CITY CONTRACT NO. 2026-170 5
CITY PROJECT NO. 25-057
Rev. 08/2025

5.2. EXCUSABLE DELAYS
Contractor shall not be in breach of the Contract in the event that performance of Services is temporarily interrupted or discontinued due to a “Force Majeure” event which is defined as: riots, wars, sabotage, civil disturbances, insurrections, or explosions; natural disasters, such as floods, earthquakes, landslides, and fires; strikes, lockouts, and other labor disturbances; or other catastrophic events, which are beyond the reasonable control of Contractor. Force Majeure does not include Contractor’s financial inability to perform, Contractor’s failure to obtain any necessary permits or licenses from other governmental agencies, or Contractor’s failure to obtain the right to use the facilities of any public utility where such failure is due solely to the acts or omissions of Contractor. If Contractor’s performance of the Services is delayed by an excusable delay, the Substantial and Final Completion Due Dates shall be extended for such reasonable time as determined by the City Engineer. Extensions in time must be requested by Contractor within fifteen (15) calendar days of the excusable delay in order to receive consideration.

5.3. EMERGENCY - ADDITIONAL TIME FOR PERFORMANCE - PROCUREMENT OF

MATERIALS
If, because of war or other declared national emergency, the federal or state government restricts, regulates, or controls the procurement and allocation of labor or materials, or both, and if solely because of said restrictions, regulations or controls, Contractor is, through no fault of Contractor, unable to perform the Services, or the work is thereby suspended or delayed, any of the following steps may be taken:

A. City may, pursuant to resolution of the City Council, grant Contractor additional time for the performance of the Contract, sufficient to compensate in time, for delay or suspension.

To qualify for such extension in time, Contractor within ten (10) days of Contractor's discovering such inability to perform, shall notify the City Engineer in writing thereof, and give specific reasons therefore; the City Engineer shall thereupon have sixty (60) days within which to procure such needed materials or labor as is specified in this agreement, or permit substitution, or provide for changes in the work in accordance with subdivision (b) of this Section.

Substituted materials, or changes in the work, or both, shall be ordered in writing by the City Engineer, and the concurrence of the City Council shall not be necessary. All reasonable expenses of such procurement incurred by the City Engineer shall be defrayed by the Contractor; or B. If such materials or labor cannot be procured through legitimate channels within sixty (60) days after the filing of the aforesaid notice, either Party may, upon thirty (30) days' written notice to the other, terminate this agreement. In such event, Contractor shall be compensated for all work executed upon a unit basis in proportion to the amount of the work completed, or upon a cost plus-ten-percent (10%) basis, whichever is the lesser. Materials on the ground, in process of fabrication or in route upon the date of notice of termination specially ordered for the Project and which cannot be utilized by Contractor, shall be compensated for by City at cost, including freight, provided Contractor shall take all steps possible to minimize this obligation; or
C. The City Council, by resolution, may suspend the Contract until the cause of inability to perform is removed for a period of not to exceed sixty (60) days.

If the Contract is not canceled, and the inability of Contractor to perform continues without fault on Contractor's part, beyond the time during which the Contract may have been suspended, as herein above Contract Packet - 5 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 425 of 616 ends

CITY CONTRACT NO. 2026-170 6
CITY PROJECT NO. 25-057
Rev. 08/2025
provided, the City Council may further suspend the Contract, or either Party hereto may, without incurring any liability, elect to declare the Contract terminated upon the ground of impossibility of performance. In the event City declares this agreement terminated, such declaration shall be authorized by the City Council by resolution, and Contractor shall be notified in writing thereof within five (5) days after the adoption of such resolution. Upon such termination, Contractor shall be entitled to proportionate compensation at the Contract Price for such portion of the Contract as may have been performed; or
D. City may terminate the Contract, in which case Contractor shall be entitled to proportionate compensation at the agreed rate for such portion of the Contract as may have been performed. Such termination shall be authorized by resolution of the City Council. Notice thereof shall be forthwith given in writing to Contractor, and the Contract shall be terminated upon receipt by Contractor of such notice.

In the event of the termination provided in this sub paragraph (iv), none of the covenants, conditions or provisions hereof shall apply to the Services not performed, and City shall be liable to Contractor for the proportionate compensation last herein mentioned.

5.4. DELAY DAMAGES
In the event Contractor, for any reason, fails to perform the Services to the satisfaction of the City Engineer by the Substantial Completion Due Date, City may, in accordance with Section 7203 of the Public Contract Code, in lieu of any other of its rights authorized by TERMINATION of this agreement, deduct from payments or credits due Contractor after such breach a sum equal to Five Thousand Two Hundred and No/100ths Dollars ($5,200.00) for each calendar day beyond the Substantial Completion Due Date. Upon Substantial Completion of the work, and in the event Contractor, for any reason, fails to perform the Services to the satisfaction of the City Engineer by the Final Completion Due Date, City may, in accordance with Section 7203 of the Public Contract Code, in lieu of any other of its rights authorized by TERMINATION of this agreement, deduct from payments or credits due Contractor after such breach a sum equal to One Thousand One Hundred and No/100ths Dollars ($1,100.00) for each calendar day beyond the Final Completion Due Date. This deduction shall not be considered a penalty but shall be considered as delay damages. The aforementioned rate of deduction is an amount agreed to by the Parties as reasonably representing additional construction engineering costs incurred by City if Contractor fails to complete the Services by the Substantial and Final Completion Due Dates. However, any deduction assessed as delay damages shall not relieve Contractor from liability for any damages or costs resulting from delays to other contractors on the project or other projects caused by a failure of the assessed Contractor to complete the Services by the Substantial and Final Completion Due Dates.

Due account shall be taken of any time extensions granted to Contractor by City. Permitting Contractor to continue work beyond the Substantial and Final Completion Due Dates shall not operate as a waiver on the part of City of any of its rights under the Contract nor shall it relieve Contractor from liability for any damages or costs resulting from delays to other contractors on the project or other projects caused by a failure of the assessed Contractor to complete the Services by the Substantial and Final Completion Due Dates.

6. TERMINATION
A. Option of City to Terminate Contract for Failure to Complete Services. If a Party should fail to perform any of its obligations hereunder within the time and in the manner herein provided, or otherwise violates Contract Packet - 6 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 426 of 616 ends

CITY CONTRACT NO. 2026-170 7
CITY PROJECT NO. 25-057
Rev. 08/2025
any of the terms of the Contract (the “Defaulting Party”), the other Party shall give notice to the Defaulting Party and allow the Defaulting Party ten (10) days to correct such deficiency. If the Defaulting Party does not correct such deficiency, the other Party may immediately terminate the Contract by giving written notice of such termination, stating the reason for such termination. In such event, Contractor shall be entitled to receive payment for all Services satisfactorily rendered until such termination, provided, however, there shall be deducted from such amount the amount of damage, if any, sustained by virtue of any breach of the Contract by Contractor, including Delay Damages. If payment under the Contract is based upon a lump sum in total or by individual task, payment for Services satisfactorily rendered shall be an amount which bears the same ratio to the total fees specified in this Agreement as the Services satisfactorily rendered hereunder by Contractor to the total services otherwise required to be performed for such total fee, provided, however, that there shall be deducted from such amount the amount of damage, if any sustained by City by virtue of any breach of the Contract by Contractor. Upon termination, Contractor shall deliver copies of all Work Product, as defined in OWNERSHIP OF WORK PRODUCT of this Agreement, to City. If District terminates the Contract before Contractor commences any Services hereunder, City shall not be obligated to make any payment to Contractor.

B. If Contractor should be adjudged bankrupt or if it should make a general assignment for the benefit of its creditors, or if a receiver should be appointed on account of its insolvency, or if it or any of its subcontractors should violate any of the provisions of the Contract, City may serve written notice upon it and its surety of its intention to terminate the Contract. Such notice shall contain the reasons for City’s intention to terminate the Contract, and unless such violations shall cease within five (5) calendar days after serving of such notice, the Contract shall cease and terminate upon the expiration of said five (5) calendar days. In the event of any such termination, City shall immediately serve written notice thereof upon the surety and Contractor, and the surety shall have the right to take over and perform the Contract; provided however, that, if the surety does not give City written notice of its intention to take over and perform the Contract or does not commence performance thereof within thirty (30) calendar days from the date of the service of such notice, City may take over the work and prosecute the same to completion by contract or any other method it may deem advisable, for the account and at the expense of Contractor, and Contractor and its surety shall be jointly liable to City for any excess cost occasioned City thereby, and in such event City may, without liability for so doing, take possession of and utilize in completing the work, such materials, appliances, and other property belonging to Contractor as may be on the Project site and necessary thereof.

7. LIABILITY FOR BREACH
Neither Party waives the right to recover direct damages against the other for breach of the Contract, including any amount necessary to compensate City for all detriment proximately caused by Contractor's failure to perform its obligations hereunder or which in the ordinary course of things would be likely to result therefrom. City reserves the right to offset such damages against any payments owed to Contractor. City shall not, in any manner, be liable for special or consequential damages, including but not limited to Contractor's actual or projected lost profits had Contractor completed the Services required by the Contract. In the event of termination by either Party, copies of all finished or unfinished Work Product, as defined in OWNERSHIP OF Contract Packet - 7 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 427 of 616 ends

CITY CONTRACT NO. 2026-170 8
CITY PROJECT NO. 25-057
Rev. 08/2025
WORK PRODUCT of this Agreement, shall become the property of City. Notwithstanding the foregoing, in no event shall City be liable, regardless of whether any claim is based on contract or tort, for any special, consequential, indirect or incidental damages, including, but not limited to, lost profits or revenue, arising out of or in connection with the Contract or the Services performed in connection with the Contract.

8. COMPENSATION
City shall make payments to Contractor in accordance with the provisions of DISPUTES PERTAINING TO PAYMENT FOR WORK of the City Standards in legally executed and regularly issued warrants of City, drawn on the appropriate fund or funds as required by law and order of the City Council thereof. Contractor shall be administered a progress payment approximately every thirty (30) calendar days from the time work begins according to the payment schedule furnished by the City Engineer at the time work begins. Contractor shall provide access at all reasonable times to all reports, contract records, contract documents, contract files, and personnel necessary to audit and verify Contractor’s charges to City under this Contract.

Monthly progress payments in the amount of 95 percent (95%) of the value of the work will be made to Contractor based on the Contractor’s estimate and the schedule of prices contained in the accepted bid. The remaining 5 percent (5%) will be retained by City as partial security for the fulfillment of the Contract except that at any time after 50 percent (50%) of the work has been completed, if the City Engineer finds that satisfactory progress is being made and the Project’s critical path of work are on schedule, City may discontinue any further retention. Such discontinuance will only be made upon the written request of Contractor. City may, at any time the City Engineer finds that satisfactory progress is not being made, again institute retention of 5 percent (5%) as specified above. Payment will be made as soon as possible after the preparation of the Contractor’s estimate. City shall pay the remaining 5 percent (5%) of the value of the Services completed under this Contract, if unencumbered by retentions for claims, not sooner than the expiration of thirty-five (35) calendar days from the date of recordation of the Notice of Completion, pursuant to TERM of this agreement, and not later than sixty (60) days from the “completion” of the Services as said term is defined in Public Contract Code section 7107(c).

No estimate or payment shall be made if, in the judgment of the City Engineer, the work is not proceeding in accordance with the provisions of the Contract, or when, in his judgment, the total value of the work done since the last estimate amounts to less than $1,000. No progress payments will be made if the time allotted for the job is thirty (30) working days or less. Payment of any progress payment, or the acceptance thereof by Contractor, shall not constitute acceptance of the work performed under this Contractor, or any portion thereof, and shall in no way reduce the liability of Contractor to replace unsatisfactory work or materials, though the unsatisfactory character of such work or materials may not have been apparent or detected at the time such payment was made.

Additionally, as a precondition to City’s progress payments hereunder, Contractor shall provide to City, prior to payment, unconditional waivers and releases of stop notices pursuant to Civil Code section 8128 et seq. from each subcontractor and materials supplier. The form of said waivers and releases shall be as set forth in Civil Code section 3262(d)(2).

Pursuant to Public Contract Code section 22300 et seq., Contractor may request the right to substitute securities for any moneys withheld by City to ensure the performance required of Contractor under the Contract, or that City make payment of retentions earned directly into an escrow account established at the expense of Contractor.

9. DISPUTES PERTAINING TO PAYMENT FOR WORK
Contract Packet - 8 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 428 of 616 ends

CITY CONTRACT NO. 2026-170 9
CITY PROJECT NO. 25-057
Rev. 08/2025
Should any dispute arise respecting the true value of any work performed, of any work omitted, or of any extra work which Contractor may be required to do, or respecting the size of any payment to Contractor during the performance of the Contract, such dispute shall be decided by the City Engineer, and the decision of the latter shall be final and conclusive. The Parties agree to comply with the claims resolution procedures set forth in Public Contract Code section 9204 when applicable.

9.1. CLAIMS PROCESSING
Any submission of a claim by Contractor must comply with the requirements of Public Contract Code section 9204. Upon receipt of a claim pursuant to this section, City shall conduct a reasonable review of the claim and, within a period not to exceed forty-five (45) days, shall provide Contractor a written statement identifying what portion of the claim is disputed and what portion is undisputed. Upon receipt of a claim, the Parties may, by mutual agreement, extend the time period provided in this subdivision. Contractor shall furnish reasonable documentation to support the claim. Any payment due on an undisputed portion of the claim shall be processed and made within sixty (60) days after City issues its written statement. If Contractor disputes City’s written response, or if City fails to respond to a claim issued pursuant to this section within the time prescribed, Contractor may demand in writing an informal conference to meet and confer for settlement of the issues in dispute.

9.2. MEET-AND-CONFER CONFERENCE
Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, City shall schedule a meet-and-confer conference within thirty (30) days for settlement of the dispute. Within ten (10) business days following the conclusion of the meet-and-confer conference, if the claim or any portion of the claim remains in dispute, City shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within sixty (60) days after the City issues its written statement.

9.3. NONBINDING MEDIATION
Any disputed portion of the claim, as identified by Contractor in writing, shall be submitted to nonbinding mediation, with the Parties sharing the associated costs equally. The Parties shall mutually agree to a mediator within ten (10) business days after the disputed portion of the claim has been identified in writing. If the Parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each Party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject judicial review pursuant to ARBITRATION OF DISPUTES of this Agreement.

Notwithstanding any claim, dispute, or other disagreement between the Parties regarding performance under the Contract, the scope of work hereunder, or any other matter arising out of or related to, in any manner, the Contract, Contractor shall proceed diligently with performance of the Services in accordance with City's written direction, pending any final determination or decision regarding any such claim, dispute, or disagreement.

10. PERMITS AND CARE OF WORK
Contractor shall, at Contractor's expense, obtain all necessary permits and licenses for the construction of each improvement, give all necessary notices and pay all fees and taxes required by law, except those City fees set forth in Special Provisions. Contractor has examined the Project site and is familiar with its topography and condition, location of property lines, easements, building lines, and other physical factors and limitations Contract Packet - 9 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 429 of 616 ends

CITY CONTRACT NO. 2026-170 10
CITY PROJECT NO. 25-057
Rev. 08/2025
affecting the performance of the Contract. Contractor, at Contractor's expense, shall obtain any permission necessary for any operations conducted off the property owned or controlled by City. Contractor shall be responsible for the proper care and protection of all materials delivered and work performed until completion and final acceptance.

11. PUBLIC WORKS AND PAYMENT OF PREVAILING WAGE

11.1. MONITORING AND ENFORCEMENT
In accordance with the provisions of Sections 1725.5, 1771.1, 1771.3, and 1771.4 of the Labor Code, all work performed under the Contract is subject to compliance monitoring and enforcement by the Department of Industrial Relations (“DIR”). All work performed by Contractor or its subcontractors under the Contract is subject to the requirements of Labor Code section 1720 et seq. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 of the Labor Code at the time the contract is awarded. Contractor and its subcontractors shall furnish the records specified in Section 1776 of the Labor Code directly to the Labor Commissioner, at least monthly, in the format prescribed by the Labor Commissioner.

In accordance with the provisions of Section 1773.3 of the Labor Code, City shall provide notice to DIR of the award of this Contract within thirty (30) working days of the award. The notice shall be transmitted electronically in a format specified by DIR and shall include the name of Contractor, any subcontractor listed on the successful bid, the bid and contract award dates, the contract amount, the estimated start and completion dates, Project location, and any additional information DIR specifies that aids in the administration and enforcement of Section 1720 et seq. of the Labor Code.

11.2. WAGES & HOURS OF EMPLOYMENT
In the performance of the Services under the Contract, eight (8) hours shall be the maximum hours of labor on any calendar day, and the minimum wages of compensation of persons performing labor in the execution of this agreement shall be the current prevailing scale of wages determined by DIR for the community. Contractor shall forfeit as penalty Twenty-five and no/100ths Dollars ($25.00) to be paid to City for each workman employed in the execution of the Contract by Contractor or its subcontractor(s), for each calendar day during which any workman is required or permitted to labor more than eight (8) hours, in violation of provisions of Labor Code section 1810 et seq. Contractor shall post prevailing wage rates at the Project no later than the first day Contractor commences performance of the Services under the Contract.

12. SUPERINTENDENCE BY CONTRACTOR
Contractor shall give personal superintendence to the work on the Project or have a competent foreman or superintendent satisfactory to the City Engineer on the Project at all times during construction and performance of work under the Contract, with authority to act for Contractor.

13. INSPECTION AND TESTING BY CITY
Contractor shall at all times maintain proper facilities and provide safe access for inspection by City to all parts of the work performed on the Project and to the shops wherein the work is in preparation. Contractor shall notify City with sufficient time in advance of the manufacture of production materials to be supplied by Contractor under the Contract in order for City to arrange for mill or factory inspection and testing of Contract Packet - 10 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 430 of 616 ends

CITY CONTRACT NO. 2026-170 11
CITY PROJECT NO. 25-057
Rev. 08/2025
same. Any materials shipped by Contractor from factory prior to having satisfactorily passed such testing and inspection by City's representative or prior to the receipt of notice from such representative that such testing and inspection will not be required shall not be incorporated on the Project. Contractor shall also furnish to City, in triplicate, certified copies of all factory and mill test reports upon request.

14. CONFORMITY WITH LAW AND SAFETY
Contractor shall observe and comply with all applicable laws, ordinances, codes, and regulations of governmental agencies, including federal, state, municipal, and local governing bodies having jurisdiction over any or all of the scope of Services, including all provisions of the Occupational Safety and Health Act of 1979 as amended, all California Occupational Safety and Health Regulations, the California Building Code, the American with Disabilities Act, any copyright, patent, or trademark law, and all other applicable federal, state, municipal, and local safety regulations, appropriate trade association safety standards, and appropriate equipment manufacturer instructions. All Services performed by Contractor or its subcontractors must be in accordance with these laws, ordinances, codes, and regulations. Contractor’s failure to comply with any laws, ordinances, codes, or regulations applicable to the performance of the Services hereunder shall constitute a breach of contract. In cases where standards conflict, the standard providing the highest degree of protection shall prevail.

If a death, serious personal injury or substantial property damage occurs in connection with the performance of the Contract, Contractor shall immediately notify City's risk manager by telephone. If any accident occurs in connection with the Contract, Contractor shall promptly submit a written report to City, in such form as City may require. This report shall include the following information: (a) name and address of the injured or deceased person(s); (b) name and address of Contractor’s subcontractor, if any; (c) name and address of Contractor’s liability insurance carrier; and (d) a detailed description of the accident, including whether any of City's equipment, tools, or materials were involved.

If a release of a hazardous material, substance, or waste occurs in connection with the performance of the Contract, Contractor shall immediately notify City. Contractor shall not store hazardous materials or hazardous waste within City limits without a proper permit from City.

15. OTHER CONTRACTS
City may award other contracts for additional work on the Project, and Contractor shall fully cooperate with such other contractors and carefully fit Contractor's own work to that provided under other contracts as may be directed by the City Engineer. Contractor shall not commit or permit any act which will interfere with the performance of work by any other contractor.

16. BONDS
Concurrently with the execution hereof, Contractor shall furnish, on the forms provided herein as Exhibits D and E, respectively, corporate surety bonds to the benefit of City, issued by a surety company acceptable to City and authorized and admitted to do business in the state of California, as follows:

A. Faithful Performance Bond. In an amount equal to at least one hundred percent (100%) of the Contract Price as security for the faithful performance of the Contract. The bond shall contain a provision that the surety thereon waives the provisions of Sections 2819 and 2845 of the Civil Code.

B. Payment Bond. In an amount equal to at least one hundred percent (100%) of the Contract Price as security for the payment of all persons performing labor and furnishing materials in connection with the Contract Packet - 11 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 431 of 616 ends

CITY CONTRACT NO. 2026-170 12
CITY PROJECT NO. 25-057
Rev. 08/2025
Contract. The bond shall be in accordance with the provisions of Sections 3225, 3226, and 3247 through 3252, inclusive, of the Civil Code and Section 13020 of the Unemployment Insurance Code of California. Said bond shall also contain a provision that the surety thereon waives the provisions of Sections 2819 and 2845 of the Civil Code.

The surety companies shall familiarize themselves with all provisions and conditions of the Contract. It is understood and agreed that the surety or sureties waive the right of special notification of any modification or alterations, omissions or reductions, extra or additional work, extensions of time, or any other act or acts by City or its authorized agents under the terms of this Contract and failure to so notify the surety or sureties of such changes shall in no way relieve the surety or sureties of their obligations under the Contract.

17. INDEMNIFICATION

17.1. INDEMNITY FOR PROFESSIONAL LIABILITY
When the law establishes a professional standard of care for Contractor’s Services, to the fullest extent permitted by law, Contractor shall indemnify, protect, defend, and hold harmless City and any and all of its elective and appointive boards, officers, officials, agents, employees or volunteers (“City’s Agents”) from and against any and all losses, liabilities, damages, costs, and expenses, including legal counsel’s fees and costs but only to the extent Contractor or its subcontractors are responsible for such damages, liabilities and costs on a comparative basis of fault between Contractor or its subcontractors and City in the performance of professional services under the Contract. Contractor shall not be obligated to defend or indemnify City for City’s own negligence or for the negligence of others.

17.2. INDEMNITY FOR OTHER THAN PROFESSIONAL LIABILITY
Other than in the performance of professional services and to the full extent permitted by law, Contractor shall indemnify, defend, and hold harmless City and any and City’s Agents from and against any liability, including liability for claims, suits, actions, arbitration proceedings, administrative proceedings, regulatory proceedings, losses, expenses or costs of any kind, whether actual, alleged or threatened, including legal counsel’s fees and costs, court costs, interest, defense costs, and expert witness fees, where the same arise out of, are a consequence of, or are in any way attributable to, in whole or in part, the performance of the Contract by Contractor or by any individual or agency for which Contractor is legally liable, including, but not limited to, officers, agents, employees, or subcontractors of Contractor.

18. CONTRACTOR'S INSURANCE
Concurrently with the execution hereof, Contractor shall furnish City with satisfactory proof of carriage of the insurance required under this section, and that Contractor shall give City at least thirty (30) days prior notice of the cancellation of any policy during the Term of this contract. Contractor shall not commence work under this Agreement until Contractor has obtained City’s approval regarding all insurance requirements, forms, endorsements, amounts, and carrier ratings, nor shall Contractor allow any subcontractor to commence work on a subcontract until all similar insurance required of the subcontractor shall have been so obtained and approved. Contractor shall procure and maintain for the duration of the Contract insurance against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the Services hereunder by Contractor, its agents, representatives, employees or subcontractors. Failure to maintain or renew coverage or to provide evidence of renewal may constitute a material breach of the Contract. Any available insurance proceeds in excess of the specified minimum limits and coverage shall be available to City.

The City of Turlock shall be named as a certificate holder.

Contract Packet - 12 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 432 of 616 ends

CITY CONTRACT NO. 2026-170 13
CITY PROJECT NO. 25-057
Rev. 08/2025

18.1. COMMERCIAL GENERAL LIABILITY INSURANCE
Contractor shall maintain commercial general liability insurance with coverage at least as broad as Insurance Services Office form CG 00 01, in an amount not less than Two Million Dollars ($2,000,000.00) per occurrence, Four Million Dollars ($4,000,000.00) general aggregate, and Two Million Dollars ($2,000,000.00) products and completed operations for bodily injury, personal injury, and property damage, including, without limitation, blanket contractual liability and coverage for explosion, collapse, and underground property damage hazards. The general aggregate limit shall apply separately to this Project or the general aggregate shall be doubled. The policy shall contain, or be endorsed to contain, the following provisions:

A. City, its elective and appointive boards, officers, agents, employees, and volunteers are to be covered as additional insureds with respect to liability arising out of work or operations performed by or on behalf of Contractor, including materials, parts or equipment furnished in connection with such work or operations. The coverage shall be provided in the form of an endorsement to Contractor’s insurance (at least as broad as CG 20 10 for ongoing operations and CG 20 37 for products/completed operations for construction services). The City shall be named as a certificate holder on the Certificate of Insurance.

B. For any claims related to the Project, Contractor’s insurance coverage shall allow and be endorsed primary insurance as respects City and any insurance or self-insurance maintained by City shall be excess of Contractor’s insurance and shall not contribute with it.

C. In the event of cancellation, non-renewal, or material change that reduces or restricts the insurance coverage afforded to City under the Contract, the insurer, broker/producer, or Contractor shall provide City with thirty (30) days’ prior written notice of such cancellation, non-renewal, or material change.

D. Coverage shall not extend to any indemnity coverage for the sole negligence of the additional insured in any case where an agreement to indemnify the additional insured would be invalid under Subdivision (b) of Section 2782 of the Civil Code.

18.2. WORKERS' COMPENSATION INSURANCE
Contractor shall maintain Workers’ Compensation Insurance (Statutory Limits) and Employer’s Liability Insurance with limits of at least One Million Dollars ($1,000,000.00) each accident, One Million Dollars ($1,000,000.00) by disease-policy limit, and One Million Dollars ($1,000,000.00) by disease-each employee. Contractor shall submit to City, along with the Certificate of Insurance, a Waiver of Subrogation endorsement in favor of the City, its offices, agents, employees, and volunteers.

18.3. COMMERCIAL AUTOMOBILE LIABILITY INSURANCE
Contractor shall maintain commercial automobile liability insurance using ISO Business Auto Coverage form CA 00 01, or the exact equivalent, with a limit of no less than Two Million Dollars ($2,000,000.00) each accident for owned, leased, hired, non-owned, and borrowed automobiles. The policy shall provide and be endorsed that the City, its officials, officers, agents, employees, and volunteers are included or named as additional insureds. If Contractor owns no vehicles, this requirement may be met through a non-owned auto coverage or an endorsement to the CGL policy.

18.4. CONTRACTORS POLLUTION INSURANCE
Contract Packet - 13 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 433 of 616 ends

CITY CONTRACT NO. 2026-170 14
CITY PROJECT NO. 25-057
Rev. 08/2025
Pollution Coverage shall be maintained on a Contractors Pollution Liability form, or other form acceptable to City, providing coverage for liability arising out of sudden, accidental, and gradual pollution and remediation. The policy limit shall be no less than Two Million Dollars ($2,000,000.00) per claim. All activities contemplated in the Contract shall be specifically scheduled on the policy as “covered operations.” The policy shall provide coverage for the hauling of waste from the Project site to the final disposal location, including non-owned disposal sites. The policy shall provide and be endorsed to include the City, its officials, officers, agents, employees, and volunteers as insureds.

18.5. UMBRELLA OR EXCESS POLICY
Contractor may use Umbrella or Excess Policies to provide the liability limits as required in this agreement. This form of insurance will be acceptable provided that all of the Primary and Umbrella or Excess Policies shall provide all of the insurance coverages herein required. The Umbrella or Excess policies shall be provided on a true “following form” or broader coverage basis, with coverage at least as broad as provided on the underlying Commercial General Liability and Automobile Liability insurance. No coverage or insurance policies maintained by the Additional Insureds, whether primary or excess, and which also apply to a loss covered hereunder, shall be called upon to contribute to a loss until the Contractor’s primary and excess liability policies are exhausted.

