ACTION:
____________________________

Clerk/Secretary
Department: Engineering Item No: C6
Prepared by:

Erin Adams, Administrative Programs Manager
Jason Rivera, Capital Projects Manager Meeting Date: May 27, 2025 Approved by:

Greg Mayer, Department Director
John Conley, City Manager Agenda Location: Consent Calendar S
UBJECT: CIP NO. 8360 – N. SANTA FE AVE CORRIDOR LANDSCAPE AND IRRIGATION PROJECT – AWARD OF CONTRACT
RE
COMMENDATION: Adopt City Council Resolution No. 2025- , awarding a contract to Kimley-Horn and Associates, Inc. for professional services for the N. Santa Fe Ave Corridor Landscape and Irrigation Project with New Pedestrian Crossing at Washington Street (CIP No. 8360).

CO
RRELATION TO CITY COUNCIL GOALS: Climate and Environmental Responsibility, and Traffic: Continue to enhance mobility safety, improve the flow of traffic for all forms of travel, reduce congestion, and improve our roads and sidewalks.

P
RIOR ACTION: On June 11, 2024, adopted City Council Resolution No. 2024-86, adopting a Capital Project Budget for Fiscal Years 2024/25 and 2025/26 (Vote: 5-0).

S
TATEMENT ON THE SUBJECT: The purpose of Capital Improvement Project (CIP) No. 8360, N. Santa Fe Complete Streets, is to provide environmental and pedestrian improvements to the area. The City of Vista received a grant through the USDA, Forest Service Region 5, to plant 125 trees and install irrigation.

The project further includes a new signalized pedestrian crossing on N. Santa Fe Avenue at Washington Street to improve pedestrian flow and safety from the Vista Transit Center to the adjacent housing and businesses.

O
n February 21, 2025, staff issued a Request for Proposals (RFP) for professional design services for the N. S
anta Fe Ave Corridor Landscape and Irrigation Project with New Pedestrian Crossing at Washington S
treet (CIP No. 8360). The RFP was advertised on the City’s website and the City’s electronic procurement portal, OpenGov.

The f
ollowing five firms responded to the RFP:

Fi rm Office Location
D okken Engineering San Diego, CA
Kimley-Horn & Associates, Inc. San Diego, CA
Nasland Engineering San Diego, CA
Quality Infrastructure Corporation La Mesa, CA
SWS Engineering, Inc. San Marcos, CA
AGENDA
REPORT

CITY COUNCIL

COMMUNITY DEVELOPMENT COMMISSION

SUCCESSOR AGENCY

BUENA SANITATION DISTRICT

JOINT POWERS FINANCING AUTHORITY
05/27/2025
C6

Page 1 of 194 ends

MEETING DATE: May 27, 2025 PAGE 2
SUBJECT: CIP NO. 8360 – N. SANTA FE AVE CORRIDOR LANDSCAPE AND IRRIGATION PROJECT – AWARD OF CONTRACT
Staff reviewed the proposals based upon predetermined criteria identified in the RFP, including experience with similar projects, understanding of project objectives and requirements, and quality of work. Staff then reviewed the schedule of rates and determined both to be fair and equitable with respect to expertise and geographic region. Staff recommend awarding the contract for professional services for the N. Santa Fe Ave Corridor Landscape and Irrigation Project with New Pedestrian Crossing at Washington Street (CIP No. 8360) to Kimley-Horn & Associates, Inc.

F
ISCAL IMPACT: The contract has a ceiling of $219,980 over a seven-month term with an option to extend it up to an additional three months. Sufficient funding is budgeted and available in the Fiscal Years 2024/25 and 2025/26 Capital Improvement Budgets in CIP No. 8360, Source Appropriation Account (No. 1176209.578999.8360).

EXHIBITS:

1. City Council Resolution 2025- , awarding contract to Kimley-Horn and Associates, Inc. for professional services for the N. Santa Fe Ave Corridor Landscape and Irrigation Project with New Pedestrian Crossing at Washington Street (CIP No. 8360)

2. Contract with Kimley-Horn & Associates, Inc.
05/27/2025
C6

Page 2 of 194 ends

00029213 7
RESOLUTION NO. 2025-

A RESOLUTION OF THE CITY COUNCIL OF THE CHARTERED CITY OF

VISTA, CALIFORNIA, AWARDING A CONTRACT TO KIMLEY-HORN & ASSOCIATES, INC. FOR PROFESSIONAL SERVICES FOR THE N. SANTA

FE AVE CORRIDOR LANDSCAPE AND IRRIGATION PROJECT WITH NEW PEDESTRIAN CROSSING AT WASHINGTON STREET (CIP NO. 8360) The City Council of the City of Vista does resolve as follows:

1. Findings. The City Council hereby finds and declares the following:

A. Pursuant to section 3.08.060B of the Vista Municipal Code, a request for proposals (RFP) was issued on February 21, 2025.

B. Five proposals were submitted in response to the RFP and were evaluated based upon the predetermined set of criteria identified in the RFP.

C. Staff recommends the selection of Kimley-Horn & Associates, Inc. as the consultant to provide professional services for the N. Santa Fe Ave Corridor Landscape and Irrigation Project with New Pedestrian Crossing at Washington Street (CIP No. 8360).

2. Action.

A. The contract between the City of Vista and Kimely-Horn & Associates, Inc. for professional services for the N. Santa Fe Ave Corridor Landscape and Irrigation Project with New Pedestrian Crossing at Washington Street is approved and the Mayor is authorized to execute the contract.

3. Adoption. PASSED AND ADOPTED at a meeting of the City Council of the City of Vista held on May 27, 2025, by the following vote:

AYES:

NOES:

ABSTAIN:

APPROVED AS TO FORM:

WALTER CHUNG, CITY ATTORNEY
By:

APPROVED
Walter C. Chung
20250519073013
JOHN B. FRANKLIN, MAYOR
ATTEST:

KATHY VALDEZ, CITY CLERK
By:
05/27/2025
C6

Page 3 of 194 ends

EXHIBIT 1
Professional Services (Non-Construction) (RFP)(NPW) 1 of 9 KIMLEY-HORN AND ASSOCIATES, INC. [51960-2] 00051960 44911-4088-0703, v. 2

CONTRACT FOR PROFESSIONAL SERVICES
N. SANTA FE AVE CORRIDOR LANDSCAPE AND IRRIGATION PROJECT WITH NEW PEDESTRIAN CROSSING AT WASHINGTON STREET (CIP NO. 8360)
THIS “CONTRACT” is entered into by and between the “Parties” as of ___________________ (“Contract Date”).

1.0 THE “PARTIES”
The “City”:

CITY OF VISTA, a chartered municipal
corporation
200 Civic Center Drive
Vista, CA 92084
Working Contact: Jason Rivera
Billing Contact: Erin Adams
The “Contractor”
KIMLEY-HORN AND ASSOCIATES, INC., a
North Carolina corporation
401 B Street, Suite 600
San Diego, CA 92101
Contact: Mark Araujo

2.0 BASIC TERMS

2.1 The “Services” to be performed by Contractor are set forth in Exhibit B.

2.2 The “Required License” for the Services is: California Professional Civil Engineer’s License.

2.3 Contractor, an entity holding the Required License, desires to enter into this “Contract” with City for the Services.

2.4 The “Project” for which the Services are required is described in Exhibit A.

2.5 Contractor has submitted to City a Proposal to perform the Services dated March 21, 2024 (“Exhibit B”).

2.6 The “Contract Ceiling Price” is: $219,980.

2.7 Any references in Exhibit A or Exhibit B to “Consultant” shall mean Contractor for the purposes of this Contract.

3.0 CONTRACT TERM

3.1 This Contract shall take effect as of the Contract Date.

3.2 This Contract shall be in effect for 7 calendar months (“Term”) from the Contract Date. The Term may be extended at the City’s option for an additional 3 months, in increments of City’s choice, for a maximum Term of 10 months from the Contract Date.

3.3 City may terminate this Contract upon 30-days’ written notice to Contractor. In such event, or upon request of City, Contractor shall assemble all City documents in the Contractor's possession, put them in order for proper filing and closing, and deliver the documents to City. In the event of termination, Contractor shall be paid for work performed to 05/27/2025
C6

Page 4 of 194 ends

EXHIBIT 2

Professional Services (Non-Construction) (RFP)(NPW) 2 of 9 KIMLEY-HORN AND ASSOCIATES, INC. [51960-2] 00051960 44911-4088-0703, v. 2
the termination date. City shall make the final determination as to the portion of tasks completed and the compensation to be paid.

4.0 SCOPE
Contractor shall perform all Services including, but not limited to, the furnishing of all tools, equipment, materials, software, and supplies, and for furnishing all transportation, services, including fuel, power and water, essential communications, and the performance of all labor, work, or other operations, as may be required from time to time, in accordance with Exhibit A and Exhibit B. In the event of a conflict between the provisions of Exhibit A and Exhibit B, the provisions of Exhibit B shall control.

5.0 COMPENSATION

5.1 City shall pay Contractor for the Services to be performed as set forth in Exhibit B.

5.2 An invoice for payment shall be submitted in a form satisfactory to City. At a minimum, the invoice shall include: the purchase order number, the work order number, a description of the work performed, and a total amount.

5.3 Changes in, additions to, or deductions from the Services, including increases or decreases in any item or portion of the Services, shall be set forth in a written change order executed by City and by the Contractor which shall specify:

5.3.1 The changes, additions, and deductions to be made.

5.3.2 The increase or decrease in compensation due the Contractor, if any.

5.3.3 Adjustment in the time of completion, if any.

5.4 Contract Ceiling Price

5.4.1 In no event shall City be liable for paying more than the Contract Ceiling Price for Contractor's services rendered under this contract.

5.4.2 If it becomes foreseeable that Contractor will need to perform services such that the cumulative total of costs to City will exceed the maximum permitted by this Contract, any such cost overrun will be handled pursuant to the change order procedure in Vista Municipal Code Chapter 3.08. City and Contractor recognize that City lacks authority to exceed the cost ceiling without the express authorization of the City Council. If the maximum cost to City for this Contract is exceeded unexpectedly, payment shall be made as mutually agreeable and disputes shall be handled pursuant to this Contract, but work shall cease as soon as is reasonably feasible once the cost ceiling plus allowable change orders, if any, is exceeded.

5.5 Except as provided in Exhibit B, Contractor shall not be reimbursed for any expenses incurred in rendering services under this Contract. 05/27/2025
C6

Page 5 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 3 of 9 KIMLEY-HORN AND ASSOCIATES, INC. [51960-2] 00051960 44911-4088-0703, v. 2

6.0 CONTRACT DOCUMENTS
The Contract comprises the following documents including all additions, deletions, modifications, and appendices and all addenda setting forth any modifications or interpretations of any these documents: Documents required under Exhibits A–E.

7.0 TIME FOR COMPLETION AND COMMENCEMENT OF SERVICES
All Services under the Contract must be completed in compliance with the schedule in Exhibit B.

8.0 STANDARD OF PERFORMANCE

8.1 Contractor represents and warrants that it has the training, qualifications, experience, and facilities necessary to properly perform the Services required under this Contract in a thorough, competent, and professional manner. At all times Contractor shall faithfully, competently and to the best of its ability, experience, and talent, perform all services described herein. In meeting its obligations under this Contract, Contractor shall employ, at a minimum, generally accepted standards and practices utilized by persons engaged in providing services similar to those required of Contractor under this Contract.

8.2 Contractor shall keep itself informed of and comply with all applicable federal, state, and local laws, statutes, codes, ordinances, regulations, and rules in effect during the Term of this Contract. Contractor shall obtain any and all licenses, permits and authorizations necessary to perform the services set forth in this Contract, including any business licenses required by City. Neither City, nor any elected or appointed boards, officers, officials, employees, or agents of City, shall be liable, at law or in equity, as a result of any failure of Contractor to comply with this Section.

9.0 CONTRACTOR’S STATUS; CONTRACTOR’S EMPLOYEES

9.1 Contractor shall perform the services provided for herein in Contractor's own way as an independent contractor and in pursuit of Contractor's independent calling. Contractor is not to be considered an employee of City, nor shall any employees of Contractor be considered employees of City, for any purpose. Contractor shall be under the direction and control of City staff only as to the results to be accomplished. This Contract is not intended to create the relationship of partnership, joint venture, or association between City and Contractor.

9.2 Contractor represents and warrants that all professional services required under this Contract shall be provided by a person or persons duly licensed by the State of California to provide those types of services.

9.3 Neither Contractor, nor any of Contractor's officers, employees, or agents, shall obtain any rights to retirement, health care or any other benefits which may otherwise accrue to City’s employees. Contractor expressly waives any claim Contractor may have to any such rights.

9.4 Contractor is aware of the requirements of the Immigration Reform and Control Act of 1986 and shall comply with those requirements, including, but not limited to, verifying the eligibility for employment of all of Contractor’s officers, employees, agents, and subcontractors that are included in this Contract.

05/27/2025
C6

Page 6 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 4 of 9 KIMLEY-HORN AND ASSOCIATES, INC. [51960-2] 00051960 44911-4088-0703, v. 2

9.5 The payment made to Contractor pursuant to this Contract shall be the full and complete compensation to which Contractor and Contractor’s officers, employees, agents, and subcontractors are entitled for performance of any work under this contract. Neither Contractor nor Contractor’s officers or employees are entitled to any salary or wages, or retirement, health, leave or other fringe benefits applicable to employees of the City. City will not make any federal or state tax withholdings on behalf of Contractor. City shall not be required to pay any workers' compensation insurance on behalf of Contractor.

9.6 Contractor agrees to defend and indemnify City for any obligation, claim, suit, or demand for tax, retirement contribution including any contribution to the Public Employees Retirement System (PERS), social security, salary or wages, overtime payment, or workers' compensation payment which City may be required to make on behalf of Contractor or any employee of Contractor, or any employee of Contractor construed to be an employee of City, for work done under this contract. This is a continuing obligation that survives the termination of this Contract.

10.0 CIVIL RIGHTS

10.1 Contractor agrees to comply with Title VII of the Civil Rights Act of 1964, as amended, the California Fair Employment Practices Act, the Americans with Disabilities Act of 1990, any other applicable federal and state laws and regulations hereinafter enacted.

10.2 Contractor shall not knowingly deny an opportunity or benefit, discriminate against or harass, any employee or applicant for employment on account of the person’s race, color, ethnicity, national origin, ancestry, religion, creed, veteran status, physical disability, mental disability, medical condition, marital status, sex, sexual orientation, age, or other status protected from workplace discrimination by state or federal law.

10.3 Contractor shall not knowingly give preferential treatment to any applicant for employment on the basis of race, color, ethnicity, national origin, ancestry, religion, creed, physical disability, mental disability, medical condition, marital status, sex, or sexual orientation.

10.4 This section shall be interpreted in a manner that is consistent with the California and United States Constitutions and applicable state and federal statutes governing workplace discrimination. The terms used in this section shall have the same meaning as defined in state statutes governing the same subject matter.

10.5 Nothing in this section shall be interpreted as prohibiting bona fide occupational qualifications consistent with applicable state and federal law and reasonably necessary to the normal operation of Contractor. Nothing in this section shall be interpreted as prohibiting regulations and policies to prevent nepotism or conflicts of interest.

10.6 Nothing in this Section shall be interpreted as prohibiting action taken to establish or maintain eligibility for any federal program, where ineligibility would result in a loss of federal funds to City.

10.7 To the fullest extent permitted by law and without limitation by the other provisions of this Contract relating to indemnification and insurance, Contractor shall also indemnify, defend, and hold harmless City, and its directors, officers, employees, and agents from and against all liability (including without limitation all claims, damages, penalties, fines, and judgments, associated investigation and administrative expenses, and defense costs, 05/27/2025
C6

Page 7 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 5 of 9 KIMLEY-HORN AND ASSOCIATES, INC. [51960-2] 00051960 44911-4088-0703, v. 2
including but not limited to reasonable attorneys' fees, court costs, and costs of alternative dispute resolution) resulting from any claim of discrimination or harassment, including but not limited to sexual harassment, arising from the conduct of the Contractor or any of the Contractor’s officers, employees, agents, licensees, or subcontractors. In the event of a discrimination or harassment complaint against any employee, agent, licensee, or subcontractors of Contractor or its subcontractors, Contractor shall take immediate and appropriate action in response to such complaint, including, but not limited to termination or appropriate discipline of any responsible employee, agent, licensee, or subcontractors. The provisions of this Section survive completion of the services or termination of the Contract.

11.0 CONTROL OF SERVICES
Each Party shall appoint a representative who shall have the authority to represent and act for that Party (“Representative”). Any written or verbal directions or requests of City's Representative delivered to the Contractor’s Representative shall have the same force and effect as if delivered to the Contractor. The Contractor's Representative shall have the authority to sign any change order, coordinate the work of all subcontractors and make other decisions pertaining to the Contract.

12.0 ASSIGNMENT AND SUBCONSULTING

12.1 Neither this Contract nor any interest herein may be transferred, assigned, conveyed, hypothecated, or encumbered voluntarily or by operation of law, whether for the benefit of creditors or otherwise, without the prior written approval of the City. Transfers restricted hereunder shall include the transfer to any person or group of persons acting in concert of more than twenty-five (25%) of the present ownership and/or control of Contractor, taking all transfers into account on a cumulative basis. In the event of any such unapproved transfer, including any bankruptcy proceeding, this Contract shall be void. No approved transfer shall release the Contractor or any surety of Contractor of any liability hereunder without the express consent of City.

12.2 Contractor shall be fully responsible to the City for any acts and omissions of Contractor's subcontractor, including persons either directly or indirectly employed by subcontractor, in the event Contractor subcontracts any of the work to be performed under this contract. Contractor's responsibility under this paragraph shall be identical to Contractor's liability for acts and omissions of Contractor and employees of the Contractor. Nothing contained in this Contract shall create any contractual relationship between City and any subcontractor of Contractor, but Contractor shall bind every subcontractor and every subcontractor of a subcontractor by the terms of this contract applicable to Contractor's work, unless such change, omission, or addition is approved in advance in writing by the City Manager or the City Manager’s designee. All subcontractors are subject to the prior written review and approval of the City Manager or the City Manager’s designee.

13.0 LICENSES
If a license of any kind, which term is intended to include evidence of registration, is required of Contractor, its employees, agents, or subcontractors by federal, state, or local law, Contractor warrants that such license has been obtained, is valid and in good standing, and that any required bond has been posted in accordance with all applicable laws and regulations. 05/27/2025
C6

Page 8 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 6 of 9 KIMLEY-HORN AND ASSOCIATES, INC. [51960-2] 00051960 44911-4088-0703, v. 2

14.0 FINANCIAL RECORDS

14.1 Contractor shall maintain any and all documents, ledgers, books of account, invoices, vouchers, canceled checks, or records demonstrating or relating to Contractor’s performance of services pursuant to this Contract or evidencing or relating to expenditures and disbursements charged to City pursuant to this Contract. Any and all such documents or records shall be maintained in accordance with generally accepted accounting principles and shall be sufficiently complete and detailed so as to permit an accurate evaluation of the services provided by Contractor pursuant to this Contract. Any and all such documents or records shall be maintained for three years from the date of execution of this Contract and to the extent required by laws relating to audits of public agencies and their expenditures. It is expressly understood and agreed that the provisions of this Section will survive termination of this Contract.

14.2 Any and all records or documents required to be maintained pursuant to this Section shall be made available for inspection, audit and copying, at any time during regular business hours, upon request by City or its designated representative. Copies of such documents or records shall be provided directly to the City for inspection, audit and copying when it is practical to do so; otherwise, unless an alternative is mutually agreed upon, such documents and records shall be made available at Contractor's address indicated for receipt of notices in this Contract or the primary location from which services are rendered, whichever is closer.

15.0 OWNERSHIP OF DOCUMENTS
Upon delivery, the work product, including without limitation, all original reports, writings, recordings, drawings, files, and detailed calculations developed under this contract are the property of City. Contractor agrees that all copyrights which arise from creation of the work pursuant to this contract shall be vested in City and waives and relinquishes all claims to copyright or other intellectual property rights in favor of City. City acknowledges that its use of the work product is limited to the purposes contemplated by the scope of Services and that Contractor makes no representation of the suitability of the work product for use in or application to circumstances not contemplated by the scope of Services.

16.0 CONFIDENTIALITY

16.1 Contractor shall treat all information obtained from City in the performance of this Contract as confidential and proprietary to City. Contractor shall treat all records and work product prepared or maintained by Contractor in the performance of this Contract as confidential.

16.2 Contractor agrees that it will not use any information obtained as a consequence of the performance of work for any purpose other than fulfillment of Contractor’s scope of Services. Contractor will not disclose any information prepared for City, or obtained from City or obtained as a consequence of the performance of work to any person other than City, or its own employees, agents or subcontractors who have a need for the information for the performance of Services under this Contract unless such disclosure is specifically authorized in writing by City.

16.3 Contractor’s obligations under this paragraph shall survive the termination of this Contract.
05/27/2025
C6

Page 9 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 7 of 9 KIMLEY-HORN AND ASSOCIATES, INC. [51960-2] 00051960 44911-4088-0703, v. 2

17.0 CONFLICT OF INTEREST REQUIREMENT
Contractor agrees that, to the extent applicable, it shall comply with and be bound by all laws and regulations deriving from the relationship of the Contractor to the City, including the Political Reform Act (Government Codes Section 87100 et seq.) Chapters 2.32 or 2.33 of the Vista Municipal Code, the Community Redevelopment Act (Health & Safety Code 33000 et seq.) and all regulations promulgated thereunder (collectively “Conflict Laws”). As a condition precedent to the formation of this Contract, Contractor warrants and covenants that it is adequately informed regarding the obligations and duties imposed by the Conflict Laws and that to the best of Contractor's knowledge and belief, there exists no conflict of interest (under the laws) that would disqualify the Contractor from participation in any decisions arising out of the performance of this Contract. Prior to commencement of any work in the performance of this Contract, Contractor shall comply with any applicable requirements of Chapter 2.32 of the Vista Municipal Code, including any requirement to file a financial disclosure statement with the City Clerk.

Contractor further agrees that no employee, agent or subcontractor for Contractor shall perform any work for the City pursuant to this Contract which will violate the Conflict Laws.

18.0 PROHIBITION OF FINANCIAL INTEREST BY CITY OFFICIAL Contractor warrants and covenants to City that no City Official has or will have any current or future financial interest in this Contract as of the date approved, nor shall Contractor promise, offer, or enter into any written, oral or implied Contract, to provide any financial interest or remuneration of any kind or manner to any City official with respect to this Contract. For purposes of this Section, the term “City Official” shall mean and include any elected or appointed officer of City, any employee of City, or any spouse or financial dependent of a City official or employee. A violation of this provision shall render this Contract null and void and Contractor shall be subject to restitution of all fees or money paid or earned under this Contract.

19.0 DUTY OF INDEMNIFICATION

19.1 To the fullest extent permitted by law, Contractor shall (1) immediately defend and (2) indemnify City, and its directors, officers, and employees from and against all liabilities regardless of nature or type that arise out of, pertain to, or relate to the negligence, recklessness, or willful misconduct of Contractor, or its employees, agents, or subcontractors.

Liabilities subject to the duties to defend and indemnify include, without limitation, all claims, losses, damages, penalties, fines, and judgments; associated investigation and administrative expenses; defense costs, including but not limited to reasonable attorneys’ fees; court costs; and costs of alternative dispute resolution (“Duty of Indemnification”). Contractor’s obligations to both defend and indemnify apply unless it is finally adjudicated that the liability or liabilities, in whole or in part, do not arise out of, pertain to, or relate to the negligence, recklessness, or willful misconduct of Contractor or its employees, agents, or subcontractors. Defense counsel shall be approved by City.

19.2 The review, acceptance or approval of Contractor’s work or work product by any indemnified party shall not affect, relieve, or reduce Contractor’s indemnification or defense obligations. This Section survives completion of the services or the termination of this contract.

The provisions of this Section are not limited by and do not affect the provisions of this contract relating to insurance.

19.3 Contractor’s costs of defense shall not exceed Contractor’s proportionate percentage of fault as adjudicated by a court of law, as required by California Civil Code section 2782.8.
05/27/2025
C6

Page 10 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 8 of 9 KIMLEY-HORN AND ASSOCIATES, INC. [51960-2] 00051960 44911-4088-0703, v. 2

20.0 INSURANCE AND BONDS
Contractor shall comply with the insurance provisions set forth in Exhibit C.

21.0 SERVICE OF NOTICE

21.1 Any notice, which either Party may desire to give to the other Party, must be in writing and may be given by personal delivery to the Party’s Representative or by overnight courier service to the Party’s address set forth in Section 1.0. Notice may also be given by mailing it by registered or certified mail, return receipt requested, to the other Party at the address set forth in Section 1.0. Any notice given by mail will be deemed given 48 hours after such notice is deposited in the United States mail, addressed as provided with postage fully prepaid.

21.2 A Party may change its address by giving notice as provided above, and the changed address shall thereafter be deemed to be the address set forth in Section 1.0.

22.0 SPECIAL PROVISIONS
This Contract is subject to, and Contractor shall comply with, the special provisions referenced in Exhibit E, if any.

23.0 EXHIBITS
All documents referenced as exhibits in this Contract, or referenced in an exhibit to this Contract, are incorporated herein.

24.0 APPLICABLE LAW, VENUE
This Contract shall be construed and enforced under the laws of the State of California. If any action is commenced by any Party to this Contract, such action shall be filed in a court of competent jurisdiction within the County of San Diego, California.

25.0 COUNTERPARTS; ELECTRONIC SIGNATURES; ELECTRONIC DELIVERY This Agreement may be executed in separate counterparts, none of which need contain the signatures of both Parties, and each of which, when so executed, shall be deemed an original and all together shall constitute and be one of the same instrument. The Parties agree that this Agreement, whether executed by electronic signature, digital signature, or constituting a scanned or electronically reproduced copy or image of this Agreement bearing the signatures of the Parties, will be deemed an original and will represent competent evidence of the execution, terms and existence of this Agreement notwithstanding the failure or inability to produce an original executed Agreement or counterpart thereof, and without the requirement that the unavailability of such original executed Agreement or counterpart thereof first be proven.

Further, the exchange of this entire executed Agreement (and/or such exhibit(s) or document(s)) that is in photostatic or portable document format (.pdf) form by electronic mail or by another electronic means shall be considered original(s) and shall constitute effective execution and delivery of the original(s).

26.0 MODIFICATIONS
This Contract contains the entire agreement, between the Parties and supersedes all prior negotiations, discussions, obligations, and rights of the Parties in respect of each other regarding the subject matter of this Contract. There is no other written or oral understanding 05/27/2025
C6

Page 11 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 9 of 9 KIMLEY-HORN AND ASSOCIATES, INC. [51960-2] 00051960 44911-4088-0703, v. 2
between the Parties. No modification, amendment or alteration of this Contract shall be valid unless it is in writing and signed by all Parties.

27.0 EXECUTION
IN WITNESS WHEREOF; the Parties hereto have executed this Contract as of the Contract Date.

“City”

CITY OF VISTA, a chartered municipal
corporation

By:

JOHN B. FRANKLIN, MAYOR

ATTEST:

KATHY VALDEZ, CITY CLERK

By:

APPROVED AS TO FORM:

WALTER CHUNG, CITY ATTORNEY

By:

RISK MANAGEMENT REVIEW:

ANALISA HOLBROOK, RISK MANAGER

By:

APPROVED
Amanda L. Guy
20250424141812

“Contractor”

KIMLEY-HORN & ASSOCIATES, INC., a
North Carolina corporation

By:

Name/Title

By:

Name/Title

05/27/2025
C6

Page 12 of 194 ends

00051960 4 Exhibit A
4911-4088-0703, v. 2

EXHIBIT A

REQUEST FOR PROPOSALS

05/27/2025
C6

Page 13 of 194 ends

REQUEST FOR PROPOSALS (RFP)

FOR PROFESSIONAL SERVICES

FOR

N. SANTA FE AVE CORRIDOR LANDSCAPE AND IRRIGATION PROJECT

WITH NEW PEDESTRIAN CROSSING AT WASHINGTON STREET
CIP No. 8360

Issue Date: February 21, 2025

Submittal Deadline: 4:00 PM, March 21, 2025

05/27/2025
C6

Page 14 of 194 ends

2 REQUEST FOR PROPOSALS
N. SANTA FE AVE CORRIDOR LANDSCAPE AND IRRIGATION PROJECT WITH NEW

PEDESTRIAN CROSSING AT WASHINGTON STREET
CIP No. 8360
I. INTRODUCTION
The City of Vista is requesting proposals fr om te ams composed of a qualified engineering firm (lead consultant) and landscape archit ectural firm (subconsultant) to provide profe
ssional services for design surveying, underground utility survey, engineering design, landscape
design, traffic signal design and construction support for the North Santa Fe Ave Lands
cape and Irrigation with New Pedestrian crossing at Washington Street project.

All interested
firms must have sufficient, readily available resources in the form of trained personnel, support services, specialized subconsultants, and financial re sources to carry out the work without delay or shortcomings.

All Consultants must create an account on th e City’s Electronic Bidding System, OpenGov Pro
curement to submit a proposal. Consultants can re gister using the ‘Sign Up’ link at the top of the page at:
https://procurement.opengov.com/portal/cityofvista
Once registered, Consultants must download th is solicitation in order to appear on the Bidder’s List as a “Prospective Bidder.” Consultants that fail to specifically download this solicita
tion will not appear on the Bidders’ Li st and will be unable to participate or be considered for this RFP. See further instru ctio ns related to OpenGov Procurement under Section VIII (Proposal), below.

Special Requirements
As required by Article 2 of Chap te r l of Part 7 of Division 2 o f the C alifornia Labor Code, the Consultant and all subconsultants shall pay not less than the prevailing rate of wages to all wo
rkmen employed in the exe cution of this Contra ct as ascertained and adopted by the State of California, Director of Industrial Relations pursuant to the Labor Code.

The Consultant and all subconsultants shall ha ve a City of Vista Business License prior to award of contract. Business licenses can be obtained at www.vistabl.com. A Cit y of Vista Business License is not required to propose on this request for proposals. 05/27/2025
C6

Page 15 of 194 ends

3 II. BACKGROUND AND PROJECT DESCRIPTION

The City of Vista has been awarded a grant from the USDA Forest Service to plant approximately 125 trees in the median and alon g both sides of a 1.3 mile stretch of N.

Santa Fe Avenue from Vista Village Drive to W. Bobier Drive. With City funding, the project will also design and install a new midblock pede strian crossing at E. Washington Street and N. Santa Fe Ave intersection to improve the pedestrian route to and from the Vista Transit Center. Given the scope of the project, this will require a very experienced and creative Engineering and Landscape Architectural team.

The USDA Forest Service grant objectives an d goals are to increase tree canopy cover, reduce urban heat islands, reduce runoff, incr ease air quality in lower income/underserved communities per grant narrative. The project wi ll remove, replace, expand and/or upgrade the existing irrigation systems to supply wate r for the existing and new trees and will make necessary modifications to the existing hardscape and irrigation to accommodate the project’s landscape improvements. The project proposes new trees along both sides of the street and the median. The design team will need to inventory and evaluate the N. Santa Fe Ave corridor to optimize the use of the new trees in combination with existing trees, landscaping and irrigation to meet and comply with grant objectives. The tree selection will utilize the resources provided by the US Forest Service and its partners along with input from City of Vista Public Works Landscape manager.

