CONSENT CALENDAR
City of San Bernardino
Request for Council Action
Date: July 15, 2026
To: Honorable Mayor and City Council Members
From: Lynn Merrill, Director of Public Works
Department: Public Works
Subject: Approve a $500,000 Increase to the Contingency Budget for the Seccombe Lake Park Revitalization Project,
Increasing the Total Contingency Budget to $1,592,721.60 and Appropriating AB 1600 Parkland and Open Space
Funds. (Ward 2)
Recommendation:
It is recommended that the Mayor and City Council of the City of San Bernardino, California:
1. Approve an increase to the contingency budget for the Seccombe Lake Park Revitalization Project (Project) in the amount of $500,000, increasing the total contingency budget amount to $1,592,721.60; and
2. Adopt Resolution No. 2026-125 authorizing the Director of Finance and Management Services to amend the FY 2026/27 Capital Improvement Plan budget with an additional $500,000 from the AB 1600 Parkland and Open Space Fund for the Project; and
3. Authorize the City Manager or designee to expend the contingency fund, if necessary, to complete the Project.
City Manager's Comments
The City Manager recommends approval.
Executive Summary
Due to length of time that was needed to acquire the necessary permits for the prefabricated restroom/concession building, the Project construction phase is expected to run through the end of September 2026. As such, additional funding is necessary to continue the previously approved construction agreement and 3 1
9 1
construction management and inspection services. To support the final portion of the current construction phase, an additional funding allocation is recommended to increase the contingency budget.
Approval of this item will increase the project contingency by $500,000, from $1,092,721.60 to $1,592,721.60. The additional funding will be used to complete construction management, inspection, project administration, anticipated change orders, and remaining construction activities associated with the delayed completion of the project. No General Fund dollars are proposed for this action. Funding is proposed from the AB 1600 Parkland and Open Space Fund.
Background
Seccombe Lake Park is located in the center of the City and has been serving the surrounding community for many years. Due to neglect and vandalism, the Park has not felt welcoming to visitors. The Seccombe Lake Park will receive a new look and be recreated to meet the current recreational needs of the neighborhood and community.
On September 21, 2022 Mayor and City Council approved design services agreement award for Seccombe Lake Park Revitalization Project in the amount of $537,855.
On July 19, 2023, the Mayor and City Council approved a concept plan that included a variety of park improvements. The improvements included, but are not limited to, playground equipment, lighting, ADA accessibility, exercise stations, gazebo renovations, parking lot rehabilitation, renovation of dirt/gras areas, and new restrooms.
On March 6, 2024, the Mayor and City Council approved Amendment No. 1 to the Agreement with RHA Landscape Architects – Planners Inc. in the amount of $53,000 for Seccombe Lake Park Project.
On September 18, 2024, the Major and City Council received and filed an update on the City’s American Rescue Plan Act (ARPA) projects, allocations, and spending to date and authorized the City Manager to obligate ARPA funds for City led projects per the US Department of Treasury Guidelines, by executing Inter-Agency agreements.
This Project received an additional $1 million in funding from the San Manuel Band of Mission Indians to help support the renovations.
On October 2, 2024, the Mayor and City Council have authorized allocating $3,792,332 in American Rescue Plan Act (ARPA) funds to address a budget shortfall for the Seccombe Lake Park project. Staff suggests reallocating this amount from the Encanto Community Center project, which has a total budget of $9.2 million but a significant funding shortfall. By fully funding the Seccombe Lake project with these ARPA funds, the Council can ensure its completion instead of providing only partial funding to the Encanto project.
3 1
9 1
On December 4, 2024 The Mayor and City Council awarded an agreement for construction of the Project to Landscape Support Services in the amount of $10,539,509.65 and approved a Task Order with CSG Consultants in the amount of $700,305 for construction management and inspection services. A contingency budget of $1,092,721.60 was also approved for construction of the project.
