GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 2 Spec. No. 24-04 document, or to visit the site and acquaint himself with conditions there existing, shall in no way relieve the bidder from any obligation with respect to his or her proposal or to the contract. The drawings for the work show conditions as they are supposed or believed by the Engineer to exist; but, it is neither intended nor shall it be inferred that the conditions as shown thereon constitute a representation by the Engineer, the City or its officers that such conditions are actually existent, nor shall the City, the Engineer or any of their officers or representatives be liable for any loss sustained by the Contractor as a result of a variance between the conditions shown on the drawings and the conditions actually revealed during the progress of the work or otherwise.

The bidder's attention is directed to the possible existence of obstructions and public improvements within the limits of the work or adjacent thereto, which may or may not be shown on the Drawings. Any bid shall take into consideration that conditions may exist underground or otherwise that are not known to the City or easily detected during a site inspection that could impact the time or cost of completing the project. The City expects the bids to anticipate such conditions so that it can know for budgeting and other purposes the total cost to complete the project before accepting a bid and undertaking the legal obligation to construct the project. In awarding the contract the City relies on the contractor’s representation that its bid anticipates differing site conditions and the additional time or cost that such conditions may necessitate.

The bidder shall investigate to his or her satisfaction the conditions to be encountered, the character, quality and quantities of work to be performed and materials to be furnished and the requirements of the Plans, Special Provisions, Standard Specifications, Standard Plans, and Contract Documents. The submission of a proposal shall be considered conclusive evidence that the bidder has made such examination and has accepted the project workplace as a safe workplace to perform the work of the Contract.

Bidder Inquiries and Questions
Inquiries and questions must be submitted in writing via email to the following designated contact person:

Myles Fisette, Purchasing Manager
Email: [email protected]
The City reserves the right to not respond to inquiries or questions submitted within 3 business days of the bid opening.

Location of the Work
All of the work to be performed is within the City of Ukiah. Project is located at:
• 225 S Orchard Avenue
• Southwest corner of Gobbi/Orchard
• 700 Block of East Gobbi St

Page 181 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 3 Spec. No. 24-04

GENERAL CONDITIONS
SECTION 1. PROPOSAL REQUIREMENTS AND GENERAL CONDITIONS 1-01. Definitions. Whenever any word or expression defined in this section, or pronoun used in its stead, occurs in these contract documents, it shall have and is mutually understood to have the meaning given:
a. "City of Ukiah" or "City" shall mean the City of Ukiah, Mendocino County, California, acting through its City Council or any other board, body, official or officials to which or to whom the power belonging to the Council shall by virtue of any act or acts, hereafter pass or be held to appertain.
b. "Engineer" shall mean the Engineer duly and officially appointed by the City to supervise and direct the work of construction under this contract, acting personally or through agents or assistants duly authorized by him, such agents or assistants acting within the scope of the particular duties entrusted to them.
c. "Inspector" shall mean the engineering or technical inspector or inspectors duly authorized or appointed by the Engineer, limited to the particular duties entrusted to him or her or them. d. "Contractor" shall mean the party entering into contract with the City of Ukiah for the performance of work covered by this contract and his or her authorized agents or legal representatives. e. "Date of signing of contract" or words equivalent thereto, shall mean the date upon which this contract, with the signature of the Contractor affixed, together with the prescribed bonds, shall be or shall have been delivered to the City or its duly authorized representatives. f. "Day" or "days", unless herein otherwise expressly defined, shall mean a calendar day or days of twenty-four hours each.
g. "The work" shall mean and include all the work specified, indicated, shown or contemplated in the contract to construct the improvement, including all alterations, amendments or extensions thereto made by contract change order or other written orders of the Engineer. h. "Contract drawings", "drawings", "plans" shall mean and include 1) all drawings or plans which may have been prepared by or on behalf of the City, as a basis for proposals, when duly signed and made a part of this contract by incorporation or reference, 2) all drawings submitted in pursuance of the terms of this contract by the successful bidder with his or her proposal and by the Contractor to the City if and when approved by the Engineer and 3) all drawings submitted by the Engineer to the Contractor during the progress of the work as provided for herein. i. Where "as shown", "as indicated", "as detailed" or words of similar import are used, it shall be understood that reference to the drawings accompanying these Special Provisions is made unless stated otherwise.

Where "as directed", "as permitted", "approved" or words of similar import are used, it shall be understood that the direction, requirements, permission, approval or acceptance of the Engineer is intended unless stated otherwise.

As used herein, "provide" or "install" shall be understood to mean "provide or install complete in place", that is, "furnish and install". "Shall" is mandatory; "may" is permissive. 1-02. Examination of Plans, Special Provisions and Site of Work. The bidder shall examine carefully the Proposal, Plans, Special Provisions, Contract forms and the site of the work contemplated therefor. It will be assumed that the bidder has investigated to his or her satisfaction the conditions to be encountered and the character, quality and requirements of all Plans, Special Provisions, Standard Specifications, and Standard Plans involved.
1-03. Proposal. Bids shall be made on the blank forms prepared by the City. All bids shall give the prices bid, both in writing and in figures and shall be signed by the bidder or his or her authorized representative, with his or

Page 182 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 4 Spec. No. 24-04 her address. If the bid is made by an individual or partner, his or her name and the post office address of his or her business or partnership, along with his or her signature or the signature of one or more partners must be shown; if made by a corporation, the bid shall show the name of the state under the laws of which the corporation is chartered, the name of the corporation and the title of the person who signs on behalf of the corporation.

Each proposal shall be enclosed in a sealed envelope, endorsed as specified in the notice to bidders. Bidders are warned against making erasures or alterations of any kind and proposals which contain omissions, erasures, conditions, alterations, additions not called for, additional proposals or irregularities of any kind may be rejected. 1-04. Withdrawal of Bids. Any bid may be withdrawn at any time prior to the hour fixed in the notice to bidders for the openings of bids, provided that a request in writing, executed by the bidder or his or her duly authorized representative, for the withdrawal of such bid is filed with the City. The withdrawal of a bid will not prejudice the right of a bidder to file a new bid.
1-05. Public Opening of Bids. Bids will be opened and read publicly at the time and place indicated in the notice to bidders. Bidders or their agents are invited to be present. 1-06. Bid Guaranty. Each bid must be accompanied by a certified check, cashier's check or bidder's bond executed by an admitted surety insurer, payable to the order of the City of Ukiah in an amount not less than 10 percent of the bid as a guarantee that the bidder will enter into a contract, if awarded the work. 1-07. Qualification of Bidders. No contractor or subcontractor may be listed on a bid proposal for a public works project (submitted on or after March 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)]. No contractor or subcontractor may be awarded a contract for public work on a public works project (awarded on or after April 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5. The prime contractor shall be responsible for posting job site notices as prescribed by regulation. This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.

Each bidder shall be licensed under the provisions of Chapter 9, Division 3 of the Business and Professions Code and shall be skilled and regularly engaged in the general class or type of work called for under this contract. A statement setting forth this experience and business standing shall be submitted by each bidder on the form provided herewith. It is the intention of the City to award a contract only to a bidder who furnishes satisfactory evidence that he or she has the requisite experience and ability and that he or she has sufficient capital, facilities and equipment to enable him or her to prosecute the work successfully and promptly within the time and in the manner agreed.

In determining the degree of responsibility to be credited to a bidder, the City may weigh evidence that the bidder or his or her personnel charged with the responsibility in the work, has performed satisfactorily other contracts of like nature and magnitude or comparable difficulty at similar rates of progress. 1-08. Disqualification of Bidders. More than one bid from an individual business, partnership, corporation or association, under the same or different names, will not be considered. Reasonable grounds for believing that any bidder is financially interested in more than one bid for the work will cause the rejection of all bids in which he or she is so interested. If there is reason to believe that collusion exists among the bidders, none of the participants in such collusion will be considered. Bids in which the prices obviously are unbalanced may be rejected. 1-09. Identification of Subcontractors. All bids shall comply with the Subletting and Subcontracting Fair Practices Act (Public Contract Code Section 4100 and following) and shall set forth:
(a) The name and the location of the place of business of each subcontractor who will perform work or labor, or render service to the prime contractor in or about the construction of the work, or to a subcontractor licensed by the State of California who, under subcontract to the prime contractor, specially fabricates and installs a portion of the work according to detailed drawings contained in the plans and Special Provisions, in an amount in excess of one-half of 1 percent of the prime contractor's total bid. (b) The portion of the work which will be done by each such subcontractor. The prime contractor shall list only one subcontractor for each such portion defined by the prime contractor in his or her bid.

Page 183 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 5 Spec. No. 24-04 1-10. General Provisions of the Standard Specifications. All provisions of the General Provisions, Sections 1 through 11, of the Standard Specifications, shall be applicable to the contract except as modified by these Special Provisions. The Standard Specifications are set forth in Section 12-06 of these Special Provisions. 1-11. Addenda. If it becomes necessary to revise any part of these plans and specifications after they have been released, the City will issue an addendum containing the revision. All addenda will be posted on the City’s website at www.cityofukiah.com/purchasing with the rest of the bid documents. Anyone who intends to submit a bid in response to this Request for Bid must check the website frequently for any posted addenda. Anyone submitting a bid will be deemed to have seen and agreed to be bound by the posted addenda. (THIS SECTION IS LEFT INTENTIONALLY BLANK)

Page 184 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 6 Spec. No. 24-04 SECTION 2. AWARD AND EXECUTION OF CONTRACT
2-01. Award of Contract. Award of the contract, if it be awarded, will be to the lowest responsible bidder whose bid complies with all the specified requirements. The award, if made, will be made within thirty (30) days after opening of the bids. The City reserves the right to reject any and all bids and to waive any irregularity in the proposal not pertaining to cost.
2-02. Return of Proposal Guaranties. All bid guaranties will be held until the contract has been fully executed, after which they will be returned upon request to the respective bidders whose bids they accompany. 2-03. Execution of Contract. The contract agreement shall be executed in duplicate by the successful bidder and returned, together with the contract bonds, insurance certificates and endorsements, within fifteen (15) days after written notice of the award of the contract. After execution by the City; one copy shall be filed with the City and one copy shall be returned to the Contractor. If the bidder fails or refuses to enter into the contract agreement within the required time, then the bid guaranty accompanying the bid shall be forfeited to the City.

SECTION 3. SCOPE AND INTENT OF CONTRACT
3-01. Effect of Inspection and Payments. Neither the inspection by the Engineer or an inspector, nor any order, measurement or approved modification, nor certificate or payment of money, nor acceptance of any part or whole of the work, nor any extension of time, nor any possession by the City or its agents, shall operate as a waiver of any provision of this contract or of any power reserved therein to the City, or of any right to damages thereunder; nor shall any breach of this contract be held to be a waiver of any subsequent breach. All remedies shall be construed as cumulative.
3-02. Effect of Extension of Time. The granting of any extension of time on account of delays which, in the judgement of the City, are avoidable delays shall in no way operate as a waiver on the part of the City of its rights under this contract.
3-03. Extra Work. If extra work orders are given in accordance with provisions of this contract, such work shall be considered a part hereof and shall be subject to each and all of its terms and requirements. 3-04. Assignment of Contract. The contract may be assigned or sublet in whole or in part only upon the written consent of the City acting through its authorized agents. Consent will not be given to any proposed assignment which would relieve the original contractor or its surety of their responsibilities under the contract nor will the Engineer consent to any assignment of a part of the work under the contract. 3-05. Subcontractors. The Contractor shall be as fully responsible for the acts and omissions of his or her subcontractors and of persons either directly or indirectly employed by them, as he or she is for the acts and omissions of persons directly employed by him.

The Contractor shall cause appropriate provisions to be inserted in all subcontracts relative to the work to bind subcontractors to the terms of this Contract which are applicable to the work of subcontractors.

Nothing contained in this contract shall be construed to create or shall be relied upon to create any contractual relationship between any subcontractor and the City and no action may be brought by any subcontractor against the City based on this contract.
3-06. Interpretation of Special Provisions and Drawings. The Special Provisions and the Contract Drawings are intended to be explanatory of each other. Any work indicated in the Contract Drawings and not in the Special Provisions, or vice versa, is to be executed as if indicated in both. In case of a discrepancy or conflict between the Technical Specifications and Contract Plans, the Technical Specifications shall govern. All work shown on the Contract Drawings, the dimensions of which are not figured, shall be accurately followed to the scale to which the drawings are made, but figured dimensions are in all cases to be followed, where given, though they differ from scaled measurements. Large scale drawings shall be followed in preference to small scale drawings.

Should it appear that the work to be done, or any of the matters relative thereto, are not sufficiently detailed or explained in these contract documents, including the contract drawings, the Contractor shall apply to the

Page 185 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 7 Spec. No. 24-04 Engineer for such further explanations as may be necessary and shall conform thereto as part of this contract, so far as may be consistent with the terms of this contract. In the event of any doubt or questions arising respecting the true meaning of the Special Provisions, reference shall be made to the Engineer and his or her decision thereon shall be final. If the Contractor believes that a clarification or interpretation justifies an increase in the contract price or contract time, the Contractor must comply with the written notice provisions of Sections 9- 05 and 10-07 of these Special Provisions. Contractor’s attention is directed to Section 12-06 of the Technical Specifications regarding the Standard Specifications and Standard Plans. 3-07. Addenda. If it becomes necessary to revise any part of these plans and specifications after they have been released, the City will issue an addendum containing the revision. All addenda will be posted on the City’s website at www.cityofukiah.com/purchasing with the rest of the bid documents. Anyone who intends to submit a bid in response to this Request for Bid must check the website frequently for any posted addenda. Anyone submitting a bid will be deemed to have seen and agreed to be bound by the posted addenda. 3-08. Liability of City Officials. No city official, nor the Engineer, nor any authorized assistant of any of them, shall be personally responsible for any liability arising under this contract. 3-09. Dispute Resolution. Claims of $375,000 or less by the Contractor that arise under this Contract are subject to the mandatory dispute resolutions provisions in Public Contract Code Sections 20104-20104.6.

SECTION 4. BONDS
4-01. Faithful Performance Bond. As a part of the execution of this contract, the Contractor shall furnish a bond of a surety company or other securities providing equivalent protection such as cash, letter of credit, or certificates of deposit, acceptable to the City, conditioned upon the faithful performance of all covenants and stipulations under this contract. The amount of the bond shall be 100 percent of the total contract price, as this sum is set forth in the agreement.
4-02. Material and Labor Bond. As a part of the execution of this contract, the Contractor shall furnish a bond of a surety company or other securities providing equivalent protection such as cash, letter of credit or certificates of deposit acceptable to the City in a sum not less than 50 percent of the total contract price, as this sum is set forth in the agreement for the payment in full of all persons, companies or corporations who perform labor upon or furnish materials to be used in the work under this contract, in accordance with the provisions of Sections 3247 through 3252 inclusive of the Civil Code of the State of California and any acts amendatory thereof.
4-03. Defective Material and Workmanship Bond. As a condition precedent to the completion of this contract, the Contractor shall furnish a bond of a surety company acceptable to the City in an amount not less than 5 percent (5%) of the final contract price, to hold good for a period of one (1) year after the completion and acceptance of the work, to protect the City against the results of defective materials, workmanship and equipment during that time. This bond shall be delivered to the City before the final payment under this contract will be made.
4-04. Notification of Surety Companies. The surety companies shall familiarize themselves with all of the conditions and provisions of this contract and they waive the right of special notification of any change or modification of this contract or of extension of time, or decreased or increased work, or of the cancellation of the contract, or of any other act or acts by the City or its authorized agents, under the terms of this contract; and failure to so notify the aforesaid surety companies of changes shall in no way relieve the surety companies of their obligation under this contract.

SECTION 5. INSURANCE REQUIREMENTS FOR CONTRACTORS
Contractor shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the work hereunder by the Contractor, his or her agents, representatives, employees or subcontractors.

Page 186 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 8 Spec. No. 24-04 5-01. Minimum Scope of Insurance
Coverage shall be at least as broad as:

1. Insurance Services Office Commercial Liability Coverage (occurrence form CG 0001).

2. Insurance Services Office form number CA 0001 (Ed. 1/87) covering Automobile Liability, code 1 (any auto).

3. Worker's Compensation insurance as required by the State of California and Employer's Liability Insurance.

4. Course of Construction insurance covering for “all risks” of loss. 5-02. Minimum Limits of Insurance
Contractor shall maintain limits no less than:

1. General Liability: $2,000,000 per occurrence for bodily injury, personal injury and property damage including operations, products and completed operations. If Commercial General Liability Insurance or other form with a general aggregate limit is used, either the general aggregate limit shall apply separately to this project/location or the general aggregate limit shall be twice the required occurrence limit.

2. Automobile Liability: $2,000,000 per accident for bodily injury and property damage.

3. Employer's Liability: $1,000,000 per accident for bodily injury and property damage. 5-03. Deductibles and Self-insured Retentions. Any deductibles or self-insured retentions must be declared to and approved by the City. At the option of the City, either: the insurer shall reduce or eliminate such deductibles or self-insured retentions as respects the City, its officers, officials, employees and volunteers; or the Contractor shall provide a financial guarantee satisfactory to the City guaranteeing payment of losses and related investigations, claim administration and defense expenses. 5-04. Other Insurance Provisions
The general liability and automobile liability policies are to contain, or be endorsed to contain, the following provisions:

1. The City, its officers, officials, employees and volunteers are to be covered as Additional Insured with respect to liability arising out of automobiles owned, leased, hired or borrowed by or on behalf of the contractor; and with respect to liability arising out of work or operations performed by or on behalf of the Contractor including materials, parts or equipment furnished in connection with such work or operations.

General liability coverage can be provided in the form of an endorsement to the Contractor's insurance, or as a separate owner's policy.

2. The workers’ compensation policy is to be endorsed with a waiver of subrogation. The insurance company, in its endorsement, agrees to waive all rights of subrogation against the City, its officers, officials, employees and volunteers for losses paid under the terms of this policy which arises from the work performed by the named insured for the City.

3. For any claims related to this project, the Contractor's insurance coverage shall be primary insurance as respects the City, its officers, officials, employees or volunteers. Any insurance or self-insurance maintained by the City, its officers, officials, employees or volunteers shall be excess of the Contractor's insurance and shall not contribute with it.

Page 187 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 9 Spec. No. 24-04

4. Each insurance policy required by this clause shall be endorsed to state that coverage shall not be canceled by either party, except after thirty (30) days' prior written notice by certified mail, return receipt requested, has been given to the City.

5. Coverage shall not extend to any indemnity coverage for the active negligence of the additional insured in any case where an agreement to indemnify the additional insured would be invalid under Subdivision (b) of Section 2782 of Civil Code.

6. Course of Construction policies shall contain the following provisions:
a.) The City shall be named as loss payee.
b.) The insurer shall waive all rights of subrogation against the City. 5-05. Acceptability of Insurers
Insurance is to be placed with insurers with a current A.M. Best's rating of no less than the following:

A++ VII A- VIII
A+ VII B++ X
A VII B+ X
5-06. Verification of Coverage. Contractor shall furnish the City with original certificates and amendatory endorsements effecting coverage required by this clause. The endorsements shall be on forms provided by the City or on other than the City's forms, provided those endorsements or policies conform to the requirements. All certificates and endorsements are to be received within 15 days from written notice of contract award, and the work shall not commence until the certificates and endorsements have been approved by the City. The City reserves the right to require complete certified copies of all required insurance policies, including endorsements affecting the coverage required by these Special Provisions at any time. 5-07. Subcontractors. Contractor shall include all subcontractors as insureds under its policies or shall furnish separate certificates and endorsements for each subcontractor. All coverages for subcontractors shall be subject to all of the requirements stated herein.

SECTION 6. RESPONSIBILITIES AND RIGHTS OF CONTRACTOR
6-01. Legal Address of Contractor. Both the address given in the proposal and the Contractor's office in the vicinity of the work are hereby designated as places to either of which drawings, samples, notices, letters or other articles or communications to the Contractor may be mailed or delivered. The delivery at either of these places of any such thing from the City or its agents to the Contractor shall be deemed sufficient service thereof upon the Contractor and the date of such service shall be the date of such delivery. The address named in the proposal may be changed at any time by notice in writing from the Contractor to the City. Nothing herein contained shall be deemed to preclude or render inoperative the service of any drawing, sample, notice, letter or other article or communication to or upon the Contractor personally. 6-02. Office of Contractor at Site. During the performance of this contract, the Contractor shall maintain a suitable office at the site of the work which shall be the headquarters of a representative authorized to receive drawings and any such thing given to the said representatives or delivered at the Contractor's office at the site of work in his or her absence shall be deemed to have been given to the Contractor. 6-03. Attention to Work. The Contractor shall give his or her personal attention to and shall supervise the work to the end that it shall be prosecuted faithfully and when he or she is not personally present on the work, he or she shall at all reasonable times be represented by a competent superintendent or foreman who shall receive and obey all instructions or orders given under this contract and who shall have full authority to execute the same and to supply materials, tools and labor without delay and who shall be the legal representative of the Contractor. The Contractor shall be liable for the faithful observance of any instructions delivered to him or her or to his or her authorized representative.

Page 188 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 10 Spec. No. 24-04 6-04. Liability of Contractor. The Contractor shall do all of the work and furnish all labor, materials, tools and appliances, except as otherwise herein expressly stipulated, necessary or proper for performing and completing the work herein required in the manner and within the time herein specified. The mention of any specific duty or liability imposed upon the Contractor shall not be construed as a limitation or restriction of any general liability or duty imposed upon the Contractor by this contract, said reference to any specific duty or liability being made herein merely for the purpose of explanation.

The right of general supervision by the City shall not make the Contractor an agent of the City and the liability of the Contractor for all damages to persons or to public or private property, arising from the Contractor's execution of the work, shall not be lessened because of such general supervision.

Until the completion and final acceptance by the City of all the work under and implied by this contract, the work shall be under the Contractor's responsible care and charge. The Contractor shall rebuild, repair, restore and make good all injuries, damages, re-erections and repairs, occasioned or rendered necessary by causes of any nature whatsoever, excepting only acts of God and none other, to all or any portions of the work, except as otherwise stipulated.

To the fullest extent permitted by law, Contractor shall indemnify and hold harmless the City and its officers, directors, agents and employees from and against all claims, damages, losses and expenses including but not limited to attorneys' fees, costs of suit, expert witness fees and expenses and fees and costs of any necessary private investigators arising out of or resulting from the performance of the work, provided that any such claim, damage, loss or expense (1) is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property, other than the work itself, including the loss of use resulting therefrom and (2) is caused in whole or in part by any act or omission of the Contractor, any subcontractor, or anyone directly or indirectly employed by any of them, or anyone for whose acts any of them may be liable, regardless of whether or not it is caused in part by a party indemnified hereunder, or by the negligence or omission of a party indemnified herein.

In any and all claims against the City or any of its agents or employees by any employee of the Contractor, any subcontractor, anyone directly or indirectly employed by any of them, or anyone for whose acts any of them may be liable, the indemnification obligation shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for the Contractor or any subcontractor under workers' or workmen's compensation acts, disability benefit acts, or other employee benefit acts. The obligation to indemnify shall extend to and include acts of the indemnified party which may be negligent or omissions which may cause negligence.

The City shall have the right to estimate the amount of such damage and to cause the City to pay the same and the amount so paid for such damage shall be deducted from the money due the Contractor under this contract; or the whole or so much of the money due or to become due the Contractor under this contract as may be considered necessary by the City, shall be retained by the City until such suits or claims for damages shall have been settled or otherwise disposed of and satisfactory evidence to that effect furnished to the City. 6-05. Protection of Persons and Property. The Contractor shall furnish such watchman, guards, fences, warning signs, walks and lights as shall be necessary and shall take all other necessary precautions to prevent damage or injury to persons or property.

All property line fences and improvements in the vicinity of the work shall be protected by the Contractor and, if they are injured or destroyed, they and any other property injured by the Contractor, his or her employees or agents, shall be restored to a condition as good as when he or she entered upon the work. 6-06. Protection of City Against Patent Claims. All fees, royalties or claims for any patented invention, article or method that may be used upon or in any manner connected with the work under this contract shall be included in the price bid for the work and the Contractor and his or her sureties shall protect and hold the City, together with all of its officers, agents, servants and employees, harmless against any and all demands made for such fees or claims brought or made on account of this contract. The Contractor shall, if requested by the Engineer, furnish acceptable proof of a proper release from all such fees or classes.

Page 189 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 11 Spec. No. 24-04 Should the Contractor, his or her agents, servants or employees, or any of them be enjoined from furnishing or using any invention, article, material or appliance supplied or required to be supplied or used under this contract, the Contractor shall promptly substitute other articles, materials or appliance, in lieu thereof, of equal efficiency, quality, finish, suitability and market value and satisfactory in all respects to the Engineer. Or, in the event that the Engineer elects, in lieu of such substitution, to have supplied and to retain and use, any such invention, article, material or appliance, as may by this contract be required to be supplied, in that event the Contractor shall pay such royalties and secure such valid licenses as may be requisite and necessary for the City, its officers, agents, servants and employees, or any of them, to use such invention, article, material or appliance without being disturbed or in any way interfered with by any proceeding in law or equity on account thereof.

Should the Contractor neglect or refuse to make the substitution promptly, or to pay such royalties and secure such licenses as may be necessary, then in that event the Engineer shall have the right to make such substitution, or the City may pay such royalties and secure such licenses and charge the cost thereof against any money due to the Contractor from the City or recover the amount thereof from him or her and his or her sureties notwithstanding final payment under this contract may have been made. 6-07. Protection of Contractor's Work Property. The Contractor shall protect his or her work, supplies and materials from damage due to the nature of the work, the action of the elements, trespassers, or any cause whatsoever under his or her control, until the completion and acceptance of the work. Neither the City nor any of its agents assumes any responsibility for collecting indemnity from any person or persons causing damage to the work of the Contractor.
6-08. Regulations and Permits. The Contractor shall secure and pay for all permits, give all notices and comply with all laws, ordinances, rules and regulations bearing on the conduct of the work as drawn and specified. If the Contractor observes that the Plans and Special Provisions are at variance therewith, he or she shall promptly notify the Engineer in writing and any necessary changes shall be adjusted as provided in the contract for changes in the work. The contractor and any subcontractors shall each secure and maintain a valid City of Ukiah Business License. The City of Ukiah will issue a no fee encroachment permit to the Contractor allowing him or her to perform work within City right of way or within City property after the Contract Documents have been executed and insurance certificates and endorsements have been approved by the City. 6-09. Construction Utilities. The Contractor shall be responsible for providing for and in behalf of his or her work under this contract, all necessary utilities, such as special connection to water supply, telephones, power lines, fences, roads, watchmen, suitable storage places, etc. 6-10. Approval of Contractor's Plans. The approval by the Engineer of any drawing or any method of work proposed by the Contractor in accordance with paragraph 8-06 shall not relieve the Contractor of any of his or her responsibility for his or her errors therein and shall not be regarded as any assumption of risk or liability by the City or any officer or employee thereof and the Contractor shall have no claim under this contract on account of the failure or partial failure or inefficiency of any plan or method so approved. Such approval shall be considered to mean merely that the Engineer has no objection to the Contractor's using, upon his or her own full responsibility the plan or method approved.
6-11. Suggestions to the Contractor. Any plan or method of work suggested by the Engineer to the Contractor, but not specified or required, if adopted or followed by the Contractor in whole or in part, shall be used at the risk and responsibility of the Contractor; and the Engineer and the City shall assume no responsibility thereof.
6-12. Termination of Unsatisfactory Subcontracts. Should any subcontractor fail to perform in a satisfactory manner the work undertaken by him, such subcontract shall be terminated immediately by the Contractor upon notice from the Engineer.
6-13. Preservation of Stakes and Marks. The Contractor shall preserve carefully bench marks, reference points and stakes and in case of destruction he or she shall replace his or her stakes, reference points and bench marks and shall be responsible for any mistakes that may be caused by their unnecessary loss or disturbance. Contractor’s attention is directed to Section 7-03 of these Special Provisions. 6-14. Assistance to Engineer. At the request of the Engineer the Contractor shall provide men from his or her force and tools, stakes and other materials to assist the Engineer temporarily in making measurements and

Page 190 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 12 Spec. No. 24-04 surveys and in establishing temporary or permanent reference marks. Payment for such materials and assistance will be made as provided for under the caption "Extra Work," provided, however, that the cost of setting stakes and marks carelessly lost or destroyed by the Contractor's employees will be assessed to the Contractor.
6-15. Removal of Condemned Materials and Structures. The Contractor shall remove from the site of the work, without delay, all rejected and condemned materials or structures of any kind brought to or incorporated in the work and upon his or her failure to do so, or to make satisfactory progress in so doing, within forty-eight (48) hours after the service of a written notice from the Engineer, the condemned material or work may be removed by the City and the cost of such removal shall be taken out of the money that may be due or may become due the Contractor on account of or by virtue of this contract. No such rejected or condemned material shall again be offered for use by the Contractor under this Contract.
6-16. Proof of Compliance with Contract. In order that the Engineer may determine whether the Contractor has complied with the requirements of this contract, not readily enforceable through inspection and tests of the work and materials, the Contractor shall, at any time when requested, submit to the Engineer properly authenticated documents or other satisfactory proofs as to his or her compliance with such requirements. 6-17. Errors and Omissions. If the Contractor, in the course of the work, finds any errors or omissions in plans or in the layout as given by survey points and instruction, or if he or she finds any discrepancy between the plans and the physical conditions of the locality, he or she shall immediately inform the Engineer, in writing and the Engineer shall promptly verify the same. Any work done after such discovery, until authorized, will be done at the Contractor's risk.
6-18. Cooperation. The Contractor shall cooperate with all other contractors who may be performing work in behalf of the City and workmen who may be employed by the City on any work in the vicinity of the work to be done under this contract with the work of such contractors or workmen. he or she shall make good promptly, at his or her own expense, any injury or damage that may be sustained by other contractors or employees of the City at his or her hands.

