May, 2026 15052-2 Septage Hauling and Receiving Station Final
b. Install plug valves as air bleeder cocks at high points in piping. Provide one inch plug valves for water lines, and 2 inch plug valves for sewage and sludge lines, unless otherwise indicated on the Drawings.
c. Provide additional pipe taps with plug cocks and riser pipes along piping as required for venting during initial filling, disinfecting, and sampling. d. Before piping is placed into service, close plug valves and install plugs.

Protect plugs and plug valves from corrosion in accordance with Section 09960.

2. Restraining Piping:
a. Restrain piping at valves and at fittings where piping changes direction, changes sizes, and at ends.
1) When piping is underground, use concrete thrust block or mechanical restraints.
2) When piping is aboveground or under water, use mechanical or structural restraints.
3) Determine thrust forces by multiplying the nominal cross sectional area of the piping by design test pressure of the piping.
b. Provide restraints with ample size to withstand thrust forces resulting from test pressures.
1) During testing, provide suitable temporary restraints where piping does not require permanent restraints.
c. Place concrete thrust blocks against undisturbed soil. Place concrete so piping joints, fittings, and other appurtenances are accessible for assembly and disassembly.
d. Provide underground mechanical restraints where specified in the Piping Schedule.

3. Connections to Existing Piping:
a. Expose existing piping to which connections are to be made with sufficient time to permit, where necessary, field adjustments in line, grade, or fittings. 1) Protect domestic water supplies from contamination.
a) Make connections between domestic water supply and other water systems in accordance with requirements of public health authorities.
b) Provide devices approved by OWNER of domestic water supply system to prevent flow from other sources into the domestic supply system.
b. Make connections to existing piping and valves after sections of new piping to be connected have been tested and found satisfactory.
c. Provide sleeves, flanges, nipples, couplings, adapters, and other fittings needed to install or attach new fittings to existing piping and to make connections to existing piping.

4. Connections to In-service Piping:
a. Shutdown in-service piping in accordance with Section 01140. 1) Establish procedures and timing in a conference attended by CONTRACTOR, ENGINEER, and OWNER of the in-service piping. b. Where operation and maintenance of existing facilities require that a shutdown be made during hours other than normal working hours, perform the related work in coordination with the hours of actual shutdown. c. Additional provisions regarding shutdown of existing facilities are specified in Section 01140 Work Restrictions.

5. Connections at Dissimilar Metals:
a. Connect ferrous and nonferrous metal piping, tubing, and fittings with dielectric couplings especially designed for the prevention of chemical reactions between dissimilar metals.

Page 749 of 1480 ends

May, 2026 15052-3 Septage Hauling and Receiving Station Final
b. Nonferrous metals include aluminum, copper, and copper alloys.

PART 2 PRODUCTS

2.01 ESCUTCHEONS
A. Manufacturers: One of the following or equal:

1. Dearborn Brass Company, Model Number 5358.

2. Keeney Manufacturing Company, Model Number 102 or Number 105.

3. Beaton and Corbin, Model Number 1 or Number 13.

B. Material: Chrome plated steel plate.

2.02 LINK TYPE SEALS
A. Manufacturers: One of the following or equal:

1. Calpico, Inc.

2. Thunderline Corporation, Link-Seal.

B. Characteristics:

1. Modular mechanical type, consisting of interlocking neoprene or synthetic rubber links shaped to continuously fill the annular space between the pipe and wall opening.

2. Assemble links solely with stainless steel bolts and nuts to form a continuous rubber belt around the pipe.

3. Provide a stainless steel or glass reinforced nylon pressure plate under each bolt head and nut. Isolate pressure plate from contact with wall sleeve.

2.03 GASKETS
A. Gaskets for Non-steam Cleaned Ductile Iron and Steel Piping:

1. Suitable for pressures equal to and less than 150 pounds per square inch gauge, temperatures equal to and less than 250 degrees Fahrenheit, and raw sewage service.

2. Gasket Material:
a. Neoprene elastomer with minimum Shore A hardness value of 70. b. Reinforcement: Inserted 13 ounce nylon fabric cloth for pipes 20 inch or larger.
c. Thickness: Minimum 3/32 inch thick for less than 10 inch pipe; minimum 1/8 inch thick for 10 inch and larger pipe.

3. Manufacturers: One of the following or equal:
a. Pipe 20 inches in Diameter and Larger:
1) Garlock, Style 8798.
2) John Crane, similar product.
b. Pipe less than 20 inches in Diameter:
1) Garlock, Style 7797.
2) John Crane, similar product.

B. Gaskets for Flanged Joints in Polyvinyl Chloride and Polyethylene Piping:

1. Suitable for pressures equal and less than 150 pounds per square inch gauge, with low flange bolt loadings, temperatures equal and less than 120 degrees Fahrenheit, polymer, chlorine, caustic solutions, and other chemicals, except

Page 750 of 1480 ends

May, 2026 15052-4 Septage Hauling and Receiving Station Final
chemicals which liberate free fluorine including fluorochemicals and gaseous fluorine.

2. Material:
a. Microcellular Teflon outer layers with rigid center layer. b. Sealability in accordance with ASTM F37, lass than 0.55 millimeters/hr leakage of iso-octane at 1,000 psi gasket load and 9.8 psig fluid pressure.

3. Manufacturers: One of the following or equal:
a. Garlock, Style 3545.
b. John Crane, similar product.

C. Gaskets for Flanged Joints in Ductile Iron, or Steel Water Piping:

1. Suitable for hot or cold water, pressures equal and less than 150 pounds per square inch gauge, and temperatures equal and less than 160 degrees Fahrenheit.

2. Material:
a. Neoprene elastomer, compressed, non-asbestos fiber reinforcement. b. Teflon ring; or teflon envelope with nonasbestos filler.

3. Manufacturers: One of the following or equal:
a. Bluegard, Style 3300.
b. Garlock.
c. John Crane, similar product.

PART 3 EXECUTION

3.01 EXAMINATION
A. Verification of Existing Conditions:

1. Locate and expose existing structures, piping, conduits, and other facilities and obstructions which may affect construction of underground piping before starting excavation for new underground piping and appurtenances.

2. Verify sizes, elevations, locations, and other relevant features of existing facilities and obstructions. Determine conflicts for the construction of the new underground piping and appurtenances.

3. Make piping location and grade adjustments to resolve conflicts between new piping and existing facilities and obstructions.

3.02 WALL AND SLAB PENETRATIONS
A. Provide sleeves for piping penetrations through aboveground masonry and concrete walls, floors, ceilings, roofs, pilasters, columns, piers, and beams unless specified or otherwise indicated on the Drawings.

B. For piping 1 inch in nominal diameter and larger, provide sleeves with minimum inside diameters of 1 inch plus outside diameter of piping. For piping smaller than 1 inch in nominal diameter, provide sleeve of minimum twice the outside diameter of piping.

1. Arrange sleeves and adjacent joints so piping can be pulled out of sleeves and replaced without disturbing the structure.

2. Cut ends of sleeves flush with surfaces of concrete, masonry, or plaster.

3. Conceal ends of sleeves with escutcheons where piping runs through floors, walls, or ceilings of finished spaces within buildings.

4. Seal spaces between pipes and sleeves with link-type seals when not otherwise specified as indicated on the Drawings.

Page 751 of 1480 ends

May, 2026 15052-5 Septage Hauling and Receiving Station Final
C. Cast couplings or wall pieces in walls for penetrations of buried rigid piping including cast iron, ductile iron, reinforced concrete, and vitrified clay through structures.

1. Provide couplings or wall pieces with mechanical push-ons, restrained where indicated or required, or similar flexible joints at outside faces of walls.

2. Provide additional similar joints in piping at transition points between trenches and structure excavations.

3. For steel piping, single joints may be used in lieu of 2 joints. Locate single joints outside within 2 feet from outside faces of walls.

D. Link Seal: Use 2 link seals where seal is used to seal at wet wall sleeves. Mount one seal on the inside face of the wall and the other on the outside face of the wall.

Coordinate the inside diameter of the wall sleeve with the size of the seal to provide watertight sealing.

E. Where not indicated on the Drawings, penetrations for conditions other than those specified under the preceding subparagraphs shall be 1 of the 3 types specified in such subparagraphs found by ENGINEER to be the most suitable for the particular conditions.

3.03 EXPOSED PIPING
A. Install exposed piping in straight runs parallel to the axes of structures, unless indicated otherwise.

1. Install piping runs plumb and level, unless otherwise indicated on the Drawings.

Slope plumbing drain piping with 1/8 inch per foot downward in the direction of flow.

B. Install exposed piping after installing equipment and after piping and fitting locations have been determined.

C. Support piping in accordance with Section 15061.

1. Do not transfer pipe loads and strain to equipment.

D. In addition to the joints indicated on the Drawings, provide unions, flexible couplings, flanged joints, and other types of joints or means which are compatible with and suitable for the piping system, and necessary to allow ready assembly and disassembly of the piping.

E. Assemble piping without distortion or stresses caused by misalignment.

1. Match and properly orient flanges, unions, flexible couplings, and other connections.

2. Do not subject piping to bending or other undue stresses when fitting piping. Do not correct defective orientation or alignment by distorting flanged joints or subjecting flange bolts to bending or other undue stresses.

3. Flange bolts, union halves, flexible connectors, and other connection elements shall slip freely into place.

4. Alter piping assembly to fit when proper fit is not obtained.

5. Install eccentric reducers or increasers with the top horizontal for pump suction piping.

3.04 BURIED PIPING
A. Bury piping with minimum 3 foot cover without air traps, unless otherwise indicated on the Drawings.

Page 752 of 1480 ends

May, 2026 15052-6 Septage Hauling and Receiving Station Final
B. Where 2 similar services run parallel to each other, piping for such services may be laid in the same trench. Lay piping with sufficient room for assembly and disassembly of joints, for thrust blocks, for other structures, and to meet separation requirements of public health authorities having jurisdiction.

C. Laying Piping:

1. Lay piping in finished trenches free from water or debris. Begin at the lowest point with bell ends up slope.

2. Place piping with top or bottom markings with markings in proper position.

3. Lay piping on an unyielding foundation with uniform bearing under the full length of barrels.

4. Where joints require external grouting, banding, or pointing, provide space under and immediately in front of the bell end of each section laid with sufficient shape and size for grouting, banding, or pointing of joints.

5. At the end of each day's construction, plug open ends of piping temporarily to prevent entrance of debris or animals.

3.05 PIPING ALTERNATIVES
A. Provide piping in accordance with this Section, unless indicated on the Drawings or specified otherwise.

B. Alternative Pipe Ratings: Piping with greater pressure rating than specified may be substituted in lieu of specified piping without changes to the Contract Price. Piping of different material may not be substituted in lieu of specified piping.

C. Valves in Piping Sections: Capable of withstanding specified test pressures for piping sections and fabricated with ends to fit piping.

D. For flanged joints, where one of the joining flanges is raised face type, provide a matching raised face type flange for the other joining flange.

3.06 CLEANING
A. Piping Cleaning:

1. Upon completion of installation, clean piping interior of foreign matter and debris.

Perform special cleaning when required by the Contract Documents.

3.07 PIPING SCHEDULE
A. Abbreviations:

1. The following abbreviations used in the column of test method refer to the respective methods specified in Section 15956.

AM Air method
GR Gravity method
HH High head method
LH Low head method
SC Special case

2. Abbreviations to designate piping include the following:

BSP Black steel pipe

Page 753 of 1480 ends

May, 2026 15052-7 Septage Hauling and Receiving Station Final
BRV Braided Vinyl Tubing
CI Cast iron
CISP Cast iron soil pipe
Cl Class, followed by the designation
CMP Corrugated metal pipe
CPVC Chlorinated polyvinyl chloride
DIP Ductile iron piping
Ga Gauge, preceded by the designation
GSP Galvanized steel pipe
NPS Nominal pipe size, followed by the number in inches PSIG Pounds per square inch, gauge
PE Polyethylene
PVC Polyvinyl Chloride
RCP Reinforced concrete low head pressure pipe
Sch. Schedule, followed by the designation
SS Stainless steel
VCP Vitrified clay piping

3. Abbreviations to designate piping joints and fittings include the following:

B&SP Bell and spigot
FLG Flanged
GE Grooved end joint
Mech.

Rest.

Mechanically restrained
MJ Mechanical joint
PO
PVCI
Push on joint
PVC insert fittings with 316 stainless steel clamps.

SCRD Screwed joint
SW Solvent weld joint
WLD Welded joint

4. Abbreviations to designate piping joints and fittings include the following:

CLTE Coal tar enamel lining
CM Cement mortar
CTE Coal tar epoxy lining
CTP Coal tar pitch
EC Extruded coating
EPP Epoxy and polyurethane high performance coating per Section 09960 GL Glass lining
PE Polyethylene lining
PEE Polyethylene encasement
PTW Plastic tape wrap
PUL Polyurethane lined

Page 754 of 1480 ends

May, 2026 15052-8 Septage Hauling and Receiving Station Final
(The PIPING SCHEDULE follows in the next pages.)

END OF SECTION

Page 755 of 1480 ends

PIPING SCHEDULE
Process
Abbrev. Service
Nominal
Diameter
(inches)
Materials Joints/ Fittings
Test
Pressure/
Method
Lining Coating Comments
SS Sanitary Sewer
(Gravity)
Underground 8 PVC Gravity Sewer
Piping SDR-26
PVC Push on
SDR-26 Fittings 10 PSIG/LH None None Note 7
SD Storm Drain
Underground 6 PVC AWWA C900
SDR<= 18
PVC Push on
Fittings 10 psig/LH None None Note 4,5
D Drain (Gravity)
Underground/vertical
piece 8 PVC AWWA C900
SDR<= 18
DI Push on
Fittings with
flange
connection to
Sched 80 pipe
10 psig/LH None None Note 4, 5
Underground 4-6 Schedule 80 PVC PVC/ Solvent
Weld 10 PSIG/LH None None
Exposed Ell and
connection to Screen 8 Schedule 80 PVC Flanged 10 PSIG/LH None EPP Note 1 3W Plant Water
Underground 4 Schedule 80 PVC PVC/ Solvent
Weld 80 PSIG/HH None None
Exposed 0.5-4 Schedule 40 GSP Screwed 80 PSIG/HH None EPP Note 1, 6 15052-9

Page 756 of 1480 ends

PIPING SCHEDULE
Process
Abbrev. Service
Nominal
Diameter
(inches)
Materials Joints/ Fittings
Test
Pressure/
Method
Lining Coating Comments
Notes:

1. All exposed piping shall be painted and/or coated in accordance with Section 09960.

2. All buried piping under concrete slabs and/or structures shall be concrete encased per typical detail P050, unless indicated in writing otherwise.

3. All Piping shall be restrained per Section 15052 – Article 1.04 B.2.

4. Connect flange to C900 pipe with megalug adaptor or equal. Flange connection to Schedule 80 Ell is needed.

5. Provide complete pipe restraint system for all fittings and transition joints including from ductile iron to PVC. Restraints shall be megalug or equal.

6. Transition to GSP at buried valve up through riser section. PE tape wrap GSP pipe for the short portion that is underground.

7. Mandrel and Socket Test Sanitary Sewer per City Standards. 15052-10

Page 757 of 1480 ends

May, 2026 15061-1 Septage Hauling and Receiving Station Final
SECTION 15061

PIPE SUPPORTS
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Supports for pipe, fittings, valves, and appurtenances whether typical details or premanufactured supports.

B. Related Sections:

1. Section 01612 - Seismic Design Criteria

2. Section 01614 – Wind Criteria

3. Section 05120 - Structural Steel.

4. Section 09910 - Paints.

5. Section 09960 - High Performance Coatings.

6. Section 15062 – Preformed Channel Pipe Support System

1.02 REFERENCES
A. American National Standard Institute or Manufacturer's Standardization Society (ANSI/MSS):

1. SP-58 - Standard for Pipe Hangers and Supports - Materials, Design, and Manufacture.

2. SP-69 - Standard for Pipe Hangers and Supports - Selection and Application.

1.03 SYSTEM DESCRIPTION
A. Design Responsibility:

1. The CONTRACTOR providing the pipe support system shall be considered the designer of the support system. Typical details included on the contract documents are for minimum standard for style, size, and materials and shall be used as a guide for the CONTRACTOR in designing the specific pipe supports utilized on the project.
a. Seismic and Wind Design Criteria: As specified in Section 01612 and 01614 as specified for all pipe supports utilized for the project, including any typical pipe support details included on the contract documents that are actually utilized.

2. All pipe supports shall be minimum 304 stainless steel unless otherwise noted on the drawings.

1.04 SUBMITTALS
A. Shop Drawings: Prepare detailed shop drawings illustrating the layout of the support system and identifying the components of the support system. Include schedule, indicating where supports will be installed, and drawings of pipe support system components.

B. Seismic and wind design calculations and details need to be provided per Section 1.03 above.

C. Furnish Submittals in accordance with Sections 01330 and 15050.

Page 758 of 1480 ends

May, 2026 15061-2 Septage Hauling and Receiving Station Final
PART 2 PRODUCTS

2.01 PREMANUFACTURED PIPE SUPPORTS
A. See Section 1.04.A.5 for material designation all part numbers on the following supports shall be modified for correct material designation.

B. Concrete Inserts for Pipes under 30 Inch Diameter: ANSI/MSS SP-69 Type 18.

Minimum 1,140 pounds capacity with 5/8 inch diameter rod. Manufacturers: One of the following or equal:

1. Grinnell, Figure 282.

C. Concrete Inserts for Pipe 30 Inch Diameter and Larger: Hot-dip galvanized steel body with 3/4 inch diameter National Coarse zinc plated square nut, anchor insert to steel concrete reinforcement. Manufacturers: One of the following or equal:

1. Connection Specialties, Inc., Model 6MD350.

D. Hanger Rods: Sized to match suspended pipe hanger, or as indicated on the Drawings. Manufacturers: One of following or equal:

1. Grinnell, Figure 140.

2. Bergen-Paterson, Part 5000.

3. B-Line Systems, Inc., Figure B3205.

E. Hanger Rods, Continuously Threaded: Sized to match suspended pipe hanger, or as indicated on the Drawings. Manufacturers: One of the following or equal:

1. Grinnell, Figure 146.

2. Bergen-Paterson, Part BP-5006.

F. Eye Bolts: Welded and rated equal to full load capacity of rod.

G. Welded Eyebolt Rod: Manufacturers: One of the following or equal:

1. Grinnell, Figure 278.

2. Bergen-Paterson, Part 5004.

3. B-Line Systems, Inc., Figure B3210.

H. Adjustable Ring Hangers: ANSI/MSS SP 69 Type 7. Manufacturers: One of the following or equal:

1. Grinnell.

2. B-Line Systems, Inc., Figure B3172.

I. Adjustable Clevis Hangers: ANSI/MSS PS 69, Type 1. Manufacturers: One of the following or equal:

1. Grinnell, Figure 260.

2. Bergen-Paterson, Part 6750.

3. B-Line systems, Inc., Figure B3100 or B3105.

J. Adjustable Clevis Hangers for Insulated Pipe: Oversize. Manufacturers: One of the following or equal:

1. Grinnell, Figure 300.

2. Bergen-Paterson, Part 6754.

3. B-Line Systems, Inc. Figure B3108.

Page 759 of 1480 ends

May, 2026 15061-3 Septage Hauling and Receiving Station Final
K. Single Rod Hangers for Steam Pipe: ANSI/MSS SP 69 Type 43; malleable iron or steel yoke and roller hangers; swivel to allow rotation of yoke on rod. Manufacturers: One of the following or equal:

1. Grinnell, Figure 181.

2. B-Line Systems, Inc., Figure B3110.

L. Double Rod Hangers for Steam Pipe: ANSI/MSS SP 69 Type 41: Manufacturers: One of the following or equal:

1. Grinnell, Figure 171.

2. B-Line Systems, Inc., Figure B3114.

M. Brackets: ANSI/MSS SP-69 Type 32 with back plate; rated for 1,500 pounds.

Manufacturers: One of the following or equal:

1. Grinnell, Figure 195.

2. B-Line Systems, Inc., Figure B3066.

N. Standard U-bolt: ANSI/MSS SP-69 Type 24. Manufacturers: One of the following or equal:

1. Grinnell, Figure 137.

2. Bergen-Paterson, Part 6510.

3. B-Line systems, Inc., Figure B3188.

O. Riser Clamps: ANSI/MSS SP-69 Type 8. Manufacturers: One of the following or equal:

1. Grinnell, Figure 261.

2. Bergen-Paterson, Part 6302.

3. B-Line Systems, Inc., Figure B3373.

P. Pipe Clamps: ANSI/MSS SP 69 Type 4. Manufacturers: One of the following or equal:

1. Grinnell, Figure 212.

2. Bergen-Paterson, Part 6100.

3. B-Line Systems, Inc., Figure B3140.

Q. Adjustable Offset Pipe Clamp: Manufacturers: One of the following or equal:

1. Grinnell, Figure 100.

2. B-Line Systems, Inc., Figure B3149.

R. Offset Pipe Clamp: Manufacturers: One of the following or equal:

1. Grinnell, Figure 103.

2. B-Line Systems, Inc., Figure B3148.

S. Floor Stand or Stanchion Saddles: ANSI/MSS SP-69 Type 37. Provided with U-bolt hold down yokes. Manufacturers: One of the following or equal:

1. Grinnell, Figure 259.

2. Bergen-Paterson, Part 6652.

3. B-Line Systems, Inc., Figure B3090.

T. Spring Supports: Manufacturers: One of the following or equal:

1. Bergen-Paterson, Part 3200.

2. Grinnell, Figure B-268.

U. One Hole Pipe Clamps: Manufacturers: One of the following or equal:

1. Grinnell, Figure 126.

2. Carpenter and Paterson, Figure 237.

Page 760 of 1480 ends

May, 2026 15061-4 Septage Hauling and Receiving Station Final
V. Welded Beam Attachment: Manufacturers: One of the following or equal:

1. Grinnell, Figure 66.

2. Bergen-Paterson, Part 1047.

3. B-Line Systems, Inc., Figure B3083.

W. Heavy Pipe Clamp: Manufacturers: One of the following or equal:

1. Grinnell, Figure 216.

2. Bergen-Paterson, Part 6101.

X. Anchor Bolts, Flush Shells, Powder Actuated Fasteners, and Concrete Anchors: As specified in Section 05120.

2.02 MATERIALS
A. Pipe Supports:

1. Stainless Steel (type 304 or 316): Use in all in all areas except where specifically indicated on the Drawings.

2. Hot-dip Galvanized Steel: Use where specifically indicated on the Drawings

3. Hot-dip galvanize pipe support after fabrication.

4. Plastic, Aluminum, FRP and Other Miscellaneous Materials: Use where specifically indicated on the Drawings
B. Fasteners:

1. As specified in Section 05120.

PART 3 EXECUTION

3.01 INSTALLATION
A. Properly support, suspend or anchor exposed pipe, fittings, valves, and appurtenances to prevent sagging, overstressing, or movement of piping; and to prevent thrusts or loads on or against connected pumps, blowers, and other equipment. The CONTRACTOR shall provide proper supports for piping even if piping supports are not indicated on the drawings.

B. The CONTRACTOR shall follow support typical details and apply support details where applicable at all locations whether specifically called or not on the drawings.

C. Carefully determine locations of inserts. Anchor to formwork prior to placing concrete.

D. Use either epoxy anchors or cast in anchor bolts to anchor equipment and supports.

E. Do not use anchors wedge anchors or anchors relying on deformation of lead alloy.

F. Do not use stud type powder actuated fasteners for securing metallic conduit or steel pipe larger than 1 inch to concrete, masonry, or wood.

G. Suspend pipe hangers from hanger rods. Secured with double nuts.

H. Install continuously threaded hanger rods only where indicated on the Drawings.

I. Use adjustable ring hangers; or adjustable clevis hangers, for 6 inch and smaller diameter pipe.

Page 761 of 1480 ends

May, 2026 15061-5 Septage Hauling and Receiving Station Final
J. Use adjustable clevis hangers for pipe larger than 6 inches in diameter.

K. Secure pipes with double nutted U-bolts or suspend pipes from hanger rods and hangers.

L. Support Spacing:

1. Support 2 inch and smaller piping on horizontal and vertical runs at maximum 5 feet on center, unless otherwise specified.

2. Support larger than 2 inch piping on horizontal and vertical runs at maximum 10 feet on center, unless otherwise specified.

3. Support exposed polyvinyl chloride and other plastic pipes at maximum 5 feet on center, regardless of size.

4. Support tubing, copper pipe and tubing, fiber-reinforced plastic pipe or duct, and rubber hose and tubing at intervals close enough to prevent sagging greater than 1/4 inch between supports.

5. Install support within 2 feet maximum of horizontal and vertical changes in pipe alignment.

M. Install Supports At:

1. Horizontal bends.

2. Both sides of flexible pipe connections.

3. Base of risers.

4. Floor penetrations.

5. Connections to pumps, blowers and other equipment.

6. Valves and appurtenances.

N. Securely anchor plastic pipe, valves, and headers to prevent movement during operation of valves.

O. Anchor plastic pipe between expansion loops and direction changes to prevent axial movement through anchors.

P. Provide ductile iron elbows or tees supported from floors with base fittings where indicated on the Drawings.

Q. Support base fittings with metal supports or when indicated on the Drawings, concrete piers.

R. Size hanger rods, supports, clamps, anchors, brackets, and guides in accordance with ANSI/MSS SP 58 and SP 69.

S. Do not use chains, plumbers' straps, wire, or similar devices for permanently suspending, supporting, or restraining pipes.

T. Support plumbing drainage and vents in accordance with Uniform Plumbing Code.

U. Supports, Clamps, Brackets, and Portions of Support System Bearing Against Copper Pipe: Copper plated, copper throughout, or isolated with neoprene or polyvinyl chloride tape.

V. Where pipe is insulated, install over-sized supports and hangers.

W. Install insulation shield in accordance with ANSI/MSS SP 69, Type 40. Shield shall be

Page 762 of 1480 ends

May, 2026 15061-6 Septage Hauling and Receiving Station Final
stainless steel unless specified elsewhere.

X. Install riser clamps at floor penetrations and where indicated on the Drawings.

Y. Paint or Coat support system components as specified in Sections 09960 or 09910.

END OF SECTION

Page 763 of 1480 ends

May, 2026 15075-1 Septage Hauling and Receiving Station Final
SECTION 15075

MECHANICAL IDENTIFICATION
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Mechanical Identification including the following:

1. Pipe identification by color and legend.

2. Special Items.

3. Identification of equipment and components of systems with paint, brands, tags, and signboards.

B. Related Sections:

1. Section 01600 - Product Requirements.

2. Section 01770 - Closeout Procedures.

3. Section 09960 - High Performance Coatings.

1.02 REFERENCES
A. American National Standards Institute (ANSI):

1. A 13.1 Scheme for the Identification of Piping Systems.

1.03 SUBMITTALS
A. Submit Following:

1. Product Data.

2. Samples.

3. Manufacturer's Installation Instructions.

4. Submit following as specified in Section 01770:
a. Operation and Maintenance Data.
b. Warranty.

1.04 QUALITY ASSURANCE
A. Regulatory Requirements: Comply with CalOSHA.

PART 2 PRODUCTS

2.01 MANUFACTURERS
A. Snap-on Markers: One of following with for up to 4 inch pipe or covering, or 5 inch high letters for 5 inch or larger pipe or cover:

1. Brady Bradysnap-On B-915.

2. Seton Setmark.

2.02 MATERIALS
A. Pipe Markers: Snap on, suitable for outdoor application from -40 degrees to 180 degrees Fahrenheit; meet ANSI A 13.1 requirements.

1. Lettering:

Page 764 of 1480 ends

May, 2026 15075-2 Septage Hauling and Receiving Station Final
Nominal Pipe Diameter Lettering Size
Less than 1.5 ½ inch

1.5 inches to 2 inches ¾ inch

2.5 inches to 6 inches 1-1/4 inches
8 inches to 10 inches 2-1/2 inches
over 10 inches 3-1/2 inches

2. Marker Colors:

Service Lettering Background
Flammables, chemicals, toxics Black Yellow
Water, nontoxic solutions or low
hazard liquids
White Green
Nonflammable or nontoxic gases White Blue
Fire quenching fluids (foam, fire
water, CO2 Halon)
White Red
B. Paint: As specified in Section 09960.

C. Pipe Identification Tags: Aluminum or stainless steel with stamped-in 1/4 inch high identifying lettering.

D. Pipe Identification Tag Chains: Aluminum or stainless steel.

2.03 SPECIAL ITEMS
A. In addition, special painting of following items will be required:

ITEM COLOR
Valve handwheels and levers Red
Hoist hooks and blocks Yellow and black stripes
Steel guard posts In accordance with standard details.

B. Paint minimum 2 inches high numbers on or adjacent to accessible valves, pumps, flow-meters, and other items of equipment which are identified on Drawings or in Specifications by number.

Page 765 of 1480 ends

May, 2026 15075-3 Septage Hauling and Receiving Station Final
PART 3 EXECUTION

3.01 EXAMINATION
A. Verify satisfactory conditions of substrate for applying identification.

B. Verify that conditions are satisfactory for installation and application of products as specified in Section 01600.

3.02 PREPARATION
A. Prepare and paint surfaces as specified in Section 09960.

B. Prepare surface in accordance with product manufacturer's instructions.

3.03 PIPING IDENTIFICATION
A. Identify all exposed piping and valves and piping and valves in accessible chases with lettering or tags designating service of each piping system with flow directional arrows and color code.

1. Coated or Painted Piping 3 inches and larger shall have pipe designation and flow arrows painted onto piping with stencil.

2. Piping 3/4 to 2-1/2 inches shall have snap on markers.

3. Pipe smaller than 5/8 shall have metal tag markers

4. All Insulated piping have snap on markers over the insulation jacket.

5. Chemical piping shall have snap on markers or metal tags.

B. Color Code:

1. Paint piping scheduled to be color coded completely with specified colors.

2. Paint segments of pipe specified to be unpainted with specified coding color long enough to accommodate required lettering and arrows.

C. Paint piping specified to be painted to match adjacent surfaces, unless otherwise directed.

D. Lettering and Flow Direction Arrows:

1. Stencil lettering on painted bands or use snap-on markers on pipe to identify pipe.

When stenciling, stencil 3/4 inch high letters on 3/4 through 4 inch pipe or coverings, or 5 inch high letters on 5 inch and larger pipe or coverings.

2. Provide lettering and flow direction arrows near equipment served, adjacent to valves, both sides of walls and floors where pipe passes through, at each branch or tee, and at intervals of not more than 50 feet in straight runs of pipe.

E. Where scheduled, space 6 inch wide bands along stainless steel pipe at 10 foot intervals and other pipe at 5 foot intervals.

F. Label chemical tank fill pipelines at locations which are visible from chemical fill stations.

G. Metal Tags:

1. Where outside diameter of pipe or pipe covering is 5/8 inch or smaller, provide metal pipe identification tags instead of lettering.

2. Fasten pipe identification tags to pipe with chain.

3. Where tags are used, color code pipe as scheduled.

Page 766 of 1480 ends

May, 2026 15075-4 Septage Hauling and Receiving Station Final

3.04 APPLICATION
A. Identify piping with legend markers, directional arrow markers, and number markers; use self adhesive arrow roll tape to secure ends of piping markers and indicate flow direction.

B. Provide legend markers, directional arrow markers and number markers where piping passes through walls or floors, at piping intersections and at maximum 15 foot spacing on piping runs.

C. Provide piping marker letters and colors as scheduled.

D. Place markers on piping so they are visible from operator's position in walkway or working platform near piping. Locate markers along horizontal centerline of pipe, unless better visibility is achieved elsewhere.

3.05 PIPING COLOR CODE AND MARKER SCHEDULE
Service Fluid Pipe Color Marker Legend
Drain Dark Brown Drain
Plant Water (lines downstream
from backflow prevention unit
Dark Purple PW

END OF SECTION

Page 767 of 1480 ends

May, 2026 15111-1 Septage Hauling and Receiving Station Final
SECTION 15111

BALL VALVES
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Metal body ball valves and plastic body ball valves.

