CITY OF VALLEJO 138 CITYWIDE SLURRY SEAL – PW9745
SECTION 10: GENERAL CONSTRUCTION
(SECTION 10)
10-01 ORDER OF WORK
Attention is directed to the following sections of these special provisions: 10 -1.09 “Traffic Control System”, and 10-1.10 “Temporary Pavement Delineation,” of these special provisions.
Access to businesses shall be maintained at all times.
The Contractor shall submit traffic/pedestrian control plans and a construction street schedule to the Engineer within five (5) calendar days after receipt of Notice of Award from the City. Refer to Technical Requirements of this project manual for more details.
The Contractor shall have a representative on all working job sites at all times while work is actually in progress, whose sole duties shall be to supervise the work crews and coordinate activities pertaining to the contract operations, including traffic control and public notifications.
If needed, the Contractor shall secure a staging area along the project site and shall obtain a written approval from the property owner. A staging plan along with the approval letter from the property owner shall be submitted for review by the Engineer as soon as the use of the staging area is secured. Work shall not begin until the Engineer has reviewed the staging plan and approval letter.
Notifications
The Contractor shall provide written notification seven (7) calendar days in advance notifying all directly affected parties prior to beginning work. An example list of agencies, public services are mentioned below (the list is not all-inclusive):
Pacific Gas & Electric Comcast/ATT
Comcast Recology
811 USA North Local Police Authorities
SolTrans All affected businesses / residents
Contractor shall submit a draft letter to City for review at the preconstruction meeting before distribution to affected property owners. The letter shall include a description of the work being performed, the Contractor’s schedule, contact names and phon e numbers. Upon completing the notification, the Contractor shall confirm delivery of notice in writing to the City.
In addition to the Contractor’s notification letters, the City will mail advance notices to all property owners, businesses, tenants, residents, and applicable parties within the work area advising them of the pending construction.
The Contractor shall cooperate with local authorities relative to handling traffic through the area, and shall make their own arrangements for keeping the working area clear of parked vehicles.
Work Progress Criteria
Patch paving will be the construction operation to be conducted first. The contractor shall coordinate and measure with the assigned City Inspector of all dig-out locations before grinding and eventually re-paving.
Crack seal operation shall be initiated with an approved weed removal spray 1 week before crack seal installation. Contractor is to proceed with the standard crack seal installation by the use of mechanized air
CITY OF VALLEJO 139 CITYWIDE SLURRY SEAL – PW9745
spray of the dried weed removal completely before crack seal is placed. Cracks with a width between 3/8- 1inches shall be crack sealed and use a flat plate, squeegee, or overbanding for finishing.
After obliterating all Thermo-plastic striping and pavement markers, temporary markings and striping are to be re-installed on the same alignment and location. The Contractor shall install reference with a sufficient number of control points to re -establish the alignment and location of the new markers, markings, and striping.
Striping and markings to be removed shall occur no more than 3 working days prior to surface treatment operation.
Striping installation shall be complete after 5 calendar days following surface treatment operation.
Measurement and Payment
Full compensation for all items mentioned in Section 10 -01 shall be considered as included in the prices paid for the various items of work involved and no additional compensation will be allowed.
10-02 MOBILIZATION
Measurement and Payment
The contract lump sum (LS) price paid for the “Mobilization” shall include full compensation for mobilization as defined in Section 1 - General and no additional compensation will be allowed, therefore.
Full compensation for furnishing all labor, materials, tools, equipment and incidentals and for doing the work involved in the procurement, setup and maintenance of the staging area shall be considered as included as part of "Mobilization".
10-03 DUST CONTROL
Dust control shall conform to the provisions in Section 14 -9.03, "Dust Control," of the Standard Specifications.
Measurement and Payment
Full compensation for Dust Control shall be considered as included in the prices for the various items of work and no additional compensation will be allowed therefor. 10-04 WATER POLLUTION CONTROL
Water pollution control work shall conform to the requirements in Section 13, “Water Pollution Control,” of the Standard Specifications, and these special provisions.
All operations shall be in compliance with the provisions of the Clean Water Act, Regional Water Quality Control Board, and policies with regard to protection of the storm water system from any pollutants. The Contractor is required any necessary water pollution control permits.
Measurement and Payment
Full compensation for “Water Pollution Control ” shall be considered as included in the prices for the various items of work and no additional compensation will be allowed therefor.
CITY OF VALLEJO 140 CITYWIDE SLURRY SEAL – PW9745
10-05 DAMAGE REPAIR
Attention is directed to Section 5-1.39, "Damage Repair and Restoration," of the Standard Specifications.
Any damage to existing facilities or properties during the period of the work shall be returned to the original condition or better at Contractor's expense.
Measurement and Payment
Full compensation for Damage Repair shall be considered as included in the prices for the various items of work and no additional compensation will be allowed therefor.
10-06 DIGOUT REPAIRS
Digout Repair (4” Deep) will be made in and adjacent to the resurfacing areas shall conform to these Special Provisions. Digout Repair shall conform to the details shown on the Plans and consist of removal of 4" of existing concrete, asphalt concrete pavement and/or base rock in the areas as shown on the Plans and as directed by the Engineer, scarification and recompaction of base material and placing 4" of new asphalt concrete as outlined in these Special Provisions and as shown on the Plans.
Areas designated as Digout Repair (6" Deep) consists of removal of existing concrete, asphalt concrete pavement and/or base rock in the areas as shown on the Plans and as directed by the Engineer, scarification and recompaction of base material and placing 6" of new asphalt concrete as outlined in these Special Provisions and as shown on the Plans.
Digout Repair (4” Deep) and Digout Repair (6” Deep) may be repaved in lifts not exceeding 3 inches.
Digout Repair (4” Deep) and Digout Repairs (6” Deep) shall be limited to the areas marked in the field.
Care shall be taken by the Contractor not to damage concrete collars for utility frames/covers, gutters, valley gutters, or other adjacent facilities. No additional compensation will be made for excavation, grinding or other work beyond the limits of the areas marked by the Engineer for Digout Repair locations. Any additional excavation or repaving beyond the areas designated that is associated with grinding, incidental removal, sluffing or excavation, including spalling of fractured pavements done by the Contractor beyond the limits of the areas marked by the City Engineer shall be at Contractor’s cost.
Removal
The Contractor shall remove all material including asphalt concrete, concrete, base rock, or other materials to a minimum depth of 4” or 6” as measured from finish grade in the areas marked or directed by the Engineer. In areas where the existing grade is below the finish grade of the completed repair, the depth of the depression may be deducted from the depth of the removal. Areas designate d as Digout Repair (6” Deep) shall include the pruning and removal of tree roots if encountered.
The Contractor shall perform this work by either cold planing or excavation. If the Contractor elects to use excavation, all edges shall be neatly saw cut prior to the excavation operations. If the Contractor elects to use cold planing, the Contractor sh all be solely responsible for any removals and repairs in excess of the mark outs provided by the Engineer whether due to non-cohesive or alligatored asphalt, equipment size, or any other reason whatsoever.
CITY OF VALLEJO 141 CITYWIDE SLURRY SEAL – PW9745
Disposal
The Contractor shall be responsible for recycling or disposal of all removed bituminous pavement, concrete and base material in accordance with section 12 -1.05 “Remove Asphalt Concrete” of these Special Provisions.
Asphalt Concrete
Asphalt concrete base and asphalt concrete surface and the placing thereof shall conform to the requirements of Section 39, “Hot Mix Asphalt,” of the 2010 Standard Specifications, which sections are hereby incorporated in these Special Provisions as if set forth in full, with the following modifications:
Aggregate shall be Type B, 3/4" maximum, course grading with bituminous binder of steam -refined paving asphalt of PG 64-16 viscosity conforming to the latest published provisions in Section 92, “Asphalt Binders,” of the Standard Specifications. Asphalt pl aced for Digout Repairs may be placed up a depth of 2 1/2" in a single lift.
The Contractor shall furnish the City Engineer, at least ten (10) working days prior to the start of work, a list of sources of materials together with a Certified of Compliance indicating that materials to be incorporated in the work fulfill the requireme nts of these specifications and a mix design for the asphalt concrete. The mix design shall be performed in accordance with CTM 366. The Certified of Compliance shall be signed by the material supplier or his representative. The Contractor shall be resp onsible for all costs associated with the required mix design.
Prior to placement of new asphalt concrete, the Contractor shall clean the existing asphalt concrete surface in accordance with Section 16 “Pavement Preparation” of these Special Provisions.
A tack coat, type SS-1, shall be applied to all mating surfaces along edges to receive asphalt concrete prior to placement of new asphalt concrete and shall conform to Section 94, “Asphaltic Emulsions” of the Standard Specifications. Tack coat shall not b e required between lifts of new HMA in Digout Repairs or Deep Digout Repairs where more than one lift is required.
Placement of asphalt concrete shall be in accordance with Section 39 -3, “Method Construction Process,” of the 2010 Standard Specifications. Asphalt concrete shall be compacted to 91 -97% of maximum theoretical compaction (California Test 309) as determined by California Test 375 (Nuclear Density Device may be used).
The completed asphalt surfacing shall be true to grade and cross section, of uniform smoothness and texture, compacted firmly and free from depressions, humps or irregularities.
All areas excavated for Digout shall be completely repaved on the same working day. Areas where paving has been removed shall not be left unpaved. Attention is directed to Section entitled “Maintaining Traffic” of these Special Provisions. A drop-off of more than 0.10 foot will not be allowed at any time in areas open to public traffic.
Temporary asphalt concrete tapers, if permitted, shall made with ½” hot mix AC or taper grinding of the existing pavement edge to provide a slope of 30:1, or flatter, between adjacent lanes open to traffic.
Mark-outs and Quantity Verification
All areas to receive Digout Repair shall be marked and measured by the Engineer in the field. The Contractor shall review these mark outs and measurements in the field with the Engineer prior to commencing any Digout Repair work. The Contractor shall bri ng any exceptions taken to the Engineer’s mark outs and/or measurements to the Engineer’s attention prior to proceeding with any work. Any such exceptions shall be made in writing. The Engineer will review any exceptions noted by the Contractor and issue a written response. The amount of Digout Repair used for Measurement and Payment shall be based
CITY OF VALLEJO 142 CITYWIDE SLURRY SEAL – PW9745
on the measurements as adjusted by the Engineer. Measurements of post -Digout Repairs shall not be used for measurement and payment and the Contractor shall be solely responsible for the cost of any Digout Repairs made in excess of these measurements.
Measurement and Payment
“Digout Repair (4” Deep) ” and “Digout Repair (6” Deep) ” shall be measured by the square foot of material removed and repaired. Only those areas marked and measured by the Engineer prior to the work will be eligible for measurement. Any digout repairs made beyond these measurements shall not be measured for payment. The estimated quantity of Di gout Repair and Deep Digout Repairs is for bidding purposes only. This quantity may be increased, decreased, or eliminated in its entirety based on field condition evaluation by the City Engineer, and no adjustment in the contract bid price or other contract items will be made.
In the event of an increase or a decrease in the amount of the City Engineer’s estimated quantity of Digout Repair or Deep Digout Repair, such increase or decrease shall not be considered an alteration in excess of the 25 percent of the contract amount of such items and no adjustment of the contract price for Digout Repair will be made by reason of such increase or decrease.
“Digout Repair (4” Deep)” and “Digout Repair (6” Deep) will be paid for at the contract price per square foot. No payment shall be made for Digout Repair or Deep Digout Repair made by the Contractor in excess of the measurements made by the Engineer. Payment shall include full compensation for doing all work involved in as specified herein including labor, mate rials, tools and equipment, saw cutting, excavation, grinding, disposal, scarification and recompaction of base material, tack coat, asphalt concrete and compaction, traffic control, as shown on the Plans, as specified in these Special Provisions, and as directed by the Engineer and no additional compensation will be allowed.
10-07 PROGRESS SCHEDULE
Progress schedules will be required for this contract and shall conform to the provisions in Section 8, "Prosecution and Progress" of the Standard Specifications.
A project schedule detailing the work and street location of the work shall be submitted to the Engineer for review at the pre -construction meeting. Any changes to the reviewed schedule shall require a revised schedule to be resubmitted to the Engineer for review prior to commencing work for the following week.
The maximum slurry seal scheduled in a single day shall not exceed 200,000 SF and be completed a minimum of 3 hours before the end of the working day to allow for cure time.
The Contractor shall deliver an approved schedule to the following a minimum of 72 hours prior to starting work:
1. U.S. Post Office
2. Recology
3. SolTrans
Work shall be scheduled in such a way that will not impact garbage collection. 10-08 OBSTRUCTIONS
Attention is directed to Sections 5-1.36D, "Non-highway Facilities," and Section 15, "Existing Facilities," of the Standard Specifications.
CITY OF VALLEJO 143 CITYWIDE SLURRY SEAL – PW9745
10-09 SPECIFIC BRAND OR TRADE NAME AND SUBSTITUTION
Attention is directed to Section 6 -04 REQUEST FOR SUBSTITUTION OF MATERIALS of the Special Provisions.
10-10 UTILITY ADJUSTMENTS
The manhole utility covers and survey monuments in the Bid Proposal listed as “Adjust Manhole Cover to Finished Grade” and “Adjust Water Valve Cover and Survey Monument to Finished Grade” are those which may be affected by digout repairs. All utility covers, survey monuments and manholes that are within the slurry seal project limits, but not affected by digout repairs shall be protected in place and uncovered after the slurry.
The Contractor shall be responsible for replacing and/or adjusting all frames and covers of existing storm drain and sanitary sewer manholes, valve and monument boxes, and other utilities (collectively, “iron”) affected by digout repairs to finished grade.
This work shall consist of adjusting iron below the grading plane in excavation (roadway inlay) areas, and then to finished grade following placement of the top layer of asphalt concrete pavement. The Contractor shall adjust the iron to below the planed surface prior to cold planning/excavation operation.
Work by the Contractor shall include locating, referencing, and setting sufficient marks prior to adjusting facilities below the planed surface or grading plane to enable their subsequent retrieval by the Contractor.
The Contractor shall reference and set marks for all facilities.
Adjustments below the planed surface shall include placement of a temporary false bottom in sanitary sewer manholes, removal of rings as required, placing and securing an acceptable temporary lid or cover below the planed surface or grading plane elevation s, and placement of temporary asphalt concrete over and around the temporary lid or cover as required to allow for the passage of vehicular traffic prior to and following cold planning (milling) or excavation operations.
The final adjustment to finished grade of all manhole frames shall consist of resetting the manhole frame to grade by adjusting and/or reconstructing the existing concrete riser rings within the throat area. The existing concrete collar shall be reconstructed to conform to the detail shown on the plans, and the existing concrete riser rings shall be replaced, if damaged. The reconstructed sections shall be at least equal in quality to the existing structure. In no case shall the precast barrel section be disturbed. Cast iron extension or adjustment rings will not be allowed in the adjusted structure.
Measurement and Payment
The unit price per each paid for the “Adjust Manhole Cover to Finish Grade” and “Adjust Water Valve Cover and Survey Monument to Finish Grade” shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all work involved in raising lowering existing utility frames to grade, including coordination with the utility companies, inventorying, r emoving, and storing covers, removing concrete collars, placing temporary traffic rated covers, placing temporary or permanent HMA (Type A) pavement, tack coat, placing concrete collars, shimming or grade rings as required, adjusting to finish grade, complete in place; as directed by the Engineer.
END OF SECTION
CITY OF VALLEJO 144 CITYWIDE SLURRY SEAL – PW9745
SECTION 11: TEMPORARY TRAFFIC CONTROL
(SECTION 12)
11-01 TRAFFIC AND PEDESTRIAN CONTROL
Construction Area Signs
Construction area signs are required for the direction of public vehicle and pedestrian traffic through or around the work during construction.
Construction area signs shall be furnished, installed, maintained and removed when no longer required in accordance with the provisions in Section 12, “Temporary Traffic Control,” of the Standard Specifications, which sections are hereby incorporated in these Special Provisions as if set forth in full, and these Special Provisions. Sections 7 -1.03, “Public Convenience,” and 7 -1.04, “Public Safety,” of the Standard Specifications set forth the Contractor’s responsibilities for public convenience and public safety.
Construction area signs shall not be used until they are needed, and when no longer needed, they shall be removed from the site of the work.
Maintaining Traffic
Attention is directed to Section 7-1.03, “Public Convenience,” Section 7 -1.04, “Public Safety,” and Section 12 “Temporary Traffic Control,” of the Standard Specifications. Nothing in these Special Provisions shall be construed as relieving the Contractor from his responsibilities as provided in said Section 7-1.04.
Construction area traffic control devices shall be installed and maintained in accordance with the applicable sections of these Special Provisions and to the current edition of the California Manual of Uniform Traffic Control Devices (CAMUTCD), Chapter 6, “Temporary Traffic Control”.
At the Pre -construction meeting the Contractor shall submit proof of “Qualification of Flaggers”, and “Documentation of Training” as per the most current CAMUTCD ( 2014, Rev. March 29, 2019 ) Section 6E.01. Further, Contractor shall comply with the following references by the CAMUTCD: “To ensure that the traffic control device practitioner is accessing the most current information regarding traffic control device topics for California, the practitioner is advised to always reference the California MUTCD web site.” The California MUTCD, California Sign Specifications and other publications and related current information is available on the Internet at the following web link: https://dot.ca.gov/programs/safety-programs/camutcd
Whenever vehicles or equipment are parked on the shoulder within 6 feet of a traffic lane, the shoulder area shall be closed with fluorescent traffic cones or portable delineators placed on a taper in advance of the parked vehicles or equipment and along the edge of the pavement at 25 -foot intervals to a point not less than 25 feet past the last vehicle or piece of equipment. A minimum of 9 cones or portable delineators shall be used for the taper. A C23 (Road Work Ahead) or C24 (Shoulder Work Ahead) sign shall be mounted on a telescoping flag tree with flags. The flag tree shall be placed where directed by the Engineer.
