Regular City Council Meeting Agenda
September 22, 2026 at 6:00 PM
Wheatland Community Center
101 C Street, Wheatland, CA 95692
City Council meetings are held in-person and are no longer available via ZOOM.
In compliance with the Americans with Disabilities Act, if you are a disabled person and you need a disability-related modification or accommodation to participate in this meeting, please contact City Hall at (530) 633-2761 or (530) 633-9102 (fax). Requests must be made as early as possible and at least one full business day before the start of the meeting.
1. OPENING MATTERS
1.1 Call to Order and Roll Call
1.2 Pledge of Allegiance to the Flag
2. PUBLIC COMMENT
At this time, the public is permitted to address the City Council on non-agendized items. Comments should not exceed three (3) minutes. In accordance with State Law, however, no action or discussion may take place on any item not appearing on the posted agenda. The Council may respond to statements made or questions asked or may request Staff to report back at a future meeting concerning the matter. Any member of the public may contact the City Clerk’s Office related to the proper procedure to place an item on a future City Council agenda. The exceptions under which the Council may discuss and/or act on items not appearing on the agenda are contained in Government Code §54954.2(b) (1) (2) (3)
3. CONSENT CALENDAR
3.1 Minutes - September 8, 2026
3.2 Consideration and Adoption of Resolution Authorizing Execution of Amendment to the Reimbursement Agreement between the City of Wheatland and Mercy Housing California 63, LP for Transit Services
3.3 Consideration and Adoption of Resolution Authorizing Acceptance of Department of Alcoholic Beverage Control’s ABC-OTS (Office of Traffic Safety) Grant Program for $22,000
3.4 Consideration and Adoption of a Resolution Approving Modification of the Classifications in the Bargaining Unity Represented by the Wheatland Sergeants Association 1 3.5 Consideration of Approval of Task Order #23 with Raney Planning and Management, Inc. to Provide Planning and Environmental Services for the Durst Mansion Event Center Conditional Use Permit Project
3.6 Consideration and Adoption of Resolution for Purchase of Environmental Mitigation Credits for Construction of the Wheatland Regional Sewer Pipeline Project
4. PUBLIC HEARING
5. PRESENTATIONS
5.1 Presentation from Recology on Solid Waste Collection Changes
6. REGULAR CALENDAR
6.1 Consideration of a Presentation and Update on the Status of an Agreement Between Olivehurst Public Utility District (OPUD) and the City of Wheatland Regarding the South Yuba County Regional Wastewater Project
6.2 Consideration and Adoption of a Resolutions Awarding Construction Contracts for Construction of the Wheatland Regional Sewer Pipeline Project [CWSRF Project No. C-06- 8753-110]; and Authorizing the City Manager to Execute Change Orders Not-To-Exceed the Project Budget.
6.3 Consideration and Adoption of a Resolution Authorizing the City Manager to Execute a Professional Service Agreement for Construction Management and Inspection, and Issue Task Orders for Engineering and Environmental Support Services During Construction of the Wheatland Regional Sewer Pipeline Project [CWSRF Project No. C-06-8753-110]
7. REPORTS
8. CLOSED SESSION
8.1 Conference with Legal Counsel - Existing Litigation (Government Code Section 54956.9):
City of Wheatland v. Garcia et al. (Yuba County Sup. Ct.) No. CVED26-00172 City of Wheatland v. Waltz et al. (Yuba County Sup. Ct.) No. CVED26-00191
8.2 Conference with Legal Counsel – Anticipated Litigation - Initiation of litigation pursuant to Government Code section 54956.9(d)(4): One Potential Case
9. ADJOURN
2 AGENDA POSTING CERTIFICATION
I, Jessy Johnson, Deputy City Clerk for the City of Wheatland, do hereby declare under penalty of perjury that I caused the above agenda to be posted at City of Wheatland City Hall at 111 C Street, Wheatland, CA 95692 and on the City website at www.wheatland.ca.gov.
Date: September 17, 2026 /s/ Jessy Johnson, Deputy City Clerk 3 City Council Regular Meeting Minutes
September 08, 2026 at 6:00 PM
Wheatland Community Center
101 C Street, Wheatland, CA 95692
1. OPENING MATTERS
1.1 Call to Order and Roll Call - 6:00 p.m., All present.
1.2 Pledge of Allegiance to the Flag - Performed.
2. PUBLIC COMMENT - None.
3. CONSENT CALENDAR
3.1 Minutes - August 25, 2026
3.2 Ratification of the August 25, 2026 City Council Proclamation Recognizing and Thanking Bill Zenoni for his Dedicated Service to the City and Wishing Him a Well-deserved Retirement Motion to approve Consent Calendar made by Councilmember Teter and Seconded by Councilmember B. Abe
AYES: Teter, B. Abe, J. Abe, Pesenti, McIntosh
NOES: None
ABSTAIN: None
ABSENT: None
Motion passes 5-0-0-0
4. PUBLIC HEARING - None.
5. PRESENTATIONS
5.1 Proclamation - 9/11 Day of Remembrance & 25th Anniversary - Presented by City Manager Grayson. Moment of silence to be held at City Hall Friday, September 11.
6. REGULAR CALENDAR
6.1 Consideration of Stop and Yield Signs at Residential Intersections - Presented by Dane Schilling.
6.2 Wheatland Road Complete Streets Project Update - Presented by Lindsey Katt, Dokken Engineering. Comments received from Chris Walsh, Tate Henderson, and Tony Lopez.
7. REPORTS
4 Section 3, Item # 3.1
8. CLOSED SESSION - 7:36 p.m.
8.1 Conference with Legal Counsel - Existing Litigation (Government Code Section 54956.9):
City of Wheatland v. Garcia et al. (Yuba County Sup. Ct.) No. CVED26-00172 City of Wheatland v. Waltz et al. (Yuba County Sup. Ct.) No. CVED26-00191
8.2 Conference with Legal Counsel - Anticipated Litigation - Initiation of litigation pursuant to Government Code section 54956.9(d)(4): One Potential Case Council reconvened from Closed Session at 9:41 p.m. with no reportable action.
9. ADJOURN - 9:42 p.m.
MINUTES CERTIFICATION
I, Josie Camacho, City Clerk for the City of Wheatland, do hereby declare under penalty of perjury that the above minutes are a true depiction of all actions taken at the City Council meeting held on the first date above written at Wheatland Community Center, 101 C Street, CA.
Date: September 9, 2026 /s/ Josie Camacho, City Clerk
5 Section 3, Item # 3.1
STAFF REPORT
Meeting Date: September 22, 2026
SUBJECT: Consideration and Adoption of Resolution Authorizing Execution of Amendment to the Reimbursement Agreement between the City of Wheatland and Mercy Housing California 63, LP for Transit Services
PREPARED BY: Sean Grayson, City Manager
RECOMMENDATION:
Staff recommends that the Wheatland City Council consider adoption of a resolution authorizing execution of an amendment to the reimbursement agreement between the City of Wheatland and Mercy Housing 63, LP for transit services.
DISCUSSION:
The City of Wheatland and Yuba-Sutter Transit Authority (YSTA) entered into an agreement in July 2007 which provided that YSTA would provide Wheatland residents with one round trip between Wheatland and the City of Marysville three days per week. Those services are paid for, in part, by State Transit Assistance funds allocated to the City of Wheatland by the California Department of Transportation.
Mercy Housing California 63, LP (Mercy Housing) owns an 88 unit affordable housing apartment complex known as Sunset Valley, located at 512 Spruce Street. The City of Wheatland and Mercy Housing entered into an agreement in October 2015 which provided that Mercy Housing would reimburse the City for the cost of two additional days of transit service per week. Those funds are remitted by the City to YSTA.
YSTA has proposed an expanded level of transit service for Wheatland residents which would provide bidirectional fixed route service between the cities of Marysville, Wheatland and Lincoln/Roseville, including a demand-response service within Wheatland at least five days per week (Monday through Friday). Mercy Housing has agreed to reimburse the City of Wheatland for the additional cost of the expanded service. This change will result in improved transit service for Wheatland residents at no additional cost to the City.
FISCAL IMPACT:
There is no fiscal impact to the City associated with this item.
ATTACHMENTS:
A. Resolution w/Exhibits
6 Section 3, Item # 3.2
Attachment ‘A’
RESOLUTION NO. 26-___
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF WHEATLAND
AUTHORIZING THE EXECUTION OF AMENDMENT TO THE REIMBURSEMENT AGREEMENT BETWEEN THE CITY OF WHEATLAND AND MERCY HOUSING CALIFORNIA 63, LP
FOR TRANSIT SERVICES
WHEREAS, the City Council, on July 1, 2007, approved an agreement with Yuba-Sutter Transit Authority for the provision of transit services to Wheatland residents three days per week; and
WHEREAS, the City Council, on October 27, 2015 authorized execution of an agreement with Mercy Housing California 63, LP which provided that Mercy Housing would reimburse the City of Wheatland for the cost of two additional days of transit service per week; and WHEREAS, Yuba-Sutter Transit Authority has proposed an expanded level of transit service which would provide bidirectional fixed route service between the cities of Marysville, Wheatland and Lincoln/Roseville, including a demand-response service within Wheatland at least five days per week; and
WHEREAS, Mercy Housing California 63 LP has agreed to reimburse the City of Wheatland for the additional cost of this expanded service which will provide improved transit service for Wheatland residents at no additional cost to the City.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Wheatland as follows:
1. The foregoing recitals are true and correct.
2. The City Council of the City of Wheatland hereby authorizes the Mayor to execute an amendment to the 2015 reimbursement agreement with Mercy Housing California 63, LP for transit services. As attached hereto as Exhibit A.
The foregoing resolution was adopted by the City Council of the City of Wheatland at a regular meeting held on the 22nd day of September, 2026 by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
7 Section 3, Item # 3.2
The foregoing resolution is hereby approved.
________________________
Lisa McIntosh, Mayor
ATTEST:
________________________
Josie Camacho, City Clerk
8 Section 3, Item # 3.2
Exhibit A
AMENDMENT TO REIMBURSEMENT AGREEMENT BETWEEN CITY OF
WHEATLAND AND MERCY HOUSING CALIFORNIA 63, LP FOR TRANSIT
SERVICES
This Amendment is made effective on September 22, 2026 to amend the Reimbursement Agreement for Transit Services between the City of Wheatland, California, a municipal corporation ("Wheatland"), and Mercy Housing California 63, LP; a California limited partnership ("Mercy Housing”), effective October 27, 2015 (“Agreement”).
RECITALS
A. Wheatland and the Yuba-Sutter Transit Authority ("Authority") entered an agreement on July 1, 2007 ("2007 Transit Agreement") under which Authority provides on-demand public transit services for the benefit of Wheatland residents, which services are paid for in part by State Transit Assistance funds that are allocated to Wheatland by the California Department of Transportation each year;
B. Under the 2007 Transit Agreement, Authority provided Wheatland residents with one round trip between Wheatland and the City of Marysville three (3) times a week on Tuesdays, Wednesdays and Thursdays;
C. On October 27, 2015, Wheatland and Mercy Housing entered into the Agreement, pursuant to which Mercy Housing agreed to pay Wheatland, and Wheatland agreed to remit those payments to the Authority, to fund the provision of transit service for two additional days per week;
D. Authority desires that the current transit services be modified and expanded such that the Authority would provide bidirectional, express fixed route service between the cities of Marysville, Wheatland and Lincoln/Roseville, including a general public, demandresponse service within Wheatland, at least five (5) days a week, from Monday through Friday ("Additional Transit Services");
E. Authority shall operate the Additional Transit Services, provided that Wheatland and Mercy Housing agree to reimburse a portion of the associated transit-related costs.
Authority shall invoice Wheatland for the reimbursable portion of the costs of the Additional Transit Services. Mercy Housing shall remit payment for such costs to Wheatland, and Wheatland shall, in turn, remit those payments to Authority in accordance with the terms of the 2007 Transit Agreement; F. Wheatland and Mercy Housing desire to amend the Agreement to effectuate the reimbursement for the Additional Transit Services.
9 Section 3, Item # 3.2
[Type here]
AMENDMENT
In consideration of the mutual covenants contained herein, the parties agree as follows:
1. The foregoing recitals are true and incorporated herein by reference.
2. “Additional Transit Services” shall mean bidirectional, express fixed route service between Marysville, Wheatland and Lincoln/Roseville, including a general public, demand-response service within Wheatland, at least five (5) days a week, from Monday through Friday.
3. Section 2 (Reimbursement) of the Agreement is hereby replaced as follows:
To obtain reimbursement from Mercy Housing for its applicable portion of the costs of the Additional Transit Services, Wheatland shall submit an invoice to Mercy Housing no more than once each quarter, following the Authority’s commencement of the Additional Transit Services. Each invoice shall state that the reimbursement request is limited to Mercy Housing’s portion of the costs of the Additional Transit Services provided by Authority to Wheatland for the applicable quarter. Mercy Housing shall review all reimbursement requests submitted by Wheatland and within thirty (30) days of receipt, make full payment of the invoice.
For the first twelve-month period (Year One), the applicable portion of costs reimbursable to Authority by the parties for the Additional Transit Services shall be fixed at $11,500 each quarter ($46,000 annually), beginning with the first full month after Authority starts providing the Additional Transit Services. Mercy Housing shall reimburse Wheatland for all such costs.
Beginning with the first quarter of the following year (Year 2), and thereafter, the applicable portion of costs reimbursable to Authority by the parties for the Additional Transit Services shall be administratively adjusted on an annual basis by applying the percentage change (rounded to two decimal places) in the Consumer Price Index – All Urban Consumers U.S. City Average - All items (Series ID CUUR0000SA0), to the reimbursable amount for the immediate preceding twelvemonth period, providing that adjustment shall not be less than two percent (2%) nor greater than four percent (4%).
The applicable portion of costs reimbursable to Authority by the parties for Additional Transit Services shall be subject to change only by mutual agreement of Authority and the parties to this agreement.
10 Section 3, Item # 3.2
[Type here]
4. Section 4 (Notices) of the Agreement is hereby amended as follows:
A copy of all notices for Wheatland shall be remitted to:
BKS Law Firm, PC
1600 K St., Suite 4A
Sacramento, CA 95814
Attention: Jennifer Buckman
5. Except as specifically provided in this Amendment, the remaining provisions of the Agreement are unchanged and remain in full effect and are incorporated herein by this reference.
City of Wheatland:
__________________________________
Lisa McIntosh
Mayor
Mercy Housing California 63, LP:
_________________________________
Name
President
11 Section 3, Item # 3.2
12 Section 3, Item # 3.2
13 Section 3, Item # 3.2
14 Section 3, Item # 3.2
15 Section 3, Item # 3.2
16 Section 3, Item # 3.2
17 Section 3, Item # 3.2
18 Section 3, Item # 3.2
19 Section 3, Item # 3.2
20 Section 3, Item # 3.2
21 Section 3, Item # 3.2
22 Section 3, Item # 3.2
STAFF REPORT
Meeting Date: September 22, 2026
SUBJECT: Consideration and Adoption of Resolution Authorizing Acceptance of Department of Alcoholic Beverage Control’s ABC-OTS (Office of Traffic Safety) Grant Program for $22,000 PREPARED BY: Michael Garlock, Chief of Police
RECOMMENDATION:
Staff recommends that the Wheatland City Council consider adoption of a resolution authorizing the acceptance of an enforcement-only grant for $22,000 from the Department of Alcoholic Beverage Control for the purpose of enforcing and educating on alcohol-related statutes with the city’s alcohol establishments.
DISCUSSION:
The Wheatland Police Department has been awarded a $22,000 enforcement-only grant from the Department of Alcoholic Beverage Control ABC-OTS Grant Program from October 1, 2026, through September 30, 2027. This grant allows Wheatland Police Officers to conduct operations enforcing alcohol-related statutes with licensed alcohol establishments within the City of Wheatland.
The City of Wheatland has a population of 4,300 residents over 8 square miles, some of which is undeveloped land or farmland. The real concern involves the city’s geography and nearby venues.
Highway 65 is the main thoroughfare in the city of Wheatland, connecting residents to the Toyota Amphitheater and Hard Rock Casino, both in the unincorporated area of Yuba County, each less than 7 miles outside the city limits. Increased traffic and visitors from these venues will mean more people frequenting licensed alcohol on- or off-sale establishments within the city.
From September 6 through November 15, 2026, Bishop’s Pumpkin Farm will be open seven days a week, which can draw several thousand visitors per day, depending on the day or special event, such as movie night or fireworks. It is estimated that throughout the pumpkin season, 350,000 people, including numerous minors, will visit the pumpkin farm. The pumpkin farm also serves 6 flavors of hard cider at 5 serving venues. With this kind of activity, the police department would welcome the funding and the opportunity to work with ABC to keep alcohol violations at the pumpkin farm to a minimum, particularly by preventing the serving of minors and overserving patrons of legal drinking age. 23 Section 3, Item # 3.3
Additionally, Wheatland High School has a student body of 1,185, and the campus is located the following distances from the following off-sale establishments. .4 mile from Raj’s Mini Mart: 100 D Street
.8 mile from Chevron Gas Station: 500 McDevitt Drive
.9 mile from Dollar General: 1920 Hwy 65
.7 mile from Wheatland Liquor: 419 4th Street
.5 mile from Big Al’s Market: 422 Main Street.
The department would work to ensure minors (under 21 years of age) are not possessing, stealing, or being sold alcohol at any of the 11 ABC-licensed establishments in the City of Wheatland, including those listed above. Enforcement and education would be conducted through IMPACT inspections and shoulder-tap programs, using minor decoy operations, including holiday enforcement. Conducting these operations will help minimize DUIs within the city, as DUIs were the top crime in the City of Wheatland in 2024, with 38, and again in 2025, with 23. Another goal is to ensure that all alcohol establishments comply with state statutes.
Accepting this grant would provide funding to enforce and educate citizens and businesses regarding alcohol violations within the City of Wheatland.
Finally, to ensure the community is aware of our facilitation and participation in enforcement operations, the Police Department is prepared to issue news releases regarding all Shoulder Tap and Minor Decoy Operations.
FISCAL IMPACT:
There is de minimus fiscal impact with officers' salaries and/or overtime for alcohol-related enforcement operations being funded by the grant.
ATTACHMENTS:
A. Resolution w/Exhibit
24 Section 3, Item # 3.3
Attachment ‘A’
RESOLUTION NO. 26-___
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF WHEATLAND AUTHORIZING THE CITY OF WHEATLAND POLICE DEPARTMENT TO АССЕРТ А
GRANT FROM THE STATE OF CALIFORNIA DEPARTMENT OF ALCOHOLIC
BEVERAGE CONTROL SPONSORED BY THE STATE OF CALIFORNIA OFFICE OF THE TRAFFIC SAFETY IN THE AMOUNT OF $22,000 FOR THE POLICE DEPARTMENT IMPLEMENT
NUMEROUS ALCOHOL MITIGATION AND EDUCATION PROGRAMS AND AUTHORIZING THE
CITY MANAGER TO EXECUTE ALL GRANTS DOCUMENTS ON BEHALF OF THE CITY WHEREAS, the State of California Department Alcoholic Beverage Control (ABC), sponsored by the State of California Office of Traffic Safety (OTS), through the National Highway Traffic Safety Administration (NHSTA) has awarded the City of Wheatland a grant in the amount of $22,000 through its ABC-OTS Grant Program; and
WHEREAS, the City of Wheatland Police Department submitted a letter of interest to the Department of Alcoholic Beverage Control for the ABC-OTS Local Law Enforcement Grant, in August 2026; and
WHEREAS, on September 1, 2021, the City of Wheatland Police Department was awarded the ABC-OTS Local Law Enforcement Grant in amount not to exceed $22,00; and NOW, THEREFORE, BE IT RESOLVED AND DETERMINED by the City Council of the City of Wheatland that:
A. The foregoing recitals are true and correct.
B. The City of Wheatland Police Department is authorized to accept the grant.
C. That the City Manager or designee of the City of Wheatland is authorized to execute all grant-related documents, including the State of California Standard Agreement, any extensions, or amendments thereof, and any subsequent contract with the State in relation to the ABC-OTS Local Enforcement Grant.
D. That the Finance Director or designee are authorized to make the necessary budget adjustments upon the award of the grant.
25 Section 3, Item # 3.3
The foregoing resolution was adopted by the City Council of the City of Wheatland at a regular meeting held on the 22
nd day of September 2026, by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
The foregoing resolution is hereby approved.
________________________
Lisa McIntosh, Mayor
ATTEST:
________________________
Josie Camacho, City Clerk
26 Section 3, Item # 3.3
27 Section 3, Item # 3.3
STAFF REPORT
Meeting Date: September 22, 2026
SUBJECT: Consideration and Adoption of a Resolution Approving Modification of the Classifications in the Bargaining Unity Represented by the Wheatland Sergeants Association
PREPARED BY: Sean Grayson, City Manager
RECOMMENDATION:
Staff recommends that the Wheatland City Council consider adoption of a resolution approving modification of the classifications in the bargaining unit represented by the Wheatland Sergeants Association.
DISCUSSION:
Section 2.16.030(C) of the Wheatland Municipal Code states that the City Manager shall prepare City personnel rules and revisions and amendments to such rules. Section 2.16.050 of the Municipal Code provides that personnel rules shall be adopted by resolution of the City Council.
Section 25 of the Wheatland Personnel rules addresses employer-employee relations. Article II Subsection 8 prioritizes bargaining units comprised of the “broadest feasible grouping of positions that share an identifiable community of interest,” as well as similarity of work performed, qualifications required, the organizational structure of the City, the number of employees and classifications, and the effect on the administration and stability of employee relations.
The Wheatland Sergeants Association (WSA) has historically only had one person in the bargaining unit and currently has none. There are no current personnel filling a Police Sergeant position and there are no current WSA members. In order to best meet employer-employee relations the City has proposed that the Wheatland Police Officers Association (WPOA) become the exclusive bargaining unit representative of the Police Sergeant classification. The terms and conditions of the WSA memorandum of understanding (MOU) would remain in effect until it ends June 30, 2027 or when the WPOA negotiates a new WPOA MOU that includes the Police Sergeant classification, whichever comes first.
This proposed action to eliminate the WSA and for the WPOA to represent the Police Sergeant classification was reviewed with representatives of WPOA which were supportive of the action.
FISCAL IMPACT:
There is no fiscal impact associated with this item.
ATTACHMENTS:
A. Resolution
28 Section 3, Item # 3.4
Attachment ‘A’
RESOLUTION NO. 26-___
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF WHEATLAND APPROVING
MODIFICATION OF THE CLASSIFICATIONS IN THE BARGAINING UNIT REPRESENTED BY THE
WHEATLAND SERGEANTS ASSOCIATION
WHEREAS, the Wheatland Police Officers Association (WPOA) is the exclusive bargaining representative of the classifications of Police Officer and Police Corporal; and WHEREAS, the Wheatland Sergeants Association (WSA) currently is the exclusive bargaining representative of the classification of Police Sergeant; and WHEREAS, the City wishes to modify its bargaining units consistent with Personnnel Rule Section 25, Article II, Sections 8 and 9 to have the Police Sergeant classification represented by the WPOA; and
WHEREAS, this change is consistent with Personnel Rule Section 25, Article II, Section 8 which prioritizes bargaining units comprised of the “broadest feasible grouping of positions that share an identifiable community of interest,” as well as similarity of work performed, qualifications required, the organizational structure of the City, the number of employees and classifications, and the effect on the administration and stability of employee relations; and WHEREAS, there currently are no filled Police Sergeant positions or WSA members, and the WPOA agrees to and supports being the exclusive bargaining representative for the Police Sergeant classification; and
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Wheatland as follows:
1. The foregoing recitals are true and correct and are incorporated herein by this reference.
2. Effective the date of City Council approval of this Resolution, the WPOA rather than the WSA will become the exclusive bargaining representative of the Police Sergeant classification, and henceforth represent the classification of Police Sergeant classification in future meet and confer and other representation matters.
3. The terms and conditions set forth in the current City/WSA MOU with effective dates July 1, 2025 – June 30, 2027 shall continue to govern and apply to the classification of Police Sergeant moving forward until the City and WPOA in 2027 negotiate a new City/WPOA MOU that includes the Police Sergeant classification (or such sooner time should the City and WPOA negotiate and agree to a change in the City/WSA MOU prior to the City/WSA MOU expiring on June 30, 2027).
4. The City Clerk is authorized and directed to attest to the adoption of this Resolution and to maintain it in the official records of the City. 29 Section 3, Item # 3.4
The foregoing resolution was adopted by the City Council of the City of Wheatland at a regular meeting held on the 22nd day of September, 2026 by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
The foregoing resolution is hereby approved.
________________________
Lisa McIntosh, Mayor
ATTEST:
________________________
Josie Camacho, City Clerk
30 Section 3, Item # 3.4
RECOMMENDATION:
Staff recommends that the Wheatland City Council consider approval of the attached Task Order #23 with Raney Planning and Management, Inc. (Raney) to conduct the necessary tasks required to process a Conditional Use Permit (CUP) and prepare an Initial Study/Mitigated Negative Declaration (IS/MND) for the Durst Mansion Event Center Project (proposed project).
This action does not include any recommendations on the project itself. The Task Order will allow the review and processing of the proposed project.
DISCUSSION:
The proposed project consists of the preparation and processing of an IS/MND to analyze the potential environmental effects associated with the operation of the Durst Mansion Event Center. It is anticipated that Raney will complete the IS/MND in January 2027, and the proposed project would be considered by the Planning Commission at a public hearing in March 2027.
Task Order #23 authorizes Raney (the consultant) to perform the following tasks to process this project application (see Attachment 1):
Task 1 Project Initiation
Task 2 Planning Services
Task 2.1 Application Review
Task 2.2 Agency Coordination
Task 2.3 Prepare Staff Reports, Findings, and Resolutions Task 2.4 Prepare Public Noticing
Task 2.5 Project Management
STAFF REPORT
Meeting Date: September 22, 2026
SUBJECT: Consideration of Approval of Task Order #23 with Raney Planning and Management, Inc. to Provide Planning and Environmental Services for the Durst Mansion Event Center Conditional Use Permit Project PREPARED BY: Sean Grayson, City Manager
31 Section 3, Item # 3.5
Task 3 Environmental Services
Task 3.1 Prepare Administrative Draft IS/MND
Task 3.2 Air Quality and Greenhouse gas Analysis
Task 3.3 Prepare Mitigation Monitoring and Reporting Program Task 3.4 Responses to Comments Project Management
In addition to completing the above tasks, Raney will work with Kittleson & Associates to perform an analysis of transportation impacts and Saxelby Acoustics to conduct a noise analysis.
Based on the information contained in the staff report, staff recommends that the Wheatland City Council approve the attached Task Order #23, authorizing Raney Planning and Management Inc. to provide planning and environmental services for the Durst Mansion Event Center Project, and authorize the City Manager to sign Task Order #23.
FISCAL IMPACT:
The costs of this review should not exceed $69,812, which would be funded by the project applicant.
ATTACHMENTS:
A. Raney Planning and Management Task Order #23
32 Section 3, Item # 3.5
TASK ORDER #23
Durst Mansion Event Center Conditional Use Permit Project Date: September 22, 2026
Contact: City of Wheatland
Sean Grayson
111 C Street, Wheatland, CA 95692
[email protected]
Consultant: Raney Planning & Management, Inc.
1501 Sports Drive, Suite A
Sacramento, CA 95834
(916) 372-6100
[email protected]
Tim Raney, President
Project Funding Source: Project Applicant
The Consultant is hereby authorized to perform the following work subject to the provisions of the Contract identified above:
Fee (Not to Exceed): Estimate of $69,812
Scope:
Please see Attachment A for a complete scope of work.
Raney will complete the following tasks to provide planning services for the Durst Mansion Event Center Project:
1. Application Review
2. Agency Coordination
3. Prepare Staff Reports, Findings, and Resolutions
4. Prepare Public Noticing
5. Project Management
Raney will complete the following tasks to provide environmental services for the proposed project:
1. Prepare Administrative Draft Initial Study/Mitigated Negative Declaration (IS/MND)
2. Air Quality and Greenhouse gas Analysis
3. Prepare Mitigation Monitoring and Reporting Program
33 Section 3, Item # 3.5
4. Responses to Comments
5. Project Management
In addition to completing the above tasks, Raney will work with Kittleson & Associates to perform an analysis of transportation impacts and Saxelby Acoustics to conduct a traffic noise increase analysis.
Payment and Invoicing Procedures
Invoicing and Payment is per Professional Services Agreement executed on May 16, 2022.
The undersigned consultant hereby agrees that it will provide all equipment, furnish all materials, except as may be otherwise noted above, and perform all services for the work above specified in accordance with the Contract identified above and will accept as full payment therefore the amount shown above.
City of Wheatland Consultant:
Dated: ______ Dated: ________ ______
Title: City Manager Title: _____________
Print Name: Sean Grayson Print Name:
Signature: Signature:
34 Section 3, Item # 3.5
SCOPE OF WORK:
DURST MANSION EVENT CENTER PROJECT
Please find below Raney’s scope of work, schedule, and budget for the Durst Mansion Event Center Project (proposed project).
PROJECT UNDERSTANDING
Project Location
The project site is an approximately 42-acre northern portion of the approximately 145.4-acre parcel identified by Assessor’s Parcel Number (APN) 015-360-052-000. The project site is bounded by Spenceville Road to the north, located immediately south of the McCurry Street and Spenceville Road intersection, and bounded by a walnut orchard to the south.
The project site consists of relatively flat land and the Durst Mansion property. The site includes Durst Mansion and agricultural structures, including a walnut dryer, on the northeastern portion of the project site, a centrally located barn, and a rural residence on the southwestern portion of the project site. Trees are scattered along the site’s southern boundary and as part of Durst Mansion’s landscaping, including trees along Spenceville Road.
The City of Wheatland General Plan designates the site as Public/Quasi Public (Civic Center). The site is zoned Hop Farm Planned Development.
Surrounding land uses include single-family residences and multi-family residential to the north, across Spenceville Road; an agricultural structure, unidentified structure, undeveloped land, and a walnut orchard to the east; a walnut orchard to the immediate south; and undeveloped land to the west, as well as single-family residences further west.
Project Description
The proposed project would require a Conditional Use Permit (CUP) to allow use of the site as an event venue for indoor and outdoor, small to mid-size gatherings such as 35 Section 3, Item # 3.5
2 weddings, receptions, ceremonies, and small concerts. Indoor gatherings would primarily take place in Durst Mansion. The proposed project would include the planting of a wildflower garden north of the existing Durst Mansion, the development of a parking area southwest of the existing Durst Mansion, and the development of a farm trail south of the existing Durst Mansion that would connect to the existing southern walnut orchards and centrally located barn. The southwestern existing rural residence would be used as a four-bedroom guest house.
The existing centrally located barn and northeastern walnut dryer would be preserved.
Raney assumes that all existing on-site structures would be improved as needed to adequately serve their intended uses, including new lighting, repainting, etc. The existing on-site dirt/gravel roads would be paved.
The proposed project would primarily be accessed through the three existing driveways off Spenceville Road.
APPROACH
Raney’s approach to environmental and planning services is to act as an extension of City of Wheatland (City) staff to review the application for completeness, assist with agency consultation, prepare staff reports, and attend meetings and public hearings.
Raney would coordinate extensively with City Departments to ensure a complete, thorough review of the application. Raney’s scope of work anticipates attendance at one in-person Planning Commission public hearing.
Based on Raney’s preliminary analysis of the proposed project and conversations with the City, Raney proposes to prepare an Initial Study/Mitigated Negative Declaration (IS/MND) to analyze the potential environmental effects associated with the proposed project. The IS/MND would be prepared using the checklist contained in Appendix G of the California Environmental Quality Act (CEQA) Guidelines and the standard City of Wheatland format. Raney anticipates that the potential impacts would be less-thansignificant; therefore, the appropriate CEQA document would be an IS/MND.
Raney would work closely with City staff throughout the preparation of the IS/MND and determination of appropriate findings. The IS/MND would provide a discussion of the impacts related to implementation of the proposed project. 36 Section 3, Item # 3.5
3 Technical Reports to be provided by Raney
The air quality technical analysis would be conducted in-house by Raney’s Air Quality Division led by Vice President/Air Quality Specialist, Rod Stinson, and Division Manager/Air Quality Specialist, Angela DaRosa. All air quality studies would be prepared consistent with the regulations and requirements of Feather River Air Quality Management District (FRAQMD) and the City.
Subconsultants
Raney proposes to subcontract with the following consultants to prepare project-specific technical reports:
• Saxelby Acoustics (Saxelby) – Noise and Vibration Study; and • Kittleson & Associates – Transportation Impact Study.
TECHNICAL SCOPE OF SERVICES
Raney proposes to perform the following tasks for the provision of planning services and preparation of the IS/MND for the proposed project:
TASK 1 PROJECT INITIATION........................................................................... $1,480 TASK 2 PLANNING SERVICES .......................................................................... $7,800 Task 2.1 Application Review........................................................................................... $1,860 Task 2.2 Agency Coordination (Including Preparation of AB 52 Letters)....................$970 Task 2.3 Prepare Staff Reports, Findings, and Resolution......................................... $2,560 Task 2.4 Prepare Public Noticing.......................................................................................$310 Task 2.5 Project Management (Planning Services) .................................................... $2,100 TASK 3 ENVIRONMENTAL SERVICES ............................................................ $18,070 Task 3.1 Prepare Administrative Draft IS/MND............................................................ $8,820 Task 3.1a Air Quality and Greenhouse Gas (GHG) Analysis ....................................... $2,910 Task 3.2 Prepare Mitigation Monitoring Reporting Program (MMRP)...................... $1,025 37 Section 3, Item # 3.5
4 Task 3.3 Responses to Comments ................................................................................ $1,415 Task 3.4 Project Management (Environmental Services) .......................................... $3,900 ADDITIONAL EXPENSES.................................................................................... $24,862 Printing/Copying/Travel/Postage/Etc...................................................................................$350 CHRIS Search.........................................................................................................................$500 Subconsultant: Saxelby Acoustics................................................................................... $6,658 Subconsultant: Kittleson & Associates.......................................................................... $12,000 CDFW/NOD Filing Fee....................................................................................................... $3,044 County Filing Fee......................................................................................................................$50 Raney 10% Administrative Fee (Printing/Copying/Etc. and Subconsultants) ........... $2,260 Optional: Kittleson & Associates Non-CEQA Transportation Analysis.................... $17,600 (Includes Raney’s 10% Administrative Fee)
38 Section 3, Item # 3.5
5 TENTATIVE SCHEDULE
The schedule could be lengthened or shortened depending on the needs of the City.
Factors that could lengthen or shorten the schedule include dates of receipt of project information, length of document reviews, changes in the project description, and unanticipated issues arising from City staff.
Milestones & Deliverables Timing Anticipated Date
Notice to Proceed (NTP) To be determined (TBD) Week of
July 13, 2026
Receipt of Technical Reports Ten weeks from NTP September 21, 2026 Administrative Draft IS/MND to the
City of Wheatland
Three weeks from
Receipt of Technical
Reports
October 12, 2026
Receipt of City comments on the
Administrative Draft IS/MND Two weeks October 26, 2026
Submit Public Review IS/MND and
Draft MMRP to the City of
Wheatland
One week November 2, 2026
Public Review Period 30 days* November 5, 2026, to
December 4, 2026
Final MMRP and Responses to
Comments (if necessary) to the
City of Wheatland
One week December 11, 2026
Planning Commission Hearing TBD December/
January 2026
*Allow three days for State Clearinghouse processing.
39 Section 3, Item # 3.5
6 BUDGET
The cost of completion for the Durst Mansion Event Center IS/MND and Planning Services is not to exceed $52,212. Raney’s costs are based on the estimates of time for each task provided in the spreadsheet on the following page. Costs for the planning services would be billed on a not-to-exceed basis, following Raney standard billing rates included in the spreadsheet below.
