A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF COSTA MESA ,
CALIFORNIA, APPROVING THE STATUS AND UPDATE OF THE PAVEMENT MANAGEMENT PLAN FOR THE MEASURE M2 (M2) PROGRAM
THE CITY COUNCIL OF THE CITY OF COSTA MESA, CALIFORNIA HEREBY FINDS, DETERMINES AND DECLARES AS FOLLOWS:
WHEREAS, the City is required to meet eligibility requirements and submit eligibility verification packages to Orange County Transportation Authority (OCTA) in order to remain eligible to receive M2 funds; and
WHEREAS, the City is required to adopt and update a Pavement Management Plan (PMP), using OCTA’s required format, regarding the status of road pavement conditions and implementation of the PMP on a biennial basis; and
WHEREAS, the City is required to provide a plan that manages the preservation, rehabilitation, and maintenance of paved roads by analyzing pavement life cycles, assessing overall system performance costs, and determining alternative strategies and costs necessary to improve paved roads.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Costa Mesa as follows:
Section 1. The City Council hereby approves the PMP update in the form attached hereto as Exhibit A to this Resolution.
S ection 2 . The City Council hereby informs OCTA that:
(a) The PMP is in conformance with the PMP Submittal Template provided in the Countywide Pavement Management Plan Guidelines.
(b) The City hereby adopts the PMP update and has provided an updated PMP report, using the required format, to OCTA.
(c) The Public Works Director, City Engineer or designee is authorized to sign the PMP certification form.
210
ATTACHMENT 3
Resolution No. 2024-xx Page 2 of 3
PASSED AND ADOPTED this 4th day of June, 2024.
John Stephens, Mayor
ATTEST: APPROVED AS TO FORM:
___________________________________ _ _______________________________ Brenda Green, City Clerk Kimberly Hall Barlow, City Attorney
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss
CITY OF COSTA MESA )
I, BRENDA GREEN, City Clerk of the City of Costa Mesa, DO HEREBY CERTIFY that the above and foregoing is the original of Resolution No. 20 24-xx and was duly passed and adopted by the City Council of the City of Costa Mesa at a regular meeting held on the 4
th day of June, 2024, by the following roll call vote, to wit:
AYES: COUNCIL MEMBERS:
NOES: COUNCIL MEMBERS:
ABSENT: COUNCIL MEMBERS
IN WITNESS WHEREOF, I have hereby set my hand and affixed the seal of the City of Costa Mesa this 4
th day of June, 2024.
___________________________
Brenda Green, City Clerk
211
ATTACHMENT 3
Resolution No. 2024-xx Page 3 of 3
EXHIBIT A
PAVEMENT MANAGEMENT PLAN
212
FINAL REPORT
UPDATED CITYWIDE
PAVEMENT MANAGEMENT PLAN
OC Go
2024-2031
Submitted to:
City of Costa Mesa, CA
May 4, 2024
213
May 4, 2024
Mr. Seung Yang, P.E.
City Engineer
CITY OF COSTA MESA
77 Fair Drive
Costa Mesa, CA 92626
Subject: City of Costa Mesa –OCTA Pavement Management Compliance Report 2024
Dear Mr. Yang:
As part of the 2024 Update of the Pavement Management Plan (PMP) for the City of Costa Mesa, Bucknam Infrastructure Group, Inc. is pleased to submit the PMP reporting required by the Orange County Transportation Authority (OCTA). This data/report will be submitted to OCTA as part of the City’s required biennial PMP prior to June 30, 2024.
The information contained in this report was used to develop the recommended improvement program for the pavement network. The report covers the following categories:
• Pavement Management Plan Certification
• Quality Assurance / Quality Control (QA/QC) Plan
• Pavement Management Data Files (electronic Costa Mesa.e70 file format)
• Pavement Management Plan that includes the following:
• Average Pavement Conditions For Each Segment in the Network (PCI Report) The Pavement Condition Index report shows the present condition of each street in the pavement network (MPAH and Locals). In addition, the report shows the basic geometry of each street segment.
• Seven-year Projected PCI Under Existing Funding Levels This report identifies the projected PCI’s based on the local agencies current funding programs. This report details the PCI projects for the entire network, MPAH roadways and Local streets.
• Seven-year Plan for Road Maintenance and Rehabilitation (Forecast Maintenance Report – FMR)
The FMR projects the street maintenance activities required for the next seven years, broken down to show maintenance levels for all streets. This includes all scheduled projects provided by the City for fiscal years 2024 through 2031.
214
• Alternative Funding Levels
OCTA has requested two reports indicating the necessary funding to maintain the City’s current weighted average PCI as well as the necessary funding to improve the weighted average PCI by one PCI point over the next seven years.
• Backlog by Fiscal Year (re: unfunded restoration, rehabilitation and reconstruction)
• Percentage of total network in each of the five condition categories based on centerline mileage
• Local Match Reduction Reporting
In order to be eligible for Local Match Reduction of 10%, the following must be submitted:
o Measurable improvement of paved road conditions during the previous reporting period defined as an overall weighted (by area) average system improvement of one PCI point.
o No reduction in the overall weighted (by area) average PCI in the MPAH or local street categories
- or –
o Have road pavement conditions, for the overall network, during the previous reporting period within the highest twenty (20%) of the scale for road pavement conditions in conformance with OCTA Ordinance No. 3, defined as a PCI of 75 or higher, otherwise defined as in “good condition”.
These reports will be submitted to the City of Costa Mesa as part of the biennial Pavement Management Plan that is due prior to June 30, 2024. These reports will be packaged in a way that it will be easy for staff to review.
All comments received from the City have been incorporated in the reports that follow. All of the City’s issues and needs that were brought to our attention are included in the report. It has been a pleasure working with you and the City on updating your Pavement Management Plan. We look forward to the continued success of this project and future teamwork with City staff.
Sincerely,
Bucknam Infrastructure Group, Inc.
Peter J. Bucknam
Project Manager
Infrastructure Management – GIS Services
215
City of Costa Mesa, CA Page i
2024 Citywide Pavement Management Plan – OCTA Submittal Final Report – June 30, 2024
AGENCY SUBMITTAL TABLE OF CONTENTS
I. Pavement Management Plan Certification.............................................................................. 2
II. Executive Summary ................................................................................................................. 3
III. Background ...................................................................................................................... 4
IV. Current Pavement Conditions (PCI) ......................................................................................... 7
V. Projected Pavement Conditions (PCI) ...................................................................................... 8
VI. Alternative Funding Levels ....................................................................................................... 9 a. Maintain Existing Average Network PCI ................................................................ 9 b. Improve Average Network PCI ............................................................................... 9
VII. Current and Projected Backlog by Year of Pavement Maintenance Needs ............................ 9
VIII. Centerline Mileage ................................................................................................................. 10
IX. Percentage of Network in Each of Five Condition Categories Based on Centerline mileage 10
X. Reduction in M2 Local Match ................................................................................................ 11
XI. Appendix A – Seven-Year Road Maintenance and Rehabilitation Plan Based on Current or Expected Funding Level .............................................................................. 12
XII. Appendix B – Complete Street Listing Current Conditions .................................................... 13
XIII. Appendix C – GIS Digital Data ................................................................................................ 14
XIV. Appendix D – Quality Assurance / Quality Control Plan ........................................................ 16 • Introduction ......................................................................................................... 16 • Objectives ............................................................................................................ 16 • Structure of QA/QC Plan ...................................................................................... 16 • Condition Survey Procedures ............................................................................... 17 • Accuracy Required for Data Collection ................................................................ 18 • Random and Systematic Re-Inspections .............................................................. 18 • PCI Comparison with Past Surveys ....................................................................... 19 • Inspector Qualifications and Experience ............................................................. 19 • Safety Procedures ................................................................................................ 19
XV. Appendix E – Pavement Management Data Files ............................................................. 20
XVI. Appendix F – GIS Maps – Current Conditions ................................................................... 21
216
City of Costa Mesa, CA Page 1
2024 Citywide Pavement Management Plan – OCTA Submittal Final Report – June 30, 2024
CITY OF COSTA MESA PAVEMENT MANAGEMENT PLAN
- part of -
COUNTYWIDE PAVEMENT MANAGEMENT PLAN GUIDELINES
(OCTA Guideline – March 2024)
Prepared by: Bucknam Infrastructure Group, Inc.
Submitted to OCTA: June 30, 2024
217
City of Costa Mesa, CA Page 2
2024 Citywide Pavement Management Plan – OCTA Submittal Final Report – June 30, 2024
I. Pavement Management Plan Certification
The City of Costa Mesa, CA certifies that it has a Pavement Management Plan in conformance with the criteria stated in the Orange County Transportation Authority Ordinance No. 3. This ordinance requires that a Pavement Management Plan be in place and maintained to qualify for allocation of revenues generated from renewed Measure M (M2).
The plan was developed by Bucknam Infrastructure Group, Inc. using MicroPAVER , a pavement management system conforming to American Society for Testing and Materials (ASTM) Standard D6433, and contains, at a minimum, the following elements:
• Inventory of MPAH and Local routes reviewed and updated biennially. The last update of the inventory was completed on February, 2024 for the Arterial (MPAH) and March, 2022 for the Local streets;
• Assessment of the pavement condition for all routes in the system, updated biennially. The last field review of the pavement condition was completed in February, 2024; • Percentage of all section of pavement needing:
o Preventive Maintenance = 32.2%;
o Rehabilitation = 17.9%;
o Reconstruction = 0.9%
• Budget needs for preventive maintenance, rehabilitation and/or reconstruction of deficient sections of pavement for:
o Current biennial period $19,173,900;
o following biennial period $18,806,700
• Funds budgeted or available for Preventive Maintenance, Rehabilitation and/or Reconstruction. o Current biennial period $16,500,000;
o following biennial period $19,000,000
• Backlog by year of unfunded rehabilitation, restoration and reconstruction needs (See page 10); • The Pavement Management Plan is consistent with countywide pavement condition assessment standards as described in the OCTA Countywide Pavement Management Plan Guidelines adopted by the OCTA Board of Directors.
*An electronic copy of the Pavement Management Plan ( with MicroPAVER or StreetSaver compatible files) has been or will be submitted with the certification statement. A copy of this certification is being provided to the Orange County Transportation Authority.
Submitted by:
__ ______City of Costa Mesa Name (Print) Jurisdiction
___ __________________________ __________
Signed Date
_ City Engineer
Title
SEUNG YANG
MAY 16, 2024
218
City of Costa Mesa, CA Page 3
2024 Citywide Pavement Management Plan – OCTA Submittal Final Report – June 30, 2024
II. EXECUTIVE SUMMARY
2024 UPDATE OF PAVEMENT MANAGEMENT PLAN (PMP)
As the City of Costa Mesa’s infrastructure continues to mature Public Works priorities such as Local street maintenance and Arterial rehabilitation are key projects to City staff. With the City mostly built-out, wear and tear on the infrastructure will occur at an ever increasing rate. Pavement aging through annual weathering, dynamic and static vehicle loading , and increased usage, compounded with the increased cost of performing maintenance and rehabilitation, add to the yearly operational budget of the pavement network. System sustainability can only be achieved through proactive scheduling and the implementation of cost-efficient pavement applications.
In the upcoming years as the City continues to build upon this study through future inspections and maintenance work history, Costa Mesa pavement data will continue to provide reliable data. This will enhance the PMP through detailed Orange County Transportation Authority (OCTA) OC Go funding analysis, City specific budgetary reporting and level of service reporting.
The Costa Mesa PMP has been developed to assist City personnel by providing current data on the City’s street network and to develop cost- effective maintenance strategies to maintain a desirable level of pavement performance on a network scale, while optimizing the expenditure of limited fiscal resources.
The project consisted of analyzing the City’s 2022 dataset for quality and usability. In doing this, we were tasked to generate an updated Capital Improvement Program report that identified recommendation s and deficiencies in the current operating and maintenance efforts put forth by the City.
We surveyed all designated arterial, collector (MPAH) and local routes this past winter to assist the City in being compliant with OCTA – OC Go March 2024 guidelines. Additionally, we updated the City’s unique Pavement Management – GIS layer that will continue to assist the City in analyzing pavement conditions and other attribute information through the use of MyRoads® and ESRI ArcMap.
Bucknam Infrastructure Group reviewed the City’s previous maintenance efforts and the current 2024-25 proposed street improvements for pertinent pavement information in order to generate a CIP report that identified recommendations and opportunities for improvement in the current operating and maintenance efforts put forth by the City. The result of these work efforts is this report.
219
City of Costa Mesa, CA Page 4
2024 Citywide Pavement Management Plan – OCTA Submittal Final Report – June 30, 2024
III. BACKGROUND – COSTA MESA PMP
In late 1990, voters throughout Orange County approved a ½ -cent sales tax for transportation improvements known as OC Go, formerly known as Measure M2. Funding for streets and roads are included within the sales tax and are distributed to locals agencies through both formula and a competitive method. In late 2006, the renewal of OC Go was approved by voters that would continue the ½-cent sales tax for thirty additional years, starting in 2011.
The primary goal of this report is to comply with established guidelines from OCTA to ensure that field data collection and reporting efforts performed by outside consultants or local agency staff are consistent.
This is required in order that funding allocations can be reviewed and based on agency comparable pavement conditions. Specifically, our findings and recommendations provide Public Works administrators, managers and field personnel with:
* PMP report consistent with OCTA OC Go guidelines
* the present condition status of the pavement network (arterial, collector, residential and industrial streets), as a whole and of any grouping or individual component within the City; * a ranked list of all streets, or segments of streets, by condition within the network; * rehabilitation/maintenance needs of each street segment by year; * an optimized priority maintenance and rehabilitation program based on cost/benefit analysis and various levels of funding;
* optimum annual pavement expenditure levels for pavement maintenance for the next seven (7) years;
* prediction of the life -cycle performance of the City’s pavement network and each individual street section; and
* pavement condition data and analysis presented in GIS through MyRoads® and ESRI ArcMap
Pavement is a dynamic structure where deterioration is constantly occurring; thus the pavement management system needs to be updated on a regular basis to reflect these changes in pavement conditions, pavement maintenance histories, and maintenance strategies based upon budgetary constraints. In our approach to develop the City’s forecasted maintenance recommendations we worked with Costa Mesa Public Works/Engineering staff in identifying unit costs for all maintenance practices used on an annual basis. Currently, based upon the City’s maintenance practices and their associated unit costs, the total replacement value of the Costa Mesa pavement network is $ 525,260,600. This value clearly indicates that the City’s pavement network is the most valuable and essential asset to Costa Mesa.
The City’s use of slurry seal, AC Overlay and R&R practices are typically applied at a five year, ten year and 25 year frequency respectively. These frequencies are typical b ut the City may see increases in deterioration rates due to environmental, load and high average daily traffic (ADT) volumes. For example, high ADT volumes along one of Costa Mesa’s arterial streets will increase deterioration rates for a previously applied AC Overlay compared to a small local street. These deterioration rates are monitored through frequent inspections and functional class deterioration analysis within the City’s PMP database.
220
City of Costa Mesa, CA Page 5
2024 Citywide Pavement Management Plan – OCTA Submittal Final Report – June 30, 2024
FINDINGS AND RECOMMENDATIONS
Through our assessment of historical maintenance performed within the City and through our discussions with City staff the conditional data found across the network clearly shows that the City has applied strong, preventative maintenance strategies over the past decad e. Pavement management involves frequent preventative maintenance; as pavement deteriorates through heavy traffic impacts, weathering and time, preventative maintenances (such as slurry seal, stop gap, etc.) have limited benefits. More aggressive mainten ance applications must be used. Our study has shown that key arterial and local overlay projects will be needed over the next seven years to maintain the network’s high level of condition. Currently, the City’s two major streets networks (Local & Arterial) hold high weighted PCI values; it is our recommendation that a proactive, common sense overlay program and a continued slurry seal program be scheduled over the next several fiscal years. This will ensure that the citywide weighted PCI will sustain itself and allow for routine slurry seal maintenance to continue. The optimal weighted PCI for a local agency is between 82 and 84.
We have found and recommend the following detailed items which should be reviewed and considered for a proactive approach to the future management of the PMP:
ARTERIAL / COLLECTOR (MPAH) FINDINGS AND RECOMMENDATIONS
The actual workload requirements identified indicate that the Arterial (MPAH) street network is currently in “very good” condition. To maintain this condition, it is critical that preventive maintenance and overlay activities are funded at the levels identified on page 9 to maintain a “very good” network weighted average PCI value. Our MPAH findings for conditional data an d recommendations for revenue expenditures are shown below:
• The MPAH network has a weighted PCI of 86.8
• The MPAH network consists of 74.4 centerline miles and 16,632,332 SF of pavement;
• Currently, 34% of the MPAH network ( 25.6 centerline miles) qualify for slurry seal/stop gap maintenance; 11% of the Arterial network ( 8.4 centerline miles) qualify for rehabilitation/reconstruction maintenance;
• At a minimum, MPAH maintenance projects should focus on the maintaining the current PCI above a weighted average of 83 over the next 7 years;
• Develop a proactive fiscal and planned approach to identify MPAH overlay projects based on the deterioration modeling within MicroPAVER;
o Maintain the MPAH revenues at the $ 2,380,500/yr level for the term of the CIP to generate the projects identified on page 8;
o Demonstrated budget shown in page 9 is ample sustain the MPAH weighted PCI of 8 6.8 after seven years, additionally, the citywide deferred backlog decreases from a level of $37.9 million to $27.5 million after seven years; and
221
City of Costa Mesa, CA Page 6
2024 Citywide Pavement Management Plan – OCTA Submittal Final Report – June 30, 2024
• Perform pavement inspections on the MPAH network every two years to continue the City’s solid planning model within MicroPAVER to track PCI deterioration; also follows new OCTA guidelines for Measure M2.
LOCAL FINDINGS AND RECOMMENDATIONS
The actual workload requirements identified indicate that the Local street network is currently in “good” condition. To maintain this condition, it is critical that preventive maintenance and overlay activities are funded at the levels identified on page 9 to maintain a “good” network weighted average PCI value. Our Local network findings for conditional data and recommendations for revenue expenditures are shown below:
• The Local network has a weighted PCI of 81.4;
• The Local network consists of 156.8 centerline miles and 31,775,945 SF of pavement;
• Currently, 42% of the Local network ( 65.5 centerline miles) qualifies for slurry seal/stop gap maintenance; 17% of the Local network ( 25.9 centerline miles) qualify for rehabilitation/reconstruction maintenance;
• At a minimum, Local maintenance projects should focus on the maintaining the current PCI above a weighted average of 82 over the next 7 years;
• Develop a proactive fiscal and planned approach to identify arterial overlay projects based on the deterioration modeling within MicroPAVER;
o Maintain the Local revenues at the $7,044,600 Million/yr level for the term of the CIP to generate the projects identified on page 8;
o Demonstrated budget shown in page 9 is ample to increase the Local weighted PCI of 81.4 to 85.0 after seven years, additionally, the citywide deferred backlog decreases from a level of $37.9 million to $27.5 million after seven years;
• Perform pavement inspections on
the Local network every two years to
continue the City’s solid planning
model within MicroPAVER to track
PCI deterioration; and
• Image right, typical AC pavement 25-
year life cycle deterioration graph
demonstrating proactive slurry
management for PMP’s with high
weighted PCI’s (80 to 85)
222
City of Costa Mesa, CA Page 7
2024 Citywide Pavement Management Plan – OCTA Submittal Final Report – June 30, 2024
IV. CURRENT PAVEMENT CONDITIONS (PCI)
223
City of Costa Mesa, CA Page 8
2024 Citywide Pavement Management Plan – OCTA Submittal Final Report – June 30, 2024
V. PROJECTED PAVEMENT CONDITIONS (PCI)
224
City of Costa Mesa, CA Page 9
2024 Citywide Pavement Management Plan – OCTA Submittal Final Report – June 30, 2024
VI. ALTERNATIVE FUNDING LEVELS
Maintain Existing Average Network PCI
Improve Average Network PCI
VII. CURRENT AND PROJECTED BACKLOG BY YEAR OF PAVEMENT
MAINTENANCE NEEDS
DEFERRED MAINTENANCE
Delaying repairs on streets where pavement conditions indicate a need generates deferred maintenance or “backlog”. Deferred maintenance is work that is postponed to a future budget cycle, or until funds are available. As maintenance is deferred, the opportunity to apply preventive, life extending pavement treatments is forfeited and the ultimate cost of rehabilitation multiplies (i.e. slurry seal costs to overlay costs). By using the City’s pavement maintenance applications and their associated unit costs, when a budgetary model is exercised within the PMP software the amount of deferred maintenance is calculated. Based upon the available budget applied to the model, deferred maintenance will increase or decrease.
225
City of Costa Mesa, CA Page 10
2024 Citywide Pavement Management Plan – OCTA Submittal Final Report – June 30, 2024
As maintenance is deferred, the opportunity to apply life extending preventive pavement applications is lost and the ultimate cost of rehabilitation multiples.
In the case of Costa Mesa, the City’s current funding budgets through FY 2030-31 will continue to decrease the amount of deferred maintenance on the network to a $32.7 million level by FY 2031.
VIII. CENTERLINE MILEAGE
IX. PERCENTAGE OF NETWORK IN EACH OF FIVE CONDITION CATEGORIES
BASED ON CENTERLINE MILES
226
City of Costa Mesa, CA Page 11
2024 Citywide Pavement Management Plan – OCTA Submittal Final Report – June 30, 2024
X. REDUCTION IN M2 LOCAL MATCH
A local agency match reduction of 10% of the eligible cost for projects submitted for consideration of funding through the M2 Comprehensive Transportation Funding Programs (CTFP) call for projects is available if the local agency either:
a. Shows measurable improvement of paved road conditions during the previous reporting period defined as an overall weighted (by area) average system improvement of one Pavement Condition Index (PCI) point with no reduction in the overall weighted (by area) average PCI in the Master Plan of Arterial Highways (MPAH) or local categories:
or
b. Have road pavement conditions during the previous reporting period, within the highest 20% of the scale for road pavement conditions in conformance with OCTA Ordinance No. 3, defined as a PCI of 75 or higher, otherwise defined as in “good condition”.
Road conditions found through our 2024 PMP management study shows that the City is eligible for Local Match Reduction based on the current network weighted PCI of 83. 4. Additionally, the City of Costa Mesa has demonstrated with the enclosed budget projection (page 8) that the City’s weighted average PCI (based upon condition and area) remains above a PCI of 75 after the seven year program.
227
City of Costa Mesa, CA Page 12
2024 Citywide Pavement Management Plan – OCTA Submittal Final Report – June 30, 2024
XI. APPENDIX A – SEVEN YEAR ROAD MAINTENANCE AND REHABILITATION
PLAN BASED ON CURRENT OR EXPECTED FUNDING LEVEL
228
City of Costa Mesa, CA
Forecast Maintenance / Rehabilitation (FMR) Report - FY 2024-31 Sorted by Rank, FY, Name Order (A-Z)
FY BranchID Sec ID Name From To Type Rank Zone L W Area PCI PCI Pct Climate PCI Pct Load PCI Pct Other Maint. Type Total $ Arterials / Collectors
2024-25 Fairview 490 Fairview Rd Wilson St Fair Dr AC A 24 2,760 35 106,978 76 42 40 18 Type II Slurry $313,446 2024-25 Fairview 491 Fairview Rd Fair Dr Wake Forest Rd AAC A 24 1,961 35 68,635 72 16 53 31 ARHM $377,493 2024-25 Fairview 492 Fairview Rd Wake Forest Rd Wilson St AAC A 24 792 35 27,720 82 35 0 65 Type II Slurry $81,220 2024-25 Fairview 501 Fairview Rd Merrimac Way Fair Dr AC A 10 1,300 35 44,850 67 51 49 0 ARHM $246,675 2024-25 Fairview 510 Fairview Rd Merrimac Way Arlington Dr AC A 10 510 35 17,595 89 59 0 41 Preventative - Stop Gap $1,232 2024-25 Fairview 511 Fairview Rd Arlington Dr Merrimac Way AC A 10 510 35 17,595 86 100 0 0 Type II Slurry $51,553 2024-25 Fairview 515 Fairview Rd Arlington Dr Adams Ave AC A 10 2,603 35 88,905 79 84 0 16 Type II Slurry $260,492 2024-25 Fairview 516 Fairview Rd Adams Ave Arlington Dr AC A 10 2,603 35 88,905 76 100 0 0 Type II Slurry $260,492 2024-25 Fairview 530 Fairview Rd Baker St S'ly edge of Bridge over I-405 AC A 15 2,665 35 93,275 77 50 26 24 Type II Slurry $273,296 2024-25 Fairview 531 Fairview Rd S'ly edge of Bridge over I-405 Baker St AC A 15 2,665 35 89,475 81 24 66 10 Type II Slurry $262,162 $2,128,058
2025-26 Harbor 310 Harbor Blvd Wilson St Fair Dr AC A 24 2,570 40 102,100 86 47 50 3 Type II Slurry $311,405 2025-26 Harbor 311 Harbor Blvd Fair Dr Wilson St AC A 24 2,570 40 102,800 77 11 68 21 Type II Slurry $313,540 2025-26 Harbor 321 Harbor Blvd Adams Ave Merrimac Way AC A 10 1,802 40 72,080 85 18 55 27 Type II Slurry $219,844 2025-26 Harbor 322 Harbor Blvd Merrimac Way Fair Dr AC A 10 1,862 40 74,480 83 31 41 28 Type II Slurry $227,164 2025-26 Harbor 370 Harbor Blvd South Coast Dr Sunflower Ave AC A 30 1,460 40 58,400 87 84 1 15 Preventative - Stop Gap $4,088 2025-26 Harbor 371 Harbor Blvd Sunflower Ave South Coast Dr AC A 30 1,460 40 58,400 75 11 74 15 Type II Slurry $178,120 2025-26 Harbor 380 Harbor Blvd Sunflower Ave MacArthur Ave AC A 30 2,315 40 92,600 71 46 39 15 AC Grind-Overlay $512,078 2025-26 Harbor 381 Harbor Blvd MacArthur Ave Sunflower Ave AC A 30 2,315 40 92,600 87 41 18 41 Preventative - Stop Gap $6,482 2025-26 Main 11760 Main St CL SR-55 Sunflower Ave AC A 28 780 70 54,600 71 70 0 30 AC Grind-Overlay $301,938 2025-26 NewportSB 15416 Newport Blvd South Bound Fair Dr Vanguard Way AC S 24 2,645 32 84,980 74 39 55 6 Type II Slurry $259,189 2025-26 NewportSB 261 Newport Blvd South Bound Mesa Dr Fair Dr AC S 24 1,315 44 63,660 75 38 33 29 Type II Slurry $194,163 2025-26 NewportSB 271 Newport Blvd South Bound Bristol St Arlington Dr AC S 10 1,780 32 56,960 80 86 0 14 Type II Slurry $173,728 $2,701,739
2026-27 17th 2860 17th St W'ly End Monrovia Ave AC S 6 1,670 36 60,120 84 79 0 21 Type II Slurry $190,580 2026-27 17th 2870 17th St Monrovia Ave Placentia Ave AC S 6 1,320 36 47,520 83 69 23 8 Type II Slurry $150,638 2026-27 17th 2895 17th St 615' e/o Pomona Ave Superior Ave AC P 7 600 54 32,400 75 69 0 31 Type II Slurry $102,708 2026-27 17th 2900 17th St Superior Ave Newport Blvd AC P 8 452 47 21,244 83 100 0 0 Type II Slurry $67,343 2026-27 17th 2901 17th St Newport Blvd Superior Ave AC P 8 452 47 21,244 77 100 0 0 Type II Slurry $67,343 2026-27 Gisler 8830 Gisler Ave W'ly End Country Club Dr AC S 17 2,450 50 122,500 63 16 75 9 ARHM $728,875 2026-27 Gisler 8850 Gisler Ave Country Club Dr Harbor Blvd AAC S 17 3,400 56 190,400 80 91 0 9 Type II Slurry $603,568 2026-27 NewportNB 15411 Newport Blvd North Bound Bay St 22nd St AC S 5 1,965 30 63,950 86 74 0 26 Type II Slurry $202,722 2026-27 NewportNB 15412 Newport Blvd North Bound Wilson St Santa Isabel Ave AAC S 5 515 34 18,495 77 50 33 17 Type II Slurry $58,629 2026-27 NewportNB 15413 Newport Blvd North Bound Monte Vista Ave Del Mar Ave AAC S 24 1,349 37 49,913 77 63 25 12 Type II Slurry $158,224 2026-27 NewportNB 15414 Newport Blvd North Bound Del Mar Ave Mesa Dr AAC S 24 1,275 34 45,390 79 100 0 0 Type II Slurry $143,886 2026-27 NewportSB 15417 Newport Blvd South Bound Bay St Ford Rd AC S 5 1,436 32 45,895 79 24 71 5 Type II Slurry $145,487 2026-27 SouthCoast 730 South Coast Dr Harbor Blvd Fairview Rd AC P 30 3,570 33 117,810 69 46 20 34 AC Grind-Overlay $677,408 2026-27 SouthCoast 731 South Coast Dr Fairview Rd Susan St AC P 30 1,963 33 64,779 57 39 54 7 ARHM $385,435 2026-27 SouthCoast 732 South Coast Dr Susan St Harbor Blvd AC P 30 1,610 33 53,130 75 62 35 3 Type II Slurry $168,422 $3,851,270
2027-28 19th 3425 19th St W'ly City Limits Parkcrest Dr AC P 6 360 42 15,120 87 100 0 0 Preventative - Stop Gap $1,058 2027-28 19th 3460 19th St Pomona Ave Anaheim Ave AC P 2 1,305 36 46,980 84 88 0 12 Type II Slurry $155,034 2027-28 19th 3461 19th St Anaheim Ave Pomona Ave AC P 2 1,305 36 46,980 88 75 0 25 Preventative - Stop Gap $3,289 2027-28 19th 3470 19th St Anaheim Ave Park Ave AC P 2 650 36 23,400 85 100 0 0 Type II Slurry $77,220 2027-28 19th 3471 19th St Park Ave Anaheim Ave AC P 2 650 36 23,400 90 100 0 0 Preventative - Stop Gap $1,638 2027-28 19th 4140 19th St Newport Blvd Fullerton Ave AAC C 8 680 35 23,800 83 52 0 48 Type II Slurry $78,540 2027-28 19th 4141 19th St Fullerton Ave Newport Blvd AAC C 8 680 35 23,800 77 23 53 24 Type II Slurry $78,540 2027-28 19th 4150 19th St Fullerton Ave Orange Ave AAC C 8 680 36 24,465 74 72 0 28 Type II Slurry $80,735 2027-28 Baker 655 Baker St Loren Ln Fairview Rd AC P 21 515 80 40,255 76 100 0 0 Type II Slurry $132,842 2027-28 Baker 660 Baker St Fairview Rd Babb St (N) AAC P 15 2,572 60 171,444 80 48 46 6 Type II Slurry $565,765 $1,174,660
2028-29 NewportNB 240 Newport Blvd North Bound Walnut St Bay St AC S 5 1,518 32 48,653 89 96 0 4 Preventative - Stop Gap $3,406 2028-29 NewportNB 250 Newport Blvd North Bound 22nd St Wilson St AAC S 5 2,140 34 73,960 77 54 7 39 Type II Slurry $253,683 2028-29 NewportNB 260 Newport Blvd North Bound Santa Isabel Ave Monte Vista Ave AAC S 24 1,310 37 48,470 73 63 37 0 Type II Slurry $166,252 2028-29 NewportNB 270 Newport Blvd North Bound Mesa Dr Bristol St AC S 10 2,964 37 109,668 76 53 27 20 Type II Slurry $376,161 2028-29 NewportSB 241 Newport Blvd South Bound Victoria St Bay St AC S 5 1,900 40 80,500 80 45 55 0 Type II Slurry $276,115 2028-29 NewportSB 251 Newport Blvd South Bound Vanguard Way Wilson St AC S 5 780 30 28,500 76 35 63 2 Type II Slurry $97,755 2028-29 NewportSB 252 Newport Blvd South Bound Wilson St 55 FWY SB Off Ramp Merge AC S 5 870 30 20,095 87 100 0 0 Preventative - Stop Gap $1,407 2028-29 NewportSB 253 Newport Blvd South Bound 55 FWY SB Off Ramp Merge Victoria St AC S 5 940 47 46,255 74 52 44 4 Type II Slurry $158,655 $1,333,433
2029-30 NewportSB 15415 Newport Blvd South Bound Arlington Dr Mesa Dr AC S 10 1,274 44 57,785 86 50 33 17 Type II Slurry $205,715 2029-30 Sunflower 770 Sunflower Ave Harbor Blvd Hyland Ave AC P 30 1,700 60 99,300 86 37 0 63 Type II Slurry $353,508 2029-30 Sunflower 780 Sunflower Ave Harbor Blvd Fairview Rd AC P 30 2,590 33 83,070 73 19 77 4 Type II Slurry $295,729
229
City of Costa Mesa, CA
Forecast Maintenance / Rehabilitation (FMR) Report - FY 2024-31 Sorted by Rank, FY, Name Order (A-Z)
FY BranchID Sec ID Name From To Type Rank Zone L W Area PCI PCI Pct Climate PCI Pct Load PCI Pct Other Maint. Type Total $ 2029-30 Sunflower 781 Sunflower Ave Fairview Rd Harbor Blvd AC P 30 2,590 33 85,470 75 23 56 21 Type II Slurry $304,273 2029-30 Sunflower 790 Sunflower Ave Fairview Rd Wimbledon Wy AC P 27 1,095 60 76,039 74 41 37 22 Type II Slurry $270,699 $1,429,924
2030-31 Sunflower 791 Sunflower Ave Wimbledon Wy Fuschia St AC P 27 1,735 60 102,478 83 92 0 8 Type II Slurry $380,193 2030-31 Sunflower 792 Sunflower Ave Fuschia St Bear St AC P 27 2,035 60 140,031 75 17 60 23 Type II Slurry $519,515 2030-31 Sunflower 800 Sunflower Ave Bear St Bristol St AAC A 27 1,990 36 99,843 86 46 0 54 Type II Slurry $370,418 2030-31 Sunflower 801 Sunflower Ave Bristol St Bear St AAC A 27 1,990 36 94,669 73 22 71 7 Type II Slurry $351,222 2030-31 Sunflower 810 Sunflower Ave Bristol St Avenue of the Arts AAC A 28 1,360 36 48,960 79 48 19 33 Type II Slurry $181,642 2030-31 Sunflower 811 Sunflower Ave Main St Avenue of the Arts AC A 28 3,850 36 138,600 83 76 24 0 Type II Slurry $514,206 2030-31 Sunflower 812 Sunflower Ave Avenue of the Arts Anton Blvd AAC A 28 2,750 36 99,000 81 26 45 29 Type II Slurry $367,290 2030-31 Sunflower 814 Sunflower Ave Anton Blvd Main St AC A 28 1,125 36 40,500 87 89 0 11 Preventative - Stop Gap $2,835 2030-31 Sunflower 816 Sunflower Ave Avenue of the Arts Park Center Dr AAC A 28 795 36 33,570 90 71 0 29 Preventative - Stop Gap $2,350 2030-31 Sunflower 817 Sunflower Ave Park Center Dr Bristol St AAC A 28 536 36 27,340 54 28 52 20 ARHM $190,286 2030-31 VictoriaSt 15418 Victoria St Doctors Cir Newport Blvd SB AAC S 5 1,255 60 76,389 76 100 0 0 Type II Slurry $283,403 2030-31 VictoriaSt 390 Victoria St E'ly edge of Bridge at SA River Valley Rd AAC P 1 1,300 65 84,500 84 61 36 3 Type II Slurry $313,495 2030-31 VictoriaSt 400 Victoria St Valley Rd Canyon Dr AAC S 1 700 68 47,600 78 62 0 38 Type II Slurry $176,596 2030-31 VictoriaSt 411 Victoria St National Ave Canyon Dr AAC S 18 2,155 34 73,270 76 83 0 17 Type II Slurry $271,832 $3,925,283
Locals
