CITY OF BEAUMONT CONTRACTOR SUBMITTALS
BEAUMONT MESA L-S FORCE MAIN 013300 - 4

2. Note date and content of revision in label or title block and clearly indicate extent of revision.

3. Resubmit submittals until they are marked with approval notation from Engineer's action stamp.

H. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

I. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Engineer's action stamp.

PART 2 - PRODUCTS

2.1 SUBMITTAL PROCEDURES
A. General Submittal Procedure Requirements:

1. Action Submittals: Submit one (1) electronic copy of each submittal unless otherwise indicated.

2. Informational Submittals: Submit one (1) electronic copy unless otherwise indicated.

3. Certificates and Certifications Submittals: Provide a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
a. Provide a digital signature with digital certificate on el ectronically-submitted certificates and certifications where indicated.
b. Provide a notarized statement on original paper copy certificates and certifications where indicated.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards. e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:

Page 869 of 1492 ends

CITY OF BEAUMONT CONTRACTOR SUBMITTALS
BEAUMONT MESA L-S FORCE MAIN 013300 - 5
a. Wiring diagrams showing factory-installed wiring.
b. Printed performance curves.
c. Operational range diagrams.
d. Clearances required to other construction, if not indicated on accompanying Shop Drawings.

5. Submit Product Data before or concurrent with Samples.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement. f. Relationship and attachment to adjoining construction clearly indicated. g. Seal and signature of professional engineer if specified.

2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches, but no larger than 30 by 42 inches.

D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Identification: Attach label on unexposed side of Samples that includes the following:
a. Generic description of Sample.
b. Product name and name of manufacturer.
c. Sample source.
d. Number and title of applicable Specification Section.

3. For projects where electronic submittals are required, provide corresponding electronic submittal of Sample transmittal, digital image file illustrating Sample characteristics, and identification information for record.

4. Disposition: Maintain sets of approved Samples at Project site, available for quality- control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set. a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use.
b. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the property of Contractor.

Page 870 of 1492 ends

CITY OF BEAUMONT CONTRACTOR SUBMITTALS
BEAUMONT MESA L-S FORCE MAIN 013300 - 6

5. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available. a. Number of Samples: Submit two (2) full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Engineer will return submittal with options selected.

6. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.
a. Number of Samples: Submit two (2) sets of Samples. Engineer will retain one (1) Sample sets; remainder will be returned. Mark up and retain one returned Sample set as a project record sample.
1) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least three sets of paired units that show approximate limits of variations.

E. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:

1. Submit product schedule in the following format:
a. Four (4) paper copies of product schedule or list unless otherwise indicated.

Engineer will return three (3) copies.

F. Coordination Drawings Submittals: Comply with requirements specified in Section 013100 "Project Management and Coordination."
G. Contractor's Construction Schedule: Comply with requirements specified in Section 013200 "Construction Progress Documentation."
H. Test and Inspection Reports and Schedule of Tests and Inspections Submittals: Comply with requirements specified in Section 014000 "Quality Requirements." I. Closeout Submittals and Maintenance Material Submittals: Comply with requirements specified in Section 017700 "Closeout Procedures."
J. Maintenance Data: Comply with requirements specified in Section 017823 "Operation and Maintenance Data."
K. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of engineers and owners, and other information specified.

Page 871 of 1492 ends

CITY OF BEAUMONT CONTRACTOR SUBMITTALS
BEAUMONT MESA L-S FORCE MAIN 013300 - 7
L. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified.

M. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

N. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.

O. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

P. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

Q. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

R. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

S. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project.

T. Schedule of Tests and Inspections: Comply with requirements specified in Section 014000 "Quality Requirements."
U. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.

V. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

W. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

X. Design Data: Prepare and submit written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations.

Include list of assumptions and other performance and design criteria and a summary of loads.

Page 872 of 1492 ends

CITY OF BEAUMONT CONTRACTOR SUBMITTALS
BEAUMONT MESA L-S FORCE MAIN 013300 - 8
Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.

2.2 DELEGATED-DESIGN SERVICES
A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.

1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Engineer.

B. Delegated-Design Services Certification: In addition to Shop Drawings, Product Data, and other required submittals, submit three electronic copies of the certificate(s), signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.

1. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in pe rforming these services.

PART 3 - EXECUTION

3.1 CONTRACTOR'S REVIEW
A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Engineer.

B. Project Closeout and Maintenance Material Submittals: See requirements in Section 017700 "Closeout Procedures."
C. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include P roject name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents. In the case of shop drawings, each sheet shall be so dated, signed and certified.

3.2 ENGINEER'S ACTION
A. General: Engineer will not review submittals that do not bear Contractor's approval stamp and will return them without action.

B. Action Submittals: Engineer will review each submittal, make marks to indicate corrections or revisions required, and return it. Engineer will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action, as follows:

Page 873 of 1492 ends

CITY OF BEAUMONT CONTRACTOR SUBMITTALS
BEAUMONT MESA L-S FORCE MAIN 013300 - 9

1. “NO EXCEPTIONS TAKEN” or “EXCEPTIONS AS NOTED” will require no formal revision and resubmission.

2. “REVISE AND RESUBMIT” or “REJECTED” will require the Contractor to revise said submittal and shall resubmit the required number of copies of said revised submittal to the Engineer.

C. Informational Submittals: Engineer will review each submittal and will not return it, or will return it if it does not comply with requirements. Engineer will forward each submittal to appropriate party.

D. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.

E. Submittals not required by the Contract Documents may not be reviewed and may be discarded.

F. Fabrication of an item shall commence only after the Engineer has reviewed the submittal and returned copies to the Contractor marked either “NO EXCEPTIONS TAKEN” or “EXCEPTIONS AS NOTED”. Corrections indicated on submittals shall be considered as changes necessary to meet the requirements of the Contract Documents and shall not be taken as the basis of claims for extra work.

END OF SECTION 013300

Page 874 of 1492 ends

CITY OF BEAUMONT CONTRACTOR SUBMITTALS
BEAUMONT MESA L-S FORCE MAIN 013300 - 10

THIS PAGE INTENTIONALLY LEFT BLANK

Page 875 of 1492 ends

CITY OF BEAUMONT QUALITY REQUIREMENTS
BEAUMONT MESA L-S FORCE MAIN 014000-1
SECTION 014000 - QUALITY REQUIREMENTS
PART 1 - GENERAL

1.1 SUMMARY
A. Section includes administrative and procedural requirements for quality assurance and quality control.

B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.

1. Specified tests, inspections, and related actions do not limit Contractor's other quality- assurance and -control procedures that facilitate compliance with the Contract Document requirements.

2. Requirements for Contractor to provide quality-assurance and -control services required by Engineer, Owner, Construction Manager, or authorities having jurisdiction are not limited by provisions of this Section.

3. Specific test and inspection requirements are not specified in this Section.

1.2 DEFINITIONS
A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.

B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Services do not include contract enforcement activities performed by Engineer or Construction Manager.

C. Preconstruction Testing: Tests and inspections performed specifically for Project before products and materials are incorporated into the Work, to verify performance or compliance with specified criteria.

D. Product Testing: Tests and inspections that are performed by an NRTL, an NVLAP, or a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with specified requirements.

E. Source Quality-Control Testing: Tests and inspections that are performed at the source, e.g., plant, mill, factory, or shop.

F. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work.

G. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.

Page 876 of 1492 ends

CITY OF BEAUMONT QUALITY REQUIREMENTS
BEAUMONT MESA L-S FORCE MAIN 014000-2
H. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.

1. Use of trade-specific terminology in referring to a trade or entity does not require that certain construction activities be performed by accredited or unionized individuals, or that requirements specified apply exclusively to specific trade(s).

I. Experienced: When used with an entity or individual, "experienced" means having successfully completed a minimum of five (5) previous projects similar in nature, size, and extent to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.

1.3 CONFLICTING REQUIREMENTS
A. Referenced Standards: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer conflicting requirements that are different, but apparently equal, to Engineer for a decision before proceeding.

B. In instances where a conflict arises between standards and/or between the Technical Specifications and the Design Drawings, the more stringent standard or requirement shall govern at the discretion of Owner and Engineer.

C. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits.

To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Engineer for a decision before proceeding.

1.4 INFORMATIONAL SUBMITTALS
A. Contractor's Statement of Responsibility: When required by authorities having jurisdiction, submit copy of written statement of responsibility sent to authorities having jurisdiction before starting work on the following systems:

1. Seismic-force-resisting system, designated seismic system, or component listed in the designated seismic system quality-assurance plan prepared by Engineer.

2. Main wind-force-resisting system or a wind-resisting component listed in the wind-force- resisting system quality-assurance plan prepared by Engineer.

B. Testing Agency Qualifications: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.

Page 877 of 1492 ends

CITY OF BEAUMONT QUALITY REQUIREMENTS
BEAUMONT MESA L-S FORCE MAIN 014000-3

1.5 REPORTS AND DOCUMENTS
A. Test and Inspection Reports: Prepare and submit certified written reports specified in other Sections. Include the following:

1. Date of issue.

2. Project title and number.

3. Name, address, and telephone number of testing agency.

4. Dates and locations of samples and tests or inspections.

5. Names of individuals making tests and inspections.

6. Description of the Work and test and inspection method.

7. Identification of product and Specification Section.

8. Complete test or inspection data.

9. Test and inspection results and an interpretation of test results.

10. Record of temperature and weather conditions at time of sample taking and testing and inspecting.

11. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements.

12. Name and signature of laboratory inspector.

13. Recommendations on retesting and re-inspecting.

B. Manufacturer's Field Reports: Prepare written information documenting tests and inspections specified in other Sections. Include the following:

1. Name, address, and telephone number of representative making report.

2. Statement on condition of substrates and their acceptability for installation of product.

3. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken.

4. Results of operational and other tests and a statement of whether observed performance complies with requirements.

5. Other required items indicated in individual Specification Sections.

C. Permits, Licenses, and Certificates: For Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.

1.6 QUALITY ASSURANCE
A. General: Qualifications paragraphs in this article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.

B. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in -service performance, as well as sufficient production capacity to produce required units.

C. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

Page 878 of 1492 ends

CITY OF BEAUMONT QUALITY REQUIREMENTS
BEAUMONT MESA L-S FORCE MAIN 014000-4
D. Installer Qualifications: A firm or individual experienced in installing, ere cting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.

E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar in material, design, and extent to those indicated for this Project.

F. Specialists: Certain Specification Sections require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.

1. Requirements of authorities having jurisdiction shall supersede requirements for specialists.

G. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspecting indicated, as documented according to ASTM E 329; and with additional qualifications specified in individual Sections; and, where required by authorities having jurisdiction, that is acceptable to authorities.

1. NRTL: A nationally recognized testing laboratory according to 29 CFR 1910.7.

2. NVLAP: A testing agency accredited according to NIST's National Voluntary Laboratory Accreditation Program.

H. Manufacturer's Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to observe and inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.

I. Preconstruction Testing: Where testing agency is indicated to perform preconstruction testing for compliance with specified requirements for performance and test methods, comply with the following:

1. Contractor responsibilities include the following:
a. Provide test specimens representative of proposed products and construction. b. Submit specimens in a timely manner with sufficient time for testing and analyzing results to prevent delaying the Work.
c. Build laboratory mockups at testing facility using personnel, products, and methods of construction indicated for the completed Work. d. When testing is complete, remove test specimens, assemblies, and mockups, and laboratory mockups; do not reuse products on Project.

2. Testing Agency Responsibilities: Submit a certified written report of each test, inspection, and similar quality-assurance service to Engineer, through Construction Manager, with copy to Contractor. Interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.

Page 879 of 1492 ends

CITY OF BEAUMONT QUALITY REQUIREMENTS
BEAUMONT MESA L-S FORCE MAIN 014000-5

1.7 QUALITY CONTROL
A. Owner Responsibilities: Where quality-control services are indicated as Owner's responsibility, Owner will engage a qualified testing agency to perform these services. It is the Contractor’s responsibility to schedule the testing provided by such agencies.

1. Owner will furnish Contractor with names, addresses, and telephone numbers of testing agencies engaged and a description of types of testing and inspecting they are engaged to perform.

2. Costs for retesting and re-inspecting construction that replaces or is necessitated by work that failed to comply with the Contract Documents will be charged to Contractor.

B. Owner will engage a qualified testing agency to perform following services:

1. Soil Density Testing

2. Cast -in -Place concrete testing

3. Special Inspections
C. Contractor Responsibilities: Tests and inspections not explicitly assigned to Owner are Contractor's responsibility. Perform additional quality-control activities required to verify that the Work complies with requirements, whether specified or not.

1. Where services are indicated as Contractor's responsibility, engage a qualified testing agency to perform these quality-control services.
a. Contractor shall not employ same entity engaged by Owner, unless agreed to in writing by Owner.

2. Notify testing agencies at least twenty-four (24) hours in advance of time when Work that requires testing or inspecting will be performed.

3. Where quality-control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality-control service.

4. Testing and inspecting requested by Contractor and not required by the Contract Documents are Contractor's responsibility.

5. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.

D. Manufacturer's Field Services: Where indicated, engage a manufacturer's representative to observe and inspect the Work. Manufacturer's representative's services include examination of substrates and conditions, verification of materials, inspection of completed portions of the Work, and submittal of written reports.

E. Retesting/Re-inspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that replaced Work that failed to comply with the Contract Documents.

F. Testing Agency Responsibilities: Cooperate with Engineer, Construction Manager, and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.

1. Notify Engineer, Construction Manager, and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.

Page 880 of 1492 ends

CITY OF BEAUMONT QUALITY REQUIREMENTS
BEAUMONT MESA L-S FORCE MAIN 014000-6

2. Determine the location from which test samples will be taken and in which in-situ tests are conducted.

3. Conduct and interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.

4. Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor.

5. Do not release, revoke, alter, or increase the Contract Document requirements or approve or accept any portion of the Work.

6. Do not perform any duties of Contractor.

G. Associated Services: Cooperate with agencies performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:

1. Access to the Work.

2. Incidental labor and facilities necessary to facilitate tests and inspections.

3. Adequate quantities of representative samples of materials that require testing and inspecting. Assist agency in obtaining samples.

4. Facilities for storage and field curing of test samples.

5. Delivery of samples to testing agencies.

6. Preliminary design mix proposed for use for material mixes that require control by testing agency.

7. Security and protection for samples and for testing and inspecting equipment at Project site.

H. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and -control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.

1. Schedule times for tests, inspections, obtaining samples, and similar activities.

1.8 SPECIAL TESTS AND INSPECTIONS
A. Special Tests and Inspections: Conducted by a qualified special inspector as required by authorities having jurisdiction, as indicated in individual Specification Sections and in Statement of Special Inspections included in the Contract Documents (Drawings), and as follows:

1. Verifying that manufacturer maintains detailed fabrication and quality-control procedures and reviews the completeness and adequacy of those procedures to perform the Work.

2. Notifying Engineer, Construction Manager, and Contractor promptly of irregularities and deficiencies observed in the Work during performance of its services.

3. Submitting a certified written report of each test, inspection, and similar quality-control service to Engineer, through Construction Manager, with copy to Contractor and to authorities having jurisdiction.

4. Submitting a final report of special tests and inspections at Substantial Completion, which includes a list of unresolved deficiencies.

5. Interpreting tests and inspections and stating in each report whether tested and inspected work complies with or deviates from the Contract Documents.

Page 881 of 1492 ends

CITY OF BEAUMONT QUALITY REQUIREMENTS
BEAUMONT MESA L-S FORCE MAIN 014000-7

6. Retesting and re-inspecting corrected work.

PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION

3.1 TEST AND INSPECTION LOG
A. Test and Inspection Log: Prepare a record of tests and inspections. Include the following:

1. Date test or inspection was conducted.

2. Description of the Work tested or inspected.

3. Date test or inspection results were transmitted to Engineer.

4. Identification of testing agency or special inspector conducting test or inspection.

B. Maintain log at Project site. Post changes and revisions as they occur. Provide access to test and inspection log for Engineer's and Construction Manager's reference during normal working hours.

3.2 REPAIR AND PROTECTION
A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.

1. Provide materials and comply with installation requirements specified in other Specification Sections or matching existing substrates and finishes. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible.

B. Protect construction exposed by or for quality-control service activities.

C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.

END OF SECTION 014000

Page 882 of 1492 ends

CITY OF BEAUMONT QUALITY REQUIREMENTS
BEAUMONT MESA L-S FORCE MAIN 014000-8

THIS PAGE INTENTIONALLY LEFT BLANK

Page 883 of 1492 ends

CITY OF BEAUMONT PERMITS
BEAUMONT MESA L-S FORCE MAIN 014120-1

SECTION 014120 – PERMITS

PART 1 - GENERAL

1.1 ADMINISTRATIVE REQUIREMENTS
A. Obtain permits required for the execution of Work in accordance with the Contract Documents.

Provide copies of these permits to Owner.

B. The intent of this Section is to furnish the known list of required permits for the Work under the Contract Documents. Contractor is responsible for determining and verifying the extent of all permits required and for obtaining such permits.

C. In the Bid Price, include costs for obtaining all necessary permits, including application fees and other costs, and the costs of complying with the conditions of all permits. Any fees listed in this section are estimates and are for information only. Verify and pay all actual fees.

D. Within 30 Days of the Limited Notice to Proceed, submit a list of all permits and licenses to be obtained, indicating the agency required to grant the permit, the expected date of submittal for the permit, and required date for receipt of the permit.

1.2 SUMMARY OF PERMITS TO BE OBTAINED BY CONTRACTOR
A. Obtain the following permits. Submit copies of these permits to Engineer and maintain copies on- site. Comply with all conditions of the permits and pay all applicable fees. Types of permits that may be required include:

1. SWPPP.

2. Any required construction permits from City, County, or State agencies. (City Encroachment Permit).

3. Permits for road construction.

4. Permits for transport of equipment and materials to/from the site.

5. Permits for disposal of any debris or demolition materials (as needed)

6. Permits required for environmental protection including dewatering and discharging of waters.

7. Permits for noise or pollution control as required.

8. Any temporary AQMD permits associated with construction efforts.

1.3 SUMMARY OF PERMITS OBTAINED BY OWNER
A. N/A
END OF SECTION 014120

Page 884 of 1492 ends

CITY OF BEAUMONT PERMITS
BEAUMONT MESA L-S FORCE MAIN 014120-2

THIS PAGE INTENTIONALLY LEFT BLANK

Page 885 of 1492 ends

CITY OF BEAUMONT ABBREVIATIONS AND REFERNCE STANDARDS
BEAUMONT MESA L-S FORCE MAIN 014200-1

SECTION 014200 – ABBREVIATIONS AND REFERENCE STANDARDS
PART 1 - GENERAL

1.1 DEFINITIONS
A. General: Basic Contract definitions are included in the Conditions of the Contract.

B. "Approved": When used to convey Engineer's action on Contractor's submittals, applications, and requests, "approved" is limited to Engineer's duties and responsibilities as stated in the Conditions of the Contract.

C. "Directed": A command or instruction by Engineer. Other terms including "requested," "authorized," "selected," "required," and "permitted" have the same meaning as "directed." D. "Indicated": Requirements expressed by graphic representations or in written form on Drawings, in Specifications, and in other Contract Documents. Other terms including "shown," "noted," "scheduled," and "specified" have the same meaning as "indicated." E. "Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the construction industry that control performance of the Work.

F. "Furnish": Supply and deliver to Project site, ready for unloading, unpacking, assembly, installation, and similar operations.

G. "Install": Unload, temporarily store, unpack, assemble, erect, place, anchor, apply, work to dimension, finish, cure, protect, clean and similar operations at Project site.

H. "Provide": Furnish and install, complete and ready for the intended use.

I. "Project Site": Space available for performing construction activities. The extent of Project site is shown on Drawings and may or may not be identical with the description of the land on which Project is to be built.

1.2 INDUSTRY STANDARDS
A. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference.

B. Publication Dates: Comply with standards in effect as of date of the Contract Documents unless otherwise indicated.

C. Copies of Standards: Each entity engaged in construction on Project should be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents.

Page 886 of 1492 ends

CITY OF BEAUMONT ABBREVIATIONS AND REFERNCE STANDARDS
BEAUMONT MESA L-S FORCE MAIN 014200-2

1. Where copies of standards are needed to perform a required construction activity, obtain copies directly from publication source.

D. All work specified herein shall conform to or exceed the requirements of the referenced specifications, codes and standards to the extent that the provisions of such documents are not in conflict with the requirements of these Specifications.

E. References herein to "Building Code" shall mean the California Building Code (CBC) of the International Code Council (ICC). The latest edition of the code, as approved and adopted by the agency having jurisdiction, including all addenda, modifications, amendments or other lawful changes thereto, shall apply to the Work.

F. In case of conflict between codes, reference standards, drawings and the other Contract Documents, the most stringent requirements shall govern. All conflicts shall be brought to the attention of the Engineer for clarification and directions prior to ordering or providing any materials or labor. The Contractor shall bid the most stringent requirements.

G. Applicable Standard Specifications: The Contractor shall construct the Work specified herein in accordance with the requirements of the Contract Documents and the referenced portions of those referenced codes, standards and specifications listed herein.

H. References herein to "OSHA Regulations for Construction" shall mean Title 29, Part 1926, Construction Safety and Health Regulations, Code of Federal Regulations (OSHA), including all changes and amendments thereto.

1.3 ABBREVIATIONS AND ACRONYMS
A. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities indicated in Gale's "Encyclopedia of Associations: National Organizations of the U.S." or in Columbia Books' "National Trade & Professional Associations of the United States." B. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list.

AA Aluminum Association
AAMA American Architectural Manufacturers Association
AASHTO American Association of State Highway and Transportation Officials ACI American Concrete Institute (Formerly: ACI International) ACPA American Concrete Pipe Association
AGA American Gas Association
AGC Associated General Contractors
AHRI Air-Conditioning, Heating, and Refrigeration Institute (The) AI Asphalt Institute
AIA American Institute of Architects (The)
AISC American Institute of Steel Construction
AISI American Iron and Steel Institute
AITC American Institute of Timber Construction
AMCA Air Movement and Control Association International, Inc.

ANSI American National Standards Institute
APA APA - The Engineered Wood Association

Page 887 of 1492 ends

CITY OF BEAUMONT ABBREVIATIONS AND REFERNCE STANDARDS
BEAUMONT MESA L-S FORCE MAIN 014200-3

APA Architectural Precast Association
API American Petroleum Institute
APWA American Public Works Association
ASA Acoustical Society of America
ASAE American Society of Agriculture Engineer
ASCE American Society of Civil Engineers
ASCE/SEI American Society of Civil Engineers/Structural Engineering Institute (See ASCE) ASHRAE American Society of Heating, Refrigerating and Air-Conditioning Engineers ASLE American Society of Lubricating Engineers
ASME American Society of Mechanical Engineers
ASQC American Society for Quality Control
ASSE American Society of Safety Engineers (The)
ASSE American Society of Sanitary Engineering
ASTM American Society for Testing and Materials International ATIS Alliance for Telecommunications Industry Solutions AWPA American Wood Protection Association
AWPI American Wood Preservers Institute
AWS American Welding Society
AWWA American Water Works Association
BHMA Builders Hardware Manufacturers Association
BIA Brick Industry Association (The)
BOCA BOCA (Building Officials and Code Administrators International Inc.) CDA Copper Development Association
CGA Compressed Gas Association
CLFMI Chain Link Fence Manufacturers Institute
CMA Concrete Masonry Association
CPA Composite Panel Association
CRSI Concrete Reinforcing Steel Institute
DASMA Door and Access Systems Manufacturers Association DHI Door and Hardware Institute
ETL Electrical Test Laboratories
GA Gypsum Association
GANA Glass Association of North America
HI Hydraulic Institute
HMMA Hollow Metal Manufacturers Association (See NAAMM) HPVA Hardwood Plywood & Veneer Association
ICBO International Conference of Building Officials (See ICC) ICC International Code Council
ICEA Insulated Cable Engineers Association, Inc.

ICPA International Cast Polymer Alliance
ICRI International Concrete Repair Institute, Inc.

IEEE Institute of Electrical and Electronics Engineers, Inc. (The) IES Illuminating Engineering Society
IPC Institute of Printed Circuits
IPCEA Insulated Power Cable Engineers Association
ISA International Society of Automation
ISO International Organization for Standardization
LPI Lightning Protection Institute
MBMA Metal Building Manufacturers Association
MCA Metal Construction Association
MHIA Material Handling Industry of America

Page 888 of 1492 ends

CITY OF BEAUMONT ABBREVIATIONS AND REFERNCE STANDARDS
BEAUMONT MESA L-S FORCE MAIN 014200-4

MPI Master Painters Institute
MSS Manufacturers Standardization Society of The Valve and Fittings Industry Inc.

NAAMM National Association of Architectural Metal Manufacturers NACE NACE International (National Association of Corrosion Engineers International) NAIMA North American Insulation Manufacturers Association NBS National Bureau of Standards
NCMA National Concrete Masonry Association
NEC National Electrical Code
NECA National Electrical Contractors Association
NEMA National Electrical Manufacturers Association
NFPA NFPA (National Fire Protection Association)
NFPA National Forest Products Association
NFRC National Fenestration Rating Council
NHLA National Hardwood Lumber Association
NLGI National Lubricating Grease Institute
NRCA National Roofing Contractors Association
NRMCA National Ready Mixed Concrete Association
NSF NSF International (National Sanitation Foundation International) NSPE National Society of Professional Engineers
NSSGA National Stone, Sand & Gravel Association
OSHA Occupational Safety and Health Administration
PCA Portland Cement Association
PCI Precast/Prestressed Concrete Institute
PDI Plumbing & Drainage Institute
SDI Steel Door Institute
SEI/ASCE Structural Engineering Institute/American Society of Civil Engineers (See ASCE) SJI Steel Joist Institute
SMA Screen Manufacturers Association
SMACNA Sheet Metal and Air Conditioning Contractors' National Association SPFA Spray Polyurethane Foam Alliance
SPRI Single Ply Roofing Industry
SSPC Society for Protective Coatings
SSPC Steel Structures Painting Council
SSPWC Standard Specifications for Public Works Construction SWPA Submersible Wastewater Pump Association
UBC Uniform Building Code (See ICC)
UL Underwriters Laboratories Inc.

WASTEC Waste Equipment Technology Association
WCRSI Western Concrete Reinforcing Steel Institute
WDMA Window & Door Manufacturers Association
WRI Wire Reinforcement Institute, Inc.

WWPA Western Wood Products Association
C. Code Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list.

