SCOPE OF WORK FOR ENVIRONMENTAL DOCUMENTATION AND
REGULATORY PERMITTING
FOR THE
SAND CITY MULTI-USE BIKE TRAIL FINAL DESIGN PROJECT
Prepared June 18, 2026
Task 1. Project Management
Task 1.2 Progress Meetings
DD&A will support Whitson Engineers with project coordination and progress meetings throughout the duration of the project. DD&A staff will attend the project kick-off meeting at Sand City Hall and participate in monthly coordination meetings, as requested by Whitson Engineers. Meeting participation may include in-person attendance, teleconferences, or video-based meetings, as appropriate.
DD&A will provide technical input within its areas of expertise, coordinate with project team members, and assist Whitson Engineers in addressing action items and project-related issues. DD&A will review meeting agendas, meeting minutes, and other coordination materials prepared by Whitson Engineers, as necessary, to support effective communication and project progress.
Task 1.3 Review of Existing Documents and Environmental Impact Report DD&A will support Whitson Engineers in reviewing existing project documentation, environmental compliance records, and related technical materials relevant to project development and environmental clearance. DD&A will review available project information, including the Project Description, Notice of Exemption (NOE), Preliminary Environmental Study (PES), and other environmental documentation provided by the City, Caltrans, or Whitson Engineers.
DD&A will provide technical input regarding environmental constraints, permitting considerations, stakeholder concerns, and regulatory requirements within its areas of expertise. As requested by Whitson Engineers, DD&A will assist in evaluating environmental commitments, identifying potential environmental issues requiring consideration during project development, and preparing technical information necessary for Caltrans review and final NEPA clearance. Coordination with Whitson Engineers and other team members will be conducted throughout the review process to support project objectives and regulatory compliance.
Task 1.4 Field Review of Project Alignment
DD&A will support Whitson Engineers during field reviews of the proposed project alignment, as requested. DD&A staff will participate in site visits and alignment walk-throughs with Whitson Engineers, City staff, and other project stakeholders, as appropriate. During field reviews, DD&A will identify and document environmental constraints, biological resources, permitting considerations, and other site conditions within its areas of expertise that may affect project design, environmental 162
compliance, or implementation. DD&A will provide technical input and recommendations to Whitson Engineers to support project development and environmental review.
Task 1.5 Agreements and Permits
As requested, DD&A will assist with coordination and consultation with federal, state, and local resource agencies regarding biological resources, jurisdictional resources, environmental compliance, and permitting requirements within its areas of expertise.
DD&A will provide technical information, environmental documentation, permit application support, and agency coordination assistance necessary to support permit and agreement preparation by Whitson Engineers. Support may include assistance related to Caltrans encroachment permit requirements, City encroachment permits, TAMC agreements, and other environmental permits or approvals determined to be necessary during project development. DD&A's role will be limited to environmental and regulatory support services coordinated through Whitson Engineers.
Task 4. Engineering Design (PS&E)
Task 4.2.6 Caltrans Environmental Certification and Commitments Record At the request of the City and Whitson Engineers, DD&A will prepare environmental technical documentation necessary to support Caltrans environmental review and final NEPA clearance for the project. Work will be performed in accordance with the approved Project Description, Preliminary Environmental Study (PES), and applicable Caltrans requirements.
Biological Resources Report: DD&A will prepare a Biological Resources Report documenting existing biological resources within the project area, including common and special-status plant and wildlife species, and evaluating potential project impacts. The report will include an assessment of potential direct and indirect effects to Monterey spineflower and identify appropriate avoidance and minimization measures, such as environmentally sensitive area fencing, nesting bird surveys, construction avoidance measures, and other resource protection recommendations, as warranted.
Area of Potential Effects (APE) Map: DD&A will retain Albion Environmental, Inc. to prepare the Area of Potential Effects (APE) Map in accordance with Caltrans Section 106 requirements and District 5 guidance.
Archaeological Survey Report (ASR): DD&A will retain Albion Environmental, Inc. to prepare the Archaeological Survey Report (ASR) for the project. Extended archaeological investigations, Archaeological Evaluation Reports (AERs), Historic Resource Evaluation Reports (HRERs), Historic Resource Compliance Reports (HRCRs), historical architectural assessments, and Native American consultation support beyond the baseline ASR effort are excluded from this scope and may be completed through an amendment, if required.
Hazardous Waste Technical Memorandum: DD&A will retain Cornerstone Earth Group to prepare a Hazardous Waste Technical Memorandum consisting of a high-level hazardous materials screening sufficient to satisfy Preliminary Environmental Study requirements. Additional hazardous materials investigations, site assessments, sampling, testing, or remediation planning are excluded from this scope and may be completed through an amendment, if required.
Environmental Commitment Record: DD&A will prepare an Environmental Commitments Record summarizing environmental commitments, avoidance and minimization measures, permit conditions, and 163
mitigation requirements identified through technical studies and agency coordination. The commitments record will be provided in a format suitable for incorporation into project environmental documentation and construction specifications.
DD&A will coordinate environmental deliverables with Whitson Engineers and Caltrans, as necessary, to support final environmental approval of the project.
164
DD&A STAFF & AVAILABILITY
Matt Johnson, Senior Project Manager/Environmental Scientist. Availability: 25%.
Jami Colley, Senior Environmental Scientist. Availability: 25%.
DD&A REFERENCES
Client: California American Water
Contact: Scott Ottmar, P.E., Senior Project Engineer, 831.737.5505, [email protected] Services: DD&A has prepared numerous Biological Resources Reports for California American Water for various regulatory agencies, including a recent report for slant well installation for the Sand City Desalination Plant located in Sand City.
Client: Monterey One Water
Contact: Tom Kouretas, P.E., Associate Engineer, 408.529.3618, [email protected] Services: DD&A has prepared numerous Biological Resources Reports for Monterey One Water for various regulatory agencies, including a recent report for the Monterey One Water Treatment Plant on West Bay Street in Sand City.
Client: Transportation Agency for Monterey County
Contact: Janneke Strause, Associate Transportation Planner, 831.775.4410, [email protected] Services: DD&A conducted field assessments; prepared a biological resources report, arborist report, and biological assessment for the MSTSurf! project; facilitated communication and coordination between MST and regulators, including the U.S. Fish and Wildlife Service and the California Coastal Commission; and assisted MST in preparing permit applications and acquiring a Biological Opinion and Coastal Development Permit for MSTSurf!.
165
BERMUDA DUNES | FREMONT | HOLLISTER | PALMDALE | PASADENA | SALINAS | SAN LUIS OBISPO | SANTA BARBARA | SANTA MARIA | VENTURA
EARTH SYSTEMS
1514 Moffett Street, Suite A | Salinas, CA 93905 | (831) 240-4624 | www.earthsystems.com June 30, 2026 Proposal No.: SAL-26-06-009
(Revised July 1, 2026)
Whitson Engineers
Attn: Nathaniel Milam, PE
6 Harris Court
Monterey, CA 93940
PROJECT: SAND CITY MULTI-USE TRAIL
DEL MONTE BOULEVARD
SAND CITY, CALIFORNIA
SUBJECT: Proposal for a Geotechnical Engineering Report Dear Mr. Milam:
As requested, Earth Systems Pacific (Earth Systems) is pleased to present this proposal to prepare a geotechnical engineering report for the proposed multi-use trail to be located along Del Monte Boulevard, in Sand City, California. The project area is located within a Transportation Agency for Monterey County (TAMC) railroad right-of-way. The right-of-way runs parallel to Del Monte Boulevard. The area to be explored encompasses approximately one mile of new trail starting near Canyon Del Rey Boulevard and ending at Playa Avenue.
The site is located within a seismically active area but is outside an Alquist-Priolo Earthquake Fault Rupture Zone as delineated by the State of California. A review of geological maps indicates the site is underlain by coastal terrace deposits (Qcto), as described by Clark et. al. (1997). A review of the Monterey County Hazards Map indicates that the site is located within an area evaluated to have low liquefaction and low landslide hazards. The site area has not been evaluated by the State of California for liquefaction and landslide hazards. Additional evaluation of geologic hazards at the site is beyond the scope of work proposed herein.
Geotechnical Engineering
The purpose of Earth Systems’ geotechnical engineering investigation would be to identify and evaluate the subsurface soil and groundwater conditions at the site, and to use that information to generate design-level soil engineering recommendations for the proposed multi-use trail.
Earth Systems proposes to evaluate subsurface soil conditions at the site by drilling exploratory borings using a track-mounted drill rig. During the drilling process, we would log soil conditions and collect samples of subsurface soils for laboratory testing. 166
Sand City Mixed-Use Trail June 30,2026
(Revised July 1, 2026)
Doc. No.: 2606-019.PRP.REV1/ta 2 Proposal No.: SAL-26-06-009 Selected soil samples collected from our borings would be tested in our laboratory to measure the index and strength properties pertinent to the development. Using the data collected from the subsurface exploration and laboratory testing, engineering analysis would be performed to develop conclusions which would be used to generate recommendations for site preparation and grading. Further details of the scope of work are described below:
A. Site reconnaissance by our staff geologist/engineer to evaluate access conditions and mark tentative locations of the proposed borings prior to contacting Underground Service Alert who would be responsible for marking the locations of the known utilities within the marked areas. This step is required by the law and the purpose of this exercise is to minimize the chances of drilling through/damaging any existing utility lines.
B. Exploration and evaluation of the subsurface conditions through drilling of four to five borings to depths of 5 to 10 feet below ground surface (bgs).
Subsurface conditions encountered in the boreholes would be described by our staff engineer/geologist supervising the drilling process to create a continuous log. The boring logs would include a description of soil encountered including: color, major and minor components, USCS classification, changes in soil conditions with depth, qualitative moisture content, consistency/density and plasticity, sampler type, and sampling depths and laboratory test results. Copies of the boring logs would be included in the report. Soon after collecting the final sample from the borings the borehole would be backfilled with drill cuttings.
C. Laboratory analysis of selected samples collected during our exploratory program. Anticipated tests would include Atterberg limits, gradation analysis, R-value, dry density, and moisture content. The actual types and numbers of tests performed would depend on the subsurface conditions encountered.
D. The field and laboratory data would be reviewed by a Registered Engineer and evaluated with respect to development of criteria for site preparation and grading, exterior concrete flatwork, backfilling of utility trenches, management of site drainage and finish improvements, and required geotechnical observation and testing.
167
Sand City Mixed-Use Trail June 30,2026
(Revised July 1, 2026)
Doc. No.: 2606-019.PRP.REV1/ta 3 Proposal No.: SAL-26-06-009 E. Engineering analysis of the data generated from this subsurface exploration, resulting in the compilation of a written report presenting our conclusions and geotechnical engineering recommendations and design criteria for the proposed multi-use trail. The following items would be addressed in the report:
• Soil and groundwater conditions encountered at the site, • Expansion potential of near surface soil at the site, • Preparation of the site prior to grading,
• Grading criteria and suitability of onsite soils as engineered fill, • Exterior concrete flatwork,
• Utility trench backfills,
• Surface drainage and finish improvements,
• Geotechnical observation and testing.
Evaluation of the site geology; analysis of the soil for percolation rates, corrosivity, contaminants or other chemical properties; construction issues within the domain of contractors; and any other services not specifically noted in the preceding paragraphs are beyond the scope of the proposed work.
FEES
(fees intentionally omitted from submitted SOQ.)
168
Sand City Mixed-Use Trail June 30,2026
(Revised July 1, 2026)
Doc. No.: 2606-019.PRP.REV1/ta 4 Proposal No.: SAL-26-06-009
SCHEDULE AND CONDITIONS
The fees and conditions of this proposal will remain in effect for a period of 90 days. Earth Systems is prepared to assign personnel to your project upon receiving written authorization.
Field work will be scheduled within three to four weeks (drilling subcontractor availability). The laboratory testing will take approximately 7 to 10 working days from the date of field exploration.
The final report should be available within approximately three weeks following completion of laboratory testing. Preliminary information can be provided to the client and design professionals as soon as it is available.
Prior to initiating the subsurface investigation, Underground Service Alert will be contacted to locate utilities that fall within their scope of services. Earth Systems will contract with a private utility locater to assist with location of onsite utilities. However, responsibility for accurate location of underground utilities lies with the client, and Earth Systems Pacific shall not be held responsible for damage resulting from the incomplete or inaccurate identification of underground utilities.
It is our understanding that the project is subject to California Prevailing Wage Law. For your convenience in setting up the project, we have included our DIR registration numbers below.
DIR Public Works Registration Numbers
Legal
Name
Registration
Number
License
Type*
Registration
Date
Expiration
Date
Earth Systems
Pacific
1000003643 N100143 6/7/2018 6/30/2027
*Professional Corporation License Number assigned by DIR March 27, 2015 Please note that effective August 1, 2016, we are required to submit certified payrolls for all Prevailing Wage projects via eCPR. In order to upload certified payrolls to the State’s website, the project’s DIR number is necessary. Please complete the attached SB 854 DIR and eCPR Compliance Information Request form and return to our office at your earliest convenience. 169
Sand City Mixed-Use Trail June 30,2026
(Revised July 1, 2026)
Doc. No.: 2606-019.PRP.REV1/ta 5 Proposal No.: SAL-26-06-009 If the client finds the proposed scope of work, terms (attached), and fees satisfactory, the return of the attached work order, signed and dated by the party responsible for payment, along with the requested retainer, will constitute authorization for work on the project to begin. A verbal authorization will expedite the scheduling of drilling equipment. This agreement can be terminated by either party upon notification in writing. Earth Systems’ responsibility for the project will end upon completion of the services described herein or termination of the agreement, unless authorization to perform additional work and agreement for payment thereof is provided by the client.
We thank you for your consideration of Earth Systems for this project. Please feel free to contact the office at your convenience if you have any questions or require additional information.
Sincerely,
Earth Systems Pacific
Michelle Garcia, CEG Brett Faust, CEG 2386
Associate Engineering Geologist Vice President
Attachments: Work Order
Terms of Services
Prevailing Wage & Accounts Payable Information Request
170
EARTH SYSTEMS
1514 Moffett Street, Suite A | Salinas, CA 93905 | (831) 240-4624 | www.earthsystems.com
W O R K O R D E R
EARTH SYSTEMS PACIFIC (“CONSULTANT”) AND CLIENT AGREE TO A WORK ASSIGNMENT FOR EARTH SYSTEMS PACIFIC AS FOLLOWS:
Date: June 30, 2026 Proposal Number: SAL-26-06-009
(Revised July 1, 2026) Doc. Number: 2606-019.PRP.REV1
Name of Project: Sand City Mixed Use Trail
Order Received by: Michelle Garcia
Client Name: Whitson Engineers, Attn: Mr. Nathaniel Milam Client Address: 6 Harris Court, Monterey, California
Location of Project: Sand City, California
Scope of Services: Geotechnical Engineering Report
Estimated Fee:
I have read and agree to all terms of this document,
including the attached terms for services (7/2017).
AGREED TO AND ACCEPTED:
Earth Systems Pacific
Client (Party responsible for payment)
____________________________________
Brett Faust, CEG 2386
Vice President by Authorized Representative (please print) July 1, 2026
Date Signature and Title
Date
PLEASE RETURN A SIGNED COPY
TO EARTH SYSTEMS PACIFIC Telephone Number
Email Address
IF THE CLIENT DOES NOT OWN THE PROPERTY, PLEASE FILL IN THE PROPERTY OWNER'S NAME AND ADDRESS:
Name:
Address:
*Rates are subject to change due to changes in prevailing wage law or its application. In the event that it is determined or alleged that Prevailing Wage Law applies to any additional aspect of the project, the client agrees to pay Earth Systems Pacific (Consultant) any and all additional compensation necessary to adjust Consultant's wage, to pay any penalties that may be levied against Consultant due to alleged noncompliance with the Prevailing Wage Law, and to pay for apprentices, supervision, certified payrolls, and other administrative costs as necessary to comply with Prevailing Wage Law. In the event that work thought to be subject to prevailing wage is determined not to be subject to prevailing wage, no refund of fees will be given. July 2026 Fee Schedule 171
_
TERMS FOR SERVICES
1. INVESTIGATION, MONITORING & INSPECTION If the services include monitoring or inspection of soil, construction and/or materials, Client shall authorize and pay for Consultant to provide sufficient observation and professional inspection to permit Consultant to form opinions according to accepted statistical sampling methods as to whether the work has been performed in accordance with recommendations. Such opinions, while statistically valid, do not guaranty uniformity of conditions or materials. Similarly, soils and geology investigations do not guaranty uniformity of subsurface conditions. Client hereby represents and warrants that it has provided and shall provide to Consultant all information and sufficient advance notice necessary in order for Consultant to perform the appropriate level of services. No statement or action of Consultant can relieve Client’s contractors of their obligation to perform their work properly.
Consultant has no authority to stop the work of others.
2. SITE ACCESS & UTILITIES Client has sole responsibility for securing site access and locating utilities.
3. BILLING AND PAYMENT Client will pay Consultant the proposal amount or, if none is stated, according to the fee schedule attached to the proposal. Payment is due on presentation of invoices, and is delinquent if Consultant has not received payment within thirty (30) days from date of an invoice. Client will pay an additional charge of 1 1/2 (1.5) percent per month (or the maximum percentage allowed by law, whichever is lower) on any delinquent amount, excepting any portion of the invoiced amount that is disputed in good faith. Each payment will first be applied to accrued interest, costs and fees and then to the principal unpaid amount. All time spent and expenses incurred (including any in‐house or outside attorney's fees) in connection with collection of any delinquent amount will be paid by the Client to Consultant per Consultant's current fee schedule. Services to be performed by Consultant hereunder which are not set forth in this proposal and/or Work order are additional services. Any additional services provided by Consultant shall be subject to the terms of this contract and charged per Consultant’s current fee schedule.
4. OWNERSHIP OF DOCUMENTS Consultant owns all documents it creates and grants Client limited license to use the documents for the purposes stated in the documents. Consultant reserves the right to withhold delivery of documents to Client until payment in full of current invoices has been received.
5. TERMINATION This agreement may be terminated by either party effective 7 days from the date of written notice, or if the client suspends the work for three (3) months. In the event of termination, Consultant will be paid for services performed prior to the date of termination plus reasonable termination expenses. If Consultant has not received payment for any invoice within 30 days from the date of the invoice, or in the event of anticipatory breach by Client, Consultant may suspend performance of its services immediately and may terminate this contract.
6. RISK ALLOCATION In order for Client to obtain the benefit of a fee which includes a lesser allowance for compensating Consultant for its litigation risk, Client agrees to indemnify, hold harmless and defend Consultant, its agents, employees, or officers, from and against any and all loss, claim, expenses, including attorney’s fees, injury, damages, liability or costs arising out of non‐design services (i.e., services other than as defined by Civil Code Section 2784) performed by Consultant on this project, except where such loss injury, damage, liability, cost, expenses or claims are the result of the sole negligence or willful misconduct of Consultant. Regarding any loss due to the negligence or willful misconduct of Consultant, or any loss due to design defects, Client agrees to limit the total aggregate liability of Consultant, its agents, employees, and officers to Client, and to all construction contractors and subcontractors on the entire project, to the greater of $25,000.00 or total fees charged by Consultant. Client further agrees to require of the contractor and his subcontractors an identical limitation of Consultant's liability for damage suffered by the contractor or the subcontractor arising from any alleged breach or negligence of Consultant. You should consult with an attorney experienced in construction contracts and litigation regarding this provision.
7. HAZARDOUS MATERIALS Consultant is responsible only for hazardous materials brought by Consultant onto the site. Client retains ownership and responsibility in all respects for other hazardous materials and associated damage.
8. THIRD PARTIES AND ASSIGNMENT This Contract is intended only to benefit the parties hereto. No person who is not a signatory to this Contract shall have any rights hereunder to rely on this Contract or on any of Consultant’s services or reports without the express written authorization of Consultant. This Contract shall not be assigned by Client without the Consultant’s written consent. This Contract is binding on any successor companies to Client or Consultant, and on the surviving corporation in the event of a merger or acquisition.
9. GOVERNING LAW, SURVIVAL AND FORUM SELECTION The contract shall be governed by laws of the Federal Government. If any of the provisions contained in this agreement are held invalid, the enforceability of the remaining provisions will not be impaired. Limitations of liability, indemnities, representations and warranties by Client will survive termination of this agreement. The signatories represent and warrant that they are authorized by the entities on whose behalf they sign to enter into this contract and that their principals have filed fictitious business name statements, if required. All disputes between Consultant and client related to this agreement will be submitted to the court of the county where Consultant's principal place of business is located and client waives the right to remove the action to any other county or judicial jurisdiction.
7/2017 HANDWRITTEN CHANGES NOT VALID Page 2
(PW Terms) 172
EARTH SYSTEMS
1514 Moffett Street, Suite A | Salinas, CA 93905 | (831) 240-4624 | www.earthsystems.com Prevailing Wage and Accounts Payable Information Request Thank you for this opportunity to be of service on your public works project. Please complete and return this form to allow us to comply with California’s prevailing wage requirements, and to prepare Earth Systems’ invoices in accordance with your organization’s billing requirements in a timely manner. Thank you! Legal Name of Earth Systems
PWC Registration No.
Earth Systems Pacific
1000003643
Earth Systems Project No.
PUBLIC WORKS PROJECT REGISTRATION INFORMATION:
CLIENT’S PROJECT NAME Sand City Mixed Use Trail
DIR PROJECT ID (PWC-100)
APPLICABLE BID
ADVERTISEMENT DATE
CLIENT’S REPRESENTATIVE FOR
DIR PROJECT ID INFORMATION
Name:
E-mail:
Phone No.:
LABOR COMPLIANCE
PROGRAM (LCP) APPLICABLE
TO THIS PROJECT?
Yes or No
If yes, please confirm if Earth Systems will be subject to the LCP and provide a copy of the LCP manual to Earth Systems before start of project.
CLIENT’S BILLING REQUIREMENTS:
PURCHASE ORDER NO.
(if applicable)
ADDITIONAL INFORMATION
REQUIRED ON INVOICES
SPECIFY ANY ADDITIONAL
FORMS OR BILLING FORMATS
REQUIRED TO BE SUBMITTED
WITH INVOICES
(please attach example)
ACCOUNTS PAYABLE CONTACT
INFORMATION
Name:
E-mail:
Phone No.:
INVOICE DELIVERY METHOD E-mail:
Mailing Address:
Date July 1, 2026
Doc. No.: 2606-019.PRP.REV1/ta
173
Traffic Signal Design Services for the Sand City Multi-Use Trail Project in Sand City, California
Project Understanding
Hexagon Transportation Consultants, Inc. will provide traffic signal design services to the Whitson Engineers team for the City of Sand City Multi-Use Trail Final Design project.
The approximately one-mile trail will close a gap in the Monterey Bay Coastal Recreation Trail, extending from the Canyon Del Rey Boulevard (SR 218)/Del Monte Avenue intersection in Seaside to Playa/California Avenue in Sand City. Traffic signal modifications, including new bicycle signals, will be required to accommodate the trail crossing and intersection improvements described below.
Hexagon’s scope includes the following tasks:
• Traffic signal modification design at the Canyon Del Rey Boulevard (SR 218) and Del Monte Avenue intersection (located in the City of Seaside) to accommodate the multi-use trail crossing, including a new bicycle signal and right-turn vehicle signals for the raised bike lane positioned to the right of the right-turn-only lane, and associated signal head, signal pole, conduit, and detection modifications resulting from the bike signal improvements and the new curb bulb out at the northeast corner. • Coordination with and permitting through Caltrans District 5 for the work within SR 218 right-of-way, including the encroachment permit and the anticipated Design Engineering Evaluation Report (DEER) process for the intersection modifications. • Review of the signing and striping plans prepared by Whitson Engineers for conformance with the traffic signal modification design at the intersection. • Traffic engineering assistance to Whitson Engineers throughout the course of the project including technical input for the project's community and stakeholder outreach efforts.
It is our understanding that the civil, landscape, environmental, and survey components of the project, including the trail design, grading, drainage, trailside parking lots, curb ramps, curb bulbouts, and the signing and striping plans, will be designed by Whitson Engineers and its other subconsultants, and that Whitson Engineers will manage all plan submittals and coordination with the City of Sand City and the stakeholder jurisdictions (City of Seaside, TAMC, and Caltrans).
Work Scope
Design Standards
The plans will be designed in accordance with all applicable federal, state, and local regulations and standards, such as, the California Manual on Uniform Traffic Control Devices (CA MUTCD) requirements, the Americans with Disabilities Act (ADA) requirements, Caltrans Standard plans and Specifications, etc. In addition, Hexagon will ensure that equipment specified on the plans is in accordance with City of Seaside preferences.
174
Traffic Signal Design Scope – Sand City Multe Use Trail June 30, 2026
Traffic Signal Improvement Plans
Traffic signal improvement plans will be developed for the intersection of Canyon Del Rey Boulevard (SR 218) and Del Monte Avenue.
Signal Interconnect Plans
Since the existing controller cabinet at the intersection does not appear to be affected by the proposed improvements, it is assumed that any existing signal interconnect cables at the intersection will also be unaffected by the proposed improvements. Therefore, our scope of work does not include the preparation of traffic signal interconnect installation or modification plans. If it is found that signal interconnect facilities (copper or fiber optic) need to be replaced or installed, then additional time and budget may be necessary to develop that plan.
Intersection Safety Lighting Photometric Analysis
Hexagon will conduct a photometric analysis of the safety lighting at the project intersection. The results of the analysis will be presented to the City along with the project plans to verify that the safety lighting layout and luminaire types specified in the design adequately satisfy the City’s lighting standards. Note that this analysis is for signalized intersection only and does not cover new street lighting on the street segments adjacent to the signalized intersection or trail lighting.
Traffic Engineering Design Support
Hexagon will provide input to the project team throughout the design process to ensure that the proposed geometry of new intersection curbs, lane configurations, wheelchair ramps, and crosswalk alignments accommodate the turning movements of design vehicles, are compatible with the safe and efficient operation of the traffic signal systems, and meet ADA standards and City requirements for signal pole and pedestrian push button locations. This effort will also focus on recommending reasonable adjustments to the proposed civil improvements to minimize impacts to existing signal equipment.
Because the Canyon Del Rey Boulevard (SR 218)/Del Monte Boulevard intersection is located within the City of Seaside and within Caltrans State Route 218 right-of-way, Hexagon will provide traffic engineering assistance to support Whitson Engineers in coordinating the signal modification design with the City of Seaside and Caltrans District 5.
Additionally, Hexagon will review signing and striping plans produced by Whitson Engineers for the project and will make recommendations based on traffic engineering industry standards.
Work Tasks
1. Project Management
Project Management and Administration
Throughout the course of the project, Hexagon will conduct periodic billings, summarize project completion status and budget status, as necessary or as requested by Whitson Engineers. We will maintain close communication with the design team to coordinate our design work with other aspects of the project.
Progress Meetings
Hexagon will attend an in-person kick-off meeting with City staff and the project team to discuss the scope of work and goals and objectives of the project. Hexagon will attend monthly progress meetings (via video conference) with the project team and City staff. 175
Traffic Signal Design Scope – Sand City Multe Use Trail June 30, 2026
Obtain and Review Background Information
Hexagon will contact the City of Seaside Public Works Department to research any special requirements the City may have regarding the proposed traffic signal improvements. Hexagon will work with City staff to obtain any relevant background information that may be useful or required to complete the design work, such as traffic studies and as-built plans. We will obtain existing and proposed utility plans from the project team for use in the design of new traffic signal pole locations.
Field Investigations
Hexagon will field-verify existing traffic signal interconnect and street light facilities, the routing of electrical conduits, and the size, location, and contents of existing pull boxes and cabinets near the intersection. Our design base maps will be updated as necessary to accurately reflect existing conditions. Potential conflicts with overhead and underground utilities and obstructions, and other conflicts not readily apparent on the topographic maps will be identified in the field.
Agency Permitting Assistance
Coordination with Caltrans and City of Seaside
It is anticipated that the City of Sand City, the City of Seaside, and Caltrans will be reviewing and providing plan-check comments on the traffic signal plans. Upon receipt of comments from each agency, all comments will be addressed and any conflicting comments between the agencies will be resolved to the satisfaction of each agency.
Caltrans Application Process
Hexagon’s scope includes assisting the team in answering traffic-related questions from Caltrans and answering questions from the project team with respect to completing Caltrans forms and applications.
Per the City’s RFP, it is anticipated that a Design Engineering Evaluation Report (DEER) will be necessary for this project. Hexagon will take the lead on preparing the DEER and will work with the City and project team to collect the necessary information to fill out the various forms and report sections. Some of the key components of this process include purpose and need narrative, proposed scope, traffic operations and collision assessment, right-of-way evaluation, design standards decision document for non-standard features, and a Quality Management Plan.
Our scope and budget for this task include time and cost for Hexagon to attend one (1) meeting at Caltrans headquarters in San Luis Obispo, if necessary. Attendance at additional in-person meetings with Caltrans would require additional budget. Additional meetings with Caltrans staff will be held via video conference, as necessary.
2. Land Surveying
Review Available Survey Data
Hexagon will review available survey data and base maps for the Canyon Del Rey Boulevard/Del Monte Boulevard intersection, identify lacking topographic base map information, and make recommendations for expanding the base map or adding additional data, such as underground utilities.
3. Final Landscape Design
Hexagon has no scope items for this task.
176
Traffic Signal Design Scope – Sand City Multe Use Trail June 30, 2026
4. Engineering Design (PS&E)
Schematic Design
Based on the City’s 30% design plans included in the RFP, it appears the City intends to connect the new Multi-Use trail to the existing Monterey Bay Trail through the Canyon Del Rey Boulevard and Del Monte Boulevard intersection. However, the 30% plans do not currently show adequate width for a two-way multi-use trail to be implemented through the intersection. The additional improvements required to maintain a continuous two-way trail connection through that intersection may be significant, and it is unclear if the City intends for the project to resolve this issue, or if the intent is for counter-flow (eastbound) bicyclists to dismount and operate as pedestrians in the segment adjacent to the intersection. Hexagon will evaluate two-way bike facilities design standards, explore opportunities and constraints, and develop high level schematic drawings early in the design process for coordination with the City and project team, to determine the scope of work in the vicinity of the intersection prior to beginning construction drawings.
Preparation of Base Maps
Hexagon will prepare base maps for the traffic signal improvement plans utilizing files containing topographic mapping and proposed civil improvements furnished by Whitson Engineers. The mapping files must contain the following information:
• Location and configuration of existing and new curb, gutter, edge of pavement, sidewalk, driveways, and wheelchair ramps.
• Location of existing and new street lights, utility poles, and large trees. • Existing and proposed intersection and roadway striping, including lane lines, legends, arrows, and crosswalk locations.
• Locations of existing and proposed property lines and right-of-way lines.
All of the elements described above must be provided within the limits specified below before Hexagon can begin work on the design plans:
• The Canyon Del Rey Boulevard and Del Monte Boulevard intersection, with at least 200 feet on all intersection approaches.
The mapping files provided by Whitson Engineers must also show the locations of existing pull boxes, utility vaults, cabinets, street light poles, utility poles, traffic signal poles, and all existing above and below ground utilities on all four quadrants of the intersection.
If topographical mapping is not available within the limits specified above, then additional time and budget may be necessary for Hexagon to extend the coverage of base maps.
Plans, Specifications, and Estimates
Plans - The construction plans will include a layout of the proposed improvements at the intersection and will include all design elements, full equipment specifications, and any other features necessary for complete and biddable construction plans.
Specifications - A separate set of Technical Special Provisions for electrical systems construction, if required by the City, will be prepared for inclusion in the Project Specifications.
Cost Estimates - A detailed estimate of probable construction costs will be prepared and will be submitted for review along with the construction plans. 177
Traffic Signal Design Scope – Sand City Multe Use Trail June 30, 2026
Review Submittals - Our scope and fee include time and cost for up to three submittals of the construction plans, specifications, and cost estimates to the City for review and comment. Unless specifically requested otherwise, all review submittals will be made electronically to Whitson Engineers.
As part of each submittal, we will return the marked-up plans from the previous submittal along with a list of the City comments and our responses.
Final Design (Bid Set Submittal)
Upon notification that the 100% PS&E have been approved, Hexagon will prepare final deliverables (construction documents) which will include PDFs of the plan sheets featuring the signature of a responsible Professional Engineer.
Traffic Design Coordination
We will coordinate the improvements at the Canyon Del Rey Boulevard (SR 218) and Del Monte Boulevard intersection with the design of other aspects of the proposed new trail. As discussed above under Task 1, Hexagon will assist with Caltrans coordination with respect to improvements at the Canyon Del Rey Boulevard and Del Monte Boulevard intersection.
Meetings
Hexagon will participate in conference calls and video conferences with the project team and/or City staff, as necessary, during the design phase of the project. In-person meetings are not included in this scope of work.
5. Community and Stakeholder Outreach Support
The City of Sand City will lead all community engagement for the project. Hexagon will support the project team by providing information for technical exhibits related to the traffic signal modification and the trail crossing at the Canyon Del Rey Boulevard/Del Monte Boulevard intersection. Additionally, our scope of work and fee assumes Hexagon staff attendance at the following meetings as a technical resource to answer traffic engineering and design questions:
• Sand City City Council meetings (up to three meetings), • Stakeholder Jurisdictions board and committee meetings (up to two meetings), • Staff-level coordination meetings (up to two meetings), and • Community workshops in Sand City and Seaside (up to two workshops). 178
2 ATTACHMENT B
COST PROPOSALS AND RATE SHEET
(On a Separate Sheet)
179
City of Sand City | RFP 26-03 Proposal and Interview Rankings Page 1 City of Sand City
Proposal and Interview Rankings
RFP 26-03: Sand City Multi-Use Trail Final Design | Federal Project No. 5366(002)
1. Written Proposal Evaluation
Scores
Whitson
Engineers Kimley-Horn Harris &Associates GHD
Reviewer 1: Vibeke Norgaard 105 80 75 85
Reviewer 2: Michael Groves 93 78 75 98
Reviewer 3: Nick McIlroy 98 110 84 93
Reviewer 4: Richard Deal 88 97 73 96
Ranking
Whitson
Engineers Kimley-Horn Harris &Associates GHD
Reviewer 1: Vibeke Norgaard 1 3 4 2
Reviewer 2: Michael Groves 2 3 4 1
Reviewer 3: Nick McIlroy 2 1 4 3
Reviewer 4: Richard Deal 3 1 4 2
Average Rank 2.00 2.00 4.00 2.00
Overall Rank 1 (tie) 1 (tie) 4 1 (tie)
2. Interview Evaluation and Final Ranking
Scores
Whitson
Engineers Kimley-Horn Harris &Associates GHD
Reviewer 1: Vibeke Norgaard 110 77 70 91
Reviewer 2: Michael Groves 96 72 75 83
Reviewer 3: Nick McIlroy 107 74 70 83
Reviewer 4: Richard Deal 98 79 76 87
Ranking
Whitson
Engineers Kimley-Horn Harris &Associates GHD
Reviewer 1: Vibeke Norgaard 1 3 4 2
Reviewer 2: Michael Groves 1 4 3 2
Reviewer 3: Nick McIlroy 1 3 4 2
Reviewer 4: Richard Deal 1 3 4 2
Average Rank 1.00 3.25 3.75 2.00
Overall Rank 1 3 4 2
180
3 ATTACHMENT C
INSURANCE REQUIREMENTS
Without limiting CONSULTANT’s indemnification of CITY, and prior to commencement of Work, CONSULTANT shall obtain, provide and maintain at its own expense during the term of this AGREEMENT, policies of insurance of the type and amounts described below and, in a form, satisfactory to CITY.
General liability insurance. CONSULTANT shall maintain commercial general liability insurance with coverage at least as broad as Insurance Services Office form CG 00 01, in an amount not less than $1,000,000 per occurrence, $2,000,000 general aggregate, for bodily injury, personal injury, and property damage. The policy must include contractual liability that has not been amended. Any endorsement restricting standard ISO “insured contract” language will not be accepted.
Automobile liability insurance. CONSULTANT shall maintain automobile insurance at least as broad as Insurance Services Office form CA 00 01 covering bodily injury and property damage for all activities of the Consultant arising out of or in connection with Work to be performed under this AGREEMENT, including coverage for any owned, hired, non-owned or rented vehicles, in an amount not less than $1,000,000 combined single limit for each accident.
Professional liability (errors & omissions) insurance. CONSULTANT shall maintain professional liability insurance that covers the Services to be performed in connection with this AGREEMENT, in the minimum amount of $1,000,000 per claim and in the aggregate. Any policy inception date, continuity date, or retroactive date must be before the effective date of this AGREEMENT and CONSULTANT agrees to maintain continuous coverage through a period no less than three (3) years after completion of the services required by this AGREEMENT.
Workers’ compensation insurance. CONSULTANT shall maintain Workers’ Compensation Insurance (Statutory Limits) and Employer’s Liability Insurance (with limits of at least $1,000,000).
CONSULTANT shall submit to CITY, along with the certificate of insurance, a Waiver of Subrogation endorsement in favor of CITY, its officers, agents, employees and volunteers.
Umbrella or excess liability insurance. [Optional depending on limits required]. CONSULTANT shall obtain and maintain an umbrella or excess liability insurance policy with limits that will provide bodily injury, personal injury and property damage liability coverage at least as broad as the primary coverages set forth above, including commercial general liability, automobile liability, and employer’s liability. Such policy or policies shall include the following terms and conditions:
• A drop down feature requiring the policy to respond if any primary insurance that would otherwise have applied proves to be uncollectible in whole or in part for any reason; • Pay on behalf of wording as opposed to reimbursement; • Concurrency of effective dates with primary policies; • Policies shall “follow form” to the underlying primary policies; and • Insureds under primary policies shall also be insureds under the umbrella or excess policies.
Other provisions or requirements
181
4 Proof of insurance. CONSULTANT shall provide certificates of insurance to CITY as evidence of the insurance coverage required herein, along with a waiver of subrogation endorsement for workers’ compensation.
Insurance certificates and endorsements must be approved by City’s Risk Manager prior to commencement of performance. Current certification of insurance shall be kept on file with CITY at all times during the term of this contract. CITY reserves the right to require complete, certified copies of all required insurance policies, at any time.
Duration of coverage. CONSULTANT shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damages to property, which may arise from or in connection with the performance of the Work hereunder by CONSULTANT, his agents, representatives, employees or subconsultants.
Primary/noncontributing. Coverage provided by CONSULTANT shall be primary and any insurance or selfinsurance procured or maintained by CITY shall not be required to contribute with it. The limits of insurance required herein may be satisfied by a combination of primary and umbrella or excess insurance. Any umbrella or excess insurance shall contain or be endorsed to contain a provision that such coverage shall also apply on a primary and non-contributory basis for the benefit of CITY before the CITY’s own insurance or selfinsurance shall be called upon to protect it as a named insured.
City’s rights of enforcement. In the event any policy of insurance required under this AGREEMENT does not comply with these specifications or is canceled and not replaced, CITY has the right but not the duty to obtain the insurance it deems necessary and any premium paid by CITY will be promptly reimbursed by CONSULTANT or CITY will withhold amounts sufficient to pay premium from CONSULTANT payments. In the alternative, CITY may cancel this AGREEMENT.
Acceptable insurers. All insurance policies shall be issued by an insurance company currently authorized by the Insurance Commissioner to transact business of insurance or is on the List of Approved Surplus Line Insurers in the State of California, with an assigned policyholders’ Rating of A- (or higher) and Financial Size Category Class VI (or larger) in accordance with the latest edition of Best’s Key Rating Guide, unless otherwise approved by the City Manager.
Waiver of subrogation. All insurance coverage maintained or procured pursuant to this Agreement shall be endorsed to waive subrogation against CITY, its elected or appointed officers, agents, officials, employees and volunteers or shall specifically allow CONSULTANT or others providing insurance evidence in compliance with these specifications to waive their right of recovery prior to a loss. CONSULTANT hereby waives its own right of recovery against CITY, and shall require similar written express waivers and insurance clauses from each of its subconsultants.
Enforcement of contract provisions (non estoppel). CONSULTANT acknowledges and agrees that any actual or alleged failure on the part of the CITY to inform CONSULTANT of non-compliance with any requirement imposes no additional obligations on the CITY nor does it waive any rights hereunder.
Requirements not limiting. Requirements of specific coverage features or limits contained in this Section are not intended as a limitation on coverage, limits or other requirements, or a waiver of any coverage normally provided by any insurance. Specific reference to a given coverage feature is for purposes of clarification only as it pertains to a given issue and is not intended by any party or insured to be all inclusive, or to the 182
5 exclusion of other coverage, or a waiver of any type. If the Consultant maintains higher limits than the minimums shown above, the CITY requires and shall be entitled to coverage for the higher limits maintained by the Consultant. Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to the CITY.
Notice of cancellation. Consultant agrees to oblige its insurance agent or broker and insurers to provide to CITY with a thirty (30) day notice of cancellation (except for nonpayment for which a ten (10) day notice is required) or nonrenewal of coverage for each required coverage.
Additional insured status. General liability policies shall provide or be endorsed to provide that CITY and its officers, officials, employees, and agents, and volunteers shall be additional insureds under such policies. This provision shall also apply to any excess/umbrella liability policies.
Prohibition of undisclosed coverage limitations. None of the coverages required herein will be in compliance with these requirements if they include any limiting endorsement of any kind that has not been first submitted to CITY and approved of in writing.
Separation of insureds. A severability of interests provision must apply for all additional insureds ensuring that Consultant’s insurance shall apply separately to each insured against whom claim is made or suit is brought, except with respect to the insurer’s limits of liability. The policy(ies) shall not contain any crossliability exclusions.
Pass through clause. CONSULTANT agrees to ensure that its subconsultants, subcontractors, and any other party involved with the project who is brought onto or involved in the project by CONSULTANT, provide the same minimum insurance coverage and endorsements required of CONSULTANT. CONSULTANT agrees to monitor and review all such coverage and assumes all responsibility for ensuring that such coverage is provided in conformity with the requirements of this section. CONSULTANT agrees that upon request, all Agreements with consultants, subcontractors, and others engaged in the project will be submitted to CITY for review.
City’s right to revise specifications. The CITY reserves the right at any time during the term of the contract to change the amounts and types of insurance required by giving the CONSULTANT ninety (90) days advance written notice of such change. If such change results in substantial additional costs to the CONSULTANT, the CITY and CONSULTANT may renegotiate CONSULTANT’s compensation.
Self-insured retentions. Any self-insured retentions must be declared to and approved by CITY. CITY reserves the right to require that self-insured retentions be eliminated, lowered, or replaced by a deductible. Selfinsurance will not be considered to comply with these specifications unless approved by CITY.
Timely notice of claims. CONSULTANT shall give CITY prompt and timely notice of claims made or suits instituted that arise out of or result from CONSULTANT’s performance under this AGREEMENT, and that involve or may involve coverage under any of the required liability policies.
Additional insurance. CONSULTANT shall also procure and maintain, at its own cost and expense, any additional kinds of insurance, which in its own judgment may be necessary for its proper protection and prosecution of the work.
183
6 EXHIBIT A: Scope of Work and Schedule
(On a Separate Sheet)
184
WORK PLAN
Project Understanding
The Sand City Multi-Use Trail Project will transform the former Monterey Branch Line rightof-way of the historic Southern Pacific Railroad into a vibrant recreational and active transportation corridor. The project extends through the City of Sand City from Playa Avenue to State Route 218 in Seaside, utilizing a corridor currently owned by the Transportation Agency for Monterey County (TAMC). While portions of the existing corridor remain unused, other segments are presently used by adjacent property owners.
The primary project element is the construction of an asphalt concrete multi-use path throughout the corridor. In select locations, an adjacent pedestrian path will provide dedicated space for walkers and runners. The project also includes a variety of trailside amenities designed to enhance the user experience, including picnic areas, outdoor fitness stations, and new public parking facilities. The remaining portions of the right-ofway will be landscaped to establish a continuous greenbelt and improve the visual character of the corridor.
The trail will cross Olympia Avenue, Contra Costa Avenue, and Tioga Avenue. To ensure safe and convenient access, proposed improvements at these intersections include curb extensions (bulb-outs) and decorative, raised, high-visibility crosswalks.
Rectangular Rapid Flashing Beacons (RRFBs) are proposed at the Contra Costa Avenue crossing to further enhance pedestrian and bicyclist safety. Decorative, high-visibility crosswalks will also be installed where the trail crosses the proposed parking lot driveways.
At the trail’s southern terminus, improvements are proposed at State Route 218 to provide a safer and more direct connection to the existing Monterey Bay Sanctuary Scenic Trail. These improvements are identified as an Optional Service because they may ultimately be delivered as part of a separate project.
Improvements at the Playa Avenue intersection are not included within the scope of this project, as they are being implemented separately by Monterey-Salinas Transit (MST) as part of the Bus Rapid Transit (BRT) project currently under construction.
Upon completion, the Sand City Multi-Use Trail Project will create an attractive, milelong linear park and non-motorized transportation facility. The project will provide new opportunities for walking, bicycling, recreation, fitness, and community gathering while enhancing connectivity, safety, and environmental quality throughout the corridor. 185
WORK PLAN
Task 1: Project Management
Task 1.1: General Project Management
Whitson Engineers will serve as the Consultant Team’s Project Manager. Project management tasks will include:
• Prepare and update the project schedule
• Coordinate progress meetings
• Effectively communicate with City Staff regarding progress • Coordinate with other agencies as needed
• Manage subconsultants
• Oversee all the project components listed in this Work Plan • Budget, schedule, and resource management
• Ensure Quality Assurance and Quality Control Measures are completed • Invoicing
Nathaniel Milam will serve as Whitson Engineer’s Project Manager. Richard Weber and Andrew Hunter will provide quality control, design oversight, and constructability review.
Task 1.2: Progress Meetings
Coordinate the following meetings:
1. Kickoff meeting with the City and project team. The kickoff meeting will provide a project overview to the project team; introduce the project team to the city; review schedule, scope and cost controls; and set communication protocols.
2. Monthly coordination meetings for the duration of the project. Subconsultants will attend as needed. Progress meetings may be in person or via Teams/Zoom, as deemed appropriate.
Prepare meeting agendas and meeting minutes highlighting decisions made and action items, and will distribute them to the City and design team.
Task 1.2 Deliverables
Meeting agendas
Meeting minutes and action items
Task 1.3: Review of Existing Documents
Review project documents to understand the prior work performed and commitments made, outreach status and stakeholder engagement work completed, and ensure the final design effort is completed accordingly.
186
WORK PLAN
Project documents to review include environmental documentation; permits and agreements; available mapping and preliminary design drawings; stakeholder outreach materials, meeting summaries and correspondence; project memoranda; and other materials as provided by the City and as publicly available.
Task 1.3 Deliverables
Memorandum outlining documents reviewed and any follow-up needed Task 1.4 Field Review
1. Lead a field review with city staff and other parties (such as City of Seaside and TAMC) as determined by the city.
2. Perform additional field reviews as needed during the design phase.
Task 1.4 Deliverables
Field review notes.
Task 1.5: Agreements and Permits
Caltrans Encroachment Permit (Optional Task)
An Encroachment Permit will be required in the event work is proposed within the Caltrans right of way at State Route 218, or affecting the intersection’s operations (see Task 5). In this event, Whitson Engineers will prepare and submit the Caltrans Encroachment Permit Application and coordinate with Caltrans.
City of Seaside Encroachment Permit (Optional Task)
If a City of Seaside Encroachment Permit is required for preconstruction activities, Whitson Engineers will prepare and submit the Encroachment Permit Application and coordinate with the city.
TAMC Use Agreement (Optional Task)
Whitson Engineers will provide technical assistance to the City as requested for the TAMC Use Agreement. This may include review of legal descriptions and plats. (Preparation of legal descriptions and plats is included in Task 8.1.) Task 1.5 Deliverables
Permit Applications.
187
WORK PLAN
Task 2: Land Surveying
Task 2.1: Review Available Survey Data
Review available mapping to identify what additional survey work is needed for final design and permitting. Review will include project information provided by the city; utility system maps requested of and provided by utility owners; recorded maps available from the County Surveyor; and maps and as-builts provided by Sand City, Seaside, Caltrans and TAMC.
We understand the existing mapping consists of a 1”=40’ scale, 1-foot-contour interval aerial survey; right of way mapping; and limited utility mapping.
We understand a pre-construction Record of Survey (for monument preservation) will be completed prior to construction by the City, and is therefore excluded from our scope.
Task 2.1 Deliverables:
Memorandum (including site photographs and maps as applicable) outlining results of the review and providing recommendations for subsequent work.
Task 2.2: Supplemental Field Surveying
Perform supplemental surveying as required for final design. The precise scope of this Optional Task is not known at this time, but may include:
1. Recover existing site control and search for additional record boundary monuments.
2. Review title information and plot the TAMC right of way, city street and highway rights of way, and adjacent parcels as appropriate. Review and plot easements and lease agreements, as applicable.
3. Set ground control point (GCP) targets throughout the project area for use as control and ground-truthing for a small Unmanned Aircraft System (sUAS, “Drone”) survey.
4. Coordinate airspace authorization and conduct a sUAS mission to collect lowaltitude nadir aerial photography of the site. Utilizing GCP’s and RTK-GPS positioning, process the photography to produce a current, high-resolution digital orthophoto and digital surface model of the project corridor.
5. Conduct supplemental ground-based topographic surveys where needed for final design and permitting. Locate all observed site features including structures, hardscape improvements (pavements, curbs, gutters, walkways), fences, surface and overhead utility structures, trees greater than 6” diameter (with approximate drip lines), terrain grade breaks, and spot elevations as appropriate for design. Where needed, measure storm drain and sanitary sewer invert elevations and note pipe sizes and directions within manholes within the project area.
188
WORK PLAN
6. Plot existing utility information based on utility owner maps and surveyed surface evidence (ASCE 38-02 “Utility Quality C”).
7. Prepare an updated existing conditions base map for the project including the city-provided aerial mapping, updated boundary mapping, sUAS aerial imagery, supplemental survey information, and utility information.
Task 2.2 Deliverables
Updated existing conditions base map (AutoCAD 2018 format) Rectified digital orthophoto (0.2’ pixel resolution or better) in .JPG /.JGW or .TIF/.TFW format
Task 3: Final Landscape Design
BFS Landscape Architects will prepare the landscape architectural design for the project, advancing the current conceptual design through final Landscape Plans, Specifications, and Estimate (PS&E). Design elements include planting, irrigation, site furnishings, hardscape materials that are not covered by the civil design, and landscape restoration.
1. Prepare up to three alternative design concepts. The intent will be to obtain the city’s direction on conceptual trail aesthetics and equipment selection before moving into final design.
2. Prepare 60%, 90% and 100% Drawings for review, permitting, bidding and construction. The following sheets are anticipated:
Landscape Cover Sheet
Landscape General Notes
Landscape Construction Plan
Landscape Layout Plan
Site Furnishing &Trail Amenities Plan
Landscape Construction Details
Irrigation Plan
Planting Plan
Restoration Planting Plan
Irrigation and Planting Details
3. Prepare 60%, 90% and 100% Construction Cost Estimates
4. Prepare 90% and 100% Specifications
5. Participate in design review meetings and incorporate review comments.
Task 3 Deliverables
189
WORK PLAN
Up to three alternative landscape design concepts
60%, 90% and 100% Landscape PS&E
Task 4: Engineering Design
Geotechnical Engineering
Earth Systems will perform a geotechnical engineering investigation to identify and evaluate the subsurface soil and groundwater conditions at the site, and generate design-level engineering recommendations for development the project.
Recommendations will be provided for site grading, drainage, infiltration, trenching and utilities, paving, and construction observations and testing.
Civil Engineering
Whitson Engineers will prepare the Civil Plans, Specifications and Estimates (PS&E) and supporting documents with primary submittals provided at the 60% (Draft), 90% (Plan Check) and 100% (Bid Set) stages. Each submittal will reflect the comments received from the prior submittal.
1. Prepare 60%, 90% and 100% Drawings for permitting, bidding and construction.
The following sheets are anticipated:
General
Title Sheet and Location Map
General Notes, Legends and Abbreviations
Temporary Water Pollution Control Plan
Temporary Water Pollution Control Notes and Details
Civil
Key Map
Typical Sections
Demolition Plans
Construction Plans
Grading Plans (Plan and Profile Sheets)
Retaining Walls (if required)
Construction Details
Utility Plans
Construction Area Signs
Construction Staging (if required)
Signing and Striping Plans
190
WORK PLAN
Signing and Striping Notes, Details and Quantities
Summary of Quantities
2. Estimate 60%, 90% and 100% earthwork volumes.
3. Prepare 60%, 90% and 100% Construction Cost Estimates.
4. Prepare 60%, 90% and 100% Specifications.
5. Prepare 60%, 90% and 100% Storm Water Control Plan (SWCP) including required calculations, narrative, and exhibits.
6. Prepare 90% and 100% Storm Water Operation and Maintenance Plan (O&M Plan) outlining the long term, post-construction activities associated with the proposed Stormwater Control Measures (SCMs).
Electrical Engineering and Lighting Design
Aurum Consulting Engineers will prepare the project’s electrical and lighting PS&E for the proposed trail and parking lots. Electrical and lighting PS&E will be prepared at the 60%, 90% and 100% stages.
We anticipate electrical service will be provided by PG&E. (Solar lights will be evaluated, but are not anticipated to be the most lifecycle-cost-effective alternative.) We anticipate the project will use decorative gooseneck lights along the trail and either standard or decorative gooseneck lights at the proposed parking lots. Street lighting will also be evaluated for the street crossings.
Task 4 Deliverables
Geotechnical Investigation Report and Geotechnical Review Letter 60%, 90% and 100% Civil and Electrical PS&E
Storm Water Control Plan
Storm Water Operation and Maintenance Plan
Task 5: Intersection Improvements at SR 218 (Optional Task) Whitson Engineers and Hexagon Transportation Consultants will prepare PS&E and supporting documents for proposed changes to the intersection geometry and traffic signals at the intersection of State Route 218 and Del Monte Boulevard to accommodate the multi-use trail crossing the north leg of the intersection.
Improvements would include a new bicycle signal and right-turn vehicle signals, curb bulb-outs and sidewalk widening for the multi-use trail connection along Del Monte Boulevard, and associated vehicular lane modifications.
Hexagon Transportation Consultants will prepare the project’s traffic signal design and PS&E should this optional task be awarded. Whitson Engineers will prepare the roadway PS&E and will collaborate with Hexagon to prepare the required Caltrans permit documents, which are anticipated to be primarily a Design Engineering Evaluation 191
WORK PLAN
Report (DEER) and an Encroachment Permit.
Task 5 Deliverables
60%, 90% and 100% Engineering PS&E
Design Engineering Evaluation Report (DEER)
Task 6: NEPA Support
Denise Duffy & Associates (DD&A), under subcontract to Whitson Engineers, will prepare the following environmental technical documentation to support Caltrans environmental review and final NEPA clearance for the project.
Biological Resources Report
Intentionally omitted.
Area of Potential Effects (APE) Map
Intentionally omitted.
Archaeological Survey Report (ASR)
Intentionally omitted.
Hazardous Waste Technical Memorandum
DD&A will retain Cornerstone Earth Group to prepare a Hazardous Waste Technical Memorandum consisting of a high-level hazardous materials screening sufficient to satisfy Preliminary Environmental Study requirements. Additional hazardous materials investigations, site assessments, sampling, testing, or remediation planning are excluded from this scope and may be completed through an amendment, if required.
Environmental Commitment Record
DD&A will prepare an Environmental Commitments Record summarizing environmental commitments, avoidance and minimization measures, permit conditions, and mitigation requirements identified through technical studies and agency coordination.
The commitments record will be provided in a format suitable for incorporation into project environmental documentation and construction specifications.
Task 6 Deliverables
Biological Resources Report
Area of Potential Effects (APE) Map
Archaeological Survey Report (ASR)
192
WORK PLAN
Hazardous Waste Technical Memorandum
Environmental Commitment Record
Task 7: Community Outreach and Grant Support
Task 7.1: Community and Stakeholder Meetings and Outreach Our team will support the City in its community outreach and stakeholder meetings by preparing maps, presentation graphics, and written information, and by attending meetings and participating in presentations to the City Council, the community, and stakeholders.
While the entire consultant team will support the city’s community and stakeholder outreach effort, BFS will spearhead this task due to their ongoing history with the project, and expertise in supporting public outreach. Recognizing the significance of this project, and of continuing a robust outreach program, we propose the following:
Graphic Services
1. Prepare and update project overview exhibits.
2. Prepare up to three (3) corridor and vicinity maps.
3. Prepare up to six (6) illustrative site plans and enlarged project exhibits.
4. Prepare up to four (4) landscape character, planning, and material palette exhibits.
5. Prepare up to six (6) illustrative sections and design diagrams.
6. Prepare up to four (4) rendered perspectives or photo simulations, as appropriate.
7. Prepare presentation boards and digital graphics for public meetings.
8. Prepare graphic exhibits supporting future grant applications, as requested.
9. Revise graphic materials in response to City, stakeholder, and agency comments.
Community Engagement Services
10. Attend one (1) project kickoff meeting.
11. Participate in up to six (6) stakeholder and community meetings/workshops.
12. Participate in up to four (4) City Council, Commission, or committee meetings, as requested.
13. Present landscape architectural concepts, graphics, and visual exhibits.
14. Respond to questions related to the landscape architecture and visual character of the Project.
193
WORK PLAN
15. Revise and update outreach materials in response to stakeholder and public input.
Task 7 Deliverables
Maps, presentation graphics, and narrative information as noted Meeting attendance at meetings
Meeting notes and action items
Task 7.2: Grant Support
Our team will provide technical support to the City in its search for future grant funding.
Such technical support may include preparation of specific quantity and cost estimates, and cost/benefit analyses.
Task 8: Right of Way and Utilities (Optional Task)
Task 8.1: Right of Way
We understand the city is currently coordinating with the City of Seaside and TAMC to acquire rights via temporary construction easements and use agreements (no acquisition of private land is anticipated).
Therefore, this Optional Task entails preparation of legal descriptions and plats as may be requested by the city to support this effort.
Task 8.2: Utility Coordination
Provide Utility Coordination if needed to address utility conflicts. At this time we understand no utilities are anticipated to require relocation (no utilities are believed to exist within the TAMC right of way, except at the street crossings) and therefore no utility coordination is anticipated. Utility coordination, if required, could consist of preparation of Utility Verification Letter to Owner, Utility Conflict Plans, Utility Relocation Cost Estimates, Right of Way Data Sheet, Relocation Claim Letter to Owner, Report of Investigation, Utility Agreements, and Notice to Owner letters.
Task 9: Bid Phase Support
Our team will provide design support during the bidding phase of the project. Services may include:
1. Participate in a nonmandatory Pre-Bid Site Walk
2. Prepare Bid Addenda and responses to Bidder Inquiries
3. Revisions to the Plans and Specifications, if required
4. Review the bids received and prepare the Bid Summary 194
WORK PLAN
Assumptions
1. Project will be subject to review and approval by TAMC (Use Agreement), Sand City and City of Seaside (Encroachment Permits). No retaining walls (over 4-feet tall) will be needed, therefore no Building Permit will be required from Sand City or Seaside.
2. Project will be subject to review and approval by Caltrans only in the event Optional Task 5 is awarded.
3. The project will not be subject to Coastal Commission review.
4. Design and permitting will be completed within approximately 12 months.
5. Project will be subject to the Regional Post-Construction Requirements (PCRs) as well as city-specific drainage requirements.