2024-25 Abbie 3690 Abbie Way W'ly Cul-de-sac Irvine Ave AAC E 9 531 37 21,821 84 73 0 27 Type II Slurry $30,549 2024-25 Ayon 7790 Ayon Cir Balearic Cir Cul-de-sac AC E 22 200 37 9,574 78 53 47 0 Type II Slurry $13,404 2024-25 Azalia 11330 Azalea Dr Begonia Ave Fuschia St AC E 27 1,520 37 56,240 85 85 15 0 Type II Slurry $78,736 2024-25 Babb 10420 Babb St Post Rd Baker St AC E 20 640 37 23,680 84 98 0 2 Type II Slurry $33,152 2024-25 Babb 10610 Babb St Baker St Paularino Ave AC E 16 831 37 30,747 55 39 56 5 AC Grind-Overlay $135,902 2024-25 Baker 630 Baker St Samar Dr Mesa Verde Dr AC E 21 1,670 37 62,194 57 20 65 15 AC Grind-Overlay $274,897 2024-25 Baker 710 Baker St Red Hill Ave Airway Ave AC E 29 1,030 60 62,109 80 88 10 2 Type II Slurry $86,953 2024-25 Broadway 3970 Broadway Newport Blvd Orange Ave AC E 1,330 50 66,500 83 100 0 0 Type II Slurry $93,100 2024-25 Broadway 3980 Broadway Orange Ave Santa Ana Ave AC E 1,330 42 52,115 84 86 14 0 Type II Slurry $72,961 2024-25 Broadway 3990 Broadway Santa Ana Ave Tustin Ave AC E 1,350 50 67,500 82 86 14 0 Type II Slurry $94,500 2024-25 Broadway 4000 Broadway Tustin Ave Irvine Ave AAC E 9 1,345 40 53,800 84 100 0 0 Type II Slurry $75,320 2024-25 Buchanan 10480 Buchanan Way Cul-de-sac Dorset Ln AAC E 16 280 37 12,534 75 100 0 0 Type II Slurry $17,548 2024-25 Bunting 7570 Bunting Cir Oriole Dr Cul-de-sac AAC E 11 500 37 20,674 74 53 47 0 Type II Slurry $28,944 2024-25 Carnation 11310 Carnation Ave Fuschia St Cul-de-sac AC E 27 1,315 37 50,829 84 76 24 0 Type II Slurry $71,161 2024-25 Carnegie 7100 Carnegie Ave Fair Dr Princeton Dr AC E 10 1,254 37 46,398 59 13 75 12 AC Grind-Overlay $205,079 2024-25 Carson 10720 Carson St Van Buren Ave Coolidge Ave AC E 16 783 37 29,241 59 94 0 6 Cape Seal $50,002 2024-25 Cecil 6590 Cecil Pl Newport Blvd Santa Ana Ave AC E 25 2,513 37 88,533 63 43 33 24 AC Grind-Overlay $391,316 2024-25 Cedar 4260 Cedar Pl Republic Ave Monrovia Ave AAC E 1 753 33 24,808 87 92 0 8 Type II Slurry $34,731 2024-25 Century 10380 Century Pl Cul-de-sac Baker St AAC E 13 710 47 35,544 83 61 0 39 Type II Slurry $49,762 2024-25 El Camino 10040 El Camino Dr Mendoza Dr La Salle Ave AC E 20 980 48 51,772 84 77 23 0 Type II Slurry $72,481 2024-25 El Rio 10050 El Rio Cir El Camino Dr Cul-de-sac AC E 20 551 37 22,561 60 41 52 7 AC Grind-Overlay $99,720 2024-25 Elba 7870 Elba Cir Cul-de-sac Stromboli Rd AAC E 21 350 37 15,124 68 58 42 0 AC Grind-Overlay $66,848 2024-25 Elden 5480 Elden Ave 21st St 22nd St AC E 3 1,150 37 42,550 77 49 37 14 Type II Slurry $59,570 2024-25 Elden 5500 Elden Ave Santa Isabel Ave Monte Vista Ave AC E 26 1,300 37 48,100 83 42 26 32 Type II Slurry $67,340 2024-25 Elden 5510 Elden Ave Monte Vista Ave Mesa Dr AC E 26 2,650 37 98,050 86 74 17 9 Type II Slurry $137,270 2024-25 Ellesmere 7970 Ellesmere Ave Pitcairn Dr Samar Dr AC E 21 845 37 31,265 83 86 0 14 Type II Slurry $43,771 2024-25 Ellesmere 7972 Ellesmere Ave Samar Dr Ceylon Dr AC E 21 960 37 35,520 40 22 62 16 AC Grind-Overlay $156,998 2024-25 Glen 4520 Glen Cir Cul-de-sac Canyon Dr AC E 1 270 37 12,164 25 61 32 7 AC Recon $130,763 2024-25 Gleneagles 4430 Gleneagles Terr Cul-de-sac Valley Rd AC E 1 1,060 37 41,394 78 70 28 2 Type II Slurry $57,952 2024-25 Goldeneye 7390 Goldeneye Pl Sandpiper Dr Mallard Dr AAC E 11 780 37 28,860 85 75 23 2 Type II Slurry $40,404 2024-25 GolfCourse 7530 Golf Course Dr Tanager Dr Mesa Verde Dr E AC E 11 1,200 16 18,600 80 78 20 2 Type II Slurry $26,040 2024-25 GolfCourse 7531 Golf Course Dr Mesa Verde Dr E Tanager Dr AAC E 11 1,200 16 18,600 78 87 13 0 Type II Slurry $26,040 2024-25 Lavender 11270 Lavender Ln Begonia Ave Poppy Cir AC E 27 420 37 15,540 87 80 18 2 Type II Slurry $21,756 2024-25 Lear 11840 Lear Ave Red Hill Ave Airway Ave AC E 29 550 40 22,000 78 89 11 0 Type II Slurry $30,800 2024-25 Lehigh 7150 Lehigh Pl Cul-de-sac Bucknell Rd AAC E 10 360 37 15,494 69 42 40 18 Type II Slurry $21,692 2024-25 Lemnos 7740 Lemnos Dr Europa Dr Chios Rd AC E 22 920 37 34,540 77 63 9 28 Type II Slurry $48,356 2024-25 Lemon 8350 Lemon St Elm Ave Ponderosa St AAC E 21 360 33 11,880 85 25 39 36 Type II Slurry $16,632 2024-25 LenwoodCir 2740 Lenwood Cir Aliso Ave Cul-de-sac AAC E 9 226 33 9,632 82 84 16 0 Type II Slurry $13,485 2024-25 LenwoodDr 2730 Lenwood Dr Tustin Ave Aliso Dr AAC E 9 658 37 24,346 76 53 45 2 Type II Slurry $34,084 2024-25 Lincoln 10880 Lincoln Way Cheyenne Ave Cul-de-sac AAC E 16 470 37 19,648 75 90 9 1 Type II Slurry $27,507 2024-25 LittletonC 6530 Littleton Cir Villanova Rd Cul-de-sac AC E 24 430 37 18,084 86 91 0 9 Type II Slurry $25,318 2024-25 LittletonP 6520 Littleton Pl Cul-de-sac Villanova Rd AC E 24 343 37 14,865 32 21 76 3 AC Recon $159,799 2024-25 Paularino 10450 Paularino Ave Fairview Rd Helena Pl AAC E 16 3,860 37 142,820 87 74 26 0 Type II Slurry $199,948 2024-25 Paularino 11580 Paularino Ave Bear St Bristol St AAC E 31 2,162 37 79,994 70 44 44 12 Type II Slurry $111,992 2024-25 Paularino 11900 Paularino Ave Red Hill Ave Airway Ave AC E 29 880 60 52,800 80 90 10 0 Type II Slurry $73,920
230
City of Costa Mesa, CA
Forecast Maintenance / Rehabilitation (FMR) Report - FY 2024-31 Sorted by Rank, FY, Name Order (A-Z)
FY BranchID Sec ID Name From To Type Rank Zone L W Area PCI PCI Pct Climate PCI Pct Load PCI Pct Other Maint. Type Total $ 2024-25 Pemba 8040 Pemba Dr Samar Dr Ceylon Dr AC E 21 1,448 37 54,137 53 30 68 2 AC Grind-Overlay $239,286 2024-25 PepperTree 8400 Pepper Tree Ln Royal Palm Dr Royal Palm Dr AC E 21 1,361 37 50,357 52 23 68 9 AC Grind-Overlay $222,578 2024-25 Peterson 9300 Peterson Pl Harbor Blvd Adams St AC E 10 1,346 37 49,802 43 33 54 13 AC Grind-Overlay $220,125 2024-25 Phalarope 7400 Phalarope Ct Swan Dr Swan Dr AAC E 11 1,450 37 53,650 81 73 27 0 Type II Slurry $75,110 2024-25 Samar Dr 7960 Samar Dr Cul-de-sac Mesa Verde Dr AC E 21 2,700 37 102,074 37 19 77 4 AC Grind-Overlay $451,167 2024-25 Samar Pl 8510 Samar Pl Cul-de-sac Andros St AC E 21 400 37 16,974 61 29 71 0 AC Grind-Overlay $75,025 2024-25 Samoa 8210 Samoa Pl Cul-de-sac Gibraltar Ave AC E 23 1,849 37 70,587 66 24 76 0 AC Grind-Overlay $311,995 2024-25 SanBrnrdno 2230 San Bernardino Pl Cul-de-sac 16th St AAC E 9 200 33 8,774 83 80 20 0 Type II Slurry $12,284 2024-25 San Carlos 9960 San Carlos Ln De Soto Ave Coronado Dr AAC E 20 795 37 30,365 82 100 0 0 Type II Slurry $42,511 2024-25 WstmnstrAv 2410 Westminster Ave 15th St Knox Pl AAC E 8 970 35 33,950 76 43 55 2 Type II Slurry $47,530 2024-25 WstmnstrAv 2710 Westminster Ave 16th St Alley #53 AAC E 8 830 37 30,710 81 40 58 2 Type II Slurry $42,994 2024-25 WstmnstrAv 4180 Westminster Ave 17th St 19th St AAC E 8 2,670 37 98,790 82 38 54 8 Type II Slurry $138,306 2024-25 WstmnstrAv 5040 Westminster Ave Costa Mesa St Walnut St AAC E 3 321 37 11,877 84 82 16 2 Type II Slurry $16,628 2024-25 WstmnstrAv 5050 Westminster Ave Walnut St 20th St AAC E 3 655 18 11,790 65 53 45 2 AC Grind-Overlay $52,112 2024-25 WstmnstrAv 5370 Westminster Ave Sierks St 21st St AAC E 3 990 37 36,630 78 44 55 1 Type II Slurry $51,282 2024-25 WstmnstrAv 5570 Westminster Ave 21st St Rose Ln AC E 3 783 37 28,971 62 28 64 8 AC Grind-Overlay $128,052 2024-25 WstmnstrAv 6810 Westminster Ave Wilson St Santa Isabel Ave AAC E 25 532 37 19,684 83 30 70 0 Type II Slurry $27,558 $5,763,041
2025-26 16th 2905 16th St Superior Ave Newport Blvd AC E 7 800 37 29,600 39 38 62 0 AC Grind-Overlay $136,160 2025-26 Balearic 7710 Balearic Dr Europa Dr Boa Vista Dr AC E 22 1,421 36 51,775 61 42 57 1 AC Grind-Overlay $238,165 2025-26 Baltra 7720 Baltra Pl Europa Dr Inroz Dr AC E 22 779 37 29,323 51 36 62 2 AC Grind-Overlay $134,886 2025-26 Barbados 8240 Barbados Pl Labrador Dr Madagasgar St AC E 23 1,316 37 53,433 51 19 68 13 AC Grind-Overlay $245,792 2025-26 CeylonDr 8030 Ceylon Dr Palau Pl Cul-de-sac AC E 21 1,180 37 45,834 57 33 66 1 AC Grind-Overlay $210,836 2025-26 CeylonRd 8160 Ceylon Rd Cul-de-sac Madeira Ave AC E 23 1,424 37 54,862 44 27 73 0 AC Grind-Overlay $252,365 2025-26 Cibola 9930 Cibola Ave Presidio Dr Coronado Dr AAC E 20 1,167 37 43,179 84 100 0 0 Type II Slurry $63,041 2025-26 Esther 5150 Esther St Walnut Pl Tustin Ave AAC E 4 650 35 22,425 74 42 46 12 Type II Slurry $32,741 2025-26 Esther 5180 Esther St Westminster Ave Santa Ana Ave AAC E 3 640 37 23,680 85 81 19 0 Type II Slurry $34,573 2025-26 Esther 5210 Esther St Santa Ana Ave Raymond Ave AAC E 4 650 37 24,050 83 82 16 2 Type II Slurry $35,113 2025-26 Esther 5220 Esther St Raymond Ave Tustin Ave AAC E 4 660 37 24,420 87 91 9 0 Type II Slurry $35,653 2025-26 Esther 5280 Esther St W'ly end Irvine Ave AAC E 4 617 35 21,287 80 57 38 5 Type II Slurry $31,078 2025-26 Europa 7650 Eurpoa Dr Calvert Ave Kornat Dr AC E 21 1,600 37 59,700 55 39 57 4 AC Grind-Overlay $274,620 2025-26 Farallon 7950 Farallon Dr Club House Rd Samar Dr AC E 21 265 37 9,805 76 88 9 3 Type II Slurry $14,315 2025-26 Fayette 11630 Fayette Cir Ludington St Cul-de-sac AAC E 12 221 37 10,351 83 100 0 0 Type II Slurry $15,112 2025-26 KnoxPl 2150 Knox Pl Orange Ave Santa Ana Ave AAC E 8 1,320 37 48,840 78 34 42 24 Type II Slurry $71,306 2025-26 KnoxSt 2120 Knox St Orange Ave Santa Ana Ave AAC E 8 1,320 37 48,840 82 50 50 0 Type II Slurry $71,306 2025-26 Kornat 7660 Kornat Dr Europa Dr Boa Vista Dr AC E 22 1,050 37 39,350 86 100 0 0 Type II Slurry $57,451 2025-26 La Perle 2180 La Perle Ln/Pl Tustin Ave (Southern) Tustin Ave (Northern) AAC E 9 1,245 33 41,085 85 77 0 23 Type II Slurry $59,984 2025-26 La Salle 10190 La Salle Ave Coronado Dr Mission Dr AAC E 20 1,235 36 60,650 87 49 51 0 Type II Slurry $88,549 2025-26 Murray 9450 Murray Ln Baker St Watson Ave AC E 15 331 37 12,247 84 20 80 0 Type II Slurry $17,881 2025-26 Murray 9550 Murray Ln Conway Ave Belfast AC E 15 971 37 35,927 84 37 63 0 Type II Slurry $52,453 2025-26 Nassau 6450 Nassau Rd College Dr Loyola Rd AC E 24 1,692 37 61,531 85 83 15 2 Type II Slurry $89,835 2025-26 National 4400 National Ave Victoria Ave Congress St AAC E 18 460 37 17,020 85 100 0 0 Type II Slurry $24,849 2025-26 National 4402 National Ave Congress St Wilson St AAC E 18 713 37 25,613 74 35 54 11 Type II Slurry $37,395 2025-26 Nevis 7800 Nevis Cir Boa Vista Dr Cul-de-sac AC E 22 518 37 21,340 84 77 16 7 Type II Slurry $31,156 2025-26 NewportNBF 2020 Newport Blvd N/B Frontage Road AC 16th St PCC E 8 1,022 36 42,552 65 20 69 11 AC Grind-Overlay $195,739 2025-26 NewportNBF 2030 Newport Blvd N/B Frontage Road 16th St AC PCC E 8 960 36 34,560 61 24 50 26 AC Grind-Overlay $158,976 2025-26 NewportNBF 2040 Newport Blvd N/B Frontage Road PCC 17th St AC E 138 37 4,673 68 100 0 0 Cape Seal $8,318 2025-26 NewportNBF 2070 Newport Blvd N/B Frontage Road 15th St PCC AC E 315 36 11,340 64 34 63 3 AC Grind-Overlay $52,164 2025-26 NewportSBF 2021 Newport Blvd S/B Frontage Road 16th St Industrial Way AC E 7 1,200 36 43,200 84 65 27 8 Type II Slurry $63,072 2025-26 Robin Hood 5390 Robin Hood Ln Cul-de-sac Westminster Ave AAC E 3 349 33 13,691 84 83 15 2 Type II Slurry $19,989 2025-26 Robin Hood 5400 Robin Hood Ln Westminster Ave Santa Ana Ave AAC E 3 653 37 24,161 76 77 9 14 Type II Slurry $35,275 2025-26 Robin Hood 5410 Robin Hood Ln Santa Ana Ave Cul-de-sac AAC E 3 653 37 26,335 79 89 11 0 Type II Slurry $38,449 2025-26 Rochester 3620 Rochester St Newport Blvd Orange Ave AAC E 8 1,340 37 49,580 61 41 46 13 AC Grind-Overlay $228,068 2025-26 Rochester 3630 Rochester St Orange Ave Cul-de-sac AAC E 8 531 28 17,042 81 75 23 2 Type II Slurry $24,881 2025-26 Rochester 3640 Rochester St Westminster Ave Cul-de-sac AAC E 8 322 33 12,800 80 90 10 0 Type II Slurry $18,688 2025-26 Rochester 3650 Rochester St Santa Ana Ave Tustin Ave AAC E 9 1,324 37 48,988 78 58 41 1 Type II Slurry $71,522 2025-26 Sunflower 775 Sunflower Ave Cadillac Ave Hyland Ave AC E 30 1,775 60 106,500 59 38 57 5 AC Grind-Overlay $489,900 2025-26 Superior 2972 Superior Ave E. 17th St 400' n/o E. 17th St AC E 7 400 37 14,800 83 85 11 4 Type II Slurry $21,608 2025-26 Superior 2974 Superior Ave Newport Blvd Entrance 18th St AAC E 7 800 48 38,400 61 43 56 1 AC Grind-Overlay $176,640 2025-26 Susan 9830 Susan St South Coast Dr Pavement Change AC E 30 493 37 18,241 85 76 21 3 Type II Slurry $26,632 2025-26 Susan 9831 Susan St Sunflower Ave South Coast Dr AC E 30 1,500 37 55,500 62 62 35 3 Cape Seal $98,790 2025-26 Susan 9835 Susan St Pavement Change Sunflower Ave AC E 30 1,004 37 37,148 51 61 29 10 Cape Seal $66,123 2025-26 Sutter 10230 Sutter Way Junipero Dr Magellan St AAC E 20 260 37 9,620 85 100 0 0 Type II Slurry $14,045 2025-26 Suva 7770 Suva Cir Balearic Dr Cul-de-sac AC E 22 400 37 16,974 82 100 0 0 Type II Slurry $24,782
231
City of Costa Mesa, CA
Forecast Maintenance / Rehabilitation (FMR) Report - FY 2024-31 Sorted by Rank, FY, Name Order (A-Z)
FY BranchID Sec ID Name From To Type Rank Zone L W Area PCI PCI Pct Climate PCI Pct Load PCI Pct Other Maint. Type Total $ 2025-26 Swan Dr 7330 Swan Dr Sandpiper Dr E'ly end AAC E 11 2,190 37 81,030 83 55 41 4 Type II Slurry $118,304 2025-26 Swarthmore 7120 Swarthmore Ln Cul-de-sac Carnegie Ave AC E 10 390 33 15,044 78 28 57 15 Type II Slurry $21,964 2025-26 Wallace 3140 Wallace Ave 19th St Hamilton St AC E 2 2,650 37 98,050 72 62 37 1 Type II Slurry $143,153 2025-26 Wallace 5920 Wallace Ave Congress St Wilson St AC E 19 659 37 24,383 60 100 0 0 Cape Seal $43,402 2025-26 Walnut Pl 5140 Walnut Pl Tustin Ave Esther Pl AAC E 4 650 35 22,750 86 98 0 2 Type II Slurry $33,215 2025-26 Walnut Pl 5260 Walnut Pl Irvine Ave Aliso Ave AAC E 4 535 35 18,725 87 82 18 0 Type II Slurry $27,339 2025-26 Walnut St 5080 Walnut St Newport Blvd Fullerton Ave AAC E 3 670 37 24,790 87 57 14 29 Type II Slurry $36,193 2025-26 Warren 9420 Warren Ln Baker St Stonefield St AC E 15 1,857 37 68,709 75 14 86 0 Type II Slurry $100,315 2025-26 Waterman 6640 Waterman Way Cul-de-sac 23rd St AAC E 25 245 37 11,239 87 80 20 0 Type II Slurry $16,409 2025-26 Watson 9470 Watson Ave Loren Ln Dublin St AC E 15 3,083 37 114,071 80 10 89 1 Type II Slurry $166,544 2025-26 Waxwing 7610 Waxwing Ct Hummingbird Dr Cul-de-sac AAC E 11 385 37 16,419 80 77 23 0 Type II Slurry $23,972 2025-26 Wellesley 7280 Wellesley Ln Columbia Dr Cul-de-sac AAC E 10 372 33 14,450 74 33 57 10 Type II Slurry $21,097 2025-26 WstmnstrPl 6970 Westminster Pl Del Mar Ave Cul-de-sac AC E 26 529 33 19,631 66 23 51 26 AC Grind-Overlay $90,303 2025-26 White Oak 8450 White Oak St Jacaranda Ave Redwood Ave AC E 21 540 38 20,552 48 22 71 7 AC Grind-Overlay $94,539 2025-26 Wilson 5790 Wilson St State Ave Placentia Ave AC E 18 2,422 37 92,885 82 47 42 11 Type II Slurry $135,612 2025-26 Wilson 6720 Wilson St Newport Blvd Orange Ave AAC E 25 1,326 37 49,062 67 19 73 8 AC Grind-Overlay $225,685 2025-26 Wimbledon 11010 Wimbledon Way South Coast Dr Sunflower Ave AC E 14 2,440 37 90,280 81 81 17 2 Type II Slurry $131,809 2025-26 Wintergrn 8630 Wintergreen Pl Coral Ave Mace Ave AAC E 23 900 37 33,300 86 23 77 0 Type II Slurry $48,618 2025-26 Woodland 5290 Woodland Pl Tustin Ave Cul-de-sac AAC E 4 450 37 18,824 83 63 37 0 Type II Slurry $27,483 2025-26 Yale 7270 Yale Pl Princeton Dr Bowling Green Dr AAC E 10 290 37 10,730 85 100 0 0 Type II Slurry $15,666 2025-26 Yellowstn 11560 Yellowstone Dr Paularino Ave Olympic Ave AAC E 31 1,569 37 57,803 71 49 48 3 Type II Slurry $84,392 $5,796,294
2026-27 21st 5450 21st St Newport Blvd Santa Ana Ave AAC E 3 2,690 37 99,530 84 49 21 30 Type II Slurry $150,290 2026-27 21st 5460 21st St Santa Ana Ave Tustin Ave AAC E 4 1,300 37 48,100 81 46 19 35 Type II Slurry $72,631 2026-27 Begonia 11260 Begonia Ave Smalley Rd Fuschia St AC E 27 775 37 28,103 80 61 39 0 Type II Slurry $42,436 2026-27 Begonia 11320 Begonia Ave Fuchsia St Azalea St AC E 27 1,069 37 39,553 84 85 15 0 Type II Slurry $59,725 2026-27 Bermuda 8230 Bermuda Dr Labrador Dr Gisler Ave AC E 23 1,194 37 46,221 77 34 42 24 Type II Slurry $69,794 2026-27 Bimini 8540 Bimini Pl Cul-de-sac Baker St AC E 21 783 37 31,145 43 22 64 14 AC Grind-Overlay $148,873 2026-27 Bismark 10700 Bismark Way Cul-de-sac Van Buren Ave AAC E 16 435 37 18,149 80 78 22 0 Type II Slurry $27,405 2026-27 Blue Bird 7620 Blue Bird Cir Hummingbird Dr Cul-de-sac AAC E 11 722 37 28,888 78 60 39 1 Type II Slurry $43,621 2026-27 BoaVistaC 7820 Boa Vista Cir Cul-de-sac Stromboli Rd AC E 21 496 37 20,526 44 18 80 2 AC Grind-Overlay $98,114 2026-27 BoaVistaDr 7670 Boa Vista Dr Kornat Dr Mesa Verde Dr AC E 22 1,800 37 66,600 53 14 78 8 AC Grind-Overlay $318,348 2026-27 Bonnie 6770 Bonnie Pl Santa Isabel Ave Cul-de-sac AC E 26 320 33 12,734 60 30 70 0 AC Grind-Overlay $60,869 2026-27 Cape Verde 8820 Cape Verde Pl Cul-de-sac Gisler Ave AAC E 22 260 37 11,794 83 88 0 12 Type II Slurry $17,809 2026-27 Capital 5754 Capital St Republic Ave National Ave AAC E 18 656 37 24,735 73 13 87 0 Type II Slurry $37,350 2026-27 Capital 5980 Capital St Pomona Ave E'ly end AAC E 19 490 37 18,130 84 100 0 0 Type II Slurry $27,376 2026-27 Capri Cir 8120 Capri Cir Cul-de-sac Capri Ln AC E 22 280 37 12,534 87 96 0 4 Type II Slurry $18,926 2026-27 Capri Ln 8110 Capri Ln Mesa Verde Dr Cul-de-sac AC E 22 1,328 37 51,310 78 43 52 5 Type II Slurry $77,478 2026-27 Caraway 8710 Caraway Dr Coral Ave Cinnamon Ave AC E 23 1,426 37 52,762 55 38 57 5 AC Grind-Overlay $252,202 2026-27 Carlton 6820 Carlton Pl Wilson St Santa Isabel Ave AAC E 25 500 37 18,500 86 35 64 1 Type II Slurry $27,935 2026-27 Carmel 11030 Carmel Dr South Coast Dr Salinas Ave AC E 14 448 37 16,576 74 44 56 0 Type II Slurry $25,030 2026-27 Danielle 20020 Danielle Dr Wimbeldon Way Deedee Dr AC E 389 25 9,725 87 75 23 2 Type II Slurry $14,685 2026-27 Darrel 5870 Darrel St Republic Ave Federal Ave AC E 18 1,890 37 69,930 64 2 91 7 AC Grind-Overlay $334,265 2026-27 Darrel 6020 Darrel St Pomona Ave Meyer Pl AC E 19 1,050 37 38,850 67 18 72 10 AC Grind-Overlay $185,703 2026-27 Dartmouth 6420 Dartmouth Pl Columbia Dr Cul-de-sac AC E 24 216 37 10,166 75 70 0 30 Type II Slurry $15,351 2026-27 Davis 8735 Davis Pl Monte Vista Ave Cul-de-sac AC E 26 195 33 8,609 79 37 61 2 Type II Slurry $13,000 2026-27 De Soto 9950 De Soto Ave Presidio Dr Coronado Dr AAC E 20 929 37 34,373 86 100 0 0 Type II Slurry $51,903 2026-27 Debra 11100 Debra Dr Deedee Dr Salinas Ave AC E 14 470 37 17,945 82 77 23 0 Type II Slurry $27,097 2026-27 Deedee 11110 Deedee Dr Debra Dr San Jose Ave AC E 14 749 37 27,713 67 31 69 0 AC Grind-Overlay $132,468 2026-27 Denver 10620 Denver Dr Babb St Cul-de-sac AAC E 16 747 37 29,813 76 89 9 2 Type II Slurry $45,018 2026-27 Fuschia 11380 Fuschia St Carnation Ave Begonia Ave AC E 27 230 37 8,510 86 69 31 0 Type II Slurry $12,850 2026-27 Galway 9404 Galway Ln College Ave Killybrooke Ln AC E 15 370 37 13,690 64 6 94 0 AC Grind-Overlay $65,438 2026-27 Gannet 7430 Gannet Dr Swan Dr Pelican Pl AC E 11 890 37 32,930 86 48 17 35 Type II Slurry $49,724 2026-27 Garfield 10570 Garfield Ave Cul-de-sac Paularino Ave AAC E 16 763 37 30,405 85 98 0 2 Type II Slurry $45,912 2026-27 Geranium 11290 Geranium Ln Poppy Cir Begonia Ave AC E 27 390 37 14,430 83 85 15 0 Type II Slurry $21,789 2026-27 Gibraltar 8290 Gibraltar Ave Labrador Dr Gisler Ave AC E 23 2,089 37 77,293 85 48 0 52 Type II Slurry $116,712 2026-27 Gisler 9690 Gisler Ave Harbor Blvd College Ave AAC E 15 812 36 29,132 79 41 59 0 Type II Slurry $43,989 2026-27 Gisler 9700 Gisler Ave College Ave 1000' E'ly AAC E 15 1,005 22 24,236 74 30 46 24 Type II Slurry $36,596 2026-27 Gisler 9704 Gisler Ave 1000' e/o College Ave E'ly end AAC E 15 735 22 15,135 55 52 40 8 AC Grind-Overlay $72,345 2026-27 Jamaica 8170 Jamaica Rd Country Club Dr Cul-de-sac AC E 22 600 37 22,200 64 31 69 0 AC Grind-Overlay $106,116 2026-27 Jamaica 8175 Jamaica Rd Madeira Ave Country Club Dr AC E 23 280 37 10,360 85 84 0 16 Type II Slurry $15,644 2026-27 Jasmine 11450 Jasmine Cir Larkspur St Cul-de-sac AC E 27 440 37 18,454 87 70 0 30 Type II Slurry $27,866 2026-27 Java 8080 Java Rd Tahiti Dr Mesa Verde Dr AC E 21 1,053 37 38,920 82 58 40 2 Type II Slurry $58,769 2026-27 Jefferson 10890 Jefferson Ave Cheyenne St Concord st AAC E 16 698 37 26,355 82 81 18 1 Type II Slurry $39,796
232
City of Costa Mesa, CA
Forecast Maintenance / Rehabilitation (FMR) Report - FY 2024-31 Sorted by Rank, FY, Name Order (A-Z)
FY BranchID Sec ID Name From To Type Rank Zone L W Area PCI PCI Pct Climate PCI Pct Load PCI Pct Other Maint. Type Total $ 2026-27 Jeffrey 11470 Jeffrey Dr Baker St Paularino Ave AC E 13 960 37 35,520 74 36 53 11 Type II Slurry $53,635 2026-27 Jennifer 11480 Jennifer Ln Jeffrey Dr Cul-de-sac AC E 13 290 37 12,904 85 83 17 0 Type II Slurry $19,485 2026-27 Johnson 10800 Johnson Ave Paularino Ave Cheyenne St AAC E 16 800 37 29,600 81 87 13 0 Type II Slurry $44,696 2026-27 Miner 6140 Miner St Cul-de-sac Wilson St AC E 19 1,250 37 48,424 81 22 58 20 Type II Slurry $73,120 2026-27 Mission 10015 Mission Dr Mendoza Dr La Salle Ave AAC E 20 1,300 37 48,100 84 81 19 0 Type II Slurry $72,631 2026-27 Monaco 6790 Monaco Terr Riviera Dr Monte Vista Ave AC E 26 900 33 29,700 69 28 60 12 Type II Slurry $44,847 2026-27 Monroe 10860 Monroe Way Cheyenne Ave Cul-de-sac AAC E 16 470 37 19,762 75 73 27 0 Type II Slurry $29,841 2026-27 Monrovia 25 Monrovia Ave 20th St Victoria St Frontage Road AC E 1 1,982 33 65,406 74 34 51 15 Type II Slurry $98,763 2026-27 Monrovia 5880 Monrovia Ave Wilson St Joann St AAC E 18 476 37 18,428 85 100 0 0 Type II Slurry $27,826 2026-27 MonteVista 6910 Monte Vista Ave Newport Blvd Orange Ave AAC E 26 1,350 37 49,950 81 49 49 2 Type II Slurry $75,425 2026-27 MonteVista 6930 Monte Vista Ave Santa Ana Ave Irvine Ave AAC E 26 1,314 37 48,618 82 24 63 13 Type II Slurry $73,413 2026-27 Orange 2290 Orange Ave 15th St 16th St AAC E 8 1,320 36 47,520 84 53 47 0 Type II Slurry $71,755 2026-27 Orange 2300 Orange Ave 16th St 17th St AAC E 8 1,313 36 46,818 83 52 13 35 Type II Slurry $70,695 2026-27 Orange 2310 Orange Ave 17th St 18th St AC E 8 1,322 36 46,092 87 64 28 8 Type II Slurry $69,599 2026-27 Orange 2340 Orange Ave 19th St 20th St AC E 3 1,323 36 46,628 78 89 9 2 Type II Slurry $70,408 2026-27 Orange 2350 Orange Ave 20th St 21st St AC E 3 1,318 36 46,498 78 61 0 39 Type II Slurry $70,212 2026-27 Orange 2360 Orange Ave 21st St 22nd St AC E 3 1,330 36 45,880 80 84 1 15 Type II Slurry $69,279 2026-27 Raymond 4120 Raymond Ave Magnolia St 19th St AAC E 9 996 37 36,852 78 82 5 13 Type II Slurry $55,647 2026-27 Raymond 4130 Raymond Ave 19th St 20th St AAC E 4 1,300 37 48,100 83 74 26 0 Type II Slurry $72,631 2026-27 Redding 11080 Redding Ave Visalia Dr San Leandro Ln AC E 14 873 37 32,301 85 61 36 3 Type II Slurry $48,775 2026-27 Redwing 7600 Redwing Cir Hummingbird Dr Cul-de-sac AAC E 11 260 37 11,794 78 80 20 0 Type II Slurry $17,809 2026-27 Republic 4570 Republic Ave Union Ave Victoria St Frontage Road AC E 1 500 33 16,500 85 53 22 25 Type II Slurry $24,915 2026-27 Republic 5690 Republic Ave Senate St Wilson St AAC E 18 500 37 18,500 84 31 55 14 Type II Slurry $27,935 2026-27 Republic 5700 Republic Ave Wilson St Joann St AAC E 18 500 37 18,500 82 52 48 0 Type II Slurry $27,935 2026-27 Sicily 8270 Sicily Ave Sumatra Pl Gisler Ave AC E 23 800 37 29,600 71 9 81 10 Type II Slurry $44,696 2026-27 Skylark 7560 Skylark Cir Cul-de-sac Kinglet Ct AAC E 11 198 37 9,216 76 87 13 0 Type II Slurry $13,916 2026-27 Smalley 11180 Smalley Rd Salinas Ave Sunflower Ave AAC E 27 1,526 36 59,055 81 54 44 2 Type II Slurry $89,173 2026-27 Sonora 10200 Sonora Rd La Salle Ave Velasco Ln AAC E 20 770 37 28,490 73 33 67 0 Type II Slurry $43,020 2026-27 Capella S 7690 South Capella Ct Europa Dr North Capella Ct AC E 22 740 37 30,224 83 70 23 7 Type II Slurry $45,638 2026-27 Springfld 10820 Springfield St Hayes Ave Cheyenne St AAC E 16 600 37 23,150 78 59 40 1 Type II Slurry $34,957 2026-27 Starbird 7630 Starbird Dr Tanager Dr Cul-de-sac AAC E 11 785 37 31,219 78 59 40 1 Type II Slurry $47,141 2026-27 State 4350 State Ave Grove Pl Oak St AC E 1 560 33 18,480 69 26 73 1 Type II Slurry $27,905 2026-27 State 5660 State Ave Cul-de-sac Wilson St AAC E 18 1,240 33 43,094 76 62 0 38 Type II Slurry $65,072 2026-27 Stonefield 9590 Stonefield St Killybrooke Ln Limerick Ln AC E 15 530 37 19,335 75 24 72 4 Type II Slurry $29,196 2026-27 Tustin 2550 Tustin Ave 15th St 16th St AC E 9 1,300 36 46,800 70 27 58 15 Type II Slurry $70,668 2026-27 Tustin 2560 Tustin Ave 16th St 17th St AC E 9 1,300 36 46,800 87 50 47 3 Type II Slurry $70,668 2026-27 Tustin 2590 Tustin Ave 19th St 20th St AAC E 4 1,322 36 47,592 81 63 37 0 Type II Slurry $71,864 2026-27 Tustin 2600 Tustin Ave 20th St Emerson St AAC E 4 820 36 29,520 72 50 48 2 Type II Slurry $44,575 2026-27 Tyler 10680 Tyler Way Cul-de-sac Austin St AAC E 16 438 37 18,380 79 80 19 1 Type II Slurry $27,754 2026-27 Valley Rd 4420 Valley Rd Aviemore Terr Sea Bluff Dr AAC E 1 604 37 22,348 78 77 15 8 Type II Slurry $33,745 2026-27 Valley Rd 4470 Valley Rd Sea Bluff Dr Victoria St AAC E 1 598 37 22,126 79 86 14 0 Type II Slurry $33,410 $5,213,923
2027-28 Airport 11930 Airport Loop Dr Red Hill Ave Cul-de-sac AC E 29 1,726 60 107,558 79 79 18 3 Type II Slurry $168,866 2027-28 Airway 11800 Airway Ave Clinton Ave Fischer Ave AC E 29 2,721 60 276,209 70 63 34 3 Type II Slurry $433,648 2027-28 Airway 11805 Airway Ave Fischer Ave Paularino Ave AC E 29 1,852 60 276,209 71 72 24 4 Type II Slurry $433,648 2027-28 Airway 11810 Airway Ave Paularino Ave Airport Loop Dr AC E 29 2,306 60 139,282 80 75 11 14 Type II Slurry $218,673 2027-28 Alanzo 10080 Alanzo Ln Cul-de-sac Mission Dr AAC E 20 200 33 8,774 80 46 9 45 Type II Slurry $13,775 2027-28 Aliso 2780 Aliso Ave 16th St Cambridge Cir AAC E 9 873 37 32,301 72 41 54 5 Type II Slurry $50,713 2027-28 Aliso 5270 Aliso Ave Walnut Pl Esther St AAC E 4 330 37 12,210 85 73 27 0 Type II Slurry $19,170 2027-28 Aliso 5310 Aliso Ave 20th St Cul-de-sac AAC E 4 789 37 31,367 78 37 7 56 Type II Slurry $49,246 2027-28 Allegheny 11520 Allegheny Ave Canadian Dr Yellowstone Dr AAC E 31 599 37 22,163 76 80 19 1 Type II Slurry $34,796 2027-28 Alva 5200 Alva Ln Santa Ana Ave Raymond Ave AAC E 4 650 37 24,050 84 95 5 0 Type II Slurry $37,759 2027-28 American 5640 American Ave Victoria St State Ave AAC E 18 980 37 36,260 79 43 53 4 Type II Slurry $56,928 2027-28 AmericanPL 5650 American Pl American Ave Cul-de-sac AC E 18 255 37 11,609 47 22 78 0 AC Grind-Overlay $57,697 2027-28 Amherst Pl 6390 Amherst Pl Columbia Dr Cul-de-sac AC E 24 210 37 9,944 75 21 63 16 Type II Slurry $15,612 2027-28 Amherst Rd 6380 Amherst Rd Notre Dame Dr Columbia Dr AC E 24 575 37 22,835 61 13 85 2 AC Grind-Overlay $113,490 2027-28 Andover 6480 Andover Pl Nassau Rd Cul-de-sac AC E 24 360 37 15,494 82 55 45 0 Type II Slurry $24,326 2027-28 Andover 7180 Andover Pl Cul-de-sac Bucknell Rd AAC E 10 370 37 15,864 78 98 0 2 Type II Slurry $24,906 2027-28 Andros 8490 Andros St Elm Ave Samar Pl AC E 21 840 37 31,080 84 34 0 66 Type II Slurry $48,796 2027-28 Boston 10750 Boston Way Cul-de-sac Charldston St AC E 16 260 37 12,380 58 29 66 5 AC Grind-Overlay $61,529 2027-28 Bowdoin 7170 Bowdoin Pl Cul-de-sac Bucknell Rd AAC E 10 360 37 15,494 82 97 0 3 Type II Slurry $24,326 2027-28 Bowling 7260 Bowling Green Dr Hanover Dr Yale Pl AC E 10 1,176 37 43,512 64 55 40 5 AC Grind-Overlay $216,255 2027-28 Bray 9670 Bray Ln McCormack St Londonderry St AC E 15 614 37 22,968 81 14 65 21 Type II Slurry $36,060 2027-28 BrentwdPl 6890 Brentwood Pl Cul-de-sac Brentwood St AC E 26 145 37 7,539 79 67 31 2 Type II Slurry $11,836
233
City of Costa Mesa, CA
Forecast Maintenance / Rehabilitation (FMR) Report - FY 2024-31 Sorted by Rank, FY, Name Order (A-Z)
FY BranchID Sec ID Name From To Type Rank Zone L W Area PCI PCI Pct Climate PCI Pct Load PCI Pct Other Maint. Type Total $ 2027-28 BrentwdSt 6880 Brentwood St Norse St Santa Ana Ave AAC E 26 1,290 37 47,730 82 78 20 2 Type II Slurry $74,936 2027-28 Briggs 11880 Briggs Ave Pullman St Red Hill Ave AC E 29 730 60 43,800 73 79 21 0 Type II Slurry $68,766 2027-28 Cinnamon 8720 Cinnamon Ave Caraway Dr Gisler Ave AC E 23 1,300 37 48,100 75 26 68 6 Type II Slurry $75,517 2027-28 Cleveland 10490 Cleveland Ave Cul-de-sac Paularino Ave AAC E 16 749 37 29,887 74 100 0 0 Type II Slurry $46,923 2027-28 Clinton 11790 Clinton Ave Red Hill Ave Cul-de-sac AC E 29 1,275 40 53,150 84 85 14 1 Type II Slurry $83,446 2027-28 Club House 7890 Club House Rd Mesa Verde Dr W N'ly end at Golf Course Parking Lot AAC E 22 750 37 27,750 57 34 66 0 AC Grind-Overlay $137,918 2027-28 Club Mesa 7060 Club Mesa Pl Cul-de-sac Mesa Dr AAC E 26 490 33 18,344 86 78 19 3 Type II Slurry $28,800 2027-28 Colby 7140 Colby Pl Cul-de-sac Bucknell Rd AAC E 10 351 37 15,161 76 83 17 0 Type II Slurry $23,803 2027-28 Colgate 6350 Colgate Dr Wake Forest Rd Villanova Rd AC E 24 1,131 37 41,847 75 45 23 32 Type II Slurry $65,700 2027-28 Colleen 20000 Colleen Pl Santa Ana Ave CDS AC E 554 37 21,586 76 56 41 3 Type II Slurry $33,890 2027-28 CollegeAve 9355 College Ave Baker St Gisler Ave AC E 15 2,500 37 92,500 72 7 93 0 Type II Slurry $145,225 2027-28 CollegeDr 6320 College Dr Wake Forest Rd Cul-de-sac AC E 24 1,741 37 66,591 84 68 30 2 Type II Slurry $104,548 2027-28 Columbia 6360 Columbia Dr Wake Forest Rd Loyola Rd AC E 10 1,126 37 41,662 68 30 65 5 AC Grind-Overlay $207,060 2027-28 Columbia 6440 Columbia Dr Fair Dr Hanover Dr AC E 10 1,148 37 42,476 56 22 75 3 AC Grind-Overlay $211,106 2027-28 Concord 10850 Concord St Pierce Ave Jefferson Ave AAC E 16 1,045 36 39,269 78 83 17 0 Type II Slurry $61,652 2027-28 Congress 5680 Congress St State Ave Placentia Ave AAC E 18 2,500 33 82,500 80 32 67 1 Type II Slurry $129,525 2027-28 Congress 5910 Congress St W'ly end Raleigh Ave AC E 19 456 37 16,872 83 100 0 0 Type II Slurry $26,489 2027-28 Congress 5960 Congress St Pomona Ave Puente Ave AAC E 19 520 37 19,240 82 100 0 0 Type II Slurry $30,207 2027-28 Elm 8330 Elm Ave Andros St Royal Palm Dr AC E 21 897 37 33,189 67 20 63 17 AC Grind-Overlay $164,949 2027-28 Elm 8340 Elm Ave Royal Palm Dr Harbor Blvd AC E 21 800 37 29,600 71 64 0 36 Type II Slurry $46,472 2027-28 Elmhurst 7110 Elmhurst Ln Cul-de-sac Carnegie Ave AC E 10 351 33 13,723 85 93 0 7 Type II Slurry $21,545 2027-28 Enterprise 11600 Enterprise St Baker St Paularino Ave AC E 12 800 37 29,600 83 52 26 22 Type II Slurry $46,472 2027-28 Francis 10240 Francis Ln Magellan St Loreto Ave AC E 20 864 37 32,968 84 96 0 4 Type II Slurry $51,760 2027-28 Fullerton 3510 Fullerton Ave 17th St Cabrillo St AAC E 8 478 37 17,686 84 69 31 0 Type II Slurry $27,767 2027-28 Fullerton 3930 Fullerton Ave 18th St 19th St AAC E 8 1,300 33 42,900 83 94 0 6 Type II Slurry $67,353 2027-28 Fullerton 3940 Fullerton Ave 20th St Bay St AAC E 3 620 36 22,320 52 16 84 0 AC Grind-Overlay $110,930 2027-28 Fullerton 3950 Fullerton Ave 19th St 20th St AAC E 3 1,320 33 43,560 83 85 15 0 Type II Slurry $68,389 2027-28 Junipero 9880 Junipero Dr Arlington Dr Presidio Dr AC E 20 1,119 60 67,140 70 35 56 9 Type II Slurry $105,410 2027-28 Junipero 9890 Junipero Dr Presidio Dr Sutter Way AAC E 20 1,730 37 27,010 72 60 37 3 Type II Slurry $42,406 2027-28 Junipero 9894 Junipero Dr Sutter Way La Salle Ave AC E 20 1,000 37 37,000 77 71 27 2 Type II Slurry $58,090 2027-28 Kalmus 11850 Kalmus Dr Airway Ave Red Hill Ave AC E 29 645 40 27,150 80 77 23 0 Type II Slurry $42,626 2027-28 Kalmus 11851 Kalmus Dr Red Hill Ave Pullman St AC E 29 1,615 60 101,768 68 81 17 2 Cape Seal $195,395 2027-28 Kerry 9640 Kerry Ln Killarney Ln Londonderry St AC E 15 730 37 27,210 60 26 69 5 AC Grind-Overlay $135,234 2027-28 Killarney 9630 Killarney Ln Londonderry St Kerry Ln AC E 15 594 37 21,978 72 16 73 11 Type II Slurry $34,505 2027-28 Kinglet 7540 Kinglet Ct Tanager Dr (West) Tanager Dr (East) AAC E 11 1,515 37 56,273 84 83 17 0 Type II Slurry $88,349 2027-28 McCormack 9660 McCormack St Cork Ln Fairview Rd AC E 15 491 37 18,342 78 13 44 43 Type II Slurry $28,797 2027-28 McCormick 11940 McCormick Ave Pullman St Airway Ave AC E 29 1,555 40 62,200 77 61 38 1 Type II Slurry $97,654 2027-28 McKinley 10870 McKinley Way Cheyenne Ave Cul-de-sac AAC E 16 470 37 19,378 76 57 42 1 Type II Slurry $30,423 2027-28 Mendoza 9920 Mendoza Dr Lorenzo Ave El Camino Dr AC E 20 1,451 37 58,090 81 51 45 4 Type II Slurry $91,201 2027-28 Mendoza 9924 Mendoza Dr Mission Dr Baker St AC E 20 1,010 37 37,370 77 75 0 25 Type II Slurry $58,671 2027-28 Merrill 5540 Merrill Pl Elden Ave Orange Ave AC E 3 650 37 24,050 76 40 16 44 Type II Slurry $37,759 2027-28 Mesa 7080 Mesa Dr Newport Blvd Orange Ave AAC E 26 1,342 36 48,312 82 34 31 35 Type II Slurry $75,850 2027-28 Mesa 7090 Mesa Dr Orange Ave Santa Ana Ave AC E 26 1,320 36 47,520 85 50 48 2 Type II Slurry $74,606 2027-28 Pierce 10840 Pierce Ave Cheyenne Ave Concord St AAC E 16 698 36 27,082 72 82 17 1 Type II Slurry $42,519 2027-28 Pierpont 11660 Pierpont Dr Ludington St Sturgeon Dr AAC E 12 1,787 37 66,119 87 100 0 0 Type II Slurry $103,807 2027-28 Pine 4320 Pine Pl Federal Ave Cul-de-sac AAC E 1 200 27 7,574 82 77 0 23 Type II Slurry $11,891 2027-28 Pitcairn 7830 Pitcairn Dr Cul-de-sac Corvo Pl AC E 21 1,795 37 66,415 79 29 71 0 Type II Slurry $104,272 2027-28 Platte 11500 Platte Dr Paularino Ave Roanoke Ln AAC E 31 950 37 35,150 85 69 30 1 Type II Slurry $55,186 2027-28 Plum 4310 Plum Pl Federal Ave Cul-de-sac AAC E 1 200 27 7,574 72 91 9 0 Type II Slurry $11,891 2027-28 Pomona 6010 Pomona Ave Wilson St Joann St AAC E 19 535 37 19,795 87 97 0 3 Type II Slurry $31,078 2027-28 Ponderosa 8310 Ponderosa St Andros St Royal Palm Dr AC E 21 1,067 37 39,479 56 18 81 1 AC Grind-Overlay $196,211 2027-28 Ponderosa 8320 Ponderosa St Royal Palm Dr Harbor Blvd AC E 21 790 37 29,230 76 100 0 0 Type II Slurry $45,891 2027-28 Poppy 11280 Poppy Cir Lavender Ln Geranium St AC E 27 350 37 15,125 82 63 37 0 Type II Slurry $23,746 2027-28 Post 10410 Post Rd Babb St Milbro St AAC E 20 780 37 28,860 86 46 54 0 Type II Slurry $45,310 2027-28 Scenic 9760 Scenic Dr Hyland Ave Harbor Blvd AC E 30 1,891 54 102,114 43 44 39 17 AC Grind-Overlay $507,507 2027-28 Sea Bluff 4440 Sea Bluff Dr Gleneagles Terr Canyon Dr AAC E 1 1,154 37 42,698 82 63 19 18 Type II Slurry $67,036 2027-28 Senate 5970 Senate St Pomona Ave Puente Ave AC E 19 519 37 19,203 85 100 0 0 Type II Slurry $30,149 2027-28 Serang 8000 Serang Pl Tabago Pl Mesa Verde Dr AC E 21 1,049 37 38,813 75 100 0 0 Type II Slurry $60,936 2027-28 Serra 9980 Serra Way Fremont Ln Coronado Dr AC E 20 590 37 21,830 68 21 71 8 AC Grind-Overlay $108,495 2027-28 Shamrock 9500 Shamrock Ln Dublin St Watson Ln AC E 15 518 37 19,166 65 19 46 35 AC Grind-Overlay $95,255 2027-28 Shannon 9408 Shannon Ln College Ave Watson Ln AC E 15 500 37 18,500 60 7 93 0 AC Grind-Overlay $91,945 2027-28 Shantar 7420 Shantar Dr Adams Ave Balearic Dr AC E 22 898 37 35,813 62 37 45 18 AC Grind-Overlay $177,991 2027-28 Sharon 9610 Sharon Ln Stonefield St Londonderry St AC E 15 576 37 21,562 87 20 80 0 Type II Slurry $33,852 2027-28 SherwoodPl 5420 Sherwood Pl Cul-de-sac Westminster Ave AAC E 3 332 33 13,130 81 70 28 2 Type II Slurry $20,614
234
City of Costa Mesa, CA
Forecast Maintenance / Rehabilitation (FMR) Report - FY 2024-31 Sorted by Rank, FY, Name Order (A-Z)
FY BranchID Sec ID Name From To Type Rank Zone L W Area PCI PCI Pct Climate PCI Pct Load PCI Pct Other Maint. Type Total $ 2027-28 SherwoodSt 5430 Sherwood St Westminster Ave Santa Ana Ave AAC E 3 658 37 24,346 80 58 21 21 Type II Slurry $38,223 2027-28 Van Buren 10645 Van Buren Ave Paularino Ave Charleston St AAC E 14 1,485 36 53,239 86 86 14 0 Type II Slurry $83,585 2027-28 Vanguard 6570 Vanguard Way Newport Blvd (SB) Fair Dr AC E 24 2,270 60 136,200 87 74 16 10 Type II Slurry $213,834 2027-28 Velasco 10260 Velasco Ln Sonara Rd Saint Clair St AAC E 20 910 37 34,170 82 82 0 18 Type II Slurry $53,647 2027-28 Velasco 10264 Velasco Ln Magellan St Sonora Rd AAC E 20 240 37 8,880 80 100 0 0 Type II Slurry $13,942 2027-28 VictoriaPl 4490 Victoria Pl Pacific Ave Victoria St AAC E 18 299 37 10,313 81 27 73 0 Type II Slurry $16,191 2027-28 VictoriaFR 4550 Victoria St Frontage Road W'ly Cul-de-sac E'ly Cul-de-sac AC E 1 2,177 37 84,897 66 65 30 5 Cape Seal $163,002 2027-28 Virginia 6580 Virginia Pl Newport Blvd Santa Ana Ave AC E 25 2,658 37 98,346 62 46 43 11 AC Grind-Overlay $488,780 2027-28 Visalia 11070 Visalia Dr San Leandro Ln Redding Ave AC E 14 996 37 38,352 77 50 50 0 Type II Slurry $60,213 2027-28 Vistabaya 20010 Vista Baya Santa Ana Ave CDS AC E 557 37 23,189 75 66 34 0 Type II Slurry $36,407 2027-28 Wakeham 11008 Wakeham Pl Cul-de-sac Bear St AAC E 27 1,290 37 49,904 45 25 37 38 AC Grind-Overlay $248,023 $8,791,603