B. Related Sections:

1. Section 13445B - Pneumatic Controllers and Control Valves.

1.02 REFERENCES
A. American Water Works Association (AWWA):

1. C 507 Standard for Ball Valves 6 Inch Through 48 Inch.

1.03 SYSTEM DESCRIPTION
A. General: Unless otherwise indicated on the Drawings use:

1. Metal body ball valves on metal pipelines,

2. Plastic body ball valves on plastic pipelines,

1.04 SUBMITTALS
A. Product Data.

B. Certifications:

1. Metal Body Ball Valves: Submit affidavit of compliance with AWWA C 507.

2. Sludge Cake Ball Valves: Submit affidavit of satisfactory completion of shell test and seat test.

1.05 WARRANTY
A. As specified in Section 15050.

PART 2 PRODUCTS

2.01 METAL BODY BALL VALVES
A. Manufacturers: One of the following or equal:

1. Lunkenheimer Company.

2. MARPAC, Inc.

B. General.

1. Type: Non-lubricated, and capable of sealing in either flow direction.

2. Conform to AWWA C 507.

3. Stem Packing: Manually adjustable while valve is under pressure.

4. Temperature Limits: Suitable for operation between minus 20 and 350 degrees Fahrenheit.

C. Materials:

Page 768 of 1480 ends

May, 2026 15111-2 Septage Hauling and Receiving Station Final

1. Valves in Copper Lines: Bronze body with solder ends.

2. Valves in Ductile Iron Piping: Ductile iron or cast steel bodies

3. Valves in Stainless Steel Piping: 316 Stainless steel bodies and ball.

4. Ends as follows:
a. Threaded for sizes 3 inch and smaller.
b. Flanged for sizes larger than 3 inch.

5. Ball: Type 304 or Type 316 stainless steel.

6. Seats: TFE.

7. Stem Seals: TFE or Viton.

2.02 PLASTIC BODY BALL VALVES
A. Manufacturers: One of the following or equal:

1. Asahi America.

2. Chemtrol Division, NIBCO Inc.

3. Spears
B. General:

1. Type: Non-lubricated and capable of sealing in either flow direction and manufactured per ASTM F 1970

2. End Connections: True union.

3. Operator Handle: High Impact Polypropylene Handle
C. Materials:

1. Body: Schedule 80 Chlorinated Polyvinyl chloride (CPVC) full bore design.

2. Ball: Chlorinated Polyvinyl chloride (CPVC).

3. Seats: PTFE (Teflon).

4. O-rings: EPDM
PART 3 EXECUTION

3.01 INSTALLATION
A. Follow manufacturer's published instructions.

END OF SECTION

Page 769 of 1480 ends

May, 2026 15115-1 Septage Hauling and Receiving Station Final
SECTION 15115

GATE, GLOBE, AND ANGLE VALVES
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Gate, globe, angle, plug disc and plain hose valves, and yard hydrants.

B. Related Sections:

1. Section 15110 - Valves.

1.02 REFERENCES
A. American Society for Testing and Materials (ASTM):

1. B 98 - Specification for Copper-Silicon Alloy Rod, Bar and Shapes.

B. American Water Works Association (AWWA):

1. C 500 - Standard for Metal-Seated Gate Valves for Water Supply Service (includes addendum C500a-95).

2. C 509 - Standard for Resilient-Seated Gate Valves for Water-Supply Service (includes addendum C509a-95).

1.03 WARRANTY
A. As specified in Section 15050.

PART 2 PRODUCTS

2.01 GATE VALVES
A. Gate Valves Aboveground:

1. Valves less than 3 Inches in Size for Clean Water and Air Service: Manufacturer's standard bronze, solid wedge disc, rising stem, screwed end, Class 150 pounds. a. Manufacturers: One of the following or equal:
1) Crane, Figure 431.
2) Jenkins, Figure 47.
3) Lunkenheimer Company, Figure 2151.

2. Valves 3 Inches in Size and Larger: Flanged 200 pound iron body; bronze mounted; outside screw and yoke (OS&Y); double disc; parallel seat; with stems of silicon bronze in accordance with ASTM B 98, Alloy No. C 66100; and handwheel. a. Manufacturers: One of the following or equal:
1) M&H Valve Company, Figure 68-02.
2) Mueller, A-2483-6.

B. Gate Valves Underground:

1. Valves 3 Inches through 12 Inches in Size for Underground Service: Iron body, resilient seat, non-rising stem, double O-ring stem seal, in accordance with AWWA C 509.
a. Manufacturers: One of the following or equal:
1) M&H Valve Company.

Page 770 of 1480 ends

May, 2026 15115-2 Septage Hauling and Receiving Station Final
2) Mueller Company.

2. Valves 14 Inch Size and Larger for Underground Service: Double disc, parallel seat, iron body, bronze mounted, non-rising stem (NRS) in accordance with AWWA C 500.
a. Manufacturers: One of the following or equal:
1) M&H Valve Company.
2) Mueller Company.

C. Steam and Condensate Gate Valves:

1. Valves 3 Inches and Smaller in Size: Bronze, screwed, rising stem, solid wedge, screwed bonnet, suitable for service under pressures equal to and less than 125 pounds per square inch gauge, steam working pressure (SWP). a. Manufacturers: One of the following or equal:
1) Crane, No. 428.
2) Jenkins, Figure 47U.
3) Lunkenheimer Company, Figure 2127.

2. Valves Larger than 3 Inches in Size: Suitable for service under pressures equal to and less than 125 pounds per square inch gauge, steam working pressure (SWP), flanged, iron body, bronze mounted, solid wedge, outside screw and yoke (OS&Y). a. Manufacturers: One of the following or equal:
1) Crane No. 465-1/2.
2) Jenkins, Figure 651C.
3) Lunkenheimer Company, Figure 1430.

D. Stainless Steel Knife Gate Valves for FOG service

1. Size: 4 inch

2. Cast 316 stainless steel body and packing gland

3. 316 Stainless steel gate and stem.

4. 304 Stainless steel Yoke.

5. Bi-directional resilient seated valve.

6. Seat material: EPDM to 250°F.

7. Pressure rating 150 psi. C.W.P.

8. Lug connections.

9. Actuator: Stainless Steel Manual lever.
a. Manufacturers: One of the following or equal
1) Dezurik KGN-RSB
2) Valtorc Series 4200
3) Velan

2.02 GLOBE AND ANGLE VALVES
A. General Purpose Globe and Angle Valves:

1. Valves 3 inches and smaller:
a. Manufacturers: One of the following or equal except in welded steel piping:
1) Crane, No. 1 Globe or No. 2 Angle.
2) Lunkenheimer Company Figure No. 2140 Globe or No. 2141 Angle. b. Design:
1) Valve: Class 125 threaded ends, rated for 250 degrees Fahrenheit at pressure of 170 pounds per square inch.
c. In Welded Steel Piping: One of the following or equal:
1) Crane, No. 351.
2) Lunkenheimer Company, Figure No. 1123; or equal with flanged ends.

2. Valves Larger than 3 Inches:
a. Manufacturers: One of the following or equal:

Page 771 of 1480 ends

May, 2026 15115-3 Septage Hauling and Receiving Station Final
1) Crane, No. 351.
2) Lunkenheimer Company, Figure No. 1123.

3. Plug Disc Globe Valves:
a. Manufacturers: One of the following or equal:
1) Crane, No. 212P or No. 384P.
2) Lunkenheimer Company, 72-PS or 73-PS1.
b. Plug disc globe or angle valves specified in the Specifications or indicated on the Drawings for throttling or for severe service: Iron body stainless steel trimmed plug type seat and disc.

4. Needle Valves:
a. Manufacturers: One of the following or equal:
1) Powell, Figure No. 180.
2) Lunkenheimer Company, Figure No. 906-BS or No. 907-BS. 3) Crane No. 88 or No. 89.
b. Valves for Metering: As recommended by the meter manufacturer and furnished with the meters.

5. Globe or Angle Hose Valves:
a. Manufacturers:
1) Globe Threaded Valve: One of the following or equal:
a) Crane, No. 7TF.
b) Stockham, Figure No. B22T.
2) Angle Threaded Valve: One of the following or equal:
a) Crane, No. 17TF.
b) Stockham, Figure No. B222T.
b. Design:
1) Valve: Globe or angle valve with threaded ends size 1/8 inch to 3 inches in diameter, size as indicated on the Drawings.
2) Disc: Renewable, made of teflon or Buna-N.
3) Class 150 threaded ends, rate for 200 degrees Fahrenheit at a pressure of 270 pounds per square inch.

6. Freezeless Yard Hydrant:
a. Manufacturers: One of the following or equal:
1) Josam, Series 71700.
2) Zurn, Z-1385.

PART 3 EXECUTION

3.01 INSTALLATION
A. Install valves in accordance with Section 15110.

B. Mount yard hydrants on iron pipe risers minimum 1 inch nominal diameter or size indicated on the Drawings.

END OF SECTION

Page 772 of 1480 ends
Page 773 of 1480 ends

May, 2026 15120-1 Septage Hauling and Receiving Station Final
SECTION 15120

PIPING SPECIALTIES
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Piping specialties including:

1. Flexible rubber connections.

2. Expansion joints.

3. Vibration control joints.

4. Pipe saddles.

5. Tapping sleeves.

6. Surge cushions.

7. Sight glasses.

8. Pressure gauges.

9. Thermometers.

10. Mechanical Variable Area Vane Type Flow Meters
B. Related Sections:

1. Section 11388 - Digester Gas Manometers.

2. Section 15052 - Basic Piping Materials and Methods.

1.02 REFERENCES
A. American National Standards Institute/American Society of Mechanical Engineers (ANSI/ASME).

B. American National Standards Institute/American Water Works Association (ANSI/AWWA):

1. ANSI/AWWA C153/A21.53 - Ductile-iron Compact Fittings.

2. ANSI/AWWA C111/A21.11 - Rubber Gasket Joints for Ductile-iron and Gray-iron Pressure Pipe and Fittings.

3. ANSI/AWWA C110/A21.10 - Ductile-iron and Gray-iron Fittings.

4. ANSI/AWWA C213 - Fusion-bonded Epoxy Coatings and Linings for Steel Water Pipelines.

5. ANSI/AWWA C151/A21.51 - Ductile-iron Pipe, Centrifugally Cast.

C. American Society for Testing and Materials (ASTM).

1. ASTM A148 - Specification for steel castings, high- Strength, for Structural Purposes.

2. ASTM A536 - Specification For Ductile Iron Castings.

D. Society of Automotive Engineers (SAE).

1.03 SUBMITTALS
A. Assemblies:

1. Manufacturer's certificate attesting successful performance of specified steam test.

2. Shop drawings detailing dimensions and materials.

3. Manufacturer's published installation instructions.

4. Operation and maintenance manuals.

Page 774 of 1480 ends

May, 2026 15120-2 Septage Hauling and Receiving Station Final

1.04 DELIVERY, STORAGE, AND HANDLING
A. Expansion Joints and Vibration Control Joints:

1. Protect joint bellows and sliding surfaces against damage during packing, shipping and installation, and also during pressure test.

2. Lock expansion joints against movement until pressure tests are completed.

3. Replace damaged expansion joints with new and undamaged expansion joints.

B. Ball-Type Flexible Expansion Joints:

1. Protect joint bellows and sliding surfaces against damage during packing, shipping, and installation.

2. Lock expansion joints against movement until installation is completed.

3. Do not repair but discard damaged expansion joints and in their place provide new and undamaged flexible expansion joints.

1.05 MAINTENANCE
A. Extra Materials: Furnish 4 complete spare sets of gaskets for each size and type of ball joint.

1.06 WARRANTY
A. As specified in Section 15050.

PART 2 PRODUCTS

2.01 FLEXIBLE RUBBER CONNECTIONS
A. Manufacturers: One of the following or equal:

1. Mercer Rubber Company, Type 150 Vibraflex.

B. Provide flexible rubber connections with 3/8 inch thick EPDM rubber tube with full faced flanged ends suitable to withstand a pressure of 150 pounds per square inch gauge.

C. Provide complete flexible rubber connections, including galvanized retaining rings and control rods.

2.02 EXPANSION JOINTS
A. Expansion Joints for Steam:

1. Manufacturers: One of the following or equal:
a. Flex-Weld, Inc., Keflex, Series 308-1215.
b. Flexonics, Inc., Controlled Flexing Expansion Joint.

2. Design:
a. Flexible bellows type.
b. Pressure and Temperature Ratings: 150 pounds per square inch gauge, and 500 degrees Fahrenheit service.
c. Bellows: Laminated Type 321 stainless steel, equipped with a Type 321 stainless steel liner.
d. Axial Travel of Expansion Joints: 3 inches, minimum. e. Ends: 150 pound ANSI flanges.

B. Rubber Expansion Hot Water, Sludge, and Air Service:

Page 775 of 1480 ends

May, 2026 15120-3 Septage Hauling and Receiving Station Final

1. Manufacturers: One of the following or equal:
a. Mercer Rubber Company, Style 500.

2. Provide rubber expansion joints complete with control rods and split retaining rings.

3. Design:
a. Material: EPDM, reinforced with embedded steel rings, and a strong synthetic fabric.
b. Single Arch Expansion Joints for Air and Sludge Service, 1) Pressure Rating: Suitable for continuous operation at a pressure of at least 250 Pounds per square inch gauge.
2) Vacuum Rating: Suitable for a vacuum of 30 inches of mercury 3) Temperature Rating: Minimum continuous operation at 250°F. 4) Axial Extension: 1/2"
5) Axial Compression: 3/4"
6) Split retaining rings, stainless steel.
7) Ends of expansion joints, stainless steel 150 pound ANSI flanges with drilling to match that of the piping.
c. Dual Arch Expansion Joints for Hot Water service,
1) Pressure Rating: Suitable for continuous operation at a pressure of at least 180 Pounds per square inch gauge.
2) Vacuum Rating: Suitable for a vacuum of 30 inches of mercury 3) Temperature Rating: Minimum continuous operation at 250°F. 4) Axial Extension: 1"
5) Axial Compression: 1-1/2""
6) Split retaining rings, stainless steel.
7) Ends of expansion joints, stainless steel 150 pound ANSI flanges with drilling to match that of the piping.

C. Rubber Expansion Digester Gas and Chemical Service:

1. Manufacturers: One of the following or equal:
a. Mercer Rubber Company, Style 700.

2. Provide rubber expansion joints complete with control rods and split retaining rings.

3. Design:
a. Material: EPDM with Teflon liner etched and permanently bonded to the expansion joint body and flange faces, reinforced with embedded steel rings, and a strong synthetic fabric.
b. Coating: Hypalon paint to provide protection against ozone, weathering, and chemical exposure.
c. Single Arch Expansion Joints for Digester Gas and Chemical service, 1) Pressure Rating: Suitable for continuous operation at a pressure of at least 150 Pounds per square inch gauge.
2) Vacuum Rating: Suitable for a vacuum of 30 inches of mercury 3) Temperature Rating: Minimum continuous operation at 250°F. 4) Split retaining rings, stainless steel.
5) Ends of expansion joints, stainless steel 150 pound ANSI flanges with drilling to match that of the piping.

D. Copper Piping Expansion Joints:

1. Expansion Joints for Copper Pipe: As specified before, except externally guided, without equalizing rings, and provide for 3-1/4 inch expansion per 100 feet of piping.

Page 776 of 1480 ends

May, 2026 15120-4 Septage Hauling and Receiving Station Final

2.03 VIBRATION CONTROL JOINTS
A. Manufacturers:

1. Braided Bronze Flexible Vibration Joints 2 Inches and less in Size: One of the following or equal:
a. Flexonics, Inc., Type Vibra Sorber.
b. Flex-Weld, Inc, Keflex, Type KFCB.

2. Flexible Vibration Joints Larger than 2 Inches: One of the following or equal:
a. Flexonics, Inc., Type TCS.
b. Flex-Weld, Inc., Keflex, Series 151-TR-1215.

3. Corrugated Stainless Steel with Stainless Steel Braid Flexible Vibration Joints:

One of the following or equal:
a. Flexonics, Inc., Type FCS.
b. Flex-Weld, Inc., Keflex, Type USFNSS-31.

B. Design:

1. Flexible Vibration Joints 2 Inches and Smaller: Braided bronze, suitable for pressures of not less than 250 pounds per square inch gauge.

2. Flexible Vibration Joints Larger than 2 Inches: Flexible bellows type, suitable for pressures of not less than 150 pounds per square inch gauge, at 70 degrees Fahrenheit, except as follows:
a. Provide vibration joints in piping subject to test pressures higher than 150 pounds per square inch gauge, suitable for such higher pressures. b. Bellows: Stainless steel, equipped with a stainless steel liner. c. Ends: ANSI Class 150 flanges.

3. Vibration Joints in High Pressure Air Piping and in Digester Gas Piping:

Corrugated Type 316 stainless steel with stainless steel braid, suitable for pressures of not less than 150 pounds per square inch gauge. a. Ends: ANSI Class 150 flanges.

C. Protection: Protect vibration absorbers against end loading and torsional stresses by anchoring attached piping.

2.04 PIPE SADDLES
A. Manufacturers: One of the following or equal:

1. BTR Inc./Smith-Blair, Inc., Style 317.

2. Romac Industries, Inc., Style 202S.

B. Materials:

1. Pipe Saddles: Ductile iron.

2. Straps, Bolts, and Nuts: Type 304 stainless steel with Teflon coating on nuts.

3. Gaskets: EPDM.

2.05 TAPPING SLEEVES
A. Manufacturers: One of the following or equal:

1. BTR Inc./Smith-Blair, Inc., Style 622.

2. Romac Industries, Inc., Style FTS 420.

B. Materials:

1. Tapping Sleeves: Steel construction.

2. Bolts and Nuts: Type 304 stainless steel.

3. Nuts: Teflon coated.

Page 777 of 1480 ends

May, 2026 15120-5 Septage Hauling and Receiving Station Final

4. Gaskets: EPDM.

5. Size of Tapped Boss: As indicated on the Drawings.

2.06 SIGHT GLASSES
A. Assembly: Body casting with ANSI standard adapter flanges, Pyrex glass section, cleaning assembly with scalloped neoprene wipers, operating rod and handle, packing gland with packing and suitable adapter, and cock with solvent hand pump.

B. Suitable for a minimum pressure of 30 pounds per square inch gauge.

C. Manufacturers: One of the following or equal:

1. EIMCO Process Machinery Division of Envirotech Corporation.

2. Ernst, Type K2 or K3 Cleanable Sight Glass.

2.07 PRESSURE GAUGES
A. Design:

1. Provide dual-range, liquid filled gauges with ranges as indicated on the Drawings.

2. Size: As follows, unless otherwise indicated on the Drawings or specified:
a. For 1 Inch Pipe and Larger: 4-1/2 inch diameter.
b. For Smaller than 1 Inch Pipe: 2-1/2 inch diameter.

3. Provide gauges with back flanged aluminum cases with threaded ring, except for panel mounting, in which case provide gauge with front flanged aluminum case with threaded ring. Apply black epoxy coating to cases.

4. Provide case fitted with a rupture disc which shall relieve out the back of the case.

5. Window: Shatterproof glass or high temperature acrylic.

6. Provide gauges with Type 316 stainless steel socket and bellows or bourdon tube, depending on pressure range.
a. Where the maximum pressure is less than or equal to 15 pounds per square inch the gauge shall use bellows as the measuring element. b. Where the maximum pressure is greater than 15 pounds per square inch, the measuring element shall be a bourdon tube.

7. Socket Tips:
a. Socket Tips for Bellows and Bourdon Tube: Type 316 Stainless steel. b. Size: 1/2 inch for 4-1/2 inch diameter gauges, 1/4 inch for 2-1/2 inch diameter gauges.

8. Mount gauges on diaphragm seals where indicated on the Drawings. a. Provide diaphragm seals with Type 316 stainless steel top housing, bottom housing, and bolt assemblies.
1) Bottom housing shall be fitted with a 1/4 inch flushing connection. 2) This flushing connection shall be fitted with a Type 316 stainless steel close nipple and a brass shutoff cock.
3) Diaphragm Seal: Removable.
a) For pressure less than or equal to 15 pounds per square inch, provide viton diaphragm seal.
b) For pressures greater than 15 pounds per square inch, provide Type 316 stainless steel diaphragm seal.
b. Fit diaphragm seal gauge assembly with a snubber.
1) Snubber shall have porous metal disc sized to dampen pressure fluctuations in the filled system.
2) Snubber: Stainless steel.
3) Snubber filter disc shall be sized to prevent the gauge from pulsating. c. Provide diaphragm seal gauge assemblies filled with silicon.

Page 778 of 1480 ends

May, 2026 15120-6 Septage Hauling and Receiving Station Final

9. Pressure gauges, except gauges with diaphragm seals, shall have pulsation dampeners installed between the gauge and the shut-off valve. a. Pulsation Dampeners: Stainless steel.

10. Mount gauges on pressure ring where indicated on the Drawings. a. Suitable for sludge, fats, oils, grease, and food waste materials. b. Design:
1) Full port design rated for 300 psig.
2) Sense pressure on 360 degrees around the inner ring. 3) Prevent plugging or fouling of sensor.
4) All areas exposed to process fluid covered with elastomer. 5) Bolt Through or Flange connection to Pipe Flange.
6) Drill to 125#/150# ANSI standard.
c. Materials:
1) Sensor Body: stainless steel.
2) Body Trim: Stainless Steel.
3) Flexible Liner / Diaphragm: EPDM
B. Manufacturers:

1. Pressure Gauges: One of the following or equal:
a. U.S. Gauge Division of Ametek, Inc., Solfrunt Gauges, Figure Number 1931T. b. Dresser Industries, Inc., Ashcroft Figure Number 1379.

2. Pressure Gauges for Digester Gas Systems: One of the following or equal:
a. Dresser Industries, Inc.
b. Ashcroft, Figure 1179 compound gauge.

3. Diaphragm Seal: One of the following or equal:
a. For pressure less than or equal to 15 pounds per square inch:
1) Ashcroft, Type 301.
2) Mansfield and Green, Type LG.
b. For pressures greater than 15 pounds per square inch:
1) Ashcroft, Type 101.
2) Mansfield and Green, Type RG.

4. Snubber: One of the following or equal:
a. Chemiquip, Ashcroft.

5. Pulsation Dampeners: One of the following or equal:
a. Dresser Industries, Inc., Ashcroft Figure Number 1106S. b. Operation and Maintenance Specialties, Charlotte, N.C., Ray Pressure Snubbers.

6. Pressure Rings: one of the following or equal.
a. Ashcroft Type 81.
b. Red Valve series 48.

2.08 THERMOMETERS
A. Tube Type Thermometers:

1. 9 inch size with adjustable angle from temperature well.

2. Type 316 stainless steel separable sockets with extension necks on insulated pipes and where indicated on the Drawings.

3. Range indicated on the Drawings.

4. Manufacturers: One of the following or equal:
a. H.O. Trerice Company, Series BX9.
b. Jay Instruments Company.

B. Bimetallic Type Thermometers:

1. Scales graduated in degrees Fahrenheit.

Page 779 of 1480 ends

May, 2026 15120-7 Septage Hauling and Receiving Station Final

2. 5 inch diameter dials.

3. Heads capable of being rotated 360 degrees and titled 180 degrees.

4. Type 304 stainless steel construction.

5. Shatterproof glass.

6. Stem length as necessary for the installation conditions; 4 inch minimum.

7. Accuracy: plus or minus 1.0 percent of full scale with external adjustment.

8. Manufacturers: One of the following or equal:
a. Ametek, U.S. Gauge Division, Figure 6530.
b. Dresser Industries, Ashcroft Instrument Division, EI Everyangle.

2.09 MECHANICAL VARIABLE AREA VANE TYPE FLOW METERS
A. Mechanical variable area vane type flow meter with mechanical display.

1. Universal Flow Monitors MN or LN Series based on flow range.

2. MN series for flows less than 100 gpm.

3. LN series for flows greater than 100 gpm.

4. Suitable for water service.

5. Maximum pressure drop at maximum flow MN series 5 psig, LN series 3.8 psig.

6. Brass housing with nylon flow chamber, Stainless Steel internal parts, EPR seals pressure range 0 to 150 psig and up to 210°F service water temperature.

7. In-line type suitable for mounting vertical or horizontal.

8. Individually calibrated for the service fluid.

9. Display flow in gallons per minute.

10. Flow range as indicated on the Drawings or specified elsewhere.

PART 3 EXECUTION

3.01 INSTALLATION
A. Expansion and Vibration Control Joints:

1. Prevent equipment vibration transmitted through piping system, and prevent damaging stresses due to normal expansion and contraction with temperature changes in piping and connected equipment.
a. Where anticipated expansion is greater than can be absorbed by the normal piping configuration, install loops, bends, and expansion joints as indicated on the Drawings, to absorb excess expansion.

2. Install expansion joints so as to allow 2-1/4 inch expansion per 100 linear feet of piping.

3. Where possible, install expansion joints adjacent to an anchor, and provide one concentric guide on piping within 12 pipe diameters, but not more than 5 feet, from the end of the joint opposite the anchor.
a. Locate a similar guide approximately 30 diameters but not more than 10 feet from the first.

4. For expansion joints not installed adjacent to an anchor provide 2 concentric guides similarly located at each end of the joint.

5. Provide control rods and additional guides where indicated on the Drawings, but at no greater intervals than recommended by the joint manufacturer in published instructions.

6. Space intermediate supports a minimum of 10 feet, and tack weld the protective saddles to the pipe.

B. Expansion Joints for Steam Cleaned Piping:

1. Install no less than one expansion joint in a run of steam cleaned piping which exceeds 20 feet in length. Do not exceed 200 feet in spacing of expansion joints.

Page 780 of 1480 ends

May, 2026 15120-8 Septage Hauling and Receiving Station Final

2. Install expansion joints in steam cleaned piping between anchors.

C. Expansion Joints for Steam and Hot Water:

1. Install not less than 1 expansion joint in a run of steam or hot water piping which exceeds 20 feet in length. Do not exceed 150 feet spacing of expansion for steam piping and 200 feet for hot water piping.

2. Where possible, install expansion joints adjacent to an anchor; provide piping with 2 concentric guides, the first being within 2 feet of the end of the joint opposite the anchor.

3. At expansion joints not installed adjacent to an anchor, provide 2 concentric guides on piping within 2 feet off both ends of the expansion joint.

4. Lock expansion joint against movement until pressure test is completed.

D. Vibration Control Joints:

1. For piping running to or from mechanical equipment, provide flexible vibration joint at equipment connection.

E. Pipe Saddles:

1. Coat threads on bolts with anti-gall coating prior to installation.

F. Tapping Sleeves:

1. Coat threads on bolts with anti-gall coating prior to installation.

G. Pressure Gauges:

1. Install pressure and compound gauges as indicated on the Drawings, in the Pressure Gauge Schedule, and as specified.

2. Install gauges as specified, and as recommended by the manufacturer in published instructions.

H. Thermometers:

1. Drill and tap piping for the thermometers as generally indicated on the Drawings.

Select final position in the field with the objective of achieving best readability.

I. Mechanical Flow Meters

1. Install per manufacturer’s instructions. Orient so flow is easily visible by operators.

3.02 FIELD QUALITY CONTROL
A. Testing: Field test gauges with a calibrated test gauge, in the presence of ENGINEER.

END OF SECTION

Page 781 of 1480 ends

May, 2026 15121-1 Septage Hauling and Receiving Station Final
SECTION 15121

FLEXIBLE COUPLINGS
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Flexible couplings.

B. Related Sections:

1. Section 15052 - Basic Piping Materials and Methods.

1.02 REFERENCES
A. American National Standards Institute/American Society of Mechanical Engineers (ANSI/ASME).

B. American Society for Testing and Materials (ASTM).

C. Society of Automotive Engineers (SAE).

1.03 SUBMITTALS
A. Shop drawings detailing dimensions and materials.

B. Manufacturer's published installation instructions.

1.04 WARRANTY
A. As specified in Section 15050.

PART 2 PRODUCTS

2.01 FLEXIBLE COUPLINGS
A. Line and coat flexible couplings, except for stainless steel flexible couplings, with fusion-bonded epoxy of minimum 0.012 inches thickness.

B. Flexible Couplings Used for Connecting Piping Having Different Outside Diameters:

Use products specifically designed and manufactured for that application.

C. Gaskets for Flexible Couplings:

1. Air Piping: EPDM.

2. Piping Other than Air Piping: EPDM.

D. Manufacturers:

1. Flexible Couplings in Steel and Ductile Iron Piping: One of the following or equal, except where other types are required for particular applications:
a. Dresser Industries, Inc. Style 38.
b. Smith-Blair, Inc., Series 441.
c. Romac Industries, Inc., Style 400.

2. Flanged Coupling Adapters in Steel Piping: One of the following or equal:

Page 782 of 1480 ends

May, 2026 15121-2 Septage Hauling and Receiving Station Final
a. Dresser Industries, Inc., Style 128.
b. Smith-Blair, Inc., Series 913.
c. Romac Industries, Inc., Style FCA501.

PART 3 EXECUTION

3.01 INSTALLATION
A. In underground and underwater installations, coat the coupling exterior after installation with a protective coating.

1. Manufacturers: One of the following or equal:
a. Tapecoat Company, Inc., T.C. Mastic.
b. Kop-Coat Company, Inc., Bitumastic Number 50.

2. Thickness: Minimum 0.040 inch.

B. Where flexible couplings are installed underground or underwater, provide Type 316 stainless steel bolts.

C. Provide joint harnesses for flexible couplings unless otherwise indicated on the Drawings with a written note.

1. Design joint harnesses on steel and stainless steel piping for the test pressures specified with the Piping Schedule in Section 15052.

END OF SECTION

Page 783 of 1480 ends

May, 2026 15251-1 Septage Hauling and Receiving Station Final
SECTION 15251

DUCTILE IRON PIPING
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Ductile iron piping, joints, fittings, gaskets, and pipe lining and coating.

B. Related Sections:

1. Section 02318 - Trenching.

2. Section 09960 - High Performance Coatings

3. Section 15052 - Basic Piping Materials and Methods.

1.02 REFERENCES
A. American National Standards Institute/American Society of Mechanical Engineers (ANSI/ASME):

1. B 16.1 - Cast Iron Pipe Flanges and Flanged Fittings.

B. American Society for Testing and Materials (ASTM):

1. A 47 - Specifications for Ferritic Malleable Iron Castings.

2. A 183 - Specifications for Carbon Steel Tank Bolts and Nuts.

3. A 283 - Specifications for Low and Intermediate Tensile Strength Carbon Steel Plates.

4. A 536 - Ductile Iron Castings.

5. A 674 - Practice for Polyethylene Encasement for Ductile Iron Pipe for Water or Other Liquids.

6. D 792 - Test Methods for Density and Specific Gravity (Relative Density) of Plastics by Displacement.

7. D 1248 - Specifications for Polyethylene Plastics Molding and Extrusion Materials.

C. American Water Works Association (AWWA):

1. C 104 - Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water.

2. C 105 - Polyethylene Encasement for Ductile-Iron Pipe Systems.

3. C 110 - Ductile-Iron and Gray-Iron Fittings, 3 Inches Through 48 Inches, for Water and Other Liquids.

4. C 111 - Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings.

5. C 115 - Flanged Ductile-Iron Pipe with Ductile-Iron or Gray-Iron Threaded Flanges.

6. C 150 - Thickness Design of Ductile-Iron Pipe.

7. C 151 - Ductile-Iron Pipe, Centrifugally Cast, for Water or Other Liquids.

8. C 153 - Ductile-Iron Compact Fittings, 3 Inches Through 24 Inches, and 54 Inches Through 64 Inches, for Water Service.

9. C 600 - Installation of Ductile-Iron Water Mains and Their Appurtenances.

10. C 606 - Grooved and Shouldered Joints.

1.03 SUBMITTALS
A. Shop Drawings:

1. Detailed layout drawings showing alignment of pipes, location of valves, fittings, and appurtenances, types of joints, connections to structures and thrust restraint

Page 784 of 1480 ends

May, 2026 15251-2 Septage Hauling and Receiving Station Final
system layouts.

2. Thrust Restraint Systems: Layouts and supporting calculations for restrained joint thrust restraint systems.

B. Pipe Design Calculations: Calculations for required wall thickness in accordance with AWWA C 150.

C. Product Data: Photographs, drawings, and descriptions of fittings, gaskets, couplings, grooving of pipe and fittings, pipe linings, and coatings.

D. Test Reports:

1. Manufacturer's test reports for lining certifying successful performance of the wet sponge spark tests.

2. Manufacturer’s test results for glass lined pipe certifying compliance with specified material requirements for glass lining.

E. Certificates: Submit certified documentation of holiday detection testing results with all glass lined pipe shipments. This documentation shall identify each piece by mark designation and show the actual test results during the final inspection by the manufacturer prior to shipment. Acceptance criteria shall be as specified under Field Quality Control.

1.04 DELIVERY, STORAGE, AND HANDLING
A. Block piping material for shipment, prevent damage to castings and linings.

B. Carefully handle piping material during loading, unloading, and installation. Do not drop piping material from cars or trucks. Lower piping material by mechanical means. Do not drop or pound pipe to fit grade.

C. Repair damaged cement mortar lining to match quality, thickness, and bonding of original lining in accordance with AWWA C 104. When lining cannot be repaired or repairs are defective, replace defective piping with undamaged piping.

D. Protect gaskets and polyethylene encasement from long term exposure to sunlight.

E. Store fittings and other accessories such that they do not accumulate and hold rainwater, dirt, and debris.

1.05 QUALITY ASSURANCE
A. Qualifications of Lining Manufacturers: For piping specified to receive glass lining or polyethylene lining use only a manufacturer having a minimum of 5 years experience supplying this type of product to the wastewater and water treatment industry.