6. The project SWPPP will be deferred and will be prepared by the construction contractor.
7. Caltrans Standard Special Provisions (SSPs) will be used as the specifications template.
8. Relocation of public utilities is not anticipated.
9. Other assumptions, as listed in our subconsultant proposals.
Exclusions
The following work is specifically excluded from the Engineer’s Scope of Services:
1. Utility relocation design
2. Structural engineering (including retaining wall design)
3. Construction phase services
4. Other exclusions, as listed in our subconsultant proposals. 195
7 EXHIBIT B: Cost Proposals and Rate Sheet
(On a Separate Sheet)
196
Note: Mark-ups are Not Allowed
Consultant
Project No. Contract No. Date 09/08/2026
DIRECT LABOR
Hours
200
480
40 360
360
20 360
1208
80 40
LABOR COSTS
a) Subtotal Direct Labor Costs
b) Anticipated Salary Increases (see Antcipated Salary Increases page for calculations) c) Total Direct Labor Costs [(a) + (b)] $ 155,881.84
INDIRECT COSTS
d) Fringe Benefits ( Rate: 29.34%
) e) Total Fringe Benefits [(c) x (d)] $ 45,735.73
f) Overhead ( Rate: 41.02%) $ 63,942.73
h) General and Administrative ( Rate: 59.00%
) i) Gen & Admin [(c) x (h)] $ 91,970.28
j) Total Indirect Costs [(e) + (g) + (i)] $ 201,648.74
FIXED FEE
k) TOTAL FIXED FEE [(c) + (j)]* fixed fee 10%
] $ 35,753.06
Quatity Unit
l) TOTAL OTHER DIRECT COSTS $
-
Subconsultant 1: $188,261
Subconsultant 2: $31,614
Subconsultant 3: $15,503
Subconsultant 4: $8,604
Subconsultant 5: $38,988
$ 282,969.82
$ 282,969.82
$ 676,253.46
1. Calculate average hourly rate for 1st year of the contract (Direct Labor Subtotal divided by total hours) Direct Labor
Subtotal per
Cost Proposal
Total
Hours per
Cost
Proposal
Avg Hourly
Rate
$152,079.84 / 2068
= $73.54 Year 1 Avg Hourly Rate
2. Calculate hourly rate for all periods (Increase the Average hourly rate for a period by proposed escalation %) Avg Hourly
Rate
Proposed
Escalation
Year 1 $73.54 + 5%= $77.22
Year 2 $77.22 + 5%= $81.08
Year 3 $81.08 + 5%
= $85.13 Year 4 Avg Hourly Rate
Year 4 $85.13 + 5%= $89.39 Year 5 Avg Hourly Rate
3. Calculate estimated hours per year (Multiply estimate % each period by total hours) Estimated %
Completed
Each Period
Total
Hours per
Cost
Proposal
Total Hours per
Period
Year 1 50.00%* 2068
= 1034 Estimated Hours Year 1
Year 2 50.00%* 2068
= 1034 Estimated Hours Year 2
Year 3 0.00%* 2068=0 Estimated Hours Year 3
Year 4 0.00%* 2068=0 Estimated Hours Year 4
Year 5 0.00%* 2068=0 Estimated Hours Year 5
Total 100% Total= 2068
4. Calculate Total Costs including Escalation (Multiply average hourly rate by the number of hours) Avg Hourly
Rate
Estimated
Hours
(calculated above) (calculated
above)
Year 1 $73.54 * 1034= $76,039.92 Estimated Hours Year 1 Year 2 $77.22 * 1034
= $79,841.92 Estimated Hours Year 2
Year 3 $81.08 *0= $0.00 Estimated Hours Year 3
Year 4 $85.13 *0= $0.00 Estimated Hours Year 4
Year 5 $89.39 *0= $0.00 Estimated Hours Year 5 = $155,881.84 = $152,079.84 = $3,802.00 Transfer to Page 1 Direct Labor Subtotal before escalation
Estimated total of Direct Labor Salary Increase
Exhibit 10-H1 Cost Proposal
Certification of Direct Costs:
I, the undersigned, certify to the best of my knowledge and belief that all direct costs identified on the cost proposal(s) in this contract are
1. Generally Accepted Accounting Principles (GAAP)
Cost
Per Period
Total Direct Labor Cost with Escalation
Year 2 Avg Hourly Rate
Year 3 Avg Hourly Rate
Actual Cost-Plus-Fixed Fee or Lump Sum or Firm Fixed Price Contracts (Calculations for Anticipated Salary Increases)
5 Year
Contract Duration
(n) TOTAL OTHER DIRECT COSTS INCLUDING SUBCONSULTANTS [(l) + (m)] TOTAL COST [(c) + (j) + (k) + (n)]
Exhibit 10-H1 Cost Proposal
m) SUBCONSULTANTS' COSTS (Add additional pages if necessary) BFS
DD&A
Earth Systems
Aurum
(m) TOTAL SUBCONSULTANS' COSTS
Hexagon
$0.00 $ -
$0.00 $ -
$0.00 $ -
$0.00 $ -
$ 152,079.84
$ 3,802.00
g) Overhead [(c) x (f)
l) CONSULTANT'S OTHER DIRECT COSTS (ODC) - ITEMIZE (Add additional pages if necessary) Description of Item Unit Cost Total
Associate Engineer Daniel Garrett $45.00 $ 16,200.00
Field Survey Crew 2 Person DIR Chief of Party and Rodman $190.69 $ 15,255.20 Civil Engineer Emily Imfeld $53.50 $ 19,260.00
Administrative Support Adam Tucker $55.50 $ 2,220.00
Land Surveyor Mike Hink $75.00 $ 1,500.00
Associate Surveyor Jon Bell $54.00 $ 6,480.00
Field Survey Crew 1 Person DIR Chief of Party $100.58 $ 804.64 Civil Engineer Brent Edelman $55.00 $ 19,800.00
Principal Richard Weber $145.00 $ 29,000.00
Senior Civil Engineer Nathaniel Milam $80.50 $ 38,640.00 Senior Land Surveyor Thomas Hannah $73.00 $ 2,920.00
Sand City multi-use trail 4927
Classification/Title Name Actual Hourly Rate Total
Exhibit 10-H1 Cost Proposal
Cost-Plus-Fixed Fee or Lump Sum or Firm Fixed Price Contracts (Design, Engineering and Environmental Studies)
Whitson Engineers dba Whitson and Associates, Inc
Prime Consultant Subconsultant 2nd Tier Subconsultant
197
Name: Title*:
Signature: Date of Certification (mm/dd/yyyy): 09/08/2026 Email: Phone Number:
Address:
List services the consultant is providing under the proposed contract:
2. Terms and conditions of the contract
3. Title 23 United States Code Section 112 - Letting of Contracts
4. 48 Code of Federal Regulations Part 31 - Contract Cost Principles and Procedures
5. 23 Code of Federal Regulations Part 172 - Procurement, Management, and Administration of
6. 48 Code of Federal Regulations Part 9904 - Cost Accounting Standards Board (when applicable) All costs must be applied consistently and fairly to all contracts. All documentation of compliance must be retained in the project files and be 6 Harris Court, Monterey, CA 93940
*An individual executive or financial officer of the consultant’s or subconsultant’s organization at a level no lower than a Vice Professional Civil Engineering and Land Surveying services Local governments are responsible for applying only cognizant agency approved or Caltrans accepted Indirect Cost Rate(s).
Prime Consultant or Subconsultant Certifying:
Kimberley Woltman CFO
[email protected] 831-649-5225
198
Note: Mark-ups are Not Allowed
Consultant
Project No. Contract No. Date 8/12/2026
DIRECT LABOR
Hours
40 160
80 80
80 LABOR COSTS
a) Subtotal Direct Labor Costs
b) Anticipated Salary Increases (see Antcipated Salary Increases page for calculations) c) Total Direct Labor Costs [(a) + (b)] $ 31,734.00
INDIRECT COSTS
d) Fringe Benefits ( Rate: 29.34% ) e) Total Fringe Benefits [(c) x (d)] $ 9,310.76 f) Overhead ( Rate: 41.02% ) $ 13,017.29
h) General and Administrative ( Rate: 59.00% ) i) Gen & Admin [(c) x (h)] $ 18,723.06 j) Total Indirect Costs [(e) + (g) + (i)] $ 41,051.10
FIXED FEE
k) TOTAL FIXED FEE [(c) + (j)]* fixed fee 10% ] $ 7,278.51 Quatity Unit
l) TOTAL OTHER DIRECT COSTS $ -
Subconsultant 1: $128,895
Subconsultant 2: $
Subconsultant 3: $
Subconsultant 4: $
$ 128,895.00
$ 128,895.00
$ 208,958.61
1. Calculate average hourly rate for 1st year of the contract (Direct Labor Subtotal divided by total hours) Direct Labor
Subtotal per
Cost Proposal
Total Hours
per Cost
Proposal
Avg Hourly Rate
$ 30,960.00 / 440 = $70.36 Year 1 Avg Hourly Rate
Sand City multi-use trail 4927 optional task 5
Classification/Title Name Actual Hourly Rate Total
Exhibit 10-H1 Cost Proposal
Cost-Plus-Fixed Fee or Lump Sum or Firm Fixed Price Contracts (Design, Engineering and Environmental Studies)
Whitson Engineers dba Whitson and Associates, Inc
Civil Engineer Brent Edelman $55.00 $ 4,400.00
Principal Richard Weber $145.00 $ 5,800.00
Senior Civil Engineer Nathaniel Milam $80.50 $ 12,880.00 Associate Engineer Daniel Garrett $45.00 $ 3,600.00
Civil Engineer Emily Imfeld $53.50 $ 4,280.00
$0.00 $ -
$0.00 $ -
$ 30,960.00
$ 774.00
g) Overhead [(c) x (f)
l) CONSULTANT'S OTHER DIRECT COSTS (ODC) - ITEMIZE (Add additional pages if necessary) Description of Item Unit Cost Total
m) SUBCONSULTANTS' COSTS (Add additional pages if necessary) Hexagon
(m) TOTAL SUBCONSULTANS' COSTS
$0.00 $ -
$0.00 $ -
Actual Cost-Plus-Fixed Fee or Lump Sum or Firm Fixed Price Contracts (Calculations for Anticipated Salary Increases)
5 Year
Contract Duration
(n) TOTAL OTHER DIRECT COSTS INCLUDING SUBCONSULTANTS [(l) + (m)] TOTAL COST [(c) + (j) + (k) + (n)]
Exhibit 10-H1 Cost Proposal
Prime Consultant Subconsultant 2nd Tier Subconsultant
199
2. Calculate hourly rate for all periods (Increase the Average hourly rate for a period by proposed escalation %) Avg Hourly
Rate
Proposed
Escalation
Year 1 $70.36 + 5% = $73.88
Year 2 $73.88 + 5% = $77.58
Year 3 $77.58 + 5% = $81.45 Year 4 Avg Hourly Rate
Year 4 $81.45 + 5% = $85.53 Year 5 Avg Hourly Rate
3. Calculate estimated hours per year (Multiply estimate % each period by total hours) Estimated %
Completed
Each Period
Total Hours
per Cost
Proposal
Total Hours per
Period
Year 1 50.00% * 440 = 220 Estimated Hours Year 1
Year 2 50.00% * 440 = 220 Estimated Hours Year 2
Year 3 0.00% * 440 = 0 Estimated Hours Year 3
Year 4 0.00% * 440 = 0 Estimated Hours Year 4
Year 5 0.00% * 440 = 0 Estimated Hours Year 5
Total 100% Total = 440
4. Calculate Total Costs including Escalation (Multiply average hourly rate by the number of hours) Avg Hourly
Rate
Estimated
Hours
(calculated above) (calculated
above)
Year 1 $70.36 * 220 = $15,480.00 Estimated Hours Year 1 Year 2 $73.88 * 220 = $16,254.00 Estimated Hours Year 2 Year 3 $77.58 * 0 = $0.00 Estimated Hours Year 3
Year 4 $81.45 * 0 = $0.00 Estimated Hours Year 4
Year 5 $85.53 * 0 = $0.00 Estimated Hours Year 5
= $31,734.00
= $30,960.00
= $774.00 Transfer to Page 1
Cost
Per Period
Total Direct Labor Cost with Escalation
Year 2 Avg Hourly Rate
Year 3 Avg Hourly Rate
2. Terms and conditions of the contract
3. Title 23 United States Code Section 112 - Letting of Contracts
4. 48 Code of Federal Regulations Part 31 - Contract Cost Principles and Procedures
5. 23 Code of Federal Regulations Part 172 - Procurement, Management, and Administration of
6. 48 Code of Federal Regulations Part 9904 - Cost Accounting Standards Board (when applicable) pp y y p p j
in compliance with applicable federal and state requirements. Costs that are noncompliant with the federal and state requirements are not Direct Labor Subtotal before escalation
Estimated total of Direct Labor Salary Increase
Exhibit 10-H1 Cost Proposal
Certification of Direct Costs:
I, the undersigned, certify to the best of my knowledge and belief that all direct costs identified on the cost proposal(s) in this contract are
1. Generally Accepted Accounting Principles (GAAP)
Local governments are responsible for applying only cognizant agency approved or Caltrans accepted Indirect Cost Rate(s).
Prime Consultant or Subconsultant Certifying:
200
Name: Title*:
Signature: Date of Certification (mm/dd/yyyy): 08/12/2026 Email: Phone Number:
Address:
List services the consultant is providing under the proposed contract:
6 Harris Court, Monterey, CA 93940
g
President or a Chief Financial Officer, or equivalent, who has authority to represent the financial information utilized to Professional Civil Engineering and Land Surveying services Kimberley Woltman CFO
[email protected] 831-649-5225
201
Note: Mark-ups are Not Allowed
Consultant
Project No. Contract No. Date 8/12/2026
DIRECT LABOR
Hours
20 40
20 40
20 20
20 LABOR COSTS
a) Subtotal Direct Labor Costs
b) Anticipated Salary Increases (see Antcipated Salary Increases page for calculations) c) Total Direct Labor Costs [(a) + (b)] $ 14,145.00
INDIRECT COSTS
d) Fringe Benefits ( Rate: 29.34% ) e) Total Fringe Benefits [(c) x (d)] $ 4,150.14 f) Overhead ( Rate: 41.02% ) $ 5,802.28
h) General and Administrative ( Rate: 59.00% ) i) Gen & Admin [(c) x (h)] $ 8,345.55 j) Total Indirect Costs [(e) + (g) + (i)] $ 18,297.97
FIXED FEE
k) TOTAL FIXED FEE [(c) + (j)]* fixed fee 10% ] $ 3,244.30 Quatity Unit
l) TOTAL OTHER DIRECT COSTS -$
Subconsultant 1: $
Subconsultant 2: $
Subconsultant 3: $
Subconsultant 4: $
-$
-$
$ 35,687.27
1. Calculate average hourly rate for 1st year of the contract (Direct Labor Subtotal divided by total hours) Sand City multi-use trail 4927 optional task 8
Classification/Title Name Actual Hourly Rate Total
Exhibit 10-H1 Cost Proposal
Cost-Plus-Fixed Fee or Lump Sum or Firm Fixed Price Contracts (Design, Engineering and Environmental Studies)
Whitson Engineers dba Whitson and Associates, Inc
Civil Engineer Brent Edelman $55.00 $ 1,100.00
Principal Richard Weber $145.00 $ 2,900.00
Senior Civil Engineer Nathaniel Milam $80.50 $ 3,220.00 Senior Land Surveyor Thomas Hannah $80.50 $ 1,610.00
Land Surveyor Mike Hink $75.00 $ 3,000.00
Associate Engineer Daniel Garrett $45.00 $ 900.00
Civil Engineer Emily Imfeld $53.50 $ 1,070.00
$0.00 $ -
$0.00 $ -
$ 13,800.00
$ 345.00
g) Overhead [(c) x (f)
l) CONSULTANT'S OTHER DIRECT COSTS (ODC) - ITEMIZE (Add additional pages if necessary) Description of Item Unit Cost Total
m) SUBCONSULTANTS' COSTS (Add additional pages if necessary) (m) TOTAL SUBCONSULTANS' COSTS
$0.00 $ -
$0.00 $ -
Actual Cost-Plus-Fixed Fee or Lump Sum or Firm Fixed Price Contracts (Calculations for Anticipated Salary Increases)
(n) TOTAL OTHER DIRECT COSTS INCLUDING SUBCONSULTANTS [(l) + (m)] TOTAL COST [(c) + (j) + (k) + (n)]
Exhibit 10-H1 Cost Proposal
Prime Consultant Subconsultant 2nd Tier Subconsultant
202
Direct Labor
Subtotal per
Cost Proposal
Total Hours
per Cost
Proposal
Avg Hourly Rate
$ 13,800.00 / 180 = $76.67 Year 1 Avg Hourly Rate
2. Calculate hourly rate for all periods (Increase the Average hourly rate for a period by proposed escalation %) Avg Hourly
Rate
Proposed
Escalation
Year 1 $76.67 + 5% = $80.50
Year 2 $80.50 + 5% = $84.53
Year 3 $84.53 + 5% = $88.75 Year 4 Avg Hourly Rate
Year 4 $88.75 + 5% = $93.19 Year 5 Avg Hourly Rate
3. Calculate estimated hours per year (Multiply estimate % each period by total hours) Estimated %
Completed
Each Period
Total Hours
per Cost
Proposal
Total Hours per
Period
Year 1 50.00% * 180 = 90 Estimated Hours Year 1
Year 2 50.00% * 180 = 90 Estimated Hours Year 2
Year 3 0.00% * 180 = 0 Estimated Hours Year 3
Year 4 0.00% * 180 = 0 Estimated Hours Year 4
Year 5 0.00% * 180 = 0 Estimated Hours Year 5
Total 100% Total = 180
4. Calculate Total Costs including Escalation (Multiply average hourly rate by the number of hours) Avg Hourly
Rate
Estimated
Hours
(calculated above) (calculated
above)
Year 1 $76.67 * 90 = $6,900.00 Estimated Hours Year 1
Year 2 $80.50 * 90 = $7,245.00 Estimated Hours Year 2
Year 3 $84.53 * 0 = $0.00 Estimated Hours Year 3
Year 4 $88.75 * 0 = $0.00 Estimated Hours Year 4
Year 5 $93.19 * 0 = $0.00 Estimated Hours Year 5
= $14,145.00
= $13,800.00
= $345.00 Transfer to Page 1
5 Year
Contract Duration
Cost
Per Period
Total Direct Labor Cost with Escalation
Year 2 Avg Hourly Rate
Year 3 Avg Hourly Rate
2. Terms and conditions of the contract
3. Title 23 United States Code Section 112 - Letting of Contracts
4. 48 Code of Federal Regulations Part 31 - Contract Cost Principles and Procedures
5. 23 Code of Federal Regulations Part 172 - Procurement, Management, and Administration of
6. 48 Code of Federal Regulations Part 9904 - Cost Accounting Standards Board (when applicable) pp y y p p j
in compliance with applicable federal and state requirements. Costs that are noncompliant with the federal and state requirements are not Direct Labor Subtotal before escalation
Estimated total of Direct Labor Salary Increase
Exhibit 10-H1 Cost Proposal
Certification of Direct Costs:
I, the undersigned, certify to the best of my knowledge and belief that all direct costs identified on the cost proposal(s) in this contract are
1. Generally Accepted Accounting Principles (GAAP)
203
Name: Title*:
Signature: Date of Certification (mm/dd/yyyy): 08/12/2026 Email: Phone Number:
Address:
List services the consultant is providing under the proposed contract:
6 Harris Court, Monterey, CA 93940
g
President or a Chief Financial Officer, or equivalent, who has authority to represent the financial information utilized to Professional Civil Engineering and Land Surveying services Local governments are responsible for applying only cognizant agency approved or Caltrans accepted Indirect Cost Rate(s).
Prime Consultant or Subconsultant Certifying:
Kimberley Woltman CFO
[email protected] 831-649-5225
204
Project No.
Consultant
Note: Mark-ups are Not Allowed
Contract No. Date 7/1/26
DIRECT LABOR
Hours
20 545
480
270
35 75
b) Anticipated Salary Increases
a) Subtotal Direct Labor Costs
LABOR COSTS
(see Antcipated Salary Increases page for calculations) c) Total Direct Labor Costs [(a) + (b)] 72,594.40 $
d) Fringe Benefits
INDIRECT COSTS
( Rate: 64.00% ) e) Total Fringe Benefits [(c) x (d)] 46,460.41 $ f) Overhead ( Rate: 56.00% ) 40,652.86 $
h) General and Administrative ( Rate: 12.00% ) i) Gen & Admin [(c) x (h)] 8,711.33 $ j) Total Indirect Costs [(e) + (g) + (i)] 95,824.60 $
FIXED FEE
k) TOTAL FIXED FEE [(c) + (j)]* fixed fee 10% ] 16,841.90 $ Quatity Unit
1 l) TOTAL OTHER DIRECT COSTS 3,000.00 $
Subconsultant 1: $
Subconsultant 2: $
Subconsultant 3: $
Subconsultant 4: $
- $
3,000.00 $
188,260.90 $
Sand City Multi-Use Trail
Classification/Title Name Actual Hourly Rate Total
Exhibit 10-H1 Cost Proposal
Cost-Plus-Fixed Fee or Lump Sum or Firm Fixed Price Contracts (Design, Engineering and Environmental Studies)
BFS LANDSCAPE ARCHITECTS
Project Manager Nicole Limesand $46.18 22,166.40 $
Designer Cinthia Zavala $33.14 18,061.30 $
Principal Larry Foster $144.23 2,884.60 $
Associate Principal Elizabeth Matz $87.62 23,657.40 $
- $
- $
Technical Support Michelle Parravano $37.60 2,820.00 $
Admin Support Erin Gustaveson $35.26 1,234.10 $
Reimbursables - Reproduction $3,000.00 3,000.00 $
$0.00 - $
70,823.80 $
$1,770.60
g) Overhead [(c) x (f)
l) CONSULTANT'S OTHER DIRECT COSTS (ODC) - ITEMIZE (Add additional pages if necessary) Description of Item Unit Cost Total
m) SUBCONSULTANTS' COSTS (Add additional pages if necessary) (m) TOTAL SUBCONSULTANS' COSTS
$0.00 - $
$0.00 - $
(n) TOTAL OTHER DIRECT COSTS INCLUDING SUBCONSULTANTS [(l) + (m)] TOTAL COST [(c) + (j) + (k) + (n)]
Exhibit 10-H1 Cost Proposal
Prime Consultant Subconsultant 2nd Tier Subconsultant
205
1. Calculate average hourly rate for 1st year of the contract (Direct Labor Subtotal divided by total hours) Direct Labor
Subtotal per
Cost
Proposal
Total
Hours per
Cost
Proposal
Avg Hourly
Rate
$70,823.80 / 1425 = $49.70 Year 1 Avg Hourly Rate
2. Calculate hourly rate for all periods (Increase the Average hourly rate for a period by proposed escalation %) Avg Hourly
Rate
Proposed
Escalation
Year 1 $49.70 + 5% = $52.19
Year 2 $52.19 + 5% = $54.80
Year 3 $54.80 + 5% = $57.54 Year 4 Avg Hourly Rate
Year 4 $57.54 + 5% = $60.41 Year 5 Avg Hourly Rate
3. Calculate estimated hours per year (Multiply estimate % each period by total hours) Estimated %
Completed
Each Period
Total
Hours per
Cost
Proposal
Total Hours
per Period
Year 1 50.00% * 1425 = 712.5 Estimated Hours Year 1
Year 2 50.00% * 1425 = 712.5 Estimated Hours Year 2
Year 3 0.00% * 1425 = 0 Estimated Hours Year 3
Year 4 0.00% * 1425 = 0 Estimated Hours Year 4
Year 5 0.00% * 1425 = 0 Estimated Hours Year 5
Total 100% Total = 1425
4. Calculate Total Costs including Escalation (Multiply average hourly rate by the number of hours) Avg Hourly
Rate
Estimated
Hours
(calculated
above)
(calculated
above)
Year 1 $49.70 * 712.5 = $35,411.90 Estimated Hours Year 1 Year 2 $52.19 * 712.5 = $37,182.50 Estimated Hours Year 2 Year 3 $54.80 * 0 = $0.00 Estimated Hours Year 3
Year 4 $57.54 * 0 = $0.00 Estimated Hours Year 4
Year 5 $60.41 * 0 = $0.00 Estimated Hours Year 5
= $72,594.40
= $70,823.80
= $1,770.60 Transfer to Page 1
Actual Cost-Plus-Fixed Fee or Lump Sum or Firm Fixed Price Contracts (Calculations for Anticipated Salary Increases)
5 Year
Contract Duration
Cost
Per Period
Total Direct Labor Cost with Escalation
Year 2 Avg Hourly Rate
Year 3 Avg Hourly Rate
Direct Labor Subtotal before escalation
Estimated total of Direct Labor Salary Increase
206
Name: Title*:
Signature: Date of Certification (mm/dd/yyyy): 7/1/26
Email: Phone Number:
Address:
List services the consultant is providing under the proposed contract:
2. Terms and conditions of the contract
3. Title 23 United States Code Section 112 - Letting of Contracts
4. 48 Code of Federal Regulations Part 31 - Contract Cost Principles and Procedures
5. 23 Code of Federal Regulations Part 172 - Procurement, Management, and Administration of
6. 48 Code of Federal Regulations Part 9904 - Cost Accounting Standards Board (when applicable) All costs must be applied consistently and fairly to all contracts. All documentation of compliance must be retained in the project files and be Exhibit 10-H1 Cost Proposal
Certification of Direct Costs:
I, the undersigned, certify to the best of my knowledge and belief that all direct costs identified on the cost proposal(s) in this contract are
1. Generally Accepted Accounting Principles (GAAP)
425 Pacific Street, Suite 201, Monterey CA 93940
*An individual executive or financial officer of the consultant’s or subconsultant’s organization at a level no lower than a Vice President or a Chief Financial Officer, or equivalent, who has authority to represent the financial information utilized to establish the cost proposal for the contract.
Landscape architecture design and construction documentation. Bid support, community outreach support and grant support.
Local governments are responsible for applying only cognizant agency approved or Caltrans accepted Indirect Cost Rate(s).
Prime Consultant or Subconsultant Certifying:
Larry Foster CEO/CFO
[email protected] 831-646-1383
207
COST PROPOSAL 1
Note: Mark-ups are Not Allowed
Consultant
Project No. Contract No. Date 6/18/2026
DIRECT LABOR
Hours
32 8
12 24
32 32
16 12
8 LABOR COSTS
a) Subtotal Direct Labor Costs
b) Anticipated Salary Increases (see Anticipated Salary Increases page for calculations) c) Total Direct Labor Costs [(a) + (b)] 8,993.26$
INDIRECT COSTS
d) Fringe Benefits ( Rate: 58.17% ) e) Total Fringe Benefits [(c) x (d)] 5,231.38$ f) Overhead ( Rate: 94.67% ) 8,513.92$
h) General and Administrative ( Rate: 16.39% ) i) Gen & Admin [(c) x (h)] 1,474.00$ j) Total Indirect Costs [(e) + (g) + (i)] 15,219.30$
FIXED FEE
k) TOTAL FIXED FEE [(c) + (j)]* fixed fee 10% ] 2,421.26$ Quantity Unit
0 mile
0 actual cost
0 actual cost
0 per day
l) TOTAL OTHER DIRECT COSTS -$
Subconsultant 1: $4,980
Subconsultant 2:
Subconsultant 3: $
Subconsultant 4: $
$ 4,980.00
4,980.00$
$ 31,613.82
(n) TOTAL OTHER DIRECT COSTS INCLUDING SUBCONSULTANTS [(l) + (m)] TOTAL COST [(c) + (j) + (k) + (n)]
m) SUBCONSULTANTS' COSTS (Add additional pages if necessary) Cornerstone Earth Group, Inc.
(m) TOTAL SUBCONSULTANS' COSTS
Field Supplies $200.00 -$
GIS/Trimble Equipment $80.00 -$
Staff $44.31 1,417.92$
GIS/Computer Specialist
Copying $50.00 -$
8,948.52$
44.74$
g) Overhead [(c) x (f)
l) CONSULTANT'S OTHER DIRECT COSTS (ODC) - ITEMIZE (Add additional pages if necessary) Description of Item Unit Cost Total
Mileage $0.73 -$
Administrative Assistant Staff $28.49 227.92$
Administrative Manager Staff $35.87 430.44$
Staff $44.84 717.44$
Sr. Planner/Scientist I Staff $57.50 690.00$
Sr. Project Manager Matt Johnson* $70.94 2,270.08$
Sr. Scientist II Jami Colley* $64.36 514.88$
Assoc. Planner/Scientist II Staff $49.06 1,177.44$
Assoc. Planner/Scientist I Staff $46.95 1,502.40$
Asst. Planner/Scientist II
Classification/Title Name Actual Hourly Rate Total
COST PROPOSAL 1
COST-PLUS-FIXED FEE OR LUMP SUM OR FIRM FIXED PRICE CONTRACTS (DESIGN, ENGINEERING AND ENVIRONMENTAL STUDIES)
Denise Duffy & Associates
Prime Consultant Subconsultant 2nd Tier Subconsultant
January 2020
208
COST PROPOSAL 1
1. Calculate average hourly rate for 1st year of the contract (Direct Labor Subtotal divided by total hours) Direct Labor
Subtotal per
Cost Proposal
Total Hours
per Cost
Proposal
Avg Hourly
Rate
$ 8,948.52 / 176 = $50.84 Year 1 Avg Hourly Rate
2. Calculate hourly rate for all periods (Increase the Average hourly rate for a period by proposed escalation %) Avg Hourly
Rate
Proposed
Escalation
Year 1 $50.84 + 5% = $53.39
Year 2 $53.39 + 5% = $56.06
Year 3 $56.06 + 5% = $58.86 Year 4 Avg Hourly Rate
Year 4 $58.86 + 5% = $61.80 Year 5 Avg Hourly Rate
3. Calculate estimated hours per year (Multiply estimate % each period by total hours) Estimated %
Completed
Each Period
Total Hours
per Cost
Proposal
Total Hours
per Period
Year 1 90.00% * 176 = 158.4 Estimated Hours Year 1
Year 2 10.00% * 176 = 17.6 Estimated Hours Year 2
Year 3 0.00% * 176 = 0 Estimated Hours Year 3
Year 4 0.00% * 176 = 0 Estimated Hours Year 4
Year 5 0.00% * 176 = 0 Estimated Hours Year 5
Total 100% Total = 176
4. Calculate Total Costs including Escalation (Multiply average hourly rate by the number of hours) Avg Hourly
Rate
Estimated
Hours
(calculated above) (calculated
above)
Year 1 $50.84 * 158.4 = $8,053.67 Estimated Hours Year 1 Year 2 $53.39 * 17.6 = $939.59 Estimated Hours Year 2
Year 3 $56.06 * 0 = $0.00 Estimated Hours Year 3
Year 4 $58.86 * 0 = $0.00 Estimated Hours Year 4
Year 5 $61.80 * 0 = $0.00 Estimated Hours Year 5
= $8,993.26
= $8,948.52
= $44.74 Transfer to Page 1
Direct Labor Subtotal before escalation
Estimated total of Direct Labor Salary Increase
Cost
Per Period
Total Direct Labor Cost with Escalation
Year 2 Avg Hourly Rate
Year 3 Avg Hourly Rate
COST-PLUS-FIXED FEE OR LUMP SUM OR FIRM FIXED PRICE CONTRACTS (CALCULATIONS FOR ANTICIPATED SALARY INCREASES)
5 Year
Contract Duration
COST PROPOSAL 1
January 2020
209
COST PROPOSAL 1
Name: Title*:
Signature: Date of Certification (mm/dd/yyyy): 6/18/2026 Email: Phone Number:
Address:
List services the consultant is providing under the proposed contract:
2. Terms and conditions of the contract
3. Title 23 United States Code Section 112 - Letting of Contracts
4. 48 Code of Federal Regulations Part 31 - Contract Cost Principles and Procedures
5. 23 Code of Federal Regulations Part 172 - Procurement, Management, and Administration of
6. 48 Code of Federal Regulations Part 9904 - Cost Accounting Standards Board (when applicable) All costs must be applied consistently and fairly to all contracts. All documentation of compliance must be retained in the project files and be in compliance with applicable federal and state requirements. Costs that are noncompliant with the federal and state requirements are not eligible for reimbursement.
COST PROPOSAL 1
Certification of Direct Costs:
I, the undersigned, certify to the best of my knowledge and belief that all direct costs identified on the cost proposal(s) in this contract are actual, reasonable, and allocable to the contract in accordance with the contract terms and the following requirements:
1. Generally Accepted Accounting Principles (GAAP)
947 Cass Street, Suite 5, Monterey, CA 93940
*An individual executive or financial officer of the consultant’s or subconsultant’s organization at a level no lower than a Vice President or a Chief Financial Officer, or equivalent, who has authority to represent the financial information utilized to establish the cost proposal for the contract.
Meetings and Data Analysis Support
Permit Acquisition Support
Biological Resources Report
APE Map
Archeological Survey Report
Hazardous Waste Technical Memorandum
Environmental Connitment Record
Local governments are responsible for applying only cognizant agency approved or Caltrans accepted Indirect Cost Rate(s).
Prime Consultant or Subconsultant Certifying:
Denise Duffy Principal
[email protected] (831) 373-4341
January 2020
210
Note: Mark-ups are Not Allowed
Consultant
Project No. Contract No. Date 9/4/2026
DIRECT LABOR
Hours
5 0
12 0
16 0
6 LABOR COSTS
a) Subtotal Direct Labor Costs
b) Anticipated Salary Increases (see Anticipated Salary Increases page for calculations) c) Total Direct Labor Costs [(a) + (b)] $ 2,915.90
INDIRECT COSTS
d) Fringe Benefits ( Rate: 55.00% ) e) Total Fringe Benefits [(c) x (d)] $ 1,603.74 f) Overhead ( Rate: 0.00% ) - $
h) General and Administrative ( Rate: 107.00% ) i) Gen & Admin [(c) x (h)] $ 3,120.01 j) Total Indirect Costs [(e) + (g) + (i)] $ 4,723.76
FIXED FEE
k) TOTAL FIXED FEE [(c) + (j)]* fixed fee 10% ] $ 763.97 Quantity Unit
1 LS
l) TOTAL OTHER DIRECT COSTS $ 200.00
Subconsultant 1: $
Subconsultant 2: $
Subconsultant 3: $
Subconsultant 4: $
$ -
$ 200.00
$ 8,603.62
(n) TOTAL OTHER DIRECT COSTS INCLUDING SUBCONSULTANTS [(l) + (m)] TOTAL COST [(c) + (j) + (k) + (n)]
m) SUBCONSULTANTS' COSTS (Add additional pages if necessary) (m) TOTAL SUBCONSULTANTS' COSTS
$0.00 - $
$0.00 - $
Mileage $200.00 200.00 $
$0.00 - $
$ 2,844.78
$ 71.12
g) Overhead [(c) x (f)
l) CONSULTANT'S OTHER DIRECT COSTS (ODC) - ITEMIZE (Add additional pages if necessary) Description of Item Unit Cost Total
Admin Jeanette Garcia $59.57 357.42 $
$ -
Engineer II Jocelyn Lee* $60.21 963.36 $
Engineer I Ethan Heckman $43.00 - $
Sr. Associate I Tim Chang* $82.00 984.00 $
Associate Eng. II Ling Jin $77.44 - $
Principal Jeff Elia* $108.00 540.00 $
Sr. Associate II Gicela Del Rio $90.43 - $
Classification/Title Name Actual Hourly Rate Total
Exhibit 10-H1 Cost Proposal
Cost-Plus-Fixed Fee or Lump Sum or Firm Fixed Price Contracts (Design, Engineering and Environmental Studies)
Hexagon Transportation Consultants, Inc.
Prime Consultant Subconsultant 2nd Tier Subconsultant
211
1. Calculate average hourly rate for 1st year of the contract (Direct Labor Subtotal divided by total hours) Direct Labor
Subtotal per
Cost
Proposal
Total Hours
per Cost
Proposal
Avg Hourly
Rate
$ 2,844.78 / 39 = $72.94 Year 1 Avg Hourly Rate
2. Calculate hourly rate for all periods (Increase the Average hourly rate for a period by proposed escalation %) Avg Hourly
Rate
Proposed
Escalation
Year 1 $72.94 + 5% = $76.59
Year 2 $76.59 + 5% = $80.42
Year 3 $80.42 + 5% = $84.44 Year 4 Avg Hourly Rate
Year 4 $84.44 + 5% = $88.66 Year 5 Avg Hourly Rate
3. Calculate estimated hours per year (Multiply estimate % each period by total hours) Estimated %
Completed
Each Period
Total Hours
per Cost
Proposal
Total Hours
per Period
Year 1 50.00% * 39 = 19.5 Estimated Hours Year 1
Year 2 50.00% * 39 = 19.5 Estimated Hours Year 2
Year 3 0.00% * 39 = 0 Estimated Hours Year 3
Year 4 0.00% * 39 = 0 Estimated Hours Year 4
Year 5 0.00% * 39 = 0 Estimated Hours Year 5
Total 100% Total = 39
4. Calculate Total Costs including Escalation (Multiply average hourly rate by the number of hours) Avg Hourly
Rate
Estimated
Hours
(calculated
above)
(calculated
above)
Year 1 $72.94 * 19.5 = $1,422.39 Estimated Hours Year 1 Year 2 $76.59 * 19.5 = $1,493.51 Estimated Hours Year 2 Year 3 $80.42 * 0 = $0.00 Estimated Hours Year 3
Year 4 $84.44 * 0 = $0.00 Estimated Hours Year 4
Year 5 $88.66 * 0 = $0.00 Estimated Hours Year 5
= $2,915.90
= $2,844.78
= $71.12 Transfer to Page 1
Direct Labor Subtotal before escalation
Estimated total of Direct Labor Salary Increase
Cost
Per Period
Total Direct Labor Cost with Escalation
Year 2 Avg Hourly Rate
Year 3 Avg Hourly Rate
Actual Cost-Plus-Fixed Fee or Lump Sum or Firm Fixed Price Contracts (Calculations for Anticipated Salary Increases)
5 Year
Contract Duration
Exhibit 10-H1 Cost Proposal
212
Name: Title*:
Signature: Date of Certification (mm/dd/yyyy): 9/4/2026 Email: Phone Number:
Address:
List services the consultant is providing under the proposed contract:
100 Century Center Courte, Suite 501, San Jose, CA 95112 *An individual executive or financial officer of the consultant’s or subconsultant’s organization at a level no lower than a Vice President or a Chief Financial Officer, or equivalent, who has authority to represent the financial information utilized to establish the cost proposal for the contract.
Traffic Engineering Services
Local governments are responsible for applying only cognizant agency approved or Caltrans accepted Indirect Cost Rate(s).
Prime Consultant or Subconsultant Certifying:
Jeff Elia Vice President
[email protected] 408-846-7413
2. Terms and conditions of the contract
3. Title 23 United States Code Section 112 - Letting of Contracts
4. 48 Code of Federal Regulations Part 31 - Contract Cost Principles and Procedures
5. 23 Code of Federal Regulations Part 172 - Procurement, Management, and Administration of Engineering and Design Related Service 6. 48 Code of Federal Regulations Part 9904 - Cost Accounting Standards Board (when applicable) All costs must be applied consistently and fairly to all contracts. All documentation of compliance must be retained in the project files and be in compliance with applicable federal and state requirements. Costs that are noncompliant with the federal and state requirements are not eligible for reimbursement.
Exhibit 10-H1 Cost Proposal
Certification of Direct Costs:
I, the undersigned, certify to the best of my knowledge and belief that all direct costs identified on the cost proposal(s) in this contract are actual, reasonable, and allocable to the contract in accordance with the contract terms and the following requirements:
1. Generally Accepted Accounting Principles (GAAP)
213
Note: Mark-ups are Not Allowed
Consultant
Project No. Contract No. Date 9/4/2026
DIRECT LABOR
Hours
91 10
178
30 194
59 10
LABOR COSTS
a) Subtotal Direct Labor Costs
b) Anticipated Salary Increases (see Anticipated Salary Increases page for calculations) c) Total Direct Labor Costs [(a) + (b)] $ 44,163.54
INDIRECT COSTS
d) Fringe Benefits ( Rate: 55.00% ) e) Total Fringe Benefits [(c) x (d)] $ 24,289.95 f) Overhead ( Rate: 0.00% ) - $
h) General and Administrative ( Rate: 107.00% ) i) Gen & Admin [(c) x (h)] $ 47,254.99 j) Total Indirect Costs [(e) + (g) + (i)] $ 71,544.93
FIXED FEE
k) TOTAL FIXED FEE [(c) + (j)]* fixed fee 10% ] $ 11,570.85 Quantity Unit
1 LS
1 LS
l) TOTAL OTHER DIRECT COSTS $ 1,616.00
Subconsultant 1: $
Subconsultant 2: $
Subconsultant 3: $
Subconsultant 4: $
$ -
$ 1,616.00
$ 128,895.32
(n) TOTAL OTHER DIRECT COSTS INCLUDING SUBCONSULTANTS [(l) + (m)] TOTAL COST [(c) + (j) + (k) + (n)]
m) SUBCONSULTANTS' COSTS (Add additional pages if necessary) (m) TOTAL SUBCONSULTANTS' COSTS
$0.00 - $
$0.00 - $
Mileage $1,400.00 1,400.00 $
Mail and Delivery $216.00 216.00 $
$ 42,464.94
$ 1,698.60
g) Overhead [(c) x (f)
l) CONSULTANT'S OTHER DIRECT COSTS (ODC) - ITEMIZE (Add additional pages if necessary) Description of Item Unit Cost Total
Admin Jeanette Garcia $59.57 595.70 $
$ -
Engineer II Jocelyn Lee* $60.21 11,680.74 $
Engineer I Ethan Heckman $43.00 2,537.00 $
Sr. Associate I Tim Chang* $82.00 14,596.00 $
Associate Eng. II Ling Jin $77.44 2,323.20 $
Principal Jeff Elia* $108.00 9,828.00 $
Sr. Associate II Gicela Del Rio $90.43 904.30 $
Classification/Title Name Actual Hourly Rate Total
Exhibit 10-H1 Cost Proposal
Cost-Plus-Fixed Fee or Lump Sum or Firm Fixed Price Contracts (Design, Engineering and Environmental Studies)
Hexagon Transportation Consultants, Inc.
Prime Consultant Subconsultant 2nd Tier Subconsultant
214
1. Calculate average hourly rate for 1st year of the contract (Direct Labor Subtotal divided by total hours) Direct Labor
Subtotal per
Cost
Proposal
Total Hours
per Cost
Proposal
Avg Hourly
Rate
$42,464.94 / 572 = $74.24 Year 1 Avg Hourly Rate
2. Calculate hourly rate for all periods (Increase the Average hourly rate for a period by proposed escalation %) Avg Hourly
Rate
Proposed
Escalation
Year 1 $74.24 + 5% = $77.95
Year 2 $77.95 + 5% = $81.85
Year 3 $81.85 + 5% = $85.94 Year 4 Avg Hourly Rate
Year 4 $85.94 + 5% = $90.24 Year 5 Avg Hourly Rate
3. Calculate estimated hours per year (Multiply estimate % each period by total hours) Estimated %
Completed
Each Period
Total Hours
per Cost
Proposal
Total Hours
per Period
Year 1 20.00% * 572 = 114.4 Estimated Hours Year 1
Year 2 80.00% * 572 = 457.6 Estimated Hours Year 2
Year 3 0.00% * 572 = 0 Estimated Hours Year 3
Year 4 0.00% * 572 = 0 Estimated Hours Year 4
Year 5 0.00% * 572 = 0 Estimated Hours Year 5
Total 100% Total = 572
4. Calculate Total Costs including Escalation (Multiply average hourly rate by the number of hours) Avg Hourly
Rate
Estimated
Hours
(calculated
above)
(calculated
above)
Year 1 $74.24 * 114.4 = $8,492.99 Estimated Hours Year 1 Year 2 $77.95 * 457.6 = $35,670.55 Estimated Hours Year 2 Year 3 $81.85 * 0 = $0.00 Estimated Hours Year 3
Year 4 $85.94 * 0 = $0.00 Estimated Hours Year 4
Year 5 $90.24 * 0 = $0.00 Estimated Hours Year 5
= $44,163.54
= $42,464.94
= $1,698.60 Transfer to Page 1
Direct Labor Subtotal before escalation
Estimated total of Direct Labor Salary Increase
Cost
Per Period
Total Direct Labor Cost with Escalation
Year 2 Avg Hourly Rate
Year 3 Avg Hourly Rate
Actual Cost-Plus-Fixed Fee or Lump Sum or Firm Fixed Price Contracts (Calculations for Anticipated Salary Increases)
5 Year
Contract Duration
Exhibit 10-H1 Cost Proposal
215
Name: Title*:
Signature: Date of Certification (mm/dd/yyyy): 9/4/2026 Email: Phone Number:
Address:
List services the consultant is providing under the proposed contract:
100 Century Center Courte, Suite 501, San Jose, CA 95112 *An individual executive or financial officer of the consultant’s or subconsultant’s organization at a level no lower than a Vice President or a Chief Financial Officer, or equivalent, who has authority to represent the financial information utilized to establish the cost proposal for the contract.
Traffic Engineering Service. Traffic Signal Design.
Local governments are responsible for applying only cognizant agency approved or Caltrans accepted Indirect Cost Rate(s).
Prime Consultant or Subconsultant Certifying:
Jeff Elia Vice President
[email protected] 408-846-7413
2. Terms and conditions of the contract
3. Title 23 United States Code Section 112 - Letting of Contracts
4. 48 Code of Federal Regulations Part 31 - Contract Cost Principles and Procedures
5. 23 Code of Federal Regulations Part 172 - Procurement, Management, and Administration of Engineering and Design Related Service 6. 48 Code of Federal Regulations Part 9904 - Cost Accounting Standards Board (when applicable) All costs must be applied consistently and fairly to all contracts. All documentation of compliance must be retained in the project files and be in compliance with applicable federal and state requirements. Costs that are noncompliant with the federal and state requirements are not eligible for reimbursement.
Exhibit 10-H1 Cost Proposal
Certification of Direct Costs:
I, the undersigned, certify to the best of my knowledge and belief that all direct costs identified on the cost proposal(s) in this contract are actual, reasonable, and allocable to the contract in accordance with the contract terms and the following requirements:
1. Generally Accepted Accounting Principles (GAAP)
216
Note: Mark-ups are Not Allowed
Consultant
Project No. Contract No. Date 6/24/2026
DIRECT LABOR
Hours
55 8
94 55
34 LABOR COSTS
a) Subtotal Direct Labor Costs
b) Anticipated Salary Increases (see Antcipated Salary Increases page for calculations) c) Total Direct Labor Costs [(a) + (b)] 14,684.47$
INDIRECT COSTS
d) Fringe Benefits ( Rate: 31.04% ) e) Total Fringe Benefits [(c) x (d)] 4,558.06$ f) Overhead ( Rate: 97.59% ) 14,330.57$
h) General and Administrative 12.12% ) i) Gen & Admin [(c) x (h)] 1,779.76$ j) Total Indirect Costs [(e) + (g) + (i)] 20,668.39$
FIXED FEE
k) TOTAL FIXED FEE [(c) + (j)]* fixed fee 10% ] 3,535.29$ Quatity Unit
l) TOTAL OTHER DIRECT COSTS -$
Subconsultant 1: 100.00$
Subconsultant 2: $
Subconsultant 3: $
Subconsultant 4: $
100.00$
100.00$
38,988.14$
26-348.00
Classification/Title Name Actual Hourly Rate Total
Exhibit 10-H1 Cost Proposal
Cost-Plus-Fixed Fee or Lump Sum or Firm Fixed Price Contracts (Design, Engineering and Environmental Studies)
Aurum Consulting Engineers Monterey Bay, Inc.
Designer Reynaldo Casiano $45.74 4,299.56$
Cadd Manager Jose Gonzalez $40.43 2,223.65$
Director Eldridge Bell $108.48 5,966.40$
Senior Project Manager Charles Denley $112.50 900.00$
-$
-$
Cadd Operator Jose Torres $27.55 936.70$
-$
$0.00 -$
$0.00 -$
14,326.31$
$358.16
g) Overhead [(c) x (f)
l) CONSULTANT'S OTHER DIRECT COSTS (ODC) - ITEMIZE (Add additional pages if necessary) Description of Item Unit Cost Total
m) SUBCONSULTANTS' COSTS (Add additional pages if necessary) Mileage
(m) TOTAL SUBCONSULTANS' COSTS
$0.00 -$
$0.00 -$
(n) TOTAL OTHER DIRECT COSTS INCLUDING SUBCONSULTANTS [(l) + (m)] TOTAL COST [(c) + (j) + (k) + (n)]
Prime Consultant Subconsultant 2nd Tier Subconsultant
217
1. Calculate average hourly rate for 1st year of the contract (Direct Labor Subtotal divided by total hours) Direct Labor
Subtotal per
Cost Proposal
Total
Hours per
Cost
Proposal
Avg Hourly
Rate
$ 14,326.31 / 246 = $58.24 Year 1 Avg Hourly Rate
2. Calculate hourly rate for all periods (Increase the Average hourly rate for a period by proposed escalation %) Avg Hourly
Rate
Proposed
Escalation
Year 1 $58.24 + 5% = $61.15
Year 2 $61.15 + 5% = $64.21
Year 3 $64.21 + 5% = $67.42 Year 4 Avg Hourly Rate
Year 4 $67.42 + 5% = $70.79 Year 5 Avg Hourly Rate
3. Calculate estimated hours per year (Multiply estimate % each period by total hours) Estimated %
Completed
Each Period
Total
Hours per
Cost
Proposal
Total
Hours per
Period
Year 1 50.00% * 246 = 123 Estimated Hours Year 1
Year 2 50.00% * 246 = 123 Estimated Hours Year 2
Year 3 0.00% * 246 = 0 Estimated Hours Year 3
Year 4 0.00% * 246 = 0 Estimated Hours Year 4
Year 5 0.00% * 246 = 0 Estimated Hours Year 5
Total 100% Total = 246
4. Calculate Total Costs including Escalation (Multiply average hourly rate by the number of hours) Avg Hourly
Rate
Estimated
Hours
(calculated above) (calculated
above)
Year 1 $58.24 * 123 = $7,163.16 Estimated Hours Year 1
Year 2 $61.15 * 123 = $7,521.31 Estimated Hours Year 2
Year 3 $64.21 * 0 = $0.00 Estimated Hours Year 3
Year 4 $67.42 * 0 = $0.00 Estimated Hours Year 4
Year 5 $70.79 * 0 = $0.00 Estimated Hours Year 5
= #########
= #########
= $358.16 Transfer to Page 1
Actual Cost-Plus-Fixed Fee or Lump Sum or Firm Fixed Price Contracts (Calculations for Anticipated Salary Increases)
5 Year
Contract Duration
Exhibit 10-H1 Cost Proposal
Cost
Per Period
Total Direct Labor Cost with Escalation
Year 2 Avg Hourly Rate
Year 3 Avg Hourly Rate
Direct Labor Subtotal before escalation
Estimated total of Direct Labor Salary Increase
218
Name: Title*:
Signature: Date of Certification (mm/dd/yyyy): 6/26/2026 Email: Phone Number:
Address:
List services the consultant is providing under the proposed contract:
2. Terms and conditions of the contract
3. Title 23 United States Code Section 112 - Letting of Contracts
4. 48 Code of Federal Regulations Part 31 - Contract Cost Principles and Procedures
5. 23 Code of Federal Regulations Part 172 - Procurement, Management, and Administration of Engineering and Design Related Service 6. 48 Code of Federal Regulations Part 9904 - Cost Accounting Standards Board (when applicable) All costs must be applied consistently and fairly to all contracts. All documentation of compliance must be retained in the project files and be in compliance with applicable federal and state requirements. Costs that are noncompliant with the federal and state requirements Exhibit 10-H1 Cost Proposal
Certification of Direct Costs:
I, the undersigned, certify to the best of my knowledge and belief that all direct costs identified on the cost proposal(s) in this contract are actual, reasonable, and allocable to the contract in accordance with the contract terms and the following requirements:
1. Generally Accepted Accounting Principles (GAAP)
404 W. Franklin Street, Suite 100, Monterey, CA 93940
*An individual executive or financial officer of the consultant’s or subconsultant’s organization at a level no lower than a Vice President or a Chief Financial Officer, or equivalent, who has authority to represent the financial information utilized Local governments are responsible for applying only cognizant agency approved or Caltrans accepted Indirect Cost Rate(s).
Prime Consultant or Subconsultant Certifying:
Eldridge O. Bell, P.E. Director
[email protected] 831-646-3330
219
Local Assistance Procedures Manual EXHBIT 10-H
Cost Proposal
Note: Mark-ups are Not Allowed
Consultant
Project No. Contract No. Date 6/30/2026
DIRECT LABOR
Hours Actual Hourly Rate
4 $91.35
4 $57.69
28 $45.50
LABOR COSTS
a) Subtotal Direct Labor Costs 1,870.16$
c) Total Direct Labor Costs [(a) + (b)] 1,870.16$
FRINGE BENEFITS
d) Fringe Benefits Rate: e) Total Fringe Benefits [(c) x (d)] -$ f) Overhead Rate: 225.24% g) Overhead [(c) x (f)]
h) General and Administrative Rate: i) Gen & Admin [(c) x (h)] j) Total Indirect Costs [(e) + (g) + (i)] $4,212.35
FIXED FEE
k) TOTAL FIXED PROFIT [(c) + (j)] x fixed fee 10.00% 608.25$ l) CONSUTLANT'S OTHER DIRECT COSTS (ODC) - ITEMIZE (Add additional pages if necessary) Mileage Costs 58.00$
Equipment Rental and Supplies -$
Permit Fees -$
Plan Sheets -$
Tests 1,530.00$
1,588.00$
m) SUBCONSULTANTS' COSTS
Coast Wide Utility Locaters 1,600.00$
Cenozoic Drilling 5,624.00$
Subconsultant 3 -$
Subconsultant 4 -$
7,224.00$
7,224.00$
n) Total Other Direct Costs Including Subconsultants [(l) + (m)] 8,812.00$ TOTAL COST [(c) + (j) + (k) + (n)] $15,502.76
1,274.00$
-$
-$
-$
$4,212.35
$0.00
m) Total Subconsultants' Costs
l) Total Other Direct Costs
Staff Professional
Exhibit 10-H Cost Proposal
Actual Cost-Plus-Fixed Fee or Lump Sum or Firm Fixed Price contracts (Design, Engineering and Environmental Studies)
Earth Systems Pacific
Classification/Title Name Total
Principal Professional 365.40$
Associate Professional 230.76$
Prime Consultant Subconsultant 2nd Tier Subconsultant
LPP 13-01
January 14, 2015
220
Local Assistance Procedures Manual EXHBIT 10-H
Cost Proposal
OTHER DIRECT COSTS (ODC) ITEMIZATION
Travel/Mileage Costs Cost
58.00$
-$
-$
-$
Total 58.00$
Equipment Rental and Supplies
-$
-$
-$
-$
Total -$
Laboratory Testing
550.00$
280.00$
325.00$
375.00$
Total 1,530.00$
Project Professional trip (80 miles @ $0.725)
Long Hydrometer - 1
Moisture / Density - 10
Plasticity Index - 1
R-Value - 1
LPP 13-01
January 14, 2015
221
8 EXHIBIT C: ADA Best Practices for Documents and Outreach The following are best practices that Sand City commits to complying with, and asks that all final and public draft documents comply, as they align with best practices for web-content accessibility:
Public Outreach Guidance
• Offer alternative ways to engage in outreach for the hard-of-hearing and the blind o Example: Have Talk-to-Text capacity available to engage with the hard of hearing • Ensure public meeting rooms are set up in a way that is wheelchair accessible • Ensure an alternative to a podium or stage is available in the event an individual cannot participate that way
• Have at least one wireless microphone available to help ensure public comments are projected in the meeting
• Develop public workshop handouts in font size 14 (minimum) o Handouts could include a project summary sheet, survey, comment card, etc.
Developing ADA Accessible Documents
• Use Calibri, Helvetica, or Arial Font Type
• Ensure final document content is at least font size 12 (minimum) • Utilize proper features in Microsoft Word, including, but not limited to:
o Alt Text for Images and Tables
o “Styles” Feature to add emphasis or titles
o Built in “Spacing” feature
• Indicate at the bottom of a Final Document’s Title Page, an ADA Notice stating:
o ADA Notice: For individuals with sensory disabilities, this document is available in alternate formats. For information call (831) 775-0903 or Email [email protected].
Web Content Accessibility Guidelines
The Web Content Accessibility Guidance (WCAG) was integrated into Section 508 of the American with Disabilities Act in January 2018 as the industry standard in accessibility.
Guidance and Success Criteria from the WCAG are organized into the following four principles:
1. Perceivable
• Provide text alternatives for non-text content.
• Provide captions and other alternatives for multimedia. 222
9 • Create content that can be presented in different ways, including by assistive technologies, without losing meaning.
• Make it easier for users to see and hear content.
2. Operable
• Make all functionality available from a keyboard.
• Give users enough time to read and use content.
• Do not use content that causes seizures.
• Help users navigate and find content.
3. Understandable
• Make text readable and understandable.
• Make content appear and operate in predictable ways
• Help users avoid and correct mistakes.
4. Robust
• Maximize compatibility with current and future user tools A few key aspects that relate to content to be posted onto the Sand City website include:
• Integrating alternative text for images and maps
• Using distinguishable colors and design techniques that are comprehensible for the color-blind For a complete list of WCAG’s Guidance, see: https://www.w3.org/TR/WCAG20/ If Consultant or subconsultant needs clarification on ADA best practices, please contact [email protected].