Any difference or conflict which may arise between the Contractor and other contractors, or between the contractor and workmen of the City in regard to their work shall be adjusted and determined by the Engineer. If the work of the Contractor is delayed because of any acts or omissions of any other contractor or of the City, the Contractor shall on that account have no claim against the City other than for an extension of time. 6-19. Right of Contractor to Stop Work. Under the following conditions the Contractor shall have the right, if he or she so desires, to stop the work and terminate the contract upon ten (10) days written notice to the Engineer and recover from the City payment for all work actually performed and for all satisfactory materials actually delivered to the site of the work for permanent incorporation therein, all as may be shown by the estimate of the Engineer.
(1) If the work is stopped under an order of any court or other competent public authority for a period of time of three (3) months through no act or fault of the Contractor or of anyone employed by him.
(2) If the Engineer fails to issue the monthly certificate for payment in accordance with the terms of this contract.
(3) If the City fails to pay the Contractor within sixty (60) days after it shall have become due, as provided by the terms of this contract, any sum certified by the Engineer or awarded by the City.

All provided that if such action to terminate the contract be not instituted by the Contractor within ten (10) days after the alleged existence of such condition and if written notice of such action be not at that time delivered to the City and the Engineer, then such right shall lapse until another occasion arises according to this section. 6-20. Hiring and Dismissal of Employees. The Contractor shall employ only such foremen, mechanics and laborers as are competent and skilled in their respective lines of work and whenever the Engineer shall notify the

Page 191 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 13 Spec. No. 24-04 Contractor that any person on the work is, in his or her opinion, incompetent, unfaithful, intemperate or disorderly, or refuses to carry out the provisions of this contract, or uses threatening or abusive language to any person on the work representing the City, or is otherwise unsatisfactory, such person shall be discharged im mediately from the work and shall not be re-employed upon it except with the consent of the Engineer. 6-21. Wage Rates.

1. Contractor shall pay all mechanics and laborers employed or working upon the site of the work unconditionally and without subsequent deductions or rebate on any account the full amounts due at the time of payment at wage rates not less than those contained in the applicable prevailing wage determination, regardless of any contractual relationship which may be alleged to exist between the Contractor and subcontractors and such laborers and mechanics.

2. Contractor shall comply with the California Labor Code Section 1775. In accordance with said Section 1775, Contractor shall forfeit as a penalty to the Owner, $50.00 (or the higher minimum penalty as provided in Section 1775(B)(ii) – (iii)) for each calendar day or portion thereof, for each workman paid less than the stipulated prevailing rates for such work or craft in which such workman is employed for any work done under the Contract by him or her or by any subcontractor under him or her in violation of the provisions of the Labor Code and in particular, Labor Code Sections 1770 to 1780, inclusive. In addition to said penalty and pursuant to Section 1775, the difference between such stipulated prevailing wage rates and the amount paid to each workman for each calendar day or portion thereof for which each workman was paid less than the stipulated prevailing wage rate shall be paid to each workman by the Contractor.

3. Pursuant to the provision of Section 1770 of the Labor Code of the State of California, Owner has ascertained the general prevailing rate of wages (which rate includes employer payments for health and welfare, vacation, pension and similar purposes) applicable to the work to be done, for straight time work. The holiday wage rate listed shall be applicable to all holidays recognized in the collective bargaining agreement of the particular craft, classification or type of workmen concerned. Copies of the General Prevailing Wage Determination are available on the Internet at web address:
http://www.dir.ca.gov/DLSR/PWD The Contractor shall post the wage determination at the site of work in a prominent place where it can easily be seen by the workers.

4. City will not recognize any claim for additional compensation because the Contractor has paid any rate in excess of the prevailing wage rate obtained by the Contractor. The possibility of wage increases is one of the elements to be considered by the Contractor in determining his or her bid and will not in any circumstances be considered as the basis for a claim against the City.

5. The Labor Commissioner through the Division of Labor Standards Enforcement (DLSE) may at any time require contractors and subcontractors to furnish electronic certified payroll records directly to DLSE.

Commencing with contracts awarded or after April 1, 2015, all contractors and subcontractors must furnish electronic certified payroll records directly to the DLSE.

6. Travel and Subsistence Payments.

Contractor shall make travel and subsistence payments to each workman needed to execute the work in accordance with the requirements in Section 1773.8 of the Labor Code (Chapter 880, Statutes of 1968).

7. Apprentices.

Attention is directed to the provisions in Sections 1777.5 (Chapter 1411, Statutes of 1968) and 1777.6 of the California Labor Code concerning the employment of apprentices by the Contractor or any subcontractor under him. Contractor and any subcontractor under him or her shall comply with the requirements of said sections in the employment of apprentices.

Information relative to apprenticeship standards, wage schedules and other requirements may be obtained from the Director of Industrial Relations, ex officio the Administrator of

Page 192 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 14 Spec. No. 24-04 Apprenticeship, San Francisco, California, or from the Division of Apprenticeship Standards and its branch offices.
6-22. Cleaning Up. The Contractor shall not allow the site of the work to become littered with trash and waste material but shall maintain the same in a neat and orderly condition throughout the construction period. The Engineer shall have the right to determine what is or is not waste material or rubbish and the place and manner of disposal.

On or before the completion of the work, the Contractor shall without charge therefore carefully clean out all pits, pipes, chambers or conduits and shall tear down and remove all temporary structures built by him or her and shall remove rubbish of all kinds from any of the grounds which he or she has occupied and leave them in first class condition.
6-23. Guaranty. All work shall be guaranteed for a period of one year from the date of acceptance by the City.

The Contractor shall promptly make all needed repairs arising out of defective materials, workmanship, and equipment.

The City is hereby authorized to make such repairs if within ten days after the mailing of a notice in writing to the Contractor or his or her agent, the Contractor shall neglect to make or undertake with due diligence the aforesaid repairs, provided, however, that in case of an emergency where, in the opinion of the City delay would cause serious loss or damage, repairs may be made without notice being sent to the Contractor and the Contractor shall pay the costs thereof.

Pursuant to the provisions of Section 4-03 of these Special Provisions, the Contractor shall furnish a Defective Material and Workmanship Bond in an amount not less than 5 percent of the final contract price, which shall be effective for a period of one (1) year after the completion and acceptance of the work. 6-24. Public Notification. The contractor shall be responsible for all public notification regarding construction work including detours, lane and street closures, hours of operations, and notification of effected commercial businesses within 1000 feet of the construction. For any business impacted by construction, the contractor shall provide adequately sized on-site signage indicating that businesses are open during construction. The contractor shall prepare public noticing via the newspaper, radio announcements, notification of the emergency vehicle agencies, public transit, Ukiah Unified School District and St. Mary’s School, that the project streets will be affected by potential detours and street closures, with recommended alternate routes of travel. Through street access will be restricted to businesses and residents only during construction closures. Location of Street Closures signage shall be positioned to give motorists the ability to use alternate routes prior to coming to a dead-end road closed for construction. All proposed detours, closures and traffic control methods shall be submitted to the Engineer for approval prior noticing to the public. All public noticing shall be performed a minimum of one week prior to instituting traffic control, and lane or street closures. The tentative construction schedule shall be included in the public noticing. The contractor shall submit all public notice language to the City Engineer for approval prior to publication of notices. All road closures, detour routes, and traffic control including temporary lane closure plans shall be submitted by the Contractor to the City Engineer for approval prior to public noticing and use.

SECTION 7. RESPONSIBILITIES AND RIGHTS OF CITY
7-01. Authority of the Engineer. All work done under this contract shall be done in a workmanlike manner and shall be performed to the reasonable satisfaction of the Engineer, who shall have general supervision of all work included hereunder. To prevent disputes and litigation, the Engineer (1) shall in all cases determine the amount, quality, acceptability and fitness of the several kinds of work and materials which are to be paid for under this contract, (2) shall decide all questions relative to the true construction, meaning and intent of the Special Provisions and Drawings, (3) shall decide all questions which may arise relative to the classifications and measurements of quantities and materials and the fulfillment of this contract and (4) shall have the power to reject or condemn all work or material which does not conform to the terms of this contract. his or her estimate and decision in all matters shall be a condition precedent to an appeal for arbitration, or the right of the Contractor to receive, demand, or claim any money or other compensation under this agreement and a condition

Page 193 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 15 Spec. No. 24-04 precedent to any liability on the part of the City to the Contractor on account of this contract. Whenever the Engineer shall be unable to act, in consequence of absence or other cause, then such engineer as the Engineer or the City shall designate, shall perform any and all of the duties and be vested with any or all of the powers herein given to the Engineer.
7-02. Inspection. The City will provide engineering personnel for the inspection of the work.

The Engineer and his or her representatives shall at all times have access to the work whenever it is in preparation or progress and the Contractor shall provide proper facilities for such access and inspection.

If the Special Provisions, the Engineer's instruction, laws, ordinances, or any public authority require any work to be specially tested or approved, the Contractor shall give the Engineer timely notice of its readiness for inspection and, if the inspection is by an authority other than the Engineer, of the date fixed for such inspection.

Inspections by the Engineer shall be promptly made at the source of supply where practicable. If any work shall be covered up without approval or consent of the Engineer, it must, if required by the Engineer, be uncovered for examination and properly restored at the Contractor's expense.

Re-examination of any work may be ordered by the Engineer and, if so ordered, the work must be uncovered by the Contractor. If such work is found to be in accordance with the contract documents, the City shall pay the cost of re-examination and replacement. If such work is not in accordance with the contract documents, the Contractor shall pay such cost.

Properly authorized and accredited inspectors shall be the representatives of the City limited to the duties and powers entrusted to them. It will be their duty to inspect materials and workmanship of those portions of the work to which they are assigned, either individually or collectively, under instructions of the Engineer and to report any and all deviations from the Drawings, Special Provisions and other contract provisions which may come to their notice. Any inspector may be considered to have the right to order the work entrusted to his or her supervision stopped, if in his or her opinion such action becomes necessary, until the Engineer is notified and has determined and ordered that the work may proceed in due fulfillment of all contract requirements. 7-03. Surveys. Contractor shall furnish all land surveys, establish all base lines and benchmarks and make sufficient detailed surveys needed for working points, lines and elevations. The Contractor shall develop all slope stakes and batter boards. Contractor shall also develop all additional working points, lines and elevations as he or she may desire to facilitate his or her methods and sequence of construction. 7-04. Rights-of-Way. The City will provide all necessary rights-of-way and easements in or beneath which work will be performed by the Contractor under this contract. 7-05. Retention of Imperfect Work. If any portion of the work done or material furnished under this contract shall prove defective and not in accordance with the Plans and Special Provisions, and if the imperfection in the same shall not be of sufficient magnitude or importance to make the work dangerous or undesirable, the Engineer shall have the right and authority to retain such work instead of requiring the imperfect work to be removed and reconstructed, but he or she shall make such deductions therefor in the payments due or to become due the Contractor as may be just and reasonable. 7-06. Changes in the Work. The Engineer shall have the right, in writing, to order additions to, omissions from, or corrections, alterations and modifications in the line, grade, form, dimensions, plan, or kind or amount of work or materials herein contemplated, or any part thereof, either before or after the beginning of construction.

However, the arithmetical sum of the cost to the City of additions and subtractions from the work under this contract shall not exceed 10 percent of original contract amount or $5,000, whichever is the greater, unless based upon a supplementary agreement to be made therefore.

The order of such additions, omissions, corrections, alterations and modifications shall be in writing and signed by the Engineer and, in order, shall then be binding upon the Contractor. The Contractor shall proceed with the work as changed and the value of such change shall be determined as provided for in section 10-07 of these Special Provisions.

Page 194 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 16 Spec. No. 24-04 Such alterations shall in no way affect, vitiate, or make void this contract or any part thereof, except that which is necessarily affected by such alterations and is clearly the evident intention of the parties to this contract. 7-07. Additional Drawings by City. The drawings made a part of this contract at the time of its execution are intended to be fairly comprehensive and to indicate in more or less detail the scope of the work. In addition to these drawings, however, the Engineer shall furnish such additional drawings from time to time during the progress of the work as are necessary to make clear or to define in greater detail the intent of the Special Provisions and the contract drawings and the Contractor shall make his or her work conform to all such drawings.
7-08. Additional and Emergency Protection. Whenever, in the opinion of the Engineer, the Contractor has not taken sufficient precautions for the safety of the public or the protection of the works to be constructed under this contract, or of adjacent structures or property which may be injured by the processes of construction on account of such neglect and whenever, in the opinion of the Engineer, an emergency shall arise and immediate action shall be considered necessary in order to protect public or private, personal or property interest, then and in that event, the Engineer, with or without notice to the Contractor may provide suitable protection to the said interests by causing such work to be done and such material to be furnished as shall provide such protection as the Engineer may consider necessary and adequate.

The cost and expense of such work and material so furnished shall be borne by the Contractor and, if the same shall not be paid on presentation of the bills therefor, then such costs shall be deducted from any amounts due or to become due the Contractor.

The performance of such emergency work under the direction of the Engineer shall in no way relieve the Contractor from any damages which may occur during or after such precaution has been taken by the Engineer. 7-09. Suspension of Work. The City may at any time suspend the work or any part thereof by giving five (5) days written notice to the Contractor. The work shall be resumed by the Contractor within ten (10) days after the date fixed in the written notice from the City to the Contractor so to do. The City shall reimburse the Contractor for expense incurred by the Contractor in connection with the work under this contract as a result of such suspension.

If the work, or any part thereof, shall be stopped by the notice in writing aforesaid and if the City does not give notice in writing to the Contractor to resume work at a date within ten (10) days of the date fixed in the written notice to suspend, then the Contractor may abandon that portion of the work so suspended and he or she will be entitled to the estimates and payments for all work done on the portions so abandoned, if any, plus 5 percent of the value of the work so abandoned, to compensate for loss of overhead, plant expense and anticipated profit. 7-10. Right of City to Terminate Contract. If the Contractor should be adjudged a bankrupt, or if he or she should make a general assignment for the benefit of his or her creditors, or if a receiver should be appointed on account of his or her insolvency, or if he or she should persistently or repeatedly refuse or should fail, except in cases for which extension of time is provided, to supply sufficient properly skilled workmen or proper materials, or if he or she should fail to make prompt payments to subcontractors or for material or labor, or persistently disregard laws, ordinances or the instructions of the Engineer, or otherwise be guilty of a substantial violation of any provision of the contract, then the City, upon the certificate of the Engineer that sufficient cause exists to justify such action, may, without prejudice to any other right or remedy and after giving the Contractor seven days written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances and finish the work by whatever method the City may deem expedient. In such case, the Contractor shall not be entitled to receive any further payment until the work is finished. If the unpaid balance of the contract price shall exceed the expense of finishing the work, including compensation for additional managerial and administrative services, such excess shall be paid to the Contractor. If such expense shall exceed such unpaid balance, the Contractor shall pay the difference to the City. The expense incurred by the City as herein provided and the damage incurred through the Contractor's default, shall be certified by the Engineer. In the event that a termination under this section is determined to be improper, such termination shall be deemed a constructive termination for convenience taken pursuant to section 7-12 below. 7-11. Use of Completed Portions. The City shall have the right to take possession of and use any completed or partially completed portions of the work, notwithstanding the time for completing the entire work or such

Page 195 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 17 Spec. No. 24-04 portions which may not have expired; but such taking possession and using shall not be deemed an acceptance of any work not completed in accordance with the contract documents. If such prior use increases the cost of or delays the work, the Contractor shall be entitled to such extra compensation, or extension of time or both, as the Engineer may determine.
7-12. Right of City to Terminate Contract for Convenience. The City may terminate performance of the work called for by the contract documents in whole or, from time to time, in part, if the City determines that a termination is in the City’s best interest. The Contractor shall terminate all or any part of the work upon delivery to the Contractor of a notice of termination specifying that the termination is for the convenience of the City, the extent of termination, and the effective date of such termination. After receipt of notice of termination, and except as directed by the Engineer, the Contractor shall, regardless of any delay in determining or adjusting any amounts due under this termination for convenience clause, immediately proceed with the following obligations:

1. Stop work as specified in the notice.

2. Complete any work specified in the notice of termination in a least cost/shortest time manner while still maintaining the quality called for under the contract documents.

3. Leave the property upon which the Contractor was working and upon which the facility (or facilities) forming the basis of the contract documents is situated in a safe and sanitary manner such that it does not pose any threat to the public health or safety.

4. Terminate all subcontracts to the extent that they relate to the portions of the work terminated.

5. Place no further subcontracts or orders, except as necessary to complete the continued portion of the contract.

6. Submit to the Engineer, within ten (10) calendar days from the effective date of the notice of termination, all of the usual documentation called for by the contract documents to substantiate all costs incurred by the Contractor for labor, materials and equipment through the effective date of the notice of termination.

Any documentation substantiating costs incurred by the Contractor solely as a result of the City's exercise of its right to terminate this Contract pursuant to this clause, which costs the contractor is authorized under the contract documents to incur, shall: (1) be submitted to and received by the Engineer no later than 30 calendar days after the effective date of the notice of termination; (2) describe the costs incurred with particularity; and (3) be conspicuously identified as “Termination Costs occasioned by the City's Termination for Convenience.”
Termination of the contract shall not relieve Surety of its obligation for any just claims arising out of or relating to the work performed. In the event that the City exercises its right to terminate this contract pursuant to this clause, the City shall pay the Contractor, upon the Contractor's submission of the documentation required by this clause and other applicable provisions of the contract documents, the following amounts:

All actual reimbursable costs incurred according to the provisions of this contract.

1. A reasonable allowance for profit on the cost of the Work performed, provided Contractor establishes to the satisfaction of the Engineer that it is reasonably probable that Contractor would have made a profit had the contract been completed and provided further, that the profit allowed shall in no event exceed fifteen (15%) percent of the costs.

2. A reasonable allowance for Contractor's administrative costs in determining the amount payable due to termination of the contract under this Article.

Notwithstanding any other provision of this Article, when immediate action is necessary to protect life and safety or to reduce significant exposure or liability, the City may immediately order Contractor to cease work on the project until such safety or liability issues are addressed to the satisfaction of the City or the contract is terminated.

SECTION 8. WORKMANSHIP, MATERIALS and EQUIPMENT
8-01. General Quality. Materials and equipment shall be new and of a quality equal to that specified or approved. Work shall be done and completed in a thorough and workmanlike manner. 8-02. Quality in Absence of Detailed Specifications. Whenever under this contract it is provided that the Contractor shall furnish materials or manufactured articles or shall do work for which no detailed specifications are set forth, the materials or manufactured articles shall be of the best grade in quality and workmanship obtainable in the market from firms of established good reputation, or, if not ordinarily carried in stock, shall conform to the usual standards for first-class materials or articles of the kind required, with due consideration of

Page 196 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 18 Spec. No. 24-04 the use to which they are to be put. In general, the work performed shall be in full conformity and harmony with the intent to secure the best standard of construction and equipment of the work as a whole or in part. 8-03. Materials and Equipment Specified by Name. Whenever any material or equipment is indicated or specified by patent or proprietary name or by the name of the manufacturer, such specification shall be considered as used for the purpose of describing the material or equipment desired and shall be considered as followed by the words "or approved equal". The Contractor may offer any material or equipment which shall be equal in every respect to that specified, provided that written approval first is obtained from the Engineer. 8-04. Source of Materials. Price, fitness and quality being equal, preference shall be given by the Contractor for supplies grown, manufactured or produced in the State of California and, next, for such products partially produced in this State in accordance with Government Code Section 4332. 8-05. Storage of Materials. Materials shall be so stored to ensure the preservation of their quality and fitness for the work. They shall be so located and disposed that prompt and proper inspection thereof may be made. 8-06. Drawings, Samples and Tests. As soon as possible after execution of the contract, the Contractor shall submit to the Engineer, in quintuplicate, sufficient information including, if necessary, assembly and detail drawings to demonstrate fully that the equipment and materials to be furnished comply with the provisions and intent of these Special Provisions and Drawings. If the information thus submitted indicates the equipment or materials is acceptable, the Engineer will return one copy stamped with his or her approval; otherwise, one copy will be returned with an explanation of why the equipment or material is unsatisfactory. The Contractor shall have no claims for damages or for extension of time on account of any delay due to the revision of drawings or rejection of material. Fabrication or other work performed in advance of approval shall be done entirely at the Contractor's risk. After approval of equipment or material, the Contractor shall not deviate in any way from the design and specifications given without the written consent of the Engineer.

When requested by the Engineer, a sample or test specimens of the materials to be used or offered for use in connection with the work shall be prepared at the expense of the Contractor and furnished by him or her in such quantities and sizes as may be required for proper examination and tests, with all freight charges prepaid and with information as to their sources.

All samples shall be submitted before shipment and in ample time to permit the making of proper tests, analyses, or examination before the time at which it is desired to incorporate the material into the work. All tests of materials furnished by the Contractor shall be made by the Engineer. Samples shall be secured and tested whenever necessary to determine the quality of the material.

SECTION 9. PROSECUTION OF WORK
9-01. Equipment and Methods. The work under this contract shall be prosecuted with all materials, tools, machinery, apparatus, and labor and by such methods as are necessary to the complete execution of everything described, shown, or reasonably implied. If at any time before the beginning or during the progress of the work, any part of the Contractor's plant or equipment, or any of his or her methods of execution of the work, appear to the Engineer to be unsafe, inefficient, or inadequate to insure the required quality or the rate of progress of the work, he or she may order the Contractor to increase or improve his or her facilities or methods and the Contractor shall comply promptly with such orders; but, neither compliance with such orders nor failure of the Engineer to issue such orders shall relieve the Contractor from his or her obligation to secure the degree of safety, the quality of the work and the rate of progress required of the Contractor. The Contractor alone shall be responsible for the safety, adequacy and efficiency of his or her plant, equipment and methods. 9-02. Time of Completion. The Contractor shall promptly begin the work under this contract and shall complete and make ready for full use all portions of the project made the subject of this contract within the time set forth in the agreement bound herewith.
9-03. Avoidable Delays. Avoidable delays in the prosecution or completion of the work shall include all delays which might have been avoided by the exercise of care, prudence, foresight, and diligence on the part of the

Page 197 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 19 Spec. No. 24-04 Contractor. The City will consider as avoidable delays within the meaning of this contract (1) delays in the prosecution of parts of the work, which may in themselves be unavoidable, but do not necessarily prevent or delay the prosecution of other parts of the work nor the completion of the whole work within the time herein specified, (2) reasonable loss of time resulting from the necessity of submitting plans to the Engineer for approval and from the making of surveys, measurements, inspections, and testing and (3) such interruptions as may occur in the prosecution of the work on account of the reasonable interference of other contractors employed by the City which do not necessarily prevent the completion of the whole work within the time herein specified.
9-04. Unavoidable Delays. Unavoidable delays in the prosecution or completion of the work under this contract shall include all delays which may result, through cause beyond the control of the Contractor and which he or she could not have provided against by the exercise of care, prudence, foresight, and diligence. Orders issued by the City changing the amount of work to be done, the quantity of material to be furnished or the manner in which the work is to be prosecuted and unforeseen delays in the completion of the work of other contractors under contract with the City will be considered unavoidable delays, so far as they necessarily interfere with the Contractor's completion of the whole of the work. Delays due to normally adverse weather conditions will not be regarded as unavoidable delays. However, truly abnormal amounts of rainfall, temperatures, or other weather conditions for the location of the work and time of year may be considered as unavoidable delays if those conditions necessarily cause a delay in the completion of the work. 9-05. Notice of Delays. Whenever the Contractor foresees any delay in the prosecution of the work and, in any event, immediately upon the occurrence of any delay which the contractor regards as an unavoidable delay, he or she shall notify the Engineer in writing of the probability of the occurrence of such delay and its cause, in order that the Engineer may take immediate steps to prevent, if possible, the occurrence or continuance of the delay, or, if this cannot be done, may determine whether the delay is to be considered avoidable or unavoidable, how long it continues and to what extent the prosecution and completion of the work are to be delayed thereby. 9-06. Extension of Time. Should any delays occur which the Engineer may consider unavoidable, as herein defined, the Contractor shall, pursuant to his or her application, be allowed an extension of time proportional to said delay or delays, beyond the time herein set forth, in which to complete this contract; and liquidated damages for delay shall not be charged against the Contractor by the City during an extension of time granted because of unavoidable delay or delays.

Any claim by Contractor for a time extension based on unavoidable delays shall be based on written notice delivered to the Engineer within 15 days of the occurrence of the event giving rise to the claim. Failure to file said written notice within the time specified shall constitute a waiver of said claim. Notice of the full extent of the claim and all supporting data must be delivered to the Engineer within 45 days of the occurrence unless the Engineer specifies in writing a longer period. All claims for a time extension must be approved by the Engineer and incorporated into a written change order.
9-07. Unfavorable Weather and Other Conditions. During unfavorable weather and other conditions, the Contractor shall pursue only such portions of the work as shall not be damaged thereby. No portions of the work whose satisfactory quality or efficiency will be affected by any unfavorable conditions shall be constructed while these conditions remain, unless, by special means or precautions approved by the Engineer, the Contractor shall be able to overcome them.

The Contractor shall be granted a time extension of one day for each unfavorable weather day which prevents him or her from placing concrete forms or placing and finishing concrete or asphalt concrete. Such unfavorable weather day is defined as a rain day where precipitation prevents the contractor from performing the work more than four (4) continuous hours within the authorized work period or a temperature day where the ambient temperature is below that specified for the placement of materials associated with the controlling work item for more than four (4) continuous work hours of the authorized work period. 9-08. Saturday, Sunday, Holiday and Night Work. No work shall be done between the hours of 6 p.m. and 7 a.m., nor on Saturdays, Sundays or legal holidays except such work as is necessary for the proper care and protection of work already performed, or except in cases of absolute necessity and in any case only with the permission of the Engineer.

Page 198 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 20 Spec. No. 24-04 It is understood, however, that night work may be established as a regular procedure by the Contractor if he or she first obtains the written permission of the Engineer and that such permission may be revoked at any time by the Engineer if the Contractor fails to maintain at night adequate force and equipment for reasonable prosecution and to justify inspection of the work.
9-09. Hours of Labor. Eight (8) hours of labor shall constitute a legal day's work and the Contractor or any subcontractor shall not require or permit more than eight hours of labor in a day from any person employed by him or her in the performance of the work under this contract, unless paying compensation for all hours worked in excess of eight (8) hours per day at not less than 1½ times the basic rate of pay. The Contractor shall forfeit to the City, as a penalty, the sum of twenty-five dollars ($25.00) for each workman employed in the execution of the contract by him or her or by any subcontractor, for each calendar day during which such laborer, workman, or mechanic is required or permitted to labor more than eight hours in violation of the provisions of Section 1810 to 1816, inclusive, (Article 3, Chapter 1, Part 7, Division 2) of the Labor Code of the State of California and any acts amendatory thereof.

