POTHOLE DAMAGE
TABLE OF CONTENTS
SUMMARY ................................................................................................................................... 2 BACKGROUND ........................................................................................................................... 3 Who Is Responsible for Pothole Damage................................................................................ 3 Why So Many Claims Are Rejected........................................................................................ 3 The California Government Claims Act................................................................................. 4 Why the Civil Grand Jury Conducted This Investigation .................................................... 4 METHODOLOGY ....................................................................................................................... 5 INVESTIGATION........................................................................................................................ 6 How Jurisdictions Investigate Claims..................................................................................... 6 Two Common Reasons for Rejection...................................................................................... 7 Rejection Notices are Often Vague.......................................................................................... 8 Filing a Claim: Determining which Jurisdiction is Responsible .......................................... 9 Filing a Claim: Obtaining and Submitting a Claim Form.................................................. 10 CONCLUSION ........................................................................................................................... 13 FINDINGS AND RECOMMENDATIONS ............................................................................. 14 REQUIRED RESPONSES......................................................................................................... 16 APPENDIX A: Reporting a Pothole ......................................................................................... 17 REFERENCES............................................................................................................................ 18
POTHOLE DAMAGE
SUMMARY
If you hit a pothole within Santa Clara County and damage your vehicle, chances are that your local government will decline to reimburse you for repairs. According to data analyzed by the 2025-26 Santa Clara County Civil Grand Jury (Civil Grand Jury), 92% of pothole claims filed with the County of Santa Clara (County) and the 15 cities and towns in Santa Clara County from 2020 to 2025 were rejected.
People who file claims may find this high rejection rate disappointing. They may also be frustrated by the state law that establishes the claims process, which can often be complex and opaque.
For example, in some jurisdictions, it’s not easy to figure out how to file a claim. Also, while the City of Palo Alto (Palo Alto) and the City of Saratoga (Saratoga) offer e-filing options, claims filed in other jurisdictions must be mailed in or returned in person. And when a claim is denied, the rejection notice often provides little or no explanation.
The County, cities, and towns can and should do better. Specifically, they should:
• Make online claim forms available or easier to find, and include clearer instructions and timelines;
• Provide forms in multiple languages that reflect their specific demographics; • Make it easier for claimants to determine which jurisdiction is responsible for a given roadway;
• Update their rejection letters to specify why claims were denied.
Implementing these changes would make the claims process simpler and more accessible. It would also minimize at least one source of frustration for residents who are already burdened by unexpected repair costs.
POTHOLE DAMAGE
BACKGROUND
For the purposes of this report, a pothole is defined as a depression or hole in the road that forms when pavement breaks apart due to traffic stress and weather conditions.
Potholes can cause severe damage to tires and the underside of vehicles, with a particular risk to two-wheeled vehicles. If drivers believe the local government is responsible for their damage, they can file a claim seeking reimbursement.
According to local media reports, Bay Area drivers in 2022 filed more than 1,000 claims for potholes and other road damages. According to data that the California Department of Transportation (Caltrans) provided to CBS News, it rejected more than 95% of Bay Area claims (Feingold and Manthey, 2024; Manthey and Watts, 2024).
Who Is Responsible for Pothole Damage
Claims for road-related damage must be filed with the state, county, or city agency that has jurisdiction over the road where the damage occurred.
For example:
• Caltrans is generally responsible for major freeways and highways, such as US-101, I-280, and State Route 87.
• The County is responsible for expressways and county roads, such as Capitol and Lawrence Expressways.
• Cities and towns are generally responsible for local streets within their boundaries, including residential neighborhoods.
Why So Many Claims Are Rejected
The Civil Grand Jury requested and received claims data from the County and the 15 cities and towns in Santa Clara County covering the period from 2020 to 2025. The Civil Grand Jury’s analysis of that data revealed that only 9% of pothole claims across Santa Clara County were settled.
Under the California Government Claims Act (Cal. Gov. Code §§ 810 et seq.), local agencies have wide discretion to reject a pothole claim for reasons including but not limited to:
• The claim form was incomplete or not filed by the required deadline;
POTHOLE DAMAGE
• It was filed in the wrong jurisdiction;
• The responsible county, city, or town either was not aware of the pothole or was aware but had not had sufficient time to repair it.
These laws make it difficult for a claimant to dispute a denial. For example, if an agency rejects a claim on the grounds that it was not aware of the pothole, the law does not require it to provide evidence to back up its assertion.
In addition, because different agencies can have jurisdiction over different sections of the same road, it can be difficult for a claimant to determine which agency is responsible for the specific location where the damage occurred. If the person files with the wrong jurisdiction, the agency can reject the claim with no obligation to specify the reason or redirect the claimant to the correct jurisdiction.
If a claim is rejected, the claimant can pursue legal action according to the California Government Claims Act.
The California Government Claims Act
The California Government Claims Act (Cal. Gov. Code §§ 810 et seq.) establishes timelines and procedures for filing lawsuits seeking money or damages from a public entity.
In general, the Government Claims Act specifies that a claim must be filed no later than six months from the date of the incident. The claim must include what happened, what harm occurred, and the amount of compensation requested.
Once the public entity receives the claim, it has 45 days to review, investigate, and decide whether to settle or reject it. If a claim is rejected, the claimant has six months to file a lawsuit.
Why the Civil Grand Jury Conducted This Investigation
The Civil Grand Jury believes that claims processes should be consistent, accessible, and transparent. It also believes the public interest is served by highlighting when processes fall short of that standard.
The Civil Grand Jury conducted this investigation to:
• Examine how local government agencies manage pothole claims; • Understand why so many claims are denied;
POTHOLE DAMAGE
• Recommend how jurisdictions can make it easier for potential claimants to engage in the process.
METHODOLOGY
The Civil Grand Jury requested data from all 16 jurisdictions responsible for road maintenance within Santa Clara County. The data excluded state routes and interstate highways because Caltrans, a state agency, is not subject to Civil Grand Jury review. Jurisdictions provided data about all claims filed against them for road-related damages between 2020 and 2025. Information provided included the number of pothole claims, the amount claimed, the resolution, and the reason for rejection. Three jurisdictions provided response letters sent to claimants.
The Civil Grand Jury reviewed the websites of the following 16 agencies to analyze what content was included and how clearly it was presented:
• County of Santa Clara (County)
• City of Campbell (Campbell)
• City of Cupertino (Cupertino)
• City of Gilroy (Gilroy)
• City of Los Altos (Los Altos)
• Town of Los Altos Hills (Los Altos Hills)
• Town of Los Gatos (Los Gatos)
• City of Milpitas (Milpitas)
• City of Monte Sereno (Monte Sereno)
• City of Morgan Hill (Morgan Hill)
• City of Mountain View (Mountain View)
• City of Palo Alto (Palo Alto)
• City of San José (San José)
• City of Santa Clara (Santa Clara)
• City of Saratoga (Saratoga)
• City of Sunnyvale (Sunnyvale)
The Civil Grand Jury also interviewed representatives from four jurisdictions that together account for about two-thirds of the roads in Santa Clara County. These interviews provided further insight into the agencies’ processes and decision‑making practices.
POTHOLE DAMAGE
INVESTIGATION
There are over 10,000 miles of locally maintained lanes in Santa Clara County (Metropolitan Transportation Commission, 2026). Between 2020 and 2025, the agencies received exactly 400 claims specifically due to potholes.
Of the pothole claims, the Civil Grand Jury determined that the jurisdictions collectively settled 34 claims, or 8.5%. The percentage of settlements for damages varied among the individual entities. The data showed that during that five-year period:
• Gilroy and Saratoga each settled 50% of claims filed (however, they each averaged 1-2 claims per year, among the smallest sample sizes in Santa Clara County). • Four jurisdictions paid at least 10% of claims: Morgan Hill (17%), the County (11%), Santa Clara (11%), and Milpitas (10%).
• The remaining jurisdictions paid 9% of claims or fewer.
The Civil Grand Jury acknowledges that the significance of this data is limited; if an entity received a high volume of claims filed in the wrong jurisdiction, it will not settle those claims.
How Jurisdictions Investigate Claims
Jurisdictions within Santa Clara County generally follow a similar process for receiving and evaluating a claim.
First, the claim gets submitted to a city clerk, city manager, or equivalent official, who logs it along with any accompanying documents. Next, the official notifies the local public works department so it can investigate the incident site as needed.
In the meantime, the official assigns the claim to an investigator, usually in the city attorney’s or county counsel’s office. The investigator verifies whether the agency has jurisdiction, ensures the form was filled out correctly, and reviews any photographs and receipts that were submitted.
If the jurisdiction agrees to pay out the claim, it will often mail a check. But if the claim involves injuries or death, or the claimant is seeking tens of thousands of dollars, the settlement may need approval from the respective city council or the County Board of Supervisors.
If the jurisdiction rejects the claim, it will inform the claimant via a form letter or email. The California Government Claims Act does not require jurisdictions to specify the reason for denial.
POTHOLE DAMAGE
Two Common Reasons for Rejection
According to the data provided to the Civil Grand Jury, claims are frequently denied for one of two reasons: The claim was out of the entity’s jurisdiction, or the County, city, or town had no prior notice of the pothole.
Out of Jurisdiction
A claim must be filed with the agency that has jurisdiction over the specific location where the incident occurred. According to interviews conducted by the Civil Grand Jury, claims that are filed with the wrong jurisdiction will almost certainly be rejected as outside of jurisdiction.
A road’s location within an agency’s boundaries does not necessarily mean that agency is responsible for receiving or resolving related claims. Jurisdiction over road maintenance can shift multiple times as roads cross between state, county, and municipal boundaries. This patchwork of responsibility can be confusing, making it hard for claimants to figure out which agency has jurisdiction over the specific location of their incident.
Agencies typically verify their jurisdiction by consulting their local public works, utilities, or roads departments.
No Prior Notice
The Government Claims Act also establishes limits to the public entities’ liability for the condition of its roadways. One of those limitations is the issue of notice to the public entity. The Civil Grand Jury found this was one of the two most common reasons pothole claims are rejected.
Notice typically requires evidence that at least one of four circumstances exists:
1. The public entity created the condition;
2. The pothole had been reported prior to an incident in which a vehicle was damaged;
3. An agency’s employee observed the pothole and reported it;
4. The pothole existed long enough that the jurisdiction should have known about it through regular inspections.
If none of these circumstances applies, the agency can declare it had no prior notice and deny the claim.
When an agency receives notice of a pothole, state law allows for a reasonable period to address the hazard. It does not specify what constitutes a reasonable timeframe.
POTHOLE DAMAGE
Drivers can help ensure that a jurisdiction receives prior notice by promptly reporting any potholes.
All jurisdictions have a mechanism for reporting potholes and other issues (see Appendix A).
Rejection Notices are Often Vague
As noted above, it is not unusual for an agency to withhold its reason for rejecting a claim. A rejection notice would contain this language, in part, which is required by the California Government Claims Act (Cal. Gov. Code § 913):
NOTICE OF REJECTION OF CLAIM
Dear Claimant,
Notice is hereby given that the claim you presented to (insert title of board or officer) on (date) was rejected on (date).
WARNING
Subject to certain exceptions, you have only six (6) months from the date this notice was personally delivered or deposited in the mail to file a court action on this claim.
See Government Code Section 945.6.
You may seek the advice of an attorney of your choice in connection with this matter. If you desire to consult an attorney, you should do so immediately.
Agencies may provide further information, such as the reason for rejection. A notice of denial can be aggravating enough, but when it is written in minimal legalistic terms, claimants may feel even more frustrated. The Civil Grand Jury learned about rejection letters from the County, Los Altos, Los Gatos, Mountain View, Palo Alto, and San José and found that some but not all rejection letters provide a reason for rejection. Rejection letters from other jurisdictions may follow this same approach.
In Civil Grand Jury interviews, one agency official suggested that people who receive a letter like this contact the agency and see if it will share the reason for rejection. Although the reason for rejection is recorded by the agency, there is no legal obligation to provide this information, and agencies may limit this information.
POTHOLE DAMAGE
Filing a Claim: Determining which Jurisdiction is Responsible Caltrans Jurisdiction
If a pothole is located on a state route or interstate highway, the claim would generally fall under Caltrans’s jurisdiction. These routes, which, according to Caltrans, cover about 250 miles throughout Santa Clara County (California Department of Transportation, 2025) include:
• U.S. Route 101 (US-101)
• Interstate 280 (I-280)
• Interstate 680 (I-680)
• Interstate 880 (I-880)
• State Route 17 (SR-17)
• State Route 35 (SR-35)
• State Route 82 (SR-82), which includes El Camino Real • State Route 85 (SR-85)
• State Route 87 (SR-87)
• State Route 130 (SR-130), which includes part of Alum Rock Road and Mount Hamilton Road
• State Route 152 (SR-152)
• State Route 237 (SR-237)
Residents may not realize that some common local routes fall under Caltrans jurisdiction. These include SR-82, a large part of which includes El Camino Real; Mount Hamilton Road; and SR130, which is part of Alum Rock Avenue.
When a local road crosses or overlaps a state route or interstate, that portion is generally under Caltrans jurisdiction.
County Jurisdiction
Expressways and many county roads are maintained by the County Roads and Airports Department.
Major roads include:
• Almaden Expressway
• Capitol Expressway
• Central Expressway
• Foothill Expressway
• Lawrence Expressway
POTHOLE DAMAGE
• Montague Expressway
• Oregon Expressway
• San Tomas Expressway
• Southwest Expressway
Complicated Exceptions
Further complicating efforts to determine which agency has jurisdiction over a particular area, cities, Caltrans, the County, and even the federal government (such as near Moffett Federal Airfield) have maintenance agreements that specify which agency is responsible for certain roadway segments – such as onramps, offramps, and other defined areas (City of Mountain View, 2019). It is not always easy to determine which agency is responsible for which segments.
Complicated Maps
Some jurisdictions have no public maps indicating which roads they are responsible for. The County and some cities, including San José, Campbell, and Mountain View, do post searchable maps online that can help the public narrow down which jurisdiction is responsible for a particular road. However, the maps often use complicated interfaces rather than a simple image or printout, and many maps are not specific to just the roads maintained by the jurisdictions.
San José, which maintains more than 4,000 miles of locally maintained lanes within its borders, has its own mapping website (Metropolitan Transportation Commission, 2026; City of San José, 2020). It shows whether a particular street within its boundaries is maintained by San José, the County, a private entity, or another agency. The website provides a large amount of information, although it is complicated for the average user to navigate.
An alternative source of information is pavement management plans that some agencies make available. These plans may list all roads maintained by the jurisdiction and can be used as a reference. As an example, Morgan Hill has a link to its latest 2024 Pavement Management Report with a list of streets at the end. However, there is no direct link from the claim forms webpage, so claimants would not be aware of this reference (AMS Consulting, 2025).