When leaving a work area and entering a roadway carrying public traffic, the Contractor's equipment, whether empty or loaded, shall in all cases yield to public traffic.
Whenever the Contractor's operations obliterate pavement delineation (lane lines, either pavement markers or painted lines or both, or temporary delineation), such pavement delineation shall be replaced by either permanent or temporary delineation before opening the traveled way to public traffic. Temporary delineation shall consist of reflective traffic line tape applied in pieces not less than 4 feet long nor less than 4 inches wide spaced no more than 10 feet apart on curves nor more than 20 feet apart o n tangents. Reflective traffic line tape shall be applied in accordance with the manufacturer's instructions.
CITY OF VALLEJO 145 CITYWIDE SLURRY SEAL – PW9745
If any component in the traffic control system is damaged, displaced or ceases to operate or function as specified, from any cause, during the progress of the work, the Contractor shall immediately repair said component to its original condition or replace said component and shall restore the component to its original location.
When lane closures are made for work periods only, at the end of each work period, all components of the traffic control system, except portable delineators placed along open trenches or excavation adjacent to the traveled way shall be removed from the tra veled way and shoulder. If the Contractor so elects, said components may be stored at selected central locations, approved by the Engineer, within the limits of the highway right-of-way.
Flagging Costs
Section 12-1.04, “Payment,” of the Standard Specifications is amended to read:
The cost of furnishing all flaggers, including transporting flaggers, to provide for passage of public traffic through the work under the provisions in Section 7-1.03, “Public Convenience,” and Section 7-1.04, “Public Safety,” of the Standard Specifications shall be considered as included in the contract lump sum price paid for Traffic Control System and no additional allowance will be made therefor.
Traffic Control Plan
It is the responsibility of the Contractor to provide an updated schedule and Traffic Control Plan ten (10) working days prior to beginning construction. Work shall not begin until the schedule and plan is approved by the Engineer.
The content of the Traffic Control Plan shall include, but not be limited to, the following:
a. Show location and limits of the work zone.
b. Give dimensions of lanes affected by traffic control that will be open to traffic. c. Indicate signing, cone placement, and other methods of delineation and reference to appropriate City or Caltrans standard.
d. Dimension location of signs and cone tapers.
e. Identify side streets and driveways affected by construction and show how they will be handled.
f. Show how pedestrian traffic will be handled through the construction site. g. Demonstrate how two-way traffic will be maintained.
No work except for the installation of project identification signage will be allowed to commence prior to approval of the work zone Traffic Control Plan.
Removal of On-Street Parking
Forty-eight (48) hours prior to construction, the Contractor shall place barricades signed “NO PARKING – TOW AWAY – Specific Time and Date(s)” at 100 -foot intervals or a minimum of two (2) signs per block, whichever is greater, in the work area. “NO PARKING” signs must also state “C.V.C. 22651 (L)”. See example below.
CITY OF VALLEJO 146 CITYWIDE SLURRY SEAL – PW9745
“NO PARKING – TOW AWAY” signs shall be submitted for approval by the Engineer prior to their use. The Contractor shall notify the Engineer immediately after the “NO PARKING” signs are in place. “NO PARKING” signs and barricades shall be supplied by the Contractor.
Failure to comply with this section will prevent the City from towing vehicles parked in the proposed work area. Any resulting delay will be the responsibility and at the expense of the Contractor.
Measurement and Payment
The contract lump sum price paid for “Traffic and Pedestrian Control” shall include full compensation for furnishing all labor (including flagging costs), materials (including signs), Traffic Control Plan, tools, equipment, and incidentals and for doing all the work involved in placing, removing, storing, maintaining, and moving to new locations, replacing, and disposing of the components of the traffic control system as specified in the Standard Specifications and these Special Provisions, and as directed by the Engineer.
The adjustment provisions in Section 4 -1.05, "Changes and Extra Work," of the Standard Specifications, shall not apply to the item of traffic control system. Adjustments in compensation for traffic control system will be made only for increased or decreas ed traffic control system required by changes ordered by the Engineer and will be made on the basis of the cost of the increased or decreased traffic control necessary.
Such adjustment will be made in accordance with Sections 5-1.04 and 5-1.05 of these Special Provisions.
11-02 TEMPORARY PAVEMENT DELINEATION
Temporary pavement delineation shall be furnished, placed, maintained and removed in conformance with the provisions in Section 12 -1.01, “General,” of the Standard Specifications and these special provisions.
Nothing in these special provisions shall be construed as reducing the minimum standards specified in the California MUTCD or as relieving the Contractor from his responsibility as provided in Section 7 -1.04, “Public Safety,” of the Standard Specifications.
General
Whenever the work causes obliteration of pavement delineation, temporary or permanent pavement delineation shall be in place prior to opening the traveled way to public traffic. Lane line or centerline pavement delineation shall be provided at all times for traveled ways open to public traffic.
TOW AWAY
NO PARKING
THERE SHALL BE NO
PARKING ON THIS STREET
BETWEEN THE HOURS OF:
_________ AND _________
ON ________________
VEHICLES FOUND IN
VIOLATION WILL BE
TOWED.
C.V.C. 2265(L)
CITY OF VALLEJO 147 CITYWIDE SLURRY SEAL – PW9745
Work necessary, including required lines or marks, to establish the alignment of temporary pavement delineation shall be performed by the Contractor. Surfaces to receive temporary pavement delineation shall be dry and free of dirt and loose material. Temporary pavement delineation shall not be applied over existing pavement delineation or other temporary pavement delineation. Temporary pavement delineation shall be maintained until superseded or replaced with a new pattern of temporary pavement delineation or permanent pavement delineation.
Temporary pavement markers and removable traffic type tape which conflicts with a new traffic pattern or which is applied to the final layer of surfacing or existing pavement to remain in place shall be removed when no longer required for the direction of public traffic, as determined by the Engineer.
Temporary Laneline, Centerline, and Edgeline Delineation
Whenever lane lines and centerlines are obliterated the minimum lane line and centerline delineation to be provided shall be temporary reflective raised pavement markers placed at longitudinal intervals of not more than 20 feet. The temporary reflective raised pavement markers shall be the same color as the lane line or centerline the markers replace. Temporary reflective raised pavement markers shall be, at the option of the Contractor, one of the temporary pavement markers listed for short term day/night use (14 days or less) or long-term day/night use (6 months or less) in “Approved Traffic Products” of the Standard Plans and Standard Specifications.
Temporary reflective raised pavement markers shall be placed in conformance with the manufacturer’s instructions and shall be cemented to the surfacing with the adhesive recommended by the manufacturer, except epoxy adhesive shall not be used to place pavement markers in areas where removal of the markers will be required.
Removal of Temporary Pavement Markers Prior to Surface Treatment
Temporary lane line or centerline delineation consisting of entirely of temporary reflective raised pavement markers placed on longitudinal intervals of not more than 20 feet shall be used on lanes opened to public traffic for a maximum of 14 days. Prior to the end of the 14 days the permanent pavement delineation shall be placed. If the permanent pavement delineation is not placed within the 14 days, the Contractor shall provide, at the Contractor’s expense, additional temporary pavement delineation. The additional temporary pavement delineation to be provided shall be equivalent to the pattern specified for the permanent pavement delineation for the area, as determined by the Engineer.
Measurement and Payment
Full compensation for Temporary Laneline, Centerline, and Edgeline Delineation; Removal of Temporary Pavement Markers Prior to Surface Treatment; and Portable Changeable Message Signs shall be considered as included in the various items of work and no separate payment will be made therefor.
END OF SECTION
CITY OF VALLEJO 148 CITYWIDE SLURRY SEAL – PW9745
SECTION 12: CLEARING, GRUBBING AND REMOVALS
(SECTION 17)
Clearing, grubbing, and removal shall conform to provisions in Section 17 -2.03B, “Clearing” and Section 17-2.03C “Grubbing,” of the Standard Specifications and these Special Provisions.
12-01 CLEARING, GRUBBING AND REMOVALS
Measurement and Payment
The contract lump sum (LS) price paid for “Clearing, Grubbing and Removals ” shall include full compensation for clearing grubbing and removals as described in these Technical Specifications and no additional compensation will be allowed therefor. Full compensation for doing all work involved as specified herein including furnishing all labor, materials, tools, equipment for removal, providing storage and disposal of removed material, and for providing personnel protective equipment, training, air monitoring, and medical surveillance and incidentals as specified in these Special Provisions, and as directed by the Engineer.
12-02 CRACK SEALING
Crack sealing shall consist of preparing and sealing pavement cracks on roadway sections to receive micro- surfacing seal with a hot applied rubberized crack sealant to prolong the life of existing pavements by preventing moisture from penetrating the roadway structure, and by preventing the spalling of material from the edges of the cracks. A roadway will include all travel lanes, shoulders, and intersections. Crack sealing shall be required to clean, prepare, and seal all cracks between 1/8 inch and one inch in width in asphalt concrete pavement as noted on the Plans. Crack sealing shall not be performed within areas designated for dig-outs.
Materials
Attention is directed to the provisions in Section 37, “Bituminous Seals,” Section 92, “Asphalt Binders,” and Section 94, “Asphaltic Emulsions,” of the Standard Specifications. Crack sealant shall be a commercial rubberized material of paving asphalt and ground rubber or ground rubber and polymer. Rubber content shall be a minimum of 20% by weight. The gradation of the ground rubber shall be such that 100 percent will pass a No. 8 sieve.
Modified asphalt crack sealant shall conform to the following requirements:
Test ASTM Designation Requirements
Softening Point D 36 82°C min.
Cone Penetration @ 25°C D 5329 30 dmm, min.
Resilience @ 25°C D 5329 40 percent min.
Flow D 5329 3 mm max.
Modified asphalt sealant material shall be furnished premixed in containers with an inside liner of polyethylene. Packaged material shall not exceed 66 pounds in weight and shall be capable of being melted and applied to cracks at temperatures below 400°F and shall readily penetr ate cracks ¼ inch wide or wider.
Materials supplied shall be subject to a Laboratory Evaluation prior to use. When a sample of the product has been heated at 350° F. for two hours, it shall pass the following tests: 1) Softening Point (R&B) 135° F.
CITY OF VALLEJO 149 CITYWIDE SLURRY SEAL – PW9745
min. (ASTM D-312), and 2) Flexibility: A 1/8” thick specimen of the product conditioned to 10° F shall be capable of being bent to a 90-degree angle over a 1” mandrel without cracking.
Preparation
Prior to crack cleaning, the Contractor shall inspect the roadway. All cracks within the entire width of the pavement surface, which are greater than 1/8 inch in width showing signs of raveling or spalling shall be cleaned. All cracks ¼ inch to 1 inch shall be cleaned. In cracks where sealant has been previously, old sealant that is not firmly adhered to at least one side of the crack shall be removed us ing a router or other approved method. All cracks previously sealed where the sealant has separated f rom one wall by 1/8” or more shall be cleaned and re-sealed. Do not clean cracks greater than 1 inch, and do not use rubberized crack sealant to seal spalls or cavities greater than 4 inches, unless otherwise directed.
Seven days prior to crack cleaning, the Contractor shall apply a broad-spectrum contact herbicide (industrial Round Up or equal). The herbicide shall include an integral dye to identify areas of application. One-week of contact time of the approved weed removal spray shall be allowed between herbicide application and further work on crack sealing. Once this time has elapsed and all weeds are visibly dead, Contractor is to proceed with the crack cleaning by the use of pressurized air spray or approved mec hanical methods as required to completely remove dried weed, moisture, old sealants, and all other loose material. Heating and/or burning are not acceptable methods of weed removal. Cracks shall be cleaned to a minimum of two times the width of the crack or one inch whichever is greater. Old sealant which protrudes above the asphalt concrete surfacing shall be completely removed. Keep these areas clean and dry until all sealing operations are completed. Use a propane lance unit capable of producing a blast of hot air that operates at 97 psi, 2.5 cubic feet per second, 900°F and a gas velocity of 2,000 feet per second. Take care to not burn or overheat pavement with hot-air lance. The temperature of the hot -air lance shall be kept below 930°F and the t ip 2 to 4 inches from the crack.
Sealing
Crack sealant shall be applied only after the cracks and adjacent asphalt concrete surfacing have been thoroughly cleaned and dried. Crack sealant material shall be spread with a nozzle or device approved for use by the Engineer and is placed within the s pecified temperature range. The sealing operation shall follow directly behind the cleaning operation. In no instance shall the crack sealing operation be separated from the cleaning operation by more than 250 feet.
All cracks within the entire width of the pavement surface, which are greater than 1/8 inch shall be sealed as follows:
1. All cracks within the entire width of the pavement surface, which are greater than 1/8 inch and less than ¼ inch, shall be sealed. These cracks shall be cleaned only if they show signs of raveling or spalling.
2. All cracks greater than ¼ inch and less than 1 inch shall be cleaned and sealed.
3. Do not seal cracks greater than 1 inch (25 mm) wide, and do not seal spalls or cavities greater than 4 inches (100 mm), unless otherwise directed.
4. When directed, cracks that are one inch wide or wider shall be filled with sealant flush with the existing asphalt concrete surfacing. While the sealant is still hot, these cracks shall be covered with crushed aggregate conforming to the provisions for Type II slurry seal in Section 37-3.01B(2), “Aggregate,” of the Standard Specifications and compacted with a wetted steel wheel roller or vibrating plate compactor large enough to compact the sealant to the cross section shown on the Plans. Light brooming shall be performed to remove loose excessive sand prior to opening a lane to public traffic that is not controlled by a pilot car.
5. Sealant application shall be to a minimum 1-inch depth.
CITY OF VALLEJO 150 CITYWIDE SLURRY SEAL – PW9745
6. Where cracks are over ½ inch wide and over 3 inches in depth the crack shall be filled with sand prior to sealing. Fill the crack to 1 inch below the adjacent pavement surface and tamp lightly with a steel rod to reduce any voids in the sand.
7. Except where cracks show signs of raveling or spalling, crack sealing shall be filled flush with no overbanding. All sealant left on the surface shall be squeegeed.
8. Where cracks have been filled with sand, the finish surface of the sealant shall be slightly recessed from the adjacent pavement surface.
Where cracks show signs of raveling or spalling, overband the crack ½ inch on each side of the crack.
Squeegee flush with surface.
Heat the sealant in a kettle or melter constructed as a double boiler, with the space between the inner and outer shells filled with oil or other heat-transfer fluid. Use a kettle or melter with separate thermometers for the oil bath and mixing vat. Equip the kettle with a full sweep type agitator. Also, equip the kettle with a 2- inch (50 mm) minimum recirculating pump to provide circulation of the materials when not applying the crack sealant. Do not apply direct heat to the sealant.
Follow manufacturer’s recommendations for sealant application temperatures. Hot-pour crack sealant shall be heated to the temperature specified by the manufacturer. [Hot rubberized asphalt is generally applied at 370°F to 390°F.] Overheating will not be permitted. The sealant shall be circulated in the hose when the installation train is idle.
Use a mechanical applicator wand capable of continuously feeding the sealant through nozzles capable of placing the crack sealant. A positive sealant flow shutoff mechanism is required. Sealant shall be even and consistent. Sealant shall not be reheated more than the allowable number of times nor greater than the recommended period of time as recommended by the manufacturer. Sealant shall flow evenly with no surging. The vat is to be kept part full at all times.
Cracks shall be filled from the bottom up. There shall be no bubbles due to moisture present in the crack.
Crack sealant shall be applied so that the crack is flush filled immediately following application. Fill the entire crack reservoir with the seala nt from the bottom up to approximately 1/16 inch above the pavement surface.
Excess crack sealant shall be removed from the pavement surface immediately following application.
Removal shall involve the use of a squeegee, starting from the centerline and proceeding to the shoulder.
Immediately scrape the filled cracks with a V-shaped or U-shaped squeegee, or similar hand tool, to smooth the overfill. Squeegee shall be the correct shape and shall not be worn. Squeegee shall be kept clean and free of carbon or filler build up. Squeegee shall be operated at the correct distance fro m the crack and be centered on the crack.
Reapply sealant to any areas that are underfilled or material shrinkage has resulted in a depressed sealant surface. Application shall not be accepted unless it has an even and uniform appearance flush with the pavement surface.
Traffic shall be kept off sealed cracks until the crack sealant has cured enough that it will not track under the action of traffic. The Contractor shall be required to use an approved de -tackifier on crack sealant to allow roadways to open and minimize the duration of closure. Water shall not be considered an acceptable de-tackifier. Within 2 days after application of sealant, sealed cracks that reopen or in which the sealant material sags below the surrounding asphalt concrete surfacing and shoulders sh all be resealed.
Fuel, asphalt and any other spills shall be cleaned up to the satisfaction of the Engineer at the Contractor’s expense.
CITY OF VALLEJO 151 CITYWIDE SLURRY SEAL – PW9745
Measurement and Payment
The contract lump sum (LS) price paid for “Crack Sealing” shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all work involved in the inspecting, herbicide application, cleaning, routing, procurement, setup and maintenance of the crack sealing as depicted on the plans, as specified on these specifications, and as directed by the Engineer, and no additional compensation will be allowed therefor.
12-03 TREE TRIMMING INCLUDING CERTIFIED ARBORIST
Tree trimming will be done to allow for the clearance of slurry seal equipment. From the back of curb, trees will be trimmed to a clearance height of 16 feet.
Measurement and Payment
The contract lump sum (LS) price paid for “Tree Trimming Including Certified Arborist” shall include full compensation for tree trimming including certified arborist as described in these Technical Specifications and no additional compensation will be allowed therefor . Full compensation for furnishing all labor, materials, tools, equipment, removal, hauling, and disposal of resulting material, and incidentals shall be considered as included as part of “Tree Trimming Including Certified Arborist.”