PROPOSED COST ESTIMATE Project Director Division Manager Project Manager/ Principal Planner
Air Quality Specialist
Air Quality Technician
Senior Associate
Associate
Cost Per Task
Task 1 Project Initiation 2 6 $ 1,480
Task 2 Planning Services
Task 2.1 Application Review 6 6 $ 1,860
Task 2.2 Agency Coordination 4 2 $ 970
Task 2.3 Prepare Staff Reports, Findings, and Resolutions 2 6 8 $ 2,560 Task 2.4 Prepare Public Noticing 1 1 $ 310
Task 2.5 Project Management (Planning Services) 12 $ 2,100 Task 3 Environmental Services
Task 3.1 Prepare Administrative Draft IS/MND 4 6 8 42 8,820 $ Task 3.1.a Air Quality and GHG Analysis 6 12 $ 2,910
Task 3.2 Prepare MMRP 1 2 4 $ 1,025
Task 3.3 Responses to Comments 1 2 2 4 $ 1,415
Task 3.4 Project Management (Environmental Services) 8 4 8 $ 3,900 Total Hours 17 4 52 6 12 12 67
Hourly Rate $ 215 $ 195 $ 175 $ 175 $ 155 $ 155 $ 135
Total Labor $ 3,655 $ 780 $ 9,100 $ 1,050 $ 1,860 $ 1,860 $ 9,045 $ 27,350 Subconsultants and Expenses $ 24,862
Copying/Printing/Travel/Postage/Etc.* $ 350
CHRIS Search $ 500
Subconsultant: Saxelby Acoustics $ 6,658
Subconsultant: Kittleson & Associates $ 12,000
CDFW/NOD Filing Fee $ 3,044
County Filing Fee $ 50
10% Administrative Fee $ 2,260
Total Budget $ 52,212
Subconsultant: Kittleson & Associates Optional Non-CEQA Transportation Analysis (includes Raney's 10% administrative fee) $ 17,600 * Estimate only, To Be Billed at Cost
40 Section 3, Item # 3.5
7 The cost for copying, printing, travel, postage, and any other expenses is an estimate only and would be billed at cost.
The following assumptions have been made in the calculations:
• Attendance at additional meetings and hearings could easily be accommodated and would be billed on a time-and-materials basis.
• Raney costs assume that the provided data and information from the City and the project team is accurate and current and would be readily available. • Raney assumes that the provision of environmental and planning services would be a continuous process without excessive delays. Raney would propose renegotiating the contract with respect to schedule and cost shall substantial delays occur.
Factors that would increase the scope of work and estimated costs outlined in the proposal include:
• Attendance at additional virtual or in-person meetings or hearings; • Printing of reports;
• Additional reviews and revisions beyond those included in this scope of work; • Changes in the project; and
• Requests or revisions for WCAG 2.1 Level AA compliance.
Raney would renegotiate these items or charge on a time-and-materials basis.
Thank you for the opportunity to submit our proposal for your consideration. Additional information regarding our qualifications, including resumes, is available upon request.
Please do not hesitate to contact me if you have any questions regarding the scope of work or if you need any additional information. We look forward to the continued opportunity to work with you on this project.
Thank you,
Kevin Valente, AICP, Principal Planner
Raney Planning & Management, Inc.
[email protected]
41 Section 3, Item # 3.5
Attachment A:
Saxelby Acoustics Scope of Work
42 Section 3, Item # 3.5
June 29, 2026
Bryce Madden
Raney Planning & Management
1501 Sports Drive, Suite A
Sacramento, California 95834
[email protected]
Subject: Proposal to Provide Acoustical Consulting Services for the Durst Mansion Event Center – City of Wheatland, CA
Dear Mr. Madden:
Thank you for contacting us regarding this project, we look forward to working with you on this. Attached is our scope to address the requirements of the City of Wheatland for this project.
Scope of Work:
Task 1 – Preparation of Noise Study
1A. Community Noise Survey: Saxelby Acoustics will conduct a noise survey within the project area to quantify existing background noise levels at the nearest existing residential uses. The noise survey will consist of continuous noise level measurements for a minimum period of 48 hours, over a typical Friday and Saturday.
1B. Prediction of Exterior Noise Levels: We will model event noise levels at the existing sensitive receptors located around the project site. This will be done using the SoundPLAN acoustic noise prediction model, location and size of proposed events, and typical noise levels associated with amplified music. We will model noise levels for up to three separate locations where music may occur. This would include evaluation of potential noise control options as necessary to meet the City’s exterior noise standards.
1C. Report Preparation: Saxelby Acoustics will prepare a written report analyzing project noise levels at the nearest sensitive receptors, including noise contours for typical operations. The report will be prepared to meet the requirements of the City of Wheatland. If necessary, we will evaluate potential noise control measures if required to meet the City standards.
Fee:
Saxelby Acoustics will conduct the above-described scope of work for a fee of $6,658.00. 43 Section 3, Item # 3.5
www.SaxNoise.com June 29, 2026 Page 2 of 3
\\Saxelby-Syn1\Saxelby Acoustics\General\Sax Acoustic Files\Proposals\Environmental - RPM - City of Wheatland - Durst Mansion Event Center.docx Saxelby Acoustics Fee Proposal
Attendance at additional meetings or performance of additional work which is outside of this proposal will be invoiced based upon hourly rates and expenses, as outlined in the attached fee schedule.
Timing:
We will commit to meeting deadlines as required to keep to the project schedule. We request three to four weeks to provide a completed study after approval.
Saxelby Acoustics maintains automobile, general, workers compensation, and professional liability insurance policies as outlined on the attached fee schedule.
Thank you again for inviting our proposal, and please call or email me if you have any questions.
Sincerely,
Saxelby Acoustics LLC
Luke Saxelby, INCE Bd. Cert.
Principal Consultant
Board Certified, Institute of Noise Control Engineering Proposal Accepted by:
Print Name:
Company:
Title:
Date:
Task Description Fee
1A Community Noise Survey
Principal Consultant 2 hrs. $ 275 /hr. $550.00
Technical Staff 8 hrs. $ 175 /hr. $1,400.00
Mileage 80 miles $ 0.725 /mile $58.00
1B Prediction of Exterior Noise Levels
Principal Consultant 4 hrs. $ 275 /hr. $1,100.00
Technical Staff 12 hrs. $ 175 /hr. $2,100.00
1C Report Preparation
Principal Consultant 4 hrs. $ 275 /hr. $1,100.00
Technical Staff 2 hrs. $ 175 /hr. $350.00
Total for Task 1: $6,658.00
Task 1 – Preparation of Noise Study
Quantity Rate
44 Section 3, Item # 3.5
www.SaxNoise.com June 29, 2026 Page 3 of 3
\\Saxelby-Syn1\Saxelby Acoustics\General\Sax Acoustic Files\Proposals\Environmental - RPM - City of Wheatland - Durst Mansion Event Center.docx Saxelby Acoustics 2026 Fee Schedule and Consulting Terms Item Rate
Principal Consultant
Regular Rate
Legal Rate (Inspections, depositions, court testimony, expert witness conference, etc.)
$275/hr.
$600/hr.
Noise & Vibration Engineer / Project Manager $225/hr.
Technical Staff $175/hr.
Administrative Staff $125/hr.
Mileage Rate IRS Rate ($0.725/mile)
Meals and Lodging $250/day
Sound Level Meter
Basic (daily)
Basic (weekly)
Advanced (daily)
Advanced (weekly)
Very Low Noise (daily)
Very Low Noise (weekly)
Sound Meter – Advanced Outdoor Setup
Very low noise, wind measurement, audio recording, solar panels, environmental protection shroud, etc.
$100/day
$400/week
$150/day
$600/week
$200/day
$800/week
$1,000/week
IIC Tapping Machine $500/day
$2,000/week
Sound System for Acoustic Testing $200/day
$800/week
Vibration Sensor with Calibrator $200/day
$800/week
Insurance Coverage
Saxelby Acoustics LLC maintains the following insurance limits:
Commercial General Liability – $2,000,000 per occurrence / $4,000,000 aggregate Auto Liability – $1,000,000
Umbrella Liability – $3,000,000 per occurrence / $3,000,000 aggregate Worker’s Compensation – Per Statute
Professional Liability – $2,000,000 per occurrence / $2,000,000 aggregate Certificates of insurance to our clients can be issued for no additional fee.
Request for Retainers
For new clients, a retainer of up to 50% of the contract is required prior to beginning work on the project. Payment for the balance of the study will be required prior to issuance of signed/stamped report.
Invoicing and Terms of Payment
Saxelby Acoustics reserves the right to submit monthly invoices for services and expenses which have been incurred when the project duration is expected to exceed 30 days. Payment for professional services is due within 30 days of the invoice date, and past due thereafter. Past due invoices will incur interest at the rate of 2% per month on the balance due, unless otherwise agreed upon. We will accept bank transfer (ACH) and credit card payments for no additional fee. Cash payments are not accepted.
45 Section 3, Item # 3.5
Attachment B:
Kittleson & Associates Scope of Work
46 Section 3, Item # 3.5
FILENAME: H:\33\33586 - DURST MANSION EVENTS CTR TIA\ADMIN\P\04_WORKINGDOCS_QAQC\33586_WHEATLAND_DURST MANSION EVENT CENTER TRAFFIC STUDY_KITTELSON PROPOSAL_2026-06-17.DOCX
June 22, 2026 Project #: 33586
Kevin Valente, AICP
Principal Planner
Raney Planning & Management, Inc.
1501 Sports Drive, Suite A
Sacramento, CA 95834
RE: Durst Mansion Event Center Transportation Impact Study Dear Kevin:
Attached is a proposal to conduct a Transportation Impact Study (TIS) associated with Durst Mansion Event Center in Wheatland, CA (“Project”). This scope was developed based on our discussions with you, our review of the proposed development plan, and our familiarity with the City of Wheatland (City).
We propose to conduct the services (detailed in Part “A” herein) on a time & materials basis for a fee not to exceed $12,000. This fee excludes the optional Non-CEQA Transportation Analysis task, which is estimated at $16,000. If the City elects to authorize the optional task, the total not-to-exceed fee for all services will be $28,000. This proposal (scope of work, budget, and timeline) is effective for sixty days.
I (Dhawal Kataria) will serve as the Project Manager and Fernando Sotelo will serve as the Project Principal providing senior review and quality assurance. Any questions of a technical or contractual nature can be directed to either of us.
Please review this proposal at your earliest convenience. If the attached Professional Services Agreement is satisfactory, please return a signed copy electronically. A fully executed copy will be returned for your records.
Thank you for the opportunity to propose on this project. If you have any questions please call us at 510.433.8093.
Sincerely,
Kittelson & Associates, Inc.
Pioneer Ridge Annexation VMT Study
30324
Dhawal Kataria, AICP, RSP1 Fernando Sotelo, T.E.
Senior Planner| Project Manager Principal Engineer | Project Principal 155 Grand Avenue, Suite 505
Oakland, CA 94612
P 510.839.1742 F 510.839.0871
47 Section 3, Item # 3.5
33586
Durst Mansion Event Center Transportation Impact Study Page: 2 of 5 Kittelson & Associates, Inc.
PART A - SCOPE OF WORK
Project Understanding
The proposed project consists of the development of an event center located on Spenceville Road in eastern Wheatland, California. The project involves limited site improvements, including the construction of an overflow parking area with ADA-compliant parking spaces and a small amphitheater.
The event center is intended to accommodate gatherings of up to 150 guests. Attendees will access the site via the western driveway to Spenceville Road, which provides direct access to the primary parking area. The main driveway entrance will be reserved for use by the bridal party and other event-related vehicles.
The site will provide approximately 20 parking spaces within the paved parking area adjacent to the residence, along with an additional 60 spaces in the overflow parking area, for a total of 80 on-site parking spaces. Should parking demand exceed the available on-site supply, a shuttle service will be provided to transport attendees from off-site parking locations.
Task 1: Project Management and Coordination
Kittelson staff will be available to participate in a kick-off meeting and two (2) project coordination calls, via videoconference. The kick-off meeting will be scheduled with the City staff and the applicant to discuss transportation scope, project schedule and to gain better project understanding.
The purpose of the project coordination calls is to discuss the methodology and results. Kittelson will share the materials in advance of each meeting and will distribute a summary of notes and action items following each meeting.
Kittelson’s project manager will prepare monthly invoices for the duration of the project. The project manager will provide regular updates to the City staff on the status of each task as well as the overall status of the project budget and schedule.
Task 1: Deliverables
Attend up to three one-hour videoconference meetings (Kick-off and 2 project coordination calls) Monthly invoices
Task 2: Scoping Memorandum
Kittelson will prepare a scoping memorandum to be reviewed and approved by City staff prior to initiating the technical analysis. The scoping memorandum will include a trip generation estimate for the project, and vehicle miles traveled (VMT) assessment methodology. Kittelson will identify an appropriate approach for VMT assessment in consultation with City staff.
Trip Generation: Kittelson will estimate the trip generation for the proposed project using the information provided by the project applicant and our experience with similar projects. The ITE Trip Generation Manual 12th Edition does not have a land use for the event center nor any land use that would be similar to the project. The 48 Section 3, Item # 3.5
33586
Durst Mansion Event Center Transportation Impact Study Page: 3 of 5 Kittelson & Associates, Inc.
trip generation will be estimated based on the capacity (150 guests) of the event center factoring that some of the visitors will be coming together in the same vehicle, vendors, and deliveries.
For the purpose of this scope we assume the project can screen out from a detailed VMT analysis, see Task 3 below. Kittelson will address one round of comments and will discuss the scope during the project coordination calls (Task 1). The scoping memorandum will be used to inform the preparation of the TIS for the project. One round of revision is included in this scope.
Kittelson will confirm the following information prior to beginning any technical analysis:
Number of staff including catering, bartenders, servers, maintenance, security, valet, logistics and support staff
What is the anticipated annual number of events?
What are the expected peak days of the week?
What are the peak months or seasons for events?
Will multiple events occur simultaneously on-site?
What are the typical event start and end times?
How long do events generally last?
What is the anticipated attendee arrival distribution (e.g., percentage arriving 1 hour before, 30 minutes before, etc.)?
What is the anticipated attendee departure distribution? Are there events that may end late at night?
Are there events that may begin during weekday peak commute periods? What are the anticipated busiest hours of operation?
Will there be setup and breakdown activities occurring outside event hours? Task 2: Deliverables
Scoping Memorandum (draft and final)
Task 3: CEQA Analysis
Subtask 3.1: VMT Screening Assessment
Pursuant to Senate Bill (SB) 743, the Governor’s Office of Land Use and Climate Innovation (LCI formerly OPR), updated the California Environmental Quality Act (CEQA) Guidelines to identify vehicle miles traveled (VMT), rather than vehicle level of service (LOS), as the appropriate measure of transportation impacts under CEQA.
Kittelson will prepare a VMT assessment consistent with the methodology established in the Task 2 Scoping Memorandum and approved by the City.
Based on the project's size and operational characteristics, Kittelson anticipates that the project will qualify for screening as a small project and/or a local-serving land use and therefore may not require a detailed VMT analysis. Accordingly, this scope of work includes a screening-level VMT assessment only and does not include a detailed VMT analysis.
Subtask 3.2 CEQA Checklist Items
Kittelson will address the four transportation questions CEQA Guidelines Appendix G Checklist. These Transportation checklist questions, including VMT, are as follows:
49 Section 3, Item # 3.5
33586
Durst Mansion Event Center Transportation Impact Study Page: 4 of 5 Kittelson & Associates, Inc.
Would the project:
a) Conflict with a program, plan, ordinance or policy addressing the circulation system, including transit, roadway, bicycle and pedestrian facilities?
b) Whether the project conflicts, or is inconsistent, with CEQA Guidelines section 15064.3, subdivision (b). – [VMT Assessment completed in Subtask 3.1]
c) Substantially increase hazards due to a geometric design feature (e.g. sharp curves or dangerous intersections) or incompatible uses (e.g. farm equipment)? d) Result in inadequate emergency access?
Task 4: Non-CEQA Focused Transportation Analysis (Optional) If it is determined during preparation of the scoping memorandum in this Task 2 that additional transportation and circulation analysis is required, we propose to perform the following supplemental analyses. The scope may be refined based on those findings, and the fee will be adjusted accordingly.
Subtask 4.1: Study Location and Traffic Counts
Kittelson proposes to analyze up to four intersections. Traffic counts will be collected at the study intersections during the two 2-hour peak periods to be determined in consultation with the Project applicant and City staff.
Subtask 4.2: LOS, Queuing and Gap Analysis
Existing intersection lane configurations and peak-hour turning movement volumes will be used to evaluate intersection operations during the peak hours. Level of Service (LOS) and average delay will be calculated for the study intersections using Synchro traffic analysis software. This will be conducted for existing, and exiting plus project conditions only.
Kittelson will also conduct a vehicle queuing analysis at the study intersections and project driveways to assess whether the project would affect available storage lengths or result in operational deficiencies.
In addition, Kittelson will evaluate driveway access conditions to determine whether adequate gaps are available for event attendees to safely enter and exit the site without creating undue conflicts or requiring abrupt braking maneuvers by motorists traveling on Spenceville Road. A sight distance assessment will also be conducted to confirm that the project driveways provide adequate visibility for safe ingress and egress in accordance with applicable engineering standards. The sight distance analysis will be limited to reviewing the site plan for any obstructions and estimating the stopping sight distance as per the CA MUTCD, 2026.
Task 5: Focused Transportation Impact Study Documentation Kittelson will summarize the results of the CEQA VMT analysis and Non-CEQA LOS analysis in a draft TIS memorandum and submit it to the City staff for review. Kittelson will address two rounds of non-conflicting comments and submit a final TIS report to be included in the environmental analysis.
Task 5: Deliverables
Draft TIS Memorandum
Final TIS Memorandum
50 Section 3, Item # 3.5
33586
Durst Mansion Event Center Transportation Impact Study Page: 5 of 5 Kittelson & Associates, Inc.
SCHEDULE
Kittelson will deliver a scoping memorandum within two (2) weeks of contracting, and a draft report within eight (8) weeks of written approval of the scoping memorandum.
BUDGET
Kittelson will perform the services described in this scope of work for a fee not to exceed $12,000. This fee excludes the optional Non-CEQA Focused Transportation Analysis task, which is estimated at $16,000. These costs do not include fees that the City may require to review the scoping agreement and studies. If the City elects to authorize the optional task, the total not-to-exceed fee for all services will be $28,000.
Monthly invoices will be issued based on time and materials basis. 51 Section 3, Item # 3.5
CITY COUNCIL MEETING STAFF REPORT
Meeting Date: September 22, 2026
SUBJECT: Consideration and Adoption of Resolution for Purchase of Environmental Mitigation Credits for Construction of the Wheatland Regional Sewer Pipeline Project PREPARED BY: Sean Grayson, City Manager
Dane Schilling, City Engineer
RECOMMENDATION:
Staff recommends that the Wheatland City Council consider adoption of a resolution approving the “Agreement for Sale of Mitigation Credits” with AKT Investments, Inc. for the Wheatland Regional Sewer Pipeline Project and authorizing staff to execute the agreement and purchase environmental mitigation credits for construction of the project.
DISCUSSION:
The Wheatland Regional Sewer Pipeline Project (“Project”) is a portion of the larger South Yuba County Wastewater Infrastructure Project (a coordinated effort between Yuba Water Agency (YWA), Olivehurst Public Utilities District (OPUD), Yuba County and the City of Wheatland). The Wheatland Regional Sewer Project consists of the first 7.72-miles of a conveyance pipeline and pump stations that are capable of transporting 1.5-million gallons of sewage daily from the Malone Avenue Pump Station in Wheatland to the southerly limits of the OPUD service area on Rancho Road in south Yuba County. OPUD will construct a pipeline from the terminus of this Project to the OPUD wastewater treatment plant.
The following is a partial list of City Council actions taken to advance the environmental work for the Project:
On July 28, 2020, the City Council adopted Resolution No. 35-20 approving the $2.6M grant/loan agreement to fund environmental and design efforts for the Wheatland Regional Sewer Pipeline Project (Project) and authorizing the City Manager to sign the agreement. On November 10, 2020, the City Council adopted Resolution No. 43-20 amending the FY 2020-21 Budget and authorizing the City Manager to proceed with environmental review and engineering design for the Project.
The City conducted an environmental review and prepared an Environmental Impact Report (EIR) for the Project (SCH No. 2021110022). Based on the EIR, a Notice of Determination was made by the City Council on February 28, 2023, and was filed by the County Recorder on March 2, 2023. On July 14, 2026, the City Council adopted Resolution No. 26-38, approving contract documents and authorizing a call for bids for construction of the Wheatland Regional Sewer Pipeline Project. 52 Section 3, Item # 3.6
City staff received bids for construction of the Project on August 25, 2026, and anticipates awarding the construction contracts on September 22, 2026. Prior to commencing construction, the City is required to purchase mitigation credits to satisfy the requirements of the environmental permits issued by the California Department Fish and Wildlife (CDFW) and United States Army Corps of Engineers (USACE) for the purpose of offsetting loss of environmental habitat associated with the project. In consultation with CDFW and USACE, the City’s environmental consultant for the Project, has identified the Antonio Mountain Ranch Mitigation Bank, owned by AKT Investments, Inc., as a suitable mitigation bank for meeting the requirements of the permits.
An “Agreement for Sale of Mitigation Credits” from AKT Investments, Inc. (Attachment ‘B’), has been provided to the City for purchase of the required mitigation credits. The City Attorney’s office has reviewed the agreement and has approved it as to form.
FISCAL IMPACT:
The total purchase price of the mitigation credits is $81,000. This cost was anticipated and included in the project budget. The purchase of environmental mitigation credits is a grant reimbursable expense.
No General Fund resources will be utilized to fund this action.
ATTACHMENTS:
A. Resolution
B. Agreement for Sale of Mitigation Credits
53 Section 3, Item # 3.6
Attachment ‘A’
RESOLUTION NO. 26-___
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF WHEATLAND AUTHORIZING
THE PURCHASE OF ENVIRONMENTAL MITIGATION CREDITS FROM
AKT INVESTMENTS, INC., IN THE AMOUNT OF $81,000.00 FOR CONSTRUCTION OF THE
WHEATLAND REGIONAL SEWER PIPELINE PROJECT
WHEREAS, on November 10, 2020, the City Council adopted Resolution No. 43-20 amending the FY 2020-21 Budget and authorizing the City Manager to proceed with environmental review and engineering design for the Wheatland Regional Project (“Project”); and
WHEREAS, the City has conducted an environmental review and prepared an Environmental Impact Report (EIR) for the Project (SCH No. 2021110022). Based on the EIR, a Notice of Determination was made by the City Council on February 28, 2023, and was filed with the County Recorder on March 2, 2023; and
WHEREAS, on July 14, 2026, the City Council adopted Resolution No. 26-38, approving documents for construction and authorizing a call for bids for construction for the Project; and WHEREAS, prior to commencing construction on the Project, the City is required to purchase environmental mitigation credits to satisfy the requirements of the environmental permits issued by the California Department Fish and Wildlife (CDFW) and United States Army Corps of Engineers (USACE) for the purpose of offsetting the loss of environmental habitat associated with the Project; and
WHEREAS, CDFW and USACE will accept credits purchased from the Antonio Mountain Ranch Mitigation Bank, owned by AKT Investments, Inc., as suitable mitigation for meeting the requirements of the permits for the Project.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Wheatland that the City Manager is authorized to take any and all actions necessary to purchase environmental mitigation credits in the amount of $81,000.00 from AKT Investments, Inc., to meet the requirements of the environmental permits for the Wheatland Regional Sewer Pipeline Project. 54 Section 3, Item # 3.6
The foregoing resolution was adopted by the City Council of the City of Wheatland at a regular meeting held on the 22nd day of September 2026 by the following vote:
AYES:
NOES:
ABSTAIN:
ABSENT:
The foregoing resolution is hereby approved.
________________________
Lisa McIntosh, Mayor
ATTEST:
________________________
Josie Camacho, City Clerk
55 Section 3, Item # 3.6
1 Antonio Mountain Ranch M.B.
AGREEMENT FOR SALE OF MITIGATION CREDITS
USACE No. SPK-2022-00533
NWP 14, 39, 58
CDFW EPIMS Notification No. YUB-55651-R2
WDID No. 5A58CR00206
Wheatland Regional Sewer Pipeline Project
(CWSRF Project no. C-06-8753-110)
Contract #51
This Agreement is entered into this _______ day of ____________2026, (“Effective Date”), by and between Antonio Mountain Ranch Mitigation Bank (“Bank”) and City of Wheatland (“Project Applicant”), jointly referred to as the “Parties”, as follows:
RECITALS
A. Lewis Antonio Mountain Ranch, LLC (“Bank Sponsor”) has developed the Antonio Mountain Ranch Mitigation Bank located in Placer County, California; and B. The Bank was approved by U.S. Army Corps of Engineers (“USACE”), U.S.
Environmental Protection Agency (“USEPA”), U.S. Fish and Wildlife Service (“SERVICE”), and California Department of Fish and Wildlife (“CDFW”) on June 6, 2018, and is currently in good standing with these agencies; and
C. The Bank has received approval from the SERVICE to offer Vernal Pool Fairy Shrimp Habitat Establishment and Vernal Pool Fairy Shrimp Habitat Preservation credits; USACE and USEPA to offer Vernal Pool, Seasonal Wetland, Perennial Stream, Intermittent Stream, and Perennial Stream credits; and CDFW to offer Intermittent Stream Preservation, Intermittent Stream Re-establishment, Intermittent Stream Riparian Enhancement, Intermittent Stream Enhancement, Perennial Stream Riparian Enhancement, Perennial Stream Enhancement, Perennial Marsh Rehabilitation, Riparian Re-establishment, Riparian Enhancement, Floodplain Seasonal Wetland Re-establishment, Tricolored Blackbird Nesting Habitat, Tricolored Blackbird Foraging Habitat, and Swainson’s Hawk Foraging Habitat credits for sale as compensation for the loss of vernal pool fairy shrimp habitat, vernal pools, seasonal wetlands, intermittent streams, perennial streams, perennial marsh, riparian habitat, tricolored blackbird nesting and foraging habitat, and Swainson’s hawk foraging habitat, respectively, through the Antonio Mountain Ranch Mitigation Bank Enabling Instrument (“BEI”); and
D. Project Applicant is seeking to implement the project described in Exhibit “A” attached hereto (“Project”), which would unavoidably and adversely permanently impact 0.014 acres of seasonal wetland, and 0.154 acres of streambank/bed and seeks to compensate for the loss by purchasing credits from Bank; and
E. Project Applicant has been authorized by CDFW to purchase from the Bank 0.02 seasonal wetland creation credits, and 0.16 stream channel credits upon confirmation by the Bank Sponsor of credit availability/adequate balance of credits remaining for sale; and 56 Section 3, Item # 3.6
2 Antonio Mountain Ranch M.B.
F. Project Applicant desires to purchase from Bank and Bank desires to sell to Project Applicant the 0.02 Seasonal Wetlands Creation credits, and 0.16 Intermittent Stream (CDFW – Preservation) credits.
NOW, THEREFORE, THE PARTIES AGREE AS FOLLOWS:
1. Bank hereby agrees to sell to Project Applicant and Project Applicant hereby agrees to purchase from Bank 0.02 Seasonal Wetlands Creation credits, and 0.16 Intermittent Stream (CDFW – Preservation) credits(the “Credits”) for the purchase price of EIGHTY-ONE THOUSAND AND 00/00 DOLLARS ($81,000.00). Promptly following the delivery of the purchase price by Project Applicant to Bank, Bank will deliver to Project Applicant an executed Bill of Sale in the manner and form as attached hereto and marked Exhibit “B”. The purchase price for said Credits shall be paid by cashier’s check or, at the option of Bank, wire transfer of funds according to written instructions by Bank to Project Applicant.
2. The sale and transfer herein are not intended as a sale or transfer to Project Applicant of a security, license, lease, easement, or possessory or non-possessory interest in real property, nor the granting of any interest of the foregoing.
3. Project Applicant shall have no obligation whatsoever by reason of the purchase of the Credits, to support, pay for, monitor, report on, sustain, continue in perpetuity, or otherwise be obligated or liable for the success or continued expense or maintenance in perpetuity of the Credits sold, or the Bank. Pursuant to the BEI and any amendments thereto, Bank shall monitor and make reports to the appropriate agency or agencies on the status of the Credits sold to Project Applicant.
Bank shall be fully and completely responsible for satisfying any and all conditions placed on the Bank or the Credits by all state or federal jurisdictional agencies.
4. The Credits sold and transferred to Project Applicant shall be non-transferable and nonassignable, and shall not be used as compensatory mitigation for any other project or purpose, except as set forth herein.
5. Project Applicant shall pay Bank a deposit fee of SIXTEEN THOUSAND TWO HUNDRED AND 00/00 Dollars ($16,200.00) in immediately available funds within 10 days of the Effective Date of this Agreement. The deposit fee shall be credited to the purchase price and shall be refunded to Project Applicant if the 30-day period runs, as provided for in Section 6, and this Agreement becomes null and void.
6. Project Applicant must provide Bank with the remaining SIXTY-FOUR THOUSAND EIGHT HUNDRED DOLLARS ($64,800) within 30 days of the effective date of the Effective Date of this Agreement. After the 30-day period this Agreement will be considered null and void.
7. Upon purchase of the Credits specified in Section 1 above, the Bank shall submit to the parties listed in the Notices section of the BEI, copies of the: a) Agreement for Sale of Mitigation Credits; b) Bill of Sale; c) Payment Receipt; and d) an updated ledger. The updated inventory / ledger must detail: i) Project Applicant; ii) Project Name; iii) Status (sale complete/sale not complete); iv) Credit Sale Date; v) SERVICE/USACE/CDFW/CEQA File or Permit Number (as applicable); vi) Total Number of Credits Authorized to Sell; vii) Total Number of Credits Sold to Date (inclusive); and ix) Balance of all Credits Available. The inventory / ledger should include all sales data from bank opening/establishment to the present. 57 Section 3, Item # 3.6
3 Antonio Mountain Ranch M.B.
IN WITNESS WHEREOF, the parties have executed this Agreement the day and year first above written.
BANK:
Antonio Mountain Ranch Mitigation Bank
Lewis Antonio Mountain Ranch, LLC, a California Limited Liability Company By: AKT Investments, Inc., a California corporation
Its: Manager
By: ______________________________
Ron Bertolina, Vice President
Date: ______________________________
PROJECT APPLICANT:
City of Wheatland
By:
Name: Sean Grayson
Title: City Manager
Date: ______________________________
Exhibit List:
A - Project Description
B - Bill of Sale
C - Payment Receipt
58 Section 3, Item # 3.6
4 Antonio Mountain Ranch M.B.
APPROVED
UNITED STATES FISH AND WILDLIFE SERVICE:
This Agreement fulfills a portion of the Project Applicant’s proposed_________________habitat conservation measures, as described in the Service’s Biological Opinion Service File Number ______________ dated ________. The Service verifies that Antonio Mountain Ranch Mitigation Bank is in good standing as of the date of this signature.
By: ______________________________ Date: ________________________ Sacramento Fish and Wildlife Office
59 Section 3, Item # 3.6
5 Antonio Mountain Ranch M.B.
Exhibit “A”
DESCRIPTION OF PROJECT
TO BE
MITIGATED
Wheatland Regional Sewer Pipeline Project (CWSRF Project no. C-06-8753-110) is limited to the installation of eight miles of regional sewer pipeline and associated structures, including 3 pump stations and a new City Public Works Corporation Yard at one of the pump stations sites as further described and depicted in the improvement plans and specification for the City of Wheatland Regional Sewer Pipeline Project dated 07/07/2026, and approved by City Council Resolution 26-38.
Project location
Address: Local roadways East and North of Wheatland
County: Yuba
Nearest City: Wheatland
Section 4, Township 13N, Range 5E, MDB&M
Latitude: 39°0’31.82” and Longitude: -121°25’25.88”
******
60 Section 3, Item # 3.6
6 Antonio Mountain Ranch M.B.
Exhibit “B”
USACE No. SPK-2022-00533
NWP 14, 39, 58
CDFW EPIMS Notification No. YUB-55651-R2
WDID No. 5A58CR00206
Wheatland Regional Sewer Pipeline Project
(CWSRF Project no. C-06-8753-110)
Contract #51
In consideration of EIGHTY-ONE THOUSAND AND 00/00 DOLLARS ($81,000.00), receipt of which is hereby acknowledged, Antonio Mountain Ranch Mitigation Bank does hereby bargain, sell and transfer to City of Wheatland, 0.02 Seasonal Wetlands Creation credits, and 0.16 Intermittent Stream (CDFW – Preservation) credits from the Antonio Mountain Ranch Mitigation Bank in Placer County, California, developed, and approved by U.S. Fish and Wildlife Service, U.S. Army Corps of Engineers, U.S. Environmental Protection Agency, and the California Department of Fish and Wildlife.
Lewis Antonio Mountain Ranch, LLC (Bank Sponsor) represents and warrants that it has good title to the credits, has good right to sell the same, and that they are free and clear of all claims, liens, or encumbrances.
Lewis Antonio Mountain Ranch, LLC (Bank Sponsor) covenants and agrees with the buyer to warrant and defend the sale of the credits hereinbefore described against all and every person and persons whomsoever lawfully claiming or to claim the same.
DATED: _____________________________________
BANK:
Antonio Mountain Ranch Mitigation Bank
Lewis Antonio Mountain Ranch, LLC, a California Limited Liability Company By: AKT Investments, Inc., a California corporation
Its: Manager
By: ______________________________
Ron Bertolina, Vice President
61 Section 3, Item # 3.6
7 Antonio Mountain Ranch M.B.
Exhibit “C-1”
Antonio Mountain Ranch Mitigation Bank
CONTRACT #51
CREDITS: PAYMENT RECEIPT
PROJECT APPLICANT INFORMATION
Name: City of Wheatland
Address: 111 C Street, Wheatland, CA 95692
Telephone: (530) 401-4610
Contact: Dane Schilling, City Engineer
PROJECTINFORMATION
Project Description: Wheatland Regional Sewer Pipeline Project USACE No.: SPK-2022-00533
CDFW SSA: EPIMS Notification No. YUB-55651-R2
WDID No.: 5A58CR00206
Species/Habitat Affected: 0.014 acres of seasonal wetland, and 0.154 acres of streambank/bed Credits to be Purchased: 0.02 acre – Seasonal Wetland creation, and 0.16 acre – Intermittent Stream (CDFDW – Preservation)
(at $450,000 per credit, total purchase price $81,000)
Payment Amount: $ 16,200.00 (20% of purchase price)
Project Location: City of Wheatland, Yuba County.
PAYMENTINFORMATION
Payee: Lewis Antonio Mountain
Ranch, LLC
Payer: City of Wheatland
Amount: $16,200.00
Method of payment: Check No.________ Wire: __________
Received by: Date:
(Signature)
Name: Chris Donnelly Title: CFO
62 Section 3, Item # 3.6
8 Antonio Mountain Ranch M.B.
Exhibit “C-2”
Antonio Mountain Ranch Mitigation Bank
CONTRACT #51
CREDITS: PAYMENT RECEIPT
PROJECT APPLICANT INFORMATION
Name: City of Wheatland
Address: 111 C Street, Wheatland, CA 95692
Telephone: (530) 401-4610
Contact: Dane Schilling, City Engineer
PROJECTINFORMATION
Project Description: Wheatland Regional Sewer Pipeline Project USACE No.: SPK-2022-00533
CDFW SSA: EPIMS Notification No. YUB-55651-R2
WDID No.: 5A58CR00206
Species/Habitat Affected: 0.014 acres of seasonal wetland, and 0.154 acres of streambank/bed Credits to be Purchased: 0.02 acre – Seasonal Wetland creation, and 0.16 acre – Intermittent Stream (CDFDW – Preservation)
(at $450,000 per credit, total purchase price $81,000)
Payment Amount: $ 64,800.00 (80% of purchase price)
Project Location: City of Wheatland, Yuba County.