B. Regulatory Requirements: Install work of this Section in accordance with local, state, and federal regulations.

1.06 THRUST RESTRAINT SYSTEM DESIGN
A. Assume responsibility for the restrained joint thrust restraint system design.

B. Determine the length of pipe that must be restrained on each side of the focus of a thrust load in accordance with the procedures and criteria established by the Ductile

Page 785 of 1480 ends

May, 2026 15251-3 Septage Hauling and Receiving Station Final
Iron Pipe Research Association (DIPRA) and the following additional criteria:

1. Design Pressure: Test pressure or 100 pounds per square inch, whichever is greater.

2. Laying Condition: Type 3 as defined by AWWA C150.

3. Soil Type: as defined by geotechnical report.

4. Unit Friction Resistance: Based upon polyethylene encasement of pipe.

5. Safety Factor: 1.5 (for thrust restraint calculations only).

PART 2 PRODUCTS

2.01 MATERIALS
A. Ductile Iron Piping:

1. Type, Typical: AWWA C 150 and AWWA C 151 with minimum pressure class wall thickness that meets project pressure and structural requirements, unless otherwise specified or indicated on the Drawings.

2. Type with Screw-on Flanges: AWWA C 115 with minimum special thickness Class 53 wall thickness that meets project pressure and structural requirements, unless otherwise specified or indicated on the Drawings.

3. Laying Condition: Type 3 as defined by AWWA C 150.

B. Joints:

1. Flanged Joints:
a. Flanges, Screw-on: Comply with the diameter, thickness, drilling, and other characteristics in accordance with ANSI B 16.1. In addition, comply with the following requirements:
1) Ductile iron.
2) Long hub, threaded, and specially designed for ductile iron pipe. 3) After attaching to pipe, machine flange face to make pipe end and flange even and perpendicular to the axis of the pipe.
b. Bolt Holes on Flanges: 2-holed and aligned at both ends of pipe. c. Cap Screw or Stud Bolt Holes: Tapped.
d. Bolts and Nuts: As specified in ANSI/ASME B 16.1 except when connecting flanges underground, in concrete pipe valve boxes, or underwater, use Type 304 or Type 316 stainless steel. Cut and finish bolts to project a maximum of 1/4 inch beyond nut when joints are assembled. e. Gaskets: As specified in Section 15052.

2. Mechanical Joints: In accordance with AWWA C 111/ANSI A 21.11.

3. Restrained Mechanical Joints:
a. Design: Integral retainer weldment type or lugged type joint with Type 304 stainless steel rods and nuts.
b. Manufacturers: One of the following or equal:
1) Pacific States Cast Iron Pipe Company, Lock Mechanical Joint. 2) American Cast Iron Pipe Company, MJ Coupled Joint.

4. Push-on Rubber Gasket Joints: AWWA C 111/ANSI A 21.11.

5. Restrained Push-on Joints:
a. Manufacturers: One of the following or equal:
1) United States Pipe and Foundry Company, TR Flex.
2) Pacific States Cast Iron Pipe Company, Perma Lock.
3) American Cast Iron Pipe Company, Flex Ring or Lok-Ring. b. Design: Suitable for the following working pressures:
1) For 4 Through 24 inch Pipe: 350 pounds per square inch gauge. 2) For 30 Through 54 inch Pipe: 250 pounds per square inch gauge.

6. Grooved Joints: AWWA C 606, as complemented and modified below, radius-cut

Page 786 of 1480 ends

May, 2026 15251-4 Septage Hauling and Receiving Station Final
type, with following components:
a. Couplings: Rigid type, cast from ductile iron in accordance with ASTM A 536, Grade 65-45-12 or malleable iron in accordance with ASTM A 47, Grade 32510.
b. Bolts and nuts in accordance with ASTM A 183, Grade 2. c. Gaskets: Capable of being applied on surface of piping with cavities to provide for an improved seal with the internal piping pressure; material for following services:
1) For Liquid Service: [Halogenated butyl] [EPDM] [Viton]. 2) For Air Service: Fluoroelastomer.
3) For Hot Water Service: EPDM
d. Fittings: AWWA C 606, rigid radius-cut groove.
1) Center-to-center Dimensions: AWWA C 110/ANSI A 21.10. 2) Wall Thickness and Other Characteristics: AWWA C 153. e. Flanged Unit Connections: Flanged to grooved joint adapters or a long enough spool with 1 end flanged and the other grooved to prevent interference with the operation of adjacent valves, pumps, or other items.

2.02 FITTINGS
A. Fittings: Ductile iron conforming with AWWA C 110/ANSI A 21.10 or AWWA C 153/ANSI A 21.53.

B. Joint Type: Same as that of the associated piping as specified in Section 15052.

C. Plain end-to-flanged joint connectors using set screws are not acceptable.

2.03 PIPE LININGS AND COATINGS
A. Asphaltic Base Coating: Apply over cement mortar linings and to outside surface of pipes which will not receive another coating. Apply in accordance with AWWA C151/ANSI A21.51.

B. Cement-mortar Lining: AWWA C 104/ANSI A 21.4, apply on clean bare metal surfaces; extended to faces of flanges, ends of spigots, and shoulders of hubs.

C. Polyethylene Lining:

1. Manufacturers: One of the following or equal:
a. U. S. Pipe, polylined.
b. American Ductile Iron Pipe, polybond.

2. Material: ASTM D 1248, blend of high-density and low-density polyethylene powders; compounded with an inert filler and carbon black; minimum 30 mils thick; resistant to ultraviolet light.

3. Application:
a. Remove minimum 75 percent of high temperature oxide film. b. Sandblast fittings to commercial grade.
c. Uniformly preheat pipe and fittings to a temperature adequate to provide a uniform fusing of the polyethylene powders and proper bonding to pipe and fittings.

4. Coverage:
a. Push-on Joints: Extend lining from spigot end to edge of gasket sealing area. b. Mechanical Joints: Extend lining from spigot end to edge of gauging ring.

5. Source Quality Control: Test pipe and fitting lining with a 400 volt wet sponge spark tester. Discard piping or reline piping when pinholes or discontinuities are

Page 787 of 1480 ends

May, 2026 15251-5 Septage Hauling and Receiving Station Final
found.

D. Glass Lining:

1. Manufacturers: One of the following or equal:
a. Water Works Manufacturing, Ferrock MEH-32 Lining; Vitco Corporation, SG14 Lining.

2. Material: Special glasses and inorganic materials suited for lining of sewage, sludge, and scum piping with the following characteristics:
a. Thickness: 0.008 to 0.012 inch.
b. Hardness: 5 to 6 on the Mohs Scale.
c. Density: 2.5 to 3.0 grams per cubic centimeter, measured in accordance with ASTM D 792.
d. Thermal Shock Resistance: Capable of withstanding 350 degrees Fahrenheit change from 430 degrees Fahrenheit to 80 degrees Fahrenheit without crazing, blistering, or spalling.
e. Gloss Retention: Capable of retaining gloss after immersion of an 8 percent sulfuric acid solution at 148 degrees Fahrenheit for 10 minutes. f. Weight Loss: Maximum 3 milligrams per square inch when tested in accordance with ASTM C 283.

3. Fabrication:
a. Use piping that is suitable for glass lining with minimum Class 53 wall thickness after application of glass lining.
b. Machine interior of pipe (bore or grit blast to near white metal) prior to application of glass lining.
c. Screw factory assembled flanges on pipe and align bolt holes and flange faces, unless otherwise specified.
d. Apply lining to surfaces free of chemicals.
e. Place piping in especially designed furnaces and heat piping until glass melts and fuses with a integral molecular bond to the base metal.

2.04 POLYETHYLENE ENCASEMENT
A. Polyethylene Encasement Sheets or Tubes:

1. 8 mil thickness low density polyethylene, or

2. 4 mil thickness high density, cross laminated polyethylene.

2.05 COAL TAR ENAMEL LINING
A. Pipe specified or shown to be coal tar enamel lined shall be lined in accordance with the requirements of AWWA C 203.

2.06 EPOXY LINING
A. The interior of all pipe specified or indicated on the Drawings as coal tar epoxy lined, shall be lined with epoxy coating as specified for submerged metal in Section 09960.

PART 3 EXECUTION

3.01 INSTALLATION
A. General:

1. Install ductile iron piping in accordance with AWWA C 600, modified as specified in Section 15052.

2. Lay mechanical joint or bell and spigot pipe with 1/8 inch space between the spigot

Page 788 of 1480 ends

May, 2026 15251-6 Septage Hauling and Receiving Station Final
and shoulder of the pockets.

B. Polyethylene Encasement:

1. Wrap ductile iron pipe to be buried with polyethylene encasement in accordance with ASTM A 674 and AWWA C 105.

2. Repair tears and make joints with two layers of plastic tape.

3.02 JOINTS
A. Install types of joints as specified in piping schedule in Section 15052.

3.03 GROOVED JOINTS
A. Install piping with grooved joints where specified or indicated on the Drawings.

B. Assemble grooved joints in accordance with manufacturer's published instructions.

C. Support grooved-end pipe in accordance with manufacturer's published instructions.

Install at least 1 support between consecutive couplings.

D. Grooved joints may be installed where flanged joints are scheduled, except under the following conditions:

1. In underground and underwater installations.

2. In piping subject to test pressure of 150 pounds per square inch gauge or more.

3. In steam and in combustible gas piping systems.

4. In sludge and scum piping designed to be steam cleaned as indicated on the Drawings.

5. When wall thickness of pipe is less than the minimum recommended in published instructions by the manufacturer of the grooved end coupling.

E. Make connections to flanged valves, pumps and piping appurtenances by either:

1. Flanged-to-grooved joint adapters.

2. Flanged-by-grooved end pipe spool of sufficient length to prevent interference with the operation of adjacent valves, pumps or other items.

3. Integrally cast flanged-by-grooved end pipe fittings.

3.04 FIELD QUALITY CONTROL
A. Test ductile iron piping as specified in Section 15052.

1. Do not test sections longer than 1/2 mile in total pipe length.

B. Verify that interior surfaces of glass lined pipe and fittings have continuous coverage.

Verify with low voltage wet sponge holiday detector. Discard glass lined ductile iron piping and fittings with voids or casting anomalies that represent more than

0.01 percent of the total glassed surface (no more than 1-2 pinholes per fitting or an average of 5 or less per 20 feet of pipe). Discard lined piping and fittings found to have pinholes, crazing, or fishscales which expose the metal substrate.

END OF SECTION

Page 789 of 1480 ends

May, 2026 15252-1 Septage Hauling and Receiving Station Final
SECTION 15252

STEEL PIPING
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Steel piping, joints, fittings, pipe lining and coating, and fabricated steel piping fittings and specials.

B. Related Sections:

1. Section 09960 - High Performance Coatings.

2. Section 15052 - Basic Piping Materials and Methods.

1.02 REFERENCES
A. American Association of State Highway and Transportation Officials (AASHTO):

1. Standard H-20.

B. American National Standards Institute/American Society of Mechanical Engineers (ANSI/ASME):

1. B16.1 - Cast Iron Pipe Flanges and Flanged Fittings, Class 25, 125, 250 and 800.

2. B16.3 - Malleable-Iron Threaded Fittings, Classes 150 and 300.

3. B16.5 - Pipe Flanges and Flanged Fittings.

4. B16.9 - Factory-Made Wrought Steel Buttwelding Fittings.

5. B16.12 - Cast Iron Threaded Drainage Fittings.

C. American Society for Testing and Materials (ASTM):

1. A 47 - Ferritic Malleable Iron Casting.

2. A 53 - Pipe, Steel, Black and Hot-Dipped, Zinc-Coated Welded and Seamless.

3. A 105 - Forgings, Carbon Steel, for Piping Components.

4. A 106 - Seamless Carbon Steel Pipe for High-Temperature Service.

5. A 153 - Zinc Coating (Hot-Dip) on Iron and Steel Hardware.

6. A 183 - Carbon Steel Track Bolts and Nuts.

7. A 536 - Ductile Iron Castings.

8. D 297 - Steel Casting, Iron-Chromium and Iron-Chromium-Nickel, Heat-Resistant, for General Application.

9. C 150 - Portland Cement.

10. D 395 - Rubber Property-Compression Set.

11. D 977 - Emulsified Asphalt.

12. D 471 - Rubber Property-Effect of Liquids.

13. D 573 - Rubber Property-Deterioration in an Air Oven.

14. D 412 - Rubber Properties in Tension.

15. D 429 - Rubber Property-Adhesion to Rigid Substrates.

16. D 2000 - Classification System for Rubber Products in Automotive Applications.

17. D 2240 - Rubber Property-Durometer Hardness.

D. American Water Works Association (AWWA):

1. C 200 - Steel Water Pipe 6 Inches and Larger.

2. C 203 - Coal-Tar Protective Coatings and Linings for Steel Water PipelinesEnamel and Tape-Hot Applied.

3. C 205 - Cement-Mortar Protective Lining and Coating for Steel Water Pipe-4

Page 790 of 1480 ends

May, 2026 15252-2 Septage Hauling and Receiving Station Final
Inches and Larger-Shop Applied.

4. C 206 - Field Welding of Steel Water Pipe.

5. C 207 - Steel Pipe Flanges for Waterworks Service-Sizes 4 inches Through 144 inches.

6. C 208 - Dimensions for Fabricated Steel Water Pipe Fittings.

7. C 606 - Grooved and Shouldered Joints.

8. M 11 - Design Manual.

E. National Association of Corrosion Engineers (NACE):

1. RP0274-74 - Standard Recommended Practice.

1.03 SYSTEM DESCRIPTION
A. Design Requirements:

1. Design Criteria for Pipe and Pipe Fittings: In accordance with AWWA Manual M11 with the following modifications:
a. Wall Thickness: As designed or minimum 1/4 inch for pipe from 12 inches in diameter to, and including, 72 inches in diameter or minimum 5/16 inch for pipe larger than 72 inches in diameter, whichever is thicker. b. Inside Diameter of Unlined Pipe: Nominal.
c. Inside Diameter of Lined Pipe: As measured from face to face of liner, but not less than nominal.
d. Deflection of Underground Pipe Inside Diameter: Maximum 2 percent under trench load of H-20 live load in accordance with AASHTO specifications. e. Working Stress of Steel: Maximum 50 percent of yield stress.

1.04 SUBMITTALS
A. Shop Drawings: Details of fittings and specials showing thickness and dimensions of plates, detail of welds, and materials; listing of proposed services and locations for use of grooved joint type piping; tabulated layout schedules for cement-mortar lined and coated steel pipe.

B. Product Data: Details of fittings and specials showing thickness and dimensions of plates, detail of welds, and materials; grooved joint piping fittings, gaskets, couplings, grooving of pipe and fittings, and pipe lining and coating.

C. Certificates of Compliance: Cement-mortar lined and coated steel pipe.

D. Design Calculations: Wall thicknesses for external loading, special loading and internal pressure.

E. Mill certificates.

F. Test Reports: Rubber gaskets.

1.05 QUALITY ASSURANCE
A. Applicable Standards:

1. Cement-mortar lined and coated steel pipe shall conform to the following standards, as complemented and modified herein:
a. Steel Pipe: AWWA C 200.
b. Cement-Mortar Lining and Coating: AWWA C 205.

Page 791 of 1480 ends

May, 2026 15252-3 Septage Hauling and Receiving Station Final
c. Fittings and Specials: AWWA C 208.
d. Reinforcement of Fittings and Specials: AWWA M 11.

PART 2 PRODUCTS

2.01 MATERIALS
A. Steel Pipe:

1. Type, Pipe 6 inches and Smaller: ASTM A 53, black or galvanized, seamless or straight seam electric resistance welded. Minimum Schedule

40. 2. Type, from 6 to 12 inches: ASTM A 53, black or galvanized pipe, seamless or straight seam electric resistance welded. Minimum Schedule 20.

3. Type, Larger than 12 inches: AWWA C 200, without butt strap, riveted, or swaged joints; wall thickness as specified in Design Requirements.

4. Type, 24 inches and Larger, with Grooved Type Couplings and Wall Thickness less than 1/2 inch: Provided with stub ends, sized as follows, for grooves. a. Thickness: As recommended by coupling manufacturer, but not less than 1/2 inch.
b. Length: Width of coupling plus 1 inch, but not less than 6 inches.

5. Type for Liquid or Gaseous Dry Chlorine: ASTM A 106, Grade A, Schedule 80, assembled with 300 pounds per square inch malleable iron fittings and ammonia type flanges.

B. Steel Pipe Fittings:

1. Screwed Fittings:
a. Malleable Iron: ANSI/ASTM B16.3, 150 pounds; galvanized in accordance with ASTM A 153 where used with galvanized pipe.
b. Cast Iron Drainage: ANSI/ASTM B16.12; galvanized in accordance with ASTM A 153 where used with galvanized pipe.

2. Flanged Fittings:
a. Type for 12 inch and Smaller Pipe: ANSI/ASTM B16.1, cast iron or ductile iron, 125 pounds; or ANSI/ASTM B16.5, steel, 150 pounds, galvanized in accordance with ASTM A 153 where used with galvanized pipe. b. Type for Larger than 12 inch Pipe: ANSI/ASTM B16.5, steel, 150 pounds; galvanized in accordance with ASTM A 153 where used with galvanized pipe; or AWWA C 207 and AWWA C 208, fabricated from flanges and steel pipe, respectively.
c. Companion Flanges for 4 inches and Smaller Pipe: ANSI/ASTM B16.1, cast iron or ductile iron, 125 pounds; ANSI/ASTM B16.5, steel, 150 pounds, slip-on or welding neck; or ammonia type for use on chlorine liquid or gas piping. d. Companion Flanges for Larger than 4 inch to and Including 12 inch Pipe:

ANSI/ASTM B16.5, slip-on or welding neck type.
e. Companion Flanges for Larger than 12 inch Pipe: ANSI/ASTM B16.5, steel, 150 pounds; galvanized in accordance with ASTM A 153 where used with galvanized pipe; or AWWA C 207, steel plate or raised hub type. f. Weld flanges to pipe or fittings before applying lining. g. Machine flanges or provide tapered filler for changes in grade or to slope lines for drainage.
h. Flange Bolts: ANSI/ASTM B16.1 for typical applications; or Type 304 or 316 stainless steel, or Everdur for underground or underwater applications. 1) Cut and finish flange bolts to project a maximum of 1/4 inch beyond outside face or nut after assembly.

Page 792 of 1480 ends

May, 2026 15252-4 Septage Hauling and Receiving Station Final
2) Tap holes for cap screws or stub bolts when used.
i. Gaskets: In accordance with Section 15052.

3. Welding Fittings:
a. Welding Fittings for Piping 8 inches and less in Nominal Diameter: Buttwelding fittings in accordance with ANSI/ASTM B16.9, standard wall or standard weight.
b. Welding Fittings for Piping Larger than 8 inches in Nominal Diameter: Buttwelding fittings in accordance with ANSI/ASTM B16.9, or, at the option of the CONTRACTOR, made up out of sections of pipe welded together, except where smooth bends are indicated for air lines.
c. Fittings made up of sections of pipe welded together shall be made of pipe of at least the same wall thickness as the pipe with which used, and bends shall be miter bends, fabricated in accordance with AWWA C 208 and as supplemented by AWWA Manual M 11. Welding of these made-up fittings shall be in accordance with AWWA C 206.
1) Design and fabricate outlets and 4 branch fittings in accordance with AWWA Manual M 11.
2) Bends may be welded to adjacent pipe sections.
a) Bends shall be manufactured of the following number of pieces:
b) Bends from 0 to 30 degrees angle, 2 pieces.
c) Bends from 30 to 45 degrees angle, 3 pieces.
d) Bends from 45 to 67-1/2 degrees angle, 4 pieces.
e) Bends from 67-1/2 to 90 degrees angle, 5 pieces.

4. Grooved Joint Fittings:
a. Fittings for Grooved Joint Steel Piping: Rigid-grooved type, and as follows:
1) Grooves: Cut; rolled grooves are not acceptable.
2) Couplings: Cast in 2 or more segments of ductile iron conforming to ASTM A 536, Grade 65-45-12 or malleable iron conforming to ASTM A 47, Grade 32510.
3) Bolts and Nuts: ASTM A 183, Grade 2.
4) Gaskets: Composition water-sealing designed so that the internal piping pressure serves to increase the seal's watertightness. 5) Gaskets for water service and oil-free air systems at temperatures less than 230 degrees Fahrenheit shall be made of ethylene propylene diene monomers (EPDM) in accordance with ASTM D 2000 Line Call Out 2CA615A25B24.
6) Gaskets for use with cement-mortar lined steel piping shall be captured between the ends of the pipe to protect exposed metal from corrosion, and shall be made of nitrile in accordance with ASTM D 2000, Line Call Out 2CA615A25B24.
7) Perform grooving of the pipe wall only on standard or heavier schedule weight pipe.
a) For pipe with wall thickness less than standard weight, weld a shouldered end on the pipe in accordance with AWWA C 606. b) Fabricated pipe, pipe conforming to AWWA C 200, shall have shouldered ends welded onto the pipe.
c) Shoulder: Type B or D in accordance with AWWA C 606. 8) Couplings and Grooving: As manufactured by Gustin-Bacon Piping Products, Victaulic Company of America, or equal.
b. Fittings for Grooved Joint Piping: Ductile iron conforming to ASTM A 536, Grade 65-45-12, or malleable iron conforming to ASTM A 47, Grade 32510,

Page 793 of 1480 ends

May, 2026 15252-5 Septage Hauling and Receiving Station Final
and as follows:
1) Where cast fittings are not made, standard fittings including large diameter elbows shall be made of forged steel conforming with ASTM A 105, Grade B with 0.375 inch wall thickness, or shall be standard segmentally welded fittings fabricated of Schedule 40 carbon steel pipe. a) Grooves: As manufactured by Gustin-Bacon Piping Products, Victaulic Company of America, or equal.
2) Fittings for grooved joint piping shall be furnished by the manufacturer of the grooved joint material.
3) Fittings for grooved joint piping shall be for rigid-grooved type joints. 4) Connection to flanged units shall be by means of flange to grooved joint adapters.
a) Where the flanged to grooved joint adapters interfere with the operation of adjacent valves, pumps, or other items, the connection shall be by means of a spool with one end flanged and the other grooved, long enough to prevent interference with adjacent valves, pumps, or other items.

C. Steel Pipe Lining and Coating:

1. General:
a. Except where otherwise specified in the Specifications and indicated on the Drawings, lining and coating for steel pipe shall be as specified hereinafter. b. Pipe Coating:
1) Except as otherwise specified or indicated on the Drawings, provide underground steel piping with one of the coatings specified hereinafter. 2) Extend pipe coating for underground piping 6 inches above finish grade or finish floor, and neatly terminate.
3) Field paint aboveground steel pipe as specified in Part 3 of this Section.

2. Cement-mortar Lining and Coating:
a. Lining:
1) Shop apply cement-mortar lining for steel pipe, interior, in accordance with AWWA C 205; or, at the option of CONTRACTOR, field apply with a pipe lining machine.
b. Coating:
1) Cement-mortar Coating for Steel Pipe Exterior: In accordance with AWWA C 205, modified as follows:
a) Portland Cement: ASTM C 150, Type II, low alkali.
b) Sand: AWWA C 205 except that the total percentage of deleterious material shall not exceed 3 percent.

3. Coal-Tar Enamel Lining:
a. Coal-tar enamel lining for interior of steel pipe: In accordance with AWWA C 203.

4. Coal-Tar Epoxy Lining:
a. Coal-tar Epoxy Lining for Interior of Steel Pipe: Epoxy bituminous coating as specified for submerged metal in Section 09960, High Performance Coatings. b. Polyurethane Lining for Interior of Steel Pipe: Polyurethane as specified for submerged metal in Section 09960, High Performance Coatings.

5. Plastic Tape Wrap:
a. Plastic tape wrap for exterior of steel piping shall consist of a prime coat followed with spirally applied tape layers to a minimum system thickness of 80 mils.
b. Plastic Tape Wrap Coating: Plastic tape wrap for exterior of steel pipe, fittings and specials shall conform to the requirements of AWWA C209 and AWWA C214 as applicable.

Page 794 of 1480 ends

May, 2026 15252-6 Septage Hauling and Receiving Station Final

6. General: The tape coating system shall consist of primer, one layer of 20 mil inner wrap, one layer of 30 mil outer wrap and a second layer of 30 mil outer wrap, for a total coating thickness of 80 mils. All materials shall be of products of the same manufacturer.
a. Primer: As manufactured by one of the following or equal:
1) Polyken Pipeline Coatings, Number 1029 or 1039 Primer. 2) The Tapecoat Company, TC Omniprime Primer.
b. Pipe Wrap:
1) First Wrap: As manufactured by one of the following or equal:
a) Polyken Pipeline Coatings, Number 989-20 (932-50 for fittings). b) The Tapecoat Company, Tapecoat 1020B.
2) Middle Wrap: As manufactured by one of the following or equal:
a) Polyken Pipeline Coatings, Number 955-30.
b) The Tapecoat Company, Tapecoat 2030B.
3) Finish Wrap: As manufactured by one of the following or equal:
a) Polyken Pipeline Coatings, Number 956-30 White.
b) The Tapecoat Company, Tapecoat CT 2030B.

7. Filler Tape:
a. Polyken 939.
b. or equal.

8. Joint Wrap:
a. Polyken 932-50, white Hi-Tack Joint Wrap tape.
b. Tapecoat Company, Joint Tape.

9. Application on Welded Joints:
a. Remove sharp edges of weld spatter and slag wit a file or ball peen hammer before wrapping joints.
b. Apply plastic tape wrap in accordance with AWWA C-209. 1) Clean and prime all surfaces, then apply a wrap of 0.125 thick by 2 inch wide filler tape centered on the weld. Push and knead the tape into all voids.
c. Apply two wraps of 30 mil joint tape; or the tape may be half lapped to obtain the double thickness.
d. Finish Wrap: Apply final wrapping in same manner.
e. Wrap fittings, valves, and other odd shaped components in the pipeline with first and finish wrapping over the prime coat , total thickness of tape 80 mils.

10. Extruded Coatings:
a. Coat pipe with a film of high density polyethylene, plant extruded onto the pipe over a thermoplastic adhesive primer.
1) Coating Thickness: In accordance with the extruder's standards but not less than 6 pounds per diameter inch per 100 feet of pipe. 2) Coating: Manufacturers: One of the following or equal:
a) Plexco (Pipe Line Service Co.).
b) Extrucoat.

D. Rubber Lined Piping:

1.General:
a. Rubber lined piping for abrasion resistant services: Black steel piping conforming to ASTM A 53, Schedule 40, lined as specified herein.

2.Fittings and Couplings:
a. Fittings: Grooved joint type, machined for rubber lining. b. Couplings: Grooved type.

3.Lining Material:
a. Rubber for Rubber Lined Piping: Neoprene compounded to provide maximum

Page 795 of 1480 ends

May, 2026 15252-7 Septage Hauling and Receiving Station Final
resistance to abrasion, temperature variations, and aging, and shall have a Durometer A hardness of 60 within 5.

4. Lining Application:
a. Preparation:
1) Immediately before application of adhesive for rubber lining, sandblast metal surfaces to obtain a bright, clean, and dry surface. 2) The interior of the piping shall be free of sunken seams or other defects that may detract from the rubber lining quality.
b. Application:
1) Prepare the metal and apply the lining to provide a uniform thickness of rubber and a uniform finished diameter.
a) Rubber Lining: Not less than 1/4 inch thick, applied to provide a smooth and continuous surface.
b) Apply such that lining does not have circumferential seams. 2) Return rubber lining at ends of pipe and openings in fittings over the end as recommended by the lining manufacturer.
3) Apply rubber lining in a manner that provides continuous and uninterrupted adhesion to the piping walls.
a) Air pockets, blisters, and similar defects shall be cause for rejection of the item wherein such defects are found.

5.Testing Lining Adhesion:
a. Testing for adhesion: In accordance with ASTM D 429, Method B. 1) Conduct pull test with not less than 35 pounds at 45 degree angle. b. Do not install items which fail the pull test.

E. Fabricated Steel Piping Fittings and Specials:

1.General: Specified herein are the design and fabrication of fabricated steel piping fittings and specials, which include elbows, branches, nozzles, manifolds, headers, heads, collars, stiffeners, reinforcements, and other steel fabrications relating to steel piping, but shall not include steel pipe.

2. Design:
a. CONTRACTOR shall design and detail fittings and specials. 1) Design: In accordance with the recommended procedures in AWWA Manual M 11, as complemented and modified herein.
2) Nozzles: Reinforced in conformance with recommended practice in AWWA M 11, Steel Pipe Manual.
3) Design reinforcing for fittings and specials for the specified test pressure.
4) Fittings shall conform in dimension to AWWA C 208, complemented with the provisions specified herein.
5) The working stress for steel used for fabrication of pipe shall not exceed 50 percent of the yield stress.
b. The thickness of pipe, large elbows, and headers, except header nozzles, shall be the thicker of:
1) The thickness designed in accordance with the design methods specified in the preceding paragraph “Fabricated Steel Piping Fittings and Specials.”
2) The thickness indicated on the Drawings.
3) The following thicknesses:
a) For Pipes Smaller than 72 inches in Diameter: Minimum 1/4 inch. b) For Pipes 72 inches in Diameter and Larger: Minimum 5/16 inch. c. Elbows shall be of the number of pieces specified under paragraph Steel Pipe Fittings, “Welding and Fittings”, and thickness of material shall conform to thickness of pipe or manifold shells specified.

Page 796 of 1480 ends

May, 2026 15252-8 Septage Hauling and Receiving Station Final
d. Ends of fittings to be welded to pipe shall be beveled for welding.

3. Fabrication:
a. Shop fabricate steel piping fittings and specials in units as long as practicable for safe hauling and installation. Minimize number of field welds. b. Fabricate fittings and specials to uniform lengths with proper end clearance for the specified types of joint or attachment.
c. Fabricate fittings and specials to allow field assembly without cutting or special work.
d. Where specified in the Piping Schedule in Section 15052 - Pipes and Pipe Fittings, or indicated on the Drawings, the inside of fabricated steel manifolds and other fittings and specials shall receive a cement-mortar lining in accordance with AWWA C 205.
1) Reinforce lining for piping 24 inches in diameter and larger with wire fabric.
e. Do not weld flanges to nozzles until the nozzles and reinforcements are completely welded to the header.
1) Accurately space and align flanges so that when connections have been made there will be no stress on the header, piping, or equipment.

Properly locate and align equipment.

4. Dished Heads:
a. Dished Heads on 84 inch Diameter and Smaller Manifolds: 1 piece (seamless) spherically dished (torispherical) heads.
1) Larger heads may be seamed.
b. Dish Radius: Same dimension as the outside diameter of the head measured at skirt.
c. Skirt Face Length: Not less than 3 inches.
d. Design heads in conformance with recommended practice in AWWA M 11, Steel Pipe Manual.

5.Testing: No shop testing will be required for manifolds or piping connected thereto.

F. Steel Pipe, Cement-mortar Lined and Coated:

1.General:
a. Applicable Standards: Cement-mortar lined and coated steel pipe shall conform to the standards specified in Part 1 of this Section. b. Identification Marks: Provide identification marks in compliance with AWWA C 200. These marks shall be stenciled or otherwise shown at the top of the piping items exterior, including the following information:
1) Name or trademark of the manufacturer.
2) Date of manufacture of the item.
3) Internal diameter in inches.
4) Number of the item, sequential from initial to end station. c. Diameter Designation: The pipe diameter specified in the Specifications and indicated on the Drawings shall be the clear inside diameter after application of the cement-mortar lining with a tolerance of plus 0 inch and minus 1/4 inch.

2. Design:
a. Pipe and fittings shall be designed by CONTRACTOR.
b. Design: In accordance with the recommended procedures in AWWA Manual M 11, as complemented and modified herein.
c. Thicknesses of Pipe, Fittings and Specials Shall Be the Thicker Of:
1) The thickness designed in accordance with the design methods specified in the preceding Subparagraph 2.
2) The thickness indicated on the Drawings.
3) The following thicknesses:
a) For pipes 26 inches and less in nominal diameter, not less than 1/4

Page 797 of 1480 ends

May, 2026 15252-9 Septage Hauling and Receiving Station Final
inch.
b) For pipes more than 26 inches and less than 38 inches in nominal diameter, not less than 5/16 inch.
c) For pipes 38 inches to and including 54 inches in nominal diameter, not less than 3/8 inch.
d. The working stress for steel used for fabrication of pipe shall not exceed 50 percent of the yield stress.
e. Break longitudinal and girth seams for straight seam pipe shall be no greater in number than would be required for the fabrication of pipe with 96 inch by 120 inch steel plates.
1) Break longitudinal seams at the girth seams.
f. Calculate earth loads using the following formula:
1) W = [X] x H x B
2) wherein the various terms shall have the following meaning:
3) W:Earth load, pounds per linear foot of pipe.
4) H:Height of fill over the pipe, feet.
5) B:Outside diameter of the pipe, feet.
6) x: Mathematical symbol for multiplication.
g. Add AASHTO's H-20 loading to earth loads.
h. Design pipe, fittings and specials for a deflection, under external loads, not to exceed 2 percent of the diameter.
1) Stiffness computations shall not consider the effect of the cement-mortar lining and coating.
2) Calculate deflection using the Spangler formula and the following values:
a) Bedding constant K = 0.100.
b) Modulus of soil reaction E' = 700 pounds per square inch. c) Deflection lag constant D1 = 1.00.
i. Where piping is designated to be flanged or welded in order to restrain thrust, the design of the cylinder and flange or welded joint shall take into account the effect of stresses caused by thrust loads.
j. Steel cylinder shall be subject to no more than the lesser of 15,000 pounds per square inch or 50 percent of the steel yield stress.