12-04 REMOVAL OF OIL DEPOSITS
Oil-deposit build-up, if found, shall be removed from the asphalt prior to slurry seal. The location and size of these removal areas shall be determined by the Engineer. The Contractor shall remove the excess oil deposits by any method acceptable to industry standards and as approved by the Engineer. Typical removal methods may include burning or scraping (power washing is not permitted).
Oil deposit residual shall be removed and disposed of by the Contractor as mandated by local agencies.
Measurement and Payment
Full compensation for Removal of Oil Deposits shall be considered as included in the various items of work involved and no additional compensation will be allowed therefor.
12-05 CLEANUP
The Contractor shall keep the site in a sanitary and neat condition each day during the project. The Contractor shall eliminate refuse from the site as necessary and when directed by the City in order to avoid an unsightly appearance or inconvenience to others.
The Contractor shall remove and sweep all debris from sidewalks, curb and gutter by the end of each day. This includes staging sites of trucks and haul routes.
Upon completion of Striping, Markings and Raised Pavement Markers installation, the Contractor shall thoroughly clean the work site of all waste, rubbish, construction debris, drips, over sprays, improper markings, and the tracked thermoplastic materials; all of which shall be removed immediately from the pavement surface by methods approved by the Engineer.
Upon completion of the work, the Contractor shall remove from the site all unused materials and all
CITY OF VALLEJO 152 CITYWIDE SLURRY SEAL – PW9745
equipment belonging to or used by Contractor and all rubbish resulting from Contractor’s work on this project.
Contractor agrees to assume sole and complete responsibility for the job site during the course of construction of this project, including safety of all persons and property, that this requirement shall apply continuously and not be limited to normal worki ng hours, and that the Contractor shall hold the City and City representatives harmless from any and all liability in conjunction with the performance of the contractor's work.
Measurement and Payment
Full compensation for Cleanup shall be considered as included in the various items of work involved and no additional compensation will be allowed, therefor.
END OF SECTION
CITY OF VALLEJO 153 CITYWIDE SLURRY SEAL – PW9745
SECTION 13: SLURRY SEAL (TYPE II WITH BLACK ROCK)
(SECTION 37)
13-01 SLURRY SEAL (TYPE II WITH BLACK ROCK)
The slurry seal shall consist of a mixture of a polymer modified asphalt emulsion, mineral aggregate, mineral filler, water and specified additives. The materials shall be proportioned, mixed and uniformly spread over a properly prepared surface as directed by these Special Provisions and the Engineer. The slurry seal shall conform to the requirements of Section 37-2 of the Standard Specifications, Section 37, “Bituminous Seals” of the SJSS and in these Special Provisions. The completed slurry seal shall leave a homogeneous mat and adhere firmly to the prepared surface.
The terminology “latex -modified” and “polymer -modified” asphaltic emulsion are used interchangeably in these Special Provisions to mean the same thing.
13-02 MATERIAL
13-02(A) Asphaltic Emulsion
Asphaltic Emulsion used for slurry seal shall be designated as grade PMCQS -1h or equal.
The polymer used to modify the asphaltic emulsion, shall be, at the option of the Contractor, neoprene, or a co-polymer of butadiene and styrene. Solid polymers shall be adequately blended into the asphalt prior to emulsification. If a liquid latex such as neoprene or similar is used, the latex shall be “co-milled” into the emulsion through the water phase during manufacturing.
Each load of polymer modified asphaltic emulsion shall have a certificate from the asphalt emulsion manufacturer guaranteeing that either asphalt blending or “co-milling” processes were used. The certificate shall also state the percentage of the solid ru bber polymer added by weight of the asphalt as well as the composition of the polymer. The addition of latex to the emulsion after emulsion manufacturing is prohibited.
The polymer modified asphalt emulsion shall conform to the following specifications:
TESTS ON EMULSION: TEST METHOD REQUIREMENT
Minimum Maximum
Viscosity SSF, @ 77° F, seconds AASHTO T59 15 90
Sieve Test, % AASHTO T 539 --- 0.30
Storage Stability Test, 1 day % AASHTO T 59 --- 1.0
Residue by Evaporation, % CTM 331 57 ---
Particle Charge AASHTO T 59 Positive
TESTS ON RESIDUE : TYPICAL REQUIREMENT
Minimum Maximum
Penetration, 77° F AASHTO T 49 40 90
Ductility, 77° F, mm AASHTO T 51 400 ---
Polymer Content, %
See Section 94-1.03 of Standard
Specifications for Sampling Requirements
CTM 401 2.5% ---
OR
Torsional Recovery, % CTM 332 18 ---
CITY OF VALLEJO 154 CITYWIDE SLURRY SEAL – PW9745
A Certificate of Compliance shall be furnished to the Engineer in accordance with Section 6 -1.07, “Certificates of Compliance” of the Standard Specifications and of these Special Provisions. The Certificate of Compliance shall include all information stip ulated in Section 94 of the Standard Specifications.
Additional information relevant to the specifications shall be furnished if requested by the Engineer.
Samples will be obtained in accordance with ASTM Method D140 or such other methods as are approved by the Engineer.
13-02(B) Aggregate
Aggregate for the slurry seal shall comply in all respects to requirements in Section 37 -2 of the Standard Specifications for a Type II Slurry Seal except for the following:
Aggregate shall consist of sound, durable, crushed stone or crushed gravel. If approved by the Engineer, Mineral Filler will be allowed. Aggregates shall be 100% crushed with no rounded particles, volcanic in origin and black in color.
The use of gray or light-colored aggregate shall not be allowed. Aggregate shall be 100% crushed with no round particles, volcanic in origin and black in color, as supplied by George Reed, Table Mountain, Sonora, CA or approved equal.
The percentage composition by weight of the aggregate shall conform to the following grading:
PERCENTAGE PASSING
SIEVE SIZES TYPE II
3/8” (9.5 – mm) 100
No. 4 (4.75 – mm) 90 - 100
No. 8 (2.36 – mm) 65 - 90
No. 16 (1.18 – mm) 40 - 70
No. 30 (600 – um) 25 - 50
No. 200 (75 – um) 5 - 15
Theoretical asphalt content, % based on dry
aggregate
7.5 - 13.5
Approximate application rate (Pounds/Square
Yard)
14-18
The aggregate shall also conform to the following quality requirements:
TEST METHOD OF TEST REQUIREMENT
Sand Equivalent California Method 217 60 MIN.
Durability Index California Method 229 55 MIN.
When the results of both the aggregate grading and the Sand Equivalent test do not conform to the requirement specified, both payments to the City shall apply. The City may deduct these amounts from any monies due, or that may become due the Contractor un der the contract. No single aggregate grading or Sand Equivalent test shall represent more than 300 tons or one-day’s production whichever is smaller.
The Contractor, in accordance with Section 6 -1.07 of Standard Specifications will furnish a certificate of compliance for aggregates used in the slurry seal. The certificate of compliance shall include results of laboratory tests indicating the average gr adation, minimum sand equivalent and maximum film stripping and durability index, all in accordance with Section 37-2.02 C of the Standard Specifications.
CITY OF VALLEJO 155 CITYWIDE SLURRY SEAL – PW9745
13-02(C) Mineral Filler
Mineral Filler shall be either Portland Cement, hydrated lime, limestone dust, fly ash or other approved filler meeting the requirements of ASTM D242 and shall be used if required by the mix design. The mineral filler shall be considered as part of the aggregate in calculations regarding slurry seal asphalt content. 13-02(D) Additives
Additives may be used to accelerate or retard the mixing and setting characteristics of the slurry seal or improve the resulting finished surface. The use of additives in the slurry mix (or individual materials) shall be made initially in quantities predetermined by the mix design with field adjustments if required. If the use of additives during application requires a greater than + or – 1.0% deviation from the recommendations of the mix design, a new mix design will be performed to verify system performance at higher or lower additive levels.
13-02(E) Mix Design
At least seven (7) working days before slurry seal placement commences, the Contractor shall submit to the Engineer for approval a laboratory report of tests and proposed mix design covering the specific materials to be used on the project. The percentage of aspha lt emulsion proposed in the mix design shall be within the percentage range specified in Section 37-2.04, “Proportioning” of the Standard Specifications.
The tests and mix design shall be performed by a laboratory capable of performing the applicable International slurry Seal Association (ISSA) tests. The proposed slurry seal mixture shall conform to the requirements specified when tested in accordance with the following tests:
TEST DESCRIPTION SPEC
ISSA TB 106 Slurry Seal Consistency, mm 30 maximum
ISSA TB-139 Wet Cohesion (using project source aggregate, asphalt emulsion and set-control agents, if used)
30 minutes min
60 minutes min
12kg-cm minimum
20kg-cm minimum
ISSA TB-109 Excess Asphalt
By LWT Sand Adhesion
50 g/ft2 maximum
(538 g/m2 maximum)
ISSA TB-114 Wet Stripping Pass
ISSA TB 115 Compatibility Pass
ISSA TB-100 Wet Track Abrasion Loss, one-hour soak
(minimum asphalt content)
75 g/ft2 maximum
(807 g/m2 maximum)
ISSA TB-113 Mix Time (Mixing test and set time test shall be done at the highest temperature expected during construction
Controllable to 180 sec.
minimum
The laboratory report shall be signed by the laboratory that performed the tests and mix design and shall show the results of the tests on individual materials, comparing the test results to those required by the specifications. The report shall clearly s how the proportions of aggregate, filler (as determined from the tests, minimum and maximum), water (minimum and maximum), asphalt solids content based on the dry weight of aggregate and set -control agent usage. The laboratory shall also report the quanti tative effects of moisture content on the unit weight of the aggregate (bulking effect). Previous laboratory reports covering the same materials may be accepted provided they are made during the same calendar year.
The Engineer shall approve the mix design and all slurry seal materials and methods prior to use. The job mix design shall conform to the specification limits and be suitable for the traffic climate conditions, curing conditions and final use. This will include recommended application rate of slurry to suit the job conditions.
CITY OF VALLEJO 156 CITYWIDE SLURRY SEAL – PW9745
Any changes in the proportions will be made only when approved by the Engineer. 13-02(F) Proportioning
Proportioning shall conform to the provisions in Section 37 -2.04, “Proportioning” of the Standard Specifications and these Special Provisions.
The completed mixture, after addition of water and any set-control agent used, shall be such that the slurry seal mixture has proper workability and (a) will permit uncontrolled traffic on the slurry seal within two (2) hours after placement without the occurrence of tracking, bleeding, raveling, separation or other distresses, and (b) prevent development of bleeding, raveling, separation or other distress within fifteen (15) days after placing the slurry seal.
13-02(G) Mixing and Spreading Equipment
Mixing and spreading equipment shall conform to the provisions in Section 37-2.05, “Mixing and Spreading Equipment” of the Standard Specifications and of these Special Provisions.
A minimum of two 7-cubic yard capacity or larger slurry machines shall be on the job and in good operating condition at all times. Machines must be able to negotiate all turns next to the curbs in cul -de-sacs, on initial pass in one continuous pass.
13-03 CONSTRUCTION
13-03(A) Sequencing Requirements
Slurry seal work on residential streets shall be sequenced in such a manner as to minimize inconvenience to the residents or Recology, the trash management company. Contractor shall schedule its work in conformance with Recology’s schedule as provided for on the Plans. In addition to the traffic control plan requirements, the Contractor shall communicate in his notification flyer to residents, the proposed streets not being worked on. To the maximum extent possible so as to minimize walking distances for residents, the proposed streets not being worked on shall not exceed more than approximately 1,000 feet from the furthest property affected by the slurry seal operation. Any deviations from this requirement shall be approved in advance by the Engineer.
13-03(B) Surface Preparation
Before the polymer modified slurry seal is applied, the pavement surface shall be swept free of all loose debris using power sweepers, cracks shall be filled, and digouts completed. Contractor shall remove all existing weeds and plant materials from all cracks in all street sections that will receive slurry seal surfacing.
This includes vegetation removal from cracks along the edge of pavement or concrete gutter lip. Crack sealing shall be paid under Section 10-5, “Asphalt Crack Sealing”.
WEED REMOVAL - ALL VEGETATION SHALL BE REMOVED FROM CRACKS IN THE PAVEMENT AND AT THE INTERFACE OF PAVEMENT AND GUTTER PRIOR TO SWEEPING. TO FACILITATE
THE CLEANING OPERATIONS, THE CONTRACTOR SHALL USE A WEED SPRAY (ROUND UP OR ITS EQUIVALENT) TEN DAYS PRIOR TO PERFORMING THE CRACK SEALING OPERATIONS.
All existing/temporary pavement markers, paint and thermoplastic shall be removed and disposed of by the Contractor. Said removal shall not occur sooner than two days prior to the slurry sealing is performed and shall be paid under Section 10-6, “Pavement Marker, Thermoplastic Marking and Striping Removal.” Manholes, valves, survey monuments, or miscellaneous frames and covers shall not receive a seal coat.
CITY OF VALLEJO 157 CITYWIDE SLURRY SEAL – PW9745
These shall be protected as noted in Section 10 -3 “Existing Facilities”. Any frame or cover seal coated shall be cleaned to the satisfaction of the Engineer and the cost for the cleaning shall be borne by the Contractor.
13-03(C) Placing
Placing shall conform to the provisions in Section 37-2.06, “Placing” of the Standard Specifications.
No application of slurry mixture shall be permitted when the temperature of the pavement to be surfaced is below 50° F or when the air temperature is below 60°F in the shade or when, in the opinion of the Engineer, road conditions, road temperatures, immin ence of rain, wetness or dampness are not conducive to successful results.
The slurry mixture shall be uniformly spread by means of a controlled spreader box conforming to the requirements of Section 37-2.05 of the Standard Specifications.
If required by the Engineer, the slurry machine shall be inspected and calibrated on a 300-foot test section.
The calibration shall establish the settings required to obtain the application rate for the slurry and correct proportions of ingredients in accordance with these Special Provisions.
The spreader box shall move forward at a rate not greater than 3 miles per hour (270 feet per minute) such that the fluid slurry mixture will penetrate and substantially fill all available voids. All surfaces to be slurry sealed shall be lightly dampened with a fog spray of water. The slurry box squeegees, rubber belting or similar material, shall be flexible enough to wipe the slurry uniformly over the surface of the roadway without gouging, scouring or abrading the existing surface or chips.
Type II slurry seal shall be spread at a rate between 13-15 pounds of dry aggregate per square yard as required or dictated by surface conditions or as determined by the Engineer. The completed spread rate shall be within ten percent of the designated rate.
Areas which cannot be reached with the slurry seal machine shall be surfaced using hand squeegees to provide complete and uniform coverage. Care shall be taken to leave no unsightly appearance from the handwork. All handwork shall achieve the same type of finish as applied by the spreader box. All incidental handwork such as surfacing of driveway aprons and returns shall be done concurrently with the surfacing of the street proper.
The joint between the edge of pavement and the concrete gutter shall be sealed/filled with slurry seal and not overlap into the gutter pan more than one to two inches (1 -2”). Any application spillage beyond this joint shall be removed or cleaned up by the Contractor to the satisfaction of the Engineer. Gutter spills and any tracking of slurry seal onto concrete improvements shall be cleaned immediately. The edges of the limits of the slurry seal application of both sides of the street shall be maintained in a neat and uniform line.
All lines of termination of slurry sealing shall be neat and straight. Contractor shall use building paper or an approved equal header materials at all limits of work. Longitudinal joints shall be at the crown of the street or at the edge of the traveled lanes. No excessive buildup or unsightly appearance shall be permitted on longitudinal and transverse joints.
Care will be taken to avoid leaving ridges at the lap joints between adjoining passes. Wherever possible, joints will coincide with lane lines or in the center of the lane. In no case will ridges be allowed in the normal wheel track of vehicles. The forward speed of the slurry spreader shall be adjusted to eliminate corrugations or surface irregularities in the slurry coat, which are caused by excessive speed.
No lumping, balling, or unmixed aggregate shall be permitted. No segregation of the emulsion and fines from the coarse aggregate shall be permitted. If coarse aggregate settles to the bottom of the mix, the slurry mix shall be removed from the pavement. No excessive breaking of emulsion shall be allowed in the
CITY OF VALLEJO 158 CITYWIDE SLURRY SEAL – PW9745
spreader box. No streaks caused by oversize aggregates will be left on the finished pavement, and ridges, washboarding in the finished product shall not be allowed.
Weight tags shall be furnished to the Engineer for all materials delivered to the site including aggregates, emulsified asphalt for slurry and retardant.
The Contractor shall immediately remove any excess slurry from the gutters. The Contractor shall not continue to the next street until all excess slurry is removed as determined by the Engineer. No extension of time will be granted due to delay caused by non-compliance with this provision.
The Contractor shall furnish and maintain in good operating condition all tools and equipment necessary to do the work with a minimum of inconvenience to the public, and shall employ sufficient personnel to operate all equipment efficiently and skillfully.
The Contractor shall refrain from using fuel or solvents of any kind for cleaning tools and equipment in such a manner as to permit spillage of diesel fuel or solvent on the pavement, curbs, gutters, parkways or other adjoining areas.
13-03(D) Rolling
Following the slurry seal, the surface shall be rolled by a self-propelled, 10-ton pneumatic roller. The intent is to roll these street sections because it may not experience traffic volumes in the various stalls. Roller shall have a tire pressure of 50 PSI and be equipped with a water spray system. All tires shall be smooth surfaced and inflated to the same pressure. The slurry sealed area to be rolled shall be subjected to at least five (5) full coverage passes such that the material is compacted to a uniform surface texture.
Rolling shall occur the same day as the slurry is placed, however it shall not commence until the slurry seal has cured and will not pick up on the tires of the roller. 19-03(E) Initial and Final Sweeping Following Slurry Seal
The Contractor shall provide all necessary equipment, skill, and manpower to sweep all completed slurry sealed streets to the satisfaction of the Engineer, and in accordance with these Special Provisions.