223
EXHIBIT D: Title VI Exhibit for Federal Contracts
(US DOT Order 1050.2A)
During the performance of this contract, the contractor, for itself, its assignees, and successors in interest (hereinafter referred to as the “contractor”) agrees to comply with the following nondiscrimination statutes and authorities; including but not limited to:
Pertinent Nondiscrimination Authorities:
• Title VI of the Civil Rights Act of 1964 (42 U.S.C. § 2000d et seq., 78 stat. 252), (prohibits discrimination on the basis of race, color, national origin); and 49 CFR Part 21. • The Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, (42 U.S.C.§ 4601), (prohibits unfair treatment of persons displaced or whose property has been acquired because of Federal or Federal-aid programs and projects);
• Federal-Aid Highway Act of 1973, (23 U.S.C. § 324 et seq.), (prohibits discrimination on the basis of sex); • Section 504 of the Rehabilitation Act of 1973, (29 U.S.C. § 794 et seq.), as amended, (prohibits discrimination on the basis of disability); and 49 CFR Part 27; • The Age Discrimination Act of 1975, as amended, (42 U.S.C. § 6101 et seq.), (prohibits discrimination on the basis of age);
• Airport and Airway Improvement Act of 1982, (49 U.S.C. § 4 71, Section 4 7123), asamended, (prohibits discrimination based on race, creed, color, national origin, or sex); • The Civil Rights Restoration Act of 1987, (PL 100-209), (Broadened the scope, coverage and applicability of Title VI of the Civil Rights Act of 1964, The Age Discrimination Act of 1975 and Section 504 of the Rehabilitation Act of 1973, by expanding the definition of the terms “programs or activities” to include all of the programs or activities of the Federal-aid recipients, subrecipients and contractors, whether such programs or activities are Federally funded or not); • Titles II and III of the Americans with Disabilities Act, which prohibit discrimination on the basis of disability in the operation of public entities, public and private transportation systems, places of public accommodation, and certain testing entities (42 U.S.C. §§ 12131-12189) as implemented by Department of Transportation regulations at 49 C.F.R. parts 37 and 38; • The Federal Aviation Administration's Nondiscrimination statute (49 U.S.C. §47123) (prohibits discrimination on the basis of race, color, national origin, and sex); • Executive Order 12898, Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations, which ensures nondiscrimination against minority populations by discouraging programs, policies, and activities with disproportionately high and adverse human 224
health or environmental effects on minority and low-income populations; • Executive Order 13166, Improving Access to Services for Persons with Limited English Proficiency, and resulting agency guidance, national origin discrimination includes discrimination because of limited English proficiency (LEP). To ensure compliance with Title VI, you must take reasonable steps to ensure that LEP persons have meaningful access to your programs (70 Fed. Reg. at 74087 to 74100); and
• Title IX of the Education Amendments of 1972, as amended, which prohibits you from discriminating because of sex in education programs or activities (20 U.S.C. 1681 etseq). https://dot.ca.gov/-/media/dot-media/programs/local-assistance/documents/title-vi/appendix-e-of- the-title-v-iassurances.pdf 225
MEMORANDUM
To: Caltrans District 5, Division of Local Assistance
From: Nick McIlroy, AICP, Planning Manager, City of Sand City Date: September 28, 2026
Subject: Summary of Contract Negotiations and Fair and Reasonable Price Determination, Whitson Engineers, Sand City Multi-Use Trail Final Design, Federal Project No. 5366(002)
Purpose
This memo summarizes how the City negotiated the architectural and engineering (A&E) agreement with Whitson and Associates, Inc. dba Whitson Engineers (Whitson) for final design of the Sand City Multi-Use Trail, and how the City determined the negotiated price is fair and reasonable. The agreement is a cost-plus-fixed-fee contract with a not-to-exceed amount of $920,899.34.
Selection
• The City first advertised this work through an RFP and received only one proposal, at $1,898,599. The City did not award that proposal and re-solicited the work through a qualifications-based RFQ consistent with LAPM Chapter 10. • Statements of qualifications were due July 6, 2026. The evaluation panel interviewed Whitson on July 16, 2026, and ranked Whitson first based on combined written and interview scores. Cost was not considered in the ranking. • On July 27, 2026, the City notified Whitson it was the top-ranked firm and asked for a scoping meeting. The City said a formal LAPM cost proposal would be requested once scope was final.
Independent Cost Estimate
The City completed the Caltrans Part 1 ICE Worksheet on August 1, 2026, before receiving any cost information from Whitson. The ICE totals $1,268,390.83 and covers the full RFQ scope, including the SR 218 intersection work and right-of-way and utility support. It uses:
• 6,647 hours across project management, roadway, landscape, traffic, electrical, geotechnical, survey, environmental, public involvement, and administrative tasks • Labor rates from BLS OEWS wage data for the Salinas MSA, with California statewide data as a fallback
• A conservative 222% indirect cost rate, a 13% fixed fee from the Caltrans Profit/Fee Worksheet (weighted guidelines method), and 3% annual escalation The ICE and Profit/Fee Worksheet were submitted to Caltrans. 226
Scope Negotiations
• July 27, 2026: Whitson sent written scope questions. The City responded that (1) Task 5, SR 218 intersection improvements, stays in the scope but is priced as a separate optional item rather than folded into the base; (2) supplemental field survey (Task 2.2) applies only to Caltrans right of way if the SR 218 work proceeds; and (3) the Coastal Development Permit will be heard by the Sand City City Council, with Coastal Commission review only on appeal, so no Coastal Commission process was budgeted.
• August 18, 2026: Whitson provided a meeting agenda and a summary of its proposed fee, and asked for the current construction cost estimate and survey CAD files. • August 21, 2026: The City held a scoping meeting with Whitson, BFS Landscape Architects, and Denise Duffy & Associates (DD&A) to confirm tasks, deliverables, and responsibilities. • Scope refinements after the meeting: three technical reports were removed from DD&A’s scope because another City consultant (EMC) has already prepared them, which avoids paying twice for the same work. Whitson also removed a fixed trail width from the project description so design is not locked in before the City decides. • Whitson then submitted Exhibit 10-H cost proposals for the base scope and for optional Tasks 5 and 8, along with individual 10-H forms for each subconsultant (BFS, DD&A, Earth Systems Pacific, Hexagon Transportation Consultants, and Aurum Consulting Engineers).
Each form shows hours by classification, actual hourly rates, indirect cost rates, fixed fee, and other direct costs.
Cost Proposal Review
The City compared the cost proposals to the ICE line by line. • Hours. The Whitson team proposes 5,182 hours, 22% fewer than the ICE. The difference mostly reflects Whitson building on the existing 30% design and survey, and the scope refinements described above.
• Labor rates. Several of Whitson’s actual hourly rates for senior staff are higher than the BLS-based ICE rates. For example, Whitson’s Senior Civil Engineer is $80.50 per hour, compared to $62.48 in the ICE. Total direct labor is nearly the same, however: $346,983 in the proposal compared to $345,105 in the ICE. Whitson is using fewer, more experienced hours.
• Indirect cost rates. Whitson’s ICR is 129.36% (fringe 29.34%, overhead 41.02%, G&A
59.00%). Subconsultant ICRs range from 132% to 225%. All are well below or close to the 222% assumed in the ICE. Once the higher labor rates are fully loaded, Whitson’s Senior Civil Engineer costs about $203 per hour, compared to about $227 per hour for the equivalent ICE classification. Indirect costs are reimbursed only at approved rates and remain subject to audit under Article IX of the agreement. • Fixed fee. All firms used a 10% fixed fee, below the 13% calculated in the City’s Profit/Fee Worksheet.
• Escalation. Whitson used 5% annual salary escalation, compared to 3% in the ICE. The effect is $4,921 across all three cost proposals, and escalation is reimbursed only as actually incurred.
• Other direct costs and subconsultants. Other direct costs are limited: $3,000 for BFS reproduction, $100 for Aurum mileage, and lower-tier subconsultants for DD&A 227
(Cornerstone Earth Group, $4,980) and Earth Systems ($7,224). Whitson’s totals match the subconsultant 10-H forms.
Table 1. ICE compared to Whitson team proposal
Item City ICE Whitson team proposal
Total hours 6,647 5,182
Direct labor (before escalation) $345,105 $346,983
Indirect cost rate (ICR) 222% (conservative
assumption)
129.36% (Whitson); subs 132% to
225%
Fixed fee 13% (Profit/Fee Worksheet) 10% (all firms)
Annual escalation 3% 5% ($4,921 total)
Average fully loaded cost per hour $191 $178
Total $1,268,391 $920,899
Table 2. Negotiated contract amount
Contract component Total cost Fixed fee
Base scope (Whitson and five subconsultants) $676,253.46 $59,923.73 Optional Task 5: SR 218 intersection improvements
(Whitson and Hexagon)
$208,958.61 $18,849.36
Optional Task 8: Right of way and utilities (Whitson) $35,687.27 $3,244.30 Not-to-exceed total $920,899.34 $82,017.39
Fair and Reasonable Determination
The City accepted Whitson’s cost proposal without a price reduction. Scope was refined during negotiations, but the fee in the final 10-H forms matches Whitson’s initial fee summary. The City did not seek a further reduction because the evidence below shows the price is already fair and reasonable:
• The negotiated amount is $347,491 (27%) below the City’s ICE, which was prepared independently before any cost information was received. • It is 40% below the $1,526,000 PS&E budget in the ATP Cycle 8 project estimate. That budget was based on 30% design plans and included engineering estimates prepared and reviewed by Harris & Associates and Kimley-Horn.
• It is 51% below the only proposal received under the City’s earlier RFP ($1,898,599). • Direct labor is within 1% of the ICE. The savings come from lower indirect cost rates and a lower fee, not from under-scoping the work.
• The 10% fixed fee is below the 13% calculated with the Caltrans weighted guidelines method.
• The total is about 10.6% of the $8,678,000 construction estimate (construction items plus contingency).
• The agreement is cost-plus-fixed-fee. The City pays only actual, allowable costs at approved rates plus the fixed fee, up to the not-to-exceed amount. Optional Tasks 5 and 8 are priced separately so their costs can be tracked and controlled apart from the base scope. 228
Table 3. Price comparisons
Estimate or proposal Amount Negotiated contract compared Single proposal received under the City’s earlier
RFP
$1,898,599 $977,700 (51%) lower
PS&E budget in ATP Cycle 8 project estimate
(30% design)
$1,526,000 $605,101 (40%) lower
City Independent Cost Estimate (ICE), August 1,
2026
$1,268,391 $347,491 (27%) lower
Negotiated contract, Whitson Engineers (base
+ Tasks 5 and 8)
$920,899 n/a
Conclusion
Based on the ICE, the ATP project estimate, the earlier RFP result, and a detailed review of each firm’s 10-H cost proposal, the City has determined that the negotiated not-to-exceed amount of $920,899.34, including a fixed fee of $82,017.39, is fair and reasonable. The agreement will next go to the Sand City City Council for approval.
Nick McIlroy, AICP
Planning Manager, City of Sand City
Attachments
• Part 1 ICE Worksheet (August 1, 2026) and Profit/Fee Worksheet • ATP Cycle 8 Detailed Project Estimate (June 18, 2026) 229
Local Agency :
Project Name :
Project Location :
Control No. :
Local Agency Responsible Charge :
Phone :
E-mail :
Date :
Tasks Total Hours Direct Costs Overhead Fixed Fee Escalation Rate Total Project Cost
222% 13% 3%
1. Construction Engineering & Inspection 0 $ - $ - - $ - $ - $
2. Project Management and QC 1312 $ 80,743 $ 33,799 179,250 $ 2,422 $ 296,214 $
3. Roadway Design 2047 $ 107,272 $ 44,904 238,143 $ 3,218 $ 393,536 $
4. Bridge Design 0 $ - $ - - $ - $ - $
5. Landscape Design 959 $ 47,504 $ 19,885 105,460 $ 1,425 $ 174,274 $
6. Admininstration 542 $ 13,751 $ 5,756 30,526 $ 413 $ 50,445 $
7. Public Involvement 605 $ 36,056 $ 15,093 80,045 $ 1,082 $ 132,276 $
8. Geotechnical Analysis 324 $ 20,244 $ 8,474 44,941 $ 607 $ 74,265 $
9. Material Testing 0 $ - $ - - $ - $ - $
10. Survey and Mapping 588 $ 26,551 $ 11,114 58,943 $ 797 $ 97,405 $
11. Environmental 270 $ 12,984 $ 5,435 28,825 $ 390 $ 47,634 $
12. User Defined 1 0 $ - $ - - $ - $ - $
13. User Defined 2 0 $ - $ - - $ - $ - $
14. User Defined 3 0 $ - $ - - $ - $ - $
15. User Defined 4 0 $ - $ - - $ - $ - $
Direct Costs (includes ICR + Fix Fee + Escalation Rate) $ 1,266,051 Other Direct Costs (ODC) $ 2,340
PROJECT COST $ 1,268,390.83
Vibeke Norgaard, City Manager, City of Sand City
831-394-3054
[email protected]
August 1, 2026
Independent Cost Estimate - Part 1
(Summary Cost by Task)
City of Sand City
Sand City Multiuse Bike Trail - Final Design
Sand City and Seaside, CA (along the TAMC R-O-W and APN 011-301-028-000) #26-03
230
Detailed Project Estimate and Total Project Costs - Cycle 8 revised 04/16/2026 v1 Important: Read the Instructions in the first sheet (tab) before entering data. Do not enter data in shaded fields (with formulas).
Project Information: Agency: City of Sand City Date:
Project Description:
Project Location:
Licensed Engineer in responsible charge of preparing or reviewing this PSR-Equivalent Cost Estimate: License #: 69767 Project Estimate and Cost Breakdown:
Cost Breakdown
Project Estimate (for Construction Items Only) ATP Eligible/ ATP Ineligible and/or Corps/CCC ATP Funded Costs Non-ATP Funded Costs to Construct
Item No. Item Quantity Units Unit Cost Total
Item Cost %$ %$ % $
General Overhead-Related Construction Items
1 Mobilization 1 LS $410,000.00 $410,000 100% $410,000
2 Traffic Control 1 LS $70,000.00 $70,000 100% $70,000
3 Stormwater Protection Plan 1 LS $75,000.00 $75,000 100% $75,000 4 LS 100%
5 LS 100%
6 LS 100%
7 LS 100%
8 LS 100%
9 LS 100%
10 LS 100%
General Construction Items
11 1 LS $45,000.00 $45,000 100% $45,000
12 1 LS $55,000.00 $55,000 100% $55,000
13 1 LS $55,000.00 $55,000 100% $55,000
14 1 LS $100,000.00 $100,000 100% $100,000
15 221486 LF $4.50 $996,687 100% $996,687
16 43 EA $365.00 $15,695 100% $15,695
17 36 EA $1,500.00 $54,000 100% $54,000
18 5310 LF $19.00 $100,890 100% $100,890
19 666 LF $80.00 $53,280 100% $53,280
20 9250 LF $30.00 $277,500 100% $277,500
21 1115 SF $30.00 $33,450 100% $33,450
22 17 EA $1,200.00 $20,400 100% $20,400
23 9870 TON $155.00 $1,529,850 100% $1,529,850
24 1 LS $135,000.00 $135,000 100% $135,000
25 132 EA $8,500.00 $1,122,000 100% $1,122,000
26 Lighting System (Pull Box, Service Equipment & Enclosure, Conductors and Conduit, PG&E Service Connection) 1 LS $260,600.00 $260,600 100% $260,600 27 RRFB System 2 EA $60,000.00 $120,000 100% $120,000
28 Landscape - Minor Concrete (Paving & Pavers) 3197 SF $30.00 $95,910 100% $95,910 29 Landscape - Surface Treatments (Decomposed Granite & Rubber Paving) 4490 SF $25.00 $112,250 100% $112,250 30 Landscape - Trail Amenities (Table, Bench, Receptables, Bike Racks, Bike Repair Station, Pet Litter Station, Tree Grate 43 EA $4,200.00 $180,600 100% $180,600 31 Landscape - Fitness Equipment 15 EA $3,900.00 $58,500 100% $58,500 32 Landscape - Trail Signage 1 LS $58,000.00 $58,000 100% $58,000 33 Landscape - Irrigation (Controller, Master Valve, Flow Sensor) 2 LS $15,000.00 $30,000 100% $30,000 34 Landscape - Irrigation (Meter, Backflow, Valve, Bubblers) 60 EA $610.00 $36,600 100% $36,600 35 Landscape - Irrigation Pipe Infrastructure 4380 LF $25.00 $109,500 100% $109,500 36 Landscape - Drip Irrigation including infrastructure 37450 SF $2.00 $74,900 100% $74,900 37 Landscape - Soil Preparation 486490 SF $0.25 $121,623 100% $121,623 38 Landscape - Soil Import 233 CY $50.00 $11,650 100% $11,650 39 Landscape - Shrubs, Plants and Recycled Mulch 266390 SF $2.50 $665,975 100% $665,975 40 Landscape - Trees (Shade and Accent) 94 EA $670.00 $83,000 100% $83,000 41 Landscape - 4-month Maintenance Agreement 1 LS $58,500.00 $58,500 100% $58,500 42 Striping 1 LS $75,110.00 $75,110 100% $75,110
43 Signs 1 LS $6,000.00 $6,000 100% $6,000
44 Corner Ramps (Canyon Del Rey Blvd) 2 EA $20,000.00 $40,000 100% $40,000 45 Bike Ramps (Del Monte Blvd) 1 EA $8,000.00 $8,000 100% $8,000 46 Modify Signal and Lighting Systems (Canyon Del Rey Blvd at Del Monte Blvd) 1 LS $190,000.00 $190,000 100% $190,000 47 100%
48 100%
49 100%
50 100%
51 100%
52 100%
Subtotal of Construction Items: $7,545,470 $7,545,470
Construction Item Contingencies (% of Construction Items): 15.00% $1,131,820 $1,131,820 Total (Construction Items & Contingencies) cost: $8,678,000 $8,678,000 Project Delivery Costs: Type of Project Cost Cost $
Preliminary Engineering (PE) ATP Eligible and
ATP Funded Costs
ATP Ineligible
and/or
Non-ATP Funded
Costs
Project Approval and Environmental Document (PA&ED): $ 523,000 $523,000 Plans, Specifications and Estimates (PS&E): $ 1,526,000 $1,526,000 "PE" costs / "CON" costs Total PE: 2,049,000 $ $2,049,000 24% 25% Max
Right of Way (RW)
Right of Way Engineering: $ -
Acquisitions and Utilities: $ 40,000 $40,000
Total RW: 40,000 $ $40,000
Total Pre-Construction Costs (PE+RW): $2,089,000 $2,089,000 Construction Engineering (CE) "CE" costs / "CON" costs
Construction Engineering (CE): $ 1,295,000 $1,295,000 15% 15% Max Total Construction Costs (Construction Items & Contingencies + CE): $9,973,000 $9,973,000 ATP Eligible and
ATP Funded Costs
ATP Ineligible
and/or
Non-ATP Funded
Costs
Total Project Cost: $12,062,000 $12,062,000
Documentation of Eligible and/or Ineligible Costs:
The Engineer's justification for including typical ATP-Ineligible items in the ATP-Eligible column and logic and/or calculations for splitting costs between ATP-Eligible and Ineligible costs must be documented in this section of the Estimate form. Separate justification is required for each item which is partly ineligible for ATP funding or is required for the construction of an ineligible item/element of the project.
Item #: Description of Engineer's Justification: (See example shown in the Instructions) Adjust and Relocate Utilities to Grade
Stormwater Improvements
Asphalt Concrete Pavement including Aggregate Base
LED Lights (Standard and Type 15) with Foundation
7-day After Con Long Term User Count- Infrastructure
Remove and Dispose Existing Fences and Walls
Remove and Dispose Existing Tree
Minor Concrete (Curb and Gutter)
Minor Concrete (Curb)
Minor Concrete (ADA, Raised Crosswalk, Sidewalk, Driveway) Remove and Dispose Minor Structures including Sheds, Signs/Posts, and Tables 6/18/2026
Multiuse Trail Project
City of Sand City and City of Seaside
Leon D. Gomez, P.E.
Remove and Dispose Existing Concrete Improvements, Asphalt Concrete Pavement, Gravel Surface Clearing & Grubbing
7-day Before Con User Count- Infrastructure
7-day After Con Near Term User Count- Infrastructure
9/30/2026 1 of 1
231
AGENDA ITEM
9B.
Approve a Resolution Approving a Public
Works Contract for Construction Services
with Monterey Peninsula Engineering
(MPE) in an Amount not to Exceed
$1,081,285 for the FY 25-26 Street
Maintenance and Rehabilitation
232
City of Sand City
STAFF REPORT
TO: Honorable Mayor and City Council Members
FROM: Vibeke Norgaard, City Manager, Lean Gomez, City Engineer, and Mark Parker, Public Works Manager
SUBJECT: Adopt a resolution approving a public works contract for construction services with Monterey Peninsula Engineering, Inc. in an amount not to exceed $1,081,285 for the "FY25-26 Street Maintenance and Rehabilitation (M+R)" Project and authorizing the City Manager to execute said contract.
DATE: October 20, 2026
BACKGROUND/DISCUSSION:
The City of Sand City (City) has developed a Pavement Management Program (PMP) to provide a systematic, data-driven framework to maintain, repair, and optimize its street network balancing life-cycle costs and to provide recommendations for maintenance and rehabilitation of streets. City Staff, including the City Engineer, Public Works Manager and Planning Manager have been working to implement recommendations from the PMP and developed the "FY 25-26 Street Maintenance and Rehabilitation (M+R)" Project (Project) which includes the M+R of asphalt pavement, concrete curb, gutter, sidewalk, creation of additional parking, ADA ramp upgrades, signing, striping, and storm drainage improvements, and related work. The Project will also implement recommendations from the West End Parking Plan to increase parking where feasible.
The Base Bid scope of work includes:
. Holly Street from California Avenue to Ortiz Avenue.
. Contra Costa Street from the north of Bay Ave at State Route 1 to Redwood Avenue. . City Hall Parking Lot, including replacement of the existing sewer line.
The Additive Alternate scope of work includes:
. Playa Avenue from California Avenue to Metz Road
. California Avenue from the State Route 1 off-ramp/Caltrans Right-of-Way to approximately 150 feet south of the entrance to the Edgewater Shopping Center.
Due to limited funding, the basis of award for the Project was the Base Bid scope of work only The Additive Alternate scope of work will not be awarded at this time. 233
On April 7, 2026, the City Council approved the 70% design of the Project. Based on this approval, the Project design was finalized and bid documents were prepared by the City Engineer. To ensure a competitive bid process, the Project was formally advertised on PlanetBids on August 28, 2026, with a bid closing date of September 28, 2026. A total of six (6) bids were received as summarized below, from lowest to highest.
Name of Bidder
Montere Peninsula En ineerin , Inc.
McKim Cor oration
The Don Cha in Co., Inc.
Anderson Pacific En ineerin Construction, Inc.
Granite Rock Corn an
Precision Grade Inc.
Base Bid
$1, 081,285. 00
$1, 198, 792. 65
$1,294,000.00
$1,317,755.00
$1,332, 969. 50
$1,365, 229. 20
Staff reviewed all bid proposals and determined that Monterey Peninsula Engineering, Inc. (MPE) is the lowest responsive and responsible bidder. The Opinion of Probable Construction Cost (OPCC) for the Base Bid prepared by the City Engineer was $1, 200, 319. 00. Therefore, staff recommends approval of a public works contract with MPE for construction services for the Project.
CEQA:
The Project is categorically exempt from the California Environmental Quality Act (CEQA) understate CEQA Guidelines Sections 15301 (Existing Facilities), 15302 (Replacement or Reconstruction), and 15303 (New Construction or Conversion of Small Structures). The Project consists of the repair and minor alteration of existing streets, sidewalks, curbs, gutters, and parking areas; the replacement of existing sewer and storm drain facilities with facilities of the same purpose and capacity; and limited new sidewalk, curb ramp, and drainage improvements within the existing developed right-of-way. None of the exceptions in CEQA Guidelines Section 1 5300. 2 apply.
FISCAL IMPACT:
The three projects that make up the Project are included in the Five-Year Capital Improvement Plan (CIP) that was approved by Council on April 15, 2025. The City budgeted the following funds for these projects in FY 25-26:
$412, 000 Pavement Management Program (account 6000-704) 350 000 Parkin Construction (account 6000-704)
$762, 000 Total FY 25/26 Funds
The following funding will be brought to Council for approval with the FY 26/27 Budget:
$412,000 Pavement Management Program
65000 Cit Hall
$477, 000 Total FY 26/27 Funds
234
The Five-Year CIP proposes $412, 000 to be allocated for street management for FY 27/28 and $412,000 for FY 28/29. This additional funding for the project will be brought to Council for approval during the budget process at a later date, if needed.
The project will be funded through an allocation of $283, 000 from the Measure X Fund, with the remaining $798, 285 funded by the General Fund. These allocations may be adjusted based on the timing and amount of Measure X revenues received by the City on a quarterly basis.
RECOMMENDATION:
Adopt a resolution approving a public works contract for construction services with Monterey Peninsula Engineering, Inc. in an amount not to exceed $1, 081, 285. 00 for the Fiscal Year (FY) 25-26 Street Maintenance and Rehabilitation (M+R) Project and authorize the City Manager to execute said contract.
ATTACHMENTS:
1. Resolution
2. Contract
a. Exhibit A
b. Exhibit B
235
CITf OF SAND CITY
RESOLUTION SC _, 2026
RESOLUTION OF THE CITT COUNCIL OF SAND CITY APPROVING A PUBLIC
WORKS CONTRACT FOR CONSTRUCTION SERVICES WITH MONTEREY
PENINSULA ENGINEERING (MPE) IN AN AMOUNT NOT TO EXCEED $1,081,285 FOR THE "FY 25-26 STREET MAINTENANCE AND REHABILITATION" PROJECT AND AUTHORIZING THE Cinf MANAGER TO EXECUTE SAID CONTRACT WHEREAS, the City of Sand City (City) has developed a Pavement Management Program (PMP) to provide a systematic, data-driven framework to maintain, repair, and optimize its street network balancing life-cycle costs and to provide recommendations for maintenance and rehabilitation of streets; and
WHEREAS, staff have been working to implement recommendations from the PMP and developed the Fiscal Year 25-26 Street Maintenance and Rehabilitation (M+R) Project (Project) which includes the M+R of asphalt pavement, concrete curb, gutter, sidewalk, creation of additional parking, ADA ramp upgrades, signing, striping, and storm drainage improvements, and related work; and
WHEREAS, the Project will also implement recommendations from the West End Parking Plan to increase parking where feasible; and
WHEREAS, the Base Bid scope of work consists of Holly Street from Ortiz Ave. to California Ave., Contra Costa St. from Redwood Ave. to the north of Bay Ave. at State Route 1, and the City Hall Parking Lot, and the Additive Alternate scope of work consists of California Ave. from State Route 1 to 150 feet south of the Edgewater Center entrance and Playa Ave. from California Ave. to Metz Rd. ; and
WHEREAS, due to limited funding available, only the Base Bid scope of work will be awarded at this time; and
WHEREAS, the City Engineer and staff prepared bid documents and formally advertised the Project on PlanetBids, a web-based electronic procurement and vendor management software system, on August 28, 2026, with a bid closing date of September 28, 2026: and WHEREAS, a total of six (6) bid proposals were received for the Project which were reviewed by staff, who determined that the lowest responsive and responsible bidder was Monterey Peninsula Engineering, Inc. (MPE); and
WHEREAS, the City Council finds that the Project is categorically exempt from the California Environmental Quality Act (CEQA) under State CEQA Guidelines Sections 15301 (Existing Facilities), 15302 (Replacement or Reconstruction), and 15303 (New Construction or Conversion of Small Structures), and none of the exceptions in CEQA Guidelines Section 15300.2 apply; and
WHEREAS, staff recommends approval of a contract with MPE for construction services for the Project; and
236
NOW, THEREFORE, BE IT HEREBY RESOLVED, ORDERED AND FOUND by the City Council of the City of Sand City, State of California, as follows:
1. That the City Council approve a Public Works Contract between the City of Sand City and Monterey Peninsula Engineering, Inc. in an amount not to exceed $1,081,285 for the FY 25-26 Street M+R Project, in substantially the same form as shown in "Attachment 2" and by reference incorporated herein, and the City Manager is authorized and directed to execute the same.
PASSED AND ADOPTED, at a regular meeting of the City Council of the City of Sand City, this 20th day of October 2026 by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
APPROVED:
Mary Ann Carbone, Mayor
ATTEST:
DATED:
Kerry Lindstrom, City Clerk
237
PUBLIC WORKS CONTRACT
"FY 25/26 PAVEMENT MAINTENANCE AND REHABILITATION (M+R)"
PROJECT
THIS AGREEMENT, hereinafter referred to as the "Agreement", made and entered into this 20th day of October 2026, by and between the CITY OF SAND CITY, a municipal corporation, hereinafter referred to as the "City", and Monterey Peninsula Engineering, hereinafter referred to as the "Contractor"; WITNESSETH:
WHEREAS, the Council of the City has awarded a contract to the Contractor for performing the work hereinafter described in accordance with the City's Plans Specifications and Contractor's sealed proposal;
NOW, THEREFORE, IT IS AGREED AS FOLLOWS:
1. SCOPE OF WORK. Contractor shall furnish all labor, materials, equipment, and transportation necessary to perform the "FY 25/26 Pavement Maintenance and Rehabilitation (M+R)" Project ("the Work"), as more particularly described in the Notice to Contractors, Bid Schedule, and Special Provisions, attached hereto and incorporated herein as Exhibit A, and in accordance with the Contractor's accepted Proposal, attached hereto and incorporated herein as Exhibit B. In the event of a conflict or inconsistency between the text of the main body of this Agreement and Exhibit A or Exhibit B, the text of the main body of this Agreement shall prevail. The timing of commencement and completion of the Work is set forth in Section 3, Time of Performance, below.
2. PAYMENT. City shall pay Contractor an amount not to exceed: One Million Eighty-One Thousand Two Hundred and Eighty-Five Dollars ($1, 081,285) for the full and satisfactory completion of the Work in accordance with the terms and conditions of this Agreement. The calculation of payment for the Work shall be set forth as described in the Compensation Form, attached hereto and incorporated herein as Exhibit B. The amount stated above is the entire compensation payable to Contractor for the Work performed hereunder, including all labor, materials, tools and equipment furnished by Contractor.
Contractor shall not be compensated for any services rendered in connection with its performance of this CONTRACT which are in addition to those set forth herein, unless such additional services are authorized in advance and in writing by the City Manager. Contractor shall be compensated for any additional services in the amounts and in the manner as agreed to by City Manager and Contractor at the time CITY'S written authorization is given to Contractor for the performance of said services. The City Manager may approve additional work not to exceed ten percent (10%) of the amount of the CONTRACT, but in no event shall such sum exceed One Hundred and Eight Thousand One Hundred Twenty-Eight Dollars and Fifty Cents ($108, 128.50) unless otherwise specified in the CONTRACT. Any additional work in excess of this amount shall be approved by the City Council of Sand City.
(A) Invoices. City shall make monthly payments, based on invoices received, for Work satisfactorily performed. City shall have thirty (30) days from the receipt of an invoice that complies with all of the requirements above to pay Contractor. To be deemed complete and eligible for processing, each monthly progress payment invoice must include and be accompanied by the following required documentation: (1) current certified payroll reports and statements of compliance through the invoice date; (2) daily reports containing detailed task listings for all personnel, equipment, and subcontractors; (3) certified quantity calculations supporting all pay 238
items requested; and (4) conditional lien waivers for the current payment and unconditional lien waivers for previous payments pursuant to Civil Code Articles 8122-8138. Failure to submit complete documentation with the monthly invoice will result in the City returning the invoice without action.
(B) False Claims Act. Presenting a false or fraudulent claim for payment, including a change order, is a violation of the California False Claims Act and may result in treble damages and a fine of five thousand ($5,000) to ten thousand dollars ($10,000) per violation. (C) Retention. Pursuant to California Public Contract Code Section 7107, City shall retain five percent (5%) of the value of Work completed and materials furnished as security for Contractor's faithful performance, to be released in accordance with the retention and progress payment procedures set forth in the Special Provisions.
3. TIME OF PERFORMANCE. The work under this contract shall commence within fourteen (14) calendar days from the effective date of the Notice to Proceed and shall be completed on or before the expiration of 90 calendar days from the effective date of the Notice to Proceed.
4. SEVERABILITY. If any provision in this Agreement is held by a court of competent jurisdiction to be invalid, void, or unenforceable, the remaining provisions will continue in full force without being impaired or invalidated in any way.
5. GOVERNING LAW AND VENUE. Contractor agrees that in the performance of this Agreement, it will comply with all applicable state, federal and local laws, codes and regulations. This Agreement shall be governed by and construed in accordance with the laws of the State of California and the City of Sand City. Venue for any action regarding this Agreement shall be in the Superior Court of the County of Monterey or in the United States District Court for the Northern District of California.
6. PUBLIC BIDDING. In accordance with the provisions of Sections 1 725.5, 1771. 1, 1771.3, and 1771.4 of the Labor Code, this project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined by that chapter of the Labor Code, unless currently registered and qualified to perform public work pursuant to Section 1725.5 of the Labor Code. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029. 1 of the Business and Professions Code or by Section 10164 or 20103. 5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.
7. COMPLIANCE WITH LAWS AND LABOR STANDARDS
8. 1 General Corn liance. Contractor shall comply with all applicable local, state, and federal laws, regulations, and ordinances in the performance of this Agreement, including California Health and Safety Code Section 33422. 1 and California Labor Code Section 1770 et seq.
8.2 Prevailin Wa es. Not less than the general prevailing rate of per diem wages, and not less than the general prevailing rate of per diem wages for holidays and overtime work, for each craft, classification, or type of worker needed to execute the Project shall be paid to all workers, laborers, and mechanics employed in the execution of the Project by Contractor or any subcontractor. Local prevailing wage rates shall apply on all public works construction contracts exceeding twenty-five thousand dollars ($25, 000) and all public works contracts for alteration, demolition, repair, or maintenance work exceeding fifteen thousand dollars ($15, 000), pursuant to Sand City Municipal Code Section 12. 18.060. The DIR wage determinations are on file at 1 Pendergrass Way, Sand City, CA 93955, and shall be posted at the job site by the Contractor.
8. 3 De artment Of Industrial Relations Dir Re istration Re uirements. In accordance with Labor Code Sections 1725.5, 1771.1, 1771.3, and 1771.4, this project is subject to compliance 239
8. monitoring and enforcement by the Department of Industrial Relations (DIR). No contractor or subcontractor may be listed on a bid proposal or engage in the performance of any public work contract unless currently registered and qualified to perform public work pursuant to Section 1725.5.
8.4 Certified Pa roll Records and Submittals. Contractor and each subcontractor shall keep, maintain and submit certified payroll records in accordance with California Labor Code Section 1776 and all applicable Department of Industrial Relations requirements, including electronic submission requirements.
8.5 Workin Hours And Overtime Restrictions. Eight hours labor constitutes a legal day's work.
Contractor or any subcontractor shall forfeit penalties to the State for workers required or permitted to work more than 8 hours in any one calendar day or 40 hours in any one calendar week without proper overtime compensation, pursuant to Labor Code Sections 1810 through 1815.A renticeshi Corn liance. Contractor and all subcontractors shall comply with the provisions of Labor Code Sections 1777.5, 1777.6, and 1777.7 concerning the employment and training of apprentices.
Payment of Taxes; Tax Withholding. Contractor is solely responsible for the payment of employment taxes incurred under this Agreement and any similar federal or state taxes. To be exempt from tax withholding, Contractor must provide City with a valid California Franchise Tax Board form 590 ("Form 590"). Unless Contractor provides City with a valid Form 590 or other valid, written evidence of an exemption or waiver from withholding, City may withhold California taxes from payments to Contractor as required by law. Contractor shall obtain, and maintain on file for three (3) years after the termination of this Agreement, Form 590s (or other written evidence of exemptions or waivers) from all subcontractors. Contractor accepts sole responsibility for withholding taxes from any non-California resident subcontractor and shall submit written documentation of compliance with Contractor's withholding duty to City upon request.
9. WORKER'S COMPENSATION. By execution of this Agreement, the Contractor certifies as follows:
"I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for workers' compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract."
10. Indemnification
11. 1 Contractor's Performance. Contractor shall indemnify, defend with counsel selected by the City, and hold harmless City, its officers, agents, employees and representatives from and against any and all claims, losses, liabilities or damages, demands and actions, including payment of reasonable attorney's fees, arising out of or resulting from Services performed pursuant to this Agreement caused in whole or in part by any negligent or willful act or omission of Contractor, its officers, agents, employees, or anyone directly or indirectly acting on behalf of Contractor. The foregoing obligation of Contractor shall not apply when (1) the injury, loss of life, damage to property, or violation of law arises wholly from the gross negligence or willful misconduct of the City or its officers, employees, agents, or volunteers and (2) the actions of Contractor or its employees, subcontractor, or agents have contributed in no part to the injury, loss of life, damage to property, or violation of law. It is understood that the duty of Contractor to indemnify and hold harmless includes the duty to defend as set forth in Section 2778 of the California Civil Code. Acceptance by City of insurance certificates and endorsements required under this Agreement does not relieve Contractor from liability under this indemnification and hold harmless clause. This indemnification and hold harmless clause shall apply to any damages or claims for damages whether or not such insurance policies shall have been determined to apply. By execution of this Agreement, Contractor acknowledges and agrees to the provisions of this Section and that it is a material element of consideration. 240
11.2 Excuse for Performance. The City and Contractor (collectively "Parties") shall be excused from performing their respective obligations hereunder and from any obligation to pay liquidated damages if they are prevented from so performing by reason of earthquakes, fires, floods, war, civil insurrection, riots, strikes, freight embargoes, pandemics, and other similar catastrophic events which are beyond the control of and not the fault of the party claiming excuse from performance hereunder, and are not reasonably foreseeable or discoverable through due diligence. Notwithstanding the foregoing, adverse market conditions or the inability to obtain financing shall not constitute an excuse from performance. The Party claiming excuse from performance shall, within five (5) calendar days after such Party has notice of such cause, give the other Party notice of the facts constituting such cause and asserting its claim to excuse under this Section. If either Party validly exercises its rights under this Section, the Parties hereby waive any claim against each other for any damages sustained thereby. The partial or complete interruption or discontinuance of Contractor's services caused by one (1) or more of the events described in this section shall not constitute a default by Contractor under this contract. Notwithstanding the foregoing, however, if Contractor is excused from performing its obligations hereunder for any of the causes listed in this section for a period of thirty (30) calendar days or more, City shall nevertheless have the right, in its sole discretion, to terminate this contract by giving ten (10) Business Days' notice to Contractor. In no event shall an excuse of performance delay cumulatively exceed one hundred and eighty (180) days.
11.3 PERS Indemnification. In the event that Contractor or any employee, agent, or subcontractor of Contractor providing Services under this Agreement is determined by a court of competent jurisdiction of the California Public Employees Retirement System ("PERS") to be eligible for enrollment in PERS as an employee of City, Contractor shall indemnify, defend, and hold harmless City for the payment of any and all employee and/or employer contributions for PERS benefits on behalf of Contractor or its employees, agents, or subcontractors, as well as for the payment of any penalties and interest on such contributions, which would otherwise be the responsibility of City, and any attorneys' fees and costs incurred by the City to enforce this Section.
11.4 No Limitation of Liabilit . The indemnities set forth in this Section shall not be limited by the insurance requirements set forth in this Agreement.
11. Corn liance with All A licable Laws.
(A) Contractor shall comply with all applicable local, state and federal laws, regulations and ordinances in the performance of this Agreement.
(B) Contractor shall not discriminate, on the basis of a person's race, religion, color, national origin, age, physical or mental handicap or disability, medical condition, marital status, sex, or sexual orientation, against any employee, applicant for employment, subcontractor, bidder for a subcontract, or participant in, recipient of, or applicant for any services or programs provided by Contractor under this Agreement. Contractor shall comply with all applicable federal, state, and local laws, policies, rules, and requirements related to equal opportunity and nondiscrimination in employment, contracting, and the provision of any services that are the subject of this Agreement, including but not limited to the satisfaction of any positive obligations required of Contractor thereby. Contractor shall include the provisions of this section in any subcontract approved by the City.
(C) Contractor shall comply with the requirements of the Secretary of Labor and the latest amendments to: Executive Orders 11246 as amended by Executive Order 11375, as supplemented in Department of Labor regulations (41 C. F. R. chapter 60); the Copeland "AntiKickback" Act (18 U.S.C. § 874) as supplemented in Department of Labor regulations (29 C. F. R. part 3); Section 3 of the Housing and Urban Development Act of 1968 (12 U.S.C. §§ 1701 et seq.); Title VI of the Civil Rights Act of 1964 (42 U. S.C. §§ 2000); Section 109 of Title I of the Housing and Community Development Act of 1974 (42 U.S.C. §§ 5301 et seq. ); the Age Discrimination Act of 1975 (42 U.S. C. §§6101 et seq. ); and Section 504 of the Rehabilitation Act of 1973 (29 U. S. C. §§ 701 et seq.)
(D) Contractor shall comply with all applicable rules, regulations, and standards issued by the California Air Resources Board (CARB), including but not limited to regulations governing 241
vehicular emissions, off-road diesel equipment, and portable engines. Contractor shall furnish certificates of compliance with CARB regulations for all applicable equipment utilized in the performance of the Work upon request by the City.
(E) Pursuant to California Labor Code Section 6500, Contractor shall possess a valid Construction Activity Permit for excavations or trenches that are five (5) feet or deeper into which a person is required to descend, and shall maintain such permit for the life of the contract. Furthermore, pursuant to California Labor Code Section 6705, prior to commencing excavation of any trench five (5) feet or more in depth, Contractor shall submit to the Engineer a detailed shoring and bracing plan designed by a registered civil or structural engineer at least five (5) working days prior to the commencement of excavation.
12. AMENDMENTS. No modification or amendment of this Agreement is effective unless made in writing and signed by both the City and Contractor.
13. ASSIGNMENT AND SUBCONTRACTING. Contractor shall not assign or transfer any interest in this Agreement without the prior written consent of the City. Any substitution of subcontractors shall comply with the Subletting and Subcontracting Fair Practices Act, Public Contract Code Section 4100etseq.
14. Inde endent Contractor. It is understood and agreed that this Agreement is not a contract of employment and does not create an employer-employee relationship between the City and Contractor. At all times, Contractor shall be an independent contractor and Contractor is not authorized to bind the City to any contracts or other obligations without the express written consent of the City.
15. Excavations. In accordance with Public Contracts Code Section 7104, Contractor shall promptly notify the City in writing of discovery of any material Contractor believes may be hazardous waste as defined in Section 251 17 of the Health and Safety Code or of any subsurface or latent physical conditions at the site of any unusual nature differing materially from those generally inherent in the work described in Exhibit A. Upon receipt of such communication, City shall promptly investigate the conditions and if conditions do materially differ, shall issue a change order providing for additional time or payment of additional costs.
16. Relocation of Utilities. In the event that the completion of the services described in Exhibit A requires the removal or protection of main or trunk line public utility facilities, the City shall be responsible for removal and protection of such public utilities pursuant to Government Code Section 4215.
17. Insurance. Prior to beginning the Work and continuing throughout the term of this Agreement, Contractor (and any subcontractors) shall, at Contractor's (or subcontractor's) sole cost and expense, furnish the City with certificates of insurance evidencing that Contractor has obtained and maintains insurance in the following amounts:
A. Workers' Compensation that satisfies the minimum statutory limits. Employer's Liability insurance shall be maintained with a limit of no less than ONE MILLION DOLLARS ($1, 000, 000) per accident for bodily injury or disease.
B. Commercial General Liability and Property Damage Insurance in an amount not less than TWO MILLION DOLLARS ($2,000,000) combined single limit per occurrence, FIVE MILLION DOLLARS ($5, 000, 000) annual aggregate, for bodily injury, property damage, products, completed operations and contractual liability coverage. The policy shall also include coverage for liability arising out of the use and operation of any City-owned or City-furnished equipment used or operated by the Contractor, its personnel, agents or subcontractors.
C. Comprehensive automobile insurance in an amount not less than ONE MILLION DOLLARS ($1,000,000) per occurrence for bodily injury and property damage including coverage for owned and non-owned vehicles.
242
All insurance policies shall be written on an occurrence basis and shall name the City Indemnitees as additional insureds. The certificates shall contain a statement of obligation on the part of the carrier to notify the City of any material change, cancellation, termination or non-renewal of the coverage at least thirty (30) days in advance of the effective date of any such material change, cancellation, termination or non-renewal. Further, if the Contractor's insurance policy includes a self-insured retention that must be paid by a named insured as a precondition of the insurer's liability, or which has the effect of providing that payments of the self-insured retention by others, including additional insureds or insurers do not serve to satisfy the self-insured retention, such provisions must be modified by special endorsement so as to not apply to the additional insured coverage required by this agreement so as to not prevent any of the parties to this agreement from satisfying or paying the self-insured retention required to be paid as a precondition to the insurer's liability. Additionally, the certificates of insurance must note whether the policy does or does not include any self-insured retention and also must disclose the deductible.
18. General Warranties and Guarantee. Contractor warrants that: (A) All Work, Products and/or Services are as described in this Agreement, including any exhibits incorporated, conform to all drawings, samples, descriptions and specifications; (B) All Work, Products and/or Services delivered are new and of good merchantable quality, free from material defects of workmanship and fit for the purpose for which sold or provided; (C) Contractor has good title to all Products delivered and all Products delivered are free from liens and other encumbrances; and (D) Contractor's Work will be in strict conformity with all applicable local, state, and federal laws. For purposes of this warranty, any parts not meeting the foregoing quality shall be deemed defective.
Contractor shall guarantee the Work to be free of defects in material and workmanship for a period of one (1) year following the City's acceptance of the Work ("Contractor's Guarantee"). As part of Contractor's Guarantee, Contractor agrees to make, at Contractor's own expense, any repairs or replacements made necessary by defects in material or workmanship which become evident within the one-year guarantee period. The Contractor's Guarantee is effective regardless of whether or not a maintenance bond is required by the City for this Agreement.
19. Licenses. Contractor represents and warrants that Contractor possesses all licenses, permits, and qualifications legally required for the performance of the Work, including but not limited to a business license from the City and payment of any applicable business license tax. Contractor shall, at Contractor's sole cost and expense, maintain all such licenses, permits and qualifications in full force and effect throughout the term of this Agreement. Contractor shall hold, and shall maintain in good standing throughout the term of this Agreement, a Class "A" Contractor's License issued by the California Contractors State License Board.
20. Dama e to Cit Facilities and Site Safet . Damage to City or public facilities or private property caused by the Contractor or by its subcontractors during performance of the Work shall be repaired and/or replaced in kind at no cost to the City. The worksite shall be kept clean and free of hazards at all times during installation. After work is completed at the site, Contractor shall clean the surrounding area to the condition prior to performance of the Work.
21. Final Ins ection and Work Acce tance. All Work shall be subject to final inspection and acceptance or rejection by the City. Contractor shall guarantee the Work to be free of defects in material and workmanship for a period of one (1) year following the City's acceptance of the Work.
22. MISCELLANEOUS PROVISIONS.
23. 1 Dis ute Resolution. Prior to initiating litigation in a court of competent jurisdiction, both Contractor and City shall undergo alternative dispute procedures as outlined in Public Contract Code Section 20104, et seq. The Parties also expressly agree that such procedures are incorporated as though fully set forth in this Agreement.
23. 2 Prevailin Part . In the event that either party to this Agreement commences any legal action or proceeding (including but not limited to arbitration) to interpret the terms of this Agreement, the prevailing party in such a proceeding shall be entitled to recover its reasonable attorney's fees associated with that legal action or proceeding.
23. 3 Termination. City may terminate or suspend this Agreement at any time and without 243
cause upon written notification to Contractor. Upon receipt of notice of termination or suspension, Contractor shall immediately stop all work in progress under this Agreement.
The City's right of termination shall be in addition to all other remedies available under law to the City.
23.4 Successors. This Agreement shall bind and insure to the heirs, devisees, assignees, and successors in interest of Contractor and to the successors in interest of Contractor in the same manner as if such parties had been expressly named herein. All times stated herein or in the contract documents are of the essence hereof. As used in this instrument, the singular includes the plural, and the masculine includes the feminine and the neuter. This Agreement may create a possessory interest subject to property taxation, and Contractor may be subject to the payment of property taxes levied on such interest.
23.5 Contract Administration. This Agreement shall be administered by Audrey Cray ("Contract Administrator"). All correspondence shall be directed to or through the Contract Administrator or his or her designee.
23.6 Notices. Any written notice to Contractor shall be sent to:
Any written notice to City shall be sent to:
City of Sand City
Department of Public Works
1 Pendergrass Way
Sand City, CA 93955
23. 7 IRS Form W-9. Contractor shall complete and submit Internal Revenue Service Form W9 to the City before execution of this Agreement. The City's Finance Director shall have authority to waive this requirement.
23. 8 Attorne s' Fees. If a Party to this Agreement brings any action, including an action for declaratory relief, to enforce or interpret the provisions of this Agreement, the prevailing Party shall be entitled to reasonable attorneys' fees in addition to any other relief to which that Party may be entitled. The court may set such fees in the same action or in a separate action brought for that purpose.
23. 9 No Im lied Waiver of Breach. The waiver of any breach of a specific provision of this Agreement does not constitute a waiver of any other breach of that term or any other term of this Agreement.
23.10 Entire A reement. This Agreement represents the entire and integrated agreement between the Parties. This Agreement may be modified or amended only by a subsequent written agreement signed by both Parties.
23.11 Non-Liabilit of Officials Em lo ees and A ents. No officer, official, employee or agent of City shall be personally liable to Contractor in the event of any default or breach by City or for any amount which may become due to Contractor pursuant to this Agreement.
23.12 Survival. The obligations of this Agreement, which by their nature would continue beyond the term or expiration of this Agreement, including without limitation obligations regarding indemnification shall survive the term or expiration of this Agreement.
23. 13 Contract Bonds. Prior to execution of this Agreement, Contractor shall furnish to City (i) a Performance Bond in an amount equal to one hundred percent (100%) of the 244
Contract amount, and (ii) a Payment (Labor and Materials) Bond in an amount equal to one hundred percent (100%) of the Contract amount, each in a form acceptable to City and in accordance with Public Contract Code Section 9550 et seq. Contractor may substitute securities for any bond as permitted by Public Contract Code Section 22300.
Contractor shall maintain the Performance Bond in effect throughout the guarantee period described in Section 18, or substitute a bond equal to twenty percent (20%) of the total Contract amount, whichever is greater.
23.14 Li uidated Dama es. If the Work is not completed within the time specified in Section 3, Time of Performance, as such time may be extended in writing by the City, Contractor shall pay City liquidated damages of $4, 200 for each calendar day of delay beyond the time specified, or the actual damages sustained, whichever is greater. City may deduct such liquidated damages from any amounts due or to become due to Contractor. The Parties agree that City's actual damages in the event of such delay would be impracticable or extremely difficult to ascertain, and that this liquidated damages provision represents a reasonable estimate of such damages.
23.15 Local Hi rin Re uirement. Contractor shall make good-faith efforts to comply with Sand City Municipal Code Section 12.20.030 et seq. to hire qualified individuals who are residents of the Monterey Bay Area (Monterey, Santa Cruz, and San Benito Counties) in sufficient numbers so that no less than eighty percent (80%) of Contractor's total construction workforce, including subcontractor work force and measured in labor work hours, is comprised of Monterey Bay Area residents. Contractor shall require the same commitment of all subcontractors.
23. The Sand City City Council awarded this contract on October 20, 2026 by Resolution c. s.
24. This Agreement shall consist of this Public Works Contract document and the following items, all of which are on file in the office of the City Clerk and are incorporated herein and made a part hereof by reference:
A. Plans and Specifications
B. Accepted Proposal
C. Performance Bond
D. Payment Bond (Labor and Materials)
E. Certificates of Compliance with CARB
Regulations
F. Non-Collusion Declaration
G. Debarment and Suspension Certification
H. Certification(s) of Good Faith Effort to Hire Local Residents I. Subcontractor's List
J. Acknowledgement of Addenda
K. Certification of Worker's Compensation Insurance
L. Declaration of Bidder
IN WITNESS WHEREOF, said Contractor and said City have hereunto set their hands, all on the day and year first above written.
MONTEREY PENINSULA ENGINEERING
Signer Date
CITY OF SAND OTV
245
Vibeke Norgaard, City Manager Date
ATTEST
By; Date:
Kerry Lindstrom, City Clerk
By: Date:
Audrey Cray, Risk Manager
APPROVED AS TO FORM
By: Date;
Adam Lindgren, City Attorney
246
FY 25/26 PAVEMENT MAINTENANCE AND REHABILITATION (M+R) PROJECT
SPECIAL PROVISIONS
GENERAL
The work, in general, consists of: the maintenance and rehabilitation of street pavement and associated infrastructure, including the demolition and/or removal of concrete curbs, gutters and sidewalks, concrete planters, concrete crosswalks, curb ramps, cross gutters and spandrels, trees and landscaping, and the construction of new concrete curbs, gutters, and sidewalks, asphalt concrete dikes, asphalt pavement rehabilitation including aggregate base, stamped asphalt concrete crosswalks, storm drain catch basins, manholes, and pipes, minor sanitary sewer improvements, utility cover adjustments, utility cover relocations, signing and striping.
PLANS AND SPECIFICATIONS
A component in one Contract part applies as if appearing in each. The parts are complementary and describe and provide for a complete work. The work embraced herein shall be done in accordance with the appropriate provisions of the Standard Specifications insofar as the same may apply, and in accordance with the specifications and plans. In case of conflict between the Standard Specifications, Standard Plans, and these Special Provisions and the Plans, the order of precedence shall be as follows:
Special Provisions shall take precedence over Plans and the Plans shall take precedence over Standard Specifications and Standard Plans. These Special Provisions shall also take precedence over conflicting portions of the "General Provisions, Part III" of these project specifications.
ADMINISTRATIVE WORKFLOW
Notwithstanding any reference to Caltrans Standard Specifications regarding dispute resolution, progress payments, or administrative submittals:
. Claims Resolution: Any claim by Contractor for a time extension, for payment of money not otherwise provided for, or for payment of a disputed amount, shall first be resolved through the mandatory claim, response, and meet-and-confer/mediation process set forth in Public Contract Code Section 9204, which applies to all such claims regardless of amount and is set forth in full in the "Resolution of Construction Claims" section below. For claims of $375,000 or less that remain unresolved after that process, subsequent proceedings shall be governed by Public Contract Code Section 20104 et seq., including referral to judicial arbitration as provided therein. Nothing in this section waives or diminishes the City's or Contractor's rights or obligations under Public Contract Code Section 9204.
. Progress Payments: Monthly progress estimates and retention withholdings shall be administered directly through the Sand City Engineer, utilizing simplified local invoicing forms rather than complex state highway data systems.
CARB - CERTIFICATES OF REPORTED COMPLIANCE NEW RE UIREMEN The California Air Resources Board ("CARB") has approved amendments to the In-Use Off-Road DieselFueled Fleet regulations ("Regulations") which impact construction contractors and subcontractors and will apply to public works projects awarded after January 1, 2024. For a project involving the use of dieselfueled vehicles subject to these Regulations, the apparent low bidder shall obtain and submit to the City, within fourteen (14) calendar days after the Bid Opening Date, copies of valid Certificates of Reported Compliance ("CRC") for all subject vehicles (both the bidder's and its listed subcontractors') that will be used on the Project. The CRCs, or a detailed explanation of any exemption from the CRCs, must be 247
submitted within this period so that the bidder's responsibility can be evaluated by the City prior to award.
Failure to timely submit the required CRCs, or a detailed explanation of any exemption from the Regulations, may render the bidder non-responsible, in which case the City may reject the bid and proceed to evaluate the next lowest responsive, responsible bidder.
The In-Use Off-Road Diesel-Fueled Fleets regulations apply to all self-propelled off-road diesel vehicles 25 horsepower or greater and most two-engine diesel vehicles (except on-road two-engine sweepers) owned and operated in California. The Regulations cover a wide range of vehicle types ranging from small skid steer loaders used in small landscaping jobs to bulldozers, forklifts, cranes, and excavators, and includes vehicles/fleets that are rented or leased.
All CRCs must contain a fleet identification number, which is stored on CARB's database and available through the CARB website. All CRCs are available for download starting March 1 of each year and until February 28 of the following year and are automatically updated by CARB if a Contractor is in compliance.
The City is required to retain CRCs for three years after the project is complete, and the CRCs are subject to CARB review upon five calendar days' notice.
Further information regarding the Regulations and this new requirement may be found on the California Air Resources Board website at htt s://ww2.arb.ca. ov/our-work/ ro rams/use-road-diesel-fueled-fleetsre ulation.
CONTRACT BONDS
For Bid Bond requirements, see Part I, Bid Bond, of these Specifications.
The Contractor, at the time of signing and executing the contract, shall execute and file with the City a performance bond to the satisfaction and approval of said City, in a sum of not less than one hundred percent (100%) of the amount of the contract conditional upon the faithful performance of the contract. For additional information, see Guarantees elsewhere in these specifications.
The Contractor, at the time of signing and executing any contract in excess of twenty-five thousand dollars ($25, 000), shall execute and file with the City a payment bond (public works labor and materials bond) to the satisfaction and approval of said City, in a sum of one hundred percent (100%) of the amount of the contract in accordance with Civil Code §9550 et seq.
All bonds must be signed by principal(s) of the Contractor. All required signatures on the bond must be notarized. The surety's Attorney-in-Fact must sign all copies of the bonds, impress or affix the corporate seal on each copy, and provide one current copy of the Power of Attorney for the Attorney-in-fact.
The surety shall be an admitted carrier in California with a valid surety license and possess a minimum rating from A. M. Best Company of A-VII. The Surety and /or co-sureties must be listed as an acceptable surety on federal bonds by the United States Department of the Treasury, subject to the maximum amount shown in the listing. If co-sureties are used, their bonds shall be on a joint and several basis.
Please refer to the separate bond forms on PlanetBids.
Notwithstanding the above, the Contractor may substitute adequate securities for any bond called for under the provisions of these Specifications as set forth in Public Contracts Code Section 22300. Alternate security substitutions shall be submitted to the City no later than ten (10) days after written notice that a contract has been awarded to the contractor to allow processing and escrow agreement for in lieu security.
The Contractor shall submit the contract with their signature affixed thereto, required bonds or alternate security and evidence of insurance that conforms to the contract within fifteen (15) calendar days after written notice that a contract has been awarded to them.
The Contractor shall maintain the performance bond in full force and effect during the guarantee period for 248
the purpose of insuring that said repairs or replacements will be made, or may, at the Contractor's option, replace said performance bond for a similar bond in the amount of twenty percent (20%) of the total contract amount, including adjustments, or the original performance bond, whichever is greater.
TIME LIMITS
Within fifteen (15) calendar days after written notice that a contract has been awarded (Notice of Award), the Contractor shall submit two (2) signed original contracts, required bonds or alternative security, evidence of insurance that conforms to the contract, and City of Sand City Business License or evidence of application for said license.
The Contractor shall diligently prosecute the contract to completion on or before the expiration of 90 calendar days from the effective date of the Notice to Proceed.
LICENSES AND PERMITS
Prior to the execution of any contractual agreements, the successful Bidder shall obtain a City of Sand City Business License, and all applicable permits for construction.
City permits shall be issued at no charge.
Contractor shall be required to obtain and hold an appropriate Permit (such as an Encroachment Permit) from the Engineering Department and/or a Building Permit from the Building Department. Contractor shall provide a copy of the completed permit(s) to the Engineering Department no later than three (3) days prior to the start of construction. The permit application fee(s) shall be waived. Where applicable, the City shall submit permit applications.
SITE INSPECTION
It shall be the Contractor's responsibility to inspect the site and become thoroughly familiar with all aspects of the work to be done.
The submission of a bid shall be conclusive evidence that the Bidder has investigated the site and is thoroughly satisfied as to the conditions to be encountered, as to the character, quality, and scope of the work to be performed; the quantity of materials to be furnished; and as to all the requirements of these specifications.
It shall be the Contractor's responsibility to be aware of surface and subsurface drainage conditions that may exist at the site. The Contractor is further responsible for work necessary to rectify any resulting drainage problems; labor, materials, equipment, and incidentals necessary to achieve the solution shall be borne by the Contractor.
SUBMITTALS
The review of submittals and approval thereof by the City does not relieve the Contractor from compliance with the requirements and intentions of the plans and specifications to which the submittals pertain.
Submittal Format:
1 Contractor shall submit individually bound copies of all submittals and revised submittals to the City's construction manager. A minimum of two (2) copies shall be submitted unless otherwise directed. Submittal submission may be done in pdf form via email.
2. All submittals shall have a cover sheet containing the following:
249
a. Submittal date, submittal number and submittal revision number (as applicable), b. City project name,
3. Each submittal item shall clearly identify the specification section(s) and paragraph(s) for with the submittal item pertains to.