PAYMENTINFORMATION
Payee: Lewis Antonio Mountain
Ranch, LLC
Payer: City of Wheatland
Amount: $64,800.00
Method of payment: Check No.________ Wire: __________
Received by: Date:
(Signature)
Name: Chris Donnelly Title: CFO
63 Section 3, Item # 3.6
STAFF REPORT
Meeting Date: September 22, 2026
SUBJECT: Consideration of a Presentation and Update on the Status of an Agreement Between Olivehurst Public Utility District (OPUD) and the City of Wheatland Regarding the South Yuba County Regional Wastewater Project
PREPARED BY: Sean Grayson, City Manager
RECOMMENDATION:
Staff recommends that the Wheatland City Council receive the presentation and update and provide any needed direction.
DISCUSSION:
The City of Wheatland and Olivehurst Public Utility District, along with Yuba County and Yuba Water Agency have, for the past six years, been working together to develop a regional solution to wastewater treatment needs in South Yuba County. The City of Wheatland’s wastewater treatment plant is aging, has limited treatment capacity to accommodate infill growth and does not meet current environmental standards for disposal of municipal wastewater. A portion of the City’s wastewater treatment plant is located on the river side of the Bear River Levee, which leaves the plant at risk for potential flooding.
The South Yuba County Regional Wastewater Project will result in construction of a wastewater conveyance system from Wheatland to the OPUD wastewater treatment plant. The project has been separated into two segments. The first segment is Wheatland’s responsibility and will transport wastewater from Wheatland up Spenceville Road, Jasper Lane and South Beale Road to Pump Station No. 3 on Rancho Road. The second segment will be managed by OPUD and will continue the pipeline from Pump Station No. 3 to the OPUD wastewater treatment plant. Both Wheatland and OPUD have received bids for their portions of the project and are ready to award contracts once the project financing has been finalized.
OPUD and the City have been working to create a term sheet that outlines conditions and responsibilities for both agencies as it relates to the various stages and contracts involved in the project. Both agencies have tentatively approved a term sheet that is in legal review. Either the term sheet will be incorporated into amendments to the three agreements between OPUD and the City or an MOU will be developed to direct the implementation of the conditions of the term sheet. The updated agreements and/or MOU will be in a format approved by the City Attorney. OPUD has indicated they intend to call a special meeting to approve the agreements or MOU in the future. Given the timing of contract awards and the initiation of the Wheatland portion of the project, staff is requesting in another agenda item for the City Council to approve two construction contracts and a construction management contract for the Wheatland portion of the project referred to as “Contract 1”. Staff will proceed to work with the 64 Section 6, Item # 6.1
awardees toward pre-construction activities but will not issue a notice to proceed unless and until the agreements are amended or an MOU is approved by both OPUD and the City.
FISCAL IMPACT:
There is no direct fiscal impact associated with this action. The estimated construction cost of this project is more than $100 million. This regional solution has been endorsed by the State Water Resources Control Board, which has approved a $75 million grant to fund a major portion of the project. The Yuba County Board of Supervisors approved a Memorandum of Understanding (MOU) with Wheatland and OPUD wherein the County committed to loan up to $10 million for the construction phase of the project.
The Estom Yumeka Maidu Tribe of the Enterprise Rancheria (Enterprise) has also approved an MOU with OPUD and Wheatland for an additional $10 million loan. The landowner and developer AKT has offered to partner with the City for pre-payment of impact fees up to $5 million. A $23 million loan and $3.9 million grant from the United States Department of Agriculture is pending approval for the project.
ATTACHMENTS:
None
65 Section 6, Item # 6.1
CITY COUNCIL MEETING STAFF REPORT
Meeting Date: September 22, 2026
SUBJECT: Consideration and Adoption of a Resolutions Awarding Construction Contracts for Construction of the Wheatland Regional Sewer Pipeline Project [CWSRF Project No.
C-06-8753-110]; and Authorizing the City Manager to Execute Change Orders NotTo-Exceed the Project Budget.
PREPARED BY: Sean Grayson, City Manager
Dane Schilling, City Engineer
RECOMMENDATION:
Staff recommends that the Wheatland City Council consider adoption of resolutions rejecting a bid protest; awarding construction contracts to RCI General Engineering and Mountain Cascade, Inc.; and authorizing the City Manager to execute change orders not to exceed the project budget for the Wheatland Regional Sewer Pipeline Project.
DISCUSSION:
The Wheatland Regional Sewer Pipeline Project (“Project”) is a portion of the larger South Yuba County Wastewater Infrastructure Project (a coordinated effort between Yuba Water Agency (YWA), Olivehurst Public Utilities District (OPUD), Yuba County and the City of Wheatland). The Wheatland Regional Sewer Project consists of the first 7.72-miles of a conveyance pipeline and pump stations that are capable of transporting 1.5-million gallons of sewage daily from the Malone Avenue Pump Station in Wheatland to the southerly limits of the OPUD service area on Rancho Road in south Yuba County. OPUD will construct a pipeline from the terminus of this Project to the OPUD wastewater treatment plant.
The following is a partial list of City Council actions taken to advance the design and environmental work for the Project:
On July 28, 2020, the City Council adopted Resolution No. 35-20 approving the $2.6M grant/loan agreement to fund environmental and design efforts for the Wheatland Regional Sewer Pipeline Project (Project) and authorizing the City Manager to sign the agreement. On November 10, 2020, the City Council adopted Resolution No. 43-20 amending the FY 2020-21 Budget and authorizing the City Manager to proceed with environmental review and engineering design for the Project.
April 27, 2021, the Basis of Design Report for the Project was presented to the Wheatland City Council and adopted by Resolution No.16-21.
66 Section 6, Item # 6.2
October 11, 2022, the City Council adopted Resolution No. 34-22, which, among other actions, authorized acceptance of an additional $2 million loan from the Yuba Water Agency for work associated with environmental, engineering design, right-of-way acquisition and grant funding work for the Project.
The City conducted an environmental review and prepared an Environmental Impact Report (EIR) for the Project (SCH No. 2021110022). Based on the EIR, a Notice of Determination was made by the City Council on February 28, 2023, and was filed by the County Recorder on March 2, 2023. On November 25, 2025, City Council adopted Resolution No. 58-25 approving contract documents and authorizing a call for bids for construction of the Wheatland Regional Sewer Pipeline Project.
On February 19, 2026, the bid period closed with the City receiving 13 bids for the Project. Per the bid documents, the bids were valid for 90-days after the bid opening (thru May 20, 2026). On February 13, 2026, the Yuba Water Agency experienced a catastrophic failure of the penstock at the New Colgate Powerhouse. Shortly thereafter, Yuba Water Agency withdrew its intended future financial support for the Project. In response to that action, the City Council, on May 12, 2026, adopted Resolution No. 26-19 authorizing an extension to the 90-day bid expiration date by 35 calendar days, from May 20, 2026, to June 24, 2026, to provide additional time for staff to identify replacement funding for the Project.
While potential additional funding sources have been identified, including loans from Yuba County and the Estom Yumeka Maidu Tribe of the Enterprise Rancheria, it has been determined that the project scope must be altered to enable the City to fully fund the Project. Due to the sudden loss of funding, the City Council adopted a resolution on June 23, 2026 rejecting all bids for the February 19 bids and authorized staff to initiate revisions to alter the project scope and return to Council to rebid the Project. On July 14, 2026, the City Council adopted Resolution No. 26-38, approving contract documents and authorizing a call for bids for construction of the Wheatland Regional Sewer Pipeline Project.
Accordingly, the Project was re-advertised for bids between July 17, 2026, and August 25, 2026 (39 days).
On August 25, 2026, the City received ten bids for the Project. Bidders were allowed to bid on just the pipeline portion (Schedule A), just the pump station portion (Schedule B), or to bid on both components (Schedule C). The City would award contracts to the contractor or contractors that provided the lowest possible monetary combination of bid results. The following is a summary of the bids received, with the apparent low bidders for Schedule A and Schedule B (equaling the lowest combined total bid amount) denoted by asterisks:
67 Section 6, Item # 6.2
On September 1, 2026, the City received a bid protest from Marques General Engineering (MGE), the apparent second low bidder on Schedule A, protesting the bid received from RCI General Engineering (RCI) the apparent low bidder (see Attachment 3). On September 9, 2026, RCI provided a formal response to the bid protest (Attachment 4). The protest from MGE and response from RCI were reviewed by the City Engineer and City Attorney, and on September 15, 2026, the City issued a response letter to MGE conditionally rejecting the bid protest (Attachment 5).
On September 15, 2026, the City Engineer issued a Notice of Intent to Award to RCI General Engineering of Oroville, California for work identified in Schedule A and to Mountain Cascade, Inc. of Livermore, California for work identified in Schedule B (see Attachment 6).
Staff performed a detailed review of the apparent low bids, insurance, license information, and other required documents and responses accompanying the bids, and no substantial irregularities were found.
Therefore, Staff is recommending that the City Council:
1. Reject the bid protest filed by Marques General Engineering against the bid submitted by RCI General Engineering for Schedule A - Pipelines;
2. Award a construction contract to RCI General Engineering in the amount of $16,618,050.00 for construction of the work in Schedule A;
3. Award a construction contract to Mountain Cascade, Inc. in the amount of $27,918,000.00 for Schedule B (Staff is not recommending awarding any Bid Alternatives at this time); 68 Section 6, Item # 6.2
4. Authorize the City Manager to execute contract change orders up to $1,442,968.00 for unforeseen and additional costs that may arise during the course of construction.
FISCAL IMPACT:
The total as-bid construction cost for the Project of $44,536,050.00 and contingency of $1,442,968.00 are within in the project budget and will be paid for under the various funding sources for the Project including State Water Resources Control Board grant funds, other outside loan funding, and City of Wheatland sewer impact fees. No General Fund resources will be utilized for this Project.
While the current funding package secured for the Project is sufficient to support the Phase 1A construction contracts, additional funding actions remain necessary to complete the broader Regional Wastewater Project. If additional funding is not secured and the Project is unable to proceed to completion as contemplated (both Phase 1A and Phase 1B), the City would remain responsible for funding any resulting shortfall and for satisfying its contractual obligations under the proposed construction contracts. Depending on the timing and circumstances, such obligations could include costs associated with work performed, contractor commitments, materials procurement, project delays, project administration, contract closeout, and other related expenses.
In addition, certain property acquisitions necessary for Project implementation remain outstanding.
Because these acquisitions are critical-path items, delays in securing the required property interests could affect Project scheduling, increase costs, delay construction activities, or otherwise impede completion of the Regional Wastewater Project.
Accordingly, successful completion of the Project remains dependent upon continued coordination of funding, interagency agreements, property acquisition efforts, and other implementation requirements.
ATTACHMENTS:
Attachment 1 – Resolution to Award Construction Contract to RCI General Engineering Attachment 2 – Resolution to Award Construction Contract to Mountain Cascade, Inc.
Attachment 3 – Bid Protest from Marques General Engineering Attachment 4 – Response to MGE Bid Protest from RCI General Engineering Attachment 5 – Response to MGE Bid Protest from City of Wheatland Attachment 6 – Notice of Intent to Award
69 Section 6, Item # 6.2
Attachment ‘A’
RESOLUTION NO. 26-___
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF WHEATLAND AUTHORIZING
THE CITY MANAGER TO ENTER INTO A CONSTRUCTION CONTRACT WITH RCI GENERAL ENGINEERING IN THE AMOUNT OF $16,618,050.00 FOR CONSTRUCTION OF SCHEDULE APIPELINES FOR THE WHEATLAND REGIONAL SEWER PIPELINE PROJECT AND AUTHORIZING THE CITY MANAGER TO EXECUTE CONTRACT CHANGE ORDERS NOT TO EXCEED $538,424.00 WHEREAS, on November 10, 2020, the City Council adopted Resolution No. 43-20 amending the FY 2020-21 Budget and authorizing the City Manager to proceed with environmental review and engineering design for the Wheatland Regional Project (“Project”); and;
WHEREAS, on April 27, 2021, the Basis of Design Report for the Project was presented to the Wheatland City Council and adopted by Resolution No.16-21; and WHEREAS, the City conducted an environmental review of the Project, prepared an Environmental Impact Report (EIR), the City Council made a Notice of Determination on the EIR on February 28, 2023, and the City filed the Notice of Determination with the County Recorder on March 2, 2023; and
WHEREAS, on July 14, 2026, the City Council approved the contract documents for construction including a notice to bidders, bidders’ book, sample contract, plans and specifications for the Wheatland Regional Sewer Pipeline Project; and authorized City staff to call for bids for construction of the project; and
WHEREAS, on August 25, 2026, the bid period closed, and the City received ten bids for construction of the Project, and
WHEREAS, the City Engineer has reviewed the bids and determined that RCI General Engineering of Oroville, California submitted the lowest responsive and responsible bid for construction of Schedule A - Pipelines in the amount of $16,618,050.00; and WHEREAS, on September 1, 2026, the City received a bid protest from Marques General Engineering alleging irregularities in the bid submitted by RCI General Engineering; and WHEREAS, the City Engineer and City Attorney have reviewed the bid protest submitted by Marques General Engineering and have determined that the alleged irregularities are unfounded and therefore recommend that the bid protect be rejected by the City Council. 70 Section 6, Item # 6.2
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Wheatland asfollows for construction of improvements known as Schedule A – Pipelines of the Wheatland Regional Sewer Pipeline Project:
1. the City Council hereby rejects the bid protest submitted by Marques General Engineering, dated September 1, 2026, challenging the apparent low bidder’s bid;
2. the City Council authorizes the City Manager to enter into a construction contract in the amount of $16,618,050.00 with RCI General Engineering of Oroville, California; and
3. authorizes the City Manager to expend an additional $538,424.00 for additional and unforeseen costs that may arise during construction of Schedule A – Pipelines.
The foregoing resolution was adopted by the City Council of the City of Wheatland at a regular meeting held on the 22nd day of September 2026, by the following vote:
AYES:
NOES:
ABSTAIN:
ABSENT:
The foregoing resolution is hereby approved.
________________________
Lisa McIntosh, Mayor
ATTEST:
________________________
Josie Camacho, City Clerk
71 Section 6, Item # 6.2
Attachment ‘A’
RESOLUTION NO. 26-___
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF WHEATLAND AUTHORIZING
THE CITY MANAGER TO ENTER INTO A CONSTRUCTION CONTRACT WITH MOUNTAIN CASCADE INC. IN THE AMOUNT OF $27,918,000.00 FOR
CONSTRUCTION OF SCHEDULE B-PUMP STATIONS FOR THE WHEATLAND REGIONAL
SEWER PIPELINE PROJECT AND AUTHORIZING THE CITY MANAGER TO EXECUTE CONTRACT CHANGE ORDERS NOT TO EXCEED $904,543.00
WHEREAS, on November 10, 2020, the City Council adopted Resolution No. 43-20 amending the FY 2020-21 Budget and authorizing the City Manager to proceed with environmental review and engineering design for the Wheatland Regional Project (“Project”); and;
WHEREAS, on April 27, 2021, the Basis of Design Report for the Project was presented to the Wheatland City Council and adopted by Resolution No.16-21; and WHEREAS, the City conducted an environmental review of the Project, prepared an Environmental Impact Report (EIR), the City Council made a Notice of Determination on the EIR on February 28, 2023, and the City filed the Notice of Determination with the County Recorder on March 2, 2023; and
WHEREAS, on July 14, 2026, the City Council approved the contract documents for construction including a notice to bidders, bidders’ book, sample contract, plans and specifications for the Wheatland Regional Sewer Pipeline Project; and authorized City staff to call for bids for construction of the project; and
WHEREAS, on August 25, 2026, the bid period closed, and the City received ten bids for construction of the Project, and
WHEREAS, the City Engineer has reviewed the bids and determined that Mountain Cascade, Inc. of Livermore, California submitted the lowest responsive and responsible bid for construction of Schedule B – Pump Stations in the amount of $27,918,000.00.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Wheatland asfollows for construction of improvements known as Schedule B–Pump Stations of the Wheatland Regional Sewer Pipeline Project:
1. the City Council authorizes the City Manager to enter into a construction contract with Mountain Cascade, Inc. of Livermore, California in the amount of $27,918,000.00; and 72 Section 6, Item # 6.2
2. authorizes the City Manager to expend an additional $904,543.00 for additional and unforeseen costs that may arise during construction of Schedule B – Pump Stations.
The foregoing resolution was adopted by the City Council of the City of Wheatland at a regular meeting held on the 22nd day of September 2026, by the following vote:
AYES:
NOES:
ABSTAIN:
ABSENT:
The foregoing resolution is hereby approved.
________________________
Lisa McIntosh, Mayor
ATTEST:
________________________
Josie Camacho, City Clerk
73 Section 6, Item # 6.2
Attachment 'C'
74 Section 6, Item # 6.2
75 Section 6, Item # 6.2
76 Section 6, Item # 6.2
77 Section 6, Item # 6.2
78 Section 6, Item # 6.2
Sean J. Filippini
[email protected]
916.520.5430 Direct
916.520.5830 Fax
Downey Brand LLP
621 Capitol Mall, 18th Floor
Sacramento, CA 95814
916.444.1000 Main
downeybrand.com
September 9, 2026
VIA E-MAIL
Dane H. Schilling
City Engineer
City of Wheatland
111 C Street
Wheatland, CA 95692
[email protected]
Re: Response to Marques General Engineering, Inc. Bid Protest Wheatland Sewer Pipeline Project; Project C-06-8753-110 Dear Mr. Schilling:
This law firm represents RCI General Engineering (“RCI”). RCI is the lowest, responsive, responsible bidder for the Wheatland Sewer Pipeline Project; Project C-06-8753-110 (the “Project”).
This letter responds to the September 1, 2026 letter submitted by Marques General Engineering, Inc. (“MGE”) protesting the City of Wheatland’s anticipated award of the contract to RCI as the apparent low, responsive, responsible bidder (the “Protest”). We have extensively reviewed the Protest. It has no legal or factual merit and should be summarily rejected.
In its effort to persuade the City to pay over $500,000 more for the exact same scope of work, MGE’s Protest asserts objectively false facts that are foundational to its premise, manufactures requirements that don’t exist anywhere in the bid documents, and solely points to pure technicalities that have no practical impact on any aspect of RCI’s bid. It then tellingly proceeds to offer next to no analysis supporting the bald assertion that RCI’s bid “contains material irregularities that cannot be waived as a matter of law.” Remarkably, the Protest essentially concedes its extensive shortcomings. The Protest pointed to a delay by the City in providing information and claimed that the delay resulted in “inadequate time to prepare a proper protest.” The City responded by extending the protest period to September 8 and by expressly inviting MGE to supplement the Protest. Yet MGE tellingly did not accept the City’s invitation to supplement the Protest despite MGE’s claimed inability to “prepare a proper protest.”
Attachment 'D'
The Protest is not a close call and does not come remotely close to justifying the needless waste of over half a million dollars in taxpayer funds for which it advocates. Indeed, the Protest itself 79 Section 6, Item # 6.2
Dane H. Schilling
September 9, 2026
tells us everything we need to know about its merits: it is the product of MGE’s inability to “prepare a proper protest.” RCI respectfully requests that the City reject the Protest in its entirety and proceed promptly to award the contract to RCI, the lowest, responsive, responsible bidder.
I. The City’s Standard of Review.
The Protest points to five alleged irregularities in RCI’s bid in support of its assertion that the bid is materially non-responsive. As the protesting party, the burden is on MGE to establish that its claimed irregularities satisfy two different tests.
First, MGE must establish that a claimed irregularity renders the bid non-responsive. A bid is responsive if it conforms to, or is “responsive” to, the bid specifications. (Taylor Bus Service, Inc. v. San Diego Board of Education (1987) 195 Cal.App.3d 1331, 1341.) If the City concludes that the claimed irregularity does not render the bid non-responsive, the inquiry ends and the protest is summarily rejected without any further consideration.
Second, if MGE can establish that a claimed irregularity renders the bid non-responsive, it must also establish that the irregularity is “material.” An irregularity is immaterial as a matter of law if it does not affect price, quality, quantity, or give RCI a competitive advantage. (Konica Business Machines v. Regents of the University of California (1988) 206 Cal.App.3d 449, 454; Ghilotti Construction Co. v. Richmond (1996) 45 Cal.App.4th 897, 904.) California law dictates that if the irregularity is immaterial, the City has broad discretion to waive it—and generally should, so as to avoid the delay and expense to the public of rejecting the lowest bid over an immaterial technicality. (Ghilotti, supra, 45 Cal.App.4th at pp. 904–905.) In the event that the claimed variance is immaterial, the City may reject the Protest.
II. Each Ground Raised in the Protest is Meritless.
Although the Protest identifies five different claimed irregularities in RCI’s bid, it tellingly provides no argument or analysis regarding how each alleged irregularity: 1) makes the bid nonresponsive; and 2) is material and affects price, quality, quantity, or gives RCI a competitive advantage.
The only remote analysis provided relates to argument that RCI failed to “submit a valid bid bond” and that this failure resulted in a competitive advantage. (Protest at p. 4.) But there is zero analysis supporting the conclusion that RCI’s bid bond is not valid.
There is zero argument or analysis as to how any of the five claimed irregularities render RCI’s bid non-responsive, let alone how any of the five claimed irregularities are material (i.e. affect price, quality, quantity, or give RCI a competitive advantage).
For this reason alone, the City should reject the Protest. The burden was on MGE to establish both non-responsiveness and materiality. The Protest does neither.
Nevertheless, RCI addresses each claimed irregularity below. 80 Section 6, Item # 6.2
Dane H. Schilling
September 9, 2026
A. MGE is Mistaken About The Absence of A Corporate Seal.
MGE’s lead claimed irregularity is an assertion that RCI failed to emboss its bid with its corporate seal. That assertion is factually false. The bid that RCI submitted to the City included its embossed corporate seal. It appears that in its haste to come up with arguments to support its Protest, MGE did not consider that the scanned and emailed copy of RCI’s bid that it apparently received from the City did not capture the fact that the bid submitted to the City was, in fact, embossed. Therefore, the submitted bid is clearly responsive. For this reason alone, MGE’s lead argument must be summarily rejected.
However, even assuming that RCI did not emboss the bid it submitted to the City with its corporate seal, this would have been of no consequence whatsoever—i.e. it would not have been “material.” California law does not require a corporation to have or use a seal, and the absence of one does not affect the validity of an instrument the corporation executes. (Corp. Code, § 207.) RCI’s bid form was signed by Spencer Mendez, Chief Operating Officer, and attested by Jake Richter, Corporate Secretary — the two signatures the form itself requires — and Mr.
Mendez’s authority to bind RCI is independently confirmed by the Board of Directors’ and Shareholder’s written consents submitted with the bid. The absence of an impressed seal does not affect the amount or scope of RCI’s bid, does not create any doubt that RCI is bound by its bid, and confers no advantage on RCI relative to any other bidder.
B. RCI’s Bidder’s Bond Fully Complies with Section 00 40 10.
MGE next contends that the Bidder’s Bond “does not have an acknowledgement of the Principal’s or Contractor’s signature.” This mischaracterizes the bond form and manufactures a requirement that is not stated or even contemplated in the bid documents. Section 00 40 10 requires only the Principal’s signature, printed name, and business address — all of which RCI provided (Spencer Mendez; RCI General Engineering; P.O. Box 2531, Oroville, CA 95966).
The notarized acknowledgment included in RCI’s bid package authenticates the signature of Elizabeth Collodi as attorney-in-fact for Western Surety Company, because it is the surety’s delegated signing authority — not the contractor’s own signature — that requires notarial proof, consistent with the accompanying Western Surety power of attorney. RCI also submitted the California Department of Insurance Certificate of Authority confirming that Western Surety is an admitted surety in California, together with a Department of Insurance company-profile printout confirming the same, exactly as the Instructions to Bidders require. The bond, on its face, is fully executed, in the amount of ten percent of RCI’s total bid, on the form included in the Contract Documents.
Accordingly, this claimed irregularity is no irregularity at all. The bid bond is plainly valid and MGE has failed to establish that there is any responsiveness issue here.
C. RCI’s Listed Projects Satisfy Section 00 40 45, Which Does Not Request the Information MGE Claims Is Missing.
MGE next asserts that “none of the provided projects specifically indicate” that RCI meets the fused-HDPE/HDD experience threshold. But Section 00 40 45’s certification form does not ask bidders to state pipe material or linear footage for each listed project — it asks only for the 81 Section 6, Item # 6.2
Dane H. Schilling
September 9, 2026
project name, owner, construction cost, contract dates, and owner/engineer contacts, and RCI completed every field the form requests.
Several of RCI’s listed projects, including the Module 5 Phase C Project and the Palermo Dry Well Consolidation Project are pipeline installation projects of the type contemplated by the qualification standard. The form itself contemplates that the City will verify bidder experience with the listed references. Therefore, RCI’s bid included 100% of the information that the bid documents required for project experience. Therefore, this claimed irregularity is no irregularity at all. RCI’s bid is responsive.
That aside, RCI’s past projects do, in fact, satisfy the condition of pipeline installations of 2,000 feet or greater. RCI will separately provide supplemental information to the City establishing the details of the past projects and welcomes the City to contact its references.
Lastly, to the extent that this requirement was an issue (it isn’t), it bears on the question as to whether RCI is a responsible bidder, not whether RCI’s bid is responsive. Accordingly, as a matter of law, it could not even be a basis for summary rejection of RCI’s bid as non-responsive. (Great West Contractors, Inc. v. Irvine Unified School Dist. (2010) 187 Cal.App.4th 1425, 1447– 1450.)
D. RCI’s Corporate Authorization Documents Establish Mr. Mendez’s Authority to Execute the Bid and Bond.
Finally, MGE’s final two claimed irregularities point to a reference to “Bonds from InterWest” in RCI’s corporate resolutions, and to Richter Construction, Inc.’s appearance as the signing shareholder on the Shareholder’s written consent, as supposed inconsistencies. Neither undermines RCI’s bid.
The Board of Directors’ and Shareholder’s written consents broadly authorize Spencer Mendez to execute, among other things, “Bonds … for submitting with bids on Public Works projects” and “Proposal forms for submitting bids on Public Works projects.” The parenthetical reference to a particular bonding agency is, at most, descriptive template language; it does not purport to condition or narrow Mr. Mendez’s authority to bonds issued through any single agency, and MGE identifies no language in the resolutions that does so. Read as a whole, the resolutions satisfy the actual requirement of Article 10.3(C)(3) — a board resolution “showing the authority of the officer signing the Bid to execute Bid on behalf of the corporation” — which they plainly do.
Richter Construction, Inc.’s appearance as a shareholder is likewise unremarkable; it reflects RCI’s ownership structure and has no bearing on whether the Board of Directors validly authorized Mr. Mendez to sign. MGE has identified no evidence that Mr. Mendez lacked actual authority to execute RCI’s bid or bond.
Finally, we have reviewed a September 4 letter from John Hopkins, Vice-President of InterWest Insurance Company, which will be separately forwarded to the City. The Hopkins letter explains that InterWest is a licensed bond broker for various sureties, including Western Surety Company.
The Hopkins letter further explains that InterWest has the authority to legally bind Western 82 Section 6, Item # 6.2
Dane H. Schilling
September 9, 2026
Surety Company and that Mr. Mendez has express authority to sign bonds brokered by InterWest. Notably, Mr. Hopkins points out that this type of relationship is standard for all sureties that provide public works bonds. There is zero question as to the validity of the bid bond.
III. Conclusion.
For the foregoing reasons, RCI respectfully requests that the City summarily reject MGE’s protest and proceed promptly to award the Project contract to RCI as the lowest, responsive, responsible bidder.
RCI reserves all rights to supplement this response, to respond to any further submission by MGE, and to be heard before the City Council or other decisionmaker prior to any final determination adverse to RCI.
Please do not hesitate to contact me with any questions.
Sincerely,
DOWNEY BRAND LLP
Sean J. Filippini
cc: Jason Anderson, VP Marques General
Engineering (via email: [email protected])
5332161.3
83 Section 6, Item # 6.2
City of Wheatland
111 C Street
Wheatland, CA 95692
Phone 530-633-2761
Fax 530-633-9102
September 15, 2026
Via Email: [email protected]
Marques General Engineering, Inc.
Jason Anderson – Vice President, Estimating
200 S Harding Blvd.
Roseville, CA 95678
Attn: Jason Anderson – Vice President, Estimating
Re: Response to Letter of Bid Protest for the Wheatland Regional Sewer Pipeline Project Dear Mr. Anderson:
The City of Wheatland is in receipt of a letter from Marques General Engineering (MGE) dated September 1, 2026, which protests the bid received by RCI General Engineering (RCI), the apparent low bidder (“Protest Letter”) for the above mentioned project.
City Staff, including legal counsel, have reviewed the Protest Letter which asserts that RCI failed to provide certain requisite information with their bid. The City provides the following responses to the five alleged irregularities contained in the Protest Letter:
1. Corporate Seal – The Protest Letter alleges that RCI’s bid lacked a corporate seal. While the corporate seal did not appear on the electronically scanned (PDF) file that was provided to MGE by the City, the City Clerk physically examined the original document in question and has verified that an embossed corporate seal is present on the original document.
2. Acknowledgment of Bidders Bond – The Protest Letter contends that the Bidder’s Bond “does not have an acknowledgement of the Principal’s or Contractor’s signature”. A notarized acknowledgement of the signature of the bidder on the bond is not a requirement stated in the bid documents. Section 00 40 10 only requires the Principal’s signature, printed name, and business address which were provided. In addition, the signatory’s signature is duly and properly acknowledged by notary as required elsewhere in the bid package submitted.
3. Fused HDPE Pipeline Experience – The Protest Letter alleges that “none of the provided projects specifically indicate” that RCI meets the fused-HDPE/HDD experience threshold. As part of the City’s review of bids submitted, the RCI’s experience claimed on various required in Section 00 40 45 was reviewed and validated by City Staff.
4. Written Consent of Bonding Company – The Protest Letter alleges “the Written Consent document outlines signatory authority for "Bonds from Interwest", however, the bid bond submitted and signed is from Western Surety”. The City has reviewed the documents provided Attachment 'E'
84 Section 6, Item # 6.2
and determined that Interwest is an authorized bonding agent for Western Surety and that the bond presented is valid.
5. Written Consent of RCI General Engineering – The Protest Letter alleges “the Written Consent document is for RCI General Engineering, however the signatory portion indicates Richter Construction, Incorporated”. The City has reviewed the documents provided and determined that Mr. Mendez is in fact duly authorized by RCI’s Board of Directors to execute bid documents on behalf of RCI.
In conclusion, City Staff has determined that assertions made in the protest letter are not valid and do not constitute rejecting the bid submitted by the apparent low bidder. Accordingly, City Staff has recommended to the City Council that they reject the protest made by MGE and award the Schedule APipelines construction contract to RCI General Engineering at their September 22, 2026, City Council meeting.
Dane H. Schilling, PE
City Engineer
City of Wheatland
CC: Sean Grayson – City Manager
Gavin Ralphs – Assistant City Attorney
85 Section 6, Item # 6.2
City of Wheatland
111 C Street
Wheatland, CA 95692
Phone 530-633-2761
Fax 530-633-9102
September 15, 2026
NOTICE OF INTENT TO AWARD
The City of Wheatland California has reviewed the bids received on August 25, 2026, for the Wheatland Regional Sewer Pipeline Project [CWSRF Project No. C-06-8753-110]. After careful review of the bids, City staff has recommended to the City Council to award two contracts for the project at the September 22, 2026, City Council meeting as follows:
BID SCHEDULE A – PIPELINES
Awardee: RCI General Engineering of Oroville, CA
Contractors License No.: 1024998
Award Amount: $16,618,050.00
BID SCHEDULE B – PUMP STATIONS
Awardee: Mountain Cascade, Inc. of Livermore, CA
Contractors License No.: 422496
Award Amount: $27,918,000.00
Dane H. Schilling, PE
City Engineer
City of Wheatland, California
Attachment 'F'
86 Section 6, Item # 6.2
CITY COUNCIL MEETING STAFF REPORT
Meeting Date: September 22, 2026
SUBJECT: Consideration and Adoption of a Resolution Authorizing the City Manager to Execute a Professional Service Agreement for Construction Management and Inspection, and Issue Task Orders for Engineering and Environmental Support Services During Construction of the Wheatland Regional Sewer Pipeline Project [CWSRF Project No.
C-06-8753-110]
PREPARED BY: Sean Grayson, City Manager
Dane Schilling, City Engineer
RECOMMENDATION:
Staff recommends that the Wheatland City Council consider adoption of a resolution authorizing the City Manager to execute professional service agreements for construction management and inspection (CM&I) services, and issue task orders for engineering services during construction and environmental support services during construction of the Wheatland Regional Sewer Pipeline Project.
DISCUSSION:
The Wheatland Regional Sewer Pipeline Project (“Project”) is a portion of the larger South Yuba County Wastewater Infrastructure Project (a coordinated effort between Yuba Water Agency (YWA), Olivehurst Public Utilities District (OPUD), Yuba County and the City of Wheatland). The Wheatland Regional Sewer Project consists of the first 7.72-miles of a conveyance pipeline and pump stations that are capable of transporting 1.5-million gallons of sewage daily from the Malone Avenue Pump Station in Wheatland to the southerly limits of the OPUD service area on Rancho Road in south Yuba County. OPUD will construct a pipeline from the terminus of this Project to the OPUD wastewater treatment plant.
The following is a partial list of City Council actions taken to advance the design and environmental work for the Project:
On July 28, 2020, the City Council adopted Resolution No. 35-20 approving the $2.6M grant/loan agreement to fund environmental and design efforts for the Wheatland Regional Sewer Pipeline Project (Project) and authorizing the City Manager to sign the agreement. On November 10, 2020, the City Council adopted Resolution No. 43-20 amending the FY 2020-21 Budget and authorizing the City Manager to proceed with environmental review and engineering design for the Project.
87 Section 6, Item # 6.3
October 11, 2022, the City Council adopted Resolution No. 34-22, which, among other actions, authorized acceptance of an additional $2 million loan from the Yuba Water Agency for work associated with environmental, engineering design, right-of-way acquisition and grant funding work for the Project.
The City conducted an environmental review and prepared an Environmental Impact Report (EIR) for the Project (SCH No. 2021110022). Based on the EIR, a Notice of Determination was made by the City Council on February 28, 2023, and was filed by the County Recorder on March 2, 2023. On July 17, 2026, the City advertised the Project for bids and on August 25, 2026, the City received ten bids for the Project.
The award of construction contracts for the Project is anticipated at the September 22, 2026, City Council meeting.
On April 20, 2026, the City and OPUD jointly released a Request for Proposals (RFP) for construction Management and Inspection Services (CM&I) for the South Yuba County Wastewater Infrastructure Project (Attachment ‘B’). Six written proposals were received by May 20, 2026, submission deadline.
Proposals were evaluated by a review panel, consisting of the OPUD Public Works Manager Swarnjit Boyal, City Engineer Dane Schilling, a Principal Construction Manager from Coastland|DCCM and an Associate Engineer from Coastland|DCCM. Proposals were evaluated on the following criteria and weighted scoring:
Project Understanding & unique ideas to enhance the project 20% Experience of firm(s) and specific staff including QA/QC 20% Ability to control costs and contractor schedule 30%
References from former clients 20%
Completeness and compliance with RFP format 10%
After individual evaluations were completed, the review panel met to confer and decided to invite five of the six firms to in-person interviews with the panel. Interviews were conducted on June 4, 2026. At the conclusion of the interviews, the selection panel deliberated and unanimously chose ICM Group (ICM) as its top-ranked proposer. ICM’s cost proposal was reviewed by City and OPUD staff and minor adjustments were made. ICM’s proposal and cost proposal are included in Attachment C.