Sweeping shall not begin until a sufficient bond h as developed between the emulsion and the aggregate.
Sweeping shall not dislodge aggregate or patches of applied surface.
The Contractor shall use a commercial sweeper to sweep each street that is slurry sealed. During the sweeping, the sweeper shall use only the rear broom. The front brooms shall not be used during this sweeping operation. Brooms shall be vertically adjustable so as to avoid excess pressure during sweeping.
For slurry sealed streets, the initial sweeping shall be performed no sooner than three (3) calendar days after the slurry seal has been applied to the street. The Contractor shall conduct additional sweepings at seven (7) calendar days and again at fourt een (14) calendars days after the slurry seal has been applied.
A final sweeping shall be performed no sooner than twenty-eight (28) days and no later than forty-two (42) days following the slurry seal application. The Contractor shall submit a schedule of the dates for sweeping.
The sweeping schedule shall be approved by the Engineer prior to occurring.
Sidewalks and driveways adjacent to slurry sealed streets shall also be swept and kept clean of aggregates or other materials resulting from the application operation. 13-03(F) Scheduling of Striping after Slurry Seal has Cured
Permanent traffic stripes, pavement markings and pavement markers shall be installed in accordance with Section 14-03, “Traffic Stripes and Pavement Markings,” of these Special Provisions.
CITY OF VALLEJO 159 CITYWIDE SLURRY SEAL – PW9745
The Contractor shall be responsible for implementing and maintaining temporary delineation until permanent striping, pavement markings and pavement markers have been permanently installed in accordance with Section 10-9, “Temporary Pavement Delineation,” of these Special Provisions.
Any tire tracking from slurry seal surfaced streets to other streets that defaces existing striping and markings shall be washed off the street.
13-03(G) Repair and Acceptance of the Work
In the event that the applied slurry seal surface violates the contract specifications or has the following conditions: tire or wheel tracks, longitudinal or transverse ridges, surface blemishes, wash boarding, footprints, excessively rough sand blotter locations, lack of uniformity in color, or other undesired markings; the Contractor shall, at the direction of the Engineer and at no additional cost to the City, repair and reseal those locations where the conditions exists. The method of treatment shall be approved by the City Engineer or his authorized representative.
Measurement and Payment
The contract square foot price paid for “ Slurry Seal (Type II with Black Rock) ” shall include full compensation for doing all of the work involved with the polymer modified slurry seal and in compliance with the plans and specifications, including the spraying of weeds with weed killer.
Compensation for removing completely and disposing of all existing thermoplastic and painted traffic stripes, pavement markings, and pavement markers, performed in advance of the slurry seal placement, shall be considered as included in the price paid for “Traffic and Pedestrian Control” and no additional compensation will be allowed therefor.
END OF SECTION
CITY OF VALLEJO 160 CITYWIDE SLURRY SEAL – PW9745
SECTION 14: TRAFFIC STRIPING, MARKINGS AND MARKERS
(SECTION 84)
The provisions of Section 84-02, “TRAFFIC STRIPE AND PAVEMENT MARKINGS,” of the Standard Specifications shall apply in their entirety unless modified or supplemented herein.
14-01 REMOVE TRAFFIC STRIPES AND PAVEMENT MARKINGS
Existing pavement markers and thermoplastic striping, when no longer required for traffic lane delineation as directed by the Engineer, shall be removed and disposed of by grinding. Traffic striping and marking shall only be removed within three (3) working days of the slurry seal on each street. Temporary striping shall be placed upon removal of pavement markers and striping. The contractor is required to maintain temporary striping at all times.
The Contractor shall reference all thermoplastic pavement striping and markings and submit the reference information to the City prior to any removal.
Full compensation for Remove Traffic Stripes and Pavement Markings shall be considered as included in the various items of work involved and no additional compensation will be allowed therefor. 14-02 REMOVE PAVEMENT MARKERS
Existing pavement markers (including fire hydrant markers) when no longer required for traffic lane delineation as directed by the Engineer shall be removed and disposed of by an approved method. Temporary striping shall be placed upon removal of pavement markers and striping. The contractor is required to maintain temporary striping at all times.
Full compensation for Remove Pavement Markers shall be considered as included in the various items of work involved and no additional compensation will be allowed therefor. 14-03 TRAFFIC STRIPES AND PAVEMENT MARKINGS
Traffic stripes and pavement markings shall be thermoplastic and conform to the provisions in Section 84 -02, "TRAFFIC STRIPE AND PAVEMENT MARKINGS," of the Standard Specifications and these Technical Specifications.
Contractor shall locate existing striping and legends prior to slurry seal and be able to replace these stripes and legends. When no previously applied figures, markings, or traffic striping are available to serve as a guide, suitable layouts shall be spotted in advance of the permanent application. All layout, spotting, and cat tracking required shall be performed by the Contractor and reviewed by the City Engineer prior to placement of pavement striping or markings. Traffic lines may be spotted by usin g a rope as a guide for marking spots every five (5) feet, by using a marking wheel mounted on a vehicle, or by any other means satisfactory to the Engineer.
The Contractor shall provide an experienced technician to supervise the location, alignment, layout, dimensions, and application of the thermoplastic. The Contractor shall install temporary traffic stripes and pavement markings 4 to 5 hours after applying slurry seal.
All equipment required to perform the work shall be approved in advance by the City Engineer.
Standard word markings, letters, numerals and symbols shall be used. In the absence of such information, all stencils and templates shall be identical with those used by the City. The Contractor shall obtain stencils for all required legends.
All permanent thermoplastic traffic stripes and pavement markings shall be installed and completed after 7
CITY OF VALLEJO 161 CITYWIDE SLURRY SEAL – PW9745
working days immediately after the slurry seal installation.
Newly applied traffic stripes shall be protected from damage by public traffic or other causes until the thermoplastic has thoroughly set up.
Attention is directed to the layout of existing limit lines and crosswalks. New striping shall match existing layout, unless otherwise noted in the plans and specifications. 14-04 PAVEMENT MARKERS
Pavement markers shall conform to the provisions in Section 81 -3, "PAVEMENT MARKERS," of the Standard Specifications and these Technical Specifications.
Pavement markers shall be type AY (non -reflective yellow markers), D (2 -way yellow reflective markers) or B (2 - way clear reflective markers) or non -reflective white markers and conform to the provisions in Section 81 -3, "Pavement Markers," of the Standard Specifications, these Special Provisions, and the Standard Plans.
Two-way blue reflective markers will be placed at each fire hydrant location. Markers are to be located six inches off the centerline of the roadway at right angles to the fire hydrant.
Measurement and Payment
Full compensation for pavement markers, shown on the traffic stripe details, shall be considered as included in the prices paid per linear foot for that traffic stripe and no separate payment will be made therefore.
The unit price paid per “Blue Hydrant Marker” shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all work involved in placing blue hydrant markers, complete in place, including referencing original locations, as shown on the plans, as specified in the Standard Specifications, and these Technical Specifications, and as directed by the City Engineer. 14-05 STRIPE – CENTERLINE (CALTRANS DETAIL 1)
Measurement and Payment
“Stripe – Centerline (Caltrans Detail 1)” shall be measured per linear foot (LF) along the line of the traffic stripe, without deductions for gaps in broken traffic stripes. For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for payment, not the total length of the individual component lines.
Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer.
The contract unit price paid per linear foot (LF) for “ Stripe – Centerline (Caltrans Detail 1)” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement mark ing, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as specified in these Technical Specifications and as direc ted by the City Engineer and no additional compensation will be made thereof.
14-06 STRIPE – CENTERLINE (CALTRANS DETAIL 2)
Measurement and Payment
“Stripe – Centerline (Caltrans Detail 2)” shall be measured per linear foot (LF) along the line of the traffic stripe, without deductions for gaps in broken traffic stripes. For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for payment, not the total length of the individual component lines.
Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer. (Addendum No. 1, July 10, 2024)
CITY OF VALLEJO 162 CITYWIDE SLURRY SEAL – PW9745
The contract unit price paid per linear foot (LF) for “ Stripe – Centerline (Caltrans Detail 2)” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement mark ing, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as specified in these Technical Specifications and as direc ted by the City Engineer and no additional compensation will be made thereof.
14-07 STRIPE – CENTERLINE (CALTRANS DETAIL 9)
Measurement and Payment
“Stripe – Centerline (Caltrans Detail 9)” shall be measured per linear foot (LF) along the line of the traffic stripe, without deductions for gaps in broken traffic stripes. For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for payment, not the total length of the individual component lines.
Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer.
The contract unit price paid per linear foot (LF) for “ Stripe – Centerline (Caltrans Detail 9)” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement mark ing, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as specified in these Technical Specifications and as directed by the City Engineer and no additi onal compensation will be made thereof.
14-08 STRIPE – CENTERLINE (CALTRANS DETAIL 21)
Measurement and Payment
“Stripe – Centerline (Caltrans Detail 21)” shall be measured per linear foot (LF) along the line of the traffic stripe.
For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for payment, not the total length of the individual component lines. Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer.
The contract unit price paid per linear foot (LF) for “ Stripe – Centerline (Caltrans Detail 21)” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement mark ing, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as specified in these Technical Specifications and as directed by the City Engineer and no additi onal compensation will be made thereof.
14-09 STRIPE – CENTERLINE (CALTRANS DETAIL 22)
“Stripe – Centerline (Caltrans Detail 22 )” will be measured per linear foot (LF) along the line of the traffic stripe, without deductions for gaps in broken traffic stripes. For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for payme nt, not the total length of the individual component lines.
Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer.
The contract unit price paid per linear foot ( LF) for “ Stripe – Centerline (Caltrans Detail 22) ” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement mark ing, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as specified in these Technical Specifications and as dire cted by the City Engineer and no additional compensation will be made thereof.
(Addendum No. 1, July 10, 2024)
CITY OF VALLEJO 163 CITYWIDE SLURRY SEAL – PW9745
14-10 STRIPE – LEFT EDGE LINE (CALTRANS DETAIL 24)
“Stripe – Left Edge Line (Caltrans Detail 2 4)” will be measured per linear foot (LF) along the line of the traffic stripe, without deductions for gaps in broken traffic stripes. For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for payme nt, not the total length of the individual component lines. Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer.
The contract unit price paid per linear foot ( LF) for “Stripe – Left Edge Line (Caltrans Detail 24)” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement mark ing, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as specified in these Technical Specifications and as directed by the City Engineer and no additional compensation will be made thereof.
14-11 STRIPE – LEFT EDGE LINE (CALTRANS DETAIL 26B)
“Stripe – Left Edge Line (Caltrans Detail 26B)” will be measured per linear foot (LF) along the line of the traffic stripe, without deductions for gaps in broken traffic stripes. For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for payme nt, not the total length of the individual component lines. Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer.
The contract unit price paid per linear foot ( LF) for “Stripe – Left Edge Line (Caltrans Detail 2 6B)” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement marking, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as specified in these Technical Specifications and as directed by the City Engineer and no additional compensation will be made thereof.
14-12 STRIPE – RIGHT EDGE LINE (CALTRANS DETAIL 27B)
“Stripe – Right Edge Line (Caltrans Detail 27B)” shall be measured per linear foot (LF) along the line of the traffic stripe, without deductions for gaps in broken traffic stripes. For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for payment, not the total length of the individual component lines. Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer.
The contract unit price paid per linear foot ( LF) for the “ Stripe – Right Edge Line (Caltrans Detail 27B) ” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement marking, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as shown on the plans, as specified in these Tec hnical Specifications and as directed by the City Engineer and no additional compensation will be made thereof.
14-13 STRIPE – MEDIAN ISLAND (CALTRANS DETAIL 29)
“Stripe – Median Island (Caltrans Detail 2 9)” will be measured per linear foot (LF) along the line of the traffic stripe, without deductions for gaps in broken traffic stripes. For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for payme nt, not the total length of the individual component lines. Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer.
The contract unit price paid per linear foot ( LF) for “Stripe – Median Island (Caltrans Detail 29)” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement mark ing, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as specified in (Addendum No. 1, July 10, 2024)
CITY OF VALLEJO 164 CITYWIDE SLURRY SEAL – PW9745
these Technical Specifications and as directed by the City Engineer and no additional compensation will be made thereof.
14-14 STRIPE – CHANNELIZING LINE (CALTRANS DETAIL 38 AND 38B) “Stripe – Channelizing Line (Caltrans Detail 38 and 38B)” shall be measured per linear foot (LF) along the line of the traffic stripe, without deductions for gaps in broken traffic stripes. For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for payment, not the total length of the individual component lines. Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer.
The contract unit price paid per linear foot (LF) for “Stripe – Channelizing Line (Caltrans Detail 38 and 38B)” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement marking, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as shown on the plans, as specified in thes e Technical Specifications and as directed by the City Engineer and no additional compensation will be made thereof.
14-15 STRIPE – BIKE LANE (CALTRANS DETAIL 39)
“Stripe – Bike Lane (Caltrans Detail 39)” shall be measured per linear foot (LF) along the line of the traffic stripe, without deductions for gaps in broken traffic stripes. For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for payment, not t he total length of the individual component lines.
Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer.
The contract unit price paid per linear foot ( LF) for “ Stripe – Bike Lane (Caltrans Detail 39) ” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement mark ing, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as shown on the plans, as specified in these Technical Spec ifications and as directed by the City Engineer and no additional compensation will be made thereof.
14-16 STRIPE – THERMOPLASTIC PAVEMENT MARKINGS
“Stripe – Thermoplastic Pavement Markings” shall be measured per square foot (SF) installed. This will include stop, bicycle, arrow or crossings legends.
“Stripe – Thermoplastic Pavement Markings” will be measured as a unit item (SF).
The contract unit price paid per square foot (SF) for “Stripe – Thermoplastic Pavement Markings” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement marking, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as shown on the plans, as specified in these Technical Spe cifications and as directed by the City Engineer and no additional compensation will be made thereof.
14-17 STRIPE - 4” THERMOPLASTIC (WHITE)
“Install 4” white stripe” shall be measured in Liner foot (LF) along the length of the traffic stripe, without deductions for gaps in broken traffic stripes. For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for pay ment, not the total length of the individual component lines. Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer. (Addendum No. 1, July 10, 2024)
CITY OF VALLEJO 165 CITYWIDE SLURRY SEAL – PW9745
The contract unit price paid per linear foot (LF) for “ Stripe - 4” Thermoplastic (White) ” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement markings, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, pavement markers, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as shown on the plans, as specified in these Technical Specifications and as directed by the City Engineer and no additional compensation will be made thereof.
14-18 STRIPE - 12” THERMOPLASTIC (WHITE)
“Install 12” white stripe” and “Install basic crosswalk” shall be measured in Liner foot (LF) along the length of the traffic stripe, without deductions for gaps in broken traffic stripes. For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for pay ment, not the total length of the individual component lines. Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer.
The contract unit price paid per linear foot (LF) for “ Stripe - 12” Thermoplastic (White) ” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement markers, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, pavement markers, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as shown on the plans, as specified in these Technical Specifications and as directed by the City Engineer and no additional compensation will be made thereof.
14-19 STRIPE - 24” THERMOPLASTIC (WHITE)
“Install 24” white stripe” and “Install Ladder crosswalk” shall be measured in Liner foot (LF) along the length of the traffic stripe, without deductions for gaps in broken traffic stripes. For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for payment, not the total length of the individual component lines. Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer.
The contract unit price paid per linear foot (LF) for “ Stripe - 24” Thermoplastic (White) ” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement markers, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, pavement markers, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as shown on the plans, as specified in these Technical Specifications and as directed by the City Engineer and no additional compensation will be made thereof.
14-20 STRIPE - 12” THERMOPLASTIC (YELLOW)
“Install 12” yellow stripe” and “Install basic crosswalk” shall be measured in Liner foot (LF) along the length of the traffic stripe, without deductions for gaps in broken traffic stripes. For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for payment, not the total length of the individual component lines. Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer.
The contract unit price paid per linear foot (LF) for “ Stripe - 12” Thermoplastic (White) ” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement markers, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, pavement markers, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as shown on the plans, as specified in these Technical Specifications and as directed by the City Engineer and no additional compensation (Addendum No. 1, July 10, 2024)
CITY OF VALLEJO 166 CITYWIDE SLURRY SEAL – PW9745
will be made thereof.
14-21 STRIPE - 24” THERMOPLASTIC (YELLOW)
“Install 24” yellow stripe” and “Install Ladder crosswalk” shall be measured in Liner foot (LF) along the length of the traffic stripe, without deductions for gaps in broken traffic stripes. For traffic stripe details requiring multiple lines, the composite section will count as a lineal foot of striping for pay ment, not the total length of the individual component lines. Measurement will be performed in the field by the Contractor upon completion and checked by the Engineer.
The contract unit price paid per linear foot (LF) for “ Stripe - 24” Thermoplastic ( Yellow)” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in applying thermoplastic traffic stripes, pavement markers, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, pavement marking, complete in place, including any necessary cat tracks, dribble lines, alignment for stripes, layout work and temporary traffic stripes and pavement markers, as shown on the plans, as specified in these Technical Specifications and as directed by the City Engineer and no additional compensation will be made thereof.
14-22 BLUE HYDRANT MARKERS
“Two-way blue reflective markers” will be placed at each fire hydrant location. Markers are to be located six inches off the centerline of the roadway at right angles to the fire hydrant.
Full compensation for pavement markers, shown on traffic stripe details, shall be considered as included in the prices paid per linear foot for that traffic stripe and no separate payment will be made therefore.
The contract unit price paid for each (EA) for "Blue Hydrant Markers” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in removing and disposal of existing markers and applying new blue retroreflective hydrant markers as shown in the project drawings, as specified in these Technical Specifications and as directed by the city Engineer, and no additional compensation will be made thereof.