1. DIN- Deutsches Institut fur Normung e. V.; www.din.de .

2. IAPMO – International Association of Plumbing and Mechanical Officials; www.iapmo.org .

3. ICC – International Code Council; www.iccsafe.org .

4. ICC-ES – ICC Evaluation Service, LLC; www.icc-es.org .

Page 889 of 1492 ends

CITY OF BEAUMONT ABBREVIATIONS AND REFERNCE STANDARDS
BEAUMONT MESA L-S FORCE MAIN 014200-5

D. Federal Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list.

1. COE - Army Corps of Engineers; www.usace.army.mil .

2. CPSC - Consumer Product Safety Commission; www.cpsc.gov .

3. DOC - Department of Commerce; National Institute of Standards and Technology; www.nist.gov .

4. DOD - Department of Defense; www.quicksearch.dla.mil .

5. DOE - Department of Energy; www.energy.gov .

6. EPA - Environmental Protection Agency; www.epa.gov .

7. FAA - Federal Aviation Administration; www.faa.gov .

8. FG - Federal Government Publications; www.gpo.gov .

9. GSA - General Services Administration; www.gsa.gov .

10. HUD - Department of Housing and Urban Development; www.hud.gov .

11. LBL - Lawrence Berkeley National Laboratory; Environmental Energy Technologies Division; www.eetd.lbl.gov .

12. OSHA - Occupational Safety & Health Administration; www.osha.gov .

13. SD - Department of State; www.state.gov .

14. TRB - Transportation Research Board; National Cooperative Highway Research Program; The National Academies; www.trb.org .

15. USDA - Department of Agriculture; Agriculture Research Service; U.S. Salinity Laboratory; www.ars.usda.gov .

16. USDA - Department of Agriculture; Rural Utilities Service; www.usda.gov .

17. USDJ - Department of Justice; Office of Justice Programs; National Institute of Justice; www.ojp.usdoj.gov .

18. USP - U.S. Pharmacopeial Convention; www.usp.org .

USPS - United States Postal Service; www.usps.com .

END OF SECTION 014200

Page 890 of 1492 ends

CITY OF BEAUMONT ABBREVIATIONS AND REFERNCE STANDARDS
BEAUMONT MESA L-S FORCE MAIN 014200-6

THIS PAGE INTENTIONALLY LEFT BLANK

Page 891 of 1492 ends

CITY OF BEAUMONT TEMPORARY FACILITIES AND CONTROLS
BEAUMON MESA L-S FORCE MAIN 015000-1

SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL

1.1 SUMMARY
A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities.

B. Related Requirements:

1. Section 011000 "Summary of Work" for work restrictions and limitations on utility interruptions.

2. Requirements given in the General Conditions.

1.2 USE CHARGES
A. General: Installation and removal of and use charges for temporary facilities shall be included in the Contract Sum unless otherwise indicated. Allow other entities to use temporary services and facilities without cost, including, but not limited to, Owner's construction forces, Engineer, occupants of Project, testing agencies, and authorities having jurisdiction.

1.3 INFORMATIONAL SUBMITTALS
A. Erosion- and Sedimentation-Control Plan for projects disturbing more than 1 acre: Show compliance with requirements of EPA Construction General Permit or authorities having jurisdiction, whichever is more stringent.

B. Fire-Safety Program: Show compliance with requirements of NFPA 241 and authorities having jurisdiction. Indicate Contractor personnel responsible for management of fire prevention program.

1.4 QUALITY ASSURANCE
A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.

B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.

C. Accessible Temporary Egress: Comply with applicable provisions in the U.S. Architectural & Transportation Barriers Compliance Board's ADA-ABA Accessibility Guidelines and ICC/ANSI A117.1.

Page 892 of 1492 ends

CITY OF BEAUMONT TEMPORARY FACILITIES AND CONTROLS
BEAUMON MESA L-S FORCE MAIN 015000-2

1.5 PROJECT CONDITIONS
A. Temporary Use of Permanent Facilities: Engage Installer of each permanent service to assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Owner's acceptance, regardless of previously assigned responsibilities.

PART 2 - PRODUCTS

2.1 MATERIALS
A. Chain-Link Fencing: Minimum 2-inch, 0.148-inch- thick, galvanized-steel, chain-link fabric fencing; minimum 6 feet high with galvanized-steel pipe posts; minimum 2-3/8-inch- OD line posts and 2-7/8-inch- OD corner and pull posts.

B. Portable Chain-Link Fencing: Minimum 2-inch, 0.148-inch- thick, galvanized-steel, chain-link fabric fencing; minimum 6 feet high with galvanized-steel pipe posts; minimum 2-3/8-inch- OD line posts and 2-7/8-inch- OD corner and pull posts, with 1-5/8-inch- OD top and bottom rails.

Provide galvanized-steel bases for supporting posts.

2.2 TEMPORARY FACILITIES
A. Field Offices, Local Storage Yard, General: The contractor shall provide location and lease information regarding any local storage yard intended to be used. Only previously disturbed sites can be used as a local storage yard.

B. Contractor’s Field Office: NOT USED.

C. Inspector’s Field Office: NOT USED.

D. Storage and Fabrication Sheds: NOT USED.

E. Final location of Contractor’s temporary facilities shall be coordinated with the Owner to ensure that access critical to plant operations is maintained at all times.

2.3 EQUIPMENT
A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures. The Contractor shall provide fire extinguishers and other fire protection equipment to adequately protect new and existing facilities and temporary facilities against damage by fire. Hose connections and hose, water casks, chemical equipment or other sufficient means shall be provided for fighting fires in the new, existing and temporary structures and other portions of the Work and responsible persons shall be designated and instructed in the operation of such fire apparatus so as to prevent or minimize the hazard of fire.

The Contractor's fire protection program shall conform to the requirements of the OSHA Standards for Construction. The Contractor shall employ every reasonable means to prevent the hazard of fire.

Page 893 of 1492 ends

CITY OF BEAUMONT TEMPORARY FACILITIES AND CONTROLS
BEAUMON MESA L-S FORCE MAIN 015000-3

B. HVAC Equipment: Unless Owner authorizes use of permanent HVAC system, provide vented, self-contained, liquid-propane-gas or fuel-oil heaters with individual space thermostatic control.

1. Use of gasoline-burning space heaters, open-flame heaters, or salamander-type heating units is prohibited.

2. Heating Units: Listed and labeled for type of fuel being consumed, by a qualified testing agency acceptable to authorities having jurisdiction, and marked for intended location and application.

3. Permanent HVAC System: If Owner authorizes use of permanent HVAC system for temporary use during construction, provide filter with MERV of 8 at each return-air grille in system and remove at end of construction and clean HVAC system as required in Section 017700 "Closeout Procedures".

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL
A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.

1. Locate facilities to limit site disturbance as specified in Section 011000 "Summary of Work."
B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.

3.2 TEMPORARY UTILITY INSTALLATION
A. General: Install temporary service or connect to existing service.

1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.

B. Water Service: Install water service and distribution piping in sizes and pressures adequate for construction.

1. The Contractor shall provide an adequate supply of water of a quality suitable for all domestic and construction purposes.

2. Non-Potable water is not available on site. If procured from an alternative location, it may be used for grading and hydraulic structures and pipeline testing as approved by the Engineer.

3. The Contractor shall properly identify all construction water trucks and vessels and inform all workmen and the general public when reclaimed waste water is used as construction water.

Page 894 of 1492 ends

CITY OF BEAUMONT TEMPORARY FACILITIES AND CONTROLS
BEAUMON MESA L-S FORCE MAIN 015000-4

4. All drinking water on the site during construction shall be furnished by the Contractor and shall be bottled water or water furnished in approved metal dispensers. Notices shall be posted conspicuously throughout the site warning the Contractor's personnel that piped water may be contaminated.

5. The Contractor shall not make connection to, or draw water from, any fire hydrant or pipeline without first obtaining permission of the authority having jurisdiction over the use of said fire hydrant or pipeline and from the agency owning the water system. For each such connection made the Contractor shall first attach to the fire hydrant or pipeline a valve, backflow preventer and a meter, if required by the said authority, of a size and type acceptable to said authority and agency.

6. Before final acceptance of the Work all temporary water connections and piping installed by the Contractor shall be entirely removed, and all affected improvements shall be restored to their original condition, or better, to the satisfaction of the Engineer and to the agency owning the affected utility.

C. Waste Collection: Provide trash cans and instruct personnel to maintain a clean site.

D. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of construction personnel. Comply with requirements of authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.

1. Toilets: Portable chemical toilets shall be provided wherever needed for the use of employees. Toilets at construction job sites shall conform to the requirements of Subpart D, Section 1926.51 of the OSHA Standards for Construction. The Owner's toilet facilities shall not be used by the Contractor's work force.

2. The Contractor shall establish adequate and regular collection of all sanitary and organic wastes. All wastes and refuse from sanitary facilities provided by the Contractor or organic material wastes from any other source related to the Contractor's operations shall be disposed of in a manner satisfactory to the Engineer and in accordance with all laws and regulations pertaining thereto.

E. Heating and Cooling: Provide temporary heating and cooling required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of low temperatures or high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed.

F. Ventilation and Humidity Control: Provide temporary ventilation required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed. Coordinate ventilation requirements to produce ambient condition required and minimize energy consumption.

G. Electric Power Service: Electric Power Service from Existing System: Electric power from Owner's existing system will be made available for all Field office power requirements and construction activities limited by the site’s electrical system capacity as a whole or at a specific location. All use of power from Owner’s existing system shall be coordinated with the Owner and shall be associated with the activities related to construction.

Page 895 of 1492 ends

CITY OF BEAUMONT TEMPORARY FACILITIES AND CONTROLS
BEAUMON MESA L-S FORCE MAIN 015000-5

The Contractor shall be responsible to provide necessary electrical power. The contractor will be responsible for all temporary power and generators required during the construction and planned power shut-downs. The Contractor shall provide all necessary temporary power connection, disconnects and distribution lines required for its operations under the Contract and shall provide and maintain all temporary power systems required to perform the Work in a safe and satisfactory manner. All temporary connections for electricity shall be subject to approval of the Engineer and shall be completely removed at the Contractor's expense prior to final acceptance of the Work. All wiring for temporary electric light and power shall be properly installed and maintained and shall be securely fastened in place. All electrical facilities shall conform to the requirements of the OSHA Safety and Health Standards for Construction.

H. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions.

1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system.

I. Telephone Service: The Owner’s telephone system shall not be used by the Contractor’s work force.

1. Post a list of important telephone numbers in the project field office. a. Police and fire departments.
b. Ambulance service.
c. Contractor's home office.
d. Contractor's emergency after-hours telephone number. e. Engineers' offices.
f. Owner's office.
g. Principal subcontractors' field and home offices.

2. Provide superintendent with cellular telephone or portable two-way radio for use when away from field office.

3. The Contractor shall provide a telephone in their facility with an adequate speaker phone for use on conference calls. This system may be used for weekly conference calls/project progress meetings.

J. Electronic Communication Service: Provide a computer in the primary field office adequate for use by Engineer and Owner to access project electronic documents and maintain electronic communications.

3.3 SUPPORT FACILITIES INSTALLATION
A. General: Comply with the following:

1. Provide construction for temporary offices, shops, and sheds located within construction area or within 30 feet of building lines that is noncombustible according to ASTM E 136.

Comply with NFPA 241.

2. Maintain support facilities until Engineer schedules Substantial Completion inspection.

Remove before Substantial Completion. Personnel remaining after Substantial

Page 896 of 1492 ends

CITY OF BEAUMONT TEMPORARY FACILITIES AND CONTROLS
BEAUMON MESA L-S FORCE MAIN 015000-6

Completion will be permitted to use permanent facilities, with prior consent from the Owner and under conditions acceptable to Owner.

B. Temporary Roads: Access to the site shall be permitted by the Owner. The Contractor shall not construct any staging areas, haul roads, and access roads without the approval of the Owner.

1. Contractor to maintain clear access roadways and walkways necessary for the daily operation and maintenance of the plant. All road closures, trenching/excavation, or other construction activities that may interfere or impede access must be coordinated with and approved by Owner.

2. Where public road(s) pass through the construction area, access to and along this route must be maintained during construction. Contractor shall maintain a graded, non-paved road, to accommodate traffic on the road and allow for construction activities until the permanent road is installed. Contractor is responsible to provide suitable road-grade backfill, graded, for the road. Contractor shall maintain and regrade the road as required to maintain the road in acceptable condition. In addition, contractor shall maintain proper barricades and fencing along this road to secure the construction/staging areas from the public access road. Finally, contractor shall furnish traffic controls along public road as detailed below.

3. Provide dust-control treatment that is non-polluting and non-tracking. Reapply treatment as required to minimize dust.

C. Traffic Controls: Comply with requirements of authorities having jurisdiction and coordinate with the Owner’s Facility personnel.

1. Protect existing site improvements to remain including curbs, pavement, and utilities.

2. Maintain access for fire-fighting equipment and access to fire hydrants.

3. Contractor shall provide all lights, signs, barricades, flaggers, and other appurtenances necessary for safety.

D. Parking: Use designated areas of Owner's existing parking areas for construction personnel.

E. Dewatering Facilities and Drains: Comply with all Federal, State, and Local Government requirements. Maintain Project site, excavations, and construction free of water.

1. Dispose of rainwater in a lawful manner that will not result in flooding Project or adjoining properties or endanger permanent Work or temporary facilities.

2. Remove snow and ice as required to minimize accumulations.

F. Project Signs: Provide Project sign. Unauthorized signs are not permitted.

1. Temporary Signs: Provide other signs as indicated and as required to inform public and individuals seeking entrance to Project.
a. Provide temporary, directional signs for construction personnel and visitors.

2. Maintain and touchup signs so they are legible at all times.

Page 897 of 1492 ends

CITY OF BEAUMONT TEMPORARY FACILITIES AND CONTROLS
BEAUMON MESA L-S FORCE MAIN 015000-7

G. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction.

H. Lifts and Hoists: Provide facilities necessary for hoisting materials and personnel.

1. Truck cranes and similar devices used for hoisting materials are considered "tools and equipment" and not temporary facilities.

I. Temporary Stairs: Until permanent stairs are available, provide tempo rary stairs where ladders are not adequate.

J. Existing Stair Usage: Use of Owner's existing stairs will be permitted, provided stairs are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore stairs to condition existing before initial use.

1. Provide protective coverings, barriers, devices, signs, or other procedures to protect stairs and to maintain means of egress. If stairs become damaged, restore damaged areas so no evidence remains of correction work.

K. Temporary Use of Permanent Stairs: Use of new stairs for construction traffic will be permitted, provided stairs are protected and finishes restored to new condition at time of Substantial Completion.

3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other improvements at Project site and on adjacent properties, except those indicated to be removed or altered. Repair damage to existing facilities.

B. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

C. Temporary Erosion and Sedimentation Control: Provide measures to prevent soil erosion and discharge of soil-bearing water runoff and airborne dust to undisturbed areas and to adjacent properties and walkways, according to erosion- and sedimentation-control Drawings.

D. Stormwater Control: Comply with requirements of authorities having jurisdiction. Provide barriers in and around excavations and subgrade construction to prevent flooding by runoff of stormwater from heavy rains.

E. Tree and Plant Protection: Install temporary fencing located as indicated or outside the drip line of trees to protect vegetation from damage from construction operations. Protect tree root systems from damage, flooding, and erosion.

F. Pest Control: Engage pest-control service to recommend practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at Substantial Completion. Perform control operations lawfully, using environmentally safe materials.

Page 898 of 1492 ends

CITY OF BEAUMONT TEMPORARY FACILITIES AND CONTROLS
BEAUMON MESA L-S FORCE MAIN 015000-8

G. Site Access: Prior to commencing work the Owner will supply the contractor with access key(s) for the facility front gate. The contractor is responsible to:

1. Maintain security by limiting number of keys and restricting distribution to authorized personnel. Furnish one set of keys to Owner for any gates, enclosures or fenced areas constructed by the contractor.

2. The contractor shall be responsible for security of the site during non-working hours of the facility personnel.

H. Security Enclosure and Lockup: Install temporary enclosure around partially completed areas of construction. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security. Lock entrances at end of each work day.

I. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.

J. Temporary Egress: Maintain temporary egress from existing occupied facilities as indicated and as required by authorities having jurisdiction.

K. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weather tight enclosure for building exterior.

1. Where heating or cooling is needed and permanent enclosure is not complete, insulate temporary enclosures.

L. Temporary Partitions: Provide floor-to-ceiling dustproof partitions to limit dust and dirt migration and to separate areas occupied by Owner and tenants from fumes and noise.

1. Construct dustproof partitions with gypsum wallboard with joints taped on occupied side, and fire-retardant-treated plywood on construction operations side.

2. Construct dustproof partitions with two layers of 6-mil polyethylene sheet on each side.

Cover floor with two layers of 6-mil polyethylene sheet, extending sheets 18 inches up the sidewalls. Overlap and tape full length of joints. Cover floor with fire-retardant- treated plywood.
a. Construct vestibule and airlock at each entrance through temporary partition with not less than 48 inches between doors. Maintain water-dampened foot mats in vestibule.

3. Where fire-resistance-rated temporary partitions are indicated or are required by authorities having jurisdiction, construct partitions according to the rated assemblies.

4. Insulate partitions to control noise transmission to occupied areas.

5. Seal joints and perimeter. Equip partitions with gasketed dustproof doors and security locks where openings are required.

6. Protect air-handling equipment.

7. Provide walk-off mats at each entrance through temporary partition.

M. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with NFPA 241; manage fire prevention program.

Page 899 of 1492 ends

CITY OF BEAUMONT TEMPORARY FACILITIES AND CONTROLS
BEAUMON MESA L-S FORCE MAIN 015000-9

1. Prohibit smoking in construction areas.

2. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition according to requirements of authorities having jurisdiction.

3. Develop and supervise an overall fire-prevention and -protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings and information.

4. Provide temporary standpipes and hoses for fire protection. Hang hoses with a warning sign stating that hoses are for fire-protection purposes only and are not to be removed.

Match hose size with outlet size and equip with suitable nozzles.

3.5 MOISTURE AND MOLD CONTROL
A. Contractor's Moisture Protection Plan: Avoid trapping water in finished work. Document visible signs of mold that may appear during construction.

B. Exposed Construction Phase: Before installation of weather barriers, when materials are subject to wetting and exposure and to airborne mold spores, protect materials from water damage and keep porous and organic materials from coming into prolonged contact with concrete.

C. Partially Enclosed Construction Phase: After installation of weather barriers but before full enclosure and conditioning of building, when installed materials are still subject to infiltration of moisture and ambient mold spores, protect as follows:

1. Do not load or install drywall or other porous materials or components, or items with high organic content, into partially enclosed building.

2. Keep interior spaces reasonably clean and protected from water damage.

3. Discard or replace water-damaged and wet material.

4. Discard, replace, or clean stored or installed material that begins to grow mold.

5. Perform work in a sequence that allows any wet materials adequate time to dry before enclosing the material in drywall or other interior finishes.

D. Controlled Construction Phase of Construction: After completing and sealing of the building enclosure but prior to the full operation of permanent HVAC systems, maintain as follows:

1. Control moisture and humidity inside building by maintaining effective dry-in conditions.

2. Remove materials that cannot be completely restored to their manufactured moisture level within 48 hours.

3.6 OPERATION, TERMINATION, AND REMOVAL
A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.

B. Maintenance: Maintain facilities in good operating condition until removal.

1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.

Page 900 of 1492 ends

CITY OF BEAUMONT TEMPORARY FACILITIES AND CONTROLS
BEAUMON MESA L-S FORCE MAIN 015000-10

C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.

D. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.

1. Materials and facilities that constitute temporary facilities are property of Contractor.

Owner reserves right to take possession of Project identification signs.

2. At Substantial Completion, repair, renovate, and clean permanent facilities used during construction period. Comply with final cleaning requirements specified in Section 017700 "Closeout Procedures."

END OF SECTION 015000

Page 901 of 1492 ends

CITY OF BEAUMONT PROTECTION OF EXISTING FACILITIES
BEAUMONT MESA L-S FORCE MAIN 015300-1

SECTION 015300 – PROTECTION OF EXISTING FACILITIES
PART 1 - GENERAL

1.1 GENERAL
A. The Contractor shall protect all existing utilities, piping and improvements not designated for removal and shall restore damaged or temporarily relocated utilities, piping and improvements to a condition equal to or better than they were prior to such dam age or temporary relocation. Where required, existing improvements shall be protected with shoring, sheeting, piles, or other necessary means.

B. The Contractor shall verify the exact locations and depths of all underground piping and utilities shown and not shown and shall make exploratory excavations of all piping and utilities that may interfere with the Work. It shall be the Contractor's responsibility to ascertain the actual location of all existing utilities, piping and other improvements that will be encountered in its construction operations and to see that such utilities or other improvements are adequately protected from damage due to such operations.

C. The Contractor shall notify the Owner’s representative of any change of condition or extra work as soon as it is discovered, including any damage to existing facilities, pipelines and improvements not designated for removal. The Contractor shall also notify the Owner’s representative of any plans to relocate existing piping or facilities to accommodate new construction.

D. Maintaining in Service: All pipelines, electrical, power, telephone, communication cables, gas and water mains shall remain continuously in service during all the operations under the Contract, unless other arrangements satisfactory to the Engineer are made with the Owner. Where the proper completion of the Work requires the temporary or permanent removal and/or relocation of an existing utility or other improvement the Contractor, after necessary scheduling and approval, shall remove and, without unnecessary delay, temporarily replace or relocate such utility or improvement in a manner satisfactory to the Engineer and the owner of the facility. In all cases of such temporary removal or relocation, the Wo rk shall be accomplished by the Contractor in a manner that will restore or replace the utility or improvement to a new condition meeting the specification requirements.

E. Buried pipelines, utilities, conduits, duct banks, or other improvements that must remain in service and are exposed due to excavation or construction activities shall be protected and supported as required. Segments of pipelines or duct that is suspended over excavated areas shall be temporarily supported until they can be properly backfilled. All temporary support strategies shall be reviewed and approved by Owner and Engineer.

F. All repairs to a damaged utility or improvement are subject to inspection and approval by an authorized representative of the improvement owner before being concealed by backfill or other work.

1.2 RIGHTS-OF-WAY

Page 902 of 1492 ends

CITY OF BEAUMONT PROTECTION OF EXISTING FACILITIES
BEAUMONT MESA L-S FORCE MAIN 015300-2

A. The Contractor shall not do any work or enter upon the rights -of-way of any oil, gas, sewer or water pipeline; any telephone or electric transmission line; any fence; or any other structure, until notified by the Engineer that the Owner has secured authority to do so. After authority has been obtained, the Contractor shall give the governing utility proper advanced notice of its intention to begin work.

1.3 RESTORATION OF PAVEMENT AND SIDEWALKS

A. All paved areas and sidewalks not designated for replacement, cut or damaged during construction shall be replaced with similar materials and of equal thickness to match the existing adjacent undisturbed areas unless otherwise noted. All sidewalks and pavements which are subject to partial removal shall be neatly saw-cut in straight lines. All restoration shall be at the Contractor’s expense.

1.4 UNDERGROUND UTILITIES

A. All care shall be exercised to protect existing underground utilities during construction activity.

The contractor shall protect pipelines (existing and new) from heavy vehicle loads and ensure that cranes or other heavy outrigging equipment is not parked or stored directly above these utilities without added protection.

B. If the Contractor damages existing utilities, piping or improvements that are not shown or the location of which was not made known to the Contractor prior to excavation and the damage was not due to failure of the Contractor to exercise reasonable care th e Contractor shall immediately notify the Engineer. If directed by the Engineer, repairs shall be made by the Contractor under the provisions for changes and extra work contained in the Contract Documents.

1.5 NOTIFICATION BY THE CONTRACTOR:

A. Prior to any excavation in the vicinity of any existing underground facilities, including water, sewer, storm drain, gas, petroleum products, or other pipelines; all buried electric power, communications or telecommunication cables; all traffic signal and street lighting facilities; and all roadway and state highway rights-of-way, the Contractor shall notify the respective authorities representing the owners or agencies responsible for such facilities not less than three (3) working days prior to excavation so that a representative can be present during such work if they are required to do so.

END OF SECTION 015300

Page 903 of 1492 ends

CITY OF BEAUMONT PROJECT ENVIRONMENTAL CONTROLS
BEAUMONT MESA L-S FORCE MAIN 015600-1

SECTION 015600 – PROJECT ENVIRONMENTAL CONTROLS
PART 1 - GENERAL

1.1 SUMMARY
A. The following sections include mitigation measures to be integrated into the project to reduce the potentially environmental impacts resulting from the construction activities. The Contractor shall implement mitigation measures identified below during the construction process, as well as any other measures required in these documents, on the design drawings, and as required by other local, state, and federal agencies.

1.2 WATER QUALITY
A. NPDES Construction Activity Stormwater Permit: Contractor shall comply with the provisions of the NPDES Construction Activity Stormwater permit, including preparation of Notice of Intent to comply with the provisions of this General Permit and preparation of a Storm Water Pollution Prevention Plan (SWPPP). The SWPPP will identify implementation measures necessary to mitigate potential water quality degradation as a result of construction-related runoff. These measures will include BMPs and other standard pollution prevention actions, such as erosion and sediment control measures, proper control of non-stormwater discharges, and hazardous spill prevention and response. The SWPPP will also include requirements for BMP inspections, monitoring, and maintenance.

B. The following items are examples of BMPs that would be implemented during construction to avoid causing water quality degradation:

1. Erosion control BMPs, such as use of mulches or hydroseeding to prevent detachment of soil, following guidance presented in the California BMP Handbooks – Construction (CASQA 2003). A detailed site map will be included in the SWPPP outlining specific areas where soil disturbance may occur, and drainage patterns associated with excavation and grading activities. In addition, the SWPPP will provide plans and details for the BMPs to be implemented prior, during, and after construction to prevent erosion of exposed soils and to treat sediments before they are transported offsite.

2. Sediment control BMPs such as silt fencing or detention basins that trap soil particles.

3. Construction staging areas designed so that stormwater runoff during construction will be collected and treated in a detention basin or other appropriate structure.

4. Management of hazardous materials and wastes to prevent spills.

5. Groundwater treatment BMPs such that localized trench dewatering does not impact surface water quality.

6. Vehicle and equipment fueling BMPs such that these activities occur only in designated staging areas with appropriate spill controls.

7. Maintenance checks of equipment and vehicles to prevent spills or leaks of liquids of any kind.

Page 904 of 1492 ends

CITY OF BEAUMONT PROJECT ENVIRONMENTAL CONTROLS
BEAUMONT MESA L-S FORCE MAIN 015600-2

1.3 AIR QUALITY
A. Construction Fugitive Dust Control Plan: Contractor shall prepare, submit for review and approval, and implement a dust control plan that conforms to the local requirements. The dust control plan shall include the following dust control procedures, or others as required the local authority:

1. Water all active construction areas at least twice daily, taking into consideration temperature and wind conditions.

2. Cover all trucks hauling soil, sand, and other loose materials or require trucks to maintain at least two feet of freeboard.