SECTION 10. PAYMENT
10-01. Certification by Engineer. All payments under this contract shall be made upon the presentation of certificates in writing from the Engineer and shall show that the work covered by the payments has been done and the payments thereof are due in accordance with this contract. 10-02. Progress Estimates and Payment. The Engineer shall, within the first seven (7) days of each month, make an estimate of the value of the work performed in accordance with this contract during the previous calendar month.

The first estimate shall be of the value of the work satisfactorily completed in place and meeting the requirements of the contract. And every subsequent estimate, except the final estimate, shall be of the value of the work satisfactorily completed in place since the last preceding estimate was made; provided, however, that should the Contractor fail to adhere to the program of completion fixed in this contract, the Engineer shall deduct from the next and all subsequent estimates the full calculated accruing amount of the liquidated damages to the date of said estimate, until such time as the compliance with the program has been restored.

The estimate shall be signed by the Engineer and, after approval, the City shall pay or cause to be paid to the Contractor in the manner provided by law, an amount equal to 95 percent of the estimated value of the work satisfactorily performed and complete in place.
10-03. Substitution of Securities.

1. At such times that Pubic Contract Code Section 22300 is in effect Contractor may propose the substitution of securities of at least equal market value for any moneys to be withheld to ensure performance under the Contract. Market value shall be determined as of the day prior to the date such substitution is to take place.

Such substitution shall be made at the request and expense of the Contractor. The securities shall be one or more of the following types:
(a) Bonds or interest-bearing notes or obligations of the United States, or those for which the faith and credit of the United States are pledged for the payment of principal and interest. (b) Bonds or interest-bearing notes on obligations that are guaranteed as to principal and interest by a federal agency of the United States.
(c) Bonds of the State of California, or those for which the faith and credit of the State of California are pledged for the payment of principal and interest.
(d) Bonds or warrants, including, but not limited to, revenue warrants, of any county, city, metropolitan water district, California water district, California water storage district, irrigation district in the State of California, municipal utility district, or school district of the State of California, which are rated by Moody's or Standard and Poor as A or better.

Page 199 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 21 Spec. No. 24-04 (e) Bonds, consolidated bonds, collateral trust debentures, consolidated debentures, or other obligations issued by federal land banks or federal intermediate credit banks established under the Federal Farm Loan Act, as amended; debentures and consolidated debentures issued by the Central Bank for Cooperatives and banks for cooperatives established under the Farm Credit Act of 1933, as amended; bonds, or debentures of the Federal Home Loan Bank Board established under the Federal Home Loan Bank Act; and stock, bonds, debentures and other obligations of the Federal National Mortgage Association established under the National Housing Act as amended and bonds of any Federal Home Loan Mortgage Corporation.
(f) Commercial paper of "prime" quality as defined by a nationally recognized organization which rates such securities. Eligible paper is further limited to issuing corporations: (1) organized and operating within the United States; (2) having total assets in excess of five hundred million dollars ($500,000,000); and (3) approved by the Pooled Money Investment Board of the State of California. Purchases of eligible commercial paper may not exceed 180 days' maturity, nor represent more than 10 percent of the outstanding paper of an issuing corporation.
(g) Bills of exchange or time drafts on and accepted by a commercial bank, otherwise known as bankers acceptances, which are eligible for purchase by the Federal Reserve System. (h) Certificates of deposits issued by a nationally or state-chartered bank or savings and loan association.
(i) The portion of bank loans and obligations guaranteed by the United States Small Business Administration or the United States Farmers Home Administration. (j) Student loan notes insured under the Guaranteed Student Loan Program established pursuant to the Higher Education Act of 1965, as amended (20 U.S.C. 1001, et seq.) and eligible for resale to the Student Loan Marketing Association established pursuant to Section 133 of the Education Amendments of 1972, as amended (20 U.S.C. 1087-2).
(k) Obligations issued, assumed or guaranteed by International Bank for Reconstruction and Development, the Inter-American Development Bank, the Asian Development Bank, or the Government Development Bank of Puerto Rico.
(l) Bonds, debentures and notes issued by corporations organized and operating within the United States. Such securities eligible for substitution shall be within the top three ratings of a nationally recognized rating service.

2. The securities shall be deposited with City or with any commercial bank as escrow agent, who shall arrange for transfer of such securities to the Contractor upon satisfactory completion of the contract. Any interest accrued or paid on such securities shall belong to the Contractor and shall be paid upon satisfactory completion of the contract.

The market value of the securities deposited shall at all times be maintained in an amount at least equal, in the sole judgment of City, to the moneys to be withheld pursuant to the Contract Documents to ensure performance of the Contract. In order to comply with this condition, Contractor shall deposit additional securities as necessary upon request by City or the escrow agent.

3. Upon acceptance of any Proposal that includes substituting securities for amounts withheld to ensure performance, a separate escrow agreement satisfactory in form and substance to City shall be prepared and executed by City, the Contractor and the escrow agent, which may be City. The escrow agreement shall specify, among other matters, value of securities to be deposited; procedures for valuing the securities and for adding or withdrawing securities to maintain the market value of the deposited securities at least equal to the amount of moneys which would otherwise be withheld; the terms and conditions of conversion to cash in case of the default by the Contractor; and terms, conditions and procedure for termination of the escrow. City shall have no obligation to enter any such Agreement that does not provide the City with the unilateral right to convert securities to cash and to gain immediate possession of the cash.

Page 200 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 22 Spec. No. 24-04 10-04. Acceptance. The work must be accepted by vote of the City Council of the City of Ukiah when the whole shall have been completed satisfactorily. The Contractor shall notify the Engineer, in writing, of the completion of the work, whereupon the Engineer shall promptly, by personal inspection, satisfy himself as to the actual completion of the work in accordance with the terms of the contract and shall thereupon recommend acceptance by the City Council.
10-05. Final Estimate and Payment. The Engineer shall, as soon as practicable after the final acceptance of the work done under this contract, make a final estimate of the amount of work done thereunder and the value thereof.

Such final estimate shall be signed by the Engineer, and after approval, the City shall pay or cause to be paid to the Contractor, in the manner provided by law, the entire sum so found to be due hereunder, after deducting therefrom all previous payments and such other lawful amounts as the terms of this contract prescribe.

In no case will final payment be made in less than thirty-five (35) days after the filing of the notice of completion with the County Recorder.
10-06. Delay Payments. Should any payment due the Contractor or any estimate be delayed, through fault of the City beyond the time stipulated, such delay shall not constitute a breach of contract or be the basis for a claim for damages, but the City shall pay the Contractor interest on the amount of the payment at the rate of 6 percent per annum for the period of such delay. The terms for which interest will be paid shall be reckoned, in the case of any monthly or progress payment, from the twentieth day of the month next succeeding the month in which the work was performed to the date of payment of the estimate; and in the case of the final estimate, from the forty-fifth day after acceptance to the date of payment of the final estimate.

The date of payment of any estimate shall be considered the day on which the payment is offered or mailed as evidenced by the records of the Treasurer of the City. If interest shall become due on any delayed payment, the amount thereof, as determined by the City, shall be added to a succeeding payment. If the interest shall become due on the final payment, it shall be paid on a supplementary voucher to interest or any sum or sums which, by the terms of this contract, the City is authorized to reserve or retain. 10-07. Extra Work and Work Omitted. Whenever corrections, alterations, or modifications of the work under this contract ordered by the Engineer and approved by the City increase the amount of work to be done, such added work shall be known as "extra work"; and when such corrections, alterations, or modifications decrease the amount of work to be done, such subtracted work shall be known as "work omitted".

When the Contractor considers that any changes ordered involve extra work, he or she shall immediately notify the Engineer in writing and subsequently keep him or her informed as to when and where extra work is to be performed and shall make claim for compensation therefor each month not later than the first day of the month following that in which the work claimed to be extra work was performed and he or she shall submit a daily complete statement of materials and labor used and expenses incurred on account of extra work performed, showing allocation of all materials, labor and expenses.

All such claims shall state the date of the Engineer's written order and the date of approval by the City authorizing the work on account of which claim is made. Unless such notification is made in writing within the time specified and unless complete statements of materials used and expenses incurred on account of such extra work are furnished as above required, the Contractor shall not be entitled to payment on account of extra work and Contractor shall be deemed to have waived the right to make any future claims for compensation for such extra work.

When changes decrease the amount of work to be done, they shall not constitute a claim for damages on account of anticipated profits on the work that may be omitted. 10-08. Compensation for Extra Work or Work Omitted. Whenever corrections, additions, or modifications in the work under this contract change the amount of work to be done or the amount of compensation due the Contractor, excepting increases or decreases in contract items having unit contract prices for each measurable quantity installed in place, and such changes have been ordered in writing by the Engineer and approved by the City prior to the Contractor performing the extra work, then a price may be agreed upon. Failing such an

Page 201 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 23 Spec. No. 24-04 agreement in price, the Contractor shall be compensated for performing extra work pursuant to the provisions of Section 4-1.03 D,"Extra Work", and Section 9-1.03,"Force Account Payment" of the Standard Specifications.

This method of determining the price of work shall not apply to the performance of any work which is required or reasonably implied to be performed or furnished under this contract. 10-09. Compensation to the City for Extension of Time. In case the work called for under this contract is not completed within the time limit stipulated herein, the City shall have the right as provided hereinabove, to extend the time of completion thereof. If the time limit be so extended, the City shall have the right to charge to the Contractor and to deduct from the final payment for the work the actual cost to the City of engineering, inspection, superintendence and other overhead expenses which are directly chargeable to the contract and which accrue during the period of such extension, except that the cost of final unavoidable delays shall not be included in such charges.
10-10. Liquidated Damages for Delay. It is agreed by the parties to the contract that time is of the essence and that, in case all the work is not completed before or upon the expiration of the time limit as set forth, damage, other than those cost items identified in section 10-09, will be sustained by the City and that it is and will be impracticable to determine the actual amount of damage by reason of such delay; and it is therefore agreed that the Contractor will pay to the City the sum of five hundred dollars ($500.00) per day for each and every calendar day's delay beyond the time prescribed.

In compliance with the provisions of California Public Contract Code § 7102, the Contractor will be compensated for damages incurred due to delays in completing the work due solely to the fault of the City, where such delay is unreasonable under the circumstances and not contemplated by the parties. The Contractor and City agree that determining actual damages is impracticable and extremely difficult. As such, the Contractor shall be entitled to the appropriate time extension and to payment of liquidated damages in the sum of $250 per day of delay in excess of the time specified for the completion of the work. Such amount shall constitute the only payment allowed and shall necessarily include all overhead (direct or indirect), all profit, all administrative costs, all bond costs, all labor, materials, equipment and rental costs, and any other costs, expenses and fees incurred or sustained as a result of such delay. The Contractor expressly agrees to be limited solely to the liquidated damages for all such delays as defined in this subsection.

SECTION 11. MISCELLANEOUS
11-01. Notice. Whenever any provision of the contract documents requires the giving of written notice, it shall be deemed to have been validly given if delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended, or if delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. If mailed, the notice shall be deemed received on the date of delivery stated in the return receipt. 11-02. Computation of Time. When any period is referred to in the Contract Documents by days, it shall be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day shall be omitted from the computation.
11-03. Claims Procedure. Contractor shall timely comply with all notices and requests for changes to the contract time or contract price, as a prerequisite to filing any claim governed by this Article. The failure to timely submit a notice of delay or notice of change, or to timely request a change to the contract time or contract price, or to timely provide any other notice or request required herein shall constitute a waiver of the right to further pursue the claim under the contract or at law.

A. Intent. Effective January 1, 1991, Section 20104 et seq., of the California Public Contract Code prescribes a process utilizing informal conferences, non-binding judicial supervised mediation, and judicial arbitration to resolve disputes on construction claims of $375,000 or less. Effective January 1, 2017, Section 9204 of the Public Contract Code prescribes a process for negotiation and mediation to resolve disputes on construction claims. The intent of this Article is to implement Sections 20104 et seq.

Page 202 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 24 Spec. No. 24-04 and Section 9204 of the California Public Contract Code. This Article shall be construed to be consistent with said statutes.

B. Claims. For purposes of this Article, “Claim” means a separate demand by the Contractor, for (A) a time extension, (B) payment of money or damages arising from work done by or on behalf of the Contractor pursuant to the Contract, or (C) an amount the payment of which is disputed by the District.

Claims governed by this Article may not be filed unless and until the Contractor completes all procedures for giving notice of delay or change and for the requesting of a time extension or change order. Claims governed by this Article must be filed no later than the date of final payment. The claim shall be submitted in writing to the District and shall include on its first page the following in 16 point capital font: “THIS IS A CLAIM.” Furthermore, the claim shall include the documents necessary to substantiate the claim. Nothing herein is intended to extend the time limit or supersede notice requirements otherwise provided by contract for the filing of claims, including all requirements pertaining to compensation or payment for extra work, disputed work, and/or changed conditions. Failure to follow such contractual requirements shall bar any claims or subsequent lawsuits for compensation or payment thereon.

C. Supporting Documentation. The Contractor shall submit all claims in the following format:

Summary of claim merit and price, reference Contract Document provisions pursuant to which the claim is made.

List of documents relating to claim:

Specifications
Drawings
Clarifications (Requests for Information)
Schedules
Other
Chronology of events and correspondence
Analysis of claim merit
Analysis of claim cost
Time impact analysis in CPM format
If Contractor’s claim is based in whole or in part on an allegation of errors or omissions in the Drawings or Specifications for the project, Contractor shall provide a summary of the percentage of the claim subject to design errors or omissions and shall obtain a certificate of merit in support of the claim of design errors and omissions.

D. City’s Response. Upon receipt of a claim pursuant to this Article, City shall conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide the Contractor a written statement identifying what portion of the claim is disputed and what portion is undisputed. Any payment due on an undisputed portion of the claim will be processed and made within 60 days after the City issues its written statement.

If the City needs approval from its governing body to provide the Contractor a written statement identifying the disputed portion and the undisputed portion of the claim, and the City’s governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, the City shall have up to three days following the next duly publicly noticed meeting of the City’s governing body after the 45-day period, or extension, expires to provide the Contractor a written statement identifying the disputed portion and the undisputed portion.

Within 30 days of receipt of a claim, the City may request in writing additional documentation supporting the claim or relating to defenses or claims the District may have against the Contractor. If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of City and the Contractor. The City’s written response to the claim, as further documented, shall be submitted to the Contractor within 30 days (if the claim is less than $15,000, within 15 days) after receipt of the further documentation, or within a period of time no greater than that

Page 203 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 25 Spec. No. 24-04 taken by the Contractor in producing the additional information or requested documentation, whichever is greater.

E. Meet and Confer. If the Contractor disputes the City’s written response, or the City fails to respond within the time prescribed, the Contractor may so notify the City, in writing, either within 15 days of receipt of the City’s response or within 15 days of the City’s failure to respond within the time prescribed, respectively, and demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand, the City shall schedule a meet and confer conference within 30 days for settlement of the dispute.

F. Mediation. Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the City shall provide the Contractor a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed.

Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the City issues its written statement. Any disputed portion of the claim, as identified by the Contractor in writing, shall be submitted to nonbinding mediation, with the City and the Contractor sharing the associated costs equally. The City and Contractor shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing, unless the parties agree to select a mediator at a later time.

If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim.

Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator.

For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.

Unless otherwise agreed to by the City and the Contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Public Contract Code Section 20104.4 to mediate after litigation has been commenced.

The mediation shall be held no earlier than the date the Contractor completes the work or the date that the Contractor last performs work, whichever is earlier. All unresolved claims shall be considered jointly in a single mediation, unless a new unrelated claim arises after mediation is completed.

G. Procedures After Mediation. If following the mediation, the claim or any portion remains in dispute, the Contractor must file a claim pursuant to Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code prior to initiating litigation. For purposes of those provisions, the running of the period of time within which a claim must be filed shall be tolled from the time the Contractor submits his or her written claim pursuant to subdivision (a) until the time the claim is denied, including any period of time utilized by the meet and confer conference.

H. Civil Actions. The following procedures are established for all civil actions filed to resolve claims of $375,000 or less:

Within 60 days, but no earlier than 30 days, following the filing or responsive pleadings, the court shall submit the matter to non-binding mediation unless waived by mutual stipulation of both parties or unless mediation was held prior to commencement of the action in accordance with Public Contract Code section 9204 and the terms of this Contract. The mediation process shall provide for the selection within 15 days by both parties of a disinterested third person as mediator, shall be commenced within 30 days of the submittal, and shall be concluded within 15 days from the commencement of the mediation unless a time requirement is extended upon a good cause showing to the court.

Page 204 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 26 Spec. No. 24-04 If the matter remains in dispute, the case shall be submitted to judicial arbitration pursuant to Chapter

2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, notwithstanding Section 1114.11 of that code. The Civil Discovery Act of 1986 (Article 3 (commencing with Section 2016) of Chapter 3 of Title 3 of Part 4 of the Code of Civil Procedure) shall apply to any proceeding brought under this subdivision consistent with the rules pertaining to judicial arbitration. In addition to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, (A) arbitrators shall, when possible, be experienced in construction law, and (B) any party appealing an arbitration award who does not obtain a more favorable judgment shall, in addition to payment of costs and fees under that chapter, also pay the attorney’s fees on appeal of the other party.

I. Government Code Claims. In addition to any and all contract requirements pertaining to notices of and requests for compensation or payment for extra work, disputed work, construction claims and/or changed conditions, the Contractor must comply with the claim procedures set forth in Government Code Sections 900, et seq. prior to filing any lawsuit against the City. Such Government Code claims and any subsequent lawsuit based upon the Government Code claims shall be limited to those matters that remain unresolved after all procedures pertaining to extra work, disputed work, construction claims, and/or changed conditions have been followed by Contractor. If no such Government Code claim is submitted, or if the prerequisite contractual requirements are not satisfied, no action against the City may be filed. A Government Code claim must be filed no earlier than the date the work is completed or the date the Contractor last performs work on the project, whichever occurs first.

A Government Code claim shall be inclusive of all unresolved claims unless a new unrelated claim arises after the Government Code claim is submitted.

J. Non-Waiver. The City’s failure to respond to a claim from the Contractor within the time periods described in this Article or to otherwise meet the time requirements of this Article shall result in the claim being deemed rejected in its entirety.
11-04. Litigation and Forum Selection. Contractor and City stipulate and agree that any litigation relating to the enforcement or interpretation of this contract, arising out of Contractor's performance or relating in any way to the work shall be brought in Mendocino County and that venue will lie in Mendocino County.

Except as otherwise expressly provided by law, the parties waive any objections they might otherwise have to the propriety of jurisdiction or venue in the state courts in Mendocino County and agree that California law shall govern any such litigation.

The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto and, in particular but without limitation, the warranties, guaranties and obligations imposed upon the Contractor and all of the rights and remedies available to the City thereunder, shall be in addition to and shall not be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by law or contract, by special warranty or guaranty, or by other provisions of the contract documents and the provisions of this paragraph shall be as effective as if repeated specifically in the contract documents in connection with each particular duty, obligation, right and remedy to which they apply. All warranties and guaranties made in the contract document shall survive final payment and termination or completion of this contract. The City disclaims an express or implied warranty that the plans and specifications identify all site conditions that could affect the time or cost to complete the Work. 11-05. Waiver. The Contractor shall strictly comply with all notices and other contract requirements. Waiver by the City of any failure of the Contractor to comply with any term of the contract, including the notice provisions, shall not be deemed a waiver of a subsequent breach.

Page 205 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 27 Spec. No. 24-04

TECHNICAL SPECIFICATIONS
SECTION 12. GENERAL INFORMATION
12-01. Scope of Work and Location. All the work to be performed will be within City of Ukiah located at:
• 225 S Orchard Avenue
• Southwest corner of Gobbi/Orchard
• 700 Block of East Gobbi St
The scope of work consists of trenching, backfilling, compacting and installing underground conduits, pedestal and padmount switch box.

The vicinity of the work shall be protected from injury by Contractor during construction and until completion of the work. Contractor shall be liable for all damages to such facilities.

Contractor to furnish all labor, methods, materials, tools, permits, licensing, certification, and equipment necessary to complete the work. All work is to be conducted in accordance with accepted industry practices.

The City Electric Department will not perform any work for the Contractor except in an emergency or as determined necessary by the Project Manager to adequately protect the City’s electrical or other facilities.

Incidental items of construction necessary to complete the whole work in a satisfactory and acceptable manner as shown on the Project Plans and as provided for in the Special provisions and not specifically referred to in this section will be understood to be furnished by the Contractor. All areas or fixtures disturbed by the Contractor’s activities shall be restored to their original condition.

Unless otherwise specified herein, all construction activity, except for emergency situations, will be confined to Monday through Friday between the hours of 7:30 a.m. and 6:00 p.m., to minimize nuisances to local residents. Mufflers and/or baffles will be required on all construction equipment to control and minimize noise. The Contractor must comply with all applicable noise regulations in the City’s Zoning Ordinance.

Saturday, Sunday, holidays, and overtime shall not be regarded as working days. Work shall not be allowed on non-working days without the written approval of the PM. A request for PM approval from the Contractor must be in writing. The Contractor shall pay the City of Ukiah for all overtime labor charges incurred by the City to supervise overtime work by the Contractor’s employees at the rate of $80 per hour per inspector and/or resident engineer. All overtime labor charges shall be deducted from the final payment along with any liquidated damages.

The Contractor should familiarize themselves with the local conditions of the project sites. Failure to do so will in no way relieve them of the responsibility for performing any of the work or operations required as a part of this contract. Further information regarding the work or these specifications can be obtained from Myles Fisette at (707) 463-6225.
12-02. Arrangement of Technical Specifications. The Technical Specifications are arranged in sections covering the various phases of work as follows:

Section No. Title
12 General Information
13 Project Details/Scope of Work
14 Exclusions from General Conditions
15 Amendments to General Conditions

12-03. Arrangement of Plans. Plans delineating the scope of work are provided and indexed per Appendix “A” List of Drawings.

Page 206 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 28 Spec. No. 24-04 12-04. Temporary Facilities. All temporary facilities are the responsibility of the Contractor. The removal of said facilities shall be the responsibility of the Contractor. The Contractor shall be responsible for any and all damages to existing facilities which are a result of the works. 12-05. Stream Pollution. The Contractor shall exercise every reasonable precaution to prevent muddying or silting of live streams, and the Contractor’s attention is called to the fact that the terms of this contract do not relieve him of responsibility for compliance with Section 5650 and 12015 of the Fish and Game code or other applicable statutes relating to pollution prevention or abatement. 12-06. License. The Contractor for the work herein shall have proper equipment and possess the necessary skills to complete the work herein. A City Business License is required to contract the work, and Contractor is responsible for obtaining all necessary licenses or permits. 12-07. Location of Work. The locations of work are listed as:
• 225 S Orchard Avenue
• Southwest corner of Gobbi/Orchard
• 700 Block of East Gobbi St
12-08. Permits. The Contractor shall provide, procure, and pay for all permits required to complete this work. 12-09. Public Convenience and Safety. The Contractor shall conduct operations so as to cause the least possible obstruction and inconvenience to the public traffic. The Contractor shall, at his or her expense, furnish such flag persons and furnish, erect, construct and maintain such fences, barriers, lights, signs, detours, pedestrian walkways, driveway ramps and bridging as may be necessary to give adequate warning to the public that work is in progress and that dangerous conditions exist, to provide access to abutting properties and to permit the flow of pedestrian and vehicular traffic to safely and expeditiously pass until all work is completed. 12-10. Maintaining Traffic. Attention is directed to Section 7-1.08 “Public Convenience. “7-1.09, “Public Safety. “7-1.092. “Lane Closure.” and 7-1.095. “Flagging Costs.” of the California Standard Specifications.

Streets shall be open to through vehicular traffic during non-working hours. All public traffic shall be permitted to pass through the work with as little inconvenience and delay as possible.

Full costs for “Maintaining Traffic”, including “flagging Costs”, shall be considered as included in the various items of work and no additional compensation will be made. 12-11. Warranties. Unless otherwise indicated, the Contractor shall warrant all materials provided and work performed under this contract for a period of one year from the date of final acceptance. He shall replace promptly and at his own expense any materials and/or workmanship which fail during this warranty period. 12-12. Utilities. No water, sewer or electrical services will be provided by the City. It is the contractor’s sole responsibility to arrange such services as necessary.
12-13. Preconstruction Conference. A preconstruction conference will be held before any work will be allowed to commence. This meeting will cover inspection, schedule for work, and among other items, the responsibilities, and procedures of each of the interested parties to assure that the project will be completed in accordance with the contract documents.
12-14. Safety Requirements. The Contractor shall comply with all pertinent provisions of the Department of Labor "Safety and Health Regulations for Construction (29 FCS Part 1518, 36 CFR 7340)", with additions or modifications thereto, in effect during this project.
12-15. Notification of Underground Service Alert (USA). The Contractor shall notify Underground Service Alert (USA) two (2) working days prior to any excavation.

USA dial (toll free) 1-800-227-2600

Page 207 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 29 Spec. No. 24-04 SECTION 13 - PROJECT DETAILS/SCOPE OF WORK
13-01. General. Contractor shall be responsible for furnishing all labor, materials, equipment, tools and incidentals necessary for completing the projects at three different locations as shown on the plans and specifications. Locations of the work will be within City of Ukiah, as more specifically defined in the construction drawings attached with the specification 24-04. • 225 S Orchard Avenue - Work will consist of trenching, backfilling, and compacting, installing 1-4” PVC Schedule 40 conduit, installing one (1) pedestal box pad (provided by City), blacktopping and removing and replacement of sidewalk according to City of Ukiah Electric Department drawing and in conjunction with all specification on the forementioned drawing.
• Southwest corner of Gobbi/Orchard - Work will consist of trenching, backfilling and compacting, installing 4” and 6” PVC Schedule 40 conduits, installing one (1) primary switch box pad (provided by City) and replacement of sidewalk according to City of Ukiah Electric Department drawings and in conjunction with all specification on the forementioned drawing. • 700 Block of East Gobbi St - Work will consist of trenching, backfilling, compacting, and installing conduits, blacktopping, sidewalk removal and replacement, and other incidental and related work, as shown on the plans and specifications.

CUSTOMER SERVICE OUTAGE TIME SHALL BE CUT TO A MINIMUN AND SHALL NOT EXCEED ONE WORKDAY.
13-01 (a). Insurance Requirements. In addition to the project insurance requirements stated in Section 5, 13-02. Materials. Materials shall be new and of merchantable grade, free from defect. Contractor shall be responsible for providing any and all materials necessary for the completion of the project, which include, but are not limited to, all conduits, conduit sweeps and conduit fittings. Conduit sizes shall be as specified on the plans.

Conduit shall be free of dirt, rocks or other obstructions which could prevent, hinder, or harm the installation of cable. Over-Rodding of the conduit shall be completed as indicated on the drawings in Appendix A. Mule Tape must be installed in each conduit. The open end of all conduits must be protected in such a manner that it prohibits dirt and debris from entering. The ends of all stub conduit shall be securely capped. No substitutions shall be permitted from the original specifications unless bidder obtains prior written approval. 13-03. Quantities. The preliminary estimate of the quantities of work to be done and materials to be furnished shown in the proposal are approximate only, being given as a basis for the comparison of bids. The City of Ukiah does not expressly or by implication agree that the actual amount of work will correspond therewith but reserves the right to increase or decrease the amount of any class or portion of work or to omit portions of the work that may be deemed necessary or expedient by the City.

Upon completion of successful bid, the Contractor shall furnish to the Engineer a cost break-down for each contract lump sum item.

The contractor shall determine the quantities of the items required to complete all work shown on the plans.

