kennel operations are restricted to between the hours of 8:00 AM to 8:00 PM; and
(c) When located more than 200 feet fr om the boundary of any residentially zoned parcel; and
(d) When located on parcels that direct ly abut a State Highway, Interstate Highway, or Arterial Road, as desi gnated in the General Plan Circulation Element and the noise from the roadway facilities is the predominant noise source at the kennel location; and
(e) When a sign is installed and mainta ined at the edge of the public right-of- way that clearly displays the name and telephone number of a designated business representative responsibl e for addressing noise or odor complaints.

5. The operations of the kennel shall comp ly with all applicable regulations and requirements of county and state agencies. All health and safety permits shall be posted in a public location
24 City Council
Staff Report

Subject:

Accounts Paid List - January to March 2026
Date:

May 26, 2026
Submitted By:

Diane Ahn, Accounting Officer
Daniel Choe, Administrative Services Deputy Director
Department:

Administrative Services - Finance
Recommendation:

Receive the Accounts Paid List for January 1, 2026 to March 31, 2026.

Background:

The Accounts Paid List (Attachment 1) details expenses by payee, expense type, and amount paid for the period between January 1, 2026 to March 31, 2026.

Fiscal Impact:

This report will not have a direct fiscal impact. The items included are either within the current year budget or have been approved through budget amendments.

Item Number C3.

ATTACHMENTS:

1. Accounts Paid List January to March 2026
25 26
27 28
29 30
31 32
33 34
35 City Council
Staff Report

Subject:

Setting a Public Hearing on Delinquent Nuisance Abatement Charges (Weed Abatement)
Date:

May 26, 2026
Submitted By:

Angela Doyle, Senior Accountant
Diane Ahn, Accounting Officer
Daniel Choe Administrative Services Deputy Director
Department:

Administrative Services - Finance
Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Setting a Public Hearing on Delinquent Nuisance Abatement Charges (Weed Abatement).

Background:

Each year, the City notifies owners of vacant lots that they must maintain their property to minimize fire risk. If the properties are not abated by the land owners, the City has the right under state law to abate the properties and seek reimbursement for the abatement costs.

Rocklin Municipal Code section 8.12.010 provides for weed and rubbish abatement in accordance with state statutory provisions. California Government Code section 39501 provides: “The legislative body may compel the owner, lessee, or occupant of buildings, grounds, or lots to remove dirt, rubbish, weeds, and rank growths from buildings or grounds and adjacent sidewalks. If the person compelled by the legislative body defaults, after notice prescribed by the legislative body, it may authorize the removal or destruction of the dirt, rubbish, weeds, and rank growths at that person's expense by a city officer. The legislative body may prescribe a procedure for the removal or destruction and make the expense a lien upon the buildings or grounds.”

California Government Code sections 39502 through 39588 set forth the requirements for notice, including a public hearing for this weed abatement process.

On April 8, 2025, the City Council adopted Resolution No. 2025-062, which identified vacant parcels requiring abatement, ordered that such abatement be completed by June 1, 2025, and set a public hearing to hear any protests. The resolution also provided that the City may perform abatement on properties that were not properly abated by the owners, and bill the responsible land owner for any costs incurred by the City.

Item Number C4.

36 In accordance with California Government Code section 39567.1, owners of affected vacant parcels were timely notified by mail of the abatement requirements, and the public hearing. On April 22, 2025, the City Council held a public hearing and ordered the nuisances be abated.

The City's contractor performed abatement on properties that had not been abated by the owners and billed the City for its costs during the period of June through August 2025. The City then billed the property owners for the costs of abatement and sent second notices on those properties that did not pay after the first invoice. Those that currently remain unpaid after second invoice are the subject of this process.

Government Code sections 39574 and 39576 require the City Council to conduct a public hearing, to receive and consider a report on the costs of abatement, as well as any objections of the property owners liable to be assessed on the property tax roll for the abatement. The report is attached to the Resolution.

City Council approval of the staff recommendation will set a public hearing for June 23, 2026, at 6 p.m., or as soon thereafter as the matter may be heard by the City Council of the City of Rocklin at the Council Chambers located at 3970 Rocklin Road, Rocklin, for the receipt, consideration, and confirmation of the itemized written report showing the properties delinquent in paying the costs of nuisance abatement performed between June and August 2025. At the public hearing, objections of property owners liable to be assessed for the abatement shall be heard.

Fiscal Impact:

The City charges a fee of 15% of delinquent charges for parcels that require the processing of a property tax special assessment. Delinquent accounts can make payment to the City without incurring the 15% fees, up until the public hearing date. If delinquent payments are made between now and the public hearing, staff will update the list of parcels and respective delinquent amounts owed, including fees, prior to the public hearing as needed.

ATTACHMENTS:

1. Resolution
37 Resolution No. 2026-
2026-
May 26, 2026 Page 1 of 2
1 RESOLUTION NO. 2026-

RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ROCKLIN

SETTING A PUBLIC HEARING ON DELINQUENT NUISANCE

ABATEMENT CHARGES (WEED ABATEMENT)

WHEREAS, pursuant to Rocklin Municipal Code section 8.12.010 and California Government Code section 39501 et seq., the City may abate nuisances and consider the imposition of said abatement costs, subject to notice and public hearing requirements; and

WHEREAS, on April 8, 2025, Council adopted Resolution No. 202 5-062, which identified vacant parcels in the City of Rocklin that required abatement, ordered abatement to be completed by June 1, 2025, and set a public hearing for protests; and

WHEREAS, the City provided written notice to the owners of affect ed vacant parcels of the abatement requirements and the public hearing for protests; on April 22, 2025 the public hearing was held, and thereafter, Council adopted Resolution No. 2025- 077, which ordered the nuisances abated; and

WHEREAS, the C ity of Rocklin contracted fo r weed abatement services with Northern State Contractors, the lowest responsible bidder, and thereafter, Northern State Contractors performed abatement on the properties, and billed the City for its services between June and August 2025; and

WHEREAS, the City sent billing statements to the property owners for the costs of the nuisance abatement of their properties, and a second notice to the owners that did not respond to the first statement; and

WHEREAS, an itemized written report of parcels delinquent in paying the nuisance abatement fees as of this resolution date is attached hereto as Exhibit “A.”

NOW THEREFORE, BE IT RESOLVED by the City Council of the City of Rocklin as follows:

Section 1. The foregoing recitals are true and correct.

Section 2. A public hearing is s et for June 23, 202 6, at 6 p.m ., or as soon thereafter as the matter may be heard by the City Council of the City of Rocklin at the Council Chambers located at 3970 Rocklin Road, Rocklin, for the receipt, consideration, and confirmation of the itemized written report showing the properties delinquent in paying the costs of nuisance abatement performed between June and August 2025. At the public hearing, objections of property owners liable to be assessed for the abatement shall be heard.

38 Resolution No. 2026- May 26, 2026 Page 2 of 2
1 Section 3. Notice of the hearing shall be mailed to each affected owner of record as shown on the report by certified, return receipt mail to the address of the owners as shown on the last equalized assessment roll of the County of Placer or as otherwise known to the City of Rocklin at least ten ( 10) days prior to the hearing. This resolution shall also be posted near the Council Chambers at least five (5) days prior to the public hearing. Notice of the Public Hearing shall also be published once in the Placer Herald, a newspaper of general circulation circulated in the City of Rocklin, not less than ten (10) days before the hearing.

Section 4. The City Council may, after such hearing, and after considering any objections or protests of property owners liable to be assessed for the abatement, modify and/or confirm the report, and establish assessment liens for the delinquent abatement costs, plus City and County lien processing fees, on the secured property tax roll.

PASSED AND ADOPTED this 26th day of May, 2026, by the following vote:

AYES: Councilmembers:

NOES: Councilmembers:

ABSENT: Councilmembers:

ABSTAIN: Councilmembers:

____________________________________
David Bass, Mayor

ATTEST:

____________________________
Avinta Singh, City Clerk

39 Exhibit A

Page 1 of 1 ends

to Reso. No. 2026-

DELINQUENT WEED ABATEMENT CHARGES

*Amounts past due as of May 12, 2026 for services provided Summer of 2025. Subject to change as payments are received by City before public hearing date.

APN AMOUNT PAST
DUE*

CITY ADMIN
FEE
COUNTY

COLLECTION
FEE
TOTAL

ASSESSMENT
AMOUNT
030-140-024-000 $4,313.00 $646.95 $49.60 $5,009.55
365-020-068-000 $3,624.00 $543.60 $41.68 $4,209.28
045-031-014-000 $949.00 $142.35 $10.91 $1,102.26
045-011-012-000 $198.70 $29.81 $2.29 $230.80
045-011-017-000 $2,897.50 $434.63 $33.32 $3,365.45
371-040-024-000 $907.00 $136.05 $10.43 $1,053.48
045-021-045-000 $934.00 $140.10 $10.74 $1,084.84
010-144-010-000 $465.00 $69.75 $5.35 $540.10
017-087-011-000 $1,687.00 $253.05 $19.40 $1,959.45
010-230-008-000 $751.00 $112.65 $8.64 $872.29
045-013-022-000 $761.50 $114.23 $8.76 $884.49
045-013-005-000 $1,870.50 $280.58 $21.51 $2,172.59
010-010-028-000 $294.41 $44.16 $3.39 $341.96
010-010-017-000 $462.51 $69.38 $5.32 $537.21
010-040-040-000 $74.59 $11.19 $0.86 $86.64
010-010-016-000 $203.90 $30.59 $2.34 $236.83
010-010-029-000 $74.59 $11.19 $0.86 $86.64
010-024-002-000 $452.00 $67.80 $5.20 $525.00
030-140-003-000 $1,063.00 $159.45 $12.22 $1,234.67
017-190-045-000 $2,896.00 $434.40 $33.30 $3,363.70
016-210-011-000 $1,037.00 $155.55 $11.93 $1,204.48
045-101-059-000 $959.00 $143.85 $11.03 $1,113.88
$26,875.20 $4,031.31 $309.08 $31,215.59

40 City Council
Staff Report

Subject:

Setting a Public Hearing on Delinquent Refuse Collection Charges Date:

May 26, 2026
Submitted By:

Angela Doyle, Senior Accountant
Diane Ahn, Accounting Officer
Daniel Choe, Administrative Services Deputy Director
Department:

Administrative Services - Finance
Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Setting a Public Hearing on Delinquent Refuse Collection Charges.

Background:

Each year, pursuant to the terms of the franchise agreement with Recology Auburn Placer (Recology), the City assists Recology with the collection of delinquent solid waste collection fees within the City of Rocklin. If the fees are not paid, the City has the right, under state law, to administer special assessment liens against the properties through the County property tax bills. To begin this process, the City must first schedule a public hearing on the report of delinquent fees and notify affected landowners of the hearing.

Pursuant to Rocklin Municipal Code section 13.08.110(C) and California Government Code sections 25831 and 38790.1, refuse collection fees that remain unpaid for a period of 60 or more days after the date upon which they were billed may constitute a special assessment against the respective parcels of land and are a lien on the property.

Pursuant to the City's franchise agreement with Recology, the City shall assist with the collection of unpaid bills for services provided to customers on accounts that are more than 180 days delinquent. The City has typically assisted Recology with the collection of unpaid bills by asking the County to add these bills as levies on the property tax rolls as allowed by State law. If the City intends to impose the special assessment liens on parcels with unpaid refuse collection charges, state law requires the City first hold a public hearing and notify affected landowners.

City Council approval of the staff recommendation will set a public hearing for June 23, 2026, at 6:00 p.m., or as soon thereafter as the matter may be heard by the City Council of the City of Rocklin at the Council Chambers located at 3970 Rocklin Road, Rocklin. At the conclusion of the hearing, and after considering any objections or protests of landowners liable to be assessed for delinquent fees, the City Council will consider a resolution establishing an Item Number C5.

41 assessment on the property tax roll on those properties for which services were rendered to the owner thereof for collection of refuse collection charges.

Fiscal Impact:

The City charges a fee of 15% of delinquent charges for parcels that require the processing of a property tax lien assessment. The exact amount of the City fees associated with City collection efforts will be known for the public hearing on June 23, 2026.

ATTACHMENTS:

1. Resolution
42 Resolution No. 2026- May 26, 2026 Page 1 of 2
1 RESOLUTION NO. 2026-

RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ROCKLIN

SETTING A PUBLIC HEARING ON DELINQUENT REFUSE

COLLECTION CHARGES

WHEREAS, the City of Rocklin has a franchise agreement with Recology Auburn Placer for the collection of solid waste within the City of Rocklin; and

WHEREAS, under the terms of the franchise agreement, the City may at the request of Recology Auburn Placer, assist in collecting delinquent garbage bills in accordance with Government Code sections 25831 and 38790.1; and

WHEREAS, Recology Auburn Placer has requested the City to conduct proceedings under Government Code section s 25831 and 38790.1 to place special assessment liens against those properties’ delinquent in their solid waste collection fees.

NOW, THEREFO RE, BE IT RESOLVED by the City Council of the City of Rocklin as follows:

Section 1. The recitals set forth above are true and correct.

Section 2. The City Council hereby sets a public hearing to be held on June 23, 2026, at the City of Rocklin City Hall, located at 3970 Rocklin Road, Rocklin , on or after the hour of 6:00 p.m. At the hearing, the City Council shall consider a report of Recology Auburn Placer collection charges for parcels located in the City of Rocklin that have remained unpaid for a t least 180 days, said report to include identification of the property and an itemized record of the delinquent charge. At the hearing, Council will hear protests, modify and/or confirm the report, and consider the imposition of assessment liens on properties for delinquent solid waste collection charges.

Section 3. Notice of the hearing shall be mailed to each affected owner of record as s hown on the report by certified, return receipt mail to the address of the owners as shown on the last equalized a ssessment roll of the County of Placer or as otherwise known to the City at least ten (10) days prior to the hearing.

Section 4. The City Council may, after the hearing, and after considering any objections or protests of landowners liable to be liened f or delinquent fees, adopt a resolution establishing a special assessment lien on the property tax roll on those properties for which services were rendered to the owner thereof for collection of refuse plus City and County lien processing fees.

43 Resolution No. 2026- May 26, 2026 Page 2 of 2
1 Section 5. Notice of the Public Hearing shall be posted in one public place within the City and published on ce in the Placer Herald, a newspaper of general circulation circulated in the City of Rocklin, not less than ten (10) days before the hearing.

PASSED AND ADOPTED this 26th day of May, 2026, by the following vote:

AYES: Councilmembers:

NOES: Councilmembers:

ABSENT: Councilmembers:

ABSTAIN: Councilmembers:

____________________________________
David Bass, Mayor

ATTEST:

____________________________
Avinta Singh, City Clerk

44 City Council
Staff Report

Subject:

Position Reclassification
Date:

May 26, 2026
Submitted By:

Tameka Usher, Administrative Services Director
Department:

Administrative Services - Human Resources
Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Approving the Deletion of One Administrative Technician Allocation from the Community Development Department, and the Addition of One Administrative Analyst Allocation to the Community Development Department.

Background:

In October 2025, the incumbent Administrative Technician in the Community Development Department submitted a request for a classification review, seeking reclassification to an Administrative Analyst. A completed Position Description Questionnaire was provided to Human Resources in January 2026.

Staff conducted a classification study which included an analysis of the position’s duties, responsibilities, and interviews. The study confirmed that the predominant duties and level of responsibility is consistent with the Administrative Analyst classification. A review of the Department's needs as a result of the implementation of the Department's 2023 Organizational Assessment also indicate that the Administrative Analyst classification is supported.

Therefore, staff recommends that 1.0 FTE Administrative Technician in the Community Development Department be reclassified to the classification of Administrative Analyst. If approved, the incumbent’s salary will be set in accordance with the Memorandum of Understanding between the City and AFSCME Council 57, Local 146, representing the Public Service Employees Bargaining Unit Article 47, Section III.B (MOU). In accordance with the MOU, the incumbent shall receive the salary increase retroactive to the pay period sixty (60) days following the receipt of the acknowledgement of the completed Position Description Questionnaire.

HR satisfied the meet and confer process with the Public Service Employees Bargaining Unit represented by AFSCME regarding the proposed reclassification in accordance with the City of Rocklin Employee-Employer Resolution.

Item Number C6.

45 Recommendation:

Add 1.0 FTE Administrative Analyst
Delete 1.0 FTE Administrative Technician

Fiscal Impact:

The annual fiscal impact associated with the Administrative Technician and Administrative Analyst Salary adjustments is approximately $7,300 to the General Fund, which will be absorbed within the Department's Operating Budget.

ATTACHMENTS:

1. Resolution
46 Resolution No. 2026- May 26, 2026 Page 1 of 2
1 RESOLUTION NO. 2026-

RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ROCKLIN

APPROVING THE DELETION OF ONE ADMINISTRATIVE

TECHNICIAN ALLOCATION FROM THE COMMUNITY

DEVELOPMENT DEPARTMENT AND THE ADDITION OF

ONE ADMINISTRATIVE ANALYST ALLOCATION TO THE

COMMUNITY DEVELOPMENT DEPARTMENT

WHEREAS, the incumbent Administrative Technician in the Community Development Department requested a reclassification review; and

WHEREAS, Human Resources (HR) performed a classification study and confirmed that the predominant duties and level of responsibility is consistent with the Administrative Analyst classification; and

WHEREAS, HR recommends reclassifying one 1.0 full -time equivalent (FTE) Administrative Technician allocation to 1.0 FTE Administrative Analyst allocation in the Community Development Department; and

WHEREAS, in accordance with the Memorandum of Understanding between the City and AFSCME Coun cil 57, Local 146 Representing the Public Service Employees Bargaining Unit Article 47, Section III.B (MOU), the incumbent shall receive the salary increase retroactive to the pay period sixty (60) days after acknowledgement of the completed Job Analysis Questionnaire.

NOW THEREFORE, BE IT RESOLVED by the City Council of the City of Rocklin as follows:

Section 1. The recitals are true and correct and are incorporated herein by reference.

Section 2. The deletion of one (1.0) FTE Administrative Technician allocation from the Community Development Department , and the addition of one (1.0) FTE Administrative Analyst allocation in the Community Development Department is hereby approved.

Section 3. Effective retroactively to March 21, 2026, and in-line with the MOU, the incumbent’s salary increase is hereby approved.

47 Resolution No. 2026- May 26, 2026 Page 2 of 2
1 PASSED AND ADOPTED this 26th day of May, 2026, by the following vote:

AYES: Councilmembers:

NOES: Councilmembers:

ABSENT: Councilmembers:

ABSTAIN: Councilmembers:

ATTEST:

David Bass, Mayor

Avinta Singh, City Clerk

48 City Council
Staff Report

Subject:

The Bluffs Subdivision Road Reconstruction Phase II Bid Award Date:

May 26, 2026
Submitted By:

Richard Lawrence, Public Works Manager
Justin Nartker, Public Works Director
Department:

Public Works
Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Awarding the Contract for the Bluffs Subdivision Road Reconstruction Phase II to All Phase Construction & Engineering, Inc., and Authorizing the City Manager to Execute an Agreement with All Phase Construction & Engineering, Inc.

Background:

The Bluffs Subdivision Road Reconstruction Phase II project (Project No. 74200) is included in the 2026-2031 Capital Improvement Program approved by the City Council on June 24, 2025.

This project consists of removing and replacing aged and failing asphalt in the Bluffs Subdivision area.

The invitation for bids for the Bluffs Subdivision Road Reconstruction Phase II project was advertised on March 27, 2026, with the bid opening held on April 16, 2026. Five (5) bids were received, as shown below (see Attachment 3):

CONTRACTOR (LOCATION)
BID
All Phase Construction & Engineering, Inc. (Citrus Heights) $661,667.00
Consolidated Engineering, Inc. (Valley Springs)
$673,284.00
Central Valley Engineering & Asphalt, Inc. (Roseville)
$740,880.00
Martin General Engineering, Inc. (Rancho Cordova)
$765,004.00
B&M Civil, LLC. (Rancho Cordova)
$849,690.00

Staff reviewed the bids for completeness and responsiveness and determined that All Phase Construction & Engineering, Inc. submitted the lowest responsible bid. Staff recommends that the City Council award the contract to All Phase Construction & Engineering, Inc. In addition, a contingency amount of twenty percent (20%) of the contract, in the amount of $132,333.40, is recommended, bringing the total authorized project amount to $794,000.40.

Item Number C7.

49 Environmental Analysis:

The City of Rocklin’s Environmental Coordinator has reviewed the Bluffs Subdivision Road Reconstruction Phase II project and determined that it falls under the previously approved Notice of Exemption for City’s Road Resurfacing Projects (Resolution 2019-236) and is exempt from review under the California Environmental Quality Act (CEQA), pursuant to California Code of Regulations Sections 15301 and 15302.

Fiscal Impact:

There is no fiscal impact to the General Fund. Funding for Project No. 74200 has been appropriated as part of the FY 2026-2031 Capital Improvement Program and is budgeted within the SB1 – Road Maintenance and Rehabilitation Allocation Fund (Fund 205).

ATTACHMENTS:

1. Resolution

2. Resolution Exhibit A - Construction Agreement

3. Bid Summary
50 Resolution No. 2026- May 26, 2026 Page 1 of 2
1 RESOLUTION NO. 2026-

RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ROCKLIN

AWARDING THE CONTRACT FOR THE BLUFFS SUBDIVISION ROAD

RECONSTRUCTION PHASE II TO ALL PHASE CONSTRUCTION &
ENGINEERING, INC., AND AUTHORIZING THE CITY MANAGER

TO EXECUTE AN AGREEMENT WITH ALL PHASE
CONSTRUCTION & ENGINEERING, INC.

WHEREAS, the Bluffs Subdivision Road Reconstruction Phase II project (Project No. 74200) consists of removing and replacing aged and failing asphalt in the Bluffs Subdivision area; and

WHEREAS, the invitation for bids was advertised on March 27, 2026, with the bid opening held on Wednesday, April 16, 2026, and the bids were thereafter examined and found to be in compliance with all applicable specifications; and

WHEREAS, th e lowest responsible bid was determined to be $661,667.00, submitted by All Phase Construction & Engineering, Inc., and staff recommends that the contract for the project be awarded to All Phase Construction & Engineering, Inc.; and

WHEREAS, a contingency amount of twenty percent (20%) of the contract, in the amount of $ 132,333.40, is authorized by the City Council , and the City Manager is authorized to utilize these funds as long as adequate appropriations are available, bringing the total authorized project amount to $794,000.40; and

WHEREAS, funding for this project is included in the FY 2026-2031 Capital Improvement Program and is budgeted within the SB1 – Road Maintenance and Rehabilitation Allocation Fund (Fund 205).

NOW, THEREFORE, the City Council of the City of Rocklin d oes resolve as follows:

Section 1. The recitals set forth above are true and correct.

Section 2. The City Council hereby awards the contract for the Bluffs Subdivision Road Reconstruction Phase II project to All Phase Construction & Engineering, Inc., in an amount not -to-exceed $ 661,667.00 and authorizes t he City Manager to execute the Agreement with All Phase Construction & Engineering, Inc., in substantially the form attached hereto as Exhibit “A.”

Section 3. The City Council hereby authorizes the C ity Manager the authority to approve any reasonably necessary change orders or amendments to the agreement with All Phase Construction & Engineering, Inc., for the Bluffs Subdivision Road Reconstruction Phase II Project for the additional contingency amoun t of up to $132,333.40.
51 Resolution No. 2026- May 26, 2026 Page 2 of 2
1 PASSED AND ADOPTED this 26th day of May, 2026, by the following vote:

AYES: Councilmembers:

NOES: Councilmembers:

ABSENT: Councilmembers:

ABSTAIN: Councilmembers:

_________________________________
David Bass, Mayor

ATTEST:

____________________________
Avinta Singh, City Clerk

52 53
54 55
56 57
58 59
60 61
62 63
64 65
66 67
68 69
70 71
72 73
74 75
76 77
78 79
80 81
82 83
84 85
86 87
88 89
90 91
92 93
94 95
96 97
98 99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
© 2026 Microsoft Corporation © 2026 Maxar ©CNES (2026) Distribution Airbus DS

DAYS BEFORE YOU DIGCALL TWO WORKING
CITY OF ROCKLINPLACER COUNTY, CALIFORNIACOMMUNITY DEVELOPMENT DEPARTMENTTHE BLUFFS PHASE IIPAvEmEnT REHABILITATIOn SOUTH PLACERMUNICIPAL UTILITY DISTRICTCITY OF ROCKLINPUBLIC WORKS DEPARTMENTAPPROVED BY:APPROVED BY:DISTRICT ENGINEERDATEDIRECTORDATE

PROJECT LOCATION MAP
UTILITY REPRESENTATIVESUTILITYCOMPANYCONTACTPHONEU.S.A.-- -- (800) 642-2444GAS & ELECTRICITYP.G. & E.KEVIN MEYERS(916) 384-8092WATERPCWARICHARD WIRTH(530) 823-4886SEWERSPMUDCARIE HUFF(916) 786-8555DRAINAGECITY OF ROCKLINRICK LAWRENCE(916) 625-5521TRAFFIC SIGNALSCITY OF ROCKLINANDREW LINDNER(916) 625-5520TELECOMASTOUNDFRANK BARGIEL(916) 315-3203TELECOMATTLEE NIETO(916) 484-2384TELECOMCONSOLIDATEDLARRY MONTGOMERY(916) 786-1217

PROJECTLOCATION
VICINITY MAPSHEET INDEXDWG NO.SHT NO.DWG NAME
PLACER COUNTY WATER AGENCYAPPROVED BY:DISTRICT ENGINEERDATE 225

DAYS BEFORE YOU DIGCALL TWO WORKING
·····
226

DAYS BEFORE YOU DIGCALL TWO WORKING
227

DAYS BEFORE YOU DIGCALL TWO WORKING
228
© 2026 Microsoft Corporation © 2026 Maxar ©CNES (2026) Distribution Airbus DS

DAYS BEFORE YOU DIGCALL TWO WORKING
229
© 2026 Microsoft Corporation © 2026 Maxar ©CNES (2026) Distribution Airbus DS

DAYS BEFORE YOU DIGCALL TWO WORKING
230

DAYS BEFORE YOU DIGCALL TWO WORKING
231

DAYS BEFORE YOU DIGCALL TWO WORKING
232

DAYS BEFORE YOU DIGCALL TWO WORKING
233

DAYS BEFORE YOU DIGCALL TWO WORKING
234

DAYS BEFORE YOU DIG

CALL TWO WORKING
235

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 2

TABLE OF CONTENTS

1.00 GENERAL ..........................................................................................................................................................4

1.01 LOCATION .........................................................................................................................................................4

1.02 DESCRIPTION OF PROJECT ...........................................................................................................................4

1.03 TIME OF COMPLETION ....................................................................................................................................4

1.04 LIQUIDATED DAMAGES ...................................................................................................................................4

1.05 INSURANCE REQUIREMENTS ........................................................................................................................4

1.06 COORDINATION ................................................................................................................................................4

1.07 ORDER OF WORK ............................................................................................................................................4

1.08 HOURS OF WORK ............................................................................................................................................5

1.09 DUST CONTROL ...............................................................................................................................................5

1.10 PUBLIC NOTIFICATION ....................................................................................................................................6

1.11 PUBLIC CONVENIENCE ...................................................................................................................................6

1.12 SUBMITTALS .....................................................................................................................................................6

1.13 AS-BUILT PLANS ...............................................................................................................................................7

1.14 PROJECT APPEARANCE .................................................................................................................................7

1.15 STAGING AREA .................................................................................................................................................8

1.16 PROPERTY AND FACILITY PRESERVATION .................................................................................................8

1.17 PRECONSTRUCTION PHOTOGRAPHS ..........................................................................................................8

1.18 MEASUREMENT AND PAYMENT.....................................................................................................................8

2.00 MOBILIZATION ..................................................................................................................................................9

2.01 MEASUREMENT AND PAYMENT.....................................................................................................................9

3.00 TRAFFIC CONTROL SYSTEM ....................................................................................................................... 10

3.01 MATERIALS .................................................................................................................................................... 10

3.02 EXECUTION .................................................................................................................................................... 10

3.03 PUBLIC ACCESSIBILITY ................................................................................................................................ 11

3.04 ON-STREET PARKING ................................................................................................................................... 13

3.05 PORTABLE CHANGEABLE MESSAGE SIGNS ............................................................................................. 13

3.06 MEASUREMENT AND PAYMENT.................................................................................................................. 14

4.00 WATER POLLUTION CONTROL PLAN (WPCP) .......................................................................................... 15

4.01 WPCP PREPARATION, APPROVAL, AND UPDATES .................................................................................. 15

4.02 WPCP IMPLEMENTATION AND MAINTENANCE ......................................................................................... 16

4.03 MEASUREMENT AND PAYMENT.................................................................................................................. 17

5.00 ADJUST EXISTING FACILITIES TO GRADE ................................................................................................ 18

5.01 SPMUD REQUIREMENTS .............................................................................................................................. 18

5.02 PCWA REQUIREMENTS ................................................................................................................................ 19

5.03 EXECUTION .................................................................................................................................................... 20

5.04 MEASUREMENT AND PAYMENT.................................................................................................................. 21

6.01 EXECUTION .................................................................................................................................................... 22

6.02 MEASUREMENT AND PAYMENT.................................................................................................................. 23

7.00 HOT MIX ASPHALT ........................................................................................................................................ 24

7.01 MATERIALS .................................................................................................................................................... 24

7.02 EXECUTION .................................................................................................................................................... 25

7.03 DAILY SUBMITTAL ......................................................................................................................................... 26

7.04 MEASUREMENT AND PAYMENT.................................................................................................................. 26

8.00 TRAFFIC STRIPING AND PAVEMENT MARKINGS ..................................................................................... 28

8.01 PAVEMENT MARKERS/DELINEATORS/STRIPING/PAVEMENT MARKINGS ............................................ 28

8.02 TEMPORARY STRIPING AND PAVEMENT MARKINGS .............................................................................. 28

8.03 MATERIAL ....................................................................................................................................................... 29 236

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 3

8.04 APPLICATION ................................................................................................................................................. 30

8.05 TOLERANCES AND APPEARANCE .............................................................................................................. 30

8.06 PAVEMENT MARKERS .................................................................................................................................. 30

8.07 MEASUREMENT AND PAYMENT.................................................................................................................. 30

9.00 ELECTRICAL SYSTEMS ................................................................................................................................ 32

9.01 LOOP DETECTORS ....................................................................................................................................... 32

9.02 DETECTOR HANDHOLES ............................................................................................................................. 32

9.03 MEASUREMENT AND PAYMENT.................................................................................................................. 33

10.00 QUALITY ASSURANCE PROGRAM ........................................................................................................... 34

10.01 ACCEPTANCE TESTING ............................................................................................................................. 34

10.02 CERTIFICATE OF COMPLIANCE ................................................................................................................ 34

10.03 MEASUREMENT AND PAYMENT................................................................................................................ 35

237

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 4

1.00 GENERAL
All references to the State Standard Specifications means the 2023 State of California Standard Specifications issued by the California Department of Transportation.

1.01 LOCATION
The work under this contract is located on Portsmouth St., Leland St., Stoney Rd., Terrace Pl., Terrace Dr., Summit Dr., and Bluffs Dr. as shown on the plan sheets.

1.02 DESCRIPTION OF PROJECT
The work to be performed consists, in general, of: replacement of pavement sections through cold planing, and fiber reinforced hot mix asphalt overlay; adjusting irons within the paving limits; replacing traffic signal loops; restoring traffic striping and markings, and all other work shown in the contract documents.

1.03 TIME OF COMPLETION
For the purpose of this contract, all work for the base project under this contract shall be complete within 30 WORKING DAYS beginning on the first working day as specified in the Notice to Proceed (NTP).

1.04 LIQUIDATED DAMAGES
For the purpose of this contract, Liquidated Damages shall be set at the amount of Four Thousand Two Hundred Dollars ($4,200) per calendar day.

1.05 INSURANCE REQUIREMENTS
The Contractor is hereby made aware that these Special Provisions require no additional insurances, in addition to those required by the General Provisions.

1.06 COORDINATION
The Contractor shall coordinate his activities in a manner that will provide the least interference with the City's operations, other contractors, and utility companies working in the area.

At a minimum, the Contractor shall coordinate his operations with the following:
 City Traffic Signals and Street Lighting
Contractor shall notify Andrew Linder at the City of Rocklin (916) 919-5520, a minimum of ten (10) working days before any electrical work begins, or to coordinate placement of traffic signals into flash mode.
 Compost, Recycling and Landfill
Contractor shall notify Recology at (530) 613-5870, a minimum of ten (10) working days before any paving operations begin.

1.07 ORDER OF WORK
Order of work shall conform to the provisions in Section 5, "Control of Work," of the State Standard Specifications and these Special Provisions.
238

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 5

The following shall be performed prior to the Notice to Proceed:

1. Prepare and submit a work plan, progress schedule for all items of work and traffic and pedestrian control plans in a form provided by or acceptable to the Engineer. The work plan and schedule shall be updated weekly to reflect all items of work performed at the site and shall clearly indicate the proposed completed date. No work may begin under contract until the Progress Schedule and Traffic Control Plan have been approved by the Engineer. Time required for review and approval of these items shall not constitute a basis for time extension.

2. The prime contractor shall prepare and submit a City of Rocklin encroachment permit application to the Public Works Department located at 4081 Alvis Court. All fees for the encroachment permit will be waived.

3. Prepare and submit a Water Pollution Control Plan (WPCP), as specified in these Special Provisions, in a form acceptable to the Engineer. Work shall not commence until the plan is reviewed and approved by the Engineer.

4. Before commencement of any demolition work on the project, the Contractor shall visit each private property to verify existing conditions of private irrigation facilities that may be impacted by the project. The Contractor shall submit a log listing each address, the date of testing, and whether the existing system within the footprint of the project is functional; see the Clearing and Grubbing section of these Special Provisions for additional details.

The above item(s) shall clearly disclose the Contractor’s proposed procedures and methods of operation, including identifying any special equipment intended for use on the project and method of addressing traffic. It will be the responsibility of the Contractor to arrange for the towing and removal of any vehicles which have not been removed by the owner and which interfere with any operations.

1.08 HOURS OF WORK
The Contractor’s hours of work for this project shall be Monday to Friday 7 AM to 5 PM.

1.09 DUST CONTROL
Dust control shall conform to the provisions in Section 10-5, “Dust Control,” of the State Standard Specifications.

The Contractor shall provide adequate levels of watering to control dust as well as street sweeping. At a minimum, the Contractor shall sweep the street once a week, or more often as directed by the Engineer/Inspector, to ensure dust is controlled, especially during cold planing operations. The Contractor shall furnish all water necessary for dust control.

The Contractor shall:
 enclose, cover, or water twice daily all soil piles;
 water exposed soil with adequate frequency for continued moist soil;  water all haul roads twice daily; and
 cover loads of all haul/dump trucks securely.

The project area is serviced by Placer County Water Agency (PCWA). The Contractor shall coordinate with the water provider for a hydrant meter.
239

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 6

1.10 PUBLIC NOTIFICATION
The Contractor shall be required to notify, in writing, the public, residents, businesses, public transit companies, utility companies and any other persons or agencies affected by this project at least two (2) weeks prior to starting construction. Other notifications may be required during project construction as outlined below. City staff will coordinate with law enforcement and fire districts.

Two-Week Notice: A written notice (in letter format) to residents and businesses to provide general information about the project, approximate range of dates on when construction will take place, time of work, tree trimming requirements: “Trees shall be trimmed to a minimum height of 8’ over the sidewalk and 14’ over the street” and Contractor’s name and phone number. Notice to be approved by City prior to distributing to the public.
72-Hour Notice: Door hanger (or other approved notice) shall include date(s), times, tree trimming requirements: “Trees shall be trimmed to a minimum height of 8’ over the sidewalk and 14’ over the street” and other pertinent information as directed by the Engineer with a link to the City’s project-specific website. The notice shall include the Contractor’s name and phone number for residents and businesses to contact with any concerns after hours and on weekends. Notice to be approved by City prior to distributing to the public. Door hangers shall be provided for:
 Traffic delays and alternate routes
 Tree trimming or removals
 Driveway closures
 Water service interruptions
 Temporary relocation of bus stops

Failure to comply with the notification requirement will result in a stop work order. The Contractor shall maintain an updated and chronological record at the job site of all written notifications along with a list of recipients. Such records shall be made available upon request by the Engineer.

1.11 PUBLIC CONVENIENCE
The Contractor shall comply with Sections 7-1.03, “Public Convenience,” and 7-1.04, “Public Safety,” of the State Standard Specifications.

1.12 SUBMITTALS
The Contractor shall comply with the submittal requirements as set forth in Section 5-1.23, “Submittals,” of the State Standard Specifications and these Special Provisions.

The Contractor shall submit via the City’s online platform (e.g., Virtual Project Manager) one electronic PDF of each material submittal to the Engineer at minimum ten (10) days prior to using said material.

Submittals will be reviewed and one (1) copy will be returned to the Contractor with conditions and/or approvals.

The Contractor shall review the Quality Assurance Program section of these Special Provisions for materials requiring certificates of compliance (COCs); submit COCs with material submittals.

See individual sections for submittal requirements included in, but not limited to the following sections:

1. Progress Schedule

2. Water Pollution Control Plan

3. Traffic Control, Pedestrian Access, and Stage Construction Plan 240

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 7

4. Hot Mix Asphalt Job Mix Formula

5. Aramid Reinforcing Fibers Literature and Specifications

6. Pavement Striping and Marking Literature and Specifications

7. Pre-Construction Log of Survey Monuments

8. Log or Map of Utility Facilities Adjusted to Grade

9. Certificates of Compliance

10. Traffic Signal Literature and Specifications for Loops

11. As-Built Plans

12. Proof of Prompt Payment to All Subcontractors

13. CCTV Inspection Video of SPMUD Facilities

14. Any other items required by the City

1.13 AS-BUILT PLANS
Upon completion of the work, the Contractor shall furnish to the City a complete set of as-built plans showing all changes or deviations from the plans taking care to note the location of objects not installed at the location shown on the plans. Improvements will not be accepted by the City for permanent maintenance until the Contractor has submitted all as-built plans to the Engineer. The as-built plans shall conform to the following:

1. The plans must be stamped or otherwise noted “AS-BUILT,” be neat, clear, and readable.

2. As-built plans must contain the Contractor’s name, permanent address, date prepared, and signature.

3. Disclaimer statements of any kind that differ from the obligations and protections provided by Sections 6735 through 6735.6 of the California Business and Professions Code must not be included on the as-built plans.

1.14 PROJECT APPEARANCE
The Contractor shall maintain a neat appearance to the work. In areas visible to the public, the following shall apply:

A. When practicable, broken concrete and debris developed during construction activities shall be disposed of concurrently with its removal. Debris stockpiling is not allowed in the public right of way or on private property. If stockpiling is necessary, the Contractor is to stockpile at Contractor’s yard.

B. All streets, driveways, sidewalks, and haul routes within the project limits shall be kept clean and clear of debris, dirt and dust in a manner acceptable to the Engineer. The Contractor shall sweep works areas on a daily basis.

Failure to meet these requirements of this section may result in a “Stop Work” notice. The “Stop Work” notice will not be rescinded until the appearance of the work is acceptable to the Engineer.

At the end of each workday, all debris, branches, roots, removed fence, rubbish, and other debris in the work area shall be collected and placed in a suitable disposal bin or pile. Materials to be used later in construction shall be neatly stockpiled. All parts of the work shall be left in a neat and presentable condition at the end of the work shift.
241

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 8

1.15 STAGING AREA
The City will not provide a staging area for the work.

1.16 PROPERTY AND FACILITY PRESERVATION
Attention is directed to Section 5-1.36, “Property and Facility Preservation,” of the State Standard Specifications and these Special Provisions.

Existing hardscape, retaining walls, curb, utilities, trees, shrubs, other plants and irrigation facilities not called out on the plans to be removed, which are injured or damaged by reason of the Contractor's operations, shall be replaced or restored by the Contractor at the Contractor’s expense.

The minimum size of tree replacement shall be 24-inch box and the minimum size of shrub replacement shall be 5-gallon and maximum of 15-gallon, whichever is most appropriate for the species of plant, as determined by the Engineer. Replacement ground cover plants shall be from 1-gallon containers and shall be planted 12 inches on center. Replacement planting shall conform to the requirements in Section 20-4.03F, “Replacement Plants,” of the State Standard Specifications. The Contractor shall water replacement plants in conformance with the provisions in Section 20-4.03G, "Watering," of the State Standard Specifications. Replacement planting of injured or damaged trees, shrubs, and other plants shall be completed prior to the start of the plant establishment period.

1.17 PRECONSTRUCTION PHOTOGRAPHS
Preconstruction photographs shall be taken by the Contractor before any construction begins. Each photograph shall be taken from a point between four feet (4’) and eight feet (8’) above the ground. All photographs shall show good details in both shadow and sunlit areas. The Contractor shall submit digital photography files either in .TIF or uncompressed .JPEG raster files. All photos shall be time and date stamped to confirm existing field conditions at the time the notice to proceed with construction is issued.

The Contractor shall submit all photos taken to the City via the City’s online platform (e.g., Virtual Project Manager). Photographs shall be grouped according to street, lateral or line, and in sequence.

The views in preconstruction photographs shall include the entire construction zone and, in particular, show the interface between the right-of-way and construction zone, and abutting property features such as, but not limited to, condition of existing streets, sidewalks, driveways, fences, landscaping, buildings abutting work site, and existing surface utility facilities on and close to the work.

A sample of six (6) photographs shall be submitted to the City for approval before proceeding with the remaining photographs. All photographs which do not conform to these Special Provisions, as determined by the City, shall be retaken.

1.18 MEASUREMENT AND PAYMENT
Full compensation for conforming to the requirements of this section of these Special Provisions shall be considered as included in the prices paid for the various items of work involved and no additional compensation will be allowed therefore.
242

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 9

2.00 MOBILIZATION
Mobilization shall conform to Section 9-1.16D, “Mobilization,” of the State Standard Specifications and consist of preparatory work and operations, including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for the establishment of all facilities necessary for work on the project; and for all other work and operations which must be performed or costs incurred prior to beginning work on the various contract items on the project site.

It is the Contractor’s responsibility to plan and perform all work within the time of completion as allowed in this contract.

This section also includes all necessary permits required by the Contractor.

2.01 MEASUREMENT AND PAYMENT
Mobilization shall be measured and paid for on a LUMP SUM basis. The lump sum price paid for mobilization shall include full compensation for furnishing all labor, materials, tools, equipment, administrative cost, permit fees, and incidentals for doing all work involving mobilization as specified in these Special Provisions, the State Standard Plans and Specifications and as directed by the Engineer and no additional compensation will be allowed, therefore.

The City shall not pay additional mobilization compensation for a contract change order or for a second mobilization if the project is extended due to weather. Payment for mobilization will be subject to retention.

243

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 10

3.00 TRAFFIC CONTROL SYSTEM
This work shall include signage, flagging, traffic-handling equipment, devices and other related items to provide for safety and convenience to the public and traffic during construction.

3.01 MATERIALS
Traffic control shall conform to Section 12, “Temporary Traffic Control,” Section 7-1.03, “Public Convenience,” and Section 7- 1.04, “Public Safety”, of the State Standard Specifications, and the Manual on Uniform Traffic Control Devices, current California edition, available at the following website:
https://dot.ca.gov/programs/safety-programs/camutcd.

3.02 EXECUTION
Prior to installation of temporary traffic control devices, the Contractor shall have a field meeting with the foreman overseeing installation of traffic control and the Engineer to review the approved traffic control plans and discuss their implementation. Traffic control will be an agenda item at each weekly construction meeting.

Traffic Control Plans (hereinafter "TCP") shall be developed for the Project to assure that adequate consideration is given to the safety and convenience of motorists, pedestrians, bicyclists, and workers during construction. The TCP shall include all work within the City rights-of-way, and applicable, private streets adjacent to the construction zone. Individual TCP’s shall be submitted to the Engineer for review a minimum of ten (10) working days prior to starting any work covered by a particular TCP. Non- compliance with any stipulation of this Section will be justification for the City to stop work.

Pedestrian access shall be provided throughout construction areas within the right of way, and as appropriate, on private property where City construction may occur.

The Contractor shall notify interested parties and/or agencies required by the Engineer as to any road closures, the expected duration, and detours. City staff will notify law enforcement and fire district personnel.

Driveways shall be usable at all times, unless the Contractor has made special arrangements with the property owner to close a driveway.

The Contractor shall be solely responsible for pedestrian and vehicular movement through the project area and shall assume full liability for any and all claims arising out of the construction of the project.

All traffic control devices including, but not limited to, traffic cones or portable delineators, telescoping flag trees, arrow boards, barricades, and signs shall be placed before beginning work and shall be removed from the right-of-way at the end of each day or shift, or, for long-term closures, when no longer needed, and shall be placed so as to not obstruct bicycle lanes and pedestrian facilities. All traffic control devices left in the right-of-way by the Contractor are subject to removal by the City.

The Contractor shall be required to pay any costs incurred by the City associated with the removal of these devices. No equipment shall be parked within any traffic lanes, medians, or within the public right of way at any time of day or night, including holidays and weekends, without an approved lane or road closure. The Contractor shall notify the City a minimum of three (3) Working Days in advance of any lane closure and twenty (20) Working Days in advance of any road closure.

Flagging
244

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 11

Flaggers shall perform their duties and shall be provided with the necessary equipment in accordance with Manual and the current “Flagging Handbook” published by the American Traffic Safety Services Association (ATSSA). The equipment shall be furnished and kept clean and in good repair by the Contractor at the Contractor's expense. All flaggers shall be trained as required by Cal/OSHA Title 8, Section 1599, and proof of such training shall be made available by the Contractor upon request by the City. Any flagger, in the opinion of the City, not performing in a safe manner or in a manner conducive to public safety must be removed and replaced by the Contractor immediately.

Flaggers shall be used where necessary to control the flow of traffic through the construction site and shall be used in all cases where traffic is being routed through the construction zone under one-lane, two-way traffic controls, or when ordered by the City.

Flagging Costs
Unless specified elsewhere in these Special Provisions, the cost of furnishing all flaggers, including transporting flaggers to provide for passage of public traffic through the construction site shall be considered included in the Traffic Control System bid item and no additional compensation will be made.

3.03 PUBLIC ACCESSIBILITY
The Contractor shall provide access to the public through the project site at all times. The Contractor shall provide access to adjacent properties at all times. The Contractor shall maintain access to properties and pedestrian access even after hours for the life of the construction. Temporary access ramps shall be installed to maintain access and shall be shown on the Contractors staging plan.

The Contractor shall be responsible for designing working drawings, constructing and providing a safe and adequate continuous, accessible and safe path of travel around or through localized construction work zones and to each building, business and property utilized by the public. The Contractor shall use temporary asphalt, aggregate base, wood/metal ramps, signs, cones, barricades, flashers, and flaggers to direct and channel the public during and after construction. All proposed closures of a pedestrian access path shall be submitted in writing to the Engineer for review and approval. Advance warning shall be provided to the public should an access path be closed. All safe paths of travel shall be in compliance with Americans with Disabilities Act Accessibility Guidelines (ADAAG), Americans with Disabilities Act (ADA) regulations and the California Manual on Uniform Traffic Control Devices (CAMUTCD).

Materials
Materials used for public accessibility during construction include, but is not limited to:
 Temporary Hot-mix Asphalt Concrete (cut back asphalt concrete not permitted)  Temporary Wood Ramp
 Aluminum Modular Ramps. EZ-Access, or approved equal.

Contact info: www.ezaccess.com, Phone 800-451-1903.
 Four (4) foot wide minimum walking surface with running slope not to exceed eight (8) percent.  Barricade materials: Delineators, A-Frames, Barrier Caution Tape, Fencing Material  Non-skid tape
 Four (4) inch timber, or equivalent, at the bottom of any railing to provide for the sight impaired

Installation
Temporary ramps shall be constructed so installation and removal will not damage existing pavement, curb and/or gutter.

Temporary ramps shall have a minimum four (4) foot wide walking surface and a running slope not to exceed eight (8) percent.

245

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 12

Temporary ramps shall meet existing surfaces without gaps. When required for drainage, a Schedule 40 PVC pipe, with minimum 2-inch diameter, shall be installed under or through ramp in gutter or flow line.

Transitions between temporary ramps and the street or sidewalk surfaces shall be smooth.

Sides of the temporary ramps shall be protected where drop-offs exceed six (6) inches.

Temporary ramps shall be provided to the public leading to businesses. Temporary ramps at the corners of the intersections shall be made of temporary AC pavement to ensure that a smooth transition is provided for the public as well as auto traffic. All temporary wooden ramps shall be maintained throughout the construction project. The Contractor shall maintain the structural integrity of the ramps. No loose, splintered boards or nails will be acceptable.

Maintenance of a Clear and Accessible Public Corridor
The Contractor shall maintain a four (4) foot accessible corridor that provides at least one safe path of travel for the public at all times for the duration of the project. Conversely, if a safe path of travel is not available, the Contractor shall post the sidewalk as being closed, however, access must still be maintained to each business. Signage shall be placed at the location of closure and at the next intersection in both directions, advising of the closure but noting that access is still available to all businesses. All proposed closures of a pedestrian access path shall be submitted in writing to the Engineer for review and approval.

The Contractor shall provide a path to the businesses and residents, using aggregate base to backfill, after demolition of the concrete sidewalk, curb and gutter. The aggregate base shall be firmly packed to establish a safe and ADA compliant path, along the entire work zone.

Installation of Barricades
Barricades, which will provide protection for the public from traffic or construction operations, shall be installed in the following locations:
 Between the access route and any adjacent construction site.  Between the alternate circulation path and any adjacent construction site.  Between the alternate circulation path and the vehicular way, if the alternate circulation path is diverted into the street.
 Between the alternate circulation path and any protruding objects, drop-offs, or other hazards to the public.
 At the down curb ramp of an intersection, if opposite up curb ramp is temporarily or completely blocked, and no adjacent alternative circulation path is provided.

Surfacing of Public Corridors
During construction, tripping hazards and barriers must be removed to maintain an accessible safe path of travel. The surface of the path of travel shall be skid resistant and free of irregularities.

Opened crosswalks, ramps and walkways in general shall be kept free of debris and obstructions.

Identification of Safe Path of Travel
If alternate circulation routes are provided for the public to bypass the construction site, the route shall be clearly defined and advance warning shall be provided to clearly delineate the alternate circulation route.

Any change of level in a path of travel that is over ¼ inch (1/2” maximum) height must be beveled at 45 degrees to provide a smooth, non-tripping transition. The Engineer shall review and approve any public access limitations and notification requirements for pedestrians with mobility or vision impairments.

When using A-frames for defining a path of travel, A-frames shall be placed end to end (no spacing between barricades) to provide a continuous guide for individuals using canes. A-frames shall be connected with 246

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 13

2x4’s that are continuous and are attached to the base of the barricade system at two (2) to four (4) inches from the ground.

Caution tapes shall not be used as barricades or to define a path of travel but may be used to highlight danger or in conjunction with barricades. Excavated areas shall be secured by means of barricades or temporary fences.

The bottom three (3) inches of any fencing material used shall be made solid to act as a guide for canes used by the visually impaired. Wood, sheet metal, railings, or other approved material may be used at the bottom portion of the fence.

Curb ramps leading to closed crosswalks shall be appropriately barricaded. Temporary ramps shall be provided at temporary crosswalks and shall be able to direct blind pedestrians to and through the temporary path of travel. R9-3a and R9-3b signs shall be mounted on the barricade to advise pedestrians of closed sidewalk and directed routes.

No trucks or equipment shall be parked or obstructing the public path of travel at any time.

Warning Signs
The Contractor shall provide warning signs for temporary ramps and barricades. Warning signs shall be located at both the near side and the far side of the intersection preceding a temporarily completely blocked public way.

Restoration of Public Routes
After construction, the site shall be restored to its former condition, or new condition as required.

3.04 ON-STREET PARKING
Contractor shall furnish, install, maintain and remove “No Parking” signs in areas where the Contractor’s work will require restricted parking. The Contractor shall place notification for the elimination of on-street parking, if required, at least forty-eight (48) hours, but not more than seventy-two (72) hours prior to the start of work. The signs shall clearly show the date(s) and hours of the parking prohibition, as well as the date and time the signs were posted. The notification shall include the Contractor's phone number and the phrase "VEHICLES WILL BE TOWED PURSUANT TO CVC SECTION 22654 (d)". This notice shall be affixed to a Type II barricade that is placed in the lane of the road, near lip of gutter, (max. 200 ft. spacing) used for on-street parking. No other location or method of placement is acceptable. The notification shall be in a form approved by the Engineer. Non-compliance with any stipulation of this section will be justification for the City to stop work.