Historically, this section of N. Santa Fe Ave has always been a major route from the early 1900’s as a 2-lane road nestled in an agricult ural community to its current function as 4 lane divided arterial in the heart of an urbanized Vista. As the City of Vista developed from rural to urban, there have been many, unus ual and/or undocumented improvements with the underground facilities. For example, in the southbound direction starting from East Drive south to the Linda Rhoades Recreation Center across the street from Nevada Ave there was a large 6’ x 13’ concrete open channel that conveyed drainage for area along the west side of the original 2 lane road. When N. Santa Fe Ave was widened to a 4-lane divided arterial, the channel was capped with a reinforced concrete top which is inches below the current asphalt pavement and aligns directly under th e bike and outside lane of the southbound direction for approximately 0.4 miles. In addition to this storm drain the existing underground utilities throughout the entire corridor is very crowded with fiber optic, communication, streetlight, sewer, water, electrical utilities along with old errant utilities therefore, the irrigation alignment will be ch allenging and will require careful surveying, evaluation, potholing and design. Even the placement of each tree may be dictated or influenced by the congested underground alignments.

In addition, the City of Vista would like to in stall a new midblock pedestrian crossing at the end of the curb return north of E. Washington Street and N. Santa Fe Ave. intersection. This would provide a signalized crossing for pedestrians who hazardously cross the median at the left turn pocket in the northbound directio n where there is an opening in the median 05/27/2025
C6

Page 16 of 194 ends

4 fencing. The new pedestrian signal will provid e a safer crossing and improve the pedestrian route to/from the Vista Transit Center.

With crowded underground utilities along with a traffic signal design it was determined that a lead civil engineering firm partnered with a landscape architect subconsultant would provide the best solutions. Team members wo uld provide expertise in their perspective fields. The lead engineering firm can tackle the complexities of the utilities and traffic signal while the landscape architect can navigate the USDA Forest Service grant requirements and landscape design.

Reconstruction of the sidewalk, median, ir rigation, landscaping and pavement will be needed to accommodate the proposed improvements.

The following design objectives should be considered during the design development of the project:

1. Incorporate sustainable/practical land scape and irrigation design principles.

2. Maximize tree canopy improvements and integrate into existing street improvements.

3. Identify and evaluate potential util ity conflicts and avoid any costly utility relocation or modifications.

4. Minimize impacts to private property,

5. Maximize the preservation of mature landscaping and healthy tree specimens.

6. Incorporate sustainable design principl es and meet or exceed all stormwater regulations and requirements.

7. Minimize construction costs and long-term maintenance costs.

8. Ensure all USDA Forest Service gr ant requirements are met to maintain funding reimbursement. Provide a plan that is within the Forest Service Grant budget allowance, there are no additional funds.

9. Increase the pedestrian safety and mobility at the Washington Street mid block pedestrian crossing

10. Maximize the use of existing power and water source connections and minimize or eliminate the need for additional water/electric meters.

Attachment “A” contains exhibits showing the Grant Narrative for the landscape improvements and construction cost estimate. Also attached is the midblock pedestrian crossings on N. Santa Fe Ave recently constructed with the Townsite Complete Street Project. The engineer’s estimate of probable construction cost for landscape project is $1,358,370.00. The Construction estimate for th e traffic signal is $250,000. The total cost for construction is $1,608,370.00.

05/27/2025
C6

Page 17 of 194 ends

5 III. PROPOSED SCOPE OF SERVICES

A Scope of Work, included as Attachment “B”, details the tasks that the selected consultant will likely be required to perform to complete the project. The proposed scope and fees should be based on the tasks listed in the Scope of Work.

IV. CITY RESPONSIBILITIES

The following is a list of the City’s responsibilities during the term of the agreement:

1. Provide all available existing plans, studies, reports, aerial photos, available LIDAR topographic information, and other records.

2. Coordinate access to the site for Consultant review prior to submittal of proposal.

3. Process and respond to requests to the City.

4. Provide contact information for both internal staff and external stakeholders.

5. Coordinate, notice, and schedule all public meetings, and meetings with City’s boards, commissions, and City Council.

6. Prepare all administrative reports to the commissions and City Council.

7. Provide meeting site arrangements for public meetings and workshops.

8. Review submittals from the Consultant in a timely manner.

9. Distribute public information through newsletters, mailings, email blasts, City website, and printed flyers.

10. Submit CEQA Environmental documents to State Clearinghouse,

11. Prepare and execute agreements with other agencies or entities.

12. Obtain and pay for all permits, agreements, and permissions for contract work on property not owned or controlled by the City.

13. Provide templates and examples of WQTR’s, plans, and specifications to Consultant.

14. Provide utility company contact information for use in coordination.

15. Prepare all project specifications.

16. Advertise and award construction contracts.

17. Administer construction contract.

V. COORDINATION

Coordination with the City, other consultants and other involved agencies is required to achieve compatible designs, phasing of construction with existing or design conditions, and timely delivery of the contract services. Coordination may include, but not be limited to, coordination with Vista Unified School District, Vista Irrigation District, USDA Forest Service, San Diego Regional Water Quality Control Board, California Department of Fish and Wildlife, NCTD, San Diego Gas & Electric and other organizations.

The City will decide the manner in which the coordination of individual matters is undertaken. At the City’s option, coordination efforts may be performed by the Consultant’s direct contact, by the Consultant acting though the City or by the City only. When 05/27/2025
C6

Page 18 of 194 ends

6 coordination efforts require agreement, such an agreement shall be coordinated through the City.

VI. PROJECT PROGRESS

The Contract shall begin upon approval by the City, and the Consultant shall commence work after notification to proceed by the Cit y. Unless extended by contract amendment, the contract shall terminate upon acceptance by the City of the project as constructed and upon completion by the Consultant and approval of the City of the as-built plans.

The Consultant is advised that any recommendation for contract award is not binding on the City until the Agreement is fully executed and approved by the City.

Progress Review Meetings shall be held at inte rvals deemed appropriate by the City. At or before each of these meetings, the Consultant shall furnish two (2) copies of all completed or partially completed work products which have been developed or altered since the last Progress Review Meeting.

Progress Reports shall be submitted at monthly intervals, indicating progress achieved during the reporting period in relation to the progress scheduled. The Consultant shall provide the City with the Progress Report at le ast four (4) working days before the Monthly Progress Meeting.

VII. PROPOSAL

A. Schedule. The City’s schedule for the selection process is as follows:

1. City Releases RFP February 21, 2025

2. Deadline for Questions March 12, 2025, at 4:00 PM

3. Proposals Due March 21, 2025, at 4:00 PM

4. Notice of Consultant Shortlist April 3, 2025

5. Consultant Interview (If Needed) April 10, 2025

6. Notice of Consultant Selection April 14, 2025

7. Complete Negotiation of Agreement April 24, 2025

8. Council Award May 27, 2025

A Notice to Proceed for this project is tentatively scheduled to be issued in June 2025. Upon issuance of Notice to Proceed, the Consultant shall submit a detailed schedule for the project including milestones and progress reports.

All dates are subject to change, and the City re serves the right to extend the date by which proposals are due.

05/27/2025
C6

Page 19 of 194 ends

7 All questions must be submitted via “Q&A” th rough the City’s Electronic Bidding System, OpenGov Procurement. Phone call questions will not be accepted. Answers to all submitted questions will be provided in an addendum through OpenGov Procurement.

To receive addenda and submit a proposal, Consultants shall register on the City’s Electronic Bidding System at https://secure.procurenow.com/portal/cityofvista. Once registered, Consultants must do wnload the RFP while logged in under their own name and identification number to appear on the Electronic Prospective Bidders List as a “Prospective Bidder.” Consultants that fail to download the RFP will not appear on the Electronic Prospective Bidders List and their proposals will be considered non-responsive. If a C o n s u l t a n t i s u n a b l e t o r e g i s t e r o r d o w nload the RFP from OpenGov Procurement, a Consultant representative may contact OpenGov Procurement to troubleshoot the problem.

All proposal documents and supplementary do cuments must be uploaded using OpenGov Procurement prior to event date and time as inst ructed in this solicitation. Once file(s) have been uploaded and the Submission Status shows as “Submitted” the submission is complete. At that point respondents will re ceive an email confirmation from OpenGov Procurement.

OpenGov Procurement will determine the official time for the advertised proposal due date and such determination will be final. Any propos als not received in a timely manner on the Proposal Due Date, as described above, will not be considered.

Note: The City of Vista complies with the Americans with Disabilities Act. If you require reasonable accommodations, please contact th e Office of the City clerk, 760-639-6125, at least forty-eight (48) hours prior to the bid opening.

B. Requirements.

In order to maintain uniformity with all proposals furnished by Consultants, it is hereby requested the proposals be limited to a maximum of ten (10) pages (excluding front and back covers, section dividers, Scope of Work, Fee Proposal, Work Schedule, sample Work Product, and resumes).

The Proposal should typically be formatted to fit on 8-1/2 x 11 pages. Larger pages up to 11x17 can be used for exhibits, such as a schedule, if needed to make the exhibits legible due to a substantial amount of detail. The page count is based on pages of information included in the RFP that indicates the Consultant’s qualifications. Double-sided pages are acceptable, and a page that says “this side intentionally left blank” does not count toward the page limit. Proposals should include, at a minimum, the following elements:

1. COVER LETTER, which includes:
a. The name and address of the firm on formal letterhead, 05/27/2025
C6

Page 20 of 194 ends

8 b. The name of the project, and
c. The name, title, and signature of an individual with authority to bind the Consultant.

2. STATEMENT OF QUALIFICATIONS, which includes:
a. A synopsis of the firm’s qualifications,
b. An Organization Chart showing the names and classifications of key personnel, and project team relationships,
c. A staffing plan and descriptions of the qualifications of the Project team members,
d. Resumes of key prime and subconsultant staff members assigned to the project, e. A list of similar contracts completed by the firm or team members within the last five (5) years. Include the project name; project description; location; role and level of involvement of the prime firm as well as any sub-consultants; design and/or construction dates of completion; bid costs vs. final construction costs, and client references with name, phone number and email address, and f. Information related to the financial responsibility of the firm.

3. WORK PLAN which describes:
a. The Consultant’s understanding of the project,
b. The approach and methodology to be used to accomplish the required services, and
c. The Consultant’s proposed Scope of Work. The proposed Scope of Work should be based on the tasks listed in the Scope of Work included in this Request for Proposals, with suggested alternatives to the proposed tasks or deliverables that may improve upon achievement of the project objectives. The Consultant should clearly identify any proposed modifications to the tasks listed in the Scope of Work.

4. FEE PROPOSAL which includes:
a. A breakdown of costs by task, together with
b. The cost of non-labor and subconsultant services. This information will be used by City staff to evaluate the reasonableness of the fee proposal and will be used in negotiating the final fee amounts for the Professional Services Agreement. The Consultant’s Standard Hourly Billing Rates for all classifications of staff likely to be involved in the project shall be included with the fee proposal along with the mark-up rate for any non-labor expenses and subconsultants.

5. Detailed WORK SCHEDULE, which shows:
a. The time required for each task, and
b. The reasonable amount of time the Consultant will require to perform the required services. The proposed Work Schedule should list the tasks with begin and end dates and should be based on the proposed start date listed in this RFP. 05/27/2025
C6

Page 21 of 194 ends

9 Project milestones such as submittals should be shown, and a reasonable amount of time should be shown for City review of each submittal.

6. Comments on the City of Vista Standard CONSULTANT AGREEMENT. Identify any concerns with the terms and conditions of the City’s Standard Consultant Agreement, including Insurance and Indemnification provisions. If terms are acceptable, provide a statement that the Consultant will sign the City’s Agreement as presented.

7. Copies of SAMPLE WORK PRODUCT from a previous similar project completed by the Consultant. The consultant shall submit examples of reports and bid packages consisting of Plans, Specifications, and Es timates for a project similar to the ones described in this RFP.

VIII. CRITERIA FOR SELECTION

The City's consultant evaluation and select ion process is based on Qualifications Based Selection (QBS) for professional services. An evaluation committee appointed by the City Engineer will review the proposals. The criteria and weight for evaluating the proposals submitted will be as follows:

1. Project Understanding: Demonstrated understanding of the project requirements, degree of creativity and innovation demonstrated with respect to the project approach and scope of work, and reasonableness of the schedule for the work and how the time has been allocated to specific tasks (30 points)

2. Responsiveness to Client’s Needs: Familiarity with City, State, and federal requirements and procedures; and thoroughness and completeness of proposal in response to RFP (20 points)

3. Firm’s Experience with Similar Projects: Technical experience of project team in performing work of a closely related nature, experience working with public agencies, record of completing work on schedule and within budget. (20 points)

4. Staff and Project Experience: Qualifications of project team staff members, key personnel’s level of involvement in performing related work, logic of project organization, and adequacy of labor commitment. (15 points)

5. Quality of Work Product: Demonstrated technical ability based on relevance and quality of sample work product (15 points)

Fee Schedule (separate electronic file uploaded to OpenGov Procurement). The fee schedule of the top ranked Consultant will be opened at the conclusion of the consultant evaluation and selection process. Fees will not be used to determine the ranking of the consultants. The City may interview a short li st of top ranked qualified consultants or proceed directly to negotiating the final fee schedule with the top ranked consultant. The ultimate consultant selection will be based upon both technical merit and value to the City.

The contract award, if any, will go to the Consultant whose proposal best serves the interests of 05/27/2025
C6

Page 22 of 194 ends

10 the City, as it determines in its sole discretion according to the evaluation criteria described above.

The individual or composite ratings and evaluation forms prepared by City’s evaluators will not be revealed.

IX. REQUIREMENTS FOR PROVIDING SERVICES
The selected Consultant shall be expected to comply with all applicable federal, state, and local regulations, and contract provisions. The selected consultant will be expected to perform the work as described in this RFP.

The consultant shall carry out the instructions received from the City and shall cooperate with the City and other involved agencies.

The Consultant will be required to assume resp onsibility for all services offered in their proposals. The selected consultant will be the sole point of contact with regard to contractual matters, including payment of any and all charges resulting from contracts.

The Consultant shall have a Quality Control and Quality Assurance (QA/QC) plan in effect during the entire time work is being performed under the Agreement. The QC/QA plan shall establish a process whereby plans and other work products are independently checked, corrected, and back checked, and all job-related correspondence and memoranda are dated and then bound in appropriate job files.

Consultant is responsible for researching available records, determining their usefulness on this project, and paying any charges for copies of records.

All exhibits, studies, reports, plans, specifications, estimates, calculations, and other documents shall be prepared in accordance with the scope of work. City of Vista standards and San Diego Regional Standard Drawings shall be utilized where applicable and may be called out on the plans as a reference. Improvement plans shal l adhere to City of Vista Standards and the Standard Specifications for Public Works Construction (GREENBOOK). Plans and exhibits shall be computer drafted in AutoCAD, ArcView or other compatible software and delivered to the City of Vista at project completion on electronic media in a format readable by the City, along with .pdf files for archival purposes.

The exhibits, studies, reports, plans, specif ications, estimates, calculations, and other documents furnished under the Agreement shall be of a quality acceptable to the City. All work products shall be of neat appearance, well organized, technically and grammatically correct, internally consistent, thoroughly reviewed and checked, dated, designated with an accurate “percent complete” number, and having the maker and checker identified. The minimum standard of appearance, organization and content of the drawings an d other work products shall be that of similar types provided by th e Consultant in its Proposal as Sample Work Products and as set forth in related City of Vista standards and guidelines. The Consultant shall 05/27/2025
C6

Page 23 of 194 ends

11 modify its work as necessary to meet the level of acceptability defined by the criteria above.

The Consultant has total respon sibility for the accuracy and completeness of the studies, reports, exhibits, plans and related designs, specifications and estimates prepared and shall check all such materials accordingly. The report s, plans, and other work products will be reviewed by the City for conformity with the requirements of the Agreement. Reviews by the City do NOT include detailed review or checking of design or the accuracy with which such designs are depicted on the plans. The responsibility for accuracy and completeness of such items remains solely that of Consultant.

Consultant or its subconsultants shall not incorporate in the design any materials or equipment of single or sole source origin without written approval of the City.

All completed work, including surveys, workshop documents, schematic designs, ancillary reports, calculations, correspondence, and all other work produc t developed as part of this project, whether in written, video, or electronic formats, becomes the property of the City at the end of the project.

X. ESTABLISHMENT OF FEES

The Consultant shall be paid based upon hourly rates and unit costs for services rendered as negotiated.

Sub-consultant costs shall be allocated on a per task basis but does not need to be broken out by each staff classifications. The City limits mark up for sub-consultants and direct costs to 5%. This information will be used by City staff to evaluate the reasonableness of the estimated cost of services and will be used in negotiating the final fee amounts for the contract agreement. Hourly rates shall be based on work occurring in 2023. Proposed rates shall clearly correlate with names and classi fications of staff likely to be involved with the projects.

The Consultant shall be paid based upon hourly rates for services rendered as negotiated.

There will be no compensation to the Consultant for hours expended due to the Consultant’s errors and omissions. There will be no adjustments including an increase in the hourly rate.

XI. METHOD OF PAYMENT

The Consultant shall submit monthly invoices to the City. Each invoice shall include a detailed breakdown of the services, the tasks, the hours, the personnel, and staff type who worked on the project, and ho urly rates. No more than 85 percent of the total payment amount will be made prior to the final complet ion and approval of all work and delivery of final products.
05/27/2025
C6

Page 24 of 194 ends

12 XII. CONSULTING AGREEMENT

A sample Standard Consulting Agreement is enclosed for review, as Attachment “C”. The RFP and the Consultant’s Proposals will be atta ched and become part of the Agreement as exhibits.

The signer of the proposal must declare in writing that the only person, persons, company or parties interested in the proposal as principals are named therein; that the proposal is made without collusion with any other person, persons, company, or parties submitting a proposal; that it is in all respects fair and in good faith without collusion or fraud; and, that the signer of the proposal has full authority to bind the principal proposer.

Please refer to the sample agreement for th e necessary amounts of general liability, automotive, worker’s compensation and professional liability insurance. The appropriate endorsements are also shown within the sample contract agreement. The insurance certificate shall include the City of Vista, its officers and employees as insured or additional insured.

The contents of the Proposal of the successf ul Consultant shall become a contractual obligation if a contract ensues. Failure of a Cons ultant to accept this obligation will result in the cancellation of any award. Any damage accr ued by the City as a result of a failure to contract may be recovered from the Consultant.

XIII. ASSIGNED REPRESENTATIVES

The City will assign a responsible representative to administer the contract, and to assist the Consultant in obtaining information. The Co nsultant also shall assign a responsible representative (Project Manager), who shall be identified in the proposal. The Consultant’s representative will remain in responsible charge of the Consultant’s duties from the Notice- to-Proceed through project completion. If the Consultant’s Project Manager should be unable to continue with the project, then the Consultant shall notify the City’s representative in writing. The City’s representative shall first approve any substitution of representatives or sub-consultants identified in the proposal in wr iting. The City reserves the right to review and approve/disapprove all key staff and sub-consultant substitution or removal and may consider such changes not approved to be a brea ch of contract. This breach of contract will not apply if the Project Manager leaves the Consulting firm.

XIV. RIGHT TO REJECT PROPOSALS

The City reserves the right to delay the project or reject any or all proposals submitted, and no representation is made hereby that any contract will be awarded pursuant to this RFP or otherwise.
05/27/2025
C6

Page 25 of 194 ends

13 The City reserves the right to extend the due date for proposals, accept or reject any or all proposals received as a result of this RFP, negotiate with any qualified consultant or cancel this RFP in part or in its entirety. The City may require the selected Consultant to participate in negotiations and to submit such technical fee, or other revisions of their proposals as may result from negotiations.

All costs incurred in the preparation of th e proposal, the submission of additional information and/or any aspect of a proposal prior to award of a written contract will be borne by the Respondent. The City will provid e only the staff assistance and documentation specifically referred to herein and will not be re sponsible for any other cost or obligation of any kind, which may be incurred by the Responde nt. All proposals submitted to the City of Vista become the property of the City.

XV. DISCLOSURE

The City is a public agency subject to the disc losure requirements of the Public Records Act, California Government Code Section 6250 and following. These requirements include an exemption for “trade secrets”. If any proprietary information is contained in or attached to the written proposal, it must be clearly identified in Consultant’s proposal. In order to protect trade secrets from disclosure, pursuant to a Public Records Act request, you must agree in writing to defend and indemnify the City of Vista if litigation results.

XVI. LATE, MODIFIED, OR WITHDRAWN PROPOSAL

Any Proposal received after the exact time specified for submittal will not be considered.

Any modification of a proposal, except a modification resulting from the City's request for "best and final" offer, is subject to the same conditions as the initial submission.

Proposals may be withdrawn by written notice received at any time prior to Notice of Intent to Award. Thereafter, all proposals constitute firm offers, subject to negotiation and execution of definitive documents that will remain open and cannot be revoked, withdrawn, or modified for a period of six (6) months thereafter.

XVII. CONCLUSION

If after reviewing the above requirements, the Consultant is interested in proposing your services to the City of Vista, the Consultant should notify the City of their interest and their intent to submit a proposal. All submittals must be received in the Engineering Department by the date and time listed in this RFP.

The selected consultant will be asked to negotiate a final scope of work, fee, and schedule for the project. Small contracts up to $150,000 may be awarded by the City Manager.

Larger contracts over $150,000 must be approved by the City Council. 05/27/2025
C6

Page 26 of 194 ends

14 Any questions shall be submitted through the Open Gov procurement portal by March 12, 2025, at 4:00 PM.

Attachment A: USDA Forest Service Grant Narrative for the landscape improvements and construction cost estimate. Midblock pedestrian crossings on N. Santa Fe Ave constructed with the Townsite Complete Street Project.

Attachment B: Scope of Work

Attachment C: City of Vista Standard Consulting Agreement

05/27/2025
C6

Page 27 of 194 ends

15 ATTACHMENT A

USDA Forest Service Grant Narrative for landscape improvements and construction cost estimate.

Midblock pedestrian crossings on N. Santa Fe Ave constructed with the Townsite Complete Street Project.

05/27/2025
C6

Page 28 of 194 ends

N. SANTA FE AVE
PLANNING | ENGINEERING |

CONSTRUCTION MANAGEMENT
5095 Murphy Canyon Rd, Suite 330
San Diego, California 92123
Tel: (619) 683-2933 Fax: (619) 683-7982

NEVADA AVE
Ø4P
Ø4P
Ø2
Ø2
2 F=14'
F=14'
1 3
44 55
Ø6
Ø6
7 6
8 9 9
1010
Ø6
Ø2
Ø6
Ø6
Ø6
Ø6
Ø6
Ø2
Ø2
Ø2
Ø2
Ø2
#6
EVP Ø2
EVP Ø6
05/27/2025
C6

Page 29 of 194 ends

N. SANTA FE AVE
PLANNING | ENGINEERING |

CONSTRUCTION MANAGEMENT
5095 Murphy Canyon Rd, Suite 330
San Diego, California 92123
Tel: (619) 683-2933 Fax: (619) 683-7982
Ø6
Ø6
Ø2
Ø2
2 1
3 44
53Ø2
Ø2
Ø2
Ø2
Ø2
7 6
8 9 9
1010
Ø6
Ø6
Ø6
Ø6
Ø6
Ø2
Ø4P
Ø4P
F=14'
F=12'
#6
Ø6
EVP Ø2
EVP Ø6
05/27/2025
C6

Page 30 of 194 ends

NEWPORT DR

E VISTA WAYTOWNSITE DR

NORTH SANTA FE AVE

NORTH SANTA FE AVE

NEVADA AVE

TRULY TERRACE
PLANNING | ENGINEERING |

CONSTRUCTION MANAGEMENT
5095 Murphy Canyon Rd, Suite 330
San Diego, California 92123
Tel: (619) 683-2933 Fax: (619) 683-7982
W16-7P(L/R)
R1-1
A24E
LIMIT
A24E
38 56'
27B
395'
39 111'
R81(CA),
R81A(CA)
R81(CA),
R81B(CA)
R81(CA)
R81B(CA)
R81(CA),
R81A(CA)
R1-1
SPEED
R2-1(30)
25 LIMIT
R81(CA)
BEGIN
R81A(CA)
END
R81B(CA)
W11-2W16-7P(MOD)
W16-9P
DETAIL

CONTINENTAL

BIKE LANE

CROSSWALK
N.T.S.

R10-6
W11-2,
W16-7P(R)
R10-6
R10-6
R10-6
39 408'
39A
90'
2'
3'
4'-5'
XX

PAVEMENT MARKING AND STRIPING NOTES

SIGN NOTES
OM-1

PARKING OF

VEHICLES

FOR SALE

PROHIBITED
39A
SNS
50'
16'
27B
125'
46'
38A
60'
W3-3
SNS
LIMIT
A24E
LIMIT
R10-6
A24E
LIMIT
W11-2,
W16-7P(L)
W11-2,
W16-7P(R)
W11-2,
W16-7P(L)
W11-2,
W16-7P(L)
A24E
LIMIT
A24E
LIMIT
W11-2,
W16-7P(L)
R1-5(MOD)

PROPOSED SIGNS THIS SHEET
6" WHITE
PAINT

GREEN PAINT
LEGEND
(X')
RC
A24D
22 R2-1(25)
R30B(CA)25
A24C
1397'
9 9
9 9
R26(CA)
DETAIL
LADDER

CROSSWALK
N.T.S.
6'

DETAIL (PAINT)
N.T.S.
"BIKE LANE SYMBOL
WITH PERSON" PER
CALTRANS A24C
6'6'
BIKE LANE ARROW PER CALTRANS A24A

DETAIL (PAINT)
N.T.S.

9.75'
"SHARED ROADWAY BICYCLE
MARKING" PER CALTRANS A24C
2'
2'
10' 1'
05/27/2025
C6

Page 31 of 194 ends

NORTH SANTA FE AVE
PLANNING | ENGINEERING |

CONSTRUCTION MANAGEMENT
5095 Murphy Canyon Rd, Suite 330
San Diego, California 92123
Tel: (619) 683-2933 Fax: (619) 683-7982

NEVADA AVE
05/27/2025
C6

Page 32 of 194 ends

NORTH SANTA FE AVE
PLANNING | ENGINEERING |

CONSTRUCTION MANAGEMENT
5095 Murphy Canyon Rd, Suite 330
San Diego, California 92123
Tel: (619) 683-2933 Fax: (619) 683-7982
05/27/2025
C6

Page 33 of 194 ends

05/27/2025
C6

Page 34 of 194 ends

Infla�on Reduc�on Act (IRA) Urban and Community Forestry (UCF) Grant Narra�ve and Budget Template

1. S&PF PROGRAM or PROJECT – Infla�on Reduc�on Act Urban and Community Forestry Program

2. PROJECT TITLE – N. Santa Fe Corridor Vista CA Landscaping and Irriga�on Project

3. GRANTEE NAME City of Vista

4. PROJECT COORDINATOR(S) – The Project Coordinator will be Greg Mayer, Director of Engineering, email [email protected] p hone 760 -643-5408.

Jason Rivera, Capital Projects Manager, will be responsible for progress and financial repor�ng.

Email [email protected] p hone 760 -643-5422.

5. STATEMENT OF NEED/PROBLEM –
The City of Vista, CA is proposing a project to plant an es�mated total of 125 trees in the median and along both sides of a 1.3-mile stretch of N. Santa Fe Ave. and install and upgrade outdated irriga�on systems to supply water for the planted trees. It is necessary to update the irriga�on system as part of the addi�onal tree canopy project. The exis�ng irriga�on system would not be able to sustain the addi�onal newly planted trees and the dated pipes themselves prove to be unstable requiring costly maintenance for old technology. The exis�ng outdated piping for irriga�on would prove poten�ally dangerous, costly, and ineffec�ve to retro fit into a newer system of irriga�on.

This area is densely traveled by motorized vehicles, includes a transit center for buses and commuter trains, and is heavily u�lized with ac�ve transporta�on like walking and biking. It includes schools, a skate park, a transit center, mul�ple businesses, and residen�al homes (soon to include 62 affordable housing units for homeless seniors). The area is lacking in tree canopy; according to the Tree Equity Score Data, th
e census tracts along this sec�on of N. Santa Fe are
among the highest priority for the area with a range of 7%-16% current canopy coverage in the census tracts. This project aligns with the Jusitce40 ini�a�ve, State Forest Ac�on Plans, and the 10- year Urban and Community Forestry Ac�on Plan as well as the City of Vista’s Master Plan and Climate Ac�on Plan. The project will enhance the city’s urban tree canopy, provide numerous environmental benefits, improve health and well-being for the residents, promote environmental jus�ce for underserved/disadvantaged communi�es, and align with the City’s resource conversa�on and sustainability goals.

6. GOALS – Describe the goals this work will help to achieve. Goals must be consistent with program authori�es and guidelines. Iden�fy and briefly summarize the long-term strategies working toward this goal being implemented in this grant narra�ve. Provide concise reference to strategies in the State’s Forest Ac�on Plan (page number, strategy number). Do not copy and paste long sec�ons of text.

The project of plan�ng 125 trees and installing and upgrading the irriga�on system for the 1.3-mile stretch of N.

Santa Fe Rd between Vista Village and Bobier Dr. contributes to the goals in this funding opportunity to:
05/27/2025
C6

Page 35 of 194 ends

a. Foster individuals, groups, and organiza�ons in the communi�es served to become engaged par�cipants in urban forest planning, plan�ng, and management, especially those in disadvantaged communi�es that do not have adequate resources to install or maintain green infrastructure or are underrepresented.
b. Protect, enhance, and expand equitable urban tree canopy cover to maximize community access to human health, social, ecological, and economic benefits par�cularly in disadvantaged and nature-deprived communi�es experiencing low tree canopy cover, extreme heat and frequent flooding. Improve and increase access to parks and nature in communi�es. c. Encourage proac�ve and systema�c maintenance and monitoring of urban trees and forested natural areas to improve forest health; assess risk to forests from pests, disease, and adverse climate impacts; and formulate adap�ve management strategies to improve forest resilience. d. Aid in planning, goal se�ng, and skill sharing with other professions such as urban planners, engineers, educators, recrea�onal and public health officials.

The project will address environmental issues of air quality, ground water contamina�on, climate change, and provide green infrastructure health and biodiversity to promote a resilient environment. In alignment with the goals from the State of California’s Forest Ac�on Plan of protec�ng and enhancing public benefit from trees by increasing urban forestry programs in communi�es that would strongly benefit from the increased canopy cover, cooling effects and air quality improvements that trees offer, the addi�on of 125 trees in this area would provide cooling and shading benefits that would improve the quality of life while also ac�ng as carbon sinks to reduce greenhouse gases, and reducing ground water runoff.

According to The Ten-Year Urban and Community Forestry Ac�on Plan studies have revealed trees not only contribute to posi�ve health consequences like improved air quality and reduced urban heat island effect, but also contribute to cogni�ve, emo�onal, and physiological health, including stress reduc�on. In alignment with the goals of The Ten-Year Urban and Community Forestry Ac�on Plan of diversity, equity, and leadership, this project will provide access to nature by plan�ng 125 trees in underserved neighborhoods that have less access to trees and green space and will promote health and well-being to these underserved communi�es.