Filing a Claim: Obtaining and Submitting a Claim Form
Once a person has found the proper jurisdiction, the next step is to download the claim form from the local agency’s website.
Of the 16 jurisdictions, the Civil Grand Jury found that only Gilroy, Los Gatos, Palo Alto, Santa Clara, and Sunnyvale provide adequate claims process information on their webpages or on the claim form itself.
POTHOLE DAMAGE
Most jurisdictions provide forms only in English. This is an omission that could potentially disenfranchise community members who have limited proficiency in English.
The Civil Grand Jury identified three cities that took the helpful step of providing additional language options:
• Morgan Hill provides a PDF of its claim form in English and Spanish. • Sunnyvale has a translation feature that allows claimants to translate the form into one of 200+ languages. Users can either fill out the translated form online and print a copy or print out a blank translated form and fill it out by hand.
• Saratoga’s website uses a third-party widget to translate its website in addition to an online form to many other languages.
The Civil Grand Jury also investigated how easy it is to find claim forms on each jurisdiction’s website by searching for the term “claim form.”
The Civil Grand Jury could not find any information about submitting a pothole claim in four entities: Campbell, Los Altos, Los Altos Hills, and Monte Sereno.
Cupertino provides a claim form, but users must use the website’s search function to find it.
Gilroy does not link directly to a claim form, although it does provide instructions on how to request a form by email or in person.
POTHOLE DAMAGE
Table 1: Access to online claim process instructions and link to claim form (See References for links)
Jurisdiction Online Claims Process
Instructions
Link to
Claim Form
Caltrans Yes Yes
County of Santa Clara No Yes
Campbell No No
Cupertino No Yes
Gilroy Yes No
Los Altos No No
Los Altos Hills No No
Los Gatos Yes Yes
Milpitas No Yes
Monte Sereno No No
Morgan Hill No Yes
Mountain View No Yes
Palo Alto Yes Yes
San José No Yes
Santa Clara Yes Yes
Saratoga No Yes
Sunnyvale Yes Yes
Many jurisdictions recommend that claimants deliver the claim form in person, including all relevant information, such as photos, receipts, and witness statements. The claimant should retain a signed copy.
Some agencies allow for email submission, but this is the exception. Alternatively, a claimant could submit the claim by mail to the city or town clerk (or, for the County, the Clerk of the Board).
According to the California Government Claims Act, the agency has 45 days from the date the claim form was mailed or delivered in person to respond to the claimant.
POTHOLE DAMAGE
CONCLUSION
Even though state law sets strict rules for filing and reviewing claims, local government agencies retain significant discretion over their processes. By offering clearer online information, improving access to claim forms, expanding language options, and providing more detailed explanations when claims are denied, jurisdictions can significantly improve public trust, reduce frustration, and increase fairness.
Implementing the recommended updates is not only feasible, but it also aligns with the spirit of responsive and transparent public service. The Civil Grand Jury urges all jurisdictions to adopt these improvements by the recommended deadlines to ensure that the claims process is fairer, more consistent, and easier for the public to navigate.
POTHOLE DAMAGE
FINDINGS AND RECOMMENDATIONS
Finding 1
Jurisdictions within Santa Clara County rejected 92% of pothole claims from 2020 to 2025 due to reasons including missed deadlines, incorrect jurisdiction, and lack of prior notice.
Recommendation 1
No recommendation.
Finding 2
Claims are often rejected because the claimant filed with the incorrect jurisdiction, which can happen because jurisdictional lines are often unclear or poorly communicated. The claims websites of all jurisdictions within Santa Clara County lack information about how to determine if a road is in its jurisdiction.
Recommendation 2a
All jurisdictions within Santa Clara County should include a link to a map or list of roads they maintain on their claims website.
The jurisdictions should implement this by December 15, 2026.
Recommendation 2b
All jurisdictions within Santa Clara County should update their claims websites to identify roads that are commonly mistaken as being in their jurisdictions.
The jurisdictions should implement this by December 15, 2026.
Finding 3
Fifteen jurisdictions – the County, Campbell, Cupertino, Gilroy, Los Altos, Los Altos Hills, Los Gatos, Milpitas, Monte Sereno, Morgan Hill, Mountain View, Palo Alto, San José, Santa Clara, and Saratoga – have websites with deficiencies that make it difficult to file a claim.
Recommendation 3a
Eleven jurisdictions – the County, Campbell, Cupertino, Los Altos, Los Altos Hills, Milpitas, Monte Sereno, Morgan Hill, Mountain View, San José, and Saratoga – should update their websites to provide clear instructions and information about how to file a claim in addition to a link to the claim form.
The jurisdictions should implement this by December 15, 2026.
POTHOLE DAMAGE
Recommendation 3b
Fourteen jurisdictions – the County, Campbell, Cupertino, Gilroy, Los Altos, Los Altos Hills, Los Gatos, Milpitas, Monte Sereno, Morgan Hill, Mountain View, Palo Alto, San José, and Santa Clara – should incorporate useable software on their websites that can translate claim forms into multiple languages or provide claim forms in multiple languages based on the demographics they serve.
The jurisdictions should implement this by December 15, 2026.
Finding 4
When pothole claims are rejected, claimants filing claims against the County, Los Altos, Los Gatos, Mountain View, Palo Alto, and San José receive a notice that provides little or sometimes no explanation for the rejection. Although jurisdictions within Santa Clara County are not legally obligated to provide a reason for rejection, the lack of clarity in the decisions made on the claims can add to a claimant’s frustration.
Recommendation 4
The County, Los Altos, Los Gatos, Mountain View, Palo Alto, and San José should update their rejection letters to specify whether the decision was due to lack of timeliness, incorrect jurisdiction, lack of prior notice, or other reason and to provide a specific contact to call or email if the claimant has further questions about the reason for rejection.
The jurisdictions should implement this by December 15, 2026.
POTHOLE DAMAGE
REQUIRED RESPONSES
Pursuant to California Penal Code section 933(a) et seq. and California Penal Code section 933.05, the 2025-2026 Santa Clara County Civil Grand Jury requests responses from the following governing body:
Responding Agency Findings Recommendations
County of Santa Clara 1, 2, 3, 4 2a, 2b, 3a, 3b, 4
City of Campbell 1, 2, 3 2a, 2b, 3a, 3b
City of Cupertino 1, 2, 3 2a, 2b, 3a, 3b
City of Gilroy 1, 2, 3 2a, 2b, 3b
City of Los Altos 1, 2, 3, 4 2a, 2b, 3a, 3b, 4
Town of Los Altos Hills 1, 2, 3 2a, 2b, 3a, 3b
Town of Los Gatos 1, 2, 3, 4 2a, 2b, 3b, 4
City of Milpitas 1, 2, 3 2a, 2b, 3a, 3b
City of Monte Sereno 1, 2, 3 2a, 2b, 3a, 3b
City of Morgan Hill 1, 2, 3 2a, 2b, 3a, 3b
City of Mountain View 1, 2, 3, 4 2a, 2b, 3a, 3b, 4
City of Palo Alto 1, 2, 3, 4 2a, 2b, 3b, 4
City of San José 1, 2, 3, 4 2a, 2b, 3a, 3b, 4
City of Santa Clara 1, 2, 3 2a, 2b, 3b
City of Saratoga 1, 2, 3 2a, 2b, 3a
City of Sunnyvale 1, 2 2a, 2b
POTHOLE DAMAGE
APPENDIX A: Reporting a Pothole
Residents who see a pothole can report it so the jurisdiction can repair it in a timely manner.
Based on a Civil Grand Jury review, here is a list of contacts (as of April 15, 2026) where potholes or other needed street repairs can be reported:
Jurisdiction Website to report a pothole
Caltrans https://csr.dot.ca.gov/index.php/Msrsubmit
County of Santa Clara https://roads.santaclaracounty.gov/services/service-requests Campbell https://www.campbellca.gov/requesttracker.aspx Cupertino https://cupertinoca.citysourced.com/servicerequests/create Gilroy https://seeclickfix.com/gilroy
Los Altos https://www.losaltosca.gov/FormCenter/Public-Works-6/ Maintenance-Service-Request-46
Los Altos Hills https://www.losaltoshills.ca.gov/requesttracker.aspx Los Gatos https://www.losgatosca.gov/FormCenter/PPW-15/Report-aParks-Public-Works-Concern-87 Milpitas https://seeclickfix.com/web_portal/
chZ2d7WdKoe4V2BriJxUCFqd/report/category
Monte Sereno https://www.montesereno.org/forms.aspx?FID=80 Morgan Hill https://www.morganhill.ca.gov/509/Maintenance Mountain View https://www.mountainview.gov/our-city/departments/publicworks/roads-and-transportation/street-maintenance Palo Alto https://www.paloalto.gov/Residents/Services/Report-an-Issue San José https://311.sanjoseca.gov/
Santa Clara https://www.santaclaraca.gov/our-city/government/mayor-andcouncil/contact-city-council Saratoga https://www.saratoga.ca.us/FormCenter/Report-a-Concern6/Fix-It-Form-45 Sunnyvale https://sunnyvale.dynamics365portals.us/neighborhoodcomplaints/
POTHOLE DAMAGE
REFERENCES
Bibliography
AMS Consulting. “Pavement Management Technical Assistance Program (P-TAP) Round 25, 2024/2025 Pavement Management Report.” March 21, 2025.
(https://www.morganhill.ca.gov/DocumentCenter/View/53950/Updated-Morgan-HillPTAP-25-Rev01-for-Web). Accessed April 16, 2026.
Cal. Gov. Code § 810 et seq.
Cal. Gov. Code § 913 et seq.
California Department of Transportation. “California Road Data 2024.” November 2025. (https://dot.ca.gov/-/media/dot-media/programs/research-innovation-systeminformation/documents/hpms/hpms-2024-prd-a11y.pdf). Accessed April 28, 2026.
California Department of Transportation. “Submit Damage Claim.” n.d. (https://dot.ca.gov/ online-services/submit-damage-claim). Accessed April 15, 2026.
City of Cupertino. “Claim Form.” September 2022.
(https://cupertinoca.prelive.opencities.com/files/assets/city/v/1/yourcity/documents/claim-form-rev-102523.pdf). Accessed April 29, 2026.
City of Gilroy. “How to File a Claim.” n.d. (https://www.cityofgilroy.org/966/How-to-File-aClaim). Accessed April 15, 2026.
City of Milpitas. “Helpful Links.” n.d. (https://www.milpitas.gov/188/Helpful-Links). Accessed April 15, 2026.
City of Morgan Hill. “Claim for Damages Form.” n.d. (https://www.morganhill.ca.gov/1411/ Claim-for-Damages-Form). Accessed April 15, 2026.
City of Mountain View. “Claim Form.” n.d. (https://www.mountainview.gov/our-city/ departments/city-attorneys-office/claim-form). Accessed April 15, 2026.
City of Mountain View. “GIS/Mapping Portal, Map Road Centerline” July 18, 2019. (https://data-mountainview.opendata.arcgis.com/search?q=roads). Accessed April 28, 2026.
POTHOLE DAMAGE
City of Palo Alto. “Submit a Claim Against the City.” n.d. (https://www.paloalto.gov/ Departments/City-Attorney/Submit-a-Claim-Against-the-City). Accessed April 15, 2026.
City of San José. “File Claim Against City Form.” n.d. (https://www.sanjoseca.gov/yourgovernment/appointees/city-clerk/forms-filings/file-claim-against-city-form). Accessed April 15, 2026.
City of San José. “Streets.” August 27, 2020. (https://gisdatacsj.opendata.arcgis.com/datasets/CSJ::streets/about). Accessed April 16, 2026.
City of Santa Clara. “Frequently Asked Questions.” July 23, 2015. (https://www.santaclaraca.gov/our-city/departments-a-f/city-attorney-s-office/frequentlyasked-questions). Accessed April 15, 2026.
City of Saratoga. “Claims Against Saratoga.” n.d. (https://www.saratoga.ca.us/FormCenter/ Claims-Form-37/Claims-Against-Saratoga-102). Accessed April 15, 2026.
City of Sunnyvale. “File a Claim Against the City.” n.d. (https://www.sunnyvale.ca.gov/yourgovernment/city-clerk/file-a-claim-against-the-city). Accessed April 15, 2026.
County of Santa Clara. “File a claim of loss against the County.” n.d. (https://cob.santaclaracounty.gov/services/file-claim-loss-against-county). Accessed April 15, 2026.
Feingold, Lindsey and Manthey, Grace. “Less than 4% of Bay Area Caltrans pothole, other damage claims approved in recent years: data.” KGO-TV. January 25, 2024. (https:// abc7news.com/post/bay-area-potholes-caltrans-claims-car-damages/14359988/).
Accessed April 14, 2026.
Metropolitan Transportation Commission. “Pavement Conditions of Bay Area Jurisdictions 2024.” January 5, 2026. (https://mtc.ca.gov/digital-library/5099739-pavement-conditionbay-area-jurisdictions-2024). Accessed April 15, 2026.
Town of Los Gatos. “File a Claim.” n.d. (https://www.losgatosca.gov/2422/File-a-Claim).
Accessed April 15, 2026.
Watts, Julie and Manthey, Grace. “California freeways with the most potholes and car damage claims.” CBS News California. May 23, 2024.
(https://www.cbsnews.com/news/california-freeways-most-potholes-damage-claims/).
Accessed April 14, 2026.
POTHOLE DAMAGE
This report was ADOPTED by the 2025-2026 Santa Clara County Civil Grand Jury on this 12th day of June, 2026.
______________________________
Dinesh Ramde
Foreperson
City of Santa Clara
Agenda Report
1500 Warburton Avenue
Santa Clara, CA 95050
santaclaraca.gov
@SantaClaraCity
26-915 Agenda Date: 8/25/2026
REPORT TO COUNCIL
SUBJECT
Action on the City Council's Response to the Santa Clara County Civil Grand Jury Report Entitled "VTA’s Management and Oversight of BART Silicon Valley Phase II"
BACKGROUND
On or about June 17, 2026, the Santa Clara County Civil Grand Jury published a report entitled "VTA’s Management and Oversight of BART Silicon Valley Phase II" (Civil Grand Jury report) (Attachment 1). The Civil Grand Jury report contains findings and recommendations directed to several agencies, including the City of Santa Clara.
California Penal Code Section 933(c) requires the governing body of a public agency or department that is the subject of a Civil Grand Jury final report to respond within 90 days to the findings and recommendations that pertain to matters under the control of the governing body.
