Quantity Unit Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price
1.1 MOBILIZATION LS 1 1,000.00$ $1,000.00 -$ $0.00 3,500.00$ $3,500.00 60,891.00$ $60,891.00 11,750.00$ $11,750.00 213,500.00$ $213,500.00
1.2 TEMPORARY TRAFFIC CONTROL EA 1 1,000.00$ $1,000.00 -$ $0.00 1,500.00$ $1,500.00 6,380.00$ $6,380.00 11,750.00$ $11,750.00 26,920.00$ $26,920.00
1.3 RETROFIT AN EXISTING SINGLE ACORN POLE WITH ONE NEW LED SOLAR FIXUTRE WITH ONE NEW BLACK TENON TYPE “S”
ADAPTER
EA 76 1,001.50$ $76,114.00 -$ $0.00 1,525.00$ $115,900.00 1,438.00$ $109,288.00 1,947.00$ $147,972.00 906.20$ $68,871.20
1.4 RETROFIT AN EXISTING DOUBLE ACORN POLE WITH ONE
NEW LED SOLAR FIXUTRE WITH ONE NEW BLACK TENON
TYPE “D” ADAPTER
EA 26 1,004.50$ $26,117.00 -$ $0.00 1,525.00$ $39,650.00 1,438.00$ $37,388.00 2,687.00$ $69,862.00 906.20$ $23,561.20
1.5 PROJECT SIGN COMFORMING TO CALTRANS STANDARD RS1 & RS2 EA 129,521.00$ $29,521.00 -$ $0.00 2,639.00$ $2,639.00 3,560.00$ $3,560.00 3,554.00$ $3,554.00 1,500.00$ $1,500.00 Apparent Low Bidder 1 Apparent Low Bidder 2 Apparent Low Bidder 3 Apparent Low Bidder 4 Apparent Low Bidder 5 Apparent Low Bidder 6
$133,752.00 $0.00 $163,189.00 $217,507.00 $244,888.00 $334,352.40 $133,752.00 $163,165.54 $163,189.00 $217,507.00 $244,888.00 $241,920.00 $0.00 -$163,165.54 $0.00 $0.00 $0.00 $92,432.40
2.1 RETROFIT AN EXISTING SINGLE ACORN POLE WITH ONE NEW LED SOLAR FIXUTRE WITH ONE NEW BLACK TENON TYPE “S” ADAPTER.
ALONG E ST FROM 4TH ST TO 5TH ST.
EA 16
1,001.50$ 16,024.00$ -$ -$ 1,525.00$ 24,436,600.00$ 2,031.00$ 32,496.00$ 1,947.00$ 31,152.00$ -$ -$ $16,024.00 $0.00 $24,436,600.00 $32,496.00 $31,152.00 $0.00 $149,776.00 $0.00 $24,599,789.00 $250,003.00 $276,040.00 $334,352.40
0.00% $0.00
NA NA NA NA NA NA
#DIV/0! $0.00 0.00% $0.00 0.00% $0.00 0.00% $0.00 0.00% $0.00 TOTAL $0.00
TOTAL $0.00 TOTAL $0.00 TOTAL $0.00 TOTAL $0.00 TOTAL $0.00
SUBCONTRACTORS
TOTAL BID AMOUNT CALCULATED BASED ON UNIT PRICES
IS THE BIDDER QUALIFIED BASED ON REFERENCE PROJECTS
CALCULATION CORRECTIONS TO BID AMOUNT SUBMITTED BY CONTRACTOR BASED ON CALCULATED BID AMOUNT
ADDITIVE ALTERNATE #1 (HUCHABAA FIELD LIGHTING)
ADDITIVE ALTERNATE #1 TOTAL
BASE BID + ADDITIVE ALTERNATVE #1
Apparent Low Bidder 3
Crosstown Electrical & Data Inc.
1. BID TABULATION
PROJECT NAME: EECBG Voucher Program – Solar Retrofit 2024 PROJECT NO: TC25-004
Bid Item and Description
Apparent Low Bidder 1
Sierra Pacific Electrical Contracting
Apparent Low Bidder 5
Elecnor Belco Electric Inc.
Apparent Low Bidder 2
Horizon Lighting Inc
(Non Responsive: Unit Prices blank) Quality Light and Electrical Apparent Low Bidder 4 Apparent Low Bidder 6
Blue Collar Contractors
BID RANKING
SUBCONTRACTOR % AND AMOUNT SHOWN IN THE BID
DID THE BIDDER MEET MAX 49% SUB CONTRACTOR (MIN 51% WORK BY PRIME CONTRACTOR) REQUIREMENT
TOTAL BID AMOUNT INDICATED BY BIDDER
BID TABULATION
S:\ENGINEERING\RFCA's\2024 All\12.18.24\EECBG Vocher\TC25-004 BID ANALYSISBID TABULATION 1 of 1