Cities Index.
Agenda, second session

Fairfield City Council
October 20, 2026

Document
Agenda, second session
Meeting
October 20, 2026
Body
Fairfield City Council
Pages
1,497
Original file
248.5 MB
Text extracted from the city's file for reading and search. Open the original on pub-fairfield.escribemeetings.com. That file is the official record.

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026
4 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -216 The Project would continue to use existing electric power, telecommunications, and, where applicable, natural gas infrastructure to support facility operations. Utility connections associated with the Project would be within the NBRWTP site, existing roadway corridors, or established utility corridors and would not require construction of major new off-site utility transmission facilities.

Although the Project includes construction of new utility infrastructure, the environmental effects associated with such construction are addressed throughout this Initial Study/Mitigated Negative Declaration and would not result in significant unavoidable impacts. In addition, the Project would not facilitate development beyond that anticipated in adopted planning documents, expand municipal service boundaries, or require substantial new utility infrastructure outside established service areas. Therefore, the Project would not require or result in the construction or relocation of utility facilities in a manner that would cause significant environmental effects, and impacts would be less than significant.
b. Would the project have sufficient water supplies available to serve the project and reasonably foreseeable future development during normal, dry and multiple dry years? Less Than Significant Impact. The Project would expand treatment capacity and improve operational reliability to meet projected potable water demands identified in the City’s 2024 Public Utilities Master Plan and applicable water planning documents for both Fairfield and Vacaville. The Project is intended to address a treatment capacity shortfall identified for future buildout conditions, provide operational redundancy and resiliency, and maintain reliable service during periods of high demand, maintenance activities, and emergency conditions. The Project is consistent with the General Plans, UWMPs,
86 and water system planning documents of both cities, which anticipate continued provision of water service to planned development within established service areas.

The NBRWTP currently has a treatment capacity of approximately 52.7 mgd, and the Project would increase treatment capacity up to 65 mgd. However, the Project would not increase water supply entitlements, contractual water allocations, water rights, or groundwater extraction beyond levels already evaluated through the applicable planning process. Rather, the Project would improve the ability of the NBRWTP to treat and deliver existing and planned water supplies available to Fairfield and Vacaville. Water supplies serving the cities are derived primarily from surface water conveyed through the North Bay Aqueduct and Solano Project facilities, supplemented by local groundwater resources.

The adopted UWMPs for Fairfield and Vacaville evaluate projected water demands and available water supplies over the long-term planning horizon and assess water supply reliability during normal, single-dry, and multiple-dry year conditions, consistent with California Water Code requirements. These planning documents are intended to demonstrate that adequate water supplies are available to meet existing and projected demands under varying hydrologic conditions 86 City of Fairfield. 2025. 2025 Urban Water Management Plan Draft. Website: https://www.fairfield.ca.gov/ home/showpublisheddocument/14567/639142813372170000 (accessed May 25, 2026).

Page 360 of 1497 ends

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) 4-217 and drought scenarios. The Project would not result in water demand beyond that already anticipated in the applicable UWMPs, General Plans, and water system planning documents.

Accordingly, the Project would improve treatment and delivery capacity for planned water demands rather than create a need for additional water supplies. Because sufficient water supplies have been planned for and evaluated through the applicable UWMP process and the Project would not increase demands beyond those projections, sufficient water supplies would be available to serve the Project and reasonably foreseeable development during normal, dry, and multiple-dry year conditions. Therefore, impacts would be less than significant.

Reasonably Foreseeable Future Development.

Less Than Significant Impact. Although the Project would increase treatment capacity up to 65 mgd, the additional capacity is intended to serve the combined planned water demands of Fairfield and Vacaville and does not represent excess capacity available to support unplanned development. The NBRWTP is a regional facility that would be used by both cities, and the increased treatment capacity is intended to accommodate demands already anticipated in adopted General Plans, UWMP, master planning documents, and regional growth forecasts.

The Project would not increase water supply entitlements, expand municipal service boundaries, establish new service areas, or provide infrastructure to areas not designated for development.

Any future development served by the NBRWTP would remain subject to applicable General Plan designations, zoning regulations, infrastructure planning requirements, and environmental review. The Project’s primary purpose is to improve treatment reliability, operational flexibility, and system resiliency rather than facilitate new growth.

Accordingly, the Project would support planned development previously evaluated through local and regional planning processes and would not directly or indirectly induce substantial growth beyond that already anticipated in adopted planning documents. Impacts would be less than significant.
c. Would the project result in a determination by the wastewater treatment provider which serves or may serve the project that it has adequate capacity to serve the project’s projected demand in addition to the provider’s existing commitments?
Less Than Significant Impact. The Project consists of expansion and modernization of an existing regional water treatment facility and construction of a treated-water transmission pipeline. The Project would not include residential, commercial, industrial, or other land uses that typically generate substantial wastewater flows. Wastewater generated by the NBRWTP is limited primarily to domestic wastewater associated with facility employees and minor process wastewater generated during treatment operations.

Although operation of the expanded NBRWTP may require a limited increase in staffing, resulting in a small increase in domestic wastewater generation, the increase would be negligible relative to the capacity of the City’s existing wastewater collection and treatment system. The Project would not substantially increase wastewater flows, require expansion of wastewater treatment capacity, or

Page 361 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026
4 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -218 necessitate construction of new wastewater treatment facilities. In addition, the transmission pipeline facilities would not generate wastewater during operation, other than negligible amounts associated with periodic maintenance activities.

The City’s wastewater collection and treatment system currently serves the NBRWTP, and the Project would continue to use existing wastewater infrastructure. Because the Project would not generate wastewater volumes that would exceed the available capacity of the existing wastewater treatment system or affect the provider’s ability to serve existing commitments, no new or expanded wastewater treatment facilities would be required. Therefore, the Project would not result in a determination that additional wastewater treatment capacity is needed, and no impacts would be less than significant.
d. Would the project generate solid waste in excess of State or local standards, or in excess of the capacity of local infrastructure, or otherwise impair the attainment of solid waste reduction goals? and
e. Would the project comply with federal, state, and local management and reduction statutes and regulations related to solid waste?
Less Than Significant Impact. The Project would generate minor amounts of solid waste during construction, primarily from temporary construction debris such as concrete, asphalt, scrap metal, packaging, and vegetation trimmings. Operational activities at the expanded NBRWTP would generate routine utility-related solid waste, including minor packaging, maintenance materials, and office refuse. All waste generated by the Project would be collected and disposed of through existing City solid waste collection services, which are managed in accordance with local ordinances and are supported by adequate landfill capacity at facilities serving the region.

The Project would comply with all applicable federal, State, and local regulations governing solid waste management, including the California Integrated Waste Management Act (AB 939), City’s waste diversion and recycling ordinances, and applicable CalRecycle standards. Construction and operational solid waste would be recycled or reused to the maximum extent feasible, and disposal would occur only at permitted facilities.

Because the Project’s waste generation is small relative to the capacity of local infrastructure and would be managed in compliance with all applicable regulations, it would not exceed State or local standards or impair attainment of solid waste reduction goals and impacts would be less than significant.

4.19.4 Mitigation Measures
No mitigation measures are warranted.

Page 362 of 1497 ends

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD - V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) 4-219

4.20 WILDFIRE
Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
If located in or near state responsibility areas or lands classified as very high fire hazard severity zones, would the project:
a. Substantially impair an adopted emergency response plan or emergency evacuation plan?
b. Due to slope, prevailing winds, and other factors, exacerbate wildfire risks, and thereby expose project occupants to pollutant concentrations from a wildfire or the uncontrolled spread of a wildfire?
c. Require the installation or maintenance of associated infrastructure (such as roads, fuel breaks, emergency water sources, power lines or other utilities) that may exacerbate fire risk or that may result in temporary or ongoing impacts to the environment?
d. Expose people or structures to significant risks, including downslope or downstream flooding or landslides, as a result of runoff, post-fire slope instability, or drainage changes?

4.20.1 Baseline Conditions

4.20.1.1 Fire Hazard Severity Zones and Fire Protection Responsibility The California Department of Forestry and Fire Protection (CAL FIRE) classifies wildfire risk throughout California using Fire Hazard Severity Zones (FHSZs), which identify areas as Moderate, High, or Very High based on factors such as vegetation, topography, weather, and expected fire behavior. Fire protection responsibility is further categorized as State Responsibility Areas (SRAs), Local Responsibility Areas (LRAs), and Federal Responsibility Areas. 87 The NBRWTP and both pipeline alignments are located within a Local Responsibility Area (LRA), where fire protection services are provided by local agencies. According to CAL FIRE Fire Hazard Severity Zone mapping, the North Bay Regional Water Treatment Plant (NBRWTP) site is not within a Moderate, High, or Very High Fire Hazard Severity Zone. Portions of the Project vicinity, particularly undeveloped lands to the north and west, transition into areas designated as Moderate Fire Hazard Severity Zones.

4.20.1.2 Existing Wildfire Conditions
The existing NBRWTP is within a developed utility facility characterized by treatment infrastructure, paved surfaces, managed landscaping, and regularly maintained operational areas. As a result, the facility contains limited combustible vegetation and exhibits a relatively low wildfire risk compared to surrounding undeveloped lands.
87 CAL FIRE. 2026b. Fire Hazard Severity Zones. Website: https://osfm.fire.ca.gov/what-we-do/community-wildfire-preparedness-and-mitigation/fire-hazard-severity-zones (accessed May 6, 2026).

Page 363 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026
4 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -220 The proposed Linear Trail Pipeline Alignment traverses a combination of utility corridors, open space areas, drainage features, and lands adjacent to the Putah South Canal and former railroad corridor.

Vegetation along portions of this alignment consists primarily of annual grasslands, ruderal vegetation, scattered shrubs, and limited tree cover. These areas may support grassfire conditions during hot, dry, and windy periods typical of late summer and fall.

The proposed Peabody Road Pipeline Alignment is primarily within or adjacent to the existing Peabody Road corridor, where surrounding land uses include agricultural lands, utility corridors, roadway infrastructure, scattered residential development, and open space areas. Vegetation consists primarily of roadside grasses, agricultural vegetation, and ornamental landscaping. Wildfire risk along this alignment is generally lower than in more remote wildland areas due to the developed nature of the corridor and the presence of existing roadways that may serve as fire breaks and provide emergency access.

Although portions of the Project area are near the wildland-urban interface, particularly where development transitions to open space and grassland areas, the Project vicinity is not characterized by dense forested vegetation or steep topography typically associated with elevated wildfire hazards. Fire protection services are provided by the Fairfield Fire Department and Vacaville Fire Department, as applicable, with support through mutual aid agreements and regional wildfire response coordination involving CAL FIRE and neighboring jurisdictions.

4.20.2 Regulatory Requirements

4.20.2.1 Federal Regulations
National Fire Protection Association Code 1710. Code 1710 of the National Fire Protection Association (NFPA) provides the minimum requirements for the organization and deployment of fire suppression operations, emergency medical operations, and special operations to the public by career fire departments.

National Incident Management System. The National Incident Management System (NIMS) provides a systematic, proactive approach to guide government agencies, nongovernmental organizations, and the private sector to work together to prevent, report, recover from, and mitigate the effects of fire incidents, regardless of cause, size, location, or complexity, to reduce the loss of life and property harm to the environment. The City participates in NIMS, which improves its ability to prepare for and respond to potential incidents and hazard scenarios.

4.20.2.2 State Regulations
California Department of Forestry and Fire Protection and Resources Assessment Program. CAL FIRE publishes maps that predict the threat of fire for each county within the State. LRAs, SRAs, and Federal Responsibility Areas are classified as either Very High Fire Hazard Severity Zones (VHFHSZ) or non-VHFHSZ based on factors including fuel availability, topography, fire history, and climate. The 2024 Strategic Fire Plan for California was generated by CAL FIRE to provide guidelines and objectives to account for associated fire impacts.

Page 364 of 1497 ends

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) 4-221 California Fire Code. The California Fire Code includes regulations for emergency planning, fire service features, fire protection systems, hazardous materials, fire flow requirements, and fire hydrant locations, distribution, and spacing. Several fire safety requirements include installation of sprinklers in all high-rise buildings; the establishment of fire resistance standards for fire doors, building materials, and particular types of construction; and the clearance of debris and vegetation within a prescribed distance from occupied structures in wildlife hazard areas.

California Strategic Fire Plan. This statewide plan is a strategic document that guides fire policy for much of California. The plan is aimed at reducing wildfire risk through pre-fire mitigation efforts tailored to local areas through assessments of fuels, hazards, and risks.

California State Hazard Mitigation Plan. The purpose of the California State Hazard Mitigation Plan (SHMP) is to significantly reduce deaths, injuries, and other losses attributed to natural and human-caused hazards in California. The SHMP provides guidance for hazard mitigation activities emphasizing partnerships among local, State, and federal agencies as well as the private sector.

California Government Code. California Government Code Section 51175 defines VHFHSZs and designates lands considered by the State to be a very high fire hazard. California Government Code Section 51189 directs the Office of the State Fire Marshal to create building standards for wildland fire resistance. The Government Code includes measures that increase the likelihood of a structure withstanding intrusion by fire (e.g., building design and construction requirements that use fire-resistant building materials) and provides protection of structure projections (e.g., porches, decks, balconies, and eaves) and structure openings (e.g., attics, eave vents, and windows).

California Public Resources Code. The State’s Fire Safe Regulations are set forth in PRC Section 4290, which include the establishment of SRAs. PRC Section 4291 sets forth defensible space requirements, which are applicable to anyone that “… owns, leases, controls, operates, or maintains a building or structure in, upon, or adjoining a mountainous area, forest-covered lands, brush covered lands, grass-covered lands, or land that is covered with flammable material” (PRC §4291(a)).

Assembly Bill 337. Per AB 337, local fire prevention authorities and CAL FIRE are required to identify VHFHSZs in LRAs. Standards related to brush clearance and the use of fire-resistant materials in Fire Hazard Severity Zones (FHSZs) are also established.

California Code of Regulations, Title 14 (Natural Resources). Division 1.5 (Department of Forestry and Fire Protection), Title 14 of the CCR establishes a variety of wildfire preparedness, prevention, and response regulations.

California Building Code, Chapter 7A. Chapter 7A applies to building materials, systems, and/or assemblies used in the exterior design and construction of new buildings located within a Wildland Urban Interface Fire Area. This section of the CBC establishes minimum standards for features such as fire retardant-treated wood and wood shingles, surface treatment protection, ignition-resistant construction, roof coverings and gutters, vents, exterior walls and coverings, exterior porch ceilings, underfloor protection, exterior windows, skylights, doors, decking, and accessory structures.

Page 365 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026
4 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -222 Executive Order N-04-19. On January 9, 2019, Governor Newsom announced Executive Order (EO) N-04-19, which requires State agencies to identify innovative and sustainable solutions to address the State’s wildfire crisis, such as upgraded fire detection technology.

Executive Order N-05-19. On January 9, 2019, Governor Newsom also announced EO N-05-19, which requires CAL FIRE and other State agencies to compile policy and regulatory recommendations concerning wildfire mitigation, emphasizing environmental sustainability and public health. EO N-05-19 requires the incorporation of socioeconomic analysis when conducting risk management of wildfires and mandates that agencies identify geographic areas with populations that are more vulnerable to the impacts of wildfires.

Executive Order N-18-25. In February 2025, Governor Newsom issued EO N-18-25, which is intended to strengthen wildfire resilience in urban and suburban areas by enhancing “Zone 0” defensible space and improving hazard mapping and preparedness systems. EO N-18-25 also initiated the development of a comprehensive, state-wide wildfire resilience framework through an interagency, stakeholder-led process. Specifically, EO N-18-25 directs the State Board of Forestry and Fire Protection, in consultation with the State Fire Marshal, to finalize formal regulations establishing an ember-resistant zone within 5 feet of structures and instructs the Office of the State Fire Marshal to release updated FHSZ maps for areas within a LRA, which was completed in early 2025.

4.20.2.3 Regional/Local Regulations
City of Fairfield General Plan. 88
• Goal HS-2. Prevent urban fires and protect the community from wildfire danger. ○ Policy HS-2.1 Structural Fires. Continue, enhance, or implement programs that seek to reduce the risk of structural fires.
○ Policy HS-2.4 Fire Department Review. Ensure the Fire Department has opportunity to review and provide appropriate conditions prior to project approval. Incorporate Fire Department input on longer-range plans related to water supply and water systems, transportation projects, and utilities.

4.20.3 Impact Analysis
The upgrades to the existing NBRWTP along with two practicable transmission pipeline alignments are being considered to convey treated water from the expanded facility to the City of Vacaville distribution system. These alignments include the Linear Trail pipeline alignment and the Peabody Road pipeline alignment. Each alignment would traverse a range of conditions, including developed and unpaved areas of the water treatment NBRWTP, across and along Putah South Canal, paved roadways, and unpaved open space areas that are generally not accessible to the public. For 88 City of Fairfield. 2024c. Draft Environmental Impact Report for the Fairfield General Plan 2050 and Climate Action Plan. Page 3.1-7. July 26. Website: https://www.fairfield.ca.gov/home/showpublisheddocument/ 12145/638718493339670000 (accessed February 11, 2026).

Page 366 of 1497 ends

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) 4-223 resource areas where environmental conditions vary between the alignments and could result in different impact outcomes, the analysis distinguishes between the Linear Trail Pipeline Alignment and the Peabody Road Alignment, as appropriate.
a. Would the project substantially impair an adopted emergency response plan or emergency evacuation plan?
Less Than Significant Impact. The Project includes expansion of the NBRWTP and construction of a new treated-water transmission pipeline along either the Linear Trail Pipeline Alignment or the Peabody Road Pipeline Alignment. Emergency access to the NBRWTP is currently provided via Waterworks Lane and Peabody Road, while emergency response and evacuation routes in the vicinity are maintained through the existing local and regional roadway network.

Construction of the NBRWTP improvements and either pipeline alignment could result in temporary disruptions to traffic circulation due to lane closures, shoulder closures, trenching operations, equipment staging, material deliveries, and temporary detours. The potential for temporary impacts would be greatest along the Peabody Road Pipeline Alignment because construction would be within or adjacent to an active roadway corridor that serves local residents, businesses, agricultural operations, and emergency responders. Construction of the Linear Trail Pipeline Alignment would be primarily within utility corridors, access roads, and open space areas and would have more limited impact on the public roadway network, although temporary disruptions could occur at roadway, trail, or access-road crossings.

Any temporary traffic disruptions would be subject to review and approval by the applicable Public Works Departments and other affected agencies through the encroachment permitting process. The Project would be required to prepare and implement traffic control plans and maintain adequate emergency vehicle access throughout construction. Construction activities would be coordinated with local fire, police, emergency medical service providers, and other emergency response agencies, as appropriate, and would comply with applicable local requirements and the California Manual on Uniform Traffic Control Devices. Emergency access routes would remain available during construction, and temporary lane closures or detours would be limited in duration and managed to avoid substantial interference with emergency response activities.

Upon completion, the expanded NBRWTP would remain within an existing developed utility facility and the transmission pipeline would operate underground. Neither the NBRWTP improvements nor either pipeline alignment would permanently alter roadway circulation, eliminate emergency access routes, interfere with adopted emergency response plans, or impede regional evacuation routes.

Accordingly, the Project would not substantially impair implementation of an adopted emergency response plan or emergency evacuation plan. Impacts would be less than significant. b. Would the project, due to slope, prevailing winds, and other factors, exacerbate wildfire risks, and thereby expose project occupants to pollutant concentrations from a wildfire or the uncontrolled spread of a wildfire?
Less Than Significant with Mitigation Incorporated. The NBRWTP is within an LRA and is not within a mapped Moderate, High, or Very High Fire Hazard Severity Zone. The facility consists primarily of

Page 367 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026
4 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -224 developed utility infrastructure, paved surfaces, maintained operational areas, and managed landscaping, resulting in limited combustible vegetation and a relatively low potential for wildfire ignition or spread. The Project would not introduce new components, such as structures and landscaping, that would substantially exacerbate wildfire risk.

Construction of the NBRWTP improvements and either pipeline alignment would involve temporary activities that could create ignition sources, including operation of construction equipment, vehicles, welding, cutting, generators, and other construction-related activities.

The Linear Trail Pipeline Alignment traverses portions of open space, utility corridors, and grassland areas where combustible vegetation is present and where wildfire risk may be greater than within the developed NBRWTP site.

The Peabody Road Pipeline Alignment is located primarily within or adjacent to an existing roadway corridor characterized by disturbed lands, transportation infrastructure, agricultural uses, and developed areas that generally contain lower fuel loads and greater accessibility for fire response.

Implementation of Mitigation Measure WF-1 would require maintenance of defensible space and reduction of flammable vegetation, dry debris, leaves, and dead limbs near and within active Project work areas during construction activities, as appropriate. Defensible space and fire breaks would be established around Project work areas where needed to reduce available fuels and limit the potential for fire spread. Implementation of Mitigation Measure WF-2 would require adequate on-site water sources during high fire risk construction activities, which may include water trucks, water backpacks, and/or fire extinguishers. These measures would supplement compliance with applicable fire prevention regulations, permit conditions, and standard construction best management practices, including controlling ignition sources, maintaining equipment, restricting certain activities during high fire danger conditions as required, and maintaining emergency access throughout construction.

Following construction, the expanded NBRWTP and completed transmission pipeline would be consistent with existing land uses and would not substantially increase wildfire fuel loads, alter topography, modify prevailing wind patterns, or create conditions that would contribute to the uncontrolled spread of wildfire. The transmission pipeline would operate underground and would not introduce permanent wildfire hazards along either alignment. Although portions of the Project area are located near open space and grassland areas that may be susceptible to wildfire during hot, dry, and windy conditions, implementation of Mitigation Measures WF-1 and WF-2 would reduce construction-related wildfire risk by reducing available fuels and ensuring adequate fire suppression resources are available during high-risk activities.

Accordingly, with implementation of Mitigation Measures WF-1 and WF-2, the Project would not substantially exacerbate wildfire risks due to slope, prevailing winds, or other environmental factors, and would not expose Project occupants to substantial pollutant concentrations from a wildfire or the uncontrolled spread of wildfire. Impacts would be less than significant with mitigation incorporated.

Page 368 of 1497 ends

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) 4-225 c. Would the project require the installation or maintenance of associated infrastructure (such as roads, fuel breaks, emergency water sources, power lines or other utilities) that may exacerbate fire risk or that may result in temporary or ongoing impacts to the environment? Less Than Significant Impact. The NBRWTP improvements would occur within the existing developed utility facility and would not require new off-site roads, fuel breaks, emergency water sources, or major linear infrastructure in surrounding open-space areas. Utility connections needed to support the expanded treatment facilities would occur primarily within the existing NBRWTP property or established utility corridors.

The Linear Trail Pipeline Alignment would generally follow an existing transmission main corridor adjacent to the Putah South Canal and former railroad corridor. Portions of this alignment traverse open space, utility corridors, and access-road areas outside paved roadways. Construction and long-term maintenance may require restoration, widening, or improvement of all-weather access routes to provide safe access for routine maintenance and emergency repair activities. These improvements could result in localized vegetation removal, grading, or surface disturbance; however, they would occur within or adjacent to existing utility and access corridors and would not create a new roadway network or substantially increase public access into undeveloped wildland areas. Vegetation management associated with access improvements would be limited to that necessary for construction, maintenance, and fire-safe access and would not substantially increase wildfire ignition risk.

The Peabody Road Pipeline Alignment would be located primarily within or adjacent to the existing Peabody Road corridor and other previously disturbed transportation and utility areas. This alignment would not require construction of new permanent access roads through open space areas. Any utility adjustments, temporary staging, or access improvements would occur within or adjacent to existing roadway and utility corridors and would be restored following construction, as applicable.

Construction activities associated with either alignment could temporarily increase wildfire ignition risk through the use of vehicles, heavy equipment, welding, cutting, generators, and other construction equipment. However, construction would be required to comply with applicable fire safety regulations and standard construction best management practices, including maintaining fire extinguishing equipment on-site, controlling ignition sources, maintaining emergency access, managing vegetation in active work areas, and coordinating with local fire and public works agencies, as appropriate.

Operation of the completed Project would not require new fuel breaks, permanent emergency water sources, aboveground power transmission lines, or other infrastructure that would substantially exacerbate wildfire risk. The transmission pipeline would operate underground, and routine maintenance activities would be periodic and limited in scope. Because infrastructure associated with the Project would be limited, primarily located within existing developed or utility corridors, and subject to applicable fire safety and environmental controls, the Project would not exacerbate fire risk or result in significant temporary or ongoing environmental impacts related to infrastructure associated with the Project. Impacts would be less than significant.

Page 369 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026
4 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -226 d. Would the project expose people or structures to significant risks, including downslope or downstream flooding or landslides, as a result of runoff, post-fire slope instability, or drainage changes?
Less Than Significant Impact. The NBRWTP is on relatively flat terrain characterized by gentle slopes and limited topographic relief. The facility consists of developed utility infrastructure, including treatment basins, buildings, access roads, and associated drainage facilities. Stormwater runoff from the NBRWTP is currently managed through an existing stormwater conveyance system that directs runoff to local drainage facilities in accordance with applicable municipal stormwater requirements.

The Project area is not located within an area known for significant landslide hazards, steep slopes, or terrain susceptible to widespread slope instability.

The Linear Trail Pipeline Alignment traverses a combination of utility corridors, open space areas, and drainage features, including areas adjacent to Union Creek, the Putah South Canal, South Putah Creek, and other localized drainage facilities. Construction activities would require temporary trenching, excavation, and soil disturbance that could temporarily alter localized drainage patterns within active work areas. However, disturbed areas would be restored following construction, erosion and sediment control measures would be implemented in accordance with the State Construction General Permit and applicable stormwater requirements, and drainage conveyance features would be maintained or restored to pre-construction conditions. The alignment traverses generally level terrain and does not include substantial slopes that would be susceptible to post-fire slope instability, debris flows, or landslide hazards.

The Peabody Road Pipeline Alignment would be located primarily within or adjacent to existing roadway and utility corridors characterized by relatively flat terrain and established drainage infrastructure. Construction activities would require temporary trenching, excavation, and soil disturbance that could temporarily alter localized drainage patterns within active work areas.

However, disturbed areas would be restored following construction, erosion and sediment control measures would be implemented in accordance with the State Construction General Permit and applicable stormwater requirements, and existing drainage facilities would be maintained or restored to pre-construction conditions. Similar to the Linear Trail Pipeline Alignment, the corridor traverses generally level terrain and does not contain steep slopes that would be susceptible to post-fire slope instability, debris flows, or landslide hazards.

Operation of the completed Project would not substantially alter regional drainage patterns, increase flood risk, create unstable slopes, or place structures in areas susceptible to post-fire debris flows or landslides. The NBRWTP improvements would be within an existing developed utility facility, and the transmission pipeline would operate underground following restoration of surface conditions. The Project would not introduce development into wildfire-prone mountainous terrain where post-fire flooding, debris flows, or slope instability are typically of greatest concern.

Furthermore, the Project would not substantially increase impervious surfaces or modify drainage systems in a manner that would expose people or structures to increased flooding risks.

Because any temporary drainage-related effects during construction would be minor, localized, and controlled through compliance with applicable stormwater, erosion control, and restoration requirements, and the Project site is generally flat and not susceptible to slope instability and

Page 370 of 1497 ends

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) 4-227 landslides, and would not alter drainage or cause flooding, the Project would not expose people or structures to significant risks associated with runoff, post-fire slope instability, drainage changes, flooding, or landslides. Therefore, impacts would be less than significant.

4.20.4 Mitigation Measures
Mitigation Measure WF-1 Defensible Space. Prior to and during construction, the Contractor shall implement measures to reduce wildfire risk within and adjacent to active work areas. Measures will include, as appropriate:
• Highly flammable vegetation near Project areas will be trimmed to reduce fire fuel, as appropriate
• Dispose of debris, such as dry debris, leaves, and dead limbs near and within the Project areas
• Design of defensible spaces with fire breaks around the Project site, as appropriate
Mitigation Measure WF-2 Fire Suppression Equipment During Construction. Prior to the start of construction and throughout all construction activities, the Contractor will maintain appropriate fire suppression equipment at active work areas whenever construction activities have the potential to generate sparks, flames, or other ignition sources, or when work is conducted during periods of elevated fire danger as determined by the applicable fire authority or Red Flag Warning conditions. Applicable activities may include, but are not limited to, welding, cutting, grinding, use of internal combustion equipment, and other hot work.

Fire suppression equipment will be readily accessible at active work areas and, as appropriate, will include water trucks, portable water backpacks, fire extinguishers with the appropriate fire rating, or other fire suppression equipment approved by the applicable fire authority.

Page 371 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD - V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026
4 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -228

4.21 MANDATORY FINDINGS OF SIGNIFICANCE
Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a. Does the project have the potential to substantially degrade the quality of the environment, substantially reduce the habitat of a fish or wildlife species, cause a fish or wildlife population to drop below self-sustaining levels, threaten to eliminate a plant or animal community, substantially reduce the number or restrict the range of a rare or endangered plant or animal or eliminate important examples of the
major periods of California history or prehistory?
b. Does the project have impacts that are individually limited, but cumulatively considerable? (“Cumulatively considerable” means that the incremental effects of a project are
considerable when viewed in connection with the effects of past projects, the effects of other current projects, and the effects of probable future projects.)
c. Does the project have environmental effects which will cause substantial adverse effects on human beings, either directly or indirectly?

4.21.1 Impact Analysis
a. Does the project have the potential to substantially degrade the quality of the environment, substantially reduce the habitat of a fish or wildlife species, cause a fish or wildlife population to drop below self-sustaining levels, threaten to eliminate a plant or animal community, substantially reduce the number or restrict the range of a rare or endangered plant or animal or eliminate important examples of the major periods of California history or prehistory? Less Than Significant with Mitigation Incorporated. As discussed in Section 5.4, Biological Resources, the Project has the potential to significantly impact various special-status species, including various special-status plant species, vernal pool fair shrimp and vernal pool tadpole shrimp, Crotch’s bumble bee, Monarch butterfly, California tiger salamander, northwestern pond turtle, burrowing owl, Swainson’s hawk, tricolored blackbird, other migratory birds, and American badger. However, with implementation of Mitigation Measures BIO-1 through BIO-43, potential Project-related impacts to special-status species would be less than significant. Mitigation Measures BIO-1 through BIO-43 require the following: obtaining all required authorizations from USFWS and/or CDFW; providing environmental awareness training to people working at the Project site; the completion of protocol-level preconstruction special-status plant surveys for all potentially occurring species by a qualified botanist; completing consultation with CDFW and USFWS if special-status plant populations are present to determine appropriate mitigation measures and permit requirements; restoration of existing wetlands and uplands to pre-disturbance conditions at a 1:1 ratio; providing a temporary restoration plan for review and approval by regulatory agencies; mitigating for loss of modeled vernal pool and upland habitat; restoring wetlands and uplands to pre-disturbance conditions to mitigate for temporary effects; preserving vernal pool and swale habitats to mitigate for permanent effects; completing focused surveys for special-status species

Page 372 of 1497 ends

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) 4-229 that have the potential to occur at the Project site; conducting preconstruction surveys to identify active nests; establishing non-disturbance buffers if evidence of any special status-species, nests, or dens are detected during the focused survey; relocating or following proper procedure should special status species or habitat/nesting sites be discovered; preparing and implementing a revegetation plan; mitigating for loss of permanent impacts to grassland habitat conducting preconstruction surveys for milkweed and nectar plants; placing buffers around milkweed and nectar plants if present during breeding season; reseeding temporarily impacted grassland areas; limiting ground-disturbing work to the dry season; only initiating ground disturbing activities after a 72-hour, no precipitation forecast is obtained and ceasing ground disturbance activities 24 hours prior to a 40 percent or greater chance of rain forecast; submitting a California Tiger Salamander Relocation Plan to CDFW and USFWS; installing a temporary barrier fence; completing daily preconstruction surveys by a qualified biologist; implementing best management practices under the Project’s SWPPP; preserving grassland habitat at a 1:1 ratio for temporary impacts and 3:1 ratio for permanent impacts and creating 0.01 acre of breeding habitat for each acre of upland habitat permanently removed; preserving suitable burrowing owl habitat at a 3:1 ratio and preserving any lost nest sites at a 1:1 ratio; and preserving 3 acres of valley floor grassland habitat for every 1 acre of permanent impact and retaining active and suitable nest trees.

Several sensitive natural communities have also been identified within the Project area, including riparian habitat associated with Union Creek and a detention basin, as well as seasonal wetlands and other jurisdictional waters. Construction activities associated with the Project could potentially impact these communities. To avoid or reduce potential impacts to sensitive natural communities, implementation of Mitigation Measures BIO-1 through BIO-23 would be required, which entail obtaining the necessary permits under Sections 404 and 401 of the federal Clean Water Act, the Porter-Cologne Water Quality Control Act, and Section 1602 of the California Fish and Game Code and implementing permit conditions; evaluating alternatives that avoid fill in any vernal pools, seasonal wetlands, or Union Creek; restoring wetland habitat at a 1:1 ratio for temporary impacts and a minimum 2:1 ratio for permanent impacts; and replacing native woody vegetation according to appropriate ratios and performance standards. With implementation of Mitigation Measures BIO-1 through BIO-23, impacts to riparian habitat and other sensitive natural communities would be less than significant.

To avoid or reduce potential impacts to wetlands, implementation of Mitigation Measures BIO-1, through BIO-23 would be required, which entail obtaining all required authorizations from USFWS and/or CDFW; mitigating for loss of modeled vernal pool and upland habitat; and obtaining the necessary permits under Sections 404 and 401 of the federal Clean Water Act, the Porter-Cologne Water Quality Control Act, and Section 1602 of the California Fish and Game Code and implementing permit conditions. With implementation of Mitigation Measures BIO-1 through BIO-23, impacts to wetlands would be less than significant.

As discussed in Section 4.5, Cultural Resources, implementation of the Project would not eliminate important examples of the major periods of California history or prehistory. A Cultural Resources Inventory identified no historical resources listed in or eligible for listing in the California Register of Historical Resources within the Project area. Although portions of the Project area retain the potential to contain previously undiscovered archaeological resources associated with California

Page 373 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026
4 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -230 prehistory, implementation of Mitigation Measures CUL-1 through CUL-5, including worker environmental awareness training, archaeological and tribal monitoring in sensitive areas, and procedures for the treatment of unanticipated discoveries and human remains, would reduce potential impacts to historical, archaeological, and tribal cultural resources to a less than significant level. Accordingly, the Project would not eliminate important examples of the major periods of California history or prehistory.