This project directly provides benefits for disadvantaged communi�es (See Atachment B. Disadvantaged Communi�es Area Mapping Images 1-6) in the City of Vista in the areas iden�fied by the Jus�ce40 Ini�a�ve including addressing climate change, remedia�on and reduc�on of legacy pollu�on, and cri�cal clean water infrastructure. By reducing greenhouse gas and improving air quality through cardon sequestering and reducing urban island heat, street trees address issues of both climate change and pollu�on. Trees also reduce urban runoff (e.g., debris/oils/heavy metals) and stormwater runoff that can lead to the degrada�on of surface water quality in our watersheds. This has led to many of the beneficial uses of watersheds not being atained. Increasing trees in urban areas will reduce impairments to the waterbodies within Vista’s watersheds and will promote cri�cal clean water infrastructure.

Upgrading outdated and installing new drip irriga�on systems eliminates overspray runoff that can contribute to water pollutants and installing bubblers directs the water directly to the trees’ root systems to eliminate flooding and runoff while improving water conserva�on efforts. Addi�onally, the project will enhance the economic opportuni�es for the community by enhancing the appeal of the neighborhood to encourage development and private investment.

The City of Vista’s General Plan 2030 gui
des the city’s future growth through sets of goals and policies. Specifically, this included the goal (Resources Conserva�on and Sustainability Goal 2) to reduce GHG emissions from community ac�vi�es and municipal facili�es within the city to support the state’s efforts under AB 32, and to mi�gate the community’s contribu�on to global climate change (City of Vista 2012a). Vista recognizes the interconnectedness of water quality and conserva�on to these goals. As men�oned, urban runoff and storm water have been shown to contribute to the degrada�on of surface water quality. To address this as part of this project the City will prac�ce low impact development by plan�ng trees that are low water use and drought resistant. It is 05/27/2025
C6

Page 36 of 194 ends

also paramount to install and upgrade outdated irriga�on in the project area to avoid overwatering, ongoing maintenance issues, and corroded and poten�ally harmful outdated materials. Low impact development will include installing drip irriga�on systems that do not allow for overspray and runoff. Installing bubblers focuses water to the root zone to mi�gate flooding and runoff in the area as well, while installing smart sensors prevent overwatering and aid in water conserva�on efforts. Smart sensors provide water saving automa�on that saves �me and can pinpoint issues early that can make a difference between trees thriving or not.

Sta�s�cs show up to 40% savings on water usage when smart sensors are installed in an irriga�on system which provides significant cost savings.

Dukes, M. D. (n.d.). Water Conserva�on Poten�al of Landscape Irriga�on Smart Controllers. American Society of Agricultural and Biological Engineers, 2151–0032. The General Plan 2030 includes RCS Policy 3.3: Manage the city’s stock of vegeta�on on public property (e.g., street trees, planted medians, lawns at public facili�es and parks, etc.) to reduce water consump�on.

The City’s goals to reduce GHG emissions and improve energy efficiency resulted in the adop�on of the City of Vista Climate Ac�on Plan in 2013 (2013 CAP) and the city’s Energy Roadmap, the City of Vista Bicycle Master Plan, the development of new bicycle and pedestrian facili�es, increased tree plan�ng in public parks and right-of-way, and improved energy efficiency in exis�ng buildings and includes the goal to reduce the projected demand for water service in the city through water conserva�on and increased use of recycled water. Plan�ng 125 trees and installing and upgrading the exis�ng irriga�on system in the project area will make a posi�ve impact towards those goals.

Vi
sta has completed projects of similar or larger scope, such as the now re-envisioned corridor of S. Santa Fe Ave that the City saw through three phases to comple�on. A reconstruc�on of almost a mile of S. Santa Fe Avenue between Vista Village Drive and Civic Center Drive provides a pedestrian-friendly thoroughfare through the downtown core. This area, known as the Paseo Santa Fe corridor, creates a sense of place and has revitalized and beau�fied downtown. Now established, the street enhancements will drive other downtown uses and will benefit local businesses and the community alike. Construc�on took place in three phases, with the final comple�on in December 2020. The project began in May 2014 and the first phase (.25 miles) was completed in early April 2016. This por�on extends from Main Street to Ocean View Drive.

T
he streetscape improvements included the complete makeover of this segment of S. Santa Fe Avenue, including below ground improvements such as new water, sewer, and storm drain lines. The visible improvements included placing overhead u�lity lines underground, narrowing the road from four lanes to two lanes, construc�ng new sidewalks; installing streetlights and street furnishings; installing a gateway arch sign; and construc�ng Vista's first roundabout at Eucalyptus Avenue. Veterans Memorial Park w as constructed by Affirmed Housing and the Pinamon� family. While much of the project included tree-lined streets, they are palm trees that do not provide large amounts of shade that would come from a different tree species. In the project that this grant is funding, we want to be mindful of the amount of shade provided for heat-island reduc�on and GHG reduc�on by the trees we plant, thus considering species of trees more suited to those goals.

L
essons learned from the S. Santa Fe project include allowing for con�ngencies and ensuring flow between mul�ple phases of the project. This will be especially important in the current project on N. Santa Fe that this grant will fund, as it aims to feed into the larger CIP project for a complete streets vision for N. Santa Fe to create a corridor that is safe and accessible for all users, including pedestrians, cyclists, public transit riders, and motorists.

These projects o�en involve redesigning streets to include features such as sidewalks, bike lanes, crosswalks, and traffic calming measures, with the goal of promo�ng ac�ve transporta�on and improving overall safety and mobility for all users. These factors will need to be established early on in design to incorporate with the establishment of a tree canopy and installa�on of irriga�on systems.

7. OBJECTIVES/OUTPUTS –List the objec�ves to be met to address the goals/strategies. Objec�ves are specific ac�ons this program/project is intended to achieve during the �me of this grant to 05/27/2025
C6

Page 37 of 194 ends

meet or work towards achieving the goals that are listed. Objec�ves are “SMART” – Specific, Measurable, Accountable, Realis�c, and Timely. Also include objec�ves to meet any specific targets or direc�on for use of program funds, as highlighted in the funding advice. Provide specific details to clearly quan�fy the deliverables (outputs), such as number and names of communi�es assisted, loca�on and number of acres surveyed or treated, number of trees grown in the nursery/planted, descrip�on and dollar value of equipment purchased, number of personnel trained.

Measurable outcomes:

1. Number of trees planted.
a. Goal approx. 125 trees
i. The area for tree plan�ng and irriga�on is a 1.3 mile stretch of N. Santa Fe Dr. in Vista, CA. This will include trees on both sides of the road as well as in the median. (Approx .26 square miles) This area includes por�ons of four different census tracts: 195.01, 195.02, 192.06, and 194.04)

2. Tree growth and survival rate.
a. Goal 90% survival rate or higher a�er the first year of plan�ng.

3. Increase in tree canopy cover.
a. The current tree canopy is 7%-16% in the designated project area census tracts for an average of 11.5% for the area- goal to increase average tree canopy coverage to 15%.

4. Reduc�on in urban heat island effect.
a. This reduc�on should taper over �me with tree growth and increased shade. This can be monitored with California’s Heat Assessment Tool.)

5. Reduc�on in stormwater runoff.
a. With smart-senor technology installed, an average of 40% decrease in run-off.

6. Increase in air quality. *

7. Increase in carbon sequestra�on. *

8. Increase in biodiversity. *

9. Increase in public awareness and educa�on about the benefits of trees. (This will be evaluated with city-wide pre- and post-project survey tools sent via newsleters and available on the city website with a goal of 150 survey response both pre- and post-project) .

10. Reduced water waste. *

11. Improved water quality. *

12. Community Engagement regarding educa�on on urban forestry. a. Previous community workshop feedback will be incorporated with project specific community mee�ngs to assess par�cipa�on and understanding of project goals and outcomes.)

*The outcomes can be monitored over �me through assessment tools like EJ Screen f rom the
EPA, CalEnviroScreen, and C EJST ( Climate and Economic Jus�ce Screening Tool).

8. SPECIFIC ACTIVITIES – Describe in detail what work will be done to achieve the objec�ves. Include who will lead and perform the ac�vity, the responsibility others have (including partners), the geographic area where the work will be done, and �meframes when the work will be done. You must include the census tracts where the work is occurring and the tool(s) that was used to determine whether those tracts are in disadvantaged communities (CEJST, EJScreen, CalEnviroScreen, EPA EnviroAtlas Interactive Map, Opportunity Zones, Hawaiʻi Urban Tree Canopy Viewer, etc).

05/27/2025
C6

Page 38 of 194 ends

The project's objec�ve is to plant 125 trees in the median and along both sides of N. Santa Fe Ave, spanning approximately 1.3 miles from Vista Village Drive at the southern end to Bobier Dr. at the northern end. In addi�on, the outdated irriga�on systems will be updated and installed to supply water for the planted trees using sustainable methods that reduce water usage using smart sensors and minimize water run-off. The exis�ng outdated piping for irriga�on would prove poten�ally dangerous, costly, and ineffec�ve to retro fit into a newer system of irriga�on. The exis�ng irriga�on system would not be able to sustain the addi�onal newly planted trees and the dated pipes themselves prove to be unstable requiring costly maintenance for old technology.

This ini�a�ve aims to improve the city's urban tree canopy, offer various environmental advantages, enhance the well-being of the residents, and promote environmental jus�ce for underserved and disadvantaged communi�es.

There are four census tracts in the designated project area: 192.06, 194.04, 195.01, and 195.02. Census tracts 195.01 and 194.04 border the east side of the N. Santa Fe Corridor from Vista Village Drive to Bobier Dr, while 195.02 and 192.06 border the west side. All four census tracts encompass low-income neighborhoods and a large percentage of under-represented racial/ethnic minori�es.

The Ten-Year Urban and Community Forestry Ac�on Plan defines Underserved Communi�es as communi�es that do not receive equitable financial and technical assistance as other communi�es might, in maximizing the benefits from the conserva�on and management of their natural resources. In this context, the term “underserved” encompasses low income, under-represented racial / ethnic minori�es; Na�ve Americans; people with disabili�es; and the elderly.

According to the Interim Implementa�on Guide for the Jus�ce40 Ini�a�ve, agencies should define community as “either a group of individuals living in geographic proximity to one another, or a geographically dispersed set of individuals (such as migrant workers or Na�ve Americans), where either type of group experiences common condi�ons.” The N. Santa Fe Corridor that consists of the project loca�on can be considered a community by the defini�on of a group of individuals living in geographic proximity to each other even though it consists of four separate census tracts.

According to the Interim Implementa�on Guide for the Jus�ce40 Ini�a�ve for an area to be “disadvantaged” agencies should consider appropriate data, indices, and screening tools to determine whether a specific community is disadvantaged based on a combina�on of variables that may include, but are not limited to, the following:
o Low income, high and/or persistent poverty.
o High unemployment and underemployment.
o Racial and ethnic residen�al segrega�on, par�cularly where the segrega�on stems from discrimina�on by government en��es.
o Linguis�c isola�on.
o High housing cost burden and substandard housing.
o Distressed neighborhoods.
o High transporta�on cost burden and/or low transporta�on access. o Dispropor�onate environmental stressor burden and high cumula�ve impacts. o Limited water and sanita�on access and affordability.
o Dispropor�onate impacts from climate change.
o High energy cost burden and low energy access.
o Jobs lost through the energy transi�on.
o Access to healthcare.

The project area comprises of four census tracts, all of which exhibit mul�ple variables of a disadvantaged community, albeit not consistently across all four tracts. To gain a comprehensive understanding of the specific project area concerning these factors, the EJ Screen Tool was u�lized. The project area was marked on a map that encompasses the N. Santa Fe Corridor, selected for tree plan�ng, and extends only to the east and west sides, excluding the en�rety of each census tract, but instead, focusing on the project area itself. This area covers approximately 0.26 square miles and has a popula�on of around 3,204. The project area ranks excep�onally high 05/27/2025
C6

Page 39 of 194 ends

in the Environmental Jus�ce indexes in the USA percen�le comparison. For example, air quality indicators range from the 80th percen�le (air toxins respiratory HI EJ index) to the 98th percen�le (par�culate mater 2.5 EJ index).

Even when compared to the state, the area's air toxics cancer risk EJ index is in the 90th percen�le, indica�ng dispropor�onate environmental stressor burden and high cumula�ve impacts. According to the same report, 97% of the popula�on in the area are people of color, indica�ng racial and ethnic residen�al segrega�on, with 69% falling under the EJ Screen tool's "low-income" index, and 32% belonging to limited English-speaking households, indica�ng linguis�c isola�on. (See Atachment C. EJ Screen Report). Median household income in the four census tracts is well below the median income of $91,003 for San Diego County where the cost of living is 47% higher than the na�onal average, 8th in the na�on according to a recent report by Apartment list.

Taking a more comprehensive view of the broader area, including all four complete census tracts, each tract meets the criteria of being a disadvantaged community. The CJEST mapping tool iden�fies census tracts 195.01 and 195.02 as disadvantaged communi�es based on its criteria (Atachment B. Image 1). Addi�onally, both census tracts are categorized as "opportunity zones" on the HUD resources map (Atachment B. Image 2). Census tract 195.01 is classified as an area of persistent poverty and a historically disadvantaged community, while census tract 195.02 is an area of persistent poverty and census tract 192.06 is a historically disadvantaged community. (Atachment B. Images 3-6) The term "Area of Persistent Poverty" refers to a census tract where the project is located, with a poverty rate of at least 20% based on the 2014-2018 5-year data series from the American Community Survey of the Bureau of the Census. "Historically Disadvantaged Community" is defined for the Department of Transporta�on RAISE program, in line with OMB's Interim Guidance for the Jus�ce40 Ini�a�ve.

USDA’s The Free and Reduced Meal Program, another na�onally recognized vulnerability indicator based on household income and poverty level, reveals high percentages of students qualifying for the program in the project census tracts. Census tract 194.04 with Bobier Elementary has 89.4% of the students qualifying for the program and Maryland Elementary with 91.7% qualifying for the program. Census tract 195.01 with Vista Academy of Visual Arts has 78.3% of the students qualifying for the program and California Ave. Elementary School has 76.9% qualifying for the program. (Atachment D.). Addi�onally, the project area along N. Santa Fe Ave. will benefit disadvantaged communi�es in these census tracts as defined by the federally-approved EPA IRA Disadvantage Communi�es mapping too l (Atachment E.).

This project aims to address the issue that many studies reveal that the distribu�on of trees and park space o�en dispropor�onately benefits predominantly White and more affluent communi�es (Wolch, J.R., J. Byrne, and J.P.

Newell, 2014). It is important to note that this project is a vital one that will compliment addi�onal improvements slated for the area as part of a complete streets program to include mul�-modal connec�vity, traffic calming measures, pedestrian crosswalks at mul�ple points and improved bus sta�ons, and art installa�ons.

Groundbreaking took place May 2023 on a 62-unit complex for homeless seniors on N. Santa Fe Ave. in the tree plan�ng project area. The census tracts and the targeted area for the project of plan�ng trees and installing and upgrading the irriga�on for watering them will benefit a disadvantaged, low-income community, comprised of mostly people of color that have environmental and health burdens and limited access to trees and park spaces and thus qualifies for the match waiver.

Project schedule �meline with goals/ milestones

1. RFP and consultant selec�on for the Landscape Architect/Cer�fied Arborist: approx. October 2023- July 2024

2. Landscape Architect/Cer�fied Arborist, conceptual design comple�on: July 2024- July 2025

3. Public hearings, Community Outreach: July 2025-Decmeber 2025

4. Bids and selec�on- for contractor furnishing and installing irriga�on system upgrades and furnish and install of 125 trees: December 2025- July 2025

5. Site prepara�on: July 2025- September 2025
05/27/2025
C6

Page 40 of 194 ends

6. Irriga�on system purchase and installa�on: October 2025-April 2026

7. Development and installa�on of signage: April 2026-May 2026

8. Tree purchases and plan�ng, soil amendments and tree grates installed: April 2026-June 2026

9. Ini�al Maintenance Period to monitor and sustain newly planted trees to establish and increase survival rate: June 2026-June 2027.
a. The first year of maintenance will include that watering of the trees and as-needed pruning, adding soil amendments as needed, and monitoring for pests. This area will be maintained by the City’s Landscape Contractor with the oversight of the Public Works Supervisor

10. Project comple�on es�mated for July 1st, 2027 (3 years, 8 months from date of funding award).

The bidding process for contracts and consultant selec�ons in the City of Vista purchases involves writen specifica�ons outlining quality, quan�ty, delivery, and work scope, along with terms and condi�ons. City staff review specifica�ons to ensure fair compe��on. The basis for awarding contracts is to select the lowest responsible and responsive bid mee�ng quality, fitness, and capacity requirements at the lowest price. Factors like delivery �me, quality, references, and payment terms influence the award.

9. KEY PERSONNEL – The City of Vista’s Finance department is responsible for managing all financial ac�vi�es of the City of Vista. The department oversees the City’s revenues, expenditures, investments, accoun�ng, and debt. The department also provides dependable, efficient service to the City Council, City Manager, all City departments, employees, suppliers of goods and services, bond holders, and the public. In addi�on to planning for and monitoring the City’s fiscal health, the department also prepares all necessary financial reports and complies with audit requirements. The department works closely with grant managers to ensure compliance with awards. The City receives more than $10 million in grant funds annually, and leverages Federal, State, Local, and Private-Sector grant funds. A grant management system is in place to organize grant awards. The City has received no findings from external annual audits and remains in good standing with all local, federal, and state grantors.

The project improvements will be maintained through the City’s Public Works Department, funds for maintenance ac�vi�es are managed for landscape projects throughout the City. Public Works will also manage the new landscaping at these loca�ons, ensuring the trees and new plants are established. Staff understand that there is a failure rate when plan�ng, so funding will be budgeted to do any necessary replan�ng. City of Vista’s Public Works Supervisor, Yale Jefferies, has 19 years in park and landscape maintenance and is a Qualified Water Efficient Landscape (QWEL) cer�fied and is in the process of becoming a Cer�fied Arborist. He has successfully overseen projects of similar scope including Redevelopment of Center Medians for the City of Coronado in Coronado Cay’s and re-modeling of the center medians for the City of Vista on Sycamore Avenue and SR-78.

Husam Hasenin, the City of Vista’s Traffic Engineer, has been working for the City of Vista for 15 years, during which he has been engaged in local and regional transporta�on planning. He led the comple�on of mul�ple local planning efforts including corridor studies and mul�modal complete street plans. He has also worked closely with NCTD (North County Transit District) on both opera�onal and planning issues. On the regional level, he has been part of technical working groups tasked with the development of various types of short- and long- range plans such as the regional transporta�on plan, microtransit use, and most recently the North County Comprehensive 05/27/2025
C6

Page 41 of 194 ends

Mul�modal Corridor Plan- all of which look comprehensively at the development of our streets, including the need for trees, irriga�on, and landscaping.

Our Di
rector of the City of Vista’s Engineering Department, Greg Mayer, will have project. oversight. Mr. Mayer has a BS in Civil Engineering and 32 years of experience, sixteen of which has been with the City of Vista. He has successfully managed over $30 million dollars of street scape projects including green street landscaping, most recently the now complete Paseo Santa Fe Streetscape Project.

1. RESPONSIBILITIES – If applicable, describe any special responsibili�es of the Forest Service or others. N/A

2. MONITORING & EVALUATION – Describe how ac�vity progress and achievement of objec�ves will be monitored and reported, including the personnel responsible for conduc�ng the monitoring and repor�ng. Include a statement on the frequency and method of federal repor�ng.

De
scribe how project evalua�on will take place to determine whether goals are being met and Forest Ac�on Plans are being fulfilled.

Project Assessment:

1. Pre- a nd post -plan�ng assessments of soil quality, tree size, and species diversity: Pub lic works city staff
and their landscape contractor is responsible for this.

2. Monitoring tree growth and survival rates by using characteris�cs of specific tree species through SelecTree: A Tree Selection Guide (calpoly.edu) : P
ublic works city staff is responsible for this.

3. Assessment of the impact of the tree canopy on the surrounding environment, including air and water quality, temperature, and biodiversity. City staff are responsible for repor�ng completed projects to SANDAG, who use the informa�on to calculate and produce this data to report out every two years.

4. Assessment of the community’s response to the project, including public awareness and educa�on, and community engagement. City staff in the City Manager’s office, including the communica�ons team is responsible for this.

Ev
alua�on methods:

1. Monitoring of environmental and social indicators to assess the project’s effec�veness in comple�ng its goals. Public works city staff and their landscape contractor is responsible for this.

2. Analysis of economic data to determine the project’s impact on property values and other economic factors. Staff in the City Manager’s office and Economic Development department are responsible for this.

3. Comparison of the project outcomes to establish benchmarks and best prac�ces in urban forestry and tr
ee plan�ng programs. Publi
c works city staff and their landscape contractor is responsible for this.

4. Surveys of community members to assess their percep�ons of the project and its impact on the community. Survey’s will be available in person during community workshops and sent via the City’s newsleters online (es�mate a total of three �mes- at the beginning, mid-point, and end of the project). The surveys will be available in both English and Spanish. City staff in the City Manager’s office, including the communica�ons team is responsible for this.

An overall, comprehensive evalua�on plan will be developed to assess the effec�veness of the city’s tree canopy plan�ng project on N. Santa Fe between Vista Village Dr. and Bobier Dr. with a focus on measuring the project’s impact on environment, economy, and community. Ci ty staff in public works is responsible for
tracking and monitoring city owned landscaped areas. They work with a landscape con tractor for maintenance such as watering, as needed pruning, and maintaining healthy soil condi�ons. The San Diego Associa�on of Governments (SANDAG) requests informa�on from ci�es about projects such as this one that feeds into a report that is published every two years. This report includes GHG data and other environmental markers such as water used, and wastewater produced. The results of the evalua�on will be reported to 05/27/2025
C6

Page 42 of 194 ends

stakeholders and disseminated through various channels, such as social media, newsleters, and community events at the comple�on of the project.

For this pro
gram, financial and progress repor�ng are required semi-annually. We will provide the required financial report form and the recommended progress report template.

3. BUDGET – Outline the federal grant amount, match amount, and leverage amount based on the specific work ac�vi�es. If you have a match waiver, include the federal grant amount only. If applicable, iden�fy the source of non-federal resources. Provide sufficient detail so the Regional UCF Program Manager can determine the allowability of the expense: describe or display how the costs were derived for the ac�vi�es described above (e.g., # hours at $ per hour; # acres at $ per acre, equipment costs, # and type of supplies at $ each, etc.) and the basis for cost es�mates (e.g., historical costs, phone es�mates, catalog price). Personnel/salary costs must be adequately supported and documented in your records (e.g., �me sheets, personnel ac�vity reports).

BUDGET NARRATIVE
The USDA Forest Service Urban and Community Forestry Grant is intended to promote sustainable urban and community forests, enhance the quality of life in urban environments and underserved/disadvantaged communi�es. The project narra�ve includes jus�fica�on for a match waiver and thus all project costs are federal funds that would be funded through this grant opportunity. To achieve the objec�ves of the grant, we have iden�fied several budget items to support our efforts. In this budget narra�ve, we will explain and jus�fy each of the budget items that we have included. The total project cost es�mate is $ . Two categories are included in this es�mate: personnel at $ and contractual at $ . Supplies are not listed under the supply category because the contracted service provider will be responsible as part of the contract for furnishing the items needed for installa�on and project comple�on based on final design of the landscape architect.

1. Personnel: total
The personnel budget item includes base salaries for two City of Vista staff members who will be involved in the project. This includes a project manager and an inspector. These individuals will be responsible for the planning, implementa�on, and management of the project.
• Project Manager base salary per year. 10% of full-�me hours devoted to this project= $ per year. Total for four years= $
• Inspector base salary $ 10% of full-�me hours devoted to this project = $ per year. Total for four years= $
Although the project is an�cipated to be completed in 3 years 8 months, four years is used as an es�mate to allow for delays and/or salary increases. Base salaries were provided by the City of Vista finance department budget manager, Sara Taylor. (Atachment A)

2. Contractual: total $
The breakdown of contractual costs below was obtained by consul�ng with a landscape architect, cer�fied arborist, a principal engineer, a public works supervisor, and obtaining a cost schedule from Vista Irriga�on District for up upgrades and reloca�on of meters. The costs consider the project site area size, current condi�ons, goal of maximizing the number of trees that could be planted in the project site while maintaining viability, considering climate and environmental factors like resilient trees, water use and poten�al run-off. The breakdown of the contractual costs are as follows:

Landscape Design
a. Landscape design: $
The landscape design budget item includes the crea�on of a comprehensive design plan for the project. The plan will incorporate the principles of sustainable urban and community forestry, considering factors such as tree 05/27/2025
C6

Page 43 of 194 ends

species selec�on, soil health, and water management. The design will be created by professionals in the field, and will be based on community input, site analysis, and other relevant factors.

The
landscape design cost es�mate is based on previous contracted services of similar scope and were provided by the City of Vista Public Works department.

Sit
e Prepara�on
b. Mobiliza�on: $10,000
The mobiliza�on budget item includes the costs associated with preparing the site for the start of the project. This includes delivering and se�ng up equipment at the site. Safety will be paramount as this project area is a high traffic area for motor vehicles, pedestrians, and cyclists. The funds will be used to ensure that the construc�on site is safe and secure, and that the project can be completed efficiently. c. Potholing for exis�ng u�li�es: $17,000
The potholing budget item includes the costs associated with loca�ng and protec�ng exis�ng u�li�es, such as water lines, gas pipes, and electrical cables. This is a cri�cal step in the project process, as failure to locate and protect exis�ng u�li�es can result in accidents, service disrup�ons, and costly repairs. d. Demoli�on: $10,000
The demoli�on budget item includes the costs associated with removing or upda�ng exis�ng infrastructure that may be in the way of the new project. This may include por�ons of the sidewalk and other features that are no longer needed or may impede the new design, specifically obstruc�ng or impeding new trees being planted or irriga�on systems required for the new trees.

Site
prepara�on cost es�mates were based on previously contracted services of similar scope and were provided by the City of Vista Engineering department.

Irrig
a�on
e. Furnishing and installing and upgrading irriga�on system: $1,177,370 The irriga�on budget item includes the costs associated with providing an adequate water supply for the trees.

This includes the installa�on or upgrading of an irriga�on system that is designed to provide water efficiently, while minimizing water waste. The current pipes and irriga�on system are outdated, corroded, and would not produce adequate water supply based on their current size and loca�ons for the number of trees being planted to survive. Corroded pipes and components in the old irriga�on system may pose a risk of contamina�on to the new irriga�on water, poten�ally affec�ng plant health and safety. Maintenance to exis�ng infrastructure would prove to be cost prohibi�ve over �me compared to installing upgraded irriga�on systems. Tying new irriga�on into these aging systems could result in uneven water distribu�on, leading to overwatering in some areas and underwatering in others, affec�ng tree health and viability as well as crea�ng inefficiencies in water usage.

The
current water meters and piping do not span the en�rety of the project area where trees would be planted and would need to be updated to 2” pipes for adequate water supply. To maximize water efficiency and minimize water waste, updated water delivery will be achieved with the use of bubblers, drip irriga�on, and smart controllers with weather sta�ons. Drip irriga�on systems do not allow for overspray and runoff. Installing bubblers focuses water to the root zone to mi�gate flooding and runoff in the area as well, while installing smart sensors prevent overwatering and aid in water conserva�on efforts. Smart sensors provide water saving automa�on that saves �me and can pinpoint issues early that can make a difference between trees thriving or not. Sta�s�cs show up to 40% savings on water usage when smart sensors are installed. i. Furnish and install 2” lateral pipes by trenching and direc�onal boring (es�mate for 2200 linear foot)- $750,00

0. ii. Furni
sh and install, upgrade, and restore irriga�on systems including piping, valves, couplers, bubblers, back flows with master valve flow sensors- $96,000. iii. Upgrade exis�ng 10 water meters and relocate as needed ($25,937 each)-$259,370. iv. Furnish and Install 6 Smart-controllers with weather sta�on ($12,000 each)- $72,000. 05/27/2025
C6

Page 44 of 194 ends

Ir
riga�on cost es�mates for items i., ii., and iv. were provided in a mee�ng that included City of Vista Traffic Engineer Husam Hasenin, Public Works Supervisor Yale Jeffery, and an outside subject mater expert Laurie Levine who is a landscape architect and cer�fied arborist.

The
cost es�mate for item iii. was provided by Vista Irriga�on District’s price list for potable and reclaimed water meters that was effec�ve 01/01/23.

Tr
ee Installa�on
f. Sit
e prep, furnish and install 125 trees, root barrier, soil amendments, and one year maintenance of trees: $142,000.

The tree installa�on budget item includes the costs associated with site prepara�on, tree selec�on, tree plan�ng, and one year of maintenance. This includes the purchase and delivery of high-quality na�ve drought resistant tree specimens, as well as the installa�on of the trees in accordance with best prac�ces such as soil amendments and root barriers. The City of Vista typically recommends the following tree species in right-of-way areas: Brisbane Box, Crape Myrtle, Fruitless Olive, Jacaranda, African Sumac, and Australian Willow. Vista recommends plan�ng these trees which will not damage or li� sidewalks, curbs, or guters. Fina l determina�on of the species of trees
planted will be made with public works Supervisor Yale Jeffery and the contracted cer�fied a rborist/landscape architect. Maintenance ac�vi�es will include water monitoring, pruning, and disease preven�on, among other tasks to promote trees that are well established and survive. i. Sit
e prepara�on (soil prep/fine grade)- $2,800
ii. Furnish & install 125, 24 Gallon, Trees w/ 24" box ($300 each)-$37,500. iii. Furnish and Install Root barrier es�mate 1620 linear feet ($10 per linear foot)-$16,200. iv. Furnish and Install Soil amendments (compost, sand, bark mulch)- $18,000. v. Furnish and Install 85 metal street tree grates for public safety along sidewalks. Tree grates can be expanded easily by using a cu�ng wheel to cut or score through the inner ring cas�ng. This can be performed on site as needed to accommodate tree growth. ($500 each)- $42,500.
vi. One-yea
r ini�al maintenance period for 125 trees- $25,000
Tr
ee installa�on costs were provided by subject mater expert Laurie Levine who is a landscape architect and cer�fied arborist.

Sign
age
g. Des
ign, furnish, and install signage: $2,000.

The
signage budget item includes the costs associated with the design, crea�on, and installa�on of 2 signs that will info
rm visitors about the project and acknowledge the Infla�on Reduc�on Act and the USDA and Forest Service funding source for iden�fica�on and educa�onal purposes. The Project will acknowledge the Infla�on Reduc�on Act funding source, as well as USDA and Forest Service support in any publica�ons, audiovisuals, and electronic media developed as deliverables.

Signage
costs were based on previous contractual services of similar scope.

In co
nclusion, the budget items listed above are cri�cal to the success of the USDA Forest Service Urban and Community Forestry Grant project in the City of Vista for the project site of the N. Santa Fe Corridor from Vista Village Dr. to Bobier Dr. Each item supports a specific aspect of the project from personnel, site prepara�on, and irriga�on, to tree installa�on and maintenance. The budget has been designed to ensure that the project is implemented efficiently, safely, and sustainably, while also achieving the desired benefits for the community. 05/27/2025
C6

Page 45 of 194 ends

A su
ggested table format is provided below for inser�ng detailed budget informa�on by each federal Object Class Category that is summarized in the SF-424A. Delete or add lines as needed to reflect work in this narra�ve. Following the suggested table format is an example of a completed table.