3. Pave, apply water three times daily, or apply (non-toxic) soil stabilizers on unpaved access roads, parking areas and staging areas at construction sites.

4. Sweep daily (with water sweepers) all paved access roads, parking areas and staging areas at construction sites.

5. Sweep streets daily (with water sweepers) if visible soil material is carried onto adjacent public streets.

6. Hydroseed or apply (non-toxic) soil stabilizers to inactive construction areas (previously graded areas inactive for ten days or more).

7. Enclose, cover, water twice daily or apply (non-toxic) soil binders to exposed stockpiles (dirt, sand, etc.)

8. Limit traffic speeds on unpaved roads to 5 mph.

9. Install sandbags or other erosion control measures to prevent silt runoff to public roadways, consistent with Mitigation Measures for Erosion Control.

10. Replant vegetation in disturbed areas as quickly as possible.

11. Contractor may use onsite treated effluent for dust abatement. Coordinate access and allowable volumes with Owner.

B. Construction Exhaust Emissions Control Plan: Contractor shall implement an exhaust emissions control plan that shall include the following controls and practices:

1. On road vehicles with a gross vehicular weight rating of 10,000 pounds or greater shall not idle for longer than five minutes at any location as required by Section 2485 of Title 13, Division 3, Chapter 10, Article 1 of the California Code of Regulations. This restriction does not apply when vehicles remain motionless during traffic or when vehicles are queuing.

2. Off road equipment engines shall not idle for longer than five minutes per Section 2449(d)(3) of Title 13, Division 3, Chapter 9, Article 4.8 of the California Code of Regulations. All vehicle operators shall receive a written idling policy to inform them of idling restrictions. The policy shall list exceptions to this rule that include the following: idling when queuing; idling to verify that the vehicle is in safe operating condition; idling for testing, servicing, repairing or diagnostic purposes; idling necessary to accomplish work for which the vehicle was designed (such as operating a crane); idling required to bring the machine to operating temperature as specified by the manufacturer; and idling necessary to ensure safe operation of the vehicle.

3. Off road engines greater than 50 horsepower shall, at a minimum, meet Tier 2 emissions standards. When available, higher Tier engines shall be utilized.

Page 905 of 1492 ends

CITY OF BEAUMONT PROJECT ENVIRONMENTAL CONTROLS
BEAUMONT MESA L-S FORCE MAIN 015600-3

1.4 NOISE
A. Contractor shall develop, submit for review and approval, and implement a Construction Noise Reduction Plan that requires, at a minimum, the following:

1. The contractor shall locate all stationary noise-generating equipment, including hammer bore and drill rigs, as far as possible from nearby noise-sensitive receptors. Stationary noise sources located within 500 feet of noise-sensitive receptors shall be equipped with noise reducing engine housings, and the line of sight between such sources and nearby sensitive receptors shall be blocked by portable acoustic barriers.

2. The contractor shall assure that construction equipment with internal combustion engines have sound control devices at least as effective as those provided by the original equipment manufacturer. No equipment shall be permitted to have an un-muffled exhaust.

3. All construction activities within unincorporated areas shall be limited to between the hours depending upon the jurisdiction.

4. Construction equipment including compressors, generators, and mobile equipment shall be fitted with properly working mufflers.

5. Residences and other sensitive receptors within 200 feet of a construction area shall be notified of the construction schedule in writing, at least two weeks prior to the commencement of construction activities. This notice shall indicate the allowable hours of construction activities as specified by the applicable local jurisdiction or as defined by this mitigation measure. The Owner shall designate a noise disturbance coordinator who would be responsible for responding to complaints regarding construction noise . The coordinator shall determine the cause of the complaint and ensure that reasonable measures are implemented to correct the problem. A contact number for the noise disturbance coordinator shall be conspicuously placed on construction site fences and entrances by the contractor and included in the construction schedule notification sent to nearby residences and sensitive receptors.

1.5 HAZARDS AND HAZARDOUS MATERIALS
A. In the event that evidence of potential soil contamination such as soil discoloration, noxious odors, debris, or buried storage containers, is encountered during construction, the contractor will have a contingency plan for sampling and analysis of potentially hazardous substances, including use of a photoionization detector. The required handling, storage, and disposal methods shall depend on the types and concentrations of chemicals identified in the soil. Any site investigations or remediation shall comply with applicable laws and will coordinate with the appropriate regulatory agencies.

B. If unknown USTs are discovered during construction, the UST, associated piping, and impacted soil shall be removed by a licensed and experienced UST removal contractor. The UST and contaminated soil shall be removed in compliance with applicable county and state requirements governing UST removal.

C. Contractor shall prepare, submit for review and approval, and implement a project -specific Health and Safety Plan that would apply to excavation activities. The plan shall establish policies and procedures to protect workers and the public from potential hazards posed by hazardous materials. The plan shall be prepared according to federal and California OSHA regulations and submitted to the appropriate agency with jurisdiction prior to beginning site

Page 906 of 1492 ends

CITY OF BEAUMONT PROJECT ENVIRONMENTAL CONTROLS
BEAUMONT MESA L-S FORCE MAIN 015600-4

activities. The health and safety plan shall also be submitted to the Owner for review and approval.

D. Consistent with the SWPPP requirements, the construction contractor shall be required to implement BMPs for handling hazardous materials onsite. The use of construction BMPs will minimize any adverse effects on groundwater and soils, and will include, but not limited to, the following:

1. Follow manufacturers’ recommendations and regulatory requirements for use, storage, and disposal of chemical products and hazardous materials used in construction;

2. Spill control and countermeasures, including employee spill prevention/response training;

3. Avoid overtopping construction equipment fuel gas tanks;

4. During routine maintenance of construction equipment, properly contain and remove grease and oils; and

5. Properly dispose of discarded containers of fuels and other chemicals.

E. The contractor shall follow the provisions of California Code of Regulations, Title 8, Sections 5163 through 5167 for General Industry Safety Orders to protect the project area from being contaminated by the accidental release of any hazardous materials and/or wastes. The local Certified Unified Program Agency (CUPA) will be contacted for any site-specific requirements regarding hazardous materials or hazardous waste containment or handling.

F. Oil and other solvents used during maintenance of construction equipment shall be recycled or disposed of in accordance with applicable regulatory requirements. All hazardous materials shall be transported handled and disposed of in accordance with applicable regulatory requirements.

G. In the event of an accidental release of hazardous materials during construction, containment and clean up shall occur in accordance with applicable regulatory requirements.

H. Contractor shall prepare, submit for review and approval, and implement a Fire Safety Plan for each of the service areas associated with the project. The Fire Safety Plan(s) will describe various potential scenarios and action plans in the event of a fire.

I. During project construction, all staging areas, welding areas, or areas slated for development using spark-producing equipment will be cleared of dried vegetation or other material that could ignite. Any construction equipment that includes a spark arrestor shall be equipped with a spark arrestor in good working order. All vehicles and crews working at the project site(s) will have access to functional fire extinguishers at all times. In addition, construction crews will be required to have a spotter during welding activities to look out for potentially dangerous situations, including accidental sparks.

1.6 CULTURAL RESOURCES
A. Inadvertent Discoveries: If discovery is made of items of historical or archaeological interest, the contractor shall immediately cease all work activities in the area (within approximately 100 feet) of discovery. Prehistoric archaeological materials might include obsidian and chert flaked- stone tools (e.g., projectile points, knives, scrapers) or toolmaking debris; culturally darkened soil (“midden”) containing heat-affected rocks, artifacts, or shellfish remains; and stone milling equipment (e.g., mortars, pestles, handstones, or milling slabs); and battered stone tools, such as

Page 907 of 1492 ends

CITY OF BEAUMONT PROJECT ENVIRONMENTAL CONTROLS
BEAUMONT MESA L-S FORCE MAIN 015600-5

hammerstones and pitted stones. Historic-period materials might include stone, concrete, or adobe footings and walls; filled wells or privies; and deposits of metal, glass, and/or ceramic refuse. After cessation of excavation the contractor shall immediately contact the NBWRA and the Owner. The contractor shall not resume work until authorization is received from the Owner.

1. In the event of unanticipated discovery of archaeological indicators during construction, the Owner shall retain the services of a qualified professional archaeologist to evaluate the significance of the items prior to resuming any activities that could impact the site.

2. In the case of an unanticipated archaeological discovery, if it is determined that the find is unique under the National Historic Preservation Act (NHPA) and/or potentially eligible for listing in the National Register, and the site cannot be avoided, the Owner shall provide a research design and excavation plan, prepared by an archaeologist, outlining recovery of the resource, analysis, and reporting of the find. The research design and excavation plan shall be submitted to NBWRA and the Owner and approved by the Owner prior to construction being resumed.

B. Discovery of Human Remains: If potential human remains are encountered, the Contractor shall halt work in the vicinity of the find and contact the county coroner in accordance with Public Resources Code Section 5097.98 and Health and Safety Code Section 7050.5. If the coroner determines the remains are Native American, the coroner shall contact the Native American Heritage Commission (NAHC). As provided in Public Resources Code Section 5097.98, the NAHC shall identify the person or persons believed to be most likely descended from the deceased Native American. The most likely descendent makes recommendations for means of treating or disposing of, with appropriate dignity, the human remains and any associated grave goods as provided in Public Resources Code Section 5097.98.

1.7 EXPLOSIVES AND BLASTING:

A. The use or storage of explosives on the Work or site will not be permitted.

1.8 SANITATION
A. The Contractor shall provide approved fixed or portable chemical toilets wherever needed for its employees. The Contractor shall establish regular intervals of collection of all sanitary and organic wastes. All wastes and refuse from sanitary facilities provided by the Contractor or organic material wastes from any other source related to the Contractor's operations shall be disposed of in a manner satisfactory to the Engineer and in accordance with all laws and regulations pertaining thereto. The Owner's toilet facilities shall not be used by the Contractor.

END OF SECTION 015600

Page 908 of 1492 ends

CITY OF BEAUMONT PROJECT ENVIRONMENTAL CONTROLS
BEAUMONT MESA L-S FORCE MAIN 015600-6

THIS PAGE INTENTIONALLY LEFT BLANK

Page 909 of 1492 ends

CITY OF BEAUMONT PRODUCT REQUIREMENTS
BEAUMONT MESA L-S FORCE MAIN 016100-1

SECTION 016100 - PRODUCT REQUIREMENTS
PART 1 - GENERAL

1.1 SUMMARY
A. Section includes administrative and procedural requirements for selection of products for use in Project; product delivery, storage, and handling; manufacturers' standard warranties on products; special warranties; and comparable products.

B. Related Requirements:

1. General Conditions

1.2 DEFINITIONS
A. Products: Items obtained for incorporating into the Work, whether purchased for Proje ct or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent.

1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's published product literature that is current as of date of the Contract Documents.

2. New Products: Items that have not previously been incorporated into another project or facility. Products salvaged or recycled from other projects are not considered new products.

3. Comparable Product: Product that is demonstrated and approved through submittal process to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.

B. Basis-of-Design Product Specification: A specification in which a specific manufacturer's product is named and accompanied by the words "basis-of-design product," including make or model number, manufacturer name, or other designation, to establish the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics for purposes of evaluating comparable products of additional manufacturers named in the specification.

1.3 ACTION SUBMITTALS
A. Comparable Product Requests: Submit request for consideration of each comparable product.

Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

Page 910 of 1492 ends

CITY OF BEAUMONT PRODUCT REQUIREMENTS
BEAUMONT MESA L-S FORCE MAIN 016100-2

1. Engineer's Action: If necessary, Engineer will request additional information or documentation for evaluation within one week of receipt of a comparable product request. Engineer will notify Contractor of approval or rejection of proposed comparable product request within fifteen (15) days of receipt of request, or seven (7) days of receipt of additional information or documentation, whichever is later. a. Form of Approval: As specified in Section 013300 "Contractor Submittals." b. Use product specified if Engineer does not issue a decision on use of a comparable product request within time allocated.

B. Basis-of-Design Product Specification Submittal: Comply with requirements in Section 013300 "Contractor Submittals." Show compliance with requirements.

1.4 QUALITY ASSURANCE
A. Compatibility of Options: If Contractor is given option of selecting between two or more products for use on Project, select product compatible with products previously selected, even if previously selected products were also options.

B. To the greatest extent possible for each unit of work, the Contractor shall provide products, materials or equipment from a single source.

1.5 PRODUCT DELIVERY, STORAGE, AND HANDLING
A. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft and vandalism. Comply with manufacturer's written instructions.

B. Delivery and Handling:

1. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces.

2. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.

3. Deliver products to Project site in an undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.

4. Inspect products on delivery to determine compliance with the Contract Documents and to determine that products are undamaged and properly protected.

C. Storage:

1. Store products to allow for inspection and measurement of quantity or counting of units.

2. Store materials in a manner that will not endanger Project structure.

3. Store products that are subject to damage by the elements, under cover in a weathertight enclosure above ground, with ventilation adequate to prevent condensation.

4. Protect foam plastic from exposure to sunlight, except to extent necessary for period of installation and concealment.

Page 911 of 1492 ends

CITY OF BEAUMONT PRODUCT REQUIREMENTS
BEAUMONT MESA L-S FORCE MAIN 016100-3

5. Comply with product manufacturer's written instructions for temperature, humidity, ventilation, and weather-protection requirements for storage.

6. Protect stored products from damage and liquids from freezing.

D. Fabricated structural components shall be stored on supports above ground and in a manner to prevent accumulation of water and warping. Products subject to deterioration from atmospheric conditions shall be covered in a manner that will provide adequate ventilation to avoid condensation.

E. Products, materials and equipment not stored in a manner that will insure the maintaining of a new condition will be rejected by the Engineer. Such rejected products, materials and equipment shall be immediately removed from the Work site.

1.6 PRODUCT WARRANTIES
A. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents.

1. Manufacturer's Warranty: Written warranty furnished by individual manufacturer for a particular product and specifically endorsed by manufacturer to Owner.

2. Special Warranty: Written warranty required by the Contract Documents to provide specific rights for Owner.

B. Special Warranties: Prepare a written document that contains appropriate terms and identification, ready for execution.

1. Manufacturer's Standard Form: Modified to include Project-specific information and properly executed.

2. Specified Form: When specified forms are included with the Specifications, prepare a written document using indicated form properly executed.

3. Refer to other Sections for specific content requirements and particular requirements for submitting special warranties.

C. Submittal Time: Comply with requirements in Section 017700 "Closeout Procedures." PART 2 - PRODUCTS

2.1 PRODUCT SELECTION PROCEDURES
A. General Product Requirements: Provide products that comply with the Contract Documents, are undamaged and, unless otherwise indicated, are new at time of installation.

1. Provide products complete with accessories, trim, finish, fasteners, and other items needed for a complete installation and indicated use and effect.

Page 912 of 1492 ends

CITY OF BEAUMONT PRODUCT REQUIREMENTS
BEAUMONT MESA L-S FORCE MAIN 016100-4

2. Standard Products: If available, and unless custom products or nonstandard options are specified, provide standard products of types that have been produced and used successfully in similar situations on other projects.

3. Owner reserves the right to limit selection to products with warranties not in conflict with requirements of the Contract Documents.

4. Descriptive, performance, and reference standard requirements in the Specifications establish salient characteristics of products.

B. Product Selection Procedures:

1. Where Specifications name a product or manufacturer as the “Basis-of-Design”, provide product(s) as listed or by the manufacturer listed. Where Specifications include a list of available products or manufacturers, followed by the phrase “or equal,” provide a product by one of the manufacturers listed, or a product by an unnamed manufacturer subject to requirements of General Conditions.

PART 3 - EXECUTION (Not Used)
END OF SECTION 016100

Page 913 of 1492 ends

CITY OF BEAUMONT CLOSEOUT PROCEDURES
BEAUMONT MESA L-S FORCE MAIN 017700-1

SECTION 017700 - CLOSEOUT PROCEDURES
PART 1 - GENERAL

1.1 SUMMARY
A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:

1. Substantial Completion procedures.

2. Final completion procedures.

3. Warranties.

4. Final cleaning.

5. Repair of the Work.

B. Related Requirements:

1. Section 017500 “Commissioning” for commissioning requirements.

2. Section 017823 "Operation and Maintenance Data" for operation and maintenance manual requirements.

3. Section 017839 "Project Record Documents" for submitting record Drawings, record Specifications, and record Product Data.

1.2 ACTION SUBMITTALS
A. Product Data: For cleaning agents (submitted by the Contractor) B. Contractor's List of Incomplete Items: Initial submittal by the Contractor at Substantial Completion.

C. Certified List of Incomplete Items: Final submittal by the Contractor at Final Completion.

1.3 CLOSEOUT SUBMITTALS
A. Certificates of Release: From authorities having jurisdiction.

B. Certificate of Insurance: For continuing coverage.

1.4 SUBSTANTIAL COMPLETION PROCEDURES
A. Contractor's List of Incomplete Items: Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.

Page 914 of 1492 ends

CITY OF BEAUMONT CLOSEOUT PROCEDURES
BEAUMONT MESA L-S FORCE MAIN 017700-2

1. Organize list of spaces in sequential order.

2. Organize items applying to each space by major element, including categories for ceiling, individual walls, floors, equipment, and building systems.

3. Include comments from the Construction Manager, Owner and Engineer.

4. Submit list of incomplete items in the following format:
a. MS Excel electronic file. Engineer will return annotated copy.

B. Submittals Prior to Substantial Completion: Complete the following a minimum of 14 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request.

1. Certificates of Release: Obtain and submit releases from authorities having jurisdiction permitting Owner unrestricted use of the Work and access to services and utilities.

Include occupancy permits, operating certificates, and similar releases.

2. Submit closeout submittals specified in other Division 01 Sections, including project record documents, operation and maintenance manuals, final completion construction photographic documentation, damage or settlement surveys, property surveys, and similar final record information.

3. Submit closeout submittals specified in individual Sections, including specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents.

4. Submit maintenance material submittals specified in individual Sections, including tools, spare parts, extra materials, and similar items, and deliver to location designated by Engineer. Label with manufacturer's name and model number where applicable. a. Schedule of Maintenance Material Items: Prepare and submit schedule of maintenance material submittal items, including name and quantity of each item and name and number of related Specification Section. Obtain Engineer’s signature for receipt of submittals.

5. Submit test/adjust/balance records.

6. Submit changeover information related to Owner's occupancy, use, operation, and maintenance.

C. Procedures Prior to Substantial Completion: Complete the following a minimum of 14 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request.

1. Make final changeover of permanent locks and deliver keys to Owner.

2. Complete startup and testing of systems and equipment.

3. Perform preventive maintenance on equipment used prior to Substantial Completion.

4. Instruct Owner's personnel in operation, adjustment, and maintenance of products, equipment, and systems.

5. Terminate and remove temporary facilities from Project site, along with mockups, construction tools, and similar elements.

6. Complete final cleaning requirements, including touchup painting.

7. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.

Page 915 of 1492 ends

CITY OF BEAUMONT CLOSEOUT PROCEDURES
BEAUMONT MESA L-S FORCE MAIN 017700-3

D. Inspection: Submit a written request for inspection to determine Substantial Completion a minimum of 14 days prior to date the work will be completed and ready for final inspection and tests. On receipt of request, Engineer and Construction Manager will either proceed with inspection or notify Contractor of unfulfilled requirements. Engineer will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by Engineer, that must be completed or corrected before certificate will be issued.

1. Re-inspection: Request re-inspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for final completion.

1.5 FINAL COMPLETION PROCEDURES
A. Preliminary Procedures: Before requesting final inspection for determining final completion, complete the following:

1. Certified List of Incomplete Items: Submit certified copy of Engineer's Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by Engineer. Certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.

2. Instruct Owner's personnel in operation, adjustment, and maintenance of products, equipment, and systems.

B. Inspection: Submit a written request for final inspection to determine acceptance. On receipt of request, Engineer will either proceed with inspection or notify Contractor of unfulfilled requirements. Engineer will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Re-inspection: Request re-inspection when the Work identified in previous inspections as incomplete is completed or corrected.

1.6 SUBMITTAL OF PROJECT WARRANTIES
A. Time of Submittal: Submit written warranties on request of Engineer for designated portions of the Work where commencement of warranties other than date of Substantial Completion is indicated, or when delay in submittal of warranties might limit Owner's rights under warranty.

B. Organize warranty documents into an orderly sequence based on the table of contents of the Project Manual.

1. Bind warranties and bonds in heavy-duty, three-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch paper.

2. Provide heavy paper dividers with plastic-covered tabs for each separate warranty. Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.

Page 916 of 1492 ends

CITY OF BEAUMONT CLOSEOUT PROCEDURES
BEAUMONT MESA L-S FORCE MAIN 017700-4

3. Identify each binder on the front and spine with the typed or printed title "WARRANTIES," Project name, and name of Contractor.

4. Warranty Electronic File: Scan warranties and bonds and assemble complete warranty and bond submittal package into a single indexed electronic PDF file with links enabling navigation to each item. Provide bookmarked table of contents at beginning of document.

C. Provide additional copies of each warranty to include in operation and maintenance manuals.

D. Operating manuals, technical manuals and instructions. The Contractor's attention is directed to the condition that one percent (1%) of the contract price will be deducted from any m onies due the Contractor as progress payments if at the seventy-five percent (75%) construction completion point the approved technical manuals have not been submitted in accordance with Section 013300 entitled, "Contractor Submittals". The aforementioned amount will be retained by the Owner as the agreed estimated value of the approved technical manuals. Any such retention of money for failure to submit the approved technical manuals on or before the seventy-five percent (75%) construction completion point shall be in addition to the retention of any payments due to the Contractor as specified in Article 4 of the Contract.

E. Releases from all parties who are entitled to claims against the subject project, property or improvement pursuant to the provisions of law.

PART 2 - PRODUCTS

2.1 MATERIALS
A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

1. Use cleaning products that comply with Green Seal's GS-37, or if GS-37 is not applicable, use products that comply with the California Code of Regulations maximum allowable VOC levels.

PART 3 - EXECUTION

3.1 FINAL CLEANING
A. General: Perform final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program. Comply with manufacturer's written instructions.

1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a designated portion of Project:

Page 917 of 1492 ends

CITY OF BEAUMONT CLOSEOUT PROCEDURES
BEAUMONT MESA L-S FORCE MAIN 017700-5

a. Clean Project site in areas disturbed by construction activities, including removal and disposal of rubbish, waste material, litter, and other foreign substances. b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.
c. Rake grounds that are neither planted nor paved to a smooth, even -textured surface.
d. Remove tools, construction equipment, machinery, and surplus material from Project site.
e. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces.
f. Remove labels that are not permanent.

3.2 REPAIR OF THE WORK
A. Complete repair and restoration operations before requesting inspection for determination of Substantial Completion.

B. Repair or remove and replace defective construction. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment. Where damaged or worn items cannot be repaired or restored, provide replacements. Remove and replace operating components that cannot be repaired.

Restore damaged construction and permanent facilities used during construction to specified condition.

1. Remove and replace chipped, scratched, and broken glass, reflective surfaces, and other damaged transparent materials.

2. Touch up and otherwise repair and restore marred or exposed finishes and surfaces.

Replace finishes and surfaces that that already show evidence of repair or restoration. a. Do not paint over "UL" and other required labels and identification, including mechanical and electrical nameplates. Remove paint applied to required labels and identification.

3. Replace parts subject to operating conditions during construction that may impede operation or reduce longevity.

4. Replace burned-out bulbs, bulbs noticeably dimmed by hours of use, and defective and noisy starters in fluorescent and mercury vapor fixtures to comply with requirements for new fixtures.

END OF SECTION 017700

Page 918 of 1492 ends

CITY OF BEAUMONT OPERATION & MAINTENANCE DATA
BEAUMONT MESA L-S FORCE MAIN 017823 - 1
SECTION 017823 - OPERATION AND MAINTENANCE DATA
PART 1 - GENERAL

1.1 SUMMARY
A. Section includes administrative and procedural requirements for preparing operation and maintenance manuals, including the following:

1. Operation and maintenance documentation directory.

2. Emergency manuals.

3. Operation manuals for systems, subsystems, and equipment.

4. Product maintenance manuals.

5. Systems and equipment maintenance manuals.

1.2 CLOSEOUT SUBMITTALS
A. Manual Content: Operations and maintenance manual content is specified in individual Specification Sections to be reviewed at the time of Section submittals. Submit reviewed manual content formatted and organized as required by this Section.

1. Engineer will comment on whether content of operations and maintenance submittals are acceptable.

2. Where applicable, clarify and update reviewed manual content to correspond to revisions and field conditions.

B. Format: Submit operations and maintenance manuals in the following format:

1. PDF electronic file. Assemble each manual into a composite electronically indexed file.

Submit on digital media acceptable to Engineer.
a. Name each indexed document file in composite electronic index with applicable item name. Include a complete electronically linked operation and maintenance directory.
b. Enable inserted reviewer comments on draft submittals.

2. Four (4) paper copies. Include a complete operation and maintenance directory. Enclose title pages and directories in clear plastic sleeves. One set will be provided to the Engineer and three sets to the Owner.

C. Manual Submittal: Submit each manual in final form prior to requesting inspection for Substantial Completion and at least 15 days before commencing demonstration and training.

Engineer will return copy with comments.

1. Correct or revise each manual to comply with Engineer's comments. Submit copies of each corrected manual within 15 days of receipt of Engineer's comments and prior to commencing demonstration and training.

Page 919 of 1492 ends

CITY OF BEAUMONT OPERATION & MAINTENANCE DATA
BEAUMONT MESA L-S FORCE MAIN 017823 - 2
PART 2 - PRODUCTS

2.1 REQUIREMENTS FOR EMERGENCY, OPERATION, AND MAINTENANCE MANUALS A. Directory: Prepare a single, comprehensive directory of emergency, operation, and maintenance data and materials, listing items and their location to facilitate ready access to desired information.

B. Organization: Unless otherwise indicated, organize each manual into a separate section for each system and subsystem, and a separate section for each piece of equipment not part of a system.

Each manual shall contain the following materials, in the order listed:

1. Title page.

2. Table of contents.

3. Manual contents.

C. Title Page: Include the following information:

1. Subject matter included in manual.

2. Name and address of Project.

3. Name and address of Owner.

4. Date of submittal.

5. Name and contact information for Contractor.

6. Name and contact information for Construction Manager.

7. Name and contact information for Engineer.

8. Name and contact information for Commissioning Authority.

9. Names and contact information for major consultants to the Engineer that designed the systems contained in the manuals.

10. Cross-reference to related systems in other operation and maintenance manuals.

D. Table of Contents: List each product included in manual, identified by product name, indexed to the content of the volume, and cross-referenced to Specification Section number in Project Manual.

E. Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system, subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and components of one system into a single binder.

F. Manuals, Electronic Files: Submit manuals in the form of a multiple file composite electronic PDF file for each manual type required.