With implementation of mitigation and regulatory compliance measures, the potential for the Project to degrade the quality of the environment, substantially reduce the habitat of a fish or wildlife species, cause a fish or wildlife population to drop below self-sustaining levels, threaten to eliminate a plant or animal community, reduce the number or restrict the range of rare or endangered plants or animals, or eliminate important examples of the major periods of California history or prehistory would be less than significant.
b. Does the project have impacts that are individually limited, but cumulatively considerable? (“Cumulatively considerable” means that the incremental effects of a project are considerable when viewed in connection with the effects of past projects, the effects of other current projects, and the effects of probable future projects)?
Less Than Significant with Mitigation Incorporated. Section 15065(a)(3) of the State CEQA Guidelines states that a project’s cumulative impacts are the possible environmental effects that may be cumulatively considerable when considered with other reasonably foreseeable projects.

Cumulatively considerable impacts occur when the incremental effects of a particular project or program are significant when viewed in connection with the effects of other past, current, or reasonably foreseeable future projects. Section 15355 of the State CEQA Guidelines defines a cumulative impact as an impact that is created as a result of the combination of the project evaluated in the CEQA document together with other projects causing related impacts.

Based on the analysis provided throughout this IS/MND, the Project would have either no impact, a less than significant impact, or a less than significant impact with mitigation incorporated with respect to all environmental issues pursuant to CEQA. Furthermore, due to the limited scope of direct physical impacts to the environment associated with the Project, the Project’s impacts are primarily Project-specific in nature.

Although various projects within Fairfield and/or Vacaville have the potential to be under construction concurrent with the Project, concurrent projects within the Cities of Fairfield and Vacaville would be subject to independent CEQA review and regulations similar to those outlined in this document and would incorporate mitigation measures, as necessary, that would reduce impacts of the project. Implementation of the Project has the potential to result in effects to the environment that are individually limited and may be cumulatively considerable in the following areas: Biological Resources, Cultural Resources, Geology and Soils, Hazards and Hazardous Materials, Noise, Tribal Cultural Resources, and Wildfire. As shown in the discussion above, environmental impacts associated with the Project can be reduced to less than significant levels with the implementation of Project-specific mitigation measures or existing regulations. All Project-related impacts are localized and confined to the immediate Project area. Given that the potential Project-related impacts are less than significant and limited to the Project site, implementation of

Page 374 of 1497 ends

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) 4-231 the Project would not result in impacts that are cumulatively considerable when evaluated with the impacts of other current projects, or the effects of probable future projects. Therefore, cumulative impacts would be less than significant with mitigation incorporated. c. Does the project have environmental effects which will cause substantial adverse effects on human beings, either directly or indirectly?
Less Than Significant with Mitigation Incorporated. Implementation of the Project would result in temporary construction-related effects associated with air quality, biological resources, cultural resources, tribal cultural resources, geology and soils, hazards and hazardous materials, hydrology and water quality, noise, transportation, utilities and service systems, and wildfire. Long-term operational effects would primarily consist of continued operation of an expanded regional water treatment facility and underground treated water transmission pipeline within the existing service areas of the Cities of Fairfield and Vacaville. As discussed throughout this Initial Study/Mitigated Negative Declaration (IS/MND), the Project has been designed to avoid and minimize environmental impacts through project design features, compliance with applicable federal, State, and local regulations, and implementation of the mitigation measures identified in the MMRP.

Implementation of Mitigation Measures BIO-1 through BIO-23; CUL-1 through CUL-5 (which also address Tribal Cultural Resources); GEO-1 and GEO-2; HAZ-1; NOI-1; and WF-1 and WF-2 would reduce or avoid potentially significant environmental impacts identified in this IS/MND. These measures include, but are not limited to, airport compatibility review and preparation of a Wildlife Hazard Analysis, if required; worker environmental awareness training; preconstruction biological surveys; avoidance, minimization, monitoring, habitat restoration, and compensatory mitigation for special-status species and sensitive habitats; wetland permitting and mitigation; archaeological worker awareness training; tribal consultation and tribal monitoring; archaeological monitoring; procedures for the treatment of inadvertent discoveries of cultural resources and human remains; design-level geotechnical investigations; paleontological resource protection; hazardous materials management; construction noise controls; and wildfire prevention and fire suppression measures during construction.

With implementation of Mitigation Measures BIO-1 through BIO-23; CUL-1 through CUL-5; GEO-1 and GEO-2; HAZ-1; NOI-1; and WF-1 and WF-2, all potentially significant environmental impacts would be reduced to a less than significant level. Construction-related impacts would be temporary and localized, and long-term operation of the Project would not expose the public to significant hazards or result in environmental effects that would directly or indirectly cause substantial adverse effects on human beings. Accordingly, with implementation of the mitigation measures identified in the MMRP, the Project would not have environmental effects that would cause substantial adverse effects on human beings, either directly or indirectly.

Page 375 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATERWORKS P ROJECT

F AIRFIELD , C ALIFORNIA

INITIAL S TUDY /MITIGATED NEGATIVE DECLARATION
OCTOBER 2026
4 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -232 This page intentionally left blank

Page 376 of 1497 ends

5-1

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26)

5.0 MITIGATION MONITORING AND REPORTING PROGRAM (MMRP)
This Mitigation Monitoring and Reporting Program (MMRP) is formulated based upon the findings of the Initial Study/Mitigated Negative Declaration (IS/MND) prepared for the North Bay Regional Water Treatment Plant, Fairfield-Vacaville Water Works Project (Project). The MMRP, which is found in Table 1, lists mitigation measures recommended in the IS/MND prepared for the Project and identifies mitigation monitoring requirements. The Final MMRP must be adopted when the City of Fairfield (City) makes a final decision on the Project.

This MMRP has been prepared to comply with the requirements of State law (Public Resources Code Section 21081.6). State law requires the Lead Agency to adopt an MMRP when mitigation measures are required to avoid significant impacts. The MMRP is intended to ensure compliance with the mitigation measures identified in the IS/MND during implementation of the Project.

The MMRP is organized in a matrix format. The first two columns identify the potential impacts and corresponding mitigation measures. The third column, entitled “Timeframe for Implementation,” refers to when monitoring will occur to ensure that the mitigating action is completed. The fourth column, entitled “Responsibility for Implementation,” refers to the party responsible for implementing the mitigation measure. The fifth column, entitled, “Oversight of Implementation,” refers to the party responsible for oversight or ensuring that the mitigation measure is implemented.

Page 377 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
5 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -2 This page intentionally left blank

Page 378 of 1497 ends

5-1

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD - V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation

4.4 Biological Resources
Potential
impacts to
listed,
candidate, or
proposed
special-status
species.

MM-BIO-1: Permitting and Regulatory Compliance. The Project applicant(s) shall obtain all required authorizations from the United States Fish and Wildlife Service (USFWS) and/or the California Department of Fish and Wildlife (CDFW) for actions resulting in the incidental take of or effects on listed, candidate, or proposed species under the Endangered Species Act (ESA) and/or the California Endangered Species Act (CESA) prior to the start of construction and shall comply with all avoidance, minimization, and mitigation requirements specified in the permit(s).

Prior to initiating
ground disturbance
activities
Project Proponent
City of Fairfield/City of
Vacaville Director, or
designee
Potential
impacts to
special-status
species during
construction.

MM-BIO-2: Onsite Worker Environmental Awareness Training. Prior to the initiation of work, an environmental awareness training shall be provided by a qualified biologist to all people working at the Project site.

The training shall be conducted by a qualified biologist and shall include a discussion of biology and general behavior, distribution and habitat needs, sensitivity to human activities, and status pursuant to the ESA and the CESA for all special-status species potentially impacted by the Project. The training shall also include information on Project-specific protection measures and penalties for violations. Interpretation shall be provided for non-English-speaking workers, and the same instruction shall be provided to any new workers before they are authorized to perform work at the Project site. Upon completion of the program, employees shall be required to sign a form stating they attended the training and understand all protection measures.

Prior to any
construction activities
and vegetation
removal
Qualified Biologist
City of Fairfield/City of
Vacaville Director, or
designee
Potential
impacts to
special-status
plant species.

MM-BIO-3: Special Status Plants. A qualified botanist shall conduct protocol-level preconstruction special-status plant surveys in accordance with CDFW’s 2018 Protocol for Surveying and Evaluating Impacts to Special-Status Native Plant Populations and Sensitive Natural Communities, or subsequent applicable CDFW guidance, and during the appropriate blooming or identifiable period for potentially occurring species. The surveys shall be conducted no more than two growing seasons prior to and no later than the blooming period prior to the start of ground-disturbing activities. If no special-status plants are found during focused surveys, no additional mitigation is required.

No more than two
growing seasons prior
to and during the
blooming period
before ground
disturbance;
restoration monitoring
for a minimum of two
growing seasons, if
required
Qualified Biologist
City of Fairfield/City of
Vacaville Director, or
designee;
CDFW/USFWS, as
applicable

Page 379 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
5 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -2 Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
 If special-status plant populations are present, the Project applicant(s) shall consult with CDFW and USFWS, as appropriate, to determine appropriate mitigation measures and permit requirements for direct and indirect impacts on any special-status plant population. In general, special-status plant populations shall be avoided to the maximum extent feasible. Possible avoidance measures include fencing populations before construction and exclusion of Project activities from the fenced-off areas, and construction monitoring by a qualified botanist to keep construction crews away from the population.  Temporary effects to seasonal wetlands and uplands supporting special-status plants lasting no more than one growing season shall be mitigated by restoring the existing wetlands and uplands to pre-disturbance conditions by the end of the following growing season at a 1:1 ratio. Long-term effects lasting longer than one growing season shall be mitigated as though they are permanent impacts under Mitigation Measure BIO-4, below.
 The applicant shall provide a temporary restoration plan for review and approval by the regulatory agencies to ensure successful restoration of temporarily disturbed areas and any affected special-status plant populations prior to completing the Project. All temporarily affected habitats shall be monitored for a minimum of two growing seasons to document that wetland hydrology and vegetation have been restored to pre-Project conditions. Additional monitoring and remedial measures, including possible mitigation, may be required if hydrology is not reestablished or special-status plants fail to meet performance criteria established in the restoration plan.

Potential
impacts to
loss of
modeled
vernal pool
and
associated
upland
habitat
MM-BIO-4: Vernal Pool and Upland Habitat Conservation. Prior to the initiation of ground-disturbing activities, the Project Applicant shall mitigate for the permanent loss of modeled vernal pool and associated upland habitat supporting special-status plant and wildlife species. Habitat mitigation shall be accomplished through one or a combination of the following: (1) purchase of credits at an approved mitigation bank; (2) onsite habitat preservation; (3) offsite conservation lands; or (4) another mitigation strategy approved by the applicable regulatory agencies that provides equivalent conservation value. All mitigation lands shall be Prior to initiating
ground-disturbing
activities
Project Proponent
City of Fairfield/City of
Vacaville Director, or
designee; applicable
regulatory agencies

Page 380 of 1497 ends

5-3

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
supporting
special-status
species.
permanently protected through a conservation easement or other approved long-term protection mechanism.

Where appropriate, habitat mitigation may overlap with mitigation required for Crotch's bumble bee, monarch butterfly, California tiger salamander, burrowing owl, and Swainson's hawk, provided all applicable mitigation requirements and habitat functions are fully achieved.

Potential
temporary
and
permanent
impacts to
seasonal
wetlands,
vernal pools,
swales, and
associated
uplands.

MM-BIO-5: Wetland Restoration and Compensation. Consistent Temporary impacts to seasonal wetlands and associated uplands that persist for no more than one growing season shall be restored to pre-disturbance conditions no later than the end of the first growing season following construction. Prior to construction, the Project Applicant shall prepare and submit a Wetland Restoration Plan, for approval by the applicable regulatory agencies. The plan shall include restoration methods, performance standards, contingency measures, and a monitoring program. Restored wetlands shall be monitored for a minimum of two wet seasons to document successful restoration of hydrology and native vegetation. If monitoring demonstrates that hydrology or vegetation has not been restored to pre-project conditions, additional monitoring, adaptive management, remedial actions, or compensatory mitigation shall be implemented in consultation with the applicable regulatory agencies. Permanent wetland impacts shall be mitigated as follows:
 Indirect impacts to avoided vernal pools and swales located within 250 feet of project development shall be compensated through preservation of comparable habitat at a minimum ratio of 1:1.  Direct impacts to vernal pools and swales shall be compensated through preservation at a minimum ratio of 2:1 and restoration at a ratio of 1:1 where restored habitat is established and functional prior to project impacts, or 2:1 where restoration occurs concurrent with or after project impacts.

Prior to construction;
restoration following
construction;
monitoring for a
minimum of two wet
seasons
Project Proponent
City of Fairfield/City of
Vacaville Director, or
designee; applicable
regulatory agencies

Page 381 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
5 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -4 Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
Potential
temporary
impacts to
grassland
habitat.

MM-BIO-6: Grassland Restoration. All temporarily disturbed grassland habitats shall be restored using native plant plugs, native forb seed mixes, or other appropriate plant materials that are compatible with pre-project habitat conditions. A Grassland Revegetation Plan shall be submitted to the California Department of Fish and Wildlife (CDFW) for review and approval at least 90 days prior to implementation. Temporary impacts to seasonal wetlands and associated uplands that persist for no more than one growing season shall be restored to pre-disturbance conditions no later than the end of the first growing season following construction.

The plan shall identify restoration methods, seed and plant sources, success criteria, monitoring requirements, contingency measures, and measures to provide suitable habitat for Crotch's bumble bee and monarch butterfly, including the use of insecticide-free flowering species that provide pollen and nectar resources. All seed and plant materials shall originate from stock collected within California's Great Central Valley unless otherwise approved in writing by CDFW. Neonicotinoid insecticides shall not be used within restoration areas. Revegetation shall be completed as soon as practicable and no later than one year following completion of construction in the affected area. Monitoring shall continue until performance standards identified in the approved Revegetation Plan are achieved.

Where appropriate, grassland restoration may also satisfy mitigation requirements for Crotch's bumble bee, monarch butterfly, California tiger salamander, burrowing owl, and Swainson's hawk, provided all species-specific mitigation requirements are met.

Plan submitted at least
90 days prior to
implementation;
revegetation as soon
as practicable and no
later than one year
after construction in
the affected area;
monitoring until
performance standards
are achieved
Project
Proponent/Qualified
Biologist or Restoration
Specialist
City of Fairfield/City of
Vacaville Director, or
designee; CDFW
Potential
indirect
impacts to
avoided
upland
habitat within
250 feet of
Project
development.

MM-BIO-7: Indirect Upland Habitat Protection. Indirect impacts to avoided upland habitat located within 250 feet of project development shall be mitigated through preservation of comparable upland habitat at a minimum ratio of 1:1. Mitigation shall be accomplished through purchase of mitigation credits, onsite preservation, offsite conservation lands, or another mitigation strategy approved by the applicable regulatory agencies. All mitigation lands shall be permanently protected through a conservation easement or other approved long-term protection mechanism.

Prior to initiating
ground-disturbing
activities
Project Proponent
City of Fairfield/City of
Vacaville Director, or
designee; applicable
regulatory agencies

Page 382 of 1497 ends

5-5

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
Where appropriate, mitigation may overlap with habitat mitigation required for Crotch's bumble bee, monarch butterfly, California tiger salamander, burrowing owl, and Swainson's hawk, provided all applicable mitigation requirements are met.

Potential
permanent
direct impacts
to upland
habitat.

MM-BIO-8: Permanent Upland Habitat Compensation. Permanent direct impacts to upland habitat shall be mitigated through preservation of suitable habitat at a minimum ratio of 3:1. Mitigation shall be accomplished through one or a combination of the following: (1) purchase of credits at an approved mitigation bank; (2) onsite habitat preservation; (3) offsite conservation lands; or (4) another mitigation strategy approved by the applicable regulatory agencies that provides equivalent conservation value. All mitigation lands shall be permanently protected through a conservation easement or other approved long-term protection mechanism. temporarily disturbed grassland.

Where appropriate, upland habitat mitigation may overlap with mitigation required for Crotch's bumble bee, monarch butterfly, California tiger salamander, burrowing owl, and Swainson's hawk, provided all applicable mitigation requirements are fully satisfied.

Prior to initiating
ground-disturbing
activities
Project Proponent
City of Fairfield/City of
Vacaville Director, or
designee; applicable
regulatory agencies
Potential take
or adverse
effects on
Crotch's
bumble bee.

MM-BIO-9: Minimize Take and Adverse Effects on Crotch’s Bumblebee. A qualified biologist shall conduct a focused survey of all suitable habitat within and adjacent to the Project before the start of any ground-disturbing activities at a time when Crotch’s bumble bee is most likely to be identified, typically from April through August when floral resources and ideal weather conditions are present. Surveys shall follow the methods in Survey Considerations for California Endangered Species Act (CESA) Candidate Bumble Bee Species (CDFW 2023) or any subsequent protocol approved by CDFW. If Crotch’s bumble bees are not detected during the focused survey, no additional mitigation is required.

If Crotch’s bumble bees are detected during the focused survey, non-disturbance buffers shall be established around active nesting colonies until a qualified biologist has determined that they are no longer active.

The size of the buffer shall be determined by the qualified biologist in Focused survey prior to
ground-disturbing
activities during the
active season (typically
April-August); buffers
maintained during
construction while
nests remain active
Project
Proponent/Qualified
Biologist/Construction
Contractor
City of Fairfield/City of
Vacaville Director, or
designee; CDFW

Page 383 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
5 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -6 Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
consultation with CDFW but shall typically be at least 50 feet. The buffer shall be delineated using high-visibility fencing, flagging, or similar materials along with appropriate signage. Construction personnel shall be informed of the nest location and avoidance requirements during the preconstruction environmental awareness training. Use of neonicotinoid insecticides shall not be used within non-disturbance buffers.

Preconstruction surveys shall be completed prior to the initiation of ground-disturbing activities during the active season for Crotch's bumble bee. Nest avoidance measures and buffers shall be maintained throughout construction while the nest remains active.

If Crotch’s bumble bee is detected and take cannot be avoided through implementation of avoidance measures, the Project applicant shall obtain applicable incidental take authorization from CDFW prior to conducting activities that could result in take and shall comply with the terms and conditions of such authorization.

Potential take
or adverse
effects on
monarch
butterfly.

MM-BIO-10: Minimize Take and Adverse Effects on Monarch Butterfly.

Preconstruction surveys for milkweed and nectar plants shall be conducted during the monarch breeding season (March 16 through November 30) to determine if milkweed is present within the site and is being used for monarch breeding. Surveys shall be conducted by a qualified biologist no more than 14 days prior to ground or vegetation disturbance. The biologist shall search for evidence of monarch eggs, caterpillars, chrysalises, and adults. If no active monarch breeding is identified, no further mitigation is required.

If milkweed is present and monarch eggs, larva, or pupa (chrysalis) are present during breeding season from March 16 to November 30, buffers shall be placed around patches of milkweed and associated nectar plants.

No vegetation removal or herbicide use may occur inside of the buffers.

Buffer size shall be determined by the qualified biologist in consultation with USFWS; the expected buffer size is 125 feet. Buffers shall remain in place throughout the monarch breeding season or until all monarch breeding activity has been completed. Vegetation removal is allowed without restriction between December 1 and March 15.

Within 14 days prior to
ground or vegetation
disturbance during the
breeding season
(March 16-November
30); buffers
maintained as required
Project
Proponent/Qualified
Biologist/Construction
Contractor
City of Fairfield/City of
Vacaville Director, or
designee; USFWS, as
applicable

Page 384 of 1497 ends

5-7

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
Potential take
or adverse
effects on
California
tiger
salamander.

MM-BIO-11: Minimize Take and Adverse Effects on California Tiger Salamander. To minimize the potential for take of California tiger salamander, initial ground-disturbing activities within designated tiger salamander habitat areas shall be limited to the dry season (June 15 and October 15), unless otherwise approved by CDFW and USFWS and/or as approved through the permitting process outlined in MM-BIO-01. Ground-disturbing activities may only commence following confirmation of a 72- hour forecast from the National Weather Service (NWS) indicating no precipitation at the Project site. Ground disturbance shall cease at least 24 hours before the NWS forecasts a 40 percent or greater chance of precipitation and may resume no sooner than 24 hours after rainfall has ended, provided no precipitation is forecast within the subsequent 24- hour period.

At least 30 days prior to the initiation of construction, the Project Applicant shall prepare and submit a California Tiger Salamander Relocation Plan to CDFW and USFWS for review and approval. The approved plan shall describe relocation procedures, suitable release locations, monitoring requirements, and reporting protocols.

A temporary barrier fence shall be installed prior to the start of work to prevent California tiger salamanders from entering the Project site. The fence shall be designed to allow California tiger salamanders to leave the Project site using one-way funnels or other methods approved by regulatory agencies. The fence shall remain in place until work is completed, including during periods of inactivity. Coverboards shall be placed along the fence on both sides to provide refuge. A qualified biologist shall inspect fencing and cover boards daily during active work periods and weekly during periods of inactivity or during and following storm events. Animals found within the Project site may be relocated outside of the barrier by a qualified biologist in accordance with an approved relocation plan.

Daily California tiger salamander preconstruction surveys shall be conducted by a qualified biologist. The biologist shall survey suitable Relocation Plan at least
30 days prior to
construction; fencing
and surveys prior to
and during ground-disturbing activities
Project
Proponent/Qualified
Biologist/Construction
Contractor
City of Fairfield/City of
Vacaville Director, or
designee;

CDFW/USFWS

Page 385 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
5 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -8 Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
habitat within the work area prior to disturbance. The survey shall also include all construction pipes, culverts, and similar structures if they are not capped to prevent animal entry. If a California tiger salamander is found, the qualified biologist may move it out of the work area in accordance with an approved relocation plan.

If take of California tiger salamander cannot be avoided, prior to conducting activities that could result in take, the Project applicant shall obtain applicable incidental take authorization from CDFW pursuant to CESA and authorization from USFWS pursuant to the federal Endangered Species Act, as applicable, and shall comply with the terms and conditions of such authorization.

Potential
temporary
and
permanent
impacts to
California
tiger
salamander
habitat and
movement
corridors.

MM-BIO-12: California Tiger Salamander Habitat Compensation. To compensate for impacts to California tiger salamander habitat and movement corridors, the Project Applicant shall implement habitat mitigation. Temporary impacts to upland grassland habitat shall be compensated through preservation or restoration at a minimum ratio of 1:1. Permanent impacts to upland habitat shall be compensated through preservation at a minimum ratio of 3:1. Habitat mitigation may be accomplished through approved mitigation banks, onsite preservation, offsite conservation lands, or another mitigation strategy approved by the applicable regulatory agencies. Preserved lands shall be permanently protected through a conservation easement or other approved long-term protection mechanism.

In addition, the Project Applicant shall create a minimum 0.01 acre of California Tiger Salamander breeding habitat for each acre of upland habitat permanently removed. Created breeding habitat shall consist of seasonal wetlands meeting the following minimum criteria:
 Each wetland created as breeding habitat shall be a minimum of 0.02 acre.
 Multiple created compensatory breeding habitats may be clustered within 1,300 feet of each other
 Created wetland shall be within 2,100 feet of known breeding habitat Prior to initiating
ground-disturbing
activities; habitat
creation and
monitoring in
accordance with
approved plan
Project Proponent
City of Fairfield/City of
Vacaville Director, or
designee;

CDFW/USFWS

Page 386 of 1497 ends

5-9

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
 Created wetlands shall be located within or adjacent to at least 300 contiguous acres of suitable upland habitat.

A Habitat Mitigation and Breeding Habitat Creation Plan shall be submitted to CDFW and USFWS for review and approval prior to implementation. The plan shall include construction specifications, performance standards, long-term management, monitoring, adaptive management measures, and financial assurances sufficient to ensure successful establishment of breeding habitat.

Potential take
or adverse
effects on
northwestern
pond turtle
and nests.

MM-BIO-13: Minimize Take and Adverse Effects on Northwestern Pond Turtle. A qualified biologist shall conduct a preconstruction survey for northwestern pond turtles and active nests within all suitable aquatic habitat and potential nesting habitat (upland loose soils, sands, sediment bars, grassy areas, or duff that is within 1,500 feet of a waterways which may support breeding or hibernation). Surveys shall be completed within seven days prior to the initiation of ground-disturbing activities and shall encompass the construction footprint and a minimum 100-foot buffer.

Surveys shall be conducted under suitable environmental conditions including sunny days between 9:00 a.m. and 4:00 p.m., with air temperatures between 55 and 90 degrees Fahrenheit, and wind speeds less than 12 miles per hour.

Individual turtles may be relocated by a qualified biologist to an appropriate nearby location, if necessary. Relocation areas shall be approved by the CDFW prior to the relocation of any turtles. If an active nest is found, a 50-foot buffer shall be placed around the nest. No work shall occur within the buffer until the eggs have hatched or the nest is no longer active, as determined by a qualified biologist.

Prior to the start of Project activities, exclusionary fencing shall be installed around the work area to ensure that northwestern pond turtles are kept out of the construction area. The fencing shall be maintained throughout the duration of construction. The integrity of the exclusion fencing shall be checked daily by a biological monitor. Additionally, a biological monitor shall check the work area every morning before Within 7 days prior to
ground-disturbing
activities; daily
monitoring during
construction
Project
Proponent/Qualified
Biologist/Construction
Contractor
City of Fairfield/City of
Vacaville Director, or
designee; CDFW

Page 387 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
5 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -10 Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
construction begins to ensure that no turtles are within the exclusion area.

Potential take
or adverse
effects on
burrowing
owl.

MM-BIO-14: Minimize Take and Adverse Effects on Burrowing Owls. A qualified biologist shall conduct a preconstruction survey in accordance with CDFW’s 2012 Staff Report on Burrowing Owls (CDFG 2012). Surveys for nesting burrowing owls shall be conducted if Project construction starts during nesting season (February 1 to August 31), and surveys for wintering burrows owls shall be conducted if the construction starts during the wintering season (September 1 to January 31). The surveys shall encompass the Project area and surrounding suitable habitat within the applicable survey area as identified in CDFWs 2012 Staff report on Burrowing Owl Mitigation, to the extent that access is available or the area can otherwise be adequately surveyed, to detect burrowing owls that may be affected by Project activities. Surveys shall occur each year of Project construction, as conditions may change annually and suitable refugia for burrowing owl, such as small mammal burrows, can be created within a few hours or days, unless otherwise approved in writing by CDFW. Time lapses between surveys or Project activities shall trigger subsequent surveys including, but not limited to, a final survey within 24 hours prior to ground disturbance.

If an active burrow is found during the non-breeding season (September 1 through January 31) and cannot be avoided or adequately protected, the Project applicant shall obtain the necessary incidental take permit from the CDFW and may evict the owls from the area using passive relocation as described in CDFW’s Staff Report on Burrowing Owls (CDFG 2012) or as specified in the incidental take permit.

If an active burrow is found during the breeding season (February 1 through August 31), an appropriate avoidance buffer shall be established by the qualified biologist in accordance with CDFW’s 2012 Staff Report on Burrowing Owl Mitigation, based on the season, type and intensity of Project activity, existing site conditions, and anticipated potential for disturbance. The buffer shall be maintained until the burrow is no longer occupied or the qualified biologist determines that Project activities would Preconstruction
surveys each year of
construction, including
a final survey within 24
hours prior to ground
disturbance;
buffers/avoidance
during construction as
required
Project
Proponent/Qualified
Biologist/Construction
Contractor
City of Fairfield/City of
Vacaville Director, or
designee; CDFW

Page 388 of 1497 ends

5-11

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
not result in disturbance or take. If take cannot be avoided, the Project applicant shall obtain applicable incidental take authorization from CDFW prior to conducting activities that could result in take.

Potential
permanent
loss or
conversion of
burrowing
owl habitat.

MM-BIO-15: Burrowing Owl Habitat Compensation. Project applicants shall mitigate for the permanent loss or conversion of burrowing owl habitat (i.e., valley floor or vernal pool grassland) by preserving suitable habitat at a 3:1 ratio. Habitat mitigation may be accomplished through one or a combination of the following: (1) purchase of credits at an approved mitigation bank; (2) onsite habitat preservation; (3) offsite conservation lands; or (4) another mitigation strategy approved by the applicable regulatory agencies that provides equivalent conservation value. All mitigation lands shall be permanently protected through a conservation easement or other approved long-term protection mechanism.

Where appropriate, preserved grassland habitat may also satisfy habitat mitigation requirements for California tiger salamander and Swainson's hawk, provided all species-specific mitigation requirements and habitat functions are fully achieved.

Prior to permanent
loss or conversion of
suitable habitat
Project Proponent
City of Fairfield/City of
Vacaville Director, or
designee; CDFW, as
applicable
Potential
permanent
loss of active
burrowing
owl nest sites.

MM-BIO-16: Burrowing Owl Nest Compensation. If preconstruction surveys identify active burrowing owl nests that cannot be avoided and would be permanently lost as a result of Project activities the Project Applicant shall mitigate the loss through permanent preservation of occupied or otherwise suitable burrowing owl nest sites at a minimum of ratio of 1:1, consistent with applicable CDFW guidance.

Preservation sites shall include suitable nesting and foraging habitat and be within Solano County, unless otherwise approved by agency review.

Preserved lands shall be permanently protected through a conservation easement or other approved long-term protection mechanism and shall be managed in perpetuity under an approved long-term management and monitoring plan.

Prior to disturbance of
an active nest site that
cannot be avoided
Project Proponent
City of Fairfield/City of
Vacaville Director, or
designee; CDFW, as
applicable

Page 389 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
5 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -12 Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
Potential take
or adverse
effects on
Swainson's
hawk.

MM-BIO-17: Minimize Take and Adverse Effects on Swainson’s Hawk. A qualified biologist shall conduct preconstruction surveys to identify active Swainson’s Hawk nests on and within 0.5 mile of the Project site. The surveys shall be conducted no more than 14 days prior to the start of construction. Guidelines provided in Recommended Timing and Methodology for Swainson’s Hawk Nesting Surveys in the Central Valley (Swainson’s Hawk Technical Advisory Committee 2000) shall be followed.

If no nests are found, no further mitigation is required.

If a Swainson’s hawk nest is found, a buffer shall be established around the nest. No work shall be conducted within the buffer until a qualified biologist has determined that the young have fledged or the nest is no longer active. CDFW guidelines recommend implementation of 0.25- or

0.5-mile-wide buffers, but the size of the buffer may be adjusted if a qualified biologist, in consultation with CDFW, determines that such an adjustment would not be likely to adversely affect the nest. Monitoring of the nest by a qualified biologist during and after construction activities shall be required if the activity has potential to adversely affect the nest.

An incidental take permit (Mitigation Measure BIO-1) from CDFW may be required if construction disturbance could result in abandonment or lowered productivity of an active nest.

Within 14 days prior to
construction; buffers
and monitoring
maintained during
construction as
required
Project
Proponent/Qualified
Biologist/Construction
Contractor
City of Fairfield/City of
Vacaville Director, or
designee; CDFW
Potential
permanent
impacts to
Swainson's
hawk foraging
habitat.

MM-BIO-18: Swainson’s Hawk Habitat Compensation. Permanent impacts to Swainson’s hawk foraging habitat shall be mitigated through the preservation of suitable foraging habitat at a ratio of 3 acres of valley floor grassland habitat be preserved for every 1 acre Active and suitable nest trees within and adjacent to foraging habitat be retained through (1) permanent preservation of the species’ foraging habitat through a conservation easement and implementing and funding a long-term management plan in perpetuity, or (2) purchase of Swainson’s hawk foraging habitat credits at a CDFW-approved mitigation bank in the Solano County This mitigation can be concurrent with mitigation for California tiger salamander habitat under Mitigation Measure BIO-4 provided the valley floor grassland habitat preserved is suitable for both species.

Prior to permanent
impacts to suitable
foraging habitat
Project Proponent
City of Fairfield/City of
Vacaville Director, or
designee; CDFW, as
applicable

Page 390 of 1497 ends

5-13

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
Potential take
or adverse
effects on
tricolored
blackbird.

MM-BIO-19: Minimize Take and Adverse Effects on Tricolored Blackbirds. To avoid and minimize impacts to tricolored blackbird, the Project applicant(s) shall conduct a preconstruction survey prior to any Project activity that would occur during the nesting season (February 1– August 31). The preconstruction survey shall be conducted by a qualified biologist before any activity occurring within 500 feet of suitable nesting habitat, including freshwater marsh, riparian scrub, and ruderal (weedy) areas. The survey shall be conducted within 5 days prior to the start of Project activity. As Tricolored blackbirds may renest late in the breeding season an additional survey may be required later in the breeding season (summer) depending on the timing of construction and availability of nesting habitat within or adjacent to the project. If no tricolored blackbird colony is present, no further mitigation is required.

If a colony is found, the qualified biologist shall establish a buffer around the nesting colony. No Project activity shall commence within the buffer area until a qualified biologist confirms that the colony is no longer active.

The size of the buffer shall be determined in consultation with CDFW.

Buffer size is anticipated to range from 100 to 500 feet, depending on the nature of the Project activity, the extent of existing disturbance in the area, and other relevant circumstances.

The preconstruction survey shall be conducted by a qualified biologist before any activity occurring within 500 feet of suitable nesting habitat, including freshwater marsh, riparian scrub, and ruderal (weedy) areas.

Within 5 days prior to
Project activities
occurring during
nesting season
(February 1-August
31); additional surveys
and buffers during
construction as
required
Project
Proponent/Qualified
Biologist/Construction
Contractor
City of Fairfield/City of
Vacaville Director, or
designee; CDFW
Potential
impacts to
nesting
migratory
birds.

MM-BIO-20: Minimize Take and Adverse Effects on Other Migratory Birds. A nesting bird survey shall be conducted by a qualified biologist prior to any ground disturbing work occurring during the nesting season (February 1 to August 31). The survey shall extend out 500 feet from the boundaries of the Project site to the extent feasible based on land uses and ownership of surrounding properties. The survey shall be completed no more than 5 days prior to the start of work. If no nests are found, no further mitigation is required.