18.6. DEDUCTIBLES AND SELF-INSURED RETENTIONS
Upon request of City, any deductibles or self-insured retentions must be declared to and approved by City. At the option of City, either: (1) the insurer shall reduce or eliminate such deductibles or self-insured retentions as respects City and City’s Agents; or (2) Contractor shall provide a financial guarantee satisfactory to City guaranteeing payment of losses and related investigations, claim administration, and defense expenses.

18.7. ACCEPTABILITY OF INSURERS
Insurance is to be placed with insurers with a current A.M. Best’s rating of no less than A-:VII or with an insurer to which City has provided prior approval.

18.8. VERIFICATION OF COVERAGE
Contractor shall furnish City with original certificates and amendatory endorsements or copies of the applicable policy language effecting coverage required by CONTRACTOR'S INSURANCE. All certificates and endorsements are to be received and approved by City before work commences. However, failure to obtain the required documents prior to the work beginning shall not waive Contractor’s obligation to provide them. City reserves the right, at any time, to require complete, certified copies of all required insurance policies and endorsements.

18.9. WAIVER OF SUBROGATION
With the exception of professional liability, Contractor hereby agrees to waive subrogation which any insurer of Contractor may acquire from Contractor by virtue of the payment of any loss. The commercial general liability policy, automobile liability policy, and workers’ compensation policy shall be endorsed to contain a waiver of subrogation in favor of City for all work performed by Contractor, its agents, employees, independent contractors and subcontractors. Contractor shall provide written proof of waiver of subrogation in the Certificate of Insurance. Additionally, Contractor agrees to obtain any available endorsements that may be necessary to effectuate this waiver of subrogation.

18.10. SUBCONTRACTORS
Contract Packet - 14 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 434 of 616 ends

CITY CONTRACT NO. 2026-170 15
CITY PROJECT NO. 25-057
Rev. 08/2025
Contractor shall ensure all subcontractors furnish separate certificates and endorsements for each subcontractor. All coverages for subcontractors shall be subject to all of the requirements stated herein.

19. OWNERSHIP OF WORK PRODUCT
Any and all work, artwork, copy, posters, billboards, photographs, videotapes, audiotapes, systems designs, software, reports, designs, specifications, drawings, diagrams, surveys, source codes, professional or technical information or data, photographs, notes, letters, emails, or any original works of authorship created by contractor or its subcontractors or subcontractors in connection with Services performed under the Contract (“Work Product”) shall be works for hire as defined under Title 17 of the United States Code, and all copyrights in such works are the property of City. In the event that it is ever determined that any Work Product created by Contractor or its subcontractors or subcontractors under the Contract are not works for hire under U.S. law, Contractor hereby assigns all copyrights to such Work Product to City. With the prior written approval of the City Engineer, Contractor may retain and use copies of such Work Product for reference and as documentation of its experience and capabilities.

All Work Product shall become the property of City irrespective of where located or stored and Contractor agrees to deliver all such documents and information to City, without charge and in whatever form it exists, upon the Final Completion Date, as may be extended. Contractor shall have no ownership interest in such Work Product.

All Work Product of Contractor under the Contract, including written information which City will cause to be distributed for either internal or public circulation, including both preliminary and final drafts, shall be delivered to City in both printed and electronic form, or as may be specific in Exhibit A.

When the Contract is terminated, Contractor agrees to return to City all documents, drawings, photographs, and other written or graphic material, however produced, that it received from City or City’s Agents, in connection with the performance of its Services under the Contract. All materials shall be returned in the same condition as received.

20. TAXES
Payment of any taxes, including California sales and use taxes, levied upon the Contract, the transaction, or the Services or goods delivered pursuant hereto, shall be the obligation of Contractor. Contractor shall cooperate with City to the full extent possible to maximize the local allocation of California sales and use tax to City. Such cooperation shall include, but not be limited to:

A. Use Tax Direct Payment Permits. Contractor shall apply for, obtain, and utilize, to the maximum extent reasonable, a California Use Tax Direct Payment Permit.

B. Purchases of $500,000 or More. Contractor shall require vendors and suppliers located outside California from whom Contractor makes purchases of $500,000 or more to allocate the use tax to City.

21. INDEPENDENT CONTRACTOR
At all times during the Term of the Contract, Contractor shall be deemed to be an independent contractor and shall be wholly responsible for the manner in which Contractor performs the Services required under the Contract. Contractor shall be liable for its acts and omissions, and those of its employees, contractors, subcontractors, representatives, volunteers, and its agents. Nothing contained herein shall be construed as creating an employment, agency, or partnership relationship between City and Contractor. City shall have the Contract Packet - 15 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 435 of 616 ends

CITY CONTRACT NO. 2026-170 16
CITY PROJECT NO. 25-057
Rev. 08/2025
right to control Contractor only insofar as the result of Contractor’s Services rendered pursuant to the Contract; however, City shall not have the right to control the means by which Contractor accomplishes Services rendered pursuant to the Contract.

22. CONTRACTOR NOT AGENT
Except as City may specify in writing, Contractor shall have no authority, express or implied, to act on behalf of City in any capacity whatsoever as an agent. Contractor shall have no authority, express or implied, pursuant to the Contract to bind City to any obligation whatsoever.

23. ARBITRATION OF DISPUTES
All claims, disputes, and other matters in question between City and Contractor arising out of, or relating to, this Contract or the breach thereof, including claims of Contractor for extra compensation of Services related to the project, shall be decided by arbitration before a single arbitrator in accordance with the provisions of Sections 1281 through 1284.2 of the Code of Civil Procedure (the “Arbitration Laws”) unless the Parties mutually agree otherwise. The provisions of Section 1283.05 of the Arbitration Laws apply to any arbitration proceeding except as otherwise provided in the Contract. The arbitrator shall have authority to decide all issues between the Parties including, but not limited to, claims for extras, delay, and liquidated damages, if any, provided for the Contract, matters involving defects in the Services performed by Contractor or its subcontractors, rights to payment, and whether the necessary procedures for arbitration have been followed. The award rendered by the arbitrator shall be final and judgment may be entered upon it in accordance with applicable law in any court having competent jurisdiction thereof.

Notice of the demand for arbitration shall be filed in writing with the other Party. The demand for arbitration shall be made within a reasonable time after the claim, dispute, or other matter in question has arisen, and in no event shall it be made after the date when institution of legal or equitable proceedings based on such claim, dispute, or other matter in question would be barred by the applicable statute of limitations.

The parties shall jointly appoint an arbitrator within fifteen (15) calendar days of the date of giving the notice of the demand for arbitration. If the Parties are unable to jointly agree upon the appointment of an arbitrator within said fifteen (15) calendar day period, and do not agree in writing to extend said period for a fixed period, then either Party may seek to have the arbitrator appointed by the Superior Court of Stanislaus County in accordance with the Arbitration Laws.

If any proceeding is brought to contest the right to arbitrate and it is determined that such right exists, the losing Party shall pay all costs and attorney’s fees incurred by the prevailing Party.

In addition to the other rules of law which may be applicable to any arbitration hereunder, the following shall apply:

A. Promptly upon the filing of the arbitration, each Party shall be required to set forth in writing and to serve upon each other Party a detailed statement of its contentions of fact and law.

B. All Parties to the arbitration shall be entitled to the discovery procedures provided under Section 1283.05 of the California Code of Civil Procedure.

C. The arbitration shall be commenced and conducted as expeditiously as possible consistent with affording reasonable discovery as provided herein.

D. These additional rules shall be implemented and applied by the arbitrator.

Contract Packet - 16 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 436 of 616 ends

CITY CONTRACT NO. 2026-170 17
CITY PROJECT NO. 25-057
Rev. 08/2025
The costs of arbitration shall be borne by the Parties as determined by the arbitrator, but each Party shall bear its own attorney’s fees associated with the dispute with the other Party and to the arbitration.

All administrative remedies required under DISPUTES PERTAINING TO PAYMENT FOR WORK of this Agreement or pursuant to Public Contract Code section 9204, or required by any other law, shall be exhausted prior to commencement of any arbitration under this ARBITRATION OF DISPUTES.

24. PROVISIONS CUMULATIVE
The provisions of the Contract are cumulative, and in addition to and not in limitation of, any other rights or remedies available to City.

25. NOTICES
All notices shall be in writing and delivered in person or transmitted by certified mail, postage prepaid. Any Party hereto may at any time, by giving ten (10) days’ written notice to the other Party hereto, designate any other address in substitution of the address to which such notice or communication shall be given. Such notices or communications shall be given to the Parties at their addresses set forth below.

If to City: City of Turlock
Attn: City Engineer
156 S. Broadway, Suite 150
Turlock, CA 95380-5461
With courtesy copies to: City of Turlock, City Attorney’s Office Attn: Katie Lucchesi, City Attorney
156 S. Broadway, Suite 230
Turlock, CA 95380-5456
If to Contractor: Ensure Utility Inc dba Phoenix Water Solutions Attn: Kyler Colin, President
8222 S 48th St Suite 180
Phoenix, AZ 85044
If to Contractor’s Sureties: To be added
to contract
record

26. CITY CONTRACT ADMINISTRATOR
The City’s contract administrator and contact person for this Agreement is:

Contract Packet - 17 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 437 of 616 ends

CITY CONTRACT NO. 2026-170 18
CITY PROJECT NO. 25-057
Rev. 08/2025
Julian Avila, Associate Civil Engineer
City of Turlock Engineering Division
156 S. Broadway, Suite 150
Turlock, CA 95380
Telephone: (209) 668-5491
E-mail: [email protected]

27. INTERPRETATION
As used herein, any gender includes each other gender, the singular includes the plural and vice versa.

28. ANTITRUST CLAIMS
Contractor or its subcontractors offer and agree to assign to City all rights, title, and interest to any causes of action under Section Four of the Clayton Act and the Cartwright Act concerning antitrust claims.

29. USE OF CITY PROJECT NUMBER
Contractor or its subcontractors agree to use the aforementioned City project number on all maps, drawings, submittals, billing, and written correspondence that involve City staff or contracted consultants. Nothing in this section shall preclude Contractor or its subcontractors from using their own project numbers for their own internal use.

30. NO CONFLICT OF INTEREST
Contractor represents that no conflict of interest will be created under state or federal law by entering into or in carrying out the Contract.

31. CONFIDENTIALITY
Contractor understands and agrees that, in the performance of Services under the Contract, or in the contemplation thereof, Contractor may have access to private or confidential information that may be owned or controlled by City and that such information may contain proprietary or confidential details, the disclosure of which to third parties may be damaging to City (“Confidential Information”). Contractor shall not, either during or after the Term, disclose to any third party any Confidential Information without the prior written consent of City. If City gives Contractor written authorization to make any such disclosure, Contractor shall do so only within the limits and to the extent of that authorization. Contractor may be directed or advised by the City Attorney on various matters relating to the performance of Services on the Project or on other matters pertaining to the Project, and in such event, Contractor agrees that it will treat all communications between itself, its employees, and its subcontracts as being communications which are within the attorney-client privilege.

32. MODIFICATION
No alteration, amendment, modification, or termination of the Contract shall be valid unless made in writing and executed by all Parties to the Contract.

33. WAIVER
No covenant, term, or condition or the breach thereof shall be deemed waived, except by written consent of the Party against whom the waiver is claimed, and any waiver of the breach of any covenant, term, or condition Contract Packet - 18 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 438 of 616 ends

CITY CONTRACT NO. 2026-170 19
CITY PROJECT NO. 25-057
Rev. 08/2025
shall not be deemed to be a waiver of any preceding or succeeding breach of the same or any other covenant, term, or condition.

34. ASSIGNMENT
No Party to the Contract shall assign, transfer, or otherwise dispose of this Agreement in whole or in party to any individual, firm, or corporation without the prior written consent of the other Party. Subject to the foregoing provisions, the Contract shall be binding upon, and inure to the benefit of, the respective successors and assigns of the Parties hereto.

35. AUTHORITY
All Parties to this Agreement warrant and represent that they have the power and authority to enter into this Agreement and the names, titles, and capacities herein stated on behalf of any entities, persons, states, or firms represented or purported to be represented by such entities, person, states, or firms and that all former requirements necessary or required by state or federal law in order to enter into the Contract have been fully complied with. Further, by entering into this Agreement, neither Party hereto shall have breached the terms or conditions of any other contract or agreement to which such Party is obligated, which such breach would have a material effect hereon.

36. GOVERNING LAW
The Contract shall be governed and construed in accordance with the laws of the state of California.

37. SEVERABILITY
If the Contract in its entirety is determined by an arbitrator or a court of competent jurisdiction to be invalid or unenforceable, the Contract shall automatically terminate as of the date of final entry of judgment. If any provision of the Contract shall be determined to be invalid and unenforceable, or if any provision of the Contract is rendered invalid or unenforceable according the terms of any federal or state statute, which becomes effective after the Effective Date of this Agreement, the remaining provisions shall continue in full force and effect and shall be construed to give effect to the intent of this Agreement.

38. EXECUTION AND COUNTERPARTS
This Agreement may be executed simultaneously and, in several counterparts, each of which shall be deemed an original but together shall constitute one and the same instrument. The Parties agree that this Agreement and any other documents to be delivered in connection herewith may be electronically signed and that any electronic signatures appearing on this Agreement or such other documents are the same as handwritten signatures for the purposes of validity, enforceability, and admissibility.

39. MANDATORY AND PERMISSIVE
“Shall” and “will” and “agrees” are mandatory. “May” and “can” are permissive.

40. HEADINGS
Headings used in this Agreement are for reference purposes only and shall not be considered in construing this Agreement.

41. ATTORNEY'S FEES AND COSTS
Contract Packet - 19 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 439 of 616 ends

CITY CONTRACT NO. 2026-170 20
CITY PROJECT NO. 25-057
Rev. 08/2025
Except as expressly provided for in ARBITRATION OF DISPUTES of this Agreement, if any action at law or in equity, including action for declaratory relief, is brought to enforce or interpret the provisions of the Contract, the prevailing Party shall be entitled to reasonable attorney’s fees and costs, which may be set by the court in the same action or in a separate action brought for that purpose, in addition to any other relief to which such Party may be entitled.

42. NECESSARY ACTS AND FURTHER ASSURANCES
The Parties shall, at their own cost and expense, execute and deliver such further documents and instruments and shall take such other actions as may be reasonably required or appropriate to evidence or carry out the intent and purposes of the Contract.

43. RECITALS
The recitals set forth above (“Recitals”) are true and correct and are hereby incorporated into and made part of this Agreement by this reference. In the event of any inconsistency between the Recitals and Sections of this Agreement, the Sections shall prevail.

Contract Packet - 20 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 440 of 616 ends

IN WITNESS WHEREOF, the Parties have caused this Agreement to be executed by and through their respective officers thereunto duly authorized.

Ensure Utility Inc dba Phoenix Water Solutions, a
California corporation
CITY OF TURLOCK, a California municipal corporation
**signature_152082**

SIGNATURE
**name_152082**

FULL NAME
**role_152082**
TITLE
**text_152082_5dca5ea3**

ADDRESS
**text_152082_a4a9c7b0**
PHONE
**date_signed_152082**

DATE SIGNED
**signature_152086**

SIGNATURE
**name_152086**

FULL NAME
**role_152086**
TITLE
**date_signed_152086**

DATE SIGNED
APPROVED AS TO SUFFICIENCY:
**signature_152084**

SIGNATURE
**name_152084**

FULL NAME
**role_152084**
TITLE
**date_signed_152084**

DATE SIGNED
**signature_152079**

SIGNATURE
**name_152079**

FULL NAME
**role_152079**
TITLE
**date_signed_152079**

DATE SIGNED
APPROVED AS TO FORM:

Contract Packet - 21 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3 602 445-3912
7/1/2026
8222 S 48th St Suite 180 Phoenix, AZ 85044
President
Kyler Colin
RCE, PLS, City Engineer
William D. Morris

Page 441 of 616 ends

**signature_152089**

SIGNATURE
**name_152089**

FULL NAME
**role_152089**
TITLE
**date_signed_152089**

DATE SIGNED
ATTEST:
**signature_152080**

SIGNATURE
**name_152080**

FULL NAME
**role_152080**
TITLE
**date_signed_152080**

DATE SIGNED
Contract Packet - 22 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 442 of 616 ends

Exhibits List

A - A- EXHIBIT A CONTRACTOR'S PROPOSAL FOR SERVICES

B - EXHIBIT B PAYMENT BY FORCE ACCOUNT
C - EXHIBIT C WORKERS’ COMPENSATION INSURANCE CERTIFICATION D - EXHIBIT_D_PERFORMANCE_BOND
E - EXHIBIT_E_PAYMENT_BOND
Contract Packet - 23 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 443 of 616 ends

Exhibit A

A- EXHIBIT A CONTRACTOR'S PROPOSAL FOR

SERVICES
Contract Packet - 24 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 444 of 616 ends

EXHIBIT A
CONTRACTOR’S PROPOSAL FOR SERVICES
Contract Packet - 25 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 445 of 616 ends

City of Turlock, CA
Municipal Services-Engineering
Chris Fisher, Director
156 So. Broadway, Turlock, CA 95380
[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT CIFB-E DBE No. CP 25-057
System Wide AMI and Water Meter Installation – Phase 1
RESPONSE DEADLINE: June 22, 2026 at 4:00 pm
Report Generated: Thursday, June 25, 2026
Ensure Utility Inc dba Phoenix Water Solutions Response

CONTACT INFORMATION
Company:

Ensure Utility Inc dba Phoenix Water Solutions
Email:
[email protected]
Contact:

Luke Sharman
Address:
8222 S 48th St
Suite 180
Phoenix, AZ 85044
Phone:
(602) 445-3912
Website:
phoenixwatersolutions.com
Submission Date:

Jun 22, 2026 11:41 AM (Pacific Time)
Contract Packet - 26 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 446 of 616 ends

[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT CIFB-E DBE No. CP 25-057
System Wide AMI and Water Meter Installation – Phase 1
[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT Invitation For Bid - System Wide AMI and Water Meter Installation – Phase 1

Page 2 ends

ADDENDA CONFIRMATION
Addendum #1
Confirmed Jun 21, 2026 4:02 PM by Luke Sharman
Addendum #2
Confirmed Jun 21, 2026 4:02 PM by Luke Sharman

QUESTIONNAIRE

1. Proposal*
Pass
Bids are to be submitted for the entire work. The amount of the bid for comparison purposes will be the total of all items. The bidder shall set forth for each unit basis item of work a unit price and a total for the item, and for each lump sum item a total for the item.

In accordance with the annexed Notice to Contractors, the undersigned, as bidder, declares that he has carefully examined the location of the proposed work, the plans, specifications and technical requirements therefore, and the proposed forms of contract and bonds mentioned or referred to in said Notice and on file in the Office of the City Engineer of the City of Turlock, together with the prevailing rate of per diem wages for each craft or type of workmen needed to execute said contract; and he proposes and agrees that if this proposal is accepted, he will furnish all labor, materials, equipment, plant transportation, service, sales taxes, permit fees and other costs necessary to complete the construction in strict conformity to the plans and specifications and he will enter into a written contract with the City of Turlock in the form of contract on file in the Office of the City Engineer for such purposes, and that he will execute and/or provide all bonds and insurance certificates required by law and/or by said contract and/or mentioned in said Notice to Contractors all in accordance with and subject to all applicable laws, and that he will take in full payment therefore the unit prices entered on the Bidder's Form.

Confirmed
Contract Packet - 27 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 447 of 616 ends

[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT CIFB-E DBE No. CP 25-057
System Wide AMI and Water Meter Installation – Phase 1
[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT Invitation For Bid - System Wide AMI and Water Meter Installation – Phase 1

Page 3 ends

2. Request for Substitutions*
Pass
You may upload information relative to material or equipment for which you would like to request approval of that were not specifically named in the project specifications. City staff will make an effort to respond to requests for substitution as part of the Q&A and addendum process, though will not be obligated to comment on, approve, or deny any request for substitution.

Confirmed

3. Affidavit*
Pass
Please download the below documents, complete, and upload. • AFFIDAVIT.pdf
AffidavitProposalChecklist_Notarized.pdf

4. INFORMATION REQUIRED OF BIDDER
NUMBER OF YEARS’ EXPERIENCE AS A CONTRACTOR IN CONSTRUCTION WORK OR INSTALLATION WORK SIMILAR TO THAT REQUIRED IN THESE SPECIFICATIONS.*
Pass
10 NAME OF PERSON WHO INSPECTED THE SITE OF THE PROPOSED WORK FOR YOUR FIRM.* Pass
Bryce Crawford
DATE OF INSPECTION*
Pass
Contract Packet - 28 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 448 of 616 ends

[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT CIFB-E DBE No. CP 25-057
System Wide AMI and Water Meter Installation – Phase 1
[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT Invitation For Bid - System Wide AMI and Water Meter Installation – Phase 1

Page 4 ends

06/12/2026

5. PREVIOUS WORK/REFERENCES
Please provide information for four (4) recent projects. If bidder is unable to provide information for four (4) reference projects, it shall provide as many reference projects that it can and City will make a determination as to bidder responsibility based on the available information.

REFERENCE #1: PROJECT NO. AND TITLE OF A PREVIOUS PROJECT YOU COMPLETED.* Pass
Contract CS-2025-0107 - AMI Water Meter Installation and Service Line Investigation Project REFERENCE #1: NAME THE CLASS AND TYPE OF WORK FOR THE COMPLETED PROJECT.* Pass
PWS was contracted by the City of Globe to complete their AMI Water Meter Installation and Service Line Investigation Project. The work included replacement of 3,500 water meters ranging from ¾-inch to 6-inch, along with comprehensive verification of customerside and utility-side service line materials in accordance with ADEQ requirements. Additional scopes of work included excavation and replacement of meter boxes where needed, installation of new curb stops & angle stops, leak repairs, precise GPS documentation, and integration of all collected field data into the City’s utility system.

REFERENCE #1: NAME, ADDRESS AND PHONE NO. OF THE OWNER OF THE COMPLETED PROJECT.* Pass
City of Globe, 150 N Pine St, Globe, AZ 85501, (928) 425-7146.

REFERENCE #1: WHO WAS THE REGISTERED ENGINEER IN CHARGE OF THE COMPLETED PROJECT?* Pass
Travis Ashbaugh, Assistant Public Works Director, City of Globe.

Contract Packet - 29 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 449 of 616 ends

[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT CIFB-E DBE No. CP 25-057
System Wide AMI and Water Meter Installation – Phase 1
[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT Invitation For Bid - System Wide AMI and Water Meter Installation – Phase 1

Page 5 ends

REFERENCE #1: LIST THE TOTAL CONTRACT AMOUNT OF THE COMPLETED PROJECT AND THE AMOUNT OF THE CONTRACT YOU PERFORMED.*
Pass
Total Contract Amount: $972,022.30; Amount Performed by PWS: $972,022.30.

REFERENCE #1: NAME OF PRIME CONTRACTOR (IF YOU WERE SUB) Pass
N/A - PWS was prime contractor.

REFERENCE #1: DATE OF PROJECT COMPLETION
Pass
02/2026
REFERENCE #1: LIST ANY LIQUIDATED DAMAGES THAT WERE ASSESSED.

Pass
None.

REFERENCE #2: PROJECT NO. AND TITLE OF A PREVIOUS PROJECT YOU COMPLETED.

Pass
Contract No. 25-0006 - Meter Reading, Register and Endpoint Installation Services REFERENCE #2: NAME THE CLASS AND TYPE OF WORK FOR THE COMPLETED PROJECT.

Pass
AMI register & endpoint retrofits on 6,100 Badger meters. Dual monthly manual reads completed alongside AMI rollout; 1,115 lid and endpoint installations; endpoint replacements; AMR-to-AMI conversions across San Juan Capistrano, Dana Point, and Laguna Beach.

Contract Packet - 30 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 450 of 616 ends

[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT CIFB-E DBE No. CP 25-057
System Wide AMI and Water Meter Installation – Phase 1
[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT Invitation For Bid - System Wide AMI and Water Meter Installation – Phase 1

Page 6 ends

REFERENCE #2: NAME, ADDRESS AND PHONE NO. OF THE OWNER OF THE COMPLETED PROJECT.

Pass
South Coast Water District, 31592 West Street, Laguna Beach, CA 92651, (949) 499-4555. Contact: Sander Huang.

REFERENCE #2: WHO WAS THE REGISTERED ENGINEER IN CHARGE OF THE COMPLETED PROJECT? Pass
Marc Serna, Assistant General Manager/Chief Engineer, South Coast Water District.

REFERENCE #2: LIST THE TOTAL CONTRACT AMOUNT OF THE COMPLETED PROJECT AND THE AMOUNT OF THE CONTRACT YOU PERFORMED.

Pass
Total Contract Amount: $279,711.00; Amount Performed by PWS: $279,711.00.

REFERENCE #2: NAME OF PRIME CONTRACTOR (IF YOU WERE SUB) Pass
N/A - PWS was prime contractor.

REFERENCE #2: DATE OF PROJECT COMPLETION
Pass
03/2025.

REFERENCE #2: LIST ANY LIQUIDATED DAMAGES THAT WERE ASSESSED.

Pass
None.

Contract Packet - 31 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 451 of 616 ends

[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT CIFB-E DBE No. CP 25-057
System Wide AMI and Water Meter Installation – Phase 1
[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT Invitation For Bid - System Wide AMI and Water Meter Installation – Phase 1

Page 7 ends

REFERENCE #3: PROJECT NO. AND TITLE OF A PREVIOUS PROJECT YOU COMPLETED.

Pass
RFP No. 3749 - Water Meter & Metering Infrastructure (AMI) Installation REFERENCE #3: NAME THE CLASS AND TYPE OF WORK FOR THE COMPLETED PROJECT.

Pass
PWS was selected to complete AMI retrofits and meter replacements across approximately 4,000 service locations. Our scope included meter installation, programming of Sensus FlexNet MXUs, exchange of AMR registers, and replacement of damaged lids.

REFERENCE #3: NAME, ADDRESS AND PHONE NO. OF THE OWNER OF THE COMPLETED PROJECT.

Pass
Eastern Municipal Water District, 2270 Trumble Rd, Perris, CA 92570, (951) 928-3777. Contact: Myrna Vazquez, Senior Buyer, ext. 4521.

REFERENCE #3: WHO WAS THE REGISTERED ENGINEER IN CHARGE OF THE COMPLETED PROJECT? Pass
Rafael Ojeda, Meter Services Manager, Eastern Municipal Water District.

REFERENCE #3: LIST THE TOTAL CONTRACT AMOUNT OF THE COMPLETED PROJECT AND THE AMOUNT OF THE CONTRACT YOU PERFORMED.

Pass
Total Contract Amount: $355,200.00; Amount Performed by PWS: $355,200.00.

REFERENCE #3: NAME OF PRIME CONTRACTOR (IF YOU WERE SUB) Pass
N/A - PWS was prime contractor.

Contract Packet - 32 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 452 of 616 ends

[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT CIFB-E DBE No. CP 25-057
System Wide AMI and Water Meter Installation – Phase 1
[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT Invitation For Bid - System Wide AMI and Water Meter Installation – Phase 1

Page 8 ends

REFERENCE #3: DATE OF PROJECT COMPLETION
Pass
06/2025.

REFERENCE #3: LIST ANY LIQUIDATED DAMAGES THAT WERE ASSESSED.

Pass
None.

REFERENCE #4: PROJECT NO. AND TITLE OF A PREVIOUS PROJECT YOU COMPLETED.

Project No. PW 25-004 / Plan No. 3058 - Water Meter Replacement Project - Phase 1 REFERENCE #4: NAME THE CLASS AND TYPE OF WORK FOR THE COMPLETED PROJECT.