4. Contractor is not guaranteed a specific review time period. If Contractor requires a quick submittal turnaround of specific submittal items, Contractor must indicate which submittal items require a quick turnaround by attaching a memo to the submittal indicating such and the requested turnaround period. The City shall make every effort to meet the requested review period.
5. Contractor shall place orders for all materials or equipment in time to prevent any delays to the construction schedule or project completion. If any materials or equipment are not ordered in a timely fashion, any additional charges made by equipment manufacturers and/or suppliers to complete the manufacturer and/or delivery in time to meet the construction schedule or project completion, together with any special handling charges shall be borne by the Contractor.
Submittal Content and Product Data:
1. Contractor shall review and accept submittals prior to submission.
2. Submittals shall contain all required information such as shop drawings, product data, etc.
3. Each submittal item shall be identified by manufacturer, brand name, trade name, model number, size, rating and additional information as is necessary to properly identify and verify the materials and equipment. The phrase "as specified" is not considered sufficient.
4. Where possible, submittal information shall be limited to the specific item being submitted. In the event multiple materials or equipment are described in one submittal, Contractor shall clearly identify the pertinent information being submitted on.
5. Accessories, controls, finish, etc. not required to be submitted or identified with the submittal shall be furnished and installed as specified.
CONSTRUCTION SURVEYS
The City shall provide construction staking and survey control for this project. The City's Surveyor, who performed the original base survey, will furnish all construction stakes and marks necessary to establish the tines and grades required for the completion of the work as shown on the plans and specifications. The Contractor shall give at least seventy-two (72) hours' written notice to the Construction Manager when staking is required and shall have at least a half days' worth of work per visit. The City's surveyor or the City shall provide the Contractor with request forms and additional information.
The City Surveyor shall also be responsible for identifying, referencing, protecting, perpetuating, resetting, and/or replacing existing survey monuments that may be disturbed or destroyed by construction activities, including preparation and filing of any required Corner Records or Records of Survey. The Contractor shall notify the City Surveyor immediately upon discovering any monument that may be affected by construction operations and shall not disturb any survey monument without prior coordination.
All distances and measurements are given and will be made in a horizontal plane. Grades will be given from the top of stakes or nails, unless otherwise noted.
Finished surfaces in all cases shall conform to the lines, grades, cross-sections and dimensions shown on the approved plans and specifications. Deviations from the approved plans and specifications must be approved by the Engineer and authorized in writing.
250
Staking will include one set of stakes or marks at about twenty-five feet on center (25' 0/C) which shall be used for excavation, filling, and alignment of improvements.
The Contractor shall preserve all stakes and points set for lines, grades, or measurement of the work in their proper places until authorized to remove them by the Engineer. All expenses incurred in replacing stakes that have been removed without proper authority, or damaged due to the Contractor's operations, shall be paid by the Contractor.
The City shall be given the opportunity to check forms for line and grade prior to any concrete being placed.
Should the Contractor request staking beyond that described above, or re-staking due to the Contractor's failure to preserve stakes, such additional staking shall be performed by the City's Surveyor at the Contractor's expense, and the cost shall be deducted from monies due the Contractor.
PROTECTION OF PRIVATE PROPERTT
Private property grounds and facilities, if damaged or removed because of the Contractor's operations, shall be restored or replaced to same or better than the original condition and located in the same position and alignment as is reasonably possible. Contractor shall comply with the applicable portions of Section 5-1 .36, "Property and Facility Preservation", Section 7-1. 05, "Indemnification", and Section 7-1. 06, "Insurance" of the Standard Soecifications.
CONSTRUCTION QUALITY CONTROL
Definitions
Quality Management (QM) - All control and assurance activities instituted to achieve the product quality established by the contract requirements.
Contractor Quality Control (CQC) - The construction contractor's system to manage, control, and document contractor's, suppliers', and subcontractor's activities to comply with contract requirements.
Contractor Res onsibilit
General: The Contractor shall establish and maintain an effective quality control system in compliance with the Plans and Specifications. The quality control system shall consist of plans, procedures, and organization necessary to provide materials, equipment, workmanship, fabrication, construction, and operations which comply with contract requirements. The system shall cover construction operations both onsite and offsite, and shall be keyed to the proposed construction sequence.
The Qualit Control Plan
Quality Control Plans and Procedures.
The Contractor will be required to prepare a Quality Control Plan. This plan shall include, as a minimum, the following:
1. A description of the quality control procedures, including a chart showing lines of authority and acknowledgement that the Contractor shall implement the control system for all aspects of the work specified and shall report to the project manager or someone higher in the Contractor's organization.
2. The name, qualifications, duties, responsibilities, and authorities of each person assigned a QC function.
3. A copy of the letter to the Engineer signed by an authorized official of the firm which describes the 251
responsibilities and delegates the authority to implement the QC plan shall be furnished.
4. Procedure for scheduling and managing submittals, including those of subcontractors, offsite fabricators, suppliers, and purchasing agents.
5. Control testing procedures for each specific case. Note that in the case of federally-funded projects, QA/QC testing must be performed by the city by a Caltrans-certified lab.
6. Reporting procedures including proposed reporting formats.
QC Plan Im lementation
1. Preconstruction Conference. During the pre-construction conference, a mutual understanding of the CQC system details shall be developed, including the forms for recording the CQC operations, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's management with the Engineer's inspection. Minutes of the conference shall be prepared by City staff, and be signed by both the Contractor and the Engineer.
The minutes shall become a part of the contract file. There may also be occasions when subsequent conferences will be called to reconfirm mutual understandings.
2. General. After issuance of the Notice to Proceed, and prior to the start of construction, the Contractor shall furnish, for acceptance by the Engineer, the Contractor Quality Control (CQC) Plan with which he proposes to implement the requirements of Contract Clause entitled "Construction Quality Control". The plan shall identify personnel, procedures, instructions, records, and forms to be used. If the Contractor fails to submit an acceptable QC plan within the time herein prescribed, the Engineer may refuse to allow construction to start if an acceptable interim plan is not furnished.
3. Control of Materials Tests and Ins ections. As listed below, and noted elsewhere in the specifications but not limited to the following items, the Quality Control Plan will include the dates for the Contractor to furnish certificates for product, or product test compliance, shop drawings or catalog cuts and requests for inspection or review.
a. Tests and Ins ections:
Sub-grade compaction
Aggregate placement and compaction
Forms Placement
Trench backfill and bedding
Reinforcing bar placement
Fill Material (if applicable)
Pipe placement
Lateral Connections
High Strength Fasteners and Bolts
Epoxy
b. Materials and Materials Certification:
Aggregate Base
Hot Mix AsphalVAsphalt Concrete
Concrete
Catch Basin and Manhole Casting
Reinforcing Bar
Pipe Material
Trench backfill material
Lumber
RC pipe
Slurry backfill
252
c. Daily Reports
The Contractor shall provide copies of daily reports which describe the work performed, weather conditions, personnel and equipment on site, and quality control activities performed.
The Contractor will not be paid for work prior to Engineer reviewing and accepting daily reports for the period of time payment is requested.
4 Acce tance of Plan. Acceptance of the Contractor's plan is required prior to the start of construction. Acceptance is conditional and will be predicated on satisfactory performance during the construction. The Engineer reserves the right to require the Contractor to make changes in the CQC plan and operations as necessary to obtain the quality specified.
5. Notification of Chan es. After acceptance of the QC plan, the Contractor shall notify the Engineer in writing of any proposed change. Proposed changes are subject to acceptance by the Engineer.
6. Testin and Certification. The Contractor shall pay for all tests and inspections as required by the Plans and Specifications. The Contractor shall furnish certification of materials being used, upon request of the Engineer, without additional charge.
GUARANTEE
Materials and labor guarantees shall be per Part III of these specifications. All warranty shall be to the satisfaction of the City. Final payment will not be released without submission of warrantees. Any materials installed in Army Buildings (with City of Sand City approval) shall issue warranty (if exists) to the United States Army prior to formal acceptance of work, and deliver to the City of Sand City, Engineering Department.
REGULATIONS
The Contractor and all subcontractors shall give all notices and comply with all laws, ordinances, rules, and regulations applicable to the work, safety and hiring/employment practices. Nothing in the Plans and Specifications shall be construed to permit work not conforming to the regulations and codes set forth herein which include, but are not limited to the following:
1. Americans with Disabilities Act (ADA) accessibility and employment standards. In the event of conflicting federal and state standards, the standard that provides greater access will take precedence.
2. Sand City Municipal Code, as amended,
3. California Building Code, latest edition as adopted by the City of Sand City,
4. California Electrical Code, latest edition as adopted by the City of Sand City,
5. California Mechanical Code, latest edition as adopted by the City of Sand City,
6. California Plumbing Code, latest edition as adopted by the City of Sand City,
7. California Green Building Standards Code, latest edition as adopted by the City of Sand City,
8. California Historic Building Code, latest edition as adopted by the City of Sand City,
9. California Occupational Safety and Health Administrative Code, latest edition,
10. California Government Code Section 4216, Protection of Underground Infrastructure, 253
11. National Fire Protection Associations NFPA 1 Fire Code, latest edition,
12. The California Labor Code,
13. Federal Water Pollution Control Act (Clean Water Act), and,
14. Porter-Cologne Water Quality Control Act (California Water Code Section 13000 et seq. ).
15. Title 13, California Code of Regulations, Sections 2449, 2449. 1, and 2449. 2.
PUBLIC SAFETY AND PROTECTION OF THE WORK
The Contractor shall furnish, erect and maintain such fences, barricades, guards, lights and other devices as are necessary to prevent accidents and avoid damage to the construction work or injury to the public.
No separate payment shall be made for such work. If in the opinion of the Engineer, adequate barricades or warning devices are not maintained by the Contractor, the City may furnish and erect same and charge the Contractor therefore. Attention is directed to Sections 7-1.03 "Public Convenience" and 7-1.04, "Public Safety", of the Standard Specifications published by the State of California Department of Transportation.
PRE-CONSTRUCTION CONFERENCE
Prior to the beginning of any work on this project, a pre-construction conference shall be held at the City Hall, 1 Pendergrass Way, Sand City, CA. The date and time of this conference shall be established by the Contractor contacting that office at 831-394-3054 not less than forty-eight (48) hours in advance of the meeting date and time.
An itemized list of materials and equipment the Contractor proposes to use on the project shall be submitted to the City prior to or during the preconstruction conference.
A preliminary project timeline shall be submitted to the City prior to or during the preconstruction conference.
LIQUIDATED DAMAGES
Unless stated otherwise in the Specifications, it is agreed by the parties to the contract that in case all the work called for under the contract is not completed before or upon the expiration or the time limit as set forth in these specifications, damage will be sustained by the City of Sand City and that it is and will be difficult or impossible to ascertain and determine the actual damage which the City will sustain in the event of and by reason of such delay; and it is therefore agreed that the Contractor will pay to the City of Sand City the sum of four thousand two hundred dollars ($4, 200) per day for each and every day's delay beyond the time prescribed to complete the work or the actual damages ascertained, whichever will be greater; and the Contractor agrees to pay such liquidated damages as herein provided; and in case the same are not paid, agrees that the City of Sand City may deduct the amount thereof from any money due or that may become due the Contractor under the contract.
It is further agreed that, in case the work called for under the contract is not finished and completed in all parts and requirements within the time specified, the City shall have the right to extend the time for completion of the contract or not, as may seem best to serve the interest of the City; and if it decides to extend the time limit for the completion of the contract, it shall further have the right to charge to the Contractor, their heirs, assigns or sureties, and to deduct from the final payment of the work, all or any part, as it may deem proper, of the actual cost of engineering, inspection, superintendence and other overhead expenses during the period of such extension, except that the cost of final measurements and preparation of final estimate shall not be included in such charges.
NOTICES
254
All notices which the City or the Contractor may be required, or may desire, to serve on the other, shall be effective only if delivered by personal delivery or by postage prepaid, First Class Certified Return Receipt Requested
United States Mail, addressed to the City or the Contractor at their respective address set forth in the Declaration of Bidder, or such other address(es) as either the City or the Contractor may designate from time to time by written notice to the other in conformity with the provisions hereof. In the event of personal delivery, such notices shall be deemed effective upon delivery, provided that such personal delivery requires a signed receipt by the recipient acknowledging delivery of the same. In the event of mailed notices, such notice shall be deemed effective on the third working day after deposit in the mail.
CONSTRUCTION PROCEDURE
An outline of the proposed construction procedure shall be submitted by the Contractor to the Engineer for review and shall obtain their approval before beginning work. The Engineer will be especially interested in:
1. Minimizing any interruption to use of driveways (no more than 4-hour interruption). Any interruption more than 4 hours shall be prearranged with the Engineer. Residence occupant shall be notified with a written notice a minimum of five (5) business days in advance.
2. Adjacent property owners shall be notified with a written notice a minimum of three (3) business days in advance of any construction impacts.
3. Minimizing any interruption to building operations and parking lots. Contractor shall notify the Engineer a minimum of one week in advance of any interruptions to building operations and parking lots.
4. Minimizing any hazard to the general public.
5. Proper handling of hazardous materials.
6. All work will occur between 7 am and 7 pm unless otherwise approved in writing.
7. Contractor shall notify the Engineer a minimum of twenty-four (24) hours in advance of concrete placement for checking and acceptance of forms by the Engineer prior to concrete placement.
Mitigation of concrete placement done without acceptance of forms by the Engineer prior to concrete placement shall be the sole responsibility of the Contractor. The costs of such mitigation shall be borne by the Contractor.
Traffic control requirements cited elsewhere in these Specifications must be considered in the construction procedure submitted to the Engineer.
TRAFFIC CONTROL
Pursuant to the authority contained in the California Vehicle Code, Section 591, the City has determined that within those areas that are within the limits of the project and are open to traffic, the Contractor shall comply with all the requirements set forth in Divisions 11, 12, 13, 14 and 15 of the Vehicle Code. In accordance with the statement in Vehicle Code Section 591, this section shall not relieve the Contractor or any person from the duty of exercising due care. The Contractor shall take all necessary precautions for safe operation of the Contractor's equipment and the protection of the public from injury and damage from the Contractor's equipment.
Traffic control shall conform to the provisions of Section 12, "Temporary Traffic Control" of the Standard Specifications and the most current version of the California Manual on Uniform Traffic Control Devices (CA MUTCD) as adopted by Caltrans.
A Traffic Control Plan (TCP) shall be submitted to the Engineer for approval at least 10 workings days prior 255
to scheduled construction and must be applicable to existing site conditions. When site specific TCPs are used the plan must be to scale and include a scale, north arrow, and street names. If plans are developed by a licensed engineer, the plans shall be stamped, signed, and dated by the professional civil or traffic engineer in accordance with the California Professional Engineers Act. When typical applications from Chapter 6H of the MUTCD are used the Engineer may approve their use with or without additional conditions. The Engineer has 10 days to respond and must approve the traffic control plan before work can begin. The City is not responsible for any delays resulting from rejected TCPs that do not meet the requirements of the MUTCD and these Specifications.
Contractor shall notify all emergency services, affected residences, affected businesses, and the Engineering Department (831) 394-3054 a minimum of five (5) business days in advance as to proposed closures and alternate routes available.
The following shall be incorporated into the Traffic Control Plan:
1. Two (2) travel lanes shall be open during non-working hours.
2. At least one (1) travel lane shall remain open during working hours. Flag persons or other appropriate traffic control devices as approved by the Engineer shall be used during periods ofoneway travel.
3. Access to driveways shall be left open unless work is actually being performed in areas fronting the driveway. All driveways shall be accessible during non-working hours. See Construction Procedure elsewhere in these specifications.
4. No trench shall be left open during non-working hours.
5. Parking restrictions will be acceptable when and where needed. (All require prior approval of the Engineer).
The following requirements apply to Traffic Control Plans:
1. All Traffic Control Plans shall follow the CA MUTCD Chapter 6. Examples may be found at:
htt s://dot. ca. ov/-/media/dot-media/ ro rams/safe - ro rams/documents/ca-mutcd/rev5/camutcd2014-rev5-a11 . df
2. The contractor shall submit a TCP using legible lettering. Show location and dimensions of the work zone, lanes, tapers, parking and any staging areas.
3. Label streets and proposed traffic control area. Show all nearby streets with street names to assure proper orientation.
4. Show all affected sidewalks, crosswalks, bike lanes, driveways and intersections in the construction work zone including areas affected by taper transition.
5. If a sidewalk, crosswalk or path is obstructed or partially obstructed, contractor must then submit an ADA compliant pedestrian traffic control plan in accordance with the CA MUTCD chapter 6D and the Public Rights-of-Way Accessibility Guidelines (PROWAG). Please refer to:
htt s://dot. ca. ov/-/media/dot-media/ ro rams/safet - ro rams/documents/ca-mutcd/rev5/camutcd2014- art6-rev5. df
6. Label all taper lengths and widths, delineator spacing and sign spacing. Indicate location of construction signs, barricades and delineators.
7. Show all parking restriction zones and signs, as appropriate. Temporary "NO PARKING" signs shall be posted seventy-two (72) hours prior to commencing work. 256
8. Indicate on the TCP the duration of the construction work, including dates and times.
9. Indicate on the TCP the Contractor's name, address and telephone number. Include the Contractor's during and after hours Representative's contact information (name, telephone number).
10. It is the Contractor's responsibility to assure that all Traffic Control Plans (TCP) and traffic control devices are in compliance with the current version of the CA MUTCD as adopted by Caltrans.
Traffic Control Plans shall contain the following notes:
1. Minimum width of temporary traffic lanes is ten (10) feet clear (from delineator or cone base, not center). Minimum width at truck routes is eleven (11 ) feet clear.
2. The City Traffic Engineer or their representative has the authority to make any field changes to assure public safety.
3. All traffic control devices shall be removed from view when not in use. Signs shall not be facing traffic when not in use.
4. Spacing of channelizing devices shall not exceed twenty-five (25) feet.
5. Any road closure also requires notification be provided to the City of Sand City Fire Department and Police Department. Notifications may be made at the non-emergency telephone number, 831.646. 3914.
6. All temporary traffic delineation (delineators and cones) used shall be a minimum of thirty-six (36) inches tall. Retroreflective bands are required for night time traffic control.
7. Any work that disturbs normal traffic signal operations shall be coordinated with the Streets Division and Traffic Signal Maintenance Contractor.
8. The Contractor is responsible for restoring the road back to satisfactory condition including, but not limited to, paving, striping, markings, signs and traffic signal loop detectors within five (5) calendar days of completion of work at affected intersections or road segments.
9. Any work that created an undue safety risk or creates severe congestion may be shut down by the City Traffic Engineer, their representative, Field Inspector or Police Department personnel.
The Contractor is to notify residences and/or businesses a minimum of three (3) business days in advance of closing access to any driveways or providing any detours or changes in on-street parking.
Notifications shall be in writing.
Contractor shall provide all labor and facilities required for safe and expeditious handling of traffic during the course of construction. Contractor shall provide all flaggers, signs, delineators, and barricades required for traffic control and shall modify or remove same at appropriate times. The Engineer shall be the sole judge as to the adequacy of the Contractor's traffic control measures. If such measures are found to be inadequate by the Engineer, the City may furnish and install same and charge the Contractor therefor.
The Contractor shall, at their own expense, construct and maintain in good condition, such detours, detour bridges and temporary crossings for use by the public as deemed necessary or expedient by the Engineer for the proper execution of the work.
The Contractor shall designate a representative who can be reached immediately (24 hours per day) in the event of traffic control device failures.
257
CONSTRUCTION PROJECT SIGNS
The Contractor shall post temporary Sand City Capital Improvement Project signs, one at each end of the blocks or at entrances to project sites, in a manner approved by the Engineer. Sign panels shall be provided by the City and mounted on stakes. Sign panels and posts, if provided by the City, shall be returned to the City in good condition.
REMOVAL OF OBSTRUCTIONS
The Contractor shall remove and dispose of all structures, debris or other obstructions of any character to the construction called for in the plans, specifications, and as required by the Engineer.
If archeological items or hazardous wastes are discovered during construction operations, the Contractor shall cease operations in those areas and the Contractor shall immediately notify the Engineer.
The Contractor shall remove and dispose of all trees designated for removal as shown on the plans, designated by the specifications and as required by the Engineer for the proper completion of the work.
See Tree Protection Requirements elsewhere in these specifications.
UNDERGROUND UTILITIES
Contractor shall locate all underground obstructions and utilities, (electric, gas, water lines, etc.). Prior to any trenching operation, Contractor shall pothole underground obstructions and utilities that appear to be in conflict with the new construction. The Plans show the approximate location of underground facilities in the project area as they have been provided to the City. Repair of damage to any utility line shown on the Plans with reasonable accuracy shall be made at the Contractor's expense, hfowever, the City shall fairly compensate the Contractor for costs of locating and repairing damage not due to failure of the Contractor to exercise reasonable care, and removing or relocating such facilities not indicated or in a location different from that indicated on the Plans and Specifications with reasonable accuracy, and for equipment on the project necessarily idled during such work. Contractor shall not be assessed liquidated damages for delay in completion of the project when such delay was caused by the failure of the City or utility company to provide for removal or relocation of such utility facilities. Contractor shall notify all utility companies of trenching operations forty-eight (48) hours in advance to enable the utility companies to take any action they deem appropriate.
UTILITY COMPANY COORDINATION
Contractor shall coordinate construction activities with the utility companies as required and shall adjust the construction schedule to accommodate utility relocation as necessary.
CONTRACT PLANS AND SPECIFICATIONS
The Contractor will be supplied with five sets of plans and specifications at no expense. One of these sets of plans is to be used for the purpose of recording record (as-built) conditions. Additional sets will be furnished on request at the cost of reproduction. The work shall conform to the contract plans and specifications, all of which form a part of the contract documents and are available in the office of the City Engineer, City Hall, Sand City, California.
DUST CONTROL
The Contractor shall minimize dust generation from the jobsite and shall spray the site with water or dust palliative as required, in accordance with Section 14-9, "Air Quality", of the Standard Specifications.
CONNECTION TO EXISTING UTILITIES
258
The City shall permit the Contractor to use available existing utilities at the City's expense, excluding telephone; however, if the Contractor chooses to make use of said utilities, Contractor shall assume full responsibility for any changes made by Contractor related thereto, and for any consequences caused thereby. Upon completion of the work, Contractor shall remove any modifications to existing utilities made by Contractor, and shall restore existing utilities to conditions existing at time of award.
SANITARY FACILITIES
Contractor may provide their own portable sanitary facilities on-site, for the duration of the work. Coordinate location(s) with the Engineer. Existing City-owned sanitary facilities may be used.
INSPECTION OF WORK
It is the responsibility of the contractor to call for all required inspections within the required time lines. The City of Sand City reserves the right to perform random inspections at any time.
The Engineer shall at all times have access to the work during construction, and shall be furnished with every reasonable facility for ascertaining full knowledge respecting the progress, workmanship and character of materials used and employed in the work.
Whenever the work provided and contemplated by the contract shall have been satisfactorily completed and the final cleanup performed, the Engineer will make the final inspection.
RECORD DRAWINGS
A set of marked-up prints, clear, legible, and made with standard drafting tools and indicating all changes, added work, and deviations from the design and reflecting the record (As-Built) condition of the work must be received before the work is considered complete. Existing utilities exposed during construction are to be located, including invert or top elevation, and shown on the Record (As-Built) drawings.
The Record (As-Built) Drawings shall be submitted for the Engineer's acceptance with each progress payment. Final Record (As-Built) Drawings shall be submitted for the Engineer's acceptance before final payment and Notice of Completion on this contract will be made. The final pay application will not be considered complete until accurate Record (As-Built) Drawings have been submitted by the contractor and accepted by the City.
The Contractor shall prepare final as-built drawings of the project based on actual conditions after construction. As-built drawings shall be prepared in AutoCAD with any changes clearly delineated within the file. The City will provide the AutoCAD drawings for the plan set and reference files for the contractor's use. AutoCAD and PDF files shall be submitted electronically to the City for record.
ENVIRONMENTAL/POLLUTION PREVENTION REQUIREMENTS
Contractor shall comply with all air pollution and environmental control rules, regulations, ordinances and statutes that apply to the project and any work performed pursuant to the contract. Additionally, Sand City Municipal Code Chapter 13.05 Stormwater Management Section 13.05.060 Prohibition of Illegal Discharges, states,
"/Vo person shall discharge or cause to be discharged into the municipal storm drain system or water courses any materials. including, but not limited to, pollutants or waters containing any pollutants that cause or contribute to a violation of applicable water quality standards, other than stormwater."
Regardless of project size, the Contractor shall submit a site-specific Erosion and Sediment Control Plan or Storm Water Pollution Prevention Plan for City review and approval prior to start of work. The Contractor shall effectively implement and properly maintain storm water best management practices (BMPs) during 259
construction to prevent discharges of pollutants, and including trash, to local drainages and waterways.
Contractor shall comply with all water quality regulations in Sand City Municipal Code Chapter 13.05 Stormwater Management, and City Phase II Storm Water Permit requirements as prescribed by the State Water Resources Control Board (SWRCB) and Central Coast Regional Water Quality Control Board (RWQCB) regulations for the prevention of construction site discharges of pollutants, illicit discharges, and enforcement of prohibited and illicit discharges. The contractor shall employ at all times storm water runoff controls and BMPs at the site, including but not limited to erosion prevention, sediment controls, site stabilization, good housekeeping practices, proper materials storage, handling, and waste management, and similar pollution prevention measures to prevent dumping or illegal discharges during construction into the street and/or storm drain system. Storm water management and control practices shall result in the following outcomes on all construction sites, regardless of size:
. Protection of storm drain inlets and adjacent waterways must be implemented at all times to prevent illicit discharges of sediment, construction debris and fluids, and waste of any kind; . No release of hazardous substances, such as oils, paints, thinners, fuels, and other chemicals; if such a spill occurs that may threaten local water quality, contractor must call 911 immediately and notify City Public Works staff;
. Minimization of site disturbance shall be kept to that portion necessary for construction only, and perimeter controls shall be implemented at all times during all weather conditions; . Soil stabilization of graded areas shall be in place at all times where construction activities have temporarily and/or permanently ceased;
. No deposit of mud, soil, sediment, concrete washout, trash, dewatering, or other similar constructionrelated material or waste shall occur on or into public rights of way, private streets, or into the City's storm water system and related natural resources, either by direct deposit, dropping, discharge, erosion, or tracking by construction vehicles. Any such discharge shall be cleaned-up promptly if an immediate threat to water quality exists, or if not immediate, at the end of the current work shift or workday in which the deposit occurred, whichever comes first; . No runoff from graded areas or stockpile areas shall contain sediments and/or pollutants. Stockpiles shall be adequately and securely covered to avoid contact with rainfall and wind to prevent soil and stockpile movement by water and/or wind;
. Runoff containing sediments shall be captured in secondary containment structures and either treated to remove sediments prior to discharge or infiltrated in the soil on-site; . No exposure of graded areas and stockpile areas to storm water run-on shall occur. Run-on shall be controlled by diversion structures such as dikes, secondary containment, or stockpile covers; and, . All hard-surfaced areas are to be swept regularly and free of dirt and construction debris such that the surface of the pavement is clearly visible at all locations, and construction entrance/exist(s) shall be adequately stabilized to prevent tracking of soil/sediment from reaching streets/paved surfaces and drainage pathways.
Best management practices (BMPs) are required to be illustrated in construction Plans and employed on all construction sites as applicable to the construction activity and shall provide for, and not be limited to:
inlet protections, perimeter protections, erosion prevention and soil control measures, soil stabilization measures, spill prevention and discharge control measures; solid waste containment; concrete waste management; proper vehicle and equipment cleaning, fueling, and maintenance; and proper materials management and storage. Detailed procedures to accomplish these protections can be found through the California Storm Water Quality Association's Construction BMP Handbook Portal, U.S. EPA Construction BMP Database and Factsheets, Caltrans Storm Water Quality Manuals and Handbooks, and the Erosion 260
and Sediment Control Field Manual by San Francisco Bay Regional Water Quality Control Board.
Referenced documents are available for viewing at the City of Sand City, City Hall.
Activities to be performed by Contractor include, but are not limited to:
. Development and submittal of an Erosion and Sediment Control Plan or Storm Water Pollution Prevention Plan for City review and approval prior to construction start. . At all times, Contractor shall implement and maintain the temporary and permanent vegetation (if any), erosion and sediment control measures, and other protective BMP measures in good and effective operating condition by performing routine inspections to determine condition and effectiveness of BMPs, restoration needs for destroyed vegetative cover, and by repair of erosion, sediment, and other protective measures.
. Contractor shall inspect the following areas at least once every seven (7) calendar days, unless otherwise necessary based on current weather conditions or as directed by City inspector, and always within 24 hours prior to and after any predicted storm:
o Inlet protections and perimeter controls;
o Vehicle entry and exist locations;
o Vehicle parking and storage areas;
o Disturbed areas of the construction site,
o Areas that have not been finally stabilized,
o Areas used for storage of materials that are exposed to wind or precipitation, o Equipment and staging areas that are exposed to wind or precipitation; and, o All waste storage and handling devices and areas.
Where sites have been finally stabilized, such inspection shall be conducted at least once every month. . Areas noted above shall be inspected for proper BMP implementation and necessary BMP maintenance, as well as evidence of, or the potential for:
o Erosion, or
o Sediments entering waterways or the drainage system, or o Pollutants entering waterways or the drainage system.
Erosion and sediment control measures shall be observed and maintained to ensure that they are operating correctly. Discharge locations or points shall be inspected regularly to ascertain whether erosion control measures are effective in preventing sedimentation and subsequent degradation of receiving water quality in violation of receiving water quality standards. Vehicle entry and exist locations shall be inspected for evidence of offsite sediment and pollutant tracking and need for cleanup and improved BMP protection measures
. Deficiencies observed during inspections shall be noted and rectified before the end of the workday.
Additionally, the Contractor shall comply with the State Water Resources Control Board's Construction General Permit (CGP), as applicable to the project. Projects subject to the CGP include those that disturb one or more acres of soil, are less than one acre and are part of a common plan of development or sale, or applicable Linear Underground/Overhead Projects, and are required to obtain coverage under the State's CGP for Discharges of Storm Water associated with Construction Activity Construction General Permit Order 2009-0009-DWQ, and subsequent amendments thereto. Construction activities subject to this permit include clearing, grading, and disturbances to the ground such as stockpiling, or excavation, but do not include regular maintenance activities performed to restore the original line, grade, or capacity of the facility.
Application for CGP coverage is made by the Contractor through a Notice of Intent (N01) to the SWRCB and involves much interaction with the applicable RWQCB as CGP regulator. The Contractor shall develop 261
and supply the City with N01 and associated Storm Water Pollution Prevention Plan (SWPPP) for review and records purposes.
CGP coverage requires the development and implementation of a SWPPP. The SWPPP contents are mandated by the SWRCB and are subject to change, and typically contain site map(s) which shows the construction site perimeter, existing and proposed buildings, lots, roadways, storm water collection and discharge points, general topography both before and after construction, and drainage patterns across the project. The SWPPP must illustrate the placement of BMPs for the construction project and list pollution prevention BMPs the discharger will use to protect storm water runoff. Additionally, applicable SWPPPs must contain a visual monitoring program and a chemical monitoring program for "non-visible" pollutants to be implemented. All SWPPPs must be developed by a Qualified SWPPP Developer (QSD) and implemented by a Qualified SWPPP Practitioner (QSP), and supplied to the City for review and comment. Additional CGP information on can be found at the State Water Resources Control Board CGP website:
http://www. waterboards. ca. gov/water_issues/programs/stormwater/constpermits. shtml Construction site storm water management and control measures shall be implemented year-round regardless of "season". All construction site BMPs shall be implemented at the appropriate level for the construction activity at hand and in a proactive manner during all seasons while construction is ongoing.
In addition to inspections performed by the City, the City's Environmental Compliance Division representative may perform periodic site monitoring visits to ensure the contractor complies with the requirements specified herein. The City shall provide copies of the completed site monitoring reports to the Contractor. In the event work is found non-compliant, a follow up site monitoring visit will be conducted to ensure non-compliant items have been corrected to the satisfaction of the City. If non-compliant items are not properly addressed prior to the follow up site monitoring visit, the costs associated with additional follow up site monitoring visits shall be deducted from the Contractor's final payment.
TREE PROTECTION REQUIREMENTS
The following guidelines are established pursuant to Chapter 16.12 of the Sand City Municipal Code, which states:
The City Council of the City of Sand City finds that the trees located within the City limits are a valuable aesthetic resource. Removal of significant trees could reduce scenic beauty and the attractiveness of the area to residents, business owners and visitors.
1. The Tree Protection Guidelines shall apply to all "significant trees" in the City of Sand City, defined as any tree which is equal to or greater than 10 inches DBhl.
2. These standards do not apply to unprotected trees or trees previously approved for removal as shown in the plan set.
3. All cut, fill, and/or building foundations shall be located a minimum of 4.0 times the diameter of the tree away from the outside edge of the trunk of all trees scheduled for preservation. However, the minimum distance permitted shall be 6' - O", away from the outside edge of the trunk for all trees of a trunk diameter less than 2' - O". The diameter of a tree shall be measured at four feet six inches (4' - 6") above the surrounding grade [Diameter at Standard Height (DSH)].
4. All significant trees shall be marked with a spot of paint, or flagging and temporarily fenced during construction. The marking serves to notify City inspectors and workers that the tree is to be fenced at all times during construction. Fencing and marking shall be installed prior to the issuance of building or grading permits and shall be located at the edge of the root zone. The root zone is determined to be that area located out a distance 15 times the trunk diameter in all directions. At no time shall the fencing be located closer than 3' - 0" from the outside edge of the trunk or further 262
than 3' - 0" away from the approved building wall line, foundation, retaining wall, or grade cut, whichever provides the greater distance from the tree trunk. Tree Protection Fencing (TPF) shall consist of six (6) feet tail plastic snow fencing and shall be rigidly supported and maintained during all phases of construction. Fenced areas shall not be used for material stockpile, storage, vehicle parking, or dumping of materials, chemicals, or garbage. Fenced areas shall be maintained in a natural condition and not compacted. Removal of fencing shall only be approved by the City Planner.
5. All approved construction work within the root zone of trees scheduled for preservation shall observe the following minimum tree protection practices:
a. Hand trenching at point or line of grade cuts closest to the trunk to expose major roots 2" in diameter or larger. In cases where rock or unusually dense soil prevents hand trenching, mechanical equipment may be approved by the City Planner, provided that work is closely supervised to prevent tearing or other damage to major roots. b. Exposed major roots shall be cut with a saw to form a smooth surface and avoid tears or jagged edges.
c. Absorbent tarp or heavy cloth fabric shall be placed over new grade cuts where roots are exDOsed and secured by stakes. 2" to 4" of compost or woodchip mulch shall be spread over the tarp to prevent soil moisture loss. The tarp should be thoroughly wetted at least twice per week to ensure constant moisture levels until backfilling occurs. In very dry climate conditions, additional watering may be required to maintain a constant moisture level. This program of watering shall be maintained through all phases of construction including delays and other periods of inactivity.
6. All Tree Protection devices must be in place prior to the start of construction. Please contact the City Planner 831-394-3054 for inspection to confirm Tree Protection or with any general tree preservation questions.
7. Chapter 16. 12, Significant Tree Protection, is available at htt s://ecode360.com/42879785.
CLEANUP
All work sites shall be kept as clear of equipment, material and waste material as is practicable at all times. The City of Sand City and/or government Representative shall make the determination that this requirement is being complied with.
If the City is required to provide cleanup of the work sites due to failure of the Contractor to so provide, or in case of emergency, the City shall charge the Contractor the actual cost of labor and materials and may deduct said costs from any monies due and owing the Contractor.
Upon completion and before making application for acceptance of the work, the Contractor shall clean the street and/or other areas of work, and all ground occupied by the Contractor in connection with the work, of all rubbish, excess materials, temporary structures, and equipment, and all parts of the work shall be left in a neat and presentable condition.
CONTROL OF WORK
CONTRACT COMPONENTS
These specifications, the plans and all supplementary documents are essential parts of the contract, and a requirement occurring in one is as binding as though occurring in all; they are intended to be cooperative, to describe, and to provide for a complete job.
263
Shop drawings required by the plans, specifications or the Engineer shall be furnished by the Contractor and approved by the Engineer before any work relating to the shop drawings is performed unless approval is waived in writing by the Engineer.
It is mutually agreed that shop drawing approval by the Engineer does not relieve the Contractor of any responsibility for accuracy of dimensions and details, and that the Contractor shall be responsible for agreement and conformity of the shop drawings with the approved plans, specifications and site conditions.
Submittal review and approval by the Engineer does not relieve the Contractor from compliance with the requirements and intentions of the plans and specifications.
All authorized alterations affecting the requirements and information given on the approved plans and specifications shall be in writing. No changes shall be made on any plan, specification or drawing after the same has been approved by the Engineer, except by direction of the Engineer.
In the event of discrepancy, written dimensions shall take precedence over scaled dimensions.
ENGINEER'S AUTHORITY
The Engineer shall respond to any and all inquiries as to the quality or acceptability of materials furnished and work performed, and as to the manner of performance and rate of progress of the work; all inquiries as to the interpretation of the plans and specifications; all inquiries as to the acceptable fulfillment of the contract on the part of the Contractor; and all inquiries as to claims and compensation. The Engineer's response shall be final and the Engineer shall have executive authority to enforce and make effective such responses.
Should it appear that the work to be done, or any matter relative thereto, is not sufficiently detailed or explained in the plans and specifications, the Contractor shall submit a written Request for Information (RFI) to the Engineer. Responses to RFI's shall be in writing and deemed part of the contract documents.
Contractor shall comply with response explanation or interpretation so far as may be consistent with the intent of the plans, specifications and amendments thereto.
In the event of doubt or question relative to the true meaning of the plans and specifications, reference shall be made to the City Manager, or their designee, whose decision thereon shall be final.
ASSIGNMENT
The contract may be assigned only upon the written consent of the City Council.
SUBCONTRACTING
Any Proposed substitution of subcontractors must comply with the requirements of the Subletting and Subcontracting Fair Practices Act, California Public Contract Code §4100, et seq.
The Contractor shall give their personal attention to the fulfillment of the contract and shall keep the work under their control.
Subcontractors will not be recognized as such, and all persons engaged in the work of construction will be considered as employees of the Contractor, and their work shall be subject to the provisions of the contract, plans and specifications.
Where a portion of the work sublet by the Contractor is not being prosecuted in a manner satisfactory to 264
the Engineer, the subcontractor shall be removed immediately on the requisition of the Engineer and shall not again be employed on the work.
REPRESENTATIVE
The Contractor shall assign a representative per Section 5-1.16, Representative, of the Standard Specifications and submit contact information (name, telephone number) to the City of Sand City Engineering Department. If the after-hours representative is different than the on-site representative, provide contact information for both.
The Contractor shall be constantly on the work during its progress or shall be represented by a foreman who is competent to receive and carry out instructions which may be given by the proper authorities, and the Contractor shall be held liable for the faithful observance of any lawful instructions of the Engineer not in conflict with the contract, and which may be delivered to the Contractor, contractor's superintendent, foreman, or other representatives on the work. If the Contractor believes the Engineer's instructions are in conflict with the contract, the Contractor shall immediately bring it to the attention of the Engineer in writing.
The Contractor shall provide and maintain an office in the City of Sand City near the site of the work and shall allot such space to the Engineer or their representative as is required for proper keeping of records and plans of work, if re uired b the lans or s ecifications.
EQUIPMENT
While certain sections of these specifications may provide that equipment of a particular size and type is to be used to perform portions of the work, it is to be understood that the development and use of new or improved equipment is to be encouraged.
The Contractor may request, in writing, permission from the Engineer to use equipment of a different size or type in place of the equipment specified.
The Engineer, before considering or granting such request, may require the Contractor to furnish, at Contractor's expense, evidence satisfactory to the Engineer that the equipment proposed for use by the Contractor is capable of producing work equal to, or better than, that which can be produced by the equipment specified.
PROPERTY AND FACILITY PRESERVATION
Attention is directed to Section 5-1. 36, Property and Facility Preservation, Section 7-1. 05, Indemnification and Section 7-1. 06, Insurance, of the Standard Specifications. Due care shall be exercised to avoid injury to existing street improvements or facilities, utility facilities, adjacent property, roadside trees and shrubbery that are not to be removed.
The Contractor shall be held responsible for any damages to existing streets, highways, roads, driveways, sidewalks, curbs, gutters, utilities, other public facilities or private property caused by Contractor's operations. Where the work calls for cutting into or disturbing existing materials, the Contractor shall patch or repair the existing area to a neat, finished product. This shall include touch up or repair of the existing which was disturbed, and repair to the same structural capacity as the existing facility or better.
Full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in protecting or repairing property, shall be considered as included in the prices paid for the various contract items of work, and no additional compensation will be allowed.
CONTRACTOR'S RESPONSIBILITY FOR WORK
All work which is defective in its construction or deficient in any of the requirements of the plans and 265
specifications shall be remedied or removed and replaced by the Contractor in an acceptable manner, and no compensation will be allowed for such correction.
The inspection of the work shall not relieve the Contractor of any of their obligations to fulfill the contract as prescribed. Defective work shall be made good, and unsuitable materials may be rejected, notwithstanding the fact that such defective work and unsuitable materials have been previously overlooked or approved by the Engineer and accepted or estimated for payment.
All work done beyond the lines and grades shown on plans or established by the Engineer, or any extra work done without written authority, will be considered as unauthorized and will not be paid for.
Upon failure on the part of the Contractor to comply forthwith with any order of the Engineer made under the provisions of this article, the Engineer shall have authority to cause defective work to be remedied, or removed and replaced, and unauthorized work to be removed. The cost of removing, replacing, or repairing said defective or unauthorized work may be deducted from any monies due and owing the Contractor but said right of set-off shall be an alternative and not the sole remedy of the City.
Until the formal acceptance of the work by the City (as constituted by the filing of the Notice of Completion), the Contractor shall have the charge and care thereof and shall bear the risk of injury or damage to any part thereof by the action of the elements or from any other cause whether arising from the execution or from the non-execution of the work. The Contractor shall rebuild, repair, restore, and make good all injuries or damages to any portion of the work occasioned by any of the above causes before final acceptance and shall bear the expense thereof, except such injuries or damages occasioned by the acts of the federal government or the public enemy.
Should the City elect to occupy a project before acceptance, the City will issue a Notice of Substantial Completion designating those portions of the work that will be occupied or utilized. Contractor shall be relieved from maintenance and from the responsibility of injury and damage to this work. However, any guarantees will not begin until acceptance of the entire project, and the Contractor shall retain responsibility for making good defective work or materials.
EMPLOYEES
All workmanship shall be fully up to the highest standard of modern construction and practice. The employment of labor shall comply with the prevailing local labor conditions and the Contractor shall employ only competent, careful, orderly persons upon the work. If at any time it shall appear to the Engineer that any person employed upon the work is incompetent, careless, reckless, or disorderly, or disobeys or evades orders and instructions, such person shall be immediately discharged and not again employed upon the work.
CONTROL OF MATERIALS
GENERAL
The Contractor shall furnish without charge such samples of materials and tests of materials as are required by the plans, specifications or the Engineer. No material shall be used until it has been approved by the Engineer.
All tests of materials ordered by the Engineer and made by the Contractor shall be made in accordance with commonly recognized standards of national organizations, and such special methods of tests as are prescribed in the plans and specifications.
All materials not conforming to the requirements of the plans and specifications shall be considered defective, and all such materials, whether in place or not, shall be rejected and shall be removed immediately from the site of the work unless otherwise permitted by the Engineer. No rejected materials, 266
the defects of which have been subsequently corrected, shall be used until approved in writing by the Engineer.
Upon failure on the part of the Contractor to comply with any order of the Engineer made under the provisions of this article, the Engineer shall have authority to remove and replace defective material. The cost of removing, replacing or repairing said defective or unauthorized material may be deducted from any monies due and owing the Contractor but said right of set-off shall be an alternative and not the sole remedy of the City.
For convenience in designation on the plans or in the specifications, certain articles or materials to be incorporated in the work may be designated under a trade name or the name of a manufacturer and their catalog information. The use of an alternative article or material which is of equal quality and of the required characteristics for the purpose intended will be permitted, provided that the burden of proof as to the quality and suitability of alternatives shall be upon the Contractor who shall furnish, at the contractor's expense, all information necessary as required by the Engineer. The Engineer shall be the sole judge as to the quality and suitability of alternative articles or materials and that decision shall be final.
MATERIAL SOURCE
At the option of the Engineer, the source of supply of each of the materials shall be approved by the Engineer before delivery is started and before such material is used in the work. Representative preliminary samples of the character and quality prescribed shall be submitted by the Contractor or producer of all materials to be used in the work, for testing or examination by the Engineer.
QUALITY
Except as otherwise provided, sampling and testing of all materials, and the laboratory methods and testing equipment required under the plans and specifications shall be in accordance with the latest requirements of the State of California, Department of Transportation, Office of Materials Engineering and Testing Services. Sampling and testing of materials not covered by Caltrans specifications and not otherwise provided for, shall be in accordance with the latest Test Methods and Standards of the American Society for Testing and Materials (ASTM).
GUARANTEE
All materials supplied and all work done under this contract shall be guaranteed by the Contractor for a period of one (1) year from the date of formal acceptance by the City of Sand City. Upon receipt of notice from the Engineer of failure of any part of the guaranteed materials during the guarantee period, the affected parts shall be replaced promptly and at the expense of the Contractor.
The Contractor shall maintain the performance bond (See Part IV, Contract Bonds) in full force and effect during the guarantee period for the purpose of insuring that said repairs or replacements will be made, or may, at the Contractor's option, replace said performance bond for a similar bond in the amount of twenty percent (20%) of the total contract amount including adjustments or the original performance bond, whichever is greater.
APPRENTICES
The Contractor and subcontractors shall comply with the provisions in Sections 1777. 5, 1777. 6 and 1777. 7 of the California Labor Code and Title 8, California Code of Regulations Section 200 et seq. To ensure compliance and complete understanding of the law regarding apprentices, and specifically the required ratio thereunder, the Contractor and each subcontractor should, where some question exists, contact the Division of Apprenticeship Standards, 455 Golden Gate Avenue, San Francisco, CA 94102, or one of its branch offices prior to commencement of Work on the contract. Responsibility for compliance with this section lies with the Contractor. It is State and City policy to encourage the employment 267
and training of apprentices on public works contracts as may be permitted under local apprenticeship standards.
WORKING HOURS
Eight hours labor constitutes a legal day's Work. The Contractor or any subcontractor under the Contractor shall forfeit, as a penalty to the State of California, twenty five dollars ($25) or such other amount as may be amended by the Department of Industrial Relations from time to time for each worker employed in the execution of the contract by the respective Contractor or subcontractor for each calendar day during which that worker is required or permitted to Work more than 8 hours in any one calendar day and 40 hours in any one calendar week in violation of the requirements of the Labor Code, and in particular. Section 1810 to Section 1815, thereof, inclusive, except that Work performed by employees of Contractors in excess of 8 hours per day, and 40 hours during any one week, shall be permitted upon compensation for all hours worked in excess of 8 hours per day at not less than one and one-half times the basic rate of pay, as provided in Section 1815 thereof.
OCCUPATIONAL SAFETY AND HEALTH STANDARDS
The Contractor shall conform to all local, state and federal rules and regulations pertaining to safety.
Furnished equipment, material and services shall comply with all OSHA Standards and regulations and all applicable governmental laws and orders. The Contractor shall post an OShlA poster in a conspicuous location as required by law.
EXCAVATION SAFETY
Per California Labor Code Section 6500, Contractor shall possess a valid Construction Activity Permit for construction of trenches or excavations which are five (5) feet or deeper and into which a person is required to descend. When trenches or excavations five (5) feet or deeper are anticipated as part of the contract, Contractor shall possess a valid permit at the time of bidding and for the life of the contract.
Contractor shall furnish copies of valid permits to the City of Sand City Engineering Department. When required in Part I, Notice to Contractors, Contractor must provide evidence of a current T1 Annual Trench/ Excavation Permit at the time of bidding.
Contractor shall comply with California Labor Code Section 6705 which provides that prior to the commencement of excavation of any trench or trenches five (5) feet or more in depth, Contractor shall submit to the Engineer a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If such plan varies from the shoring system standards established by the Construction Safety Orders, the plan shall be prepared by a registered civil or structural engineer.
Plans must be submitted to the Engineer at least five (5) working days prior to the commencement of excavation. If said plans are not submitted five (5) days prior to the commencement of said excavation, the City shall not be liable to Contractor for any delay in work caused by delinquent submission of said plans.
Trenching of more than four (4) feet below the surface shall require the Contractor to promptly notify the Engineer if unknown hazardous wastes, subsurface or latent physical site conditions different from those indicated or unusual site conditions are encountered, and inform the City as to its duty to investigate those conditions. The Contractor may file for a change order for any conditions different from those indicated.
PUBLIC CONVENIENCE AND PUBLIC SAFETY
Attention is directed to Section 7-1. 03, Public Convenience, and Section 7-1. 04, Public Safety, of the Standard Specifications for the provisions relating to the Contractor's responsibility for providing for the 268
convenience and safety of the public in connection with their operations. Standard Specifications are on file in the office of the City Engineer.
Contractor is to notify the Engineer of the start date and construction schedule at least nine (9) calendar days prior to the planned start of construction unless otherwise noted in Part IV.
Unless otherwise provided by the City Engineer, or the Special Provisions the Contractor's construction activities shall be limited to working days as defined by the State Standard Specifications. Daily work time shall be between the hours of 8:30 a. m. and 4:30 p. m. on all City streets, and other public right of way. Should the City Engineer or Special Provisions allow for working hours other than listed above, construction work and related activities shall desist between the hours of 9:00 p. m. and the following 7:00 a. m. and, all Saturdays, Sundays, and legal Holidays. Time limitations are established to minimize traffic interference and nuisance to the adjacent development and to the traveling public. In the event construction activities continue outside of working hours where overtime pay to City of Sand City personnel has been incurred, the Contractor shall reimburse the overtime costs to the City of Sand City.
The Contractor shall conduct their operations as to cause the least possible inconvenience to public traffic.
The Contractor shall provide traffic control devices or personnel where necessary in conformance with traffic safety standards. The Contractor shall provide sufficient warning signs or devices to give adequate notice to the public of dangerous or changed conditions existing during construction.
The City Engineer shall determine the adequacy of said devices and, in cases of dispute, their determination shall be final.
If the City is required to provide traffic direction, personnel, signs or devices, due either to failure of the Contractor to so provide or in case of emergency, the City shall charge Contractor the actual cost of labor and materials and may deduct said costs from any monies due and owing the Contractor.
WORKER'S COMPENSATION
Pursuant to the requirements in Section 1860 of the Labor Code, the Contractor will be required to secure the payment of workers' compensation to the Contractor's employees in conformance with the requirements in Section 3700 of the Labor Code.
PATENTS
If any material, composition, process, method of construction or any other thing called for or required by the plans and specifications or used in the work is covered by letter patent, all royalties and expenses thereof, all litigation thereupon, or anything whatsoever which may develop as a cost from the use of such materials, composition, process, method, or any other thing which is covered by letter patent, shall be borne by the Contractor.
RIGHT OF PROPERTY
Nothing in the contract shall be construed as vesting the Contractor with any right of property in the materials furnished and used in the work herein provided for after they have been attached to the work and have become an integral portion of the work herein provided. All such materials shall, upon their becoming an integral part of the work herein provided, be, and remain, the property of the City of Sand City.
INCREASED FORCE
In case of emergency involving danger to life or property, continuous work with increased force may be required by the Engineer.
LIABILITIES
269
Right of general supervision by the City shall not make the Contractor an agent of the City, and the liability of the Contractor for all damages to persons or to public or private property arising from the Contractor's execution of the work shall not be lessened because of such general supervision.
PROSECUTION AND PROGRESS
GENERAL
If at any time in the opinion of the Engineer, the Contractor has failed to supply an adequate working force, or material of proper quality, or has failed in any other respect to prosecute the work with the diligence and force specified and intended in and by the terms of the contract, notice thereof in writing shall be served upon the Contractor. Should the Contractor neglect or refuse to provide means for a satisfactory compliance with the contract, as directed by the Engineer, within the time specified in such notice, the Engineer in any such case shall have the power to suspend the operation of the contract.
Upon receiving notice of such suspension, the Contractor shall discontinue said work, or such parts of it as the City may designate.
Upon such suspension, the Contractor's control shall terminate, and thereupon the Engineer or duly authorized representative may take possession of all or any part of the Contractor's materials, tools, equipment, and appliances upon the premises, and use the same for the purpose of completing said contract, and hire such force and buy or rent such additional machinery and appliances, tools, and equipment and buy or rent such additional materials and supplies at the Contractor's expense as may be necessary for the proper construction of the work and for the completion thereof; or may employ other parties to carry the contract to completion, employ the necessary workers, substitute other machinery or materials and purchase the materials contracted for in such manner as the City may deem proper; or the City may annul and cancel the contract and re-let the work or any part thereof.
Any excess of cost arising therefrom over and above the contract price will be charged against the Contractor and their sureties, who will be liable therefor. In the event of such suspension, all money due the Contractor or retained under the terms of this contract shall be forfeited to the City, but such forfeiture will not release the Contractor or their sureties from liability for failure to fulfill the contract. The Contractor and their sureties will be credited with the amount of money so forfeited toward any excess of cost over and above the contract price, arising from the suspension of the operations of the contract and the completion of the work by the City as above provided, and the Contractor will be so credited with any surplus remaining after all just claims for such completion have been paid.
In the determination of the question whether there has been any such noncompliance with the contract as to warrant the suspension or annulment thereof, the decision of the City Manager shall be binding on all parties to the contract.
SUSPENSIONS AND DELAYS
Suspensions of work and delays shall be in accordance with Section 8-1.06, Suspensions, and Section 8-
1.07, Delays, of the Standard Specifications.
The Engineer shall have the authority to suspend the work wholly or in part, for such period as the Engineer may deem necessary due to unsuitable weather, or to such other conditions as are considered unfavorable for the suitable prosecution of the work, or for such time as the Engineer may deem necessary due to the failure on the part of the Contractor to carry out Engineer's orders given or to perform any provisions of the work. The Contractor shall immediately obey such order of the Engineer and shall not resume work until ordered in writing by the Engineer.
Any act of, or any omission of anything required to be done by the City, its officers, agents or employees which shall cause the Contractor delay in the completion of the work shall be a ground for extension of 270
time on the part of the Contractor to complete the work but shall not grant the Contractor any monetary damages for such delay.
RIGHTS OF WAY
Rights-of-way or easements for work to be constructed will be provided by the City. The Contractor shall make their own arrangements and pay all expenses for additional area required outside of the limits of rights-of-way or easements unless otherwise especially provided. In the event of delay on the part of the City, its officers, agents or employees in obtaining any such rights-of-way or easements for the work to be constructed, then the Contractor shall have time for the completion of their contract for the period or periods caused by such delay or delays but shall have no damages against the local agency, its officers, agents or employees.