1. Electronic Files: Use electronic files prepared by manufacturer where available. Where scanning of paper documents is required, configure scanned file for minimum readable file size.

2. File Names and Bookmarks: Enable bookmarking of individual documents based on file names. Name document files to correspond to system, subsystem, and equipment names used in manual directory and table of contents. Group documents for each system and subsystem into individual composite bookmarked files, then create composite manual, so that resulting bookmarks reflect the system, subsystem, and equipment names in a readily

Page 920 of 1492 ends

CITY OF BEAUMONT OPERATION & MAINTENANCE DATA
BEAUMONT MESA L-S FORCE MAIN 017823 - 3
navigated file tree. Configure electronic manual to display bookmark panel on opening file.

G. Manuals, Paper Copy: Submit manuals in the form of hard copy, bound and labeled volumes.

1. Binders: Heavy-duty, three-ring, vinyl-covered, loose-leaf binders, in thickness necessary to accommodate contents, sized to hold 8-1/2-by-11-inch paper; with clear plastic sleeve on spine to hold label describing contents and with pockets inside covers to hold folded oversize sheets.
a. Identify each binder on front and spine, with printed title "OPERATION AND MAINTENANCE MANUAL," Project title or name, subject matter of contents.

Indicate volume number for multiple-volume sets.

2. Dividers: Heavy-paper dividers with plastic-covered tabs for each section of the manual.

Mark each tab to indicate contents. Include typed list of products and major components of equipment included in the section on each divider, cross-referenced to Specification Section number and title of Project Manual.

3. Protective Plastic Sleeves: Transparent plastic sleeves designed to enclose diagnostic software storage media for computerized electronic equipment.

4. Drawings: Attach reinforced, punched binder tabs on drawings and bind with text. a. If oversize drawings are necessary, fold drawings to same size as text pages and use as foldouts.
b. If drawings are too large to be used as foldouts, fold and place drawings in labeled envelopes and bind envelopes in rear of manual. At appropriate locations in manual, insert typewritten pages indicating drawing titles, descriptions of contents, and drawing locations.

2.2 OPERATION MANUALS
A. Content: In addition to requirements in this Section, include operation data required in individual Specification Sections and the following information:

1. System, subsystem, and equipment descriptions. Use designations for systems and equipment indicated on Contract Documents.

2. Performance and design criteria if Contractor is delegated design responsibility.

3. Operating standards.

4. Operating procedures.

5. Operating logs.

6. Wiring diagrams.

7. Control diagrams.

8. Piped system diagrams.

9. Precautions against improper use.

10. License requirements including inspection and renewal dates.

B. Descriptions: Include the following:

1. Product name and model number. Use designations for products indicated on Contract Documents.

Page 921 of 1492 ends

CITY OF BEAUMONT OPERATION & MAINTENANCE DATA
BEAUMONT MESA L-S FORCE MAIN 017823 - 4

2. Manufacturer's name.

3. Equipment identification with serial number of each component.

4. Equipment function.

5. Operating characteristics.

6. Limiting conditions.

7. Performance curves.

8. Engineering data and tests.

9. Complete nomenclature and number of replacement parts.

C. Operating Procedures: Include the following, as applicable:

1. Startup procedures.

2. Equipment or system break-in procedures.

3. Routine and normal operating instructions.

4. Regulation and control procedures.

5. Instructions on stopping.

6. Normal shutdown instructions.

7. Seasonal and weekend operating instructions.

8. Required sequences for electric or electronic systems.

9. Special operating instructions and procedures.

D. Systems and Equipment Controls: Describe the sequence of operation, and diagram controls as installed.

E. Piped Systems: Diagram piping as installed and identify color-coding where required for identification.

2.3 PRODUCT MAINTENANCE MANUALS
A. Content: Organize manual into a separate section for each product, material, and finish.

Include source information, product information, maintenance procedures, repair materials and sources, and warranties and bonds, as described below.

B. Source Information: List each product included in manual, identified by product name and arranged to match manual's table of contents. For each product, list name, address, and telephone number of Installer or supplier and maintenance service agent, and cross -reference Specification Section number and title in Project Manual.

C. Product Information: Include the following, as applicable:

1. Product name and model number.

2. Manufacturer's name.

3. Color, pattern, and texture.

4. Material and chemical composition.

5. Reordering information for specially manufactured products.

D. Maintenance Procedures: Include manufacturer's written recommendations and the following:

1. Inspection procedures.

2. Types of cleaning agents to be used and methods of cleaning.

Page 922 of 1492 ends

CITY OF BEAUMONT OPERATION & MAINTENANCE DATA
BEAUMONT MESA L-S FORCE MAIN 017823 - 5

3. List of cleaning agents and methods of cleaning detrimental to product.

4. Schedule for routine cleaning and maintenance.

5. Repair instructions.

E. Repair Materials and Sources: Include lists of materials and local sources of materials and related services.

F. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds.

2.4 SYSTEMS AND EQUIPMENT MAINTENANCE MANUALS
A. Content: For each system, subsystem, and piece of equipment not part of a system, include source information, manufacturers' maintenance documentation, maintenance procedures, maintenance and service schedules, spare parts list and source information, maintenance service contracts, and warranty and bond information, as described below.

B. Source Information: List each system, subsystem, and piece of equipment included in manual, identified by product name and arranged to match manual's table of contents. For each product, list name, address, and telephone number of Installer or supplier and maintenance service agent, and cross-reference Specification Section number and title in Project Manual.

C. Manufacturers' Maintenance Documentation: Manufacturers' maintenance documentation including the following information for each component part or piece of equipment:

1. Standard maintenance instructions and bulletins.

2. Drawings, diagrams, and instructions required for maintenance, including disassembly and component removal, replacement, and assembly.

3. Identification and nomenclature of parts and components.

4. List of items recommended to be stocked as spare parts.

D. Maintenance Procedures: Include the following information and items that detail essential maintenance procedures:

1. Test and inspection instructions.

2. Troubleshooting guide.

3. Precautions against improper maintenance.

4. Disassembly; component removal, repair, and replacement; and reassembly instructions.

5. Aligning, adjusting, and checking instructions.

6. Demonstration and training video recording, if available.

E. Maintenance and Service Schedules: Include service and lubrication requirements, list of required lubricants for equipment, and separate schedules for preventive and routine maintenance and service with standard time allotment.

F. Spare Parts List and Source Information: Include lists of replacement and repair parts, with parts identified and cross-referenced to manufacturers' maintenance documentation and local sources of maintenance materials and related services.

Page 923 of 1492 ends

CITY OF BEAUMONT OPERATION & MAINTENANCE DATA
BEAUMONT MESA L-S FORCE MAIN 017823 - 6
G. Maintenance Service Contracts: Include copies of maintenance agreements with name and telephone number of service agent.

H. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds.

PART 3 - EXECUTION

3.1 MANUAL PREPARATION
A. Emergency Manual: Assemble a complete set of emergency information indicating procedures for use by emergency personnel and by Owner's operating personnel for types of emergencies indicated.

B. Product Maintenance Manual: Assemble a complete set of maintenance data indicating care and maintenance of each product, material, and finish incorporated into the Work.

C. Operation and Maintenance Manuals: Assemble a complete set of operation and maintenance data indicating operation and maintenance of each system, subsystem, and piece of equipment not part of a system.

D. Manufacturers' Data: Where manuals contain manufacturers' standard printed data, include only sheets pertinent to product or component installed. Mark each sheet to identify each product or component incorporated into the Work. If data include more than one item in a tabular format, identify each item using appropriate references from the Contract Documents.

Identify data applicable to the Work and delete references to information not applicable.

E. Drawings: Prepare drawings supplementing manufacturers' printed data to illustrate the relationship of component parts of equipment and systems and to illustrate control sequence and flow diagrams. Coordinate these drawings with information contained in record Drawings to ensure correct illustration of completed installation.

1. Do not use original project record documents as part of operation and maintenance manuals.

F. Comply with Section 017700 "Closeout Procedures" for schedule for submitting operation and maintenance documentation.

END OF SECTION 017823

Page 924 of 1492 ends

CITY OF BEAUMONT PROJECT RECORD DOCUMENTS
BEAUMONT MESA L-S FORCE MAIN 017839 - 1
SECTION 017839 - PROJECT RECORD DOCUMENTS
PART 1 - GENERAL

1.1 SUMMARY
A. Section includes administrative and procedural requirements for project record documents, including the following:

1. Record Drawings.

2. Record Specifications.

3. Record Product Data.

B. Related Requirements:

1. Section 017823 "Operation and Maintenance Data" for operation and maintenance manual requirements.

1.2 CLOSEOUT SUBMITTALS
A. Record Drawings: Comply with the following:

1. Number of Copies: The Contractor shall submit one (1) set of marked-up record prints to the Engineer.

B. Record Specifications: The Contractor shall submit one paper copy of Project's Specifications, including addenda and contract modifications.

C. Record Product Data: Submit one paper copy of each submittal to the Engineer.

PART 2 - PRODUCTS

2.1 RECORD DRAWINGS
A. Record Prints: Maintain one set of marked-up paper copies of the Contract Drawings and Shop Drawings, incorporating new and revised Drawings as modifications are issued.

1. Preparation: Mark record prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to provide information for preparation of corresponding marked-up record prints. a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.
b. Record data as soon as possible after obtaining it.
c. Record and check the markup before enclosing concealed installations.

Page 925 of 1492 ends

CITY OF BEAUMONT PROJECT RECORD DOCUMENTS
BEAUMONT MESA L-S FORCE MAIN 017839 - 2

2. Mark the Contract Drawings and Shop Drawings completely and accurately. Use personnel proficient at recording graphic information in production of marked-up record prints.

3. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.

4. Note Construction Change Directive numbers, alternate numbers, Change Order numbers, and similar identification, where applicable.

B. Record Digital Data Files: Immediately before inspection for Certificate of Substantial Completion, review marked-up record prints with Engineer and Construction Manager. When authorized, prepare a full set of corrected digital data files of the Contract Drawings, as follows:

1. Format: Same digital data software program, version, and operating system as the original Contract Drawings.

2. Incorporate changes and additional information previously marked on record prints.

Delete, redraw, and add details and notations where applicable.

3. Refer instances of uncertainty to Engineer through Construction Manager for resolution.

4. Engineer will furnish Contractor one set of digital data files of the Contract Drawings for use in recording information.

C. Format: Identify and date each record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location.

1. Record Prints: Organize record prints and newly prepared record Drawings into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.

2. Identification: As follows:
a. Project name.
b. Date.
c. Designation "PROJECT RECORD DRAWINGS."
d. Name of Engineer and Construction Manager.
e. Name of Contractor.

2.2 RECORD SPECIFICATIONS
A. Preparation: Mark Specifications to indicate the actual product installation where installation varies from that indicated in Specifications, addenda, and contract modifications.

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Mark copy with the proprietary name and model number of products, materials, and equipment furnished, including substitutions and product options selected.

3. Record the name of manufacturer, supplier, Installer, and other information necessary to provide a record of selections made.

4. Note related Change Orders, record Product Data, and record Drawings where applicable.

B. Format: Submit record Specifications as paper copy.

Page 926 of 1492 ends

CITY OF BEAUMONT PROJECT RECORD DOCUMENTS
BEAUMONT MESA L-S FORCE MAIN 017839 - 3

2.3 RECORD PRODUCT DATA
A. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal.

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation.

3. Note related Change Orders, record Specifications, and record Drawings where applicable.

B. Format: Submit record Product Data as paper copy.

2.4 MISCELLANEOUS RECORD SUBMITTALS
A. Assemble miscellaneous records required by other Specification Sections for miscellaneous record keeping and submittal in connection with actual performance of the Work. Bind or file miscellaneous records and identify each, ready for continued use and reference.

B. Format: Submit miscellaneous record submittals as paper copy.

PART 3 - EXECUTION

3.1 RECORDING AND MAINTENANCE
A. Recording: Maintain one copy of each submittal during the construction period for project record document purposes. Post changes and revisions to project r ecord documents as they occur; do not wait until end of Project.

B. Maintenance of Record Documents and Samples: Store record documents and Samples in the field office apart from the Contract Documents used for construction. Do not use project record documents for construction purposes. Maintain record documents in good order and in a clean, dry, legible condition, protected from deterioration and loss. Provide access to project record documents for Engineer's and Construction Manager's reference during normal working hours.

END OF SECTION 017839

Page 927 of 1492 ends

CITY OF BEAUMONT PROJECT RECORD DOCUMENTS
BEAUMONT MESA L-S FORCE MAIN 017839 - 4

THIS PAGE INTENTIONALLY LEFT BLANK

Page 928 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-1

SECTION 099723 - EPOXY COATING FOR CONCRETE WASTEWATER

STRUCTURES

PART 1 - GENERAL

1.01 DESCRIPTION

This section covers all workmanship, materials and quality requirements for providing and applying a high-build epoxy coating for protecting concrete wastewater structures and manholes in order to eliminate infiltration and provide corrosion protection.

1.02 SCAQMD COMPLIANCE

All coatings shall be in compliance with all South Coast Air Quality Management District requirements including volatile organic compounds (VOC).

1.03 REFERENCES

A. GENERAL: The references indicated herein are a part of this section as specified and modified. In case of conflict between the requirements of this section and those of the listed documents, the most stringent of the requirements shall govern.

Unless otherwise specified, references to documents shall mean the documents in effect at the time of receipt of bid proposals. If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, whether or not the document has been superseded by a version with a later date, discontinued, or replaced.

Referenced publications found within this specification shall be the latest revision unless otherwise specified; and applicable parts of the referenced publications shall become a part of this specification as if fully included.

B. REFERENCE STANDARDS:

A. ASTM D638 - Tensile Properties of Plastics.

B. ASTM D790 - Flexural Properties of Unreinforced and Reinforced Plastics.

C. ASTM D695 - Compressive Properties of Rigid Plastics.

D. ASTM D4541 - Pull-off Strength of Coatings Using a Portable Adhesion Tester.

Page 929 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-2
E. ASTM D2584 - Volatile Matter Content.

F. ASTM D22409 - Durometer Hardness, Type D.

G. ASTM D543 - Resistance of Plastics to Chemical Reagents.

H. ASTM C109 - Compressive Strength Hydraulic Cement Mortars.

I. ASTM C396 - Compressive Strength of Cement Mortars.

J. ACI 506.2-77 - Specifications for Materials, Proportioning, and Application of shotcrete.

K. ASTM C579 - Compressive Strength of Chemically Setting Silicate and Silica Chemical Resistant Mortars.

L. ASTM - The published standards of the American Society for Testing and Materials, West Conshohocken, PA.

M. NACE - The published standards of National Association of Corrosion Engineers (NACE International), Houston, TX.

N. NACE - RP0892-92 – Standard Recommended Practice, "Lining Over Concrete in Immersion Service".

O. SSPC - The published standards of the Society of Protective Coatings, Pittsburgh, PA.

1.04 QUALITY ASSURANCE

A. GENERAL: Quality assurance procedures and practices shall be used to monitor all phases of surface preparation, application and inspection throughout the duration of the project. Procedures or practices not specifically defined herein may be used provided they meet recognized and acceptable professional standards and are approved by the Owner.

B. INSPECTION BY OWNER OR OWNER: All materials furnished and all work accomplished under the Contract shall be subject to inspection by the Owner. The Contractor shall be held strictly to the true intent of the Specifications in regard to quality of materials, workmanship, and diligent execution of the requirements of the Contract.

Except as otherwise provided herein, the cost of inspection will be paid by the Owner.

C. FIELD TESTS: The Owner will make, or have made, such tests as he deems necessary to assure the work is being accomplished in accordance with the requirements of the Contract. Unless otherwise specified in the Contract Requirements, the cost of such testing will be borne by the Owner. In the event such tests reveal non-compliance with the requirements of the Contact, the

Page 930 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-3
Contractor shall bear the cost of such corrective measures deemed necessary by the Owner, as well as the cost of subsequent retesting. It is understood and agreed the making of tests shall not constitute an acceptance of any portion of the work, nor relieve the contractor from compliance with the terms of the Contract.

D. OTHER QUALITY ASSURANCE REQUIREMENTS:

1. Do not use or retain contaminated, outdated, or diluted materials for resurfacing.

Do not use materials from previously opened containers.

2. Use only products of the approved Manufacturer. Use products of one manufacturer in any one resurfacing system with compatible materials. Provide same material product for touch-up as for original material.

3. If any requirements of this specification conflict with a referenced standard, the more stringent requirement shall apply.

4. Make available all locations and phases of the work for access by the Owner or other personnel designated by the Owner. The Contractor shall provide ventilation and egress to safely access the coating work areas for inspection.

5. Conduct work so that the resurfacing system is installed as specified herein.

Inspect work continually to ensure that the resurfacing system is installed as specified herein. The Contractor shall inspect the work to determine conformance with the specifications and referenced documents. The Contractor shall inform the Owner of the progress and the quality of the work through daily reports as specified below. Any nonconforming coating system work shall be corrected as specified herein or as recommended by the Manufacturer.

6. Summarize test data, work progress, areas covered, ambient conditions, quality control inspection test findings, and other information pertinent to the resurfacing system installation in daily reports to be submitted to the Owner or the Owner’s Representative.

7. The methods of construction shall be in accordance with all requirements of this specification.

8. Employ only trades people who have at least three years of experience performing resurfacing work of similar size and complexity as the work specified in this Section. Submittals to verify these qualifications are to be made within thirty (30) days of the Notice-to-Proceed and are subject to approval by the Owner.

9. The Specified System is the minimum standard of quality for this project.

Submissions of alternative manufacturers shall be in accordance with provisions stated in the Contract Requirements.

1.05 PRE-COATING CONFERENCE

A. A Pre-Coating Conference shall be scheduled prior to start of project. The Owner, Contractor, Coating Manufacturer's representative and Owner shall be present. A

Page 931 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-4
schedule of work to be accomplished and a list of labor, material and equipment rates for additional work will be established and maintained throughout the project.

Contractor shall furnish submittal data per Contract Requirements. Resumes of personnel to be used on the project shall be submitted.

B. The Contractor shall submit, prior to the Pre-Coating Conference, manufacturers' literature and Material Safety Data Sheets on all materials to be used in coating and painting operations, including, but not limited to coatings, paints, thinners, solvents and cleaning fluids per Contract Requirements. Contractor shall maintain copies of submittal data at jobsite at all times.

1.06 SUBMITTALS

A. GENERAL: Submit shop drawings, coating data and related information in accordance with Contract Requirements.

B. TECHNICAL DATA SHEETS: Submit technical data sheet on each product used, including ASTM test results indicating the product conforms to and is suitable for its intended use per these specifications.

C. MSDS: Submit Material Safety Data Sheets (MSDS) for each product used.

D. GUIDELINES: Project specific guidelines and recommendations.

E. APPLICATOR QUALIFICATIONS:

1. Manufacturer certification that Applicator has been trained and approved in the handling, mixing and application of the products to be used.

2. Certification by the protective coating manufacturer that the equipment to be used for applying the products has been approved and Applicator personnel have been trained and certified for proper use of the equipment.

3. Five (5) recent references of Applicator (projects of similar size and scope) indicating successful application of a high-build solvent-free epoxy coating by spray application.

4. Proof of any necessary federal, state or local permits or licenses necessary for the project.

5. Submit applicator's certification that resurfacing materials comply with Federal, State, and Local regulations for VOC (Volatile Organic Compounds).

6. Submit daily reports that contain the following information: substrate conditions, ambient conditions, application procedures, work completed and location thereof. Mark-up drawings that show location of work.

Page 932 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-5

7. Submit letter(s) with associated product data signed by Manufacturer certifying that submitted products are suitable for application on the surfaces to be resurfaced and for the service conditions.

F. DESIGN DETAILS: Submit design details for any additional ancillary systems and equipment to be used in site and surface preparation, application and testing.

1.07 DELIVERY AND STORAGE

A. GENERAL: Materials shall be stored in accordance with Manufacturer's recommendations in enclosed structures and shall be protected from weather and adverse temperature conditions. Flammable materials shall be stored in accordance with state and local codes. Materials exceeding storage life recommended by the manufacturer shall be removed from the site.

B. STORAGE: Store all materials only in area or areas designated by the Owner solely for this purpose. Confine mixing, thinning, clean-up and associated operations, and storage of materials-related debris before authorized disposal, to these areas. All materials are to be stored on pallets or similar storage/handling skids off the ground in sheltered areas in which the temperature is maintained between 50oF and 90oF.

C. MIXING: Mix all resurfacing materials in an enclosed mixing area designated by the Owner. This enclosed area must protect the mixing operation and materials from direct sunlight, inclement weather, freezing, or other means of damage or contamination. Protect all other concrete and metallic surfaces and finishes from any spillage of material(s) within the mixing area.

D. DISPOSAL: Contractor shall be responsible for legal disposal of materials. Do not use floor drains, dikes or storm drains for disposal of resurfacing system materials.

E. PRECAUTIONS AGAINST HAZARDS: The Contractor shall take all precautions and implement all measures necessary to avert potential hazards associated with the resurfacing system materials as described on the pertinent Material Safety Data Sheets or container labels.

E. DELIVERED MATERIALS: Deliver all materials to the jobsite in their original, unopened containers. Each container shall bear the Manufacturer's name and label.

1. Labels on all material containers must show the following information:

a. Name or title of product.
b. Federal Specification Number if applicable.
c. Manufacturer's batch number and date of manufacture. d. Manufacturer's name.
e. Generic type of material.
f. Application and mixing instructions.
g. Hazardous material identification label.

Page 933 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-6
h. Shelf life date.
i. Storage requirements.

2. All containers shall be clearly marked indicating any personnel safety hazards associated with the use of or exposure to the materials.

3. All materials shall be handled and stored to prevent damage or loss of label.

4. Resurfacing material storage and mixing areas shall be designated by the Owner.

5. Do not use or retain contaminated, outdated, prematurely opened, diluted materials, or materials which have exceeded their shelf life.

1.08 SAFETY

A. COMPLIANCE WITH STANDARDS: The Contractor's work forces should comply with the provisions outlined in the following documents:

1. SSPC-PA-3 "A Guide to Safety in Paint Application"

2. NACE Pub. "A Manual for Painter Safety"

3. OSHA 1915.35 Standards – 29CFR – Painting Safety

B. SAFETY EQUIPMENT: The Contractor shall provide personnel with all safety equipment necessary to protect them during any phase of the work. This shall include, but not be limited to, safety glasses, goggles, earplugs, hard hats, steel toed work shoes, appropriate personal protective clothing, gloves, and plant approved escape respirators (where required).

C. FLAMMABLE MATERIALS: Keep any flammable materials such as cleaning solvents, thinners, or resurfacing materials away from open flames, sparks or temperatures higher than 150oF. Drums containing flammable materials will be grounded. No solvent in any quantity shall be allowed inside containment enclosures or permitted confined spaces at any time during resurfacing work.

D. POWER TOOLS: Power tools are to be in good working order to avoid open sparking. No spark producing tools shall be utilized in restricted areas as indicated herein.

E. FIRE PROOFING: The Contractor shall fireproof all work areas by maintaining a clean work area and having Underwriter's Laboratories approved fire extinguishers on-hand. The Contractor shall furnish these fire extinguishers.

F. ABRASIVE BLASTING: Workers doing abrasive blasting operations shall wear a fresh air supplied protective helmet and hood and personal prot ective clothing acceptable to industry standards and all government regulations.

G. DISPOSAL OF RAGS: Dispose of rags used for wiping up resurfacing materials, solvents, and thinners by drenching them with water and placing in a metal

Page 934 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-7
container with a tight fitting metal cover. Complete this disposal process at the end of each day. Final disposal of these materials is the Contractor's responsibility.

H. FLAMES AND SPARK REQUIREMENTS: Matches, smoking, flames, or sparks resulting from any source including welding, must be remote from the work area during coating work. Smoking is permitted only in designated areas of the plant.

1.09 WARRANTY

The coating shall carry an extended warranty for a two-year period from the date of acceptance.

All warranties shall be turned into the Owner prior to project acceptance. Contractor shall, within a reasonable time after receipt of written notice thereof, repair defects in materials or workmanship which may develop during said two (2) year period, and any damage to other work caused by such defects or the repairing of same, at his own expense and without cost to the Owner.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

Approved manufacturers are:

1. Raven Lining Systems; Kansas City, KS (800-321-0906).

2. Tnemec Company; Kansas City, Missouri (800-863-6321).

2.02 MATERIALS

A. EPOXY LINING SYSTEM: The epoxy lining system shall be a high-build, 100% solids, solvent-free epoxy system; and shall be one of the following:

1. Raven 405FS

2. Tnemec Company products:

a. Surfaces: MortarClad – Series 218
b. Lining: Perma-Shield H2S – Series 434
c. Topcoat/gelcoat: Perma-Glaze – Series 435

B. MATERIALS TESTING REQUIREMENTS: Materials specified shall have been tested in a Severe Accelerated Wastewater Test. Submit evidence of successful test results to Owner.

C. ABRASIVE BLAST MEDIA: If dry or wet abrasive blast cleaning is the selected method of surface preparation, provide slag grit of a sieve size, gradation, and quality necessary to produce the degree of cleanliness and surface profile required herein (ICRI Guideline 03732, CSP-5 and SSPC-SP13/NACE No. 6).

D. REPAIR MATERIALS: Repair materials shall be used to fill voids, structurally reinforce and/or rebuild surfaces, etc. as determined necessary by the Owner and protective coating applicator. Repair materials must be compatible with the

Page 935 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-8
specified epoxy coating and shall be applied in accordance with the manufacturer's recommendations.

PART 3 – EXECUTION

3.01 GENERAL

A. HOISTING, SCAFFOLDING, STAGING, AND PLANKING:

1. Provide, set-up, and maintain all required hoists, scaffolds, and staging and planking, and perform all access related hoisting work required to complete the work of this section as indicated and specified.

2. Scaffolds shall have solid backs and floors to prevent dropping materials from there to the floors or ground below.

B. ENVIRONMENTAL REQUIREMENTS:

1. Comply with the Manufacturer's recommendations as to environmental conditions under which resurfacing system materials can be applied.

2. Do not apply resurfacing system materials when dust is in work site.

3. The Contractor shall provide all temporary lighting during the work.

C. PROTECTION:

1. Cover or otherwise protect finish work or other surfaces not being resurfaced.

2. Erect and maintain protective tarps, enclosures and/or maskings to contain debris (such as dust or airborne particles resulting from surface preparation) generated during any and all work activities. This includes, but is not limited to, the use of dust/debris collection apparatus as required.

D. INITIAL INSPECTION OF SURFACES TO BE COATED: It is the responsibility of the Contractor to inspect and report unacceptable concrete substrate surface conditions to the Owner prior to the commencement of surface preparation activities. Unacceptable surface conditions are defined as the presence of cracked surfaces or concrete deteriorated to a depth of greater than 1” or otherwise unable to withstand surface preparation as specified herein.