Replacement and disposal of 1,485 existing water meters, installation of 1” Badger ultrasonic meters and Orion radio-read endpoints, replacement of meter box lids, endpoint verification, GPS and photo documentation.

REFERENCE #4: NAME, ADDRESS AND PHONE NO. OF THE OWNER OF THE COMPLETED PROJECT.

City of Coalinga, 155 W Durian Ave, Coalinga, CA 93210, (559) 935-1533. Project administered through Tri City Engineering, 4630 W Jennifer Ave, Suite 101, Fresno, CA 93722.

REFERENCE #4: WHO WAS THE REGISTERED ENGINEER IN CHARGE OF THE COMPLETED PROJECT? Tri City Engineering, Inc. (City Engineer).

REFERENCE #4: LIST THE TOTAL CONTRACT AMOUNT OF THE COMPLETED PROJECT AND THE AMOUNT OF THE CONTRACT YOU PERFORMED.

Total Contract Amount: $301,275.80; Amount Performed by PWS: $301,275.80.

REFERENCE #4: NAME OF PRIME CONTRACTOR (IF YOU WERE SUB) Contract Packet - 33 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 453 of 616 ends

[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT CIFB-E DBE No. CP 25-057
System Wide AMI and Water Meter Installation – Phase 1
[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT Invitation For Bid - System Wide AMI and Water Meter Installation – Phase 1

Page 9 ends

N/A - PWS was prime contractor.

REFERENCE #4: DATE OF PROJECT COMPLETION
06/2025 (45 day Phase 1 installation schedule).

REFERENCE #4: LIST ANY LIQUIDATED DAMAGES THAT WERE ASSESSED.

None.

6. BOND INFORMATION
You can enter your Bid Bond information in the Surety2000 question below.

OR
You may also submit hard copy original bonds by mail or hand delivery prior to the bid due date and time to the following address:

City of Turlock Engineering Division
156 S. Broadway Suite 150
Turlock, CA 95380
DO YOU WANT TO USE SURETY2000 TO SUBMIT YOUR BONDING INFORMATION?* Pass
If you choose to upload bond forms not using Surety2000, you will need to submit the hard copy originals, prior to the bid due date and time, to engineering at:

City of Turlock Engineering Division
156 S. Broadway Suite 150
Turlock, CA 95380
Yes
BIDDER'S BOND - SURETY2000*
Contract Packet - 34 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 454 of 616 ends

[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT CIFB-E DBE No. CP 25-057
System Wide AMI and Water Meter Installation – Phase 1
[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT Invitation For Bid - System Wide AMI and Water Meter Installation – Phase 1

Page 10 ends

Pass
Please enter your Bid Bond information from Surety2000 below.

Bond ID: SCA0622840058
Vendor ID: 821333768

7. OTHER DOCUMENTS AND CERTIFICATIONS
SUBCONTRACTORS*
Pass
Please download the below documents, complete, and upload. • SUBCONTRACTORS.Update.pdf
SUBCONTRACTORS-Ensure_Utility_.pdf
IRAN CONTRACTING ACT CERTIFICATION*
Pass
As required by California Public Contract Code Section 2204, the Contractor certifies subject to penalty for perjury that the option checked below relating to the Contractor's status in regard to the Iran Contracting Act of 2010 (Public Contract Code Section 2200 et seq.) is true and correct:

Note: In accordance with Public Contract Code Section 2205, false certification of this form shall be reported to the California Attorney General and may result in civil penalties equal to the greater of $250,000 or twice the Contract amount, termination of the Contract and/or ineligibility to bid on contracts for three years.

The Contractor is not: (i) identified on the current list of persons and entities engaging in investment activities in Iran prepared by the California Department of General Services in accordance with subdivision (b) of Public Contract Code Section 2203; or (ii) a financial institution that extends, for 45 days or more, credit in the amount of $20,000,000 or more to any other person or entity identified on Contract Packet - 35 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 455 of 616 ends

[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT CIFB-E DBE No. CP 25-057
System Wide AMI and Water Meter Installation – Phase 1
[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT Invitation For Bid - System Wide AMI and Water Meter Installation – Phase 1

Page 11 ends

the current list of persons and entities engaging in investment activities in Iran prepared by the California Department of General Services in accordance with subdivision (b) of Public Contract Code Section 2203, if that person or entity uses or will use the credit to provide goods or services in the energy sector in Iran.

PRICE TABLES

BASE BID
Line Item Description Quantity Unit of
Measure
Unit Cost Total
1 Mobilization & Demobilization 1 L.S. $73,348.00 $73,348.00 2 Prepare and Maintain Pedestrian and Traffic Control Plan(s) 1 L.S. $10,000.00 $10,000.00 3 Allowance for Potholing 1 Allow $35,000.00 $35,000.00 4 Replace 3/4" Water Meter and Endpoint 842 EA. $90.35 $76,074.70 5 Replace 1" Water Meter and Endpoint 3,351 EA. $90.60 $303,600.60 6 Replace 1 1/2" Water Meter and Endpoint 100 EA. $152.20 $15,220.00 7 Install Private 3/4" Brass Ball Valve on Downstream Side of Meter 450 EA. $222.05 $99,922.50 8 Install Private 1" Brass Ball Valve on Downstream Side of Meter 1,200 EA. $276.95 $332,340.00 9 Install Private 1 1/2" Brass Ball Valve on Downstream Side of Meter 40 EA. $467.00 $18,680.00 10 Replace B16 Meter Box 250 EA. $128.40 $32,100.00
11 Replace B30 Meter Box 50 EA. $230.00 $11,500.00
Contract Packet - 36 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 456 of 616 ends

[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT CIFB-E DBE No. CP 25-057
System Wide AMI and Water Meter Installation – Phase 1
[ENSURE UTILITY INC DBA PHOENIX WATER SOLUTIONS] RESPONSE DOCUMENT REPORT Invitation For Bid - System Wide AMI and Water Meter Installation – Phase 1

Page 12 ends

Line Item Description Quantity Unit of
Measure
Unit Cost Total
12 Replace FL16D Meter Box Lid 3,480 EA. $110.55 $384,714.00 13 Replace FL30D Meter Box Lid 83 EA. $130.00 $10,790.00 14 Allowance for Minor Concrete 1 Allow $70,000.00 $70,000.00 15 Alowance for Irrigation and Landscaping Repairs 1 Allow $50,000.00 $50,000.00 16 Allowance for Unknown Utilities 1 Allow $25,000.00 $25,000.00 17 Work Not Included in Other Bid Items 1 L.S. $55,000.20 $55,000.20 TOTAL $1,603,290.00
Contract Packet - 37 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 457 of 616 ends

Ensure Utility Inc dba Phoenix Water Solutions Response (Draft)

CONTACT INFORMATION

ADDENDA CONFIRMATION
 Addendum #1
Confirmed Jun 21, 2026 7:02 PM by Luke Sharman
 Addendum #2
Confirmed Jun 21, 2026 7:02 PM by Luke Sharman

QUESTIONNAIRE

1. Proposal*
Bids are to be submitted for the entire work. The amount of the bid for comparison purposes will be the total of all items. The bidder shall set forth for each unit basis item of work a unit price and a total for the item, and for each lump sum item a total for the item.

In accordance with the annexed Notice to Contractors, the undersigned, as bidder, declares that he has carefully examined the location of the proposed work, the plans, specifications and technical requirements therefore, and the proposed forms of contract and bonds mentioned or referred to in said Notice and on file in the Office of the City Company
Ensure Utility Inc dba Phoenix Water Solutions No Reviews Email
[email protected]
Contact
Luke Sharman
Address
8222 S 48th St
Suite 180
Phoenix, AZ 85044
Phone
(602) 445-3912
Website
phoenixwatersolutions.com
Submission Date
N/A
6/22/26, 9:32 AM Ensure Utility Inc dba Phoenix Water Solutions Response (Draft) https://procurement.opengov.com/vendors/167918/proposals/530914/edit?section=questionnaire 1/6 Contract Packet - 38 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 458 of 616 ends

Engineer of the City of Turlock, together with the prevailing rate of per diem wages for each craft or type of workmen needed to execute said contract; and he proposes and agrees that if this proposal is accepted, he will furnish all labor, materials, equipment, plant transportation, service, sales taxes, permit fees and other costs necessary to complete the construction in strict conformity to the plans and specifications and he will enter into a written contract with the City of Turlock in the form of contract on file in the Office of the City Engineer for such purposes, and that he will execute and/or provide all bonds and insurance certificates required by law and/or by said contract and/or mentioned in said Notice to Contractors all in accordance with and subject to all applicable laws, and that he will take in full payment therefore the unit prices entered on the Bidder's Form.  Confirmed

2. Request for Substitutions*
You may upload information relative to material or equipment for which you would like to request approval of that were not specifically named in the project specifications. City staff will make an effort to respond to requests for substitution as part of the Q&A and addendum process, though will not be obligated to comment on, approve, or deny any request for substitution.
 Confirmed

3. Affidavit*
Please download the below documents, complete, and upload.  AFFIDAVIT.pdf
No response submitted

4. INFORMATION REQUIRED OF BIDDER

4.1. Number of years’ experience as a contractor in construction work or installation work similar to that required in these specifications.*
10 4.2. Name of person who inspected the site of the proposed work for your firm.* Bryce Crawford

4.3. Date of Inspection*
06/12/2026

5. PREVIOUS WORK/REFERENCES
Please provide information for four (4) recent projects. If bidder is unable to provide information for four (4) reference projects, it shall provide as many reference projects that it can and City will make a determination as to bidder responsibility based on the available information.

5.1. Reference #1: Project No. and Title of a previous project you completed.* Contract CS-2025-0107 - AMI Water Meter Installation and Service Line Investigation Project

5.2. Reference #1: Name the Class and Type of Work for the completed project.* 6/22/26, 9:32 AM Ensure Utility Inc dba Phoenix Water Solutions Response (Draft) https://procurement.opengov.com/vendors/167918/proposals/530914/edit?section=questionnaire 2/6 Contract Packet - 39 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 459 of 616 ends

PWS was contracted by the City of Globe to complete their AMI Water Meter Installation and Service Line Investigation Project. The work included replacement of 3,500 water meters ranging from ¾-inch to 6-inch, along with comprehensive verification of customer-side and utility-side service line materials in accordance with ADEQ requirements. Additional scopes of work included excavation and replacement of meter boxes where needed, installation of new curb stops & angle stops, leak repairs, precise GPS documentation, and integration of all collected field data into the City’s utility system.

5.3. Reference #1: Name, Address and Phone No. of the Owner of the completed project.* City of Globe, 150 N Pine St, Globe, AZ 85501, (928) 425-7146.

5.4. Reference #1: Who was the Registered Engineer in charge of the completed project?* Travis Ashbaugh, Assistant Public Works Director, City of Globe.

5.5. Reference #1: List the Total Contract Amount of the completed project and the amount of the contract you performed.*
Total Contract Amount: $972,022.30; Amount Performed by PWS: $972,022.30.

5.6. Reference #1: Name of Prime Contractor (if you were Sub) N/A - PWS was prime contractor.

5.7. Reference #1: Date of Project Completion
02/2026

5.8. Reference #1: List any Liquidated Damages that were assessed.

None.

5.9. Reference #2: Project No. and Title of a previous project you completed.

Contract No. 25-0006 - Meter Reading, Register and Endpoint Installation Services

5.10. Reference #2: Name the Class and Type of Work for the completed project.

AMI register & endpoint retrofits on 6,100 Badger meters. Dual monthly manual reads completed alongside AMI rollout; 1,115 lid and endpoint installations; endpoint replacements; AMR-to-AMI conversions across San Juan Capistrano, Dana Point, and Laguna Beach.

5.11. Reference #2: Name, Address and Phone No. of the Owner of the completed project.

South Coast Water District, 31592 West Street, Laguna Beach, CA 92651, (949) 499-4555. Contact: Sander Huang.

5.12. Reference #2: Who was the Registered Engineer in charge of the completed project? Marc Serna, Assistant General Manager/Chief Engineer, South Coast Water District.

5.13. Reference #2: List the Total Contract Amount of the completed project and the amount of the contract you performed.

Total Contract Amount: $279,711.00; Amount Performed by PWS: $279,711.00.

5.14. Reference #2: Name of Prime Contractor (if you were Sub) N/A - PWS was prime contractor.
6/22/26, 9:32 AM Ensure Utility Inc dba Phoenix Water Solutions Response (Draft) https://procurement.opengov.com/vendors/167918/proposals/530914/edit?section=questionnaire 3/6 Contract Packet - 40 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 460 of 616 ends

5.15. Reference #2: Date of Project Completion
03/2025.

5.16. Reference #2: List any Liquidated Damages that were assessed.

None.

5.17. Reference #3: Project No. and Title of a previous project you completed.

RFP No. 3749 - Water Meter & Metering Infrastructure (AMI) Installation

5.18. Reference #3: Name the Class and Type of Work for the completed project.

PWS was selected to complete AMI retrofits and meter replacements across approximately 4,000 service locations.

Our scope included meter installation, programming of Sensus FlexNet MXUs, exchange of AMR registers, and replacement of damaged lids.

5.19. Reference #3: Name, Address and Phone No. of the Owner of the completed project.

Eastern Municipal Water District, 2270 Trumble Rd, Perris, CA 92570, (951) 928-3777. Contact: Myrna Vazquez, Senior Buyer, ext. 4521.

5.20. Reference #3: Who was the Registered Engineer in charge of the completed project? Rafael Ojeda, Meter Services Manager, Eastern Municipal Water District.

5.21. Reference #3: List the Total Contract Amount of the completed project and the amount of the contract you performed.

Total Contract Amount: $355,200.00; Amount Performed by PWS: $355,200.00.

5.22. Reference #3: Name of Prime Contractor (if you were Sub) N/A - PWS was prime contractor.

5.23. Reference #3: Date of Project Completion
06/2025.

5.24. Reference #3: List any Liquidated Damages that were assessed.

None.

5.25. Reference #4: Project No. and Title of a previous project you completed.

Project No. PW 25-004 / Plan No. 3058 - Water Meter Replacement Project - Phase 1

5.26. Reference #4: Name the Class and Type of Work for the completed project.

Replacement and disposal of 1,485 existing water meters, installation of 1” Badger ultrasonic meters and Orion radio-read endpoints, replacement of meter box lids, endpoint verification, GPS and photo documentation.

5.27. Reference #4: Name, Address and Phone No. of the Owner of the completed project.

City of Coalinga, 155 W Durian Ave, Coalinga, CA 93210, (559) 935-1533. Project administered through Tri City Engineering, 4630 W Jennifer Ave, Suite 101, Fresno, CA 93722.

5.28. Reference #4: Who was the Registered Engineer in charge of the completed project? 6/22/26, 9:32 AM Ensure Utility Inc dba Phoenix Water Solutions Response (Draft) https://procurement.opengov.com/vendors/167918/proposals/530914/edit?section=questionnaire 4/6 Contract Packet - 41 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 461 of 616 ends

Tri City Engineering, Inc. (City Engineer).

5.29. Reference #4: List the Total Contract Amount of the completed project and the amount of the contract you performed.

Total Contract Amount: $301,275.80; Amount Performed by PWS: $301,275.80.

5.30. Reference #4: Name of Prime Contractor (if you were Sub) N/A - PWS was prime contractor.

5.31. Reference #4: Date of Project Completion
06/2025 (45 day Phase 1 installation schedule).

5.32. Reference #4: List any Liquidated Damages that were assessed.

None.

6. BOND INFORMATION
You can enter your Bid Bond information in the Surety2000 question below.

OR
You may also submit hard copy original bonds by mail or hand delivery prior to the bid due date and time to the following address:

City of Turlock Engineering Division
156 S. Broadway Suite 150
Turlock, CA 95380

6.1. Do you want to use Surety2000 to submit your bonding information?* If you choose to upload bond forms not using Surety2000, you will need to submit the hard copy originals, prior to the bid due date and time, to engineering at:

City of Turlock Engineering Division
156 S. Broadway Suite 150
Turlock, CA 95380
Yes

6.1.2. Bidder's Bond - Surety2000*
Please enter your Bid Bond information from Surety2000 below.

Bond ID: No response submitted
Vendor ID: No response submitted
Unable to verify. Bond information incomplete.

7. OTHER DOCUMENTS AND CERTIFICATIONS

7.1. Subcontractors*
Please download the below documents, complete, and upload.  Verify Bid Bond
6/22/26, 9:32 AM Ensure Utility Inc dba Phoenix Water Solutions Response (Draft) https://procurement.opengov.com/vendors/167918/proposals/530914/edit?section=questionnaire 5/6 Contract Packet - 42 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 462 of 616 ends

 SUBCONTRACTORS.Update.pdf
 SUBCONTRACTORS-Ensure_Utility_.pdf

7.2. Iran Contracting Act Certification*
As required by California Public Contract Code Section 2204, the Contractor certifies subject to penalty for perjury that the option checked below relating to the Contractor's status in regard to the Iran Contracting Act of 2010 (Public Contract Code Section 2200 et seq.) is true and correct:

Note: In accordance with Public Contract Code Section 2205, false certification of this form shall be reported to the California Attorney General and may result in civil penalties equal to the greater of $250,000 or twice the Contract amount, termination of the Contract and/or ineligibility to bid on contracts for three years.

The Contractor is not: (i) identified on the current list of persons and entities engaging in investment activities in Iran prepared by the California Department of General Services in accordance with subdivision (b) of Public Contract Code Section 2203; or (ii) a financial institution that extends, for 45 days or more, credit in the amount of $20,000,000 or more to any other person or entity identified on the current list of persons and entities engaging in investment activities in Iran prepared by the California Department of General Services in accordance with subdivision (b) of Public Contract Code Section 2203, if that person or entity uses or will use the credit to provide goods or services in the energy sector in Iran.

PRICE TABLES 
 Pricing information has not been unsealed yet
6/22/26, 9:32 AM Ensure Utility Inc dba Phoenix Water Solutions Response (Draft) https://procurement.opengov.com/vendors/167918/proposals/530914/edit?section=questionnaire 6/6 Contract Packet - 43 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 463 of 616 ends

AFFIDAVIT
The undersigned bidder, being first duly sworn, deposes and says that he/she are the party making the foregoing proposal or bid, that this bid is genuine and not collusive or sham, that said bidder has not colluded, conspired, connived or agreed, directly or indirectly, with any other person or bidder, to put in a sham bid, or that said other person shall refrain from bidding, and has not in any manner sought by collusion to secure any advantage against the said City or any person interested in said improvement, for him/herself or any other person.

X
Signature of Bidder
Jurat (Government Code Section 8202)
State of California
County of
Subscribed and sworn to (or affirmed) before me on this day of , 20 by proved to me on the basis of satisfactory evidence to be the person(s) who appeared before me.
(AFFIX SEAL)

NOTARY PUBLIC SIGNATURE

NOTARY PUBLIC PRINTED NAME
Contract Packet - 44 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 464 of 616 ends

SUBCONTRACTORS
Prime Contractor:___________________________________________ DIR NUMBER:_______________ Pursuant to California Public Contract Code §4100, the Bidder shall list each subcontractor who will perform Work or Labor or who will render service to the Prime Contractor in or about the construction of the Work or Improvement, or a subcontractor duly licensed who, under subcontract to the Prime Contractor, specially fabricates and installs a portion of the Work or Improvement according to detailed Drawings contained in the Contract Documents, in an amount in excess of 1/2 of 1 percent of the Prime Contractor's Total Bid or, in the case of Bids or Offers for the construction of streets or highways, including bridges, in excess of 1/2 of 1 percent of the Prime Contractor's total Bid or $10,000 whichever is greater. After the opening of Bids, no changes or substitutions will be allowed except as otherwise provided by law. The listing of more than one subcontractor for each item of Work to be performed with the words "and/or" will not be permitted.

IF NO SUBCONTRACTORS WILL FURNISH WORK, THEN WRITE "NONE" BELOW IN THE SPACE PROVIDED.

NAME LICENSE NUMBER DIR NUMBER ADDRESS WORK ITEMS TO BE PERFORMED AND % OF ITEM
__________________________________________________________________________________________________________ __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ Contract Packet - 45 of 59 Ensure Utility Inc dba Phoenix Water Solutions 2000004378 None Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 465 of 616 ends

Exhibit B

EXHIBIT B PAYMENT BY FORCE ACCOUNT
Contract Packet - 46 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 466 of 616 ends

1 EXHIBIT B

PAYMENT BY FORCE ACCOUNT
For work paid by force account, the City Engineer compares City’s records to Contractor’s daily force account work report. When the City Engineer and Contractor agree on the contents of the daily force account work reports, the City Engineer accepts the report and City pays for the work.

If the records differ, City pays for the work based only on the information shown on City’s records.

If a subcontractor performs work at force account, work paid at force account will be accepted at an additional 2 percent (2%) markup to the total cost of that work, including markups, as reimbursement for additional administrative costs. The markups specified in labor, materials, and equipment includes compensation for all delay costs, overhead costs, and profit. If an item's unit price is adjusted for work-character changes, City excludes Contractor’s cost of determining the adjustment. Payment for owner-operated labor and equipment is made at the market-priced invoice submitted.

A. Labor. Labor payment is full compensation for the cost of labor used in the direct performance of the work plus a fifteen percent (15%) markup, as set forth below, and consistent with California Labor Code section 1770 et seq. Force account labor payment consists of:

1. Employer payment to the worker for:

1.1 Basic hourly wage

1.2 Health and welfare

1.3 Pension

1.4 Vacation

1.5 Training

1.6 Other State and federal recognized fringe benefit payments

2. Labor surcharge percentage in Labor Surcharge and Equipment Rental Rates current during the work paid at force account for:

2.1 Workers' compensation insurance

2.2 Social security

2.3 Medicare

2.4 Federal unemployment insurance

2.5 State unemployment insurance

2.6 State training taxes

3. Subsistence and travel allowances paid to the workers

4. Employer payment to supervisors, if authorized
The fifteen percent (15%) markup consists of payment for all overhead costs related to labor but not designated as costs of labor used in the direct performance of the work including:
(a) Home office overhead
Contract Packet - 47 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 467 of 616 ends

2 (b) Field office overhead
(c) Bond costs
(d) Profit
(e) Labor liability insurance
(f) Other fixed or administrative costs that are not costs of labor used in the direct performance of the work
B. Materials. Material payment is full compensation for materials the Contractor furnishes and uses in the work. The City Engineer determines the cost based on the material purchase price, including delivery charges, except:

1. A fifteen percent (15%) markup is added;

2. Supplier discounts are subtracted whether the Contractor takes them or not;

3. If the City Engineer believes the material purchase prices are excessive, City pays the lowest current wholesale price for a similar material quantity;

4. If Contractor procured the materials from a source Contractor wholly or partially own, the determined cost is based on the lower of the:

4.1 Price paid by the purchaser for similar materials from that source on Contract items; and

4.2 Current wholesale price for those materials;
5 If Contractor does not submit a material cost record within thirty (30) days of billing, the determined cost is based on the lowest wholesale price:

1.1 During that period

1.2 In the quantities used
C. Equipment Rental. Equipment rental payment is full compensation for:

1. Rental equipment costs, including moving rental equipment to and from the change order work site using its own power.

2. Transport equipment costs for rental equipment that cannot be transported economically using its own power. No payment is made during transport for the transported equipment.

3. Fifteen percent (15%) percent markup.

If Contractor wants to return the equipment to a location other than its original location, the payment to move the equipment must not exceed the cost of returning the equipment to its original location. If Contractor uses the equipment for work other than work paid by force account, the transportation cost is included in the other work.

Contract Packet - 48 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 468 of 616 ends

3 Before moving or loading the equipment, Contractor must obtain authorization for the equipment rental's original location.

The City Engineer determines rental costs:

1. Using rates in Labor Surcharge and Equipment Rental Rates:

1.1. By classifying equipment using manufacturer's ratings and manufacturerapproved changes.

1.2. Current during the work paid by force account.

1.3. Regardless of equipment ownership but City uses the rental document rates or minimum rental cost terms if:

1.3.1. Rented from equipment business Contractor does not own.

1.3.2. The Labor Surcharge and Equipment Rental Rates hourly rate is $10.00 per hour or less.

2. Using rates established by the City Engineer for equipment not listed in Labor Surcharge and Equipment Rental Rates. Contractor may submit cost information that helps the City Engineer establish the rental rate but City uses the rental document rates or minimum rental cost terms if:

2.1. Rented from equipment business Contractor does not own.

2.2. The City Engineer establishes a rate of $10.00 per hour or less.

3. Using rates for transport equipment not exceeding the hourly rates charged by established haulers.

Equipment rental rates include the cost of:

1. Fuel 7. Repairs and maintenance

2. Oil 8. Depreciation

3. Lubrication 9. Storage

4. Supplies 10. Insurance

5. Small tools that are not consumed by use 11. Incidentals

6. Necessary attachments
City pays for small tools consumed by use. The City Engineer determines payment for small tools consumed by use based on Contractor-submitted invoices.

The City Engineer may authorize rates in excess of those in the Labor Surcharge and Equipment Rental Rates if:

1. Contractor submits a request to use rented equipment

2. Equipment is not available from Contractor’s normal sources or from one of Contractor’s subcontractors

3. Rented equipment is from an independent rental company

4. Proposed equipment rental rate is reasonable
Contract Packet - 49 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 469 of 616 ends

4 5. The City Engineer authorizes the equipment source and the rental rate before Contractor uses the equipment
D. Equipment on the Job Site. For equipment on the job site at the time required to perform work paid by force account, the time paid is the time:

1. To move the equipment to the location of work paid by force account plus an equal amount of time to move the equipment to another location on the job site when the work paid by force account is completed

2. To load and unload equipment

3. Equipment is operated to perform work paid by force account and:

3.1. Hourly rates are paid in 1/2-hour increments

3.2. Daily rates are paid in 1/2-day increments
E. Equipment Not on the Job Site Required for Original-Contract Work. For equipment not on the job site at the time required to perform work paid by force account and required for original-Contract work, the time paid is the time the equipment is operated to perform work paid by force account and the time to move the equipment to a location on the job site when the work paid by force account is completed.

The minimum total time paid is:

1. 1 day if daily rates are paid

2. 8 hours if hourly rates are paid
If daily rates are recorded, equipment:

1. Idled is paid as 1/2 day

2. Operated four (4) hours or less is paid as 1/2 day

3. Operated four (4) hours or more is paid as one (1) day If the minimum total time exceeds eight (8) hours and if hourly rates are listed, City rounds up hours operated to the nearest 1/2-hour increment and pays based on the hours shown in the following table. The table does not apply when equipment is not operated due to breakdowns, in which case rental hours are the hours the equipment was operated.

Equipment Rental Hours
Hours
operated
Hours
paid

0.0 4.00

0.5 4.25

1.0 4.50

1.5 4.75

2.0 5.00

2.5 5.25
Contract Packet - 50 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 470 of 616 ends

5 3.0 5.50

3.5 5.75

4.0 6.00

4.5 6.25

5.0 6.50

5.5 6.75

6.0 7.00

6.5 7.25

7.0 7.5

7.5 7.75
≥8.0 hours
used
F. Equipment Not on the Job Site Not Required for Original-Contract Work. For equipment not on the job site at the time required to perform work paid by force account and not required for original-Contract work, the time paid is the time:

1. To move the equipment to the location of work paid by force account plus an equal amount of time to return the equipment to its source when the work paid by force account is completed

2. To load and unload equipment

3. Equipment is operated to perform work paid by force account G. Non-Owner-Operated Dump Truck Rental. Contractor shall submit the rental rate for non-owner-operated dump truck rental to City. The City Engineer shall determine the payment rate. Payment for non-owner-operated dump truck rental is for the cost of renting a dump truck, including its driver. For the purpose of markup payment only, the non-owner-operated dump truck is rental equipment and the owner is a subcontractor.