In the event that towing is required after proper notifications have been delivered and posted, and reasonable attempt have been made to the property owner or resident, the Contractor shall be responsible for contacting the Rocklin Police Department at (916) 625-5400 to dispatch a towing company. It will be the Contractor’s responsibility to determine if towing is required. The City will not be responsible for any claims made as a result of towing from the Contractor.

3.05 PORTABLE CHANGEABLE MESSAGE SIGNS
Portable Changeable Message Signs (CMS) shall be furnished, placed, operated, and maintained at locations designated by the Engineer and shall conform to the provisions in Section 12, “Temporary Traffic Control,” of the State Standard Specifications and these Special Provisions. Messages displayed on the portable changeable message signs shall be as directed by the Engineer and shall conform to Section 12-3.32 “Portable Changeable Message Signs,” of the State Standard Specifications and “Traffic Control System” of these Special Provisions.
247

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 14

A minimum of one (1) CMS board shall be placed at each entrance to the neighborhood, on Cobblestone Dr., Stoney Rd., Agate Way, and Sand St., for a minimum total of four (4) CMS boards. CMS boards shall be placed at least 7 calendar days prior to any construction activity and shall remain in place until project completion, or until approved by the Engineer to be removed beforehand. A portable changeable message sign shall be placed in advance of the first warning sign for each stationary lane closure.

Should the CMS boards need to be located on private property due to lack of room within the public right of way, the Contractor shall coordinate this effort with private property owners and furnish written proof to the City of the property owner’s acceptance.

A messaged displayed on a portable changeable message sign shall first be approved by the City.

3.06 MEASUREMENT AND PAYMENT
Traffic Control System shall be measured and paid for on a LUMP SUM basis. The lump sum price paid for Traffic Control System shall include full compensation for furnishing all labor, material, tools, equipment and incidentals, including but not limited to private property coordination as necessary, preparing and maintaining an adequate traffic control plan, furnishing portable changeable message signs, furnishing, placing, removing storing, maintaining, moving to new locations, replacing, and disposing of the components of the temporary traffic control system, as specified in these Special Provisions, and as directed by the Engineer and no additional compensation will be allowed therefore.

The City shall not pay additional traffic control compensation for a change work order or for a second mobilization if the project is extended due to weather. Payment for traffic control will be subject to retention.

The adjustment provisions in Section 4-1.05, “Changes and Extra Work,” of the State Standard Specifications, shall not apply to the item of Traffic Control System. Adjustments in the compensation for Traffic Control System will be made only for increased or decreased traffic control system required by changes ordered by the Engineer and will be made on the basis of the cost of the increased or decreased traffic control necessary. Such adjustment will be made on a force account basis as provided in Section 9-1.04, “Force Account,” of the State Standard Specifications for increased work, and estimated on the same basis in the case of decreased work.
248

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 15

4.00 WATER POLLUTION CONTROL PLAN (WPCP)
The Contractor shall develop and implement a WPCP in accordance with Section 13, “Water Pollution Control,” of the State Standard Specifications, and these Technical Specifications.

The Contractor shall generate the WPCP and submit to the Engineer for review and approval.

Within this section, references to Water Pollution Control shall be consistent with content and requirements of the Project WPCP preparation, execution, and final stabilization requirements.

Unless arrangements for disturbance of areas outside the project limits are made by the City and made part of the contract, it is expressly agreed that the City assumes no responsibility whatsoever to the Contractor or property owner with respect to any arrangements made between the Contractor and property owner to allow disturbance of areas outside the project limits.

The Contractor shall be responsible for the costs and for liabilities imposed by law as a result of the Contractor’s failure to comply with the provisions set forth in these Technical Specifications, including but not limited to, compliance with the provisions of the 2009 Approved Stormwater Quality Improvement Plan (SQIP) and Federal, State, and local regulations. For the purposes of this paragraph, costs and liabilities include, but are not limited to, fines, penalties, and damages whether assessed against the City or Contractor, including those levied under the Federal Clean Water Act and the State Porter Cologne Water Quality Act.

At reasonable times and upon presentation of credentials and other documents as may be required by law, the Contractor shall allow authorized agents of the California Regional Water Quality Control Board, State Water Resources Control Board, United States Environmental Protection Agency and the local storm water management agency to:

A. Enter upon the construction site and the Contractor’s facilities pertinent to the work; and B. Inspect the construction site and related soil stabilization practices and sediment control measures.

The Contractor shall notify the Engineer immediately upon request from the regulatory agencies to enter, inspect, sample, monitor or otherwise access the project site or the Contractor’s records.

4.01 WPCP PREPARATION, APPROVAL, AND UPDATES
The Contractor must provide a Qualified SWPPP Developer (QSD) to prepare the WPCP. The Contractor will provide a QSD and Qualified SWPPP Practitioner (QSP) to perform the testing and inspection. This does not relieve the Contractor from their duties to amend and follow the WPCP to include inspections and implementing corrections.

The Contractor shall be required to amend the WPCP and submit to the Engineer for review and comment. Erosion and sediment control shall conform to the requirements of the current edition of the “Storm Water Quality Design Manual, Sacramento Region,” which is available at the following website:
https://www.beriverfriendly.net/stormwater-quality-design-manual/ Within 20 working days of receiving a copy of the fully executed contract, the Contractor shall submit a copy of the WPCP to the Engineer. The Engineer will have 10 days to review the WPCP. If revisions are required, as determined by the Engineer, the Contractor shall revise and resubmit the WPCP to the Engineer within 15 days of receipt of the Engineer’s comments. The Engineer will have 5 days to review 249

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 16

the revisions. A copy of the WPCP shall be kept on the job site (in the job trailer) at all times.

Soil stabilization Best Management Practices (BMPs) shall be maintained on any area disturbed. All BMPs shall be installed/implemented and maintained throughout the duration of construction. These BMPs shall include (but not be limited to) the BMPs checked on the Construction Site BMPs Consideration Checklist shown in Table 1 below:

The Contractor shall provide a QSP to perform regular inspection of the site and the installed BMPs. The Contractor’s QSP shall place a record of all inspections in the project WPCP binder within 24 hours of any inspection. The project WPCP binder shall be made available to the City for review at any time during normal working hours.

Erosion and sediment control BMPs shall be placed, monitored for effectiveness, and maintained throughout the construction process.

The following precautions shall be implemented regardless of the season:

1. A stabilized construction site access should be constructed at any construction staging and/or stockpile site as determined appropriate by the Engineer.

2. Temporary stockpiling of construction materials, including vehicles and portable equipment, supplies, fuels and chemicals, will be restricted to designated construction staging areas within the project area.

3. Any wet season requirement shall be implemented if conditions exist which may cause erosion and sedimentation.

4. The Contractor shall not be limited to the requirements listed above but shall be responsible for implementing whatever measures are necessary to prevent erosion and sedimentation.

The Contractor shall recommend amendments to the WPCP, graphically and in narrative form, whenever there is a change in construction activities or operations which may affect the discharge of significant quantities of pollutants to surface waters, ground waters, municipal storm drain systems or when deemed necessary by the Engineer. The WPCP shall be amended by the Contractor’s QSD if the WPCP is in violation of any condition of the Permit or has not effectively achieved the objective of reducing pollutants in storm water discharges. Amendments shall show additional control measures or revised operations, including those in areas not shown in the initially approved WPCP, which are required on the project to control water pollution effectively. Amendments to the WPCP shall be submitted to the Engineer for review and approval in the same manner specified for the initially approved WPCP. Approved amendments shall be dated and logged in the WPCP. Upon approval of the amendment, the Contractor shall implement the additional control measures or revised operations within 3 business days or prior to any forecast rain event of 50% or greater per National Oceanic and Atmospheric Administration (NOAA).

If the project is in non-compliance at any time, the Contractor shall make a written report to the Engineer within 15 calendar days of identification of non-compliance.

4.02 WPCP IMPLEMENTATION AND MAINTENANCE
Upon approval of the WPCP, the Contractor shall be responsible throughout the duration of the project for installing, constructing, inspecting, and maintaining the control measures included in the WPCP and any amendments thereto and for removing and disposing of temporary control measures. Unless otherwise directed by the Engineer or specified in these Technical Specifications, the Contractor's responsibility for WPCP implementation shall continue throughout any temporary suspension of work. 250

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 17

Soil-disturbed area of the project site shall be not more than 1 acre. The Engineer may approve, on a case-by-case basis, expansions of the active, soil-disturbed area limit. The Contractor shall demonstrate the ability and preparedness to fully deploy soil stabilization practices and sediment control measures to protect soil-disturbed areas on the project site before the onset of precipitation. A quantity of soil stabilization and sediment control materials shall be maintained on site equal to 100 percent of that sufficient to protect unprotected, soil-disturbed areas on the project site. A detailed plan for the mobilization of sufficient labor and equipment shall be maintained to fully deploy control measures required for the protection of soil-disturbed areas on the project site prior to the onset of precipitation. A current inventory of control measure materials and the detailed mobilization plan shall be included as part of the WPCP.

Soil-disturbed areas of the project site shall be considered to be non-active whenever soil disturbance activities are to be discontinued for a period of 20 or more days and the areas are fully protected. Areas that will become non-active during the wet season shall be fully protected with soil stabilization practices and sediment control measures within 10 days of the discontinuance of soil disturbing activities or prior to the onset of precipitation, whichever is first to occur.

Soil-disturbed areas of the project site shall be fully protected at the end of each day with soil stabilization practices and sediment control measures unless fair weather is predicted through the following workday.

The Contractor shall monitor the weather forecast on a daily basis. The NOAA forecast shall be used.

Construction scheduling shall be modified, as required, and functioning control measures shall be deployed prior to the onset of the precipitation.

The Contractor shall comply with all provisions of the WPCP, including inspection and maintenance during the life of the project, including any work stoppages for any reason, including weather, holidays, moratorium, utility conflicts, etc.

If the Contractor or the Engineer identifies a deficiency in the deployment or functioning of an identified control measure, the deficiency shall be corrected immediately. The deficiency may be corrected at a later date and time if requested by the Contractor and approved by the Engineer in writing, but not later than the onset of subsequent precipitation. The correction of deficiencies shall be at no additional cost to the City.

4.03 MEASUREMENT AND PAYMENT
Water Pollution Control Plan (WPCP) shall be paid for as LUMP SUM and include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in preparing the WPCP, and installing Best Management Practices (BMP). This bid item includes implementing measures prescribed in amendments, and installing, constructing, maintaining, removing, and disposing of control measures, as shown in the plans, as specified in the State Standard Specifications and these Technical Specifications, and as directed by the Engineer.

The City of Rocklin pays a total of 40% of the lump sum price upon approval of the WPCP by the City, 55% of the lump sum price as determined by the Engineer spread across monthly pay estimates, and the final 5% as part of retention.

251

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 18

5.00 ADJUST EXISTING FACILITIES TO GRADE
Storm drain/sanitary sewer manhole covers and any other existing facility within the limits of pavement rehabilitation shall be adjusted to final grade following the placement of the top lift of hot mix asphalt.

Traffic signal detector handholes shall be preserved and protected in place unless directed otherwise on the plans.

Utility boxes/vaults requiring adjustment in the sidewalk shall be adjusted to grade concurrently with the installation of new sidewalk. Utility box/vault lids shall be protected to avoid concrete splatter or other debris from accumulating on top.

The Contractor shall adjust all storm drain manhole frames and covers in accordance with City of Rocklin Standard Drawing #3-9 and Section 78-23, “Adjust Utility Frames, Covers, and Manholes,” of the State Standard Specifications, these Special Provisions, and as directed by the Engineer.

5.01 SPMUD REQUIREMENTS
Lower and Restore to Grade SPMUD Sewer Manhole Frame & Cover (EA)

The Contractor shall adjust all South Placer Municipal Utility District (SPMUD) manhole frames and covers in accordance with Section 5.22 Manholes of the SPMUD Standard Specifications and Improvement Standard for Sanitary Sewers, latest edition, and these Special Provisions, and as directed by the Engineer.

The Contractor shall notify SPMUD at least 48 hours prior to the start of construction and shall coordinate a pre-construction conference by calling (916) 786-8555.

The Contractor shall provide SPMUD with 24-hour emergency contact information (name, title, and telephone number) prior to commencing work.

The Contractor shall obtain a no-cost Sewer Access Permit from SPMUD prior to the start of construction activities.

The Contractor shall be responsible for maintaining sanitary sewer flows and shall be liable for all SPMUD-owned sewer facilities within the project limits until construction is complete.

The Contractor shall accurately locate, reference, and mark all SPMUD sewer structures prior to any removal of castings, frames, or covers, using a method acceptable to SPMUD. Reference markings shall be maintained throughout the duration of the project. Sewer structures shall be made accessible as soon as practicable after construction. In some cases, SPMUD may require manholes to remain accessible at all times.

Manhole adjustment grade rings shall total a minimum of three (3) inches and a maximum of eleven (11) inches in height. If these limits cannot be met, replacement of the barrel or cone section may be required to achieve proper final grade, subject to SPMUD approval.

The Contractor shall implement appropriate protective measures before, during, and after such work to prevent intrusion of debris. All protective coverings shall remain in place until final paving is complete and may only be removed with SPMUD approval or at the request of SPMUD for emergency response or required maintenance.

252

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 19

Protective measures shall not interfere with or obstruct the normal function or drainage of the sewer system. All sealing, containment, or protective methods must maintain the integrity of the sewer’s hydraulic performance and be removable without damaging structures or restricting flow.

Prior to any paving or overlay activities—including but not limited to grinding, cold planing, and asphalt overlay—all SPMUD sewer manholes, cleanouts, and appurtenances within the project area shall be clearly identified and adequately protected to prevent the entry of debris, asphalt, or other construction- related material into the public sewer system. Manhole covers shall be tightly sealed using methods and materials approved by SPMUD.

Any damage to SPMUD-owned frames and covers resulting from removal, adjustment, or construction activities shall be the Contractor’s responsibility. Damaged structures shall be replaced in-kind at the Contractor’s sole expense, in accordance with SPMUD Standard Specifications and Improvement Standards for Sanitary Sewers, subject to SPMUD inspection and approval.

All SPMUD-owned manholes are classified as Permit-Required Confined Spaces (PRCS) under California Code of Regulations, Title 8, Sections 5156–5159. It is the responsibility of the Owner/Developer, as the Host Employer, to ensure that any contractor or subcontractor entering a confined space complies with applicable confined space entry requirements.

Any contractor performing work involving confined space entry into SPMUD facilities must:

1. Possess a written Confined Space Entry Program in full compliance with Title 8 CCR §§ 5156–5159,

2. Adhere to all SPMUD procedures related to Permit-Required Confined Space Entry,

3. Coordinate with SPMUD prior to entry and obtain approval for work involving access to SPMUD sewer manholes.

No entry into SPMUD-owned confined spaces shall occur without full compliance with SPMUD’s PRCS protocols and regulatory requirements.

Flush/Clean SPMUD Sewer System

The Contractor shall clean and flush the system post-construction, which shall be coordinated with SPMUD upon completion of roadway work. The flushing operation is intended to remove incidental dust or fines resulting from paving activities.

If construction-related debris or foreign material is observed entering the sewer system during the course of work, the Contractor shall immediately cease operations and shall be fully responsible for the immediate removal of the material at their own expense. SPMUD reserves the right to require such remedial action prior to allowing further work near affected sewer facilities.

5.02 PCWA REQUIREMENTS
The Contractor shall adjust all Placer County Water Agency (PCWA) facility frames and covers in accordance with PCWA Improvement Standards 2017 Edition (https://www.pcwa.net/business/standards), and these Special Provisions, and as directed by the Engineer.

The Contractor shall contact PCWA Inspector 48 hours prior to commencement of initial construction, and again by 7:30 AM each day work on PCWA facilities occurs. 253

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 20

5.03 EXECUTION
A. Frames, covers and grates of existing manholes, or other facilities, shall be adjusted to grade in accordance with the provisions of 71-5.03B, “Frames, Covers, Grates, and Manholes,” of the State Standard Specifications, and the unit price bid shall include all necessary excavation, backfilling, sealing, and concrete and that the unit price shall be the average depths and limits of adjustment required.

B. The Contractor shall cooperate and coordinate all adjustments with the various utility owners when adjusting their facilities.

C. Work shall also include the provision of lowering structures in advance of cold planning, in accordance with these Special Provisions.

D. Work shall include protecting all facility covers from adherence of asphalt concrete to the cover during the paving operation. This may be accomplished by means of removal of the cover and placement of a temporary traffic rated lid, placement of heat resistant barrier material on the cover or other method approved by the Engineer. If asphalt concrete is found to be bonded to the cover after paving is complete, the Contractor is responsible for removing all asphalt from the cover to the satisfaction of the Engineer or replace the cover at the Contractor’s sole cost and expense.

E. Contractor shall raise to finished grade all facilities located within the limits of pavement rehabilitation following the placement of the top layer of asphalt concrete. No structure shall be adjusted to finished grade until the paving operation adjacent to the facility has been completed.

F. Contractor shall be solely responsible for locating, referencing, and setting marks for all valve and manhole frames and covers, and survey monuments and spikes. Survey monument boxes and spikes shall be located and referenced by or under the direction of a licensed land surveyor or licensed civil engineer legally authorized to practice land surveying. Contractor shall submit a neat and accurate plan to the Engineer, at least two (2) working days in advance of any asphalt concrete paving, showing all reference marks and offset distances set for each facility.

G. The final adjustment to finished grade of all manhole frames and covers may be accomplished with reinforced concrete grade rings or formed concrete in the throat area. Existing structure pre- cast elements, adjustment rings, frames, and covers removed in adjustments may be reinstalled only when such undamaged items are permitted by the Engineer. Cast iron extension or adjustment rings will not be allowed in the adjusted structure.

H. Water valve covers, and other facility covers shown on the plans shall be raised in accordance with PCWA Improvement Standards. If the existing frame and cover is determined to be unsuitable for reinstallation due to the Contractor’s damage, it shall be replaced with a new one at Contractor expense. In this situation, the Contractor shall immediately notify the Engineer.

I. Survey monument boxes shall be adjusted to finished grade by or under the direction of a licensed land surveyor or licensed civil engineer legally authorized to practice land surveying and included for payment in the bid item for adjusting survey monument boxes as specified elsewhere in these Special Provisions.

J. Survey spikes shall be reset at finished grade by or under the direction of a licensed land surveyor or licensed civil engineer legally authorized to practice land surveying and included for payment in the bid item for adjusting survey monument boxes as specified elsewhere in these Special Provisions.

K. When exposing the facility to be raised to grade, Contractor shall cut the new asphalt pavement by such method necessary to result in a clean-cut line and prevent raising the lip of the asphalt to remain. For all adjustments, the top surface of the adjusted facility shall be within 1/8 inch of the adjacent finished grade.
254

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 21

L. Work shall include placement of temporary asphalt around the facilities if the permanent concrete collar or asphalt concrete patching cannot be placed the same day the facility is raised to grade.

M. Finished concrete collars shall have an integral dark black color (no surface coloring). The color shall be obtained by adding powdered Davis Colors Graphite (Carbon) 8084, powdered Solomon Colors 908 Carbon Black or other equal, approved by the Engineer, to the 6-sack PCC mix at a ratio of 12 lbs per 1 cubic yard. Submittal: Contractor shall provide a mix design for the colored concrete collars. The same mix design shall be used throughout the project for utility adjustments.

N. Extreme care shall be taken to prevent asphalt concrete from entering the drainage or sanitary sewer system.

O. The Engineer may require the Contractor to immediately remove manhole covers for inspection to determine if any asphalt has fallen into the manhole. The Contractor shall be required to immediately remove all asphalt and/or construction debris from the manhole's interior.

P. Adjustments to all utility covers will be performed within 5 working days from the date the final lift of asphalt concrete overlay is applied to that roadway segment. Failure to adjust utility covers within the time period allowed, the Contractor shall pay liquidated damages of $200 per calendar day for each utility cover not adjusted.

Q. Adjusting manholes to grade within publicly used traffic lanes must be completed, including placing paving material around and to the level of the frame and cover, by the end of the same day on which work is started. If permanent pavement backfill cannot be completed by the end of the work day, the Contractor must place temporary paving material to the finished grade level of the frame and cover. The Contractor must maintain the temporary paving smooth and level with the frame and cover until the permanent paving is placed.

5.04 MEASUREMENT AND PAYMENT
Resetting of survey spikes as shown in the bid schedule shall be measured and paid for per EACH. The contract unit price paid for resetting each survey spike shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals and for performing all the work involved in resetting each survey spike at final grade, including locating, referencing, and setting marks both before and after construction activity as specified in the State Standard Specifications and these Special Provisions, and as directed by the Engineer, and no additional payment will be allowed therefore.

Adjustment of utility irons and survey monument boxes as shown in the bid schedule shall be measured and paid for per EACH. The contract unit price paid for adjusting each frame and cover to grade shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals and for performing all the work involved in lowering the frame and cover to accommodate cold planing operations and adjusting the frame and cover to the final grade complete in place, including locating, referencing, and setting marks, as specified in the State Standard Specifications and these Special Provisions, and as directed by the Engineer, and no additional payment will be allowed therefore. The unit price for adjusting sanitary sewer manhole frames and covers shall be identical to the unit price bid for adjusting City storm drain manhole frames and covers.

6.00 COLD PLANING
The Contractor shall perform cold planing at the locations and to the depths shown on the plans, and as directed by the Engineer. All work shall be in accordance with Section 39-3.04, “Cold Planing Asphalt Concrete Pavement,” of the State Standard Specifications, these Special Provisions and as directed by the Engineer.
255

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 22

6.01 EXECUTION
A. Planing asphalt concrete pavement shall be performed by cold planing. The cold planing machine shall have a cutter head not less than 30” wide and shall be operated so as not to produce fumes or smoke. The cold planing machine shall be capable of planing the pavement without requiring the use of a heating device to soften the pavement during or prior to the planing operation.

B. For all cold planing operations, the final cut shall result in a uniform surface conforming to the typical cross-sections. The outside lines of the planed area shall be neat and uniform. The road surfacing to remain in place shall not be damaged in any way. The planed road surface shall not be damaged or spalled.

C. Planed widths of pavement shall be continuous except for intersections at cross streets where the planing shall be carried around the corners and through the conform lines.

D. The depth of the cold planing shall taper down starting 6’ from the existing lip of gutter so the depth at the lip of gutter is 1/4” less than the nominal thickness of the final overlay to be applied to the roadway (e.g., final overlay = 4” then depth of cold plane at lip of gutter = 3¾”).

E. The depth of the cold planing shall taper down starting 50’ from a transverse conform so the depth at the conform to the existing pavement is equal to the nominal thickness of the final overlay to be applied to the roadway.

F. Frames, covers and grates of existing manholes, water valves, survey monuments or other facilities within the cold planing limits shall be ‘tied down’ and lowered prior to cold planing operations unless to be protected in place. See other sections of these Special Provisions for adjusting utility irons to grade.

G. If permanent asphalt concrete has not been placed to the level of existing pavement before the pavement is to be opened to public traffic, a temporary asphalt concrete taper shall be constructed. Asphalt concrete for temporary tapers shall be placed to the level of the existing pavement and tapered in two (2) feet to the level of the planed area or as directed by the Engineer.

Asphalt concrete for tapers shall be commercial quality and may be spread and compacted by any method that will produce a smooth riding surface. Asphalt concrete tapers shall be completely removed, including removing all loose material from the underlying surface, before placing the permanent surfacing.

H. All material planed from the roadway surface, including material deposited in existing gutters, adjacent traveled way, or catch basins, shall be immediately removed from the surface and disposed of off-site as directed in these Special Provisions or by the Engineer. The removal crew shall follow within 150 feet of the cold planer.

I. All planed material, not used as backfill or shoulder backing on this project, shall be transported and properly disposed of off-site. Transport and off-loading of material shall be considered incidental and included in the unit price paid for this item.

J. This item of work shall also include cold planing driveway tapers.

K. The limits of the designated area for cold planing shall be marked on site. However, should there be any doubt as to areas marked for cold planing, the Contractor shall consult immediately with the Engineer.

256

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 23

L. The required cold planing is to be performed without disturbing the existing curb and gutter. Any concrete gutter chipped by the cold planing operations shall be repaired at the Contractor’s expense.

M. Contractor shall assure that all cold planed roadways are cleaned, and free from rock and debris at all times. All cold planed streets shall remain safe and passable. The City shall be held harmless to any vehicle/property damage or injury that may occur due to the Contractors work.

6.02 MEASUREMENT AND PAYMENT
Cold Planing shall be a final pay item based upon the estimated quantity in SQUARE FEET indicated in the Bid Proposal. Cold planing performed outside of the design measurements as marked in the field will be at the Contractor’s expense.

The square foot price paid for Cold Planing shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in cold planing, removing and disposing of existing asphalt concrete, installation and subsequent removal of temporary tapers, and compaction of subgrade, complete in place, all as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer, and no additional compensation will be allowed therefore.

257

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 24

7.00 HOT MIX ASPHALT
The Contractor shall furnish and install hot mix asphalt (HMA) for crack repair sections, and fiber reinforced HMA for all overlay applications at the locations and to the depths shown on the plans in accordance with Section 39-2, “Hot Mix Asphalt,” of the State Standard Specifications, and these Special Provisions.

For streets to receive an HMA overlay, all existing striping, markings, and markers shall be fully removed.

The Contractor is referred to the Traffic Striping and Pavement Markings section of these Special Provisions for additional information on striping removal.

7.01 MATERIALS
The Contractor shall submit in writing to the Engineer a complete mix design as described in Section 39-

2.01A(3)(b), “Job Mix Formula,” of the State Standard Specifications. Mix designs must include the name of the material plant, the product name, a mix design ID number, and item of work in which it is to be used.

Hot mix asphalt shall be Type A with 1/2" aggregate.

All asphalt binder shall be PG 64-10 and shall conform to the requirements of Section 92, “Asphalt Binders,” of the State Standard Specifications. The Contractor’s mix design shall include aramid fibers per the manufacturer’s recommendation. Reinforcing fibers shall be high tensile strength aramid fiber blend specially formulated to reinforce HMA.

The Contractor shall have the fiber manufacturer’s representative on site during mixing and production.

This requirement can be waived if fiber manufacturer and asphalt producer can supply evidence of manufacturer’s brand of fiber being successfully produced a minimum of three times at the asphalt plant to be used for the project. Mix fibers per manufacturer’s recommendation.

The Contractor shall furnish and install an emulsified asphalt (Type SSI) tack coat conforming to Sections 39-2.01C(3)(f), “Tack Coat,” and 94, “Asphaltic Emulsions,” of the State Standard Specifications.

The Contractor shall submit certification from the supplier that the material he is furnishing has been properly tested within the last 6 weeks and designed so as to meet the aforementioned specifications.

Cost of any such testing shall be the responsibility of the Contractor and/or supplier. Once a supplier's material has been found acceptable, the Contractor shall furnish material from no other source without the prior approval of the Engineer in writing.

Pre-Approved Products & Suppliers:

Product: ACE XP Fiber™ and AQU Fiber™
Supplier: Surface Tech LLC
Contact: Pat Weaver, COO / CRO
Phone: (602) 919-4851
Email: [email protected]
Address: 312 S. Cedros Ave, S200
258

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 25

Solana Beach, CA 92075

Product: Forta-Fi Asphalt Fiber
Supplier: Forta
Website: https://forta-fi.com/products/forta-fi/

The Contractor shall verify that the mix design, with ID number written on weighmaster tags, delivered to the job site matches the approved mix design. If the mix design ID numbers do not match, the product shall be rejected at no cost to the City.

7.02 EXECUTION
The HMA structural section in areas of roadway widening shall be brought to the elevation of the adjacent existing pavement before overlay is placed. The overlay joints on the top lift shall overlap the joint between the new and the existing pavement.

Surface preparation and tack coat application shall be in accordance with the State Standard Specifications. The surfaces upon which asphalt concrete is to be placed shall be thoroughly cleaned of all dirt, vegetation, and debris.

Prior to application of tack coat, the street shall be cleaned with a vacuum street sweeper and be clean of all dust.

Existing paved surfaces shall be given a tack coat by spraying with penetration type emulsified asphalt at the rate of 0.05 to 0.10 gallon per square yard as directed by the Engineer.

The HMA shall be placed in 3-inch maximum lifts after compaction. Conform sections shall be squared off and hand raked to a neat straight line. Edges at curb shall be hand raked and rolled with a small roller or tamper when larger roller cannot be used.

Spreading and Compaction

1. Vehicles used for hauling HMA mixtures must have tight, smooth, metal beds, and must be free from dust, screenings, excessive petroleum oils, volatiles, or other mineral spirits that may affect the mix being hauled. Trucks must be provided with tarpaulins or cargo covers of sufficient size and weight to protect the entire load.

2. Should the methods and equipment furnished by the Contractor fail to produce a layer of HMA conforming to the requirements, including straightedge tolerance, of Section 39-2.01C(2), “Spreading and Compacting Equipment,” of the State Standard Specifications, the paving operations shall be discontinued, and the Contractor shall modify his equipment or furnish substitute equipment.

Finishing Roadway

1. The completed surface shall be thoroughly compacted, smooth, and true to grade and cross section, free from ruts, humps, depressions or irregularities. When a straight edge 12 feet long is laid on the finished surface and parallel with the center line of the highway, the surface shall not vary more than 0.01 feet from the lower edge of the straight edge. When tested 259

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 26

transversely to traffic, the surface shall incline continuously in the direction of the drainage so that no depressions, which will not drain, remain in the surface after rolling. Any ridges, indentations or other objectionable marks left in the surface of the HMA by equipment shall be eliminated by rolling or other means. The use of any equipment that leaves ridges, indentations or other objectionable marks in the HMA shall be discontinued and other acceptable equipment shall be furnished by the Contractor.

2. Half-width surfacing operations shall be conducted in such manner that, at the end of each day’s work, the distance between the ends of adjacent surfaced lanes shall not be greater than can be completed in the following day of normal surfacing operations.

3. Finishing roadway shall conform to Section 22, “Finishing Roadway,” of the State Standard Specifications. The entire roadway and right-of-way shall be left in a neat and presentable condition to the satisfaction of the Engineer.

4. Temporary pavement markings shall be installed for all roadway centerlines, stop lines and channelizing lines following the final lift of HMA. Temporary pavement markers shall be the same color as the lane line or centerline markers being replaced. Temporary pavement markings shall comply with ‘Temporary pavement markers for short term day/night use (14 days or less) of Section 12-6, “Temporary Pavement Delineation,” of the State Standard Specifications. The costs of temporary pavement markings or floppies are included in the asphalt concrete bid item.

Testing and Certification
During the work, the City may periodically sample and test the furnished material to ensure quality assurance in accordance with the City’s Quality Assurance Program. The Contractor will perform all required quality control testing. The City will assume the cost of all quality assurance testing, however, the Contractor will be required to pay for all failing test.

7.03 DAILY SUBMITTAL
The Contractor shall submit HMA Weighmaster’s Certificates as the material arrives at the job site, or at any time upon request of the Engineer. If the Contractor does not submit the Certificates at the end of the day when HMA is installed, a temporary stop work order may be issued on the paving operation with no associated cost incurred by the City. The paving operation may resume with the Engineer’s written approval upon receiving and reviewing the Certificates.

7.04 MEASUREMENT AND PAYMENT
Hot Mix Asphalt Overlay as determined by Weighmaster’s Certificates, shall be per TON and shall include full compensation for furnishing all the labor, materials, tools, equipment, incidentals, and for doing all the work involved in furnishing and installing fiber reinforced hot mix asphalt, including production, delivery, placement, and compaction of fiber reinforced HMA, complete in place, including tack coat, pre- overlay preparation, and all incidental work, as shown on the project plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer, and no additional compensation will be made therefore.

Quantities of material wasted or disposed of in a manner not called for under the contract, or rejected loads of material, including material rejected after it has been placed by reason of the failure of the Contractor to conform to the provisions of the contract, or materials placed outside the lines indicated from the transporting vehicle, or material remaining on hand after completion of the work, will not be paid for and such quantities will be deducted from the final total quantities. No compensation will be allowed 260

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 27

for hauling rejected material. The final weighmaster tag shall note the amount of tonnage to be deducted from the pay estimate.
261

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 28

8.00 TRAFFIC STRIPING AND PAVEMENT MARKINGS
Traffic stripes and pavement markings, of the various colors indicated on the plans (white or yellow), shall be installed in accordance with these Special Provisions and Section 84, “Markings,” of the State Standard Specifications.

The Contractor shall install cat-tracks at least two (2) working days ahead of, and receive approval from the Engineer prior to, installation of any permanent striping and pavement markings.

New, permanent traffic striping shall be installed on the roadway within five (5) working days after final paving operations.

Thermoplastic stripes and pavement markings shall not be placed over utility covers including, but not limited to, manhole covers, utility boxes, traffic signal detector hand holes, or water valves covers.

Thermoplastic traffic stripes and pavement markings shall be free of runs, bubbles, craters, drag marks, stretch marks, and debris.

Retroreflectivity of the thermoplastic traffic stripes and pavement markings shall conform to the requirements in ASTM Designation: D6359-99. White thermoplastic traffic stripes and pavement markings shall have a minimum initial retroreflectivity of 250 mcd⋅m-2⋅lx-1. Yellow thermoplastic traffic stripes and pavement markings shall have a minimum initial retroreflectivity of 150 mcd⋅m-2⋅lx-1.

8.01 PAVEMENT MARKERS/DELINEATORS/STRIPING/PAVEMENT MARKINGS The Contractor shall remove all existing traffic stripes and pavement markings from within the limits of the streets or private properties to be overlaid and/or seal coated in accordance with Section 84-9, “Existing Markings,” of the State Standard Specifications.

The Contractor’s attention is directed to the “Lead Compliance Plan” section of these Special Provisions for additional information, including the testing and disposal of yellow thermoplastic traffic stripes.

Sandblasting of traffic stripes shall not be permitted. Removal of traffic stripes shall be by grinding, or by other methods approved in writing by the Engineer. Drain inlets adjacent to areas to be ground shall be protected from grinding entering the storm drain system.

For removal of pavement markings, a rectangular area shall be ground to prevent ghosting of the original markings. Conflicting striping shall be removed completely.

All striping or pavement markings damaged during construction shall be repaired at the Contractor’s expense. Repairs shall consist of complete replacement of markings or legends, replacement of sections of striping, and replacement of damaged or missing markers as directed by the Engineer.

8.02 TEMPORARY STRIPING AND PAVEMENT MARKINGS
The Contractor shall supply and install temporary striping to control traffic until permanent striping and pavement markings are installed. All temporary striping, pavement markings, tape, floppies, etc. shall be removed when no longer needed to safely direct traffic.

Painted white striping/pavement markings shall conform to Section 84-2.03B(6), “Paint,” of the State Standard Specifications.

262

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 29

The Contractor is not required to remove painted temporary traffic stripes that will be covered by paving work.

Full compensation for furnishing and installing temporary striping and pavement markings is included in the prices paid for the various items of work involved and no additional compensation will be allowed therefore.

8.03 MATERIAL
Thermoplastic shall be Alkyd type for extrusion application and shall produce an adherent reflectorized strip capable of resisting deformation by traffic.

Thermoplastic material shall be free of lead and chromium and shall conform to the requirements in State Specification PTH-02ALKYD.

The thermoplastic material shall be 100 percent solids. The binder shall consist of synthetic alkyd resins and shall be homogeneously incorporated with all the necessary prime pigments, fillers, and glass beads to produce a traffic coating to meet the requirements as specified herein.

Characteristics of Finished Thermoplastic:

White Yellow
Glass Beads, AASHTO M-247, Type I, percent by
weight, min. (Cal. Test Method 423)
30 30
Titanium Dioxode (TiO2), percent by weight, min.
(AASHTO T250-77)
10 Lead Chromate, Medium Heat Stability, percent by
weight, min.

2.5 Specific Gravity, max. (Cal. Test Method 423) 2.15 2.15 Binder, percent by weight, min.
(Cal. Test Method 423)
18 18
Ring & Ball Softening Point, °F (ASTM E28) 200-240 200-240

Bond Strength to Concrete, 0.125-inch-thick film
drawdown at 425°F test at 75°F + 2°F, psi, min
(Cal. Test Method 423)
180 180
Brookfield Thermosel Viscosity, Spindle SC4-27, 20
RPM at 425°F, Poise (Cal. Test Method 423)
30 – 45 30 – 45
Impact Resistance, Falling Ball Method, 0.125-inch-thick film drawdown at 425°F on concrete. Test at 75°F + 2°F
inch-lbs., (ASTM D2794)
10 10
Daylight Luminous Reflectance, min. (ASTM E97) 75 40 Yellowness Index, max., (ASTM E313) .15 Hardness, Shore A-2 Durometer with 2-kilogram weight
at 115°F (Cal. Test 423)
60 – 80 60 – 80
Low Temperature Stress Cracking, Resistance at 25°
(AASHTO)
No Crack No Crack
Color Match, Federal Std. No. 595a, Color No. 33538 Passes 263

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 30

8.04 APPLICATION
Thermoplastic Traffic Striping Material, Alkyd Binder, White and Yellow. All thermoplastic must be applied per Section 84-2.03B(2)(b), “Extruded Thermoplastic,” of the State Standard Specifications.

The Contractor shall apply an adhesive primer base coat prior to the application of any thermoplastic material on treated pavement, stamped pavement, colored pavement, concrete surfaces, or pavement older than 30 days.

Unless otherwise specified in these Special Provisions, the thermoplastic material for traffic stripes shall be applied at a minimum thickness of 0.075-inch. Thermoplastic Material for pavement markings shall be applied at a minimum thickness of 0.125-inch. Glass beads shall be applied immediately to the surface of the molten thermoplastic material, at a rate of not less than 8 lbs. per 100 sq. ft. The amount of glass beads applied shall be measured by stabbing the glass beads tank with a calibrated rod.

8.05 TOLERANCES AND APPEARANCE
The completed traffic stripes and markings shall have clean and well-defined edges without deformations and shall be free of tears or other disfigurements. Improperly placed, defective, or disfigured traffic stripes and markings shall be immediately removed from the pavement surface by methods approved by the Engineer. All such removal work shall be at the Contractor's expense.

Completed traffic stripes shall be uniform, shall be straight on tangent alignment, and shall be on a true arc on curved alignment. On tangent alignment, when a 100' string line is stretched taught and placed directly on the outer edge of the completed traffic stripe, the distance between the string and the edge of the traffic stripe shall not exceed three-fourths of one inch (3/4") when measured anywhere along any 100' interval of the tangent alignment. On curved alignment, the outer edge of the traffic stripe shall not deviate more than three-fourths of one inch (3/4") from the true arc. The lengths of the gaps and individual stripes that form broken traffic stripes shall not deviate more than 2" from the lengths required to produce a uniformly repeating, broken-stripe pattern.

8.06 PAVEMENT MARKERS
Pavement markers shall be placed in conformance with the provisions in Section 84, “Markings,” of the State Standard Specifications and these Special Provisions.

Retroreflective pavement markers shall comply with the specific intensity provisions for reflectance after abrading the lens surface in conformance with the “Steel Wool Abrasion Procedure” specified for pavement markers placed in pavement recesses in Section 81-3.02C, “Retroreflective Pavement Markers,” of the State Standard Specifications.

Blue raised reflective fire hydrant markers with two reflective faces shall be included in this item of work. Hydrant markers shall be placed in the street, 6”-12” off the centerline and perpendicular to the fire hydrant.

8.07 MEASUREMENT AND PAYMENT
Thermoplastic Traffic Stripes (Bid Item by Detail) shall be measured and paid for by the LINEAR FOOT, for the various detail numbers referenced in the project plans, along the line of the traffic stripes, without deductions for gaps in broken traffic stripes. The price shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved in furnishing and installing traffic stripes, including pavement markers, blue reflective pavement markers identifying fire hydrants (included in Detail 22 cost regardless of which street a hydrant is located on), replacement of damaged stripes, 264

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 31

and pavement surface preparation, all per the project plans, State Standard Plans/Specifications, and these Special Provisions, and no additional compensation will be allowed therefore.

Thermoplastic Pavement Markings including letters, turn arrows, symbols, limit lines, and crosswalks shall be measured and paid for by the SQUARE FOOT, which price shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all work involved in placing pavement markings, replacement of damaged pavement markings, and pavement surface preparation, all per the project plans, State Standard Plans/Specifications, and these Special Provisions, and no additional compensation will be allowed therefore.

The square foot area of pavement markings will be determined from the most recent State Standard Plans.

Removal of existing traffic stripes shall be included in the various items of work involved and no separate payment shall be allowed therefore.
265

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 32

9.00 ELECTRICAL SYSTEMS
The work shall conform to the provisions of Sections 86, "Electrical Work," and 87, “Electrical Systems,” of the State Standard Specifications, the information shown on the Plans, City of Rocklin Standard Drawing #8-5, and these Special Provisions.

In general, the work consists of the following items:

1. Installation of inductive loop detectors; and

2. Installation of a detector handhole

Traffic signal work is located at the following location:

1. Stanford Ranch Rd./Stoney Rd.

9.01 LOOP DETECTORS
The Contractor shall be responsible for locating and marking the positions of all traffic signal loops. All locations shall be approved by the Engineer before any work is performed.

The Contractor shall coordinate with the City of Rocklin’s Traffic Control and Lighting Technician, Andrew Linder, at 916-625-5520 or [email protected]. Work on or near existing traffic loops shall be meticulously planned and coordinated to identify the minimal impact necessary.

Once existing traffic loops are removed, the Contractor shall furnish and install temporary video camera detectors to maintain traffic signals in continuous operation until new traffic loops can be installed.

All vehicle detectors shall be cut in and be inductive loop detector Type “A” and “D”.

Loop wire shall be Type 2 as noted in Section 86-1.02F(2)(c)(iii), “Inductive Loop Conductors,” of the State Standard Specifications and be THWN or XHHW, in polyethylene, or vinyl, tubing, # 14 stranded copper.

Lead-in cable shall be Type B copper per Section 86-1.02F(3)(d)(iii), “Detector Lead-in Cables,” of the State Standard Specifications.

Inductive loop detector includes a completely installed loop or group of loops in the roadway, and a lead- in cable installed and connected inside a controller cabinet. Vehicle detection loops shall be cut into the newly paved asphalt surface within 72 hours following paving operations. Contractor shall furnish loop continuity test results to the City within 24 hours of splicing.

Verify in the presence of the Engineer or Traffic Supervisor that the loops are operational before making the final splices between loop conductors and the lead-in cable.

Identify and tag each lead-in cable with the detector designation at the cabinet and pull box adjacent to the loops.

9.02 DETECTOR HANDHOLES
Detector Handholes shall be installed in accordance with these Special Provisions and Plan ES-5D, of the State Standard Plans.

266

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 33

9.03 MEASUREMENT AND PAYMENT
Installation of loop detectors shall be measured and paid for per EACH. The contract unit price paid for installation of the loop detectors as shown on the plans shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals for doing all the work involved to construct a complete and functioning traffic signal loop detection system at the various traffic signals, complete and in place.

The work shall include, but is not limited to, supplying and installing traffic signal loops, loop wire, detector lead-in cables (DLCs) where existing DLCs are unable to be reused at the sole discretion of the Engineer, termination inside controller cabinets of DLCs, coordination with City of Rocklin staff to confirm proper vehicle detection, and all incidentals, as shown on the plans, as detailed in the State Standard Specifications, these Special Provisions and as directed by the Engineer and no additional payment shall be allowed therefore.

Installation of detector handholes shall be measured and paid for per EACH. The contract unit price paid for installation of the detector handholes as shown on the plans shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals for doing all the work involved, complete and in place. The work shall include, but is not limited to, supplying and installing detector handholes, as shown on the plans, as detailed in the State Standard Specifications, these Special Provisions and as directed by the Engineer and no additional payment shall be allowed therefore.

267

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 34

10.00 QUALITY ASSURANCE PROGRAM
The City has a Caltrans approved Quality Assurance Program (QAP), which can be found in appendix A, that will ensure the materials and workmanship incorporated into the construction project conform to the requirements of the contract plans and Special Provisions, including approved changes.

Material testing and sampling noted in the QAP shall be done in accordance with California Test Method (CTM) procedures. The QAP specifies which CTM to follow depending upon the material in question.

10.01 ACCEPTANCE TESTING
At a minimum, and as outlined in the City’s QAP, the following materials shall be sampled and tested for acceptance into the project:

1. Hot Mix Asphalt

2. Hot Mix Asphalt (Aggregates)

3. Aggregate Base

4. Soil Subgrade

See Attachment 1, Acceptance Sampling and Testing Frequencies, in the QAP for frequency tables.

The Contractor shall coordinate with the Engineer or batch plant for material sampling and testing. The City’s independent consultant shall have full access to all areas of the worksite necessary to fulfill the requirements of the City’s QAP.

Whenever failing tests occur, sufficient additional acceptance tests must be taken to isolate the affected work. Documentation of the results of such additional tests must be included in the City’s records, including a description of the corrective measures taken by the Contractor. Any material tested and found out of compliance with these Special Provisions and the QAP shall be removed and replaced at no cost to the City.

For clarification purposes, the City’s materials testing consultant will complete Local Assistance Procedures Manual (LAPM) Exhibit 16-Z2, Acceptance Testing Results Summary Log, outlining the results of all testing, a copy of which can be provided to the Contractor upon request.

Compaction testing of hot mix asphalt shall be per State Standard Specifications and while aggregate base shall achieve 95% relative compaction.

10.02 CERTIFICATE OF COMPLIANCE
The Contractor shall review Local Assistance Procedures Manual (LAPM) Exhibit 16-T1, Materials Requiring a Certificate of Compliance per Caltrans Standard Specifications, and submit certificates of compliance (COCs) for all materials listed which are to be used in the construction of this project. The current version of this form is located at the following website: https://dot.ca.gov/programs/local- assistance/forms/local-assistance-procedures-manual-forms.

COCs shall be project specific (no generic forms accepted), approved before material is incorporated into the project, and include, at a minimum, the following information:

 Statement that the material complies with the specifications;  Certified material lot number matching lot tags affixed or stenciled to the released materials; and  Signature of authorized manufacturer representative.
268

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 35

COCs shall be approved by the City prior to any progress payments being made to the Contractor for the material covered by the COC.

10.03 MEASUREMENT AND PAYMENT
Full compensation for conforming to the requirements of this section of these Special Provisions shall be considered as included in the prices paid for the various items of work involved and no additional compensation will be allowed therefore.

269

SPECIAL PROVISIONS

THE BLUFFS PHASE II
PAVEMENT REHABILITATION SPECIAL PROVISIONS - 36

Appendix A

270
', ,
·�\-i..... ... --.1\.·,_i_ ____ __
Construction Quality
Assurance Program
City of Rocklin
State of California

ROCKLIN
CALIFO�NIA
July
2023-2028
• ,
Approved:
_______________________
Hunter Young, City Engineer
License #: C76228 (Expires 6/30/2024)
Date: 6/30/2023
271
i

TABLE OF CONTENTS
Table of Contents .......................................................................................................................................... 1

1.0 INTRODUCTION ................................................................................................................................. 1

1.1 Purpose and Scope ........................................................................................................................ 1

2.0 APPLICABILITY ................................................................................................................................... 1

3.0 APPROVAL ......................................................................................................................................... 1

4.0 TESTING REQUIRED ........................................................................................................................... 1

4.1 Acceptance Testing ....................................................................................................................... 2

4.2 Timing ............................................................................................................................................ 2

4.3 Test Methods ................................................................................................................................ 2

4.4 Frequency...................................................................................................................................... 2

4.5 Tests to be Performed .................................................................................................................. 2

4.6 Test Result Reporting Guidelines .................................................................................................. 2

4.7 Summary Logs ............................................................................................................................... 2

4.8 Minor Quantities ........................................................................................................................... 3

4.9 Re-testing ...................................................................................................................................... 3

5.0 INDEPENDENT ASSURANCE SAMPLING AND TESTING (IAST) ........................................................... 3

5.1 Applicability ................................................................................................................................... 3

5.2 IAST Testers ................................................................................................................................... 3

5.3 Frequency of IAST ......................................................................................................................... 3

6.0 TESTING OF MANUFACTURED AND ASSEMBLED MATERIALS .......................................................... 4

6.1 Certificate of Compliance .............................................................................................................. 4

6.2 Applicable Materials ..................................................................................................................... 4

6.3 Source Inspection .......................................................................................................................... 4

6.4 Documentation ............................................................................................................................. 4

6.5 Re-Testing ..................................................................................................................................... 4

7.0 COORDINATING SAMPLING AND MATERIAL TESTING ...................................................................... 5

7.1 Construction Documents ................................ .................................................................................... 5

7.2 Sampling and Testing Options ............................................................................................................ 5

7.3 Engineer in Charge .............................................................................................................................. 5

7.4 Contractor Influence ........................................................................................................................... 5 272
i
i

7.5 Certification of Laboratory Personnel ................................................................................................. 5

7.6 Laboratory Equipment Calibration...................................................................................................... 5

7.7 Records................................................................................................................................................ 6

7.8 Project Certification ............................................................................................................................ 6 APPENDIX A ................................................................................................................................................... 7 APPENDIX B ................................................................................................................................................. 10 Exhibit 16-T1: Materials Requiring a Certificate of Compliance per Caltrans Standard Specifications .......................................................................................................................................... 11 273
1 CONSTRUCTION QUALITY ASSURANCE PROGRAM

1.0 INTRODUCTION
This document presents the Quality Assurance Program guidelines for the City of Rocklin (City).

1.1 PURPOSE AND SCOPE
This Quality Assurance Program (QAP) is a sampling and testing program that will provide assurance that the materials and workmanship incorporated into the City’s construction projects are in conformance with the contract specifications. This program should be updated every five years or more frequent if there are changes of the testing frequencies or to the tests themselves. The following elements of the QAP are procedures for:
• Acceptance Testing (AT)
• Independent Assurance Sampling and Testing (IAST)
• Testing of Manufactured Materials

2.0 APPLICABILITY
This QAP applies to City projects off the National Highway System (NHS) and off the State Highway System (SHS).

On-NHS Projects
On-NHS projects are governed by Caltrans’ FHWA-a pproved QAP, found in Section 16.11 of the 2023 Local Assistance Procedures Manual (LAPM), Chapter 16.

Off-NHS Projects
Off-NHS Federally funded projects are governed by the procedures of this City of Rocklin QAP. Its use is mandatory for Federal-aid projects and is recommended for other City street and hig hway projects. This local QAP is based upon the requirements for local QAP’s contained in the aforementioned Section 16.11 of the LAPM and the Caltrans QAP Manual.

3.0 APPROVAL
This local QAP has been approved by the City Engineer, who is a registered Civil Engineer. It shall be kept on file and available for review.

4.0 TESTING REQUIRED
General
This local QAP describes procedures for three types of required testing. 274
2 4.1 ACCEPTANCE TESTING
This Section provides procedures for regular testing of materials entering a construction project to verify that the materials, or products, comply with contract specifications or standards.

4.2 TIMING
Sampling should begin as soon as materials are placed on a project. Testing should be performed promptly to enable data evaluation and necessary measures to be taken by the Resident Engineer (RE) and contractor.

4.3 TES T METHODS
Both California and American Society of Testing and Materials (ASTM) test methods are acceptable.

4.4 FREQUENCY
Sampling and testing shall occur in accordance with the attached frequency tables (Appendix A). The tables are intended as a guide: the actual quality of materials tested may justify decreasing or increasing the frequency of subsequent similar samples and tests.

4.5 TESTS TO BE PERFORMED
The tests to be performed shall be in accordance with Caltrans Standard Specifications as modified by the project Special Provisions, except as modified in writing by the City Engineer. As a guideline, the following tests comprise a minimum scope for commonly used materials:
• A
ggregate Base: Sieve Analysis, Sand Equivalent, R-Value, and Durability for each new source. • Aggregate Sub-base: Sieve Analysis, Sand Equivalent, and R-Value • Asphalt Concrete: Maximum Density, In-Place Density (relative compaction) at the site. • Concrete: Compressive Strength, minimum of three cylinders per sample.

4.6 TES T RESULT REPORTING GUIDELINES
Results should be submitted to the RE within five (5) working days of sampling, or as dictated by the construction schedule. Results may be expedited by transmitting via fax, telephone, or email.