Also, the City’s design engineering team, headed by Coastland|DCCM, is needed to provide technical support to ICM’s efforts in overseeing the proper construction of the City’s Regional Sewer Pipeline Project. When needed and requested, Coastland|DCCM will provide responses to design related questions from the contractor, review engineering submittals and perform as-needed construction observations during the course of the 30-month construction process.
Similarly, the City’s planning and environmental team, headed by Raney Planning and Management, will provide on-going environmental review and permitting services during construction of the project as required by the environmental permits issued by California Department of Fish and Wildlife (CDFW) and the US Army Corps of Engineers (USACOE).
88 Section 6, Item # 6.3
FISCAL IMPACT:
The total proposed cost to the City for the above-described services are:
Construction Management and Inspection - ICM Group (City only) $2,943,829 Engineering Services During Construction-Coastland|DCCM $1,336,982 Environmental Services During Construction-Raney Planning & Mgmt $ 200,000 TOTAL $4,480,685
Although the CM&I services contract will be established with the City, the services and costs will be shared with OPUD in accordance with the individual fee proposals submitted by ICM Group for each agency’s project. These City’s costs for these services are within the project budget and will be paid for under the various funding sources for the Project including State Water Resources Control Board grant funds, potential USDA loan and grant funding, other outside loan funding, and City of Wheatland sewer impact fees. No General Fund resources will be utilized for this Project.
A Memorandum of Understanding between the City of Wheatland and OPUD (MOU) is being finalized.
Accordingly, a Notice to Proceed will not be issued by the City to either contractor until the MOU is executed by both parties.
ATTACHMENTS:
Attachment A – Resolution
Attachment B – RFP for Construction Management & Inspection Services Attachment C – ICM Proposal
89 Section 6, Item # 6.3
Attachment ‘A’
RESOLUTION NO. 26-___
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF WHEATLAND AUTHORIZING
THE CITY MANAGER TO ENTER INTO A CONSTRUCTION CONTRACT WITH RCI GENERAL ENGINEERING IN THE AMOUNT OF $16,618,050.00 FOR CONSTRUCTION OF SCHEDULE APIPELINES FOR THE WHEATLAND REGIONAL SEWER PIPELINE PROJECT AND AUTHORIZING THE CITY MANAGER TO EXECUTE CONTRACT CHANGE ORDERS NOT TO EXCEED $538,424.00 WHEREAS, on November 10, 2020, the City Council adopted Resolution No. 43-20 amending the FY 2020-21 Budget and authorizing the City Manager to proceed with environmental review and engineering design for the Wheatland Regional Project (“Project”); and;
WHEREAS, on April 27, 2021, the Basis of Design Report for the Project was presented to the Wheatland City Council and adopted by Resolution No.16-21; and WHEREAS, the City conducted an environmental review of the Project, prepared an Environmental Impact Report (EIR), the City Council made a Notice of Determination on the EIR on February 28, 2023, and the City filed the Notice of Determination with the County Recorder on March 2, 2023; and
WHEREAS, on July 14, 2026, the City Council approved the contract documents for construction including a notice to bidders, bidders’ book, sample contract, plans and specifications for the Wheatland Regional Sewer Pipeline Project; and authorized City staff to call for bids for construction of the project; and
WHEREAS, on August 25, 2026, the bid period closed, and the City received ten bids for construction of the Project and the City intends to award construction contracts on September 22, 2026, and
WHEREAS, on April 20, 2026, the City and Olivehurst Public Utilities District (OPUD) jointly released a Request for Proposals (RFP) for construction Management and Inspection Services (CM&I) for the South Yuba County Wastewater Infrastructure Project; and WHEREAS, by the May 20, 2026, submission deadline, six proposals were received and later evaluated by a review panel of City and OPUD representatives; and WHEREAS, the selection committee conducted in-person interviews with five firms on June 4, 2026, and at the conclusion of the interviews, the selection panel deliberated and unanimously chose ICM Group (ICM) as its top-ranked proposer; and 90 Section 6, Item # 6.3
WHEREAS, it is necessary that the City engage with the design engineer and planner responsible for the design engineering and environmental processing of the Project during the course of construction to support the successful completion of the Project.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Wheatland as follows:
1. Authorizes the City Manager to execute a professional service agreement for construction management and inspection (CM&I) services during construction of the Wheatland Regional Sewer Pipeline Project to ICM Group in the amount not to exceed $2,943,703.00 without prior City Council authorization.
2. Authorizes the City Manager to issue a task order to Coastland|DCCM for engineering services during construction of the Wheatland Regional Sewer Pipeline Project in the amount not to exceed $1,336,982.00 without prior City Council authorization.
3. Authorizes the City Manager to issue a task order to Raney Planning and Management for environmental support services during construction of the Wheatland Regional Sewer Pipeline Project in the amount not to exceed $200,00.00 without prior City Council authorization.
The foregoing resolution was adopted by the City Council of the City of Wheatland at a regular meeting held on the 22nd day of September 2026, by the following vote:
AYES:
NOES:
ABSTAIN:
ABSENT:
The foregoing resolution is hereby approved.
________________________
Lisa McIntosh, Mayor
ATTEST:
________________________
Josie Camacho, City Clerk
91 Section 6, Item # 6.3
REQUEST FOR PROPOSALS (RFP) TO PROVIDE
CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES
FOR THE
WHEATLAND-OPUD REGIONAL SEWER PIPELINE
PROJECT (CWSRF PROJECT NO. C-06-8753-110)
FOR THE
CITY OF WHEATLAND AND OLIVEHURST PUBLIC UTILITIES DISTRICT Questions regarding this RFP must only be submitted to the website listed in this RFP.
Proposers may not submit questions directly to agency staff.
Release Date: April 20, 2026
Questions Due: April 30, 2026
Response to Questions Due: May 7, 2026
Proposal Submittal Deadline: 2:00 P.M. May 14, 2026
Funding for this project has been provided in part through an agreement with the State Water Resources Control Board. California’s Clean Water State Revolving Fund is capitalized through a variety of funding sources, including grants from the United States Environmental Protection Agency and state bond proceeds. Funding has also been provided in part by the Yuba Water Agency.
The contents of this document do not necessarily reflect the views and policies of the foregoing, nor does mention of trade names or commercial products constitute endorsement or recommendation for use.
Attachment 'B'
92 Section 6, Item # 6.3
2 Request for Proposals (RFP) for Construction Management and Inspection (CM&I) Services for the
WHEATLAND-OPUD REGIONAL SEWER PIPELINE PROJECT
(CWSRF PROJECT NO. C-06-8753-110)
I. DESCRIPTION OF THE PROJECT
The City of Wheatland (City) and Olivehurst Public Utilities District (OPUD), (collectively Agencies), are seeking written proposals from qualified firms to perform construction management and inspection (CM&I) services for the construction of three wastewater conveyance contracts (Project). See Attachment A - Location Map. The selected consultant or consultant team (Consultant) must have extensive knowledge and experience in construction management and inspection of large wastewater conveyance projects. The Agencies’ budget for the services described in this RFP is $5,000,000. Proposals exceeding this amount may be, at the Agencies’ discretion, set aside from further consideration. Controlling all costs is a high priority for the Agencies. The design firms for each agency will be providing engineering services during construction to support and assist the Consultant in responding to RFIs, submittal reviews, difficulties encountered in construction, meetings as needed and other technical support to the CM&I Consultant.
The Agencies have programmed, designed, bid, and issued Notices of Intent to Award for three contracts to accomplish conveyance of wastewater from the City of Wheatland’s existing collection system to OPUD’s wastewater treatment plant. The following construction contracts will be included in this construction management and inspection contract:
Contract 1A - City of Wheatland Pipelines
This contract involves constructing conveyance pipelines including:
• 12-inch dia. HDPE force main - 8,768 LF
• 18-inch dia. HDPE force main – 32,048 LF
• 18-inch dia. HDD crossings – 1,450 and 600 LF
• Jack and Bore Crossings – five locations totaling 1,000 LF • Stormwater culvert replacement
• 4,000 LF water main extension and booster pump station • Road restoration, paving and pavement markings
• Award amount $15,621,813
• Contractor: RCI General Engineering
• Substantial Completion: 380 working days, approximately 11/01/2027 • Final Completion: approximately 02/01/2028
93 Section 6, Item # 6.3
3 Contract 1B - City of Wheatland Pump Stations
This contract involves constructing sewer conveyance pumpstation including:
• Pump Station No. 1 including influent sewer modifications, existing PS demolition, storage tanks, control building, odor control, generator, yard piping, yard improvements and landscaping
• Pump Station No. 2 including sewer and force main, influent splitter, biofilter, storage tanks, equalization tanks, lab building, maintenance building, well, water main, water storage tank, booster PS, yard piping, yard improvements and landscaping
• Pump Station No. 3 including control building, sewer and force main, control building, yard piping, yard improvements and landscaping • Control panel and SCADA upgrades at existing lift stations • Site grading and fencing
• Electrical instrumentation and controls
• Yard piping
• Site grading and fencing
• Electrical instrumentation and controls
• Award amount $38,558,793
• Contractor: Gateway Pacific Contractors, Inc.
• Substantial Completion: 535 working days, approximately 06/01/2028 • Final Completion: approximately 09/01/2028
Contract 2 - OPUD Regional Sewer Pipeline and Pump Stations This project involves constructing sewer conveyance pipelines and pumpstations including:
• 36-inch dia. PVC C-900 force main 5,100 LF
• 24-inch dia. PVC C-900 force main 6,900 LF
• 24-inch dia. PVC C-900 force main 1,100 LF
• 18-inch dia. PVC C-900 force main 24,800 LF
• Pump Station 21 including grading, influent sewer and manhole, wet wells A &B, flushing system, odor control beds, piping, force main, valves and fittings, yard piping and improvements
• Trenchless crossings at SR 65, Hutchinson Creek, Reeds Creek, Kimball Creek at Rancho Road (HDD) and Virginia Creek at Rancho Road (five crossings) • Rehabilitation and force main connection at existing Pump Station No.2 • Contractor: Mozingo Construction
• Substantial Completion: 715 calendar days, approximately 3/31/2028 • Final Completion: 870 calendar days, approximately 8/31/2028 94 Section 6, Item # 6.3
4 Electronic copies of the project plans, specifications, bid tabs, and other reference documentation can be found on the Public Purchase website for this project.
In addition to the Project described above and conditioned upon satisfactory performance, the Agencies may engage the Consultant for subsequent and related projects which include modifications to the OPUD Wastewater Treatment Plant (between $15M to $30M construction cost) and, demolition and decommissioning of the Wheatland Wastewater Plant (approximately $2M construction cost).
II. SCOPE OF SERVICES
The selected CM&I Consultant will be expected to provide services covering all applicable aspects of construction management and inspection including but not limited to the following:
A. Construction Phase
1. Provide on-site construction management and inspection.
2. Provide and maintain professional liaison with the contractor, residents, homeowners, local business owners and the traveling public.
3. Ensure the contractor meets all required obligations according to the contract documents.
4. Maintain daily on-site project log and as-built schedule report. Prepare daily reports of observations and activities. Secure the general contractor's daily log reports.
5. Document the Contractor’s progress through video recordings and digital photography with date and time of the recording included in the imagery.
6. Document all non-compliance issues as well as any other site condition requested by the agency.
7. Coordinate, review and approve the Contractor's proposed CPM schedule for completion of the project.
8. Review contractor's schedule update submittals for conformance to master schedule and contract documents.
9. Conduct pre-construction and weekly job-site progress meetings to discuss procedures, progress, problems, scheduling and other matters impacting project progress and costs. Prepare and promptly distribute meeting minutes.
10.Establish and implement procedures for reviewing and processing of all project documentation.
11.Facilitate review and response to Contractor’s Requests for Information (RFI).
12.Oversee Quality Assurance of the construction activities to conform to plans and specifications.
13.Perform all special inspection and materials testing required for each project. 95 Section 6, Item # 6.3
5 14.Provide QSD/QSP certified personnel experienced in SWPPP monitoring and enforcement of SWPPP permits. Complete the inspection, sampling, and reporting requirements of the project SWPPP. Inspect and oversee contractor required repairs and adjustments to project BMPs.
15.Coordinate the activities of inspectors and ensure completion and filing of appropriate reports, logs, photos and other documentation.
16.Maintain project documents, drawings, contract change orders, contractor submittals, shop drawing and correspondence in electronic form and hard copy.
17.Maintain at the project site on an "as-current" basis, a record copy of all contracts, drawings, specifications, addenda, change orders and other modifications, in good order and marked to record all changes made during construction.
18.Review, and adjust, if necessary, contractor payment applications for accuracy (amount due, certified payroll, appropriate rate, etc.) and recommend to agency’s Engineer approval and payment
19.Collect and review, for compliance with all State and Federal regulations, certified payroll records requirements.
20.Maintain a daily RE log including weather, contractor and subcontractor personnel, work tasks being done, work accomplished, problems encountered, solutions agreed upon, and other relevant data necessary to show project progress and whether the contractor is timely in their compliance with the contract documents.
21.Monitor the establishment and implementation of appropriate safety programs by the Contractor.
22.Monitor Contractor and the sub-contractors’ compliance with prevailing wage rates and affirmative action requirements applicable to the project including a Labor Compliance Program in accordance with AB 1506 and SB 854.
23.Review and evaluate proposed change orders and advise the agency as to their effect on the contract time and cost. Perform independent cost estimates of proposed change order work as necessary. Lead negotiations of change orders and recommend approval or denial to the agency.
24.Provide special inspection and testing for soil compaction, concrete, steel, masonry, welding, asphalt, and other construction materials and activities identified within the construction plans and specifications.
B. Construction Completion and Closeout
1. Advise the agency of key milestones such as substantial and final completion and liquidated damages issues.
2. Compile detailed "punch-lists" and review with the agency.
3. Evaluate any contractor claim, negotiate and recommend resolution to Agency.
Submit to Agency a warranty process and schedule.
96 Section 6, Item # 6.3
6 4. Coordinate closeout procedures. Monitor the Contractor's progress to finalize all project records, complete and correct as-builts, and other documentations required by the contract documents.
5. Oversee the performance of punch list items and final clean-up prior to contractor de-mobilization.
6. Coordinate final testing, documentation and regulatory inspections.
7. Obtain the contractor’s red-line record (as built) drawings; O & M materials, if any, required documents, lien releases, and written warrantees. Review and make recommendations to agency regarding final acceptance.
8. Advise agency on final payment.
9. Provide agency with complete project documentation for archival records storage.
10. Oversee the complete performance of all warranty repair items.
11. Confirm environmental requirements are being met per environmental permit (refer to special inspections).
12. Meet all necessary requirements for construction as highlighted in each bid submittal for all three contracts.
Please note that Contracts 1A and 1B, and Contract 2 will require separate and stand-alone construction record keeping and accounting, which will be subject to inspection and audit by the Agencies and the State Water Resources Control Board.
Additional duties for these contracts will include coordination between the three projects and their contractors, separate project accounting and records between projects, and separate itemized accounting of construction including the apportionment of any shared costs between the projects and/or items of work.
On-site field offices as well as internet and electrical power will be provided by Agencies. All other furnishings, equipment and utilities for the execution of this work will be the responsibility of the consultant.
III. ASSUMPTIONS
Proposers shall use the following assumptions in the preparation of their cost proposals:
Contract Time Contract durations are as indicated in Section I and assumed to run concurrently. Final testing
and start-up of system depends on the
completion of all three contracts.
RFIs 1A = 30
1B = 85
2 = 85
97 Section 6, Item # 6.3
7 Submittal Reviews -
Actionable, Engineering
Review Required
1A = 30
1B = 160
2 = 164
Submittals – Routine,
Information Only
1A = 30
1B = 160
2 = 329
Change Orders 1A = 10
1B = 15
2 = 15
Claims 1A = 1
1B = 1
2 = 1
Pay Requests 1A = 19
1B = 26
2 = 24
IV. TASK ORDER
The selected Consultant will be issued two task orders – one for Contracts 1A and 1B (City), and one for Contract 2 (OPUD). Consultant shall track and invoice time and expenses for each task order separately. No work is authorized and no payments will be made prior to execution of Task Orders.
V. REQUIRED CONTENTS OF PROPOSAL
Proposals should be concise and specific to this RFP and limited to 20 single sided pages, excluding 1) the cover letter, 2) the cost proposal (in separate file) and 3) full resumes and sample documents (specifically described below) included in appendices. Proposals must be in the following format:
1. Consultant Identification and Qualifications:
Provide the legal name of the firm, the firm’s mailing and physical address, the names and contact information of the legally responsible principal and the primary contact person (Project Manager) for this project. Provide a brief summary of the firm’s (or team’s) qualifications specific to this project.
2. Project Understanding and Approach:
Describe the unique overall approach and methodologies for this Project. Provide a more detailed description of the program to respond to each specific work element.
Describe how to track and control contractor and Consultant costs to keep them within budget.
98 Section 6, Item # 6.3
8 3. Quality Assurance/Quality Control (QA/QC):
Describe the team’s established QA/QC program to be used throughout the Project.
Provide the name, licenses and a brief bio of the person responsible for QA/QC.
4. Related Project/Client Information:
Briefly describe three (3) comparable projects that best exhibit the firm’s experience in each of the required services. Include the specific project name and location, overall project size and cost, initial CM fee, final CM cost and why it went over (change orders, time extensions, etc.), client contact person, including title, organization, address, current telephone number and E-mail address.
5. Individual Staff Experience and Project Organization:
i. Provide an organization chart showing the project manager and key staff members for the project.
ii. Provide a brief bio of each key staff.
iii. Provide a summary of each sub-consultant, their area of responsibility and percentage of the project cost.
iv. Provide a realistic statement of current staffing workload commitments, additional resources of the firm, and ability of the firm(s) to respond to any request for additional or contingency services in a timely manner. v. Provide a statement that the departure, reassignment or substitution for any named member of the designated project team including subconsultant(s) will not be made without the prior written approval of the agency.
6. Cost Proposal:
Include a cost estimate of all required services and associated fees in a separate file entitled “COST PROPOSAL - <name of firm> ”.
The cost proposal must:
i. Meet the Agencies budget listed above. After qualifications of proposers are evaluated and firms are determined to be qualified, any proposals exceeding the budget amount may be set aside or rejected.
ii. Be broken down by task order, task and personnel category to indicate the level of effort and duration for each task,
iii. Show one hourly rate for each personnel category necessary for each task.
The hourly labor rate must:
• Conform to State of California prevailing wages insofar as they may apply. • Include the differential cost for any night work or overtime work. • Include all expenses for materials, supplies, mobile phones, computers, travel, housing per diem and any expenses necessary to meet the requirements and deliverables listed in the Scope of Services and the approved construction management plan.
• Include allowances for annual escalation and/or inflation. iv. Show a “not to exceed” total for each contract.
99 Section 6, Item # 6.3
9 7. Exceptions
List any exceptions to any portion of this RFP. The City and OPUD will consider the exception(s) and may or may not reject the RFP as non-responsive.
8. Appendices:
Appendices may or may not be reviewed in detail. They will not count against the stated page limit and may include:
i. auxiliary/ancillary materials.
ii. sample documents that exhibit the firm’s standard of documentation, such as sample field reports, lab reports, invoices and other relevant documents expected to be used during the Project.
iii. Full resumes of key staff
iv. Full project descriptions.
VI. SUBMISSION OF THE PROPOSAL
To be eligible to submit a proposal, proposers must register their firm with Public Purchase page for the project:
https://www.publicpurchase.com/gems/wheatlandpd,ca/buyer/public/home Digital files of proposal and cost proposals must be uploaded to the Public Purchase site for the Project by the specified deadline. Note the website will not accept proposals after the deadline.
VII. CONSULTANT SELECTION PROCESS
The Agencies will evaluate and rank the proposals using the following scoring:
Project Understanding & unique ideas to enhance the project 20 Points Experience of firm(s) and specific staff including QA/QC 20 Points Ability to control costs and contractor schedule 30 Points References from former clients 20 Points
Completeness and compliance with RFP format 10 Points
Total Points Possible 100 Points
At the discretion of the Agencies, one or more of the top ranked teams may be interviewed based upon the relative ranking by total score. Interviews will be for the purpose of meeting the project team, discussion of the scope of work, and review of the factors considered in the preparation of the proposal. The teams may also be requested to provide further clarification of submitted materials and/or submit additional materials for consideration.
After the interviews and review of any additional material requested, the Agencies will begin negotiations with the top-ranked proposer.
Proposals may become discoverable as public information. Proposers should describe in an appendix any proprietary or sensitive information that they would want to remain confidential. 100
Section 6, Item # 6.3
10 The Proposal should reflect the most favorable terms available to the Agencies, as the Agencies may make award on the Proposal alone without interviews or any further contact with the Proposer.
VIII. SCHEDULE
The following activities and dates are anticipated:
RFP Issued April 20, 2026
Questions Due April 30, 2026, 5:00PM
Proposal Due May 14, 2026, 2:00PM
Interviews (if necessary) May 26, 2026
Award of Contract June 9, 2026
Final Execution of Contract/ Notice to Proceed June 12, 2026 The Agencies reserve the right to change the schedule.
IX. DOCUMENTS AND QUESTIONS
Background documents such as plans, specs, reports, bid tabulations and other information may be found on the Public Purchase website.
Direct any questions regarding this RFP to the Public Purchase website for the Project. All questions and requests for information must be received no later than 5:00 pm on the date noted in the schedule above to ensure a response can be provided. Responses may be provided via Addendum. Do not contact any City or District staff or their consultants before the submission deadline.
Addenda to this RFP will be transmitted to firms registered on Public Purchase. Failure of the proposer to be aware of addenda or failure to return signed acknowledgment of addenda may be cause for rejection at the sole discretion of the Agencies. Verbal conversations with any person will not modify any term or obligation of this RFP.
X. SUBMITTAL INSTRUCTIONS
1. All proposals become the property of the Agencies and will not be returned.
2. All costs for proposal preparation shall be borne by proposers.
3. Proposers may withdraw their proposal or correct a mistake in their proposal prior to the proposal submission deadline by submitting a withdrawal request or correction/addendum in writing. Oral communication will not be accepted.
XI. ATTACHMENTS
Attachment A – Location Map
Attachment B – Sample Professional Services Agreement
101
Section 6, Item # 6.3
11 WHEATLAND-OPUD REGIONAL SEWER PIPELINE PROJECT
(CWSRF PROJECT NO. C-06-8753-110) Attachment A – Location Map 102
Section 6, Item # 6.3
12 ATTACHMENT B - Sample Professional Services Agreement 103
Section 6, Item # 6.3
13104
Section 6, Item # 6.3
14105
Section 6, Item # 6.3
15106
Section 6, Item # 6.3
16107
Section 6, Item # 6.3
17108
Section 6, Item # 6.3
18109
Section 6, Item # 6.3
19110
Section 6, Item # 6.3
20111
Section 6, Item # 6.3
21112
Section 6, Item # 6.3
Prepared for
City of Wheatland
7040 Settlers Trail
Shingle Springs, CA 95682
(530) 683-4038
www.icmgroupusa.com
Proposal for
CONSTRUCTION MANAGEMENT
AND INSPECTION SERVICES
Wheatland-OPUD Regional
Sewer Pipeline Project
June 13, 2026
ICM
Attachment 'C'
113
Section 6, Item # 6.3
ICM
7040 Settlers Trail
Shingle Springs, CA 95682
www.icmgroupusa.com Phone 530-683-4038
June 13, 2026
Dane Schilling Swarnjit Boyal
City Engineer Public Works Engineer
City of Wheatland Olivehurst Public Utility District
111 C Street 1970 9th Avenue
Wheatland, CA 95692 Olivehurst, CA 95961
RE: Proposal to Provide Construction Management and Inspection Services for the Wheatland-OPUD Regional Sewer Pipeline Project
(CWSRF Project No. C-06-8753-110)
Dear Gentlemen:
Inferrera Construction Management Group, Inc. (ICM) is excited to present you with our revised proposal for construction management (CM) and inspection services for the WheatlandOPUD Regional Sewer Pipeline Project! Constructing wastewater pump stations and force mains is exciting! New facilities, such as yours, requires attention to details and a team focused approach for success. Starting with reputable contractors, like Gateway Pacific, Mozingo and RCI General Engineering, will lessen the number of issues that arise. We know first-hand, having worked with Gateway Pacific and Mozingo on large complicated projects.
At ICM, all we do is construction management and inspection of local wastewater and water public works projects. We have one of the largest, if not the largest, team of professionals located here in the Sacramento area dedicated solely to the CM and inspection of local wastewater and water projects. Wastewater pump stations and pipelines are our specialty.
We recently completed or are about to complete the CM and inspection of the following projects:
• The $47 million Sly Park Intertie Project, with a pump station and 7 miles of pipeline. (El Dorado Irrigation District, Pollock Pines, CA)
• The $100 million Arden Area Mainline and Meter Replacement Project including 32 miles of pipeline. (Sacramento County Water Agency)
• The $240 million regional water treatment plant, pipeline, and pump station projects for Stanislaus Regional Water Authority in Hughson, CA (near Turlock).
Included under separate cover is our Cost Proposal. We look forward to helping you on this important project. If you have questions or comments, please call me at 530-683-4038.
Sincerely,
Inferrera Construction Management Group, Inc.
Jeffrey Inferrera, PE
President
114
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
1 ICM
ICM Identification and Qualifications
Inferrera Construction Management Group, Inc. (ICM) offers comprehensive construction management (CM) and inspection services. We are 100 percent dedicated to water and wastewater public works projects. ICM is not a design firm. ICM does not provide CM and inspection services for other industries like transportation, schools, or hospitals. Founded in 2005, we are solely focused on your water and wastewater projects. Our contact information is as follows:
Principal/Project Manager: Jeffrey Inferrera, PE
Address: 7040 Settlers Trail
Shingle Springs, CA 94630
Phone: 530-683-4038
Email: [email protected]
ICM is a local specialized third-party construction management and inspection firm. All of our projects are within a two hour radius of Sacramento and all of our staff live locally.
Services we provide include the following:
• Construction Management
• Resident Engineering
• Inspection
• Special Inspection
• Contract Administration
• Document Control
• Cost Estimating
• Constructability Review
• Startup Support
• Bid Support
• Schedule Review
• Claims Support
ICM’s specialty is water and wastewater
public works projects. We have experienced
professionals who have successfully completed the following types of projects since 2005:
• Pump Stations more than 30 projects
• Sewer Lift Stations more than 17 projects
• Open-Cut Pipelines more than 90 projects
• Trenchless Pipeline more than 15 projects
• Wastewater Treatment Plants more than 26 projects
• Water Treatment Plants more than 16 projects
• Water Tanks more than 8 projects
• Backup Generators more than 35 installed
The following three pages show a sampling of the local projects we have successfully completed.
VFWD, Mare Island Way Sewer
Rehabilitation Project, 2019
115
Section 6, Item # 6.3
ICM CM and Inspection
Owner: Central Contra Costa
Sanitary District
Projects: - Pleasant Hill Sewer
Renovations - Lafayette Sewer Renovations
Years: 2023-present
ICM CM and Inspection
Owner: San Juan Water District
Project: Cooperative Transmission
Main
Year: 2010-2011
ICM CM and Inspection
Owner: City of Manteca
Projects: - North Trunk Sewer
- FEZ Trunk Sewer
Year: 2020-2021, 2016-2017
ICM CM and Inspection
Owner: Stanislaus Regional Water
Authority
Project: Ceres and Turlock
Transmission Main
Year 2019-2021
ICM PIPELINE PROJECTS
ICM has successfully completed over
100 pipeline projects in the Sacramento
area.
Included on this page are representative
projects.
ICM
ICM CM and Inspection
Owner: Sacramento County Water
Agency
Project: Arden Pipe and Meter
Installation
Year: 2023-present
ICM CM and Inspection
Owner: City of Yuba City
Project: Garden Road CIPP
Year: 2019-2021
ICM CM and Inspection
Owner: City of Roseville
Project: Church St Main Replacement
Year: 2024-2025
ICM CM and Inspection
Owner: El Dorado Irrigation District
Project: Motherlode Force Main
Year: 2023-2025
ICM CM and Inspection
Owner: Vallejo Flood and
Wastewater District
Project: Mare Island Main
Replacement
Year: 2019
116
Section 6, Item # 6.3
ICM CM and Inspection
Owner: City of Manteca
Projects: - Tara Park Pump Station
- Atherton Pump Station
- Woodbridge Pump Station
Years: 2006
2012-2014
2006-2008
ICM CM and Inspection
Owner: El Dorado Irrigation District
Project: Carson Creek Lift Station
Year: 2014-2015
ICM CM and Inspection
Owner: Calaveras County Water
District
Project: Lower Cross Country Pump
Station
Year: 2007-2008
ICM CM and Inspection
Owner: Stanislaus Regional Water
Authority
Project: Surface Water Pump Station
Year 2021-2022
ICM Pump Station Projects
ICM has successfully completed
over 30 pump station projects.
Below is a representation of a few
of them.
ICM
ICM CM and Inspection
Owner: Delta Diablo
Project: Pump Station Improvements
Year: 2019-2024
ICM CM and Inspection
Owner: City of Yuba City
Project: Bogue Road Pump Station
Year: 2025-present
ICM CM and Inspection
Owner: City of Folsom
Projects: - Oak Avenue Pump Station
- Lake Forest Pump Station
Years: 2014-2015
2010-2011
ICM CM and Inspection
Owner: El Dorado Irrigation District
Project: Sly Park Intertie Pump Station
Year: 2024- present
ICM CM and Inspection
Owner: City of Ceres
Project: River Bluff Pump Station
Year: 2021-2022
117
Section 6, Item # 6.3
ICM CM and Inspection
Key Personnel: Jeff Inferrera
Ricardo Bedoy
Paul Lopez
Owner: City of Manteca
Project: Treatment Plant Expansion
Year: 2005-2015
ICM CM and Inspection
Key Personnel: Jeff Inferrera
Ricardo Bedoy
Paul Lopez
Owner: San Juan Water District
Project: Peterson Water Treatment
Plant
Year: 2010-2023
ICM CM and Inspection
Key Personnel: Jeff Inferrera
Owner: City of Ione
Project: Wastewater Treatment Plant
Year: 2015-2018
ICM CM and Inspection
Key Personnel: Jeff Inferrera
Paul Lopez
Matt Livingston
Owner: Stanislaus Regional Water
Authority
Project: Water Treatment Plant
Year 2021-2022
ICM Treatment Plant Projects
ICM has successfully completed
over 40 treatment plant projects.
Below is a representation of a few
of them.
ICM
ICM CM and Inspection
Key Personnel: Jeff Inferrera
Owner: City of Davis
Project: Wastewater Treatment Plant
Year: 2013-2014
ICM CM and Inspection
Key Personnel: Jeff Inferrera
Paul Lopez
Owner: City of Yuba City
Project: Wastewater Treatment Facility
Improvements
Year: 2019-2021
ICM CM and Inspection
Key Personnel: Jeff Inferrera
Paul Lopez
Owner: City of Folsom
Project: Water Treatment Plant
Year: 2022-2023
ICM CM and Inspection
Key Personnel: Jeff Inferrera
Paul Lopez
Owner: El Dorado Irrigation District
Project: Water and Wastewater
Treatment Plants
Year: 2015-2026
ICM CM and Inspection
Key Personnel: Jeff Inferrera
Matt Livingston
Owner: City of Stockton
Project: Water Treatment Plant
Year: 2025-2026
118
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
2 ICM
The table below shows a list of our clients.
DIR Registration
Inferrera Construction Management Group, Inc. is registered with the Department of Industrial Relations (DIR). Our DIR number is 1000036717.
Client List and Their
Facilities
Size (x1,000 Customers)Wastewater Treatment PlantsWater Treatment PlantsSewer Lift StationWater Pump StationWater Storage TanksSewer PipelinesWater PipelinesWater ServicesDeveloper ProjectsReservoirs and CanalsNumber of ICM Projects Central Contra Costa Sanitary District 483 ⬧ ⬧ ⬧ 11
City of Manteca 72 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 20
City of Folsom 73 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 7
City of Ceres 49 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 2
City of Roseville 145 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 1
City of Davis 66 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 1
City of Ione 5 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 2
City of Modesto 218 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 2
City of Stockton 326 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 1
City of Yuba City 69 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 6
Citrus Heights Water District 67 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 8
Calaveras County Water District 17 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 5
Delta Diablo Sanitation District 200 ⬧ ⬧ ⬧ 2
El Dorado Irrigation District 100 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 33 Groveland Community Services District 5 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 2
Golden State Water Company 255 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 6
Nevada County <98 ⬧ ⬧ ⬧ ⬧ 1
Sacramento County Water Agency 55 ⬧ ⬧ ⬧ ⬧ 4
Sacramento Suburban Water District 173 ⬧ ⬧ ⬧ 2
San Juan Water District 160 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 8
Stanislaus Regional Water Authority 100 ⬧ 2
Town of Discovery Bay 13 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 1
Tuolumne Utilities District 44 ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 2
Turlock Irrigation District 110 ⬧ ⬧ ⬧ ⬧ ⬧ 3
Vallejo Flood and Wastewater District 124 ⬧ ⬧ ⬧ 3
119
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
3 ICM
Subconsultants
Brown and Caldwell is a dynamic international company with over 2,400 employees, providing services for nearly 80 years. Brown and Caldwell will be providing inspection services for the Regional Sewer Pipeline Project and will also be available to provide other construction management, inspection and administrative resources as needed. With a concentration in water, wastewater and environment, Brown and Caldwell brings a depth and breadth of resources to our project team.
Their office is located in Rancho Cordova.
Youngdahl Consulting Group will provide materials, and
special inspection testing services, including compaction testing, concrete, rebar, and welding inspection on an as needed basis. In addition, they will provide quality assurance testing as needed. Youngdahl Associates will also be available for geotechnical review. ICM has worked with Youngdahl extensively for more than 10 years. Youngdahl has proven to be a valuable team member successfully performing their scope of work responsibilities to the satisfaction of all team members. Their office is located in El Dorado Hills.
American River Environmental (ARE) will provide quality assurance audits on an as needed basis. ICM has worked with the ARE staff for a number years on projects in the Sacramento area. They have a proven record to keep projects in compliance. Their office is located in Placerville.
R.E.Y. Engineers must be one of the best surveying outfits in Northern California. ICM has recently worked with REY on two projects and their performance was stellar. REY will provide survey quality assurance on this project. We look forward to working with them again on the Wheatland-OPUD Regional Sewer Pipeline Project. Their office is located in Folsom.
Madrone Ecological Consulting will provide environmental compliance services for Contract 2. Madrone Ecological is already providing excellent services on Contract 1A and Contract 1B. We are looking forward to working with them on the WheatlandOPUD Regional Sewer Pipeline Project. Their office is located in Citrus Heights.
Bay Area Coating Consultants, Inc. (BACC) will provide NACE Certified Coating and Lining Inspection Services in an as needed QA role. ICM has worked with BACC for the past 10 years. BACC has been in the coating inspection industry for the past 25 years. BACC is the top coatings inspection firm in California. Their office is located in Modesto. 120
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
4 ICM
Project Understanding and Approach
Project Understanding
When completed, the Wheatland-OPUD Regional
Sewer Pipeline Project will be an important part of
the expansion of critical infrastructure in the area.
It will allow Wheatland to decommission their
wastewater treatment plant and send the area
wastewater flows to the OPUD wastewater
treatment plant. The City of Wheatland (City) and
Olivehurst Public Utilities District (OPUD) have
designed, bid, and issued Notices of Intent to
Award for three contracts to accomplish
conveyance of wastewater from the City of
Wheatland’s existing collection system to OPUD’s
wastewater treatment plant.
We understand the uniqueness of your Project – the
cooperation of two agencies, with multiple funding
sources, having three contractors build interconnected pipelines and pump stations and the most critical aspect of the project is that the pump stations need to communicate with Pump Station 2 where they will all be controlled.