The above markups shall constitute full compensation for all home office overhead, field office overhead, bond costs, profit, labor liability insurance, and other fixed or administrative costs that are not costs specifically designated as cost or equipment rental as stated above. The total payment made as provided above shall be deemed to be the actual cost of the work and shall constitute full compensation therefor.

When extra work to be paid for on a force account basis is performed by a subcontractor, an additional markup of 2 percent (2%) will be added to the total cost of that extra work including all markups specified in this Section. The additional 2 percent (2%) markup shall reimburse Contractor for additional administrative costs, and no other additional payment will be made by reason of performance of the extra work by a subcontractor.

Contract Packet - 51 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 471 of 616 ends

Exhibit C
EXHIBIT C WORKERS’ COMPENSATION INSURANCE

CERTIFICATION
Contract Packet - 52 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 472 of 616 ends

1 EXHIBIT C
WORKERS’ COMPENSATION INSURANCE CERTIFICATION
Pursuant to Section 18(b) of the Agreement, Contractor certifies as follows:

I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for worker’s compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.

Signed: Date:
(Typed or Printed Name)
Business Address (Street Address, City, State & Zip Code):

Business Phone: ( )
Contract Packet - 53 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 473 of 616 ends

Exhibit D
EXHIBIT_D_PERFORMANCE_BOND
Contract Packet - 54 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 474 of 616 ends

1 EXHIBIT D

PERFORMANCE BOND
[Signatures on Following Page]
KNOW ALL MEN BY THESE PRESENTS:

WHEREAS, the City of Turlock, State of California, has awarded to Ensure Utiity Inc dba Phoenix Water Solutions, hereinafter designated as the “Principal,” a contract for Project No. 25-057, “System Wide AMI and Water Meter Installation Phase 1”; and,
WHEREAS, said Principal is required under the terms of said contract to furnish a bond for the faithful performance of said contract.

NOW, THEREFORE, we the Principal, and as Surety, are
held and firmly bound unto the City of Turlock in the penal sum of _____________________________________ ($_____________), lawful money of the United States for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors, or assigns jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH, that if the above bounden Principal, or Principal’s heirs, executors, administrators, successors, or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions, and agreements in said contract and any alteration thereof made as therein provided, on the Principal’s part, to be kept and performed at the time and in the manner therein specified and in all respects according to their true intent and meaning; and shall defend, indemnify and save harmless the City of Turlock, its officers and agents as therein stipulated, then this obligation shall become null and void; otherwise it shall be and remain in full force and virtue.

And the Surety, for value received hereby stipulates and agrees that, in accordance with the Plans, Standard Specifications, Special Provisions, and other contract documents, no change, extension of time, alteration, or addition to the terms of the contract, or to the work to be performed hereunder, or to the specifications accompanying the same shall in anywise affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration of additions to the terms of the Contract to the work, or to the specifications.

The City of Turlock reserves the right to refuse use of any Contractor assigned by any surety to complete the work.

Contract Packet - 55 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 475 of 616 ends

2 IN WITNESS WHEREOF, the above-bound parties have executed this instrument under their seals this __________ day of _______________, 20__, the name and corporate seals of each corporate party being hereto affixed and these presents duly signed by its undersigned representative, pursuant to authority of its governing body. (Corporate Seal) Principal
By
Title
(Attach Notarial Acknowledgment)
(Corporate Seal) Surety
Address
Phone No.: ( ) Fax No.: ( )
By
Attorneys-in-Fact
Title
(Attach Notarial Acknowledgment)
NOTE TO SURETY COMPANY: There must be submitted a certified copy of unrevoked resolution of authority for the attorneys-in-fact.
(Seal) Witness
Approved as to form:

Risk Manager
Contract Packet - 56 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 476 of 616 ends

Exhibit E
EXHIBIT_E_PAYMENT_BOND
Contract Packet - 57 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 477 of 616 ends

1 EXHIBIT E

PAYMENT BOND
[Signatures on Following Page]
KNOW ALL MEN BY THESE PRESENTS:

WHEREAS, the City of Turlock, a municipal corporation, has awarded to Ensure Utility day Phoenix Water Solutions, hereinafter designated as the “Principal”, a contract for Project No. 25-057, “System Wide AMI and Water Meter Installation - Phase 1”; and
WHEREAS, said Principal is required to furnish a bond in connection with said contract, to secure payment of claims of laborers, mechanics, or materialmen employed on work under said contract, as provided by law.

NOW, THEREFORE, we the undersigned Principal and Surety are held and firmly bound unto the City of Turlock in the sum of ____________________________________________ ($_________), said sum being equal to the estimated amount payable by said City of Turlock under the terms of the contract, for which payment well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors, or assigns jointly and severally, firmly by these presents.

THE CONDITIONS OF THIS OBLIGATION ARE SUCH that if said Principal, or Principal’s heirs, executors, administrators, successors, or assigns, or subcontractors shall fail to pay for any material, provisions, provender, or other supplies, implements, or machinery used in, upon, for or about the performance of the work contracted to be done, or for any work or labor thereon of any kind, or for amounts due under the Unemployment Insurance Code with respect to such work or labor, or for any amounts required to be deducted, withheld, and paid over to the Franchise Tax Board from these wages of employees of the Contractor and Contractor’s subcontractors pursuant to the Revenue and Taxation Code, with respect to such work and labor, the Surety or Sureties hereon will pay for the same in an amount not exceeding the sum specified in this bond, otherwise the above obligation shall be void. In case suit is brought upon this bond, said Surety will pay a reasonable attorney’s fee to be fixed by the court.

This bond shall inure to the benefit of any and all persons, companies, and corporations entitled to file claims under Section 3138 of the Civil Code of the State of California so as to give a right of action to them or their assigns in any suit brought upon this bond.

Said Surety, for value received, hereby stipulates and agrees that, in accordance with the Plans, Standard Specifications, Special Provisions, and other Contract Documents, no change, extension of time, alteration or addition to the terms of the contract, or to the work to be performed there under, or to the specifications accompanying the same, shall in anywise affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract, or to the work, or to the specifications.

Contract Packet - 58 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 478 of 616 ends

2 IN WITNESS WHEREOF, the above-bound parties have executed this instrument under their seals this ___________ day of ________________, 20__, the name and corporate seals of each corporate party being hereto affixed and these presents duly signed by its undersigned representative, pursuant to authority of its governing body. (Corporate Seal) Principal
By
Title
(Attach Notarial Acknowledgment)
(Corporate Seal) Surety
Address
Phone No.: ( ) Fax No.: ( )
By
Attorneys-in-Fact
Title
(Attach Notarial Acknowledgment)
NOTE TO SURETY COMPANY: There must be submitted a certified copy of unrevoked resolution of authority for the attorneys-in-fact.
(Seal) Witness
Approved as to form:

Risk Manager
Contract Packet - 59 of 59
Docusign Envelope ID: 20C42002-BB6E-88C4-81EB-EAFA1F3C92D3

Page 479 of 616 ends

CITY CONTRACT NO. 2027-049 1

AGREEMENT BETWEEN THE CITY OF TURLOCK
and
Willdan Engineering
for

PROFESSIONAL SERVICES
City Contract No. 2027-049
City Project No. 25-057
THIS PROFESSIONAL SERVICES AGREEMENT (the “Agreement”) is entered into by and between the City of Turlock, a California municipal corporation (“City”), and Willdan Engineering, a California corporation (“Professional”), on Tuesday, July 14, 2026 (the “Effective Date”). City and Professional may be collectively referred to herein as the “Parties” or individually as “Party.” There are no other parties to this Agreement.

RECITALS
A. City seeks to hire an independent contractor to perform professional services to assist City with the Construction Management Services for System Wide AMI and Water Meter Installation - Phase 1 Project (the “Project”).

B. Professional has made a proposal to City to provide such professional services. A description of the services Professional proposes to provide is included in the Scope of Services in Exhibit A attached hereto and incorporated herein by reference (“Services”). City desires to retain Professional to perform the Services, subject to the terms and conditions set forth in this Agreement.

C. The Parties have outlined the schedule or timeline for providing the Services (“Completion Schedule”), which shall be included in the Scope of Services in Exhibit A.

D. The Parties have outlined the rates and method of payment to Professional for its performance of the Services under this Agreement (“Compensation Schedule”), which shall be included in the Scope of Services in Exhibit A.

NOW, THEREFORE, in consideration of the promises and covenants set forth below, the Parties agree as follows:

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 480 of 616 ends

CITY CONTRACT NO. 2027-049 2

AGREEMENT

1. RECITALS:

The recitals set forth above (“Recitals”) are true and correct and are hereby incorporated into and made part of this Agreement by this reference. In the event of any inconsistency between the Recitals and Sections 1 through 53 of this Agreement, the Sections 1 through 53 shall prevail.

2. TERM:

The term of this Agreement shall be one (1) year and will commence on the Effective Date and terminate on Wednesday, July 14, 2027 (“Term”) unless the Parties mutually agree in writing to terminate the Agreement earlier or extend the Term pursuant to this Agreement.

3. EXTENSION OF AGREEMENT:
{Intentionally Omitted}

4. EFFECTIVE DATE:

This Agreement shall only become effective once all of the Parties have executed the Agreement (the “Effective Date”).

5. WORK:

5.1. SERVICES:

Subject to the terms and conditions set forth in this Agreement, Professional shall provide City the Services described in Exhibit A. Any request for Services not included in Exhibit A will be considered a request for additional or modified Services (“Modification” or “Modifications”). Professional shall not receive additional compensation for any Modification of the Services unless the Parties agree otherwise in a writing executed by both Parties.

5.2. CITY REQUESTED MODIFICATION OF SERVICES:

City may, by written order, authorize Modifications to the Services described in Exhibit A. If such Modifications cause an increase in the cost or time required for performance of Professional’s Services, the Parties shall enter into a written amendment to this Agreement to adjust the Services and the compensation to be paid to Professional and, if necessary, amend the Completion Schedule or Compensation Schedule. The Services, Completion Schedule, or Compensation Schedule shall not be revised unless City and Professional mutually agree to a written amendment to this Agreement reflecting such revisions, additional compensation, time for performance or such other terms or conditions mutually agreed upon by the Parties.

5.3. PROFESSIONAL REQUESTED MODIFICATION IN SERVICES:

Professional shall not be compensated for work outside the Services described in this Agreement, unless, prior to the commencement of the Services:

A. Professional provides City with written notice that specific work requested by City or required to complete the Project is outside the agreed upon Services. Such notice shall: (1) be supported by substantial evidence that the work is outside the Services; (2) set forth the Professional’s proposed course of action for completing the work and a specific request for City to approve the Modification to the Services; (3) set Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 481 of 616 ends

CITY CONTRACT NO. 2027-049 3
forth the Professional’s proposed revisions, if any, to the Completion Schedule; and (4) set forth the Professional’s proposed revisions, if any, to the Compensation Schedule; and B. City agrees that the work requires a Modification;
C. City approves all adjustments, if any, to the Completion Schedule and Compensation Schedule; and D. The Parties execute a written amendment to this Agreement describing any Modification, together with any adjustment in the Completion Schedule and Compensation Schedule for Professional’s work.

6. COMPENSATION:

6.1. AMOUNT, TIME AND MANNER OF PAYMENT FOR PROFESSIONAL SERVICES:

City shall pay Professional according to the rates and timing set forth in the Compensation Schedule. On each anniversary date of the Effective Date, Professional will be allowed to increase prices with thirty (30) days’ written notice to City. Increases may not exceed increases in the San Francisco-Oakland Consumer Price Index for all urban consumers or percentage increases in Professional’s published prices, whichever is lower. In all cases, City may cancel this Agreement if a requested price increase is not acceptable. City’s total compensation to Professional shall not exceed Three Hundred Seventeen Thousand Seven Hundred Thirteen and No/100ths Dollars($317,713.00) (“Maximum Payment”), unless the Parties mutually agree in writing otherwise.

6.2. DEPOSIT:
{Intentionally Omitted}

6.3. SUBSEQUENT PAYMENTS:

City shall make monthly payments in the amount invoiced by Professional within thirty (30) calendar days of receiving such invoice. In the event that an amount of an invoice is in dispute, City shall inform Professional of the amount and basis for the dispute and may withhold the amount which is in dispute until the dispute has been resolved.

6.4. INVOICES:

Professional shall provide City with monthly invoices sufficiently evidencing Professional’s expenses and completion of the Services. All invoices furnished to City by Professional shall be in a form approved by City.

The payments specified shall be the only payments made to Professional for performance of the Services, including compensation for any Modification. Professional shall submit all billings for Services to City within forty-five (45) days of the performance of such Services. City shall issue payment according to City’s customary procedures and practices for issuing payments to independent contractors.

7. NOTICE TO PROCEED:

Professional shall not commence the performance of the Services until it has been given notice by City (“Notice to Proceed”).

8. TIME OF PERFORMANCE:

Professional warrants that it will commence performance of the Services within ten (10) calendar days of the date the agreement was executed and shall conform to the Completion Schedule. The time of performance is a material term of this Agreement relied on by City in entering into this Agreement.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 482 of 616 ends

CITY CONTRACT NO. 2027-049 4

9. CITY ASSISTANCE TO PROFESSIONAL:

Professional shall, at its sole cost and expense, furnish all facilities, equipment, materials, information, personnel and administrative assistance which may be required to perform its obligations under this Agreement, with the exception of items of City assistance provided in Exhibit B: City Assistance to Professional (“City Assistance to Professional”). City shall furnish to Professional only the facilities, equipment, materials, information, personnel and administrative assistance listed in Exhibit B. Notwithstanding the foregoing, City shall cooperate with Professional and shall not actively interfere with Professional’s performance of Services under this Agreement.

10. TIME AND PERSONNEL DEVOTED TO SERVICES:

Professional shall devote such time and personnel to the performance of this Agreement, as is necessary to perform the Services in compliance with the Completion Schedule, Compensation Schedule, and this Agreement.

11. PERFORMANCE BY QUALIFIED PERSONNEL; NO SUBCONTRACTING:

Services under this Agreement shall be performed only by competent personnel under the supervision and direct employment of Professional. Professional will conform with City’s reasonable requests regarding assignment of personnel, but all personnel, including those assigned at City’s request, shall be supervised by Professional.

Professional is prohibited from subcontracting this Agreement or any part of it unless such subcontracting is expressly approved by City in writing. Neither Party shall, on the basis of this Agreement, contract on behalf of, or in the name of the other Party. An agreement made in violation of this provision shall confer no rights on any Party and shall be null and void.

12. REPRESENTATIONS OF PROFESSIONAL:

City relies upon the following representations by Professional in entering into this Agreement:

12.1. QUALIFICATIONS:

Professional represents that it is qualified to perform the Services provided in Exhibit A and that it possesses the necessary licenses and permits required to perform the Services or will obtain such licenses or permits prior to the time such licenses or permits are required. Professional shall also ensure that all subcontractors are similarly licensed and qualified. Professional and all subcontractors shall also obtain a business license from City before they commence performance of the Services. Professional represents and warrants to City that Professional shall, at Professional's sole cost and expense, keep in effect or obtain at all times during the Term of this Agreement, any licenses, permits, and approvals which are legally required for Professional to practice Professional's profession at the time the Services are rendered.

12.2. PROFESSIONAL PERFORMANCE:

Professional represents that all Services under this Agreement shall be performed in a professional manner and shall conform to the customs and standards of practice observed on similar, successfully completed projects by specialists in the Services to be provided. Professional shall adhere to accepted professional standards as set forth by relevant professional associations and shall perform all Services required under this Agreement in a manner consistent with generally accepted professional customs, procedures and standards for such Services. All work or products completed by Professional shall be completed using the best practices available for the profession.

Professional agrees that, if a Service is not so performed, in addition to all of its obligations under this Agreement and at law, Professional shall re-perform or replace unsatisfactory Service at no additional expense to City.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 483 of 616 ends

CITY CONTRACT NO. 2027-049 5

12.3. NO WAIVER OF CLAIMS:

The granting of any progress payment by City, or the receipt thereof by Professional, or any inspection, review, approval or oral statement by any representative of City, or state certification shall not, in any way, waive, limit, or replace any certification or approval procedures normally required or lessen the liability of Professional to reperform or replace unsatisfactory Service, including, but not limited to, cases where the unsatisfactory character of such Service may not have been apparent or detected at the time of such payment, inspection, review or approval.

12.4. CITY'S REMEDIES ARE CUMULATIVE:

Nothing in this Section shall constitute a waiver or limitation of any right or remedy, whether in equity or at law, which City or Professional may have under this Agreement or any applicable law. All rights and remedies of City, whether under this Agreement or applicable law, shall be cumulative.

12.5. NO CONFLICT OF INTEREST:

Professional represents that no conflict of interest will be created under state or federal law by entering into or in carrying out this Agreement.

13. CONFORMITY WITH LAW AND SAFETY:

Professional shall observe and comply with all applicable laws, ordinances, codes and regulations of governmental agencies, including federal, state, municipal and local governing bodies having jurisdiction over any or all of the scope of Services, including all provisions of the Occupational Safety and Health Act of 1979 as amended, all California Occupational Safety and Health Regulations, the California Building Code, the Americans with Disabilities Act, any copyright, patent, or trademark law, and all other applicable federal, state, municipal and local safety regulations, appropriate trade association safety standards, and appropriate equipment manufacturer instructions. All Services performed by Professional must be in accordance with these laws, ordinances, codes and regulations. Professional’s failure to comply with any laws, ordinances, codes, or regulations applicable to the performance of the Services hereunder shall constitute a breach of contract. In cases where standards conflict, the standard providing the highest degree of protection shall prevail.

If a death, serious personal injury or substantial property damage occurs in connection with the performance of this Agreement, Professional shall immediately notify City's risk manager by telephone. If any accident occurs in connection with this Agreement, Professional shall promptly submit a written report to City, in such form as City may require. This report shall include the following information: (a) name and address of the injured or deceased person(s); (b) name and address of Professional's subcontractor, if any; (c) name and address of Professional's liability insurance carrier; and (d) a detailed description of the accident, including whether any of City's equipment, tools or materials were involved.

If a release of a hazardous material, substance, or waste occurs in connection with the performance of this Agreement, Professional shall immediately notify City. Professional shall not store hazardous materials or hazardous waste within City limits without a proper permit from City.

14. CONTACT BY PROFESSIONAL WITH PROJECT OWNER OR PROJECT APPLICANT:

Unless otherwise set forth in the Services, neither Professional nor Professional's subcontractors shall directly contact the owner of the property involved in the Project or any party who is the applicant for the Project (“Interested Party”), or an employee or contractor of an Interested Party, on any matter relating to the Project Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 484 of 616 ends

CITY CONTRACT NO. 2027-049 6
without the prior consent of the Contract Administrator. In no event shall Professional take any instructions or directions from an Interested Party on any matter pertaining to the Professional's Services to be performed for City under this Agreement.

15. CONFIDENTIALITY:

Professional understands and agrees that, in the performance of Services under this Agreement or in the contemplation thereof, Professional may have access to private or confidential information that may be owned or controlled by City and that such information may contain proprietary or confidential details, the disclosure of which to third parties may be damaging to City (“Confidential Information”).

Professional shall not, either during or after the Term, disclose to any third party any Confidential Information without the prior written consent of City. If City gives Professional written authorization to make any such disclosure, Professional shall do so only within the limits and to the extent of that authorization. Professional may be directed or advised by the City Attorney on various matters relating to the performance of the Services on the Project or on other matters pertaining to the Project and, in such event, Professional agrees that it will treat all communications between itself, its employees and its subcontractors as being communications which are within the attorney-client privilege.

Notwithstanding the foregoing, Professional may disclose Confidential Information required to be disclosed under law, provided that, prior to disclosure, Professional shall first give notice to City and make a reasonable effort to obtain a protective order requiring that City’s Confidential Information not be disclosed. This exception is limited to the extent disclosure is required under law.

16. EXCUSABLE DELAYS; NOTICE TO OTHER PARTY OF DELAY:

Professional shall not be in breach of this Agreement in the event that performance of Services is temporarily interrupted or discontinued due to a “Force Majeure” event which is defined as: riots, wars, sabotage, civil disturbances, insurrections, explosion, natural disasters such as floods, earthquakes, landslides, fires, strikes, lockouts and other labor disturbances or other catastrophic events, which are beyond the reasonable control of Professional. Force Majeure does not include: (a) Professional’s financial inability to perform; (b) Professional’s failure to obtain any necessary permits or licenses from other governmental agencies; or (c) Professional’s failure to obtain the right to use the facilities of any public utility where such failure is due solely to the acts or omissions of the Professional.

17. ASSIGNMENT PROHIBITED:

No Party to this Agreement may assign any right or obligation pursuant to this Agreement. Any attempt or purported assignment of any right or obligation pursuant to this Agreement shall be void and of no effect.

18. SUSPENSION OF SERVICES BY CITY:

City reserves the right to suspend Professional's Services under this Agreement when City determines that it is necessary to do so. When possible, City shall give Professional notice of such suspension and Professional shall, upon receipt of said notice, suspend all Services except any Services, the completion of which is authorized by the notice given by City. If the Services are suspended by City for more than sixty (60) consecutive days, for reasons other than the fault of the Professional, the Professional shall be compensated for Services performed prior to notice of such suspension. When the Project is resumed, the Professional's compensation shall be equitably adjusted by City to provide for expenses incurred by the interruption of the Services. In this regard, Professional shall furnish to City such financial information that, in the judgment of the City Manager, is Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 485 of 616 ends

CITY CONTRACT NO. 2027-049 7
necessary to determine the reasonable value of the Services rendered by Professional during the period when Services were suspended.

If the Parties are unable to agree upon the amount of extra compensation which is due to Professional within thirty (30) days of Professional resuming Services, the amount of such additional compensation, if any, that is required to appropriately compensate the Professional for its expenses incurred by the interruption of Services may, upon the request of either Party, be determined by arbitration conducted in accordance with "ARBITRATION OF DISPUTES" of this Agreement. Such arbitration shall be commenced by the Professional no later than sixty (60) calendar days following the event which entitles the Parties to pursue arbitration unless the Parties agree in writing to an extended time period for commencement of arbitration. Unless otherwise agreed in writing, all Parties shall carry on the Services and perform their duties during any arbitration proceedings, and City shall continue to make payments for the Services in progress as required by this Agreement.

19. OWNERSHIP OF WORK PRODUCT:

Any and all work, artwork, copy, posters, billboards, photographs, videotapes, audiotapes, systems designs, software, reports, designs, specifications, drawings, diagrams, surveys, source codes, professional or technical information or data, photographs, notes, letters, emails or any original works of authorship created by Professional or its subcontractors or subcontractors in connection with Services performed under this Agreement (“Products”) shall be works for hire as defined under Title 17 of the United States Code, and all copyrights in such works are the property of City. In the event it is ever determined that any Product created by Professional or its subcontractors, or subcontractors under this Agreement, are not works for hire under U.S. law, Professional hereby assigns all copyrights to such Products to City. With the prior written approval of City's point of contact for the Project, Professional may retain and use copies of such Products for reference and as documentation of its experience and capabilities.

All Products shall become the property of City irrespective of where located or stored, and Professional agrees to deliver all such documents and information to City, without charge and in whatever form it exists, on the completion of the Professional's Services hereunder. Professional shall have no ownership interest in such Products.

All work product of Professional under this Agreement, including written information which City will cause to be distributed for either internal or public circulation, including both preliminary and final drafts, shall be delivered to City in both printed and electronic form, or as may be specified in Exhibit A.

When this Agreement is terminated, Professional agrees to return to City all documents, drawings, photographs and other written or graphic material, however produced, that it received from City, its contractors or agents, in connection with the performance of its Services under this Agreement. All materials shall be returned in the same condition as received.

20. TERMINATION OF WORK BY CITY FOR ITS CONVENIENCE:

City shall have the right to terminate this Agreement at any time for its convenience by giving notice of such termination to Professional. In the event City shall give such notice of termination, Professional shall cease rendering Services upon receipt of said notice given as required in this Agreement. If City terminates this Agreement:

A. Professional shall deliver copies of all Products prepared by it pursuant to this Agreement.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 486 of 616 ends

CITY CONTRACT NO. 2027-049 8
B. If City terminates this Agreement for convenience before City issues the Notice to Proceed to Professional or before Professional commences any Services hereunder, whichever last occurs, City shall not be obligated to make any payment to Professional. If City terminates this Agreement after City has issued the Notice to Proceed to Professional and after Professional has commenced performance under this Agreement, City shall pay Professional the reasonable value of the Services rendered by Professional pursuant to this Agreement prior to termination of this Agreement. City shall not in any manner be liable for Professional's actual or projected lost profits had Professional completed the Services. Professional shall furnish to City such financial information that, in the judgment of the City Manager, is necessary to determine the reasonable value of the Services rendered by Professional prior to termination. In the event of a dispute as to the reasonable value of the Services rendered by Professional prior to termination and the Parties are unable to agree upon said amount within sixty (60) calendar days following the date of the notice of termination by City, such dispute may, upon the request of either Party, be resolved by arbitration conducted in accordance with "ARBITRATION OF DISPUTES" of this Agreement.

C. Except as provided in this Agreement, in no event shall City be liable for costs incurred by or on behalf of Professional after the date of the notice of termination.

21. ASSURANCE OF PERFORMANCE:

If, at any time, City believes Professional may not be adequately performing its obligations under this Agreement or may fail to complete the Services as required by this Agreement, City may submit a written request to Professional for written assurances of performance and a plan to correct observed deficiencies in Professional's performance. Failure to provide written assurances subsequent to such written request, constitutes grounds to declare a breach under this Agreement.

22. CANCELLATION FOR BREACH BY EITHER PARTY:

Should either Party fail to substantially perform its obligations in accordance with the provisions of this Agreement, the other Party shall thereupon have the right to cancel the Agreement by giving written notice and specifying the effective date of such cancellation. If City cancels this Agreement for breach and it is subsequently determined that Professional did not fail to substantially perform its obligations in accordance with this Agreement, then cancellation for breach by City shall be deemed, and treated, as termination for convenience.

Neither Party waives the right to recover damages against the other for breach of this Agreement, including any amount necessary to compensate City for all detriment proximately caused by Professional's failure to perform its obligations hereunder or which in the ordinary course of things would be likely to result therefrom. City reserves the right to offset such damages against any payments owed to Professional.

City shall not in any manner be liable for Professional's actual or projected lost profits had Professional completed the Services required by this Agreement.

23. NON-DISCRIMINATION:

In its performance of the Services, Professional shall adhere to City’s Equal Employment Opportunity Policy which states, “The City is committed to ensuring that all qualified individuals have a full and fair opportunity to compete in all phase of the hiring process and promotion, and to enjoy the benefits of employment with the City.

All employees and applicants shall receive equal consideration and treatment in employment without regard to race, color, religion, gender, sexual orientation, national origin, age, disability, genetic information, marital status, Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 487 of 616 ends

CITY CONTRACT NO. 2027-049 9
amnesty, or status as a covered veteran in accordance with applicable federal or state statutes, the City’s ordinances, resolutions, rules or regulations.”
In addition, all agreements with sub-contractors will include language as required by the Office of Federal Contract Compliance Programs (OFCCP) that requires sub-contractors to maintain equal employment opportunity policies, and, as necessary, affirmative action policies.

24. ARBITRATION OF DISPUTES:

All claims, disputes, and other matters in question between City and Professional arising out of or relating to this Agreement or the breach thereof, including claims of Professional for extra compensation for Services related to the Project, shall be decided by arbitration before a single arbitrator in accordance with the provisions of Sections 1281 to 1284.2 of the California Code of Civil Procedure (the “Arbitration Laws”) unless the Parties mutually agree otherwise. The provisions of Section 1283.05 of the Arbitration Laws apply to any arbitration proceeding except as otherwise provided in this Agreement. The arbitrator shall have authority to decide all issues between the Parties including, but not limited to, claims for extras, delay and liquidated damages, if any, provided for in this Agreement, matters involving defects in the work product of the Professional, rights to payment, and whether the necessary procedures for arbitration have been followed. The award rendered by the arbitrator shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.