4.7 SUMMARY LOGS
Materials Testing Summary Logs shall be maintained by the Resident Engineer (RE) for each material requiring multiple sampling and testing. Log data shall include date, time, station location, test sample depth, approximate quantity of sample material, test result, and tester.
275
3 4.8 MINOR QUANTITIES
Relatively minor quantities of materials from a known reliable source may be accepted with testing if:
• The RE performs visual examination of materials, or
• The manufacturer
or supplier certifies that the material furnished complies with specification requirements.
• The manufacturer or supplier has recently furnished similar materials found to be satisfactory using normal sampling and testing requirements.

Such records of acceptance shall be placed in the RE’s project files with related inspection notes.

Examples of maximum “minor” quantities” include (From LAPM 16.11):
• Bituminous material: 100 gallons per project
• Aggregates used for other than Portland cement concrete: 100 tons per day or 500 tons per project. • Bituminous mixtures: 50 tons per day or 500 tons per project

4.9 RE- TESTING
Failing test results require re-testing to isolate the failed area. The log summary shall cross reference the re-test to the initial failed test.

5.0 INDEPENDENT ASSURANCE SAMPLING AND TESTING (IAST)
Definition
The purpose of these procedures is to verify that Acceptance Testing is being performed correctly and reliably, and to ensure that equipment is properly calibrated.

5.1 APPLICABILITY
IAST procedures are required for federally funded projects on and off the National Highway System (NHS). For on- NHS projects LAPM 16.11 procedures apply. For off-NHS projects, the City will verify that its consultant laboratory’s QAP includes IAST procedures for “testing the testers”. IAST procedures are optional, and may be required at the discretion of the City Engineer, for non-federally funded projects.

5.2 IAST TESTERS
Only persons holding an Independent Assurance Sampler Tester Certificate may perform IAST. These may include individually certified Caltrans or City Resident Engineer (RE) or laboratory personnel of consultant testers. Testers shall be free of conflict of interest if also performing other testing work.

5.3 FREQUENCY OF IAST
The IAST frequency shall be as specified in the consultant laboratory’s QAP for each project where IAST is required. 276
4 6.0 TESTING OF MANUFACTURED AND ASSEMBLED MATERIALS
Definition
This section provides methods for inspecting, accepting and testing materials that are manufactured or prefabricated off the project site.

6.1 CERTIFICATE OF COMPL IANCE
The City may accept manufactured products, materials, or assemblies if accompanied by a Certificate of Compliance (COC), provided they do not involve structural integrity or safety to the public. Such Certificate shall be signed by the manufacturer and shall state that materials and workmanship conform in all respects to the proj ect specifications for the material.

6.2 APPLICABLE MATERIALS
Contract documents shall specify that materials require a Certificate of Compliance (or optional Source Inspection).

Materials Accepted by Certificate of Compliance are listed in Appendix B of this QAP.

6.3 SOURCE INSPECTION
As an alternative to a Certificate of Compliance, the City or its consultant, may perform a Source Inspection in accordance with LAPM 16.11. Caltrans no longer provides source inspection for projects off the State Highway System (SHS).

6.4 DOCUMENTATION
The COC must be furnished before the material is incorporated into the work and must include:
• Project Number
• Certified material lot number matching lot tags affixed or stenciled to the released materials • Manufacturer’s signature
• A statement that the material complies with the specifications of the contract All materials accepted on the basis of a signed COC shall be documented in the inspector’s daily reports. The Resident Engineer shall ensure that COC’s are furnished with material deliveries and are kept in the RE’s project file.

6.5 RE- TESTING
Manufactured products, materials or assemblies used on the basis of a Certificate of compliance may be sampled again at the job site and tested at any time during the life of the contract. Items found not in conformance with contract requirements must be rejected whether in place or not. 277
5 7.0 COORDINATING SAMPLING AND MATERIAL TESTING

7.1 CONSTRUCTION DOCUMEN TS
The City does not provide its own testing and inspection of materials. Pro visions for such services shall be arranged prior to advertising a project and addressed appropriately in the construction documents.

7.2 SAMPLING AND TES TING OPTIONS
The City may select from the following sources to perform sampling and testing:
• Another agency’s laboratory
• Caltrans’ laboratory
• Private consultant laboratory

7.3 ENGINEER IN CHAR GE
All laboratories shall be under the responsible engineering management of a California registered professional engineer who shall verify results of tests performed under their supervision.

7.4 CONTRACTOR INFLU ENCE
The contractor shall not select of exercise any authority over the laboratory utilized.

7.5 CERTIFICATION OF LABORATORY PERSONNEL
The following certification requirements shall apply:
• Current certification is required for the following sampling and testing personnel: construction management/inspection, l ocal agency, consultant laboratory and their sub-consultants. • For off-NHS projects, certification of pe rsonnel for AT and IAST shall be either Caltrans or similar certification acceptable to the City Engineer.
• Certificates for personnel on a project shall be retained in the Resident Engineer’s (RE) project files. • Sampling and testing by an uncertified person is acceptable upon assurance by the RE that t he unc
ertified person is competent to perform the work.

7.6 LABORATORY EQUIP MENT CALIBRATION
The City shall obtain documentation of consultant laboratory’s calibration of its equipment in accordance with LAPM 16.11 and nationally recognized calibration standards. The laboratory is responsible for performing the calibrations and providing such records to the City. Calibration of laboratory equipment (E.g. sand cones, scales, moisture tests, slump cones, air meters) shall occur on regular, appropriate intervals not exceeding one year. 278
6 7.7 RECORDS
City’s QAP and consultant’s QAP material record of samples and tests, material releases, and certificates of compliance for a project shall be incorporated into the RE’s project files. For Federally funded projects, records shall be retained for a period of three (3) years.

7.8 PROJECT CERTIFICATION
Upon project completion, the RE shall complete and sign a “Materials Certificate” (Caltrans LAPM Exhibit 17-G ).

The Certificate shall be retained in the project construction files. All non -conforming materials must be explained and justified on the Certificate.
279
7 APPENDIX A

ACCEPTANCE SAMPLING AND TESTING FREQUENCIES
280

8 Portland Cement Concrete (PCC)
Materials to
be Sampled or
Tested
Sample Size Sampling/Testing Frequency Typical Test
Methods
Description or
Comments
Freshly Mixed
Concrete
(Sampling)
Approx. 150 ob.
(or 1 cu. Ft.) near
mixer discharge
When tests are required, take at least
one sample for each 500 to 1000 cubic
yards (CY) of PCC
ASTM C172,
C685
CTM 539

Freshly Mixed
Concrete
(Testing)
Approx. 150 ob.
(or 1 cu. Ft.) near
mixer discharge
On projects with 500 CY or more test
at least on sample per job.

ASTM C143 Slump Test
Freshly Mixed
Concrete
(Testing)
Approx. 150 ob.
(or 1 cu. Ft.) near
mixer discharge
On projects with 500 CY or more test
at least on sample per job.

ASTM C360 Ball Penetration
Freshly Mixed
Concrete
(Testing)
Approx. 150 ob.
(or 1 cu. Ft.) near
mixer discharge
On projects with 500 CY or more test
at least on sample per job.

ASTM C231
CTM 504
Air content
Freshly Mixed
Concrete
(Testing)
Approx. 150 ob.
(or 1 cu. Ft.) near
mixer discharge
Fabricate at least three (3) concrete
cylinders per sample. Test for
compressive strength at least once for
each 500 to 1000 CY of structural
concrete.

ASTM C39
CTM 521
Fabricate 6”x12”
cylinders. Test at 7
days, and 28 days.

Soils and Aggregates
Materials to
be Sampled or
Tested
Sample Size Sampling/Testing Frequency Typical Test
Methods
Description or
Comments
Aggregate
(Sampling)
One 50 lb.
sample
Take one sample for every 500 to 1000
tons of material
ASTM D75
CTM 125
Random sampling
Fine
Aggregates
(Testing)
One 50 lb.
sample
Take one sample for every 500 to 1000
tons of material
ASTM C128
CTM 208
Specific Gravity
Fine
Aggregates
(Testing)
One 50 lb.
sample
Take one sample for every 500 to 1000
tons of material
ASTM C128
CTM 207
Bulk Specific
Gravity and
absorption
Course
Aggregate
(Testing)
One 50 lb.
sample
Take one sample for every 500 to 1000
tons of material
CTM 206 Cleanness
Course
Aggregate
(Testing)
One 50 lb.
sample
Take one sample for every 500 to 1000
tons of material
ASTM C127
CTM 227
Specific Gravity
and Absorption
Soils and
Aggregates
(Testing)
One 50 lb.
sample
Take one sample for every 500 to 1000
tons of material
ASTM C136
CTM 202
Sieve analysis
Soils and
Aggregates
(Testing)
One 50 lb.
sample
Take one sample for every 500 to 1000
tons of material
ASTM D2419
CTM 217
Sand Equivalent
Soils and
Aggregates
(Testing)
One 50 lb.
sample
Take one sample for every 500 to 1000
tons of material
ASTM D3744
CTM 229
Durability Index
Soils and
Aggregates
(Testing)
One 50 lb.
sample
Take one sample for every 500 to 1000
tons of material
ASTM D2844
CTM 301
R – Value
Soils and
Aggregates
(Testing)
One random
location for every
2500 sq. ft.

Take one sample for every 500 to 1000
tons of material
ASTM D2922
CTM 231
Field Density using
a nuclear gage
Soils and One random Take one sample for every 500 to 1000 ASTM D3017 Water content 281

9 Aggregates
(Testing)
location for every
2500 sq. ft.
tons of material CTM 231 using a nuclear
gage
Soils and
Aggregates
(Testing)
One (1) 50 lb.
sample
Take one sample for every 500 to 1000
tons of material
ASTM D1557 Maximum density
and optimum
moisture content
Asphalt Concrete
Materials to
be Sampled or
Tested
Sample Size Sampling/Testing Frequency Typical Test
Methods
Description or
Comments
Asphalt
Concrete
(Sampling)
Obtain one (1)
30-lb. sample
each day of
production
Obtain one sample at the asphalt
concrete plant for each 5000 tons of
asphalt concrete placed
ASTM D75,
D140, D979
CTM 125
---
Asphalt
Concrete
(Testing)
Obtain one (1)
30-lb. sample
each day of
production
At least one sample for each 5000 tons
of asphalt concrete placed
ASTM D1188,
D1560,
D1561,
D5361
CTM 304
Maximum density
and relative
compaction
Asphalt
Concrete
(Testing)
Obtain one (1)
30-lb. sample
each day of
production
At least one sample for each 5000 tons
of asphalt concrete placed
ASTM C117,
D2172
Gradation
Asphalt
Concrete
Sample any test
location
(random)
One test for every 1000 tons of asphalt
concrete placed
ASTM D2950
CTM 375
Field density by
nuclear gage
Asphalt
Concrete
One (1) 10-lb.
sample
One sample per day ASTM D1560,
D1561
CTM 366
Stability

282
10 APPENDIX B
EXHIBIT 16-T1: CONSTRUCTION MATERIALS REQUIRING A

CERTIFICATE OF COMPLIANCE PER CALTRANS STANDARD

SPECIFICATIONS
283

Local Assistance Procedures Manual Exhibit 16-T1
Materials Requiring a Certificate of Compliance per Caltrans Standard Specifications Exhibit 16-T1: Materials Requiring a Certificate of Compliance per Caltrans Standard Specifications Caltrans 2018 Standard
Specifications
Material Additional Info and/or
Attachments Required*
6-1.04 BUY AMERICA
6-1.04B Crumb rubber COC
6-1.04C Steel and iron materials COC + cert. mill test reports 11-2 WELDING QUALITY CONTROL
11-2.03D Welding COC
12-3 TEMP. TRAFFIC CONTROL DEVICES
12-3.03A(3) Plastic traffic drums COC
12-3.20A(3) Type K temporary railing COC
12-3.23A(3) Attenuator COC
12-3.32A(3) Portable CMS COC
13-2 WATER POLLUTION CONTROL PROGRAM
13-9 TEMP. CONCRETE WASHOUTS
13-9.01C Fabric bags for gravel-filled bags COC
Plastic liner COC
13-10 TEMP. LINEAR SEDIMENT BARRIERS
13-10.01C Fiber rolls COC
Silt fence fabrics COC
Sediment filter bags COC
Foam barriers COC
Fabric for gravel-filled bags COC
16-2.03 TEMP. HIGH -VISIBILITY FENCES
16-2.03A(3) High-visibility fabric COC
18 DUST PALLIATIVES
18-1.01C Dust suppressant COC
Dust control binders COC
Fibers COC
20 LANDSCAPE
20-2 IRRIGATION
20-2.08A(3) Polyethylene pipe COC
Plastic pipe supply line COC
* For those materials requiring additional information on or with the COC, see specification. Page 1 of 8 January 2021
284

Local Assistance Procedures Manual Exhibit 16-T1
Materials Requiring a Certificate of Compliance per Caltrans Standard Specifications Caltrans 2018 Standard
Specifications
Material Additional Info and/or
Attachments Required*
20-3 PLANTING
20-2.08A(3) Sod COC
Soil amendment COC
20-5 LANDSCAPE ELEMENTS
20-5.03A(1)(c) Filter fabric COC + product data
20-5.03D(1)(c) Solidifying emulsion COC + product data & samples 20-5.04A(3) Wood mulch COC + sample & authorization
21-2 EROSION CONTROL WORK
21-2.01C(1) Straw COC
Weed-free straw COC + cert. of quarantine
Fiber COC

RECP COC
Fasteners COC
Hydraulically applied erosion control materials Submit records 21-2.01C(2) Compost Submit reports
21-2.01C(3) Seed Submit reports
21-2.01C(4) Tackifier COC
Bonded fiber matrix COC
24 STABILIZED SOILS
24-1.01C(1) Stabilizing agent COC + sample
24-3 CEMENT STABILIZED SOIL
24-3.01C Cement COC + sample
36-2 BASE BOND BREAKER
36-2.01C Base bond breaker COC
37 BITUMINOUS SEALS
37-1.01C Asphalt binder COC + test results
Asphalt emulsion COC + test results
37-3 SLURRY SEALS AND MICRO-SURFACINGS
37-3.01A(3) Asphaltic emulsion COC + samples & test results Polymer modified asphaltic emulsion COC + samples & test results Micro-surfacing emulsion COC + sample & test results
37-2.04 ASPHALT RUBBER BINDER CHIP SEALS
37-2.04A(3) Asphalt rubber binder ingredients COC + permits & submittals * For those materials requiring additional information on or with the COC, see specification. Page 2 of 8 January 2021
285

Local Assistance Procedures Manual Exhibit 16-T1
Materials Requiring a Certificate of Compliance per Caltrans Standard Specifications Caltrans 2018 Standard
Specifications
Material Additional Info and/or
Attachments Required*
37-5 PARKING AREA SEALS
37-5.01C Parking area seal material COC + sample & test results 37-6 CRACK TREATMENTS
37-6.01C Crack treatment materials COC or sample & test results 39-2 HOT MIX ASPHALT
39-2.01A(3)(f) Liquid antistrip COC + sample & production data 39-2.03A(3)(c) Crumb rubber modifier COC + test results Asphalt modifier COC + test results
39-2.05A(1)(c) Asphaltic emulsion COC + test results
40 CONCRETE PAVEMENT
40-1.01C(2) Tie bars COC
Splice couplers for threaded bars COC
Dowel bars COC
Tie bar baskets COC
Joint filler COC
Epoxy-powder coating COC
41 EXISTING CONCRETE PAVEMENT
41-5 JOINT SEALS
41-5.01C Liquid joint sealant COC + SDS & instructions
Backer rods COC + SDS & instructions
Compression joint seal COC + SDS & instructions
Lubricant adhesives COC + SDS & instructions
41-10 DRILL AND BOND BARS
41-10.01C Tie bars COC
Dowel bars COC
Dowel bar lubricant COC
Chemical adhesive COC
Epoxy powder coating COC
48-2 FALSEWORK
48-2.01C(1) Structural composite lumber COC + submittals 49-2 DRIVEN PILING
49-2.02A(3)(d) Steel pipe piles COC + tests & mill reports 49-2.03A(3) Structural shape steel piling COC + test reports * For those materials requiring additional information on or with the COC, see specification. Page 3 of 8 January 2021
286

Local Assistance Procedures Manual Exhibit 16-T1
Materials Requiring a Certificate of Compliance per Caltrans Standard Specifications Caltrans 2018 Standard
Specifications
Material Additional Info and/or
Attachments Required*
51 CONCRETE STRUCTURES
51-1.01C(3) Bonding materials COC or sample & authorization 51-2 JOINTS
51-2.01A(3) Polyethylene material for snowplow deflectors COC 51-2.02B(1)(c) Sealant COC + test reports & samples
51-2.02C(1)(c) Elastomeric joint seal COC + test reports Lubricant-adhesive COC + test reports
51-2.02D(1)(c) Joint seal materials COC + authorization 51-2.02E(1)(c)(iii) Joint seal assembly materials COC
51-2.02F(1)(c)(iv) Material used in the joint seals COC + test reports 51-2.04A(3) Waterstop material COC + a statement
51-3 BEARINGS
51-3.02A(3)(c) Elastomer for bearing pads COC + test reports 51-4 PRECAST CONCRETE MEMBERS
51-4.01C(1) Concrete box culvert COC
52 REINFORCEMENT
52-1.01C(3) Reinforcement (rebar) COC + mill test report 52-2 EPOXY-COATED REINFORCEMENT
52-2.02A(3)(c) Epoxy-coated reinforcement COC + submittals Patching material COC + a statement
52-5.01C(4) Headed bar reinforcement COC + test reports 52-6 SPLICING
52-6.01C(5) Service or butt splice material COC + submittals 54 WATERPROOFING
54-3 PREFORMED MEMBRANE WATERPROOFING
54-3.01C Preformed membrane sheet COC + report
54-5 DECK SEAL
54-5.01C Preformed membrane sheet COC + report
57-2 WOOD STRUCTURES
57-2.01A(3) Timber and lumber COC + report
Glued laminated timbers/decking COC
57-3 PLASTIC LUMBER STRUCTURES
57-3.01C(1) Plastic lumber COC + test report & sample
* For those materials requiring additional information on or with the COC, see specification. Page 4 of 8 January 2021
287

Local Assistance Procedures Manual Exhibit 16-T1
Materials Requiring a Certificate of Compliance per Caltrans Standard Specifications Caltrans 2018 Standard
Specifications
Material Additional Info and/or
Attachments Required*
58-2 MASONRY BLOCK
58-2.01C(7) CMUs COC
Aggregate for grout COC
Grout COC
59 STRUCTURAL STEEL COATINGS
59-1.01C Blast cleaning material COC + SDS
59-5 THERMAL SPRAY COAT STRUCTURAL STEEL
59-5.01C(1) Wire feedstock COC
60-3.04B POLYESTER CONCRETE OVERLAYS
60-3.04B(1)(c) Methacrylate resins COC + samples & test report Polyester resins COC + samples & test report
Aggregates COC + samples & test report
61-2 CULVERT AND DRAINAGE PIPE JOINTS
61-2.01C Joint systems COC + test results & reports
Couplers COC
64 PLASTIC PIPE
64-1.01C Plastic pipe COC + report
65-2 REINFORCED CONCRETE PIPE
65-2.01C RCP, direct design method COC + report
66 CORRUGATED METAL PIPE
66-1.01C Corrugated steel materials COC
Corrugated aluminum materials COC
67-3 METAL LINE PLATE PIPE
67-3.01C Metal liner plate pipe COC + mill test reports 68 SUBSURFACE DRAINS
68-1.01C Subsurface drain COC
68-2 UNDERDRAINS
68-2.01C Pipe COC
Tubing COC
Fittings COC
68-7 GEOCOMPOSITE DRAIN SYSTEMS
68-7.01C Geocomposite drain COC + flow capability graph * For those materials requiring additional information on or with the COC, see specification. Page 5 of 8 January 2021
288

Local Assistance Procedures Manual Exhibit 16-T1
Materials Requiring a Certificate of Compliance per Caltrans Standard Specifications Caltrans 2018 Standard
Specifications
Material Additional Info and/or
Attachments Required*
69 OVERSIDE DRAINS
69-1.01C Steel pipe piles COC
Aluminum COC
Plastic COC
70-6 GRATED LINE DRAINS
70-6.01C Grated line drains COC + docu. & inspec. report 71-3.09 MACHINE SPIRAL WOUND PVC PIPELINERS
71-3.09A(1)(c) Reel of PVC strip COC + report
72-16 GABIONS
72-16.01C Gabion basket COC
PVC coating COC + identify
75-3 MISCELLANEOUS BRIDGE METAL
75-3.01C(1) Anchorage devices COC
75-3.01C(2) BRIDGE DECK DRAINAGE SYSTEM
75-3.01C(2) Fiberglass pipe and fittings COC
80-3 CHAIN LINK FENCES
80-3.01C Protective coating system COC
Posts and braces COC + test results
81 MISCELLANEOUS TRAFFIC CONTROL DEVICES
81-2 DELINEATORS
81-2.01C Metal target plates COC
Enamel coating COC
81-3 PAVEMENT MARKERS
81-3.01C Pavement markers COC
82 SIGNS AND MARKERS
82-2 SIGN PANELS
82-2.01C Aluminum sheeting COC
Retroreflective sheeting COC
Screened-process colors COC
Nonreflective, opaque, black film COC
Protective overlay film COC
* For those materials requiring additional information on or with the COC, see specification. Page 6 of 8 January 2021
289

Local Assistance Procedures Manual Exhibit 16-T1
Materials Requiring a Certificate of Compliance per Caltrans Standard Specifications Caltrans 2018 Standard
Specifications
Material Additional Info and/or
Attachments Required*
82-5 MARKERS
82-5.01C Metal target plates COC
Enamel coating COC
Retroreflective sheeting COC
83-3 CONCRETE BARRIERS
83-3.01C Type 60K portable concrete barrier COC or test reports 84-2 TRAFFIC STRIPES AND PAVEMENT MARKINGS
84-2.01C Thermoplastic COC + autho., SDS & data sheet
Paint COC + autho., SDS & data sheet
Glass beads COC + autho., SDS & data sheet
Thermoplastic primer COC + test results

DIVISION X ELECTRICAL WORK
86-1.01C(6) Signal heads COC + test data
Visors COC + test data
87-2 LIGHTING SYSTEMS
87-2.01C High mast lighting luminaires COC + test data
90 CONCRETE
90-1.01C(3) Cementitious materials COC + app. signature Blended cement COC + app. signature
90-1.01C(4) Admixture COC + authorization
90-1.01C(5) Curing compound COC + test samples
90-2 MINOR CONCRETE
90-2.01C Minor concrete COC + weighmaster cert
90-3 RAPID STRENGTH CONCRETE
90-3.01C(3) Aggregate COC + certified weight
Cementitious materials COC + certified weight
Admixtures COC + certified weight
90-4 PRECAST CONCRETE
90-4.01C(2) and
90-4.01D(2)(a)
Cementitious materials COC + app. signature
Precast members (each) COC + app. signature
Curing compound COC + test samples
94 ASPHALTIC EMULSIONS
94-1.01C Asphaltic emulsion COC + reports
* For those materials requiring additional information on or with the COC, see specification. Page 7 of 8 January 2021
290

Local Assistance Procedures Manual Exhibit 16-T1
Materials Requiring a Certificate of Compliance per Caltrans Standard Specifications Caltrans 2018 Standard
Specifications
Material Additional Info and/or
Attachments Required*
95 EPOXY
95-1.01C Epoxy COC
96 GEOSYNTHETICS
95-1.01C(1) Geosynthetic COC + test samples
* For those materials requiring additional information on or with the COC, see specification. Page 8 of 8 January 2021
291
292
City Council
Staff Report

Subject:

Park Drive Dig Outs Bid Award
Date:

May 26, 2026
Submitted By:

Rick Lawrence, Public Works Manager
Justin Nartker, Public Works Director
Department:

Public Works
Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Awarding the Contract for the Park Drive Dig Outs Project to JB Bostick Company and Authorizing the City Manager to Execute an Agreement with JB Bostick Company.

Background:

The Park Drive Dig Outs project is part of the Pavement Management Program (Program No. 50007) and is included in the 2026-2031 Capital Improvement Program and the Fiscal Years (FY) 2025-2027 Operating Budget, both approved by the City Council on June 24, 2025. This project consists of removing existing asphalt concrete surfacing and underlying base material and replacing the removed surfacing and base material with new asphalt concrete on various roads within the City.

The bid for the Park Drive Dig Outs Project was advertised on March 13, 2026, with the bid opening on Wednesday, April 1, 2026. Ten (10) bids were received from the following companies (see Attachment 3):

CONTRACTOR (LOCATION)
BID
JB Bostick Company (Roseville)
$216,392.00
Central Valley Engineering & Asphalt, Inc. (Roseville)
$236,398.00
RNR Paving, Inc. (Hayward)
$240,312.49
Martin General Engineering, Inc. (Rancho Cordova)
$295,495.00
Martin Brothers Construction (Sacramento)
$308,264.00
Action Asphalt & Concrete (Sacramento)
$313,055.00
LaFleur Engineering, Inc. (Roseville)
$327,695.00
Always Paving, Inc. (Hayward, CA)
$330,375.00
Vintage Paving Company, Inc. (Winters)
$389,975.00
Western Engineering Contractors, Inc. (Loomis)
$475,129.00

Item Number C8.

293
Staff has reviewed the bids for sufficiency, confirmed they were responsive, and determined JB Bostick Company submitted the lowest responsible bid. Staff recommends that the City Council award the contract to JB Bostick Company.

In addition, a contingency amount of twenty percent (20%) of the contract, in the amount of $43,278.40, is recommended, bringing the total authorized project amount to $259,670.40.

Environmental Analysis:

The City of Rocklin’s Environmental Coordinator has reviewed the Park Drive Dig Outs project and determined that it falls under the previously approved Notice of Exemption for the City of Rocklin Dig Outs projects, Resolution 2018-115, and is exempt from review under the California Environmental Quality Act (CEQA), pursuant to California Code of Regulations Sections 15301 and 15302.

Fiscal Impact:

There is no fiscal impact to the General Fund. Funding for Program No. 50007 has been appropriated through the 2026-2031 Capital Improvement Program and is budgeted within the SB1 – Road Maintenance & Rehab Allocation Fund (Fund 205) and the SB 325 Sales Tax Fund (Fund 210).

ATTACHMENTS:

1. Resolution

2. Resolution Exhibit A - Construction Agreement

3. Bid Summary
294
Resolution No. 2026- May 26, 2026 Page 1 of 2
1 RESOLUTION NO. 2026-

RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ROCKLIN

AWARDING THE CONTRACT FOR THE PARK DRIVE DIG OUTS

PROJECT TO JB BOSTICK COMPANY AND AUTHORIZING THE

CITY MANAGER TO EXECUTE AN AGREEMENT

WITH JB BOSTICK COMPANY

WHEREAS, the Park Drive Dig Outs project consists of removing existing asphalt concrete surfacing and underlying base material and replacing the removed surfacing and base material with new asphalt concrete on various roads within the City; and

WHEREAS, the project was advertised for bids on March 13, 2026, and bids were opened on Wednesday, April 1, 2026, after which they were examined and found to be in compliance with all applicable specifications; and

WHEREAS, the lowest responsive and responsible bid in the amount of $216,392.00 was submitted by JB Bostick Company , and staff recommends that the contract for the project be awarded to JB Bostick Company; and

WHEREAS, a contingency amount of twenty (20%) percent of the contract , in the amount of $43,278.40, is approved by the City Council , and the City Manager is authorized to utilize these funds provided that adequate appropriations are available , bringing the total authorized project amount to $259,670.40; and

WHEREAS, this project is funded using SB1 – Road Maintenance and Rehab Allocation Funds (205).

NOW, THEREFORE, the City Council of the City of Rocklin does resolve as follows:

Section 1. The recitals set forth above are true and correct.

Section 2. The City Council hereby awards the contract for the Park Drive Dig Outs project to JB Bostick Company , in an amount not -to-exceed $216,392.00 and authorizes the City Manager to execute an Agreement with JB Bostick Company , in substantially the form attached hereto as Exhibit “A.”

Section 3. The City Council hereby authorizes the City Manager the authority to approve any reasonably necessary change orders or amendments to the agreement with JB Bostick Company for the Project in the additional contingency amount of up to $43,278.40.

295
Resolution No. 2026- May 26, 2026 Page 2 of 2
1 PASSED AND ADOPTED this 26th day of May, 2026, by the following vote:

AYES: Councilmembers:

NOES: Councilmembers:

ABSENT: Councilmembers:

ABSTAIN: Councilmembers:

David Bass, Mayor
ATTEST:

Avinta Singh, City Clerk

296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351

City of Rocklin General Conditions
2026 i

CITY OF ROCKLIN

GENERAL CONDITIONS
Table of Contents
ARTICLE SUBJECT Pages
ARTICLE 1. DEFINITIONS AND PRINCIPLES OF INTERPRETATION ......................................... 1 SECTION 1.01. GENERAL. ..................................................................................................... 1 SECTION 1.02. ABBREVIATIONS. ......................................................................................... 1 SECTION 1.03. DEFINITIONS.................................................................................................. 4 ARTICLE 2. BID REQUIREMENTS AND CONDITIONS ............................................................... 13 SECTION 2.01. BID FORM. .................................................................................................... 13 SECTION 2.02. PREPARATION AND SUBMISSION OF BIDS. ............................................. 14 SECTION 2.03. EXAMINATION OF PLANS, SPECIFICATIONS AND SITE OF WORK. ....... 15 SECTION 2.04. SUBSURFACE CONDITIONS. ..................................................................... 15 SECTION 2.05. CONTRACTORS/SUBCONTRACTORS REQUIRED TO BE LICENSED AND REGISTERED. .................................................................. 15 SECTION 2.06. COMPETENCY OF BIDDERS. ..................................................................... 16 SECTION 2.07. JOINT VENTURE BIDS................................................................................. 16 SECTION 2.08. SUBCONTRACTORS. .................................................................................. 17 SECTION 2.09. ADDENDA. .................................................................................................... 18 SECTION 2.10. ASSIGNMENT OF ANTITRUST ACTIONS. .................................................. 18 SECTION 2.11. CERTIFICATION REGARDING DEBARMENT, SUSPENSION,

PROPOSED DEBARMENT OR SUSPENSION AND OTHER
RESPONSIBILITY MATTERS. ..................................................................... 19 SECTION 2.12. BID GUARANTY. .......................................................................................... 20 SECTION 2.13. WITHDRAWAL OF BID. ................................................................................ 20 SECTION 2.14. PUBLIC OPENING OF BIDS. ........................................................................ 20 SECTION 2.15. REJECTION OF BIDS. .................................................................................. 20 SECTION 2.16. DISQUALIFICATION OF BIDDERS. ............................................................. 21 SECTION 2.17. RELIEF OF BIDDERS. .................................................................................. 21 SECTION 2.18. BID PROTESTS. ........................................................................................... 21 ARTICLE 3. AWARD AND EXECUTION OF CONTRACT; BONDS AND INSURANCE ............... 23 SECTION 3.01. AWARD OF CONTRACT. ............................................................................. 23 SECTION 3.02. TIME OF AWARD. ........................................................................................ 23 SECTION 3.03. CONSIDERATION OF BIDS. ........................................................................ 24 SECTION 3.04. PERFORMANCE AND PAYMENT BONDS. ................................................. 24 352

City of Rocklin General Conditions
2026 ii

SECTION 3.05. NOTIFICATION OF SURETY COMPANIES. ................................................ 25 SECTION 3.06. RETURN OF BID GUARANTYS. .................................................................. 25 SECTION 3.07. EXECUTION OF CONTRACT. ...................................................................... 25 SECTION 3.08. FAILURE TO EXECUTE CONTRACT. .......................................................... 25 SECTION 3.09. INSURANCE. ................................................................................................ 26 ARTICLE 4. SCOPE OF WORK .................................................................................................... 34 SECTION 4.01. THE CONTRACT. ......................................................................................... 34 SECTION 4.02. INTENT OF CONTRACT DOCUMENTS. ...................................................... 34 SECTION 4.03. PLANS AND SPECIFICATIONS FURNISHED. ............................................. 35 SECTION 4.04. CONFORMANCE WITH CODES AND STANDARDS. .................................. 35 SECTION 4.05. DIAGRAMMATIC DRAWINGS. ..................................................................... 36 SECTION 4.06. INSTRUCTION BULLETINS AND DRAWINGS. ........................................... 36 SECTION 4.07. FIELD DIRECTIVES OR OTHER WRITTEN DIRECTIVES........................... 36 SECTION 4.08. COMPLEMENTARY FEATURE OF CONTRACT DOCUMENTS; ORDER OF PRECEDENCE. ........................................................................ 37 SECTION 4.09. INTERPRETATION AND ADDITIONAL INSTRUCTIONS; REQUESTS FOR INFORMATION. ................................................................................... 38 SECTION 4.10. NOTIFICATION OF DISAGREEMENT REGARDING SCOPE OF WORK. ......................................................................................................... 39 SECTION 4.11. DELETED ITEMS. ......................................................................................... 39 SECTION 4.12. EXTRA WORK. ............................................................................................. 40 SECTION 4.13. USE OF COMPLETED PORTIONS. ............................................................. 40 SECTION 4.14. LANDS AND RIGHTS-OF-WAY. ................................................................... 40 SECTION 4.15. WARRANTY. ................................................................................................. 40 ARTICLE 5. CONTROL OF WORK AND MATERIALS ................................................................. 42 SECTION 5.01. AUTHORITY OF THE CITY. ......................................................................... 42 SECTION 5.02. ATTENTION AND COOPERATION OF CONTRACTOR. ............................. 42 SECTION 5.03. SUGGESTIONS TO CONTRACTOR. ........................................................... 42 SECTION 5.04. SEPARATE CONTRACTS. ........................................................................... 42 SECTION 5.05. COOPERATION WITH OTHER CONTRACTORS. ....................................... 43 SECTION 5.06. SUPERVISION PROCEDURES. ................................................................... 43 SECTION 5.07. SKILLED LABOR. ......................................................................................... 43 SECTION 5.08. CONTRACTOR’S DISMISSAL OF UNSATISFACTORY EMPLOYEES. ....... 43 SECTION 5.09. CONTRACTOR'S EQUIPMENT. ................................................................... 44 SECTION 5.10. CONTRACTOR'S SUBMITTALS. .................................................................. 44 SECTION 5.11. DAILY REPORTS. ......................................................................................... 47 353

City of Rocklin General Conditions
2026 iii

SECTION 5.12. SURVEYS. .................................................................................................... 47 SECTION 5.13. RESPONSIBILITY FOR ACCURACY. .......................................................... 49 SECTION 5.14. DUTIES AND POWERS OF INSPECTORS. ................................................. 49 SECTION 5.15. INSPECTION. ............................................................................................... 50 SECTION 5.16. QUALITY OF MATERIALS AND WORKMANSHIP. ...................................... 51 SECTION 5.17. SUBSTITUTIONS. ......................................................................................... 51 SECTION 5.18. PREPARATION FOR TESTING. ................................................................... 52 SECTION 5.19. MATERIALS SAMPLING AND TESTING. ..................................................... 52 SECTION 5.20. APPROVAL OF MATERIALS OR EQUIPMENT. .......................................... 53 SECTION 5.21. PROVISIONS FOR EMERGENCIES. ........................................................... 53 SECTION 5.22. RIGHT TO RETAIN IMPERFECT WORK...................................................... 53 SECTION 5.23. REMOVAL OF REJECTED MATERIALS OR WORK. ................................... 54 SECTION 5.24. TEMPORARY SUSPENSION OR DELAY OF WORK. ................................. 54 SECTION 5.25. TERMINATION.............................................................................................. 54 SECTION 5.26. TERMINATION OF UNSATISFACTORY SUBCONTRACTS. ....................... 58 ARTICLE 6. LEGAL RELATIONS AND RESPONSIBILITIES ........................................................ 59 SECTION 6.01. COMPLIANCE WITH LAWS AND REGULATIONS....................................... 59 SECTION 6.02. WAGES, HOURS AND EQUAL OPPORTUNITY .......................................... 59 SECTION 6.03. SUBCONTRACTING; SUBSTITUTION OF SUBCONTRACTORS. .............. 65 SECTION 6.04. USE OF PESTICIDES. .................................................................................. 65 SECTION 6.05. OCCUPATIONAL SAFETY AND HEALTH. ................................................... 65 SECTION 6.06. INDEMNIFICATION. ..................................................................................... 66 SECTION 6.07. PROTECTION OF CITY AGAINST PATENT CLAIMS. ................................. 67 SECTION 6.08. CONTRACTOR'S LEGAL ADDRESS; WRITTEN NOTICE. .......................... 67 SECTION 6.09. CONTRACTOR NOT AN AGENT OF CITY. ................................................. 68 SECTION 6.10. ASSIGNMENT OF CONTRACT. ................................................................... 68 SECTION 6.11. ASSIGNMENT OF MONIES. ......................................................................... 68 SECTION 6.12. CONTRACTORS LICENSE. ......................................................................... 68 SECTION 6.13. RESPONSIBILITY OF CONTRACTOR. ........................................................ 68 SECTION 6.14. PERMITS AND LICENSES. .......................................................................... 69 SECTION 6.15. RIGHTS AND REMEDIES. ............................................................................ 70 SECTION 6.16. UNENFORCEABILITY OF ANY CLAUSE. .................................................... 70 SECTION 6.17. GENERAL SAFETY REQUIREMENTS. ........................................................ 70 SECTION 6.18. PUBLIC CONVENIENCE AND SAFETY. ...................................................... 74 SECTION 6.19. PUBLIC SAFETY AND TRAFFIC CONTROL. ............................................... 77 354

City of Rocklin General Conditions
2026 iv

SECTION 6.20. CONFINED SPACES. ................................................................................... 80 SECTION 6.21 TRAFFIC CONTROL PLANS (TCP). .............................................................. 81 SECTION 6.22. BARRICADING OPEN TRENCHES. ............................................................. 82 SECTION 6.23. EXISTING UTILITIES. ................................................................................... 82 SECTION 6.24. EXCAVATION AND TRENCH SAFETY. ....................................................... 86 SECTION 6.25. OVERLOADING. ........................................................................................... 87 SECTION 6.26. PRESERVATION OF PROPERTY. ............................................................... 87 SECTION 6.27. APPROVAL OF CONTRACTOR'S PLANS NO RELEASE FROM LIABILITY. .................................................................................................... 87 SECTION 6.28. CONTRACTOR SHALL NOT MORTGAGE EQUIPMENT. ........................... 87 SECTION 6.29. PROPERTY RIGHTS IN MATERIALS. ......................................................... 88 SECTION 6.30. CONFLICT OF INTEREST. ........................................................................... 88 SECTION 6.31. NO AGREEMENTS. ...................................................................................... 88 ARTICLE 7. PROSECUTION OF THE WORK .............................................................................. 89 SECTION 7.01. BEGINNING OF WORK. ............................................................................... 89 SECTION 7.02. AMOUNT OF WORK UNDER CONSTRUCTION. ........................................ 89 SECTION 7.03. PRECONSTRUCTION CONFERENCE AND PROGRESS MEETINGS. ...... 89 SECTION 7.04. WORK TO BE UNDERTAKEN WITH ADEQUATE SUPERVISION, LABOR FORCE, EQUIPMENT AND METHODS. ........................................ 89 SECTION 7.05. SCHEDULES. ............................................................................................... 90 SECTION 7.06. UNUSUAL SITE CONDITIONS. .................................................................... 96 SECTION 7.07. PURSUANCE OF WORK DURING INCLEMENT WEATHER. ...................... 97 SECTION 7.08. PEAK HOURS, HOURS OF DARKNESS, HOLIDAYS, AND WEEKENDS. ................................................................................................ 98 SECTION 7.09. TEMPORARY FACILITIES AND SERVICES. ............................................... 99 SECTION 7.10. PROTECTION OF WORK, PERSONS AND PROPERTY. ........................... 99 SECTION 7.11. PROOF OF COMPLIANCE WITH CONTRACT. ........................................... 99 SECTION 7.12. DELAYS. ....................................................................................................... 99 SECTION 7.13. NOTICE OF DELAYS. ................................................................................. 100 SECTION 7.14. CARELESS DESTRUCTION OF STAKES AND MARKS NO CAUSE FOR DELAY. .............................................................................................. 101 SECTION 7.15. TIME OF COMPLETION. ............................................................................ 101 SECTION 7.16. EXTENSION OF TIME NOT A WAIVER. .................................................... 101 SECTION 7.17. INCLEMENT WEATHER AND CONTRACT TIME. ..................................... 101 SECTION 7.18. EXTENSION OF TIME. ............................................................................... 101 SECTION 7.19. SUBSTANTIAL COMPLETION. .................................................................. 102 355

City of Rocklin General Conditions
2026 v

SECTION 7.20. CLEANING UP. ........................................................................................... 102 SECTION 7.21. FINAL INSPECTION AND FIELD ACCEPTANCE....................................... 103 SECTION 7.22. FINAL ACCEPTANCE AND NOTICE OF COMPLETION. .......................... 103 SECTION 7.23. WARRANTY WORK. ................................................................................... 103 ARTICLE 8. MEASUREMENT AND PAYMENT .......................................................................... 105 SECTION 8.01. BASIS AND MEASUREMENT OF PAYMENT QUANTITIES. ..................... 105 SECTION 8.02. SCOPE OF PAYMENT................................................................................ 106 SECTION 8.03. WORK TO BE DONE WITHOUT DIRECT PAYMENT. ............................... 107 SECTION 8.04. PAYMENT FOR USE OF COMPLETED PORTIONS OF WORK. ............... 107 SECTION 8.05. PROGRESS PAYMENT PROCEDURES. ................................................... 107 SECTION 8.06. INSPECTION AND PROGRESS PAYMENTS NOT A WAIVER OF CONTRACT PROVISIONS. ....................................................................... 108 SECTION 8.07. RETENTION. .............................................................................................. 108 SECTION 8.08. WITHHOLDINGS/DENIAL OF PROGRESS PAYMENT REQUEST. .......... 109 SECTION 8.09. DEDUCTIONS FOR IMPERFECT WORK................................................... 110 SECTION 8.10. LIQUIDATED DAMAGES FOR DELAY. ...................................................... 110 SECTION 8.11. FINAL ESTIMATE AND PAYMENT. ............................................................ 111 SECTION 8.12. FINAL PAYMENT TO TERMINATE LIABILITY OF city. .............................. 112 SECTION 8.13. DISPUTED PAYMENTS. ............................................................................. 113 ARTICLE 9. CHANGES AND CLAIMS ........................................................................................ 114 SECTION 9.01. AUTHORITY FOR CHANGES. ................................................................... 114 SECTION 9.02. ORDERING OF CHANGES. ....................................................................... 114 SECTION 9.03. CONSTRUCTION INCENTIVE CHANGE PROPOSAL (CICP). .................. 114 SECTION 9.04. PROSECUTION OF CHANGES TO THE CONTRACT. .............................. 117 SECTION 9.05. COST AND PRICING DATA. ...................................................................... 117 SECTION 9.06. ACCESS TO RECORDS. ............................................................................ 118 SECTION 9.07. PAYMENT FOR CHANGES. ....................................................................... 118 SECTION 9.08. MARKUPS FOR CHANGED WORK. .......................................................... 121 SECTION 9.09. COMPENSABLE EXCUSABLE DELAYS. ................................................... 121 SECTION 9.10. LIMITATIONS ON PAYMENTS FOR CHANGED WORK. ........................... 122 SECTION 9.11. TIME EXTENSIONS FOR CHANGES. ........................................................ 123 SECTION 9.12. EFFECT ON SURETIES OF CHANGES TO THE WORK. .......................... 123 SECTION 9.13. CONTRACT CHANGE ORDER. ................................................................. 123 SECTION 9.14. ACCEPTANCE OF ORDERS FOR CHANGES. .......................................... 123 SECTION 9.15. DISPUTE REGARDING CONTRACT REQUIREMENTS. ........................... 124 356

City of Rocklin General Conditions
2026 vi

SECTION 9.16. NOTICE OF POTENTIAL CLAIM. ............................................................... 124 SECTION 9.17. SUBMISSION OF CLAIMS. ......................................................................... 124 SECTION 9.18. ENGINEER’S DECISION. ........................................................................... 130 SECTION 9.19. ALTERNATIVE DISPUTE RESOLUTION ................................................... 130 SECTION 9.20. NO ALTERNATIVE CLAIMS PROCEDURE. ............................................... 130 SECTION 9.22. ASSIGNMENT OF CLAIMS. ....................................................................... 130 ARTICLE 10. ENVIRONMENTAL CONTROLS AT WORK SITE ................................................. 131 SECTION 10.1. DUST CONTROL. ....................................................................................... 131 SECTION 10.2. AIR POLLUTION CONTROL. ...................................................................... 131 SECTION 10.03. BURNING. ................................................................................................. 131 SECTION 10.04. EROSION, SEDIMENT, AND WATER POLLUTION CONTROL. .............. 131 SECTION 10.05. CONTROL OF WATER IN THE WORK. ................................................... 135 SECTION 10.06. NOISE CONTROL. .................................................................................... 135 SECTION 10.07. CONTAMINATED AND HAZARDOUS MATERIALS OR
ENVIRONMENTS. ..................................................................................... 136 SECTION 10.08. USE OF EXPLOSIVES. ............................................................................. 136 SECTION 10.09. SANITARY REGULATIONS. ..................................................................... 136 SECTION 10.10. ARCHEOLOGICAL AND CULTURAL RESOURCES. ............................... 136 SECTION 10.11. PROTECTION OF EXISTING TREES. ..................................................... 137 ARTICLE 11 PRECONSTRUCTION PHOTOGRAPHS AND RECORD DRAWINGS.................. 138 SECTON 11.01. GENERAL. ................................................................................................. 138 SECTION 11.02. PRECONSTRUCTION PHOTOGRAPHS.................................................. 138 SECTION 11.03. RECORD DRAWINGS. ............................................................................. 138 SECTION 11.04. MEASUREMENT AND PAYMENT. ........................................................... 139

357

1 General Conditions
2026

ARTICLE 1. DEFINITIONS AND PRINCIPLES OF INTERPRETATION SECTION 1.01. GENERAL.

The Contract Documents are written to the Bidder before award and Contractor after award. Before award, interpret sentences written in the imperative mode as starting with “The Bidder must” and interpret “you” as “the Bidder” and “your” as “the Bidder’s.” After award, interpret sentences written in the imperative mode as starting with “Contractor shall” and “you as “Contractor” and “your” as “Contractor’s”.

Where a location is not specified with the words “shown,” “specified,” or “described”, interpret:

1. “Shown” as “shown on the plans.”

2. “Specified” as “specified in the Specifications.”

3. “Described” as “described in the Contract Documents.” “Described” means “shown, specified or both.”
Whenever the following terms, titles, or abbreviations are used in the Contract Documents, the intent and meaning shall be as herein defined. Working titles having a masculine gender, such as "workman" and "journeyman" and the pronoun "he”, are utilized in the Contract Documents for the sake of brevity, and are intended to refer to persons of either gender.

SECTION 1.02. ABBREVIATIONS.

AASHTO American Association of State Highway and Transportation Officials AC Asphalt Concrete
ACI American Concrete Institute
ADA Americans with Disabilities Act
AISC American Institute of Steel Construction
AISI American Iron and Steel Institute
ANSI American National Standards Institute
APA American Plywood Association
ARB California Air Resources Board
ASA American Standards Association
ASME American Society of Mechanical Engineers
ASNT American Society of Nondestructive Testing
ASTM American Society for Testing and Materials
AT&T American Telephone and Telegraph
AWG American Wire Gage
AWS American Welding Society
AWWA American Water Works Association
BMP Best Management Practice
MUTCD California Manual of Uniform Traffic Control Devices Cal-OSHA California Occupational Safety and Health Administration Caltrans California Department of Transportation
CBC California Building Code
358

2 General Conditions
2026

CCR California Code of Regulations
CDFW California Department of Fish and Wildlife
CEC California Electric Code
CEQA California Environmental Quality Act of 1970
CFR Code of Federal Regulations
CL Centerline
cm. centimeter (centimeters)
CPC California Plumbing Code
CPM Critical Path Method
CPUC California Public Utilities Commission
CSI Construction Specifications Institute
CWA Clean Water Act
CY Cubic Yards
DI Drop Inlet
Dia. diameter
DIR California Department of Industrial Relations
DLSE Division of Labor Standards Enforcement
DWR Daily Work Report
EA Each
EP Edge of Pavement
EPA Environmental Protection Agency
ESCP Erosion and Sediment Control Plan
FS Federal Specifications
Gal. gallon (gallons)
GPD gallons per day
GPM gallons per minute
Hr. hour
HVAC Heating, Ventilating and Air Conditioning
IBC International Building Code
IEEE Institute of Electrical and Electronic Engineers
In. inch (inches)
Inc. Incorporated
ISO International Organization for Standardization
Kg. kilogram (kilograms)
Km. kilometer (kilometers)
Kw Kilowatt
l. liter (liters)
lbs. pounds
LF Linear Feet
LS Lump Sum
M meter (meters)
MBE Minority Business Enterprise
Mfg. manufacturing
Mg. milligram (milligrams)
ml./mls. milliliter (milliliters)
mm. millimeter (millimeters)
MSDS Material Safety Data Sheet
NEC National Electrical Code
359

3 General Conditions
2026

NEMA National Electrical Manufacturers Association
NFPA National Fire Protection Association
NIBS National Institute of Building Systems
No. number
NPA National Forest Products Association
NSF National Sanitation Foundation
o.c. on center
O.D. outside diameter
OSHA Occupational Safety and Health Administration
OPRL DIR, Director’s Office of Policy, Research and Legislation PCC Portland Cement Concrete
PG&E Pacific Gas & Electric
PS Pump Station
Psi pounds per square inch
QC Quality Control
QSD Qualified SWPPP Developer
QSP Qualified SWPPP Practitioner
SD Storm Drain or Storm Drainage
SF Square Foot/Feet
Sq. Square
SS Sanitary Sewer
SSPC Society for Protective Coatings
STA Station
SWPPP Storm Water Pollution Prevention Plan
SWRCB State Water Resources Control Board
TCP Traffic Control Plan
TIE Time Impact Evaluation
TEMA Tubular Exchanger Manufacturer’s Association
Title 8 Title 8 (Construction Safety Orders) of the California Code of Regulations Title 19 Title 19 (Public Safety) of the California Code of Regulations Title 24 Title 24 (Building Standards) of the California Code of Regulations TOC Top of Curb
Typ. or TYP Typical
UL Underwriters' Laboratories, Inc.

UBC Uniform Building Code (latest edition)
UFC Uniform Fire Code
UMC Uniform Mechanical Code (latest edition)
UPC Uniform Plumbing Code (latest edition)
U.S. United States
USA Underground Service Alert
WBE Woman-Owned Business Enterprise
Yd. yard (yards)

360

4 General Conditions
2026

SECTION 1.03. DEFINITIONS.

Acceptance, Final Acceptance.
“Acceptance or “Final Acceptance” shall mean form al action of the City of Rocklin in determining that Contractor’s work has been completed in accordance with the Contract Documents and in notifying Contractor in writing of the acceptability of the Work.

Acts of God.
“Acts of God ” shall include only the following occurrences or conditions and effects:
earthquakes in excess of a magnitude of 3.5 on the Richter Scale, tidal waves, flooding, tornadoes and hurricanes.

Addendum/Addenda.
“Addendum” or “Addenda” are written documents issued by the City prior to opening of Bids that clarify, correct, or change the bidding requirements of the proposed Contract Documents.

Agreement.

The “Agreement” is the written agreement signed by the City and Contractor covering the Work and the furnishing of labor, materials, tools, equipment, supplies, transportation, supervision, resources, and everything necessary to complete the Work.

Allowance.

An “Allowance” is an amount of money set aside under the Contract for a special purpose identified in the Contract.

Architect, Consulting Engineer and/or Construction Manager.

The “Architect, Consulting Engineer and/or Construction Manager, if used, is a person or persons, firm, partnership, joint venture, corporation, or combination thereof or authorized representative thereof, acting in the capacity of consultant to the City. The Architect or Consulting Engineer or Construction Manager shall issue directions to Contractor only through the City. When the Contract Documents require that approval be obtained from the Architect or Consulting Engineer or Construction Manager , such approval shall be requested from and be given by the City.

As Shown, Etc.

Where "as shown", "as latest indicated", "as detailed", or words of similar import are used, the reference is to the Contract unless specifically stated otherwise. Where "as directed", "as permitted", "approved", or words of similar import are used, they shall mean the written direction, permission, or approval of the City.

Bid.
“Bid” shall mean the offer of the B idder to complete the Work at the price shown on the Bidder’s bid form, when submitted on the prescribed bid form, properly executed and guaranteed, at the designated time and location. In the case of a solicitation involving a Request for Proposals, all references to “Bid” shall be deemed to mean “Proposal”.