E. THINNERS AND SOLVENTS: The Contractor shall use only solvents and thinners as recommended by the Manufacturer.

3.02 ACCEPTABLE APPLICATORS

A. TRAINING: Applicators shall be trained to properly apply the coating according to manufacturer's recommendations.

Page 936 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-9
B. APPLICATOR CERTIFICATION: Protective coating must be applied by a Certified applicator of the protective coating manufacturer and according to manufacturer specifications.

3.03 CURING OF NEW CONCRETE

Portland cement or new concrete must be well cured (28 days minimum) prior to application of the protective coating. Contractor shall account for this curing time in his bid proposal, and no additional Contract Time extension will be allowed therefore.

3.04 SURFACE PREPARATION REQUIREMENTS

A. GENERAL: The following general requirements shall apply to all surface preparation:

1. Applicator shall inspect all surfaces specified to receive a protective coating prior to surface preparation. Applicator shall notify Owner of any noticeable disparity in the surfaces which may interfere with the proper preparation or application of the specified protective coating.

2. All contaminants including: oils, grease, unsound or incompatible existing coatings, waxes, form release, curing compounds, efflorescence, sealers, salts, or other contaminants shall be removed.

3. All specified surface preparation shall be performed in accordance with the latest version of the SSPC, NACE, ICRI and other standards referenced in this section.

4. Concrete surfaces shall be abraded to produce a minimum surface profile as recommended by the coating manufacturer. This preparation will be followed by vacuum cleaning to remove all dust, dirt or friable substances leaving clean, dust free surfaces for resurfacing as detailed in SSPC-SP 13/NACE No. 6).

5. The air used for blast cleaning shall be free of oil and moisture to not cause contamination of the surfaces to be resurfaced.

6. Clean cloths and clean fluids shall be used in solvent cleaning.

7. Cleaning and resurfacing shall be scheduled so that dust and other contaminants from the cleaning process will not fall on wet, newly resurfaced areas.

8. Prepare concrete joint and install sealant following resurfacing material installation pursuant to the coating manufacturer's recommendations.

Page 937 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-10
B. INITIAL CLEANING/DECONTAMINATION:

1. All existing areas to be resurfaced shall be pressure washed with alkaline –based detergent to remove all loose materials, acid constituents, grease, oil, and other contaminants.

2. Verify that the pH of the cleaned concrete surfaces to be coated is within the range of to 8 to 11. Application of coating materials outside this range will not be permitted without written approval from the Owner.

C. ABRASIVE BLAST CLEANING

1. Used or spent blast abrasive shall not be reused on work covered by this section.

2. The compressed air used for blast cleaning will be filtered free of condensed water or oil. Moisture traps will be cleaned at least once every four hours or more frequently as is appropriate.

3. Oil separators shall be installed just downstream of compressor discharge valves and at the discharge of the blast pot discharges. Oil separators shall be cleaned at least once every four hours or more frequently as is appropriate.

4. A paper blotter test shall be performed by the Contractor when requested by the Owner or the Owner’s representative to determine if the air is sufficiently free of oil and moisture (Reference ASTM D 4285).

5. Regulators, gauges, filters, and separators will be in good working order for all of the compressor air lines to blasting nozzles at all times during this work.

6. An air dryer or drying unit shall be installed which dries the compressed air prior to blast connections. This dryer shall be used and maintained for the duration of surface preparation work.

7. The quality, volume, and velocity of life support and ventilation air used during surface preparation shall be in accordance with applicable safety standards and as required to ensure adequate visibility and proper dissipation of volatiles without impacting the prepared surface or the health of the public or personnel working for the Contractor, Subcontractors, Owner, Owner’s representatives, or anyone who may be affected by on-site maintenance coating work activities.

8. The abrasive blast nozzles used shall be the venturi or other high velocity type supplied with the minimum air pressure and the necessary volume to obtain the required specified degree of cleanliness.

9. The Contractor must provide adequate ventilation for airborne particulate evacuation and lighting (meeting all pertinent safety standards) to

Page 938 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-11
optimize visibility for both blast cleaning and observation of the substrate during surface preparation work.

10. All phases of surface preparation work specified herein must be inspected by the Owner before the Contractor proceeds with the subsequent phase of surface preparation.

11. If, between final surface preparation work and coating application, contamination of the prepared and cleaned substrate occurs, or if the prepared concrete's appearance darkens or changes color, reblasting will be required until the specified degree of cleanliness is established.

3.05 SPECIFIC SURFACE PREPARATION REQUIREMENTS

A. SPECIFIC REQUIREMENTS: In addition to the paragraph 3.04 requirements, the Contractor shall follow the requirements of this section.

B. TERMINATIONS: Where the coating is specified to be terminated, the Contractor shall prepare and apply materials per the Manufacturer's recommendations.

C. PENETRATIONS: For applications around penetrations and/or drains, the contractor shall prepare and apply coatings in accordance with Manufacturer's recommendations. All hardware mounting bolts or studs shall be in place and masked with the hardware removed for the coating process. The coating shall contact the mounting bolts/studs so no break in the coating will occur.

D. FLOOR PITCH: When the floor area is scheduled to receive a mortar application to pitch the floor, the walls above the floor shall be sawcut to a depth of 1/2 inch at a height from 0’-0” to 0’-6” above the floor. The cut shall be straight and level.

E. NOTIFICATION TO OWNER: The Contractor shall notify the Owner should jobsite conditions prevent the above operations and/or applications.

3.06 APPLICATION REQUIREMENTS

A. GENERAL: The following general application requirements shall apply to the project:

1. Application procedures shall conform to the recommendations of the protective coating manufacturer, including material handling, mixing, environmental controls during application, safety, and spray equipment.

2. When spray equipment is used, the spray equipment shall be specifically designed to accurately ratio and apply the specified protective coating materials and shall be regularly maintained and in proper working order.

3. Areas not to be resurfaced shall be masked using duct tape or other protection materials to prevent these surfaces from being resurfaced.

Page 939 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-12

4. Ensure straight, even termination of resurfacing/topcoat materials on wall edges and flush with embedded steel.

5. The Contractor must follow the minimum and maximum recoat limitation times and related temperature range restrictions between successive lifts for all products specified herein per Manufacturer's stated requirements.

6. All equipment and procedures used for resurfacing system application shall be as recommended by the Manufacturer.

7. Unless specified elsewhere herein, the Contractor shall comply with the Manufacturer's most recent written instructions with respect to the following:

a. Mixing of All Materials.
b. Protection and Handling of All Materials.
c. Recoat Limitation and Cure Times.
d. Minimum Ambient and Substrate Temperatures, Substrate's Degree of Dryness, Relative Humidity, and Dew Point of Air. e. Application.
f. Final Curing.
g. Use of Proper Application Equipment.

8. Curing of Resurfacing System: The applied resurfacing system shall be protected from damage during curing and shall be cured as recommended by the Manufacturer. Ambient conditions shall be controlled by the Contractor during curing to ensure the minimum air temperature and minimum relative humidity as required by the Manufacturer is maintained.

B. CHEMICAL RESISTANT LINING: The following shall apply to the specified Tnemec Coating System:

1. General Note: The Contractor is advised that with all thick-film, quick curing materials applied to concrete surfaces, outgassing of the concrete may occur. Possible remedies include applying materials when the temperature of the concrete surfaces is descending, or applying a thin (1/16”) layer of the specified surfacing material. Other remedies may exist, and may be submitted for the Owner’s approval.

2. Fill all voids, bugholes and other surface imperfections with Tnemec Series 218 MortarClad.

3. Apply Tnemec Series 434 Perma-Shield H2S chemical resistant mortar to all floor areas and walls scheduled to be coated at a nominal thickness of 125 mils. Application shall be either by trowel or spray. If spray-applied, material shall be finish-troweled and finish-rolled (Reference manufacturers application guides for explicit instructions).

4. Series 435 Perma-Glaze shall be a minimum of 15.0 mils thick upon cure regardless of the number of coats required.

Page 940 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-13

C. SAFETY AND VENTILATION REQUIREMENTS: Requirements for safety and ventilation shall be in accordance with SSPC Paint Application Guide No. 3.

3.07 SPECIFIED APPLICATION THICKNESS

All interior surfaces of the new sewer manholes shall be coated as specified with a nominal dry film thickness of 125 mils.

3.08 FIELD QUALITY CONTROL INSPECTION AND TESTING

A. INSPECTION BY OWNER: Inspection by the Owner or others does not limit the Contractor's responsibilities for quality control inspection and testing as specified herein or as required by the Manufacturer's instructions.

B. QUALITY CONTROL PROCEDURES: Perform the quality control procedures listed below in conjunction with the requirements of this Section.

1. Inspect all materials upon receipt to ensure that all are supplied by the Manufacturer.

2. Provide specified storage conditions for the resurfacing system materials, solvents, and abrasives.

3. Inspect and record findings for the degree of cleanliness of substrates used.

The pH of the concrete substrate will be measured using pH indicating papers. pH testing is to be performed once every 50 sq. ft. Acceptable pH values shall be between 8.0 and 11.0 as measured by a full-range (1-12) color indicating pH paper with readable color calibrations and a scale at whole numbers (minimum). Use Hydrion Insta-Check Jumbo 0-13 or 1- 12 or equal. The paper shall be touched to the surface once using moderate gloved finger pressure. The surface shall not be wiped or moved laterally to disturb the surface during pH testing. Following the one touch, lift the paper vertically to not "wipe" the surface. Compare the color indicated with the scale provided and record the pH.

4. Inspect and record substrate profile (anchor pattern). Surfaces shall be abraded, as a minimum, equal to the roughness of CSP-5 ICRI Guideline 03732.

5. Measure and record ambient air temperature once every two hours of each shift using a thermometer and measure and record substrate temperature once every two hours using a surface thermometer.

5. Measure and record relative humidity every two hours of each shift using a sling psychrometer in accordance with ASTM E337.

6. Provide correct mixing of resurfacing materials in accordance with the Manufacturer’s instructions.

Page 941 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-14

8. Inspect and record that the "pot life" of resurfacing materials is not exceeded during installation.

9. Verify curing of the resurfacing materials in accordance with the Manufacturer's instructions.

10. Upon full cure, the installed lining system shall be checked by high voltage spark detection in accordance with NACE RP0188-90, and the manufacturer’s printed application guide to verify a pinhole-free surface.

Areas which do not pass the spark detection test shall be corrected at no cost to the Owner and rechecked.

11. Upon completion of the lining system installation, the lined area shall be cleaned and prepared to permit close visual inspection by the Owner. Any and all deficiencies or defective work (not in compliance with this section or related sections) will be marked for repair or removal/replacement by the Contractor at no additional cost to the Owner.

C. TESTING: The following testing requirements shall apply as determined by the Owner.

1. During application a wet film thickness gage, such as those available through Paul N. Gardner Company, Inc. meeting ASTM D4414 – Standard Practice for Measurement of Wet Film Thickness of Organic Coatings by Notched Gages, shall be used to ensure a monolithic coating and uniform thickness during application.

2. After the protective coating has set hard to the touch it shall be inspected with high-voltage holiday detection equipment. Surfaces shall first be dried, an induced holiday shall then be made on to the coated concrete surface and shall serve to determine the minimum/maximum voltage to be used to test the coating for holidays at hat particular area. The spark tester shall be initially set at 100 volts per 1 mil (25 microns) of film thickness applied but may be adjusted as necessary to detect the induced holiday (refer to NACE RPO188-99). All detected holidays shall be marked and repaired by abrading the coating surface with grit disk paper or other hand tooling method. After abrading and cleaning, additional protective coating material can be hand applied to the repair area. All touch-up/repair procedures shall follow the protective coating manufacturer's recommendations.

3. Measurement of bond strength of the protective coating to the substrate can be made at regular intervals and along different sections of the structure (i.e. crown of pipe, wall, invert – every 200 ft). Bond strength can be measured in accordance with ASTM D4541. Any areas detected to have inadequate bond strength shall be evaluated by the Owner. Further bond tests may be performed in that area to determine the extent of potentially deficient bonded area and repairs shall be made by Applicator in strict accordance with manufacturer's recommendations.

Page 942 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-15

4. A final visual inspection shall be made by the Inspector and manufacturer's representative. Any deficiencies in the finished coating shall be marked and repaired according to the procedures set forth herein by Applicator.

3.09 ACCEPTANCE CRITERIA

A. ACCEPTANCE CRITERIA FOR SURFACE PREPARATION WORK: All surfaces shall be prepared in accordance with the specification and referenced standards therein.

B. ACCEPTANCE CRITERIA FOR COATING SYSTEM APPLICATION
WORK: The following acceptance criteria for applicant work shall apply:

1. Acceptable coating work will be based upon the following:

a. No pock-marks, trowel marks, depressions, unconsolidated areas, waviness or ridges, pinholes or holidays in either size or frequency.
b. No intercoat bond failures between lifts.
c. Proper curing of coatings.

2. Resurfaced areas shall pitch to drains.

3. There shall be no areas that puddle when flood tested.

4. The Owner or Owner’s representative shall, at their discretion, inspect the following:

a. Profile and degree of cleanliness of substrate.
b. Thickness of materials/coverage rate confirmation.
c. Ambient temperature and humidity requirements and substrate temperature.
d. Curing and recoat times.
e. Proper curing of the resurfacing materials.

5. Rework required on any holidays or any other inadequacies found by the Owner or the Owner’s representative in the quality of the coating work shall be marked. Such areas shall be recleaned and reworked by the Contractor according to these specifications and the manufacturer's recommendations at no additional cost to the Owner.

6. The Contractor is responsible for keeping the Owner informed of all progress so that inspection for quality can be achieved.

7. The Contractor is ultimately responsible for the quality performance of the applied materials and workmanship. Inspections by the Owner or the Owner’s representative do not limit this responsibility.

3.10 FINAL INSPECTION

Page 943 of 1492 ends

CITY OF BEAUMONT EPOXY COATING FOR CONCRETE

BEAUMONT MESA L-S FORCE MAIN WASTEWATER STRUCTURES
099723-16
Perform a final inspection to determine whether the resurfacing system work meets the requirements of the specifications. The Owner, the Contractor and the Manufacturer's representative will conduct the final inspection.

3.11 CLEANUP

Upon completion of work, the Contractor shall remove surplus materials, equipment, protective coverings, and accumulated rubbish, and thoroughly clean all surfaces and repair any work-related damage. The surrounding surface areas including roadways and all other surfaces shall be restored to their pre-project condition.

3.12 SERVICES OF MANUFACTURERS

A. GENERAL: The services described herein are for the field observation, inspection assistance and quality control for the specified coating applications. For purposes of this paragraph, a work day is defined as an 8-hour period at the site, excluding travel time. The Owner may require that the Manufacturer's services described herein be furnished in twelve (12) separate trips. Four (4) hours or less at the jobsite will be considered as one-half (1/2) of a working day.

B. MANUFACTURER'S ATTENDANCE JOBSITE: The service representative(s) of the manufacturer shall be present at the site during all major phases of the work (surface preparation, surface application, inspection and testing, etc.), for each facility or structure receiving the specified coating. For purposes of this specification, eight (8) working days of manufacturer's attendance at the jobsite shall be required.

END OF SECTION 099723

Page 944 of 1492 ends

CITY OF BEAUMONT EXCAVATION SUPPORT AND PROTECTION
BEAUMONT MESA L-S FORCE MAIN 315000-1

SECTION 315000 - EXCAVATION SUPPORT AND PROTECTION
PART 1 - GENERAL

1.1 SUMMARY
A. Section includes temporary excavation support and protection systems.

1.2 RELATED SECTIONS
A. Section 319000 – Geotechnical Report

1.3 PREINSTALLATION MEETINGS
A. Preinstallation Conference: NOT USED.

1.4 INFORMATIONAL SUBMITTALS
A. Contractor Calculations: For excavation support and protection system. Include analysis data signed and sealed by the qualified professional engineer responsible for their preparation.

B. Record Drawings: Identify locations and depths of capped utilities, abandoned-in-place support and protection systems, and other subsurface structural, electrical, or mechanical conditions.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS
A. Provide, design, monitor, and maintain excavation support and protection system capable of supporting excavation sidewalls and of resisting earth and hydrostatic pressures and superimposed and construction loads.

1. Design excavation support and protection system, including comprehensive engineering analysis by a qualified professional engineer.

B. All excavations shall be adequately shored, braced, and sheeted to prevent earth movement or settlement. Existing structures, piping, duct bank/conduits, and other improvements that are to remain shall be fully protected from damage.

C. Proper shoring, sloping, sheeting, and bracing is required for all excavation where five feet in depth or more is required. A CALOSHA permit shall be obtained for trenches five feet or great in depth. A copy of this permit shall be supplied to the Owner with an additional copy kept at the job site at all times.

D. Contractor shall submit shoring, underpinning, and earth retention calculations and shop

Page 945 of 1492 ends

CITY OF BEAUMONT EXCAVATION SUPPORT AND PROTECTION
BEAUMONT MESA L-S FORCE MAIN 315000-2

drawings to the District and Engineer prior to commencing the work that requires said retention.

All calculations and drawings shall be prepared under the supervision of and signed and stamped by a civil engineer licensed in California.

E. Contractor shall provide positive protection (mat/sheet coverings) for all excavation slopes to protect slopes from instability and deterioration. This includes slopes on soil piles used for pre- loading and surcharging of areas.

PART 3 - EXECUTION

3.1 GENERAL REQUIREMENTS
A. Contractor shall coordinate all elements of the soil retention system with all surrounding utilities, structures, buildings, pipelines, and other improvements that are to remain and need to be protected. Shoring shall account for surcharge and other loading from adjacent footings and structures that are near excavation and require protection.

3.2 REMOVAL AND REPAIRS
A. Remove excavation support and protection systems when construction has progressed sufficiently to support excavation and earth and hydrostatic pressures. Remove in stages to avoid disturbing underlying soils and rock or damaging structures, pavements, facilities, and utilities.

1. Remove excavation support and protection systems to a minimum depth of 48 inches below overlying construction and abandon remainder.

END OF SECTION 315000

Page 946 of 1492 ends

Furnish and Install PVC Force Main
Section 02768 – 1

SECTION 02768

FURNISH AND INSTALL PVC FORCE MAIN

PART 1 - GENERAL

1.01 DESCRIPTION
Under these specifications, the Contractor shall furnish all labor, material, equipment and tools required for the complete installation and testing of force main and appurtenances and allied structures as stated on the Bidding Sheets, shown on the contract drawings or specified herein, and all within the contract time. The Contractor shall be responsible for all work specified herein and the orderly progress and completion of the work in accordance with an approved schedule of construction.

The work includes, but is not limited to, all excavation, backfill, disposal, resurfacing of roads and driveways, verification of utilities, installation of all pipe and specials such as elbows, bends and tapers.

All restraint for pipe, such as at the elbows, bends, etc., shall be sufficient to withstand all unbalanced forces. Unless otherwise approved by the Engineer, restraint shall be provided by means of restraint fittings as required by the Contract Drawings and these specifications. The use of concrete anchorage in lieu of restrained joints will be considered on a case by case basis. All restraint shall be included in the bid price for the installation of pipe.

It shall be the responsibility of the Contractor to furnish the District with accurate tie dimensions to all valves installed in the course of constructing this project.

Refer to Section 02201 of the District's standard specifications for requirements relating to Construction Methods and Earthwork and Section 02221 for requirements relating to Trenching, Backfilling and Compacting.

1.02 QUALITY ASSURANCE
Unless otherwise specified, all work specified herein and as shown on the drawings shall conform to the applicable requirements of the latest revision of the following standards. Unless specifically stated otherwise, the most stringent requirement will govern when there is a conflict.

A. AWWA C-900. American Water Works Association (AWWA) C-900 standard for polyvinyl chloride (PVC) pressure pipe 4 inches through 12 inches.

B. AWWA C-905. American Water Works Association (AWWA) C-905 standard for polyvinyl chloride (PVC) transmission pipe 14 inches through 36 inches.

1.03 SUBMITTALS
Shop drawings for all pipe and appurtenances shall be submitted pursuant to the requirements of the Contract Documents for Submittals, and shall show the materials, dimensions, stations and all relevant details of all specials.

Page 947 of 1492 ends

Furnish and Install PVC Force Main
Section 02768 – 2

1.04 PRODUCT DELIVERY

A. Materials Furnished by the Contractor. Except as otherwise stated on the Bidding Sheet, all materials, including pipe and appurtenances, shall be furnished in place by the Contractor. Materials to be furnished by the Contractor shall include that necessary for replacement of all obstructions, road surfacing, etc. The Contractor shall furnish the Engineer, as soon as issued, duplicate copies of all orders placed outside the Contractor's plant for articles or materials to be furnished by the Contractor for incorporation in the work. The Contractor shall also furnish the Engineer with such additional information as reasonably may be required respecting the character of the material and progress of their procurement.

B. Materials Furnished by the District. ONLY AS SHOWN ON THE CONTRACT DRAWINGS OR ON THE BIDDING SHEETS, OR ORDERED BY THE ENGINEER, will the District furnish any or all of the following materials necessary for the completion of the work under these specifications.

1. PVC pipe with rubber gaskets joints and gasket rings. Pipe will be delivered, unloaded and strung along trench site by the Pipe Supplier. Approximately 5% of each size of pipe will be furnished in the standard short lengths manufactured by the pipe supplier, except as otherwise requested by the Contractor.

2. Valves, Gaskets, bends, elbows, tapers, and air valve assemblies complete with piping and valves, etc.

3. Joint materials.

4. Locating wire required for PVC pipe systems.

5. Telemetry wire where noted on the construction drawings.

The Contractor shall, within seven (7) days after execution of the contract, meet with the Engineer for approval of his proposed schedule of construction and shall furnish the Engineer a written statement of the Contractor's requirements for delivery of materials and equipment to be furnished by the District with the dates upon which delivery of each class of said materials and equipment will be necessary in order to conform to the Contractor's program of construction.

Materials to be furnished by the District, except for pipe, will be delivered to the Contractor f.o.b. the Contractor's trucks at the District yard or warehouse, and the Contractor will sign for these materials received. No direct payment will be made to the Contractor for hauling or handling materials or equipment furnished by the District, but payment for such handling and hauling will be included in the prices

Page 948 of 1492 ends

Furnish and Install PVC Force Main
Section 02768 – 3

named for the contract items wherein the materials and equipment are used. The Contractor shall be responsible for coordinating the delivery and the actual placement of all pipe in accordance with his requirements and construction schedule, shall properly barricade the pipe and other materials, and shall be responsible for any damage to property as a result of the unloading or placement of the pipe or other materials.

If the delivery of any materials or equipment specified herein to be furnished by the District shall be delayed by strikes, acts of God, or other causes beyond the control or without the fault or negligence of the District, the Contractor shall have no claim against the District for such delay in delivery, but shall be entitled to so much additional time wherein to perform and complete the contract on his part as the Engineer shall certify in writing to be just.

C. Hauling and Handling Pipe. The Contractor shall protect all pipes from damage during hauling and handling. Dropping or dumping of pipe will not be permitted. Pipe shall not be strung prior to blasting in those areas where blasting is required. Damaged pipe shall be replaced or repaired by the Contractor at his expense, and be subject to approval by the Engineer.

1.05 JOB CONDITIONS.

Water Furnished by District. The District will make water available for construction at the locations stated in the Special Provisions.

1.06 PAYMENT

A. Measurement for Payment. Quantities for installation of pipelines and appurtenances on District-administered projects shall be measured for payment as specified herein and described on the Bidding Sheet:

1. Pipelines. Will be measured in place along the horizontal axis of the pipe by the linear foot, on the basis of pipeline completely installed and tested including earthwork, special bedding included in the work, pipe, gaskets, fittings, polyethylene encasement, specials, concrete and miscellaneous materials. The measurement will be continuous through all valves and fittings.

2. Valves will be measured on the basis of each valve completely installed and tested including valve, valve riser and cap, earthwork and miscellaneous materials.

3. Sewage Air Valves. Will be measured on the basis of each air valve assembly completely installed and tested including tap-to-main, piping, all valves, fittings, valve vault, earthwork, and miscellaneous materials.

Page 949 of 1492 ends

Furnish and Install PVC Force Main
Section 02768 – 4

4. Special Bedding. Will be measured on the basis of the cubic yards of special bedding required to bring the bedding up to grade for the trench size excavated up to the maximum size of trench allowable under these specifications. Only that special bedding for which there are stipulated costs, or for which special bid items are listed in the bid sheet will be measured for payment. No allowance will be made for over-excavation except as directed by the Engineer, or for special bedding required in the contract work under other bid items.

5. Bore Casing. Will be measured on the basis of horizontal centerline distance and shall include all excavation, furnishing and placement of casing, furnishing and placement of all required back-packing and grouting around casing, backfilling within casing, pipe bracing, restoration of surfaces, and all labor and material for a finished job. Furnishing and installation of pipe within casing shall be included in pipeline measurement.

6. Paving. Will be measured as a part of project causing removal and/or replacement of paving, except as otherwise specified on the Bidding Sheet.

B. Payment. Payment for quantities for installation of pipeline and appurtenances on District-administered contracts will be paid for in the following manner. Quantities of items listed herein, measured as stated above and accepted, will be paid for at the unit bid prices as stated herein, which prices and payments shall constitute full compensation for furnishing all labor, equipment and tools necessary to complete the described work in place. No additional compensation will be paid above the unit bid prices for changes in quantities.

1. Pipelines. Quantities of pipelines will be paid for at the respective unit bid prices per horizontal linear foot for the kinds and sizes of pipe stated in the bidding sheet. Work includes all earthwork, installation and testing of pipe, specials, fittings, anchors, removal and restoration of pavement, curbs, gutters and sidewalks, and clean-up.

Payment for pipe in place shall be further broken down based upon the Contractor's submittal under Section F-10 of the General Conditions, as concurred by the Engineer, but not to exceed in the ordinary project the following percentages of the linear foot price stated on the Bidding Sheet:

Trench excavation ..................................................................................... 10% Pipe laid in place and shaded .................................................................... 65% Trench backfilled and backfill compacted ................................................. 20% Testing and clean-up, exclusive of pavement replacement ....................... 5%

Page 950 of 1492 ends

Furnish and Install PVC Force Main
Section 02768 – 5

2. Fittings and Specials. Payments for quantities of fittings and specials shall be included in the payment for installation of pipelines. Work includes installation of bends, tapers, and all earthwork, and no additional compensation will be made therefore.

3. Valves. Quantities of valves will be paid for at the respective unit bid prices for the size and type of valves stated in the bidding sheet. Work includes installation of valves, flanges, gaskets, bolts, and all earthwork.

4. Sewage Air Valves. Quantities of air valve assemblies will be paid for at the respective unit bid prices for the size of air valves stated in the bidding sheet.

Work includes installation of tap-to-main, valves, service stops, elbows, bends, valve vaults, and all piping.