END OF SECTION
(Addendum No. 1, July 10, 2024; Addendum No. 4, July 12, 2024) CITY OF VALLEJO 167 CITYWIDE SLURRY SEAL – PW9745
SECTION 15: FIBERIZED MICRO-SURFACING
15-1 MATERIALS
Micro-surfacing, shall be Type II as specified herein and as shown on the plans and conform to the requirements of Section 37 -3, “Slurry Seals and Micro -Surfacings,” of the Standard Specifications which section is hereby incorporated in these Special Provisions as if set forth in full, the Plans, and these Special Provisions and Technical Specifications. Polymer modified asphaltic emulsion shall be used and mineral filler shall be Portland cement in accordance with Section 37-3.03 B (4).
Fiber shall also be added to the mix. Fiber used in the fiberized micro surfacing shall be FORTA Surface‐EXT fiber, or equivalent alkali and acid resistant fiber, meeting the following specifications. It shall be cut to ¼ to ½ inch in length by an automated fiber cutter system installed on truck prior to adding to the MSE. The fiber shall be added at the rates outlined below. The alkali and acid resistant glass fiber shall meet the following requirements:
Test Requirement
Linear Weight of Roving (tex.) ISO 1889 4,500 min Linear Weight of Strand (tex.) ISO 1889 82 min
Moisture Content (%) ISO 3344 0.35 max
Specific Gravity (g/cm3) 2.68
Softening Point (ºC) 860 min
Tensile Strength (MPa) 1,700 min
Aggregate shall consist of sound, durable, crushed stone or crushed gravel and approved mineral filler. The material shall be washed, clean and free from vegetable matter and other deleterious substances. Aggregates shall be Type II, 100% crushed with no rounded particles, volcanic in origin and black in color, as supplied by George Reed, Table Mountain Plant, Sonora, CA., or Approved Equal. The use of white, gray, or light-colored aggregate will not be allowed. Aggregate shall be in accordance with Section 37-3.03 B (3) and shall be black or dark grey in color. 15-2 MIX DESIGN
At least seven (15) working days before fiberized micro-surfacing placement commences, the Contractor shall submit to the Engineer for approval a laboratory report of tests and proposed mix design covering the specific materials to be used on the project. The mix design shall be proportioned such that the final micro -surfacing is drivable to normal traffic without rutting or shedding within one hour of application . The percentage of asphalt emulsion proposed in the mix design shall be within the percentage range specified in Section 37.3.03 B (5) “Proportion Limits.” T he tests and mix design shall be performed by a laboratory capable of performing the applicable International Slurry Seal Association (ISSA) tests. The proposed fiberized micro-surfacing mixture shall conform to the requirements specified when tested in accordance with 37-3.03 B (5), Micro-Surfacing Mix Designs.
The laboratory that performed the tests and designed the mixture shall sign the laboratory report and shall be AMRL certified and/or participate in the AASHTO Proficiency Program. The report shall show the results of the tests on individual materials and shall compare their values to those required by these special provisions. The report shall clearly show the proportions of aggregate, fiber, filler (minimum and maximum), water (minimum and maximum), set control additive, and PMCQS -1h solids content (mini mum and maximum) based on the dry weight of aggregate.
The laboratory shall report the quantitative effects of moisture content on the unit weight of the aggregate (bulking effect) in conformance with the requirements of ASTM Designation C 29M. Previous laboratory reports covering the same materials may be accepted provided the material test reports were completed within the previous 12 months.
The component materials used in the mix design shall be representative of the fiberized micro-surfacing materials proposed by the Contractor for use on the project.
Once the mix design is approved by the Engineer, no substitution of other material will be permitted unless the materials proposed for substitution are first tested and a laboratory report is submitted for the substituted design in (Addendum No. 4, July 12, 2024)
CITY OF VALLEJO 168 CITYWIDE SLURRY SEAL – PW9745
conformance with the provisions of these special provisions. Substituted materials shall not be used until the mix design for those materials has been approved by the Engineer.
The completed mixture, after addition of water and set control agent, if used, shall be such that the fiberized micro- surfacing mixture has proper workability. At the expiration of the road closure hours, in conformance with the provisions in “Maintaining Traffic” of these special provisions, the fiberized slurry seal mixture shall be sufficiently cured to support unrestricted traffic.
The percentages of each individual material proposed in the mix design shall be shown in the laboratory report.
Individual materials shall be within the following limits:
Material Limits
Residual Asphalt 6.5% to 13.5% by dry weight of aggregate Mineral Filler 0.5% to 3% by dry weight of aggregate
Glass Fiber Top Lift: 0.15% to 0.30% by dry weight of aggregate Glass Fiber Bottom Lift: 0.20% to 0.40% by dry weight aggregate Additive and Water As needed
Proportioning
Aggregate, mineral filler, PMCQS -1h, fiber, water, and additives, including the set -control agent, if used, shall be proportioned by volume utilizing the mix design approved by the Engineer. If more than one kind of aggregate is used, the correct amount of each kind of aggregate to produce the required grading shall be proportioned separately, prior to adding the other materials of the mixture, in a manner that will result in a uniform and homogeneous blend.
The aggregate shall be proportioned using a belt feeder operated with an adjustable cut off gate. The height of the gate opening shall be determinable. The PMCQS -1h shall be proportioned by a positive displacement pump.
Variable rate emulsion pumps, if used, shall be calibrated and sealed in the pump’s calibrated condition in conformance with the ISSA Inspector’s Manual MA-1 prior to usage.
The delivery rate of aggregate and PMCQS -1h per revolution of the aggregate feeder shall be calibrated at the appropriate gate settings for each mixer -spreader truck used on the project in conformance with ISSA Inspector’s Manual MA-1 and in conformance with the provisions of these special provisions.
The aggregate belt feeder shall deliver aggregate to the pug-mill with such volumetric consistency that the deviation for any individual aggregate delivery rate check -run shall not exceed 2.0 percent of the mathematical average of 3 runs of at least three tons each. The emulsion pump shall deliver PMCQS -1h to the pug-mill with such volumetric consistency that the deviation for any individual delivery rate check -run shall be within 2.0 percent of the mathematical average of 3 runs of at least 300 gallons ea ch. The water pump shall deliver water to the pug -mill with such volumetric consistency that the deviation for any individual delivery rate check -run shall be within 2.0 percent of the mathematical average of 3 runs of at least 300 gallons each.
The PMCQS-1h storage tank shall be located immediately before the emulsion pump and shall be equipped with a device which will automatically shut down the power to the emulsion pump and aggregate belt feeder when the PMCQS-1h level is lowered to a point where the pump suction line is exposed.
A temperature-indicating device shall be installed in the emulsion storage tank at the pump suction level. The device shall indicate the temperature of the PMCQS-1h and shall be accurate to within 10°F.
The fiber shall be added at a rate of 0.05 to 0.40% by dry weight of aggregate. The mixer -spreader trucks shall be equipped with a fiber chopper, fiber storage and control systems for injecting fibers into the micro -surfacing mix. It shall be capable of providing up to 7 lbs./min. of fiber injection. The chopper shall cut from 3 to 4 bobbins of fiber into 3/8 +/- 1/8-inch-long pieces and feed them into the aggregate as it enters the inlet hopper. The system shall turn on and off with the main start of the mixer-spreader truck. The system shall be powered by the main hydraulic system of the mixer-spreader truck. The mixer-spreader truck shall be capable of providing 3 to 5 cu. ft./min. of air from the truck air compressor for nozzle cooling and chopper flushing. The mixer -spreader truck shall include an enclosure/mounting and feed system for up to 4 bobbins of fiber roving. (Addendum No. 4, July 12, 2024)
CITY OF VALLEJO 169 CITYWIDE SLURRY SEAL – PW9745
The belt delivering the aggregate to the pug -mill shall be equipped with a device to monitor the depth of aggregate being delivered to the pug-mill. The device for monitoring the depth of aggregate shall automatically shut down the power to the aggregate belt feeder whenever the depth of aggregate is less than the target depth of flow. A second device shall be located where the device will monitor the movement of the aggregate belt by detecting revolutions of the belt feeder. The devices for monitoring no flow or belt movement shall automatically shut down the power to the aggregate belt when the aggregate belt movement is interrupted. The device to detect revolutions of the belt feeder will not be required where the aggregate delivery belt is an integral part of the drive chain. To avoid erroneous shutdown by normal fluctuation, a delay of 3 seconds will be permitted between sensing and shutdown of the operation
15-3 VEGETATION TRIMMING
All Vegetation interfering with or obstructing the work shall be trimmed prior to the start of micro -surfacing in accordance with Section 10-1.01, “Vegetation Trimming”, of these Special Provisions and Technical Specifications. 15-4 MIXING AND SPREADING EQUIPMENT
The fiberized micro-surfacing shall be mixed in continuous pug-mill mixers of adequate size and power for the type of fiberized micro-surfacing to be placed. All indicators shall be in conformance with the provisions of these special provisions and Technical Specifications and shall be in working order prior to commencing mixing and spreading operations.
Mixer-spreader trucks shall be equipped to proportion the PMCQS -1h, water, aggregate, mineral filler, and set - control additives by volume. Rotating and reciprocating equipment on mixer -spreader trucks shall be covered with metal guards.
The mixer-spreader truck shall not be operated unless low -flow and no-flow devices and revolution counters are in good working condition and functioning and metal guards are in place. Indicators required by these special provisions shall be visible while walking alongside the mixer-spreader truck.
Aggregate feeders shall be connected directly to the drive on the emulsion pump. The drive shaft of the aggregate feeder shall be equipped with a revolution counter reading to the nearest one-tenth of a revolution. In addition to the requirements of Section 5-1.33, “Equipment” of the State Standard Specifications, the identifying number of mixer - spreader trucks shall be at least three inches in height, located on the front and rear of the vehicle.
The fiberized micro-surfacing mixture shall be spread by means of a spreader box conforming to the requirements in the “Spreader Box” section of these specifications.
The Engineer or authorized representative shall be present during all equipment calibration or testing prior to the seal coat application.
10.1.01.1. Spreader Box
The spreader box shall be capable of spreading to a width of one travel lane and equipped with a material such as flexible rubber belting on each side and in contact with the pavement. If the spread box is less than
7.5 feet wide, it shall be equipped with a means, such as baffles or reversible motor -driven augers, to uniformly apply micro-surfacing on wider areas, superelevated sections, shoulder slopes, etc. The spreader box shall be equipped with rear flexible strike -off blades making close contact with t he pavement and adjustable to various crown shapes in order to apply a uniform micro-surfacing. The spreader box shall be equipped with flexible drags attached to the rear and cleaned daily and changed if longitudinal scouring occurs. The spreader box shall be clean and free of excess micro-surfacing and/or PMCQS-1h at the start of each work shift.
(Addendum No. 4, July 12, 2024)
CITY OF VALLEJO 170 CITYWIDE SLURRY SEAL – PW9745
10.1.01.2. Wheel Path Depression (Rut) Box
The wheel path depression (rut) box shall be designed to have adjustable strike -off devices to regulate the depth and shall have a width of between five feet and six feet. Hydraulic augers, or similar devices, shall be installed and shall be capable of moving the mixed material from the rear to the front of the filling chamber.
These devices shall also be capable of guiding the larger aggregate into the center, deeper section of the wheel path depression, and forcing the finer material toward the outer edges of the spreader box.
The fiberized micro-surfacing mixture, to be spread in areas inaccessible to the controlled spreader box, may be spread by other methods upon approval of the Engineer. 15-5 TACK COAT
The Contractor shall apply an approved tack coat conforming to Section 94, “Asphaltic Emulsions” of the Standard Specifications which section is hereby incorporated in these Special Provisions as if set forth in full, to the entire existing asphalt surface to be micro-surfaced prior to the application of the micro-surfacing. The grade shall be SS- 1 unless otherwise approved by the Engineer. The asphalt emulsion may be mixed with additional water before applying a micro-surfacing. The maximum ratio of wat er to asphaltic emulsion must be 2 to 1. Tack coat shall be applied at a rate from 0.10 to 0.15 gal/sq yd with the exact rate must be authorized by the Engineer. Tack coat shall be applied using a truck mounted sprayer system capable of a uniform applica tion rate capable of achieving a minimum width of 12-feet in a single pass.
15-6 PREPARATORY WORK
Prior to placement of the surfacing, the Contractor shall clean the existing asphalt concrete surface and remove pavement markings in accordance with section 14, “Adjust Water Valve Frame & Cover to Grade”, 15, “Digout Repair”, 16, “Pavement Preparation,” and 17 “Crack Sealing”. All valve boxes, manholes, utility covers, and monument covers shall be covered with heavy paper or roofing felt prior to placement of the surfacing and shall be uncovered after the surfacing has set. All drainage inlets shall hav e adequate protection and coverings to prevent any surfacing materials from entering the storm drain system.
Test Strip
The Contractor shall construct a test strip for evaluation by the Engineer. The test strip shall be 300 feet to 500 feet long and shall consist of the application courses specified. The test strip shall be constructed at the same time of day or night that the full production of fiberized micro-surfacing will be placed and may be constructed in 2 days or nights when multiple course applications are specified. To be considered acceptable, the test strip shall be drivable and opened to traffic within one hour of application of the fiberized micro-surfacing.
The Engineer will evaluate the completed test strip after a minimum of 12 hours of traffic on the completed test strip to determine if the mix design and placement procedure are acceptable. If the mix design or the placement procedure is determined by the Engineer to be unacceptable, the test strip will be rejected, the Contractor shall make modifications, and a new test strip shall be constructed and evaluated by the Engineer. The cost of materials and placement of the test strips, which have been rejected, shall be borne by the entirely by Contractor and will not be considered as part of the contract work. If ordered by the Engineer, rejected test strips shall be removed at the Contractors expense. If proposed by the Contractor and approved by the Engi neer, the Contractor may continue with production work after placement of the test strip at his own risk. If the test strip is rejected, all production work shall be stopped and evaluated by the Engineer. The production work will be evaluated in the same manner as the placement of the test strip and shall conform to the same requirements for the test strip material. 15-7 PLACING
(Addendum No. 4, July 12, 2024)
CITY OF VALLEJO
171 CITYWIDE SLURRY SEAL – PW9745
Type II fiberized micro-surfacing shall be spread at a rate of 12 to 15 pounds of dry aggregate per square yard.
The fiberized micro-surfacing mixture shall be uniformly spread on the existing surface within the rate specified without spotting, rehandling or otherwise shifting of the mixture.
The fiberized micro-surfacing mixture shall not be placed when the ambient temperature is below 50 °F, there is any surface moisture on the pavement, or during unsuitable weather. Fiberized micro-surfacing shall not be placed if rain is imminent or if there is the possibility that there will be freezing temperatures within 24 hours.
Wheel path and/or trench depressions shall be repaired prior to micro-surfacing. Depressions less than ½ inch shall be filled with a scratch course. When wheel path depressions have a cross section that is deformed ½ inch or more, the individual wheel pa ths shall first be filled with fiberized micro-surfacing utilizing a wheel path depression (rut) box in conformance with the provisions of the Special Provisions and Technical Specifications at the discretion of the Engineer or authorized representative. The depth of the wheel path depression shall be determined after the adjacent ridges have been removed, when applicable. The maximum single application for wheel path depressions shall be one inch. Wheel path depressions of depths greater than one inch s hall require multiple applications in each depression.
Wheel path depression repair shall be constructed with a slight crown to allow for initial compaction by traffic on the fiberized micro-surfacing. Freshly filled wheel path depressions shall be compacted by traffic for a minimum of 24 hours before additional lifts of fiberized micro-surfacing material are placed for rut filling purposes or as surface courses.
Longitudinal joints shall correspond with the edges of the traffic lanes. The Engineer may permit other patterns of longitudinal joints if the patterns will not adversely affect the quality of the finished product.
Through traffic lanes shall be spread in full lane widths only. Longitudinal joints common to 2 traffic lanes shall be (butt joints) with overlaps not to exceed 3 inches. Building paper shall be placed at the transverse joints to avoid double placement o f the fiberized micro-surfacing. Other suitable methods to avoid double placement of the fiberized micro-surfacing will be allowed. Hand tools shall be available to remove spillage.
The mixture shall be uniform and homogeneous after placing on the surfacing and shall not show separation of the PMCQS-1h and aggregate after setting. The completed surface shall be of uniform texture and free from ruts, humps, depressions, or irregularities and shall be drivable within one hour of fiberized micro-surfacing application.
Adequate means shall be provided to protect the fiberized micro-surfacing from damage by traffic until such time that the mixture has cured sufficiently so that the fiberized micro-surfacing will not adhere to or be picked up by the tires of vehicles.
When placing multiple layers of fiberized micro-surfacing (excluding wheel path depressions) the second layer shall not be placed until the following day or later.
Placement of the fiberized micro-surfacing shall cease a minimum of one hour before the expiration of the road closure hours as specified in Section 10 -1.06 “Maintaining Traffic and Pedestrian Operations, ” of these Special Provisions, unless the Contractor proves to the satisfaction of the Engineer that the surface will be ready for unrestricted traffic at the expiration of the road closure hours.
After the initial break of the micro -surfacing and within a minimum of 2 hours after placement the micro -surfacing shall be rolled with a pneumatic tire roller. Surfacing areas shall be rolled with a pneumatic rubber tire roller, not to exceed 7 tons and non-ballasted. Roller shall travel slowly, not more than 5 mph 15-8 POST SWEEPING
Self-propelled power brooms shall be used that are capable of removing loose aggregates generated by the micro- surfacing. Nylon gutter brooms shall be the only brooms used. On the day of the actual micro-surfacing operations, (Addendum No. 4, July 12, 2024)
CITY OF VALLEJO 172 CITYWIDE SLURRY SEAL – PW9745
no sweeping shall take place. Three (3) sweepings shall be performed after placement of the micro-surfacing to remove all loose aggregates. The Contractor must remove all loose aggregates as required by the Engineer. During the sweeping, the sweeper shall use only the rear broom, the front brooms shall not be used during this sweeping operation. The initial sweeping shall be performed no sooner than three (3) and no more than five (5) calendar days after the micro-surfacing has been applied to the stree t. The two (2) remaining sweepings shall be performed no sooner than two (2) weeks and no later than five (5) weeks after the micro-surfacing has been applied to the street.