The Penal Code outlines the following legal requirements for responses:
Response Standard for Findings
Penal Code Section 933.05(a) requires the responding entity to report one of the following for each Civil Grand Jury finding:
1. The respondent agrees with the finding.
2. The respondent disagrees wholly or partially with the finding, in which case the response shall specify the portion of the finding that is disputed and shall include an explanation of the reasons therefor.
Response Standard for Recommendations
Penal Code Section 933.05(b) requires the responding entity to report one of the following actions for each Civil Grand Jury recommendation:
1. The recommendation has been implemented, with a summary regarding the implemented action.
2. The recommendation has not yet been implemented, but will be implemented in the future, with a timeframe for implementation.
3. The recommendation requires further analysis, with an explanation and the scope and parameters of an analysis or study, and a timeframe for the matter to be prepared for discussion by the officer or head of the agency or department being investigated or reviewed, including the governing body of the public agency when applicable. This timeframe cannot exceed six months from the date of publication of the grand jury report.
4. The recommendation will not be implemented because it is not warranted or is not reasonable, City of Santa Clara Page 1 of 5 Printed on 8/21/2026
powered by Legistar™
26-915 Agenda Date: 8/25/2026
with an explanation therefor.
Consistent with Penal Code Sections 933.05(a) and 933.05(b), this report contains draft responses for the City Council’s consideration and approval. A response letter will be prepared consistent with the City Council’s direction on the draft responses below and will be transmitted to the Civil Grand Jury.
The City Council’s final responses on the Civil Grand Jury report findings and recommendations are due to the office of the Honorable Julie A. Emede, Presiding Judge, Superior Court of California, County of Santa Clara by September 15, 2026.
DISCUSSION
The Civil Grand Jury report made ten findings and ten recommendations, not all of which require a response from the City. The City of Santa Clara has been directed to respond to two (2) findings (Findings 6 and 7) and two (2) recommendations (Recommendations 6 and 7).
The complete list of all findings and recommendations in the Civil Grand Jury’s “VTA’s Management and Oversight of BART Silicon Valley Phase II” report can be found on pages 27-30 of the document, which is attached to this staff report (Attachment 1) and can also be found on the Civil Grand Jury’s website: https://santaclara.courts.ca.gov/system/files/civil/vtas-management-and-oversight-bartsilicon-valley-phase-ii.pdf Proposed Responses to Civil Grand Jury Findings and Recommendations For the City Council’s consideration, below are proposed responses to the Civil Grand Jury’s findings and recommendations to which the City was directed to respond:
Finding 6
VTA Board Appointing Authority Groups 2 through 5 often do not follow VTA Administrative Code (Section 2-14) admonitions to “appoint individuals with appropriate experience and qualifications in transportation” and to “reappoint representatives to consecutive terms.” Draft Response
The City partially disagrees with this finding.
The City disagrees with the finding to the extent it applies to the City of Santa Clara. Santa Clara is a member of Appointing Authority Group 5, along with the cities of Milpitas and Sunnyvale. The City's appointments to the VTA Board of Directors comply with State law, specifically Section 100060(a)(3) of the California Public Utilities Code, which governs the composition of the Santa Clara Valley Transportation Authority Board of Directors and the representation of cities other than the City of San Jose:
"Five city council members or mayors selected from among the city councils and mayors of all of the cities in the county, other than the City of San Jose, as provided by agreements among those cities.
The agreements may provide for the appointment of alternates, who shall be city council members or City of Santa Clara Page 2 of 5 Printed on 8/21/2026
powered by Legistar™
26-915 Agenda Date: 8/25/2026
mayors, for those city representatives."
The City follows this requirement, and all of its appointees and alternates to the VTA Board are Santa Clara Councilmembers or the Mayor.
Section 2-14 of the VTA Administrative Code provides that Board Appointing Authority Groups 2 through 5 are "strongly encouraged, where possible" to appoint individuals with appropriate experience and qualifications in transportation and to reappoint representatives to consecutive terms.
By its own terms, this provision encourages but does not require either practice. As a practical matter, the City has no way of guaranteeing that one or more of the individuals elected to the position of Councilmember or Mayor had experience or qualifications specifically in the field of transportation.
The requirements to run for such an elected position are set forth in the City Charter, Section 600, et seq. and do not include any requirements for subject matter expertise.
By practice, the City compiles a list each January of Councilmember appointments to City Committees and to regional and outside agency committees for City Council review and consideration. The Mayor recommends which Councilmembers serve as members or alternates, and those recommendations are brought forward at a City Council meeting for the Council to review and approve. Because appointments reflect individual Councilmember interest and the changing needs of the City, and because one City Council cannot bind a future City Council, reappointment to consecutive terms, including on the VTA Board, is not automatic. As a matter of practice, however, the City has generally sought to reappoint the same individual from one year to the next.
The City takes no position on the portion of the finding that concerns the appointment practices of the other agencies in Appointing Authority Groups 2 through 5, as the City has no information regarding how those agencies make their appointments.
Recommendation 6
VTA Board Appointing Authority Groups 2 through 5 should certify to the VTA Board that they will adhere to VTA Administrative Code (Section 2-14) admonitions, regarding Board member expertise and appointment to consecutive terms.
This should be implemented by December 31, 2026.
Draft Response
The recommendation will not be implemented because it is not warranted.
The City appreciates the intent of this recommendation, but it does not plan to bind the City Council to administrative rules adopted by a partner agency. The City will continue to follow the California Public Utilities Code and its current practice, which preserves the City Council's discretion to determine appointments to City boards and committees and to regional and outside agency committees.
The City can and will consider the encouraged actions in Section 2-14 of the VTA Administrative Code when making appointments, where possible; this is what the Administrative Code requires.
City of Santa Clara Page 3 of 5 Printed on 8/21/2026
powered by Legistar™
26-915 Agenda Date: 8/25/2026
However, as stated above, the City cannot guarantee that a future appointee will have experience and qualifications in transportation, nor can it commit a future City Council to reappointing a representative to consecutive terms. Further, this should not disenfranchise Santa Clara voters from having a representative on the VTA Board.
Finding 7
VTA Board Appointing Authority Groups 2 through 5 have different processes for making Board appointments.
Draft Response
The City partially disagrees this this finding.
The City disagrees with the finding to the extent it suggests that the absence of a uniform process results in appointments that do not comply with State law. While Santa Clara does not have an adopted policy or ordinance governing City Council appointments to committees, by practice, the City compiles a list each January of Councilmember appointments to City Committees and to regional and outside agency committees for City Council review and consideration. The Mayor recommends which Councilmembers serve as members or alternates, and those recommendations are brought forward at a City Council meeting for the Council to review and approve. As a matter of practice, however, the City has generally sought to reappoint the same individual from one year to the next. In every instance, the appointment satisfies Section 100060(a)(3) of the California Public Utilities Code.
The City takes no position on the portion of the finding that concerns the processes used by the other agencies in Appointing Authority Groups 2 through 5, as the City is unable to confirm those processes.
Recommendation 7
The cities represented in Appointing Authority Groups 2 through 5 should agree on a uniform process for making Board appointments.
This should be implemented by December 31, 2026.
Draft Response
The recommendation will not be implemented because it is not warranted.
The City appreciates the intent of this recommendation, but it does not plan to commit the City Council to an appointment process that differs from its current practice for making appointments to City boards and committees and to regional and outside agency committees. Each city's approach may reflect its own charter, city policies, and local needs, and State law already establishes who is eligible to serve.
The City remains willing to share its current practice with the other cities in Appointing Authority Groups 2 through 5 should those cities wish to compare approaches.
ENVIRONMENTAL REVIEW
City of Santa Clara Page 4 of 5 Printed on 8/21/2026
powered by Legistar™
26-915 Agenda Date: 8/25/2026
The action being considered does not constitute a “project” within the meaning of the California Environmental Quality Act (“CEQA”) pursuant to CEQA Guidelines section 15378(b)(5) in that it is fiscal activity that does not involve any commitment to any specific project which may result in a potential significant impact on the environment.
FISCAL IMPACT
There is no fiscal impact related to sending the response other than administrative staff time and expense.
COORDINATION
This report was coordinated between the City Attorney and City Manager’s Offices.
PUBLIC CONTACT
Public contact was made by posting the Council agenda on the City’s official-notice bulletin board outside City Hall Council Chambers. A complete agenda packet is available on the City’s website and in the City Clerk’s Office at least 72 hours prior to a Regular Meeting and 24 hours prior to a Special Meeting. A hard copy of any agenda report may be requested by contacting the City Clerk’s Office at (408) 615-2220, email [email protected] or at the public information desk at any City of Santa Clara public library.
RECOMMENDATION
1. Discuss and approve a final response to the Civil Grand Jury Report entitled "VTA’s Management and Oversight of BART Silicon Valley Phase II" and direct the City Attorney to prepare the formal response consistent with City Council direction; and
2. Authorize the City Manager to submit the City’s response to the Civil Grand Jury Report in the form approved, subject only to finalization of response language, as directed, and any technical, conforming, non-substantive modifications approved by the City Attorney, to the Honorable Julie A. Emede, Presiding Judge, Superior Court of California, County of Santa Clara, no later than September 15, 2026.
Reviewed by: Glen Googins, City Attorney
Approved by: Jovan Grogan, City Manager
ATTACHMENTS
1. Civil Grand Jury Report: "VTA’s Management and Oversight of BART Silicon Valley Phase II” City of Santa Clara Page 5 of 5 Printed on 8/21/2026
powered by Legistar™
2025-2026 Santa Clara County Civil Grand Jury
VTA’s Management and
Oversight of BART
Silicon Valley Phase II
June 17, 2026
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II
TABLE OF CONTENTS
SUMMARY ................................................................................................................................... 2 BACKGROUND ........................................................................................................................... 3 METHODOLOGY ....................................................................................................................... 7 INVESTIGATION........................................................................................................................ 8 Financial Risks.......................................................................................................................... 8 Oversight Concerns ................................................................................................................ 13 Coordination with BART....................................................................................................... 21 Board Experience and Continuity......................................................................................... 22 Public Communication........................................................................................................... 25 CONCLUSION ........................................................................................................................... 26 FINDINGS AND RECOMMENDATIONS ............................................................................. 27 REQUIRED RESPONSES......................................................................................................... 31 APPENDIX A: BART Management Letter ............................................................................. 32 CONFLICTS ............................................................................................................................... 34 REFERENCES............................................................................................................................ 34
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II
SUMMARY
The Santa Clara Valley Transportation Authority (VTA) project to extend rapid transit rail service through downtown San José is controversial and the most costly and complex project it has ever undertaken. Known as BART Silicon Valley Phase II (BSVII), the $12.7 billion project extends rail service six miles and includes a large, single-bore underground tunnel and will take 10 years or more from 2026 to complete (VTA, March 2024).
Despite significantly reduced ridership projections and uncertainty about funding sources for both capital and operating costs, VTA has awarded major construction contracts, including for the construction of a launch structure to stage a specialized one-of-a-kind Tunnel Boring Machine (TBM), which will be owned by VTA. Over the next few years, VTA anticipates awarding further construction contracts worth billions of dollars. To reduce uncertainty, the spokesperson for an independent peer review of the project urged VTA to move quickly to “build as much as you can, as fast as you can” (VTA Special Board Meeting, 2025). Such an approach assumes that there will be political will and taxpayer support to finish an incomplete project regardless of cost increases, delays, or reduced ridership.
The VTA’s Board of Directors (Board) has recognized the need for additional oversight and guidance, but the Board has failed to exercise its obligation to provide the strategic direction needed for a successful project. The Oversight Committee it created has been left to define its own role. It was not required to, and does not, provide reports that share available independent analyses of critical issues. The Oversight Committee does not routinely make policy recommendations to the Board and does not hold VTA staff accountable for providing the timely analysis it has requested.
The 2025-26 Santa Clara County Civil Grand Jury (Civil Grand Jury) investigated the role of the VTA Board, its Oversight Committee, its staff, and officials in the management and oversight of the BSVII project.
This report identifies financial challenges, risks, and accountability issues that VTA must address to earn the public’s trust in delivering the Bay Area Rapid Transit (BART) extension to Silicon Valley and to secure support for future sales tax measures.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II
BACKGROUND
The Valley Transportation Authority is a transportation agency established by state law. It is responsible for operating public transit services, including buses, light rail, and paratransit within Santa Clara County. In addition to public transit, VTA is a planning and funding agency for transportation infrastructure projects throughout Santa Clara County. As established by the California Public Utilities Code Sections 100060-100070, the VTA is governed by a 12-person Board of Directors composed of elected officials appointed by the County of Santa Clara (County) and the cities in Santa Clara County, who each serve two-year terms. The Board has many responsibilities and its monthly meeting agendas are lengthy.
The San Francisco Bay Area Rapid Transit District provides regional commuter rail service and is governed by a nine-person Board of Directors elected to four-year termsfrom districtsrepresenting San Francisco, Alameda, and Contra Costa counties. As part of its larger regional system, BART operates the commuter rail service within Santa Clara County.
By contract with BART, VTA is solely responsible for paying the capital and net operating costs of extending commuter rail service into Santa Clara County (BART and VTA, Comprehensive Agreement, 2001). Although the County was not included in the legislation establishing BART, voters of Santa Clara County supported three sales tax measures which provided funds to plan, build, and operate the extension of BART to Santa Clara County. Today, 1.625% of sales tax collected in Santa Clara County supports VTA and other local jurisdictions (see Table 1). If a currently proposed measure qualifies for the ballot, in November 2026, voters will decide whether to approve an additional 0.5% sales tax to fund local transit, which would increase the County’s base sales tax rate from the current 9.75% to 10.25%.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II Table 1: Countywide Sales Tax in Santa Clara County, Effective April 2026 Description Sales Tax % Expiration Funding Purpose
California Base 7.250% No Expiration
State General Fund
Local Revenue Fund
Local Public Safety
Health & Social Services
1976 Measure A 0.500% No Expiration Transit: VTA
2000 Measure A 0.500% 2036 Transit: VTA, BART Silicon
Valley
2008 Measure B 0.125% 2042 Transit: BART Silicon Valley 2016 Measure B 0.500% 2047
Transit: VTA +
County/City/Caltrain/Caltrans
Infrastructure
2012 Measure A 0.125% No Expiration County General Fund 2020 Measure RR 0.125% 2050 Transit: Caltrain
2026 Measure A 0.625% 2031 General incl. Healthcare
Total Base Sales Tax
Rate 9.750%
Data extracted from: California Department of Tax and Fee Administration. 2026. (https://cdtfa.ca.gov/formspubs/cdtfa105.pdf); VTA Annual Comprehensive Financial Report.
Note: Some cities have higher voter-approved rates in addition to the County base rate; Highlighted section of the table refers to sales tax measures that fund VTA.