Within 5 days prior to
ground-disturbing
work during nesting
season (February 1-
August 31); buffers
maintained until nests
are inactive
Project
Proponent/Qualified
Biologist/Construction
Contractor
City of Fairfield/City of
Vacaville Director, or
designee

Page 391 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
5 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -14 Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
If an active nest is found, the qualified biologist shall establish a buffer around the nest site that shall be avoided until the young have fledged or the nest has otherwise become inactive. The size of the buffer shall be determined by the qualified biologist based on the nesting bird species and the context of the nest location relative to potential disturbance activities. Buffer size is expected to range from 50 to 500 feet, depending on the bird species, the nature of the Project activity, the extent of existing disturbance in the area, and other relevant circumstances.

If ground-disturbing activities cease for 5 consecutive days or more during the nesting season, an additional nesting bird survey shall be completed prior to resuming such activities.

Potential take
or adverse
effects on
American
badger.

MM-BIO-21: Minimize Take and Adverse Effects on American Badgers. A qualified biologist shall conduct a survey for American badgers no more than 14 days prior to the initiation of ground‐disturbing activities. Surveys shall consist of walking parallel transects looking for badger burrows and signs. If no badger dens are found, no further mitigation is required.

If active badger dens are identified, a non-disturbance buffer of 200 feet shall be established around the den and associated occupied areas. If avoidance is not feasible, a biologist shall determine if the burrow is being used as an active maternity den through use of remote cameras. If young are determined to be present, the burrow shall be avoided until a qualified biologist has determined that the young have vacated the burrow. If the burrow is determined not to be an active maternity den and young are not present, a one‐way eviction door may be installed between September 1 and January 1 to passively relocate the badger after consultation with CDFW. If the badger digs back into the burrow, CDFW staff may allow the use of live traps to relocate badgers to suitable habitat outside of the Project area.

Within 14 days prior to
ground-disturbing
activities;
avoidance/monitoring
during construction as
required
Project
Proponent/Qualified
Biologist/Construction
Contractor
City of Fairfield/City of
Vacaville Director, or
designee; CDFW, as
applicable

Page 392 of 1497 ends

5-15

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
Potential
impacts to
wetlands and
other waters
of the United
States and
State.

MM-BIO-22: Wetland Mitigation and Resource Agency Permits. Prior to the start of work, the Project applicant(s) shall secure the necessary permits under Sections 404 and 401 of the federal Clean Water Act, the Porter-Cologne Water Quality Control Act, and Section 1602 of the California Fish and Game Code, and shall implement all permit conditions to ensure no net loss of functions and values of wetlands and other waters of the United States and State of California.

During the Project design, the Project applicant(s) shall evaluate alternatives that avoid fill in any vernal pools, seasonal wetlands, or Union Creek. Where fill of aquatic communities cannot be avoided, documentation shall be provided explaining why avoidance is not practicable. This analysis shall be consistent with the Environmental Protection Agency’s (EPA) Section 404(b)(1) guidelines, as required by the United States Army Corps of Engineers and as adopted by the State Water Resources Control Board.

Temporary impacts to wetland habitat shall be restored at a 1:1 ratio.

Permanent impacts shall require establishment of new wetlands at a minimum 2:1 ratio. Mitigation shall be provided through one or a combination of the following: (1) purchase of credits at an approved mitigation bank; (2) onsite habitat preservation; (3) offsite conservation lands; or (4) another approved mitigation strategy that achieves equivalent conservation outcomes. This mitigation can overlap with and be satisfied by wetland mitigation for special-status plants under Mitigation Measure BIO-4.

During Project design
and prior to the start
of work;
restoration/compensat
ion following impacts
as required by permits
Project
Proponent/Construction
Contractor
City of Fairfield/City of
Vacaville Director, or
designee;

USACE/RWQCB/CDFW,
as applicable

Page 393 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD - V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
5 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -16 Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
Potential
removal of
native woody
vegetation
and protected
trees.

MM-BIO-23: Tree Preservation. All native woody vegetation greater than 1 inch in diameter at breast height removed during project activities shall be replaced by planting native woody vegetation at the following minimum ratios and performance standards:

The number of native riparian plants that become established at the end of a minimum of the 5-year monitoring period shall equal a minimum of 80 percent of total required plantings. Established plants may include natural regeneration and volunteer plants.

The Project shall inventory all trees planned for removal to assess their status as protected trees. If protected trees are to be removed, the water treatment plant shall obtain applicable tree removal permits and mitigate tree removal consistent with Ordinance 25.36 that encourages the replacement of protected trees on an inch-for-inch basis determined by diameter at breast height (4-1/2 feet above the normal surface). Inches of replacement may be translated into standard nursery planting sizes using the following formulas:
 24-inch boxed tree = 3 replacement inches
 15-gallon tree = 1 replacement inch
 5-gallon tree = 1/2 replacement inch
Vegetation
Replacement Size
(inches)
Native Species (except
Oaks and Elderberry)
Oak
Species
Nonnative
Species
<12 3:1 5:1 1:1
12–24 6:1 7:1 2:1
>24 10:1 12:1 3:1
Prior to
vegetation/tree
removal; replacement
planting and minimum
5-year monitoring, as
applicable
Project
Proponent/Construction
Contractor/Qualified
Biologist or Arborist
City of Fairfield/City of
Vacaville Director, or
designee

4.5 Cultural Resources
Potential
disturbance of
archaeological
, historical, or
tribal cultural
resources
during
ground-MM-CUL-1: Worker Environmental Awareness Training. Prior to commencement of ground-disturbing activities, the Applicant shall retain a Secretary of the Interior-qualified archaeologist to provide Worker Environmental Awareness Program (WEAP) training to all construction personnel, including contractors and subcontractors. The training shall describe the types of archaeological, historical, and tribal cultural resources that may be encountered, applicable legal protections, procedures to be followed if cultural resources are discovered, and the Prior to
commencement of
ground-disturbing
activities; new
personnel trained
before beginning work
Project
Proponent/Secretary of
the Interior-qualified
Archaeologist/Construct
ion Contractor
City of Fairfield/City of
Vacaville Director, or
designee

Page 394 of 1497 ends

5-17

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
disturbing
activities.
prohibition against collecting artifacts. Additional training information shall be provided to all personnel who join the Project after the initial training.

Potential
impacts to
tribal cultural
resources in
culturally
sensitive
areas.

MM-CUL-2: Tribal Monitoring and Coordination. Prior to issuance of grading permits, the City shall continue consultation with culturally affiliated California Native American tribes, as appropriate, and execute a Tribal Monitoring Agreement, as requested by the consulting tribe. Tribal monitoring shall be conducted during ground-disturbing activities within culturally sensitive areas identified during Assembly Bill 52 consultation, including the vicinity of Union Creek, South Putah Creek, and the area near California State Prison, Solano, or other locations identified through consultation. The tribal monitor shall coordinate with the Project archaeologist throughout construction.

Prior to issuance of
grading permits and
during ground-disturbing activities in
identified culturally
sensitive areas
Project
Proponent/Tribal
Monitor/Construction
Contractor
City of Fairfield/City of
Vacaville Director, or
designee
Potential
impacts to
archaeological
resources in
archaeological
ly sensitive
areas.

MM-CUL-3: Archaeological Monitoring. A Secretary of the Interior-qualified archaeologist shall monitor ground-disturbing activities within archaeologically sensitive areas identified in Cultural Resources Report (Appendix C), including the vicinity of archaeological isolate WY-ISO-01 and site P-48-000199. Monitoring shall continue until the Project archaeologist determines that excavation has reached previously disturbed or culturally sterile soils or that the potential for encountering buried cultural resources has been substantially reduced. Monitoring frequency may be reduced, with concurrence of the Project archaeologist, based on observed field conditions. If archaeological resources are encountered, work shall cease in the vicinity of the discovery until the resource has been evaluated and appropriate treatment measures are implemented.

During ground-disturbing activities in
archaeologically
sensitive areas; until
monitoring is reduced
or concluded by the
Project archaeologist
Project
Proponent/Secretary of
the Interior-qualified
Archaeologist/Construct
ion Contractor
City of Fairfield/City of
Vacaville Director, or
designee
Potential
impacts from
unanticipated
discovery of
archaeological
or other
cultural
resources.

MM-CUL-4: Unanticipated Discovery of Cultural Resources. If archaeological materials or other cultural resources are encountered during construction, all ground-disturbing activities within at least 100 feet of the discovery, or another distance determined appropriate by the project archaeologist, shall cease immediately. The discovery shall be evaluated by a Secretary of the Interior-qualified archaeologist, in consultation with the tribal monitor, as appropriate, to determine whether the resource qualifies as a historical resource, unique archaeological resource, or tribal cultural resource pursuant to CEQA. If During construction, if
cultural resources are
encountered; prior to
resuming work in the
vicinity of the
discovery
Project
Proponent/Construction
Contractor/Secretary of
the Interior-qualified
Archaeologist
City of Fairfield/City of
Vacaville Director, or
designee; affiliated
tribes, as appropriate

Page 395 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD - V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
5 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -18 Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
the resource is determined to be significant, it shall be avoided where feasible. If avoidance is not feasible, appropriate treatment measures, including data recovery, documentation, curation, or other measures developed in consultation with the City and affiliated tribes, shall be implemented before construction resumes.

Potential
disturbance of
human
remains,
including
remains
outside formal
cemeteries.

MM-CUL-5: Discovery of Human Remains. If human remains are encountered during construction, all work within the vicinity of the discovery shall cease immediately. The Solano County Coroner shall be notified in accordance with California Health and Safety Code Section 7050.5. If the Coroner determines the remains are of Native American origin, the Coroner shall notify the Native American Heritage Commission, which shall designate a Most Likely Descendant pursuant to Public Resources Code Section 5097.98. The Applicant shall comply with the recommendations of the Most Likely Descendant, as appropriate, and all applicable State laws governing the treatment and disposition of human remains before construction resumes.

During construction, if
human remains are
encountered; prior to
resuming work in the
vicinity
Project
Proponent/Construction
Contractor
City of Fairfield/City of
Vacaville Director, or
designee; Solano
County Coroner/NAHC,
as applicable

4.7 Geology and Soils
Potential
exposure to
geologic and
soil hazards.

MM GEO-1: Design-Level Geotechnical Investigation. Prior to the start of construction, a licensed Geotechnical Engineer or their representative shall be retained to perform a design‐level geotechnical investigation once site development plans are final. The design‐level geotechnical investigation shall further evaluate the potential geologic hazards of the Project site, shall be used to address any identified geotechnical concerns, and shall develop detailed recommendations for Project design and construction. Any recommendations included in the design‐level geotechnical investigation for the Project shall be incorporated into all Project-related design and engineering plans. At the end of construction, the Geotechnical Engineer shall provide a letter confirming contractor compliance with Project plans and specifications and with the recommendations of the Geotechnical Investigation and any supplemental recommendations issued during construction. The letter shall be submitted to the City of Fairfield Building Division for review.

Prior to construction
and during final design;
compliance
confirmation at
completion of
construction
Project
Proponent/Licensed
Geotechnical
Engineer/Construction
Contractor
City of Fairfield Building
Division

Page 396 of 1497 ends

5-19

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD - V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
Potential
disturbance or
destruction of
significant
paleontologica
l resources.

MM-GEO-2: Paleontological Resources Impact Mitigation Program.

Should paleontological resources be encountered during Project subsurface construction activities, all ground-disturbing activities within 25 feet shall be redirected and a qualified paleontologist contacted to assess the situation, consult with agencies as appropriate, and make recommendations for the treatment of the discovery. For purposes of this mitigation, a “qualified paleontologist” shall be an individual with the following qualifications: (1) a graduate degree in paleontology or geology and/or a person with a demonstrated publication record in peer-reviewed paleontological journals; (2) at least 2 years of professional experience related to paleontology; (3) proficiency in recognizing fossils in the field and determining their significance; (4) expertise in local geology, stratigraphy, and biostratigraphy; and (5) experience collecting vertebrate fossils in the field.

If the paleontological resources are found to be significant and Project activities cannot avoid them, the construction contractor shall implement measures to ensure that the Project does not cause a substantial adverse change in the significance of the paleontological resource. Measures will be determined by the qualified paleontologist and may include monitoring, recording the fossil locality, data recovery and analysis, a final report, and accessioning the fossil material and technical report to a paleontological repository. Upon completion of the assessment, a report documenting methods, findings, and recommendations shall be prepared and submitted to the City of Fairfield for review. If paleontological materials are recovered, this report also shall be submitted to a paleontological repository such as the University of California Museum of Paleontology, along with significant paleontological materials.

During subsurface
construction, if
paleontological
resources are
encountered;
treatment completed
before work resumes
in the affected area
Project
Proponent/Construction
Contractor/Qualified
Paleontologist
City of Fairfield/City of
Vacaville Director, or
designee

4.9 Hazards and Hazardous Materials
Potential
aviation
safety
hazards
associated
with wildlife
attractants
MM-HAZ-1: Wildlife Hazard Analysis. Prior to issuance of grading or building permits, the City will submit the Project to the Solano County Airport Land Use Commission for consistency review with the Travis Air Force Base Airport Land Use Compatibility Plan, as applicable. If the Airport Land Use Commission, in coordination with Travis Air Force Base, determines that the Project constitutes a new or expanded land use with the potential to attract hazardous wildlife movement within the Outer Prior to issuance of
grading or building
permits;
recommendations
incorporated into final
design, construction,
and operation, as
Project Proponent
City of Fairfield/City of
Vacaville Director, or
designee; Solano
County Airport Land
Use Commission/Travis
Air Force Base, as
applicable

Page 397 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD - V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
5 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -20 Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation
within the
Travis Air
Force Base
Airport
Influence
Area.

Perimeter of the Airport Influence Area, the applicant will prepare a Wildlife Hazard Analysis in accordance with the Travis Air Force Base Airport Land Use Compatibility Plan and applicable Federal Aviation Administration guidance. Any recommendations or measures identified in the approved Wildlife Hazard Analysis will be incorporated into the final Project design, construction, and operation, as applicable, to minimize the potential for wildlife hazards to aircraft operations.
applicable

4.13 Noise
Potential
temporary
construction
noise impacts
at nearby
sensitive
receptors.

MM-NOI-1: Construction Noise. During construction, the Contractor shall be required to implement the following construction noise control measures when activities are within 100 feet of sensitive receptors:
 Construction activities occurring as part of the Project shall be subject to the limitations and requirements of the City of Fairfield Municipal Code, which states that construction activities are allowed between the hours of 7:00 a.m. to 10:00 p.m.
 Construction activities between 10:00 p.m. and 7:00 a.m. may occur only with written permission from the City of Fairfield Director of Public Works pursuant to Fairfield Municipal Code Section 25.1404.  Equip all internal combustion engine-driven equipment with intake and exhaust mufflers that are in good condition and appropriate for the equipment.
 Locate stationary noise-generating equipment as far as possible from sensitive receptors when sensitive receptors adjoin or are near a construction area.
 Use “quiet” air compressors and other stationary noise sources where technology exists.

Throughout
construction Construction Contractor
City of Fairfield/City of
Vacaville Director, or
designee

4.18 Tribal Cultural Resources
Potential
impacts to
tribal cultural
resources.

See 4.5: MM-CUL-1 through MM-CUL-5 See MM-CUL-1
through MM-CUL-5
See MM-CUL-1 through
MM-CUL-5
See MM-CUL-1 through
MM-CUL-5

Page 398 of 1497 ends

5-21

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD - V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) Mitigation Monitoring and Reporting Program
Impact Mitigation Measures Timeframe for
Implementation
Responsibility for
Implementation
Oversight of
Implementation

4.20 Wildfire
Potential
increased
wildfire risk
during
construction.

MM-WF-1: Defensible Space. Prior to and during construction, the Contractor shall implement measures to reduce wildfire risk within and adjacent to active work areas. Measures will include, as appropriate:
 Highly flammable vegetation near Project areas will be trimmed to reduce fire fuel, as appropriate
 Dispose of debris, such as dry debris, leaves, and dead limbs near and within the Project areas
 Design of defensible spaces with fire breaks around the Project site, as appropriate.

Prior to and
throughout
construction
Construction Contractor
City of Fairfield/City of
Vacaville Director, or
designee
Potential
ignition of
wildfire from
construction
equipment or
hot work.

MM-WF-2: Fire Suppression Equipment During Construction. Prior to the start of construction and throughout all construction activities, the Contractor shall maintain appropriate fire suppression equipment at active work areas whenever construction activities have the potential to generate sparks, flames, or other ignition sources, or when work is conducted during periods of elevated fire danger as determined by the applicable fire authority or Red Flag Warning conditions. Applicable activities may include, but are not limited to, welding, cutting, grinding, use of internal combustion equipment, and other hot work.

Fire suppression equipment shall be readily accessible at active work areas and, as appropriate, shall include water trucks, portable water backpacks, fire extinguishers with the appropriate fire rating, or other fire suppression equipment approved by the applicable fire authority.

Prior to the start of
construction and
throughout
construction activities
Construction Contractor
City of Fairfield/City of
Vacaville Director, or
designee; applicable
fire authority, as
appropriate
Source: LSA (2026).

Page 399 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
5 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -22 This page intentionally left blank

Page 400 of 1497 ends

6-1

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26)

6.0 LIST OF PREPARERS
LSA Associates, Inc.
1504 Eureka Road, Suite 310
Roseville, CA California 95661
Pam Reading, Principal in Charge
Dena Giacomini, Project Manager
Ashley Honer, Environmental Planner
Shannon Adan, Assistant Environmental Planner
Alyson Schmidt, Senior Biologist
Avery Hansen, Biologist
Jennifer Roth, Associate Biologist
Steve Foreman, Principal Biologist
Anthony Davolio, Field Archaeologist
Brie DeOrnellas, Archaeologist
Bruce Flores, Field Archaeologist
Jaimi Starr, Cultural Resources Assistant
JT Stephens, Noise and Vibration Principal
Benjamin Gold, Noise and Vibration Analyst
Corey Knips, Noise Specialist
Moe Abushanab, Mechanical Noise Engineer
Jessica Coria, Principal Air Quality and Climate Change Specialist Briette Shea, Senior Air Quality Specialist
Meredith Canterbury, Associate/Director of GIS
Eva Newby, GIS Specialist
Gregory Gallaugher, Associate GIS Specialist
Jason Thomas, Graphics Specialist

Page 401 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
6 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -2 This page intentionally left blank

Page 402 of 1497 ends

7-1

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26)

7.0 REFERENCES
AECOM. 2010. Draft Environmental Impact Report for the Fairfield Train Station Specific Plan.

Sacramento: AECOM. December.

Bay Area Air District. 2017. Final 2017 Clean Air Plan. April 19. Website: www.baaqmd.gov/~/media/ files/ planning-and-research/plans/2017-clean-air-plan/attachment-a_-proposed-final-cap-vol-1-pdf.pdf?la=en (accessed June 2026). _____. 2022 CEQA Guidelines. Website: https://www.baaqmd.gov/plans-and-climate/california-environmental-quality-act-ceqa/updated-ceqa-guidelines (accessed June 2026). _____. Air Quality Standards and Attainment Status. Website: https://www.baaqmd.gov/about-air-quality/research-and-data/air-quality-standards-and-attainment-status (accessed September 2026).

Bay Area Census. 2026. Fairfield. Website: https://census.bayareametro.gov/population?location= fairfield (accessed June 24, 2026).

California Air Resources Board (CARB). 2017. California’s 2017 Climate Change Scoping Plan.

November.
_____. 2022. 2022 Scoping Plan for Achieving Carbon Neutrality. November 16. Website:
https://ww2.arb.ca.gov/sites/default/files/2022-12/2022-sp_1.pdf (accessed June 2026).

California Department of Conservation (DOC). 2004. A Guide to the Farmland Mapping and Monitoring Program. 2004. p. 6.
_____. 2022. California Important Farmland Finder (map). Website: maps.conservation.ca.gov/ dlrp/ciff/ (accessed May 5, 2026).
_____. 2025. DOC Maps: Mines and Mineral Resources. Website: https://maps.conservation.ca.gov/ mineralresources/ (accessed May 7, 2025).

California Department of Conservation California Geological Survey (CGS). 2021. Earthquake Zones of Required Investigation. Website: https://maps.conservation.ca.gov/cgs/EQZApp/app/ (accessed July 2, 2024).

California Department of Finance. 2025. Economic and Revenue Updates. Website:
https://dof.ca.gov/forecasting/economics/economic-and-revenue-updates/ (accessed June 25, 2026).

California Department of Fish and Wildlife (CDFW). 2026. California Natural Diversity Database.

Commercial Version Dated January 6, 2026. Sacramento: California Department of Fish and Wildlife, Wildlife Habitat Data Analysis Branch.

Page 403 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
7 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -2 California Department of Forestry and Fire Protection (CAL FIRE). 2026a. Fire and Resource Assessment Program. Website: https://www.fire.ca.gov/what-we-do/fire-resource-assessment-program (accessed May 5, 2026). _____. 2026b. Fire Hazard Severity Zones. Website: https://osfm.fire.ca.gov/what-we-do/ community-wildfire-preparedness-and-mitigation/fire-hazard-severity-zones (accessed May 6, 2026).

California Department of Transportation (Caltrans). 2020. Transportation and Construction Vibration Guidance Manual.

California Department of Water Resources. 2020. Sustainable Groundwater Management Act 2019 Basin Prioritization Process and Results. May.
_____. 2026. California’s Groundwater Bulletin 118, Basin Boundaries Data Viewer. Website:
https://water.ca.gov/programs/groundwater-management/bulletin-118 (accessed May 6, 2026).

California Energy Commission (CEC). 2024. 2024 Integrated Energy Policy Report Update. Docket Number 24-IEPR-01.

California Native American Heritage Commission (NAHC). 2026. Sacred Lands File Search Results for the North Bay Regional Water Treatment Plant Expansion Project and Associated Pipeline Alignments. Sacramento, California.

California Office of Environmental Health Hazard Assessment. 2010. California Human Health Screening Levels. September 23.

California Office of Historic Preservation (OHP). 1999. California Register and National Register: A Comparison (for purposes of determining eligibility for the California Register), OHP Technical Assistance Series #6.

California Public Utilities Commission (CPUC). 2019. Renewables Portfolio Standard Program.

Website: cpuc.ca.gov/rps (accessed September 2025).

California State Mining and Geology Board. 2014. Surface Mining Reclamation Act Regulations.

California Code of Regulations, Title 14, Division 2, Chapter 8, Subchapter 1.

City of Fairfield. 2022. Emergency Operations Plan. Website: https://www.fairfield.ca.gov/home/ showpublisheddocument/9947/638356466726400000 (accessed May 6, 2026). _____. 2024a. General Plan Land Use Diagram Map.
_____. 2024b. General Plan and Zoning Map

Page 404 of 1497 ends

7-3

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) _____. 2024c. Draft Environmental Impact Report for the Fairfield General Plan 2050 and Climate Action Plan. Page 3.1-7. July 26. Website: https://www.fairfield.ca.gov/home/ showpublisheddocument/12145/638718493339670000 (accessed February 11, 2026). _____. 2024d. General Plan Documents. December. Website: https://www.fairfield.ca.gov/ government/city-departments/community-development/planning-division/general-plan/general-plan-documents (accessed June 2026). _____. 2024e. City of Fairfield General Plan, Open Space, Conservation, and Recreation Element. p. 6-29. Website: https://www.fairfield.ca.gov/home/showpublisheddocument/12145/ 638718493339670000 (accessed February 13, 2026).
_____. 2024f. City of Fairfield Climate Action Plan. December. Website:
https://www.fairfield.ca.gov/home/showpublisheddocument/12085/638701095833270000 (accessed June 2026).
_____. City of Fairfield. 2025. 2025 Urban Water Management Plan Draft. Website:
https://www.fairfield.ca.gov/home/showpublisheddocument/14567/639142813372170000 (accessed May 25, 2026).
_____. n.d. Operations. Website: https://www.fairfield.ca.gov/government/city-departments/fire/ operations (accessed May 7, 2026).

City of Vacaville. 2015. Vacaville General Plan. Website: https://www.cityofvacaville.gov/home/ showpublisheddocument/14102/637045896849400000 (accessed June 2026). _____. 2023. City of Vacaville Water Master Plan. February.

County of Solano. 2024a. Travis Air Force Base Land Use Compatibility Plan. August 8. Website:
https://www.solanocounty.gov/government/resource-management/commissions-special-districts/solano-county-airport-land-use-commission (accessed June 2, 2026). _____. 2024b. Figure 2 - 2015 Maximum Mission CNEL Contours, Travis Air Force Base Land Use Compatibility Plan. August 8. Website: https://www.solanocounty.gov/government/ resource-management/commissions-special-districts/solano-county-airport-land-use-commission (accessed June 2, 2026). _____. 2026. Agricultural Preserves/Williamson Act Contracts. Website:
https://www.solanocounty.gov/government/resource-management/planning-services/ development-programs/agricultural-preserveswilliamson-act-contracts (accessed May 5, 2026).

County of Solano Department of Resource Management. 2024. Land Use Compatibility Plan for Travis Air Force Base, Figure 1 Compatibility Zones. August 8.

Page 405 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
7 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) -4 County of Solano Department of Resource Management. 2024. Land Use Compatibility Plan for Travis Air Force Base, Figure 4 Wildlife Hazard Analysis Boundaries. August 8.

Federal Transit Administration. 2018. Transit Noise and Vibration Impact Assessment Manual, FTA Report No. 0123. September.

LSA Associates, Inc. (LSA). 2026a. Aquatic Resources Delineation Report, Fairfield Vacaville Water Works Project, Solano County, California. June.

LSA. 2026b. Biological Resources Report, Fairfield Vacaville Water Works Project, Solano County, California. June.

NOAA National Centers for Environmental Information (NCEI). n.d. Climate Data Online and Climate at a Glance. Website: https://www.ncei.noaa.gov/
National Park Service. n.d. The Native American Graves Protection and Repatriation Act (NAGPRA).

Website: https://www.nps.gov/archeology/tools/laws/nagpra.htm (accessed March 30, 2026).

Solano County Office of Emergency Services. 2022. Multi-Jurisdictional Hazard Mitigation Plan.

Website: https://www.solanocounty.gov/archival-document?document=https://content. solanocounty.gov/sites/default/files/2025-05/Solano-MJHMP-VOL-1-FEMA_Approval_and_ Adoptions_0.pdf&ad=aHR0cHM6Ly9jb250ZW50LnNvbGFub2NvdW50eS5nb3Yvc2l0ZXMvZG VmYXVsdC9maWxlcy8yMDI1LTA1L1NvbGFuby1NSkhNUC1WT0wtMS1GRU1BX0FwcHJvdmF sX2FuZF9BZG9wdGlvbnNfMC5wZGY=&title=Solano%20MJHMP:%20Volume%20I (accessed May 6, 2026).

Solano County GIS and Mapping Services. n.d. Topography, elevation, and drainage datasets. https://www.solanocounty.com (accessed February 2026).

State Water Resources Control Board (SWRCB). 2024. 2024 California Integrated Report (Clean Water Act Section 303(d)). Website: https://www.waterboards.ca.gov/water_issues/ programs/water_quality_assessment/2024-integrated-report.html (accessed April 27, 2026).

U.S. Climate Data. n.d. Climate Fairfield, California. Website: https://www.usclimatedata.com/ climate/fairfield/california/united-states/usca0364
United States Fish and Wildlife Service (USFWS). 2026. Information for Planning and Consultation (IPaC) Online Database. Sacramento: Sacramento Fish and Wildlife Office. Website:
https://ecos.fws.gov/ipac (accessed January 7, 2026).

Page 406 of 1497 ends

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26)

APPENDIX A

CALIFORNIA EMISSIONS ESTIMATOR MODEL (CALEEMOD) RESULTS

Page 407 of 1497 ends

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26) This page intentionally left blank

Page 408 of 1497 ends

CARLSBAD
CLOVIS

EMERYVILLE
IRVINE

LOS ANGELES

PALM SPRINGS

RIVERSIDE

ROSEVILLE

SAN LUIS OBISPO
1504 Eureka Rd, Suite 310, Roseville, California 95661 916.772.7450 www.lsa.net

MEMORANDUM
DATE: September 30, 2026
TO: City of Fairfield
FROM: Briette Shea, Senior Air Quality Specialist
SUBJECT: Air Quality and Greenhouse Gas Emissions Technical Memorandum for the Proposed Fairfield-Vacaville Water Works Project in Solano County, California

INTRODUCTION
The purpose of this Air Quality and Greenhouse Gas Emissions Technical Memorandum is to present the results of the emissions modeling that was prepared to support the grant application for the Clean Water State Revolving Fund Environmental Package and CEQA compliance for the Fairfield-Vacaville Water Works Project (proposed project). This analysis has been prepared using methods and assumptions recommended by the Bay Area Air District (Air District), and includes a description of existing regulatory framework, an assessment of construction and operation-period air quality and greenhouse gas (GHG) emissions, and an evaluation of the proposed project’s compliance with adopted plans related to clean air and the reduction of GHG emissions.

PROJECT LOCATION AND DESCRIPTION
The project site is located within the central portion of Solano County, approximately 6 miles northeast of downtown Fairfield and 1 mile south of the Vacaville city limits. The project extent covers the following Solano County parcels, 0166060200 and 0166020010 (NBRWTP), and 0166202180, 0166020170, and 01365130030 (Linear Trail Pipeline Alignment) and road right-of-way easements, 0136130010, 0128070060, 0128070070, and 0128070080 (Peabody Road Pipeline Alignment).

The proposed project would expand the capacity and operational efficiency of the existing North Bay Regional Water Treatment Plant (NBRWTP), a joint effort between the City of Fairfield and the City of Vacaville, and would include construction of an associated new pipeline. The proposed project would expand total plant capacity to 65 million gallons per day to support buildout of both general plans.

The improvements are designed to enhance water treatment reliability, accommodate projected

Page 409 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 2 population and service demand, and modernize aging infrastructure to ensure continued regulatory compliance.

Construction activities would occur within the existing treatment plant property and adjacent utility corridors, with measures implemented to minimize impacts to ongoing operations. The proposed project would introduce new treatment facilities, expand the capacity of existing processes, and relocate or modify certain features to improve site function, circulation, and access. Key elements include a new mechanical screen at the Putah South Canal intake structure, pre-ozone contactors, additional flash mixing facilities, additional flocculation/sedimentation basins, additional filters, one or more chlorine contact basins, wash water recovery and clarifier facilities, sludge management lagoons, and upgrades to chemical storage, ozone (O3) generation, ozone destruction, and treated water pumping systems. The proposed project also includes expansion of the administration building and electrical and control system upgrades to integrate new and existing processes and power systems with the plant’s Supervisory Control and Data Acquisition (SCADA) monitoring and operational controls, as well as installation and operation of an on-site microgrid system.

The proposed project also includes a pipeline from the NBRWTP to the City of Vacaville’s existing water distribution system. The pipeline will have an all-weather access road where it lies outside of a paved street.

Consistent with the Bay Area Air District’s Basic Best Management Practices, the project applicant has committed to implement the following controls during construction as a Project Design Feature (PDF). The following control measures will be included as specifications for the proposed project and implemented at the construction site:
• All exposed surfaces (e.g., parking areas, staging areas, soil piles, graded areas, and unpaved access roads) shall be watered two times per day.
• All haul trucks transporting soil, sand, or other loose material off site shall be covered. • All visible mud or dirt tracked onto adjacent public roads shall be removed using wet power vacuum street sweepers at least once per day. The use of dry power sweeping is prohibited. • All vehicle speeds on unpaved roads shall be limited to 15 miles per hour. • All roadways, driveways, and sidewalks to be paved shall be completed as soon as possible.

Building pads shall be laid as soon as possible after grading unless seeding or soil binders are used.
• All excavation, grading, and/or demolition activities shall be suspended when average wind speeds exceed 20 miles per hour.
• All trucks and equipment, including their tires, shall be washed off prior to leaving the site.

Page 410 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 3 • Unpaved roads providing access to sites 100 feet or farther from a paved road shall be treated with a 6- to 12-inch layer of compacted layer of wood chips, mulch, or gravel. • A publicly visible sign shall be posted with the telephone number and person to contact at the City of Fairfield regarding dust complaints. This person shall respond and take corrective action within 48 hours. The Air District’s phone number shall also be visible to ensure compliance with applicable regulations.

ENVIRONMENTAL SETTING
Air Quality Background
Air quality is primarily a function of local climate, local sources of air pollution, and regional pollution transport. The amount of a given pollutant in the atmosphere is determined by the amount of the pollutant released and the atmosphere’s ability to transport and dilute the pollutant. The major determinants of transport and dilution are wind, atmospheric stability, terrain, and, for photochemical pollutants, sunshine.

A region’s topographic features have a direct correlation with air pollution flow and, therefore, are used to determine the boundary of air basins. The project area is located within the San Francisco Bay Area Air Basin (Air Basin), a large, shallow air basin ringed by hills that taper into a number of sheltered valleys around the perimeter. Two primary atmospheric outlets exist. One is through the strait known as the Golden Gate, a direct outlet to the Pacific Ocean. The second extends to the northeast, along the West Delta region of the Sacramento and San Joaquin rivers.

The project site is within the jurisdiction of the Air District, which regulates air quality in the Bay Area.

Air quality conditions in the Bay Area have improved significantly since the Air District was created in 1955. Ambient concentrations of air pollutants and the number of days during which the region exceeds air quality standards have fallen dramatically. Neither State nor national ambient air quality standards (AAQS) of the following chemicals have been violated in recent decades: nitrogen dioxide (NO2), sulfur dioxide (SO2), sulfates, lead (Pb), hydrogen sulfide, and vinyl chloride. Those exceedances of air quality standards that do occur primarily happen during meteorological conditions conducive to high pollution levels (e.g., cold, windless nights or hot, sunny summer afternoons).

Both State and federal governments have established health-based AAQS for six criteria air pollutants: carbon monoxide (CO), O3, NO2, SO2, Pb, and suspended particulate matter. In addition, the State has set standards for sulfates, hydrogen sulfide, vinyl chloride, and visibility-reducing particles. These standards are designed to protect the health and welfare of the populace with a reasonable margin of safety. Two criteria pollutants, O3 and NO2, are considered regional pollutants because they (or their precursors) affect air quality on a regional scale. Pollutants such as CO, SO2, and Pb are considered localized pollutants because they are emitted directly from sources and tend to affect air quality primarily in the surrounding area rather than over a broad regional scale. The Air District is under State nonattainment status for O3 and PM10 standards. The Air District is classified as nonattainment for the federal O3 8-hour standard and nonattainment for the federal particulate matter less than 2.5 microns in size (PM2.5) 24-hour standard. As such, the primary pollutants of concern within the Bay Area are ozone precursors (ROG and NOx), PM2.5, and PM10.