Bid Documents.
“Bid Documents” shall mean the sum of the documents that comprise the Bid by a 361

5 General Conditions
2026

Bidder to perform the Work.

Bid Form.

The “Bid Form” , sometimes referred to as the “Bid Schedule” is the approved form, which includes a sum of requirement documents, upon which City requires a formal Bid be prepared and submitted for the Work. In the case of a solicitation involving a Request for Proposals, the Bid Form may be referred to as a “Proposal Form.” Bid Guaranty.
“Bid Guarant y” is the cashier’s check, certified check or Bidder’s bond accompanying the Bid submitted by the Bidder as a guaranty that the Bidder will enter into a Contract with the City for the performance of the Work if the Contract is awarded to the Bidder.

Bid Item.
“Bid Item” or “Bid Items” shall mean individual line items to be included in the Bid, as set forth on the Bid Form.

Bid Opening.
“Bid Opening” shall mean the event conducted by the City during which the sealed Bids submitted by Bidders to perform the Work are opened and publicly read.

Bidder.
“Bidder” shall mean a ny person, persons, firm, partnership, joint venture, corporation, limited liability company or combination thereof, submitting a Bid for the Work, acting directly or through a duly authorized representative. In the case of a solicitation involving a Request for Proposals, all references to “Bidder” shall be deemed to mean “Proposer.”

By Others.
“By Others” shall mean Work that is outside scope of Work to be performed by Contractor under this Contract, which will be performed by the City, other contractors, or other means.

Calendar Day.
“Calendar Day” shall mean every day shown on the calendar. When the Contract Time is stated in Calendar Days, every day will be charged toward the Contract Time.

Change Order.
“Change Order” (“CO”) shall mean a written amendment approved by the City that includes, but is not limited to, alterations, deviations, additions to, or deletions from, the Contract that are required for the proper completion of the Work. A Change Order may or may not include adjustments to the Contract Time and/or to the Contract Sum.

City.
“City” or “Owner” shall mean the City of Rocklin, acting through its authorized representatives.

City Council.
362

6 General Conditions
2026

“City Council” means the City Council of the City of Rocklin, a political subdivision of the State of California. Also referred to as “Council”.

City of Rocklin Construction Standard Specifications.
“City of Rocklin Construction Standard Specifications” mean the City’s standard specifications for construction, located on the City’s website.

City of Rocklin Improvement Standards.
“City of Rocklin Improvement Standards” mean the City’s standard requirement for improvement projects, located on the City’s website.

Closeout Documents.
“Closeout Documents” are the documents required to meet the requirements of final completion as referenced in Section 7.22 of these General Conditions.

Completion.
“Completion” is the point in the Project at which the Work and all required close- out reports and submissions are 100% performed.

Construction Change Directive (CCD).
“Construction Change Directive” (“CCD”) or “Directive” or “Field Directive” shall mean a written order to Contractor, issued after execution of the Contract, signed by the City or the Owner’s Representative directing a change in the Work and stating a proposed basis for adjustment, if any, in the Contract Sum or Contract Time, or both, and which shall be used in the absence of total agreement with Contractor on the terms of a Change Order or when time does not permit processing of a Change Order prior to implementation of the change.

Contract.

The “Contract” is the entire binding agreement and contract between the City and Contractor relating to the Project, including the Agreement, and all documents incorporated into the Agreement by reference and all Contract Documents.

Contract Documents.

The “Contract Documents” shall include the Notice to Contractors , Addenda, Bid Form (including the Bid Guaranty), A greement, the Performance Bond, the Payment Bond, Escrow Agreement for Security Deposits in Lieu of Retention (if used), Guarantee Form, the General Conditions, the Special Provisions, General Requirements (Division 1), Technical Specifications (Divisions 2 through 16), Contract Drawings, Permits from other agencies as may be required by law, City of Rocklin Construction S pecifications, Improvement Standards and Standard Drawings , Caltrans Standard Plans and Specifications as applicable, Standard Forms, Supplemental Drawings, Exhibits, the Contract Schedule, Storm Water Pollution Prevention Plan (whether prepared by the City or Contractor), and any and all supplemental agreements amending or extending the Work contemplated and which may be required to complete the Work in an acceptable manner. Supplemental agreements are written agreements covering alterations, amendments or extensions to the Contract Documents and include Change Orders, Construction Change Directives, Field Directives, Field Orders , Bulletins and Supplemental Drawings.
363

7 General Conditions
2026

Contract Commencement Date.

The “Contract Commencement Date” shall mean the date established in the Notice to Proceed. If there is no Notice to Proceed, it shall be date of the executed Agreement for Construction or such other date as may be established therein.

Contract Completion Date.

The “Contract Completion Date” shall mean the date by which the Contract requires Completion.

Contract Drawings or Plans.

The “Contract Drawings” (sometimes referred to as “Drawings” or “Plans”) are the graphic and pictorial portions of the Contract Documents, showing the design, location and dimensions of the Work, generally including plans, elevations, sections, details, schedules and diagrams. This information may be developed and stored in a 3D or 4D model of the Project. Once approved, all such drawings are incorporated into and become a part of the Contract Documents.

Contract Schedule.

The “Contract Schedule” is the schedule produced by Contractor in response to the requirements of the Contract Documents.

Contract Sum.
“Contract Sum” is the total price for the Work as bid by Contractor, including any additions or subtractions via Change Orders.

Contract Time.
“Contract Time” shall mean the period specified for completion of the Work, as set forth in the Contract and adjusted by any Change Order issued pursuant to the Contract Documents. The Contract Time may be a single allotment of time, a group of times specific to portions of the Work, or a combination of the two
Contractor.
“Contractor” shall mean the person or persons, firm, partnership, joint venture, or corporation, who has (have) entered into the Contract for the Work with City or its legal representatives, or successors, assigns, executors, or heirs. Contractor is required by law to be licensed and will perform work or render services as a prime contractor in or about the construction of the Work.

Engineer of the City of Rocklin.
“Engineer” means the City’s Engineer for whom work will be done under the Contract Documents, acting personally or through agents or assistants duly authorized by the Engineer.

Equal (as in “or equal”).
“Equal” shall mean a system, process, product or material which is similar in all respects to that shown or specified but produced by a manufacturer not listed in the specification.

See also: Substitution.
364

8 General Conditions
2026

Estimated Quantities.
“Estimated Quantities” are t he list of items of Work and the estimated quantities associated with the Work. The Estimated Quantities provide the basis for the Bid.

General Conditions.
“General Conditions” are specific clauses that are part of the Contract and are located in Section 0700. They assist in the governing of the Contract and in the contract performance, setting forth conditions and requirements of the Contractor and the City.

General Requirements.
“General Conditions” are the part of the Contract Documents establishing special conditions or requirements particular to the Work and general clauses that establish how the Project is to be administered and supplementary to the General Conditions and Special Provisions.

Hazardous Waste.
“Hazardous Waste” shall have the meaning provided in Section 1004 of the Solid Waste Disposal Act (42 USC Section 6903) as amended from time to time.

Inspector.

The “Inspector” or “Project Inspector” shall mean the person or persons authorized to act as agent(s) for the City in the inspection of the Work.

Instruction Bulletin or Bulletin.
“Instruction Bulletins” or “Bulletins” are supplemental drawings, clarifications, instructions, explanations or interpretations which may be issued by the Architect or Consulting Engineer as necessary from time to time pursuant to Article 4 to make clear or define in greater detail the intent of the Contract Drawings and Specifications. There may be a change in Contract Sum or Contract Time involved with the work shown in the Bulletin.

Invitation for Bids.

The “Invitation for Bids” is the written notice whereby interested parties are informed of the date, location and time of the Bid Opening of a proposed City project and the terms and conditions of submitting Bids to perform the Work. The Invitat ion for Bids is sometimes referred to as a Notice to Contractors and, in the case of a solicitation for proposals is referred to as the Request for Proposals.

Legal Holidays.

Legal Holidays shall include the following holidays designated by the City : New Year's Day, Martin Luther King Jr. Day, President’s Day, Cesar Chavez Day, Memorial Day, Independence Day, Labor D ay, Veteran’s Day, Thanksgiving Day, the day after Thanksgiving, and Christmas Day.

Notice to Contractors.
“Notice to Contractors” shall have the same meaning as “Invitation for Bids.” Notice to Proceed.
“Notice to Proceed” is the written authorization by the City to Contractor specifying the date the Work may begin and any conditions regarding the beginning of the Work. 365

9 General Conditions
2026

Owner’s Representative
“Owner’s Representative” shall mean the City’s designated agent engaged to perform all functions delegated to the Owner’s Representative by the Contract Documents. The Owner’s Representative may or may not be the Project Manager or a construction manager. The Owner’s Representative will be the Contractor’s primary contact during construction of the Project.

Progress Schedule.
“Progress Schedule” is the schedule prepared and maintained by the Contractor indicating the current status of the Work and the projected activities, tasks, and durations planned to complete the Work in accordance with the Contract Time of Completion dates.

Project.
“Project” shall mean the Work.

Project Manager
“Project Manager” is the City’s representative assigned to oversee the Project on a daily basis.

Proposed Change Order (PCO).

A “Proposed Change Order” (“PCO”) is a document issued by Contractor proposing a change to the Work and stating a proposed basis for adjustment, if any, in the Contract Sum or Contract Time, or both. A PCO shall be used by Contractor to respond to a Request for Proposal. A PCO is not effective to authorize the proposed change to the Work, to the Contract Sum or to the Contract Time unless it is accepted in writing by the the City.

Record Drawings.
“Record Drawings” are drawings prepared by Contractor that document changes to, additions to, or deductions f rom the Plans and that represent the Work as constructed, including, but not limited to existing utilities found during construction of the Work.

Reference to Codes.

Unless otherwise noted, all references to statutes are to the laws of the State of California and/or of the United States as codified in the various specified codes.

Request for Information (RFI).
“Request for Information” (“RFI”) is a document issued by Contractor seeking clarification and/or additional information regarding an aspect of the Work. An RFI is not to be used to request materials/equipment substitutions or value engineering/cost reduction incentive proposals. The response to the RFI does not constitute authorization or direction to proceed with any changed or additional work. Changed or additional work must be separately authorized by
the City.

Request for Proposal.

A “Request for Proposal” or “RFP” during the course of construction is the name given to a document issued by the Owner’s Representative requesting pricing information and/or an adjustment in Contract Time for a described scope of work. An RFP is not a Change 366

10 General Conditions
2026

Order, a Directive or a direction to proceed with the scope of work described in the RFP.

Contractor’s response to the RFP shall be in the form of a Proposed Change Order.

Schedule of Submittals.
“Schedule of Submittals” is a schedule prepared and maintained by Contractor of required submittals and the time requirements to support scheduled performance of related construction activities.

Schedule of Values.
“Schedule of Values” is the statement furnished by Contractor to the City reflecting the portions of the Contract Sum allotted for the various parts of the Work for each work activity contained on the Contract Schedule. Unless otherwise indicated in the Specifications, the total of the Schedule of Values shall equal the full cost of the Work, including all labor, material, equipment, overhead, and profit. For lump sum contracts, the Schedule of Values is the basis for reviewing Contractor ’s application for progress payments.

Special Provisions.
“Special Provisions” are specific clauses setting forth conditions or requirements particular to the Work and supplementary to the General Conditions.

Specifications.
“Specifications” include the General Conditions , S pecial Provisions, General Requirements, and Technical Specifications applicable to the Work.

Standard Drawings.
“Standard Drawings” meand the City of Rocklin Construction Specifications, Improvement Standards and Standard Drawings, which are incorporated into the Standard Construction Specifications, and made a part of the Plans by reference to one or more specific Standard Drawings.

State.
“State” means the State of California.

State Specifications.

Unless otherwise stated in the Special Provisions, “State Specifications” means the version of the Standard Specifications of the State of California, Department of Transportation, in effect at the time of Notice to Contractors.

State Plans.

Unless otherwise stated in the Special Provisions, “State Plans” means the version of the Standard Plans of the State of California, Department of Transportation, in effect at the time of Notice to Contractors.

Subcontractor.
“Subcontractor” shall mean each person or firm who is required by law to be and who is licensed to and will perform work, labor, or render services to Contractor in or about the construction of the Work, or who, under subcontract to Contractor, fabricates and installs a portion of the W ork or improvement. “Subcontractor” shall include all persons or firms 367

11 General Conditions
2026

within the authority of the Subletting and Subcontracting Fair Practices Act, Chapter 2 of Division 5, Title I of the Public Contract Code, commencing with Section 4100.

Substantial Completion.
“Substantial Completion” is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so
City can occupy or utilize the Work for its intended use, and only minor corrective Work remains to be performed, all required approvals, certificates of occupancy and other sign- off from any other public agencies with jurisdiction have been obtained, (provided such approvals are not delayed as a result of causes unrelated to Contractor’s or its Subcontractors', sub-subcontractors', or suppliers' performance or failure to perform the Work or to satisfy its obligations under the Contract Documents ), and Contractor has
cleaned up and removed all equipment, tools and other materials from the Work area.

Contractor shall secure and deliver to City written warranties and guaranties from its Subcontractors, sub- subcontractors and suppliers bearing the date of Substantial Completion or some other date as may be agreed to by City and stating the period of warranty as required by the Contract Documents.

Substitution.
“Substitution” shall mean a system, process, product or material similar in form or function and equal in quality and performance to that shown or specified, but differing in some essential element, e.g., chemical composition, mechanism of action, surface finish, dimensions, durability, electrical or mechanical or plumbing requirements. See also:

Equal.

Supplemental Drawing.
“Supplemental Drawings” define the Plans or Specifications in greater detail by providing additional information that may have not been specifically or clearly shown or called out on the Plans or in the Specifications.

Technical Specifications.
“Technical Specifications” are the provisions of the Specifications that describe the technical aspects of the Work, including all technical references contained therein.

Total Bid Price.

The “Total Bid Price” is the aggregate sum of the Bid, including all additive items.

Work.

The “Work” shall mean all obligations and/or actions which Contractor is contractually required to fulfill and/or perform as specified, indicated, shown, contemplated, or implied in the Contract, including but not limited to (1) all alterations, amendments, or extensions made by Change Order or other written directives or directives of the City; (2) furnishing of
all materials, supplies, equipment, tools, labor, transportation, supervision, and all incidentals necessary to perform all tasks required by the Contract; (3) all tasks, duties and obligations required by the Contract; and (4) closing documents for the Project such as complete Record Drawings and submission of all manuals. 368

12 General Conditions
2026

Working Day.
“Working Day shall mean any day except: (a) Saturdays, Sundays, and City Legal Holidays; (b) days on which Contractor is specifically required by the Special Provisions or by law to suspend construction operations; or (c ) days on which the Contractor is prevented from proceeding with the current controlling operation or operations of the Work for at least five (5) hours per day due to inclement weather, or conditions resulting immediately therefrom.

Working Drawing.
“Working Drawings” detail a particular item of W ork and the manner in which it is to be accomplished or performed. Working Drawings are prepared by Contractor as a submittal or a portion of a submittal and may be specifically requested by the City or required in the Contract or a Field Directive or other written directive. 369

13 General Conditions
2026

ARTICLE 2. BID REQUIREMENTS AND CONDITIONS
SECTION 2.01. BID FORM.

The City will furnish to each prospective Bidder a Bid Form as part of the Contract Documents which, when properly completed and executed, must be submitted as the Bidder's Bid for the Work. All Bids must be submitted on the City-furnished Bid Form to be
valid and accepted. Bids that are not submitted on the City -furnished Bid Form will be rejected. The completed Bid Form shall be in English and legible, and shall be properly signed in longhand by the Bidder, if an individual, by a member of a partnership, by an officer of a corporation authorized to sign contracts on behalf of the corporation, or by an agent of the Bidder. If submitted by a corporation or limited liability company, the Bid shall show the name of the state under the laws of which the corporation or limited liability company is chartered or organized.

SECTION 2.01A. Unit Price Bid.

Where the Bid for an item of Work is to be submitted on a unit price basis, the Bidder shall bid a unit price as total compensation for completion of one unit of the work described under that item. This price shall be multiplied by the Estimated Quantity included in the Bid Form to derive a total bid price for that item. The total amount bid for a unit price contract shall be entered on the space provided on the Bid Form as a grand total of all individual items. The Estimated Quantities included on the Bid Form are approximate and are only included in the Bid Form as a basis for comparison of Bids.

The
City does not, expressly or by implication, represent or agree that the actual amount of Work will equal the approximate Estimated Quantities. Payment will be made for the actual quantity of Work performed in accordance with the Contract. The City reserves the right to increase or decrease the amount of any class or portion of the Work, or to omit portions of the Work, as may be deemed necessary or advisable in the sole discretion of the City . For compensation for alterations in quantities of work, including deviations greater than twenty-five percent (25%), see Section 9.07B, “Payment for Changes – Unit Prices”, of these General Conditions.

SECTION 2.01B. Lump Sum Bid.

Where the Bid for an item of Work is to be submitted on a "Lump Sum" or "Job" basis, a single lump-sum price shall be submitted in the appropriate place on the Bid Form. Items bid on a lump- sum basis shall result in a complete project, structure, operating plant, or system, in satisfactory working condition with respect to the functional purposes of the installation, as described in the Contract, and no extra compensation will be paid for anything omitted but fairly implied.

SECTION 2.01C. Allowances.

Where specific allowance items have been entered on the Bid Form by the City, the total amount entered on the Bid Form shall be included in the Total Bid Price. However, the total amount to be paid for the Work included in the Allowance shall be the amount of the Allowance actually utilized in the course of completing the Work.

370

14 General Conditions
2026

SECTION 2.02. PREPARATION AND SUBMISSION OF BIDS.

The Project is a public works project within the requirements of Division 2, Part 7, Chapter 1 of the California Labor Code. Each Bidder and listed Subcontractor is required to be registered pursuant to Labor Code section 1725.5 at the time of bidding.

Failure of the Bidder to be registered at the time of bidding shall render the Bid non- responsive and ineligible for award. An unregistered Subcontractor will not be permitted to work on the Project and Contractor may be required to substitute, at its cost and with no adjustment in the Contract Sum , an unregistered Subcontractor with a registered Subcontractor.

By submission of a Bid, the Bidder acknowledges acceptance of the nature and location of the Work, the general and local conditions, conditions of the site, the character, quality and scope of work to be performed, the availability of labor, electric power, water, the kind of surface and subsurface materials on the site, the materials and equipment to be furnished, and all requirements of the Contract or other matters which may affect the Work or the cost. Any failure of a Bidder to become acquainted with all of the available information concerning conditions will not relieve the Bidder from the responsibility for estimating properly the difficulties or cost of the Work.

The Bidder declares by the submission of a Bid that the Bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation; that the Bid is genuine and not collusive or a sham; that the Bidder has not directly or indirectly induced or solicited any other Bidder to put in a false or sham Bid, and has not directly or indirectly colluded, conspired, connived or agreed with any Bidder or anyone else to put in a sham Bid or to refrain from bidding; that the Bidder has not directly or indirectly sought by agreement, communication, or conference with anyone to fix the Bid price of the Bidder or the Bid price of any other Bidder, or to fix any overhead, profit, or cost element of such Bid price or of that of any other Bidder, or to secure any advantage against
the City , anyone interested in the Bid as principal, or those named within the Bid; that all statements contained in the Bid are true; that the Bidder has not directly or indirectly submitted a Bid price or any breakdown thereof or the contents thereof, or divulged information or data relative thereto, to any other corporation, partnership, company, association, organization, bid depository, or to any member or agent therefore, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such a purpose.

Any person executing the above declaration on behalf of a Bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity hereby represents that he has full power to execute the declaration on behalf of the Bidder.

Bid prices shall include everything necessary for the completion of the Work and fulfillment of the Contract, except as may be provided otherwise in the Contract Documents. Bid prices shall include all Federal, State, and local taxes, and all other fees and costs not expressly paid for by
the City as stated in the Special Provisions.

The Bid shall be submitted in a sealed envelope and/or as directed in the Invitation for Bids. The Bidder shall plainly mark the exterior of the envelope in which the Bid is 371

15 General Conditions
2026

submitted to indicate that it contains a Bid for the project for which the Bid is submitted, and the date of the Bid opening therefore.

Bids submitted in envelopes that are not properly marked will be rejected.

SECTION 2.03. EXAMINATION OF PLANS, SPECIFICATIONS AND SITE OF WORK.

The Bidder shall examine carefully the site of the proposed Work and the Plans, Specifications and Contract Documents, and shall be satisfied as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered. The submission of a Bid shall be conclusive evidence that the Bidder is satisfied through the Bidder’s own investigation as to the conditions to be encountered; the character, quality, quantity and scope of W ork to be performed; and the materials and equipment to be furnished.

If material discrepancies or apparent material errors are found in the Plans and Specifications prior to the date of bid opening, an Addendum may be issued (see Section

2.09, “Addenda”, below). Otherwise, in figuring the Work, Bidders shall consider that any discrepancies or conflict between Plans and Specifications will be governed by Section

4.01, “Intent of Contract Documents” of these General Conditions.

SECTION 2.04. SUBSURFACE CONDITIONS.

Where investigations of subsurface conditions have been made by the City with respect to subsurface conditions, utilities, foundation, or other structural designs, and that information is shown in the Plans, it represents only a statement by the City as to the
character of materials which have actually been encountered by the City’s investigation.

This information is only included for the convenience of Bidders.

Investigations of subsurface conditions are made for the purpose of design only. The City assumes no responsibility with respect to the sufficiency or accuracy of borings or of the log of test borings or other preliminary investigations or of the interpretation thereof. There is no guaranty, either expressed or implied, that the conditions indicated are representative of those existing throughout the Work, or any part of it, or that unanticipated conditions may not occur. When a log of test borings is included in the Plans, it is expressly understood and agreed that said log of test borings does not constitute a part of the Contract. The log of test borings represents only an opinion of the
City as to the character of the materials to be encountered, and is included in the Plans only for the convenience of the Bidders. Making information available to Bidders is not to be construed in any way as a waiver of the provisions of the first paragraph of this Section, and Bidders must satisfy themselves through their own investigations as to conditions to be encountered.

SECTION 2.05. CONTRACTORS/SUBCONTRACTORS REQUIRED TO BE LICENSED AND REGISTERED.

The Bidder shall be licensed under the provisions of Chapter 9, Division 3, of the Business and Professions Code to do the type of work contemplated in the Project, and shall be skilled and regularly engaged in the general class or type of work called for under 372

16 General Conditions
2026

the Contract. The specific type of license required will be indicated in the Invitation for Bids. Unless specified otherwise in the Special Provisions, the Bidder shall indicate the license number and class in the space provided for that purpose on the bid form.

All Subcontractors engaged to perform portions of the Work shall be licensed under the provisions of Chapter 9, Division 3, of the Business and Professions Code to do the type of work for which they are subcontracted, and shall be skilled and regularly engaged in the general class or type of work called for under their subcontracts. Additionally, Subcontractors listed in the Bid shall be licensed at the time the Bid is submitted to do the type of work for which they are subcontracted.

Attention is also directed to the provisions of Public Contract Code Section 20103.5, which addresses Contractor licensing requirements.

The City may not award the Contract
if it cannot be verified that the low Bidder is an appropriately licensed Contractor at the time of Contract award.

The Project is a public works project within the requirements of Division 2, Part 7, Chapter 1 of the California Labor Code. Each Bidder and listed Subcontractor is required to be registered pursuant to Labor Code section 1725.5 at the time of bidding. Failure of the Bidder to be registered at the time of bidding shall render the Bid non- responsive and ineligible for award. An unregistered Subcontractor will not be permitted to work on the Project and Contractor may be required to substitute, at its cost and with no adjustment in the Contract Sum, an unregistered Subcontractor with a registered Subcontractor .

Contractor and all Subconcontractors shall maintain their registrations throughout the term of the Project.

SECTION 2.06. COMPETENCY OF BIDDERS.

It is the intention of the City to award a Contract only to a Bidder who furnishes satisfactory evidence that the Bidder has the requisite experience and ability, and has sufficient capital, facilities, and plant to enable Contractor to prosecute the Work successfully and promptly, and to complete the Work within the time stated in the Contract.

If required by the Bid Form, a statement of experience and business standing for the Bidder and any or all Subcontractors designated in the Bid shall be provided to the City at Bid time.

To determine the experience of a Bidder, the City may consider any relevant evidence that the Bidder, and/or its key personnel assigned to the Project for the duration of the Project, and/or the Subcontractor(s) has or has not satisfactorily performed on other contracts of similar nature, value, magnitude and/or difficulty.

SECTION 2.07. JOINT VENTURE BIDS.

If two or more prospective Bidders desire to bid jointly as a joint venture on a single project, the joint venture Bid must be accompanied by either a notarized copy of a valid license issued to the joint venture by the Contractor’s State License Board or the license 373

17 General Conditions
2026

number and class of a valid license issued by the Contractor’s State License Board to each member of the joint venture.

Attention is also directed to the provisions of Business and Professions Code Sections 7028.15 and 7029.1 and Public Contract Code Section 20103.5, which address Contractor licensing requirements for joint ventures. Unless it has done so with its Bid, the joint venture must provide to
the City, prior to award of the Contract, a notarized copy of a valid license issued to the joint venture. The City may not award the Contract if it cannot be verified that the joint venture is appropriately licensed at the time of Contract award.

SECTION 2.08. SUBCONTRACTORS.

In accordance with the Subletting and Subcontracting Fair Practices Act, of the Public Contract Code, Section 4100 et seq., each Bidder shall list in the bid form:
• The name, California contractor license number, and the location of the place of business of each Subcontractor whom the Bidder proposes to perform work or labor or render service to the prime Contractor in or about the construction of the Work, or a Subcontractor licensed by the State of California who, under subcontract to the prime Contractor, is proposed by the Bidder to specially fabricate and install a portion of the Work according to detailed drawings contained in the Contract, in an amount in excess of one- half of one percent (0.5%) of the Total Bid Price or, in the case of a Bid for the construction of streets or highways, including bridges, in excess of one- half of one percent (0.5%) of the Bidder’s Total Bid Price or ten thousand dollars ($10,000), whichever is greater. In the case of a Bid including additive Alternates, the bid amount for determining whether a Subcontractor is required to be listed shall be the base bid amount, and the Bidder shall list all Subcontractors subject to this requirement even if the Subcontractor only meets the threshold amount based on work included in one or more Alternates.
• The portion of the Work
(type of work ) that will be done by each Subcontractor.

The Bidder shall list only one Subcontractor for each portion as is defined by the Bidder in the Bid.
• DIR Registration number or other proof of registration.

If a Bidder fails to specify a Subcontractor for any portion of the Work to be performed under the Contract (or specifies more than one Subcontractor for the same work), the Bidder agrees that the Bidder is fully qualified and shall perform that portion of the Work.

Within 24 hours following the bid opening date and time, a Bidder may further define its description of the “portion” of work to be performed by a listed Subcontractor, including for example by specifying Bid Items to be performed by a listed Subcontractor, but the Bidder shall not vary the portion of work to be provided to the listed Subcontractor. Bidders who list a Subcontractor for less than all of a type of work as described in the Subcontractor listing in the Bid must provide an additional, unique description of the work to be performed by the listed Subcontractor within 24 hours following the Bid Opening date and 374

18 General Conditions
2026

time or the Subcontractor will be deemed to have been listed to perform all work falling within the description of work.

No Subcontractor listed in the Bid as furnishing and installing carpeting shall sublet any portion of the labor to be performed unless the Subcontractor specified its Subcontractor in its bid to the Bidder.

If after the award of the Contract, Contractor subcontracts any portion of the Work, except as provided in Section 4107 or 4109 of the Public Contract Code, Contractor shall be subject to the penalties specified in Section 4111 of the Public Contract Code.

Pursuant to Public Contract Code Section 6109, a Contractor may not perform work with a Subcontractor who is ineligible to perform work on public works projects pursuant to Labor Code Section 1777.1.

Contractor shall include provisions in every subcontract and/or purchase order that the Contract between Contractor and
the City is part of the subcontract or purchase order, and that all terms and provisions of the Contract are incorporated in the subcontract or purchase order. Copies of all subcontracts and purchase orders shall be available to the
City upon written request.

SECTION 2.09. ADDENDA.

The correction of any material discrepancies in, or material additions to/omissions from, the Plans, Specifications, or other Contract Documents, or any interpretation thereof, during the bidding period will be made only by an Addendum issued by the City. A copy of
each Addendum issued by the City will be posted on the City’s website and notice will be provided to each plan holder listed on the City plan holder list and is a part of the Contract. Any interpretation or explanation not included in the addenda will not be considered binding.

SECTION 2.10. ASSIGNMENT OF ANTITRUST ACTIONS.

The Bidder is required to comply with Public Contract Code Section 7103.5(b), which addresses assignment of antitrust actions. By execution of the Contract Documents, or any subcontract awarded by Contractor , Contractor or any Subcontractor offers and agrees to assign and hereby does assign to the City all rights, title, and interest in and to all causes of action Contractor or Subcontractor may have under Section 4 of the Clayton Act (15 USC Section 15) or under the Cartwright Act (Chapter 2 of Part 2 of Division 7 of the Business and Professions Code, commencing with Section 16700), arising from purchases of goods, services, or materials pursuant to this public works contract or subcontract. This assignment shall be made and shall become effective at the time the City tenders final payment to Contractor, without further acknowledgment by the parties. 375

19 General Conditions
2026

SECTION 2. 11. CERTIFICATION REGARDING DEBARMENT, SUSPENSION,

PROPOSED DEBARMENT OR SUSPENSION AND OTHER RESPONSIBILITY MATTERS.

As stipulated in the Certification Regarding Debarment, Suspension, Proposed Debarment or Suspension to be submitted at Bid time, the Bidder certifies, to the best of its knowledge and belief, except as expressly disclosed in the referenced Certificate, that:

1. The Bidder and/or any of its Principals:
a. Are not presently debarred, suspended, proposed for debarment or suspension, or declared ineligible for award of the contract by any Federal, State, or local agency.
b. Have not, within a three-year period preceding this offer, been convicted of or had a civil judgment rendered against them for: commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) contract or subcontract; violation of Federal or State antitrust statutes relating to the submission of offers; or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, tax evasion, or receiving stolen property.
c. Are not presently indicted for, or otherwise criminally or civilly charged by a government entity with, commission of any of the offenses enumerated in Item 1b. above.
d. The Bidder has not, within a three- year period preceding this offer, had one or more contracts terminated for default by any Federal, State, or local agency.

2. "Principals,” for the purposes of this certification, means: officers; directors; owners; partners; and, persons having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a subsidiary, division, or business segment, and similar positions).

3. The Bidder shall provide immediate written notice to the City if, at any time prior
to contract award, the Bidder learns that its certification was erroneous when submitted or has become erroneous by reason of changed circumstances.

4. A certification that any of the items in Paragraph 2.11(1) of this provision exists will not necessarily result in withholding of an award. However, the certification will be considered in connection with a determination of the Bidder's responsibility. Failure of the Bidder to furnish a certification or provide such additional information as requested by
the City may render the Bidder non-
responsible or nonresponsive.

5. A Bidder must disclose those exceptions within the scope of the certification which are known to it, or which could be determined from a reasonable inquiry.

Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to render, in good faith, the required certification. The knowledge and information of a Bidder is not required to 376

20 General Conditions
2026

exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.

6. T he above- described certification is a material representation of fact upon which reliance will be placed when making the award, if and when made. If it is later determined that the Bidder knowingly rendered an erroneous certification, in addition to other remedies available to
the City, the City may terminate the
contract resulting from this solicitation for default.

If the Bidder has any exceptions to the certification set forth above, the exception and an explanation of the circumstances must be attached to the Bid.

SECTION 2.12. BID GUARANTY.

The Bid shall be accompanied by a Bid Guarant y in the form of a certified check, a cashier’s check, or a bidder’s bond issued in favor of the City in the form included in the bid documents as Attachment A, Bid Bond, and provided by a surety company authorized to do business in the State of California and listed in the current Federal Department of Treasury Circular 570. The Bid Guarantee shall be not less than ten percent (10%) of the Total Bid Price, excluding alternates. No Bid will be considered unless accompanied by a Bid Guarantee.

The City is authorized to forfeit such Bid Guarantee as necessary to reimburse for costs incurred for failure of the successful Bidder to enter into a contract.

The amount of the Bid Guarantee shall not be deemed to constitute a penalty or liquidated damages.

The City is not precluded by a Bid Guarantee from recovering from the defaulting Bidder damages in excess of the amount of said Bid Guarantee incurred as a result of the failure of the successful Bidder to enter into a contract with the City for the
Work.

SECTION 2.13. WITHDRAWAL OF BID.

A Bid may be withdrawn at any time prior to the hour fixed in the Invitation for Bids for the submission of Bids by a written request of the Bidder filed with the City at the location where the Bid was submitted. The withdrawal of a Bid will not prejudice the right of a Bidder to file a new Bid within the time prescribed.

SECTION 2.14. PUBLIC OPENING OF BIDS.

Bids will be opened and read publicly at the time and place indicated in the Notice to Contractors or in a subsequent Addendum. Bidders or their authorized representatives and other interested parties are invited to be present.

SECTION 2.15. REJECTION OF BIDS.

The City reserves the right to reject any or all Bids . The City reserves the right to waive irregularities in a Bid and to make an award in the best interest of the City. Bids containing omissions, erasures, alterations, conditions, or additions not called for may be rejected. 377

21 General Conditions
2026

SECTION 2.16. DISQUALIFICATION OF BIDDERS.

More than one Bid from any individual, firm, partnership, corporation, limited liability company association, or joint venture under the same or different names, will not be considered. Reasonable ground for believing that any Bidder is interested in more than one Bid for the Work will cause rejection of all Bids in which such Bidder is interested.

This prohibition shall not prevent any proposed Subcontractor from being listed in more than one Bid. This prohibition shall not prevent Bids by Bidders with partial ownership in common unless the two Bidders have identified the same individual as their responsible managing employee, member, manager or officer. If there is reason to believe that collusion exists among Bidders, none of the participants of such collusion will be considered.

Any Bid in which the prices obviously are unbalanced may be rejected.

SECTION 2.17. RELIEF OF BIDDERS.

Attention is directed to Public Contract Code Sections 5100 through 5107, concerning relief of Bidders and in particular to the requirement therein that if the Bidder claims a material mistake was made in its Bid, the Bidder shall give the City written notice within
five (5) days after the opening of the Bids (excluding Saturdays, Sundays, or Legal Holidays) of the alleged mistake, explaining in the notice in detail how the mistake occurred.

SECTION 2.18. BID PROTESTS.

If the Bidder believes that any provision in the solicitation for Bids is vague, ambiguous, conflicting or contrary to law, then the Bidder shall promptly bring its concern to the City by written notice specifying the provision(s) in question and the factual and legal bases for concern. Failure of the Bidder to raise any concern relating to a solicitation requirement within at least seven (7) calendar days prior to the Bid due date will be deemed a waiver of the Bidder’s right to protest based on alleged vague, ambiguous, conflicting or unlawful requirements in the solicitation.

As set forth in the “Resolution of Disputes Regarding the Bidding Process,” Attachment E to the Bid Documents , any Bidder may file a protest against the award of the Contract to any other Bidder. In submitting a Bid to the City, the Bidder agrees to comply with and to be bound by that procedure, as summarized below.

No later than five (5) calendar days after B ids are opened, the Bidder must submit in writing to the City an explanation of all legal and factual grounds for any protest. These requirements are to be strictly construed. Untimely protests and/or grounds not set forth in the protest will not be considered. Failure to timely protest or otherwise comply with the protest requirements will constitute a waiver of the right to challenge and forever bar the Bidder from challenging, whether before the City or any administrative or judicial tribunal, any particular Bid(s), the bidding process, or the Contract award on any ground not set forth in the protest. Upon receipt of a protest, the City will provide a copy to any Bidder whose Bid is challenged in the protest.

378

22 General Conditions
2026

If a timely written protest is provided to the City at least two (2) business days before any City Council meeting at which the award of the Contract will be considered, then the City shall make reasonable efforts to provide the protesting Bidder with a written response to the protest prior to the City Council meeting. A copy of any City response will be provided to any other Bidder responding to the protest.

Notice of the date and time of the City Council meeting at which the award of the Contract for the Project shall be considered will be posted on the City’s website.

379

23 General Conditions
2026

ARTICLE 3. AWARD AND EXECUTION OF CONTRACT; BONDS AND INSURANCE SECTION 3.01. AWARD OF CONTRACT.

Unless stated otherwise in the Invitation for Bids , the award of the Contract, if the Contract is to be awarded, will be to the lowest responsive, responsible Bidder. In addition to price in determining the lowest responsive, responsible Bidder, consideration will be given to:
• The ability, capacity and skill of the Bidder to perform the Work; • The ability of the Bidder to perform the Work within the time specified, without delay;
• The ability of the Bidder to perform the Work in a safe manner; • The character, integrity, reputation, judgment, experience and efficiency of the Bidder; and,
• The quality of the Bidder's performance on previous work with the City.

Unless otherwise specified in the Invitation for Bids or Special Provisions, if an alternate or alternates are identified by the City to the B idders, award will be based on any combination of Base Bid and Alternates as determined by the City. This process is conducted by the City in a “blind selection” format, i.e., without knowledge of the identity of any of the Bidders before ranking of all Bidders from lowest to highest has been determined. Bidders are to submit their Bid in two sealed envelopes, both containing all identifying information for the Project, and both of which are then to be included in a third sealed envelope containing all identifying information for the Project, but without any identifying information regarding the Bidder. The first envelope shall be marked “Envelope 1” and shall contain only an unsigned copy of the bidder’s bid form, without any identifying information for the bidder and without any other required bid submissions. The second envelope shall be marked “Envelope 2” and shall contain a complete copy of all required bid documents, including a signed copy of the bid form. Any discrepancies in the pricing information in the two sealed envelopes may render the bid nonresponsive. Alternates may be selected for award by
the City at its discretion. All awards will be made in the City’s best interest.

If the Invitation for Bids provides for a different basis of award, the basis and process identified therein shall apply.

SECTION 3.02. TIME OF AWARD.

The award, if made, will be made within sixty (6 0) days after the Bid Opening, unless otherwise specified. The period for contract award shall be tolled while any protest of an intended award is pending. The specified period of time within which the award of the Contract may be made may be extended as agreed upon in writing by the City and the Bidder before the last day specified in the solicitation for award.

If the lowest responsive, responsible Bidder refuses or fails to execute the Contract, or to provide required bonds and/or insurance certificates,
the City may award the Contract to
the second lowest responsive, responsible Bidder. If the second lowest responsive, 380

24 General Conditions
2026

responsible Bidder refuses or fails to execute the Contract or to provide required bonds and/or insurance, the City may award the Contract to the third lowest responsive, responsible Bidder.

SECTION 3.03. CONSIDERATION OF BIDS.

After the Bids have been opened and read, they will be checked for accuracy and compliance with the Specifications. In the event that the product of a unit price and an estimated quantity does not equal the extended amount quoted, the unit price shall govern and the correct product of the unit price and the estimated quantity shall be deemed to be the amount bid. If the sum of two or more items in a bidding schedule or the sum of two or more bidding schedules does not equal the total amounts quoted, the individual item or schedule amounts shall govern and the correct total shall be deemed to be the amount bid. If the Bid is missing the unit price, then it may be deemed incomplete and the Bid may be rejected.

After the City has made any necessary corrections in mathematical errors appearing on the face of the Bid, all Bids will be compared based on the bid form.

SECTION 3.04. PERFORMANCE AND PAYMENT BONDS.

As part of the execution of the Contract, and within ten (10) days after receiving notice of award, the successful Bidder shall furnish the following corporate surety bonds to the benefit of
the City. The format of the Performance Bond and Payment Bond forms shall be those contained in the Invitation for Bids. Bonds shall be executed by a surety company authorized to do business in the State of California and listed in the current Federal Department of Treasury Circular 570.

The successful Bidder must submit with the bonds
the original, or a certified copy, of the unrevoked appointment, power of attorney, bylaws or other instrument entitling or authorizing the person who executed the bond to do so.

When the amount to be paid to
the Contractor is based upon units of work to be performed or items to be provided, the term “Contract Sum” as used below for the purpose of posting Performance and Payment Bonds shall be computed on the basis of the unit price bid multiplied by the Estimated Quantities of work to be performed.

SECTION 3.04A. Performance Bond.

The Performance Bond, to guarantee the performance of all covenants and stipulations of the Contract, shall be on the form provided by
the City and shall be in a sum not less than
one hundred percent (100%) of the original Contract Sum as set forth in the Contract.

SECTION 3.04B. Payment Bond.

The Payment Bond, to guarantee the payment of wages and of bills contracted for materials, supplies, or equipment used in the performance of the Contract, shall be on the form provided by
the City and shall be in a sum not less than one hundred percent (100%) of the original Contract Sum as set forth in the Contract. 381

25 General Conditions
2026

SECTION 3.05. NOTIFICATION OF SURETY COMPANIES.

The surety company shall be familiar with all the provisions and conditions of the Contract. It is understood and agreed that the surety company waives notice of change, extension of time, alteration or addition to the terms of the Contract or to the work to be performed thereunder or to the specifications accompanying the same, or any other act or acts by
the City or the City’s authorized agents under the terms of the Contract; and failure to so notify the surety company of changes shall in no way relieve the surety company of its obligations under the Contract. Any alteration or alterations made in any provision of this Contract shall not operate to release any surety from liability on any bond required hereunder and the consent to make such alterations is hereby given, and any surety on said bonds hereby waives the provisions of Section 2819 of the Civil Code.

SECTION 3.06. RETURN OF BID GUARANTYS.

After Bids have been received and reviewed by the City, Bid Guarantys will be returned to the respective Bidders except those submitted by the three lowest responsive, responsible Bidders.

Bid Guarantys for Bids not to be further considered in executing the Contract will be returned within ten (10) days after the award of the Contract. The Bid Guarant ys of the three lowest responsive, responsible Bidders will be returned within ten (10) days after the successful Bidder has filed satisfactory bonds and proof of insurance as specified and the Bidder and the City have executed the Contract.

If all Bids are rejected and no award is made, all Bid Guarantys will be returned within ten (10) days of the decision of the City to not award the Contract.

SECTION 3.07. EXECUTION OF CONTRACT.

The Contract shall be executed by the successful Bidder and returned to the City, together with the Performance Bond, Payment Bond, certificates of insurance and insurance endorsements, and any other documents required at the time of Contract execution by the Special Provisions within ten (10) days of the Bidder’s receipt of the documents. Insurance certificates shall be signed by a person authorized by the insurer to bind coverage on its behalf and shall be accompanied by copies of all endorsements required by Section 3.09 below.

When requested by the City, the successful bidder shall furnish complete, certified copies of all required insurance policies, including endorsements specifically required by Section

3.09. After execution by the City , one copy of the Contract, bonds, and certificates of insurance will be returned to Contractor.

SECTION 3.08. FAILURE TO EXECUTE CONTRACT.

If the Bidder to whom the Contract is awarded fails to execute the Contract and file acceptable bonds and insurance certificates as provided herein within ten (10) days from the time the Contract forms are received by the Bidder, the award may be annulled and 382

26 General Conditions
2026

the Bidder’s Bid Guarantee forfeited to the City. At the City’s discretion, the Contract may then be awarded to the next lowest responsive, responsible Bidder.

If the City awards the Contract to the second lowest responsive, responsible Bidder, the amount of the lowest responsive, responsible Bidder's Bid Guarantee shall be applied by the City to the difference between the lowest Bid and the Bid of the second lowest responsive, responsible Bidder, and the surplus, if any, will be returned to the lowest responsive, responsible Bidder if a check or cash is used, or credited to the surety on the Bidder's Bond if a bond is used.

On refusal or failure of the second lowest responsive, responsible Bidder to execute the Contract, the City may award it to the third lowest responsive, responsible Bidder. If the City awards the Contract to the third lowest responsive, responsible Bidder, in addition to application of the lowest Bidder’s Bid Guarantee as aforesaid, the amount of the second lowest responsive, responsible Bidder’s Bid Guarantee shall be applied by the City to the difference between the Bid of the second lowest responsive, responsible Bidder and the Bid of the third lowest responsive, responsible Bidder, and the surplus, if any, shall be returned to the second lowest responsive, responsible Bidder if a check or cash is used, or credited to the surety on the second lowest Bidder’s Bid Bond if a bond is used.

Additionally, any forfeited Bid Guarantee shall be applied as necessary to reimburse for the costs incurred for failure of the successful Bidder(s) to enter into a contract. The surplus, if any, will be returned to the defaulting Bidder(s), if a check or cash is used, or credited to the surety on the Bidder’s Bond, if a bond is used.

The amount of the Bid Guarantee shall not be deemed to constitute a penalty or liquidated damages. The liability of the Surety shall not exceed the limits of the bid bond amount.

SECTION 3.09. INSURANCE.

Contractor shall procure, maintain, and keep in force at all times during the term of the Contract in insurance companies acceptable to the City, at Contractor’s sole expense, the following insurance:

SECTION 3.09A. General Liability.

General Liability insurance including, but not limited to, protection for claims of bodily injury and property damage liability, personal and advertising injury liability, contractual liability applicable to the Contractor’s assumed liability under the Contract, and products and completed operations liability. Coverage shall be at least as broad as “Insurance Services Office Commercial General Liability Coverage Form CG 0001” (occurrence).

The limits of liability shall be not less than:

383

27 General Conditions
2026

Each Occurrence Two Million Dollars ($2 ,000,000) combined single limits for Bodily Injury and Property
Damage

Personal and Advertising Injury One Million Dollars ($1,000,000)

Products and Completed
Operations Aggregate One Million Dollars ($1,000,000) combined single
Limits for Bodily Injury and Property Damage

General Aggregate Four Million Dollars ($ 4,000,000) combined single limits for Bodily Injury and Property
Damage

Fire Damage One Hundred Thousand Dollars ($100,000)

The policy shall provide coverage for claims arising out of subsidence.

Contractor shall procure and maintain Products and Completed Operations Coverage with a carrier acceptable to the City through the expiration of the patent deficiency in the statute of repose set forth in the Code of Civil Procedure section 337.1.

SECTION 3.09B. Automobile Liability.

Automobile Liability insurance providing protection against claims of bodily injury and property damage arising out of ownership, operation, maintenance, or use of owned, hired, and non- owned automobiles. Coverage shall be at least as broad as “Insurance Services Office Business Auto Coverage Form CA 0001,” symbol 1 (any auto). The limits of liability shall not be less than:

Bodily Injury and Property Damage
Combined Single Limit One Million Dollars ($1,000,000)

SECTION 3.09C. Workers' Compensation.

Workers' Compensation insurance in accordance with California Labor Code section 3200 et seq. in the statutory amount (unless the Contractor is a qualified self -insurer with the State of California), and Employers’ Liability coverage. The limits of Employers’ Liability shall not be less than:

Each Accident One Million Dollars ($1,000,000)
Disease Each Employee One Million Dollars ($1,000,000) Disease Policy Limit One Million Dollars ($1,000,000)

The Workers’ Compensation policy required hereunder shall be endorsed to state that the Workers’ Compensation carrier waives its right of subrogation against the City its officers, officials, employees, agents or volunteers.
384

28 General Conditions
2026

In the event the Contractor is self-insured, the Contractor shall furnish a Certificate of Permission to Self -Insure by the Department of Industrial Relations Administration of Self-Insurance, Sacramento. Contractor shall provide evidence of waiver of its right of subrogation against the City, its offices, officials, employees, agents or volunteers as a self-insurer.

SECTION 3.09D. Excess or Umbrella Liability.

If the Special Provisions require limits of insurance greater than those specified in the General Conditions, Contractor shall maintain excess or umbrella liability insurance providing excess coverage at least as broad as the underlying coverage for G eneral Liability, Automobile and Employer’s Liability with a limit equal to the amount stated in the Special Provisions per occurrence and aggregate.

SECTION 3.09E. Contractor’s Equipment.

Contractor, and each of its Subcontractors, shall separately insure its own equipment for loss and damage. Contractor’s Property and Inland Marine policies shall include, or be endorsed to include, a waiver of subrogation against the City, its officers, officials, employees, agents, and volunteers which might arise by reason of damage to the Contractor’s property or equipment (owned, leased or borrowed) in connection with work performed under this Contract by Contractor.

SECTION 3.09F. Railroad Protective Liability.

When stated as a requirement in the Special Provisions, Contractor shall procure, maintain, and keep in force at all times during the term of the Contract, at the Contractor’s sole expense, Railroad Protective Liability insurance with limits of liability as set forth in the Special Provisions.

SECTION 3.09G. Builder’s Risk Insurance.

When stated as a requirement in the Special Provisions, Contractor shall procure, maintain, and keep in force at all times during the term of the Contract and until the date of transfer of the insurable interest to and acceptance by the City, at Contractor’s sole expense, Builder's Risk insurance with limits of liability equal to one hundred percent (100%) of the full replacement cost of the Work.

1. Coverage shall be written on a Replacement Cost basis without application of coinsurance and shall cover the Project sites against losses included in perils usually included in a “Special Form” policy format in addition the policy shall include:

a. Earthquake and Land Movement and Flood.

b. Loss that ensues from design error, defective materials, or faulty workmanship.

c. Mechanical breakdown or electrical damage, including testing, magnetic 385

29 General Conditions
2026

disturbance and changes in temperature or humidity disturbance, and changes in temperature or humidity.

The property covered shall include the Work, including any materials, equipment, or other items to be incorporated therein while the same are located at the construction site, stored off site, while in transit or at the place of manufacture. In addition, the policy shall cover collapse, falsework, temporary buildings and debris removal including demolition occasioned by enforcement of any applicable legal requirements, and shall cover reasonable compensation for architects, engineers and other design professionals required as a result of such insured loss. The policy shall contain a provision that the interests of the City and Contractor , Subcontractors and material suppliers are insureds under the policy and that any loss shall be payable to the insureds as their interests may appear.

When stated as a requirement in the Special Provisions, Builder’s Risk Insurance shall include Delay in Opening coverage with limits of liability, and for the period of time, as set forth in the Special Provisions. Coverage shall include debt service, expense, loss of earnings or rental income or other loss incurred by the City, without deduction, due to the failure of the Project being completed on schedule.

2. The maximum deductible for earthquake, land movement and flood allowable under this policy shall be five percent (5%) of replacement value at risk at the time loss . A one hundred thousand dollars ($100,000) minimum is acceptable. The maximum deductible for all other perils allowable under this policy shall be ten thousand dollars ($10,000). All deductibles shall be borne solely by Contractor, Subcontractors, or material suppliers, and the City shall not be responsible to pay any deductible, in whole or in part.

3. The City and C ontractor waive all rights against each other and against all other contractors for loss or damage to the extent reimbursed by Builder ’s Risk insurance or any other property or equipment insurance applicable to the Work, except such rights as they may have to the proceeds of such insurance. If the policies of insurance referred to in this section require an endorsement or consent of the insurance company to provide for continued coverage where there is a waiver of subrogation, the owners of such policies will cause them to be so endorsed to obtain such consent.

4. If not covered by Builder ’s Risk insurance or any other property or equipment insurance required by this Contract, Contractor shall procure, maintain, and keep in force at all times during the term of the Contract, at the Contractor’s sole expense, property insurance for portions of the Contractor's work and/or equipment to be incorporated therein stored offsite or in transit.

386

30 General Conditions
2026

SECTION 3.09H. Environmental Liability Insurance.

When stated as a requirement in the Special Provisions, Contractor shall procure, maintain, and keep in force at all times during the term of the Contract, at Contractor’s sole expense, Environmental Liability insurance, using an occurrence form (Claims Made forms at not acceptable unless expressly allowed by the City), which includes coverage for sudden and accidental pollution arising out of the handling of hazardous materials or hazardous wastes; non-hazardous materials or non-hazardous wastes that, when released into the environment, violate regulatory standards of the Federal, State or Local Government; and coverage for liability arising out of the handling of asbestos.

If coverage for Environmental Liability insurance is allowed by the City to be written on a claims-made form, the following provisions apply:

Limit of coverage shall be not less than ten million dollars combined single limits for Bodily Injury and Property Damage ($10,000,000).

Insurance must be maintained and evidence of insurance must be provided for at least four (4) years after completion of the Work. Additional provisions, including Project specific coverage may be required at the sole discretion of the City.

SECTION 3.09(I). Other Provisions.