Notice of the demand for arbitration shall be filed in writing with the other Party. The demand for arbitration shall be made within a reasonable time after the claim, dispute, or other matter in question has arisen, and in no event shall it be made after the date when institution of legal or equitable proceedings based on such claim, dispute, or other matter in question would be barred by the applicable statute of limitation.

The Parties shall jointly appoint an arbitrator within fifteen (15) calendar days of the date of giving of the notice of the demand for arbitration. If the Parties are unable to jointly agree upon the appointment of an arbitrator within said fifteen (15) calendar day period, and do not agree in writing to extend said period for a fixed period, then either Party may seek to have the arbitrator appointed by the Superior Court of Stanislaus County in accordance with the Arbitration Laws.

If any proceeding is brought to contest the right to arbitrate and it is determined that such right exists, the losing Party shall pay all costs and attorneys' fees incurred by the prevailing party.

In addition to the other rules of law which may be applicable to any arbitration hereunder, the following shall apply:

A. Promptly upon the filing of the arbitration, each Party shall be required to set forth in writing and to serve upon each other Party a detailed statement of its contentions of fact and law.

B. All parties to the arbitration shall be entitled to the discovery procedures as provided in Section 1283.05 of the California Code of Civil Procedure.

C. The arbitration shall be commenced and conducted as expeditiously as possible consistent with affording reasonable discovery as provided herein.

D. These additional rules shall be implemented and applied by the arbitrator.

The costs of arbitration shall be borne by the Parties as determined by the arbitrator, but each Party shall bear its own attorney's fees associated with the dispute with the other Party and to the arbitration.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 488 of 616 ends

CITY CONTRACT NO. 2027-049 10

25. INSURANCE COVERAGE:

During the Term, the Professional, at its own cost and expense, shall maintain in full force and effect policies of insurance set forth herein, which shall be placed with insurers admitted in California with a current A M Best’s rating of no less than A-:VII and will provide City with written proof of said insurance. Professional shall maintain coverage as follows:

25.1. COMMERCIAL GENERAL LIABILITY:

Professional shall maintain commercial general liability insurance with coverage at least as broad as Insurance Services Office (ISO) form CG 00 01, in the amount of no less than Two Million Dollars ($2,000,000.00) per occurrence, Four Million Dollars ($4,000,000.00) general aggregate, and Two Million Dollars ($2,000,000.00) products and completed operations for bodily injury, personal injury, and property damage. The general aggregate limit shall apply separately to this Project or the general aggregate shall be doubled.

25.2. WORKERS' COMPENSATION INSURANCE AND EMPLOYER'S LIABILITY:

Professional shall maintain workers’ compensation insurance as required by the State of California under the Labor Code. Professional shall also carry employer’s liability insurance in the amount of One Million Dollars ($1,000,000.00) per accident, with a One Million Dollars ($1,000,000.00) policy limit for bodily injury by disease, and a One Million Dollars ($1,000,000.00) limit for each employee’s bodily injury by disease.

25.3. PROFESSIONAL LIABILITY:

Professional shall maintain professional liability insurance that insures against professional errors and omissions that may be made in performing professional services in the amount of no less than Two Million Dollars ($2,000,000.00) per claim and in the aggregate or greater if appropriate for the Professional's profession. Any deductibles or self-insured retentions must be declared to and approved by City. At the option of City, either the insurer shall reduce or eliminate such deductibles or self-insured retentions with respect to City, its elected and appointed councils, commissions, directors, officers, employees, agents, and representatives (“City’s Agents”); or the Professional shall provide a financial guarantee satisfactory to City guaranteeing payment of losses and related investigations, claims administration and defense expenses.

25.4. COMMERCIAL AUTOMOBILE LIABILITY:

Professional shall maintain commercial automobile liability insurance using ISO Business Auto Coverage form CA 00 01 (or equivalent) in the amount of no less than Two Million Dollars ($2,000,000.00) or greater per accident for owned, leased, hired, and non-owned, borrowed automobiles.

25.5. UMBRELLA OR EXCESS POLICY:

Professional may use Umbrella or Excess Policies to provide the liability limits as required in this agreement. This form of insurance will be acceptable provided that all of the Primary and Umbrella or Excess Policies shall provide all of the insurance coverages herein required. The Umbrella or Excess policies shall be provided on a true “following form” or broader coverage basis, with coverage at least as broad as provided on the underlying Commercial General Liability and automobile Liability insurance. No insurance coverage or policies maintained by the City (“Additional Insured”), whether primary or excess, and which also apply to a loss covered hereunder, shall be called upon to contribute to a loss until the Professional’s primary and excess liability policies are exhausted.

25.6. WAIVER OF SUBROGATION:

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 489 of 616 ends

CITY CONTRACT NO. 2027-049 11
With the exception of professional liability, Professional hereby agrees to waive subrogation which any insurer of Professional may acquire from Professional by virtue of the payment of any loss. The commercial general liability policy, automobile liability policy, and workers’ compensation policy shall be endorsed to contain a waiver of subrogation in favor of City for all work performed by Professional, its agents, employees, independent contractors and subcontractors. Professional shall provide written proof of waiver of subrogation in the Certificate of Insurance. Additionally, Professional agrees to obtain any available endorsements that may be necessary to effectuate this waiver of subrogation.

26. ADDITIONAL INSURANCE REQUIREMENTS:

Within five (5) days of the Effective Date, Professional shall provide City with certificates of insurance and amendatory endorsements for all of the policies required under this Agreement (“Certificates and Endorsements”). Such Certificates and Endorsements shall be kept current for the Term of the Agreement and Professional shall be responsible for providing updated copies. With the exception of the workers’ compensation insurance, all of the insurance policies required in this Agreement shall: (a) provide that the policy will not be cancelled, allowed to expire, or materially reduced in coverage without at least thirty (30) days’ prior written notice to City of such cancellation, expiration, or reduction and each policy shall be endorsed to state such; (b) name City, and City’s Agents as additional insureds with respect to liability arising out of Services, work or operations performed by or on behalf of Professional and shall be endorsed to state such; (c) cover products and completed operations of Professional, premises owned, occupied, or used by the Professional, or automobiles owned, leased, or hired or borrowed by the Professional; contain no special limitations on the scope of protection afforded to City; (d) allow and be endorsed primary with respect to any insurance or self-insurance programs covering City or City’s Agents and any insurance or self-insurance maintained by City or City’s Agents shall be in excess of Professional’s insurance and shall not contribute to it; (e) contain standard separation of insured provisions; and (f) state that any failure to comply with reporting or other provisions of the policy including breaches of warranties shall not affect the coverage provided to City.

27. INDEMNIFICATION BY PROFESSIONAL:

To the fullest extent permitted by law, Professional shall defend with legal counsel reasonably acceptable to City, indemnify and hold harmless City and City’s Agents from and against any and all claims, loss, cost, damage, injury (including, without limitation, injury to or death of an employee of Professional or its subcontractors), expense and liability of every kind, nature and description that arise out of, pertain to, or relate to acts or omissions of Professional, or any direct or indirect subcontractor, employee, contractor, representative or agent of Professional, or anyone that Professional controls (collectively “Liabilities”). Such obligations to defend, hold harmless, and indemnify City and City’s Agents shall not apply to the extent that such Liabilities are caused in whole by the sole negligence, active negligence, reckless or willful misconduct of City or City’s Agents, but shall apply to all other Liabilities. With respect to third party claims against the Professional, the Professional waives any and all rights of any type of express or implied indemnity against City and City’s Agents.

28. LIABILITY OF CITY:

Notwithstanding any other provision of this Agreement, in no event shall City be liable, regardless of whether any claim is based on contract or tort, for any special, consequential, indirect or incidental damages, including, but not limited to, lost profits or revenue, arising out of or in connection with this Agreement or the Services performed in connection with this Agreement.

29. INDEPENDENT CONTRACTOR:

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 490 of 616 ends

CITY CONTRACT NO. 2027-049 12
At all times during the Term, Professional shall be deemed to be an independent contractor and shall be wholly responsible for the manner in which Professional performs the Services required under this Agreement.

Professional shall be liable for its acts and omissions and those of its employees, contractors, subcontractors, representatives, volunteers, and its agents. Nothing contained herein shall be construed as creating an employment, agency or partnership relationship between City and Professional. City shall have the right to control Professional only insofar as the result of Professional’s Services rendered pursuant to this Agreement; however, City shall not have the right to control the means by which Professional accomplishes Services rendered pursuant to this Agreement.

30. PROFESSIONAL NOT AGENT:

Except as City may specify in writing, Professional shall have no authority, express or implied, to act on behalf of City in any capacity whatsoever as an agent. Professional shall have no authority, express or implied, pursuant to this Agreement to bind City to any obligation whatsoever.

31. PAYMENT OF TAXES AND OTHER EXPENSES:

Payment of any taxes, including California sales and use taxes, levied upon this Agreement, the transaction, or the Services or goods delivered pursuant hereto, shall be the obligation of Professional.

32. NOTICES:

All notices shall be in writing and delivered in person or transmitted by certified mail, postage prepaid. Any Party hereto may at any time, by giving ten (10) days’ written notice to the other Party hereto, designate any other address in substitution of the address to which such notice or communication shall be given. Such notices or communications shall be given to the Parties at their addresses set forth below.

If to City: City of Turlock
Attn: Chris Fisher, Director
156 S. Broadway, Suite 150
Turlock, California 95380
With courtesy copies to: City of Turlock, City Attorney’s Office Attn: Katie O. Lucchesi, City Attorney
156 S. Broadway, Suite 230
Turlock, California 95380-5456
If to Professional: Willdan Engineering
Attn: Vanessa Munoz, President
2401 E. Katella Avenue, Suite 300
Anaheim, CA 92806

33. CITY CONTRACT ADMINISTRATOR:

City’s contract administrator and contact person for this Agreement is:

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 491 of 616 ends

CITY CONTRACT NO. 2027-049 13
Julian Avila, Associate Civil Engineer
156 S Broadway Suite 150
Turlock, CA 95380
Telephone: (209) 668-5491
E-mail: [email protected]

34. INTERPRETATION:

As used herein, any gender includes each other gender, the singular includes the plural and vice versa.

35. USE OF CITY PROJECT NUMBER:

Professional or its subcontractors agree to use the aforementioned City project number on all maps, drawings, submittals, billing, and written correspondence that involve City staff or contracted consultants. Nothing in this Section shall preclude Professional or its subcontractors from using their own project numbers for their own internal use.

36. MODIFICATION:

No alteration, amendment, modification, or termination of this Agreement shall be valid unless made in writing and executed by all of the Parties to this Agreement.

37. WAIVER:

No covenant, term, or condition or the breach thereof shall be deemed waived, except by written consent of the Party against whom the waiver is claimed, and any waiver of the breach of any covenant, term, or condition shall not be deemed to be a waiver of any preceding or succeeding breach of the same or any other covenant, term, or condition.

38. ASSIGNMENT:

No Party to this Agreement shall assign, transfer, or otherwise dispose of this Agreement, in whole or in part, to any individual, firm, or corporation without the prior written consent of the other Party. Subject to the forgoing provisions, this Agreement shall be binding upon, and inure to the benefit of, the respective successors and assigns of the Parties hereto.

39. AUTHORITY:

All Parties to this Agreement warrant and represent that they have the power and authority to enter into this Agreement and the names, titles, and capacities herein stated on behalf of any entities, persons, states, or firms represented or purported to be represented by such entities, persons, states or firms and that all former requirements necessary or required by state or federal law in order to enter into the Agreement have been fully complied with. Further, by entering into this Agreement, neither Party hereto shall have breached the terms or conditions of any other contract or agreement to which such Party is obligated, which such breach would have a material effect hereon.

40. DRAFTING AND AMBIGUITIES:

Each Party acknowledges that it has reviewed this Agreement with its own legal counsel, and based upon the advice of that counsel, freely entered into this Agreement. Each Party has participated fully in the review and Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 492 of 616 ends

CITY CONTRACT NO. 2027-049 14
revision of this Agreement. Any rule of construction that ambiguities are to be resolved against the drafting Party does not apply in interpreting this Agreement.

41. GOVERNING LAW:

This Agreement shall be governed by and construed in accordance with the laws of the state of California.

42. VENUE:

Venue for all legal proceedings shall be in the Superior Court of the State of California, in and for the County of Stanislaus.

43. SEVERABILITY:

If this Agreement in its entirety is determined by a court to be invalid or unenforceable, this Agreement shall automatically terminate as of the date of final entry of judgment. If any provision of this Agreement shall be determined by a court to be invalid and unenforceable, or if any provision of this Agreement is rendered invalid or unenforceable according to the terms of any federal or state statute, which becomes effective after the Effective Date of this Agreement, the remaining provisions shall continue in full force and effect and shall be construed to give effect to the intent of this Agreement.

44. EXECUTION AND COUNTERPARTS:

This Agreement may be executed simultaneously, and in several counterparts, each of which shall be deemed an original, but which together shall constitute one and the same instrument. The Parties agree that this Agreement and any other documents to be delivered in connection herewith may be electronically signed utilizing services such as DocuSign and Nitro Sign, or by transmitting signatures in pdf or similar format, and that any electronic signatures appearing on this Agreement or such other documents are the same as handwritten signatures for the purposes of validity, enforceability, and admissibility.

45. AUDIT:

City shall have access at all reasonable times to all reports, contract records, contract documents, contract files, and personnel necessary to audit and verify Professional’s charges to City under this Agreement.

46. ENTIRE AGREEMENT:

This Agreement, together with its specific references, attachments, and exhibits, constitutes the entire agreement of the Parties with respect to the subject matters hereof and supersedes any and all prior negotiations, understanding, and agreements with respect hereto, whether oral or written.

47. SUPERSEDES PRIOR AGREEMENT:

It is the intention of the Parties hereto that this Agreement shall supersede any prior agreements, discussions, commitments, or representations, whether written, electronic or oral, between the Parties with respect to the subject matter of this Agreement.

48. MANDATORY AND PERMISSIVE:
“Shall” and “will” and “agrees” are mandatory. “May” and “can” are permissive.

49. SUCCESSORS AND ASSIGNS:

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 493 of 616 ends

CITY CONTRACT NO. 2027-049 15
All representations, covenants, and warranties specifically set forth in this Agreement, by or on behalf of, or for the benefit of, any or all of the Parties hereto, shall be binding upon and inure to the benefit of such Party, its successors and assigns.

50. HEADINGS:

Headings used in this Agreement are for reference purposes only and shall not be considered in construing this Agreement.

51. ATTORNEY'S FEES AND COSTS:

If any action at law or in equity not resolved pursuant to "ARBITRATION OF DISPUTES" of this Agreement, including action for declaratory relief, is brought to enforce or interpret provisions of this Agreement, the prevailing Party shall be entitled to reasonable attorney's fees and costs, which may be set by the court in the same action or in a separate action brought for that purpose, in addition to any other relief to which such Party may be entitled.

52. NECESSARY ACTS AND FURTHER ASSURANCES:

The Parties shall at their own cost and expense execute and deliver such further documents and instruments and shall take such other actions as may be reasonably required or appropriate to evidence or carry out the intent and purposes of this Agreement.

53. TIME IS OF THE ESSENCE:

Time is of the essence in this Agreement for each covenant and term of a condition herein.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 494 of 616 ends

IN WITNESS WHEREOF, the Parties have caused this Agreement to be executed by and through their respective officers thereunto duly authorized.

Willdan Engineering, a California corporation CITY OF TURLOCK, a California municipal corporation **signature_130530**

SIGNATURE
**name_130530**

FULL NAME
**role_130530**
TITLE
**date_signed_130530**

DATE SIGNED
**signature_130538**

SIGNATURE
**name_130538**

FULL NAME
**role_130538**
TITLE
**date_signed_130538**

DATE SIGNED
APPROVED AS TO SUFFICIENCY:
**signature_130535**

SIGNATURE
**name_130535**

FULL NAME
**role_130535**
TITLE
**date_signed_130535**

DATE SIGNED
APPROVED AS TO FORM:
**signature_130539**

SIGNATURE
**name_130539**

FULL NAME
**role_130539**
TITLE
**date_signed_130539**

DATE SIGNED
ATTEST:

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED 7/6/2026
President
Vanessa Munoz
Municipal Services Director
Christopher Fisher

Page 495 of 616 ends

**signature_130537**

SIGNATURE
**name_130537**

FULL NAME
**role_130537**
TITLE
**date_signed_130537**

DATE SIGNED
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 496 of 616 ends

Exhibits List
A - Scope of Services - Willdan
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 497 of 616 ends

Exhibit A
Scope of Services - Willdan
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 498 of 616 ends

CITY OF TURLOCK

CALIFORNIA
Proposal for
Construction Management Services for System
Wide AMI and Water Meter Installation
#2026-RFP-021
June 24, 2026

CONTACT
Mike Bustos, PE, ENV SP
Principal-in-Charge
[email protected]
805.653.6597
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 499 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
i
} Table of Contents
Cover Letter .........................................................................................................................................................1

4.1. General..........................................................................................................................................................3

4.2. Qualifications and Experience........................................................................................................................3 History of Willdan and Project Team........................................................................................................................ 3 Company Identification ............................................................................................................................................ 4 Sub-Consultants and Division of Responsibilities..................................................................................................... 4 Willdan’s Experience................................................................................................................................................. 4 Experience with Public Agencies and Water Districts............................................................................................... 8 Statement of all Claims/Litigation ............................................................................................................................ 9 Proposed Project Team ............................................................................................................................................ 9

4.3. Methodology Section...................................................................................................................................10 Implementation Plan .............................................................................................................................................. 10 Achieving Client Satisfaction and Scope of Work Requirements............................................................................ 12 Scope of Work Satisfaction................................................................................................................................. 13 Specific Tasks Required from City Staff .................................................................................................................. 16 Scope of Work Satisfaction................................................................................................................................. 17 Mitigation Methods and Practices.......................................................................................................................... 18 Experience with Internet Based Construction Management Systems: Virtual Project Manager........................... 20 Innovative and Creative Approaches...................................................................................................................... 20

4.4. Staffing........................................................................................................................................................22 Team Consistency and Personnel Change Management........................................................................................ 25

4.5. Similar Projects............................................................................................................................................26

4.6. Labor and Fee Estimate................................................................................................................................28 A. Labor Estimate.................................................................................................................................................... 28 B. Fee Estimate ....................................................................................................................................................... 28

7. Qualified Local Vendor Information................................................................................................................29

8. Conflict of Interest Statement.........................................................................................................................30

9. City of Turlock Business License Number ........................................................................................................31

10. SAM.gov .......................................................................................................................................................32

11. Terms of the Sample Agreement...................................................................................................................33 Appendix: Resumes............................................................................................................................................34 Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 500 of 616 ends

City of Turlock
#2026-RFP-021
Construction Management Services for System
Wide AMI and Water Meter Installation
Willdan's Proposal
1 Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 501 of 616 ends

916.661.3520 | fax: 916.478.6005 | 9281 Office Park Circle, Suite 148, Elk Grove, CA 95758-8068 | www.willdan.com 9144
Cover Letter
June 24, 2026
City of Turlock
Submitted via OpenGov Procurement Portal
RE: Proposal for Construction Management Services for System Wide AMI and Water Meter Installation Request For Proposal #2026-RFP-021
The City of Turlock (“City”) undertaking an important infrastructure modernization effort to replace aging water meters, implement AMI technology, improve meter accuracy, and support more efficient water system operations.

Willdan Engineering (“Willdan”) understands that the City needs a responsive construction management partner to protect its interests during construction. Our team will provide field oversight, documentation, schedule and cost control, VPM-based administration, labor compliance, materials testing coordination, and stakeholder coordination. Our team is prepared to provide these services through final completion and will work as an extension of City staff to help deliver a fully operational AMI water meter system.

Unlike many traditional construction management firms, Willdan combines direct AMR/AMI construction management experience, utility operations expertise, and hands-on AMI-to-billing integration experience, allowing us to support both the physical meter replacement program and the successful implementation of the City's new AMI platform. Willdan brings direct experience managing, inspecting, and even installing water meter, AMR/AMI, and municipal water infrastructure projects throughout California. Our relevant experience includes the City of South Gate’s Automatic Water Meter Upgrade projects, City of Fillmore’s Citywide Advanced Metering Infrastructure (AMI) development and implementation project, water main replacement projects, and numerous water distribution, pipeline, and utility improvement assignments for public agencies. This experience gives our team a practical understanding of meter replacement logistics, resident coordination, service interruption constraints, quality documentation, and timely project closeout.

Our proposed team is led by Mike Bustos, PE, ENV SP, who will serve as Principal-inCharge and Project Manager, providing a single point of contact for the City. Mike is supported by experienced construction inspection, QA/QC, labor compliance, and materials testing personnel with strong water infrastructure backgrounds. Willdan’s team will use proven project controls, site-specific inspection checklists, Virtual Project Manager, materials testing coordination, and clear issue-resolution procedures to maintain accountability, reduce risk, and support timely decision-making.

Willdan is committed to delivering this project safely, efficiently, and in full compliance with the City’s Scope of Work. We will focus on protecting the City’s interests, minimizing impacts to residents and businesses, maintaining complete and accurate project records, and supporting completion of a high-quality AMI water meter installation project on schedule and within budget.

We appreciate the opportunity to submit our qualifications and look forward to partnering with the City of Turlock on this important project. Please contact Mike at (805) 279-6870 or email at [email protected] to discuss our qualifications in further detail. We have received and acknowledge Addendum #1 dated June 18, 2026.

Respectfully submitted,

WILLDAN ENGINEERING
Chris Baca, RCI
Director of Construction Services
Project Manager
Mike Bustos, PE, ENV SP
[email protected]
805.279.6870
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 502 of 616 ends

No. Evaluation Criteria Willdan Response

1. Demonstrated qualifications,
competence, abilities, and
knowledge of personnel
assigned
ü Mike Bustos, PE, ENV SP, leads delivery with support from Arne Cvek and inspectors with direct water utility experience
ü Willdan’s proposed team combines senior CM leadership, QA/QC oversight, labor compliance, materials testing, and experienced water infrastructure inspectors.

2. Experience of the Consultant
to provide the specified
services
ü Willdan has delivered CM, inspection, labor compliance, and materials testing for similar municipal water meter replacement projects
ü Our experience includes AMR/AMI development and
implementation, upgrades, water main replacements, pipelines, and public agency utility improvements.

3. Record of the Consultant in
accomplishing similar work
within budget
ü Willdan emphasizes early issue identification, schedule tracking, cost control, accurate documentation, and timely change order review ü Our project controls and experienced field staff help minimize claims, avoid delays, and protect agency budgets

4. Completeness of proposal ü Willdan’s proposal directly responds to each RFP requirement and evaluation criterion.
ü The proposal includes the required scope, methodology, staffing, similar projects, fee information, forms, and acknowledgments.

5. Approach/ Methodology ü Willdan’s methodology centers on proactive CM, full-time inspection, VPM documentation, and clear issue resolution
ü Our approach supports quality assurance, schedule control, public outreach coordination, labor compliance, materials testing, and closeout

6. Consultant Fees ü Willdan provides clear labor assumptions, task-level effort, and a notto-exceed cost ü Our staffing plan balances cost-effective delivery with responsive senior oversight and specialty support

7. Financial responsibility ü Willdan offers the stability of a California corporation backed by a publicly traded parent company
ü With 62 years in business, 1,800+ employees, and 50+ offices, Willdan has the resources to support the City through completion ü Willdan has worked extensively with over 96% of the cities and counties, as well as over 90 water districts in California

8. Qualified Local Vendor
Preference
ü Willdan maintains an active City of Turlock business license and is prepared to perform work in compliance with City requirements. ü Willdan’s statewide public agency experience and local project readiness provide strong value despite no QLV preference.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 503 of 616 ends

City of Turlock
#2026-RFP-021
Construction Management Services for System
Wide AMI and Water Meter Installation
Qualifications and
Experience
2 Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 504 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
3 4.1. General
Willdan has reviewed and understands the requirements of RFP #2026-RFP-021, including the formal proposal guidelines, submission requirements, and project coordination responsibilities. We confirm that this proposal has been prepared in the required order and format and will be submitted electronically through the City’s OpenGov eProcurement portal by the stated deadline.

Willdan acknowledges that all submitted materials become property of the City, may be subject to disclosure under the California Public Records Act, and may not be amended, modified, or supplemented after the proposal deadline.

4.2. Qualifications and Experience
History of Willdan and Project Team
Willdan Engineering (Willdan), a California corporation since 1964, is a subsidiary of Willdan Group, Inc., a publicly traded corporation. Services are provided to nationwide clientele through three subsidiary firms – Willdan Engineering, Willdan Energy Solutions, and Willdan Financial Services – that offer a portfolio of diversified strengths.

Willdan has more than 1,800 employees, including licensed engineers, program and construction managers, financial analysts, planners, and other skilled professionals, operating out of 50+ offices located throughout the United States. Willdan benefits from well-established relationships with local and state government agencies, investor-owned and municipal utilities, and private sector commercial and industrial firms throughout the United States. We have supported the implementation of community visions through engineering, construction management, inspection, planning, building safety, and staff augmentation services. Willdan is in good standing with the State of California and is licensed to practice in California.

Throughout our 62-year history in California, Willdan has been a consistent industry leader, providing all aspects of municipal, infrastructure, and transportation engineering; program management; financial consulting; municipal planning; and environmental and energy-related services, along with a full complement of related disciplines. Dedicated to providing public agencies with reliable, high quality, and cost-effective services, Willdan merges sound solutions with a solid respect for the fiscal responsibility faced by public agencies and the concerns of affected communities. This approach has proven responsive to the most challenging budget, schedule, and aesthetic requirements; it is the foundation of our excellent reputation and our company growth. Willdan addresses the varied demographics of our public agency clients through focused, specialized services offering solutions tailored to the unique goals and visions of each agency.

Our resident engineers, construction managers,
and construction observers offer reliable service,
quality workmanship, use of good judgment, fair
and equitable treatment, and adherence to our
corporate integrity. These experienced team
members identify and correct discrepancies,
ambiguities, omissions, or conflicts in plans,
specifications, and bid schedules that might
generate misinterpretation and/or lead to agency
and contractor disagreements. Our professionals
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 505 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
4 are adept at anticipating issues before they arise through continual review of project plans, specifications, contractors’ schedules, and contract documents. Potential problems are brought to the attention of the City's Project Manager and/or the contractor, along with constructive recommendations for solutions, so costly delays and negative impacts to the public and projects are avoided.

Company Identification
Company Identification
Legal Form of Company Corporation
Ownership of Company Publicly Traded Company
Senior Officials of Company § Michael A. Bieber, Chairman of the Board § Vanessa Munoz, President, Chief Executive Officer
§ Creighton K. Early, Chief Financial Officer, Treasurer § Aaron Etzkorn, Senior Vice President
§ Patrick Johnson, Vice President
§ Kate Nguyen, Secretary
§ Pattie Casey, Assistant Secretary
Name and Email of Main Contact (for project) Mike Bustos, PE, ENV SP, [email protected] Phone Number 805.279.6870
E-mail Address (for proposals) [email protected]
Website www.willdan.com
Unique Entity Identifier (SAM.GOV) VUFLJX1FNUG1
Sub-Consultants and Division of Responsibilities
Willdan will be the primary participating party for the City. We will utilize one sub-consultant to provide specialty support under the direction of Willdan staff.

Sierra Geotech (Materials Testing Subconsultant)
Division of Responsibilities: Sierra Geotech will provide specialized materials sampling, testing, and laboratory services to complement Willdan's in-house geotechnical capabilities under Manuel Guzman, PE. Sierra's testing personnel will coordinate daily with the Construction Manager and Construction Inspector to ensure timely testing of construction materials. Manuel Guzman will provide technical oversight and quality assurance review of all materials testing reports, with results communicated through the established project reporting structure to the City.