Page 411 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 4 Because of the conservative nature of the significance thresholds and the basin-wide context of individual development project emissions, there is no direct correlation between a single project and localized air quality-related health effects. One individual project that generates emissions exceeding a threshold does not necessarily result in adverse health effects for residents in the project vicinity.

This condition is especially true when the criteria pollutants exceeding thresholds are those with regional effects, such as O3 precursors like nitrogen oxides (NOX) and reactive organic gases (ROG).

Further, by its very nature, air pollution is largely a cumulative impact. No single project is sufficient in size to, by itself, result in nonattainment of AAQS. Instead, a project’s individual emissions contribute to existing cumulatively significant adverse air quality impacts. If a project’s contribution to the cumulative impact is considerable, then its impact on air quality would be considered significant. In developing thresholds of significance for air pollutants, the air districts have considered the emission levels for which a project’s individual emissions would be cumulatively considerable. If a project exceeds the identified significance thresholds, its emissions would be cumulatively considerable, resulting in significant adverse air quality impacts to the region’s existing air quality conditions.

Greenhouse Gas Background
GHGs are present in the atmosphere naturally, are released by natural sources, or are formed from secondary reactions taking place in the atmosphere. The gases that are widely seen as the principal contributors to human-induced global climate change are:
• Carbon dioxide (CO2);
• Methane (CH4);
• Nitrous oxide (N2O);
• Hydrofluorocarbons (HFCs);
• Perfluorocarbons (PFCs); and
• Sulfur hexafluoride (SF6).

Over the last 200 years, humans have caused substantial quantities of GHGs to be released into the atmosphere. These extra emissions are increasing GHG concentrations in the atmosphere and enhancing the natural greenhouse effect, which is believed to be causing global warming. Although manmade GHGs include naturally occurring GHGs (e.g., CO2, CH4, and N2O), some gases (e.g., HFCs, PFCs, and SF6) are completely new to the atmosphere.

Certain gases, such as water vapor, are short-lived in the atmosphere. Others remain in the atmosphere for significant periods of time, contributing to climate change in the long term. Water vapor is excluded from the list of GHGs above because it is short-lived in the atmosphere and its atmospheric concentrations are largely determined by natural processes, such as oceanic evaporation.

These gases vary considerably in terms of global warming potential (GWP), which is a concept developed to compare the ability of each GHG to trap heat in the atmosphere relative to another gas. The GWP is based on several factors, including the relative effectiveness of a gas to absorb

Page 412 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 5 infrared radiation and the length of time the gas remains in the atmosphere (i.e., atmospheric lifetime). The GWP of each gas is measured relative to CO2, the most abundant GHG; the definition of GWP for a particular GHG is the ratio of heat trapped by one unit mass of the GHG to the ratio of heat trapped by one unit mass of CO2 over a specified time period. GHG emissions are typically measured in terms of pounds or tons of CO2 equivalents (CO2e).

REGULATORY SETTING
This section provides a summary of relevant regulatory background information for air quality and GHGs.

Air Quality
This section provides regulatory background information for air quality at the federal, State, regional, and local level.

Federal Regulations
The 1970 Federal Clean Air Act (CAA) authorized the establishment of national health-based air quality standards and set deadlines for their attainment. The CAA Amendments of 1990 changed deadlines for attaining national standards as well as the remedial actions required for areas of the nation that exceed the standards. Under the CAA, State and local agencies in areas that exceed the national standards are required to develop State Implementation Plans to demonstrate how they will achieve the national standards by specified dates.

State Regulations
In 1988, the California Clean Air Act (CCAA) required that all air districts in the State endeavor to achieve and maintain California Ambient Air Quality Standards (CAAQS) for CO, O3, SO2, and NO2 by the earliest practical date. The CCAA provides districts with authority to regulate indirect sources and mandates that air quality districts focus particular attention on reducing emissions from transportation and area-wide emission sources. Each nonattainment district is required to adopt a plan to achieve a 5 percent annual reduction, averaged over consecutive 3-year periods, in district-wide emissions of each nonattainment pollutant or its precursors. A Clean Air Plan shows how a district would reduce emissions to achieve air quality standards. Generally, the State standards for these pollutants are more stringent than the national standards.

The California Air Resources Board (CARB) is the State’s “clean air agency.” CARB’s goals are to attain and maintain healthy air quality, protect the public from exposure to toxic air contaminants (TACs), and oversee compliance with air pollution rules and regulations.

Regional Regulations
Bay Area Air District. The Air District seeks to attain and maintain air quality conditions in the Air Basin through a comprehensive program of planning, regulation, enforcement, technical innovation, and education. The clean air strategy includes the preparation of plans for the attainment of AAQS, adoption and enforcement of rules and regulations, and issuance of permits for stationary sources.

The Air District also inspects stationary sources and responds to citizen complaints, monitors

Page 413 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 6 ambient air quality and meteorological conditions, and implements programs and regulations required by law.

The Air District 2017 Clean Air Plan (Clean Air Plan), which was adopted on April 19, 2017, by the Air District Board of Directors, is the current Clean Air Plan and contains district-wide control measures to reduce O3 precursor emissions (e.g., ROG and NOx), particulate matter, and GHG emissions. The Clean Air Plan guides the region’s air quality planning efforts to attain the CAAQS. 1 The Air District 2017 Clean Air Plan:
• Describes the Air District’s plan toward attaining all State and federal air quality standards and eliminating health risk disparities from exposure to air pollution among Bay Area communities; • Defines a vision for transitioning the region to a post-carbon economy needed to achieve ambitious GHG reduction targets for 2030 and 2050;
• Provides a regional climate protection strategy that will put the Bay Area on a pathway to achieving GHG reduction targets; and
• Includes a wide range of control measures designed to decrease emissions of air pollutants that are most harmful to Bay Area residents (e.g., particulate matter, O3, and TACs), to reduce emissions of CH4 and other “Super-GHGs” that are potent climate pollutants in the near term, and to decrease emissions of CO2 by reducing fossil fuel combustion.

The Air District’s California Environmental Quality Act (CEQA) Air Quality Guidelines (CEQA Guidelines) were prepared to assist in the evaluation of air quality impacts of projects and plans proposed within the Bay Area. The guidelines provide recommended procedures for evaluating potential air impacts during the environmental review process, consistent with CEQA requirements, and include recommended thresholds of significance, mitigation measures, and background air quality information. They also include recommended assessment methodologies for air toxics, odors, and GHG emissions.

In 2023, the Air District published an updated version of the CEQA Guidelines. The Air District’s CEQA Guidelines include thresholds to evaluate project impacts to protectively evaluate the potential effects of the project on air quality. These protective thresholds are appropriate in the context of the size, scale, and location of the proposed project.
1 Bay Area Air District. 2017. Final 2017 Clean Air Plan. April 19. Website: www.baaqmd.gov/~/media/files/ planning-and-research/plans/2017-clean-air-plan/attachment-a_-proposed-final-cap-vol-1-pdf.pdf?la=en (accessed June 2026).

Page 414 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 7 Local Regulations
City of Fairfield General Plan. The Environmental Justice and Public Health Element of the City of Fairfield’s General Plan 2 includes goals and policies related to air quality and pollution. The following policies may be applicable to the proposed project:
• Goal EJPH-1. Reduce air, land, and water pollution, mitigate the impacts of pollution on existing sensitive land uses, and alleviate associated health disparities. • Policy EJPH-1.1. Sensitive Receptors. Protect sensitive receptors such as schools, childcare centers, senior living facilities, and residences from the impacts of stationary and non-stationary sources of pollution by ensuring adequate buffers or mitigation measures. Establish vegetative barriers or green wall barriers between industrial land and sensitive land uses, and along heavy-duty truck/goods movement corridors and freeways to protect sensitive land uses from pollution impacts.
• Policy EJPH-1.2. Impact Assessment and Mitigation. Continue to use the Bay Area Air Quality and Monitoring District modeling tools and guidance documents, as appropriate, to identify and mitigate air quality impacts from proposed development projects, including projects within 500 feet of a major freeway.

City of Vacaville General Plan. The Conservation and Open Space Element of the City of Vacaville General Plan includes goals and policies that relate to air quality. The following policies may be applicable to the proposed project: 3
• Goal COS-12. Maintain and improve air quality.
• Policy COS-P12.3. Encourage project designs that protect and improve air quality and minimize direct and indirect air pollutant emissions by including components that reduce vehicle trips and promote energy efficiency.
• Policy COS-P12.4. Require that development projects implement best management practices to reduce air pollutant emissions associated with the construction and operation of the project.
• Policy COS-P12.5. Require dust control measures as a condition of approval for subdivision maps, site plans, and all grading permits.
2 City of Fairfield. 2024. General Plan Documents. December. Website: https://www.fairfield.ca.gov/ government/city-departments/community-development/planning-division/general-plan/general-plan-documents (accessed June 2026). 3 City of Vacaville. 2015. Vacaville General Plan. Website:
https://www.cityofvacaville.gov/home/showpublisheddocument/14102/637045896849400000 (accessed June 2026).

Page 415 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 8 Greenhouse Gas Emissions
This section describes regulations related to global climate change at the federal, State, regional, and local levels.

Federal Regulations
The United States has historically had a voluntary approach to reducing GHG emissions. However, on April 2, 2007, the United States Supreme Court ruled that the United States Environmental Protection Agency (USEPA) has the authority to regulate CO2 emissions under the CAA. The USEPA commenced several actions in 2009 to implement a regulatory approach to global climate change, including the 2009 USEPA final rule for mandatory reporting of GHGs from large GHG emission sources in the United States. Additionally, the USEPA Administrator signed an endangerment finding action in 2009 under the CAA, finding that seven GHGs (CO2, CH4, N2O, HFCs, NF3, PFCs, and SF6) constitute a threat to public health and welfare, and that the combined emissions from motor vehicles cause and contribute to global climate change, leading to national GHG emission standards.

The 2009 endangerment finding was repealed in early 2026.

The Inflation Reduction Act (IRA) of 2022 reaffirmed the USEPA’s authority to regulate GHG emissions under the CAA. In January 2025, Executive Order (EO) 14153, Unleashing American Energy, agencies were directed to stop issuing funds under the IRA.

State Regulations
CARB is the lead agency for implementing climate change regulations in the State. Since its formation, CARB has worked with the public, the business sector, and local governments to find solutions to California’s air pollution problems. Key efforts by the State are described below.

Assembly Bill 32, California Global Warming Solutions Act (2006). Assembly Bill (AB) 32 established California’s comprehensive framework for reducing statewide GHG emissions, directing the CARB to develop the Scoping Plan, which identifies statewide strategies and measures to reduce GHG emissions from major source sectors, including transportation, energy production, and land use development. The legislation initially established a statewide target of reducing GHG emissions to 1990 levels by 2020 and laid the foundation for California’s long-term climate policies and emissions reduction programs.

CARB’s 2022 Scoping Plan 4 outlines the State’s current strategy for achieving California’s long-term climate change goals, including reducing GHG emissions 40 percent below 1990 levels by 2030 and achieving carbon neutrality by 2045. The Scoping Plan identifies measures intended to reduce emissions through increased renewable energy generation, transportation, electrification, energy efficiency improvements, and transition to zero-emission vehicle fleets. The Scoping Plan also serves 4 California Air Resources Board (CARB). 2022. 2022 Scoping Plan Documents. Final 2022 Scoping Plan.

December. Website: https://ww2.arb.ca.gov/our-work/programs/ab-32-climate-change-scoping-plan/ 2022-scoping-plan-documents (accessed June 2026).

Page 416 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 9 as the primary statewide framework guiding future emissions reduction efforts and forecasting assumptions.

Senate Bill 32, California Global Warming Solutions Act of 2016, and Assembly Bill 197 (2016).

Senate Bill (SB) 32 codified California’s target of reducing statewide GHG emissions to 40 percent below 1990 levels by 2030. AB 197 established additional legislative direction for CARB related to implementation of statewide GHG reduction strategies.

Assembly Bill 1279 (2022). AB 1279 was signed in September 2022 and codifies the State goals of achieving net carbon neutrality by 2045 and maintaining net negative GHG emissions thereafter. This bill also requires California to reduce statewide GHG emissions by 85 percent compared to 1990 levels by 2045 and directs CARB to work with relevant State agencies to achieve these goals.

Regional Regulations
The Air District is the regional government agency that regulates sources of air pollution within the nine Bay Area counties.

CEQA Guidelines. The Air District’s CEQA Guidelines 5 identify applicable GHG significance thresholds. The Air District recommends these thresholds of significance for use in determining whether a proposed project will have a significant impact related to climate change. These thresholds evaluate a project based on its effect on California’s efforts to meet the State’s long-term climate goals. Applying this approach, the Air District identifies and provides supporting documentation outlining the requirements that new land use development projects must comply with to achieve California’s long-term climate goal of carbon neutrality by 2045. Based on this research, the Air District has determined that new land use development projects need to incorporate design elements to contribute the “fair share” toward implementation of the goal of carbon neutrality by 2045. If a project is designed and built to incorporate the identified design elements, it will contribute its portion of what is necessary to achieve California’s long-term climate goals—its “fair share”—and an agency reviewing the project under CEQA can conclude that the project will not make a cumulatively considerable contribution to global climate change.

Local Regulations
City of Fairfield General Plan. The Sustainability Element of the City of Fairfield’s General Plan 6 includes goals and policies related to GHG emissions and climate change vulnerability. The following policies may be applicable to the proposed project:
5 Bay Area Air District. 2022 CEQA Guidelines. Website: https://www.baaqmd.gov/ plans-and-climate/ california-environmental-quality-act-ceqa/updated-ceqa-guidelines (accessed June 2026). 6 City of Fairfield. 2024. General Plan Documents. December. Website: https://www.fairfield.ca.gov/ government/city-departments/community-development/planning-division/general-plan/general-plan-documents (accessed June 2026).

Page 417 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 10 • Goal SUS-1. Strive to reduce greenhouse gas emissions to 40 percent below 1990 levels by 2030, and reach carbon neutrality by 2045, consistent with State law. • Policy SUS-1.1. Climate Action Plan (CAP). Use the CAP (concurrently adopted with the General Plan) as the primary tool for achieving the City’s GHG reduction targets. Monitor and periodically report on CAP implementation progress and update the CAP as necessary to make progress toward the City’s greenhouse gas reduction goals.
• Goal SUS-5. Coordinate with partners and the public to reduce energy consumption and promote energy conservation
• Policy SUS-5.1. Electricity Provider Conservation Efforts. Support efforts that increase energy conservation in all households and businesses.

City of Fairfield Climate Action Plan. In December 2024, the City of Fairfield adopted a Climate Action Plan (CAP) that is qualified under CEQA Section 15183.5(b). 7 The CAP identifies several GHG reduction measures that, when implemented, would help the City achieve their GHG reduction targets. The GHG reduction measures are divided into the following sectors: transportation, built environment, solid waste, wastewater, potable water, and carbon sequestration. The following measures may be applicable to the proposed project:
• Measure BE-3: Reduce energy demand and consumption through energy efficiency and conservation.
• Measure SW-1: Reduce the amount of solid waste that is generated and sent to landfills, especially organic waste.
○ Supporting Action SW-1E: Construction and Demolition Waste • Measure PW-1: Reduce water utility emissions by 60% below 2020 levels by 2030 and 100% by 2050.
○ Supporting Action PW-1A: Landscape Efficiency
○ Supporting Action PW-1B: Water Conservation Ordinance ○ Supporting Action PW-1C: Recycled Water Program
○ Supporting Action PW-1D: Education and Incentives
City of Fairfield Municipal Code. Chapter 5, City of Fairfield Building and Housing Code, of the City’s Municipal Code adopts the 2025 California Building Standards Code, including Title 24 and the California Green Building Standards Code (CALGreen Code). 7 City of Fairfield. 2024. City of Fairfield Climate Action Plan. December. Website: https://www.fairfield.ca. gov/home/showpublisheddocument/12085/638701095833270000 (accessed June 2026).

Page 418 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 11 City of Vacaville General Plan. The Conservation and Open Space Element of the City of Vacaville General Plan includes goals and policies that relate to GHG emissions. In addition, the Safety Element of the City of Vacaville General Plan includes goals and policies that relate to climate change. The following policies may be applicable to the proposed project: 8 • Goal COS-9. Reduce greenhouse gas emissions and improve the sustainability of actions by City government, residents, and businesses in Vacaville.
• Policy COS-P9.8. Promote green building practices in new development.

City of Vacaville Energy and Conservation Action Strategy. In 2015, the City of Vacaville adopted the Energy and Conservation Action Strategy (ECAS), which meets the requirements of a qualified CAP under CEQA Section 15183.5(b). The ECAS establishes a strategy to reduce GHG emissions and achieve greater conservation of resources with regards to transportation and land use, energy, water, solid waste, and open space. The ECAS includes communitywide measures, which aim to reduce GHG emissions from activities that take place within the City, and municipal measures, which apply exclusively to City government operations. 9 There are not measures in the ECAS that are applicable to the portion of the proposed project that takes place within City of Vacaville limits, which is limited to an underground pipeline connection.

MODELING APPROACH AND ASSUMPTIONS
The California Emissions Estimator Model (CalEEMod), Version 2022.1, computer program was used to calculate air quality and GHG emissions from on-site construction equipment and emissions from worker and vehicle trips to the site. CalEEMod is a statewide land use emissions web model designed to provide a uniform platform for government agencies, land use planners, and environmental professionals to quantify potential criteria pollutants associated with both construction and operation of a variety of land use projects. The model quantifies direct emissions from construction and operations (including vehicle use), as well as indirect emissions, such as GHG emissions from energy use, solid waste disposal, vegetation planting and/or removal, and water use for land use developments and linear projects. Default data (e.g., emission factors, trip lengths, meteorology, source inventory) have been provided by the various California air districts to account for local requirements and conditions.

Construction of the proposed project is anticipated to begin in early 2027 and occur for approximately 5 years. For purposes of this analysis, it is assumed that construction of the NBRWTP on-site improvements would occur from January 2027 through September 2032, and construction of 8 City of Vacaville. 2015. Vacaville General Plan. Website:
https://www.cityofvacaville.gov/home/showpublisheddocument/14102/637045896849400000 (accessed June 2026). 9 City of Vacaville. 2015. City of Vacaville Energy and Conservation Action Strategy. Website:
https://www.cityofvacaville.gov/home/showpublisheddocument/5454/636234161698230000(accessed June 2026).

Page 419 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 12 the pipeline would occur from January 2027 through July 2032. The modeled off-road equipment list was developed using model defaults and project-specific information. The comprehensive list is included in the CalEEMod output sheets (see Appendix A). The modeling accounted for 22,763 cubic yards of material export in order to accommodate the three proposed ozone basins, three proposed flocculation/sedimentation basins, an equalization basin, and two sludge lagoons. In addition to material export, new lagoons and basins were accounted for by including the entire disturbance area in the inputted land uses. Other detailed construction information is currently unavailable (eg., number of construction workers, worker commute trips, construction equipment horsepower, etc.; therefore, this analysis uses CalEEMod default assumptions for those values. CalEEMod output sheets are included in Appendix A.

The operational analysis quantifies the emissions associated with new changes proposed under the project. The proposed project analysis was conducted using land use codes Industrial – Unrefrigerated Warehouse No Rail to represent the battery energy storage system (BESS) facility units, General Office Building to represent expansion of the operational building on the NBRWTP site, and Linear – Road Widening to represent the proposed pipeline alignment.

One of the two pipeline alignments will be selected for development (either the Linear Trail pipeline alignment or the Peabody Road pipeline alignment). This analysis considers the longer pipeline alignment as the more conservative scenario. If the shorter pipeline alignment is ultimately selected, emissions will be less than what is presented herein. The building square footage for the expanded administration building was modeled as 13,700 square feet. The disturbance area for the new pipeline was estimated using the 9,500-linear-foot length and assumed a 6-foot width for trenching.

The additional pumps required to support increased flows were modeled as 3 50-horsepower electric-powered pumps that were assumed to operate 24 hours per day, 365 days per year. Vehicle trip generation rates applied in CalEEMod were based on the assumption that full buildout of the proposed project would generate up to 34 new one-way daily vehicle trips to accommodate expanded staffing requirements, and up to 550 chemical delivery trips per year.

The project includes installation and operation of an on-site microgrid system which would consist of a microgrid controller, a BESS, one or more new diesel-fueled emergency generators, communication and coordination with the onsite photovoltaic array and associated electrical distribution and control equipment. Stationary-source emissions were modeled assuming two 1,800-horsepower diesel-fueled emergency generators associated with the proposed microgrid, operating up to 1 hour per day and 50 hours per year for routine testing and maintenance. In the absence of project-specific generator specifications, the generator size was based on a comparable City of Fairfield water treatment facility.

Where project-specific data were not available, default assumptions (e.g., trip length, energy usage, water usage) from CalEEMod were used to estimate proposed project emissions. CalEEMod output sheets are included in Appendix A.

Page 420 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 13

THRESHOLDS OF SIGNIFICANCE
General Conformity Analysis
To support the grant application for the Clean Water State Revolving Fund Environmental Package, a federal General Conformity Analysis was prepared. General Conformity is the federal air pollution prevention program that requires any federal activity or activities using federal funds to demonstrate conformance to the purpose of applicable implementation plans and to not interfere with a state or tribe's ability to attain and maintain the National Ambient Air Quality Standards (NAAQS) for air quality, as required under CAA Section 176(c). The General Conformity rule includes de minimis threshold rates, which are the minimum rates, in tons per year, below which no conformity determination is required. Table A lists the applicable de minimis thresholds based on the attainment status for the project area. The project area is designated as nonattainment for the ozone and PM2.5 NAAQS. 10
Table A: De Minimis Thresholds
Pollutant Emissions Threshold (tons per year)
ROG NOX CO SOx PM10 PM2.5
100 100 100 100 100 100
Source: USEPA. 2025. De Minimis Tables. Website: https://www.epa.gov/general-conformity/de-minimis-tables (accessed June 2026).

CO = carbon monoxide
NOX = nitrogen oxides
PM2.5 = particulate matter less than 2.5 microns in size PM10 = particulate matter less than 10 microns in size
ROG = reactive organic gases
SOX = sulfur oxides
USEPA = United States Environmental Protection Agency
CEQA Analysis
Air Quality
The State CEQA Guidelines indicate that a project would normally have a significant adverse air quality impact if project-generated pollutant emissions would:
• Conflict with or obstruct implementation of the applicable air quality plan; • Result in a cumulatively considerable net increase of any criteria pollutant for which the project is in nonattainment under an applicable federal or State AAQS; • Expose sensitive receptors to substantial pollutant concentrations; or • Result in other emissions (such as those leading to odors) adversely affecting a substantial number of people.
10 Bay Area Air District. 2026. Air Quality Standards and Attainment Status. Website: https://www.baaqmd. gov/about-air-quality/research-and-data/air-quality-standards-and-attainment-status (accessed June 2026).

Page 421 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 14 The NBRWTP and a majority of the proposed project site is within the Bay Area Air District (Air District). In addition, the CEQA lead agency, the City of Fairfield, is within the Air District. It is noted that the northernmost portion of the proposed pipeline alignment extends into the jurisdiction of the Yolo-Solano Air Quality Management District. However, the majority of emissions that would be emitted as a result of the project would occur within the Air District boundaries. In addition, Yolo-Solano Air Quality Management District thresholds are generally similar to the Air District thresholds. 11 As a result, project emissions are compared to the Air District thresholds of significance.

According to the Air District’s California Environmental Quality Act (CEQA) Guidelines, to meet air quality standards for criteria air pollutant and air precursor impacts, a proposed project must not:
• Contribute to carbon monoxide (CO) concentrations exceeding the State ambient air quality standards;
• Generate average daily construction emissions of reactive organic gases (ROG), nitrogen oxides (NOX), or PM2.5 (exhaust) greater than 54 pounds per day or particulate matter less than 10 microns in size (PM10) exhaust emissions greater than 82 pounds per day; • Generate operational emissions of ROG, NOX or PM2.5 of greater than 10 tons per year or 54 pounds per day, or PM10 emissions greater than 15 tons per year or 82 pounds per day; or • Result in an increased cancer risk greater than 10.0 in one million; increased non-cancer hazard risk index (chronic or acute) greater than 1.0; or increased PM2.5 concentrations greater than 0.3 µg/m3 annual average.

Greenhouse Gas Emissions
The State CEQA Guidelines indicate that a project would normally have a significant adverse GHG emission impact if the project would:
• Generate GHG emissions, either directly or indirectly, that may have a significant impact on the environment; or
• Conflict with an applicable plan, policy, or regulation adopted for the purpose of reducing the emissions of GHGs.

According to the Air District, a project would have a less than significant impact related to GHG emissions if it would:

A. Include, at a minimum, the following project design elements:
11 For PM10, the Yolo-Solano Air Quality Management District has adopted a more stringent threshold of significance of 80 lbs/day compared to the Air District threshold of 82 lbs/day. All other thresholds are similar or less stringent.

Page 422 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 15

1. Buildings
a. The project will not include natural gas appliances or natural gas plumbing (in both residential and nonresidential development).
b. The project will not result in any wasteful, inefficient, or unnecessary electrical usage as determined by the analysis required under CEQA Section 21100(b)(3) and Section 15126.2(b) of the State CEQA Guidelines.

2. Transportation
a. Achieve a reduction in project-generated vehicle miles traveled (VMT) below the regional average consistent with the current version of the California Climate Change Scoping Plan (currently 15 percent) or meet a locally adopted Senate Bill 743 VMT target, reflecting the recommendations provided in the Governor’s Office of Planning and Research's Technical Advisory on Evaluating Transportation Impacts in CEQA:

1. Residential projects: 15 percent below the existing VMT per capita

2. Office projects: 15 percent below the existing VMT per employee

3. Retail projects: no net increase in existing VMT
b. Achieve compliance with off-street electric vehicle requirements in the most recently adopted version of CALGreen Tier 2.

B. Or be consistent with a local GHG reduction strategy that meets the criteria under State CEQA Guidelines Section 15183.5(b).

In December 2024, the City of Fairfield adopted a Climate Action Plan (CAP) that is qualified under CEQA Section 15183.5(b). 12 The City of Fairfield’s CAP meets the requirements for a Qualified Greenhouse Gas Reduction Strategy and is designed to streamline environmental review of future development projects in Fairfield. Therefore, consistent with threshold item B, the level of significance is determined by evaluating the proposed project for consistency with the City of Fairfield’s CAP. A consistency analysis with the CARB’s 2022 Scoping Plan is also provided.

Although a small portion of the project site is within the City of Vacaville, the City of Fairfield is the lead agency and the project site is primarily within Fairfield. The City of Vacaville Energy and Conservation Action Strategy (ECAS) was reviewed, and no policies or measures were identified that are applicable to the proposed pipeline facilities. Therefore, a detailed consistency evaluation with the ECAS was not warranted.
12 City of Fairfield. 2024. City of Fairfield Climate Action Plan. December. Website:
https://www.fairfield.ca.gov/home/showpublisheddocument/12085/638701095833270000 (accessed June 2026).

Page 423 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 16 In addition, the Air District guidance states that a project with stationary sources of emissions must fall below the bright-line threshold of 10,000 MTCO2e per year to have a less-than-significant impact related to stationary source GHG emissions. 13 Therefore, total quantified operational emissions are compared to the 10,000 MTCO2e per year threshold.

IMPACT ANALYSIS
This section identifies the air quality and GHG emissions impacts associated with implementation of the proposed project.

General Conformity Analysis
As noted previously, General Conformity is the federal air pollution prevention program that requires any federal activity or activities using federal funds to demonstrate project conformance with applicable air quality implementation plans, as required under the CAA. This analysis is presented to support the grant application for the Clean Water State Revolving Fund Environmental Package.

Construction-related emissions, in tons per year, as compared to the applicable de minimis levels are presented in Table B. As shown in the table, construction of the proposed project would not exceed the applicable de minimis thresholds. As a result, a formal conformity analysis is not required for construction.

Table B: Project Construction Emissions – General Conformity Analysis Construction Year Criteria Pollutant Emissions (tons per year) ROG NOX CO SOX PM10 PM2.5
2027 0.6 4.9 5.7 0.0 0.6 0.4
2028 0.6 4.8 6.9 0.0 0.2 0.2
2029 0.6 4.5 6.9 0.0 0.2 0.2
2030 0.4 3.6 5.4 0.0 0.2 0.1
2031 0.4 3.0 4.7 0.0 0.1 0.1
2032 0.1 0.8 1.5 0.0 0.0 0.0
De Minimis Level 100 100 100 100 100 100
Exceeds Threshold? No No No No No No
Source: Compiled by LSA (September 2026).

CO = carbon monoxide
NOX = nitrogen oxides
PM2.5 = particulate matter less than 2.5 microns in size PM10 = particulate matter less than 10 microns in size
SOX = sulfur oxides
ROG = reactive organic gases
New operational emissions, in tons per year, as compared to the applicable de minimis levels are presented in Table C. As shown in the table, operations of the proposed project would not exceed the applicable de minimis thresholds. As a result, a formal conformity analysis is not required for operations.
13 Bay Area Air District. 2022 CEQA Guidelines. Website: https://www.baaqmd.gov/ plans-and-climate/ california-environmental-quality-act-ceqa/updated-ceqa-guidelines (accessed September 2026).

Page 424 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 17 Table C: Project Operational Emissions – General Conformity Analysis Emissions Source Criteria Pollutant Emissions (tons per year) ROG NOX CO SOx PM10 PM2.5
Mobile Source <0.1 <0.1 0.1 0.0 <0.1 <0.1
Area Source 0.1 <0.1 <0.1 0.0 0.0 0.0
Energy Source <0.1 <0.1 <0.1 0.0 <0.1 <0.1
Off-Road 0.0 0.0 0.0 0.0 0.0 0.0
Stationary Source 0.1 0.7 0.4 < 0.1 <0.1 <0.1
Total Project Emissions 0.2 0.7 0.5 < 0.1 0.1 <0.1
De Minimis Level 100 100 100 100 100 100
Exceeds Threshold? No No No No No No
Source: Compiled by LSA (September 2026).

CO = carbon monoxide
NOX = nitrogen oxides
PM2.5 = particulate matter less than 2.5 microns in size PM10 = particulate matter less than 10 microns in size
SOX = sulfur oxides
ROG = reactive organic gases
CEQA Air Quality Analysis
Air pollutant emissions associated with the proposed project would occur over the short term from construction activities and over the long term from operational activities associated with the proposed land uses.

Consistency with Applicable Air Quality Plans
The applicable air quality plan is the Air District’s 2017 Clean Air Plan, which defines control strategies to reduce emissions and ambient concentrations of air pollutants; safeguard public health by reducing exposure to air pollutants that pose the greatest health risk, with an emphasis on protecting the communities most heavily affected by air pollution; and reduce GHG emissions to protect the climate. Consistency with the Clean Air Plan can be determined if the proposed project:
(1) supports the goals of the Clean Air Plan; (2) includes applicable control measures from the Clean Air Plan; and (3) would not disrupt or hinder implementation of any control measures from the Clean Air Plan.

Clean Air Plan Goals. The primary goals of the Clean Air Plan are to attain air quality standards, reduce population exposure and protect public health in the Bay Area, and reduce GHG emissions and protect the climate.

The Air District has established significance thresholds for project construction and operational impacts at a level at which the cumulative impact of exceeding these thresholds would have an adverse impact on the region’s attainment of air quality standards. The health and hazards thresholds were established to help protect public health. As discussed below, construction and operation of the proposed project would not result in the generation of criteria air pollutants that would exceed the Air District’s thresholds of significance. Therefore, the proposed project would not conflict with the Clean Air Plan goals.

Page 425 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 18 Clean Air Plan Control Measures. The control strategies of the Clean Air Plan include measures in the following categories: Stationary Source Measures, Transportation Measures, Energy Measures, Building Measures, Agriculture Measures, Natural and Working Lands Measures, Waste Management Measures, Water Measures, and Super-GHG Pollutants Measures. The proposed project’s compliance with each of these control measures is discussed below.

Stationary Source Control Measures. The Stationary Source Control Measures are intended to reduce emissions from major stationary sources such as metal melting facilities, cement kilns, refineries, glass furnaces, and other industrial operations. The proposed project would not introduce any of these types of emission sources. Although the proposed project would include upgrades and expansion of existing water treatment plant facilities to increase treatment capacity and meet future operational needs, the proposed project would not involve the types of major industrial stationary sources targeted by these control measures. Implementation of the proposed project would require installation of new electric-powered pumps, which do not result in stationary emissions. In addition, the proposed project is expected to include one or more diesel-fueled emergency generators to support the BESS, as well as new ozone generators for water treatment upgrades. These pieces of equipment would result in stationary source emissions. However, any future stationary equipment would be subject to the Air District’s permitting requirements, including Regulation 2, Rule 1 (Permits—General Requirements) and Regulation 2, Rule 2 (Permits—New Source Review). These regulations require review of new and modified stationary sources prior to construction and implementation of applicable emission control requirements. Accordingly, the proposed project would not conflict with or obstruct implementation of the Stationary Source Control Measures.

Transportation Control Measures. The Air District identifies Transportation Control Measures as part of the Clean Air Plan to decrease emissions of criteria pollutants, TACs, and GHGs by reducing demand for motor vehicle travel, promoting efficient vehicles and transit service, decarbonizing transportation fuels, and electrifying motor vehicles and equipment. The proposed project is an infrastructure improvement and expansion project intended to increase treatment capacity and reliability at an existing water treatment facility and is not a transportation project that would alter the regional transportation network, affect transit service, or influence travel demand patterns. Operation of the expanded facility would result in a limited increase in vehicle trips associated with routine facility operations, including employee commutes, operations and maintenance staff activities, equipment inspections, preventative maintenance, service vehicles, and delivery of supplies and treatment chemicals. While these activities would generate additional vehicle trips, the increase would be limited and would primarily consist of periodic service and delivery trips necessary to support operation of the facility. Because the project would not induce substantial new travel demand, alter transportation infrastructure, or conflict with strategies intended to reduce regional vehicle emissions, it would not interfere with implementation of the Transportation Control Measures Energy Control Measures. The Clean Air Plan also includes Energy Control Measures, which are designed to reduce emissions of criteria air pollutants, TACs, and GHGs by decreasing the amount of electricity consumed in the Bay Area, as well as decreasing the carbon intensity of the

Page 426 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 19 electricity used by switching to less GHG-intensive fuel sources for electricity generation.