271
EXHIBIT A
CITY OF SAND CITY
ENGINEERING AND PUBLIC WORKS DEPARTMENT
SPECIFICATIONS
FOR
FY 25/26 PAVEMENT MAINTENANCE AND
REHABILITATION (M+R) PROJECT
FORMAL BID
This is a Capital Improvement Project
APPROVED FOR CONSTRUCTION AND TECHNICAL SPECIFICATIONS REVIEWED AND CONFIRMED BY:
Leon Gomez, PE, QSD, Sr. Project Manager, Engineering Services DATE:8/25/2026
Master Specification Revision: 07/08/2026
Project Specification Revision: 09/01/2026
272
FY 25/26 PAVEMENT MAINTENANCE AND REHABILITATION (M+R) PROJECT
TABLE OF CONTENTS
PART I: NOTICE TO CONTRACTORS.........................................................................................................................1 SPECIFICATIONS AND BID FORMS ....................................................................................................................... 1 NON-MANDATORY PRE-BID CONFERENCE ......................................................................................................... 1 PREVAILING WAGES ............................................................................................................................................... 2 CARB CERTIFICATES OF REPORTED COMPLIANCE (NEW REQUIREMENT) ............................................... 2 BID BOND .................................................................................................................................................................. 2 BID VALIDITY ............................................................................................................................................................ 3 RESPONSIBLE BIDDER ........................................................................................................................................... 3 BID REJECTION ........................................................................................................................................................ 4 UNBALANCED BID .................................................................................................................................................... 4 BIDDER PROTEST .................................................................................................................................................... 4 INTERPRETATION OF SPECIFICATIONS .............................................................................................................. 4 DEFINITIONS............................................................................................................................................................. 4 PART II: ......................................................................................................................................................................... 1 BID SCHEDULE ......................................................................................................................................................... 1 BID ITEM DESCRIPTIONS........................................................................................................................................ 4 Base Bid: Bid Item Descriptions and Payment .............................................................................................................. 5 Bid Item 01-Mobilization/Demobilization .................................................................................................................... 5 Bid Item 02-Traffic Control System ............................................................................................................................ 5 Bid Item 03-Water Pollution Control........................................................................................................................... 6 Bid Item 04-Critical Path Method (CPM) Schedule.................................................................................................... 6 Bid Item 05-Remove and Replace Unsuitable Subgrade (Revocable if not used) .................................................... 6 Bid Item 06 Excavation Safety (Temporary Sheeting, Shoring, and Bracing) ........................................................ 6 Bid Item 07- Grind and Offhaul, Disposal of Existing Roadway ................................................................................ 7 Bid Item 08-Demolition, Offhaul, Disposal of Existing Stamped Concrete ................................................................ 7 Bid Item 09-Installation of Stamped Asphalt concrete ............................................................................................... 8 Bid Item 10-Wedge Grind (8 ft wide).......................................................................................................................... 8 Bid Item 11 - Localized Base Repairs (Digouts) - (4 Inch Depth) .............................................................................. 8 Bid Item 12-14 - Hot Mix Asphalt (Type A) ................................................................................................................ 9 Bid Item 15-17-AC Dike ............................................................................................................................................. 9 Bid Item 18 - Demolition and Offhaul of Existing Concrete (C&G, Sidewalk, Curb Ramps, Cross Gutters, Spandrels, ac, ab) .................................................................................................................................................... 10 Bid Item 19 Construct Minor Concrete - Curb and Gutter .................................................................................... 10 Bid Item 20 Construct Minor Concrete-Cross Gutter and Spandrel (8 inch thick) ................................................ 10 Bid Item 21 Construct Minor Concrete-Sidewalk (4 inch thick) ............................................................................ 11 Bid Item 22-Construct Minor Concrete-Curb Ramps (6 inch thick) ......................................................................... 11 Bid Item 23-Construct 6-inch Minimum Vertical Curb .............................................................................................. 11 Bid Item 24 Detectable Warning Surface (DWS) .................................................................................................. 12 Bid Item 25- Parking Wheel Stops ........................................................................................................................... 12 Bid Item 26-Remove and Dispose Existing Storm Drain Catch Basin .................................................................... 12 273
Bid Item 27 & 28-Remove Existing Storm Drain Pipe ............................................................................................. 12 Bid Item 29 & 30-Construct Storm Drain Pipe (HDPE)............................................................................................ 13 Bid Item 31 & 32-Construct Storm Catch Basin....................................................................................................... 13 Bid Item 33-Connect New Storm Drain Pipe to Existing Storm Drain Structure ..................................................... 13 Bid Item 34-Connect New Storm Drain Pipe to Existing Storm Drain Pipe ............................................................. 13 Bid Item 35-Remove Existing 3-inch Sanitary Sewer Service Line ......................................................................... 14 Bid Item 36-Construct New 4-inch Sanitary Sewer Service Line ............................................................................ 14 Bid Item 37-Construct New Sanitary Sewer Cleanout (SSCO) ............................................................................... 14 Bid Item 38-Remove and Relocate Existing Sanitary Sewer Cleanout ................................................................... 15 Bid Item 39-44-Adjust to Grade ............................................................................................................................... 15 Bid Item 45 - 46 - Thermoplastic Pavement Markings ............................................................................................. 15 Bid Items 47 - Thermoplastic Traffic Stripe .............................................................................................................. 16 Bid Item 48 - Blue Reflective Markers at Fire Hydrants ........................................................................................... 16 Bid Items 49 Remove Existing Sign and Post ...................................................................................................... 16 Bid Items 50 Install New Sign and post ................................................................................................................ 16 Bid Item 51-Removal of Existing Trees/Bushes ...................................................................................................... 17 Additive Alternate 1: Bid Item and Descriptions and Payment ................................................................................... 17 Bid Item 1a- Mobilization/Demobilization ................................................................................................................. 17 Bid Item 2a- Traffic Control System ......................................................................................................................... 18 Bid Item 3a- Water Pollution Control Plan ............................................................................................................... 18 Bid Item 4a- Critical Path Method (CPM) Schedule................................................................................................. 18 Bid Item 5a-MicroSlurry (Type II)............................................................................................................................. 19 Bid Item 6a-Crack Seal ............................................................................................................................................ 19 Bid Item 7a-Localized Base Repairs (Digouts) (6 inch depth) .............................................................................. 19 Bid Item 8a-ThermoplaStic Pavement Markings ..................................................................................................... 19 Bid Item 9a-Blue Reflective Markers at Fire Hydrants ............................................................................................. 20 Bid Item 10a-14a- Thermoplastic Traffic Stripe ....................................................................................................... 20 Additive Alternate 2: Bid Item Descriptions and Payment ....................................................................................... 20 Bid Item 1b-Mobilization/Demobilization .................................................................................................................. 20 Bid Item 2b-Traffic Control System .......................................................................................................................... 21 Bid Item 3b-Water Pollution Control Plan ................................................................................................................ 21 Bid Item 4b-Critical Path Method (CPM) Schedule.................................................................................................. 21 Bid Item 5b- Grind, Offhaul, Disposal if Existing Roadway (Depth 6 inch minimum) .............................................. 21 Bid Item 6b-Hot Mix Asphalt (Type A) (6 inch Inlay) ................................................................................................ 22 Bid Item 7b-Remove and Replace Unsuitable Subgrade (Revocable if not used) .................................................. 22 Bid Item 8b-Demolition and Offhaul of Existing Curb Ramps .................................................................................. 23 Bid Item 9b-11b-Construct Accessible Curb Ramp-Case B/Case C/Case CM+..................................................... 23 Bid Item 12b-14b-Adjust to Grade ........................................................................................................................... 24 Bid Item 15b-Thermoplastic Pavement Markings .................................................................................................... 25 Bid Item 16b-Blue Reflective Markers at Fire Hydrants ........................................................................................... 25 Bid Item 17b-21b-Thermoplastic Traffic Stripe ........................................................................................................ 25 ANCILLARY ITEMS ................................................................................................................................................. 26 274
LUMP SUM PRICE BREAKDOWN ......................................................................................................................... 26 EXAMINATION OF SITE ......................................................................................................................................... 26 BID CLARIFICATION ............................................................................................................................................... 26 LOCAL HIRING REQUIREMENT ............................................................................................................................ 27 PART III: GENERAL PROVISIONS .............................................................................................................................. 1 CONTRACT AWARD AND EXECUTION .................................................................................................................. 1 PART IV: SPECIAL PROVISIONS ................................................................................................................................ 9 GENERAL .................................................................................................................................................................. 9 ADMINISTRATIVE WORKFLOW .............................................................................................................................. 9 PLANS AND SPECIFICATIONS ................................................................................................................................ 9 CARB CERTIFICATES OF REPORTED COMPLIANCE (NEW REQUIREMENT) ............................................... 9 CONTRACT BONDS ............................................................................................................................................... 10 TIME LIMITS ............................................................................................................................................................ 10 LICENSES AND PERMITS...................................................................................................................................... 11 SITE INSPECTION .................................................................................................................................................. 11 SUBMITTALS ........................................................................................................................................................... 11 CONSTRUCTION SURVEYS .................................................................................................................................. 12 PROTECTION OF PRIVATE PROPERTY .............................................................................................................. 12 CONSTRUCTION QUALITY CONTROL ................................................................................................................. 12 GUARANTEE ........................................................................................................................................................... 15 REGULATIONS ....................................................................................................................................................... 15 PUBLIC SAFETY AND PROTECTION OF THE WORK ......................................................................................... 15 PRE-CONSTRUCTION CONFERENCE ................................................................................................................. 15 LIQUIDATED DAMAGES......................................................................................................................................... 16 NOTICES ................................................................................................................................................................. 16 CONSTRUCTION PROCEDURE ............................................................................................................................ 16 TRAFFIC CONTROL ............................................................................................................................................... 17 REMOVAL OF OBSTRUCTIONS ............................................................................................................................ 19 UNDERGROUND UTILITIES .................................................................................................................................. 19 UTILITY COMPANY COORDINATION ................................................................................................................... 19 CONTRACT PLANS AND SPECIFICATIONS ........................................................................................................ 19 DUST CONTROL ..................................................................................................................................................... 20 CONNECTION TO EXISTING UTILITIES ............................................................................................................... 20 SANITARY FACILITIES ........................................................................................................................................... 20 INSPECTION OF WORK ......................................................................................................................................... 20 RECORD DRAWINGS ............................................................................................................................................. 20 ENVIRONMENTAL/POLLUTION PREVENTION REQUIREMENTS ...................................................................... 20 TREE PROTECTION REQUIREMENTS ................................................................................................................. 23 CONTROL OF WORK ............................................................................................................................................. 25 CONTROL OF MATERIALS .................................................................................................................................... 27 PROSECUTION AND PROGRESS......................................................................................................................... 30 PART V: TECHNICAL SPECIFICATIONS .................................................................................................................... 1 275
1. MOBILIZATION ..................................................................................................................................................... 1
2. TRAFFIC CONTROL SYSTEM ............................................................................................................................ 1
3. WATER POLLUTION CONTROL ......................................................................................................................... 3
4. CRITICAL PATH METHOD (CPM) SCHEDULE .................................................................................................. 3
5. EXCAVATION SAFETY ........................................................................................................................................ 4
6. CLEARING AND GRUBBING ............................................................................................................................... 4
7. HOT MIX ASPHALT .............................................................................................................................................. 5
8. MIRCROSLURRY TYPE II ................................................................................................................................... 8
9. CRACK SEAL ....................................................................................................................................................... 8
10. CLASS 2 AGGREGATE BASE MATERIAL ..................................................................................................... 9
11. WEDGE GRIND AND CONFORM GRIND .................................................................................................... 10
12. LOCALIZED BASE FAILURE REPAIRS (DIGOUTS) .................................................................................... 10
13. TACK COAT ................................................................................................................................................... 12
14. GRIND AND OFFHAUL EXISTING ROADWAY ............................................................................................ 12
15. MINOR CONCRETE....................................................................................................................................... 14
16. REMOVE CONCRETE ................................................................................................................................... 17
17. ADJUST UTILITY COVER/MANHOLES TO GRADE .................................................................................... 18
18. CONSTRUCT STORM DRAIN MANHOLE AND CATCH BASIN .................................................................. 19
19. CONSTRUCT STORM DRAIN PIPES ........................................................................................................... 19
20. REMOVE EXISTING STORM DRAIN PIPES, MANHOLES, AND CATCH BASINS .................................... 21
21. SANITARY SEWER PIPE IMPROVEMENTS ................................................................................................ 21
22. TRAFFIC SIGNS, PAVEMENT MARKINGS, AND PAVEMENT MARKERS ................................................ 22
23. ONE WAY STREET CONVERSION .............................................................................................................. 26
24. INSTALLATION OF STAMEPD ASPHALT CONCRETE AND MOCKUP ..................................................... 28 276
Part I, Page 1
CITY OF SAND CITY
ENGINEERING AND PUBLIC WORKS DEPARTMENT
SAND CITY, CALIFORNIA
PART I: NOTICE TO CONTRACTORS
Sealed, unbound bid proposals for furnishing all labor, materials, tools, equipment and incidentals for the construction of the FY 25/26 Pavement Maintenance and Rehabilitation (M+R) Project in Sand City, California, in accordance with these plans and specifications, will be received electronically -Procurement Portal, PlanetBids, until 2:00 pm, Monday, September 28, 2026 electronically opened, read, and publicly avail -Procurement Portal.
In general, the work consists of, but is not limited to: the maintenance and rehabilitation of street pavement and associated infrastructure, including the demolition and/or removal of concrete curbs, gutters and sidewalks, concrete planters, concrete crosswalks, curb ramps, cross gutters and spandrels, removal of trees and landscaping, and the construction of new concrete curbs, gutters, and sidewalks, asphalt concrete dikes, asphalt pavement rehabilitation including aggregate base, stamped asphalt concrete crosswalks, storm drain catch basins, manholes, and pipes, minor sanitary sewer improvements, utility cover adjustments, utility cover relocations, signing and striping.
The Project is presented as follows:
Base Bid
- Holly Street from Ortiz Avenue to California Avenue
- Contra Costa Street from Redwood Avenue to north of Bay Avenue - City Hall Parking Lot
Additive Alternate 1
-
driveway entrance
Additive Alternate 2
- Playa Avenue from California Avenue to Metz Road
At the time of the bid opening, the successful Bidder must be legally entitled to perform contracts requiring a Class Contractor's license. Any Bidder or contractor not so licensed shall be subject to all penalties imposed by law including, but not limited to, any appropriate disciplinary action by the Contractors' State License Board. All contractor and sub-contractor license(s) must remain in good standing throughout the term of the Contract. The Contractor shall notify the City in writing in the event its license is suspended, expires, or has a change in signatory.
SPECIFICATIONS AND BID FORMS
Specifications, including instructions to Bidders and all necessary contract documents and forms, are available online -Procurement Portal, PlanetBids, at https://sandcity.org/rfps-rfqs/. In order to download project documents, you must register as a vendor, at no cost, through PlanetBids. Potential bidders, subcontractors and suppliers are responsible for reviewing the complete bidding documents, including all addenda, prior to submitting their bid via PlanetBids. They are also advised to check PlanetBids periodically and prior to submitting their bid.
Prior to the Bid Opening Date, bids may be withdrawn through PlanetBids by means of the responding firm PlanetBids. After withdrawing a previously submitted proposal, the responding firm may submit another proposal at any time up to the deadline for submitting proposals.
NON-MANDATORY PRE-BID CONFERENCE
A non-mandatory pre-bid conference is scheduled for 11:00 AM on Thursday, September 4, 2026, at City Hall, 1 Pendergrass Way, Sand City, CA, 93955. The meeting will be hybrid, and the Zoom meeting information is:
City Clerk is inviting you to a scheduled Zoom meeting.
Topic: Pre-Bid Meeting - Streets M+R
Time: Sep 4, 2026 11:00 AM Pacific Time (US and Canada) Join Zoom Meeting: https://us02web.zoom.us/j/81744185875?pwd=lTJy4fScAlP6F8IEHikyYUrCybETR0.1 277
Part I, Page 2
Meeting ID: 817 4418 5875
Passcode: 502700
The City will also post the Pre-Bid Conference information to PlanetBids.
PREVAILING WAGES
Local prevailing wage rates shall be paid in accordance with Sections 1770, 1773, and 1782, as amended, of the California Labor Code, and Section 12.18.060 of the Sand City Municipal Code, on all public works construction contracts exceeding twenty-five thousand dollars ($25,000) and all public works contracts for alteration, demolition, repair or maintenance work exceeding fifteen thousand dollars ($15,000). Local wage rates may be obtained from the City of Sand City, 1 Pendergrass Way, Sand City, CA, (831-394-3054) or the Director, Department of Industrial Relations, State of California, 455 Golden Gate Avenue, San Francisco, California (415-703-4774). Any Bidder or contractor awarded a public works contract that uses a craft or classification not in the general prevailing wage determinations may be required to pay the wage rate most closely related in the general determinations, effective at the time of the call for bids.
In accordance with the provisions of Sections 1725.5, 1771.1, 1771.3, and 1771.4 of the Labor Code, this project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal (subject to the requirements of Section 4104 of the Public Contract Code), or engage in the performance of any contract for public work, as defined by that chapter of the Labor Code, unless currently registered and qualified to perform public work pursuant to Section 1725.5 of the Labor Code. See Part III of these Specifications for additional requirements.
In accordance with the provisions of Section 1773.3 of the Labor Code, the City of Sand City shall provide notice to the Department of Industrial Relations (DIR) of the award of any public works contract subject to the requirements of Chapter 1 of the Labor Code, within thirty days of the award, and in accordance with all applicable Department of Industrial Relations requirements. The notice shall be transmitted electronically in a format specified by the DIR (see https://www.dir.ca.gov/pwc100ext/) and shall include the name of the contractor, any subcontractor listed on the successful bid, the bid and contract award dates, the contract amount, the estimated start and completion dates, job site location, and any additional information the DIR specifies that aids in the administration and enforcement of this chapter.
CARB CERTIFICATES OF REPORTED COMPLIANCE (NEW REQUIREMENT) -Use Off-Road Diesel-Fueled Fleet
public works
projects involving the use of vehicles subject to the regulation that are awarded after January 1, 2024. While compliance with CARB regulations has been a long-standing requirement for all Contractors who own off-road diesel fleet vehicles (e.g. construction equipment) in California, the amended Regulations now place monitoring obligations on California public agencies. Because of this new obligation, the apparent low bidder shall submit valid Certificates of Reported Compliance ("CRC") for the bidder and all listed subcontractors, or a detailed explanation of any exemption from the Regulations, to the City within fourteen (14) calendar days after the Bid Opening Date. Failure to timely submit the required CRCs, or a detailed explanation of any exemption, may render the bidder non-responsible and disqualify the bidder from award. Further information regarding this requirement is set forth in Part IV of these Specifications.
BID BOND
An original certified check or cashier's check payable to the order of the City of Sand City, or a satisfactory bid bond executed by the Bidder and an acceptable surety in an amount equal to ten percent (10%) of the bid amount shall be uploaded with each bid, as a guarantee that the bidder, if its bid is accepted, will promptly execute the Agreement.
The bid bond must be notarized, include the embossed surety seal, and include a Power of Attorney if the signee is not an officer of the surety.
must be received by the City no later than three (3)
business days after the Bid Opening Date by 1 p.m. In order to check, or bid bond is received by the deadline, the City recommends bidders use express mail or personal delivery.
The original shall be addressed to:
278
Part I, Page 3
City of Sand City
Attention Finance Manager
1 Pendergrass Way
Sand City, CA 93955
Please have the Bidder Name, Contract Title ("Project Title"), and Contract Number ("Project ID") listed clearly on the outside of the envelope.
result in the bid being deemed non-responsive.
Further, the amount so posted shall be forfeited to the City if the Bidder does not, within fifteen (15) calendar days after written notice that the contract has been awarded to said Bidder, enter into contract with the City for the work.
BID VALIDITY
No Bidder may withdraw their bid for a period of ninety (90) days from the Bid Opening Date, which time shall be used by the City for reviewing the bids and investigating the qualifications of Bidders, prior to awarding of the contract.
In the
event of a bid mistake resulting from a clerical error made by the Bidder, withdrawal of such bid without forfeiture of the Bid Bond may only be allowed if the criteria set forth in California Public Contracts Code Sec. 5103 are met and the procedures set forth therein are followed; any such approval by City of bidders request to withdraw bid shall be at the sole discretion of the City.
RESPONSIBLE BIDDER
Responsible bidder as it pertains to this contract shall be as follows:
1. Standards of Responsibility: The City may reject bids on the basis of non-responsibility. A responsible bidder is one that has the capacity in all respects to perform fully the contract requirements, and the integrity and reliability which will assure good faith performance of the contract. Factors to be considered in determining whether the standard of responsibility has been met include whether a bidder has:
a. The appropriate financial, material, equipment, facility, capacity (adequate workforce to complete the job in a timely fashion) and personnel resources, including all required certifications, licenses, and expertise necessary to indicate its capacity to meet all contractual requirements, including the following specific requirements:
i. Adequate workforce to meet multiple critical work schedules at once; ii. Ability to start projects on the commencement dates set forth by the City and satisfactorily complete ;
b. A satisfactory record of performance, including but not limited to any prior work performed by bidder for the City or other agency;
c. Evidence of ability to provide the required bonding and insurance capacity. Apparent low bidder -qualification letter from an acceptable
of the bid opening;
d. A satisfactory record of integrity, diligence, and professionalism in the specific contract work; e. The legal qualifications to contract with the City; and f. Supplied all information requested by the City in connection with the inquiry concerning responsibility.
2. Information Pertaining to Responsibility. The prospective contractor shall supply any information requested by the City concerning the responsibility of such contractor, including the qualifications and performance If the prospective contractor fails to supply
the requested information, the City shall base the determination of responsibility in award of the Contract 279
Part I, Page 4
upon any available information, or may find the prospective contractor non-responsible on the basis of its failure to provide the requested information to the City.
3. . Before awarding a contract, the City must be satisfied that the prospective contractor is responsible. The City may use the information provided by prospective contractor prospective contractor and employees.
4. Written Determination of Non-Responsibility Requirements. If a bidder or offeror who otherwise would have been awarded the Contract is found non-responsible, a written determination of non-responsibility setting forth the basis determination shall be prepared by the City and sent to the non-responsible bidder or offeror.
The bidder or offeror shall have an -responsibility.
BID REJECTION
The City reserves the right to reject any or all bids as the best interests of the City may dictate and, to the extent permitted by law, waive any irregularity in any bid. If there is any reason for believing that collusion exists among the bidders, the City may reject any or all bids.
UNBALANCED BID
Bids which are obviously unbalanced may be rejected. For the purposes of this section, an unbalanced bid is one that (a) has unit prices based on nominal prices for some items of work and enhanced unit prices for other items of work, and (b) the amount and manner in which the unit prices are distributed is not reflective of the true cost to perform the work. Any unbalanced bid may be rejected by the City whether or not the result of the unbalanced bid increases the cost of the project to the City.
BIDDER PROTEST
All bid protests shall follow the procedures set forth in Sand City Municipal Code §12.18.100 Purchasing Procedures, both of which are available on- https://sandcity.org/citylaws/. Payment of a bid protest filing fee in the amount set forth in the City Code and Purchasing Procedures shall be prerequisite to the filing of any such protest.
INTERPRETATION OF SPECIFICATIONS
Should a Bidder be in doubt as to the true meaning of any item in the Plans or Specifications or discover items containing discrepancies or omissions, the Bidder is responsible for immediately notifying the Engineer. All questions must be submitted in writing through the PlanetBids Procurement Question/Answer Tab, on or before the Question & Answer Submission Date and Time. Please include the section title of this Specification for each question, if applicable, in order to ensure that questions asked are responded to correctly. All questions submitted and answers provided shall be electronically distributed to all bidders follow this Specification on the City's e-Procurement Portal, PlanetBids.
Any addenda shall be posted on the City's e-Procurement Portal, PlanetBids. Addenda notifications will be emailed to all persons who have selected to follow this Specification. Failure of any Bidder to receive any such addenda or interpretation shall not relieve such Bidder from any obligation under their bid as submitted. All addenda so issued shall become part of the contract documents. Such addenda are to be considered as part of the contract documents, and the Bidder shall acknowledge this condition in the e-Procurement Portal, PlanetBids. The Engineer shall not be held responsible for any oral interpretations or instructions. No addenda can be issued less than forty-eight (48) hours before bid opening without an accompanying bid time extension. The Engineer reserves the right to make decisions on extending the bid period.
DEFINITIONS
For the purposes of this document, the following definitions shall apply:
CITY: The term City refers to and indicates the City of Sand City, Monterey County, State of California.
280
Part I, Page 5
ENGINEER OR The term Engineer or City Engineer refers to and indicates the City Engineer CITY ENGINEER of the City of Sand City or their duly authorized representative.
BIDDER: Party submitting a bid for consideration by the City of Sand City.
CONTRACTOR: The term Contractor refers to and indicates the party or parties contracting to perform the work to be done in pursuance of this contract and specifications.
COUNCIL OR The City Council of the City of Sand City.
CITY COUNCIL:
PLANS: The project plans referred to herein.
SPECIAL Part IV of these Specifications.
PROVISIONS:
SPECIFICATIONS: This document, in its entirety.
STANDARD
SPECIFICATIONS: of latest publication on file in the office of the City Engineer of the City of Sand City.
STANDARD
PLANS:
ADA: Americans with Disabilities Act of 1990, Titles II and III, revised September 15, 2013.
CBC: California Building Standards Codes, latest edition as adopted by the City of Sand City.
IBC: International Building Codes, latest edition.
281
Part II, Page 1
FY 25/26 PAVEMENT MAINTENANCE AND REHABILITATION (M+R) PROJECT
CITY OF SAND CITY
PART II:
BID SCHEDULE
BASE BID SCHEDULE HOLLY STREET, CONTRA COSTA STREET, CITY HALL 282
Part II, Page 2
283
Part II, Page 3
ADDITIVE ALTERNATE #1: CALIFORNIA AVENUE
Item
No.
Item Description Unit Estimated
Quantity
Unit Cost Total
Cost
1A Mobilization/Demobilization LS 1
2A Traffic Control System LS 1
3A Water Pollution Control Plan LS 1
4A CPM Schedule LS 1
5A Micro slurry Seal (Type II) SY 3,026
6A Crack Seal LF 1,000
7A Localized Base Repairs (Digouts) - (6 inch depth) -
Assume 15% of Roadway
TON 153
8A Thermoplastic Pavement Marking (White) SF 1,208
9A Blue Reflective Markers at Fire Hydrants EA 0
10A Thermoplastic Traffic Stripe - Detail 22 LF 315
11A Thermoplastic Traffic Stripe - Detail 29 LF 188
12A Thermoplastic Traffic Stripe - Detail 38 LF 506
284
Part II, Page 4
13A Thermoplastic Traffic Stripe - Detail 39 LF 813
14A Thermoplastic Traffic Stripe - Detail 39A LF 100
TOTAL
ADDITIVE ALTERNATE #2: PLAYA AVENUE
(From California Avenue to Metz Road)
Item
No.
Item Description Unit Estimated
Quantity
Unit Cost Total
Cost
1B Mobilization/Demobilization LS 1
2B Traffic Control System LS 1
3B Water Pollution Control Plan LS 1
4B CPM Schedule LS 1
5B Grind, Off haul, Disposal of Existing Roadway Depth of 6 inches
SY 3,988
6B Hot Mix Asphalt (Type A) for 6 inch Inlay TON 1,346
7B Remove and Replace Unsuitable Subgrade
(Revocable if not used)
CY 10
8B Demolition and Off haul of Existing Curb Ramps EA 9
9B Construct Accessible Curb Ramp per Caltrans A88A -
Case B
EA 1
10B Construct Accessible Curb Ramp per Caltrans A88A -
Case C
EA 7
11B Construct Accessible Curb Ramp per Caltrans A88A -
Case CM
EA 1
12B Adjust Storm Drain Manhole Cover to Grade (SDMH) EA 22 13B Adjust Sanitary Sewer Manhole Cover to Grade
(SSMH)
EA 0
14B Adjust Water Valve/Meter Cover to Grade (WV/WM) EA 3 15B Thermoplastic Pavement Marking (White) SF 1989
16B Blue Reflective Markers at Fire Hydrants EA 4
17B Thermoplastic Traffic Stripe - Detail 22 LF 228
18B Thermoplastic Traffic Stripe - Detail 32 LF 482
19B Thermoplastic Traffic Stripe - Detail 38 LF 117
20B Thermoplastic Traffic Stripe - Detail 39 LF 760
21B Thermoplastic Traffic Stripe - Detail 39A LF 435
TOTAL
BASIS OF AWARD
Award of contract, if any be made, shall be made to the Contractor with the lowest responsive responsible bid based on the Total Base Bid listed above (items 1 through 51).iThe City reserves the right to award, in addition to the base bid, any, all or none of the additive alternate bid schedules.
BID ITEM DESCRIPTIONS
This section covers details of individual items listed in the Bid Schedule to ensure that it is clear as to what is to be included in each item. The costs submitted with each item are to reflect the work to be completed under that bid item only. Payment of all bid items shall be for actual materials installed on the job and for actual work accomplished. 285
Part II, Page 5
Base Bid: Bid Item Descriptions and Payment
Bid Item 01-Mobilization/Demobilization
DESCRIPTION OF WORK:
Mobilization shall conform to the provision of Section 10.2 of the General Provisions.
MEASUREMENT AND PAYMENT:
The contract lump sum price paid for shall be considered full compensation for mobilization as specified herein, including but not limited to notifications, project records and documents, obtaining all required permits, licenses, and paying all fees, moving on the site any equipment required for the operations, preparatory work, coordination and cooperation, inquiring information about other anticipated projects in the project areas and coordination to minimize delays, project meetings, developing construction water supply, providing on-site sanitary facilities, developing a temporary construction staging area, subcontractor insurance and bonds, Contractor insurance and bonds, demobilization and all other mobilization work, and no additional payment shall be allowed therefor.
The department shall make partial payments for the mobilization costs of the contract, not to exceed the following:
1. When 5 percent of the original contract amount is earned, 50 percent of the amount bid for mobilization, or 5 percent of the original contract amount, whichever is lesser, may be paid.
2. When 10 percent of the original contract amount is earned, 75 percent of the amount bid for mobilization or 7.5 percent of the original contract amount, whichever is lesser, may be paid.
3. When 20 percent of the original contract amount is earned, 95 percent of the amount bid for mobilization, or 9.5 percent of the original contract amount, whichever is lesser, may be paid.
4. When 50 percent of the original contract amount is earned, 100 percent of the amount bid for mobilization, or 10 percent of the original contract amount, whichever is lesser, may be paid.
5. Upon completion of all work on the project, payment of any amount bid for mobilization in excess of 10 percent of the original contract amount will be paid.
Bid Item 02-Traffic Control System
MEASUREMENT AND PAYMENT:
The contract lump sum price paid for shall include full compensation for furnishing all labor, materials (including signs), tools, equipment, incidentals, furnishing all flaggmen, and for doing all the work as described below, as directed by the Engineer, and as specified in the Standard Specifications and these special provisions. No additional compensation will be allowed:
The installation of the traffic and pedestrian control complete in place as specified in the General Provisions, these Special Provisions, and as directed by the Engineer.
Furnishing, placing, maintaining, and removing the temporary reflective raised pavement markers, used for temporary lane line and centerline delineation, for those areas where temporary lane line and centerline delineation are required, and for providing equivalent patterns of permanent traffic lines for such areas when required.
Placing, removing, storing, maintaining, moving to new locations, replacing, and disposing of the components of the traffic control system.
Furnishing and installing funding signs as shown on the plans and as directed by the City and Engineer.
Furnishing of Traffic Control Flaggers for the project.
Traffic control plans, including revisions to the satisfaction of the Engineer. 286
Part II, Page 6
The contractor shall comply with the permit required by Caltrans for all work to be performed by the Contractor in Caltrans right of way. The Contractor is responsible for determining the need for and obtaining the requisite permits.
Bid Item 03-Water Pollution Control
MEASUREMENT AND PAYMENT:
The contract lump sum price paid for shall include full compensation for preparing a water pollution prevention plan, developing and implementing the plan, providing a WPC manager, conducting WPC training, and monitoring, inspection, reporting, and correcting WPC practices the lump sum. Payment will be made according to Section 13-2.04 of the Standard Specifications, with 75% of the item total paid upon authorization of the WPCP and the final 25% of the item paid upon project acceptance.
Bid Item 04-Critical Path Method (CPM) Schedule
MEASUREMENT AND PAYMENT:
Preparing, maintaining, and implementing of the is paid for as a lump sum. The CMP schedule shall be kept up to date and coordinated with the City and the Engineer. A 3-week look ahead shall be provided at every weekly meeting to discuss the specific upcoming activities and any changes that may occur. The CPM schedule shall be updated immediately upon request from the City and/or Engineer.
Bid Item 05-Remove and Replace Unsuitable Subgrade (Revocable if not used) DESCRIPTION OF WORK:
Should the base material found at the required elevations prove to be soft, spongy, or otherwise unsuitable, the Contractor shall obtain a written order from the City Engineer for such additional excavation as may be necessary to obtain a foundation suitable for the asphaltic concrete or concrete to be supported. This additional excavation shall be replaced by the Contractor with select material as directed by the City Engineer.
All work shall be done under the direction of the Engineer. Material that has been deemed unsuitable for reasons including, but not limited to, excessive moisture, shall be removed to a depth as directed by the engineer. All material removed shall become the property of the Contractor and should be disposed of outside of City right-of-way.
Material that is not adequately compacted shall be compacted in place, and is included in other items of work.
Subgrade shall be finished graded and compacted in a manner and to a density that is acceptable to the Engineer. A geo-textile shall be placed for subgrade stabilization prior to placing fill material. Subgrade stabilization fabric shall be MIRAFI HP370 or approved equal.
Asphaltic pavement grindings or aggregate base removed and stockpiled may be used to replace unsuitable material that was removed. The engineer shall approve any material prior to placement. The stockpiled material shall only be placed to the bottom of the existing aggregate subbase. 1- in the zone of the existing aggregate base and subbase. Placement and compaction shall conform to the requirements of Section 26 of the Caltrans Standard Specification.
MEASUREMENT AND PAYMENT:
The contract price paid per cubic yard for includes full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all work involved in removing unsuitable material to required depth, disposing of material, as directed by the Engineer, providing and placing subgrade stabilization fabric, providing and placing stockpiled material (or equal), providing and placing 1- Remove and Replace Unsuitable Material shall be measured by the cubic yard. The depth shall be measured from the elevation that the new Asphaltic Concrete is placed or the aggregate underlaying concrete.
No adjustment in the contract unit price for Remove and Replace Unsuitable Material shall be made for increases or decreased of more than 25 percent of the quantities set forth in the Schedule of Bid Prices, and portions of Section 4.3.2 of the General Provisions shall not apply.
If the Engineer determines that there is no unsuitable material, this item of work shall be revoked.
Bid Item 06 Excavation Safety (Temporary Sheeting, Shoring, and Bracing) 287
Part II, Page 7
DESCRIPTION OF WORK:
shall consist of furnishing all labor, materials,
equipment, engineering, installation, maintenance, monitoring, adjustment, relocation, and removal of temporary sheeting, shoring, bracing, trench boxes, shielding systems, soldier piles, lagging, hydraulic shoring, and all other temporary excavation support systems necessary to safely perform excavation operations.
The work shall include providing excavation support systems necessary to protect workers, adjacent facilities, utilities, roadways, sidewalks, structures, and the public from movement, settlement, or collapse resulting from excavation activities. Temporary support systems shall comply with the requirements of the 2025 Caltrans Standard Specifications, applicable Cal/OSHA Excavation Safety Orders, and all other governing federal, state, and local regulations.
The Contractor shall be solely responsible for the design, installation, maintenance, monitoring, modification, and removal of all temporary excavation support systems. Where required by law, excavation support systems shall be designed, reviewed, and stamped by a Professional Engineer registered in the State of California.
The Contractor shall continuously inspect and maintain all temporary excavation support systems throughout construction and shall immediately repair, replace, or modify any system that becomes inadequate or unsafe. Upon completion of the work, all temporary sheeting, shoring, and bracing shall be removed unless otherwise directed by the Engineer or shown on the Plans.
MEASUREMENT AND PAYMENT:
will be measured and paid for on a Lump
Sum (LS) basis.
The lump sum price paid shall constitute full compensation for furnishing all labor, materials, equipment, engineering, design, calculations, permits, excavation support systems, installation, maintenance, monitoring, relocation, adjustment, removal, disposal, and all incidentals necessary to complete the work, including compliance with applicable safety regulations and the requirements of the Contract Documents.
No additional compensation will be made for excavation support required due to the Contractor's means and methods, sequence of construction, equipment selection, trench width, or compliance with safety regulations. Any costs associated with temporary sheeting, shoring, and bracing not specifically identified as a separate bid item shall be considered included in the Contract lump sum price for this item.
Bid Item 07- Grind and Offhaul, Disposal of Existing Roadway MEASUREMENT AND PAYMENT:
The Contract unit price per square yard for shall include full compensation for furnishing all labor, materials, tools, equipment, transportation, and incidentals, and for doing all the work including excavation, grinding, removal, and disposal of materials such as pavement fabric and road mesh, grading and compaction, complete in place as specified in these Special Provisions, as shown on the Plans and as directed by the Engineer and no additional compensation will be allowed therefor.
This item is revocable if not used and Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply to this bid item.
Bid Item 08-Demolition, Offhaul, Disposal of Existing Stamped Concrete DESCRIPTION OF WORK:
This work shall consist of demolition of existing stamped concrete crosswalk at the four way intersection of Holly Street and Redwood Avenue. The stamped concrete depths are unknown.
MEASUREMENT AND PAYMENT:
The Contract unit price per square foot for
shall include full compensation for furnishing all labor, materials, tools, equipment, transportation, and incidentals, and for doing all the work including excavation, demolition, removal, and disposal of existing stamped concrete as identified in these Special Provisions, as shown on the Plans and as directed by the Engineer and no additional compensation will be allowed therefor.
288
Part II, Page 8
Bid Item 09-Installation of Stamped Asphalt concrete
DESCRIPTION OF WORK:
This work shall include installation of Stamped Asphalt Concrete at the following intersections:
Holly Street at Dias Avenue (4 crossings)
Holly Street at Redwood Avenue (4 crossings)
Holly Street at California Avenue (1 crossing)
Contra Costa Street at Redwood Avenue (1 crossing)
Contractor must refer to project plans for exact locations and limits of stamped asphalt.
Stamped Asphalt Concrete shall be performed by Contractor shown below. All other stamped asphalt contractors must be approved by the City prior to start of construction.
Contractor Name: Asphalt Impressions Incorporated.
Address: 8150 37th Avenue, Sacramento, CA 95824
Phone: 916-383-0441
Website: www. Acstamp.com
Stamped Asphalt shall be color or Approved Equal and pattern shall be in Streetbond materials and application requirements.
Contractor shall provide a full-size mockup of the proposed stamped asphalt crosswalk, including the specified color and pattern, for review prior to installation. No stamped asphalt crosswalks shall be installed until the mockup has been reviewed and approved by both the Engineer and the City. The City reserves the right to modify the color, pattern, or both based on the approved mockup. Any required revisions shall be incorporated into the final installation at no additional cost to the City.
It is assumed that Traffic Control will be provided by the prime contractor for the project. Asphalt Impressions Incorporated or Approved equal contractor, to coordinate traffic control efforts with prime contractor for the application of the stamped asphalt concrete.
MEASUREMENT AND PAYMENT:
The Contract unit price per square foot for shall include full compensation for furnishing all labor, materials, tools, equipment, transportation, and incidentals, and for doing all the work associated with mockup and final application of stamped asphalt concrete including reheating of asphalt surface, stamping pattern, and applying (4) coats of StreetBond SB 150 mixed with chosen color, and as specified in these Special Provisions, as shown on the Plans and as directed by the Engineer and no additional compensation will be allowed therefor. The contract unit price does not include traffic control. It is assumed that traffic control will be provided by the prime contractor of the project.
All construction surveying and staking will be performed by the City.
Bid Item 10-Wedge Grind (8 ft wide)
DESCRIPTION OF WORK:
Wedge Grind shall be performed along Contra Costa Street where a 2-inch HMA Overlay is required as shown on the project plans. Refer to project plans for exact paving limits. Bid Item 10 does not account for placement of new asphalt. Wedge Grind only includes tapered grind and off haul of existing roadway to accommodate a new uniform placement of a 2-inch overlay.
MEASUREMENT AND PAYMENT:
is measured and paid per square yard and shall include furnishing all labor, equipment, transportation, and materials necessary to perform the work complete in place in conformance with these special provisions, project plans, and as directed by the engineer. Refer to project plans for allowable wedge grind lengths and maximum allowable slopes.
Full compensation for furnishing asphalt concrete for temporary tapers and for constructing, maintaining, removing and disposing of the tapers shall be considered as included in the contract price paid per square yard for grinding pavement and no additional compensation will be allowed therefor.
Bid Item 11 - Localized Base Repairs (Digouts) - (4 Inch Depth) DESCRIPTION OF WORK:
shall consist of grinding the roadway to the specified depth, removing and disposing of the existing depth of pavement and any underlying unsuitable material as determined by the Engineer, compacting the exposed surface and replacing it with the specified thickness of asphalt concrete in accordance 289
Part II, Page 9
with the detail in these special provisions.
Localized Base Failure Repair (Digouts) for base bid shall be performed as follows:
Contra Costa Street shall have localized base repairs (digouts) at a maximum depth of 4 inches. Localized Base Repair areas to be marked out in the field by the engineer prior to start of construction.
MEASUREMENT AND PAYMENT:
The contract unit price paid per TON for shall include full compensation for furnishing all labor, material (including Hot Mix Asphalt and tack coat), tools, equipment, sweeping, and off haul of complete in place as shown in the detail in these special provisions, as specified herein, and as directed by the Engineer, and no additional compensation will be allowed therefor.
No payment shall be made for materials placed outside of the limits marked by the Engineer. increased or decreased based on field conditions evaluation by the Engineer, and no adjustment in the contract bid price or other contract items
Schedule of Bid Prices, and portions of Section 4.3.2 of the General Provisions shall not apply.
Bid Item 12-14 - Hot Mix Asphalt (Type A)
DESCRIPTION OF WORK:
This work includes producing and placing hot mix asphalt (HMA) Type A for the following street segments and pavement improvement types:
Base Bid:
Holly Street between Ortiz Avenue and California Avenue O Full Depth HMA (7-inches in Depth)
Holly Street between Redwood Avenue and California Avenue O -
project plans.
Contra Costa Street between Redwood Avenue and West End Near Bay Street O HMA Overlay (2-inches in Depth), Wedge Grind, and Localized Base Repairs City Hall Parking Lot
O Full Depth HMA (3-inches in Depth)
The contractor shall place hot mix asphalt (HMA) Type A along street segments identified in the plans. Engineer to mark out exact pavement improvement limits in the field prior to the start of construction. -
not be used except for temporary paving operations.
Contractor must comply with Section 39, "Hot Mix Asphalt," of the Standard Specifications except as modified herein.
MEASUREMENT AND PAYMENT:
Payment for shall be at the contract price per TON and shall be considered full compensation for all labor, materials, tools, equipment, transportation, and incidentals to do all the work involved. The contractor shall supply weight tags to the Engineer on a daily basis. Quantities of asphalt concrete will be determined and approved by the Engineer by using the tags. Asphalt concrete weight tags shall contain the project name and indicate tonnage used on each street.
Payment for Tack Coat shall be considered as included in the contract prices bid for various items of work shown on the bid schedule and no additional compensation shall be allowed therefor.
Bid Item 15-17-AC Dike
DESCRIPTION OF WORK:
This work includes producing and placing hot mix asphalt (HMA) Type A for the installation of AC Dikes at the following locations:
Holly Street between Redwood Avenue and California Avenue:
O
Contra Costa Street north of Bay Street
290
Part II, Page 10
O
Prior to the start of construction, the Engineer shall field mark the exact locations of AC Dike installations. The contractor shall coordinate with the engineer before performing this work.
Contractor must comply with Section 39, "Hot Mix Asphalt," of the Standard Specifications except as modified herein.
MEASUREMENT AND PAYMENT:
Payment for shall be at the contract price per LF and shall be considered full compensation for all labor, materials, tools, equipment, transportation, and incidentals to do all the work involved.
Payment for Tack Coat shall be considered as included in the contract prices bid for various items of work shown on the bid schedule and no additional compensation shall be allowed therefor.
All construction surveying and staking will be performed by the City.
Bid Item 18 - Demolition and Offhaul of Existing Concrete (C&G, Sidewalk, Curb Ramps, Cross Gutters, Spandrels, ac, ab)
The contract price paid per square foot for
Curb Ramps, Cross Gutter, Spandrels, AC, AB) is Final Pay and shall include full compensation for furnishing all labor, materials, tools, equipment, transportation, and incidentals; and for performing all of the work involved for removal and disposal of existing concrete including curb & gutter, sidewalk, curb ramps, and cross gutters with spandrels, existing roadway (AC & AB), AC berms, pavers, and any other existing concrete surfaces that must be demoed to successfully install the proposed concrete improvement, as detailed in the Standard Specifications, these Special Provisions, and the project plans.
Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply to this bid item.
Prior to digging, the contractor shall call 811 and pothole to determine exact utility horizontal locations and depths.
All construction surveying and staking will be performed by the City.
Bid Item 19 Construct Minor Concrete - Curb and Gutter
MEASUREMENT AND PAYMENT:
The contract price paid per linear foot for curb and gutter concrete improvements under Minor Concrete Curb and Gutter is Final Pay and -shall include full compensation for furnishing all labor, materials, tools, equipment, transportation, and incidentals; and for performing all work involved as detailed in the Standard Specifications, these Special Provisions, and the plans and typical sections.
The price for Minor Concrete bid item includes subgrade preparation, furnishing, placing and compaction of class II aggregate base, all costs associated with incidental work such as the cost of restoring adjacent pavement and backfilling the adjacent area with native material to accommodate new curb and gutter as shown on plans shall be included in the unit cost of the work and no additional compensation will be allowed therefor. Hot Mix Asphalt used for the HMA plug adjacent to new curb and gutter is paid as part of the respective bid item and no additional compensation will be allowed therefor. Curb and Gutter shall be constructed in accordance with City of Seaside Standard Plan ST-410.
Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply.
Prior to digging, the contractor must call 811 and pothole to determine exact utility horizontal locations and depths.
All construction surveying and staking will be performed by the City.
Bid Item 20 Construct Minor Concrete-Cross Gutter and Spandrel (8 inch thick) MEASUREMENT AND PAYMENT:
The contract price paid per square foot for cross gutter concrete improvements under Minor Concrete is Final Pay-shall include full compensation for furnishing all labor, materials, tools, equipment, transportation, and incidentals; and for performing all work involved as detailed in the Standard Specifications, these Special Provisions, and the plans and typical sections.
The price for Minor Concrete Cross Gutter and Spandrel (8- item includes subgrade preparation, furnishing, placing and compaction of class II aggregate base, all costs associated with incidental work such as the cost of restoring adjacent pavement and backfilling the adjacent area with native material to accommodate new concrete cross gutter and spandrel as shown on project plans, shall be included in the unit cost of the work and no additional compensation will be allowed therefor. Hot Mix Asphalt used for the HMA plug adjacent to new cross gutter is paid as part of the respective bid item and no additional compensation will be allowed therefor. Concrete Cross Gutter and Spandrel shall be constructed in accordance with City of Seaside Standard Plan ST-720.
291
Part II, Page 11
Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply.
Prior to digging, the contractor must call 811 and pothole to determine exact utility horizontal locations and depths.
All construction surveying and staking will be performed by the City.
Bid Item 21 Construct Minor Concrete-Sidewalk (4 inch thick) MEASUREMENT AND PAYMENT:
The contract price paid per square foot for sidewalk concrete improvements under is Final Pay and -shall include full compensation for furnishing all labor, materials, tools, equipment, transportation, and incidentals; and for performing all work involved as detailed in the Standard Specifications, these Special Provisions, and the plans and typical sections.
The price for bid item includes subgrade preparation,
furnishing, placing and compaction of class II aggregate base, all costs associated with incidental work such as the cost of restoring adjacent pavement and backfilling the adjacent area with native material to accommodate new sidewalk as shown on plans shall be included in the unit cost of the work and no additional compensation will be allowed therefor. New sidewalk shall match existing back of sidewalk limits unless otherwise noted on the plans.
New sidewalk shall conform the existing finish grade of all building entryways. Sidewalk shall be constructed in accordance with City of Seaside Standard Plan ST-415.
Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply.
Prior to digging, the contractor must call 811 and pothole to determine exact utility horizontal locations and depths.
All construction surveying and staking will be performed by the City.
Bid Item 22-Construct Minor Concrete-Curb Ramps (6 inch thick) MEASUREMENT AND PAYMENT:
The contract price paid per square foot for curb ramp concrete improvements under is Final Pay and -shall include full compensation for furnishing all labor, materials, tools, equipment, transportation, and incidentals; and for performing all work involved as detailed in the Standard Specifications, these Special Provisions, and the plans and typical sections.
The price for bid item includes subgrade preparation, furnishing, placing and compaction of class II aggregate base, all costs associated with incidental work such as the cost of restoring adjacent pavement and backfilling the adjacent area with native material to accommodate new sidewalk as shown on plans shall be included in the unit cost of the work and no additional compensation will be allowed therefor. Curb Ramps shall be constructed in accordance to City of Seaside Standard Plan ST-455. Curb ramps must include a 6-inch thick concrete section under the detectable warning surface (DWS) and the gutter pan.
Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply.
Prior to digging, the contractor must call 811 and pothole to determine exact utility horizontal locations and depths.
All construction surveying and staking will be performed by the City.
Bid Item 23-Construct 6-inch Minimum Vertical Curb
DESCRIPTION OF WORK:
- shall consist of constructing Portland cement concrete vertical curb with a minimum 6-inch curb reveal at proposed curb ramp locations, as shown on the Plans and as directed by the Engineer.
The work shall include furnishing all labor, materials, equipment, excavation, subgrade preparation, forming, reinforcing (when required), concrete placement, finishing, curing, construction joints, expansion joints, dowels (where required), backfilling, disposal of surplus material, and all incidental work necessary to complete the installation.
The vertical curb shall be constructed in accordance with Section 73, "Concrete Curbs and Sidewalks," of the 2025 Caltrans Standard Specifications, the applicable 2025 Caltrans Standard Plans (A87A and curb ramp details), and the details shown on the Plans. The curb shall be constructed to provide a minimum 6-inch vertical curb reveal adjacent to each proposed curb ramp and shall transition smoothly into adjacent curb, gutter, sidewalk, and curb ramp improvements without abrupt changes in grade or alignment.
292
Part II, Page 12
MEASUREMENT AND PAYMENT:
- will be measured by the linear foot (LF) along the face of curb actually constructed and accepted.
The contract unit price paid per linear foot shall constitute full compensation for furnishing all labor, materials, equipment, excavation, removal of existing improvements where required, subgrade preparation, forming, concrete, finishing, curing, joints, dowels, backfill, disposal of surplus material, and all incidentals necessary to complete the work in accordance with the Plans, Specifications, and the direction of the Engineer.
No separate payment will be made for excavation, subgrade preparation, forming, curing, construction joints, expansion joints, or transitions to adjacent improvements, as these costs shall be considered Construct 6-Inch Minimum Vertical Curb
All construction surveying and staking will be performed by the City.
Bid Item 24 Detectable Warning Surface (DWS)
MEASUREMENT AND PAYMENT:
The contract price paid per square feet for shall include full compensation for furnishing all labor, materials, tools, equipment, transportation, installation, complete in place, as shown on the plans, as specified in the Standard Specifications, these special provisions, and as shown on the project plans.
The Detectable Warning Surface (DWS) must be wet-set type (mot surface mounted) prefabricated composite panels listed on the Caltrans authorized material list. DWS color shall be federal yellow. Surface-mounted panels may be used in retrofit applications only, upon approval of the City and the Engineer.
Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply.
All construction surveying and staking will be performed by the City.
Bid Item 25- Parking Wheel Stops
MEASUREMENT AND PAYMENT:
The contract price paid per each for shall include full compensation for furnishing all labor, materials, tools, equipment, transportation, installation, complete in place, as shown on the plans, as specified in the Standard Specifications, these special provisions, and as shown on the project plans.
Wheel Stops shall be made from steel reinforced concrete and must have a minimum length of 6 ft.
Alternative wheel stop types such as materials and dimensions will require approval from the engineer.
All construction surveying and staking will be performed by the City.
Bid Item 26-Remove and Dispose Existing Storm Drain Catch Basin MEASUREMENT AND PAYMENT:
The Contract Price Paid per each shall include all
work associated with the removal of existing storm drain catch basin as indicated on the plans. The work shall include but not limited to saw cutting, grinding, trenching, removal and disposal of asphalt (including reinforcing fabric, if present), concrete pavement, removal of pipes, spoil disposal, backfill, compaction, cleaning, temporary paving, surface restoration of all public and private improvements including asphalt paving, concrete paving, driveway, striping, landscaping and all incidentals required by these specifications and drawings.
Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply.
Prior to digging, the contractor shall call 811 and pothole to determine exact utility horizontal locations and depths.
All construction surveying and staking will be performed by the City.
Bid Item 27 & 28-Remove Existing Storm Drain Pipe
MEASUREMENT AND PAYMENT:
Remove Existing 10-
Existing 15- shall include all work associated with the removal of existing storm drain pipe as indicated on the plans. The work shall include but not limited to saw cutting, grinding, trenching, 293
Part II, Page 13
removal and disposal of asphalt (including reinforcing fabric, if present), concrete pavement, removal of pipes, spoil disposal, backfill, compaction, cleaning, temporary paving, surface restoration of all public and private improvements including concrete paving, driveway, striping, landscaping and all incidentals required by these specifications and drawings. The length paid shall be measured from the outside face of manhole/inlet structure.
Restoration of pavement is included in this bid item only when proposed project paving is not taking place.
Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply.
Prior to digging, the contractor shall call 811 and pothole to determine exact utility horizontal locations and depths.
All construction surveying and staking will be performed by the City.
Bid Item 29 & 30-Construct Storm Drain Pipe (HDPE)
MEASUREMENT AND PAYMENT:
The Contract Price Paid per linear foot Construct 12- -inch shall include all work associated with the installation of storm drain pipe as indicated on plans. The work shall include but not limited to all potholing, site clearing, saw cutting, grinding, trenching, dewatering and bypass pumping if required, removal and disposal of asphalt (including reinforcing fabric, if present), concrete pavement, spoil disposal, dewatering, installation of bedding, furnishing and placing pipe and fittings, connection to new manholes, backfill, compaction, pipeline testing, cleaning, temporary paving, surface restoration of all public and private improvements including, concrete paving, driveway, striping, landscaping and all incidentals required by these specifications and drawings. Restoration of pavement is included in this bid item only when proposed project paving is not taking place. The length paid shall be measured from the outside edge of manhole/inlet structure.
Storm Drain pipe must be HDPE DR-17 or approved equal.
Prior to digging, the contractor shall call 811 and pothole to determine exact utility horizontal locations and depths.
All construction surveying and staking will be performed by the City.
Bid Item 31 & 32-Construct Storm Catch Basin
MEASUREMENT AND PAYMENT:
The Contract Price Paid per each shall include full compensation for all work associated with the installation of the drainage inlets including, but not limited to, furnishing all labor, materials, tools, equipment, transportation, and incidentals, as noted on the plans, per the Standard Specifications and these special provisions.
Full compensation for earthwork related to installing drainage inlets shall be considered as included in the items of work involved and no additional compensation will be allowed therefor. Restoration of pavement is included in this bid item only when proposed project paving is not taking place.
Storm Drain Catch Basins along Holly Street shall be constructed per City of Seaside Standard Plan SD-510 except for one Storm Drain Catch Basin at the intersection of Holly Street and Redwood Avenue that must e 2025 Caltrans Standard Plan D72B.
Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply.
Prior to digging, the contractor shall call 811 and pothole to determine exact utility horizontal locations and depths.
All construction surveying and staking will be performed by the City.
Bid Item 33-Connect New Storm Drain Pipe to Existing Storm Drain Structure MEASUREMENT AND PAYMENT:
The Contract Price Paid per each Connect New Storm Drain shall include all work associated with the connection of new storm drain pipe to existing storm drain manhole as indicated on plans. The work shall include but not limited to all potholing, site clearing, saw cutting, grinding, trenching, dewatering and bypass pumping if required, removal and disposal of asphalt (including reinforcing fabric, if present), concrete pavement, removal of abandoned pipes, spoil disposal, dewatering, backfill, compaction, pipeline testing, cleaning, temporary paving, surface restoration of all public and private improvements including concrete paving, driveway, striping, landscaping and all incidentals required by these specifications and drawings.
New Storm Drain Connections to existing structures shall be constructed in accordance with City of Seaside Standard Plan SD-210.
Prior to digging, the contractor shall call 811 and pothole to determine exact utility horizontal locations and depths.
All construction surveying and staking will be performed by the City.
Bid Item 34-Connect New Storm Drain Pipe to Existing Storm Drain Pipe 294
Part II, Page 14
MEASUREMENT AND PAYMENT:
The Contract Price Paid per each shall
include all work associated with the connection of new storm drain pipe to existing storm drain manhole as indicated on plans. The work shall include but not limited to all potholing, site clearing, saw cutting, grinding, trenching, dewatering and bypass pumping if required, removal and disposal of asphalt (including reinforcing fabric, if present), concrete pavement, removal of abandoned pipes, spoil disposal, dewatering, backfill, compaction, pipeline testing, cleaning, temporary paving, surface restoration of all public and private improvements including concrete paving, driveway, striping, landscaping and all incidentals required by these specifications and drawings.
Existing Storm Drain Connections to New Storm Drain manholes shall be constructed in accordance to City of Seaside Standard Plan SD-110.
Prior to digging, the contractor shall call 811 and pothole to determine exact utility horizontal locations and depths.
All construction surveying and staking will be performed by the City.
Bid Item 35-Remove Existing 3-inch Sanitary Sewer Service Line MEASUREMENT AND PAYMENT:
The Contract Price paid per linear foot for -inch Sanitary Sewer Service Line measured along the centerline of the pipe and shall constitute full compensation for furnishing all labor, materials, tools, equipment, excavation, shoring, dewatering, sawcutting, removal and disposal of the existing 3-inch sanitary sewer service line, backfill and compaction, restoration of disturbed areas, and all incidental work necessary to complete the work as shown on the Plans and as directed by the Engineer.
The location of the existing 3-inch sanitary sewer service line shown on the Plans at City Hall is approximate.
The Contractor shall verify the exact location, alignment, and depth of the existing 3-inch sanitary sewer service line prior to the start of construction. Any discrepancies between the existing field conditions and the Plans shall be immediately reported to the Engineer before proceeding with the work.
All vegetation, landscaping, concrete, asphalt, and curbs disturbed during the removal of the 3-inch sanitary sewer service line must be replaced in kind.
No separate payment will be made for traffic control, utility coordination, temporary support of existing utilities, or any other incidental work required to complete the removal, as these costs shall be included in the contract unit price.
Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply. Prior to digging, the contractor shall call 811 and pothole to determine exact utility horizontal locations and depths.
All construction surveying and staking will be performed by the City.
Bid Item 36-Construct New 4-inch Sanitary Sewer Service Line MEASUREMENT AND PAYMENT:
The Contract Price Paid per linear foot Construct New 4- shall include all work associated with the installation of sanitary sewer pipe as indicated on plans. The work shall include but not limited to all potholing, site clearing, saw cutting, grinding, trenching, dewatering and bypass pumping if required, removal and disposal of asphalt (including reinforcing fabric, if present), concrete pavement, removal of abandoned pipes, spoil disposal, dewatering, installation of bedding, furnishing and placing pipe and fittings, connection to new or existing manholes, backfill, compaction, pipeline testing, cleaning, temporary paving, surface restoration of all public and private improvements including concrete paving, driveway, striping, landscaping and all incidentals required by these specifications and drawings. The length paid shall be measured from the center of sanitary sewer structure to connection of existing pipe.
All vegetation, landscaping, concrete, asphalt, and curbs disturbed during the construction of new 4-inch sanitary sewer service line must be replaced in kind.
Prior to digging, the contractor shall call 811 and pothole to determine exact utility horizontal locations and depths.
All construction surveying and staking will be performed by the City.
Bid Item 37-Construct New Sanitary Sewer Cleanout (SSCO) MEASUREMENT AND PAYMENT:
The Contract Price Paid per each shall include full
compensation for all work associated with the installation of sanitary sewer cleanout as indicated on plans. The work shall include but not limited to all potholing, site clearing, saw cutting, grinding, trenching, dewatering and bypass pumping if required, removal and disposal of asphalt (including reinforcing fabric, if present), concrete pavement, removal of abandoned pipes, spoil disposal, dewatering, installation of bedding, furnishing and placing pipe and fittings, backfill, compaction, pipeline testing, cleaning, temporary paving, surface restoration of all public and private improvements including concrete paving, driveway, striping, landscaping and all incidentals required by 295
Part II, Page 15
these specifications and drawings.
Prior to digging, the contractor shall call 811 and pothole to determine exact utility horizontal locations and depths.
All construction surveying and staking will be performed by the City.
Bid Item 38-Remove and Relocate Existing Sanitary Sewer Cleanout MEASUREMENT AND PAYMENT:
The Contract Price Paid per each shall include full
compensation for all work associated with the removal and replacement sanitary sewer cleanout as indicated on plans. The work shall include but not limited to all potholing, site clearing, saw cutting, grinding, trenching, dewatering and bypass pumping if required, removal and disposal of asphalt (including reinforcing fabric, if present), concrete pavement, removal of abandoned pipes, spoil disposal, dewatering, installation of bedding, furnishing and placing pipe and fittings, backfill, compaction, pipeline testing, cleaning, temporary paving, surface restoration of all public and private improvements including concrete paving, driveway, striping, landscaping and all incidentals required by these specifications and drawings.
Prior to digging, the contractor shall call 811 and pothole to determine exact utility horizontal locations and depths.
All construction surveying and staking will be performed by the City.
Bid Item 39-44-Adjust to Grade
MEASUREMENT AND PAYMENT:
The Contract Price Paid per each for shall include full compensation for all work associated with the adjusting to grade of utility covers/manholes as indicated on plans. All quantities will be determined from actual counts. The unit costs shall govern regardless of the method used to make the adjustments. No compensation will be allowed for the work performed by the owners of the facilities.
Facilities to be adjusted to finish grade during construction of concrete improvements and after paving operations shall include, but not be limited to, Storm Drain Manholes, Sanitary Sewer Manholes, Water Valves, Water Meters, Gas Valves, Gas Meters, Electrical Boxes, Street Monuments, and/or Irrigation Valves.
If existing utility covers are in inadequate condition, contractor must replace existing utility covers and boxes with new. Contractor shall request new utility covers and boxes from the local utility agencies. If utility agencies are not able to provide new covers and boxes, Contractor shall purchase new covers and boxes and install. Inadequate condition is determined by the Engineer. New utility covers and boxes purchased by Contractor after approval of the engineer.
Gas Valve adjustments must be coordinated with PG&E prior to the start of construction.
Water Valve and/ Water Meter adjustments must be coordinated with California American Water Company prior to the start of construction.
The above contract unit costs shall be considered full compensation for furnishing all labor, materials, tools, equipment, transportation, and incidentals; and for performing all of the work involved as detailed in the Standard Specifications, these Special Provisions, and the plans and typical sections and no additional compensation will be allowed therefor. Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply.
All construction surveying and staking will be performed by the City.
Bid Item 45 - 46 - Thermoplastic Pavement Markings
DESCRIPTION OF WORK:
These items of work include layout, providing markers, adhesive, and installation of markers to produce markings as shown on the plans and detailed in 2025 Caltrans Standard Plans. The markings shall conform to Section 81-3, Pavement Markers and layout shall conform with Section 84-2, Traffic Stripes and Pavement Markings of the Caltrans Standard Specifications. Engineer shall inspect and approve layout of striping prior to final installation.