Sierra Geotech Office (location): 4470 Yankee Hill Rd, Rocklin, CA Willdan’s Experience
Water Meter and AMR/AMI Installation Projects. Willdan has successfully delivered comprehensive construction management and inspection services for multiple automatic meter reading and water meter replacement projects throughout California. In the City of South Gate, Willdan provided construction management, inspection, and labor compliance services for the Automatic Meter Reading (AMR) Phase 3, Project No. 649-WTR. This $1.3 million project involved removing and replacing approximately 1,725 existing water meters ranging from 3/4-inch to 2- Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 506 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
5 inch with new Automatic Meter Reading based water meters and Itron 500W transmitters throughout Route C-1 of the City's water distribution system. The project also included replacing and connecting piping and valves on customer side connections as needed. Willdan is currently providing similar services for the City of South Gate's Phase 5 AMR Upgrade Project, demonstrating the City's continued confidence in Willdan's construction management capabilities. Willdan is also scheduled to begin providing construction inspection services in July 2026 for the City of Glendale Water and Power’s Advance Meter Infrastructure (AMI) System Replacement, which will feature 34,662 new water AMI meter assemblies.

Willdan has also successfully supported large-scale water meter and AMI programs through a Section 4217 performance contracting procurement process, including the City of Fresno’s 110,000 residential water meter and AMR installation program and the City of Woodland’s citywide meter replacement project. Our experience includes coordinating multiple installation crews, maintaining quality control across thousands of residential and commercial locations, and ensuring compliance with agency specifications while minimizing impacts to customers.

Turn-Key AMI Delivery and Billing Integration. Willdan has recent, directly applicable experience delivering complete water metering modernization on a turn-key, design-build basis — taking single-point responsibility from system design through installation, integration, and commissioning. For the Cities of Paramount and Fillmore, Willdan replaced each City’s entire meter population with ultrasonic meters on cellular AMI and deployed a combined platform that ingested the AMI head-end data, served a customer engagement portal, and transmitted consumption data into each City’s utility billing system (Eden in Paramount, Springbrook in Fillmore).

That last step — getting AMI reads to flow accurately and reconcile into the billing system — is where these programs live or die, and Willdan owned it end to end as the integrator. Having delivered the meter-to-cash chain as the design-builder, our team knows where AMI-to-billing integrations succeed and where they break down:
endpoint and meter-ID mapping, head-end-to-billing data flow, billing-determinant validation, and maintaining billing continuity through both a meter-technology change and a billing-system transition. That experience lets us anticipate integration risks early and hold the contractor, AMI vendor, and billing vendor to a defined datavalidation and commissioning standard.

Water Distribution System Projects. Willdan's expertise extends to water distribution pipeline construction that supports municipal utility operations. In addition to the standalone meter replacement projects mentioned above, Willdan has also provided construction management and or inspection services to public agencies on numerous water distribution pipelines, including over a dozen for the City of Downey, which include water main replacement and replacement of existing meters with AMI/AMR based water meters.

Representative Projects. Willdan's team expertise and experience are a well-suited match for the City’s project.

Our experience encompasses the full realm of services that could be involved in the City's project as highlighted in the following experience matrix.

These projects represent Willdan’s successful record in accomplishing similar work within budget.

Project Client
Construction Management
Construction InspectionMaterial TestingWater Meter Installs AMI/AMRProperty Owner Coordination
Contractor Cooperation

WATER INFRASTRUCTURE PROJECTS
649-WTR Automatic Meter Reading
(AMR) Upgrade – Phase III City of South Gate § § § § § § § 740-WTR Automatic Meter Reading
(AMR) Upgrade – Phase V City of South Gate § § § § § § § Advanced Meter Infrastructure (Ph 1)
System Replacement*
Glendale Water &
Power § § § § §
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 507 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
6 Project Client
Construction ManagementConstruction InspectionMaterial TestingWater Meter InstallsAMI/AMRProperty Owner Coordination Contractor
Cooperation
Residential Water Meter and AMI
Program City of Fresno § § § § § §
Citywide Meter Replacement City of Woodland § § § § § § Water Meter and AMI Upgrade City of Fillmore § § § § § § CIP 19-04 Woodruff Ave Water System
Improvements City of Downey § § § § § § §
CIP 19-04 Samoline Ave and Melva St
Water System Improvements City of Downey § § § § § § §
CIP 20-23 Third Street Water System
Improvements City of Downey § § § § § § §
CIP 22-13 Third Street Water System
Improvements City of Downey § § § § § §
CIP 23-20 4th Street Water System
Improvements City of Downey § § § § § §
CIP 21-15 5th Street Water System
Improvements City of Downey § § § § § §
CIP 23-19 6th Street Water System
Improvements City of Downey § § § § § §
CIP 23-21 Stamps Rd Water System
Improvements City of Downey § § § § § §
Foothill Neighborhood Public Utilities City of Santa Paula § § § § Tract 5520 Public Improvements City of Fillmore § § § § SP4037 Annual Water Line Project City of Orange § § § § Annual Water Main Replacement City of Santa Monica § § § § § Phase 1 Watermain Replacement City of South Gate § § § § § § Associated Road Water High Pressure
Waterline City of Brea § § § § §
Cliffwood Industrial Park Water
Improvements City of Brea § § § § § §
Country Hills Water Phase II City of Brea § § § § § §
Euclid Street Water Main City of La Habra § § § § § §
*Project in preconstruction phase – scheduled to start in July 2026 Maintaining Cooperative Atmosphere and Attitude with Contractor. Willdan's construction management methodology emphasizes maintaining a cooperative atmosphere with contractors while serving as the owner's representative. Our approach integrates proven project management methodologies with tailored local strategies, ensuring efficiency, transparency, and public accountability. Throughout construction, our team will maintain a project-first philosophy with the contractor. When this is achieved, construction is easy, straight forward, and accomplished with a minimum of issues. When this collaborative atmosphere is established, it creates a fair environment for all, and project success is achieved. Most contractors will avoid combative arguments and approach projects with a collaborative, team mindset when they know they will be treated fairly, in turn, leading to open, transparent communication, and often less change orders.

Property Owner Coordination and Public Communication. Water service interruptions are among the most sensitive aspects of a water meter replacement project. Temporary shutdowns and service interruptions must be Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 508 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
7 carefully coordinated, communicated, and documented to minimize impacts to residents and businesses. Willdan will proactively coordinate with the Contractor, City staff, residents, businesses, and property owners to minimize impacts associated with planned water shutoffs. Prior to construction activities, our team will review, monitor, and support the City’s public outreach program, including notification letters, door hangers, and other project communications to verify that affected customers receive timely notice of upcoming work and anticipated service interruption durations. During construction, Willdan’s field staff will remain available to engage directly with property owners and occupants, respond to questions, and coordinate special accommodations when operational constraints exist, such as medical needs, business operations, irrigation systems, or other critical water-use requirements.

In addition to customer communication, Willdan recognizes that accurate documentation during meter replacement is essential to maintaining billing continuity and preventing account discrepancies. Our inspectors will monitor the Contractor’s meter replacement documentation process to verify that existing meter serial numbers, final meter readings, service addresses, customer account information, new meter serial numbers, and AMI endpoint identifiers are accurately recorded and reconciled for each installation. We will review completed meter replacement forms for completeness and consistency and verify that documentation is properly transmitted to the City and project stakeholders to support successful integration with the AMI platform and Tyler New World billing system. This process helps ensure that customer usage history, billing records, and account assignments remain accurate throughout the transition to the new AMI system.

Willdan will also monitor compliance with notification requirements, verify that additional notices are provided when schedules change or shutoffs are extended, and promptly communicate emerging issues to City staff.

Through proactive communication, detailed documentation oversight, and responsive issue resolution, Willdan will help minimize customer inconvenience while supporting accurate billing records and efficient completion of meter replacement activities.

Timely Contract Close Out. Willdan understands that timely contract closeout is essential to achieving final project acceptance, releasing retention, and transitioning the AMI system into full operational use by the City. Throughout construction, our team will maintain organized project records, track outstanding items, monitor submittal and documentation requirements, and proactively identify closeout deliverables well before project completion. We will coordinate with the Contractor, AMI vendor, and City staff to verify completion of punch list items, resolution of deficiencies, acceptance of commissioning and integration activities, submission of as-builts, warranties, operation and maintenance information, testing records, and all required closeout documentation. Willdan will conduct substantial and final completion inspections, prepare and track punch lists, verify corrective actions, and provide recommendations regarding project acceptance. By managing closeout activities continuously throughout the project rather than waiting until construction is complete, Willdan helps avoid unnecessary delays and supports a smooth, efficient transition to final acceptance and project completion.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 509 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
8 Experience with Public Agencies and Water Districts
Willdan has worked extensively with over 96% of the cities and counties, as well as over 90 water districts in California, providing construction management, engineering, and inspection services. This extensive public sector experience provides the firm with unique insight into municipal operations, procurement requirements, and the fiscal challenges facing local agencies. A significant portion of Willdan's staff have served in public agency management positions prior to joining the firm, bringing firsthand knowledge of client needs and operational realities.

Water District Experience. Willdan has provided construction management and engineering services to numerous California water districts and municipal water departments. Representative water district clients include:
§ City of Santa Ana
§ Western Municipal Water District
§ Liberty Water (formerly Park Water Company)
§ Santa Monica Water Department
§ Downey Water Department
§ Brea Water Department
§ Lakewood Water Department
§ Long Beach Water Department
§ South Gate Water Department
§ San Bernardino Municipal Water Department
These assignments have involved construction management for water treatment facilities, well installations, reservoir construction, pipeline replacements, pump station upgrades, and distribution system improvements.

Regulatory Compliance and Procurement. Willdan is highly experienced with permitting and regulatory requirements for water infrastructure projects, including Caltrans LAPM procedures for federally funded projects, with participation in more than 200 successful Caltrans audits. Our construction managers are well versed in federal and state funding administration, Davis-Bacon compliance, and grant management for agencies such as the EPA, Caltrans, and the State Water Resources Control Board.

Environmental and Water Quality Compliance. Our team includes Qualified SWPPP Practitioners and Developers who oversee compliance with State Water Resources Control Board Construction General Permit requirements and municipal stormwater permits.

We monitor BMP implementation, ensure proper documentation, and coordinate with regulatory agencies to protect water quality during construction.

Ongoing Public Agency Relationships. Willdan has worked extensively with public agencies throughout California for more than 62 years, providing engineering, construction management, inspection, labor compliance, materials testing, and program management services. We have supported over 96% of California’s cities and counties and maintain long-standing relationships with municipalities, water departments, special districts, transportation agencies, and utility providers. This extensive public-sector experience has given our team a thorough understanding of public agency procurement requirements, contract administration procedures, regulatory compliance obligations, funding requirements, and stakeholder expectations.

Many of Willdan’s professionals have previously served in public agency leadership and management roles, providing firsthand insight into the operational, financial, and political considerations that influence successful project delivery. Our experience working as an extension of agency staff enables us to communicate effectively with City personnel, consultants, contractors, utility providers, elected officials, and the public while maintaining accountability, transparency, and responsiveness throughout project execution. This public agency perspective allows Willdan to consistently deliver projects that protect agency interests, support informed decision-making, and achieve successful outcomes for the communities we serve.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 510 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
9 Comprehensive Municipal Service Portfolio. Willdan's understanding of public agency needs and issues is unique in the industry, stemming from the significant portion of staff who have served in public agency management positions prior to joining Willdan. Willdan merges sound solutions with a solid respect for the fiscal responsibility faced by local agencies and the concerns of affected communities. This approach has proven responsive to the most challenging budget, schedule, and aesthetic requirements, contributing to the firm's industry reputation and company growth.

Statement of all Claims/Litigation
Willdan Engineering, from time to time, has claims arising from workers compensation, automobile liability and other liability claims in the past five (5) years. Willdan Engineering has not had any claims that made a material impact to its financial condition or the performance of any of its contracts.

Proposed Project Team
Our proposed project team contains 7 employees and 3 construction inspector alternates. See Section 4.4 for additional details and full resumes.

Willdan Staff Role
Mike Bustos, PE, ENV SP Principal-in-Charge/Project Manager Arne Cvek Construction Manager
Scott Griffith, LEED GA AMI Integration Specialist
Simon Hernandez Construction Inspector (Lead)
Marti Martin Construction Inspector (Alternate)
Heleo Espinoza Construction Inspector (Alternate)
Manny Trujillo Construction Inspector (Alternate)
Jane Freij Labor Compliance Manager
Manuel Guzman, PE Supervising Engineer, Material Testing John Borquez Schedule Reviewer
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 511 of 616 ends

City of Turlock
#2026-RFP-021
Construction Management Services for System
Wide AMI and Water Meter Installation
Methodology Section
3 Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 512 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
10 4.3. Methodology Section
Willdan’s project delivery methodology is built around proactive construction management, rigorous project controls, continuous communication, and comprehensive documentation. Our approach is designed to provide the City of Turlock with real-time visibility into project status while ensuring construction quality, schedule adherence, budget control, regulatory compliance, and successful implementation of the City’s Advanced Metering Infrastructure (AMI) system. Our objective is to protect the City’s interests while facilitating successful completion of approximately 4,293 meter replacements, implementation of the AMI system, and integration of meter data into the City’s billing platform within the established schedule and budget.

Implementation Plan
Willdan provides comprehensive construction management services fully aligned with the City’s RFP requirements, to modernize the City’s water metering infrastructure. § Pre-Construction. Prior to construction, Willdan will conduct a comprehensive review of the construction documents, contractor schedule, public outreach requirements, AMI implementation requirements, and project-specific risks. We will establish project controls, communication protocols, documentation procedures, and VPM workflows to ensure efficient management of RFIs, submittals, change orders, schedules, and project correspondence. We will lead the pre-construction meeting and coordinate with the Design Engineer, City staff, Contractor, and key stakeholders to establish clear expectations and responsibilities.
§ Pre-Construction and Progress Meeting Management. Willdan will prepare agendas, conduct meetings, and prepare and distribute meeting minutes for weekly progress meetings and bi-weekly progress meetings as required by the City. Virtual meeting capabilities will be provided through Cisco WebEx Teams, Microsoft Teams, or Zoom to conduct virtual meetings, allowing meeting attendees to share computer screens so that all attendees can review reference documents such as photos and plan sheets while working remotely from different locations. Willdan Engineering will provide tablets or laptops and mobile hot spot hardware to field staff to maintain communication with all parties.

Weekly coordination meetings and bi-weekly progress meetings will be conducted to review project status, installation production rates, schedule performance, outstanding RFIs, submittals, change orders, public outreach activities, AMI integration progress, and critical action items. Meeting minutes, action item logs, and project decisions will be documented and tracked through completion. § Public Outreach Monitoring. Willdan’s inspectors provide greater understanding of the City's cause to the general public, residents, and businesses. Typically, efforts begin by having the inspector visit the job site before construction starts, identifying key stakeholders in the project area, introducing themselves, and handing out business cards. Willdan Engineering is available to act as liaison between the City and community partners to further the goals of the project. § Construction Management and Administration. Experienced construction managers and resident engineers provide field oversight, manage contract documentation, process progress payments, and proactively facilitate the project activities to ensure compliance and clear communication. Willdan will utilize Virtual Project Manager (VPM) as the primary platform for project documentation, communication, and record management. Through VPM, our team will manage RFIs, submittals, working day statements, meeting minutes, daily reports, progress photos, change orders, and project correspondence. Utilizing our in-house Scheduler, we will continuously monitor project progress against the approved baseline schedule, evaluate schedule updates, identify potential delays, and work collaboratively with the Contractor to implement corrective actions when necessary.

Basic Principles to
Project Approach
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 513 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
11 § Inspection and Quality Control. During construction, Willdan will provide full-time field observation services to verify that work is completed in accordance with the plans, specifications, manufacturer requirements, City standards, and approved submittals. Our inspectors will document daily activities, monitor contractor performance, verify temporary traffic and pedestrian controls, review public notification efforts, and coordinate closely with affected property owners during meter replacement activities and water shutoffs. Particular emphasis will be placed on maintaining accurate installation records, documenting existing and replacement meter information, verifying meter testing and functionality, and ensuring that customer account data is accurately transferred to support uninterrupted billing operations.
§ Erosion Control Review and Compliance. Willdan's inspectors are fully knowledgeable in the latest regulations for storm water abatement and QSP/QSD training. The construction managers and inspectors have the authority and capability to quickly identify any flaws in the contractor's erosion control plans and meet with the contractor to rectify the issue with agreed-upon solutions that meet standards while avoiding delays.
§ Specialty Testing. While the material testing needs on this type of project are very minimal, Willdan and Sierra Geotech will work collaboratively to provide responsive, high-quality materials testing and quality assurance services throughout construction as the needs arise. Sierra Geotech will perform the day-to-day field and laboratory testing activities and Willdan will provide technical oversight through Supervising Engineer Manuel Guzman, PE, one of Willdan's technical leads for geotechnical engineering and materials testing services, providing the City with an additional layer of technical review and quality assurance beyond standard testing services. This integrated approach provides the City with the responsiveness of a local accredited laboratory, combined with the technical expertise, engineering judgment, and quality assurance oversight of Willdan's geotechnical and construction management professionals. § Coordination. Willdan will serve as the City’s single coordination point across the installation contractor, AMI vendor, billing system vendor, and City staff regarding the integration of new meter and AMI data into the City’s billing system. To keep that coordination disciplined, Willdan will establish and maintain a coordination tracker that maps the interfaces and data hand-offs along the full path — meter → endpoint → head-end → billing → reports — so responsibilities, dependencies, and open items stay clear and nothing falls between vendors.
§ Integration Testing, Commissioning, and Data Validation. Willdan will review the AMI vendors’ integration testing, commissioning, and data-validation activities — including phased testing (system integration, user acceptance, and field testing) and validation of AMI reads against field reads and prior consumption history — and provide recommendations to the City before it accepts data into production billing. Because Willdan has performed AMI-to-billing integration as the design-builder, these reviews go beyond confirming that tests were run to assessing whether the right things were tested and whether results actually demonstrate billing-ready data. We have established relationships with vendors who specialize in AMI billing integration and can assist our team with the City’s project. As part of inspection, Willdan will also perform installationlevel quality assurance — verifying meter number, read accuracy, and installation correctness — so installation defects are caught before they affect billing. § Business Process Evaluation. Willdan will assist the City in evaluating its existing meter-to-cash and customer service business processes and identifying the process updates needed to incorporate AMI data and functionality — for example, exception-based billing, leak and continuous-consumption alerts, and streamlined high-bill investigation and move-in/move-out workflows. § Monitoring and Reporting. Willdan will monitor the status of integration activities and report issues, risks, and coordination needs to the City on a regular cadence, maintaining an issues-and-risk log with defined escalation paths so dependencies are surfaced and resolved before they affect schedule or billing accuracy. § Project Closeout. At project closeout, Willdan will conduct substantial and final completion inspections, prepare and track punch list items, verify completion of commissioning and integration activities, review Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 514 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
12 project documentation, coordinate final acceptance requirements, and provide recommendations to the City regarding project completion. By maintaining rigorous oversight from pre-construction through final acceptance, Willdan will help ensure the City receives a high-quality, fully functional AMI system delivered safely, efficiently, and in accordance with the project requirements.

Achieving Client Satisfaction and Scope of Work Requirements Willdan’s primary objective is to serve as a trusted extension of City staff throughout the delivery of the System Wide AMI and Water Meter Installation – Phase 1 Project. Our approach is centered on proactive communication, responsive project management, comprehensive field oversight, and disciplined project controls that provide the City with confidence that construction activities, AMI implementation, and system integration are progressing safely, efficiently, and in accordance with project requirements.

Client satisfaction begins with communication and accountability. Willdan will designate a single point of contact responsible for coordinating all construction management activities and maintaining consistent communication with City staff. Our team will provide timely responses to City requests, maintain open communication channels with project stakeholders, and promptly elevate issues requiring City input or decision-making. Regular progress meetings, status updates, schedule reviews, and project reporting will ensure that City staff remain informed regarding project progress, budget status, potential risks, public concerns, and upcoming activities.

To satisfy the requirements of the Scope of Work, Willdan will provide full-time field inspection and construction management services throughout the duration of the project. Our inspectors will document daily construction activities, monitor contractor compliance with the plans and specifications, verify traffic and pedestrian controls, review public notification efforts, observe meter installation and testing activities, and maintain complete project records. Construction activities will be documented through daily reports, photographs, quantity tracking, and inspection logs maintained within the City’s Virtual Project Manager (VPM) platform.

Because the project involves replacement of approximately 4,293 water meters and implementation of a new AMI system, Willdan will place particular emphasis on quality assurance, documentation accuracy, and system integration. Our team will monitor the Contractor’s meter replacement documentation process to verify that existing meter serial numbers, final meter readings, service addresses, new meter serial numbers, and endpoint identifiers are accurately recorded and reconciled. We will review installation records, monitor meter testing and endpoint activation activities, and coordinate with the Contractor, AMI vendor, Tyler Technologies representatives, Design Engineer, and City staff to support successful commissioning and integration of the new AMI system.

Willdan will utilize Virtual Project Manager (VPM) as the primary project management platform for RFIs, submittals, daily reports, meeting minutes, working day statements, change orders, payment reviews, and project correspondence. Our familiarity with VPM allows us to provide the City with transparent, real-time access to project information while maintaining complete and organized project records.

To protect the City’s schedule and budget, Willdan will continuously monitor contractor performance, review baseline and updated schedules, evaluate potential delays, verify quantities, review payment applications, and assess change order requests. Our proactive management approach helps reduce claims, avoid unnecessary delays, and minimize impacts to project costs.

Willdan will also provide labor compliance monitoring services with in-house staff, including review of certified payroll submissions, spot-checking prevailing wage compliance, maintaining labor compliance records, and notifying the Contractor of any identified deficiencies. These efforts help ensure compliance with applicable labor regulations and protect the City from potential regulatory issues.

Throughout construction, our team will support the City’s commitment to customer service by monitoring public outreach efforts, coordinating with property owners affected by water shutoffs, responding to stakeholder concerns, and helping minimize impacts to residents and businesses. Our inspectors understand that successful project delivery requires not only quality construction but also positive interactions with the public.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 515 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
13 Finally, Willdan will actively manage project closeout from the beginning of construction through final acceptance.

We will track closeout requirements, coordinate substantial and final completion inspections, prepare and monitor punch list items, review final documentation, support commissioning and integration acceptance activities, and provide recommendations regarding project acceptance. This proactive approach helps ensure an efficient transition from construction to full operation of the City’s new AMI system.

Through responsive service, proactive communication, rigorous project controls, and comprehensive oversight of construction and AMI implementation activities, Willdan will deliver the high level of service necessary to achieve client satisfaction and successfully fulfill all requirements of the City’s Scope of Work.

Scope of Work Satisfaction
Willdan has reviewed and understands the Scope of Work for the City of Turlock’s System Wide AMI and Water Meter Installation – Phase 1 Project. Willdan will provide the scope of services required by the RFP through the estimated Final Completion due date.

Willdan’s scope of services will include the following:
§ Enter into and provide all required documentation specified in the sample agreement and provide said documentation within one week of the approval of the agreement by the City Council. § Utilize Virtual Project Manager (VPM) for reviewing, approving, and viewing of all construction documentation for the duration of the construction contract and for project correspondence to the maximum extent possible.
§ Use computer hardware and software that meets the requirements of the VPM system and ensure connectivity to VPM.
§ Lead and document a pre-construction meeting, in coordination with the Design Engineer. § Lead and document regularly scheduled construction progress meetings on a bi-weekly basis. § Provide a virtual option to participants for each meeting, such as Zoom, Microsoft Teams, Webex, or similar platform.
§ Create and approve Weekly Statements of Working Days in VPM on a weekly basis and include them in regular progress meeting agenda packets.
§ Review, verify, and monitor the Contractor’s public outreach efforts, including notification letters and door hangers to affected property owners and residents, including tenants where applicable. § Be available to engage and communicate with nearby property owners and residents during water shutoff periods.
§ Monitor the Contractor’s public notification efforts during construction and verify that additional notices are provided for extended shutoffs, schedule changes, or other significant impacts. § Review the Contractor’s performance in tracking and providing a form for each water meter being replaced and advise the Contractor of any deficiencies. § Provide full-time field inspection of the work in progress on the site for conformance with the project details and specifications with skilled and professional personnel. § Monitor all construction work and document the work.
§ Maintain daily written reports.
§ Track and record change order work on a Force Account basis, except when the cost of change order work has been approved as a lump sum amount prior to any change order work performed. § Perform daily inspection of temporary traffic and pedestrian control devices placed by the Contractor for conformance with the approved temporary pedestrian and traffic control plans, as needed. § Monitor the Contractor’s compliance with work restrictions and City projects coordination requirements. § Advise the Contractor of observed violations or potential conflicts related to access limitations, traffic or pedestrian impacts, and overlapping City projects.
§ Coordinate with City staff, involved vendors, the Design Engineer, the Contractor, and other City project contractors as needed.
§ Document coordination issues and unresolved conflicts in the project records.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 516 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
14 § Perform review of the Erosion and Sediment Control Plan. § Review effectiveness of Best Management Practices placed by the Contractor and advise the Contractor of any BMP deficiencies noted while inspecting the work. § Perform, or subcontract, coordinate, and administer any required materials testing and special inspections during construction.
§ Observe and document the Contractor’s required functional verification of installed meters, including bucket testing or other Engineer-approved method.
§ Verify that deficiencies, including leaks, improper meter registration, or communication failures, are corrected and retested prior to acceptance.
§ Coordinate with the City of Turlock Water Division for water quality sampling and testing when required. § Coordinate, monitor, and support implementation of the AMI solution as it interfaces with the City’s software systems and related business processes.
§ Coordinate with the Contractor, AMI vendor, billing system vendor, and City staff regarding integration of new meter and AMI data into the City’s billing system.
§ Review integration testing, commissioning, and data validation activities and provide recommendations to the City.
§ Assist the City in evaluating existing business processes and identifying process updates needed to incorporate AMI data and functionality.
§ Monitor the status of integration activities and report issues, risks, and coordination needs to the City. § Assist the Design Engineer and Contractor with general coordination of submittals, RFIs, design clarifications, and Design Engineer responses.
§ Monitor the Contractor’s activities related to utility coordination efforts and advise the Contractor and City staff of any corrections needed.
§ Maintain detailed project records, including inspection reports, photos, measurement of quantities, submittal logs, RFI logs, meeting minutes, and decision logs. § Review and approve the construction baseline schedule and other schedules required to be submitted by the construction contractor.
§ Monitor the Contractor’s progress of the approved baseline schedule. § Review baseline schedule updates and require recovery schedules as may be required in the progress of the work.
§ Review the construction contractor’s invoices on a monthly basis and provide recommendation to the City for payment based on quantities placed and materials or equipment purchased and stored. § Document, review, and comment on change order requests and contract change orders, including work related to allowance bid items.
§ Provide assessment of schedule impacts and potential contractor delays. § Provide recommendation for Owner’s action on potential change orders. § Maintain notes and documents to support the Owner and Design Engineer during claims proceedings. § Include a separate task and an allowance in the amount of $10,000 to analyze, coordinate, administer, and make recommendations regarding potential claims.
§ Provide labor compliance monitoring activities.
§ Verify that the Contractor is regularly uploading certified payroll reports to the DIR website and to the City/Construction Manager as required.
§ Spot check the Contractor’s certified payroll reports. § Track any payments noted as being less than the required prevailing wage rate and notify the Contractor of non-compliance.
§ Maintain a record of all certified payroll records submitted by the Contractor and safeguard the information to the maximum extent permitted by law.
§ Inspect the work for Substantial Completion and Final Completion. § Issue punchlists.
§ Recommend final acceptance of the project upon completion of all punchlist items.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 517 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
15 AMI Integration and Commissioning Approach
The City of Turlock’s System Wide AMI and Water Meter Installation Project is more than a meter replacement program. Successful project delivery requires accurate installation of new meters and endpoints, reliable communication with the AMI system, validation of meter and account data, successful integration with the City’s billing platform, and implementation of business processes that allow City staff to fully utilize the new AMI capabilities. Willdan will provide construction management oversight throughout the installation, testing, commissioning, and integration phases to help ensure a successful transition to the new AMI system.