The first phase of BART to Silicon Valley extended service to Milpitas and then to the Berryessa Transit Center (Berryessa). Construction started in 2012 and was completed in 2020. Ridership for Phase I has not met forecasts, and due to operational, maintenance, and depreciation expenses, VTA has experienced significant financial losses. According to data reviewed by the Civil Grand Jury, BART to Silicon Valley Phase I has lost an average of $69 million annually during the first five years of operation.
The second phase consists of a six-mile, four-station extension from Berryessa through downtown San José to the City of Santa Clara. For this phase, VTA is targeting completion by 2037. As a condition of federal funding, the Federal Transit Administration (FTA) has appointed a Project Management Oversight Consultant (PMOC). The PMOC uses a more conservative schedule and forecasts completion in 2039 (AtkinsRéalis USA Holdings LLC, 2026).
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II At an early planning stage in 2014, the BSVII project cost was estimated at $4.7 billion. By 2020, the cost estimate increased to $6.9 billion. In 2022, based on the PMOC’s projected cost analysis, VTA submitted an estimate of $9.1 billion to the federal government for an Early Start Grant. In October 2023, VTA estimated the construction cost at $12.2 billion with operations to begin in 2036. The most recent estimate is $12.7 billion, and operations are pushed back to 2037 (VTA Auditor General Report, January 2024).
The project's funding sources include federal and state grants, as well as local revenues from voterapproved sales tax measures. All the funding sources are subject to risks, which are identified in this report. Figure 1 shows the funding sources with $700 million to be determined (TBD) and $375 million from a potential ballot measure in November 2026.
Figure 1: Components of $12.7 Billion in BSVII Funding Sources as of April 2026 Source: vtabart.org website (accessed April 9, 2026)
Although two years earlier, VTA had asked for a federal commitment of $6.3 billion, in August 2024, the FTA announced that its share of funding would be capped at $5.1 billion (Geha, 2024).
VTA was forced to increase its reliance on local sales tax revenue and still faced a gap of approximately $700 million (VTA, Summer 2025). To reduce project costs, VTA has been studying design changes while maintaining the full six-mile extension with four stations. Options discussed by VTA staff and officials include (VTA, November 11, 2024):
• Simplifying station configurations;
FTA New Starts --s
$5,098M
Available Loe~
- Measure
$502M
Local _____/
$4,5 4M
TBD
,,,,--$700M
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II • Modifying the Santa Clara Newhall Yard and Maintenance Facility; • Modifying the tunnel and station ventilation systems; • Substituting a surface parking lot for a parking structure; • Reconfiguring the tunnel to use less concrete and steel.
In addition, the funding strategy assumes $375 million from the yet-to-be-approved regional sales tax measure for a total outstanding gap of $1.075 billion.
Due in part to the significant increase in estimated cost and a perceived lack of communication about the project’s cost, risks, and schedule, the Board conducted a workshop in October 2023 to review the project’s status. At this workshop, individual Board members expressed a lack of confidence in the VTA staff’s management of the project and requested a new system of oversight and project management.
In response, the Board chair established an Ad Hoc BART Silicon Valley Phase II oversight committee (Oversight Committee) responsible for overseeing all aspects of the project, focusing on a full, independent, and transparent review of costs, funding, risks, and completion schedule.
The Oversight Committee’s bylaws later stated that its purpose was to provide “guidance and oversight” of the project (VTA, April 4, 2024).
The VTA independent auditor general was tasked with providing staff support to the Oversight Committee and was authorized to contract with Subject Matter Experts (SMEs) to independently review and comment on VTA staff recommendations regarding costs, risks, and schedule. In turn, the Oversight Committee authorized the SME firm, Gall Zeidler (GZ), to independently assess the risks and viability of cost-saving alternatives.
In a 2001 Agreement, VTA and BART agreed to cooperate in the project’s planning, design, and construction. They established a series of interagency committees, the latest of which is the Joint VTA/BART Working Committee, which depending on the availability of its members, is scheduled to meet quarterly. BART staff members have been assigned to co-locate with VTA engineers to participate in the preparation and review of BSVII designs in accordance with the agreed Project Design Criteria Manual. According to the BART Inspector General, VTA has reimbursed BART $19.2 million through 2025 for the cost of the assigned employees (BART, December 19, 2025). In August 2025, the BART assistant general manager, operations, rejected some of VTA’s proposed design changes and scope reductions and complained about inadequate coordination (see Appendix A). The BART inspector general issued a report in December 2025 that also raised concerns about inadequate coordination and criticized VTA’s communication with BART officials (Id.).
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II
METHODOLOGY
The Civil Grand Jury reviewed every meeting of the BSVII Oversight Committee, as well as select VTA Board meetings. This included reviewing agendas, minutes, agenda item reports, public comment submittals, and associated discussions.
In addition, the Civil Grand Jury conducted 17 interviews of officials from VTA, BART, and the State of California. The Civil Grand Jury also reviewed publicly available documents as described in the reference section, as well as documents requested from VTA and submitted to the Civil Grand Jury.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II
INVESTIGATION
The Civil Grand Jury investigation of the BSVII project covered critical aspects of VTA’s management and oversight, including:
• VTA’s funding strategy and its reliance on voter-approved sales tax measures, some of which expire before completion of the project, and some of which have yet to be approved; • The establishment of a separate Oversight Committee which provides guidance on the BSVII project and how it evaluates independent analyses provided by the VTA auditor general, contracted SMEs, and the federally mandated PMOC; • The contractual and practical requirement to closely coordinate with BART, which will serve as the system operator;
• The impact of the VTA Board’s governance structure on the effectiveness of strategic direction, management, and oversight of the project;
• VTA’s approach for keeping the public informed of costs, risks, and schedule.
Financial Risks
The 10-year project completion timeline of BSVII exposes VTA to financial risks that require careful, ongoing assessment of capital and operating costs, including that:
• Rising labor and material costs, combined with aggressive construction methods and schedules, may increase total project costs and strain the budget’s contingency for unforeseen risks and unexpected expenses;
• Delays or reductions in state and federal funding will create greater pressure to rely on local funding sources or scale back the scope of the project; • Lower ridership levels will increase VTA’s ongoing obligation to pay net operating costs, which would necessitate service level reductions or voter approval of new or extended sales tax measures;
• Failure to maintain a cash-flow model exclusive to BSVII, means that contracting options for accelerating work may not be able to be financed with available resources.
Risk of Increased Costs of Labor and Materials
The FTA fiscal year 2025 New Starts Financial Assessment report for BSVII stated the VTA inflation estimate was optimistic. If labor and material costs were to rise above those estimated in VTA’s budget, it could lead to funding shortfalls (FTA, 2024).
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II The VTA auditor general’s May 1, 2025, report to the Board also identified BSVII financial risks associated with project construction costs. The report found that the assumptions and historical data underlying VTA’s financial plan could be more robust to enable the Board and the public to evaluate the financial risk associated with the potential cost increases (VTA, 2025).
Another factor that increases the difficulty in predicting materials and labor costs is the possible extension of the 2037 project completion date. The longer timeline for BSVII increases the likelihood that future costs will differ from current estimates, thereby increasing financial risk.
Local, State, and Federal Funding Risks
The capital cost of construction and the net operating costs are to be paid by VTA from specific revenue sources, some of which are grants with fixed amounts.
The financial risks identified by the Civil Grand Jury have been experienced by other major transit agencies. For example, the various rail projects of the Los Angeles County Metropolitan Transportation Authority (LA Metro) faced escalating cost estimates, reductions in federal funding, cuts into smaller construction segments to match available funding, and shifting agency priorities (Shalby, 2026).
Local Funding Risks
VTA’s capital financing plan calls for the 2016 Measure B to pay $2.5 billion and for the 2000 Measure A to pay $2.0 billion of the estimated $12.7 billion BSVII project. Measure A expires in 2036, before BSVII is expected to be completed. Measure B expires in 2047 (VTA, About 2016 Measure B, n.d.). As the project’s cost estimates have evolved, so have the planned funding sources. Measure B has become a much more significant source of proposed funding.
Because Measure B also funds bus transit, local streets, and highway projects, there are built-in limitations on the amount available to close a BSVII financing gap. Measure B limits spending on BSVII to 23.8% of net sales tax revenue over its 30-year life (FTA, 2024). Net sales tax revenue (defined as Program Tax Revenue in the measure) is calculated as the amount remaining after deducting administrative costs and any debt service.
To close current and potential future funding gaps, VTA could issue bonds to be repaid from Measure B sales tax revenue. However, this would reduce the revenue available for other voterapproved projects. Every dollar spent on debt service for BSVII is a dollar that cannot be spent on
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II the other transportation projects approved by the voters. Because of bond issuance and interest costs, the total project costs would exceed the current estimate of $12.7 billion.
Another risky approach to filling funding gaps would allow the Board to change the rules and permit a greater percentage of Measure B net sales tax revenue to be used for BSVII. One VTA official acknowledged to the Civil Grand Jury that this would be a “heavy lift” because VTA would first have to notify all the local agencies of the proposed increase in the percentage limit and then approve it by a ¾ vote of the Board (9 of 12 Board members). The County and the cities that have planned other transportation measures are likely to object to reduced funding for their projects.
Of course, more Measure B funds could become available to support the capital costs of BSVII if the expected sales tax revenue exceeds previously anticipated levels. While early projections were based on 2016 economic conditions, it is important for the strategic funding plan that the sales tax forecast be updated regularly. The Civil Grand Jury wasinformed that VTA has ordered an updated forecast.
Because two key sales tax measures are set to expire, several VTA officials stated in interviews that they would simply place a measure on a future ballot for voter consideration if an extension were needed. Given the current sales tax rates applicable within Santa Clara County and the need for management and oversight reforms identified in this report, there is a risk that voters may not approve such a measure.
State Funding Risk
As of April 2026, the capital construction funding strategy required $1.5 billion from two State of California grants. The VTA has received commitments for nearly $200 million of that total. The sources of funding are the Transit and Intercity Rail Capital Program (TIRCP) and transportation funds administered by the Metropolitan Transportation Commission (MTC), both of which may be affected by a recent state decision to provide a bridge loan to Bay Area transit agencies (MTC, 2026).
In February 2026, the California legislature appropriated $590 million from the same TIRCP account to provide a 12-year loan to MTC. These loan proceeds will be made available to San Francisco Municipal Transportation Agency, AC Transit, BART, and Caltrain to help address a greater need for public transit subsidies. The agencies are required to repay the loan over 12 years (MTC, 2026).
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II The state justified the loan on the basis that the transit agencies would be able to stabilize their financial situations and avoid service reductions pending the anticipated approval in November of a regional sales tax measure. If the regional measure does not pass, or if for any other reason the agencies do not repay the loans on time, the timing of the receipt of funding to VTA might create some cash flow risk for the project.
Further, the TIRCP account itself is funded by payments from private parties who agree to purchase pollution credits in the state’s Cap and Invest program. The program’s future is uncertain in light of federal changes to environmental regulations and pending legal challenges from the State of California (California State Transportation Agency, n.d.).
Federal Funding Risk
In August 2024, the FTA advised VTA that the federal government’s total contribution to the project would be limited to $5.1 billion. To receive these funds, VTA plans to apply for a Full Funding Grant Agreement (FFGA) by the end of 2026.
Federal support for large-scale rail projects is uncertain. In 2025, the FTA canceled a $4.2 billion commitment to the California High-Speed Rail Project (Shalby, 2025). VTA’s lobbyists have suggested delaying the FFGA application until similar requests from other states are resolved.
Considering the political, economic, and budgetary conditions of the United States, approval of VTA’s request for an FFGA is highly uncertain. It may be delayed, reduced, or denied.
Low Levels of Ridership Could Increase VTA’s Future Costs BART ridership on the current regional system has not recovered to pre-pandemic levels.
Ridership in January 2026 remains only 48% of the levels in January 2019 (BART, January 2026; BART, 2019). Recovering ridership may prove difficult due to the growth of hybrid work patterns.
The Civil Grand Jury also reviewed the forecasts for the first phase of the project, which included the new Milpitas and Berryessa stations. For January 2026, ridership was 86% below estimates (see Table 2).
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II Table 2: BART Ridership at Milpitas and Berryessa Stations Forecast for Average Daily
Weekday Ridership for
June 2021 at launch
Actual Ridership,
January 2026
Ridership/Day 20,110 2,789
Source: Joint VTA/BART Working Committee Meeting, December 4, 2020; BART February 2026 Monthly Ridership Snapshot.
Note: VTA created forecasts in 2020, expressed as rides per day. BART actuals are based on recorded station entries and exits. To normalize BART actuals to the VTA forecast, entries and exits were averaged to produce a daily ridership figure.
An overall decrease in ridership hasled BART to project a $376 million budget deficit for FY2026-
27. To seek additional revenue, BART is relying on a 0.5% additional sales tax measure on the November 2026 ballot that would begin in 2027 and remain in place for 14 years. If the ballot measure does not pass, BART has proposed closing up to 15 stations and reducing service hours and train frequency (BART, February 26, 2026). Ironically, the proposed station closures would not affect Santa Clara County because VTA is solely responsible for the net operating costs.
According to VTA records reviewed by the Civil Grand Jury, for the first three years of operation, VTA forecasts annual average costs of $274 million for operations, maintenance, and capital costs.
Average fare revenue is forecast at $60 million, offsetting VTA's financial obligation to BART, resulting in an average annual financial loss of $214 million. Any drop in ridership will lead to further financial losses.
The Need for a BSVII Cash Flow Model
With a price tag of $12.7 billion, BSVII is the largest public infrastructure project in Santa Clara County (Aragon, 2025). Nearly 60% of the planned funding sources include revenue from grants that will not be distributed in advance but will be reimbursed in accordance with each grant’s draw schedule (See Figure 1). The timing of those cash inflows must be carefully matched with the timing of payment schedules for construction contracts worth billions of dollars.
VTA staff is evaluating different approaches to contracting the construction work. Alternatives are being evaluated for the following reasons: 1) to identify segments of work that could be bid out separately to accelerate the overallschedule; and 2) to identify segmentsfor which there is a greater likelihood of strong competitive bids. For each contract, the cash outflows will be specified and must be carefully matched with the cash inflows.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II A cash flow model that matches receipts and expenditures for BSVII would enable VTA decisionmakers to fully evaluate the alternative approaches being studied. However, VTA officials have advised the Civil Grand Jury that such a model has not yet been developed. A cash flow model is necessary to avoid unplanned delays from cash shortfalls.
Oversight Concerns
VTA Board Recognizes That Oversight Must be Improved
Independent reports and audits have identified problems with project management and VTA Board oversight, including those identified by a prior Civil Grand Jury, the California State Auditor, and the PMOC (AtkinsRéalis USA Holdings LLC, 2026). VTA’s cost-estimation practices, along with its lack of transparency around changes to project scope and cost, were identified as significant deficiencies. VTA’s oversight and management of the BSVII project have also been heavily criticized by the media, in public comments presented at Board meetings, and in lettersto the editor of multiple local publications.