2028-29 16th Pl 2620 16th Pl Santa Ana Ave Tustin Ave AAC E 9 1,320 37 48,840 84 41 45 14 Type II Slurry $80,098 2028-29 16th Pl 2622 16th Pl Orange Ave Santa Ana Ave AAC E 9 1,350 37 49,950 83 51 49 0 Type II Slurry $81,918 2028-29 16th Pl 2624 16th Pl Tustin Ave Irvine Ave AAC E 9 1,320 37 48,840 77 45 45 10 Type II Slurry $80,098 2028-29 16th 2260 16th St Orange Ave Santa Ana Ave AAC E 8 1,320 37 48,840 77 44 54 2 Type II Slurry $80,098 2028-29 16th 2270 16th St Santa Ana Ave Tustin Ave AAC E 9 1,300 37 48,100 75 40 60 0 Type II Slurry $78,884 2028-29 16th 2280 16th St Tustin Ave Irvine Ave AAC E 9 1,334 36 48,024 75 26 58 16 Type II Slurry $78,759 2028-29 18th 3760 18th St Newport Blvd Orange Ave AC E 8 1,360 45 61,200 79 59 17 24 Type II Slurry $100,368 2028-29 18th 3770 18th St Orange Ave Santa Ana Ave AAC E 8 1,323 36 47,628 88 50 50 0 Type II Slurry $78,110 2028-29 18th 3780 18th St Santa Ana Ave Irvine Ave AAC E 9 2,643 36 95,148 88 38 37 25 Type II Slurry $156,043 2028-29 Balearic 7760 Balearic Dr Boa Vista Dr Suva Cir AC E 22 884 37 32,708 81 70 30 0 Type II Slurry $53,641 2028-29 Ballow 10100 Ballow Ln El Camino Dr Mission Dr AAC E 20 440 36 16,240 82 74 0 26 Type II Slurry $26,634 2028-29 Bay 5300 Bay St Tustin Ave Aliso Ave AAC E 4 672 37 24,864 85 79 16 5 Type II Slurry $40,777 2028-29 Bay 5340 Bay St NB Newport Blvd Frontage Road Orange Ave AAC E 3 1,354 36 48,744 82 49 49 2 Type II Slurry $79,940 2028-29 Bay 5380 Bay St Westminster Ave Santa Ana Ave AAC E 3 671 37 24,827 84 59 33 8 Type II Slurry $40,716 2028-29 Bear 10340 Bear St Bristol St Baker St AC E 20 2,600 31 79,300 85 82 16 2 Type II Slurry $130,052 2028-29 Belfast 9520 Belfast Ave Killybrooke Ln Fairview Rd AAC E 15 1,850 36 66,600 88 45 52 3 Type II Slurry $109,224 2028-29 Cabrillo 3530 Cabrillo St Newport Blvd Orange Ave AAC E 8 1,300 37 48,100 81 82 14 4 Type II Slurry $78,884 2028-29 Cabrillo 3540 Cabrillo St Orange Ave Santa Ana Ave AAC E 8 1,330 37 49,210 79 47 41 12 Type II Slurry $80,704 2028-29 Cabrillo 3550 Cabrillo St Santa Ana Ave Raymond Ave AAC E 9 642 37 23,754 81 58 11 31 Type II Slurry $38,957 2028-29 Cabrillo 3680 Cabrillo St Tustin Ave Irvine Ave AAC E 9 1,340 37 49,580 77 64 15 21 Type II Slurry $81,311 2028-29 Cadillac 9730 Cadillac Ave Sunflower Ave Cul-de-sac AC E 30 1,900 37 72,474 67 41 44 15 AC Grind-Overlay $374,691 2028-29 Calvert 7680 Calvert Ave Europa Dr Shantar Dr AC E 22 950 37 35,150 52 49 51 0 AC Grind-Overlay $181,726 2028-29 Canyon 4545 Canyon Dr Wilson St 700' n/o Wilson St AC E 18 700 37 25,900 88 63 18 19 Type II Slurry $42,476 2028-29 Cardinal 7480 Cardinal Dr Swan Cir Oriole Dr AAC E 11 880 37 32,560 88 88 0 12 Type II Slurry $53,398 2028-29 CharleSt 4840 Charle St Bernard St Hamilton St AC E 2 1,880 37 69,560 87 70 17 13 Type II Slurry $114,078 2028-29 Charleston 10760 Charleston St Boston Way Coolidge Ave AAC E 16 1,090 37 42,732 74 73 25 2 Type II Slurry $70,080 2028-29 Cheyenne 10780 Cheyenne St Coolidge Ave Paularino Ave AAC E 16 2,800 37 104,547 77 76 21 3 Type II Slurry $171,457 2028-29 Chios 7750 Chios Rd Balearic Dr Lemnos Dr AC E 22 530 37 19,860 72 51 42 7 Type II Slurry $32,570 2028-29 Church 4980 Church St 19th St 20th St AAC E 3 1,330 37 49,210 83 62 34 4 Type II Slurry $80,704 2028-29 Continentl 4235 Continental Ave Oak St Victoria St AC E 1 790 33 26,070 85 60 0 40 Type II Slurry $42,755 2028-29 Continentl 5740 Continental Ave Senate St Wilson St AC E 18 530 37 19,610 88 42 58 0 Type II Slurry $32,160 2028-29 Coolidge 10510 Coolidge Ave Baker St Paularino Ave AC E 16 840 21 17,220 80 23 77 0 Type II Slurry $28,241 2028-29 Coolidge 10511 Coolidge Ave Paularino Ave Baker St AC E 16 840 21 17,220 77 16 61 23 Type II Slurry $28,241 2028-29 Coolidge 10770 Coolidge Ave Paularino Ave Charleston St AAC E 16 1,496 36 55,337 79 65 33 2 Type II Slurry $90,753 2028-29 Coral 8640 Coral Ave Wintergreen Pl Caraway Dr AAC E 23 400 37 14,800 88 43 57 0 Type II Slurry $24,272 2028-29 Coral 8740 Coral Ave Caraway Dr Coriander Dr AAC E 23 270 37 9,990 75 34 66 0 Type II Slurry $16,384 2028-29 Coriander 8750 Coriander Dr Coral Ave Cinnamon Ave AC E 23 1,387 37 51,319 38 17 72 11 AC Grind-Overlay $265,319 2028-29 Cork 9650 Cork Ln McCormack St Londonderry St AC E 15 580 37 21,635 60 15 85 0 AC Grind-Overlay $111,853 2028-29 Cornell 6330 Cornell Dr Wake Forest Rd Villanova Rd AC E 24 1,100 37 40,145 74 43 48 9 Type II Slurry $65,838 2028-29 Coronado 9900 Coronado Dr Presido Dr La Salle Ave AAC E 20 1,480 37 54,760 65 47 52 1 AC Grind-Overlay $283,109 2028-29 Date 8730 Date Pl Cinnamon Ave Harbor Blvd AAC E 23 240 60 14,400 88 0 100 0 Type II Slurry $23,616 2028-29 DonnyBrook 9530 Donnybrook Ln Conway Ave Belfast Ave AC E 15 684 37 25,308 88 68 1 31 Type II Slurry $41,505 2028-29 Federal 4300 Federal Ave 19th St Oak St AC E 1 2,560 37 94,720 88 53 39 8 Type II Slurry $155,341 2028-29 Federal 4305 Federal Ave Oak St Victoria St Frontage Road AC E 1 690 37 25,530 87 64 0 36 Type II Slurry $41,869 2028-29 Federal 5890 Federal Ave Wilson St Joann St AC E 18 500 37 18,500 84 100 0 0 Type II Slurry $30,340 2028-29 Fernheath 9440 Fernheath Ln Baker St Watson Ave AC E 15 488 37 18,056 75 16 84 0 Type II Slurry $29,612 2028-29 Fillmore 10550 Fillmore Way Cul-de-sac Cul-de-sac AAC E 16 699 37 30,211 87 100 0 0 Type II Slurry $49,546 2028-29 Fischer 11870 Fischer Ave Pullman St Red Hill Ave AC E 29 1,037 40 41,480 76 76 21 3 Type II Slurry $68,027 2028-29 Fischer 11871 Fischer Ave Red Hill Ave Airway Ave AC E 29 1,037 40 41,480 81 98 0 2 Type II Slurry $68,027 2028-29 Flower 4060 Flower St Santa Ana Ave Irvine Ave AAC E 9 2,620 37 96,940 84 79 21 0 Type II Slurry $158,982 2028-29 Ford 4900 Ford Rd Harbor Blvd Alley #40/#41 AC E 5 866 33 28,578 50 17 66 17 AC Grind-Overlay $147,748 2028-29 Fordham 6210 Fordham Dr Wilson St Wake Forest Rd AC E 24 750 37 28,305 75 4 87 9 Type II Slurry $46,420
235
City of Costa Mesa, CA
Forecast Maintenance / Rehabilitation (FMR) Report - FY 2024-31 Sorted by Rank, FY, Name Order (A-Z)
FY BranchID Sec ID Name From To Type Rank Zone L W Area PCI PCI Pct Climate PCI Pct Load PCI Pct Other Maint. Type Total $ 2028-29 Fordham 6220 Fordham Dr Wake Forest Rd Fair Dr AC E 24 1,830 37 67,710 80 15 76 9 Type II Slurry $111,044 2028-29 Fordham 6230 Fordham Dr Fair Dr Princeton Dr AC E 10 1,265 37 46,805 70 31 44 25 Type II Slurry $76,760 2028-29 Joann 5720 Joann St Placentia Ave Miner St AC E 19 3,160 37 116,920 88 86 0 14 Type II Slurry $191,749 2028-29 Labrador 8220 Labrador Dr Baker St Bermuda Dr AC E 23 1,950 37 72,150 76 60 40 0 Type II Slurry $118,326 2028-29 Lanai 7920 Lanai Dr W'ly end Club House Dr AC E 22 560 37 20,720 68 61 27 12 Cape Seal $41,440 2028-29 Lansing 10830 Lansing Ln Hayes Ave Cheyenne St AAC E 16 819 37 30,303 80 76 22 2 Type II Slurry $49,697 2028-29 Larkspur 11440 Larkspur St Dahlia Ave Carnation Ave AC E 27 747 33 24,651 87 73 20 7 Type II Slurry $40,428 2028-29 Laurie 5350 Laurie Ln Cul-de-sac Bay St AAC E 3 300 37 13,274 84 52 44 4 Type II Slurry $21,769 2028-29 Loreto 10310 Loreto Ave Cortez St Sonora Rd AC E 20 1,162 37 42,994 88 84 0 16 Type II Slurry $70,510 2028-29 Lupine 11360 Lupine Cir Cul-de-sac Goldenrod Dr AC E 27 189 36 8,978 88 100 0 0 Type II Slurry $14,724 2028-29 Marquette 11650 Marquette Cir Ludington St Cul-de-sac AAC E 12 222 37 10,388 88 100 0 0 Type II Slurry $17,036 2028-29 Melody 5330 Melody Ln Cul-de-sac Fullerton Ave AAC E 3 380 37 16,234 88 80 20 0 Type II Slurry $26,624 2028-29 Meyer 5990 Meyer Pl Cul-de-sac Wilson St AC E 19 1,290 37 49,904 88 100 0 0 Type II Slurry $81,843 2028-29 Meyer 6000 Meyer Pl Wilson St Joann St AAC E 19 500 37 18,500 75 28 69 3 Type II Slurry $30,340 2028-29 Milbro 10440 Milbro St Post Rd Baker St AC E 20 630 37 23,310 75 40 51 9 Type II Slurry $38,228 2028-29 Mindanao 8130 Mindanao Dr Pemba Dr Cul-de-sac AAC E 21 670 37 26,964 81 22 78 0 Type II Slurry $44,221 2028-29 Myrtlewood 8440 Myrtlewood St Jacaranda Ave Royal Palm Dr AC E 21 830 37 30,710 88 40 27 33 Type II Slurry $50,364 2028-29 Oregon 9020 Oregon Ave Cul-de-sac California St AAC E 17 1,060 37 41,394 88 91 0 9 Type II Slurry $67,886 2028-29 Presidio 9840 Presidio Dr Lorenzo Ave Junipero Dr AAC E 20 2,460 37 91,020 81 57 0 43 Type II Slurry $149,273 2028-29 Presidio 9850 Presidio Dr Junipero Dr Newport Blvd AAC E 20 1,435 37 53,095 82 92 0 8 Type II Slurry $87,076 2028-29 PresidioSq 9860 Presidio Sq Presidio Dr S'ly end AC E 20 150 37 5,550 39 8 92 0 AC Grind-Overlay $28,694 2028-29 PresidioSq 9865 Presidio Sq Presidio Sq West Presidio Sq East AC E 928 60 55,680 61 49 51 0 AC Grind-Overlay $287,866 2028-29 PresidioSq 9870 Presidio Sq S'ly end Presidio Dr AAC E 20 150 37 5,550 64 29 68 3 AC Grind-Overlay $28,694 2028-29 Primrose 8420 Primrose St Jacaranda Ave Royal Palm Dr AC E 21 769 37 28,326 67 30 42 28 AC Grind-Overlay $146,445 2028-29 Princeton 7210 Princeton Dr Harbor Blvd Oxford Ln AC E 10 1,000 37 37,000 47 11 70 19 AC Grind-Overlay $191,290 2028-29 Princeton 7220 Princeton Dr Oxford Ln Fairview Rd AAC E 10 2,740 37 101,380 80 36 62 2 Type II Slurry $166,263 2028-29 Snt Isabel 6750 Santa Isabel Ave Orange Ave Santa Ana Ave AC E 26 1,320 37 48,840 58 26 73 1 AC Grind-Overlay $252,503 2028-29 Santiago 10280 Santiago Rd Velasco Ln Sonora Rd AAC E 20 921 37 35,077 75 35 65 0 Type II Slurry $57,526 2028-29 SantoTomas 7050 Santo Tomas St Cul-de-sac Santa Ana Ave AAC E 26 687 37 27,593 82 37 63 0 Type II Slurry $45,253 2028-29 Tabago 7990 Tabago Pl Serang Pl Minorca Pl AC E 21 700 37 25,900 80 40 0 60 Type II Slurry $42,476 2028-29 Taft 10730 Taft Way Cul-de-sac Carson St AAC E 16 377 37 15,985 63 53 46 1 AC Grind-Overlay $82,642 2028-29 Tahiti 8060 Tahiti Dr Mesa Verde Dr Java Rd AC E 22 1,090 37 40,330 61 49 51 0 AC Grind-Overlay $208,506 2028-29 Tanager 7520 Tanager Dr Canary Dr Golf Course Dr AAC E 11 2,400 37 88,800 78 51 38 11 Type II Slurry $145,632 2028-29 Taylor 10690 Taylor Way Cul-de-sac Austin St AAC E 16 423 37 17,825 80 59 41 0 Type II Slurry $29,233 2028-29 Teakwood 8480 Teakwood Pl Cul-de-sac Myrtlewood St AC E 21 324 37 14,162 76 28 40 32 Type II Slurry $23,226 $7,611,941
2029-30 20th 4285 20th St Monrovia Ave Federal Ave AC E 1 535 33 17,655 85 42 41 17 Type II Slurry $30,014 2029-30 20th 5240 20th St Newport Blvd Frontage Road Santa Ana Ave AC E 3 2,650 37 98,050 75 32 61 7 Type II Slurry $166,685 2029-30 20th 5250 20th St Santa Ana Ave Irvine Ave AAC E 4 2,634 37 97,458 85 74 1 25 Type II Slurry $165,679 2029-30 Alaska 9190 Alaska Ave Alabama Cir California St AC E 17 437 37 16,169 89 81 0 19 Type II Slurry $27,487 2029-30 Albatross 7410 Albatross Rd Swan Dr Adams Ave AC E 11 1,344 37 49,728 89 65 22 13 Type II Slurry $84,538 2029-30 Annapolis 10580 Annapolis St Garfield Ave Harding Way AAC E 16 500 37 18,225 86 100 0 0 Type II Slurry $30,983 2029-30 Anza 10060 Anza Ln Cul-de-sac Mission Dr AAC E 20 200 33 8,774 77 100 0 0 Type II Slurry $14,916 2029-30 Arizona 9250 Arizona Ln Cul-de-sac Iowa St AC E 17 364 37 15,642 89 99 0 1 Type II Slurry $26,591 2029-30 Arthur 10460 Arthur Ave Dorset Ln Paularino Ave AAC E 16 269 37 9,953 83 100 0 0 Type II Slurry $16,920 2029-30 Atlanta 10650 Atlanta Way Cul-de-sac Van Buren Ave AAC E 16 440 37 18,454 74 100 0 0 Type II Slurry $31,372 2029-30 Augusta 10660 Augusta St Fairview Rd Van Buren Ave AAC E 16 520 37 19,240 65 51 49 0 AC Grind-Overlay $103,511 2029-30 Austin 10670 Austin St Van Buren Ave Coolidge Ave AAC E 16 782 37 28,934 76 77 23 0 Type II Slurry $49,188 2029-30 Avalon 6280 Avalon St Wilson St Joann St AC E 24 470 36 17,048 84 100 0 0 Type II Slurry $28,982 2029-30 Balmoral 4460 Balmoral Pl S'ly Cul-de-sac Sea Bluff Dr AAC E 1 160 37 8,094 89 95 0 5 Type II Slurry $13,760 2029-30 Bay 4910 Bay St Harbor Blvd Newport Blvd AAC E 5 2,000 37 74,000 89 73 23 4 Type II Slurry $125,800 2029-30 Boise 10710 Boise Way Cul-de-sac Van Buren Ave AC E 16 416 37 17,591 57 81 0 19 Cape Seal $36,589 2029-30 Bowdoin 6470 Bowdoin Pl Nassau Rd Cul-de-sac AC E 24 360 37 15,494 89 100 0 0 Type II Slurry $26,340 2029-30 Colgate 6270 Colgate Dr Wilson St Joann St AC E 24 470 36 17,190 89 80 0 20 Type II Slurry $29,223 2029-30 Cornell 6250 Cornell Dr Wilson St Joann St AC E 24 470 36 17,239 89 69 0 31 Type II Slurry $29,306 2029-30 Damascus 11230 Damascus Cir Smalley Rd Cul-de-sac AAC E 27 560 37 22,894 89 70 19 11 Type II Slurry $38,920 2029-30 Dogwood 4250 Dogwood St Republic Ave Monrovia Ave AAC E 1 843 33 29,038 89 63 37 0 Type II Slurry $49,365 2029-30 Donegal 9570 Donegal Pl Loren Ln Cul-de-sac AC E 15 270 37 12,164 89 65 35 0 Type II Slurry $20,679 2029-30 DonnyBrook 9430 Donnybrook Ln Baker St Watson Ave AC E 15 657 37 24,309 68 14 86 0 AC Grind-Overlay $130,782 2029-30 Dorset 10470 Dorset Ln Cul-de-sac Cleveland Ave AAC E 16 832 37 30,509 79 100 0 0 Type II Slurry $51,865 2029-30 Dorset 9560 Dorset Ln Loren Ln Fairview Rd AC E 15 330 37 12,210 81 29 71 0 Type II Slurry $20,757 2029-30 Drake 10320 Drake Ave Presidio Dr St Clair St AC E 20 1,860 37 68,820 83 97 0 3 Type II Slurry $116,994 2029-30 Dublin 9490 Dublin St Shamrock Ln N'ly end AC E 15 470 37 17,390 63 17 83 0 AC Grind-Overlay $93,558 2029-30 Duke 6490 Duke Pl Nassau Rd Cul-de-sac AC E 24 321 37 14,051 86 53 47 0 Type II Slurry $23,887
236
City of Costa Mesa, CA
Forecast Maintenance / Rehabilitation (FMR) Report - FY 2024-31 Sorted by Rank, FY, Name Order (A-Z)
FY BranchID Sec ID Name From To Type Rank Zone L W Area PCI PCI Pct Climate PCI Pct Load PCI Pct Other Maint. Type Total $ 2029-30 Duke 7190 Duke Pl Cul-de-sac Bucknell Rd AAC E 10 360 37 15,494 84 90 0 10 Type II Slurry $26,340 2029-30 Fuschia 11300 Fuschia St Dahlia Ave Carnation Ave AC E 27 870 37 32,190 89 92 0 8 Type II Slurry $54,723 2029-30 Garlinford 9680 Garlinford St College Ave Killybrooke Ln AAC E 15 846 37 31,302 89 55 41 4 Type II Slurry $53,213 2029-30 Governor 5670 Governor St State Ave Placentia Ave AC E 18 2,460 33 81,180 63 4 92 4 AC Grind-Overlay $436,748 2029-30 Grace 10390 Grace Ln Cul-de-sac Baker St AAC E 20 660 37 26,594 87 31 0 69 Type II Slurry $45,210 2029-30 Grant 10590 Grant Ave Baker St Cul-de-sac AAC E 16 749 37 29,887 81 100 0 0 Type II Slurry $50,808 2029-30 Green 9480 Green St Watson Ave N' End AC E 15 120 37 4,440 47 36 47 17 AC Grind-Overlay $23,887 2029-30 Greenbriar 7240 Greenbriar Ln Princeton Dr Oxford Ln AC E 10 850 37 31,450 80 34 40 26 Type II Slurry $53,465 2029-30 Grove 4340 Grove Pl Cul-de-sac Republic Ave AAC E 1 1,007 33 35,405 89 93 0 7 Type II Slurry $60,189 2029-30 Haiti 8810 Haiti Cir Bahama Pl Cul-de-sac AC E 22 251 37 11,461 67 39 58 3 AC Grind-Overlay $61,660 2029-30 Hanover 6240 Hanover Dr Princeton Dr Cul-de-sac AC E 10 2,058 37 78,320 77 60 27 13 Type II Slurry $133,144 2029-30 Joann 5710 Joann St Republic Ave Placentia Ave AC E 18 2,140 37 79,180 65 34 56 10 AC Grind-Overlay $425,988 2029-30 Joann 6300 Joann St Fordham Dr Columbia Dr AC E 24 1,452 37 53,942 62 36 45 19 AC Grind-Overlay $290,208 2029-30 Knowell 4770 Knowell Pl Meyer Pl Maple Ave AC E 2 870 37 32,190 89 100 0 0 Type II Slurry $54,723 2029-30 LittletonP 7200 Littleton Pl Cul-de-sac Bucknell Rd AC E 10 282 37 12,608 89 93 0 7 Type II Slurry $21,434 2029-30 Loma 10250 Loma Cir Francis Ln Cul-de-sac AAC E 20 175 37 8,649 84 100 0 0 Type II Slurry $14,703 2029-30 Londondrry 9620 Londonderry St Sharon Ln Bray Ln AC E 15 1,330 37 49,710 55 6 81 13 AC Grind-Overlay $267,440 2029-30 Loren 9460 Loren Ln Baker St Belfast Ave AC E 15 1,552 37 57,424 76 26 68 6 Type II Slurry $97,621 2029-30 Loyola 6500 Loyola Rd Fairview Rd Fair Dr AC E 24 1,253 37 46,213 71 58 39 3 Type II Slurry $78,562 2029-30 Loyola 6510 Loyola Rd Fair Dr Bucknell Rd AC E 10 449 37 16,613 69 30 47 23 Type II Slurry $28,242 2029-30 Ludington 11610 Ludington St Paularino Ave Traverse Dr AAC E 12 1,500 37 55,500 70 100 0 0 Type II Slurry $94,350 2029-30 Madagasgar 8200 Madagasgar St Madeira Ave Barbados Pl AC E 23 481 37 17,797 69 43 57 0 Type II Slurry $30,255 2029-30 Marian 5470 Marian Way Cul-de-sac 21st St AAC E 3 325 37 14,199 89 100 0 0 Type II Slurry $24,138 2029-30 Miner 6150 Miner St Wilson St Joann St AAC E 19 500 37 18,500 89 100 0 0 Type II Slurry $31,450 2029-30 Minorca Dr 8300 Minorca Dr Mesa Verde Dr Royal Palm Dr AC E 21 1,584 37 58,608 51 6 94 0 AC Grind-Overlay $315,311 2029-30 Minorca Pl 7980 Minorca Pl Ellesmere Ave Cul-de-sac AC E 21 950 37 37,324 50 22 77 1 AC Grind-Overlay $200,803 2029-30 Molokai 8280 Molokai Pl Cul-de-sac Gibralter Ave AC E 23 500 37 20,674 63 34 57 9 AC Grind-Overlay $111,226 2029-30 Monrovia 20 Monrovia Ave 19th St 20th St AAC E 1 1,330 33 43,890 89 34 59 7 Type II Slurry $74,613 2029-30 MonteVista 6920 Monte Vista Ave Orange Ave Santa Ana Ave AC E 26 1,328 37 49,136 62 26 66 8 AC Grind-Overlay $264,352 2029-30 Norse 6860 Norse Ave Cul-de-sac Santa Isabel Ave AC E 25 330 29 11,744 89 69 22 9 Type II Slurry $19,965 2029-30 Capella N 7700 North Capella Ct South Capella Ct Europa Dr AC E 22 675 37 28,230 80 43 49 8 Type II Slurry $47,991 2029-30 Nutmeg 8620 Nutmeg Pl Mace Ave Harbor Blvd AAC E 23 531 36 19,116 89 63 37 0 Type II Slurry $32,497 2029-30 Oahu 8020 Oahu Pl Palau Pl Cul-de-sac AC E 21 483 37 20,045 74 40 57 3 Type II Slurry $34,077 2029-30 Oak 4360 Oak St State St President Pl AAC E 1 1,058 33 35,714 86 34 62 4 Type II Slurry $60,714 2029-30 Oak 4362 Oak St President Pl Continental Ave AAC E 1 817 33 26,961 56 24 60 16 AC Grind-Overlay $145,050 2029-30 Oak 4365 Oak St Continental Ave Federal Ave AAC E 1 285 33 9,405 86 8 84 8 Type II Slurry $15,989 2029-30 Orange 2320 Orange Ave 18th St Broadway AAC E 8 662 36 23,832 89 89 0 11 Type II Slurry $40,514 2029-30 Oriole 7504 Oriole Dr Placentia Ave E'ly Boundry of Tract 6757 AC E 11 1,320 37 48,840 89 75 20 5 Type II Slurry $83,028 2029-30 Parkglen 3290 Parkglen Cir Parkhill Dr Cul-de-sac AC E 6 126 37 6,836 88 100 0 0 Type II Slurry $11,621 2029-30 Portola 10220 Portola Dr Loreto Ave Drake Ave AAC E 20 1,140 37 43,680 89 100 0 0 Type II Slurry $74,256 2029-30 President 4380 President Pl Cul-de-sac Oak St AAC E 1 661 33 23,987 89 61 0 39 Type II Slurry $40,778 2029-30 Puente 5950 Puente Ave Cul-de-sac Senate St AAC E 19 770 37 30,664 62 54 35 11 AC Grind-Overlay $164,972 2029-30 Pullman 11860 Pullman Ave Kalmus Rd 420' S/O Briggs Ave AC E 29 2,011 55 109,600 72 70 29 1 Type II Slurry $186,319 2029-30 Pullman 11920 Pullman Ave Paularino Ave Red Hill Ave AC E 29 2,300 60 138,920 78 64 21 15 Type II Slurry $236,164 2029-30 Raleigh 5930 Raleigh Ave Cul-de-sac Wilson St AC E 19 1,280 37 49,534 76 98 0 2 Type II Slurry $84,208 2029-30 RamonaPl 2160 Ramona Pl Santa Ana Ave Cul-de-sac AAC E 9 534 37 21,932 88 91 0 9 Type II Slurry $37,284 2029-30 RamonaWy 2190 Ramona Way Cul-de-sac Tustin Ave AAC E 9 560 33 20,654 84 95 0 5 Type II Slurry $35,112 2029-30 Randolph 10360 Randolph Ave E'ly end Bristol St AC E 13 649 37 23,763 61 97 0 3 Cape Seal $49,427 2029-30 Randolph 11490 Randolph Ave Baker St Cul-de-sac AAC E 13 1,070 37 39,590 89 73 21 6 Type II Slurry $67,303 2029-30 Raymond 3610 Raymond Ave 17th St N'ly end AAC E 9 650 25 15,750 66 30 60 10 AC Grind-Overlay $84,735 2029-30 Rutgers 6260 Rutgers Dr Wilson St Joann St AC E 24 470 36 17,190 89 70 0 30 Type II Slurry $29,223 2029-30 Salvador 9990 Salvador St Monterey Ave Lorenzo Dr AAC E 20 1,158 37 42,846 89 95 0 5 Type II Slurry $72,838 2029-30 San Jose 11120 San Jose Ave Deedee Dr Santa Clara Cir AC E 14 580 36 20,725 68 34 66 0 AC Grind-Overlay $111,501 2029-30 San Juan 9940 San Juan Ln Cibola Ave Coronado Dr AAC E 20 1,043 37 39,541 81 100 0 0 Type II Slurry $67,220 2029-30 Sanderling 7440 Sanderling Cir Gannet Dr Cul-de-sac AAC E 11 330 37 14,384 86 79 17 4 Type II Slurry $24,453 2029-30 Sandpiper 7350 Sandpiper Dr Swan Dr Flamingo Dr AAC E 11 1,170 37 43,290 84 83 15 2 Type II Slurry $73,593 2029-30 Santa Ana 2430 Santa Ana Ave 16th St 17th St AAC E 8 1,320 36 47,520 68 26 73 1 AC Grind-Overlay $255,658 2029-30 Santa Ana 2440 Santa Ana Ave 17th St 18th St AC E 8 1,313 36 47,268 87 39 50 11 Type II Slurry $80,356 2029-30 Santa Ana 2510 Santa Ana Ave 23rd St Santa Isabel Ave AC E 25 1,322 36 47,592 68 30 52 18 AC Grind-Overlay $256,045 2029-30 SantaClara 11140 Santa Clara Cir Salinas Ave Cul-de-sac AC E 14 1,363 37 51,630 81 51 49 0 Type II Slurry $87,771 2029-30 Snt Isabel 6740 Santa Isabel Ave Newport Blvd Orange Ave AAC E 26 1,320 37 48,840 71 36 49 15 Type II Slurry $83,028 2029-30 Santa Rosa 11150 Santa Rosa Ave Santa Clara Cir Smalley Rd AAC E 14 659 37 24,383 89 80 20 0 Type II Slurry $41,451 2029-30 Secretarit 11220 Secretariat Cir Smalley Rd Cul-de-sac AAC E 27 572 37 23,338 89 100 0 0 Type II Slurry $39,675 2029-30 Sonora 10202 Sonora Rd Velasco Ln Loreto Ave AC E 20 1,150 37 44,550 42 7 67 26 AC Grind-Overlay $239,679
237
City of Costa Mesa, CA
Forecast Maintenance / Rehabilitation (FMR) Report - FY 2024-31 Sorted by Rank, FY, Name Order (A-Z)
FY BranchID Sec ID Name From To Type Rank Zone L W Area PCI PCI Pct Climate PCI Pct Load PCI Pct Other Maint. Type Total $ 2029-30 Sparrow 7550 Sparrow Cir Tanager Dr Cul-de-sac AAC E 11 195 36 9,608 89 78 22 0 Type II Slurry $16,334 2029-30 Sturgeon 11670 Sturgeon Dr Ludington St Pierpont Dr AAC E 12 1,700 37 62,900 88 100 0 0 Type II Slurry $106,930 2029-30 Town Cntr 11730 Town Center Dr Bristol St Park Center Dr AAC E 28 650 46 29,900 88 46 0 54 Type II Slurry $50,830 2029-30 Turlock 11090 Turlock Dr Redding Ave Salinas Ave AC E 14 853 36 37,158 65 25 74 1 AC Grind-Overlay $199,910 2029-30 Union 4560 Union St Victoria St Frontage Road Republic Ave AAC E 18 770 33 25,410 89 91 0 9 Type II Slurry $43,197 2029-30 Utah 9120 Utah Cir Cul-de-sac California St AAC E 17 162 33 7,446 89 86 0 14 Type II Slurry $12,658 2029-30 Vallejo 11210 Vallejo Cir Cul-de-sac Smalley Rd AAC E 14 423 37 17,812 89 79 21 0 Type II Slurry $30,280 2029-30 Vassar 6460 Vassar Pl Nassau Rd Cul-de-sac AC E 24 348 37 15,050 88 93 0 7 Type II Slurry $25,585 2029-30 VictoriaPl 4970 Victoria Pl Newport Blvd Victoria St AC E 5 348 31 10,788 89 96 0 4 Type II Slurry $18,340 2029-30 Walnut St 5120 Walnut St Orange Ave Santa Ana Ave AAC E 3 1,316 37 48,692 89 80 20 0 Type II Slurry $82,776 2029-30 Wells 3520 Wells Pl Cabrillo St Fullerton Ave AAC E 8 406 37 15,022 89 73 27 0 Type II Slurry $25,537 2029-30 Westbrook 7230 Westbrook Pl Fordham Dr Princeton Dr AC E 10 534 37 19,758 89 100 0 0 Type II Slurry $33,589 2029-30 WstmnstrAv 6680 Westminster Ave 23rd St Wilson St AAC E 25 803 37 29,711 88 74 20 6 Type II Slurry $50,509 2029-30 WstmnstrAv 6960 Westminster Ave Monte Vista Ave Del Mar Ave AC E 26 1,323 34 44,982 89 67 21 12 Type II Slurry $76,469 2029-30 Whittier 2840 Whittier Ave S'ly End 19th St AC E 6 3,300 36 118,800 89 54 0 46 Type II Slurry $201,960 2029-30 Wisteria 11420 Wisteria Cir Dahlia Ave Cul-de-sac AC E 27 520 37 21,414 88 96 0 4 Type II Slurry $36,404 2029-30 Woodland 5288 Woodland Pl Cul-de-sac Tustin Ave AAC E 4 740 37 29,554 89 93 0 7 Type II Slurry $50,242 $9,085,539
2030-31 AveOTArts 11740 Avenue of the Arts Anton Ave Sunflower Ave AAC E 28 1,457 21 31,034 71 63 37 0 Type II Slurry $54,930 2030-31 AveOTArts 11741 Avenue of the Arts Sunflower Ave Anton Blvd AAC E 28 1,457 21 31,034 71 43 38 19 Type II Slurry $54,930 2030-31 AveOTArts 11744 Avenue of the Arts Anton Ave S'ly City limits AC E 28 360 75 27,000 84 96 0 4 Type II Slurry $47,790 2030-31 Aviemore 4410 Aviemore Terr Gleneagles Terr Valley Rd AC E 1 941 37 34,817 84 89 0 11 Type II Slurry $61,626 2030-31 Cambridge 2770 Cambridge Cir W'ly Cul-de-sac E'ly Cul-de-sac AAC E 9 590 37 26,178 78 91 7 2 Type II Slurry $46,335 2030-31 Camellia 5630 Camellia Ln Orange Ave Santa Ana Ave AC E 3 1,320 37 48,840 84 37 29 34 Type II Slurry $86,447 2030-31 Canadian 11530 Canadian Dr Allegheny Ave Olympic Ave AAC E 31 500 37 18,500 72 73 27 0 Type II Slurry $32,745 2030-31 Canary 7510 Canary Dr S'ly end Oriole Dr AAC E 11 780 37 28,860 78 77 22 1 Type II Slurry $51,082 2030-31 Canyon 4540 Canyon Dr Victoria St Wilson St AC E 18 1,700 35 59,500 83 42 54 4 Type II Slurry $105,315 2030-31 Canyon 4547 Canyon Dr 700' n/o Wilson St N'ly end AAC E 11 640 20 12,800 83 29 54 17 Type II Slurry $22,656 2030-31 Coronado 9904 Coronado Dr La Salle Ave Mendoza Ave AC E 20 838 50 44,257 86 100 0 0 Type II Slurry $78,335 2030-31 Corsica 8600 Corsica Pl Gibralter Ave Royal Palm Dr AC E 23 1,461 37 54,057 51 18 67 15 AC Grind-Overlay $302,179 2030-31 Cortez 10290 Cortez St Junipero Dr Drake Ave AAC E 20 1,085 37 40,145 81 79 0 21 Type II Slurry $71,057 2030-31 Corvo 7840 Corvo Pl Pitcairn Dr Minorca Pl AC E 21 630 37 23,310 77 100 0 0 Type II Slurry $41,259 2030-31 Costa Mesa 5010 Costa Mesa St Santa Ana Ave Irvine Ave AAC E 4 2,639 37 97,643 84 49 36 15 Type II Slurry $172,828 2030-31 Cottage 5580 Cottage Pl Cul-de-sac Westminster Ave AC E 3 168 37 8,390 63 62 36 2 Cape Seal $18,122 2030-31 Crocus 11460 Crocus Cir Larkspur St Cul-de-sac AC E 27 452 37 18,898 87 82 0 18 Type II Slurry $33,449 2030-31 Dahlia 11400 Dahlia Ave Fuschia St Cul-de-sac AC E 27 1,200 37 46,574 86 85 15 0 Type II Slurry $82,436 2030-31 HarborGtwN 9780 Harbor Gateway North Scenic Ave Mac Arthur Blvd AC E 30 900 37 33,300 75 71 20 9 Type II Slurry $58,941 2030-31 HarborGtwS 9800 Harbor Gateway South Sunflower Ave Scenic Dr AC E 30 1,328 37 49,136 74 68 31 1 Type II Slurry $86,971 2030-31 Harding 10600 Harding Way Cul-de-sac Cul-de-sac AAC E 16 678 37 29,434 55 48 33 19 AC Grind-Overlay $164,536 2030-31 Harla 7640 Harla Ave Cul-de-sac Mesa Verde Dr E AAC E 11 600 37 24,374 74 64 36 0 Type II Slurry $43,142 2030-31 Hartford 10900 Hartford Way Jefferson Ave Cul-de-sac AAC E 16 292 37 13,987 78 89 10 1 Type II Slurry $24,757 2030-31 Hayes 10810 Hayes Ave Paularino Ave Springfield St AAC E 16 520 37 19,240 80 71 29 0 Type II Slurry $34,055 2030-31 HelenaCir 10640 Helena Cir Cul-de-sac Cul-de-sac AAC E 16 560 37 24,793 83 81 13 6 Type II Slurry $43,884 2030-31 HelenaPl 10630 Helena Pl Helena Cir Paularino Ave AAC E 16 264 37 9,768 86 79 21 0 Type II Slurry $17,289 2030-31 Hudson 11550 Hudson Ave Canadian Dr Yellowstone Dr AAC E 31 826 37 30,562 68 46 37 17 AC Grind-Overlay $170,842 2030-31 Hummingbrd 7580 Hummingbird Dr Bunting Cir Tanager Dr AAC E 11 1,840 37 68,080 74 49 50 1 Type II Slurry $120,502 2030-31 Industrial 2010 Industrial Way Superior Ave Newport Blvd S/B AAC E 8 800 36 28,800 74 63 36 1 Type II Slurry $50,976 2030-31 Inroz 7730 Inroz Dr Baltra Pl Lemnos Dr AC E 22 260 37 9,620 69 64 34 2 Type II Slurry $17,027 2030-31 Jacaranda 8430 Jacaranda Ave Cul-de-sac Myrtlewood St AC E 21 1,387 37 54,670 86 97 0 3 Type II Slurry $96,766 2030-31 Madeira 8190 Madeira Ave Ceylon Rd Madagasgar St AC E 23 2,136 37 81,470 79 67 33 0 Type II Slurry $144,202 2030-31 Madison 10790 Madison Ave Paularino Ave Cheyenne St AAC E 16 800 37 29,600 77 66 34 0 Type II Slurry $52,392 2030-31 Magellan 10210 Magellan St Cul-de-sac Loreto Ave AC E 20 1,666 37 62,891 84 72 28 0 Type II Slurry $111,317 2030-31 Magnolia 3830 Magnolia St Fullerton Ave Santa Ana Ave AAC E 8 1,875 33 61,370 85 84 16 0 Type II Slurry $108,625 2030-31 Magnolia 3840 Magnolia St Santa Ana Ave Irvine Ave AAC E 9 2,645 37 97,865 79 68 12 20 Type II Slurry $173,221 2030-31 Mallard 7380 Mallard Dr Mandarin Dr Flamingo Dr AAC E 11 560 37 20,495 82 21 74 5 Type II Slurry $36,276 2030-31 Mandarin 7370 Mandarin Dr Sandpiper Dr Mallard Dr AAC E 11 980 37 36,260 84 98 0 2 Type II Slurry $64,180 2030-31 Maple St 6120 Maple St Victoria St Wilson St AC E 19 1,316 37 48,692 78 56 44 0 Type II Slurry $86,185 2030-31 Maple St 6130 Maple St Wilson St Joann St AAC E 19 500 37 18,500 69 16 84 0 Type II Slurry $32,745 2030-31 Maui Cir 8100 Maui Cir Cul-de-sac Java Rd AC E 22 391 37 16,641 63 47 36 17 AC Grind-Overlay $93,023 2030-31 Maui Pl 8070 Maui Pl Tahiti Dr Cul-de-sac AC E 21 557 37 23,100 54 31 66 3 AC Grind-Overlay $129,129 2030-31 Ogle Cir 2750 Ogle Cir Cul-de-sac Aliso Ave AAC E 9 400 37 16,974 79 52 22 26 Type II Slurry $30,044 2030-31 Ogle St 2650 Ogle St Orange Ave Santa Ana Ave AAC E 8 1,338 37 49,506 84 69 28 3 Type II Slurry $87,626 2030-31 Ogle St 2660 Ogle St Santa Ana Ave Tustin Ave AAC E 9 1,330 37 49,210 84 59 35 6 Type II Slurry $87,102 2030-31 Ogle St 2760 Ogle St Aliso Ave Irvine Ave AAC E 9 665 37 24,605 87 70 30 0 Type II Slurry $43,551
238
City of Costa Mesa, CA
Forecast Maintenance / Rehabilitation (FMR) Report - FY 2024-31 Sorted by Rank, FY, Name Order (A-Z)
FY BranchID Sec ID Name From To Type Rank Zone L W Area PCI PCI Pct Climate PCI Pct Load PCI Pct Other Maint. Type Total $ 2030-31 Olympic 11540 Olympic Ave Canadian Dr Yellowstone Dr AAC E 31 850 37 31,450 74 63 36 1 Type II Slurry $55,667 2030-31 Orcas 8250 Orcas Dr Samoa Pl Sumatra Pl AC E 23 230 37 8,510 76 100 0 0 Type II Slurry $15,063 2030-31 Oriole 7500 Oriole Dr E'ly Boundry of Tract 6757 Tanager Dr AAC E 11 820 37 30,340 75 55 44 1 Type II Slurry $53,702 2030-31 Oxford 7250 Oxford Ln Greenbriar Ln Princeton Dr AC E 10 600 37 22,200 76 27 60 13 Type II Slurry $39,294 2030-31 Pacific 4500 Pacific Ave Victoria Pl N'ly End AC E 18 2,515 36 90,540 71 24 75 1 Type II Slurry $160,256 2030-31 Palau 8010 Palau Pl Samar Dr Cul-de-sac AC E 21 974 37 38,212 69 39 61 0 Type II Slurry $67,635 2030-31 Palau 8530 Palau Pl Cul-de-sac Andros St AC E 21 375 37 16,049 81 98 0 2 Type II Slurry $28,407 2030-31 Palmer 2090 Palmer St Orange Ave Santa Ana Ave AAC E 8 1,325 37 49,025 82 71 12 17 Type II Slurry $86,774 2030-31 Pamela 5900 Pamela Ln Cul-de-sac Joann St AC E 19 440 37 16,280 79 100 0 0 Type II Slurry $28,816 2030-31 Panay 8790 Panay Cir Cul-de-sac Country Club Dr AC E 22 242 37 10,204 53 39 61 0 AC Grind-Overlay $57,040 2030-31 Parnell 9580 Parnell Pl Loren Ln Cul-de-sac AC E 15 277 37 12,423 71 40 60 0 Type II Slurry $21,989 2030-31 Paros 7860 Paros Cir Cul-de-sac Stromboli Rd AC E 21 446 37 18,676 55 18 79 3 AC Grind-Overlay $104,399 2030-31 Ridgecrest 4480 Ridgecrest Cir Valley Rd Cul-de-sac AC E 1 271 37 12,201 52 81 18 1 Cape Seal $26,354 2030-31 Riverside 2210 Riverside Pl Cul-de-sac 16th St AAC E 9 200 33 8,774 77 58 0 42 Type II Slurry $15,530 2030-31 Riviera 6780 Riviera Dr Rue De Cannes Tustin Ave AC E 26 910 33 30,030 70 21 51 28 Type II Slurry $53,153 2030-31 Roanoke 11510 Roanoke Ln Cul-de-sac Allegheny Ave AAC E 31 700 37 28,074 71 71 28 1 Type II Slurry $49,691 2030-31 Roosevelt 10740 Roosevelt Way Cul-de-sac Carson St AAC E 16 368 37 15,992 75 98 0 2 Type II Slurry $28,306 2030-31 Rose 5620 Rose Ln Orange Ave Santa Ana Ave AC E 3 1,300 37 48,100 62 43 51 6 AC Grind-Overlay $268,879 2030-31 Rosemary 5100 Rosemary Pl Cul-de-sac 20th St AAC E 3 600 37 24,374 87 80 18 2 Type II Slurry $43,142 2030-31 Royal Palm 8550 Royal Palm Dr Adams Ave Baker St AC E 21 2,641 37 97,717 72 26 61 13 Type II Slurry $172,959 2030-31 Royal Palm 8560 Royal Palm Dr Baker St Corsica Pl AC E 23 362 37 13,394 47 34 66 0 AC Grind-Overlay $74,872 2030-31 Royce 9410 Royce Ln Baker St Watson Ave AC E 15 953 37 35,261 66 10 90 0 AC Grind-Overlay $197,109 2030-31 Rue Cannes 6800 Rue De Cannes Riviera Dr Monte Vista Ave AC E 26 890 33 29,370 81 34 65 1 Type II Slurry $51,985 2030-31 Rural Ln 5520 Rural Ln 22nd St Rural Pl AC E 3 560 33 18,480 73 41 48 11 Type II Slurry $32,710 2030-31 Rural Pl 5530 Rural Pl Rural Ln 22nd St AC E 3 750 33 24,750 70 44 47 9 Type II Slurry $43,808 2030-31 Rutgers 6340 Rutgers Dr Wake Forest Rd Villanova Rd AC E 24 1,130 37 41,810 72 40 58 2 Type II Slurry $74,004 2030-31 SaintClair 10270 Saint Clair St Velasco Ln Bear St AC E 20 1,160 37 42,920 83 100 0 0 Type II Slurry $75,968 2030-31 Salinas 11040 Salinas Ave Wimbledon Way Smalley Rd AC E 14 1,805 37 70,291 72 25 46 29 Type II Slurry $124,415 2030-31 Stromboli 7850 Stromboli Rd Pitcairn Dr Club House Rd AC E 21 1,399 37 51,763 45 22 73 5 AC Grind-Overlay $289,355 2030-31 Sumatra 8260 Sumatra Pl Orcas Dr Gibraltar Ave AC E 23 1,086 37 40,182 78 24 21 55 Type II Slurry $71,122 2030-31 Sumba 7780 Sumba Cir Balearic Dr Cul-de-sac AC E 22 240 37 11,054 78 48 39 13 Type II Slurry $19,566 2030-31 Tern 7470 Tern Cir Placentia Ave Cul-de-sac AAC E 11 580 37 23,634 76 46 52 2 Type II Slurry $41,832 2030-31 TheMasters 11780 The Masters Cir Newport Blvd Cul-de-sac AAC E 29 1,050 37 41,024 87 79 0 21 Type II Slurry $72,612 2030-31 Thurin 4920 Thurin St Bay St Victoria St AAC E 5 1,340 36 48,240 87 78 19 3 Type II Slurry $85,385 2030-31 Toronto 9740 Toronto Way Cadillac Ave Cul-de-sac AC E 30 439 37 18,417 72 50 39 11 Type II Slurry $32,598 2030-31 Trabuco 5770 Trabuco Cir Canyon Dr Cul-de-sac AC E 18 248 37 9,176 87 60 21 19 Type II Slurry $16,242 2030-31 Traverse 11680 Traverse Dr Ludington St Sturgeon Dr AAC E 12 2,000 37 74,000 87 100 0 0 Type II Slurry $130,980 2030-31 Trenton 10910 Trenton Way Jefferson Ave Cul-de-sac AAC E 16 450 37 20,024 80 86 13 1 Type II Slurry $35,442 2030-31 Trinity 11570 Trinity Dr Paularino Ave Yellowstone Dr AAC E 31 1,086 37 40,182 78 57 14 29 Type II Slurry $71,122 2030-31 Tulane Pl 6410 Tulane Pl Columbia Dr Cul-de-sac AC E 24 195 37 9,389 52 16 62 22 AC Grind-Overlay $52,485 2030-31 Tulane Rd 6400 Tulane Rd Notre Dame Rd Columbia Dr AC E 24 600 37 22,395 70 22 51 27 Type II Slurry $39,639 2030-31 Tulare 11050 Tulare Dr Salinas Ave San Leandro Ln AC E 14 1,721 37 63,677 60 31 69 0 AC Grind-Overlay $355,954 2030-31 Tulip 5550 Tulip Ln Elden Ave Orange Ave AC E 3 640 37 23,680 76 78 16 6 Type II Slurry $41,914 $6,981,000
239
City of Costa Mesa, CA Page 13
2024 Citywide Pavement Management Plan – OCTA Submittal Final Report – June 30, 2024
XII. APPENDIX B – COMPLETE STREET LISTING CURRENT CONDITIONS
240
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Arterials / Collectors
17th 2860 17th St W'ly End Monrovia Ave AC S 6 1,670 36 60,120 3/26/24 84 Complete Reconstruction - AC 2/1/06 17th 2870 17th St Monrovia Ave Placentia Ave AC S 6 1,320 36 47,520 1/30/24 83 Complete Reconstruction - AC 10/1/04 17th 2880 17th St Placentia Ave Pomona Ave AC P 7 1,310 36 47,160 1/30/24 95 Complete Reconstruction - AC 9/1/04 17th 2890 17th St Pomona Ave 615' e/o Pomona Ave AC P 7 615 54 33,210 1/30/24 91 Complete Reconstruction - AC 8/1/04 17th 2895 17th St 615' e/o Pomona Ave Superior Ave AC P 7 600 54 32,400 1/30/24 75 New Construction - Initial 1/1/00 17th 2900 17th St Superior Ave Newport Blvd AC P 8 452 47 21,244 2/28/24 83 New Construction - Initial 1/1/00 17th 2901 17th St Newport Blvd Superior Ave AC P 8 452 47 21,244 2/28/24 77 New Construction - Initial 1/1/80 17th 2980 17th St Newport Blvd 200' w/o Fullerton Ave AAC A 8 425 44 18,700 2/28/24 100 Mill & Overlay - ARHM 1/1/24 17th 2981 17th St 200' w/o Fullerton Ave Newport Blvd AAC A 8 425 44 18,700 2/28/24 100 Mill & Overlay - ARHM 1/1/24 17th 2990 17th St 200' w/o Fullerton Ave Orange Ave AC A 8 725 43 31,175 2/28/24 91 Overlay - AC Thin 8/1/04 17th 2991 17th St Orange Ave 200' w/o Fullerton Ave AC A 8 725 43 31,175 2/28/24 81 Overlay - AC Thin 8/1/04 17th 3000 17th St Orange Ave Santa Ana Ave AC A 8 1,455 61 88,755 1/30/24 94 Complete Reconstruction - AC 10/1/06 17th 3010 17th St Santa Ana Ave Tustin Ave AC A 9 1,320 57 75,240 1/30/24 94 Complete Reconstruction - AC 5/1/08 17th 3020 17th St Tustin Ave Irvine Ave AC P 9 1,340 57 76,380 1/30/24 95 Complete Reconstruction - AC 5/1/08 19th 3425 19th St W'ly City Limits Parkcrest Dr AC P 6 360 42 15,120 1/30/24 87 Surface Treatment - Slurry Seal 1/1/24 19th 3430 19th St Parkcrest Dr Monrovia Ave AC P 1 1,710 46 78,660 1/30/24 95 Surface Treatment - Slurry Seal 1/1/24 19th 3440 19th St Monrovia Ave Placentia Ave AC P 1 1,320 46 60,720 1/30/24 95 Surface Treatment - Slurry Seal 1/1/24 19th 3450 19th St Placentia Ave Pomona Ave AC P 2 1,325 36 34,450 1/31/24 95 Surface Treatment - Slurry Seal 1/1/24 19th 3451 19th St Pomona Ave Placentia Ave AC P 2 1,325 36 47,700 1/31/24 95 Surface Treatment - Slurry Seal 1/1/24 19th 3460 19th St Pomona Ave Anaheim Ave AC P 2 1,305 36 46,980 1/31/24 84 New Construction - Initial 1/1/00 19th 3461 19th St Anaheim Ave Pomona Ave AC P 2 1,305 36 46,980 1/31/24 88 New Construction - Initial 1/1/80 19th 3470 19th St Anaheim Ave Park Ave AC P 2 650 36 23,400 1/31/24 85 Overlay - AC Thin 5/1/07 19th 3471 19th St Park Ave Anaheim Ave AC P 2 650 36 23,400 1/31/24 90 Overlay - AC Thin 5/1/07 19th 3480 19th St Park Ave Harbor Blvd AC P 2 665 35 23,275 2/27/24 92 6 in Cold Mill & Overlay in Secure area 9/1/13 19th 3481 19th St Harbor Blvd Park Ave AC P 2 665 35 23,275 2/27/24 93 6 in Cold Mill & Overlay in Secure area 9/1/13 19th 3490 19th St Harbor Blvd Newport Blvd AC P 5 720 35 25,200 2/27/24 96 6 in Cold Mill & Overlay in Secure area 9/1/13 19th 3491 19th St Newport Blvd Harbor Blvd AC P 5 720 35 25,200 2/27/24 93 6 in Cold Mill & Overlay in Secure area 9/1/13 19th 4140 19th St Newport Blvd Fullerton Ave AAC C 8 680 35 23,800 2/27/24 83 Overlay - AC Structural 4/12/12 19th 4141 19th St Fullerton Ave Newport Blvd AAC C 8 680 35 23,800 2/27/24 77 Overlay - AC Structural 4/12/12 19th 4150 19th St Fullerton Ave Orange Ave AAC C 8 680 36 24,465 2/27/24 74 Overlay - AC Structural 4/1/12 19th 4160 19th St Orange Ave Santa Ana Ave AC C 8 1,278 36 46,070 1/30/24 95 Complete Reconstruction - AC 1/1/03 19th 4170 19th St Santa Ana Ave Irvine Ave AC C 9 2,599 35 85,985 1/30/24 94 Complete Reconstruction - AC 6/1/08 22nd 460 22nd St Newport Blvd Orange Ave AC C 3 1,341 36 48,276 2/27/24 83 Surface Treatment - Slurry Seal 3/20/16 22nd 470 22nd St Orange Ave Santa Ana Ave AC C 3 1,326 36 47,736 2/14/24 92 Surface Treatment - Slurry Seal 12/1/19 22nd 475 22nd St Santa Ana Ave Tustin Ave AAC C 1,283 37 51,266 2/14/24 95 Overlay - AC Structural 1/1/21 Adams 580 Adams Ave Begin of Bridge at River Placentia Ave AAC A 22 2,688 40 107,935 3/28/24 100 Mill & Overlay - ARHM 3/28/24 Adams 581 Adams Ave Placentia Ave Begin of Bridge at River AAC A 22 2,688 40 105,965 3/28/24 100 Mill & Overlay - ARHM 3/28/24 Adams 590 Adams Ave Placentia Ave Mesa Verde Dr East AAC A 21 3,125 40 125,000 3/28/24 100 Mill & Overlay - ARHM 3/28/24 Adams 591 Adams Ave Mesa Verde Dr East Placentia Ave AAC A 21 3,125 40 125,000 3/28/24 100 Mill & Overlay - ARHM 3/28/24 Adams 600 Adams Ave Mesa Verde Dr East Royal Palm Dr AAC A 21 1,000 40 40,000 3/28/24 100 Mill & Overlay - ARHM 3/28/24 Adams 601 Adams Ave Royal Palm Dr Mesa Verde Dr East AAC A 21 1,000 40 40,000 3/28/24 100 Mill & Overlay - ARHM 3/28/24 Adams 610 Adams Ave Royal Palm Dr Harbor Blvd AC A 21 810 47 38,070 2/14/24 93 New Construction - Initial 1/1/00 Adams 611 Adams Ave Harbor Blvd Royal Palm Dr AC A 21 810 47 38,070 2/14/24 86 New Construction - Initial 1/1/80 Adams 620 Adams Ave Harbor Blvd Fairview Rd AC A 15 3,644 34 150,416 1/10/24 95 Surface Treatment - Slurry Seal 12/1/00 Adams 621 Adams Ave Fairview Rd Harbor Blvd AC A 15 3,642 35 145,550 1/10/24 94 Surface Treatment - Slurry Seal 12/1/00 Anton 11710 Anton Blvd Bristol St Avenue of the Arts AAC A 28 1,360 33 44,880 2/15/24 81 Overlay - AC Structural 6/1/06 Anton 11711 Anton Blvd Avenue of the Arts Bristol St AAC A 28 1,360 33 44,880 2/15/24 82 Overlay - AC Structural 6/1/06 Anton 11715 Anton Blvd Avenue of the Arts Sakioka Dr AAC A 28 938 33 30,954 2/15/24 95 Overlay - AC Structural 2/1/14 Anton 11716 Anton Blvd Sakioka Dr Avenue of the Arts AAC A 28 938 33 30,954 2/15/24 91 Overlay - AC Structural 2/1/14 Anton 11720 Anton Blvd Sakioka Dr Sunflower Ave AC A 28 2,730 33 90,090 1/18/24 87 New Construction - Initial 1/1/00 Anton 11721 Anton Blvd Sunflower Ave Sakioka Dr AC A 28 2,730 33 90,090 1/18/24 89 New Construction - Initial 1/1/00 Arlington 7300 Arlington Dr Fairview Rd Lane Change (2 lanes) AAC C 20 900 55 48,700 1/10/24 91 2 in Cold Mill & Overlay 12/10/18 Arlington 7310 Arlington Dr Lane Change (2 lanes) Newport Blvd AAC C 20 3,730 42 103,055 1/10/24 93 2 in Cold Mill & Overlay 12/10/18 Baker 640 Baker St Mesa Verde Dr Harbor Blvd AC S 21 2,900 60 174,000 1/23/24 69 Surface Treatment - Slurry Seal 3/15/22 Baker 650 Baker St Harbor Blvd Loren Ln AC P 21 2,870 60 191,665 1/11/24 92 Complete Reconstruction - AC 2/1/03