We are experienced in this type of project and qualified to provide the construction management and inspection services for Wheatland and OPUD. ICM recently completed the construction management and inspection of the $240 million Stanislaus Regional Water Authority’s project that consisted of two cities, the City of Ceres and Turlock, cooperating in constructing a new water treatment plant, four pump stations, three reservoirs, and 10 miles of 42 inch pipeline, with four contractors. A critical component of the SRWA project, like your project, was the communication and control of the treatment plant, reservoirs, and pump stations.
However, the SRWA project is not our only large project similar to yours. We are currently completing the $47 million Sly Park Intertie Project that includes two pump stations, two treatment plants, three reservoirs, and 7 miles of 24 and 30 inch pipeline. The Sly Park Intertie Project also has a critical component of the need to communicate with and control of the pump stations. Plus, ICM has worked on over 100 pipeline and over 40 pump station projects, all having similarities with your Project.
Another important aspect of your Project are the horizontal direction drilling (HDD) and jack and bore components. ICM has inspected numerous HDD and jack and bore tunnelling operations; most recently at the SRWA project (described above), two trunk sewer projects for the City of Manteca, and the Motherlode sewer force main project for the El Dorado Irrigation District.
We understand the construction contracts are awarded, and in the process of being approved, to the following apparent low bidders:
EID, Sly Park Intertie pipeline, current
121
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
5 ICM
Contract Owner Contractor Amount
Contract 1A - Pipelines Wheatland RCI Gen Engineering $15.6 million Contract 1B – Pump Stations Wheatland Gateway Pacific $38.6 million Contract 2 – Pipeline/Pump Stations OPUD Mozingo $49.5 million We have worked successfully with Gateway Pacific on the Stockton Recharge Basin Project and with Mozingo on the Manteca North Trunk Sewer Project and EID Sly Park Intertie Project. They are both reputable firms with a team attitude. Based on their excellent past performance, we anticipate they will work well with us, the Agencies, and the designers as a valuable team member.
We understand the design firms for each agency will be providing engineering services during construction to support and assist the construction manager in responding to RFIs, submittals, difficulties encountered in construction, meetings as needed and other technical support. The designers are listed below:
Contract Designers
Contract 1A – Pipelines Coastland, DCCM
Contract 1B – Pump Stations Coastland, NexGen, Control Point Contract 2 – Pipeline/Pump Stations Jacobs, Domenichelli, MHM, Frisch ICM has an excellent team spirit with all design firms. Being a third party CM firm doing only construction management and inspection, we do not compete with designers for design work and have no conflict of interest. We have worked well with Coastland Engineers, NexGen, Domenichelli and Associates, Verdantas, Control Point, and Frisch on numerous projects. Control Point and Frisch being the most important team members to get all project components up and running.
We understand that the Project consists of the following components:
Contract 1A - City of Wheatland Pipelines
This contract involves constructing wastewater pipelines including:
• 12-inch dia. HDPE force main - 8,768 LF
• 18-inch dia. HDPE force main – 32,048 LF
• 18-inch dia. HDD crossings – 1,450 and
600 LF
• Jack and Bore Crossings – five locations
totaling 1,000 LF
• Stormwater culvert replacement
• 4,000 LF water main extension and booster
pump station
• Road restoration, paving and pavement
markings
• Substantial Completion: 380 working days,
approximately 11/01/2027
• Final Completion: approximately
02/01/2028 SRWA, Raw Water Pump Station, 2020
122
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
6 ICM
Contract 1B - City of Wheatland Pump Stations
This contract involves constructing wastewater pump stations including:
• Pump Station No. 1 including influent sewer modifications, existing PS demolition, storage tanks, control building, odor control, generator, yard piping, yard improvements and landscaping
• Pump Station No. 2 including sewer and
force main, influent splitter, biofilter,
storage tanks, equalization tanks, lab
building, maintenance building, well,
water main, water storage tank, booster
PS, yard piping, yard improvements and
landscaping
• Pump Station No. 3 including control
building, sewer and force main, control
building, yard piping, yard improvements
and landscaping
• Work at five small subdivision pump
stations in Wheatland
• Control panel and SCADA upgrades at
existing lift stations
• Electrical instrumentation and controls
• Yard piping
• Site grading and fencing
• Substantial Completion: 535 working days, approximately 06/01/2028 • Final Completion: approximately 09/01/2028
Contract 2 - OPUD Regional Sewer Pipeline and Pump Stations This project involves constructing wastewater pipelines and pump stations including:
• 36-inch dia. PVC C-900 force main 5,100 LF
• 24-inch dia. PVC C-900 force main 6,900 LF
• 24-inch dia. PVC C-900 force main 1,100 LF
• 18-inch dia. PVC C-900 force main 24,800 LF
• Pump Station 21 including grading, influent sewer and manhole, wet wells A &B, flushing system, odor control beds, piping, force main, valves and fittings, yard piping. • Trenchless crossings at SR 65, Hutchinson Creek, Reeds Creek, Kimball Creek at Rancho Road (HDD) and Virginia Creek at Rancho Road (five crossings) • Rehabilitation and force main connection at existing Pump Station No.2 • Substantial Completion: 715 calendar days, approximately 3/31/2028 • Final Completion: 870 calendar days, approximately 8/31/2028 City of Folsom, Oak Avenue Wastewater
Pipeline Project, 2023
123
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
7 ICM
To maintain meticulous and organized project documents for three projects, ICM will institute a separate document control system for each project. We prefer to use Procore for each project, but are flexible to use the document management system most effective for each project and each project team. For example, we are able to use one document management system, like ProCore, for Wheatland’s projects, and a different document management system, like VPM, for OPUD’s project. The key is to establish those
management systems that allow the project
teams to attain high performance.
All high performance construction teams have
similarities: great and open communication,
prompt resolution of issues, quick turn around
times, and finishing on time or early. ICM
excels at building high performance
construction teams and driving for project
success. The following are goals for the
Regional Sewer Pipeline Project.
Goals for the Regional Sewer
Pipeline Project
ICM will put your interests first and help you
achieve your goals for the Regional Sewer
Pipeline Project. We assume you will have the
following goals that we find important on this type of project:
➢ Complete the Project on time or early.
➢ Complete the Project on budget.
➢ Achieve quality construction as required by the Contract documents and industry standards.
➢ Avoid claim escalation such as litigation or arbitration. ➢ Comply with permits and environmental regulations.
➢ Maintain good relationship with other stake holders including CalTrans, the County Department of Transportation.
➢ Maintain good relationships with private landowners and the public. ➢ And other goals as identified by the Agencies.
ICM's Approach to Achieve the Project Goals
On Time, On Budget, High Quality, and No Claims - ICM believes that project goals are best achieved by taking a Team Approach. We will establish a good working relationship with the contractors at the start of their projects. ICM has been in the local construction business long enough that we have a well-known reputation as a fair, firm and talented construction management company that works hard to resolve issues quickly to keep the project progressing. By anticipating project issues and resolving them promptly, we keep the project on track, earning the trust and good will of the contractor, to the benefit of all parties.
City of Manteca, Woodbridge Pump Station, 2008
124
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
8 ICM
As our team faces challenges, the best way to achieve the goals of the project (on time, on budget, with high quality and no claims) is to focus on quick responses to challenges so the contractor can complete the job on time or early. On-time project delivery provides the highest probability of a project that will also be on budget, have no claims, and has high quality construction.
Comply with Permits and Environmental Regulations - The key to maintaining compliance with permitting and environmental regulations is to enforce the permit requirements and maintain regular status updates with the contractors on permit compliance. As we have learned on other projects, even experienced contractors can employ staff who are inexperienced in complying with permits. So, we will be vigilant that permit compliance is maintained.
Maintain Good Relationship with Stakeholders,
Private Landowners, and the Public - We will keep
regular contact with the permitting agencies to keep
them informed of the Project status and allow them to
provide input if they have concerns and address those
concerns quickly. We will assist the Agencies with
addressing the concerns of landowners and the
public. For all stakeholders, prompt response and
quick resolution of issues goes a long way to build
trust and goodwill.
Other Agency Goals - ICM looks forward to learning
about other important goals of both Agencies. Once
identified, we will work with the team to plan an
approach and then achieve those goals.
Insights for Successful Completion of
Multi-Contract Pump Station and Pipeline
Projects
At ICM, we understand that the Project plans/specifications may be stamped and signed at bid time, but they are not 100% perfect. The project is fine-tuned and perfected as it is built in a collaborative approach with the contractor, engineer, and owner. The systems that have been developed to perfect the plans/specifications are the submittal process, RFIs, value engineering, and change orders. In addition, we get valuable information on how to resolve challenges from the contractor, who typically brings useful experience and ideas to the team that we can use to make the project better. At ICM, we leverage everyone's ideas to construct the better project to achieve the Agency’s goals.
To make this all happen successfully, we work collaboratively as a team: both Agencies, the design firms, the contractors, and ICM. Through subsidiarity, we resolve challenges at the lowest level possible while keeping all team members informed, thus progressing the work expeditiously and preventing claims. And based on our experience, we know where the challenges will be and we are proactive in resolving them before they negatively impact the Project. The list of Project Challenges below are some of the items that ICM will be proactive to help mitigate issues.
CCCSD, Lafayette Sewer Renovations,
current
125
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
9 ICM
Project Challenges - Based on our extensive experience in the construction of pump stations and pipelines, we have identified the following list of project challenges:
➢ SCADA and PLC Controls - It just seems whether it is Tesco, Telstar, Primex, or any other integrator, instrumentation, controls, and SCADA seem to be one of the more frustrating aspects of pump station and treatment plant startups, hidden from most eyes except operations. Jeff Inferrera is experienced at testing and troubleshooting I&C and SCADA, (including SCADA architecture, loop to loop testing, alarm lists, historian and trending) and will take the lead so that there is a smooth transition for operations. ➢ Tunnelling - ICM has a specialty tunnelling inspector on our team to enforce Agency and CalTrans requirements.
➢ Difficult Pipeline Construction - Joe Saylor is our experienced pipeline inspector that is knowledgeable of rock excavation and different
types of tunnelling. If the contractor has
difficulties, Joe will inform the team if an extra
is warranted or not and any impacts.
➢ Narrow easements - The engineer will need to
design custom thrust blocks where there is
insufficient room to pour a standard thrust block.
➢ Congestion of Underground Utilities - As we
build the pipeline and fiber optic extension
through the treatment plant, we will encounter
underground utility conflicts that will need good
locational information for the engineer to decide
on alternative pipe and fiber optic locations. We
will give the engineer advice on how to route the
pipe and fiber optic around conflicts.
➢ Long Equipment Delivery Times - The District
should consider pre-purchase of equipment such
as the emergency generators, electrical panels
and switchgear, VFDs, and vertical turbine pumps to avoid project delays.
Construction Management and Inspection Tasks
We agree with the Scope of Services presented in the RFP under "Construction Phase" and "Construction Completion and Closeout". We acknowledge the "Assumptions” presented in the RFP. We would like to add the following tasks/clarifications:
1. We suggest ICM provides each Agency with a monthly report for each project (an example is provided in the Appendix)
2. We have included Madrone Ecological on our team to assist with environmental awareness training and ecological surveys to comply with permit requirements for Contract 2 only.
3. ICM field staff will assist with public relations on an as needed basis.
4. For general construction inspection services, we anticipate having full time inspection during excavations and underground pipeline installation. However, depending on the task, above ground work at pump stations and surface work at pipelines, may be full time or part time.
City of Manteca, Tara Park Pump Station,
2006
126
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
10 ICM
5. ICM’s construction managers will review the contractors’ CPM baseline schedules and updates. ICM will maintain a master schedule that will consist of time critical milestones and tasks, and share this schedule with the project teams. However, the master schedule will exclude the granularity that is required in the contractors’ baseline schedules.
6. For special inspection and material testing, ICM has included Youngdahl on our team.
7. We have included American River Environmental on our team to assist with SWPPP QA audits. Since all three contractors are responsible for SWPPP planning and inspection per their contracts, this task is oversight only.
8. Labor compliance monitoring will be done on a periodic basis by ICM staff, not with a specialty firm certified in labor compliance monitoring.
9. We have included a separate budget item for warranty assistance.
10. We will track our work under two task orders, one for Contracts 1A and 1B and the other for Contract 2 or to meet the needs of the Agencies.
Exclusions to our Scope of Services are as follows:
1. Environmental surveys to be performed by others for
Contract 1A and 1B.
2. We exclude ADA compliance certification and/or
warranty.
3. We exclude SWPPP plan development, SWPPP
certification and SWPPP uploading to State web site.
SWPPP monitoring to be performed by contractors.
4. We exclude surveying by a CA licensed Land
Surveyor, it is to be done by the contractor.
5. We exclude construction staking.
6. We exclude engineering support services such as
technical review of submittals and RFIs with the
exception of schedule submittal, schedule of values
submittal, and RFIs better answered by our field
staff.
7. ICM is not responsible for Contractor's safety or safety program.
8. ICM is not responsible for Contractor's schedule.
ICM is qualified to provide construction management and inspection services for the Regional Sewer Pipeline Project. With the successful completion of over 20 pump station projects (including potable water pump stations) and over 50 pipeline projects (including 30" mortar lined and coated steel pipe), the Regional Sewer Pipeline Project is exactly the type of project that we focus on and excel. We have the following unique ideas:
1. The HDD and jack and bore tasks have unique challenges. We have assigned an inspector who has successfully completed many tunnelling projects and will keep the tunnelling tasks on track.
2. To enhance project productivity and to build top performing teams, we encourage open team communication. This is accomplished in two very crucial ways. First, we believe in the practice of subsidiarity. This allows issues to be resolved at the field level while management is kept informed. As such, we allow the contractor and engineer to call each EID, Town Center Force Main
Replacement, 2018
127
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
11 ICM
other and discuss the issues at hand for quick resolution. It may be a submittal missing a piece of information, or a conflict with an existing structure. These phone calls are followed up with emails and RFIs and are reviewed at each weekly progress meeting. In so doing, the project advances more rapidly and, at the same time, everyone is made aware of issues.
If the issue is too difficult or complex to handle at the field level, special meetings are held to resolve the issue. At any time this approach can be changed to a rigid hierarchical communication structure, depending on the project needs.
The second approach is to use the features of today’s
document management systems, such as ProCore, to
allow for concurrent review of submittals and RFIs. This means that the contractor will transmit a submittal
directly to the engineer who will answer that submittal directly back to the contractor, while the CM and Agency is reviewing the document concurrently. This concurrent review process saves a significant amount of time and
will help us to complete the projects on time. At any time this approach can be changed to the more traditional,
rigid “hub and spokes” approach, where all RFIs and
submittals are first routed through the construction
manager.
3. Open Item List. At 75 percent completion, ICM will
issue an Open Item List to the contractor. The Open Item List is similar to a Punchlist. It itemizes the incomplete work so that the contractor has a good understanding of the components ICM considers requiring attention. This allows the contractor to complete this work prior to demobilization, rather than later, after Substantial Completion. In this way, the Punchlist should be small and quickly resolved.
4. Control of Costs: ICM is firm but fair in determining equitable adjustments for time and money. We will keep the Agencies appraised of potential changes on a regular basis. We perform an independent cost estimate for change orders. We are meticulous in every change having a paper trail and detailed, appropriately approved paperwork.
5. Control of Contactor’s Schedule: ICM performs our own schedule review. We verify the schedule meets the requirements of the Construction Contract. We review the project milestones and critical tasks. We will develop a master schedule of the three projects that will allow all parties to see the track of the projects, especially as we get close to start up.
ICM will work with Control Point, Frisch, and the contractors to develop a master startup schedule, this being one of the most critical aspects of the projects.
The Agencies are starting their projects with excellent design firms and three successful contractors, all with great reputations. ICM offers the Agencies a local firm who knows the local project participants, a firm with the know-how to deliver you three successful projects and successfully get them to function together. Our approach is thorough, and detail oriented, but it is also simple, without many layers of redundancy. This allows you to be in direct contact with our team leaders on a daily basis.
SRWA, Raw Water Pump Station, 2020
128
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
12 ICM
Quality Assurance/Quality Control (QA/QC)
The purpose of ICM’s Quality Assurance/Quality Control
program is to verify that the Project is constructed to the highest levels of quality and for overall construction contract compliance. Our QA/QC program has two components: our staff and our standard operating procedures. All our staff are part of ICM’s QA/QC program in differing capacities as follows. The managers of the QA/QC program are Jeffrey Inferrera, Ricardo Bedoy, Paul Lopez, and Garrett Shonkwiler.
Jeffrey Inferrera is the lead manager of, and has ultimate responsibility for, ICM’s QA/QC program. Jeff is assisted by Ricardo Bedoy, Paul Lopez, and Garrett Shonkwiler. Ricardo is a California Licensed Civil Engineer with over 35 years of experience as a construction manager and resident engineer of small and large water and wastewater public works projects. Paul has over 35 years of experience as a construction inspector of small and large water and wastewater public works projects.
Garrett Shonkwiler has recently joined ICM to assist with our QA/QC program and has an accounting degree.
Supporting the QA/QC team are our experienced staff made up of two construction managers and 13 inspectors, each with more than 10 years in the water and wastewater public works industry. These engineers and inspectors are experienced and qualified. We love encouraging and training the next generation of engineers and inspectors. Currently, we have one “junior” engineer and one “junior” inspector, with less than 10 years of experience, and they are trained by our more experienced staff.
To maintain quality, we use Standard Operating Procedures (SOPs). These procedures include QA/QC procedures, inspection procedures and administration procedures.
The purpose of the QA/QC SOPs is to oversee our construction management and inspection services. This is accomplished by our QA/QC team. Through periodic, as well as random, review of ICM’s work products, we are able to maintain and improve our work.
The purpose of the inspection SOPs is to attain high quality construction. The inspection procedures set the standard for the review and inspection of the contractor’s quality of construction for each trade’s workmanship, products, and installation. It also includes quality control testing standards.
The purpose of the administration SOPs is to provide our Owner’s with the documentation needed to assist with project technical needs and for claims support. The administration procedures provide standards for project documentation, file retention and file retrieval. They address the accuracy, completeness and timeliness of project meeting minutes, contract change orders, progress payments, schedule reviews, submittal reviews, RFI reviews, labor compliance documentation, as-builts, and other
reports/deliverables.
Jeffrey Inferrera, California Licensed
Civil Engineer, Registered Construction
Inspector. Jeffrey has over 35 years of
experience as a construction manager,
resident engineer, inspector and designer
on small and large water and wastewater
public works projects.
ICM employee talking with Contractor
at the SJWD Hinkle Reservoir Project,
2023
129
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
13 ICM
Related Project/Client Information
1. Bob Granberg - Former General
Manager
Stanislaus Regional Water Authority
156 S Broadway # 270
Turlock, CA 95380
[email protected]
ICM provided construction management and
inspection services for a $240,000,000 brand new
treatment plant, pump station and 7 miles of
pipeline. Five contractors provided services for
this large project, Jacobs, Overaa Construction,
Mozingo Construction, San Joaquin Electric, and
Garney Construction. This project included
horizontal directions drilling and jack and bore,
under railroad tracks and canals.
2. Liz Carrington – Senior
Civil Engineer
El Dorado Irrigation District
2890 Mosquito Road
Placerville, CA 95667
[email protected]
(530) 642-4077
ICM provided construction management and
inspection services for two consecutive projects
for Liz Carrington, the Motherlode Force Main
Project and the Sly Park Intertie Improvements
Project. The Motherlode Force Main Project
consisted of installing 3.3 miles of C900 sewer
force main. This project included horizontal
directional drilling and bore and jack. Teichert
was the contractor on this project. The Sly Park
Intertie Improvements Project is a $47,000,000
project consisting of building a brand-new pump
station and 7 miles of pipeline. There were two
contractors for this project; Mozingo
Construction and W.M. Lyles Co.
3. Nicholas Menezes – Public
Works Director
City of Yuba City
1201 Civic Center Blvd.
Yuba City, CA 95993
[email protected]
(530) 822-4640
ICM provided construction
management and inspection services for
multiple projects for Nicholas Menezes,
including the Bogue Road Sewer
Extension Project and the Wastewater
Treatment Facility Improvements
Project. The Bogue Road project
consisted of a new pump station and 1.5
miles of sewer force main.
130
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
1 ICM
Individual Staff Experience and Project Organization
ICM has assembled a highly experienced and qualified group of professionals for the Regional Sewer Pipeline Project. Our team has worked together on numerous projects similar to the Agency’s Project. Jeffrey Inferrera will be your Project Manager and Lead Construction Manager.
Jeffrey has more than 30 years of experience specializing in pipelines, pump stations, and treatment plants on projects up to $250 million. He is a team builder who has successfully managed projects with multiple contractors and multiple owners. He will work full time on your project.
Project Manager and Contract 1A and 1B Construction Manager - Jeffrey Inferrera, PE, RCI
Mr. Inferrera will be responsible for managing the overall construction management services, inspection coverage, and mitigation measure implementation for the Regional Sewer Pipeline Project and will report directly to the Agency Project Manager. He will conduct executive project meetings and, for Wheatlands projects, he will be the first point of contact between the engineer, the Agency, and the contractor. Mr. Inferrera will also be responsible to managethe tracking of project paperwork. He will respond to field oriented RFIs and submittals and negotiate change orders.
Jeffrey is one of northern California's top resident engineers and builds a high performing team on his projects that brings in the Owner, the contractor, and the designer into a collaborative relationship that is benefit to all parties. He has over 30 years of experience as a resident engineer and inspector working on large and small public water and wastewater systems. He is knowledgeable of all trades including civil, mechanical, structural, electrical, I&C, and SCADA.
He has worked on over 25 pump station and pipeline projects. He has just completed the Regional Treatment Plant, Pump Station, and Pipeline project for the Stanislaus Regional Water District. He also recently completed the Motherload Sewer Force Main Project and the Sly Park Intertie Pump Station and Pipeline Project. These projects are detailed in his resume.
PROJECT MANAGER
Jeffrey Inferrera, PE
CONSTRUCTION MANAGER
CONTRACT 1A/1B
Jeffrey Inferrera, PE
CONSTRUCTION MANAGER
CONTRACT 2
Ricardo Bedoy, PE
AGENCY PROJECT MANAGERS
Dane Schilling and Swarnjit Boyal
131
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
2 ICM
Contract 1A CM and Inspection Team
Contract 1A Pipeline Inspector - Scott Ahlstrom (ICM)
Mr. Ahlstrom has over 40 years installing and inspector pipelines. He formerly owned Ahlstrom Construction where he installed all types of pipe materials, including HDPE and C900, in all types of soils and configurations. Over the past 10 years, Scott has been one of the most sought-after pipeline inspectors in the Sacramento Area.
Contracts 1A and 2 Tunnel Inspector - Casey Kirk (Brown and Caldwell) Casey has over 30 years of experience in construction management and inspection of water and wastewater treatment facilities and pumping facilities. His specialty is tunneling and trenchless technologies and will be responsible to be the lead inspector for the Projects HDD and jack and bore tasks.
CONSTRUCTION MANAGER
TAC
Jeffrey Inferrera, P.E.
TUNNEL INSPECTOR
Casey Kirk
SUBCONSULTANTS
Youngdahl
R.E.Y. Engineers
American River Environmental
Circlepoint
Cumming Group
ADMINISTRATIVE SUPPORT
Roman Gary – Project Engineering
Elena Inferrera – Administration
Garrett Shonkwiler - QA
PIPELINE INSPECTOR
Scott Ahlstrom
132
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
3 ICM
Contract 1B CM and Inspection Team
Contract 1B Pump Station Inspector - Paul Lopez (ICM)
Mr. Lopez has over 30 years as a construction inspector for pump stations, as well as treatment plants and pipelines. He has worked on over 7 pump station projects while working with ICM. He is experienced in all trades.
Contracts 1B and 2 Electrical Inspector - Akil Barris, ICC (ICM) Mr. Barris is ICM's certified, full time, electrical inspector with over 12 years of experience. We depend upon him for inspecting switchgear, breaker testing, panels and PLCs, generator installation, and generally all of the larger voltage equipment. He also inspects instrumentation and controls and provides SCADA support. Mr. Barris checks our projects for code compliance on an as needed basis.
PUMP STATION INSPECTOR
Paul Lopez
CONSTRUCTION MANAGER
TAC
Jeffrey Inferrera, P.E.
2 ND INSPECTOR
Akil Barris TAC
ELECTRICAL INSPECTOR
Akil Barris
SUBCONSULTANTS
Youngdahl
R.E.Y. Engineers
American River Environmental
Circlepoint
Bay Area Coating Consultants
ADMINISTRATIVE SUPPORT
Roman Gary – Project Engineering
Elena Inferrera – Administration
Garrett Shonkwiler – QA
133
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
4 ICM
Contract 2 CM and Inspection Team
Contract 2 Construction Manager - Ricardo Bedoy (ICM)
Mr. Bedoy will be the main point of contact for Contract 2. His role is to provide resident engineering services on a part time basis. He will conduct meetings, review schedules, evaluate payment applications, resolve issue, and trouble shoot technical problems. Mr. Bedoy has more than 30 years of experience in the wastewater and water industry with emphasis in resident engineering and inspection for public works projects. He specializes in small and large pipelines and pump station projects.
Contract 2 Pipeline Inspector - Joe Saylor (ICM)
Mr. Saylor has over 30 years constructing and inspecting wastewater and water pipelines. He inspected 7 pipeline projects while working with ICM. Like Scott Ahlstrom, he has incredible experience as a pipeline contractor and will verify the pipeline is installed per the Contract.
Contract 2 Pump Station Inspector - Matt Livingston
(ICM)
Mr. Livingston has over 20 years of experience working on public works projects.
His experience includes pipelines, force mains, gravity lines, trenching, jack and bore, HDD, large earthwork projects, treatment plants, pump stations and roads.
CONSTRUCTION MANAGER
TAC
Ricardo Bedoy, P.E.
PIPELINE INSPECTOR
Joe Saylor
TUNNEL INSPECTOR
Casey Kirk
ELECTRICAL INSPECTOR
Akil Barris
PUMP STATION INSPECTOR
Matt Livingston
SUBCONSULTANTS
Youngdahl
R.E.Y. Engineers
American River Environmental
Circlepoint
Cumming Group
Bay Area Coating Consultants
ADMINISTRATIVE SUPPORT
Roman Gary – Project Engineering
Elena Inferrera – Administration
Garrett Shonkwiler – QA
134
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
5 ICM
Construction Management and Inspection Support
ICM has the largest, if not one of the largest, construction management and inspection groups in Northern California dedicated solely to working on wastewater and water treatment plants, pump stations, and pipelines. Our staffing resources, all local to Sacramento, is presented on the Table below:
ICM
Resources Chart
CA Licensed EngineerConstruction ManagementTreatment Plant InspectionBuilding InspectionPipeline InspectionCivil InspectionStructural InspectionMechanical InspectionElectrical InspectionCoatings InspectionDesign BuildConfined Space/10 hr OSHAYears at ICMYears’Experience Principal / Project Manager / Construction Manager / Inspector Jeffrey Inferrera, PE ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 19 34
Construction Manager / Inspectors
Augustine Inferrera, PE ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 2 4
Eric Harman, PE ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 2 35
Ricardo Bedoy, PE ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 10 36
Inspectors
Akil Barris, ICC ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 1 16
Chris Inferrera, EIT, ICC ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 6 13
Daniel Waymire ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 2 21
Don Kurosaka, PE ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 6 37
George Guorgui ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 1 21
John Inferrera, EIT ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 1 1
Joe Saylor ⬧ ⬧ ⬧ ⬧ ⬧ 3 28
Keith DeLapp, B. Sc. Arch. Eng. ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 7 32
Matt Livingston, ICC ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 10 26
Paul Lopez ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 14 30
Peter Lian ⬧ ⬧ ⬧ ⬧ ⬧ 1 35
Scott Ahlstrom ⬧ ⬧ ⬧ 3 35
Sam Zeitulaev, ICC ⬧ ⬧ ⬧ ⬧ ⬧ 1 3
Project Engineer / Document Control / Administration
Colleen Inferrera ⬧ ⬧ 6 7
Roman Gary, EIT, MS ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ ⬧ 2 3
Garrett Shonkwiler ⬧ 1 1
Elena Inferrera ⬧ ⬧ 3 3
Kateri Inferrera ⬧ 1 1
135
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
6 ICM
Administration Support
The following ICM team members will provide office support and quality assurance.
Project Engineering - Roman Gary, EIT, MS
Mr. Gary will assembling the as builts, including RFIs, submittals, change orders, and field revisions. He will also assist with operating the document management system. He has been performing these functions for ICM for the past 3 years.
Quality Assurance - Garrett Shonkwiler
Mr. Shonkwiler has 6 years of experience in accounting and auditing. He will provide quality assurance for this Project. He has performed quality assurance audits for five of our projects to date and his work has helped improve ICM services.
Administration - Elena Inferrera
Ms. Inferrera has 4 years of experience working in administration for ICM. She will is proficient in ProCore, Virtual PM, and handles all the paperwork that keeps the project moving.
Brown and Caldwell Support
ICM teams again with Brown and Caldwell who have offered their extensive firm services to support our team. Currently, Casey Kirk, a tunnelling specialist, is on our team to inspect the HDD and jack and bore work. Brown and Caldwell has also offered the services of the following location individuals.
➢ Stephen Walters - Construction Manager
➢ Gavin Lee - Pipeline Inspector
➢ Rick Sasser - Pump Station Inspector
➢ Dane Forsberg - Electrical Inspector
➢ Anthony Knapp - Pump Station Inspector
We understand that, if selected, you selected the construction managers and inspectors that ICM has presented in our proposal. ICM’s staff and subconsultants are local and are dedicated to your project.
Exceptions
ICM takes no exceptions to the Sample Contract.
ICM’s proposal does not contain proprietary or sensitive information. 136
Section 6, Item # 6.3
Proposal for
CONSTRUCTION MANAGEMENT AND INSPECTION
Wheatland-OPUD Regional Sewer Pipeline Project
1 ICM
Appendices
➢ Resumés
➢ Sample Documents – Monthly Report Example
137
Section 6, Item # 6.3
Jeffrey J. Inferrera, PE, RCI Construction Manager
Qualifications
Registrations:
Professional Civil
Engineer, California No.
62190
Registered Construction
Inspector (Division 1)
ACIA, No. 5832
DBIA, pending
Education:
MS, Environmental
Engineering, Cornell
University, 1991
BS, cum laude,
Environmental Science
and Engineering, Rutgers
University, 1986
Mr. Inferrera has more than 30 years of experience in the water and wastewater industry with emphasis in construction management, resident engineering, and inspection. He specializes in water and wastewater treatment plants, pump stations, and pipelines.
Sly Park Intertie Project, El Dorado Irrigation District Provided construction management for a new pump station and 5 miles of pipeline from Sportsman Pump Station to Reservoir A WTP. Work included three 700 hp pumps, VFDs, three 500 KW generators, concrete and CMU building, 24-inch CMLC steel pipeline, slip line piping, treatment plant modifications
Regional Surface Water Supply Project, Stanislaus Regional Water Authority Provided construction management for a new $240 million 15 MGD treatment plant and 7 miles of 42” and 30" pipeline. Final capacity will be 45 MGD. System components included pre-oxidation with permanganate; flash mixing; flocculation; sedimentation; ozonation; GAC/sand filters; chlorine disinfection; clear well; pumping station; residuals handling facility; chemical storage and feed equipment; corrosion control; cybersecurity provisions; power supply and emergency generator power; I&Cs; administration, operation, maintenance, and laboratory facilities; and site civil improvements.
Peterson WTP Floc/Sed Rehabilitation Project, San Juan Water District - Resident Engineer and inspector for the rehabilitation of the WTP flocculation systems. The project consists of removal and replacement of five flocculation systems and four sludge collection systems, construction of settled water channel, baffle walls, launders, polymer pumps as well as new MCCs, fiber optics and SCADA upgrades.
WWTF Rehabilitation Project, City of Yuba City - Construction manager for this project which consisted of Digester fixed covers and gas system piping, Bar Screen replacement, structural steel canopy and sludge dewatering screw presses including conveyance system. Major electrical and control improvements included new Motor Control Centers, PLC’s, 12KV transformers, electrical ductbanks, and SCADA integration of five process areas, plus modernization of facility network.
Hindle Reservoir Project, San Juan Water District - Resident engineer for the installation of a new liner and new cover on the 15-acre Hinkle Reservoir Project. This project was completed one week early.
Oak Avenue Wastewater Pump Station, City of Folsom - Performed resident engineering and inspection of the Oak Avenue Wastewater Pump Station. Station consisted of the construction vactor discharge location, piping, concrete ramp, manhole, and fencing. Mr. Inferrera was responsible for contract administration, inspection, change orders, resolution of contractor conflicts and of technical issues.
Lake Forest Pump Station, City of Folsom - Resident Engineer for the demolition of the existing pump station and the construction of a new pump station with wet well, electrical, instruments, pumps, piping, flow meter, associated equipment, and site improvements. Two 15 hp submersible pumps were set at the bottom of a wet well. The pumps discharged to 8inch ductile iron force main and flowed through a magnetic 138
Section 6, Item # 6.3
Jeffrey J. Inferrera, PE, RCI Construction Manager
flowmeter. Mr. Inferrera was responsible for contract administration, change orders, resolution of contractor conflicts and of technical issues.
Jenny Lind Water Treatment Plant Filter & Solids Handling Project, Valley Springs, CA. - Resident Engineer for the WTP expansion upgrading the plant capacity from 5mgd to 6 mgd. The project consisted of adding a 700-gpm filter and 2,000 sq of floor area to an existing treatment building, installing solids thickener tank and sludge collector equipment, and upgrading instrumentation and controls.
Treatment Plant Expansion and Improvement Projects, City of Manteca - Construction manager and/or inspector for over $100 million of plant expansion and improvement projects including the following:
• New Influent Pump Station.
• Construction of aeration basins and secondary clarifiers. • New 10 mgd tertiary filtration and UV disinfection.
• New solids handling facility including sludge mixing tank. • North Plant Aeration Efficiency Improvements.
• Two new digesters, rehabilitation of two existing digesters, new digester control building. • Digester gas fueling facility.
Raw Water Pump Station Project, Stanislaus Regional Water District, Construction Manager for a 45,000 gpm (100 cfs) raw water pump station in the levee of the Tuolumne River, east of Modesto. This work included soil freeze excavation shoring and construction of a large pump station within a levee. Site civil work in the flood plain and discharge of high pump station flows in the river made this Project environmentally sensitive.
Atherton Booster Pump Station and Water Tank Project, City of Manteca - Construction manager for the construction of a 5 MGD booster pump station, 3.6 million steel tank, and related electrical, controls, instrumentation, piping, and site civil work.
Pump Stations Rehabilitation Project, Delta Diablo - Construction Manager for this project which consisted of rehabilitation of five active and elderly pump stations. All trades were working including piping, pumps, electrical, instrumentation and controls, coatings, concrete, HVAC, and site civil plus critical shut downs and bypass pumping.
Ione Wastewater Treatment Plant Phase 1 and 2, City of Ione - Resident engineer and inspector for the Phase 1 improvements including new wastewater pipelines interconnecting the wastewater lagoons, new dual wastewater pump station, aeration pond modifications, new aerators, electrical, coatings, vaults, and valves. Phase 2 improvements included the lining of five ponds; 550,000 sq ft of liner.
St. Andrew’s Lift Station Upgrade, El Dorado Irrigation District - Resident engineer for the $1 million upgrade of St. Andrew’s Lift Station upgrade project. Construction work includes demolition of the existing electrical/mechanical dry pit, installation of five raw sewage pumps ranging from 3 to 150 hp, installation of a 500 kW generator, miscellaneous valves and piping, and a masonry electrical control building.