5. Special Bedding. Quantities of special bedding measured as stated above and accepted, will be paid for at the stipulated cost price, or the respective unit bid price for the quantities as stated in the bidding sheet, which price shall constitute full compensation for all labor, materials, and equipment necessary to complete the work in place, including the special bedding material.

6. Bore Casing. Payment for bore casing in place measured as stated above shall be made as specified on the bidding sheet.

7. Paving. Payment for quantities of paving measured as stated above and accepted shall be included in the unit bid for pipeline. Work includes removal and/or restoration of paving and all earthwork, and no additional compensation will be made therefore, except as otherwise provided on the bidding sheet.

1.07 GUARANTEE
All work, materials, and equipment shall be guaranteed for one year after the filing of the notice of completion except where the periods of time are set forth elsewhere in the contract documents for General Guaranty or Warranty.

PART 2 - PRODUCTS & MATERIALS

2.01 MATERIALS
Contractor to furnish PVC pipe as hereinafter described.

A. Type of PVC Pipe. PVC pipe shall be extruded from 12454 A or B compound providing a hydrostatic design basis (HDB) of 4000 p.s.i. in accordance with AWWA C-900 and C-905.

Pipe shall have cast iron outside diameters.

Page 951 of 1492 ends

Furnish and Install PVC Force Main
Section 02768 – 6

B. Pipe Class or Working Pressure. AWWA C-900 PVC pipe shall be Class 150 and AWWA C- 905 pipe shall be rated at 165 p.s.i. (DR-25) or as specified on approved drawings.

2.02 VALVES ENDS
Where valves do not connect to fittings, the fitting may be hub-end, or flange x hub-end. However, where valves connect to cast iron or welded steel fittings, fittings shall be flanged. Where flange x hub-end valves are not available for use with PVC pipe, flanged valves shall be used with flange x hub-end adaptors.

All valves shall be hung plumb, with the stems vertical.

2.03 RESTRAINED JOINTS
Restrained joints shall be provided by a clamping ring and an additional ring designed to seat on the bell end of the pipe. The rings shall be connected with T-Head bolts or rods. Restraining devices shall provide full (360°) support around the circumference of the pipe. No point loading shall be permitted.

Restraint of mechanical joint fittings shall be provided by a clamping ring installed on the PVC pipe and connected to the mechanical joint fitting with T-Head bolts or rods.

Restraining devices shall meet or exceed the requirements of UNI-Bell B-13 "Recommended Standard Performance Specification for Joint Restrainers for Use with PVC Pipe." Restraining devices shall be Uni-Flange Series 1300 or 1350 or approved equal.

All buried steel parts shall be sand blasted in accordance with the coating manufacturer's technical data sheet for "submerged" service and coated with a two coat epoxy. Epoxy shall be Tnemac Series 66 or equal. All bolts and tie rod materials shall be either high strength cast iron containing a minimum of 0.5% copper or high-strength, low alloy steel, as specified in AWWA C-111 for buried mechanical joints.

2.04 PORTLAND CEMENT CONCRETE
Cast-in-place structures of plain and reinforced concrete shall conform to the requirements of Chapter 26 of the Uniform Building Code and ACI 318, unless otherwise approved by the Engineer.

Classes of concrete used in the construction of cast-in-place structures shall be proportioned as specified in Section 03300 of the District standard specifications.

Page 952 of 1492 ends

Furnish and Install PVC Force Main
Section 02768 – 7

2.05 LOCATOR WIRE
Locator wire shall be installed over all waterlines, reclaimed waterlines and forcemains whether or not telemetry wire is buried with pipe. Locator wire per Standard Drawing B-656 shall be 14-1 solid insulated copper wire (UF), in a continuous strand, placed on top of pipe and secured with tape.

Locator wire shall be brought to the surface at the edge of the right of way at 660 feet maximum on centers in Brooks No. 1-SP, or equal, valve boxes. The valve boxes shall be placed within two feet of fire hydrants when fire hydrants are available at 660' or less on center. Where no fire hydrants are available EMWD marker posts shall be installed within two feet of the valve boxes. For subdivision construction, instead of the marker post, mark the face of the curb in front of the box with the letters “LW”. Loop 2 feet of wire in valve box. Provide the inspector survey stations at each valve box for as- built drawings.

2.06 TELEMETRY CABLE
On District-administered contracts, the District will supply the telemetry cable for installation in accordance with these specifications and contract drawings. The telemetry cable will be delivered to the Contractor at the District's warehouse. Prior to acceptance and delivery of the cable, a continuity test will be performed by District personnel or the Contractor's representative. Certification of the test results will be acknowledged by the Contractor or his representative in writing. The Contractor will be responsible for the safe handling, installation and retesting for total continuity of the cable installation prior to acceptance by the District.

2.07 POLYETHYLENE ENCASEMENT
All ductile iron fittings shall be polyethylene encased at the time of installation. Polyethylene encasement and installation shall be in accordance with ANSI/AWWA C105/A21.5.

PART 3 - EXECUTION

3.01 GENERAL
It shall be the responsibility of the Contractor, prior to start of construction, to meet with the Engineer:

A. For approval of schedule of construction for work and completion of pipelines or sections thereof;

B. To submit the required forms listed in the General Conditions.

C. To coordinate delivery of District-furnished materials.

1. Determine location and placing of the pipe to be unloaded and direction of placing bells;

2. Determine the quantity of pipe to be placed in a particular location;

Page 953 of 1492 ends

Furnish and Install PVC Force Main
Section 02768 – 8

3. Coordinate delivery of pipe and other materials to meet his construction schedule.

D. To furnish such additional information as may be required from time to time as construction progresses, regarding the progress of the procurement and delivery of the required equipment and materials, and/or the scheduling of the work.

Any subsequent shuttling of pipe, turning of bells, etc., will be at the Contractor's expense and no additional compensation will be allowed above the unit bid price, unless authorized by the Engineer in writing. All quantities shown on the Bidding Sheet and the contract drawings indicate the estimated quantities of materials for the completed pipelines in place.

3.02 BEDDING PIPE

A. General. Each section of pipe shall be lowered into the trench in a manner that will prevent injury to the pipe, or joints and shall be carefully bedded to provide continuous bearing and prevent uneven settlement. The inside of the pipe shall be clean and free from foreign material of any kind before being installed.

B. Tolerance. The pipe shall be accurately laid to alignment and grade shown on the drawings or established by the Engineer. Where grade stakes are provided with which to establish the proper pipeline grade, pipe shall be laid to grade within a tolerance of

0.1', or 0.2' cumulative deviation from elevations set by adjacent grade stakes. As ordered by the Engineer, the allowed tolerance may be greater than herein indicated for lines on steep grades, or less than herein indicated for the larger lines or lines on flat grades, where necessary to avoid air pockets.

C. Pipe Zone Bedding. The pipe zone bedding material shall conform to the requirements for solid wall PVC pipe on Standard Drawing SB-157, SB-158, and SB-159.

3.03 RUBBER GASKET PIPE JOINTS
After the subgrade has been prepared as specified, the rubber gasket shall be placed in the groove on the spigot ring, and the spigot end of the pipe then entered into the bell of the adjoining pipe and forced into position. Care shall be taken to avoid twisting or cutting the gasket when jointing the pipe.

The inside surface of the bell shall be lubricated with a compound recommended by Manufacture which will facilitate the telescoping of the joint.

Page 954 of 1492 ends

Furnish and Install PVC Force Main
Section 02768 – 9

3.04 CURVES, ANGLES, CLOSURES AND SHORT SECTIONS
The laying of pipe on curved alignment by means of unsymmetrical closure of spigot into bell rings will be permitted. The amount of pull permitted from normal closure on one side of the joint shall not exceed the manufacturer's recommendation. For the purpose of reducing the angular deflections at pipe joints and for closure sections, the Contractor shall be permitted to install pipe sections of less than standard length. Where such installations are allowed, Contractor shall be responsible for anchorage of the necessary joints, as directed by the Engineer.

3.05 FLANGE, FITTING AND BOLT PROTECTION
All appurtenances and fittings at the pipeline shall be primed, and wrapped with Protecto-Wrap No. 200 with No. 1170 Primer, or approved equal.

3.06 VALVE CAP AND RISER INSTALLATION
In new subdivision developments Contractor shall leave valve cans 3" minimum below rough-graded subgrade street surface, properly covered, and shall return after paving of the street is completed by others, to raise the valve slip can and cap to grade. Contractor shall coordinate his work with that of the paving contractor to place the slip can during placement of the road sub-base, if desirable.

3.07 TEMPORARY BULKHEADS
The Contractor shall furnish and install complete, all the necessary temporary bulkheads or skillets and appurtenances thereto in the pipeline used for backfilling or testing purposes and shall remove such bulkheads upon completion of the line.

The Contractor shall furnish, at his own expense, any openings in the pipeline or bulkhead and any valves or by-pass arrangements which are for his convenience in filling, testing and/or emptying the pipeline.

At all times when the work of installing pipe is not in progress, all openings into the pipe and the ends of the pipe in the trench shall be tightly closed to prevent entrance of animals and foreign materials.

The Contractor shall take all necessary precautions to prevent the pipe from floating due to water entering the trench from any source, shall assume full responsibility for any damage due to this cause and shall at his own expense restore and replace the pipe to its specified condition and grade if it is displaced due to floating. If the Contractor, upon approval by the Engineer, elects to test a system utilizing valves and connecting pipe installed by the District, the District will assume responsibility for any leaks occurring in any pipeline or valve furnished and installed by the District. In the event Contractor is unable to satisfactorily test his system because of leaks in the District-installed system, Contractor shall install temporary bulkheads in his construction to perform tests, as determined necessary by the Engineer.

Page 955 of 1492 ends

Furnish and Install PVC Force Main
Section 02768 – 10

Full compensation for furnishing all labor, tools, materials, and equipment (except water when provided by the District), and for doing all work involved in testing, and for repairing any leaks shall be included in the price paid for installation of the pipe, and no additional compensation by the District will be allowed therefore.

3.08 FIELD HYDROSTATIC TEST
Upon completion of the laying, jointing, backfilling, and proper curing of the joints, and compaction of backfill, the pipeline or portions thereof shall be hydrostatically tested.

For convenience of testing, the pipeline may be divided into sections and each section tested separately. Main line valves may be used in lieu of special bulkheads, or if valves are not conveniently located, temporary bulkheads shall be constructed. Bulkheads shall be constructed to safely withstand the hydraulic pressures imposed upon them. No payment will be made expressly for the work and materials required for the bulkheads and any
compensation desired by the Contractor for this work shall be included in the price quoted for the installation of pipe. The Contractor shall have no claim against the District by reason of required construction of bulkheads due to the omission of the installation of any or all main line valves.

After the section of pipeline has been bulkheaded and completely filled with water, it shall be allowed to stand under pressure a sufficient time to allow the escape of air from any air pockets. The pressure shall then be increased to the specified test pressure as hereinafter described, and shall be maintained at this pressure for not less than four (4) hours.

All pipe shall be tested under a pressure 1 1/2 times the design operating pressure of the pipe.

Maximum test pressure shall not exceed that determined by the Engineer.

If any leakage is evidenced in the testing of the pipeline, the various sections of the pipeline shall be isolated for testing between available valves, or between bulkheads located as directed by the Engineer. The maximum allowable leakage for pipe shall be two (2) gallons per day per mile of pipe per inch of pipe inside diameter. If the leakage exceeds this amount, the section being tested will be considered defective. The Contractor shall determine the points of leakage, make the necessary repairs and perform another test. This procedure shall be continued until the leakage in each section falls below the allowable maximum for that section of pipeline.

Leakage shall be determined by metering the water injected into the pipeline while under the required pressure. The Contractor shall submit to the District before and after the test the gage and meter used so that these devices may be tested by this District.

Page 956 of 1492 ends

Furnish and Install PVC Force Main
Section 02768 – 11

The Contractor shall provide all calibrated meters for measurement of leakage, all bulkheads or skillets, piping, calibrated gages, pumps and other equipment, all water not furnished by the District, and all power and labor necessary for the performance of pressure tests satisfactory to the Engineer. The Contractor shall furnish all necessary equipment and labor to fill each section of pipeline tested and for pumping the water from one test section to another as may be necessary for obtaining and maintaining the required water pressure and for filling the entire pipeline with water after the conclusion of the testing, as hereinafter provided.

The Contractor, at his own expense, shall do any excavation necessary to locate and repair leaks or other defects which may develop under test, including removal of backfill already placed, shall replace such excavated material, and shall make all repairs necessary to meet the required water tightness after which the test shall be repeated until the pipe meets the test requirements. All tests shall be made in the presence of the Engineer. After the pipe has met successfully all test requirements specified herein, the entire pipeline shall be filled with water and so maintained until the completion of the contract unless otherwise ordered by the Engineer.

END OF SECTION 02768

Page 957 of 1492 ends

Furnish and Install PVC Force Main
Section 02768 – 12

[PAGE LEFT INTENTIONALLY BLANK]

Page 958 of 1492 ends

Plastic (PVC) Pressure Water Pipe & Fittings
Section 15064 – 1

SECTION 15064

PLASTIC (PVC) PRESSURE WATER PIPE & FITTINGS

PART 1 - GENERAL

1.01 REQUIREMENT
It is required that the Contractor shall furnish, deliver, unload and string along the trench site, all pipe and material as hereinafter described in the specifications. All fabrication, workmanship, material and testing of pipe shall conform to the latest revision of the specifications.

1.02 DELIVERY

A. Transport, deliver, unload, store and handle all materials in a manner to prevent damage to the materials or the work.

B. All damaged, broken or otherwise defective materials will be rejected.

C. Store all circular rubber gaskets and special lubricants in packaged materials with the manufacturer's name, brand and all other applicable data plainly marked thereon.

1.03 QUALITY ASSURANCE
Unless otherwise specified, all work specified herein and as shown on the drawings shall conform to the applicable requirements of the latest revision of the following standards. Unless specifically stated otherwise, the most stringent requirement will govern when there is a conflict.

A. AWWA C-900. American Water Works Association (AWWA) C-900 standard for polyvinyl chloride (PVC) pressure pipe 4 inches through 60 inches for water.

B. Any pipe showing discoloration, chaulking, checking or other visible damage due to ultraviolet light exposure shall not be accepted by the District.

1.04 MEASUREMENT AND PAYMENT
Payment for pipe shall be made on a unit price basis per lineal foot of pipe.

Page 959 of 1492 ends

Plastic (PVC) Pressure Water Pipe & Fittings
Section 15064 – 2

PART 2 - PRODUCTS AND MATERIALS

2.01 TYPE OF PVC PIPE
PVC pipe and fabricated fittings shall be made from virgin PVC resin that has been compounded to provide physical and chemical properties that equal or exceed cell class 12454 as defined in ASTM D1784 providing a hydrostatic design basis (HDB) of 4000 p.s.i. in accordance to AWWA C-900. Pipe shall have cast iron outside diameters.

All rubber rings shall be furnished by the pipe manufacturer. These rubber rings (elastomeric gaskets) shall be manufactured to conform with the requirements of ASTM F-477.

2.02 PIPE CLASS OR WORKING PRESSURE
AWWA C-900 PVC pipe shall be Pressure Class 235 and shall have a Dimension Ratio of 18.0 (DR-18).

2.03 TYPE OF FITTING
Fittings for PVC pipe shall be flanged or bolted mechanical joint or push-on joint ductile or gray iron fittings and shall conform to ANSI/AWWA C110/A21.10 or C153/A21.53, and ANSI/AWWA C111/A21.11. All fittings shall be cement mortar lined and tar (seal) coated in accordance with ANSI/AWWA CI04/A21.4.

2.04 RESTRAINED SYSTEM
Restrained Joints shall be provided by a clamping ring and an additional ring designed to seat on the bell end of the pipe. The rings shall be connected with T-Head bolts or rods. Restraining devices shall provide full (360 degree) support around the circumference of the pipe. No point loading shall be permitted. Restraint of mechanical joint fittings shall be provided by a clamping ring installed on the PVC pipe and connected to the mechanical joint fitting with T-Head bolts or rods. Restraining devices shall meet or exceed the requirements of ASTM F-1674 or UNI-Bell B-13 "Recommended Standard Performance Specification for Joint Restrainers for Use with PVC Pipe." Restraining devices shall be UNI-Flange Series 1300 or 1350 or approved equal.

All buried steel parts shall be sand blasted in accordance with the coating manufacturer's technical data sheet for "submerged" service and coated with a two coat epoxy. Epoxy shall be Tnemac Series 66 or equal. All bolts and tie rod materials shall be either high strength cast iron containing a minimum of 0.5% copper or high-strength, low alloy steel, as specified in AWWA C-111 for buried mechanical joints.

2.05 SERVICE CONNECTION OUTLETS
All service connections to PVC pressure pipe water main shall be constructed with bronze service saddles with CS threads for receiving a bronze corporation stop in accordance with standard drawings.

Service saddle shall be Jones, Mueller, or approved equal.

Page 960 of 1492 ends

Plastic (PVC) Pressure Water Pipe & Fittings
Section 15064 – 3

2.06 POLYETHYLENE ENCASEMENT
All ductile or gray iron fittings shall be encased with V-Bio enhanced polyethylene at the time of installation. Polyethylene encasement and installation shall be in accordance with ANSI/AWWA C105.

PART 3 - EXECUTION

3.01 FACTORY TESTING
All pipe shall be tested in the United States in accordance with AWWA C900 and certification of the testing shall be furnished to the engineer upon his request prior to delivery. The engineer may be present during physical testing of pipe.

3.02 INSTALLATION
PVC pipe shall be installed in accordance with Sections 02718 and 02201 of Eastern Municipal Water District Specifications.

END OF SECTION 15064

Page 961 of 1492 ends

Plastic (PVC) Pressure Water Pipe & Fittings
Section 15064 – 4

[PAGE LEFT INTENTIONALLY BLANK]

Page 962 of 1492 ends

Nuts & Bolts
Section 15089 – 1

SECTION 15089

NUTS & BOLTS

PART 1 - GENERAL

1.01 REQUIREMENT
Bolts and nuts for flanged fittings shall be bare steel conforming to SAE J429 Grade 5 or ASTM A449 medium carbon steel quenched and tempered meeting the following requirements, and shall have hex heads and lite-pattern hex nuts.

¼” Through 1" diameter

85,000 p.s.i. proof strength
92,000 p.s.i. yield strength
120,000 p.s.i. tensile strength

Over 1" to 1½” diameter

74,000 p.s.i. proof strength
81,000 p.s.i. yield strength
105,000 p.s.i. tensile strength

1.02 USE OF ZINC CAPS FOR BURIED PIPE
Each bolted fitting including couplings, flange adapters, restrained joints, etc. that have manufactured bolts and nuts shall have a minimum of 2 zinc caps anodes as specified below.

Bolt sizes and number of zinc caps:

through 1" diameter - 2 zinc caps
over 1" diameter - 4 zinc caps

Weight of zinc caps:

Zinc caps to be 6 oz. weight.

Material reference:

Zinc caps shall be per ASTM B418-80 and Mil-A-18001J, and be manufactured by Mars, Reliance, or equal.

END OF SECTION 15089

Page 963 of 1492 ends

Nuts & Bolts
Section 15089 – 2

[PAGE LEFT INTENTIONALLY BLANK]

Page 964 of 1492 ends

Plug Valves
Section 15105 – 1

SECTION 15105

PLUG VALVES

PART 1 GENERAL

1.01 REQUIREMENT
Under this specification, the Contractor shall be required to furnish, deliver, and unload within the time specified in the Special Conditions, the plug valves as specified on the bidding sheets and hereinafter described in these specifications.

1.02 VALVE MANUFACTURER
The name of the manufacturer of the valves to be furnished by the bidder shall be stated on the bidding sheets.

Inasmuch as valves require an in-service review over an extended period of time for evaluation by the District for acceptance, it is necessary that proposed valves other than those specified must be submitted for evaluation well in advance of the bid opening, for acceptance prior to the award of the contract. Generally, the 35-day period following issuance of the Acceptance of Proposal will not result in approval of alternate valves.

1.03 GUARANTEE
The Contractor shall guarantee all materials and workmanship of items furnished under these specifications shall be free from defects for a period of one (1) year after final completion and acceptance of the entire contract work. The Contractor shall, at his own expense, repair or replace all defective materials or workmanship supplied by him found to be deficient with respect to any provisions of this Specification.

PART 2 PRODUCTS

2.01 ECCENTRIC PLUG VALVES
Valves shall be of the non-lubricated eccentric type with semi-steel bodies, resilient faced plugs and ends as shown. The port area shall be cylindrical/rectangular and100% of the standard pipe area.

Valves shall be operated by lever or gear operator unless otherwise shown. Flanged valves shall conform to the 125-lb standard unless otherwise shown. Valves 6-inch and larger, and all submerged valves, shall be equipped with gear operators, lubricated and sealed to prevent entry of dirt and water into the operator. All shaft bearings shall be furnished with permanently-lubricated bearing surfaces.

The operator shall clearly indicate valve position. Valves 4-inch and larger shall be epoxy-coated in the water passages. Valves and operators shall be as manufactured by DeZurik Corporation or approved equal.

Page 965 of 1492 ends

Plug Valves
Section 15105 – 2

PART 3 EXECUTION

3.01 INSTALLATION

Before installation, remove foreign material such as weld spatter, oil, grease, and dirt from the valve and pipeline.

Install the valve as shown in Figure 2.

a. In HORIZONTAL pipelines, install the valve so that the plug is horizontal and rotates upward as the valve opens.

b. In VERTICAL pipelines, install the valve with the end marked “SEAT” (specified for DeZURIK plug valves) at top of valve.

END OF SECTION 15105

Page 966 of 1492 ends

Air Release Valves for Sewage Service
Section 15108 – 1

SECTION 15108

AIR RELEASE VALVES FOR SEWAGE SERVICE

PART 1 - GENERAL

1.01 DESCRIPTION
This section includes materials and installation of air-release valves for sewage service.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Paint and Coating: 09900.

1.03 SUBMITTALS

A. Submit shop drawings in accordance with the General Conditions.

B. Submit manufacturer’s catalog data. Show dimensions, materials or construction by ASTM reference and grade, and coatings.

1.04 MEASUREMENT AND PAYMENT
Payment for work in this section shall be included as part of the lump sum bid amount as stated in the Proposal.

PART 2 - MATERIALS

2.01 COATINGS
Coat valves located above ground or in vaults and structures the same as the connecting piping. Apply prime coat at the place of manufacture. Color of finish coat shall match the color of the adjacent piping. Do not coat stainless steel pieces.

2.02 LINING
Coat interior surfaces of cast iron valves at the place of manufacture per Section 09900. Do not coat seating areas and plastic, bronze, stainless steel, or other high alloy parts.

Page 967 of 1492 ends

Air Release Valves for Sewage Service
Section 15108 – 2

2.03 VALVE DESIGN AND OPERATION
Air release valves for sewage service shall have elongated, cylindrical chambers designed to release entrained air and sewage gases through an air release orifice. Float shall withstand an external pressure of 500 psi without collapsing. Provide a -inch clearance around the float in the chamber.

Provide isolation valve, quick disconnect coupling and valve for back flushing, and back flushing hose.

Provide blowoff outlet and valve at the bottom of the chamber.

2.04 MATERIALS OF CONSTRUCTION

Materials of construction for air release valves for sewage service shall be as follows:

ITEM MATERIAL SPECIFICATION
Body, cover Cast Iron ASTM A126 GR.B
Float, Stainless Steel ASTM A240 T304
Internal Linkage, Stem Stainless Steel Series T300
Needle Buna-N Nitrile Rubber

2.05 VALVE END CONNECTIONS

A. Valves smaller than 3 inches shall have threaded ends. Valves 3 inches and larger shall have flanged ends.

B. Flanges for Class 150 valves shall comply with ANSI B16.1, Class 125. Flanges for Class 300 valves shall comply with ANSI B16.1, Class 250.

2.06 VALVES
Sewage Air Release Valves, Class 150: After entraining air escapes through the orifice, the orifice shall be closed by a needle on a compound lever mechanism to prevent the escape of sewage. The orifice shall remain closed until more gas accumulates and the cycle automatically repeats. Valve shall seat to prevent sewage from leaking through the valve at any pressure. Valves shall have an operating pressure of at least 175 psi. Venting capacity shall be at least 300 CFFAM. Valves shall be APCO model 450, or approved equal.

PART 3 - EXECUTION

3.01 INSTALLATION
Clean threaded joints by wire brushing or swabbing. Apply Teflon joint compound or Teflon tape to pipe threads before installing threaded valves. Joints shall be watertight.

Page 968 of 1492 ends

Air Release Valves for Sewage Service
Section 15108 – 3

3.02 VALVE PRESSURE TESTING
Test valves at the same time that the connection pipeline are being pressure tested. Protect or isolate any parts of valves, operators, or control and instrumentation systems whose pressure rating is less \than the test pressure.

END OF SECTION

Page 969 of 1492 ends

Air Release Valves for Sewage Service
Section 15108 – 4

[PAGE LEFT INTENTIONALLY BLANK]

Page 970 of 1492 ends

Manholes and Fittings
Section 15340 – 1

SECTION 15340

MANHOLES AND FITTINGS

PART 1 - GENERAL

1.01 REQUIREMENT
Under this specification, the Contractor shall be required to furnish, deliver and unload within the time specified in the Contract Documents, the manholes and fittings as specified on the Bidding Sheets, shown on the Contract Drawings, and described in these specifications, except as otherwise approved in writing by the Engineer.

1.02 MEASUREMENT AND PAYMENT
Payment for quantities of manholes will be made at the unit prices as stated on the Bidding Sheets.

1.03 GUARANTEE
The Contractor shall guarantee all materials and workmanship of items furnished under these specifications to be free from defects for a period of one (1) year after final completion and acceptance of the entire contract work. The Contractor shall, at his own expense, repair or replace all defective materials or workmanship supplied by him found to be deficient with respect to any provisions of this specification.

PART 2 - PRODUCTS

2.01 MANHOLES
All manhole rings, tops, and cones, as constructed in place, shall be designed for A.A.S.H.O. H-20 highway loading, and shall conform to District standard drawings and the requirements of ASTM C-478 and the following requirements.

2.02 RINGS
All manhole rings shall be centrifugally spun or compactly vibrated in forms.

2.03 TOPS
All manhole tops and cones shall be compactly vibrated in forms.

Page 971 of 1492 ends

Manholes and Fittings
Section 15340 – 2

2.04 MANHOLE COVERS
All manhole covers and frames shall conform to District standard drawings and the requirements for Class 30 gray iron castings in ASTM Designation A-48, or Class 60 Ductile Iron castings in ASTM A-536.

The castings shall be thoroughly cleaned and coated with commercial quality asphaltum paint. Frames and covers shall be matchmarked in pairs before delivery to the work site and must be machined matched between cover and frame to avoid rocking.