The self-propelled power broom may not be able to pick up loose aggregates in some locations, thus the Contractor shall remove the loose aggregates in these locations using a vacuum sweeper or other acceptable means, as approved by the Engineer. At the time of each sweeping, all loose materials shall likewise be removed from the sidewalks, driveways, landscaped areas, and properties adjacent to the work area either manually or by any other means acceptable to the Engineer. The Contractor shall use water on these sweepings to achieve dust removal and the aggregates shall be salvaged and removed from the job site.
Up to three (3) additional sweepings shall be performed as directed by the Engineer to remove all loose aggregates from sidewalks, driveways, adjacent private property areas, and the street gutter, and the excess aggregates shall be salvaged and stockpiled at a designated location or removed from the job site. 15-9 REPAIR OF EARLY DISTRESS
If bleeding, raveling, delamination, rutting, excessive shedding, or wash-boarding occurs within 60 days after placing the fiberized micro-surfacing, the Contractor shall diligently pursue repairs by any method approved by the Engineer.
The Contractor shall not be relieved from maintenance until repairs have been completed to the satisfaction of the Engineer.
Measurement and Payment
Micro-surfacing (Type II with Black Rock) bid item will be measured and paid for at the contract price per square yard. Payment for micro -surfacing shall include full compensation for furnishing all labor, materials, tools, equipment, FORTA Surface-EXT fiber or equivalent alkali and acid resistant fiber and incidentals and for doing all the work involved in furnishing and applying the micro -surfacing, including, but not limited to surface preparation, placing the surfacing, protecting the surfacing until it has set, rolling, post sweeping and all other w ork described herein, as directed by the Engineer, or involved in placing Micro-surfacing (Type II with Black Rock ) not specifically enumerated in the Plans or Specifications, and no additional compensation will be allowed.
END OF SECTION
(Addendum No. 4, July 12, 2024)
CITY OF VALLEJO 173 CITYWIDE SLURRY SEAL – PW9745
ATTACHMENT A
PROJECT LABOR AGREEMENT
Project Labor Agreement
for the City of Vallejo
1 PRO
JECT LABOR AGREEMENT
FOR THE CITY OF VALLEJO
INTRODUCTION/FINDINGS
This Project Labor Agreement is entered into this day of , 20 by and between the City of Vallejo (hereinafter the “City”), together with contractors and subcontractors of all tiers, who shall become signatory to this Agreement by signing the “Agreement to be Bound” (Addendum 1) (referred to herein as “Contractor(s)/Employer(s)”), and the Napa-Solano Building and Construction Trades Council (referred to herein as the “Trades Council”) and the local Unions that have executed this Agreement (referred to collectively herein as the “Union(s)”).
The purpose of th
is Agreement is to promote the efficiency of construction operations for the City of Vallejo through the use of skilled labor resulting in quality construction outcomes, and to provide for the orderly settlement of labor disputes and grievances without strikes or lockouts, thereby promoting the public interest in assuring the timely and economical completion of Covered Projects as defined in Section 1.10 below.
WHEREAS, the timely and successful completion of Covered Projects is of the utmost importance to meet the needs of the City and avoid increased costs resulting from delays in construction; and
WHEREAS, large numbers of workers of various skills are required in the performance of construction work on Covered Projects who will be represented by the Unions who are signatory to this Agreement and employed by the Contractors and subcontractors who are also signatory to this Agreement; and
WHEREAS, the use of skilled labor on construction work increases the safety of construction projects as well as the quality of completed work; and WHEREAS, it is recognized that on Covered Projects with multiple contractors and bargaining units on the job site at the same time over an extended period of time, the potential for work disruption may be substantial without an overriding commitment to maintain continuity of work; and
WHEREAS, the interests of the general public, the City, the Unions, and the Contractors/Employers are best served if the construction work proceeds in an orderly manner without disruption because of strikes, sympathy strikes, work stoppages, picketing, lockouts, slowdowns or other interferences with work; and
WHEREAS, the Contractors/Employers and the Unions desire to mutually establish and stabilize wages, hours and working conditions for the workers employed on Covered Projects and to encourage close cooperation among the Contractors/Employers and the Unions so that a satisfactory, continuous and harmonious relationship will exist among the parties to this Agreement; and
(Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
2 WHEREAS, the parties agree that one of the primary purposes of this Agreement is to avoid the tensions that might arise on the Covered Projects if Union and non-union workers of different employers were to work side by side on the Covered Projects, potentially leading to labor disputes that could delay completion of the Covered Projects; and WHEREAS, this Agreement is not intended to replace, interfere with, abrogate, diminish or modify existing local or national collective bargaining agreements in effect during the duration of this Agreement, insofar as a legally binding agreement exists between the Contractors/Employers and the Unions, except to the extent that the provisions of this Agreement are inconsistent with said collective bargaining agreements, in which event the provisions of this Agreement shall prevail. It is understood that Contractor(s)/Employer(s) are bound and shall remain bound, for the duration of this Agreement, by the terms of this Agreement and the applicable local and national collective bargaining agreements for the craft work performed, established between the signatory Unions and Contractors/Employers, in effect and covering the area of these Covered Projects; and
WHEREAS, the City places high priority upon the development of comprehensive programs for the recruitment, training and employment of local area residents and military veterans, and recognizes the ability of local pre-apprenticeship and apprenticeship programs to provide meaningful and sustainable career pathways in the construction industry; and WHEREAS, the contract(s) for construction work on Covered Projects will be awarded in accordance with the applicable provisions of the California State Public Contract Code, the Charter of the City of Vallejo, the Vallejo Municipal Code, and all state, local and federal laws; and
WHEREAS, The City has adopted this Agreement which will provide construction employment and training opportunities in ways calculated to mitigate the harms caused by poverty, unemployment, and underemployment; and
WHEREAS, this Agreement reflects a commitment by all parties to the diversity in the workforce on Covered Projects to the extent allowed by law, to reflect levels of minority, women and other worker utilization at levels which are representative of the relevant workforce of these groups in the Vallejo area as determined by the U.S. Census Bureau; and WHEREAS, the parties to this Agreement pledge their full good faith and trust to work toward the mutually satisfactory completion of all Covered Projects;
NOW, THEREFORE, IT IS AGREED BETWEEN AND AMONG THE PARTIES HERETO, AS FOLLOWS:
ARTICLE I
DEFINITIONS
“Agreement” means this Project Labor Agreement.
“Agreement to be Bound” means the agreement (attached hereto as Addendum 1) (Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
3 t
hat shall be executed by each and every Contractor/Employer as a condition of working on Covered Projects.
“Apprentice” means any worker who is indentured in a bona fide joint Labor/Management construction apprenticeship program, registered and approved by the State of California Department of Industrial Relations (DIR) Division of Apprenticeship Standards (DAS), and in the case of Covered Projects with Federal funding, consistent with the requirements of the US Department of Labor (DOL). “Apprentice Program” means any joint Labor/Management Construction apprenticeship program certified and approved by the California DAS, and in the case of Covered Projects with Federal funding, consistent with the requirements of the US DOL. “City” means the City of Vallejo and its city council, officers, agents, attorneys and employees, including managerial personnel.
“Completion” means that point at which there is Final Acceptance by the City of a Covered Project and the City has filed a Notice of Completion. For purposes of this definition, "Final Acceptance" means that point in time at which the City has determined upon final inspection that the work has been completed and all required contract documents, contract drawings, warranties, certificates, manuals and data have been submitted and training completed in accordance with the contract documents and the City has executed a written acceptance of the work.
“Construction Contract” means all contracts under which construction is done which are necessary to complete the Covered Project(s). “Contractor(s)/Employer(s)” means any individual, firm, partnership, or corporation (including the prime contractor, general contractor, subcontractor of any tier, or combination thereof, including joint ventures, and their successors and assigns), that is a business enterprise and which is properly licensed for the work intended, and has entered into a Construction Contract for a Covered Project under this Agreement, with respect to the construction of any part of a Covered Project within this Agreement. “Core Worker” means a verifiable member of the Contractor(s)/Employer(s) core workforce whose name appears on the Contractor(s)/Employer(s) active payroll for 60 of 100 working days immediately prior to the award of the Construction Contract; who has worked at least four-thousand (4,000) hours in the construction craft in which they are employed, during the prior four (4) years; who resides in Priority 1-3 as set forth in Section 9.1; and who meets all standards required by applicable local, state or federal law or regulation.
“Covered Project” means City capital improvement projects where either the engineer’s estimate of the total cost of the project or the actual cumulative bid amount(s) submitted by the contractor(s) awarded the Construction Contract(s) for the Project, exceeds seven hundred and fifty thousand dollars ($750,000). All Construction Contracts required to complete a Covered Project shall be considered in determining whether this (Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
4 thr
eshold is met. The City and the Trades Council may mutually agree in writing to add additional projects or components to be covered by this Agreement. Covered Projects and Construction Contracts will not be split, divided or otherwise separated for the purpose of avoiding application of this Agreement. The term “Covered Project” applies to each and all projects as defined in this section, whether used in the singular or plural. “Employment Hiring Plan” or (“EHP”-) means a Contractor/Employer’s detailed hiring plan.
“Local Resident” means an individual who resides within the City Limits of the City of Vallejo.
“Master Agreement” means the Master Collective Bargaining Agreement negotiated and executed from time to time by each craft Union signatory hereto. “Project Manager” means the person(s) or entity(ies) designated by the City to oversee all phases of construction on any Covered Project and the implementation of this Agreement.
“Trades Council” means the Napa-Solano Building and Construction Trades Council.
“Union” or “Unions” means the Napa-Solano Building and Construction Trades Council and the Unions signatory to this Agreement, acting on their own behalf and on behalf of their respective affiliates and member organizations whose names are subscribed hereto and who have through their officers executed this Agreement.
ARTICLE II
SCOPE OF AGREEMENT
1.1 Parties: This Agreement applies to and is limited to the City and all Contractors/Employers performing work pursuant to Construction Contracts on a Covered Project and their successors and assigns, the Trades Council, and the Unions signatory to this Agreement.
1.2 Applicability: This Agreement shall apply to all Construction Contracts awarded on a Covered Project. Construction Contracts shall be considered Completed as set forth in Section 1.6, except when the City directs a Contractor to engage in repairs, construction warranty work, modifications, or punch list work under a Construction Contract or when a Contractor performs work under a change order for a Construction Contract. The City has the absolute right to combine, consolidate or cancel contracts or portions of contracts identified as part of the Covered Project. However, should the City remove any contract, subcontract, or work from a Covered Project and thereafter authorize such work to be commenced after a new competitive bidding process, such work shall be performed under the terms of this Agreement unless said contract, subcontract, or work is awarded under a new contract and is less than seven hundred fifty thousand dollars ($750,000).
(Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
5 1.3 Covered Work: This Agreement covers, without limitation, all site preparation, surveying, construction, alteration, demolition, installation, improvement, remediation, retrofit, painting or repair of buildings, structures and other works, and related activities for a Covered Project that is within the craft jurisdiction of one of the Unions and that is part of a Covered Project, including, without limitation the following examples: geotechnical and exploratory drilling, soils and materials testing and inspection , temporary HVAC, landscaping and temporary fencing, pipelines (including those in linear corridors built to serve a Covered Project), pumps, pump stations, start-up, modular furniture installation (as covered by California Prevailing Wage Determinations) included as part of the Covered Project, and final clean-up.
Covered Work includes work done for a Covered Project in temporary yards, dedicated sites, or areas adjacent to a Covered Project, and at any on-site or off-site batch plant constructed to supply materials to a Covered Project. Covered Work does not include excluded work as set forth in Section 2.4 below or any work performed pre-bid for a Covered Project.
1.3.1 T
his Agreement applies to any start -up, calibration, commissioning, performance testing, repair, maintenance, and operational revisions to systems and/or subsystems for the Covered Project performed after Completion, unless performed by City employees or is exempt pursuant to Section 2.4. For the avoidance of doubt, this Agreement applies to post- Completion work on a Covered Project only if such work is performed pursuant to the original Construction Contract for the Covered Project. Notwithstanding the foregoing, if a Project involves the start-up, commissioning or performance testing of highly specialized or proprietary equipment and/or systems, such work may be performed by personnel of the company providing such equipment and/or systems.
1.3.2 This Agreement covers all on-site fabrication work over which the City, Contractor(s)/Employer(s) or subcontractor(s) possess the right of control (including work done for a Covered Project in any temporary yard or area established for a Covered Project) This Agreement also covers any off-site work, including fabrication (unless excluded otherwise in this Agreement), that is traditionally performed by the Unions and is part of a Covered Project, provided such work is covered by a Master Agreement or local addenda to a national agreement of the applicable Union(s). For the avoidance of doubt, the provisions of this Agreement shall only apply to work within the scope of a Covered Project
1.3.3 The City is not limited or restricted on the choice of materials or the full use and installation of equipment, machinery, package units, factory pre-cast, prefabricated or preassembled materials, tools, or other labor-saving devices, except as set forth in Section 2.3.2.
Otherwise, the City has the right to purchase material and equipment from any source, and craft persons covered by this Agreement will handle and install such material and equipment unless the manufacturer requires that it or its specialized contractor handle or install such material and equipment, as provided in Section 2.4.10.
1.3.4 This Agreement covers all construction trucking work, including the hauling and delivery of ready-mix, asphalt, aggregate, sand, soil or other fill or similar material that is directly incorporated into the construction process as well as the off-hauling of soil, sand, gravel, rocks, concrete, asphalt, excavation materials, construction debris and excess fill, material and/or mud. Contractor(s)/Employer(s), including brokers, of persons providing (Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
6 c
onstruction trucking work shall provide certified payroll records to the City within ten (10) days of written request or as required by the bid specifications.
1.3.5 Work covered by this Agreement within the following craft jurisdictions shall be performed under the terms of their National Agreements as follows: the National Transient Lodge (NTL) Articles of Agreement, the National Stack/Chimney Agreement, the National Cooling Tower Agreement, the National Agreement of Elevator Constructors, and any instrument calibration work and loop checking shall be performed under the terms of the UA/IBEW Joint National Agreement for Instrument and Control Systems Technicians, with the exception that Articles IV, XII and XIII of this Agreement shall apply to such work.
1.3.6 The City shall not be responsible for interpretation or application of any of the National Agreements in Section 2.3.5 nor shall the City be liable to any party for the breach of any such agreement.
1.4 E
xclusions: The following shall be excluded from the scope of this Agreement.
1.4.1 Work performed by the City’s own employees as permitted by the Public Contract Code.
1.4.2 Work performed by Contractor/Employer’s non-construction craft executives, managerial employees, administrative personnel, and supervisors above the level of general foreman (unless covered by a Prevailing Wage determination).
1.4.3 The off-site maintenance of leased equipment and on-site supervision of such work.
1.4.4 Work performed on or near or leading to the site of a Covered Project that is undertaken by state, county, city, or other governmental bodies or their contractors.
1.4.5 This Agreement shall not apply to Emergency Projects as defined by the Public Contract Code or other state law, or the Vallejo Municipal Code, where the work is exempted from the obligation to solicit bids.
1.4.6 This Agreement shall not apply to any non-Project work performed on or near or leading to the site of work covered by this Agreement that is undertaken by state, county, city, or other governmental bodies or their contractors.
1.4.7 Work related to the creation of any Artwork by an individual Artist as part of the City’s Public Art Program, or other work related to public art. For purposes of this Agreement, “Artwork” is a unique, one-of-a-kind decorative element to be incorporated into the building or site, the design, illustration, and detailing of which can only be fully completed in the field and can only be performed by the individual Artist. An “Artist” is an individual that is engaged by the City to create and install Artwork. This Agreement does not apply to final adjustments, finishing touches, and final painting of any Artwork performed by the Artist.
1.4.8 Contracts entered into before the effective date of this Agreement. (Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
7 1.4.9
Contracts that are outside the scope of this Agreement.
1.4.10 Work performed by manufacturers or manufacturers’ representatives of specialty process equipment or systems where the work must be performed by such persons as expressly stated in the manufacturer’s or vendor’s written warranty or guarantee as a condition of the warranty or guarantee, provided the manufacturer or the manufacturer’s representative possesses any license required for the performance of the work. In the case of a warranty exemption, the Contractor/Employer shall provide copies of the written warranty requirement to the affected Union and the City prior to the commencement of work by the manufacturer or vendor.
1.4.11 In the event the City intends to award a contract without a competitive bidding process pursuant to the sole source exemption contained in Vallejo Municipal Code Sections 3.20.90(a)(2) and 3.20.150, the City may request that the Trades Council meet and confer regarding the applicability of this Agreement or any accommodations necessary under this Agreement.
1.4.12 Work performed by public or private utilities including all electrical utility, voice-data-video, and security installation work ahead of and up to the service provider point of termination shall be excluded. All electrical utility, voice-data-video, and security installation work performed after the service provider point of termination shall be Covered Work. Additionally, all contracted work performed ahead of the service provider point of termination that is inside the property line and provides for access to the building via a conduit or series of conduits shall be Covered Work.
1.4.13 In the event the City intends to procure modular buildings or structures, the City may request that the Trades Council meet and confer regarding the applicability of Section 2.3.2 or any other accommodations necessary under this Agreement.
1.4.14 Maintenance work performed pursuant to a multi-year maintenance contract, unless the average annual value of the multi-year maintenance contract exceeds the Covered Project threshold identified in Section 1.10.