On December 3, 2025, the Mayor and City Council approved Amendment No. 2 to the Design Services Agreement with RHA Landscape Architects – Planners, Inc. to extend the term of the agreement through June 30, 2027.
Discussion
The Project included the purchasing and installation of two buildings. A standalone restroom building, and a combination restroom/concession building. As part of the design process for the prefabricated restroom/concession building, a County Health Department review and permit is required. This permit is specific to the concession portion of the prefabricated building that is equipped to be used as a kitchen. Since this permit can result in modifications to the design, the fabrication of the restroom/concession building did not start until after the permit is acquired. This resulted in the fabrication and delivery being completed past the originally scheduled Project deadline. As a result, other portions of the project construction scheduled also needed to be adjusted.
The tentative project completion date has shifted from February 2026 to September 2026. To complete the Project, funding for additional construction, professional services (construction management, inspection, construction support etc.) and administrative costs are recommended.
Project Contingency Budget Summary
Current Contingency Budget $1,092,721.60
Authorized Change Orders ($526,521.26)
Authorized CSG Engineering Task Order Amendment ($542,408.00) RHA Amendment No. 1 ($53,000)
City Administrative Costs (43,199.33)
Estimated Pending Change Orders ($325,000)
Contingency Budget Funding Need ($397,406.99)
A contingency budget increase of $500,000 is recommended to cover the current $387,406 needed and additional items that may be identified as the Project progresses.
Proposed Contingency Budget
Original Approved Funding $1,092,721.60
Proposed Funding Increase (Contingency) $500,000.00
Total Proposed Project Budget $1,592,721.60
There is sufficient funding available within the AB 1600 Parkland and Open Space 3 1
9 1
Fund balance for the proposed contingency increase of $500,000. 2021-2025 Strategic Targets and Goals
This Project is consistent with Key Target No.4: Economic Growth & Development.
The additional amenities to Seccombe Lake Park will improve community participation for recreational activities and provide a safe and well-maintained community park.
Fiscal Impact
Approval will appropriate an additional $500,000 from the AB 1600 Parkland and Open Space Fund to increase the project contingency budget from $1,092,721.60 to $1,592,721.60. No General Fund dollars are proposed for this action. Following this appropriation, staff should disclose the remaining available balance in the AB 1600 Parkland and Open Space Fund and confirm whether the appropriation affects any currently programmed park projects.
Conclusion
It is recommended that the Mayor and City Council of the City of San Bernardino, California:
1. Approve an increase to the contingency budget for the Seccombe Lake Park Revitalization Project (Project) in the amount of $500,000, increasing the total contingency budget amount to $1,592,721.60; and
2. Adopt Resolution No. 2026-125 authorizing the Director of Finance and Management Services to amend the FY 2026/27 Capital Improvement Plan budget with an additional $500,000 from the AB 1600 Parkland and Open Space Fund for the Project; and
3. Authorize the City Manager or designee to expend the contingency fund, if necessary, to complete the Project.
Attachments
Attachment 1 Resolution No. 2026-125
Attachment 2 Location Map
Ward:
First Ward
Synopsis of Previous Council Actions:
September 21, 2022 Approved design services agreement award for Seccombe Lake Park Revitalization Project
3 1
9 1
July 19, 2023 Approved the Concept Plan for the Seccombe Lake Park Revitalization Project
March 6, 2024 Approved Amendment No. 1 to Agreement with RHA Landscape Architects – Planners Inc. for Seccombe Lake Park Design Services in the amount of $53,000 (Ward 1)
October 2, 2024 Approved allocation of $3,792,332 in additional American Rescue Plan Act funds for the project.
December 4, 2024 Awarded agreement for construction of the Project to Landscape Support Services in the amount of $10,539,509.65, approved Task Order with CSG Consultants in the amount of $700,305, and a total contingency budget of $1,092,721.60.
December 3, 2025 Approved Amendment No. 2 to the Design Services agreement with RHA Landscape Architects – Planners, Inc. to extend the term of the agreement through June 30, 2027.
CC: Eric Levitt, City Manager