Las Vegas Wastewater Treatment Plant, City of Las Vegas - Resident engineer for plant expansion of city’s water pollution control facility expansion from 66 to 93 mgd. This $105 million expansion program involved 13 separate construction contracts, six separate contractors, and multiple contracts. Facilities involved in this expansion include secondary clarifiers, blower building, primary sedimentation, biological nutrient removal, chlorination/dichlorination, chemical feed facilities, filtration, anaerobic digesters, pumping stations, SCADA, headworks, mechanical dewatering, odor control, and O&M building.
Approximately 10,000 lineal feet of pipeline was installed ranging in size from 8 to 120 inches in diameter. 139
Section 6, Item # 6.3
Ricardo Bedoy, PE Resident Engineer
Mr. Bedoy has over 30 years of experience in the construction management and inspection of construction projects. Projects range up to $84 million. His expertise is in the management and inspection of treatment plants, pump stations and pipelines.
Arden Service Area Pipe & Meter Installation Phases 1B, 3, & 4,5,6 Project – Sacramento County Water Agency
Mr. Barris was the construction inspector for this potable water pipeline and meter project. The combined construction value of all three phases is $117 million. The three phases of the Project are as follows:
Phase 1B: 1/2 mile of 8" pipe, 4 miles of 10" pipe, 1/2 mile of 12" pipe, 1 mile of 16" pipe, and 299 meters.
Phase 3: 5 miles of 8" pipe, 1/2 mile of 10" pipe, 1 mile of 12" pipe and 618 meters.
Phase 4,5,6: 12 miles of 8" pipe, 1/2 mile of 10" pipe, 3 miles of 12" pipe and 1,423 meters.
The construction of the 35 miles of water mains and 2,919 meters installations included fire hydrants, backflow preventers, appurtenances, disinfection, and tie ins.
Also included was inspection of pipe installation, lateral tie ins, bedding, backfill, shoring, and traffic control.
Arden Service Area Pipe & Meter Installation Ph 1B Project – Sacramento County Water Agency
Construction Manager for the construction of 8 inch and 12 inch water mains as well as fire hydrants, backflow preventers, appurtenances and tie ins, new metered services. Consisted of approximately 3 miles of pipeline. Inspection was performed on the pipe installation, lateral tie ins, bedding and backfill, shoring, and traffic control. Construction cost $7,800,000.
Arden Service Area Pipe & Meter Installation Ph 2B Project – Sacramento County Water Agency CM and inspector for the construction of 8 inch and 12 inch water mains as well as fire hydrants, backflow preventers, appurtenances and tie ins, new metered services. Consisted of approximately 3 miles of pipeline. Inspection was performed on the pipe installation, lateral tie ins, bedding and backfill, shoring, and traffic control. Construction cost $9,900,000.
Penn Valley Pipeline, Pump Station and WWTP – Nevada County Resident engineer for the installation of 46,000 LF of 6” HDPE Sewer Force Main, Hwy 20 bore & jack, and Horizontal Directional Drill (HDD), 20” HDPE sewer gravity line, 20” HDPE pipe burst of a 15” VCP sewer line, new manholes, and rehabilitation of existing manholes, new pump station in Penn Valley, and headworks improvements at the Lake Wildwood Treatment Plant. Headworks improvements included recoating with Enduroflex, a new grit removal system and headworks odor control system. Construction cost $6,000.000.
Peterson WTP Floc/Sed Rehabilitation Project – San Juan Water District, CA. Resident Engineer and Inspector for the rehabilitation of the WTP flocculation systems. The project consists of removal and replacement of five flocculation systems and four sludge collection systems, construction of settled Qualifications
Registrations:
Professional Civil
Engineer, California
No. 39403
Education:
B.S., Civil Engineering,
California State
Polytechnic University,
Pomona, 1983
Certification
Army Corps
Contractors CQM
Certification
(Expired 2020)
140
Section 6, Item # 6.3
Ricardo Bedoy, PE Resident Engineer
water channel, baffle walls, launders, polymer pumps as well as new MCCs, fiber optics and SCADA upgrades.
Newark Sub-Basin Upper Relief Sewer Project - Union Sanitary District Construction Inspector for the construction of 3,500 feet of 21-inch polycrete sewer using microtunneling methods to cross under a highway bridge and railroad, and construction in residential and commercial areas. Construction cost $3,000,000.
BMP CDS Project - Pajaro Valley Water Management Agency Construction Manager for the construction of 10 miles of recycled water pipeline, 12-inch to 36-inch steel pipe, bores across Highway 1, Horizontal Directional Drill across the Pajaro River with 1,300 feet of 36-inch steel pipe, having a construction cost of $17,250,000.
Willow Pass Pump Station and Pipeline - Contra Costa Water District Resident Engineer for the construction of a 20,000 GPM pump station and two miles of 30-inch steel pipeline through commercial areas and contaminated soil removal. Construction cost $7,000,000.
Bay Point Pipeline and Pump Station - Contra Costa Water District Resident Engineer for the construction of three miles of 20-inch steel pipeline and new pump station.
The project consisted of pipeline construction through residential areas and Federal property, contaminated soil removal and extensive utility conflicts. Construction cost $3,200,000.
Castroville Seawater Intrusion Project - Monterey County Water Resources Agency Construction Manager for the construction of 43 miles of HDPE and CCP recycled water pipeline, ranging from 12-inch to 51-inch diameter, retrofit of existing water wells, new wells, pump stations, and bore crossings. Construction cost $32,000,000.
East Segment Pipeline: WSIP San Joaquin Region Projects - San Francisco PUC Lead Inspector for the construction of 6.7 miles of 78-inch welded steel pipe, three valve structures, fabrication inspection, having a construction cost of $45,000,000.
West Segment Pipeline, WSIP San Joaquin Region Projects - San Francisco PUC Lead Inspector for the construction of 11 miles of 78-inch welded steel pipe, four highway borecrossings, crossing Delta-Mendota Canal and California Aqueduct, Construction cost $48,000,000.
Pipeline Phase II Project - San Diego Gas & Electric
Project Engineer for Phase II consisting of 30,000 feet of 36-inch steel gas main through heavily travelled commercial districts and a $6,000,000 construction cost.
Pipeline 4 Extension, Phase II - San Diego County Water Authority Resident Engineer for 7.75 miles of 72-inch steel pipeline construction through fully developed residential areas, open country, tunnel crossings of major arterials, and environmentally sensitive areas.
Construction cost $25,000,000.
Reservoir 4A & Pump Plant No. 6 - La Habra Heights County Water District Project Manager for the design and construction of a 2.0 MG steel reservoir and pump station relocation having a $1,100,000 construction cost.
141
Section 6, Item # 6.3
Akil Barris, ICC Electrical and Controls Inspector
Qualifications
Certificates/ Registrations
ICC Mechanical Inspector
ICC Electrical Inspector
OSHA 10/20/40 hr Training
Confined Space Training
Mr. Barris has more than 16 years of experience in the construction industry. With one year of experience inspecting, under ICM's tutelage, Mr. Barris has become an outstanding public works inspector. His emphasis is in electrical systems for water and wastewater projects.
Sly Park Intertie Project – El Dorado Irrigation District Special electrical inspector for a new pump station at Reservoir A WTP. Work inspected included three 700 hp pumps, VFDs, three 500 KW generators, conduits, ductbanks, communications, and main switch board modification which involved a green tag inspection with PG&E.
FEMA Generator Project - El Dorado Irrigation District. Special inspector for the installation of fifteen emergency backup generators at District's remote facilities. The facilities were both wastewater lift stations and water pump stations.
Generator installation required shut downs, startup and testing. Other parts of the project included retaining walls, concrete slabs, and electrical installation.
Arden Service Area Pipe & Meter Installation Phases 1B, 3, & 4,5,6 Project – Sacramento County Water Agency
Mr. Barris was the construction inspector for this potable water pipeline and meter project. The combined construction value of all three phases is $117 million. The three phases of the Project are as follows:
Phase 1B: 1/2 mile of 8" pipe, 4 miles of 10" pipe, 1/2 mile of 12" pipe, 1 mile of 16" pipe, and 299 meters.
Phase 3: 5 miles of 8" pipe, 1/2 mile of 10" pipe, 1 mile of 12" pipe and 618 meters.
Phase 4,5,6: 12 miles of 8" pipe, 1/2 mile of 10" pipe, 3 miles of 12" pipe and 1,423 meters.
The construction of the 35 miles of water mains and 2,919 meters installations included fire hydrants, backflow preventers, appurtenances, disinfection, and tie ins. Also included was inspection of pipe installation, lateral tie ins, bedding, backfill, shoring, and traffic control.
Prior Construction Project Experience
Mr. Barris has worked as a project manager and a tradesman on multiple water projects including pipeline installation, bore pit construction, water tank construction, valve installation, and construction of concrete vaults. His wastewater construction experience includes pipeline installation, manhole installation, manhole rehabilitation, CCTV and cleaning of sewer pipes.
142
Section 6, Item # 6.3
Joseph Saylor Construction Inspector
Mr. Saylor has more than 35 years of experience working on construction projects. His experience includes all types of pipe materials, trenchless technologies, site civil work, working in streets and working with the public. His inspector duties include verifying work is installed per plans and specifications, documenting work with photographs and daily reports, completing as-built drawings, and coordinating with the design engineer, agencies, and the public.
Sly Park Intertie Project - El Dorado Irrigation District. Inspector for the construction of a potable water pump station and a pipeline interconnecting two water treatment plants. The pump station consisted of three 700 hp pumps in a concrete and CMU building, piping, valves, three backup generators, MCC, fiber optics, electrical, instrumentation, controls, and SCADA. The pipeline work included 5-miles of 24- inch, a half mile of 30-inch CMLC steel pipe, 1,000 feet of sliplining a 22-inch steel pipe with 14-inch PVC, creek crossings, 60 degree slopes, bedrock, blow offs, ARVs, and cathodic protection. The pipeline portion of this $45 million project is scheduled to be completed in 2025. Joe worked together with District staff for shutdowns and tie ins including operational staff at Reservoir A and distribution staff for the pipeline. He is knowledgeable of the District’s testing, flushing and disinfection procedures.
Flume 47A – El Dorado Irrigation District. Inspector for flume replacement, retaining wall, slope stabilization, and access road.
Mother Lode Force Main Project – El Dorado Irrigation District. Inspector for this $13 million project consisting of 3 miles of 18- and 20-inch C900 sewer force main installed from the El Dorado Lift Station to the Shingle Springs Lift Station mostly in the east bound lane of Mother Lode Drive, including rock excavation, three microtunnels, paving, and valves. This project was successfully finished with no claims. 30” WSP Pipe Highway 50 Project – El Dorado Irrigation District. Inspector for 1,000 linear feet of welded steel pipeline for transmission of potable water including appurtenances, testing, flushing, and disinfection.
Carson Creek Lift Station – El Dorado Irrigation District. Inspector for this new lift station in the Town Center Development in El Dorado Hills. This was a developer project as part of the development backbone infrastructure.
Pollock Pines Pipeline Project – El Dorado Irrigation District. Inspector for 4 miles of 4 to 10 inch ductile iron potable water pipe. This pipeline was constructed in roadways requiring extensive traffic control and coordination with El Dorado County Department of Transportation. Joe worked with EID’s distribution staff for the testing, flushing, and disinfection of the pipeline.
Developer Subdivision Pipeline Projects – El Dorado Irrigation District. Inspector for water and sewer pipelines in ten subdivisions for an ultimate build out of 618 homes. Joe verified compliance with the District’s standards and specifications. He also coordinated with EID’s distribution staff for the testing, flushing, and disinfection of the water lines.
143
Section 6, Item # 6.3
Matthew Livingston, ICC Inspector
Qualifications
Certifications:
ICC Building Inspector,
5232456-10
ACI Level 1 01031459
Troxler Nuclear Gauge
Certification 44154
Mr. Livingston has over 20 years of experience as a construction inspector. He has performed inspection on water and wastewater treatment and distribution projects including treatment facilities. His experience includes building inspections, code compliance, site civil work, pipelines, force mains, gravity lines, trenching, working in streets and working with the public.
Water Treatment Plant and Pipeline Project - Stanislaus Regional Water Agency. SRWA's $250 million Regional Surface Water Supply Project consisted in the construction of a new 15 MGD water treatment plant, 7 miles of potable water pipeline to the City of Turlock, 5 miles of potable water pipeline to the City of Ceres, and a 1 mile raw water pipeline from the Tuolumne River Water Intake Pump Station to the treatment plant. Matt was inspector on this 3-year project from start to finish. The pipelines consisted of two potable water force mains made of 30" MCML and 40" MCML steel pipe, and one 48" MCML raw water pipeline.
There were six jack and bore tunnels including two under the Santa Fe Railroad and others under EID canals. The treatment plant consisted of rapid mix tanks, flocculation and sedimentation tanks, filter building, chemical building, backwash tank, sludge lagoons, administration building, laboratory, and maintenance building.
Arden Service Area Pipe and Meter Installation Project – Sacramento County Water Agency. These were three concurrent but separate pipeline projects. The projects included the installation of 6 inch to 12 inch ductile iron pipe and C900 pipe. Each project encompassed about 3 miles of water force main in Sacramento neighborhoods and installation of 100s of meters, plus valves and hydrants. This work also included disinfection inspection.
Raw Water Pump Station Project - Stanislaus Regional Water Agency. Inspector for a 45,000 gpm (100 cfs) raw water pump station in the levee of the Tuolumne River, near Hughson. This work included soil freeze shoring to a depth of 75 feet that facilitated the excavation and construction of a large pump station within the levee. Site civil work in the flood plain and discharge of high pump station flows in the river made this Project environmentally sensitive.
North Trunk Sewer Project – Manteca, CA. This project involved the construction of two miles of 48- inch RCP sewer pipe and 12-inch C900 water force main. Matt was the inspector mostly for the micro tunnel portion of the Project. Two micro tunnels were constructed. The first micro tunnel consisted in a 230 foot long, and 30 foot deep, 80-inch micro tunnel under Airport Road. The second micro tunnel consisted in a 375 foot long, and 35 foot deep, 60-inch micro tunnel under Yosemite Boulevard.
FEZ South Trunk Sewer Project – Manteca, CA. This project involved the construction of two miles of 48-inch RCP sewer pipe and 12-inch C900 water force main. Matt was the inspector mostly for the micro tunnel portion of the Project. The micro tunnel consisted in a 500 foot long, and 30 foot deep, 80-inch micro tunnel under State Highway 120.
144
Section 6, Item # 6.3
Matthew Livingston, ICC Inspector
SFPUC San Joaquin Eastern Segment Water Pipeline. Civil QA Inspector on a 6.7-mile, 78-inch water pipeline project with a construction cost of $45,000,000. Responsible for QA inspection of rebar & concrete construction for three Valve Vault structures and the Oakdale Portal Protection structure.
SFPUC San Joaquin Western Segment Water Pipeline. Civil QA Inspector on an 11-mile, 78-inch water pipeline project with a construction cost of $48,000,000. Responsible for QA inspection of native soil cement placement in the pipe zone & trench backfill.
SFPUC Tesla Water Treatment Facility. Civil QA Inspector on design-build project with a construction cost of $84,000,000. Responsible for inspection of concrete, roofing, building inspection of the various building trades, AC paving, and punch list inspections.
WQCF Digester Project – Manteca, CA. lead inspector for the construction of two digesters, and rehabilitation of two existing digesters including grading, stone column soil densification, underground utilities (gas, electrical, process piping, storm water), reinforced concrete structures, CMU digester control building, 17kv power, instrumentation, controls, CMMS, and SCADA.
BART Intermodal Modernization Project - Union City CA. as a Quality Control Manager, provided all inspection work for civil, underground, concrete structures and building trades.
Presidio Monterey, General Instruction Building. Provided QC inspection of structural construction.
Perform civil and building inspection of general civil works and the various building trades. This was a $42 million project.
Deuel Institute, Water Treatment Facility - Tracy CA. Performed civil inspection and testing.
Deuel Institute, Reverse Osmosis Facility - Tracy CA. Performed civil inspection and testing throughout entire project. Performed special inspections including epoxy anchors and pull testing. This was a $32 million facility.
145
Section 6, Item # 6.3
Paul Lopez Inspector
Qualifications
Education/Certifications
Civil Engineering, California
State University, San Diego,
1983 to 1986
Registered Construction
Inspector (Division 1),
American Construction
Inspectors Association, No
6035
D1 – Water Distribution
Operation, California
Department of Health, No
42251
Competent Person Training,
Trenching and Excavation
Confined Space Training,
Asbestos Concrete Pipe
Safety Training
Mr. Lopez has 29 years of experience as a public works construction inspector. He has performed inspection on water and wastewater treatment and distribution projects including treatment facilities, pump stations, and pipelines. His work includes reinforced concrete and masonry structures, mechanical equipment, force mains, gravity lines, trenching, jack and bore, electrical and instrumentation, working in streets and working with the public.
Pleasant Grove Wastewater Treatment Plant, City of Roseville, CA Inspector for the Pleasant Grove $98 million wastewater treatment plant. For three years, provided inspection and reporting of over 20 structures including the pump station and headworks. Covered civil, structural and mechanical disciplines.
Inspected deep underground pipelines that required shoring and dewatering.
Inspected ductile iron pipe, vitrified clay pipe, reinforced concrete pipe, and lined piping systems. Mechanical inspection included vertical turbine pumps, compressed air filtration and HVAC systems. Inspected utilities, reinforced concrete and masonry structures, structural backfill, and roadway construction.
Provided inspection for coatings and electrical. Reviewed contractor progress payments, submittals, RFI’s and SWPPP.
Water Treatment Plant Sedimentation and Flocculation Improvements Project – San Juan Water District, CA. Inspector for the replacement of sludge removal system, flocculator drive motors and paddles, rapid mixers and motor control cabinets (MCC). Work included new structural support columns, 500 linear feet of a concrete settled water channel, chlorine and polymer distribution systems, stainless steel and ductile iron piping systems and new sample pumps and analyzers.
Yuba WWTF Rehabilitation , City of Yuba City, CA
Inspector for the City of Yuba City Wastewater Treatment Facility Improvements Project consisted of Digester fixed covers and gas system piping, Bar Screen replacement, structural steel canopy and sludge dewatering screw presses including conveyance system. Major electrical and control improvements included new Motor Control Centers, PLC’s, 12KV transformers, electrical ductbanks, and SCADA integration of five process areas, plus modernization of facility network.
Wastewater Treatment Plant Expansion Project, City of Woodland, CA Senior construction inspector on this $28 million wastewater treatment plant expansion project. With a project duration of two years, provided inspection and reporting of over 10 structures including a new pump station at a depth of 15 feet including dewatering and Class 3 soils. Underground pipe trenches were shored and dewatered, soil conditions were poor. Inspected aboveground piping, concrete structures, manholes, and pump and mechanical systems. As the inspector of record, provided oversight of all construction activities, coordinated work activities with the general contractor, and was responsible for project daily inspection and report writing. In addition, worked directly with the design engineer to work through design changes and resolve construction issues. Reviewed progress payments, submittals, and RFI’s. 146
Section 6, Item # 6.3
Paul Lopez Inspector
Peterson Water Treatment Plant Pipeline and Plant Improvements, San Juan Water District, CA.
Inspector for construction at this 120 MGD plant. This $4 million project consisted in the complicated construction of 78 inch, 72 inch, and 60 inch mortar lined and coated welded steel pipe within the District’s water treatment facility. Pipes ran over, under and around all types of utilities and structures. Extensive blasting was performed in granite rock. Multiple complete plant shutdowns were performed. Plant improvements included chlorine and laboratory piping.
Wastewater Treatment Plant Improvements Project, City of Manteca, CA Inspector for a sludge removal system, water diversion structure, mechanical shop and employee locker room. The work included new masonry buildings, concrete diversion structure, underground pipelines, aboveground piping systems, mechanical systems and electrical improvements. As the inspector of record, provided oversight of all construction activities, coordinated work activities with the general contractor, and was responsible for project daily inspection and report writing. In addition, worked directly with the design engineer to work through design changes and resolve construction issues. Reviewed progress payments, submittals, and RFI’s.
Carson Creek Pump Station – El Dorado Irrigation District, CA. Inspector for the demolition of an existing sewer pump station and construction of a new replacement pump station. The work included new wet well, electrical/operations building, pumps, emergency generator, force main piping, gravity piping, electrical, and site civil.
Bridlewood Canyon Pump Station – El Dorado Irrigation District, CA. Inspector for the rehabilitation of an existing sewer pump station. The work included wet well improvements, new MCC’s and instrumentation, pumps, emergency generator, odor control, force main piping, electrical, and site civil.
Lake Forest Pump Station – City of Folsom, CA. Inspector for the demolition of an existing pump station and construction of a new replacement pump station. The work included new wet well, pumps, emergency generator, force main piping, gravity piping, electrical, and site civil.
Oak Avenue Pump Station – City of Folsom, CA. Inspector for the rehabilitation of an existing pump station and installation of new pumps. The work included new overflow holding tanks, pumps, force main piping, gravity piping, electrical, and site civil.
Atherton Pump Station and Tank Project – Manteca, CA. Inspector for the construction of a 5 MGD pump station, 3.6 million steel tank, and related electrical, controls, instrumentation, piping, and site civil work.
Municipal Well Pump Station and Piping System - City of Woodland, CA Senior construction inspector on this $1.5 million water pumping and piping system. The project included over 4,000 feet of underground piping including ductile iron pipe in City roadways. As the inspector of record, provided oversight of all construction activities, coordinated work activities with the general contractor, and was responsible for project daily inspection and report writing.
Van Maren Pumping Station, County of Sacramento, CA
Construction inspector for a new $17 million pump station. This 2 year project included a T-lock lined 35 foot deep wet well, two diversion structures, three tunnel borings and 1500 feet of 36” sanitary sewer pipeline 24 feet below grade. With poor soil conditions, shoring and dewatering was critical. Inspected subgrade, rebar, formwork, concrete placement, T-lock lining system, pipeline installation, backfill, pump installation, and instrumentation. Reviewed contractor progress payments, submittals, RFI’s and performed SWPPP inspections.
147
Section 6, Item # 6.3
Scott Ahlstrom Construction Inspector
Qualifications
Certificates/ Registrations
Class A Contractors License
D1 Water Distribution
Operator
Confined Space Training
Mr. Ahlstrom has over 20 years of experience as a public works construction inspector. He has performed inspection on water and wastewater treatment and distribution projects including pipelines, treatment facilities, and pump stations.
Arden Service Area Pipe & Meter Installation Phases 1B, 3, & 4,5,6 Project – Sacramento County Water Agency
Inspector for the construction of 8 inch and 12 inch water mains as well as fire hydrants, backflow preventers, appurtenances and tie ins, new metered services.
Consisted of approximately 30 miles of pipeline. Inspection was performed on the pipe installation, lateral tie ins, bedding and backfill, shoring, and traffic control.
Construction cost $24.1 million.
Other Project Experience
• Well 41 Pump Station Improvements Project, SSWD
• Well 78 Butano/Cottage Pumping Plant Project, SSWD
• Greenberry Water Meter Retrofit Project, SSWD
• Arcade Creek Crossing Project, SSWD
• U Street Loop Project, SSWD
• Thor Water Main Replacement Project, SSWD
• Jonas Water Main Replacement Project, SSWD
• Albatross Water Main Replacement Project, SSWD
• Naomi Water Main Project, SSWD
• Edison Meadows Water Main Replacement Project, SSWD
• Parkland Estates Water Main Replacement Project, SSWD • Drayton Heights Water Main Replacement Project, SSWD
• Santa Anita Water Main Replacement Project, SSWD
• Arden Oaks Water Main Replacement Project, SSWD
• North Country Club Estates Water Main Replacement Project, SSWD • Oak Plains Estates Water Main Replacement Project, SSWD • North Highlands Phase II Water Main Replacement Project, SSWD • Tower-Tesla Water Main Replacement Project, SSWD
• New Broadmoor Water Main Replacement Project, SSWD
• Country Club Estates Water Main Replacement Project, SSWD • Terry Lynn Estates Water Main Replacement Project, SSWD 148
Section 6, Item # 6.3
Elena Inferrera Project Administrator
Qualifications
Certifications:
Confined Space Certified
OSHA Certified
CPR/First Aid Certified
Ms. Inferrera has over 4 years of experience in the administrative world, including document control, certified payroll, electronic filing, ProCore and Virtual PM. She will manage the document tracking system and general administration. She specializes in document control of pipelines, pump stations, and water and wastewater treatment plants.
Project Administration and Controls on the following projects:
Pump Stations
• Arden Fluoridation Facilities Project – Golden State Water Company • Reservoir 3 and Clarifier Re-Coating Project – Golden State Water Company • Trussel Plant – Well Equipping, Booster Station & Reservoir – Golden State Water Company
• Raw Water Pump Station Phase 1 – Stanislaus Regional Water Authority • River Bluff Reservoir and Pump Station – City of Ceres • Pump Stations Rehabilitations – Delta Diablo Sanitation District • Oak Avenue Pump Station PWWF Relief Project – City of Folsom Pipelines
• Barrett Ranch East Phase 1 – Sacramento Suburban Water Distict • Arden Water Services and Pipeline Phase 1B – Sacramento County Water Agency • Arden Water Services and Pipeline Phase 2A – Sacramento County Water Agency • Arden Water Services and Pipeline Phase 2B – Sacramento County Water Agency • Arden Water Services and Pipeline Phase 3 – Sacramento County Water Agency • Arden Water Services and Pipeline Phases 4, 5, 6 – Sacramento County Water Agency
• Fair Oaks 40 Pipeline Relining Project – San Juan Water District • Hanks Exchange Pipeline – El Dorado Irrigation District • Mare Island Way Sewer – Vallejo Flood & Wastewater District • Stormwater Trash Capture Project – Vallejo Flood & Wastewater District • Lafayette Sewer Renovations – Central Contra Costa Sanitary District • North Trunk Sewer Project – City of Manteca
• Water Mains and Services Project – San Juan Water District • Valley Vista Development Project – Tuolumne Utilities District • Garden Highway Trunk Line Rehab Phase 1 Project – City of Yuba City • Town Center Force Main Phase 3 - El Dorado Irrigation District Treatment Plants
• Peterson Water Treatment Plant FLOC/SED Rehabilitation – San Juan Water District • Regional Surface Water Supply Water Treatment Plant – Stanislaus Regional Water Authority • Hinkle Reservoir Outage Temporary Tanks – San Juan Water District • Wastewater Treatment Facility Improvements Project – City of Yuba City • Wastewater Treatment Plant Odor Control Project – El Dorado Irrigation District • Deer Creek Process Improvements – El Dorado Irrigation Distract • WTP Backwash and Recycled Water Upgrades Project – City of Folsom • Hinkle Liner and Cover Replacement – San Juan Water District • Collections Relocation EDHWWTP – El Dorado Irrigation District 149
Section 6, Item # 6.3
Garrett Shonkwiler Quality Assurance
Qualifications
Certifications:
Confined Space Training
OSHA / 10 Hr
Construction Scheduling
and Claims Course
Since joining ICM, Mr. Shonkwiler has provided quality assurance/quality control audits on our projects. Coming from the accounting field, we are excited at meticulous attention to detail.
Mr. Shonkwiler has six years of experience in accounting and one year with ICM.
He is proficient in quality assurance and has worked on several ICM projects including the following:
Arden Service Area Pipe and Meter Installation Project, Phases 4,5,6 – Sacramento County Water Agency
Provided Quality Assurance and auditing to ICM’s construction management and construction inspection.
Sly Park Intertie Project – El Dorado Irrigation District Provided Quality Assurance and auditing to ICM’s construction management and construction inspection.
Water System Flow Control Facilities Rehabilitation Project – City of Folsom Provided Quality Assurance and auditing to ICM’s construction management and construction inspection.
Pleasant Hill Sewer Renovations Phase 4 Project - Central Contra Costa Sanitary District
Provided Quality Assurance and auditing to ICM’s construction management and construction inspection.
Groundwater Recharge Basins Project- City of Stockton
Provided Quality Assurance and auditing to ICM’s construction management and construction inspection.
5 Star Intertie Project - City of Roseville
Provided Quality Assurance and auditing to ICM’s construction management and construction inspection.
150
Section 6, Item # 6.3
Roman Gary, EIT, MS Project Engineer
Qualifications
Registrations:
EIT, Civil, 163958, 2018
OSHA 10 Hour
Confined Space Training
Education:
MS, Civil Engineering,
Sacramento State
University, 2022
BS, cum laude, Civil
Engineering, San Diego
State University, 2018
Mr. Gary specializes in keeping projects on track. His emphasis is coordinating bid documents, conformed documents and as built documents. He is experienced in document control using Procore, Virtual Project Manager, and Synology NAS.
Sly Park Intertie Project, El Dorado Irrigation District Assistant resident engineer for the construction of a potable water pump station and a pipeline interconnecting two water treatment plants. The pump station consisted of three 700 hp pumps in a concrete and CMU building, piping, valves, three backup generators, MCC, fiber optics, electrical, instrumentation, controls, and SCADA. The pipeline work included 5-miles of 24-inch, a half mile of 30-inch CMLC steel pipe, 1,000 ft of sliplining a 22-inch steel pipe with 14- inch PVC, creek crossings, 60 degree slopes, bedrock, blow offs, ARVs, and cathodic protection. This $45 million project is scheduled to be completed in 2025.
Mother Lode Force Main Project, El Dorado Irrigation District Assistant resident engineer for this $13 million project consisting of 3 miles of 18- and 20-inch C900 force main installed from the El Dorado Lift Station to the Shingle Springs Lift Station mostly in the east bound lane of Mother Lode Drive, including rock excavation, tunnelling, paving, and valves.
Five Lift Stations Rehabilitation Project, Delta Diablo Assistant construction manager for the Delta Diablo Sanitation District Pump Station Rehab project which consisted of rehabilitation of five wastewater pump stations. Work included all trades including pipelines, pumping systems, electrical, instrumentation and controls, industrial coatings, concrete, HVAC, and building construction.
Document Control using Procore on the following projects:
• EID 2024 Collections Rehabilitation Project
• EID East Ridge Tank and Pump Station
• EID Braden Court PRS #1 Replacement and
Transmission Valve Upgrades
• El Dorado Hills Wastewater Treatment Plant
Filter Rehabilitation
• EID Emergency Backup Generator Upgrades
• EID Flume 47A Replacement
• EID Folsom Heights – Phase 1
• EID Motherlode Force Main Phase 3
• EID Reservoir 4 and Reservoir 7A/7B Tank
Rehabilitation
• EID Reservoir 1 WTP Generator Replacement
• EID Sly Park Intertie
• EID Silver Lake Well
• EID Silver Springs Unit 3
• EID Reservoir 1 Floating Cover Emergency
Replacement
• EID Pioneer Place Force Main
151
Section 6, Item # 6.3
1 Stephen Walters, P.E.
Construction Manager
Stephen is a Construction Manager with 25 years of
experience in construction management and civil
engineering design in Northern California.
He has served every role from Resident Engineer to Construction Inspector to deliver hundreds of millions of dollars of water, wastewater, and bridge construction projects.
His areas of expertise include water pumping, well, storage, and treatment facilities, wastewater pumping facilities, piping, pipe rehabilitation, and various trenchless construction methods. His background includes bridge construction, structures construction, paving, civil improvements, electrical, and instrumentation and controls (I&C) systems. His design experience aids in performing constructability reviews that allow him to bridge gaps between design and field staff.
Paradise Pump Station Replacement, City of Corte Madera, Corte Madera, CA
Construction Manager. The project included construction of a new wet-well/dry-pit type
13.1 MGD facility located within a building on the property adjacent to and north of the existing pump station, demolition of this existing pump station, and associated site improvements. The new facility included five pumps; two 30 HP and three 300 HP drywell mounted submersible pumps housed in a 50- by 60-foot, two-story structure with a 28-foot-deep overflow and wet-well/pump intake area. Additional systems included a 1250 kW standby diesel generator, fuel storage and delivery, chemical injection, and surge suppression. Stephen coordinated several value engineering proposals, saving approximately $200,000 in construction costs.
Golden Hind Pump Station and Collection System Replacement, City of Corte Madera, Corte Madera, CA
Construction Manager. The new pump station included a submersible pump station, control system, emergency diesel generator, and directional drill replacement of 8,500 feet of gravity sewer. The project included video inspection and cure-in-place pipelining of over 200 laterals.
Stephen was responsible for daily inspections, quality assurance, document control, meetings, progress payments, change orders, negotiations, start-up assistance, punchlist, and close-out.
Parallel Forcemain Construction Management, City of Corte Madera, Corte Madera, CA
Construction Manager. This project rehabilitated approximately 4,500 LF of sanitary sewer forcemain. The work included sliplining portions of an existing forcemain and installing new force using sliplining, horizontal directional drilling, and traditional open cut. The project restored and improved sidewalks, pavement, traffic medians, and traffic signals. Stephen performed a pre-bid constructability review focused on staging and location of sliplining and receiving pits. He coordinated value engineering proposals to directional drill portions of the new forcemain and hot tap final connection to the District’s primary force main.
ASSIGNMENT
Construction Manager
EDUCATION
B.S., Civil Engineering,
California Polytechnic State
University, San Luis Obispo,
2000
YEARS OF EXPERIENCE
25 JOINED FIRM
2020
CERTIFICATION/TRAINING
Certificate Local Assistance
Resident Engineer Academy,
Institute of Transportation
Technology, 2008
Confined Space Trained, 2016
Competent Person Training for
Excavations, 2016
RELEVANT EXPERIENCE
- Construction Management
- Constructability Reviews
- Water & Wastewater
Construction
- Bridge & Structures
Construction
- Paving & Civil Improvements
- Electrical
- Instrumentation and controls
(I&C) Systems
- Multiple Web-based
Construction Management
Software (eBuilder, Procore,
VPM)
- Basic AutoCAD
- Partnering
- Microsoft Project
152
Section 6, Item # 6.3
Stephen Walters // Continued
Brown and Caldwell 2
Family Entertainment Zone – Phase 1 Underground Utilities, City of Manteca, Manteca, CA Construction Manager. This project included the construction of new drainage, wastewater, and water facilities.
Stephen was responsible for overall contractor administration, inspection, coordination, quality assurance, schedule, and budget management. He performed constructability reviews prior to bid. The existing force main that delivers wastewater from south of SR 120 to the Water Quality Control Facility will be replaced by completing a 4,405 LF extension of the existing 48-inch trunk. For this extension, 1,905 LF will be placed by means of microtunneling, including 315 LF of a 78-inch casing crossing SR120. The remaining 2,500 will be installed using open-cut methods.
South County Water Supply Program, South San Joaquin County Irrigation District, San Joaquin County, CA
Assistant Construction Manager. This project constructed 37 miles of 30- to 54-inch pipeline which will carry 150 MGD of treated water. This project consisted of five separate contracts with three different contractors performing work.
Stephen assisted with overall construction management and inspection of the project. The project included a 640-foot prefabricated steel pedestrian/bike bridge over the San Joaquin River; 730 feet of directional drill crossing of Paradise Cut; and 25 bore-and-jack crossings under railroads, pipes, culverts, roads, and channels. Permits were required for two crossings of Caltrans freeways, a 1,600-foot longitudinal encroachment along Caltrans right-of-way, 10 UPRR crossings, and a BNSF railroad crossing. The Project included environmental permit compliance and an extensive Mitigation Monitoring Reporting Program for the South San Joaquin Irrigation District.
Downtown Water Mains Replacement Hillcrest Neighborhood, City of Roseville, Roseville, CA Construction Manager. BC provided construction management and inspection services for this $7 million Design-Assist water main replacement project. The project replaced 20,000 feet of 8-inch and 12-inch water main in the 80-year-old Hillcrest neighborhood. It included the replacement of over 350 1-inch to 2-inch service lines and connections to existing meters. The project required close coordination with the contractor, City Operations and Construction staff, and the design engineer to locate existing utilities, analyze final alignments, and preplan for shutdowns and tie-ins.