1. Contractor's General Liability, Automobile Liability, and any Excess or Umbrella Liability or other insurances required in the Special Provisions , shall contain the following provisions:

a. The City, its officers, officials, employees, agents, and volunteers shall be covered as additional insureds as respects liability arising out of the activities performed by or on behalf of Contractor, products and completed operations of Contractor, premises owned, occupied, or used by Contractor, or automobiles owned, leased, hired, or borrowed by Contractor. The policy shall contain no special limitations on the scope of coverage afforded to the City, its officers, officials, employees, agents, or volunteers.

b. For any claims related to this Contract, the Contractor's insurance coverage shall be primary insurance as respects the City, its officers, officials, employees, agents, or volunteers. Any insurance or self - insurance maintained by the City, its officers, officials, employees, agents, or volunteers shall be excess of the Contractor's insurance and shall not contribute with it.

c. Any failure to comply with reporting or other provisions of the policies on the part of the Contractor, including breaches of warranties, shall not affect coverage provided to the City, its officers, officials, employees, agents, or volunteers.

2. The Contractor's General Liability and any Excess or Umbrella Liability 387

31 General Conditions
2026

insurance policies shall contain an endorsement stating that any aggregate limits shall apply separately to the Work.

3. Contractor’s insurance shall apply separately to each insured against whom claim is made or suit is brought, except with respect to the limits of the insurer’s liability.

4. Each insurance policy by endorsement or provision shall state that coverage shall not be suspended, voided, cancelled, reduced in scope of coverage or in limits, non-renewed, or materially changed unless the insurer(s) provide thirty (30) Calendar D ays written notice by certified mail to the City prior to such change. Ten (10) Calendar D ays prior written notice by certified mail shall be given to the City in the event of cancellation due to nonpayment of premium.

5. For all work Contractor or its Subcontractors perform during the guarantee period, worker's compensation, and commercial general liability insurance and insurance in the amounts and format required herein, shall remain in effect.

6. All of Contractor's insurance coverage, except as noted below, shall be placed with insurance companies with a current A.M. Best rating of at least A- IX.

Exception: Workers' Compensation which is provided through a State Compensation Insurance Fund or a qualified self -insurer for Workers' Compensation under California law.

7. Contractor shall sign and file with the City the following certification prior to commencing performance of the work of the Contract:

“I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for worker’s compensation or to undertake self -insurance in accordance with the provisions of the Code, and I will comply with such provisions before commencing the performance of the Work of this Contract.”

Said certification is included in the Contract, and signature and return of the Contract shall constitute signing and filing of the said certification.

8. Contractor or its insurance broker shall submit a copy of the Declarations page for each policy required hereunder. The page shall include the name of the carrier, the policy number, the types of coverage and limits, the effective dates of the policy, and the broker’s name and license number.

9. The City, at its discretion, may require new types of insurance coverage or increase the limits of insurance coverage required hereunder at any time during the term of the Contract by giving thirty (30) Calendar D ays written 388

32 General Conditions
2026

notice to Contractor. Contractor shall immediately procure such insurance or increase the limits of coverage and provide certificates of insurance, including copies of all required endorsements, to the City within thirty (30) Calendar Days of receipt of the City’s request.

10. The required insurance coverage shall be subject to the approval of the City, but any acceptance of insurance certificates by the City shall in no way limit or relieve Contractor of its duties and responsibilities in this Contract.

11. If Contractor fails to procure or maintain insurance as required by this Section

3.09 and each of its subsections and any Special Provisions, or fails to furnish the City with proof of such insurance, the City, at its discretion, may procure any or all such insurance. Premiums for such insurance procured by the City shall be deducted and retained from any sums due Contractor under the Contract. Failure of the City to obtain such insurance shall in no way relieve Contractor from any of Contractor’s responsibilities under the Contract. Any failure of Contractor to maintain any item of the required insurance is sufficient cause for termination of the Contract as a material breach.

12. The making of progress payments to Contractor shall not be construed as relieving Contractor of responsibility for loss or damage, or destruction occurring prior to final acceptance by the City. Partial payment does not constitute partial acceptance.

13. The City is authorized to execute amendments and waivers, with or without conditions, to the insurance requirements of the Contract. The City will provide such amendments or waivers in writing to Contractor.

14. The Contractor is responsible for the acts and omission of all of its Subcontractors and shall require all of its Subcontractors to maintain adequate insurance. Except that Subcontractors need obtain only $1,000,000 of Comprehensive General Liability insurance, all Subcontractors shall maintain the same insurance required to be maintained by Contractor with respect to their portions of the Work, and Contractor shall cause the Subcontractors to furnish proof thereof to the City within ten d ays of the City's request.

The failure of the City to enforce in a timely manner any of the provisions of this Section

3.09 and/or any of its subsections shall not act as a waiver to enforcement of any of these provisions at any time during the term of the Contract.

3-9.04.F Deductibles and Self-Insurance Retention

Any deductible or self-insured retention over $10,000 that applies to General Liability or Automobile Liability must be declared to and approved by the City. 389

33 General Conditions
2026

SECTION 3.09J. Notification of Accident or Occurrence.

Contractor shall report by telephone to the City within twenty-four (24) hours and also report in writing to the City within fifteen (15) Calendar Days after Contractor or any Subcontractors or agents have knowledge of any accident or occurrence involving death of or injury to any person or persons, or damage in excess of ten thousand dollars ($10,000) to the Work, property of the City or others, arising out of any work done by or on behalf of Contractor as part of the Contract. Such report shall contain:

1. The date and time of the occurrence,

2. The names and addresses of all persons involved, and

3. A description of the accident or occurrence and the nature and extent of injury or damage.

SECTION 3.09K. Notification of Claim.

If any claim for damages is filed with Contractor or if any lawsuit is instituted against Contractor, that arises out of or is in any way connected with Contractor ’s performance under this Contract and that in any way, directly or indirectly, contingently or otherwise, affects or might reasonably affect the City, Contractor shall give prompt and timely notice thereof to the City. Notice shall be prompt and timely if given within thirty (30) Calendar Days following the date of receipt of a claim or ten (10) Calendar Days following the date of service of process of a lawsuit.
390

34 General Conditions
2026

ARTICLE 4. SCOPE OF WORK
SECTION 4.01. THE CONTRACT.

The Contract Documents form the Contract for Construction. This Contract represents the entire and integrated agreement between the City and Contractor and supersedes all prior negotiations, representations or agreements, either written or oral. The Contract may be amended or modified only by a Change Order. Nothing contained in the Contract Documents shall create any contractual relationship between the City , City Representative, Architect or Consulting Engineer, on the one hand, and any Subcontractor or sub- subcontractor on the other hand, or between the City ’s Representative, Architect or Consulting Engineer, on the one hand, and Contractor on the other hand.

SECTION 4.02. INTENT OF CONTRACT DOCUMENTS.

It is the overriding intent of the Contract Documents that the work performed shall result in a complete and operable project in satisfactory condition for occupancy, with all mechanical equipment in functional operating condition and fit for the use for which it is intended, and which complies in all respects with the Contract Documents. No extra compensation will be allowed for anything omitted but fairly implied to be included in the Contract Documents. The prices paid for the various items in the bid shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and doing all items necessary to complete the Work as provided by the Contract Documents.

The prices paid include all taxes, overhead, markups and profit.

Unless otherwise specified, Contractor agrees to furnish and pay for all materials, supplies, equipment, tools, labor, transportation, supervision, resources, and everything else necessary to perform and complete the Work , including any Change Order work or disputed work directed by
the City, in a good and workmanlike manner to the satisfaction of the City, in the manner designated, and in strict conformity to the Contract and any applicable code or statute, whether or not specifically described herein, as long as same is reasonably inferable therefrom as being necessary to produce the intended results, whether temporary or permanent, and whether or not incorporated or to be incorporated in the Work.

When portions of the Work are described in general terms, but not in complete detail, it is understood that Contractor will employ only the best general practice and incorporate only the best quality materials and workmanship in the Work.

Scale drawings, full-size details, and specifications are intended to be fully coordinated and to agree. Where not specifically stated otherwise, all work and materials necessary for each unit of construction, even though only briefly mentioned or indicated, shall be furnished and installed fully and completely, including, but not limited to, the manufacturer’s instructions and/or recommendations, as part of this Contract.

All work shown on the Plans, the dimensions of which are not figured, shall be accurately followed to the scale to which the drawings are made; however, figured dimensions shall in all cases be followed, even if they differ from scaled measurements. 391

35 General Conditions
2026

Full-size drawings shall be followed in the execution of the Work.

If the Contract does not specifically allow Contractor a choice of quality or cost of items to be furnished, but could be interpreted to permit such a choice, Contractor shall furnish the highest quality under current industry standards, regardless of the cost of the item.

If Contractor discovers any discrepancies during the course of the Work between the Plans and conditions in the field, or any errors or omissions in the Plans and conditions in the field, or any errors or omissions in the Plans, the Specifications, or in the layout given by stakes, points, or instructions, it shall be Contractor 's duty to inform the City immediately, and the City shall promptly verify the same. Any work done after such discovery, until authorized by the City, will be done at Contractor's risk.

SECTION 4.03. PLANS AND SPECIFICATIONS FURNISHED.

The Contractor may obtain online, at no cost, copies of Project Plans (except Standard Drawings or State Plans), Project Specifications (the State Specifications), and Special Provisions, and the fully executed Contract for the Contractor’s use in prosecuting the Work. The Contractor may purchase from the City hard copies of these documents.

The Contractor shall retain an approved set of Contract documents on the job during the progress of the Work. This set shall be used by the Contractor as the Record Drawings as described in Section 11.03, “Record Drawings” of these General Conditions.

SECTION 4.04. CONFORMANCE WITH CODES AND STANDARDS.

The Work shall be in full compliance with the latest adopted edition of the following applicable standards and regulations:
• California Department of Transportation (“Caltrans”) standard plans and specifications
• The State Fire Marshal regulations and requirements
• City Design and Construction Standards
• Placer County applicable standards and permitting
• The UBC
• Title 8
• Title 22
• Title 24
• Title 29
• The NEC
• The UPC
• Storm Water Pollution Prevention Plans and Standards
• Other codes, laws or regulations applicable to the Work or the Contract. 392

36 General Conditions
2026

Nothing in the Contract is to be construed to permit work not conforming to these requirements. When the Work detailed in the Plans and Specifications differs from governing codes, Contractor shall complete the Work in accordance with the higher standard. If the higher standard is more expensive than the Work detailed in the Plans and Specifications, Contractor will be compensated for Contractor ’s additional costs by Contract Change Order as provided in Article 9, “Changes and Claims”, of these General Conditions.

SECTION 4.05. DIAGRAMMATIC DRAWINGS.

Drawings showing the locations of equipment, wiring, piping, etc., unless dimensioned, are diagrammatic, and conditions will not always permit their installation in the exact location shown. In such event, Contractor shall submit an RFI and obtain a response before proceeding with the work in question. Unless there is a material increase in Contractor’s scope of work, installation as specified in the response to the RFI shall be without any additional compensation to Contractor and without any increase in the Contract Time. Any work done after discovery of the issue, until authorization to proceed based on the response to the RFI, will be done at Contractor’s risk.

SECTION 4.06. INSTRUCTION BULLETINS AND DRAWINGS.

In addition to the Drawings incorporated in the Contract Documents, the Architect , Consulting Engineer or Engineer may furnish such supplemental drawings or instructions from time to time as may be necessary to make clear or to define in greater detail the intent of the Contract Drawings and Specifications. In furnishing additional drawings or instructions, the Architect, Consulting Engineer or Engineer shall have the authority to make minor changes in the Work, not involving any extra cost, and not inconsistent with the overall design of the Project. If extra cost is known to be involved, these instructions will be accompanied by an RFP. These supplemental drawings and instructions shall become a part of the Contract Documents; Contractor shall make its work conform to them.

SECTION 4.07. FIELD DIRECTIVES OR OTHER WRITTEN DIRECTIVES.

The City may issue Field Directives or other written directives from the office or field during the course of the Work, and Contractor shall immediately comply with the Field Directive or other written directive. Contractor must perform all work directed by a field directive, whether or not Contractor believes the work is included in the Contract and regardless of any disputes regarding money, time and/or other issues. Contractor acknowledges that continued progress
of the Work is of high importance and that such
disputes can be resolved as the Work progresses.

A Field Directive or other written directive may be used to add, delete, modify, or reject work, to note deficiencies in work, to clarify the Contract or to order work to be performed.

Work required by a Field Directive or other written directive shall be in accordance with the Contract and any previously executed Change Orders, except as delineated otherwise in the directive. Drawings included with Field Directives or other written directives are part of the Contract and shall be incorporated into the Record Drawings. 393

37 General Conditions
2026

If Contractor refuses or neglects to comply with or make progress in the execution of any Field Directive or other written directive, the City , in addition to all other rights under the Contract and/or applicable law, may employ any person or persons to perform such work at Contractor’s cost, and Contractor shall not interfere with the person or persons so employed.

At appropriate intervals, Field Directives and/or other written directives that alter the Contract may be grouped to form a Change Order as described in Article 9, “Changes and Claims”, of these General Conditions.

SECTION 4.08. COMPLEMENTARY FEATURE OF C ONTRACT DOCUMENTS ; ORDER OF PRECEDENCE.

The Contract Documents, including the Specifications and Plans and Drawings, are complementary and what is called for by any one shall be as binding as if called for by all.

In case of conflict , the following order of precedence will govern interpretation of the Contract:

1. Permits from other agencies as may be required by law;

2. The Agreement for Construction, as amended by Change Orders and any other Contract amendments;

3. Special Provisions;

4. Technical Specifications;

5. Plans and Drawings;

6. General Conditions and General Requirements;

7. Invitation for Bids [Notice to Contractors], including attachments and addenda;

8. City of Rocklin Construction Standard Specifications;

9. City of Rocklin Improvement Standards;

10. State of California Department of Transportation Standard Plans and Specifications.

In addition, the following shall also apply:

1. Written numbers and notes on a drawing shall govern over graphics.

2. A detail drawing governs over a general drawing.

3. A detail specification governs over a general specification.

4. A specification in a section governs over a specification referenced by that section.

5. Changes last in time govern prior requirements.

In case of conflict between the Project Plans and Technical Specifications, the Plans shall govern in matters of quantity and size, the Technical Specifications in matters of quality.

In case of conflict within the Plans involving quantities or within the Technical Specifications involving quality, the greater quantity and the higher quality shall be provided.
394

38 General Conditions
2026

Where on any Drawing a portion of the Work is drawn out and the remainder is indicated in outline, the drawn out parts shall apply to all other like portions of the Work. Where ornament or other detail is indicated as starting, such detail shall be continued throughout the courses or parts in which it occurs and shall also apply to other similar parts in the Work, unless otherwise indicated.

A typical or representative detail on Drawings shall constitute the standard for workmanship and material throughout corresponding parts of Work. Where necessary, and where reasonably inferable from Drawings, Contractor shall adapt such representative detail for application to such corresponding parts of Work. The details of such adaptation shall be subject to prior approval by the City . Repetitive features shown in outline on Drawings shall be in exact accordance with corresponding features completely shown.

All work shown on the Plans, the dimensions of which are not figured, shall be accurately followed to the scale to which the drawings are made; however, figured dimensions shall in all cases be followed, even if they differ from scaled measurements. Full-size drawings shall be followed in the execution of the Work.

Any material specified by reference to the number, symbol, or title of a specified standard such as a Commercial Standard, a Federal Specification, a trade association standard, or other similar standards, shall comply with the requirements in the latest approved revision thereof and any amendments or supplements thereto in effect on the date of Notice to Contractors, except as limited to type, class, or grade, or modified in such reference. The standards referred to, except as modified in the Contract Documents, shall have full force and effect as though printed in
the Contract Documents.

SECTION 4.09. INTERPRETATION AND ADDITIONAL INSTRUCTIONS; REQUESTS FOR INFORMATION.

SECTION 4.09A. General.

Contractor shall prepare a Request for Information (RFI) when additional information, clarification, or interpretation of the Contract is required. RFIs may also be used for apparent conflicts, inconsistencies, ambiguities, or omissions.

RFIs shall be submitted to the City sufficiently in advance of the work to permit time for investigation and preparation of a response. Any work undertaken prior to receipt of a response to an RFI will be at Contractor’s risk.

RFIs shall not be used for submittals or for substitution of material or equipment, or for waiving of requirements.

SECTION 4.09B. Procedure.

An RFI shall be submitted on an approved form as defined at the preconstruction meeting, and shall be numbered consecutively. A status log shall be prepared and updated by
the Contractor and reviewed with the City at each progress meeting. Each RFI shall deal with only one topic, item, issue, or system. The RFI shall clearly describe 395

39 General Conditions
2026

and specifically state what is being requested. Relevant portions of the Contract shall be cited, marked-up, and attached.

Contractor shall review each RFI before submittal and compare it with the Contract to verify that a response is required. RFIs will only be accepted from the Contractor and not from Subcontractors or suppliers. A recommendation or proposed solution may be included when appropriate or expedient. RFIs that are not clear or RFIs for which a response is clearly identified in the Contract will not be accepted.

SECTION 4.09C. Response.

Unless otherwise specified in the Contract Documents, the City will normally respond within fifteen (15) Working Days. The City will provide a written response, and that response shall control. Contractor shall indicate a priority for responses to RFIs if more than five (5) RFIs are pending at the same time. In case of a dispute between Contractor and the City , protest may be made as provided in Section 9.15 , “Dispute Regarding Contract Requirements”, of these General Conditions.

Subsequent resubmittals of an RFI shall be identified with the same RFI number and a letter designation. Resubmittals shall clearly state the reason for the resubmittal.

Responses to
RFIs indicating a change to drawings shall be recorded by Contractor on the Record Drawings.

SECTION 4. 10. NOTIFICATION OF DISAGREEMENT REGARDING SCOPE OF WORK.

If agreement cannot be reached as to cost, and Contractor does not agree that work due to an interpretation or supplemental drawing or instruction or directive is within the scope of the Contract Documents, Contractor shall, within seven (7) days after receipt of the interpretation, supplemental drawing, instruction or directive, submit a Proposed Change Order to the City specifying in detail in what particulars the contract requirements were exceeded and the change in cost resulting there from. The City shall then determine whether a Change Order shall be issued in accordance with Article 9 of these General Conditions. Contractor shall nevertheless perform such work without delay.

The time during which the protest is pending shall not affect the Contract Time.

SECTION 4.11. DELETED ITEMS.

The City may delete from the Work any item of work. Contractor will be paid for all work done toward the completion of the item prior to such deletion, as provided in Article 9, “Changes and Claims”, of these General Conditions but in no event will the amount paid exceed the Bid or Schedule of Values amount less the value of the deleted work.

Contractor shall make no claim, nor receive any compensation for profits, for loss of profit, for damages, or for any extra payment whatever because of any deleted items of work. 396

40 General Conditions
2026

SECTION 4.12. EXTRA WORK.

Work not covered by the Contract but necessary for the proper completion of the Project will be classed as extra work and shall be performed by the Contractor in accordance with the Contract and as directed by the City.

Extra work must be authorized in writing by the City before the work is started. Payment for extra work will not be made unless such prior written authorization is obtained.

In the event of an emergency or other situation that endangers the Work or endangers public safety, the City will direct Contractor to perform such extra work necessary to protect the Work or the public.

SECTION 4.13. USE OF COMPLETED PORTIONS.

The City has the right during the progress of the Work to occupy and/or use any completed or partially completed portion of the Work. Such use shall not be deemed acceptance of that portion, nor of any other portions of the Work, nor of work not completed in accordance with the Contract.

Under unusual circumstances on an exception basis, and only by written approval of the City, the City may provide a field acceptance of a completed portion of the Work under Section 7.21, “Final Inspection and Field Acceptance”, of these General Conditions, such that the warranty period for that portion will be considered to commence and Contractor will be relieved of any further maintenance and protection of that portion. No final payment shall occur for a limited portion of the work. Contractor will not be relieved of the Contract requirements for repairing or replacing defective work and materials in accordance with Sections 7.21 and 7.23, “Warranty Work”, of these General Conditions.

SECTION 4.14. LANDS AND RIGHTS-OF-WAY.

The City shall provide the lands, rights-of-way, and easements upon which the Work is to be done, and such other lands as may be designated on the Plans for the use of Contractor. Contractor shall confine its operations to within these limits. Contractor shall comply with the terms and conditions of right of entry, right of way and easement documents. The City shall provide photocopies of these documents to Contractor prior to Contractor’s use of, or commencement of Work, in the lands in question.

Contractor shall provide at the Contractor's own expense any additional land and access that is required for temporary construction facilities or storage of materials. Contractor shall obtain all required permissions for use of private property prior to taking possession or use. The permission shall be obtained in writing and a copy forwarded to the City prior to Contractor taking possession of said property.

SECTION 4.15. WARRANTY.

Unless otherwise specified in the Contract Documents, the warranty time period will be one year after the City’s acceptance of Work (see Section 7. 22, “Final Acceptance and Notice of Completion”, of these General Conditions) and subject to the terms of 397

41 General Conditions
2026

Contractor Guarantee Form in accordance with Attachment M to the Bid Documents. The Performance Bond furnished by Contractor as part of the execution of the Contract shall include the terms and time period of the Warranty of Contractor ’s work . In lieu of continuing the original performance bond through the warranty period, Contractor may submit a warranty bond, on a form substantially the same as the Performance Bond, for a minimum of ten percent (10%) of the total project value to be valid for one year from the date of acceptance by
the Council, subject to extension in accordance with Contractor Guarantee Form for corrected defective work.

If required by the Contract Documents , Contractor shall enter into and sign Warranty statements in the form provided to warranty various segments of the Work for the time specified.

If failure of any portion of the Work can be attributed to faulty materials, poor workmanship, defective equipment, or any other reason that can be attributed to Contractor’s performance, and this failure occurs prior to the end of the specified warranty period, Contractor shall promptly make the needed repairs at Contractor 's expense in accordance with Section 7.23, “Warranty Work”, of these General Conditions. 398

42 General Conditions
2026

ARTICLE 5. CONTROL OF WORK AND MATERIALS
SECTION 5.01. AUTHORITY OF THE CITY.

The City will decide all questions regarding the quality and acceptability of materials furnished, work performed, and rate of progress of the Work . The City will decide all questions regarding the interpretation and fulfillment of the Contract on the part of Contractor, and all questions as to the rights of different contractors that may be involved with the Work.

The City will determine the amount and quality of the Work performed and materials furnished for which payment is to be made under the Contract.

The City will administer its authority through a duly designated representative identified at the preconstruction meeting. Contractor and the City representative shall make good faith attempts to resolve disputes that arise during the performance of the Work.

Any order given by the City not otherwise required by the Contract to be in writing will be given or confirmed by the City in writing at Contractor’s request. Such request shall state the specific subject of the decision, directive, instruction, or notice and, if it has been given orally, its date, time, place, author and recipient.

SECTION 5.02. ATTENTION AND COOPERATION OF CONTRACTOR.

Contractor shall comply with any written instruction delivered to Contractor or Contractor’s authorized representative by appropriately authorized representatives of the City.

SECTION 5.03. SUGGESTIONS TO CONTRACTOR.

Any plan or method suggested to Contractor by the City, but not specified or required in writing, if adopted or followed in whole or in part by Contractor , shall be used at the risk and responsibility of Contractor. The City assumes no responsibility.

SECTION 5.04. SEPARATE CONTRACTS.

The City reserves the right to award other contracts in connection with the Work.

Contractor shall afford other contractors reasonable opportunity for the delivery and storage of their materials and the execution of their work and shall properly connect and coordinate its work with the other contractors.

If any part of Contractor's work depends upon the work of any other contractor for proper execution or results, Contractor shall inspect and promptly report to the City any defects in such work that render the other contractor’s work unsuitable for proper execution and results. Contractor's failure to so inspect and promptly report shall constitute an acceptance of the other contractor's work as fit and proper for the reception of Contractor's work, unless defects develop in the other contractor's work after the execution of Contractor's work.
399

43 General Conditions
2026

SECTION 5.05. COOPERATION WITH OTHER CONTRACTORS.

Other contractors and other forces, including the City and/or adjacent property owners, may perform work adjacent to or within the Work area concurrent with Contractor 's operations. Contractor shall conduct operations to minimize interference with the work of other forces or contractors. Any disputes or conflicts between Contractor and other forces or contractors retained by the City which create delays or hindrance to each other shall be referred to the City for resolution. If Contractor’s work is delayed because of the acts or omissions of any other force or contractor, Contractor shall have no claim against the City other than for an extension of time (see Section 7. 18, “Extension of Time”, of these General Conditions).

SECTION 5.06. SUPERVISION PROCEDURES.

Contractor shall supervise and direct the Work using its best skill and attention.

Contractor shall be solely responsible for all construction means, methods, techniques, and procedures and for coordinating all portions of the Work under the Contract.

Contractor shall be responsible to the City for the acts and omissions of its employees, subcontractors and their agents and employees and other persons performing any of the Work.

It is prohibited to hire undocumented workers. Contractor shall secure and cause its Subcontractors to secure proof of eligibility/citizenship to work from all workers.

Contractor shall not be relieved from its obligations to perform the Work in accordance with the Contract Documents either by the activities or duties of the Architect, Consulting Engineer or Owner’s Representative in their administration of the Contract or by inspections, tests or approvals (or the lack thereof) required or performed by persons other than Contractor.

SECTION 5.07. SKILLED LABOR.

All non-apprentice labor shall have the skills of a journeyman in the applicable trade. All workmanship shall be of the highest quality and finish in all respects.

SECTION 5.08. CONTRACTOR’S DISMISSAL OF UNSATISFACTORY EMPLOYEES.

If any person employed by Contractor or any Subcontractor shall fail or refuse to carry out the directions of the City or the provisions of the Contract, or is, in the opinion of the City, incompetent, unfaithful, intemperate, or disorderly; or uses threatening or abusive language or conduct to any person on or associated with the Work or with the public; or is acting or working in a manner that compromises the safety of the public, Work or persons or property involved with the Work, or is otherwise unsatisfactory, Contractor shall, when requested by the City , remove the worker from the Work site immediately, and shall not again employ the removed worker on the Work except with the written consent of the City
.
400

44 General Conditions
2026

SECTION 5.09. CONTRACTOR'S EQUIPMENT.

Contractor shall provide adequate and suitable equipment, labor, and means of construction to meet all the requirements of the Work, including completion within the Contract Time. Only equipment suitable to produce the quality of work required will be permitted to operate on the Project. Specific types of equipment may be requested by the City on component parts of the Work.

The City may, at the City’s option, permit the use of new or improved equipment, at Contractor’s cost. If such permission is granted, it is understood that it is granted for the purpose of testing the quality and continuous attainment of work produced by the equipment, and the City shall have the right to withdraw such permission at any time that the City determines that the alternative equipment is not producing work that is equal in all respects to that specified, or will not complete the Work in the time specified in the Contract. The cost for mobilizing and demobilizing new or improved equipment shall be borne by Contractor.

In any case where the use of a particular type or piece of equipment has been banned, or in cases where the City has condemned for use on the Work any piece or pieces of equipment, Contractor shall promptly remove such equipment from the site of the Work at its cost. Failure to do so within a reasonable time may be considered a breach of contract.

The cost for mobilizing and demobilizing replacement equipment shall be borne by Contractor.

SECTION 5.10. CONTRACTOR'S SUBMITTALS.

SECTION 5.10A. Submittals – General.

Contractor shall furnish all working drawings, plans, specifications, descriptive data, certificates, samples, tests, methods, schedules, and manufacturer's instructions as required in the Contract, and any other information required to demonstrate that the materials and equipment to be furnished and the methods of work comply with the provisions and intent of the Contract. Submittals shall be submitted by the dates specified in the Contract or, in the City’s sole discretion, a fine of $100 per day will be levied until the appropriate submittals are properly submitted.

Submittals for systems shall be bound together , include all information for the system and, unless otherwise specified, submitted to the City electronically.

Depending on the complexity of the submittal, the number of submittals, and the express needs of the Contractor, the submittal and/or submittal review comments will be returned to the Contractor within thirty (30) Calendar Days, exclusive of any time awaiting clarification or further information. Where any item of the work is required to be installed in accordance with the manufacturer's recommendations, the Contractor shall furnish a complete set of the manufacturer's installation recommendations to the City prior to starting the installation. These submittals will be retained by the City.

401

45 General Conditions
2026

If the information furnished in a submittal shows any deviation from the Contract requirements, Contractor shall, by a statement in writing accompanying the information, advise the City of the deviation and state the reasons. It shall be Contractor 's responsibility to ensure there is no conflict with other submittals and to notify the City in any case where Contractor's submittal may concern work by another contractor, adjacent property owners, other forces or the City.

Contractor is solely responsible for coordination of submittals among all related crafts performing the Work. Contractor shall verify that its Subcontractors’ submittals are complete in every way and meet the requirements of the Contract.

Direction from the City to proceed following return of Contractor 's submittals shall not relieve Contractor of responsibility for any error or of any obligation for accuracy of dimensions and details, for agreement with and conformity to the Contract, or responsibility to fulfill the Contract as prescribed. Nor shall such direction be considered as approval of any deviation or conflict in the submittal unless the City has been expressly advised in writing of the same as set forth immediately above, and the City has expressly approved such deviation or conflict in writing.

Contractor shall make no changes to any submittal after it has been returned, and the equipment or materials shall not deviate in any way except with written approval by the City. Fabrication or other work performed in advance of return of the submittal with a direction to proceed shall be done entirely at Contractor's risk.

Minimum requirements for submittals are contained in these General Conditions .

Additional and/or project -specific requirements may be contained in the Contract Documents. Contractor is responsible for identifying and providing all required submittals.

SECTION 5.10B. Resubmittals.

Resubmittals shall address all comments from the City . Partial resubmittals may be returned ‘REVISE AND RESUBMIT.” Contractor is responsible for the City’s review costs for each resubmittal in excess of the first resubmittal. These costs will be charged to Contractor and will be deducted from progress payments.

SECTION 5.10C. Submittals Containing Proprietary Information.

All required information shall be provided even though some or all of such information may be considered proprietary. If any of the information required herein is considered proprietary, a proprietary agreement shall be executed between the City and the Contractor, stipulating that all such information will be supplied by the Contractor and kept confidential by the City. All proprietary data shall be identified as part of Contractor's Bid and the proprietary agreement shall be executed before award of the Contract.

Proprietary information is defined as any information or data describing or defining a product, process or system which 1) was developed at the expense of the Contractor, a Subcontractor or supplier; 2) is not generally available in the industry; and 3) is kept secret by its owner for purposes of preventing its use by others. Application software and all other documentation, or any other product, prepared by Contractor , 402

46 General Conditions
2026

Subcontractor, or supplier at the expense of the City for specific use on the facility being constructed under the Contract shall not be considered proprietary.

All submitted proprietary information shall describe the final record Work. No part of the Work covered by the proprietary agreement shall be modified after proprietary submittal acceptance until updated proprietary information has been submitted by Contractor and accepted by the City . Updated proprietary information shall fully document all modifications to be implemented. All proprietary data shall be marked “PROPRIETARY” by Contractor.

SECTION 5.10D. Electrical, Instrumentation, Control, and Communication Systems.

Electrical, instrumentation, control, and communication system drawings shall include elementary and loop diagram drawings, functional single line system layout drawings, connection drawings, interconnection drawings, panel/cabinet fabrication drawings, and detailed circuit board and component drawings. Detailed circuit schematics and circuit board layout drawings shall clearly show, locate, and identify all components and wiring.

Each circuit board component shall be identified by the component's original manufacturer name and part number.

Industry standard part numbers shall be used. Component values, voltage/current levels, setpoints, and timing values shall be defined. Drawings shall be in the latest version of AutoCAD or other electronic reproducible medium specified by the City.

Conduit layout diagrams shall be provided for all electrical conduits, and conduits shall be labeled in the field consistent with the layout diagrams.

Complete annotated software/firmware source code listings and program documentation shall be provided for all electronic/electrical systems, subsystems, assemblies, parts, components, and equipment that incorporate programmable devices. All instructions and hardware necessary to load, store, modify, and activate software/firmware source codes and programs shall be provided.

SECTION 5.10E. Operation and Maintenance (O&M) Submittals.

For use in subsequent maintenance and operations , Contractor shall furnish to the City electronically and bound together and indexed all maintenance and operation information, including all the highest level of factory maintenance manuals (greatest level of detail) that are available to factory representatives with a three-year subscription to newsletters and updates supplied by the manufacturer covering all equipment and systems included in the Contract. The City may withhold up to thirty percent (30%) of the Contract Sum until O&M submittals have been submitted and approved. The submittal shall include at a minimum:
• Drawings
• Illustrations
• Parts lists
403

47 General Conditions
2026

• Wiring diagrams of systems
• Internal wiring diagrams and circuit board schematics and layout drawings • Manufacturer's recommended spare parts lists
• Name, address and phone number of nearest parts and service provider • Systems balance data
• Maintenance and service instructions
• Operation instructions
• Software including annotated source lists and programs The submittal of maintenance and operation information is required for all mechanical, electrical, instrumentation, control, communications, sound, or special equipment and systems.

Contractor shall obtain approval of the required data at least thirty (30) Calendar Days prior to any required training or the final inspection date.

SECTION 5.11. DAILY REPORTS.

No less than on a weekly basis, Contractor shall submit, upon request of the City, to the City daily reports, which shall include, without limitation, the identity of Subcontractors on the site, an accurate headcount of workers on the site, materials and equipment delivered to the site, visitors to the site, work performed, and any problems encountered.

SECTION 5.12. SURVEYS.

SECTION 5.12A. Surveys.

Except as set forth in this Section or in the Special Provisions, Contractor shall be responsible for performing all necessary surveys to lay out and control the Work to the locations, elevations, lines, and dimensions shown or specified in the Contract. Any deviations must receive prior written approval of the City. All surveys affecting the line or elevation of underground drainage, sewers, or utilities, and all other work within public rights-of-way or easements, shall be performed by or under the direction and supervision of a California Registered Civil Engineer authorized to practice land surveying or a California Licensed Land Surveyor. Contractor shall be responsible for protecting and perpetuating survey monuments affected by construction activities in accordance with Business and Professions Code Section 8771(b). Contractor shall be responsible for the accuracy of Contractor's own layout work, and shall be liable for the preservation of all established lines and grades.

Stakes damaged or destroyed by the operations of Contractor shall be replaced at Contractor’s expense.

Contractor’s surveys also shall include, without limitation, the following surveys:

404

48 General Conditions
2026

5.12A.1 Streets and Highways
• Slope Stakes -- One line of slope stakes at fifty -foot (50’) intervals for the construction of each pavement edge. The Contractor shall set back and reference the stakes.

• Subgrade -- One line of blue tops at centerline or at a location directed by the City for each two (2) lanes of the roadway at fifty-foot (50’) intervals, and three (3) lines on super -elevated sections for each two (2) lanes. The Contractor shall reference subgrade stakes for the subbase and base layers.

• Finished Base -- One (1) line of blue tops at centerline or at a location directed by the City for each two (2) lanes of roadway at fifty-foot (50’) intervals, and three (3) lines for each (2) lanes on super-elevated and widened sections.

• All necessary line, location, and elevation stakes for curb and gutter, inlets, pipes, drainage structures, signals, box culverts, and other miscellaneous facilities.

5.12A.2 Sewer, Water, and Drainage Facilities
• For all pipelines to be laid on grade: the City will establish an offset line at fifty - foot (50’) intervals, furnish cut sheets and necessary land surveys, and establish bench marks, base lines, and reference points for locating principal structures.

• For drainage channels: the City will furnish slope stakes at fifty -foot (50’) intervals.

From this information, Contractor shall develop and make all additional detail surveys and measurements necessary for the construction of the Work.

SECTION 5.12B. Survey Monuments.

The City shall show on the construction Plans, to the best of its knowledge, the location and character of survey monuments located within the construction area. It is Contractor’s responsibility to arrange and pay for a diligent and thorough search for survey monuments. This shall be performed by or under the direction of a California Licensed Land Surveyor or a California Registered Civil Engineer authorized to practice Land Surveying, prior to the beginning of construction or maintenance work that could disturb or destroy a survey monument. Any monuments found shall be referenced and reset by or under the direction of a California Licensed Land Surveyor or a California Registered Civil Engineer authorized to practice Land Surveying in accordance with Business and Professions Code Section 8771. On thin surface treatments, such as chip seals, the monuments can be covered in advance of the maintenance treatment with a suitable material and then removed to expose the monument.

When survey monuments not shown on the Plans are discovered, Contractor shall bring them to the attention of the City prior to damaging them. Any City survey monuments damaged or destroyed by Contractor shall be reset by the City or Contractor at 405

49 General Conditions
2026

Contractor’s expense. Any other damaged or destroyed survey monuments shall by reset by Contractor at its sole expense in accordance with the Land Surveyors Act (Business & Professions Code 8700 et seq.).

When the Special Provisions require that Contractor provide all surveys, Contractor shall be responsible for referencing, resetting, and filing of corner records for all survey monuments disturbed or destroyed by construction activities in accordance with Business and Professions Code Section 8771.

All survey monuments and references shall be set or reset by or under the direction of a California Licensed Land Surveyor or a California Registered Civil Engineer authorized to practice Land Surveying.

SECTION 5.12C. Documentation.

Contractor shall furnish the City with one (1) copy of all land surveyor notes, calculations, sketches and drawings within 48 hours after completion of each survey task.

Contractor shall prepare, maintain and submit Record D rawings as specified in Article 11 of these General Conditions. Contractor’s land surveyor is to affix its signature and registration number to applicable record drawings certifying the accuracy of lines and grades shown.

Contractor shall submit survey Record Drawings before final completion.

SECTION 5.13. RESPONSIBILITY FOR ACCURACY.

Contractor shall obtain all necessary measurements for and from the Work, and shall check dimensions, elevations, and grades for all layout and construction work and shall supervise such work; the accuracy for all of which Contractor shall be responsible.

Contractor is responsible for adjusting, correcting, and coordinating the work of all Subcontractors so that no discrepancies result.

SECTION 5.14. DUTIES AND POWERS OF INSPECTORS.

Inspectors are the authorized representatives of the City. Their duty is to inspect materials and workmanship of those portions of the Work to which they are assigned, either individually or collectively, under instructions of the City, and to report all deviations from the Contract.

The Project Inspector shall have the authority to order the work designated for inspection stopped if a determination is made that work is proceeding in violation of the Contract Documents or any orders issued by the City, its representatives, or the Architect or Consulting Engineer. The failure of the Project Inspector to order the work stopped does not excuse Contractor from complying with the Contract Documents for that work.

Upon issuing a stop work notice, the Project Inspector shall notify the Project Manager, Engineer, Architect or Consulting Engineer, as the case may be for the Project, who then shall inspect the work in question and determine whether it does or does not comply with the Contract Documents. The decision of the Project Manager, Engineer, Architect or 406

50 General Conditions
2026

Consulting Engineer shall be final, subject to the disputes procedures in Article 9, “Changes and Claims”, of these General Conditions . Contractor shall thereafter comply with the instructions of the Project Manager, Engineer, Architect or Consulting Engineer regarding corrections needed to cure the defect. The suspended work shall be resumed only when the Project Manager, Engineer, Architect or Consulting Engineer’s instructions are fulfilled. Contractor shall not be entitled to an extension of time in the event of such suspension of work, provided the stop work notice is determined to be supported by the facts.

City work site inspections will only be conducted Monday through Thursday from 7AM to 3:30PM, excluding Legal Holidays. Any inspections outside of these hours shall be requested in writing at least three (3) days prior, must be approved by the Project Manager, and all costs associated with the inspections shall be paid by Contractor.

SECTION 5.15. INSPECTION.

The inspection of the Work does not relieve Contractor of the obligation to fulfill all Contract requirements. The purpose of inspection is not to assure Contractor that all of the Work is meeting all of the Contract requirements.

All work and materials furnished pursuant to the Contract shall be subject to inspection and approval by the City
. Contractor shall provide the City and Inspectors with access to the Work during construction and shall furnish every reasonable facility and assistance for ascertaining that the materials, equipment and the workmanship are in accordance with the requirements and intent of the Contract. Any work, materials, or equipment not meeting the requirements and intent of the Contract will be rejected, and unsuitable work, equipment or materials shall be made good, notwithstanding the fact that such work, materials or equipment may have been previously inspected or approved and /or payment may have been made. Contractor shall be solely responsible for any costs associated with the removal of any defective work, equipment or materials discovered during the inspection and the complete cost of reconstruction.

Unless authorized in writing by the City
, any work done in the absence of an Inspector,
whether completed or in progress, shall be subject to inspection. Contractor shall furnish all tools, labor, materials, access facilities, and other facilities necessary to allow such inspection, even to the extent of uncovering or taking down completed portions of the Work. Contractor shall pay all costs incurred, whether or not any defective work is discovered. Contractor shall also be solely responsible for any costs associated with the removal of any defective work discovered during the inspection and the complete cost of reconstruction.

Reexamination of any part of the Work may be ordered by the City , and such part of the Work shall be uncovered by Contractor . Contractor shall pay the entire cost of such uncovering, reexamination, and replacement if the reexamined work does not conform to the Contract.

Contractor shall notify the City of the time and place of any factory tests and submit test procedures for approval thirty (30) Calendar Days in advance for any tests that are required by the Contract. Contractor shall report the time and place of preparation, 407

51 General Conditions
2026

manufacture or construction of any material for the Work, or any part of the Work, that the City wishes to inspect. Contractor shall give five (5) Working Days ’ notice in advance of the beginning of work on any such material or of the beginning of any such test to allow the City to make arrangements for inspecting and testing or witnessing.

SECTION 5.16. QUALITY OF MATERIALS AND WORKMANSHIP.

Unless otherwise allowed or required by the Special Provisions, all equipment and materials shall be new and of a quality at least equal to that specified. All workmanship shall also be of the highest quali ty. When Contractor is required to furnish equipment, materials or manufactured articles or do work for which no detailed specifications are set forth, the equipment, materials or manufactured articles shall be of the best grade in quality and workmanship obtainable in the market. If not ordinarily carried in stock, the articles shall conform to the usual standards for first-class materials or articles of the kind required. The work performed shall secure the best standard of construction and equipment of the Work as a whole or in part.

Materials shall be furnished in sufficient quantities and at such times to ensure uninterrupted progress of the Work. All required spare parts shall be delivered in new condition, not in a used or unknown condition, and with any certificates required.

Materials, supplies, and equipment shall be stored properly and protected as required.

Contractor shall be entirely responsible for damage or loss by weather or other causes.

SECTION 5.17. SUBSTITUTIONS.

Certain materials, articles, or equipment may be designated in the Contract by brand or trade name or manufacturer together with catalog designation or other identifying information. Substitute material, article, or equipment which is of equal quality and of required characteristics for the intended purpose may be proposed for use, provided Contractor complies with the requirements of the following paragraphs.

SECTION 5.17A. Written Request.

Unless otherwise specified in the Contract Documents, Contractor shall submit any request for substitution in writing no later than thirty (30) Calendar Days after the award of the Contract.

SECTION 5.17B. Documentation.

If requested by the City , a proposal for substitution must be accompanied by complete information and descriptive data, including cost of operation, cost of maintenance, and physical requirements necessary to determine the equality of offered materials, articles, or equipment.

Contractor shall also submit such shop drawings, descriptive data, and samples as requested. The burden of proof of comparative quality, suitability, and performance of the offered proposal shall be upon Contractor. The determination of equal quality, suitability, and performance shall be at the sole discretion of the City. The City will examine such submittals with reasonable promptness. If the City rejects the request for such substitution, then one of the particular products designated by brand name in the Contract 408

52 General Conditions
2026

shall be furnished. Acceptance of substitution by the City shall not relieve Contractor from responsibility for deviations from the Plans and Specifications or from responsibility for errors in submittals. Failure by Contractor to identify deviations in the request material from the Plans and Specifications shall void the submittal and any action taken thereon by the City.

Changes required for proper installation and fit of substitute materials, articles or equipment, or because of deviations from the Contract shall not be made without the written consent of the City and shall be made by Contractor without additional cost to the City. Contractor shall pay the costs of design, drafting, architectural or engineering services and alterations of the construction required to accommodate any Contractor substitution or construction error to maintain the original function and design.

SECTION 5.18. PREPARATION FOR TESTING.

Contractor shall maintain proper facilities and provide safe access for inspection by the City to all parts of the Work and to the shops wherein parts of the Work are in preparation.

Where the Contract requires work to be tested or approved, such work shall not be tested or covered up without at least a five (5) Working Day notice to the City of its readiness for inspection, unless the written approval of the City for such testing or covering is first obtained.

SECTION 5.19. MATERIALS SAMPLING AND TESTING.

Materials to be used in the Work will be subject to sampling and tests by the City .

Contractor shall furnish the City with a list of Contractor ’s sources of materials and the locations at which such materials will be available for inspection. The list shall be furnished to the City in time to permit the inspection and testing of materials in advance of their use.

Testing shall be done to such standards as set forth in the Plans, Specifications, or Special Provisions. References made in these documents to standard methods of testing materials shall make such standards a part of the Specifications.

Whenever a reference is made in the Specifications to a specification or test designation of any recognized State or national organization or State of California Agency, and the number or other identification representing the year of adoption or the latest revision is omitted, it shall mean the specification or test designation in effect on the date of the original Notice to Contractors for the Work.

When requested by the City
, samples or test specimens of the proposed materials shall be prepared at the expense of Contractor and furnished by Contractor in such quantities and sizes required for proper examination and tests, and with complete information describing type, kind, or size of material, and its source. All samples shall be submitted in time to permit the making of proper tests, analyses, or examinations before incorporating the materials into the Work. No material shall be used in the Work unless or until it has been approved by the City. All material tests shall be made by the City in accordance with recognized standard practice. Contractor shall pay the cost of the first retest and any 409

53 General Conditions
2026

subsequent retest of any area or material. The City will secure and test samples whenever necessary.

SECTION 5.20. APPROVAL OF MATERIALS OR EQUIPMENT.

SECTION 5.20A. Sources of Supply.

The City’s approval at the source of supply may be required prior to procurement. Such approval shall not prevent subsequent disapproval or rejection of materials or equipment by the City if the quality is less than required by the Contract.

SECTION 5.20B. Plant Inspection.

The City assumes no obligation to inspect materials or equipment at the source of supply.

Contractor is responsible for incorporating satisfactory materials and equipment into the Work, notwithstanding any prior inspections or tests.

The City will inspect materials or equipment at the source if Contractor submits a written request and if the City deems the inspection necessary. Contractor and the supplier will cooperate with and assist the t he City while performing the inspection. The City shall have access to all production areas of the material or equipment source or place of manufacturing.

SECTION 5.21. PROVISIONS FOR EMERGENCIES.

The City may provide necessary labor, material and equipment to correct any emergency resulting from Contractor’s operation including noncompliance with the Contract, public convenience, safety, traffic control, and protection of Work, persons, environment, and property. The nature of the emergency may prevent the City from notifying Contractor prior to taking action. The costs of such labor, material, and equipment shall be borne by Contractor and will be deducted from progress payments.

The performance of such emergency work under the direction of the City shall not relieve Contractor from any damages resulting from the emergency, nor relieve Contractor of its obligations to be solely responsible for safety, including, without limitation, as required by Section 6.17, “Safety Requirements” and all subsections thereunder of these General Conditions.

SECTION 5.22. RIGHT TO RETAIN IMPERFECT WORK.

If any portion of the work done or materials or equipment furnished under the Contract shall prove defective or not in accordance with the Contract, and if the defect in the work, materials or equipment is not of sufficient magnitude or importance to make the work, materials or equipment dangerous or undesirable, or if the removal of such work, materials or equipment is impracticable or will create conditions which are dangerous or undesirable, the City shall have the right and authority to retain the work, materials or equipment instead of requiring it to be removed and reconstructed or replaced. Progress payment deductions will be made as described in Section 8.09, “Deductions for Imperfect Work”, of these General Conditions.
410

54 General Conditions
2026

SECTION 5.23. REMOVAL OF REJECTED MATERIALS OR WORK.

Contractor shall remove all rejected or condemned materials, equipment or structures brought to or incorporated in the Work within two (2) Working Days of the City’s written directive. No such rejected or condemned materials or equipment shall again be offered for use in the Work. Contractor shall, at Contractor’s expense, bring into Contract compliance all rejected material, equipment or work in a manner acceptable to the City.

The City may bring into Contract compliance the rejected material or equipment if Contractor fails to comply with this Section. All costs shall be borne by Contractor and will be deducted from any unpaid payment otherwise due to Contractor.

SECTION 5.24. TEMPORARY SUSPENSION OR DELAY OF WORK.

The City has the authority to suspend or delay the Work, wholly or in part, for any period the City deems necessary. Contractor shall immediately comply with t he City’s wr itten directive to suspend or delay the Work. The suspended or delayed work shall be resumed only when conditions are favorable or methods are corrected, as ordered or approved in writing by the City . Public safety and convenience must be maintained throughout the suspension or delay.

Delays due to suspension of work shall be classified as Inexcusable or Excusable Delays in accordance with Section 7.12, “Delays”, of these General Conditions. Such suspension shall not relieve Contractor of Contractor’s responsibilities as described in the Contract.

SECTION 5.25. TERMINATION.

SECTION 5.25A. Reasons for Termination.

The City reserves the right to terminate the Contract, Contractor’s right to proceed, and/or Contractor’s control over the Work for any of the reasons listed below.

SECTION 5.25A.1. Termination for Convenience.

The City may at any time and for any reason terminate the Contract or Contractor ’s performance of the Work, in whole or in part.

If the Contract, Contractor’s right to proceed, and/or Contractor’s control over the Work is terminated for cause and if it is later determined that the termination for cause was wrongful, such termination for cause automatically shall be converted to and treated as a termination for convenience. In such event, Contractor shall be entitled to receive only the amount payable under Section 5.2 5D of these General Conditions , and Contractor specifically waives any claim for any other amounts or damages, including any claim for consequential damages or lost profits.

SECTION 5.25A.2. Termination for Cause.

The City may terminate the Contract, Contractor’s right to proceed, and/ or Contractor’s control over the Work and so notify Contractor and Contractor’s sureties for the following causes:
411

55 General Conditions
2026

• Contractor is adjudged bankrupt or makes an assignment for the benefit of Contractor’s creditors, or if a receiver is appointed because of Contractor 's insolvency.
• The City has made a determination that Contractor will be unable to complete the Work on or before the completion date as adjusted by Change Order, or Contractor has not completed the Work on or before the completion date as adjusted by Change Order.
• Contractor abandons the Work.
• The Work or any portion is sublet or assigned without the City’s consent. • The rate of progress is not in accordance with the Contract. • Any portion of the Work is unnecessarily delayed.
• Contractor willingly violates any terms or conditions of the Contract. • Contractor does not supply sufficient materials or properly skilled and staffed labor. • Contractor fails to promptly pay its Subcontractors.
• Contractor disregards laws, ordinances, or City orders. • Contractor fails to correct defective work in response to defective work notices. • Contractor fails to comply with written directives.

SECTION 5.25B. Termination After Contract Time.

In addition to any other rights it may have, the City may terminate the Contract , Contractor’s right to proceed, and/or Contractor’s control over the work at any time after the Contract Completion Date, as adjusted by Change Order. Upon such termination, in addition to Contractor ’s other obligations under the Contract, Contractor shall not be entitled to receive any compensation after such termination until the Work is completed, and Contractor shall be liable to the City for liquidated damages for all periods of time from the Contract Completion Date, as adjusted by Change Order, until the date of Completion, as well as for all losses incurred by the City in completing the Work, as set forth in Section 5.25D of these General Conditions.

SECTION 5.25C. Notice of Termination; City Completion.

If grounds exist under Sections 5.25A.2 or 5 .25B above, then the City may issue to Contractor and its sureties a Notice of Intent to Terminate the Contract, Contractor’s right to proceed, and/or Contractor’s control over the Work for Cause. The Notice shall state the grounds for termination for cause that exist and demand that Contractor cure the grounds, or make satisfactory arrangement for cure of the grounds, within ten (10) days of the date of the Notice, or else the City will terminate the Contract, Contractor’s right to proceed, and/or Contractor’s control over the Work.

If Contractor fails to cure the grounds, or make satisfactory arrangement for cure of the grounds, stated in the Notice of Intent to Terminate within ten (10) days of the date of the Notice of Intent to Terminate, the City may give written Notice of Termination for Cause to Contractor and Contractor's sureties that the Contract, or a portion of the Contract, has 412

56 General Conditions
2026

been terminated and/or that Contractor's right to proceed and/or control over the Work, or a portion of the Work, has been terminated for the reasons stated in the Notice of Termination. The Notice shall also demand that Contractor’s surety take over and perform the Work through Completion. Contractor’s surety shall then have the right to take over and perform the Work through Completion. The City may take over the Work through Completion at Contractor ’s and surety’s expense if the surety does not commence performance within thirty (30) Calendar Days from the date of mailing the Notice of Termination or if immediate resumption of the Work is necessary to avoid significant additional cost.