PROGRA
M: Infla�on Reduc�on Act Urban and Community Forestry
Budget Items by
SF 424A Object Class
Categories
Local object
class category
(if different)
Federal
$
*State
Match
$
*Other
Match
$
*Leverage
above
required
match
*Source of
“Other
Match”
a. Personnel
Project Manager
annual base salary
$ at 10% for this
project over 4
y
ears= $
Inspector annual
base salary $ at 10%
for this project over 4
y
ears=
b. Fringe Benefits
[Specific Budget Item]
c. Travel
[Specific Budget Item]
d. Equipment
Equipment purchases
over $5,000 are not
allowed
e. Supplies
[Specific Budget Item]
f. Contractual
Landscape Design
Site Preparation
Mobilization-
(Delivering and
setting up equipment
at the site)
10,000
Site Preparation
Potholing- (Locate,
protect, and restore
existing utilities and
improvements)
17,000
Site Preparation
Demolition- (Removal
of existing non-
10,000
05/27/2025
C6

Page 46 of 194 ends

Budget Items by
SF 424A Object Class
Categories
Local object
class category
(if different)
Federal
$
*State
Match
$
*Other
Match
$
*Leverage
above
required
match
*Source of
“Other
Match”
thriving trees,
invasive ground
cover, removing
areas of sidewalk
and/or updating
median areas to
accommodate new
trees)
Irrigation-Furnish &
install 2" lateral pipes
by
trenching/directional
boring (22000 linear
feet)
750,000
Irrigation- Furnish
and install, upgrade,
and restore irrigation
systems including
piping, valves,
couplers, bubblers,
back flows with
master valve flow
sensors
96,000
Irrigation- Upgrade
10 existing water
meters and relocate
as needed ($25,937
each)
259,370
Irrigation- Furnish
and Install 6 Smart-
controllers with
weather station
($12,000 each)
72,000
Tree Installation-
Ground prep (soil
prep/fine grade)
2,800
Tree Installation-
Furnish & install 24
Gallon 125 Trees w/
24" box ($300 each)
37,500
Tree Installation-
Furnish and Install
approx. 1620 linear
foot of Root barrier
($10 per linear foot)
16,200
05/27/2025
C6

Page 47 of 194 ends

Budget Items by
SF 424A Object Class
Categories
Local object
class category
(if different)
Federal
$
*State
Match
$
*Other
Match
$
*Leverage
above
required
match
*Source of
“Other
Match”
Tree Installation-
Furnish and Install
Soil amendments
(compost, sand, bark
mulch)
18,000
Tree Installation-
Furnish and Install
Street 85 tree grates
($500 each)
42,500
Tree Installation-
One-year initial
maintenance period
for 125 trees
25,000
Signage- Design,
Creation, and
Installation of 2 signs
($1,000 each)
2,000
g. Construction
Construction activities
are not allowed
h. Other
[Specific Budget Item]
i. Total Direct Charges
(sum of a-h)
j. Indirect Charges**
k. Totals (i + j) 1,358,370
l. Program Income
*If
your match is waived, leave these columns blank or delete. **If you are claiming indirect charges, you must either include your NICRA (Nego�ated Indirect Cost Rate Agreement) or use the de minimis rate of 10%.
05/27/2025
C6

Page 48 of 194 ends

1 Angela Baggett
From: Sara Taylor
Sent: Wednesday, May 17, 2023 9:41 AM
To: Angela Baggett
Subject: RE: salary info needed for grant
See below.

Salary OT RETIRE UAL GRP INS
Last
Name
First
Name Job Class Code Long Description BU Alloc Position Total

RIVERA JASON CAPTIAL PROJECTS MANAGER MGCF 1 -
GROSCUP KURT CONSTRUCTION INSPECTOR I - II VCEA 1

From: Angela Baggett <[email protected]>
Sent: Tuesday, May 16, 2023 9:20 AM
To: Sara Taylor <[email protected]>
Subject: salary info needed for grant
Hi Sara,
I need a base salary for a CIP manager and a construcƟon inspector for the grant I am working on.

Thank you!!!
Angie
Angie Baggett
City of Vista | Management Analyst- Grants Writer
200 Civic Center Drive | Vista, CA 92084
P: 760.643.5362 | E: [email protected]
Website | Twitter | Facebook | Instagram
Attachment A. Base Salary
05/27/2025
C6

Page 49 of 194 ends

Attachment B. Disadvantaged Communities Area Mapping Images 1 B. 1
Image 1
CJEST Disadvantaged Community Map and with Project Area Red indicates project area N. Santa Fe Ave. and light blue indicates disadvantaged community.
05/27/2025
C6

Page 50 of 194 ends

Attachment B. Disadvantaged Communities Area Mapping Images 2 B. 2
Image 2
Opportunity Zone Map for the area:

Red indicates project area N. Santa Fe Ave. and pink indicates Opportunity Zone
05/27/2025
C6

Page 51 of 194 ends

Attachment B. Disadvantaged Communities Area Mapping Images 3 B. 3
Image 3
Grant Project Location Verification (dot.gov) Areas of Persistent Poverty and Historically Disadvantaged Communities
Red indicates project area N. Santa Fe Ave.
05/27/2025
C6

Page 52 of 194 ends

Attachment B. Disadvantaged Communities Area Mapping Images 4 Image 4
05/27/2025
C6

Page 53 of 194 ends

Attachment B. Disadvantaged Communities Area Mapping Images 5 Image 5
05/27/2025
C6

Page 54 of 194 ends

Attachment B. Disadvantaged Communities Area Mapping Images 6 Image 6
05/27/2025
C6

Page 55 of 194 ends

State
Percentile
USA
Percentile
1/4
Selected Variables
Particulate Matter 2.5 EJ index
Ozone EJ index
Diesel Particulate Matter EJ index*
Underground Storage Tanks EJ index
Environmental Justice Indexes
EJ Indexes - The EJ indexes help users screen for potential EJ concerns. To do this, the EJ index combines data on low income and people of color populations with a single environmental indicator.

Air Toxics Cancer Risk EJ index*
Air Toxics Respiratory HI EJ index*
Traffic Proximity EJ index
Lead Paint EJ index
Superfund Proximity EJ index
RMP Facility Proximity EJ index
Hazardous Waste Proximity EJ index
EJScreen Report
Wastewater Discharge EJ index
*Diesel particular matter, air toxics cancer risk, and air toxics respiratory hazard index are from the EPA’s Air Toxics Data Update, which is the Agency’s ongoing, comprehensive evaluation of air toxics in the United States. This effort aims to prioritize air toxics, emission sources, and locations of interest for further study. It is important to remember that the air toxics data presented here provide broad estimates of health risks over geographic areas of the country, not definitive risks to specific individuals or locations. Cancer risks and hazard indices from the Air Toxics Data Update are reported to one significant figure and any additional significant figures here are due to rounding. More information on the Air Toxics Data Update can be found at: https://www.epa.gov/haps/air-toxics-data-update. 90 60
72 58
39 79
65 70
36 73
95 82
95 98
80 87
77 96
69 89
the User Specified Area, CALIFORNIA, EPA Region 9
Approximate Population: 3,204
N. Santa Fe Corridor
May 10, 2023
Input Area (sq. miles): 0.26
(Version 2.11)
N/A
N/A
0 0
Attachment C. EJ Screen Report
05/27/2025
C6

Page 56 of 194 ends

2/4
EJScreen Report
Superfund NPL
Hazardous Waste Treatment, Storage, and Disposal Facilities (TSDF) Sites reporting to EPA
the User Specified Area, CALIFORNIA, EPA Region 9
Approximate Population: 3,204
N. Santa Fe Corridor
May 10, 2023
Input Area (sq. miles): 0.26
(Version 2.11)
0 0
05/27/2025
C6

Page 57 of 194 ends

EJScreen Report
Value State
Avg.
%ile in
State
USA
Avg.
%ile in
USA
3/4
RMP Facility Proximity (facility count/km distance)
Hazardous Waste Proximity (facility count/km distance)
Wastewater Discharge (toxicity-weighted concentration/m distance) Demographic Index
Over Age 64
People of Color
Low Income
Unemployment Rate
Less Than High School Education
Under Age 5
Demographic Indicators
EJScreen is a screening tool for pre-decisional use only. It can help identify areas that may warrant additional consideration, analysis, or outreach. It does not provide a basis for decision-making, but it may help identify potential areas of EJ concern. Users should keep in mind that screening tools are subject to substantial uncertainty in their demographic and environmental data, particularly when looking at small geographic areas. Important caveats and uncertainties apply to this screening-level information, so it is essential to understand the limitations on appropriate interpretations and applications of these indicators. Please see EJScreen documentation for discussion of these issues before using reports. This screening tool does not provide data on every environmental impact and demographic factor that may be relevant to a particular location. EJScreen outputs should be supplemented with additional information and local knowledge before taking any action to address potential EJ concerns.

Selected Variables
Pollution and Sources
Particulate Matter 2.5 (µg/m3)
Ozone (ppb)
Diesel Particulate Matter* (µg/m3)
Air Toxics Cancer Risk* (lifetime risk per million)
Air Toxics Respiratory HI*
Traffic Proximity (daily traffic count/distance to road) Lead Paint (% Pre-1960 Housing)
Superfund Proximity (site count/km distance)
Socioeconomic Indicators
Limited English Speaking Households
Underground Storage Tanks (count/km2)
Supplemental Demographic Index
Low Life Expectancy
the User Specified Area, CALIFORNIA, EPA Region 9
Approximate Population: 3,204
N. Santa Fe Corridor
May 10, 2023
Input Area (sq. miles): 0.26
(Version 2.11)

43.9 10.4

0.22 N/A

2.7 0.16

0.071

0.096
280

0.3 30
83%
97%
5%
9%
53%
32%
69%

47.7 11.7

0.33 67

5.2 1.1

0.17 0.28
1400

0.43 31
44%
63%
29%
9%
16%
6%
14%
35%
40%
30%
5%
12%
6%
16%

42.5 8.67

0.294
12 2.2

0.77 0.13

0.27 760

0.36 28
39 28
30 N/A
38 15
43 35
47 24
76 97
92 95
95 96
77 10
96 94
93 96
98 78
9 66
89 <50th
N/A
76 29
55 34
53 <50th
80-90th
2%
6%
28 5%
36 0

1.5 3.9
0 0
98 15%
98 15%
39%
5%
0 18%
20%
0 05/27/2025
C6

Page 58 of 194 ends

State
Percentile
USA
Percentile
4/4
Selected Variables
Particulate Matter 2.5 Supplemental Index
Ozone Supplemental Index
Diesel Particulate Matter Supplemental Index*
Underground Storage Tanks Supplemental Index
Supplemental Indexes
This report shows the values for environmental and demographic indicators, EJScreen indexes, and supplemental indexes. It shows environmental and demographic raw data (e.g., the estimated concentration of ozone in the air), and also shows what percentile each raw data value represents. These percentiles provide perspective on how the selected block group or buffer area compares to the entire state, EPA region, or nation. For example, if a given location is at the 95th percentile nationwide, this means that only 5 percent of the US population has a higher block group value than the average person in the location being analyzed. The years for which the data are available, and the methods used, vary across these indicators. Important caveats and uncertainties apply to this screening-level information, so it is essential to understand the limitations on appropriate interpretations and applications of these indicators.

Please see EJScreen documentation for discussion of these issues before using reports. For additional information, see: www.epa.gov/environmentaljustice.

Air Toxics Cancer Risk Supplemental Index*
Air Toxics Respiratory HI Supplemental Index*
Traffic Proximity Supplemental Index
Lead Paint Supplemental Index
Superfund Proximity Supplemental Index
RMP Facility Proximity Supplemental Index
Hazardous Waste Proximity Supplemental Index
EJScreen Report
Wastewater Discharge Supplemental Index
Supplemental Indexes - The supplemental indexes offer a different perspective on community-level vulnerability. They combine data on low-income, limited English speaking, less than high school education, unemployed, and low life expectancy populations with a single environmental indicator. the User Specified Area, CALIFORNIA, EPA Region 9
Approximate Population: 3,204
N. Santa Fe Corridor
May 10, 2023
Input Area (sq. miles): 0.26
(Version 2.11)
95 74
83 72
55 89
77 84
49 86
98 90
98 99
89 93
80 98
74 94
N/A
N/A
0 0
05/27/2025
C6

Page 59 of 194 ends

Educati
onal NSLP Charter Charter Charter Enrollm
ent
Free
Meal
Percent
(%)
FRPM
Count
Percent
(%)
Enrollm
ent
Free
Meal
Percent
(%)
FRPM
Count
Percent
(%)
CALPA
DS Fall
1 Option
Type
Provisi
on School School Funding (K-12) Count Eligible
Free (K-12) Eligible
FRPM
(Ages 5-
17) Count Eligible
Free
(Ages 5-
17)
Eligible
FRPM
Certific
ation
Status
Status (Y/N) Number Type (K-12) (K-12) (K-12) (Ages 5-
17)
(Ages 5-
17)
(Ages 5-
17)
2021-2022 37 68452 105882 San DiegoVista UnifiedFoothill Oak Elementary Unified School DistrictElementary Schools (Public)TraditionalCEP N N/A N/A N K 5 476 401 84.20% 455 95.60% 467 392 83.90% 446 95.50% Y 2021-2022 37 68452 111237 San DiegoVista UnifiedMaryland Elementary Unified School DistrictElementary Schools (Public)TraditionalCEP N N/A N/A N K 5 526 437 83.10% 480 91.30% 515 430 83.50% 472 91.70% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedRancho Minerva Middle Unified School DistrictIntermediate/Middle Schools (Public)TraditionalCEP N N/A N/A N 6 8 599 476 79.50% 545 91.00% 599 476 79.50% 545 91.00% Y 2021-2022 37 68452 115451 San DiegoVista UnifiedMajor General Raymond Murray HighUnified School DistrictContinuation High SchoolsContinuation SchoolCEP N N/A N/A N 10 12 190 143 75.30% 170 89.50% 150 115 76.70% 136 90.70% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedBobier Elementary Unified School DistrictElementary Schools (Public)TraditionalCEP N N/A N/A N K 5 537 416 77.50% 478 89.00% 528 411 77.80% 472 89.40% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedBeaumont Elementary Unified School DistrictElementary Schools (Public)TraditionalCEP N N/A N/A N K 5 504 372 73.80% 433 85.90% 494 366 74.10% 424 85.80% Y 2021-2022 37 68452 4E+06 San DiegoVista UnifiedAlta Vista High (Continuation) Unified School DistrictContinuation High SchoolsContinuation SchoolCEP N N/A N/A N 9 12 122 77 63.10% 96 78.70% 100 66 66.00% 81 81.00% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedGrapevine Elementary Unified School DistrictElementary Schools (Public)TraditionalCEP N N/A N/A N K 5 752 522 69.40% 605 80.50% 743 514 69.20% 597 80.30% Y 2021-2022 37 68452 106120 San DiegoVista UnifiedSIATech Unified School DistrictHigh Schools (Public)TraditionalN/A Y 627 Directly fundedY 10 12 537 429 79.90% 476 88.60% 121 87 71.90% 95 78.50% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedVista Academy of Visual and Performing ArtsUnified School DistrictElementary Schools (Public)TraditionalCEP N N/A N/A N K 5 642 424 66.00% 503 78.30% 642 424 66.00% 503 78.30% Y 2021-2022 37 68452 100933 San DiegoVista UnifiedHannalei Elementary Unified School DistrictElementary Schools (Public)TraditionalCEP N N/A N/A N K 5 490 318 64.90% 382 78.00% 485 316 65.20% 378 77.90% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedCalifornia Avenue Elementary Unified School DistrictSpecial Education Schools (Public)Special Education SchoolN/A N N/A N/A N K 8 13 6 46.20% 10 76.90% 13 6 46.20% 10 76.90% Y 2021-2022 37 68452 126300 San DiegoVista UnifiedVista Visions Academy Unified School DistrictAlternative Schools of ChoiceAlternative School of ChoiceN/A N N/A N/A N K 12 407 251 61.70% 299 73.50% 401 246 61.30% 294 73.30% Y 2021-2022 37 68452 4E+06 San DiegoVista UnifiedVista High Unified School DistrictHigh Schools (Public)TraditionalN/A N N/A N/A N 9 12 2,231 1,356 60.80% 1,597 71.60% 2,205 1,342 60.90% 1,582 71.70% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedRoosevelt Middle Unified School DistrictIntermediate/Middle Schools (Public)TraditionalN/A N N/A N/A N 6 8 785 440 56.10% 540 68.80% 785 440 56.10% 540 68.80% Y 2021-2022 37 68452 114637 San DiegoVista UnifiedVista Magnet Middle School of Technology, Science, and MathUnified School DistrictIntermediate/Middle Schools (Public)TraditionalCEP N N/A N/A N 6 8 822 444 54.00% 551 67.00% 822 444 54.00% 551 67.00% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedBreeze Hill Elementary Unified School DistrictElementary Schools (Public)TraditionalN/A N N/A N/A N K 5 779 405 52.00% 508 65.20% 765 400 52.30% 502 65.60% Y 2021-2022 37 68452 100925 San DiegoVista UnifiedT.H.E Leadership Academy Unified School DistrictElementary Schools (Public)TraditionalN/A N N/A N/A N K 5 593 283 47.70% 384 64.80% 579 275 47.50% 374 64.60% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedMadison Middle Unified School DistrictIntermediate/Middle Schools (Public)TraditionalCEP N N/A N/A N 6 8 975 523 53.60% 625 64.10% 975 523 53.60% 625 64.10% Y 2021-2022 37 68452 4E+06 San DiegoVista UnifiedRancho Buena Vista High Unified School DistrictHigh Schools (Public)TraditionalN/A N N/A N/A N 9 12 2,027 977 48.20% 1,245 61.40% 1,998 964 48.20% 1,229 61.50% Y 2021-2022 37 68452 128223 San DiegoVista UnifiedBella Mente Montessori Academy Unified School DistrictElementary Schools (Public)TraditionalN/A Y 1515 Directly fundedY K 8 424 229 54.00% 254 59.90% 416 224 53.80% 248 59.60% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedMission Meadows Elementary Unified School DistrictElementary Schools (Public)TraditionalN/A N N/A N/A N K 5 485 218 44.90% 275 56.70% 478 216 45.20% 273 57.10% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedMonte Vista Elementary Unified School DistrictElementary Schools (Public)TraditionalN/A N N/A N/A N K 5 465 208 44.70% 261 56.10% 450 202 44.90% 252 56.00% Y 2021-2022 37 68452 4E+06 San DiegoVista UnifiedGuajome Park Academy Charter Unified School DistrictK-12 Schools (Public)TraditionalN/A Y 50 Directly fundedY K 12 1,347 639 47.40% 750 55.70% 1,341 638 47.60% 749 55.90% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedVista Innovation and Design AcademyUnified School DistrictIntermediate/Middle Schools (Public)TraditionalN/A N N/A N/A N 6 8 794 338 42.60% 439 55.30% 794 338 42.60% 439 55.30% Y 2021-2022 37 68452 114264 San DiegoVista UnifiedNorth County Trade Tech High Unified School DistrictHigh Schools (Public)TraditionalN/A Y 884 Directly fundedY 9 12 167 83 49.70% 89 53.30% 160 81 50.60% 87 54.40% Y 2021-2022 37 68452 124917 San DiegoVista UnifiedGuajome Learning Center Unified School DistrictK-12 Schools (Public)TraditionalN/A Y 1351 Directly fundedY K 12 90 41 45.60% 49 54.40% 89 40 44.90% 48 53.90% Y 2021-2022 37 68452 1 San DiegoVista UnifiedNonpublic, Nonsectarian Schools Unified School DistrictN/A N/A N/A N/A N/A N/A N/A N/A N/A 20 9 45.00% 9 45.00% 17 9 52.90% 9 52.90% Y 2021-2022 37 68452 4E+06 San DiegoVista UnifiedVista Adult Transition Center Unified School DistrictSpecial Education Schools (Public)Special Education SchoolN/A N N/A N/A N Adult Adult 115 45 39.10% 56 48.70% 16 7 43.80% 8 50.00% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedCasita Center for Science/Math/TechnologyUnified School DistrictElementary Schools (Public)TraditionalN/A N N/A N/A N K 5 653 192 29.40% 286 43.80% 653 192 29.40% 286 43.80% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedAlamosa Park Elementary Unified School DistrictElementary Schools (Public)TraditionalN/A N N/A N/A N K 5 477 140 29.40% 202 42.30% 468 138 29.50% 199 42.50% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedEmpresa Elementary Unified School DistrictElementary Schools (Public)TraditionalN/A N N/A N/A N K 5 692 182 26.30% 276 39.90% 692 182 26.30% 276 39.90% Y 2021-2022 37 68452 118430 San DiegoVista UnifiedMission Vista High Unified School DistrictAlternative Schools of ChoiceAlternative School of ChoiceN/A N N/A N/A N 9 12 1,658 397 23.90% 628 37.90% 1,625 389 23.90% 614 37.80% Y 2021-2022 37 68452 6E+06 San DiegoVista UnifiedLake Elementary Unified School DistrictElementary Schools (Public)TraditionalN/A N N/A N/A N K 5 698 173 24.80% 237 34.00% 686 172 25.10% 235 34.30% Y Free and Reduced Meal program stats, Highlighted schools are in the project area census tracts School Name District
Type
School
Type IRC Low
Grade
High
Grade
District
Name
Academic
Year
Cou
nty
Cod
e
District
Code
School
Code
County
Name
Attachment D. Free and reduced meal census tracts
05/27/2025
C6

Page 60 of 194 ends

Attachment E:

Project area is noted with red.

EPA IRA Disadvantaged Communities
05/27/2025
C6

Page 61 of 194 ends

16 ATTACHMENT B

Scope of Work

05/27/2025
C6

Page 62 of 194 ends

B-1
N. SANTA FE AVE CORRIDOR LANDSCAPE AND IRRIGATION PROJECT WITH NEW

PEDESTRIAN CROSSING AT WASHINGTON STREET
CIP 8360

SCOPE OF WORK
The Scope of
Work included in the Proposal should include the following tasks:

Task 1 – Project Initiation, Management and Coordination A. Schedule and hold an initial (in person) meeting with City staff and subconsultants to discuss the approach to the project, scope of work, schedule and address any questions or requests for information from the consultant or subconsultants
B. Coordinate the day-to-day activities on the project and manage all subconsultants and coordinate their activities
C. Hold up to six formal (in person) meetings with City staff to develop the design of the project, resolve design issues, discuss staff comments on plans, estimate, and document submittals, discuss progress and address any other issues. It is important that the design of the project is developed in coordination with the City to ensure that the City’s goals and objectives are met.

D. Produce and distribute meeting agendas and minutes.

E. Maintain open and regular communications with City staff and subconsultants.

Deliverables:

Meeting agendas; meeting minutes; progress reports, and project documentation.

Task 2 – Data Collection and Field Review
A. Collect existing as-built plans for street improvements, traffic signal, landscape, sewer, water, and storm drain systems for the project site.

B. Obtain utility maps from utility companies.

C. Conduct a field review to become familiar with the physical layout and features of the project site. Evaluate and inventory existing landscape, trees, irrigation, equipment, meters, points of connection and determine which features can be utilized and integrated in the design to maximize tree canopy and preservation of existing trees. For the pedestrian traffic crossing at Washington Street, evaluate the existing improvements for the integration of proposed traffic signal, sidewalk modifications, ramps, point of connections, electric meter, traffic loops, and appurtenances which includes but not limited to, underground and overhead utilities. Note any features that may need special attention or may present a challenge in the design development or final design of the project.

D. Research Forest Service resources per grant for recommended trees and landscape list. Meet with Public Works Landscape management for project input and maintenance requirements.

Coordinate with City on the appropriate proposed street tree selections.

E. Conduct a study of existing conflicts and determine the best layout for the proposed midblock pedestrian traffic signal at E. Washington Street. See proposed improvements in Attachment A and recently constructed midblock signal per Townsite Complete Street drawings.

Deliverables:

Documentation of all data collected in the tasks above. 05/27/2025
C6

Page 63 of 194 ends

B-2
Task 3 –Design Surveying and Base Map Development
A. Obtain and review existing maps, Records of Survey (ROS), Corner Records (CR), etc. for existing right-of-way / property lines, easements, etc.

B. Establish horizontal control for the project based on City of Vista benchmarks and first order control map, ROS 14023.

C. Notify property owners / tenants with “doorknob” hangers at least two working days prior to entering private property if needed. The format of the notification shall be approved by the City’s Project Manager prior to distribution.

D. Locate and identify existing boundaries and other survey monumentation to establish right-of- way & property line, and to perpetuate monumentation within the limits of work. Show all existing monuments within the project limits on the topographic base map so all monuments can be labeled on the improvement plans to be protected or replaced.

E. Establish the centerline and right-of way for the project streets and depict on the base map. Tie the public right-of-way and topography to NAD ’83 Coordinate system.

F. Develop a base map within the project limits of work and 20 feet beyond the ultimate right-of- way of the project which shows surface features, depicts existing improvements and utilities. For the traffic signal location at E. Washington Street develop base map for 50 feet beyond the intersection in all directions. Limited and localized topography may be required for the proposed ramp and median crossing associated with the pedestrian crossing and proposed tree locations which require curb, gutter and sidewalk modifications.

G. Locate and identify all visible VID water and franchise utility facilities. Identify any water meters used for irrigation.

H. Locate and identify all SDGE meters.

I. Locate and identify all streetlight facilities.

J. Locate and identify all sewer and storm drain facilities. Provide finish surface, top of rim or grate, flowline, and invert elevations and size for all structures, manholes, pipes, cleanouts, and enclosures.

K. Obtain USA mark-out and locate and identify underground utility pipe and conduit locations based on utility mark-outs prior to potholing.

L. Locate and identify other surface features, including:

1. Top of curb (PCR, BC, EC, PCC, etc.)

2. Gutter lip

3. Pedestrian ramps

4. Cross Gutters

5. Structures

6. Trees and large shrubs. Coordinates shall be to the center of the tree or shrub and include tree type and diameter, elevation of tree at trunk base, approximate tree height, surface root and drip line perimeters

7. Driveways

8. Sidewalks include back of sidewalk location.

9. Fences and walls including type and condition

10. Mailboxes including type and condition

11. Steps including type and condition

12. Retaining walls including type (reinforced or unreinforced, footing or no footing) and condition

13. AC paving and dikes

14. Signs

15. Striping and paveme
nt markings

16. Other significant surface features
M. Prepare a digital AutoCAD base map of all the elements. 05/27/2025
C6

Page 64 of 194 ends

B-3
Deliverables:

A digital AutoCAD base map containing all the elements and elevations obtained in the tasks above, and existing utilities and surface features. Provide centerline stations.

Task 4 – Water Quality Technical Report
A. Prepare a Project Determination Checklist using the template provided by the City. The City of Vista has determined that the Urban Runoff Threat Assessment is “high” for all projects.

B. If the project is determined to be a Standard or Priority Project, prepare a Stormwater Quality Management Plan(SWQMP) using the template provided by the City.

C. Prepare Municipal Stormwater Permit documentation in accordance with San Diego Regional Water Quality Control Board Order No. R9-2013-0001/2015-0001, using the City of Vista BMP Design Manual. Determine applicable design requirements. Evaluate potential for any exemptions related to sidewalk projects. Submit report to the City for review and make changes as requested by the City.

D. Incorporate all required hydro-modification improvements and permanent BMP’s into the project design.

Deliverables:

Project Determination Checklist, SWQMP, Water Quality Technical Report, and Design Exhibits.

Task 6 – Preliminary and Final Design
A. Coordinate with other ongoing and planned projects such to ensure compatibility of the proposed improvements with those other projects.

B. Using the AutoCAD base map which includes mapped underground utilities, develop a preliminary horizontal layout of the landscape, hardscape modifications and pedestrian signal improvements. A preliminary striping/signal plan showing lane configuration and traffic loops associated with E. Washington Street shall be submitted for review and acceptance by the City.

Make adjustments as requested by the City.

C. Prepare conceptual landscape exhibits for City Council meetings or workshops, as needed.

D. Coordinate and/or assist with USDA Forest Service grant elements. Represent the City in any periodic update meetings as needed.

E. Identify and label existing features, including survey monuments, utilities, streetlights, and meters.

F. Based on supplemental survey elevations, develop, design and draft the horizontal geometrics and alignments of the project improvements in plan view.

G. Design hydromodification and stormwater treatment improvements based off the recommendations within the Water Quality Technical Report.

H. Call out all the proposed improvements using detailed and distinct construction notes and refer to standard drawings or details shown elsewhere on the plans as appropriate I. Design typical cross sections to reflect the existing conditions and the proposed improvements J. Provide details of improvements such as tree wells, irrigation, planting, sidewalk modifications, points of connection, to clearly show the required construction, to enable a contractor to construct the improvements with minimal, if any, requests for information and change orders. 05/27/2025
C6

Page 65 of 194 ends

B-4
K. Draft Title Sheet and detail sheets containing general notes, special notes, special provisions, typical sections, construction details, etc., similar to other City of Vista projects, using City standard templates adjusted for this project.

L. Prepare traffic signal, striping and signing plans.

M. Prepare landscape, civil, demo, irrigation, planting, BMP, detail and utility plan.

N. Design a schematic erosion control plan with specific erosion control measures and temporary BMPs called out at specific locations where excavation is proposed, similar to other City of Vista projects, using City standard templates adjusted for this project.

O. Submit the plans to the City for review at 60%, 90% and 100% design levels. Depending on the level of completeness of the submitted plans, allow for a minimum of four iterations of comments by the City and corrections or revisions to the plans.

Deliverables:

Preliminary horizontal layout, design plans of the project improvements at the 60%, 90%, and 100% design levels, and bid-ready construction plans signed and sealed by the Engineer of Work.

Task 7 –Utility Coordination
A. Submit preliminary horizontal layout on base map to utility companies and request confirmation that utility facilities are depicted accurately.

B. Submit the preliminary design plans to all utility companies and request a conflict check.

C. Coordinate with utility companies who have utilities in conflict with the proposed improvements.

Obtain pothole information for utility conflicts and adjust locations of facilities to avoid or minimize conflicts if possible. Request relocation of utility facilities where conflicts cannot be avoided. Obtain schedule of relocation design and construction from utility companies.

D. Submit final construction plans signed by the Engineer of Work and City Engineer and confirm that utility companies are designing their relocations.

E. Ensure that the utility companies who have utilities in conflict with the proposed improvements schedule the construction of the relocation of their utilities through their internal procedures.

F. Obtain signatures from VID on the plans if any water facilities are affected by the proposed improvements.

Deliverables:

Copies of correspondence with utility companies and copy of pothole report.

Task 8 –Construction Cost Estimates
A. Using the 60% design plans, develop a preliminary engineer’s estimate of the costs to construct the proposed improvements. The estimate is to include a list of all items of work, including any items not detailed on the 60% plans. Cost information shall include item quantities, unit cost per item and total cost for each item as well as contingencies and total construction cost. Submit the engineer’s estimate to the City for review and make adjustments to the design to keep the project costs within budget.

B. Update the engineer’s estimates at the 90% and 100% design levels to include all items of work and appropriate quantities and contingencies. Submit the engineer’s estimate to the City for review and make adjustments to the design to keep the project costs within budget.