VTA Board Outsources Guidance and Oversight of the BSVII Project Following a workshop on the project’s direction in October 2023, the VTA Board Chairman announced the creation of an Ad Hoc BART Silicon Valley Phase II Oversight Committee (VTA, 2023).
However, only the Board can make binding decisions on the project’s scope, funding, risks, schedule, and contracting approach. While ultimately accountable itself, the Board nonetheless effectively delegated oversight to a committee without providing clear direction. By abdicating its responsibility to set its expectations of how the Oversight Committee can best support the Board, the committee has been left to set its own course. That course does not keep the Board fully informed of issues raised by independent experts or the PMOC, hampering its ability to make the best decisions about the project's funding and schedule.
At its meeting on January 15, 2026, the Oversight Committee adopted what it called a revised charter intended to clarify the lines of communication and relationships among the auditor general, SME, VTA staff, and Oversight Committee (VTA, January 15, 2026). Members of the Oversight Committee had expressed concern about a perceived lack of coordination between VTA staff and the SME. Nonetheless, the question remains: Is the role of an SME to provide the Board with an independent review of VTA staff recommendations as originally intended, or is it to help VTA staff improve their recommendations? Notably, in the following excerpt, the Charter requires the
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II auditor general to document issues raised by the SME and the VTA staff but does not require that the full Board be advised of the critical issues:
To ensure transparency and balanced oversight, selected advisory input from SME will be documented in Oversight Committee materials. Where consensus exists between the SME and the Project Team, it will be noted. Where minority or dissenting views are expressed, the AG [auditor general] will explicitly record final input received alongside the majority view (VTA Oversight Committee Charter, 2026).
During Oversight Committee meetings, there are few deliberations or actions to provide collective guidance or oversight, leaving individual members to raise questions and propose guidance for VTA staff to consider. VTA staff also receives input from individual members in private premeeting briefings. As a result, the full Board does not benefit from Oversight Committee analysis, and the public is not fully informed about individual Board member perspectives.
The Committee Has Two Purposes: Guidance and Oversight
“Guidance” suggests that the committee helps the Board establish a strategic direction and recommend actions to keep the project on track. “Oversight,” on the other hand, is a separate function that ensures VTA staff is accountable for following the Board’s direction in an efficient and effective manner. “Guidance” looks forward. “Oversight” monitors implementation as it happens.
Better at Oversight than Guidance
The Oversight Committee requires VTA staff to produce a comprehensive monthly report detailing the financing and construction progress of the BSVII project. The auditor general provides insightful periodic reports on his independent review of the project’s costs, risks, and schedule.
The VTA staff’s monthly reports address the information gap identified in the auditor general’s January 2024 report. As a result, the Oversight Committee can effectively monitor compliance with the Board’s direction.
However, the Oversight Committee often fails to provide guidance on issues critical to future strategic direction.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II Strategic Guidance on Critical Issues is Informal, Intermittent, and Often Late VTA staff routinely provide private briefings to Oversight Committee members prior to meetings.
Those briefings allow VTA staff to explain and advocate for their recommendations and to receive input and questions from individual members. Occasionally, some agenda materials for an Oversight Committee meeting are not published with the rest of the agenda because VTA staff members will modify presentations up to the last minute based on what they have heard in private briefings.
The Oversight Committee has established an informal standard of limiting its once-monthly meetings to no more than two hours, and meetings often do not begin on time. At the meetings, VTA staff often deliver lengthy presentations on issues for which it will subsequently seek Board approval, leaving little time for committee deliberations.
During these presentations, only a few members ask questions, and rarely does a committee member propose a policy recommendation that the Oversight Committee might take action on.
Individual Oversight Committee members are given the opportunity to express support or concern about a proposed VTA staff position, providing VTA staff with some insight into how to frame their recommendations to the Board.
The Oversight Committee receives independent analyses from the VTA auditor general, its contracted SME, and the PMOC. The committee often receives lengthy written comments from the public but limits oral comments to one minute. Members of the committee rarely comment on materials received from the public, many of which are extensive critiques of the VTA staff recommendations. Following each meeting, the Oversight Committee chair submits a short report summarizing discussion topics, which is placed on the VTA Board’s consent calendar.
Following presentation to the Oversight Committee, formal VTA staff recommendations are made to the VTA Board, but without the benefit of a summary or synthesis of the alternative perspectives from the auditor general, SME, PMOC, or informed public comment.
The Civil Grand Jury identified three examples of policy issues for which guidance was needed but delivered inadequately. One of the examples, the single-bore versus twin-bore issue, illustrates both the failure of the committee to make recommendations and the VTA staff’s failure to follow through on committee requests in a timely manner.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II Example of Inadequate Guidance: The KST Contract Decision The Oversight Committee endorsed a major contract change without providing independent analysis, articulating its rationale, or conveying identified risks to the Board.
VTA had issued a contract to a construction consortium, Kiewit Shea Traylor (KST), using a “progressive/design/build” approach, under which KST would design the tunnel project and, after reviews by VTA and its construction management consultant, KST would build it. By the spring of 2025, VTA believed that KST’s proposed design could significantly increase the project’s estimated cost by up to $1 billion and that it would be preferable to engage in a competitive bidding processfor the remaining tunnel work. In a more traditional contract approach, VTA would prepare the design specifications and contract conditions. To accomplish this, it was necessary to limit the contract with KST to only the work required to prepare for the TBM, which VTA would own but make available to the tunneling contractor to operate and maintain.
At its June 12, 2025, meeting, VTA staff presented its proposal to modify the KST contract to the Oversight Committee, which unanimously endorsed it. Two weeks later, the VTA Board met and approved VTA staff recommendations. Although the VTA staff agenda report did include a reference to the Committee’s recommendation, it did not include the risk analysis that had been reviewed by the Committee. The Oversight Committee’s regular report to the VTA Board was placed on the consent calendar and simply reported the committee’s concurrence with the VTA staff recommendation. There was no report or analysis laying out the reasons for the Oversight Committee’s concurrence or the SME’s risk assessment. Therefore, the Board made its decision without a complete understanding of the risks.
Example of Inadequate Guidance: The Twin-Bore versus Single-Bore Decision The Oversight Committee retroactively requested a side-by-side analysis of tunnel options through Downtown San José.
A preliminary design controversy was whether to tunnel two smaller bores for the downtown San José underground tracks or to tunnel a single larger bore at greater depth. Downtown businesses had raised concerns that the twin-bore approach would require additional work and disrupt their operations during construction.
BART initially opposed the single-bore tunnel approach because it differed from its existing, smaller twin-bore tunnels. However, the BART inspector general reported that in the spirit of
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II cooperation, BART officials consented to the single-bore approach after being assured that operational and safety concerns would be met (BART, December 19, 2025).
In December 2022, VTA approved the fabrication and purchase of a large TBM for $76 million, effectively locking in the single-bore approach. In a news article dated November 7, 2023, in the Mountain View Voice, San José Mayor Matt Mahan was quoted as saying: “There is no turning back now” (Hicks, 2023).
Nonetheless, individual Board members and informed public commenters continued to raise questions about whether a twin-bore approach might be cheaper, faster, and safer for BART operations. In response, members of the Oversight Committee commissioned an analysis of the two options for costs, risks, and impact on schedules.
In September 2025, more than 18 months after the request, VTA and its engineering consultants presented their analysis to the Oversight Committee, confirming the single-bore approach.
Although it had requested the analysis, the Oversight Committee did not make a recommendation to the Board. In October 2025, the Board was presented with the VTA staff and consultants’ analysis and confirmed the single-bore approach by declining to take steps to amend the environmental documents or modify the tunneling contracts.
Example of Inadequate Guidance: Scenario 1 versus 1a Decision In October 2025, VTA decided on an approach to the construction of the tunnel without the benefit of the SME’s analysis that the Oversight Committee had requested.
Before design work could progress to a more advanced level, the VTA Board needed to decide between two alternatives for staging the actual tunneling work. The SME had suggested that concurrent tunneling from both ends could reduce costs and accelerate the schedule (VTA, June 12, 2025). The two options were labeled “Scenario 1” (a straight-through tunneling using the larger TBM from west-to-east) and “Scenario 1a” (an option of concurrent tunneling starting at both the east and west portals using two TBMs).
Although this would require two TBMs, the east-to-west work could be done simultaneously with a smaller-bore tunneling machine. Further, the SME reported that a smaller-bore TBM was readily available and would require less lead time than the TBM being fabricated in Germany.
Because the Oversight Committee considered the potential benefits significant, the committee asked both VTA staff and the SME to analyze the options and prepare a recommendation. On
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II August 4, 2025, the Oversight Committee authorized an expenditure of $110,000 and directed the auditor general to contract with GZ for the requested work. GZ presented interim reports on September 11, 2025, and October 9, 2025, and promised to deliver its completed report at the November 2025 meeting of the Oversight Committee.
VTA staff subsequently presented its analysis and recommendations to the Oversight Committee on October 9, 2025. Although the Project Manager stated that the VTA staff was aware of some of GZ’s preliminary analysis (especially differing assumptions about the rate at which each of the two TBMs can move forward when digging a tunnel), VTA staff requested a Board meeting to decide between the two alternatives. In prior presentations to the Oversight Committee, VTA staff said that the analysis would be presented at a Board “workshop” (at which no formal action could be taken). However, a special meeting of the Board was called for October 17, 2025, and VTA staff made its recommendations to the Board, neglecting to advise the Board that the Oversight Committee was still awaiting the GZ analysis that the Committee had authorized.
The Oversight Committee failed to present any report or recommendation at the special meeting.
As a result, the Board adopted ‘Scenario 1’ without the benefit of an independent analysis of the risks.
On February 12, 2026, four months after the Board made its decision, the SME presented his written report analyzing the options and raising concerns that should have been considered before the decision.
VTA Staff Accountability for Responding to Oversight Committee Member Requests The auditor general maintains two types of monitoring reports: a tracking report that lists the requests of individual committee members for information or analysis, and a work plan that lists the schedule for upcoming formal reports, including risk assessments such as financing and procurement risks. Both monitoring reports establish a due date, but the deadlines are often not met.
During public meetings, Oversight Committee members rarely discuss the tracking report or the work plan and do not publicly comment on changes to the expected date in subsequent reports.
More importantly, neither the auditor general nor the Oversight Committee holds VTA staff accountable for late responses to issues raised in the tracking report. Below, the Civil Grand Jury presents two examples:
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II Example of Lack of Accountability: Prolonged Delay in Analysis of Single-Bore versus Twin-Bore The side-by-side analysis of two design options was not provided until more than 18 months after it was first requested.
At the Oversight Committee’s first meeting in November 2023, a member of the public requested that the committee order a cost and risk analysis of the single-bore versus twin-bore options, which remained controversial following the VTA Board’s selection of the single-bore option in 2018. In 2023, the Chair of the Oversight Committee responded that such an “apples-to-apples” (side-byside) analysis would be one of the committee’s first tasks. Here are some of the subsequent activities:
• At the committee’s meeting on January 19, 2023, two committee members formally requested the “apples-to-apples” analysis and placed it on the committee’s tracking list. (VTA, March 2025). At its meeting on June 13, 2024, the Project Manager reported that the scope of the twin-bore analysis would be worked on and reported to the Board “over the course of the summer.”
• At its meeting on August 8, 2024, a member of the public asked about the status of the “apples-to-apples” analysis.
• At the September 12, 2024, Oversight Committee, the auditor general announced that VTA staff had asked engineering design contractor Mott Macdonald to conduct the “apples-toapples” review. • The March 2025 tracking report included a comment regarding the “apples-to-apples” comparison: “These items are being evaluated as part of cost savings task force efforts with participation from GZ” (VTA, April 2024).
• One year later, on September 11, 2025, Mott Macdonald presented its analysis of the twinbore versus single-bore options – nearly 22 months after the request was first discussed at an Oversight Committee meeting – concluding that the single-bore option was preferred (VTA, September 11, 2025).
Example of Lack of Accountability: An Alternative Strategy Some Call “Plan B” Despite multiple requests for an alternative strategy to address risks associated with the federal funding decision, VTA staff advised the Oversight Committee that it would wait until after the federal decision.
Since the Oversight Committee meeting on October 9, 2025, committee members have stressed the need for an alternative strategy in the event the federal government delays or denies the FFGA
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II for the promised $5.1 billion. Some committee members asked whether a “Plan B” might include reducing the number of planned stations or revising the funding strategy. VTA staff reported to the Civil Grand Jury that there was reluctance to discuss a “Plan B” out of concern that the discussion itself might jeopardize the FFGA. At public meetings, VTA staff dismissed requests for an alternative funding strategy, instead reporting that an alternative plan should not be prepared until the FTA made its decision in 2027. This is an example of the VTA staff’s dismissal of the Oversight Committee direction.
Expediency of Decisions versus Rigorous Analysis
The Civil Grand Jury identified tension between VTA Board members’ competing goals: avoiding delays in decision-making and requiring rigorous, independent analysis of costs, risks, and schedule. In public meetings, the Project Manager has often stated that each month of delay adds $20 to $30 million to the overall project cost (Dorsey, 2025).
There is a strong financial incentive to keep the project moving by advancing decisions incrementally—approving one component at a time to show visible progress—without fully evaluating how each step alters the project’s overall cost, scope, and risk. For a project of this size, complexity, and cost, this piecemeal approach masks cumulative effects, increasing the likelihood of cost escalation and delays. These should be identified and addressed through rigorous, frontend analysis.
With two-year terms and constituencies limited to portions of the County, Board members may understandably focus on immediate actions rather than the long-term, systemwide implications that demand a coherent strategic plan.
The Role Assigned to the Auditor General
The Oversight Committee benefits from periodic risk assessments and audits performed by the VTA auditor general on the BSVII project. However, by assigning the auditor general the responsibility to also provide staff support to the Oversight Committee, VTA has created a situation in which the auditor general is asked to provide an independent audit of prior decisions while also assisting the committee in evaluating future policy and management decisions.
At the June 2025 public Board meeting, the auditor general stated that he sometimes feels like a referee among the analyses provided by VTA staff, the SME, the public, and the PMOC. However, the VTA Board is the final arbiter, not the auditor general.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II The Board is best served when it hears all relevant views on an upcoming decision and is presented with options and a recommendation. The auditor general’s participation and input are critical, but he should not be placed in the position of having to synthesize all the competing views, including his own.