241
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Baker 655 Baker St Loren Ln Fairview Rd AC P 21 515 80 40,255 2/14/24 76 Complete Reconstruction - AC 2/1/03 Baker 660 Baker St Fairview Rd Babb St (N) AAC P 15 2,572 60 171,444 1/23/24 80 Overlay - AC Structural 2/1/09 Baker 670 Baker St Babb St (N) Bear St AAC P 16 1,400 74 110,056 1/23/24 89 Overlay - AC Structural 2/1/09 Baker 680 Baker St Bear St Bristol St AC A 13 2,685 44 118,140 1/23/24 91 New Construction - Initial 1/1/00 Baker 681 Baker St Bristol St Bear St AAC A 13 2,685 44 118,140 2/28/24 89 Overlay - AC Structural 9/15/15 Baker 690 Baker St Bristol St Newport Blvd (NB) AC A 12 2,150 40 86,000 2/28/24 84 Complete Reconstruction - AC 2/1/03 Baker 691 Baker St Newport Blvd (NB) Bristol St AC A 13 2,150 40 86,000 2/28/24 85 New Construction - Initial 1/1/80 Baker 700 Baker St Newport Blvd (NB) Red Hill Ave AC A 29 1,050 40 42,000 2/28/24 90 6 in Cold Mill & Overlay in Secure area 8/1/13 Baker 701 Baker St Red Hill Ave Newport Blvd (NB) AC A 13 1,050 40 42,000 2/28/24 94 6 in Cold Mill & Overlay in Secure area 8/1/13 Bear 10990 Bear St Baker St On/Off Ramps SR-73 SB AC A 13 400 40 16,000 2/15/24 95 Overlay-Rubber Hot Mix 1/1/21 Bear 10991 Bear St On/Off Ramps SR-73 SB Baker St AC A 16 400 40 16,000 2/15/24 95 Overlay-Rubber Hot Mix 1/1/21 Bear 10995 Bear St On/Off Ramps SR-73 SB Yukon/Paularino Ave AC A 13 860 40 33,400 2/15/24 95 Overlay-Rubber Hot Mix 1/1/21 Bear 10996 Bear St Yukon/Paularino Ave On/Off Ramps SR-73 SB AC A 860 40 34,400 2/15/24 95 Overlay-Rubber Hot Mix 1/1/21 Bear 10997 Bear St Yukon/Paularino Ave S'ly Edge of Bridge over I-405 AC A 13 1,500 40 60,000 2/15/24 95 Overlay-Rubber Hot Mix 1/1/21 Bear 10998 Bear St S'ly Edge of Bridge over I-405 Yukon/Paularino Ave AC A 1,500 40 60,000 2/15/24 95 Overlay-Rubber Hot Mix 1/1/21 Bear 11000 Bear St S'ly Edge of Bridge over I-405 Sunflower Ave AC A 27 2,330 36 114,710 1/16/24 93 New Construction - Initial 1/1/00 Bear 11001 Bear St Sunflower Ave S'ly Edge of Bridge over I-405 AC A 2,330 37 108,360 1/16/24 94 New Construction - Initial 1/1/80 Bear 11005 Bear St Sunflower Ave Wakeham Ave AC S 27 770 40 30,800 1/16/24 94 New Construction - Initial 1/1/00 Bear 11006 Bear St Wakeham Ave Sunflower Ave AC S 27 770 40 30,800 1/16/24 94 New Construction - Initial 1/1/80 Bristol 820 Bristol St E'ly City Limits (w/o Irvine Ave) Red Hill Ave AC P 29 1,440 42 60,480 2/22/24 92 6 in Cold Mill & Overlay in Secure area 8/1/13 Bristol 821 Bristol St Red Hill Ave E'ly City Limits (w/o Irvine Ave) AC P 29 1,450 42 60,900 2/21/24 74 6 in Cold Mill & Overlay in Secure area 8/1/13 Bristol 830 Bristol St Santa Ana Ave Newport Blvd (NB) AC A 29 2,243 47 101,256 2/21/24 76 Overlay-Rubber Hot Mix 12/31/21 Bristol 831 Bristol St Newport Blvd (NB) Santa Ana Ave AC A 29 2,250 47 113,074 2/21/24 81 Overlay-Rubber Hot Mix 12/31/21 Bristol 840 Bristol St 300' s/o Bear St SB Newport Blvd On Ramp AC A 20 680 42 30,849 2/22/24 95 Overlay-Rubber Hot Mix 7/19/22 Bristol 841 Bristol St SB Newport Blvd On Ramp 300' s/o Bear St AAC A 645 38 24,565 2/21/24 94 Overlay-Rubber Hot Mix 7/19/22 Bristol 842 Bristol St SB Newport Blvd On Ramp NB Newport Blvd Off Ramp AC A 20 835 38 35,900 2/22/24 95 Asphalt Rubber Hot Mix 7/19/22 Bristol 843 Bristol St NB Newport Blvd Off Ramp SB Newport Blvd On Ramp AAC A 835 35 39,545 2/21/24 89 Asphalt Rubber Hot Mix 7/19/22 Bristol 844 Bristol St 300' s/o Bear St Randolph Ave AC A 12 1,025 47 48,175 2/21/24 95 Overlay-Rubber Hot Mix 7/19/22 Bristol 850 Bristol St Randolph Ave Baker St AAC A 12 1,275 47 59,925 2/22/24 93 Overlay - AC Structural 9/22/17 Bristol 851 Bristol St Baker St Randolph Ave AAC A 12 1,275 47 59,925 2/22/24 91 Overlay - AC Structural 10/13/17 Bristol 855 Bristol St Randolph Ave 300' s/o Bear St AC A 1,025 47 48,175 2/22/24 95 Overlay-Rubber Hot Mix 12/31/21 Bristol 860 Bristol St Baker St Paularino Ave AC A 12 820 34 27,470 2/22/24 90 New Construction - Initial 1/1/00 Bristol 861 Bristol St Paularino Ave Baker St AC A 12 820 34 27,470 2/22/24 90 New Construction - Initial 1/1/00 Bristol 865 Bristol St Paularino Ave S'ly Edge of Bridge over I-405 AC A 12 1,680 34 56,280 2/22/24 91 New Construction - Initial 1/1/00 Bristol 866 Bristol St S'ly Edge of Bridge over I-405 Paularino Ave AC A 12 1,680 34 56,280 2/22/24 89 New Construction - Initial 1/1/00 Bristol 870 Bristol St N'ly Edge of Bridge over I-405 Anton Blvd AC A 27 865 62 53,630 2/22/24 91 6 in Cold Mill & Overlay in Secure area 10/1/13 Bristol 871 Bristol St Anton Blvd N'ly Edge of Bridge over I-405 AC A 27 865 62 53,630 2/22/24 90 6 in Cold Mill & Overlay in Secure area 10/1/13 Bristol 880 Bristol St Anton Blvd Sunflower Ave AAC A 27 1,475 34 49,413 1/18/24 85 Overlay - AC Structural 10/1/06 Bristol 881 Bristol St Sunflower Ave Anton Blvd AAC A 27 1,475 34 48,613 1/18/24 86 Overlay - AC Structural 10/1/06 Del Mar 6990 Del Mar Ave N/B Newport Blvd Elden Ave AAC P 26 670 90 59,800 2/21/24 70 Overlay - AC Structural 4/1/15 Del Mar 6995 Del Mar Ave Elden Ave Orange Ave AAC P 26 650 37 24,050 2/21/24 89 Overlay - AC Structural 12/1/15 Del Mar 7000 Del Mar Ave Orange Ave Santa Ana Ave AAC P 26 1,310 37 48,470 2/21/24 90 Overlay - AC Structural 12/1/15 Fair 560 Fair Dr Harbor Blvd Fairview Rd AAC P 10 3,530 60 211,800 1/9/24 93 Overlay - AC Structural 6/1/08 Fair 570 Fair Dr Fairview Rd S/B Newport Blvd AAC P 10 2,960 60 177,600 1/9/24 82 Overlay - AC Structural 9/1/04 Fairview 480 Fairview Rd Newport Blvd (SB) Wilson St AAC A 5 1,015 28 28,420 1/11/24 95 Overlay - AC Structural 2/1/03 Fairview 481 Fairview Rd Wilson St Newport Blvd (SB) AAC A 5 1,086 28 30,408 1/9/24 85 Overlay - AC Structural 2/1/03 Fairview 490 Fairview Rd Wilson St Fair Dr AC A 24 2,760 35 106,978 1/10/24 76 New Construction - Initial 1/1/00 Fairview 491 Fairview Rd Fair Dr Wake Forest Rd AAC A 24 1,961 35 68,635 1/10/24 72 2 in overlay 7/1/04 Fairview 492 Fairview Rd Wake Forest Rd Wilson St AAC A 24 792 35 27,720 1/10/24 82 2 in overlay 7/1/04 Fairview 500 Fairview Rd Fair Dr Merrimac Way AC A 10 1,300 35 43,750 1/10/24 91 Complete Reconstruction - AC 7/1/01 Fairview 501 Fairview Rd Merrimac Way Fair Dr AC A 10 1,300 35 44,850 1/10/24 67 Complete Reconstruction - AC 7/1/01 Fairview 510 Fairview Rd Merrimac Way Arlington Dr AC A 10 510 35 17,595 1/10/24 89 Complete Reconstruction - AC 7/1/01 Fairview 511 Fairview Rd Arlington Dr Merrimac Way AC A 10 510 35 17,595 1/10/24 86 Complete Reconstruction - AC 7/1/01 Fairview 515 Fairview Rd Arlington Dr Adams Ave AC A 10 2,603 35 88,905 1/10/24 79 Complete Reconstruction - AC 7/1/01 Fairview 516 Fairview Rd Adams Ave Arlington Dr AC A 10 2,603 35 88,905 1/10/24 76 Complete Reconstruction - AC 7/1/01 Fairview 520 Fairview Rd Adams Ave Paularino Channel AC A 15 570 40 22,800 2/14/24 96 Overlay-Rubber Hot Mix 1/1/21 Fairview 521 Fairview Rd Paularino Channel Adams Ave AC A 15 570 40 22,800 1/11/24 95 Overlay-Rubber Hot Mix 1/1/21
242
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Fairview 525 Fairview Rd Paularino Channel Baker St AC A 15 930 35 32,550 1/11/24 94 Overlay-Rubber Hot Mix 1/1/21 Fairview 526 Fairview Rd Baker St Paularino Channel AC A 15 930 35 32,550 1/11/24 95 Overlay-Rubber Hot Mix 1/1/21 Fairview 530 Fairview Rd Baker St S'ly edge of Bridge over I-405 AC A 15 2,665 35 93,275 1/23/24 77 New Construction - Initial 1/1/00 Fairview 531 Fairview Rd S'ly edge of Bridge over I-405 Baker St AC A 15 2,665 35 89,475 1/23/24 81 New Construction - Initial 1/1/00 Fairview 540 Fairview Rd N'ly edge of Bridge over I-405 South Coast Dr AC A 30 1,130 37 41,810 1/23/24 93 New Construction - Initial 1/1/00 Fairview 541 Fairview Rd South Coast Dr N'ly edge of Bridge over I-405 AAC A 30 1,130 37 41,810 1/23/24 88 Overlay - AC Structural 4/1/15 Fairview 550 Fairview Rd South Coast Dr Sunflower Ave AC A 30 1,600 37 59,200 3/26/24 81 New Construction - Initial 1/1/00 Fairview 551 Fairview Rd Sunflower Ave South Coast Dr AAC A 30 1,600 37 59,200 1/16/24 84 Overlay - AC Structural 4/1/15 Fairview 552 Fairview Rd Sunflower Ave N'ly City Limits AAC A 178 64 11,392 2/22/24 65 Overlay - AC Structural 3/1/16 Gisler 8830 Gisler Ave W'ly End Country Club Dr AC S 17 2,450 50 122,500 1/18/24 63 Surface Treatment - Slurry Seal 10/6/15 Gisler 8850 Gisler Ave Country Club Dr Harbor Blvd AAC S 17 3,400 56 190,400 1/18/24 80 Overlay - AC Structural 6/1/08 Harbor 280 Harbor Blvd Newport Blvd 19th St AAC A 5 820 37 28,740 1/9/24 91 Overlay - AC Structural 5/1/09 Harbor 281 Harbor Blvd 19th St Newport Blvd AAC A 5 820 37 28,740 1/9/24 92 Overlay - AC Structural 5/1/09 Harbor 290 Harbor Blvd 19th St Bay St AAC A 5 1,995 40 69,746 1/9/24 86 Overlay - AC Structural 5/1/09 Harbor 291 Harbor Blvd Victoria St 19th St AAC A 3,330 40 125,749 1/9/24 91 Overlay - AC Structural 5/1/09 Harbor 295 Harbor Blvd Bay St Victoria St AAC A 5 1,315 40 52,600 1/9/24 91 Overlay - AC Structural 5/1/09 Harbor 300 Harbor Blvd Victoria St Wilson St AAC A 5 1,321 40 52,390 1/9/24 83 Overlay - AC Structural 5/1/09 Harbor 301 Harbor Blvd Wilson St Victoria St AAC A 5 1,321 40 52,840 1/9/24 84 Overlay - AC Structural 5/1/09 Harbor 310 Harbor Blvd Wilson St Fair Dr AC A 24 2,570 40 102,100 1/9/24 86 New Construction - Initial 1/1/00 Harbor 311 Harbor Blvd Fair Dr Wilson St AC A 24 2,570 40 102,800 1/9/24 77 New Construction - Initial 1/1/00 Harbor 320 Harbor Blvd Fair Dr Merrimac Way AC A 10 1,863 40 74,520 1/10/24 89 New Construction - Initial 1/1/00 Harbor 321 Harbor Blvd Adams Ave Merrimac Way AC A 10 1,802 40 72,080 1/9/24 85 New Construction - Initial 1/1/00 Harbor 322 Harbor Blvd Merrimac Way Fair Dr AC A 10 1,862 40 74,480 1/10/24 83 New Construction - Initial 1/1/00 Harbor 325 Harbor Blvd Merrimac Way Adams Ave AC A 10 1,801 40 72,040 1/11/24 91 New Construction - Initial 1/1/00 Harbor 330 Harbor Blvd Adams Ave Baker Ave AC A 15 2,450 40 97,600 1/11/24 94 New Construction - Initial 1/1/00 Harbor 331 Harbor Blvd Baker Ave Adams Ave AC A 15 2,450 40 98,000 1/9/24 86 New Construction - Initial 1/1/00 Harbor 340 Harbor Blvd Baker Ave Gisler Ave AAC A 15 2,525 40 101,000 1/25/24 86 Overlay - AC Structural 4/1/13 Harbor 341 Harbor Blvd Gisler Ave Baker Ave AAC A 15 2,525 40 101,000 1/9/24 79 Overlay - AC Structural 4/1/13 Harbor 350 Harbor Blvd Gisler Ave I-405 AAC A 15 790 40 31,600 1/25/24 87 Overlay - AC Structural 4/1/13 Harbor 351 Harbor Blvd I-405 Gisler Ave AAC A 15 790 40 31,600 1/25/24 85 Overlay - AC Structural 4/1/13 Harbor 360 Harbor Blvd I-405 South Coast Dr AAC A 30 885 40 35,400 1/25/24 88 Overlay - AC Structural 4/1/13 Harbor 361 Harbor Blvd South Coast Dr I-405 AAC A 30 885 40 35,400 1/11/24 73 Overlay - AC Structural 4/1/13 Harbor 370 Harbor Blvd South Coast Dr Sunflower Ave AC A 30 1,460 40 58,400 1/11/24 87 New Construction - Initial 1/1/00 Harbor 371 Harbor Blvd Sunflower Ave South Coast Dr AC A 30 1,460 40 58,400 1/11/24 75 New Construction - Initial 1/1/00 Harbor 380 Harbor Blvd Sunflower Ave MacArthur Ave AC A 30 2,315 40 92,600 1/11/24 71 New Construction - Initial 1/1/00 Harbor 381 Harbor Blvd MacArthur Ave Sunflower Ave AC A 30 2,315 40 92,600 1/11/24 87 New Construction - Initial 1/1/00 Hyland 9710 Hyland Ave South Coast Dr Sunflower Ave AAC P 30 1,332 60 79,920 1/11/24 74 Overlay - AC Structural 1/1/09 Hyland 9720 Hyland Ave Sunflower Ave Mac Arthur Blvd AAC P 30 2,347 66 151,402 1/11/24 82 Overlay - AC Structural 1/1/09 Irvine 2801 Irvine Ave 330' n/o 20th St (Baycrest Rd) 20th St AC P 4 330 35 11,550 1/30/24 95 Asphalt Rubber Hot Mix 11/27/18 Irvine 2811 Irvine Ave 20th St 19th St AC P 4 1,330 33 43,890 1/30/24 95 Asphalt Rubber Hot Mix 11/27/18 Irvine 2821 Irvine Ave 19th St 17th St AC P 3 2,620 31 81,220 1/30/24 95 Asphalt Rubber Hot Mix 11/27/18 Irvine 2830 Irvine Ave 17th St 16th St AC P 3 1,300 48 62,400 1/30/24 95 Asphalt Rubber Hot Mix 11/27/18 MacArthur 9784 MacArthur Blvd 600' w/o Harbor Blvd Harbor Blvd AC A 30 600 75 45,000 1/11/24 95 Overlay-Rubber Hot Mix 11/15/19 MacArthur 9786 MacArthur Blvd 600' e/o Hyland Ave 600' w/o Harbor Blvd AC A 30 730 75 54,750 1/11/24 95 Overlay-Rubber Hot Mix 11/15/19 MacArthur 9788 MacArthur Blvd 600' w/o Hyland Ave 600' e/o Hyland Ave AC A 30 1,150 75 86,250 1/11/24 95 Overlay-Rubber Hot Mix 11/15/19 MacArthur 9790 MacArthur Blvd E'y edge of SA River Bridge 600' w/o Hyland Ave AAC P 30 580 75 43,500 1/11/24 95 Mill & Overlay - ARHM 11/15/19 Main 11760 Main St CL SR-55 Sunflower Ave AC A 28 780 70 54,600 2/22/24 71 New Construction - Initial 1/1/00 Merrimac 7290 Merrimac Way Harbor Blvd Fairview Rd AC P 10 2,580 29 74,820 1/10/24 95 Overlay-Rubber Hot Mix 1/1/21 Merrimac 7291 Merrimac Way Fairview Rd Harbor Blvd AC P 10 2,580 29 74,820 1/10/24 100 Overlay-Rubber Hot Mix 1/1/21 Mesa Verde 150 Mesa Verde Dr Adams Ave (W) Country Club Dr AC P 21 3,765 24 90,360 1/25/24 90 Surface Treatment - Slurry Seal 1/1/10 Mesa Verde 151 Mesa Verde Dr Country Club Dr Adams Ave (W) AC P 21 3,765 24 90,360 1/18/24 81 Surface Treatment - Slurry Seal 1/1/10 Mesa Verde 160 Mesa Verde Dr Country Club Dr Baker St AC P 21 1,055 24 25,320 1/25/24 81 Surface Treatment - Slurry Seal 1/1/10 Mesa Verde 161 Mesa Verde Dr Baker St Country Club Dr AC P 21 1,055 24 25,320 1/25/24 81 Surface Treatment - Slurry Seal 1/1/10 Mesa Verde 170 Mesa Verde Dr Baker St Adams Ave (E) AC P 21 2,555 24 61,320 1/25/24 83 Surface Treatment - Slurry Seal 1/1/10 Mesa Verde 171 Mesa Verde Dr Adams Ave (E) Baker St AC P 21 2,555 24 61,320 1/25/24 85 Surface Treatment - Slurry Seal 1/1/10 Mesa Verde 180 Mesa Verde Dr Adams Ave (E) Harbor Blvd AAC P 11 2,453 60 147,180 1/30/24 90 Overlay - AC Structural 10/1/15 NewportNB 15411 Newport Blvd North Bound Bay St 22nd St AC S 5 1,965 30 63,950 2/27/24 86 New Construction - Initial 1/1/00
243
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date NewportNB 15412 Newport Blvd North Bound Wilson St Santa Isabel Ave AAC S 5 515 34 18,495 2/28/24 77 Overlay - AC Structural 4/1/13 NewportNB 15413 Newport Blvd North Bound Monte Vista Ave Del Mar Ave AAC S 24 1,349 37 49,913 2/28/24 77 Overlay - AC Structural 4/1/13 NewportNB 15414 Newport Blvd North Bound Del Mar Ave Mesa Dr AAC S 24 1,275 34 45,390 2/21/24 79 Overlay - AC Structural 4/1/13 NewportNB 240 Newport Blvd North Bound Walnut St Bay St AC S 5 1,518 32 48,653 2/27/24 89 New Construction - Initial 1/1/00 NewportNB 250 Newport Blvd North Bound 22nd St Wilson St AAC S 5 2,140 34 73,960 2/28/24 77 Overlay - AC Structural 4/1/13 NewportNB 260 Newport Blvd North Bound Santa Isabel Ave Monte Vista Ave AAC S 24 1,310 37 48,470 2/28/24 73 Overlay - AC Structural 4/1/13 NewportNB 270 Newport Blvd North Bound Mesa Dr Bristol St AC S 10 2,964 37 109,668 2/21/24 76 New Construction - Initial 1/1/00 NewportSB 15415 Newport Blvd South Bound Arlington Dr Mesa Dr AC S 10 1,274 44 57,785 2/27/24 86 New Construction - Initial 1/1/00 NewportSB 15416 Newport Blvd South Bound Fair Dr Vanguard Way AC S 24 2,645 32 84,980 2/27/24 74 New Construction - Initial 1/1/00 NewportSB 15417 Newport Blvd South Bound Bay St Ford Rd AC S 5 1,436 32 45,895 2/27/24 79 New Construction - Initial 1/1/00 NewportSB 241 Newport Blvd South Bound Victoria St Bay St AC S 5 1,900 40 80,500 2/27/24 80 New Construction - Initial 1/1/00 NewportSB 251 Newport Blvd South Bound Vanguard Way Wilson St AC S 5 780 30 28,500 2/27/24 76 New Construction - Initial 1/1/00 NewportSB 252 Newport Blvd South Bound Wilson St 55 FWY SB Off Ramp Merge AC S 5 870 30 20,095 1/9/24 87 New Construction - Initial 1/1/00 NewportSB 253 Newport Blvd South Bound 55 FWY SB Off Ramp Merge Victoria St AC S 5 940 47 46,255 2/27/24 74 New Construction - Initial 1/1/00 NewportSB 261 Newport Blvd South Bound Mesa Dr Fair Dr AC S 24 1,315 44 63,660 2/27/24 75 New Construction - Initial 1/1/00 NewportSB 271 Newport Blvd South Bound Bristol St Arlington Dr AC S 10 1,780 32 56,960 2/28/24 80 New Construction - Initial 1/1/00 Paularino 11590 Paularino Ave Bristol St N/B Newport Blvd AC P 12 2,760 60 163,200 2/22/24 87 Complete Reconstruction - AC 10/1/03 Paularino 11890 Paularino Ave N/B Newport Blvd Red Hill Ave AC P 29 1,110 60 66,600 1/23/24 92 6 in Cold Mill & Overlay in Secure area 8/1/13 Placentia 100 Placentia Ave 19th St Victoria St AAC P 2 3,320 60 199,200 1/31/24 95 Overlay - AC Structural 5/1/07 Placentia 120 Placentia Ave Victoria St Wilson St AAC P 19 1,310 60 77,000 1/31/24 95 Overlay - AC Structural 5/1/07 Placentia 130 Placentia Ave Wilson St City Yard AC P 11 1,000 60 60,000 1/31/24 100 Asphalt Rubber Hot Mix 1/1/24 Placentia 131 Placentia Ave City Yard Estancia N AC P 11 1,220 60 73,200 1/31/24 100 Asphalt Rubber Hot Mix 1/1/24 Placentia 132 Placentia Ave Estancia N Fairview Park AC P 11 1,460 60 87,600 1/31/24 100 Asphalt Rubber Hot Mix 1/1/24 Placentia 133 Placentia Ave Fairview Park Fairview Channel AC P 1,510 60 90,600 1/30/24 100 Asphalt Rubber Hot Mix 1/1/24 Placentia 134 Placentia Ave Fairview Channel Tern Cir AC P 11 1,091 60 65,460 1/30/24 100 Asphalt Rubber Hot Mix 1/1/24 Placentia 135 Placentia Ave Tern Cir Adams Ave AC P 11 790 60 47,400 1/30/24 100 Asphalt Rubber Hot Mix 1/1/24 Placentia 70 Placentia Ave Production Pl (s/o 16th St) 17th St AAC P 7 1,660 60 98,000 1/31/24 95 Surface Treatment - Slurry Seal 1/1/24 Placentia 80 Placentia Ave 17th St 18th St AAC P 7 1,320 60 76,800 1/31/24 95 Surface Treatment - Slurry Seal 1/1/24 Placentia 90 Placentia Ave 18th St 19th St AC P 7 1,310 60 76,200 1/31/24 95 Surface Treatment - Slurry Seal 1/1/24 Red Hill 11820 Red Hill Ave Bristol Ave Kalmus Dr AC P 29 2,372 28 76,031 2/21/24 88 6 in Cold Mill & Overlay in Secure area 8/1/13 Red Hill 11821 Red Hill Ave Kalmus Dr Bristol Ave AC P 29 2,340 28 72,778 2/21/24 78 6 in Cold Mill & Overlay in Secure area 8/1/13 Red Hill 11822 Red Hill Ave Kalmus Dr Paularino Ave AC P 29 3,240 28 118,163 2/21/24 93 6 in Cold Mill & Overlay in Secure area 8/1/13 Red Hill 11823 Red Hill Ave Paularino Ave Kalmus Dr AC P 29 3,275 28 109,914 2/21/24 85 6 in Cold Mill & Overlay in Secure area 8/1/13 Red Hill 11824 Red Hill Ave Airport Loop Dr S'ly edge of Bridge over I-405 AC P 29 800 40 32,000 2/22/24 95 Complete Reconstruction - AC 4/1/13 Red Hill 11825 Red Hill Ave S'ly edge of Bridge over I-405 Airport Loop Dr AC P 29 800 40 32,000 2/22/24 95 Complete Reconstruction - AC 4/1/13 Red Hill 11830 Red Hill Ave Paularino Ave Airport Loop Dr AC P 29 2,210 40 88,400 2/21/24 86 Complete Reconstruction - AC 4/1/13 Red Hill 11831 Red Hill Ave Airport Loop Dr Paularino Ave AC P 29 2,210 40 88,400 2/21/24 88 Complete Reconstruction - AC 4/1/13 Sakioka 11750 Sakioka Dr Anton Blvd Sunflower Ave AAC P 28 1,475 32 47,200 1/18/24 93 Overlay - AC Structural 10/1/08 Sakioka 11751 Sakioka Dr Sunflower Ave Anton Ave AAC P 28 1,475 32 47,200 1/18/24 93 Overlay - AC Structural 10/1/08 Santa Ana 2540 Santa Ana Ave Del Mar Ave Mesa Dr AC S 26 1,330 36 47,880 2/21/24 91 Surface Treatment - Slurry Seal 1/1/17 SouthCoast 720 South Coast Dr Hyland Ave 650' w/o Harbor Blvd AAC P 30 1,000 51 51,000 1/11/24 75 Overlay-Rubber Hot Mix 11/15/19 SouthCoast 724 South Coast Dr 650' w/o Harbor Blvd Harbor Blvd AAC P 30 680 66 44,880 1/11/24 85 Overlay-Rubber Hot Mix 11/15/19 SouthCoast 730 South Coast Dr Harbor Blvd Fairview Rd AC P 30 3,570 33 117,810 1/16/24 69 Surface Treatment - Slurry Seal 1/1/00 SouthCoast 731 South Coast Dr Fairview Rd Susan St AC P 30 1,963 33 64,779 1/16/24 57 Surface Treatment - Slurry Seal 1/1/00 SouthCoast 732 South Coast Dr Susan St Harbor Blvd AC P 30 1,610 33 53,130 1/16/24 75 Surface Treatment - Slurry Seal 1/1/00 SouthCoast 740 South Coast Dr Fairview Rd Carmel Dr AC P 14 835 60 50,100 1/16/24 86 Surface Treatment - Slurry Seal 1/1/18 SouthCoast 750 South Coast Dr Carmel Dr San Leandro Ln AC P 14 1,590 60 95,400 1/16/24 89 Surface Treatment - Slurry Seal 1/1/18 SouthCoast 760 South Coast Dr San Leandro Ln Bear St AC P 27 2,800 46 128,800 1/16/24 86 Complete Reconstruction - AC 1/1/10 SouthCoast 761 South Coast Dr Bear St San Leandro Ln AC P 27 2,800 38 106,400 1/16/24 81 Complete Reconstruction - AC 1/1/10 Sunflower 770 Sunflower Ave Harbor Blvd Hyland Ave AC P 30 1,700 60 99,300 1/11/24 86 Complete Reconstruction - AC 7/1/00 Sunflower 780 Sunflower Ave Harbor Blvd Fairview Rd AC P 30 2,590 33 83,070 2/22/24 73 New Construction - Initial 1/1/00 Sunflower 781 Sunflower Ave Fairview Rd Harbor Blvd AC P 30 2,590 33 85,470 1/18/24 75 New Construction - Initial 1/1/00 Sunflower 790 Sunflower Ave Fairview Rd Wimbledon Wy AC P 27 1,095 60 76,039 1/16/24 74 New Construction - Initial 1/1/00 Sunflower 791 Sunflower Ave Wimbledon Wy Fuschia St AC P 27 1,735 60 102,478 1/16/24 83 New Construction - Initial 1/1/00 Sunflower 792 Sunflower Ave Fuschia St Bear St AC P 27 2,035 60 140,031 1/16/24 75 New Construction - Initial 1/1/00 Sunflower 800 Sunflower Ave Bear St Bristol St AAC A 27 1,990 36 99,843 1/18/24 86 Overlay - AC Structural 10/1/06 Sunflower 801 Sunflower Ave Bristol St Bear St AAC A 27 1,990 36 94,669 2/15/24 73 Overlay - AC Structural 10/1/06
244
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Sunflower 810 Sunflower Ave Bristol St Avenue of the Arts AAC A 28 1,360 36 48,960 2/15/24 79 Overlay - AC Structural 10/1/06 Sunflower 811 Sunflower Ave Main St Avenue of the Arts AC A 28 3,850 36 138,600 2/15/24 83 New Construction - Initial 1/1/00 Sunflower 812 Sunflower Ave Avenue of the Arts Anton Blvd AAC A 28 2,750 36 99,000 2/15/24 81 2 in overlay 8/1/09 Sunflower 814 Sunflower Ave Anton Blvd Main St AC A 28 1,125 36 40,500 2/15/24 87 New Construction - Initial 1/1/00 Sunflower 816 Sunflower Ave Avenue of the Arts Park Center Dr AAC A 28 795 36 33,570 2/15/24 90 Overlay - AC Structural 10/1/06 Sunflower 817 Sunflower Ave Park Center Dr Bristol St AAC A 28 536 36 27,340 2/15/24 54 Overlay - AC Structural 10/1/06 Superior 2950 Superior Ave S'ly City Limits (450' s/o 16th St) Industrial Way AAC P 7 430 78 33,540 2/28/24 89 Overlay - AC Structural 11/1/08 Superior 2960 Superior Ave Industrial Way E 17th St AAC P 7 1,745 55 95,975 2/28/24 90 Overlay - AC Structural 11/1/08 VictoriaSt 15418 Victoria St Doctors Cir Newport Blvd SB AAC S 5 1,255 60 76,389 1/9/24 76 Overlay - AC Structural 2/1/14 VictoriaSt 390 Victoria St E'ly edge of Bridge at SA River Valley Rd AAC P 1 1,300 65 84,500 2/14/24 84 Overlay - AC Structural 4/1/15 VictoriaSt 400 Victoria St Valley Rd Canyon Dr AAC S 1 700 68 47,600 2/14/24 78 Overlay - AC Structural 4/1/15 VictoriaSt 410 Victoria St Canyon Dr National Ave AC S 18 2,155 34 73,270 2/14/24 89 New Construction - Initial 1/1/00 VictoriaSt 411 Victoria St National Ave Canyon Dr AAC S 18 2,155 34 73,270 2/14/24 76 Overlay - AC Structural 4/1/15 VictoriaSt 420 Victoria St National Ave Placentia Ave AAC S 18 1,470 34 49,980 2/14/24 91 Overlay - AC Structural 2/1/14 VictoriaSt 421 Victoria St Placentia Ave National Ave AAC S 18 1,470 34 49,980 2/14/24 88 Overlay - AC Structural 2/1/14 VictoriaSt 430 Victoria St Placentia Ave Pomona Ave AAC S 2 1,320 68 89,760 1/31/24 92 Overlay - AC Structural 2/1/14 VictoriaSt 440 Victoria St Pomona Ave Harbor Blvd AAC S 2 2,625 68 178,500 1/31/24 92 Overlay - AC Structural 2/1/14 VictoriaSt 450 Victoria St Harbor Blvd Doctors Cir AAC S 5 1,840 60 114,552 1/9/24 88 Overlay - AC Structural 2/1/14 Wilson 5800 Wilson St Placentia Ave Raleigh Ave AC S 19 830 36 29,880 1/9/24 100 Asphalt Rubber Hot Mix 9/19/23 Wilson 5810 Wilson St Raleigh Ave Pomona Ave AC S 19 492 36 17,712 1/9/24 100 Asphalt Rubber Hot Mix 9/19/23 Wilson 5820 Wilson St Pomona Ave Fountain Way E AC S 19 1,322 36 47,592 1/9/24 100 Asphalt Rubber Hot Mix 9/19/23 Wilson 5830 Wilson St Fountain Way E Harbor Blvd AC S 19 1,638 46 75,184 1/9/24 100 Asphalt Rubber Hot Mix 9/19/23 Wilson 5840 Wilson St Harbor Blvd College Ave AC S 24 885 61 53,720 1/9/24 100 Asphalt Rubber Hot Mix 9/19/23 Wilson 5850 Wilson St College Ave Fairview Rd AC S 24 2,620 36 94,320 1/9/24 100 Asphalt Rubber Hot Mix 9/19/23
74.4 16,632,332
Locals
15th 2170 15th St Redlands Ave Tustin Ave AC E 9 650 19 12,025 10/8/21 74 Surface Treatment - Slurry Seal 9/1/22 15th 2175 15th St Santa Ana Ave Newport Blvd AC E 9 1,670 18 30,060 10/8/21 65 Surface Treatment - Slurry Seal 9/1/22 16th Pl 2620 16th Pl Santa Ana Ave Tustin Ave AAC E 9 1,320 37 48,840 10/15/21 84 Overlay - AC Structural 4/12/12 16th Pl 2622 16th Pl Orange Ave Santa Ana Ave AAC E 9 1,350 37 49,950 10/15/21 83 Overlay - AC Structural 4/12/12 16th Pl 2624 16th Pl Tustin Ave Irvine Ave AAC E 9 1,320 37 48,840 10/15/21 77 Overlay - AC Structural 4/12/12 16th 2000 16th St Superior Ave Placentia Ave AAC E 7 1,458 36 52,488 9/30/21 99 Overlay - AC Structural 1/1/21 16th 2250 16th St Newport Blvd Orange Ave AAC E 8 470 37 17,390 12/6/21 94 Overlay - AC Structural 4/12/12 16th 2260 16th St Orange Ave Santa Ana Ave AAC E 8 1,320 37 48,840 10/8/21 77 Overlay - AC Structural 4/12/12 16th 2270 16th St Santa Ana Ave Tustin Ave AAC E 9 1,300 37 48,100 10/8/21 75 Overlay - AC Structural 4/12/12 16th 2280 16th St Tustin Ave Irvine Ave AAC E 9 1,334 36 48,024 10/8/21 75 Overlay - AC Structural 4/12/12 16th 2905 16th St Superior Ave Newport Blvd AC E 7 800 37 29,600 1/5/22 39 Surface Treatment - Slurry Seal 9/1/08 17th 3030 17th St Newport Blvd "V"-Right (w/o Bullnose) AAC E 8 450 18 8,100 11/29/21 72 Surface Treatment - Slurry Seal 3/3/22 17th 3031 17th St "V"-Right (w/o Bullnose) Newport Blvd AAC E 8 480 18 8,640 12/28/21 65 Surface Treatment - Slurry Seal 3/3/22 18th 3060 18th St W'ly City Limits Whittier Ave AC E 6 660 37 24,420 10/1/21 79 Surface Treatment - Slurry Seal 1/1/21 18th 3065 18th St Whittier Ave Monrovia Ave AC E 6 1,320 36 47,520 10/1/21 86 Surface Treatment - Slurry Seal 1/1/21 18th 3070 18th St Monrovia Ave Placentia Ave AC E 6 1,312 36 47,232 10/1/21 86 Surface Treatment - Slurry Seal 1/1/21 18th 3080 18th St Placentia Ave Pomona Ave AC E 7 1,321 36 47,556 10/1/21 90 Surface Treatment - Slurry Seal 1/1/21 18th 3090 18th St Pomona Ave Anaheim Ave AC E 7 1,320 36 47,520 10/1/21 87 Surface Treatment - Slurry Seal 1/1/21 18th 3100 18th St Anaheim Ave Newport Blvd AAC E 7 880 36 31,680 10/1/21 97 Overlay - AC Structural 1/1/21 18th 3760 18th St Newport Blvd Orange Ave AC E 8 1,360 45 61,200 10/8/21 79 Complete Reconstruction - AC 2/1/12 18th 3770 18th St Orange Ave Santa Ana Ave AAC E 8 1,323 36 47,628 10/8/21 88 Overlay - AC Structural 4/12/12 18th 3780 18th St Santa Ana Ave Irvine Ave AAC E 9 2,643 36 95,148 10/8/21 88 Overlay - AC Structural 4/12/12 20th 4280 20th St Cul-de-sac Monrovia Ave AAC E 1 320 27 10,814 11/16/21 91 Overlay - AC Structural 5/1/10 20th 4285 20th St Monrovia Ave Federal Ave AC E 1 535 33 17,655 12/6/21 85 Overlay - AC Thin 8/1/08 20th 4610 20th St Placentia Ave Pomona Ave AC E 2 1,218 37 46,104 10/1/21 90 Surface Treatment - Slurry Seal 12/1/19 20th 5240 20th St Newport Blvd Frontage Road Santa Ana Ave AC E 3 2,650 37 98,050 11/9/21 75 Mill and Overlay 4/12/12 20th 5250 20th St Santa Ana Ave Irvine Ave AAC E 4 2,634 37 97,458 11/9/21 85 Overlay - AC Structural 4/12/12 21st 5450 21st St Newport Blvd Santa Ana Ave AAC E 3 2,690 37 99,530 10/8/21 84 Overlay - AC Structural 4/12/12 21st 5460 21st St Santa Ana Ave Tustin Ave AAC E 4 1,300 37 48,100 10/8/21 81 Overlay - AC Structural 4/12/12 23rd 6610 23rd St Newport Blvd Elden Ave AAC E 25 683 37 25,271 10/7/21 96 Overlay - AC Structural 1/8/19
245
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date 23rd 6620 23rd St Elden Ave Santa Ana Ave AAC E 25 1,976 37 73,112 10/7/21 98 2 in Cold Mill & Overlay 1/1/17 23rd 6630 23rd St Santa Ana Ave Waterman Way AAC E 25 240 37 8,880 10/7/21 90 2 in Cold Mill & Overlay 1/1/17 24th 6840 24th Pl Cul-de-sac Hill Pl AAC E 26 450 34 17,474 10/5/21 96 2 in Cold Mill & Overlay 1/1/17 Abbie 3690 Abbie Way W'ly Cul-de-sac Irvine Ave AAC E 9 531 37 21,821 11/19/21 84 Overlay - AC Structural 4/12/12 Airport 11930 Airport Loop Dr Red Hill Ave Cul-de-sac AC E 29 1,726 60 107,558 11/8/21 79 6 in Cold Mill & Overlay in Secure area 8/1/13 Airway 11800 Airway Ave Clinton Ave Fischer Ave AC E 29 2,721 60 276,209 11/8/21 70 6 in Cold Mill & Overlay in Secure area 8/1/13 Airway 11805 Airway Ave Fischer Ave Paularino Ave AC E 29 1,852 60 276,209 11/8/21 71 6 in Cold Mill & Overlay in Secure area 8/1/13 Airway 11810 Airway Ave Paularino Ave Airport Loop Dr AC E 29 2,306 60 139,282 10/28/21 80 6 in Cold Mill & Overlay in Secure area 8/1/13 Alabama 9180 Alabama Cir Cul-de-sac Cul-de-sac AC E 17 660 37 28,768 10/21/21 75 Surface Treatment - Slurry Seal 10/3/23 Alanzo 10080 Alanzo Ln Cul-de-sac Mission Dr AAC E 20 200 33 8,774 11/17/21 80 Overlay - AC Structural 6/28/11 Alaska 9190 Alaska Ave Alabama Cir California St AC E 17 437 37 16,169 10/21/21 89 Surface Treatment - Slurry Seal 3/3/22 Albany 10520 Albany St Coolidge Ave Fillmore Way AAC E 16 330 37 12,210 11/17/21 94 Overlay - AC Structural 10/1/15 Albatross 7410 Albatross Rd Swan Dr Adams Ave AC E 11 1,344 37 49,728 10/6/21 89 Complete Reconstruction - AC 1/1/03 Albert 6600 Albert Pl Newport Blvd Santa Ana Ave AAC E 25 2,650 37 98,050 10/7/21 94 2 in Cold Mill & Overlay 1/1/17 Aliso 2780 Aliso Ave 16th St Cambridge Cir AAC E 9 873 37 32,301 10/15/21 72 Overlay - AC Structural 4/12/12 Aliso 5270 Aliso Ave Walnut Pl Esther St AAC E 4 330 37 12,210 11/9/21 85 Overlay - AC Structural 4/12/12 Aliso 5310 Aliso Ave 20th St Cul-de-sac AAC E 4 789 37 31,367 11/19/21 78 Overlay - AC Structural 4/12/12 Allegheny 11520 Allegheny Ave Canadian Dr Yellowstone Dr AAC E 31 599 37 22,163 10/28/21 76 Overlay - AC Structural 10/1/15 Alva 5200 Alva Ln Santa Ana Ave Raymond Ave AAC E 4 650 37 24,050 11/10/21 84 Overlay - AC Structural 4/12/12 American 5640 American Ave Victoria St State Ave AAC E 18 980 37 36,260 12/29/21 79 Overlay - AC Structural 10/1/15 AmericanPL 5650 American Pl American Ave Cul-de-sac AC E 18 255 37 11,609 11/9/21 47 Surface Treatment - Slurry Seal 10/6/15 Amherst Pl 6390 Amherst Pl Columbia Dr Cul-de-sac AC E 24 210 37 9,944 11/10/21 75 Surface Treatment - Slurry Seal 9/1/09 Amherst Rd 6380 Amherst Rd Notre Dame Dr Columbia Dr AC E 24 575 37 22,835 11/10/21 61 Surface Treatment - Slurry Seal 9/1/09 Anaheim 3210 Anaheim Ave Superior Ave 19th St AC E 7 2,500 37 92,500 11/15/21 99 Surface Treatment - Slurry Seal 1/1/21 Anaheim 3220 Anaheim Ave 19th St Bay St AAC E 2 1,994 37 73,778 11/12/21 97 Overlay - AC Structural 11/15/19 Anaheim 6090 Anaheim Ave Cul-de-sac Wilson St AAC E 19 560 37 22,894 11/23/21 90 Overlay - AC Structural 5/3/10 Andover 6480 Andover Pl Nassau Rd Cul-de-sac AC E 24 360 37 15,494 11/10/21 82 Surface Treatment - Slurry Seal 9/1/09 Andover 7180 Andover Pl Cul-de-sac Bucknell Rd AAC E 10 370 37 15,864 11/10/21 78 Overlay - AC Structural 5/1/06 Andros 8490 Andros St Elm Ave Samar Pl AC E 21 840 37 31,080 11/16/21 84 Surface Treatment - Slurry Seal 1/1/10 Andros 8500 Andros St Samar Pl Baker St AC E 21 1,535 37 57,495 1/5/22 91 Surface Treatment - Slurry Seal 1/1/10 Annapolis 10580 Annapolis St Garfield Ave Harding Way AAC E 16 500 37 18,225 11/17/21 86 Overlay - AC Structural 10/1/15 Anza 10060 Anza Ln Cul-de-sac Mission Dr AAC E 20 200 33 8,774 11/17/21 77 Overlay - AC Structural 5/28/11 Arbor 4210 Arbor St W'ly Cul-de-sac Whittier Ave AAC E 1 261 37 11,831 10/1/21 93 Overlay - AC Structural 3/20/16 Arbor 4220 Arbor St Whittier Ave Continental Ave AC E 1 1,668 33 58,872 10/15/21 90 Surface Treatment - Slurry Seal 3/20/16 Arizona 9250 Arizona Ln Cul-de-sac Iowa St AC E 17 364 37 15,642 10/21/21 89 Surface Treatment - Slurry Seal 10/23/23 Arnold 4700 Arnold Ave Beach St Cove St AAC E 2 1,082 37 42,508 12/28/21 94 Overlay - AC Structural 6/16/15 Arthur 10460 Arthur Ave Dorset Ln Paularino Ave AAC E 16 269 37 9,953 11/16/21 83 Overlay - AC Structural 10/1/15 Aster 5600 Aster Pl S'ly Cul-de-sac N'ly Cul-de-sac AAC E 3 381 37 18,445 11/9/21 94 Overlay - AC Structural 3/20/16 Atlanta 10650 Atlanta Way Cul-de-sac Van Buren Ave AAC E 16 440 37 18,454 11/17/21 74 Overlay - AC Structural 10/1/15 Augusta 10660 Augusta St Fairview Rd Van Buren Ave AAC E 16 520 37 19,240 10/26/21 65 Overlay - AC Structural 10/1/15 Austin 10670 Austin St Van Buren Ave Coolidge Ave AAC E 16 782 37 28,934 10/26/21 76 Overlay - AC Structural 10/1/15 Avalon 6200 Avalon St Avocado St Wilson St AC E 5 661 37 24,457 11/23/21 95 Surface Treatment - Slurry Seal 12/1/19 Avalon 6280 Avalon St Wilson St Joann St AC E 24 470 36 17,048 11/23/21 84 Surface Treatment - Slurry Seal 2/1/06 AveOTArts 11740 Avenue of the Arts Anton Ave Sunflower Ave AAC E 28 1,457 21 31,034 10/28/21 71 Overlay - AC Structural 10/1/06 AveOTArts 11741 Avenue of the Arts Sunflower Ave Anton Blvd AAC E 28 1,457 21 31,034 10/28/21 71 Overlay - AC Structural 10/1/06 AveOTArts 11744 Avenue of the Arts Anton Ave S'ly City limits AC E 28 360 75 27,000 10/28/21 84 New Construction - Initial 1/1/00 Aviemore 4410 Aviemore Terr Gleneagles Terr Valley Rd AC E 1 941 37 34,817 11/16/21 84 New Construction - Initial 1/1/00 Avocado 6180 Avocado St College Ave Fairview Rd AAC E 5 2,580 37 95,160 10/6/21 100 Overlay - AC Structural 11/15/19 Ayon 7790 Ayon Cir Balearic Cir Cul-de-sac AC E 22 200 37 9,574 10/25/21 78 Surface Treatment - Slurry Seal 1/1/10 Azalia 11330 Azalea Dr Begonia Ave Fuschia St AC E 27 1,520 37 56,240 10/29/21 85 Surface Treatment - Slurry Seal 1/1/18 Babb 10420 Babb St Post Rd Baker St AC E 20 640 37 23,680 10/22/21 84 New Construction - Initial 1/1/00 Babb 10610 Babb St Baker St Paularino Ave AC E 16 831 37 30,747 10/19/21 55 New Construction - Initial 1/1/00 Babcock 2910 Babcock St 16th St 17th St AAC E 6 1,300 37 48,100 10/1/21 84 Surface Treatment - Slurry Seal 3/15/22 Bahama 8800 Bahama Pl Country Club Dr Cul-de-sac AC E 22 527 37 21,673 11/16/21 100 Surface Treatment - Slurry Seal 3/15/22 Baker 630 Baker St Samar Dr Mesa Verde Dr AC E 21 1,670 37 62,194 1/4/22 57 Surface Treatment - Slurry Seal 1/1/10 Baker 710 Baker St Red Hill Ave Airway Ave AC E 29 1,030 60 62,109 11/8/21 80 6 in Cold Mill & Overlay in Secure area 8/1/13 Balearic 7710 Balearic Dr Europa Dr Boa Vista Dr AC E 22 1,421 36 51,775 10/25/21 61 Surface Treatment - Slurry Seal 1/1/10
246