Installation Verification and Quality Control
Willdan will monitor the Contractor’s installation activities to verify that all meters, registers, endpoints, meter boxes, and associated appurtenances are installed in accordance with the contract documents, manufacturer requirements, and approved submittals. Inspection staff will review installation records and perform field verification of completed installations to confirm:
§ Correct meter size and model installation
§ Proper endpoint installation and activation
§ Accurate meter serial number and endpoint identification recording § Proper customer account association
§ Compliance with project specifications and approved installation procedures Willdan will review the Contractor’s meter replacement tracking forms and installation database records to verify completeness and accuracy before acceptance.

Functional Verification and Commissioning
Willdan will observe and document the Contractor’s required functional verification testing of installed meters and AMI components. This includes verification of meter operation, communication functionality, and successful registration of meter data within the AMI system.

Deficiencies such as leaks, improper registration, communication failures, incorrect account assignments, or data transmission issues will be documented and tracked through resolution. Willdan will verify that corrective actions have been completed and that affected installations have been retested prior to acceptance.

AMI System Integration Oversight
Willdan will coordinate with the Contractor, AMI vendor, Tyler billing system representatives, Design Engineer, and City staff to support implementation of the AMI solution and integration with the City’s existing software systems.

Our team will monitor integration activities including:
§ Meter and endpoint data transfers
§ Account-to-meter association verification
§ Data synchronization between AMI and billing systems
§ Interface testing and validation
§ Exception reporting and resolution
§ System acceptance testing activities
Willdan will facilitate communication among project stakeholders to identify and resolve integration issues quickly while minimizing impacts to project schedule and operations.

Data Validation and Account Reconciliation
Accurate customer billing depends on proper assignment of each installed meter and endpoint to the correct customer account. Willdan will review the Contractor’s data management procedures and monitor implementation of data validation protocols throughout the project.

Our team will assist the City by reviewing:
§ Meter serial number inventories
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 518 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
16 § Endpoint identification records
§ Customer account assignments
§ Installation completion reports
§ Data validation and reconciliation reports
Any discrepancies identified during installation or integration testing will be documented and tracked through resolution prior to project acceptance.

Business Process Coordination
Implementation of AMI technology often requires updates to utility operations, customer service procedures, and billing workflows. Willdan will assist the City in identifying operational impacts and coordinating implementation activities among City staff, the Contractor, the AMI vendor, and billing system representatives.

This support may include review of:
§ New meter reading workflows
§ Exception management procedures
§ Leak notification processes
§ Customer service coordination
§ Reporting and dashboard requirements
§ Billing process updates associated with AMI deployment Risk Management and Reporting
Willdan will maintain an AMI Integration and Commissioning Issues Log to track integration risks, testing results, unresolved issues, corrective actions, and responsible parties. Integration status updates will be included in regular progress meetings and project reporting to provide City staff with clear visibility into testing progress, outstanding issues, and readiness for final acceptance.

Through proactive coordination, documentation, testing oversight, and issue resolution, Willdan will help ensure the City receives a fully operational AMI system that is successfully integrated with the City’s business systems and ready for long-term operation.

Specific Tasks Required from City Staff
Willdan’s project delivery approach is structured to minimize demands on City staff while maintaining the City’s control of project decisions, policy matters, budget approvals, and overall project direction. Our goal is to function as an extension of City staff by assuming responsibility for the day-to-day management, inspection, coordination, documentation, and administration activities required to successfully deliver the project.

Willdan anticipates requiring the following support and participation from City staff throughout the project:

Project Oversight and Decision Making
§ Designate a primary City Project Manager to serve as the City's representative § Provide direction regarding project priorities, operational constraints, and City objectives § Review and approve recommendations involving change orders, claims, contract modifications, and major project decisions in a timely manner
§ Participate in key project meetings and provide timely decisions when City direction is required Information Provision and Technical Support from City
§ Provide Willdan with access to the VPM system at no cost § Provide existing project documentation and background information § Identify responsible City staff for various technical areas § Facilitate access to project sites
§ Coordinate with other City departments as needed
§ Respond to consultant requests for direction or clarification in a timely manner.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 519 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
17 AMI and Utility Operations Coordination
§ Coordinate with Willdan, the Contractor, Badger Meter representatives, Tyler Technologies representatives, and other City departments regarding operational requirements associated with the AMI implementation
§ Provide existing meter account information, billing system information, and utility operational procedures as needed to support integration activities
§ Review and approve business process modifications associated with implementation of the AMI system Project Documentation and Records
§ Provide available utility records, GIS information, account information, meter inventories, and other project-related data
§ Review consultant recommendations and project reports § Coordinate internal City reviews when required
Public Agency Coordination
§ Provide support for issues requiring City authority, including customer complaints, service interruption concerns, or operational issues that require City involvement § Coordinate communication with elected officials or other City departments when necessary Project Acceptance
§ Participate in substantial completion and final completion inspections with the Willdan Team § Review closeout documentation and approve final acceptance of the project Scope of Work Satisfaction
Willdan will be responsible for managing and administering the day-to-day activities necessary to satisfy the Scope of Work and successfully deliver the project, including:

Construction Management
§ Lead and document pre-construction and progress meetings § Administer construction contracts and project documentation § Coordinate activities among the City, Contractor, Design Engineer, AMI vendor, Tyler Technologies, utility providers, and testing laboratories
§ Monitor contractor performance and schedule compliance Inspection and Quality Assurance
§ Serve as the City’s representative in the field
§ Provide full-time field inspection services
§ Maintain daily inspection reports and project records § Verify compliance with plans, specifications, permits, and City standards § Monitor traffic control, pedestrian access, public safety, and erosion control measures § Observe meter installation, testing, and commissioning activities Schedule and Cost Control
§ Review baseline schedules and schedule updates
§ Prepare and manage Weekly Statements of Working Days
§ Monitor installation production rates and project progress § Review contractor payment applications
§ Review and evaluate change order requests and potential claims § Provide recommendations regarding contract modifications and schedule impacts AMI Integration and Data Validation
§ Coordinate AMI implementation activities among the Contractor, Badger Meter, Tyler Technologies, Design Engineer, and City staff
§ Monitor meter replacement documentation and account reconciliation activities Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 520 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
18 § Verify recording of existing meter information, final readings, new meter serial numbers, endpoint identifiers, and account assignments
§ Monitor integration testing, commissioning activities, and data validation efforts § Track and assist with resolution of integration-related issues and discrepancies Public Outreach and Property Owner Coordination
§ Monitor contractor compliance with public notification requirements § Assist in resolving issues involving service interruptions, property access, and customer concerns § Document and track public inquiries and project-related complaints through resolution Labor Compliance and Materials Testing
§ Monitor prevailing wage compliance requirements
§ Review certified payroll submissions and maintain labor compliance records § Coordinate materials testing and special inspection services § Review testing results and monitor corrective actions when deficiencies are identified Project Closeout
§ Conduct substantial completion and final completion inspections § Prepare and track punch list items
§ Verify completion of commissioning and integration requirements § Review closeout documentation, warranties, testing records, and project files § Provide recommendations regarding project acceptance
Collaborative Approach to Project Delivery. Our Project Manager and team members will work as an extension of City staff, optimizing communication between the City and consultant team. Willdan emphasizes open communication through regular correspondence, teleconference discussions, and meetings with City staff to obtain direction on issues that may arise and keep City staff apprised of project status. Emails and teleconferences will be utilized whenever possible and appropriate to minimize City staff time spent in meetings.

Mitigation Methods and Practices
Cost and Change Management Controls. Willdan will implement structured cost controls to monitor contract expenditures and evaluate potential changes in scope. Controls include:
§ Monthly review of contractor payment applications
§ Verification of installed quantities
§ Independent review of change order requests
§ Force account documentation and verification
§ Assessment of schedule impacts associated with proposed changes § Tracking of allowance expenditures and contingency usage Recommendations will be provided to the City regarding change order justification, cost reasonableness, and potential budget impacts.

Schedule Controls. Willdan’s in-house Scheduler will review and approve the Contractor’s baseline schedule and monitor monthly updates throughout construction. Schedule controls will include:
§ Review of baseline CPM schedule logic and sequencing
§ Weekly review of installation progress and production rates § Review of three-week look-ahead schedules
§ Evaluation of schedule updates and recovery plans
§ Tracking of working days and preparation of Weekly Statements of Working Days (WSWD) § Identification and documentation of potential schedule impacts and delays Progress will be measured against planned installation quantities, project milestones, AMI commissioning activities, and substantial completion requirements. Potential delays will be identified early and corrective actions discussed with the Contractor before impacts become critical.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 521 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
19 Quality Assurance and Inspection Controls. Willdan's construction inspectors offer reliable service, quality workmanship, use of good judgment, fair and equitable treatment, and adherence to corporate integrity. These experienced team members identify and correct discrepancies, ambiguities, omissions, or conflicts in plans, specifications, and bid schedules that might generate misinterpretation or lead to agency and contractor disagreements. The professionals are adept at anticipating issues before they arise through continual review of project plans, specifications, contractors' schedules, and contract documents. Potential problems are brought to the attention of the City's Project Manager and the contractor, along with constructive recommendations for solutions, so that costly delays and negative impacts to the public and the project are avoided.

Willdan will provide full-time inspection services to verify that work is completed in accordance with the plans, specifications, manufacturer requirements, City standards, and approved submittals. Quality controls will include:
§ Daily field observation and reporting
§ Site-specific inspection checklists
§ Verification of meter installations and appurtenances § Verification of meter box, lid, and valve replacement work § Observation of bucket testing and functional verification procedures § Verification of AMI endpoint activation and communication testing § Review of materials certifications and testing documentation § Tracking and resolution of deficiencies through punch lists and corrective action logs All deficiencies will be documented, assigned to responsible parties, and tracked through resolution before acceptance.

Documentation and Record Controls. Willdan will utilize Virtual Project Manager (VPM) as the primary project management platform in accordance with City requirements. VPM will be used to manage:
§ RFIs
§ Submittals
§ Daily inspection reports
§ Progress photographs
§ Change orders
§ Meeting minutes
§ Working day statements
§ Quantity tracking
§ Payment documentation
Our team will maintain complete project records throughout construction to support project transparency, claims avoidance, audit readiness, and efficient project closeout.

AMI Integration and Data Management Controls. A critical component of our methodology is oversight of the AMI implementation and integration process. Willdan will leverage our experience rolling out AMI programs for other public agencies to coordinate with the Contractor, Badger Meter representatives, Tyler Technologies, and City staff to monitor meter programming, endpoint activation, system testing, commissioning, data validation, and billing system integration activities. We will verify that installation documentation is complete, meter and endpoint information is correctly associated with customer accounts, and identified deficiencies are corrected prior to acceptance. Because this project includes implementation of a new AMI system and integration with the City’s Tyler New World billing platform, Willdan will apply additional controls to ensure accurate data migration and successful commissioning.

These controls include:
§ Verification of existing meter serial numbers and final readings § Verification of new meter serial numbers and endpoint identifiers § Review of meter replacement documentation forms
§ Validation of meter-to-account assignments
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 522 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
20 § Monitoring of endpoint activation and communication testing § Review of integration testing and commissioning activities § Tracking and resolution of data discrepancies and communication failures These procedures help ensure accurate customer billing records, successful data transfer into the AMI platform, and reliable operation of the City’s new metering system.

Experience with Internet Based Construction
Management Systems: Virtual Project Manager
Willdan’s in-house construction management software directly aligns with the City’s specified software. Willdan has had an account with Virtual Project Manager since 2022 and we utilize the software for all of the CIP projects which we manage or inspect, unless our clients requests that an alternative software be utilized. Willdan currently uses VPM on more than 50 active projects and has completed more than 150 projects utilizing the platform. Having used the software for over 200 projects, we are very familiar and experienced with all portals within VPM, including daily logs, documents, RFIs, submittals, payments, change orders, transmittals, utility, and punch list. In fact, Virtual Project Manager recently named Willdan it’s customer of the month on LinkedIn.

Innovative and Creative Approaches
Willdan will apply practical, proven tools and procedures to maximize efficiency, control costs, maintain schedule, and improve project performance.

Additional Capabilities
Willdan can bring specialized AMI advisory capabilities through its consulting partners — including formal business-process re-engineering (current- to future-state design with post-go-live process audits), AMI datamanagement governance and staff coaching, and a water loss monitoring dashboard aligned to State Water Resources Control Board (SWRCB) water loss reporting requirements. These can be scoped as added tasks if the City sees value.

AMI Data Validation and Billing Continuity Reviews
Willdan will implement a meter replacement reconciliation review process that includes verification of existing meter serial numbers, final meter readings, new meter serial numbers, endpoint identifiers, service addresses, and customer account information. Our team will periodically review installation records and exception reports to identify discrepancies before they impact customer billing or system integration activities.

Production Dashboard Tracking
Willdan will develop a production tracking dashboard utilizing information from contractor reports, VPM records, and field observations. The dashboard will track completed meter installations, remaining quantities, daily production rates, route completion status, rejected installations, punch list items, and AMI commissioning activities. This allows potential schedule concerns to be identified early and corrective action implemented before project milestones are impacted.

Early Closeout Program
Rather than waiting until the end of construction, Willdan will implement an Early Closeout Program that continuously tracks punch list items, warranty documentation, testing records, meter replacement forms, AMI commissioning records, and project documentation throughout construction. This approach reduces the likelihood of delays between substantial completion and final acceptance.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 523 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
21 Turnkey Design-Build Solutions for Future Phases
Since this is Phase 1 of a multi-phase program, replacing just about 25% of the City’s total water meters, Willdan would like to make the City aware that there may be alternative ways to procure and fund future phases of this type of water meter replacement projects. California General Code Section 4217 allows public agencies to enter into Energy Savings Performance Contracts (ESPCs) with an Energy Service Company (ESCO), which guarantees cost savings from efficiency improvements. Those guaranteed savings are used by a lender to underwrite leasepurchase financing, often structured to be cash-flow positive (self-funding). This setup essentially allows the public agency to reallocate CIP funds to other needs. Willdan has provided this type of turnkey design-built programs for numerous public agencies in California and would be happy to discuss the suitability and feasibility of this approach for future City projects.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 524 of 616 ends

City of Turlock
#2026-RFP-021
Construction Management Services for System
Wide AMI and Water Meter Installation Staffing
4 Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 525 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
22 4.4. Staffing
Below is a list of individuals who will be working on this project, their relevant experience, the functions that each will perform, and the anticipated hours of service of each individual. Full resumes can be found in the appendix.

Mike Bustos, PE, ENV SP – Principal-in-Charge/Project Manager (96 hours total, 4 hrs/week during construction)
Mike Bustos currently serves as Deputy Director of Willdan's Construction Services Group, which encompasses construction management, geotechnical/materials testing, and labor compliance services. He brings 25 years of professional experience and holds a California Professional Engineer license (No. 73173) and is an Envision Sustainability Professional (No. 2696).

Mike is responsible for construction management, analysis, design, and plan review of roadway reconstructions, drainage, water and sewer pipelines, pavement rehabilitation, and street projects including traffic signal, landscaping, irrigation, grading, and ADA improvements. He has served as Resident Engineer for over a dozen federally and state-funded projects over the last five years and as a Construction Manager or Resident Engineer for 150+ public works projects for various agencies throughout California with projects totaling over $250 million in construction costs.

Arne Cvek – Construction Manager
(316 hours total, 12 hrs/week during construction)
Arne will serve as Construction Manager with 20+ years of professional experience in the field of full lifecycle construction management/project management. Mr. Cvek has recent relevant experience serving as Construction Manager for the City of South Gate’s Phase 3 and Phase 5 Automatic Meter Reading (AMR) Upgrade Projects. He manages cost, scope, schedules, and quality of projects, coordinates testing and sampling of construction materials, and ensures safety and environmental compliance by monitoring and enforcing applicable regulations. He is specifically skilled at managing contractors, equipment, personnel, and resources to maximize productivity.

Scott Griffith, LEED GA – AMI Integration Specialist
(200 hours total)
Scott serves as the AMI Integration Specialist for the project and has over 35 years of experience bringing innovative solutions to water conservation, helping municipalities preserve infrastructure and support critical water savings initiatives and policies unique to California. Scott brings experience in over 100+ water utility projects, delivering innovative water conservation and smart utility solutions to municipalities across the western U.S., with a focus on California’s regulatory and infrastructure environment. Scott has supported system optimization and AMI deployments for numerous California agencies including Chino, Dublin San Ramon Services District, Elsinore Valley MWD, and Padre Dam MWD – integrating SCADA, AMI, GIS, and billing platforms to enhance performance and revenue - and has delivered largescale ESPC and AMI programs in Roswell, NM and Silver City, NM resulting in millions in nonrevenue water recovery and operational savings across ~30,000 accounts. Scott utilizes state of the art data analytics to help improve water systems performance; optimizing AMR to AMI transitions, implementing SMART SCADA and integrating the billing systems to enhance customer experience and drive maximum revenue recovery.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 526 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
23 Simon Hernandez – Construction Inspector
(840 hours total, 8 hrs/day during construction)
Simon serves as Inspector for this project and is a Senior Public Works Observer with 28 years of construction and inspection experience. He has coursework in Technology for Public Works from Saddleback Community College and holds certifications including E-Rail, Roadway Workers, CIC, Fall Protection, Rubberized Asphalt Plant Inspection, OSHA Trenching and Excavations, First Aid/CPR, Competent Person, and Traffic Control for Safer Work Zones.

He is also a former certified water distribution operator (Grade 2) with experience working directly for multiple public water agencies prior to joining Willdan.

Mr. Hernandez has extensive experience in water operations, pavement rehabilitation, concrete structures, and materials testing. His relevant work includes inspection for the City of South Gate’s Phase 3 Automatic Meter Reading (AMR) Upgrade Project, as well as various water distribution main replacement projects in Downey and new water main installations that Cities of Santa Paula and Fillmore, each of which involved AMR based water meters. His responsibilities include daily field inspection, traffic control, and coordination with the Construction Manager.

Marti Martin – Construction Inspector (Alternate)
(0 hours total, 8 hrs/day during construction if needed as alternate inspector) Marti serves as an Alternate Inspector for this project and has over 30 years of increasingly responsible experience providing construction oversight & inspection for a variety of infrastructure projects involving public works, water/wastewater, and civil engineering improvements. He regularly serves as an onsite agency, owner & contractor liaison. Marti has an ability to anticipate potential construction dimensional/applicability issues and is proactive in providing timely resolution to mitigate negative impacts to the project. He is experienced in construction schedule review/updates, general construction logic, addressing potential conflicts, and monitoring adherence to safety, quality, and ethical standards in accordance with owner/stakeholder policies. His responsibilities include daily field inspection, traffic control, and coordination with the Construction Manager.

Heleo Espinoza – Construction Inspector (Alternate)
(0 hours total, 8 hrs/day during construction if needed as alternate inspector) Heleo serves as an Alternate Inspector for this project and has 40+ years of experience in Public Works, with strong leadership qualities and the ability to manage projects successfully. He possesses exceptional decision-making capabilities and is meticulous in ensuring project specifications are compliant with contracts and requirements. He holds State Certifications in Water Treatment (Grade 1) and Water Distribution (Grade 2). Mr.

Espinoza has outstanding customer service skills dealing with clients and contractors and is well organized, with excellent time management abilities, to complete projects on time and within budget. He has provided construction inspection for numerous water infrastructure projects involving water meter installations. His responsibilities will include daily field inspection of pipe bursting operations, water main installations, valve and hydrant assemblies, trenching and backfill, traffic control, and coordination with the Construction Manager.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 527 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
24 Manny Trujillo – Construction Inspector (Alternate)
(0 hours total, 8 hrs/day during construction if needed as alternate inspector) Manny serves as an Alternate Inspector for this project and has 35+ years of experience in the water utility industry, with multifaceted field experience in water distribution, inventory control, water supply, and construction inspection. He holds State Certifications in Water Distribution (Grade 3) and Water Treatment (Grade 3) and has over 30 years of public agency utility experience working directly for a public water agency. Mr. Trujillo is committed, efficient, and has a high-quality standard. He has provided construction inspection for Phase 3 and Phase 5 of the Automatic Meter Reading (AMR) Upgrade Project for the City of South Gate, which include installation of ¾”, 1”, 1-1/2”, and 2” Badger Meter Recordall Disc water meters. His responsibilities include daily field inspection, traffic control, and coordination with the Construction Manager.

Jane Freij – Labor Compliance Manager
(80 hours total, 4 hrs/week during construction)
Jane will be responsible for the delivery of the requested labor compliance services. She is an experienced Labor Compliance Officer and Project Manager with a proven track record in profitability achieved through comprehensive and effective management of time and budget. Jane provides oversight of labor compliance monitoring services for local, state, county, and federally funded projects. Jane is responsible for ensuring the City’s projects will be sufficiently staffed in the appropriate numbers to ensure Willdan’s excellent performance of the City’s scope of work for the duration of this contract.

Manuel Guzman, PE – Supervising Engineer, Material Testing (16 hours total, 1.25 hrs/week during construction)
Manuel is a Supervising Engineer with extensive experience in geotechnical engineering design and construction phase services for both federal and non-federal clients. He has over a decade of experience supporting complex infrastructure projects, including transportation, rail, water resources, energy facilities, and military facilities. Manuel has expertise in shallow and deep foundation design, retaining wall design, pavement design, and geotechnical investigations. He is experienced in leading field exploration programs, preparing geotechnical reports, and providing construction quality assurance. His background also includes dam safety modifications, levee inspections, and emergency response efforts in compliance with FEMA guidelines.

John Borquez – Schedule Reviewer
(25 hours total, 2 hrs/month during construction)
John serves as the Schedule Reviewer and is a Civil Engineer with over 25 years of specialized experience in Critical Path Method (CPM) scheduling across utility, transportation, infrastructure, power, and industrial construction sectors. He is highly skilled in applying AACE International’s recommended practices for project planning, data validation, and forensic schedule analysis, ensuring accurate, defensible results. John has extensive expertise in construction claims, change management, and time impact analysis. He has been formally recognized by the courts as an expert in CPM scheduling and has provided expert testimony in arbitration proceedings, demonstrating his ability to translate complex technical issues into clear, actionable findings.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 528 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
25 Team Consistency and Personnel Change Management
Willdan Engineering is committed to maintaining team consistency throughout the life of the City of Turlock's AMI and Water Meter Installation project. The proposed team members have confirmed their availability for the duration of this project and will remain assigned except in cases of termination of employment or if required by the City due to failure to perform the scope of the contract.

Staffing Stability and Resource Management. Willdan's staffing approach focuses on assembling dedicated teams with confirmed availability and appropriate workload capacity to ensure consistency throughout the project lifecycle. The project management philosophy revolves around early and frequent communication with project team members, including City staff, subconsultants, and project stakeholders. The most effective management tool utilized is open and documented communication, especially when meeting project deadlines.

Personnel Change Protocol. In the event that a team member's employment with Willdan is terminated or if the City determines that a personnel change is necessary due to failure to perform the scope of the contract, Willdan will implement the following process:

Immediate Notification. Willdan will notify the City immediately upon becoming aware of any circumstance that may necessitate a personnel change, providing full transparency regarding the reason for the change and the proposed timeline for transition.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 529 of 616 ends

City of Turlock
#2026-RFP-021
Construction Management Services for System
Wide AMI and Water Meter Installation
Similar Projects
5 Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 530 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
26 4.5. Similar Projects
We have included a list of three (3) municipal/public agency references for similar services provided by Willdan.

Automatic Water Meter (AMR) Upgrade Phase III, 649-WTR
Client Name City of South Gate
Project Description The $1.3 million project included
removing and replacing approximately
1,725 ¾”, 1”, 1-1/2”, and 2” existing
water maters in Route C-1 of the City of
South Gate Water distribution system
with new Automatic Meter Reading
(AMR) based water meters to allow the
City to automate the meter reading
process using a handheld device,
reducing the time spent on meter
readings. Th e Project also included replacing and connecting piping and the valve on the customer side connection as needed. Willdan’s services included construction management, inspection, and lab or compliance.

Project Start and End Dates August 2024 – February 2025 Client Project Manager
Name, Telephone Number,
and E-mail address
Derwin Dy
323.563.5769
[email protected]
Automatic Water Meter (AMR) Upgrade Phase V, 740-WTR
Client Name City of South Gate
Project Description The $1.6 million project includes the removal and replacement of existing water
meters. The removal and replacement of
aging water meters will be approximately
for 1,659 water meters of ¾ “, 1”, 1-½”, 2”,
and 4” in Route C-4 for the City of South
Gate’s Water distribution system with new
automatic reading (AMR) and Advanced
Metering Infrastructure (AMI) based water
meters. The proposed work will also i
nclude replacing and connecting piping and
customer side valve as needed.

Project Start and End Dates May 2026 – September 2026 (Projected) Client Project Manager
Name, Telephone Number,
and E-mail address
Derwin Dy
323.563.5769
[email protected]
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 531 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
27 CIP 20-23 Third Street Water System Improvements
Client Name City of Downey
Project Description Willdan provided construction management, inspection, and material testing services for this water main
replacement project in a residential area on Third Street between Old River School Rd and Rives Avenue. The
project involved the installation of new potable water
ductile iron pipe, gate valves, tees, bends, thrust blocks and appurtenant fittings; installation of new fire hydrant assemblies, water service lines, AMR meters, and boxes; abandonment of existing water mains, service lines, and associated facilities; trenching, backfill, and compacting; asphalt concrete (AC) and Portland cement concrete (PCC) pavement reconstruction; reconstruction of miscellaneous PCC improvements; and other appurtenant work.

This Project demonstrates Willdan’s capability to provide construction management, inspection, and materials testing on a water pipeline replacement project on narrow residential streets, including management of service transfers.

Project Start and End Dates August 2020 – November 2020 Client Project Manager
Name, Telephone Number,
and E-mail address
Daniel Mueller
562.904.7110
[email protected]
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 532 of 616 ends

City of Turlock
#2026-RFP-021
Construction Management Services for System
Wide AMI and Water Meter Installation
Fee Proposal
6 Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 533 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
28 4.6. Labor and Fee Estimate
The following sections have been submitted as a separate attachment in “6. Fee Proposal,” as requested on OpenGov.

A. Labor Estimate
B. Fee Estimate
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 534 of 616 ends

City of Turlock
#2026-RFP-021
Construction Management Services for System
Wide AMI and Water Meter Installation
Qualified Local
Vendor Information
7 Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 535 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
29 7. Qualified Local Vendor Information
N/A – Willdan is not a Qualified Local Vendor
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 536 of 616 ends

City of Turlock
#2026-RFP-021
Construction Management Services for System
Wide AMI and Water Meter Installation
Conflict of Interest
Statement
8 Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 537 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
30 8. Conflict of Interest Statement
Willdan certifies and affirms that with respect to the procurement of Construction Management Services for System Wide AMI and Water Meter Installation - Phase 1 Project:

A. Neither Willdan nor any of its owners, officers, directors, employees, or agents has any personal, financial, or organizational interest that would conflict, or appear to conflict, with the fair and impartial execution of responsibilities in connection with this procurement.

B. Willdan has not offered, given, or promised anything of value—such as gifts, favors, or financial incentives—to any City official, employee, or representative involved in the procurement process.