Del Rio Tank No. 14, Well No. 68, and Pump Station, City of Modesto, Modesto, CA Construction Manager. The facility included a 250,000-gallon potable water storage tank, a 1 MGD pump station, and a 1,000 GPM domestic well. The 60-foot diameter steel tank will be constructed in accordance with AWWA D100 specifications. The pump station includes three 60 horsepower axially split centrifugal pumps and will be housed in a 40- by 51-foot concrete masonry building. Additional features include approximately 2,650-feet of 16” transmission main, an emergency generator, drainage basin, and site improvements.
Water Storage Improvement, City of Tulare, Tulare, CA
Construction Manager. This program constructed three new potable water storage and pumping facilities. Each site consists of a 1.5 to 2-million-gallon pre-stressed concrete tank, 1,000 to 1,200 GPM well, 6 MGD booster pumps, electrical building, emergency generator, associated electrical and instrumentation systems, and civil site improvements.
Industrial Tank No. 13 and Pump Station, City of Modesto, Modesto, CA Construction Manager. This project consisted of a 12 MGD water booster pumping station; a 4 million gallon prestressed concrete water storage reservoir; a building for the pump station, generator, and controls; a 1 million gallon retention basin; and site piping and improvements.
SR 99/219 (Kiernan Avenue) Interchange – Bridge and Pumping Plant Replacement, Stanislaus County, Salida, CA
Construction Manager. Stephen provided a constructability review and construction management services for this freeway widening, interchange improvement, bridge replacement, and storm water pumping plant replacement project.
The improvements will reconstruct the SR 99/SR 219 (Kiernan Avenue) interchange, add four additional travel lanes to SR 219 (Kiernan Avenue) within the project limits, and modify the existing interchange on- and off-ramps to and from SR 99.
153
Section 6, Item # 6.3
1 Dane Forsberg, P.E.
Electrical Inspector
Dane is an electrical engineer and ICC commercial
electrical inspector with experience designing electric power and control systems for water and wastewater
treatment plants, solar photovoltaic, and energy storage facilities.
The systems he has designed include motor control centers, variable frequency drives, transformers, switchgear, and inverters. Dane has designed instrumentation and control (I&C) systems including wired and wireless networking hardware, PLCs, field instruments, SCADA, and fiber-optic communication.
Pleasant Grove WWTP Expansion and Energy Recovery Projects, City of Roseville, Roseville, CA
Lead Electrical Inspector/Engineer. These are design-assist projects that include the construction of new primary clarifiers, solids thickening, anaerobic digesters and control building, digested sludge, centrate storage tank conversions, new biogas upgrading system, high strength waste (HSW) receiving station, HSW storage, energy recovery building, and compressed natural gas (CNG) fueling facility.
Dane provided all on site electrical inspections for both projects and coordinated all process shutdowns with the City and the Contractor.
Influent Pump Station Electrical Improvements, Central Contra Costa Sanitary District, Martinez, CA
Project Electrical Engineer. This design project included the replacement of the influent pump station’s motor control centers (MCCs), remote I/O panels, and variable frequency drives for three 400 HP and three 600 HP pumps. The new equipment was specified with network control using Modbus TCP protocol which allowed for a large portion of the hardwired I/O to be permanently demolished. The construction sequence for the project also had to be carefully planned to maintain continuous pumping capacity year-round.
Dane developed the drawing package which included the single line diagrams, MCC elevations, motor control schematics, power and control plans, communication diagrams, loop diagrams for the demolition, modification, and replacement of the electrical equipment. This included the diagrams for the vibration and temperature monitoring for the influent pumps. He also provided engineering services during the project’s construction including reviewing equipment submittals, responding to RFIs, and developing design clarification memos.
ASSIGNMENT
Electrical Inspector
EDUCATION
BS, Mechanical Engineering,
California Polytechnic State
University, San Luis Obispo,
2009
REGISTRATION
Engineer (Electrical), No.
E23627, CA
YEARS OF EXPERIENCE
16 JOINED FIRM
2019
CERTIFICATION/TRAINING
Commercial Electrical Inspector,
International Code Council (ICC),
No.9752135, 2020
SUBJECT MATTER SPECIALTIES
Electrical (General Electrical,
Electrical Dist. Systems Design -
LV)
RELEVANT EXPERIENCE
- Electrical Power and Control
Systems
- PV Power Generation
- Battery Storage
- Wired and Wireless Networks
Process Instrumentation
- Site Commissioning
- Operations & Maintenance
(O&M)
- Electrical Inspection
154
Section 6, Item # 6.3
Dane Forsberg // Continued
Brown and Caldwell 2
Palo Alto Regional Water Quality Control Plant: Secondary Treatment Upgrades, City of Palo Alto, Palo Alto, CA
Project Electrical Engineer. This project included a rehabilitation of the plant's secondary treatment process area which included the aeration tanks, air blower and distribution system, waste and return activated sludge systems, and primary effluent lift station. The electrical distribution system was also expanded by the addition of new low-voltage substation with low-voltage switchgear close-coupled to a medium-voltage transformer. Three new motor control centers were added in different areas of the plant to fed power to the new process equipment loads. The existing standby generator was also demolished and replaced with new tier 4 complaint diesel generator.
Dane developed the single line diagrams, control schematics, and electrical plans and conduit schedules for the new switchgear, and motor control centers which feed the new process pumps and equipment at the secondary treatment area. He is currently providing engineering services during the project’s construction including reviewing equipment submittals, responding to RFIs, and developing design clarification memos.
San Pablo Reservoir Hypolimnetic Oxygenation System Design, East Bay Municipal Utility District (EBMUD), San Pablo, CA
Project Electrical Engineer. This project included the design and construction of a new hypolimnetic oxygenation system to improve the taste and odor the water in the San Pablo Reservoir. A new liquid oxygen tank was installation at the top of the dam along with a pair of vaporizers. The vaporized oxygen was piped down to the bottom of the reservoir to a speece cone skid where a submersible pump circulates water through the cone where it is thoroughly mixed before being discharged back into the reservoir bottom. The remotely automated system was integrated into EBMUD’s Distributed Control System and monitored remotely by operators at the El Sobrante Water Treatment Plant.
Dane designed the electrical and instrumentation and controls and supported the construction of this project. This included developing single line diagrams, motor control schematics, power and control plans, conduit and cable schedules, communication block diagrams, security system diagrams, and loop and interconnection diagrams. He is currently providing engineering services during the project’s construction including reviewing equipment submittals, responding to RFIs, and developing design clarification memos.
Wastewater Treatment Plant Bioenergy Generation Project, Fairfield-Suisun Sewer District, Fairfield, CA
Project Electrical Engineer. This project included the design of a new 1.1 MW cogeneration engine and the replacement of the existing biogas upgrade system at the plant. The low voltage switchgear, motor control center (LV), and PLC panel in the cogeneration building will be demolished and replaced. An existing 900 kW cogeneration engine and four 66 kW wind turbines also had to be integrated into the electrical design.
Dane developed the electrical and instrumentation and controls design for this cogeneration project which included single line diagrams, motor control center and switchgear elevations, motor control schematics, power and control plans, lighting and grounding plans, conduit and cable schedules, panelboard schedules, network diagrams, and piping and instrumentation diagrams (P&IDs). He is currently providing engineering services during the project’s construction including reviewing equipment submittals, responding to RFIs, and developing design clarification memos.
Influent Pump 5, Regional San, Sacramento, CA
Instrumentation & Controls Engineer. This project includes the design to install a new 1250 HP vertical driven influent pump at the wastewater facility. The pump will be VFD driven and will include a machine health monitoring system for monitoring the pump and motor vibration and temperature.
Dane is leading the instrumentation & controls portion of the project. This includes the development of the pump control panel elevations and wiring schematics, piping & instrumentation diagrams, and communication block diagrams. This also includes the development of specifications for the machine health monitoring and control panel equipment.
Sumps 157 and 160 Alternatives Analysis, City of Sacramento, Sacramento, CA Project Electrical Engineer. The analysis includes weighing the resiliency, costs, sustainability, O&M, and footprint of the several proposed designs. The City will use the summary report as guidance for the future design development at these critical storm water pump stations.
Dane is part of the team evaluating several options to upgrade the existing sumps 157 and 160 located in Sacramento. 155
Section 6, Item # 6.3
1 Gavin Lee, PE
Construction Inspector (Pipeline)
Gavin is an experienced engineer with leadership and
hands-on experience managing complex construction
projects.
Throughout Gavin’s career, he has provided high level management and on-site inspection services to a variety of construction projects. He has worked with many contractors and subcontractors and has had proven success managing their compliance with contracts, construction plans and specifications, material testing, SWPPP, state and county regulations, and permits. He has extensive experience with utility installation inside and outside of high traffic roadways where traffic control and pedestrian foot traffic needs to be managed and monitored. He has strong project documentation skills and can review and processed submittals, RFI’s, progress payments, and change orders.
Pure Water Soquel Conveyance and Water Treatment Project, Soquel Creek Water District, Santa Cruz, CA
Construction Management/Inspection Services. This $122 million design-build project consists of installing eight miles of 16" and 14" PVC pipeline under various streets between Santa Cruz and Aptos. The conveyance pipeline ($30 million) carries treated water from the existing Santa Cruz Wastewater Treatment Facility to the new (under construction) Chanticleer Water Purification Center ($92 million). The purified water from the Water Purification Center will be conveyed to three Seawater Intrusion Prevention Wells, where it will recharge the ground water basin.
Gavin was responsible for daily inspections of pipeline and appurtenance installation, verifying conformance with project documents and manufactures installation requirements, as well as provide daily documentation and monitor traffic control in the public right of way. He also served as Assistant CM assisting in document controls, progress payments and change orders.
WWTF Thickener No. 2 Rehabilitation Project, City of Santa Cruz, Santa Cruz, CA
Inspection Services. This $1.6 million dollar rehabilitation project that involved the replacement and modification of existing facilities within the gravity sludge thickening process. This project involved removing and replacing the thickeners interior mechanical devices, refurbishing and coating the existing concrete, replacement of existing pumps and piping, and the installation of upgraded electrical equipment, controls, and programing.
Gavin provided inspection services throughout construction and oversaw all construction activities. He performed civil, mechanical, and electrical field inspections, and prepared inspection reports.
ASSIGNMENT
Construction Inspector
EDUCATION
BS, Mechanical Engineering,
University of Maine, 2015
YEARS OF EXPERIENCE
13 JOINED FIRM
2022
CERTIFICATION/TRAINING
PMP, Project Management
Institute, No.3705520, 2023
FE Mechanical Exam, New
Hampshire P.E. Board, 2018
HAZWOPER 40-Hour
Certification, OSHA, 2022
Work Zone, Confined Space, and
Construction Site Safety and
Safety Policies and Procedures
Safety Trainings, Wright-Pierce,
2020
Local Public Agency (LPA)
Certification for Labor
Compliance, 2017
Occupational Safety and Health
Administration (OSHA) 10-Hour
Construction Training, Red
Vector, 2017
RELEVANT EXPERIENCE
- Engineering Services
- Construction Management
- Mechanical/Civil Inspection
- Concrete Form and Placement
Management
- Survey Control
- Constructability Reviews
- Transportation, Water, and
Wastewater Construction
- Paving and Civil
Improvements
- Supervision of Inspectors
156
Section 6, Item # 6.3
Gavin Lee // Continued
Brown and Caldwell 2
Sheila Tank Replacement and PRV Improvements Project, North Coast County Water District, Pacifica, CA
Construction Management/Inspection Services. BC provided design and construction management services for this $5.9 million dollar project. This project includes the installation of a 600,000-gallon prestressed concrete tank, tank utility connections, on site pipelines, valve vaults, concrete block retaining walls, and the installation of accompanying electrical work. In addition to tank construction and site work, two pressure reducing valve stations will be installed on pipelines outside of the tank project site.
Gavin provides full-service construction management and inspection services throughout construction and is responsible for overseeing all construction activities. He is responsible for running weekly progress meetings, processing submittals and RFIs, reviewing progress payments, writing inspection reports, and change management.
Gavin successfully facilitates communication between all parties and keeps the project on task.
Westlake Pump Station GSR Modifications, City of Daly City, Daly City, CA Construction Management/Inspection Services. BC provided design and construction management services for this $3.6 million GSR upgrade project that involved interior and exterior upgrades to the facility. Upgrades included the installation of new exterior cast in place valve vaults, yard piping, paving, and concrete placement. Interior upgrades included the installation of new chemical containment rooms, chemical injection systems, a reverse osmosis system, interior electrical, and control systems.
Gavin provided full-service construction management and inspection services throughout construction and oversaw all construction activities. He performed civil, mechanical, and electrical field inspections, and prepared inspection reports.
Gavin was responsible for running weekly progress meetings, processing submittals and RFIs, reviewed progress payments, and change management.
Lebanon Sewer Separation Contract 12, City of Lebanon, Lebanon, NH Resident Project Representative. The $4.3 million combined sewer overflow (CSO) project involved water main, sewer main, and storm drain replacement and full-depth road, sidewalk, curbing, and retaining wall construction along seven city streets in a densely populated residential neighborhood, including a cross-country section.
Gavin’s daily responsibilities included installation observation for sewer, water and storm drain piping, manholes, cleanouts, curb stops, sidewalk, curbing, road base gravels, paving, striping, and surface restoration. Related responsibilities included monitoring hydrostatic pressure, leakage testing, and chlorination of water main systems; coordinating water main sampling, laboratory paperwork, and testing; final sewer testing; attending weekly and monthly project meetings; and performing Davis-Bacon wage rate interviews.
Lebanon Sewer Separation Contract 11: Phase I, City of Lebanon, Lebanon, NH Resident Project Representative. The $1.6 million combined sewer overflow (CSO) project involved water main, sewer main, and storm drain replacement and full-depth road, sidewalk, curbing, and retaining wall construction along multiple city streets in a densely populated residential neighborhood.
Gavin’s daily responsibilities included installation observation for sewer, water and storm drain piping, manholes, cleanouts, curb stops, sidewalk, curbing, paving, striping, signs, and surface restoration. Related responsibilities included attendance at project meetings; monitoring hydrostatic pressure, leakage testing, and chlorination of water main systems; coordinating with DPW in water main sampling, laboratory paperwork, and testing; final sewer testing; reviewing pay requisitions; performing Davis-Bacon wage rate interviews; completing final measurement; and developing and monitoring a punch list until final completion.
Lebanon Sewer Separation Contract 11: Phase II, City of Lebanon, Lebanon, NH Resident Project Representative. The $18.4 million combined sewer overflow (CSO) project involved water main, sewer main and storm drain replacement and full-depth road, sidewalk, curbing, and retaining wall construction along 15 city streets in a densely populated residential neighborhood.
Gavin’s daily responsibilities included installation observation for sewer, water and storm drain piping, manholes, cleanouts, curb stops, sidewalk, curbing, road base gravels, paving, striping, and surface restoration. Related responsibilities include monitoring hydrostatic pressure, leakage testing, and chlorination of water main systems; coordinating with DPW in water main sampling, laboratory paperwork, and testing; final sewer testing, attending weekly and monthly project meetings; and performing Davis-Bacon wage rate interviews. 157
Section 6, Item # 6.3
1 Tony Knapp, P.E.
Construction Inspector (Pump Stations)
Tony is a construction inspector with experience in the construction and design of water and wastewater
facilities.
He has extensive field and inspection experience at various water and wastewater facilities in California and Texas.
Pure Water Soquel, Soquel Creek Water District, Santa Cruz, CA Construction Inspector. This is a $122 million groundwater replenishment and seawater intrusion prevention project. The project included a new advanced treatment facility and approximately 9 miles of 14” to 18” PVC conveyance pipe. The treatment plant work includes new microfiltration, reverse osmosis and ultraviolet (UV) light facilities.
Tony performed underground pipeline inspection services for this construction project.
The work was located on highly congested roadways and at the treatment plant. He worked closely with the client and contractor to assure that the pipeline installation complied with the project specifications and the manufacturer’s installation requirements. (2023-2024)
Pleasant Grove WWTP Energy Recovery Project, City of Roseville, Roseville, CA
Construction Manager/Lead Inspector. This $24 million project involved the construction of a high strength waste receiving station, an energy recovery building with microturbines, a biogas conditioning system and a compressed natural gas fueling facility. The project included the installation of water, sewer, natural gas and chemical piping above and below ground.
Tony was the CM and lead inspector for this energy recovery construction project. He provided daily on-site inspection for the concrete, civil, electrical and mechanical work. He was responsable for reviewing and approving the Contractor schedule, pay requests and change orders. Tony worked closely with the City staff to ensure that equipment met their operation and maintenance concerns. (2019-2023)
Pleasant Grove WWTP Expansion Project, City of Roseville, Roseville, CA Construction Manager/Inspector. The Project involved the construction of primary clarifiers, solids thickening, anerobic digester tanks, a ferric chloride facility and sludge storage tanks.
Tony provided CM and inspection services for this $59 million wastewater treatment plant expansion. He performed concrete, mechanical and electrical inspections for this project. He worked with the engineer of record and city staff to resolve construction issues in the field.
ASSIGNMENT
Construction Inspector
EDUCATION
MS, Civil Engineering, University
of California at Davis, 2007
BS, Civil Engineering, University
of California at Davis, 1998
REGISTRATION
Engineer (Civil), No. 68525, CA
YEARS OF EXPERIENCE
22 JOINED FIRM
2018
CERTIFICATION/TRAINING
OSHA 30-Hour Construction
Safety, OSHA, No.34-
602078316, 2019
RELEVANT EXPERIENCE
- Inspection and Construction
Administration for Water and
Wastewater
- Inspection of Mechanical,
Civil, and Electrical
Construction Work
158
Section 6, Item # 6.3
Tony Knapp // Continued
Brown and Caldwell 2
Dry Creek Cogeneration, City of Roseville, Roseville, CA Construction Inspector. BC is designing a cogeneration facility for the City of Roseville's Dry Creek WWTP. BC helped secure more than $600,000 from the California Self-Generation Incentive Program for the City’s design. The new cogeneration facility will include one high-efficiency, lean burn internal combustion engine with associated heat recovery equipment, a biogas conditioning system to remove hydrogen sulfide, siloxane and moisture, and a pipe rack to support biogas and hot water pipes above ground due to congested site yard piping. The engine will be fueled by treated digester gas from the digestion wastewater treatment process. BC is providing design, air permitting, and construction management services, as well as monitoring grant requirements.
As the Construction Inspector, Tony monitors the daily construction activities to ensure quality workmanship and overall compliance with the contract documents. He works with the contractor, the City staff and BC engineers to resolve issues arising in the field. He communicates often with City staff and the Contractor to assure that the work proceeds as expected.
Flocculation/Sedimentation Basin Project, San Juan Water District, Granite Bay, CA Project Engineer. This $7 million contract involved replacing the flocculation and sludge collector system at a 120 million gallon per day water plant.
Tony’s tasks included laying out the concrete structures, overseeing installation of mechanical equipment and preparing shop drawing submittals.
Aeration System Replacement, Terminal Island Water Reclamation Plant, City of Los Angeles, CA Project Engineer. This $12 million contract entailed demolition and replacement of the blowers and diffuser assembly for the City’s activated sludge basins.
Tony’s major responsibilities included preparing shop drawing submittals, coordinating equipment fabrication, and collaborating with the electrical and controls subcontractors.
Deep Filter Modification Project, Village Creek Water Reclamation Plant, Fort Worth, TX Project Engineer. An Emerson Ovation control system was installed and programmed for this one million dollar subcontract.
Tony oversaw the installation of a distributed control system for the filter gallery at this 160 million gallon per day treatment plant.
Ultraviolet Pilot Project, Trinity River Authority, Dallas, TX Project Engineer. The project diverted 28 million gallons per day of secondary wastewater at the treatment plant to six treatment systems. He also managed nine separate subcontractors for this project.
Tony oversaw the construction and startup of a pilot ultraviolet treatment project. (2013) Integrated Pipeline Project, Tarrant Regional Water District, Fort Worth, TX Project Engineer. The yard pipe design included the layout of welded steel pipe, gate valves and butterfly valves ranging in size from 84 to 114 inches diameter. Tony’s major responsibilities included the design of the yard piping and valve vaults for this 350 million gallon per day pump station.
Southern Regional Tertiary Treatment Plant, Marine Corps Base Camp Pendleton, San Diego County, CA
Project Engineer. Tony designed and sized the pumps for the influent, filter feed and drainage pump stations.
Wastewater Treatment Plant Repairs and Upgrade, Navy Facilities Engineering Command, Apra Harbor, Guam
Project Engineer. Tony designed and sized a dissolved air flotation thickener and polymer feed system for this wastewater plant.
159
Section 6, Item # 6.3
1 Casey Kirk, CCM, ICC
Construction Inspector (Trenchless)
Casey has construction management and inspection
experience on environmental projects, specializing in
constructing water and wastewater treatment facilities, pumping facilities, storage facilities, conveyance systems, and startup & testing.
Casey specializes in work throughout California, Arizona and Hawaii. His background allows him to excel in a variety of positions on projects. His experience as an inspector strengthens his skills as a Construction Manager and vice versa. Casey has overseen challenging trenchless pipeline installations under railroad crossings, bodies of water and through busy intersections. His understanding of the various trenchless methods helps ensure successful set-ups and traffic control plans, helps minimize risks and issues during drilling, and helps ensure alignment and grade compliance of the final pipeline.
Water Distribution System Improvements, City of Roseville, City of Roseville, California
Construction Manager. Construction management and inspection services for three distribution system improvements. (1) Jack and bore under Cirby Creek. (2) Pipe suspended on Douglas Blvd bridge across Dry Creek. (3) Open cut in the Hillcrest neighborhood. Improvements will allow City to abandon 3 shallow pipes that cross HWY 80.
Casey was Construction Manager and lead inspector, conducted project meetings, field coordination, correspondence, change orders, submittal & RFI review, startup & testing and daily on-site inspection.
Arden Parallel Force Main, County of Sacramento, Sacramento, CA Inspector. Project included installation of new secondary 60-inch diameter pressure force main parallel to the existing 60-inch diameter pressure force main. Installation of 10,400 linear feet of 60 inch diameter pipe, two air release/vacuum valve vaults, two air release man ways, surge control facility with 4 – 60 foot surge tanks and control building, five hottaps on 60 inch diameter force main and 36 inch bypass piping at one location, an 48 inch bypass, four access manways, two open cut crossings of the U.S. Army Corps of Engineer’s American River Levee, two 72 inch micro tunnel crossings of the American River, and three excavated tunneling service shafts.
Fruitridge Center Sewage Pumping Station, Power Inn Sewage PS, and Fruitridge Road Pipeline, Sacramento Regional County Sanitation District (Regional San), Sacramento, CA
Inspector. Project involves over 32,000 linear feet of gravity and interceptor sewer pipeline ranging in size from 8 inches to 54 inches in diameter, 186 manholes, 22,000 linear feet of force mains ranging in size from 24 to 30 inches in diameter, four railroad crossings, catholic protection system, water line relocations, and service connections.
ASSIGNMENT
Construction Inspector
YEARS OF EXPERIENCE
30 JOINED FIRM
2021
CERTIFICATION/TRAINING
Certified Construction Manager,
Construction Management
Association of America,
No.29337, 2022
Confined Space Training, 2022
First Aid Training, 2024
CPR Training, 2024
NACE CIP Level 1 - Basic
Coatings Inspector, AMPP -The
Association for Materials
Protection and Performance,
No.14222, 2007
ICC Master of Special
Inspection, International Code
Council, No.5111146, 2022
ICC Structural Welding Special
Inpector, International Code
Council, No.5111146, 2002
ICC Structural Steel and Bolting
Special Inspector, International
Code Council, No.5111146,
2002
ICC Structural Masonry Special
Inspector, International Code
Council, No.5111146, 2013
ICC Reinforced Concrete Special
Inspector, International Code
Council, No.5111146, 2013
ACI Concrete Field Testing
Technician - Grade 1, ACI -
American Concrete Institute,
No.20514, 1999
30-Hour OSHA, 2023
RELEVANT EXPERIENCE
- Construction Management
- Inspection
- Water and Wastewater
Treatment Facilities
- Pump Stations
- Storm Drains
- Potable Water Storage
Facilities
- Water Storage Tanks
160
Section 6, Item # 6.3
Casey Kirk // Continued
Brown and Caldwell 2
Casey was inspector for two separate construction projects, which includes two new sewage pumping stations and gravity and force main sewer pipelines.
Suburban Rose Pipeline, California American Water, Sacramento, CA Lead Inspector. This project consisted of the installation of a water pipeline ranging from 8 inch to 24 inch. The pipeline was excavated by open trench and three tunnel crossings of a freight railroad track, as well as two light rail tracks with casing sizes 36 inches to 42 inches.
Export Pipeline Segment 1 and Mill Creek Diversion Construction Dam Services, Incline Village General Improvement District, Incline Village, NV
Construction Services. Project included replacement of 3 - mile segment of wastewater effluent pipeline Segment 1 while existing pipeline remained in service. Also, installation of Mill Creek Diversion Dam and pipeline to divert creek around emergence storage bason at treatment wastewater plant.
Pleasant Grove WWTP Expansion and Energy Recovery Projects, City of Roseville, Roseville, CA Construction Manager/Lead Inspector (Expansion Project)/Inspector (Energy Recovery Project). These are designassist projects that include the construction of new primary clarifiers, solids thickening, an anaerobic digesters and control building, digested sludge, centrate storage tank conversions, a new biogas upgrading system, a high strength waste (HSW) receiving station, HSW storage, an energy recovery building, and a compressed natural gas (CNG) fueling facility.
Casey was Construction Manager and lead inspector, conducted project meetings, field coordination, correspondence, change orders, submittal & RFI review, startup & testing and daily on-site inspection.
Wastewater Treatment Plant Expansion, City of Davis, Davis, CA Lead Inspector/Assistant Construction Manager. Owners Representative/Quality Assurance for Design Build project building new secondary and tertiary treatment facilities at their existing primary treatment plant, while maintaining functionality of existing plant operations. New or modified facilities included aeration basins, secondary clarifiers, disk filters, chlorine contact basin, rotating drum thickeners, screw presses, new 12kv service, SCADA upgrade, standby generators, several pump stations, existing digester upgrades, new multi fuel boilers, levee around new treatment plant, existing pond modifications and pond sludge drying, removal and off haul.
Wastewater Treatment Plant Expansion, City of Hughson, Hughson, CA Lead Inspector. The project consisted of a new wastewater treatment plant within the site of the existing operating treatment plant, while maintaining functionality. The new treatment facility employs a headworks facility, including screening, an oxidation ditch, two secondary clarifiers, solids thickening gravity belt thickener, operations building improvements, new electrical service, and SCADA improvements. The work also includes demolition of various existing facilities. Proper construction sequencing is required to allow new facilities to be phased into operation so existing facilities can be taken out of service.
Water Treatment Plant Expansion, Modesto Irrigation District, Modesto, CA Lead Inspector/Assistant Construction Manager. The project consisted of a new water treatment plant on the site of the existing operating treatment plant, while maintaining functionality. The new treatment facility employs membrane filtration building, ozone generation with ozone contactor basin, and DAF waste recovery system. The work also includes demolition of various new constructed facilities and rebuild. Proper construction sequencing is required to allow new facilities to be phased into operation to work with existing facilities.
Wastewater Treatment Plant, Novato Sanitary District, Novato, CA Lead Inspector. Project consists of expansion of existing wastewater treatment plant while maintaining functionality of existing plant operations. The new treatment facility employs a conventional activated sludge process. The headworks facilities include screening and grit removal, primary clarification, aeration, and secondary clarifiers. The work also includes demolition of various existing facilities. Proper construction sequencing is required to allow new facilities to be phased into operation so existing facilities can be taken out of service and demolished to make room for other new processes.
161
Section 6, Item # 6.3
1 Rick Sasser
Construction Inspector (Pump Stations)
Rick’s construction background enhances his abilities as a construction inspector.
Rick has significant experience providing construction and inspection services. He specializes in inspecting water and wastewater treatment facilities, storm water and potable water pump stations, water storage tanks, water control structures, prefabricated metal buildings, commercial remodels, and new construction. Rick's expertise includes supervising projects, including organizing and managing project materials and manpower, being well versed on overall project plans and specifications, maintaining a safe working environment on job sites, and coordinating and overseeing concrete form construction, concrete placement, and various types and sizes of pipe and equipment installation.
Wastewater Treatment Plant Expansion and Energy Recovery Projects, City of Roseville, Roseville, CA
Construction Inspector. Both projects (totaling $80 million) are being run under the design-assist delivery method and include construction of new primary clarifiers, solids thickening, anaerobic digesters, a control building, digested sludge, centrate storage tank conversions, new biogas upgrading system, HSW receiving station, HSW storage, energy recovery building, and CNG fueling facility.
Rick provided inspection services. He took the lead on the underground construction and yard piping that includes large-diameter HDPE piping.
Coke and Triangle Sewer Lift Station Rehabilitation Project, City of West Sacramento, West Sacramento, CA
Construction Inspector. This project consisted of furnishing and installing new manholes, fiber reinforced plastic wet wells, valve vaults, submersible pumps, bypass piping and pumping, level transducers, control systems, lighting, and backup diesel generators.
Work also included demolishing existing infrastructure; reconstructing curb, gutter, and sidewalk; installing equipment for temporary bypassing during construction; and placing new security fencing and gates at both lift stations. BC provided CM and inspection services for the City, including taking over the utility coordination with PG&E and AT&T when their utilities were discovered during construction.
Rick provided construction inspection and oversaw the start-up and commissioning of both facilities.
Downtown Water Mains Replacement - Hillcrest Neighborhood, City of Roseville, Roseville, CA
Construction Inspector. This $7M design-assist water main replacement project replaced 20,000 feet of eight- and 12-inch water main in the 80-year-old Hillcrest neighborhood.
It included replacing more than 350, one- to two-inch service lines and connections to existing meters.
ASSIGNMENT
Construction Inspector
YEARS OF EXPERIENCE
36 JOINED FIRM
2021
CERTIFICATION/TRAINING
30 Hour, OSHA
First Aid & CPR
Concrete Field -Testing
Technician Grade 1, American
Concrete Institute
Confined Space Competent
Person Fall Protection Safety
First Aid & CPR
All Terrain Fork Lift
Fall Protection Safety
Training, Mine Safety and Health
Administration (MSHA)
RELEVANT EXPERIENCE
- Construction Management
- Construction Inspection
- Water and Wastewater
Treatment Facilities
- Stormwater and Potable
Water Pump Stations
- Water Storage Tanks
- Water Control Structures
- Prefabricated Metal Buildings
- Commercial Remodeling
- New Construction
- Safety
- Concrete Form Construction
- Pipe Instillation
162
Section 6, Item # 6.3
Rick Sasser // Continued
Brown and Caldwell 2
Rick provided inspection services. Rick took the lead in the day-to-day public outreach to minimize impacts to residents, businesses, and schools. He also coordinated closely with City operations staff, the contractor’s staff, design staff, and utility representatives to locate existing utilities.
Pure Water Soquel Conveyance and Water Treatment Project, Soquel Creek Water District, Santa Cruz, CA
Construction Inspector. This $122 million design build project consists of installing eight miles of 16" and 14" PVC pipeline under various streets between Santa Cruz and Aptos. The conveyance pipeline ($30 million) carries treated water from the existing Santa Cruz Wastewater Treatment Facility to the new (under construction) Chanticleer Water Purification Center ($92 million). The purified water from the Water Purification Center will be conveyed to three Seawater Intrusion Prevention Wells, where it will recharge the ground water basin.
Rick was responsible for daily inspections of pipeline and appurtenance installation, verifying conformance with project documents and manufactures installation requirements, as well as provide daily documentation and monitor traffic control in the public right of way. Inspect and document treatment facility construction activities including pressure testing of various piping systems.
Water Treatment Plant Polymer Improvement Project, City of Folson, Folsom, CA Construction Inspector. This $550,000 project installed new dry polymer feed equipment, polymer mixing and aging tanks, and associated piping, as well as structural, electrical, and control modifications.
Rick was responsible for conducting daily inspections for general conformance with contract documents, documenting the work, collaborating with plant staff to maintain operations, coordinating quality assurance testing, and assisting with start-up and testing.
Del Rio Tank No. 14, Well No. 68 and Pump Station, City of Modesto, Modesto, CA Construction Inspector. This $9 million project consisting of a 250,000-gallon potable water storage tank, a 1-mgd pump station, a 1,000 gpm domestic well, and a wellhead treatment facility. The project also included 2,600 feet of 16- inch water line to connect the new facility to the existing distribution system. Close coordination was required with the Department of Utilities – Engineering and Water Operation departments.
Rick was responsible for conducting daily inspections for general conformance with contract documents, providing documentation of the work, coordinating quality assurance testing, and assisting with start-up and testing.
Water Storage Improvement Project, Tulare County, Tulare, CA Construction Inspector. This $16 million program constructed three new potable water storage pumping facilities. Each site consists of a 1.5- to 2-million-gallon post tension concrete tank, a 1,000 to 2,000 gpm well, six-mgd booster pumps, an electrical building, emergency generator, associated electrical instrumentation systems, and civil site improvements.
Rick was responsible for daily inspections for general conformance with contract documents, providing documentation of work, collaborating with operations staff, coordinating quality assurance testing, and assisting with start-up and testing.
Industrial Tank No. 13 and Pump Station, City of Modesto, Modesto, CA Construction Inspector. This $9.2 million project consisted of a four-million-gallon potable water storage tank and a 12 million gpd booster pumping station. The potable water storage tank was constructed at grade of strand-wound prestressed concrete in accordance with AWWA D110, Type 1 specifications. The pump station included four 150- horsepower horizontal split-case pumps. The pumps, piping, and electrical equipment were housed in a 40- by 82-foot concrete masonry building. Additional features included an emergency generator, drainage basin, and site improvements.
Rick was responsible for conducting daily inspections for general conformance with contract documents, documenting the work, collaborating with operations staff, coordinating quality assurance testing, and assisting with start-up and testing.
163
Section 6, Item # 6.3
QSD/QSP Services
(Qualified Storm Water Pollution Prevention Plan Developer and Practitioner Services) Resume of
Hank J. Heath
Education
California State University, Sacramento, Sacramento, CA Water Treatment Plant Operation, Volume 1 Certificate, 2013 Certifications
Qualified SWPPP Developer/Practitioner #28463
Certified Erosion and Sediment Storm Water Inspector #9975 Proficiencies
Microsoft Word, Excel, Power Point, Database systems, Adobe Acrobat Employment History
Senior Inspector, American River Environmental, June – Present Perform site inspections including sampling, visual observation, and report preparation for LUP and Traditional projects, including weekly, quarterly, and storm related inspections as required by the Construction General Permit.
Work with contractors to determine the most practical and effective BMPs to use and maintain. Collect photo documentation for COIs and NOTs.
Inspection Scheduling
Staff Inspector, BTConsulting, Inc., October 2017 – June 2025 Perform site inspections including sampling, visual observation, and report preparation for LUP and Traditional projects, including weekly, quarterly, and storm related inspections as required by the Construction General Permit.
Work with contractors to determine the most practical and effective BMPs to use and maintain. Collect photo documentation for COIs and NOTs.
Assemble spill kits and inventory spill kit supplies.
Bartender, Vanguard July 2014 – October 2017
Consistently create and meet goals related to sales and time efficiency. Solve problems and create an environment that results in customer satisfaction. Regularly arrive to work early and eager to assist management.
Bartender/Supervisor, River City Brewing Company December 2013 – March 2015 Assist in general maintenance of equipment; including small and large machinery. Consistently maintain standards while assisting coworkers in a functioning team effort. Prepare and finalize finances as well as prepare staff regarding their daily duties. Create and maintain excellent relationships with clientele thus making a comfortable atmosphere.