The auditor general is better placed to assist the Oversight Committee in its role of “oversight” and less so in commenting on the Oversight Committee's “guidance” functions. Accordingly, the Oversight Committee and the VTA Board would be better served if a VTA staff person were assigned responsibility for staffing the committee. This person could be part of the General Manager’s Office and should not report to the Project Manager. The position would be like that of the chief of staff, which was recently assigned to support the chair of the Board.
Coordination with BART
Because the County of Santa Clara is not part of the BART District, the extension of rail service to San José required a contract that established both VTA’s and BART’s commitment to cooperate.
Under the 2001 Cooperative Agreement, VTA is financially responsible for paying for the design, construction, and operation of the segment in Santa Clara County (BART and VTA, Comprehensive Agreement, 2001). BART retained approval authority over design elements that affect operations, maintenance, and safety. To date, this has been accomplished through the joint preparation of a Design Criteria Manual.
As recently as December 2025, BART’s Independent Office of the Inspector General (OIG) issued a report titled: “Transparency & Communication Gaps in the BSVII Project.” The report summarizes years of controversy over the single-bore versus twin-bore approach but acknowledges that BART eventually agreed to the single-bore concept evaluated in the final environmental impact statement. However, the BART OIG remained critical of the extent of cooperation between the two agencies:
We also determined that the length of time since the project began, extensive media coverage of the project, conflicting subject-matter opinions, and some public displeasure with the single-bore design have created uncertainty about the project’s direction. We concluded that gaps in transparency and communication, including limited public discussions in recent years, have resulted in mixed messaging on a project that has evolved over multiple decades (BART Independent Office of the Inspector General, 2025).
In August 2025, the lack of communication and cooperation was publicly exposed when a BART official wrote a letter to VTA (Appendix A) specifically objecting to the consideration of reducing
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II the size of the Newhall Yard and Maintenance Facility as a capital cost-saving measure. The VTA Project Manager publicly acknowledged a failure to keep BART informed of design issues that might impact BART’s operational efficiency and pledged to develop recommendations to the administrative heads of both agencies on a more formal process to identify and resolve those issues (VTA Oversight Committee, 2025).
Board Experience and Continuity
Since 2019, five audits and reports have critiqued VTA’s governance structure and recommended a series of revisions to improve VTA’s capability to provide Board direction and oversight of the BART extension. Those audits have included the 2018-19 Santa Clara County Civil Grand Jury in 2019; the Auditor of the State of California, in 2024; the BART Independent Office of the Inspector General in 2025; RSM US LLC, a VTA subcontractor, in 2019; and the VTA Auditor General in 2024. VTA has accepted and acted on most of the recommendations for governance reform, except those relating to the terms and required experience level of Board members.
During the investigation of the BSVII project, sources repeatedly raised concerns about the level of knowledge and decision-making ability of the full VTA Board, which is responsible for the project’s success. Decisions made today will have a direct impact on its ultimate success. Diligent oversight of its schedule, cost, progress, and scope is required.
According to the California Public Utilities Code, which established the VTA Board, “to the extent possible, the appointing powers shall appoint individuals who have expertise, experience, or knowledge relative to transportation issues” (Pub. Util. Code 10000 et seq).
VTA Board members are appointed to two-year terms by appointing agencies, organized into six groups as detailed in Table 3. Appointing agency groups are established and defined by VTA Administrative Code, which states “Appointing Authorities are strongly encouraged, where possible, to: (1) appoint individuals with appropriate experience and qualifications in transportation; (2) ensure that there is sufficient remaining time in the elected official’s term of office to allow full completion of their term as a Director; and (3) reappoint representatives to consecutive terms” (VTA Administrative Code § 2-13).
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II Table 3: Appointing Authorities Composition of the VTA Board Appointing
Agency
Group
Jurisdiction Represented Number of
Board Members
Method of
Appointment
Group 1 San José 5 members
1 alternate
Appointed by city
council from city
council members/mayor
Group 2 Los Altos, Los Altos Hills,
Mountain View, Palo Alto
1 member
1 alternate
Determined by
Group 2 members
Group 3
Campbell, Cupertino,
Los Gatos, Monte Sereno,
Saratoga
1 member
1 alternate
Determined by
Group 3 members
Group 4 Gilroy, Morgan Hill 1 member
1 alternate
Determined by
Group 4 members
Group 5 Milpitas, Santa Clara,
Sunnyvale
2 members
1 alternate
Determined by
Group 5 members
Group 6 County of Santa Clara 2 members
1 alternate
Appointed by County
Board of Supervisors
Source: California Pub. Util. Code section 100060.
While VTA continues to insist that two-year terms are suitable for its governance (as specified in PUC § 100060.2), peer agencies in the state appoint their Board members to four-year terms, leading to much longer average lengths of service and potentially greater experience and transportation-related knowledge (see Figure 2).
Multiple reports and audits have suggested weaknesses introduced by VTA’s approach to the appointment of Board members. For example, the 2019 Board Governance Assessment concluded, in part, that some processes and policies (e.g., committee structure, term limits, and Board member selection guidelines) might not reflect best practices or support long-term Board stability (VTA, 2019). Additionally, a report by the 2018-19 Santa Clara County Civil Grand Jury found that the VTA Board suffers from:
• A lack of experience and limited continuity by many Board members; • Inadequate time for the directors to devote to the Board’s oversight and policy-making functions;
• A lack of engagement by some of the directors, fostered in part by the committee system, resulted in VTA functioning largely as a staff-driven organization.
More recently, a critical 2024 report from the State Auditor regarding VTA’s project management and financial oversight noted the following weaknesses:
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II • The process for selecting directors for the Board is not always transparent enough to ensure the appointment of directors experienced in transportation issues. • Some groups of cities appoint VTA directors without public deliberation, limiting transparency and sometimes bypassing the statutory recommendation for transportation expertise.
• VTA directors have shorter tenures, on average, than their peers, meaning that VTA’s Board has less experience overseeing the agency’s operations than the Boards of peer agencies.
Figure 2: Average Directors’ Tenure among VTA and Peer Agencies Source: Auditor of the State of California, “Santa Clara Valley Transportation Authority, Improvements Are Necessary to Strengthen Its Project Management and Financial Oversight,” June 2024.
Note: LA Metro stands for Los Angeles County Metropolitan Transportation Authority; OCTA stands for Orange County Transportation Authority; SacRT stands for Sacramento Regional Transit District.
During interviews and in reviewing existing reports and audits about VTA, the Civil Grand Jury learned that Board members and elected officials broadly support a four-year term for directors.
Lengthening terms would require a change to VTA’s enabling legislation. The findings of the State and VTA’s own auditors’ governance reform recommendations remain unchanged.
VTA Directors1 Average Tenure Is Shorter Than Average Tenures of Directors at P,eer Agencies VTA 3.lyears
LA Metro 9.3 years
OCTA
SacRT 8.3 years
0 2 3 4 5 6 7 8 9 10
Average Years of Service
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II Public Communication
Following the VTA auditor general’s report in January 2024, public communication and community outreach regarding the BSVII project have improved. The Civil Grand Jury noted improvements to the VTA BSVII project website, including efforts to deliver timely updates to residents about the impact of construction activities, and a section for frequently asked questions (FAQ) (VTA, BART Silicon Valley Phase II Project, n.d.). In addition, many interviewees told the Civil Grand Jury that VTA has made efforts to better inform the public and officials since the auditor general's report highlighted communication breakdowns in 2023.
However, there are areas where the public would benefit from VTA focusing more on improving communication.
The VTA’s BSVII project website does not offer a simple, clear dashboard outlining the costs, timeline, and progress of the BSVII project. Although it includes technical reports from the federally sponsored PMOC, it does not include the independent analyses by the SME or the VTA auditor general.
A high-level dashboard would consolidate information from multiple sources, present project metrics to the public, and provide access to source materials. Today, information on funding, expenditures, and schedule status is available on the website, but is buried in layers of reports that are nonintuitive to find or navigate.
In addition, the Civil Grand Jury found the site’s search function inadequate for locating specific details or addressing questions not covered in the FAQ, and it often returned results for irrelevant materials. The website would be more user-friendly if VTA incorporated a more robust search engine.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II
CONCLUSION
The VTA Board has failed in its responsibility to provide effective management, oversight, and financial control of the BSVII Project.
Based on its investigation, the Civil Grand Jury concludes:
• There is no realistic plan to deal with foreseeable financial risks, including significant uncertainty about BSVII’s construction and operating costs, reliance on expiring voterapproved sales tax measures, uncertain federal government support, cash flow, and declining ridership.
• When considering major scope and design decisions, the Oversight Committee and the VTA Board do not take into account the ongoing operations and maintenance costs that will be borne by VTA and will require voter approval of subsequent sales tax measures. • The Oversight Committee exercises its oversight responsibility by requiring monthly progress reports and by questioning VTA project staff, but when it declines to make recommendations to the VTA Board, it fails in its responsibility to provide guidance on critical policy issues.
• The Oversight Committee receives valuable input from multiple sources but does not share this information with the VTA Board in the form of helpful reports that synthesize the different perspectives of VTA staff, the Subject Matter Expert, the auditor general, the Project Management Oversight Consultant, and the public. • The VTA Board and the Oversight Committee have failed to hold VTA staff accountable for missing deadlines to provide analysis and information requested by members of the Oversight Committee.
• There is a lack of meaningful communication and cooperation between BART and VTA officials, which undermines public confidence.
• VTA’s failure to adopt governance reform recommendations from prior Civil Grand Jury reports and independent audits has led to a lack of Board member continuity and expertise, weakening the Board’s ability to successfully oversee the BSVII project.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II
FINDINGS AND RECOMMENDATIONS
Finding 1
The BSVII project currently requires voter approval of additional sales tax measures to address gaps in construction and operations funding.
Recommendation 1
VTA should adopt and publish a strategy for the completion and operation of the project that reduces dependency on new sales tax measures.
This should be implemented by December 31, 2026.
Finding 2
VTA does not maintain a cash-flow model for the BSVII project.
Recommendation 2
The VTA Board should direct the General Manager to prepare a cash-flow model for the BSVII project and present it quarterly to the Oversight Committee and the Board.
This should be implemented by December 31, 2026.
Finding 3
VTA has not developed an alternative funding strategy for the project in the event that planned funding sources are unavailable or insufficient.
Recommendation 3
The VTA Board should direct the General Manager to prepare an alternative funding strategy to meet the project’s estimated total capital costs and VTA’s responsibility for operating and maintenance costs and present it to the Oversight Committee and Board for approval.
This should be implemented by December 31, 2026.
Finding 4
Project management does not consistently report the operating and maintenance cost implications of design and construction decisions to the Oversight Committee or the Board.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II Recommendation 4
VTA should adopt a policy requiring staff to present an analysis of operating and maintenance costs when considering design and construction alternatives for BSVII.
This should be implemented by December 31, 2026.
Finding 5
The VTA Board would benefit from longer terms of office to improve continuity and institutional knowledge.
Recommendation 5
VTA should reconsider its prior rejections of audit recommendations calling for the establishment of four-year terms and direct its legislative advocates to seek a legislative author to amend VTA’s enabling statute to require four-year terms.
This should be implemented by December 31, 2026
Finding 6
VTA Board Appointing Authority Groups 2 through 5 often do not follow VTA Administrative Code (Section 2-14) admonitions to “appoint individuals with appropriate experience and qualifications in transportation” and to “reappoint representatives to consecutive terms.” Recommendation 6
VTA Board Appointing Authority Groups 2 through 5 should certify to the VTA Board that they will adhere to VTA Administrative Code (Section 2-14) admonitions, regarding Board member expertise and appointment to consecutive terms.
This should be implemented by December 31, 2026.
Finding 7
VTA Board Appointing Authority Groups 2 through 5 have different processes for making Board appointments.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II Recommendation 7
The cities represented in Appointing Authority Groups 2 through 5 should agree on a uniform process for making Board appointments.
This should be implemented by December 31, 2026.
Finding 8
The role assigned to the auditor general is outside the traditional scope of an auditor’s responsibilities and has introduced conflict and uncertainty among VTA staff and the Oversight Committee. Being involved in the management and policy-making process threatens the auditor general’s independence.
Recommendation 8
The Board should implement an alternative model for supporting the Oversight Committee that does not rely on the auditor general to provide services such as agenda preparation, monitoring of VTA staff assignments, or preparation of a synthesis of multiple independent inputs to the Committee’s deliberations.
This should be implemented by December 31, 2026
Finding 9
The Board of Directors has not approved the bylaws, nor the charter of the Oversight Committee.
Recommendation 9
VTA should formally adopt a revised Charter for the Oversight Committee, setting the Board’s expectations on the following issues:
• Defining the role of the auditor general to no longer require him to supervise the presentations by VTA staff to the Oversight Committee;
• The responsibility of the Oversight Committee to report regularly to the Board on the independent analyses of costs, risks, and schedule by the PMOC and any SMEs; and to provide the Oversight Committee’s synthesis of those analyses with recommendations to resolve conflicts when necessary;
• The responsibility of the Oversight Committee to consider and present its recommendations before the Board considers major decisions such as scope of the project, contracting, risk management, budgeting, and funding strategy;
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II • The responsibility of the Oversight Committee to hold subject matter experts accountable for timely analysis of costs, risk, and schedule;
• The responsibility of the Oversight Committee to report to the Board on the implications of design and construction issues that impact future ongoing operations and maintenance costs to be borne by VTA.
This should be implemented by December 31, 2026.
Finding 10
VTA’s vtabart.org website is poorly organized and not always intuitive to navigate, making it hard to find information about the status, cost, and schedule of the BSVII project.
Recommendation 10
The VTA Board should direct the General Manager to implement and maintain a project dashboard on its vtabart.org website that includes status, cost, and schedule information.