C. Willdan has not been involved in drafting, evaluating, or developing specifications, requirements, or other procurement-related documents for this solicitation in a manner that would provide an unfair competitive advantage.

D. If any actual or potential conflict of interest exists, Willdan has fully disclosed such conflicts in an attached statement, including steps taken to mitigate any potential bias or undue influence. If any conflict of interest arises at any stage before or after the award of the contract, Willdan will notify the City in writing.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 538 of 616 ends

City of Turlock
#2026-RFP-021
Construction Management Services for System
Wide AMI and Water Meter Installation
City of Turlock Business
License Number
9 Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 539 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
31 9. City of Turlock Business License Number
Willdan’s City of Turlock Business License Number is 503353 and is scheduled to renew at the end of June 2026 Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 540 of 616 ends

City of Turlock
#2026-RFP-021
Construction Management Services for System
Wide AMI and Water Meter Installation
SAM.gov
10 Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 541 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
32 10. SAM.gov
Willdan’s Unique Identity Number is VUFLJX1FNUG1
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 542 of 616 ends

City of Turlock
#2026-RFP-021
Construction Management Services for System
Wide AMI and Water Meter Installation
Terms of the Sample
Agreement
11 Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 543 of 616 ends

Construction Management Services for System Wide
AMI and Water Meter Installation
Second Line
33 11. Terms of the Sample Agreement
Willdan acknowledges and accepts the terms of the sample agreement.

Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 544 of 616 ends

City of Turlock
#2026-RFP-021
Construction Management Services for System
Wide AMI and Water Meter Installation
Resumes
Appendix
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 545 of 616 ends

35 Mike Bustos, PE, ENV SP
Deputy Director of Construction Services
Project Manager/Principal In Charge
Mike Bustos currently serves as Deputy Director of Willdan’s Construction Management and Inspection Group, which also encompasses geotechnical/materials testing, and labor compliance services. He is responsible for construction management, analysis, design, and plan review of roadway reconstructions; drainage; water and sewer pipelines; pavement rehabilitation; and street projects including traffic signal, landscaping, irrigation, grading, and American with Disabilities Act (ADA) improvements. He has served as Resident Engineer for over a dozen federally and state-funded projects over the last five years and also as a Construction Manager or Resident Engineer for 150+ public works projects for various agencies throughout California with projects totaling $300M+ on construction costs. Through his unique experience and vantage point of serving as a Design Engineer, Project Engineer, Project Manager, Resident Engineer, and Construction Manager, Mike has developed an expertise in public infrastructure planning, design, award, funding, and construction; he understands the varying unknowns project construction can present; and he tackles those unknowns by working with contractors, City staff, and other stakeholders to resolve challenges. He is also currently serving as Project Manager for the City’s FY 2025 Wastewater Main Rehabilitation project, which Willdan is providing inspection services for.

Relevant Project Experience
Automatic Water Meter (AMR) Upgrade – Phase 5, Project No. 740-WTR, City of South Gate, CA. Resident Engineer. The $1.6 million project includes the removal and replacement of existing water meters. The removal and replacement of aging water meters will be approximately for 1,659 water meters of ¾ “, 1”, 1-½”, 2”, and 4” in Route C-4 for the City of South Gate’s Water distribution system with new automatic reading (AMR) and Advanced Metering Infrastructure (AMI) based water meters. The proposed work will also include replacing and connecting piping and customer side valve as needed.

Automatic Water Meter (AMR) Upgrade – Phase 3, Project No. 649-WTR, City of South Gate, CA. Resident Engineer. The $1.3 million project included removing and replacing approximately 1,725 ¾”, 1”, 1-1/2”, and 2” existing water maters in Route C-1 of the City of South Gate Water distribution system with new Automatic Meter Reading (AMR) based water meters. The Project also included replacing and connecting piping and the valve on the customer side connection as needed. Willdan’s services included construction management, inspection, and labor compliance.

CIP 20-23 Third Street Water Improvements, City of Downey, CA. Public Works Inspector.

The project involved the installation of 3,000 LF of new potable water ductile iron pipe, gate valves, tees, bends, thrust blocks; installation of new fire hydrant assemblies, water service lines, meters, and boxes; and other appurtenant work on Third Street between River Ave and Old River School Road.

Water Main Replacement Project – Phase 1, City Project No. 689-WTR, City of South Gate, CA. Project Manager/Resident Engineer. Responsible for oversight of Willdan’s construction management, inspection, labor compliance, and material testing services for this water main replacement project. The project includes the installation of approximately 6,150 LF of new 8” and 12” ductile iron water mains, removal and replacement of water services, fire hydrants, water meters, and isolation valves. Services being provided include contract administration, construction observation/inspection, concrete testing, utility coordination, labor compliance, traffic engineering support, geotechnical and material testing services, and project close-out services.

EDUCATION
BS, Civil Engineering
(Magna Cum Laude),
California Polytechnic State
University, San Luis Obispo
Caltrans Resident Engineer
Academy

PROFESSIONAL

CERTIFICATIONS
Civil Engineer, California No.
73173
Envision Sustainability
Professional, Institute for
Sustainable Infrastructure
No. 2696
25 YEARS OF EXPERIENCE
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 546 of 616 ends

36 East Area 1 – Harvest at Limoneira Public Utility Improvements, City of Santa Paula, CA.

Project Manager. Willdan provided plan checking, construction management, and inspection services for the public utility improvements being constructed as part of the Harvest at Limoneria subdivision development in the City of Santa Paula. Willdan provides inspection and responds to submittals and RFIs on behalf of the City for all public improvements, including mass grading, rough grading, lot grading, utility infrastructure, flood control and drainage features, parks, street improvements, traffic signals, and landscaping. The public utility improvements constructed to date include a new groundwater well (with iron and manganese treatment filtration system), one converted irrigation well, a booster pump station, a 3MG reservoir, two 736,000 gallon water tanks, 17,000 LF of water distribution pipeline, 2,000 LF of water transmission main, and 508 new water meters.

CIP 20-23 Third Street Water Improvements, City of Downey, CA. Construction Manager.

The project involved the installation of 3,000 LF of new potable water ductile iron pipe, gate valves, tees, bends, thrust blocks; installation of new fire hydrant assemblies, water service lines, meters, and boxes; and other appurtenant work on Third Street between River Ave and Old River School Road.

Heritage Valley Parks Tract 5520 Public Improvements, City of Fillmore, CA. Project Manager. Willdan provided project management, plan checking, and public works inspection services for this developer-built project associated with the Heritage Valley Parks Tract 5520 development, which included for the public offsite and onsite improvements, as well as Pole Creek Bridge, including observation of rough grading, drainage improvements, wet utilities, curb, gutter, and sidewalks, and paving. The onsite improvements included rough grading, drainage improvements, wet utilities (potable water, recycled water, and sewer), curb, gutter, sidewalks, and paving. The potable water improvements included approximately 20,000 LF of 8" PVC, 2,535 of 12" PVC, 3,250 LF 8" DIP, 461 water services, and 65 fire hydrant assemblies.

Phase 1 Watermain Replacement Project, City of South Gate, CA. Project Manager. Willdan provided construction management, inspection, material testing, and labor compliance services for this water mainline replacement project which included the installation of 6,150 LF of new 8” and 12” ductile iron water main, removal and replacement of water laterals, fire hydrants, water meters, blowoffs and air vacs, and isolation valves. The Project involved work on Tweedy Blvd, State Street, Elizabeth Street, and four residential streets.

Westside Water and Sewer Main Replacement Program Phase 1, City of South Gate, CA.

Construction Manager. Responsible for overseeing contract administration, construction management, materials testing, and public works observation for this groundwater treatment project. Willdan provided construction management and public works observation services for the City's water and sewer main replacement project. The project included replacement of 1,000 lineal feet of 12-inch DIP, 17,600 lineal feet of 8-inch DIP, and 950 lineal feet of 6-inch DIP water mains, and 450 lineal feet of 12-inch VCP and 1,700 lineal feet of 10-inch VCP sewer mains. Existing water mains were abandoned in place, while the existing sewer mains were removed from the trench and new mains installed in the same alignment.

Mike Bustos
Continued
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 547 of 616 ends

37 Arne Cvek
Construction Manager
Mr. Arne Cvek possesses 20 years of professional experience in the field of full lifecycle construction management/project management. He is proficient in leading and managing projects and executing extensive scopes of work on strict deadlines. He is adept at communicating effectively and developing working relationships across diverse populations, while working toward a common goal of delivering quality projects within established timeframes and budget. He is specifically skilled at managing contractors, equipment, personnel, and resources to maximize productivity. He ensures excellent communication with contractors regarding construction obligations and legal requirements across multiple trades, and he is especially adept at maintaining excellent quality control of construction projects.

Relevant Experience
Automatic Water Meter (AMR) Upgrade – Phase 5, Project No. 740-WTR, City of South Gate, CA. Construction Manager. The $1.6 million project includes the removal and replacement of existing water meters. The removal and replacement of aging water meters will be approximately for 1,659 water meters of ¾ “, 1”, 1-½”, 2”, and 4” in Route C4 for the City of South Gate’s Water distribution system with new automatic reading (AMR) and Advanced Metering Infrastructure (AMI) based water meters. The proposed work will also include replacing and connecting piping and customer side valve as needed.

Automatic Water Meter (AMR) Upgrade – Phase 3, Project No. 649-WTR, City of South Gate, CA. Construction Manager. The $1.3 million project included removing and replacing approximately 1,725 ¾”, 1”, 1-1/2”, and 2” existing water maters in Route C-1 of the City of South Gate Water distribution system with new Automatic Meter Reading (AMR) based water meters. The Project also included replacing and connecting piping and the valve on the customer side connection as needed. Mr. Cvek managed contractor performance, quality control, and compliance with project specifications, while overseeing optional scope elements including replacement of meter boxes and lids, customer-side connectors and valves, and minor piping reconnections. Coordinated with City staff, field crews, and stakeholders to address access, service interruptions, and public communication.

Monitored budget, reviewed progress and change orders, and ensured successful implementation of advanced metering infrastructure in accordance with project goals and timelines.

Associated Road High Pressure Waterline, City of Brea, CA. Construction Manager. Mr. Cvek served as Construction Manager overseeing installation of approximately 3,963 linear feet of 12-inch steel CML&C water pipeline, including fittings, appurtenances, and system tieins. Directed contractor activities for installation of gate valves, blowoff assemblies, and air vacuum assemblies, ensuring compliance with plans, specifications, and applicable standards. He managed all phases of construction including saw cutting, trench excavation, base and asphalt concrete removal, trench bedding, backfill, compaction, slurry backfill, and pavement restoration. He also coordinated surveying, utility potholing, and implementation of BMPs, while overseeing traffic control, striping, and roadway restoration within an active public right-of-way.

EDUCATION
MS, Construction
Management, Louisiana
State University, Baton
Rouge
Post-Baccalaureate
Certificate, Construction
Management, Louisiana
State University, Baton
Rouge
BS, Molecular, Cellular and
Developmental Biology,
University of Colorado,
Boulder

PROFESSIONAL

CERTIFICATIONS
Caltrans Resident Engineer
Academy
FEMA IS-0008.a, IS00005.a, IS-00100.b, IS00200.c, IS-00320, IS00700.a 20 YEARS OF EXPERIENCE
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 548 of 616 ends

38 Scott Griffith, LEED GA
AMI Integration Specialist
Scott has over 35 years of experience bringing innovative solutions to water conservation, helping municipalities preserve infrastructure and support critical water savings initiatives and policies unique to California. Scott brings experience in over 100+ water utility projects, delivering innovative water conservation and smart utility solutions to municipalities across the western U.S., with a focus on California’s regulatory and infrastructure environment.

Scott has supported system optimization and AMI deployments for numerous California agencies including Chino, Dublin San Ramon Services District, Elsinore Valley MWD, and Padre Dam MWD – integrating SCADA, AMI, GIS, and billing platforms to enhance performance and revenue - and has delivered large-scale ESPC and AMI programs in Roswell, NM and Silver City, NM resulting in millions in non-revenue water recovery and operational savings across ~30,000 accounts. Scott utilizes state of the art data analytics to help improve water systems performance; optimizing AMR to AMI transitions, implementing SMART SCADA and integrating the billing systems to enhance customer experience and drive maximum revenue recovery.

Project Experience
City of Fillmore, CA.

Scott supported the development and implementation of a citywide Advanced Metering Infrastructure (AMI) project for Fillmore’s 4,000+ water accounts, resulting in $5M in turnkey construction and over $575K in annual savings and revenue recovery. He played a key role in designing the funding strategy, which allowed the City to deliver the project with no upfront capital contribution by leveraging TELP financing. The project modernized Fillmore’s water system with ultrasonic meters, real-time data, and a Customer Experience Portal (CEP), supporting enhanced billing accuracy and long-term water conservation.

City of Chino Hills, CA.

Scott served as a subject matter expert supporting Chino Hills with planning and strategy for water system modernization, including AMI, SCADA, and data integration efforts.

Drawing on his extensive experience with neighboring Chino, he advised the City on how to achieve operational visibility, non-revenue water reduction, and improved customer service through smart infrastructure investment. His role focused on ensuring system interoperability and aligning future upgrades with statewide water conservation and electrification policies.

City of Chino, CA.

Scott served as the project development consultant for a full water system optimization initiative, integrating SCADA, AMI, GIS, hydraulic modeling, and CMMS into one unified smart water platform. The Chino project focused on improving operational efficiency, reducing non-revenue water, and lowering energy consumption through advanced pump and distribution optimization. The platform empowered the City to extract greater value from its existing technologies, enabling real-time decision-making and measurable cost reductions across its utility operations.

Education
BA, Architecture
Georgia Institute of
Technology;
BVA – Design & Material
Sciences, Georgia State
University;
Portfolio Completion,
Parsons School of Design,
NYC;
Registrations &
Certifications
LEED Green Associate
Accreditation, U.S. Green
Building Council
35 YEARS OF EXPERIENCE
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 549 of 616 ends

39 Simon Hernandez
Main Construction Inspector
Simon Hernandez is a motivated team player with a strong background in the water operations and construction inspection areas of the private and public sectors. He has exceptional decision-making and communication skills, displays strong leadership qualities, and conveys ideas with clarity and diplomacy. He has the ability to identify and build strong collaborative relationships within any team environment, manages time and resources effectively, and is highly capable of performing and prioritizing multiple tasks. Overall description and relative experience summary. He has also served as Backup/Secondary Inspector for the City’s current FY 2025 Wastewater Main Rehabilitation project.

Relevant Project Experience
Automatic Water Meter (AMR) Upgrade – Phase 3, Project No. 649-WTR, City of South Gate, CA. Public Works Inspector. The $1.3 million project included removing and replacing approximately 1,725 ¾”, 1”, 1-1/2”, and 2” existing water maters in Route C-1 of the City of South Gate Water distribution system with new Automatic Meter Reading (AMR) based water meters. The Project also included replacing and connecting piping and the valve on the customer side connection as needed. Willdan’s services included construction management, inspection, and labor compliance.

CIP 20-23 Third Street Water Improvements, City of Downey, CA. Public Works Inspector.

The project involved the installation of 3,000 LF of new potable water ductile iron pipe, gate valves, tees, bends, thrust blocks; installation of new fire hydrant assemblies, water service lines, meters, and boxes; and other appurtenant work on Third Street between River Ave and Old River School Road. Mr. Hernandez served as the construction inspector, responsible for daily monitoring of the construction activities, ensuring compliance with the contract documents, preparing daily reports, tracking quantities, coordinating materials testing, and reporting.

East Area 1 – Harvest at Limoneira Public Utility Improvements, City of Santa Paula, CA.

Public Works Inspector. Willdan provided plan checking, construction management, and inspection services for the public utility improvements being constructed as part of the Harvest at Limoneria subdivision development in the City of Santa Paula. Willdan provides inspection and responds to submittals and RFIs on behalf of the City for all public improvements, including mass grading, rough grading, lot grading, utility infrastructure, flood control and drainage features, parks, street improvements, traffic signals, and landscaping. The public utility improvements constructed to date include a new groundwater well (with iron and manganese treatment filtration system), one converted irrigation well, a booster pump station, a 3MG reservoir, two 736,000 gallon water tanks, 17,000 LF of water distribution pipeline, 2,000 LF of water transmission main, and 508 new water meters.

Heritage Valley Parks Tract 5520 Public Improvements, City of Fillmore, CA. Public Works Inspector. Willdan provided project management, plan checking, and public works inspection services for this developer-built project associated with the Heritage Valley Parks Tract 5520 development, which included for the public offsite and onsite improvements, as well as Pole Creek Bridge, including observation of rough grading, drainage improvements, wet utilities, curb, gutter, and sidewalks, and paving. The onsite improvements included rough grading, drainage improvements, wet utilities (potable water, recycled water, and sewer), curb, gutter, sidewalks, and paving. The potable water improvements included approximately 20,000 LF of 8" PVC, 2,535 of 12" PVC, 3,250 LF 8" DIP, 461 water services, and 65 fire hydrant assemblies.
28 YEARS OF EXPERIENCE

EDUCATION
Technology Course for
Public Works, Saddleback
Community College, Orange,
California

PROFESSIONAL

CERTIFICATIONS
E-Rail certified
Roadway Workers certified
CIC certified
Fall protection certified and
trained
American Construction
Inspectors Association:

Rubberized Asphalt Plant
Inspection
Certification in Safety on Job
Sites
OSHA Certifications:

Trenching and Excavations
First Aid and CPR Certified
Competent Person Certified
Traffic Control for Safer
Work Zones Certification
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 550 of 616 ends

40 Santa Monica SP2640 Water Main Replacement Project, City of Santa Monica, CA. Public Works Inspector. Willdan provided construction management and inspection services for the Citywide replacement of water main lines project, which replaced approximately 9,600 LF of water mains, fire and domestic services, fire hydrants, service laterals and water meters.

Construction cost was approximately $6 million.

Olympic Water Transmission Main Expansion, City of Santa Monica, CA. Public Works Inspector. Willdan provided construction management and inspection services for this $5 million transmission main installation project. Improvements for the transmission main involved 265 linear feet of 12-inch and 6,620 linear feet of 16-inch ductile iron water transmission pipelines from the new Olympic Wells (SM-8, SM-9, & SM-10i) in the City of Santa Monica to the Arcadia Water Treatment Plant in the City of Los Angeles. The pipeline installations entailed valves, air vacuum valves, pump outs, casing pipe, tie ins to the new wells, and abandonment of an existing 16-inch ACP waterline.

Non-Potable Water Main Expansion Project, City of Santa Monica, CA. Public Works Inspector. The Non-Potable Water Main Expansion Project (SP2563) consists of installation of approximately 3,180 linear feet of 12” AWWA C909 PC235 PVCO water main, and appurtenances. The construction cost of this portion of the project was estimated at $1.67 million with a construction duration of 6 months. Mr. Hernandez is currently providing inspection services on this project. Daily reports and photographs are prepared in Procore.

Water Distribution Operator II, Golden State Water, City of Ojai, CA. Water System Operator. Prior to joining Willdan, Mr. Hernandez served as a Water Distribution Operator for Golden State Water. He communicated both verbally and in writing with local government officials, company management, staff, and customers. He ensured all water distribution operations and maintenance programs complied with applicable Federal, State, and local ordinances and regulations. Mr. Hernandez performed basic customer support activities involving the service, installation, modification and repair of water distribution equipment and systems. He also maintained detailed records, prepared reports, and procured materials.

Water Distribution Operator II, California Water Service Company, Westlake Village, CA.

Operator. Mr. Hernandez performed all customer service/distribution activities as assigned. He maintained detailed records, prepared reports, and procured materials; located and marked out underground utilities; investigated water leaks and repairs leaks; and responded to water distribution, production, treatment duties as assigned.

Water Distribution Operator I, City of Ventura, CA. Operator. Mr. Hernandez’s duties included the installation, maintenance, repair and replacement of water mains, service connections and fire hydrants. He assisted with repairing gate valves, mainlines and valves; cleaning, greasing and repairing mechanical equipment and tools and other equipment to ensure proper working order; operated a variety of motorized and mechanized equipment to maintain an effective water system for the City; operated loader and backhoe; interpreted provisions of municipal, state and federal laws and/or regulations pertaining to the water system; and responded to citizen's complaints and city easements regarding the water system.

Simon Hernandez
Continued
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 551 of 616 ends

41 Marti Martin
Construction Inspector (Backup)
Marti Martin has over 30-years years of increasingly responsible experience providing construction oversight & inspection for a variety of infrastructure projects involving public works, heavy and civil engineering improvements. He regularly serves as an onsite agency, owner & contractor liaison. Marti has an ability to anticipate potential construction dimensional/applicability issues and is proactive in providing timely resolution to mitigate negative impacts to the project. He is experienced in construction schedule review/updates, general construction logic, addressing potential conflicts, and monitoring adherence to safety, quality, and ethical standards in accordance with owner/stakeholder policies. Marti has also served as Main Inspector for the City’s current FY 2025 Wastewater Main Rehabilitation project.

Relevant Project Experience
Water Line Improvements Project, City of Hayward, CA. Construction Inspector. Through our on-call contract, Willdan is currently providing full-time public works inspection services for the City’s Water Line Improvements Project (City Project No. 07093) consisting of approximately 2,080 linear feet (LF) of 6-inch, 8-inch, and 12-inch earthquake resistant ductile iron pipe (ERDIP), 11,110 LF of 8-inch and 12-inch ducitle iron pipe (DIP), and 24,100 LF of 6-inch, 8-inch, and 12-inch PVC C-900 water mains, fire hydrants, water services, meters, and all appurtenances. The project also includes 489 LF of jack and bore operations and 161 LF of microtunneling operations. Pavement maintenance work after water line installation includes 150,000 square feet of microsurfacing.

Sewer Line Improvements Project, City of Hayward, CA. Construction Inspector. Willdan is currently providing public works inspection services for the City’s $11.4 million Sewer Line Improvements Project (City Project No. 07761) consisting of approximately 17,400 linear feet (LF) of 8-inch, 10-inch, 12-inch, and 15-inch sewer main by open cut method, 3,150 linear feet of 8-inch, 12-inch, and 15-inch sewer main by pipe bursting, 700 linear feet of sewer main by pipe reaming, and a 24-inch steel casing jack and bore. The project also includes service laterals, drop manholes, and manhole removal, reconstruction, and lining.

FY 2025 Wastewater Main Rehabilitation, City of Santa Barbara, CA. Main Public Works Inspector. Willdan is currently providing full-time construction inspection for the City’s 2025 Wastewater Main Rehabilitation project, which consists of rehabilitation of just over 15,000 LF of gravity sewer pipelines ranging from 6” to 15” diameter by means of cured in place pipe, including cleaning, pre- and post-lining CCTV, dye testing, and service lateral connection seal. The Project also includes lining of existing manholes, installing new internal drop inlets, re-establishing service connections, and grinding down protruding service laterals. The Project areas are at 75 locations spread throughout the city. Several of the pipe segments to be lined require implementation of a sewer bypass system.

Previous Work Experience
Public Works Inspection, City/County of San Francisco, CA. City Inspector. With a previous employer, Mr. Martin provided inspection services to the City and County of San Francisco for various projects including:
§ Castro Street - Sewer, Water, ADA, Flatwork & Roadway (Concrete & HMA Paving) § Lombard Vision Zero Project - Water, Sewer, ADA, Traffic Signals & Roadway § Polk Streetscape Project - Water, Sewer, ADA, Street Lighting, Landscaping & Roadway

EDUCATION/TRAINING
City & County San Francisco
Confined Space Entry
Training
APWA Construction &
Inspection Workshop (Parts
1 thru 8)
City & County San Francisco
Public Works Ethics Training
2022
Asbestos, Lead and Silica
Awareness Training
P6 101 Pt.#1 & Pt.#2
Training
24-Hour HAZWOPER
Training, Labor &
Occupational Health
Program
Public Works Project
Administration, APWA
SF-BRWQCB Construction
Site Compliance for Water
Quality Protection Soils
Engineering
NASTT Cured-in-Place Pipe
Lining

PROFESSIONAL

CERTIFICATIONS
OSHA 10-Hr Refresher
Course, Red Vector
Paving Inspector
Certification, Asphalt
Institute
HAZWOPER 8-Hr Refresher
Course
Concrete Field-Testing
Technician - Grade 1, ID#
01170287
Soils Nuclear Density Gauge
Certification
30+ YEARS OF EXPERIENCE
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED

Page 552 of 616 ends

42 Heleo Espinoza
Construction Inspector (Backup)
Heleo has over 40 years of experience in Public Works, with leadership qualities and the ability to manage projects. He possesses decision-making capabilities and is meticulous in ensuring project specifications are compliant with contracts and requirements. He has customer service skills dealing with clients and contractors and is well organized, with time management abilities, to complete projects on time and within budget.

Relevant Project Experience
3rd Street Water System Improvements Project, City of Downey, California. Public Works Inspector. Mr. Espinoza performed public works inspection of the 3rd Street Water System Improvements project, which consisted of installation of new water mains, valves, fittings, and appurtenances, abandoning of old undersized water main, replacement of existing fire hydrants, installation of new fire hydrants, installation of new copper water service lines, replacement of old water meters with remote-read water meters on 3rd Street from Paramount Blvd to Civic Center Drive.
4th Street Water, CIP 23-20, City of Downey, California. Public Works Observer. Willdan provided public works inspection and materials testing services for the 4th Street Water System Improvements Project which consisted of installation of new water mains, valves, fittings, and appurtenances, abandoning of old undersized water main, replacement of existing fire hydrants, installation of new fire hydrants, installation of new copper water service lines, replacement of old water meters with remote-read water meters, and completion of associated asphalt and concrete work on 4th Street from Paramount Blvd to La Reina Avenue.
5th Street Water System Improvements, CIP 21-15, City of Downey, CA. Public Works Inspector. Willdan provided construction inspection and materials testing to the City’s 5th Street Water Improvements project. The project included installation of new water mains, valves, fittings, and appurtenances, abandoning of old undersized water main, replacement of existing fire hydrants, installation of new fire hydrants, installation of new copper water service lines, replacement of old water meters with remote-read water meters, and completion of associated asphalt and concrete work on 5th Street between Downey Ave and Lakewood Blvd.

Lakewood Blvd and Firestone Blvd Water System Improvements, City of Downey, CA. Public Works Inspector. Willdan provided construction inspection and materials testing to the City’s Lakewood Blvd and Firestone Blvd Water System Improvements project. The project water main replacements, including jack and bore under railroad tracks on Lakewood Blvd at Firestone Blvd.

Phase 1 Watermain Replacement Project, City of South Gate, CA. Public Works Inspector.

Willdan provided construction management, inspection, material testing, and labor compliance services for this water mainline replacement project which included the installation of 6,150 LF of new 8” and 12” ductile iron water main, removal and replacement of water laterals, fire hydrants, water meters, blowoffs and air vacs, and isolation valves. The Project involved work on Tweedy Blvd, State Street, Elizabeth Street, and four residential streets.

PFAS Treatment System Project No. 50042, City of Pico Rivera, CA. Public Works Inspector.

Willdan provided constructability review, construction management, utility coordination, public works inspection, labor compliance, and close-out services for this project, which consisted of construction of equipment pads and installation of water treatment process

EDUCATION
Citrus College, Mount San
Antonio College, and
Rancho Santiago College
Courses in: Water Science
and Public Works involving
Traffic Control Safety,
Concrete, Asphalt, Trees,
Storm Systems
JPIA Training Courses
AWWA Training Courses
City of Santa Fe Springs
Supervisor Training Courses

PROFESSIONAL

CERTIFICATIONS
State Certified in Water
Treatment (T1)
State Certified in Water
Distribution (D2)

ASSOCIATIONS
Member of Municipal
Superintendents Association
(MSA)
40+ YEARS OF EXPERIENCE
Docusign Envelope ID: 1363B391-5437-89AA-8325-74C7BC17D2ED