1.4.15 This Agreement shall not apply to work funded by any federal, state, local or other public agency that prohibits the use of project labor agreements on projects receiving its funding, or the funding of projects on which such agreements are used. Notwithstanding the foregoing, should only a specific provision of the Agreement be prohibited by the funding source, then, upon mutual agreement of the City and the Trades Council, the parties will modify the requirements of this Agreement accordingly, to allow this Agreement to remain in place and to advance the purposes of this Agreement to the maximum extent feasible.
1.4.16 Work performed under any takeover agreement with a surety company that has guaranteed performance pursuant to a performance bond for a public works contract.
1.5 Award of Contracts: The City holds the right to select any qualified bidder for the award of Construction Contracts for Covered Projects under this Agreement. The bidder shall be responsive, responsible, willing, ready and able to execute and comply with this Agreement as it (Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
8 applies to a Covered Project. This Agreement shall be included in all invitations to bid or solicitations for proposals from Contractors or subcontractors for work on Covered Projects. A copy of all invitations to bid for Covered Projects shall be provided to the Trades Council at the time of issuance.
ARTICLE III
EFFECT OF AGREEMENT
3.1 B y executing this Agreement, the Trades Council, the Unions and the City agree to be bound by each and all of the provisions of the Agreement.
3.2 By accepting the award of work under a Construction Contract for a Covered Project, whether as a Contractor or subcontractor thereunder, all Contractors/Employers agree to be bound by each and every provision of this Agreement and agree to evidence their acceptance prior to the commencement of work by executing the Agreement to be Bound in the form attached hereto as Addendum 1.
3.3 At the time that any Contractor/Employer enters into a subcontract with any subcontractor providing for the performance of work under a Construction Contract, the Contractor/Employer shall provide a copy of this Agreement to said subcontractor and shall require the subcontractor, as a condition of accepting the award of a construction subcontract, to agree in writing, by executing the Agreement to be Bound, to be bound by each and every provision of this Agreement prior to the commencement of work. The obligations of a Contractor may not be evaded by subcontracting. If the subcontractor refuses to execute the Agreement to be Bound, then such subcontractor shall not be awarded a Construction Contract on the Covered Project.
3.4 This Agr eement shall only be binding on the signatory parties hereto, and their successors and assigns, and shall not apply to the parents, affiliates, subsidiaries, or other ventures of any such party. Each Contractor shall alone be liable and responsible for its own individual acts and conduct and for any breach or alleged breach of this Agreement.
Notwithstanding the foregoing, any shared liability provided by law or a Master Agreement shall apply. Any dispute between the Union(s) and the Contractor(s) with respect to compliance with this Agreement shall not affect the rights, liabilities, obligations and duties between the Union(s) and other Contractor(s) party to this Agreement.
3.5 It is mutually agreed by the parties that any liability by a Union signatory to this Agreement shall be several and not joint. Any alleged breach of this Agreement by a Union shall not affect the rights, liabilities, obligations and duties between the Contractor(s) and the other Union(s) party to this Agreement.
3.6 The provisions of this Agreement and the applicable Master Agreements shall apply to the work covered by this Agreement, notwithstanding the provisions of any other local, area and/or national agreements which may conflict with or differ from the terms of this Agreement. To the extent a provision of this Agreement conflicts with a Master Agreement, the provision of this Agreement shall prevail. Where a provision of a Master Agreement does not conflict with this Agreement, the provision of the Master Agreement shall apply. (Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
9 3.7 N
otwithstanding any other provision of this Article or this Agreement, the City shall not be liable for any violation or breach and is not a party to any Master Agreement.
ARTICLE IV
WORK STOPPAGES, STRIKES, SYMPATHY STRIKES AND LOCKOUTS
4.1. The Unions, the City, and the Contractor(s)/Employer(s) covered by this Agreement agree that for the duration of a Covered Project:
4.1.1 There shall be no strikes, sympathy strikes, work stoppages, picketing, handbilling, slowdown, withholding of work, refusal to work, sick-out, walk-off, sitdown, stand- in, wobble, boycott, disruption or otherwise advising the public that a labor dispute exists, or slowdowns of any kind, for any reason, by the Unions or employees employed on a Covered Project, at the job site of a Covered Project or any other facility of City because of a dispute on a Covered Project and shall not sanction, aid, abet or encourage same, and will affirmatively take all reasonable and lawful measures necessary to effectively induce their respective members to cross any and all picket lines. Disputes arising between the Unions and Contractor(s)/ Employer(s) on other City projects are not governed by the terms of the Agreement or this Article.
4.1.2 There shall be no lockout of any kind by a Contractor/Employer of workers employed on a Covered Project.
4.1.3 If a Master Agreement expires before the Contractor/Employer completes the performance of work under a Construction Contract and the Union or Contractor/Employer gives notice of a demand for a new or modified Master Agreement, the Union agrees that it will not strike on work covered by this Agreement and the Union and the Contractor/Employer agree that the expired Master Agreement will continue in full force and effect for work covered under this Agreement until a new or modified Master Agreement is executed. If the new or modified Master Agreement provides that any terms of the Master Agreement shall be retroactive, provided the new Master Agreement does not conflict with this Agreement, the Contractor/ Employer agrees to comply with any retroactive terms of the new or modified Master Agreement that are applicable to any employee(s) on the Covered Project during the interim, with retroactive payment due within seven (7) calendar days of the effective date of the new or modified Master Agreement.
4.1.4 In the case of nonpayment of wages or trust fund contributions on a Covered Project, the Union shall give the City and the Contractor/Employer three (3) business days’ notice when nonpayment of trust fund contributions has occurred, and one (1) business days’ notice when nonpayment of wages has occurred or when paychecks being tendered to a financial institution normally recognized to honor such paychecks will not honor such paycheck, of the intent to withhold labor from the Contractor/Employers or their subcontractor’s workforce, during which time the Contractor/Employer may correct the default. In this instance, a Union's withholding of labor (but not picketing) from a Contractor/Employer who has failed to pay its fringe benefit contributions or failed to meet its weekly payroll shall not be considered a violation of this Article.
(Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
10 4.1.5 Notification: If the City or any Contractor contends that any Union has violated this Article, it will so notify in writing the Senior Executive of the Trades Council and the Senior Executive of the Union, setting forth the facts alleged to violate the Article, prior to instituting the expedited arbitration procedure set forth below. The Trades Council will immediately use its best efforts to cause the cessation of any violation of this Article. The leadership of the Union will immediately inform the workers of their obligations under this Article. A Union complying with this obligation shall not be held responsible for the unauthorized acts of employees it represents.
4.2 Expedited Arb
itration: Any party to this Agreement shall institute the following procedure, prior to initiating any other action at law or equity, when a breach of this Article is alleged to have occurred.
4.2.1 Upon receipt of notice that a party is invoking this procedure, the parties sh
all meet and confer to select an arbitrator. If the parties cannot mutually agree on the selection of an arbitrator, the parties shall each provide a list of three arbitrators. The parties shall select the arbitrator using the alternate striking method. The order of striking names from the list of arbitrators shall be determined by a coin toss, the winner of which shall decide whether they wish to strike first or second. Notice to the arbitrator shall be by the most expeditious means available, with notice by email and telephone to the City, the involved Contractor, and the party alleged to be in violation, and to the Trades Council and involved local Union if a Union is alleged to be in violation.
4.2.2 Upon receipt of notice that an arbitrator has been selected, the City will contact the selected arbitrator and attempt to convene a hearing within twenty-four (24) hours if it is contended that the violation still exists.
4.2.3 The arbitrator shall notify the parties by email and telephone of the place and time for the hearing. Said hearing shall be completed as soon as reasonably possible. An intentional failure of any party to attend said hearings shall not delay the hearing of evidence or the issuance of an award by the arbitrator.
4.2.4 The sole issue at the hearing shall be whether or not a violation of Section
4.1 of the Agreement has occurred. The arbitrator shall have no authority to consider any matter of justification, explanation or mitigation of such violation or to award damages, which issue is reserved for court proceedings, if any. The award shall be issued in writing within three (3) hours after the close of the hearing, and may be issued without a written opinion. If any party desires a written opinion, one shall be issued within fifteen (15) calendar days, but the parties shall not delay compliance with or enforcement of the award due to the issuance of a written opinion. The arbitrator may order cessation of the violation of this Article, and the arbitrator’s award shall be served on all parties by hand or registered mail upon issuance. Should a party found in violation of this Article fail to comply with the arbitrator's award ordering the party to cease the violation, the party in violation shall pay to the affected party as liquidated damages the sum of ten thousand dollars ($10,000.00) per shift for which it failed to comply, or portion thereof, until such violation is ceased. The arbitrator shall retain jurisdiction to resolve any disputes regarding the liquidated damages claimed under this section.
(Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
11 4.2.5 The arbitrator’s award may be enforced by any court of competent jurisdiction upon the fili ng of this Agreement and all other relevant documents referred to above in the following manner. The party filing such enforcement proc eedings shall g ive written notice to the other party. In a proceeding to obta in a temporary order enforcing the arbitrator's award as issued under this Article, all parties waive the right to a hearing and agree that such proceeding may be ex parte. H owever , such agreement does not waive any party's right to seek or pa rticipate in a hearing for a final order of enforcement. Any court order enforcing the arbitrator's award sha
ll be served on all parties by hand or delivered by certified mail.
4.2.6 Any rights created by statute or law governing arbitration proceedings inconsistent with the above procedure, or which interfere with compliance with the above procedure, are waived by the parties to the extent such rights are legally waivable.
4.2.7 The fees and expenses of the arbitrator shall be divided equally between the party instituting the arbitration proceedings provided in this Article and the party alleged to be in breach of its obligation under this Article.
ARTICLE V
CRAFT ASSIGNMENT PRE-JOB C ONFERENCES
5.1 Timing: The G eneral Contractor for a Covered Project and the Trades Council shall convene and conduct, at a l ocation and time mutually agreeable to the T rades Council and the City, a craft assignment pre-job conference with the Unions and the representatives of all involved Contractors/Employers, who shall be prepared to announce craft assignments and discuss in detail the scope of work and the other issues set forth below, at least fourteen (14) calendar days prior to:
(a) Th
e commencement of any Covered Project work, and
(b) The commencement of Covered Project work on any subsequently awarded Construction Contract.
5.2 The craft assignment pre-job conference shall be attended by a representative of each participating Contractor and each affected Union; the Trades Council and City representatives may attend at their discretion.
5.3 The craft assignment pre-job conference shall include but not be limited to the following subjects:
(a) A listing of each Contractor’s scope of work;
(b) The craft assignments;
(c) The estimated number of craft workers required to perform the work; (d) Transportation arrangements;
(e) The estimated start and completion dates of the work; and (Addendum No. 3 , July 11, 2024)
Project Labor Agreement
for the City of Vallejo
12 (f) Discussion of pre-fabricated materials.
5.4 Joint Administrative Committee: In order to ensure the terms of this Agreement are being fulfilled and concerns pertaining to the operation of this Agreement are addressed, the City and the Trades Council shall establish a Joint Administrative Committee comprised of up to four representatives with an equal number of representatives from the City and the Trades Council. The Joint Administrative Committee shall meet on a periodic basis during the term of construction, at least semi-annually, to assess the implementation of this Agreement, review the progress of any Covered Projects, and facilitate harmonious relations between the parties. Both the City and the Trades Council shall have the right to call a meeting of the Joint Administrative Committee.
ARTICLE VI
NO DISCRIMINATION
6.1 The Contractors/Employers and the Unions agree to comply with all anti- discrimination provisions of federal, state, and local law, to protect employees and applicants for employment, on Covered Projects.
ARTICLE VII
UNION REPRESENTATION AND REFERRAL
7.1 The Contractors/Employers recognize the Unions as the sole bargaining representative of all craft employees performing Covered Work under this Agreement, and all such employees must be represented by a Union for the duration of their employment on Covered Projects.
7.2 The Contractors/Employers shall make and transmit all deductions for Union dues, fees, and assessments that have been authorized by employees in writing in accordance with the applicable Master Agreement. This Agreement does not require any employee of a non- Union contractor to join a Union or to pay dues or fees to a Union as a condition of working on the Project; however, nothing in this Article is intended to supersede the requirements of the applicable Master Agreements as to Contractors/Employers signatory to such Master Agreements and as to employees of those Contractors/Employers who are performing Covered Work.
7.3 Authorized representatives of the Unions shall have access to a Covered Project whenever work covered by this Agreement is being, has been, or will be performed on that Covered Project.
7.4 C ore Workers: A Contractor may request by name, and the Union shall honor, referral of Core Workers who have applied to the Union for Covered Project work and who demonstrate to the Union dispatcher and provide satisfactory proof (with a copy of such proof provided to the Project Manager) that the worker meets all the following qualifications:
1. Appearance on the Contractor/Employer’s active payroll for at l
east the last sixty (60) out of the one hundred (100) working days (Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
13 pri
or to award of a Construction Contract;
2. Possession of all licenses and certifications required by applicable state and federal law for the Covered Project work;
3. Has worked at least four thousand (4,000) hours in the appropriate construction craft during the past two years; and
4. Is a resident of the City of Vallejo or the Counties of Napa, Contra Costa, Alameda, Marin, Solano, Sonoma, San Mateo, and San Francisco.
7.4.1 The following procedure shall apply for dispatch of Core Workers: the first one (1) worker will be referred from the applicable Union hiring hall out-of-work list, then one (1) Core Worker shall be selected and referred from the hiring hall, followed by one (1) worker from the hiring hall out-of-work list, and this process shall repeat until such Contractor/Employer’s requirements are met or until such Contractor/Employer has hired three (3) such Core Workers for that trade or craft, whichever occurs first. Thereafter, all additional employees in the affected trade or craft shall be hired exclusively from the applicable hiring hall out-of-work list. In the event the Contractor/Employer reduces the workforce, such reduction will take place in the reverse order of assignment and in the same ratios as was applied in hiring.
7.4.2 Contractor/Employer(s) signatory to a Local, Regional, and/or National collective bargaining agreement with Union(s) signatory hereto shall be bound to use the hiring hall provisions contained in the Master Agreement of the affected Union(s), and nothing in the referral provisions of this Agreement shall be construed to supersede the local hiring hall provisions of the Master Agreement(s) as they relate to such Contractor/Employer(s).
Contractor/Employer(s) shall be bound by and utilize the registration facilities and referral systems established or authorized by the signatory Unions when such procedures are not in violation of Federal law.
7.4.3 The Contractor/Employer shall identify Core Workers in their Employment Hiring Plan and shall provide payroll records evidencing the worker’s qualification as a Core Worker upon request by the City. Prior to each Contractor performing any Covered Project work, such Contractor or subcontractor shall provide a list of its Core Workers to the City and the Trades Council. Failure of such a Contractor to do so will result in that Contractor being prohibited from using any Core Workers on that Construction Contract.
7.5 C
ontractor(s)/Employer(s) performing construction work on a Covered Project shall, in filling craft job requirements, utilize and be bound by the registration facilities and referral systems established or authorized by the Unions signatory hereto. The Contractor(s)/Employer(s) shall have the right to reject any applicant referred by the Union(s), in accordance with the applicable Master Agreement.
(Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
14 7.6 Contractor(s)/Employer(s) shall have the unqualified right to select and hire directly all supervisors above the level of general foreman it considers necessary and desirable, without such persons being referred by the Union(s), unless such craft construction employee is covered by a Master Agreement.
7.7 I n the event that referral facilities maintained by the Union(s) are unable to fill the requisition of a Contractor/Employer for employees within a forty-eight (48) hour period (Saturdays, Sundays and Holidays excluded) after such requisition is made by the Contractor/Employer, the Contractor/Employer shall be free to obtain the worker(s) from any source. A Contractor/Employer who hires a worker(s) pursuant to this section shall immediately provide the appropriate Union with the name and address of such worker(s) and shall immediately direct such worker(s) to the appropriate Union hiring hall to be referred for work on a Covered Project.
ARTICLE VIII
WAGES AND BENEFITS
8.1 The Contractors/Employers agree to pay contributions to the vacation, pension and/or other deferred compensation plan, apprenticeship, worker protection and assistance, and health benefit funds established by the applicable Master Agreement(s) for each hour worked on the Covered Project, in the amounts designated in the applicable Master Agreement(s). The Master Agreements require such benefit contributions to be made on an hourly basis to such health benefit Trust Funds, each of which is separately administered by a Taft-Hartley Board of Trustees comprised of half labor and half management representatives and is administered via a Trust Agreement.
8.2 By signing this Agreement, the Contractors/Employers adopt and agree to be bound by the written terms of the legally established Trust Agreements described in Section 8.1, which may from time to time be amended, specifying the detailed basis upon which payments are to be made into, and benefits paid out of, such Trust Funds. The Contractors/Employers authorize the parties to such local Trust Agreements to appoint trustees and successor trustees to administer the Trust Funds and hereby ratify and accept the trustees so appointed as if they were appointed by the Contractors/Employers. The Contractors/Employers agree to execute a separate subscription agreement(s) when such Trust Fund(s) requires such document(s).
8.3 Wages, Hours, Terms and Conditions of Employment: The wages, hours and other terms and conditions of employment on the Covered Project shall be governed by the Master Agreement of the respective craft, to the extent such Master Agreement is not inconsistent with this Agreement. Where a subject is covered by the Master Agreement and not covered by this Agreement, the Master Agreement will prevail. When a subject is covered by both the Master Agreement and this Agreement, to the extent there is any inconsistency, this Agreement will prevail.