Because these measures apply to electrical utility providers and local government agencies (and not individual projects), the Energy Control Measures of the Clean Air Plan are not applicable to the proposed project. Nonetheless, the project would include modernization and replacement of water treatment infrastructure and equipment, which would improve the operational efficiency of the facility and support the overall intent of the Energy Control Measures by reducing energy demand associated with water treatment operations.

Building Control Measures. The Air District has authority to regulate emissions from certain sources in buildings (e.g., boilers and water heaters) but has limited authority to regulate buildings themselves. Therefore, the strategies in the control measures for this sector focus on working with local governments that do have authority over local building codes to facilitate adoption of best GHG control practices and policies. The proposed project consists of upgrades and expansion of an existing water treatment facility and is not primarily a building development project. Nevertheless, building improvements constructed as part of the project would be required to comply with applicable provisions of the California Building Standards Code, including Title 24 energy efficiency requirements and applicable green building standards. In addition, the proposed project would incorporate modernized treatment equipment and infrastructure designed to improve operational efficiency and reliability. Therefore, the proposed project would not conflict with implementation of the Building Control Measures identified in the Clean Air Plan.

Agriculture Control Measures. The Agriculture Control Measures are designed to primarily reduce emissions of CH4. Because the project does not include any agricultural activities, the Agriculture Control Measures of the Clean Air Plan are not applicable to the proposed project.

Natural and Working Lands Control Measures. The Natural and Working Lands Control Measures focus on increasing carbon sequestration on rangelands and wetlands, as well as encouraging local governments to adopt ordinances that promote urban tree plantings. Because the proposed project would not result in permanent effects to rangelands or wetlands, the Natural and Working Lands Control Measures of the Clean Air Plan are not applicable to the proposed project.

Waste Management Control Measures. The Waste Management Control Measures focus on reducing or capturing CH4 emissions from landfills and composting facilities, diverting organic materials away from landfills, and increasing waste diversion rates through efforts to reduce, reuse, and recycle. The proposed project would comply with local requirements for waste management (e.g., recycling and composting services). Therefore, the proposed project would be consistent with the Waste Management Control Measures of the Clean Air Plan.

Water Control Measures. The Water Control Measures focus on reducing emissions of criteria pollutants, TACs, and GHGs by encouraging water conservation, limiting GHG emissions from publicly owned treatment works (POTWs), and promoting the use of biogas recovery systems.

While many of these measures are directed toward water and wastewater utilities and local government agencies rather than individual projects, the proposed project would expand and

Page 427 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 20 modernize an existing water treatment facility to improve treatment capacity, operational reliability, and system efficiency. The proposed project would not interfere with implementation of any Water Control Measures and may support the overall intent of these measures through the replacement and modernization of aging infrastructure and installation of more efficient treatment equipment. Therefore, the proposed project would not conflict with the Water Control Measures identified in the Clean Air Plan.

Super-GHG Control Measures. The Super-GHG Control Measures are designed to facilitate the adoption of best GHG control practices and policies through the Air District and local government agencies. Because these measures do not apply to individual projects, the Super-GHG Control Measures are not applicable to the proposed project.

Clean Air Plan Implementation. As discussed above, the proposed project would generally implement the applicable measures outlined in the Clean Air Plan. The proposed project is an infrastructure project that supports regional growth planned in the General Plan. As described further below, implementation of the proposed project would result in no substantial increase in permanent operational emissions. Emissions that occur during construction activities are temporary and would cease upon completion of the construction period. The Air District thresholds of significance were adopted to work towards regional attainment of the AAQS. Both short-term construction and long-term operational emissions would be well below the applicable thresholds of significance, which further supports project consistency with the Clean Air Plan. Therefore, the proposed project would not disrupt or hinder implementation of a control measure from the Clean Air Plan.

In conclusion, the proposed project is determined to be consistent with the Clean Air Plan because it supports the goals of the Clean Air Plan, is consistent with applicable control measures from the Clean Air Plan, and would not disrupt or hinder implementation of any control measures from the Clean Air Plan.

Criteria Pollutant Analysis
The Air Basin is currently designated as a nonattainment area for State and federal O3 standards, the State PM10 standard, and federal nonattainment for PM2.5.The Air District’s nonattainment status is attributed to the region’s development history. Past, present, and future development projects contribute to the region’s adverse air quality impacts on a cumulative basis. By its very nature, air pollution is largely a cumulative impact. No single project is sufficient in size to, by itself, result in nonattainment of AAQS. Instead, a project’s individual emissions contribute to existing cumulatively significant adverse air quality impacts. If a project’s contribution to the cumulative impact is considerable, then the project’s impact on air quality would be considered significant.

In developing thresholds of significance for air pollutants, the Air District considered the emission levels for which a project’s individual emissions would be cumulatively considerable. If a project exceeds the identified significance thresholds, its emissions would be cumulatively considerable, resulting in significant adverse air quality impacts to the region’s existing air quality conditions.

Page 428 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 21 Therefore, additional analysis to assess cumulative impacts is unnecessary. The following analysis assesses the potential project-level construction- and operation-related air quality impacts.

Construction Emissions. During construction, short-term degradation of air quality may occur due to the release of particulate emissions generated by demolition, grading, paving, and other activities.

Emissions from construction equipment are also anticipated and would include CO, NOX, ROG, directly emitted particulate matter (PM2.5 and PM10), and TACs such as diesel exhaust particulate matter.

Table D presents the proposed project’s average daily construction emissions for each construction year compared to the Air District thresholds.

Table D: Project Construction Emissions – Bay Area Air District Analysis Construction Year
Criteria Pollutant Emissions (average pounds per day)

ROG NOX
Exhaust
PM10
Fugitive Dust
PM10
Exhaust
PM2.5
Fugitive Dust
PM2.5
2027 3.1 27.1 1.1 2.0 1.0 0.9
2028 3.2 26.4 1.0 0.3 0.9 0.1
2029 3.1 24.9 0.9 0.3 0.8 0.1
2030 2.4 19.8 0.6 0.3 0.6 0.1
2031 2.0 16.6 0.5 0.2 0.5 0.1
2032 0.8 4.5 0.1 0.1 0.1 0.0
Air District Thresholds 54.0 54.0 82.0 BMP 54.0 BMP
Exceed Threshold? No No No N/A No N/A
Source: Compiled by LSA (June 2026).

Note: Consistent with Bay Area Air District thresholds, project construction emissions presented above are average daily emissions for each construction year.

BMP = Best Management Practices
N/A = not applicable
NOX = nitrogen oxides
PM2.5 = particulate matter less than 2.5 microns in size PM10 = particulate matter less than 10 microns in size
ROG = reactive organic gases
As shown in the table, construction of the proposed project would not exceed the applicable Air District thresholds for ROG, NOx, exhaust PM10, and exhaust PM2.5. It is noted that total PM10 emission also would not exceed the Yolo-Solano Air Quality Management District’s threshold of 80 lbs/day. In addition to the construction emissions thresholds, the Air District requires implementation of its Basic Construction Best Management Practices (BMPs) to minimize fugitive dust emissions during construction and to conclude that a less than significant impact related to PM would occur. As noted in the Project Description, the project has committed to implement these control measures as a Project Design Feature. Compliance with these existing regulatory requirements, including implementation of the Air District’s Basic Construction BMPs, would minimize construction-related fugitive dust emissions. Therefore, with implementation of BMPs during construction, the proposed project would not result in a cumulatively considerable net increase of any criteria pollutant for which the project region is in nonattainment under an applicable federal or State ambient air quality standards.

Page 429 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 22 Operational Emissions. Long-term air pollutant emissions associated with the proposed project would primarily include mobile emissions from additional staff trips and material deliveries, as well as stationary source emissions associated with the two modeled diesel-fueled backup generators.

Emissions from the ozone generation system were not explicitly modeled because the system would be equipped with an ozone destruct unit that would treat residual ozone in the process off-gas prior to its release to the atmosphere. The ozone destruct unit would operate as a passive process wherein off-gas from the ozone treatment process would be routed through catalytic media that converts residual ozone (O₃) into oxygen (O₂). The ozone destruct unit would not involve an internal combustion engine and therefore would not generate combustion-related criteria pollutant emissions. The treated off-gas would consist primarily of the oxygen resulting from ozone decomposition. Accordingly, operation of the ozone generation and ozone destruct system is expected to result in negligible ozone emissions and no other substantive criteria pollutant emissions.

The daily and annual emissions associated with project operational trip generation, energy, stationary, and area sources are identified in Table E for ROG, NOX, PM10, and PM2.5.

Table E: Project Operational Emissions – Bay Area Air District Analysis Emissions Source ROG NOX PM10 PM2.5
Average Pounds per Day
Mobile Source 0.1 0.2 <0.1 <0.1
Area Source 0.3 <0.1 0.0 0.0
Energy Source <0.1 0.1 <0.1 <0.1
Off-Road 0.0 0.0 0.0 0.0
Stationary Source 0.8 3.6 <0.1 <0.1
Total Emissions 1.2 3.9 0.1 <0.1
Air District Thresholds 54.0 54.0 82.0 54.0
Exceed Threshold? No No No No
Tons per Year
Mobile Source <0.1 <0.1 <0.1 <0.1
Area Source 0.1 <0.1 0.0 0.0
Energy Source <0.1 <0.1 <0.1 <0.1
Off-Road 0.0 0.0 0.0 0.0
Stationary Source 0.1 0.7 <0.1 <0.1
Total Emissions 0.2 0.7 0.1 <0.1
Air District Thresholds 10.0 10.0 15.0 10.0
Exceed Threshold? No No No No
Source: Compiled by LSA (September 2026).

NOX = nitrogen oxides
PM2.5 = particulate matter less than 2.5 microns in size PM10 = particulate matter less than 10 microns in size
ROG = reactive organic gases
The results shown in Table E indicate the proposed project would not exceed the significance criteria for daily or annual ROG, NOX, PM10, and PM2.5 emissions; therefore, operation of the proposed project would not result in a cumulatively considerable net increase of any criteria pollutant for which the project region is in nonattainment under an applicable federal or State AAQS.

Page 430 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 23 Localized CO Impacts. Emissions and ambient concentrations of CO have decreased dramatically in the Bay Area with the introduction of the catalytic converter in 1975. No exceedances of the State or federal CO standards have been recorded at Bay Area monitoring stations since 1991. The Air District’s CEQA Guidelines include recommended methodologies for quantifying concentrations of localized CO levels for proposed transportation projects. A screening-level analysis using guidance from the Air District’s CEQA Guidelines was performed to determine the impacts of the proposed project. The screening methodology provides a conservative indication of whether the implementation of a proposed project would result in significant CO emissions. According to the Air District’s CEQA Guidelines, a proposed project would result in a less than significant impact related to localized CO concentrations if the following screening criteria are met:
• The project is consistent with an applicable congestion management program established by the county congestion management agency for designated roads or highways, and with the regional transportation plan and local congestion management agency plans. • Project traffic would not increase traffic volumes at affected intersections to more than 44,000 vehicles per hour.
• The project would not increase traffic volumes at affected intersections to more than 24,000 vehicles per hour where vertical and/or horizontal mixing is substantially limited (e.g., tunnel, parking garage, bridge underpass, natural or urban street canyon, or below-grade roadway).

Given the minor expected increase in vehicle trips required to support the proposed project, the addition of project traffic would not result in peak-hour traffic volumes at intersections in the vicinity of the project site in excess of 44,000 vehicles per hour. In addition, the project site is not located in an area where vertical or horizontal mixing is substantially limited. As such, the proposed project would not result in localized CO concentrations that exceed State or federal standards.

Sensitive Receptors
Sensitive receptors are land uses where occupants are more susceptible to adverse effects from air pollution, including residences, schools, daycare centers, hospitals, nursing homes, parks, and similar facilities. Sensitive receptors in the vicinity of the project disturbance area include residential neighborhoods and scattered rural residences located along portions of the pipeline corridors and within surrounding Fairfield and Vacaville neighborhoods. The nearest sensitive receptor to construction activities at the existing NBRWTP would be the single-family residences located approximately 540 feet west of the center of construction activities. The nearest sensitive receptor to construction activities along the pipeline alternatives would be the single-family residences located approximately 50 feet west of the centerline of the proposed Peabody Road pipeline alignment. Vamden High School is the closest school to the NBRWTP and is located approximately

1.05 miles to the south.

Construction of the NBRWTP improvements and either pipeline alignment would result in temporary emissions of criteria air pollutants, fugitive dust, diesel particulate matter (DPM), and other exhaust emissions from heavy-duty construction equipment, haul trucks, worker vehicles, and construction

Page 431 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 24 activities. Should the Peabody Road Pipeline Alignment be selected, the greatest potential for exposure would occur during active construction periods adjacent to nearby residences, where construction activities would occur closer to existing residential development. The Linear Trail Pipeline Alignment traverses predominantly open space, utility corridors, and undeveloped areas and generally maintains greater separation from sensitive receptors.

As shown in Table D, construction emissions would be well below applicable Air District significance thresholds. In addition, construction activities would be temporary, would move progressively along the pipeline alignments, and would not result in long-term exposure of nearby receptors to elevated pollutant concentrations. Active diesel-powered construction equipment would be located near any individual receptor only temporarily as trenching, pipeline installation, backfilling, and surface restoration progress along the corridor. Fugitive dust emissions would be controlled through implementation of the Air District’s Basic BMPs, including watering exposed soils, covering haul trucks, limiting track-out, and stabilizing disturbed surfaces.

Construction activities within the existing water treatment facility would be limited in scope and would primarily consist of localized site improvements, with minimal use of off-road construction equipment and correspondingly low DPM emissions. On-site excavation, grading, and material hauling associated with export of soils for the proposed new basins would generally take place in the northern portion of the NBRWTP facility, away from the nearest sensitive receptors that are located near the southern boundaries of the NBRWTP facility, thereby further reducing potential exposure at receptor locations. The majority of construction-related DPM emissions would be associated with installation of the new pipeline alignment. Most of the pipeline corridor extends through areas with no adjacent sensitive receptors. Where the alignment does approach residential land uses along the northern segment, construction activities would be linear and mobile in nature, advancing along the corridor rather than occurring at a fixed location for an extended duration. As a result, no single receptor location would be subject to sustained exposure from concentrated construction emissions. Based on the characteristics described above and the low construction emission estimates, a quantitative construction health risk assessment is not warranted for the proposed project. Overall, the potential for prolonged exposure to construction TACs is limited and significant construction-related health risk impacts are not expected to occur.

Operational emissions associated with the completed project would be minimal and would consist primarily of employee commute trips, occasional maintenance activities, chemical delivery vehicles, and operation of treatment and pumping equipment. The additional pumps would be electric-powered and would not result in TAC emissions. The new stationary equipment, including emergency generators, would result in a potential increase in TAC emissions; however, the backup generators would be operated only during emergency situations and would not represent a continuous source of emissions. In addition, the nearest sensitive receptors are located approximately 540 feet west of the center of the NRWTP site, allowing for substantial dispersion of DPM before reaching these receptors. Furthermore, as shown in Table E, operational emissions would be well below the applicable Air District significance thresholds. The proposed project would not include substantial increases in diesel truck traffic or other activities that would generate substantial concentrations of criteria pollutants or toxic air contaminants. As a result, operation of

Page 432 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 25 the proposed project would not create a localized air quality hotspot or a new source of diesel particulate matter that would expose nearby sensitive receptors to substantial health risks.

Based on the discussion above, the proposed project would not expose sensitive receptors to substantial pollutant concentrations, and impacts would be less than significant.

Objectionable Odors
Typical sources of objectionable odors include wastewater treatment facilities, landfills, composting operations, rendering plants, confined animal facilities, and certain industrial operations. The proposed project consists of expansion and modernization of the existing NBRWTP and construction of an underground transmission pipeline. Unlike wastewater treatment facilities, potable water treatment facilities, like the NBRWTP, generally do not generate substantial odor emissions because treatment processes primarily involve filtration, chemical treatment, and disinfection of drinking water supplies.

Construction of the proposed project would result in temporary emissions associated with operation of heavy-duty equipment, construction vehicles, paving activities, coatings, solvents, and other construction-related activities. These activities may generate localized odors such as diesel exhaust, asphalt, paint, or fuel odors. However, construction-related odors would be temporary, intermittent, and confined to active work areas. Construction activities would progress along the pipeline alignments and would not occur at a single location for extended periods. Therefore, any odor impacts would be localized and would not affect a substantial number of people.

Operation of the expanded NBRWTP would continue the existing potable water treatment processes currently conducted at the facility and would not introduce new odor-generating industrial activities.

The facility treats raw water for potable use and is not a wastewater or sewage treatment plant.

Although the facility includes lagoons used for management of treatment residuals generated during the potable water treatment process, the proposed project would not introduce sludge digestion, biosolids processing, wastewater treatment, or other activities commonly associated with objectionable odors. In addition, operation of the underground transmission pipeline would not generate odors. The expanded NBRWTP would continue to operate in a manner similar to existing conditions, and no substantial new odor sources would be introduced.

Therefore, the proposed project would not result in odor emissions adversely affecting local residents, and impacts would be less than significant.

CEQA Greenhouse Gas Emissions Analysis
This section describes the potential GHG impacts associated with implementation of the proposed project.

Generate Greenhouse Gas Emissions
The proposed project would generate construction- and operation-related GHG emissions and contribute to global climate change. The Air District has not addressed emissions thresholds for

Page 433 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 26 construction in its CEQA Guidelines; however, construction emissions are discussed in this section for disclosure purposes.

Construction GHG Emissions. Construction activities associated with the proposed project would produce combustion emissions from various sources. During construction, GHGs would be emitted through the operation of construction equipment and from worker and builder supply vendor vehicles, each of which typically use fossil-based fuels to operate. The combustion of fossil-based fuels creates GHGs such as CO2, CH4, and N2O. Furthermore, CH4 is emitted during the fueling of heavy equipment. Exhaust emissions from on-site construction activities would vary daily as construction activity levels change.

The Air District does not have an adopted threshold of significance for construction-related GHG emissions. However, lead agencies are encouraged to quantify and disclose GHG emissions that would occur during construction. Using CalEEMod, it was estimated that construction of the proposed project would generate approximately 5,858.5 metric tons (MT) of CO2e.

Operational GHG Emissions. Long-term GHG emissions associated with the proposed project would typically be generated from mobile sources (e.g., vehicle trips), area sources (e.g., maintenance activities and landscaping), indirect emissions from sources associated with energy consumption, waste sources (land filling and waste disposal), and water sources (water supply and conveyance, treatment, and distribution). Mobile-source GHG emissions would include project-generated vehicle trips to and from the project site. Area-source emissions would be associated with activities such as landscaping and maintenance on the project site. Energy-source emissions would be generated at off-site utility providers as a result of increased electricity demand generated by the project. Waste-source emissions generated by the proposed project include energy generated by land filling and other methods of disposal related to transporting and managing project-generated waste. In addition, water-source emissions associated with the proposed project are generated by water supply and conveyance, water treatment, water distribution, and wastewater treatment. Stationary-source emissions associated with diesel-fueled emergency generators proposed as part of the on-site microgrid were included in the operational emissions analysis.

Project GHG emissions were estimated using CalEEMod and are presented in Table F below. As presented in Table F, proposed project emissions, including those estimated for stationary sources, would be well below the 10,000 MT CO2e per year bright-line threshold applicable to stationary source projects. Therefore, the proposed project would not result in a significant impact related to stationary-source GHG emissions.

Page 434 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 27 Table F: Operational Greenhouse Gas Emissions
Emissions Source Operational Emissions
(MT CO2e/yr)
Mobile 31.4
Area 0.1
Energy 102.7
Water 4.8
Waste 3.8
Off-Road 0.0
Stationary 68.8
Total Project Operational Emissions 211.5
Air District Bright-Line Threshold 10,000
Exceeds Threshold? No
Source: Compiled by LSA (September 2026).

CO2e = carbon dioxide equivalent
MT/yr = metric tons per year
In addition to evaluating the proposed project's GHG emissions against the applicable stationary source significance threshold, the project's consistency with the City’s CAP was evaluated. As described above, the City’s CAP meets the Air District requirements for a Qualified GHG Reduction Strategy and is designed to streamline environmental review of future development projects in the City consistent with State CEQA Guidelines Section 15183.5(b) and the Air District CEQA Air Quality Guidelines. 14 The City’s CAP sets forth a menu of strategies to achieve GHG emission reductions; therefore, a qualitative analysis of the proposed project’s consistency with these policies and strategies is provided. These policies and other strategies include measures in transportation, land use, building energy, water, waste, and green infrastructure. The proposed project consists of improvements and expansion of an existing potable water treatment facility and associated transmission pipeline infrastructure. Given the nature of the proposed, many of the CAP strategies are not applicable.

The following measures and supporting actions are applicable to the proposed project:
• Measure BE-3: Reduce energy demand and consumption through energy efficiency and conservation.
• Measure SW-1: Reduce the amount of solid waste that is generated and sent to landfills, especially organic waste.
○ Supporting Action SW-1E: Construction and Demolition Waste 14 City of Fairfield. 2024. City of Fairfield Climate Action Plan. December. Website: https://www.fairfield. ca.gov/home/showpublisheddocument/12085/638701095833270000 (accessed June 2026).

Page 435 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 28 • Measure PW-1: Reduce water utility emissions by 60% below 2020 levels by 2030 and 100% by 2050.
○ Supporting Action PW-1A: Landscape Efficiency
○ Supporting Action PW-1B: Water Conservation Ordinance ○ Supporting Action PW-1C: Recycled Water Program
○ Supporting Action PW-1D: Education and Incentives
The proposed project would also be consistent with Measure BE-3 by directly improving energy efficiency of treatment operations. Construction of the proposed project would be consistent with Measure SW-1 and Supporting Action SW-1E because construction activities would implement standard construction and demolition debris management practices, including recycling and diversion of materials to the extent feasible. The proposed project would be consistent with Measure PW-1 and its supporting actions (PW-1A through PW-1D) by modernizing and expanding existing potable water treatment infrastructure in a manner that improves operational efficiency and reliability. While the proposed project would increase overall treatment capacity, it would incorporate updated treatment processes, high efficiency pumps, and associated equipment designed to improve energy efficiency relative to existing conditions, thereby reducing energy consumption per unit of water treated. Furthermore, implementation of the proposed project would not conflict with other CAP sectors, including transportation (TR-1 through TR-3), wastewater (WW-1), or carbon sequestration (CS-1), as it would not notably affect regional transportation patterns, wastewater treatment operations, or carbon sequestration programs. Therefore, the proposed project would be consistent with the applicable GHG reduction strategies from the City’s CAP.

Consistency with Greenhouse Gas Reduction Plans
Relevant GHG reduction plans include the City’s CAP and the CARB’s 2022 Scoping Plan. 15 As discussed above, the proposed project was determined to be consistent with the City’s CAP, which is a qualified GHG reduction strategy under State CEQA Guidelines Section 15183.5(b). The following discussion evaluates the proposed project for consistency with the goals of the 2022 Scoping Plan.

The 2022 Scoping Plan establishes a plan to achieve the State’s climate goals established by AB 32, SB 32, and AB 1279. The 2022 Scoping Plan focuses on outcomes needed to achieve carbon neutrality by assessing paths for clean technology, energy deployment, natural and working lands, and others, and is designed to meet the State’s long-term climate objectives and support a range of economic, environmental, energy security, environmental justice, and public health priorities. The proposed project consists of the expansion and modernization of an existing potable water treatment facility and associated infrastructure and would incorporate energy-efficient equipment and operational improvements that reduce energy use per unit of water treated compared to existing conditions.
15 CARB. 2022. 2022 Scoping Plan for Achieving Carbon Neutrality. November 16. Website:
https://ww2.arb.ca.gov/sites/default/files/2022-12/2022-sp_1.pdf (accessed June 2026).

Page 436 of 1497 ends

9/30/26 \\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx 29 As a utility infrastructure project, the proposed project supports planned General Plan buildout and does not induce growth beyond that already assumed in adopted planning documents. Furthermore, the proposed project would not substantially increase VMT, and would be subject to applicable Air District permitting requirements for any new stationary equipment. Therefore, the proposed project would be consistent with the overarching objectives set forth in the 2022 Scoping Plan, and would not conflict with an applicable plan, policy, or regulation adopted for the purpose of reducing GHG emissions.

CONCLUSION
Based on the air quality modeling prepared for the proposed project, construction and operational criteria pollutant emissions would not exceed the applicable General Conformity de minimis levels nor the applicable Air District thresholds of significance. In addition, the proposed project is not expected to produce significant emissions that would affect nearby sensitive receptors. The proposed project would also not result in objectionable odors affecting a substantial number of people. Finally, the proposed project would not generate GHG emissions that result in a significant impact on the environment or otherwise conflict with a plan or policy adopted for the purpose of reducing GHG emissions.

Attachment A: CalEEMod Output Sheets

Page 437 of 1497 ends

AIR QUALITY AND GREENHOUSE GAS E MISSIONS T ECHNICAL MEMORANDUM S EPTEMBER 2026

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

SOLANO C OUNTY , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\Technical Studies\Air Quality\v5\NBRWTP - AQ.GHG Memo.docx (09/30/26)

ATTACHMENT A

CALEEMOD OUTPUT SHEETS

Page 438 of 1497 ends

Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Fairfield-Vacaville Water Works Project v5 Custom Report Table of Contents

1. Basic Project Information

1.1. Basic Project Information

1.2. Land Use Types

1.3. User-Selected Emission Reduction Measures by Emissions Sector

2. Emissions Summary

2.1. Construction Emissions Compared Against Thresholds

2.2. Construction Emissions by Year

2.2.1. Total Construction Emissions by Year, Unmitigated

2.2.2. Onsite Construction Emissions by Year, Unmitigated

2.2.3. Offsite Construction Emissions by Year, Unmitigated

2.3. Operations Emissions Compared Against Thresholds

2.4. Operations Emissions by Sector, Unmitigated

3. Construction Emissions Details

3.1. Demolition (2027)

3.1.1. Onsite - Unmitigated

3.1.2. Offsite - Unmitigated

3.2. Site Preparation (2027)

3.2.1. Onsite - Unmitigated
1 / 100 Page 439 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

3.2.2. Offsite - Unmitigated

3.3. Grading (2027)

3.3.1. Onsite - Unmitigated

3.3.2. Offsite - Unmitigated

3.4. Building Construction (2027)

3.4.1. Onsite - Unmitigated

3.4.2. Offsite - Unmitigated

3.5. Building Construction (2028)

3.5.1. Onsite - Unmitigated

3.5.2. Offsite - Unmitigated

3.6. Building Construction (2029)

3.6.1. Onsite - Unmitigated

3.6.2. Offsite - Unmitigated

3.7. Building Construction (2030)

3.7.1. Onsite - Unmitigated

3.7.2. Offsite - Unmitigated

3.8. Building Construction (2031)

3.8.1. Onsite - Unmitigated

3.8.2. Offsite - Unmitigated

3.9. Building Construction (2032)

3.9.1. Onsite - Unmitigated

3.9.2. Offsite - Unmitigated
2 / 100 Page 440 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

3.10. Paving (2032)

3.10.1. Onsite - Unmitigated

3.10.2. Offsite - Unmitigated

3.11. Architectural Coating (2032)

3.11.1. Onsite - Unmitigated

3.11.2. Offsite - Unmitigated

3.12. Linear, Grubbing & Land Clearing (2027)

3.12.1. Onsite - Unmitigated

3.12.2. Offsite - Unmitigated

3.13. Linear, Grading & Excavation (2027)

3.13.1. Onsite - Unmitigated

3.13.2. Offsite - Unmitigated

3.14. Linear, Grading & Excavation (2028)

3.14.1. Onsite - Unmitigated

3.14.2. Offsite - Unmitigated

3.15. Linear, Grading & Excavation (2029)

3.15.1. Onsite - Unmitigated

3.15.2. Offsite - Unmitigated

3.16. Linear, Grading & Excavation (2030)

3.16.1. Onsite - Unmitigated

3.16.2. Offsite - Unmitigated

3.17. Linear, Drainage, Utilities, & Sub-Grade (2030)
3 / 100 Page 441 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

3.17.1. Onsite - Unmitigated

3.17.2. Offsite - Unmitigated

3.18. Linear, Drainage, Utilities, & Sub-Grade (2031)

3.18.1. Onsite - Unmitigated

3.18.2. Offsite - Unmitigated

3.19. Linear, Paving (2031)

3.19.1. Onsite - Unmitigated

3.19.2. Offsite - Unmitigated

3.20. Linear, Paving (2032)

3.20.1. Onsite - Unmitigated

3.20.2. Offsite - Unmitigated

4. Operations Emissions Details

4.1. Mobile Emissions by Land Use

4.1.1. Unmitigated

4.2. Energy

4.2.1. Electricity Emissions By Land Use - Unmitigated

4.2.3. Natural Gas Emissions By Land Use - Unmitigated

4.3. Area Emissions by Source

4.3.1. Unmitigated

4.4. Water Emissions by Land Use

4.4.1. Unmitigated

4.5. Waste Emissions by Land Use
4 / 100 Page 442 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

4.5.1. Unmitigated

4.6. Refrigerant Emissions by Land Use

4.6.1. Unmitigated

4.7. Offroad Emissions By Equipment Type

4.7.1. Unmitigated

4.8. Stationary Emissions By Equipment Type

4.8.1. Unmitigated

4.9. User Defined Emissions By Equipment Type

4.9.1. Unmitigated

4.10. Soil Carbon Accumulation By Vegetation Type

4.10.1. Soil Carbon Accumulation By Vegetation Type - Unmitigated

4.10.2. Above and Belowground Carbon Accumulation by Land Use Type - Unmitigated

4.10.3. Avoided and Sequestered Emissions by Species - Unmitigated

5. Activity Data

5.1. Construction Schedule

5.2. Off-Road Equipment

5.2.1. Unmitigated

5.3. Construction Vehicles

5.3.1. Unmitigated

5.4. Vehicles

5.4.1. Construction Vehicle Control Strategies

5.5. Architectural Coatings
5 / 100 Page 443 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

5.6. Dust Mitigation

5.6.1. Construction Earthmoving Activities

5.6.2. Construction Earthmoving Control Strategies

5.7. Construction Paving

5.8. Construction Electricity Consumption and Emissions Factors

5.9. Operational Mobile Sources

5.9.1. Unmitigated

5.10. Operational Area Sources

5.10.1. Hearths

5.10.2. Architectural Coatings

5.10.3. Landscape Equipment

5.11. Operational Energy Consumption

5.11.1. Unmitigated

5.12. Operational Water and Wastewater Consumption

5.12.1. Unmitigated

5.13. Operational Waste Generation

5.13.1. Unmitigated

5.14. Operational Refrigeration and Air Conditioning Equipment

5.14.1. Unmitigated

5.15. Operational Off-Road Equipment

5.15.1. Unmitigated

5.16. Stationary Sources
6 / 100 Page 444 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

5.16.1. Emergency Generators and Fire Pumps

5.16.2. Process Boilers

5.17. User Defined

5.18. Vegetation

5.18.1. Land Use Change

5.18.1.1. Unmitigated

5.18.1. Biomass Cover Type

5.18.1.1. Unmitigated

5.18.2. Sequestration

5.18.2.1. Unmitigated

8. User Changes to Default Data

8.1. Justifications

8.3. Land Use

8.4. Construction

8.4.4. Dust from Material Movement

8.5. Operations

8.5.1. Mobile Sources

8.5.1.1. Vehicle Data

8.5.1.2. Fleet Mix

8.5.7. Off-Road Equipment

8.5.7.1. Off-Road Equipment
7 / 100 Page 445 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

1. Basic Project Information

1.1. Basic Project Information
Data Field Value
Project Name Fairfield-Vacaville Water Works Project v5 Construction Start Date 1/1/2027
Operational Year 2033
Lead Agency —
Land Use Scale Project/site
Analysis Level for Defaults County
Windspeed (m/s) 5.70000
Precipitation (days) 2.20000
Location 38.29075227496273, -121.93970102741707
County Solano-San Francisco
City Fairfield
Air District Bay Area AQMD
Air Basin San Francisco Bay Area
TAZ 841
EDFZ 4
Electric Utility Pacific Gas & Electric Company
Gas Utility Pacific Gas & Electric
8 / 100 Page 446 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Data Field Value
App Version 2022.1.1.46

1.2. Land Use Types
Land Use Subtype Size Unit Lot Acreage Building Area (sq ft) Landscape Area (sq ft)
Special Landscape
Area (sq ft)
Population Description
Road Widening 1.80000 Mile 1.30000 0.00000 — — — represents new pipeline alignment
General Office
Building

10.00000 1000sqft 56.1100 10,000.00 0.00000 — — expanded operations building
Unrefrigerated
Warehouse-No Rail

2.90000 1000sqft 0.00000 0.00000 0.00000 — — represents BESS enclosures

1.3. User-Selected Emission Reduction Measures by Emissions Sector No measures selected

2. Emissions Summary

2.1. Construction Emissions Compared Against Thresholds Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Un/Mit. TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Unmit. 7.92891 6.62491 56.5889 68.3697 0.14595 2.28116 7.93863 9.29507 2.09002 4.00333 5.25125 — 16,842.5 16,842.5 0.66966 0.42392 5.61954 16,991.1 9 / 100 Page 447 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Un/Mit. TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Unmit. 7.91707 6.61217 56.7597 68.1332 0.14595 2.28116 3.43080 5.71196 2.09002 1.55964 3.64967 — 16,799.6 16,799.6 0.67412 0.42541 0.14585 16,943.4 Average
Daily
(Max)
— — — — — — — — — — — — — — — — — —
Unmit. 3.80151 3.19821 27.0804 37.9826 0.07027 1.09877 1.97466 3.07343 1.00827 0.92524 1.93351 — 7,807.91 7,807.91 0.31114 0.14844 0.89500 7,840.06 Annual
(Max)
— — — — — — — — — — — — — — — — — —
Unmit. 0.69378 0.58367 4.94217 6.93183 0.01282 0.20053 0.36038 0.56090 0.18401 0.16886 0.35287 — 1,292.69 1,292.69 0.05151 0.02458 0.14818 1,298.01