Such quantities and their values (including labor, equipment, and materials) shall be included in the cost break-down submitted to the Engineer for approval. The sum of the quantity units’ times the unit price shall equal the contract quantities and values used in the cost break-down submitted for approval. Unbalancing of the unit prices will not be allowed.

Overhead, profit, bond premium, temporary construction facilities, and other such items shall be included in each individual unit listed in the cost break-down, however, costs for traffic control system shall not be included.

No adjustment of the compensation will be made in the contract lump sum prices paid for various work items due to any differences between quantities shown in the cost break-down furnished by the Contractor and the quantities required to complete the work as shown on the plans and as specified in these Special Provisions.

Page 208 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 30 Spec. No. 24-04 The cost break-down shall be submitted to the Engineer within 10 working days after the contract has been approved. The cost break-down shall be approved by the Engineer, in writing, before any partial payments for the items of work will be made. The approved cost break-down will be used to determine partial payments during the progress of the work and as the basis of calculating the adjustment of compensation for the items(s) of work due to the changes ordered by the Engineer. When an ordered change increases or decreases the quantities of an approved cost break-down, the adjustment in the compensation will be determined in the same manner specified for increases and decreases in the quantity of a contract item of work in accordance with increases and decreases in the quantity of a contract item of work in accordance with the Contractor bid price.

Additions or deletions in the quantity of work as set forth in these specifications and accompanying drawings for lump sum items may be ordered by the Engineer after the contract price has been adjusted accordingly to the satisfaction of both the Contractor and the City of Ukiah, and they have been accepted in writing by the Engineer.
13-04. Payment. Payment will be at the unit price bid and will be compensation in full for all labor, materials, equipment, tools, including all incidentals. 13-05. Trenching and Conduit. Trench depth and location may have to be adjusted slightly in the field to avoid existing facilities. Sewer and water laterals will be encountered. They will have to be worked around and any damage caused by construction activities are the responsibility of the Contractor. The Contractor shall pothole all underground utility locations to determine exact depth prior to trenching. Any damages to City or other utilities caused by trenching or other project operations shall be the Contractor’s responsibility to repair to predamaged condition.

All conduits shall be mandrelled according to the conduit size. 13-06. Bonding and Grounding If a box is replaced with a ground bed, it must remain intact or be completely replaced should damage occur. This is the responsibility of the Contractor.

Known Ground beds are located at:

SB-N25 (located on drawing 6 of 10), Corner of Gobbi St. and Waugh Lane. 13-07. Maintaining Traffic. The Contractor shall notify local authorities of the Contractor’s intent to begin work at least 5 days before work is begun. The Contractor shall cooperate with local authorities relative to handling traffic through the area and shall make all arrangements relative to keeping the working area clear of parked vehicles.

Lane closures shall conform to the provisions in the section of these special provisions entitled “Traffic Control”.

See Section 13-25 for traffic camera requirements.

Payment – Full compensation for conforming to the requirements of this section shall be considered as included in the prices paid for the various contract items of work involved and no additional compensation will be allowed, therefore.
13-08. Dust Control and Watering. Dust control and watering shall conform to the provisions in Sections 10 "Dust Control" and 17 "Watering" of the California Standard Specifications and these Special Provisions.

The Contractor at their expense shall provide their own water for dust control and project construction.

Necessary precautions to prevent dust nuisance shall be taken during all phases of construction, on nonworking days, and to final acceptance of the work.

Payment for dust control and watering shall be considered as included in the various items of work and no additional compensation will be allowed, therefore.

Page 209 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 31 Spec. No. 24-04 13-09. Traffic Control Traffic control shall conform to Section 12 "Construction Area Traffic Control Devices" of the California Standard Specifications and these Special Provisions. Attention is particularly directed to the "MANUAL OF TRAFFIC CONTROLS FOR CONSTRUCTION AND MAINTENANCE WORK ZONES" published by Caltrans. Nothing in these Specifications is to be construed as to reduce the minimum standards set in said manual.

Traffic shall be maintained at all times as provided in these Special Provisions except as otherwise approved by the Engineer.

The Contractor will be required to keep all residents and businesses notified of the work schedule as it affects their access.

The Contractor shall maintain contact with the Ukiah Electric Utility Department dispatch office regarding start and completion of the following:
• Construction activity that may impede emergency vehicles, school buses, etc. • Construction activity such as trenches or other excavation that prohibit access. • Construction activity that removes a fire hydrant from service.

The Contractor shall provide the name and telephone number of a person directly responsible for the construction activity to the Ukiah Police and Fire Departments and Life Medical Paramedic Ambulance Service The City will furnish "No Parking" signs which shall be posted by the Contractor.

The Contractor shall be responsible for supplying, installing, and maintaining such fences, barriers, lights, signs and flaggers as are necessary to give adequate warning to the public at all times that the road or street is under construction and of any dangerous conditions to be encountered as a result thereof.

All traffic control equipment shall be removed when it is no longer required.

Upon request, the Contractor shall submit to the Engineer a sketch showing the proposed signing and barricading to be used in the project.

All existing warning, regulatory, and information signs shall be maintained in a visible location during all phases of the construction by the Contractor.

If it becomes necessary for the City of Ukiah to replace or place additional barricades to provide adequate safety to the public, the Contractor will be charged $1 per barricade per day or portion thereof plus the cost of placement and removal. The Contractor will also be charged for replacement of damaged City barricades. The Contractor shall furnish and place barricades within 3 working days. No removal charge will be made if the Contractor returns City barricades to the Municipal Service Center.

Full compensation for furnishing all labor, materials, tools, equipment and incidentals for doing all work involved in furnishing and placing barricades, warning devices, and for flaggers as may be required by the Engineer shall be considered as included in the price paid for the various items of work, and no additional compensation will be allowed, therefore.
13-10. Protection of Existing Facilities Protection of existing facilities shall conform to all the applicable provisions in Section 8-1.10 "Utility and Non-Highway Facilities".

All known obstructions to the work are indicated on the plans. However, the City cannot guarantee the accuracy of this information. The Contractor will be held responsible for the maintenance and protection of or damage to existing facilities, structures, obstructions, and all underground facilities shown on the Plans or brought to the Contractor's attention during the work.

Page 210 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 32 Spec. No. 24-04 The Contractor shall notify owner agencies for locations of utilities or facilities prior to excavation.

The owning utility shall be immediately notified of any damage which is caused by the operations of the Contractor to any facility, utility, or structure. At the owning utility's discretion, repairs shall be made by the Contractor at the owning utility's direction or by the utility, all to the satisfaction of the Engineer. 13-11. Removal Methods All portions of existing concrete to be removed shall be removed in a smooth, neat, vertical plane. Where expansion, contraction or construction joints are not present, the concrete shall be saw cut to a minimum depth of 1-1/2 inches. If an expansion, contraction, or construction joint is within 3 feet of the concrete to be removed, the concrete shall be removed to that joint.

Prior to final paving, all portions of existing pavement to be removed shall be cut on a neat, straight line.

Pavement removed outside the removal line shall be cut parallel to and at right angles to the removal line. The face of the cut shall be smooth and shall not overhang the removal area. Drop hammers are not allowed.

Jackhammers may be used if the cuts are overlapped and meet the above criteria. Where edges of remaining pavement are raised by the removal method used, they shall be flattened with a mechanical tamper prior to setting frames or replacing pavement.

Where an excavation leaves less than 2 feet of pavement adjacent to the gutter, the remaining pavement shall be removed and replaced.

All removed material, unless otherwise specified, shall become the property of the Contractor, and shall be disposed of outside of the right-of-way.
13-12. Vacuum Excavation All pothole works to expose existing utilities shall be done by vacuum excavation methods. The preferred method of excavation shall be by high pressure air. Use of water fluid for excavation shall only be by permission of the City Engineer. Maximum dimension of the pothole shall be 12 inches by 12 inches. All excavation material shall be removed and disposed of by the contractor. Backfill material shall be Class 2 aggregate base compacted to 90% relative compaction. Prior to paving, the pothole shall be cut to provide a clean vertical edge to pave against. The final dimension of the pothole prior to paving shall be 12 inches by 12 inches maximum. The asphalt concrete shall be a ½ inch mix having a depth of 4 inches.

All pothole work shall comply with the Traffic Control provisions of these specifications.

Full compensation for furnishing all labor, materials, tools, equipment, and incidentals for doing the work involved in performing the pothole operation shall be considered as included in the price paid for the various items of work, and no additional compensation will be allowed, therefore. 13-13. Pipe and Structure Excavation, Backfill and Compaction Excavation and backfill for pipe, manholes and miscellaneous structures shall conform to the provisions in Section 19.3 "Structure Excavation and Backfill" of the California Standard Specifications, and these Special Provisions.

Pavement and concrete removal shall conform to Section 13-11 "Removal Methods" of these Special Provisions.

All excavation shall be made to the lines and grades shown on the Plans. Trench edges shall be no closer than 1 foot to the toe of the gutter unless otherwise approved by the Engineer. Where mud, peat or any unstable or objectionable material is encountered at or within 6 inches of the bottom of any excavation, such material shall be removed to a depth of at least 12 inches below the established grade and the trench brought to grade by placing a suitable material thoroughly compacted in place, all as approved by the Engineer.

Trench width, bedding and backfill for pipe shall conform to "Pipe Bedding and Backfill Requirements", as shown on plans.

Ponding or jetting of backfill is not allowed unless specifically shown on the Plans.

Trench backfills shall attain a relative compaction of 90 percent around conduit duct bank and 95 percent within

Page 211 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 33 Spec. No. 24-04 30” of finish grade. Backfill compaction within the structural section shall be as shown on the Plans. Structural backfill around all structures and manholes shall attain a relative compaction of 92 percent. The Contractor shall be responsible for scheduling compaction testing per City requirements (required every 50 lineal feet of trench).

The cost for compaction testing shall be included in the total bid cost.

Backfill in street areas shall be brought to subgrade and the existing surfacing shall be replaced with the structural section shown on the Plans.

Trench backfills shall be accomplished as soon as possible after the pipe has been installed.

The Contractor shall conduct the construction operations so that trench backfill at all intersections is adequate to allow 2-way traffic in both directions during all phases of construction unless otherwise specified.

Payment for pipe and structure excavation and backfill shall be considered as included in the price paid for the various items of work requiring excavation and backfill and no additional compensation will be allowed, therefore.
13-14. Excavation Safety Excavation Safety shall conform to the provisions in Sections 5-1.02A "Trench Excavation Safety Plans" and 7-1.01E "Trench Safety" of the California Standard Specifications and these Special Provisions.

In making excavations for the project, the Contractor shall be fully responsible for providing and installing adequate sheeting, shoring, and bracing as may be necessary as a precaution against slides or cave-ins and to fully protect all existing improvements of any kind from damage.

The Contractor shall obtain a permit from the Division of Industrial Safety and shall submit a copy of the approved permit to the Engineer prior to the start of any excavation greater than 5 foot in depth. The cost of the permit shall be included in the total bid cost. If the shoring and bracing plan varies from the shoring system standards established by the Construction Safety Orders, the plan shall be prepared by a registered civil or structural engineer.

The criteria given by the California Department of Industrial Relations are MINIMA for the conditions shown thereon. In addition to shoring the excavation as specified, it shall be the Contractor's responsibility to provide all additional shoring required to support the sides of the excavation against the effects of loads which may exceed those derived by using the criteria set forth by said governing agency. The Contractor shall be solely responsible for any damages which may result from failure to provide adequate shoring to support the excavations under any or all the conditions of loading which may exist, or which may arise during the construction project.

The contract price paid per lump sum for excavation safety shall include full compensation for furnishing all labor, materials, permits and equipment and for doing all work involved as specified under these Special Provisions and no additional compensation will be allowed, therefore. 13-15. Sprinklers and Landscaping All sprinkler systems, landscaping, sod, or turf shall be reinstalled to its original condition.
13-16. Clean-Up Clean-up shall conform to the provisions in Section 22 "Finishing Roadway" of the California Standard Specifications and these Special Provisions.

Upon completion of the work, and prior to requesting final inspection, the work area shall be thoroughly cleaned of all rubbish, construction forms, stakes, excess material, and equipment, and all portions of the work shall be left in a neat and orderly condition. The final inspection will not be made until this has been accomplished.

Full compensation for clean-up shall be considered as included in the price paid for the various contract items of work requiring finishing, and no additional compensation will be allowed, therefore. 13-17. Aggregate Base Aggregate base shall be Class 2 and shall conform to the provisions of Section 26 "Aggregate Bases" of the California Standard Specifications and these Special Provisions.

Page 212 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 34 Spec. No. 24-04 Aggregate grading shall be 3/4" maximum unless otherwise approved by the Engineer. The Contractor shall submit current gradation, R-value, sand equivalent, and durability index test results as requested by the Engineer.

Aggregate base shall not be placed until the subgrade has been approved by the Engineer. In lieu of the placement requirements specified in Section 26, aggregate base material shall be placed upon prepared subgrade in a uniform windrow or layer, and after placing, the material shall be graded, compacted, and watered in accordance with the requirements of Section 26-1.05 "Compaction" of the California Standard Specifications and the construction plans. Motor graders may be used for the aforementioned grading.

Aggregate base shall be compacted as specified in the Standard Specifications to a relative compaction of 95 percent.

Finished grade shall be within 0.05 feet of plan grade.

The contract price paid per ton of aggregate base shall include full compensation for furnishing all labor, materials, tools and equipment and for doing all work involved in placing, compacting and watering aggregate base as shown on the plans and as specified in these Special Provisions, and no additional compensation will be allowed, therefore. 13-18. Asphalt Concrete Asphalt concrete shall be ½-inch maximum, medium grade, Type A and shall conform to these Special Provisions and the following sections of the Standard Specifications:
39-1 General
39-2 Materials
39-3 Storing, Proportioning and Mixing Materials
39-4.01 Subgrade
39-4.02 Prime Coat and Paint Binder
Paving asphalt shall be PG64-16 conforming to the latest published provisions in Section 92, “Asphalts,” of the California Standard Specifications. Asphalt Concrete pavement shall be placed at a minimum compacted thickness as shown on the Plans. Asphalt Concrete pavement shall be placed in lifts; the surface lift shall not exceed a compacted thickness of two (2) inches, initial spreading of asphalt shall be at a mix temperature not less than 250 degrees F. Breakdown compaction shall be completed before the temperature of the mix drops below 200 degrees F. (See Caltrans Std. Spec Section 39-6.01).

Binder Coat (tack coat) shall be Type SS-1, conforming to previsions of the American Asphalt institute Specifications and California Standard Specifications, Section 94, “Asphaltic Emulsions.” All articles apply except Article 94-1.07, “Measurement.”
Measurement: Asphalt concrete will be measured by the ton as determined by the Public Weighmaster Certificates. Duplicate load slips shall be furnished to the Engineer by and at the sole expense of the Contractor. Where the Contractor has performed unauthorized grinding, the Contractor shall backfill with asphalt concrete to the original subgrade plane shown on the Plans at the Contractor’s expense. The Engineer shall calculate the excess quantity of asphalt concrete necessary to backfill to the original subgrade plane and this quantity will be deducted from the total asphalt concrete tonnage installed.” 13-19. Asphalt Concrete Trench Paving. Asphalt concrete and the placing thereof shall conform to the requirements of Section 39, “Asphalt Concrete,” of the California Standard Specifications, and these Special Provisions.

Final asphalt concrete trench paving shall be 0.45’ to 12” outside either side of the trench width.

Asphalts: Temporary paving on all trenches shall be hot mix asphalt concrete installed a minimum 2” thick placed each day over the work.

The amount of asphalt binder to be mixed with the aggregate will be specified by the Engineer at the time of

Page 213 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 35 Spec. No. 24-04 paving. A different asphalt binder content may be specified for each lift and each location.

General Requirements: The Contractor shall provide compaction of backfill and base material as the job progresses, each day. Temporary paving will be placed over the work, each day, leaving not more than 100 feet unpaved. This temporary paving shall be removed for final trench paving. The balance of the trench shall be covered with skid resistant steel plates (with a coefficient of friction of 0.35 or greater per CTM342), capable of sustaining normal (H20) traffic loads without shifting or bouncing and shall be secured per Caltrans requirements. Hot Mix asphalt concrete shall be placed and compacted around all edges of steel plates with a sufficient width and gradual slope to provide a smooth transition to existing pavement.

Finished asphalt trench paving shall be even, smooth riding and have an appearance that is compatible to the surrounding surface, unless proper written approval has been provided by the Engineer.

The Engineer may require additional paving beyond the minimum dimensions shown in STD. 220 (36” beyond the trench wall), or as shown on the plans, where records indicate that the existing pavement or structural section is as shown on the plans.

Payment: Full compensation for furnishing and installing temporary and permanent trench paving shall be considered as included in the prices paid for the pipe items and no additional allowance will be made, therefore. 13-20. Curbs, Sidewalks and Miscellaneous Concrete Curb, gutter, sidewalk, driveways, alley approaches and any other miscellaneous concrete structures shall be constructed as shown on the plans, and applicable City of Ukiah Standard Plans, and shall conform to the provisions in Section 73 "Concrete Curbs and Sidewalks" of the California Standard Specifications and these Special Provisions. Any damage to curbs, sidewalks, and other concrete because of construction activities are the responsibility of the Contractor to repair to predamaged condition. a.) Earthwork: Earthwork shall conform to the plans and Section 13-12 of these Special Provisions.

The area between the right-of-way line and the back of sidewalk shall be graded to 1/4-inch per foot and sufficient compactive effort and moisture shall be applied to this area to prevent settlement.

Voids shall be filled with topsoil, not sand. Water service or other boxes and facilities shall be adjusted to grade.
b.) Curb, gutter, and sidewalk: Curb, gutter and sidewalk shall be of monolithic construction.

Construction joints shall be edged and shall conform to the proposed scoring pattern.

Expansion joint material shall be installed to the full depth of the concrete at locations shown on the plans and as designated by the Engineer.

Side inlets catch basin and drop inlet catch basin concrete may be placed against neat excavation of undisturbed earth.

Concrete retaining walls shall be formed with plywood and all exposed edges shall be edged. After the back form has been removed, the void shall be backfilled to grade with clean native topsoil. c.) Commercial curb, gutter, and sidewalk: Commercial curb, gutter and sidewalk shall be of monolithic construction. Construction joints shall be edged and shall conform to the existing scoring pattern. Curb, gutter and sidewalk shall be constructed per City of Ukiah Standard Plan. d.) Concrete: Portland cement concrete shall be Class "B" conforming to Section 90 "Portland Cement Concrete" of the Standard Specifications with a minimum compressive strength of 2500 psi at 28 days.

All concrete used shall be mixed completely in a truck mixer, commonly known in the industry as "transit-mixed concrete".

Page 214 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 36 Spec. No. 24-04 e.) Forms: Forming requirements shall conform to the provisions in Section 73-1.04 "Forms" of the California Standard Specifications. If clean neat lines can be cut, the Contractor may pour against undisturbed earth with prior approval by the Engineer. If any sloughing or caving of material occurs, both front and back forms may be required.

Forms shall be true to lines and grades as shown on the plans.

Forms previously used shall be thoroughly cleaned before re-use. Before concrete is placed within any form, all inside surfaces of the forms shall be thoroughly coated with an approved oil.

All forms shall be free of any foreign material before placing concrete. f.) Concrete Reinforcement: Mesh and reinforcing steel shall conform to the provisions in Section 52-

1.02 "Materials" of the California Standard Specifications.

All reinforcing steel shall be accurately placed as shown on the plans.

All reinforcement shall be cleaned of dirt, rust, grease, loose scale and any other substance that may prevent concrete bonding. All reinforcement shall be securely positioned and supported so as to maintain the proper position during placement of concrete. g.) Concrete Placement: Concrete shall not be placed without approval of the Engineer. Placing concrete without notifying the Engineer may be reason for rejection of the work.

Prior to placing concrete, the subgrade and inside face of the forms shall be thoroughly wetted as the Engineer may direct.

Concrete shall not be deposited when it appears likely that the air temperature may fall below 40°F during the placing of concrete or within the following 24 hours unless special approval has been received from the Engineer prior to placing of concrete. Concrete which, in the opinion of the Engineer, has been damaged by freezing shall be removed and replaced.

Monolithic curb, gutter and sidewalk or median curb and gutter may be placed with extrusion machinery. The machinery shall be approved by the Engineer prior to use.

The Contractor shall install benchmark monuments as shown on the plans. The City of Ukiah will furnish the benchmark monuments without cost to the Contractor.

If the plans do not call for sidewalk, side inlet catch basins shall be constructed with a 3-foot by 5- foot section unless otherwise indicated on the plans.
h.) Finishing: After steel troweling, the concrete surfaces shall be given a fine hair broom finish.

Brooming on sidewalk shall be transverse to the length of curb.

All exposed concrete surfaces shall be finished unless otherwise directed by the Engineer.

Score marks and weakened plane joints shall be located as shown on the plans and as directed by the Engineer.
i.) Cure: Concrete cure shall be accomplished by either the water, pigmented curing compound or waterproof membrane method and shall conform to the provisions in Section 90-7 "Curing Concrete" of the California Standard Specifications. White pigmented curing compound shall not be used on exposed surfaces.
j.) Tolerances: Dimensional tolerances for concrete work are listed below. Work done outside of these tolerances will be rejected by the Engineer.

Curb, gutter, sidewalk thickness: Up to 1/4-inch below specified thickness.

Page 215 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 37 Spec. No. 24-04 Flow line: Puddles shall not exceed 1/4-inch in depth, 6 inches in width or 10 feet in length.

Grinding more than 1/2-inch and the use of epoxy fillers are not acceptable.

Sidewalk crossfall: Total crossfall on 5-foot sidewalks shall be within 1/2-inch of design.

Catch basins: The opening shall be a full 8 inches across the face of the catch basin with the top properly aligned within 3 inches of the base.
k.) Payment: Curb and gutter, sidewalk, street sign posts, driveways and mow strips shall be paid for under the various contract items and shall include full compensation for furnishing all labor, materials, including the cast-iron frames and grates, adjusting facilities within the sidewalk to grade, grading and adjustments at the back of walk, removal of existing facilities, tools and equipment, and for doing all work involved in their construction as shown on the plans and as specified under these Special Provisions, and no additional compensation will be allowed therefore. 13-21. Soil and Groundwater Disposal.
13-21 (A) General: Bidder’s attention is directed to the fact that the proposed project is in an area that contains no known subsurface petroleum hydrocarbon contamination.

The contractor shall maintain awareness of potential signs of soil and groundwater contamination throughout the project limits and shall notify the City immediately upon discovery. Conditions indicative of contamination may be either visual (staining in soil, sheen on water surface) or olfactory (petroleum hydrocarbon odors.) Upon the discovery of suspected contaminated materials, the Contractor shall immediately provide 40-hour OSHA-HAZWOPER certified workers in the contaminated area. The Contractor shall also provide a field Site Safety Officer that is also an 8-hour OSHA-HAZWOPER Supervisor trained to directly oversee the contaminated materials removal and handling operation. All workers in this circumstance must have their initial and annual renewal refresher training, medical clearance, and personal protection equipment in accordance with 8CCR Section 5192.
13-21 (B) Soil: None of the excavated material shall be disposed of on the work site. All material excavated from trenches in the project area shall be the property of the Contractor. Prior to disposal of any excess material from the work site, the Contractor shall submit to the Engineer written authorization for such disposal and entry permission signed by the approved disposal site. Contractor shall comply with all disposal regulations such as City, County, and/or State permits and license, as may be required. 13-21 (C) Water: Groundwater may be encountered during excavation. If it is encountered, the Contractor shall immediately notify the City. The Contractor shall remove all water which accumulates in the excavation during the progress of work until the pipe or other structures are installed and until backfilling has progressed to a sufficient height to anchor the work against possible flotation or leakage. At all times, the Contractor shall have a minimum of 2 working pumps available for immediate use at all times.

Water accumulated in excavations shall be discharged to the sanitary sewer under the supervision of City staff.

Said water shall be disposed of in a manner as to cause no injury to public or private property or be a menace to public health. Sediment shall be removed from any water to be disposed of, prior to discharge, by placing the pump inlet hose into a sump filled with clean gravel, or a perforated bucket filled with clean gravel. The outlet of the pump shall have a filter sock installed to retain residual sediment.

If any odor, sheen or other visual discrepancy is noted during excavation or discharge, stop pumping and immediately notify the Engineer. Pumped groundwater will not be allowed into any watercourse or storm drain system.

Contractor shall be responsible for constructing, operating, and maintaining all necessary features to complete the work including furnishing, installing and maintaining all pumping and other equipment required to dewater any trenches containing water as may be encountered during performance of the work. Dewatering plan for each occurrence shall be approved by the Engineer prior to implementation. At the permanent conclusion of

Page 216 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 38 Spec. No. 24-04 dewatering operations, all dewatering equipment shall be removed from the job site.

Payment: Full compensation for disposal of all excavated material and trench water, including, but not limited to, transportation costs and soil disposal fees and providing all necessary equipment and labor (including back-up pumping equipment) shall be considered as included in the contract prices paid for various contract items of work and no additional compensation will be allowed therefor. The City will pay discharge fees for the necessary disposal of trench water. 13-22. Traffic Stripes and Pavement Markings Traffic stripes and pavement markings shall conform to the applicable provisions of Section 84, “Traffic Stripes and Pavement Markings,” of the California Standard Specifications, City of Ukiah Standards, and these Special Provisions and shall be placed at the locations shown on the plans.

Stripes and pavement markings shall be thermoplastic.

Existing stripes and pavement markings which are damaged by the work shall be replaced. Replaced sections shall match existing sections. Patching is not acceptable in lieu of complete replacement.

Payment: Traffic Stripes and Pavement Markings shall be paid for at the contract lump sum price, which price shall include full compensation for furnishing all equipment, tools, and labor, and doing all the work involved, as herein specified, including
• removal of existing striping and markings,
• furnishing all paint and glass beads,
• thermoplastic pavement marking material,
• tape,
• eradication of existing and temporary traffic stripes, • temporary traffic stripes and pavement markings,
• replacement of damaged stripes and markings,
and doing all the work involved as herein specified and no additional allowance will be made, therefore. 13-23. Signal, Lighting and Electrical Systems All work shall meet the requirements of Section 86-1.02 “Regulations and Code” of the California Standard Specifications. 13-24. Maintaining Existing Systems The Contractor shall maintain existing signal and lighting systems in accordance with Section 86-1.05 “Maintaining Existing and Temporary Electrical Systems” and these Special Provisions.
13-25. Maintaining Traffic and Pedestrian Operations. The Contractor must so conduct his or her operations so as to cause the least possible obstruction and inconvenience to public traffic. All traffic control and related devices shall conform to requirements set forth in the California MUTCD. All traffic must be permitted to pass through the Work unless otherwise approved by the PM.

Full compensation for conforming to the requirements of this section will be deemed included in the prices paid or the various Contract items of Work and no additional allowances will be made therefore.

Due to the need to accommodate and minimize inconvenience to the public, unless expressly specified or approved in writing by the Department of Public Works, no road closures will be permitted. Public vehicular and pedestrian traffic must be allowed to travel through the Work area with an absolute minimum of interruption or impedance unless otherwise provided for in the Special Provisions or approved in writing by the PM. The Contractor must make provisions for the safe passage of pedestrians around the area of Work at all times. 13-26. Accessibility. Where approved in writing by the PM and the Department of Public Works, the Contractor must construct and maintain detours for the use of public traffic at his or her own expense. Failure or refusal of the Contractor to construct and maintain detours so approved at the proper time will be a material breach of the Contract subject to any and all remedies available pursuant to the Agreement and at law and equity. Such remedies include, but are not limited to, termination.