3. Materials:
a. Cement: ASTM C 150, Type II, low alkali.
b. Gaskets shall be as specified in Section 15052 and meet the following requirements:
1) Minimum tensile strength, tested in accordance with ASTM D 412, between 2,000 and 2,700 pounds per square inch.
2) Minimum elongation, tested in accordance with ASTM D 412, between 350 and 400 percent.
3) Shore A durometer hardness, tested in accordance with ASTM D 2240, between 50 and 65.
4) Specific gravity, tested in accordance with ASTM D 297, between 0.90 and 1.50.
5) Maximum compression set, tested in accordance with Method B of ASTM D 395, 20 percent.
6) Maximum tension strength loss, tested in accordance with ASTM D 573 at 96 hours, 70 degrees Centigrade, in air, 20 percent. 7) Maximum elongation loss, tested in accordance with ASTM D 573 at 96 hours, 70 degrees Centigrade, in air, 20 percent.
8) Maximum absorption, tested in accordance with ASTM D 471 at 48

Page 798 of 1480 ends

May, 2026 15252-10 Septage Hauling and Receiving Station Final
hours, 70 degrees Centigrade, in air, 5 percent.

4. Fabrication:
a. Joints: Except as otherwise specified or indicated on the Drawings, provide bell and spigot type joints with rubber gaskets.
1) Bell and Spigot Rings: Rolled Carnegie shape M-3516. b. Flanges: AWWA C 207, Class D, steel ring, and as follows:
1) Match pipe flanges to the valve flanges.
a) At flanged joints connecting to valves, provide a steel pipe section without rod reinforcing and not less than 24 inches in length. b) Apply cement-mortar lining and coating to the steel pipe section. c. Shop Coat of Primer: Flanges and portions of pipe not covered with cementmortar shall be given a shop coating of primer. d. Bend Radii of Fittings: Not less than 2.5 times the nominal diameter.

PART 3 EXECUTION

3.01 INSTALLATION
A. Joints:

1. Steel pipe joints shall be screwed, welded, flanged, grooved, or made with flexible joints. The type of joint for piping is specified in the Piping Schedule in Section 15052.

2. In addition to the joints indicated on the Drawings, provide unions, flexible couplings, flanged joints, and other types of joints or means necessary to allow ready assembly and disassembly of the piping.

3. Unless otherwise indicated on the Drawings or specified in the Piping Schedule in Section 15052, pipe joints shall be as follows:
a. Pipe smaller than 2 inches in nominal diameter shall have screwed joints or flexible couplings.
b. Pipe 2 inches to 4 inches in nominal diameter shall have screwed joints, flanged joints, welded joints, or joints made with flexible couplings. c. Pipe larger than 4 inches in nominal diameter shall have flanged joints, welded joints, or joints made with flexible couplings.

B. Screwed Joints:

1. Perform threading with clean, sharp dies.
a. Wavy, rough, or otherwise defective pipe threads are not acceptable.

2. Make screwed joints tight and clean with an application of Teflon tape or approved paste compound applied to the male threads only, except as follows:
a. Make up liquid and dry chlorine lines, and liquefied petroleum gas lines, with litharge and glycerine.

3. Provide railroad type unions with bronze-to-iron seat, galvanized where used with galvanized pipe.
a. Flanged joints may be used instead of unions.

C. Flanged Joints:

1. In flanged joints, flanges shall come together at the proper orientation with no air gaps between the flanges after the gaskets are in place.

2. Attach slip-on flanges to pipe by two fillet welds, in accordance with AWWA C 207.

3. Secure welding neck flanges with full penetration butt welds without backing rings. a. After welding in place, the faces of flanges shall be perpendicular to the axis of the pipe, or, in the case of fittings, at the proper angle to each other, and bolt holes shall be in proper alignment.

Page 799 of 1480 ends

May, 2026 15252-11 Septage Hauling and Receiving Station Final
D. Welded Joints:

1. Welded joints shall be electric welded in accordance with AWWA C 206.

2. Welders shall be qualified pursuant to the provisions of AWWA C 206. a. Welders' testing shall be at the CONTRACTOR's expense, including cost of test nipples, welding rods, and equipment.

3. Do not weld galvanized pipe.

E. Grooved Joints:

1. Piping with grooved joints shall be installed where indicated on the Drawings and may be installed in place of flanged piping and screwed piping, except that grooved joint piping shall not be used in the following installations:
a. In underground and underwater installations.
b. In piping subject to test pressures of 150 pounds per square inch gauge, or more.
c. In steam and gas piping.
d. In sludge and scum piping designed to be steam cleaned.

2. Assemble in accordance with manufacturer's published instructions.

3. Support grooved-end pipe in accordance with manufacturer's recommendations. In addition, provide at least 1 support between consecutive couplings.

F. Lining and Coating:

1. Field paint aboveground steel pipe as specified in Section 09960, High Performance Coatings.

2. Field applied cement-mortar lining shall be of the same density, smoothness, and thickness as shop applied lining, and shall conform to applicable portions of AWWA C 602.

3. Plastic tape wrap application procedures shall be in accordance with manufacturer's published instructions.
a. Apply primer with brush, without runs and drips.
b. Lap wrapping not less than 1/2 inch. A single wrap lapped 50 percent or more will not be acceptable.
c. Application on Welded Joints:
1) Remove sharp edges of weld spatter and slag with a file or ball peen hammer before wrapping welded joints.
2) Apply a single thickness of tape base wrap over the primer, around the weld.
3) Start first wrapping 4 inches back on the pipe wrap, spiral wrap tape over the joint holding the proper tension and overlap, and finish 4 inches back on the pipe wrap on the other side of the joint.
4) Apply final wrapping in same manner.
d. Wrap fittings, valves, and other odd shaped components in the pipeline with first and finish wrapping over the prime coat.
e. Wrap joints, fittings, valves, and other irregular shapes of piping with extruded coatings with tape as specified in this Subparagraph.

4. Protect lining of fabricated steel piping fittings and specials during hauling, installation, and operation.

5. Finish joints of fabricated steel piping fittings and specials as specified for pipe lining after field welding is done.

6. After final field welding of fabricated steel piping fittings and specials, complete the lining and exterior painting at and near the welded connections. a. Repair or replace lining damaged as a result of welding heat, handling, or other causes.

3.02 FIELD QUALITY CONTROL

Page 800 of 1480 ends

May, 2026 15252-12 Septage Hauling and Receiving Station Final
A. Testing: Fabricated steel manifolds shall be field tested with the pipe to which they connect.

B. Holiday Detection Testing of Plastic Tape Wrap Coatings:

1. Perform a complete high voltage electrical inspection (holiday detection testing) of all steel piping systems and fittings coated with plastic tape wrap prior to burying. a. Perform high voltage electrical inspection in strict accordance with NACE RP0274-74.
b. Test voltage used for the electrical inspection of the piping and fittings shall be in accordance with the recommendations given by the tape coating manufacturer in their published literature.
c. Repair all holidays and defects found in the coating system through the high voltage electrical inspection in strict accordance with the tape coating manufacturer's recommendations.
d. Retest repaired areas in the coating prior to burial of the piping to ensure that all holidays and defects in the coating have been properly repaired.

2. Before conducting holiday detection testing on any piping systems, submit to the ENGINEER for review and approval technical literature and data describing the testing instrumentation, equipment, electrodes, and other accessories that will be used.
a. The literature and data shall include complete information covering the operation and use of the testing equipment, including operational voltage ranges.

3. All holiday detection testing and coating repair work shall be witnessed, inspected and approved by the ENGINEER.

C. Holiday Detection Testing of Extruded Coatings:

1. Perform a complete high voltage electrical inspection (holiday detection testing) of all steel piping systems and fittings coated with extruded high density polyethylene prior to burial of the pipe.

2. Perform the high voltage electrical testing as specified under the preceding paragraph “Holiday Detection Testing of Plastic Tape Wrap Coatings .”

END OF SECTION

Page 801 of 1480 ends

May, 2026 15265-1 Septage Hauling and Receiving Station Final
SECTION 15265

PLASTIC PIPING AND TUBING
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Plastic pipe, tubing, and fittings.

B. Related Sections:

1. Section 15052 - Basic Piping Materials and Methods.

2. Section 15251 - Ductile Iron Piping.

3. Section 15956 - Piping Systems Testing.

1.02 REFERENCES
A. American National Standards Institute (ANSI):

1. B 16.12 - Cast Iron Threaded Screwed Drainage Fittings.

B. American Society for Testing and Materials (ASTM):

1. D648 - Test Method for Deflection Temperature of Plastics Under Flexural Load.

2. D1248 - Specification for Polyethylene Plastics Molding and Extrusion Materials.

3. D1784 - Specification for Rigid Poly(Vinyl Chloride) (PVC) Compounds and Chlorinated Poly(Vinyl Chloride) (CPVC) Compounds.

4. D1785 - Specification for Poly(Vinyl Chloride) (PVC) Plastic Pipe, Schedules 40, 80 and 120.

5. D2661 - Specification for Acrylonitrile-Butadiene-Styrene (ABS) Schedule 40 Plastic Drain, Waste, and Vent Pipe and Fittings.

6. D2751 - Standard Specification for Acrylonitrile-Butadiene-Styrene (ABS) Sewer Pipe and Fittings.

7. D1869 - Specification for Rubber Rings for Asbestos-Cement Pipe.

8. D2412 - Test Method for Determination of External Loading Characteristics of Plastic Pipe by Parallel-Plate Loading.

9. D2466 - Specification for Poly(Vinyl Chloride) (PVC) Plastic Pipe Fittings, Schedule 40.

10. D2467 - Specification for Socket-Type Poly(Vinyl Chloride) (PVC) Plastic Pipe Fittings, Schedule 80.

11. D2513 - Specification for Thermoplastic Gas Pressure Pipe Tubing and Fittings.

12. D2564 - Specification for Solvent Cements for Poly(Vinyl Chloride) (PVC) Plastic Piping Systems.

13. D2665 - Specification for Poly(Vinyl Chloride) (PVC) Plastic Drain, Waste, and Vent Pipe and Fittings.

14. D2680 - Specification for Acrylonitrile-Butadiene-Styrene (ABS) and Poly(Vinyl Chloride) (PVC) Composite Sewer Piping.

15. D3034 - Specification for Type PSM Poly(Vinyl Chloride) (PVC) Sewer Pipe and Fittings.

16. D3212 - Specification for Joints for Drain and Sewer Plastic Pipes Using Flexible Elastomeric Seals.

17. D3261 - Specification for Butt Heat Fusion Polyethylene (PE) Plastic Fittings for Polyethylene (PE) Plastic Pipe and Tubing.

18. D3350 - Specification for Polyethylene Plastic Pipes and Fittings Materials.

19. D4101 - Specification for Propylene Plastic Injection and Extrusion Materials.

Page 802 of 1480 ends

May, 2026 15265-2 Septage Hauling and Receiving Station Final

20. F439 - Specification for Socket-Type Chlorinated Poly(Vinyl Chloride) (CPVC) Plastic Pipe Fittings, Schedule 80.

21. F441 - Specification for Chlorinated Poly(Vinyl Chloride) (CPVC) Plastic Pipe, Schedules 40 and 80.

22. F477 - Specification for Elastomeric Seals (Gaskets) for Joining Plastic Pipe.

23. F483 - Test Method for Total Immersion Corrosion Test for Aircraft Maintenance Chemicals.

24. F493 - Specification for Solvent Cements for Chlorinated Poly(Vinyl Chloride) (CPVC) Plastic Pipe and Fittings.

25. F645 - Guide for Selection, Design and Installation of Thermoplastic Water Pressure Piping Systems.

26. F679 - Specification for Poly(Vinyl Chloride) (PVC) Large-Diameter Plastic Gravity Sewer Pipe and Fittings.

27. F714 - Specification for Polyethylene (PE) Plastic Pipe (SDR-PR) Based on Outside Diameter.

C. American Water Works Association (AWWA):

1. C 900 - Polyvinyl/Chloride (PVC) Pressure Pipe, 4 Inches through 12 Inches, for Water Distribution.

D. Code of Federal Regulations:

1. Title 49 - Transportation.

E. Plastics Pipe Institute (PPI).

F. United States Department of Transportation:

1. Materials Transportation Bureau.

1.03 ABBREVIATIONS
A. ABS: Acrylonitrile-Butadiene-Styrene.

B. CPVC: Chlorinated Polyvinyl Chloride.

C. DWV: Drain, waste, and vent.

D. ID: Inside diameter of piping or tubing.

E. NPS: Nominal pipe size followed by the size designation.

F. NS: Nominal size of piping or tubing.

G. PE: Polyethylene.

H. PP: Polypropylene.

I. PVC: Polyvinyl Chloride.

J. SDR: Standard dimension ratio.

1.04 SUBMITTALS
A. Product Data: Describe materials and installation equipment including fusion machine.

Page 803 of 1480 ends

May, 2026 15265-3 Septage Hauling and Receiving Station Final
B. Manufacturer's Published Installation Instructions.

C. Certificates:

1. Submit manufacturer's certificate attesting that plastic pipe, tubing, and fitting types meet specified requirements.
a. PVC gravity sewer piping: Requirements of ASTM D3034 or ASTM F679, as applicable.

2. Manufacturer's certification of date of manufacture of plastic pipe and tubing for each lot delivered.

3. Copies of solvent cement manufacturer's report and certification in accordance with ASTM D2564 for PVC piping, and ASTM F493 for CPVC piping.

D. Qualifications of installation crew for drain, PE piping, including qualifications of the fusion machine technician.

1.05 QUALITY ASSURANCE
A. Fusion Machine Technician Qualifications: 1 year experience in the installation of similar PE piping systems from the same manufacturer.

B. Provide pipe and tubing bearing NSF seal, except for drainage piping.

C. Mark plastic pipe with nominal size, type, class, schedule or pressure rating, and manufacturer.

1.06 DELIVERY, STORAGE, AND HANDLING
A. Protect piping materials from sunlight, scoring, and distortion.

B. Do not allow surface temperatures on pipe and fittings to exceed 120 degrees Fahrenheit.

C. Store and handle PE pipe and fittings as recommended by manufacturer in published instructions.

PART 2 PRODUCTS

2.01 MATERIALS
A. Extruding and Molding Material: Virgin material containing no scrap, regrind, or rework material except where permitted in the referenced standards.

B. Fittings: Same material as the pipe and of equal or greater pressure rating, except that DWV fittings need not be pressure rated.

C. Unions 2-1/2 Inches and Smaller: Socket end screwed unions. Make unions 3 inches and larger of socket flanges with 1/8 inch full face soft EPDM gasket.

2.02 PVC PIPING, SCHEDULE TYPE
A. Materials:

1. PVC Schedule Type Piping: Designation PVC 1120 conforming to ASTM D1785 and appendices thereto.

Page 804 of 1480 ends

May, 2026 15265-4 Septage Hauling and Receiving Station Final
a. Pipe and Fittings: Extruded from Type I, Grade 1, Class 12454-B material in accordance with ASTM D1784.
b. PVC Schedule Type Piping: Schedule 80 unless otherwise indicated on the Drawings.

2. Fittings:
a. Supplied by pipe manufacturer.
b. Pressure Fittings: In accordance with ASTM D2466 or ASTM D2467. c. DWV Fittings: In accordance with ASTM D2665.

3. Solvent Cement: In accordance with ASTM D2564.

2.03 PVC PIPING, CLASS TYPE
A. Materials:

1. PVC Pipe, Class Type: ASTM D2241, except that pipe shall have outside diameters of ductile iron pipe sizes rather than of iron pipe sizes. a. PVC Class 150 pipe: SDR not more than 18, and Uni-Bell Standard UNI-B-2-72.
b. PVC Pipe, Class Type: AWWA C 900, pressure Class 150 and SDR not more than 18.
c. Bell Section: At least as strong as the pipe barrel.

2. Fittings:
a. If not otherwise scheduled, use cast or ductile iron fittings as specified under Section 15251, sized for the dimensions of the pipe being used. a. PVC when scheduled:
1) Iron Pipe Size Fittings: SDR21, SDR26, SDR32.5 and SDR41 IPS PVC Gasketed Tees, Bends, and Reducers conform to the following Specifications and Standards. ASTM D1784, “Standard Specification for Rigid Poly(Vinyl Chloride) (PVC) Compounds and Chlorinated Poly(Vinyl Chloride) (CPVC) Compounds.” ASTM D2241 “Standard Specification for Poly(Vinyl Chloride) (PVC) Pressure-Rated Pipe (SDRSeries). ”Fittings shall be: Class 200, SDR21 or Class 160, SDR26 or Class 125 SDR32.5 or Class 100 SDR41 as scheduled. Fittings shall confirm to ASTM D3139, “Standard Specification for Joints for Plastic Pressure Pipes Using Flexible Elastomeric Seals.” and ASTM F477, “Standard Specification for Elastomeric Seals (Gaskets) for Joining Plastic Pipe.” 2) Manufacturer: Specified Fittings or equal.
b. Fittings for Joining Pipe 4 Inches in Diameter and Larger: Push-on rubber gasket or mechanical joint type.

3. Gaskets: EPDM meeting the requirements of ASTM D1869 or ASTM F477.

2.04 PVC GRAVITY SEWER PIPING
A. Materials:

1. Polyvinyl-chloride (PVC) Gravity Sewer Pipe and Fittings: In accordance with ASTM D3034 for piping NPS 15 and smaller diameter, and to ASTM F679 for piping NPS 18 and larger diameter.
a. Referenced standards apply as complemented and modified herein. b. Fittings: Supplied by the pipe manufacturer.

2. PVC Compounds: Class Number 12454-B, as specified in ASTM D1784. a. Stabilizers, antioxidants, lubricants, colorants, and other additives and fillers:

Not to exceed 10 parts by weight per 100 of PVC resin in the compound.

3. Pipe NPS 15 and Smaller Diameter: Wall thickness SDR 26. a. Joints: Push-on joints in accordance with ASTM D3212.

4. Pipe NPS 18 and Larger diameter: Type T-1 with an SDR not greater than 35.

Page 805 of 1480 ends

May, 2026 15265-5 Septage Hauling and Receiving Station Final
a. Joints: Integral bell gasketed joints in accordance with ASTM F679. b. Bell: Thickened, integral with the pipe wall, and at least as strong as the pipe barrel.
c. Gasket Ring: Locked into the bell.
d. Spigot End of the Pipe: Marked by the manufacturer to identify the final in-place position of the spigot in the bell.

5. Fittings, Including Wyes, Tees, Elbow Caps, Plug Adapters, and Manhole Waterstops: Same wall thickness as the pipe.
a. Fittings: Factory molded with joints and gaskets equal to those of the pipe.

6. Gasket: EPDM conforming to ASTM D3212 or ASTM F477.
a. Keep rubber gasket in place during pipe joining.

7. Gasket for Connection to Manhole: Stainless steel clamp with gasket or similar device to seal the penetration.

2.05 CPVC PIPING
A. Materials:

1. CPVC Pipe: Schedule 40 or Schedule 80, as specified, in accordance with ASTM F441 and Appendix, CPVC 4120.
a. Pipe: Extruded from Type IV, Grade 1, Class 23447 material in accordance with ASTM D1784.
b. Manufacturers: One of the following or equal:
1) Charlotte Pipe and Foundry Company.
2) Eslon Thermoplastics, Inc.
3) Harvel Plastics, Inc.

2. Fittings: Conform to ASTM F438 or ASTM F439 for pressure fittings, as appropriate to the service and pressure requirement.
a. Fittings: Supplied by the pipe manufacturer.
b. Manufacturers: One of the following or equal:
1) Colonial Engineering.
2) Eslon Thermoplastics, Inc.
3) Chemtrol.
4) Spears Manufacturing Company; or equal.

3. Solvent Cement: In accordance with ASTM F493.

2.06 PE TUBING AND FITTINGS
A. Materials:

1. PE Piping for air service rated at 160 PSI minimum.

2. Small Bore PE Tubing: Black flexible virgin PE tubing, OD copper tubing size. a. Plastic tubing ID as follows:
1) For NS 1/4 inch, ID of 0.170 inch.
2) For NS 5/16 inch, ID of 0.187 inch.
3) For NS 3/8 inch, ID of 0.251 inch.
4) For NS of ½ inch, an ID of 0.375 inch.

3. Fittings: Compression fittings, Dekoron E-Z; or equal.

4. Protective Sheath: Manufacturers: One of the following or equal:
a. Dekoron, "Poly-Cor."
b. Parker Hannifin Corp./Fluidconnector Products, Parflex Division, Multitube.

5. Plug-in Fittings for Connection to Instruments: Brass quick-connect fittings.

2.07 PE PIPING FOR UNDERGROUND GAS DISTRIBUTION
A. Materials:

Page 806 of 1480 ends

May, 2026 15265-6 Septage Hauling and Receiving Station Final

1. Extra High Molecular Weight (EHMW) High Density Polyethylene (HDPE) for gas distribution.

2. Manufacturers: One of the following or equal:
a. Polypipe GDB30 PE3608 Gas Pipe
b. DuPont.
c. Amsted Industries, Inc., Plexco.

3. Design Pressure Rating of 125 PSIG at 70 F.

4. PE Piping and Tubing for Underground Gas Distribution: Manufactured from a compound conforming to ASTM D1248 Type III Category 5, PE 3608. a. Pipe: In accordance with ASTM D2513.
b. Maximum SDR: 11.

5. Fittings: In accordance with ASTM D2513 for socked fusion joints, and ASTM D3261 for butt fusion joints.

2.08 PE PIPING FOR DRAIN, WASTE, AND VENT
A. General:

1. Pipe and Fittings: High density polyethylene.

2. Dimensions of Pipe and Fittings: Based on controlled outside diameter in accordance with ASTM F714.
a. SDR: Equal to or less than 11.

B. Materials:

1. Manufacturers: One of the following or equal:
a. DuPont, Sclairpipe.
b. Polaris, Duratuff; or equal.
1) Pipe, Fittings, and Adapters: Furnished by the same manufacturer, and compatible with components in the same system and with components of other systems to which connected.

2. Polyethylene: In accordance with ASTM D1248, Type III, Class C, Category 5, Grade P34; listed by the Plastic Pipe Institute under the designation PE 3408; and have a minimum cell classification, in accordance with ASTM D3350, of 345434C. a. Pipe and Fittings: Manufactured from material with the same cell classification.

2.09 BRAIDED VINYL TUBING (BRV)
A. General:

1. Tubing for chemical service.

2. Synthetic fiber braid sandwiched between two layers of plasticized PVC.

3. Rated for working pressure of 176 psi for tubing sizes one inch OD or less.

4. Pipe diameters indicated on pipe schedule are inside diameters.

5. Fittings shall be PVC inserts with 316 stainless steel hose clamps.

6. Pipe diameters as indicated below.

ID (in) OD (in) Wall Thickness (in)

0.375 0.5625 0.09375

0.5 0.75 0.125

0.75 1.0 0.125

1.0 1.3125 0.15625

2.10 SOURCE QUALITY CONTROL

Page 807 of 1480 ends

May, 2026 15265-7 Septage Hauling and Receiving Station Final
A. PVC Piping, Schedule Type:

1. Mark pipe and fittings in accordance with ASTM D1785.

B. PVC Piping, Class Type:

1. Test pipe to withstand, without failure, 600 pounds per square inch, gauge, hydrostatic pressure for a minimum of 5 seconds.

2. Test integral bell with the pipe.

C. PVC Gravity Sewer Piping:

1. Mark pipe and fittings in accordance with ASTM D3034. Also mark the production control code.

PART 3 EXECUTION

3.01 INSTALLATION
A. General:

1. Where not otherwise specified, install piping in accordance with ASTM F645, or manufacturer's published instructions for installation of piping, as applicable to the particular type of piping.

2. Provide molded transition fittings for transitions from plastic to metal or IPS pipe.

Do not thread plastic pipe.

3. Locate unions where indicated on the Drawings, and elsewhere where required for adequate access and assembly of the piping system.

4. Provide serrated nipples for transition from plastic pipe to rubber hose.

B. Installation of PVC Piping, Schedule Type:

1. Solvent weld joints in accordance with ASTM D2855.

2. Install piping in accordance with manufacturer's published instructions.

C. Installation Of PVC Piping, Class Type:

1. Install piping in accordance with the Appendix of AWWA C 900 complemented with manufacturer's published instructions.

2. Provide for contraction and expansion at each joint with a rubber ring and integral thickened bell as part of each joint.

D. Installation of PVC Gravity Sewer Piping.

1. Install piping in accordance with manufacturer's published instructions, as modified and complemented herein.

2. Install pipe and fittings not later than 4 months after their manufacture.

3. Provide for contraction and expansion at joints with a gasket ring.

4. Provide plugs or caps for stubs and branch pipes left unconnected to laterals.

5. Lubricate and assemble joints in accordance with the pipe manufacturer's published instructions.

6. Make connections to manholes with a manhole gasket that prevents infiltration and exfiltration through the penetrations.
a. Provide opening for connection large enough to allow subsequent grouting around the manhole gasket.
b. Grout around the manhole gasket and seal the opening.

E. Installation of CPVC Piping:

1. Clean dirt and moisture from pipe and fittings.

2. Bevel pipe ends in accordance with manufacturer's instructions with chamfering tool or file. Remove burrs.

Page 808 of 1480 ends

May, 2026 15265-8 Septage Hauling and Receiving Station Final

3. Use solvent cement and primer formulated for CPVC.

4. Use primer on pressure and non-pressure joints.

5. Do not solvent weld joints when ambient temperatures are below 40 degrees Fahrenheit or above 90 degrees Fahrenheit unless solvent cements specially formulated for these conditions are utilized.

F. Installation of Polyethylene (PE) Tubing and Fittings:

1. Install small bore PE tubing in accordance with manufacturer's printed instructions, in neat straight lines, supported at close enough intervals to avoid sagging, and in continuous runs wherever possible.

2. Bundle tubing in groups of parallel tubes within protective sheath.

3. Tubes within protective sheath may be color coded, but protect tubing other than black outside the sheath by wrapping with black plastic electrician's tape.

4. Grade tubing connected to meters in 1 direction.

G. Installation of PE Piping for Underground Gas Distribution:

1. Socket fuse joints for piping equal or less than NPS 2.

2. Butt fuse joints for piping larger than NPS 2.

3. Install piping in accordance with requirements of the gas utility company and with manufacturer's published instructions.

H. Installation of PE Piping for Drain, Waste, and Vent:

1. Install piping as recommended in manufacturer's published instructions.

3.02 FIELD QUALITY CONTROL
A. Leakage Test for PVC Piping, Class Type:

1. Polyvinyl-chloride (PVC) piping, Class Type: Subject to visible leaks test and to pressure test with maximum leakage allowance, as specified in Section 15956.

2. Pressure Test with Maximum Leakage Allowance: Perform test after backfilling. a. Pressure: 125 pounds per square inch, gauge.
b. Maximum leakage allowance as follows, wherein the value for leakage is in gallons per 100 joints per hour:

NPS, Inches 1-1/2 2 2-1/2 3 4 6 8 10 12
Leakage 0.41 0.52 0.63 0.76 0.98 1.45 1.88 2.35 2.80
B. Mandrel Tests for PVC Gravity Sewer Piping:

1. Perform Initial Mandrel Test:
a. After cleaning and completion of other tests.
b. After placement and compaction of backfill.
c. Before construction of pavement or surfacing.
d. Not sooner than 30 days after pipe installation.
e. Not later than 60 days after installation.

2. Utilize a 9 rod mandrel with minimum length equal to NPS and diameter as follows:

Nominal Pipe Size (NPS) Mandrel Diameter, inches

Page 809 of 1480 ends

May, 2026 15265-9 Septage Hauling and Receiving Station Final
Nominal Pipe Size (NPS) Mandrel Diameter, inches
6 5.50
8 7.37
10 9.21
12 10.96
15 13.56

3. Test Procedure: Pull the mandrel through the line under test by 1 person, by hand, with reasonable effort, without the aid of mechanical equipment.

4. Failing Test: Where the mandrel test is not successful, remove and replace the section of piping with the obstruction, and test the piping again, including visible leaks test, pressure test with maximum leakage allowance, mandrel tests, and other specified tests.
a. Correction of excessive deflection or obstructions by methods other than removal of the affected piping and replacement of the removed piping with new piping will not be accepted.

END OF SECTION

Page 810 of 1480 ends
Page 811 of 1480 ends

May, 2026 15956-1 Septage Hauling and Receiving Station Final
SECTION 15956

PIPING SYSTEMS TESTING
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Test requirements for piping systems.

B. Related Sections:

1. Section 01500 - Temporary Facilities and Controls.

2. Section 15052 - Basic Piping Materials and Methods.

1.02 REFERENCES
A. Uniform Plumbing Code (UPC).

B. National Fuel Gas Code: ANSI Z 223.1 or NFPA 54.

C. American National Standards Institute/American Society of Mechanical Engineers (ANSI/ASME):

1. B31.8 - Gas Transmission and Distribution Piping Systems.

2. B31.1 - Power Piping.

3. B31.3 - Process Piping.

D. Uniform Mechanical Code (UMC).

1.03 TESTING REQUIREMENTS
A. General Requirements:

1. Testing requirements are stipulated in Laws and Regulations; are included in the Piping Schedule in Section 15052; are specified in the specifications covering the various types of piping; and are specified herein.

2. Requirements in Laws and Regulations supersede other requirements of Contract Documents, except where requirements of Contract Documents are more stringent, including higher test pressures, longer test times, and lower leakage allowances.

3. Test plumbing piping in accordance with Laws and Regulations, the Uniform Plumbing Code, and UL requirements.

4. Test Natural Gas or Digester Gas Piping:
a. For less than 125 pounds per square inch gauge working pressure, test in accordance with Uniform Mechanical Code or the National Fuel Gas Code, whichever is more stringent.
b. For 125 pounds per square inch gauge or greater working pressure, test per ANSI/ASME B31.3 or ANSI/ASME B31.8, whichever is more stringent.

5. When testing with water, the specified test pressure is considered to be the pressure at the highest point of the piping section under test. Lower test pressure as necessary to prevent testing the lowest point above a safe test pressure.

B. Furnish necessary personnel, materials, and equipment, including bulkheads, restraints, anchors, temporary connections, pumps, water, pressure gauges, and other means and facilities required to perform tests.

Page 812 of 1480 ends

May, 2026 15956-2 Septage Hauling and Receiving Station Final
C. Water for Testing, Cleaning, and Disinfecting:

1. Water for testing, cleaning, and disinfecting will be provided as specified in Section 01500.

D. Pipes to Be Tested: Test only those portions of pipes that have been installed as part of this Contract. Test new pipe sections prior to making final connections to existing piping. Furnish and install test plugs, bulkheads, and restraints required to isolate new pipe sections. Do not use existing valves as test plug or bulkhead.

E. Unsuccessful Tests:

1. Where tests are not successful, correct defects or remove defective piping and appurtenances and install piping and appurtenances that comply with the specified requirements.

2. Repeat testing until tests are successful.

F. Test Completion: Drain and leave piping clean after successful testing.

G. Test Water Disposal: Dispose of testing water at location designated by OWNER in accordance with requirements of federal, state, county, and city regulations governing disposal of wastes in the location of the Project and disposal site.

1.04 SUBMITTALS
A. Schedule and Notification of Tests:

1. Submit a list of scheduled piping tests by noon of the working day preceding the date of the scheduled tests.

2. Notification of Readiness to Test: Immediately before testing, notify ENGINEER in writing of readiness, not just intention, to test piping. Have personnel, materials, and equipment specified in place before submitting notification of readiness.

1.05 SEQUENCE
A. Clean piping before pressure or leak tests.

B. Test gravity piping underground, including sanitary sewers, for visible leaks before backfilling and compacting.

C. Underground pressure piping may be tested before or after backfilling when not indicated or specified otherwise.

D. Backfill and compact trench, or provide blocking that prevents pipe movement before testing underground piping with a maximum leakage allowance.

E. Test underground piping before encasing piping in concrete or covering piping with slab, structure, or permanent improvement.

PART 2 PRODUCTS
Not Used.

Page 813 of 1480 ends

May, 2026 15956-3 Septage Hauling and Receiving Station Final
PART 3 EXECUTION

3.01 TESTING ALIGNMENT, GRADE, AND DEFLECTION
A. Alignment and Grade:

1. Visually inspect the interior of gravity piping with artificial light, reflected light, or laser beam.

2. Consider inspection complete when no broken or collapsed piping, no open or poorly made joints, no grade changes that affect the piping capacity, or no other defects are observed.

B. Deflection Test:

1. Pull a mandrel through the clean piping section under test.

2. Perform the test not sooner than 30 days after installation and not later than 60 days after installation.

3. Use a 9 rod mandrel with a contact length of not less than the nominal diameter of the pipe within one percent plus or minus.

4. Consider test complete when the mandrel can be pulled through the piping with reasonable effort by 1 person, without the aid of mechanical equipment.

3.02 AIR TESTING METHOD FOR PRESSURE PIPING
A. Air test piping, indicated with "AM" in the Piping Schedule, with air or another nonflammable or inert gas.