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Balearic 7760 Balearic Dr Boa Vista Dr Suva Cir AC E 22 884 37 32,708 10/25/21 81 Surface Treatment - Slurry Seal 1/1/10 Bali 8180 Bali Cir Cul-de-sac Jamaica Rd AC E 22 138 37 7,280 11/16/21 100 Surface Treatment - Slurry Seal 6/1/21 Ballow 10100 Ballow Ln El Camino Dr Mission Dr AAC E 20 440 36 16,240 11/17/21 82 Overlay - AC Structural 8/1/07 Balmoral 4460 Balmoral Pl S'ly Cul-de-sac Sea Bluff Dr AAC E 1 160 37 8,094 11/16/21 89 Overlay - AC Structural 6/1/08 Baltra 7720 Baltra Pl Europa Dr Inroz Dr AC E 22 779 37 29,323 12/29/21 51 Surface Treatment - Slurry Seal 1/1/10 Barbados 8240 Barbados Pl Labrador Dr Madagasgar St AC E 23 1,316 37 53,433 1/5/22 51 Surface Treatment - Slurry Seal 1/1/10 Bay 4760 Bay St Meyer Pl Maple Ave AAC E 2 882 37 32,634 10/18/21 98 Overlay - AC Structural 11/15/19 Bay 4910 Bay St Harbor Blvd Newport Blvd AAC E 5 2,000 37 74,000 9/30/21 89 Overlay - AC Structural 5/19/17 Bay 5300 Bay St Tustin Ave Aliso Ave AAC E 4 672 37 24,864 11/19/21 85 Overlay - AC Structural 4/12/12 Bay 5340 Bay St NB Newport Blvd Frontage Road Orange Ave AAC E 3 1,354 36 48,744 9/17/21 82 Overlay - AC Structural 4/12/12 Bay 5380 Bay St Westminster Ave Santa Ana Ave AAC E 3 671 37 24,827 11/9/21 84 Overlay - AC Structural 4/12/12 Beach 4690 Beach St Arnold Ave Meyer Pl AAC E 2 600 37 22,200 12/28/21 94 Overlay - AC Structural 6/16/15 Bear 10340 Bear St Bristol St Baker St AC E 20 2,600 31 79,300 11/1/21 85 Complete Reconstruction - AC 1/1/10 Begonia 11260 Begonia Ave Smalley Rd Fuschia St AC E 27 775 37 28,103 10/27/21 80 Surface Treatment - Slurry Seal 1/8/19 Begonia 11320 Begonia Ave Fuchsia St Azalea St AC E 27 1,069 37 39,553 10/29/21 84 Surface Treatment - Slurry Seal 1/8/19 Belfast 9520 Belfast Ave Killybrooke Ln Fairview Rd AAC E 15 1,850 36 66,600 11/15/21 88 Overlay - AC Structural 3/20/16 Bermuda 8230 Bermuda Dr Labrador Dr Gisler Ave AC E 23 1,194 37 46,221 11/16/21 77 Surface Treatment - Slurry Seal 1/1/10 Bernard 4855 Bernard St Maple Ave Harbor Blvd AC E 2 866 37 32,042 11/12/21 93 Surface Treatment - Slurry Seal 12/1/19 Bernard 4860 Bernard St Harbor Blvd E'ly end AC E 5 870 33 28,710 11/15/21 91 Surface Treatment - Slurry Seal 12/1/19 Bimini 8540 Bimini Pl Cul-de-sac Baker St AC E 21 783 37 31,145 1/5/22 43 Surface Treatment - Slurry Seal 1/1/10 Bismark 10700 Bismark Way Cul-de-sac Van Buren Ave AAC E 16 435 37 18,149 11/17/21 80 Overlay - AC Structural 10/1/15 Blue Bird 7620 Blue Bird Cir Hummingbird Dr Cul-de-sac AAC E 11 722 37 28,888 10/6/21 78 Overlay - AC Structural 10/1/15 BoaVistaC 7820 Boa Vista Cir Cul-de-sac Stromboli Rd AC E 21 496 37 20,526 1/5/22 44 Surface Treatment - Slurry Seal 1/1/10 BoaVistaDr 7670 Boa Vista Dr Kornat Dr Mesa Verde Dr AC E 22 1,800 37 66,600 11/11/21 53 Surface Treatment - Slurry Seal 1/1/10 Boise 10710 Boise Way Cul-de-sac Van Buren Ave AC E 16 416 37 17,591 11/17/21 57 New Construction - Initial 1/1/00 Bonnie 6770 Bonnie Pl Santa Isabel Ave Cul-de-sac AC E 26 320 33 12,734 11/9/21 60 Surface Treatment - Slurry Seal 1/8/19 Boston 10750 Boston Way Cul-de-sac Charldston St AC E 16 260 37 12,380 11/17/21 58 New Construction - Initial 1/1/00 Bowdoin 6470 Bowdoin Pl Nassau Rd Cul-de-sac AC E 24 360 37 15,494 11/10/21 89 Surface Treatment - Slurry Seal 9/1/09 Bowdoin 7170 Bowdoin Pl Cul-de-sac Bucknell Rd AAC E 10 360 37 15,494 11/10/21 82 Overlay - AC Structural 10/1/07 Bowling 7260 Bowling Green Dr Hanover Dr Yale Pl AC E 10 1,176 37 43,512 11/10/21 64 6 in Cold Mill & Overlay in Secure area 2/1/12 Bray 9670 Bray Ln McCormack St Londonderry St AC E 15 614 37 22,968 11/15/21 81 Surface Treatment - Slurry Seal 3/20/16 BrentwdPl 6890 Brentwood Pl Cul-de-sac Brentwood St AC E 26 145 37 7,539 10/5/21 79 6 in Cold Mill & Overlay in Secure area 12/1/13 BrentwdSt 6880 Brentwood St Norse St Santa Ana Ave AAC E 26 1,290 37 47,730 10/5/21 82 Overlay - AC Structural 7/1/12 Briggs 11880 Briggs Ave Pullman St Red Hill Ave AC E 29 730 60 43,800 11/8/21 73 6 in Cold Mill & Overlay in Secure area 8/1/13 Broadway 3970 Broadway Newport Blvd Orange Ave AC E 1,330 50 66,500 11/15/21 83 New Construction - AC 1/1/80 Broadway 3980 Broadway Orange Ave Santa Ana Ave AC E 1,330 42 52,115 11/15/21 84 New Construction - AC 1/1/80 Broadway 3990 Broadway Santa Ana Ave Tustin Ave AC E 1,350 50 67,500 11/15/21 82 New Construction - AC 1/1/80 Broadway 4000 Broadway Tustin Ave Irvine Ave AAC E 9 1,345 40 53,800 11/15/21 84 Overlay - AC Structural 4/12/12 Buchanan 10480 Buchanan Way Cul-de-sac Dorset Ln AAC E 16 280 37 12,534 11/16/21 75 Overlay - AC Structural 10/1/15 Bucknell 7130 Bucknell Rd Carnegie Ave Columbia Dr AAC E 10 2,560 37 94,720 11/10/21 95 Overlay - AC Structural 5/19/20 Bunting 7570 Bunting Cir Oriole Dr Cul-de-sac AAC E 11 500 37 20,674 10/6/21 74 Overlay - AC Structural 10/1/15 Buoy 3960 Buoy St Fullerton Ave Orange Ave AAC E 3 630 37 23,310 9/17/21 94 Overlay - AC Structural 4/12/12 Cabrillo 3530 Cabrillo St Newport Blvd Orange Ave AAC E 8 1,300 37 48,100 11/29/21 81 Overlay - AC Structural 4/12/12 Cabrillo 3540 Cabrillo St Orange Ave Santa Ana Ave AAC E 8 1,330 37 49,210 10/8/21 79 Overlay - AC Structural 4/12/12 Cabrillo 3550 Cabrillo St Santa Ana Ave Raymond Ave AAC E 9 642 37 23,754 11/29/21 81 Overlay - AC Structural 7/1/12 Cabrillo 3680 Cabrillo St Tustin Ave Irvine Ave AAC E 9 1,340 37 49,580 11/19/21 77 Overlay - AC Structural 1/1/10 Cadillac 9730 Cadillac Ave Sunflower Ave Cul-de-sac AC E 30 1,900 37 72,474 10/21/21 67 New Construction - Initial 1/1/00 California 9140 California St Gisler Ave Minnesota Ave AC E 17 2,150 60 129,000 11/17/21 95 Surface Treatment - Slurry Seal 12/1/19 California 9145 California St Minnesota Ave Iowa St (N'ly BCR) AAC E 17 1,140 60 68,400 11/17/21 92 Overlay - AC Structural 11/15/19 California 9150 California St Iowa St (N'ly BCR) New Hampshire Dr (S'ly BCR) AC E 17 350 26 8,925 11/17/21 96 Surface Treatment - Slurry Seal 12/1/19 California 9155 California St New Hampshire Dr (S'ly BCR) Iowa St (N'ly BCR) AAC E 17 350 26 8,925 11/17/21 96 Surface Treatment - Slurry Seal 12/1/19 California 9158 California St New Hampshire Dr (S'ly BCR) Nevada Ave AAC E 17 640 40 25,600 10/6/23 100 Overlay - AC Structural 10/6/23 Calvert 7680 Calvert Ave Europa Dr Shantar Dr AC E 22 950 37 35,150 10/25/21 52 Surface Treatment - Slurry Seal 1/1/10 Cambridge 2770 Cambridge Cir W'ly Cul-de-sac E'ly Cul-de-sac AAC E 9 590 37 26,178 10/15/21 78 Overlay - AC Structural 4/1/12 Camellia 5630 Camellia Ln Orange Ave Santa Ana Ave AC E 3 1,320 37 48,840 10/7/21 84 New Construction - Initial 1/1/00 Canadian 11530 Canadian Dr Allegheny Ave Olympic Ave AAC E 31 500 37 18,500 10/28/21 72 Overlay - AC Structural 10/1/15 Canary 7510 Canary Dr S'ly end Oriole Dr AAC E 11 780 37 28,860 10/6/21 78 Overlay - AC Structural 10/1/15
247
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Cannonade 11250 Cannonade Cir Venetian Dr Cul-de-sac AAC E 27 400 37 14,800 10/27/21 94 2 in Cold Mill & Overlay 1/1/18 Canyon 4530 Canyon Dr Sea Bluff Dr Victoria Dr AAC E 1 667 37 24,679 11/16/21 90 Overlay - AC Structural 1/1/10 Canyon 4540 Canyon Dr Victoria St Wilson St AC E 18 1,700 35 59,500 11/9/21 83 Surface Treatment - Slurry Seal 10/6/15 Canyon 4545 Canyon Dr Wilson St 700' n/o Wilson St AC E 18 700 37 25,900 10/6/21 88 Complete Reconstruction - AC 9/1/04 Canyon 4547 Canyon Dr 700' n/o Wilson St N'ly end AAC E 11 640 20 12,800 10/6/21 83 Overlay - AC Structural 8/1/08 Cape Verde 8820 Cape Verde Pl Cul-de-sac Gisler Ave AAC E 22 260 37 11,794 11/16/21 83 Overlay - AC Structural 1/12/12 Capital 5750 Capital St National Ave Continental Ave AAC E 18 661 37 24,651 11/9/21 94 Overlay - AC Structural 5/1/07 Capital 5754 Capital St Republic Ave National Ave AAC E 18 656 37 24,735 11/9/21 73 Surface Treatment - Slurry Seal 10/6/15 Capital 5980 Capital St Pomona Ave E'ly end AAC E 19 490 37 18,130 11/9/21 84 Overlay - AC Structural 6/1/03 Capri Cir 8120 Capri Cir Cul-de-sac Capri Ln AC E 22 280 37 12,534 10/4/21 87 Surface Treatment - Slurry Seal 1/1/10 Capri Ln 8110 Capri Ln Mesa Verde Dr Cul-de-sac AC E 22 1,328 37 51,310 10/4/21 78 Surface Treatment - Slurry Seal 1/1/10 Caraway 8710 Caraway Dr Coral Ave Cinnamon Ave AC E 23 1,426 37 52,762 10/22/21 55 Surface Treatment - Slurry Seal 1/1/10 Cardinal 7480 Cardinal Dr Swan Cir Oriole Dr AAC E 11 880 37 32,560 10/4/21 88 Overlay - AC Structural 10/1/15 Carlton 6820 Carlton Pl Wilson St Santa Isabel Ave AAC E 25 500 37 18,500 10/5/21 86 Surface Treatment - Slurry Seal 4/1/16 Carlton 6830 Carlton Pl Santa Isabel Ave 24th Pl AC E 26 270 37 9,990 10/5/21 91 Surface Treatment - Slurry Seal 1/8/19 Carmel 11030 Carmel Dr South Coast Dr Salinas Ave AC E 14 448 37 16,576 10/27/21 74 Surface Treatment - Slurry Seal 1/8/19 Carnation 11310 Carnation Ave Fuschia St Cul-de-sac AC E 27 1,315 37 50,829 10/27/21 84 Surface Treatment - Slurry Seal 1/8/19 Carnegie 7100 Carnegie Ave Fair Dr Princeton Dr AC E 10 1,254 37 46,398 11/10/21 59 Surface Treatment - Slurry Seal 9/1/09 Carson 10720 Carson St Van Buren Ave Coolidge Ave AC E 16 783 37 29,241 11/17/21 59 New Construction - Initial 1/1/00 Cassia 8660 Cassia Ave Wintergreen Pl Caraway Dr AC E 23 410 37 15,170 11/15/21 95 Surface Treatment - Slurry Seal 1/1/10 Catherine 6670 Catherine Pl Cul-de-sac Cecil Pl AAC E 25 118 34 6,581 10/7/21 99 2 in Cold Mill & Overlay 1/1/17 Cecil 6590 Cecil Pl Newport Blvd Santa Ana Ave AC E 25 2,513 37 88,533 10/7/21 63 Surface Treatment - Slurry Seal 4/1/16 Cedar 4260 Cedar Pl Republic Ave Monrovia Ave AAC E 1 753 33 24,808 10/1/21 87 Overlay - AC Structural 1/1/10 Center 3330 Center St Monrovia Ave Placentia Ave AAC E 6 1,294 37 47,878 10/1/21 100 Overlay - AC Structural 11/15/19 Center 3340 Center St Placentia Ave Pomona Ave AAC E 7 1,332 37 49,284 10/1/21 100 Overlay - AC Structural 11/15/19 Center 3380 Center St Pomona Ave Anaheim Ave AC E 7 1,323 33 43,659 11/15/21 97 Surface Treatment - Slurry Seal 6/1/21 Century 10380 Century Pl Cul-de-sac Baker St AAC E 13 710 47 35,544 11/1/21 83 Overlay - AC Structural 7/1/04 CeylonDr 8030 Ceylon Dr Palau Pl Cul-de-sac AC E 21 1,180 37 45,834 12/15/21 57 Surface Treatment - Slurry Seal 1/1/10 CeylonRd 8160 Ceylon Rd Cul-de-sac Madeira Ave AC E 23 1,424 37 54,862 11/16/21 44 Surface Treatment - Slurry Seal 1/1/10 CharleDr 6160 Charle Dr Victoria St Cul-de-sac AC E 19 240 37 11,054 12/28/21 90 Surface Treatment - Slurry Seal 10/6/15 CharleSt 4840 Charle St Bernard St Hamilton St AC E 2 1,880 37 69,560 11/12/21 87 Surface Treatment - Slurry Seal 12/1/19 Charleston 10760 Charleston St Boston Way Coolidge Ave AAC E 16 1,090 37 42,732 11/17/21 74 Overlay - AC Structural 10/1/16 Chestnut 8410 Chestnut Ave Minorca Dr Primrose St AC E 21 487 37 18,235 10/15/21 90 Surface Treatment - Slurry Seal 1/1/10 Cheyenne 10780 Cheyenne St Coolidge Ave Paularino Ave AAC E 16 2,800 37 104,547 10/19/21 77 Overlay - AC Structural 10/1/15 Chios 7750 Chios Rd Balearic Dr Lemnos Dr AC E 22 530 37 19,860 10/15/21 72 Surface Treatment - Slurry Seal 1/1/10 Church 4980 Church St 19th St 20th St AAC E 3 1,330 37 49,210 11/10/21 83 Overlay - AC Structural 4/1/12 Cibola 9930 Cibola Ave Presidio Dr Coronado Dr AAC E 20 1,167 37 43,179 11/22/21 84 Overlay - AC Structural 12/1/15 Cinnamon 8720 Cinnamon Ave Caraway Dr Gisler Ave AC E 23 1,300 37 48,100 10/22/21 75 6 in Cold Mill & Overlay in Secure area 10/1/13 Clearbrook 6550 Clearbrook Way Cul-de-sac Vanguard Way AAC E 24 460 37 19,194 12/15/21 90 Overlay - AC Structural 10/1/06 Cleveland 10490 Cleveland Ave Cul-de-sac Paularino Ave AAC E 16 749 37 29,887 11/16/21 74 Overlay - AC Structural 10/1/15 Clinton 11790 Clinton Ave Red Hill Ave Cul-de-sac AC E 29 1,275 40 53,150 9/16/21 84 6 in Cold Mill & Overlay in Secure area 8/1/13 Club House 7880 Club House Rd Pitcairn Dr Mesa Verde Dr W AC E 21 1,860 37 68,820 11/11/21 100 Surface Treatment - Slurry Seal 6/1/21 Club House 7890 Club House Rd Mesa Verde Dr W N'ly end at Golf Course Parking Lot AAC E 22 750 37 27,750 11/11/21 57 Overlay - AC Structural 10/14/11 Club Mesa 7060 Club Mesa Pl Cul-de-sac Mesa Dr AAC E 26 490 33 18,344 9/17/21 86 Overlay - AC Structural 1/8/19 Colby 7140 Colby Pl Cul-de-sac Bucknell Rd AAC E 10 351 37 15,161 11/10/21 76 Overlay - AC Structural 7/1/08 Colgate 6270 Colgate Dr Wilson St Joann St AC E 24 470 36 17,190 11/23/21 89 Surface Treatment - Slurry Seal 2/1/06 Colgate 6350 Colgate Dr Wake Forest Rd Villanova Rd AC E 24 1,131 37 41,847 11/10/21 75 Surface Treatment - Slurry Seal 9/1/09 Colleen 20000 Colleen Pl Santa Ana Ave CDS AC E 554 37 21,586 10/8/21 76 Surface Treatment - Slurry Seal 4/1/16 CollegeAve 4940 College Ave S'ly end Victoria St AAC E 5 432 37 15,984 11/11/21 91 Surface Treatment - Slurry Seal 12/1/19 CollegeAve 6170 College Ave Victoria St Wilson St AC E 5 1,310 57 74,670 11/23/21 91 Surface Treatment - Slurry Seal 12/1/19 CollegeAve 9350 College Ave Village Way Baker St AC E 15 911 37 33,707 10/29/21 99 2 in Cold Mill & Overlay 1/1/18 CollegeAve 9355 College Ave Baker St Gisler Ave AC E 15 2,500 37 92,500 11/15/21 72 Surface Treatment - Slurry Seal 3/20/16 CollegeDr 6320 College Dr Wake Forest Rd Cul-de-sac AC E 24 1,741 37 66,591 11/10/21 84 Surface Treatment - Slurry Seal 9/1/09 ColoradoLn 9290 Colorado Ln Cul-de-sac Iowa St AAC E 17 695 37 27,889 3/3/22 100 Overlay - AC Structural 3/3/22 ColoradoPl 9100 Colorado Pl Cul-de-sac California St AAC E 17 500 37 20,674 3/3/22 100 Overlay - AC Structural 3/3/22 Columbia 6290 Columbia Dr Wilson St Wake Forest Rd AC E 24 793 37 29,341 11/23/21 79 Surface Treatment - Slurry Seal 1/1/21 Columbia 6360 Columbia Dr Wake Forest Rd Loyola Rd AC E 10 1,126 37 41,662 11/10/21 68 Surface Treatment - Slurry Seal 2/1/06
248
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Columbia 6440 Columbia Dr Fair Dr Hanover Dr AC E 10 1,148 37 42,476 11/23/21 56 Surface Treatment - Slurry Seal 2/1/06 Concord 10850 Concord St Pierce Ave Jefferson Ave AAC E 16 1,045 36 39,269 10/19/21 78 Overlay - AC Structural 10/1/15 Congress 5680 Congress St State Ave Placentia Ave AAC E 18 2,500 33 82,500 11/9/21 80 Overlay - AC Structural 9/15/15 Congress 5910 Congress St W'ly end Raleigh Ave AC E 19 456 37 16,872 11/9/21 83 Complete Reconstruction - AC 2/1/07 Congress 5960 Congress St Pomona Ave Puente Ave AAC E 19 520 37 19,240 11/9/21 82 Overlay - AC Fabric 6/1/03 Continentl 4230 Continental Ave Arbor St Oak St AAC E 1 2,205 33 72,765 12/29/21 93 Overlay - AC Structural 3/20/16 Continentl 4235 Continental Ave Oak St Victoria St AC E 1 790 33 26,070 11/16/21 85 Surface Treatment - Slurry Seal 1/1/07 Continentl 5740 Continental Ave Senate St Wilson St AC E 18 530 37 19,610 11/9/21 88 Surface Treatment - Slurry Seal 10/6/15 Conway 9510 Conway Ave Killybrook Ln Cul-de-sac AAC E 15 2,167 37 82,353 11/15/21 100 Overlay - AC Structural 1/1/21 Coolidge 10510 Coolidge Ave Baker St Paularino Ave AC E 16 840 21 17,220 11/16/21 80 New Construction - Initial 1/1/00 Coolidge 10511 Coolidge Ave Paularino Ave Baker St AC E 16 840 21 17,220 11/16/21 77 New Construction - Initial 1/1/00 Coolidge 10770 Coolidge Ave Paularino Ave Charleston St AAC E 16 1,496 36 55,337 10/19/21 79 Overlay - AC Structural 10/1/15 Coral 8640 Coral Ave Wintergreen Pl Caraway Dr AAC E 23 400 37 14,800 11/15/21 88 Surface Treatment - Slurry Seal 1/1/10 Coral 8740 Coral Ave Caraway Dr Coriander Dr AAC E 23 270 37 9,990 10/26/21 75 Surface Treatment - Slurry Seal 1/1/10 Coriander 8750 Coriander Dr Coral Ave Cinnamon Ave AC E 23 1,387 37 51,319 10/26/21 38 Surface Treatment - Slurry Seal 1/1/10 Cork 9650 Cork Ln McCormack St Londonderry St AC E 15 580 37 21,635 11/15/21 60 Surface Treatment - Slurry Seal 3/20/16 Cornell 6250 Cornell Dr Wilson St Joann St AC E 24 470 36 17,239 11/23/21 89 Surface Treatment - Slurry Seal 2/1/06 Cornell 6330 Cornell Dr Wake Forest Rd Villanova Rd AC E 24 1,100 37 40,145 11/23/21 74 Surface Treatment - Slurry Seal 9/1/09 Corona 9995 Corona Ln Salvador St El Camino Dr AAC E 20 1,200 37 46,400 11/17/21 91 Overlay - AC Structural 12/1/15 Coronado 9900 Coronado Dr Presido Dr La Salle Ave AAC E 20 1,480 37 54,760 12/29/21 65 Overlay - AC Structural 3/1/08 Coronado 9904 Coronado Dr La Salle Ave Mendoza Ave AC E 20 838 50 44,257 11/17/21 86 New Construction - Initial 1/1/00 Corsica 8600 Corsica Pl Gibralter Ave Royal Palm Dr AC E 23 1,461 37 54,057 1/5/22 51 Surface Treatment - Slurry Seal 1/1/10 Cortez 10290 Cortez St Junipero Dr Drake Ave AAC E 20 1,085 37 40,145 11/22/21 81 Overlay - AC Structural 4/1/07 Corvo 7840 Corvo Pl Pitcairn Dr Minorca Pl AC E 21 630 37 23,310 11/11/21 77 Surface Treatment - Slurry Seal 1/1/10 Costa Mesa 5000 Costa Mesa St Fullerton Ave Santa Ana Ave AAC E 3 1,960 37 72,520 9/17/21 94 Overlay - AC Structural 4/1/12 Costa Mesa 5010 Costa Mesa St Santa Ana Ave Irvine Ave AAC E 4 2,639 37 97,643 10/8/21 84 Overlay - AC Structural 4/1/12 Cottage 5580 Cottage Pl Cul-de-sac Westminster Ave AC E 3 168 37 8,390 10/7/21 63 Surface Treatment - Slurry Seal 3/20/16 Country Cl 8140 Country Club Dr Pemba Dr Mesa Verde Dr AC E 21 630 37 23,310 11/11/21 100 Surface Treatment - Slurry Seal 6/1/21 Country Cl 8150 Country Club Dr Mesa Verde Dr Gisler Ave AC E 23 2,700 37 99,900 11/11/21 100 Surface Treatment - Slurry Seal 6/1/21 Cove 4720 Cove St Arnold Ave Meyer Pl AAC E 2 567 37 21,913 12/28/21 95 Overlay - AC Structural 6/16/15 Crestmont 3190 Crestmont Pl Shalimar Dr 18th St AAC E 7 520 37 19,240 11/15/21 99 Surface Treatment - Slurry Seal 6/1/21 Crocus 11460 Crocus Cir Larkspur St Cul-de-sac AC E 27 452 37 18,898 10/27/21 87 Surface Treatment - Slurry Seal 1/1/18 Croftdon 10430 Croftdon St Post Rd Baker St AC E 20 650 37 24,050 10/22/21 91 New Construction - Initial 1/1/00 Cynthia 6690 Cynthia Ct Cul-de-sac Santa Ana Ave AAC E 25 300 37 13,274 10/8/21 92 2 in Cold Mill & Overlay 1/8/19 Dahlia 11400 Dahlia Ave Fuschia St Cul-de-sac AC E 27 1,200 37 46,574 10/29/21 86 Surface Treatment - Slurry Seal 1/1/18 Dakota 9090 Dakota Ave Gisler Ave California St AAC E 17 900 37 33,300 3/3/22 100 Overlay - AC Structural 3/3/22 Dakota 9094 Dakota Ave California St Iowa St AAC E 17 730 37 27,010 3/3/22 100 Overlay - AC Structural 3/3/22 Dale 9340 Dale Way Harbor Blvd College Ave AC E 15 850 37 31,450 10/29/21 94 2 in Cold Mill & Overlay 1/1/18 Damascus 11230 Damascus Cir Smalley Rd Cul-de-sac AAC E 27 560 37 22,894 10/27/21 89 2 in Cold Mill & Overlay 1/1/18 Danielle 20020 Danielle Dr Wimbeldon Way Deedee Dr AC E 389 25 9,725 10/27/21 87 Surface Treatment - Slurry Seal 1/1/18 Darrel 5870 Darrel St Republic Ave Federal Ave AC E 18 1,890 37 69,930 11/9/21 64 Surface Treatment - Slurry Seal 10/6/15 Darrel 6020 Darrel St Pomona Ave Meyer Pl AC E 19 1,050 37 38,850 11/23/21 67 Surface Treatment - Slurry Seal 10/6/15 Dartmouth 6420 Dartmouth Pl Columbia Dr Cul-de-sac AC E 24 216 37 10,166 11/10/21 75 Surface Treatment - Slurry Seal 9/1/09 Date 8730 Date Pl Cinnamon Ave Harbor Blvd AAC E 23 240 60 14,400 11/17/21 88 Surface Treatment - Slurry Seal 1/1/10 Davis 8735 Davis Pl Monte Vista Ave Cul-de-sac AC E 26 195 33 8,609 10/7/21 79 Surface Treatment - Slurry Seal 1/8/19 De Soto 9950 De Soto Ave Presidio Dr Coronado Dr AAC E 20 929 37 34,373 11/22/21 86 Overlay - AC Structural 12/1/15 Debra 11100 Debra Dr Deedee Dr Salinas Ave AC E 14 470 37 17,945 10/27/21 82 Surface Treatment - Slurry Seal 1/1/18 Deedee 11110 Deedee Dr Debra Dr San Jose Ave AC E 14 749 37 27,713 10/27/21 67 Surface Treatment - Slurry Seal 1/1/18 Delaware 8930 Delaware Pl New Jersey St Cul-de-sac AC E 17 205 37 9,759 10/22/21 77 Surface Treatment - Slurry Seal 10/3/23 Denver 10620 Denver Dr Babb St Cul-de-sac AAC E 16 747 37 29,813 10/19/21 76 Overlay - AC Structural 10/1/15 Deodar 8590 Deodar Ave Baker St Nutmeg Pl AC E 23 667 37 24,679 11/16/21 90 Surface Treatment - Slurry Seal 1/1/10 Doctors 4960 Doctors Cir Cul-de-sac Victoria St AAC E 5 400 37 16,974 11/12/21 95 Surface Treatment - Slurry Seal 12/1/19 Dogwood 4250 Dogwood St Republic Ave Monrovia Ave AAC E 1 843 33 29,038 12/29/21 89 Overlay - AC Structural 3/28/11 Donegal 9570 Donegal Pl Loren Ln Cul-de-sac AC E 15 270 37 12,164 11/15/21 89 Surface Treatment - Slurry Seal 3/20/16 DonnyBrook 9430 Donnybrook Ln Baker St Watson Ave AC E 15 657 37 24,309 11/15/21 68 Surface Treatment - Slurry Seal 3/20/16 DonnyBrook 9530 Donnybrook Ln Conway Ave Belfast Ave AC E 15 684 37 25,308 11/15/21 88 Surface Treatment - Slurry Seal 4/1/16 Dorset 10470 Dorset Ln Cul-de-sac Cleveland Ave AAC E 16 832 37 30,509 11/16/21 79 Overlay - AC Structural 10/1/15
249
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Dorset 9560 Dorset Ln Loren Ln Fairview Rd AC E 15 330 37 12,210 11/15/21 81 Surface Treatment - Slurry Seal 4/1/16 Drake 10320 Drake Ave Presidio Dr St Clair St AC E 20 1,860 37 68,820 11/22/21 83 New Construction - Initial 1/1/00 Dublin 9490 Dublin St Shamrock Ln N'ly end AC E 15 470 37 17,390 11/15/21 63 Surface Treatment - Slurry Seal 3/20/16 Duke 6490 Duke Pl Nassau Rd Cul-de-sac AC E 24 321 37 14,051 11/10/21 86 Surface Treatment - Slurry Seal 9/1/09 Duke 7190 Duke Pl Cul-de-sac Bucknell Rd AAC E 10 360 37 15,494 11/10/21 84 Overlay - AC Structural 9/1/07 El Camino 10020 El Camino Dr Fairview Rd Monterey Ave AC E 20 540 57 30,780 10/19/21 90 Complete Reconstruction - AC 1/1/06 El Camino 10030 El Camino Dr Monterey Ave Mendoza Dr AC E 20 1,520 36 57,038 10/19/21 97 Surface Treatment - Slurry Seal 6/1/21 El Camino 10040 El Camino Dr Mendoza Dr La Salle Ave AC E 20 980 48 51,772 10/19/21 84 Surface Treatment - Slurry Seal 2/1/06 El Rio 10050 El Rio Cir El Camino Dr Cul-de-sac AC E 20 551 37 22,561 10/19/21 60 Surface Treatment - Slurry Seal 2/1/06 Elba 7870 Elba Cir Cul-de-sac Stromboli Rd AAC E 21 350 37 15,124 11/11/21 68 Surface Treatment - Slurry Seal 1/1/10 Elden 5480 Elden Ave 21st St 22nd St AC E 3 1,150 37 42,550 10/8/21 77 Surface Treatment - Slurry Seal 3/20/16 Elden 5490 Elden Ave 22nd St Santa Isabel Ave AAC E 25 2,630 37 97,310 12/28/21 92 Overlay - AC Structural 8/20/16 Elden 5500 Elden Ave Santa Isabel Ave Monte Vista Ave AC E 26 1,300 37 48,100 9/30/21 83 Surface Treatment - Slurry Seal 1/1/17 Elden 5510 Elden Ave Monte Vista Ave Mesa Dr AC E 26 2,650 37 98,050 9/30/21 86 Surface Treatment - Slurry Seal 1/1/17 Ellesmere 7970 Ellesmere Ave Pitcairn Dr Samar Dr AC E 21 845 37 31,265 1/4/22 83 Surface Treatment - Slurry Seal 1/1/10 Ellesmere 7972 Ellesmere Ave Samar Dr Ceylon Dr AC E 21 960 37 35,520 1/4/22 40 Surface Treatment - Slurry Seal 1/1/10 Elm 8330 Elm Ave Andros St Royal Palm Dr AC E 21 897 37 33,189 11/16/21 67 Surface Treatment - Slurry Seal 1/1/10 Elm 8340 Elm Ave Royal Palm Dr Harbor Blvd AC E 21 800 37 29,600 11/16/21 71 Surface Treatment - Slurry Seal 1/1/10 Elmhurst 7110 Elmhurst Ln Cul-de-sac Carnegie Ave AC E 10 351 33 13,723 11/10/21 85 Surface Treatment - Slurry Seal 9/1/09 Enterprise 11600 Enterprise St Baker St Paularino Ave AC E 12 800 37 29,600 9/16/21 83 Surface Treatment - Slurry Seal 1/1/00 Esther 5150 Esther St Walnut Pl Tustin Ave AAC E 4 650 35 22,425 11/10/21 74 Overlay - AC Structural 4/1/12 Esther 5180 Esther St Westminster Ave Santa Ana Ave AAC E 3 640 37 23,680 11/10/21 85 Overlay - AC Structural 4/1/12 Esther 5210 Esther St Santa Ana Ave Raymond Ave AAC E 4 650 37 24,050 11/10/21 83 Overlay - AC Structural 4/15/12 Esther 5220 Esther St Raymond Ave Tustin Ave AAC E 4 660 37 24,420 11/10/21 87 Overlay - AC Structural 4/15/12 Esther 5280 Esther St W'ly end Irvine Ave AAC E 4 617 35 21,287 11/9/21 80 Overlay - AC Structural 4/15/12 Europa 7650 Eurpoa Dr Calvert Ave Kornat Dr AC E 21 1,600 37 59,700 10/26/21 55 Surface Treatment - Slurry Seal 1/1/10 Evergreen 4270 Evergreen Pl Cul-de-sac Monrovia Ave AAC E 1 567 33 20,885 10/1/21 90 Overlay - AC Structural 3/20/16 Fairway Dr 6900 Fairway Dr Brentwood St Monte Vista Ave AC E 26 525 33 17,325 10/5/21 94 Surface Treatment - Slurry Seal 1/1/17 Fairway Dr 6940 Fairway Dr Monte Vista Ave Del Mar Ave AAC E 26 1,300 35 44,850 10/5/21 97 2 in Cold Mill & Overlay 1/1/17 Fairway Dr 6950 Fairway Dr Del Mar Ave Fairway Pl AAC E 26 550 35 18,975 10/5/21 92 2 in Cold Mill & Overlay 1/1/17 Fairway Pl 7040 Fairway Pl Fairway Dr Orange Ave AC E 26 542 35 18,699 10/5/21 90 Surface Treatment - Slurry Seal 1/1/17 Farad 2940 Farad St Cul-de-sac Pomona Ave AC E 7 560 37 22,894 11/1/21 100 Surface Treatment - Slurry Seal 6/1/21 Farallon 7950 Farallon Dr Club House Rd Samar Dr AC E 21 265 37 9,805 11/11/21 76 Surface Treatment - Slurry Seal 1/1/10 Fayette 11630 Fayette Cir Ludington St Cul-de-sac AAC E 12 221 37 10,351 11/23/21 83 Overlay - AC Structural 3/20/16 Federal 4300 Federal Ave 19th St Oak St AC E 1 2,560 37 94,720 10/15/21 88 New Construction - Initial 1/1/00 Federal 4305 Federal Ave Oak St Victoria St Frontage Road AC E 1 690 37 25,530 11/16/21 87 Surface Treatment - Slurry Seal 3/20/16 Federal 5890 Federal Ave Wilson St Joann St AC E 18 500 37 18,500 11/9/21 84 Complete Reconstruction - AC 2/1/04 Fernheath 9440 Fernheath Ln Baker St Watson Ave AC E 15 488 37 18,056 11/15/21 75 Surface Treatment - Slurry Seal 4/1/16 Fernheath 9540 Fernheath Ln Conway Ave Belfast Ave AC E 15 800 37 29,600 11/15/21 93 Surface Treatment - Slurry Seal 3/20/16 Fillmore 10550 Fillmore Way Cul-de-sac Cul-de-sac AAC E 16 699 37 30,211 11/17/21 87 Overlay - AC Structural 10/1/15 Fischer 11870 Fischer Ave Pullman St Red Hill Ave AC E 29 1,037 40 41,480 11/8/21 76 6 in Cold Mill & Overlay in Secure area 8/1/13 Fischer 11871 Fischer Ave Red Hill Ave Airway Ave AC E 29 1,037 40 41,480 11/8/21 81 6 in Cold Mill & Overlay in Secure area 8/1/13 Flamingo 7360 Flamingo Dr Sandpiper Dr Pelican Pl AC E 11 1,700 37 62,900 10/4/21 92 Complete Reconstruction - AC 1/1/04 Flamingo 7364 Flamingo Dr Albatros Dr Pelican Pl AC E 11 704 37 26,048 10/4/21 94 New Construction - Initial 1/1/80 Florida 9200 Florida Cir Cul-de-sac Alaska Ave AC E 17 275 37 12,349 10/21/21 76 Surface Treatment - Slurry Seal 10/3/23 Flower 4050 Flower St Newport Blvd Santa Ana Ave AAC E 9 2,659 37 98,383 11/15/21 90 Overlay - AC Structural 4/15/12 Flower 4060 Flower St Santa Ana Ave Irvine Ave AAC E 9 2,620 37 96,940 11/15/21 84 Overlay - AC Structural 4/15/12 Ford 4900 Ford Rd Harbor Blvd Alley #40/#41 AC E 5 866 33 28,578 11/15/21 50 New Construction - Initial 1/1/00 Fordham 6210 Fordham Dr Wilson St Wake Forest Rd AC E 24 750 37 28,305 11/23/21 75 Surface Treatment - Slurry Seal 2/1/06 Fordham 6220 Fordham Dr Wake Forest Rd Fair Dr AC E 24 1,830 37 67,710 11/23/21 80 Surface Treatment - Slurry Seal 2/1/06 Fordham 6230 Fordham Dr Fair Dr Princeton Dr AC E 10 1,265 37 46,805 11/23/21 70 Surface Treatment - Slurry Seal 2/1/06 Francis 10240 Francis Ln Magellan St Loreto Ave AC E 20 864 37 32,968 11/22/21 84 New Construction - Initial 1/1/00 Freemont 9970 Fremont Ln Presidio Dr Coronado Dr AC E 20 640 37 23,680 11/17/21 90 Surface Treatment - Slurry Seal 2/1/06 Fullerton 3510 Fullerton Ave 17th St Cabrillo St AAC E 8 478 37 17,686 11/29/21 84 Overlay - AC Structural 4/15/12 Fullerton 3930 Fullerton Ave 18th St 19th St AAC E 8 1,300 33 42,900 11/19/21 83 Overlay - AC Structural 4/15/12 Fullerton 3940 Fullerton Ave 20th St Bay St AAC E 3 620 36 22,320 9/17/21 52 Overlay - AC Structural 4/15/12 Fullerton 3945 Fullerton Ave Bay St Bouy St AAC E 3 220 36 5,920 9/17/21 93 Overlay - AC Structural 4/15/12
250
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Fullerton 3950 Fullerton Ave 19th St 20th St AAC E 3 1,320 33 43,560 11/19/21 83 Overlay - AC Structural 4/15/12 Fuschia 11300 Fuschia St Dahlia Ave Carnation Ave AC E 27 870 37 32,190 10/29/21 89 Surface Treatment - Slurry Seal 1/1/18 Fuschia 11380 Fuschia St Carnation Ave Begonia Ave AC E 27 230 37 8,510 10/27/21 86 Surface Treatment - Slurry Seal 1/1/18 Fuschia 11390 Fuschia St Begonia Ave Sunflower Ave AAC E 27 950 37 35,150 10/29/21 93 Overlay - AC Structural 1/8/19 Galway 9404 Galway Ln College Ave Killybrooke Ln AC E 15 370 37 13,690 11/15/21 64 Surface Treatment - Slurry Seal 4/1/16 Gannet 7430 Gannet Dr Swan Dr Pelican Pl AC E 11 890 37 32,930 10/6/21 86 Complete Reconstruction - AC 1/1/04 Garden 5440 Garden Ln Woodland Pl 21st St AAC E 4 1,040 37 38,480 10/8/21 90 Overlay - AC Structural 4/1/12 Garfield 10570 Garfield Ave Cul-de-sac Paularino Ave AAC E 16 763 37 30,405 11/17/21 85 Overlay - AC Structural 10/1/15 Garlinford 9680 Garlinford St College Ave Killybrooke Ln AAC E 15 846 37 31,302 11/15/21 89 Overlay - AC Structural 3/20/16 Georgeanne 6715 Georgeanne Pl Elden Ave Cul-de-sac AAC E 25 271 37 12,201 12/6/21 97 2 in Cold Mill & Overlay 1/1/17 Georgia 9000 Georgia Pl Cul-de-sac Iowa St AC E 17 152 37 7,798 10/22/21 81 Surface Treatment - Slurry Seal 10/3/23 Geranium 11290 Geranium Ln Poppy Cir Begonia Ave AC E 27 390 37 14,430 10/29/21 83 Surface Treatment - Slurry Seal 1/1/18 Gibraltar 8290 Gibraltar Ave Labrador Dr Gisler Ave AC E 23 2,089 37 77,293 11/17/21 85 Surface Treatment - Slurry Seal 1/1/10 Ginger 8680 Ginger Ave Wintergreen Pl Caraway Dr AAC E 23 400 37 14,800 11/15/21 94 Surface Treatment - Slurry Seal 1/1/10 Gisler 9690 Gisler Ave Harbor Blvd College Ave AAC E 15 812 36 29,132 11/8/21 79 Overlay - AC Structural 3/20/16 Gisler 9700 Gisler Ave College Ave 1000' E'ly AAC E 15 1,005 22 24,236 11/5/21 74 Overlay - AC Structural 3/20/16 Gisler 9704 Gisler Ave 1000' e/o College Ave E'ly end AAC E 15 735 22 15,135 11/5/21 55 Overlay - AC Structural 3/1/09 Glen 4520 Glen Cir Cul-de-sac Canyon Dr AC E 1 270 37 12,164 12/29/21 25 Surface Treatment - Slurry Seal 9/1/09 Gleneagles 4430 Gleneagles Terr Cul-de-sac Valley Rd AC E 1 1,060 37 41,394 11/16/21 78 New Construction - Initial 1/1/00 Goldeneye 7390 Goldeneye Pl Sandpiper Dr Mallard Dr AAC E 11 780 37 28,860 10/6/21 85 Overlay - AC Structural 10/1/15 Goldenrod 11350 Goldenrod Dr Plumeria Pl Begonia Ave AC E 27 840 37 31,080 10/29/21 90 Surface Treatment - Slurry Seal 1/1/18 GolfCourse 7530 Golf Course Dr Tanager Dr Mesa Verde Dr E AC E 11 1,200 16 18,600 10/6/21 80 New Construction - Initial 1/1/00 GolfCourse 7531 Golf Course Dr Mesa Verde Dr E Tanager Dr AAC E 11 1,200 16 18,600 10/6/21 78 Overlay - AC Structural 10/1/15 Governor 5670 Governor St State Ave Placentia Ave AC E 18 2,460 33 81,180 11/9/21 63 Surface Treatment - Slurry Seal 10/1/00 Governor 5940 Governor St Pomona Ave Puente Ave AAC E 19 550 37 20,350 11/9/21 90 Overlay - AC Structural 7/1/03 Grace 10390 Grace Ln Cul-de-sac Baker St AAC E 20 660 37 26,594 11/17/21 87 Overlay - AC Structural 12/1/08 GrandHaven 11640 Grand Haven Cir Ludington St Cul-de-sac AAC E 12 222 37 10,388 11/23/21 91 Overlay - AC Structural 3/20/16 Grant 10590 Grant Ave Baker St Cul-de-sac AAC E 16 749 37 29,887 11/17/21 81 Overlay - AC Structural 10/1/15 Green 9480 Green St Watson Ave N' End AC E 15 120 37 4,440 11/15/21 47 Surface Treatment - Slurry Seal 3/20/16 Greenbriar 7240 Greenbriar Ln Princeton Dr Oxford Ln AC E 10 850 37 31,450 11/10/21 80 Surface Treatment - Slurry Seal 2/1/06 Greenbrook 11430 Greenbrook Dr South Coast Dr Dahlia Ave AAC E 27 376 37 13,912 10/27/21 97 2 in Cold Mill & Overlay 1/1/18 Grove 4340 Grove Pl Cul-de-sac Republic Ave AAC E 1 1,007 33 35,405 11/16/21 89 Overlay - AC Structural 3/20/16 Haiti 8810 Haiti Cir Bahama Pl Cul-de-sac AC E 22 251 37 11,461 11/16/21 67 Surface Treatment - Slurry Seal 1/1/10 Hamilton 4620 Hamilton St Placentia Ave Pomona Ave AC E 2 1,320 37 48,840 11/12/21 95 Surface Treatment - Slurry Seal 12/1/19 Hamilton 4623 Hamilton St Pomona Ave Charle St AC E 2 2,200 37 81,400 11/12/21 97 Overlay-Rubber Hot Mix 1/1/21 Hamilton 4629 Hamilton St Charle St Harbor Blvd AAC E 2 460 37 17,020 11/12/21 97 Overlay-Rubber Hot Mix 1/1/21 Hamilton 4630 Hamilton St Harbor Blvd Thurin St AC E 5 1,540 37 56,980 11/12/21 95 Surface Treatment - Slurry Seal 12/1/19 Hamilton 4634 Hamilton St Thurin St Cul-de-sac AAC E 5 1,540 37 59,154 11/12/21 95 Surface Treatment - Slurry Seal 12/1/19 Hanover 6240 Hanover Dr Princeton Dr Cul-de-sac AC E 10 2,058 37 78,320 11/10/21 77 6 in Cold Mill & Overlay in Secure area 2/1/12 HarborGtwN 9780 Harbor Gateway North Scenic Ave Mac Arthur Blvd AC E 30 900 37 33,300 10/21/21 75 New Construction - Initial 1/1/00 HarborGtwS 9800 Harbor Gateway South Sunflower Ave Scenic Dr AC E 30 1,328 37 49,136 10/21/21 74 New Construction - Initial 1/1/00 Harding 10600 Harding Way Cul-de-sac Cul-de-sac AAC E 16 678 37 29,434 11/17/21 55 Overlay - AC Structural 10/1/15 Harla 7640 Harla Ave Cul-de-sac Mesa Verde Dr E AAC E 11 600 37 24,374 10/18/21 74 Overlay - AC Structural 10/1/15 Hartford 10900 Hartford Way Jefferson Ave Cul-de-sac AAC E 16 292 37 13,987 10/19/21 78 Overlay - AC Structural 10/1/15 Hawaii 9170 Hawaii Cir California St Cul-de-sac AC E 17 327 37 14,273 10/21/21 77 Surface Treatment - Slurry Seal 10/3/23 Hayes 10810 Hayes Ave Paularino Ave Springfield St AAC E 16 520 37 19,240 10/19/21 80 Overlay - AC Structural 10/1/15 HelenaCir 10640 Helena Cir Cul-de-sac Cul-de-sac AAC E 16 560 37 24,793 10/19/21 83 Overlay - AC Structural 10/1/15 HelenaPl 10630 Helena Pl Helena Cir Paularino Ave AAC E 16 264 37 9,768 10/19/21 86 Overlay - AC Structural 10/1/15 Hickory 8360 Hickory Pl Ponderosa Stq Cul-de-sac AC E 21 262 37 11,868 11/16/21 92 Surface Treatment - Slurry Seal 1/1/10 Hill 6850 Hill Pl 24th Pl Cul-de-sac AAC E 26 459 34 17,780 10/5/21 97 2 in Cold Mill & Overlay 1/8/19 Howard 9770 Howard Way Cul-de-sac Scenic Dr AC E 30 560 37 22,894 10/21/21 92 New Construction - Initial 1/1/00 Hudson 11550 Hudson Ave Canadian Dr Yellowstone Dr AAC E 31 826 37 30,562 10/29/21 68 Overlay - AC Structural 10/1/15 Hummingbrd 7580 Hummingbird Dr Bunting Cir Tanager Dr AAC E 11 1,840 37 68,080 10/6/21 74 Overlay - AC Structural 10/1/15 Idaho Ln 9280 Idaho Ln Cul-de-sac Missouri St AC E 17 365 37 15,679 10/21/21 79 Surface Treatment - Slurry Seal 10/3/23 Idaho Pl 9080 Idaho Pl Cul-de-sac California St AC E 17 602 37 24,448 10/21/21 76 Surface Treatment - Slurry Seal 10/3/23 Illinois 8960 Illinois St Indiana Ave Washington Ave AAC E 17 365 37 14,499 3/3/22 100 Overlay - AC Structural 3/3/22 Indiana 8970 Indiana Ave Illinois St Iowa St AAC E 17 734 37 28,178 3/3/22 100 Overlay - AC Structural 3/3/22
251
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Industrial 2010 Industrial Way Superior Ave Newport Blvd S/B AAC E 8 800 36 28,800 12/6/21 74 Overlay - AC Structural 10/1/15 Inroz 7730 Inroz Dr Baltra Pl Lemnos Dr AC E 22 260 37 9,620 10/15/21 69 Surface Treatment - Slurry Seal 1/1/10 Iowa 8860 Iowa St Gisler Ave (West end) California St AAC E 17 2,180 37 80,660 3/3/22 100 Overlay - AC Structural 3/3/22 Iowa 8870 Iowa St California St Arizona Ln AAC E 17 340 37 12,580 3/3/22 100 Overlay - AC Structural 3/3/22 Iowa 8880 Iowa St Arizona Ln Colorado Ln AAC E 17 1,400 37 51,800 3/3/22 100 Overlay - AC Structural 3/3/22 Iowa 8890 Iowa St Colorado Ln Gisler Ave (East end) AAC E 17 2,730 37 101,010 3/3/22 100 Overlay - AC Structural 3/3/22 Iris 5610 Iris Pl Lilac Ln Cul-de-sac AAC E 3 244 37 11,202 12/28/21 92 Overlay - AC Structural 3/20/16 Jacaranda 8430 Jacaranda Ave Cul-de-sac Myrtlewood St AC E 21 1,387 37 54,670 10/15/21 86 Surface Treatment - Slurry Seal 1/1/10 Jamaica 8170 Jamaica Rd Country Club Dr Cul-de-sac AC E 22 600 37 22,200 10/26/21 64 Surface Treatment - Slurry Seal 1/1/10 Jamaica 8175 Jamaica Rd Madeira Ave Country Club Dr AC E 23 280 37 10,360 11/16/21 85 Surface Treatment - Slurry Seal 1/1/10 James 3150 James St Wallace Ave Pomona Ave AC E 7 650 37 24,050 11/15/21 99 Surface Treatment - Slurry Seal 6/1/21 Jasmine 11450 Jasmine Cir Larkspur St Cul-de-sac AC E 27 440 37 18,454 10/27/21 87 Surface Treatment - Slurry Seal 1/1/18 Java 8080 Java Rd Tahiti Dr Mesa Verde Dr AC E 21 1,053 37 38,920 11/11/21 82 Surface Treatment - Slurry Seal 1/1/10 Java 8090 Java Rd Mesa Verde Dr Tahiti Dr AAC E 22 1,280 37 47,360 11/11/21 93 Surface Treatment - Slurry Seal 1/1/10 Jeanette 6660 Jeanette Pl Cul-de-sac Cecil Pl AAC E 25 118 34 6,570 10/7/21 97 2 in Cold Mill & Overlay 1/8/19 Jefferson 10890 Jefferson Ave Cheyenne St Concord st AAC E 16 698 37 26,355 10/19/21 82 Overlay - AC Structural 10/1/15 Jeffrey 11470 Jeffrey Dr Baker St Paularino Ave AC E 13 960 37 35,520 10/29/21 74 Surface Treatment - Slurry Seal 9/1/09 Jennifer 11480 Jennifer Ln Jeffrey Dr Cul-de-sac AC E 13 290 37 12,904 10/29/21 85 Surface Treatment - Slurry Seal 9/1/09 Joann 5710 Joann St Republic Ave Placentia Ave AC E 18 2,140 37 79,180 11/9/21 65 Surface Treatment - Slurry Seal 10/6/15 Joann 5720 Joann St Placentia Ave Miner St AC E 19 3,160 37 116,920 11/9/21 88 Complete Reconstruction - AC 3/1/03 Joann 6300 Joann St Fordham Dr Columbia Dr AC E 24 1,452 37 53,942 11/23/21 62 Surface Treatment - Slurry Seal 2/1/06 Johnson 10800 Johnson Ave Paularino Ave Cheyenne St AAC E 16 800 37 29,600 10/19/21 81 Overlay - AC Structural 10/1/15 Junipero 9880 Junipero Dr Arlington Dr Presidio Dr AC E 20 1,119 60 67,140 11/22/21 70 New Construction - Initial 1/1/00 Junipero 9890 Junipero Dr Presidio Dr Sutter Way AAC E 20 1,730 37 27,010 10/19/21 72 Overlay - AC Structural 9/15/15 Junipero 9894 Junipero Dr Sutter Way La Salle Ave AC E 20 1,000 37 37,000 10/19/21 77 New Construction - Initial 1/1/00 Kalmus 11850 Kalmus Dr Airway Ave Red Hill Ave AC E 29 645 40 27,150 11/8/21 80 6 in Cold Mill & Overlay in Secure area 8/1/13 Kalmus 11851 Kalmus Dr Red Hill Ave Pullman St AC E 29 1,615 60 101,768 11/8/21 68 6 in Cold Mill & Overlay in Secure area 8/1/13 Kauai 7930 Kauai Dr Lanai Dr Club House Rd AC E 22 440 37 16,280 11/11/21 100 Surface Treatment - Slurry Seal 6/1/21 Kentucky 8990 Kentucky Pl Indiana Ave Cul-de-sac AAC E 17 163 37 8,205 3/3/22 100 Overlay - AC Structural 3/3/22 Kenwood 3180 Kenwood Pl Shalimar Dr 18th St AC E 7 500 37 18,500 11/15/21 98 Surface Treatment - Slurry Seal 3/15/22 Kerry 9640 Kerry Ln Killarney Ln Londonderry St AC E 15 730 37 27,210 11/15/21 60 Surface Treatment - Slurry Seal 3/20/16 Killarney 9630 Killarney Ln Londonderry St Kerry Ln AC E 15 594 37 21,978 11/15/21 72 Surface Treatment - Slurry Seal 3/20/16 Killdeer 7450 Killdeer Cir Gannet Dr Cul-de-sac AC E 11 460 37 19,194 10/6/21 90 Complete Reconstruction - AC 1/1/04 Killybrk 9400 Killybrooke Ln Baker St Garlinford St AAC E 15 2,470 37 90,890 11/15/21 100 Overlay - AC Structural 1/1/21 Kinglet 7540 Kinglet Ct Tanager Dr (West) Tanager Dr (East) AAC E 11 1,515 37 56,273 10/18/21 84 Overlay - AC Structural 10/1/15 Klondike 10930 Klondike Ave Yukon Ave Peace Pl AC E 13 655 37 24,235 11/1/21 100 Surface Treatment - Slurry Seal 3/15/22 Knowell 4770 Knowell Pl Meyer Pl Maple Ave AC E 2 870 37 32,190 11/12/21 89 Surface Treatment - Slurry Seal 12/1/19 KnoxPl 2150 Knox Pl Orange Ave Santa Ana Ave AAC E 8 1,320 37 48,840 12/15/21 78 Overlay - AC Structural 7/1/12 KnoxSt 2120 Knox St Orange Ave Santa Ana Ave AAC E 8 1,320 37 48,840 11/19/21 82 Overlay - AC Structural 7/1/12 Kornat 7660 Kornat Dr Europa Dr Boa Vista Dr AC E 22 1,050 37 39,350 10/25/21 86 Surface Treatment - Slurry Seal 1/1/10 La Perle 2180 La Perle Ln/Pl Tustin Ave (Southern) Tustin Ave (Northern) AAC E 9 1,245 33 41,085 11/19/21 85 Overlay - AC Structural 7/1/12 La Salle 10190 La Salle Ave Coronado Dr Mission Dr AAC E 20 1,235 36 60,650 11/22/21 87 Overlay - AC Structural 9/15/15 Labrador 8220 Labrador Dr Baker St Bermuda Dr AC E 23 1,950 37 72,150 11/16/21 76 Surface Treatment - Slurry Seal 1/1/10 Lanai 7920 Lanai Dr W'ly end Club House Dr AC E 22 560 37 20,720 11/11/21 68 Surface Treatment - Slurry Seal 1/1/10 Lansing 10830 Lansing Ln Hayes Ave Cheyenne St AAC E 16 819 37 30,303 10/19/21 80 Overlay - AC Structural 10/1/15 Lantana 11370 Lantana Ln Carnation Ave Begonia Ave AC E 27 255 37 9,435 10/29/21 95 Surface Treatment - Slurry Seal 1/1/18 Larkspur 11440 Larkspur St Dahlia Ave Carnation Ave AC E 27 747 33 24,651 10/27/21 87 Surface Treatment - Slurry Seal 1/1/18 Laurie 5350 Laurie Ln Cul-de-sac Bay St AAC E 3 300 37 13,274 12/28/21 84 Overlay - AC Structural 4/15/12 Lavender 11270 Lavender Ln Begonia Ave Poppy Cir AC E 27 420 37 15,540 10/29/21 87 Surface Treatment - Slurry Seal 1/1/18 Lear 11840 Lear Ave Red Hill Ave Airway Ave AC E 29 550 40 22,000 9/16/21 78 6 in Cold Mill & Overlay in Secure area 8/1/13 Lehigh 7150 Lehigh Pl Cul-de-sac Bucknell Rd AAC E 10 360 37 15,494 11/10/21 69 Overlay - AC Structural 10/1/05 Lemnos 7740 Lemnos Dr Europa Dr Chios Rd AC E 22 920 37 34,540 10/15/21 77 Surface Treatment - Slurry Seal 1/1/10 Lemon 8350 Lemon St Elm Ave Ponderosa St AAC E 21 360 33 11,880 11/16/21 85 Surface Treatment - Slurry Seal 1/1/10 LenwoodCir 2740 Lenwood Cir Aliso Ave Cul-de-sac AAC E 9 226 33 9,632 10/15/21 82 Overlay - AC Structural 4/15/12 LenwoodDr 2730 Lenwood Dr Tustin Ave Aliso Dr AAC E 9 658 37 24,346 10/15/21 76 Overlay - AC Structural 4/15/12 Liard 10950 Liard Pl Yukon Ave Cul-de-sac AC E 13 654 37 26,372 11/1/21 99 Surface Treatment - Slurry Seal 6/1/21 Lilac 5590 Lilac Ln Aster Pl Santa Ana Ave AAC E 3 530 37 19,610 12/28/21 93 Overlay - AC Structural 3/20/16