Page 217 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 39 Spec. No. 24-04 The Contractor will be responsible for keeping all emergency services, including the Ukiah police and fire departments and Department of Public Works informed of obstructions to, or detours around any public or private roads caused by reasons of his or her operations. Where there is a need to close down public streets or thoroughfares for an extended period of time, the Contractor will notify the PM and the Department of Public Works 48 hours in advance. The PM and Department of Public Works Project Analyst can be reached at:

Activity Written Approval Notify E-mail address Contact Phone # Road Closure*
Public Works
Project Manager
Public Safety
Public Works
Project Manager
[email protected]
[email protected]
[email protected]
(707) 463-6262
(707) 467-5719
(707) 467-5775
Lane Closure*
Public Works
Project Manager
Public Safety
Public Works
Project Manager
[email protected]
[email protected]
[email protected]
(707) 463-6262
(707) 467-5719
(707) 467-5775
Driveway or
Property Access
Restriction
Project Manager [email protected] (707) 467-5775 *Requires 48 hr. advanced notification
13-27. Public Safety. The Contractor must at all times conduct the Work in accordance with Construction Safety Orders of the Division of Industrial Safety, State of California, to ensure the least possible obstruction to traffic and inconvenience to the general public, and adequate protection of persons and property in the vicinity of the work.

No pedestrian or vehicle passage may be closed to the public without first obtaining permission of the PM. Should the Contractor fail to provide public safety as specified or if, in the opinion of the PM, the warning devices furnished by the Contractor are not adequate, the City may place any warning lights or barricades or take any necessary action to protect or warn the public of any dangerous condition connected with the Contractor’s operations and the Contractor will be liable to the City for, and the City may deduct from amounts due or that may become due the Contractor under the Contract, all costs incurred including, but not limited to, administrative costs.

Nothing in this section will be construed to relieve the Contractor of the obligation to maintain a safe worksite. This section provides the City and the PM with the right, but not the obligation, to remedy the Contractor’s deficiencies in maintaining a safe worksite.
13-28. Payment. Payment for all work and work requirements specified in this Scope of Work shall be considered as included in the Contract Price and no additional allowances shall be made, therefore.

SECTION 14. EXCLUSIONS FROM GENERAL CONDITIONS
14-01. Provisions to be Excluded from General Conditions. The following designated provisions of the General Conditions are hereby determined to be inapplicable to the proposed work and, therefore, are hereby excluded from the terms of the Notice to Bidders, Proposal, Agreement, and other contract documents as though entirely omitted from said General Conditions:
(1) Section 6-02. Office at the Site
No other exclusions.

SECTION 15. AMENDMENTS TO GENERAL CONDITIONS
15-01. Sections of General Conditions to be Amended. The following designated sections of the Special Provisions are hereby amended to read as follows:

No amendments.

Page 218 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 40 Spec. No. 24-04

BID SUBMITTAL CHECKLIST
The following is a checklist to assist you in your submission of your bid documents. Please make sure you include the following when submitting your bid documents to reduce the risk of having your bid rejected:

Did you include?...
o Proposal (Page 41)
 Unit prices filled out clearly.
 Extended prices filled out clearly and calculated correctly  Total bid amount filled out clearly and calculated correctly  Sign the proposal, and provide complete information
 CLSB No. and expiration date
 Department of Industrial Relations Public Works Contractor Registration Number o Fair Employment Practices Certification (Page 46)
 Filled out completely per instruction
o Worker’s Compensation Certificate (Page 47)
 Filled out completely per instruction
o Certification of Non-Discrimination in Employment (Page 48)  Filled out completely per instruction
o List of Proposed Subcontractors (Page 49)
 Filled out completely per instruction
o Statement of Experience (Page 50)
o Signature of Bidder (Page 51)
 Filled out completely per instruction
 Authorized signature provided
o Bidder’s Bond (Page 52)
 Filled out completely per instruction
o Non-Collusion Affidavit (Page 53)
 Filled out completely per instruction
 Notarized
o Iran Contracting Act Certification (Page 54)
o Addenda Issued
 Check the City website for any addenda issued: www.cityofukiah.com/purchasing. Please note that actual acknowledgment of addenda is not required to submit with your bid. Refer to Section 1-11 and 3-07 of the General Conditions.

Page 219 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 41 Spec. No. 24-04

CITY OF UKIAH

MENDOCINO COUNTY, CALIFORNIA

PROPOSAL
FOR
GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT SPECIFICATION NO. 24-04
The undersigned, as bidder, declares that he or she has examined thoroughly all of the contract documents herein contained, that this proposal is made without collusion with any other person, firm or corporation and that all laws and ordinances relating to the interest of public officers in this contract have been complied with in every respect.

AND he or she proposes and agrees, if this proposal is accepted, 1) that he or she will contract with the City of Ukiah, Mendocino County, California, in the form of the copy of the agreement herein contained
a) to provide all necessary machinery, tools, apparatus and other means of construction; b) to furnish all materials;
c) to provide all superintendence, overhead expenses and all labor and expenses of whatever nature necessary to complete the job in conformity with the specifications and drawings and other contract provisions herein or reasonably implied hereby or as necessary to complete the work in the manner and within the time named herein and according to the requirements and to the reasonable satisfaction of the City Engineer;
d) to pay all charges of freight transportation and hauling; 2) that he or she indemnifies the City against any loss or damage arising from any act of the undersigned as Contractor; and
3) that he or she will accept as full payment therefor the following sums:

Page 220 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 42 Spec. No. 24-04

BIDDING SCHEDULE
In the case of any discrepancy between the unit price and the total set forth for the item, the unit price shall prevail; provided, however, that if the amount set forth as a unit price is ambiguous, unintelligible or uncertain for any reason, or is omitted, or in the case of lump sum items, is not the same amount as the entry in the “Total” column, then the amount set forth in the “Total” column for the item shall prevail in accordance with the following:

1. As to lump sum items, the amount set forth in the “Total” column shall be the unit price;

2. As to unit basis items, the amount set forth in the “Total” column shall be divided by the estimated quantity for the item and the price thus obtained shall be the unit price.

The Total Base Bid shall be the sum of the items in the “Total” column. In case of discrepancy between the sum of the items in the “Total” column and the amount entered as Total Base Bid, the sum of the “Total” column items shall prevail. The bid comparison will be based on the sum of the items in the “total” column for each bidder.

The Unit prices for the various Construction Items below include all costs associated with the General Conditions, Special Provisions, Requirements of the Construction Contract, and represent the total, complete, in-place cost for each specific Construction Item in accordance with the Construction Documents, including all elements, work components, accessories, and connections, shown in applicable details or required to yield a complete, sound and functional component or system appropriate for its intended function, whether or not such is specifically described or listed in any description of measurement or payment. The total amount of the Construction items below shall represent the total and complete cost of the fully functional Project. All work not specifically listed below be required to complete the work of the various construction items and the cost of such shall be considered as included throughout the various unit prices indicated.

Lowest bid will be based on the lowest Base Bid.

Page 221 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 43 Spec. No. 24-04 NAME OF BIDDER:

SPEC #: 24-04
PROJECT NAME: GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT BASE BID ITEM #1
NEW PED - 225 S ORCHARD AVE - BIG LOTS
Item
No. Description Quantity Unit of Measure Unit Price Item Total

1. EXCAVATE, TRENCH, BACKFILL AND
COMPACTION (24”X59” TRENCH) 30 LF $__________ $__________________

2. REMOVE AND REPLACE ASPHALT
CONCRETE (24” TRENCH) 72 SF $__________ $__________________

3. 4” PVC SCH 40 CONDUIT INCLUDING
INSTALLATION (ELECTRIC) 40 FT $__________ $__________________

4. SIDEWALK REMOVAL AND

REPLACEMENT FOR INSTALLATION

OF ELECTRIC, CABLE & AT&T VAULTS

AND BOXES
24 SF $__________ $__________________

5. EXCAVATE, BACKFILL, COMPACTION

AND INSTALL PEDESTAL BOX PAD
(CITY TO PROVIDE)
1 EA $__________ $__________________

6. LANDSCAPE REMOVAL AND

REPLACEMENT
1 LS $__________ $__________________

7. $__________ $__________________

8. $__________ $__________________
TOTAL BID ==>> $__________________
BASE BID ITEM #2
ORCHARD AND GOBBI ST – NEW PADMOUNT SWITCH
Item
No. Description Quantity Unit of Measure Unit Price Item Total

1. EXCAVATE, TRENCH, BACKFILL AND
COMPACTION (24”X59” TRENCH) 80 LF $__________ $__________________

2. 4” PVC SCH 40 CONDUIT INCLUDING
INSTALLATION (ELECTRIC) 30 FT $__________ $__________________

Page 222 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 44 Spec. No. 24-04

3. 6’ PVC SCH 40 CONDUIT INCLUDING
INSTALLATION (ELECTRIC) 100 FT $__________ $__________________

4. SIDEWALK REMOVAL AND

REPLACEMENT FOR INSTALLATION

OF ELECTRIC, CABLE & AT&T VAULTS

AND BOXES
48 SF $__________ $__________________

5. EXCAVATE, BACKFILL, COMPACTION

AND INSTALL PADMOUNT SWITCH

BOX PAD (CITY TO PROVIDE)
1 EA $__________ $__________________
TOTAL BID ==>> $__________________
BASE BID ITEM #3
NEW PADMOUNT SWITCH – 751 EAST GOBBI ST
Item
No. Description Quantity Unit of Measure Unit Price Item Total

1. EXCAVATE, TRENCH, BACKFILL AND
COMPACTION (24”X59” TRENCH) 340 LF $__________ $__________________

2. REMOVE AND REPLACE ASPHALT
CONCRETE (24” TRENCH) 870 SF $__________ $__________________

3. 4” PVC SCH 40 CONDUIT INCLUDING
INSTALLATION (ELECTRIC) 180 FT $__________ $__________________

4. 6’ PVC SCH 40 CONDUIT INCLUDING
INSTALLATION (ELECTRIC) 190 FT $__________ $__________________

5. SIDEWALK REMOVAL AND

REPLACEMENT FOR INSTALLATION

OF ELECTRIC, CABLE & AT&T VAULTS

AND BOXES
12 SF $__________ $__________________

6. EXCAVATE, BACKFILL, COMPACTION

AND INSTALL PADMOUNT SWITCH

BOX PAD (CITY TO PROVIDE)
1 EA $__________ $__________________

7. LANDSCAPE REMOVAL AND
REPLACEMENT 1 LS $__________ $__________________
TOTAL BID ==>> $__________________

Page 223 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 45 Spec. No. 24-04 TOTAL BASE BID AMOUNT IN FIGURES
Total Base Bid (#1 through #3) amount in words:
______________________________________________________________________Dollars $_____________________________
We, the undersigned, acknowledge that the City Council has reserved the right to reject any or all bids and to determine which proposal is, in its opinion, the lowest responsive bid from a responsible bidder and that which it deems in the best interest of the City to accept. We, the undersigned, further agree, if this proposal shall be accepted, to sign the agreement and to furnish the required bonds with satisfactory surety, or sureties, within fifteen (15) calendar days after written notice that the contract is ready for signature; and, if the undersigned shall fail to contract, as aforesaid, it shall be understood that he or she has abandoned the contract and that, therefore, this proposal shall be null and void and the proposal guaranty accompanying this proposal, or the amount of said guaranty, shall be forfeited to and become the property of the City. Otherwise, the proposal guaranty accompanying this proposal shall be returned to the undersigned.

Witness our hands this day of ___________________, 20____.

Licensed in accordance with an act providing for the registration of California Contractors License No. ___________, expiration date _____________.

THE CONTRACTOR'S LICENSE NUMBER AND EXPIRATION DATE STATED HEREIN ARE MADE UNDER PENALTY OF PERJURY.

Department of Industrial Relations Public Works Contractor Registration Number: _____________________ Signature of bidder or bidders, with business name, address, phone number and fax number:
_________________________________________________________________ _________________________________________________________________ _________________________________________________________________ _________________________________________________________________ Notice: In the case of a corporation, give below the addresses of the principal office thereof and names and addresses of the President, Secretary, Treasurer.
_________________________________________________________________ _________________________________________________________________ _________________________________________________________________

Page 224 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 46 Spec. No. 24-04

FAIR EMPLOYMENT PRACTICES CERTIFICATION
TO:_____________________________________________________________ ________________________________________________________________ The undersigned, in submitting a bid for performing the following work by Contract, hereby certifies that he or she has or will meet the standards of affirmative compliance with the Fair Employment Practices requirements of the Special Provisions contained herein.

SPEC 24-04 GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT ________________________________________________________________ (Signature of Bidder)
Business Mailing Address:
_________________________________________________
_________________________________________________
_________________________________________________
Business Location:
_________________________________________________
_________________________________________________
(The bidder shall execute the certification of this page prior to submitting his or her proposal.)

Page 225 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 47 Spec. No. 24-04

WORKER'S COMPENSATION CERTIFICATE
I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for Worker's Compensation or undertake self-insurance in accordance with the provisions of that code and I will comply with such provisions before commencing the performance of the work of this contract.

Witness my hand this________ day of _______________, 200____ Signature of Bidder, with Business Address:
__________________________________________________
__________________________________________________
__________________________________________________
__________________________________________________

Page 226 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 48 Spec. No. 24-04

CERTIFICATION OF NONDISCRIMINATION IN EMPLOYMENT
The bidder represents that he or she has/has not, participated in a previous contract or subcontract subject to either the equal opportunity clause herein or the clause contained in Section 301 of Executive Order 10925; that he or she has/has not, filed all required compliance reports; and that representations indicating submission of required compliance prior to subcontract awards.

Signature and address of Bidder:
__________________________________________________ Date_____________ __________________________________________________
__________________________________________________
__________________________________________________
(This certification shall be executed by the bidder in accordance with Section 60-1.6 of the Regulations of the President's Committee on Equal Employment Opportunity for implementing Executive Orders 10925 and 11114.)

Page 227 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 49 Spec. No. 24-04

LIST OF PROPOSED SUBCONTRACTORS
In compliance with the provisions of Sections 4100-4108 of the California Public Contract Code and any amendments thereof, each bidder shall set forth (a) the name and location of the place of business of each subcontractor who will perform work or labor or render service in or about the construction site or a subcontractor licensed by the State of California who, under subcontract to the prime contractor, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications in an amount in excess of one-half of 1 percent of the total bid and (b) the California Contractor License Number for each subcontractor, and (c) the portion of the work to be done by each subcontractor.(See General Conditions Section 1-09.) Include with the name of each sub-contractor their Department of Industrial Relations Public Works Contractor Registration Number.

SUBCONTRACTOR
NAME

SUBCONTRACTOR

LICENSE NUMBER

SUBCONTRACTOR
DIR

REGISTRATION
NUMBER

SUBCONTRACTOR

BUSINESS

ADDRESS

DESCRIPTION

OF WORK

Page 228 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 50 Spec. No. 24-04

STATEMENT OF EXPERIENCE OF BIDDER
The bidder is required to state below what work of similar magnitude or character he or she has done and to give references that will enable the City Council to judge of his or her experience, skill and business standing and his or her ability to conduct work as completely and rapidly as required under the terms of the contract. ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________

Page 229 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 51 Spec. No. 24-04

SIGNATURE(S) OF BIDDER
Accompanying this proposal is ___________________________________ (insert the words "cash ($)", "cashier's check" or "bidder's bond", as the case may be) in an amount equal to at least 10 percent of the bid.

The names of all persons interested in the foregoing proposal as principals are as follows:

IMPORTANT NOTICE: If bidder or other interested person is a corporation, provide the legal name of corporation and also the names of the president, secretary, treasurer and manager thereof. If a co-partnership, provide the true name of firm and also the names of all individual co-partners composing the firm. If bidder or other interested person is an individual, provide the first and last names in full. _________________________________________________________________ _________________________________________________________________ _________________________________________________________________ Licensed in accordance with an act providing for the registration of Contractors:

License No. ______________________________, License Expiration Date .

Signature(s) of Bidder: ______________________________________________ ______________________________________________
______________________________________________
NOTE: If bidder is a corporation, the legal name of the corporation shall be set forth above together with the signature of the officer or officers authorized to sign contracts on behalf of the corporation; if bidder is a co-partnership, the true name of the firm shall be set forth above together with the signature of the partner or partners authorized to sign contracts in behalf of the co-partnership; and if bidder is an individual, his or her signature shall be placed above. If a member of a partnership, a Power of Attorney must be on file with the Department prior to opening bids or submitted with the bid; otherwise, the bid will be disregarded as irregular and unauthorized.

Business address: ___________________________________________________ ___________________________________________________
Place of residence: ___________________________________________________ ___________________________________________________
Dated: __________________

Page 230 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 52 Spec. No. 24-04

CITY OF UKIAH
Mendocino County, California

BIDDER'S BOND

KNOW ALL MEN BY THESE PRESENTS,
That we, ______________________________________________________________ ________________________________________________________________, as PRINCIPAL and ________________________________________________________________ ________________________________________________________________, as SURETY, are held and firmly bound unto the City of Ukiah in the penal sum of 10 PERCENT OF THE TOTAL AMOUNT OF THE BID of the Principal above named, submitted by said Principal to the City of Ukiah, as the case may be, for the work described below, for the payment of which sum in lawful money of the United States, well and truly to be made, to the City Clerk to which said bid was submitted, we bind ourselves, our heirs, executors, administrators and successors jointly and severally, firmly by these presents. In no case shall the liability of the surety hereunder exceed the sum of $____________________

THE CONDITION OF THIS OBLIGATION IS SUCH,
That whereas the Principal has submitted the above mentioned bid to the City of Ukiah, as aforesaid, for certain construction specifically described as follows, for which bids are to be opened at the Office of the City Clerk, Ukiah Civic Center, Ukiah, California, on June 11, 2024 for GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT, SPEC. NO. 24-04.

NOW, THEREFORE, If the aforesaid Principal is awarded the contract and, within the time and manner required under the specifications, after the prescribed forms are presented to him or her for signatures, enters into a written contract, in the prescribed form, in accordance with the bid and files two bonds with the City of Ukiah, one to guarantee faithful performance and the other to guarantee payment for labor and materials, as required by law, then this obligation shall be null and void; otherwise, it shall be and remain in full force and virtue.

IN WITNESS WHEREOF, we have hereunto set our hands and seals on this ______ day of ________________, A.D. 20_____.
__________________________________________________(Seal) __________________________________________________(Seal) __________________________________________________(Seal) Principal
__________________________________________________(Seal) __________________________________________________(Seal) __________________________________________________(Seal) Surety
Address: __________________________________________________________ __________________________________________________________ __________________________________________________________

Page 231 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 53 Spec. No. 24-04

NON-COLLUSION AFFIDAVIT
Note: Bidder shall execute the affidavit on this page prior to submitting his or her bid.

To City Council, City of Ukiah:

The undersigned in submitting a bid for performing GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT, SPEC. NO. 24-04 by contract, being duly sworn, deposes and says:
that he or she has not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with such contract. __________________________________________________
__________________________________________________
__________________________________________________
Signature(s) of Bidder
Business Address:__________________________________________________ __________________________________________________
__________________________________________________
Place of Residence:__________________________________________________ __________________________________________________
__________________________________________________

NOTARIZATION
Subscribed and sworn to before me this ______ day of _________, 20____. __________________________________________________
Notary Public in and for the County of______________________________, State of California.

My Commission Expires ________________________, 20 ____.

Page 232 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 54 Spec. No. 24-04

IRAN CONTRACTING ACT CERTIFICATION
(Public Contract Code Section 2200 et seq.)
As required by California Public Contract Code Section 2204, the Contractor certifies subject to penalty for perjury that the Contractor is not:
(i) identified on the current list of persons and entities engaging in investment activities in Iran prepared by the California Department of General Services in accordance with subdivision (b) of Public Contract Code Section 2203; or
(ii) a financial institution that extends, for 45 days or more, credit in the amount of $20,000,000 or more to any other person or entity identified on the current list of persons and entities engaging in investment activities in Iran prepared by the California Department of General Services in accordance with subdivision (b) of Public Contract Code Section 2203, if that person or entity uses or will use the credit to provide goods or services in the energy sector in Iran.

Signed______________________________________________________ Titled_______________________________________________________ Firm_________________________________________________________ Date_________________________________________________________ Note: In accordance with Public Contract Code Section 2205, false certification of this form shall be reported to the California Attorney General and may result in civil penalties equal to the greater of $250,000 or twice the Contract amount, termination of the Contract and/or ineligibility to bid on contracts for three years.

Page 233 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 55 Spec. No. 24-04

CITY OF UKIAH
Mendocino County, California

AGREEMENT
FOR
GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT SPECIFICATION NO. 24-04
THIS AGREEMENT, made this ______ day of ___________________, 20____, by and between the City of Ukiah, Mendocino County, California, hereinafter called the City and _______________________ hereinafter called the Contractor,
WITNESSETH:

WHEREAS, the City has caused to be prepared in accordance with law, specifications, drawings and other contract documents for the work herein described and shown and has approved and adopted these contract documents, specifications and drawings and has caused to be published in the manner and for the time required by law a notice to bidders inviting sealed proposals for doing the work in accordance with the terms of this contract and
WHEREAS, the Contractor, in response to the notice to bidders, has submitted to the City a sealed proposal accompanied by a proposal guaranty in an amount of not less than 10 percent of the bid price for the construction of the proposed work in accordance with the terms of this contract and WHEREAS, the City, in the manner prescribed by law, has publicly opened, examined and canvassed the proposals submitted and as a result has determined and declared the Contractor to be the lowest and best regular responsible bidder for the work and for the sums named in the proposal, NOW, THEREFORE, THIS AGREEMENT WITNESSETH:

Article 1. Work to be Done and Contract Days Allowed.

That the Contractor shall provide all necessary machinery, tools, apparatus and other means of construction; shall furnish all materials, superintendence, overhead, expenses, all labor and expenses of whatever nature necessary for completion of the work in conformity with the Special Provisions and other contract documents hereto attached and according to such instructions as may be given by the Engineer. The Contractor shall complete the work within <<NINETY>> (<<90>>) calendar days. Contract days shall be counted starting with the 10th day following receipt of notice that the contract has been executed by the City. Contractor, at his or her option, may begin work prior to start of counting contract days, however, in no event shall the Contractor start work without giving notification to the Engineer at least 72 hours prior to the start of work, without obtaining an encroachment permit from the City, or without having submitted certificates of insurance that have been accepted and approved by the Engineer.

Article II. Contract Prices.

That the City shall pay the Contractor the prices stated in the proposal submitted by the Contractor, for complete performance of the contract by the Contractor. The Contractor hereby agrees to accept the prices as full

Page 234 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 56 Spec. No. 24-04 compensation for all material and appliances necessary to the work, for all labor and use of tools and other implements necessary to execute the work contemplated in this contract; for all loss or damage arising out of the nature of the work or from the action of the elements, or from any unforeseen obstructions or difficulties which may be encountered in the prosecution of the work; for all risks of every description connected therewith; for all expenses of the work, as herein specified; for all liability and other insurance, for all overhead and other expenses incident to the work; all according to the Contract Drawings, the Special Provisions, the Details, the instructions and the requirements of the City.

Article III. Labor Discrimination.

Attention is directed to Section 1735 of the Labor Code, which reads as follows:
"No discrimination shall be made in the employment of persons upon public works because of the race, color, national origin or ancestry, or religion of such persons and every contractor for public works violating this section is subject to all the penalties imposed for a violation of this chapter." In connection with the performance of work under this contract, the Contractor agrees as follows:
(a) The Contractor will not willfully discriminate against any employee or an applicant for employment because of race, color, religion, ancestry, or national origin. The Contractor will take affirmative action to ensure that applicants are employed and that employees are treated during employment without regard to their race, color, religion, ancestry, or national origin. Such action shall include, but not be limited to, the following: employment, upgrading, demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided by the awarding authority setting forth the provisions of this Fair Employment Practice section. (b) The Contractor will send to each labor union or representative of workers with which he or she has a collective bargaining agreement or other contract or understanding, a notice, to be provided by the awarding authority, advising the said labor union or worker's representative of the Contractor's commitments under this section, to employees and applicants for employment. (c) The Contractor will permit access to his or her records of employment, employment advertisements, application forms and other pertinent data and records by the Fair Employment Practices Commission, City of Ukiah or any other appropriate agency of the State of California designated by the awarding authority, for the purposes of investigation to ascertain compliance with the Fair Employment Practices section of this contract.
(d) A finding of willful violation of the Fair Employment Practices section of this Contract or of the Fair Employment Practices Act shall be regarded by the awarding authority as a basis for determining the Contractor to be not a "responsible bidder" as to future contracts for which such Contractor may submit bids, for revoking the Contractor's pre-qualification rating, if any and for refusing to establish, reestablish or renew a pre-qualification rating for the Contractor.

The City of Ukiah shall deem a finding of willful receipt of written notice from the Fair Employment Practices Act to have occurred upon that it has investigated and determined that the Contractor has violated the Fair Employment Practices Act and has issued an order under Labor Code Section 1426 or obtained an injunction under Labor Code Section 1429.

Upon receipt of such written notice from the Fair Employment Practices Commission, the City shall notify the Contractor that unless he or she demonstrates to the satisfaction of the awarding authority within a stated period that the violation has been corrected, his or her pre-qualification rating will be revoked at the expiration of such period.

Page 235 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 57 Spec. No. 24-04 (e) The Contractor agrees that should the City determine that the Contractor has not complied with the Fair Employment Practices section of this Contract, then pursuant to Labor Code Section 1735 and 1775 the Contractor shall, as a penalty to the City, forfeit for each calendar day or portion thereof, for each person who was denied employment as a result of such non-compliance, the penalties provided in the Labor Code for violation of prevailing wage rates. Such monies may be recovered from the Contractor. The City may deduct any such damages from any monies due the Contractor. (f) Nothing contained in this Fair Employment Practices section shall be construed in any manner of fashion so as to prevent the City or the State of California from pursuing any other remedies that may be available at law.
(g) Prior to awarding the Contract, the Contractor shall certify to the awarding authority that he or she has or will meet the following standards for affirmative compliance, which shall be evaluated in each case by the awarding authority:
(1) The Contractor shall provide evidence, as required by the City that he or she has notified all supervisors, foremen and other personnel officers in writing of the content of the anti-discrimination clause and their responsibilities under it.
(2) The Contractor shall provide evidence, as required by the City, that he or she has notified all sources of employees’ referrals (including unions, employment agencies, advertisements, Department of Employment) of the content of the anti-discrimination clause. (3) The Contractor shall file a basic compliance report, as required by the City. Willfully false statements made in such reports shall be punishable as provided by law. The compliance report shall also spell out the sources of the work force and who has the responsibility for determining whom to hire, or whether or not to hire.
(4) Personally, or through his or her representatives, the Contractor shall, through negotiations with the unions with whom he or she has agreements, attempt to develop an agreement which will:
a. Spell out responsibilities for nondiscrimination in hiring, referral, upgrading and training. b. Otherwise implement an affirmative anti-discrimination program in terms of the unions' specific areas of skill and geography to the end that qualified minority workers will be available and given and equal opportunity for employment.
(5) The Contractor shall notify the City of opposition to the anti-discrimination clause by individuals, firms or organizations during the period of its pre-qualification. (h) The Contractor will include the provisions of the foregoing paragraphs 1 through 5 in every first tier subcontract so that such provisions will be binding upon each such subcontractor. (i) The "Fair Employment Practices Certification" must be completed and signed prior to the time of submitting the bid.

Article IV. Parts of the Contract.

That the complete contract consists of the following documents, all of which shall be considered a part of this agreement.

1. Notice to Bidders

2. Wage Rates

3. General Conditions

4. Technical Specifications

Page 236 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 58 Spec. No. 24-04

5. Proposal

6. Fair Employment Practices Certification

7. Agreement

8. Addenda

9. Contract Bonds

10. Contract Drawings and Construction Details

11. Standard Drawings

12. Indemnification Agreement
IN WITNESS WHEREOF, this contract being executed in duplicate and the parties having caused their names to be signed by authority of their duly authorized office this _____ day of _____________, 20____.

CITY OF UKIAH, MENDOCINO COUNTY, CALIFORNIA
By: ______________________________________________________________

CITY MANAGER, CITY OF UKIAH
Attest: ______________________________________________________________

CITY CLERK, CITY OF UKIAH
By: ______________________________________________________________

CONTRACTOR
Attest: ______________________________________________________________ Title: ______________________________________________________________ The foregoing contract is approved as to form and legality this ______ day of ______________, 20 ____. __________________________________________________

CITY ATTORNEY, CITY OF UKIAH

Page 237 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 59 Spec. No. 24-04

INDEMNIFICATION AGREEMENT
This Indemnification Agreement is made and entered in Ukiah, California, on _________________, 20____, by and between the City of Ukiah (Ukiah) and ______________________________________ (Contractor).