This should be implemented by October 31, 2026.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II
REQUIRED RESPONSES
Pursuant to California Penal Code section 933(a) et seq. and California Penal Code section 933.05, the 2025-26 Santa Clara County Civil Grand Jury requests responses from the following governing bodies:
Responding Agency Findings Recommendations
VTA Board of Directors 1, 2, 3, 4, 5, 8, 9, 10 1, 2, 3, 4, 5, 8, 9, 10 County of Santa Clara, Board of Supervisors 6 6
The City of Campbell, City Council 6, 7 6, 7
The City of Cupertino, City Council 6, 7 6, 7
The City of Gilroy, City Council 6, 7 6, 7
The City of Los Altos, City Council 6, 7 6, 7
The Town of Los Altos Hills, Town Council 6, 7 6, 7
The Town of Los Gatos, Town Council 6, 7 6, 7
The City of Milpitas, City Council 6, 7 6, 7
The City of Monte Sereno, City Council 6, 7 6, 7
The City of Morgan Hill, City Council 6, 7 6, 7
The City of Mountain View, City Council 6, 7 6, 7
The City of Palo Alto, City Council 6, 7 6, 7
The City of San José, City Council 6, 7 6, 7
The City of Santa Clara, City Council 6, 7 6, 7
The City of Saratoga, City Council 6, 7 6, 7
The City of Sunnyvale, City Council 6, 7 6, 7
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II APPENDIX A: BART Management Letter
BART SILI CON VALLEY
P ASE (BSV 1)
M RA
TO: 'A naral an g .r
DATE: Augu;.1 IS, _025
FR M: n1 eneral l na er. pe ti n
BJE T: oncem Regarding La k oflnf◄ rotation haring and 01ificaciori on e Pro'e l han
Dear eneral an ger onot:
The Ba Are ' T it ismct (B
prior notice ug 11 pre rel
' gra ely c n emed with VT ' failure top
n th twin re "t rep n u date and the I
odvnn~ di, t ignifi ant.ly s wn \'ersion ofLhe ord p d al 1h O\' igh1 Commiuee Meeting on glht 14 2025. Both actions iola1e es1ablished prut l:s m1dem1i.ne the • ati th t have guided • oership, and represent erions brea.cbes of p B ill under the clear impre after m nth of partnership, and oollaborati n. th a • ard with n J f rd de ign.
In 201 , B RT and VTA re confi
m rk~ng the ulminatian of yea~ ofcooroin loo cffart,joinl od oc.a.c , (Ind mutlllll lian . Since lh :!oigning of the Compn:hcn,i Agreement 1be n:quin:1n 111 ho;. been 1D1equivoc-al: any ignifi ant proj I hange part:i ular!l th affi ting peracion f. , or long-ccrm s st m perfonnan , m t be di l ed to BAR in advamce of any publi release.
The deci ion 10 withhold advance notification ofllhe t 11 release, coupled i1h die ence fmeaningful prior discu ion w ncepts of yard rede i n fi re presentin in the fon11n f publi 01n111it1 . , llrTie, dire t and !as.ling op ration l ons uen es for B RT's abiliry to 511fcl and cffi ic:mtly operate th.c -expanded s~tem. These lap!>e;. are iocomp:uib!c \ ·ith the lc,,cl of transparen and peration -c_ pe I d be[\,\ CCII prims proj t partners.. 11: h omi ion hinder BAR 's abiti lo fuHiLI il:S responsibilities lo the publi dam ge takeholder confidence, and rai fundamental ncer about A' adherence to it c mmitment . the ale, c ity f thi p . ~eel, th e fi ilures re not are una c bre
I om formally nolifying , and th Phase [I Proj t tlml th rd on ept pre nted t the VTA Audit • ommilt.:.: on ugu;,t 14 2025 i, rej ted. The L'.bl c:rsion of yafd dc:,,,igii tha1 BART re ·iewed as re i ion J.
BSV I I: Co laboratIon, I nnovation, Sae y, Rel1ab1lI y 1
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II IBART SILICOlil VALLEY
P ASE I (BSV )
B RT remain fully c mmined t the . fill delivery f dl. crifca1 rcgi n I inve.1ment.
How vc , dlas ornmitm nl d
and 11. :,ountabi.lity.
onVTK imme-di le •-
incerely.,
l G ntt[II Man ger Op rnrions
ircclor
I m1ger
I
Bo ram Director
mmitte Memb
To (lgu· _ ·cfDelivery ,ffi erofMeg.i Proj ts
BSV I I: Co l ebora ion, Innova t ion, Sa t y, R l1abd1 y 2
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II
CONFLICTS
Members of the Civil Grand Jury are conflicted from a Civil Grand Jury investigation if, as a result of prior or current employment or associations, investment in public or private enterprise, financial interest, bias, or personal relationship, they are subject to recusal from participating in a matter before the Civil Grand Jury. One juror was recused from this matter.
REFERENCES
Bibliography
2018-19 Santa Clara County Civil Grand Jury. “Inquiry Into Governance of the Valley Transportation Authority.” June 18, 2019.
(https://santaclara.courts.ca.gov/system/files/cgj-vta-final-report-061819_0.pdf).
Accessed April 5, 2026.
Aragon, Greg, “Single-Bore Tunnel Method Chosen for BART Silicon Valley Phase II.” ENRWest. November 4, 2025. (https://www.enr.com/articles/61798-single-bore-tunnelmethod-chosen-for-bart-silicon-valley-phase-ii). Accessed April 29, 2026.
AtkinsRéalis USA Holdings LLC. “Project Monitoring Report.” March 9, 2026. (https://vtabart.org/transparency-commitment/#docaccess8dd20a14312d4f35dd29658c7e4d5f55). Accessed May 1, 2026.
Auditor General, Santa Clara Valley Transportation Authority. “Auditor General’s Risk Assessment Report on VTA’s BSVII Finance Risks.” May 1, 2025. (https://santaclaravta.iqm2.com/Citizens/Detail_LegiFile.aspx?MeetingID=4412&ID= 9358). Accessed April 5, 2026.
Auditor of the State of California. “Santa Clara Valley Transportation Authority, Improvements Are Necessary to Strengthen Its Project Management and Financial Oversight.” June 2024. (https://www.auditor.ca.gov/wp-content/uploads/2024/06/2023-101-Report.pdf).
Accessed April 5, 2026.
California State Transportation Agency. “Transit and Intercity Rail Capital Program.” n.d. (https://calsta.ca.gov/subject-areas/transit-intercity-rail-capital-prog). Accessed May 12, 2026.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II Cal. Pub. Util. Code section 10000 et seq.
Cal. Pub. Util. Code section 100060 et seq.
Dorsey, Dustin. “Silicon Valley BART Extension construction remains on time, budget.” ABC Eyewitness News. December 8, 2025. (https://abc7news.com/post/silicon-valley-bartextension-construction-remains-time-budget-west-portal-site/18265543/). Accessed April 29, 2026.
Federal Transit Administration. “FY 2025 New Starts Financial Assessment.” June 2024. (https://www.transit.dot.gov/funding/grants/grant-programs/capital-investments/bartsilicon-valley-phase-ii-project-profile-fy-0).
Federal Transit Administration. “BART Silicon Valley Phase II Extension Project San Jose, California. June 2024. (https://www.transit.dot.gov/sites/fta.dot.gov/files/2024-08/CABART-Silicon-Valley-Phase-II-Eng-Profile-20240705.pdf). Accessed March 30, 2026.
Geha, Joseph. “Feds Commit $5.1 Billion to South Bay BART Extension.” KQED.org. August 2, 2024. (https://www.kqed.org/news/11998646/feds-commit-5-1-billion-to-south-baybart-extension#:~:text=Joseph%20Geha,increases%20to%20the%20current%20figure).
Accessed April 22, 2026.
Hicks, Tony. “VTA Board approves purchase of machine to bore BART line.” Mountain View Voice. November 7, 2023. (https://www.mv-voice.com/news/2023/11/07/vta-boardapproves-purchase-of-machine-to-bore-bart-line/). Accessed April 5, 2026.
Metropolitan Transportation Commission. “Agreement Reached on Loan for Bay Area Transit Agencies.” January 30, 2026. (https://mtc.ca.gov/news/agreement-reached-loan-bay-areatransitagencies#:~:text=Because%20many%20transit%20capital%20projects,funds%20remaine d%20in%20state%20accounts.). Accessed April 28, 2026
Office of the County Counsel, County of Santa Clara. “County Counsel’s Impartial Analysis of Measure B.” 2016. (https://www.vta.org/sites/default/files/2025- 08/2016%20Measure%20B%20Ballot.pdf). Accessed April 29, 2026.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II San Francisco Bay Area Rapid Transit District Independent Office of the Inspector General. “Transparency & Communication Gaps in BSVII Project.” December 19, 2025. (https://www.bartoig.org/investigation-reports-2025#docaccess-98152ed2acf38 cd4da53e1efbb737c86cc96ef6c2e1f439edf6ec6f51905271f). Accessed April 5, 2026.
San Francisco Bay Area Rapid Transit District and Santa Clara Valley Transportation Authority, Comprehensive Agreement, November 22, 2001.
(www.bart.gov/sites/default/files/docs/O%26M%20Agreement_Silicon%20Valley%20B ART%20Extn.pdf). Accessed May 12, 2026.
San Francisco Bay Area Rapid Transit District. “BART Board initially approves Alternative Service Plan outlining budget balancing details.” February 26, 2026. (https://www.bart.gov/news/articles/2026/news20260226-0). Accessed April 29, 2026.
San Francisco Bay Area Rapid Transit District. "January 2026 Monthly Ridership Snapshot." February 2026. (https://www.bart.gov/sites/default/files/2026- 02/202601%20Monthly%20Ridership%20Snapshot.pdf). Accessed April 29, 2026.
San Francisco Bay Area Rapid Transit District. " 2019 Monthly Ridership Reports." 2019. (https://www.bart.gov/sites/default/files/docs/ridership_2019.zip). Accessed April 29, 2026.
Santa Clara Valley Transportation Authority, BART Silicon Valley Phase II Project. n.d. (https://www.vtabart.org). Accessed May 12, 2026.
Santa Clara Valley Transportation Authority, “VTA Board of Directors Workshop Reviews BART Phase II Timeline, Costs, And Next Steps.” October 23, 2023. (https://www.vta.org/blog/vta-board-directors-workshop-reviews-bart-phase-ii-timelinecosts-and-next-steps). Accessed April 29, 2026.
Santa Clara Valley Transportation Authority Auditor General. “Auditor General’s Initial Monitoring Report on VTA’s BART Silicon Valley Phase II Extension Project.” VTA’s BART Silicon Valley Phase II Extension Oversight Committee Agenda. Item 8a. January 19, 2024. (https://santaclaravta.iqm2.com/Citizens/Detail_Meeting.aspx?ID=4233).
Accessed April 5, 2026.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II Santa Clara Valley Transportation Authority/RSM US LLC. “Board Governance Assessment – Santa Clara Valley Transportation Authority.” December 20, 2019. (https://www.vta.gov/ sites/default/files/2020-01/VTA%20Board%20Governance%20Assessment%20 %281%29.pdf). Accessed April 5, 2026.
Santa Clara Valley Transportation Agency. “BART Silicon Valley Extension Project Implements Major Cost Reductions.” November 13, 2024. (https://www.vta.org/blog/bart-siliconvalley-extension-project-implements-major-cost-reductions). Accessed April 23, 2026.
Santa Clara Valley Transportation Authority/HayGroup. “Santa Clara Valley Transportation Authority Organizational and Financial Assessment Executive Report.” March 2007. (https://ti.org/pdfs/HayGrouponVTA.pdf). Accessed April 5, 2026.
Santa Clara Valley Transportation Authority. “Operations and Maintenance Agreement By and Between the Santa Clara Valley Transportation Authority and The San Francisco Bay Area Rapid Transit District.” May 22, 2020. (https://www.vta.org/sites/default/files/2020- 12/VTA%20BART%20Operations%20and%20Maintenance%20Agreement_0.pdf).
Accessed April 23, 2026.
Santa Clara Valley Transportation Authority. “Santa Clara Valley Transit Authority Administrative Code (With Amendments through March 6, 2025).” March 2025. (https://www.vta.org/sites/default/files/2025-04/VTA_Administrative_Code_2025-3-
6.pdf). Accessed April 5, 2026.
Santa Clara Valley Transportation Authority. “Bylaws for VTA’s BART Silicon Valley Phase II Oversight Committee.” April 4, 2024. (https://www.vta.gov/sites/default/files/2024-04/ vta-bsv-oversight-committee-bylaws_0.pdf). Accessed April 8, 2026.
Santa Clara Valley Transportation Authority. Special Board Meeting. October 17, 2025. (https:// santaclaravta.iqm2.com/Citizens/FileOpen.aspx?Type=14&ID=4297&Inline=True) Accessed April 9, 2026.
Santa Clara Valley Transportation Authority. “VTA's BART Silicon Valley Phase II Oversight Committee Regular Meeting”, Agenda Item 9.a, Item #25. April 17, 2024. (https://santaclaravta.iqm2.com/Citizens/FileOpen.aspx?Type=1&ID=3940&Inline=True ). Accessed May 1, 2026.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II Santa Clara Valley Transportation Authority. “VTA's BART Silicon Valley Phase II Oversight Committee Regular Meeting.” Agenda Item 4, Item #4. March 13, 2025. (https://santaclaravta.iqm2.com/Citizens/FileOpen.aspx?Type=1&ID=4138&Inline=True ). Accessed May 1, 2026.
Santa Clara Valley Transportation Authority. “VTA's BART Silicon Valley Phase II Oversight Committee Regular Meeting.” Item 11a. June 12, 2025.
(https://santaclaravta.iqm2.com/Citizens/Detail_Meeting.aspx?ID=4430). Accessed April 29, 2026.
Santa Clara Valley Transportation Authority. “BSVII Project Update.” Summer, 2025. (https://vtabart.org/vtas-bart-silicon-valley-phase-ii-extension-project-summer-2025/).
Accessed May 13, 2026.
Santa Clara Valley Transportation Authority. “VTA's BART Silicon Valley Phase II Oversight Committee Regular Meeting.” Item 8. January 15, 2026.
(https://santaclaravta.iqm2.com/Citizens/FileOpen.aspx?Type=1&ID=4354&Inline=True ). Accessed April 22, 2026.
Santa Clara Valley Transportation Authority. “2000 Measure A.” n.d. (https://www.vta.org/projects/funding/2000-measure-a). Accessed April 29, 2026.
Santa Clara Valley Transportation Authority. “About 2016 Measure B.” n.d. (https://2016measureb.vta.org/about). Accessed April 29, 2026.
Santa Clara Valley Transportation Authority. “VTA's BART Silicon Valley Phase II Oversight Committee Regular Meeting.” Item 10b. Slide 21. September 11, 2025. (https://santaclaravta.iqm2.com/Citizens/FileOpen.aspx?Type=1&ID=4273&Inline=True ). Accessed April 13, 2026.
Santa Clara Valley Transportation Authority. “Fact Sheet: VTA's Bart Silicon Valley Phase 2 Extension Project.” March 2024. (https://www.vta.org/sites/default/files/2024- 07/VTABSV_FactSheet_2024_OverviewBenefits%201.pdf). Accessed April 13, 2026.
Shalby, Colleen. “Trump administration pulls billions in funding for high-speed rail project; state leaders call decision ‘illegal.’” Los Angeles Times. July 16, 2025. (https://www.latimes.com/california/story/2025-07-16/trump-administration-cancelsfunding-for-high-speed-rail-project). Accessed April 29, 2026.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II Shalby, Colleen. “Multibillion-dollar transit project to tunnel through the Santa Monica Mountains is approved by L.A. Metro.” LA Times. January 22, 2026. (https://www.latimes.com/california/story/2026-01-22/this-multibillion-dollar-transitproject-could-improve-traffic-across-la-it-goes-to-vote-today - :~:text=This is read by an,transit projects in the country). Accessed April 13, 2026.