8.4 Holidays: Holidays shal l be as set forth in the applicable Master Agreement. (Addendum No. 3 , July 11, 2024)
Project Labor Agreement
for the City of Vallejo
15 ARTICLE IX
LOCAL HIRE, APPRENTICES, AND WORKFORCE DEVELOPMENT
9.1 Local Hire: It is in the interest of the parties to this Agreement to facilitate employment of City of Vallejo residents and to develop increased numbers of local skilled construction workers to meet the requirements of the regional construction economy. For purposes of this Article, the “Local Area” is defined as the City of Vallejo. It is the objective of the parties that not less than thirty percent (30%) of the combined journey-level and apprentice hours worked on the Project will be worked by residents of the Local Area. The Unions agree that residents of the Local Area shall be first referred for Project Work, including journey-level workers and apprentices covered by this Agreement. While the objective is to utilize as many workers from the Local Area as possible, the parties recognize that it may not always be possible. So, the parties agree that recruitment of workers shall be in the following priority:
Prio
rity 1: Residents of the City of Vallejo.
Priority 2: Residents of Solano County outside of the City of Vallejo.
Priority 3: Residents of the Counties of Napa, Contra Costa, Alameda, Marin, Sonoma, San Mateo, and San Francisco.
Priority 4: All other areas.
The Contractors shall provide monthly reports to the parties. The workforce reports shall include information regarding the number of: (i) journey-level workers broken down by Priority number; (ii) Apprentices broken down by Priority number. The Contractors and the Unions agree to furnish all information required to prepare these reports. The reports shall be made available to the Unions by the Contractors within ten (10) days of receiving a request.
9.2 Recognizing the need to develop adequate numbers of competent workers in the construction industry, including on public works projects, the Contractors/Employers shall employ apprentices from a California state-approved Joint Apprenticeship Training Program in their respective crafts, to perform such work as is within their capabilities and that is customarily performed by the craft in which they are indentured.
9.3 A
pprentice ratios will be in compliance with the provisions of the California Labor Code and the applicable state prevailing wage determination.
9.4 Consistent with the Master Agreements, there shall be no restriction on the utilization of apprentices in performing the work of their craft provided they are properly indentured and supervised. The Unions will exert their best effort to recruit and identify residents in the Local Area and assist individuals in qualifying and becoming eligible for such apprenticeship programs.
9.5 When Local Residents are requested by the Contractor/Employers, the Unions will grant priority referral to such workers. In the event that a Contractor/Employer, having not achieved its targeted hiring participation levels, requests a Local Resident from the Union hiring facility, and is referred a worker who is not a Local Resident the Contractor/Employer is under no obligation to hire the referred worker for the C ove r ed Project work and shall notify (Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
16 t
he Union hiring facility and the Jobs Coordinator and shall request another referral of another Local Resident. The Contractor/Employer shall not be required to hire that worker unless there is no Local Resident available for hire.
9.6 The Contractor/Employers agree to maintain copies of all written dispatch requests for the Project submitted or received including transmission verification reports that are date/time imprinted. All written dispatch requests and transmission verification reports shall be available for inspection and copies provided, upon request by the City representative.
9.7 Workforce Development: The Parties recognize the need to maintain continuing support of the programs designed to develop adequate numbers of competent workers in the construction industry, the obligation to capitalize on the availability of the City's local work force, and the opportunities to provide continuing work for C ov e r e d Projects covered by this Agreement. To these ends, the Parties shall facilitate, encourage, and assist Local Residents to commence and progress in Labor/Management apprenticeship programs in the construction industry leading to participation in such apprenticeship programs.
9.7.1 The City and the Trades Council shall continue to work cooperatively with the pre-apprenticeship programs established to serve the Vallejo community, namely the pre-apprenticeship course at Vallejo High School, the North Bay Trades Introduction Program, and the adult education courses operating at Vallejo Adult School and Benicia Adult School.
9.7.2 The City and Trades Council shall also work cooperatively with the Solano County Workforce Development Board, the Construction Trades Workforce Initiative, other non-profit entities and organizations, and the Unions, to identify, establish and maintain effective programs and procedures for Local Residents interested in entering the construction industry and which will help prepare them for the formal joint Labor/Management apprenticeship programs.
9.7.3 The Trades Council shall also conduct outreach activities, including, but not limited to, career fairs, classroom visits, and tours for high school students of apprenticeship programs, to identify Local Residents interested in entering the construction industry and facilitate their entry into a local pre-apprenticeship program or a joint Labor/Management apprenticeship program.
9.8 The Unions shall collect and compile a list of all apprentices, and their residency information, who have worked on Covered Projects and submit an apprenticeship report to the City on a quarterly basis.
(Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
17 ARTICLE X
HELMETS TO HARDHATS
10.1 The Contractor s/Employers and Unions recognize a desire to facilitate the entry into the building and construction trades of veterans who are interested in careers in the building and construction industry. The Contractors/Employers and Unions agree to utilize the services of the organization known as the Center for Military Recruitment, Assessment and Veterans Employment (hereinafter “Center”) and the Center’s “Helmets to Hardhats” program to serve as a resource for preliminary orientation, assessment of construction aptitude, referral to apprenticeship programs or hiring halls, counseling and mentoring, support network, employment opportunities and other needs as identified by the parties.
10.2 The Unions and Contractors/Employers agree to coordinate with the Center to participate in an integrated database of veterans interested in working on Covered Projects and of apprenticeship and employment opportunities for Covered Projects. To the extent permitted by law, the Unions will give credit to such veterans for bona fide, provable past experience.
ARTICLE XI
COMPLIANCE
11.1 I t shall be the responsibility of the Contractors/Employers and Unions to investigate and monitor compliance with the provisions of Article VIII of this Agreement.
Nothing in this Agreement shall be construed to interfere with or supersede the usual and customary legal remedies available to the Unions and/or employee benefit Trust Funds to collect delinquent wages or Trust Fund contributions from Contractors/Employers on a Covered Project.
ARTICLE XII
GRIEVANCE ARBITRATION PROCEDURE
12.1 Pr oject Labor Disputes: All disputes involvi ng the application or interpretation of a Master Agreement to which a Contractor/Employer and a Union are parties shall be resolved pursuant to the resolution procedures of the Master Agreement. All disputes relating to the interpretation or application of this Agreement, other than disputes under Article IV and Article XIII, shall be subject to resolution by the grievance arbitration procedures set forth in this Article.
12.2 Employee Discipline: All disputes involving the discipline and/or discharge of an employee working on a Covered Project shall be resolved through the grievance and arbitration provisions contained in the Master Agreement for the craft of the affected employee. No employee working on a Covered Project shall be disciplined or discharged without just cause.
12.3 No grievance shall be recognized unless the grieving party (Union or Trades Council on its own behalf, or on behalf of an employee whom it represents, or a Contractor/Employer on its own behalf) provides notice in writing to the party with whom it has a dispute within five (5) business days after becoming aware of the dispute but in no event more (Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
18 t
han thirty (30) business days after it reasonably should have become aware of the event giving rise to the dispute. Time limits may be extended by mutual agreement of the parties.
12.4 Grievances shall be settled according to the following procedures:
Step 1: Within five (5) business days after the receipt of the written notice of the grievance, the representative of the involved Union or Trades Council, or his/her designee, and the representative of the involved Contractor/Employer, shall confer and attempt to resolve the grievance.
Step 2: If the grievance is not resolved at Step 1, within five (5) business days of the Step 1 meeting or the conclusion of efforts to resolve the grievance at Step 1, the alleged grievance may be referred in writing by either involved party to the Business Manager(s) of the affected Union(s) involved and the Labor Relations Manager of the Contractor/Employer, or the Contractor/Employer’s designated representative, for discussion and resolution. This time limit may be extended by mutual consent of both parties. Regardless of which party has initiated the grievance, the Union shall notify its International Union representative prior to the Step 2 meeting, and the International Union representative shall advise if it intends to participate in the Step 2 meeting. The Project Manager and the Trades Council shall have the right to participate in any efforts to resolve the dispute at Step 2.
Step 3: If the grievance is not resolved at Step 2, either party may request the dispute be submitted to arbitration within five (5) business days of the Step 2 meeting or the conclusion of efforts to resolve the grievance at Step 2. This time limit may be extended by mutual consent of both parties. Within five (5) business days after referral of a dispute to arbitration, the representatives shall utilize the procedure for selecting an arbitrator designated in Article IV and notify the selected arbitrator for final and binding arbitration. The decision of the arbitrator shall be final and binding on all parties. The arbitrator shall have no authority to change, amend, add to or detract from any of the provisions of the Agreement. The expense of the arbitrator shall be borne equally by both parties. The arbitrator shall arrange for a hearing on the earliest available date from the date of his/her selection. A decision shall be given to the parties within five (5) calendar days after completion of the hearing unless such time is extended by mutual agreement. A written opinion may be requested by a party from the presiding arbitrator.
12.5 T
he time limits specified at any step of the grievance procedure may be extended by mutual agreement of the parties. However, failure to process a grievance, or failure to respond in writing within the time limits provided above, without an agreed upon extension of time, shall be deemed a waiver of such grievance without prejudice, or without precedent to the processing and/or resolution of like or similar grievances or disputes.
12.6 In order to encourage the resolution of disputes and grievances at Steps 1 and 2 of this grievance procedure, the parties agree that such settlements shall not be precedent setting. (Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
19 ARTICLE XIII
WORK ASSIGNMENTS AND JURISDICTIONAL DISPUTES
13.1 The assignment of Covered Work will be solely the responsibility of the Employer performing the work involved; and such work assignments will be in accordance with the Plan for the Settlement of the Jurisdictional Disputes in the Construction Industry (the “Plan”) or any successor Plan.
13.2 All jurisdictional disputes on Covered Projects between or among the building and construction trades Unions and the Employers parties to this Agreement, shall be settled and adjusted according to the present Plan established by the Building and Construction Trades Department or any other plan or method of procedure that may be adopted in the future by the Building and Construction Trades Department. Decisions rendered shall be final, binding and conclusive on the Employers and Unions that are parties to this Agreement.
13.3 I f a dispute arising under this Article involves the Northern California Carpenters Regional Council or any of its subordinate bodies, an arbitrator shall be chosen by the procedures specified in Article V, Section 5 of the Plan from a list composed of John Kagel, Thomas Angelo, Robert Hirsch and Thomas Pagan, and the arbitrator’s hearing on the dispute shall be held at the offices of the California State Building and Construction Trades Council in Sacramento, California within fourteen (14) calendar days of the selection of the arbitrator. All other procedures shall be as specified in the Plan.
13.4 All jurisdictional disputes shall be resolved without the occurrence of any strike, work stoppage, or slow-down of any nature, and the Employer’s assignment shall be adhered to until the dispute is resolved. Individual employees violating this section shall be subject to immediate discharge.
13.5 The Trades Council and the General Contractor for a Covered Project will conduct a craft assignment pre-job conference with each Employer prior to commencing work.
The City will be advised in advance of all such conferences and may participate if they wish.
Craft assignment pre-job conferences for different Employers may be held together.
ARTICLE XIV
MANAGEMENT RIGHTS
14.1 Consistent with a ny Master Agreement, the Contractor(s)/Employer(s) shall retain full and exclusive authority for the management of their operations, including the right to direct their work force in their sole discretion. No rules, customs or practices shall be permitted or observed which limit or restrict production, or limit or restrict the working efforts of employees, except that all lawful manning provisions in the Master Agreement shall be recognized. For the avoidance of doubt, this provision shall not apply to the City.
ARTICLE XV
SAFETY AND DRUG AND ALCOHOL POLICY
(Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
20 15.1 The use, sal e, transfer, purchase and/or possession of a controlled substance, alcohol and/or firearms at any time during the work day is prohibited. Drug and alcohol testing shall be conducted in accordance with the substance abuse prevention policies set forth in the applicable Master Agreement.
15.2 I t shall be the responsibility of each Contractor/Employer to ensure safe working conditions and employee compliance with any safety rules contained herein or established by the City, the state and the Contractor/Employer. It is understood that the employees have an individual obligation to use diligent care to perform their work in a safe manner and to protect themselves and the property of the Contractor/Employer and the City.
15.3 The safety, security and visitor rules established by the Contractor/Employer and the City shall be reasonable, uniformly applicable, and posted in conspicuous places throughout the work site. An employee's failure to adher e to such rules may subject him or her to discipline, including discharge. Any discipline or discharge shall be subject to the procedures in the applicable Master Agreement. Notwithstanding the immediately preceding sentence, the City can ban anyone it so chooses from its property.
15.4 The Parties acknowledge that the City and the Contractor/Employer have a policy, which prohibits the use, sale, transfer, purchase and/or possession of an illegal controlled substance, alcohol and/or firearms while on the City's premises. Additionally, the City has a "drug fr ee" work place policy, which prohibits those working on the City's premises f rom being impaired by alcohol or any controlled substances in their system. Any discipline or discharge shall be subject to the procedures in the applicable Master Agreement. Nothi ng herein shall prevent the City from enforcing its policy and requiring the removal from the job site of any impaired employee.
ARTICLE XVI
SAVINGS CLAUSE
16.1 I f any article, provision, clause, sentence or word of this Agreement is determined to be illegal or void as being in contravention of any applicable law, by a court of competent jurisdiction, the remainder of the Agreement shall remain in full force and effect. The parties further agree that if any article, provision, clause, sentence or word of the Agreement is determined to be illegal or void, by a court of competent jurisdiction, the parties shall substitute, by mutual agreement, in its place and stead, an article, provision, clause, sentence or word that will meet the objections to its validity and will be in accordance with its original intent.
16.2 I n the event a decision of a court of competent jurisdiction materially alters the terms of this Agreement such that the intent of the parties is defeated, then the entire Agreement shall be null and void.
16.3 I f a court of competent jurisdiction determines that all or part of the Agreement is invalid and/or enjoins the City from complying with all or part of the Agreement’s provisions, and the City accordingly determines that compliance with this Agreement will not be required in (Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
21 order to perform work under a Construction Contract, the Unions will no longer be bound by the provisions of Article IV.
ARTICLE XVII
TERM
17.1 This Agreement shall be included in all bid documents, requests for proposals, or other equivalent Covered Project solicitations during the term of this Agreement, which shall indicate that entering into this Agreement is a condition of the award of a Construction Contract(s) for the Covered Project.
17.2 This Agr eement shall apply until the Completion of each Covered Project in accordance with Sections 1.6 and 2.2.
17.3 This Agreement shall become effective upon approval by the City Council and final execution by the City and the Trades Council. Prior to each five (5) year anniversary of the effective date of this Agreement, the City and the Trades Council shall meet to discuss proposed changes, if any, to the Agreement. No less than six months before the five-year anniversary of this Agreement, either party may request from the other party that the Agreement be extended with or without revisions. The parties may mutually agree in writing to an extension or amendment of this Agreement.
17.4 Any Covered Project awarded during the term of this Agreement shall continue to be covered hereunder, until completion of the Covered Project, notwithstanding the expiration date of this Agreement.
ARTICLE XVIII
MISCELLANEOUS PROVISIONS
18.1 The section headings contained in this Agreement are inserted for convenience only and shall not affect in any way the meaning or interpretation of this Agreement. All defined terms used in this Agreement shall be deemed to refer to the singular and/or plural, in each instance as the context and/or particular facts may require.
18.2 This Agreement may be executed in counterparts, such that original signatures may appear on separate pages and when bound together all necessary signatures shall constitute an original. Faxed or emailed signature pages transmitted to other parties to this Agreement shall be deemed the equivalent of original signatures.
18.3 Each of the persons signing this Agreement represents and warrants that such person has been duly authorized to sign this Agreement on behalf of the party indicated, and each of the parties signing this Agreement warrants and represents that such party is legally authorized and entitled to enter into this Agreement.
18.4 The parties acknowledge that this is a negotiated agreement, that they have had the opportunity to have this Agreement reviewed by their respective legal counsel, and that the (Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
22 te
rms and conditions of this Agreement are not to be construed against any party on the basis of such party's draftsmanship thereof.
18.5 All defined terms used in this Agreement shall be deemed to refer to the singular and/or plural, in each instance as the context and/or particular facts may require.
18.6 In the event of any dispute, jurisdiction shall be in the Superior Courts of the State of California with venue in Solano County.
[
SIGNATURES TO FOLLOW]
(Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
23 CIT
Y OF VALLEJO
Date:
Andrew Murray, City Manager
Appr
oved as to Form
Date:
Veronica A.F. Nebb, City Attorney
NAPA
-SOLANO BUILDING AND
CONSTRUCTION TRADES COUNCIL
Date:
Danny Bernardini, Secretary-Treasurer
(Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
24 [
UNION SIGNATURES]
(Addendum No. 3, July 11, 2024)
Project Labor Agreement
for the City of Vallejo
25 A
ddendum 1
AGREEMENT TO BE BOUND
[Date]
[Addressee]
[Address]
Re: City of Vallejo Project Labor Agreement
Agreement to be Bound
Dear :
The undersigned confirms that it agrees to be a party to and bound by the City of Vallejo Project Labor Agreement (“Agreement”) as such Agreement may, from time to time, be amended by the parties or interpreted pursuant to its terms.
By executing this Agreement to be Bound, the undersigned subscribes to, adopts and agrees to be bound by the written terms of the legally established trust fund documents as set forth in Section
8.1 of the Agreement, as they may from time to time be amended, specifying the detailed basis upon which contributions are to be made into, and benefits made out of, such trust funds, and ratifies and accepts the trustees appointed by the parties to such trust funds. The undersigned agrees to execute a separate subscription agreement(s) for such trust funds when such trust fund(s) require(s) such document(s).
The obligation to be a party to and bound by the Agreement shall extend to all work covered by the City of Vallejo Project Labor Agreement undertaken by the undersigned. The undersigned shall require all of its subcontractors, of whatever tier, to become similarly bound for all their work within the scope of the Agreement by signing an identical Agreement to be Bound.
This letter shall constitute a subscription agreement, to the extent of the terms of the letter.
C
ONTRACTOR/SUBCONTRACTOR:
California Contractor State License No. or Motor Carrier (CA) Permit No.:
Name of Authorized Person (print):
Signature of Authorized Person:
Title of Authorized Person:
Telephone Number of Authorized Person:
Address of Authorized Person:
State Public Works Registration Number:
156657\1448596