Contractor is
_________________________________________________________________________________ ___________________________________________ for Ukiah.

As a condition of issuing the work order, attached hereto, Ukiah requires assurance that Contractor will protect Ukiah from damage or damage claims which arise from its performance of the work.

Accordingly, Contractor agrees as follows:

1. Indemnification. Contractor shall indemnify and hold harmless Ukiah and its officers, agents, and employees from and against any claim, loss, or damage, including the legal and other costs of defending against any claim of damage or loss which arises out of the Contractor’s negligent or wrongful performance under the work order attached hereto, except for claims, losses, or damages resulting from the sole and exclusive negligence or other wrongful conduct of Ukiah or its officers, agents and employees.

CONTRACTOR
BY: _______________________________________________
TITLE: _______________________________________________

Page 238 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 60 Spec. No. 24-04

CITY OF UKIAH
Mendocino County, California

FAITHFUL PERFORMANCE BOND

KNOW ALL MEN BY THESE PRESENTS,
That we the undersigned, ______________________________________________________________ __________________________________________________________________________________, AS PRINCIPAL, and
__________________________________________________________________________________,

AS SURETY,
are held firmly bound unto THE CITY OF UKIAH, hereinafter called the “City”, in the penal sum of dollars ($____________________)
for the payment of which sum we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally.

WHEREAS, the Principal has entered into a certain Contract with the City, dated __________, 20_____, a copy of which is hereto attached and made a part hereof, NOW, THEREFORE, the condition of this obligation is such that if the Principal shall in all respects fully perform the Contract and all duly authorized modifications thereof, during its original term and any extensions thereof that may be granted and during any guaranty period for which the Contract provides, and if the Principal shall fully satisfy all claims, arising out of the prosecution of the work under the Contract and shall fully indemnify the City for all expenses which it may incur by reason of such claims, including its attorney's fees and court costs, and if the Principal shall make full payment to all persons supplying labor, services, materials, or equipment in the prosecution of the work under the Contract, in default of which such persons shall have a direct right of action hereupon; and if the Principal shall pay or cause to be paid all sales and use taxes payable as a result of the performance of the Contract as well as payment of gasoline and special motor fuels taxes in the performance of the Contract and all motor vehicle fees required for commercial motor vehicles used in connection with the performance of the Contract, then this obligation shall be void; otherwise, it shall remain in full force and effect. No modification of the Contract or extension of the term thereof, nor any forbearance on the part of the City shall in any way release the Principal or the Surety from liability hereunder. Notice to the Surety of any such modification, extension, or forbearance is hereby waived.

IN WITNESS WHEREOF, the aforesaid Principal and Surety have executed this instrument and affixed their seals hereto, this ________ day of _______________,20_______.

In the presence of:

WITNESS:
_________________________________
________________________________(SEAL)
(Individual Principal)
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)

Page 239 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 61 Spec. No. 24-04 WITNESS:
____________________________________
______________________________(SEAL)
(Corporate Principal)
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)
ATTEST:

________________________________
(Corporate Principal) Affix
Corporate
Seal
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)
ATTEST:
____________________________ ________________________________ Affix (Corporate Surety) Corporate
Seal
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)
The rate of premium on this bond is $___________________________ per thousand.

The total amount of premium charges is $____________________________.. (The above is to be filled in by Surety Company). (Power of Attorney of person signing for Surety Company must be attached).
(CERTIFICATE AS TO CORPORATE PRINCIPAL)
I,_________________________________________, certify that I am the ______________________________ Secretary of the corporation named as Principal in the foregoing bond; that _______________________________________, who signed the said bond on behalf of the Principal, was then ____________________________________________ of said corporation; that I know his signature, and that his signature thereto is genuine; and that said bond was duly signed, sealed, and attested to for and in behalf of said corporation by authority of its governing body.
____________________________________________ Affix Corporate Seal

Page 240 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 62 Spec. No. 24-04

CITY OF UKIAH
Mendocino County, California

MATERIAL AND LABOR BOND

KNOW ALL MEN BY THESE PRESENTS,
That we the undersigned, ______________________________________________________ __________________________________________________________________________, AS PRINCIPAL, and
__________________________________________________________________________ __________________________________________________________________________, AS SURETY, are held firmly bound unto THE CITY OF UKIAH, hereinafter called the “City” in the penal sum of

dollars ($____________________)
for the payment of which sum we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally.

WHEREAS, the Principal has entered into a certain Contract with the City, dated _________________, 20_____, a copy of which is hereto attached and made a part hereof, NOW, THEREFORE, the condition of this obligation is such that if the Principal shall in all respects fully perform the Contract and all duly authorized modifications thereof, during its original term and any extensions thereof that may be granted and during any guaranty period for which the Contract provides, and if the Principal shall fully satisfy all claims, arising out of the prosecution of the work under the Contract and shall fully indemnify the City for all expenses which it may incur by reason of such claims, including its attorney's fees and court costs, and if the Principal shall make full payment to all persons supplying labor, services, materials, or equipment in the prosecution of the work under the Contract, in default of which such persons shall have a direct right of action hereupon; and if the Principal shall pay or cause to be paid all sales and use taxes payable as a result of the performance of the Contract as well as payment of gasoline and special motor fuels taxes in the performance of the Contract and all motor vehicle fees required for commercial motor vehicles used in connection with the performance of the Contract, then this obligation shall be void; otherwise, it shall remain in full force and effect. No modification of the Contract or extension of the term thereof, nor any forbearance on the part of the City shall in any way release the Principal or the Surety from liability hereunder. Notice to the Surety of any such modification, extension, or forbearance is hereby waived.

IN WITNESS WHEREOF, the aforesaid Principal and Surety have executed this instrument and affixed their seals hereto, this ________ day of _______________,20_______.

In the presence of:

WITNESS:
____________________________________
________________________________(SEAL)
(Individual Principal)
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)

Page 241 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 63 Spec. No. 24-04 WITNESS:
____________________________________
______________________________(SEAL)
(Corporate Principal)
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)
ATTEST:

________________________________
(Corporate Principal) Affix
Corporate
Seal
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)
ATTEST:
____________________________ ________________________________ Affix (Corporate Surety) Corporate
Seal
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)
The rate of premium on this bond is $___________________________ per thousand.

The total amount of premium charges is $____________________________.. (The above is to be filled in by Surety Company). (Power of Attorney of person signing for Surety Company must be attached).
(CERTIFICATE AS TO CORPORATE PRINCIPAL)
I,_________________________________________, certify that I am the ______________________________ Secretary of the corporation named as Principal in the foregoing bond; that _______________________________________, who signed the said bond on behalf of the Principal, was then ____________________________________________ of said corporation; that I know his signature, and that his signature thereto is genuine; and that said bond was duly signed, sealed, and attested to for and in behalf of said corporation by authority of its governing body.
____________________________________________ Affix Corporate Seal

Page 242 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 64 Spec. No. 24-04

DIRECTIONS FOR PREPARATION OF PERFORMANCE AND MATERIAL AND LABOR BOND

1. Individual sureties, partnerships, or corporations not in the surety business will not be acceptable.

2. The name of the Principal shall be shown exactly as it appears in the Contract.

3. The penal sum shall not be less than required by the Specifications.

4. If the Principals are partners or joint venturers, each member shall execute the bond as an individual and state his place of residence.

5. If the Principal is a corporation, the bond shall be executed under its corporate seal.

If the corporation has no corporate seal, it shall so state and affix a scroll or adhesive seal following the corporate name.

6. The official character and authority of the person(s) executing the bond for the Principal, if a corporation, shall be certified by the Secretary or Assistant Secretary thereof under the corporate seal, or copies attached to such records of the corporation as will evidence the official character and authority of the officer signing, duly certified by the Secretary or Assistant Secretary, under the corporate seal, to be true copies.

7. The current power-of-attorney of the person signing for the surety company must be attached to the bond.

8. The date of the bond must not be prior to the date of the Contract.

9. The following information must be placed on the bond by the surety company:
a. The rate of premium in dollars per thousand; and
b. The total dollar amount of premium charged.

10. The signature of a witness shall appear in the appropriate place attending to the signature of each party of the bond.

11. Type or print the name underneath each signature appearing on the bond.

12. An executed copy of the bond must be attached to each copy of the Contract (original counterpart) intended for signing.

Page 243 of 750 ends

GOBBI CKT 202 SWITCHING AND RELIABILITY ENHANCEMENT PROJECT 65 Spec. No. 24-04

CITY OF UKIAH
Mendocino County, California

DEFECTIVE MATERIAL AND WORKMANSHIP (MAINTENANCE) BOND

KNOW ALL MEN BY THESE PRESENTS,
That we, _____________________________________________________________________ __________________________________________________________________, as PRINCIPAL and__________________________________________________________________________ ___________________________________________________________________, as SURETY, are held and firmly bound unto the City of Ukiah as Obligee, in the penal sum of ___________________________________________________________________________________ _________________________________________________________($____________________), (5 PERCENT OF THE FINAL CONTRACT AMOUNT)
to which payment well and truly to be made, we do bind ourselves, our and each of our heirs, executors, administrators’ successors and assigns jointly and severally, firmly by these presents.

WHEREAS, the said Principal entered into a Contract with the City of Ukiah dated_________________________
for _________________________________________________________________________________ ____________________________________________________________________________________ WHEREAS, said Contract has been completed, and was approved on the ______ day of ___________, _________,
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal shall guarantee that the work will be free of any defective materials or workmanship which become apparent during the period of one (1) year following completion of the Contract, then this obligation shall be void, otherwise to remain in full force and effect, provided however, any additional warranty or guarantee whether expressed or implied is extended by the Principal or Manufacturer only, and the surety assumes no liability for such a guarantee.

Signed, sealed, and dated this __________ day of ____________, 20_____. __________________________________________________(Seal) BY:_______________________________________________(Seal) __________________________________________________(Seal) Principal
__________________________________________________(Seal) BY:_______________________________________________(Seal) __________________________________________________(Seal) Surety

Page 244 of 750 ends

W.O.

GRID
SCALE
DWG. No.

SHEET of- 9
1 4
APPROVED BY: TITLE:

AS BUILT
- 1" = 20'

DATE DRAWN CHECKED

ELECTRIC UTILITY DEPARTMENT

DESIGNED
5/7/2024 AMS AMS
NOT TO SCALE.

THEN DRAWING IS
NOT MEASURE 1"

IF THIS BAR DOES
No. REVISIONS DATE DSG. BY BY CKD APPD
Switching and Reliability Enhancement Project
Project Locations - 225 S Orchard Ave, Southwest
corner of Gobbi/Orchard, 700 Block of East Gobbi St
1) CONFORM TO THESE SPECIFICATIONS AND REQUIREMENTS OF THE CITY ENGINEER. 2) COMPACTION: CONFORM TO SECTION 19-5, "COMPACTION" OF CALTRANS STANDARD SPECIFICATIONS, THESE PLANS, AND REQUIREMENTS OF THE CITY ENGINEER. CONTRACTOR TO PROVIDE INDEPENDENT MATERIALS AND COMPACTION TESTING.
3) AGGREGATE SUBBASE: CLASS 3. CONFORM TO SECTION 25, "AGGREGATE SUBBASES", OF CALTRANS STANDARD SPECIFICATIONS. SUBJECT TO CITY ENGINEER'S INSPECTION AND APPROVAL, REUSE EXITING SURFACING AND AGGREGATE BASE. CRUSH A.C. PAVEMENT FOR REUSE AS REQUIRED. IF EXISTING MATERIAL IS INSUFFICIENT IN QUALITY OR QUANTITY USE CLASS 2 AGGREGATE SUBBASE.
4) AGGREGATE BASE: CLASS 2, CONFORM TO SECTION 26, "AGGREGATE BASES", OF CALTRANS STANDARD SPECIFICATIONS. 5) ASPHALT CONCRETE: TYPE B. CONFORM TO SECTION 39, "ASPHALT CONCRETE", OF CALTRANS STANDARD SPECIFICATIONS.
6) FOG SEAL COAT: CONFORM TO SECTION 37, "BITUMINOUS SEALS", OF CALTRANS STANDARD SPECIFICATIONS. 7) CONCRETE: CLASS B. CONFORM TO SECTION 90, "PORTLAND CEMENT CONCRETE", OF CALTRANS STANDARD SPECIFICATIONS.
8) TRAFFIC STRIPES: CONFORM TO SECTION 84, "TRAFFIC STRIPES AND PAVEMENT MARKINGS", OF CALTRANS STANDARD SPECIFICATIONS.
9) ANY SIDEWALK REMOVAL AND REPLACEMENT SHALL BE DONE TO SCORE LINES. 10) TRENCH WIDTH TO BE 24" IN THE STREET AND 12" FOR RESIDENTIAL SERVICE UNLESS OTHERWISE SPECIFIED. DEPTH TO VARY DEPENDING ON CONDUIT SIZE AND CLEARANCE.
11) TWELVE INCHES OF SEPARATION MUST BE KEPT BETWEEN ELECTRIC AND ALL OTHER UTILITIES.

TRENCH DETAILS

IN ROADWAY NOT IN ROADWAY

CURB & SIDEWALK SECTION
A. CONTRACTOR TO FURNISH AND/OR INSTALL:

1. All trenching, backfill and compaction per City Specifications, AT&T requirement and Comcast Specifications. Construction work shall be done according to applicable rules and regulations.

2. Clean sand shall be used to backfill to a minimum of 3 in. above conduit(s) when a single layer of conduit is placed. Slurry cement per Caltrans Specification 19.3.02E shall be used when more than one conduit layer is present or conduits are placed in spacers.

3. All conduit, see Conduit Table A. Including all stubs for future.

4. Concrete bags are required at all vertical 90' degree bends. 2 bags for 1-2 conduits, 6 bags for 3-4 conduits, and 8 bags for 5-6 conduits. The amount of bags may be increased in the field by Project Manager, if required, and will be paid on line item.

5. Remove and replace existing asphalt concrete and sidewalk as required to install conduits and related equipment per City specifications. Please contact COU Public Works Department.

6. Prove and install pull line (Mule Tape - 2500 lbs., 3 4" polyester) in all conduit (electric, phone and cable). All Mule Tape shall have footage markers. UEUD Project manager shall be present for all mandrelling and conduit must be proved in both directions. Conduit line items are paid in actual footage at time of proving conduit.

7. Exact grade and location for all equipment:
a. Primary Vault (installation only) 504 vault with 6" riser and cover Specification # 317 2530 b. Padmount transformer box pad (installation only) Specification # 922 5402 & 317 2425 (4) c. Primary Pedestal enclosure box pad (installation only) Specification # 922 5405 & 317 2431 d. Grounding per Electrical Construction Standard 314 1007 at each primary vault, primary junction box and grounding per Electrical Construction Standard 314 1008 at each transformer pad, primary pedestal enclosure, primary riser and each location otherwise noted on plans. e. Secondary electric boxes (installation only) Specification # 311 2105 f. Bumper posts per City of Ukiah Specification # 326 1503.

8. Excavation, backfill and compaction for primary vaults, including installation of 12" to 18" of drain rock below vault. (Hydro hammer is not to be used around substructures) City of Ukiah to inspect each primary junction box upon project backfill completion. Box to be set level and flush with adjacent paving. Vaults located in traffic locations may require a 2'-3' apron at the discretion of the COUEUD Project Manager.

9. CATV SERVICE VAULTS - shall be N30, N36 & B48 (w/ 10" extension) per Comcast Specifications. Service box shall be Oldcastle Precast and marked CABLE TV. The cover shall be a reinforced concrete lid. Conduit entry and service box placement shall meet Comcast Specifications. Exact grade and location for all CATV equipment shall be met.

10. AT&T SERVICE BOXES - shall be Jensen Precast K243630AT with H-20 traffic rated non-skid covers or approved equal. Exact grade and location for all AT&T equipment shall be met. All conduit entries to AT&T boxes and vaults shall be horizontal.

11. During Construction signage in business districts are required at each end of the project and all intersections indicating businesses are open. Signage must be approved by the City of Ukiah Electric Utility Department.

CITY OF UKIAH TO SUPPLY THE FOLLOWING MATERIALS AND SERVICES:

12. Conductor, terminations, equipment and labor necessary to convert the existing overhead system to an underground system.

13. Answer questions regarding the drawing, specifications and locations of all electrical substructures.

14. Inspection of all electrical substructures prior to backfill.

15. Primary vault(s) (material only).

16. Padmount transformer box pad(s) (material only).

17. Primary pedestal enclosure box pad(s) (material only).

18. Secondary services boxes (material only).

CONSTRUCTION NOTES:
a. Electrical substructures including conduit and grounding shall be inspected by the UEUD for proper installation prior to backfill of any excavation. You may call the UEUD at (707) 467-5775 to schedule inspection. The Contractor shall notify the UEUD 48 hours in advance of any inspection to be performed outside the normal workday (Monday through Thursday) b. Contractor to be responsible for condition of all substructures (for example, trench settlement, damaged substructures, etc.) until one year after the date of completion of project. c. Contractor shall not excavate until all utility agencies have been given the opportunity to mark their facilities in the field. d. Contractor shall pothole all underground utilities locations to determine exact depth prior to trenching. Contractor shall follow all USA laws.
e. All landscape shall be returned to its original condition, or better; including repairs of all water lines that were removed due to construction.
f. All road closures must be approved by the City of Ukiah 72 hours in advance. g. Existing utilities are shown in approximate locations based on available records. Service laterals are not indicated. Contact public works engineering department at 707-463-6282. It is the Contractor's responsibility to determine actual vertical and horizontal alignments of any and all utilities in the vicinity of the work area prior to any work being performed and shall adjust the depth of the new utilities to clear as directed by the Engineer. The City of Ukiah and the Engineer assume no responsibility for underground obstructions that may be encountered. h. Any damages to City or other utilities caused by project operations shall be the contractor's responsibility. Contractor must repair all disturbed or damaged conduit immediately regardless if the conduit appears abandoned and must notify the owner utility for immediate repair. No conduit is to be considered abandoned unless the utility owner gives written permission. i. Caution shall be exercised when digging within the dripline of any tree. Roots larger than 2 inches shall not be cut without permission from the Engineer. In the event that a tree root larger than 2 inches needs to be removed, the root pruning shall be performed by a City approved licensed arborist only. Contact the City Public Works Department for a list of approved arborists, 707-463-6282.
j. Contractor shall protect and preserve City survey monuments. If not possible contractor shall coordinate 10 days in advance with City of Ukiah for referencing of existing monuments prior to work in the area. If monument(s) are disturbed contractor shall reconstruct per City Standards. Please Contact the City Public Works Engineer, 707-463-6284. k. Contractor shall notify all customers within the construction zone of proposed work schedule at the start of project. l. Contractor shall notify all customers 48 hours in advance of any construction or disruption of traffic flow impacting the property and any driveway closures by hanging door knockers and distributing flyers at each residence or business entrance.
m. Contractor shall remove and replace sidewalk and concrete planter strips to the nearest transverse score mark on both sides as required by the Engineer for conduit installations. Contact the City Public Works Engineering Department, 707-463-6282, for sidewalk specifications and concrete color matching. Concrete color must match existing. n. All trenches shall be backfilled and compacted per City Specifications. Compaction tests are required for all trenches in roadway, every 200', and for every intersection crossing. o. Trench depth and location may have to be adjusted in the field to avoid existing facilities. All depth changes must be approved by engineer.
p. All conduit shall be proved with the appropriate size mandrel to match conduit size and must be acceptable to the UEUD.

Conduit shall be free of dirt, rocks or other obstructions which could prevent, hinder or harm the installation of electric cable.

Project Manager shall be present for all mandrelling and conduit must be proved in both directions. Conduit line items are paid by actual footage at time of proving conduit.
q. Mule Tape shall be installed in all conduits (electric, phone & cable). The open end of all conduits must be protected in a manner that prohibits dirt or debris from entering. Mule tape shall have footage markers. r. Maximum deflection of a 20' section of conduit shall be 5” unless pre-made bends are used. s. Standard interlocking conduit spacers that provide a separation of 2" (min) between conduit shall be used, where specified.

Spacers shall be spaced 5' apart (max.) or where conduit transitions are made. Provisions must be made ahead of time to keep conduit from floating during slurry pour.
t. The ends of all stub conduits shall be securely capped. All trenching of electrical conduit shall have tracer tape installed above electrical conduit.
u. The UEUD shall assist the contractor with the installation of all conduit into any energized equipment (vaults, pads or boxes).

An UEUD Qualified Electrical Worker is required to be present during the installation of conduit into any energized equipment. Customer service outage time should be held to a minimum and shall not exceed one working day. All outages shall be coordinated with the City of Ukiah Electric Department.

CONSTRUCTION RESPONSIBILITIES

CONDUIT TABLE A
Size Electric Cable TV Phone Conduit in Trench
1Minimum Radius 90° Elbows
1" 18" 18" - 2" 24" 24" 60"
3" 36" 24" - 4" 36" - 60"
6" 48" - - Conduit Type All PVC 402 PVC 40 PVC 40
Fittings Type All TC-3
Long Line Couplings
Standards All
NEMA TC-2
UL 651
UL 514B
Color All Gray White Gray or
White
Marking All "CATV" Every 5' Streetlight Boring Conduit3Conduit Type 1" HDPE Smoothwall Sch 40 N/A N/A Standards All NEMA TC 7
ANSI D1248 N/A N/A
Color All Gray N/A N/A

1. Conduits shall be joined using a medium body, clear, electrical conduit PVC solvent cement approved by the UEUD.

2. Risers locations: Sweeps Shall be schedule 40 with concrete bags on the vertical 90 degree bends, but shall be schedule 80 and steel conduit coming out of the ground. UEUD requires compaction tests for all trenches in roadway, every 200', and every intersection crossing. Conduit shall be stubbed 6" above ground level and mounted per spec 311 2007.

3. Conduit shall be installed by horizontal directional drilling (boring). Conduit shall be equipped with SILICORE® inner lining or approved equivalent system for ease of installing conductor. Conduit shall be continuous - couplings or joints are not permitted except couplings may be used immediately adjacent to streetlight foundations, junction boxes and /or power sources for connection of a schedule 40 elbow to the HDPE conduit. Couplings shall be of the compression type.

Switching and Reliability Enhancement Project
Project Locations - 225 S Orchard Ave, Southwest corner of Gobbi/Orchard, 700 Block of East Gobbi St

THE PLACEMENT OF BOXES/VAULTS AND CONDUITS AS SHOWN
ON PLANS ARE FOR RECOMMENDED INSTALL ONLY. IT IS THE

RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE CORRECT
LOCATION AND DEPTH WITH APPROPRIATE AGENCIES. NEITHER

UTILITY DESIGN SERVICES LLC NOR THE DESIGNER ASSUME ANY RESPONSIBILITY FOR FINAL INSTALLATION.

NTS

ELECTR IC

U T I L I T Y

C ITY OF UKIAH
FOUNDED 1 8 7 6

MENDOCINO

C O U N T Y
2 Specifications, Contractor Responsibilities, & Notes updated 1/30/2024 ENG DPT KJ ATTACHMENT - 2

Page 245 of 750 ends

VAULT 27 10ORCHS05
Sidewalk Dwy

S ORCHARD AVE STELLA DR
232 599 Dwy
Dwy
Dwy

BIG LOTS
225
Sidewalk Sidewalk
Sidewalk
Sidewalk Sidewalk
Sidewalk
285
195
INTERCEPT (E) 4" PRIMARY CONDUIT & EXTEND TO NEW PED CAP CONDUIT END INTERCEPT (E) 4" PRIMARY CONDUIT GOING TO VAULT 96 & EXTEND TO NEW PED ABANDON 4" PRIMARY CONDUIT SECTION BETWEEN NEW PED & VAULT 27 CAP CONDUIT END. 1-P4'' 1-P4'' 1-P4'' RELOCATE (E) IRRIGATION SPRINKLER OH 3-397 kcmil AL (Lower CKT) OH 3-397 kcmil AL (Top CKT) B AC B AC # 100A (E) 3-6" CONDUITS WITH LOW GAP & ORCHARD CIRCUITS A NEW PED E PERKINS ST

S ORCHARD AVE

STELLA DR

PEACH ST

WARREN DR
POMEROY 14M 14M 14M 14M 14M 14M 14M 18M 18M 14M 208Y/120 T1487 150 T1169 208Y/120 750 T1170 208Y/120 225 T1167 208Y/120 300 T1902 208Y/120 225 28 VAULT-28 VAULT-27 V VVAULT 96 T2167 208Y/120 75 #SB # 100A PED 29 PMS-119 S T2125 25 BC PPB
U.S. HIGHWAY 101 V PED 115 10ORCHS01 10STELL01 10ORCHS02 10ORCHS0310ORCHS04 10ORCHS05
10ORCHS06
10ORCHS07
10ORCHS12 10ORCHS11 10ORCHS08 10PEACH03 10ORCHS09
10PEACH04
10STELL02
10STELL03
10STELL04
10STELL05
10STELL06
10STELL07 10STELL08
10WARRN06
10WARRN07 10WARRN08 10WARRN09 10-29 10-30 10-31 10-32 10-36 10-4310-44 AB 2056 CB 50 CB 314 50CP CB 60 37.5 CP 2027 CB 25 303 CB 37.5 620 BA 37.5 CP 2023 CB 25 #30A # 100A S2S1 V1 V2 S.B. STELLA DR NEW PED NEW PED - SOUTH ELEVATION PED BIG LOTS 1"=3' NEW PED FRONT S ORCHARD AVE NEW PED NEW PED - WEST ELEVATION PED BIG LOTS 1"=3' SIDEWALK SIDEWALK CURB RAMP W.O. GRID SCALE DWG. No. SHEET of- 10 2 4 BIG LOTS - NEW PED 225 S. ORCHARD AVE. APPROVED BY: TITLE: AS BUILT - AS SHOWN No. REVISIONS DSG. BY BY CKD APPD DATE DRAWN CHECKED ELECTRIC UTILITY DEPARTMENT DESIGNED DATE 02/5/22 AMS AMS SCALE 1" = 10' NOT TO SCALE. THEN DRAWING IS NOT MEASURE 1" IF THIS BAR DOESSINGLE LINE CA$LE DIAGRAM NTS ONE LINE DIAGRAM 10ORCHS05 NEW PED 1-4" Pri 1-4" Pri X# (E) 1-4" PRIMARY CONDUIT TO VAULT 96

Page 246 of 750 ends

S ORCHARD AVENUE

E GOBBI STREET
Vault 51
Vault 52
PED 455
V-15
14M

LOWER OH CKT)

UPPER OH CKT)
490
(E) CKT 202 UG
(E) CKT UG TO PED 455
(E) CKT 202 UG
(E) CKT 202 OH TO BE REMOVED
(E) CKT UG TO POLE 14GBBIE23
724 697
MH-26
14ORCHS11
14GBBIE22
14GBBIE21 14GBBIE20
V-1
V-25
INSTALL 2-6"

CONDUITS
INTERCEPT (E) 6"
(CKT 202) CONDUIT &

EXTEND TO NEW PMS

E GOBBI STREET

S ORCHARD AVENUE
(E) 1-6" CONDUIT
INTERCEPT (E) 4" CONDUIT
FROM PED 455 TO VAULT
15 & EXTEND TO NEW PMS TO VAULT 53
NEW
PMS 1-P6''
2-P6''

E GOBBI ST

S ORCHARD AVE

CINDEE DR
14M
150
T1078 208Y/120
75 T1876 208Y/120
75 208Y/120 T1884
T1869 208Y/120
75 480Y/277 T1874
300
PPB
V
V
2 PED 726
V
2A
PED 722
V
1PPB
PPB
V 15
PED 455
1 2
3 PMS
724 S
SB
100A
2B
V
87 V
88 V
V25
89 V
85 V
86 V
14ORCHS11
14GBBIE19
14GBBIE23
Old SUB Pole
90 V PPB PPB
NEW
PMS S
NEW PMS INSTA..ATION DETAI.