252
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Lilian 7020 Lilian Pl Orange Ave Fairway Dr AAC E 26 530 37 19,610 10/5/21 96 2 in Cold Mill & Overlay 1/8/19 Limerick 9600 Limerick Ln Stonefield St Londonderry St AC E 15 580 37 21,460 11/15/21 91 Surface Treatment - Slurry Seal 3/20/16 Lincoln 10880 Lincoln Way Cheyenne Ave Cul-de-sac AAC E 16 470 37 19,648 10/19/21 75 Overlay - AC Structural 10/1/15 Linden 4370 Linden Pl Cul-de-sac Republic Ave AC E 1 1,284 33 44,546 11/16/21 91 Surface Treatment - Slurry Seal 3/20/16 Lisa 7070 Lisa Ln Cul-de-sac Elden Ave AAC E 26 291 37 12,941 9/30/21 95 Surface Treatment - Slurry Seal 1/1/17 LittletonC 6530 Littleton Cir Villanova Rd Cul-de-sac AC E 24 430 37 18,084 11/10/21 86 Surface Treatment - Slurry Seal 9/1/09 LittletonP 6520 Littleton Pl Cul-de-sac Villanova Rd AC E 24 343 37 14,865 1/5/22 32 Surface Treatment - Slurry Seal 9/1/09 LittletonP 7200 Littleton Pl Cul-de-sac Bucknell Rd AC E 10 282 37 12,608 11/10/21 89 Surface Treatment - Slurry Seal 2/1/06 Logan 9360 Logan Ave College Ave Mc Clintock Way AAC E 15 2,120 37 78,440 7/19/22 100 Overlay - AC Fabric 7/19/22 Loma 10250 Loma Cir Francis Ln Cul-de-sac AAC E 20 175 37 8,649 11/22/21 84 Overlay - AC Structural 2/1/06 Londondrry 9620 Londonderry St Sharon Ln Bray Ln AC E 15 1,330 37 49,710 11/15/21 55 Surface Treatment - Slurry Seal 3/20/16 Loren 9460 Loren Ln Baker St Belfast Ave AC E 15 1,552 37 57,424 11/15/21 76 Surface Treatment - Slurry Seal 3/20/16 Lorenzo 9910 Lorenzo Dr Presido Dr El Camino Dr AAC E 20 1,504 37 56,895 11/17/21 90 Overlay - AC Structural 6/1/07 Loreto 10310 Loreto Ave Cortez St Sonora Rd AC E 20 1,162 37 42,994 11/22/21 88 New Construction - Initial 1/1/00 Loyola 6500 Loyola Rd Fairview Rd Fair Dr AC E 24 1,253 37 46,213 11/10/21 71 Surface Treatment - Slurry Seal 9/1/09 Loyola 6510 Loyola Rd Fair Dr Bucknell Rd AC E 10 449 37 16,613 11/10/21 69 New Construction - Initial 1/1/00 Ludington 11610 Ludington St Paularino Ave Traverse Dr AAC E 12 1,500 37 55,500 11/23/21 70 Overlay - AC Structural 9/1/04 Lupine 11360 Lupine Cir Cul-de-sac Goldenrod Dr AC E 27 189 36 8,978 10/29/21 88 Surface Treatment - Slurry Seal 1/1/18 Mace 8580 Mace Ave Nutmeg Pl Caraway dr AAC E 23 510 37 18,870 11/15/21 98 Surface Treatment - Slurry Seal 1/1/10 Mackenzie 10970 Mackenzie Pl Yukon Ave Cul-de-sac AC E 13 713 37 28,155 11/1/21 99 Surface Treatment - Slurry Seal 6/1/21 Madagasgar 8200 Madagasgar St Madeira Ave Barbados Pl AC E 23 481 37 17,797 11/16/21 69 Surface Treatment - Slurry Seal 1/1/10 Madeira 8190 Madeira Ave Ceylon Rd Madagasgar St AC E 23 2,136 37 81,470 11/16/21 79 Surface Treatment - Slurry Seal 1/1/10 Madison 10790 Madison Ave Paularino Ave Cheyenne St AAC E 16 800 37 29,600 10/19/21 77 Overlay - AC Structural 10/1/15 Magellan 10210 Magellan St Cul-de-sac Loreto Ave AC E 20 1,666 37 62,891 11/22/21 84 New Construction - Initial 1/1/00 Magnolia 3820 Magnolia St W'ly end Fullerton Ave AAC E 8 400 37 14,800 11/19/21 90 Overlay - AC Structural 4/15/12 Magnolia 3830 Magnolia St Fullerton Ave Santa Ana Ave AAC E 8 1,875 33 61,370 11/19/21 85 Overlay - AC Structural 4/15/12 Magnolia 3840 Magnolia St Santa Ana Ave Irvine Ave AAC E 9 2,645 37 97,865 11/19/21 79 Overlay - AC Structural 4/15/12 Mallard 7380 Mallard Dr Mandarin Dr Flamingo Dr AAC E 11 560 37 20,495 10/6/21 82 Overlay - AC Structural 5/1/05 Mandarin 7370 Mandarin Dr Sandpiper Dr Mallard Dr AAC E 11 980 37 36,260 10/6/21 84 Overlay - AC Structural 10/1/15 Manistee 11690 Manistee Dr Paularino Ave Pierpont Dr AAC E 12 1,983 37 73,371 11/23/21 93 Overlay - AC Structural 3/20/16 Maple Ave 4790 Maple Ave 19th St Hamilton St AC E 2 2,650 37 98,050 11/12/21 94 Surface Treatment - Slurry Seal 12/1/19 Maple St 6120 Maple St Victoria St Wilson St AC E 19 1,316 37 48,692 11/23/21 78 Surface Treatment - Slurry Seal 10/6/15 Maple St 6130 Maple St Wilson St Joann St AAC E 19 500 37 18,500 11/23/21 69 Surface Treatment - Slurry Seal 10/6/15 Marian 5470 Marian Way Cul-de-sac 21st St AAC E 3 325 37 14,199 10/8/21 89 Overlay - AC Structural 4/15/12 Marigold 11410 Marigold Cir Dahlia Ave Cul-de-sac AC E 27 563 37 23,005 10/29/21 90 Surface Treatment - Slurry Seal 1/1/18 Marquette 11650 Marquette Cir Ludington St Cul-de-sac AAC E 12 222 37 10,388 11/23/21 88 Overlay - AC Structural 3/20/20 Maryland 9230 Maryland Cir New Hampshire Dr Cul-de-sac AAC E 17 500 37 20,674 3/3/22 100 Overlay - AC Structural 3/3/22 Maui Cir 8100 Maui Cir Cul-de-sac Java Rd AC E 22 391 37 16,641 11/11/21 63 Surface Treatment - Slurry Seal 1/1/10 Maui Pl 8070 Maui Pl Tahiti Dr Cul-de-sac AC E 21 557 37 23,100 11/11/21 54 Surface Treatment - Slurry Seal 1/1/10 McClintock 9370 McClintock Way Logan Ave Baker St AC E 15 450 37 16,650 10/29/21 99 Surface Treatment - Slurry Seal 6/1/21 McCormack 9660 McCormack St Cork Ln Fairview Rd AC E 15 491 37 18,342 11/15/21 78 Surface Treatment - Slurry Seal 3/20/16 McCormick 11940 McCormick Ave Pullman St Airway Ave AC E 29 1,555 40 62,200 9/16/21 77 6 in Cold Mill & Overlay in Secure area 8/1/13 McKinley 10870 McKinley Way Cheyenne Ave Cul-de-sac AAC E 16 470 37 19,378 10/19/21 76 Overlay - AC Structural 10/1/15 Melody 5330 Melody Ln Cul-de-sac Fullerton Ave AAC E 3 380 37 16,234 9/17/21 88 Overlay - AC Structural 4/15/12 Mendoza 9920 Mendoza Dr Lorenzo Ave El Camino Dr AC E 20 1,451 37 58,090 11/22/21 81 New Construction - Initial 1/1/00 Mendoza 9924 Mendoza Dr Mission Dr Baker St AC E 20 1,010 37 37,370 11/17/21 77 Surface Treatment - Slurry Seal 2/1/06 Mendoza 9926 Mendoza Dr El Camino Dr Mission Dr AC E 20 548 36 21,005 12/15/21 90 New Construction - Initial 1/1/00 Merrill 5540 Merrill Pl Elden Ave Orange Ave AC E 3 650 37 24,050 10/7/21 76 Surface Treatment - Slurry Seal 3/20/16 Mesa 7080 Mesa Dr Newport Blvd Orange Ave AAC E 26 1,342 36 48,312 10/5/21 82 Surface Treatment - Slurry Seal 1/8/19 Mesa 7090 Mesa Dr Orange Ave Santa Ana Ave AC E 26 1,320 36 47,520 9/16/21 85 Surface Treatment - Slurry Seal 1/1/17 Meyer 4680 Meyer Pl 19th St Hamilton St AAC E 2 2,634 37 97,458 10/18/21 97 Overlay - AC Structural 11/15/19 Meyer 5990 Meyer Pl Cul-de-sac Wilson St AC E 19 1,290 37 49,904 11/23/21 88 Surface Treatment - Slurry Seal 10/6/15 Meyer 6000 Meyer Pl Wilson St Joann St AAC E 19 500 37 18,500 11/23/21 75 Overlay - AC Structural 5/1/03 Michigan 9110 Michigan Ave Cul-de-sac Iowa St AAC E 17 1,300 37 50,274 3/3/22 100 Overlay - AC Structural 3/3/22 Miguel 10090 Miguel Ln Cul-de-sac Mission Dr AAC E 20 200 33 8,774 11/17/21 94 Overlay - AC Structural 8/1/07 Milbro 10440 Milbro St Post Rd Baker St AC E 20 630 37 23,310 10/22/21 75 New Construction - Initial 1/1/00 Mindanao 8130 Mindanao Dr Pemba Dr Cul-de-sac AAC E 21 670 37 26,964 11/11/21 81 Surface Treatment - Slurry Seal 1/1/10
253
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Miner 6140 Miner St Cul-de-sac Wilson St AC E 19 1,250 37 48,424 11/23/21 81 Surface Treatment - Slurry Seal 10/6/15 Miner 6150 Miner St Wilson St Joann St AAC E 19 500 37 18,500 11/9/21 89 Overlay - AC Structural 2/1/03 Minnesota 9050 Minnesota Ave Gisler Ave California St AAC E 17 734 37 27,158 3/3/22 100 Overlay - AC Structural 3/3/22 Minnesota 9060 Minnesota Ave California St Iowa St AAC E 17 790 37 29,230 3/3/22 100 Overlay - AC Structural 3/3/22 Minorca Dr 8300 Minorca Dr Mesa Verde Dr Royal Palm Dr AC E 21 1,584 37 58,608 11/16/21 51 Surface Treatment - Slurry Seal 1/1/10 Minorca Pl 7980 Minorca Pl Ellesmere Ave Cul-de-sac AC E 21 950 37 37,324 1/4/22 50 Surface Treatment - Slurry Seal 1/1/10 Mission 10010 Mission Dr Monterey Ave Mendoza Dr AAC E 20 1,680 37 62,160 11/17/21 93 Overlay - AC Structural 12/1/15 Mission 10015 Mission Dr Mendoza Dr La Salle Ave AAC E 20 1,300 37 48,100 11/1/21 84 Overlay - AC Structural 4/1/05 Missouri 9260 Missouri St Minnesota Ave Dakota Ave AAC E 17 796 37 29,452 10/21/21 86 Surface Treatment - Slurry Seal 10/3/23 Modjeska 5760 Modjeska Cir Canyon Dr Cul-de-sac AC E 18 241 37 11,091 1/5/22 90 Surface Treatment - Slurry Seal 9/1/09 Molokai 8280 Molokai Pl Cul-de-sac Gibralter Ave AC E 23 500 37 20,674 11/16/21 63 Surface Treatment - Slurry Seal 1/1/10 Monaco 6790 Monaco Terr Riviera Dr Monte Vista Ave AC E 26 900 33 29,700 10/7/21 69 Surface Treatment - Slurry Seal 1/1/17 Monroe 10860 Monroe Way Cheyenne Ave Cul-de-sac AAC E 16 470 37 19,762 10/19/21 75 Overlay - AC Structural 10/1/15 Monrovia 10 Monrovia Ave n/o 16th St (City Limits) 18th St AC E 6 2,320 37 85,840 10/1/21 93 Surface Treatment - Slurry Seal 12/1/19 Monrovia 15 Monrovia Ave 18th St 19th St AAC E 6 1,335 37 49,395 10/1/21 99 Overlay - AC Structural 11/15/19 Monrovia 20 Monrovia Ave 19th St 20th St AAC E 1 1,330 33 43,890 12/29/21 89 Overlay - AC Structural 3/20/16 Monrovia 25 Monrovia Ave 20th St Victoria St Frontage Road AC E 1 1,982 33 65,406 11/16/21 74 Surface Treatment - Slurry Seal 3/20/16 Monrovia 5880 Monrovia Ave Wilson St Joann St AAC E 18 476 37 18,428 11/9/21 85 Overlay - AC Structural 8/1/07 Montana 9040 Montana Ave Cul-de-sac California St AAC E 17 750 37 29,924 10/22/21 80 Surface Treatment - Slurry Seal 10/3/23 MonteVista 6910 Monte Vista Ave Newport Blvd Orange Ave AAC E 26 1,350 37 49,950 10/5/21 81 Surface Treatment - Slurry Seal 1/1/17 MonteVista 6920 Monte Vista Ave Orange Ave Santa Ana Ave AC E 26 1,328 37 49,136 10/5/21 62 Surface Treatment - Slurry Seal 1/1/17 MonteVista 6930 Monte Vista Ave Santa Ana Ave Irvine Ave AAC E 26 1,314 37 48,618 10/5/21 82 Overlay - AC Structural 6/26/18 Monterey 10000 Monterey Ave Salvador St Mission Dr AC E 20 920 37 34,040 11/17/21 94 2 in Cold Mill & Overlay 1/1/18 Murray 9450 Murray Ln Baker St Watson Ave AC E 15 331 37 12,247 11/15/21 84 Surface Treatment - Slurry Seal 3/20/16 Murray 9550 Murray Ln Conway Ave Belfast AC E 15 971 37 35,927 11/15/21 84 Surface Treatment - Slurry Seal 3/20/16 Myrtlewood 8440 Myrtlewood St Jacaranda Ave Royal Palm Dr AC E 21 830 37 30,710 10/15/21 88 Surface Treatment - Slurry Seal 1/1/10 Nassau 6450 Nassau Rd College Dr Loyola Rd AC E 24 1,692 37 61,531 11/10/21 85 Surface Treatment - Slurry Seal 9/1/09 National 4390 National Ave Victoria St Oak St AAC E 1 800 33 26,400 11/16/21 91 Overlay - AC Structural 3/20/16 National 4391 National Ave Oak St Monrovia Ave AC E 1 1,000 33 33,000 12/29/21 94 New Construction - Initial 2/3/14 National 4400 National Ave Victoria Ave Congress St AAC E 18 460 37 17,020 11/9/21 85 2 in overlay 8/1/11 National 4402 National Ave Congress St Wilson St AAC E 18 713 37 25,613 11/9/21 74 2 in overlay 4/1/02 NebraskaLn 9270 Nebraska Ln Cul-de-sac Missouri St AC E 17 380 37 16,234 10/21/21 87 Surface Treatment - Slurry Seal 10/3/23 NebraskaPl 9070 Nebraska Pl Cul-de-sac California St AAC E 17 629 37 25,447 10/21/21 82 Surface Treatment - Slurry Seal 10/3/23 Nevada 9160 Nevada Ave California St New Hampshire Dr AAC E 17 1,165 37 43,105 3/3/22 100 Overlay - AC Structural 3/3/22 Nevis 7800 Nevis Cir Boa Vista Dr Cul-de-sac AC E 22 518 37 21,340 10/6/21 84 Surface Treatment - Slurry Seal 1/1/10 NHampshire 9210 New Hampshire Dr California St Iowa St AAC E 17 2,370 37 87,690 10/20/21 77 Surface Treatment - Slurry Seal 10/3/23 New Jersey 8920 New Jersey St New York Ave Delaware Pl AC E 17 494 37 18,278 10/22/21 86 Surface Treatment - Slurry Seal 10/3/23 New Mexico 9010 New Mexico St Washington Ave Montana Ave AAC E 17 432 37 16,030 10/22/21 76 Surface Treatment - Slurry Seal 10/3/23 New York 8910 New York Ave Cul-de-sac Iowa St AC E 17 955 37 37,510 10/22/21 68 Surface Treatment - Slurry Seal 10/3/23 Newhall 3040 Newhall St W'ly end Monrovia Ave AC E 6 659 37 24,383 10/1/21 100 Surface Treatment - Slurry Seal 6/1/21 NewportNBF 2020 Newport Blvd N/B Frontage Road AC 16th St PCC E 8 1,022 36 42,552 12/15/21 65 Complete Reconstruction - PCC 1/8/19 NewportNBF 2030 Newport Blvd N/B Frontage Road 16th St AC PCC E 8 960 36 34,560 12/15/21 61 Complete Reconstruction - PCC 1/8/19 NewportNBF 2040 Newport Blvd N/B Frontage Road PCC 17th St AC E 138 37 4,673 12/6/21 68 New Construction - AC 1/1/00 NewportNBF 2070 Newport Blvd N/B Frontage Road 15th St PCC AC E 315 36 11,340 12/15/21 64 New Construction - AC 1/1/00 NewportSBF 2021 Newport Blvd S/B Frontage Road 16th St Industrial Way AC E 7 1,200 36 43,200 12/6/21 84 Surface Treatment - Slurry Seal 10/6/15 Newton 3110 Newton Way Placentia Ave Cul-de-sac AC E 7 580 37 21,460 11/15/21 98 Surface Treatment - Slurry Seal 6/1/21 Norse 6860 Norse Ave Cul-de-sac Santa Isabel Ave AC E 25 330 29 11,744 10/5/21 89 Surface Treatment - Slurry Seal 1/1/17 Norse 6870 Norse Ave Santa Isabel Ave Cul-de-sac AAC E 26 1,068 29 33,146 10/5/21 94 2 in Cold Mill & Overlay 1/1/17 Capella N 7700 North Capella Ct South Capella Ct Europa Dr AC E 22 675 37 28,230 10/15/21 80 Surface Treatment - Slurry Seal 1/1/10 Notre Dame 6370 Notre Dame Rd Amherst Rd Villanova Rd AC E 24 852 37 33,198 11/10/21 95 Surface Treatment - Slurry Seal 3/15/22 Nutmeg 8620 Nutmeg Pl Mace Ave Harbor Blvd AAC E 23 531 36 19,116 11/15/21 89 Overlay - AC Structural 1/8/19 Oahu 8020 Oahu Pl Palau Pl Cul-de-sac AC E 21 483 37 20,045 11/16/21 74 Surface Treatment - Slurry Seal 1/1/10 Oahu 8520 Oahu Pl Cul-de-sac Andros St AC E 21 424 37 17,767 12/15/21 75 Surface Treatment - Slurry Seal 1/1/21 Oak 4360 Oak St State St President Pl AAC E 1 1,058 33 35,714 11/16/21 86 Surface Treatment - Slurry Seal 3/20/16 Oak 4362 Oak St President Pl Continental Ave AAC E 1 817 33 26,961 11/16/21 56 Surface Treatment - Slurry Seal 3/20/16 Oak 4365 Oak St Continental Ave Federal Ave AAC E 1 285 33 9,405 10/1/21 86 Overlay - AC Structural 1/1/00 Ogle Cir 2750 Ogle Cir Cul-de-sac Aliso Ave AAC E 9 400 37 16,974 10/15/21 79 Overlay - AC Structural 4/15/12
254
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Ogle St 2650 Ogle St Orange Ave Santa Ana Ave AAC E 8 1,338 37 49,506 10/15/21 84 Overlay - AC Structural 4/15/12 Ogle St 2660 Ogle St Santa Ana Ave Tustin Ave AAC E 9 1,330 37 49,210 10/15/21 84 Overlay - AC Structural 4/15/12 Ogle St 2760 Ogle St Aliso Ave Irvine Ave AAC E 9 665 37 24,605 10/15/21 87 Overlay - AC Structural 4/15/12 Ohio 8980 Ohio Pl Indiana Ave Cul-de-sac AC E 17 132 37 7,062 10/22/21 48 Surface Treatment - Slurry Seal 10/3/23 Ohms 2930 Ohms Way Cul-de-sac Farad St AC E 7 700 37 28,074 11/1/21 100 Surface Treatment - Slurry Seal 6/1/21 Olympic 11540 Olympic Ave Canadian Dr Yellowstone Dr AAC E 31 850 37 31,450 10/29/21 74 Overlay - AC Structural 10/1/15 Orange 2290 Orange Ave 15th St 16th St AAC E 8 1,320 36 47,520 11/19/21 84 Overlay - AC Structural 4/12/12 Orange 2300 Orange Ave 16th St 17th St AAC E 8 1,313 36 46,818 11/19/21 83 Overlay - AC Structural 2/1/10 Orange 2310 Orange Ave 17th St 18th St AC E 8 1,322 36 46,092 11/19/21 87 Complete Reconstruction - AC 1/1/10 Orange 2320 Orange Ave 18th St Broadway AAC E 8 662 36 23,832 12/28/21 89 Overlay - AC Structural 4/12/12 Orange 2330 Orange Ave Broadway 19th St AC E 8 658 36 23,688 10/8/21 94 Complete Reconstruction - AC 1/1/03 Orange 2340 Orange Ave 19th St 20th St AC E 3 1,323 36 46,628 9/17/21 78 New Construction - Initial 1/1/00 Orange 2350 Orange Ave 20th St 21st St AC E 3 1,318 36 46,498 9/17/21 78 New Construction - Initial 1/1/00 Orange 2360 Orange Ave 21st St 22nd St AC E 3 1,330 36 45,880 9/17/21 80 New Construction - Initial 1/1/00 Orange 2370 Orange Ave 22nd St Wilson St AAC E 25 2,220 36 79,920 9/17/21 98 2 in Cold Mill & Overlay 1/8/19 Orange 2380 Orange Ave Wilson St Santa Isabel Ave AAC E 25 520 36 18,720 9/17/21 98 2 in Cold Mill & Overlay 1/8/19 Orange 2390 Orange Ave Santa Isabel Ave Del Mar Ave AAC E 26 2,645 36 95,220 9/17/21 97 2 in Cold Mill & Overlay 1/8/19 Orange 2400 Orange Ave Del Mar Ave Mesa Dr AC E 26 1,300 36 46,800 9/17/21 90 Surface Treatment - Slurry Seal 1/1/17 Orcas 8250 Orcas Dr Samoa Pl Sumatra Pl AC E 23 230 37 8,510 11/16/21 76 Surface Treatment - Slurry Seal 1/1/10 Oregon 9020 Oregon Ave Cul-de-sac California St AAC E 17 1,060 37 41,394 10/22/21 88 Surface Treatment - Slurry Seal 10/3/23 Oriole 7500 Oriole Dr E'ly Boundry of Tract 6757 Tanager Dr AAC E 11 820 37 30,340 10/6/21 75 Overlay - AC Structural 10/1/15 Oriole 7504 Oriole Dr Placentia Ave E'ly Boundry of Tract 6757 AC E 11 1,320 37 48,840 10/6/21 89 Complete Reconstruction - AC 1/1/04 Oxford 7250 Oxford Ln Greenbriar Ln Princeton Dr AC E 10 600 37 22,200 11/10/21 76 Surface Treatment - Slurry Seal 2/1/06 Pacific 4500 Pacific Ave Victoria Pl N'ly End AC E 18 2,515 36 90,540 11/9/21 71 Surface Treatment - Slurry Seal 10/6/15 Palau 8010 Palau Pl Samar Dr Cul-de-sac AC E 21 974 37 38,212 11/11/21 69 Surface Treatment - Slurry Seal 1/1/10 Palau 8530 Palau Pl Cul-de-sac Andros St AC E 21 375 37 16,049 11/16/21 81 Surface Treatment - Slurry Seal 1/1/10 Palmer 2090 Palmer St Orange Ave Santa Ana Ave AAC E 8 1,325 37 49,025 11/19/21 82 Overlay - AC Structural 7/1/12 Paloma 5320 Paloma Dr 20th St 660' N'ly AAC E 4 660 37 24,420 11/19/21 81 Surface Treatment - Slurry Seal 4/23/24 Pamela 5900 Pamela Ln Cul-de-sac Joann St AC E 19 440 37 16,280 11/23/21 79 Surface Treatment - Slurry Seal 4/1/03 Panay 8790 Panay Cir Cul-de-sac Country Club Dr AC E 22 242 37 10,204 11/16/21 53 Surface Treatment - Slurry Seal 1/1/10 Park Ave 3420 Park Ave 18th St 19th St AAC E 7 1,290 53 68,370 11/15/21 98 Overlay - AC Structural 11/15/19 ParkCenter 11770 Park Center Dr Sunflower Ave Town Center Dr AAC E 28 600 30 18,000 10/28/21 95 Overlay - AC Structural 6/1/06 ParkCenter 11771 Park Center Dr Town Center Dr Sunflower Ave AAC E 28 600 30 18,000 10/28/21 95 Overlay - AC Structural 6/1/06 Park Dr 3160 Park Dr Pomona Ave Crestmont Pl AAC E 7 790 37 29,230 11/15/21 98 Surface Treatment - Slurry Seal 6/1/21 Park Dr 3240 Park Dr Anaheim Ave 18th St AAC E 7 593 33 19,569 11/15/21 98 Surface Treatment - Slurry Seal 6/1/21 Parkcrest 3310 Parkcrest Dr Parkhill Dr 19th St AC E 6 700 37 25,900 10/1/21 100 Surface Treatment - Slurry Seal 6/1/21 Parkglen 3290 Parkglen Cir Parkhill Dr Cul-de-sac AC E 6 126 37 6,836 12/16/21 88 Surface Treatment - Slurry Seal 1/1/21 Parkhill 3280 Parkhill Dr Parkview Cir Whittier Ave AAC E 6 966 37 35,742 10/1/21 98 Overlay - AC Structural 1/1/21 Parkview 3270 Parkview Cir S'ly end Cul-de-sac AC E 6 509 37 21,007 10/1/21 100 Surface Treatment - Slurry Seal 6/1/21 Parkvista 3300 Parkvista Cir Parkhill Dr Cul-de-sac AC E 6 143 37 7,465 10/1/21 100 Surface Treatment - Slurry Seal 6/1/21 Parnell 9580 Parnell Pl Loren Ln Cul-de-sac AC E 15 277 37 12,423 11/15/21 71 Surface Treatment - Slurry Seal 3/20/16 Paros 7860 Paros Cir Cul-de-sac Stromboli Rd AC E 21 446 37 18,676 1/5/22 55 Surface Treatment - Slurry Seal 1/1/10 Parson 4870 Parson St Bernard St Bay St AAC E 5 1,375 37 50,875 11/15/21 98 Overlay - AC Structural 11/15/19 Parson 4930 Parson St S'ly end Victoria St AC E 5 430 37 15,910 11/11/21 92 Surface Treatment - Slurry Seal 12/1/19 Paularino 10450 Paularino Ave Fairview Rd Helena Pl AAC E 16 3,860 37 142,820 10/19/21 87 Overlay - AC Structural 10/1/15 Paularino 11580 Paularino Ave Bear St Bristol St AAC E 31 2,162 37 79,994 11/2/21 70 Overlay - AC Structural 10/1/15 Paularino 11900 Paularino Ave Red Hill Ave Airway Ave AC E 29 880 60 52,800 10/28/21 80 6 in Cold Mill & Overlay in Secure area 8/1/13 Pauline 5560 Pauline Pl Orange Ave Cul-de-sac AAC E 3 320 37 14,014 12/28/21 94 Overlay - AC Structural 3/20/16 Peace 10960 Peace Pl Yukon Ave Klondike Ave AC E 13 600 37 22,200 11/1/21 98 Surface Treatment - Slurry Seal 6/1/21 Pelican 7460 Pelican Pl Albatross Dr Flamingo Ave AC E 11 970 37 35,890 10/4/21 91 Complete Reconstruction - AC 8/1/04 Pemba 8040 Pemba Dr Samar Dr Ceylon Dr AC E 21 1,448 37 54,137 1/5/22 53 Surface Treatment - Slurry Seal 1/1/10 PepperTree 8400 Pepper Tree Ln Royal Palm Dr Royal Palm Dr AC E 21 1,361 37 50,357 11/16/21 52 Surface Treatment - Slurry Seal 1/1/10 Peterson 9300 Peterson Pl Harbor Blvd Adams St AC E 10 1,346 37 49,802 11/9/21 43 New Construction - Initial 1/1/00 Phalarope 7400 Phalarope Ct Swan Dr Swan Dr AAC E 11 1,450 37 53,650 11/23/21 81 Overlay - AC Structural 10/1/15 Pierce 10840 Pierce Ave Cheyenne Ave Concord St AAC E 16 698 36 27,082 10/19/21 72 Overlay - AC Structural 10/1/15 Pierpont 11660 Pierpont Dr Ludington St Sturgeon Dr AAC E 12 1,787 37 66,119 11/23/21 87 Overlay - AC Structural 3/20/16 Pine 4320 Pine Pl Federal Ave Cul-de-sac AAC E 1 200 27 7,574 11/16/21 82 Overlay - AC Structural 1/1/10
255
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Pinecreek 9320 Pinecreek Dr Adams Ave Village Way AC E 15 990 37 36,630 10/29/21 99 2 in Cold Mill & Overlay 1/1/18 Pitcairn 7830 Pitcairn Dr Cul-de-sac Corvo Pl AC E 21 1,795 37 66,415 10/25/21 79 Surface Treatment - Slurry Seal 1/1/10 Platte 11500 Platte Dr Paularino Ave Roanoke Ln AAC E 31 950 37 35,150 10/29/21 85 Overlay - AC Structural 10/1/15 Plum 4310 Plum Pl Federal Ave Cul-de-sac AAC E 1 200 27 7,574 11/16/21 72 Overlay - AC Structural 9/14/10 Plumer 3400 Plumer St Pomona Ave Anaheim Ave AAC E 7 1,320 33 43,560 11/15/21 99 Surface Treatment - Slurry Seal 6/1/21 Plumer 3410 Plumer St W'ly end Park Ave AAC E 7 232 37 8,584 11/15/21 99 Overlay - AC Structural 1/1/21 Plumeria 11340 Plumeria Pl Begonia Ave Goldenrod Dr AC E 27 540 37 19,980 10/29/21 90 Surface Treatment - Slurry Seal 1/1/18 Pomona 30 Pomona Ave 16th St 18th St AAC E 7 2,635 36 94,860 9/30/21 99 2 in Cold Mill & Overlay 1/1/17 Pomona 40 Pomona Ave 18th St 19th St AAC E 7 1,313 36 47,268 9/30/21 100 2 in Cold Mill & Overlay 12/1/18 Pomona 50 Pomona Ave 19th St Victoria St AAC E 2 3,300 36 118,800 9/30/21 99 Overlay - AC Structural 11/15/19 Pomona 60 Pomona Ave Victoria St Wilson St AC E 19 1,330 36 47,880 9/30/21 98 Surface Treatment - Slurry Seal 12/1/19 Pomona 6010 Pomona Ave Wilson St Joann St AAC E 19 535 37 19,795 11/23/21 87 Overlay - AC Structural 5/1/03 Ponderosa 8310 Ponderosa St Andros St Royal Palm Dr AC E 21 1,067 37 39,479 11/16/21 56 Surface Treatment - Slurry Seal 1/1/10 Ponderosa 8320 Ponderosa St Royal Palm Dr Harbor Blvd AC E 21 790 37 29,230 11/16/21 76 Surface Treatment - Slurry Seal 1/1/10 Poppy 11280 Poppy Cir Lavender Ln Geranium St AC E 27 350 37 15,125 10/29/21 82 Surface Treatment - Slurry Seal 1/1/18 Portola 10220 Portola Dr Loreto Ave Drake Ave AAC E 20 1,140 37 43,680 11/22/21 89 Overlay - AC Structural 1/1/10 Post 10410 Post Rd Babb St Milbro St AAC E 20 780 37 28,860 10/22/21 86 Overlay - AC Structural 1/1/10 President 4380 President Pl Cul-de-sac Oak St AAC E 1 661 33 23,987 11/16/21 89 Overlay - AC Structural 3/20/16 President 4580 President Pl Cul-de-sac Victoria St Frontage Road AC E 1 590 33 21,644 11/16/21 92 Surface Treatment - Slurry Seal 3/20/16 Presidio 9840 Presidio Dr Lorenzo Ave Junipero Dr AAC E 20 2,460 37 91,020 11/22/21 81 Overlay - AC Structural 3/1/07 Presidio 9850 Presidio Dr Junipero Dr Newport Blvd AAC E 20 1,435 37 53,095 11/22/21 82 Overlay - AC Structural 7/1/06 PresidioSq 9860 Presidio Sq Presidio Dr S'ly end AC E 20 150 37 5,550 11/22/21 39 New Construction - Initial 1/1/00 PresidioSq 9865 Presidio Sq Presidio Sq West Presidio Sq East AC E 928 60 55,680 11/22/21 61 New Construction - AC 1/1/80 PresidioSq 9870 Presidio Sq S'ly end Presidio Dr AAC E 20 150 37 5,550 12/29/21 64 Overlay - AC Structural 12/1/15 Primrose 8420 Primrose St Jacaranda Ave Royal Palm Dr AC E 21 769 37 28,326 10/15/21 67 Surface Treatment - Slurry Seal 1/1/10 Princeton 7210 Princeton Dr Harbor Blvd Oxford Ln AC E 10 1,000 37 37,000 11/10/21 47 Surface Treatment - Slurry Seal 12/1/00 Princeton 7220 Princeton Dr Oxford Ln Fairview Rd AAC E 10 2,740 37 101,380 11/10/21 80 2 in overlay 6/1/00 Prospect 10940 Prospect Pl Klondike Ave Cul-de-sac AC E 13 300 37 11,100 11/1/21 99 Surface Treatment - Slurry Seal 6/1/21 Puente 5950 Puente Ave Cul-de-sac Senate St AAC E 19 770 37 30,664 11/9/21 62 Overlay - AC Structural 5/1/03 Pullman 11860 Pullman Ave Kalmus Rd 420' S/O Briggs Ave AC E 29 2,011 55 109,600 11/8/21 72 6 in Cold Mill & Overlay in Secure area 8/1/13 Pullman 11865 Pullman Ave 420' S/O Briggs Ave Baker St AC E 29 887 55 48,342 11/8/21 93 6 in Cold Mill & Overlay in Secure area 8/1/13 Pullman 11920 Pullman Ave Paularino Ave Red Hill Ave AC E 29 2,300 60 138,920 9/16/21 78 6 in Cold Mill & Overlay in Secure area 8/1/13 Purdue 6540 Purdue Dr Villanova Rd Cul-de-sac AC E 24 400 37 16,974 11/10/21 100 Surface Treatment - Slurry Seal 6/1/21 Ralcam 4950 Ralcam Pl Cul-de-sac Thurin St AC E 5 545 37 22,339 11/11/21 93 Surface Treatment - Slurry Seal 12/1/19 Raleigh 4650 Raleigh Ave Hamilton St Cul-de-sac AAC E 2 599 37 24,337 11/12/21 95 Overlay - AC Structural 11/15/19 Raleigh 5930 Raleigh Ave Cul-de-sac Wilson St AC E 19 1,280 37 49,534 11/9/21 76 Complete Reconstruction - AC 2/1/06 RamonaPl 2160 Ramona Pl Santa Ana Ave Cul-de-sac AAC E 9 534 37 21,932 11/19/21 88 Overlay - AC Structural 7/1/12 RamonaWy 2190 Ramona Way Cul-de-sac Tustin Ave AAC E 9 560 33 20,654 11/19/21 84 Overlay - AC Structural 4/12/12 Randolph 10360 Randolph Ave E'ly end Bristol St AC E 13 649 37 23,763 11/22/21 61 Surface Treatment - Slurry Seal 1/1/00 Randolph 10370 Randolph Ave Bristol St Baker St AC E 13 1,230 60 73,800 11/1/21 50 Surface Treatment - Slurry Seal 12/6/22 Randolph 11490 Randolph Ave Baker St Cul-de-sac AAC E 13 1,070 37 39,590 11/1/21 89 Overlay - AC Structural 12/1/08 Raymond 3610 Raymond Ave 17th St N'ly end AAC E 9 650 25 15,750 11/29/21 66 Overlay - AC Structural 4/1/12 Raymond 4120 Raymond Ave Magnolia St 19th St AAC E 9 996 37 36,852 11/19/21 78 Overlay - AC Structural 4/1/12 Raymond 4130 Raymond Ave 19th St 20th St AAC E 4 1,300 37 48,100 11/19/21 83 Overlay - AC Structural 4/1/12 Redding 11080 Redding Ave Visalia Dr San Leandro Ln AC E 14 873 37 32,301 10/27/21 85 Surface Treatment - Slurry Seal 1/1/18 Redlands 2220 Redlands Pl Cul-de-sac 16th St AAC E 9 200 33 8,774 11/19/21 92 Surface Treatment - Slurry Seal 9/15/15 Redwing 7600 Redwing Cir Hummingbird Dr Cul-de-sac AAC E 11 260 37 11,794 10/6/21 78 Overlay - AC Structural 10/1/15 Redwood 8470 Redwood Ave Cul-de-sac Myrtlewood St AAC E 21 1,285 37 49,719 12/31/21 100 Overlay - AC Structural 12/31/21 Regis 10070 Regis Ln Cul-de-sac Mission Dr AAC E 20 200 33 8,774 11/17/21 94 Overlay - AC Structural 4/28/11 Republic 4240 Republic Ave Arbor St Dogwood St AAC E 1 518 33 19,122 11/9/21 91 Overlay - AC Structural 2/28/11 Republic 4330 Republic Ave Cul-de-sac Oak St AAC E 1 1,200 33 41,774 11/16/21 94 Overlay - AC Structural 3/20/16 Republic 4570 Republic Ave Union Ave Victoria St Frontage Road AC E 1 500 33 16,500 11/16/21 85 New Construction - Initial 1/1/00 Republic 5690 Republic Ave Senate St Wilson St AAC E 18 500 37 18,500 11/9/21 84 Overlay - AC Structural 9/1/10 Republic 5700 Republic Ave Wilson St Joann St AAC E 18 500 37 18,500 12/15/21 82 Overlay - AC Structural 1/1/10 Rhode Isl 9240 Rhode Island Cir New Hampshire Dr Cul-de-sac AAC E 17 121 37 6,651 3/3/22 100 Overlay - AC Structural 3/3/22 Rhodes 7810 Rhodes Dr Mesa Verde Dr Stromboli Rd AC E 21 680 37 25,160 11/11/21 100 Surface Treatment - Slurry Seal 6/1/21 Ridgecrest 4480 Ridgecrest Cir Valley Rd Cul-de-sac AC E 1 271 37 12,201 11/16/21 52 Surface Treatment - Slurry Seal 9/1/09
256
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Riverside 2210 Riverside Pl Cul-de-sac 16th St AAC E 9 200 33 8,774 11/19/21 77 Overlay - AC Structural 4/12/12 Riviera 6780 Riviera Dr Rue De Cannes Tustin Ave AC E 26 910 33 30,030 10/5/21 70 Surface Treatment - Slurry Seal 1/1/17 Roanoke 11510 Roanoke Ln Cul-de-sac Allegheny Ave AAC E 31 700 37 28,074 10/29/21 71 Overlay - AC Structural 10/1/15 Robin Hood 5390 Robin Hood Ln Cul-de-sac Westminster Ave AAC E 3 349 33 13,691 11/9/21 84 Overlay - AC Structural 4/1/12 Robin Hood 5400 Robin Hood Ln Westminster Ave Santa Ana Ave AAC E 3 653 37 24,161 11/9/21 76 Overlay - AC Structural 4/1/12 Robin Hood 5410 Robin Hood Ln Santa Ana Ave Cul-de-sac AAC E 3 653 37 26,335 11/9/21 79 Overlay - AC Structural 4/1/12 Rochester 3620 Rochester St Newport Blvd Orange Ave AAC E 8 1,340 37 49,580 1/5/22 61 Overlay - AC Structural 4/1/12 Rochester 3630 Rochester St Orange Ave Cul-de-sac AAC E 8 531 28 17,042 10/8/21 81 Overlay - AC Structural 4/1/12 Rochester 3640 Rochester St Westminster Ave Cul-de-sac AAC E 8 322 33 12,800 11/29/21 80 Overlay - AC Structural 4/1/12 Rochester 3650 Rochester St Santa Ana Ave Tustin Ave AAC E 9 1,324 37 48,988 10/8/21 78 Overlay - AC Structural 4/1/12 Rogers 3710 Rogers Pl S'ly end 18th St AAC E 8 300 37 11,100 11/19/21 92 Overlay - AC Structural 11/17/10 Roosevelt 10740 Roosevelt Way Cul-de-sac Carson St AAC E 16 368 37 15,992 11/17/21 75 Overlay - AC Structural 10/1/15 Rose 5620 Rose Ln Orange Ave Santa Ana Ave AC E 3 1,300 37 48,100 10/7/21 62 Surface Treatment - Slurry Seal 4/1/16 Rosemary 5100 Rosemary Pl Cul-de-sac 20th St AAC E 3 600 37 24,374 11/10/21 87 Overlay - AC Structural 4/1/12 Ross 4740 Ross St Arnold Ave Meyer Pl AAC E 2 600 37 22,200 12/28/21 92 Overlay - AC Structural 6/16/15 Royal Palm 8550 Royal Palm Dr Adams Ave Baker St AC E 21 2,641 37 97,717 10/4/21 72 Surface Treatment - Slurry Seal 1/1/10 Royal Palm 8560 Royal Palm Dr Baker St Corsica Pl AC E 23 362 37 13,394 11/16/21 47 Surface Treatment - Slurry Seal 1/1/10 Royce 9410 Royce Ln Baker St Watson Ave AC E 15 953 37 35,261 11/15/21 66 Surface Treatment - Slurry Seal 4/1/16 Rue Cannes 6800 Rue De Cannes Riviera Dr Monte Vista Ave AC E 26 890 33 29,370 10/5/21 81 Surface Treatment - Slurry Seal 1/1/17 Rural Ln 5520 Rural Ln 22nd St Rural Pl AC E 3 560 33 18,480 10/7/21 73 New Construction - Initial 1/1/00 Rural Pl 5530 Rural Pl Rural Ln 22nd St AC E 3 750 33 24,750 10/7/21 70 New Construction - Initial 1/1/00 Rutgers 6190 Rutgers Dr Avocado St Wilson St AC E 5 668 37 24,716 11/23/21 98 Surface Treatment - Slurry Seal 12/1/19 Rutgers 6260 Rutgers Dr Wilson St Joann St AC E 24 470 36 17,190 11/23/21 89 Surface Treatment - Slurry Seal 2/1/06 Rutgers 6340 Rutgers Dr Wake Forest Rd Villanova Rd AC E 24 1,130 37 41,810 11/10/21 72 Surface Treatment - Slurry Seal 9/1/09 SaintClair 10270 Saint Clair St Velasco Ln Bear St AC E 20 1,160 37 42,920 11/22/21 83 6 in Cold Mill & Overlay in Secure area 2/1/12 SaintClair 10350 Saint Clair St Cul-de-sac Randolph Ave AAC E 13 320 60 21,374 11/1/21 83 Surface Treatment - Slurry Seal 12/6/22 Salinas 11040 Salinas Ave Wimbledon Way Smalley Rd AC E 14 1,805 37 70,291 10/27/21 72 Surface Treatment - Slurry Seal 1/1/18 Salvador 9990 Salvador St Monterey Ave Lorenzo Dr AAC E 20 1,158 37 42,846 11/17/21 89 Overlay - AC Structural 1/1/10 Samar Dr 7960 Samar Dr Cul-de-sac Mesa Verde Dr AC E 21 2,700 37 102,074 1/5/22 37 Surface Treatment - Slurry Seal 1/1/10 Samar Pl 8510 Samar Pl Cul-de-sac Andros St AC E 21 400 37 16,974 11/16/21 61 Surface Treatment - Slurry Seal 1/1/10 Samoa 8210 Samoa Pl Cul-de-sac Gibraltar Ave AC E 23 1,849 37 70,587 11/16/21 66 Surface Treatment - Slurry Seal 1/1/10 SanBrnrdno 2230 San Bernardino Pl Cul-de-sac 16th St AAC E 9 200 33 8,774 11/19/21 83 Overlay - AC Structural 4/12/12 San Carlos 9960 San Carlos Ln De Soto Ave Coronado Dr AAC E 20 795 37 30,365 11/22/21 82 Overlay - AC Structural 12/1/15 San Jose 11120 San Jose Ave Deedee Dr Santa Clara Cir AC E 14 580 36 20,725 10/27/21 68 Surface Treatment - Slurry Seal 1/1/18 San Juan 10180 San Juan Ln Coronado Dr El Camino Dr AC E 20 497 37 18,389 12/29/21 94 6 in Cold Mill & Overlay in Secure area 9/1/13 San Juan 9940 San Juan Ln Cibola Ave Coronado Dr AAC E 20 1,043 37 39,541 11/22/21 81 Overlay - AC Structural 12/1/15 SanLeandro 11060 San Leandro Ln South Coast Dr Redding Ln AAC E 27 683 37 25,271 10/27/21 95 2 in Cold Mill & Overlay 1/1/18 San Lucas 10330 San Lucas Ln Presidio Dr Cul-de-sac AAC E 20 310 37 13,644 11/22/21 100 Overlay - AC Structural 1/1/21 San Marino 11170 San Marino Cir Santa Rosa Ave Cul-de-sac AAC E 14 377 37 16,123 10/27/21 93 Surface Treatment - Slurry Seal 1/1/18 San Pablo 11200 San Pablo Cir Cul-de-sac Smalley Rd AAC E 14 423 37 17,771 10/27/21 90 Surface Treatment - Slurry Seal 1/1/18 San Rafael 11160 San Rafael Cir Santa Rosa Ave Cul-de-sac AAC E 14 360 37 15,494 10/27/21 92 Surface Treatment - Slurry Seal 1/1/18 Sanderling 7440 Sanderling Cir Gannet Dr Cul-de-sac AAC E 11 330 37 14,384 10/6/21 86 Overlay - AC Structural 10/1/15 Sandlewood 8460 Sandlewood St Jacaranda Ave Redwood Ave AAC E 21 593 37 21,941 12/31/21 100 Overlay - AC Structural 12/31/21 Sandpiper 7350 Sandpiper Dr Swan Dr Flamingo Dr AAC E 11 1,170 37 43,290 10/4/21 84 Overlay - AC Structural 10/1/15 Santa Ana 2420 Santa Ana Ave 15th St 16th St AAC E 8 1,321 35 46,235 12/28/21 49 Surface Treatment - Slurry Seal 9/1/22 Santa Ana 2430 Santa Ana Ave 16th St 17th St AAC E 8 1,320 36 47,520 12/28/21 68 Overlay - AC Structural 4/1/12 Santa Ana 2440 Santa Ana Ave 17th St 18th St AC E 8 1,313 36 47,268 10/8/21 87 Complete Reconstruction - AC 1/1/10 Santa Ana 2450 Santa Ana Ave 18th St Broadway AC E 8 668 33 22,044 10/8/21 94 Complete Reconstruction - AC 1/1/10 Santa Ana 2460 Santa Ana Ave Broadway 19th St AC E 8 660 37 24,420 12/28/21 94 Complete Reconstruction - AC 1/1/10 Santa Ana 2470 Santa Ana Ave 19th St 20th St AC E 3 1,250 32 40,000 9/17/21 92 Complete Reconstruction - AC 1/1/10 Santa Ana 2480 Santa Ana Ave 20th St 21st St AC E 3 1,290 36 46,440 9/17/21 91 Complete Reconstruction - AC 1/1/10 Santa Ana 2490 Santa Ana Ave 21st St 22nd St AC E 3 1,319 36 47,484 9/17/21 93 Complete Reconstruction - AC 1/1/10 Santa Ana 2500 Santa Ana Ave 22nd St 23rd St AAC E 25 1,317 36 47,412 9/17/21 99 Overlay-Rubber Hot Mix 1/1/21 Santa Ana 2510 Santa Ana Ave 23rd St Santa Isabel Ave AC E 25 1,322 36 47,592 10/7/21 68 New Construction - Initial 1/1/00 Santa Ana 2520 Santa Ana Ave Santa Isabel Ave Monte Vista Ave AC E 26 1,324 36 47,664 9/17/21 95 Surface Treatment - Slurry Seal 1/1/17 Santa Ana 2530 Santa Ana Ave Monte Vista Ave Del Mar Ave AC E 26 1,320 36 47,520 9/17/21 96 Surface Treatment - Slurry Seal 1/1/17 SantaClara 11140 Santa Clara Cir Salinas Ave Cul-de-sac AC E 14 1,363 37 51,630 10/27/21 81 Surface Treatment - Slurry Seal 1/1/18
257