164
Section 6, Item # 6.3
QSD/QSP Services
(Qualified Storm Water Pollution Prevention Plan Developer and Practitioner Services) Resume of
John R. Brenner
Education
American Public University, Internet Based
Bachelors of Science, Environmental Management, 2012 to Current Folsom Lake College, Folsom, CA
Associate of Arts, General Education, 2007
Sacramento City College, Sacramento, CA
Elementary Surveying, May 2008
Ponderosa High School, Shingle Springs, CA
Diploma, May 2001
Certifications
Qualified SWPPP Developer/Practitioner #25335
Certified Professional in Erosion and Sediment Control #8056 Certified Erosion and Sediment Storm Water Inspector #3051 Trainer of Record (ToR) authorized by CASQA for QSD and QSP Training Proficiencies
Adobe Acrobat, AutoCAD, Carlson Civil Suite, Excel, Word, Power Point, SMARTS, and SWIM Employment History
President, American River Environmental, January 2025 – Present Conduct day-to-day business activities including client and agency coordination, scheduling, accounting, human relations, and general company operations. Train, schedule, and manage employees.
Manage Sacramento and foothill area projects for SWPPP development and inspections.
Manager of Field/Inspection Personnel, BTConsulting, Inc., August 2010 – June 2025 Coordinate day-to-day business activities including client and agency coordination, scheduling, information technology, and general company operations. Employee coordination, management, and training.
Schedule and manage field crews, including Bay Area, Sacramento, and foothill areas. Prepare SWPPPs, WPCPs, Erosion and Sediment Control Drawings, and other related documents.
Develop and maintain CAD standards.
Present tailgate training and represent BTC at project pre-construction meetings. Manage SMARTS uploads and QA/QC for documents ready to be uploaded to the State.
Correctional Officer, State of Nevada, November 2010 – January 2012 Monitor correctional facilities and ensure order and security through strict monitoring of inmate activities.
Search prisons and other facilities for banned material, fire and safety hazards, and unsanitary conditions.
Record daily activities, disturbances, and illegal activities. 165
Section 6, Item # 6.3
Prepared for
City of Wheatland
7040 Settlers Trail
Shingle Springs, CA 95682
(530) 683-4038
www.icmgroupusa.com
MONTHLY REPORT EXAMPLE
May 20, 2026
ICM
166
Section 6, Item # 6.3
PROJECT STATUS REPORT
FOR THE MONTH OF
JANUARY 2026
EL DORADO IRRIGATION DISTRICT
SLY PARK INTERTIE IMPROVEMENTS PROJECT
February
ICM
26, 2026
Landing Power Cables to Pump Motors Installing Pipe Supports inside Pump Station Installing 24” Butterfly Valve at Station 335+98 Cathodic Protection Wrap of Valves at Canchulagua 167
Section 6, Item # 6.3
2 ICM
CONTRACTOR PROGRESS SUMMARY
I. Mozingo Construction Activities Completed
In the month of January, Mozingo performed the following activities:
• Completed installation of the pump station roof
• Continued installing electrical wires in and around the pump station • Installed PG&E transformer at pump Station
• Installed control panel in pump station
• Completed most of site grading, preparing to place concrete slabs around pump station. • Installed Trench Dams North of Canchalagua
• Excavated from Station 321+68 to 336+20
• Installed Pipes 389 to 430
• SWPPP and BMPs maintained
• Transmitted 3 submittals; of which 1 was a re-submittal. • Submitted 6 RFIs.
II. Project Budget
The Project Budget Summary Table is presented below. Actual Payments to the Contractor and Retention to Date are based on pay estimates prepared by Mozingo. Mozingo has had nine progress payments as of the end of January 2026.
Project Budget Summary Table
Original Budget $45,680,000.00
Executed Change Orders $1,700,224.22
Current Budget $47,309,221.97
Pending Change Orders $22,222.38
Potential Change Orders $355,447
Budget Projection $47,757,893.60
Actual Contractor Payments to Date $34,027,481.66
Retention to Date $1,701,374.08
Change Order Details Table
Executed Change Orders $1,700,224.22
CO1 CPR01 Pine Tree Lane Road Base $43,812.40
CO2 CPR05 Added Potholes $22,783.20
CO3 CPR04 Fac 20 Tree Removal $786,033.30
CO4 CPR11 Breaker and Conduit Changes $10,659.60
CO5 CPR14 Concrete Demo for RWMH1 $19,822.95
CO6 CPR10 Reservoir A Electrical Room Waterproofing $17,108.70 CO7 CPR12 Northwest Pipeline Reset Reach 2 $20,569.20
CO8 CPR30 UFCA $10,827.24
CO9 CPR16 Ice House Piping Replacement $127,039.86
168
Section 6, Item # 6.3
3 ICM
CO10 CPR15 Deletion of UPS ($8,038.80)
CO11 CPR19 NWP Redesign $37,800.00
CO12 CPR23 Fuel Tank Power Cables $16,980.60
CO13 CPR26 VFD Harmonic Filters $16,002.00
CO14 CPR18 Ice House Concrete Plug Removal $51,356.55
CO15 CPR22 CC POM Bypass Valves $81,679.50
CO16 CPR21 Fire Hydrant 8in Gate Valve $5,347.97
CO17 CPR29 Admin Bldg Water Service $7,205.33
CO18 CPR38 NWP Expedite Fab Delivery $99,900.00
CO19 CPR28 14in SPH Butterfly Valve $7,814.48
CO20 CPR36 Ice House Pipe Coating $42,933.45
CO21 CPR31 POM RCP to Steel Pipe Transition $72,349.20
CO22 CPR2 Clear Creek Flow Meter Valve Control $94,781.40 CO23 CPR27 Flowmeter Tariff $3,977.78
CO24 CPR24 VFD Wire Changes $8,642.55
CO25 CPR30 Flow Meter Vault Floor Elevation Change $35,811.30 CO26 CPR06 Fiber Optic Terminations $21,855.23
CO27 CPR46 Clear Creek Restoration $29,796.18
CO28 CPR37 Extended Slab for ATS $5,214.30
CO29 CPR47 DI Extension $10,158.75
CPR40 10 to 15 OIT Programming $0
CPR34 Integration Hours Part 1 $0
Pending Change Orders $22,222.38
CPR13 Ridgeway Pothole $9,517.79
CPR25 VFD Digital Inputs $3,850.94
CPR35 Weldolet and Valve $1,152.90
CPR51 PIT 40 02 $4,153.56
CPR53 Dewatering $3,547.19
Potential Change Orders Estimated at $355,447
CPR08 Fac 40 Tree Removal $0
CPR17 County Trench Details $25,000
CPR32 Slalom Gate $7,500
CPR33 Chlorine Retention Pipeline $75,000
CPR39 2inch to Drying Beds $35,000
CPR41 Dry Creek Pipe Concrete $10.000
CPR42 Vault Demo $10,000
CPR43 Boulders $2,500
CPR44 Integration Hours Refresh Line $0
CPR48 POM Installl $20,000
CPR49 Eyewash Station $40,000
CPR50 Fiber Extension $90,000
CPR52 Rock Area Extension $7,500
CPR54 Conduit Types $8,447
CPR55 Bollards $5,000
CPR56 Gates $12,000
Extra Concrete at Starkes Grade/Creek $7,500
Paving Changes Starkes Grade $0
169
Section 6, Item # 6.3
4 ICM
The Payment Projections and Budget Expenditure Diagrams are below. Projected values are estimates based on the contractor’s Schedule of Values and Cost Loaded Baseline Schedule.
Actual Payments are based on approved monthly progress payments.
Payment Projections. This chart provides a visual representation of monthly cash flow from the El Dorado Irrigation District to Mozingo.
Budget Expenditure Graph. This chart provides a visual representation of cumulative monthly cash flow from the El Dorado Irrigation District to Mozingo. $-
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
Jul-24
Sep-24
Nov-24
Jan-25
Mar-25
May-25
Jul-25
Sep-25
Nov-25
Jan-26
Mar-26
May-26
Jul-26
Sep-26
Nov-26
Jan-27
Payment Projections
Projected Payments Actual Payments
$-
$5,000,000
$10,000,000
$15,000,000
$20,000,000
$25,000,000
$30,000,000
$35,000,000
$40,000,000
$45,000,000
$50,000,000
Jul-24
Sep-24
Nov-24
Jan-25
Mar-25
May-25
Jul-25
Sep-25
Nov-25
Jan-26
Mar-26
May-26
Jul-26
Sep-26
Nov-26
Jan-27
Budget Expenditure Graph
Projected Payments Actual Payments
170
Section 6, Item # 6.3
5 ICM
Schedule/Schedule Impacts
Based on Mozingo's November 2026 schedule update, the Interim Milestone is scheduled to be completed significantly late, shown as September 22, 2026. The pump station is scheduled to be on-line by February 28, 2026. However, the pipeline is running late which can be traced back to the earlier project delays that are telegraphing through the schedule. The pump station cannot be started until the 24 inch Facility 10 pipeline is disinfected and accepted by the District. The Interim Milstone is expected to be completed in March or April but possibly to take until September 22, 2026 and is weather dependent.
Currently, winter weather is delaying the pipeline installation portion of the project because the earthwork equipment cannot work on the slick and steep soils in wet weather. However, with a number of dry and sunny days, the contractor is able to continue construction, thus the entire winter season will not be lost and some productive work will continue. The less rain means the closer the pipeline will be ready around the February 28, 2026 milestone.
Schedule Summary Table
Activity Contractual Dates Contractor Schedule
Notice to Proceed July 24, 2024 July 24, 2024
Interim Milestone February 28, 2026 September 22, 2026
Substantial Completion December 30, 2026 January 21, 2027 Final Completion February 3, 2027 February 3, 2027
171
Section 6, Item # 6.3
6 ICM
CONSTRUCTION MANAGEMENT TEAM
PROGRESS SUMMARY
I. CM Activities Completed
During the month of January, ICM performed the following activities:
• Conducted 3 weekly progress meetings.
• Conducted 1 startup meeting.
• Assisted at fourth SCADA Workshop meeting.
• Coordinated activities on a regular basis with Mozingo and W. M. Lyles • Inspected pump station concrete placements, backfill and other work. • Inspected pump station electrical work.
• Inspected pump station mechanical work.
• Inspected pipeline installation and the installation of appurtenances such as air release valves, blow offs, and trench dams.
• Youngdahl conducted concrete and soil testing, welding inspections.
II. CM Project Budget
At the end of January, approximately 59% of the construction management and inspection budget has been expended over 60% of time to the original Final Completion date.
ICM has performed the following additional scope items:
1. The District approved added scope for ICM to assist with full Procore administrative duties. We are billing for this work but these costs were not included in our proposal budget.
2. The District approved added scope for ICM to increase our scope of land surveying services to address field issues. We are billing for this work but these costs were not included in our proposal budget.
3. The District approved added scope for ICM to assist with public relations and interfacing with homeowners. We are billing for this work but these costs were not included in our proposal budget.
172
Section 6, Item # 6.3
7 ICM
DESIGN TEAM PROGRESS SUMMARY
I. Water Works Engineering Activities Completed
In the month of January, Water Works performed the following activities:
• 6 RFIs were reviewed this month.
• 3 submittals were reviewed this month.
• Assisted with change order reviews.
• Attended three weekly meetings.
II. Request For Information
As of the end of January, there have been 147 RFIs. Based on the RFI count through the end of January and projecting to the end of January 2027, the number of RFIs is anticipated to be 253.
The total average project turnaround time on RFIs is 8.9 days. Graphs of RFIs per Month, Cumulative RFI count, and Average Turnaround Time per Month are shown below (these reflect aggregate numbers for the project team: the District, the Engineer and the Construction Manager).
0 5
10 15
20 25
30 RFIs (per Month)
173
Section 6, Item # 6.3
8 ICM
0 20
40 60
80 100
120
140
160
RFIs (Cumulative)
0 5
10 15
20 25
30 35
40 45
Days
RFI (Turnaround Times)
174
Section 6, Item # 6.3
9 ICM
III. Submittals
Currently, the project team has reviewed 317 submittals (of which 79 were re-submittals) with an average turnaround time of 12.7 days. Graphs of Submittals per Month, Cumulative Submittals, and Submittal Turnaround Times are shown below (these reflect aggregate numbers for the project team: the District, the Engineer & the Construction Manager). 0 10
20 30
40 50
Jul-24
Sep-24
Nov-…
Jan-25
Mar-…
May-…
Jul-25
Sep-25
Nov-…
Jan-26
Mar-…
May-…
Jul-26
Sep-26
Nov-…
Jan-27
Submittals (per Month)
0 50
100
150
200
250
300
350
Jul-24
Sep-24
Nov-24
Jan-25
Mar-25
May-25
Jul-25
Sep-25
Nov-25
Jan-26
Mar-26
May-26
Jul-26
Sep-26
Nov-26
Jan-27
Submittals (Cumulative)
0 5
10 15
20 25
Jul-24
Sep-24
Nov-24
Jan-25
Mar-25
May-25
Jul-25
Sep-25
Nov-25
Jan-26
Mar-26
May-26
Jul-26
Sep-26
Nov-26
Jan-27
Days
Submittals (Turnaround Times)
175
Section 6, Item # 6.3
Prepared for
City of Wheatland
7040 Settlers Trail
Shingle Springs, CA 95682
(530) 683-4038
www.icmgroupusa.com
Cost Proposal for
CONSTRUCTION MANAGEMENT
AND INSPECTION SERVICES
Wheatland-OPUD Regional
Sewer Pipeline Project
May 20, 2026
ICM
176
Section 6, Item # 6.3
ICM
7040 Settlers Trail
Shingle Springs, CA 95682
www.icmgroupusa.com Phone 530-683-4038
May 20, 2026
Dane Schilling Swarnjit Boyal
City Engineer Public Works Engineer
City of Wheatland Oliverhurst Public Utility District
111 C Street 1970 9th Avenue
Wheatland, CA 95692 Olivehurst, CA 95961
RE: Cost Proposal to Provide Construction Management and Inspection Services for the Wheatland-OPUD Regional Sewer Pipeline Project
(CWSRF Project No. C-06-8753-110)
Dear Gentlemen:
Enclosed please find our cost proposal for the referenced project. Our cost proposal includes a proposed budget and fee schedules. Assumptions related to the proposed budget are included. Our fees, those of ICM and our subconsultants, are good through December 31, 2026; thereafter there will be a yearly increase noted on our fee schedules.
Our proposed Total Budget for ICM’s construction management and inspection services for your Project is $4,959,205.
ICM complies with the Department of Industrial Relations (DIR) Prevailing Wage requirements.
Our DIR number is: 1000036717. Our subconsultants also comply with DIR requirements.
Thank you for reviewing our cost proposal. If you have questions or comments, please call me at 916-683-4038.
Sincerely,
Inferrera Construction Management Group, Inc.
Jeffrey Inferrera, PE
President
177
Section 6, Item # 6.3
Start Finish
NTP Lay Pipe Lay Pipe Appurt Appurt Paving Paving SC FC 2026
Construction Activities Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb NTP (June 15)
Submittals
Procurement, Delivery
Lay Pipe weather weather
2 HDD
5 Jack and Bore
Appurtenances
Paving
PS Tie In (April 2028, N.A.)
Punchlist
Total Rate Total Rate Total Rate
Labor Classification Personnel 2026 hrs 2026 2027 hrs 2027 2028 hrs 2028 Total $ Construction Manager Jeffrey Inferrera 40 80 80 80 80 80 80 24 24 80 80 80 80 80 80 80 80 80 24 24 520 $ 255 792 $265.20 24 $ 275.81 $ 349,257.79 Pipeline Inspector Scott Ahlstrom 40 80 160 160 160 160 160 160 160 160 160 160 160 160 160 160 80 760 $ 180 1600 $187.20 80 $ 194.69 $ 451,895.04 Tunnelling Casey Kirk 160 160 160 160 160 800 $ 250 0 $260.00 0 $ 270.40 $ 200,000.00 Project Engineer Roman Gary 8 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 8 28 $ 110 40 $114.40 8 $ 118.98 $ 8,607.81 Administration Elena Inferrera 8 4 4 4 4 4 2 2 4 4 4 4 4 4 4 4 4 4 8 28 $ 95 44 $ 98.80 8 $ 102.75 $ 7,829.22 Quality Assurance Garrett Shonkwiler 4 4 4 4 4 4 4 4 8 12 $ 110 20 $114.40 8 $ 118.98 $ 4,559.81 Warranty Jeffrey Inferrera 8 $ 281.00 $ 2,248.00
Material Testing Youngdahl 32 32 32 32 32 32 32 32 32 32 32 32 32 16 16 160 $ 151 288 $155.53 0 $ 160.20 $ 68,952.64 Survey QA R.E.Y. $ 15,000.00
SWPPP QA A.R.E. 16 16 $ 134 0 $139.36 0 $ 144.93 $ 2,144.00 Community Relations CirclePoint 24 16 16 16 16 8 8 16 16 16 16 16 16 8 8 88 $ 218 128 $226.72 0 $ 235.79 $ 48,204.16 Labor Compliance Cumming $ 33,713.00
ProCore $ 15,600.00
Subconsultant Fee, 5% $ 18,400.69
Contract 1A Total $1,226,412
5/20/2026 ICM
City of Wheatland and Olivehurst Public Utilities District 2028
Wheatland-OPUD Regional Sewer Pipeline Project
Contract 1A Pipeline
ICM Schedule and Budget Table
2027
178
Section 6, Item # 6.3
NTP SC FC
2026 2028
Construction Activities Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep NTP (June 15)
Submittals
Procurement, Delivery
Pump Station 1
Pump Station 2
Pump Station 3
Startup
Other PSs
Paving
PS Tie In (April 2028, N.A.)
Punchlist
Total Rate Total Rate Total Rate
Labor Classification Personnel 2026 hrs 2026 2027 hrs 2027 2028 hrs 2028 Total $ Construction Manager Jeffrey Inferrera 40 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 520 $ 255 960 $ 265.20 720 $ 275.81 $ 585,773.76 Pipeline Inspector Paul Lopez 40 160 160 160 160 160 160 160 160 160 160 160 160 160 160 160 160 160 160 160 160 160 160 160 160 160 80 840 $ 180 1920 $ 187.20 1360 $ 194.69 $ 775,399.68 Second Inspector Akil Barris 160 0 $ 180 160 $ 187.20 0 $ 194.69 $ 29,952.00 Electrical Inspector Akil Barris 16 16 40 40 16 40 16 16 40 80 80 32 $ 190 152 $ 197.60 216 $ 205.50 $ 80,504.06 Project Engineer Roman Gary 8 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 8 28 $ 110 48 $ 114.40 32 $ 118.98 $ 12,378.43 Administration Elena Inferrera 8 4 4 4 4 4 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 8 28 $ 95 44 $ 98.80 40 $ 102.75 $ 11,117.28 Quality Assurance Garrett Shonkwiler 4 4 4 4 4 4 4 4 4 4 8 12 $ 110 24 $ 114.40 12 $ 118.98 $ 5,493.31 Warranty Jeffrey Inferrera 16 $ 281.00 $ 4,496.00
Material Testing Youngdahl 40 40 40 40 40 40 8 40 40 40 8 16 16 120 $ 151 248 $ 155.53 40 $ 160.20 $ 63,099.28 Survey QA R.E.Y. $ 15,000.00
SWPPP QA A.R.E. 16 16 $ 134 0 $ 139.36 0 $ 144.93 $ 2,144.00 Coatings Inspection BACC 24 24 24 24 $ 150 24 $ 156.00 24 $ 162.24 $ 11,237.76 Labor Compliance Cumming $ 75,855.00
ProCore $ 36,600.00
Subconsultant Fee, 5% $ 8,366.80
Contract 1B Total $ 1,717,417
5/20/2026
ICM
City of Wheatland and Olivehurst Public Utilities District 2027
Wheatland-OPUD Regional Sewer Pipeline Project
Contract 1B Pump Stations
ICM Schedule and Budget Table
179
Section 6, Item # 6.3
NTP SC FC
2026 2028
Construction Activities Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Total Hrs Rate Total $ NTP (June 15)
Submittals
Procurement, Delivery
Lay Pipe weather weather
5 Trenchless Crossings
Appurtenances
PS21
PS2
Paving
PS Tie In (April 2028, N.A.)
Punchlist
Startup
Total Rate Total Rate Total Rate
Labor Classification Personnel 2026 hrs 2026 2027 hrs 2027 2028 hrs 2028 Total $ Construction Manager Ricardo Bedoy 80 140 140 140 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 80 80 24 24 24 24 100 100 800 $ 255 1200 $265.20 456 $ 275.81 $ 648,008.45 Pump Station Inspector Matt Livingston 24 160 160 160 160 160 160 160 160 160 160 160 160 160 160 160 160 80 80 160 160 824 $ 180 1760 $187.20 480 $ 194.69 $ 571,242.24 Pipeline Inspector Joe Saylor 80 160 160 160 160 160 160 160 160 160 160 40 720 $ 180 1000 $187.20 0 $ 194.69 $ 316,800.00 Tunnelling Casey Kirk 160 160 160 160 640 $ 250 0 $260.00 0 $ 270.40 $ 160,000.00 Electrical Inspector Akil Barris 16 16 16 40 16 16 40 80 80 32 $ 190 128 $197.60 160 $ 205.50 $ 64,253.44 Project Engineer Roman Gary 8 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 8 28 $ 110 48 $114.40 12 $ 118.98 $ 9,998.91 Administration Elena Inferrera 8 4 4 4 4 4 2 2 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2 2 4 8 28 $ 95 44 $ 98.80 28 $ 102.75 $ 9,884.26 Quality Assurance Garrett Shonkwiler 4 4 4 4 4 4 4 4 4 4 8 12 $ 110 24 $114.40 12 $ 118.98 $ 5,493.31 Warranty Jeffrey Inferrera 16 $ 281.00 $ 4,496.00
Material Testing Youngdahl 8 8 8 8 16 $ 151 16 $155.53 0 $ 160.20 $ 4,904.48 Survey QA R.E.Y. $ 15,000.00
SWPPP QA A.R.E. 16 16 16 $ 134 16 $139.36 0 $ 144.93 $ 4,373.76 Community Relations CirclePoint 24 16 16 16 16 8 8 8 8 8 8 8 8 88 $ 218 64 $226.72 0 $ 235.79 $ 33,694.08 Coatings Inspection BACC 24 24 24 $ 150 24 $156.00 0 $ 162.24 $ 7,344.00 Labor Compliance Cumming $ 94,397.00
ProCore $ 49,500.00
Subconsultant Fee, 5% $ 15,985.67
Contract 2 Total $ 2,015,376
5/20/2026 ICM
City of Wheatland and Olivehurst Public Utilities District 2027
Wheatland-OPUD Regional Sewer Pipeline Project
Contract 2 Pipeline and Pump Stations
ICM Schedule and Budget Table
180
Section 6, Item # 6.3
5/20/26
Inferrera Construction Management Group, Inc.
Fee Schedule
Wheatland-OPUD
Construction Management and Inspection
Regional Sewer Pipeline Project
Labor Hourly Rates by Position
Construction Manager $255
Pump Station Inspector $180
Pipeline Inspector $180
Electrical Inspector $190
Project Engineer $110
Quality Assurance $110
Administrator $95
Other ICM Support $180
Expense Rates
Project Travel, Mileage N.C.
Project Travel, Time N.C.
Field Computer/Phone N.C.
Other ODCs billed separately
Administrative Fees
Expenses 0%
Subconsultants 5%
Notes:
1. Minimum 4-hour onsite charge per site or off-site visits.
2. Overtime for work performed on Monday thru Friday will be charged 1.5 times the hourly rate for time worked over eight hours a day up to 12 hours, and 2 times the hourly rate for time worked over twelve hours.
3. Work on Saturday will be charged the 1.5 time overtime rate for the first eight hours and 2 times the hourly rate for time worked over 8 hours.
4. Work on Sunday and Holidays will be charged at the 2 time overtime rate.
5. Second shift work performed commencing after 2 p.m. or before 4 a.m. will be charged an additional $25 per hour.
6. This Rate Schedule is valid until December 31, 2026. There will be an annual increase of 4% starting January 1, 2027, and each year thereafter.
181
Section 6, Item # 6.3
5/20/26 1 ICM
Wheatland-OPUD
Regional Sewer Pipeline Project
Cost Proposal Assumptions
To plan construction management and inspection resource allocation for the Regional Sewer Pipeline Project, we used the requirements of the Agency’s Request for Proposal, project plans and specifications, and our experience on other similar projects. Assumptions we used to develop our proposed budget are explained below.
Important Dates and Times
• We assume that construction management services will start mid June 2026. • We estimate the latest Final Completion Date will be in September 2028. • We assume construction management services will end by September 2028. • Our budget assumes Contractor and all of its subcontractors will work 8-hour days. • We assume that the Contractor and all of its subcontractors will start their work day and end their work day at the same time.
Comments on Pipeline
1. In regards the duration of pipeline projects, typical production rates for these types of pipes are 200 to 400 LF per day. Considering the impact of existing utilities, we assumed the lower production rate of 200 LF per day. which equates to durations provided in the budget table. Our assumption is based on each pipeline project having one pipe laying crew for excavation, lay, and backfill, and one appurtenance crew.
2. In regards the duration of pump station and associated treatment plant work, we based their durations on our recently completed Bogue Road Wastewater Pump Station Project in Yuba City.
The Bogue Road Wastewater Pump Station has a similar size and complexity as Contract 1B pump stations 1, 2, and 3. We increased the duration for Pump Station 21.
Weather Impacts
We assume that inclement weather in the winter months will stop pipeline work for two months.
Assumptions for Resident Engineers Hours
For all three contracts of their size and complexity, an experienced construction manager, such as Jeffrey Inferrera and Ricardo Bedoy, will have a utilization on average of 50 percent. Their hours are reflected accordingly in the Proposed Budget Table.
Assumptions for Pipeline Inspector Hours
For this project, based on the pipe size and trenching, we assume a pipe installation production rate of 200 LF per day. It is common to have one pipe laying crew and one appurtenance crew working at the same time. One inspector with Scott Ahlstrom and Joe Saylor's experience can inspect two crews, one laying pipe and the other installing appurtenances on the same pipeline segment.
182
Section 6, Item # 6.3
5/20/26 2 ICM
Assumptions for Tunnelling Inspector Hours
We assume each trenchless crossing is 4 weeks long, with 2 weeks of boring, and they are all completed in the first dry season. Our team includes Casey Kirk, an experienced tunnelling inspector.
Assumptions for Pump Station Inspector Hours
We have budgeted for one full time pump station inspector for Contract 1B, Paul Lopez, and one full time pump station inspector for Contract 2, Matt Livingston. Paul Lopez and Matt Livingston are both experienced inspectors who are qualified to all trades. However, we have allotted additional hours for other inspectors to help them on an as needed basis. This additional support will be used for inspecting specific technical details or to supplement field staff when work is at peak construction activity.
Assumptions for Electrical Inspector Hours
Our electrical inspector, Akil Barris, ICC, will provide specialty electrical inspection for the pump stations on a part time basis, as needed. His hours are incorporated in the budget table.
Assumptions for Material Testing Inspector Hours
Youngdahl will provide material testing services for Contract 1A and 1B. For Contract 2, since the contractor is responsible for material testing, we have included QA testing services.
Youngdahl’s work is included in the budget table.
Assumptions for SWPPP Inspection Hours
All three projects require the contractors to provide SWPPP services including design and inspection. American River Environmental will provide SWPPP quality assurance on an as needed basis.
Assumptions for Public Relations Hours
CirclePoint, an experienced public relations firm, will provide public relations support on an as needed basis. We based their budget on their work for our recent Arden Area Main Lines Project for Sacramento County Water Agency.
NACE Certified Coatings Inspection
Wastewater pump stations normally have specialty coatings. We have included the services of Bay Area Coatings Consultants, a NACE certified coatings inspection firm, to provide these services. Our proposed budget includes an estimate of the needed resource allocation.
Licensed Land Surveying
Since there are multiple pipelines and connections, we have included R.E.Y. Engineers to provide survey quality insurance services. They will verify, at the start of the job, that all contractors are using the same coordinate systems and check for errors.
Assumptions for Labor Compliance
The Cummings Group used the project information to develop a labor compliance budget which is included in the budget table.
183
Section 6, Item # 6.3
5/20/26 3 ICM
Project Engineering
We have budgeted for an engineer, Roman Gary, M.S., to assist with conformed drawings, as built drawings, RFI and submittal coordination.
Administrative Services
We provide, on an as needed basis, the services of our administrators who are experienced with ProCore, VPM, and other document management systems and the other miscellaneous project tasks.
Warranty Support Services
We have provided warranty support services for past pump station and treatment plant projects.
The number of hours required to assist operations and maintenance staff is minimal. We included what we consider sufficient budget.
Other Considerations
• In the future event that we discover that our assumptions were not accurate, we will need to be afforded the opportunity to adjust our budget accordingly or change our scope of services so that we can meet the Agency's needs while being properly reimbursed for our services. This is because the actual construction management and inspection budget needed to provide the Agency with the resource allocation needed to meet their needs is dependent on the contractor's actual schedule, productivity and progression of their work, resource allocation, and material availability and delivery, which is not known at this time. Additional inspection support above and beyond what is budgeted may be appropriate depending on these and other factors.
• This budget is in agreement with RFP Scope of Services with comments in our Proposal. • This proposal is based on a time and materials contract. This cost proposal is only an estimate; actual labor effort will be dependent on the contractors’ schedule. Budgeted hours and cost proposal may change based on the actual project schedule. ICM reserves the right to transfer budgeted hours between contracts, between projects, and between tasks and subtasks.
• This proposal excludes hiring of an inspector apprentice which can be required by the State Department of Industrial Relations although we have not seen it done to date and have not included hours for an apprentice.
• Contractors will provide office space and utilities at the job site for construction management and inspection staff. These costs have not been included in the proposed budget.
184
Section 6, Item # 6.3
5/20/26 4 ICM
Wheatland-OPUD
Regional Sewer Pipeline Project
Proposal Exclusions
1. We exclude ADA compliance certification and/or warranty.
2. Our inspectors will note and address SWPPP violations in their normal daily activities. However, ICM will not provide SWPPP special inspection services except for QA inspection as needed. We exclude SWPPP plan development, SWPPP certification and SWPPP uploading to State web site.
3. We exclude surveying by a California Licensed Land Surveyor except as QA inspection only.
4. We exclude construction staking.
5. We exclude litigation, arbitration, or other dispute resolution support. These are optional services we can add.
6. We exclude engineering support services such as technical review of submittals and RFIs with the exception of schedule submittal, schedule of values submittal, and RFIs better answered by our field staff.
7. We exclude submittal and RFI routing and/or review through or by ICM. Routing of submittals and RFIs will be by direct transmission from contractor to engineer (and vice versa) with copies to ICM and Owner. Transmission will be by ProCore, or equal, document management system. Review of submittals will be performed by the design engineer and Owner.
8. We provide daily field reports and daily inspection reports. We exclude building official reports or sign offs as well as project final inspection reports. However, this can be provided as additional services if needed.
9. ICM is not responsible for Contractor's safety or safety program.
10. ICM is not responsible for Contractor's schedule.
185
Section 6, Item # 6.3
Wheatland-OPUD Regional Sewer Pipeline Project
Brown and Caldwell
City of Wheatland and Olivehurst Public Utilities District Wheatland-OPUD Regional Sewer Pipeline Project
2026 Charge Rates Schedule – CM Only
Professional Services
Principal in Charge…………………………………………………,,,……..$330.00/hour Project Manager….……………………………………….....$280.00 - $320.00/hour Administrative Personnel*………..…………………..…$100.00 - $150.00/hour Construction Management
Construction Manager……………………………………..$250.00 - $320.00/hour Construction Inspector……………………………………..$215.00 - $250.00/hour Electrical Inspector…………………………………………..$210.00 - $250.00/hour * Includes Administrative Professional, Project Analyst and Project Biller.
Assumptions:
• Rates are effective through December 31, 2026. Rates will be adjusted by 4% escalation per year thereafter at the beginning of each calendar year. • BC staff will be provided with an on-site field office with furnishing, internet services and reproduction capabilities.
2026 Hourly Rates for Specific Personnel
Stephen Walters - $330
Gavin Lee - $250
Casey Kirk - $250
Rick Sasser - $240
Dane Forsberg - $225
Anthony Knapp - $211
186
Section 6, Item # 6.3
CLASSIFICATION 2026/27 2027/28 2028/29 AVG
COMPLIANCE SPECIALIST $ 135.00 $ 140.40 $ 146.02 $ 140.47 ANNUAL ESCALATION 4%
# CONTRACT AWARD TERM MONTHS HOURS/MO. EST. HOURS SUBTOTAL 1A WHEATLAND PIPELINES $ 15,621,813.00 380 WORKING DAYS 20 12 240 $ 33,713.28 1B WHEATLAND PUMP STATIONS $ 38,558,793.00 535 WORKING DAYS 27 20 540 $ 75,854.88 2 OPUD PIPELINE/PUMP STATIONS $ 49,000,000.00 715 CALENDAR DAYS 24 28 672 $ 94,397.18 $ 203,965.34
HOURLY RATE
City of Wheatland and Olivehurst Public Utilities District Wheatland-OPUD Regional Sewer Pipeline Project
Contracts 1A/1B/2
Cumming Fee and Budget Table
187
Section 6, Item # 6.3
PREVAILING WAGE FEE SCHEDULE FOR PROFESSIONAL SERVICES (2026)
PERSONNEL STANDARD RATE
Principal Engineer
Senior Engineer/Geologist/Scientist
Project Engineer/Geologist/Environmental Scientist
Staff Engineer/Geologist/Scientist
Field Supervisor
NDT Special Inspector/Floor Flatness
ICC Lead Special Inspector, DSA Masonry – Group 1 (excluding NDT) For Non-Prevailing Wage Tasks
ICC/AWS/CWI Certified Special Inspector – Group 2
For Non-Prevailing Wage Tasks
Soils Engineering Technician ; ACI Groups 3 & 4
For Non-Prevailing Wage Tasks
Environmental Technician
QSD-Qualified SWPPP Developer
QSP-Qualified SWPPP Practitioner
Laboratory Manager
Senior Laboratory Technician
Laboratory Technician
Draftsperson
Clerical
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
230.00
190.00
173.00
163.00
163.00
173.00
157.00
138.00
156.00
135.00
151.00
110.00
116.00
156.00
116.00
162.00
126+.00
102.00
112.00
106.00
/hr
/hr
/hr
/hr
/hr
/hr
/hr
/hr
/hr
/hr
/hr
/hr
/hr
/hr
/hr
/hr
/hr
/hr
/hr
/hr
BASIS OF CHARGES
Equipment Charges:
All of the above rates are inclusive of routine test equipment.
Exceptions:
• Coring Machine
• Generator
• High Precision GPS Receiver
• Photo-Ionization Detector
• Skidmore
• Fireproofing Adhesion
- $200/day
- $75/day
- $150/day
- $100/day
- $100/day
- $25/test
Hours are billed portal to portal in accordance with the following minimum charges:
• Times are rounded up to the nearest ½ hour.
• 2-hour minimum on-site charge for each site visit.
• 4-hour minimum on-site charge for weekend work.
• 2-hour minimum charge for work scheduled that was not cancelled by 5pm the day before.
Overtime:
• Over eight (8) hours a day
• Saturdays
• Over eight (8) hours on Saturdays
• Sundays and Holidays
• Over twelve (12) hours a day
• Night Work 5:00 pm – 5:00 am
- 1.5 x hourly rate
- 1.5 x hourly rate
- 2.0 x hourly rate
- 2.0 x hourly rate
- 2.0 x hourly rate
- $10+ hourly rate
Mobilization Charge:
A mobilization charge of $ 80.00/site visit will be added for all projects requiring site visits within 40 miles of our corporate yard. For projects beyond 40 miles, a mileage fee will be assessed at $0.95/mile portal to portal per visit from our corporate headquarters address to the project site. Distance will be determined by Google Maps quickest calculated distance.