If the City is forced to take over the Work, it may prosecute the same to completion by day labor, by contract or by any other method it may deem advisable, for the account and at the expense of Contractor and its sureties, and Contractor and its sureties shall be liable to the City for any and all excess costs, including management, supervision, and design support, occasioned thereby, whether incurred by City personnel, agents and/or consultants. In such event, the City may, without liability, take possession of and utilize in completing the Work, Contractor’s materials whether stored at the Site or elsewhere, that are necessary for completion. The City may also take possession of and use all or any part of Contractor ’s tools, equipment and appliances on the premises to complete the Work. The City assumes the responsibility for returning such equipment in as good condition as when it was taken over, reasonable wear and tear excepted. The items shall be returned to Contractor when the Work is complete or sooner, at the City’s discretion.

The City agrees to pay a reasonable amount for the use of such tools and equipment.

Contractor hereby assigns to the City all of its interest in orders and/or contracts , including subcontracts, existing at the time of termination. The assignment of said orders and/or contracts, including subcontracts, shall be effective upon notice of acceptance by the City in writing, and only as to those orders and/or contracts , including subcontracts, which the City designates in writing.

Whenever the Contract, Contractor’s right to proceed, and/or Contractor’s control over the Work is terminated for cause, Contractor and its sureties and shall be liable to the City for liquidated damages for all periods of time from the Contract Completion Date, as adjusted by Change Order and whether or not the termination date precedes or post -dates the adjusted Contract Completion Date, until the date of Completion, as well as for all losses incurred by the City in completing the Work, as set forth in Section 5.25D of these General Conditions.

Immediately upon receipt of a Notice of Termination for Cause or for Convenience, except as otherwise directed in writing by the City, Contractor shall:

1. Stop work under the Contract on the date and to the extent specified in the Notice of Termination.

2. Place no further orders or subcontracts for materials, services, or facilities except as necessary to complete the portion of the Work that is not terminated.

3. Terminate all orders and subcontracts to the extent that they relate to the performance of work terminated by the Notice of Termination. 413

57 General Conditions
2026

4. Assign to the City, in the manner, at the times, and to the extent directed by the City, all of the rights, titles, and interests of Contractor under the orders and subcontracts so terminated. The City shall have the right, at its discretion, to settle or pay any or all claims arising out of the termination of such orders and subcontracts.

5. Settle all outstanding liabilities and all claims arising out of such termination of orders and subcontracts with the approval or ratification of the City. The City's approval or ratification shall be final.

6. Transfer title to the City , and deliver in the manner, at the times, and to the extent directed by the City , fabricated or unfabricated parts, work in process, completed work, supplies, other material produced as a part of, or acquired in connection with, the terminated work, and the completed or partially completed drawings, information, and other property that, if the Contract had been completed, would have been submitted to the City.

7. Sell, in the manner, at the times, to the extent, and at the price that the City directs or authorizes, any property of the types referred to in Item 6 of this Section (Section 5.25C ). Contractor is not required to extend credit to any purchaser, and may acquire any such property under the conditions prescribed and at a price approved by the City. The proceeds of any such transfer or disposition shall be used to reduce any payments made to the Contractor under the Contract or be credited to the cost of the work covered by the Contract or paid as the City directs.

8. Complete performance of the Work not terminated by the Notice of Termination.

9. Take necessary action, or as the City directs, to protect and preserve the property related to the Contract in which the City has an interest.

SECTION 5.25D. Payments to Contractor Upon Termination of Contract.

In the event of a termination for convenience, Contractor and the City may agree upon an amount paid to Contractor for the total or partial termination of the Contract or of Contractor’s control over the Work. The amount may include those items specified in Article 9, “Changes and Claims”, of these General Conditions . However, such agreed amount shall not exceed the Contract Sum, reduced by the amount of payments already made and the Contract price of work not terminated. The Contract shall be amended accordingly, and Contractor shall be paid the agreed amount.

If Contractor and the City fail to agree on the amount to pay Contractor because of the termination for convenience under this Section, the City shall determine the amount due Contractor.

In the event of a termination for cause, Contractor is not entitled to receive any portion of the amount to be paid under the Contract until it is fully completed. After completion, if the unpaid balance exceeds the sum of the amount expended by the City in finishing the work, plus all damages sustained or to be sustained by the City , including, without limitation, legal expenses, City forces, administration and management, direct and 414

58 General Conditions
2026

indirect, plus liquidated damages, plus any unpaid claims on account of labor, materials, tools, equipment, or supplies contracted for by Contractor for the Work, provided that sworn statements of said claims shall have been filed as required by Article 9, “Changes and Claims”, of these General Conditions, the excess not otherwise required by the Contract Documents to be retained shall be paid to Contractor. If the sum so expended to complete, plus the City’s damages as described herein, plus liquidated damages, plus unpaid claims as described herein exceeds the unpaid balance of the Contract Sum , Contractor and Contractor's surety are liable to the City for the amount of such excess.

SECTION 5.25E. Completion Not a Waiver of City Rights.

No act by the City before the Work is finally accepted shall operate as a waiver or stop the City from acting upon any subsequent event, occurrence or failure by Contractor to fulfill the terms and conditions of the Contract. The rights of the City pursuant to this Section 5.25 and all of its subsections are in addition to all other rights of the City pursuant to the Contract, and at law or in equity.

SECTION 5.25F. Survival of Obligations.

No termination of this Contract or of Contractor’s right to proceed and/or control over the Work shall excuse or otherwise relieve Contractor of its responsibilities under the Contract with respect to any Work performed prior to the date of termination, including, without limitation, its obligation to perform the Work in a good and workmanlike manner, free of defects, and in accordance with the Contract, its warranty obligations with respect to the Work, and its obligation to make all payments due. All of Contractor ’s responsibilities under the Contract with respect to the Work performed prior to the date of termination shall survive any termination.

SECTION 5.26. TERMINATION OF UNSATISFACTORY SUBCONTRACTS.

When any portion of the Work subcontracted by Contractor is not prosecuted in a satisfactory manner, Contractor shall immediately terminate the subcontract upon written notice from the City. The Subcontractor shall not again be employed for any portion of the work on which the Subcontractor's performance was unsatisfactory. Substitution of a new subcontractor shall be accomplished in accordance with California Public Contract Code sections 4100 et seq.

415

59 General Conditions
2026

ARTICLE 6. LEGAL RELATIONS AND RESPONSIBILITIES
SECTION 6.01. COMPLIANCE WITH LAWS AND REGULATIONS.

Contractor shall be familiar and comply with all Federal, State, and local laws, ordinances, codes and regulations which in any manner affect the Work, those engaged or employed in the Work or the material or equipment used in or upon the Work, or in any way affect the conduct of the Work. No pleas of misunderstanding of such laws, ordinances, codes, or regulations or of ignorance of the same on the part of Contractor shall modify the provisions of the Contract. Contractor and Contractor’s surety shall indemnify, defend and save harmless the City and the City’s officers, officials, agents, employees, volunteers, members, affiliates and their duly authorized representatives against any claim for liability arising from, or based upon, the violation of any such law, ordinance, regulation, decree, or order, whether by Contractor or by Contractor’s employees.

The attention of Contractor is directed to certain laws that affect the Contract. The listing of these laws in this Article is not to be construed as a listing of all applicable laws.

Contractor is solely responsible for familiarity and compliance with all applicable laws.

SECTION 6.02. WAGES, HOURS AND EQUAL OPPORTUNITY
SECTION 6.02A. Hours of Labor.

Eight (8) hours of labor shall constitute a legal day's work and Contractor or any Subcontractor under Contractor, in the execution of the Contract, shall not require more than eight (8) hours of labor in any Calendar Day, and forty (40) hours of labor in any calendar week, from any person employed by Contractor in the performance of the Work under the Contract, except as permitted under the provisions of Labor Code Sections 1810 to 1815. Contractor shall forfeit, as penalty to the City, the amount specified in Labor Code section 1813 for each worker employed by Contractor or any Subcontractor under Contractor in the execution of the Contract for each Calendar Day during which any worker is required or permitted to labor more than eight (8) hours and for each calendar week during which any worker is required or permitted to labor more than forty (40) hours, in violation of the provisions of Labor Code Sections 1810 to 1815.

Overtime shall be paid at the rate of not less than one and one half (1 1/2) times the basic rate of pay, or at such higher rate as may be required by the DIR, applicable statutes or collective bargaining agreements.

The City reserves the right to approve or disapprove the days scheduled for work, and the hours during which work is in progress. Overtime and shift work may be established by Contractor with reasonable notice and the written permission of the City. Unless a different schedule for work is specified or approved by the Project Manager, no work other than overtime and shift work shall be done between the hours of 7:00 p.m. and 7:00 a.m., except such work as is necessary for the proper care and protection of the work already performed or except in case of an emergency, or as approved by the City. 416

60 General Conditions
2026

SECTION 6.02B. Prevailing Wages.

Pursuant to Labor Code Section 1772, workers employed by contractors or subcontractors in the execution of any contract for public work are deemed to be employed upon public work as defined in Labor Code Sections 1720- 1725. Therefore, Contractor and all Subcontractors on the Project shall pay not less than the prevailing rate of per diem wages, including, but not limited to, overtime, Saturday, Sunday, and holiday work, travel and subsistence, as determined by the Director of the DIR pursuant to Labor Code Section 1773. Copies of such prevailing rate of per diem wages are available upon request at the office of the City Clerk at Rocklin, 3970 Rocklin Road, Rocklin, CA 95677 or on the internet at at http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm . Those
prevailing wage rates hereby are incorporated in this agreement and made a part hereof.

Contractor shall obtain and post copies of these prevailing wage rates in a prominent place at the job site, in accordance with the regulations of the DIR.

The responsibility to check prevailing wage rates is Contractor’s. Pursuant to Labor Code Section 1773.4 Contractor may file with the Director of DIR or the Chief of the Division of Labor Standards Enforcement (“DLSE”) a petition to review a determination of any rate or rates made by the Director of DIR. Contractor may also petition the Director of DIR to make a determination for a particular craft, classification or type of work not covered by a general determination. Pending the review or determination, the wages may be assumed to be those in the applicable collective bargaining agreement, but no adjustment in the Bid or Contract Sum shall be made if such assumption is incorrect.

The wage rates determined by the Director of the California DIR refer to expiration dates.

Prevailing wage determinations with a single asterisk (*) after the expiration date that are in effect on the date of Notice to Contractors remain in effect for the duration of the Project. Prevailing wage determinations with double asterisks (**) after the expiration date indicate that the basic hourly wage rate, overtime and holiday wage rates, and employer payments to be paid for work performed after this date have been predetermined. If work extends past this date, the new rate shall be paid and should be incorporated in contracts entered into for the Project. Contractor should contact the DIR as indicated in the prevailing wage determinations to obtain predetermined wage changes. All determinations that do not have double asterisks (**) after the expiration date remain in effect for the duration of the Project.

Contractor agrees that in the event of underpayment of wages to any employee on the Project, whether by Contractor or any Subcontractor, the City may retain from payments due to Contractor, an amount sufficient to pay such worker the difference between the wages required to be paid by the DIR and the wages actually paid such worker for the total number of hours worked. The City may disburse such retention to such employees.

For each worker paid less than the applicable prevailing wages for any work done under this Contract by Contractor or any Subcontractor, Contractor shall forfeit to the City as a penalty the sum determined by the Labor Commissioner in accordance with the considerations set forth in Labor Code Section 1775, over and above any retention or withholds otherwise authorized by the Contract. If a worker employed by a Subcontractor is paid less than the prevailing wages by the Subcontractor, Contractor is not subject to 417

61 General Conditions
2026

this penalty assessment if Contractor can demonstrate that it did not have knowledge of that failure of the Subcontractor to pay the prevailing wages and that it strictly complied with the requirements of Labor Code Section 1775(b). In addition to applicable penalties, Contractor or Subcontractor shall pay each worker the difference between the prevailing wage and the amount paid for every hour the worker was paid less than the prevailing wage.

In accordance with Labor Code Section 1775, Contractor shall monitor the payment of the specified general prevailing rate of per diem wages by S ubcontractors to employees by periodic review of the certified payrolls of the subcontractors.

SECTION 6.02C. Payroll Records.

Contractor shall comply with Labor Code Section 1776. Regulations implementing Section 1776 are located in Section 16000 and Sections 16401 through 16403 of Title 8, California Code of Regulations. Contractor shall be responsible for compliance by all Subcontractors on the Project.

Contractor and Subcontractors shall keep accurate payroll records, showing the name, address, Social Security number, work classification, dates of payroll period, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by Contractor and by each Subcontractor in connection with the Work. Such records shall be certified under penalty of perjury that the information contained in the payroll record is true and correct and that the employer has complied with the requirements of Labor Code sections 1771, 1811, and 1815 for any work performed by its employees, and shall be available for inspection at all reasonable hours at the principal offices of Contractor and Subcontractors in a manner set forth in Labor Code Sections 1776 and 1812. The Contractor shall be held responsible for all Subcontractors' compliance with this requirement.

Upon a written request, Contractor and/or its Subcontractors shall file a certified copy of the payroll records with the requesting entity within 10 days after receipt of the written request. Failure to submit timely, complete certified payrolls when requested shall subject Contractor and/or the Subcontractor(s) to the penalties specified in subdivision (h) of the Labor Code section 1776, which penalties may be deducted from progress payments to Contractor.

Contractor shall not carry on its payrolls any person not actually employed by Contractor, nor shall it carry on its payrolls employees of a Subcontractor. Contractor shall show on its payrolls all persons actually employed by Contractor on the Project, in any capacity .

Contractor shall supervise all Subcontractors to ensure that all Subcontractors comply with this Section.

In accordance with Government Code Section 8546.7, or any amendments thereto, all books, records, and files of Contractor , or any Subcontractor connected with the performance of this Contract, shall be subject to examination and audit by the California State Auditor for a period of three (3) years after final payment. Contractor shall preserve and cause to be preserved such books, records and files for the audit period. 418

62 General Conditions
2026

SECTION 6.02D. Additional Requirements for Labor Compliance.

Contractor shall comply with the following additional requirements and shall cause all Subcontractors on the Project, whether under contract with Contractor or under contract with any Subcontractor, to comply.

The records kept by the Contactor and all subcontractors of the hours and wages of all employees employed on Project also shall be open at all times for inspection by the DIR and DLSE, in accordance with Sections 1776 and 1812 of the Labor Code. Such records shall be furnished electronically to the Labor Commissioner of the DIR monthly, unless more frequent submission is required herein, and shall be furnished within 10 days of any separate request by the DIR or DLSE. Payroll records shall be furnished in a format prescribed by DIR and uploaded into the electronic certified payroll reporting (eCPR) system.

On a random basis and at such other times as it deems appropriate, the DIR also may confirm the accuracy of payroll reports, including by corroboration of information in payroll reports through independent sources, including without limitation worker interviews, examination of any time and pay records found within the definition of “Payroll Records” in section 16000 of Title 8 of the California Code of Regulations, direct verification of “Employer Payments” (as defined at section 16000 of Title 8 of the California Code of Regulations) through third- party recipients of those payments, or any other legal and reasonable method of corroboration. As part of its confirmation process, the DIR may require Contractor and any of its S ubcontractors to furnish for inspection itemized statements prepared in accordance with Labor Code Section 226. The DIR may conduct random confirmation based on a recognized statistical sampling of the records submitted.

The DIR may conduct in-person inspection(s) at the site or sites at which the Work of the Project is being performed (“On-Site Visits”). On-Site Visits may include visual inspection of required job site notices, including but not limited to (1) the determination(s) of the Director of DIR of the prevailing wage rate of per diem wages required to be posted at each job site in compliance with Labor Code Section 1773.2; (2) the Notice of pay days and time and place of payment required by Labor Code Section 207; and (3) any other notices prescribed by law. On- Site Visits may also include inspections of records, inspections of the work site and observation of work activities, interviews of workers and others involved with the Project, and any other activities deemed necessary by the DIR to ensure compliance with prevailing wage requirements. In accordance with Labor Code Section 90, the Labor Commissioner and his or her deputies and agents shall have free access to any construction site or other place of labor and may obtain any information or statistics pertaining to the lawful duties of the Labor Commissioner, including but not limited to evidence of compliance with Labor Code Section 226 (itemized wage statements for employees) and any other laws enforced by the Labor Commissioner.

In accordance with Section 16463 of Title 8 of the California Code of Regulations (“8 CCR Section 16463”), the City may, on its own or if required by the Labor Commissioner, withhold funds due to Contractor when payroll records are delinquent or inadequate. The amount withheld shall be those payments due or estimated to be due to Contractor or Subcontractor whose payroll records are delinquent or inadequate, plus any additional amount that the Labor Commissioner has reasonable cause to believe may be needed to 419

63 General Conditions
2026

cover a back wage and penalty assessment against Contractor or Subcontractor whose payroll records are delinquent or inadequate. Contractor shall cease all payments to a Subcontractor whose payroll records are delinquent or inadequate until the Labor Commissioner provides notice that the Subcontractor has cured the delinquency or deficiency. When payments are withheld under 8 CCR Section 16463, the Labor Commissioner will provide Contractor and Subcontractor, if applicable, with immediate written notice that includes all of the following: (1) a statement that payments are being withheld due to delinquent or inadequate payroll records, and that identifies what records are missing or states why records that have been submitted are deemed inadequate; (2) specifies what amounts the City has been directed to withhold; and (3) informs Contractor or Subcontractor of the right to request an expedited hearing to review the withholding of payments under Labor Code Section 1742, limited to the issue of whether the records are delinquent or inadequate or the Labor Commissioner has exceeded his or her authority under 8 CCR Section 16463. Where the violation is by a Subcontractor, Contractor shall be notified of the nature of the violation and reference shall be made to Contractor’s rights to withhold or recover payments from the Subcontractor under Labor Code Section 1729.

The withholdings under 8 CCR Section 16463 do not preclude assessment of penalties under Labor Code Section 1776(g) for failure to timely comply with a written request for certified payroll records, as set forth above.

SECTION 6.02E. Nondiscrimination.

Contractor shall comply with Section 1735 of the Labor Code, which provides as follows:
“A contractor shall not discriminate in the employment of persons upon public works on any basis listed in subdivision (a) of Section 12940 of the Government Code, as those bases are defined in Sections 12926 and 12926.1 of the Government Code, except as otherwise provided in Section 12940 of the Government Code. Every contractor for public works who violates this section is subject to all the penalties imposed for a violation of this chapter.”
SECTION 6.02F. Apprentices.

Attention is directed to the provisions of Sections 1777.5, 1777.6 and 1777.7 of the Labor Code concerning the employment of apprentices by Contractor or any Subcontractor.

Contractor and all Subcontractors shall comply with the requirements of Section 1777.5 and Section 1777.6 of the Labor Code in the employment of apprentices. Violation of these requirements shall subject Contractor and/or Subcontractor to the penalties set forth in Section 1777.7 of the Labor Code and/or otherwise provided by law or Contract.

Information relative to apprentice standards, wage schedules, and other requirements may be obtained from the Director of DIR, ex officio the Administrator of Apprenticeship, San Francisco, California, or from the Division of Apprenticeship Standards and its branch offices and/or on the OPRL website at www.dir.ca.gov/OPRL/PWD . Apprentices employed on the Project must at all times work with or be under the direct supervision of a journeyman or journeymen.
420

64 General Conditions
2026

SECTION 6.02G. Workers’ Compensation.

Pursuant to Labor Code Section 1860, in accordance with the provisions of Section 3700 of the Labor Code, Contractor is required to secure the payment of compensation to its employees.

SECTION 6.02H. Fair Labor Standards.

Contractor shall comply with the Fair Labor Standards Act of 1938 as amended (29 U.S.C. 3201 et seq.) as applicable.

SECTION 6.02I. Reporting Requirements and Sanctions.

Contractor’s failure to provide specific information, records, reports, certifications, or any other documents required for compliance with the Contract will be considered noncompliance. At a minimum, documents required include:

1. List of Subcontractors
A list is required from Contractor of all Subcontractors, including all lower tier Subcontractors, who are or will be performing work on the Project, using the format in the Bid Documents. This list is due within ten (10) Calendar Days after the date of the preconstruction conference or within ten (10) Calendar Days after the date of award of the subcontract. The later of the two dates will apply.

2. Certified Payroll Reports
Certified Payroll Reports are required from the Contractor and each Subcontractor, regardless of the subcontract amount or the type of procurement, for every payroll period in which work is performed. These reports are due with progress payment requests and no later than ten (1) Working Days of the ending date of the payroll period.

3. Fringe Benefit Statement
A Fringe Benefit Statement is required from Contractor and each Subcontractor if fringe benefits are paid to an approved plan, fund, or program. The statement is due with the first certified payroll report and any time the fringe benefit amounts change. The statement is not required if the fringe benefits are paid in cash to the employees.

4. Other Documentation
When required by the Special Provisions, other reporting documentation may be required depending on the source of funding for the project.

If Contractor fails to comply with the provisions of this Section, Contractor will be advised of the specific deficiencies and requested to make immediate corrections. Contractor will also be advised that monetary deductions will be made for failure to effect corrections or delinquencies.
421

65 General Conditions
2026

If Contractor fails to correct a deficiency in the reporting requirements within fifteen (15) Calendar Days after notification, a deduction may be made. In such cases, the deduction will be ten percent (10%) of the estimated value of the work done during the month, except that the deduction will not exceed ten thousand dollars ($10,000), nor be less than one thousand dollars ($1,000), and will be deducted from the next progress payment.

Deductions for non-compliance will be in addition to all other deductions provided for in the Contract and will apply irrespective of the number of instances of noncompliance.

Deductions will be made separately and cumulatively for each estimate period in which a new deficiency appears. When all deficiencies for a period have been corrected, the deduction covering that period will be released on the next progress payment. Otherwise, the deduction will be retained.

SECTION 6.03. SUBCONTRACTING; SUBSTITUTION OF SUBCONTRACTORS.

Contractor shall comply with all requirements of the Subletting and Subcontracting Fair Practices Act, Chapter 4 of Part 1 of Division 2 of the Public Contract Code, commencing with Section 4100, forbidding bid shopping and bid peddling, requiring accurate listing of all Subcontractors, and requiring Subcontractors to be licensed. Contractor shall not, without the written consent of the City: (a) substitute any party as Subcontractor in place of the Subcontractor designated in the original bid; (b) permit any such subcontract to be assigned or transferred; or (c) allow the subcontracted work to be performed by anyone other than the original Subcontractor listed on the bid. Consent for substitution or subletting shall only be given pursuant to Section 4107 of the Public Contract Code.

Should Contractor violate any of the provisions of this Section, the violation shall be deemed a breach of this Contract and the City shall have all remedies provided by California law, including but not limited to those provided in Public Contract Code Section 4110, allowing termination of the Contract or a penalty assessment of ten percent (10%) of the subcontract amount.

SECTION 6.04. USE OF PESTICIDES.

Contractor shall comply with all rules and regulations that govern the use of pesticides required in the performance of the Work, including any certifications that may be required for purchase, use, storage or application.

Pesticides include, but are not limited to, herbicides, insecticides, fungicides, rodenticides, germicides, nematocides, bactericides, inhibitors, fumigants, defoliants, desiccants, soil sterilants, and repellants.

Any substance or mixture of substances intended for preventing, repelling, mitigating, or destroying weeds, insects, diseases, rodents, or nematodes and any substance or mixture of substances intended for use as a plant regulator, defoliant or desiccant shall be considered a pesticide.

SECTION 6.05. OCCUPATIONAL SAFETY AND HEALTH.

Contractor must comply with all applicable provisions of the California Occupational Safety and Health Act (Labor Code Sections 6300 et seq.). The foregoing includes, but is 422

66 General Conditions
2026

not limited to, all applicable Title 8 Safety Orders issued by the State of California Occupational Safety and Health Administration (Cal/OSHA). Failure of the City to suspend the work or notify Contractor of the inadequacy of the safety precautions or non- compliance with existing laws and regulations shall not relieve Contractor of this responsibility.

SECTION 6.06. INDEMNIFICATION.

SECTION 6.06A. Contractor's Performance.

To the fullest extent permitted by law, Contractor shall indemnify, defend with counsel acceptable to the City , and hold harmless the City , its officers, officials, employees, agents, and volunteers from and against any and all losses, claims, demands, damages, costs, expenses, attorney’s fees, or liability of every nature arising out of or in any way connected with the performance or attempted performance of the provisions of this Contract, caused in whole or in part by any negligent or willful act or omission of Contractor, its officers, employees, or agents, or anyone directly or indirectly acting on behalf of Contractor , regardless of whether caused in part by a party indemnified hereunder. Nothing contained in the foregoing indemnity provisions shall be construed to require Contractor to indemnify the indemnified party in contravention of Section 2782 of the Civil Code for the active or sole negligence or willful misconduct of that indemnified party.

To the fullest extent permitted by law, Contractor ’s duty to defend shall extend, without limitation, to any suit or action founded upon any losses, claims, demands, damages, costs, expenses, attorney’s fees, or liability of every nature arising out of or in any way connected with the performance or attempted performance of the provisions hereof, or in any way arising out of or connected with this Contract.

The defense and indemnity obligations expressly extend to and include any and all claims, demands, damages, costs, expenses, or liability occasioned as a result of damages to adjacent property caused by the conduct of the Work.

The defense and indemnity obligations expressly extend to and include any and all claims, demands, damages, costs, expenses, or liability occasioned as a result of the violation by Contractor , Contractor’s agents, employees, or independent contractors, Subcontractors or suppliers of any provisions of federal, State or local law, including applicable administrative regulations.

The defense and indemnity obligations also expressly extend to and include any claims, demands, damages, costs, expenses, or liability occasioned by injury to or death of any person, or any property damage to property owned by any person while on or about the site or as a result of the Work, whether such persons are on or about the site by right or not, whenever the Work is alleged to have been a contributing cause in any degree whatsoever.

In claims against any person or entity herein indemnified that are made by an employee of Contractor or an employee of any of Contractor ’s agents, independent contractors, Subcontractors or suppliers, a person indirectly employed by Contractor or by any of 423

67 General Conditions
2026

Contractor’s agents, independent contractors, Subcontractors or suppliers, or anyone for whose acts Contractor or any of Contractor ’s agents, independent contractors, Subcontractors or suppliers may be liable, the defense and/or indemnification obligation herein shall not be limited by any limitation on amount or type of damages, compensation, or benefits payable by or for Contractor or Contractor’s agents, independent contractors, Subcontractors or suppliers under workers’ compensation acts, disability acts, or other employee benefit acts.

The defense and indemnification obligations herein shall not be limited by any assertion or finding that the person or entity indemnified is liable by reason of a non-delegable duty.

The defense and indemnities set forth herein shall not be limited by the insurance requirements set forth in the Contract.

The defense and indemnification requirements herein set forth shall extend to claims occurring after this Contract is terminated as well as while it is in force.

SECTION 6.06B. Indemnification of Adjacent Property Owners.

In the event Contractor enters into any agreement with owners of any adjacent property to enter upon or adjacent to such property for the purpose of performing this Contract, Contractor shall fully indemnify, defend and save harmless such person, firm, or corporation, State or other governmental agency which owns or has any interest in the adjacent property. The form and content of the indemnification agreement shall be approved by the City prior to commencement of any work on or about such property.

Contractor also shall indemnify the City and other indemnities identified in Section 6.06A of these General Conditions as provided in the Contract. These provisions shall be in addition to any other requirements of owners of adjacent property.

SECTION 6.07. PROTECTION OF CITY AGAINST PATENT CLAIMS.

Contractor shall assume all costs arising from the use of patented materials, equipment, devices, and processes on or incorporated in the Work and shall indemnify and hold harmless the City and the City
’s officers, officials, agents, employees, volunteers,
members, affiliates and their duly authorized representatives from all actions for, or on account of, the use of any patented materials, equipment, devices, or processes in the construction of, or subsequent operation of, the Work. Before final payment, if requested by the City
, Contractor shall furnish acceptable proof of a proper release from all costs or claims arising from the use of patented materials, equipment, devices, or processes used on or incorporated in the Work.

SECTION 6.08. CONTRACTOR'S LEGAL ADDRESS; WRITTEN NOTICE.

Both the address given in the Bid and Contractor 's office in the vicinity of the Work are designated as places that samples, notices, letters, or other articles or communications to Contractor may be mailed or delivered. The delivery to either of these places shall be deemed sufficient service to Contractor. Written notice may be accomplished by personal delivery, United States mail, overnight mail, delivery receipt email, facsimile or any other form of commercially accepted communication. The written notice shall become effective 424

68 General Conditions
2026

upon delivery. Delivery is complete when the notice is hand delivered, when the facsimile transmission is complete, two business days after mailing by U.S. mail , or upon actual email delivery as evidenced by a delivery receipt.

The address named in the Bid may be changed at any time by written notice from Contractor to the City. Nothing herein shall be deemed to preclude or render inoperative the service of any drawing, sample, notice, letter or other article or communication to Contractor.

SECTION 6.09. CONTRACTOR NOT AN AGENT OF CITY.

Contractor shall be an independent contractor and not an employee, agent, or other representative of the City . Nothing in the Contract shall be construed to create any relationship of joint venture, partnership or any other association of any nature whatsoever between the City and Contractor other than that of the City and independent contractor.

The City shall have the right to direct Contractor as provided in the Contract. The aforementioned right of supervision shall not reduce or abrogate Contractor's liability of all damage or injury to persons, public property, or private property that may arise directly or indirectly from Contractor's execution of the Work.

SECTION 6.10. ASSIGNMENT OF CONTRACT.

The Contract or the performance of the Contract may be assigned by Contractor, but only upon written consent of the City and Contractor’s surety, unless the surety has waived its right of notice of assignment. No such assignment or subcontracting shall be permitted that would relieve Contractor or Contractor’s surety of their responsibilities under the Contract.

SECTION 6.11. ASSIGNMENT OF MONIES.

Contractor may assign monies due Contractor under the Contract, and such assignment will be recognized by the City, if given proper notice, to the extent permitted by law. Any assignment of monies shall be subject to all deductions provided for in the Contract. All money withheld may be used by the City for the completion of the Work if Contractor defaults.

SECTION 6.12. CONTRACTORS LICENSE.

Contractor shall comply, and requires all Subcontractors to comply, with Chapter 9 of Division 3 of the Business & Professions Code.

SECTION 6.13. RESPONSIBILITY OF CONTRACTOR.

Contractor shall be solely responsible for, and have control over, construction means, methods, techniques, sequences, procedures, and coordination of all portions of the Work under the Contract, unless otherwise provided in the Contract. 425

69 General Conditions
2026

The Work shall be under Contractor's responsible care and charge until completion and final acceptance, and Contractor shall bear the entire risk of injury, loss, or damage to any part by any cause. Contractor shall rebuild, repair, restore, and make good all injuries, losses or damage to any portion of the Work, equipment or the materials occasioned by any cause, and shall bear the entire expense.

In no case shall Contractor’s use of Subcontractors in any way alter the position of Contractor or Contractor’s sureties with relation to the Contract. When a Subcontractor is used, the responsibility for every portion of the Work shall remain with Contractor. No Subcontractor will be recognized as having a direct contractual relationship with the City.

All persons engaged in the Work under the Contract will be considered as employees of Contractor and their work shall be subject to all the provisions of the Contract. The City will deal only with Contractor who is responsible for the proper execution of the Work.

Contractor shall pay when due all valid claims of Subcontractors, suppliers, and workmen with respect to the Work.

The mention herein of any specific duty or responsibility imposed upon Contractor shall not be construed as a limitation or restriction of any other responsibility or duty imposed upon Contractor by the Contract, said reference being made herein merely for the purpose of explaining the specific duty or responsibility.

Contractor shall do all of the work and furnish all labor, materials, tools, equipment, and appliances, except as otherwise herein expressly stipulated, necessary or proper for performing and completing the Work herein required, including any change order work or disputed work directed by the City in conformity with the true meaning and intent of the Plans, Specifications, and all provisions of the Contract, within the time specified.

If Contractor discovers any discrepancies during the course of the Work between the Plans and conditions in the field, or any errors or omissions in the Plans and conditions in the field, or any errors or omissions in the Plans, the Specifications, or in the layout given by stakes, points, or instructions, it shall be Contractor's duty to inform the City immediately, and the City shall promptly verify the same. Any work done after such discovery until authorized by the City, will be done at Contractor's risk.

SECTION 6.14. PERMITS AND LICENSES.

Except as set forth in the Special Provisions, Contractor shall, at Contractor ’s sole expense, obtain all necessary permits and licenses for the construction of the Work, give all necessary notices, pay all fees required by law, and comply with all laws, ordinances, rules and regulations relating to the Work and to the preservation of the public health and safety. Contractor shall also procure all permits and licenses necessary for the normal conduct of Contractor’s business and construction operations.

Unless otherwise noted in the Special Provisions, building, plumbing, heating, electrical, and similar permits that the Contractor is required to obtain from the City Building Department for City-owned projects will be obtained by the Contractor at City expense.

The California Environmental Quality Act of 1970 (CEQA) may be applicable to permits, licenses, and other authorizations that Contractor shall obtain from local agencies in 426

70 General Conditions
2026

connection with performing the Work. Contractor shall comply with the provisions of CEQA in obtaining such permits, licenses, and other authorizations, which will be obtained in time to prevent delays to the Work. Contractor shall also comply with all mitigation measures identified in the Special and/or Technical Provisions.

Contractor shall also furnish the Engineer a copy of a valid, current City of Rocklin Business License obtained at Contractor expense prior to the commencement of the work.

SECTION 6.15. RIGHTS AND REMEDIES.

The duties and obligations of Contractor imposed by the Contract Documents and the rights and remedies of the City available there under shall be in addition to and not a limitation of any duties, obligations, rights and remedies otherwise imposed or available by law.

The failure of the City, or any of its agents, employees or consultants, including, without limitation, the Owner’s Representative, the Project Inspector or the Architect or Consulting Engineer, to insist in any one or more instances upon the strict performance of any one or more of the provisions of this Contract or to exercise any right herein contained or provided by law, shall not be construed as a waiver or relinquishment of the performance of such provision or right(s) or of the right to subsequently demand such strict performance or exercise such right(s) and the rights shall continue unchanged and remain in full force and effect.

Contractor agrees that it can be adequately compensated by money damages for any breach of this Contract which may be committed by the City and hereby agrees that no default, act or omission of the City, the Owner’s Representative, the Project Inspector or the Architect or Consulting Engineer, shall constitute a material breach of the Contract entitling Contractor to cancel or rescind the provisions of the Contract or to suspend or abandon performance of all or any part of the Work. Contractor hereby waives any and all rights and remedies to which it might otherwise be or become entitled, saving only its right to money damages.

SECTION 6.16. UNENFORCEABILITY OF ANY CLAUSE.

If any clause or provision of the Contract Documents is held to be unenforceable or invalid, then that provision of the Contract shall be stricken and the remaining portion shall remain in full force and effect.

SECTION 6.17. GENERAL SAFETY REQUIREMENTS.

SECTION 6.17A. Ensuring Safety; Compliance With Safety & Health Regulations.

Safety is a prime consideration in all City contracts. Contractor shall conform to all applicable occupational safety and health standards, rules, regulations, and orders established by the State of California or Federal Government and shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work, for maintaining all safety and health conditions on the site and for ensuring 427

71 General Conditions
2026

against and/or correcting any hazardous conditions on the s ite. Contractor shall at all times, until final acceptance and payment hereunder, maintain adequate protection against (1) injury to persons, including employees, inspectors, and all other persons who may enter the site, or (2) or damage to property, on or near the Project, or adjacent to the site. In no case shall the City or any of its agents, officials, officers, employees, independent contractors or representatives have either direct or indirect responsibility for the means, methods, techniques, sequences or procedures utilized by Contractor, or for safety precautions and programs in connection with the Work, or for maintaining any safety or health conditions on the site, or for ensuring against or correcting any hazardous conditions on the site. The City or any of its agents, employees or independent contractors may call to the attention of Contractor any safety, health or hazardous conditions at the site but, by doing so, does not assume any liability or responsibility for remediation or correction of the condition, which liability and responsibility lie solely with Contractor.

Contractor shall designate a responsible member of its organization at the site whose duty shall be the prevention of accidents and overall jobsite safety for contractors/subcontractors employees and visitors and who shall have the authority to make decisions regarding safety and health concerns on the project and to direct Contractor’s personnel to abate any hazard identified by the City .

Contractor shall, upon request, submit to the City a copy of its Injury Illness Prevention Program (IIPP) (including Site Safety Plan and Code of Safe Work Practices) and all updates and revisions to the IIPP for review. Contractor is required to fulfill the requirements of these programs during the prosecution of the work.

SECTION 6.17B. 24-Hour Contact Information.

Contractor shall have on record with the City the following twenty -four (24) hour emergency contact numbers:

1. Traffic control device supplier: Supplier of barricades, steel plates, delineators, channelizers, construction signs, and other traffic control equipment to be used during construction.

2. Contractor representative: An employee of the Contractor having the authority to make decisions and the ability to respond to an emergency on the project at any time.

3. Safety representative: The Contractor’s Safety Representative who has the authorities to make decisions regarding safety and health concerns on the project, to direct the Contractor’s personnel to abate any hazard identified by the City and the ability to respond to an emergency at the Project at any time and for Contractor’s safety representative.

SECTION 6.17C. Protection and Repair of Work.

Contractor shall protect the City ’s structures, facilities, equipment, tools, materials, and any other property on or adjacent to the S ite against damage, loss, or theft by providing 428

72 General Conditions
2026

adequate security measures for its work. Contractor shall, until final payment hereunder, maintain protection of all of its work and work performed by others under this Contract from damage, loss, defacement, or vandalism. Contractor shall provide protection of completed work which may be subject to damage as a result of Contractor ’s failure to perform as scheduled.

Contractor shall repair or replace any damage and remove any damaged or defaced material and/or equipment from the Site at no cost to the City.

SECTION 6.17D. Protection of Workers.

Contractor shall take every precaution for the safety of all employees and others on the Work, and to comply with all applicable provisions of federal, state and local safety laws and building codes to prevent accidents or injury to persons on, about, or adjacent to the premises where the Work is being performed.

Contractor shall erect and properly maintain at all times, as required by the conditions and progress of the Work, all necessary safeguards for the protection of workers and the public, and shall post danger signs warning against hazards created by construction including, but not limited to, protruding nails or reinforcing steel, hod hoists, elevator hatchways, scaffolding, window openings, stairways, and falling materials.

Contractor shall immediately replace or repair any unsafe ladder, scaffolding, shoring, or bracing, or correct any other dangerous or hazardous situation that may exist.

SECTION 6.17E. Working Limits and Regulations.

Contractor shall confine its apparatus, storage and materials, and construction operations within the limits established by the City and shall not unreasonably encumber the site or adjacent areas with its materials and/or equipment.

Contractor shall enforce any instructions from the City regarding fires, placement of signs, danger signals, barricades, radios, noise and smoking.

SECTION 6.17F. Protection of Existing Improvements and Property.

Contractor shall take all necessary precautions to protect all existing improvements , facilities and property from any damage resulting from the operations, equipment or workers of Contractor during the course of the construction, and Contractor shall be strictly liable for failure to adequately protect any existing improvements and/or facilities.

Trees and shrubbery that are to remain, pole lines, fences, signs, survey markers and monuments, buildings and structures, conduits, under - or above-ground pipelines, and any other improvements and facilities shall be protected from injury or damage. If ordered by the City , Contractor shall provide and install suitable safeguards to protect such objects from injury or damage.

Contractor shall take all necessary precautions to protect existing facilities against the effects of the elements and Contractor shall be strictly liable for failure to adequately protect any facility.
429

73 General Conditions
2026

Contractor shall clean the portions of existing improvements and facilities which are used by, traversed or dirtied by the workers on the Work, normal maintenance due to use by City employees or the public excepted.

All improvements, f acilities or property injured or damaged by reason of Contractor 's operations, shall be replaced, repaired, and restored to their original condition without additional cost to the City and without an extension of the Contract Time.

SECTION 6.17G. Not Used.

SECTION 6.17H. Security of the Site.

SECTION 6.17(I). Removal of Barricades.

Upon completion of the work, Contractor shall remove from the site all materials used for barricades, temporary scaffolding, or any other temporary uses.

SECTION 6.17J. Protection of Adjacent Property; Notices.

In addition to any requirements imposed by law, Contractor shall shore up, brace, underpin, and protect as may be necessary all foundations and other parts of all existing structures on the site or adjacent to the site which are in any way affected by the excavations or other operations connected with the completion of the Work.

Prior to commencing any work which in any way affects adjoining or adjacent land or buildings thereon, or public utilities, Contractor shall notify the City , who will send the occupants thereof a notice, which specifies the type of work to be done, the schedule of the work, the impacts expected from the work and the protective measures being taken by Contractor. The notice shall also specify that any person receiving notice who has questions regarding it may contact the City.

Whenever any notice is required to be given to any adjoining or adjacent landowner , utility, governmental agency or other party before commencement of any work, the notice shall be given by Contractor at least seven days in advance of the work, or longer if required by law or regulation, with a copy delivered to the City.

Contractor shall, at the written instruction of the City , meet with any recipient of such notice to explain and discuss the proposed work.

SECTION 6.17K. Work on Private Property.

Contractor must obtain written permission from the City of any privately owned property prior to beginning any work, storing materials or otherwise conducting any operations on said property. The written approval from the property owner must be on file with the City before any operations will be permitted on said property. 430

74 General Conditions
2026

SECTION 6.17L. Not Used.

SECTION 6.17M. Repairs or Replacement.

Any damage to existing conditions, or to any other improvement or property above or below the surface of the ground, whether private or public, arising from performance of this Contract shall be repaired within 48 hours by Contractor without expense to the City, unless disruption of City operations or creation of a safety hazard has occurred, in which case damage will be corrected immediately.

If, in the opinion of the Engineer, Architect or Consulting Engineer, the best interest of the City requires that repairs be made prior to the execution of any further work, the City will so notify Contractor who shall delay or discontinue that part of the Work until the necessary repair has been made. Such delay shall be considered non-compensable, and no extension of the Contract Time will be granted therefore.

Upon the failure of Contractor to comply with any such order, or upon Contractor’s failure to make immediate emergency repairs which are necessary to protect the Work, the City may do that work itself as is necessary to protect life and property, in its sole discretion, and deduct the total cost of such work from the next progress payment. No prior notice to Contractor shall be necessary for the City to take this action.

SECTION 6.17N. Emergency Safety Actions.

In an emergency affecting the safety of life or property, including adjoining property, Contractor, without previous instructions or authorizations from the City, is authorized and shall act at its discretion and risk to prevent such threatened loss or injury, and Contractor shall bear all costs of that action. Contractor shall immediately notify the City , and thereafter shall comply with any instructions issued by the City.

SECTION 6.17(O). Work During Hours of Darkness.

Working areas utilized by Contractor during the hours of darkness shall be illuminated to conform to the minimum illumination intensities established by Cal -OSHA, Construction Safety Orders and the Traffic Control Plans (TCP).

SECTION 6.18. PUBLIC CONVENIENCE AND SAFETY.

SECTION 6.18A. Public Convenience.

All work within public streets and/or roadway rights -of-way shall be done in an expeditious manner and cause as little inconvenience to the traveling public as possible.

Vehicles, bicycles, and pedestrians must be allowed to pass at all times except during an emergency closure. See Section 7.0 8, “Peak Hours, Hours of Darkness, Holidays and Weekends”, of these General Conditions for time limitations.

SECTION 6.18B. Pedestrian and Bicyclist Access.

Contractor shall not block the movement of pedestrian or bicycle traffic. Contractor shall provide for pedestrian and bicycle traffic by phasing construction operations or by 431

75 General Conditions
2026

providing alternative pedestrian and bicyclist access through or adjacent to construction areas. Proper advance notice signage with reasonable detours shall be installed and maintained through all phases of construction. Access to pedestrian and bicycle devices at traffic signals shall be maintained at all times. At no time shall pedestrians be diverted into a portion of the street used for vehicular traffic or on to private property unless adequate lane closure signage is in place. Pedestrian and bicycle access shall consist of four -foot (4’) wide bridges across trenches and four -foot (4’) wide passageways through construction areas. Hand railings for pedestrians shall be provided when required by Cal/OSHA Regulations or the Americans with Disabilities Act (ADA) on each side of each bridge or passageway to protect pedestrians from hazards caused by construction operations or adjacent vehicular traffic. Railings or barricades, which border passageways located in roadway areas, shall be reflectorized on the side facing oncoming traffic. The provisions of this section 6- 12.02 shall apply absent written approval from the City to the contrary.

SECTION 6.18C. Written Notification To Residences and Businesses.

Contractor shall notify, in writing, residents and business establishments along the route of the Work at least ten (10) Working Days prior to road closures and at least two (2) Working Days prior to disruption of ingress and egress. The notice provided to the residences or businesses shall include, at a minimum, schedule of closures with estimated closure times, closure location, alternate route or detour, and name and twenty-four (24) hour phone number of a contact person employed by the Contractor.

Contractor shall notify, in writing, residents and business establishments along the route of the Work at least two (2) Working Days prior to placing parking restrictions within the City right-of-way. The notice provided to the residences or businesses shall include, at a minimum, schedule of parking restrictions with estimated times, location, and a name and twenty -four (24) hour phone number of a contact person employed by the Contractor.

SECTION 6.18D. Access To Driveways, Houses and Buildings.

Access and passable grades shall be maintained to the extent feasible for business establishments and residents during construction. Safe and passable pedestrian, bicyclist, and vehicular access shall be provided and maintained. Access shall be continuous and unobstructed unless otherwise approved and shall be ADA compliant .

When abutting property owner’s access across the right -of-way line is to be eliminated, repaired, or replaced under the Contract, the existing access shall not be closed until the replacement access facilities are completed and functional or suitable temporary access facilities are installed.

SECTION 6.18E. Property Damage.

Any property damage caused by Contractor shall be repaired at Contractor’s expense to the satisfaction of the City.

Pursuant to Public Contract Code Section 9201, the City shall provide Contractor with timely notification of any third-party claims received by the City relating to this Contract. 432

76 General Conditions
2026

Such notification shall not create any rights or obligations on the part of the City to respond or otherwise act on behalf of Contractor with respect to such third-party claims.

SECTION 6.18F. Erection of Signs To Expedite Passage of Vehicles.

Contractor shall erect such warning and directional signs as necessary or as directed by the City for expediting the passage of public traffic through or around the Work and the approaches. All warning and directional signs shall comply with the current version of the California-MUTCD.

SECTION 6.18G. Traffic Obstructions, Delays and Inconveniences.

All public traffic shall be permitted to pass through the Work and Contractor shall conduct operations that offer the least possible obstruction, delay, and inconvenience to the public.

SECTION 6.18H. Work On Private Property.

Contractor must obtain written permission from the owner of any privately owned property prior to beginning any work, storing materials or otherwise conducting any operations on said property. The written approval from the property owner must be on file with the City before any operations will be permitted on said property.

SECTION 6.18(I). Hazardous Conditions Created.

Whenever Contractor’s operations create a condition hazardous to pedestrians, bicyclists, or the traveling public, Contractor shall, at Contractor’s own expense, furnish, erect and maintain any fences, covers, temporary railing (Type K), barricades, lights, signs and other devices necessary or as directed by the City to prevent accidents or damage or injury to the public or property.

If needed for public use, roadway excavation shall be conducted to maintain a smooth and even surface satisfactory for use by public traffic at all times. The surface of the roadbed shall be kept in a smooth, even condition free of humps and depressions, satisfactory for the use of public traffic as determined by the City.

Temporary facilities that Contractor uses to perform the Work or store or stage material or equipment shall not be installed or placed where they will interfere with the free and safe passage of public vehicular, bicycle, or pedestrian traffic.

433

77 General Conditions
2026

SECTION 6.19. PUBLIC SAFETY AND TRAFFIC CONTROL.

SECTION 6.19A. General.

All traffic controls shall be installed in accordance with the latest edition of the Caltrans “California-MUTCD.”

SECTION 6.19B. Responsibility For Safety.

It is Contractor's responsibility to provide for public safety and traffic control. The City may review Contractor’s operations and inform Contractor if an unsafe or hazardous condition is observed. Contractor may be directed verbally or via Field Directive, letter, email, or other means to abate the hazard. Contractor must comply with all directives for hazard abatement immediately and within the timeframe imposed by the City.

SECTION 6.19C. Passage of Emergency Vehicles.

Contractor shall provide for the uninterrupted passage of emergency vehicles through the Work zone at all times regardless of the controlled traffic conditions in place at the time.

SECTION 6.19D. Furnishing, Installing, and Maintaining Traffic Controls.

Appropriate traffic control shall be furnished by Contractor to provide an adequate warning to the public of dangerous conditions to be encountered during construction at all hours of the day or night. Warning and directional signs shall be erected and maintained as required by the City and by law. All traffic controls shall be installed as required by the Specifications.

SECTION 6.19E. Inadequate Traffic Controls and After -Hour Maintenance and Repairs.

Should Contractor appear negligent in furnishing and maintaining sufficient traffic control devices or protective measures or fail to provide flaggers as necessary to control traffic, the City may direct Contractor, at Contractor’s expense, to abate the hazard.

Should the City identify the inadequacy of warning devices and protective measures, that action shall not relieve Contractor from responsibility for public safety or abrogate the obligation to furnish and pay for these devices and measures.

Should Contractor fail to properly furnish or maintain traffic controls, or correct a hazard caused by inadequate or inappropriate traffic control, the City will abate the hazard. All City costs to abate the hazard shall be reimbursed by Contractor or deducted from the progress payment. If Contractor is not available to perform after -hour maintenance and repair to traffic control devices, the City will correct the situation and deduct all costs from the progress payment.

434

78 General Conditions
2026

SECTION 6.19F. Competent Flaggers.

Contractor shall provide competent and professional flaggers to control traffic when necessary or requested by the City. All flaggers shall be trained as required by Cal - OSHA regulations and shall be prepared to provide verification of such training to the City when requested.

SECTION 6.19G. Construction Signs.

Contractor is responsible for supplying, installing, and maintaining all construction signs and posts. Contractor will receive direction from the City as to the specific locations and placement of each sign. Regulatory signs or guide signs shall be supplied, erected, and maintained by Contractor, subject to City approval, and shall be protected from damage from construction activities by Contractor throughout the duration of the Project.

SECTION 6.19H. Temporary Bridging of Excavations and Trenches.

Whenever necessary or requested by the City, excavations shall be bridged with steel plates to allow an unobstructed flow of traffic.

1. Asphalt concrete “cutback” shall be placed around the edges of the plate to provide a ramp and smooth transition from the pavement to the plate to minimize wheel impact. All ramping must be accomplished to provide a minimum angle of approach of twelve horizontal to one vertical (12H:1V).

2. Bridging shall be secured against displacement by using railroad spikes or other approved fastening devices.

3. Bridging shall be placed and secured to work to minimize noise levels.

4. Steel plates used for bridging shall extend at least one (1) trench width on each side beyond the edges of the trench. Any deviations from these requirements must be designed by a registered engineer and reviewed by the City.

5. Depending upon the depth of the excavation, soil type, vibration, and other variables, the trench may require shoring to support bridging. The excavation shall be designed by a State Registered Civil Engineer or other appropriate professional if there is any question about the capability of the excavation and bridging to support the forces of traffic.

WIDTH OF EXCAVATION MINIMUM THICKNESS OF STEEL
PLATES

2.0 ft. or less (0.6 m or less) 7/8 inch (22 mm)

3.0 ft. (0.9 m) 1 inch (25 mm)

4.0 ft. (1.2 m) 1-1/4 inch (32 mm)
435

79 General Conditions
2026

In sidewalk areas, one and one- eighth inch (1- 1/8”) plywood may be substituted for steel plating. Such plywood shall be secured to prevent removal by unauthorized persons. Asphalt concrete “cutback” or other non- displaceable material must be used to provide a ramp for pedestrian and handicap access. All ramping must be accomplished to provide a minimum angle of approach of twelve horizontal to one vertical (12H:1V). Vehicular travel over backfilled but unpaved excavations will not be allowed, unless Contractor provides a temporary surface suitable for driving consisting of at least two inches (2”) of plant mix asphalt over six inches (6”) of aggregate base, concrete slurry (completely cured), or traffic plates placed over the excavated area of sufficient width and thickness as indicated in this Section.

SECTION 6.19(I). Entering and Leaving the Construction Zone.