C. Prepare a Final Engineer’s Estimate of Construction Cost, using only the limited number of items of work that will be included in the Bid Schedule and showing no contingencies. 05/27/2025
C6

Page 66 of 194 ends

B-5
Deliverables:

Detailed Engineer’s construction cost estimates at the 60%, 90%, and 100% design stages, and a Final Engineer’s Estimate of Construction Cost.

Task 9 – Construction Support for Design
A. Provide written and graphical responses to questions from bidders related to the project plans during the construction bid phase.

B. Prepare addenda as required during the construction bid phase.

C. Provide other support during the construction bid phase as needed D. Attend the pre-construction meeting
E. Respond to Requests for Information from the construction contractor during the construction phase.

F. Provide other support during the construction phase
Deliverables:

Written responses to questions from bidders, written addenda, written responses to RFI’s from the Contractor, and other construction support documentation.

Task 10 – As-Built Plans and Project Close-out
A. Upon completion of construction and using Change Orders and red line plans marked by the City inspector and construction contractor, draft as-built plans for the project. Incorporate all changes to the plans electronically with all necessary revision notations B. Submit a plan set signed by the Engineer of Work to the City with an electronic copy of the final as-built drawings, for review and approval by the City inspector and City Engineer.

C. Submit an electronic copy of all the files developed during the project, including research, survey, geotechnical, utility coordination, design, plans, estimates and all other project documentation.

Deliverables:

Final signed as-built plans and electronic copy of the project files.

Task 11 – Conduct Quality Control and Quality Assurance The Consultant shall have a quality control & quality assurance plan in effect during the entire time work is being performed under the Agreement. The Quality control plan shall establish a process whereby plans and other project documents are independently checked, corrected, and back checked prior to submittal to the City.

The Consultant is to maintain neat and organized project files.

Deliverables:

Copy of QA/QC Plan to be followed during the project, and quality control and quality assurance evidenced in the quality of all plans and documents submitted to the City. City may request to view internal plan check comments to verify QA/QC.
05/27/2025
C6

Page 67 of 194 ends

17 ATTACHMENT C

City of Vista Standard Consulting Agreement
05/27/2025
C6

Page 68 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 1 of 9 NAMEX [51960-2] 00051960 4

CONTRACT FOR PROFESSIONAL SERVICES

TYPE OF SERVICES
THIS “CONTRACT” is entered into by and between the “Parties” as of ___________________ (“Contract Date”).

1.0 THE “PARTIES”
The “City”:

CITY OF VISTA, a chartered municipal
corporation
200 Civic Center Drive
Vista, CA 92084

Working Contact: workingname
Billing Contact: billingname
The “Contractor”

NAMEX, statusx
Address1
Address2

Contact: contactname

2.0 BASIC TERMS

2.1 The “ Services” to be performed by Contractor are set forth in the Request for Proposals attached as Exhibit A.

2.2 The “ Required License” for the Services is: type.

2.3 Contractor, an entity holding the Required License, desires to enter into this “Contract” with City for the Services.

2.4 The “ Project” for which the Services are required is described in Exhibit A.

2.5 Contractor has submitted to City a Proposal to perform the Services dated proposaldate (“Exhibit B”).

2.6 The “ Contract Ceiling Price” is: pricex

2.7 Any references in Exhibit A or Exhibit B to “Consultant” shall mean Contractor for the purposes of this Contract.

3.0 CONTRACT TERM

3.1 This Contract shall take effect as of the Contract Date.

3.2 This Contract shall be in effect for xx calendar months (“ Term”) from the Contract Date. The Term may be extended at the City’s option for an additional yy months, in increments of City’s choice, for a maximum Term of zz months from the Contract Date.

3.3 City may terminate this Contract upon 30-days’ written notice to Contractor. In such event, or upon request of City, Contractor shall assemble all City documents in the Contractor's possession, put them in order for proper filing and closing, and deliver the documents to City. In the event of termination, Contractor shall be paid for work performed to the termination date. City shall make the final determination as to the portion of tasks completed and the compensation to be paid.
05/27/2025
C6

Page 69 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 2 of 9 NAMEX [51960-2] 00051960 4

4.0 SCOPE
Contractor shall perform all Services including, but not limited to, the furnishing of all tools, equipment, materials, software, and supplies, and for furnishing all transportation, services, including fuel, power and water, essential communications, and the performance of all labor, work, or other operations, as may be required from time to time, in accordance with Exhibit A and Exhibit B. In the event of a conflict between the provisions of Exhibit A and Exhibit B, the provisions of Exhibit A shall control.

5.0 COMPENSATION

5.1 City shall pay Contractor for the Services to be performed as set forth in Exhibit B.

5.2 An invoice for payment shall be submitted in a form satisfactory to City. At a minimum, the invoice shall include: the purchase order number, the work order number, a description of the work performed, and a total amount.

5.3 Changes in, additions to, or deductions from the Services, including increases or decreases in any item or portion of the Services, shall be set forth in a written change order executed by City and by the Contractor which shall specify:

5.3.1 The changes, additions, and deductions to be made.

5.3.2 The increase or decrease in compensation due the Contractor, if any.

5.3.3 Adjustment in the time of completion, if any.

5.4 Contract Ceiling Price

5.4.1 In no event shall City be liable for paying more than the Contract Ceiling Price for Contractor's services rendered under this contract.

5.4.2 If it becomes foreseeable that Contractor will need to perform services such that the cumulative total of costs to City will exceed the maximum permitted by this Contract, any such cost overrun will be handled pursuant to the change order procedure in Vista Municipal Code Chapter 3.08. City and Contractor recognize that City lacks authority to exceed the cost ceiling without the express authorization of the City Council. If the maximum cost to City for this Contract is exceeded unexpectedly, payment shall be made as mutually agreeable and disputes shall be handled pursuant to this Contract, but work shall cease as soon as is reasonably feasible once the cost ceiling plus allowable change orders, if any, is exceeded.

5.5 Except as provided in Exhibit B, Contractor shall not be reimbursed for any expenses incurred in rendering services under this Contract. 05/27/2025
C6

Page 70 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 3 of 9 NAMEX [51960-2] 00051960 4

6.0 CONTRACT DOCUMENTS
The Contract comprises the following documents including all additions, deletions, modifications, and appendices and all addenda setting forth any modifications or interpretations of any these documents: Documents required under Exhibits A–E.

7.0 TIME FOR COMPLETION AND COMMENCEMENT OF SERVICES
All Services under the Contract must be completed in compliance with the schedule in Exhibit A.

8.0 STANDARD OF PERFORMANCE

8.1 Contractor represents and warrants that it has the training, qualifications, experience, and facilities necessary to properly perform the Services required under this Contract in a thorough, competent, and professional manner. At all times Contractor shall faithfully, competently and to the best of its ability, experience, and talent, perform all services described herein. In meeting its obligations under this Contract, Contractor shall employ, at a minimum, generally accepted standards and practices utilized by persons engaged in providing services similar to those required of Contractor under this Contract.

8.2 Contractor shall keep itself informed of and comply with all applicable federal, state, and local laws, statutes, codes, ordinances, regulations, and rules in effect during the Term of this Contract. Contractor shall obtain any and all licenses, permits and authorizations necessary to perform the services set forth in this Contract, including any business licenses required by City. Neither City, nor any elected or appointed boards, officers, officials, employees, or agents of City, shall be liable, at law or in equity, as a result of any failure of Contractor to comply with this Section.

9.0 CONTRACTOR’S STATUS; CONTRACTOR’S EMPLOYEES

9.1 Contractor shall perform the services provided for herein in Contractor's own way as an independent contractor and in pursuit of Contractor's independent calling. Contractor is not to be considered an employee of City, nor shall any employees of Contractor be considered employees of City, for any purpose. Contractor shall be under the direction and control of City staff only as to the results to be accomplished. This Contract is not intended to create the relationship of partnership, joint venture, or association between City and Contractor.

9.2 Contractor represents and warrants that all professional services required under this Contract shall be provided by a person or persons duly licensed by the State of California to provide those types of services.

9.3 Neither Contractor, nor any of Contractor's officers, employees, or agents, shall obtain any rights to retirement, health care or any other benefits which may otherwise accrue to City’s employees. Contractor expressly waives any claim Contractor may have to any such rights.

9.4 Contractor is aware of the requirements of the Immigration Reform and Control Act of 1986 and shall comply with those requirements, including, but not limited to, verifying the eligibility for employment of all of Contractor’s officers, employees, agents, and subcontractors that are included in this Contract.

05/27/2025
C6

Page 71 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 4 of 9 NAMEX [51960-2] 00051960 4

9.5 The payment made to Contractor pursuant to this Contract shall be the full and complete compensation to which Contractor and Contractor’s officers, employees, agents, and subcontractors are entitled for performance of any work under this contract. Neither Contractor nor Contractor’s officers or employees are entitled to any salary or wages, or retirement, health, leave or other fringe benefits applicable to employees of the City. City will not make any federal or state tax withholdings on behalf of Contractor. City shall not be required to pay any workers' compensation insurance on behalf of Contractor.

9.6 Contractor agrees to defend and indemnify City for any obligation, claim, suit, or demand for tax, retirement contribution including any contribution to the Public Employees Retirement System (PERS), social security, salary or wages, overtime payment, or workers' compensation payment which City may be required to make on behalf of Contractor or any employee of Contractor, or any employee of Contractor construed to be an employee of City, for work done under this contract. This is a continuing obligation that survives the termination of this Contract.

10.0 CIVIL RIGHTS

10.1 Contractor agrees to comply with Title VII of the Civil Rights Act of 1964, as amended, the California Fair Employment Practices Act, the Americans with Disabilities Act of 1990, any other applicable federal and state laws and regulations hereinafter enacted.

10.2 Contractor shall not knowingly deny an opportunity or benefit, discriminate against or harass, any employee or applicant for employment on account of the person’s race, color, ethnicity, national origin, ancestry, religion, creed, veteran status, physical disability, mental disability, medical condition, marital status, sex, sexual orientation, age, or other status protected from workplace discrimination by state or federal law.

10.3 Contractor shall not knowingly give preferential treatment to any applicant for employment on the basis of race, color, ethnicity, national origin, ancestry, religion, creed, physical disability, mental disability, medical condition, marital status, sex, or sexual orientation.

10.4 This section shall be interpreted in a manner that is consistent with the California and United States Constitutions and applicable state and federal statutes governing workplace discrimination. The terms used in this section shall have the same meaning as defined in state statutes governing the same subject matter.

10.5 Nothing in this section shall be interpreted as prohibiting bona fide occupational qualifications consistent with applicable state and federal law and reasonably necessary to the normal operation of Contractor. Nothing in this section shall be interpreted as prohibiting regulations and policies to prevent nepotism or conflicts of interest.

10.6 Nothing in this Section shall be interpreted as prohibiting action taken to establish or maintain eligibility for any federal program, where ineligibility would result in a loss of federal funds to City.

10.7 To the fullest extent permitted by law and without limitation by the other provisions of this Contract relating to indemnification and insurance, Contractor shall also indemnify, defend, and hold harmless City, and its directors, officers, employees, and agents from and against all liability (including without limitation all claims, damages, penalties, fines, and judgments, associated investigation and administrative expenses, and defense costs, 05/27/2025
C6

Page 72 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 5 of 9 NAMEX [51960-2] 00051960 4
including but not limited to reasonable attorneys' fees, court costs, and costs of alternative dispute resolution) resulting from any claim of discrimination or harassment, including but not limited to sexual harassment, arising from the conduct of the Contractor or any of the Contractor’s officers, employees, agents, licensees, or subcontractors. In the event of a discrimination or harassment complaint against any employee, agent, licensee, or subcontractors of Contractor or its subcontractors, Contractor shall take immediate and appropriate action in response to such complaint, including, but not limited to termination or appropriate discipline of any responsible employee, agent, licensee, or subcontractors. The provisions of this Section survive completion of the services or termination of the Contract.

11.0 CONTROL OF SERVICES
Each Party shall appoint a representative who shall have the authority to represent and act for that Party (“Representative”). Any written or verbal directions or requests of City's Representative delivered to the Contractor’s Representative shall have the same force and effect as if delivered to the Contractor. The Contractor's Representative shall have the authority to sign any change order, coordinate the work of all subcontractors and make other decisions pertaining to the Contract.

12.0 ASSIGNMENT AND SUBCONSULTING

12.1 Neither this Contract nor any interest herein may be transferred, assigned, conveyed, hypothecated, or encumbered voluntarily or by operation of law, whether for the benefit of creditors or otherwise, without the prior written approval of the City. Transfers restricted hereunder shall include the transfer to any person or group of persons acting in concert of more than twenty-five (25%) of the present ownership and/or control of Contractor, taking all transfers into account on a cumulative basis. In the event of any such unapproved transfer, including any bankruptcy proceeding, this Contract shall be void. No approved transfer shall release the Contractor or any surety of Contractor of any liability hereunder without the express consent of City.

12.2 Contractor shall be fully responsible to the City for any acts and omissions of Contractor's subcontractor, including persons either directly or indirectly employed by subcontractor, in the event Contractor subcontracts any of the work to be performed under this contract. Contractor's responsibility under this paragraph shall be identical to Contractor's liability for acts and omissions of Contractor and employees of the Contractor. Nothing contained in this Contract shall create any contractual relationship between City and any subcontractor of Contractor, but Contractor shall bind every subcontractor and every subcontractor of a subcontractor by the terms of this contract applicable to Contractor's work, unless such change, omission, or addition is approved in advance in writing by the City Manager or the City Manager’s designee. All subcontractors are subject to the prior written review and approval of the City Manager or the City Manager’s designee.

13.0 LICENSES
If a license of any kind, which term is intended to include evidence of registration, is required of Contractor, its employees, agents, or subcontractors by federal, state, or local law, Contractor warrants that such license has been obtained, is valid and in good standing, and that any required bond has been posted in accordance with all applicable laws and regulations. 05/27/2025
C6

Page 73 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 6 of 9 NAMEX [51960-2] 00051960 4

14.0 FINANCIAL RECORDS

14.1 Contractor shall maintain any and all documents, ledgers, books of account, invoices, vouchers, canceled checks, or records demonstrating or relating to Contractor’s performance of services pursuant to this Contract or evidencing or relating to expenditures and disbursements charged to City pursuant to this Contract. Any and all such documents or records shall be maintained in accordance with generally accepted accounting principles and shall be sufficiently complete and detailed so as to permit an accurate evaluation of the services provided by Contractor pursuant to this Contract. Any and all such documents or records shall be maintained for three years from the date of execution of this Contract and to the extent required by laws relating to audits of public agencies and their expenditures. It is expressly understood and agreed that the provisions of this Section will survive termination of this Contract.

14.2 Any and all records or documents required to be maintained pursuant to this Section shall be made available for inspection, audit and copying, at any time during regular business hours, upon request by City or its designated representative. Copies of such documents or records shall be provided directly to the City for inspection, audit and copying when it is practical to do so; otherwise, unless an alternative is mutually agreed upon, such documents and records shall be made available at Contractor's address indicated for receipt of notices in this Contract or the primary location from which services are rendered, whichever is closer.

15.0 OWNERSHIP OF DOCUMENTS
Upon delivery, the work product, including without limitation, all original reports, writings, recordings, drawings, files, and detailed calculations developed under this contract are the property of City. Contractor agrees that all copyrights which arise from creation of the work pursuant to this contract shall be vested in City and waives and relinquishes all claims to copyright or other intellectual property rights in favor of City. City acknowledges that its use of the work product is limited to the purposes contemplated by the scope of Services and that Contractor makes no representation of the suitability of the work product for use in or application to circumstances not contemplated by the scope of Services.

16.0 CONFIDENTIALITY

16.1 Contractor shall treat all information obt ained from City in the performance of this Contract as confidential and proprietary to City. Contractor shall treat all records and work product prepared or maintained by Contractor in the performance of this Contract as confidential.

16.2 Contractor agrees that it will not use any information obtained as a consequence of the performance of work for any purpose other than fulfillment of Contractor’s scope of Services. Contractor will not disclose any information prepared for City, or obtained from City or obtained as a consequence of the performance of work to any person other than City, or its own employees, agents or subcontractors who have a need for the information for the performance of Services under this Contract unless such disclosure is specifically authorized in writing by City.

16.3 Contractor’s obligations under this paragraph shall survive the termination of this Contract.
05/27/2025
C6

Page 74 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 7 of 9 NAMEX [51960-2] 00051960 4

17.0 CONFLICT OF INTEREST REQUIREMENT
Contractor agrees that, to the extent applicable, it shall comply with and be bound by all laws and regulations deriving from the relationship of the Contractor to the City, including the Political Reform Act (Government Codes Section 87100 et seq.) Chapters 2.32 or 2.33 of the Vista Municipal Code, the Community Redevelopment Act (Health & Safety Code 33000 et seq.) and all regulations promulgated thereunder (collectively “Conflict Laws”). As a condition precedent to the formation of this Contract, Contractor warrants and covenants that it is adequately informed regarding the obligations and duties imposed by the Conflict Laws and that to the best of Contractor's knowledge and belief, there exists no conflict of interest (under the laws) that would disqualify the Contractor from participation in any decisions arising out of the performance of this Contract. Prior to commencement of any work in the performance of this Contract, Contractor shall comply with any applicable requirements of Chapter 2.32 of the Vista Municipal Code, including any requirement to file a financial disclosure statement with the City Clerk.

Contractor further agrees that no employee, agent or subcontractor for Contractor shall perform any work for the City pursuant to this Contract which will violate the Conflict Laws.

18.0 PROHIBITION OF FINANCIAL INTEREST BY CITY OFFICIAL Contractor warrants and covenants to City that no City Official has or will have any current or future financial interest in this Contract as of the date approved, nor shall Contractor promise, offer, or enter into any written, oral or implied Contract, to provide any financial interest or remuneration of any kind or manner to any City official with respect to this Contract. For purposes of this Section, the term “City Official” shall mean and include any elected or appointed officer of City, any employee of City, or any spouse or financial dependent of a City official or employee. A violation of this provision shall render this Contract null and void and Contractor shall be subject to restitution of all fees or money paid or earned under this Contract.

19.0 DUTY OF INDEMNIFICATION

19.1 To the fullest extent permitted by law, Contractor shall (1) immediately defend and (2) indemnify City, and its directors, officers, and employees from and against all liabilities regardless of nature or type that arise out of, pertain to, or relate to the negligence, recklessness, or willful misconduct of Contractor, or its employees, agents, or subcontractors.

Liabilities subject to the duties to defend and indemnify include, without limitation, all claims, losses, damages, penalties, fines, and judgments; associated investigation and administrative expenses; defense costs, including but not limited to reasonable attorneys’ fees; court costs; and costs of alternative dispute resolution (“Duty of Indemnification”). Contractor’s obligations to both defend and indemnify apply unless it is finally adjudicated that the liability or liabilities, in whole or in part, do not arise out of, pertain to, or relate to the negligence, recklessness, or willful misconduct of Contractor or its employees, agents, or subcontractors. Defense counsel shall be approved by City.

19.2 The review, acceptance or approval of Contractor’s work or work product by any indemnified party shall not affect, relieve, or reduce Contractor’s indemnification or defense obligations. This Section survives completion of the services or the termination of this contract.

The provisions of this Section are not limited by and do not affect the provisions of this contract relating to insurance.

19.3 Contractor’s costs of defense shall not exceed Contractor’s proportionate percentage of fault as adjudicated by a court of law, as required by California Civil Code section 2782.8.
05/27/2025
C6

Page 75 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 8 of 9 NAMEX [51960-2] 00051960 4

20.0 INSURANCE AND BONDS
Contractor shall comply with the insurance provisions set forth in Exhibit C.

21.0 SERVICE OF NOTICE

21.1 Any notice, which either Party may desire to give to the other Party, must be in writing and may be given by personal delivery to the Party’s Representative or by overnight courier service to the Party’s address set forth in Section 1.0. Notice may also be given by mailing it by registered or certified mail, return receipt requested, to the other Party at the address set forth in Section 1.0. Any notice given by mail will be deemed given 48 hours after such notice is deposited in the United States mail, addressed as provided with postage fully prepaid.

21.2 A Party may change its address by giving notice as provided above, and the changed address shall thereafter be deemed to be the address set forth in Section 1.0.

22.0 SPECIAL PROVISIONS
This Contract is subject to, and Contractor shall comply with, the special provisions referenced in Exhibit E, if any.

23.0 EXHIBITS
All documents referenced as exhibits in this Contract, or referenced in an exhibit to this Contract, are incorporated herein.

24.0 APPLICABLE LAW, VENUE
This Contract shall be construed and enforced under the laws of the State of California. If any action is commenced by any Party to this Contract, such action shall be filed in a court of competent jurisdiction within the County of San Diego, California.

25.0 COUNTERPARTS; ELECTRONIC SIGNATURES; ELECTRONIC DELIVERY This Agreement may be executed in separate counterparts, none of which need contain the signatures of both Parties, and each of which, when so executed, shall be deemed an original and all together shall constitute and be one of the same instrument. The Parties agree that this Agreement, whether executed by electronic signature, digital signature, or constituting a scanned or electronically reproduced copy or image of this Agreement bearing the signatures of the Parties, will be deemed an original and will represent competent evidence of the execution, terms and existence of this Agreement notwithstanding the failure or inability to produce an original executed Agreement or counterpart thereof, and without the requirement that the unavailability of such original executed Agreement or counterpart thereof first be proven.

Further, the exchange of this entire executed Agreement (and/or such exhibit(s) or document(s)) that is in photostatic or portable document format (.pdf) form by electronic mail or by another electronic means shall be considered original(s) and shall constitute effective execution and delivery of the original(s).

26.0 MODIFICATIONS
This Contract contains the entire agreement, between the Parties and supersedes all prior negotiations, discussions, obligations, and rights of the Parties in respect of each other regarding the subject matter of this Contract. There is no other written or oral understanding 05/27/2025
C6

Page 76 of 194 ends

Professional Services (Non-Construction) (RFP)(NPW) 9 of 9 NAMEX [51960-2] 00051960 4
between the Parties. No modification, amendment or alteration of this Contract shall be valid unless it is in writing and signed by all Parties.

[Continued on page 9.]

27.0 EXECUTION
IN WITNESS WHEREOF; the Parties hereto have executed this Contract as of the Contract Date.

“City”

CITY OF VISTA, a chartered municipal
corporation

By:

JOHN CONLEY, CITY MANAGER
JOHN B. FRANKLIN, MAYOR

ATTEST:

KATHY VALDEZ, CITY CLERK

By:

APPROVED AS TO FORM:

W

ALTER CHUNG, CITY ATTORNEY

By:

RISK MANAGEMENT REVIEW:

A

NALISA HOLBROOK, RISK MANAGER

By:

“Contractor”

NAMEX, statusx

By:

Name/Title

By:

Name/Title

05/27/2025
C6

Page 77 of 194 ends

00051960 4 Exhibit B
4911-4088-0703, v. 2

EXHIBIT B
CONTRACTOR’S PROPOSAL

05/27/2025
C6

Page 78 of 194 ends

CITY OF VISTA

NORTH SANTA FE
Avenue Corridor
Proposal for Professional Services for
Landscape and Irrigation Project
with New Pedestrian Crossing
at Washington Street
CIP No. 8360
05/27/2025
C6

Page 79 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
a
Table of Contents

1. Cover Letter.....................................................................................................................................1

2. Statement of Qualifications

..............................................................................................................3

3. Work Plan

.........................................................................................................................................i

4. Fee Proposal

..................................................................................................................................xii

5. Detailed Work Schedule.................................................................................................................xiii

6. Comments on the Standard Consultant Agreement

.......................................................................xiv

7. Work Samples

............................................................................................................................... xv 05/27/2025
C6

Page 80 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
401 B Street, Suite 600
San Diego, CA 92101
TEL 619.234.9411
City of Vista  RSCASAND006639.2025
1 1. COVER LETTER
March 21, 2024
Erin Adams, Administrative Programs Manager
City of Vista, Department of Engineering
200 Civic Center Drive, 1st Floor
Vista, CA 92084
RE: Proposal for Professional Services for North Santa Fe Avenue Corridor Landscape and Irrigation Project With New Pedestrian Crossing at Washington Street, CIP No. 8360 Dear Ms. Adams and Members of the Selection Committee:

The City of Vista (City) has been awarded the USDA Forest Grant funding that will help fund the installation of trees, replacement of the aging irrigation system along North Santa Fe Avenue and a new pedestrian signalized crossing at Washington Street. This project aligns with the Jusitice40 initiative, State Forest Action Plans, the Ten-Year Urban Forestry Action Plan as well as the City of Vista’s Climate Action Plan. The project will enhance the city’s urban tree canopy, provide numerous environmental benefits, improve health and well-being for the residents, promote environmental justice for underserved and disadvantaged communities, and aligns with the City’s sustainability goals. To successfully achieve the project’s objectives within budget and on schedule, the City requires a consultant team with the technical expertise, creativity, passion and experience designing in utility-dense environment. Kimley-Horn possess these qualities and will help the City succeed in this endeavor. As you review our proposal, please consider the following key bene fi
ts our team will bring:

We Are Your One-Stop Shop. Kimley-Horn takes pride in the fact that we are a multidisciplinary firm. Our San Diego office staf
fs over 140 employees, including civil engineers and landscape architects. We have given careful consideration to the composition of our team, identifying the most quali
fi
ed personnel with recent, relevant experience to be available to work with you. Our dedicated project manager Mark Araujo, PE will lead our exceptional team and will also be your day-to-day contact. Mark will be supported by Randall Kopff, PLA, CLARB—our landscape architect and deputy project manager who brings over 24 years of experience working with public sector clients—and Joe Shultz, PE, TE, who’s known industry wide for his attention to detail on pedestrian safety and transportation projects.. In addition to our in-house staff, we have partnered with CE&LST (survey) and Underground Solutions, Inc. (potholing), two subconsultants we have regularly and successfully work with over numerous years and who also have experience working on projects within the City of Vista. “Working with Randall and Joe over the years has been an incredible experience. Our synergy and communication are second to none, and we share a commitment to the highest standards of quality. Together, we consistently strive to deliver outstanding work for our clients, always pushing the boundaries of excellent client service.”– Mark Araujo, PE Proven Communication. One of Kimley-Horn’s greatest strengths is our commitment to open and effective communication throughout the life of a project. We provide regular updates during all phases, ensuring City staff always have an accurate understanding of progress and are promptly informed of any potential issues or conflicts. This level of communication allows us to adapt to changing conditions or new challenges that may arise. However, our commitment to communication extends beyond just the City staff. Our team members, having collaborated on numerous projects, have already established effective communication procedures among ourselves. This enables our various disciplines within our team to ef fi
ciently coordinate
work across all phases, minimizing potential disruptions to the workflow.

Risk Management A project involving the installation of approximately 125 trees, a new irrigation system over 1.3 miles, and a traf
fi
c signal in a densely built environment with numerous existing utilities—several of which are likely unknown— demands a team with exceptional attention to detail. This level of precision is crucial to identify potential conflicts early on to mitigate risks, ensuring the project’s success and minimizing disruptions. We understand that it is imperative to complete this project in a timely manner to meet the grant funding timelines and we are ready to hit the ground running. Our in-house multidisciplinary team will methodically tackle all project challenges. 05/27/2025
C6

Page 81 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
*As Vice President, Megan is authorized to
sign a contract on behalf of Kimley-Horn.

Kimley-Horn acknowledges the receipt of Q&A
responses released by March 12, 2025.

City of Vista  RSCASAND006639.2025
2 Kimley-Horn is excited about this opportunity to partner with the City on another very important project that will bring great social and environmental bene
fi
t to the community. Thank you for your time and consideration of our team, should you have any questions about our proposal, please contact project manager Mark Araujo, PE directly at 619.744.0177, by email at [email protected], or at the address listed above.

Sincerely,
KIMLEY-HORN AND ASSOCIATES, INC.

Mark Araujo, PE
Megan Ulery
, PE, LEED AP*
Project Manager/Associate
Principal-in-Charge/Vice President
05/27/2025
C6

Page 82 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
3 2. STATEMENT OF QUALIFICATIONS
Firm Profile
Kimley-Horn is a full-service engineering, planning, and environmental consulting fi
rm providing service to both public and private sector clients nationwide. Since our founding in 1967, Kimley-Horn has grown from a small group of traf fi
c
engineers and transportation planners to a
fi
rm of more than 8,400 employees
across 141 of
fi
ces nationwide, including 14 in California. Today we are one of the largest engineering, planning, and environmental consulting fi
rms in the United
States. This year, Engineering New-Record has ranked Kimley-Horn 10th of the top 500 U.S. design firms. Our continued growth and stability over the past 58 years is the direct result of our commitment to integrity and dedicated to providing quality services to our clients.

Service Areas
Kimley-Horn is a multidisciplinary firm and can offer a wide range of services in-house.

Our project manager, Mark Araujo, PE, and our technical staff are well versed in each aspect of this project. Our in-house civil, traf fi
c, and landscape
architecture teams have a long history of providing relevant roadway, traf fi
c
engineering, and landscaping services to various clients across California. Below are summaries of our experience in the services expected to be needed for this project:

ROADWAY DESIGN
Civil engineering forms the backbone of our qualifications to serve as your consulting engineer. At Kimley-Horn, we have experienced professionals in roadwa
y, utility engineering, and traf
fi
c engineering, among others. Our engineers have developed plans, speci fi
cations,
and estimates (PS&E) for more than 4,000 miles of roadway, including neighborhood streets, rural roads, interstate highways, state highways, highway interchange structures, and urban arterials. Roadway design and planning is one of the mainstays of our fi
rm’s professional practice. We
are well-equipped to address all related aspects of roadway design projects, including route corridor studies, schematic design, environmental and utility assessments, constructability, construction sequencing, and fi
nal PS&E. The City will bene
fi
t from our team’s extensive experience and
creativity, which allow us to effectively navigate the complexities of designing around crowded underground utilities and storm drain facilities. Our prompt and frequent responses ensure that any issues are swiftly addressed, providing the City with peace of mind and con fi
dence in the project’s
timely and successful completion. Additionally, our ef
fi
cient approach and understanding of grant funding will ensure that the grant objectives are met within the required timelines.

TRAFFIC SIGNAL DESIGN
Kimley-Horn offers complete traffic engineering and design services in-house. We have completed thousands of traffic engineering and opera
tions projects both locally and across the U.S., ranging from major area wide signal systems involving hundreds of intersections to single intersection safety audits, designs, and analyses. Traf fi
c operations, traf
fi
c safety, and levels of service are key components in evaluating roadway networks and identifying areas for improvement as well as those warranting further study. We utilize the latest analytical tools including the Highway Capacity Manual (HCM), Synchro, SimTraf
fi
c, CORSIM©, and VISSIM, to perform technical operations analyses.