B. Test gas, air, liquefied petroleum gas, liquid chlorine, and chlorine gas piping by the air test method.

1. Test chlorine piping with dry air or nitrogen having a dew point of minus 40 degrees Fahrenheit or less. Supply temporary air driers as necessary.

C. Test at pressure as specified in Piping Schedule in Section 15052.

1. Provide temporary pressure relief valve for piping under test. Set at the lesser of 110 percent of the test pressure or 50 pounds per square inch gauge over the test pressure.

2. Air method test pressures shall not exceed 110 percent of the piping maximum allowable working pressure calculated in accordance with the most stringent of ANSI/ASME B31.1, ANSI/ASME B31.3, ANSI/ASE B31.8, or the pipe manufacturer's stated maximum working pressure.

3. Gradually increase test pressure to an initial test pressure equal to the lesser of one-half the test pressure or 25 pounds per square inch gauge.

4. Perform initial check of joints and fittings for leakage.

5. Gradually increase test pressure in steps no larger than the initial pressure. Check for leakage at each step increase until test pressure reached.

6. At each step in the pressure, examine and test piping being air tested for leaks with soap solution.

7. Consider examination complete when piping section under test holds the test pressure for 15 minutes without losses.

3.03 TESTING GRAVITY FLOW PIPING
A. Test Gravity Flow Piping Indicated with "GR" in the Piping Schedule, as Follows:

1. Unless Specified Otherwise, Subject Gravity Flow Piping to the Following Tests:
a. Alignment and grade.
b. For plastic piping test for deflection.

Page 814 of 1480 ends

May, 2026 15956-4 Septage Hauling and Receiving Station Final
c. Visible leaks and pressure with maximum leakage allowance, except for storm drains and culverts.

2. Inspect piping for visible leaks before backfilling. Provide temporary restraints when needed to prevent movement of piping. Pressure test piping with maximum leakage allowance after backfilling.

3. With the lower end plugged, fill piping slowly with water while allowing air to escape from high points. Keep piping full under a slight head for the water at least 24 hours.
a. Examine piping for visible leaks. Consider examination complete when no visible leaks are observed.
b. Maintain piping with water, or allow a new water absorption period of 24 hours for the performance of the pressure test with maximum leakage allowance. c. After successful completion of the test for visible leaks and after the piping has been restrained and backfilled, subject piping to the test pressure for minimum of four hours while accurately measuring the volume of water added to maintain the test pressure.
1) Consider the test complete when leakage is equal to or less than the following maximum leakage allowances:
a) For Concrete Piping with Rubber Gasket Joints: 80 gallons per day per inch of diameter per mile of piping under test.
(i). Advise manufacturer of concrete piping with rubber gasket joints of more stringent than normal maximum leakage
allowance.
b) For Vitrified Clay and Other Piping: 500 gallons per day per inch of diameter per mile of piping under test.

3.04 TESTING HIGH-HEAD PRESSURE PIPING
A. Test piping for which the specified test pressure in the Piping Schedule is 20 pounds per square inch gauge or greater, by the high head pressure test method, indicated "HH" in the Piping schedule.

B. General:

1. Test connections, hydrants, valves, blowoffs, and closure pieces with the piping.

2. Do not use installed valves for shutoff when the specified test pressure exceeds the valve's maximum allowable seat differential pressure. Provide blinds or other means to isolate test sections.

3. Do not include valves, equipment or piping specialties in test sections if test pressure exceeds the valve, equipment or piping specialty safe test pressure allowed by the item's manufacturer.

4. During the performance of the tests, test pressure shall not vary more than plus or minus 5 pounds per square inch gauge with respect to the specified test pressure.

5. Select the limits of testing to sections of piping. Select sections that have the same piping material and test pressure.

6. When Test Results Indicate Failure of Selected Sections, Limit Tests to Piping:
a. Between valves.
b. Between a valve and the end of the piping.
c. Less than 500 feet long.

7. Test piping for minimum 2 hours for visible leaks test and minimum 2 hours for the pressure test with maximum leakage allowance.

C. Testing Procedures:

1. Fill piping section under test slowly with water while venting air. Use potable water for all potable waterlines and where noted on the Piping Schedule

Page 815 of 1480 ends

May, 2026 15956-5 Septage Hauling and Receiving Station Final

2. Before pressurizing for the tests, retain water in piping under slight pressure for a water absorption period of minimum 24 hours.

3. Raise pressure to the specified test pressure and inspect piping visually for leaks.

Consider visible leakage testing complete when no visible leaks are observed.

D. Pressure Test with Maximum Leakage Allowance:

1. Leakage allowance is zero for piping systems using flanged, National Pipe Thread threaded and welded joints.

2. Pressure test piping after completion of visible leaks test.

3. For piping systems using joint designs other than flanged threaded or welded joints, accurately measure the makeup water necessary to maintain the pressure in the piping section under test during the pressure test period. a. Consider the pressure test to be complete when makeup water added is less than the allowable leakage and no damage to piping and appurtenances has occurred.
b. Successful completion of the pressure test with maximum leakage allowance shall have been achieved when the observed leakage during the test period is equal or less than the allowable leakage and no damage to piping and appurtenances has occurred.
c. When leakage is allowed, calculate the allowable leakage by the following formula:

L = S x D x P1/2 x 133,200-1
wherein the terms shall mean:

L = Allowable leakage in gallons per hour.

S = Length of the test section in feet.

D = Nominal diameter of the piping in inches.

P = Average observed test pressure in pounds per square inches, gauge, at the lowest point of the test section, corrected for elevation of the pressure gauge.
x = The multiplication symbol.

3.05 TESTING LOW-HEAD PRESSURE PIPING
A. Test piping for which the specified test pressure is less than 20 pounds per square inch gauge, by the low head pressure test method, indicated "LH" in the Piping Schedule.

B. General:

1. Test pressures shall be as scheduled in Section 15052.

2. During the performance of the tests, test pressure shall not vary more than plus or minus 2 pounds per square inch gauge with respect to the specified test pressure.

3. Test connections, blowoffs, vents, closure pieces, and joints into structures, including existing bell rings and other appurtenances, with the piping.

4. Test piping for minimum 2 hours for visible leaks test and minimum 2 hours for the pressure test with maximum leakage allowance.

C. Visible Leaks Test:

1. Subject piping under test to the specified pressure measured at the lowest end.

Page 816 of 1480 ends

May, 2026 15956-6 Septage Hauling and Receiving Station Final

2. Fill piping section under test slowly with potable water while venting air.

3. Before pressurizing for the tests, retain water in piping under slight pressure for the water absorption period of minimum 24 hours.

4. Raise pressure to the specified test pressure and inspect piping visually for leaks.

Consider testing complete when no visible leaks are observed.

D. Pressure Test with Maximum Leakage Allowance:

1. Pressure test piping after completion of visible leaks test.

2. Accurately measure the makeup water necessary to maintain the pressure in the piping section under test during the pressure test period. a. Consider the pressure test to be complete when makeup water added is less than the allowable leakage of 80 gallons per inch of nominal diameter, per mile of piping section under test after 24 hours and no damage to piping and appurtenances has occurred.
b. Successful completion of the leakage test shall have been achieved when the observed leakage is equal or less than the allowable leakage and no damage to piping and appurtenances has occurred.

E. Optional Joint Test:

1. When Joint Testing Is Allowed by Note in the Piping Schedule, the Procedure Shall Be as Follows:
a. Joint testing will be allowed only for low head pressure piping.

2. Joint testing may be performed with water or air.

3. Joint test piping after completion of backfill and compaction to the top of the trench.

4. Joint Testing with Water:
a. Measure test pressure at the invert of the pipe. Apply pressure of 4 feet plus the inside diameter of the pipe in water column within 0.20 feet in water column.
b. Maintain test pressure for one minute.
c. Base the allowable leakage per joint on 80 gallons per inch nominal diameter, per mile of piping, per 24 hours equally distributed to the actual number of joints per mile for the type of piping.
d. Consider the pressure test to be complete when makeup water added is less than the allowable leakage.
e. Successful completion of the joint test with water shall have been achieved when the observed leakage is equal or less than the allowable leakage.

5. Joint Testing with Air:
a. Apply test pressure of 3 pounds per square inch gauge with a maximum variation of plus 0.20 and minus 0.00 pounds per square inch. b. Maintain test pressure for 2 minutes.
c. Consider the pressure test to be complete when the test pressure does not drop below 2.7 pounds per square inch for the duration of the test.

END OF SECTION

Page 817 of 1480 ends

May, 2026 16010-1 Septage Hauling and Receiving Station Final
SECTION 16010

ELECTRICAL REQUIREMENTS
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Electrical distribution system and utilization equipment.

B. Related Sections:

1. The Contract Documents are a single integrated document, and as such, all Divisions and Sections apply. It is the responsibility of the CONTRACTOR and its subcontractors to review all sections to ensure a complete and coordinated project.

2. Section 01612 - Seismic Design Criteria

3. Section 01614 – Wind Design Criteria

1.02 SYSTEM DESCRIPTION
A. Furnish and install a tested and working electrical system, substantially as indicated on the Drawings and as hereinafter specified. System includes all items not specifically mentioned in these Specifications or indicated on the Drawings or accepted Shop Drawings, but which are obviously necessary to make a complete working installation, and shall be deemed to be included herein.

B. Notify ENGINEER of discrepancies within the Contract Documents and discrepancies between the Contract Documents and actual field conditions.

C. The Specifications and Drawings indicate or specify minimum sizes of equipment, electric devices, and other components of electrical system, but the Specifications and Drawings do not indicate every offset and fitting, or every structural or mechanical difficulty that may be encountered during the execution of the Work.

D. Install equipment at locations indicated on the Drawings as closely as field conditions permit. Obtain accepted equipment submittal dimensions prior to installing pads, conduits, and cable trays.

E. Make minor variations to alignment of equipment and/or installation of raceway systems to avoid conflict with other portions of the Work.

F. Single Line Diagrams Indicate Circuit Voltages. Single line diagrams also indicate wire and conduit sizes, circuit protection rating, and other pertinent data. Use single line diagrams to resolve conflicts. When not indicated on the Drawings, provide grounding in accordance with NEC Article 250 and as specified in Section 16062.

G. Temporary Power:

1. Provide and maintain temporary power, lighting, and telephone systems as needed for construction as specified in Section 01500. Include weatherproof panel(s) for main breakers and electrical power distribution system.

Page 818 of 1480 ends

May, 2026 16010-2 Septage Hauling and Receiving Station Final

2. Install temporary wiring in accordance with NEC Article 305 with Type SO portable cable, watertight connections, and ground fault interrupting equipment. After construction is completed, remove temporary systems.

H. Structural Design:

1. For all equipment provide seismic calculations in accordance with Section 01612 and wind calculations in accordance 01614.

1.03 SUBMITTALS
A. Shop Drawings and Product Data: Include data on and details of control devices, fixtures, wire, cables, raceways, and other electrical equipment or material, specified or indicated on the Drawings.

B. Cutting and Patching Requests: Submit as specified in Section 01732.

C. Furnish submittals that are fully indexed with a tabbed divider for every component.

D. Project Record Documents: Submit in accordance with Section 01770. Include drawings of wiring terminations at electrical equipment including, but not limited to, terminal/junction boxes, revised Shop Drawings reflecting modifications made during progress of the Work including testing, and revised Specifications and Drawings with conductors identified identically as on the Specifications and Drawings and accepted Shop Drawings. Updated Shop Drawings shall include all drafting work.

E. Provide Complete as-built interconnection and loop drawings for all wiring installed on the project in both AutoCAD and PDF electronic formats.

F. Seismic Connection calculations for equipment and support connection details demonstrating compliance with specified structural design requirements in section 01612 and 01614.

G. Seismic and wind anchoring calculations for all electrical equipment and supports including manufactured standard supports and any support referencing typical details included with the contract drawings.

H. Acceptance Testing Information and Documents: Submit as specified in Section 16950.

1.04 QUALITY ASSURANCE
A. Regulatory Requirements: Perform electrical work, including connection to electrical equipment integral with mechanical equipment, in accordance with latest published requirements of the following codes and code/standard making organizations:

1. American National Standards Institute (ANSI).

2. American Society for Testing and Materials (ASTM).

3. Institute of Electrical and Electronics Engineers (IEEE).

4. Insulated Cable Engineers Association (ICEA).

5. National Electrical Code (NEC).

6. National Electrical Contractors Association (NECA).

7. National Electrical Safety Code (NESC).

8. National Electrical Manufacturers Association (NEMA).

9. National Fire Protection Association (NFPA).

10. State and local codes.

11. California Building Code (CBC).

Page 819 of 1480 ends

May, 2026 16010-3 Septage Hauling and Receiving Station Final
B. When applicable, materials and equipment used in performance of electrical work shall be listed or labeled by Underwriter's Laboratories or other equivalent, recognized, and independent testing laboratory, for the class of service intended.

C. Qualifications of Low Voltage Equipment Manufacturer:

1. Manufacturer of proposed product with components uniquely selected by engineering review.

2. Proprietary bussing and enclosure designs listed by UL in manufacturer's own file for minimum 15 years with satisfactory performance record.

3. Capable of providing warranty for assembly when built-up with components from various manufacturers.

1.05 DELIVERY, STORAGE, AND HANDLING
A. Ship electrical panels, switchgear, switchboards, motor control centers, variable frequency drives, and other electrical distribution equipment in sealed dust and moisture-proof plastic sheet enclosures. Equipment containing dirt, dust, water, grease, rust, or damaged parts or components may be rejected.

B. Provide for delivery, unloading, transportation, and storage of equipment until installation. Protect electrical and instrumentation equipment and panels from physical and environmental damage. Store and maintain equipment in a weatherproof building until installed.

C. Store electrical equipment, including switchgear, motor control centers, variable frequency drives, instrumentation control panels, and other enclosures that house electronic equipment rated for a specified ambient or environmental temperature range, in air conditioned buildings to protect equipment from temperatures above 90 degrees Fahrenheit and heated buildings to protect equipment from temperatures below 40 degrees Fahrenheit. Assume liability for the storage facilities or equipment stored therein.

D. Maintain storage facilities in neat condition with utilities. Maintain stored equipment in same condition as when received.

E. Provide continuous access for inspection of stored equipment.

1.06 SEQUENCING AND SCHEDULING
A. Sequence and Schedule as specified in Sections 01352, 01140, and progress schedule submitted as specified in Section 01324.

B. Coordinate work with ENGINEER to minimize downtime of existing operating equipment and electrical distribution system and to preclude unsafe operations. Notify OWNER 10 days prior to power interruptions. Coordinate downtime with OWNER.

C. Before work is performed on low voltage or medium voltage circuits, or in manholes containing low voltage or medium voltage circuits, identify and de-energize the circuits.

1.07 PROJECT SITE CONDITIONS
A. The following operating conditions are applicable for all equipment of this Specification.

Page 820 of 1480 ends

May, 2026 16010-4 Septage Hauling and Receiving Station Final

1. Humidity: 0-95 percent. Space heaters shall be provided to prevent condensation.

2. Ambient Temperature: Minus 20 degrees Celsius to plus 50 degrees Celsius.

3. Altitude: Sea level to 200 feet.

PART 2 PRODUCTS
Not Used.

PART 3 EXECUTION

3.01 PREPARATION
A. Cutting and Repairing: Cut and patch the Work as specified in Section 01732. Where it becomes necessary to cut into existing work for the purpose of making electrical installations, use core drills for making circular holes. Other demolition methods for cutting or removing shall be reviewed by the ENGINEER prior to starting the work.

3.02 INSTALLATION
A. Corrosion Protection:

1. Isolate dissimilar metals, except conduit and conduit fittings, that may come in contact, with neoprene washers, 9 mil polyethylene tape, or gaskets.

2. Restore factory finishes which are damaged or rusted to their original new condition in accordance with manufacturer's instructions.

B. Install electrical work prior to placing floors and walls. Provide all sleeves and openings through floors and walls required for passage of all conduits and other raceways.

Sleeves shall be rigidly supported and suitably packed or sealed to prevent ingress of wet concrete or water.

C. Provide all insets and hangers required to support raceways and other electrical equipment. If the inserts, hangers, sleeves, or openings, are improperly placed or installed, do all necessary work to rectify the errors.

3.03 CLEANING
A. Clean each piece of electrical equipment, existing and new, both inside and outside, and retouch equipment to match existing paint.

3.04 PROTECTION
A. Protect products and provide heat to eliminate condensation until acceptance by OWNER.

END OF SECTION

Page 821 of 1480 ends

May, 2026 16050-1 Septage Hauling and Receiving Station Final
SECTION 16050

BASIC ELECTRICAL MATERIALS AND METHODS
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Basic electrical materials and methods.

B. Related Sections:

1. Section 01612 - Seismic Design Criteria

2. Section 01614 – Wind Design Criteria

1.02 REFERENCES
A. American Society for Testing Materials (ASTM):

1. A 525 - Specification for General Requirements for Steel Sheet, Zinc-Coated (Galvanized), by Hot-Dip Process.

B. National Electrical Manufacturers' Association (NEMA).

1.03 SYSTEM DESCRIPTION
A. Design Responsibility:

1. The CONTRACTOR providing the electrical support systems shall be considered the designer of the support systems. Typical details included on the contract documents are for minimum standard for style, size, and materials and shall be used as a guide for the CONTRACTOR in designing the specific electrical support systems utilized on the project.
a. Seismic and Wind Design Criteria: As specified in Section 01612 and 01614 as specified for all electrical support systems utilized for the project, including any typical electrical support details included on the contract documents that are actually utilized.

2. All electrical supports shall be minimum 304 stainless steel unless otherwise noted on the drawings.

1.04 SUBMITTALS
A. Shop Drawings: Prepare detailed shop drawings illustrating the layout of the support system and identifying the components of the support system. Include schedule, indicating where supports will be installed, and drawings of electrical support system components.

B. Seismic and wind design calculations and details need to be provided per Section 1.03 above.

C. Furnish Submittals in accordance with Sections 01330 and 16010.

D. Product Data showing conformance with project specifications.

1.05 WARRANTY

Page 822 of 1480 ends

May, 2026 16050-2 Septage Hauling and Receiving Station Final
A. Warranty: Minimum warranty for all equipment to be free of defects in material and workmanship for 1 year from the date of provisional acceptance for on-going municipal operational use of the equipment by the OWNER. Warranty shall cover parts and labor.

Provide longer warranties when specified in the individual equipment sections.

B. Where warranty exceeds 1 year, manufacturer’s warranty shall be issued in the OWNER’s name beginning on the date of provisional acceptance for on-going municipal operational use of the equipment by the OWNER.

C. Provisional acceptance for on-going municipal operational use shall require substantial completion for those elements to be utilized to maintain municipal operations during construction; pass all acceptance testing and all related punch list items shall be completed to the satisfaction of the ENGINEER and OWNER; and the OWNER shall agree in writing to provisionally accept those elements before operational transitioning occurs. Provisional acceptance is limited to those elements described in the written acceptance from the OWNER.

1.06 EXTRA MATERIALS
A. Furnish and install a minimum of 25 percent spare terminal blocks in each terminal/junction box, controls cabinet, PLC cabinet, and Motor Control Centers.

B. Allow a minimum of 15 percent extra wiring of each size.

C. Allow a minimum of 15 percent extra conduit of each size.

PART 2 PRODUCTS

2.01 MANUFACTURERS
A. Unless specified otherwise indicated on the Drawings, the fabricator of major electrical equipment, such as lighting and distribution panelboards, switchgear, variable frequency drives, and motor control centers, shall also be the manufacturer of the major devices herein.

2.02 MATERIALS
A. Materials, equipment, and parts comprising any unit or part thereof specified or indicated on the Drawings shall be new and unused, of current manufacture, and of highest grade consistent with the industrial industry standards. Damaged materials, equipment, and parts are not considered to be new and unused and will not be accepted.

2.03 EQUIPMENT
A. Support Channels: 316 stainless steel.

1. Manufacturers: One of the following or equal:
a. Unistrut.
b. Superstrut.
c. Globe Strut.

B. Support Channel Bolts, Nuts, and Washers: 316 Stainless steel.

C. Non-fused Terminal Blocks: Sized as required for conductors.

1. Manufacturers: One of the following or equal:

Page 823 of 1480 ends

May, 2026 16050-3 Septage Hauling and Receiving Station Final
a. Square D Company.
b. Buchanan.

D. Fused Terminal Blocks: Circuit isolation, fused switch type, sized as required for conductors. Fuse size shall be based upon actual load and conductors to be protected.

1. Manufacturers: One of the following or equal:
a. Square D Company.
b. Buchanan.

E. Control Relays:

1. Industrial 600 volt, 10 ampere type with contact arrangement and operating coils of proper voltage as required by control circuit sequence; with minimum of 4 reversible-pole contacts; coils sealed by pressure molding.

2. Non-industrial or plug-in type control relays shall be prohibited unless accepted in writing.

3. Manufacturers: One of the following or equal:
a. Square D Co.
b. Cutler-Hammer.

F. Intrinsically Safe Relays:

1. Factory Mutual approved to allow the use of every type of remote pilot device located in Class 1, Division 1 or 2, hazardous areas by providing a pilot circuit incapable of releasing sufficient electrical energy to ignite gases and vapors classified in Groups A, B, C, and D.

2. Output relay with double pole, double throw continuous rating of 10 amperes at 120 volts alternating current], capable of operating on the voltage indicated.

3. Manufacturers: One of the following or equal:
a. B/W - Controls Series 53.
b. Cutler-Hammer - Powered Relay.

G. Nameplates:

1. Type: Black lamicoid with white letters.

2. Fastener: Round head stainless steel screws.

H. Automatic Equipment and High Voltage Warning Signs:

1. Type: Suitable for exterior use and meeting OSHA regulations.

I. Medium Voltage Circuit Raceway Labels: Vinyl plastic.

1. Manufacturers: One of the following or equal:
a. Brady.
b. Seton.

J. Underground Hazard Tape: 6 inches wide.

1. Manufacturers: One of the following or equal:
a. Panduit.

K. Arc Flash Hazard Labels

1. Material and sizes as specified in Section 16305.

PART 3 EXECUTION

3.01 GENERAL
A. Verify dimensions indicated on the Drawings. Actual locations, distances, and levels

Page 824 of 1480 ends

May, 2026 16050-4 Septage Hauling and Receiving Station Final
will be governed by actual field conditions. The CONTRACTOR shall also review information indicated on the Drawings for architectural, structural, yard, mechanical, and other specialties, and the accepted electrical and mechanical shop drawings, and shall adjust his work to conform to all conditions indicated thereon.

3.02 EQUIPMENT INSTALLATION
A. Anchor electrical equipment to building floors, electrical equipment foundations, or other supports by bolts and anchor bolts and studs.

B. Anchor each piece of electrical equipment with minimum 1/2 inch diameter Type 316 stainless steel bolts, anchor bolts, or studs. Acceptable connectors shall be furnished in each corner of each section of electrical equipment, minimum.

C. Where plates are embedded in concrete supporting electrical equipment, fasten electrical equipment to the embedded plates with minimum 1/2 inch diameter welded studs. Where required, the number of studs connecting the embedded plates to floors shall be increased as required based upon the calculations of seismic forces in order to resist the forces from the electrical equipment supplied. The additional studs shall be deemed as part of these Contract Documents.

3.03 TORQUING
A. After installing and before energizing electrical equipment, torque each bolted bus and cable connection in accordance with manufacturer's recommendations with calibrated torque wrenches. Include each bolt at each connection, both factory and field installed, for motor control centers, variable frequency drives, bus ducts, switchgear, switchboards, and other equipment installed.

3.04 CONDUCTOR FASTENERS
A. Use screw type conductor fasteners and other permanent, such as epoxy conductor adhesives, in junction or pull boxes, termination cabinets, panels, panelboards, switchboards, switchgear, motor control centers, variable frequency drives, or other enclosures containing electrical devices and/or conductors. Do not use glue-on type conductor fasteners.

3.05 SUPPORT CHANNELS
A. Install channels, as required for support of raceways, cable trays, device enclosures, and other electrical equipment.

B. Separate iron or steel supports from aluminum with 1/4 inch neoprene or other nonmetallic gaskets.

C. Paint field cuts and scratches of galvanized steel channels with a cold galvanizing spray paint.

3.06 TERMINAL BLOCKS
A. Furnish and install terminal blocks in control panels, cabinets, terminal/junction boxes, variable frequency drives, motor control centers, switchgear and similar equipment and identify the terminal blocks by numbering and labeling in accordance with accepted shop drawings. The terminal blocks shall be circuit isolation fused-switch type where

Page 825 of 1480 ends

May, 2026 16050-5 Septage Hauling and Receiving Station Final
indicated on the Drawings and as required.

3.07 NAMEPLATES
A. Furnish and install nameplates where indicated on the Drawings or specified.

B. Each disconnect means for service, feeder, branch, or equipment conductors and pushbutton stations shall have nameplates indicating its purpose or identifying the load and circuit numbers.

3.08 AUTOMATIC EQUIPMENT WARNING AND HIGH VOLTAGE SIGNS A. Place a warning ribbon or other effective means suitable for conditions above underground installations.

3.09 DEMONSTRATION
A. Demonstrate operation of equipment.

END OF SECTION

Page 826 of 1480 ends
Page 827 of 1480 ends

May, 2026 16062-1 Septage Hauling and Receiving Station Final
SECTION 16062

GROUNDING
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Grounding electrode systems, consisting of concrete encased bare ground conductors and ground rods. Equipment grounding conductors, ground connections and general requirements for grounding.

B. Related Sections

1. Refer to Section 16010

1.02 REFERENCES
A. National Electrical Code (NEC), Article 250 - Grounding.

PART 2 PRODUCTS

2.01 MATERIALS
A. Driven Ground Rods:

1. Copper-covered steel.

2. 3/4 inch diameter.

3. 10 feet long, minimum.

B. Ground Conductor: Bare copper.

C. Equipment Grounding Conductors: Conductors shall be same type and insulation as the load circuit conductors.

PART 3 EXECUTION

3.01 INSTALLATION
A. Bond electrical enclosures, including metallic raceways, panels, switchboards and other similar metallic panels, cases and devices associated with power, instrumentation, and control systems to the grounding electrode system.

B. Drive ground rods and install grounding conductors prior to construction of concrete slabs and duct banks.

1. Extend grounding conductors through concrete to accessible points for grounding equipment and electrical enclosures.

2. Install grounding system at each structure where switchgear, motor control centers, switchboards, panelboards, panels, or other electrical equipment are installed.

C. Provide either exothermic welded or mechanical connections for grounding cable to rods or cable.

Page 828 of 1480 ends

May, 2026 16062-2 Septage Hauling and Receiving Station Final
D. When size is not indicated on the Drawings, size grounding conductors in accordance with NEC Table 250-66 and Table 250-122.

E. Install a green insulated equipment grounding conductor, or multi-conductor cable with integral green insulated grounding conductor, with each feeder and branch circuit from the power source grounding means to the load equipment or device.

F. Install ground bushings at both ends of rigid conduit runs. Do not use locknuts. Bond ground bushings to the grounding system.

G. When not indicated on the Drawings, install grounding electrode systems in compliance with NEC-250, Part III.

H. Shield Grounding.

1. Shielded instrumentation cable shall have its shield grounded at one end only unless shop drawings indicate otherwise. The grounding point shall be at the control panel or at the power source end of the signal carried by the cable.

3.02 FIELD QUALITY CONTROL
A. Test ground resistance per NETA Standards, for entire system and at each building/structure where electrical equipment is installed.

B. Invite ENGINEER to witness ground resistance testing.

C. Where maximum allowable ground resistance of 3 ohms is exceeded, install additional grounding mats or ground rods until ground resistance is equal to or below maximum allowable ground resistance.

END OF SECTION

Page 829 of 1480 ends

May, 2026 16070-1 Septage Hauling and Receiving Station Final
SECTION 16070

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes Requirements for:

1. Mounting and supporting electrical equipment and components.

B. Related Sections:

1. Refer to Section 16050.

1.02 REFERENCES
A. Refer to Section 16010.

1.03 DEFINITIONS
A. Refer to Section 16010.

1.04 SYSTEM DESCRIPTION
A. Support Design Responsibility:

1. The CONTRACTOR providing the electrical support system shall be considered the designer of the support system. Typical details included on the contract documents are for general minimum standard for style, size, and materials and shall be used as a guide for the CONTRACTOR in designing the specific electrical supports utilized on the project.

2. Prepare design calculations utilizing the design criteria included in these specifications.

3. Prepare detailed shop drawings illustrating the layout of the support system and identifying the components of the support system.

4. Seismic Design Criteria: As specified in Section 01612 as specified for all electrical supports utilized for the project, including any typical electrical support details included on the contract documents that are actually utilized.

B. Design Requirements:

1. Conform to the requirements of the Building Code.

2. Demonstrate the Following using Generally Accepted Engineering Methods:
a. That the anchors to the structure are adequate to resist the loads generated in accordance with the Building Code and equipment requirements. b. That the required load capacity of the anchors can be fully developed in the structural materials to which they are attached.

3. Seismic Withstand Requirements:
a. Freestanding or wall-hung equipment shall be anchored in place by methods that will meet the requirements for the seismic design indicated in Section 01612.

4. Wind Withstand Requirements:
a. All exterior freestanding equipment shall be anchored in place by methods that will meet the requirements for wind design indicated in Section 01614. b. Minimum Safety Factor Against Overturning: 1.5.

Page 830 of 1480 ends

May, 2026 16070-2 Septage Hauling and Receiving Station Final
c. The foundation shall be capable of withstanding all anchor loads.

C. Performance Requirements:

1. Hangers and supports individually and as a system shall resist all weights and code required forces without deflections and deformations.

1.05 SUBMITTALS
A. Furnish submittals in accordance with Sections 01330 and 16010.

B. Product Data:

1. Anchoring and leveling criteria and recommendations for equipment manufacturers:
a. Include these requirements in the installation recommendation submittal required by Section 16010.

C. Shop Drawings:

1. Furnish complete dimensioned and scalable shop drawings of all supporting structures, trapezes, wall supports, etc.

2. Furnish complete anchoring details for pole lights, transformers, control panels, supporting structures, trapezes, wall supports all equipment in excess of 200- pounds and all freestanding supports:
a. Stamped by a Professional Engineer registered in the State where the project is being constructed.
b. Said submittals, by virtue of the fact that they bear the stamp of a registered engineer; will be reviewed for general consistency with the requirements shown in the contract Documents, but not for context, accuracy, or method of calculation.

3. Include data on attachment hardware and construction methods that will satisfy the design loading criteria.

D. Installation Instructions:

1. The written instructions must detail the complete installation of the equipment including rigging, moving, setting into place and anchoring.

2. Provide anchorage instructions and requirements for the equipment based on the seismic conditions of the site as specified in Section 01612:
a. Stamped by a Professional Engineer registered in the State where the project is being constructed.

E. Calculations:

1. All calculations shall be performed, signed and stamped by a Professional Engineer, Registered in the State where the project is being constructed and shall show that all specifications requirements are met. Said submittals, by virtue of the fact that they bear the stamp of a registered engineer, will be reviewed for general consistency with the requirements shown in the Contract Documents, but not for context, accuracy, or method of calculation.

1.06 QUALITY ASSURANCE
A. Refer to Section 16010.

1.07 DELIVERY, STORAGE, AND HANDLING
A. Refer to Section 16010.

Page 831 of 1480 ends

May, 2026 16070-3 Septage Hauling and Receiving Station Final

1.08 PROJECT OR SITE CONDITIONS
A. Refer to Section 16010

1.09 WARRANTY
A. Refer to Section 16010

1.10 SYSTEM STARTUP
A. Refer to Section 16010.

PART 2 PRODUCTS

2.01 MANUFACTURERS
A. One of the following or equal:

1. Kindorf.

2. Super Strut.

3. Power-Strut.

4. Unistrut.

5. B-Line.

6. Rob Roy.

7. Aickinstrut.

2.02 MATERIALS
A. All areas:

1. Supports and hardware fabricated from stainless steel.

2. All hardware, clamps, etc. shall be stainless steel.

B. Indoors, Outdoors, and Corrosive Areas, NEMA 4X:

1. Supports and hardware fabricated from stainless steel, fiberglass, or PVC coated galvanized steel.

2. All hardware, clamps, etc. shall be either stainless steel, PVC coated, or fiberglass and shall be of the same material as that of the strut.

C. Use fiberglass preformed channel when attaching conduits to basin walls when in direct contact with earth:

1. Pipe Hangers and clamps shall be fiberglass and designed for the preformed channel.

2. All hardware including threaded rod, couplers, nuts, bolts, etc. shall be stainless steel or fiberglass.

D. Outdoor installation materials must be suitable for use in direct sunlight.

2.03 ACCESSORIES
A. Anchors:

1. Refer to Section 05120.

Page 832 of 1480 ends

May, 2026 16070-4 Septage Hauling and Receiving Station Final

2.04 FIELD FABRICATION
A. Re-coat all drilled holes and cut surfaces on PVC coated and FRP materials.

2.05 FINISHES
A. Paint and finish all supporting structures in conformance with the Painting and Finishing Sections of the Contract Documents.