VTA’S MANAGEMENT AND OVERSIGHT OF BART SILICON VALLEY PHASE II This report was ADOPTED by the 2025-2026 Santa Clara County Civil Grand Jury on this 17th day of June, 2026.
______________________________
Dinesh Ramde
Foreperson
City of Santa Clara
Agenda Report
1500 Warburton Avenue
Santa Clara, CA 95050
santaclaraca.gov
@SantaClaraCity
26-920 Agenda Date: 8/25/2026
REPORT TO COUNCIL
SUBJECT
Action to Designate a Voting Delegate and Alternate Delegates for the 2026 League of California Cities Annual Conference and Expo on September 23-25, 2026
BACKGROUND
The 2026 League of California Cities Annual Conference and Expo will be held in Anaheim, California from September 23 through September 25, 2026. During the Annual Conference, the League of California Cities will convene a member-driven General Assembly at the Cal Cities Annual Conference and Expo on Friday, September 25, 2026.
The League of California Cities issued an informational packet (Attachment 1) advising City Council action by September 1, 2026, as the final date to designate a voting delegate and alternate delegates.
The City of Santa Clara is a full-voting member of the League of California Cities. Each member city has a right to cast one vote on matters pertaining to League of California Cities policy. Per the League of California Cities bylaws, to vote at the General Assembly, the City Council must designate a voting delegate and up to two alternate voting delegates, one of whom may vote if the designated voting delegate is unable to serve. The voting delegate and alternates must be approved by City Council action and cannot be accomplished by individual action or by the Mayor or City Manager alone. Voting delegates will consider and vote on resolutions during the General Assembly. Potential League of California Cities bylaws amendments are also considered at this meeting. Resolutions approved during the General Assembly become League of California Cities policy.
The League of California Cities has received one resolution to be considered (Attachment 2). The General Assembly will convene on Friday, September 25, 2026 to consider any resolutions the Resolutions Committee has forwarded. However, there may be petitioned resolutions introduced and qualified during the annual conference which will convene the General Assembly, requiring the City’s voting delegate to vote on behalf of the City. Such vote(s) should align with the City’s Legislative Advocacy Position (LAP) Policy (Attachment 3) and 2026 LAPs and City staff will provide support as needed with reviewing any petitioned resolutions.
DISCUSSION
The League of California Cities requests that the City of Santa Clara designate a voting delegate and up to two alternates who will be present at the General Assembly on September 25, 2026 during the conference.
City Councilmember Kevin Park is currently registered to attend the 2026 League of California Cities Annual Conference and Expo and is the only member of City Council attending at the date of this City of Santa Clara Page 1 of 2 Printed on 8/21/2026
powered by Legistar™
City of Santa Clara
Agenda Report
1500 Warburton Avenue
Santa Clara, CA 95050
santaclaraca.gov
@SantaClaraCity
26-776 Agenda Date: 8/25/2026
REPORT TO COUNCIL
SUBJECT
Action on a Council Written Request (Council Policy 030) Submitted by Councilmember Jain to Place an Item on a Future Agenda Regarding a Dedicated Manager Responsible for Sustainability Activities such as Increasing Recycling, Reducing Water Usage, Increasing Composting, and Reducing Carbon Emissions, and Tracking Related Metrics
BACKGROUND
Council Policy 030 (Adding an Item on the Agenda) sets forth the procedure for written petitions. A member of the Council may submit a written request for inclusion of an item on a future City Council agenda. Prior to submitting a Council Item Request form, the Member shall discuss the proposed request with the City Manager (and/or the City Attorney, as appropriate),If City staff’s response does not satisfy the Member’s request, the Member may submit the Council Item Request form for placement on a future City Council agenda. Once the City Clerk’s Office receives the Council Item Request form, it should immediately be forwarded to the City Manager for placement on an agenda, if possible, within two (2) Council meetings after original receipt of the original request by the City Clerk’s Office.
DISCUSSION
The City Clerk’s Office received a Council Written Request on June 30, 2026, submitted by Councilmember Jain, requesting that an item be placed on a future meeting agenda to discuss a dedicated manager responsible for coordinating sustainability activities such as increasing recycling, reducing water usage, increasing composting, and reducing carbon emissions, and tracking related metrics. Individually many departments carry out sustainability activities, however, no single position currently coordinates those efforts or aggregates their collective impact. There is also a need to update the City’s Climate Action Plan, which was last updated in 2022.
As a reminder, this item is for purposes of discussing whether the Council wishes to agendize this matter on a future Council agenda for a report or action. It is not for the purpose of discussing the substance of the item itself. Specifically, the policy provides as follows:
1. At the meeting where the request to add an item to a future agenda is heard, Council discussion is limited to whether the item should be added to an agenda and a date, not the merit of the item. Valid considerations that can be discussed include whether the matter is within the City’s jurisdiction, being addressed in some other way, City resource requirements, legality, timing, and prioritization.
2. Council may take the following actions when a request is made:
a. No Action
b. Refer the request to City staff for further study and a timely report back to Council c. Refer the item to a future annual Council Priority Setting session meeting City of Santa Clara Page 1 of 2 Printed on 8/21/2026
powered by Legistar™
26-776 Agenda Date: 8/25/2026
d. Placement on a future Council meeting agenda for further consideration or action
3. At the meeting where the item is first considered, if a majority of the City Council supports further study of the item, then a full staff analysis shall be prepared within thirty (30) days, unless otherwise directed by the City Council. If the request requires more than thirty (30) calendar days to prepare, status updates will be provided to the City Council every sixty (60) days as an informational memo.
ENVIRONMENTAL REVIEW
The action being considered does not constitute a “project” within the meaning of the California Environmental Quality Act (“CEQA”) pursuant to CEQA Guidelines section 15378(b)(5) in that it is a administrative activity that will not result in direct or indirect physical changes to the environment.
FISCAL IMPACT
There is no fiscal impact associated with considering the request to be placed on a future agenda except for staff time.
COORDINATION
This item was coordinated with the City Manager and the City Attorney.
PUBLIC CONTACT
Public contact was made by posting the Council agenda on the City’s official-notice bulletin board outside City Hall Council Chambers. A complete agenda packet is available on the City’s website and in the City Clerk’s Office at least 72 hours prior to a Regular Meeting and 24 hours prior to a Special Meeting. A hard copy of any agenda report may be requested by contacting the City Clerk’s Office at (408) 615-2220, email [email protected] or at the public information desk at any City of Santa Clara public library.
ALTERNATIVES
a. No Action
b. Refer the request to City staff for further study and a timely report back to Council c. Refer the item to a future annual Council Priority Setting session meeting d. Placement on a future Council meeting agenda for further consideration or action
RECOMMENDATION
Staff makes no recommendation.
Reviewed by: Nora Pimentel, Assistant City Clerk
Approved by: Jovan Grogan, City Manager
ATTACHMENTS
1. Policy Procedure 030 - Adding an Item on the Agenda
2. Written Petition dated April 14, 2026, Submitted by Councilmember Jain City of Santa Clara Page 2 of 2 Printed on 8/21/2026
powered by Legistar™
Revised 10/24/2023 CP 030
Resolution No. 23-9278
City of Santa Clara
Council Policy Manual
ADDING AN ITEM TO THE
AGENDA
PURPOSE The purpose of this Policy is to establish a clear, effective, and easily understood process for members of the City Council and the public to have items, within the jurisdiction of the City Council, placed on the City Council agenda for consideration.
POLICY/
PROCESS
FOR CITY
COUNCIL
MEMBERS
Referral from Members of the City Council in Advance of a Meeting:
After consultation with the City Manager (and/or City Attorney, as appropriate), the Mayor or any individual Councilmember may submit a written request by using the Council Item Request Form to the City Manager’s Office for inclusion of an item on a future City Council agenda. An item may be referred to the City Manager for inclusion on a City Council agenda during a Council meeting by City Council action.
The procedure for written request from the City Council shall be as follows:
1. Members of the City Council shall use the Council Item Request form to submit a written request for inclusion of an item on a future City Council agenda.
2. Prior to submitting a Council Item Request form, the Member shall discuss the proposed request with the City Manager (And/or City Attorney, as appropriate) to determine if City staff’s response does not satisfy the Member’s request, the Member shall submit the Council Item Request form for placement on a future City Council agenda.
3. Once the City Clerk’s Office receives the Council Item Request form, it should immediately be forwarded to the City Manager for placement on an agenda, if possible, within two (2) Council meetings after receipt of the original request by the City Clerk’s Office. All written material (Council Item Request Form and any support material) will be submitted on the agenda in the form substantially provided by the requestor without any staff analysis, including fiscal review, legal review and policy review, until the City Council has had the opportunity to provide the direction to the City Manager.
Referrals from Members of the Council at the Council Meeting If an issue arises during a Council meeting that may require future City Council action a City Council member may also request, through a referral, that such item be agendized for future Council consideration.
Such a request may be considered by the Council following the City of
Santa Clara
The Center of What's Possible
Revised 10/24/2023 CP 030
Resolution No. 23-9278
City of Santa Clara
Council Policy Manual
POLICY/
PROCESS
FOR
COUNCIL
COMMITTEES
POLICY/
PROCESS
FOR
MEMBERS
OF THE
PUBLIC
“Procedure for Handling Requests at the City Council Meeting” set forth below.
Referral from a Council Committee:
Council Committees may request that an item to be considered for inclusion on a future City Council agenda by formal committee action. Any such request shall be submitted to the City Manager in writing. Provided the request is received two (2) days prior to the public release of the City Council agenda packet the item shall be included for consideration at that City Council meeting in accordance with the “Procedure for Handling Requests at the City Council Meeting” set forth below. .
Requests from Members of the Public:
Members of the public may request that an item be added to a City Council Agenda in any of the following ways:
1. Public Presentations: Any member of the public may address the City Council under the “Public Presentations” section of the agenda to make a request of the City Council to add an item to a future meeting. If a member of the public wishes to provide a written petition of their request prior to their appearance at a Council Meeting they may be submitted as follows:
a. Email:
City Council: [email protected]
City Manager: [email protected]
b. MySantaClara App:
santaclaraca.gov/services/make-a-service-request
Note: Written Petitions will not be listed on the City Council agenda, and the member must be present at the meeting to present their request.
2. Individual City Councilmembers: Members of the public may directly petition individual City Councilmembers to request that an item be added to a future Council meeting. The Councilmember may then choose to submit the request through the Council referral process outlined in this Policy, above.
3. City Manager and City Departments: Members of the public may also petition the City Manager or City staff for specific action. The City Manager and/or staff may respond, as appropriate, directly to this request, or direct the member of the public to the other methods of petitioning the City outlined above.
City of
Santa Clara
The Center of What's Possible
Revised 10/24/2023 CP 030
Resolution No. 23-9278
City of Santa Clara
Council Policy Manual
PROCEDURE
FOR HANDLING
REQUESTS AT
THE CITY
COUNCIL
MEETING
1. At the meeting where the request to add an item to a future agenda is heard, Council discussion is limited to whether the item should be added to an agenda and a date, not the merit of the item. Valid considerations that can be discussed include whether the matter is within the City’s jurisdiction, being addressed in some other way, City resource requirements, legality, timing, and prioritization.
2. Council may take the following actions when a request is made:
a. No Action.
b. Refer the request to City staff for further study and a timely report back to Council.
c. Refer the item to a future annual Council Priority Setting session meeting.
d. Placement on a future Council meeting agenda for further consideration or action.
3. At the meeting where the item is first considered, if a majority of the City Council supports further study of the item, then a full staff analysis shall be prepared within thirty (30) days, unless otherwise directed by the City Council. If the request requires more than thirty (30) calendar days to prepare, status updates will be provided to the City Council every sixty (60) days as an informational memo.
References
10/24/2023 Revised, Resolution No. 23-9278
10/27/2020 Revised, Resolution No. 20-8895
Attachments: Council Item Request Form
City of
Santa Clara
The Center of What's Possible
COUNCIL ITEM REQUEST FORM
The Council Item Request Form is for members of the City Council to submit written requests to the City Manager’s Office for inclusion of an item on a future City Council meeting agenda. At the meeting where the initial written request is heard, discussion should be limited to whether the item should be added to an agenda and a date, not the merit of the item. A majority vote of the City Council is required for the item to be added to future Council meeting agenda for action.
CONTACT INFORMATION
Requesting Member of City Council
Contact E-mail
Contact Phone
Today’s Date
WRITTEN REQUEST
I, , hereby request that the following item
be placed on the City of Santa Clara Council and Authorities Concurrent meeting agenda:
Reference: Council Policy 030 – Adding an Item on the Agenda Resolution No. 23-9278
City of
Santa Clara
The Center of What's Possible
COUNCIL ITEM REQUEST FORM
The Council Item Request Form is for members of the City Council to submit written requests to the City Manager’s Office for inclusion of an item on a future City Council meeting agenda. At the meeting where the initial written request is heard, discussion should be limited to whether the item should be added to an agenda and a date, not the merit of the item. A majority vote of the City Council is required for the item to be added to future Council meeting agenda for action.
CONTACT INFORMATION
Requesting Member of City Council
Contact E-mail
Contact Phone
Today’s Date
WRITTEN REQUEST
I, , hereby request that the following item
be placed on the City of Santa Clara Council and Authorities Concurrent meeting agenda:
Reference: Council Policy 030 – Adding an Item on the Agenda Resolution No. 23-9278
The City used to have a Sustainability Manager who reported to the City Manager. That person ended up working on other issues like public relations while still being in the role of the Sustainability Manager. We now have a management analyst who is supposedly dedicated for sustainability but is also working on a number of issues like supporting the Neighborhood University Relations Committee (NURC).
With a $1.6 billion overall City budget that eclipses cities that are larger in population than Santa Clara, we deserve to have a full-time sustainability manager. Fremont, Mountain View and Palo Alto have full time sustainability managers.
Santa Clara has a very aggressive Climate Action plan in terms of carbon emissions but we don't seem to be tracking how we are doing relative to our stated goals. Silicon Valley Power has a FY2024-25 operating budget is $909 million with electricity sales of $723 million. The total carbon emissions from electricity sales is immense.
We need a dedicated manager who is responsible for all kinds of activities like increasing recycling, reducing water usage, increasing composting and reducing carbon emissions and then tracking the numbers. Individually many departments have sustainability activities but there doesn't seem to be anyone to coordinate those activities and to aggregate the impacts.
We also need to update our Climate Action Plan which was last updated in 2022.