Thermoplastic Markings shall not be installed until layout has been approved by the engineer. The contractor shall request inspection of the marking layout and provide 72 hours for the engineer to review. Contractor shall make modifications to the layout as directed by the engineer, to comply with plans and the latest MUTCD standards, at no additional cost to the City.
MEASUREMENT AND PAYMENT:
Payment for
296
Part II, Page 16
shall be measured per square feet. Layout and placement of temporary tabs will be included in the unit price bid for each striping detail and no additional compensation will be allowed therefor.
Continental Crosswalks shall be installed per City of Seaside Standard Plan ST-940 and must comply with Caltrans Standard Specifications, Section 84. Pavement Markings shall be thermoplastic. Crosswalk markings located within 600 feet of a school must be yellow.
Full compensation for furnishing all labor, materials, tools, equipment and incidentals and for doing all the work involved with placing thermoplastic markings, including pavement markers, as specified in these Special Provisions, as shown on the plans and as directed by the Engineer, shall be considered as included in the contract square foot price for Thermoplastic of the various kinds identified in the Bid Schedule, and no additional compensation will be allowed.
Bid Items 47 - Thermoplastic Traffic Stripe
DESCRIPTION OF WORK:
These items of work include layout, providing markers, adhesive, and installation of markers to produce striping as shown on the plans and detailed in Caltrans Standard Plans. The markers for striping shall conform to Section 81- 3, Pavement Markers and layout shall conform with Section 84-2, Traffic Stripes and Pavement Markings of the Caltrans Standard Specifications.
prior to final installation.
MEASUREMENT AND PAYMENT:
shall be per lineal feet. Layout and placement of
compensation will be allowed therefor.
Measurement and Payment for multi-line striping shall be per linear foot, measured along the plan centerline length of the applicable striping detail, regardless of the number of individual lines within the detail. Measurement and Payment for single-line striping shall be per linear foot of the actual painted stripe length placed in the field.
of more than 25 percent of the quantities set forth in the Schedule of Bid Prices, and portions of Section 4.3.2 of the General Provisions shall not apply.
Bid Item 48 - Blue Reflective Markers at Fire Hydrants
DESCRIPTION OF WORK:
shall conform to Section 81-
Caltrans Standard Specifications. Blue Markers shall be placed in roadway to designate location of fire hydrant.
Placement is per the direction of the Engineer.
MEASUREMENT AND PAYMENT:
The contract price measured and paid per each for shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all the work involved in applying markers, complete in place, including establishing alignment for markers and layout work, as specified in these specifications and directed by the Engineer.
No adjustment in the contract unit price for Raised Pavement Markers Blue Markers items shall be made for increases or decreases of more than 25 percent of the quantities set forth in the Schedule of Bid Prices, and portions of Section 4.3.2 of the General Provisions shall not apply.
Bid Items 49 Remove Existing Sign and Post
DESCRIPTION OF WORK:
Existing Traffic Signs must be removed and relocated as identified in the project plans. Exact location of new and/or relocated traffic signs shall be identified in the field by the engineer.
MEASUREMENT AND PAYMENT:
Measurement and Payment for each and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all the work involved in removing and relocating existing traffic signs.
Bid Items 50 Install New Sign and post
297
Part II, Page 17
DESCRIPTION OF WORK:
The work under this item shall consist of furnishing all labor, materials, tools, equipment, and incidentals necessary to install new traffic signs at the locations shown on the Plans or as directed by the Engineer. Work shall include installation of new sign panels, posts, hardware, breakaway devices, foundations (if required), mounting assemblies, and all appurtenant materials necessary for a complete and functional installation.
Installation shall include setting posts to the required depth and alignment, ensuring proper vertical and horizontal orientation, fastening sign panels securely, and providing all required clearances in accordance with the California MUTCD and applicable Standard Plans. Contractor shall also be responsible for protecting existing improvements, performing minor adjustments to adjacent facilities as necessary, and restoring any disturbed areas to original or improved condition.
All work shall conform to the Standard Specifications, Project Plans, Technical Specifications, and applicable local and State requirements.
MEASUREMENT AND PAYMENT:
shall be made on a per Each basis for each sign installed and accepted by the Engineer, complete in place in accordance with the Plans and Specifications. shall be made at the contract unit price per Each, as shown on the Bid Schedule, and shall include full compensation for furnishing all labor, materials, tools, equipment, hardware, posts, foundations, sign panels, breakaway devices, mounting assemblies, installation, traffic control, and incidentals necessary to complete the work in accordance with the Plans, Specifications, and applicable Standard Plans. No additional compensation shall be allowed therefor.
Bid Item 51-Removal of Existing Trees/Bushes
MEASUREMENT AND PAYMENT:
will be measured by the each (EA) for all work necessary to remove and dispose of the existing trees, shrubs, bushes, stumps, and roots within the limits shown on the plans or as directed by the Engineer. No separate measurement will be made for individual trees, bushes, excavation, backfilling, disposal, or restoration. shall constitute full
compensation for furnishing all labor, materials, equipment, tools, and incidentals required to complete the work. Payment shall include, but not be limited to, cutting, grubbing, stump and root removal, excavation as necessary, backfilling and compaction of resulting voids, loading, hauling, legal disposal of all removed material, protection of adjacent improvements and utilities, traffic control, dust control, and all other work necessary to complete the removal in accordance with the Plans, Specifications, and as directed by the Engineer.
Project Plans require removal of trees and large bushes at the intersection of Holly Street and Dias Avenue. Contractor must coordinate tree removal with City prior to the start of construction. City to coordinate tree removal effort with property owners fronting the area of work.
No additional compensation will be allowed for work required to complete this item.
Additive Alternate 1: Bid Item and Descriptions and Payment Bid Item 1a- Mobilization/Demobilization
DESCRIPTION OF WORK:
Mobilization shall conform to the provision of Section 10.2 of the General Provisions.
MEASUREMENT AND PAYMENT:
The contract lump sum price paid for shall be considered full compensation for mobilization as specified herein, including but not limited to notifications, project records and documents, obtaining all required permits, licenses, and paying all fees, moving on the site any equipment required for the operations, preparatory work, coordination and cooperation, inquiring information about other anticipated projects in the project areas and coordination to minimize delays, project meetings, developing construction water supply, providing onsite sanitary facilities, developing a temporary construction staging area, subcontractor insurance and bonds, 298
Part II, Page 18
Contractor insurance and bonds, demobilization and all other mobilization work, and no additional payment shall be allowed therefor.
The department shall make partial payments for the mobilization costs of the contract, not to exceed the following:
6. When 5 percent of the original contract amount is earned, 50 percent of the amount bid for mobilization, or 5 percent of the original contract amount, whichever is lesser, may be paid.
7. When 10 percent of the original contract amount is earned, 75 percent of the amount bid for mobilization or 7.5 percent of the original contract amount, whichever is lesser, may be paid.
8. When 20 percent of the original contract amount is earned, 95 percent of the amount bid for mobilization, or 9.5 percent of the original contract amount, whichever is lesser, may be paid.
9. When 50 percent of the original contract amount is earned, 100 percent of the amount bid for mobilization, or 10 percent of the original contract amount, whichever is lesser, may be paid.
10. Upon completion of all work on the project, payment of any amount bid for mobilization in excess of 10 percent of the original contract amount will be paid.
Bid Item 2a- Traffic Control System
MEASUREMENT AND PAYMENT:
The contract lump sum price paid for shall include full compensation for furnishing all labor, materials (including signs), tools, equipment, incidentals, furnishing all flagmen, and for doing all the work as described below, as directed by the Engineer, and as specified in the Standard Specifications and these special provisions. No additional compensation will be allowed:
The installation of the traffic and pedestrian control complete in place as specified in the General Provisions, these Special Provisions, and as directed by the Engineer.
Furnishing, placing, maintaining, and removing the temporary reflective raised pavement markers, used for temporary lane line and centerline delineation, for those areas where temporary lane line and centerline delineation are required, and for providing equivalent patterns of permanent traffic lines for such areas when required.
Placing, removing, storing, maintaining, moving to new locations, replacing, and disposing of the components of the traffic control system.
Furnishing and installing funding signs as shown on the plans and as directed by the City and Engineer.
Furnishing of Traffic Control Flaggers for the project.
Traffic control plans, including revisions to the satisfaction of the Engineer.
The contractor shall comply with the permit required by Caltrans for all work to be performed by the Contractor in Caltrans right of way. The Contractor is responsible for determining the need for and obtaining the requisite permits.
Bid Item 3a- Water Pollution Control Plan
MEASUREMENT AND PAYMENT:
The contract lump sum price paid for shall include full compensation for preparing a water pollution prevention plan, developing and implementing the plan, providing a WPC manager, conducting WPC training, and monitoring, inspection, reporting, and correcting WPC practices the lump sum. Payment will be made according to Section 13-2.04 of the Standard Specifications, with 75% of the item total paid upon authorization of the WPCP and the final 25% of the item paid upon project acceptance.
Bid Item 4a- Critical Path Method (CPM) Schedule
Preparing, maintaining, and implementing of the is paid for as a lump sum. The CMP schedule shall be kept up to date and coordinated with the City and the Engineer. A 3 week look 299
Part II, Page 19
ahead shall be provided at every weekly meeting to discuss the specific upcoming activities and any changes that may occur. The CPM schedule shall be updated immediately upon request from the City and/or Engineer.
Bid Item 5a-MicroSlurry (Type II)
MEASUREMENT AND PAYMENT:
The contract price paid per square yard for shall include full compensation for furnishing all labor, providing all materials, tools, equipment, transportation, and incidentals and for doing all the work involved mporary striping, and notifications,
as shown on the plans, as specified in the State Standard Specifications and these special provisions, and as directed by the Engineer.
Bid Item 6a-Crack Seal
The contract price paid per linear foot for shall include full compensation for furnishing all labor, materials, tools, equipment, transportation, and incidentals and for doing all the work involved in sealing cracks, complete in place, as specified in the State Standard Specifications and these special provisions, and as directed by the Engineer.
Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply to this bid item.
Bid Item 7a-Localized Base Repairs (Digouts) (6 inch depth) DESCRIPTION OF WORK:
shall consist of grinding the roadway to the specified depth, removing and disposing of the existing depth of pavement and any underlying unsuitable material as determined by the Engineer, compacting the exposed surface and replacing it with the specified thickness of asphalt concrete in accordance with the detail in these special provisions.
Localized Base Failure Repair (Digouts) for base bid shall be performed as follows:
California Avenue shall have localized base repairs (digouts) at a maximum depth of 6 inches. Localized Base Repair areas to be marked out in the field by the engineer prior to start of construction.
MEASUREMENT AND PAYMENT:
The contract unit price paid per TON for shall include full compensation for furnishing all labor, material (including Hot Mix Asphalt and tack coat), tools, equipment, sweeping, and off haul of complete in place as shown in the detail in these special provisions, as specified herein, and as directed by the Engineer, and no additional compensation will be allowed therefor.
No payment shall be made for materials placed outside of the limits marked by the Engineer. increased or decreased based on field conditions evaluation by the Engineer, and no adjustment in the contract bid price or other contract items
Schedule of Bid Prices, and portions of Section 4.3.2 of the General Provisions shall not apply.
Bid Item 8a-ThermoplaStic Pavement Markings
DESCRIPTION OF WORK:
These items of work include layout, providing markers, adhesive, and installation of markers to produce markings as shown on the plans and detailed in 2025 Caltrans Standard Plans. The markings shall conform to Section 81-3, Pavement Markers and layout shall conform with Section 84-2, Traffic Stripes and Pavement Markings of the Caltrans Standard Specifications. Engineer shall inspect and approve layout of striping prior to final installation.
Thermoplastic Markings shall not be installed until layout has been approved by the engineer. The contractor shall request inspection of the marking layout and provide 72 hours for the engineer to review. Contractor shall make modifications to the layout as directed by the engineer, to comply with plans and the latest MUTCD standards, at no additional cost to the City.
MEASUREMENT AND PAYMENT:
Payment for
shall be measured per square feet. Layout and placement of temporary tabs will be included in the unit price bid for each striping detail and no additional compensation will be allowed therefor. 300
Part II, Page 20
Continental Crosswalks shall be installed per City of Seaside Standard Plan ST-940 and must comply with Caltrans Standard Specifications, Section 84. Pavement Markings shall be thermoplastic. Crosswalk markings located within 600 feet of a school must be yellow.
Full compensation for furnishing all labor, materials, tools, equipment and incidentals and for doing all the work involved with placing thermoplastic markings, including pavement markers, as specified in these Special Provisions, as shown on the plans and as directed by the Engineer, shall be considered as included in the contract square foot price for Thermoplastic of the various kinds identified in the Bid Schedule, and no additional compensation will be allowed.
Bid Item 9a-Blue Reflective Markers at Fire Hydrants
DESCRIPTION OF WORK:
shall conform to Section 81-
Caltrans Standard Specifications. Blue Markers shall be placed in roadway to designate location of fire hydrant.
Placement is per the direction of the Engineer.
MEASUREMENT AND PAYMENT:
The contract price measured and paid per each for shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all the work involved in applying markers, complete in place, including establishing alignment for markers and layout work, as specified in these specifications and directed by the Engineer.
No adjustment in the contract unit price for Raised Pavement Markers Blue Markers items shall be made for increases or decreases of more than 25 percent of the quantities set forth in the Schedule of Bid Prices, and portions of Section 4.3.2 of the General Provisions shall not apply.
Bid Item 10a-14a- Thermoplastic Traffic Stripe
DESCRIPTION OF WORK:
These items of work include layout, providing markers, adhesive, and installation of markers to produce striping as shown on the plans and detailed in Caltrans Standard Plans. The markers for striping shall conform to Section 81- 3, Pavement Markers and layout shall conform with Section 84-2, Traffic Stripes and Pavement Markings of the Caltrans Standard Specifications.
prior to final installation.
MEASUREMENT AND PAYMENT:
shall be per lineal feet. Layout and placement of
compensation will be allowed therefor.
Measurement and Payment for multi-line striping shall be per linear foot, measured along the plan centerline length of the applicable striping detail, regardless of the number of individual lines within the detail. Measurement and Payment for single-line striping shall be per linear foot of the actual painted stripe length placed in the field.
of more than 25 percent of the quantities set forth in the Schedule of Bid Prices, and portions of Section 4.3.2 of the General Provisions shall not apply.
Additive Alternate 2: Bid Item Descriptions and Payment Bid Item 1b-Mobilization/Demobilization
DESCRIPTION OF WORK:
Mobilization shall conform to the provision of Section 10.2 of the General Provisions.
MEASUREMENT AND PAYMENT:
The contract lump sum price paid for shall be considered full compensation for mobilization as specified herein, including but not limited to notifications, project records and documents, obtaining all required permits, licenses, and paying all fees, moving on the site any equipment required for the operations, preparatory work, coordination and cooperation, inquiring information about other anticipated projects in the project areas and coordination to minimize delays, project meetings, developing construction water supply, providing on-site sanitary facilities, developing a temporary construction staging area, subcontractor insurance and bonds, Contractor insurance and bonds, demobilization and all other mobilization work, and no additional payment shall be allowed therefor.
The department shall make partial payments for the mobilization costs of the contract, not to exceed the following:
301
Part II, Page 21
1. When 5 percent of the original contract amount is earned, 50 percent of the amount bid for mobilization, or 5 percent of the original contract amount, whichever is lesser, may be paid.
2. When 10 percent of the original contract amount is earned, 75 percent of the amount bid for mobilization or 7.5 percent of the original contract amount, whichever is lesser, may be paid.
3. When 20 percent of the original contract amount is earned, 95 percent of the amount bid for mobilization, or 9.5 percent of the original contract amount, whichever is lesser, may be paid.
4. When 50 percent of the original contract amount is earned, 100 percent of the amount bid for mobilization, or 10 percent of the original contract amount, whichever is lesser, may be paid.
5. Upon completion of all work on the project, payment of any amount bid for mobilization in excess of 10 percent of the original contract amount will be paid.
Bid Item 2b-Traffic Control System
MEASUREMENT AND PAYMENT:
The contract lump sum price paid for shall include full compensation for furnishing all labor, materials (including signs), tools, equipment, incidentals, furnishing all flagmen, and for doing all the work as described below, as directed by the Engineer, and as specified in the Standard Specifications and these special provisions. No additional compensation will be allowed:
The installation of the traffic and pedestrian control complete in place as specified in the General Provisions, these Special Provisions, and as directed by the Engineer.
Furnishing, placing, maintaining, and removing the temporary reflective raised pavement markers, used for temporary lane line and centerline delineation, for those areas where temporary lane line and centerline delineation are required, and for providing equivalent patterns of permanent traffic lines for such areas when required.
Placing, removing, storing, maintaining, moving to new locations, replacing, and disposing of the components of the traffic control system.
Furnishing and installing funding signs as shown on the plans and as directed by the City and Engineer.
Furnishing of Traffic Control Flaggers for the project.
Traffic control plans, including revisions to the satisfaction of the Engineer.
The contractor shall comply with the permit required by Caltrans for all work to be performed by the Contractor in Caltrans right of way. The Contractor is responsible for determining the need for and obtaining the requisite permits.
Bid Item 3b-Water Pollution Control Plan
MEASUREMENT AND PAYMENT:
The contract lump sum price paid for shall include full compensation for preparing a water pollution prevention plan, developing and implementing the plan, providing a WPC manager, conducting WPC training, and monitoring, inspection, reporting, and correcting WPC practices the lump sum. Payment will be made according to Section 13-2.04 of the Standard Specifications, with 75% of the item total paid upon authorization of the WPCP and the final 25% of the item paid upon project acceptance.
Bid Item 4b-Critical Path Method (CPM) Schedule
Preparing, maintaining, and implementing of the is paid for as a lump sum. The CMP schedule shall be kept up to date and coordinated with the City and the Engineer. A 3 week look ahead shall be provided at every weekly meeting to discuss the specific upcoming activities and any changes that may occur. The CPM schedule shall be updated immediately upon request from the City and/or Engineer.
Bid Item 5b- Grind, Offhaul, Disposal if Existing Roadway (Depth 6 inch minimum) MEASUREMENT AND PAYMENT:
302
Part II, Page 22
The Contract unit price per square yard for shall include full compensation for furnishing all labor, materials, tools, equipment, transportation, and incidentals, and for doing all the work including excavation, grinding, removal, and disposal of materials such as pavement fabric and road mesh, grading and compaction, complete in place as specified in these Special Provisions, as shown on the Plans and as directed by the Engineer and no additional compensation will be allowed therefor.
This item is revocable if not used and Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply to this bid item.
Bid Item 6b-Hot Mix Asphalt (Type A) (6 inch Inlay)
DESCRIPTION OF WORK:
This work includes producing and placing hot mix asphalt (HMA) Type A for the following street segments and pavement improvement types:
Additive Alternate 2:
Playa Avenue between California Avenue and Metz Road
O 6-inch Mill and Inlay
The contractor shall place hot mix asphalt (HMA) Type A along street segments identified in the plans. Engineer to mark out exact pavement improvement limits in the field prior to the start of construction. -
not be used except for temporary paving operations.
Contractor must comply with Section 39, "Hot Mix Asphalt," of the Standard Specifications except as modified herein.
MEASUREMENT AND PAYMENT:
Payment for shall be at the contract price per TON and shall be considered full compensation for all labor, materials, tools, equipment, transportation, and incidentals to do all the work involved. The contractor shall supply weight tags to the Engineer on a daily basis. Quantities of asphalt concrete will be determined and approved by the Engineer by using the tags. Asphalt concrete weight tags shall contain the project name and indicate tonnage used on each street.
Payment for Tack Coat shall be considered as included in the contract prices bid for various items of work shown on the bid schedule and no additional compensation shall be allowed therefor.
Bid Item 7b-Remove and Replace Unsuitable Subgrade (Revocable if not used) DESCRIPTION OF WORK:
Should the base material found at the required elevations prove to be soft, spongy, or otherwise unsuitable, the Contractor shall obtain a written order from the City Engineer for such additional excavation as may be necessary to obtain a foundation suitable for the asphaltic concrete or concrete to be supported. This additional excavation shall be replaced by the Contractor with select material as directed by the City Engineer.
All work shall be done under the direction of the Engineer. Material that has been deemed unsuitable for reasons including, but not limited to, excessive moisture, shall be removed to a depth as directed by the engineer. All material removed shall become the property of the Contractor and should be disposed of outside of City right-of-way.
Material that is not adequately compacted shall be compacted in place, and is included in other items of work.
Subgrade shall be finished graded and compacted in a manner and to a density that is acceptable to the Engineer. A geo-textile shall be placed for subgrade stabilization prior to placing fill material. Subgrade stabilization fabric shall be MIRAFI HP370 or approved equal.
Asphaltic pavement grindings or aggregate base removed and stockpiled may be used to replace unsuitable material that was removed. The engineer shall approve any material prior to placement. The stockpiled material shall only be placed to the bottom of the existing aggregate subbase. 1- in the zone of the existing aggregate base and subbase. Placement and compaction shall conform to the requirements of Section 26 of the Caltrans Standard Specification.
MEASUREMENT AND PAYMENT:
The contract price paid per cubic yard for includes full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all work involved in removing unsuitable material to required depth, disposing of material, as directed by the Engineer, providing and placing subgrade stabilization fabric, providing and placing stockpiled material (or equal), providing and placing 1- 303
Part II, Page 23
Remove and Replace Unsuitable Material shall be measured by the cubic yard. The depth shall be measured from the elevation that the new Asphaltic Concrete is placed or the aggregate underlaying concrete.
No adjustment in the contract unit price for Remove and Replace Unsuitable Material shall be made for increases or decreased of more than 25 percent of the quantities set forth in the Schedule of Bid Prices, and portions of Section 4.3.2 of the General Provisions shall not apply.
If the Engineer determines that there is no unsuitable material, this item of work shall be revoked.
Bid Item 8b-Demolition and Offhaul of Existing Curb Ramps Demolition and Off haul of Existing Curb Ramps is Final Pay and shall include full compensation for furnishing all labor, materials, tools, equipment, transportation, and incidentals; and for performing all of the work involved for removal and disposal of existing concrete including curb & gutter, sidewalk, curb ramps, and cross gutters with spandrels, existing roadway (AC & AB), AC berms, pavers, and any other existing concrete surfaces that must be demoed to successfully install the proposed concrete improvement, as detailed in the Standard Specifications, these Special Provisions, and the project plans.
Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply to this bid item.
Prior to digging, the contractor shall call 811 and pothole to determine exact utility horizontal locations and depths.
Bid Item 9b-11b-Construct Accessible Curb Ramp-Case B/Case C/Case CM+
DESCRIPTION OF WORK
This work shall consist of construction of new PCC curb, curb and gutter, sidewalk, longitudinal gutter, detectable dome mats, sign post relocation, utility adjustments/relocations and curb ramps as shown on the project plans, as directed by the Engineer, and per these Special Provisions and Technical Specifications. The locations calling for new PCC curb and gutter, sidewalk, and access ramp construction are shown on the project plans. All new PCC curb, curb and gutter, sidewalk, spandrels, longitudinal gutter, cross gutter, and access ramp quantities shall be measured after acceptance of work quality.
All PCC construction work shall conform to the applicable Standard Plan as shown on the project plans and in accordance with Standard Specifications.
The same brand, type and source of cement and aggregate shall be used for all Portland Cement Concrete. Concrete used for curb ramps on the project shall be 560-C-3250
The Contractor shall submit the concrete design mix to the Engineer for approval.
The certified tickets accompanying each batch of ready mix concrete delivered to the job site shall clearly show the All reinforcing steel for reinforced concrete construction shall be Grade 60.
Subgrade preparation shall conform to the provisions of the Standard Specifications and shall be compacted to a minimum relative compaction of 95%.
The Contractor shall verify, to confirm that maximum ramp and sidewalk grades do not exceed ADA requirements when marking the required saw cut removal limits and when setting the concrete forms, prior to nd utilize the proper
experienced personnel to ensure that the proper saw cut limits are established for all access ramp locations and the City shall be present to verify the concrete forms, prior to the Contractor pouring any PCC construction improvements.
Special Note To Contractor:
Prior to constructing a curb ramp where physical site constraints do not allow the access ramp construction to fully meet the ADA standards, the Contractor shall so notify the City Engineer for direction.
PCC access ramp construction shall conform to City of Seaside Standard Plans case per plan, the Project Plans and in accordance with the Standard Specifications. Typical construction tolerances to construct the new ramp shall not apply and maximum grades shall not be exceeded. The Contractor shall be responsible to remove and reconstruct curb ramps at his own cost if ramps are deemed non-compliant with City of Seaside Standard Plans, the 304
Part II, Page 24
pertinent details, these Technical Specifications and ADA standards. Where the type of curb ramp includes a retaining curb at the back or sides of curb ramp to make up for a difference in elevation between the existing grade and curb ramp grade, the construction of said retaining curb shall be considered as part of the curb ramp work.
Sub-grade materials shall be compacted to a minimum relative compaction of 95%. The depressed PCC curb and gutter reconstruction required as a part of the access ramp construction shall not be poured monolithic with the PCC ramp and shall be included in the unit price for the access ramp construction. Adjacent AC/AB removal and replacement AC Base Course shall conform to the requirements established in these specifications and shall be included in the unit price for the wheelchair ramp construction.
All concrete forms shall be removed, irrigation systems shall be repaired and backfilled within 72 hours following concrete placement at both the access ramps and curb & gutter reconstruction locations. PCC improvements subject to vehicle loads shall not be opened to vehicle traffic until concrete has cured to a minimum strength of 2,000 psi.
Detectable Warning Surface
All curb access ramps shall contain detectable warning surfaces. The detectable warning surface required for all curb ramps within the project limits shall be CAST-IN-PLACE DETECTABLE WARNING SURFACE MANUFACTURED BY ARMOR TILE SYSTEMS (800) 682-2525, www.armor-tile.com or approved equal.
The orientation of the dome pattern for all panels shall be parallel with the panel edges. including proper surface preparation and protection of the work and surrounding area The manufacturer shall provide a minimum 5-year warranty, guaranteeing replacement when there is a defect in the dome shape, color fastness, sound on cane acoustic quality, or deterioration of the detectable warning surface. The warranty period shall commence on the date of acceptance.
NOTE: Detectable Warning Surface Materials shall be installed across the full width and full depth of the ramp, in conformance with Caltrans Standard Plan A88A, A88B and latest ADA requirements.
The Contractor shall remove all debris and perform all cleanup work to the satisfaction of the Engineer within three (3) working days after forms have been removed at any location.
When applicable, PCC shall be removed and replaced to the nearest cold joint or weakened plane joint, so that no -square feet
(sidewalk).
spandrels/cross gutter in order to construct compliant ADA curb ramp.
The adjacent asphalt concrete slot patches shall be asphalt concrete Type III-C2, 1/2" maximum, conforming to the provisions in the Standard Specifications.
MEASUREMENT
Measurement for curb ramp construction, as shown on the project plans, shall include the area of the ramp, landing curb ramp limits, and adjacent
Bid Item 12b-14b-Adjust to Grade
MEASUREMENT AND PAYMENT:
The Contract Price Paid per each for shall include full compensation for all work associated with the adjusting to grade of utility covers/manholes as indicated on plans. All quantities will be determined from actual counts. The unit costs shall govern regardless of the method used to make the adjustments. No compensation will be allowed for the work performed by the owners of the facilities.
Facilities to be adjusted to finish grade during construction of concrete improvements and after paving operations shall include, but not be limited to, Storm Drain Manholes, Sanitary Sewer Manholes, Water 305
Part II, Page 25
Valves, Water Meters, Gas Valves, Gas Meters, Electrical Boxes, Street Monuments, and/or Irrigation Valves.
If existing utility covers are in inadequate condition, contractor must replace existing utility covers and boxes with new. Contractor shall request new utility covers and boxes from the local utility agencies. If utility agencies are not able to provide new covers and boxes, Contractor shall purchase new covers and boxes and install. Inadequate condition is determined by the Engineer. New utility covers and boxes purchased by Contractor after approval of the engineer.
Gas Valve adjustments must be coordinated with PG&E prior to the start of construction.
Water Valve and/ Water Meter adjustments must be coordinated with California American Water Company prior to the start of construction.
The above contract unit costs shall be considered full compensation for furnishing all labor, materials, tools, equipment, transportation, and incidentals; and for performing all of the work involved as detailed in the Standard Specifications, these Special Provisions, and the plans and typical sections and no additional compensation will be allowed therefor. Changed quantity payment adjustments under Section 9-1.06 of the Standard Specifications shall not apply.
Bid Item 15b-Thermoplastic Pavement Markings
DESCRIPTION OF WORK:
These items of work include layout, providing markers, adhesive, and installation of markers to produce markings as shown on the plans and detailed in 2025 Caltrans Standard Plans. The markings shall conform to Section 81-3, Pavement Markers and layout shall conform with Section 84-2, Traffic Stripes and Pavement Markings of the Caltrans Standard Specifications. Engineer shall inspect and approve layout of striping prior to final installation.
Thermoplastic Markings shall not be installed until layout has been approved by the engineer. The contractor shall request inspection of the marking layout and provide 72 hours for the engineer to review. Contractor shall make modifications to the layout as directed by the engineer, to comply with plans and the latest MUTCD standards, at no additional cost to the City.
MEASUREMENT AND PAYMENT:
Payment for
shall be measured per square feet. Layout and placement of temporary tabs will be included in the unit price bid for each striping detail and no additional compensation will be allowed therefor.
Continental Crosswalks shall be installed per City of Seaside Standard Plan ST-940 and must comply with Caltrans Standard Specifications, Section 84. Pavement Markings shall be thermoplastic. Crosswalk markings located within 600 feet of a school must be yellow.
Full compensation for furnishing all labor, materials, tools, equipment and incidentals and for doing all the work involved with placing thermoplastic markings, including pavement markers, as specified in these Special Provisions, as shown on the plans and as directed by the Engineer, shall be considered as included in the contract square foot price for Thermoplastic of the various kinds identified in the Bid Schedule, and no additional compensation will be allowed.
Bid Item 16b-Blue Reflective Markers at Fire Hydrants
DESCRIPTION OF WORK:
shall conform to Section 81-
Caltrans Standard Specifications. Blue Markers shall be placed in roadway to designate location of fire hydrant.
Placement is per the direction of the Engineer.
MEASUREMENT AND PAYMENT:
The contract price measured and paid per each for shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all the work involved in applying markers, complete in place, including establishing alignment for markers and layout work, as specified in these specifications and directed by the Engineer.
No adjustment in the contract unit price for Raised Pavement Markers Blue Markers items shall be made for increases or decreases of more than 25 percent of the quantities set forth in the Schedule of Bid Prices, and portions of Section 4.3.2 of the General Provisions shall not apply.
Bid Item 17b-21b-Thermoplastic Traffic Stripe
DESCRIPTION OF WORK:
These items of work include layout, providing markers, adhesive, and installation of markers to produce striping as shown on the plans and detailed in Caltrans Standard Plans. The markers for striping shall conform to Section 81- 306
Part II, Page 26
3, Pavement Markers and layout shall conform with Section 84-2, Traffic Stripes and Pavement Markings of the Caltrans Standard Specifications.
prior to final installation.
MEASUREMENT AND PAYMENT:
shall be per lineal feet. Layout and placement of
compensation will be allowed therefor.
Measurement and Payment for multi-line striping shall be per linear foot, measured along the plan centerline length of the applicable striping detail, regardless of the number of individual lines within the detail. Measurement and Payment for single-line striping shall be per linear foot of the actual painted stripe length placed in the field.
of more than 25 percent of the quantities set forth in the Schedule of Bid Prices, and portions of Section 4.3.2 of the General Provisions shall not apply.
FINAL PAY ITEMS
Specifications.
ANCILLARY ITEMS
Payment for any items that do not have instruction indicating where expenses for said items are to be accounted for or are required to be done to complete the overall project are to be considered ancillary to the work and accounted for in every one of the lump sum or unit price items and no additional compensation will be allowed therefor.
LUMP SUM PRICE BREAKDOWN
Immediately after award of the contract, the contractor shall submit a cost breakdown list to the Engineer for all Lump Sum Bid items. The list shall consist of major elements of work that make up the item and shall be used for determining progress pay estimates.
EXAMINATION OF SITE
Before submitting a Bid, each Bidder shall carefully examine the Plans and Specifications relating hereto. He/she shall also visit the site of the proposed work and shall fully inform himself/herself as to all the existing conditions relating to the construction and related labor so that he/she may fully understand the facilities, difficulties, restrictions attendant on the execution of the work, limitations applying to the work, and he/she shall estimate and include in his/her Bid a sum sufficient to cover the cost of all items which are required to attain the completed conditions contemplated in the project.
BID CLARIFICATION
Pursuant to the provisions of the California Public Contract Code Section 20103.8, City reserves the option to award any or all the additive bid items in addition to the original contract after the lowest responsive responsible Bidder has been determined, should the City later obtain additional funding for additive alternatives not awarded with the original contract.
For responsible bidder as it pertains to this contract, see Part I, Responsible Bidder.
Unit and lump sum prices shall be for items in place, as shown on the Plans, including all labor, materials, equipment, taxes, and incidentals necessary for a complete job.
Whenever unit prices are required and there is an incorrect extension thereof, the unit price correctly extended shall prevail and the total bid shall be corrected to reflect the correct extension. If a bid item amount is zero, enter zero. If The quantities listed in the bid schedule are approximate only, being given as a basis for comparison of bids, and the City of Sand City does not, expressly or by implication, agree that the actual amount of work will correspond therewith, but reserves the right to increase or decrease the amount of work by twenty-five percent (25%) or to omit portions of 307
Part II, Page 27
the work as may be deemed necessary by the Engineer.
-
in PlanetBids Procurement. After withdrawing a previously submitted proposal, the responding firm may submit another proposal at any time up to the deadline for submitting proposals prior to the bid opening. Bids may not be withdrawn for the time period specified in BID VALIDITY of Part I.
The Non- -Procurement Portal shall be executed
and submitted with each bid.
LOCAL HIRING REQUIREMENT
All Contractors who submit bids, or proposals, to construct or provide work on any City of Sand City Public Works project, or for any other Public Works construction, or improvement, on City property must comply with Sand City Municipal Code 12.20.030 et seq., which sets forth the requirements regarding the Local Hiring Requirement for Public Works Projects. Municipal Code and Local Hiring Requirements are available online at https://sandcity.org/city-laws/; Bidders are responsible for familiarizing themselves with the contents thereof before signing the certifications required below.
Among other requirements, this ordinance requires the Contractor to make good-faith efforts, with the assistance of the Employment Development Department and/or local recruitment sources, to hire qualified individuals who are residents of the Monterey Bay Area (Monterey, Santa Cruz and San Benito Counties), in sufficient numbers so that no less than eighty percent (80%) of the Contractor's total construction work force, including subcontractor work force, measured in labor work hours, is comprised of qualified individuals who are Monterey Bay Area residents. This same requirement applies to all subcontractors.
Every Bidder must complete and sign under penalty of perjury a Certification of Good-Faith effort to Hire Monterey Bay Area Residents, on the form provided, and submit said Certification with the sealed bid no later than the date and time of the bid openin
promise to meet, or to make a good-faith effort to meet, the local hiring goal.
Contractor shall include in each and every subcontract relating to the project the requirement that the subcontractor promises to make a good faith effort to hire qualified individuals who are residents of the Monterey Bay Area.
Contractor shall be respon
The local hiring requirement shall not apply under the following circumstances:
(a) Informal Bids, or
(b) Whenever a state or federal law or regulation applicable to a particular contract prohibits the provision of a local hire requirement; or
(c) Whenever the City, in accordance with the requirements of the Code or state law, determines that the contract is necessary to respond to an emergency which endangers the public health, safety, or welfare; or (d) Whenever the City determines that a suitable pool of persons providing specialized skills does not exist locally for a specific public works project. An example would be marine-related pile drivers. 308
Part IV, Page 1
PART III: GENERAL PROVISIONS
FORMAL BID
JOB SITE AND DOCUMENT EXAMINATION
The Bidder is required to thoroughly examine the job site, Plans and Specifications, including t h e f or m contract (See Part III, Page 2) for the work contemplated, and it will be assumed that the Bidder has investigated and is satisfied as to the requirements of the Plans and Specifications, including the contract. It is mutually agreed that submission of a proposal shall be considered prima facie evidence that the Bidder has made such examination.
CONTRACT AWARD AND EXECUTION
CONTRACT AWARD
The contract shall be awarded, if an award is made, to the lowest responsive responsible bidder as defined in Part II, Bid Clarification, of these specifications, within ninety (90) calendar days from the date bids are publicly opened, examined and declared unless a different bid validity period is specified in Part I, Bid Validity. If the award is not made within the specified period, then all of the bids submitted shall be deemed to have been rejected by the legislative body.
CONTRACT EXECUTION
A contract shall not be deemed to have been made between the Contractor and the City of Sand City until all of the following steps have been completed:
1. Award of the contract by the City Council,
2. Within fifteen (15) calendar days after written notice that a contract has been awarded to them (Notice of Award), the Contractor shall submit two (2) signed original contracts, required bonds or alternative security, evidence of insurance that conforms to the contract, and City of Sand City Business License or evidence of application for said license.
3. Upon approval of the foregoing documents, the City will execute the contract and return an original to the Contractor.
309
Part IV, Page 2
P U B L I C W O R K S C O N T R A C T
FY 25/26 PAVEMENT MAINTENANCE AND REHABILITATION (M+R) PROJECT this ___ day of _________________ 2026, by and between the CITY OF SAND CITY, a municipal corporation, hereinafter referred to as the "City", and ______________ hereinafter referred to as the "Contractor";
W I T N E S S E T H :
WHEREAS, the Council of the City has awarded a contract to the Contractor for performing the work
proposal;
NOW, THEREFORE, IT IS AGREED AS FOLLOWS:
1. SCOPE OF WORK. Contractor shall furnish all labor, materials, equipment, and transportation necessary to perform the FY 25/26
particularly described in the Notice to Contractors, Bid Schedule, and Special Provisions, attached hereto and incorporated herein as Exhibit A, and in accordance with the Contrac hereto and incorporated herein as Exhibit B. In the event of a conflict or inconsistency between the text of the main body of this Agreement and Exhibit A or Exhibit B, the text of the main body of this Agreement shall prevail. The timing of commencement and completion of the Work is set forth in Section 3, Time of Performance, below.
2. PAYMENT. City shall pay Contractor an amount not to exceed: __________________ ($XX) for the full and satisfactory completion of the Work in accordance with the terms and conditions of this Agreement. The calculation of payment for the Work shall be set forth as described in the Compensation Form, attached hereto and incorporated herein as Exhibit B. The amount stated above is the entire compensation payable to Contractor for the Work performed hereunder, including all labor, materials, tools and equipment furnished by Contractor.
(A) Invoices. City shall make monthly payments, based on invoices received, for Work satisfactorily performed. City shall have thirty (30) days from the receipt of an invoice that complies with all of the requirements above to pay Contractor. To be deemed complete and eligible for processing, each monthly progress payment invoice must include and be accompanied by the following required documentation: (1) current certified payroll reports and statements of compliance through the invoice date; (2) daily reports containing detailed task listings for all personnel, equipment, and subcontractors; (3) certified quantity calculations supporting all pay items requested; and (4) conditional lien waivers for the current payment and unconditional lien waivers for previous payments pursuant to Civil Code Articles 8122 8138. Failure to submit complete documentation with the monthly invoice will result in the City returning the invoice without action.
(B) False Claims Act. Presenting a false or fraudulent claim for payment, including a change order, is a violation of the California False Claims Act and may result in treble damages and a fine of five thousand ($5,000) to ten thousand dollars ($10,000) per violation. (C) Retention. Pursuant to California Public Contract Code Section 7107, City shall retain five percent performance, to be released in accordance with the retention and progress payment procedures set forth in the Special Provisions.
3. TIME OF PERFORMANCE. The work under this contract shall commence within fourteen (14) calendar days from the effective date of the Notice to Proceed and shall be completed on or before the expiration of 90 calendar days from the effective date of the Notice to Proceed.
4. SEVERABILITY. If any provision in this Agreement is held by a court of competent jurisdiction to be invalid, 310
Part IV, Page 3
void, or unenforceable, the remaining provisions will continue in full force without being impaired or invalidated in any way.
5. GOVERNING LAW AND VENUE. Contractor agrees that in the performance of this Agreement, it will comply with all applicable state, federal and local laws, codes and regulations. This Agreement shall be governed by and construed in accordance with the laws of the State of California and the City of Sand City. Venue for any action regarding this Agreement shall be in the Superior Court of the County of Monterey or in the United States District Court for the Northern District of California.
6. PUBLIC BIDDING. In accordance with the provisions of Sections 1725.5, 1771.1, 1771.3, and 1771.4 of the Labor Code, this project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined by that chapter of the Labor Code, unless currently registered and qualified to perform public work pursuant to Section 1725.5 of the Labor Code. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.
7. COMPLIANCE WITH LAWS AND LABOR STANDARDS
8.1 General Compliance. Contractor shall comply with all applicable local, state, and federal laws, regulations, and ordinances in the performance of this Agreement, including California Health and Safety Code Section 33422.1 and California Labor Code Section 1770 et seq.
8.2 Prevailing Wages. Not less than the general prevailing rate of per diem wages, and not less than the general prevailing rate of per diem wages for holidays and overtime work, for each craft, classification, or type of worker needed to execute the Project shall be paid to all workers, laborers, and mechanics employed in the execution of the Project by Contractor or any subcontractor. Local prevailing wage rates shall apply on all public works construction contracts exceeding twenty-five thousand dollars ($25,000) and all public works contracts for alteration, demolition, repair, or maintenance work exceeding fifteen thousand dollars ($15,000), pursuant to Sand City Municipal Code Section 12.18.060. The DIR wage determinations are on file at 1 Pendergrass Way, Sand City, CA 93955, and shall be posted at the job site by the Contractor.
8.3 Department Of Industrial Relations (Dir) Registration Requirements. In accordance with Labor Code Sections 1725.5, 1771.1, 1771.3, and 1771.4, this project is subject to compliance monitoring and enforcement by the Department of Industrial Relations (DIR). No contractor or subcontractor may be listed on a bid proposal or engage in the performance of any public work contract unless currently registered and qualified to perform public work pursuant to Section 1725.5.
8.4 Certified Payroll Records and Submittals. Contractor and each subcontractor shall keep, maintain and submit certified payroll records in accordance with California Labor Code Section 1776 and all applicable Department of Industrial Relations requirements, including electronic submission requirements..
8.5 Working Hours And Overtime Restrictions. Eight hours labor constitutes a legal day's work. Contractor or any subcontractor shall forfeit penalties to the State for workers required or permitted to work more than 8 hours in any one calendar day or 40 hours in any one calendar week without proper overtime compensation, pursuant to Labor Code Sections 1810 through 1815.Apprenticeship Compliance.
Contractor and all subcontractors shall comply with the provisions of Labor Code Sections 1777.5, 1777.6, and 1777.7 concerning the employment and training of apprentices.
8. Payment of Taxes; Tax Withholding. Contractor is solely responsible for the payment of employment taxes incurred under this Agreement and any similar federal or state taxes. To be exempt from tax withholding, Contractor must provide City with a valid California Franchise Tax Board form 59 Contractor provides City with a valid Form 590 or other valid, written evidence of an exemption or waiver from withholding, City may withhold California taxes from payments to Contractor as required by law.
Contractor shall obtain, and maintain on file for three (3) years after the termination of this Agreement, Form 590s (or other written evidence of exemptions or waivers) from all subcontractors. Contractor accepts sole responsibility for withholding taxes from any non-California resident subcontractor and shall submit written 311
Part IV, Page 4
9. By execution of this Agreement, the Contractor certifies as follows:
-insurance in accordance with the provisions
of that code, and I will comply with such provisions before commencing the performance of the work of this
10. Indemnification
11.1 Contractor shall indemnify, defend with counsel selected by the City, and hold harmless City, its officers, agents, employees and representatives from and against any and all claims, losses, liabilities or damages, demands and actions, including payment of fees, arising out of or resulting from Services performed pursuant to this Agreement caused in whole or in part by any negligent or willful act or omission of Contractor, its officers, agents, employees, or anyone directly or indirectly acting on behalf of Contractor. The foregoing obligation of Contractor shall not apply when (1) the injury, loss of life, damage to property, or violation of law arises wholly from the gross negligence or willful misconduct of the City or its officers, employees, agents, or volunteers and (2) the actions of Contractor or its employees, subcontractor, or agents have contributed in no part to the injury, loss of life, damage to property, or violation of law. It is understood that the duty of Contractor to indemnify and hold harmless includes the duty to defend as set forth in Section 2778 of the California Civil Code.
Acceptance by City of insurance certificates and endorsements required under this Agreement does not relieve Contractor from liability under this indemnification and hold harmless clause. This indemnification and hold harmless clause shall apply to any damages or claims for damages whether or not such insurance policies shall have been determined to apply. By execution of this Agreement, Contractor acknowledges and agrees to the provisions of this Section and that it is a material element of consideration.
11.2 Excuse for Performance. The City and Contractor (collectively "Parties") shall be excused from performing their respective obligations hereunder and from any obligation to pay liquidated damages if they are prevented from so performing by reason of earthquakes, fires, floods, war, civil insurrection, riots, strikes, freight embargoes, pandemics, and other similar catastrophic events which are beyond the control of and not the fault of the party claiming excuse from performance hereunder, and are not reasonably foreseeable or discoverable through due diligence. Notwithstanding the foregoing, adverse market conditions or the inability to obtain financing shall not constitute an excuse from performance. The Party claiming excuse from performance shall, within five (5) calendar days after such Party has notice of such cause, give the other Party notice of the facts constituting such cause and asserting its claim to excuse under this Section. If either Party validly exercises its rights under this Section, the Parties hereby waive any claim against each other for any damages sustained thereby. The partial or complete interruption or discontinuance of Contractor's services caused by one (1) or more of the events described in this section shall not constitute a default by Contractor under this contract. Notwithstanding the foregoing, however, if Contractor is excused from performing its obligations hereunder for any of the causes listed in this section for a period of thirty (30) calendar days or more, City shall nevertheless have the righ
Contractor. In no event shall an excuse of performance delay cumulatively exceed one hundred and eighty (180) days.
11.3 PERS Indemnification. In the event that Contractor or any employee, agent, or subcontractor of Contractor providing Services under this Agreement is determined by a court of competent jurisdiction of enrollment in PERS as an
employee of City, Contractor shall indemnify, defend, and hold harmless City for the payment of any and all employee and/or employer contributions for PERS benefits on behalf of Contractor or its employees, agents, or subcontractors, as well as for the payment of any penalties and interest on such contributions, to enforce this Section.
11.4 No Limitation of Liability. The indemnities set forth in this Section shall not be limited by the insurance requirements set forth in this Agreement.
11. Compliance with All Applicable Laws.
(A) Contractor shall comply with all applicable local, state and federal laws, regulations and ordinances in the performance of this Agreement.
physical or mental handicap or disability, medical condition, marital status, sex, or sexual orientation, against any employee, applicant for employment, subcontractor, bidder for a subcontract, or participant in, recipient 312
Part IV, Page 5
of, or applicant for any services or programs provided by Contractor under this Agreement. Contractor shall comply with all applicable federal, state, and local laws, policies, rules, and requirements related to equal opportunity and nondiscrimination in employment, contracting, and the provision of any services that are the subject of this Agreement, including but not limited to the satisfaction of any positive obligations required of Contractor thereby. Contractor shall include the provisions of this section in any subcontract approved by the City.
(C) Contractor shall comply with the requirements of the Secretary of Labor and the latest amendments to:
Executive Orders 11246 as amended by Executive Order 11375 , as supplemented in Department of Labor AntiDepartment of Labor regulations (29 C.F.R. part 3); Section 3 of the Housing and Urban Development Act of 1968 (12 U.S.C. §§ 1701 et seq.); Title VI of the Civil Rights Act of 1964 (42 U.S.C. §§ 2000); Section 109 of Title I of the Housing and Community Development Act of 1974 (42 U.S.C. §§ 5301 et seq.); the Age Discrimination Act of 1975 (42 U.S.C. §§ 6101 et seq.); and Section 504 of the Rehabilitation Act of 1973 (29 U.S.C. §§ 701 et seq.)
(D) Contractor shall comply with all applicable rules, regulations, and standards issued by the California Air Resources Board (CARB), including but not limited to regulations governing vehicular emissions, off-road diesel equipment, and portable engines. Contractor shall furnish certificates of compliance with CARB regulations for all applicable equipment utilized in the performance of the Work upon request by the City. (E) Pursuant to California Labor Code Section 6500, Contractor shall possess a valid Construction Activity Permit for excavations or trenches that are five (5) feet or deeper into which a person is required to descend, and shall maintain such permit for the life of the contract. Furthermore, pursuant to California Labor Code Section 6705, prior to commencing excavation of any trench five (5) feet or more in depth, Contractor shall submit to the Engineer a detailed shoring and bracing plan designed by a registered civil or structural engineer at least five (5) working days prior to the commencement of excavation.
12. AMENDMENTS. No modification or amendment of this Agreement is effective unless made in writing and signed by both the City and Contractor.
13. ASSIGNMENT AND SUBCONTRACTING. Contractor shall not assign or transfer any interest in this Agreement without the prior written consent of the City. Any substitution of subcontractors shall comply with the Subletting and Subcontracting Fair Practices Act, Public Contract Code Section 4100 et seq.
14. Independent Contractor. It is understood and agreed that this Agreement is not a contract of employment and does not create an employer-employee relationship between the City and Contractor. At all times, Contractor shall be an independent contractor and Contractor is not authorized to bind the City to any contracts or other obligations without the express written consent of the City.
15. Excavations. In accordance with Public Contracts Code Section 7104, Contractor shall promptly notify the City in writing of discovery of any material Contractor believes may be hazardous waste as defined in Section 25117 of the Health and Safety Code or of any subsurface or latent physical conditions at the site of any unusual nature differing materially from those generally inherent in the work described in Exhibit A. Upon receipt of such communication, City shall promptly investigate the conditions and if conditions do materially differ, shall issue a change order providing for additional time or payment of additional costs.
16. Relocation of Utilities. In the event that the completion of the services described in Exhibit A requires the removal or protection of main or trunk line public utility facilities, the City shall be responsible for removal and protection of such public utilities pursuant to Government Code Section 4215.
17. Insurance. Prior to beginning the Work and continuing throughout the term of this Agreement, Contractor with certificates of insurance evidencing that Contractor has obtained and maintains insurance in the following amounts:
maintained with a limit of no less than ONE MILLION DOLLARS ($1,000,000) per accident for bodily injury or disease.
B. Commercial General Liability and Property Damage Insurance in an amount not less than TWO MILLION DOLLARS ($2,000,000) combined single limit per occurrence, FIVE MILLION DOLLARS ($5,000,000) annual aggregate, for bodily injury, property damage, products, completed operations and contractual liability coverage. The policy shall also include coverage for liability arising out of the use and operation of 313
Part IV, Page 6
any City-owned or City-furnished equipment used or operated by the Contractor, its personnel, agents or subcontractors.
C. Comprehensive automobile insurance in an amount not less than ONE MILLION DOLLARS ($1,000,000) per occurrence for bodily injury and property damage including coverage for owned and non-owned vehicles.
All insurance policies shall be written on an occurrence basis and shall name the City Indemnitees as additional insureds. The certificates shall contain a statement of obligation on the part of the carrier to notify the City of any material change, cancellation, termination or non-renewal of the coverage at least thirty (30) days in advance of the effective date of any such material change, cancellation, termination or non-renewal. -insured retention that must be paid by a named
self-insured retention by others, including additional insureds or insurers do not serve to satisfy the selfinsured retention, such provisions must be modified by special endorsement so as to not apply to the additional insured coverage required by this agreement so as to not prevent any of the parties to this agreement from satisfying or paying the self-insured retention required to be paid as a precondition to the include any self-insured retention and also must disclose the deductible.
18. General Warranties and Guarantee. Contractor warrants that: (A) All Work, Products and/or Services are as described in this Agreement, including any exhibits incorporated, conform to all drawings, samples, descriptions and specifications; (B) All Work, Products and/or Services delivered are new and of good merchantable quality, free from material defects of workmanship and fit for the purpose for which sold or provided; (C) Contractor has good title to all Products delivered and all Products delivered are free from liens and other encumbrances; and (D) Contractor's Work will be in strict conformity with all applicable local, state, and federal laws. For purposes of this warranty, any parts not meeting the foregoing quality shall be deemed defective.
Contractor shall guarantee the Work to be free of defects in material and workmanship for a period of one Guarantee, Contractor agrees to make, at Con
necessary by defects in material or workmanship which become evident within the one-year guarantee required by the City for this Agreement.
19. Licenses. Contractor represents and warrants that Contractor possesses all licenses, permits, and qualifications legally required for the performance of the Work, including but not limited to a business license from the City
and expense, maintain all such licenses, permits and qualifications in full force and effect throughout the term of this Agreement. Contractor shall hold, and shall maintain in good standing throughout the term of this
20. Damage to City Facilities and Site Safety. Damage to City or public facilities or private property caused by the Contractor or by its subcontractors during performance of the Work shall be repaired and/or replaced in kind at no cost to the City. The worksite shall be kept clean and free of hazards at all times during installation.
After work is completed at the site, Contractor shall clean the surrounding area to the condition prior to performance of the Work.
21. Final Inspection and Work Acceptance. All Work shall be subject to final inspection and acceptance or rejection by the City. Contractor shall guarantee the Work to be free of defects in material and workmanship
22. MISCELLANEOUS PROVISIONS.
23.1Dispute Resolution. Prior to initiating litigation in a court of competent jurisdiction, both Contractor and City shall undergo alternative dispute procedures as outlined in Public Contract Code Section 20104, et seq. The Parties also expressly agree that such procedures are incorporated as though fully set forth in this Agreement.
23.2 Prevailing Party. In the event that either party to this Agreement commences any legal action or proceeding (including but not limited to arbitration) to interpret the terms of this Agreement, the prevailing party in such a proceeding shall be entitled to recover its reason associated with that legal action or proceeding.
23.3 Termination. City may terminate or suspend this Agreement at any time and without cause upon 314
Part IV, Page 7
written notification to Contractor. Upon receipt of notice of termination or suspension, Contractor shall be in addition to all other remedies available under law to the City.
23.4 Successors. This Agreement shall bind and insure to the heirs, devisees, assignees, and successors in interest of Contractor and to the successors in interest of Contractor in the same manner as if such parties had been expressly named herein. All times stated herein or in the contract documents are of the essence hereof. As used in this instrument, the singular includes the plural, and the masculine includes the feminine and the neuter. This Agreement may create a possessory interest subject to property taxation, and Contractor may be subject to the payment of property taxes levied on such interest.
23.5 Contract Administration. This Agreement shall be administered by Audrey Cray ("Contract Administrator"). All correspondence shall be directed to or through the Contract Administrator or his or her designee.
23.6 Notices. Any written notice to Consultant shall be sent to:
_________________________
_________________________
_________________________
Any written notice to City shall be sent to:
City of Sand City
Department of Public Works
1 Pendergrass Way
Sand City, CA 93955
23.7 IRS Form W-9. Contractor shall complete and submit Internal Revenue Service Form W-9 to the this requirement.
23.8 . If a Party to this Agreement brings any action, including an action for declaratory relief, to enforce or interpret the provisions of this Agreement, the prevailing Party shall be entitled which that Party may be entitled. The
court may set such fees in the same action or in a separate action brought for that purpose.
23.9 No Implied Waiver of Breach. The waiver of any breach of a specific provision of this Agreement does not constitute a waiver of any other breach of that term or any other term of this Agreement.
23.10 Entire Agreement. This Agreement represents the entire and integrated agreement between the Parties. This Agreement may be modified or amended only by a subsequent written agreement signed by both Parties.
23.11 Non-Liability of Officials, Employees and Agents. No officer, official, employee or agent of City shall be personally liable to Contractor in the event of any default or breach by City or for any amount which may become due to Contractor pursuant to this Agreement.
23.12 Survival. The obligations of this Agreement, which by their nature would continue beyond the term or expiration of this Agreement, including without limitation obligations regarding indemnification shall survive the term or expiration of this Agreement.
23.13 Contract Bonds. Prior to execution of this Agreement, Contractor shall furnish to City: (i) a Performance Bond in an amount equal to one hundred percent (100%) of the Contract amount, and (ii) a Payment (Labor and Materials) Bond in an amount equal to one hundred percent (100%) of the Contract amount, each in a form acceptable to City and in accordance with Public Contract Code Section 9550 et seq. Contractor may substitute securities for any bond as permitted by Public Contract Code Section 22300. Contractor shall maintain the Performance Bond in effect throughout the guarantee period described in Section 18, or substitute a bond equal to twenty percent (20%) of the total Contract amount, whichever is greater.
23.14 Liquidated Damages. If the Work is not completed within the time specified in Section 3, Time of Performance, as such time may be extended in writing by the City, Contractor shall pay City 315
Part IV, Page 8
liquidated damages of $4,200 for each calendar day of delay beyond the time specified, or the actual damages sustained, whichever is greater. City may deduct such liquidated damages from any amounts due or to become due to Contractor. The Parties agree tha the event of such delay would be impracticable or extremely difficult to ascertain, and that this liquidated damages provision represents a reasonable estimate of such damages.
23.15 Local Hiring Requirement. Contractor shall make good-faith efforts to comply with Sand City Municipal Code Section 12.20.030 et seq. to hire qualified individuals who are residents of the Monterey Bay Area (Monterey, Santa Cruz, and San Benito Counties) in sufficient numbers so that subcontractor work force and measured in labor work hours, is comprised of Monterey Bay Area residents. Contractor shall require the same commitment of all subcontractors.
23. The Sand City City Council awarded this contract on ____________,20XX by Resolution _____ C.S.
24. This Agreement shall consist of this Public Works Contract document and the following items, all of which are on file in the office of the City Clerk and are incorporated herein and made a part hereof by reference:
A. Plans and Specifications G. Debarment and Suspension Certification B. Accepted Proposal H. Certification(s) of Good Faith Effort to Hire Local Residents C. Performance Bond I. Subcontractor's List
D. Payment Bond (Labor and Materials) J. Acknowledgement of Addenda E. Certificates of Compliance with CARB
Regulations
K. Certification of Worker's Compensation Insurance
F. Non-Collusion Declaration L. Declaration of Bidder
IN WITNESS WHEREOF, said Contractor and said City have hereunto set their hands, all on the day and year first above written.
CITY OF SAND CITY
_______________________________________
Vibeke Norgaard, City Manager Date
ATTEST:
By:_____________________ Date:___________
Kerry Lindstrom, City Clerk
By:_____________________ Date:___________
Audrey Cray, Risk Manager
APPROVED AS TO FORM
By:_____________________ Date:___________
Adam Lindgren, City Attorney
316
Part IV, Page 9
FY 25/26 PAVEMENT MAINTENANCE AND REHABILITATION (M+R) PROJECT PART IV: SPECIAL PROVISIONS
GENERAL
The work, in general, consists of: the maintenance and rehabilitation of street pavement and associated infrastructure, including the demolition and/or removal of concrete curbs, gutters and sidewalks, concrete planters, concrete crosswalks, curb ramps, cross gutters and spandrels, trees and landscaping, and the construction of new concrete curbs, gutters, and sidewalks, asphalt concrete dikes, asphalt pavement rehabilitation including aggregate base, stamped asphalt concrete crosswalks, storm drain catch basins, manholes, and pipes, minor sanitary sewer improvements, utility cover adjustments, utility cover relocations, signing and striping.
