Attachment 2 - Bid Tabulation

Mayor and City Council
May 15, 2024

Document
Attachment 2 - Bid Tabulation
Meeting
May 15, 2024
Body
Mayor and City Council
Original file
158 KB
Text extracted from the city's file for reading and search. Open the original on sanbernardino.primegov.com. That file is the official record.

Quantity Unit Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price 1 Mobilization LS 1 9,248.50$ $9,248.50 48,997.50$ $48,997.50 10,000.00$ $10,000.00 47,207.00$ $47,207.00 25,000.00$ $25,000.00 2 Not Used $0.00 $0.00
3 Erosion Control Plan, BMPs and Maintenance LS 1 3,500.00$ $3,500.00 8,037.00$ $8,037.00 5,000.00$ $5,000.00 8,730.00$ $8,730.00 5,000.00$ $5,000.00 4 AC Pavement and Aggregate Base Removal SF 3,872 3.50$ $13,552.00 8.00$ $30,976.00 6.00$ $23,232.00 8.10$ $31,363.20 4.00$ $15,488.00 5 PCC Pavement and Aggregate Base Removal SF 387 3.50$ $1,354.50 26.72$ $10,340.64 10.00$ $3,870.00 10.13$ $3,920.31 6.00$ $2,322.00 6 Removal of Catch Basin EA 1 1,250.00$ $1,250.00 2,122.05$ $2,122.05 3,000.00$ $3,000.00 3,125.00$ $3,125.00 2,500.00$ $2,500.00 7 Removal of Curb & Gutter LF 31 40.00$ $1,240.00 62.62$ $1,941.22 25.00$ $775.00 108.00$ $3,348.00 25.00$ $775.00 8 Removal of Tree and Tree Well EA 1 2,500.00$ $2,500.00 5,875.00$ $5,875.00 4,250.00$ $4,250.00 2,500.00$ $2,500.00 2,500.00$ $2,500.00 9 Curb Drain Relocation EA 2 1,250.00$ $2,500.00 1,670.85$ $3,341.70 3,500.00$ $7,000.00 900.00$ $1,800.00 750.00$ $1,500.00 10 Sawcut LF 131 17.60$ $2,305.60 22.42$ $2,937.02 15.00$ $1,965.00 20.00$ $2,620.00 10.00$ $1,310.00 11 Not Used $0.00 $0.00
12 Not Used $0.00 $0.00
13 Construction Survey & Grading SF 3,872 1.35$ $5,227.20 10.31$ $39,920.32 2.00$ $7,744.00 3.87$ $15,000.00 4.00$ $15,488.00 14 Backfilling and Re-compaction; Class II Aggregate Base; Geotechnical Testing including Compaction and Percolation/Infiltraion LS 1 35,000.00$ $35,000.00 38,628.50$ $38,628.50 47,500.00$ $47,500.00 31,644.00$ $31,644.00 10,000.00$ $10,000.00 15 Not Used $0.00 $0.00
16 Full Depth AC Pavement TON 0.5 3,000.00$ $1,500.00 4,493.20$ $2,246.60 8,000.00$ $4,000.00 17,000.00$ $8,500.00 2,000.00$ $1,000.00 17 PCC Driveway (Commercial) SF 178 50.00$ $8,900.00 24.69$ $4,394.82 75.00$ $13,350.00 126.94$ $22,595.32 25.00$ $4,450.00 18 PCC Sidewalk, 95% Subgrade compaction SF 60 150.00$ $9,000.00 36.46$ $2,187.60 35.00$ $2,100.00 31.67$ $1,900.00 20.00$ $1,200.00 19 8" Curb and Gutter LF 31 60.00$ $1,860.00 48.90$ $1,515.90 75.00$ $2,325.00 240.00$ $7,440.00 100.00$ $3,100.00 20 Not Used $0.00 $0.00
21 4” PVC SDR-35 Storm Drain Pipe LF 44 45.00$ $1,980.00 66.17$ $2,911.48 180.00$ $7,920.00 18.64$ $820.00 50.00$ $2,200.00 22 12”x12” Catch Basin Traffic Rated w/ ADA Compliant Grate and Filter Insert EA 2 1,250.00$ $2,500.00 1,620.33$ $3,240.66 3,500.00$ $7,000.00 975.00$ $1,950.00 1,500.00$ $3,000.00 23 PCC Pavement including Subgrade Preparation SF 1,012 25.00$ $25,300.00 21.02$ $21,272.24 35.00$ $35,420.00 27.41$ $27,738.92 20.00$ $20,240.00 24 Permeable Pavers Incl. Subgrade Preparation SF 2,800 20.00$ $56,000.00 23.89$ $66,892.00 22.50$ $63,000.00 28.96$ $81,095.00 35.00$ $98,000.00 25 500 SF TransFold Stage Platform, Stafe/Riser Caddy, and Portable Steps.