2.2. Construction Emissions by Year

2.2.1. Total Construction Emissions by Year, Unmitigated Includes both onsite and offsite emissions.

Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Year TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily - S
ummer
(Max)
— — — — — — — — — — — — — — — — — —
2027 7.92891 6.62491 56.5889 68.3697 0.14595 2.28116 7.93863 9.29507 2.09002 4.00333 5.25125 — 16,842.5 16,842.5 0.66966 0.42392 5.61954 16,991.1 2028 5.31769 4.47532 36.7850 53.2618 0.09811 1.39864 0.44019 1.83883 1.28682 0.10365 1.39047 — 10,928.6 10,928.6 0.43329 0.11077 1.55757 10,974.0 2029 5.14628 4.33003 34.8180 52.9457 0.09809 1.27885 0.44019 1.71904 1.17662 0.10365 1.28026 — 10,917.5 10,917.5 0.43322 0.09768 1.40194 10,958.8 2030 3.90367 3.28654 27.4963 40.7723 0.07893 0.87007 0.39182 1.26189 0.80021 0.09201 0.89222 — 8,512.21 8,512.21 0.33603 0.07446 1.10256 8,543.91 10 / 100 Page 448 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Year TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e 2031 3.81901 3.21568 26.5652 40.5801 0.07893 0.82838 0.39182 1.22019 0.76213 0.09201 0.85414 — 8,503.99 8,503.99 0.33603 0.07416 0.97969 8,535.47 2032 2.37165 2.22375 12.5294 22.5609 0.03027 0.37919 0.33066 0.70985 0.34885 0.07751 0.42636 — 3,593.06 3,593.06 0.13827 0.02924 0.71558 3,605.94 Daily -
Winter
(Max)
— — — — — — — — — — — — — — — — — —
2027 7.91707 6.61217 56.7597 68.1332 0.14595 2.28116 3.43080 5.71196 2.09002 1.55964 3.64967 — 16,799.6 16,799.6 0.67412 0.42541 0.14585 16,943.4 2028 5.30975 4.46632 36.8248 53.0792 0.09811 1.39864 0.44019 1.83883 1.28682 0.10365 1.39047 — 10,896.4 10,896.4 0.43664 0.11195 0.04041 10,940.7 2029 5.14063 4.32327 34.8431 52.7911 0.09809 1.27885 0.44019 1.71904 1.17662 0.10365 1.28026 — 10,886.0 10,886.0 0.43546 0.11193 0.03627 10,930.2 2030 4.95578 4.17801 33.4588 52.5127 0.09810 1.20888 0.44019 1.64907 1.11176 0.10365 1.21540 — 10,877.2 10,877.2 0.43435 0.11139 0.03254 10,921.3 2031 3.81487 3.20956 26.5855 40.4320 0.07893 0.82838 0.39182 1.22019 0.76213 0.09201 0.85414 — 8,476.63 8,476.63 0.33801 0.08695 0.02535 8,511.02 2032 1.98878 1.67605 15.1571 25.8836 0.04139 0.40917 0.33066 0.70985 0.37646 0.07751 0.43430 — 4,553.70 4,553.70 0.18093 0.04953 0.01859 4,572.99 Average
Daily
— — — — — — — — — — — — — — — — — —
2027 3.73914 3.13114 27.0804 31.4278 0.06182 1.09877 1.97466 3.07343 1.00827 0.92524 1.93351 — 7,060.70 7,060.70 0.28212 0.14844 0.89500 7,112.88 2028 3.80151 3.19821 26.3617 37.9826 0.07027 1.00176 0.31485 1.31661 0.92168 0.07413 0.99580 — 7,807.91 7,807.91 0.31114 0.08018 0.48102 7,840.06 2029 3.67032 3.08645 24.8835 37.6676 0.07007 0.91346 0.31399 1.22745 0.84044 0.07392 0.91436 — 7,779.04 7,779.04 0.31025 0.07911 0.43222 7,810.81 2030 2.81223 2.36706 19.8143 29.3173 0.05690 0.63076 0.28080 0.91156 0.58012 0.06594 0.64606 — 6,128.80 6,128.80 0.24339 0.06226 0.34142 6,153.78 2031 2.33759 1.96762 16.5840 25.7195 0.04822 0.50731 0.24756 0.75486 0.46674 0.05821 0.52495 — 5,206.19 5,206.19 0.20678 0.04604 0.26890 5,225.35 2032 0.88780 0.79701 4.51799 7.98210 0.01132 0.12822 0.10704 0.23525 0.11796 0.02513 0.14309 — 1,298.77 1,298.77 0.05079 0.01102 0.10070 1,303.42 Annual — — — — — — — — — — — — — — — — — —
2027 0.68239 0.57143 4.94217 5.73557 0.01128 0.20053 0.36038 0.56090 0.18401 0.16886 0.35287 — 1,168.98 1,168.98 0.04671 0.02458 0.14818 1,177.62 2028 0.69378 0.58367 4.81102 6.93183 0.01282 0.18282 0.05746 0.24028 0.16821 0.01353 0.18173 — 1,292.69 1,292.69 0.05151 0.01328 0.07964 1,298.01 2029 0.66983 0.56328 4.54124 6.87434 0.01279 0.16671 0.05730 0.22401 0.15338 0.01349 0.16687 — 1,287.91 1,287.91 0.05137 0.01310 0.07156 1,293.17 11 / 100 Page 449 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Year TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e 2030 0.51323 0.43199 3.61611 5.35040 0.01038 0.11511 0.05125 0.16636 0.10587 0.01203 0.11791 — 1,014.69 1,014.69 0.04030 0.01031 0.05653 1,018.83 2031 0.42661 0.35909 3.02659 4.69382 0.00880 0.09258 0.04518 0.13776 0.08518 0.01062 0.09580 — 861.945 861.945 0.03423 0.00762 0.04452 865.117 2032 0.16202 0.14545 0.82453 1.45673 0.00207 0.02340 0.01953 0.04293 0.02153 0.00459 0.02611 — 215.025 215.025 0.00841 0.00182 0.01667 215.796

2.2.2. Onsite Construction Emissions by Year, Unmitigated Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Year TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily - S
ummer
(Max)
— — — — — — — — — — — — — — — — — —
2027 7.56457 6.35634 54.2985 65.2356 0.13378 2.24656 7.66997 9.02640 2.06684 3.94036 5.18828 — 14,487.0 14,487.0 0.58766 0.11753 0.00000 14,536.8 2028 5.13058 4.30697 36.6095 51.5440 0.09762 1.39766 0.00249 1.40015 1.28585 0.00027 1.28612 — 10,433.7 10,433.7 0.42323 0.08465 0.00000 10,469.5 2029 4.96816 4.17063 34.6469 51.3395 0.09761 1.27787 0.00249 1.28036 1.17564 0.00027 1.17591 — 10,432.1 10,432.1 0.42317 0.08463 0.00000 10,467.9 2030 3.76149 3.14880 27.3785 39.4089 0.07863 0.86947 0.00249 0.87195 0.79991 0.00027 0.80018 — 8,100.63 8,100.63 0.32860 0.06572 0.00000 8,128.43 2031 3.68287 3.08297 26.4502 39.2802 0.07863 0.82807 0.00249 0.83056 0.76183 0.00027 0.76210 — 8,100.63 8,100.63 0.32860 0.06572 0.00000 8,128.43 2032 2.30003 2.15326 12.4679 21.5032 0.03027 0.37919 0.00000 0.37919 0.34885 0.00000 0.34885 — 3,277.96 3,277.96 0.13297 0.02659 0.00000 3,289.21 Daily -
Winter
(Max)
— — — — — — — — — — — — — — — — — —
2027 7.56457 6.35634 54.2985 65.2356 0.13378 2.24656 2.38608 4.63265 2.06684 1.29557 3.36241 — 14,487.0 14,487.0 0.58766 0.11753 0.00000 14,536.8 2028 5.13058 4.30697 36.6095 51.5440 0.09762 1.39766 0.00249 1.40015 1.28585 0.00027 1.28612 — 10,433.7 10,433.7 0.42323 0.08465 0.00000 10,469.5 2029 4.96816 4.17063 34.6469 51.3395 0.09761 1.27787 0.00249 1.28036 1.17564 0.00027 1.17591 — 10,432.1 10,432.1 0.42317 0.08463 0.00000 10,467.9 2030 4.80246 4.03150 33.2681 51.1435 0.09761 1.20790 0.00249 1.21039 1.11127 0.00027 1.11154 — 10,432.1 10,432.1 0.42317 0.08463 0.00000 10,467.9 2031 3.68287 3.08297 26.4502 39.2802 0.07863 0.82807 0.00249 0.83056 0.76183 0.00027 0.76210 — 8,100.63 8,100.63 0.32860 0.06572 0.00000 8,128.43 12 / 100 Page 450 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Year TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e 2032 1.91016 1.60130 15.0583 25.2017 0.04108 0.40887 0.00000 0.40887 0.37616 0.00000 0.37616 — 4,311.77 4,311.77 0.17490 0.03498 0.00000 4,326.56 Average
Daily
— — — — — — — — — — — — — — — — — —
2027 3.59118 3.01660 26.3230 30.2127 0.05812 1.08827 1.56075 2.64902 1.00121 0.82239 1.82360 — 6,261.14 6,261.14 0.25398 0.05080 0.00000 6,282.62 2028 3.67474 3.08484 26.2213 36.9180 0.06992 1.00106 0.00178 1.00285 0.92098 0.00019 0.92117 — 7,473.03 7,473.03 0.30314 0.06063 0.00000 7,498.68 2029 3.54869 2.97902 24.7478 36.6710 0.06972 0.91276 0.00178 0.91454 0.83974 0.00019 0.83994 — 7,451.51 7,451.51 0.30227 0.06045 0.00000 7,477.08 2030 2.71530 2.27333 19.7174 28.4707 0.05668 0.63032 0.00178 0.63210 0.57989 0.00019 0.58009 — 5,850.04 5,850.04 0.23730 0.04746 0.00000 5,870.12 2031 2.25658 1.88953 16.4974 25.0167 0.04801 0.50709 0.00124 0.50833 0.46652 0.00013 0.46666 — 4,963.14 4,963.14 0.20133 0.04027 0.00000 4,980.18 2032 0.85368 0.76385 4.49395 7.68834 0.01129 0.12819 0.00000 0.12819 0.11794 0.00000 0.11794 — 1,201.05 1,201.05 0.04872 0.00974 0.00000 1,205.18 Annual — — — — — — — — — — — — — — — — — —
2027 0.65539 0.55053 4.80394 5.51382 0.01061 0.19861 0.28484 0.48345 0.18272 0.15009 0.33281 — 1,036.60 1,036.60 0.04205 0.00841 0.00000 1,040.16 2028 0.67064 0.56298 4.78538 6.73754 0.01276 0.18269 0.00033 0.18302 0.16808 0.00004 0.16811 — 1,237.25 1,237.25 0.05019 0.01004 0.00000 1,241.49 2029 0.64764 0.54367 4.51648 6.69246 0.01272 0.16658 0.00032 0.16690 0.15325 0.00004 0.15329 — 1,233.68 1,233.68 0.05004 0.01001 0.00000 1,237.92 2030 0.49554 0.41488 3.59843 5.19591 0.01034 0.11503 0.00032 0.11536 0.10583 0.00004 0.10587 — 968.541 968.541 0.03929 0.00786 0.00000 971.865 2031 0.41183 0.34484 3.01077 4.56555 0.00876 0.09254 0.00023 0.09277 0.08514 0.00002 0.08516 — 821.705 821.705 0.03333 0.00667 0.00000 824.525 2032 0.15580 0.13940 0.82015 1.40312 0.00206 0.02340 0.00000 0.02340 0.02152 0.00000 0.02152 — 198.848 198.848 0.00807 0.00161 0.00000 199.531

2.2.3. Offsite Construction Emissions by Year, Unmitigated Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Year TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily - S
ummer
(Max)
— — — — — — — — — — — — — — — — — —
13 / 100 Page 451 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Year TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e 2027 0.36434 0.26857 2.29043 3.13413 0.01216 0.03459 1.04471 1.07931 0.02319 0.26407 0.28725 — 2,355.42 2,355.42 0.08200 0.30639 5.61954 2,454.39 2028 0.18712 0.16835 0.17553 1.71778 0.00049 0.00098 0.43771 0.43868 0.00098 0.10338 0.10435 — 494.894 494.894 0.01005 0.02612 1.55757 504.488 2029 0.17812 0.15941 0.17101 1.60620 0.00049 0.00098 0.43771 0.43868 0.00098 0.10338 0.10435 — 485.352 485.352 0.01005 0.01305 1.40194 490.893 2030 0.14218 0.13775 0.11782 1.36342 0.00030 0.00061 0.38933 0.38993 0.00030 0.09174 0.09204 — 411.580 411.580 0.00744 0.00874 1.10256 415.473 2031 0.13614 0.13271 0.11504 1.29981 0.00030 0.00030 0.38933 0.38963 0.00030 0.09174 0.09204 — 403.360 403.360 0.00744 0.00844 0.97969 407.040 2032 0.11173 0.10997 0.06155 1.05769 0.00000 0.00000 0.33066 0.33066 0.00000 0.07751 0.07751 — 315.098 315.098 0.00530 0.00265 0.71558 316.735 Daily -
Winter
(Max)
— — — — — — — — — — — — — — — — — —
2027 0.35249 0.25582 2.46120 2.89756 0.01216 0.03459 1.04471 1.07931 0.02319 0.26407 0.28725 — 2,312.60 2,312.60 0.08646 0.30788 0.14585 2,406.65 2028 0.17918 0.15935 0.21533 1.53519 0.00049 0.00098 0.43771 0.43868 0.00098 0.10338 0.10435 — 462.762 462.762 0.01341 0.02730 0.04041 471.273 2029 0.17247 0.15264 0.19619 1.45166 0.00049 0.00098 0.43771 0.43868 0.00098 0.10338 0.10435 — 453.840 453.840 0.01229 0.02730 0.03627 462.319 2030 0.15332 0.14651 0.19067 1.36920 0.00049 0.00098 0.43771 0.43868 0.00049 0.10338 0.10386 — 445.131 445.131 0.01118 0.02675 0.03254 453.416 2031 0.13200 0.12659 0.13526 1.15178 0.00030 0.00030 0.38933 0.38963 0.00030 0.09174 0.09204 — 376.001 376.001 0.00942 0.02123 0.02535 382.589 2032 0.10820 0.10468 0.09872 0.94120 0.00030 0.00030 0.33066 0.33066 0.00030 0.07751 0.07751 — 291.498 291.498 0.00706 0.01455 0.01859 295.557 Average
Daily
— — — — — — — — — — — — — — — — — —
2027 0.14796 0.11454 0.75741 1.21507 0.00370 0.01050 0.41392 0.42441 0.00706 0.10285 0.10991 — 799.561 799.561 0.02814 0.09764 0.89500 830.257 2028 0.12678 0.11337 0.14046 1.06456 0.00035 0.00070 0.31306 0.31376 0.00070 0.07393 0.07463 — 334.878 334.878 0.00800 0.01955 0.48102 341.386 2029 0.12164 0.10743 0.13570 0.99660 0.00035 0.00070 0.31221 0.31291 0.00070 0.07373 0.07443 — 327.533 327.533 0.00798 0.01866 0.43222 333.726 2030 0.09694 0.09373 0.09688 0.84656 0.00022 0.00044 0.27902 0.27947 0.00022 0.06575 0.06597 — 278.758 278.758 0.00608 0.01480 0.34142 283.663 2031 0.08101 0.07809 0.08668 0.70284 0.00022 0.00022 0.24632 0.24654 0.00022 0.05808 0.05829 — 243.051 243.051 0.00545 0.00578 0.26890 245.177 2032 0.03412 0.03316 0.02404 0.29377 0.00002 0.00002 0.10704 0.10706 0.00002 0.02513 0.02515 — 97.7115 97.7115 0.00207 0.00128 0.10070 98.2440 14 / 100 Page 452 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Year TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Annual — — — — — — — — — — — — — — — — — —
2027 0.02700 0.02090 0.13823 0.22175 0.00068 0.00192 0.07554 0.07746 0.00129 0.01877 0.02006 — 132.376 132.376 0.00466 0.01617 0.14818 137.458 2028 0.02314 0.02069 0.02563 0.19428 0.00006 0.00013 0.05713 0.05726 0.00013 0.01349 0.01362 — 55.4428 55.4428 0.00133 0.00324 0.07964 56.5203 2029 0.02220 0.01961 0.02477 0.18188 0.00006 0.00013 0.05698 0.05711 0.00013 0.01346 0.01358 — 54.2268 54.2268 0.00132 0.00309 0.07156 55.2521 2030 0.01769 0.01711 0.01768 0.15450 0.00004 0.00008 0.05092 0.05100 0.00004 0.01200 0.01204 — 46.1516 46.1516 0.00101 0.00245 0.05653 46.9637 2031 0.01478 0.01425 0.01582 0.12827 0.00004 0.00004 0.04495 0.04499 0.00004 0.01060 0.01064 — 40.2398 40.2398 0.00090 0.00096 0.04452 40.5919 2032 0.00623 0.00605 0.00439 0.05361 < 0.0000
05 < 0.0000
05 0.01953 0.01954 < 0.0000
05 0.00459 0.00459 — 16.1773 16.1773 0.00034 0.00021 0.01667 16.2654

2.3. Operations Emissions Compared Against Thresholds
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Un/Mit. TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Unmit. 6.93026 6.32732 26.6444 16.1427 0.03072 0.87745 0.14878 1.02623 0.87717 0.03792 0.91509 11.1722 3,838.96 3,850.13 1.35340 0.06057 0.32965 3,902.35 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Unmit. 6.84791 6.25048 26.6554 15.7202 0.03062 0.87668 0.14878 1.02546 0.87659 0.03792 0.91451 11.1722 3,829.33 3,840.50 1.35449 0.06124 0.03224 3,892.64 Average
Daily
(Max)
— — — — — — — — — — — — — — — — — —
Unmit. 1.28330 1.18736 3.85019 2.89786 0.00614 0.12705 0.14857 0.27562 0.12686 0.03787 0.16473 11.1722 1,223.05 1,234.22 1.24922 0.04049 0.15616 1,277.67 15 / 100 Page 453 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Un/Mit. TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Annual
(Max)
— — — — — — — — — — — — — — — — — —
Unmit. 0.23420 0.21669 0.70266 0.52886 0.00112 0.02319 0.02711 0.05030 0.02315 0.00691 0.03006 1.84968 202.490 204.340 0.20682 0.00670 0.02585 211.534

2.4. Operations Emissions by Sector, Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Sector TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Mobile 0.11043 0.10194 0.14372 0.57889 0.00184 0.00172 0.14878 0.15050 0.00163 0.03792 0.03955 — 191.356 191.356 0.00911 0.01486 0.30533 196.318 Area 0.32003 0.31407 0.00366 0.43493 0.00003 0.00077 — 0.00077 0.00058 — 0.00058 — 1.78847 1.78847 0.00008 0.00002 — 1.79491 Energy 0.00853 0.00426 0.07754 0.06514 0.00047 0.00589 — 0.00589 0.00589 — 0.00589 — 614.708 614.708 0.09267 0.01041 — 620.128 Water — — — — — — — — — — — 4.69087 8.85930 13.5502 0.48243 0.01160 — 29.0683 Waste — — — — — — — — — — — 6.48128 0.00000 6.48128 0.64778 0.00000 — 22.6758 Refrig. — — — — — — — — — — — — — — — — 0.02432 0.02432 Off-Road0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 — 0.00000 — 0.00000 0.00000 0.00000 0.00000 — 0.00000 Stationa
ry

6.49127 5.90705 26.4195 15.0637 0.02839 0.86906 0.00000 0.86906 0.86906 0.00000 0.86906 0.00000 3,022.25 3,022.25 0.12135 0.02368 0.00000 3,032.34 Total 6.93026 6.32732 26.6444 16.1427 0.03072 0.87745 0.14878 1.02623 0.87717 0.03792 0.91509 11.1722 3,838.96 3,850.13 1.35340 0.06057 0.32965 3,902.35 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Mobile 0.10553 0.09658 0.15840 0.59135 0.00176 0.00173 0.14878 0.15050 0.00164 0.03792 0.03956 — 183.508 183.508 0.01027 0.01555 0.00792 188.406 16 / 100 Page 454 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Sector TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Area 0.24258 0.24258 — — — — — — — — — — — — — — — —
Energy 0.00853 0.00426 0.07754 0.06514 0.00047 0.00589 — 0.00589 0.00589 — 0.00589 — 614.708 614.708 0.09267 0.01041 — 620.128 Water — — — — — — — — — — — 4.69087 8.85930 13.5502 0.48243 0.01160 — 29.0683 Waste — — — — — — — — — — — 6.48128 0.00000 6.48128 0.64778 0.00000 — 22.6758 Refrig. — — — — — — — — — — — — — — — — 0.02432 0.02432 Off-Road0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 — 0.00000 — 0.00000 0.00000 0.00000 0.00000 — 0.00000 Stationa
ry

6.49127 5.90705 26.4195 15.0637 0.02839 0.86906 0.00000 0.86906 0.86906 0.00000 0.86906 0.00000 3,022.25 3,022.25 0.12135 0.02368 0.00000 3,032.34 Total 6.84791 6.25048 26.6554 15.7202 0.03062 0.87668 0.14878 1.02546 0.87659 0.03792 0.91451 11.1722 3,829.33 3,840.50 1.35449 0.06124 0.03224 3,892.64 Average
Daily
— — — — — — — — — — — — — — — — — —
Mobile 0.10477 0.09607 0.15174 0.55472 0.00177 0.00172 0.14857 0.15029 0.00163 0.03787 0.03950 — 184.595 184.595 0.00968 0.01522 0.13184 189.504 Area 0.28078 0.27783 0.00180 0.21448 0.00001 0.00038 — 0.00038 0.00029 — 0.00029 — 0.88198 0.88198 0.00004 0.00001 — 0.88516 Energy 0.00853 0.00426 0.07754 0.06514 0.00047 0.00589 — 0.00589 0.00589 — 0.00589 — 614.708 614.708 0.09267 0.01041 — 620.128 Water — — — — — — — — — — — 4.69087 8.85930 13.5502 0.48243 0.01160 — 29.0683 Waste — — — — — — — — — — — 6.48128 0.00000 6.48128 0.64778 0.00000 — 22.6758 Refrig. — — — — — — — — — — — — — — — — 0.02432 0.02432 Off-Road0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 — 0.00000 — 0.00000 0.00000 0.00000 0.00000 — 0.00000 Stationa
ry

0.88921 0.80919 3.61911 2.06353 0.00389 0.11905 0.00000 0.11905 0.11905 0.00000 0.11905 0.00000 414.007 414.007 0.01662 0.00324 0.00000 415.389 Total 1.28330 1.18736 3.85019 2.89786 0.00614 0.12705 0.14857 0.27562 0.12686 0.03787 0.16473 11.1722 1,223.05 1,234.22 1.24922 0.04049 0.15616 1,277.67 Annual — — — — — — — — — — — — — — — — — —
17 / 100 Page 455 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Sector TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Mobile 0.01912 0.01753 0.02769 0.10124 0.00032 0.00031 0.02711 0.02743 0.00030 0.00691 0.00721 — 30.5618 30.5618 0.00160 0.00252 0.02183 31.3746 Area 0.05124 0.05070 0.00033 0.03914 < 0.0000
05 0.00007 — 0.00007 0.00005 — 0.00005 — 0.14602 0.14602 0.00001 < 0.0000 05 — 0.14655
Energy 0.00156 0.00078 0.01415 0.01189 0.00008 0.00108 — 0.00108 0.00108 — 0.00108 — 101.772 101.772 0.01534 0.00172 — 102.669 Water — — — — — — — — — — — 0.77663 1.46676 2.24338 0.07987 0.00192 — 4.81259 Waste — — — — — — — — — — — 1.07305 0.00000 1.07305 0.10725 0.00000 — 3.75424 Refrig. — — — — — — — — — — — — — — — — 0.00403 0.00403 Off-Road0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 — 0.00000 — 0.00000 0.00000 0.00000 0.00000 — 0.00000 Stationa
ry

0.16228 0.14768 0.66049 0.37659 0.00071 0.02173 0.00000 0.02173 0.02173 0.00000 0.02173 0.00000 68.5436 68.5436 0.00275 0.00054 0.00000 68.7724 Total 0.23420 0.21669 0.70266 0.52886 0.00112 0.02319 0.02711 0.05030 0.02315 0.00691 0.03006 1.84968 202.490 204.340 0.20682 0.00670 0.02585 211.534

3. Construction Emissions Details

3.1. Demolition (2027)

3.1.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
18 / 100 Page 456 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Off-Road Eq
uipment

2.63907 2.21478 19.9005 18.6307 0.03253 0.79594 — 0.79594 0.73226 — 0.73226 — 3,426.90 3,426.90 0.13901 0.02780 — 3,438.66 Demoliti
on
— — — — — — 0.00000 0.00000 — 0.00000 0.00000 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

2.63907 2.21478 19.9005 18.6307 0.03253 0.79594 — 0.79594 0.73226 — 0.73226 — 3,426.90 3,426.90 0.13901 0.02780 — 3,438.66 Demoliti
on
— — — — — — 0.00000 0.00000 — 0.00000 0.00000 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.50612 0.42475 3.81654 3.57301 0.00624 0.15265 — 0.15265 0.14043 — 0.14043 — 657.213 657.213 0.02666 0.00533 — 659.468 Demoliti
on
— — — — — — 0.00000 0.00000 — 0.00000 0.00000 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.09237 0.07752 0.69652 0.65207 0.00114 0.02786 — 0.02786 0.02563 — 0.02563 — 108.809 108.809 0.00441 0.00088 — 109.183 19 / 100 Page 457 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Demoliti
on
— — — — — — 0.00000 0.00000 — 0.00000 0.00000 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.1.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.05536 0.05050 0.03280 0.52789 0.00000 0.00000 0.12400 0.12400 0.00000 0.02906 0.02906 — 129.174 129.174 0.00231 0.00486 0.46420 131.144 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.05337 0.04818 0.04286 0.47332 0.00000 0.00000 0.12400 0.12400 0.00000 0.02906 0.02906 — 119.460 119.460 0.00331 0.00519 0.01201 121.102 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.01011 0.00911 0.00729 0.08772 0.00000 0.00000 0.02375 0.02375 0.00000 0.00557 0.00557 — 23.1876 23.1876 0.00057 0.00100 0.03841 23.5370 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 20 / 100 Page 458 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Annual — — — — — — — — — — — — — — — — — —
Worker 0.00184 0.00166 0.00133 0.01601 0.00000 0.00000 0.00433 0.00433 0.00000 0.00102 0.00102 — 3.83898 3.83898 0.00009 0.00016 0.00636 3.89682 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.2. Site Preparation (2027)

3.2.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

3.63178 3.05170 27.9724 28.2794 0.04891 1.17173 — 1.17173 1.07799 — 1.07799 — 5,297.82 5,297.82 0.21490 0.04298 — 5,316.00 Dust
From
Material
Moveme
nt
— — — — — — 7.66623 7.66623 — 3.93995 3.93995 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Average
Daily
— — — — — — — — — — — — — — — — — —
21 / 100 Page 459 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Off-Road Eq
uipment

0.39800 0.33443 3.06547 3.09911 0.00536 0.12841 — 0.12841 0.11814 — 0.11814 — 580.583 580.583 0.02355 0.00471 — 582.575 Dust
From
Material
Moveme
nt
— — — — — — 0.84014 0.84014 — 0.43178 0.43178 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.07264 0.06103 0.55945 0.56559 0.00098 0.02343 — 0.02343 0.02156 — 0.02156 — 96.1221 96.1221 0.00390 0.00078 — 96.4520 Dust
From
Material
Moveme
nt
— — — — — — 0.15332 0.15332 — 0.07880 0.07880 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.2.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.06458 0.05891 0.03827 0.61587 0.00000 0.00000 0.14466 0.14466 0.00000 0.03391 0.03391 — 150.702 150.702 0.00270 0.00567 0.54157 153.002 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 22 / 100 Page 460 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.00674 0.00608 0.00486 0.05848 0.00000 0.00000 0.01583 0.01583 0.00000 0.00371 0.00371 — 15.4584 15.4584 0.00038 0.00066 0.02561 15.6914 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.00123 0.00111 0.00089 0.01067 0.00000 0.00000 0.00289 0.00289 0.00000 0.00068 0.00068 — 2.55932 2.55932 0.00006 0.00011 0.00424 2.59788 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.3. Grading (2027)

3.3.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

3.50534 2.94546 25.5801 27.2816 0.06093 1.04307 — 1.04307 0.95962 — 0.95962 — 6,598.08 6,598.08 0.26765 0.05353 — 6,620.72 23 / 100 Page 461 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Dust
From
Material
Moveme
nt
— — — — — — 2.38360 2.38360 — 1.29531 1.29531 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

3.50534 2.94546 25.5801 27.2816 0.06093 1.04307 — 1.04307 0.95962 — 0.95962 — 6,598.08 6,598.08 0.26765 0.05353 — 6,620.72 Dust
From
Material
Moveme
nt
— — — — — — 2.38360 2.38360 — 1.29531 1.29531 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

1.05640 0.88767 7.70907 8.22187 0.01836 0.31435 — 0.31435 0.28920 — 0.28920 — 1,988.46 1,988.46 0.08066 0.01613 — 1,995.29 Dust
From
Material
Moveme
nt
— — — — — — 0.71834 0.71834 — 0.39037 0.39037 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 24 / 100 Page 462 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.19279 0.16200 1.40691 1.50049 0.00335 0.05737 — 0.05737 0.05278 — 0.05278 — 329.213 329.213 0.01335 0.00267 — 330.342 Dust
From
Material
Moveme
nt
— — — — — — 0.13110 0.13110 — 0.07124 0.07124 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.3.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.07381 0.06733 0.04374 0.70385 0.00000 0.00000 0.16533 0.16533 0.00000 0.03875 0.03875 — 172.231 172.231 0.00309 0.00648 0.61894 174.859 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.11351 0.04050 2.11104 0.74608 0.01198 0.03422 0.47968 0.51390 0.02282 0.13133 0.15414 — 1,748.31 1,748.31 0.07073 0.28063 3.47474 1,837.19 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.07117 0.06424 0.05714 0.63110 0.00000 0.00000 0.16533 0.16533 0.00000 0.03875 0.03875 — 159.280 159.280 0.00441 0.00692 0.01601 161.470 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.11066 0.03822 2.23481 0.75463 0.01198 0.03422 0.47968 0.51390 0.02282 0.13133 0.15414 — 1,749.18 1,749.18 0.07073 0.28063 0.09038 1,834.67 25 / 100 Page 463 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.02118 0.01910 0.01527 0.18379 0.00000 0.00000 0.04976 0.04976 0.00000 0.01166 0.01166 — 48.5836 48.5836 0.00120 0.00209 0.08048 49.3157 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.03386 0.01203 0.65958 0.22605 0.00361 0.01031 0.14441 0.15472 0.00688 0.03954 0.04642 — 526.997 526.997 0.02132 0.08457 0.45280 553.186 Annual — — — — — — — — — — — — — — — — — —
Worker 0.00387 0.00348 0.00279 0.03354 0.00000 0.00000 0.00908 0.00908 0.00000 0.00213 0.00213 — 8.04357 8.04357 0.00020 0.00035 0.01332 8.16477 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00618 0.00220 0.12037 0.04125 0.00066 0.00188 0.02635 0.02824 0.00125 0.00722 0.00847 — 87.2504 87.2504 0.00353 0.01400 0.07497 91.5863

3.4. Building Construction (2027)

3.4.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

1.27596 1.06786 10.1129 13.7101 0.02476 0.34167 — 0.34167 0.31433 — 0.31433 — 2,544.69 2,544.69 0.10322 0.02064 — 2,553.42 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 26 / 100 Page 464 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.13484 0.11285 1.06868 1.44882 0.00262 0.03611 — 0.03611 0.03322 — 0.03322 — 268.910 268.910 0.01091 0.00218 — 269.833 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.02461 0.02059 0.19503 0.26441 0.00048 0.00659 — 0.00659 0.00606 — 0.00606 — 44.5211 44.5211 0.00181 0.00036 — 44.6739 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.4.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.01139 0.01028 0.00914 0.10098 0.00000 0.00000 0.02645 0.02645 0.00000 0.00620 0.00620 — 25.4849 25.4849 0.00071 0.00111 0.00256 25.8351 Vendor 0.00271 0.00129 0.05496 0.02128 0.00030 0.00061 0.01155 0.01216 0.00061 0.00319 0.00380 — 42.2448 42.2448 0.00138 0.00636 0.00237 44.1768 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
27 / 100 Page 465 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Worker 0.00119 0.00107 0.00086 0.01031 0.00000 0.00000 0.00279 0.00279 0.00000 0.00065 0.00065 — 2.72573 2.72573 0.00007 0.00012 0.00452 2.76680 Vendor 0.00029 0.00014 0.00570 0.00221 0.00003 0.00006 0.00122 0.00128 0.00006 0.00034 0.00040 — 4.46221 4.46221 0.00015 0.00067 0.00417 4.67030 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.00022 0.00020 0.00016 0.00188 0.00000 0.00000 0.00051 0.00051 0.00000 0.00012 0.00012 — 0.45128 0.45128 0.00001 0.00002 0.00075 0.45808 Vendor 0.00005 0.00003 0.00104 0.00040 0.00001 0.00001 0.00022 0.00023 0.00001 0.00006 0.00007 — 0.73877 0.73877 0.00002 0.00011 0.00069 0.77322 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.5. Building Construction (2028)

3.5.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

1.23004 1.02943 9.64691 13.7087 0.02476 0.30528 — 0.30528 0.28086 — 0.28086 — 2,545.07 2,545.07 0.10324 0.02065 — 2,553.80 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
28 / 100 Page 466 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Off-Road Eq
uipment