LANDSCAPE ARCHITECTURE
From the revitalization of community parks to the design and implementation of downtown streetscapes, we have successfully planned and implemented scores of landscape architecture projects. Kimley-Horn has a well-earned reputation for combining creative ideas, technical excellence, and client collaboration, resulting in dynamic projects that blend into their environments and become a part of the area they inhabit. Our landscape architects have a diverse range of experience from corridor plans and downtown streetscape programs to parks and recreation planning. As metropolitan urban areas continue to grow, urban design, streetscape design, and landscape architecture have become integral components of roadway and transportation system designs and infrastructure improvements in general. We understand the intricacies involved in installing landscaping and irrigation along a corridor with crowded underground facilities. Our team is well-equipped at navigating these challenges by working closely with our civil partners, ensuring that the placement of trees and irrigation systems are carefully planned to avoid conflicts with existing utilities. Our meticulous approach minimizes disruptions and ensures the successful integration of new elements into the built environment.
05/27/2025
C6

Page 83 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
4 IRRIGATION DESIGN
Water conservation is a focal issue in designing and maintaining landscapes in California. We recognize the need for proper irrigation design that utilizes the most recent technology in controllers, irrigation heads, micro-irrigation, and bubbler systems. Our irrigation specialists provide professional irrigation design integrated with water management solutions to meet the speci fi
c site and environmental
conditions of your project sites. Our goal is to develop a cost-effective irrigation system design that meets the accepted standards and maintenance requirements for the City. Our staff will help check that water conservation, water management, and irrigation design are wholly addressed—with a sensitivity to the environmental conditions of each site.

UTILITY COORDINATION
Every project is unique and presents its own special design challenges. However, the most frequent challenge faced on numerous projects in built-out environments are related to existing utilities. The North Santa Fe Avenue corridor ampli fi
es this challenge with the
crowded underground infrastructure. Like every challenge, Kimley-Horn believes in: (1) meticulous fi
eldwork and site assessments to document the
existing facilities, (2) using every resource available to draft the existing facilities including as-builts and utility provided facility maps, (3) drawing all utility lines and features to their true size in our plans to aid in identifying conflicts early in the design phase; (4) potholing potential conflict locations, which gives a better understanding of the precise locations and size of the existing lines; and (5) extensive coordination with the various utility companies to relocate, adjust or abandon some facilities. Our team has worked with all the utility providers on countless local projects and understand their process, which will be a bene
fi
t to project.

Team Organization
We have organized our team in a manner that delineates clear roles and reporting relationships. The organizational chart below shows the names, roles, and classi
fi
cations of key personnel and project team relationships. Our team will be led by project manager Mark Araujo, PE, who will also serve as our day-to-day contact with the City and will plan, direct, and coordinate the work for this project. Our team will serve the City from our San Diego of
fi
ce, which currently staffs 145 engineers, planners, designers, and support staff.

Civil
Casey Jumanan, PE, QSD/P
Utility Coordination
Josh Thompson, EIT
Survey

CE & LST
Potholing
Underground Solutions
Landscape
Corey Cameron, PLA
Claire Morris
Certified Arborist
Joe Cogswell, PLA, ISA CA
Traffic
Joe Shultz, PE, TE
Zachary McFann, PE, TE
Drainage
Heidi McMacken, PE, CFM
Principal-in-Charge
Megan Ulery, PE, LEED AP
QC/QA/Constructability
Kirk Ammerman, PE
Project Manager
Mark Araujo, PE

CITY OF
VISTA
Deputy Project Manager
Randall Kopff, PLA, CLARB
Bold = Key Staff
05/27/2025
C6

Page 84 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
5 Staff Plan and Summary of Qualifications
Kimley-Horn will provide specialized service for this project in the areas of civil design, traffic signal design, landscape architecture, irrigation design,
and utility engineering and coordination. Our team has a thorough understanding of the local laws, ordinances, regulations, policies, requirements, and permitting procedures for the region. In addition, we have reviewed the grant awarded to the City and understand the requirements that need to be met and maintained to remain compliant with the grant funding. We have also partnered with two subconsultants, CE&LST and Underground Solutions Inc., to provide survey and potholing services. We have provided brief pro fi
les on our subconsultants’
capabilities below:

CE&LST
CE&LST is a private land surveying and civil engineering small business located in Solana Beach. They have extensive surveying experience working in the City under subcontract for construction surveying and staking. They are very familiar with the City mapping and benchmark network and have surveyed throughout the city on several private land development projects for over two decades.

Underground Solutions, Inc.

Underground Solutions, Inc. (USI) has been in the locating and vacuum excavation utility potholing service business since 2003. USI has been a
fi
rm believer in the use of air/vacuum excavation for positive utility identi
fi
cation. Most importantly, because air is a compressible gas, when used to break-up soil to discover a buried utility it flows around the conduit, pipe or cable when in direct contact versus cutting into it.

Key Staff Resumes
Key staff resumes can be found on the following pages.
05/27/2025
C6

Page 85 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
R-1

MARK ARAUJO, PE
Project Manager
Mark is a highly accomplished civil engineer with roughly a decade and a half of experience delivering impactful transportation and public works projects. His extensive expertise spans a diverse range of project types, from multimodal roadways and transit systems to site development and park enhancements, guiding each project from initial concept through to successful completion. He is adept at managing large, multidisciplinary teams, along with navigating the intricate permitting processes required by agencies such as Caltrans, NCTD, MTS, CPUC, etc.

Mark’s deep experience also includes providing innovative design solutions, value engineering, and hands-on construction phase services for projects focused on green streets, ADA universal design, bus rapid transit stations and managed lanes, pedestrian rail crossings, roundabouts, bicycle facilities, utility design, parks, and stormwater management systems. His unwavering commitment to delivering high-quality projects on time and within budget has earned him a reputation for reliability and excellence.

Known for his strong communication skills, Mark consistently fosters collaborative relationships with project stakeholders, ensuring seamless project execution. His approach to design is driven by a deep commitment to equity and inclusion, ensuring that every project is not only functional but also addresses the diverse needs of the community it serves. Mark’s work stands as a testament to thoughtful, people-centered design that leaves a lasting positive impact on the public infrastructure landscape.

Relevant Experience
• City of V ista, Emerald Drive Complete Streets Corridor Improvements, Vista, CA – Project Manager •
City of Oceanside,
On-Call Traffic Engineering Services, Oceanside, CA – Contract Manager •
City of Oceanside,
Coast Highway Roundabouts and Corridor Design, Oceanside, CA – Project Manager •
City of San Marcos,
A&E On-Call, San Marcos, CA – Contract Manager
•
City of Encinitas,
As-Needed Civil Engineering Services, Encinitas, CA – Contract Manager •
City of Menifee,
On-Call Professional Engineering/Public Works Services, Menifee, CA – Contract Manager •
City of Oceanside,
RDO and Mesa Drive Traffic Signal Replacement, Oceanside, CA – Project Manager •
City of Oceanside,
Carey Road and Canyon Drive New Traffic Signal, Oceanside, CA – Project Manager •
City of Oceanside,
Inland Rail Trail, Oceanside, CA – Project Civil Advisor •
City of Carlsbad,
El Camino Real and Cannon Rd Improvements, Carlsbad, CA – Contract Manager •
City of San Marcos,
San Marcos Boulevard Pavement Rehabilitation and Traffic Signal Replacement Project, San Marcos, CA – Project Manager
•
City of San Marcos,
Rancho Santa Fe Road Pavement Rehabilitation and Traffic Signal Modification Project, San Marcos, CA – Project Manager
•
City of Escondido,
Grand Avenue Vision Corridor Improvements Phase I & II, Escondido, CA – Project Manager •
San Diego Association of Go
vernments (SANDAG), Imperial Avenue Bikeway, San Diego, CA – Project Manager •
City of Encinitas,
Glen Park ADA Improvements, Encinitas, CA – Project Manager •
City of San Marcos,
Annual Slurry and Pavements Maintenance Projects, San Marcos, CA – Project Manager •
City of La Mesa,
North Spring Street New Railroad Crossing Improvements, La Mesa, CA – Project Manager •
City of Oceanside,
Oceanside, Mission Avenue Streetscape, Oceanside, CA – Project Engineer •
City of San Marcos,
Bradley Park Bike Park, San Marcos, CA – Project Manager

PROFESSIONAL

CREDENTIALS
» Bachelor of Science,
Civil Engineering, San
Diego State University
» Professional Eng
ineer
in California #85614
» American Public
W
orks Association
(APWA), Member and
North County County
Committee Support
05/27/2025
C6

Page 86 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
R-2

MEGAN ULERY, PE, LEED AP
Principal-in-Charge
Megan has over 20 years of ATP , complete streets, and park project experience in Southern California. She routinely provides contract management, project management, and civil engineering services for municipalities and cities through multi-disciplinary projects with numerous stakeholders. Megan’s ability to partner early with the community and agency stakeholders provides the long term camaraderie and excitement on a project that spans multiple years, from planning to implementation. She strategically pursues projects that align with her passions, availability, and extensive ATP experience to remain focused and deliver what has been promised to the stakeholders and community. Her well-rounded design and project management experience, attention to detail, and constructability oversight will be a benefit to this project.

Relevant Experience
• City of V ista, Emerald Drive Complete Streets Corridor Improvements, Vista, CA – QC/QA Manager •
SAND
AG, North Park Mid-City Bikeways: Georgia/Meade and Landis Corridors, San Diego, CA – Project Manager
•
SAND
AG, Uptown Bikeways: 4th and 5th Avenues, San Diego, CA – Project Manager •
SAND
AG, Howard Bikeway, San Diego, CA – Project Manager
•
SAND
AG, Robinson Bikeway, San Diego, CA – Project Manager
•
SAND
AG, Border to Bayshore Bikeway, San Diego, CA – Project Engineer •
County of San Diego,
Various FY 2020-21 Pedestrian Ramps, San Diego County, CA – Project Manager •
County of San Diego,
Gillespie Field El Cajon Air Center Expansion, El Cajon, CA – Project Engineer •
San Diego County Regional Airport Authority (SDCRAA),
New Terminal 1 Off-Airport Roadway Improvements, San Diego, CA – Project Manager
•
San Diego Regional Airport Authority
, Sassafras Street Improvements, San Diego, CA – Project Manager •
City of Salinas,
Main Street Complete Streets Project, Salinas, CA – Project Engineer •
San Diego,
Mira Mesa Community Park Phase II Improvements, San Diego, CA – Project Engineer •
City of San Diego,
City Heights Aquatic Center and ADA Upgrades, San Diego, CA – Project Engineer •
City of Oceanside,
El Corazon Aquatic Center, Oceanside, CA – Project Engineer •
City of Escondido,
Washington Park Skate Spot, Escondido, CA – Project Engineer •
City of San Diego,
J Street Mini-Park, San Diego, CA – Project Engineer
•
San Diego Unified School District,
Marston Middle School Modernization & Joint Use Field, San Diego, CA – Project Engineer •
City of San Diego,
Father Joe’s Homeless Shelter Relocation, San Diego, CA – Project Engineer •
Meridian Development,
Millenia Park, Chula Vista, CA – Project Engineer
•
City of El Centro,
Plank Park, El Centro, CA – Project Engineer

PROFESSIONAL

CREDENTIALS
» Bachelor of Science
with Honors,
Civil
and Environmental
Engineering, University
of Iowa
» Professional Civil
Eng
ineer in California
#73385
» Leadership in Energ
y
and Environmental
Design Accredited
Professional
05/27/2025
C6

Page 87 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
R-3

KIRK AMMERMAN, PE
QC/QA Manager
Kirk has nearly 37 years of experience over a broad range of civil engineering practice, including, but not limited to, design, project and construction management, regulatory compliance, public works operations, and public contact and outreach. In addition, Kirk is knowledgeable in pertinent local, state, and federal rules, regulations, and laws. Prior to joining Kimley-Horn, Kirk was a Principal Civil Engineer with the City of Chula Vista and, at various times, managed the following sections/divisions: Construction Inspection Services; Stormwater Compliance; Design and Project Delivery; Pavement Management; Land Development and Permitting; Landscape Architecture; and Surveying.

Relevant Experience
• City of V ista, Emerald Drive Complete Streets Corridor Improvements, Vista, CA – Constructability •
San Diego Zoo Saf
ari Park, Wastewater Treatment Plant Expansion and Pipeline Upgrades, San Diego, CA – Project Engineer •
City of Rialto,
Frisbie Park Sewer Lift Station Design, Rialto, CA – QC/QA Reviewer •
San Bernardino County
, County Service Area (CSA) 64 Well Pedestal Adjustment, San Bernardino, CA – QA/QC Reviewer •
City of Escondido,
Sewer Outfall Lining, Encinitas, CA – Project Manager
•
Caltrans,
City of Solana Beach Inverted Siphon Relocation, Solana Beach, CA – Project Engineer •
Caltrans,
San Elijo Joint Powers Authority, 12” and 16” Recycled Wastewater Line Relocations, Encinitas, CA – Project Engineer •
City of Oceanside,
Downtown Water and Sewer Pipelines Replacement, Phase 2, Oceanside, CA – Principal-in-Charge •
City of Chula V
ista, Salt Creek Interceptor Sewer, Chula Vista, CA – Project Manager and Construction Manager (with City of Chula Vista, prior to Kimley-Horn)
•
City of Chula V
ista, G Street Sewage Lift Station Rehabilitation, Chula Vista, CA – QA/QC Reviewer, Constructability Task Lead, Construction Phase Support Services
•
W
aterman Industrial, Relocation of 54” Raw Sewage and 36” Recycled Wastewater Transmission Main Relocations, San Bernardino, CA – Project Manager
•
SAND
AG, South Bay Bus Rapid Transit, Chula Vista, CA – Project Manager •
City of San Marcos,
On-Call General Engineering and Architectural Services, San Marcos, CA – QC/QA Manager •
County of San Diego,
As-Needed Engineering, Project Management, and Land Surveying Services, San Diego, CA – QC/QA Manager •
City of Chula V
ista, Civil On-Call, Chula Vista, CA – Contract Manager •
City of National City
, Community Corridors, National City, CA – Project Engineer

PROFESSIONAL

CREDENTIALS
» Bachelor of Science,
Civil Engineering, San
Diego State University
» Professional Eng
ineer
in California #46482
05/27/2025
C6

Page 88 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
R-4

RANDALL KOPFF, PLA, CLARB
Deputy Project Manager; Landscape Architect
Randall’s 24 years of professional experience have encompassed a wide variety of landscape architectural, planning, and graphic services on projects throughout the U.S.

His skills include site inventory/analysis, master planning, design development, graphic presentations, 3-D modeling, project management, and detailed technical drawings. Randall utilizes his diverse project background to work closely with individual clients to interpret public input and ensure that the proper vision has been achieved throughout the planning and design implementation processes.

Relevant Experience
• City of V ista, Emerald Drive Complete Streets Project, Vista, CA – Landscape Architect •
City of Salinas,
Main Street Complete Streets Project, Salinas, CA – Project Manager •
City of Salinas,
Bardin Road Safe Route to School Enhancement (Improvements), Salinas, CA – Landscape Architect
•
City of Salinas,
Downtown Vibrancy Plan, Salinas, CA – Landscape Architect •
SAND
AG, North Park Mid-City Bikeways: Georgia/Meade and Landis Corridors, San Diego, CA – Landscape Architect
•
City of Marina,
Imjin Parkway Widening Project, Marina, CA – Landscape Architect •
City of Monterey
, North Fremont Street Bike and Pedestrian Access, and Safety Improvements, Monterey, CA – Landscape Architect •
City of Burlingame,
California Drive Roundabout Project, Burlingame, CA – Landscape Architect •
City of El Monte,
Ramona Boulevard at Valley Boulevard Intersection Improvement Project, El Monte, CA – Landscape Architect •
City of Lincoln,
Engineering Design Services on the East Joiner Parkway Widening Project, Lincoln, CA – Landscape Architect •
City of National City Signage and W
ayfinding Plan, National City, CA – Project Manager
•
Cities of Sonora and Stockton,
Washington Downtown Transit & Accessibility Project, Sonora, CA – Landscape Architect •
SAND
AG, Uptown Bikeway: 4th & 5th Avenues, San Diego, CA – Landscape Architect •
NVT
A, Vine Trail Coalition, Napa Valley Vine Trail, Calistoga to St. Helena, CA – Landscape Architect •
City of Escondido,
Grand Avenue Vision Corridor Improvements Phases I and II, Escondido, CA – Landscape Architect •
Sen Elijo Joint P
owers Authority, Multi-use Trail, Encinitas, CA – Landscape Architect

PROFESSIONAL

CREDENTIALS
» Bachelor of
Science Landsca
pe
Architecture, Ohio
State University
» Professional
Landsca
pe Architect in
California #6633
» Council of Landsca
pe
Architectural
Registration Boards
#40708
» Calif
ornia Park and
Recreation Society,
Member
05/27/2025
C6

Page 89 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
R-5

JOE SHULTZ, PE, TE
Traffic
Joe has 14 years of civil engineering experience, largely focused on transportation and traffic projects that include roadway and intersection designs, traffic signal and interconnect, traffic control and construction staging, and signing and striping. He has prepared traffic impact reports (Level of Service [LOS] and Vehicle Miles Traveled [VMT]), access evaluations, circulation studies for school drop-off/pick-up operations, and other transportation planning for more than 20 California agencies. He has performed numerous tasks for local public agencies, including improvement plan and study reviews, traffic signal warrants, all-way stop evaluations, traffic calming, and speed zone updates. Joe has successfully delivered several site development and roadway design projects from the initial transportation planning stage, through design and construction. Joe is connected to local agencies and consultants through his service to the ITE San Diego Section, where he currently serves as the President. He is known in the industry for his high quality of deliverables and commitment to client service. He is also proficient in several software packages such as AutoCAD, MicroStation, Synchro, and Vistro.

Relevant Experience
• City of V ista, Emerald Drive Complete Streets Project, Vista, CA – Traf fi c Engineer •
SAND
AG, North Park Mid-City Bikeway, San Diego, CA – Traf
fi
c Engineer
•
SAND
AG, Howard Bikeways, San Diego, CA – Traf
fi
c Engineer
•
SAND
AG, Central Avenue Bikeway, San Diego, CA – Traf
fi
c Engineer
•
SAND
AG, North Park Mid-City Bikeway, San Diego, CA – Traf
fi
c Engineer
•
City of Escondido,
Grand Avenue Visions Project, Escondido, CA – Traf
fi
c Engineer
•
SAND
AG, Imperial Avenue Bikeway, San Diego, CA – Traf
fi
c Engineer
•
SAND
AG, Uptown Bikeways, San Diego, CA – Project Engineer
•
City of La Mesa,
North Spring Street Improvements, La Mesa, CA – Team Member •
County of San Diego,
Otay Mesa Road Widening, San Diego, CA – Project Engineer •
City of Menifee,
Garbani Road Interchange, Menifee, CA – Project Analyst •
City of Los Angeles,
Department of Recreation and Parks, Griffith Park Safety and Mobility Active Transportation Project, Los Angeles, CA – Project Engineer
•
City of Oceanside,
On-Call Traffic Engineering, Oceanside, CA – Task Manager •
City of La Mesa,
On-Call Traffic Engineering, La Mesa, CA – Contract Manager •
City of National City
, On-Call Traffic Engineering, National City, CA – Task Manager •
City of Menifee,
On-Call Traffic Engineering, Oceanside, CA – Task Manager •
City of San Marcos,
A&E On-Call, San Marcos, CA – Traf
fi
c Engineer

PROFESSIONAL

CREDENTIALS
» Bachelor of Science,
Civil Engineering, San
Diego State University
» Professional Eng
ineer
in California #84152
» Professional
Traf
fi
c
Engineer in California
#3142
» Institute of
T
ransportation
Engineers (ITE), 2025
San Diego Section
President
05/27/2025
C6

Page 90 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
R-6
THOMAS C. MUELLER
Potholing
Thomas has over 30 years of hands-on general engineering contracting experience in the counties of San Diego, Orange, LA, Riverside and San Bernardino area with emphasis on safety and production. He has familiarity with various types of utility installation, soil conditions, excavation equipment, traffic control and safe practices and experience installing utilities is found to be invaluable in determining locations and depths of existing utilities when potholing and locating. `
Relevant Experience
• Eastern Municipal W ater District, As-Needed On-Call, Riverside, CA – Potholing •
Riverside County Flood Control,
As-Needed On-Call, Riverside County, CA – Potholing
•
City of Carlsbad,
As-Needed On-Call, Carlsbad, CA – Potholing
•
V
ista Irrigation District, As-Needed On-Call, Vista, CA – Potholing •
Helix W
ater, As-Needed On-Call, San Diego, CA – Potholing

JOEL VALDOVINOS, PE
Survey
Joel offers comprehensive experience in the preparation of preliminary documents survey plats, tentative maps and development estimates, as well as construction plans such as grading, improvement and site plans. He has added his construction experience to the firm, including to but not limited to concrete, asphalt work. Joel has served as design manager and project engineer of various engineering projects, serving federal, educational, municipalities and private residential/commercial clients. His 30 years of experience includes subdivision design, new road design and road widening, earthwork quantities, cost estimates, hydrologic and hydraulic analysis, lot layout, drainage, sewer and water system design, plot plan preparation, erosion control plans, preparation and determination of source control pollution prevention measures.

Relevant Experience
• City of V ista, Emerald Drive Complete Streets, City of Vista, CA – Project Manager of survey for the Kimley-Horn team corridor improvements.
•
City of Chula V
ista, Public Improvements to Sunbow II Community, Chula Vista, CA – Project Engineer of 260-lot layout community in Chula Vista. Work included the design of approximately 2 miles of public local roads, approximately including right of ways, alignments, pro fi
les,
median and curb and sidewalks designs, 8,600 LF of storm drain facilities sizes ranging from 18” RCP to 60” RCP . Public wet utilities included 10,100 LF of 8 inch sewer, and 10,400 LF of 8 inch waterline. Preparation of erosion control plans, and permit processing. Other tasks included earth work, cost estimates and hydrologic and hydraulic analysis and coordination with SDG&E. •
City of San Diego,
New Road Improvements to Carmel Valley Road, San Diego, CA – Project engineer for prepara-tion of construction documents for 120’ right of way public road from SR-125 to Paci fi
c Highlands Ranch Unit 11, approximately ¾ of a mile. Work also included coordination to realign a 36-inch potable water main, design of 12-inch reclaimed water, 8-inch sewer, 10-inch potable water, and storm drain facilities that varied in size from 18-inch RCP to 60-inch RCP . Other tasks included coordination with various utility companies.

PROFESSIONAL

CREDENTIALS
» Bachelor of Science,
Civil Engineering, San
Diego State University
» Professional Eng
ineer
in California #65256
05/27/2025
C6

Page 91 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
6 Similar Project Experience
City of Vista, Emerald Drive Complete Street Improvements, Vista, CA Emerald Drive is the main roadway through neighborhoods in the cities of Vista and Oceanside and the vehicles on this street are moving at speeds that create safety hazards and make it dif
fi
cult for people trying to cross the street to access the nearby amenities. This project will transform this community by shifting the focus away from a car-centric roadway and focusing on the mobility, circulation, and safety by implementing bicycle and pedestrian improvements with traf
fi
c calming features. Kimley-Horn is providing specialized services for this project in the areas of roundabout design; ADA universal design; landscape architecture; lighting and electrical design; utility and storm drain design; hydrology and hydraulics; water quality; traf
fi
c engineering and operations; and more. The Emerald Drive Corridor presented a complex challenge due to its densely packed above and below ground utility infrastructure. Our team meticulously navigated these constraints, ensuring the project’s objectives were met without compromising on quality or ef
fi
ciency. By proactively collaborating with the City, we identi fi
ed potential obstacles early on and proposed viable
solutions, facilitating a smoother design process and ultimately delivering a robust and well-integrated infrastructure plan.

S Kimley-Horn’
s Role/Level of Involvement: Prime (82%)
p Subconsultants/Level of Involvement:

Tory Walker (7%); CE&LST (7%); Allied Geotechnical
(3%); Underground Solutions (1%)
P Design Dates:
2024 – Present
J Construction Date
s: January 2026
💲 Bid Costs vs.

Construction Costs: $15,000,000 vs TBD
U Client Reference:

Matthew Atteberry, PE, CIP Engineering Division Manager, City of Vista • 760.643.5410 • [email protected] City of Escondido, Grand Avenue Vision Corridor Improvements Phases I and II, Escondido, CA Kimley-Horn assisted the City with public outreach by soliciting feedback from the community and stakeholders, resulting in the development of the Grand Avenue Vision Plan. The Grand Avenue Vision Plan aims to improve the economic vitality of Grand Avenue by creating a pedestrian-friendly and aesthetically appealing corridor. Once the plan was approved by City Council, Kimley-Horn assisted the City with successfully applying and securing grant funds for the
fi
rst phase of the project through SANDAG’s Smart Growth Incentive Program. Kimley-Horn worked with the City of Escondido on the PH I & II
fi
nal design of the Grand Avenue Vision project with one additional phase remaining. The corridor includes three roundabouts at Broadway, Maple St, and Kalmia St, streetscape improvements, public art features, narrowing of Grand Avenue to one lane in each direction and using the excess width to create wider, 20-foot sidewalks, diagonal parking on one side of the street resulting in increased parking, EMERALD DRIVE | COMPLETE STREET CORRIDOR

TYPICAL TRAFFIC CIRCLE
LEGEND
SIDEWALK, TYP . LOW WATER-USE, NATIVE LANDSCAPING, TYP .SHARED BIKE LANE, TYP . BOULDERS, TYP . PROPOSED STREET TREE, TYP . DECORATIVE PAVING, TYP .1 1 4
65 3
2 42 653

PLACEMAKING

ILLUSTRATIVE ONLY - CONCEPT SUBJECT TO CHANGE DURING FINAL DESIGN Relevance to North Santa Fe:

Kimley-Horn has experience working
with the City on this complete, utility
dense corridor. Close coordination
has been instrumental to keep the
project moving forward.
05/27/2025
C6

Page 92 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
7 traffic signal modifications, installation of new landscape, irrigation and hardscape improvements, new decorative street lighting and avoidance of existing subsurface utility infrastructure.

Kimley-Horn also worked with NCTD to realign the Breeze bus route off of Grand Avenue. To meet construction windows and to minimize impacts to businesses during construction, we assisted the City with construction phasing and early procurement of decorative street light poles and accessories prior to bidding the project, cutting the long lead time on the light poles. Construction of PH II is anticipated to be completed in April 2025.

S Kimley-Horn’
s Role/Level of Involvement: Prime (85%)
p Subconsultants/Level of Involvement:

Aguirre & Associates, Inc. (2%); C Below, Subsurface
Imaging, Inc. (1%); HELIX Environmental Planning, Inc. (Cultural 5%); Selbert Perkins Design (7%) P Design Dates:
2019 – 2021 (Phase 1) • 2023 – Ongoing (Phase 2)
J Construction Dates:

Phase 1 Completed in 2022 • Construction to start in 2024 (Phase 2) 💲 Bid Costs vs.

Construction Costs: $1,368,000 vs. $994,776.00 (Phase 1) • TBD vs. $9,260,000 (Phase 2)
U Client Reference:

Jonathan Schauble, PE, City Engineer, City of Escondido • 760.839.4072 • [email protected] San Elijo Joint Powers Authority, Multi-Use Path, Encinitas , CA Kimley-Horn was selected by the San Elijo Joint Powers Authority (SEJPA) and Caltrans District 11 (Caltrans) to provide civil engineering, environmental services, and construction-phase services for major drainage improvements, water quality improvements, a lighted regional shared-use trail within the San Elijo Water Reclamation Facility (“SEWRF”) property that joins with Class I Bikeway improvements within Interstate-5 at the northeast corner of the SEWRF property, and public improvements along the SEWRF Manchester Avenue frontage, including curb and gutter, sidewalk, street-level enhanced trail crossing, Class 2 bike lanes, a new traf
fi
c signal, and landscape and irrigation. The traf
fi
c signal design
required meticulous existing utility mapping and potholing to due to the sheer volume of underground utilities including a large drainage box culvert. Construction and installation of the traf
fi
c signal resulted in no
fi
eld adjustments.

S Kimley-Horn’
s Role/Level of Involvement: Prime (90%)
p Subconsultants/Level of Involvement
: Nasland (10%)
P Design Dat
es: 2018 – 2019
J Construction Dat
es: 2020 – 2021
💲 Bid Costs vs.

Construction Costs: $5,000,000 vs $5,200,000
U Client Reference:

Mike Thorton, General Manager, SEJPA • 760.753.6203 • [email protected] Relevance to North Santa
Fe: Installation of roughly 50 new
trees, new irrigation system that
maximized the use of existing
power and water sources, and over
36 decorative streetlights over
four blocks along Grand Avenue in
downtown Escondido.

Relevance to North Santa Fe:

Installation of new traf
fi
c signal to
increase pedestrian safety with
numerous underground utilities and
a large box culvert that required a
substantial number of potholes to
get it right the
fi
rst time.
05/27/2025
C6

Page 93 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
8 Financial Responsibility of Firm
Kimley-Horn and Associates, Inc. is a full-service engineering and consulting firm with approximately 8,400 employees and 141 offices in 29 states, the District of Columbia,
and Puerto Rico. The Company had 2023 revenues of $2.4 billion. Kimley-Horn has been in business since 1967. We are fi
nancially strong, and we are committed to our continued fi
nancial health. As of December 31, 2023, the Company had total assets of $1.6 billion and stockholder’s equity of approximately $314 million. In addition to the fi
nancial resources noted, Kimley-Horn also has an untapped $125 million line of credit available for short-term cash flow needs. The Company’s cash flow continues to be very strong. We maintain a disciplined focus on business fundamentals, operate the
fi
rm conservatively, and our internal controls and business standards are designed to keep our foundation strong.

Kimley-Horn uses two institutional lenders, Wells Fargo and PNC. If necessary, reference information can be obtained from the following contacts:

Michael Pugsley
Senior Vice President
Wells Fargo Bank, N.A.
150 Fayetteville Street, Suite 600
PO Box 3008
Raleigh, NC 27601
(919) 881-6469
Lesley Wilson
SVP , Relationship Manager
The PNC Financial Services Group
301 Fayetteville Street, 21st Floor
Raleigh, NC 27601
(919) 788-7573
For any questions regarding Kimley-Horn’s
fi
nancial status, please contact Lindsey Balltzglier, Controller, at (919) 678-4141.

05/27/2025
C6

Page 94 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
i

3. WORK PLAN
Project Understanding
We understand that the City received a USDA Forest Service grant to plant 125 trees in the median and along both sides of a 1.3 mile stretch of North Santa Fe Avenue from Vista Village Drive to West Bobier Drive. Additional City funding will be used to design and install a new midblock pedestrian crossing at East Washington Street and North Santa Fe Avenue intersection. This mid-block crossing will improve the pedestrian connection to and from the Vista Transit Center, mitigating pedestrians hazardously crossing the median at the left turn pocket in the northbound direction where there is an opening in the median.

The proposed project will remove, replace, expand and/or upgrade the existing, aging irrigation systems for the existing landscaping and proposed trees. Trees will be carefully selected using the US Forest Service resources which will also meet the City’s standards. Coordination with the City’s Project Manager and the Public Works Landscape Manager will be critical and exercised early in the design process to get consensus and alignment. We understand that modi
fi
cations to the existing median hardscape, sidewalks, landscape and irrigation will be required to achieve the goals of the grant. We will be mindful to minimize impacts to private property and maximize the preservation of mature landscaping and healthy trees. Additionally, our design will take into consideration constructability, construction costs, and long-term maintenance costs.

