Attachment 2 - Bid Tabulation

Mayor and City Council
January 15, 2025

Document
Attachment 2 - Bid Tabulation
Meeting
January 15, 2025
Body
Mayor and City Council
Original file
711 KB
Text extracted from the city's file for reading and search. Open the original on sanbernardino.primegov.com. That file is the official record.

Quantity Unit Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price

1.1 MOBILIZATION LS 1 1,000.00$ $1,000.00 -$ $0.00 3,500.00$ $3,500.00 60,891.00$ $60,891.00 11,750.00$ $11,750.00 213,500.00$ $213,500.00

1.2 TEMPORARY TRAFFIC CONTROL EA 1 1,000.00$ $1,000.00 -$ $0.00 1,500.00$ $1,500.00 6,380.00$ $6,380.00 11,750.00$ $11,750.00 26,920.00$ $26,920.00

1.3 RETROFIT AN EXISTING SINGLE ACORN POLE WITH ONE NEW LED SOLAR FIXUTRE WITH ONE NEW BLACK TENON TYPE “S”

ADAPTER
EA 76 1,001.50$ $76,114.00 -$ $0.00 1,525.00$ $115,900.00 1,438.00$ $109,288.00 1,947.00$ $147,972.00 906.20$ $68,871.20

1.4 RETROFIT AN EXISTING DOUBLE ACORN POLE WITH ONE

NEW LED SOLAR FIXUTRE WITH ONE NEW BLACK TENON
TYPE “D” ADAPTER
EA 26 1,004.50$ $26,117.00 -$ $0.00 1,525.00$ $39,650.00 1,438.00$ $37,388.00 2,687.00$ $69,862.00 906.20$ $23,561.20

1.5 PROJECT SIGN COMFORMING TO CALTRANS STANDARD RS1 & RS2 EA 129,521.00$ $29,521.00 -$ $0.00 2,639.00$ $2,639.00 3,560.00$ $3,560.00 3,554.00$ $3,554.00 1,500.00$ $1,500.00 Apparent Low Bidder 1 Apparent Low Bidder 2 Apparent Low Bidder 3 Apparent Low Bidder 4 Apparent Low Bidder 5 Apparent Low Bidder 6
$133,752.00 $0.00 $163,189.00 $217,507.00 $244,888.00 $334,352.40 $133,752.00 $163,165.54 $163,189.00 $217,507.00 $244,888.00 $241,920.00 $0.00 -$163,165.54 $0.00 $0.00 $0.00 $92,432.40

2.1 RETROFIT AN EXISTING SINGLE ACORN POLE WITH ONE NEW LED SOLAR FIXUTRE WITH ONE NEW BLACK TENON TYPE “S” ADAPTER.

ALONG E ST FROM 4TH ST TO 5TH ST.

EA 16
1,001.50$ 16,024.00$ -$ -$ 1,525.00$ 24,436,600.00$ 2,031.00$ 32,496.00$ 1,947.00$ 31,152.00$ -$ -$ $16,024.00 $0.00 $24,436,600.00 $32,496.00 $31,152.00 $0.00 $149,776.00 $0.00 $24,599,789.00 $250,003.00 $276,040.00 $334,352.40

0.00% $0.00

NA NA NA NA NA NA
#DIV/0! $0.00 0.00% $0.00 0.00% $0.00 0.00% $0.00 0.00% $0.00 TOTAL $0.00
TOTAL $0.00 TOTAL $0.00 TOTAL $0.00 TOTAL $0.00 TOTAL $0.00

SUBCONTRACTORS

TOTAL BID AMOUNT CALCULATED BASED ON UNIT PRICES

IS THE BIDDER QUALIFIED BASED ON REFERENCE PROJECTS

CALCULATION CORRECTIONS TO BID AMOUNT SUBMITTED BY CONTRACTOR BASED ON CALCULATED BID AMOUNT
ADDITIVE ALTERNATE #1 (HUCHABAA FIELD LIGHTING)
ADDITIVE ALTERNATE #1 TOTAL
BASE BID + ADDITIVE ALTERNATVE #1
Apparent Low Bidder 3
Crosstown Electrical & Data Inc.

1. BID TABULATION
PROJECT NAME: EECBG Voucher Program – Solar Retrofit 2024 PROJECT NO: TC25-004
Bid Item and Description
Apparent Low Bidder 1
Sierra Pacific Electrical Contracting
Apparent Low Bidder 5
Elecnor Belco Electric Inc.

Apparent Low Bidder 2
Horizon Lighting Inc
(Non Responsive: Unit Prices blank) Quality Light and Electrical Apparent Low Bidder 4 Apparent Low Bidder 6
Blue Collar Contractors

BID RANKING
SUBCONTRACTOR % AND AMOUNT SHOWN IN THE BID
DID THE BIDDER MEET MAX 49% SUB CONTRACTOR (MIN 51% WORK BY PRIME CONTRACTOR) REQUIREMENT

TOTAL BID AMOUNT INDICATED BY BIDDER

BID TABULATION
S:\ENGINEERING\RFCA's\2024 All\12.18.24\EECBG Vocher\TC25-004 BID ANALYSISBID TABULATION 1 of 1