1.23004 1.02943 9.64691 13.7087 0.02476 0.30528 — 0.30528 0.28086 — 0.28086 — 2,545.07 2,545.07 0.10324 0.02065 — 2,553.80 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.88101 0.73732 6.90953 9.81877 0.01774 0.21866 — 0.21866 0.20116 — 0.20116 — 1,822.88 1,822.88 0.07394 0.01479 — 1,829.14 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.16078 0.13456 1.26099 1.79193 0.00324 0.03990 — 0.03990 0.03671 — 0.03671 — 301.799 301.799 0.01224 0.00245 — 302.835 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.5.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.01153 0.01049 0.00603 0.10639 0.00000 0.00000 0.02645 0.02645 0.00000 0.00620 0.00620 — 27.0460 27.0460 0.00049 0.00104 0.09006 27.4574 Vendor 0.00278 0.00133 0.04966 0.01995 0.00030 0.00061 0.01155 0.01216 0.00061 0.00319 0.00380 — 41.2081 41.2081 0.00138 0.00602 0.08117 43.1177 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 29 / 100 Page 467 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.01103 0.00993 0.00825 0.09480 0.00000 0.00000 0.02645 0.02645 0.00000 0.00620 0.00620 — 25.0145 25.0145 0.00071 0.00111 0.00234 25.3645 Vendor 0.00271 0.00129 0.05258 0.02060 0.00030 0.00061 0.01155 0.01216 0.00061 0.00319 0.00380 — 41.2416 41.2416 0.00138 0.00606 0.00210 43.0829 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.00780 0.00706 0.00511 0.06572 0.00000 0.00000 0.01892 0.01892 0.00000 0.00443 0.00443 — 18.1327 18.1327 0.00040 0.00079 0.02781 18.4070 Vendor 0.00197 0.00095 0.03692 0.01449 0.00022 0.00043 0.00826 0.00870 0.00043 0.00228 0.00272 — 29.5249 29.5249 0.00099 0.00434 0.02506 30.8673 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.00142 0.00129 0.00093 0.01199 0.00000 0.00000 0.00345 0.00345 0.00000 0.00081 0.00081 — 3.00207 3.00207 0.00007 0.00013 0.00460 3.04749 Vendor 0.00036 0.00017 0.00674 0.00264 0.00004 0.00008 0.00151 0.00159 0.00008 0.00042 0.00050 — 4.88819 4.88819 0.00016 0.00072 0.00415 5.11044 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.6. Building Construction (2029)

3.6.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
30 / 100 Page 468 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Off-Road Eq
uipment

1.19846 1.00303 9.30184 13.6735 0.02476 0.28055 — 0.28055 0.25811 — 0.25811 — 2,544.44 2,544.44 0.10321 0.02064 — 2,553.17 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

1.19846 1.00303 9.30184 13.6735 0.02476 0.28055 — 0.28055 0.25811 — 0.25811 — 2,544.44 2,544.44 0.10321 0.02064 — 2,553.17 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.85604 0.71645 6.64417 9.76678 0.01768 0.20039 — 0.20039 0.18436 — 0.18436 — 1,817.46 1,817.46 0.07372 0.01474 — 1,823.69 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.15623 0.13075 1.21256 1.78244 0.00323 0.03657 — 0.03657 0.03365 — 0.03365 — 300.901 300.901 0.01221 0.00244 — 301.933 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.6.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) 31 / 100 Page 469 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.01096 0.00993 0.00596 0.09942 0.00000 0.00000 0.02645 0.02645 0.00000 0.00620 0.00620 — 26.5568 26.5568 0.00049 0.00021 0.08121 26.7134 Vendor 0.00275 0.00133 0.04755 0.01930 0.00030 0.00061 0.01155 0.01216 0.00061 0.00319 0.00380 — 40.0956 40.0956 0.00138 0.00602 0.07162 41.9956 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.01061 0.00950 0.00728 0.08960 0.00000 0.00000 0.02645 0.02645 0.00000 0.00620 0.00620 — 24.5644 24.5644 0.00063 0.00111 0.00210 24.9124 Vendor 0.00271 0.00129 0.05020 0.01995 0.00030 0.00061 0.01155 0.01216 0.00061 0.00319 0.00380 — 40.1300 40.1300 0.00138 0.00606 0.00185 41.9710 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.00748 0.00669 0.00500 0.06148 0.00000 0.00000 0.01887 0.01887 0.00000 0.00442 0.00442 — 17.7580 17.7580 0.00040 0.00074 0.02504 18.0139 Vendor 0.00196 0.00092 0.03509 0.01397 0.00022 0.00043 0.00824 0.00867 0.00043 0.00228 0.00271 — 28.6499 28.6499 0.00099 0.00430 0.02204 29.9779 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.00136 0.00122 0.00091 0.01122 0.00000 0.00000 0.00344 0.00344 0.00000 0.00081 0.00081 — 2.94004 2.94004 0.00007 0.00012 0.00415 2.98240 Vendor 0.00036 0.00017 0.00640 0.00255 0.00004 0.00008 0.00150 0.00158 0.00008 0.00042 0.00049 — 4.74331 4.74331 0.00016 0.00071 0.00365 4.96319 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.7. Building Construction (2030)
32 / 100 Page 470 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

3.7.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

1.16835 0.97784 9.11126 13.6564 0.02476 0.26487 — 0.26487 0.24368 — 0.24368 — 2,544.44 2,544.44 0.10321 0.02064 — 2,553.17 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

1.16835 0.97784 9.11126 13.6564 0.02476 0.26487 — 0.26487 0.24368 — 0.24368 — 2,544.44 2,544.44 0.10321 0.02064 — 2,553.17 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.83454 0.69846 6.50804 9.75459 0.01769 0.18919 — 0.18919 0.17406 — 0.17406 — 1,817.46 1,817.46 0.07372 0.01474 — 1,823.69 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.15230 0.12747 1.18772 1.78021 0.00323 0.03453 — 0.03453 0.03177 — 0.03177 — 300.901 300.901 0.01221 0.00244 — 301.933 33 / 100 Page 471 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.7.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.00978 0.00957 0.00507 0.09416 0.00000 0.00000 0.02645 0.02645 0.00000 0.00620 0.00620 — 26.0920 26.0920 0.00042 0.00021 0.07283 26.2384 Vendor 0.00244 0.00103 0.04548 0.01870 0.00030 0.00061 0.01155 0.01216 0.00030 0.00319 0.00349 — 38.8851 38.8851 0.00138 0.00572 0.06250 40.6856 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.00943 0.00915 0.00714 0.08446 0.00000 0.00000 0.02645 0.02645 0.00000 0.00620 0.00620 — 24.1354 24.1354 0.00056 0.00111 0.00189 24.4815 Vendor 0.00241 0.00095 0.04817 0.01927 0.00030 0.00061 0.01155 0.01216 0.00030 0.00319 0.00349 — 38.9206 38.9206 0.00138 0.00572 0.00163 40.6602 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.00664 0.00649 0.00436 0.05807 0.00000 0.00000 0.01887 0.01887 0.00000 0.00442 0.00442 — 17.4479 17.4479 0.00035 0.00074 0.02243 17.6999 Vendor 0.00172 0.00071 0.03358 0.01351 0.00022 0.00043 0.00824 0.00867 0.00022 0.00228 0.00249 — 27.7857 27.7857 0.00099 0.00408 0.01935 29.0465 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.00121 0.00118 0.00080 0.01060 0.00000 0.00000 0.00344 0.00344 0.00000 0.00081 0.00081 — 2.88870 2.88870 0.00006 0.00012 0.00371 2.93042 34 / 100 Page 472 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Vendor 0.00031 0.00013 0.00613 0.00247 0.00004 0.00008 0.00150 0.00158 0.00004 0.00042 0.00046 — 4.60024 4.60024 0.00016 0.00068 0.00320 4.80898 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.8. Building Construction (2031)

3.8.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

1.14178 0.95559 8.83650 13.6167 0.02476 0.24776 — 0.24776 0.22794 — 0.22794 — 2,544.44 2,544.44 0.10321 0.02064 — 2,553.17 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

1.14178 0.95559 8.83650 13.6167 0.02476 0.24776 — 0.24776 0.22794 — 0.22794 — 2,544.44 2,544.44 0.10321 0.02064 — 2,553.17 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
35 / 100 Page 473 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Off-Road Eq
uipment

0.81556 0.68256 6.31179 9.72621 0.01769 0.17697 — 0.17697 0.16281 — 0.16281 — 1,817.46 1,817.46 0.07372 0.01474 — 1,823.69 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.14884 0.12457 1.15190 1.77503 0.00323 0.03230 — 0.03230 0.02971 — 0.02971 — 300.901 300.901 0.01221 0.00244 — 301.933 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.8.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.00936 0.00922 0.00499 0.08973 0.00000 0.00000 0.02645 0.02645 0.00000 0.00620 0.00620 — 25.6052 25.6052 0.00042 0.00021 0.06480 25.7437 Vendor 0.00244 0.00103 0.04371 0.01836 0.00030 0.00030 0.01155 0.01185 0.00030 0.00319 0.00349 — 37.6168 37.6168 0.00138 0.00541 0.05425 39.3185 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.00908 0.00880 0.00624 0.07932 0.00000 0.00000 0.02645 0.02645 0.00000 0.00620 0.00620 — 23.6869 23.6869 0.00056 0.00111 0.00168 24.0328 Vendor 0.00233 0.00095 0.04609 0.01893 0.00030 0.00030 0.01155 0.01185 0.00030 0.00319 0.00349 — 37.6527 37.6527 0.00134 0.00541 0.00141 39.3007 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 36 / 100 Page 474 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.00628 0.00613 0.00431 0.05465 0.00000 0.00000 0.01887 0.01887 0.00000 0.00442 0.00442 — 17.1239 17.1239 0.00035 0.00015 0.01998 17.1978 Vendor 0.00172 0.00071 0.03232 0.01327 0.00022 0.00022 0.00824 0.00846 0.00022 0.00228 0.00249 — 26.8797 26.8797 0.00099 0.00387 0.01677 28.0733 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.00115 0.00112 0.00079 0.00997 0.00000 0.00000 0.00344 0.00344 0.00000 0.00081 0.00081 — 2.83506 2.83506 0.00006 0.00003 0.00331 2.84729 Vendor 0.00031 0.00013 0.00590 0.00242 0.00004 0.00004 0.00150 0.00154 0.00004 0.00042 0.00046 — 4.45025 4.45025 0.00016 0.00064 0.00278 4.64786 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.9. Building Construction (2032)

3.9.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

1.11367 0.93203 8.58827 13.5578 0.02476 0.22838 — 0.22838 0.21011 — 0.21011 — 2,544.44 2,544.44 0.10321 0.02064 — 2,553.17 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 37 / 100 Page 475 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.08718 0.07296 0.67227 1.06128 0.00194 0.01788 — 0.01788 0.01645 — 0.01645 — 199.173 199.173 0.00808 0.00162 — 199.857 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.01591 0.01331 0.12269 0.19368 0.00035 0.00326 — 0.00326 0.00300 — 0.00300 — 32.9754 32.9754 0.00134 0.00027 — 33.0886 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.9.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.00866 0.00837 0.00617 0.07530 0.00000 0.00000 0.02645 0.02645 0.00000 0.00620 0.00620 — 23.3153 23.3153 0.00056 0.00104 0.00149 23.6400 Vendor 0.00233 0.00095 0.04432 0.01829 0.00030 0.00030 0.01155 0.01185 0.00030 0.00319 0.00349 — 36.4040 36.4040 0.00104 0.00541 0.00121 38.0443 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
38 / 100 Page 476 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Worker 0.00066 0.00064 0.00040 0.00570 0.00000 0.00000 0.00207 0.00207 0.00000 0.00048 0.00048 — 1.84716 1.84716 0.00004 0.00002 0.00193 1.85500 Vendor 0.00019 0.00008 0.00341 0.00141 0.00002 0.00002 0.00090 0.00093 0.00002 0.00025 0.00027 — 2.84796 2.84796 0.00008 0.00042 0.00158 2.97783 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.00012 0.00012 0.00007 0.00104 0.00000 0.00000 0.00038 0.00038 0.00000 0.00009 0.00009 — 0.30582 0.30582 0.00001 < 0.0000 05 0.00032 0.30712
Vendor 0.00003 0.00001 0.00062 0.00026 < 0.0000
05 < 0.0000
05 0.00016 0.00017 < 0.0000
05 0.00005 0.00005 — 0.47151 0.47151 0.00001 0.00007 0.00026 0.49301 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.10. Paving (2032)

3.10.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.72492 0.60914 5.99778 9.85925 0.01395 0.19870 — 0.19870 0.18280 — 0.18280 — 1,510.63 1,510.63 0.06128 0.01226 — 1,515.81 Paving 0.04541 0.04541 — — — — — — — — — — — — — — — —
Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 39 / 100 Page 477 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.72492 0.60914 5.99778 9.85925 0.01395 0.19870 — 0.19870 0.18280 — 0.18280 — 1,510.63 1,510.63 0.06128 0.01226 — 1,515.81 Paving 0.04541 0.04541 — — — — — — — — — — — — — — — —
Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.14896 0.12517 1.23242 2.02587 0.00287 0.04083 — 0.04083 0.03756 — 0.03756 — 310.403 310.403 0.01259 0.00252 — 311.468 Paving 0.00933 0.00933 — — — — — — — — — — — — — — — —
Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.02718 0.02284 0.22492 0.36972 0.00052 0.00745 — 0.00745 0.00686 — 0.00686 — 51.3908 51.3908 0.00208 0.00042 — 51.5672 Paving 0.00170 0.00170 — — — — — — — — — — — — — — — —
Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.10.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) 40 / 100 Page 478 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.04190 0.04124 0.02308 0.39663 0.00000 0.00000 0.12400 0.12400 0.00000 0.02906 0.02906 — 118.140 118.140 0.00198 0.00099 0.26834 118.754 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.04058 0.03925 0.02894 0.35295 0.00000 0.00000 0.12400 0.12400 0.00000 0.02906 0.02906 — 109.291 109.291 0.00265 0.00486 0.00697 110.812 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.00813 0.00793 0.00495 0.07008 0.00000 0.00000 0.02544 0.02544 0.00000 0.00596 0.00596 — 22.7288 22.7288 0.00048 0.00020 0.02376 22.8252 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.00148 0.00145 0.00090 0.01279 0.00000 0.00000 0.00464 0.00464 0.00000 0.00109 0.00109 — 3.76301 3.76301 0.00008 0.00003 0.00393 3.77897 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.11. Architectural Coating (2032)
41 / 100 Page 479 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

3.11.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.11264 0.09309 0.77005 1.10069 0.00173 0.00813 — 0.00813 0.00748 — 0.00748 — 133.504 133.504 0.00542 0.00108 — 133.962 Architect
ural
Coatings

1.39090 1.39090 — — — — — — — — — — — — — — — —
Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.02314 0.01913 0.15823 0.22617 0.00035 0.00167 — 0.00167 0.00154 — 0.00154 — 27.4323 27.4323 0.00111 0.00022 — 27.5264 Architect
ural
Coatings

0.28580 0.28580 — — — — — — — — — — — — — — — —
Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.00422 0.00349 0.02888 0.04128 0.00006 0.00030 — 0.00030 0.00028 — 0.00028 — 4.54172 4.54172 0.00018 0.00004 — 4.55731 42 / 100 Page 480 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Architect
ural
Coatings

0.05216 0.05216 — — — — — — — — — — — — — — — —
Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.11.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.00179 0.00176 0.00098 0.01692 0.00000 0.00000 0.00529 0.00529 0.00000 0.00124 0.00124 — 5.04065 5.04065 0.00008 0.00004 0.01145 5.06683 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.00035 0.00034 0.00021 0.00299 0.00000 0.00000 0.00109 0.00109 0.00000 0.00025 0.00025 — 0.96976 0.96976 0.00002 0.00001 0.00101 0.97387 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.00006 0.00006 0.00004 0.00055 0.00000 0.00000 0.00020 0.00020 0.00000 0.00005 0.00005 — 0.16056 0.16056 < 0.0000 05 < 0.0000
05 0.00017 0.16124
43 / 100 Page 481 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.12. Linear, Grubbing & Land Clearing (2027)

3.12.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.50946 0.42808 3.80861 4.46942 0.00584 0.18470 — 0.18470 0.16993 — 0.16993 — 632.486 632.486 0.02566 0.00513 — 634.656 Dust
From
Material
Moveme
nt
— — — — — — 0.00373 0.00373 — 0.00040 0.00040 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.50946 0.42808 3.80861 4.46942 0.00584 0.18470 — 0.18470 0.16993 — 0.16993 — 632.486 632.486 0.02566 0.00513 — 634.656 44 / 100 Page 482 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Dust
From
Material
Moveme
nt
— — — — — — 0.00373 0.00373 — 0.00040 0.00040 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.20099 0.16889 1.50257 1.76328 0.00230 0.07287 — 0.07287 0.06704 — 0.06704 — 249.529 249.529 0.01012 0.00202 — 250.385 Dust
From
Material
Moveme
nt
— — — — — — 0.00147 0.00147 — 0.00016 0.00016 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.03668 0.03082 0.27422 0.32180 0.00042 0.01330 — 0.01330 0.01223 — 0.01223 — 41.3123 41.3123 0.00168 0.00034 — 41.4541 Dust
From
Material
Moveme
nt
— — — — — — 0.00027 0.00027 — 0.00003 0.00003 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.12.2. Offsite - Unmitigated
45 / 100 Page 483 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.05536 0.05050 0.03280 0.52789 0.00000 0.00000 0.12400 0.12400 0.00000 0.02906 0.02906 — 129.174 129.174 0.00231 0.00486 0.46420 131.144 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.05337 0.04818 0.04286 0.47332 0.00000 0.00000 0.12400 0.12400 0.00000 0.02906 0.02906 — 119.460 119.460 0.00331 0.00519 0.01201 121.102 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.02080 0.01875 0.01499 0.18045 0.00000 0.00000 0.04885 0.04885 0.00000 0.01145 0.01145 — 47.7003 47.7003 0.00117 0.00205 0.07902 48.4190 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.00380 0.00342 0.00274 0.03293 0.00000 0.00000 0.00892 0.00892 0.00000 0.00209 0.00209 — 7.89732 7.89732 0.00019 0.00034 0.01308 8.01632 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.13. Linear, Grading & Excavation (2027)
46 / 100 Page 484 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

3.13.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

4.05923 3.41088 28.7183 37.9540 0.07285 1.20350 — 1.20350 1.10722 — 1.10722 — 7,888.96 7,888.96 0.32001 0.06400 — 7,916.03 Dust
From
Material
Moveme
nt
— — — — — — 0.00249 0.00249 — 0.00027 0.00027 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

4.05923 3.41088 28.7183 37.9540 0.07285 1.20350 — 1.20350 1.10722 — 1.10722 — 7,888.96 7,888.96 0.32001 0.06400 — 7,916.03 Dust
From
Material
Moveme
nt
— — — — — — 0.00249 0.00249 — 0.00027 0.00027 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
47 / 100 Page 485 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Off-Road Eq
uipment

1.29482 1.08801 9.16065 12.1066 0.02324 0.38389 — 0.38389 0.35318 — 0.35318 — 2,516.44 2,516.44 0.10208 0.02042 — 2,525.08 Dust
From
Material
Moveme
nt
— — — — — — 0.00079 0.00079 — 0.00009 0.00009 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.23631 0.19856 1.67182 2.20946 0.00424 0.07006 — 0.07006 0.06446 — 0.06446 — 416.625 416.625 0.01690 0.00338 — 418.055 Dust
From
Material
Moveme
nt
— — — — — — 0.00014 0.00014 — 0.00002 0.00002 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.13.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.17530 0.15991 0.10388 1.67164 0.00000 0.00000 0.39266 0.39266 0.00000 0.09204 0.09204 — 409.049 409.049 0.00733 0.01539 1.46998 415.290 Vendor 0.00172 0.00083 0.03177 0.01256 0.00019 0.00037 0.00705 0.00742 0.00037 0.00195 0.00232 — 25.7547 25.7547 0.00084 0.00388 0.05588 26.9879 48 / 100 Page 486 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.16902 0.15258 0.13572 1.49885 0.00000 0.00000 0.39266 0.39266 0.00000 0.09204 0.09204 — 378.291 378.291 0.01047 0.01644 0.03802 383.490 Vendor 0.00165 0.00079 0.03353 0.01298 0.00019 0.00037 0.00705 0.00742 0.00037 0.00195 0.00232 — 25.7747 25.7747 0.00084 0.00388 0.00145 26.9535 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.05325 0.04800 0.03838 0.46201 0.00000 0.00000 0.12507 0.12507 0.00000 0.02931 0.02931 — 122.129 122.129 0.00301 0.00524 0.20231 123.970 Vendor 0.00054 0.00026 0.01049 0.00406 0.00006 0.00012 0.00224 0.00236 0.00012 0.00062 0.00074 — 8.21798 8.21798 0.00027 0.00124 0.00769 8.60122 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.00972 0.00876 0.00700 0.08432 0.00000 0.00000 0.02283 0.02283 0.00000 0.00535 0.00535 — 20.2199 20.2199 0.00050 0.00087 0.03350 20.5246 Vendor 0.00010 0.00005 0.00192 0.00074 0.00001 0.00002 0.00041 0.00043 0.00002 0.00011 0.00013 — 1.36058 1.36058 0.00004 0.00020 0.00127 1.42403 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.14. Linear, Grading & Excavation (2028)

3.14.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) 49 / 100 Page 487 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

3.90054 3.27754 26.9626 37.8353 0.07285 1.09238 — 1.09238 1.00499 — 1.00499 — 7,888.60 7,888.60 0.32000 0.06400 — 7,915.67 Dust
From
Material
Moveme
nt
— — — — — — 0.00249 0.00249 — 0.00027 0.00027 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

3.90054 3.27754 26.9626 37.8353 0.07285 1.09238 — 1.09238 1.00499 — 1.00499 — 7,888.60 7,888.60 0.32000 0.06400 — 7,915.67 Dust
From
Material
Moveme
nt
— — — — — — 0.00249 0.00249 — 0.00027 0.00027 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

2.79373 2.34751 19.3118 27.0993 0.05218 0.78241 — 0.78241 0.71982 — 0.71982 — 5,650.15 5,650.15 0.22919 0.04584 — 5,669.54 50 / 100 Page 488 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Dust
From
Material
Moveme
nt
— — — — — — 0.00178 0.00178 — 0.00019 0.00019 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.50986 0.42842 3.52440 4.94562 0.00952 0.14279 — 0.14279 0.13137 — 0.13137 — 935.447 935.447 0.03795 0.00759 — 938.657 Dust
From
Material
Moveme
nt
— — — — — — 0.00033 0.00033 — 0.00004 0.00004 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.14.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.17111 0.15572 0.08954 1.57928 0.00000 0.00000 0.39266 0.39266 0.00000 0.09204 0.09204 — 401.463 401.463 0.00733 0.01539 1.33682 407.571 Vendor 0.00170 0.00081 0.03030 0.01217 0.00019 0.00037 0.00705 0.00742 0.00037 0.00195 0.00232 — 25.1422 25.1422 0.00084 0.00367 0.04952 26.3073 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 51 / 100 Page 489 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.16378 0.14734 0.12242 1.40722 0.00000 0.00000 0.39266 0.39266 0.00000 0.09204 0.09204 — 371.309 371.309 0.01047 0.01644 0.03469 376.505 Vendor 0.00165 0.00079 0.03208 0.01257 0.00019 0.00037 0.00705 0.00742 0.00037 0.00195 0.00232 — 25.1627 25.1627 0.00084 0.00369 0.00128 26.2861 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.11581 0.10478 0.07590 0.97551 0.00000 0.00000 0.28084 0.28084 0.00000 0.06582 0.06582 — 269.157 269.157 0.00600 0.01178 0.41286 273.229 Vendor 0.00120 0.00058 0.02252 0.00884 0.00013 0.00027 0.00504 0.00531 0.00027 0.00139 0.00166 — 18.0140 18.0140 0.00060 0.00265 0.01529 18.8330 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.02113 0.01912 0.01385 0.17803 0.00000 0.00000 0.05125 0.05125 0.00000 0.01201 0.01201 — 44.5620 44.5620 0.00099 0.00195 0.06835 45.2362 Vendor 0.00022 0.00011 0.00411 0.00161 0.00002 0.00005 0.00092 0.00097 0.00005 0.00025 0.00030 — 2.98242 2.98242 0.00010 0.00044 0.00253 3.11802 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.15. Linear, Grading & Excavation (2029)

3.15.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
52 / 100 Page 490 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Off-Road Eq
uipment

3.76970 3.16760 25.3451 37.6660 0.07285 0.99732 — 0.99732 0.91753 — 0.91753 — 7,887.67 7,887.67 0.31996 0.06399 — 7,914.74 Dust
From
Material
Moveme
nt
— — — — — — 0.00249 0.00249 — 0.00027 0.00027 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

3.76970 3.16760 25.3451 37.6660 0.07285 0.99732 — 0.99732 0.91753 — 0.91753 — 7,887.67 7,887.67 0.31996 0.06399 — 7,914.74 Dust
From
Material
Moveme
nt
— — — — — — 0.00249 0.00249 — 0.00027 0.00027 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

2.69265 2.26257 18.1036 26.9043 0.05203 0.71237 — 0.71237 0.65538 — 0.65538 — 5,634.05 5,634.05 0.22854 0.04571 — 5,653.39 Dust
From
Material
Moveme
nt
— — — — — — 0.00178 0.00178 — 0.00019 0.00019 — — — — — — — 53 / 100 Page 491 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.49141 0.41292 3.30391 4.91003 0.00950 0.13001 — 0.13001 0.11961 — 0.11961 — 932.782 932.782 0.03784 0.00757 — 935.983 Dust
From
Material
Moveme
nt
— — — — — — 0.00032 0.00032 — 0.00004 0.00004 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.15.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.16273 0.14734 0.08849 1.47571 0.00000 0.00000 0.39266 0.39266 0.00000 0.09204 0.09204 — 394.202 394.202 0.00733 0.00314 1.20542 396.527 Vendor 0.00168 0.00081 0.02901 0.01178 0.00019 0.00037 0.00705 0.00742 0.00037 0.00195 0.00232 — 24.4634 24.4634 0.00084 0.00367 0.04370 25.6227 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.15750 0.14106 0.10807 1.32994 0.00000 0.00000 0.39266 0.39266 0.00000 0.09204 0.09204 — 364.627 364.627 0.00942 0.01644 0.03119 369.793 Vendor 0.00165 0.00079 0.03063 0.01217 0.00019 0.00037 0.00705 0.00742 0.00037 0.00195 0.00232 — 24.4844 24.4844 0.00084 0.00369 0.00113 25.6077 54 / 100 Page 492 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.11100 0.09926 0.07420 0.91263 0.00000 0.00000 0.28007 0.28007 0.00000 0.06564 0.06564 — 263.596 263.596 0.00598 0.01100 0.37169 267.394 Vendor 0.00120 0.00056 0.02141 0.00852 0.00013 0.00026 0.00503 0.00529 0.00026 0.00139 0.00165 — 17.4801 17.4801 0.00060 0.00262 0.01345 18.2904 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.02026 0.01811 0.01354 0.16656 0.00000 0.00000 0.05111 0.05111 0.00000 0.01198 0.01198 — 43.6413 43.6413 0.00099 0.00182 0.06154 44.2701 Vendor 0.00022 0.00010 0.00391 0.00156 0.00002 0.00005 0.00092 0.00097 0.00005 0.00025 0.00030 — 2.89403 2.89403 0.00010 0.00043 0.00223 3.02818 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.16. Linear, Grading & Excavation (2030)

3.16.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

3.63411 3.05366 24.1569 37.4870 0.07285 0.94303 — 0.94303 0.86758 — 0.86758 — 7,887.67 7,887.67 0.31996 0.06399 — 7,914.74 55 / 100 Page 493 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Dust
From
Material
Moveme
nt
— — — — — — 0.00249 0.00249 — 0.00027 0.00027 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.09956 0.08366 0.66183 1.02704 0.00200 0.02584 — 0.02584 0.02377 — 0.02377 — 216.101 216.101 0.00877 0.00175 — 216.842 Dust
From
Material
Moveme
nt
— — — — — — 0.00007 0.00007 — 0.00001 0.00001 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.01817 0.01527 0.12078 0.18744 0.00036 0.00472 — 0.00472 0.00434 — 0.00434 — 35.7779 35.7779 0.00145 0.00029 — 35.9007 Dust
From
Material
Moveme
nt
— — — — — — 0.00001 0.00001 — < 0.0000
05 < 0.0000
05 — — — — — — —
Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.16.2. Offsite - Unmitigated
56 / 100 Page 494 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.14001 0.13582 0.10598 1.25370 0.00000 0.00000 0.39266 0.39266 0.00000 0.09204 0.09204 — 358.260 358.260 0.00838 0.01644 0.02803 363.397 Vendor 0.00147 0.00058 0.02939 0.01176 0.00019 0.00037 0.00705 0.00742 0.00019 0.00195 0.00213 — 23.7466 23.7466 0.00084 0.00349 0.00099 24.8079 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.00378 0.00369 0.00248 0.03306 0.00000 0.00000 0.01074 0.01074 0.00000 0.00252 0.00252 — 9.93395 9.93395 0.00020 0.00042 0.01277 10.0774 Vendor 0.00004 0.00002 0.00079 0.00032 0.00001 0.00001 0.00019 0.00020 0.00001 0.00005 0.00006 — 0.65025 0.65025 0.00002 0.00010 0.00045 0.67975 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.00069 0.00067 0.00045 0.00603 0.00000 0.00000 0.00196 0.00196 0.00000 0.00046 0.00046 — 1.64468 1.64468 0.00003 0.00007 0.00211 1.66843 Vendor 0.00001 < 0.0000
05 0.00014 0.00006 < 0.0000
05 < 0.0000
05 0.00004 0.00004 < 0.0000
05 0.00001 0.00001 — 0.10766 0.10766 < 0.0000
05 0.00002 0.00007 0.11254
Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.17. Linear, Drainage, Utilities, & Sub-Grade (2030)

3.17.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) 57 / 100 Page 495 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

2.59313 2.17096 18.2672 25.7525 0.05387 0.60459 — 0.60459 0.55623 — 0.55623 — 5,556.19 5,556.19 0.22538 0.04508 — 5,575.26 Dust
From
Material
Moveme
nt
— — — — — — 0.00249 0.00249 — 0.00027 0.00027 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

2.59313 2.17096 18.2672 25.7525 0.05387 0.60459 — 0.60459 0.55623 — 0.55623 — 5,556.19 5,556.19 0.22538 0.04508 — 5,575.26 Dust
From
Material
Moveme
nt
— — — — — — 0.00249 0.00249 — 0.00027 0.00027 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

1.78119 1.49121 12.5475 17.6891 0.03700 0.41529 — 0.41529 0.38207 — 0.38207 — 3,816.49 3,816.49 0.15481 0.03096 — 3,829.58 58 / 100 Page 496 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Dust
From
Material
Moveme
nt
— — — — — — 0.00171 0.00171 — 0.00018 0.00018 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.32507 0.27215 2.28992 3.22826 0.00675 0.07579 — 0.07579 0.06973 — 0.06973 — 631.863 631.863 0.02563 0.00513 — 634.031 Dust
From
Material
Moveme
nt
— — — — — — 0.00031 0.00031 — 0.00003 0.00003 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.17.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.12996 0.12715 0.06727 1.25057 0.00000 0.00000 0.35133 0.35133 0.00000 0.08235 0.08235 — 346.534 346.534 0.00562 0.00281 0.96723 348.479 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 59 / 100 Page 497 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.12527 0.12152 0.09482 1.12173 0.00000 0.00000 0.35133 0.35133 0.00000 0.08235 0.08235 — 320.548 320.548 0.00750 0.01471 0.02508 325.145 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.08476 0.08283 0.05567 0.74161 0.00000 0.00000 0.24098 0.24098 0.00000 0.05648 0.05648 — 222.842 222.842 0.00451 0.00946 0.28643 226.060 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.01547 0.01512 0.01016 0.13534 0.00000 0.00000 0.04398 0.04398 0.00000 0.01031 0.01031 — 36.8940 36.8940 0.00075 0.00157 0.04742 37.4268 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.18. Linear, Drainage, Utilities, & Sub-Grade (2031)

3.18.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
60 / 100 Page 498 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Off-Road Eq
uipment

2.54109 2.12738 17.6137 25.6635 0.05387 0.58031 — 0.58031 0.53389 — 0.53389 — 5,556.19 5,556.19 0.22538 0.04508 — 5,575.26 Dust
From
Material
Moveme
nt
— — — — — — 0.00249 0.00249 — 0.00027 0.00027 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

2.54109 2.12738 17.6137 25.6635 0.05387 0.58031 — 0.58031 0.53389 — 0.53389 — 5,556.19 5,556.19 0.22538 0.04508 — 5,575.26 Dust
From
Material
Moveme
nt
— — — — — — 0.00249 0.00249 — 0.00027 0.00027 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

1.26309 1.05745 8.75514 12.7564 0.02678 0.28845 — 0.28845 0.26538 — 0.26538 — 2,761.79 2,761.79 0.11203 0.02241 — 2,771.26 Dust
From
Material
Moveme
nt
— — — — — — 0.00124 0.00124 — 0.00013 0.00013 — — — — — — — 61 / 100 Page 499 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.23051 0.19298 1.59781 2.32805 0.00489 0.05264 — 0.05264 0.04843 — 0.04843 — 457.245 457.245 0.01855 0.00371 — 458.814 Dust
From
Material
Moveme
nt
— — — — — — 0.00023 0.00023 — 0.00002 0.00002 — — — — — — — Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.18.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.12434 0.12246 0.06634 1.19173 0.00000 0.00000 0.35133 0.35133 0.00000 0.08235 0.08235 — 340.069 340.069 0.00562 0.00281 0.86063 341.908 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.12059 0.11684 0.08292 1.05352 0.00000 0.00000 0.35133 0.35133 0.00000 0.08235 0.08235 — 314.592 314.592 0.00750 0.01471 0.02226 319.185 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 62 / 100 Page 500 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.05808 0.05668 0.03982 0.50509 0.00000 0.00000 0.17438 0.17438 0.00000 0.04087 0.04087 — 158.265 158.265 0.00326 0.00140 0.18467 158.947 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.01060 0.01034 0.00727 0.09218 0.00000 0.00000 0.03183 0.03183 0.00000 0.00746 0.00746 — 26.2025 26.2025 0.00054 0.00023 0.03057 26.3155 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.19. Linear, Paving (2031)