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Santa Cruz 11190 Santa Cruz Cir Cul-de-sac Smalley Rd AAC E 14 423 37 17,871 10/27/21 91 Surface Treatment - Slurry Seal 1/1/18 Snt Isabel 6740 Santa Isabel Ave Newport Blvd Orange Ave AAC E 26 1,320 37 48,840 9/17/21 71 Surface Treatment - Slurry Seal 1/1/17 Snt Isabel 6750 Santa Isabel Ave Orange Ave Santa Ana Ave AC E 26 1,320 37 48,840 9/17/21 58 Surface Treatment - Slurry Seal 1/1/17 Snt Isabel 6760 Santa Isabel Ave Santa Ana Ave Tustin Ave AAC E 26 1,320 37 48,840 9/17/21 98 Overlay - AC Structural 11/15/19 Santa Rosa 11150 Santa Rosa Ave Santa Clara Cir Smalley Rd AAC E 14 659 37 24,383 10/27/21 89 Surface Treatment - Slurry Seal 1/1/18 Santiago 10280 Santiago Rd Velasco Ln Sonora Rd AAC E 20 921 37 35,077 11/22/21 75 Overlay - AC Structural 9/15/15 SantoTomas 7050 Santo Tomas St Cul-de-sac Santa Ana Ave AAC E 26 687 37 27,593 9/17/21 82 Surface Treatment - Slurry Seal 1/1/17 Scenic 9750 Scenic Dr Cadillac Ave Hyland Ave AC E 30 1,076 36 38,736 10/21/21 94 Overlay-Rubber Hot Mix 11/15/19 Scenic 9760 Scenic Dr Hyland Ave Harbor Blvd AC E 30 1,891 54 102,114 10/21/21 43 New Construction - Initial 1/1/00 Scott 3260 Scott Pl Placentia Ave Wallace Ave AC E 7 657 37 24,309 10/14/21 99 Surface Treatment - Slurry Seal 6/1/21 Sea Bluff 4440 Sea Bluff Dr Gleneagles Terr Canyon Dr AAC E 1 1,154 37 42,698 11/16/21 82 Overlay - AC Structural 1/1/10 Seal 4750 Seal St Arnold Ave Meyer Pl AAC E 2 554 36 20,117 10/18/21 94 Overlay - AC Structural 6/16/15 Secretarit 11220 Secretariat Cir Smalley Rd Cul-de-sac AAC E 27 572 37 23,338 10/27/21 89 2 in Cold Mill & Overlay 1/8/19 Senate 5730 Senate St Republic Ave Continental Ave AC E 18 1,376 37 53,519 11/9/21 90 Surface Treatment - Slurry Seal 10/6/15 Senate 5970 Senate St Pomona Ave Puente Ave AC E 19 519 37 19,203 11/9/21 85 Complete Reconstruction - AC 2/1/04 Serang 8000 Serang Pl Tabago Pl Mesa Verde Dr AC E 21 1,049 37 38,813 11/11/21 75 Surface Treatment - Slurry Seal 1/1/10 Serra 9980 Serra Way Fremont Ln Coronado Dr AC E 20 590 37 21,830 11/22/21 68 Surface Treatment - Slurry Seal 2/1/06 Shalimar 3120 Shalimar Dr Placentia Ave Pomona Ave AC E 7 1,260 37 46,620 11/15/21 98 Surface Treatment - Slurry Seal 6/1/21 Shalimar 3170 Shalimar Dr Cul-de-sac Kenwood Pl AC E 7 1,260 37 48,794 11/15/21 98 Surface Treatment - Slurry Seal 6/1/21 Shamrock 9500 Shamrock Ln Dublin St Watson Ln AC E 15 518 37 19,166 11/15/21 65 Surface Treatment - Slurry Seal 4/1/16 Shannon 9408 Shannon Ln College Ave Watson Ln AC E 15 500 37 18,500 11/15/21 60 Surface Treatment - Slurry Seal 3/20/16 Shantar 7420 Shantar Dr Adams Ave Balearic Dr AC E 22 898 37 35,813 10/25/21 62 Surface Treatment - Slurry Seal 1/1/10 Sharon 9610 Sharon Ln Stonefield St Londonderry St AC E 15 576 37 21,562 11/15/21 87 Surface Treatment - Slurry Seal 3/20/16 SherwoodPl 5420 Sherwood Pl Cul-de-sac Westminster Ave AAC E 3 332 33 13,130 11/9/21 81 Overlay - AC Structural 4/1/12 SherwoodSt 5430 Sherwood St Westminster Ave Santa Ana Ave AAC E 3 658 37 24,346 11/9/21 80 Overlay - AC Structural 4/1/12 Sicily 8270 Sicily Ave Sumatra Pl Gisler Ave AC E 23 800 37 29,600 11/16/21 71 Surface Treatment - Slurry Seal 1/1/10 Sierks 5360 Sierks St Orange Ave Santa Ana Ave AAC E 3 1,315 37 48,655 11/9/21 90 Overlay - AC Structural 4/1/12 Skylark 7560 Skylark Cir Cul-de-sac Kinglet Ct AAC E 11 198 37 9,216 10/18/21 76 Overlay - AC Structural 10/1/15 Smalley 11180 Smalley Rd Salinas Ave Sunflower Ave AAC E 27 1,526 36 59,055 10/27/21 81 Surface Treatment - Slurry Seal 1/1/18 Sonora 10200 Sonora Rd La Salle Ave Velasco Ln AAC E 20 770 37 28,490 11/22/21 73 Overlay - AC Structural 9/15/15 Sonora 10202 Sonora Rd Velasco Ln Loreto Ave AC E 20 1,150 37 44,550 11/22/21 42 New Construction - Initial 1/1/00 Sonora 10204 Sonora Rd Loreto Ave Drake Ave AAC E 20 450 37 16,650 11/22/21 90 Overlay - AC Structural 6/1/09 Capella S 7690 South Capella Ct Europa Dr North Capella Ct AC E 22 740 37 30,224 10/15/21 83 Surface Treatment - Slurry Seal 10/6/10 Sparrow 7550 Sparrow Cir Tanager Dr Cul-de-sac AAC E 11 195 36 9,608 10/18/21 89 Overlay - AC Structural 10/1/15 Springfld 10820 Springfield St Hayes Ave Cheyenne St AAC E 16 600 37 23,150 10/19/21 78 Overlay - AC Structural 10/1/15 Starbird 7630 Starbird Dr Tanager Dr Cul-de-sac AAC E 11 785 37 31,219 10/6/21 78 Overlay - AC Structural 10/1/15 State 4350 State Ave Grove Pl Oak St AC E 1 560 33 18,480 11/16/21 69 Surface Treatment - Slurry Seal 3/20/16 State 5660 State Ave Cul-de-sac Wilson St AAC E 18 1,240 33 43,094 11/9/21 76 Overlay - AC Structural 9/1/05 Sterling 4660 Sterling Ave Hamilton St Cul-de-sac AC E 2 600 37 24,374 11/12/21 97 Surface Treatment - Slurry Seal 12/1/19 Sterling 4664 Sterling Ave Alley 012 (300' w/o Pomona Ave) Pomona Ave AAC E 2 308 37 11,176 11/15/21 96 Surface Treatment - Slurry Seal 12/1/19 Stonefield 9590 Stonefield St Killybrooke Ln Limerick Ln AC E 15 530 37 19,335 11/15/21 75 Surface Treatment - Slurry Seal 3/20/16 Stromboli 7850 Stromboli Rd Pitcairn Dr Club House Rd AC E 21 1,399 37 51,763 1/5/22 45 Surface Treatment - Slurry Seal 1/1/10 Sturgeon 11670 Sturgeon Dr Ludington St Pierpont Dr AAC E 12 1,700 37 62,900 11/23/21 88 Overlay - AC Structural 3/20/16 Sumatra 8260 Sumatra Pl Orcas Dr Gibraltar Ave AC E 23 1,086 37 40,182 11/16/21 78 Surface Treatment - Slurry Seal 1/1/10 Sumba 7780 Sumba Cir Balearic Dr Cul-de-sac AC E 22 240 37 11,054 10/25/21 78 Surface Treatment - Slurry Seal 1/1/10 Sunflower 775 Sunflower Ave Cadillac Ave Hyland Ave AC E 30 1,775 60 106,500 11/2/21 59 New Construction - Initial 1/1/00 Sunset 3050 Sunset Dr W'ly end Monrovia Ave AC E 6 650 37 24,050 12/29/21 94 Surface Treatment - Slurry Seal 11/1/21 Superior 2970 Superior Ave 400' n/o E. 17th St Newport Blvd AAC E 7 400 37 14,800 11/15/21 97 Overlay - AC Structural 7/1/19 Superior 2972 Superior Ave E. 17th St 400' n/o E. 17th St AC E 7 400 37 14,800 11/15/21 83 Complete Reconstruction - AC 11/1/08 Superior 2974 Superior Ave Newport Blvd Entrance 18th St AAC E 7 800 48 38,400 1/5/22 61 Overlay - AC Structural 7/1/19 Surf 4730 Surf St Arnold Ave Meyer Pl AAC E 2 600 33 19,800 12/28/21 93 Overlay - AC Structural 6/16/15 Susan 9830 Susan St South Coast Dr Pavement Change AC E 30 493 37 18,241 11/29/21 85 New Construction - Initial 1/1/00 Susan 9831 Susan St Sunflower Ave South Coast Dr AC E 30 1,500 37 55,500 10/22/21 62 New Construction - Initial 1/1/00 Susan 9835 Susan St Pavement Change Sunflower Ave AC E 30 1,004 37 37,148 11/29/21 51 New Construction - Initial 1/1/00 Susannah 6980 Susannah Pl Orange Ave Cul-de-sac AAC E 26 292 33 11,810 9/17/21 99 2 in Cold Mill & Overlay 1/8/19 Sutter 10230 Sutter Way Junipero Dr Magellan St AAC E 20 260 37 9,620 11/22/21 85 Overlay - AC Structural 3/1/06 Suva 7770 Suva Cir Balearic Dr Cul-de-sac AC E 22 400 37 16,974 10/25/21 82 Surface Treatment - Slurry Seal 12/27/10
258
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Swan Cir 7340 Swan Cir Placentia Ave Cul-de-sac AAC E 11 400 37 16,974 10/4/21 90 Overlay - AC Structural 10/1/15 Swan Dr 7330 Swan Dr Sandpiper Dr E'ly end AAC E 11 2,190 37 81,030 10/4/21 83 Overlay - AC Structural 9/1/03 Swarthmore 7120 Swarthmore Ln Cul-de-sac Carnegie Ave AC E 10 390 33 15,044 11/10/21 78 Surface Treatment - Slurry Seal 9/1/09 Tabago 7990 Tabago Pl Serang Pl Minorca Pl AC E 21 700 37 25,900 11/11/21 80 Surface Treatment - Slurry Seal 1/1/10 Taft 10730 Taft Way Cul-de-sac Carson St AAC E 16 377 37 15,985 11/17/21 63 Overlay - AC Structural 10/1/15 Tahiti 8050 Tahiti Dr Pemba Dr Mesa Verde Dr AC E 21 1,171 37 43,327 11/11/21 100 Surface Treatment - Slurry Seal 6/1/21 Tahiti 8060 Tahiti Dr Mesa Verde Dr Java Rd AC E 22 1,090 37 40,330 11/11/21 61 Surface Treatment - Slurry Seal 1/1/10 Tanager 7520 Tanager Dr Canary Dr Golf Course Dr AAC E 11 2,400 37 88,800 10/6/21 78 Overlay - AC Structural 10/1/15 Tanana 10980 Tanana Pl Yukon Ave Cul-de-sac AC E 13 882 37 34,408 11/1/21 99 Surface Treatment - Slurry Seal 6/1/21 Taylor 10690 Taylor Way Cul-de-sac Austin St AAC E 16 423 37 17,825 10/26/21 80 Overlay - AC Structural 10/1/15 Teakwood 8480 Teakwood Pl Cul-de-sac Myrtlewood St AC E 21 324 37 14,162 10/15/21 76 Surface Treatment - Slurry Seal 1/1/10 Terminal 3200 Terminal Way W'ly end Anaheim Ave AAC E 7 642 37 23,754 10/1/21 100 Overlay - AC Structural 1/1/21 Tern 7470 Tern Cir Placentia Ave Cul-de-sac AAC E 11 580 37 23,634 10/4/21 76 Overlay - AC Structural 10/1/15 Texas 9130 Texas Cir Cul-de-sac California St AAC E 17 197 33 8,675 3/3/22 100 Overlay - AC Structural 3/3/22 TheMasters 11780 The Masters Cir Newport Blvd Cul-de-sac AAC E 29 1,050 37 41,024 12/6/21 87 Overlay - AC Structural 12/31/15 Thurin 4920 Thurin St Bay St Victoria St AAC E 5 1,340 36 48,240 11/11/21 87 Overlay - AC Structural 5/19/17 Timor 7940 Timor Dr Club House Rd Samar Dr AC E 21 330 37 12,210 11/11/21 100 Surface Treatment - Slurry Seal 6/1/21 Toronto 9740 Toronto Way Cadillac Ave Cul-de-sac AC E 30 439 37 18,417 10/21/21 72 New Construction - Initial 1/1/00 Town Cntr 11730 Town Center Dr Bristol St Park Center Dr AAC E 28 650 46 29,900 10/28/21 88 Overlay - AC Structural 12/1/04 Towne 3320 Towne St Monrovia Ave Placentia Ave AAC E 6 1,300 37 48,100 10/1/21 99 Overlay - AC Structural 1/1/21 Trabuco 5770 Trabuco Cir Canyon Dr Cul-de-sac AC E 18 248 37 9,176 1/5/22 87 Surface Treatment - Slurry Seal 9/1/09 Traverse 11680 Traverse Dr Ludington St Sturgeon Dr AAC E 12 2,000 37 74,000 11/23/21 87 Overlay - AC Structural 3/20/16 Trenton 10910 Trenton Way Jefferson Ave Cul-de-sac AAC E 16 450 37 20,024 10/19/21 80 Overlay - AC Structural 10/1/15 Trinity 11570 Trinity Dr Paularino Ave Yellowstone Dr AAC E 31 1,086 37 40,182 10/28/21 78 Overlay - AC Structural 10/1/15 Tulane Pl 6410 Tulane Pl Columbia Dr Cul-de-sac AC E 24 195 37 9,389 11/10/21 52 Surface Treatment - Slurry Seal 9/1/09 Tulane Rd 6400 Tulane Rd Notre Dame Rd Columbia Dr AC E 24 600 37 22,395 12/29/21 70 Surface Treatment - Slurry Seal 9/1/09 Tulare 11050 Tulare Dr Salinas Ave San Leandro Ln AC E 14 1,721 37 63,677 10/27/21 60 Surface Treatment - Slurry Seal 1/1/18 Tulip 5550 Tulip Ln Elden Ave Orange Ave AC E 3 640 37 23,680 10/7/21 76 Surface Treatment - Slurry Seal 3/20/16 Turlock 11090 Turlock Dr Redding Ave Salinas Ave AC E 14 853 36 37,158 10/27/21 65 Surface Treatment - Slurry Seal 1/1/18 Tustin 2550 Tustin Ave 15th St 16th St AC E 9 1,300 36 46,800 11/19/21 70 Complete Reconstruction - AC 2/1/10 Tustin 2560 Tustin Ave 16th St 17th St AC E 9 1,300 36 46,800 11/19/21 87 Complete Reconstruction - AC 2/1/10 Tustin 2570 Tustin Ave 17th St 18th St AAC E 9 1,328 36 47,808 11/19/21 94 Overlay - AC Structural 4/1/12 Tustin 2580 Tustin Ave 18th St 19th St AAC E 9 1,319 36 47,484 11/19/21 93 Overlay - AC Structural 4/1/12 Tustin 2590 Tustin Ave 19th St 20th St AAC E 4 1,322 36 47,592 11/19/21 81 Overlay - AC Structural 4/1/12 Tustin 2600 Tustin Ave 20th St Emerson St AAC E 4 820 36 29,520 11/19/21 72 Overlay - AC Structural 4/1/12 Tyler 10680 Tyler Way Cul-de-sac Austin St AAC E 16 438 37 18,380 10/26/21 79 Overlay - AC Structural 10/1/15 Union 4560 Union St Victoria St Frontage Road Republic Ave AAC E 18 770 33 25,410 11/16/21 89 Overlay - AC Structural 12/1/07 Utah 9120 Utah Cir Cul-de-sac California St AAC E 17 162 33 7,446 10/22/21 89 Overlay - AC Structural 11/15/19 Valencia 10130 Valencia St Mendoza Dr La Salle Ave AC E 20 1,200 37 44,400 11/1/21 94 Complete Reconstruction - AC 11/1/07 Vallejo 11210 Vallejo Cir Cul-de-sac Smalley Rd AAC E 14 423 37 17,812 10/27/21 89 Surface Treatment - Slurry Seal 1/1/18 Valley Cir 4485 Valley Cir Valley Rd Cul-de-sac AAC E 1 303 37 13,385 11/16/21 90 Overlay - AC Structural 4/1/01 Valley Rd 4420 Valley Rd Aviemore Terr Sea Bluff Dr AAC E 1 604 37 22,348 11/16/21 78 Overlay - AC Structural 1/1/10 Valley Rd 4470 Valley Rd Sea Bluff Dr Victoria St AAC E 1 598 37 22,126 11/16/21 79 Overlay - AC Structural 1/1/10 Van Buren 10645 Van Buren Ave Paularino Ave Charleston St AAC E 14 1,485 36 53,239 11/16/21 86 Overlay - AC Structural 10/1/15 Vanguard 6570 Vanguard Way Newport Blvd (SB) Fair Dr AC E 24 2,270 60 136,200 12/15/21 87 Complete Reconstruction - AC 1/1/10 Vassar 6460 Vassar Pl Nassau Rd Cul-de-sac AC E 24 348 37 15,050 1/5/22 88 Surface Treatment - Slurry Seal 9/1/09 Vassar 7160 Vassar Pl Cul-de-sac Bucknell Rd AAC E 10 365 37 15,679 11/10/21 95 Overlay - AC Structural 7/1/09 Velasco 10260 Velasco Ln Sonara Rd Saint Clair St AAC E 20 910 37 34,170 11/22/21 82 Overlay - AC Structural 4/1/06 Velasco 10264 Velasco Ln Magellan St Sonora Rd AAC E 20 240 37 8,880 11/22/21 80 Overlay - AC Structural 7/1/08 Venetian 11240 Venetian Dr Damascus Cir Cannonade Cir AAC E 27 270 37 9,990 10/27/21 93 2 in Cold Mill & Overlay 1/8/19 Vermont 8940 Vermont Ave Gisler Ave New Jersey St AAC E 17 330 37 12,210 3/3/22 100 Overlay - AC Structural 3/3/22 VictoriaPl 4490 Victoria Pl Pacific Ave Victoria St AAC E 18 299 37 10,313 11/9/21 81 Overlay - AC Structural 10/1/15 VictoriaPl 4970 Victoria Pl Newport Blvd Victoria St AC E 5 348 31 10,788 11/12/21 89 Surface Treatment - Slurry Seal 12/1/19 VictoriaFR 4550 Victoria St Frontage Road W'ly Cul-de-sac E'ly Cul-de-sac AC E 1 2,177 37 84,897 11/16/21 66 New Construction - Initial 1/1/00 Village 9330 Village Way Harbor Blvd Pinecreek Dr AC E 15 1,491 37 55,167 10/29/21 98 2 in Cold Mill & Overlay 1/8/19 Villanova 6430 Villanova Rd Fordham Dr Fair Dr AC E 24 2,386 37 88,282 11/10/21 100 Surface Treatment - Slurry Seal 6/1/21 Viola 3250 Viola Pl 18th St Cul-de-sac AAC E 7 320 33 12,734 7/9/22 100 Overlay - AC Structural 7/9/22
259
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, Name Order (A-Z)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Vireo 7590 Vireo Cir Hummingbird Dr Cul-de-sac AC E 11 240 37 11,054 10/6/21 91 New Construction - Initial 1/1/00 Virginia 6580 Virginia Pl Newport Blvd Santa Ana Ave AC E 25 2,658 37 98,346 10/7/21 62 Surface Treatment - Slurry Seal 1/1/17 Visalia 11070 Visalia Dr San Leandro Ln Redding Ave AC E 14 996 37 38,352 10/27/21 77 Surface Treatment - Slurry Seal 1/1/18 Vistabaya 20010 Vista Baya Santa Ana Ave CDS AC E 557 37 23,189 10/7/21 75 Surface Treatment - Slurry Seal 1/1/17 WakeForest 6310 Wake Forest Rd W'ly End Fairview Rd AC E 24 2,303 37 85,730 11/10/21 100 Surface Treatment - Slurry Seal 6/1/21 Wakeham 11008 Wakeham Pl Cul-de-sac Bear St AAC E 27 1,290 37 49,904 10/22/21 45 2 in Cold Mill & Overlay 1/1/18 Wallace 3130 Wallace Ave Shalimar Dr 18th St AAC E 7 485 37 17,945 11/15/21 99 Overlay - AC Structural 1/1/21 Wallace 3135 Wallace Ave 18th St 19th St AAC E 7 1,320 37 48,840 11/15/21 99 Surface Treatment - Slurry Seal 6/1/21 Wallace 3140 Wallace Ave 19th St Hamilton St AC E 2 2,650 37 98,050 11/12/21 72 New Construction - Initial 1/1/00 Wallace 4640 Wallace Ave Hamilton St Cul-de-sac AC E 2 590 37 24,004 11/12/21 92 Surface Treatment - Slurry Seal 12/1/19 Wallace 5920 Wallace Ave Congress St Wilson St AC E 19 659 37 24,383 11/9/21 60 Complete Reconstruction - AC 2/1/07 Walnut Pl 5140 Walnut Pl Tustin Ave Esther Pl AAC E 4 650 35 22,750 11/10/21 86 Overlay - AC Structural 4/1/12 Walnut Pl 5260 Walnut Pl Irvine Ave Aliso Ave AAC E 4 535 35 18,725 11/9/21 87 Overlay - AC Structural 4/1/12 Walnut St 5080 Walnut St Newport Blvd Fullerton Ave AAC E 3 670 37 24,790 11/10/21 87 Overlay - AC Structural 4/1/12 Walnut St 5120 Walnut St Orange Ave Santa Ana Ave AAC E 3 1,316 37 48,692 11/10/21 89 Overlay - AC Structural 4/1/12 Walnut St 5130 Walnut St Santa Ana Ave Tustin Ave AAC E 4 1,324 37 48,988 11/10/21 90 Overlay - AC Structural 4/1/12 Warren 9420 Warren Ln Baker St Stonefield St AC E 15 1,857 37 68,709 11/15/21 75 Surface Treatment - Slurry Seal 3/20/16 Washington 8950 Washington Ave Gisler Ave California St AAC E 17 1,406 37 53,880 10/3/23 100 Overlay - AC Structural 10/3/23 Waterman 6640 Waterman Way Cul-de-sac 23rd St AAC E 25 245 37 11,239 10/7/21 87 Surface Treatment - Slurry Seal 1/1/17 Watson 9470 Watson Ave Loren Ln Dublin St AC E 15 3,083 37 114,071 11/15/21 80 Surface Treatment - Slurry Seal 3/20/16 Waxwing 7610 Waxwing Ct Hummingbird Dr Cul-de-sac AAC E 11 385 37 16,419 10/6/21 80 Overlay - AC Structural 10/1/15 Weelo 3370 Weelo Dr Wallace Ave Pomona Ave AC E 7 654 33 21,582 10/1/21 100 Surface Treatment - Slurry Seal 6/1/21 Wellesley 7280 Wellesley Ln Columbia Dr Cul-de-sac AAC E 10 372 33 14,450 11/10/21 74 Overlay - AC Structural 11/1/06 Wells 3520 Wells Pl Cabrillo St Fullerton Ave AAC E 8 406 37 15,022 11/29/21 89 Overlay - AC Structural 1/1/10 Westbrook 7230 Westbrook Pl Fordham Dr Princeton Dr AC E 10 534 37 19,758 11/10/21 89 Surface Treatment - Slurry Seal 9/1/09 WstmnstrAv 2410 Westminster Ave 15th St Knox Pl AAC E 8 970 35 33,950 10/15/21 76 Overlay - AC Structural 4/1/12 WstmnstrAv 2710 Westminster Ave 16th St Alley #53 AAC E 8 830 37 30,710 10/15/21 81 Overlay - AC Structural 4/1/12 WstmnstrAv 4180 Westminster Ave 17th St 19th St AAC E 8 2,670 37 98,790 11/29/21 82 Overlay - AC Structural 4/1/12 WstmnstrAv 5040 Westminster Ave Costa Mesa St Walnut St AAC E 3 321 37 11,877 11/19/21 84 Overlay - AC Structural 4/1/12 WstmnstrAv 5050 Westminster Ave Walnut St 20th St AAC E 3 655 18 11,790 11/19/21 65 Overlay - AC Structural 4/1/12 WstmnstrAv 5370 Westminster Ave Sierks St 21st St AAC E 3 990 37 36,630 11/9/21 78 Overlay - AC Structural 4/1/12 WstmnstrAv 5570 Westminster Ave 21st St Rose Ln AC E 3 783 37 28,971 10/7/21 62 Surface Treatment - Slurry Seal 3/20/16 WstmnstrAv 6680 Westminster Ave 23rd St Wilson St AAC E 25 803 37 29,711 10/7/21 88 Surface Treatment - Slurry Seal 1/1/17 WstmnstrAv 6810 Westminster Ave Wilson St Santa Isabel Ave AAC E 25 532 37 19,684 10/5/21 83 Surface Treatment - Slurry Seal 1/1/17 WstmnstrAv 6960 Westminster Ave Monte Vista Ave Del Mar Ave AC E 26 1,323 34 44,982 10/5/21 89 Surface Treatment - Slurry Seal 1/1/17 WstmnstrPl 6970 Westminster Pl Del Mar Ave Cul-de-sac AC E 26 529 33 19,631 10/5/21 66 Surface Treatment - Slurry Seal 1/1/17 White Oak 8450 White Oak St Jacaranda Ave Redwood Ave AC E 21 540 38 20,552 10/15/21 48 Surface Treatment - Slurry Seal 1/1/10 Whittier 2840 Whittier Ave S'ly End 19th St AC E 6 3,300 36 118,800 10/1/21 89 Surface Treatment - Slurry Seal 3/15/22 Whittier 2850 Whittier Ave 19th St Cul-de-sac AAC E 1 773 37 30,775 10/1/21 91 Overlay - AC Structural 3/20/16 Wilson 5780 Wilson St Pacific Ave State Ave AC E 18 1,000 37 37,000 11/9/21 91 Surface Treatment - Slurry Seal 10/6/15 Wilson 5790 Wilson St State Ave Placentia Ave AC E 18 2,422 37 92,885 11/9/21 82 Surface Treatment - Slurry Seal 10/6/15 Wilson 5860 Wilson St Fairview Rd Newport Blvd AC E 24 690 37 25,806 9/19/23 100 Asphalt Rubber Hot Mix 9/19/23 Wilson 6720 Wilson St Newport Blvd Orange Ave AAC E 25 1,326 37 49,062 9/17/21 67 Surface Treatment - Slurry Seal 1/1/17 Wilson 6730 Wilson St Orange Ave Santa Ana Ave AAC E 25 1,320 37 48,840 9/17/21 98 2 in Cold Mill & Overlay 1/8/19 Wimbledon 11010 Wimbledon Way South Coast Dr Sunflower Ave AC E 14 2,440 37 90,280 10/27/21 81 Surface Treatment - Slurry Seal 1/1/18 Wintergrn 8630 Wintergreen Pl Coral Ave Mace Ave AAC E 23 900 37 33,300 11/16/21 86 Surface Treatment - Slurry Seal 1/1/10 Wisteria 11420 Wisteria Cir Dahlia Ave Cul-de-sac AC E 27 520 37 21,414 10/29/21 88 Surface Treatment - Slurry Seal 1/1/18 Woodland 5288 Woodland Pl Cul-de-sac Tustin Ave AAC E 4 740 37 29,554 10/8/21 89 Overlay - AC Structural 2/1/12 Woodland 5290 Woodland Pl Tustin Ave Cul-de-sac AAC E 4 450 37 18,824 11/19/21 83 Overlay - AC Structural 4/1/12 Wren 7490 Wren Cir Cardinal Dr Cul-de-sac AAC E 11 190 37 9,204 10/4/21 90 Overlay - AC Structural 10/1/15 Wyoming 9220 Wyoming Cir New Hampshire Dr Cul-de-sac AAC E 17 463 37 19,305 10/3/23 100 Overlay - AC Structural 10/3/23 Yale 7270 Yale Pl Princeton Dr Bowling Green Dr AAC E 10 290 37 10,730 11/10/21 85 Overlay - AC Structural 9/1/07 Yellowstn 11560 Yellowstone Dr Paularino Ave Olympic Ave AAC E 31 1,569 37 57,803 10/29/21 71 Overlay - AC Structural 10/1/15 Yorkshire 4780 Yorkshire St Anahiem Ave Maple Ave AAC E 2 450 33 14,850 11/12/21 93 Surface Treatment - Slurry Seal 12/1/19 Yukon Ave 10915 Yukon Ave Bear St Cul-de-sac AC E 13 1,990 37 75,804 11/1/21 99 Surface Treatment - Slurry Seal 6/1/21 Yukon Cir 10920 Yukon Cir Cul-de-sac Yukon Ave AC E 13 130 37 6,984 11/1/21 100 Surface Treatment - Slurry Seal 6/1/21 156.8 31,762,613
260
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, PCI Order (0-100)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Arterials / Collectors
Sunflower 817 Sunflower Ave Park Center Dr Bristol St AAC A 28 536 36 27,340 2/15/24 54 Overlay - AC Structural 10/1/06 SouthCoast 731 South Coast Dr Fairview Rd Susan St AC P 30 1,963 33 64,779 1/16/24 57 Surface Treatment - Slurry Seal 1/1/00 Gisler 8830 Gisler Ave W'ly End Country Club Dr AC S 17 2,450 50 122,500 1/18/24 63 Surface Treatment - Slurry Seal 10/6/15 Fairview 552 Fairview Rd Sunflower Ave N'ly City Limits AAC A 178 64 11,392 2/22/24 65 Overlay - AC Structural 3/1/16 Fairview 501 Fairview Rd Merrimac Way Fair Dr AC A 10 1,300 35 44,850 1/10/24 67 Complete Reconstruction - AC 7/1/01 Baker 640 Baker St Mesa Verde Dr Harbor Blvd AC S 21 2,900 60 174,000 1/23/24 69 Surface Treatment - Slurry Seal 3/15/22 SouthCoast 730 South Coast Dr Harbor Blvd Fairview Rd AC P 30 3,570 33 117,810 1/16/24 69 Surface Treatment - Slurry Seal 1/1/00 Del Mar 6990 Del Mar Ave N/B Newport Blvd Elden Ave AAC P 26 670 90 59,800 2/21/24 70 Overlay - AC Structural 4/1/15 Harbor 380 Harbor Blvd Sunflower Ave MacArthur Ave AC A 30 2,315 40 92,600 1/11/24 71 New Construction - Initial 1/1/00 Main 11760 Main St CL SR-55 Sunflower Ave AC A 28 780 70 54,600 2/22/24 71 New Construction - Initial 1/1/00 Fairview 491 Fairview Rd Fair Dr Wake Forest Rd AAC A 24 1,961 35 68,635 1/10/24 72 2 in overlay 7/1/04 Harbor 361 Harbor Blvd South Coast Dr I-405 AAC A 30 885 40 35,400 1/11/24 73 Overlay - AC Structural 4/1/13 NewportNB 260 Newport Blvd North Bound Santa Isabel Ave Monte Vista Ave AAC S 24 1,310 37 48,470 2/28/24 73 Overlay - AC Structural 4/1/13 Sunflower 780 Sunflower Ave Harbor Blvd Fairview Rd AC P 30 2,590 33 83,070 2/22/24 73 New Construction - Initial 1/1/00 Sunflower 801 Sunflower Ave Bristol St Bear St AAC A 27 1,990 36 94,669 2/15/24 73 Overlay - AC Structural 10/1/06 19th 4150 19th St Fullerton Ave Orange Ave AAC C 8 680 36 24,465 2/27/24 74 Overlay - AC Structural 4/1/12 Bristol 821 Bristol St Red Hill Ave E'ly City Limits (w/o Irvine Ave) AC P 29 1,450 42 60,900 2/21/24 74 6 in Cold Mill & Overlay in Secure area 8/1/13 Hyland 9710 Hyland Ave South Coast Dr Sunflower Ave AAC P 30 1,332 60 79,920 1/11/24 74 Overlay - AC Structural 1/1/09 NewportSB 15416 Newport Blvd South Bound Fair Dr Vanguard Way AC S 24 2,645 32 84,980 2/27/24 74 New Construction - Initial 1/1/00 NewportSB 253 Newport Blvd South Bound 55 FWY SB Off Ramp Merge Victoria St AC S 5 940 47 46,255 2/27/24 74 New Construction - Initial 1/1/00 Sunflower 790 Sunflower Ave Fairview Rd Wimbledon Wy AC P 27 1,095 60 76,039 1/16/24 74 New Construction - Initial 1/1/00 17th 2895 17th St 615' e/o Pomona Ave Superior Ave AC P 7 600 54 32,400 1/30/24 75 New Construction - Initial 1/1/00 Harbor 371 Harbor Blvd Sunflower Ave South Coast Dr AC A 30 1,460 40 58,400 1/11/24 75 New Construction - Initial 1/1/00 NewportSB 261 Newport Blvd South Bound Mesa Dr Fair Dr AC S 24 1,315 44 63,660 2/27/24 75 New Construction - Initial 1/1/00 SouthCoast 720 South Coast Dr Hyland Ave 650' w/o Harbor Blvd AAC P 30 1,000 51 51,000 1/11/24 75 Overlay-Rubber Hot Mix 11/15/19 SouthCoast 732 South Coast Dr Susan St Harbor Blvd AC P 30 1,610 33 53,130 1/16/24 75 Surface Treatment - Slurry Seal 1/1/00 Sunflower 781 Sunflower Ave Fairview Rd Harbor Blvd AC P 30 2,590 33 85,470 1/18/24 75 New Construction - Initial 1/1/00 Sunflower 792 Sunflower Ave Fuschia St Bear St AC P 27 2,035 60 140,031 1/16/24 75 New Construction - Initial 1/1/00 Baker 655 Baker St Loren Ln Fairview Rd AC P 21 515 80 40,255 2/14/24 76 Complete Reconstruction - AC 2/1/03 Bristol 830 Bristol St Santa Ana Ave Newport Blvd (NB) AC A 29 2,243 47 101,256 2/21/24 76 Overlay-Rubber Hot Mix 12/31/21 Fairview 490 Fairview Rd Wilson St Fair Dr AC A 24 2,760 35 106,978 1/10/24 76 New Construction - Initial 1/1/00 Fairview 516 Fairview Rd Adams Ave Arlington Dr AC A 10 2,603 35 88,905 1/10/24 76 Complete Reconstruction - AC 7/1/01 NewportNB 270 Newport Blvd North Bound Mesa Dr Bristol St AC S 10 2,964 37 109,668 2/21/24 76 New Construction - Initial 1/1/00 NewportSB 251 Newport Blvd South Bound Vanguard Way Wilson St AC S 5 780 30 28,500 2/27/24 76 New Construction - Initial 1/1/00 VictoriaSt 15418 Victoria St Doctors Cir Newport Blvd SB AAC S 5 1,255 60 76,389 1/9/24 76 Overlay - AC Structural 2/1/14 VictoriaSt 411 Victoria St National Ave Canyon Dr AAC S 18 2,155 34 73,270 2/14/24 76 Overlay - AC Structural 4/1/15 17th 2901 17th St Newport Blvd Superior Ave AC P 8 452 47 21,244 2/28/24 77 New Construction - Initial 1/1/80 19th 4141 19th St Fullerton Ave Newport Blvd AAC C 8 680 35 23,800 2/27/24 77 Overlay - AC Structural 4/12/12 Fairview 530 Fairview Rd Baker St S'ly edge of Bridge over I-405 AC A 15 2,665 35 93,275 1/23/24 77 New Construction - Initial 1/1/00 Harbor 311 Harbor Blvd Fair Dr Wilson St AC A 24 2,570 40 102,800 1/9/24 77 New Construction - Initial 1/1/00 NewportNB 15412 Newport Blvd North Bound Wilson St Santa Isabel Ave AAC S 5 515 34 18,495 2/28/24 77 Overlay - AC Structural 4/1/13 NewportNB 15413 Newport Blvd North Bound Monte Vista Ave Del Mar Ave AAC S 24 1,349 37 49,913 2/28/24 77 Overlay - AC Structural 4/1/13 NewportNB 250 Newport Blvd North Bound 22nd St Wilson St AAC S 5 2,140 34 73,960 2/28/24 77 Overlay - AC Structural 4/1/13 Red Hill 11821 Red Hill Ave Kalmus Dr Bristol Ave AC P 29 2,340 28 72,778 2/21/24 78 6 in Cold Mill & Overlay in Secure area 8/1/13 VictoriaSt 400 Victoria St Valley Rd Canyon Dr AAC S 1 700 68 47,600 2/14/24 78 Overlay - AC Structural 4/1/15 Fairview 515 Fairview Rd Arlington Dr Adams Ave AC A 10 2,603 35 88,905 1/10/24 79 Complete Reconstruction - AC 7/1/01 Harbor 341 Harbor Blvd Gisler Ave Baker Ave AAC A 15 2,525 40 101,000 1/9/24 79 Overlay - AC Structural 4/1/13 NewportNB 15414 Newport Blvd North Bound Del Mar Ave Mesa Dr AAC S 24 1,275 34 45,390 2/21/24 79 Overlay - AC Structural 4/1/13 NewportSB 15417 Newport Blvd South Bound Bay St Ford Rd AC S 5 1,436 32 45,895 2/27/24 79 New Construction - Initial 1/1/00 Sunflower 810 Sunflower Ave Bristol St Avenue of the Arts AAC A 28 1,360 36 48,960 2/15/24 79 Overlay - AC Structural 10/1/06 Baker 660 Baker St Fairview Rd Babb St (N) AAC P 15 2,572 60 171,444 1/23/24 80 Overlay - AC Structural 2/1/09 Gisler 8850 Gisler Ave Country Club Dr Harbor Blvd AAC S 17 3,400 56 190,400 1/18/24 80 Overlay - AC Structural 6/1/08 NewportSB 241 Newport Blvd South Bound Victoria St Bay St AC S 5 1,900 40 80,500 2/27/24 80 New Construction - Initial 1/1/00 NewportSB 271 Newport Blvd South Bound Bristol St Arlington Dr AC S 10 1,780 32 56,960 2/28/24 80 New Construction - Initial 1/1/00 17th 2991 17th St Orange Ave 200' w/o Fullerton Ave AC A 8 725 43 31,175 2/28/24 81 Overlay - AC Thin 8/1/04
261
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, PCI Order (0-100)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Anton 11710 Anton Blvd Bristol St Avenue of the Arts AAC A 28 1,360 33 44,880 2/15/24 81 Overlay - AC Structural 6/1/06 Bristol 831 Bristol St Newport Blvd (NB) Santa Ana Ave AC A 29 2,250 47 113,074 2/21/24 81 Overlay-Rubber Hot Mix 12/31/21 Fairview 531 Fairview Rd S'ly edge of Bridge over I-405 Baker St AC A 15 2,665 35 89,475 1/23/24 81 New Construction - Initial 1/1/00 Fairview 550 Fairview Rd South Coast Dr Sunflower Ave AC A 30 1,600 37 59,200 3/26/24 81 New Construction - Initial 1/1/00 Mesa Verde 151 Mesa Verde Dr Country Club Dr Adams Ave (W) AC P 21 3,765 24 90,360 1/18/24 81 Surface Treatment - Slurry Seal 1/1/10 Mesa Verde 160 Mesa Verde Dr Country Club Dr Baker St AC P 21 1,055 24 25,320 1/25/24 81 Surface Treatment - Slurry Seal 1/1/10 Mesa Verde 161 Mesa Verde Dr Baker St Country Club Dr AC P 21 1,055 24 25,320 1/25/24 81 Surface Treatment - Slurry Seal 1/1/10 SouthCoast 761 South Coast Dr Bear St San Leandro Ln AC P 27 2,800 38 106,400 1/16/24 81 Complete Reconstruction - AC 1/1/10 Sunflower 812 Sunflower Ave Avenue of the Arts Anton Blvd AAC A 28 2,750 36 99,000 2/15/24 81 2 in overlay 8/1/09 Anton 11711 Anton Blvd Avenue of the Arts Bristol St AAC A 28 1,360 33 44,880 2/15/24 82 Overlay - AC Structural 6/1/06 Fair 570 Fair Dr Fairview Rd S/B Newport Blvd AAC P 10 2,960 60 177,600 1/9/24 82 Overlay - AC Structural 9/1/04 Fairview 492 Fairview Rd Wake Forest Rd Wilson St AAC A 24 792 35 27,720 1/10/24 82 2 in overlay 7/1/04 Hyland 9720 Hyland Ave Sunflower Ave Mac Arthur Blvd AAC P 30 2,347 66 151,402 1/11/24 82 Overlay - AC Structural 1/1/09 17th 2870 17th St Monrovia Ave Placentia Ave AC S 6 1,320 36 47,520 1/30/24 83 Complete Reconstruction - AC 10/1/04 17th 2900 17th St Superior Ave Newport Blvd AC P 8 452 47 21,244 2/28/24 83 New Construction - Initial 1/1/00 19th 4140 19th St Newport Blvd Fullerton Ave AAC C 8 680 35 23,800 2/27/24 83 Overlay - AC Structural 4/12/12 22nd 460 22nd St Newport Blvd Orange Ave AC C 3 1,341 36 48,276 2/27/24 83 Surface Treatment - Slurry Seal 3/20/16 Harbor 300 Harbor Blvd Victoria St Wilson St AAC A 5 1,321 40 52,390 1/9/24 83 Overlay - AC Structural 5/1/09 Harbor 322 Harbor Blvd Merrimac Way Fair Dr AC A 10 1,862 40 74,480 1/10/24 83 New Construction - Initial 1/1/00 Mesa Verde 170 Mesa Verde Dr Baker St Adams Ave (E) AC P 21 2,555 24 61,320 1/25/24 83 Surface Treatment - Slurry Seal 1/1/10 Sunflower 791 Sunflower Ave Wimbledon Wy Fuschia St AC P 27 1,735 60 102,478 1/16/24 83 New Construction - Initial 1/1/00 Sunflower 811 Sunflower Ave Main St Avenue of the Arts AC A 28 3,850 36 138,600 2/15/24 83 New Construction - Initial 1/1/00 17th 2860 17th St W'ly End Monrovia Ave AC S 6 1,670 36 60,120 3/26/24 84 Complete Reconstruction - AC 2/1/06 19th 3460 19th St Pomona Ave Anaheim Ave AC P 2 1,305 36 46,980 1/31/24 84 New Construction - Initial 1/1/00 Baker 690 Baker St Bristol St Newport Blvd (NB) AC A 12 2,150 40 86,000 2/28/24 84 Complete Reconstruction - AC 2/1/03 Fairview 551 Fairview Rd Sunflower Ave South Coast Dr AAC A 30 1,600 37 59,200 1/16/24 84 Overlay - AC Structural 4/1/15 Harbor 301 Harbor Blvd Wilson St Victoria St AAC A 5 1,321 40 52,840 1/9/24 84 Overlay - AC Structural 5/1/09 VictoriaSt 390 Victoria St E'ly edge of Bridge at SA River Valley Rd AAC P 1 1,300 65 84,500 2/14/24 84 Overlay - AC Structural 4/1/15 19th 3470 19th St Anaheim Ave Park Ave AC P 2 650 36 23,400 1/31/24 85 Overlay - AC Thin 5/1/07 Baker 691 Baker St Newport Blvd (NB) Bristol St AC A 13 2,150 40 86,000 2/28/24 85 New Construction - Initial 1/1/80 Bristol 880 Bristol St Anton Blvd Sunflower Ave AAC A 27 1,475 34 49,413 1/18/24 85 Overlay - AC Structural 10/1/06 Fairview 481 Fairview Rd Wilson St Newport Blvd (SB) AAC A 5 1,086 28 30,408 1/9/24 85 Overlay - AC Structural 2/1/03 Harbor 321 Harbor Blvd Adams Ave Merrimac Way AC A 10 1,802 40 72,080 1/9/24 85 New Construction - Initial 1/1/00 Harbor 351 Harbor Blvd I-405 Gisler Ave AAC A 15 790 40 31,600 1/25/24 85 Overlay - AC Structural 4/1/13 Mesa Verde 171 Mesa Verde Dr Adams Ave (E) Baker St AC P 21 2,555 24 61,320 1/25/24 85 Surface Treatment - Slurry Seal 1/1/10 Red Hill 11823 Red Hill Ave Paularino Ave Kalmus Dr AC P 29 3,275 28 109,914 2/21/24 85 6 in Cold Mill & Overlay in Secure area 8/1/13 SouthCoast 724 South Coast Dr 650' w/o Harbor Blvd Harbor Blvd AAC P 30 680 66 44,880 1/11/24 85 Overlay-Rubber Hot Mix 11/15/19 Adams 611 Adams Ave Harbor Blvd Royal Palm Dr AC A 21 810 47 38,070 2/14/24 86 New Construction - Initial 1/1/80 Bristol 881 Bristol St Sunflower Ave Anton Blvd AAC A 27 1,475 34 48,613 1/18/24 86 Overlay - AC Structural 10/1/06 Fairview 511 Fairview Rd Arlington Dr Merrimac Way AC A 10 510 35 17,595 1/10/24 86 Complete Reconstruction - AC 7/1/01 Harbor 290 Harbor Blvd 19th St Bay St AAC A 5 1,995 40 69,746 1/9/24 86 Overlay - AC Structural 5/1/09 Harbor 310 Harbor Blvd Wilson St Fair Dr AC A 24 2,570 40 102,100 1/9/24 86 New Construction - Initial 1/1/00 Harbor 331 Harbor Blvd Baker Ave Adams Ave AC A 15 2,450 40 98,000 1/9/24 86 New Construction - Initial 1/1/00 Harbor 340 Harbor Blvd Baker Ave Gisler Ave AAC A 15 2,525 40 101,000 1/25/24 86 Overlay - AC Structural 4/1/13 NewportNB 15411 Newport Blvd North Bound Bay St 22nd St AC S 5 1,965 30 63,950 2/27/24 86 New Construction - Initial 1/1/00 NewportSB 15415 Newport Blvd South Bound Arlington Dr Mesa Dr AC S 10 1,274 44 57,785 2/27/24 86 New Construction - Initial 1/1/00 Red Hill 11830 Red Hill Ave Paularino Ave Airport Loop Dr AC P 29 2,210 40 88,400 2/21/24 86 Complete Reconstruction - AC 4/1/13 SouthCoast 740 South Coast Dr Fairview Rd Carmel Dr AC P 14 835 60 50,100 1/16/24 86 Surface Treatment - Slurry Seal 1/1/18 SouthCoast 760 South Coast Dr San Leandro Ln Bear St AC P 27 2,800 46 128,800 1/16/24 86 Complete Reconstruction - AC 1/1/10 Sunflower 770 Sunflower Ave Harbor Blvd Hyland Ave AC P 30 1,700 60 99,300 1/11/24 86 Complete Reconstruction - AC 7/1/00 Sunflower 800 Sunflower Ave Bear St Bristol St AAC A 27 1,990 36 99,843 1/18/24 86 Overlay - AC Structural 10/1/06 19th 3425 19th St W'ly City Limits Parkcrest Dr AC P 6 360 42 15,120 1/30/24 87 Surface Treatment - Slurry Seal 1/1/24 Anton 11720 Anton Blvd Sakioka Dr Sunflower Ave AC A 28 2,730 33 90,090 1/18/24 87 New Construction - Initial 1/1/00 Harbor 350 Harbor Blvd Gisler Ave I-405 AAC A 15 790 40 31,600 1/25/24 87 Overlay - AC Structural 4/1/13 Harbor 370 Harbor Blvd South Coast Dr Sunflower Ave AC A 30 1,460 40 58,400 1/11/24 87 New Construction - Initial 1/1/00 Harbor 381 Harbor Blvd MacArthur Ave Sunflower Ave AC A 30 2,315 40 92,600 1/11/24 87 New Construction - Initial 1/1/00
262
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, PCI Order (0-100)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date NewportSB 252 Newport Blvd South Bound Wilson St 55 FWY SB Off Ramp Merge AC S 5 870 30 20,095 1/9/24 87 New Construction - Initial 1/1/00 Paularino 11590 Paularino Ave Bristol St N/B Newport Blvd AC P 12 2,760 60 163,200 2/22/24 87 Complete Reconstruction - AC 10/1/03 Sunflower 814 Sunflower Ave Anton Blvd Main St AC A 28 1,125 36 40,500 2/15/24 87 New Construction - Initial 1/1/00 19th 3461 19th St Anaheim Ave Pomona Ave AC P 2 1,305 36 46,980 1/31/24 88 New Construction - Initial 1/1/80 Fairview 541 Fairview Rd South Coast Dr N'ly edge of Bridge over I-405 AAC A 30 1,130 37 41,810 1/23/24 88 Overlay - AC Structural 4/1/15 Harbor 360 Harbor Blvd I-405 South Coast Dr AAC A 30 885 40 35,400 1/25/24 88 Overlay - AC Structural 4/1/13 Red Hill 11820 Red Hill Ave Bristol Ave Kalmus Dr AC P 29 2,372 28 76,031 2/21/24 88 6 in Cold Mill & Overlay in Secure area 8/1/13 Red Hill 11831 Red Hill Ave Airport Loop Dr Paularino Ave AC P 29 2,210 40 88,400 2/21/24 88 Complete Reconstruction - AC 4/1/13 VictoriaSt 421 Victoria St Placentia Ave National Ave AAC S 18 1,470 34 49,980 2/14/24 88 Overlay - AC Structural 2/1/14 VictoriaSt 450 Victoria St Harbor Blvd Doctors Cir AAC S 5 1,840 60 114,552 1/9/24 88 Overlay - AC Structural 2/1/14 Anton 11721 Anton Blvd Sunflower Ave Sakioka Dr AC A 28 2,730 33 90,090 1/18/24 89 New Construction - Initial 1/1/00 Baker 670 Baker St Babb St (N) Bear St AAC P 16 1,400 74 110,056 1/23/24 89 Overlay - AC Structural 2/1/09 Baker 681 Baker St Bristol St Bear St AAC A 13 2,685 44 118,140 2/28/24 89 Overlay - AC Structural 9/15/15 Bristol 843 Bristol St NB Newport Blvd Off Ramp SB Newport Blvd On Ramp AAC A 835 35 39,545 2/21/24 89 Asphalt Rubber Hot Mix 7/19/22 Bristol 866 Bristol St S'ly Edge of Bridge over I-405 Paularino Ave AC A 12 1,680 34 56,280 2/22/24 89 New Construction - Initial 1/1/00 Del Mar 6995 Del Mar Ave Elden Ave Orange Ave AAC P 26 650 37 24,050 2/21/24 89 Overlay - AC Structural 12/1/15 Fairview 510 Fairview Rd Merrimac Way Arlington Dr AC A 10 510 35 17,595 1/10/24 89 Complete Reconstruction - AC 7/1/01 Harbor 320 Harbor Blvd Fair Dr Merrimac Way AC A 10 1,863 40 74,520 1/10/24 89 New Construction - Initial 1/1/00 NewportNB 240 Newport Blvd North Bound Walnut St Bay St AC S 5 1,518 32 48,653 2/27/24 89 New Construction - Initial 1/1/00 SouthCoast 750 South Coast Dr Carmel Dr San Leandro Ln AC P 14 1,590 60 95,400 1/16/24 89 Surface Treatment - Slurry Seal 1/1/18 Superior 2950 Superior Ave S'ly City Limits (450' s/o 16th St) Industrial Way AAC P 7 430 78 33,540 2/28/24 89 Overlay - AC Structural 11/1/08 VictoriaSt 410 Victoria St Canyon Dr National Ave AC S 18 2,155 34 73,270 2/14/24 89 New Construction - Initial 1/1/00 19th 3471 19th St Park Ave Anaheim Ave AC P 2 650 36 23,400 1/31/24 90 Overlay - AC Thin 5/1/07 Baker 700 Baker St Newport Blvd (NB) Red Hill Ave AC A 29 1,050 40 42,000 2/28/24 90 6 in Cold Mill & Overlay in Secure area 8/1/13 Bristol 860 Bristol St Baker St Paularino Ave AC A 12 820 34 27,470 2/22/24 90 New Construction - Initial 1/1/00 Bristol 861 Bristol St Paularino Ave Baker St AC A 12 820 34 27,470 2/22/24 90 New Construction - Initial 1/1/00 Bristol 871 Bristol St Anton Blvd N'ly Edge of Bridge over I-405 AC A 27 865 62 53,630 2/22/24 90 6 in Cold Mill & Overlay in Secure area 10/1/13 Del Mar 7000 Del Mar Ave Orange Ave Santa Ana Ave AAC P 26 1,310 37 48,470 2/21/24 90 Overlay - AC Structural 12/1/15 Mesa Verde 150 Mesa Verde Dr Adams Ave (W) Country Club Dr AC P 21 3,765 24 90,360 1/25/24 90 Surface Treatment - Slurry Seal 1/1/10 Mesa Verde 180 Mesa Verde Dr Adams Ave (E) Harbor Blvd AAC P 11 2,453 60 147,180 1/30/24 90 Overlay - AC Structural 10/1/15 Sunflower 816 Sunflower Ave Avenue of the Arts Park Center Dr AAC A 28 795 36 33,570 2/15/24 90 Overlay - AC Structural 10/1/06 Superior 2960 Superior Ave Industrial Way E 17th St AAC P 7 1,745 55 95,975 2/28/24 90 Overlay - AC Structural 11/1/08 17th 2890 17th St Pomona Ave 615' e/o Pomona Ave AC P 7 615 54 33,210 1/30/24 91 Complete Reconstruction - AC 8/1/04 17th 2990 17th St 200' w/o Fullerton Ave Orange Ave AC A 8 725 43 31,175 2/28/24 91 Overlay - AC Thin 8/1/04 Anton 11716 Anton Blvd Sakioka Dr Avenue of the Arts AAC A 28 938 33 30,954 2/15/24 91 Overlay - AC Structural 2/1/14 Arlington 7300 Arlington Dr Fairview Rd Lane Change (2 lanes) AAC C 20 900 55 48,700 1/10/24 91 2 in Cold Mill & Overlay 12/10/18 Baker 680 Baker St Bear St Bristol St AC A 13 2,685 44 118,140 1/23/24 91 New Construction - Initial 1/1/00 Bristol 851 Bristol St Baker St Randolph Ave AAC A 12 1,275 47 59,925 2/22/24 91 Overlay - AC Structural 10/13/17 Bristol 865 Bristol St Paularino Ave S'ly Edge of Bridge over I-405 AC A 12 1,680 34 56,280 2/22/24 91 New Construction - Initial 1/1/00 Bristol 870 Bristol St N'ly Edge of Bridge over I-405 Anton Blvd AC A 27 865 62 53,630 2/22/24 91 6 in Cold Mill & Overlay in Secure area 10/1/13 Fairview 500 Fairview Rd Fair Dr Merrimac Way AC A 10 1,300 35 43,750 1/10/24 91 Complete Reconstruction - AC 7/1/01 Harbor 280 Harbor Blvd Newport Blvd 19th St AAC A 5 820 37 28,740 1/9/24 91 Overlay - AC Structural 5/1/09 Harbor 291 Harbor Blvd Victoria St 19th St AAC A 3,330 40 125,749 1/9/24 91 Overlay - AC Structural 5/1/09 Harbor 295 Harbor Blvd Bay St Victoria St AAC A 5 1,315 40 52,600 1/9/24 91 Overlay - AC Structural 5/1/09 Harbor 325 Harbor Blvd Merrimac Way Adams Ave AC A 10 1,801 40 72,040 1/11/24 91 New Construction - Initial 1/1/00 Santa Ana 2540 Santa Ana Ave Del Mar Ave Mesa Dr AC S 26 1,330 36 47,880 2/21/24 91 Surface Treatment - Slurry Seal 1/1/17 VictoriaSt 420 Victoria St National Ave Placentia Ave AAC S 18 1,470 34 49,980 2/14/24 91 Overlay - AC Structural 2/1/14 19th 3480 19th St Park Ave Harbor Blvd AC P 2 665 35 23,275 2/27/24 92 6 in Cold Mill & Overlay in Secure area 9/1/13 22nd 470 22nd St Orange Ave Santa Ana Ave AC C 3 1,326 36 47,736 2/14/24 92 Surface Treatment - Slurry Seal 12/1/19 Baker 650 Baker St Harbor Blvd Loren Ln AC P 21 2,870 60 191,665 1/11/24 92 Complete Reconstruction - AC 2/1/03 Bristol 820 Bristol St E'ly City Limits (w/o Irvine Ave) Red Hill Ave AC P 29 1,440 42 60,480 2/22/24 92 6 in Cold Mill & Overlay in Secure area 8/1/13 Harbor 281 Harbor Blvd 19th St Newport Blvd AAC A 5 820 37 28,740 1/9/24 92 Overlay - AC Structural 5/1/09 Paularino 11890 Paularino Ave N/B Newport Blvd Red Hill Ave AC P 29 1,110 60 66,600 1/23/24 92 6 in Cold Mill & Overlay in Secure area 8/1/13 VictoriaSt 430 Victoria St Placentia Ave Pomona Ave AAC S 2 1,320 68 89,760 1/31/24 92 Overlay - AC Structural 2/1/14 VictoriaSt 440 Victoria St Pomona Ave Harbor Blvd AAC S 2 2,625 68 178,500 1/31/24 92 Overlay - AC Structural 2/1/14 19th 3481 19th St Harbor Blvd Park Ave AC P 2 665 35 23,275 2/27/24 93 6 in Cold Mill & Overlay in Secure area 9/1/13