PART 3 EXECUTION

3.01 INSTALLATION
A. Refer to Section 16010
B. General:

1. Equipment Anchoring:
a. Install equipment in accordance with the printed recommendations of the equipment manufacturer’s literature, including anchoring methods and leveling criteria.
b. Brace and anchor freestanding equipment supports using methods that provide structural support based on the seismic loads and wind loads as indicated in Sections 01612 and 01614:
1) Lateral deflection at top of supports not to exceed support height divided by 210 unless approved by the ENGINEER.
c. Provide fabricated steel support pedestals for wall mounted panels that weigh more than 500 pounds:
1) Fabricate pedestals out of welded angle, tube sections, or preformed channel.
2) If the supported equipment is a panel or cabinet, the pedestal shall match supported equipment in physical appearance and dimensions. d. Provide transformers hung from stud walls and weighing more than 300 pounds with auxiliary floor supports.

2. Furnish all conduit racks and trapeze structures needed to support the conduits from the building walls or ceiling. Group conduits and position on racks to minimize crossovers, etc.:
a. Provide the necessary sway bracing to keep trapeze type structures from swaying.

3. Mount all pull boxes, switches, panelboards, control panels, instruments, etc. in any damp or wet location on minimum of 7/8 inch stainless steel or fiberglass preformed mounting channel. Mount channel vertically along the vertical length of the device so that any water or moisture may run freely behind the device.

4. Concrete housekeeping pads are required for all floor-standing electrical equipment and conduit penetrations through floor:
a. Pads shall be a minimum of 3.5 inches above the surrounding floor or grade unless otherwise noted.
b. Pads shall extend a minimum of 2 inches beyond the extent of the equipment in all directions.
c. Pads shall be sized for the actual equipment furnished and all future equipment identified on the Contract Drawings.
d. All edges of the housekeeping pad shall be chamfered.

Page 833 of 1480 ends

May, 2026 16070-5 Septage Hauling and Receiving Station Final
C. Raceway:

1. Install all raceway cabinets, boxes, fixtures, and other appurtenances parallel or perpendicular to building lines and level and plumb.

2. Mount all raceways, cabinets, boxes, fixtures, instruments, devices, etc. on CONTRACTOR-fabricated racks unless otherwise shown on the Contract Drawings.

3. All raceways shall be supported directly from building structure. Do not suspend raceways or equipment from piping or duct work.

D. Anchor Methods:

1. Solid Concrete: Epoxy anchors or cast in place anchor bolts. 316 stainless steel anchors.

2. Metal surfaces: Machine screws or bolts.

3. Hollow masonry units: Epoxy anchors or cast in place anchor bolts. 316 stainless steel anchors.

E. Support Luminaries from Structural Elements Capable of Carrying the Total Weight:

1. Provide ceiling or pendent mounted high intensity discharge luminaries with a separate safety chain connecting the lens, reflector, ballast etc. to the building structure.

F. Obtain permission from ENGINEER before drilling or piercing a structural concrete member.

G. Plumbers perforated strap or tape is not acceptable.

H. When supporting devices on metal or wood stud construction bridge studs with mounting channel and mount the devices to the mounting channel.

3.02 FIELD QUALITY CONTROL
A. Refer to Section 16010.

3.03 PROTECTION
A. Refer to Section 16010.

END OF SECTION

Page 834 of 1480 ends
Page 835 of 1480 ends

May, 2026 16075-1 Septage Hauling and Receiving Station Final
SECTION 16075

ELECTRICAL IDENTIFICATION
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Identification of electrical and instrumentation equipment, conductors, and cables.

1.02 REFERENCES
A. National Electrical Code (NEC):

1. Article 110 - 22 - Disconnecting Means.

2. Article 210 - 4 - Multiwire Branch Circuits.

3. Article 200 - Use and Identification of Grounded Conductors.

4. Article 408 - Switchboards and Panelboards.

5. Article 300 - Wiring Methods.

1.03 SUBMITTALS
A. Refer to Section 16050.

B. Product Data: Include tagging system, labels, markers, and hazard tape.

C. Project Record Documents:

1. Document wire, cable, and conductor tags, and bundle tags installed in accordance with the Contract Documents.

2. Document installed wire, cable, and conductor tags and bundle tags when not specifically indicated.

3. Indicate on Record Drawings deviations from accepted shop drawing conductor identification.

1.04 QUALITY ASSURANCE
A. Refer to Section 16010.

PART 2 PRODUCTS

2.01 LABELS
A. Manufacturers: One of the following or equal:

1. Brady.

2. Seton.

B. Type: Sleeve type.

2.02 CONDUCTOR AND CABLE MARKERS
A. Manufacturers: One of the following or equal:

1. Brady.

2. Seton.

Page 836 of 1480 ends

May, 2026 16075-2 Septage Hauling and Receiving Station Final
B. Type: Slip-on PVC sleeve or strap-on type.

C. Printed using Brady marker "XC PLUS," or equal.

D. Markers used in tunnels or other wet locations shall be on heat-shrinkable marking sleeves.

E. Use self-laminating vinyl on white background for markers within electrical equipment such as panels, termination cabinets, motor control centers.

2.03 CONDUIT MARKERS
A. Manufacturers: One of the following or equal:

1. Almtek: Almtek Type Mini-Tag.

2. Red Lamacoid name plates with stainless steel wire attachment.

PART 3 EXECUTION

3.01 CIRCUIT IDENTIFICATION
A. This section applies to all new Contractor and new Owner installed wire on the project.

B. Identify 3-phase system conductors and cables as Phases A, B, and C and identify 1-phase system conductors and cables at electrical equipment including, but not limited to, switchgear, switchboards, panelboards, motor control centers, variable frequency drives, and motors.

1. Match OWNER's existing electrical system identification scheme or meet requirements of the authority responsible for the project.

2. 3-Phase 480 Volts AC System Conductors: Phase A, Brown; Phase B, Orange; Phase C, Yellow.

3. 3-Phase Conductors for 120/208 VAC Circuits: Phase A, Red; Phase B, black, Phase C, Blue.

4. Neutral Conductor: White for 120 VAC and gray for 277 VAC.

5. Insulated Equipment Grounding Conductor: Green.

6. General Purpose AC Control Conductors: Red.

7. General Purpose DC Control Conductors: Violet
C. Use control cable or instrumentation cable for alarm annunciator field wiring as indicated on the Drawings and specified. Use color coding and phasing consistent throughout the site. Bus bars at panelboards and motor control centers to be connected Phase A-B-C, top to bottom, or left to right facing connecting lugs.

D. Conductors Number 2 American Wire Gauge (AWG) and smaller to be factory color coded with a separate color for each phase and neutral, which shall be used consistently throughout the system. Larger cables to be coded by the use of colored tape.

E. In addition to color coding, for all 1-phase and 3-phase systems, identify each cable (single or multi-conductor) and conductor at each end, in each manhole, pullbox, cable tray, or other component of the raceway system. This identification is applicable to all power, control, alarm, signal, network, and instrumentation cables, and conductors.

Page 837 of 1480 ends

May, 2026 16075-3 Septage Hauling and Receiving Station Final
F. Identify each cable (single or multi-conductor) and groups or bundles of individual single conductors in each manhole, pullbox, cable tray or other component of the raceway system with circuit identification markers. Implement a "from-to" cable/conductor bundle tagging system as part of this identification effort.

G. Identify each individual conductor at each termination. This includes such locations as switchgear, switchboards, motor control centers, variable frequency drives, control panels, junction/terminal boxes, all field devices, and all other locations where conductors are terminated. Identify the termination of these conductors in accordance with the accepted shop drawings. Tag conductors with sleeve type labels.

H. Where more than 1 nominal voltage system exists, identify each ungrounded system conductor by phase and system. Permanently post means of identification at each branch-circuit panelboard, switchboard, switchgear, motor control center, or other type of power distribution equipment.

I. Include the following minimum information for wire and cable identification.

1. Circuit number or load identification tag number.

2. Origin (from source).

3. Destination (to load).

J. Identify each individual conduit at each end of the conduit run, including all spare conduits. This includes at such locations as switchgear, switchboards, motor control centers, panelboards, variable speed drives, manholes, and pull boxes. Conduits shall have lamacoid name plate with stainless steel wire attachment to the conduit. Nam plate shall have the circuit number for each circuit run in the conduit. Provide multiple name plates on conduits with a large number of circuits within them. Review with Engineer prior to install.

END OF SECTION

Page 838 of 1480 ends
Page 839 of 1480 ends

May, 2026 16123-1 Septage Hauling and Receiving Station Final
SECTION 16123
600 VOLT OR LESS WIRES AND CABLES
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes:

1. 600 Volt Class wire and cable.

2. Instrumentation Class wire and cable.

3. Fire Alarm wire and cable.

4. Communication wire and cable.

B. Related Sections:

1. Refer to Section 16010.

1.02 REFERENCES
A. American Society for Testing and Materials (ASTM):

1. B3 - Standard Specification for Soft or Annealed Copper Wire.

2. B8 - Specification for Concentric-LayBStranded Copper Conductors, Hard, Medium-Hard, or Soft.

B. Insulated Cable Engineers Association (ICEA).

C. National Electrical Code (NEC):

1. Article 250 - Grounding.

2. Article 310 - Conductors for General Wiring.

3. Article 760 - Fire Alarm Systems.

1.03 SUBMITTALS
A. Refer to Section 16050.

B. Shop Drawings: Show splice locations.

C. Product Data: Include wires, cables, pulling compounds, and splicing materials.

1.04 QUALITY ASSURANCE
A. Refer to Section 16010.

B. All wires and cables shall be UL listed and labeled.

1.05 WARRANTY
A. Provide minimum 12 month warranty form date of final acceptance by the OWNER.

Page 840 of 1480 ends

May, 2026 16123-2 Septage Hauling and Receiving Station Final
PART 2 PRODUCTS

2.01 WIRE AND CABLE MATERIALS
A. Conductors: ASTM B8, soft drawn copper, maximum 12 months old, minimum 97 percent conductivity; American Wire Gauge (AWG) sizes as indicated on the Drawings, Class B or C stranded.

B. Insulation Thickness: Minimum specified by Article 310 of the National Electrical Code.

2.02 600-VOLT CLASS CABLE
A. Power Wire and Cable:

1. Manufacturers: One of the following or equal:
a. Okonite Company.
b. BICC Cable.
c. Southwire Company.
d. General Cable Corporation.

B. Control Wire and Cable:

1. Manufacturers: One of the following or equal:
a. Okonite Company.
b. BICC Cable.
c. Southwire Company.
d. General Cable Corporation.

C. Insulation for Individual Wires or Multiple Conductor Cable for Power and Control Circuits: Type THWN insulation as defined by NEC Table 310-13.

D. Jackets for Multiple Conductor Cable for Power and Control Circuits: Type PVC.

E. Multi-Conductor Cable Insulated Grounding Conductors:

1. Color: Integral green.

2. Size: In accordance with 250-122 of the National Electrical Code.

F. Solid-conductor wire, Number 10 AWG and smaller, may be used for lighting and receptacle circuits.

2.03 INSTRUMENTATION CLASS CABLE
A. Single Pair or Triad Applications:

1. Manufacturers: One of the following or equal:
a. The Okonite Company, Okoseal-N Type P-OS.
b. Equivalent manufactured by Cooper Industries, Belden Wire and Cable Division.

B. Multiple Pair or Triad Applications:

1. Manufacturers: One of the following or equal:
a. The Okonite Company, Okoseal-N Type SP-OS.
b. Equivalent manufactured by Cooper Industries, Belden Wire and Cable Division.

C. Approved for cable tray installation in accordance with the National Electrical Code.

Page 841 of 1480 ends

May, 2026 16123-3 Septage Hauling and Receiving Station Final
D. Number of Individually Shielded, Twisted Pairs and Triads: As indicated on the Drawings.

E. Voltage Rating: 600 volts.

F. Cable Type: TC.

G. Temperature Rating: 90 degrees Celsius dry location, 75 degrees Celsius wet location.

H. Conductors: Bare, soft annealed copper in accordance with ASTM B3, Class B, 7- strand concentric in accordance with ASTM B8.

I. Conductor Insulation: Flame-retardant polyvinyl chloride, 15 mils nominal thickness, with nylon jacket 4 mils nominal thickness, 90 degrees Celsius temperature rating in accordance with Underwriter's Laboratory Subject 1277.

J. Color Code: Provide conductor color code as specified in Section 16075.

K. Single Pair or Triad Shielding:

1. Group Shielding: Minimum 1.35 mil double-faced aluminum/synthetic polymerbacked tape overlapped to provide 100 percent coverage.

2. Drain Wire: 7-strand tinned copper drain wire, 2 sizes smaller than conductor.

L. Multiple Pair or Triad Shielding:

1. Group Shield: 1.35 mil aluminum-polyester tape overlapped to provide 100 percent coverage and a 7-strand tinned copper drain wire, 2 sizes smaller than conductor.

Completely isolate group shields from each other.

2. Cable Shield: 2.35 mils double-faced aluminum and synthetic polymer backed tape overlapped to provide 100 percent coverage and a 7-strand tinned copper drain wire, same size as conductors.

M. Jacket: Black, flame-retardant per Underwriter's Laboratory Subject 1277, 90 degrees Celsius temperature rating, rip cord laid longitudinally under jacket to facilitate removal.

N. Conductor Size: Number 16 AWG minimum unless otherwise indicated on the Drawings.

O. Numerically identify every conductor within each pair and triad.

2.04 NETWORK CABLE
A. Provide Cat-6a STP Shielded Twisted Pair, 4 pair network cable.

2.05 ALL WEATHER INSTRUMENT CABLE
A. Instrument cable between manufacturer sensors and instrument analyzers run without conduit.

B. Manufacturers: One of the following or equal:

1. The Draka Marine Oil Gas international: BOSTRIG Type P signal cable 600V.

C. Characteristics:

1. 4 pair 18 gauge wires.

2. Suitable in Class 1 Division 1 locations.

Page 842 of 1480 ends

May, 2026 16123-4 Septage Hauling and Receiving Station Final

3. Soft annealed stranded tin copper conductors.

4. Insulation: Bostrig Type P chemically cross-linked polyolefin (XPLO) meeting IEEE 1560 (2001).

5. Shield: Aluminum/polyester tape with drain wire, 100% coverage, applied over each twisted pair and the cable core.

6. Jacket: Flame retardant Arctic Neoprene, complying with Type N Neoprene as required per IEEE-1580 (2001).

7. Armor: Braided bonze in accordance with IEEE 1580 (2001).

8. Sheath: Flame Retardant Arctic Neoprene applied over the armor.

9. Super resistant to oil, abrasion, moisture, mud, crush, and impact.

10. Meets IEEE standards for 600 V/IEC standards for 0.6/1kW.

11. UL listed.

2.06 RELATED MATERIALS
A. Splicing Material: In conformance with ANSI C119.1, IEEE 383, and ICEA 5-19-81;

1. Manufacturers: One of the following or equal:
a. Elastimold.
b. Thomas-Betts.
c. Raychem, FCSM Series.

B. Wire Nuts: Rated 600 volt with live-spring feature for tight fitting connections.

1. Manufacturers: One of the following or equal:
a. 3M.
b. Thomas and Betts.

C. Junction Boxes and Terminal Cabinets: As specified in Section 16134.

D. Pulling Compound: As recommended by conductor manufacturer.

2.07 WIRE AND CABLE FABRICATION
A. Permanently mark American Wire Gauge (AWG) size, grade of insulation, voltage, and manufacturer's name on outer covering at maximum 24 inch intervals.

B. Identify and mark conductors in accordance with NEC Article 310.

C. Color code wire and cable as specified in Section 16075.

1. Integrally color insulation for Number 2 AWG and smaller.

2. Wrap colored tape around cable larger than Number 2 AWG.

D. Fabricate cable ends with provisions for field testing.

2.08 SOURCE QUALITY CONTROL
A. Test full lengths in accordance with ASTM and ICEA Standards.

PART 3 EXECUTION

3.01 INSTALLATION
A. Install continuous circuit conductors from source to load without splices or terminations in intermediate manholes or pull boxes, except for Number 10 AWG and smaller conductors for lighting and receptacles.

Page 843 of 1480 ends

May, 2026 16123-5 Septage Hauling and Receiving Station Final
B. Splices:

1. Where splices are necessary because of extremely long wire or cable lengths that exceed standard manufactured lengths, install and label junction boxes for power conductors or termination cabinets for control and instrument conductors.

2. Power and control conductors routed in common raceways may be spliced in common junction boxes. Install NEMA 4X junction and terminal boxes in wet and outdoor locations. Clearly label junction and terminal boxes containing splices with the word "SPLICE." Leave sufficient slack at junction boxes and termination boxes to make proper splices and connections. Do not pull splices into conduits.

C. Properly coat wires and cables with pulling compound before pulling into conduits and prevent mechanical damage to conductors during installation.

3.02 600-VOLT CLASS CABLE
A. Size power conductors in accordance with National Electrical Code when sizes are not indicated on the Drawings.

B. Install minimum Number 12 AWG wiring for wire external to panels and motor control centers unless otherwise specified or indicated on the Drawings, and minimum Number 14 AWG for internal panel control wiring with Type MTW or SIS insulation, unless otherwise specified.

C. Do not exceed cable manufacturer's pulling tension and side-wall pressures.

D. Terminations and Splices (600 Volt or Less):

1. Terminations: Terminate control and instrument conductors in terminal boxes in accordance with Section 16134.

2. Splicing: Join conductors mechanically with splice connectors and install heatshrink type insulation. Splice conductors in accordance with manufacturer's instructions. Make waterproof heat shrink type splices in wet and below grade locations.

3. Splice or weld grounding conductors of different sizes.

4. Conductor Number 10 AWG and smaller for lighting and receptacle circuits may be spliced in junction boxes with wire nuts.

3.03 INSTRUMENTATION CLASS CABLE
A. Install instrumentation class cables in separate raceway systems. Install instrument cable in metallic conduit within non-dedicated manholes or pull boxes. Install cable without splices between instruments or between field devices and instrument enclosures or panels.

B. Do not make intermediate terminations, except in designated terminal boxes indicated on the Drawings.

C. Ground cable shields at only one location, typically at panels, not at field instruments.

3.04 SIGNAL CABLE AND CONDUIT INSTALLATION
A. Separate and isolate electrical signal cables from sources of electrical noise and power cables by minimum 12 inches.

Page 844 of 1480 ends

May, 2026 16123-6 Septage Hauling and Receiving Station Final

3.05 FIELD QUALITY CONTROL
A. Testing: perform functional testing of all electrical systems, and per NETA standards.

END OF SECTION

Page 845 of 1480 ends

May, 2026 16133-1 Septage Hauling and Receiving Station Final
SECTION 16133

CONDUITS
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes:

1. Galvanized rigid steel conduit,

2. Flexible conduit,

3. Polyvinyl chloride-coated rigid steel conduit, and rigid nonmetallic polyvinyl chloride conduit.

4. Rigid non-metallic (PVC)
B. Related Sections:

1. Refer to Section 16010.

1.02 REFERENCES
A. American National Standards Institute (ANSI):

1. C80.1 - Rigid Steel Conduit, Zinc Coated.

2. C80.3 - Electrical Metallic Tubing, Zinc Coated.

3. C80.5 - Rigid Aluminum Conduit.

B. National Electrical Code (NEC):

1. Article 348 - Electrical Metallic Tubing.

2. Table 300-5 - Minimum Cover Requirements (0 to 600 volts, Nominal).

3. Article 500 - Hazardous (Classified) Locations.

4. Table 300-50 - Minimum Cover Requirements (over 600 volts, Nominal).

C. National Electrical Manufacturers Association (NEMA):

1. RN-1 - Polyvinyl Chloride (PVC) Externally Coated Galvanized Rigid Steel Conduit and Intermediate Metal Conduit.

2. TC-2 Electrical Plastic Tubing and Conduit

3. TC-3 PVC Fittings for use with rigid PVC conduit and fittings

4. TC-13 Electrical non-metallic tubing
D. Underwriters Laboratories, Inc (UL):

1. UL 6 - Rigid Metal Conduit.

2. UL 651 – Schedule 40 and 80 rigid PVC conduit

3. UL 1 – Flexible metal conduit

1.03 SUBMITTALS
A. Refer to Sections 01330 and 16010.

B. Shop Drawings: Installation drawing including individual conduit numbers, routing, conduit sizes, circuit numbers contained in each conduit, and number and size of wires in each conduit.

C. Manufacturer's Quality Control Data: Include how products are inspected at work stations, defining quality process from receipt of raw material through shipping.

Page 846 of 1480 ends

May, 2026 16133-2 Septage Hauling and Receiving Station Final
D. Record Documents: Incorporate all changes in conduit routing on Conduit Drawings.

1.04 QUALITY ASSURANCE
A. Refer to Section 16010.

PART 2 PRODUCTS

2.01 CONDUIT
A. Galvanized Rigid Steel Conduit (GRC):

1. Domestic raw steel, made smooth, clean, and free of burrs and rough spots to enhance wire pulling; interior and exterior surfaces coated with solid, unbroken layer of zinc; threads hot dip galvanized after cutting; entire surface finish coated with secondary bichromate treatment applied over galvanizing able to extend surface protection and prevent oxidation; threads protected by color coded end caps to provide quick trade size identification.

2. Manufacturers: One of the following or equal:
a. LTV Steel Tubular Products Company, Galvite.
b. Triangle PWC, Inc.
c. Allied Tube and Conduit Corporation.
d. Western Tube and Conduit.

B. Liquid-tight Flexible Conduit: Grounding type, weatherproof, watertight, maximum 60 inch lengths.

1. Manufacturers: One of the following or equal:
a. AFC Cable Systems.
b. Electriflex.
c. Anaconda.

C. Polyvinyl Chloride-coated Rigid Steel Conduit:

1. Galvanized rigid steel conduit with coating conforming to ANSI C80.1 and UL 6; bendable without damage to coatings.

2. Manufacturers: One of the following or equal:
a. Robroy Industries.
b. OCAL, Inc.
c. Triangle Conduit and Cable.

D. Rigid Nonmetallic Polyvinyl Chloride Conduit:

1. High density, Schedule 40, 90 degrees Celsius, heavy-duty polyvinyl chloride, made from virgin polyvinyl chloride compound; maximum 6 grams per 100 grams smoke emission.

2. Manufacturers: One of the following or equal:
a. Carlon.
b. Triangle Conduit and Cable.

2.02 RELATED MATERIALS
A. Couplings, Connectors, and Fittings:

1. Threaded.

2. Manufactured with same materials and process as corresponding conduit.

B. Condulet Fittings:

Page 847 of 1480 ends

May, 2026 16133-3 Septage Hauling and Receiving Station Final

1. With wedge nut covers, weathertight when located outdoors or in wet or corrosive locations [indicated on the Drawings], matching type for corresponding conduit systems.

2. Manufacturers: One of the following or equal:
a. Crouse-Hinds.
b. Appleton.

C. Galvanized Rigid Steel Conduit Expansion Fittings for Exposed Locations:

1. Manufacturers: One of the following or equal:
a. OZ/Gedney, Type AX with jumper.
b. Appleton, Type XJ with Jumper.

D. Galvanized Rigid Steel Conduit Expansion Fittings at Structural Expansion Joints:

1. Manufacturers: One of the following or equal:
a. Spring City, Type D.
b. Crouse-Hinds, Type D.

E. Conduit Seals:

1. Manufacturers: One of the following or equal:
a. Appleton.
b. Crouse-Hinds.

F. Polyvinyl Chloride-coated Rigid Steel Conduit Couplings: One provided loose with each length of conduit.

G. Fasteners for Polyvinyl Chloride-Coated Rigid Steel Conduit: Polyvinyl chloride-coated steel fasteners with Type 316 stainless steel bolts, nuts, and hardware.

H. Fasteners for Galvanized Rigid Steel Conduit: 316 stainless steel fasteners with Type 316 stainless steel bolts, nuts, and hardware.

I. Conduit Mounting Strut:

1. Type 316 stainless steel.

J. Conduit Thruwall Seals:

1. 316 Stainless Steel.

2. Polyvinyl chloride oversize sleeve.

3. Manufacturers: One of the following or equal:
a. O-Z/Gedney.

2.03 POLYVINYL CHLORIDE-COATED RIGID STEEL CONDUIT FABRICATION A. Coat rigid steel conduit, conduit fittings, and hangers with polyvinyl chloride.

B. Conduit:

1. Ensure that surfaces, including galvanizing, remain intact and undisturbed on both inside and outside of conduit throughout preparation and application processing.

2. Bond polyvinyl chloride coating to outer surfaces of conduit except threads.

3. Provide bond between polyvinyl chloride coating and conduit surface that is greater than tensile strength of plastic.

4. Provide minimum 40 mil thick coating on conduit.

5. Coat interior of conduit and condulet fittings with nominal 2 mil thick corrosionresistant urethane finish.

Page 848 of 1480 ends

May, 2026 16133-4 Septage Hauling and Receiving Station Final

6. Coat threads with clear urethane finish.

C. Couplings:

1. Bond polyvinyl chloride coating to outer surfaces of couplings.

2. Extend polyvinyl chloride sleeve equal to outside diameter of uncoated conduit beyond both ends of coupling approximately 1 pipe diameter or 1-1/2 inches, whichever is smaller.

3. Provide minimum 40 mil thick coatings on couplings and sleeves.

4. Bond polyvinyl chloride coating to outer surface of conduit bodies and fittings.

5. Extend polyvinyl chloride sleeves from hubs.

6. Provide same coating thickness on conduit bodies, fittings, and sleeve walls as on couplings in length and thickness.

7. Coat covers on conduit bodies on both sides so covers are completely interchangeable.

8. Coat interior of conduit couplings, sleeves, and conduit bodies with corrosionresistant urethane finish.

D. Ensure that inside of conduit bodies remain undisturbed during processing and retain manufacturer's finish.

E. Polyvinyl Chloride Coated, Mounting Hardware, and Associated Fittings:

1. All mounting hardware and associated fittings shall be polyvinyl chloride coated in accordance with NEMA RN-1.

2. The polyvinyl chloride exterior coating shall have a normal thickness of 40 mils (.040 inch) except where part configuration or application otherwise dictate.

3. All fasteners for polyvinyl chloride coated fittings and mounting hardware shall be of the type 316 stainless steel.

2.04 SOURCE QUALITY CONTROL
A. Test and inspect rigid, hot-dip galvanized steel conduit during manufacture for conformance to UL 6 and ANSI C80.1.

PART 3 EXECUTION

3.01 INSTALLATION
A. Install conduit runs in accordance with schematic representation indicated on the Drawings and as specified. Modify conduit runs to suit field conditions, as accepted by the ENGINEER.

B. Install straight and true conduit runs with uniform and symmetrical elbows, offsets, and bends. Make changes in direction with long radius bends or with condulet fittings.

C. Install conduit runs so that runs do not interfere with proper and safe operation of equipment and not block or interfere with ingress or egress, including equipment removal hatches.

D. Expose conduit runs in buildings and structures, unless otherwise indicated on the Drawings.

E. Securely fasten exposed conduits with clamps or straps. Run exposed conduit on walls and ceilings only, parallel to planes of walls or ceilings. Do not run conduit diagonally.

Securely fasten exposed polyvinyl chloride-coated rigid steel conduits with Type 316

Page 849 of 1480 ends

May, 2026 16133-5 Septage Hauling and Receiving Station Final
stainless steel clamps or straps.

F. Use flexible conduit for short lengths required to facilitate connections between rigid conduit and motors, vibrating equipment, or control equipment.

G. Support conduit runs on water-bearing walls 1 inch away from wall on an accepted channel. Use hot-dip galvanized steel or stainless steel channels, consistent with type of conduit being installed. Do not run conduit in water-bearing walls unless otherwise indicated on the Drawings.

H. Thoroughly ream conduit after threads have been cut to remove burrs. Seal joints with accepted conductive sealant compound and make watertight. Set up joints tight. Use bushings or conduit fittings at conduit terminations.

I. Install runs between pull boxes or junction boxes with total bends equaling not more than 270 degrees. Install conduits as necessary to limit bends to not more than 270 degrees. Install NEC required pull boxes at locations acceptable to the ENGINEER.

Plug conduits brought into pull boxes, manholes, handholes, and other openings until used to prevent entrance of moisture. Cap spare conduits and provide plastic pulling tape below threaded cap. Provide bonding bushing and bond wire.

J. Provide appropriate hangers and fasteners to suit applications.

K. After complete installation of 2 inch and larger conduit runs, snake conduits with conduit cleaner equipped with a cylindrical mandrel of a diameter not less than 85 percent of nominal diameter of conduit. Remove and replace conduits through which mandrel will not pass.

L. Clean and ensure that new and existing conduit runs are not crushed or creased.

Verify internal dimensions of existing conduit prior to installation of conductors. Verify that no foreign objects or obstructions are present in conduit prior to installing conductors.

M. Install conduit system to provide firm mechanical assemblies with electrical conductivity throughout.

N. Install expansion fittings across expansion joints, including expansion joints at existing structures, and at other locations where necessary to compensate for thermal or mechanical expansion and contraction as indicated on the Drawings.

O. Install conduits complete between outlets, boxes, and circuit source before conductors are installed.

P. Install conduit thruwall seals where indicated on the Drawings.

Q. Conduit transition from underground PVC to above ground rigid or PVC coated rigid conduit shall occur underground with the sweep for the vertical portion of the conduit being rigid (PVC coated rigid conduit as scheduled) and all vertical portions of the conduit being rigid (PVC coated rigid conduit as scheduled).

3.02 POLYVINYL CHLORIDE-COATED RIGID STEEL
A. Attach cover to conduit body with Type 316 stainless steel screws.

Page 850 of 1480 ends

May, 2026 16133-6 Septage Hauling and Receiving Station Final
B. Where patching is required, apply 40 mil thick polyvinyl chloride coating in accordance with manufacturer's instructions.

C. Install and patch coated material holiday free and according to manufacturer’s recommended installation and patching instructions.

3.03 RIGID NONMETALLIC POLYVINYL CHLORIDE
A. Reinforce encasement as indicated on the Drawings. Install conduit supports at 30-inch intervals.

3.04 CONDUIT SEALS
A. Install conduit entering or leaving NEC Article 500 hazardous areas with conduit seals.

B. Install conduit seals in other hazardous locations as required by NEC.

C. Provide drains on conduit seals in locations where water accumulation is likely to enter a device or enclosure.

3.05 SCHEDULES
A. Conduit Sizes: Unless otherwise indicated on the Drawings, conduits shall be in accordance with NEC, and the minimum specified as follows:

B. Conduit Uses and Applications:

1. Galvanized Rigid Steel Conduit (GRC) :
a. For exposed indoor locations only where specifically indicated on the Drawings as non-PVC coated rigid.
b. Minimum Size:
1) As indicated in the Cable and Conduit Schedule.
2) Minimum ¾ inch where not indicated on the Drawings.
3) Minimum 1 inch when encased in Concrete

2. Flexible Conduit:
a. Use flexible conduit for final connections between rigid conduit and motors, vibrating equipment, instruments, control equipment or where required for special servicing.
1) Use type SLT with rigid metallic conduit.
2) Use type NFC with PVC conduit.
b. Minimum size ¾ inch.
1) One half inch when required for connections to instruments. c. Maximum length: 36 inches
d. Use explosion proof pvc coated flexible conduit to connect to equipment in NEMA 7 classified areas

3. PVC Coated Rigid Metallic Conduit:
a. All exposed outdoor locations, all process areas and buildings, all pump stations, all chemical areas, all UV areas, all indoor locations except where called otherwise on the drawings, and areas designated as NEMA 4X, and where indicated on the Drawings.
b. Minimum Size:
1) As indicated in the Cable and Conduit Schedule.
2) Minimum ¾ inch where not indicated on the Drawings.
3) Minimum 1 inch when encased in Concrete.

Page 851 of 1480 ends

May, 2026 16133-7 Septage Hauling and Receiving Station Final

4. PVC Schedule 40:
a. Underground and Embedded locations.
b. Minimum size:
1) Two inch in duct banks unless otherwise indicated.
2) One inch for in-slab conduits unless otherwise indicated. 3) Transition to rigid metal per Section 3.01.Q.

END OF SECTION

Page 852 of 1480 ends
Page 853 of 1480 ends

May, 2026 16133B-1 Septage Hauling and Receiving Station Final
SECTION 16133B

DUCT BANKS
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes Requirements for:

1. Electrical underground duct banks.

2. Duct spacing and terminations.

3. Excavation and Patching.

4. Coordination with other underground utilities.

B. Related Sections:

1. Refer to Section 16010.

1.02 REFERENCES
A. Refer to Section 16010.

1.03 DEFINITIONS
A. Refer to Section 16010.

1.04 SYSTEM DESCRIPTION
A. Provide trenching, backfill, compaction necessary for the complete installation of the duct banks.

B. Provide sand duct banks for all conduits installed below grade, on the site, below structures, or in contact with the earth, unless otherwise indicated on the Drawings.