Construction equipment shall enter and leave the roadway by moving in the direction of public traffic. All movements of workmen and construction equipment on or across lanes open to public traffic shall be performed in a safe manner that will not endanger the workmen or the public. When leaving a work area and entering a roadway carrying public traffic, Contractor's equipment operators shall yield to public traffic.

SECTION 6.19J. Existing Traffic Signals and Lighting Systems, Signs and Pavement Markings.

Existing traffic signals and highway lighting systems shall be kept in operation during progress of the Work. When traffic signal shutdown is permitted by the City, Contractor shall notify the City at least five (5) Working Days prior to shut down. Traffic signal detectors accidentally cut or damaged during construction shall be repaired or replaced by Contractor at Contractor’s expense and be operational within seventy-two (72) hours.

When traffic signals are approved for shutdown, Contractor shall control traffic by use of flaggers as directed by the City. “STOP” signs will not be permitted at these locations, unless allowed by the City.

Existing signs and pavement markings shall be maintained by Contractor and shall not be removed or altered without City approval.

SECTION 6.19K. Bus Stops.

If construction operations will obstruct a bus stop, Contractor shall notify the Transit provider five (5) Working Days in advance of beginning that portion of the Work and make provisions agreeable to the transit provider to provide an alternate location where people can safely board the bus.

SECTION 6.19L. Dust.

Water or dust palliative shall be applied if ordered by the City for the alleviation or prevention of dust nuisance caused by Contractor's operations as provided in Article 10, Environmental Controls, of these General Conditions.

436

80 General Conditions
2026

SECTION 6.19M. Removal of Spillage From Roadway.

Contractor shall immediately remove any spillage resulting from hauling operations along or across any public traveled way.

SECTION 6.20. CONFINED SPACES.

SECTON 6.20A. Contractor Responsibilities and Qualifications.

When working in a confined space, Contractor shall comply with all confined space requirements of Title 8, General Industry Safety Orders (Cal-OSHA), Article 108, Sections 5156 through 5159.

Prior to any confined space entry, Contractor shall submit for City review:

1. Contractor’s procedures for confined space operations.

2. Copies of all documents and certificates that qualify Contractor to safely perform work in permit-required confined spaces. Contractor shall also submit all applicable Material Safety Data Sheets (MSDS) and hazard information on chemicals, products, materials, or procedures.

3. Sufficient documentation and evidence that a permit -required confined space entry can be made in accordance with Article 108. Documentation shall include, but not be limited to the following:
• Equipment availability, suitability, and integrity.
• Personnel training.
• Experience.
• Supervision.
• Safety.
• Accident experience.
• Permit-required confined space policy.
• Hot work procedures (if applicable).
• Lock-out/tag-out procedures (if applicable).

Contractor’s submittal shall be made thirty (30) Calendar Days prior to any confined space entry in accordance with Sect ion 5.10, Contractor’s Submittals, of these General Condtions.

Contractor will not be allowed to make a permit -required confined space entry until the City has reviewed Contractor’s qualifications and proposed methods.

Contractor shall conform to the procedures established by Contractor ’s submittal during all confined space operations. Contractor shall provide all monitoring and safety equipment necessary to perform pre- entry checks of confined spaces. Contractor shall 437

81 General Conditions
2026

also provide all monitoring, safety, and communications equipment required for confined space operations.

SECTION 6.20B. City Responsiblities for Permit Confined Spaces.

Contractor shall be provided with information regarding known hazards and known or potential permit spaces . After the City has reviewed Contractor’s submittal to perform permit-required confined space entry work, Contractor will be provided with the following:

• Notification of the location, physical characteristics, known hazards, etc. regarding the permit-required confined space Contractor anticipates entering.

• Information regarding safety items (e.g. nearby emergency equipment), precautions, procedures, safeguards, etc. installed or implemented and that may be available to the Contractor's employees in or near the permit -required confined space.

The City’s failure to identify a confined space does not relieve the Contractor of the responsibility for compliance with the requirements of Article 108 (Cal -OSHA) and this Section 6.20.

SECTION 6.20C. Existing Sewers and Storm Drains.

Because of the potential danger of solvents, gasoline, and other hazardous material in existing sewers and storm drain pipes, these areas shall be treated as permit -required confined spaces unless it has been proven, through appropriate testing, that no hazards exist or are expected to develop.

SECTION 6.20D. Joint City – Contractor Entries.

Unless otherwise directed in writing by the City, when City employees work alongside the Contractor in a permit -required confined space, the permit procedures for both the City and the Contractor shall be used. The Entry Supervisor shall coordinate the requirements of both permit procedures prior to entry.

SECTION 6.21 TRAFFIC CONTROL PLANS (TCP).

SECTION 6.21A. Traffic Pattern Changes.

The Contractor shall notify the City in advance of the Contractor's desire to change any existing traffic patterns. Traffic lanes for public use shall be at least ten feet (10’) in width. Whenever feasible an additional four feet (4’) shall be provided for a bicycle lane.

If it is not feasible to provide a separate bicycle lane, the Contractor shall post signage before the construction area stating, “SHARE the Road with Bicyclists.” Additionally, when the lane is shared, the Contractor shall post signage for a maximum speed limit of 25 MPH in the shared lane. For traffic pattern changes that do not require a road closure, the Contractor shall provide the City with a minimum of five (5) Working Days advance notification, unless otherwise approved or deemed an emergency lane closure 438

82 General Conditions
2026

by the City. For all road closures, the Contractor shall provide the City with a minimum of twenty (20) Working Days’ notice prior to the desired closure date, unless otherwise approved or deemed an emergency road closure by the City.

SECTION 6.21B. Traffic Control Plans (TCP).

Contractor shall submit a Traffic Control Plan (TCP) to the City for review. The TCP shall show traffic control measures to be used for vehicles, bicyclists, and pedestrians affected by the construction. Five (5) sets of the TCP shall be submitted on eleven- inch by seventeen-inch (11”x17”) (minimum) paper. Contractor will not be allowed to begin work associated with the road or lane closure until the TCP is reviewed by the City.

TCPs will be reviewed and returned within twenty (20) Working Days.

The City reserves the right to extend the review period or request and review a TCP if special conditions warrant.

Detours used exclusively by Contractor for hauling materials and equipment shall be constructed and maintained by Contractor at Contractor’s expense. If Contractor's operations are damaging the roadway, the City has the authority to regulate the Contractor's operations and direct the Contractor to repair the roadway at the Contractor’s expense.

SECTION 6.22. BARRICADING OPEN TRENCHES.

Any excavation permitted by the City to be left open shall be barricaded with Type I, Type II, or Type III barricades with reflective tape and flashers as approved or directed by the City. Signs stating “OPEN TRENCH” shall be posted when requested by the City. All open excavated areas shall be barricaded with at least two (2) Type III barricades at the end of the excavation that faces oncoming traffic. Any excavation within four feet (4’) of the traveled way, not protected by K -rail or a similar traffic control barrier approved by the City, shall be backfilled at the end of the work shift or plated in accordance with Section 6.19H, “Temporary Bridging of Excavations and Trenches,” in this Section of these General Conditions.

SECTION 6.23. EXISTING UTILITIES.

SECTION 6.23A. General.

Contractor shall coordinate and fully cooperate with the City , utility district(s) and governmental agencies for the location, relocation, and protection of utilities.

Contractor’s attention is directed to the existence of utilities, underground and overhead, necessary for all buildings in the Work area. Before proceeding with trenching or other operations that may cause damage to existing utilities, Contractor shall, in accordance with Government Code Section 4216.2, arrange for the location of existing utilities and shall arrange for the relocation of such utilities , if necessary, by the utility district(s) or Contractor.
439

83 General Conditions
2026

SECTION 6.23B. Maintenance and Protection.

Unless otherw ise shown or specified in the Contract Documents, Contractor shall maintain in service all drainage, water, gas, sewer lines, power, lighting, telephone conduits, and any other surface or subsurface utility structure that may be affected by the Work. However, Contractor, for convenience, may arrange with the individual owners to temporarily disconnect service lines or other facilities along the line of the Work. The cost of disconnecting and restoring such utilities shall be borne by the
Contractor.

When connecting to existing utilities, Contractor shall expose all underground facilities that are to be connected to or that might be affected by the construction of the proposed improvements for verification of location and elevation prior to ordering materials.

Unless otherwise specified in the Contract Documents , Contractor shall protect all existing utilities on all projects being constructed
, whether inside or outside of highway
rights-of-way. The utility district(s) may elect to provide the necessary protective measures and bill Contractor for the cost. “Existing utilities” includes traffic control devices, conduits, streetlights, and related appurtenances. Existing utility facilities that are to be relocated, including traffic signals and light poles, shall be relocated prior to paving. No paving shall be performed around existing utility facilities that are to be relocated.

SECTION 6.23C. Exact Locations Unknown.

Where locations of existing utility facilities are shown on the Plans , they are approximate and represent the best information obtainable from utility maps and other information furnished by the various utility district(s) involved. The City warrants neither the accuracy nor the extent of actual installations as shown on the Plans. There may be additional utilities on the property unknown to either party to the Contract. If, during the course of the Work, additional subsurface utilities are discovered, the City may make adjustments to the Work. Compensation for such adjustments will be in accordance with Article 9, “Changes and Claims”, of these General Conditions.

In accordance with Government Code Section 4215, the City will compensate Contractor for the costs of locating, repairing damage not due to the failure of Contractor to exercise reasonable care, removing, relocating or protecting existing main or trunk line utility facilities not indicated in the Plans and Specifications with reasonable accuracy, and for equipment on the Work necessarily idled during such work. In no event shall the City be liable for any further or additional costs resulting directly or indirectly from any such occurrence.

Compensation will be in accordance with Article 9, “Changes and Claims”, of these General Conditions. Nothing herein shall be deemed to require the City to indicate the presence of existing utility services, laterals, or appurtenances whenever their presence can be inferred from other visible facilities such as buildings, meters, junction boxes, valves, service facilities, identification markings, and other indicators on or adjacent to the Work.
440

84 General Conditions
2026

If Contractor discovers utilities not identified in the Plans or Specifications, Contractor shall immediately notify the City and the utility district(s) by the most expeditious means available and later confirm in writing. If the completion of the Work is delayed by failure of the City or the utility district(s) to remove, repair, or relocate the utility, such delay may be an excusable delay as defined and provided for in Section 7.12B , “Excusable Delays”, of these General Conditions . Nothing herein shall preclude the City from pursuing any appropriate remedy against the utility for delays that are the responsibility of the utility.

Contractor shall not be assessed liquidated damages for delay in completion of the Work for that portion of such delay as is caused by failure of the City or the utility district(s) to provide for the removal or relocation of existing utilities.

SECTION 6.23D. Underground Service Alert (USA).

The City is a member of the Underground Service Alert North (U.S.A.) one-call program.

Except in an emergency, Contractor and any Subcontractor planning to conduct any excavation shall notify the U.S.A. at least two (2) Working Days, but no earlier than fourteen (14) Calendar Days, in advance of performing excavation work. U.S.A. can be reached by calling 811 or going to www.usanorth811.org. U.S.A. does not accept emergency calls. For emergency repairs, the Contractor or any Subcontractor planning to conduct an excavation, must contact the designated City representative. The provisions of Government Code Sections 4216 through 4215.9, inclusive, shall be followed.

Each phase of the Project shall be called into U.S.A. and continuing excavation reported every fourteen (14) Calendar Days. Contractor shall not call into U.S.A. the entire Project boundaries or, on road construction projects, the entire length of the project.

The excavator shall only request the marking of facilities within the area to be excavated within fourteen (14) Calendar Days of the call. U.S.A. will provide an inquiry identification (“Ticket”) number to the person contacting the center. The U.S.A. ticket number shall be available to the Inspector at the job site along with the date U.S.A. was called. If the U.S.A. notifications are not kept up-to-date, the excavation will be stopped, and a new two (2) Working Day notice will be required before continuing the excavation.

If, at any time during an excavation for which there is a valid ticket number, the field markings are no longer reasonably visible, Contractor shall contact U.S.A.to have the area re-marked. Contractor shall allow two (2) Working Days for re-marking of facilities.

Prior to calling U.S.A., Contractor shall clearly mark the excavation site with white, water-soluble, or spray chalk paint in paved areas or place flags, stakes, whiskers, or some other approved method in unpaved areas. Contractor shall determine the exact location (twenty -four inches (24”) from outside edge on either side of the facility) of utilities in conflict with the proposed excavation by exposing the subsurface installation with hand tools before using any power -operated or power -driven equipment. The Contractor is responsible for protecting operators’ markings or markers until they are removed.

Prior to Final Acceptance, all U.S.A. markings shall be removed by Contractor to the satisfaction of the City. During the progress of the Work, markings shall be removed by 441

85 General Conditions
2026

Contractor to the satisfaction of the City. During the progress of the Work, markings or markers shall be removed within two (2) months of the date the markings or markers are no longer needed or upon completion of the work, whichever comes sooner. The City will accept natural weathering of the markings if the markings disappear within the two-month period or prior to Final Acceptance. If the markings are in brick pavers or concrete areas and if, by natural weathering or other approved removal methods, the markings still remain, Contractor must replace the concrete or the brick pavers in- kind, unless the utility operator has failed to use chalk -based paint or other non- permanent marking materials. Contractors and utility operators are encouraged to avoid marking in these areas by using offset markings. Removal methods shall be non- destructive and residual shadowing shall not remain.

Removal of markings shall comply with requirements of any applicable Federal, State, and local laws, rules, or regulations.

U.S.A. markings not removed by the required time lines may be removed and the sidewalk or street repaired/replaced by the City at its discretion. The City will charge the Contractor a service fee equal to the actual costs of removal for removing the markings and making any repairs and/or replacements. This fee will include the cost to comply with any applicable Federal, State, and local laws, rules, or regulations.

SECTION 6.23E. Damage to Existing Utilities.

Contractor shall notify the affected utility of any contact, scrape, dent, nick, or damage to their facility. Any operator or excavator who negligently violates Government Code Section 4215 is subject to a civil penalty in an amount not to exceed ten thousand dollars ($10,000). Any operator or excavator who knowingly and willfully violates Government Code Section 4215 is subject to a civil penalty in an amount not to exceed fifty thousand dollars ($50,000).

SECTION 6.23F. Markings.

The following table designates color codes and symbols that shall be used by the Contractor and the utility owners to identify utilities:

FIELD MARKINGS

COLOR CODES AND SYMBOLS
Color Symbol Name Name
Safety Precaution
Blue W Water
Safety Alert Orange
FA
Tel
R
TV
WU
Fire Alarm
Telephone/Communication
Railroad
Television/CATV
Western Union
Safety Green S Sewer
442

86 General Conditions
2026

FIELD MARKINGS

COLOR CODES AND SYMBOLS
D Storm Drain
Safety Red
L
E
T
Street Lighting
Electric
Traffic Signals
High Visibility Safety
Yellow
G
Company Name
Gas
Oil or Chemical
Steam
Purple RW Reclaimed Water
Pink/Fuchsia TSM Temporary Survey
White USA
Proposed Excavation – Paint outline of
proposed excavation area with white dotted
line

SECTION 6.24. EXCAVATION AND TRENCH SAFETY.

SECTION 6.24A. Permit.

Contractor must obtain a permit from the Division of Industrial Relations per Labor Code Section 6500, as specified in California Code of Regulations, Title 8, Article 2 , Sections 341, 341.1 and following, and Title 8, Article 6, 1539 “Permits” of the Construction Safety Orders, for all excavations five feet (5’) or deeper to which an employee is required to descend. The permit shall be kept at the construction site at all times.

SECTION 6.24B. Shoring, Bracing. Shielding, and Sheeting.

In accordance with Labor Code Section 6705, at least five (5) Working Days in advance of excavation of any trench or trenches five feet (5’) or more in depth, with a total value of twenty-five thousand dollars ($25,000) or more, Contractor shall submit to the City a detailed plan showing the design of shoring, bracing, sloping, or other provisions for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If such plan varies from the shoring system standards, the plan shall be prepared by a California Licensed Professional Civil or Structural Engineer. A signed copy of the detailed plan shall be on the site at the time of the excavation. Nothing in this Section shall be deemed to allow the use of a shoring, sloping, or protective system less effective than that required by the Construction Safety Orders. Nothing in this Section shall be construed to impose tort liability on the City or any of its employees. These systems must support the sides of the excavation and prevent soil movement that could cause injury to any person or structure. Any damage resulting from a lack of adequate shoring, bracing, shielding or sheeting shall be repaired at Contractor's expense.

Contractor shall immediately replace or repair any unsafe ladder, scaffolding, shoring, or bracing, or correct any other dangerous or hazardous situation that exists.

A Competent Person, as defined in California Code of Regulations, Title 8, Construction Safety Orders, Section 1504, “Definitions,” shall be on site at all times when Contractor's employees are working within the trench. A "Competent Person" is one who is capable of 443

87 General Conditions
2026

identifying existing and predictable hazards in the surroundings, or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them.

The price bid for work that will require an excavation of five feet (5’) or deeper (or less if conditions warrant) shall include the cost of adequate sheeting, shoring, and bracing, or equivalent method conforming to applicable safety orders, unless a separate Bid Item for such work is included in the bid form.

SECTION 6.25. OVERLOADING.

Contractor shall determine safe loading capacities and shall not overload any structure, equipment, pavement, or material beyond its safe capacity, or significantly deteriorate the preconstruction condition, during construction. In addition to assuming full responsibility for bodily injury resulting from any such overloading, Contractor shall repair to the City ’s satisfaction or reimburse the City for the costs of repairing the damage.

SECTION 6.26. PRESERVATION OF PROPERTY.

Trees and shrubbery that are to remain, pole lines, fences, signs, traffic control devices, striping, survey markers and monuments, buildings and structures, conduits, under - or above-ground pipelines, and any other improvements and facilities shall be protected from injury or damage. If ordered by the City, the Contractor shall provide and install suitable safeguards to protect such objects from injury or damage. If such objects are injured or damaged by reason of the Contractor's operations, said objects shall be replaced or restored at the Contractor’s expense to a condition as good as when the Contractor entered upon the Work. The Contractor shall receive City approval before the removal of any road sign or permanent traffic control device that interferes with the Work.

SECTION 6.27. APPROVAL OF CONTRACTOR'S PLANS NO RELEASE FROM LIABILITY.

The review or approval by the City of any submittal, working drawing or any method of work proposed by Contractor shall not relieve Contractor of any of Contractor ’s responsibility for any errors and shall not be regarded as any assumption of risk or liability by the City or any officer, official, agent, employee, member, volunteer, affiliate, or their duly authorized representatives. Contractor shall have no claim under the Contract because of the failure or partial failure or inefficiency of any reviewed or approved plan or method. City review or approval means that the City has no objection to Contractor using the proposed plan or method at Contractor's responsibility and risk.

SECTION 6.28. CONTRACTOR SHALL NOT MORTGAGE EQUIPMENT.

Contractor shall not mortgage or otherwise convey the title of the plant, machinery, tools, appliances, supplies, or materials that may at any time be in use, or further required or useful, in the prosecution of the Work, without prior written consent of the City. 444

88 General Conditions
2026

SECTION 6.29. PROPERTY RIGHTS IN MATERIALS.

Nothing in the Contract shall be construed as vesting in Contractor any right of property in the materials used after they have been installed, attached or affixed to the Work, and on which partial payments have been made by the City. All such materials shall be the property of Contractor and the City jointly as their interests may appear, and shall not be removed from the Work by Contractor without the City’s consent.

SECTION 6.30. CONFLICT OF INTEREST.

No official of the City who is authorized on behalf of the City to negotiate, make, accept, or approve, any architectural, engineering, inspection, construction, or materials supply contract, or any subcontract in connection with the construction of the Project, or any land acquisition in connection with the Project, shall become directly or indirectly interested personally in this contract or in any part thereof.

No officer, employee, architect, attorney, engineer, or inspector of or for the City who is authorized on behalf of the City to exercise any executive, supervisory, or other similar function in connection with the construction of the Project shall become directly or indirectly interested personally in this contract or any part thereof.

SECTION 6.31. NO AGREEMENTS.

No verbal agreement or conversation with any officer, agent, or employee of the City , either before, during, or after the execution of the Contract Documents shall affect or modify any term or condition contained in the Contract Documents, nor shall such verbal agreement or conversation entitle Contractor to any additional payment or time to perform whatsoever under the terms of this agreement.
445

89 General Conditions
2026

ARTICLE 7. PROSECUTION OF THE WORK
SECTION 7.01. BEGINNING OF WORK.

No work may take place prior to receipt of the executed Contract and review of the prescribed bonds and insurance. Upon receipt of the executed Contract and approval of the bonds and insurance by the City , a Notice to Proceed will be issued which will constitute authorization to begin work. The counting of Contract Time shall begin upon issuance of the Notice to Proceed or other date as specified in that notice.

SECTION 7.02. AMOUNT OF WORK UNDER CONSTRUCTION.

Contractor shall not have more work under construction than can be undertaken properly with regard to the rights of the public and the safety and integrity of the Project.

SECTION 7.03. PRECONSTRUCTION CONFERENCE AND PROGRESS MEETINGS.

Prior to beginning work, but within ten (10) working days of issuance of the Notice to Proceed, a preconstruction conference shall be held for the purpose of reviewing the Work. Contractor must attend this preconstruction conference, and shall invite Subcontractors and others necessary to ensure all topics are adequately covered.

Topics discussed include, but are not limited to, mobilization, access, temporary facilities, utilities, subcontractors, schedules, procedures, correspondence, progress payments, payroll records, Storm Water Pollution Prevention Plans (SWPPP), coordination, safety, after -hour contacts for Contractor and City personnel, quality control/quality assurance, personnel assignments, and other topics as appropriate.

Progress meetings, as stipulated in the Special Provisions or as required by the City, will be conducted throughout the duration of the Contract. The purpose of these meetings is to inform, discuss, and resolve issues related to the Work; the Contractor or the Contractor’s agent shall attend. Topics discussed include, but are not limited to, progress, schedules, safety, SWPPP, RFI’s, Change Orders, Field Directives, field coordination, submittals, quality control/quality assurance, testing, startup, safety, and other topics related to the Work.

The City may prepare minutes of all meetings. If minutes are prepared, the City will endeavor to send them to Contractor within two (2) Working Days. Contractor will endeavor to respond within two (2) Working Days with any corrections to the minutes, and any portion of the minutes not corrected by Contractor will be deemed as accurate.

The City or Contractor may audiotape or videotape these meetings to create a record of the meeting, and a copy of any tape recordings shall be provided as part of the minutes.

SECTION 7.04. WORK TO BE UNDERTAKEN WITH ADEQUATE SUPERVISION, LABOR FORCE, EQUIPMENT AND METHODS.

Contractor shall undertake the Work under the Contract with all materials, tools, machinery, apparatus, and labor necessary to complete the Work as described, shown, 446

90 General Conditions
2026

or reasonably implied under the Contract, or as directed by the City, on or before the scheduled Contract Completion Date.

If Contractor is not diligently proceeding with the prosecution of the Work as set forth in the construction schedule, Contractor shall, immediately and at no additional cost to the City, take all measures necessary to ensure completion within the Contract Time, including but not limited to increasing the number of employees, working overtime, working additional shifts or crews, and working Saturdays, Sundays, or holidays, subject to other requirements in these provisions.

SECTION 7.04A. Superintendence.

Contractor shall keep on the Work, throughout its progress, a competent superintendent who shall have complete authority to represent and act for Contractor . Such superintendent shall be capable of reading and understanding the Contract, and shall receive and follow any instruction given by the City
.

Whenever Contractor or Contractor’s superintendent is not present on a particular part of the Work where it may be desired to give direction, orders will be given by the City and shall be received and obeyed by the foreman or other representative who may have charge of the particular work in reference to which the orders are given, or the City may stop the work until Contractor or Contractor's superintendent arrives.

SECTION 7.04B. Labor.

Workers, laborers, or mechanics skilled in each class of work shall accomplish every part of the Work. Contractor is responsible for the efficiency, safety and adequacy of its labor force and those of all Subcontractors.

SECTION 7.04C. Equipment and Methods.

Only equipment and methods suitable to produce the quality required by the Contract will be permitted to operate on the Work. Except as specified in Section 5.09 , “Contractor’s Equipment”, of these General Conditions , or in the Special Provisions or Technical Specifications, equipment shall be that used in general practice for the work undertaken.

If any part of Contractor's plant, equipment, or methods of executing the Work is unsafe, inefficient, or inadequate to ensure the required quality or rate of progress of the Work, the City may order Contractor to modify Contractor’s facilities or methods. Contractor shall promptly comply with such orders at Contractor ’s expense. However, neither compliance with such orders nor failure of the City to issue such orders shall relieve Contractor from the obligation to secure the degree of safety, the quality of the Work, and the rate of progress required by the Contract. Contractor is responsible for the safety, adequacy, and efficiency of its plant, equipment, and methods.

SECTION 7.05. SCHEDULES.

Contractor shall submit a baseline schedule and updated schedules in accordance with this Section 7.05 and Section 5.10 , “Contractor’s Submittals”, of these General Conditions, which shall illustrate Contractor’s planned schedule for carrying out the Work 447

91 General Conditions
2026

and completing the Work within the Contract Time. Contractor’s updated schedules shall show the as-built schedule for work completed.

All schedules must show completion by any milestone dates required in the Contract Documents and the Contract Completion Date. Contractor expressly waives any early completion delay claim. Contractor has the right to try to complete the Work ahead of any milestone date and/or the Contract Completion Date, but if Contractor is somehow delayed from doing so, Contractor may not base a claim for additional compensation on such delay.

Contractor acknowledges that a purpose of submitting reasonable, accurate and adequate schedules is to protect the City and Contractor against unjustified delay and disruption claims or unjustified rejections of such claims. Contractor agrees to devote all resources necessary to provide scheduling services, as with any other item of Work on the Project. Contractor agrees that its failure to submit reasonable, accurate and adequate schedules will bar claims by Contractor for additional compensation and/or time extensions based on the information contained in such a schedule, including but not limited to delay, disruption or inefficiency claims.

The City will review all schedules for conformance with the Contract. City review and/or approval of a schedule does not relieve Contractor of responsibility for the feasibility of the schedule or for accomplishing milestones and completion within Contract Time, nor does City review and/or approval warrant or acknowledge the reasonableness of the schedule’s logic, durations, labor estimates, or equipment productivity. City review and/or approval of a schedule does not indicate approval by the City of the schedule, nor does it relieve Contractor of responsibility for any characteristics of the schedule that breach the Contract or that are unreasonable, inaccurate, inadequate, or deficient.

If no separate item is provided in the Bid Form for scheduling, the cost for preparing the baseline schedule and preparing updates and revisions of the baseline schedule shall be included in payments for mobilization. If no bid item for mobilization is included in the Bid Form, conformance with this provision is incidental to and included in the various bid items and no additional payment will be made. Updates and revisions of the schedules are included in the prices paid for other items of work.

Because the City places a high value on the importance and use of project scheduling information as a management tool in achieving the completion of the Work as planned, the City will deduct 10 percent (10%) of the monthly progress payment, but not more than twenty-five thousand dollars ($25,000), for failure by Contractor to timely obtain the approved Contract Schedule or to submit any monthly updated Progress Schedule, as required by the Specifications, with each monthly progress payment request. These deductions are cumulative, and will be made for each and every month that Contractor fails to provide the required information. The monthly updated schedule and narrative shall be accurate, reflect actual events on the Project, and meet all requirements of the Specifications. If Contractor does not correct the deficiency by providing an acceptable schedule within ten (10) Calendar Days of the City’s receipt of the monthly progress payment request, the deduction may become permanent via a deductive Change Order.

The City may withhold payments from Contractor until a satisfactory baseline schedule, update, or revision has been submitted and reviewed.
448

92 General Conditions
2026

SECTION 7.05A. Baseline (Contract) Schedule.

Within 14 Calendar Days after receiving the Notice to Proceed, Contractor shall submit a detailed proposed baseline schedule presenting an orderly and realistic plan for completion of the Work, in conformance with the requirements of the Specifications. The proposed baseline schedule shall be in electronic, native format and PDF.

The proposed baseline schedule shall comply with the following requirements, unless modified by the City:

1. A time scaled CPM type schedule showing the mathematical analysis of the CPM network diagram and prepared in the version of software subject to City acceptance.

2. No activity on the schedule shall have a duration longer than fourteen (14) Working Days, with the exception of fabrication and procurement activities, unless otherwise approved by the City. Activity durations shall be the total number of actual days required to perform that activity including consideration of weather impact on completion of that activity.

3. Procurement of major equipment, through receipt and inspection at the job site, identified as a separate activity.

4. Owner furnished materials and equipment if any, identified as separate activities.

5. Dependencies (or relationships) between activities.

6. Processing/approval of submittals and shop drawings for major equipment.

Activities that are dependent on submittal acceptance and/or material delivery shall not be scheduled to start earlier than the expected acceptance or delivery dates.

7. Separate buildings and other independent project elements shall be individually identified in the network.

8. Fourteen (14) Working Days for developing punch list(s), completion of punch list items, and final clean- up for the work or any designated portion thereof.

No other activities shall be scheduled during this period.

9. Interface with the work of other contractors (or entities).

Each activity shown on the proposed baseline schedule shall have the following minimum information:

• Unique number(s) for each activity

• Activity description
449

93 General Conditions
2026

• Activity relationships and dependencies (logic)

• Activity duration in Working Days

• Early start, early finish, late start, late finish dates (calendar date, i.e., day, month, year)

• Total float, free float

• Interim milestone dates and completion dates

• Detailed list of work contained within each activity

• Manpower loading for each item of work for unit price contracts

• Cost loading for each item of work for lump sum contracts

The City will review the proposed baseline schedule for conformance with the requirements of the Contract and, within seven (7) Calendar Days after receipt, will approve the proposed baseline schedule or will return it with comments. If the proposed baseline schedule is not approved, Contractor shall revise the schedule to incorporate comments and resubmit the schedule for approval within seven (7) Calendar Days after receiving it. The approved schedule shall become the Contract Schedule.

The Contract Schedule shall be the basis for evaluating job progress, payment requests, and time extension requests. The responsibility for developing the Contract Schedule and monitoring actual progress as compared to the schedule rests with Contractor.

Failure of the Contract Schedule to include any element of the Work or any inaccuracy in the Contract Schedule will not relieve Contractor from responsibility for accomplishing all the Work in accordance with the Contract.

Approval of the Contract Schedule by the City will not relieve Contractor of the responsibility for accomplishing the Work in accordance with the Contract and the Contract Time.

SECTION 7.05B. Progress Schedules.

Contractor shall submit to the City each month with its payment application an electronic (native format and PDF) up to-date Progress Schedule with a narrative describing the general status of the Work and addressing any problem areas or delays, with impacts on critical path items of work highlighted. A corrective course of action shall also be included when problem areas or delays are encountered. The Progress Schedule shall be in the same software format and version as that used to create the Contract Schedule and shall include:

1. The Contractor's estimated percentage complete and remaining duration for each activity not yet complete.
450

94 General Conditions
2026

2. Actual start/finish dates for activities as appropriate.

3. Identification of processing errors, if any on the previous update reports.

4. Revisions, if any, to the assumed activity durations including revisions for weather impact for any activities due to the effect of the previous update on the schedule.

5. Identification of activities that are affected by requested or proposed changes to the Work.

6. Resolution of conflict between actual work progress and schedule logic.

When out of sequence activities develop in the Contract Schedule because of actual construction progress, the Contractor shall submit revisions to schedule logic to conform to current status and direction.

The City will review the updated schedule information and meet with Contractor each month, unless the City requests more frequent meetings, to determine the status of the Work. If agreement cannot be reached on any issue, Contractor will use the City ’s determination in the processing of the update.

Progress payments pursuant to the Contract will be based on the Progress Schedules.

SECTION 7.05C. Schedule Revisions.

If the sequence of construction differs significantly, as determined by the City, from the Contract Schedule, Contractor shall submit within fifteen (15) Calendar Days a revised schedule to the City for approval.

When a requested or proposed change to the Work will have an impact on the critical path, the Contractor shall submit a Time Impact Analysis in accordance with Section

7.18, “Extension of Time”, of these General Conditions showing this impact. If the requested or proposed change is accepted by the City, the schedule fragnet shall be incorporated into the Contract Schedule. Time extensions will be considered only to the extent there is insufficient remaining float to accommodate these changes, and pursuant to Sections 7 .12, “Delays” and 7. 18, “Extension of Time”, of these General Conditions .

No additional cost beyond that provided in Article 9, “Changes and Claims”, of these General Conditions will be allowed for the incorporation of approved changes into the Contract Schedule.

Should Contractor, after the City’s approval of the Contract Schedule, intend to change its plan of construction, it shall submit its requested revisions to the City, along with a written statement of the revision, including a description of the logic for rescheduling the work, methods of maintaining adherence to Intermediate milestones and other specific dates and the reasons for the revisions. If the requested changes are acceptable to the City , they will be incorporated into the Contract Schedule in the next reporting period.

Schedule revisions shall be submitted at least seven (7) Calendar Days prior to the date 451

95 General Conditions
2026

of submission of updated information. The City will have seven (7) Calendar Days to review the revisions.

SECTION 7.05D. Short Interval Schedules.

Contractor shall, if required by the City, prepare a Short Interval Schedule (SIS) to be used throughout the duration of Work. The SIS shall include all current activities and projected activities for the succeeding two (2) weeks. The SIS shall include actual start/finish dates for the preceding one (1) week. The SIS shall be submitted to the City prior to the each progress construction meeting. The Contractor shall participate in short interval scheduling coordination during the progress construction meetings.

SECTION 7.05E. Float.

All float in any activity, milestone completion date, and/or Contract Completion Date is owned by the Project and, as such, is a resource available to both the City and Contractor. Neither the City nor Contractor owns the float time.

Unless otherwise provided herein, float is synonymous with total float and total float is the period of time measured by the number of Working or Calendar Days (as specified in the Contract) any non- critical path activity may be delayed before it and its succeeding activities become part of the critical path. If a non- critical path activity is delayed beyond its float period, then that activity becomes part of the critical path and controls the completion date of the Work. Thus, delay of a non- critical path activity beyond its float period will cause delay to the Project itself.

Acceptance of any schedule based on less time than the maximum time allowed for accomplishment of milestones or Project completion within Contract Time, does not serve to contractually change any Contract duration, nor does it serve as a waiver of either Contractor’s or the City’s right to utilize the full amount of time specified in the Contract. As such, liability for delay of Project completion dates rests with the party actually causing delay to Project completion dates.

SECTION 7.05F. City’s Right to Revise the Schedule.

In the event of a delay to critical path work which is not the fault of Contractor, the City may elect to re-sequence work or otherwise modify the Contract Schedule in an attempt to minimize the effect of the delay. It shall be the responsibility of Contractor to cooperate in this effort. It is not the the City’s responsibility to ensure Contractor the ability to use “optimal” crew size throughout the Project and no adjustment of the Contract Sum will be made for minor variations in crew size or claimed loss of efficiency or disruption that result from schedule adjustments. However, overtime work or weekend work required by the City to meet schedule objectives other than those of Contractor will be reimbursed per the provisions of Article 9, “Changes and Claims”, of these General Conditions, provided that Contractor has not contributed to the delay which the City i s seeking to overcome. If Contractor contends that a schedule adjustment will cause a significant disruption of its work sequence or ability to perform work efficiently, it shall notify the City within forty eight (48) hours of receipt of the adjustment. Failure to provide timely notice constitutes a 452

96 General Conditions
2026

waiver by Contractor of any claim for compensation arising out of the schedule adjustment.

SECTION 7.05G. Responsibility for Completion.

Contractor shall furnish sufficient manpower, materials, facilities and equipment and shall work sufficient hours, including night shifts, overtime operations, Saturdays, Sundays and holidays (in accordance with Section 7. 08) as may be necessary to e nsure the progression and completion of the Work in accordance with the Contract Time. If work on the critical path is behind the currently updated Progress Schedule and it becomes apparent that the Work will not be completed within the Contract Time, Contractor will implement whatever steps it deems necessary to make up all lost time at no additional cost to the City
. If Contractor’s solution is not successful, it will make further attempts using the following sequence of events:

1. Reschedule activities to achieve maximum practical concurrence of accomplishment of activities.

2. If the above cannot be achieved then;
a. Contractor shall increase manpower in such quantities and crafts as will substantially eliminate, in the judgment of the City, the backlog of work; or increase the number of working hours, shifts per working day, working days per week or the amount of equipment or any combination of the foregoing sufficiently to substantially eliminate in the judgment of the City the backlog of work.
b. In addition, the City may require Contractor to submit a recovery schedule demonstrating its program and proposed plan to make up a lag in scheduled progress and to ensure completion of the Work within the Contract Time. If the City finds the proposed recovery schedule unacceptable, it may require the Contractor to submit a new plan. If the actions taken by the Contractor or the second plan proposed are unsatisfactory, the City may require the Contractor to take any of the actions set forth in the previous paragraph without additional cost to the City to make up the lag in scheduled progress
.

Failure of Contractor to comply with the requirements of this Section 7.05 G shall be considered grounds for a determination by the City that Contractor is failing to undertake the Work with such diligence as will ensure its completion within the time specified and will subject Contractor to all rights and remedies of the City under the Contract Documents.

SECTION 7.06. UNUSUAL SITE CONDITIONS.

Contractor shall promptly upon discovery, and before the following conditions are disturbed, notify the City, in writing, of any:
453

97 General Conditions
2026

1. Material that Contractor believes may be hazardous waste, as defined in Section 25117 of the Health and Safety Code that is required to be removed to a Class I, Class II, or Class III disposal site in accordance with provisions of existing law.

2. Subsurface or latent physical conditions at the site differing from those indicated in the Contract.

3. Unknown physical conditions at the site of any unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract.

Upon receipt of notice from Contractor, the City shall promptly investigate the conditions, and if it is determined that the conditions do materially so differ or do involve hazardous waste, and cause a decrease or increase in Contractor’s cost of, or the time required for, performance of any part of the Work, shall issue a Change Order or Directive under the procedures described in the Contract Documents.

In the event that a dispute arises between the City and Contractor as to whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in Contractor’s cost of, or time required for, performance of any part of the Work, Contractor shall not be excused from any scheduled Completion Date provided for by the Contract Documents, but shall proceed with all work to be performed under the Contract Documents. Contractor shall retain any and all rights provided either by the Contract Documents or by law which pertain to the resolution of disputes and protests between the contracting parties.

No contract adjustment which results in a benefit to Contractor will be allowed unless Contractor has provided the required written notice set forth in this Section 7.06.

No contract adjustment will be allowed under the provisions specified in this section for any effects caused on unchanged work.

SECTION 7.07. PURSUANCE OF WORK DURING INCLEMENT WEATHER.

During inclement or unsuitable weather or other unfavorable conditions, Contractor shall pursue only such portions of the Work that will not be damaged by the weather or unfavorable conditions. When the weather or unfavorable conditions creates hazardous travel or working conditions, as determined by the City, Contractor may be directed to stop that portion of the Work, in accordance with Section 5.24, “Temporary Suspension or Delay of Work”, of these General Conditions, until the weather clears or the conditions are no longer unfavorable. Contractor must keep roads safe and inspect and maintain stormwater pollution prevention and erosion control devices during inclement weather or unfavorable conditions. Lane and road closures may not be allowed if the City determines that the traffic controls will create unnecessary risk to the traveling public, Contractor , and/or City employees.
454

98 General Conditions
2026

SECTION 7.08. PEAK HOURS, HOURS OF DARKNESS, HOLIDAYS, AND WEEKENDS.

SECTION 7.08A. Allowable Times and Hours of Work.

Unless otherwise noted in the Contract Documents or approved in writing by the City, no work shall be done between the hours of 7 p.m. and 7 a.m., or on Saturdays, Sundays, or Legal Holidays.

Unless otherwise noted in the Contract Documents or approved in writing by the City, no lane of traffic shall be closed to the public during the peak hours of 7:00 a.m. to 8:00 a.m. and 3:30 p.m. to 6:00 p.m., except as necessary for the proper care and protection of work already performed or in case of an emergency repair as defined below. These exceptions are allowed only with the City’s written permission.

SECTION 7.08B. Off-Period Work.

A written request to work between 7 p.m. and 7 a.m. or on Saturdays, Sundays, or Legal Holidays, or to close a lane of traffic during peak hours must be submitted at least two (2) Working Days in advance of the intended work. The City w ill evaluate Contractor’s request to determine if there is a benefit to the City, a nuisance or a hazard to the public, the Project, or the area surrounding the site, and if Contractor should pay any City overtime costs related to the off -period work. The City may place conditions on any approval of off-period work based on this analysis.

SECTION 7.08C. Emergency Repairs.

An emergency repair is a repair to the Work (including traffic controls, barricades, or temporary signs) required as a result of an unforeseen event that poses a danger to the public or jeopardizes the integrity of the Work, whether completed or not. Contractor may be allowed to close a lane of traffic or work at night, on Saturdays, Sundays, or Legal Holidays for an emergency repair. Contractor must notify the City within one (1) hour of dispatch of Contractor ’s repair crews, and give their names, an emergency contact number, the location of the emergency repair, and a tentative completion date and time.

Contractor shall notify the City when the emergency repair is completed and the road is clear. If an extension of time is required, Contractor must provide a revised tentative Contract Completion Date. If an adjustment to the Contract Sum is required, Contractor shall notify the City of all proposed adjustments necessitated by the emergency and emergency repair.

SECTION 7.08D. Revocation of Permission For Off-Period Work.

The City may revoke permission for off-period work if Contractor endangers the public, an employee, or themselves by violating a safety and health regulation, or fails to maintain an adequate work force and equipment for reasonable prosecution and inspection of such work.
455

99 General Conditions
2026

SECTION 7.08E. Working Shifts.

Two- or three-shift operations may be established as a regular procedure by Contractor upon written permission from the City. Such permission may be revoked if Contractor fails to comply with applicable safety and health regulations, fails to provide for adequate inspection of the Work, or fails to provide sufficient means and equipment, including artificial light, to permit the Work to be carried out safely and appropriately and to permit proper inspection.

SECTION 7.09. TEMPORARY FACILITIES AND SERVICES.

Unless specified otherwise in the Contract Documents, Contractor shall be responsible for providing and maintaining necessary material storage facilities, utilities, field offices, temporary roads, fences, security, etc. for prosecuting the Work. Contractor shall obtain a City of Rocklin hydrant permit at contractor expense prior to connecting to or drawing construction water from fire hydrants.

SECTION 7.10. PROTECTION OF WORK, PERSONS AND PROPERTY.

Contractor shall protect the Work, equipment and materials from damage until completion and acceptance of the Work. Neither the City nor any of its agents assume any responsibility for collecting funds from any person or persons that damages Contractor’s work.

Contractor shall store materials and equipment in accordance with manufacturer’s recommendations and erect such temporary structures as required to protect them from damage. Contractor shall furnish guards, fences, warning signs, walks, and lights, and shall take all other necessary precautions to prevent damage or injury to persons or property.

SECTION 7.11. PROOF OF COMPLIANCE WITH CONTRACT.

When requested by the City, Contractor shall submit properly authenticated proof of Contractor’s compliance with the Contract.

SECTION 7.12. DELAYS.

Contractor shall provide notification to the City for any delays, in accordance with Section

7.13, “Notice of Delays”, of these General Conditions.

SECTION 7.12A. Inexcusable Delays.

Contractor shall not receive any time extensions or additional monetary compensation for inexcusable delays. Inexcusable delays include, but are not limited to, the following:

1. Delays that affect only a portion of the Work but do not prevent or delay the prosecution of controlling items of work nor the completion of the whole Work within the Contract Time.
456

100
General Conditions
2026

2. Delays associated with the reasonable interference of other contractors employed by the City that do not necessarily prevent or delay the prosecution of controlling items of work or the completion of the whole Work within the Contract Time.

3. Delays associated with loss of time resulting from the necessity of submitting plans for the City approval or from City
surveys, measurements,
inspections, and testing.

4. Delays that could have been avoided by the exercise of care, prudence, foresight, and diligence on the part of Contractor or Subcontractors.

SECTION 7.12B. Excusable Delays.

Contractor may be granted an extension of Contract Time for excusable delays, which are those that are determined to be beyond the control of Contractor, impact a controlling item of work, could not be prevented by the exercise of care, prudence, foresight, and diligence, and only to the extent there is insufficient remaining float to accommodate the delay. These excusable delays may include City acts, unusually severe weather or conditions resulting therefrom, Acts of God or of the public enemy, fire, epidemics, pandemics and labor strikes. Material shortages and delays in utility company relocations may be classified as excusable if Contractor produces satisfactory evidence of acting in a timely manner.

Contractor shall not receive any additional monetary compensation due to excusable delays unless the City determines that the excusable delay resulted from a City act, unusual site conditions as set forth in Section 7.06 of these General Conditions, or the discovery of archeological or cultural resources as specified in Section 10.10 , “Archeological and Cultural Resources”, of these General Conditions .

Contractor shall
also not receive any additional monetary compensation due to excusable delays under the following circumstances:

1. Contractor could have reasonably anticipated the delay and avoided the cost impacts of it.

2. When there are two (2) or more concurrent delays and at least one does not qualify for monetary compensation under Section 7.12.

3. The excusable delay does not affect controlling critical path tasks that would delay overall completion of the Work.

SECTION 7.13. NOTICE OF DELAYS.

Contractor shall immediately notify the City in writing delivered by personal delivery, U.S.

Mail First Class, or email, if Contractor foresees any delay in the prosecution of the Work or if Contractor learns of the occurrence of any excusable delay; but in no case shall the written notice be provided to the City later than five (5) Working Days after the occurrence of the event that is the cause of the excusable delay. Contractor shall describe in this notice, the nature and cause of the delay and shall state the probability of the delay occurring (if foreseen ahead of time) so the City may take steps to prevent the occurrence or continuance of the delay and may determine whether the delay is inexcusable or 457

101
General Conditions
2026

excusable, its duration, and its extent. Notification of delays in any other format than described herein, including, without limitation, in progress meetings and regardless of whether noted in the progress meeting minutes, is insufficient to constitute the required and proper notice.

In the event of a continuing delay, Contractor is required to give only one notice.

Within ten (10) Working Days after the Contractor has given notice of the delay, the Contractor shall submit a Time Impact Analysis in accordance with Section 7.18 of these General Conditions that includes both a written narrative and a schedule diagram depicting how the claimed occurrence of an excuseable delay affects other schedule activities and the critical path.

All delays shall be deemed inexcusable unless the City was notified as indicated above and through its investigation found them excusable. Contractor waives any and all claims for time extensions and/or monetary compensation based on delay if notice is not provided as described above. Contractor acknowledges that the City has a strong interest in mitigation of delay impacts and in confirmation of the existence of delay; therefore, Contractor agrees to submit these notices of delay and to waive claims if notice is not submitted as required.

SECTION 7.14. CARELESS DESTRUCTION OF STAKES AND MARKS NO CAUSE FOR DELAY.

If Contractor or Subcontractors destroy stakes and marks causing a delay in the Work, Contractor shall have no claim for damages or time extensions.

SECTION 7.15. TIME OF COMPLETION.

Time is of the essence on this Contract. Contractor shall complete all of the Work called for under the Contract within the Contract Time.

SECTION 7.16. EXTENSION OF TIME NOT A WAIVER.

Time extensions granted for excusable delays or for the execution of extra or additional work shall not operate as a waiver of any of the City’s rights under the Contract.

SECTION 7.17. INCLEMENT WEATHER AND CONTRACT TIME.

Contractor will be allowed a time extension if, in the opinion of the City , inclement or unsuitable weather or its effects prevents working on the current critical path task at the beginning of the shift for at least five (5) consecutive hours, or for at least (5) hours during the shift. (A current critical path task or controlling operation is any feature of the Work (e.g., an operation or activity including settlement, curing periods, and submittal activities) that if delayed or prolonged will delay the time of completion of the Contract.) SECTION 7.18. EXTENSION OF TIME.

Subject to the provisions of Section 7. 12B, compliance with the required contractual notice provisions in Section 7. 13, and subject to submission of a Time Impact Analysis 458

102
General Conditions
2026

(TIA) in accordance with this Section 7.18 s howing the impact on the critical path of the event giving rise to an excusable delay, Contractor will be allowed a time extension to complete the Work equal to the sum of all excusable delays as determined in accordance with Section 7.12 to Section 7.17 of these General Conditions , plus any adjustments in Contract Time due to Change Orders as outlined in Section 9.11 , “Time Extensions for Changes”, of these General Conditions . During such time extension, Contractor will not be charged for extra engineering and inspection or liquidated damages.

Contractor shall provide the City with 3 copies of any TIA. Contractor’s T IA shall include both a written narrative and a schedule diagram depicting how the changed work affects other schedule activities. The schedule diagram shall show how Contractor proposes to incorporate the changed work in the schedule, and how it impacts the current schedule update critical path or otherwise. Contractor is also responsible for requesting time extensions based on the T IA’s impact on the critical path. The diagram shall be tied to the main sequence of scheduled activities to enable the City to evaluate the impact of changed work to the scheduled critical path. Contractor is responsible for all costs associated with the preparation of TI As, and the process of incorporating T IAs into the current schedule update.

If the time extension is compensable, the Contract Sum will be adjusted as set forth in Section 9.09 of these General Conditions.

SECTION 7.19. SUBSTANTIAL COMPLETION.

When Contractor considers the entire Work, or a specific portion of the Work, substantially complete, Contractor shall certify in writing to the City that the Work is substantially complete and request that the City grant substantial completion. Within five (5) Working Days, the City and Contractor shall inspect the Work to determine the status of completion. If the City does not consider the Work ready for its intended use, the City will notify Contractor in writing, giving the City’s reasons. If the City considers the Work ready for its intended use, the City will grant Substantial Completion, and then the City will provide a list of items to be completed or corrected (often referred to as a “deficiency list” or “punch list”) before Final Acceptance and Final Payment. Immediately upon being provided a deficiency list, Contractor shall proceed to correct or complete the items on the list.

Substantial Completion does not bar liquidated damages from being assessed and accruing. Liquidated and other damages may continue to accrue until Completion.

SECTION 7.20. CLEANING UP.

Throughout the construction period, Contractor shall keep the site of the Work in a presentable condition, dispose of any surplus materials, keep roadways reasonably clear of dirt and debris, keep all sidewalk and other pedestrian areas clear of dirt, loose gravel, debris and any tripping hazards, clean out all drainage ditches and structures, and repair any fences or other property damaged during the progress of the Work, to the satisfaction of the City
. When material is disposed of outside of an easement, street, or highway right-of-way, or other City -owned properties, the Contractor shall do so in accordance with the Contract Documents.
459

103
General Conditions
2026

Contractor shall also keep the work site cleaned of all rubbish, excess material, and equipment. All portions of the work shall be left in a neat and orderly condition prior to requesting final inspection. Surplus material shall be disposed of in accordance with Section 18-7, “Surplus Material Disposal”, of the Placer County Specifications. The final inspection will not be made until final clean up has been accomplished.

Construction and demolition debris may be properly disposed of by Contractor using self- haul equipment to deliver the debris to an approved disposal site. Any paid waste/recycling collection or disposal services shall exclusively utilize the City’s designated refuse collection service provider.

SECTION 7.21. FINAL INSPECTION AND FIELD ACCEPTANCE.

Contractor shall notify the City in writing when it believes that it has corrected all items on the deficiency (punch) list and has achieved Completion, and the City shall promptly inspect the Work. Contractor or Contractor's representative shall be present at the final inspection. Contractor will be notified in writing of any further defects or deficiencies and Contractor shall proceed within ten (10) Calendar Days to correct such defects or deficiencies. When again notified that Contractor has achieved Completion, the City will again inspect the Work to ascertain that the corrections are in accordance with the Contract and Completion has occurred. The City may delay additional inspections if the City has reason to believe that Contractor is not making a good faith effort to correct deficiencies. The Engineer , Architect, Consulting Engineer or Project Manager will recommend acceptance of the Work to the Council or designee if it finds all the
corrections acceptable and Completion has occurred; otherwise, the Engineer, Architect, Consulting Engineer or Project Manager shall continue to withhold field acceptance of the work until all deficiencies on the deficiency (punch) list are corrected and Completion achieved.

SECTION 7.22. FINAL ACCEPTANCE AND NOTICE OF COMPLETION.

Upon Completion of the Work, including but not limited to acceptance of O& M manuals, Record Drawings, test reports, the Guarantee Form, and any other close-out documents required by the Contract Documents, the Engineer, Architect, Consulting Engineer or Project Manager will recommend to the Council that it accept the Contract as complete.