Midwest Folding Products Nos. TF4824P, MSC, and TST3 or Equal LS 1 20,000.00$ $20,000.00 5,146.00$ $5,146.00 17,400.00$ $17,400.00 17,781.66$ $17,781.66 18,000.00$ $18,000.00 26 Custom Neon Alley Entrance Sign, Arch, and Gate w/ Security and Knox Padlock Fabricate and Install EA 1 35,000.00$ $35,000.00 76,375.00$ $76,375.00 79,950.00$ $79,950.00 80,952.00$ $80,952.00 75,000.00$ $75,000.00 27 Tree Well EA 1 4,850.00$ $4,850.00 4,594.25$ $4,594.25 7,000.00$ $7,000.00 8,500.00$ $8,500.00 3,500.00$ $3,500.00 28 Tree Planter EA 1 3,500.00$ $3,500.00 4,937.35$ $4,937.35 4,500.00$ $4,500.00 5,297.00$ $5,297.00 2,500.00$ $2,500.00 29 Trees EA 3 1,250.00$ $3,750.00 1,529.07$ $4,587.21 5,000.00$ $15,000.00 1,000.00$ $3,000.00 1,500.00$ $4,500.00 30 Shrub and Ground Cover Per Plan LS 1 5,000.00$ $5,000.00 4,117.20$ $4,117.20 7,500.00$ $7,500.00 12,864.00$ $12,864.00 6,000.00$ $6,000.00 31 Irrigation System Per Plan LS 1 10,000.00$ $10,000.00 23,631.60$ $23,631.60 10,500.00$ $10,500.00 15,000.00$ $15,000.00 20,000.00$ $20,000.00 32 5/8” x 3/4” Irrigation Meter Service LS 1 7,600.00$ $7,600.00 11,068.50$ $11,068.50 12,500.00$ $12,500.00 31,500.00$ $31,500.00 2,500.00$ $2,500.00 33 Bike rack EA 1 1,350.00$ $1,350.00 1,915.25$ $1,915.25 1,800.00$ $1,800.00 2,150.00$ $2,150.00 1,500.00$ $1,500.00 34 Trash Reseptacle EA 7 3,250.00$ $22,750.00 3,550.51$ $24,853.57 750.00$ $5,250.00 3,679.14$ $25,754.00 4,000.00$ $28,000.00 35 Outdoor Grade Bench EA 3 3,800.00$ $11,400.00 4,214.33$ $12,642.99 3,500.00$ $10,500.00 6,177.17$ $18,531.50 4,500.00$ $13,500.00 36 Light Pole – See Plan Sheet 4 for Locations EA 6 2,650.00$ $15,900.00 5,866.67$ $35,200.02 1,200.00$ $7,200.00 3,466.67$ $20,800.02 3,000.00$ $18,000.00 37 Not Used $0.00 $0.00 $0.00
38 Not Used $0.00 $0.00 $0.00
39 Not Used $0.00 $0.00 $0.00
40 Not Used $0.00 $0.00 $0.00
41 Construction 4’x8’ Project Signs EA 1 1,500.00$ $1,500.00 3,078.50$ $3,078.50 1,250.00$ $1,250.00 1,500.00$ $1,500.00 1,500.00$ $1,500.00 42 Sole Alley Wayfinding Sign and Post per City of San Bernardino Std. Plan 50 EA 2 1,260.00$ $2,520.00 587.50$ $1,175.00 1,800.00$ $3,600.00 1,800.00$ $3,600.00 700.00$ $1,400.00 43 Anti-Littering Signs per R47 (CA) EA 3 135.00$ $405.00 195.83$ $587.49 750.00$ $2,250.00 250.00$ $750.00 600.00$ $1,800.00 44 Adjust Items to Grade as Noted per Plan EA 5 350.00$ $1,750.00 1,200.38$ $6,001.90 1,250.00$ $6,250.00 500.00$ $2,500.00 300.00$ $1,500.00 45 Connect 5” PVC SDR-35 Storm Drain Pipe to Existing 5” Storm Drains. LF 11 100.00$ $1,100.00 352.93$ $3,882.23 250.00$ $2,750.00 125.00$ $1,375.00 100.00$ $1,100.00 46 Sawcut Scorelines per Plan LF 31 89.50$ $2,774.50 56.86$ $1,762.66 35.00$ $1,085.00 20.00$ $620.00 20.00$ $620.00 47 Not Used $0.00 $0.00 $0.00
48 Protect Items in Place as Noted per Plan EA 38 125.00$ $4,750.00 34.63$ $1,315.94 100.00$ $3,800.00 118.42$ $4,500.00 50.00$ $1,900.00 49 50
51 52
53 54
Apparent Low Bidder 1 Apparent Low Bidder 4 Apparent Low Bidder 3 Apparent Low Bidder 5 Apparent Low Bidder 2
$340,617.30 $524,650.91 $449,536.00 $560,271.93 $417,893.00 $350,617.30 $524,651.41 $449,536.00 $564,918.02 $417,893.00 -$10,000.00 -$0.50 $0.00 -$4,646.09 $0.00

TOTAL BID AMOUNT CALCULATED BASED ON UNIT PRICES

CALCULATION CORRECTIONS TO BID AMOUNT SUBMITTED BY CONTRACTOR BASED ON CALCULATED BID AMOUNT
Apparent Low Bidder 3

AEC MORENO CORPORATION

1. BID TABULATION
PROJECT NAME: 4TH STREET ALLEY REHABILITATION
PROJECT NO: SS 22-008
Bid Item and Description
Apparent Low Bidder 1
SDC ENGINEERING INC.

Apparent Low Bidder 2

VIDO SAMARZICH, INC
Apparent Low Bidder 4
C.S. LEGACY INC. Preferred General Services
Apparent Low Bidder 5

BID RANKING

TOTAL BID AMOUNT INDICATED BY BIDDER

BID TABULATION
S:\ENGINEERING\RFCA's\2024 All\5.15.24\Award of Clean California Grant 4th Street Beautifucation\4thSstreet Alley BID ANALYSISBID TABULATION 1 of 1