Quantity Unit Unit Price Total Price
1 Mobilization 1 LS 4,000.00$ $4,000.00 2 Remove existing fixtures (toilets, sinks, urinals) in Men's and Women's restrooms 10 EA 100.00$ $1,000.00 3 Remove existing weight mats, punch bags, and their supports/fixtures. Clean the GYM floor before the installation of the new weight mats. 1L S 8,000.00$ $8,000.00
4 Not uses $0.00
5 Remove existing AC condensers (5 ton) including disconnect boxes from the roof (see attached pictures); cap/plug any open lines; cover open area of the roof to prevent rain entering the building until the new AC units are installed 4E A 2,000.00$ $8,000.00
6 Remove the related fan coils from the attic 4E A 2,000.00$ $8,000.00 7 Remove existing asphalt walkway, and ADA asphalt path of travel per plan 1,100 SF 20.00$ $22,000.00 8 Remove existing PCC pad/ walkway at west entrance of the building per plan 338 SF 100.00$ $33,800.00 9 Remove/cut 4 feet of existing fence and curb to allow for ADA path of travel. 4L F 500.00$ $2,000.00 10 Remove existing drinking water fountain and cap water line 1 EA 600.00$ $600.00 11 Furnish and install new restroom fixtures (toilets, sinks, urinals).Use Kohler brand fixtures. 10 EA 70.00$ $700.00 12 Furnish paint; Patch and paint restroom walls (men's and women's restrooms).Submit type of paint for approval by the city 1L S 16,000.00$ $16,000.00 13 Furnish and install new weight mats on top of the existing floor(2700 sq. ft.) Use “Greatmats” brand, 3/8 inch x 4 ft. wide with blue dots. See attached picture. Re-install the support/fixtures for the punch bags. 1L S 5,000.00$ $5,000.00
14 Install new ac condenser units on the roof, including supporting equipment.
Condenser units are provided by the City of San Bernardino (maintenance) 4E A 2,000.00$ $8,000.00 15 Furnish and install new fan coils in the attic. Match to existing controls/system s 4E A 6,000.00$ $24,000.00
16 Construct 4” thick PCC walkway (ADA path), including 95% subgrade compaction per plan and specifications. Use concrete class 560-C-3250 1450 SF 100.00$ $145,000.00 17 Furnish and install new fence- post to support the fence 1 LS 2,000.00$ $2,000.00 18 Patch/ repair curb/ gate-post base (see attached picture) 1 LS 3,000.00$ $3,000.00 19 Remove existing double doors on the south and west side of the building, and install new ADA compliant double doors, with panel bars and door closures, including doorbell & wiring. Submit door data sheets to the City for approval.
Doors to be vandal proof.
2E A 10,000.00$ $20,000.00
20 Apply 4” wide thermoplastic reflective white Striping, and blue borders for Handicap path per 2023 Caltrans Standard A90A per specification and Project Plans.
1L S 5,000.00$ $5,000.00
21 Construction 4’ x 8’ project sign 1E A 3,000.00$ $3,000.00 22 Furnish paint, and paint men’s and women’s restroom floors with epoxy paint. 1L S 8,000.00$ $8,000.00 Apparent Low Bidder 1
$327,100.00
$327,100.00
BID RANKING
TOTAL BID AMOUNT INDICATED BY BIDDER
BID TABULATION
1. BID TABULATION
PROJECT NAME: IMPROVEMENTS AT RUBEN CAMPOS COMMUNITY CENTER PROJECT NO: GB 25-007
Bid Item and Description
Apparent Low Bidder 1
Perfection Painting Corp
TOTAL BID AMOUNT CALCULATED BASED ON UNIT PRICES
CALCULATION CORRECTIONS TO BID AMOUNT SUBMITTED BY CONTRACTOR BASED ON CALCULATED BID AMOUNT
S:\ENGINEERING\RFCA's\2025 All\1.15.2025\Award Ruben Campos Community Center\Ruben Campos Bid AnalysisBID TABULATION 1 of 1