PLANS AND SPECIFICATIONS
A component in one Contract part applies as if appearing in each. The parts are complementary and describe and provide for a complete work. The work embraced herein shall be done in accordance with the appropriate provisions of the Standard Specifications insofar as the same may apply, and in accordance with the specifications and plans. In case of conflict between the Standard Specifications, Standard Plans, and these Special Provisions and the Plans, the order of precedence shall be as follows:
Special Provisions shall take precedence over Plans and the Plans shall take precedence over Standard Specifications and Standard Plans. These Special Provisions shall also take precedence over conflicting portions of the "General Provisions, Part III" of these project specifications.
ADMINISTRATIVE WORKFLOW
Notwithstanding any reference to Caltrans Standard Specifications regarding dispute resolution, progress payments, or administrative submittals:
Claims Resolution: Any claim by Contractor for a time extension, for payment of money not otherwise provided for, or for payment of a disputed amount, shall first be resolved through the mandatory claim, response, and meet-and-confer/mediation process set forth in Public Contract Code Section 9204, which applies to all such claims regardless of amount and is set forth in full in the "Resolution of Construction Claims" section below. For claims of $375,000 or less that remain unresolved after that process, subsequent proceedings shall be governed by Public Contract Code Section 20104 et seq., including referral to judicial arbitration as provided therein. Nothing in this section waives or diminishes the City's or Contractor's rights or obligations under Public Contract Code Section 9204.
Progress Payments: Monthly progress estimates and retention withholdings shall be administered directly through the Sand City Engineer, utilizing simplified local invoicing forms rather than complex state highway data systems.
CARB CERTIFICATES OF REPORTED COMPLIANCE (NEW REQUIREMENT) The California Air Resources Board ("CARB") has approved amendments to the In-Use Off-Road Diesel-Fueled Fleet regulations ("Regulations") which impact construction contractors and subcontractors and will apply to public works projects awarded after January 1, 2024. For a project involving the use of diesel-fueled vehicles subject to these Regulations, the apparent low bidder shall obtain and submit to the City, within fourteen (14) calendar days after the Bid Opening Date, copies of valid Certificates of Reported Compliance ("CRC") for all subject vehicles (both the bidder's and its listed subcontractors') that will be used on the Project. The CRCs, or a detailed explanation of any exemption from the CRCs, must be submitted within this period so that the bidder's responsibility can be evaluated by the City prior to award. Failure to timely submit the required CRCs, or a detailed explanation of any exemption from the Regulations, may render the bidder non-responsible, in which case the City may reject the bid and proceed to evaluate the next lowest responsive, responsible bidder.
The In-Use Off-Road Diesel-Fueled Fleets regulations apply to all self-propelled off-road diesel vehicles 25 horsepower or greater and most two-engine diesel vehicles (except on-road two-engine sweepers) owned and operated in California. The Regulations cover a wide range of vehicle types ranging from small skid steer loaders 317
Part IV, Page 10
used in small landscaping jobs to bulldozers, forklifts, cranes, and excavators, and includes vehicles/fleets that are rented or leased.
CARB website. All CRCs are available for download starting March 1 of each year and until February 28 of the following year and are automatically updated by CARB if a Contractor is in compliance. The City is required to retain CRCs for three years after the project is complete, and the CRCs are subject to CARB review upon five calendar days' notice.
Further information regarding the Regulations and this new requirement may be found on the California Air Resources Board website at https://ww2.arb.ca.gov/our-work/programs/use-road-diesel-fueled-fleets-regulation.
CONTRACT BONDS
For Bid Bond requirements, see Part I, Bid Bond, of these Specifications.
The Contractor, at the time of signing and executing the contract, shall execute and file with the City a performance bond to the satisfaction and approval of said City, in a sum of not less than one hundred percent (100%) of the amount of the contract conditional upon the faithful performance of the contract. For additional information, see Guarantees elsewhere in these specifications.
The Contractor, at the time of signing and executing any contract in excess of twenty-five thousand dollars ($25,000), shall execute and file with the City a payment bond (public works labor and materials bond) to the satisfaction and approval of said City, in a sum of one hundred percent (100%) of the amount of the contract in accordance with Civil Code §9550 et seq.
All bonds must be signed by principal(s) of the Contractor. All required signatures on the bond must be notarized. -in-Fact must sign all copies of the bonds, impress or affix the corporate seal on each copy, and provide one current copy of the Power of Attorney for the Attorney-in-fact.
The surety shall be an admitted carrier in California with a valid surety license and possess a minimum rating from A. M. Best Company of A-VII. The Surety and /or co-sureties must be listed as an acceptable surety on federal bonds by the United States Department of the Treasury, subject to the maximum amount shown in the listing. If co-sureties are used, their bonds shall be on a joint and several basis.
Please refer to the separate bond forms on PlanetBids.
Notwithstanding the above, the Contractor may substitute adequate securities for any bond called for under the provisions of these Specifications as set forth in Public Contracts Code Section 22300. Alternate security substitutions shall be submitted to the City no later than ten (10) days after written notice that a contract has been awarded to the contractor to allow processing and escrow agreement for in lieu security.
The Contractor shall submit the contract with their signature affixed thereto, required bonds or alternate security and evidence of insurance that conforms to the contract within fifteen (15) calendar days after written notice that a contract has been awarded to them.
The Contractor shall maintain the performance bond in full force and effect during the guarantee period for the performance bond for a similar bond in the amount of twenty percent (20%) of the total contract amount, including adjustments, or the original performance bond, whichever is greater.
TIME LIMITS
Within fifteen (15) calendar days after written notice that a contract has been awarded (Notice of Award), the Contractor shall submit two (2) signed original contracts, required bonds or alternative security, evidence of insurance that conforms to the contract, and City of Sand City Business License or evidence of application for said license.
The Contractor shall diligently prosecute the contract to completion on or before the expiration of 90 calendar days from the effective date of the Notice to Proceed.
318
Part IV, Page 11
LICENSES AND PERMITS
Prior to the execution of any contractual agreements, the successful Bidder shall obtain a City of Sand City Business License, and all applicable permits for construction.
City permits shall be issued at no charge.
Contractor shall be required to obtain and hold an appropriate Permit (such as an Encroachment Permit) from the Engineering Department and/or a Building Permit from the Building Department. Contractor shall provide a copy of the completed permit(s) to the Engineering Department no later than three (3) days prior to the start of construction.
The permit application fee(s) shall be waived. Where applicable, the City shall submit permit applications.
SITE INSPECTION
It shall be the Contractor's responsibility to inspect the site and become thoroughly familiar with all aspects of the work to be done.
The submission of a bid shall be conclusive evidence that the Bidder has investigated the site and is thoroughly satisfied as to the conditions to be encountered, as to the character, quality, and scope of the work to be performed; the quantity of materials to be furnished; and as to all the requirements of these specifications.
It shall be the Contractor's responsibility to be aware of surface and subsurface drainage conditions that may exist at the site. The Contractor is further responsible for work necessary to rectify any resulting drainage problems; labor, materials, equipment, and incidentals necessary to achieve the solution shall be borne by the Contractor.
SUBMITTALS
The review of submittals and approval thereof by the City does not relieve the Contractor from compliance with the requirements and intentions of the plans and specifications to which the submittals pertain.
Submittal Format:
1. construction manager. A minimum of two (2) copies shall be submitted unless otherwise directed. Submittal submission may be done in pdf form via email.
2. All submittals shall have a cover sheet containing the following:
a. Submittal date, submittal number and submittal revision number (as applicable), b. City project name,
3. Each submittal item shall clearly identify the specification section(s) and paragraph(s) for with the submittal item pertains to.
4. Contractor is not guaranteed a specific review time period. If Contractor requires a quick submittal turnaround of specific submittal items, Contractor must indicate which submittal items require a quick turnaround by attaching a memo to the submittal indicating such and the requested turnaround period. The City shall make every effort to meet the requested review period.
5. Contractor shall place orders for all materials or equipment in time to prevent any delays to the construction schedule or project completion. If any materials or equipment are not ordered in a timely fashion, any additional charges made by equipment manufacturers and/or suppliers to complete the manufacturer and/or delivery in time to meet the construction schedule or project completion, together with any special handling charges shall be borne by the Contractor.
Submittal Content and Product Data:
1. Contractor shall review and accept submittals prior to submission. 319
Part IV, Page 12
2. Submittals shall contain all required information such as shop drawings, product data, etc.
3. Each submittal item shall be identified by manufacturer, brand name, trade name, model number, size, rating and additional information as is necessary to properly identify and verify the materials and equipment. The sufficient.
4. Where possible, submittal information shall be limited to the specific item being submitted. In the event multiple materials or equipment are described in one submittal, Contractor shall clearly identify the pertinent information being submitted on.
5. Accessories, controls, finish, etc. not required to be submitted or identified with the submittal shall be furnished and installed as specified.
CONSTRUCTION SURVEYS
The City shall provide construction staking and survey control for this project. The City's Surveyor, who performed the original base survey, will furnish all construction stakes and marks necessary to establish the lines and grades required for the completion of the work as shown on the plans and specifications. The Contractor shall give at least seventy-two (72) hours' written notice to the Construction Manager when staking is required and shall have at least and additional information.
The City Surveyor shall also be responsible for identifying, referencing, protecting, perpetuating, resetting, and/or replacing existing survey monuments that may be disturbed or destroyed by construction activities, including preparation and filing of any required Corner Records or Records of Survey. The Contractor shall notify the City Surveyor immediately upon discovering any monument that may be affected by construction operations and shall not disturb any survey monument without prior coordination.
All distances and measurements are given and will be made in a horizontal plane. Grades will be given from the top of stakes or nails, unless otherwise noted.
Finished surfaces in all cases shall conform to the lines, grades, cross-sections and dimensions shown on the approved plans and specifications. Deviations from the approved plans and specifications must be approved by the Engineer and authorized in writing.
Staking will include one set of stakes or marks at about twenty-five feet on center (25' O/C) which shall be used for excavation, filling, and alignment of improvements.
The Contractor shall preserve all stakes and points set for lines, grades, or measurement of the work in their proper places until authorized to remove them by the Engineer. All expenses incurred in replacing stakes that have been removed without proper authority, or damaged due to the Contractor's operations, shall be paid by the Contractor.
The City shall be given the opportunity to check forms for line and grade prior to any concrete being placed.
Should the Contractor request staking beyond that described above, or re-staking due to the Contractor's failure to preserve stakes, such additional staking shall be performed by the City's Surveyor at the Contractor's expense, and the cost shall be deducted from monies due the Contractor.
PROTECTION OF PRIVATE PROPERTY
Private property grounds and facilities, if damaged or removed because of the Contractor's operations, shall be restored or replaced to same or better than the original condition and located in the same position and alignment as is reasonably possible. Contractor shall comply with the applicable portions of Section 5- - -
CONSTRUCTION QUALITY CONTROL
Definitions
320
Part IV, Page 13
Quality Management (QM) - All control and assurance activities instituted to achieve the product quality established by the contract requirements.
Contractor Quality Control (CQC) - The construction contractor's system to manage, control, and document contractor's, suppliers', and subcontractor's activities to comply with contract requirements.
Contractor Responsibility
General: The Contractor shall establish and maintain an effective quality control system in compliance with the Plans and Specifications. The quality control system shall consist of plans, procedures, and organization necessary to provide materials, equipment, workmanship, fabrication, construction, and operations which comply with contract requirements. The system shall cover construction operations both onsite and offsite, and shall be keyed to the proposed construction sequence.
The Quality Control Plan
Quality Control Plans and Procedures.
The Contractor will be required to prepare a Quality Control Plan. This plan shall include, as a minimum, the following:
1. A description of the quality control procedures, including a chart showing lines of authority and acknowledgement that the Contractor shall implement the control system for all aspects of the work specified and shall report to the project manager or someone higher in the Contractor's organization.
2. The name, qualifications, duties, responsibilities, and authorities of each person assigned a QC function.
3. A copy of the letter to the Engineer signed by an authorized official of the firm which describes the responsibilities and delegates the authority to implement the QC plan shall be furnished.
4. Procedure for scheduling and managing submittals, including those of subcontractors, offsite fabricators, suppliers, and purchasing agents.
5. Control testing procedures for each specific case. Note that in the case of federally-funded projects, QA/QC testing must be performed by the city by a Caltrans-certified lab.
6. Reporting procedures including proposed reporting formats.
QC Plan Implementation
1. Preconstruction Conference. During the pre-construction conference, a mutual understanding of the CQC system details shall be developed, including the forms for recording the CQC operations, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's management with the Engineer's inspection. Minutes of the conference shall be prepared by City staff, and be signed by both the Contractor and the Engineer. The minutes shall become a part of the contract file.
There may also be occasions when subsequent conferences will be called to reconfirm mutual understandings.
2. General. After issuance of the Notice to Proceed, and prior to the start of construction, the Contractor shall furnish, for acceptance by the Engineer, the Contractor Quality Control (CQC) Plan with which he proposes to implement the requirements of Contract Clause entitled "Construction Quality Control". The plan shall identify personnel, procedures, instructions, records, and forms to be used. If the Contractor fails to submit 321
Part IV, Page 14
an acceptable QC plan within the time herein prescribed, the Engineer may refuse to allow construction to start if an acceptable interim plan is not furnished.
3. Control of Materials, Tests, and Inspections. As listed below, and noted elsewhere in the specifications but not limited to the following items, the Quality Control Plan will include the dates for the Contractor to furnish certificates for product, or product test compliance, shop drawings or catalog cuts and requests for inspection or review.
a. Tests and Inspections:
Sub-grade compaction
Aggregate placement and compaction
Forms Placement
Trench backfill and bedding
Reinforcing bar placement
Fill Material (if applicable)
Pipe placement
Lateral Connections
High Strength Fasteners and Bolts
Epoxy
b. Materials and Materials Certification:
Aggregate Base
Hot Mix Asphalt/Asphalt Concrete
Concrete
Catch Basin and Manhole Casting
Reinforcing Bar
Pipe Material
Trench backfill material
Lumber
RC pipe
Slurry backfill
c. Daily Reports
The Contractor shall provide copies of daily reports which describe the work performed, weather conditions, personnel and equipment on site, and quality control activities performed.
The Contractor will not be paid for work prior to Engineer reviewing and accepting daily reports for the period of time payment is requested.
4. Acceptance of Plan. Acceptance of the Contractor's plan is required prior to the start of construction.
Acceptance is conditional and will be predicated on satisfactory performance during the construction. The Engineer reserves the right to require the Contractor to make changes in the CQC plan and operations as necessary to obtain the quality specified.
5. Notification of Changes. After acceptance of the QC plan, the Contractor shall notify the Engineer in writing of any proposed change. Proposed changes are subject to acceptance by the Engineer.
6. Testing and Certification. The Contractor shall pay for all tests and inspections as required by the Plans and Specifications. The Contractor shall furnish certification of materials being used, upon request of the Engineer, without additional charge.
322
Part IV, Page 15
GUARANTEE
Materials and labor guarantees shall be per Part III of these specifications. All warranty shall be to the satisfaction of the City. Final payment will not be released without submission of warrantees. Any materials installed in Army Buildings (with City of Sand City approval) shall issue warranty (if exists) to the United States Army prior to formal acceptance of work, and deliver to the City of Sand City, Engineering Department.
REGULATIONS
The Contractor and all subcontractors shall give all notices and comply with all laws, ordinances, rules, and regulations applicable to the work, safety and hiring/employment practices. Nothing in the Plans and Specifications shall be construed to permit work not conforming to the regulations and codes set forth herein which include, but are not limited to the following:
1. Americans with Disabilities Act (ADA) accessibility and employment standards. In the event of conflicting federal and state standards, the standard that provides greater access will take precedence.
2. Sand City Municipal Code, as amended,
3. California Building Code, latest edition as adopted by the City of Sand City,
4. California Electrical Code, latest edition as adopted by the City of Sand City,
5. California Mechanical Code, latest edition as adopted by the City of Sand City,
6. California Plumbing Code, latest edition as adopted by the City of Sand City,
7. California Green Building Standards Code, latest edition as adopted by the City of Sand City,
8. California Historic Building Code, latest edition as adopted by the City of Sand City,
9. California Occupational Safety and Health Administrative Code, latest edition,
10. California Government Code Section 4216, Protection of Underground Infrastructure,
11. National Fire Protection Associations NFPA 1 Fire Code, latest edition,
12. The California Labor Code,
13. Federal Water Pollution Control Act (Clean Water Act), and,
14. Porter-Cologne Water Quality Control Act (California Water Code Section 13000 et seq.).
15. Title 13, California Code of Regulations, Sections 2449, 2449.1, and 2449.2.
PUBLIC SAFETY AND PROTECTION OF THE WORK
The Contractor shall furnish, erect and maintain such fences, barricades, guards, lights and other devices as are necessary to prevent accidents and avoid damage to the construction work or injury to the public. No separate payment shall be made for such work. If in the opinion of the Engineer, adequate barricades or warning devices are not maintained by the Contractor, the City may furnish and erect same and charge the Contractor therefore. Attention is directed to Sections 7-l.03 "Public Convenience" and 7-l.04, "Public Safety", of the Standard Specifications published by the State of California Department of Transportation.
PRE-CONSTRUCTION CONFERENCE
Prior to the beginning of any work on this project, a pre-construction conference shall be held at the City Hall, 1 Pendergrass Way, Sand City, CA. The date and time of this conference shall be established by the Contractor contacting that office at 831-394-3054 not less than forty-eight (48) hours in advance of the meeting date and time. 323
Part IV, Page 16
An itemized list of materials and equipment the Contractor proposes to use on the project shall be submitted to the City prior to or during the preconstruction conference.
A preliminary project timeline shall be submitted to the City prior to or during the preconstruction conference.
LIQUIDATED DAMAGES
Unless stated otherwise in the Specifications, it is agreed by the parties to the contract that in case all the work called for under the contract is not completed before or upon the expiration or the time limit as set forth in these specifications, damage will be sustained by the City of Sand City and that it is and will be difficult or impossible to ascertain and determine the actual damage which the City will sustain in the event of and by reason of such delay; and it is therefore agreed that the Contractor will pay to the City of Sand City the sum of four thousand two hundred dollars ($4,200) per day for each and every day's delay beyond the time prescribed to complete the work or the actual damages ascertained, whichever will be greater; and the Contractor agrees to pay such liquidated damages as herein provided; and in case the same are not paid, agrees that the City of Sand City may deduct the amount thereof from any money due or that may become due the Contractor under the contract.
It is further agreed that, in case the work called for under the contract is not finished and completed in all parts and requirements within the time specified, the City shall have the right to extend the time for completion of the contract or not, as may seem best to serve the interest of the City; and if it decides to extend the time limit for the completion of the contract, it shall further have the right to charge to the Contractor, their heirs, assigns or sureties, and to deduct from the final payment of the work, all or any part, as it may deem proper, of the actual cost of engineering, inspection, superintendence and other overhead expenses during the period of such extension, except that the cost of final measurements and preparation of final estimate shall not be included in such charges.
NOTICES
All notices which the City or the Contractor may be required, or may desire, to serve on the other, shall be effective only if delivered by personal delivery or by postage prepaid, First Class Certified Return Receipt Requested United States Mail, addressed to the City or the Contractor at their respective address set forth in the Declaration of Bidder, or such other address(es) as either the City or the Contractor may designate from time to time by written notice to the other in conformity with the provisions hereof. In the event of personal delivery, such notices shall be deemed effective upon delivery, provided that such personal delivery requires a signed receipt by the recipient acknowledging delivery of the same. In the event of mailed notices, such notice shall be deemed effective on the third working day after deposit in the mail.
CONSTRUCTION PROCEDURE
An outline of the proposed construction procedure shall be submitted by the Contractor to the Engineer for review and shall obtain their approval before beginning work. The Engineer will be especially interested in:
1. Minimizing any interruption to use of driveways (no more than 4-hour interruption). Any interruption more than 4 hours shall be prearranged with the Engineer. Residence occupant shall be notified with a written notice a minimum of five (5) business days in advance.
2. Adjacent property owners shall be notified with a written notice a minimum of three (3) business days in advance of any construction impacts.
3. Minimizing any interruption to building operations and parking lots. Contractor shall notify the Engineer a minimum of one week in advance of any interruptions to building operations and parking lots.
4. Minimizing any hazard to the general public.
5. Proper handling of hazardous materials.
324
Part IV, Page 17
6. All work will occur between 7 am and 7 pm unless otherwise approved in writing.
7. Contractor shall notify the Engineer a minimum of twenty-four (24) hours in advance of concrete placement for checking and acceptance of forms by the Engineer prior to concrete placement. Mitigation of concrete placement done without acceptance of forms by the Engineer prior to concrete placement shall be the sole responsibility of the Contractor. The costs of such mitigation shall be borne by the Contractor.
Traffic control requirements cited elsewhere in these Specifications must be considered in the construction procedure submitted to the Engineer.
TRAFFIC CONTROL
Pursuant to the authority contained in the California Vehicle Code, Section 591, the City has determined that within those areas that are within the limits of the project and are open to traffic, the Contractor shall comply with all the requirements set forth in Divisions 11, 12, 13, 14 and 15 of the Vehicle Code. In accordance with the statement in Vehicle Code Section 591, this section shall not relieve the Contractor or any person from the duty of exercising due care. The Contractor shall take all necessary precautions for safe operation of the Contractor's equipment and the protection of the public from injury and damage from the Contractor's equipment.
Traffic control shall conform to the provisions of Section 12, "Temporary Traffic Control of the Standard Specifications and the most current version of the California Manual on Uniform Traffic Control Devices (CA MUTCD) as adopted by Caltrans.
A Traffic Control Plan (TCP) shall be submitted to the Engineer for approval at least 10 workings days prior to scheduled construction and must be applicable to existing site conditions. When site specific TCPs are used the plan must be to scale and include a scale, north arrow, and street names. If plans are developed by a licensed engineer, the plans shall be stamped, signed, and dated by the professional civil or traffic engineer in accordance with the California Professional Engineers Act. When typical applications from Chapter 6H of the MUTCD are used the Engineer may approve their use with or without additional conditions. The Engineer has 10 days to respond and must approve the traffic control plan before work can begin. The City is not responsible for any delays resulting from rejected TCPs that do not meet the requirements of the MUTCD and these Specifications.
Contractor shall notify all emergency services, affected residences, affected businesses, and the Engineering Department (831) 394-3054 a minimum of five (5) business days in advance as to proposed closures and alternate routes available.
The following shall be incorporated into the Traffic Control Plan:
1. Two (2) travel lanes shall be open during non-working hours.
2. At least one (1) travel lane shall remain open during working hours. Flag persons or other appropriate traffic control devices as approved by the Engineer shall be used during periods of one-way travel.
3. Access to driveways shall be left open unless work is actually being performed in areas fronting the driveway.
All driveways shall be accessible during non-working hours. See Construction Procedure elsewhere in these specifications.
4. No trench shall be left open during non-working hours.
5. Parking restrictions will be acceptable when and where needed. (All require prior approval of the Engineer).
The following requirements apply to Traffic Control Plans:
1. All Traffic Control Plans shall follow the CA MUTCD Chapter 6. Examples may be found at:
325
Part IV, Page 18
https://dot.ca.gov/-/media/dot-media/programs/safety-programs/documents/ca-mutcd/rev-5/camutcd2014- rev5-a11y.pdf
2. The contractor shall submit a TCP using legible lettering. Show location and dimensions of the work zone, lanes, tapers, parking and any staging areas.
3. Label streets and proposed traffic control area. Show all nearby streets with street names to assure proper orientation.
4. Show all affected sidewalks, crosswalks, bike lanes, driveways and intersections in the construction work zone including areas affected by taper transition.
5. If a sidewalk, crosswalk or path is obstructed or partially obstructed, contractor must then submit an ADA compliant pedestrian traffic control plan in accordance with the CA MUTCD chapter 6D and the Public Rightsof-Way Accessibility Guidelines (PROWAG). Please refer to: https://dot.ca.gov/-/media/dotmedia/programs/safety-programs/documents/ca-mutcd/rev-5/camutcd2014-part6-rev5.pdf
6. Label all taper lengths and widths, delineator spacing and sign spacing. Indicate location of construction signs, barricades and delineators.
7. posted seventy-two (72) hours prior to commencing work.
8. Indicate on the TCP the duration of the construction work, including dates and times.
9. 10.
are in compliance with the current version of the CA MUTCD as adopted by Caltrans.
Traffic Control Plans shall contain the following notes:
1. Minimum width of temporary traffic lanes is ten (10) feet clear (from delineator or cone base, not center).
Minimum width at truck routes is eleven (11) feet clear.
2. The City Traffic Engineer or their representative has the authority to make any field changes to assure public safety.
3. All traffic control devices shall be removed from view when not in use. Signs shall not be facing traffic when not in use.
4. Spacing of channelizing devices shall not exceed twenty-five (25) feet.
5. Any road closure also requires notification be provided to the City of Sand City Fire Department and Police Department. Notifications may be made at the non-emergency telephone number, 831.646.3914.
6. All temporary traffic delineation (delineators and cones) used shall be a minimum of thirty-six (36) inches tall.
Retroreflective bands are required for night time traffic control.
7. Any work that disturbs normal traffic signal operations shall be coordinated with the Streets Division and Traffic Signal Maintenance Contractor.
8. The Contractor is responsible for restoring the road back to satisfactory condition including, but not limited to, paving, striping, markings, signs and traffic signal loop detectors within five (5) calendar days of completion of work at affected intersections or road segments. 326
Part IV, Page 19
9. Any work that created an undue safety risk or creates severe congestion may be shut down by the City Traffic Engineer, their representative, Field Inspector or Police Department personnel.
The Contractor is to notify residences and/or businesses a minimum of three (3) business days in advance of closing access to any driveways or providing any detours or changes in on-street parking. Notifications shall be in writing.
Contractor shall provide all labor and facilities required for safe and expeditious handling of traffic during the course of construction. Contractor shall provide all flaggers, signs, delineators, and barricades required for traffic control and shall modify or remove same at appropriate times. The Engineer shall be the sole judge as to the adequacy of the Contractor's traffic control measures. If such measures are found to be inadequate by the Engineer, the City may furnish and install same and charge the Contractor therefor.
The Contractor shall, at their own expense, construct and maintain in good condition, such detours, detour bridges and temporary crossings for use by the public as deemed necessary or expedient by the Engineer for the proper execution of the work.
The Contractor shall designate a representative who can be reached immediately (24 hours per day) in the event of traffic control device failures.
CONSTRUCTION PROJECT SIGNS
The Contractor shall post temporary Sand City Capital Improvement Project signs, one at each end of the blocks or at entrances to project sites, in a manner approved by the Engineer. Sign panels shall be provided by the City and mounted on stakes. Sign panels and posts, if provided by the City, shall be returned to the City in good condition.
REMOVAL OF OBSTRUCTIONS
The Contractor shall remove and dispose of all structures, debris or other obstructions of any character to the construction called for in the plans, specifications, and as required by the Engineer.
If archeological items or hazardous wastes are discovered during construction operations, the Contractor shall cease operations in those areas and the Contractor shall immediately notify the Engineer.
The Contractor shall remove and dispose of all trees designated for removal as shown on the plans, designated by the specifications and as required by the Engineer for the proper completion of the work. See Tree Protection Requirements elsewhere in these specifications.
UNDERGROUND UTILITIES
Contractor shall locate all underground obstructions and utilities, (electric, gas, water lines, etc.). Prior to any trenching operation, Contractor shall pothole underground obstructions and utilities that appear to be in conflict with the new construction. The Plans show the approximate location of underground facilities in the project area as they have been provided to the City. Repair of damage to any utility line shown on the Plans with reasonable accuracy shall be made at the Contractor's expense. However, the City shall fairly compensate the Contractor for costs of locating and repairing damage not due to failure of the Contractor to exercise reasonable care, and removing or relocating such facilities not indicated or in a location different from that indicated on the Plans and Specifications with reasonable accuracy, and for equipment on the project necessarily idled during such work. Contractor shall not be assessed liquidated damages for delay in completion of the project when such delay was caused by the failure of the City or utility company to provide for removal or relocation of such utility facilities. Contractor shall notify all utility companies of trenching operations forty-eight (48) hours in advance to enable the utility companies to take any action they deem appropriate.
UTILITY COMPANY COORDINATION
Contractor shall coordinate construction activities with the utility companies as required and shall adjust the construction schedule to accommodate utility relocation as necessary.
CONTRACT PLANS AND SPECIFICATIONS
327
Part IV, Page 20
The Contractor will be supplied with five sets of plans and specifications at no expense. One of these sets of plans is to be used for the purpose of recording record (as-built) conditions. Additional sets will be furnished on request at the cost of reproduction. The work shall conform to the contract plans and specifications, all of which form a part of the contract documents and are available in the office of the City Engineer, City Hall, Sand City, California.
DUST CONTROL
The Contractor shall minimize dust generation from the jobsite and shall spray the site with water or dust palliative as required, in accordance with Section 14-
CONNECTION TO EXISTING UTILITIES
however, if the Contractor chooses to make use of said utilities, Contractor shall assume full responsibility for any changes made by Contractor related thereto, and for any consequences caused thereby. Upon completion of the work, Contractor shall remove any modifications to existing utilities made by Contractor, and shall restore existing utilities to conditions existing at time of award.
SANITARY FACILITIES
Contractor may provide their own portable sanitary facilities on-site, for the duration of the work. Coordinate location(s) with the Engineer. Existing City-owned sanitary facilities may be used.
INSPECTION OF WORK
It is the responsibility of the contractor to call for all required inspections within the required time lines. The City of Sand City reserves the right to perform random inspections at any time.
The Engineer shall at all times have access to the work during construction, and shall be furnished with every reasonable facility for ascertaining full knowledge respecting the progress, workmanship and character of materials used and employed in the work.
Whenever the work provided and contemplated by the contract shall have been satisfactorily completed and the final cleanup performed, the Engineer will make the final inspection.
RECORD DRAWINGS
A set of marked-up prints, clear, legible, and made with standard drafting tools and indicating all changes, added work, and deviations from the design and reflecting the record (As-Built) condition of the work must be received before the work is considered complete. Existing utilities exposed during construction are to be located, including invert or top elevation, and shown on the Record (As-Built) drawings.
The Record (As-Built) Drawings shall be submitted for the Engineer's acceptance with each progress payment. Final Record (As-Built) Drawings shall be submitted for the Engineer's acceptance before final payment and Notice of Completion on this contract will be made. The final pay application will not be considered complete until accurate Record (As-Built) Drawings have been submitted by the contractor and accepted by the City.
The Contractor shall prepare final as-built drawings of the project based on actual conditions after construction. Asbuilt drawings shall be prepared in AutoCAD with any changes clearly delineated within the file. The City will provide the AutoCAD drawing
shall be submitted electronically to the City for record.
ENVIRONMENTAL/POLLUTION PREVENTION REQUIREMENTS
Contractor shall comply with all air pollution and environmental control rules, regulations, ordinances and statutes that apply to the project and any work performed pursuant to the contract. Additionally, Sand City Municipal Code Chapter 13.05 Stormwater Management Section 13.05.060 Prohibition of Illegal Discharges, states, 328
Part IV, Page 21
No person shall discharge or cause to be discharged into the municipal storm drain system or water courses any materials, including, but not limited to, pollutants or waters containing any pollutants that cause or contribute to a violation of applicable water Regardless of project size, the Contractor shall submit a site-specific Erosion and Sediment Control Plan or Storm Water Pollution Prevention Plan for City review and approval prior to start of work. The Contractor shall effectively implement and properly maintain storm water best management practices (BMPs) during construction to prevent discharges of pollutants, and including trash, to local drainages and waterways. Contractor shall comply with all water quality regulations in Sand City Municipal Code Chapter 13.05 Stormwater Management, and City Phase II Storm Water Permit requirements as prescribed by the State Water Resources Control Board (SWRCB) and Central Coast Regional Water Quality Control Board (RWQCB) regulations for the prevention of construction site discharges of pollutants, illicit discharges, and enforcement of prohibited and illicit discharges. The contractor shall employ at all times storm water runoff controls and BMPs at the site, including but not limited to erosion prevention, sediment controls, site stabilization, good housekeeping practices, proper materials storage, handling, and waste management, and similar pollution prevention measures to prevent dumping or illegal discharges during construction into the street and/or storm drain system. Storm water management and control practices shall result in the following outcomes on all construction sites, regardless of size:
Protection of storm drain inlets and adjacent waterways must be implemented at all times to prevent illicit discharges of sediment, construction debris and fluids, and waste of any kind; No release of hazardous substances, such as oils, paints, thinners, fuels, and other chemicals; if such a spill occurs that may threaten local water quality, contractor must call 911 immediately and notify City Public Works staff;
Minimization of site disturbance shall be kept to that portion necessary for construction only, and perimeter controls shall be implemented at all times during all weather conditions;
Soil stabilization of graded areas shall be in place at all times where construction activities have temporarily and/or permanently ceased;
No deposit of mud, soil, sediment, concrete washout, trash, dewatering, or other similar construction-related and related natural resources, either by direct deposit, dropping, discharge, erosion, or tracking by construction vehicles. Any such discharge shall be cleaned-up promptly if an immediate threat to water quality exists, or if not immediate, at the end of the current work shift or workday in which the deposit occurred, whichever comes first; No runoff from graded areas or stockpile areas shall contain sediments and/or pollutants. Stockpiles shall be adequately and securely covered to avoid contact with rainfall and wind to prevent soil and stockpile movement by water and/or wind;
Runoff containing sediments shall be captured in secondary containment structures and either treated to remove sediments prior to discharge or infiltrated in the soil on-site; No exposure of graded areas and stockpile areas to storm water run-on shall occur. Run-on shall be controlled by diversion structures such as dikes, secondary containment, or stockpile covers; and, All hard-surfaced areas are to be swept regularly and free of dirt and construction debris such that the surface of the pavement is clearly visible at all locations, and construction entrance/exist(s) shall be adequately stabilized to prevent tracking of soil/sediment from reaching streets/paved surfaces and drainage pathways. 329
Part IV, Page 22
Best management practices (BMPs) are required to be illustrated in construction Plans and employed on all construction sites as applicable to the construction activity and shall provide for, and not be limited to: inlet protections, perimeter protections, erosion prevention and soil control measures, soil stabilization measures, spill prevention and discharge control measures; solid waste containment; concrete waste management; proper vehicle and equipment cleaning, fueling, and maintenance; and proper materials management and storage. Detailed procedures to Construction
BMP Handbook Portal, U.S. EPA Construction BMP Database and Factsheets, Caltrans Storm Water Quality Manuals and Handbooks, and the Erosion and Sediment Control Field Manual by San Francisco Bay Regional Water Quality Control Board. Referenced documents are available for viewing at the City of Sand City, City Hall.
Activities to be performed by Contractor include, but are not limited to:
Development and submittal of an Erosion and Sediment Control Plan or Storm Water Pollution Prevention Plan for City review and approval prior to construction start.
At all times, Contractor shall implement and maintain the temporary and permanent vegetation (if any), erosion and sediment control measures, and other protective BMP measures in good and effective operating condition by performing routine inspections to determine condition and effectiveness of BMPs, restoration needs for destroyed vegetative cover, and by repair of erosion, sediment, and other protective measures.
Contractor shall inspect the following areas at least once every seven (7) calendar days, unless otherwise necessary based on current weather conditions or as directed by City inspector, and always within 24 hours prior to and after any predicted storm:
o Inlet protections and perimeter controls;
o Vehicle entry and exist locations;
o Vehicle parking and storage areas;
o Disturbed areas of the construction site,
o Areas that have not been finally stabilized,
o Areas used for storage of materials that are exposed to wind or precipitation, o Equipment and staging areas that are exposed to wind or precipitation; and, o All waste storage and handling devices and areas.
Where sites have been finally stabilized, such inspection shall be conducted at least once every month.
Areas noted above shall be inspected for proper BMP implementation and necessary BMP maintenance, as well as evidence of, or the potential for:
o Erosion, or
o Sediments entering waterways or the drainage system, or o Pollutants entering waterways or the drainage system.
Erosion and sediment control measures shall be observed and maintained to ensure that they are operating correctly. Discharge locations or points shall be inspected regularly to ascertain whether erosion control measures are effective in preventing sedimentation and subsequent degradation of receiving water quality in violation of receiving water quality standards. Vehicle entry and exist locations shall be inspected for evidence of offsite sediment and pollutant tracking and need for cleanup and improved BMP protection measures 330
Part IV, Page 23
Deficiencies observed during inspections shall be noted and rectified before the end of the workday.
Permit (CGP), as applicable to the project. Projects subject to the CGP include those that disturb one or more acres of soil, are less than one acre and are part of a common plan of development or sale, or applicable Linear Water associated with Construction Activity Construction General Permit Order 2009 0009 DWQ, and subsequent amendments thereto. Construction activities subject to this permit include clearing, grading, and disturbances to the ground such as stockpiling, or excavation, but do not include regular maintenance activities performed to restore the original line, grade, or capacity of the facility. Application for CGP coverage is made by the Contractor through a Notice of Intent (NOI) to the SWRCB and involves much interaction with the applicable RWQCB as CGP regulator.
The Contractor shall develop and supply the City with NOI and associated Storm Water Pollution Prevention Plan (SWPPP) for review and records purposes.
CGP coverage requires the development and implementation of a SWPPP. The SWPPP contents are mandated by the SWRCB and are subject to change, and typically contain site map(s) which shows the construction site perimeter, existing and proposed buildings, lots, roadways, storm water collection and discharge points, general topography both before and after construction, and drainage patterns across the project. The SWPPP must illustrate the placement of BMPs for the construction project and list pollution prevention BMPs the discharger will use to protect storm water runoff. Additionally, applicable SWPPPs must contain a visual monitoring program and a chemical monitoring program for "non visible" pollutants to be implemented. All SWPPPs must be developed by a Qualified SWPPP Developer (QSD) and implemented by a Qualified SWPPP Practitioner (QSP), and supplied to the City for review and comment. Additional CGP information on can be found at the State Water Resources Control Board CGP website:
http://www.waterboards.ca.gov/water_issues/programs/stormwater/constpermits.shtml Construction site storm water management and control measures shall be implemented year round regardless of and in a proactive manner during all seasons while construction is ongoing. perform periodic site monitoring visits to ensure the contractor complies with the requirements specified herein. The City shall provide copies of the completed site monitoring reports to the Contractor. In the event work is found noncompliant, a follow up site monitoring visit will be conducted to ensure non-compliant items have been corrected to the satisfaction of the City. If non-compliant items are not properly addressed prior to the follow up site monitoring payment.
TREE PROTECTION REQUIREMENTS
The following guidelines are established pursuant to Chapter 16.12 of the Sand City Municipal Code, which states:
The City Council of the City of Sand City finds that the trees located within the City limits are a valuable aesthetic resource. Removal of significant trees could reduce scenic beauty and the attractiveness of the area to residents, business owners and visitors.
1. The Tree Protection Guidelines shall apply to all "significant trees" in the City of Sand City, defined as any tree which is equal to or greater than 10 inches DBH.
2. These standards do not apply to unprotected trees or trees previously approved for removal as shown in the plan set.
3. All cut, fill, and/or building foundations shall be located a minimum of 4.0 times the diameter of the tree away from the outside edge of the trunk of all trees scheduled for preservation. However, the minimum distance permitted shall be 6' - 0", away from the outside edge of the trunk for all trees of a trunk diameter less than 331
Part IV, Page 24
2' - -
[Diameter at Standard Height (DSH)].
4. All significant trees shall be marked with a spot of paint, or flagging and temporarily fenced during construction. The marking serves to notify City inspectors and workers that the tree is to be fenced at all times during construction. Fencing and marking shall be installed prior to the issuance of building or grading permits and shall be located at the edge of the root zone. The root zone is determined to be that area located out a distance 15 times the trunk diameter in all directions. At no time shall the fencing be located closer than 3' - 0" from the outside edge of the trunk or further than 3' - 0" away from the approved building wall line, foundation, retaining wall, or grade cut, whichever provides the greater distance from the tree trunk. Tree Protection Fencing (TPF) shall consist of six (6) feet tall plastic snow fencing and shall be rigidly supported and maintained during all phases of construction. Fenced areas shall not be used for material stockpile, storage, vehicle parking, or dumping of materials, chemicals, or garbage. Fenced areas shall be maintained in a natural condition and not compacted. Removal of fencing shall only be approved by the City Planner.
5. All approved construction work within the root zone of trees scheduled for preservation shall observe the following minimum tree protection practices:
a. Hand trenching at point or line of grade cuts closest to the trunk to expose major roots 2" in diameter or larger. In cases where rock or unusually dense soil prevents hand trenching, mechanical equipment may be approved by the City Planner, provided that work is closely supervised to prevent tearing or other damage to major roots.
b. Exposed major roots shall be cut with a saw to form a smooth surface and avoid tears or jagged edges. c. Absorbent tarp or heavy cloth fabric shall be placed over new grade cuts where roots are exposed and secured by stakes. 2" to 4" of compost or woodchip mulch shall be spread over the tarp to prevent soil moisture loss. The tarp should be thoroughly wetted at least twice per week to ensure constant moisture levels until backfilling occurs. In very dry climate conditions, additional watering may be required to maintain a constant moisture level. This program of watering shall be maintained through all phases of construction including delays and other periods of inactivity.
6. All Tree Protection devices must be in place prior to the start of construction. Please contact the City Planner 831-394-3054 for inspection to confirm Tree Protection or with any general tree preservation questions.
7. Chapter 16.12, Significant Tree Protection, is available at https://ecode360.com/42879785.
CLEANUP
All work sites shall be kept as clear of equipment, material and waste material as is practicable at all times. The City of Sand City and/or government Representative shall make the determination that this requirement is being complied with.
If the City is required to provide cleanup of the work sites due to failure of the Contractor to so provide, or in case of emergency, the City shall charge the Contractor the actual cost of labor and materials and may deduct said costs from any monies due and owing the Contractor.
Upon completion and before making application for acceptance of the work, the Contractor shall clean the street and/or other areas of work, and all ground occupied by the Contractor in connection with the work, of all rubbish, excess materials, temporary structures, and equipment, and all parts of the work shall be left in a neat and presentable condition.
332
Part IV, Page 25
CONTROL OF WORK
CONTRACT COMPONENTS
These specifications, the plans and all supplementary documents are essential parts of the contract, and a requirement occurring in one is as binding as though occurring in all; they are intended to be cooperative, to describe, and to provide for a complete job.
Shop drawings required by the plans, specifications or the Engineer shall be furnished by the Contractor and approved by the Engineer before any work relating to the shop drawings is performed unless approval is waived in writing by the Engineer.
It is mutually agreed that shop drawing approval by the Engineer does not relieve the Contractor of any responsibility for accuracy of dimensions and details, and that the Contractor shall be responsible for agreement and conformity of the shop drawings with the approved plans, specifications and site conditions.
Submittal review and approval by the Engineer does not relieve the Contractor from compliance with the requirements and intentions of the plans and specifications.
All authorized alterations affecting the requirements and information given on the approved plans and specifications shall be in writing. No changes shall be made on any plan, specification or drawing after the same has been approved by the Engineer, except by direction of the Engineer.
In the event of discrepancy, written dimensions shall take precedence over scaled dimensions.
The Engineer shall respond to any and all inquiries as to the quality or acceptability of materials furnished and work performed, and as to the manner of performance and rate of progress of the work; all inquiries as to the interpretation of the plans and specifications; all inquiries as to the acceptable fulfillment of the contract on the part of the Contractor; and all inquiries as to claims and compensation. The Engineer's response shall be final and the Engineer shall have executive authority to enforce and make effective such responses.
Should it appear that the work to be done, or any matter relative thereto, is not sufficiently detailed or explained in the plans and specifications, the Contractor shall submit a written Request for Information (RFI) to the Engineer.
Responses to shall be in writing and deemed part of the contract documents. Contractor shall comply with response explanation or interpretation so far as may be consistent with the intent of the plans, specifications and amendments thereto.
In the event of doubt or question relative to the true meaning of the plans and specifications, reference shall be made to the City Manager, or their designee, whose decision thereon shall be final.
ASSIGNMENT
The contract may be assigned only upon the written consent of the City Council.
SUBCONTRACTING
Any Proposed substitution of subcontractors must comply with the requirements of the Subletting and Subcontracting Fair Practices Act, California Public Contract Code §4100, et seq.
The Contractor shall give their personal attention to the fulfillment of the contract and shall keep the work under their control.
Subcontractors will not be recognized as such, and all persons engaged in the work of construction will be considered as employees of the Contractor, and their work shall be subject to the provisions of the contract, plans and specifications.
333
Part IV, Page 26
Where a portion of the work sublet by the Contractor is not being prosecuted in a manner satisfactory to the Engineer, the subcontractor shall be removed immediately on the requisition of the Engineer and shall not again be employed on the work.
REPRESENTATIVE
The Contractor shall assign a representative per Section 5-1.16, Representative, of the Standard Specifications and submit contact information (name, telephone number) to the City of Sand City Engineering Department. If the afterhours representative is different than the on-site representative, provide contact information for both.
The Contractor shall be constantly on the work during its progress or shall be represented by a foreman who is competent to receive and carry out instructions which may be given by the proper authorities, and the Contractor shall be held liable for the faithful observance of any lawful instructions of the Engineer not in conflict with the contract, and which may be delivered to the Contractor, superintendent, foreman, or other representatives on the work. If the Contractor believes the instructions are in conflict with the contract, the Contractor shall immediately bring it to the attention of the Engineer in writing.
The Contractor shall provide and maintain an office in the City of Sand City near the site of the work and shall allot such space to the Engineer or their representative as is required for proper keeping of records and plans of work, if required by the plans or specifications.
EQUIPMENT
While certain sections of these specifications may provide that equipment of a particular size and type is to be used to perform portions of the work, it is to be understood that the development and use of new or improved equipment is to be encouraged.
The Contractor may request, in writing, permission from the Engineer to use equipment of a different size or type in place of the equipment specified.
The Engineer, before considering or granting such request, may require the Contractor to furnish, at expense, evidence satisfactory to the Engineer that the equipment proposed for use by the Contractor is capable of producing work equal to, or better than, that which can be produced by the equipment specified.
PROPERTY AND FACILITY PRESERVATION
Attention is directed to Section 5-1.36, Property and Facility Preservation, Section 7-1.05, Indemnification and Section 7-1.06, Insurance, of the Standard Specifications. Due care shall be exercised to avoid injury to existing street improvements or facilities, utility facilities, adjacent property, roadside trees and shrubbery that are not to be removed.
The Contractor shall be held responsible for any damages to existing streets, highways, roads, driveways, sidewalks, curbs, gutters, utilities, other public facilities or private property caused by Contractor's operations.
Where the work calls for cutting into or disturbing existing materials, the Contractor shall patch or repair the existing area to a neat, finished product. This shall include touch up or repair of the existing which was disturbed, and repair to the same structural capacity as the existing facility or better.
Full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in protecting or repairing property, shall be considered as included in the prices paid for the various contract items of work, and no additional compensation will be allowed.
CONTRACTOR'S RESPONSIBILITY FOR WORK
All work which is defective in its construction or deficient in any of the requirements of the plans and specifications shall be remedied or removed and replaced by the Contractor in an acceptable manner, and no compensation will be allowed for such correction.
The inspection of the work shall not relieve the Contractor of any of their obligations to fulfill the contract as prescribed. Defective work shall be made good, and unsuitable materials may be rejected, notwithstanding the 334
Part IV, Page 27
fact that such defective work and unsuitable materials have been previously overlooked or approved by the Engineer and accepted or estimated for payment.
All work done beyond the lines and grades shown on plans or established by the Engineer, or any extra work done without written authority, will be considered as unauthorized and will not be paid for.
Upon failure on the part of the Contractor to comply forthwith with any order of the Engineer made under the provisions of this article, the Engineer shall have authority to cause defective work to be remedied, or removed and replaced, and unauthorized work to be removed. The cost of removing, replacing, or repairing said defective or unauthorized work may be deducted from any monies due and owing the Contractor but said right of set-off shall be an alternative and not the sole remedy of the City.
Until the formal acceptance of the work by the City (as constituted by the filing of the Notice of Completion), the Contractor shall have the charge and care thereof and shall bear the risk of injury or damage to any part thereof by the action of the elements or from any other cause whether arising from the execution or from the non-execution of the work. The Contractor shall rebuild, repair, restore, and make good all injuries or damages to any portion of the work occasioned by any of the above causes before final acceptance and shall bear the expense thereof, except such injuries or damages occasioned by the acts of the federal government or the public enemy.
Should the City elect to occupy a project before acceptance, the City will issue a Notice of Substantial Completion designating those portions of the work that will be occupied or utilized. Contractor shall be relieved from maintenance and from the responsibility of injury and damage to this work. However, any guarantees will not begin until acceptance of the entire project, and the Contractor shall retain responsibility for making good defective work or materials.
EMPLOYEES
All workmanship shall be fully up to the highest standard of modern construction and practice. The employment of labor shall comply with the prevailing local labor conditions and the Contractor shall employ only competent, careful, orderly persons upon the work. If at any time it shall appear to the Engineer that any person employed upon the work is incompetent, careless, reckless, or disorderly, or disobeys or evades orders and instructions, such person shall be immediately discharged and not again employed upon the work.
CONTROL OF MATERIALS
GENERAL
The Contractor shall furnish without charge such samples of materials and tests of materials as are required by the plans, specifications or the Engineer. No material shall be used until it has been approved by the Engineer.
All tests of materials ordered by the Engineer and made by the Contractor shall be made in accordance with commonly recognized standards of national organizations, and such special methods of tests as are prescribed in the plans and specifications.
All materials not conforming to the requirements of the plans and specifications shall be considered defective, and all such materials, whether in place or not, shall be rejected and shall be removed immediately from the site of the work unless otherwise permitted by the Engineer. No rejected materials, the defects of which have been subsequently corrected, shall be used until approved in writing by the Engineer.
Upon failure on the part of the Contractor to comply with any order of the Engineer made under the provisions of this article, the Engineer shall have authority to remove and replace defective material. The cost of removing, replacing or repairing said defective or unauthorized material may be deducted from any monies due and owing the Contractor but said right of set-off shall be an alternative and not the sole remedy of the City.
For convenience in designation on the plans or in the specifications, certain articles or materials to be incorporated in the work may be designated under a trade name or the name of a manufacturer and their catalog information.
The use of an alternative article or material which is of equal quality and of the required characteristics for the 335
Part IV, Page 28
purpose intended will be permitted, provided that the burden of proof as to the quality and suitability of alternatives shall be upon the Contractor who shall furnish, at the expense, all information necessary as required by the Engineer. The Engineer shall be the sole judge as to the quality and suitability of alternative articles or materials and that decision shall be final.
MATERIAL SOURCE
At the option of the Engineer, the source of supply of each of the materials shall be approved by the Engineer before delivery is started and before such material is used in the work. Representative preliminary samples of the character and quality prescribed shall be submitted by the Contractor or producer of all materials to be used in the work, for testing or examination by the Engineer.
QUALITY
Except as otherwise provided, sampling and testing of all materials, and the laboratory methods and testing equipment required under the plans and specifications shall be in accordance with the latest requirements of the State of California, Department of Transportation, Office of Materials Engineering and Testing Services. Sampling and testing of materials not covered by Caltrans specifications and not otherwise provided for, shall be in accordance with the latest Test Methods and Standards of the American Society for Testing and Materials (ASTM).
GUARANTEE
All materials supplied and all work done under this contract shall be guaranteed by the Contractor for a period of one (1) year from the date of formal acceptance by the City of Sand City. Upon receipt of notice from the Engineer of failure of any part of the guaranteed materials during the guarantee period, the affected parts shall be replaced promptly and at the expense of the Contractor.
The Contractor shall maintain the performance bond (See Part IV, Contract Bonds) in full force and effect during the guarantee period for the purpose of insuring that said repairs or replacements will be made, or may, at the option, replace said performance bond for a similar bond in the amount of twenty percent (20%) of the total contract amount including adjustments or the original performance bond, whichever is greater.
APPRENTICES
The Contractor and subcontractors shall comply with the provisions in Sections 1777.5, 1777.6 and 1777.7 of the California Labor Code and Title 8, California Code of Regulations Section 200 et seq. To ensure compliance and complete understanding of the law regarding apprentices, and specifically the required ratio thereunder, the Contractor and each subcontractor should, where some question exists, contact the Division of Apprenticeship Standards, 455 Golden Gate Avenue, San Francisco, CA 94102, or one of its branch offices prior to commencement of Work on the contract. Responsibility for compliance with this section lies with the Contractor. It is State and City policy to encourage the employment and training of apprentices on public works contracts as may be permitted under local apprenticeship standards.
WORKING HOURS
Eight hours labor constitutes a legal day's Work. The Contractor or any subcontractor under the Contractor shall forfeit, as a penalty to the State of California, twenty five dollars ($25) or such other amount as may be amended by the Department of Industrial Relations from time to time for each worker employed in the execution of the contract by the respective Contractor or subcontractor for each calendar day during which that worker is required or permitted to Work more than 8 hours in any one calendar day and 40 hours in any one calendar week in violation of the requirements of the Labor Code, and in particular, Section 1810 to Section 1815, thereof, inclusive, except that Work performed by employees of Contractors in excess of 8 hours per day, and 40 hours during any one week, shall be permitted upon compensation for all hours worked in excess of 8 hours per day at not less than one and one-half times the basic rate of pay, as provided in Section 1815 thereof.
OCCUPATIONAL SAFETY AND HEALTH STANDARDS
The Contractor shall conform to all local, state and federal rules and regulations pertaining to safety. Furnished equipment, material and services shall comply with all OSHA Standards and regulations and all applicable 336
Part IV, Page 29
governmental laws and orders. The Contractor shall post an OSHA poster in a conspicuous location as required by law.
EXCAVATION SAFETY
Per California Labor Code Section 6500, Contractor shall possess a valid Construction Activity Permit for construction of trenches or excavations which are five (5) feet or deeper and into which a person is required to descend. When trenches or excavations five (5) feet or deeper are anticipated as part of the contract, Contractor shall possess a valid permit at the time of bidding and for the life of the contract. Contractor shall furnish copies of valid permits to the City of Sand City Engineering Department. When required in Part I, Notice to Contractors, Contractor must provide evidence of a current T1 Annual Trench/ Excavation Permit at the time of bidding.
Contractor shall comply with California Labor Code Section 6705 which provides that prior to the commencement of excavation of any trench or trenches five (5) feet or more in depth, Contractor shall submit to the Engineer a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If such plan varies from the shoring system standards established by the Construction Safety Orders, the plan shall be prepared by a registered civil or structural engineer.
Plans must be submitted to the Engineer at least five (5) working days prior to the commencement of excavation.
If said plans are not submitted five (5) days prior to the commencement of said excavation, the City shall not be liable to Contractor for any delay in work caused by delinquent submission of said plans.
Trenching of more than four (4) feet below the surface shall require the Contractor to promptly notify the Engineer if unknown hazardous wastes, subsurface or latent physical site conditions different from those indicated or unusual site conditions are encountered, and inform the City as to its duty to investigate those conditions. The Contractor may file for a change order for any conditions different from those indicated.
PUBLIC CONVENIENCE AND PUBLIC SAFETY
Attention is directed to Section 7-1.03, Public Convenience, and Section 7-1.04, Public Safety, of the Standard Specifications for the provisions relating to the Contractor's responsibility for providing for the convenience and safety of the public in connection with their operations. Standard Specifications are on file in the office of the City Engineer.
Contractor is to notify the Engineer of the start date and construction schedule at least nine (9) calendar days prior to the planned start of construction unless otherwise noted in Part IV. shall be limited to working days as defined by the State Standard Specifications. Daily work time shall be between the hours of 8:30 a.m. and 4:30 p.m. on all City streets, and other public right of way. Should the City Engineer or Special Provisions allow for working hours other than listed above, construction work and related activities shall desist between the hours of 9:00 p.m. and the following 7:00 a.m. and, all Saturdays, Sundays, and legal Holidays.
Time limitations are established to minimize traffic interference and nuisance to the adjacent development and to the traveling public. In the event construction activities continue outside of working hours where overtime pay to City of Sand City personnel has been incurred, the Contractor shall reimburse the overtime costs to the City of Sand City.
The Contractor shall conduct their operations as to cause the least possible inconvenience to public traffic. The Contractor shall provide traffic control devices or personnel where necessary in conformance with traffic safety standards. The Contractor shall provide sufficient warning signs or devices to give adequate notice to the public of dangerous or changed conditions existing during construction.
The City Engineer shall determine the adequacy of said devices and, in cases of dispute, their determination shall be final.
If the City is required to provide traffic direction, personnel, signs or devices, due either to failure of the Contractor to so provide or in case of emergency, the City shall charge Contractor the actual cost of labor and materials 337
Part IV, Page 30
and may deduct said costs from any monies due and owing the Contractor.
Pursuant to the requirements in Section 1860 of the Labor Code, the Contractor will be required to secure the payment of workers' compensation to the Contractor's employees in conformance with the requirements in Section 3700 of the Labor Code.
PATENTS
If any material, composition, process, method of construction or any other thing called for or required by the plans and specifications or used in the work is covered by letter patent, all royalties and expenses thereof, all litigation thereupon, or anything whatsoever which may develop as a cost from the use of such materials, composition, process, method, or any other thing which is covered by letter patent, shall be borne by the Contractor.
RIGHT OF PROPERTY
Nothing in the contract shall be construed as vesting the Contractor with any right of property in the materials furnished and used in the work herein provided for after they have been attached to the work and have become an integral portion of the work herein provided. All such materials shall, upon their becoming an integral part of the work herein provided, be, and remain, the property of the City of Sand City.
INCREASED FORCE
In case of emergency involving danger to life or property, continuous work with increased force may be required by the Engineer.
LIABILITIES
Right of general supervision by the City shall not make the Contractor an agent of the City, and the liability of the Contractor for all damages to persons or to public or private property arising from the Contractor's execution of the work shall not be lessened because of such general supervision.
PROSECUTION AND PROGRESS
GENERAL
If at any time in the opinion of the Engineer, the Contractor has failed to supply an adequate working force, or material of proper quality, or has failed in any other respect to prosecute the work with the diligence and force specified and intended in and by the terms of the contract, notice thereof in writing shall be served upon the Contractor. Should the Contractor neglect or refuse to provide means for a satisfactory compliance with the contract, as directed by the Engineer, within the time specified in such notice, the Engineer in any such case shall have the power to suspend the operation of the contract. Upon receiving notice of such suspension, the Contractor shall discontinue said work, or such parts of it as the City may designate.
Upon such suspension, the Contractor's control shall terminate, and thereupon the Engineer or duly authorized representative may take possession of all or any part of the Contractor's materials, tools, equipment, and appliances upon the premises, and use the same for the purpose of completing said contract, and hire such force and buy or rent such additional machinery and appliances, tools, and equipment and buy or rent such additional materials and supplies at the Contractor's expense as may be necessary for the proper construction of the work and for the completion thereof; or may employ other parties to carry the contract to completion, employ the necessary workers, substitute other machinery or materials and purchase the materials contracted for in such manner as the City may deem proper; or the City may annul and cancel the contract and re-let the work or any part thereof.