263
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, PCI Order (0-100)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date 19th 3491 19th St Newport Blvd Harbor Blvd AC P 5 720 35 25,200 2/27/24 93 6 in Cold Mill & Overlay in Secure area 9/1/13 Adams 610 Adams Ave Royal Palm Dr Harbor Blvd AC A 21 810 47 38,070 2/14/24 93 New Construction - Initial 1/1/00 Arlington 7310 Arlington Dr Lane Change (2 lanes) Newport Blvd AAC C 20 3,730 42 103,055 1/10/24 93 2 in Cold Mill & Overlay 12/10/18 Bear 11000 Bear St S'ly Edge of Bridge over I-405 Sunflower Ave AC A 27 2,330 36 114,710 1/16/24 93 New Construction - Initial 1/1/00 Bristol 850 Bristol St Randolph Ave Baker St AAC A 12 1,275 47 59,925 2/22/24 93 Overlay - AC Structural 9/22/17 Fair 560 Fair Dr Harbor Blvd Fairview Rd AAC P 10 3,530 60 211,800 1/9/24 93 Overlay - AC Structural 6/1/08 Fairview 540 Fairview Rd N'ly edge of Bridge over I-405 South Coast Dr AC A 30 1,130 37 41,810 1/23/24 93 New Construction - Initial 1/1/00 Red Hill 11822 Red Hill Ave Kalmus Dr Paularino Ave AC P 29 3,240 28 118,163 2/21/24 93 6 in Cold Mill & Overlay in Secure area 8/1/13 Sakioka 11750 Sakioka Dr Anton Blvd Sunflower Ave AAC P 28 1,475 32 47,200 1/18/24 93 Overlay - AC Structural 10/1/08 Sakioka 11751 Sakioka Dr Sunflower Ave Anton Ave AAC P 28 1,475 32 47,200 1/18/24 93 Overlay - AC Structural 10/1/08 17th 3000 17th St Orange Ave Santa Ana Ave AC A 8 1,455 61 88,755 1/30/24 94 Complete Reconstruction - AC 10/1/06 17th 3010 17th St Santa Ana Ave Tustin Ave AC A 9 1,320 57 75,240 1/30/24 94 Complete Reconstruction - AC 5/1/08 19th 4170 19th St Santa Ana Ave Irvine Ave AC C 9 2,599 35 85,985 1/30/24 94 Complete Reconstruction - AC 6/1/08 Adams 621 Adams Ave Fairview Rd Harbor Blvd AC A 15 3,642 35 145,550 1/10/24 94 Surface Treatment - Slurry Seal 12/1/00 Baker 701 Baker St Red Hill Ave Newport Blvd (NB) AC A 13 1,050 40 42,000 2/28/24 94 6 in Cold Mill & Overlay in Secure area 8/1/13 Bear 11001 Bear St Sunflower Ave S'ly Edge of Bridge over I-405 AC A 2,330 37 108,360 1/16/24 94 New Construction - Initial 1/1/80 Bear 11005 Bear St Sunflower Ave Wakeham Ave AC S 27 770 40 30,800 1/16/24 94 New Construction - Initial 1/1/00 Bear 11006 Bear St Wakeham Ave Sunflower Ave AC S 27 770 40 30,800 1/16/24 94 New Construction - Initial 1/1/80 Bristol 841 Bristol St SB Newport Blvd On Ramp 300' s/o Bear St AAC A 645 38 24,565 2/21/24 94 Overlay-Rubber Hot Mix 7/19/22 Fairview 525 Fairview Rd Paularino Channel Baker St AC A 15 930 35 32,550 1/11/24 94 Overlay-Rubber Hot Mix 1/1/21 Harbor 330 Harbor Blvd Adams Ave Baker Ave AC A 15 2,450 40 97,600 1/11/24 94 New Construction - Initial 1/1/00 17th 2880 17th St Placentia Ave Pomona Ave AC P 7 1,310 36 47,160 1/30/24 95 Complete Reconstruction - AC 9/1/04 17th 3020 17th St Tustin Ave Irvine Ave AC P 9 1,340 57 76,380 1/30/24 95 Complete Reconstruction - AC 5/1/08 19th 3430 19th St Parkcrest Dr Monrovia Ave AC P 1 1,710 46 78,660 1/30/24 95 Surface Treatment - Slurry Seal 1/1/24 19th 3440 19th St Monrovia Ave Placentia Ave AC P 1 1,320 46 60,720 1/30/24 95 Surface Treatment - Slurry Seal 1/1/24 19th 3450 19th St Placentia Ave Pomona Ave AC P 2 1,325 36 34,450 1/31/24 95 Surface Treatment - Slurry Seal 1/1/24 19th 3451 19th St Pomona Ave Placentia Ave AC P 2 1,325 36 47,700 1/31/24 95 Surface Treatment - Slurry Seal 1/1/24 19th 4160 19th St Orange Ave Santa Ana Ave AC C 8 1,278 36 46,070 1/30/24 95 Complete Reconstruction - AC 1/1/03 22nd 475 22nd St Santa Ana Ave Tustin Ave AAC C 1,283 37 51,266 2/14/24 95 Overlay - AC Structural 1/1/21 Adams 620 Adams Ave Harbor Blvd Fairview Rd AC A 15 3,644 34 150,416 1/10/24 95 Surface Treatment - Slurry Seal 12/1/00 Anton 11715 Anton Blvd Avenue of the Arts Sakioka Dr AAC A 28 938 33 30,954 2/15/24 95 Overlay - AC Structural 2/1/14 Bear 10990 Bear St Baker St On/Off Ramps SR-73 SB AC A 13 400 40 16,000 2/15/24 95 Overlay-Rubber Hot Mix 1/1/21 Bear 10991 Bear St On/Off Ramps SR-73 SB Baker St AC A 16 400 40 16,000 2/15/24 95 Overlay-Rubber Hot Mix 1/1/21 Bear 10995 Bear St On/Off Ramps SR-73 SB Yukon/Paularino Ave AC A 13 860 40 33,400 2/15/24 95 Overlay-Rubber Hot Mix 1/1/21 Bear 10996 Bear St Yukon/Paularino Ave On/Off Ramps SR-73 SB AC A 860 40 34,400 2/15/24 95 Overlay-Rubber Hot Mix 1/1/21 Bear 10997 Bear St Yukon/Paularino Ave S'ly Edge of Bridge over I-405 AC A 13 1,500 40 60,000 2/15/24 95 Overlay-Rubber Hot Mix 1/1/21 Bear 10998 Bear St S'ly Edge of Bridge over I-405 Yukon/Paularino Ave AC A 1,500 40 60,000 2/15/24 95 Overlay-Rubber Hot Mix 1/1/21 Bristol 840 Bristol St 300' s/o Bear St SB Newport Blvd On Ramp AC A 20 680 42 30,849 2/22/24 95 Overlay-Rubber Hot Mix 7/19/22 Bristol 842 Bristol St SB Newport Blvd On Ramp NB Newport Blvd Off Ramp AC A 20 835 38 35,900 2/22/24 95 Asphalt Rubber Hot Mix 7/19/22 Bristol 844 Bristol St 300' s/o Bear St Randolph Ave AC A 12 1,025 47 48,175 2/21/24 95 Overlay-Rubber Hot Mix 7/19/22 Bristol 855 Bristol St Randolph Ave 300' s/o Bear St AC A 1,025 47 48,175 2/22/24 95 Overlay-Rubber Hot Mix 12/31/21 Fairview 480 Fairview Rd Newport Blvd (SB) Wilson St AAC A 5 1,015 28 28,420 1/11/24 95 Overlay - AC Structural 2/1/03 Fairview 521 Fairview Rd Paularino Channel Adams Ave AC A 15 570 40 22,800 1/11/24 95 Overlay-Rubber Hot Mix 1/1/21 Fairview 526 Fairview Rd Baker St Paularino Channel AC A 15 930 35 32,550 1/11/24 95 Overlay-Rubber Hot Mix 1/1/21 Irvine 2801 Irvine Ave 330' n/o 20th St (Baycrest Rd) 20th St AC P 4 330 35 11,550 1/30/24 95 Asphalt Rubber Hot Mix 11/27/18 Irvine 2811 Irvine Ave 20th St 19th St AC P 4 1,330 33 43,890 1/30/24 95 Asphalt Rubber Hot Mix 11/27/18 Irvine 2821 Irvine Ave 19th St 17th St AC P 3 2,620 31 81,220 1/30/24 95 Asphalt Rubber Hot Mix 11/27/18 Irvine 2830 Irvine Ave 17th St 16th St AC P 3 1,300 48 62,400 1/30/24 95 Asphalt Rubber Hot Mix 11/27/18 MacArthur 9784 MacArthur Blvd 600' w/o Harbor Blvd Harbor Blvd AC A 30 600 75 45,000 1/11/24 95 Overlay-Rubber Hot Mix 11/15/19 MacArthur 9786 MacArthur Blvd 600' e/o Hyland Ave 600' w/o Harbor Blvd AC A 30 730 75 54,750 1/11/24 95 Overlay-Rubber Hot Mix 11/15/19 MacArthur 9788 MacArthur Blvd 600' w/o Hyland Ave 600' e/o Hyland Ave AC A 30 1,150 75 86,250 1/11/24 95 Overlay-Rubber Hot Mix 11/15/19 MacArthur 9790 MacArthur Blvd E'y edge of SA River Bridge 600' w/o Hyland Ave AAC P 30 580 75 43,500 1/11/24 95 Mill & Overlay - ARHM 11/15/19 Merrimac 7290 Merrimac Way Harbor Blvd Fairview Rd AC P 10 2,580 29 74,820 1/10/24 95 Overlay-Rubber Hot Mix 1/1/21 Placentia 100 Placentia Ave 19th St Victoria St AAC P 2 3,320 60 199,200 1/31/24 95 Overlay - AC Structural 5/1/07 Placentia 120 Placentia Ave Victoria St Wilson St AAC P 19 1,310 60 77,000 1/31/24 95 Overlay - AC Structural 5/1/07 Placentia 70 Placentia Ave Production Pl (s/o 16th St) 17th St AAC P 7 1,660 60 98,000 1/31/24 95 Surface Treatment - Slurry Seal 1/1/24
264
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, PCI Order (0-100)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Placentia 80 Placentia Ave 17th St 18th St AAC P 7 1,320 60 76,800 1/31/24 95 Surface Treatment - Slurry Seal 1/1/24 Placentia 90 Placentia Ave 18th St 19th St AC P 7 1,310 60 76,200 1/31/24 95 Surface Treatment - Slurry Seal 1/1/24 Red Hill 11824 Red Hill Ave Airport Loop Dr S'ly edge of Bridge over I-405 AC P 29 800 40 32,000 2/22/24 95 Complete Reconstruction - AC 4/1/13 Red Hill 11825 Red Hill Ave S'ly edge of Bridge over I-405 Airport Loop Dr AC P 29 800 40 32,000 2/22/24 95 Complete Reconstruction - AC 4/1/13 19th 3490 19th St Harbor Blvd Newport Blvd AC P 5 720 35 25,200 2/27/24 96 6 in Cold Mill & Overlay in Secure area 9/1/13 Fairview 520 Fairview Rd Adams Ave Paularino Channel AC A 15 570 40 22,800 2/14/24 96 Overlay-Rubber Hot Mix 1/1/21 17th 2980 17th St Newport Blvd 200' w/o Fullerton Ave AAC A 8 425 44 18,700 2/28/24 100 Mill & Overlay - ARHM 1/1/24 17th 2981 17th St 200' w/o Fullerton Ave Newport Blvd AAC A 8 425 44 18,700 2/28/24 100 Mill & Overlay - ARHM 1/1/24 Adams 580 Adams Ave Begin of Bridge at River Placentia Ave AAC A 22 2,688 40 107,935 3/28/24 100 Mill & Overlay - ARHM 3/28/24 Adams 581 Adams Ave Placentia Ave Begin of Bridge at River AAC A 22 2,688 40 105,965 3/28/24 100 Mill & Overlay - ARHM 3/28/24 Adams 590 Adams Ave Placentia Ave Mesa Verde Dr East AAC A 21 3,125 40 125,000 3/28/24 100 Mill & Overlay - ARHM 3/28/24 Adams 591 Adams Ave Mesa Verde Dr East Placentia Ave AAC A 21 3,125 40 125,000 3/28/24 100 Mill & Overlay - ARHM 3/28/24 Adams 600 Adams Ave Mesa Verde Dr East Royal Palm Dr AAC A 21 1,000 40 40,000 3/28/24 100 Mill & Overlay - ARHM 3/28/24 Adams 601 Adams Ave Royal Palm Dr Mesa Verde Dr East AAC A 21 1,000 40 40,000 3/28/24 100 Mill & Overlay - ARHM 3/28/24 Merrimac 7291 Merrimac Way Fairview Rd Harbor Blvd AC P 10 2,580 29 74,820 1/10/24 100 Overlay-Rubber Hot Mix 1/1/21 Placentia 130 Placentia Ave Wilson St City Yard AC P 11 1,000 60 60,000 1/31/24 100 Asphalt Rubber Hot Mix 1/1/24 Placentia 131 Placentia Ave City Yard Estancia N AC P 11 1,220 60 73,200 1/31/24 100 Asphalt Rubber Hot Mix 1/1/24 Placentia 132 Placentia Ave Estancia N Fairview Park AC P 11 1,460 60 87,600 1/31/24 100 Asphalt Rubber Hot Mix 1/1/24 Placentia 133 Placentia Ave Fairview Park Fairview Channel AC P 1,510 60 90,600 1/30/24 100 Asphalt Rubber Hot Mix 1/1/24 Placentia 134 Placentia Ave Fairview Channel Tern Cir AC P 11 1,091 60 65,460 1/30/24 100 Asphalt Rubber Hot Mix 1/1/24 Placentia 135 Placentia Ave Tern Cir Adams Ave AC P 11 790 60 47,400 1/30/24 100 Asphalt Rubber Hot Mix 1/1/24 Wilson 5800 Wilson St Placentia Ave Raleigh Ave AC S 19 830 36 29,880 1/9/24 100 Asphalt Rubber Hot Mix 9/19/23 Wilson 5810 Wilson St Raleigh Ave Pomona Ave AC S 19 492 36 17,712 1/9/24 100 Asphalt Rubber Hot Mix 9/19/23 Wilson 5820 Wilson St Pomona Ave Fountain Way E AC S 19 1,322 36 47,592 1/9/24 100 Asphalt Rubber Hot Mix 9/19/23 Wilson 5830 Wilson St Fountain Way E Harbor Blvd AC S 19 1,638 46 75,184 1/9/24 100 Asphalt Rubber Hot Mix 9/19/23 Wilson 5840 Wilson St Harbor Blvd College Ave AC S 24 885 61 53,720 1/9/24 100 Asphalt Rubber Hot Mix 9/19/23 Wilson 5850 Wilson St College Ave Fairview Rd AC S 24 2,620 36 94,320 1/9/24 100 Asphalt Rubber Hot Mix 9/19/23
74.4 16,632,332
Locals
Glen 4520 Glen Cir Cul-de-sac Canyon Dr AC E 1 270 37 12,164 12/29/21 25 Surface Treatment - Slurry Seal 9/1/09 LittletonP 6520 Littleton Pl Cul-de-sac Villanova Rd AC E 24 343 37 14,865 1/5/22 32 Surface Treatment - Slurry Seal 9/1/09 Samar Dr 7960 Samar Dr Cul-de-sac Mesa Verde Dr AC E 21 2,700 37 102,074 1/5/22 37 Surface Treatment - Slurry Seal 1/1/10 Coriander 8750 Coriander Dr Coral Ave Cinnamon Ave AC E 23 1,387 37 51,319 10/26/21 38 Surface Treatment - Slurry Seal 1/1/10 16th 2905 16th St Superior Ave Newport Blvd AC E 7 800 37 29,600 1/5/22 39 Surface Treatment - Slurry Seal 9/1/08 PresidioSq 9860 Presidio Sq Presidio Dr S'ly end AC E 20 150 37 5,550 11/22/21 39 New Construction - Initial 1/1/00 Ellesmere 7972 Ellesmere Ave Samar Dr Ceylon Dr AC E 21 960 37 35,520 1/4/22 40 Surface Treatment - Slurry Seal 1/1/10 Sonora 10202 Sonora Rd Velasco Ln Loreto Ave AC E 20 1,150 37 44,550 11/22/21 42 New Construction - Initial 1/1/00 Bimini 8540 Bimini Pl Cul-de-sac Baker St AC E 21 783 37 31,145 1/5/22 43 Surface Treatment - Slurry Seal 1/1/10 Peterson 9300 Peterson Pl Harbor Blvd Adams St AC E 10 1,346 37 49,802 11/9/21 43 New Construction - Initial 1/1/00 Scenic 9760 Scenic Dr Hyland Ave Harbor Blvd AC E 30 1,891 54 102,114 10/21/21 43 New Construction - Initial 1/1/00 BoaVistaC 7820 Boa Vista Cir Cul-de-sac Stromboli Rd AC E 21 496 37 20,526 1/5/22 44 Surface Treatment - Slurry Seal 1/1/10 CeylonRd 8160 Ceylon Rd Cul-de-sac Madeira Ave AC E 23 1,424 37 54,862 11/16/21 44 Surface Treatment - Slurry Seal 1/1/10 Stromboli 7850 Stromboli Rd Pitcairn Dr Club House Rd AC E 21 1,399 37 51,763 1/5/22 45 Surface Treatment - Slurry Seal 1/1/10 Wakeham 11008 Wakeham Pl Cul-de-sac Bear St AAC E 27 1,290 37 49,904 10/22/21 45 2 in Cold Mill & Overlay 1/1/18 AmericanPL 5650 American Pl American Ave Cul-de-sac AC E 18 255 37 11,609 11/9/21 47 Surface Treatment - Slurry Seal 10/6/15 Green 9480 Green St Watson Ave N' End AC E 15 120 37 4,440 11/15/21 47 Surface Treatment - Slurry Seal 3/20/16 Princeton 7210 Princeton Dr Harbor Blvd Oxford Ln AC E 10 1,000 37 37,000 11/10/21 47 Surface Treatment - Slurry Seal 12/1/00 Royal Palm 8560 Royal Palm Dr Baker St Corsica Pl AC E 23 362 37 13,394 11/16/21 47 Surface Treatment - Slurry Seal 1/1/10 Ohio 8980 Ohio Pl Indiana Ave Cul-de-sac AC E 17 132 37 7,062 10/22/21 48 Surface Treatment - Slurry Seal 10/3/23 White Oak 8450 White Oak St Jacaranda Ave Redwood Ave AC E 21 540 38 20,552 10/15/21 48 Surface Treatment - Slurry Seal 1/1/10 Santa Ana 2420 Santa Ana Ave 15th St 16th St AAC E 8 1,321 35 46,235 12/28/21 49 Surface Treatment - Slurry Seal 9/1/22 Ford 4900 Ford Rd Harbor Blvd Alley #40/#41 AC E 5 866 33 28,578 11/15/21 50 New Construction - Initial 1/1/00 Minorca Pl 7980 Minorca Pl Ellesmere Ave Cul-de-sac AC E 21 950 37 37,324 1/4/22 50 Surface Treatment - Slurry Seal 1/1/10 Randolph 10370 Randolph Ave Bristol St Baker St AC E 13 1,230 60 73,800 11/1/21 50 Surface Treatment - Slurry Seal 12/6/22 Baltra 7720 Baltra Pl Europa Dr Inroz Dr AC E 22 779 37 29,323 12/29/21 51 Surface Treatment - Slurry Seal 1/1/10 Barbados 8240 Barbados Pl Labrador Dr Madagasgar St AC E 23 1,316 37 53,433 1/5/22 51 Surface Treatment - Slurry Seal 1/1/10
265
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, PCI Order (0-100)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Corsica 8600 Corsica Pl Gibralter Ave Royal Palm Dr AC E 23 1,461 37 54,057 1/5/22 51 Surface Treatment - Slurry Seal 1/1/10 Minorca Dr 8300 Minorca Dr Mesa Verde Dr Royal Palm Dr AC E 21 1,584 37 58,608 11/16/21 51 Surface Treatment - Slurry Seal 1/1/10 Susan 9835 Susan St Pavement Change Sunflower Ave AC E 30 1,004 37 37,148 11/29/21 51 New Construction - Initial 1/1/00 Calvert 7680 Calvert Ave Europa Dr Shantar Dr AC E 22 950 37 35,150 10/25/21 52 Surface Treatment - Slurry Seal 1/1/10 Fullerton 3940 Fullerton Ave 20th St Bay St AAC E 3 620 36 22,320 9/17/21 52 Overlay - AC Structural 4/15/12 PepperTree 8400 Pepper Tree Ln Royal Palm Dr Royal Palm Dr AC E 21 1,361 37 50,357 11/16/21 52 Surface Treatment - Slurry Seal 1/1/10 Ridgecrest 4480 Ridgecrest Cir Valley Rd Cul-de-sac AC E 1 271 37 12,201 11/16/21 52 Surface Treatment - Slurry Seal 9/1/09 Tulane Pl 6410 Tulane Pl Columbia Dr Cul-de-sac AC E 24 195 37 9,389 11/10/21 52 Surface Treatment - Slurry Seal 9/1/09 BoaVistaDr 7670 Boa Vista Dr Kornat Dr Mesa Verde Dr AC E 22 1,800 37 66,600 11/11/21 53 Surface Treatment - Slurry Seal 1/1/10 Panay 8790 Panay Cir Cul-de-sac Country Club Dr AC E 22 242 37 10,204 11/16/21 53 Surface Treatment - Slurry Seal 1/1/10 Pemba 8040 Pemba Dr Samar Dr Ceylon Dr AC E 21 1,448 37 54,137 1/5/22 53 Surface Treatment - Slurry Seal 1/1/10 Maui Pl 8070 Maui Pl Tahiti Dr Cul-de-sac AC E 21 557 37 23,100 11/11/21 54 Surface Treatment - Slurry Seal 1/1/10 Babb 10610 Babb St Baker St Paularino Ave AC E 16 831 37 30,747 10/19/21 55 New Construction - Initial 1/1/00 Caraway 8710 Caraway Dr Coral Ave Cinnamon Ave AC E 23 1,426 37 52,762 10/22/21 55 Surface Treatment - Slurry Seal 1/1/10 Europa 7650 Eurpoa Dr Calvert Ave Kornat Dr AC E 21 1,600 37 59,700 10/26/21 55 Surface Treatment - Slurry Seal 1/1/10 Gisler 9704 Gisler Ave 1000' e/o College Ave E'ly end AAC E 15 735 22 15,135 11/5/21 55 Overlay - AC Structural 3/1/09 Harding 10600 Harding Way Cul-de-sac Cul-de-sac AAC E 16 678 37 29,434 11/17/21 55 Overlay - AC Structural 10/1/15 Londondrry 9620 Londonderry St Sharon Ln Bray Ln AC E 15 1,330 37 49,710 11/15/21 55 Surface Treatment - Slurry Seal 3/20/16 Paros 7860 Paros Cir Cul-de-sac Stromboli Rd AC E 21 446 37 18,676 1/5/22 55 Surface Treatment - Slurry Seal 1/1/10 Columbia 6440 Columbia Dr Fair Dr Hanover Dr AC E 10 1,148 37 42,476 11/23/21 56 Surface Treatment - Slurry Seal 2/1/06 Oak 4362 Oak St President Pl Continental Ave AAC E 1 817 33 26,961 11/16/21 56 Surface Treatment - Slurry Seal 3/20/16 Ponderosa 8310 Ponderosa St Andros St Royal Palm Dr AC E 21 1,067 37 39,479 11/16/21 56 Surface Treatment - Slurry Seal 1/1/10 Baker 630 Baker St Samar Dr Mesa Verde Dr AC E 21 1,670 37 62,194 1/4/22 57 Surface Treatment - Slurry Seal 1/1/10 Boise 10710 Boise Way Cul-de-sac Van Buren Ave AC E 16 416 37 17,591 11/17/21 57 New Construction - Initial 1/1/00 CeylonDr 8030 Ceylon Dr Palau Pl Cul-de-sac AC E 21 1,180 37 45,834 12/15/21 57 Surface Treatment - Slurry Seal 1/1/10 Club House 7890 Club House Rd Mesa Verde Dr W N'ly end at Golf Course Parking Lot AAC E 22 750 37 27,750 11/11/21 57 Overlay - AC Structural 10/14/11 Boston 10750 Boston Way Cul-de-sac Charldston St AC E 16 260 37 12,380 11/17/21 58 New Construction - Initial 1/1/00 Snt Isabel 6750 Santa Isabel Ave Orange Ave Santa Ana Ave AC E 26 1,320 37 48,840 9/17/21 58 Surface Treatment - Slurry Seal 1/1/17 Carnegie 7100 Carnegie Ave Fair Dr Princeton Dr AC E 10 1,254 37 46,398 11/10/21 59 Surface Treatment - Slurry Seal 9/1/09 Carson 10720 Carson St Van Buren Ave Coolidge Ave AC E 16 783 37 29,241 11/17/21 59 New Construction - Initial 1/1/00 Sunflower 775 Sunflower Ave Cadillac Ave Hyland Ave AC E 30 1,775 60 106,500 11/2/21 59 New Construction - Initial 1/1/00 Bonnie 6770 Bonnie Pl Santa Isabel Ave Cul-de-sac AC E 26 320 33 12,734 11/9/21 60 Surface Treatment - Slurry Seal 1/8/19 Cork 9650 Cork Ln McCormack St Londonderry St AC E 15 580 37 21,635 11/15/21 60 Surface Treatment - Slurry Seal 3/20/16 El Rio 10050 El Rio Cir El Camino Dr Cul-de-sac AC E 20 551 37 22,561 10/19/21 60 Surface Treatment - Slurry Seal 2/1/06 Kerry 9640 Kerry Ln Killarney Ln Londonderry St AC E 15 730 37 27,210 11/15/21 60 Surface Treatment - Slurry Seal 3/20/16 Shannon 9408 Shannon Ln College Ave Watson Ln AC E 15 500 37 18,500 11/15/21 60 Surface Treatment - Slurry Seal 3/20/16 Tulare 11050 Tulare Dr Salinas Ave San Leandro Ln AC E 14 1,721 37 63,677 10/27/21 60 Surface Treatment - Slurry Seal 1/1/18 Wallace 5920 Wallace Ave Congress St Wilson St AC E 19 659 37 24,383 11/9/21 60 Complete Reconstruction - AC 2/1/07 Amherst Rd 6380 Amherst Rd Notre Dame Dr Columbia Dr AC E 24 575 37 22,835 11/10/21 61 Surface Treatment - Slurry Seal 9/1/09 Balearic 7710 Balearic Dr Europa Dr Boa Vista Dr AC E 22 1,421 36 51,775 10/25/21 61 Surface Treatment - Slurry Seal 1/1/10 NewportNBF 2030 Newport Blvd N/B Frontage Road 16th St AC PCC E 8 960 36 34,560 12/15/21 61 Complete Reconstruction - PCC 1/8/19 PresidioSq 9865 Presidio Sq Presidio Sq West Presidio Sq East AC E 928 60 55,680 11/22/21 61 New Construction - AC 1/1/80 Randolph 10360 Randolph Ave E'ly end Bristol St AC E 13 649 37 23,763 11/22/21 61 Surface Treatment - Slurry Seal 1/1/00 Rochester 3620 Rochester St Newport Blvd Orange Ave AAC E 8 1,340 37 49,580 1/5/22 61 Overlay - AC Structural 4/1/12 Samar Pl 8510 Samar Pl Cul-de-sac Andros St AC E 21 400 37 16,974 11/16/21 61 Surface Treatment - Slurry Seal 1/1/10 Superior 2974 Superior Ave Newport Blvd Entrance 18th St AAC E 7 800 48 38,400 1/5/22 61 Overlay - AC Structural 7/1/19 Tahiti 8060 Tahiti Dr Mesa Verde Dr Java Rd AC E 22 1,090 37 40,330 11/11/21 61 Surface Treatment - Slurry Seal 1/1/10 Joann 6300 Joann St Fordham Dr Columbia Dr AC E 24 1,452 37 53,942 11/23/21 62 Surface Treatment - Slurry Seal 2/1/06 MonteVista 6920 Monte Vista Ave Orange Ave Santa Ana Ave AC E 26 1,328 37 49,136 10/5/21 62 Surface Treatment - Slurry Seal 1/1/17 Puente 5950 Puente Ave Cul-de-sac Senate St AAC E 19 770 37 30,664 11/9/21 62 Overlay - AC Structural 5/1/03 Rose 5620 Rose Ln Orange Ave Santa Ana Ave AC E 3 1,300 37 48,100 10/7/21 62 Surface Treatment - Slurry Seal 4/1/16 Shantar 7420 Shantar Dr Adams Ave Balearic Dr AC E 22 898 37 35,813 10/25/21 62 Surface Treatment - Slurry Seal 1/1/10 Susan 9831 Susan St Sunflower Ave South Coast Dr AC E 30 1,500 37 55,500 10/22/21 62 New Construction - Initial 1/1/00 Virginia 6580 Virginia Pl Newport Blvd Santa Ana Ave AC E 25 2,658 37 98,346 10/7/21 62 Surface Treatment - Slurry Seal 1/1/17 WstmnstrAv 5570 Westminster Ave 21st St Rose Ln AC E 3 783 37 28,971 10/7/21 62 Surface Treatment - Slurry Seal 3/20/16 Cecil 6590 Cecil Pl Newport Blvd Santa Ana Ave AC E 25 2,513 37 88,533 10/7/21 63 Surface Treatment - Slurry Seal 4/1/16
266
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, PCI Order (0-100)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Cottage 5580 Cottage Pl Cul-de-sac Westminster Ave AC E 3 168 37 8,390 10/7/21 63 Surface Treatment - Slurry Seal 3/20/16 Dublin 9490 Dublin St Shamrock Ln N'ly end AC E 15 470 37 17,390 11/15/21 63 Surface Treatment - Slurry Seal 3/20/16 Governor 5670 Governor St State Ave Placentia Ave AC E 18 2,460 33 81,180 11/9/21 63 Surface Treatment - Slurry Seal 10/1/00 Maui Cir 8100 Maui Cir Cul-de-sac Java Rd AC E 22 391 37 16,641 11/11/21 63 Surface Treatment - Slurry Seal 1/1/10 Molokai 8280 Molokai Pl Cul-de-sac Gibralter Ave AC E 23 500 37 20,674 11/16/21 63 Surface Treatment - Slurry Seal 1/1/10 Taft 10730 Taft Way Cul-de-sac Carson St AAC E 16 377 37 15,985 11/17/21 63 Overlay - AC Structural 10/1/15 Bowling 7260 Bowling Green Dr Hanover Dr Yale Pl AC E 10 1,176 37 43,512 11/10/21 64 6 in Cold Mill & Overlay in Secure area 2/1/12 Darrel 5870 Darrel St Republic Ave Federal Ave AC E 18 1,890 37 69,930 11/9/21 64 Surface Treatment - Slurry Seal 10/6/15 Galway 9404 Galway Ln College Ave Killybrooke Ln AC E 15 370 37 13,690 11/15/21 64 Surface Treatment - Slurry Seal 4/1/16 Jamaica 8170 Jamaica Rd Country Club Dr Cul-de-sac AC E 22 600 37 22,200 10/26/21 64 Surface Treatment - Slurry Seal 1/1/10 NewportNBF 2070 Newport Blvd N/B Frontage Road 15th St PCC AC E 315 36 11,340 12/15/21 64 New Construction - AC 1/1/00 PresidioSq 9870 Presidio Sq S'ly end Presidio Dr AAC E 20 150 37 5,550 12/29/21 64 Overlay - AC Structural 12/1/15 15th 2175 15th St Santa Ana Ave Newport Blvd AC E 9 1,670 18 30,060 10/8/21 65 Surface Treatment - Slurry Seal 9/1/22 17th 3031 17th St "V"-Right (w/o Bullnose) Newport Blvd AAC E 8 480 18 8,640 12/28/21 65 Surface Treatment - Slurry Seal 3/3/22 Augusta 10660 Augusta St Fairview Rd Van Buren Ave AAC E 16 520 37 19,240 10/26/21 65 Overlay - AC Structural 10/1/15 Coronado 9900 Coronado Dr Presido Dr La Salle Ave AAC E 20 1,480 37 54,760 12/29/21 65 Overlay - AC Structural 3/1/08 Joann 5710 Joann St Republic Ave Placentia Ave AC E 18 2,140 37 79,180 11/9/21 65 Surface Treatment - Slurry Seal 10/6/15 NewportNBF 2020 Newport Blvd N/B Frontage Road AC 16th St PCC E 8 1,022 36 42,552 12/15/21 65 Complete Reconstruction - PCC 1/8/19 Shamrock 9500 Shamrock Ln Dublin St Watson Ln AC E 15 518 37 19,166 11/15/21 65 Surface Treatment - Slurry Seal 4/1/16 Turlock 11090 Turlock Dr Redding Ave Salinas Ave AC E 14 853 36 37,158 10/27/21 65 Surface Treatment - Slurry Seal 1/1/18 WstmnstrAv 5050 Westminster Ave Walnut St 20th St AAC E 3 655 18 11,790 11/19/21 65 Overlay - AC Structural 4/1/12 Raymond 3610 Raymond Ave 17th St N'ly end AAC E 9 650 25 15,750 11/29/21 66 Overlay - AC Structural 4/1/12 Royce 9410 Royce Ln Baker St Watson Ave AC E 15 953 37 35,261 11/15/21 66 Surface Treatment - Slurry Seal 4/1/16 Samoa 8210 Samoa Pl Cul-de-sac Gibraltar Ave AC E 23 1,849 37 70,587 11/16/21 66 Surface Treatment - Slurry Seal 1/1/10 VictoriaFR 4550 Victoria St Frontage Road W'ly Cul-de-sac E'ly Cul-de-sac AC E 1 2,177 37 84,897 11/16/21 66 New Construction - Initial 1/1/00 WstmnstrPl 6970 Westminster Pl Del Mar Ave Cul-de-sac AC E 26 529 33 19,631 10/5/21 66 Surface Treatment - Slurry Seal 1/1/17 Cadillac 9730 Cadillac Ave Sunflower Ave Cul-de-sac AC E 30 1,900 37 72,474 10/21/21 67 New Construction - Initial 1/1/00 Darrel 6020 Darrel St Pomona Ave Meyer Pl AC E 19 1,050 37 38,850 11/23/21 67 Surface Treatment - Slurry Seal 10/6/15 Deedee 11110 Deedee Dr Debra Dr San Jose Ave AC E 14 749 37 27,713 10/27/21 67 Surface Treatment - Slurry Seal 1/1/18 Elm 8330 Elm Ave Andros St Royal Palm Dr AC E 21 897 37 33,189 11/16/21 67 Surface Treatment - Slurry Seal 1/1/10 Haiti 8810 Haiti Cir Bahama Pl Cul-de-sac AC E 22 251 37 11,461 11/16/21 67 Surface Treatment - Slurry Seal 1/1/10 Primrose 8420 Primrose St Jacaranda Ave Royal Palm Dr AC E 21 769 37 28,326 10/15/21 67 Surface Treatment - Slurry Seal 1/1/10 Wilson 6720 Wilson St Newport Blvd Orange Ave AAC E 25 1,326 37 49,062 9/17/21 67 Surface Treatment - Slurry Seal 1/1/17 Columbia 6360 Columbia Dr Wake Forest Rd Loyola Rd AC E 10 1,126 37 41,662 11/10/21 68 Surface Treatment - Slurry Seal 2/1/06 DonnyBrook 9430 Donnybrook Ln Baker St Watson Ave AC E 15 657 37 24,309 11/15/21 68 Surface Treatment - Slurry Seal 3/20/16 Elba 7870 Elba Cir Cul-de-sac Stromboli Rd AAC E 21 350 37 15,124 11/11/21 68 Surface Treatment - Slurry Seal 1/1/10 Hudson 11550 Hudson Ave Canadian Dr Yellowstone Dr AAC E 31 826 37 30,562 10/29/21 68 Overlay - AC Structural 10/1/15 Kalmus 11851 Kalmus Dr Red Hill Ave Pullman St AC E 29 1,615 60 101,768 11/8/21 68 6 in Cold Mill & Overlay in Secure area 8/1/13 Lanai 7920 Lanai Dr W'ly end Club House Dr AC E 22 560 37 20,720 11/11/21 68 Surface Treatment - Slurry Seal 1/1/10 New York 8910 New York Ave Cul-de-sac Iowa St AC E 17 955 37 37,510 10/22/21 68 Surface Treatment - Slurry Seal 10/3/23 NewportNBF 2040 Newport Blvd N/B Frontage Road PCC 17th St AC E 138 37 4,673 12/6/21 68 New Construction - AC 1/1/00 San Jose 11120 San Jose Ave Deedee Dr Santa Clara Cir AC E 14 580 36 20,725 10/27/21 68 Surface Treatment - Slurry Seal 1/1/18 Santa Ana 2430 Santa Ana Ave 16th St 17th St AAC E 8 1,320 36 47,520 12/28/21 68 Overlay - AC Structural 4/1/12 Santa Ana 2510 Santa Ana Ave 23rd St Santa Isabel Ave AC E 25 1,322 36 47,592 10/7/21 68 New Construction - Initial 1/1/00 Serra 9980 Serra Way Fremont Ln Coronado Dr AC E 20 590 37 21,830 11/22/21 68 Surface Treatment - Slurry Seal 2/1/06 Inroz 7730 Inroz Dr Baltra Pl Lemnos Dr AC E 22 260 37 9,620 10/15/21 69 Surface Treatment - Slurry Seal 1/1/10 Lehigh 7150 Lehigh Pl Cul-de-sac Bucknell Rd AAC E 10 360 37 15,494 11/10/21 69 Overlay - AC Structural 10/1/05 Loyola 6510 Loyola Rd Fair Dr Bucknell Rd AC E 10 449 37 16,613 11/10/21 69 New Construction - Initial 1/1/00 Madagasgar 8200 Madagasgar St Madeira Ave Barbados Pl AC E 23 481 37 17,797 11/16/21 69 Surface Treatment - Slurry Seal 1/1/10 Maple St 6130 Maple St Wilson St Joann St AAC E 19 500 37 18,500 11/23/21 69 Surface Treatment - Slurry Seal 10/6/15 Monaco 6790 Monaco Terr Riviera Dr Monte Vista Ave AC E 26 900 33 29,700 10/7/21 69 Surface Treatment - Slurry Seal 1/1/17 Palau 8010 Palau Pl Samar Dr Cul-de-sac AC E 21 974 37 38,212 11/11/21 69 Surface Treatment - Slurry Seal 1/1/10 State 4350 State Ave Grove Pl Oak St AC E 1 560 33 18,480 11/16/21 69 Surface Treatment - Slurry Seal 3/20/16 Airway 11800 Airway Ave Clinton Ave Fischer Ave AC E 29 2,721 60 276,209 11/8/21 70 6 in Cold Mill & Overlay in Secure area 8/1/13 Fordham 6230 Fordham Dr Fair Dr Princeton Dr AC E 10 1,265 37 46,805 11/23/21 70 Surface Treatment - Slurry Seal 2/1/06 Junipero 9880 Junipero Dr Arlington Dr Presidio Dr AC E 20 1,119 60 67,140 11/22/21 70 New Construction - Initial 1/1/00
267
City of Costa Mesa, CA
Pavement Condition Index (PCI) Report - All Streets
Sorted by Rank, PCI Order (0-100)
BranchID Sec ID Name From To Type Rank Zone L W Area Insp. Date PCI Work History Type Work Date Ludington 11610 Ludington St Paularino Ave Traverse Dr AAC E 12 1,500 37 55,500 11/23/21 70 Overlay - AC Structural 9/1/04 Paularino 11580 Paularino Ave Bear St Bristol St AAC E 31 2,162 37 79,994 11/2/21 70 Overlay - AC Structural 10/1/15 Riviera 6780 Riviera Dr Rue De Cannes Tustin Ave AC E 26 910 33 30,030 10/5/21 70 Surface Treatment - Slurry Seal 1/1/17 Rural Pl 5530 Rural Pl Rural Ln 22nd St AC E 3 750 33 24,750 10/7/21 70 New Construction - Initial 1/1/00 Tulane Rd 6400 Tulane Rd Notre Dame Rd Columbia Dr AC E 24 600 37 22,395 12/29/21 70 Surface Treatment - Slurry Seal 9/1/09 Tustin 2550 Tustin Ave 15th St 16th St AC E 9 1,300 36 46,800 11/19/21 70 Complete Reconstruction - AC 2/1/10 Airway 11805 Airway Ave Fischer Ave Paularino Ave AC E 29 1,852 60 276,209 11/8/21 71 6 in Cold Mill & Overlay in Secure area 8/1/13 AveOTArts 11740 Avenue of the Arts Anton Ave Sunflower Ave AAC E 28 1,457 21 31,034 10/28/21 71 Overlay - AC Structural 10/1/06 AveOTArts 11741 Avenue of the Arts Sunflower Ave Anton Blvd AAC E 28 1,457 21 31,034 10/28/21 71 Overlay - AC Structural 10/1/06 Elm 8340 Elm Ave Royal Palm Dr Harbor Blvd AC E 21 800 37 29,600 11/16/21 71 Surface Treatment - Slurry Seal 1/1/10 Loyola 6500 Loyola Rd Fairview Rd Fair Dr AC E 24 1,253 37 46,213 11/10/21 71 Surface Treatment - Slurry Seal 9/1/09 Pacific 4500 Pacific Ave Victoria Pl N'ly End AC E 18 2,515 36 90,540 11/9/21 71 Surface Treatment - Slurry Seal 10/6/15 Parnell 9580 Parnell Pl Loren Ln Cul-de-sac AC E 15 277 37 12,423 11/15/21 71 Surface Treatment - Slurry Seal 3/20/16 Roanoke 11510 Roanoke Ln Cul-de-sac Allegheny Ave AAC E 31 700 37 28,074 10/29/21 71 Overlay - AC Structural 10/1/15 Sicily 8270 Sicily Ave Sumatra Pl Gisler Ave AC E 23 800 37 29,600 11/16/21 71 Surface Treatment - Slurry Seal 1/1/10 Snt Isabel 6740 Santa Isabel Ave Newport Blvd Orange Ave AAC E 26 1,320 37 48,840 9/17/21 71 Surface Treatment - Slurry Seal 1/1/17 Yellowstn 11560 Yellowstone Dr Paularino Ave Olympic Ave AAC E 31 1,569 37 57,803 10/29/21 71 Overlay - AC Structural 10/1/15 17th 3030 17th St Newport Blvd "V"-Right (w/o Bullnose) AAC E 8 450 18 8,100 11/29/21 72 Surface Treatment - Slurry Seal 3/3/22 Aliso 2780 Aliso Ave 16th St Cambridge Cir AAC E 9 873 37 32,301 10/15/21 72 Overlay - AC Structural 4/12/12 Canadian 11530 Canadian Dr Allegheny Ave Olympic Ave AAC E 31 500 37 18,500 10/28/21 72 Overlay - AC Structural 10/1/15 Chios 7750 Chios Rd Balearic Dr Lemnos Dr AC E 22 530 37 19,860 10/15/21 72 Surface Treatment - Slurry Seal 1/1/10 CollegeAve 9355 College Ave Baker St Gisler Ave AC E 15 2,500 37 92,500 11/15/21 72 Surface Treatment - Slurry Seal 3/20/16 Junipero 9890 Junipero Dr Presidio Dr Sutter Way AAC E 20 1,730 37 27,010 10/19/21 72 Overlay - AC Structural 9/15/15 Killarney 9630 Killarney Ln Londonderry St Kerry Ln AC E 15 594 37 21,978 11/15/21 72 Surface Treatment - Slurry Seal 3/20/16 Pierce 10840 Pierce Ave Cheyenne Ave Concord St AAC E 16 698 36 27,082 10/19/21 72 Overlay - AC Structural 10/1/15 Plum 4310 Plum Pl Federal Ave Cul-de-sac AAC E 1 200 27 7,574 11/16/21 72 Overlay - AC Structural 9/14/10 Pullman 11860 Pullman Ave Kalmus Rd 420' S/O Briggs Ave AC E 29 2,011 55 109,600 11/8/21 72 6 in Cold Mill & Overlay in Secure area 8/1/13 Royal Palm 8550 Royal Palm Dr Adams Ave Baker St AC E 21 2,641 37 97,717 10/4/21 72 Surface Treatment - Slurry Seal 1/1/10 Rutgers 6340 Rutgers Dr Wake Forest Rd Villanova Rd AC E 24 1,130 37 41,810 11/10/21 72 Surface Treatment - Slurry Seal 9/1/09 Salinas 11040 Salinas Ave Wimbledon Way Smalley Rd AC E 14 1,805 37 70,291 10/27/21 72 Surface Treatment - Slurry Seal 1/1/18 Toronto 9740 Toronto Way Cadillac Ave Cul-de-sac AC E 30 439 37 18,417 10/21/21 72 New Construction - Initial 1/1/00 Tustin 2600 Tustin Ave 20th St Emerson St AAC E 4 820 36 29,520 11/19/21 72 Overlay - AC Structural 4/1/12 Wallace 3140 Wallace Ave 19th St Hamilton St AC E 2 2,650 37 98,050 11/12/21 72 New Construction - Initial 1/1/00 Briggs 11880 Briggs Ave Pullman St Red Hill Ave AC E 29 730 60 43,800 11/8/21 73 6 in Cold Mill & Overlay in Secure area 8/1/13 Capital 5754 Capital St Republic Ave National Ave AAC E 18 656 37 24,735 11/9/21 73 Surface Treatment - Slurry Seal 10/6/15 Rural Ln 5520 Rural Ln 22nd St Rural Pl AC E 3 560 33 18,480 10/7/21 73 New Construction - Initial 1/1/00 Sonora 10200 Sonora Rd La Salle Ave Velasco Ln AAC E 20 770 37 28,490 11/22/21 73 Overlay - AC Structural 9/15/15 15th 2170 15th St Redlands Ave Tustin Ave AC E 9 650 19 12,025 10/8/21 74 Surface Treatment - Slurry Seal 9/1/22 Atlanta 10650 Atlanta Way Cul-de-sac Van Buren Ave AAC E 16 440 37 18,454 11/17/21 74 Overlay - AC Structural 10/1/15 Bunting 7570 Bunting Cir Oriole Dr Cul-de-sac AAC E 11 500 37 20,674 10/6/21 74 Overlay - AC Structural 10/1/15 Carmel 11030 Carmel Dr South Coast Dr Salinas Ave AC E 14 448 37 16,576 10/27/21 74 Surface Treatment - Slurry Seal 1/8/19 Charleston 10760 Charleston St Boston Way Coolidge Ave AAC E 16 1,090 37 42,732 11/17/21 74 Overlay - AC Structural 10/1/16 Cleveland 10490 Cleveland Ave Cul-de-sac Paularino Ave AAC E 16 749 37 29,887 11/16/21 74 Overlay - AC Structural 10/1/15 Cornell 6330 Cornell Dr Wake Forest Rd Villanova Rd AC E 24 1,100 37 40,145 11/23/21 74 Surface Treatment - Slurry Seal 9/1/09 Esther 5150 Esther St Walnut Pl Tustin Ave AAC E 4 650 35 22,425 11/10/21 74 Overlay - AC Structural 4/1/12 Gisler 9700 Gisler Ave College Ave 1000' E'ly AAC E 15 1,005 22 24,236 11/5/21 74 Overlay - AC Structural 3/20/16 HarborGtwS 9800 Harbor Gateway South Sunflower Ave Scenic Dr AC E 30 1,328 37 49,136 10/21/21 74 New Construction - Initial 1/1/00 Harla 7640 Harla Ave Cul-de-sac Mesa Verde Dr E AAC E 11 600 37 24,374 10/18/21 74 Overlay - AC Structural 10/1/15 Hummingbrd 7580 Hummingbird Dr Bunting Cir Tanager Dr AAC E 11 1,840 37 68,080 10/6/21 74 Overlay - AC Structural 10/1/15 Industrial 2010 Industrial Way Superior Ave Newport Blvd S/B AAC E 8 800 36 28,800 12/6/21 74 Overlay - AC Structural 10/1/15 Jeffrey 11470 Jeffrey Dr Baker St Paularino Ave AC E 13 960 37 35,520 10/29/21 74 Surface Treatment - Slurry Seal 9/1/09 Monrovia 25 Monrovia Ave 20th St Victoria St Frontage Road AC E 1 1,982 33 65,406 11/16/21 74 Surface Treatment - Slurry Seal 3/20/16 National 4402 National Ave Congress St Wilson St AAC E 18 713 37 25,613 11/9/21 74 2 in overlay 4/1/02 Oahu 8020 Oahu Pl Palau Pl Cul-de-sac AC E 21 483 37 20,045 11/16/21 74 Surface Treatment - Slurry Seal 1/1/10 Olympic 11540 Olympic Ave Canadian Dr Yellowstone Dr AAC E 31 850 37 31,450 10/29/21 74 Overlay - AC Structural 10/1/15 Wellesley 7280 Wellesley Ln Columbia Dr Cul-de-sac AAC E 10 372 33 14,450 11/10/21 74 Overlay - AC Structural 11/1/06