PROCESS
1 Research and identify existing utilities through data collection and survey 2 Locate and assess existing irrigation infrastructure
3 Review and assess condition and location of existing trees 4 Identify locations for additional trees and tree wells 5 Identify conflicts with existing facilities and pothole 6 Bring new irrigation lines to proposed trees by a navigating complex existing utility network and connecting drainage from tree wells where feasible.
15 2
4 455
3 6
Before After
05/27/2025
C6

Page 95 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
ii
We know that the project corridor is crowded with above and underground utilities including major subsurface drainage and sewer facilities. With this in mind, the placement of trees, proposed irrigation infrastructure, the mid-block crossing and traf fi
c signals will be meticulously assessed by
our experienced team. Our detailed inventory and
fi
eld analysis will include careful surveying,
fi
eld veri
fi
cations, strategic potholing and construction
risk and tolerance assessment. This will allow us to identify existing facilities we can reuse to reduce construction cost and waste.

Project Management Approach
Quality Control/Quality Assurance (QC/QA)
Since our founding, Kimley-Horn has aggressively pursued a commitment to quality for every task, deliverable, and service we provide. Recognizing the importance of careful quality control, Kimley-Horn developed a QC/QA manual that every project manager is required to know and use. We certify that our procedures result in high-quality services that satisfy your needs. There will be no learning curve relative to quality for our team. For this project, Kirk Ammerman, PE will provide quality control and assurance as well as constructability inputs by working with the project team programmatically for adherence to the City’s preferred design. Our QC/QA approach is based on the philosophy that:

Schedule/Budget Control
Kimley-Horn understands the importance of meeting the City’s schedule and is committed to completing this project on or ahead of schedule.

Our con
fi
dence in being able to meet the City’s timelines is attributed to our stringent approach to schedule control. We understand that schedule control must begin with a clear understanding of the scope of services and budget as well as the subsequent preparation of a detailed schedule that includes milestone completion dates, critical path items, and risks for interim deliverables. We maintain a detailed, integrated Management Information System (MIS), designed primarily to focus on schedule control. MIS tracks both effort and performance by recording time spent and percent of projects completed. Twice monthly, MIS produces a Project Effort Report, which shows the actual effort expended by task. This internal control allows us to make any timely adjustments reasonably necessary to maintain project schedules.

Budget control is achieved through two independent processing systems integrated into the MIS, providing a complete fi
nancial and reporting
overview of each individual task as well as the entire project. Our project managers receive detailed status reports twice a month but can also access the system and obtain real-time information on an ongoing basis. This level of tracking controls task budgets, allowing us to keep our clients fully informed of all administrative aspects of each task at a moment’s notice.

Workload Allocation
The individual members of our project team were selected using two criteria: (1) their experience with related projects, and (2) their availability to assume major technical responsibilities within this contract timeframe. In order to con fi
rm our team member’s availability, Kimley-Horn uses a
proactive management system known as “castaheads” to detail every project’s personnel needs and determine each staff person’s availability. This system forecasts our workload over a six-month period and helps to avoid work overload and shortfalls for each of fi
ce and discipline. Castaheads
help us con
fi
rm suf
fi
cient staff is available to meet your needs. By continuously matching project needs with staff availability, our castaheads system is an accurate tool for keeping our projects on schedule. Based on a review of our castaheads, our team members are readily available to serve you and are in an excellent position to commit themselves to delivering the scope of services outlined in the RFP .

Our selected multidisciplinary in-house team of Civil Engineers and Landscape Architects are excited and prepared to provide their expertise in helping the City achieve the enhancement of the social and environmental landscape of this underserved and disadvantaged community.

ACHIEVED
Through adequate planning,
coordination, supervision,
and technical direction

SECURED
Through careful surveillance of
work activities by parties not
involved in the initial efforts

CONTROLLED
By assigning a manager to
evaluate all work flow
and procedures

VERIFIED
Through independent
reviews by qualified staff

KIMLEY-HORN QUALITY CONTROL IS
05/27/2025
C6

Page 96 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
iii
Communication
Kimley-Horn’s professionals are experienced in both small- and large-scale projects that demand close coordination among multiple stakeholders. Our experience has shown that there really is no such thing as “over-communication.” Effective communication begins with listening to our client’s needs and objectives for each project. We mitigate and avoid potential issues by regularly con fi
rming a shared project understanding among the client’s staff and our project teams. We often use the following communications protocol, which we have employed successfully on numerous projects:
•
Kick-of
f meeting to establish the project team’s understanding of the client’s needs and objectives •
W
eekly and Bi-weekly meetings between the design team (with client participation, as needed) to discuss progress, schedule, and design issues •
Ongoing electronic communica
tion with our clients and involved subconsultants. Our
fi
rm is competent with several virtual communication
platforms, including Microsoft Teams, which we are regularly using to conduct meetings and presentations, in addition to in-person meetings for key project milestones.
•
Our communica
tion will go beyond the immediate team by including coordination with Vista Irrigation District, Vista Uni fi
ed School District, USDA
Forest Service, NCTD, SDG&E and other utility providers.

Project Approach and Scope of Work
 T ASK 1 – PROJECT INITIATION, MANAGEMENT AND COORDINATION Kimley-Horn will complete project management, coordination, and invoicing administration for up to eight (8) months during the design phase and six (6) months during the construction phase. Kimley-Horn will coordinate with the City during the life of the project up to the effort identi fi
ed in the
fee proposal. This could consist of phone calls and/or site and of fi
ce meetings to discuss speci
fi
c project related items. Kimley-Horn estimates up to
six (6) in-person and six (6) virtual meetings with City Staff for the duration of the design phase of the project. It is assumed that each meeting will be one (1) hour and require up to one (1) hour of preparation and will have up to two (2) Kimley-Horn team members in attendance.

Kimley-Horn will attend one (1) kick-off meeting with the City to discuss the project parameters, project considerations, schedule, and budget. The City shall provide direction on key design intent and site constraints, issues prior to starting the design process.

Kimley-Horn will provide prevailing wage monitoring and compliance in accordance with the City’s Labor Compliance Monitoring Program.

Deliverables:

Meeting a gendas/ minutes (PDF Format)
Prog
ress reports (PDF Format)
Project documenta
tion (PDF Format)
Castaheads: Project Workload Planning

JAN FEB MAR

JUNMAYAPR
6 MONTHS
Proactive resource planning
▶ Forecast upcoming project delivera
bles and milestones
▶ Evalua
te team availability to support future deliverables
1 AND 3 MONTHS
Review workload and assess current project needs
▶ Identify immedia
te project deliverables and milestones
▶ Evalua
te simultaneous workload needs
▶ Alloca
te staff availability to support project deliverables
WEEKLY
Address immediate project needs and weekly milestones
05/27/2025
C6

Page 97 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
iv
 T ASK 2 – DATA COLLECTION AND FIELD REVIEW
Task 2.1: Review Records, Base Mapping and Field Verification Kimley-Horn will review record drawings and other readily available documents provided by the City and/or utility providers within the project limits.

A utility base
fi
le in AutoCAD will be created to map existing wet and dry utilities based on the readily available information provided. Known utility types, sizes, materials, and as-built drawing numbers will be referenced and distributed to the design team. Utility research extents will be limited to the con
fi
nes of the project boundary as described in the project understanding.

Up to two (2) Kimley-Horn staff will perform two (2)
fi
eld visits to document existing
fi
eld conditions. Field notes and pictures will be taken
to supplement design and document discrepancies. Discrepancies will be corrected as reasonably necessary. Field veri fi
cation will include
documentation of visible above ground utilities (manholes, valve-cans, water meters, irrigation equipment, and other at grade-structures). Field work will also include evaluation and inventory of existing landscape, trees, irrigation, equipment, meters, and points of connection to determine which features can be utilized and integrated in the design to maximize the tree canopy and preservation of existing trees.

Deliverables:

W et and Dry Utility Base Map (AutoCAD 2024).

Facility Ma
ps obtained from Utility Providers (available upon request).

Utility noti fi cation letters and responses (available upon request).

Field notes,
sketches, and photographs (upon request).

Task 2.2: Pothole Existing Utilities
Kimley-Horn will prepare a pothole exhibit identifying utilities within the project footprint that may conflict with the proposed landscape and irrigation improvements, and traf
fi
c signal poles and equipment. This task will be performed in conjunction with Task 5 and Task 6.

Upon the City’s approval of pothole exhibit, Kimley-Horn will contract with Underground Solution, Inc (USI) to pothole the agreed upon locations (up to 30 potholes). USI will obtain USA mark-outs and locate and identify underground utility pipes and conduit locations based on the utility mark-outs prior to potholing. USI will prepare a pothole report identifying the utility type, size, material, and depth from top of pavement. Potholed utilities will be adjusted to reflect accurate
fi
eld conditions prior to submittal of
fi
nal utility base
fi
le.

Deliverables:

Pothole Exhibit (PDF Forma t) Pothole Da ta Report (PDF Format) Task 2.3: Forest Service Resources
Kimley-Horn will utilize the grant documentation provided by the City to research the recommended trees and landscape list provided by the Forest Service. Additionally, Kimley-Horn will meet, virtually, with the City’s Public Works Landscape Manager for input on plant selection and future maintenance concerns. Utilizing this information, Kimley-Horn will develop a plant palette showing the name and image of each plant proposed for the project.

Deliverables:

Plant Palette and Results of Findings (PDF Forma
t)
Task 2.4: Inventory and Assessment of Mid-Block Crossing Location For the pedestrian traffic crossing at E. Washington Street, Kimley-Horn will evaluate the existing improvements for the integration of proposed traf
fi
c signal, sidewalk modi
fi
cations, curb ramps, point of connections, electric meter, traf fi
c loops, and appurtenances which includes but
not limited to, underground and overhead utilities. Note any features that may need special attention or may present a challenge in the design development or
fi
nal design of the project.

Deliverables:

Preliminar
y Layout of Signal Equipment, Curb Ramp and Passageway (PDF Format) 05/27/2025
C6

Page 98 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
v
 T ASK 3 –DESIGN SURVEYING AND BASE MAP DEVELOPMENT
Task 3.1: Topographic Survey and Boundary Mapping
The Kimley-Horn team will perform field and flown topographic surveys within the project location described in the project understanding. The scope assumes up to ten (10) pre-construction and post-construction corner record of surve y and
fi
ling with the County will be completed as part
of this scope of work.

The
fi
eld surveys at the intersection identi
fi
ed will be as follows:
•
Obtain and review existing ma
ps, Records of Survey (ROS), Corner Records (CR), etc. for existing right-of-way/property lines, easements. •
Esta
blish horizontal control for the project based on City of Vista benchmarks and fi
rst order control map, ROS 14023.
•
Notify property owners/tenants with
“doorknob” hangers at least two working days prior to entering private property if needed. The format of the noti
fi
cation shall be provided by the City’s Project Manager prior to development and distribution. Up to 20 door knobs have been budgeted for the project.
•
Loca
te and identify existing boundaries and other survey monumentation to establish right-of-way & property line, and to perpetuate monumentation within the limits of work. Show all existing monuments within the project limits on the topographic base map so all monuments can be labeled on the improvement plans to be protected or replaced.

Up to eight (8) pre-construction and post-construction corner records of surve y and
fi
ling with the County.
•
Esta
blish the construction centerline and right-of way for the project streets and depict on the base map. Tie the public right-of-way and topography to NAD ’83 Coordinate system.
•
Develop a base ma
p within the project limits of work and 20 feet beyond the ultimate right-of-way of the project which shows surface features, depicts existing improvements and utilities.

For the traf
fi
c signal location at E. Washington Street the base map will extend 50 feet beyond the intersection in all directions. Limited and localized topography may be required for the proposed ramp and median crossing associated with the pedestrian crossing and proposed tree locations which require curb, gutter and sidewalk modi
fi
cations.
•
Loca
te and identify all visible VID water and franchise utility facilities. Identify any water meters used for irrigation. •
Loca
te and identify all SDGE meters.
•
Loca
te and identify all streetlight facilities.
•
Loca
te and identify all sewer and storm drain facilities. Provide fi
nish surface, top of rim or grate, flowline, and invert elevations and size for all structures, manholes, pipes, cleanouts, and enclosures.

Up to twenty (20) g
ravity structures will be dipped at the inverts.
•
Loca
te and identify other surface features, including:

T
op of curb (PCR, BC, EC, PCC, etc.)
Gutter lip
Pedestrian ramps
Cross Gutters
Corners of structures and large pullboxes
T
rees and large shrubs. Coordinates shall be to the center of the tree or shrub and include tree type and diameter, elevation of tree at trunk base, approximate tree height, surface root and drip line perimeters Driveways
Sidewalks include back of sidewalk loca
tion.

Fences and walls including type and condition
Mailboxes including type and condition
Steps including type and condition
Retaining walls including type (reinf
orced or unreinforced, footing
or no footing) and condition
AC pa
ving and dikes
Signs
Striping and pa
vement markings
Deliverables:

Results of Sur
vey (CAD Format)
 T ASK 4 – WATER QUALITY TECHNICAL REPORT
Kimley-Horn will evaluate required storm water quality improvements based upon standards established in the City of Vista’s BMP Design Manual (revised September 2021). Based upon our understanding of the project, it is assumed that the project will be eligible for a PDP exemption based 05/27/2025
C6

Page 99 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
vi
upon Table 1-1 Step 2d and Section 1.4.3(a) of the BMP Design Manual. It is understood that under this exemption, the project will be subject to “Standard Project” requirements and that pollutant control and hydromodi fi
cation management requirements are not applicable. Based upon the limits of disturbance, it is understood that the project does not discharge directly to Buena Vista Creek, an environmentally sensitive area (ESA).

The project WQTR will consist of a written memorandum which will discuss the following topics:
•
Project introduction and summar
y of improvements
•
Applica
ble storm water requirements per the City’s BMP Manual
•
Implementa
tion plan for Permanent Storm Water BMPs
Stormwater Quality Management Plan templates shall be gathered from the City of Vista’s Stormwater Division Resources webpage at the time of NTP issuance.

Assumptions and Limitations:
•
Ef
fort estimated for this task assumes that the project will qualify for PDP exemption and will only be subject to source control and site design requirements. Pollutant control and hydromodi
fi
cation management requirements are assumed to be inapplicable. •
Continuous simula
tion modelling, channel screening, geomorphic assessment, stream susceptibility analysis, evaluation of alternative compliance design approach, and evaluation of treatment credit programs are all assumed unwarranted based upon the project description and availability of current information.
•
T
ask 4 will involve coordination and approval from the City of Vista. Approvals or coordination with additional agencies or private stakeholders is beyond the extent of this scope.
•
The project a
pproach will be subject to the
fi
ndings of the geotechnical report before commencement of work.

Deliverables:

Project Determina
tion Checklist
Standard Project Stormwa
ter Quality Management Plan (SWQMP)
W
ater Quality Technical Report
 T ASK 5 – PRELIMINARY AND FINAL DESIGN
Task 5.1: 60% Construction Drawings
Kimley-Horn will prepare 60% level construction drawings (CDs) based on field observations and our understanding and feedback from the kick- of
f meeting and project data collected. The 60% design drawings will be based on the following standards: City of Vista Manual for Traf fi
c Signal
Designs and Installations, San Diego Regional Standard Drawings, City of Vista Special Provisions, Standard Speci fi
cations (Greenbook 2024
edition), Caltrans Standard Plans 2024 Edition, Caltrans Standard Speci fi
cations 2024 Edition, Caltrans Highway Design Manual, and the 2014 California Manual on Uniform Traf
fi
c Control Devices (CA-MUTCD), Rev 8. It is assumed that Design plans will be submitted to the City and include the following sheets:

Sheet Description No. of Sheets Scale
1 Title Sheet 1 NTS
2 Legend, Abbreviations and General Notes Sheet 1 NTS
3 Key Map and Project Control Sheet 1 TBD
4 Improvement Plans 5 1’ = 20’ $
5 Utility Plans 4 1’ = 40’ $
6 Landscaping Plans and Details 6 1’ = 20’
7 Irrigation Plans and Details 6 1’ = 20’
8 Traf
fi
c Signal and Striping Plans, Notes and Details 1 1’ = 20’ Total Sheets 25
Deliverables
One (1) electronic cop
y of the 60% Improvement Plans (PDF Format).
$: Potential savings
on budget by
combining these sheets
05/27/2025
C6

Page 100 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
vii
Task 5.2: 60% Comment Resolution Meeting
After review on the City’s 60% comments, Kimley-Horn will attend one (1) meeting with the City discuss any comments that need clarification to full
y understand the comments provided. Up to two (2) Kimley-Horn staff will join the estimated one (1) hour meeting.

Deliverables
60% Response to comments (PDF Forma
t).

Task 5.3: 90% Construction Drawings and Special Provisions Upon completion of 60% comment resolution meeting, Kimley-Horn will develop 90% plans and special provisions that show all proposed improvements based on feedback received. Design plans will be submitted to the City for review, and will consist of the following sheets:

Sheet Description No. of Sheets Scale
1 Title Sheet 1 NTS
2 Legend, Abbreviations and General Notes Sheet 1 NTS
3 Key Map and Project Control Sheet 1 TBD
4 Demolition Plans 5 1’ = 20’ $
5 Improvement Plans 5 1’ = 20’ $
6 Utility Plans 4 1’ = 40’ $
7 Construction Details 1 1’ = 20’
8 Landscaping Plans and Details 9 1’ = 20’
9 Irrigation Plans and Details 9 1’ = 20’
10 Traf
fi
c Signal, and Signing & Striping Plans, Notes and Details 1 1’ = 20’ 11 Erosion Control Plans 5 1’ = 40’ $
Total Sheets 52
Title Sheet, General Notes. Kimley-Horn will prepare these sheets consistent with the City’s standards and we will include Vista Irrigation District general notes.

Key Map and Project Control Sheet. Kimley-Horn will prepare a key map sheet that will include a sheet index and project controls for the centerline along N Santa Fe Avenue.

Demolition Plans. Kimley-Horn will prepare demolition plans to identify the limits of removals for sidewalk, median hardscape, curb and gutter.

The plans will identify limits of pavement, landscape, and utility removals necessary for the proposed improvements. Existing utility information will be shown based on the best available information provided at the time of design.

Improvement Plans. Kimley-Horn will prepare improvement plans that will identify sections of sidewalk replacements, curb ramp and passageway at the East Washington Street, electrical meters, points of connection, voltage drop calculations, panel schedules, and minor pavement improvements. Pavement sections will be based on recommendations provided by in the geotechnical investigation report.

Utility Plans. Kimley-Horn will prepare utility plans that will identify conflicts with existing improvements that will need to be adjusted or relocated as well as point of connections and electrical meters. Utility plans will be used for discussions and coordination with the utility providers.

Construction Details. Kimley-Horn will prepare roadway improvement plans that will identify horizontal controls for curbs, sidewalk, curb ramps, driveways, landscape, and pavement limits/sections. Pavement sections will be based on recommendations provided in the geotechnical investigation report.

Landscape Plans and Details. Kimley-Horn will prepare landscaping plans that will extend the full project limits and will include locations of existing and proposed trees, as well as rock scaping as necessary.

Irrigation Plans and Details. Kimley-Horn will prepare irrigation plans that will extend the full project limits. The existing irrigation equipment that is identi
fi
ed as in good condition and compatible with the project objectives will be repurposed for this project along with other new equipment. $: Potential savings
on budget by
combining these sheets
05/27/2025
C6

Page 101 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
viii
Traffic Signal Plans and Signing & Striping Plans. Kimley-Horn will prepare a traffic signal plan and signing and striping and plan combined tha
t will include existing inventory of existing signs, new signs and locations of proposed traf fi
c signal equipment within the vicinity of the proposed
traf
fi
c signal.

Erosion Control Plans. Kimley-Horn will prepare erosion control plans that will identify all the existing drainage inlets and propose the appropriate Construction Best Management Practice (BMP) for the inlet.

Deliverables
One (1) electronic cop
y of the 90% Construction Drawings (PDF Format).

One (1) electronic cop
y of the 90% Special Provisions (Greenbook 2024 Format) (Microsoft Word Format).

Task 5.4: 90% Comment Resolution Meeting
After review on the City’s 90% comments, Kimley-Horn will attend one (1) meeting with the City discuss any comments that need clarification to full
y understand the comments provided. Up to two (2) Kimley-Horn staff will join the estimated one (1) hour meeting.

Deliverables
90% Response to comments (PDF Forma
t).

Task 5.5: 100% Final Construction Drawings and Special Provisions Upon completion of 90% comment resolution meeting, Kimley-Horn will develop 100% design plans that show all proposed improvements based on feedback received. Design plans will be submitted to the City for review, and will consist of the same sheets identi fi
ed in the 90% Submittal.

Deliverables
One (1) electronic cop
y of the 100% Improvement Plans (PDF Format).

One (1) electronic cop
y of the 100% Special Provisions (PDF Format).

 T ASK 6 – UTILITY COORDINATION
Kimley-Horn will to identify potential utility conflicts with the proposed improvements. We will create utility plans that depict areas of potential utility conflict or high priority facilities. We will work with identi fi
ed utility companies and the

City

to determine a strategy for addressing each utility
conflict, including adjustments, relocations, and protection in place. This task does not include design of any private utilities.

Kimley-Horn will request written con
fi
rmation from each utility purveyor con
fi
rming the relocation requirements, or absence thereof, for their services within the project limits. Depending on the existing facilities within the project area, potholing may be required to determine exact locations of crossing utility conflicts or high priority facilities. We anticipate potholing of up to ten (30) locations; the fi
nal number and location will be
determined after mapping of existing utilities and completion of the 60% plans. We have budgeted for up to 80 hours of coordination for this task and assume this coordination will be through telephone and email correspondence. Additional activities that will be included as part of the utility coordination include:
•
Submit to the utility providers preliminar
y horizontal plans showing the existing facilities along the corridor and request con fi
rmation that existing
utility facilities are depicted accurately.
•
Submit the preliminar
y design plans to all utility companies and request a conflict check review. •
Submit ser
vice meter requests to SDG&E.
•
W
e will coordinate with utility companies who have utilities in conflict with the proposed improvements to either adjust or relocate accordingly. •
Our coordina
tion with the utility providers will include obtaining a schedule of each relocation from utility companies to support. •
As part of
Task 2.3, the Kimley-Horn team will obtain pothole information to support the design and to avoid utility conflicts during construction. •
Submit
fi
nal construction plans signed by the Engineer of Work and City Engineer and con fi
rm that utility companies are designing
their relocations.
•
Obtain con
fi
rmation from the utility companies who have utilities in conflict with the proposed improvements to provide a schedule for the relocation of their utilities.
05/27/2025
C6

Page 102 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
ix
• Obtain signa tures from Vista Irrigation District (VID) on the plans if any water facilities are affected by the proposed improvements.

Deliverables:

Copies of correspondence with utility companies.
(PDF Format)
 T ASK 7 – CONSTRUCTION COST ESTIMATES
Task 7.1: 60% Opinion of Probable Construction Cost (OPCC) A 60% level opinion of probable construction cost (OPCC) will be provided to the City, which will show the proposed bid items, unit prices, and an overall opinion of cost. Unit costs will be based on readily available bid results from previous Kimley-Horn projects of similar size and readily available source data provided by the City.

Deliverables
One (1) electronic cop
y of the 60% Opinion of Probable Construction Cost (PDF and Excel Format).

Task 7.2: 90% Opinion of Probable Construction Cost (OPCC) Kimley-Horn will update the 60% OPCC for the 90% submittal to show the proposed bid items, unit prices, and an overall opinion of cost.

Deliverables
One (1) electronic cop
y of the 90% Opinion of Probable Construction Cost (PDF and Excel Format).

Task 7.3: 100% Opinion of Probable Construction Cost (OPCC) Kimley-Horn will update the 100% submittal based on 90% OPCC comments.

Deliverables
One (1) electronic cop
y of the 100% Opinion of Probable Construction Cost (PDF and Excel Format).

 T ASK 8 – CONSTRUCTION SUPPORT FOR DESIGN
Kimley-Horn will perform project management and quality control/ assurance review along with providing all monthly invoices.

Kimley-Horn shall virtually attend up to four (4) construction meetings. It is assumed that each meeting will be two (2) hours long. In addition, the Kimley-Horn will attend up to two (2) construction progress meetings, in person, as directed by the City Project Manager (PM) and the contractor to resolve issues and gain approvals.

At the request of the City, Kimley-Horn will review, approve and/or take other appropriate action in respect to Contractor-prepared submittals required by the speci
fi
cations, including shop drawings, product catalog cut sheets, certi fi
cates of compliance, samples, and other data which the
Contractor is required to submit, but only for conformance with the information given in the Contract Documents. Such review and approvals or other action will not extend to means, methods, techniques, equipment choice and usage, sequences, schedules, or procedures of construction or to related safety precautions and programs. Submittals reviewed by Kimley-Horn and returned to the contractor will be marked according to the action categories stated in the project special provisions with an electronic stamp, signature of the reviewer, and date of submittal review.

Kimley-Horn will review submittals, recommend action, and return submittals to the contractor. Kimley-Horn will retain one copy of submittal for record-keeping purposes. Submittals will be returned to the City PM and CM within 10 business days of receipt. Kimley-Horn will review, up to 18 submittals during construction, review and response to further submittals shall be considered additional services.

As directed by the City, Kimley-Horn will review and respond to reasonable and appropriate Contractor RFIs, during bidding and construction, and issue necessary clari
fi
cations and interpretations of the Contract Documents as appropriate to the orderly completion of the Contractor’s work. Any orders authorizing variations from the Contract Documents will be made by the City PM. Kimley-Horn will review and prepare responses for, up to eight (8) RFI’s during bidding and construction, review and response to further RFI’s shall be considered additional services.

Kimley-Horn shall prepare revisions to design plans and technical speci fi
cations as directed by the City. Design revisions will be annotated in a 05/27/2025
C6

Page 103 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
x
manner directed by the City. Modifications to the project plans and specifications may be required prior to and during the construction phase of the project.

Kimley-Horn will work with the City and contractor to assess the purpose for implementing a potential change, to develop an appropriate solution, and will then develop corresponding revisions to the plans and speci fi
cations. Design revisions may be in response to action required by an RFI, CCO, an unforeseen site condition, informal value-engineering, etc. and will be annotated in a manner directed by the contractor. If requested by the City, Kimley-Horn will develop an opinion of probable construction cost to coincide with the proposed changes. Design revisions will be transmitted in PDF
fi
le format. Kimley-Horn will prepare, up to three (3) design revisions during bidding and construction, further design revisions shall be considered additional services.

Kimley-Horn shall attend the Pre-Final Observation site meeting and observe and punch list areas and items relating to the project. Kimley-Horn shall provide a compiled list of all observations noted. Observations will vary depending on the type of work being performed by the contractor, the location, and the contractor’s schedule. Kimley-Horn shall attend the Final Observation site meeting to observe and verify that the punch items previously identi
fi
ed at the Pre-Final Observation were properly addressed and/ or corrected. Kimley-Horn shall provide a fi
nal compiled list of all
punch items. Additional site visits and observations as directed by the City or CM will be considered an additional service.

Deliverables:

Written responses to questions from bidders (PDF Forma
t)
Written addenda (PDF Forma
t)
Written responses to Submittals and RFI’
s (PDF Format)
 T ASK 9 – AS-BUILT PLANS AND PROJECT CLOSE-OUT
Kimley-Horn will prepare Record Drawings for the City’s records upon completion of construction. It is assumed that the Contractor will provide as- built plans identifying any changes made during construction. Revisions will be made electronically, and the entire sheet will be replaced if the fi
eld
changes were determined substantial.

Deliverables
Record Dra
wings (PDF Format) and Electronic Base Files (CAD Format).

 T ASK 10 – CONDUCT QUALITY CONTROL AND QUALITY ASSURANCE Kimley-Horn will have a quality control plan in place during the life of the project that will assure that all submittals are independently checked. All calculations, plans, and documents will be independently checked prior to submittals to ensure accuracy and completeness. Kimley-Horn will also check submittals by all sub-consultants to ensure accuracy and completeness of all submittals. Documentation of QC/QA process will be available upon City’s request.

Kimley-Horn will maintain an action item matrix and a design decisions document that will be maintained throughout the life of the project and will be used to track and get buy-off on design direction from City.