1.05 SUBMITTALS
A. Furnish submittals in accordance with Sections 01330 and 16010.

B. Product Data:

1. PVC conduit spacers.

2. Detectable underground marking tape.

C. Provide Applicable Submittal Documents as Required in:

1. Section 02318.

1.06 QUALITY ASSURANCE
A. Refer to Section 16010.

1.07 DELIVERY, STORAGE, AND HANDLING
A. Refer to Section 16010.

1.08 PROJECT OR SITE CONDITIONS

Page 854 of 1480 ends

May, 2026 16133B-2 Septage Hauling and Receiving Station Final
A. Refer to Section 16010.

1.09 WARRANTY
A. Refer to Section 16010.

1.10 SYSTEM STARTUP
A. Refer to Sections 01756 and 16010.

PART 2 PRODUCTS

2.01 MANUFACTURERS
A. Conduit Spacers:

1. One of the Following or Equal:
a. Carlon Snap-Loc.
b. Cantex.
c. Osburn Associates, Inc.

B. Detectable Underground Marking Tape:

1. One of the following or equal:
a. Blackburn manufacturing Company.
b. Brady – Identoline.
c. Thomas and Betts – Protect-A-Line.
d. Panduit – Underground Hazard Tape.

C. Pull Line:

1. One of the Following or Equal:
a. Arnco.
b. Greenlee.
c. Osburn Associates, Inc.

2.02 MATERIALS
A. For Conduit Requirements, Reference Section 16133.

1. Use duct suitable for use with 90 degree Celsius rated conductors.

2.03 MANUFACTURERED UNITS
A. Conduit Spacers:

1. Provide conduit spacers recommended by the conduit manufacturer or listed above.

2. Saddle type.

3. Non-metallic, non-corrosive, non-conductive.

4. Interlocking Type:
a. Vertical interlocking.
b. Horizontal interlocking.

5. Suitable for concrete encasement.

6. Molded-in rebar holder.

7. Accommodates 2 inch through 6 inch conduit sizes.

8. Relieves the conduit from both horizontal and vertical stresses.

Page 855 of 1480 ends

May, 2026 16133B-3 Septage Hauling and Receiving Station Final
B. Pull Line:

1. Minimum ¼ inch wide, flat design.

2. Polyester.

3. Minimum pulling strength 1200 pounds.

C. Detectable Marking Tape:

1. Provide a detectable tape, locatable by a cable or metal detector from above the undisturbed grade.

2. Aluminum core laminated between polyester.

3. Six inch wide Red tape imprinted with black lettering “CAUTION – BURIED ELECTRIC UTILITIES.”
PART 3 EXECUTION

3.01 INSTALLATION
D. Refer to Section 16010.

E. Duct Banks:

1. Install duct banks encased in sand at least 36 inches below finish grade, unless otherwise indicated on the Drawings.

2. Damage Minimization:
a. Conduit should not be left exposed in an open trench longer than is necessary.
b. Protect all underground duct banks against damage during pouring of concrete or backfilling.

3. All plastic conduit fittings to be joined should be exposed to the same temperature conditions for a reasonable length of time before assembly.

4. Install Watertight Underground Ducts:
a. Slope duct banks away from buildings to pull-boxes or manholes. b. Slope duct banks uniformly from pull-boxes or both ways from high points between pull-boxes.
c. Slope a minimum of ½ inch per 10 feet.

5. Where new duct banks join to existing pull boxes or manholes make the proper fittings and fabricate the concrete envelopes to ensure smooth durable transitions, as indicated on the Drawings.

6. Install Pull Line in Spare Conduits:
a. Provide adequate pull line at both ends of conduits to facilitate conductor pulling.
b. Cap above ground spare conduit risers at each end with screw-on conduit caps.

F. Trenching:

1. Refer to Section 02318 for complete trenching requirements.

2. Trench must be uniformly graded with the bottom, rock free and covered with select material.

3. Whenever possible, use the walls of the trench as forms for concrete encasement:
a. Forms are required where the soil is not self-supporting.

4. Avoid damaging existing ducts, conduits, cables, and other utilities.

G. Duct Spacing:

1. Separate conduits with manufactured plastic spacers using a minimum space

Page 856 of 1480 ends

May, 2026 16133B-4 Septage Hauling and Receiving Station Final
between the outside surfaces of adjacent conduits of 1.5 inches:
a. Separate medium voltage ducts a minimum of 7.5 inches on center.

2. Install spacers to maintain uniform spacing of duct assembly a minimum of 4 inches above the bottom of the trench during concrete pour. Install spacers on 8 foot maximum intervals:
a. Due to some distortion of conduit from heat, and other means, it may be necessary to install extra spacers with the duct bank:

1. Install the intermediate set of spacers within normal required spacing to maintain the proper horizontal clearance:
a)Clearance is required to allow the proper amount of concrete to infiltrate vertically among the duct to ensure proper protection.

3. Spacers should Not be Located at the Center of a Bend:
a. Locate spacer in the tangent, free of the coupling on fabricated bends. b. Locate spacers midway between the tangent and the center bend on trench formed sweeps.

H. Terminating:

1. Use bell ends in duct at entrances into cable manholes.

2. Make conduit entrances into cable manhole tangential to walls of cable manholes.

3. Form trapezoidal transitions between duct bank and cable manholes as needed in order to ensure adequate cable bending radius for the duct bank-to-manholes transition.

I. Marking Tape:

1. Install a detectable marking tape 12 inches above the duct bank the entire length of the duct bank.

J. For Conduit Installations Beneath Building Slabs:

1. Install steel reinforced concrete duct banks under all building slabs as indicated on the Drawings:
a. Controlled Low Strength Material (CSLM) Backfill only.

K. Restore all surfaces to their original condition per Section 02952, unless otherwise specified.

3.02 CLEANING
A. Clean conduits of dirt and debris by use of an appropriately sized steel mandrel no less than ½-inch smaller than the inside diameter of the conduit.

3.03 PROTECTION
A. Refer to Section 16010
B. Provide shoring and pumping to protect the excavation and safety of workers.

C. Protect excavations with barricades as required by applicable safety regulations.

END OF SECTION

Page 857 of 1480 ends

May, 2026 16134-1 Septage Hauling and Receiving Station Final
SECTION 16134
BOXES
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes:

1. Outlet boxes, device boxes, metallic pull boxes, junction boxes, termination boxes.

2. Raceway System boxes.

B. Related Sections:

1. Refer to Section 16010.

1.02 REFERENCES
A. American National Standards Institute/National Electrical Manufacturers Association (ANSI/NEMA):

1. OS1 - Sheet-Steel Outlet Boxes, Device Boxes, Covers and Box Supports.

2. OS2 - Nonmetallic Outlet Boxes, Device Boxes, Covers and Box Supports.

B. National Electrical Code (NEC).

1. Article 314 - Outlet, Device, Pull and Junction Boxes, Conduit Bodies and Fittings.

C. National Electrical Manufacturers Association (NEMA):

1. NEMA FB1 - Fittings, Cast Metal Boxes, and Conduit Bodies for Conduit and Cable Assemblies.

2. NEMA 250 - Enclosures for Electrical Equipment (1000 Volts Maximum).

D. Underwriters Laboratory:

1. UL Standard 498 and 514.

1.03 SUBMITTALS
A. Refer to Section 01330 and 16050.

B. Shop Drawings: Include exact locations and sizes of pull boxes for ENGINEER's acceptance prior to fabrication and installation.

1.04 QUALITY ASSURANCE
A. Refer to Section 16010.

PART 2 PRODUCTS

2.01 MANUFACTURERS
A. Device Boxes, Metallic Pull Boxes and Junction Boxes: One of the following or equal:

1. Crouse-Hinds.

2. Appleton.

3. Hofmann

4. Saginaw

Page 858 of 1480 ends

May, 2026 16134-2 Septage Hauling and Receiving Station Final
B. All metal pull boxes shall be stainless steel with hinges and gasket.

2.02 DEVICE BOXES AND JUNCTION BOXES
A. NEMA 4X 316 Stainless Steel, hinged door with stainless steel door fasteners. compatible with the location and conduit system being used, unless otherwise specified or indicated on the Drawings.

2.03 CONCRETE PULL BOXES ADN MANHOLES
A. Precast concrete pull boxes in locations indicated on the Drawings and as required by NEC.

B. Designed for H20 traffic conditions, with pull box and cover designed for loads consistent with ASTM C1802, Load Level 5 Minimum.

C. Identification: Furnish covers with “Electrical” or “Instrumentation” and box number engraved on top side.

D. Provide wire labels on all wire in manholes and pull boxes.

E. Provide sump location in bottom of box to allow a pump to be installed to pump water out of the box.

F. Provide adjustable cover or grade ring to allow coordination with final Grade.

G. Where installed in paving, the top of the manhole shall be 2” above finish grade. Slope pavement away at 3% grade. See Drawings for grading details.

2.04 FASTENERS
A. Electroplated or stainless steel in boxes with wiring devices.

B. Screws, Nuts, Bolts, and Other Threaded Fasteners: Stainless Steel.

PART 3 EXECUTION

3.01 INSTALLATION
A. General: Comply with the National Electrical Code.

B. Terminal blocks installed in junction/terminal boxes as specified in Section 16050.

C. Provide weatherproof conduit hubs for all conduit connections to pull boxes.

D. Size pull boxes to meet National Electrical Code requirements and to provide sufficient room for the future conduits and cables indicated on the Drawings.

E. Furnish and install pull boxes as indicated on the Drawings and as specified. Install additional pull boxes as required to meet cable manufacturer's pulling tension requirements.

Page 859 of 1480 ends

May, 2026 16134-3 Septage Hauling and Receiving Station Final
F. Install pull boxes such that access to them is not restricted by obstructions such as pipes, valves, ladders.

G. Secure pull box covers with type 316 stainless steel screws or bolts with coated threads.

H. Install concrete pull boxes on 12-inches compacted clean aggregate base course as specified in Section 02722.

I. Install Cable support channels on sides of pull boxes and coil and hang cable in a neat manner inside all pull boxes. Wire laying on the floor of the box or cables stretched tight through a box will not be accepted.

J. Concrete pull boxes shall have pull box number and service engraved onto the lid.

Provide all other pull boxes with lamecoid nameplate with pull box number and service on each pull box with engraved text.

3.02 ADJUSTMENT
A. Adjust equipment as required.

END OF SECTION

Page 860 of 1480 ends
Page 861 of 1480 ends

May, 2026 16135-1 Septage Hauling and Receiving Station Final
SECTION 16135

CABINETS AND ENCLOSURES
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Cabinets and enclosures to house electrical controls, instruments, terminal blocks, and similar equipment.

B. Related Section:

1. Refer to Section 16050.

1.02 REFERENCES
A. National Electrical Code (NEC).

B. National Electrical Manufacturers' Association (NEMA).

1.03 SYSTEM DESCRIPTION
A. Design Requirements:

1. Unless otherwise specified herein or indicated on the Drawings, enclosures to house electrical controls, instruments, terminal blocks, and similar equipment shall be NEMA 12 for indoor and NEMA 4X for outdoor installations and shall be compatible with the conduit system being used.

2. Specific control panel enclosures shall be as specified in DIVISION 13 and 16 of these Specifications or as indicated on the Drawings.

1.04 SUBMITTALS
A. Furnish Submittal in accordance with Section 01330 and 16010.

1.05 WARRANTY
A. Provide 12 month warranty from data of acceptance by the Owner.

PART 2 PRODUCTS

2.01 MANUFACTURERS
A. Indoors: NEMA 12 Steel Enclosures: One of the following or equal:

1. Hoffman Engineering Company.

2. Ritta.

B. Outdoors: NEMA 4X Stainless Steel Enclosures: One of the following or equal:

1. Hoffman Engineering Company.

2. Carlon.

2.02 CONSTRUCTION
A. All Enclosures:

Page 862 of 1480 ends

May, 2026 16135-2 Septage Hauling and Receiving Station Final

1. Make enclosures from 14 gauge steel with continuous welded seams. Doors shall have full length piano hinges with the door removable by pulling the hinge pin.

2. Provide a rolled lip around 3 sides of the door and around all sides of the enclosure opening.

3. Provide hasp and staple for padlocking.

4. Provide a print pocket for each enclosure.

5. Panels with PLCs shall have an outer and inner door. Outer door shall be plane.

Inner door shall have all devices mounted on it.

6. All outdoor panels with a PLC or other temperature sensitive devices shall have an air conditioner included with the panel for proper temperature control.

7. Provide Lamicoid name plate with stainless steel screws. Glued on name plates are not accepted.

B. NEMA 12 Steel Enclosures

1. Attach gasket with oil-resistant adhesive and hold it in place with steel retaining strips.

C. NEMA 4X, 316 Stainless Steel Enclosures:

1. Provide minimum 14 gauge 316 Stainless Steel Enclosure with 316 Stainless Steel Hardware.

2. Provide enclosures that consist of a base and cover with cover hinges to forma a weather tight seal between the cabinet and the doors.

3. Provide the enclosures with gasket system of neoprene material cemented into a molded labyrinth on the cover.

D. NEMA 4X, FRP Enclosures:

1. Provide enclosures that consist of base and cover which shall be heavy-duty hot compression molded from fiberglass reinforced polyester compound containing not less than 25 percent fiberglass by weight. Transparent covers, where specified or indicated on the Drawings, shall be polycarbonate. The enclosures shall be provided with cover hinges manufactured from nonmetallic materials. The cover latch system shall be nonmetallic.

2. Provide the enclosures with gasket system of neoprene material cemented into a molded labyrinth on the cover.

3. 316 Stainless Steel Hardware

4. Provide the enclosures with gasket system of neoprene material cemented into a molded labyrinth on the cover.

2.03 FINISHES
A. Steel Enclosures:

1. Do not paint NEMA 4X enclosures. Door fronts shall be ground smooth. Print pockets and interior panels shall be steel with a white enamel finish.

2. Provide NEMA 12 and NEMA 4 enclosures with white enamel interior finish. The finish shall be light grey enamel, ANSI 61 exterior, over phosphatized surfaces.

Panels shall be white enamel. Special finishes and colors shall be furnished for wet locations. Other portions of these Contract Documents shall be checked for special conditions.

PART 3 EXECUTION

3.01 INSTALLATION
A. Install Cabinets and Enclosures per manufacturer’s instructions.

Page 863 of 1480 ends

May, 2026 16135-3 Septage Hauling and Receiving Station Final

END OF SECTION

Page 864 of 1480 ends
Page 865 of 1480 ends

May, 2026 16140-1 Septage Hauling and Receiving Station Final
SECTION 16140

WIRING DEVICES
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Wiring devices including the following:

1. Snap switches and toggle switches.

2. Plugs and receptacles.

3. Control and pushbutton stations.

4. Pilot devices.

B. Related Sections:

1. Refer to Section 16010.

1.02 SUBMITTALS
A. Refer to Sections 01330 and 16050.

1.03 QUALITY ASSURANCE
A. Provide industrial grade products for wiring devices. Commercial grade products are not acceptable, unless otherwise specified or indicated on the Drawings.

1.04 WARRANTY
A. Submit manufacturer's standard warranty.

PART 2 PRODUCTS

2.01 SNAP OR TOGGLE SWITCHES
A. Manufacturers: One of the following or equal:

1. Hubbell.

2. General Electric.

3. Leviton.

4. Bryant.

B. Number of Poles: As indicated on the Drawings.

C. Rating: 20 amperes, 125 volt.

D. Special Switches and Covers: As specified or indicated on the Drawings.

2.02 120 VOLT RECEPTACLES
A. Manufacturers: One of the following or equal:

1. Hubbell.

2. General Electric.

3. Leviton.

Page 866 of 1480 ends

May, 2026 16140-2 Septage Hauling and Receiving Station Final

4. Bryant.

B. Duplex Receptacles: 2-pole, 3-wire, grounded, 125 volts, industrial, rated at 20 amperes.

1. Special Receptacles and Covers: As specified in Section 16134 or as indicated on the Drawings.

2. Outdoor receptacles shall have cover and be weather rated for “In Use” service.

C. Ground Fault Interrupter Receptacles (GFI): Rated at 20 amperes at 125 volts alternating current.

2.03 LOCAL PUSHBUTTON MOTOR CONTROL STATIONS
A. Manufacturers: One of the following or equal:

1. Furnas Electric Company.

2. Square D Company.

3. Allen Bradley.

4. Siemens.

5. Cutler Hammer.

6. General Electric.

B. Types: Heavy duty, oil-tight/water-tight.

C. Components: Selector Switches, pilot light, and pushbuttons.

D. Enclosures: As follows, unless otherwise indicated on the Drawings or specified:

1. For Nonhazardous Indoor Locations: NEMA 12.

2. For Hazardous Indoor Locations: NEMA 7.

3. For Outdoor Locations: NEMA 4X.

4. For Hazardous Outdoor Locations: NEMA 7.

E. Field Located Maintained Pushbuttons: Red mushroom head, push-to-stop, pull-toreset, with maintained contacts.

2.04 PILOT DEVICES
A. Manufacturers: One of the following or equal:

1. Furnas Electric Company.

2. Square D Company.

3. Allen Bradley.

4. Siemens.

5. Cutler Hammer.

6. General Electric.

B. Type: Heavy-duty, suitable for mounting in control stations, on switchgear, switchboards, variable frequency drives, motor control centers, control panels, and other electrical equipment.

C. Components: Oil-tight/water-tight pushbuttons, selector switches, pilot light, and incidental items.

D. Casting: Durable 1 piece with chrome plated octagonal mounting nuts.

E. Pushbuttons: Heavy duty plastic.

Page 867 of 1480 ends

May, 2026 16140-3 Septage Hauling and Receiving Station Final
F. Pilot Light Lenses: Shatter resistant plastic, push-to-test.

2.05 CORD CONNECTOR GRIPS
A. Non-hazardous Areas:

1. Manufacturers: One of the following or equal:

Killark, Series Z.

2. Aluminum cord connector.

3. Stainless steel mesh grip.

B. Hazardous Areas:

1. Manufacturers: One of the following or equal:
a. Killark, Series ZE.

PART 3 EXECUTION

3.01 INSTALLATION
A. Install wiring devices in accordance with manufacturer's instructions.

B. Mount wiring devices as indicated on the Drawings.

3.02 LOCAL PUSHBUTTON MOTOR CONTROL STATION INSTALLATION A. Install Start-Lockout-Stop pushbutton control stations adjacent to every motor unless otherwise indicated on the Drawings.

3.03 ADJUSTMENT
A. Adjust wiring devices as specified in Section 01756.

3.04 PROTECTION
A. Protect products until acceptance by OWNER.

END OF SECTION

Page 868 of 1480 ends
Page 869 of 1480 ends

May, 2026 16212-1 Septage Hauling and Receiving Station Final
SECTION 16212

METERING AND RELAYING
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Instruments, relays, potential transformers, current transformers and other devices installed in motor control centers, variable frequency drives, switchboards, switchgear, and similar engineered equipment.

B. Related Sections:

1. Refer to Section 16010.

1.02 SUBMITTALS
A. Shop Drawings: Refer to Sections 01330 and 16050.

1.03 WARRANTY
A. Provide per Section 16050.

PART 2 PRODUCTS

2.01 MANUFACTURERS
A. Instruments: Manufacturers: One of the following or equal:

1. General Electric Company.

2. Cutler-Hammer.

3. Square D Company.

4. Allen Bradley Company.

B. Relays:

1. Induction Type: Manufacturers: One of the following or equal:
a. General Electric Company.
b. Cutler-Hammer.

2. Solid State Type: Manufacturers:
a. Schweitzer, not equal.

C. Potential transformers: Manufacturers: One of the following or equal:

1. General Electric Company.

2. Cutler-Hammer.

3. Square D Company.

D. Current Transformers: Manufacturers: One of the following or equal:

1. General Electric Company.

2. Cutler-Hammer.

3. Square D Company.

Page 870 of 1480 ends

May, 2026 16212-2 Septage Hauling and Receiving Station Final

2.02 COMPONENTS
A. Instruments, Relays, and Other Devices for Panels: Utility grade, flush or semi-flush mounted with cases of similar design.

B. Instruments: Antiglare glass fronts, antiparallax scales, and white faces with black numerals and markings.

1. Select with the full-load reading at approximately 75 percent of full scales, unless otherwise specified.

2. Accuracy of instruments: One percent of full scale values.

C. Potential Transformers: Indoor, dry type, single phase, 60 hertz, with a 0-120 volt secondary, and rated as required for the equipment furnished.

1. Furnish with current limiting fused disconnects.

2. Equip with resistors s required to limit the fault current to a value which the fuse is able to interrupt without damage.

3. Transformer Accuracy: Suitable for meters and relays.

D. Medium Voltage Potential Transformers: As specified in the respective Section of the medium voltage equipment specifications.

E. Current Transformers: Indoor, dry type insulated for the voltage for which it is used and rated as required for the equipment furnished with a 0-5 ampere secondary.

1. Rated for sufficient thermal and mechanical capacity to withstand the maximum momentary short circuit current rating of the associated circuit breaker.

2. Transformer Accuracy: Suitable for meters and relays.

PART 3 EXECUTION

3.01 FIELD QUALITY CONTROL
A. Calibrate relays and verify settings and operational characteristics using relay testing equipment manufactured by Multi-amp Corporation. Test shall be performed by qualified personnel experienced in operation of the equipment and adjustment of relays, subject to witnessing by the ENGINEER. Furnish three (3) copies of test reports to the OWNER. In the event the system should require resetting or recalibration of relays, perform such settings and testing without additional cost to OWNER.

3.02 ADJUSTMENT
A. Set adjustable protective relays to operate at time, current, voltage, and other appropriate values as determined by the coordination study as accepted by ENGINEER.

B. Install a calibration sticker with the date of calibration, due date of next calibration, settings, name of firm, and qualified test personnel.

C. Provide data sheet for each device calibrated.

D. Perform calibration with secondary standards with the appropriate certificates for calibration.

3.03 DEMONSTRATION

Page 871 of 1480 ends

May, 2026 16212-3 Septage Hauling and Receiving Station Final
A. Demonstrate operation of equipment.

3.04 PROTECTION
A. Protect products until acceptance by OWNER.

END OF SECTION

Page 872 of 1480 ends
Page 873 of 1480 ends

May, 2026 16412-1 Septage Hauling and Receiving Station Final
SECTION 16412

LOW VOLTAGE CIRCUIT BREAKERS
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Low voltage circuit breakers as indicated on the Drawings and as specified.

1.02 REFERENCES
A. National Electrical Manufacturers Association (NEMA): Standards Publication No. AB1.

B. National Electrical Code (NEC): Article 430-52.

PART 2 PRODUCTS

2.01 MANUFACTURERS
A. Circuit Breakers: Manufacturers: One of the following or equal:

1. Square D

2. Cuter Hammer

3. Allen Bradley

2.02 CIRCUIT BREAKERS - LOW VOLTAGE
A. Circuit Breaker Frame and Trip Ratings: As indicated on the Drawings and coordinated with the ratings of the equipment actually furnished. Modify ratings where necessary to suit this equipment.

B. Panelboard Circuit Breakers: Bolt-in type. Snap-in circuit breakers are not acceptable.

2.03 MOLDED-CASE CIRCUIT BREAKERS
A. Molded-case Circuit Breakers: Ambient compensating which provides inverse time delay overload and instantaneous short circuit protection by means of a thermal magnetic element. Accomplish compensation by a secondary bimetal that will allow the breaker to carry rated current between 25 degrees Centigrade and 50 degrees Centigrade with tripping characteristics which are approximately the same throughout this temperature range.

B. Circuit Breaker Ratings and Modifications: As indicated on the Drawings.

C. On Breakers with Interchangeable, Thermal, Adjustable Magnetic Trip: The accessibility and position of the adjustment knob shall not be changed from those on the standard breaker.

Page 874 of 1480 ends

May, 2026 16412-2 Septage Hauling and Receiving Station Final
D. Breakers: Operated by a handle and provided with a quick-make, quick-break switching mechanism that is mechanically trip free from the handle so that the contacts cannot be held closed against short circuits and abnormal currents.

1. Tripping Due to Overload, Short Circuit, or Ground Fault: Clearly indicate tripping by the handle automatically assuming a position between the manual ON and OFF positions.

2. Latch Surfaces: Ground and polished.

3. Poles: Constructed so they all open, close and trip simultaneously.

4. Conform to the applicable requirements of NEMA Standard No. AB1.

E. Breakers: Completely enclosed in a molded case.

1. Non-interchangeable Trip Breakers: Sealed covers.

2. Interchangeable trip breakers: Sealed trip unit to prevent tampering.

3. Ampere Ratings: Clearly visible.

4. Contacts: Non-welding silver alloy.

5. Arc Extinction: Accomplished by means of arc chutes.

6. Ground Fault Protection: Provide on main circuit breaker on switchboards and motor control centers.

F. Minimum Interrupting Ratings: Not less than 65,000 RMS amperes.

G. Circuit breakers for lighting panelboards shall be rated to 22,000 RMS amperes.

2.04 MOTOR CIRCUIT PROTECTORS
A. Motor Circuits: Protected by motor circuit protectors, as permitted by Item 1 below:

B. Motor Circuit Protectors: Operated by a handle and provided with a quick-make, quick break switching mechanism that is mechanically trip free from the handle so that the contacts cannot be held closed against short circuits and abnormal currents.

1. Tripping: Clearly indicated by the handle automatically assuming a position between the manual ON and OFF positions.

2. Latch Surfaces: Ground and polished.

3. Poles: Constructed so they all open, close, and trip simultaneously.

C. Motor Circuit Protectors: Completely enclosed in a molded case.

1. Trip Unit: Sealed to prevent tampering.

2. Ampere Ratings: Clearly visible.

3. Contacts: Non-welding silver alloy.

4. Arc Extinction: Accomplished by means of arc chutes.

D. Provide each pole of motor circuit protectors with instantaneous short circuit protection by means of a single adjustable magnetic only element. The single adjustment screw is to adjust all poles simultaneously.

E. Furnish motor circuit protectors with provision for locking the maximum achievable trip setting to values less than maximum obtainable trip setting. Each adjustment typically to have 8 main setting points and mid-setting points following a linear scale so that each point has a significant value within calibration tolerances.

F. Motor Circuit Protectors: Suitable for use with current limiters, having 100,000 ampere interrupting capacity and a built-in trip indicator, that are fully coordinated with the motor circuit protectors so that the motor circuit protectors will open all 3 phases if the limiter operates.

Page 875 of 1480 ends

May, 2026 16412-3 Septage Hauling and Receiving Station Final

1. Current limiters shall be so constructed that they can only be replaced by an identical or similar limiter having the same interrupting capacity.

G. Minimum Interrupting Ratings: Not less than 65,000 RMS amperes.

H. Motor Circuit Protectors Continuous Current Rating: As specified herein or as indicated on the Drawings.

1. Setting: The motor circuit protectors setting shall be in accordance with the Manufacturer’s protective device coordination study as accepted by the ENGINEER and in accordance with the motor circuit protectors manufacturer’s recommendation based on motor nameplate current or actual motor current, whichever is larger.

I. Utilize an instantaneous trip circuit breaker or motor circuit protector only as part of a listed combination motor controller which provides coordinated motor branch-circuit overload, and short-circuit and ground-fault protection in accordance with NEC Article 430-52.

PART 3 EXECUTION
Not Used.

END OF SECTION

Page 876 of 1480 ends
Page 877 of 1480 ends

May, 2026 16448-1 Septage Hauling and Receiving Station Final
SECTION 16448

PANELBOARDS
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Dead-front panelboards, including lighting distribution and control panelboards.

B. Related Section:

1. Refer to Section 16010.

1.02 REFERENCES
A. National Electrical Manufacturers Association (NEMA):

1. NEMA 250 - Enclosures for Electrical Equipment (1,000 Volts Maximum).

B. Underwriter's Laboratories, Inc. (UL):

1. UL 67 - Panelboards.

1.03 PERFORMANCE REQUIREMENTS
A. Minimum Interrupting Capacity of Device: Equal to available short circuit current at line terminals as determined by CONTRACTOR's short circuit fault analysis as accepted by ENGINEER, but not less than 65,000 amperes.

B. Provide main bus rating of panelboards, number of poles, and provisions for number of circuits as indicated on the Drawings.

1.04 SUBMITTALS
A. Refer to Sections 01330 and 16010.

B. Product Data: Include manufacturer's specifications and description.

C. Shop Drawings: Submit in accordance with Section 01330. Include panelboard layout.

1.05 WARRANTY
A. Provide per Section 16050.

PART 2 PRODUCTS

2.01 MANUFACTURERS
A. Panelboards: One of the following or equal:

1. Eaton Pow-R-Line 2a,

2. Square D Company.

3. General Electric Company.

Page 878 of 1480 ends

May, 2026 16448-2 Septage Hauling and Receiving Station Final

2.02 INTERIOR
A. Bus: Size main bus bars in accordance with UL standards to limit temperature rise on any current carrying part to a maximum of 50 degrees Centigrade above specified ambient maximum.

1. Tin plated copper bussing.

B. Install protective devices such that they can be replaced without disturbing adjacent units. Wire connectors shall be suitable for wire sizes [indicated on the Drawings].

C. Number branch circuits and spares as indicated on the Drawings and furnish complete typed circuit schedule in directory cardholder affixed to panel under a transparent cover.

D. Phase busing shall be full size and height without reduction. Include full size neutral bars with suitable lugs for the maximum number of circuits which can be connected to the panel.

E. Spares and spaces for future protective devices in panels indicated on the Drawings shall be bussed for panel rating or the main circuit breaker rating.

F. Provide panels with tin plated copper ground bus separate from neutral bars. Ground bus to have suitable lug for each circuit breaker installed including future circuits.

2.03 ENCLOSURES
A. Size panelboards sufficiently to provide minimum 4 inches of gutter space on all sides.

Doors shall be such that:

1. Live parts shall not be exposed when circuit breakers or switches are put in service.

2. Hinges and latches shall not require tools to operate.

B. Furnish lock and minimum 2 keys each panelboard. Key all panelboard locks alike.

C. Enclosure type as indicated on the Drawings. Where not indicated on the Drawings:

1. Indoor Enclosures: NEMA 12.

2. Outdoor Enclosures: NEMA 4X 316 stainless steel.

D. Mounting shall be as indicated on the Drawings.

E. Finish stand alone panelboards with a primer, rust-resistant phosphate undercoat and 2 coats of oven-baked enamel with finish color ANSI 61 gray or a color to be selected by the ENGINEER.

F. Finish motor control center mounted panelboards to match the MCC finish and color, unless directed otherwise.

2.04 CIRCUIT BREAKERS
A. Circuit Breakers: As specified in Section 16412.

B. Provide a means to padlock each circuit breaker in the off position.

Page 879 of 1480 ends

May, 2026 16448-3 Septage Hauling and Receiving Station Final

2.05 IDENTIFICATION
A. Label panelboards to indicate use as service entrance equipment where indicated on the Drawings or specified.

B. Label panelboards with UL short circuit current rating.

C. Provide each panelboard which is not an integral part of a motor control center with a lamicoid nameplate on outside of door, as specified in Section 16075, Electrical Identification.

PART 3 EXECUTION

3.01 INSTALLATION
A. As indicated on the Drawings, or as required, in a workmanlike manner.

3.02 FIELD QUALITY CONTROL
A. Test main circuit breaker(s) in accordance with NETA standards.

END OF SECTION

Page 880 of 1480 ends
Page 881 of 1480 ends

May, 2026 16500-1 Septage Hauling and Receiving Station Final
SECTION 16500

LIGHTING
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Lighting fixtures, lamps, poles, and accessories.

B. Related Sections:

1. Refer to Section 16010.

1.02 REFERENCES
A. Underwriter's Laboratories (UL):

1. UL 1029 - High-Intensity Discharge Lamp Ballasts.

1.03 SUBMITTALS
A. Refer to Sections 01330 and 16010.

B. Product Data:

1. Applicable coefficients of utilization tables, isolux chart of illumination on a horizontal plane, beam efficiency, horizontal and vertical beam spread, beam lumens.

2. Submit pole seismic and wind-load design calculations before fixtures and poles are manufactured.

C. Samples: Include finish Sample for lighting fixtures and poles.

D. Manufacturer's installation instructions.

1.04 WARRANTY
A. Per Section 16050.

PART 2 PRODUCTS

2.01 MANUFACTURERS
A. Lighting Fixtures: As noted on Lighting Fixture Schedule and the Drawings.

B. Plugs and Receptacles: As specified in Section 16140.

2.02 FIXTURES
A. Lighting Fixtures: As described in Lighting Fixture Schedule, as specified, and as indicated on the Drawings.

1. Fixtures shall include lamps, poles, mounting hardware, and appurtenances to provide complete operating units.

Page 882 of 1480 ends

May, 2026 16500-2 Septage Hauling and Receiving Station Final
B. All lighting Fixtures shall be LED type.

2.03 POLES
A. Design for wind design criteria as specified in Section 01614.

B. Design for seismic design criteria as specified in Section 01612 for the project site without structural damage.

C. Anchor Bolts, Washers, and Nuts: Stainless steel.

2.04 LIGHTING CONTACTORS
A. Silver-cadmium-oxide, double-break contacts.

B. 20 ampere rating for lighting circuits.

C. Mechanically held.

D. Number of poles as indicated on the Drawings with a minimum of 2 poles and a maximum of 12 poles for each contactor provided.