Upon acceptance by the Council, a Notice of Completion will be recorded with the County Recorder within fifteen (15) Calendar Days. Acceptance by the City Council shall cause the commencement of warranty periods. Acceptance shall not relieve Contractor from the responsibility of completing or correcting any work, nor from the responsibility to correct any patent or latent defects in the Work.

SECTION 7.23. WARRANTY WORK.

Should any defects or deficiency in material, equipment or workmanship, such as faulty materials, poor workmanship, defective equipment, or any other reason that can be attributed to Contractor’s performance, become apparent during any warranty period, the City shall notify Contractor in writing of the defect before expiration of the warranty period.

If so notified, Contractor has a duty to immediately correct, or immediately and satisfactorily commit to correct, the defect or deficiency to meet the Contract requirements 460

104
General Conditions
2026

at Contractor’s sole expense. This duty to correct does not expire for any reason, including but not limited to expiration of the warranty period. A new warranty period, equivalent to the original warranty period, will apply to all corrected deficiencies.

The City is hereby authorized to make such needed repairs if Contractor fails to undertake, with due diligence, the needed repairs within ten (10) Calendar Days after Contractor is given written notice of such failure and without notice to the surety; and Contractor shall pay the entire costs for the City’s work. However, in case of an emergency where, in the opinion of the City, delay would cause serious loss or damages or a serious hazard to the public, the City may immediately make repairs or take other action without prior notice to Contractor or surety; and Contractor shall pay the entire costs for the City’s work.
461

105
General Conditions
2026

ARTICLE 8. MEASUREMENT AND PAYMENT
SECTION 8.01. BASIS AND MEASUREMENT OF PAYMENT QUANTITIES.

It is Contractor ’s responsibility to measure and/or compute the quantities of work completed, subject to verification by the City , under the terms of the Contract. In computing quantities, the length, area, solid contents, number, weight, or time as specified in the Contract or the Schedule of Values shall be used.

SECTION 8.01A. Unit Price Contracts.

Payment for all work bid at a price per unit of measurement will be based upon the actual quantities of work as measured upon completion. The Estimated Quantities provided in the Bid Documents are for comparative bidding only. The City does not express or imply that the actual amount of work or materials will correspond to the Estimated Quantities.

Contractor shall make no claim nor receive any compensation for anticipated profits, loss of profit, damages, or any extra payment due to any difference between the amount of work actually completed, or materials or equipment furnished, and the Estimated Quantities. See also Section 9.13, “Contract Change Order”, of these General Conditions.

SECTION 8.01B. Lump Sum or Job Contracts.

Progress Payments will be based on the Schedule of Values prepared by Contractor and approved by the City prior to acceptance of the first p rogress payment request (see Section 8.05 , “Progress Payment Procedures”, below). If requested by the City , Contractor shall furnish full copies of subcontracts showing actual costs. The Schedule of Values shall be consistent with the baseline progress schedule prepared by Contractor pursuant to Section 7.05B, “Progress Schedules”, of these General Conditions.

SECTION 8.01C. Payment for Mobilization.

Mobilization shall consist of preparatory work and operations, including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the site; for the establishment of all offices, buildings, and other facilities necessary for the Work; and for all other work and operations which must be performed, or costs incurred, prior to beginning the Work.

Payment for mobilization will be as follows:

1. Mobilization Not a Pay Item
When the Contract does not include a separate pay item for mobilization, full compensation for mobilization will be included in the Contract lump sum price or in the prices paid for the various items of work in a unit price contract, and no additional compensation will be paid.

2. Mobilization a Pay Item
When the Contract or accepted Schedule of Values includes a separate item for mobilization, payment for mobilization will include full compensation for the furnishing of 462

106
General Conditions
2026

all labor, materials, tools, equipment, administrative costs, and incidentals for mobilization.

The City will pay no greater than five percent (5%) of the Contract Sum as a separate pay item for mobilization. In the event Contractor submits a mobilization pay item greater than five percent (5%) of the Contract Sum, the City will pay any excess mobilization amount with the final progress payment.

Absent City approval, the City will not pay additional mobilization compensation for work under a Change Order.

Payment for mobilization shall be subject to retention per Section 8.07, “Retention”, of these General Conditions.

SECTION 8.02. SCOPE OF PAYMENT.

SECTION 8.02A. General.

Compensation under the terms of the Contract shall be full payment for the Work, including loss or damage arising from the nature of the Work, action of the elements, or unforeseen difficulties encountered during the prosecution of the Work and until its final acceptance; and all risks connected with the prosecution of the Work.

SECTION 8.02B. Unit Price Contract.

Progress payments will be made based upon the unit price bid and measured quantities for work completed, plus work completed on approved Change Orders. For compensation for alterations in quantities of work, including deviations greater than twenty -five percent (25%), see Section 9 .07B, “Payment for Changes – Unit Prices”, in these General Conditions.

SECTION 8.02C. Lump Sum or Job Contract.

Progress payments will be based upon the approved Schedule of Values for work completed, plus work completed on approved Change Orders.

SECTION 8.02D Final Pay Items
An item designated as a Final Pay Item in the Contract shall be paid for as specified in Section 9-1.02C, “Final Pay Item Quantities”, of the State Specifications.

SECTION 8.02E. Allowances.

Allowances may be included in the Bid Form for materials and/or work that may be added during the course of the Contract. The Allowance may be used in whole, in part, or not at all as determined by the City. Whenever costs of the Work included in the Allowance item are more or less than the specified Allowance amount, the Contract Sum will be adjusted accordingly by Contract Change Order. Contractor shall make no claim nor receive any compensation for anticipated profits, loss of profit, damages, or any extra payment due to 463

107
General Conditions
2026

any difference between the amount of work actually completed, or materials or equipment furnished, and the Estimated Quantities for the Allowance.

SECTION 8.02F. Payment for Material Not Incorporated in the Work.

No Progress payments will be made for materials and equipment not incorporated in the Work, unless specifically set forth in the Special Provisions or authorized by the City .

SECTION 8.03. WORK TO BE DONE WITHOUT DIRECT PAYMENT.

Compensation for any portion of the Work not specifically identified in the Bid Form or Schedule of Values is understood to be included in the price for other items, unless specified in the Special Provisions as extra work. No additional compensation is allowed for additional shifts or premium pay necessary to ensure that the Work is completed within the time limits specified in the Contract.

SECTION 8.04. PAYMENT FOR USE OF COMPLETED PORTIONS OF WORK.

If the City occupies or uses a portion of the Project under Section 4.1 3, “Use of Completed Portions”, of these General Conditions, before it accepts Completion of the Work, Contractor will only be compensated in accordance with this Article 8. No final payment shall occur for a limited portion of the work.

SECTION 8.05. PROGRESS PAYMENT PROCEDURES.

No progress payment will be made when, in the judgment of the City, the Work is not proceeding in accordance with the provisions of the Contract or when the total work done since the last progress payment amounts to less than one thousand dollars ($1,000).

Unless otherwise agreed to at the preconstruction meeting or identified in the Special Provisions, Contractor shall submit in writing monthly for City review an estimate of the total amount and value of work done, including that done under approved Change Orders, and the acceptable materials furnished and incorporated in the work completed through the last day of the previous pay period. The Bid Form or Schedule of Values shall be used to prepare a progress payment request for the items, or portions of items, of the Work completed during the monthly progress period.

Unless specified otherwise in the Special Provisions, any progress payment request must be accompanied by (1) an updated Progress Schedule that complies with the Contract; (2) record drawing update confirmations; ( 3) a conditional lien release in the form prescribed by law warranting that title to all work, labor, materials and equipment covered by the request is free and clear of all liens, claims, security interests or encumbrances; and (4) unconditional lien releases for all work through the prior progress payment lien releases. If Contractor fails to submit these documents with the progress payment request, then the City, in its sole discretion, may withhold part of the progress payment or reject the progress payment request with an explanation in writing of the reason. Contractor may resubmit the progress payment request with the required documents. The City has no obligation to process the progress payment request or make a progress payment if Contractor fails to provide these required documents. 464

108
General Conditions
2026

If the required documents are submitted with the progress payment request, then the City shall review any progress payment request submitted by Contractor to determine its accuracy and validity. Any payment request determined not to be a proper payment request suitable for payment shall be returned to Contractor as soon as practicable, but not later than seven days, after receipt, along with a document stating the reasons why the payment request is not proper. Once the City has an undisputed and properly submitted payment request from Contractor, the progress payment shall be made within 30 days of its submission.

Once the City agrees with Contractor as to the amount of Work completed as of the date of the progress payment request, the City shall deduct the following from the estimated total value of that amount of Work: All previous payments, the retention previously withheld pursuant to Section 8.07 , “Retention”, of these General Conditions , and other withholdings as permitted by the Contract. The City will then approve the balance for payment to Contractor , with retention being withheld from that approved payment as described in Section 8.07 of these General Conditions.

The payment of a progress payment or the acceptance thereof by Contractor does not constitute acceptance by the City of any portion of the Work, and does not reduce Contractor’s liability to replace unsatisfactory work, material, or equipment for any or the Work, whether or not completed. Approval by the City of a progress payment request that contains an inadvertence or error by Contractor will not release Contractor or Contractor’s surety from damages arising from the work covered by the approved payment request or from enforcement of every provision of the Contract. The City also has the right to correct any error made in any p rogress payment and may withhold as much payment as necessary to correct the error in later progress payments.

SECTION 8.06. INSPECTION AND PROGRESS PAYMENTS NOT A WAIVER OF CONTRACT PROVISIONS.

No inspection, order, measurement, approval, modification, payment, acceptance of work or material (including, but not limited to, acceptance of the entire Work), time extension, or possession of the Work or any part thereof shall be a waiver of any of the terms and conditions of the Contract, the powers reserved by the City , or any right of the City to damages or to reject the Work in whole or part. No breach of this Contract shall be construed a waiver of any other or subsequent breach. All remedies provided in the Contract shall be cumulative and shall be in addition to all other rights and remedies that may exist at law or in equity.

SECTION 8.07. RETENTION.

SECTION 8.07A. Retention to Ensure Performance.

The City will retain five percent (5%) of each approved progress payment to ensure performance under the Contract. The parties acknowledge that some of the purposes of retention under this Contract are to encourage Contractor to reach Completion quickly, to ensure that Contractor completes the Work in its entirety, and to provide funds from which the City
m ay withhold for disputes, costs and claims under Section 8.08 , “Withholdings/Denial of Progress Payment Request”, of these General Conditions. 465

109
General Conditions
2026

Retention will be held by the City until at least thirty-five (35) Calendar Days, but no more than sixty (60) Calendar Days after recording of the Notice of Completion. However, the City may continue to withhold some or all of the retention beyond 60 days to the extent that any disputed amounts or Stop Payment Notices or liquidated damages exist, in which case the City may withhold 150% of the disputed amount, 150% of the amount of liquidated damages, and 125% or more of outstanding Stop Payment Notices and full amount of liquidated damages.

SECTION 8.07B. Non-Compliance.

In addition to the five percent (5%) payment retention discussed above, the City may also retain portions or all of a progress or final payment for Contractor’s noncompliance with the Contract in an amount deemed appropriate by the City .

SECTION 8.07C. Substitution of Securities.

At the request and expense of Contractor , in accordance with Public Contract Code Section 22300, in lieu of the City withholding the five percent (5%) retention defined in Section 8.07 of these General Conditions , Contractor may: (1) substitute a deposit of securities at least equivalent to the retention to be paid, or (2) request that the City pay the withheld retention directly to an escrow agent. If Contractor elects either option, Contractor and the City shall enter an escrow agreement in the exact form set forth in Public Contract Code Section 22300.

SECTION 8.08. WITHHOLDINGS/DENIAL OF PROGRESS PAYMENT REQUEST.

The City may deny a progress payment request and/or withhold amounts from a progress payment and/or withhold a release of retention for any of the following reasons:
• Stop payment notices filed pursuant to Civil Code Sections 9350 et seq., including but not limited to a reasonable amount to provide for the City’s reasonable cost (including but not limited to attorneys’ fees and experts’ fees) of litigation based on the stop notice;
• Fines levied against Contractor or the Work by the City or other entities; • Third party claims against Contractor or the City
arising from the acts or omissions
of Contractor or its subcontractors;
• Defective Work not remedied;
• Previous overpayments to Contractor;
• Failure by Contractor to make payments properly to employees or Subcontractors for labor, materials, or equipment;
• Any portion of the Work retained in accordance with Section 5.22, “Right to Retain Imperfect Work”, of these General Conditions;
• The Work may not be completed for the unpaid balance of the Contract sum; • The Work may not be completed within the Contract Time and the City incur actual
and/or liquidated damages;
466

110
General Conditions
2026

• Review of excessive resubmittals under Section 5.10B of these General Conditions, and excessive inspections or tests;
• Replacement of survey stakes and excessive survey work; • Failure by Contractor to maintain and update Record Drawings; • Damage to the City or another contractor;
• Failure by Contractor to perform the Work in accordance with the Contract; • Failure by Contractor to submit the necessary documents with a progress payment request;
• Cost of insurance purchased by the City due to cancellation or reduction of coverage of Contractor’s insurance;
• Failure by Contractor to make proper submissions under the Contract; • Any violation or non-compliance with Contractor’s legal responsibilities (see Article 6, “Legal Relations and Responsibilities” of these General Conditions ), including, without limitation, withholds for wages adjustments in accordance with the California Labor Code and any fines incurred by the City as a result of Contractor’s actions; and/or
• Any amounts otherwise necessary to protect the City ’s inter ests and/or compensate the City for past, present and future damages.

In addition to withholding a reasonable amount based on the above grounds, the City may withhold an additional 50% of that reasonable amount from a progress payment or release of retention; except that it may withhold an additional 25% or more of the Stop Payment Notice amount to provide for its reasonable cost (including but not limited to attorneys’ fees and experts’ fees) of any litigation based on a Stop Payment Notice.

If, on Completion or termination of the Contract or termination of Contractor’s control over the Work, sums withheld from Contractor are insufficient to cover the City’s charges against Contractor, the City has the right to recover the balance from Contractor or Contractor’s surety.

SECTION 8.09. DEDUCTIONS FOR IMPERFECT WORK.

For any portion of the Work, materials or equipment retained in accordance with Section

5.22 of these General Conditions , the City will deduct from a Progress Payment a reasonable amount to represent the decreased or lost value to the City .

SECTION 8.10. LIQUIDATED DAMAGES FOR DELAY.

If the Work is not completed by Contractor in the time specified in the Contract Documents, or within any period of extension authorized pursuant to these General Conditions, Contractor acknowledges and admits that the City will suffer damage, and
that it is impracticable and infeasible to fix the amount of actual damages. Therefore, it is agreed by and between Contractor and the City that Contractor shall pay to the City as fixed and liquidated damages, and not as a penalty, the sum specified in the Contract Documents for each Calendar Day of delay until the date of Completion, and that both 467

111
General Conditions
2026

Contractor and Contractor’s surety shall be liable for the total amount thereof, and that the City may deduct Liquidated Damages from any monies due or that may become due to Contractor. If it appears during the course of construction that Contractor is behind schedule and the imposition of liquidated damages is likely, or if liquidated damages begin to accrue prior to the time for final payment, the City may, at its discretion, withhold the amount accrued from any progress payment that would otherwise be due. This right to withhold funds is in addition to the City’s other rights under the Contract Documents.

This liquidated damages provision shall apply to all delays of any nature whatsoever, save and except only delays found to be excusable or time extensions granted by the City.

Pursuant to Government Code Section 4215, Contractor shall not pay fixed and liquidated damages for delay in completing the Project caused by the failure of the City or the utility
district(s) facilities located on the Project site to provide for removal or relocation of such facilities.

Payment by the City of any progress payments after liquidated damages have accrued shall not constitute a waiver by the City of its right to claim liquidated damages.

If the Contract , Contractor’s control over the Work or Contractor’s right to proceed is terminated for cause, then Contractor shall be liable to the City for liquidated damages for all periods of time from the scheduled Contract Completion Date at the time of such termination, as that date may be adjusted by any extensions of time to which Contractor is entitled, until the Date of Completion.

SECTION 8.11. FINAL ESTIMATE AND PAYMENT.

Subsequent to field acceptance as detailed in Section 7. 21 of these General Conditions and submission of all required close- out documents referenced in Section 7.22 of these General Conditions, and within thirty (30) Calendar Days after field acceptance Contractor shall provide a proposed final payment request, segregated as to Contract item and Change Order work. Contractor shall submit all previously unsubmitted documents required by the Contract with the request; otherwise the City has the right to reject the
request and require submission of these documents.

The City will review the properly submitted proposed final payment request and, after withholding for all issues as permitted by Sections 8.08, 8.09 and 8.10 of these General Conditions and making other corrections as necessary, shall return its approved f inal payment request as modified, within fifteen (15) Calendar Days of receipt. All progress payments shall be subject to correction in the final payment. If Contractor fails to file a final payment request within the time allotted, the City may create and approve one based on the best information available to it.

Within fifteen (15) Calendar Days after the approved final payment request is submitted to Contractor, Contractor shall submit back to the City a written approval of said request or a written statement of exceptions to be considered a “closeout” claim. Contractor’s statement of exceptions shall be in sufficient detail for the City to ascertain the basis and
amount of the exceptions. Not later than thirty (30) calendar days after Contractor returns 468

112
General Conditions
2026

the approved final payment request or statement of exceptions to the City, Contractor shall comply with Section 9.17 of these General Conditions for any exceptions it intends to pursue as a claim, and provided it has complied with all other contract requirements for notice and presentation of claims, or its claim(s) will be deemed waived.

Any claim of Contractor or Subcontractors or suppliers with respect to the performance or breach of the Contract or any alterations thereof (except for payment of the balance of the Contract Sum as set forth in the final payment request) not specifically set forth in the statement of exceptions, is waived by Contractor. If Contractor fails to file a statement of exceptions within the time allowed, Contractor waives its right to submit a statement of exceptions and the approved final payment request will be deemed to as accepted and approved by Contractor.

The City
shall process the final payment and a release of retention in accordance with the approved final payment request. The payment of undisputed sums due for the final payment, and excluding any sums withheld for Stop Payment Notices, shall be made within thirty -five (35) days of Contractor ’s acceptance of the approved final payment request or within sixty (60) days after the recording of the Notice of Completion, whichever is later. The release of retention shall be made in accordance with Section 8.07 of these General Conditions. If Contractor submits a timely statement of exceptions, then the City shall process these payments as a semifinal action; otherwise the payment shall be considered final.

The City
shall respond in accordance with the provisions of Section 9. 18, “ Engineer’s Decision”, of these General Condit ions, with its final decision regarding the claims and exceptions set forth by Contractor. Should the City’s final decision grant some or all of Contractor’s claims or exceptions, then to the extent necessary a supplemental final payment and/or supplemental final release of retention shall be processed within thirty (30) days.

Any claim or exception set forth by Contractor for which Contractor did not follow the required claim procedures in the Contract Documents shall be disallowed; by failing to follow the required claim procedures prior to Contractor’s written statement of claims and exceptions, Contractor will have waived all rights to compensation (whether money or time) related to such claim or exception. If not already expired, the running of time for presenting a Government Code claim (see Government Code sections 900 et seq.) shall be tolled from the time of Contractor’s timely statement of exceptions until the City’s final decision on the statement of exceptions.

SECTION 8.12. FINAL PAYMENT TO TERMINATE LIABILITY OF CITY.

If Contractor fails to timely submit a statement of exceptions, Contractor’s acceptance of the final payment and final release of retention shall release the City and the City ’s officers, officials, agents, employees, members, volunteers, affiliates, and their duly authorized representatives from all claims or liability on account of all Work performed or any alterations thereof. If Contractor timely submits a statement of exceptions, Contractor’s acceptance of the semifinal payment and semifinal release of retention shall release the City
and the City ’s officers, officials, agents, employees, members, volunteers, affiliates, and their duly authorized representatives from all claims or liability 469

113
General Conditions
2026

on account of Work performed or any alterations thereof, except unresolved items set forth in the statement of exceptions.

SECTION 8.13. DISPUTED PAYMENTS.

The City will decide disputes regarding payments under the Contract according to the procedures set forth in Article 9, “Changes and Claims”, of these General Conditions. The decision of the City will be final.
470

114
General Conditions
2026

ARTICLE 9. CHANGES AND CLAIMS
SECTION 9.01. AUTHORITY FOR CHANGES.

The City reserves the broad right to order or direct corrections, alterations, additions, modifications, deletions or other changes as required for the proper completion of the Work. The order or directive may be issued prior to the final acceptance of the Contract without voiding the Contract, without notice to Contractor ’s sureties, and in accordance with the provisions of Section 9.02, “Ordering of Changes”, of these General Conditions.

Contractor shall not perform corrections, alterations, additions, modifications, deletions, or other changes to the Work without a written directive or order from the City, in accordance with Section 9.02 of these General Conditions . Payment for changed or extra work will not be made without the City’s written authorization.

SECTION 9.02. ORDERING OF CHANGES.

The City may order or direct, including, without limitation, through a Field Directive or Construction Change Directive, a change, in writing, during the course of the Work, and Contractor shall immediately comply with the order or directive. Changes to the Work shall in no way affect, vitiate, or make void the Contract or any part thereof, except that which is necessarily affected by such changes and is clearly the evident intention of the parties to the Contract.

Changes to the Work may be initiated as described in Section 4.06 , “Field Directives or Other Written Directives”, of these General Conditions . If the City and Contractor agree that compensation in the form of an adjustment to the Contract Sum and/or the Contract Time is required, then the adjustment will be formalized in a Change Order, in accordance with Section 9.13, “Contract Change Order”, of these General Conditions . Failure of the City and Contractor to agree to terms of a Change Order based on an order or directive shall not relieve Contractor of its obligation to complete all work specified in the order or directive.

SECTION 9.03. CONSTRUCTION INCENTIVE CHANGE PROPOSAL (CICP).

SECTION 9.03A. General.

The Construction Incentive Change Proposal (CICP) Program provides a program for Contractor to use its expertise to improve Contract performance to create an overall reduction in the Contract Sum. Proposing to delete work is not a CICP. Deleted work is addressed in Section 4.10 , “Deleted Items,” in these General Conditions . The CICP Program shall not apply to City contracts of less than one hundred thousand dollars ($100,000). Contractor and Subcontractors may participate in the CICP Program.

Participation of Subcontractors shall be through Contractor , and Contractor and Subcontractors must agree upon the sharing arrangement; written evidence of such agreement must be submitted with the CICP.
471

115
General Conditions
2026

Contractor shall proceed with the Work as scheduled until Contractor receives the City’s written approval of a CICP. The City shall be the sole judge of the acceptability of a CICP and of the net capital cost reduction from the adoption of all or any part of the CICP.

SECTION 9.03B. Description.

A CICP is a formally written proposal for a Contract Change Order. A CICP must be initiated, developed, and identified as such by Contractor or Subcontractor through Contractor as identified in Section 9.03A . A CICP must result in a net capital cost reduction while causing no increase in the total life cycle cost of the Project and shall comply with the following conditions:
• Required function, reliability, and safety of the Project will be maintained without detracting from the life expectancy or increasing maintenance requirements. • The proposed change shall not cause undue interruption of the Work, nor shall it extend the Contract Time.
• The proposed change shall comply with all applicable permits, regulations, and code requirements, and any other requirements as set forth in the Contract. The proposed change shall not involve payment of royalties by the City to Contractor.

SECTION 9.03C. Submittal.

Contractor shall submit a brief description of the proposed CICP prior to preparing the detailed submittal as outlined below.

A CICP submittal must contain pertinent information in supporting documents for City evaluation. As a minimum, the following information shall be submitted:

1. Name of individuals associated with the development and preparation of the CICP.

2. A detailed description and duly signed plans and specifications showing work as presently designed and the proposed changes.

3. A clear identification of all advantages and disadvantages for each proposed change.

4. A detailed procedure and schedule for implementing the proposed change.

This detailed procedure and schedule shall include all necessary Contract amendments. Also indicated must be the latest date that the CICP can be approved for implementation.

5. A summary of estimated costs, including the following:
a. Project construction costs before and after the CICP. This shall be a detailed estimate identifying the following items for each trade involved in the CICP:
• Quantities of material and equipment.
• Unit prices of materials and equipment.
• Labor hours and rates for installation.
472

116
General Conditions
2026

• Subcontractor and prime Contractor markups.
• Operation and maintenance costs before and after the CICP. • Cost for implementing the CICP not included elsewhere. b. Contractor’s share of the savings based on the sharing provision in Section

9.03E, “Sharing Provisions and Formula,” of these General Conditions. c. Other data as required by local permits and regulations and code requirements as set forth in the Contract.

6. Time required for execution of the proposed change.

To the extent indicated herein, Contractor may restrict the City’s use of any CICP or the supporting data submitted pursuant to the CICP program. Suggested wording for inclusion in CICPs is as follows:
“This data furnished pursuant to the construction incentive clause of the Contract shall not be disclosed or duplicated in whole or in part beyond what is necessary to accomplish the review. This restriction does not limit the City ’s right to use the information if it is available from any source without limitations. The City has the right to duplicate, use and disclose any information if the CICP is accepted.”
The City may modify, accept, or reject the CICP. However, if the CICP is modified or not acted upon within the time allotted in the proposal, or if it is withdrawn or rejected, the City

will not be liable for Contractor’s cost of developing the CICP.

SECTION 9.03D. Acceptance.

The City will use the processing procedure specified for Change Orders in Section 9.13 , “Contract Change Order,” in these General Conditions, if a CICP is accepted. The City’s written approval of the CICP is required. If the CICP is rejected, Contractor shall not appeal the decision.

SECTION 9.03E. Sharing Provisions and Formula.

Upon acceptance of the CICP, Contractor will receive 50 percent (50%) of the Net Capital Savings based upon the following formula:

Net Capital Savings = Contract Cost Prior to CICP – (Revised Contract Cost After CICP + CICP Development Cost + CICP Implementation Cost) Contractor’s development cost is limited to that directly associated with the preparation of the CICP package. Development costs will be reimbursed after approval. However, the City will reject costs that cannot be satisfactorily substantiated.

The CICP implementation costs include, when appropriate the City’s engineering costs for reviewing and redesigning the changes. However, City costs for processing the CICP are excluded.
473

117
General Conditions
2026

SECTION 9.04. PROSECUTION OF CHANGES TO THE CONTRACT.

If directed by the City , within fourteen (14) Calendar Days of issuance of a Request for Proposal, Contractor shall provide a Proposed Change Order with a cost and/or time proposal prepared in accordance with the requirements of this Section, and Sections 9.07 and 9.11 of these General Conditions . Contractor’s Proposed Change Order shall indicate the amount to be added or deducted from the Contract Sum, supported by complete details of all Contractor, Subcontractor, vendor or supplier costs per Section

9.05, “Cost and Pricing Data”, of these General Conditions.

If Contractor does not submit a Proposed Change Order within fourteen (14) Calendar Days, and unless the City is otherwise notified within fourteen (14) Calendar Days of a potential cost impact, Contractor agrees to perform the work described in the change request with no additional compensation.

If the change causes a change in the monetary compensation or contract time the City will issue a Change Order in accordance with Section 9.13 , “Contract Change Order” of these General Conditions. If a Field Directive or other written order is issued on a force account basis, Contractor must immediately begin keeping records in accordance with Section 9.07C , “Force Account”, of these General Conditions . When the City and Contractor cannot agree on the credit for work deleted by a written order, the City’s estimate will be deducted from the Contract Sum, unless Contractor presents proof prior to the final payment that the City’s estimate is in error.

If agreement for a change in the Work is reached regarding payment, but not a time adjustment, the City shall have the right to direct Contractor to proceed with the change at the agreed price. The impact of the changed work on the project schedule will be considered by the City in accordance with Section 9.11, “Time Extension for Changes”, of these General Conditions.

Failure of the parties to reach agreement regarding the costs and time of the performing the change in the Work and/or any pending protest shall not relieve Contractor from performing the change in the Work promptly and expeditiously. The City may unilaterally direct Contractor in writing to perform changes in or additions to the scope of the Contract. Contractor shall perform such work and shall be compensated pursuant to the provisions of Section 9.07, “Payment for Changes”, of these General Conditions.

SECTION 9.05. COST AND PRICING DATA.

Cost and pricing data submitted by Contractor shall be true, complete, accurate, and current. The City may require a formal certification to verify Contractor-submitted cost and pricing data. Upon request by the City, Contractor shall provide the following information to support its submitted costs:

1. Copy of original quotations, purchase order or invoices to verify costs included in original bid.

2. Copy of all quotations, purchase order or actual invoices to support new costs submitted.
474

118
General Conditions
2026

3. Copy of all subcontracts.

4. Copy of all employee time records and wage rates paid.

5. Copy of all insurance and bond costs resulting from change.

6. Copy of all quantity takeoff sheets for materials, labor and equipment.

7. Certified payroll records.

8. Certified composite wage rate statements including employees base rate and Contractor’s contributions for fringe benefits, subsistence and travel.

9. A list of equipment with manufacturer’s name and model number and the alphanumeric designation used in the Equipment Rental Rates prepared by the California Department of Transportation.

10. Invoices for all rental equipment.

11. Other information, as required, to document the labor, equipment and materials used.

Additional requirements for cost and pricing data may also be included in the Special Provisions. The City shall have access to the records supporting such cost and pricing data in accordance with the Section 9.06, “Access to Records”, of these General Conditions.

SECTION 9.06. ACCESS TO RECORDS.

Upon reasonable notice and during normal business hours, the City shall have access to Contractor’s and Subcontractors’ records for the purpose of verifying, auditing, and evaluating the accuracy of cost and pricing data submitted by Contractor . “Records” as used in this Section shall include, but not be limited to: original estimates, subcontract agreements, purchase orders, books, documents, accounting records, papers, project correspondence, project files, and scheduling information necessary to determine the direct and indirect costs, job site, area and home office overhead, delay and impact costs.

Records shall include the original Bid and all documents related to the Bid and its preparation, the as -planned construction schedule and all related documents. Such access shall include the right to examine and audit such records and make excerpts, transcriptions, and electronic and/or paper copies at the City’s cost.

SECTION 9.07. PAYMENT FOR CHANGES.

The method of payment agreed upon by Contractor and the City, or selected by the City at its sole discretion in the absence of any other agreement, shall be set forth in the Request for Proposal or in the written order directing the change.

The three methods of payment are as follows:

SECTION 9.07A. Lump Sum Price.

Contractor shall submit a lump sum price proposal. The proposal shall include an estimate of labor, material, equipment, Subcontractor costs, material supplier costs, and 475

119
General Conditions
2026

any surcharges and/or markups as allowed in Section 9.08, “Markups for Changed Work” in these General Conditions.

In the event that the parties are unable to agree as to the reasonable costs and time to perform the change in or addition to the Work based upon Contractor's proposal and the City does not elect to have the change in the Work performed on a time and material basis, the City shall make a unilateral determination of the reasonable cost and time to perform the change in the Work, based upon their own estimates, Contractor 's submission, or combination thereof.

SECTION 9.07B. Unit Prices.

If payment for Contract work is based on unit prices, payment for changed work will be made based on actual quantities of work done at the unit prices contained in the Contract or unit prices otherwise agreed upon by the City and Contractor if none are contained in the Contract. Payment for changed work based on Contract or agreed upon unit prices includes the full cost of the item of work including profit and overhead; and no additional payment or adjustment will be allowed. If the final quantity of any item of work required under the Contract varies from the Engineer’s Estimate by twenty -five percent (25%) or more, or if part of the Work is eliminated in its entirety, in the absence of an executed Change order specifying the compensation to be paid, compensation will be adjusted in accordance with Section 9-1.06, “Changed Quantity Payment Adjustments”, of the State Specifications
.

SECTION 9.07C. Force Account.

In the absence of either an agreed lump sum price or unit prices for the change, the City may direct Contractor to proceed with the changed work on a force account basis.

Contractor shall keep and present, in a form acceptable to the City , a complete and correct accounting of all costs associated with the change, including all pay records, vouchers, invoices, etc. Contractor will be paid for labor, materials, and equipment actually used during the performance of the changed work as specified in this Section of these General Conditions in Sections 9.07C.1, “Labor”, 9.07C.2, “Materials”, and 9.07C.3, “Equipment”; plus the percentages stipulated in Section 9.08 , “Markups for Changed Work”.

To facilitate agreement on direct craft labor hours, construction equipment hours, and material quantities, Contractor shall notify the City not less than four (4) hours prior to starting force account work. Contractor shall submit Daily Work Reports (DWR’s) for signature not later than 9:00 a.m. the day following performance of any force account work. DWR’s shall list names of all Contractor’s staff, the staff person’s craft or trade, all craft or trade labor hours, and all material and construction equipment used. Contractor shall use the DWR’s in preparing billings for force account work.

SECTION 9.07C.1. Labor.

Contractor will be paid the cost of direct labor (foreperson and below) used in the actual and direct performance of the changed work including working foreman when authorized by the City . Except as otherwise provided, Contractor will receive no additional 476

120
General Conditions
2026

compensation for overtime work without prior written authorization from the City. The cost of labor will be the sum of the following:

SECTION 9.07C.1(a). Actual Wages.

Charges for labor will be Contractor ’s actual payroll costs for labor of any classification, including employer payments to or on behalf of the workers for health and welfare, pension, vacation, and similar purposes.

SECTION 9.07C.1(b). Labor Surcharge.

A twenty-six percent (26%) surcharge for taxes, insurance, and all other payments made to or on the behalf of the employee shall be added to the actual wages.

SECTION 9.07C.1(c). Subsistence and Travel.

The City will pay Contractor for actual subsistence and travel allowance costs associated with the changed work required by labor agreements or acceptable to the City .

Documentation must be provided to the City.

SECTION 9.07C.2. Materials.

Payment will be for the purchaser’s actual cost of supplier or vendor furnished materials.

If Contractor does not furnish satisfactory evidence of the cost of such materials, the cost will be the lowest current wholesale price at which such quantities of materials are available and delivered to the job site. The City reserves the right to purchase materials for the changed work; Contractor shall have no claims for costs or profit on such materials.

SECTION 9.07C.3. Equipment.

The prices paid for equipment directly and solely required for performance of the changed work will be those listed in the current edition of the Caltrans publication, “Labor Surcharge and Equipment Rental Rates”. If the equipment is not shown in this publication, Contractor shall be paid such rental rates as are agreed upon by Contractor and the City prior to use of the equipment, plus thirty -three and one- third percent (33- 1/3%) for the cost of fuel, oil, lubrication, and field repairs and maintenance. In no case shall the hourly rental rates exceed those of established distributors or equipment rental agencies serving the area.

The rate paid for the use of equipment constitutes full compensation to Contractor for all costs, including fuel, power, oil, lubrication, supplies, small tools, small equipment, necessary attachments, repairs and maintenance of any kind, depreciation, storage, insurance, labor (except for equipment operators) and any and all costs to Contractor incidental to the use of such equipment for the changed work.

Payment will not be made for the equipment while it is inoperative due to breakdowns or for time in which no changed work was performed. Payment for rentals will include time required to move equipment to the changed work from the nearest available rental source 477

121
General Conditions
2026

and to return it to the source. However, no moving, loading, or transportation costs will be paid if the equipment is used for any other portion of the Work.

Individual tools and pieces of equipment having replacement value of five hundred dollars ($500) or less shall be considered tools or small equipment and no payment will be made for those pieces of equipment.

SECTION 9.07C.4. Subcontracts.

Subcontract costs shall be the actual cost to Contractor for work performed by a Subcontractor. The provisions of this Section 9.07C , “Force Account”, apply to the computation of subcontract costs. Subcontractors shall compute markups per the Section

9.08, “Markups for Changed Work”, of these General Conditions.

SECTION 9.08. MARKUPS FOR CHANGED WORK.

Only the direct costs directly attributable to the performance of the changed work shall be allowed. All other costs shall be included in the allowed markups, including, but not limited to, profit, home office and field overhead, jobsite indirect costs, extended overhead, jobsite office personnel, general field superintendence, general engineering, supervision of labor, bond and insurance premiums, and general field expense, and shall constitute full compensation for all costs not included as actual labor, materials, equipment, or Subcontractor costs. Markups for changed work shall not exceed the following:

Labor 25%
Materials 15%
Equipment Rental 15
%
Bonds and Insurance 2%
Contractor or Subcontractor, whomever actually performs the changed work, may add the markups to the total of allowable costs. When a Subcontractor performs work, Contractor and any higher tiered Subcontractor may add as mark -up to the total of allowable costs an amount not to exceed five percent (5%), subject to the limitations of this Section.

When the City is entitled to credit for deleted work, a ten percent (10%) credit for deleted overhead of Contractor or Subcontractor, as applicable, will be added to such credit.

SECTION 9.09. COMPENSABLE EXCUSABLE DELAYS.

Payments will be made as follows for compensable excusable delays, as defined in Section 7.12B, “Excusable Delays”, of these General Conditions. Contractor waives any and all monetary compensation for excusable delays other than the items listed below.

SECTION 9.09A. Construction Equipment.

Compensation will be paid for construction equipment idle as a result of a compensable excusable delay to the extent costs are incurred. The prices paid for equipment will be those in the current edition of the Caltrans publication, “Labor Surcharge and Equipment Rental Rates”, with the following modifications:
478

122
General Conditions
2026

• The right-of-way delay factor for each classification of equipment will be applied to the rental rate.
• Compensation will be provided for the actual time of the delay, but not more than eight (8) hours per day.

Compensation will be provided for each day or portion of a day, excluding Saturdays, Sundays and holidays, for the duration of the delay, unless the approved current schedule identifies critical path work for these days.

SECTION 9.09B. Jobsite Indirect Costs.

Indirect costs shall be limited to the following:

1. Actual payroll costs for field office staff incurred as a result of the delay, including management, supervision, safety, estimating, engineering, drafting, clerical, secretarial and accounting. A twenty -six percent (26%) surcharge for taxes, insurance, and all other payments made to or on the behalf of the employee may be added to the payroll costs.

2. Actual cost for third- party services provided for the field office, such as management, supervision, safety, estimating, engineering, drafting, clerical, secretarial, and accounting utilized in lieu of employees.

3. Applicable field office expenses for rent and utilities that are substantiated by invoices. Compensation for on-site plant, incidentals, and facilities for non-field office personnel including branch office and home office personnel will not be provided. Compensation for these items and other incidentals is included in the Section 9.09C, “Markup for Compensable Excusable Delays”, of these General Conditions.

SECTION 9.09C. Markup for Compensable Excusable Delays.

Except for compensable excusable delays associated with archeological and cultural resources as described in Section 10.1 0, “Archeological and Cultural Resources”, of these General Conditions and right-of-way delays, fifteen percent (15%) shall be added
to job-site indirect costs for onsite plant, incidentals, overhead, home and branch office costs, bonds and profit. Contractor shall determine the distribution of the markup among Contractor, Subcontractors, and suppliers.

SECTION 9.09D. Duplicated Overhead Costs.

If Contractor is compensated for delays in accordance with this Article , and the delay is attributable to direct cost changes to which markups were added, equitable adjustments shall be made to eliminate the duplication of compensation for indirect and overhead costs and profit.

SECTION 9.10. LIMITATIONS ON PAYMENTS FOR CHANGED WORK.

The City will not pay Contractor for costs in excess of prevailing market values, unless Contractor can establish, to the satisfaction of the City, that Contractor has investigated 479

123
General Conditions
2026

all possible means of providing the work and that the excess costs could not be avoided.

The City will be the sole judge of the necessity of incurring costs in excess of market value and whether the excess costs are directly required for performance of changed work. The City’s determination will be final.

SECTION 9.11. TIME EXTENSIONS FOR CHANGES.

Contractor is entitled to adjustment in Contract Time only if completion of the entire Work or of any milestone outlined in the Special Provisions is extended due to changes impacting the controlling item of work. Each proposal submitted by Contractor in accordance with Section 9.04 , “Prosecution of Changes to the Contract”, of these General Conditions, shall state the amount of extra time Contractor believes the change added to the overall project schedule and shall be supported by a Time Impact Analysis under Section 7.18, “Extension of Time”, of these General Conditions. Failure to request a time extension within the time allowed constitutes a waiver of Contractor’s right to subsequently claim an adjustment in Contract Time. The Project Manager shall have the authority to determine if a time extension should be granted.

SECTION 9.12. EFFECT ON SURETIES OF CHANGES TO THE WORK.

No alterations, time extensions, extra or additional work or other changes authorized by these conditions or any part of the Contract shall affect the sureties’ obligations under the Contract.

SECTION 9.13. CONTRACT CHANGE ORDER.

The City will issue a Change Order if a change to the Contract Sum or Contract Time is necessary. Contractor shall not be entitled to any adjustments in either Contract Sum or Contract Time for changes performed before receipt of a written directive requiring the changes or Change Order approved by the City. Adjustments in Contract Time or Contract Sum for changes performed will not be made until a Change Order is approved by the City. A Change Order is generally comprised of one or more Field Directives or other written orders or directives, and contains a summary of each change and changes to the Contract Sum and Contract Time.

SECTION 9.14. ACCEPTANCE OF ORDERS FOR CHANGES.

A Change Order that is substantially in agreement with Contractor ’s Proposed Change Order, and/or Contractor’s written agreement of a Change Order, Field Directive or other written directive, will constitute Contractor’s final and binding agreement to the provisions of the Change Order, Field Directive, or other written directive, and a waiver of all claims in connection therewith, whether direct or consequential in nature, including those of any Subcontractors or suppliers. If Contractor disagrees with any Change Order, Field Directive, or other written directive, Contractor may submit a notice of potential claim to the City in accordance with Section 9.16 , “Notice of Potential Claim”, of these General Conditions. Disagreement with the provisions of a Change Order, Field Directive, or other written order will not relieve Contractor of Contractor’s obligations under the Contract. 480

124
General Conditions
2026

SECTION 9.15. DISPUTE REGARDING CONTRACT REQUIREMENTS.

If Contractor and the City fail to agree whether or not any work or other matter is within the scope of the Contract, Contractor shall nevertheless immediately perform such work upon receipt of a written Field Directive or other written order. If Contractor disagrees with a decision by the City that any work is within the scope of the Contract, then Contractor must follow the claims procedures in the Contract, including but not limited to Sections

7.13, 8.11, 9.16 and 9.17 of these General Conditions.

Contractor shall not stop performing the Work pending resolution of a dispute, unless so ordered in writing by the City.

SECTION 9.16. NOTICE OF POTENTIAL CLAIM.

Contractor shall not be entitled to payment of any additional compensation (whether money or time) for any cause, including any disagreement, protest, or change, any act or failure to act by the City , or the happening of any event, thing or occurrence, unless Contractor has given the City due advance written notice of potential claim as hereinafter specified. The written Notice of Potential Claim shall set forth the reasons for which Contractor believes additional monetary compensation and/or time will or may be due, the nature of the costs and/or time involved, and, insofar as possible, the amount of the potential claim.

Contractor shall promptly provide a written Notice of Potential Claim to the City upon discovery of concealed or unknown conditions or upon any disagreement, protest, situation, event, or occurrence that may result in a claim, including but not limited to changes in work and delays. The Notice shall be submitted no more than five (5) Working Days after the discovery or occurrence of any event that may be the basis for a claim for additional compensation or additional time.

Failure to timely submit the Notice waives any Claim that Contractor may otherwise have had the right to submit based on the underlying occurrence or event.

SECTION 9.17. SUBMISSION OF CLAIMS.

Claims shall be subject to the requirements of Public Contract Code sections 20104 et seq. and 9204. A summary of those provisions is set forth below. A waiver of the rights granted by the referenced statutes is void and contrary to public policy, provided, however, that (1) upon receipt of a Claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration, as applicable; and (2) the City may prescribe reasonable change order, claim, and dispute resolution procedures and requirements in addition to the statutory requirements, so long as the contractual provisions do not conflict with or otherwise impair the statutory timeframes and procedures. To the extent that the summary below is inconsistent with any requirement of those statutes, the statutes shall control. The terms below are intended to be consistent with the governing statutes, and any modifications shall be understood as lawful modifications or additions to the statutory requirements if at all possible.
481

125
General Conditions
2026

SECTION 9.17A. Definitions.
“Claim” means a separate demand by Contractor sent by registered mail or certified mail with return receipt requested, for one or more of the following:
(A) a time extension, including, without limitation, for relief from damages or penalties for delay assessed by a public entity under a contract for a public works project.
(B) payment by the public entity of money or damages arising from work done by, or on behalf of, Contractor pursuant to the contract for a public works project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled.
(C) payment of an amount that is disputed by the City.
“Mediation” means any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. “Public works contract” or “public works project” means the erection, construction, alteration, repair, or improvement of any public structure, building, road, or other public improvement of any kind.
“Subcontractor” means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who either is in direct contract with Contractor or is a lower tier subcontractor.

SECTION 9.17B. Claims Procedure.

All Claims under this Contract shall be resolved using the following procedure.

1. T he Claim shall be in writing and include the documents necessary to substantiate the Claim as set forth in Section 9.17 C. Unless a different time is stated in the Contract Documents, Claims must be filed not later than thirty (30) Calendar Days after the approved final payment request is returned to Contractor by the City. Any Claim shall be certified under penalty of perjury and in compliance with the California False Claims Act, as set forth in Section

9.17C below. Failure to include these required certifications will constitute grounds for immediate rejection of the Claim and shall be deemed a waiver and absolute bar of the Claim, including any right to pursue the Claim further.

2. If a Subcontractor, including a lower tier Subcontractor, lacks legal standing to assert a Claim against the City because privity of contract does not exist, then Contractor may present a Claim on behalf of such a Subcontractor. A first -tier Subcontractor may request in writing, either on its own behalf or on behalf of a lower tier Subcontractor, that Contractor present a Claim on behalf of the Subcontractor for work that was performed by the Subcontractor. The Subcontractor requesting that the Claim be presented shall furnish reasonable documentation to support the Claim. Within 45 days of receipt of this written 482

126
General Conditions
2026

request, Contractor shall notify the Subcontractor in writing as to whether Contractor presented the Claim and, if Contractor did not present the Claim, provide the Subcontractor with a statement of the reasons for not having done so.

3. Upon receipt of a Claim, the City shall conduct a reasonable review of the Claim. Within 30 days of receipt of the Claim, the City may request, in writing, any additional documentation supporting the Claim or relating to defenses to the Claim that the City may have against the claimant. Where additional information is requested by the City, the time in which the City must respond to a Claim shall be tolled until all requested information is provided. If additional information is thereafter required, then it shall be requested and provided upon mutual agreement of the City and Contractor.

4. Within 45 days of receipt of the Claim, as that time may be tolled as provided in Section 9.17B.3 above, the City shall provide Contractor with a written statement identifying what portion of the Claim is disputed and what portion is undisputed. Upon receipt of a Claim, the City and Contractor may, by mutual agreement, extend the time period for a response. Failure by the City to respond to a Claim within the time periods described herein shall result in the Claim being deemed rejected in its entirety. A Claim that is denied by failure of the City to respond shall not constitute an adverse finding with regard to the merits of the Claim or the responsibility or qualifications of the claimant.

5. Any payment due on an undisputed portion of the Claim shall be processed and made within 60 days after the City issues its written statement.

The City
shall not fail to pay money as to any portion of a Claim which is undisputed except as otherwise provided in the Contract Documents.

6. If the claimant disputes the City’s written response, or the City fails to respond within the time prescribed, Contractor may so notify the City, in writing, either within 15 days of receipt of the City’s response or within 15 days of the City’s failure to respond within the time prescribed, respectively, and demand an informal conference to meet and confer for settlement of the issues in dispute.

Upon receipt of a demand, sent by registered mail or certified mail, return receipt requested, the City shall schedule a meet and confer conference within 30 days for settlement of the dispute.

7. Within 10 business days following the conclusion of the meet and confer conference, if the Claim or any portion of the Claim remains in dispute, then the City shall provide Contractor a written statement identifying the portion of the Claim that remains in dispute and the portion that is undisputed. Failure by the City
to provide the written statement within the time periods described herein shall result in the remaining Claim issues being deemed rejected in their entirety. Denial by failure of the City to respond shall not constitute an adverse finding with regard to the merits of the remaining Claim issues or the responsibility or qualifications of the claimant. Any payment due on an undisputed portion of the Claim shall be processed and made within 60 days after the the City issues its written statement.
483

127
General Conditions
2026

8. Any remaining disputed portion of the Claim following the meet and confer conference shall be submitted to nonbinding mediation, with the City and Contractor sharing the associated costs equally. The City and Contractor shall mutually agree to a mediator within 10 business days after the disputed portion of the Claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the Claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. Unless otherwise agreed to by the City and Contractor in writing, the mediation conducted pursuant to this Section shall excuse any further obligation under Public Contract Code Section 20104.4 to mediate after litigation has been commenced. This Section does not preclude arbitration if mediation under this Section does not resolve the parties’ dispute.

9. If mediation is unsuccessful, then Contractor may file a claim as provided in Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code with respect to the parts of the Claim remaining in dispute. For purposes of those provisions, the running of the period of time within which a Claim must be filed shall be tolled from the time Contractor submits his or her written Claim pursuant to Section 9- 18.02.01 until the time that mediation of disputed portions of that Claim is completed. This Section does not apply to tort claims, and nothing in this Section is intended nor shall be construed to change the time periods for filing tort claims or actions specified by Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code.

10. Amounts not paid in a timely manner as required by this Section shall bear interest at seven percent (7%) per year.

11. Claims of $375,000 or less are subject to the following procedures for civil actions filed to resolve the claims:
a. The case shall be submitted to judicial arbitration pursuant to Chapter

2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, notwithstanding Section 1141.11 of that code. The Civil Discovery Act (Title 4 (commencing with Section 2016.010) of Part 4 of the Code of Civil Procedure) shall apply to any such proceeding, consistent with the rules pertaining to judicial arbitration. b. The parties stipulate that the arbitrator shall be experienced in construction law and shall be paid necessary and reasonable hourly rates of pay not to exceed their customary rate, and such fees and expenses shall be paid equally by the parties, except in the case of arbitration where the arbitrator, for good cause, determines a different division. In no event shall these fees or expenses be paid by state or county funds.
c. In addition to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, any party who, after receiving 484

128
General Conditions
2026

an arbitration award, requests a trial de novo but does not obtain a more favorable judgment shall, in addition to payment of costs and fees under that chapter, pay the attorneys’ fees of the other party arising out of trial de novo.
d. The court may, upon request by any party, order any witnesses to participate in arbitration process.

In any suit filed under Public Contract Code Section 20104.4, the City shall pay interest at the legal rate on any arbitration award or judgment. The interest shall begin to accrue on the date the suit is filed in a court of law.

SECTION 9.17C. Documentation of Claims by Contractor.

For each Claim, Contractor shall furnish claim documentation as herein specified.

Contractor shall submit three (3) certified copies of all claim documentation. All claim documentation shall be complete when submitted. The evaluation of Contractor 's claim will be based on the City’s records and the claim documentation submitted by Contractor.

Claim documentation shall conform to generally accepted auditing standards and shall be in the following format:

1. Introduction and background

2. Issues
a. Index of issues
b. For each issue:
• Background
• Chronology
• Contractor's position (reason for the City’s potential liability) • Supporting documentation of merit
• Supporting documentation of damages

3. CPM schedules, as-planned versus as-built, and delay analysis

4. Productivity and damages exhibits

5. Summary of issues and damages
Supporting documentation of merit for each issue shall be cited by reference, photocopies, or explained. Supporting documentation may include, but not be limited to, General Conditions , Technical and other Specifications, Drawings, correspondence, conference notes, shop drawing logs, survey books, inspection reports, delivery schedules, test reports, daily reports, subcontracts, fragmentary CPM schedules, Time Impact Analyses, photographs, technical reports, RFIs, Field Directives, and other related records.
485

129
General Conditions
2026

Supporting documentation of damages for each issue shall be cited, photocopied, or explained. Supporting documentation may include, but not be limited to, certified detailed labor, materials, equipment, and construction equipment and services costs; purchase orders; invoices; project as-planned and as-built costs; Subcontractor payment releases; quantity reports; other related records; general ledger and any other accounting materials.

Each submission of Claim documentation shall include the following certification, signed in the same manner as the Contract was signed:

Claim Declaration
I, [name of declarant], declare the following:
[Contractor company name] has contracted with the City of Rocklin for the [name of
project] project. I am authorized by my employer ( [contractor company name] ) to prepare the attached claim for compensation (in other words, for money and/or time extensions) to the City of Rocklin regarding this project (dated _________, 20_, and requesting $_________ and/or ___ additional working days), and I did prepare said attached claim. I am the most knowledgeable person at [contractor company name] regarding this claim.