2.05 MANHOLE STEPS
Manhole steps shall conform to District Standard Drawings and shall be constructed of 1/2" plain steel bar incapsulated with copolymer polypropylene plastic as approved by EMWD. Alternate to be approved by EMWD for casting-in-place.

END OF SECTION 15340

Page 972 of 1492 ends

City of Beaumont
Request for bid Mesa Lift Station Force Main
CIP WW-09

41 05 CONTRACT DRAWINGS
CIP WW-09 BEAUMONT MESA LIFT STATION FORCE MAIN

Page 973 of 1492 ends

City of Beaumont
Contract Drawings Mesa Lift Station Force Main
CIP WW-09

CONTRACT DRAWINGS
1 CONTRACT DRAWINGS

All standard drawings and detailed provisions referenced in the Contract Documents shall be considered part of the contract drawings. These drawings include, but are not limited to, the following standard drawings and detailed provisions:

1. City of Beaumont Public Works Standard Drawings: latest standards available at https://www.beaumontca.gov/1236/Standards

2. County of Riverside Standards and Specifications (Ordinance 461): latest edition available at: https://rctlma.org/trans/Land-Development/Road-Standards)

3. Greenbook Standard Specifications for Public Works Construction: latest standards available at: https://www.bnibooks.com/products/standard-plans-for- public-works-construction-2021-edition

4. Bid Plans: Albert A. Webb Associates; Beaumont Mesa LS FM IMPROVEMENTS, 16-IN FORCE MAIN, Sheets 1 through 18. Plans are attached to this specification.

Page 974 of 1492 ends

City of Beaumont
Request for bid Mesa Lift Station Force Main
CIP WW-09

42 06 PUBLIC WORKS AGREEMENT
CIP WW-09 BEAUMONT MESA LIFT STATION FORCE MAIN

Page 975 of 1492 ends
Page 1 of 13 ends

CITY OF BEAUMONT

PUBLIC WORKS AGREEMENT

This PUBLIC WORKS AGREEMENT (“Agreement”) is made and effective July ______, 2023 by and between the City of Beaumont, a municipal corporation (“CITY”), and ___________________________________ (“CONTRACTOR”). In consideration of the mutual covenants and conditions set forth herein, the parties agree as follows:

I. SCOPE OF WORK

The CONTRACTOR shall perform within the time set forth in Article 2 of this Agreement and shall furnish all labor, materials, equipment, tools, utility services, and transportation and perform and complete all work required in connection with the ___________________ (hereinafter “Project”). CITY’s Invitation for Bids (“Invitation”) for the Project, dated _______ 2023, and CONTRACTOR’s Bid in response to the Invitation, dated ________, 2023, are attached hereto as Exhibits A and B, respectively and incorporated herein by this reference. The Scope of Work for the Project is set forth in the Invitation. In the event that any terms of the Bid are different from the Invitation for Bids, the Invitation for Bids shall control.

Any additional terms in the Bid that purport to bind the City to any additional terms not contained in this Agreement and related attachments shall not be binding on the City.

By entering into this Agreement, CONTRACTOR acknowledges that there may be other contractors on the site whose work will be coordinated with that of its own.

CONTRACTOR expressly warrants and agrees that it will cooperate with other contractors and will do nothing to delay, hinder, or interfere with the work of other separate contractors, the CITY, the Construction Manager, the Engineer, or utilities. CONTRACTOR also expressly agrees that, in the event its work is hindered, delayed, interfered with, or otherwise affected by a separate contractor, its sole remedy will be a direct action against the separate contractor. To the extent allowed by law, the CONTRACTOR will have no remedy, and hereby expressly waives any remedy against the CITY, the Construction Manager (if any), and the Engineer on account of delay, hindrance, interference or other events.

II. TIME FOR PROJECT COMPLETION

All of CONTRACTOR’s work on the Project shall be completed within durations established for the individual activities. All work shall commence ten (10) calendar days after receiving a written Notice of Award from the CITY or Construction Manager, if a Construction Manager is employed by CITY on the Project.

CONTRACTOR shall refer to the invitations for bids, and Project Plans and Specifications, all of which, as set forth below, are incorporated herein by reference, for contractual obligations regarding individual activity durations.

Page 976 of 1492 ends
Page 2 of 13 ends

III. THE CONTRACT SUM

The CITY shall pay to the CONTRACTOR for the performance of this Agreement, subject to any additions and deductions provided in the Project documents, the sum of ____________ dollars ($_______).

IV. PROGRESS PAYMENTS

Based upon Applications for Payment submitted to the Engineer by the CONTRACTOR and Certificates for Payment issued by the Engineer, the CITY shall make progress payments on account of the Contract Sum to the CONTRACTOR as provided in the General Conditions, which are fully incorporated into this Agreement by this reference.

This Agreement is subject to the provisions of Article 1.7 (commencing at Section 20104.50) of Division 2, Part 3 of the Public Contract Code regarding prompt payment of contractors by local governments. Article 1.7 mandates certain procedures for the payment of undisputed and properly submitted payment requests within 30 days after receipt, for the review of payment requests, for notice to Contractor of improper payment requests, and provides for the payment of interest on progress payment requests which are not timely made in accordance with that Article. This Agreement hereby incorporates the provisions of Article 1.7 as though fully set forth herein.

V. INDEMNITY, DEFENSE AND HOLD HARMLESS AGREEMENT

CONTRACTOR shall indemnify, defend with legal counsel approved by CITY, and hold harmless CITY, its officers, officials, employees and volunteers from and against all liability, loss, damage, expense, cost (including without limitation reasonable legal counsel fees, expert fees and all other costs and fees of litigation) of every nature arising out of or in connection with CONTRACTOR’s negligence, recklessness or willful misconduct in the performance of work hereunder or its failure to comply with any of its obligations contained in this Agreement, except such loss or damage which is caused by the sole or active negligence or willful misconduct of the CITY. Should conflict of interest principles preclude a single legal counsel from representing both CITY and CONTRACTOR, or should CITY otherwise find CONTRACTOR’s legal counsel unacceptable, then CONTRACTOR shall reimburse the CITY its costs of defense, including without limitation reasonable legal counsels fees, expert fees and all other costs and fees of litigation. The CONTRACTOR shall promptly pay any final judgment rendered against the CITY (and its officers, officials, employees and volunteers) with respect to claims determined by a trier of fact to have been the result of the CONTRACTOR’s negligent, reckless or wrongful performance. It is expressly understood and agreed that the foregoing provisions are intended to be as broad and inclusive as is permitted by the law of the State of California and will survive termination of this Agreement.

Page 977 of 1492 ends
Page 3 of 13 ends

CONTRACTOR obligations under this section apply regardless of whether or not such claim, charge, damage, demand, action, proceeding, loss, stop notice, cost, expense, judgment, civil fine or penalty, or liability was caused in part or contributed to by an Indemnitee. However, without affecting the rights of CITY under any provision of this agreement, CONTRACTOR shall not be required to indemnify and hold harmless CITY for liability attributable to the active negligence of CITY, provided such active negligence is determined by agreement between the parties or by the findings of a court of competent jurisdiction. In instances where CITY is shown to have been actively negligent and where CITY active negligence accounts for only a percentage of the liability involved, the obligation of CONTRACTOR will be for that entire portion or percentage of liability not attributable to the active negligence of CITY.

VI. PREVAILING WAGES

A. Contractor shall comply with all applicable laws and regulations relating to prevailing wages. Wage rates for this Project shall be in accordance with the “General Wage Determination Made By the Director of Industrial Relations Pursuant To California Labor Code, Part 7, Chapter 1, Article 2, Sections 1770, 1773 and 1773.1”, for Riverside County. Wage rates shall conform with those posted at Beaumont City Hall and the Project site.

B. The following Labor Code sections are hereby referenced and made a part of this Agreement:

1. Section 1775 - Penalty for Failure to Comply with Prevailing Wage Rates.

2. Section 1777.4 - Apprenticeship Requirements.

3. Section 1777.5 - Apprenticeship Requirements.

4. Section 1813 - Penalty for Failure to Pay Overtime.

5. Sections 1810 and 1811 - Working Hour Restrictions.

6. Section 1775 - Payroll Records.

7. Section 1773.8 - Travel and Subsistence Pay.

VII. RECORD AUDIT

In accordance with Government Code, Section 8546.7, records of both the CITY and the CONTRACTOR shall be subject to examination and audit by the Auditor General for a period of three (3) years after final payment.

VIII. FINAL PAYMENT

Final payment, constituting the entire unpaid balance of the Agreement Sum, shall be paid by the CITY to the CONTRACTOR no sooner than thirty-five (35) days after a Notice of Completion has been recorded, unless otherwise stipulated in the

Page 978 of 1492 ends
Page 4 of 13 ends

Notice of Completion, provided the work has then been completed, the Agreement fully performed, and a final Certificate for Payment has been issued by the Engineer.

IX. CONTRACTOR’S FAILURE TO PROCURE COMPLETION OF PROJECT

In the event CONTRACTOR fails to furnish tools, equipment, or labor in the necessary quantity or quality, or fails to prosecute the work or any part thereof contemplated by this Agreement in a diligent and workmanlike manner, and if the CONTRACTOR for a period of three (3) calendar days after receipt of written demand from CITY or its designated representative to do so, fails to furnish tools, equipment, or labor in the necessary quantity or quality, and to prosecute its work and all parts thereof in a diligent and workmanlike manner, or after commencing to do so within said three (3) calendar days, fails to continue to do so; then the CITY may exclude the CONTRACTOR from the premises, or any portion thereof, and take possession of said premises or any portion thereof, together with all material and equipment thereon, and may complete the work contemplated by this Agreement or any portion of said work, either by furnishing the tools, equipment, labor or material necessary, or by letting the unfinished portion of said work, or the portion taken over by the CITY to another contractor or by a combination of such methods. In any event, the procuring of the completion of said work, or the portion thereof taken over by the CITY, shall be a charge against the CONTRACTOR, and may be deducted from any money due or becoming due to CONTRACTOR from the CITY, or the CONTRACTOR shall pay the CITY the amount of said charge, or the portion thereof unsatisfied. The sureties, provided for under this Agreement shall become liable for payment should CONTRACTOR fail to pay in full any said cost incurred by the CITY.

X. INSURANCE

Prior to the beginning of and throughout the duration of the Project, CONTRACTOR and its subcontractors shall maintain insurance in conformance with the requirements set forth below. Attached hereto as Exhibit C are copies of Certificates of Insurance and the waiver of subrogation endorsement as required by Section 6.B.1. CONTRACTOR will use existing coverage to comply with these requirements. If that existing coverage does not meet the requirements set forth herein, CONTRACTOR agrees to amend, supplement or endorse the existing coverage to do so.

CONTRACTOR acknowledges that the insurance coverage and policy limits set forth in this section constitute the minimum amount of coverage required. Any insurance proceeds available to CONTRACTOR or its subcontractors in excess of the limits and coverage identified in this Agreement and which is applicable to a given loss, claim or demand, will be equally available to CITY.

A. Types of Insurance

Page 979 of 1492 ends
Page 5 of 13 ends

Without limiting CONTRACTOR’s indemnification of CITY, and prior to commencement of Work, CONTRACTOR shall obtain, provide and maintain at its own expense during the term of this Agreement, policies of insurance of the type and amounts described below and in a form satisfactory to CITY:

1. General liability insurance. CONTRACTOR shall maintain commercial general liability insurance with coverage at least as broad as Insurance Services Office form CG 00 01, in an amount not less than $1,000,000 per occurrence, $2,000,000 general aggregate, for bodily injury, personal injury, and property damage, and a $2,000,000 completed operations aggregate. The policy must include contractual liability that has not been amended. Any endorsement restricting standard ISO “insured contract” language will not be accepted.

2. Automobile liability insurance. CONTRACTOR shall maintain automobile insurance at least as broad as Insurance Services Office form CA 00 01 covering bodily injury and property damage for all activities of the CONTRACTOR arising out of or in connection with Work to be performed under this Agreement, including coverage for any owned, hired, non-owned or rented vehicles, in an amount not less than $1,000,000 combined single limit for each accident.

3. Umbrella or excess liability insurance. If CONTRACTOR is using umbrella coverage to meet part of its liability insurance requirements under Paragraph 1 of this Section, CONTRACTOR shall obtain and maintain an umbrella or excess liability insurance that will provide bodily injury, personal injury, completed operations and property damage liability coverage at least as broad as the primary coverages set forth above, including commercial general liability and employer’s liability.

Such policy or policies shall include the following terms and conditions:

• A drop down feature requiring the policy to respond in the event that any primary insurance that would otherwise have applied proves to be uncollectable in whole or in part for any reason; • Pay on behalf of wording as opposed to reimbursement; • Concurrency of effective dates with primary policies; • Policies shall “follow form” to the underlying primary policies; and • Insureds under primary policies shall also be insureds under the umbrella or excess policies.

4. Workers’ compensation insurance. CONTRACTOR shall maintain Workers’ Compensation Insurance (Statutory Limits) and Employer’s Liability Insurance (with limits of at least $1,000,000) for CONTRACTOR’s employees in accordance with the laws of the State of California, Section 3700 of the Labor Code. In addition,

Page 980 of 1492 ends
Page 6 of 13 ends

CONTRACTOR shall require each subcontractor to similarly maintain Workers’ Compensation Insurance and Employer’s Liability Insurance in accordance with the laws of the State of California, Section 3700 for all of the subcontractor’s employees.

CONTRACTOR shall submit to CITY, along with the certificate of insurance, a Waiver of Subrogation endorsement in favor of CITY, its officers, agents, employees and volunteers.

5. Pollution liability insurance. Environmental Impairment Liability Insurance shall be written on a CONTRACTOR’s Pollution Liability form or other form acceptable to CITY providing coverage for liability arising out of sudden, accidental and gradual pollution and remediation. The policy limit shall be no less than $1,000,000 dollars per claim and in the aggregate. All activities contemplated in this Agreement shall be specifically scheduled on the policy as “covered operations.” The policy shall provide coverage for the hauling of waste from the project site to the final disposal location, including non-owned disposal sites.

Products/completed operations coverage shall extend a minimum of three (3) years after project completion. Coverage shall be included on behalf of the insured for covered claims arising out of the actions of independent contractors. If the insured is using subcontractors, the Policy must include work performed “by or on behalf” of the insured. Policy shall contain no language that would invalidate or remove the insurer’s duty to defend or indemnify for claims or suits expressly excluded from coverage. Policy shall specifically provide for a duty to defend on the part of the insurer. The CITY, its officials, officers, agents, and employees, shall be included as insureds under the policy.

6. Builder’s risk insurance. Upon commencement of construction and with approval of CITY, CONTRACTOR shall obtain and maintain builder’s risk insurance for the entire duration of the Project until only the CITY has an insurable interest. The Builder’s Risk coverage shall include the coverages as specified below.

The named insureds shall be CONTRACTOR and CITY, including its officers, officials, employees, and agents. All Subcontractors (excluding those solely responsible for design Work) of any tier and suppliers shall be included as additional insureds as their interests may appear.

CONTRACTOR shall not be required to maintain property insurance for any portion of the Project following transfer of control thereof to CITY.

The policy shall contain a provision that all proceeds from the builder’s risk policy shall be made payable to the CITY. The CITY will act as a fiduciary for all other interests in the Project.

Page 981 of 1492 ends
Page 7 of 13 ends

Policy shall be provided for replacement value on an “all risk” basis for the completed value of the project. There shall be no coinsurance penalty or provisional limit provision in any such policy. Policy must include: (1) coverage for any ensuing loss from faulty workmanship, Nonconforming Work, omission or deficiency in design or specifications; (2) coverage against machinery accidents and operational testing; (3) coverage for removal of debris, and insuring the buildings, structures, machinery, equipment, materials, facilities, fixtures and all other properties constituting a part of the Project; (4) Ordinance or law coverage for contingent rebuilding, demolition, and increased costs of construction; (5) transit coverage (unless insured by the supplier or receiving contractor), with sub-limits sufficient to insure the full replacement value of any key equipment item; (6) Ocean marine cargo coverage insuring any Project materials or supplies, if applicable; (7) coverage with sub-limits sufficient to insure the full replacement value of any property or equipment stored either on or off the Site or any staging area. Such insurance shall be on a form acceptable to CITY to ensure adequacy of terms and sublimits and shall be submitted to the CITY prior to commencement of construction.

B. Other provisions or requirements

1. Proof of insurance. CONTRACTOR shall provide certificates of insurance to CITY as evidence of the insurance coverage required herein, along with a waiver of subrogation endorsement for workers’ compensation. Insurance certificates and endorsements must be approved by CITY’s risk manager prior to commencement of performance. Current certification of insurance shall be kept on file with CITY at all times during the term of this contract. CITY reserves the right to require complete, certified copies of all required insurance policies, at any time.

2. Duration of coverage. CONTRACTOR shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damages to property, which may arise from or in connection with the performance of the Work hereunder by CONTRACTOR, his agents, representatives, employees or subcontractors. CONTRACTOR must maintain general liability and umbrella or excess liability insurance for as long as there is a statutory exposure to completed operations claims. CITY and its officers, officials, employees, and agents shall continue as additional insureds under such policies.

3. Primary/noncontributing. Coverage provided by CONTRACTOR shall be primary and any insurance or self-insurance procured or maintained by CITY shall not be required to contribute with it. The limits of insurance required herein may be satisfied by a combination of primary and

Page 982 of 1492 ends
Page 8 of 13 ends

umbrella or excess insurance. Any umbrella or excess insurance shall contain or be endorsed to contain a provision that such coverage shall also apply on a primary and non-contributory basis for the benefit of CITY before the CITY’s own insurance or self-insurance shall be called upon to protect it as a named insured.

4. CITY’s rights of enforcement. In the event any policy of insurance required under this Agreement does not comply with these requirements or is canceled and not replaced, CITY has the right but not the duty to obtain the insurance it deems necessary and any premium paid by CITY will be promptly reimbursed by CONTRACTOR or CITY will withhold amounts sufficient to pay premium from CONTRACTOR payments. In the alternative, CITY may cancel this Agreement.

5. Acceptable insurers. All insurance policies shall be issued by an insurance company currently authorized by the Insurance Commissioner to transact business of insurance or is on the List of Approved Surplus Line Insurers in the State of California, with an assigned policyholders’ Rating of A- (or higher) and Financial Size Category Class VII (or larger) in accordance with the latest edition of Best’s Key Rating Guide, unless otherwise approved by the CITY’s risk manager.

6. Waiver of subrogation. All insurance coverage maintained or procured pursuant to this agreement shall be endorsed to waive subrogation against CITY, its elected or appointed officers, agents, officials, employees and volunteers or shall specifically allow CONTRACTOR or others providing insurance evidence in compliance with these specifications to waive their right of recovery prior to a loss.

CONTRACTOR hereby waives its own right of recovery against CITY, and shall require similar written express waivers and insurance clauses from each of its subconsultants.

7. Enforcement of contract provisions (non estoppel). CONTRACTOR acknowledges and agrees that any actual or alleged failure on the part of the CITY to inform CONTRACTOR of non-compliance with any requirement imposes no additional obligations on the CITY nor does it waive any rights hereunder.

8. Requirements not limiting. Requirements of specific coverage features or limits contained in this Section are not intended as a limitation on coverage, limits or other requirements, or a waiver of any coverage normally provided by any insurance. Specific reference to a given coverage feature is for purposes of clarification only as it pertains to a given issue and is not intended by any party or insured to be all inclusive, or to the exclusion of other coverage, or a waiver of any type.

Page 983 of 1492 ends
Page 9 of 13 ends

If the CONTRACTOR maintains higher limits than the minimums shown above, the CITY requires and shall be entitled to coverage for the higher limits maintained by the CONTRACTOR. Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to the CITY.

9. Notice of cancellation. CONTRACTOR agrees to oblige its insurance agent or broker and insurers to provide to CITY with a thirty (30) day notice of cancellation (except for nonpayment for which a ten (10) day notice is required) or nonrenewal of coverage for each required coverage.

10. Additional insured status. General liability policies shall provide or be endorsed to provide that CITY and its officers, officials, employees, agents, and volunteers shall be additional insureds under such policies.

This provision shall also apply to any excess/umbrella liability policies.

11. Prohibition of undisclosed coverage limitations. None of the coverages required herein will be in compliance with these requirements if they include any limiting endorsement of any kind that has not been first submitted to CITY and approved of in writing.

12. Separation of insureds. A severability of interests provision must apply for all additional insureds ensuring that CONTRACTOR’s insurance shall apply separately to each insured against whom claim is made or suit is brought, except with respect to the insurer’s limits of liability. The policy(ies) shall not contain any cross-liability exclusions.

13. Pass through clause. CONTRACTOR agrees to ensure that its subconsultants, subcontractors, and any other party involved with the project who is brought onto or involved in the project by CONTRACTOR, provide the same minimum insurance coverage and endorsements required of CONTRACTOR. CONTRACTOR agrees to monitor and review all such coverage and assumes all responsibility for ensuring that such coverage is provided in conformity with the requirements of this section. CONTRACTOR agrees that upon request, all agreements with consultants, subcontractors, and others engaged in the project will be submitted to CITY for review.

14. CITY’s right to revise requirements. The CITY reserves the right at any time during the term of the contract to change the amounts and types of insurance required by giving the CONTRACTOR a ninety (90) day advance written notice of such change. If such change results in substantial additional cost to the CONTRACTOR, the CITY and CONTRACTOR may renegotiate CONTRACTOR’s compensation.

Page 984 of 1492 ends
Page 10 of 13 ends

15. Self-insured retentions. Any self-insured retentions must be declared to and approved by CITY. CITY reserves the right to require that self- insured retentions be eliminated, lowered, or replaced by a deductible.

Self-insurance will not be considered to comply with these specifications unless approved by CITY.

16. Timely notice of claims. CONTRACTOR shall give CITY prompt and timely notice of claims made or suits instituted that arise out of or result from CONTRACTOR’s performance under this Agreement, and that involve or may involve coverage under any of the required liability policies.

17. Additional insurance. CONTRACTOR shall also procure and maintain, at its own cost and expense, any additional kinds of insurance, which in its own judgment may be necessary for its proper protection and prosecution of the Work.

XI. CONTRACTOR’S LICENSE

CONTRACTOR must possess at the time of commencing work and throughout the Project duration, a Contractor’s License, issued by the State of California, which is current and in good standing. CONTRACTOR shall ensure that any subcontractor working on the Project possesses at the time of commencing work and throughout the Project duration, a Contractor’s License, issued by the State of California, which is current and in good standing.

XII. REGISTRATION REQUIREMENTS

A. Pursuant to Section 1771.1(a) of the Labor Code:

“A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.”

B. CONTRACTOR must be registered with the Department of Industrial Relations (DIR) of the State of California in order to be eligible to work on public works projects. CONTRACTOR must ensure registration with the DIR that is active and in good standing.

Page 985 of 1492 ends
Page 11 of 13 ends

C. No contractor or subcontractor may be listed on a bid proposal for a public works project (submitted on or after March 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].

No contractor or subcontractor may be awarded a contract for public work on a public works project (awarded on or after April 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5.

This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.

D. The CONTRACTOR is not subject to public works requirements (including registration with the DIR) if the public works project is under $1,000, unless the CITY knows that the same CONTRACTOR will be awarded total project costs in excess of $1,000 for a given year.

Page 986 of 1492 ends
Page 12 of 13 ends

XIII. CORPORATION IN GOOD STANDING

If CONTRACTOR is a corporation, the undersigned hereby represents and warrants that the corporation is duly incorporated and in good standing in the State of California, and that _______ whose title is President is authorized to act for and bind the corporation.

XIV. PROVISIONS REQUIRED BY LAW

Each and every provision of law and clause required by law to be inserted in this Agreement shall be deemed to be inserted herein and the Agreement shall be read and enforced as though it were included herein, and if through mistake or otherwise any such provision is not inserted, or is not currently inserted, then upon application of either party the Agreement shall forthwith be physically amended to make such insertion or correction.

XV. SUBSURFACE HAZARDOUS MATERIALS

A. In the event trenches or other excavations extend deeper than four (4) feet below the surface, the CONTRACTOR shall promptly, and before the following conditions are disturbed, notify the CITY in writing of any:

1. Material that the CONTRACTOR believes may be material that is hazardous waste, as defined in Section 25117 of the Health and Safety Code that is required to be removed to a Class I, Class II or Class III disposal site in accordance with the provisions of existing law.

2. Subsurface or latent physical conditions at the site differing from those indicated.

3. Unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in the Work or the character provided for in the CONTRACT.

B. Upon receipt of said notification the CITY will investigate the conditions, and if it finds that the conditions do materially so differ, or do involve hazardous waste, and cause a decrease or increase in the CONTRACTOR’s cost of or the time required for performance of any part of the work, the CITY will issue a change order under the procedures described in the General Conditions.

C. In the event that a dispute arises between the CITY and the CONTRACTOR whether the conditions materially differ, or involve hazardous waste or cause a decrease or increase in the CONTRACTOR’s cost of or time required for performance of any part of the work, the CONTRACTOR shall not be excused from any scheduled completion date provided for by the Agreement, but shall proceed with all work to be performed under the

Page 987 of 1492 ends
Page 13 of 13 ends

Agreement. The CONTRACTOR shall retain any and all rights provided either by Agreement or by law which pertain to the resolution of disputes and protests between the contracting parties.

XVI. COMPONENT PARTS OF THE CONTRACT

This Agreement entered into consists of the following CONTRACT DOCUMENTS, all of which are component parts of the Agreement as if herein set out in full or attached hereto:

Notice Inviting Bids
Scope of Work Summary
Information for Bidders
Bid Form
Non-Collusion Affidavit
Site Visit Certification
Faithful Performance Bond
Labor and Materials Payment
Bond
General and Supplemental
Conditions
Special Conditions
Project Construction Schedule
Proposed Subcontractors
Bid Bond
Information Required of Bidder
Construction Services Agreement
Certificate Regarding Worker’s
Compensation
Drug-free Workplace Certification
Plans and Specifications
Addenda
Drawings
Change Orders
Shop Drawing Transmittals
Contractor’s Certificate Regarding
Non-Asbestos Containing
Materials

All of the above named CONTRACT DOCUMENTS are intended to be complementary. Work required by one of the above named CONTRACT DOCUMENTS and not by others shall be done as if required by all.

XVII. ENTIRE CONTRACT

This Agreement constitutes the entire contract of the parties. No other agreements or contracts, whether oral or written, pertaining to the work to be performed, exists between the parties. This Agreement can be modified only by an amendment in writing, signed by both parties.

[Signatures on following page.]