E. Manufacturers: One of the following or equal:

1. Square D Company, Type LX.

2. ASCO, Model 917.

PART 3 EXECUTION

3.01 INSTALLATION
A. Surface and Flush Mounted Fixtures: Solidly connected to a junction box.

B. Suspended Fixtures: Hung utilizing pendant mounting or stainless steel chains and hooks. Electrically connect each fixture, or row of fixtures, by a length of Type SO flexible cord, 3 conductor Number 14 American Wire Gauge minimum, with a twist-lock plug to a twist-lock receptacle mounted in an individual junction box.

C. Pole Mounted Fixtures: Mount on steel, aluminum, or fiberglass poles as described in Lighting Fixture Schedule and as indicated on the Drawings.

1. Ground or bond metal poles to the plant grounding system.

2. Poles shall have adequate handholes in accordance with NEC requirements.

3. Poles shall have weatherproof switches, receptacles, photo cells where indicated on the Drawings.

3.02 SPARES
A. Fixtures and Mounting Accessories: No spares required.

Page 883 of 1480 ends

May, 2026 16500-3 Septage Hauling and Receiving Station Final

3.03 LIGHTING FIXTURE SCHEDULE
A. Refer to Drawings for Fixture Schedule.

3.04 PROTECTION
A. Protect products until accepted by OWNER.

END OF SECTION

Page 884 of 1480 ends
Page 885 of 1480 ends

May, 2026 16950-1 Septage Hauling and Receiving Station Final
SECTION 16950

ELECTRICAL TESTING
PART 1 GENERAL

1.01 SUMMARY
A. Section Includes: Acceptance testing of electrical system, wiring, equipment, and grounding.

B. Related Sections:

1. Refer to Section 16010.

1.02 REFERENCES
A. National Electrical Testing Association (NETA):

1. ATS-2013 - Acceptance Testing Specifications for Electric Power Distribution Equipment and Systems.

1.03 SUBMITTALS
A. Refer to Sections 01330 and 16010.

B. Pre-test Submittals:

1. Testing service qualifications.

2. Test personnel qualifications (resumes).

3. Equipment testing schedule.

4. Sample equipment test data forms for all equipment and systems to be tested.

5. Functional testing data sheets for all systems tested. Functional testing plan shall include individual testing line items for each alarm and indication feature for each mode of operation (i.e. Local, Off and Remote). Each functional test line item shall be developed in a “cause and effect” format which shall include an initial condition/set-up description field, action field (i.e. activate high-high level alarm), description of expected result field and “Expected Result Observed” field which shall include spaces for both the Contractor’s and Engineer’s initials.

C. Post-test Submittals: Summary Test Report consists of the following:

1. Summary of testing for the project.

2. Description of the equipment tested.

3. Description of the test and test procedures.

4. Test results.

5. Conclusions and recommendations.

6. Completed test forms, including witness's signatures.

7. List of test equipment and calibration documents.

8. Date and time.

9. Include the Following Data Tabulated for Each Piece of Equipment:
a. Circuit number.
b. Equipment or motor name and tag number (where applicable). c. Nameplate full-load-ampere rating.
d. Motor service factor.
e. Motor ambient temperature rating.
f. Overload relay rating.

Page 886 of 1480 ends

May, 2026 16950-2 Septage Hauling and Receiving Station Final
g. Measured full load current.
h. Measured discharge pressure (where applicable).
i. Measured flow rate (where applicable).

D. Submit Equipment Testing Schedule no later than 14 days prior to scheduled date of testing.

E. Project Record Documents: Submit as specified in Section 01770. Note or indicate wiring deviations from Contract Documents on Project Record Documents.

1.04 QUALITY ASSURANCE
A. Testing Firm Qualifications:

1. Obtain the services of an independent testing service firm that meets the Federal OSHA criteria for accreditation of testing laboratories, Title 29, Part 1910.7 and has a work history and qualifications acceptable to Engineer.

2. Prequalified Testing Services and Manufacturing Firms:
a. General Electric Company.
b. Cutler-Hammer.
c. Square D Company Technical Service Divisions.
d. Electro-Test Inc.

3. Qualifications of other testing service firms may be submitted.

4. Testing service or testing personnel may be accepted or rejected based upon, but not limited to, the testing equipment intended to be used, the qualifications of the firm, and personnel.

B. Test Equipment Traceability:

1. Testing firm shall have a calibration program which maintains applicable test instrumentation and equipment within rated accuracy.

2. Equipment and instruments used to evaluate electrical performance shall be calibrated to a secondary standard traceable to the National Institute of Standards and Technology.

3. Test equipment operating instructions and procedures shall be with the test equipment.

PART 2 PRODUCTS
Not Used.

PART 3 EXECUTION

3.01 EXAMINATION
A. Verify that electrical work is free from improper grounds, short circuits, and overloads.

B. Verify correctness of wiring first by visual comparison of the conductor connections with connection diagrams.

C. Make individual circuit continuity checks by using electrical circuit testers.

D. Verify correctness of wiring by actual electrical operation of electrical and mechanical devices in both manual and automatic modes of operation.

Page 887 of 1480 ends

May, 2026 16950-3 Septage Hauling and Receiving Station Final

3.02 ACCEPTANCE TESTING
A. Perform equipment integrity testing and invite Owner and Engineer to witness testing.

All equipment integrity testing shall be successfully completed prior to energization of equipment. Equipment that does not initially pass integrity testing shall be repaired and re-tested until successful results are obtained.

B. Perform electrical acceptance testing in accordance with latest NETA Standards.

C. Perform functional tests to assure that electrical equipment specified to be tested will operate in accordance with the specified requirements. Functional testing shall be witnessed by the Engineer. Prior to performing witnessed functional tests, the Contractor shall perform a “dry run” on all functional test line items to verify that each tested system operates successfully. During witnessed functional testing, should the tested systems not operate as expected, the testing shall be halted and re-scheduled with no time extension granted to the Contractor for this additional testing work.

D. Test motorized equipment to verify conformance with the Contract Documents and for acceptance.

E. Install equipment with acceptable data. Equipment for which acceptable test data has not been submitted, or has been submitted but rejected, shall be deemed as not meeting Contract requirements.

F. Test Project electrical equipment, including 600 volt electrical distribution equipment and grounding. Complete test reports for each individual piece of equipment.

G. Test Project electrical equipment included on, but not limited to, the following list:

1. Low-Voltage 600-volt Cables.

2. Low-Voltage Circuit Breakers.

3. Protective Relays.

4. Instrument Transformers.

5. Metering and relying

6. Grounding System.

7. Ground-Fault Protection.

8. Grounding system connection to new equipment.

9. Panelboards.

10. System Function Tests.

11. Perform a thermographic Survey of all new electrical connections in Panels and MCCs.

3.03 SUMMARY TEST REPORT
A. Upon completion of testing in every area, submit summary test report for acceptance by the Engineer.

END OF SECTION

Page 888 of 1480 ends
Page 889 of 1480 ends
Page 890 of 1480 ends
Page 891 of 1480 ends
Page 892 of 1480 ends
Page 893 of 1480 ends
Page 894 of 1480 ends
Page 895 of 1480 ends
Page 896 of 1480 ends
Page 897 of 1480 ends
Page 898 of 1480 ends
Page 899 of 1480 ends
Page 900 of 1480 ends
Page 901 of 1480 ends
Page 902 of 1480 ends
Page 903 of 1480 ends
Page 904 of 1480 ends
Page 905 of 1480 ends
Page 906 of 1480 ends
Page 907 of 1480 ends
Page 908 of 1480 ends
Page 909 of 1480 ends
Page 910 of 1480 ends
Page 911 of 1480 ends
Page 912 of 1480 ends
Page 913 of 1480 ends
Page 914 of 1480 ends
Page 915 of 1480 ends

Agenda Item 6

CITY OF YUBA CITY

STAFF REPORT
Date: June 16, 2026
To: Honorable Mayor & Members of the City Council;
From: Finance/IT Department
Presentation By: Kaylayshia Byrd, Administrative Analyst II Summary
Subject: Purchasing Policies and Procedures Manual Revisions Recommendation: Adopt a Resolution approving the revised City of Yuba City Purchasing Policies and Procedures Manual and authorize the City Manager to implement and administer the updated policies and procedures
Fiscal Impact: There is no fiscal impact
Purpose:

To adopt revisions to the City of Yuba City Purchasing Policies and Procedures Manual to improve procurement efficiency, clarify purchasing authorities and administrative procedures, update procurement requirements, and ensure continued compliance with applicable laws and City purchasing practices.

Strategic Focus Area:

This staff reports supports the City Council’s strategic goal of Fiscal Responsiblity.

Background:

In January 2022, the City Council adopted comprehensive revisions to the City's Purchasing Policies and Procedures Manual to formalize purchasing practices, clarify procurement responsibilities, and update approval thresholds. Since implementation, staff have continued to evaluate procurement processes and identified opportunities to further improve efficiency, clarify administrative procedures, and align the policy with current operational practices.

The proposed amendments update procurement procedures, clarify purchasing authorities and approval processes, revise administrative provisions, and incorporate operational improvements identified through the City's ongoing use of the policy.

Analysis:

The City's Purchasing Policies and Procedures Manual establishes the framework for the procurement of goods and services, defines approval authorities, and provides guidance to City staff regarding purchasing requirements and internal controls.

Page 916 of 1480 ends

Since the last comprehensive update, staff have identified opportunities to improve administrative efficiency, clarify procurement procedures, and align the policy with current operational practices. The proposed amendments provide additional clarification regarding procurement documentation, purchasing authorities, contract administration, approval workflows, and internal processing requirements.

The revisions also clarify procedures related to the administration of executed agreements and associated purchase orders. Under the proposed amendments, purchase orders issued pursuant to an agreement that has already been approved and executed by the authorized approving authority may be processed through established departmental authorization procedures, eliminating redundant approval steps while maintaining budgetary controls, contract limits, and existing approval thresholds.

Staff believes the proposed amendments will improve procurement efficiency, reduce administrative processing time, and maintain appropriate accountability and oversight for City expenditures.

Fiscal Impact:

There is no fiscal impact.

Alternatives:

1. Adopt the Resolution approving revisions to the Purchasing Policies and Procedures Manual as presented.

2. Direct staff to modify the proposed revisions and return with a revised Purchasing Policies and Procedures Manual for future Council consideration.

3. Decline to adopt the proposed revisions and maintain the current Purchasing Policies and Procedures Manual.

Recommendation:

Adopt a Resolution approving the revised City of Yuba City Purchasing Policies and Procedures Manual and authorize the City Manager to implement and administer the updated policies and procedures.

Attachments:

1. Attachment 1: Resolution Adopting Revisions to the Purchasing Policies and Procedures Manual

2. Exhibit A: Purchasing Policies and Procedures Manual Effective March 2022; Amended June 2026
Prepared By: Submitted By:

Kaylayshia Byrd
Administrative Analyst II
Robert Bendorf
City Manager

Page 917 of 1480 ends

ATTACHMENT 1

Page 918 of 1480 ends

RESOLUTION NO.

RESOLUTION OF THE CITY COUNCIL OF THE CITY OF YUBA CITY

APPROVING REVISIONS TO THE CITY OF YUBA CITY PURCHASING

AND PROCEDURES MANUAL

BE IT RESOLVED AND ORDERED BY THE CITY COUNCIL OF THE CITY OF YUBA CITY AS FOLLOWS:

WHEREAS, Chapter 6 of Title 2 of the Yuba City Municipal Code authorizes the Purchasing Officer to establish and amend purchasing rules and regulations, subject to approval by the City Council; and
WHEREAS, the City Council adopted the current Purchasing Policies and Procedures Manual in January 2022 to provide guidance regarding the procurement of goods and services and to establish purchasing procedures and approval authorities; and WHEREAS, staff has identified opportunities to update provisions of the Purchasing Policies and Procedures Manual while maintaining appropriate internal controls and oversight; and
WHEREAS, the proposed revisions to the Purchasing Policies and Procedures Manual are administrative in nature and are intended to improve procurement processing and contract administration practices.

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Yuba City hereby:

1. Approves the revised Purchasing Policies and Procedures Manual attached hereto as Exhibit A.

2. Authorizes the City Manager or designee to administer and implement the Purchasing Policies and Procedures Manual.

3. Authorizes the City Manager or designee to make minor administrative, formatting, and non-substantive corrections as necessary, provided such changes do not alter the intent of the policies approved by this Resolution.

The foregoing Resolution was duly and regularly introduced, passed, and adopted by the City Council of the City of Yuba City at a regular meeting thereof held on the 16th day of June 2026.

AYES:

NOES:

Page 919 of 1480 ends

ABSENT:

Marc Boomgaarden, Mayor
ATTEST:

Ciara Wakefield, City Clerk

APPROVED AS TO FORM
COUNSEL FOR YUBA CITY:

Shannon Chaffin, City Attorney
Aleshire & Wynder, LLP
Attachment(s):

A. Exhibit A – Purchasing Policies and Procedures Manual Effective March 2022; Amended June 2026

Page 920 of 1480 ends

EXHIBIT A

Page 921 of 1480 ends

City of Yuba City Effective March 2022; Amended June 2026

PURCHASING

POLICIES AND

PROCEDURES
Continuity
Uniformity
Fairness
Equity
Responsibility
City of Yuba City Purchasing

Page 922 of 1480 ends

CITY OF YUBA CITY PURCHASING POLICES AND PROCEDURES

TABLE OF CONTENTS
SECTION 1: PURPOSE AND POLICY STATEMENT 1
1-1.Purpose 1
1-2.Policy Statement 1
SECTION 2: ETHICS, GIFTS, AND UNAUTHORIZED PURCHASES 1
2-1. Code of Ethics 1
2-2. Gifts and Special Considerations 2
2-3. Unauthorized Purchases 2
SECTION 3: PURCHASING OFFICER RESPONSIBLITIES 3
SECTION 4: FINANCE DEPARTMENT RESPONSIBILITIES 3
SECTION 5: PUBLIC CONTRACT CODE 4
5-1. Engineering Division Responsibilities 4
SECTION 6: CITY CLERK RESPONSIBILITIES 4
SECTION 7: OPERATING DEPARTMENTS RESPONSIBILITIES 5
SECTION 8: PROCUREMENT PROCEDURES 6
8-1. Informal Procurement 6
8-2. Formal Procurement Over $100,000 7
8-3. Technical/Maintenance Services 9
8-4. Standard Agreement 10
8-5. Blanket Purchase Orders 10
8-6. Changes to and Cancellation of Purchase Orders 11
SECTION 9: SPECIAL PROCUREMENT CIRCUMSTANCES 11
9-1. Finance Department Procurements 11
9-2. CDBG and Other Applicable Federal Grants 12
9-3. Sole Source Purchases 12
9-4. Emergency Purchases up to $100,000 13
9-5. Emergencies Over $100,000 13
9-6. Emergency Public Projects 13
9-7. Cooperative Purchases 13
9-8. Piggyback onto Existing Contract 14
9-9. Exemptions from Obtaining a Purchase Order 14
SECTION 10: PROFESSIONAL SERVICES 16
10-1. Definition 16

Page 923 of 1480 ends

10-2. Operating Department Responsibilities 16
10-3. Decentralized 16
10-4. Solicitation of Proposals 17
10-5. Selection of Consultant 17
10-6. City Attorney Review and Approval 17
10-7. Procurement Limits 17
10-8. Changes to and Cancellation of Purchase Orders 18 SECTION 11: CONTRACT AMENDMENTS FOR TECHNICAL/MAINTENANCE OR PROFESSIONAL SERVICES 18
11-1. Operating Department Responsibilities 18
11-2. Amendment Cost Limits 19
SECTION 12: SPECIFICATIONS 19
12-1. Developing Specifications 19
12-2. Standardization 20
12-3. “Or Equal” 20
12-4. Vendor Assistance in Writing Specifications 20
12-5. Review of Specifications 20
SECTION 13: VENDOR RELATIONS 21
SECTION 14: PROTEST PROCEDURE AND ADMINISTRATIVE APPEAL 21 14-1. Bid Protests 21
14-2. Administrative Appeals 22
14-3. Public Project Protests and Appeals 22
SECTION 15: SURPLUS AND UNCLAIMED PROPERTY 23
15-1. Surplus/Unclaimed Property 23
15-2. Disposal of Personal Property (Less than $500) 23 SECTION 16: FEDERALLY DECLARED EMERGENCIES 23
APPENDIX I: DEFINITIONS

Page 924 of 1480 ends

1 CITY OF YUBA CITY

PURCHASING POLICIES AND PROCEDURES
Effective March 2022
SECTION 1: PURPOSE AND POLICY STATEMENT
1-1. Purpose:

The purpose of these policies and procedures is to provide the City of Yuba City a means of assuring continuity and uniformity in its purchasing practices; to provide for the fair and equitable treatment of all persons involved in the procurement process; to define the responsibilities of the Purchasing Officer, Finance Department, Engineering Division, City Clerk, and operating departments; and to develop a purchasing manual.

The guiding principle of these purchasing procedures shall be to comply with state law, the City’s Municipal Code, and the adopted budget on all purchases and contracts.

Guidelines for purchasing materials, supplies, and services are provided herein and the “City of Yuba City Procurement Card Handbook,” which is available on CityNET. 1-2. Policy Statement:

The policies and procedures contained herein are promulgated under the authority of the Yuba City Municipal Code Title 2, Chapter 6, Section 24, which states: “The Purchasing Officer shall establish, and from time-to-time amend, all rules and regulations authorized by this chapter and others necessary to its operation. Such rules and regulations, and amendments thereto, shall be subject to the approval of the Council by resolution.” The Finance Director is charged with the responsibility and authority for coordinating and managing the procurement of the City’s materials, supplies, and services.

Procedures outlined herein are to be followed by the Finance Department and operating departments when procuring materials, supplies, and services.

SECTION 2: ETHICS, GIFTS, AND UNAUTHORIZED PURCHASES
2-1. Code of Ethics:

1. To regard public service as a sacred trust, giving primary consideration to the interests of the public agency and citizenry that employ us.

2. To purchase without prejudice, seeking to obtain the maximum value for each dollar expended.

3. To avoid unfair practices, giving all qualified vendors equal opportunity.

4. To honor our obligations and require that obligations to our public agency be honored.

Page 925 of 1480 ends

2 5. To accord vendor representatives courteous treatment, remembering that these representatives are important sources of information and assistance in solving our purchasing needs.

6. To refuse to accept any form of commercial bribery and prevent any appearance of so doing.

7. To be receptive to counsel from our colleagues and to cooperate with them to promote a spirit of teamwork and unity.

8. To conduct ourselves with fairness and dignity, and to demand honesty and truth in the purchasing process.

9. To strive for greater knowledge of purchasing methods and of the materials we purchase.

10. To cooperate with all organizations and individuals involved in activities designed to enhance the development of the purchasing profession, remembering that our actions reflect on the entire purchasing profession.
2-2. Gifts and Special Considerations:

These policies and procedures shall not be used by a City employee to procure, or assist in procuring, any materials, supplies, services, or equipment for the personal use of any employee, officer, or official of the City.

City employees, officers, or officials by virtue of position are not entitled to any special consideration from vendors and merchants in their personal affairs, nor are they to attempt to procure materials for personal use or for any other person.

City employees shall not solicit or accept gifts, entertainment, or anything more than $50.00 in value from vendors or others. Examples of acceptable gifts might include pencils, scratch pads, and other advertising supplies.
2-3. Unauthorized Purchases:

Except for procurement card purchases, emergencies, or other authorized exemptions, no purchases shall be made without an authorized purchase order. Purchases without an authorized purchase order or otherwise falling within an exception are void and not considered an obligation of the City. See Section 9 (Special Procurement Circumstances) for further information on exemptions from the purchase order process.

Invoices without an authorized purchase order, except for procurement card purchases and other authorized exemptions per Section 9, may be returned to the vendor unpaid at the discretion of the City.

The person ordering the unauthorized purchase may be held personally responsible for the error per the Personnel Rules and Regulations Section 1.16 – Discipline.

Page 926 of 1480 ends

3 SECTION 3: PURCHASING OFFICER RESPONSIBILITIES
When there is reference to the Purchasing Officer, it refers to the City Manager or their designee. The Purchasing Officer duties are generally delegated to the Finance Director or their designee. The Purchasing Officer shall:

1. Be charged with the responsibility and authority for coordinating and managing the procurement of the City’s materials, supplies, and services.

2. Negotiate, purchase, and/or contract for the City the needed quality in equipment, supplies, and services from the lowest responsible bidder.

3. Endeavor to promote full and open competition on purchases when at all possible.

4. Monitor and ensure (or cause to be) that no single professional services consultant or sole-sourced vendor is paid more than $100,000 per fiscal year without prior Council authorization.

5. Revise and maintain these policies and procedures as needed to ensure Municipal Code compliance and protect the interest of the City of Yuba City.

6. Ensure adequate funding is secured in the fund accounts against which any purchase is to be charged.

When there is reference to the City Manager by title, it refers to the City Manager in their role as the Chief Executive Officer and their authority to approve and sign contracts and purchase orders.

SECTION 4: FINANCE DEPARTMENT RESPONSIBILITIES
The Finance Department shall ensure that the purchasing functions operate efficiently and assist operating departments. Finance shall:

1. Maintain open communication with operating departments and become acquainted with the needs of the various City departments and divisions.

2. Support department/division requisitions.

3. Assist purchasing, as needed, materials, supplies, and services required by any department/division.

4. Follow-up, expedite, and resolve problems with orders as requested.

5. Identify, evaluate, and utilize purchasing arrangements which best meet the needs of the City (e.g., cooperative purchases, blanket purchase orders, contractual agreements, etc.)

6. Assist operating departments with research and recommendations for developing specifications, and review specifications for completeness of information and open and competitive language.

7. Issue purchase orders to the requesting operating departments after completion of all required procurement processes.

8. Recommend revisions to purchasing procedures when necessary and keep informed of current developments in the field of purchasing.

Page 927 of 1480 ends

4 9. Act as the City’s agent in the disposal and transfer of surplus materials. The Finance Department may designate the operating departments to assist in or conduct this process.

10. Prescribe and maintain all forms and records necessary for efficient operation. The most current and acceptable mandatory and voluntary forms and templates shall be readily accessible to the operating departments on CityNet. The Standard Agreement and Professional Services Agreement templates shall be as approved by the City Attorney.

11. Maintain approved direct pay vendor list.

SECTION 5: PUBLIC CONTRACT CODE
The City’s Engineering Division of the Public Works Department is the focal point for all “public projects.” As per City Municipal Code 2-6.02(d) (Public project):

The City elects to be subject to the Uniform Public Construction Cost Accounting Act as set forth in Section 22000 et seq. of the Public Contract Code (“Act”), and the uniform construction cost accounting procedures as set forth in said Act. Public project shall be as defined in the Act and shall be performed or awarded in accordance with the Act as the Act now reads or as hereinafter amended.
5-1. Engineering Division Responsibilities:

1. Maintain a bid numbering system to be used citywide for all informal and formal Public Contract Code bids.

2. Maintain the City’s required public record for all Public Contract Code bids.

3. Mail a written notice in November, of each year, to construction trade journals/exchanges in accordance with the Cost Accounting Polices and Procedures Manual of the California Uniform Public Construction Cost Accounting Commission.

4. Maintain a Public Works construction projects formal and informal bidding matrix.

5. Assign a project lead for all Public Works formal bid projects being conducted for the City.

6. Have a representative attend their bid opening to be held publicly.

SECTION 6: CITY CLERK RESPONSIBILITIES
City Clerk or designee shall:

1. Receive and hold Finance formal and Public Contract Code bids prior to the bid opening.

2. Date and time stamp bids at the time of receipt. Bids will also be logged into a tracking system devised by the Office of the City Clerk.

3. Open and read bids publicly at the location, date, and time specified.

Page 928 of 1480 ends

5 4. Maintain and publicly post the official bid clock; the clock shall be clearly visible and marked.

SECTION 7: OPERATING DEPARTMENTS RESPONSIBILITIES
Any department that utilizes the goods and/or services purchased under a requisition shall be referred to as an operating department. Operating departments shall:

1. Maintain open communication with the Finance Department.

2. Monitor for any problems with vendor relations, shipping, (e.g., damaged goods, late delivery, wrong items delivered, incorrect quantity delivered, etc.) and any situations and/or concerns as necessary, in order to follow-up and resolve the problem.

3. Review and update annually, or as needed, an authorized signature list designating those individuals who are delegated the authority to sign purchase orders, Request for Payment forms, and invoices eligible for payment and their specified dollar limits. The Department Head shall provide this authorized signature list to the Purchasing Officer or designee on the form provided on CityNet.

4. Anticipate requirements sufficiently in advance, allowing adequate time to obtain materials, supplies, and services in accordance with the best purchasing practices.

5. Provide detailed and accurate specifications to ensure materials, supplies, and services obtained are consistent with expectations and requirements.

6. Coordinate and establish vendor relations, locate vendors, and evaluate vendor performance, bids, and responses.

7. Strive to obtain the highest quality goods consistent with operational needs, from the most responsible bidder, offering a price that is the most advantageous to the City.

8. Prepare purchase orders/requisitions carefully and properly in accordance with instructions; submit purchase requisitions to the Finance Department through the City’s finance management software (Pentamation at time of policy approval).

9. Minimize emergency and sole source purchases and, when such purchases are necessary, fully comply with the Municipal Code and this policy, including obtaining City Council or City Manager approval whenever necessary.

10. Make written recommendations, as required, based upon specification criteria, as well as perform reference checks to assist in determining lowest responsible bidder/proposer. Present a written memorandum to Finance when less than three quotes have been received or when not awarding to the lowest responsible vendor.

11. Ensure adequate funding is available in the fund accounts against which any purchase is to be charged.

12. Authorized individuals may purchase materials, supplies, and services by small purchase order or procurement card of a value up to $5,000. Departments must exercise reasonable prudence in seeking price quotes when purchasing such items.

All such purchases shall be made with funds in an unencumbered appropriation.

Page 929 of 1480 ends

6 SECTION 8: PROCUREMENT PROCEDURES
The primary purchasing objective is to obtain suitable goods, services, and construction at economic prices, as these acquisitions are direct costs to the taxpayer. The Municipal Code and purchasing policy require competition for all purchases over $5,000 and sealed competitive bids for over $100,000.

1. Bidding limits are generally “per order,” and orders are not to be split to circumvent the specified limits.

2. The estimated full-value cost of the item plus tax before any discount is the amount to be considered in determining bidding requirements. Even though the net purchase price could be lower than the bid thresholds, the asset value would be the full price of the item.

All purchases of supplies, equipment, and technical/maintenance services which qualify as part of a public project as defined by the Uniform Construction Cost Accounting Act shall be made in accordance with the Public Contract Code and Municipal Code Section 2-6.02. (see Section 5).
8-1. Informal Procurement:

The bidding limits below refer to supplies and technical/maintenance services and do not include professional/consultant services (see Section 10) or “public projects” (see Section 5). The bidding limits are below.
8-1.1. Bidding Limits and Requirements:

Bidding Limit Approving Authority
Procurement
Requirement Document Retention
Up to $5,000 Authorized staff No competition
required
No separate retention –
invoice should be
attached to small PO or
procurement card
report for Accounts
Payable
$5,000.01 to $25,000 Department Head
Informal bid (3 quotes
if possible) OR Sole
Source Justification
approved by
Department Head
Retained by operating
department with
purchase order
$25,000.01 to $50,000 Finance Director
Department Head
Informal bid (3 quotes
if possible) OR Sole
Source Justification
approved by
Department Head
Retained by Finance
with record of purchase
order
$50,000.01 to $100,000
City Manager
Finance Director
Department Head
Informal bid (3 quotes
if possible) OR Sole
Source Justification
approved by City
Manager
Retained by Finance
with record of purchase
order

Page 930 of 1480 ends

7 8-1.2 Informal Procurement Rules

1. Documents to be retained include written quotations and/or sole source justification, a copy of the agreement, and other associated required documents as applicable. Retention shall be in accordance with the City’s retention guidelines. Original contracts shall be given to the City Clerk’s office for retention.

2. Small purchase order or procurement card systems may be used for procurements up to $5,000; above $5,000 must use large purchase order system.

3. Staff procuring items via small purchase order or procurement card must be approved by the Department Head up to an appropriate procurement limit via the authorized signatures list maintained by the Finance Department.

4. Purchases that in total exceed a bidding limit are not to be split in order to obtain equipment, materials, or services under a lesser level of approval and procurement requirements.

5. A Request for Quotation form is recommended, though not required, for any informal bid above $25,000, and should be accompanied by specifications, insurance requirements, and contract agreement as applicable. 8-1.3. Justification:

Whenever the bidding/proposal process is dispensed with or the lowest bidder is not used, recommendation and justification for doing so shall be in writing and forwarded to the Finance Department at the time the requisition is prepared. It shall be signed by the requesting Department Head.
8-2. Formal Procurement Over $100,000 (Not for Public Projects)

1. Formal procurement process is required.

2. Competitive bidding is required unless otherwise authorized in these policies and procedures.

3. Written sole source justification can be used in certain circumstances with City Council approval, as per Section 9-3.

4. City Council approval is required.

5. Formal bids for public projects, including associated dollar thresholds, shall be done in accordance with Public Contract Code Section 22030 et seq., as per Section 5 of this policy.

Page 931 of 1480 ends

8 8-2.1. Formal Bids:

Formal quotations are written bids or proposals requiring a formal closing time/date. Public notices are posted on the City’s website and/or advertised in the local newspaper, at least ten days prior to the opening of the bids. When advertised in the newspaper, invitations for bid will be published at least two times. Formal bids are opened in public. 8-2.2. Formal Proposal Process:

The formal proposal process may be used in procurements involving complicated and performance-type specifications which may require involved negotiations or communications with vendors to clarify proposals submitted. The proposal process should be utilized in negotiated procurements or those procurements where the answer to a certain approach or a specific item necessary to satisfy the City’s needs is unknown. Public notice advertisements requesting invitations for proposal will be posted on the City’s website and/or published in the local newspaper at least two times; the first insertion must be at least ten days prior to the opening date. Formal proposals are made public upon execution of a signed contract.
8-2.3. Lowest Responsible Bidder:

Bids will be awarded to the responsive bidder who submits the lowest responsible bid that is most advantageous to the City and is consistent with the requirements of this procurement policy. The term “lowest responsible bidder” as used in the City’s bidding documents shall mean the lowest bidder whose offer best corresponds in quality, fitness, and capacity to the requirements of the proposed work or usage.

Sellers, vendors, suppliers, and contractors of supplies and equipment who maintain places of business located within the limits of the City shall be given preference if quality, price, and service are equal. In awarding the purchase, staff may consider the benefit derived by the City from sales tax revenues received by it in tabulating the lowest responsive bidder.

In determining the “lowest responsible bidder,” the following elements shall be given consideration (in addition to price):

1. The ability of the product offered to provide the quality, fitness, and capacity for the required usage.

2. The ability, capacity, and skill of the bidder to perform the contract or provide the service required.

3. The character, integrity, reputation, judgment, experience, and efficiency of the bidder, particularly with reference to past purchases by the City.

4. Whether the bidder can perform the contract and/or deliver the materials, supplies, and services within the time required.

5. The quality of performance and/or quality of products provided in previous contracts or services.

Page 932 of 1480 ends

9 6. Other information secured and having a bearing on the decision to award the contract.

7. Continuity of service.
8-2.4. Responsiveness:

A responsive bid is one which is in substantial conformance with the requirements of the invitation to bid, including specifications and the City’s contractual terms and conditions.

Bidders who substitute terms and conditions or who qualify their bids in such a manner as to nullify or limit their liability may be considered a non-responsive bidder and reject on those grounds. Conformance with the requirements of the invitation to bid may also include, but is not limited to, completion of forms, inclusion of references and attachments, and completion of required responses.
8-2.5 Rejection of Bids/Proposals:

The authority to reject is based on the authority to award. The City of Yuba City reserves the right: (1) to reject any or all bids or any part thereof and (2) to waive any informalities and/or negotiate minor deviations to the bid with the successful firm. The City of Yuba City’s decision shall be final.
8-2.6. Late Formal Bids/Proposals:

Formal bids or proposals submitted after the designated closing time shall be returned unopened and not accepted.
8-2.7. Tie Bidders:

If two or more bids are received which are in all respects equal, the City Council may award to the local vendor. If both are local vendors or none are local vendors, City Council may draw lots, re-bid, or the award may be made to the one deemed in the best interest of the City.
8-3. Technical/Maintenance Services:

Services of a general nature (as opposed to professional/consulting services) shall be contracted by following a Request for Proposal or Bid process. The method of selection shall be determined by the Purchasing Officer and may include both qualification of the service provider and cost of the service. If it is determined by the operating department in consultation with the Purchasing Officer that all vendors providing a service classification can equally provide the service satisfactorily, a bid process would be appropriate; however, if factors other than price need to be considered in awarding the contract, a proposal process may be used.

Proposals evaluated by the City for technical/maintenance services should be based on a combination of qualifications and cost. Examples of areas other than price that may be

Page 933 of 1480 ends