GOBBI/ORCHARD SOUTHWEST CORNER 1"=4'

E GOBBI ST

S ORCHARD AVE
A
B
W.O.

GRID
SCALE
DWG. No.

SHEET of
-
14 3 4
APPROVED BY: TITLE:

AS BUILT
- AS SHOWN
No. REVISIONS DSG. BY BY CKD APPD

DATE DRAWN CHECKED

ELECTRIC UTILITY DEPARTMENT

DESIGNED
DATE
02/06/22 AMS AMS
SCALE 1" = 20'
25 1/2"
600A
200A FRONT
70"

81.5"
62 3/4"
27"
(N) 4" CONDUIT
TO PED 455
6"
4"
(N) 6" CONDUIT TO
VAULT 53 FOR 202 CKT
6"
(N) 2-6" CONDUITS
TO VAULT 15 FOR
202 CKT

GOBBI/ORCHARD - NEW PMS

SOUTHWEST CORNER
NOT TO SCALE.

THEN DRAWING IS
NOT MEASURE 1"

IF THIS BAR DOES

ONE LINE DIAGRAM
V-15
NEW
PMS
1-6" Pri (Ckt 202) V-53
SING.E .INE COND7IT DIAGRAM
NTS
1-6" Pri (Ckt 202)
1-6" Pri (Ckt 202)
600A
6"
600A
To PED 455
1-4" Pri

Page 247 of 750 ends

T1409 25 AB (E) 3" PVC 2 - 2 STR AL
S.B. E GOBBI ST BABCOCK LN
Sidewalk
PED 751
PED
700 15-31 UG PRIMARY TO JUNCTION VAULT 82 PG&E-1 A BC (N) 3 - 397 KCM AL 1-P6'' 1-P6'' 1-P6'' 1-P6'' 1-P6'' 1-P6'' 1-P6'' CREEK UG PRIMARY TO PAD TRANS 15-32 UG PRIMARY TO TX 2116, PAD 15-30 CLUB HOUSE DR INSTALL 3 - #397 kcmil AA BETWEEN PG&E-1 AND POLE 15GOBBIE03 INTERCEPT EXISTING PRIMARY CONDUIT AND EXTEND TO PMS 775 Sidewalk Dwy No Sidewalk No Sidewalk No Sidewalk Sidewalk A Sidewalk E GOBBI ST Sidewalk (E) PED 751 Dwy B PG&E-2 15GBBIE03 PMS 775 1-P4'' 1-P4'' 1-P4'' 1-P4'' (E) 3 - 397 KCM AL A BC INTERCEPT EXISTING 1-4" PVC CONDUIT AND EXTEND TO PMS 775 INSTALL 1-4' PVC CONDUIT BTWN 15-31 AND PMS775 AND INSTALL 1-6" PVC CONDUIT BTWN POLE 15GBBIE03 AND PMS775. INSTALL 1-6" PVC CONDUIT BETWEEN PMS775 AND STUB CONDUIT IN STTREET. LOCATION TO BE MARK BY UEUD. BABCOCK LN E GOBBI ST J PED 595 PPB PPB PPB PPB PED 751 T1409 25 AB T1631 480Y/277 500 12470 KV T1421 300 480Y/277 T1787 500 PPB AB T980 75LF AB T2116 25 J V-82 PED 700 PPB PPB 4" EMPTY PVC 6" EMPTY PVC 15GBBIE03 15-34 15-32 15-33 15-31 15-27 15-30 15-26 15-24 PG&E-2 PG&E-1 A BC P (E) 3 - 397 KCM AL CREEK S PMS 775 PG&E-2 CHAIN-LINK FENCE PMS 775 - COND7IT LOCATION DETAIL 1"=4' SIDEWALK FOC GUTTER 97.5" 89.5" 600A 200A FRONT 62 3/4" 6" 4"
(N) 6" CONDUIT TO RISER POLE 15GBBIE03 (N) 4" CONDUIT TO PED 700 200A 4" 4"
(N) 4" CONDUIT TO XFMR 15-31 (N) 4" CONDUIT
TO(E) PPB-1 W.O. GRID SCALE DWG. No. SHEET of- 15 4 4 APPROVED BY: TITLE: AS BUILT - 1" = 20' No. REVISIONS DSG. BY BY CKD APPD DATE DRAWN CHECKED ELECTRIC UTILITY DEPARTMENT DESIGNED DATE 7/13/21 AMS AMS SCALE 1" = 20' NOT TO SCALE. THEN DRAWING IS NOT MEASURE 1" IF THIS BAR DOES SINGLE LINE CABLE DIAGRAM NTS RISER LOCATION POLE 15GBBIE03 NTS ONE LINE DIAGRAM 15GBBIE03 PMS 775 PED 700 1-6" Pri (600A) 1-4" Pri X# 25 1/2" 600A 200A FRONT78" 86" 62 3/4" 6" 4" (N) 6" CONDUIT TO RISER POLE 15GBBIE03 (N) 4" CONDUIT TO PED 700 EAST GOBBI STREET INSTALL PMS 751 202 CIRCUIT EXTENSION 4" 4" (N) 4" CONDUIT TO XFMR 15-31 (N) 4" CONDUIT TO (E) PPB-1 15-31 1-4" Pri 1-6" Pri (600A) (EMPTY) PPB (E) PPB-1 1 RELOCATE PMS TO 775 E GOBBI ST 9/14/22 AMS AMS

Page 248 of 750 ends

ENGINEER'S ESTIMATE OF QUANTITIES FOR BID ITEM #1
NEW PEDESTAL - 225 SOUTH ORCHARD AVE
Item
No. Description Quantity Unit ofMeasure Unit Price Item Total

1. EXCAVATE, TRENCH, BACKFILL AND
COMPACTION (24”X59” TRENCH) 30 LF $145.00 $3,660.00

2. REMOVE AND REPLACE ASPHALT
CONCRETE (24” TRENCH) 72 SF $26 $1,746.00

3. 4” PVC SCH 40 CONDUIT INCLUDING
INSTALLATION (ELECTRIC) 40 FT $6.08 $243.20

4. SIDEWALK REMOVAL AND REPLACEMENT

FOR INSTALLATION OF ELECTRIC, CABLE &

AT&T VAULTS AND BOXES
24 SF $38.00 $912.00

5. EXCAVATE, BACKFILL, COMPACTION AND

INSTALL PEDESTAL BOX PAD (CITY TO

PROVIDE)
1 EA $1500.00 $1,500.00

6. LANDSCAPE REMOVAL AND REPLACEMENT 1 LS $5000.00 $5,000.00

7. MOBILIZATION 1 LS $5000.00 $5000.00

8. DEMOBILIZATION 1 LS $3000.00 $3000.00
Total Bid Amount = $21,061.20
ENGINEER'S ESTIMATE OF QUANTITIES FOR BID ITEM #2
NEW PADMOUNT SWITCH – SOUTHWEST CORNER OF GOBBI/ORCHARD Item
No. Description Quantity Unit ofMeasure Unit Price Item Total

1. EXCAVATE, TRENCH, BACKFILL AND
COMPACTION (24”X59” TRENCH) 80 LF $145.00 $11,600.00

2. 4” PVC SCH 40 CONDUIT INCLUDING
INSTALLATION (ELECTRIC) 30 FT $15.00 $450.00

3. 6’ PVC SCH 40 CONDUIT INCLUDING
INSTALLATION (ELECTRIC) 100 FT $20.00 $2,000.00

4. SIDEWALK REMOVAL AND REPLACEMENT

FOR INSTALLATION OF ELECTRIC, CABLE &

AT&T VAULTS AND BOXES
48 SF $38.00 $1,824.00

5. EXCAVATE, BACKFILL, COMPACTION AND

INSTALL PADMOUNT SWITCH BOX PAD (CITY

TO PROVIDE)
1 EA $3,000.00 $3,000.00
Total Bid Amount = $18,874.00
ENGINEER'S ESTIMATE OF QUANTITIES FOR BID ITEM #3
NEW PADMOUNT SWITCH – 700 BLOCK OF EAST GOBBI STREET
Item
No. Description Quantity Unit ofMeasure Unit Price Item Total

1. EXCAVATE, TRENCH, BACKFILL AND
COMPACTION (24”X59” TRENCH) 340 LF $145.00 $49,300.00

2. REMOVE AND REPLACE ASPHALT
CONCRETE (24” TRENCH) 870 SF $26.00 $22,620.00

3. 4” PVC SCH 40 CONDUIT INCLUDING
INSTALLATION (ELECTRIC) 180 FT $15.00 $2,700.00

4. 6’ PVC SCH 40 CONDUIT INCLUDING
INSTALLATION (ELECTRIC) 190 FT $20.00 $3,800.00

5. SIDEWALK REMOVAL AND REPLACEMENT

FOR INSTALLATION OF ELECTRIC, CABLE &

AT&T VAULTS AND BOXES
12 SF $38.00 $456.00

6. EXCAVATE, BACKFILL, COMPACTION AND

INSTALL PADMOUNT SWITCH BOX PAD (CITY

TO PROVIDE)
1 EA $3,000.00 $3,000.00

7. LANDSCAPE REMOVAL AND REPLACEMENT 1 LS $5,000.00 $5,000.00 Total Bid Amount = $86,876.00
ATTACHMENT - 3

Page 249 of 750 ends
Page 1 of 2 ends

Agenda Item No: 8.c.

MEETING DATE/TIME: 5/15/2024

ITEM NO: 2024-191

AGENDA SUMMARY REPORT
SUBJECT: Approve a Resolution Authorizing the Submission of an Application for Grant Funds for the California Museum Grant Program and Approve Corresponding Budget Amendments if Awarded the Grant.

DEPARTMENT: Community Services PREPARED BY: Neil Davis, Community Services Director PRESENTER: Neil Davis
ATTACHMENTS:

1. Resolution for CA Museum Grant
Summary: Approve the Resolution authorizing the submission of an application for Grant Funds for the California Museum Grant Program and approve corresponding budget amendments if awarded the grant.

Background: Assembly Bill (AB) 716 established the California Cultural and Historical Endowment (CCHE) in 2002. Funds for the CCHE came from Proposition 40, the California Clean Water, Clean Air, Safe Neighborhood Parks, and Coastal Protection Act of 2002. $122 million in grants were distributed competitively for the acquisition, restoration, preservation, and interpretation of historical and cultural resources. In 2013, AB 482 (Atkins) authorized the creation of a specified competitive grant program administered by CCHE to support small capital projects in museums. On September 23, 2018, Senate Bill (SB) 1493 was approved and expanded the museum grant program’s project focus to include exhibits, educational programs, outreach programs, public programs, curriculum, marketing, and collections care in museums. The Budget Act of 2020 (SB 74) states that the California Natural Resources Agency shall prioritize the funds for museums severely affected by COVID-19 and that serve historically underserved communities and/or students subject to Title 1 of the Federal Elementary and Secondary Education Act. The intent of this program is to solicit proposals for program projects or capital projects that assist and enhance museums that are deeply rooted in, and reflective of, previously underserved communities.

The Sunhouse at Grace Hudson Museum is a 1911 redwood Craftsman bungalow that was the home of Grace and John Hudson. It is the cornerstone historic feature of the Grace Hudson Museum experience.

Discussion: The California Museum Grant Program funds capital improvement projects that act to preserve at-risk cultural and natural collections and historic buildings. The Sun House at GHM is a historic building. The roof of the Sun House was last replaced in the 1980s and is now badly in need of replacement. The poor state of the roof places it at increased fire risk. Additionally, the collections are at risk due to temperature swings during loss of power as can happen in Public Safety Powers Shutdown events (PSPS). GHM staff in consultation with the Director of Community Services developed and reviewed a variety of possible projects and concluded protecting the Sun House and Museum collections from fire is the most important immediate need for the GHM as well as being a fundable project.

Staff is still working on the scope and budget of the project but will likely ask for funds to replace the Sun House roof, install fire safe landscaping and a new fire alarm system, and purchase and install an emergency back-up generator. The total grant request will likely be around $350,000 - $400,000. The grant requires a minimum 5% match. Director of GHM David Burton and Director of Community Services Neil Davis plan to work with the Sun House Guild or other volunteers to fundraiser to cover the matching expenses. The grant is due on May 22nd and requires a resolution from the City Council approving the grant application. Staff

Page 250 of 750 ends
Page 2 of 2 ends

recommends Council approve the attached resolution (Attachment 1) authorizing the application for grant funds from the California Museum Grant Program.

Recommended Action: Approve the Resolution Authorizing the Submission of an Application for Grant Funds for the California Museum Grant Program and approve corresponding budget amendments if awarded the grant.

BUDGET AMENDMENT REQUIRED: Yes, contingent on award.

CURRENT BUDGET AMOUNT: 0
PROPOSED BUDGET AMOUNT: TBD
FINANCING SOURCE: Grant and Donations
PREVIOUS CONTRACT/PURCHASE ORDER NO.: NA
COORDINATED WITH: David Burton, GHM Director
DIVERSITY-EQUITY INITIATIVES (DEI): N/A
CLIMATE INITIATIVES (CI): 10a – Protect from dangerous emission by preventing fires.

GENERAL PLAN ELEMENTS (GP):GP-A4 - Public Facilities, Services, and Infrastructure Element

Page 251 of 750 ends

RESOLUTION NO. 2024-

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF UKIAH APPROVING THE APPLICATION

FOR GRANT FUNDS FOR THE CALIFORNIA MUSEUM GRANT PROGRAM WHEREAS, the Legislature and Governor of the State of California have provided funds for the program shown above; and
WHEREAS, the California Natural Resources Agency has been delegated the responsibility for the administration of this grant program, establishing necessary procedures; and WHEREAS, said procedures established by the California Natural Resources Agency require a resolution certifying the approval of application(s) by the Applicant’s governing board before submission of said application(s) to the State; and
WHEREAS the Applicant, if selected, will enter into an agreement with the State of California to carry out the project:

NOW, THEREFORE, BE IT RESOLVED that the Enter Governing Body

1. Approves the filing of an application for the for The Sunhouse: Protecting a Vital, Historic Resource; and

2. Certifies that Applicant understands the assurances and certification in the application package; and

3. Certifies that Applicant or title holder will have sufficient funds to operate and maintain the project(s) consistent with the land tenure requirements or will secure the resources to do so; and

4. Certifies that it will comply with the provisions of Section 1771.5 of the California Labor Code; and

5. If applicable, certifies that the project will comply with any laws and regulation including, but not limited to, the California Environmental Quality Act (CEQA), legal requirements for building codes, health and safety codes, disabled access laws, environmental laws and, that prior to commencement of construction, all applicable licenses and permits will have been obtained; and

6. Certifies that Applicant will work toward the State Planning Priorities intended to promote equity, strengthen the economy, protect the environment, and promote public health and safety as included in Government Code Section 65041.1; and

7. Appoints the City Manager or designee, as agent to conduct all negotiations, execute and submit all documents including, but not limited to applications, agreements, payment requests and so on, which may be necessary for the completion of the aforementioned project(s).

PASSED AND ADOPTED this 15th day of May 2024, by the following roll call vote:

AYES:

NOES:

ABSTAIN:

ABSENT:
_______________________________
Josefina Dueñas, Mayor
ATTEST:
__________________________________
Kristine Lawler, City Clerk
ATTACHMENT 1

Page 252 of 750 ends
Page 1 of 2 ends

Agenda Item No: 8.d.

MEETING DATE/TIME: 5/15/2024

ITEM NO: 2024-192

AGENDA SUMMARY REPORT
SUBJECT: Adopt Resolution Approving Transmission Owner Rate Case Agreement with Northern California Power Agency, and Authorize City Manager to Execute All Necessary Documents.

DEPARTMENT: Electric Utility PREPARED BY: Cindy Sauers, Electric Utility Director PRESENTER: Cindy Sauers, Electric Utility Director
ATTACHMENTS:

1. Transmission Owner Rate Case Agreement Resolution

2. Transmission Rate Case Program Agreement - Final
Summary: Council will consider adopting a Resolution approving the Transmission Owner Rate Case Agreement with Northern California Power Agency (NCPA), and authorize the City Manager or his designee to execute the agreement.

Background: The City is a founding member of NCPA, a joint action agency that was established in 1968 by a group of locally-owned electric utilities to make joint investments in energy resources to ensure an affordable, reliable, clean supply of electricity for its customers. The types of services that NCPA provides to member utilities include power management, scheduling and dispatch services, and legislative and regulatory advocacy. NCPA is governed by a Commission made up of representatives from each member utility.

The City participates in various generation projects through NCPA, including the Geothermal Project; the Calaveras Project, a large hydroelectric project in Calaveras County; and Lodi Energy Center. One component of energy delivery from a generation plant is the transmission system which carries electricity over long distances at high voltages. The City, as a joint owner of transmission facilities, is subject to transmission costs associated with transacting in the California Independent System Operator (CAISO) markets.

Discussion: Historically, the Transmission Agency of Northern California (TANC), a joint action agency of which the City is a member, has acted as the lead agency advocating for Ukiah's interests in Participating Transmission Owner (PTO) rate cases filed with the Federal Energy Regulatory Commission (FERC). Recently, other members of TANC have raised concerns with TANC continuing to act as lead agency in this regard due to cost and resource limitations. To ensure the City, and other interested NCPA members, can continue to participate in rate cases filed at FERC, with the objective of controlling wholesale transmission service costs, members have requested representation from NCPA to act as the lead agency by advocating for member interests at FERC. The services requested include the monitoring, analyzing and participating in transmission owner rate cases, engaging in industry developments, and striving to limit the exposure of members to increasing transmission costs.

This agreement has been reviewed by the NCPA Legal Committee, and has been approved by the NCPA Commission.

Staff recommends adopting a Resolution (Attachment 1) approving the Transmission Owner Rate Case Agreement (Attachment 2) with Northern California Power Agency (NCPA), and authorizing the City Manager or his designee to execute the agreement.

Page 253 of 750 ends
Page 2 of 2 ends

Recommended Action: Adopt Resolution approving the Transmission Owner Rate Case Agreement with Northern California Power Agency, and authorize the City Manager to execute all documents.

BUDGET AMENDMENT REQUIRED: No
CURRENT BUDGET AMOUNT: N/A
PROPOSED BUDGET AMOUNT: N/A
FINANCING SOURCE: N/A
PREVIOUS CONTRACT/PURCHASE ORDER NO.:

COORDINATED WITH: Darcy Vaughn, Deputy City Attorney
DIVERSITY-EQUITY INITIATIVES (DEI):N/A
CLIMATE INITIATIVES (CI):N/A
GENERAL PLAN ELEMENTS (GP):N/A

Page 254 of 750 ends

Attachment 1
RESOLUTION NO. 2024-

RESOLUTION OF THE CITY COUNCIL OF THE CITY OF UKIAH APPROVING THE TRANSMISSION

OWNER RATE CASE PROGRAM AGREEMENT WITH NORTHERN CALIFORNIA POWER AGENCY WHEREAS: NCPA is a public agency pursuant to the Joint Exercise of Powers Act of the Government Code of the State of California and, among other things, is authorized to acquire, construct, finance, and operate buildings, works, facilities and improvements for the generation and transmission of electric capacity and energy for resale; and
WHEREAS: Northern California Power Agency (NCPA) provides various power management and administrative services to its members pursuant to service-based agreements; and WHEREAS: The City of Ukiah (City) is a member of NCPA and currently takes certain power management and administrative services from NCPA; and
WHEREAS: Pursuant to the Power Management and Administrative Services Agreement, services may be requested from NCPA by Members under which no existing Services Agreement is available to satisfy such needs, and at the sole discretion of the Commission, certain agreements may be developed between NCPA and a Member to enable NCPA to provide such special services; and WHEREAS: The City of Ukiah, along with other Members have requested services pertaining to proceedings that effect the California Independent System Operator (CAISO) transmission costs in order to protect participating members’ (Participants) transmission assets and strive to limit the Participants’ exposure to increasing transmission costs when transacting in the CAISO markets; and WHEREAS: NCPA has established the facilities, staff, and the capability for the provision of Services to the Participants; and
WHEREAS: The NCPA Commission adopted Resolution 24-40 on March 28, 2024 approving the Transmission Owner Rate Case Program Agreement; and
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ukiah, that the City Manager is authorized, on behalf of the City of Ukiah, to enter into the Agreement for Transmission Owner Rate Case Program with Northern California Power Agency, including any non-substantial modifications to the Agreement.

PASSED AND ADOPTED at a regular meeting of the City Council of the City of Ukiah on the 15th day of May 2024, by the following roll call vote:

Page 255 of 750 ends

AYES:

NOES:

ABSENT:

ABSTAIN:
_____________________________
Josefina Duenas, Mayor
ATTEST:
_____________________________
Kristine Lawler, City Clerk

Page 256 of 750 ends

TRANSMISSION OWNER RATE CASE

PROGRAM AGREEMENT
Attachment 2

Page 257 of 750 ends

TO Rate Case Program Agreement
i

TABLE OF CONTENTS
RECITALS.................................................................................................................................... 1 Section 1. Definitions ................................................................................................................. 2 Section 2. Services to be Provided, Duties and Standards of Performance ................. 5 Section 3. Administration of Agreement ............................................................................ 8 Section 4. Term and Termination......................................................................................... 9 Section 5. Admission and Withdrawal of Participants .................................................. 10 Section 6. Cost of Services ................................................................................................... 11 Section 7. Billing and Payments ......................................................................................... 12 Section 8. Cooperation and Further Assurances.............................................................. 13 Section 9. Participant Covenants and Defaults................................................................ 14 Section 10. Settlement of Disputes and Arbitration......................................................... 17 Section 11. Miscellaneous ...................................................................................................... 18 EXHIBIT A (List of Participants and Program Participation Percentages)..................A-1

Page 258 of 750 ends

TO Rate Case Program Agreement
1 This TRANSMISSION RATE CASE PROGRAM AGREEMENT (“the
Agreement”) is made effective as of _______________________ by and among the Northern California Power Agency, a joint powers agency of the State of California (“NCPA”) and those of its Members who execute this Agreement (“Participants”).

NCPA and the Participants are referred to herein individually as a “Party” and collectively as the “Parties”.

RECITALS
A. NCPA has heretofore been duly established as a public agency pursuant to the Joint Exercise of Powers Act of the Government Code of the State of California and, among other things, is authorized to acquire, construct, finance, and operate buildings, works, facilities and improvements for the generation and transmission of electric capacity and energy for resale.

B. Each of the Participants is a signatory to the Joint Powers Agreement which created NCPA and therefore is a Member.

C. Each of the Participants to this Agreement have executed the Power Management and Administrative Services Agreement, dated October 1, 2014, which establishes the framework under which Members who are signatory to the Power Management and Administrative Services Agreement may enter into one or more Service Agreements with NCPA.

D. Pursuant to the Power Management and Administrative Services Agreement, from time to time special conditions or requirements for services may be requested from NCPA by Members under which no existing Services Agreement is available to satisfy such needs, and at the sole discretion of the Commission, certain “one-off” agreements maybe developed between NCPA and a Member, or group of Members, to enable NCPA to provide such special services.

Page 259 of 750 ends

TO Rate Case Program Agreement
2 E. The Participants have requested NCPA to establish facilities, staff and the capability to act on behalf of the Participants to engage in certain activities, either directly, indirectly, or in conjunction with legal counsel and subject matter experts, pertaining to proceedings that effect the CAISO transmission costs, or other transmission costs as may be applicable, to protect the Participants’ transmission assets and to strive to limit the Participants’ exposure to increasing transmission costs when transacting in the CAISO markets, other markets, or as otherwise may be applicable.

F. In response to the Participants’ desire for NCPA to engage in the activities further described in this Agreement, NCPA has established the facilities, staff and the capability for the provision of Services to the Participants in accordance with this Agreement.

G. Each Participant agrees to pay its equitable share of costs associated with NCPA’s provision of Services, in accordance with the Power Management and Administrative Services Agreement and this Agreement.

H. The Participants further desire, insofar as possible, to insulate other Members, whether or not such Members are also Participants, from risks inherent in the services and transactions undertaken on behalf of any given Member or group of Members.

I. Upon full execution of this Agreement, this Agreement shall be deemed a Special Conditions Services Agreement under the Power Management and Administrative Services Agreement by the Commission.

J. Each of the Parties intends to observe the provisions of this Agreement in good faith and shall cooperate with all other Parties in order to achieve the full benefits of joint action.

NOW, THEREFORE, the Parties agree as follows:

Section 1. Definitions.

Page 260 of 750 ends

TO Rate Case Program Agreement
3 1.1 Definitions. Whenever used in this Agreement (including the Recitals hereto), the following terms shall have the following respective meanings, provided, capitalized terms used in this Agreement (including the Recitals hereto) that are not defined in Section 1 of this Agreement shall have the meaning indicated in Section 1 of the Power Management and Administrative Services Agreement:

1.1.1 “Administrative Services Costs” means that portion of the NCPA administrative, general and occupancy costs and expenses, including those costs and expenses associated with the operations, direction and supervision of the general affairs and activities of NCPA, general management, treasury operations, accounting, budgeting, payroll, human resources, information technology, facilities management, salaries and wages (including retirement benefits) of employees, facility operation and maintenance costs, taxes and payments in lieu of taxes (if any), insurance premiums, fees for legal, engineering, financial and other services, power management services, general settlement and billing and general risk management costs, that are charged directly or apportioned to the provision of Services pursuant to this Agreement. Administrative Services Costs as separately defined herein and used in the context of this Agreement is different and distinct from the term Administrative Services Costs as defined in Section 1 of the Power Management and Administrative Services Agreement.

1.1.2 “Agreement” means this Transmission Rate Case Program Agreement, including all Exhibits attached hereto.

1.1.3 “All Resources Bill” means the single, combined monthly bill from NCPA to a Participant with respect to all NCPA services, programs and NCPA Projects.

1.1.4 “Defaulting Participant” has the meaning set forth in Section

9.2 of this Agreement.

Page 261 of 750 ends

TO Rate Case Program Agreement
4 1.1.5 “Effective Date” has the meaning set forth in Section 4.1 of this Agreement.

1.1.6 “Event of Default” has the meaning set forth in Section 9.2 of this Agreement.

1.1.7 “NCPA” has the meaning set forth in the recitals hereto.

1.1.8 “Participant” has the meaning set forth in the recitals of this Agreement. Participants to this Agreement are listed in Exhibit A of this Agreement.

1.1.9 “Party” or “Parties” has the meaning set forth in the recitals hereto; provided that “Third Parties” are entities that are not part to this Agreement.

1.1.10 “Power Management and Administrative Services Agreement” means the NCPA Power Management and Administrative Services Agreement, dated as of October 1, 2014 between NCPA and the Members who are signatories to that agreement by which NCPA provides Power Management and Administrative Services.

1.1.11 “Program Participation Percentage” means the Participant Program Participation Percentages set forth in Exhibit A of this Agreement.

1.1.12 “Services” has the meaning set forth in Section 2.1 of this Agreement.

1.1.13 “Term” has the meaning set forth in Section 4.1 of this Agreement.

1.1.14 “Transmission Owner” or “TO” has the meaning set forth in the CAISO Tariff.

1.2 Rules of Interpretation. All words and references as used in this Agreement (including the Recitals hereto), unless in any such case the context requires

Page 262 of 750 ends

TO Rate Case Program Agreement
5 otherwise, shall be interpreted pursuant to Section 1.2 of the Power Management and Administrative Services Agreement.

Section 2. Services to be Provided, Duties and Standards of Performance.