Page 988 of 1492 ends

14 SIGNATURE PAGE TO

CITY OF BEAUMONT

PUBLIC WORKS AGREEMENT

CITY:

CITY OF BEAUMONT

By:
________________________________
Mayor
CONTRACTOR:

_____________________________

By: ______________________________

Print Name: _______________________

Title:
_____________________________

Page 989 of 1492 ends

15 CITY OF BEAUMONT

PUBLIC WORKS AGREEMENT

EXHIBIT “A”

CITY’S INVITATION FOR BIDS

(Insert behind this page.)

Page 990 of 1492 ends

16 CITY OF BEAUMONT

PUBLIC WORKS AGREEMENT

EXHIBIT “B”

CONTRACTOR’S Bid

(Insert behind this page.)

Page 991 of 1492 ends

17 CITY OF BEAUMONT

PUBLIC WORKS AGREEMENT

EXHIBIT “C”

Insurance Certificates and Endorsements

(Insert behind this page.)

Page 992 of 1492 ends

City of Beaumont
Request for bid Mesa Lift Station Force Main
CIP WW-09

43 07 APPENDICES
CIP WW-09 BEAUMONT MESA LIFT STATION FORCE MAIN

Page 993 of 1492 ends

City of Beaumont
Request for bid

Mesa Lift Station Force Main
CIP WW-09

APPENDICES
1 APPENDICES

TABLE OF CONTENTS
APPENDIX A – CLARIFIED MMRP ........................................................................................ 1 APPENDIX B – FORCE MAIN ASBUILTS .............................................................................. 2 APPENDIX C – QST IMPACTED PROJECT REQUIREMENTS ............................................. 3 APPENDIX D – APPROVED PLUG VALVES ......................................................................... 4 APPENDIX E – POTHOLE REPORTS ................................................................................... 5 APPENDIX F – VARIOUS STANDARD DRAWINGS .............................................................. 6 APPENDIX G – PRESSURE TESTING SCOPE ..................................................................... 7 APPENDIX H – FORCE MAIN BYPASS EXHIBIT .................................................................. 8 APPENDIX I – GEOTECHNICAL REPORTS .......................................................................... 9

Page 994 of 1492 ends

City of Beaumont
Request for bid

Mesa Lift Station Force Main
CIP WW-09

APPENDICES
1 APPENDIX A – CLARIFIED MMRP

Page 995 of 1492 ends

CLARIFIED MITIGATION MONITORING AND REPORTING PROGRAM
FOR
Mesa Lift Station and Force Main Project

SCH# 2018011029

Prepared for

City of Beaumont
550 East 6th Street
Beaumont, CA 92223

Contact: Dustin Christensen, Principal Engineer
(951) 572-3192

December 2022

Page 996 of 1492 ends

Clarified Mitigation Monitoring and Reporting Program
Mesa Lift Station and Force Main Project

Clarified MMRP-1

PROJECT DESCRIPTION
In accordance with the California Environmental Quality Act (CEQA) (Public Resources Code Sections 21000–21177), the City of Beaumont (hereinafter “the City”), as Lead Agency, approved prepared a Initial Study/ Mitigated Negative Declaration for the Beaumont Water Treatment Plant Upgrade/Expansion and Brine Pipeline (State Clearinghouse No. 2018011029), which was circulated for a 30-day public review period from January 18, 2018 to February 16, 2018, pursuant to State CEQA Guidelines Section 15073 (hereinafter the “Beaumont WWTP MND”). The Beaumont WWTP MND and a Mitigation Monitoring and Reporting Program (MMRP) were approved by the Beaumont City Council on March 20, 2018. The City approved a modified MMRP on March 15, 2019.

The Beaumont Wastewater Treatment Plant Upgrade/Expansion and Brine Pipeline Project (hereinafter “the Beaumont WWTP Project”) evaluated in the Beaumont WWTP MND, includes two components: first, the expansion and upgrade of the Beaumont Waste Water Treatment Plant (WWTP); and second, the construction of a brine disposal pipeline from the Beaumont WWTP to the nearest connection point of the Inland Empire Brine Line (IEBL) located near the City of San Bernardino Water Reclamation Plant. The brine disposal pipeline was evaluated to run from the Beaumont WWTP and traverse west along W. 4th Street to the end of the existing pavement where the brine pipeline will continue north along a dirt road, where it will then cross underneath the SR-60 to Western Knolls Avenue. Alternate alignments were considered to run south of SR-60 include using Nicholas Road, and several currently unnamed roads/dirt paths, after crossing the SR-60, the brine pipeline will continue west within the future realignment of Western Knolls Avenue where it will turn north within Potrero Boulevard
Addendum No. 1 to the Beaumont WWTP MND analyzes the impacts associated with construction and operation of the Mesa Lift Station and Force Main project (hereinafter the “Lift Station and Force Main Project”) The Lift Station and Force Main Project proposes upgrades and improvements to the existing Mesa Lift Station and two segments of 16- inch diameter wastewater pipeline. The Lift Station site and proposed alignment of the Force Main alignment is adjacent to the brine pipeline component of the Beaumont WWTP Project. The purpose of the Lift Station and Force Main Project is to provide sufficient redundancy and storage to avoid wastewater backups and overflows from existing and future growth consistent with the Beaumont 2040 Plan.

Certain mitigation measures required of the Beaumont WTP MMD are not applicable to the Lift Station and Force Main project or have already been satisfied. Therefore, this clarified Mitigation Monitoring and reporting program (Clarified MMRP) has been prepared. None of the revisions to the mitigation measures change the intent or outcome of the mitigation measures contained in the modified MMRP approved March 15, 2019.

Pursuant to State CEQA Guidelines Section 15097, this Clarified MMRP consists of a written monitoring and reporting program to verify implementation of adopted mitigation measures. The Clarified MMRP is set up as a compliance report with space for confirming compliance with the mitigation measures.

Page 997 of 1492 ends

Clarified Mitigation Monitoring and Reporting Program
Mesa Lift Station and Force Main Project

Clarified MMRP-2

CLARIFIED MITIGATION MONITORING AND REPORTING PROGRAM
The enclosed Clarified Mitigation Monitoring and Reporting Program (MMRP) has been compiled to verify implementation of adopted mitigation measures. The following table provides a summary format based on the written report, including all mitigation measures, the timing of mitigation implementation, identification of the responsible monitoring party, and verification of implementation of each mitigation measure.

The following clarifies the meaning of each column in the following table:

Impact Category: Identifies potentially affected resource/ environmental condition.

Mitigation Measure: Those measures that will be implemented to minimize possible significant environmental impacts.

Implementing Timing: The phase of the project in which implementation and compliance will be monitored.

Responsible Monitoring Party: Entity responsible for monitoring implementation of the mitigation measure.

Monitoring/Reporting Method: Identifies mechanism by which implementation will be verified.

Compliance Verification: To be signed and dated by the City of Beaumont Public Works Department upon receipt of written verification of each mitigation measure.

Page 998 of 1492 ends

Clarified Mitigation Monitoring and Reporting Program
Mesa Lift Station and Force Main Project

Clarified MMRP-3

Impact
Category Mitigation Measure
Implementation
Timing
Responsible
Monitoring
Party
Monitoring/
Reporting
Method Compliance Verification
Aesthetics MM AES-1. Nighttime Lighting: Prior to any
nighttime construction, the construction contractor
shall provide evidence to the City Public Works
Department that any temporary nighttime lighting
shall be downward facing and hooded or shielded to
prevent light spillage outside of the construction
area or direct broadcast of light into the sky.

Prior to
nighttime
construction.

Contractor
Beaumont
Public Works
Dept.

Submittal of proof
that nighttime
lighting faces
down and
hooded.

Air Quality MM AQ-1. Certified Tier 3 Engines: During brine pipeline construction activities, all heavy-duty
construction equipment over 50 horsepower (hp)
shall be certified to meet or exceed United States
Environmental Protection Agency (USEPA) Tier 3
engine standards. Proof of compliance shall be
provided in the bid specifications and be verified by
the Department of Public Works prior to issuance of
construction.

Beaumont WWTP MND mitigation measure MM AQ-1 is not applicable to the Lift Station and Force Main Project because construction impacts will not exceed SCAQMD thresholds.

Biological
Resources
CMM BIO-1. Biological Resources Worker
Environmental Awareness Program: Prior to
construction, a qualified biologist (the “Project
Biologist”) shall be retained by the City of Beaumont
to prepare a Biological Resources Worker
Environmental Awareness Program (Biological
Resources WEAP) that will outline pertinent
biological issues and avoidance measures related to
the project sites and surrounding areas. Such
measures will include making sure construction
workers and equipment stay out of sensitive
vegetation communities and special-status species
During
preconstruction
meeting for
each crew
working on the
WWTP and
brine pipeline.

Project
Biologist
Contractor
Beaumont
Public Works
Dept.

Submittal of
WEAP presented
to each crew.

Page 999 of 1492 ends

Clarified Mitigation Monitoring and Reporting Program
Mesa Lift Station and Force Main Project

Clarified MMRP-4
Impact
Category Mitigation Measure
Implementation
Timing
Responsible
Monitoring
Party
Monitoring/
Reporting
Method Compliance Verification
or nesting bird habitat. The Project Biologist or
designee(s) shall present the Biological Resources
WEAP to the construction contractor and each of
the construction crews working on the Lift Station
and Force Main Project during a preconstruction
meeting. The training shall be taped and presented
to any construction crew members not present at
the preconstruction meeting during which it was
initially presented prior to working at the Lift Station Site or along the Force Main Alignment
Biological
Resources
CMM BIO-2. Preconstruction Survey(s) and
Biological Monitoring: In order to determine the
presence of active nests if work must be done
during the breeding season (March 1 through August
31), the City of Beaumont shall retain a qualified
biologist (the “Project Biologist”) to perform
preconstruction surveys in potential nesting areas
three days or less prior to disturbance. If active
nests are documented, species-specific measures,
as determined by the Project Biologist, shall be
implemented to prevent abandonment of the active
nest. including but not limited to, installation of
barriers. If construction begins in the non-breeding
season, but extends into the breeding season,
nesting bird surveys shall be conducted prior to
moving into the new areas. In areas where work is
already active, any birds building adjacent nests
shall be presumed to be unconcerned by the
activity, but the Biological Monitor shall be
Between March
and August,
prior to
construction-
related ground
disturbances
that are within
500-feet of
riparian habitat.

Project
Biologist
Beaumont
Public Works
Department.

Pre-construction
surveys
Evidence of
installation of
sound barriers, if
needed.

Report of findings
submitted to the
City.

Page 1000 of 1492 ends

Clarified Mitigation Monitoring and Reporting Program
Mesa Lift Station and Force Main Project

Clarified MMRP-5
Impact
Category Mitigation Measure
Implementation
Timing
Responsible
Monitoring
Party
Monitoring/
Reporting
Method Compliance Verification
responsible for preventing impacts to them by
stopping work or establishing buffers as needed.

To minimize impacts to special status plant species,
the Project Biologist shall flag areas where special
status species occur and those areas shall be
avoided during construction. In the event avoidance
to special-status plant species is not possible, the
Project Biologist shall collect seeds from the
plant(s), remove the plant, and then spread the
collected seeds back into the same area after
construction.

Full time biological monitoring is not required;
however, depending on the environmental
conditions where the crew(s) are working, there may
be cases where a monitor is required all day or
temporarily for a morning sweep of the site.

Biological
Resources
MM BIO-3. Work on Bridges: Work on bridges
shall occur strictly in the non-breeding season
(September 1st to January 31st). In the event that
work on bridges during the breeding season cannot
be avoided, the City of Beaumont shall retain a
qualified biologist to oversee that bird exclusion
netting is installed by a qualified professional during the non-breeding season to prevent nesting on
bridges. Netting may also exclude bats. In either
scenario, regular biological monitoring will be
required at bridge crossings to ensure that birds and
bats are not present and/or that exclusionary
devices are maintained and functioning correctly.

Beaumont WWTP MND mitigation measure MM BIO-3 is not applicable to the Lift Station and Force Main Project because no work will be done on bridges.

Page 1001 of 1492 ends

Clarified Mitigation Monitoring and Reporting Program
Mesa Lift Station and Force Main Project

Clarified MMRP-6
Impact
Category Mitigation Measure
Implementation
Timing
Responsible
Monitoring
Party
Monitoring/
Reporting
Method Compliance Verification
Exclusionary devices shall be removed upon
completion of work at the bridge.

Biological
Resources
MM BIO-4. Roosting Bats: A qualified biologist
shall perform a preconstruction survey for suitable
roosting habitat for special-status bats that will be
affected by Project construction (e.g., modification
of bridges). Survey shall be done during the
appropriate time of day to maximize detectability to
determine if bat species are roosting near the work
area no less than 7 days and no more than 14 days
prior to beginning ground disturbance and/or
construction. Survey methodology may include
visual surveys of bats (e.g., observation of bats
during foraging period), inspection for suitable
habitat, bat sign (e.g., guano), or use of ultrasonic
detectors (e.g., Anabat, etc.). Visual surveys will
include trees within 0.25 mile of Project construction
activities. The type of survey will depend on the
condition of the potential roosting habitat. If no bat
roosts are found, then no further study is required.

If evidence of bat use is observed, the number and
species of bats using the roost will be determined.

Bat detectors may be used to supplement survey
efforts.

If roosts are determined to be present and must be
removed, the bats will be excluded from the roosting
site before the facility is removed. The surveying
biologist shall develop a plan addressing
compensation, exclusion methods, and roost
Beaumont WWTP MND mitigation measure MM BIO-4 is not applicable to the Lift Station and Force Main Project because there is no suitable bat habitat at the Lift Station or along the Force Main Alignment.

Page 1002 of 1492 ends

Clarified Mitigation Monitoring and Reporting Program
Mesa Lift Station and Force Main Project

Clarified MMRP-7
Impact
Category Mitigation Measure
Implementation
Timing
Responsible
Monitoring
Party
Monitoring/
Reporting
Method Compliance Verification
removal procedures prior to implementation.

Exclusion methods may include use of one-way
doors at roost entrances (bats may leave, but not
reenter), netting, or sealing roost entrances when the
site can be confirmed to contain no bats. Exclusion
efforts may be restricted during periods of sensitive
activity (e.g., during hibernation or while females in
maternity colonies are nursing young).

If roosts of special-status bats cannot be avoided or
it is determined that construction activities may
cause roost abandonment, such activities may not
commence until permanent, elevated bat houses
have been installed outside of, but near the
construction area. Placement and height will be
determined by a qualified biologist, but the height of
bat house will be at least 15 feet. Bat houses will be
multi-chambered and be purchased or constructed
in accordance with CDFW standards. The number of
bat houses required will be dependent upon the size
and number of colonies found, but at least one bat
house will be installed for each pair of bats (if
occurring individually), or of sufficient number to
accommodate each colony of bats to be relocated.

Biological
Resources
MM BIO-5. Preconstruction surveys:

Preconstruction surveys for the pipeline located in
San Bernardino County shall be conducted within
30-days of construction for the following habitat
areas:

Beaumont WWTP MND mitigation measure MM BIO-5 is not applicable to the Lift Station and Force Main Project because no work will be done in San Bernardino County.

Page 1003 of 1492 ends

Clarified Mitigation Monitoring and Reporting Program
Mesa Lift Station and Force Main Project

Clarified MMRP-8
Impact
Category Mitigation Measure
Implementation
Timing
Responsible
Monitoring
Party
Monitoring/
Reporting
Method Compliance Verification

1. Ponded areas: If any ponded areas are
encountered during the preconstruction surveys
they should be flagged for avoidance for impacts
to western spadefoot toad.

2. Stephen’s Kangaroo Rat and San Bernardino
Kangaroo Rat Burrows: If burrows suitable for
kangaroo rats are encountered, they should be
flagged and avoided. If pedestrian or vehicle
activity is required in the area of the burrow,
load-spreading devices (e.g., one-inch plywood)
shall be placed temporarily over the burrows to
prevent burrow collapse.

For the pipeline located in both Riverside and San
Bernardino County, the following preconstruction
surveys will be conducted within 30-days of
construction:

3. Badger Burrows: If burrows suitable for the
American badger are detected during the
preconstruction surveys, they should be flagged
and avoided.

Biological
Resources
MM BIO-6. Work in Critical Habitat: If
construction equipment is required within a water of
the U.S. containing federally listed species or critical habitat for federally listed species, the City shall
transmit a pre-construction notification (PCN) to the
U.S. Army Corps of Engineers pursuant to the Clean
Water Act Section 404 Nationwide Permit program
(General Condition 18) to provide notice of
construction activities within designated Critical
Beaumont WWTP MND mitigation measure MM BIO-6 is not applicable to the Lift Station and Force Main Project because no work will be done in Critical Habitat

Page 1004 of 1492 ends

Clarified Mitigation Monitoring and Reporting Program
Mesa Lift Station and Force Main Project

Clarified MMRP-9
Impact
Category Mitigation Measure
Implementation
Timing
Responsible
Monitoring
Party
Monitoring/
Reporting
Method Compliance Verification
Habitat for federally listed species. No construction
shall commence until the City of Beaumont is
notified by the Corps that the requirements of the
Endangered Species Act have been satisfied and
that the activity is authorized.

Biological
Resources
CMM BIO-7. Work in Jurisdictional Waters: The
project is being designed to avoid impacts to
wetlands and jurisdictional areas. If construction
activities should disturb anywhere within the
jurisdictional limits of a watercourse, the following
shall apply as needed: a) notification of a lake or
streambed alteration (LSA) shall be given to the
California Department of Fish and Wildlife (CDFW);
b) a request shall be made to the Santa Ana River
Regional Water Quality Control Board for a Clean
Water Act Section 401 Water Quality Certification
(WQC); and/or c) pre-construction notification to the
Los Angeles District of the U.S. Army Corps of
Engineers. In the event trenchless methods of
construction are used the contractor shall prepare
and have on-site during hydraulic directional drilling
(HDD), a Frac-Out Contingency Plan in the event the
pipeline breeches or frac-out occurs. The Frac-Out
Contingency Plan shall identify the methods to
contain released material into the waterway and
identify the agencies that will be contacted should
frac-out occurs.

Prior to
construction
City staff Record of
submittals and
approvals.

Copy of Frac-Out
Contingency
Plan, if needed.

Page 1005 of 1492 ends

Clarified Mitigation Monitoring and Reporting Program
Mesa Lift Station and Force Main Project

Clarified MMRP-10
Impact
Category Mitigation Measure
Implementation
Timing
Responsible
Monitoring
Party
Monitoring/
Reporting
Method Compliance Verification
Biological
Resources
CMM BIO-8. Preconstruction Burrowing Owl
Surveys: Preconstruction burrowing owl survey(s)
pursuant to the MSHCP shall take place within 30-
days prior to any vegetation removal, grading or any
other disturbance to the Lift Station Site and Force
Main Project Alignment. If owls are found during the
preconstruction survey(s), the City shall ensure that
a relocation plan be prepared and approved by the
Regional Conservation Authority before disturbance
occurs. These preconstruction surveys for burrowing
owl can be conducted during the same time period
as any other preconstruction surveys needed for the
project.

Within 30-days
prior to any
vegetation
removal,
grading or any
other
disturbance to
the Lift Station
Site and Force
Main Project
Alignment
Qualified
biologist
Record of
preconstruction
surveys.

Copy of
relocation plan
and approvals, if
needed.

Biological
Resources
MM BIO-9. Smooth Tarplant: The City shall hire a
qualified biologist to monitor construction activities
in the El Casco area in areas of mapped saline-alkali
soils as depicted on Figure 7 of the AMEC HSA. The
biologist will advise the construction team on how to
avoid any smooth tarplants, if possible. If avoidance
is not possible, then the biologist will collect seeds
from the plant(s), remove the plant, and then spread
the collected smooth tarplant seeds back into the
same area after construction.

Beaumont WWTP MND mitigation measure MM BIO-9 is not applicable to the Lift Station and Force Main Project because no work will be done in the El Casco area in areas of mapped saline alkali soils.

Cultural
Resources
CMM CR-1: Archaeological and Native American
Monitors. The City of Beaumont shall retain a
qualified archaeologist (the “Project Archaeologist”)
and a Tribal Monitor from the Morongo Band of
Mission Indians (the “MBMI Tribal Monitor) who shall
monitor initial ground disturbing activities along the
Prior to and
during all
ground-
disturbing
activities.

Project
Archaeologist
MBMI Tribal
Monitor
City staff
Monitoring results
to the City.

Record of
significance
meeting and

Page 1006 of 1492 ends

Clarified Mitigation Monitoring and Reporting Program
Mesa Lift Station and Force Main Project

Clarified MMRP-11
Impact
Category Mitigation Measure
Implementation
Timing
Responsible
Monitoring
Party
Monitoring/
Reporting
Method Compliance Verification
Force Main Alignment. In the event that potentially
significant archaeological materials are encountered,
all ground disturbance activities within 100 feet of
the discovered cultural resource shall be halted and
an Environmentally Sensitive Area (ESA) physical
demarcation/barrier constructed. The contractor
shall call the City of Beaumont Public Works
Department, the Project Archaeologist, and the
MBMI Tribal Monitor immediately upon discovery of
the cultural resource. A meeting shall be convened
between the City Public Works Department and/or
City Planning Department, the Project Archaeologist,
the MBMI Tribal Monitor, and the Morongo Tribal
Historic Preservation Officer, to discuss the
significance of the find. At the meeting with the
aforementioned parties, a decision is to be made,
with the concurrence of the Project Archaeologist
and the Morongo Tribal Historic Preservation Officer
as to the appropriate treatment (documentation,
recovery, avoidance, etc.) and disposition for the
cultural resource. Further ground disturbance shall
not resume within the area of the discovery until the
appropriate treatment has been accomplished.

Monitoring may be discontinued as soon the Project
Archaeologist and the MBMI Tribal Monitor are
satisfied that construction will not disturb cultural
resources.
decision made, if
needed.

Evidence that
artifact treatment
is complete, if
needed.

Determination to
the City that
monitoring can
be discontinued,
if warranted.

Cultural
Resources
MM CR-2: Worker’s Environmental Awareness
Training. Prior to the start of construction, the City
of Beaumont shall retain a Project Archaeologist and
Prior to
construction
during each
Project
Archaeologist
Evidence to the
City of training
provided.

Page 1007 of 1492 ends

Clarified Mitigation Monitoring and Reporting Program
Mesa Lift Station and Force Main Project

Clarified MMRP-12
Impact
Category Mitigation Measure
Implementation
Timing
Responsible
Monitoring
Party
Monitoring/
Reporting
Method Compliance Verification
MBMI Tribal Monitor (see mitigation measure
CMM CR-1) and qualified paleontologist (the Project
Paleontologist) to provide a preconstruction training
for the Project construction contractor and
construction crews. The Project Archaeologist and
city shall invite the MBMI Tribal Monitor to provide
input during the training. The training shall identify
the types of archaeological resources and fossils
that could be found in the area (particularly fossils
that can be found in the San Timoteo Formation and
Pleistocene alluvial fan and axial channel deposits),
the procedures to follow should archaeological
and/or paleontological resources be encountered
and contact information for the Project
Archaeologist, MBMI Tribal Monitor, and Project
Paleontologist and/or their designee(s).

Paleontological information shall follow the Society
of Vertebrate Paleontology (2010) guidelines. The
training shall be taped and presented to any
construction crew members not present at the
preconstruction meeting during which it was initially
presented prior to working at the Lift Station Site or
along the Force Main Alignment. The training may be
conducted concurrently with other environmental
training (e.g., biological, safety training).
crew’s
preconstruction
meeting.

MBMI Tribal
Monitor
City staff
Cultural
Resources
MM CR-3: Inadvertent Paleontological Discovery.

Should any paleontological resource(s) be
accidentally discovered during construction,
construction activities shall be moved to other parts
of the construction site and a qualified
Beaumont WWTP MND mitigation measure MM CR-3 is not applicable to the Lift Station and Force Main Project because it is replaced by the functionally equivalent mitigation measures MM PALEO-1, MM PALEO-2, and MM PALEO-3.

Page 1008 of 1492 ends

Clarified Mitigation Monitoring and Reporting Program
Mesa Lift Station and Force Main Project

Clarified MMRP-13
Impact
Category Mitigation Measure
Implementation
Timing
Responsible
Monitoring
Party
Monitoring/
Reporting
Method Compliance Verification
paleontologist shall be retained to determine the
significance of the resource(s). If the find is
determined to be a unique paleontological resource,
as defined in Section 15064.5 of the State CEQA
Guidelines, then a mitigation program shall be
developed in accordance with the provisions of
CEQA as well as the guidelines of the Society of
Vertebrate Paleontology (2010).

The paleontologist (or designee(s)) shall wash any
collected samples of sediments to recover small
invertebrate and vertebrate fossils. Recovered
specimens shall be prepared so that they can be
identified and permanently preserved. Specimens
shall be identified and curated at a repository with
permanent retrievable storage to allow further
research in the future (e.g., Western Science Center,
Raymond Alf Museum, or the Natural History
Museum of Los Angeles County). The cost of
curation is assessed by the repository and is the
responsibility of the landowner. If specimens are
found, the qualified paleontologist shall prepare a
report of findings, including an itemized inventory of
recovered specimens, upon completion of all Project
fieldwork. The report shall include a discussion of
the significance of all recovered specimens. The
report and inventory, when submitted to the City of
Beaumont, shall signify completion of the program
to mitigate impacts to paleontological resources. If
the monitoring efforts produced fossils, then a copy

Page 1009 of 1492 ends

Clarified Mitigation Monitoring and Reporting Program
Mesa Lift Station and Force Main Project

Clarified MMRP-14
Impact
Category Mitigation Measure
Implementation
Timing
Responsible
Monitoring
Party
Monitoring/
Reporting
Method Compliance Verification
of the report will also be submitted to the curation
facility.

Cultural
Resources
MM CR-4: Paleontological Monitoring. Prior to the
start of construction along the pipeline alignment
between West Fern Avenue and the intersection of
Beaumont Avenue and San Timoteo Canyon Road in
the City of Redlands, the City of Beaumont shall
retain a Qualified Paleontologist for full-time
construction monitoring. This stretch of road may
have previously undisturbed deposits determined to
have a high paleontological sensitivity (i.e, the San
Timoteo Formation and Pleistocene alluvial and axial
channel deposits). Monitoring shall follow the
Society of Vertebrate Paleontology (2010) guidelines.

Monitoring should include the visual inspection of
excavated or graded areas, trench sidewalls, spoils,
and any other disturbed sediment. In the event that
a paleontological resource is discovered, the
procedures outlined in mitigation measure MM CR-3
shall apply. The approved paleontological monitor
will have the authority to halt or divert temporarily
the construction equipment around the find until it is
assessed for scientific significance and collected.

Paleontological monitoring can be reduced or
eliminated at the discretion of the Qualified
Paleontologist if no fossil resources are encountered
after 50 percent of the excavation along this stretch
is completed.

Beaumont WWTP MND mitigation measure MM CR-4 is not applicable to the Lift Station and Force Main Project because no work will be done in the City of Redlands.

Page 1010 of 1492 ends