Any excess of cost arising therefrom over and above the contract price will be charged against the Contractor and their sureties, who will be liable therefor. In the event of such suspension, all money due the Contractor or retained under the terms of this contract shall be forfeited to the City, but such forfeiture will not release the Contractor or their sureties from liability for failure to fulfill the contract. The Contractor and their sureties will be credited with the amount of money so forfeited toward any excess of cost over and above the contract price, arising from the suspension of the operations of the contract and the completion of the work by the City as above provided, and 338
Part IV, Page 31
the Contractor will be so credited with any surplus remaining after all just claims for such completion have been paid.
In the determination of the question whether there has been any such noncompliance with the contract as to warrant the suspension or annulment thereof, the decision of the City Manager shall be binding on all parties to the contract.
SUSPENSIONS AND DELAYS
Suspensions of work and delays shall be in accordance with Section 8-1.06, Suspensions, and Section 8-1.07, Delays, of the Standard Specifications.
The Engineer shall have the authority to suspend the work wholly or in part, for such period as the Engineer may deem necessary due to unsuitable weather, or to such other conditions as are considered unfavorable for the suitable prosecution of the work, or for such time as the Engineer may deem necessary due to the failure on the part of the Contractor to carry out orders given or to perform any provisions of the work. The Contractor shall immediately obey such order of the Engineer and shall not resume work until ordered in writing by the Engineer.
Any act of, or any omission of anything required to be done by the City, its officers, agents or employees which shall cause the Contractor delay in the completion of the work shall be a ground for extension of time on the part of the Contractor to complete the work but shall not grant the Contractor any monetary damages for such delay.
RIGHTS OF WAY
Rights-of-way or easements for work to be constructed will be provided by the City. The Contractor shall make their own arrangements and pay all expenses for additional area required outside of the limits of rights-of-way or easements unless otherwise especially provided. In the event of delay on the part of the City, its officers, agents or employees in obtaining any such rights-of-way or easements for the work to be constructed, then the Contractor shall have time for the completion of their contract for the period or periods caused by such delay or delays but shall have no damages against the local agency, its officers, agents or employees. 339
Part V, Page 1
PART V: TECHNICAL SPECIFICATIONS
1. MOBILIZATION
Refer to California Public Contracts Code §10104 for Mobilization requirements, Section 1-1.07B of the Standard Specifications for the definition of Mobilization and Section 9-
1.16D of the Standard Specifications.
Mobilization includes preparatory work and operations, including, but not limited to, those necessary for the movement of personnel, equipment, supplies and incidentals to the project site, for the establishment of all offices, staging areas and other facilities necessary for work on the project, and for all other work and operations which must be performed or costs incurred prior to beginning work on the various items on the project site.
The contractor shall photograph or video the entire site(s), and each existing improvement prior to construction.
Note that the City has not provided a laydown area for the Contractor. The Contractor shall be responsible for establishing a laydown area and coordinate such location with the City.
Contractor shall document all design changes and prepare red lined plans representing the finished field conditions.
Daily, the Contractor shall clean all portions of the project area. This work includes removing all debris, street sweeping, clearing Underground Service Alert marks, and power washing sidewalks.
2. TRAFFIC CONTROL SYSTEM
The Traffic Control Plans shall be prepared by a licensed Civil Engineer (Signed and Stamped) and submitted to the City prior to the scheduled Pre-Construction Meeting.
Traffic Control Plans will require approval from the City prior to the start of construction.
Traffic and pedestrian control shall consist of furnishing and installation of traffic and pedestrian signing (pedestrian signing in English and Spanish), delineators, fencing, barricades, temporary base rock or plywood walkways, temporary driveways and flaggers as necessary to maintain safe passage.
Walkways shall be open to pedestrian traffic at all times. Contractor shall provide and install temporary fencing, signing and ramping to provide safe pedestrian traffic through the project site and shall maintain safe access to all properties at all times.
Temporary pedestrian facilities must comply with the California MUTCD, Part 6, Chapter 6D, -2.02,
It is the responsibility of the Contractor to provide traffic control flaggers. The City does not share costs. The contractor is responsible for the full cost of flagging.
The roadway shall be open to emergency vehicles at all times. Contractor shall provide vehicular access to all residences and businesses at all times except when concrete, asphalt or grading work is actively in progress in the immediate area adjacent to driveway(s). Contractor shall provide vehicular access to all residences and businesses at all times during non-working 340
Part V, Page 2
hours. When work is not actively in progress barriers shall be placed to prevent vehicles or pedestrians from entering work area.
The Contractor shall comply with all applicable State, County and City requirements for closure of streets. At least 48 hours in advance of closing any street, alley, or other public thoroughfare, the Contractor shall notify the Police and Fire Departments, and shall comply with their requirements.
The contractor shall notify all businesses and property tenants at least 48 hours prior to closure of driveways. If closure is to be on Monday, notifications shall be given by Thursday. If closure is to be on Tuesday, notifications shall be given by Friday. Non-working days (Saturday, Sunday, and scheduled holidays) are not included in the 48 hours.
The provisions of this section will not relieve the Contractor from his responsibility to provide such additional devices or take such measures as may be necessary to comply with the provisions of Section 7-1.04, "Public Safety," of the Standard Specifications.
Implement Traffic Control System shall consist of closing traffic lanes in accordance with the isions, and this section of
these special provisions.
If any component in the traffic control system is damaged, displaced, or ceases to operate or function as specified from any cause, during the progress of the work, the Contractor shall immediately repair said component to its original condition or replace said component and shall restore the component to its original location.
Temporary pavement delineation shall be furnished, placed, maintained and removed in accordance with the provisions in Section 12-
these special provisions. Nothing in these special provisions shall be construed as to reduce the minimum standards specified in the California Manual on Uniform Traffic Control Devices or as relieving the Contractor from his responsibility as provided in Section 7- the Standard Specifications.
Whenever the work causes obliteration of pavement delineation, temporary or permanent pavement delineation shall be in place prior to opening the traveled way to public traffic. Lane line or centerline pavement delineation shall be provided at all times for traveled ways open to public traffic.
All work necessary, including any required lines or marks, to establish the alignment of temporary pavement delineation shall be performed by the Contractor. Surfaces to receive temporary pavement delineation shall be dry and free of dirt and loose material. Temporary pavement delineation shall not be applied over existing pavement delineation or other temporary pavement delineation. Temporary pavement delineation shall be maintained until superseded or replaced with a new pattern of temporary pavement delineation or permanent pavement delineation.
Temporary pavement markers and removable traffic type tape which conflicts with a new traffic pattern or which is applied to the final layer of surfacing or existing pavement to remain in place shall be removed when no longer required for the direction of public traffic, as determined by the Engineer.
Whenever lane lines and centerlines are obliterated, the minimum land line and centerline delineation to be provided shall be temporary reflective raised pavement markers placed at longitudinal intervals of not more than 24 feet. The temporary reflective raised pavement markers shall be the same color as the landline or centerline the markers replace.
Temporary reflective raised pavement markers shall be placed in accordance with the recommended by the manufacturer, except epoxy adhesive shall not be used to place pavement markers in areas where removal of the markers will be required. 341
Part V, Page 3
Temporary lane line or centerline delineation consisting entirely of temporary reflective raised pavement markers placed on longitudinal intervals of not more than 24 feet, shall be used on lanes opened to public traffic for a maximum of 14 days. Prior to the end of the 14 days the permanent pavement delineation shall be placed. If the permanent pavement delineation is not placed within the 14 days, the contractor shall provide, at his expense, additional temporary pavement delineation. The additional temporary pavement delineation to be provided shall be equivalent to the pattern specified for the permanent pavement delineation for the area, as determined by the Engineer.
Temporary delineation shall be removed in its entirety prior to application of the polymer modified slurry.
When lane closures are made for work periods only, at the end of each work period, all components of the traffic control system except portable delineators placed along open trenches or excavation adjacent to the traveled way, shall be removed from the traveled way, shoulder and auxiliary lanes.
Upon completion of the work requiring lane closure, all components of the traffic control system shall be removed from the site of the work and shall become the property of the Contractor.
Lane closures shall be as indicated on the plans. No work that interferes with public traffic shall be done outside these hours except for work required under Section 7- - cations.
When work is not actively in progress the full width of the traveled way shall be open for public traffic.
Improvements at intersection Highway 1-Off Ramp and California Avenue will require Caltrans Encroachment Permit for Traffic Control. Contractor must submit Caltrans Encroachment Permit application to Caltrans for approval.
The Contractor shall submit two (2) final signed copies of all Contractor obtained permits to the Engineer prior to beginning any work. Once obtained, the Contractor shall be responsible for complying with all permit conditions.
3. WATER POLLUTION CONTROL
Water Pollution Prevention Plan & Reporting shall conform to the provisions of Section 13-3 requirements of the California State Water Resources Control Board.
Work in this section shall include preparing a water pollution prevention plan, developing and implementing the plan, providing a WPC manager, conducting WPC training, and monitoring, inspection, reporting, and correcting WPC practices. The Water Pollution Prevention Plan shall include project specific layout of each item intended to prevent erosion and movement of silt and pollution. The layout shall include placement of a perimeter fence around staging area to limit access to and from the work area.
Weekly reports shall be submitted to engineer. All reports that are required and/or recommended by the Water Pollution Control Plan shall be submitted to the City prior to issuing the Notice of Completion. All reporting is included in the bid item cost of Prepare Water Pollution Prevention Plan.
4. CRITICAL PATH METHOD (CPM) SCHEDULE
Refer to Section 8-1.02C (1) of the Standard Specifications for preparing and maintaining a critical path method schedule. The schedule must be submitted for approval during the preconstruction meeting. 342
Part V, Page 4
construction during times that school is not in session. Contractor shall verify school calendars with Sand City and plan accordingly in the CPM schedule.
5. EXCAVATION SAFETY
General
Attention is directed to Section 7-
and these Special Provisions. Contractor shall comply with Labor Code § 6705 while excavating.
For an excavation 5 feet or more in depth, submit shop drawings for a protective system.
Construction
Temporary support shoring, temporary bracing, and protective covers if required, shall be designed and constructed in conformance with the provisions in Section 15-4.01C(2)(b), cifications.
Temporary construction excavations and structures should conform to the regulations of the State of California, Department of Industrial relations, Division of Industrial Safety or other stricter governing regulations. The stability of temporary cut slopes, such as those constructed during the installation of the walls shall be the responsibility of the Contractor.
If the Contractor elects to use temporary shoring, the Contractor shall submit a temporary shoring plan to the Owner prior to commencing the work. The design submittal shall be prepared by a Civil Engineer registered in the State of California and shall address all aspects of the design, installation, and removal of the shoring system.
6. CLEARING AND GRUBBING
Clearing, Grubbing and Removals shall conform to the provisions of Section 17- and Removals shall consist of thoroughly sweeping and cleaning surfaces prior to resurfacing, removal and disposal of raised pavement markers, existing weeds, brush, or other objectionable material in or along the edge of areas to receive work.
Contractor shall keep existing streets free from dirt and debris at all times. Contractor shall be prepared to sweep surfaces immediately at the request of the Engineer should he deem it is necessary for safety of public and to avoid damage to properties.
When required, existing thermoplastic pavement markings shall be removed in accordance with Section 84-
laws and regulations.
Existing pavement markers shall be removed in accordance with Section 81-8.03B of the State Standard Specifications.
Contractor shall trim overhanging limbs that may be in conflict with paving and other construction activities. Tree, roots, and bush pruning shall be performed per recommendations from a certified arborist and in accordance with "Pruning Standards," published by the Western Chapter of the International Society of Arboriculture. The certified arborist shall be approved in advance by the Engineer, and all pruning shall be done as directed by the Engineer and in the presence of the Engineer.
343
Part V, Page 5
Contractor shall remove existing landscaping (hard and soft) only within City Right of Way which is in conflict with the new improvements.
Full compensation for complying with the provisions of this section shall be considered as included in the contract price for the various bid items and no separate payment will be made therefor.
7. HOT MIX ASPHALT
General
This work includes producing and placing hot mix asphalt (HMA) Type A for Overlay Conditions, Full Depth HMA Conditions, AC Dikes, AC Conforms, and new pavement sections. The contractor shall place hot mix asphalt (HMA) Type A with the thickness shown on the plans.
Comply with Section 39, "Hot Mix Asphalt," of the Standard Specifications except as modified herein.
Submittals
Submit JMF information on Form CEM-3511 and Form CEM-3512. Submit Form CEM-3513 for mixes that have been verified within last 12 months. For unverified mixes, coordinate mix verification with Engineer.
Submit Quality Control Plan that conforms to the current Caltrans Quality Control Plan Review Checklist for Hot Mix Asphalt. Allow 20 calendar days for review.
Materials
The grade of asphalt binder mixed with aggregate for HMA Type A must be PG 64-10.
Mix shall not be
used except for temporary paving operations.
Below is a list of Hot Mix Asphalt (HMA) Type A required for the project site.
Base Bid:
Holly Street between Ortiz Avenue and California Avenue o Full Depth HMA (7-inches in Depth)
Holly Street between Redwood Avenue and California Avenue o -
in the project plans.
Contra Costa Street between Redwood Avenue and West End Near Bay Street o HMA Overlay (2-inches in Depth), Wedge Grind, and Localized Base Repairs City Hall Parking Lot
o Full Depth HMA (3-inches in Depth)
Additive Alternate 1:
344
Part V, Page 6
California Avenue between Highway 1 OffNorth Driveway Entrance O Crack Seal, Localized Base Repairs, Micro slurry (Type II) Additive Alternate 2:
Playa Avenue between California Avenue and Metz Road
O 6-inch Mill and Inlay
The tack coat shall be emulsified asphalt of grades RS1, RS2, SS1, or SS1h, conforming to Construction
Surface preparation
This work consists of preparing the existing street surface prior to the commencement of paving.
Such work shall include compacting and removing loose and broken asphalt concrete pavement and foreign material as specified in the Standard Specifications and these Technical Provisions, and as directed by the Engineer.
Sampling
and to test such samples for the purpose of determining specification compliance. The City reserves the right to obtain said samples at the point of delivery and/or at the point of manufacture. The City shall also have the right to inspect sources of materials to be used in the work to determine workmanlike procedures used by the materials supplier. The contractor shall facilitate the sampling process.
Transportation and placement
The asphalt concrete shall be delivered in a thoroughly blended condition and shall be spread by an asphalt paving machine in such a manner as to avoid segregation during the placing operations. Areas inaccessible to spreading and compaction equipment may be paved by such immediately after placement. No asphalt concrete is to be placed when the atmospheric temperature is below 50 degrees Fahrenheit.
Equipment
Paving Machine
Asphalt pavers shall be mechanical spreading and finishing equipment, provided with a screed or strike off assembly capable of distributing the material to not less than eight (8) feet. Screed action shall include any cutting, crowding or other practical action which is effective on the mixture without tearing, shoving, or gouging, and which produces a surface texture of uniform appearance. The screed shall be adjustable to the required section and thickness. The paver shall be provided with a full width roller or tamper or other suitable compacting devices. Pavers that leave ridges, indentations or other marks in the surface shall not be used unless the ridges, indentations or other marks are eliminated by rolling or prevented by adjustment in operations.
Compaction Rollers
The Contractor shall furnish equipment capable of producing the required compaction. Vibratory rollers shall be double steel drum and have adjustable amplitude settings.
Hand Equipment
345
Part V, Page 7
Sufficient vibraplates and hand tampers shall be provided to assure their immediate availability when placing asphalt concrete around planters, inside corners, or irregular areas. Torches for heating cold joints or making repairs shall be available during every paving operation. Lack of such hand equipment shall be cause to prevent paving from starting or continuing.
Tack coat
The work to be performed shall consist of furnishing and applying tack coat in conjunction with asphalt concrete overlays and other asphalt concrete paving work.
Tack coat shall be emulsified asphalt of grades RS1, RS2, SS1, or SS1h, conforming to Section The tack coat shall not be applied until the preparation of the existing surface has been completed, and then only so far in advance of placing the asphalt concrete as permitted by the Engineer. Preparation of the surface shall be performed as described in these Technical Provisions. No tack coat shall be left exposed overnight. Immediately in advance of placing the asphalt concrete, additional tack coat shall be applied as directed by the Engineer to areas where previously applied tack coat has been destroyed or otherwise rendered ineffective, and no additional compensation will be allowed for such work.
Tack coat shall be applied to all vertical surfaces of existing pavement, curbs, gutters, and construction joints, against which additional material is to be placed, to a new or old pavement to s Engineer. Shields for protecting
curb faces shall be provided and used during tacking of curb faces. The Contractor shall protect concrete surfaces that are not to be paved against from tack coat spray or splash. Any tack coat more than one inch above the paving surface shall be removed by power washing or other means.
The Engineer will determine if the pavement is sufficiently dry for the application of the tack coat.
Tack coat shall not be applied when the temperature of the surface to be tacked is below 40 degrees Fahrenheit in the shade.
Workmanship
Finished Surface
The completed surfacing shall be thoroughly compacted, smooth, and free from ruts, humps, depressions, irregularities, rock pockets, excessive coarse aggregate, and roller marks.
Any ridges, indentations, or other objectionable marks left in the surface of the asphalt concrete shall be eliminated by rolling or other means. The use of any equipment that leaves ridges, indentations, or other objectionable marks in the asphalt concrete shall be discontinued.
The Contractor shall provide sufficient manpower and manual compacting equipment to perform all handwork compaction in unison with the initial compaction rolling. If the handwork compaction begins to lag for whatever reason, the Contractor shall cease paving operations until the handwork compaction is caught up with the rest of the paving operation.
Areas of hand work at joints and miscellaneous structures shall match the smooth surface texture of all other areas of the new pavement. Any areas which have a rough surface texture shall be reworked with heat and asphalt concrete fines shall be placed. Coarse aggregate removed during raking shall not be returned to the finished mat surface. Such coarse aggregate may be returned to the hopper of the paving machine or spread immediately in front of the paver. Cold coarse aggregate shall not be reused, but discarded.
346
Part V, Page 8
Finished areas of asphalt concrete adjacent to concrete drainage facilities shall be placed in such a manner that the finished surface is no greater than 1/4 inch higher than the facility and no lower than flush with the facility.
Cold Joints
The contractor shall heat by torch or other acceptable methods paving joints which do not receive an adjacent pass within 3 hours of placement. If the cold joint goes unpaved against overnight, the contractor shall heat the joint and place tack coat prior to placing the adjacent pass.
Longitudinal pavement joints shall be on, or as close as possible to, the lane lines.
8. MIRCROSLURRY TYPE II
General:
Microslurry Type II shall comply with Section 37- - of the Caltrans Standard Specifications.
Microslurry Type II work shall be coordinated in a way that does not disrupt residential garbage collection and mail delivery. The Contractor shall coordinate with applicable agencies and time paving activities as needed to prevent disruption of service.
9. CRACK SEAL
General:
Comply with Section 37-
herein.
The work shall consist of cleaning and filling cracks prior to placement of Slurry Seal with asphalt joint seal as specified in these special provisions, and as directed by the Engineer. Crack sealing will not be performed in areas designated to receive foamed FDR. Cracks less than ½ inch in width shall be routed to a depth of ½ inch by ½ inch in width. The contractor shall remove all debris from the roadway.
Materials:
Crack sealant shall be a mixture of paving asphalt and ground rubber and shall conform to ASTM D 5078, Type II. The crack seal product shall conform to the following requirements:
Test Specification Limit
Cone Penetration 77 F(25 C)(ASTM D5329) 35-55
Resilience (ASTM D5329) 40% min.
Softening Point (ASTM D36) 200 F(93 C) min.
Ductility 77 F(25 C)(ASTM D5113) 30 cm min.
Flexibility (ASTM D3111 Modified) Pass at 20 F(-7 C)
Flow 140o F(60 C)(ASTM D5329) 3 mm max.
Brookfield Viscosity 400o F(204 C)(ASTM D2669) 100 Poise max.
Asphalt Compatibility (ASTM D5329) Pass
Bitumen Content (ASTM D4) 60% min.
347
Part V, Page 9
Tensile Adhesion (ASTM D5329) 500% min.
Safe Heating Temperature 400o F(204o C)
Recommended Pour Temperature 380o F(193o C)
The pre-emergent herbicide shall be an E.P.A. approved herbicide composed of glyphosate and oryzaline, combined and applied according to label directions. The Contractor shall submit a product information sheet on the sterilent to be used.
Construction:
All cracks indicating weed growth are to be sprayed and cleaned as follows: the Contractor shall apply herbicide to all existing weed growth within the roadway area from curb to curb including the joint between the gutter lip and asphalt pavement. A minimum of two applications shall be made with a minimum period of 7 calendar days between applications. The second application shall be applied to treated areas and any additional new weed growth between applications. Any new weed growth shall be treated a third time after a minimum of 7 days from the second application. The herbicide shall be applied by a licensed applicator and shall comply with the Seven days after the last application of herbicide (either the second or third), all remaining vegetation in the cracks shall be mechanically removed.
All existing vegetation, outside the areas to be cleared and grubbed, shall be protected from the Contractor's operations unless specifically shown on the plans to be removed.
Immediately prior to applying the sealant, the cracks shall be cleaned with high pressure air jets to remove all residue and foreign material. Any weed growth shall be physically removed.
Water jets will not be allowed. Crack surfaces shall be surface dry at the time the sealant is applied.
During all construction operations, the Contractor shall protect cracks cleaned for sealing from intrusions of solid foreign materials into the groove or into the sealant.
Crack seal materials shall be placed in conformance with the manufacturer's recommendations.
Crack seal materials shall not be placed when the surface temperature is below 50 degrees Fahrenheit.
The finished crack seal shall be bonded to the crack such that there is no separation or opening between the sealant and the crack edge and there shall be no cracks, separation or other opening in the sealant.
The Contractor shall remove crack seal material that is not placed within the conformance of these provisions, clean cracks as specified herein and then reseal the cracks at his expense.
Sequencing
as to strike off excess material and to provide a band aid effect with the sealant. After the sealant has cooled, there should be a slight depression of not more than 1/8th-inch below the adjacent pavement. Bulging as a result of overfilling of cracks must be corrected.
10. CLASS 2 AGGREGATE BASE MATERIAL
348
Part V, Page 10
General
The work covered by this section shall consist of furnishing, spreading and compacting aggregate base required during utility operations, pavement works, and concrete works, in accordance with the provisions of Standard Specifications Section 26, "Aggregate Bases", and as specified herein.
Compaction and Tolerance
95% minimum relative compaction as shown on the Plans and as determined by State of California compaction test No. 216G. The finished surface of the base course shall meet the grade and cross section of the existing pavement. Grading tolerance shall be 0.02' or less.
Testing
The City may contract with and pay for initial compaction tests for Quality Assurance. Contractor shall pay the cost for retesting and re-inspections of failed work until such work is accepted.
Quality control inspecting and testing performed exclusively shall be the sole responsibility of the Contractor.
11. WEDGE GRIND AND CONFORM GRIND
Cold planing in accordance with Section 39-3.04 of the Standard Specifications shall be used for pavement wedge removal and conform grinding at pavement transitions. Planing machine shall have cutter head at least 4 feet wide. On streets designated for overlay, contractor shall have a wedge of pavement removed to facilitate placement of overlay by wedge grinding the full length of the pavement adjacent to lip of existing gutters, and conform grinding at cross streets and at other locations shown on plans or as designated by the Engineer. Cold planing at edge of pavement shall be to depth noted on plans, below existing lip of gutter or adjacent asphalt concrete pavement.
Final cut shall result in uniform surface. Outside lines of planed area shall be neat and uniform.
If utility castings are encountered within wedge grind or conform grind area, said castings shall be protected by performing wedge removal using hand tools or other approved method and shall be adjust to finished grade as shown on plans and in conformance with these special provisions.
Wedge Grind shall be 8 feet maximum at HMA overlay conditions. Refer to project plans for locations of Wedge Grind for pavement improvements.
12. LOCALIZED BASE FAILURE REPAIRS (DIGOUTS)
Materials:
HMA for pavement failure repair must be Type A.
Asphalt binder for the HMA must be PG 64-10. The minimum asphalt binder content must be 5.0 percent. If you request and if authorized, you may reduce the minimum asphalt binder content.
The aggregate for the HMA must comply with the 3/4-inch HMA Type A.
Construction:
Place base failure repair under the Method construction process in Section 39-3.
Provide flaggers and/or traffic control to allow the Engineer to mark out base failure areas.
Refer to construction details in the project plans for proposed base repair depths. 349
Part V, Page 11
For bidding purposes, Localized Base Failure Repair (Digouts) shall be performed at a maximum depth of 4 inches along Contra Costa Street and a maximum depth of 6 inches along California Avenue.. Localized Base Repair areas to be marked out in the field by the engineer prior to start of construction.
Remove existing roadway section by grinding with a milling machine capable of cutting to a neat line. Do not damage any pavement that is to remain in place. Minimize the disturbance of materials to be left in place during removal or roadway sections.
Remove failed pavement and base rock to the required depth, then grade, water, and thoroughly compact the material remaining in place to a minimum of 95% relative compaction.
Dispose of removed material.
Apply tack coat to the bottom base rock and all vertical surfaces of the existing roadway section Section 39-2.01C (3) (f) of the Standard Specifications, using "Planed pavement".
The surface must be:
1. Textured uniformly
2. Compacted firmly
3. Without depressions, humps, and irregularities
If the base is excavated beyond the specified plane, replace it with HMA. The City does not pay for this HMA. Damage to pavement which is to remain in place shall be repaired to a condition satisfactory to the Engineer, or the damaged pavement shall be removed and replaced with new HMA if ordered by the Engineer. Repairing or removing and replacing pavement damaged outside the limits of pavement to be reconstructed shall be at the Contractor's expense.
The HMA in the base failure areas shall be placed on the same day as the removal. The HMA shall be placed and compacted in two lifts unless shown otherwise on the plans and/or as directed by the Construction Manager. Complete base failure repair prior to opening to traffic under Section 12-
Existing utilities:
Existing utilities located within areas designated for base repair shall be protected-in-place unless directed otherwise by the engineer.
Survey Monuments shall be recorded at the County Records prior to work disturbance. Any that The Contractor shall ensure that the existing survey monuments are preserved in full compliance with California Business and Professions Code, Chapter 15, 8771. To comply with this Section, the Contractor shall engage the services of a Licensed Land Surveyor.
Payment for protecting existing utilities shall be considered as included in the cost of the various items of work shown on the Bid Proposal and no additional compensation will be allowed therefor. 350
Part V, Page 12
13. TACK COAT
General:
This work includes producing and placing tack coat prior to placing hot mix asphalt.
Materials:
The tack coat shall be emulsified asphalt of grades RS1, RS2, SS1, or SS1h, conforming to
EQUIPMENT
Tack Coat
The work to be performed shall consist of furnishing and applying tack coat in conjunction with asphalt concrete overlays and other asphalt concrete paving work.
Tack coat shall be emulsified asphalt of grades RS1, RS2, SS1, or SS1h, conforming to Section The tack coat shall not be applied until the preparation of the existing surface has been completed, and then only so far in advance of placing the asphalt concrete as permitted by the Engineer. Preparation of the surface shall be performed as described in these Technical Provisions. No tack coat shall be left exposed overnight. Immediately in advance of placing the asphalt concrete, additional tack coat shall be applied as directed by the Engineer to areas where previously applied tack coat has been destroyed or otherwise rendered ineffective, and no additional compensation will be allowed for such work.
Tack coat shall be applied to all vertical surfaces of existing pavement, curbs, gutters, and construction joints, against which additional material is to be placed, to a new or old pavement to s Engineer. Shields for protecting
curb faces shall be provided and used during tacking of curb faces. The Contractor shall protect concrete surfaces that are not to be paved against from tack coat spray or splash. Any tack coat more than one inch above the paving surface shall be removed by power washing or other means.
The Engineer will determine if the pavement is sufficiently dry for the application of the tack coat.
Tack coat shall not be applied when the temperature of the surface to be tacked is below 40 degrees Fahrenheit in the shade.
14. GRIND AND OFFHAUL EXISTING ROADWAY
This work shall consist of uniform and variable depth cold planing existing asphalt concrete pavement and removing and disposing of grinded material as shown on existing pavement and aggregate base for Mill and Inlay treatments identified in the plans.
The contractor should be aware there is the possibility of encountering pavement fabric within all streets to be improved as part of this project. Contractor to Bid Accordingly.
Contractor to verify the presence of pavement fabric and/or road mesh prior to construction. Price for removal and disposal of pavement fabric and road mesh is included in the contract unit price cubic yard for this bid item. 351
Part V, Page 13
The surface after cold milling shall be uniformly grooved or ridged unless otherwise specified in the Special Provisions. The outside lines of the milled pavement shall be neat and uniform.
The milled pavement shall be true to grade and cross section. When a straightedge is laid on the finished surface parallel to the centerline of the roadway, the surface shall not vary from the edge of the straightedge more than 3/8 inch (9.5 mm) at any point, except at intersections or at changes of grade. Any areas that are not within tolerance shall be brought to grade within 1 Working Day following initial cold milling.
Cold milling operations shall be performed without damage to the remaining pavement.
Whenever cold milling is adjacent to existing Portland cement concrete curbs, gutters, PCC Bridge structures, and/or pavement, the Contractor shall protect these improvements from damage. Any Portland cement concrete curbs, gutters, PCC Bridge structures, and/or pavement damaged during cold milling operations shall be repaired as directed by the Engineer at the Contractor's expense. Any Portland cement concrete curbs, gutters, and/or pavement that is cracked or displaced shall be removed and replaced at the Contractor's expense. Replaced sections of Portland cement concrete curb, gutter or pavement shall be a minimum of 5 feet (1500 mm) in length or to the next joint.
Milling machines shall be specially designed for cold milling of asphalt concrete, Portland cement concrete, or a combination of asphalt and Portland cement concrete pavement. Milling machines shall conform to the following:
a. The cutting drum shall be a minimum 0[60 inches (1500 nun) wide and shall be equipped with carbide-tipped cutting teeth placed in a variable pattern to produce the desired finish. b. Be self-propelled and capable of removing the pavement to the depth shown on the Plans. c. Be equipped with a conveyor system that will immediately convey the milled material into a transport vehicle for disposal as specified in the Special Provisions. d. Have the capability of spraying water at the cutting drum to minimize dust. e. Be designed so that the operator can observe the milling operation, at all times, without leaving the controls.
f. Be adjustable for slope and depth.
g. Be able to deep cut, in one pass, to the maximum depth recommended by the manufacturer without producing fumes or smoke.
The Contractor shall provide smaller machines if required to cold mill areas that are inaccessible to the larger machine and to provide the surface specified in the Special Provisions.
The cold planing machine shall be specifically designed for automatically controlled profiling. The automatic controls shall provide for accurately establishing profile grades at each edge of the machine by referencing from the existing pavement or an independent grade reference, where required, or be capable of automatically maintaining a designated cross slope from a single reference.
The machine shall be self-propelled and shall have sufficient power, traction and stability to maintain an accurate depth of cut. The machine shall also be equipped with means to effectively control dust generated by the cutting operation.
Immediately following the milling process the Contractor shall have all milled material removed from the job site and disposed of. The milled section shall be cleaned of all loose material. 352
Part V, Page 14
Power-brooming shall be supplemented by hand brooming, when necessary, until the surface is free of deleterious material. Each street shall be swept immediately after the cold planning operation has been completed. Streets shall not be washed to the extent that debris may enter the storm drain system. All streets, gutters and local depression areas of catch basins shall be kept free of dirt, rocks or other debris at all times. During cold planning operations, all catch basin inlets shall be covered with a fabric which will allow the passage of water but will not allow debris to enter storm drain.
Temporary pavement markings shall be provided on all cold planed surfaces if section will be opened to traffic. Refer to Traffic Striping section of these Specifications for pavement striping and marking.
The longitudinal surface deviation of the finished cold planed surface shall not exceed 1/4" inch in 10 feet.
Hand-operated cold plane equipment may be required in areas not accessible to self-propelled machinery.
A motorized street sweeper shall follow within 50 feet (15 m) of the cold milling machine unless otherwise approved by the Engineer.
Unless otherwise specified in the Special Provisions all material removed shall be considered the property of the Contractor and shall be disposed of by the Contractor.
Cold Planing of asphalt concrete pavement shall comply with Caltrans Standard Specifications, 2022 edition, Section 39-3.04. Per CSS Section 39-3.04C(1)2, the cold planing machine shall be equipped with automatic controls for the longitudinal grade and traverse slope of the cutter head.
15. MINOR CONCRETE
General
New concrete facilities including curbs, gutters, sidewalks, ramps, and cross gutters shall be constructed at the locations indicated on the plans or as directed by the Engineer. For curb ramps, allowable construction tolerances do not apply if they would result in any ADA nonconformance in the resulting finished surface grades. Concrete curbs and sidewalks shall comply Refer to Caltrans Standard Plan A88A,A88B, and City of Seaside Standard Plans for Minor Concrete design guidelines. Curb ramps shall have a 6-inch PCC concrete slab as shown in City of Seaside Standard Plan ST-455. Driveways shall have a 6-inch PCC concrete slab as shown in City of Seaside Standard Plan ST-510. All other concrete outside of the curb ramp and driveway footprints shall be 4-inch PCC as shown in City of Seaside Standard Plan ST-415. Cross Gutter and spandrel shall have 8-inch PCC as shown in the City of Seaside Standard Plan ST-720.
Materials
Minor Concrete for curbs, curb and gutter, sidewalks, cross gutters, and driveways must comply with Section 90-2 Minor Concrete of the Standard Specifications.
Concrete mix design
The Contractor shall furnish a concrete mix design to the Engineer at least ten working days prior to the start of the work, based on the following guidelines. 353
Part V, Page 15
Minor Concrete Facilities including curb, gutter, sidewalk, driveways, access ramps, stairs, etc. shall meet the following requirements:
Min. Compressive Strength: 3500 psi @ 28 days
Maximum Slump: 5 inches
The Contractor shall be responsible for all costs associated with the required mix design.
Quality control/acceptance testing
Field testing shall include testing for concrete slump as per ASTM C-143 and compressive strength (C39). Such testing shall be at a frequency determined by the Engineer and shall be or shall furnish the
concrete necessary for casting test cylinders.
Construction
The construction of concrete curb, gutter and sidewalk marked in the field or shown on the plans shall conform to the provisions in Section 73 "Concrete Curbs and Sidewalks" of the Standard Specifications and these special provisions. Standard construction tolerances shall not apply to curb ramps.
Boundaries of concrete curb, gutter, and sidewalk removal have been noted on the plans and shall be removed according to the remove concrete section noted elsewhere in these special provisions, and as directed by the Engineer.
Expansion joints, control joints and scoring shall match adjacent existing improvements or shall be as directed by the Engineer. The new improvements shall match the existing improvements at each end. Provide constant slope between ends if no other elevations are shown on the plans.
Installation shall conform to the State Standard Specifications and the details shown in the Plans and herein in these special provisions.
The existing concrete shall be sawcut full depth prior to removal. Any concrete broken due to the The line and grade of the replaced facilities shall conform to the existing facilities. In most instances, this will consist of a straight line between existing facilities.
Four (4) Inches of Class 2 aggregate base, ¾ in. size, shall be placed under curb, gutter and sidewalks after excavating existing subgrade, as noted on plans, and be compacted to 95% relative compaction (ASTM D-1557)
The Contractor shall water test all repaired curbs and gutters, cross gutters, and other repaired Commercial driveway and alley approaches, including the adjacent curb and gutter section, shall be removed and replaced within twenty-four hours. Curing time shall be seventy-two hours.
All construction surveying and staking will be performed by the City.
Protection of existing facilities
The contractor shall protect existing facilities from damage, and discoloration from concrete splash. Adjacent concrete facilities shall be covered during concrete placement to prevent 354
Part V, Page 16
concrete splash and excess concrete from staining the adjacent concrete. After initial placement, strikeoff and finishing, the protection shall be removed and the adjacent concrete cleaned.
Vertical existing facilities such as light poles, walls, fences, etc. shall be protected with plastic extending a minimum of three feet above the concrete surface. After initial placement, strikeoff and finishing, the protection shall be removed and the vertical surfaces cleaned.
It shall be the contractor's responsibility to protect the existing improvements adjacent to new concrete improvements such as fences, landscaping, irrigation, hardscaping, etc.
Subgrade
After the subgrade is prepared, moisture conditioned, and compacted to 90% relative compaction at zero to three percent over optimum, the Contractor shall continuously maintain the sub-grade in a uniform condition at the moisture content obtained during sub-grade compaction until the concrete is placed.
Forming
Wooden forming shall be of two-inch nominal thickness staked at two-foot intervals. The maximum gap at the bottom of the forms shall be 1-3/4 inches.
Tolerances
The maximum variation from design elevation shall not exceed +/- 0.02 feet. In some instances, particularly in critical drainage areas, tolerances may be reduced to zero. Concrete facilities shall be installed to maintain or provide positive drainage. Questions regarding applicable tolerances shall be directed to the Engineer forty-eight hours in advance of the work.
When shown on the drawings, the concrete shall be set at the design elevations. When existing facilities are to be removed and replaced, they shall conform to the existing elevations and grades. Generally, this will be at a straight line between the start and end points of the removal.
Placing and finishing
General
The concrete shall be deposited on a moist grade in such a manner as to require as little rehandling as possible. Workmen shall not be allowed to walk in the freshly mixed concrete with boots or shoes coated with earth or foreign substances.
Strikeoff, Consolidation, and Finishing
In general, adding water to the surface of the concrete to assist in finishing operations shall not be permitted.
Before final finishing is completed and before the concrete has taken its initial set, the edges shall be carefully finished with the radius shown on the plans or a radius to match the existing construction.
Concrete shall be thoroughly consolidated against and along the faces of all forms and adjacent concrete. After the forms are removed, excess concrete below the form surface shall be removed to be flush with the form face.
All new concrete shall match existing facilities in texture, color, and appearance.
Concrete Protection
The Contractor shall always have materials available to protect the surface of the fresh concrete against rain. These materials shall consist of burlap, curing paper, or plastic sheeting. If plastic sheeting is used, it shall not be allowed to contact finished concrete surfaces. 355
Part V, Page 17
The Contractor shall also protect the concrete against traffic and vandalism. If the concrete is damaged or vandalized, the Contractor shall make the necessary repairs at its own expense.
The repair procedure for damaged or vandalized concrete shall be approved in advance by the Engineer.
Curing
Concrete shall be cured by protecting it against loss of moisture, rapid temperature change, and mechanical injury for at least three days after placement. White or clear liquid membrane compound shall be used. After finishing operations have been completed, the entire surface of the newly placed concrete shall be covered by the curing medium. The edges of the concrete exposed by the removal of forms shall be protected immediately to provide these surfaces with continuous curing treatment.
The concrete shall be allowed to cure for seventy-two hours prior to placing adjacent asphalt concrete.
Joints
Control joints shall be placed at a maximum spacing of ten feet unless shown otherwise on plans.
Control joints in all PCC facilities, except sidewalks, shall be formed by tooling a deep joint or by using expansion joint material. If expansion joint material is used, a minimum of two 1/2 inch by eighteen inch dowels shall be used with additional dowels placed every twenty-four inches.
Control joints in sidewalks may be made using a tooled joint which shall extend a minimum of 1/4 of the depth of the concrete and shall not be less than 1-1/2 inches in depth.
Expansion joints shall be required at a maximum of sixty-foot intervals on curbs, curbs and gutters, cross gutters, swales, and sidewalks. Expansion joints shall also be required on all corners of curbs, curbs and gutters, sidewalks, at the outside boundary of access ramps, and other locations with discontinuities or reentrant corners which may cause cracking.
Nonskid Abrasive Finish
For the stairs, nonskid abrasive finish shall be applied to the treads and landings per Section 51-
1.03E(6) of the Standard Specifications.
Cleanup and Backfill
After the concrete is placed, cured, and the forms have been removed, the Contractor shall clean the site of all concrete and forming debris.
After curing has been completed and the forms have been removed from the new curb and gutter or sidewalk, the resulting void after excavation shall be backfilled with clean native material.
The Contractor shall remove all USA markings, Engineer markings, and Surveyor markings (created for the purpose of the work being done) when work in a particular area is complete by water blasting or other non-destructive method as approved by the Engineer. Sandblasting or grinding to remove markings will not be allowed.
Payment for removing USA painted markings shall be considered as included in the cost of the various items of work shown on the Bid Proposal and no additional compensation will be allowed therefor.
16. REMOVE CONCRETE
The Contractor shall remove and dispose of existing portland cement concrete curb, gutter, sidewalk, driveway, curb ramp, and cross gutter and spandrel, at the locations shown on the 356
Part V, Page 18
Plans. When curb and gutter are removed, the Contractor shall immediately place portable delineators along the edge of the pavement. Portable delineators shall be 36-inch minimum height, orange with white reflectors. The delineators shall be maintained by the Contractor until new curb and gutter are placed. All materials removed shall be legally disposed of in accordance with Section 7-
Existing concrete to be removed shall be sawcut at the nearest joint or score line. Any existing ing and replacing the entire portion
between weakened plane joints or score lines.
Project scope includes removal of existing concrete crosswalks along Holly Street at the intersection of Holly Street and Redwood Avenue.
as specified in Section 7-
17. ADJUST UTILITY COVER/MANHOLES TO GRADE
The work covered by this Section shall include all work and materials needed to adjust existing utility frame, covers, and manholes to grade.
All work and materials for raising water valve boxes and valve covers to finished grade shall conform to the Provisions in Section 15 of the State Standard Specifications and the project plans. Water Valve Adjustments and Relocations shall be coordinated with California American Water Company prior to the start of construction. Final acceptance of the work shall be inspected by California American Water Company.
All work and materials for raising electrical and gas valves, covers, manholes, and vaults to finished grade shall conform to the Provisions in Section 15 of the State Standard Specifications and these Special Provisions. Relocations and Adjustments for electrical and gas structures must be coordinate with PG&E prior to the start of construction. Final acceptance of the work shall be inspected by PG&E.
All work and materials for raising utility vaults shall conform to the Provisions in Section 15 of the State Standard Specifications and these Special Provisions.
All existing manholes, valves, boxes, covers, and vaults are to be reset to the new finished grade conforming to the finish paving elevations. All items are to be inventoried and located whether shown on the Plans or not. Contractor shall wait until the finished paving is complete and then locate, cut out, and expose the existing covers to the new finished grade.
For manholes adjustments, the manhole base shall be covered during the entire operation so that no debris can fall into the sewer and storm drain system. Extreme care shall be taken to prevent spilling foreign material into the drainage or sanitary sewer system. The Engineer may require the Contractor to immediately remove manhole covers for inspection to determine if any foreign material has fallen into the manhole. The Contractor shall be required to immediately remove all foreign material from the manhole's interior.
For adjusting survey monuments, the contractor shall tie out the monument and record with the County surveyor. Once construction is complete, the monument shall be re-established. 357
Part V, Page 19
18. CONSTRUCT STORM DRAIN MANHOLE AND CATCH BASIN
-110, shall be in
conformance with the Project Plans, these Specifications and Section 51 of the State Standard Specifications. A 48-inch diameter manhole shall be constructed when installing pipes up to 24- inch in diameter. A 60-inch diameter manhole shall be constructed when installing pipes greater than 24-inch. Refer to project plans for size and location of proposed storm drain manholes.
Storm Drain Catch Basins along Holly Street shall be constructed per City of Seaside Standard Plan SD-510 except for one Storm Drain Catch Basin at the intersection of Holly Street and e 2025 Caltrans
Standard Plan D72B.
Proposed Manhole locations and Catch Basins locations shown on the plans reflect the intersection of the centerlines of the incoming and outgoing pipes.
Contractor must submit to the Engineer the proposed catch basin and manhole details and specifications. Proposed catch basins and manholes must meet Section 51 of the Caltrans State Standard Specifications and City Seaside Standard SD-510.
All construction surveying and staking will be performed by the City.
19. CONSTRUCT STORM DRAIN PIPES
General
-
Special Provisions and Plans.
Materials
All proposed storm drain pipe shall be HDPE DR-17 or approved equal.
Pipes and fittings must be homogeneous throughout and uniform in color, opacity, density, and other properties. The inside and outside surfaces must be semimatte or glossy in appearance and free of chalky, sticky,, or tacky material. The pipe walls must be free of cracks, holes, blisters, voids, foreign inclusions, or other defects affecting the pipe wall integrity or visible to the naked eye. Do not use pipes or fittings with abrasions or scratches deeper than 10 percent of the wall thickness. The joint surfaces where the gaskets bear must be smooth and free of imperfections, ridges, fractures, or cracks that could adversely affect the joint seal.
Store pipes in unit packages and protect the bell of the pipes from damage. Support unit packages with racks or dunnage to prevent damage and bending. If unit packages are stacked, do not allow the weight of the upper units to cause deformation to the pipes in the lower units. Do not store pipes adjacent to heat sources. Do not allow pipes to overhang vehicles or storage areas unsupported by more than 3 feet.
Cover pipes to provide temporary sun block protection. Provide adequate air circulation around the covered pipes to reduce excessive heat accumulation. Protect gaskets from exposure to weather, heat, ozone, oil, grease, and sunlight for any time period exceeding 48 hours. Do not store gaskets near electrical or exhaust heat sources.
The City reject pipes with cracked or split gaskets. Protect pipes and fittings from damage when handling and installing.
358
Part V, Page 20
Corrugated Polyethylene Pipe
Type S corrugated polyethylene pipe must be manufactured from HDPE virgin compounds and comply with AASHTO 294.
HDPE compounds used in the manufacture of corrugated polyethylene pipe and fittings must comply with AASHTO M 294 except the mix must contain from 2 to 4 percent well dispersed carbon black.
The corrugated polyethylene pipe manufacturer must:
1. Participate in the National Transportation Product Evaluation Program for each plant supplying corrugated polyethylene pipe and fittings for the project.
2. Conduct and maintain a quality control program under National Transportation Product Evaluation Program.
General
This work shall consist of furnishing and installing new and modifying storm drain pipe, catch basins, infiltration chambers, and other structures where called for in the plans and these Special Provisions.
Materials
Storm drain pipe and fittings shall be HDPE (as indicated on the plans).
Dual Wall HDPE- non-perforated, dual wall, smooth interior wall with annular exterior corrugations and shall conform to the provisions of Section 64, Plastic Pipe of the Standard Specifications. Pipe shall be joined using a bell & spigot joint meeting ASTM F2648. The joint shall be soil-tight and gaskets, when applicable, shall meet the requirements of ASTM F477.
Gaskets shall be installed by the pipe manufacturer and covered with a removable wrap to ensure the gasket is free from debris. A joint lubricant supplied by the manufacturer shall be used on the gasket and bell during assembly.
Marking at plant: Each pipe and fitting shall be marked at the plant. Marking shall include size or other information required for each type of pipe.
Construction
excavation and backfilling operations, the Contractor is specifically directed to Subsection 19- improvements, as necessary, in order to avoid causing damage.
Place bedding material at trench bottom, level materials in continuous layer. No pipe shall be laid until the trench subgrade and bedding have been inspected and approved. Laying of lines shall begin at the lowest point in the direction of flow. All piping, fittings, and accessories shall be trench, the pipe shall be inspected. Cracked, chipped, broken, or otherwise defective pipe will be rejected and removed from the job site. Where sewer lines are being crossed, pipelines of 20 foot lengths shall be used with the length centered to provide 10 feet of distance from the sewer line to the nearest joint.
Catch basins, manholes and other structures shall be placed as shown on the plans. Catch basin plumb. Establish elevations and pipe inverts for inlets and outlets as indicated on plans. All 359
Part V, Page 21
penetrations and joints shall be grouted smooth. The catch basin rim elevations shall be installed -
grade around the catch basin inlet must slope to drain storm water into the catch basin, refer to the grading plan. No depressions resulting in the ponding of water will be permitted adjacent to the catch basin grate.
Protect catch basins, pipe, and aggregate cover from damage or displacement until backfilling operation is in progress. Take care not to damage or displace installed pipe and joints during construction of pipe supports, backfilling, testing, and other operations. Repair or replace pipe that is damaged or displaced from construction operations.
Connect new pipe to existing storm drain catch basins, manhole or other structures at the locations shown on the plans. Remove only enough material from the existing structure as necessary to accommodate the new pipe. Grout gap around pipe penetration to form a smooth and watertight seal.
Modify existing structures as called for on the plans.
All construction surveying and staking will be performed by the City.
20. REMOVE EXISTING STORM DRAIN PIPES, MANHOLES, AND CATCH BASINS accordance with Section 71 of the Caltrans Standard Specifications. Existing storm drain pipes designated for removal shall remain operational until the replacement facilities have been installed, tested (if applicable), and accepted, or as otherwise approved by the Engineer.
All removed pipe, manholes, catch basins, and associated materials shall become the property of the Contractor and shall be legally disposed of outside the public right-of-way, except that all existing manhole and catch basin frames and covers shall be carefully salvaged and delivered to the City. The remaining portions of the manholes and catch basins, including all concrete structures, shall be completely removed and disposed of by the Contractor in accordance with these Specifications, the City Standard Specifications, the Caltrans Standard Specifications, and as directed by the Engineer.
All excavations resulting from the removal of existing storm drain facilities shall be backfilled and the surface restored using the same materials and methods specified for trench backfill and pavement restoration, in accordance with the City Standard Plans, Caltrans Standard Specifications, and as approved by the Engineer.
21. SANITARY SEWER PIPE IMPROVEMENTS
General
-
Sanitary Sewer improvements shall be furnished, installed, constructed in accordance with cifications, these
Special Provisions and Plans.
Materials
All proposed sanitary sewer pipe shall be PVC-SDR 26 pipe. 360
Part V, Page 22
The residue form the ignition of the PVC compounds must not exceed 30 percent as determined under ASTM D2584 except the muffle furnace temperature must be 840 ± degrees F.
Pipes and fittings must be homogeneous throughout and uniform in color, opacity, density, and other properties. The inside and outside surfaces must be semimatte or glossy in appearance and free of chalky, sticky,, or tacky material. The pipe walls must be free of cracks, holes, blisters, voids, foreign inclusions, or other defects affecting the pipe wall integrity or visible to the naked eye. Do not use pipes or fittings with abrasions or scratches deeper than 10 percent of the wall thickness. The joint surfaces where the gaskets bear must be smooths and free of imperfections, ridges, fractures, or cracks that could adversely affect the joint seal.
Store pipes in unit packages and protect the bell of the pipes from damage. Support unit packages with racks or dunnage to prevent damage and bending. If unit packages are stacked, do not allow the weight of the upper units to cause deformation to the pipes in the lower units. Do not store pipes adjacent to heat sources. Do not allow pipes to overhang vehicles or storage areas unsupported by more than 3 feet.
Cover pipes to provide temporary sun block protection. Provide adequate air circulation around the covered pipes to reduce excessive heat accumulation. Protect gaskets from exposure to weather, heat, ozone, oil, grease, and sunlight for any time period exceeding 48 hours. Do not store gaskets near electrical or exhaust heat sources.
The City reject pipes with cracked or split gaskets. Protect pipes and fittings from damage when handling and installing.
All construction surveying and staking will be performed by the City.
22. TRAFFIC SIGNS, PAVEMENT MARKINGS, AND PAVEMENT MARKERS General
Traffic Stripes and Pavement Markings shall be Thermoplastic.
Thermoplastic traffic stripes (traffic lines) shall conform to the provisions in Sections 84-1, -
these Special Provisions.
Materials
Thermoplastic
The thermoplastic material shall conform to Section 84- Specifications. Glass beads to be applied to the surface of the molten thermoplastic material shall conform to the requirements of Section 84- of the Standard Specifications.
Standard Specifications for thermoplastic material and glass beads may be obtained from the Transportation Laboratory, P.O. Box 19128, Sacramento, CA. 95819, (916) 739-2400.
Thermoplastic material for traffic stripes shall be applied at a minimum thickness of 0.125-inch.
A primer of the type recommended by the manufacturer of the thermoplastic material shall be applied over all existing painted stripes and pavement legends to be covered with thermoplastic material as shown on the plans.
Construction
361
Part V, Page 23
All construction shall conform to the respective provisions of the Standard Specifications, Existing Striping and Markings
In areas where the existing striping to be replaced and updated, the contractor shall remove and replace all striping using methods as specified in the Standard Specifications by the Engineer.
The Contractor shall replace all striping which has been damaged or obliterated by or during the work. This shall include striping replacement completely across the street even in the event that f each crosswalk shall be completely
restriped even if only a portion of a line has been obliterated. the Contractor shall replace all striping between the adjacent intersections in both directions.
Where a median exists, this work will be required only in the roadway where the work has occurred, unless a detour which altered the pavement markings occurred in the other roadway.
In such cases, the striping will be replaced in both directions.
Layout for Temporary and Permanent Striping
The Contractor shall be responsible for compiling an existing striping and marking plan including but not limited to stop bars, legends, parking stall stripes, crosswalks and other traffic delineation markings within the project prior to removing, obliterating, covering any existing striping, or starting work on the affected street. This plan must be submitted to the Engineer and approved prior to commencing any striping and marking operations on the affected street.
All alignments and layout measurements, and other work necessary to locate and replace traffic stripes and pavement markings shall be performed by the Contractor.
The City will not provide any assistance, information, or materials to the Contractor. It will be entirely the responsibility of the Contractor to perform all necessary pre-construction and construction layout work, obtain all necessary measurements and information, and marking work as specified. All traffic control systems necessary for performing striping and marking, as directed by the Engineer, shall be the responsibility of the Contractor.
The Contractor shall physically tie down the location of the beginning and ending of each paint or thermoplastic marking type in the adjacent curb top. The marking location shall not exceed 50 square inches each. Any locations exceeding this limit shall be removed by the Contractor prior to acceptance of the work. The Contractor shall contact the City Engineer for review of tie downs.
The Contractor shall be responsible for accurately referencing out and replacing the lines and positions of all traffic lines, directional lines, arrows, and other markings in accordance with the plans and City standard markings by cat tracking with painted marks. This shall occur no later than 2 hours behind the final surface course paving operation.
Cat tracking shall consist of stretching a rope on a straight line between control points on tangent alignment and on a true arc through control points on curved alignment and placing spots of paint along the rope. Temporary tab markers shall be placed no Temporary tab markers shall be the same color as the traffic stripe that they are replacing, shall -
Prior to application of permanent striping and markers, the Contractor shall call for review and 362
Part V, Page 24
right to make changes in the location and alignment of line stripes. Striping and traffic markings shall not be applied until after approval is granted by the Traffic Engineer. The Contractor shall allow a minimum of 3 working days for review of the layout by the City.
Schedule
-3.02C,
shall be placed after the surface has been open to traffic for at least ll not be
placed more than 21 days after paving or surfacing.
Permanent traffic striping and markings including legends and arrows shall be placed within 21 days after paving or surfacing, unless otherwise directed by the Engineer.
Temporary yellow marking tape denoting school crosswalks shall be placed the same day that the pavement surfacing is placed.
Failure to comply with these requirements shall result in liquidated damages of $1,000 per day for each street that has not received permanent installation of the required raised pavement markers, traffic striping, and markings.
Pavement Stencils
The Contractor shall use stencils that conform to Caltrans Standard Plans and Details.
Reflective and Raised Pavement Markers Ceramic Non-reflective Pavement Markers No Plastic Installation of both reflective and raised pavement markers shall conform to the provisions of Section 81-
placed in the same pattern and locations as they were previously, except as shown on the plans or modified herein.
Pavement Delineation Extruded Thermoplastic No Spray
Pavement temperature shall be measured at the beginning of the shift on each working day and this information shall be provided to the Traffic Engineer.
No primer or thermoplastic shall be installed within 48 hours from the last measurable rain report as provided by the City.
Thermoplastic traffic striping, legends, and arrows shall conform to the provisions of Section 84-1, - -3,
Pavement Markers Ceramic Non-Reflective Pavement Markers No Plastic Pavement markers shall be placed to the line established by the Contractor and approved by the Engineer, which will consist of temporary painted line or new or existing stripes one for each line of markers.
All additional work necessary to establish satisfactory lines for markers shall be performed by the Contractor.
363
Part V, Page 25
At the option of the Contractor, a hot melt bituminous adhesive may be used to cement the markers to the pavement instead of the Rapid Set Type or Standard Set Type epoxy adhesive.
Bituminous adhesive material shall conform to the following:
Specification ASTM Requirement
Flash Point, COC, ºF D 92 550 Min.
Softening Point, ºF D 36 200 Min.
Brookfield Thermosel
Viscosity, Centipoise, No. 27 Spindle,
20 RPM,400ºF
D 4402 3,000-6,000
Penetration dmm, 100g, 55 seconds,
77ºF D 5 10 - 20
Filler Cement, percent by weight
(Insoluble in1,1,1 Trichloroethane) D 2371 65 - 75
Filler material used in bituminous adhesive shall be Type PC, Grade III, calcium carbonate conforming to ASTM D1199, and shall conform to the following gradation:
Sieve Size Percent Passing
No. 100 100
No. 200 95
No. 325 75
Bituminous adhesive shall be heated indirectly in an applicator with continuous agitation or recirculation. Bituminous adhesive shall not be heated above the maximum safe heating temperature recommended by the manufacturer and shall not be applied at temperatures greater than 425ºF. nor less than 375ºF.
Immediately after application of the adhesive, pavement markers shall be placed in position and pressure applied until firm contact is made with the pavement.
Placement of pavement markers using bituminous adhesive shall conform to the requirements of Section 81-
cleaning shall be required.
The adjustment provisions in Section 9-1.06B of the Standard Specifications shall not apply 364
Part V, Page 26
23. ONE WAY STREET CONVERSION
DESCRIPTION
This work shall consist of furnishing all labor, materials, equipment, and incidentals necessary to convert an existing two-way roadway into a one-way roadway at Holly Street between Ortiz Avenue and Redwood Avenue, including the installation of all required regulatory signs, pavement markings, removal of conflicting traffic control devices, and any other work necessary to establish safe one-way traffic operations in accordance with the Plans, these Specifications, and the latest California Manual on Uniform Traffic Control Devices (CA MUTCD).
The Contractor shall prepare and submit a complete One-Way Regulatory Signing and Pavement Marking Plan to the Engineer and City for review and approval prior to the start of construction. No work associated with the roadway conversion shall begin until written approval has been received.
MATERIALS
All traffic signs, posts, foundations, retroreflective sheeting, pavement markings, markers, and related appurtenances shall conform to the latest Caltrans Standard Specifications, Caltrans Standard Plans, and the latest CA MUTCD.
CONSTRUCTION
The Contractor shall remove or permanently cover all existing signs, pavement markings, striping, arrows, legends, and other traffic control devices that conflict with the proposed one-way traffic operation.
The Contractor shall install all required traffic control devices necessary to establish one-way operation, including but not limited to:
o ONE WAY (R6-1 or R6-2) signs.
o DO NOT ENTER (R5-1) signs.
o WRONG WAY (R5-1a) signs where applicable.
o KEEP RIGHT signs where applicable.
o Directional arrows.
o Lane-use arrows.
o Centerline removal and restriping.
o Edge lines.
o Parking lane markings.
o Stop bars.
o Crosswalk markings.
o Curb markings.
o Delineators and object markers where shown on the Plans. o Any additional signs or pavement markings required by the Engineer or City. 365
Part V, Page 27
ONE WAY signs shall be installed at all intersecting streets, alleys, driveways, and roadway approaches in accordance with the latest CA MUTCD. At unsignalized intersections, ONE WAY signs shall be installed on the near right and far left corners facing traffic entering or crossing the one-way roadway. At signalized intersections, ONE WAY signs shall be installed in accordance with the CA MUTCD requirements.