Deliverables
Quality Control Plan (PDF Forma
t)
05/27/2025
C6

Page 104 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
xi
Project Assumptions
• Hydromodi fi cation is not anticipated for this project and not included as part of the scope of work. •
Construction speci
fi
cations can be prepared as an additional service.
•
W
e anticipate the total duration of Tasks 1-10 to be up to twelve (12) months. •
City to provided inf
ormation as listed in the RFP
•
The schedule assumes a one (1) month response time f
or utility map requests (utility companies may take up to two (2) months to respond to utility map request letters).
•
Soils testing will be perf
ormed by the contractor upon completion of site work.
•
City to provide detailed as-built of the existing irriga tion system, as well as recent pressure test data for each POC directly affected by the project.
•
Pro
fi
les of existing pipes are excluded from the utility base mapping effort. AutoCAD drawings shall depict plan information only. •
Up to ten (10) pre-construction and post-construction corner records of surve y and
fi
ling with the County.
•
Up to
fi
ve (5) easements will be developed including
fi
ve (5) Preliminary Title Reports (PTRs)
•
Up to ten (10) g
ravity structure will be dipped as part of Task 3.
•
Geotechnical investiga
tion can be provided as an additional service.
•
Pa
vement replacement shall be base existing pavement sections or from as-built data. •
Additional coordina
tion beyond effort identi
fi
ed in the fee proposal can be provided as additional effort. 05/27/2025
C6

Page 105 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
xii

4. FEE PROPOSAL
Per the City’s RFP , Kimley-Horn’s fee proposal has been submitted in a separate upload to the City’s OpenGov portal. 05/27/2025
C6

Page 106 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
xiii

5. DETAILED WORK SCHEDULE
ID Task Name Duration Start Finish Predecessors
1 Recommendation to City Council/Award of Contract 1 day Tue 5/27/25 Tue 5/27/25 2 Kick-off Meeting 1 day Mon 6/16/25 Mon 6/16/25 1FS+13 days 3 Notice to Proceed 1 day Mon 6/16/25 Mon 6/16/25 2SS
4 Task 1 - PROJECT INITIATION, MANAGEMENT AND COORDINATION 420 days Tue 6/17/25 Mon 1/25/27 5 Project Administration/Management 420 days Tue 6/17/25 Mon 1/25/27 2 6 Project Meetings and Coordination with the City 420 days Tue 6/17/25 Mon 1/25/27 2 7 Task 2 - DATA COLLECTION AND FIELD REVIEW 53 days Tue 6/17/25 Thu 8/28/25 8 Review Records, Base Mapping and Field Verification 10 days Fri 8/1/25 Thu 8/14/25 13 9 Pothole Existing Utilities 30 days Tue 6/17/25 Mon 7/28/25 3 10 Forest Service Resources 2 days Fri 8/15/25 Mon 8/18/25 8 11 Inventory and Assessment of Mid-Block Crossing Location 10 days Fri 8/15/25 Thu 8/28/25 8 12 Task 3 - DESIGN SURVEYING AND BASE MAP DEVELOPMENT 30 days Fri 6/20/25 Thu 7/31/25 13 Topographic Survey and Boundary Mapping 30 days Fri 6/20/25 Thu 7/31/25 3FS+3 days 14 Task 4 - WATER QUALITY TECHNICAL REPORT 20 days Fri 9/26/25 Thu 10/23/25 15 Project Determination Checklist 2 days Fri 9/26/25 Mon 9/29/25 19 16 Standard Storm Water Quality Management Plan (SWQMP) +WQTR 20 days Fri 9/26/25 Thu 10/23/25 19 17 Task 5 - PRELIMINARY AND FINAL DESIGN 118 days Fri 8/29/25 Tue 2/10/26 18 60% Construction Drawings 34 days Fri 8/29/25 Wed 10/15/25 19 Construction Drawings 20 days Fri 8/29/25 Thu 9/25/25 11 20 QA/QC 5 days Wed 9/17/25 Tue 9/23/25 19FF-2 days
21 City Submittal 1 day Fri 9/26/25 Fri 9/26/25 19
22 City Review 10 days Mon 9/29/25 Fri 10/10/25 21
23 Comments Resolution 1 day Wed 10/15/25 Wed 10/15/25 22FS+2 days 24 90% Construction Drawings and Special Provisions 48 days Thu 10/16/25 Mon 12/22/25 25 Improvement Plans 30 days Thu 10/16/25 Wed 11/26/25 23 26 QA/QC 5 days Tue 11/18/25 Mon 11/24/25 25FF-2 days
27 City Submittal (Holiday Consideration) 1 day Tue 12/2/25 Tue 12/2/25 25FS+3 days 28 City Review & Preliminary Construction Approval 10 days Wed 12/3/25 Tue 12/16/25 27 29 Comments Resolution 1 day Mon 12/22/25 Mon 12/22/25 28FS+3 days 30 100% Construction Drawings and Special Provisions 36 days Tue 12/23/25 Tue 2/10/26 31 Finalize Submittal Package (Holiday Consideration) 20 days Tue 12/23/25 Mon 1/19/26 29 32 City Submittal 1 day Tue 1/20/26 Tue 1/20/26 31
33 City Review 10 days Wed 1/21/26 Tue 2/3/26 32
34 Bid Documents 5 days Wed 2/4/26 Tue 2/10/26 33
35 Task 6 - UTILITY COORDINATION AND ENVIRONMENTAL APPROVAL 340 days Fri 8/22/25 Thu 12/10/26 36 Utility Coordination 340 days Fri 8/22/25 Thu 12/10/26 8FS+5 days 37 Task 7 - CONSTRUCTION COST ESTIMATES 85 days Fri 9/19/25 Thu 1/15/26 38 60% Cost Estimate 3 days Fri 9/19/25 Tue 9/23/25 19FS-5 days 39 90% Cost Estimate 3 days Thu 11/20/25 Mon 11/24/25 25FS-5 days 40 100% Cost Estimate 3 days Tue 1/13/26 Thu 1/15/26 31FS-5 days 41 Task 8 - CONSTRUCTION SUPPORT FOR DESIGN 95 days Wed 2/11/26 Tue 6/23/26 42 Bid Support 95 days Wed 2/11/26 Tue 6/23/26 34
43 Engineering Approval 5 days Wed 2/11/26 Tue 2/17/26 34 44 Advertise Project 35 days Wed 2/18/26 Tue 4/7/26 43
45 Issue Addendums (If Necessary) 5 days Wed 2/11/26 Tue 2/17/26 33 46 Open Bids & City to Assign Contruction Manager 30 days Wed 4/8/26 Tue 5/19/26 44 47 Council Approval (2nd or 4th Tuesday) 20 days Wed 5/20/26 Tue 6/16/26 46 48 Award 5 days Wed 6/17/26 Tue 6/23/26 47
49 Construction Support 120 days Wed 6/24/26 Tue 12/8/26 48 50 Task 9 - AS-BUILT PLANS AND PROJECT CLOSE-OUT 37 days Wed 12/9/26 Thu 1/28/27 51 Record Drawings (Holiday Consideration) 30 days Wed 12/9/26 Tue 1/19/27 49 52 Final Punch List 2 days Fri 1/22/27 Mon 1/25/27 51FS+2 days 53 Project File Submittal 1 day Thu 1/28/27 Thu 1/28/27 52FS+2 days 54 Task 10 - CONDUCT QUALITY CONTROL AND QUALITY ASSURANCE 423 days Tue 6/17/25 Thu 1/28/27 55 QA/QC 423 days Tue 6/17/25 Thu 1/28/27 2
56 QA/QC Plan 1 day Tue 7/1/25 Tue 7/1/25 2FS+10 days
11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 May '25 Jun '25 Jul '25 Aug '25 Sep '25 Oct '25 Nov '25 Dec '25 Jan '26 Feb '26 Mar '26 Apr '26 May '26 Jun '26 Jul '26 Aug '26 Sep '26 Oct '26 Nov '26 Dec '26 Jan '27 Feb '27 Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
ATTACHMENT B City of Vista
March 2025
N. Santa Fe Ave Corridor Landscape and Irrigation Project with New Pedestrian Crossing at Washington Street CIP No. 8360

Page 1 ends

Date: Fri 3/21/25
05/27/2025
C6

Page 107 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
xiv

6. COMMENTS ON THE STANDARD CONSULTANT AGREEMENT
Kimley-Horn has reviewed the City’s standard consultant agreement and we do not have any exceptions or comments to make regarding the contract terms.
05/27/2025
C6

Page 108 of 194 ends

NORTH SANTA FE AVENUE CORRIDOR
Proposal for Professional Services for
City of Vista  RSCASAND006639.2025
xv

7. WORK SAMPLES
Sample bid package has been included on the following pages. 05/27/2025
C6

Page 109 of 194 ends

City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.
®
Know what's below.

Call before you dig.

NORTH
NORTH

CONSTRUCTION PLANS
FOR

VICINITY MAP

OWNER / PERMITEE

DECLARATION OF RESPONSIBLE CHARGE

SHEET INDEX

LOCATION MAP

WORK TO BE DONE

STANDARD SPECIFICATIONS

STANDARD DRAWINGS

CITY TRAFFIC ENGINEER DATE

REVIEWED BY CITY OF ESCONDIDO
’
BASIS OF COORDINATES: (NAD83)
”
VERTICAL CONTROL: (NGVD29)

TOPOGRAPHY SOURCE
GRAND AVENUE VISION PROJECT - PHASE 2GRAND AVENUE VISION PROJECT - PHASE 2

TITLE SHEET
SUPPLEMENTAL CONTROL:

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.
05/27/2025
C6

Page 110 of 194 ends

NOPARKING

GRAND AVENUE CONSTRUCTION CL

KEY MAP LEGEND
GRAND
AVENUE

ESCONDIDOBOULEVARD
MAPLE
STREET

BROADWAY

JUNIPERSTREET IVY
STREET

VALLEYBLVD
GRAND
AVENUE
KALMIA
STREET
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

GENERAL NOTES STORM WATER POLLUTION PREVENTION NOTES REFERENCE DRAWINGS

ABBREVIATIONS

STREET NOTES

UTILITY NOTES

KEY MAP

LEGEND, ABBREVIATIONS, AND GENERAL NOTES
05/27/2025
C6

Page 111 of 194 ends

GENERAL NOTES

GRAND AVENUE

S BROADWAY
STREET

MAPLE STREET
PLAZA

N BROADWAY

S MAPLE
STREET
LEGEND
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

NORTH

DEMOLITION NOTES

DEMOLITION PLAN
MATCHLINE STA. 20+55 SEE SHEET 4
05/27/2025
C6

Page 112 of 194 ends

N BROADWAY

S KALMIA
STREET

N KALMIA
STREET

S BROADWAY

GRAND AVENUE

GENERAL NOTES
LEGEND
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

NORTH

DEMOLITION NOTES

DEMOLITION PLAN
MATCHLINE STA. 25+55 SEE SHEET 5
MATCHLINE STA. 20+55 SEE SHEET 3
05/27/2025
C6

Page 113 of 194 ends

JUNIPER
STREET

JUNIPER
STREET

N KALMIA
STREET

S KALMIA
STREET
WARNING!!! GAS LINE.

GENERAL NOTES
LEGEND
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

NORTH

DEMOLITION NOTES

DEMOLITION PLAN
MATCHLINE STA. 25+55 SEE SHEET 4
05/27/2025
C6

Page 114 of 194 ends

LEGEND

GRAND AVENUE

S BROADWAY

S MAPLE

STREET N MAPLE
STREET

N BROADWAY
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

CONSTRUCTION NOTES
NORTH

IMPROVEMENT PLAN
MATCHLINE STA. 20+55 SEE SHEET 7

TYPICAL SCORING PATTERN DETAILS
05/27/2025
C6

Page 115 of 194 ends

N BROADWAY

KALMIA STREET

S BROADWAY

GRAND AVENUE

KALMIA STREET

N JUNIPER

STREETS JUNIPER
STREET

GRAND AVENUE
WARNING!!! GAS LINE.

LEGEND
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

NORTH

CONSTRUCTION NOTES
MATCHLINE STA. 25+55 SEE BELOW LEFT
MATCHLINE STA. 25+55 SEE ABOVE RIGHT MATCHLINE STA. 20+55 SEE SHEET 6

IMPROVEMENT PLAN
05/27/2025
C6

Page 116 of 194 ends

City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

NORTH
MATCHLINE STA. 20+55 SEE SHEET 9

TC PROFILE - GRAND AVE BETWEEN MAPLE ST AND BROADWAY - SOUTH SIDE

HORIZONTAL AND VERTICAL CONTROL SHEET

DETAIL A

GRAND AVENUE

N MAPLE STREET

S MAPLE STREET

N BROADWAY

S BROADWAY

CURB GEOMETRIC DATA
648
652
656
660
664
668
648
652
656
660
664
668

PROFILE LEGEND

GENERAL NOTE
05/27/2025
C6

Page 117 of 194 ends

S BROADWAY

N BROADWAY

GRAND AVENUE

S KALMIA

N KALMIA

CURB GEOMETRIC DATA
652
656
660
664
668
652
656
660
664
668
652
656
660
664
668
652
656
660
664
668

PROFILE LEGEND

GENERAL NOTE
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

NORTH
MATCHLINE STA. 25+55 SEE SHEET 10
MATCHLINE STA. 20+55 SEE SHEET 8

TC PROFILE - GRAND AVE BETWEEN BROADWAY AND KALMIA - NORTH SIDE

TC PROFILE - GRAND AVE BETWEEN BROADWAY AND KALMIA - SOUTH SIDE

HORIZONTAL AND VERTICAL CONTROL SHEET
05/27/2025
C6

Page 118 of 194 ends

GRAND AVENUE

S KALMIA N KALMIA

N JUNIPER ST

CURB GEOMETRIC DATA
652
656
660
664
668
652
656
660
664
668
652
656
660
664
668
652
656
660
664
668

GENERAL NOTEPROFILE LEGEND
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

NORTH
MATCHLINE STA. 25+55 SEE SHEET 9

TC PROFILE - GRAND AVE BETWEEN KALMIA ST AND JUNIPER ST - NORTH SIDE

TC PROFILE - GRAND AVE BETWEEN KALMIA ST AND JUNIPER ST - SOUTH SIDE

HORIZONTAL AND VERTICAL CONTROL SHEET

DETAIL A

DETAIL B
05/27/2025
C6

Page 119 of 194 ends

N BROADWAY

S BROADWAY

GRAND AVENUE

LEGENDGENERAL NOTES
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

NORTH

CONSTRUCTION NOTES

IMPROVEMENT PLAN
05/27/2025
C6

Page 120 of 194 ends

N BROADWAY

S BROADWAY

GRAND AVENUE

CURB GEOMETRIC DATA
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

NORTH

HORIZONTAL AND VERTICAL CONTROL PLAN
05/27/2025
C6

Page 121 of 194 ends

651
652
656
660
651
652
656
660

PROFILE LEGEND

GENERAL NOTE
649
652
656
660
649
652
656
660
652
656
660
652
656
660
652
656
660
652
656
660
652
656
660
664
652
656
660
664
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

NORTH

CURB PROFILES

TC PROFILE - GRAND AVE AND BROADWAY - NW CORNER

TC PROFILE - GRAND AVE AND BROADWAY - SW CORNER

TC PROFILE - GRAND AVE AND BROADWAY - NE CORNER

TC PROFILE - GRAND AVE AND BROADWAY - SE CORNER

TC PROFILE - GRAND AVE AND BROADWAY - CENTER CIRCLE
05/27/2025
C6

Page 122 of 194 ends

NORTH City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

CURB RAMP ENLARGEMENT - BROADWAY (NW) CURB RAMP ENLARGEMENT - BROADWAY (NE)

CURB RAMP ENLARGEMENTS - BROADWAY (N)

CURB RAMP ENLARGEMENT - GRAND AVE (NW) CURB RAMP ENLARGEMENT - GRAND AVE (NE)

GRAND AVENUE

N BROADWAY

GRAND AVENUE
05/27/2025
C6

Page 123 of 194 ends

NORTH City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

CURB RAMP ENLARGEMENT - BROADWAY (SW) CURB RAMP ENLARGEMENT - BROADWAY (SE)

CURB RAMP ENLARGEMENTS - BROADWAY (S)

CURB RAMP ENLARGEMENT - GRAND AVE (SW) CURB RAMP ENLARGEMENT - GRAND AVE (SE)

S BROADWAY

GRAND AVENUE GRAND AVENUE
05/27/2025
C6

Page 124 of 194 ends

NORTH City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

NORTH

E SPLITTER ISLAND ENLARGEMENT - GRAND AVE & BROADWAY

W SPLITTER ISLAND ENLARGEMENT - GRAND AVE & BROADWAY

SPLITTER ISLAND ENLARGEMENTS - BROADWAY

S SPLITTER ISLAND ENLARGEMENT - GRAND AVE & BROADWAYN SPLITTER ISLAND ENLARGEMENT - GRAND AVE & BROADWAY

CURB GEOMETRIC DATA
05/27/2025
C6

Page 125 of 194 ends

GRAND AVE

S KALMIA

N KALMIA
636
640
644
648
652
656
660
664
668
672
636
640
644
648
652
656
660
664
668
672

PIPE TABLE
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

NORTH

CONSTRUCTION NOTES

DRAINAGE PLAN AND PROFILE
SD-01 PROFILE

GENERAL NOTE
05/27/2025
C6

Page 126 of 194 ends

640
644
648
652
656
660
664
640
644
648
652
656
660
664
640
644
648
652
656
660
664
640
644
648
652
656
660
664
640
644
648
652
656
660
664
640
644
648
652
656
660
664
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

CONSTRUCTION NOTES
A B

DRAINAGE PLAN AND PROFILE
SD-03 PROFILESD-02 PROFILE SD-04 PROFILE

BMP DETAIL
®

LINER ATTACHMENT DETAIL
05/27/2025
C6

Page 127 of 194 ends

SECTION A - A

PLAN VIEW
A
A
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

A B
E
D
C

CONSTRUCTION DETAILS

ROADWAY SAWCUT DETAIL CURB AND GUTTER TRANSITION TO EXISTING

ISOMETRIC VIEW PLAN VIEW

MOUNTABLE CURB DETAIL

INTEGRAL COLORED CONCRETE RIBBON GUTTER
DETAIL PER SDRSD G-12, MODIFIED

CONCRETE MAINTENANCE STRIP DETAIL
05/27/2025
C6

Page 128 of 194 ends

CONCRETE CONNECTION

SECTION A-A

PLAN VIEW

SECTION B-B

CONCRETE TURNDOWN AT
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.744.0177
SAN DIEGO, CA 92101
MARK ARAUJO, P.E.

A B C
D
E
F G
H
I

CONSTRUCTION DETAILS

CONCRETE CONTROL JOINT CONCRETE EXPANSION JOINT CONCRETE CONNECTION TO EXISTING PAVEMENT

CONCRETE PAVER (PEDESTRIAN) AND INTEGRAL COLORED CONCRETE BAND

CONCRETE TURNDOWN ADJACENT

TO EXISTING CONCRETE BAND

THICKENED CURB AND GUTTER

CURB CUT DETAILS

TREE GRATE
INLET
OUTLET

SCORED STANDARD GRAY SECTION DETAIL
05/27/2025
C6

Page 129 of 194 ends

City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.234.9411
SAN DIEGO, CA 92101

RANDALL A KOPFF JR, PLA

PLANT SCHEDULE

SITE FURNISHING SCHEDULE
GENERAL NOTES:
“ ”
“ ”

LANDSCAPE NOTES

URBAN DESIGN NOTES AND SCHEDULE
TREE RELOCATION NOTES:
05/27/2025
C6

Page 130 of 194 ends

HARDSCAPE NOTES

NOPARKINGNOPARKING

GRAND AVENUE

S BROADWAY

S MAPLE
STREET
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.234.9411
SAN DIEGO, CA 92101

RANDALL A KOPFF JR, PLA
NORTH

URBAN DESIGN PLAN
MATCHLINE STA. 20+55 SEE SHEET 23

PLANT LEGEND
05/27/2025
C6

Page 131 of 194 ends

S KALMIA
STREET

N KALMIA
STREET

GRAND AVENUE

JUNIPER
STREET

JUNIPER
STREET

GRAND AVENUE

HARDSCAPE NOTES
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.234.9411
SAN DIEGO, CA 92101

RANDALL A KOPFF JR, PLA
NORTH

URBAN DESIGN PLAN
MATCHLINE STA. 25+55 SEE BELOW LEFT
MATCHLINE STA. 25+55 SEE ABOVE RIGHT MATCHLINE STA. 20+55 SEE SHEET 22

PLANT LEGEND
05/27/2025
C6

Page 132 of 194 ends

HARDSCAPE NOTES

S BROADWAY
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.234.9411
SAN DIEGO, CA 92101

RANDALL A KOPFF JR, PLA
NORTH

URBAN DESIGN ENLARGEMENT

PLANT LEGEND
05/27/2025
C6

Page 133 of 194 ends

City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.234.9411
SAN DIEGO, CA 92101

RANDALL A KOPFF JR, PLA
TYPICAL SHRUB PLANTING5 NTS
9-12"
3 X

ROOTBALL WIDTH
6"
2-3" MULCH LAYER AS SPECIFIED
4" HIGH BERM, FIRMLY COMPACTED
3" DIA. CLEAR OF MULCH FROM
TRUNK
FINISHED GRADE.

UNDISTURBED NATIVE SOIL

SCARIFY BOTTOM AND SIDES OF

PLANTING PIT

SET ROOTBALL ON UNDISTURBED

STABLE SUBSOIL SO THAT TOP OF
ROOTBALL IS 1" ABOVE FINISHED
GRADE.

PREPARED BACKFILL

PLANT TO BE INSTALLED

CENTERED

AND PLUMB/LEVEL IN PLANTING PIT
FERTILIZER TABLETS (MAX 3" DEEP)
NOTES:

1. REFERENCE PLANTING SPECIFICATIONS/ SPECIAL PROVISIONS FOR ADDITIONAL INFORMATION.

2. WHEN SHRUBS MASSED WITH GROUNDCOVER BEDS, ENTIRE BED TO BE AMENDED.

3. WHEN SHRUBS ARE USED IN MASSES, PRUNE ALL SHRUBS TO

ACHIEVE UNIFORM MASS/HEIGHT

SECTION

BEST FACE OF SHRUB TO FACE

FRONT OF PLANTING BED

REFER TO PLANT SCHEDULE AND

PLANS FOR SPACING/LAYOUT
PLAN
4"

FRONT OF BED
36" AND LARGER BOX TREE PLANTING
1 NTS

ROOT CONTROL BARRIER
7 NTS
CONSTRUCTION AND INSTALLATION:

NOTES:

MATERIALS:

ANTI-LIFT GROUND LOCK

ZIPPER JOINING SYSTEM

DOUBLE TOP EDGE

ZIPPER JOINING SYSTEM
.085"
.085"
1/2"
1/4"
7/16"
.085"
.085"
2 1/4"
.085"3/8"

SPECIFIED TREE ROOT BARRIERS ARE A MECHANICAL BARRIER AND ROOT DEFLECTOR TO PREVENT TREE ROOTS FROM DAMAGING ADJACENT PAVING / HARDSCAPE ELEMENTS. ASSEMBLED IN 2' LONG MODULES OR FOR LINEAR APPLICATIONS DIRECTLY BESIDE AN ADJACENT HARDSCAPE AREA TO ONE SIDE OF THE TREES (LINEAR PLANTING STYLE).

1. THE CONTRACTOR SHALL FURNISH AND INSTALL TREE ROOT BARRIERS AS SPECIFIED. THE TREE ROOT BARRIERS SHALL BE PRODUCT # UB 24-2 AS MANUFACTURED BY DEEP ROOT PARTNERS, L.P. 530 WASHINGTON STREET, SAN FRANCISCO, CA 94111 (800-458-7668), OR APPROVED EQUAL. THE BARRIER SHALL BE BLACK, INJECTION MOLDED PANELS, OF 0.085" WALL THICKNESS IN MODULES 24" LONG BY 24" DEEP; MANUFACTURED WITH A MINIMUM 50% POST CONSUMER RECYCLED POLYPROPYLENE PLASTIC WITH ADDED ULTRAVIOLET INHIBITORS; RECYCLABLE.

1. THE CONTRACTOR SHALL INSTALL THE TREE ROOT BARRIERS WITH THE NUMBER OF PANELS AND IN THE MANNER SHOWN ON THE DRAWINGS. THE VERTICAL ROOT DEFLECTING RIBS SHALL BE FACING INWARDS TO THE ROOT BALL AND THE TOP OF THE DOUBLE EDGE SHALL BE 1/2" ABOVE GRADE. EACH OF THE REQUIRED NUMBER OF PANELS SHALL BE CONNECTED EITHER TO FORM A CIRCLE AROUND THE ROOT BALL OR BE JOINED IN A LINEAR FASHION AND PLACED ALONG THE ADJACENT HARDSCAPE.

2. EXCAVATION AND SOIL PREPARATION SHALL CONFORM TO THE DRAWINGS

DOUBLE TOP EDGE FOR

PREVENTION OF ROOT

OVER GROWTH
90° ROOT DEFLECTING RIBS

INTEGRAL PART OF PANEL
PANEL 0.085" (2.16MM)

THICK POLYPROPYLENE

PATENTED MOLDED

GROUND LOCKING

ANTI-LIFT PADS

ROUNDED EDGES FOR

SAFETY AND STRENGTH

ROCK MULCH
3 NTS

INSTALL WEED BARRIER IN ALL PROPOSED

LANDSCAPE AREAS, EXCEPT THOSE WHERE
STORMWATER INFILTRATION IS INTENDED.

SEE IMPROVEMENT PLANS

URBAN DESIGN DETAILS
NOTE:

ROCK TO APPEAR THAT IS HAS SETTLED
OVER TIME INTO THE LANDSCAPE.

BOULDERS TO APPEAR MORE WEATHERED

AND ANGULAR IN APPEARANCE, RATHER

THAN ROUNDED OR FLAT, AND SHALL BE
FREE OF SHARP EDGES.

BOULDER TO BE SET A MINIMUM OF 1/3 OR A
MAXIMUM OF 2/3 BELOW GRADE.

PLACE FLAT SIDE OF ROCK BELOW GRADE OR
NATURAL FACE ABOVE GRADE.

MULCH (TYP)
BOULDER4 NTS

ROCK COBBLE AT ENERGY DISSIPATORS
VARIES

SUBGRADE
2 SEE PRECISE GRADING PLANS
2' 3"-5" Ø ROCK COBBLE PER PLAN
6" DEPTH

PERMEABLE WEED BARRIER

SUBGRADE
3/4" Ø ROCK MULCH PER PLAN
2" DEPTH
SLOPE
NTS
NOTES:

1. ENERGY DISSIPATORS SHALL BE INSTALLED AT ALL
CURB CUT LOCATIONS PER PLAN.
3"-5" Ø ROCK COBBLE PER PLAN
6" DEPTH

PERMEABLE WEED BARRIER
3/4" Ø ROCK MULCH PER PLAN
2" DEPTH

PREPARED PLANTING SOIL
1/2"

ADJACENT
PAVING

MATERIAL,

SEE PLAN
3/4" Ø ROCK MULCH PER PLAN
2" DEPTH

WEED BARRIER,
MIRAFI 140N OR APPROVED EQUAL AND

APPLY PRE-EMERGENT HERBICIDE

PRIOR TO LAYING MULCH
12"

TREE GRATE PER PLAN, SEE DETAIL ON
SHEET 20

ROCK MULCH, PER PLAN

SIDEWALK PAVEMENT
- SEE IMPROVEMENT
PLANS
CROWN SET 1" ABOVE FINISH GRADE

COMPACTED SUBGRADE
3/4" DIA. GRAVEL SUMP
12"12"

SCARIFY BOTTOM AND SIDES

OF PLANTING PIT

FERTILIZER TABLETS
(MAX 3" DEEP)

IMPORTED LANDSCAPE MEDIAN
BACKFILL COMPACTED TO 80%

PROCTOR DENSITY

TREE TRUNK - LOCATE TREE IN

CENTER TREE GRATE & PLANT
PLUMB

ROOTBARRIER PER DETAIL THIS

SHEET (TYP)

GRATE STAKE

PREVAILING WIND
12"-14"
18"

TYPICAL TREE PLANTING IN TREE GRATE
NTS6

DECORATIVE FENCE
8 NTS
1 3
4" SQ. 12 GAUGE STEEL

TOP AND BOTTOM RAILS OR

FLAT BAR RAILING SYSTEM
(OR APPROVED EQUAL) (TYP)

FINISH GRADE
2 1
2" SQ. POST WITH FLAT CAPS OR FLAT

BAR RAILING SYSTEM
(OR APPROVED EQUAL) (TYP)
5" SQ. 9 GAUGE SURFACE

MOUNTING PLATE
1" SQ. 16 GAUGE DECORATIVE

PICKET OR RAILING PANEL
(OR APPROVED EQUAL) (TYP)
05/27/2025
C6

Page 134 of 194 ends

ont
c
entsee
abl
t
e
A
nI
terpretive
ont
c
ent see ablt e A nI terpretive
no
tentsee
abl
t
e
A nI
terpretive
ont
c
ent
Interp ti ev
c
e
no
tent see ablt e A
Interp
tiev
c
e
see
abl
t
e
A
nI
terpretive
ont
c
ent see ablt e A nI terpretive
City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.234.9411
SAN DIEGO, CA 92101

RANDALL A KOPFF JR, PLA

URBAN DESIGN DETAILS

TYPICAL DECORATIVE SANDBLAST DESIGN AT TREE GRATE
1 NTS

TABLE A - INTERPRETIVE CONTENT

DECORATIVE SANDBLAST STENCIL LETTERS
3 NTS

DECORATIVE SANDBLAST STENCIL PATTERN
NTS2

DECORATIVE SANDBLAST AT BROADWAY INTERSECTION
4 NTS

TYPICAL A (ONE LINE LAYOUT)

TYPICAL B (TWO LINE LAYOUT)

TYPICAL A TYPICAL B TYPICAL C
05/27/2025
C6

Page 135 of 194 ends

City of ChoiceCity of Choice
P23-0014GRAND AVENUE VISION PROJECT - PHASE 2

RECORD DRAWING
PRINT ENGINEER'S NAME DATER.C.E. _________
CITY PROJECT NO.

ENG. 21-0011

KIMLEY-HORN
401 B STREET, STE. 600
619.234.9411
SAN DIEGO, CA 92101

RANDALL A KOPFF JR, PLA

IRRIGATION NOTES

STATE OF CALIFORNIA ESTIMATED WATER USE

TOTAL WATER USE IS CALCULATED BY SUMMING THE AMOUNT OF WATER ESTIMATED FOR EACH HYDROZONE. WATER USE FOR EACH HYDROZONE IS ESTIMATED WITH THE FOLLOWING FORMULA:

EWU (HYDROZONE) = ESTIMATED WATER USE (GAL / YEAR)
ETO = REFERENCE EVAPOTRANSPIRATION (INCHES / YEAR)
PF = PLANT ETO ADJUSTMENT FACTOR
HA = HYDROZONE AREA (S.F.)
.62 = CONVERSION FACTOR
IE = IRRIGATION EFFICIENCY
SLA = SPECIAL LANDSCAPE AREA (S.F.)
EWU (HYRDROZONE) = (ETO * PF * HA * .62) / (IE)

HYDROZONE A (DRIP)

ETO PF HA IE CONVERSION

FACTOR EWU GAL/YEAR

54.2 .2 7955 .81 .62 66005

HYDROZONE B (MOD WATER BUBBLER)

ETO PF HA IE CONVERSION

FACTOR EWU GAL/YEAR

54.2 .4 1760 .81 .62 29206
ESTIMATED TOTAL WATER USE (ETWU) 95211

MAWA (MAXIMUM APPLIED WATER ALLOWANCE)

ETO ET ADJUSTMENT FACTOR TOTAL HA CONVERSION

FACTOR MAWA

54.2 .45 9715 .62 146908
ESTIMATED ANNUAL WATER USE (% OF MAWA) 65

VALVE SCHEDULE

IRRIGATION SCHEDULE
MAINTENANCE:
·
·

THE IRRIGATION MAINTENANCE SCHEDULE TASKS LISTED BELOW ARE INTENDED A S MINIMUM STANDARDS AND MORE FREQUENT ATTENTION MAY BE REQUIRED DEPENDING ON THE PARTICULAR SITE CONDITIONS.

MAINTENANCE SHALL BE DONE TO ENSURE WATER EFFICIENCY. REPAIR OF IRRIGATION EQUIPMENT SHALL BE DONE WITH THE ORIGINALLY SPECIFIED MATERIALS OR APPROVED EQUIVALENTS.

FREQUENCY - QUARTERLY
TASK - CONTROLLER CABINET : OPEN CABINET AND CLEAN OUT DEBRIS AND REPLACE BATTERY AS NECESSARY.CHECK WIRING AND REPAIR AS NEEDED AND CHECK CLOCK AND RESET IF NECESSARY.

FREQUENCY - MONTHLY
TASK - IRRIGATION SCHEDULE: ADJUST SCHEDULE FOR SEASONAL VARIATIONS AND OTHER CONDITIONS WHICH MAY AFFECT THE AMOUNT OF WATER NEEDED TO MAINTAIN PLANT HEALTH. ADJUST AS NECESSARY.

FREQUENCY - QUARTERLY
TASK - POC: VISUALLY INSPECT COMPONENTS FOR LEAKS, PRESSURE SETTINGS, SETTLEMENT OR OTHER DAMAGE AFFECTING THE OPERATION OF A COMPONENT. REPAIR AS NEEDED.

FREQUENCY - QUARTERLY
TASK - REMOTE CONTROL VALVES : ISOLATION VALVES AND QUICK COUPLER VALVES: VISUALLY INSPECT FOR LEAKS, SETTLEMENTS, WIRE CONNECTIONS AND PRESSURE SETTINGS. REPAIR AS NEEDED.

FREQUENCY - QUARTERLY
TASK - MAINLINE AND LATERALS: VISUALLY INSPECT FOR LEAKS OR SETTLEMENTS OF TRENCH.

FREQUENCY - WEEKLY

TASK - FILTERS AND STRAINERS - VISUALLY CHECK FOR ANY BROKEN MALIGNED OR CLOGGED HEADS, HEADS WITH INCORRECT ARC, INADEQUATE COVERAGE OR OVERSPRAY AND LOW HEAD DRAINAGE. REPAIR AS NEEDED.

FREQUENCY - MONTHLY
TASK - FILTERS AND STRAINERS: VISUALLY CHECK FOR LEAKS, BROKEN FITTINGS. CLEAN AND FLUSH SCREENS.

IRRIGATION MAINTENANCE SCHEDULE:

IRRIGATION NOTES & SCHEDULES
F
A
BF-A
BF-B
C-A
C-B
MB
MA
#"
##-#
C-A
C-B
05/27/2025
C6

Page 136 of 194 ends