2.1 Services. The purpose of this Agreement is to set forth the terms and conditions under which NCPA, acting on behalf of the Participants, may engage in certain activities, either directly, indirectly, or in conjunction with legal counsel and subject matter experts, pertaining to proceedings that effect CAISO transmission costs, or other transmission costs as may be applicable, to protect the Participants’ transmission assets and to strive to limit the Participants’ exposure to increasing transmission costs when transacting in the CAISO markets, other markets, or as otherwise may be applicable (the “Services”). Participants shall only be responsible to pay for Services performed and costs incurred subsequent to the effective date of this Agreement. Services provided in accordance with this Agreement generally include the following:

2.1.1 Representing the interests of the Participants by monitoring, analyzing, and participating in TO rate cases before FERC and any related judicial appeals, where this applies to TO rate cases and new related transmission activity matters that are filed;

2.1.2 Engaging in other related filings and industry developments that affect the cost or provision of transmission service under TO rate cases; and

2.1.3 Engaging in other transmission cost related activities as may be approved by the Participants.

2.2 Qualified Subject Matter Experts. NCPA’s provision of Services under this Agreement may be supported by legal services and other specialized services relevant to NCPA’s participation in proceedings that are performed by qualified subject matter experts and/or witnesses. All costs incurred by NCPA associated with the

Page 263 of 750 ends

TO Rate Case Program Agreement
6 acquisition of legal services support, or qualified subject matter experts support, associated with the Services Agreement shall be considered a Services cost pursuant to this Agreement.

2.3 Coordination with Third Parties. As part of NCPA’s duties under this Agreement, NCPA shall strive to work collaboratively with other Third Party intervenors and relevant parties, and where practicable, build alliances and find common interest in promoting the Participants’ interest consistent with the goals and objectives established pursuant to Section 2.8 of this Agreement. Such efforts include building coalitions, where strategically and economically viable, to support the alignment with other intervenors or to form “joint intervenor” perspectives for engaging in activities related to the Services provided hereunder. This joint effort may include coordinating and sharing responsibilities on areas of common interest to ensure the most efficient advancement of the Participants’ interest, and to reduce redundancy in the Services provided by NCPA.

2.4 Participant Duties. The duties of the Participants under this Agreement are to:

2.4.1 Timely provide information to NCPA that is required for NCPA to perform Services.

2.4.2 Make timely payments to NCPA for Services invoiced by NCPA to Participants in accordance with Section 7 of this Agreement.

2.4.3 Provide staff and other assistance, as may be required from time to time, to the extent necessary for NCPA to fulfill its duties under this Agreement.

2.5 NCPA Duties. NCPA’s General Manager, or his or her designee, shall establish and maintain the facilities, staff and the capability to act on behalf of the

Page 264 of 750 ends

TO Rate Case Program Agreement
7 Participants and provide Services to the Participants in accordance with this Agreement.

2.6 Standard of Performance. NCPA will perform Services using the level of skill and attention reasonably required to complete the Services in a competent and timely manner.

2.7 Assignment of Personnel. NCPA shall assign only competent personnel to perform Services pursuant to this Agreement.

2.8 Time. NCPA shall devote such time to the performance of Services pursuant to this Agreement as may be reasonably necessary to meet the standards of performance provided in Section 2.6, and to satisfy NCPA’s obligations hereunder.

2.9 Consultation with Participants. The General Manager shall consult with the Participants from time to time, as needed, to advise him or her on a particular matter relevant to this Agreement. Each year, the General Manager shall propose to the Participants, as part of the Annual Budget process, specific goals and objectives for NCPA staff as such relate to this Agreement. NCPA shall provide periodic reports to the Participants regarding progress toward meeting the proposed goals and objectives.

The periodic reports may include the following information:
(a) Overview of relevant proceedings and known schedules; (b) Assessment of the financial impact to the Participants, to the extent practicable;
(c) Scope of NCPA’s potential engagement in each TO rate case; (d) Identification of potential legal actions that the Participants should consider and the likelihood of success (by argument if practicable); (e) Estimates of potential benefits and costs associated with engagement, to the extent practicable; and

Page 265 of 750 ends

TO Rate Case Program Agreement
8 (f) Summary of NCPA and Third Party issues and levels of participation.

Section 3. Administration of Agreement.

3.1 Commission. The Commission is responsible for the administration of this Agreement. Each Member shall be represented by its Commissioner or their designated alternate Commissioner (“Alternate”) pursuant to the Joint Powers Agreement. Each Commissioner shall have authority to act for the Participant under this Section 3 with respect to matters pertaining to this Agreement.

3.2 Duties and Authorities. In addition to the administration of this Agreement, the duties and authorities of the Commission are as specified in the Joint Powers Agreement and the NCPA Commission Bylaws.

3.3 Forum. Whenever any action anticipated by this Agreement is required to be jointly taken by the Participants, such action shall be taken at regular or special meetings of the NCPA Commission; provided, however, activities associated with NCPA’s provision of Services and normal day-to-day engagement as described in Section 2.1 of this Agreement, are hereby delegated to the General Manager of NCPA, or his or her designee, and are not considered to be matters related to the Commission’s general administration of this Agreement, and therefore are not subject to the administrative procedures set forth in this Section 3.

3.4 Quorum. For purposes of acting upon matters that relate to the administration of this Agreement, a quorum of the Commission shall consist of those Commissioners, or their designated Alternates, representing a numerical majority of the Participants.

3.5 Voting. For acting upon matters that relate to the general administration of this Agreement, each Participant shall have the right to cast one (1) vote. Actions of the Commission shall be effective only upon an affirmative vote of Participants

Page 266 of 750 ends

TO Rate Case Program Agreement
9 representing a combined Program Participation Percentage of eighty percent (80%) or more.

3.6 Adoption and Amendment of Annual Budget. Annually, the Commission shall adopt an Annual Budget, which includes, but is not limited to, all costs attributed to Services, for at least the next succeeding Fiscal Year in accordance with the NCPA Joint Powers Agreement and this Agreement. Provided, however, that the Commission may in its discretion adopt a two-year budget if permitted to do so by the NCPA Commission Bylaws or the Joint Powers Agreement.

3.7 Facilities Committee. The Facilities Committee has been established pursuant to the Amended and Restated Facilities Agreement to act as an advisory committee to the Commission. The Commission or General Manager may refer matters pertaining to the administration of this Agreement to the Facilities Committee for review and recommendation, including, but not limited to, proposed amendments to this Agreement. If the Commission or General Manager refers matters pertaining to the administration of this Agreement to the Facilities Committee, NCPA will provide a copy of the public notice of the Facilities Committee meeting at which the matter will be discussed to the Participants. The Facilities Committee may act upon such matters referred to it by the Commission in accordance with the procedures, including the general administration quorum and voting procedures, set forth in the Amended and Restated Facilities Agreement. Any recommendation of the Facilities Committee shall be made to the Commission and others, as appropriate, in coordination with the General Manager.

Section 4. Term and Termination.

4.1 Effective Date. This Agreement shall become effective on the first day of the month after which it has been duly executed by all Participants, and delivered to

Page 267 of 750 ends

TO Rate Case Program Agreement
10 and executed by NCPA (the “Effective Date”). NCPA shall notify all Participants in writing of the Effective Date.

4.2 Term and Termination. The term (“Term”) Agreement shall continue in full effect until terminated by consent of all Parties.

Section 5. Admission and Withdrawal of Participants.

5.1 Admission of a New Participant. Following the initial Effective Date of this Agreement, a Member may voluntarily elect to execute this Agreement and become a Participant provided that such joinder is (i) approved by the NCPA Commission in accordance with Section 3.5 of this Agreement, and (ii) if such joinder is approved by the NCPA Commission as set forth herein, the Commission shall also amend the Program Participant Percentages set forth in Exhibit A to this Agreement to include the Program Participant Percentage for the new Participant as determined by the NCPA Commission. Subject to the requirement of this Section 5.1, such Member will become a Participant effective on the date of its delivery to NCPA of an executed counterpart of this Agreement.

5.2 Withdrawal of Participants. Any Participant may withdraw from this Agreement (“Withdrawing Participant”) by submitting notice, in writing to all Parties at least two (2) years in advance of the effective date of such withdrawal, provided that such withdrawal shall only be effective on the last day of a Fiscal Year and that the Withdrawing Participant has fully satisfied all obligations it has incurred under this Agreement. The two (2) year duration of the notice requirement may be waived or reduced by the Commission in its sole discretion. Withdrawal by any Participant shall not terminate this Agreement as to the remaining Participants.

5.3 No Effect on Prior Liabilities. Withdrawal by any Participant will not terminate any ongoing or un-discharged liabilities, credits or obligations, including any contingent liabilities, credits or obligations, resulting from this Agreement until they are

Page 268 of 750 ends

TO Rate Case Program Agreement
11 satisfied in full, or such Withdrawing Participant has provided a mechanism acceptable to NCPA, for the satisfaction in full thereof.

5.4 A Withdrawing Participant shall not be obligated to compensate the remaining Participants for loss of any benefits that would have accrued to the remaining Participants if the Withdrawing Participant had continued its participation.

Nor shall the remaining Participants be obligated to compensate the Withdrawing Participant for any benefits that accrue to the remaining Participants because of the withdrawal. Reallocation of the costs and benefits of continuing under this Agreement after a Participant has withdrawn shall not give rise to any claim against a Withdrawing Participant by the remaining Parties. Nor shall any of the remaining Parties be obligated to compensate the Withdrawing Participant for any benefits that accrue to the remaining Parties because of such a reallocation of costs and benefits.

5.5 Associated Costs. A Withdrawing Participant shall reimburse NCPA for any and all costs resulting from the withdrawal, including but not limited to the legal, accounting, and administrative costs of winding up and assuring the complete satisfaction and discharge of the Withdrawing Participant’s liabilities, credits or obligations, including any contingent liabilities, credits or obligations.

Section 6. Cost of Services.

6.1 Cost Allocation. All costs associated with NCPA’s provision of Services to the Participants, including, but not limited to, Administrative Services Costs and costs associated with NCPA’s acquisition of legal services and qualified subject matter experts services, shall be allocated among the Participants in accordance with this Agreement and the Power Management and Administrative Services Agreement. Costs allocated among the Participants in accordance with this Agreement shall be allocated to each Participant in proportion to such Participant’s Program Participation Percentage as set forth in Exhibit A of this Agreement.

Page 269 of 750 ends

TO Rate Case Program Agreement
12 6.2 Program Participation Percentages. The Program Participation Percentages as set forth in Exhibit A of this Agreement may be amended from time to time, including to account for the addition or withdrawal of a Participant as set forth in Section 5 of this Agreement, by the Commission in accordance with the voting procedures set for in Section 3 of this Agreement.

Section 7. Billing and Payments.

7.1 Invoices. NCPA will issue an invoice to each Participant for its share of costs associated with Services, and all other costs for services provided in accordance with this Agreement. Such invoice may be either the All Resources Bill or separate special invoice, as determined by NCPA. Such invoices will be made pursuant to the requirements and procedures provided for in this Agreement and all other applicable agreements. At NCPA’s discretion, invoices may be issued to Participants using electronic media or physical distribution.

7.2 Payment of Invoices. All invoices delivered by NCPA (including the All Resources Bill) are due and payable thirty (30) Calendar Days after the date thereof; provided, however, that any amount due on a day other than a Business Day may be paid on the following Business Day.

7.3 Late Payments. Any amount due and not paid by a Participant in accordance with Section 9.2 shall be considered late and bear interest computed on a daily basis until paid at the lesser of (i) the per annum prime rate (or reference rate) of the Bank of America NT&SA then in effect, plus two percent (2%) or (ii) the maximum rate permitted by law.

7.4 Billing Disputes. A Participant may dispute the accuracy of any invoice issued by NCPA under this Agreement by submitting a written dispute to NCPA, within thirty (30) Calendar Days of the date of such invoice; nonetheless the Participant shall pay the full amount billed when due. If a Participant does not timely question or

Page 270 of 750 ends

TO Rate Case Program Agreement
13 dispute the accuracy of any invoice in writing the invoice shall be deemed to be correct.

Upon review of a submitted dispute, if an invoice is determined by NCPA to be incorrect, NCPA shall issue a corrected invoice and refund any amounts that may be due to the Participant. If NCPA and the Participant fail to agree on the accuracy of an invoice within thirty (30) Calendar Days after the Participant has disputed it, the General Manager shall promptly submit the dispute to the Commission for resolution.

If the Commission and the Participant fail to agree on the accuracy of a disputed invoice within sixty (60) Calendar Days of its submission to the Commission, the dispute may then be resolved under the mediation and arbitration procedures set forth in Section 10 of this Agreement. Provided, however, that prior to resort to either mediation or arbitration proceedings, the full amount of the disputed invoice must have been paid.

7.5 Billing/Settlement Data and Examination of Books and Records.

7.5.1 Settlement Data. NCPA shall make billing and settlement data available to the Participants in the All Resources Bill, or other invoice, or upon request. NCPA may also, at its sole discretion, make billing and settlement support information available to Participants using electronic media (e.g. electronic data portal). Procedures and formats for the provision of such electronic data submission may be as established by the NCPA Commission from time to time.

Without limiting the generality of the foregoing, NCPA may, in its reasonable discretion, require the Participants to execute a non-disclosure agreement prior to providing access to the NCPA electronic data portal.

7.5.2 Examination of Books and Records. Any Participant to this Agreement shall have the right to examine the books and records created and maintained by NCPA pursuant to this Agreement at any reasonable, mutually agreed upon time.

Section 8. Cooperation and Further Assurances.

Page 271 of 750 ends

TO Rate Case Program Agreement
14 8.1 Each of the Parties agree to provide such information, execute and deliver any instruments and documents and to take such other actions as may be necessary or reasonably requested by any other Party which are consistent with the provisions of this Agreement and which do not involve the assumption of obligations other than those provided for in this Agreement, in order to give full effect to this Agreement and to carry out the intent of this Agreement.

Section 9. Participant Covenants and Defaults.

9.1 Each Participant covenants and agrees: (i) to make payments to NCPA, from its Electric System Revenues, of its obligations under this Agreement as an operating expense of its Electric System; (ii) to fix the rates and charges for services provided by its Electric System, so that it will at all times have sufficient Revenues to meet the obligations of this Agreement, including the payment obligations; (iii) to make all such payments due NCPA under this Agreement whether or not there is an interruption in, interference with, or reduction or suspension of services provided under this Agreement, such payments not being subject to any reduction, whether by offset or otherwise, and regardless of whether any dispute exists; and (iv) to operate its Electric System, and the business in connection therewith, in accordance with Good Utility Practice.

9.2 Events of Default. An Event of Default under this Agreement shall exist upon the occurrence of any one or more of the following by a Participant (the “Defaulting Participant”):
(i) the failure of any Participant to make any payment in full to NCPA when due, where such failure is not cured within thirty (30) Calendar Days following receipt of a notice from NCPA demanding cure;
(ii) the failure of a Participant to perform any covenant or obligation of this Agreement where such failure is not cured within thirty (30) Calendar Days

Page 272 of 750 ends

TO Rate Case Program Agreement
15 following receipt of a notice from NCPA demanding cure. Provided, that this subsection shall not apply to any failure to make payments specified by subsection 9.2 (i));
(iii) if any representation or warranty of a Participant material to the services provided hereunder shall prove to have been incorrect in any material respect when made and the Participant does not cure the facts underlying such incorrect representation or warranty so that the representation or warranty becomes true and correct within thirty (30) Calendar Days of the date of receipt of notice from NCPA demanding cure; or
(iv) if a Participant is in default or in breach of any of its covenants under any other agreement with NCPA and such default or breach is not cured within the time periods specified in such agreement.

9.3 Uncontrollable Forces. A Party shall not be considered to be in default in respect of any obligation hereunder if prevented from fulfilling such obligation by reason of Uncontrollable Forces. Provided, that in order to be relieved of an Event of Default due to Uncontrollable Forces, a Party affected by an Uncontrollable Force shall:
(i) first provide initial notice to the General Manager using telephone communication within two (2) Business Days of the onset of the Uncontrollable Force, and second provide further written notice to the General Manager and all other Parties within ten (10) Business Days of the onset of the Uncontrollable Force, describing its nature and extent, the obligations which the Party is unable to fulfill, the anticipated duration of the Uncontrollable Force, and the actions which the Party will undertake so as to remove such disability and be able to fulfill its obligations hereunder; and (ii) use due diligence to place itself in a position to fulfill its obligations hereunder and if unable to fulfill any obligation by reason of an Uncontrollable Force such Party shall exercise due diligence to remove such disability with reasonable

Page 273 of 750 ends

TO Rate Case Program Agreement
16 dispatch. Provided, that nothing in this subsection shall require a Party to settle or compromise a labor dispute.

9.4 Cure of an Event of Default. An Event of Default shall be deemed cured only if such default shall be remedied or cured within the time periods specified in Section 9.2 above, as may be applicable, provided, however, upon request of the Defaulting Participant the Commission may waive the default at its sole discretion, where such waiver shall not be unreasonably withheld.

9.5 Remedies in the Event of Uncured Default. Upon the occurrence of an Event of Default which is not cured within the time limits specified in Section 9.2, without limiting other rights or remedies available under this Agreement, at law or in equity, and without constituting or resulting in a waiver, release or estoppel of any right, action or cause of action NCPA may have against the Defaulting Participant, NCPA may, for so long as such Event of Default continues uncured, take any or all of the following actions:
(i) suspend the provision of services under this Agreement to such Defaulting Participant;
(ii) demand that the Defaulting Participant provide further assurances to guarantee the correction of the default, including the collection of a surcharge or increase in electric rates, or such other actions as may be necessary to produce necessary Revenues to correct the default;
(iii) terminate this Agreement as to the Defaulting Participant, on ten (10) Calendar Days prior written notice to the Defaulting Participant; or (iv) enforce all other rights or remedies available to it under any other agreement in which the Defaulting Participant is a signatory.

9.6 Effect of Termination or Suspension.

Page 274 of 750 ends

TO Rate Case Program Agreement
17 9.6.1 Generally. The termination or suspension of this Agreement will not terminate, waive, or otherwise discharge any ongoing or undischarged liabilities, credits or obligations arising from this Agreement until such liabilities, credits or obligations are satisfied in full.

9.6.2 Suspension. If performance of all or any portion of this Agreement is suspended by NCPA with respect to a Participant in accordance with subsection 9.5 (i), such Participant shall pay any and all costs incurred by NCPA as a result of such suspension including reasonable attorney fees, the fees and expenses of other experts, including auditors and accountants, or other reasonable and necessary costs associated with such suspension and any portion of the costs associated with NCPA’s provision of Services, including Administrative Services Costs, that were not recovered from such Participant as a result of such suspension.

9.7 Termination. If this Agreement is terminated by NCPA with respect to a Participant in accordance with Section 9.5 (iii), such Participant shall pay any and all costs incurred by NCPA as a result of such termination, including reasonable attorney fees, the fees and expenses of other experts, including auditors and accountants, other reasonable and necessary costs associated with such termination and any portion of costs associated with NCPA’s provision of Services that were not, or will not be, recovered from such Participant as a result of such termination; provided, however, if NCPA terminates this Agreement with respect to the last remaining Participant, then this Agreement shall terminate.

Section 10. Settlement of Disputes and Arbitration.

10.1 The Parties agree to make best efforts to settle all disputes among themselves connected with this Agreement as a matter of normal business under this Agreement. The procedures set forth in Section 10 of the Power Management and Administrative Services Agreement shall apply to all disputes that cannot be settled by

Page 275 of 750 ends

TO Rate Case Program Agreement
18 the Participants themselves; provided, that the provisions of Section 7.4 shall first apply to all disputes involving invoices prepared by NCPA.

Section 11. Miscellaneous.

11.1 Confidentiality. The Parties will keep confidential all confidential or trade secret information made available to them in connection with this Agreement, to the extent possible, consistent with applicable laws, including the California Public Records Act. Confidential or trade secret information shall be marked or expressly identified as such.

If a Party (“Receiving Party”) receives a request from a Third Party for access to, or inspection, disclosure or copying of, any of the other Party’s (the “Supplying Party”) confidential data or information (“Disclosure Request”), then the Receiving Party shall provide notice and a copy of the Disclosure Request to the Supplying Party within three (3) Business Days of receipt of the Disclosure Request. Within three (3) Business Days of receipt of such notice, the Supplying Party shall provide notice to the Receiving Party either:
(i) that the Supplying Party believes there are reasonable legal grounds for denying or objecting to the Disclosure Request, and the Supplying Party requests the Receiving Party to deny or object to the Disclosure Request with respect to identified confidential information. In such case, the Receiving Party shall deny the Disclosure Request and the Supplying Party shall defend the denial of the Disclosure Request at its sole cost, and it shall indemnify the Receiving Party for all costs associated with denying or objecting to the Disclosure Request. Such indemnification by the Supplying Party of the Receiving Party shall include all of the Receiving Party’s costs reasonably incurred with respect to denial of or objection to the Disclosure Request, including but not limited to costs, penalties, and the Receiving Party’s attorney’s fees; or

Page 276 of 750 ends

TO Rate Case Program Agreement
19 (ii) the Receiving Party may grant the Disclosure Request without any liability by the Receiving Party to the Supplying Party.

11.2 Indemnification and Hold Harmless. Subject to the provisions of Section

11.4, each Participant agrees to indemnify, defend and hold harmless NCPA and its Members, including their respective governing boards, officials, officers, agents, and employees, from and against any and all claims, suits, losses, costs, damages, expenses and liability of any kind or nature, including reasonable attorneys’ fees and the costs of litigation, including experts, to the extent caused by any acts, omissions, breach of contract, negligence (active or passive), gross negligence, recklessness, or willful misconduct of that Participant, its governing officials, officers, employees, subcontractors or agents, to the maximum extent permitted by law.

11.3 Several Liabilities. Except as otherwise provided herein, no Participant shall be liable under this Agreement for the obligations of any other Participant, each Participant shall be solely responsible and liable for performance of its obligations under this Agreement and the obligation of each Participant under this Agreement is a several obligation and not a joint obligation with those of the other Participants.

11.4 No Consequential Damages. FOR ANY BREACH OF ANY PROVISION

OF THIS AGREEMENT FOR WHICH AN EXPRESS REMEDY OR MEASURE OF

DAMAGES IS PROVIDED IN THIS AGREEMENT, THE LIABILITY OF THE

DEFAULTING PARTY SHALL BE LIMITED AS SET FORTH IN SUCH PROVISION, AND ALL OTHER DAMAGES OR REMEDIES ARE HEREBY WAIVED. IF NO

REMEDY OR MEASURE OF DAMAGE IS EXPRESSLY PROVIDED, THE LIABILITY

OF THE DEFAULTING PARTY SHALL BE LIMITED TO ACTUAL DAMAGES ONLY AND ALL OTHER DAMAGES AND REMEDIES ARE HEREBY WAIVED. IN NO

EVENT SHALL NCPA OR ANY PARTICIPANT OR THEIR RESPECTIVE

SUCCESSORS, ASSIGNS, REPRESENTATIVES, DIRECTORS, OFFICERS, AGENTS,

Page 277 of 750 ends

TO Rate Case Program Agreement
20 OR EMPLOYEES BE LIABLE FOR ANY LOST PROFITS, CONSEQUENTIAL,

SPECIAL, EXEMPLARY, INDIRECT, PUNITIVE OR INCIDENTAL LOSSES OR

DAMAGES, INCLUDING LOSS OF USE, LOSS OF GOODWILL, LOST REVENUES,

LOSS OF PROFIT OR LOSS OF CONTRACTS EVEN IF SUCH PARTY HAS BEEN

ADVISED OF THE POSSIBILITY OF SUCH DAMAGES, AND NCPA AND EACH

PARTICIPANT EACH HEREBY WAIVES SUCH CLAIMS AND RELEASES EACH OTHER AND EACH OF SUCH PERSONS FROM ANY SUCH LIABILITY.

11.5 The Parties acknowledge that California Civil Code section 1542 provides that: “A general release does not extend to claims which the creditor does not know or suspect to exist in his or her favor at the time of executing the release, which if known by him or her must have materially affected his or her settlement with the debtor.” The Parties waive the provisions of section 1542, or other similar provisions of law, and intend that the waiver and release provided by this Section of this Agreement shall be fully enforceable despite its reference to future or unknown claims.

11.6 Waiver. No waiver of the performance by a Party of any obligation under this Agreement with respect to any default or any other matter arising in connection with this Agreement shall be effective unless given by the Commission. Any such waiver by the Commission in any particular instance shall not be deemed a waiver with respect to any subsequent performance, default or matter.

11.7 Amendments. Amendments to the Program Participation Percentages as set forth in Exhibit A of this Agreement shall take effect after being approved by the Commission in a manner consistent with the voting procedures set forth in Section 3 of this Agreement, without the requirement of an approval of the individual Participants’ governing bodies. Except where this Agreement specifically provides otherwise, this Agreement may be amended only by written instrument executed by the Parties with the same formality as this Agreement.

Page 278 of 750 ends

TO Rate Case Program Agreement
21 11.8 Assignment of Agreement.

11.8.1 Binding Upon Successors. This Agreement shall inure to the benefit of and shall be binding upon the respective successors and assignees of the Parties to this Agreement.

11.8.2 No Assignment. This Agreement, nor any interest herein, shall be transferred or assigned by a Party hereto except with the consent in writing of the other Parties hereto, where such consent shall not be unreasonably withheld.

Without limiting the foregoing, this Agreement shall not be assigned by PlumasSierra Rural Electric Cooperative without the approval in writing of the Administrator of the Rural Electrification Administration Utilities Service.

11.9 Severability. In the event that any of the terms, covenants or conditions of this Agreement or the application of any such term, covenant or condition, shall be held invalid as to any person or circumstance by any court having jurisdiction, all other terms, covenants or conditions of this Agreement and their application shall not be affected thereby, but shall remain in force and effect unless the court holds that such provisions are not severable from all other provisions of this Agreement.

11.10 Governing Law. This Agreement shall be interpreted, governed by, and construed under the laws of the State of California.

11.11 Headings. All indices, titles, subject headings, section titles and similar items are provided for the purpose of convenience and are not intended to be inclusive, definitive, or affect the meaning of the contents of this Agreement or the scope thereof.

11.12 Notices. Any notice, demand or request required or authorized by this Agreement to be given to any Party shall be in writing, and shall either be personally delivered to a Participant’s Commissioner or Alternate, and to the General Manager, or shall be transmitted to the Participant and the General Manager at the addresses shown on the signature pages hereof. The designation of such addresses may be changed at

Page 279 of 750 ends

TO Rate Case Program Agreement
22 any time by written notice given to the General Manager who shall thereupon give written notice of such change to each Participant. All such notices shall be deemed delivered when personally delivered, two (2) Business Days after deposit in the United States mail first class postage prepaid, or on the first Business Day following delivery through electronic communication.

11.13 Warranty of Authority. Each Party represents and warrants that it has been duly authorized by all requisite approval and action to execute and deliver this Agreement and that this Agreement is a binding, legal, and valid agreement enforceable in accordance with its terms.

11.14 Counterparts. This Agreement may be executed in any number of counterparts, and each executed counterpart shall have the same force and effect as an original instrument and as if all the signatories to all of the counterparts had signed the same instrument. Any signature page of this Agreement may be detached from any counterpart of this Agreement without impairing the legal effect of any signatures thereon, and may be attached to another counterpart of this Agreement identical in form hereto but having attached to it one or more signature pages.

11.15 Venue. In the event that a Party brings any action under this Agreement, the Parties agree that trial of such action shall be vested exclusively in the state courts of California in the County of Placer or in the United States District Court for the Eastern District of California.

11.16 Attorneys’ Fees. If a Party to this Agreement brings any action, including an action for declaratory relief, to enforce or interpret the provisions of this Agreement, each Party shall bear its own fees and costs, including attorneys’ fees, associated with the action.

11.17 Counsel Representation. Pursuant to the provisions of California Civil Code Section 1717 (a), each of the Parties were represented by counsel in the negotiation

Page 280 of 750 ends

TO Rate Case Program Agreement
23 and execution of this Agreement and no one Party is the author of this Agreement or any of its subparts. Those terms of this Agreement which dictate the responsibility for bearing any attorney’s fees incurred in arbitration, litigation or settlement in a manner inconsistent with the provisions of Section 11.2 were intentionally so drafted by the Parties, and any ambiguities in this Agreement shall not be interpreted for or against a Party by reason of that Party being the author of the provision.

11.18 No Third Party Beneficiaries. Nothing contained in this Agreement is intended by the Parties, nor shall any provision of this Agreement be deemed or construed by the Parties, by any third person or any Third Parties, to be for the benefit of any Third Party, nor shall any Third Party have any right to enforce any provision of this Agreement or be entitled to damages for any breach by the Parties of any of the provisions of this Agreement.

Page 281 of 750 ends