3.19.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.81916 0.68832 6.58510 11.6657 0.01632 0.19181 — 0.19181 0.17646 — 0.17646 — 1,767.33 1,767.33 0.07169 0.01434 — 1,773.39 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 63 / 100 Page 501 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.81916 0.68832 6.58510 11.6657 0.01632 0.19181 — 0.19181 0.17646 — 0.17646 — 1,767.33 1,767.33 0.07169 0.01434 — 1,773.39 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.17794 0.14952 1.43042 2.53404 0.00355 0.04167 — 0.04167 0.03833 — 0.03833 — 383.901 383.901 0.01557 0.00311 — 385.219 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.03247 0.02729 0.26105 0.46246 0.00065 0.00760 — 0.00760 0.00700 — 0.00700 — 63.5592 63.5592 0.00258 0.00052 — 63.7773 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.19.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.07314 0.07204 0.03902 0.70101 0.00000 0.00000 0.20666 0.20666 0.00000 0.04844 0.04844 — 200.041 200.041 0.00331 0.00165 0.50625 201.122 64 / 100 Page 502 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.07093 0.06873 0.04878 0.61972 0.00000 0.00000 0.20666 0.20666 0.00000 0.04844 0.04844 — 185.054 185.054 0.00441 0.00865 0.01309 187.756 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.01493 0.01457 0.01024 0.12984 0.00000 0.00000 0.04483 0.04483 0.00000 0.01051 0.01051 — 40.6840 40.6840 0.00084 0.00036 0.04747 40.8595 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.00272 0.00266 0.00187 0.02370 0.00000 0.00000 0.00818 0.00818 0.00000 0.00192 0.00192 — 6.73571 6.73571 0.00014 0.00006 0.00786 6.76476 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000

3.20. Linear, Paving (2032)

3.20.1. Onsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) 65 / 100 Page 503 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.79649 0.66928 6.47007 11.6439 0.01632 0.18049 — 0.18049 0.16605 — 0.16605 — 1,767.33 1,767.33 0.07169 0.01434 — 1,773.39 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.79649 0.66928 6.47007 11.6439 0.01632 0.18049 — 0.18049 0.16605 — 0.16605 — 1,767.33 1,767.33 0.07169 0.01434 — 1,773.39 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.29927 0.25147 2.43103 4.37501 0.00613 0.06782 — 0.06782 0.06239 — 0.06239 — 664.045 664.045 0.02694 0.00539 — 666.324 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Off-Road Eq
uipment

0.05462 0.04589 0.44366 0.79844 0.00112 0.01238 — 0.01238 0.01139 — 0.01139 — 109.940 109.940 0.00446 0.00089 — 110.318 Onsite
truck

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 66 / 100 Page 504 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

3.20.2. Offsite - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Location TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.06983 0.06873 0.03847 0.66106 0.00000 0.00000 0.20666 0.20666 0.00000 0.04844 0.04844 — 196.901 196.901 0.00331 0.00165 0.44724 197.923 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Worker 0.06763 0.06542 0.04823 0.58825 0.00000 0.00000 0.20666 0.20666 0.00000 0.04844 0.04844 — 182.151 182.151 0.00441 0.00810 0.01162 184.687 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Average
Daily
— — — — — — — — — — — — — — — — — —
Worker 0.02479 0.02417 0.01508 0.21359 0.00000 0.00000 0.07754 0.07754 0.00000 0.01817 0.01817 — 69.2686 69.2686 0.00145 0.00062 0.07241 69.5624 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Annual — — — — — — — — — — — — — — — — — —
Worker 0.00452 0.00441 0.00275 0.03898 0.00000 0.00000 0.01415 0.01415 0.00000 0.00332 0.00332 — 11.4682 11.4682 0.00024 0.00010 0.01199 11.5169 Vendor 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 Hauling 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 67 / 100 Page 505 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

4. Operations Emissions Details

4.1. Mobile Emissions by Land Use

4.1.1. Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Land
Use
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
General
Office
Building

0.10491 0.09941 0.05703 0.53539 0.00137 0.00083 0.13335 0.13418 0.00078 0.03377 0.03455 — 139.648 139.648 0.00636 0.00662 0.24477 142.026 Unrefrig
erated
Wareho
use-No
Rail

0.00552 0.00253 0.08669 0.04350 0.00047 0.00089 0.01542 0.01632 0.00085 0.00415 0.00501 — 51.7078 51.7078 0.00275 0.00824 0.06056 54.2927 Total 0.11043 0.10194 0.14372 0.57889 0.00184 0.00172 0.14878 0.15050 0.00163 0.03792 0.03955 — 191.356 191.356 0.00911 0.01486 0.30533 196.318 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
General
Office
Building

0.10032 0.09432 0.06657 0.54691 0.00129 0.00083 0.13335 0.13418 0.00078 0.03377 0.03455 — 131.692 131.692 0.00754 0.00729 0.00635 134.060 Unrefrig
erated
Wareho
use-No
Rail

0.00522 0.00226 0.09183 0.04444 0.00047 0.00089 0.01542 0.01632 0.00086 0.00415 0.00501 — 51.8156 51.8156 0.00274 0.00826 0.00157 54.3463 68 / 100 Page 506 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Land
Use
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Total 0.10553 0.09658 0.15840 0.59135 0.00176 0.00173 0.14878 0.15050 0.00164 0.03792 0.03956 — 183.508 183.508 0.01027 0.01555 0.00792 188.406 Annual — — — — — — — — — — — — — — — — — —
General
Office
Building

0.01814 0.01709 0.01134 0.09322 0.00024 0.00015 0.02430 0.02445 0.00014 0.00615 0.00630 — 21.9935 21.9935 0.00115 0.00115 0.01750 22.3837 Unrefrig
erated
Wareho
use-No
Rail

0.00098 0.00044 0.01635 0.00801 0.00009 0.00016 0.00281 0.00297 0.00016 0.00076 0.00091 — 8.56831 8.56831 0.00045 0.00137 0.00433 8.99091 Total 0.01912 0.01753 0.02769 0.10124 0.00032 0.00031 0.02711 0.02743 0.00030 0.00691 0.00721 — 30.5618 30.5618 0.00160 0.00252 0.02183 31.3746

4.2. Energy

4.2.1. Electricity Emissions By Land Use - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Land
Use
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
General
Office
Building
— — — — — — — — — — — — 116.965 116.965 0.01892 0.00229 — 118.122 Unrefrig
erated
Wareho
use-No
Rail
— — — — — — — — — — — — 0.00000 0.00000 0.00000 0.00000 — 0.00000 69 / 100 Page 507 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Land
Use
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e undefine
d
— — — — — — — — — — — — 405.221 405.221 0.06556 0.00795 — 409.228 Total — — — — — — — — — — — — 522.187 522.187 0.08448 0.01024 — 527.350 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
General
Office
Building
— — — — — — — — — — — — 116.965 116.965 0.01892 0.00229 — 118.122 Unrefrig
erated
Wareho
use-No
Rail
— — — — — — — — — — — — 0.00000 0.00000 0.00000 0.00000 — 0.00000 undefine
d
— — — — — — — — — — — — 405.221 405.221 0.06556 0.00795 — 409.228 Total — — — — — — — — — — — — 522.187 522.187 0.08448 0.01024 — 527.350 Annual — — — — — — — — — — — — — — — — — —
General
Office
Building
— — — — — — — — — — — — 19.3649 19.3649 0.00313 0.00038 — 19.5564 Unrefrig
erated
Wareho
use-No
Rail
— — — — — — — — — — — — 0.00000 0.00000 0.00000 0.00000 — 0.00000 undefine
d
— — — — — — — — — — — — 67.0890 67.0890 0.01085 0.00132 — 67.7524 Total — — — — — — — — — — — — 86.4539 86.4539 0.01399 0.00170 — 87.3088 70 / 100 Page 508 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

4.2.3. Natural Gas Emissions By Land Use - Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Land
Use
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
General
Office
Building

0.00853 0.00426 0.07754 0.06514 0.00047 0.00589 — 0.00589 0.00589 — 0.00589 — 92.5210 92.5210 0.00819 0.00017 — 92.7776 Unrefrig
erated
Wareho
use-No
Rail

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 — 0.00000 — 0.00000 0.00000 0.00000 0.00000 — 0.00000 Total 0.00853 0.00426 0.07754 0.06514 0.00047 0.00589 — 0.00589 0.00589 — 0.00589 — 92.5210 92.5210 0.00819 0.00017 — 92.7776 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
General
Office
Building

0.00853 0.00426 0.07754 0.06514 0.00047 0.00589 — 0.00589 0.00589 — 0.00589 — 92.5210 92.5210 0.00819 0.00017 — 92.7776 Unrefrig
erated
Wareho
use-No
Rail

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 — 0.00000 — 0.00000 0.00000 0.00000 0.00000 — 0.00000 Total 0.00853 0.00426 0.07754 0.06514 0.00047 0.00589 — 0.00589 0.00589 — 0.00589 — 92.5210 92.5210 0.00819 0.00017 — 92.7776 Annual — — — — — — — — — — — — — — — — — —
General
Office
Building

0.00156 0.00078 0.01415 0.01189 0.00008 0.00108 — 0.00108 0.00108 — 0.00108 — 15.3179 15.3179 0.00136 0.00003 — 15.3604 71 / 100 Page 509 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Land
Use
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Unrefrig
erated
Wareho
use-No
Rail

0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 — 0.00000 — 0.00000 0.00000 0.00000 0.00000 — 0.00000 Total 0.00156 0.00078 0.01415 0.01189 0.00008 0.00108 — 0.00108 0.00108 — 0.00108 — 15.3179 15.3179 0.00136 0.00003 — 15.3604

4.3. Area Emissions by Source

4.3.1. Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Source TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Consum
er
Products

0.21400 0.21400 — — — — — — — — — — — — — — — —
Architect
ural
Coatings

0.02858 0.02858 — — — — — — — — — — — — — — — —
Landsca
pe Equip
ment

0.07745 0.07149 0.00366 0.43493 0.00003 0.00077 — 0.00077 0.00058 — 0.00058 — 1.78847 1.78847 0.00008 0.00002 — 1.79491 Total 0.32003 0.31407 0.00366 0.43493 0.00003 0.00077 — 0.00077 0.00058 — 0.00058 — 1.78847 1.78847 0.00008 0.00002 — 1.79491 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
72 / 100 Page 510 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Source TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Consum
er
Products

0.21400 0.21400 — — — — — — — — — — — — — — — —
Architect
ural
Coatings

0.02858 0.02858 — — — — — — — — — — — — — — — —
Total 0.24258 0.24258 — — — — — — — — — — — — — — — —
Annual — — — — — — — — — — — — — — — — — —
Consum
er
Products

0.03905 0.03905 — — — — — — — — — — — — — — — —
Architect
ural
Coatings

0.00522 0.00522 — — — — — — — — — — — — — — — —
Landsca
pe Equip
ment

0.00697 0.00643 0.00033 0.03914 < 0.0000
05 0.00007 — 0.00007 0.00005 — 0.00005 — 0.14602 0.14602 0.00001 < 0.0000 05 — 0.14655
Total 0.05124 0.05070 0.00033 0.03914 < 0.0000
05 0.00007 — 0.00007 0.00005 — 0.00005 — 0.14602 0.14602 0.00001 < 0.0000 05 — 0.14655

4.4. Water Emissions by Land Use

4.4.1. Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Land
Use
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
73 / 100 Page 511 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Land
Use
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e General
Office
Building
— — — — — — — — — — — 3.40580 6.43227 9.83807 0.35027 0.00842 — 21.1050 Unrefrig
erated
Wareho
use-No
Rail
— — — — — — — — — — — 1.28508 2.42702 3.71210 0.13216 0.00318 — 7.96332 Total — — — — — — — — — — — 4.69087 8.85930 13.5502 0.48243 0.01160 — 29.0683 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
General
Office
Building
— — — — — — — — — — — 3.40580 6.43227 9.83807 0.35027 0.00842 — 21.1050 Unrefrig
erated
Wareho
use-No
Rail
— — — — — — — — — — — 1.28508 2.42702 3.71210 0.13216 0.00318 — 7.96332 Total — — — — — — — — — — — 4.69087 8.85930 13.5502 0.48243 0.01160 — 29.0683 Annual — — — — — — — — — — — — — — — — — —
General
Office
Building
— — — — — — — — — — — 0.56387 1.06494 1.62880 0.05799 0.00139 — 3.49417 Unrefrig
erated
Wareho
use-No
Rail
— — — — — — — — — — — 0.21276 0.40182 0.61458 0.02188 0.00053 — 1.31842 Total — — — — — — — — — — — 0.77663 1.46676 2.24338 0.07987 0.00192 — 4.81259 74 / 100 Page 512 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

4.5. Waste Emissions by Land Use

4.5.1. Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Land
Use
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
General
Office
Building
— — — — — — — — — — — 5.01213 0.00000 5.01213 0.50094 0.00000 — 17.5357 Unrefrig
erated
Wareho
use-No
Rail
— — — — — — — — — — — 1.46915 0.00000 1.46915 0.14684 0.00000 — 5.14005 Total — — — — — — — — — — — 6.48128 0.00000 6.48128 0.64778 0.00000 — 22.6758 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
General
Office
Building
— — — — — — — — — — — 5.01213 0.00000 5.01213 0.50094 0.00000 — 17.5357 Unrefrig
erated
Wareho
use-No
Rail
— — — — — — — — — — — 1.46915 0.00000 1.46915 0.14684 0.00000 — 5.14005 Total — — — — — — — — — — — 6.48128 0.00000 6.48128 0.64778 0.00000 — 22.6758 Annual — — — — — — — — — — — — — — — — — —
75 / 100 Page 513 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Land
Use
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e General
Office
Building
— — — — — — — — — — — 0.82982 0.00000 0.82982 0.08294 0.00000 — 2.90324 Unrefrig
erated
Wareho
use-No
Rail
— — — — — — — — — — — 0.24323 0.00000 0.24323 0.02431 0.00000 — 0.85099 Total — — — — — — — — — — — 1.07305 0.00000 1.07305 0.10725 0.00000 — 3.75424

4.6. Refrigerant Emissions by Land Use

4.6.1. Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Land
Use
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
General
Office
Building
— — — — — — — — — — — — — — — — 0.02432 0.02432
Total — — — — — — — — — — — — — — — — 0.02432 0.02432
Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
General
Office
Building
— — — — — — — — — — — — — — — — 0.02432 0.02432
76 / 100 Page 514 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Land
Use
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Total — — — — — — — — — — — — — — — — 0.02432 0.02432
Annual — — — — — — — — — — — — — — — — — —
General
Office
Building
— — — — — — — — — — — — — — — — 0.00403 0.00403
Total — — — — — — — — — — — — — — — — 0.00403 0.00403

4.7. Offroad Emissions By Equipment Type

4.7.1. Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Equipme
nt Type
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Pumps 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 — 0.00000 — 0.00000 0.00000 0.00000 0.00000 — 0.00000 Total 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 — 0.00000 — 0.00000 0.00000 0.00000 0.00000 — 0.00000 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Pumps 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 — 0.00000 — 0.00000 0.00000 0.00000 0.00000 — 0.00000 Total 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 — 0.00000 — 0.00000 0.00000 0.00000 0.00000 — 0.00000 Annual — — — — — — — — — — — — — — — — — —
Pumps 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 — 0.00000 — 0.00000 0.00000 0.00000 0.00000 — 0.00000 77 / 100 Page 515 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Equipme
nt Type
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Total 0.00000 0.00000 0.00000 0.00000 0.00000 0.00000 — 0.00000 0.00000 — 0.00000 — 0.00000 0.00000 0.00000 0.00000 — 0.00000

4.8. Stationary Emissions By Equipment Type

4.8.1. Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Equipme
nt Type
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Emerge
ncy Gen
erator

6.49127 5.90705 26.4195 15.0637 0.02839 0.86906 0.00000 0.86906 0.86906 0.00000 0.86906 0.00000 3,022.25 3,022.25 0.12135 0.02368 0.00000 3,032.34 Total 6.49127 5.90705 26.4195 15.0637 0.02839 0.86906 0.00000 0.86906 0.86906 0.00000 0.86906 0.00000 3,022.25 3,022.25 0.12135 0.02368 0.00000 3,032.34 Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Emerge
ncy Gen
erator

6.49127 5.90705 26.4195 15.0637 0.02839 0.86906 0.00000 0.86906 0.86906 0.00000 0.86906 0.00000 3,022.25 3,022.25 0.12135 0.02368 0.00000 3,032.34 Total 6.49127 5.90705 26.4195 15.0637 0.02839 0.86906 0.00000 0.86906 0.86906 0.00000 0.86906 0.00000 3,022.25 3,022.25 0.12135 0.02368 0.00000 3,032.34 Annual — — — — — — — — — — — — — — — — — —
Emerge
ncy Gen
erator

0.16228 0.14768 0.66049 0.37659 0.00071 0.02173 0.00000 0.02173 0.02173 0.00000 0.02173 0.00000 68.5436 68.5436 0.00275 0.00054 0.00000 68.7724 Total 0.16228 0.14768 0.66049 0.37659 0.00071 0.02173 0.00000 0.02173 0.02173 0.00000 0.02173 0.00000 68.5436 68.5436 0.00275 0.00054 0.00000 68.7724 78 / 100 Page 516 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

4.9. User Defined Emissions By Equipment Type

4.9.1. Unmitigated
Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Equipme
nt Type
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Total — — — — — — — — — — — — — — — — — —
Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Total — — — — — — — — — — — — — — — — — —
Annual — — — — — — — — — — — — — — — — — —
Total — — — — — — — — — — — — — — — — — —

4.10. Soil Carbon Accumulation By Vegetation Type

4.10.1. Soil Carbon Accumulation By Vegetation Type - Unmitigated Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Vegetati
on
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Total — — — — — — — — — — — — — — — — — —
79 / 100 Page 517 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Vegetati
on
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Total — — — — — — — — — — — — — — — — — —
Annual — — — — — — — — — — — — — — — — — —
Total — — — — — — — — — — — — — — — — — —

4.10.2. Above and Belowground Carbon Accumulation by Land Use Type - Unmitigated Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) Land
Use
TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Total — — — — — — — — — — — — — — — — — —
Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Total — — — — — — — — — — — — — — — — — —
Annual — — — — — — — — — — — — — — — — — —
Total — — — — — — — — — — — — — — — — — —

4.10.3. Avoided and Sequestered Emissions by Species - Unmitigated Criteria Pollutants (lb/day for daily, ton/yr for annual) and GHGs (lb/day for daily, MT/yr for annual) 80 / 100 Page 518 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Species TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Daily, Su
mmer
(Max)
— — — — — — — — — — — — — — — — — —
Avoided — — — — — — — — — — — — — — — — — —
Subtotal — — — — — — — — — — — — — — — — — —
Sequest
ered
— — — — — — — — — — — — — — — — — —
Subtotal — — — — — — — — — — — — — — — — — —
Remove
d
— — — — — — — — — — — — — — — — — —
Subtotal — — — — — — — — — — — — — — — — — —
— — — — — — — — — — — — — — — — — — —
Daily,
Winter
(Max)
— — — — — — — — — — — — — — — — — —
Avoided — — — — — — — — — — — — — — — — — —
Subtotal — — — — — — — — — — — — — — — — — —
Sequest
ered
— — — — — — — — — — — — — — — — — —
Subtotal — — — — — — — — — — — — — — — — — —
Remove
d
— — — — — — — — — — — — — — — — — —
Subtotal — — — — — — — — — — — — — — — — — —
— — — — — — — — — — — — — — — — — — —
Annual — — — — — — — — — — — — — — — — — —
81 / 100 Page 519 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Species TOG ROG NOx CO SO2 PM10E PM10D PM10T PM2.5E PM2.5D PM2.5T BCO2 NBCO2 CO2T CH4 N2O R CO2e Avoided — — — — — — — — — — — — — — — — — —
Subtotal — — — — — — — — — — — — — — — — — —
Sequest
ered
— — — — — — — — — — — — — — — — — —
Subtotal — — — — — — — — — — — — — — — — — —
Remove
d
— — — — — — — — — — — — — — — — — —
Subtotal — — — — — — — — — — — — — — — — — —
— — — — — — — — — — — — — — — — — — —

5. Activity Data

5.1. Construction Schedule
Phase Name Phase Type Start Date End Date Days Per Week Work Days per Phase Phase Description Demolition Demolition 1/1/2027 4/9/2027 5.00000 70.0000 — Site Preparation Site Preparation 4/10/2027 6/5/2027 5.00000 40.0000 — Grading Grading 6/6/2027 11/7/2027 5.00000 110.000 —
Building Construction Building Construction 11/8/2027 2/9/2032 5.00000 1,110.00 — Paving Paving 2/10/2032 5/25/2032 5.00000 75.0000 —
Architectural Coating Architectural Coating 5/26/2032 9/8/2032 5.00000 75.0000 — Linear, Grubbing & Land
Clearing
Linear, Grubbing & Land
Clearing
1/1/2027 7/21/2027 5.00000 144.000 —
82 / 100 Page 520 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Phase Name Phase Type Start Date End Date Days Per Week Work Days per Phase Phase Description Linear, Grading &
Excavation
Linear, Grading &
Excavation
7/22/2027 1/14/2030 5.00000 648.000 —
Linear, Drainage,
Utilities, & Sub-Grade
Linear, Drainage,
Utilities, & Sub-Grade
1/15/2030 9/11/2031 5.00000 432.000 —
Linear, Paving Linear, Paving 9/12/2031 7/10/2032 5.00000 216.000 —

5.2. Off-Road Equipment

5.2.1. Unmitigated
Phase Name Equipment Type Fuel Type Engine Tier Number per Day Hours Per Day Horsepower Load Factor Demolition Rubber Tired Dozers Diesel Average 2.00000 8.00000 367.000 0.40000 Demolition Concrete/Industrial
Saws
Diesel Average 1.000000 8.00000 33.0000 0.73000
Demolition Excavators Diesel Average 3.00000 8.00000 36.0000 0.38000 Site Preparation Rubber Tired Dozers Diesel Average 3.00000 8.00000 367.000 0.40000 Site Preparation Tractors/Loaders/
Backhoes
Diesel Average 4.00000 8.00000 84.0000 0.37000
Grading Graders Diesel Average 1.000000 8.00000 148.000 0.41000 Grading Tractors/Loaders/
Backhoes
Diesel Average 2.00000 8.00000 84.0000 0.37000
Grading Rubber Tired Dozers Diesel Average 1.000000 8.00000 367.000 0.40000 Grading Excavators Diesel Average 2.00000 8.00000 36.0000 0.38000 Grading Scrapers Diesel Average 2.00000 8.00000 423.000 0.48000 Building Construction Cranes Diesel Average 1.000000 7.00000 367.000 0.29000 83 / 100 Page 521 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Phase Name Equipment Type Fuel Type Engine Tier Number per Day Hours Per Day Horsepower Load Factor Building Construction Forklifts Diesel Average 3.00000 8.00000 82.0000 0.20000 Building Construction Generator Sets Diesel Average 1.000000 8.00000 14.0000 0.74000 Building Construction Tractors/Loaders/
Backhoes
Diesel Average 3.00000 7.00000 84.0000 0.37000
Building Construction Welders Diesel Average 1.000000 8.00000 46.0000 0.45000 Building Construction Aerial Lifts Diesel Average 1.000000 8.00000 46.0000 0.31000 Paving Pavers Diesel Average 2.00000 8.00000 81.0000 0.42000 Paving Paving Equipment Diesel Average 2.00000 8.00000 89.0000 0.36000 Paving Rollers Diesel Average 2.00000 8.00000 36.0000 0.38000 Architectural Coating Air Compressors Diesel Average 1.000000 6.00000 37.0000 0.48000 Linear, Grubbing &
Land Clearing
Signal Boards Electric Average 3.00000 8.00000 6.00000 0.82000 Linear, Grubbing &
Land Clearing
Crawler Tractors Diesel Average 1.000000 8.00000 87.0000 0.43000 Linear, Grubbing &
Land Clearing
Excavators Diesel Average 2.00000 8.00000 36.0000 0.38000 Linear, Grading &
Excavation
Excavators Diesel Average 3.00000 8.00000 36.0000 0.38000 Linear, Grading &
Excavation
Crawler Tractors Diesel Average 1.000000 8.00000 87.0000 0.43000 Linear, Grading &
Excavation
Graders Diesel Average 2.00000 8.00000 148.000 0.41000
Linear, Grading &
Excavation
Rollers Diesel Average 2.00000 8.00000 36.0000 0.38000
Linear, Grading &
Excavation
Signal Boards Electric Average 3.00000 8.00000 6.00000 0.82000 84 / 100 Page 522 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Phase Name Equipment Type Fuel Type Engine Tier Number per Day Hours Per Day Horsepower Load Factor Linear, Grading &
Excavation
Scrapers Diesel Average 2.00000 8.00000 423.000 0.48000 Linear, Grading &
Excavation
Rubber Tired Loaders Diesel Average 1.000000 8.00000 150.000 0.36000 Linear, Grading &
Excavation
Tractors/Loaders/
Backhoes
Diesel Average 4.00000 8.00000 84.0000 0.37000
Linear, Grading &
Excavation
Skid Steer Loaders Diesel Average 1.000000 8.00000 71.0000 0.37000 Linear, Drainage,
Utilities, & Sub-Grade
Tractors/Loaders/
Backhoes
Diesel Average 3.00000 8.00000 84.0000 0.37000
Linear, Drainage,
Utilities, & Sub-Grade
Scrapers Diesel Average 1.000000 8.00000 423.000 0.48000 Linear, Drainage,
Utilities, & Sub-Grade
Signal Boards Electric Average 3.00000 8.00000 6.00000 0.82000 Linear, Drainage,
Utilities, & Sub-Grade
Rough Terrain
Forklifts
Diesel Average 1.000000 8.00000 96.0000 0.40000
Linear, Drainage,
Utilities, & Sub-Grade
Graders Diesel Average 1.000000 8.00000 148.000 0.41000 Linear, Drainage,
Utilities, & Sub-Grade
Plate Compactors Diesel Average 1.000000 8.00000 8.00000 0.43000 Linear, Drainage,
Utilities, & Sub-Grade
Pumps Diesel Average 1.000000 8.00000 11.0000 0.74000
Linear, Drainage,
Utilities, & Sub-Grade
Air Compressors Diesel Average 1.000000 8.00000 37.0000 0.48000 Linear, Drainage,
Utilities, & Sub-Grade
Generator Sets Diesel Average 1.000000 8.00000 14.0000 0.74000 Linear, Drainage,
Utilities, & Sub-Grade
Aerial Lifts Diesel Average 1.000000 8.00000 46.0000 0.31000 85 / 100 Page 523 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Phase Name Equipment Type Fuel Type Engine Tier Number per Day Hours Per Day Horsepower Load Factor Linear, Drainage,
Utilities, & Sub-Grade
Other General
Industrial Equipment
Diesel Average 1.000000 8.00000 35.0000 0.34000
Linear, Drainage,
Utilities, & Sub-Grade
Cranes Diesel Average 1.000000 8.00000 367.000 0.29000
Linear, Drainage,
Utilities, & Sub-Grade
Welders Diesel Average 1.000000 8.00000 46.0000 0.45000 Linear, Paving Rollers Diesel Average 2.00000 8.00000 36.0000 0.38000 Linear, Paving Paving Equipment Diesel Average 1.000000 8.00000 89.0000 0.36000 Linear, Paving Pavers Diesel Average 1.000000 8.00000 81.0000 0.42000 Linear, Paving Signal Boards Electric Average 3.00000 8.00000 6.00000 0.82000 Linear, Paving Tractors/Loaders/
Backhoes
Diesel Average 3.00000 8.00000 84.0000 0.37000

5.3. Construction Vehicles

5.3.1. Unmitigated
Phase Name Trip Type One-Way Trips per Day Miles per Trip Vehicle Mix Demolition Worker 15.0000 11.7000 LDA,LDT1,LDT2
Demolition Vendor — 8.40000 HHDT,MHDT
Demolition Hauling 0.00000 20.0000 HHDT
Demolition Onsite truck — — HHDT
Site Preparation Worker 17.5000 11.7000 LDA,LDT1,LDT2
Site Preparation Vendor — 8.40000 HHDT,MHDT
86 / 100 Page 524 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Phase Name Trip Type One-Way Trips per Day Miles per Trip Vehicle Mix Site Preparation Hauling 0.00000 20.0000 HHDT
Site Preparation Onsite truck — — HHDT
Grading Worker 20.0000 11.7000 LDA,LDT1,LDT2
Grading Vendor — 8.40000 HHDT,MHDT
Grading Hauling 25.8727 20.0000 HHDT
Grading Onsite truck — — HHDT
Building Construction Worker 3.20000 11.7000 LDA,LDT1,LDT2 Building Construction Vendor 1.63900 8.40000 HHDT,MHDT
Building Construction Hauling 0.00000 20.0000 HHDT
Building Construction Onsite truck — — HHDT
Paving Worker 15.0000 11.7000 LDA,LDT1,LDT2
Paving Vendor — 8.40000 HHDT,MHDT
Paving Hauling 0.00000 20.0000 HHDT
Paving Onsite truck — — HHDT
Architectural Coating Worker 0.64000 11.7000 LDA,LDT1,LDT2 Architectural Coating Vendor — 8.40000 HHDT,MHDT
Architectural Coating Hauling 0.00000 20.0000 HHDT
Architectural Coating Onsite truck — — HHDT
Linear, Grubbing & Land Clearing Worker 15.0000 11.7000 LDA,LDT1,LDT2 Linear, Grubbing & Land Clearing Vendor 0.00000 8.40000 HHDT,MHDT Linear, Grubbing & Land Clearing Hauling 0.00000 20.0000 HHDT 87 / 100 Page 525 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Phase Name Trip Type One-Way Trips per Day Miles per Trip Vehicle Mix Linear, Grubbing & Land Clearing Onsite truck — — HHDT
Linear, Grading & Excavation Worker 47.5000 11.7000 LDA,LDT1,LDT2 Linear, Grading & Excavation Vendor 1.000000 8.40000 HHDT,MHDT Linear, Grading & Excavation Hauling 0.00000 20.0000 HHDT Linear, Grading & Excavation Onsite truck — — HHDT
Linear, Drainage, Utilities, & Sub-GradeWorker 42.5000 11.7000 LDA,LDT1,LDT2 Linear, Drainage, Utilities, & Sub-GradeVendor 0.00000 8.40000 HHDT,MHDT Linear, Drainage, Utilities, & Sub-GradeHauling 0.00000 20.0000 HHDT Linear, Drainage, Utilities, & Sub-GradeOnsite truck — — HHDT Linear, Paving Worker 25.0000 11.7000 LDA,LDT1,LDT2
Linear, Paving Vendor 0.00000 8.40000 HHDT,MHDT
Linear, Paving Hauling 0.00000 20.0000 HHDT
Linear, Paving Onsite truck — — HHDT

5.4. Vehicles

5.4.1. Construction Vehicle Control Strategies
Control Strategies Applied PM10 Reduction PM2.5 Reduction Water unpaved roads twice daily 55% 55%
88 / 100 Page 526 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Control Strategies Applied PM10 Reduction PM2.5 Reduction Limit vehicle speeds on unpaved roads to 25 mph 44% 44%

5.5. Architectural Coatings
Phase Name Residential Interior Area
Coated (sq ft)
Residential Exterior Area
Coated (sq ft)
Non-Residential Interior Area
Coated (sq ft)
Non-Residential Exterior
Area Coated (sq ft)
Parking Area Coated (sq ft)
Architectural Coating 0.00000 0.00000 15,000.0 5,000.00 —

5.6. Dust Mitigation

5.6.1. Construction Earthmoving Activities
Phase Name Material Imported (cy) Material Exported (cy) Acres Graded (acres) Material Demolished (sq. ft.) Acres Paved (acres) Demolition 0.00000 0.00000 0.00000 — 0.00000
Site Preparation — — 60.0000 0.00000 0.00000
Grading — 22,763.0 2.00000 0.00000 0.00000
Paving 0.00000 0.00000 0.00000 0.00000 1.30000
Linear, Grubbing & Land
Clearing
— — 1.30000 0.00000 0.00000
Linear, Grading & Excavation — — 1.30000 0.00000 0.00000 Linear, Drainage, Utilities, &
Sub-Grade
— — 1.30000 0.00000 0.00000

5.6.2. Construction Earthmoving Control Strategies
89 / 100 Page 527 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Control Strategies Applied Frequency (per day) PM10 Reduction PM2.5 Reduction Water Exposed Area 2 61% 61%

5.7. Construction Paving
Phase Name Land Use Area Paved (acres) % Asphalt
Paving Road Widening 1.30000 100%
Paving General Office Building 0.00000 0%
Paving Unrefrigerated Warehouse-No Rail 0.00000 0%

5.8. Construction Electricity Consumption and Emissions Factors kWh per Year and Emission Factor (lb/MWh)
Year kWh per Year CO2 CH4 N2O
2028 88.0523 203.983 0.03300 0.00400
2029 88.0523 203.983 0.03300 0.00400
2030 176.105 203.983 0.03300 0.00400
2027 176.105 203.983 0.03300 0.00400
2031 176.105 203.983 0.03300 0.00400
2032 88.0523 203.983 0.03300 0.00400

5.9. Operational Mobile Sources

5.9.1. Unmitigated
90 / 100 Page 528 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Land Use Type Trips/Weekday Trips/Saturday Trips/Sunday Trips/Year VMT/Weekday VMT/Saturday VMT/Sunday VMT/Year General Office
Building

34.0000 34.0000 34.0000 12,410.0 189.487 189.487 189.487 69,162.6 Unrefrigerated
Warehouse-No Rail

3.01600 3.01600 3.01600 1,100.84 16.8086 16.8086 16.8086 6,135.13

5.10. Operational Area Sources

5.10.1. Hearths
Land Use Hearth Type Unmitigated (number) Mitigated (number) General Office Building Wood Fireplaces 0 0
General Office Building Gas Fireplaces 0 0
General Office Building Propane Fireplaces 0 0
General Office Building Electric Fireplaces 0 0
General Office Building No Fireplaces 0 0
General Office Building Conventional Wood Stoves 0 0
General Office Building Catalytic Wood Stoves 0 0
General Office Building Non-Catalytic Wood Stoves 0 0
General Office Building Pellet Wood Stoves 0 0
Unrefrigerated Warehouse-No Rail Wood Fireplaces 0 0
Unrefrigerated Warehouse-No Rail Gas Fireplaces 0 0
Unrefrigerated Warehouse-No Rail Propane Fireplaces 0 0 Unrefrigerated Warehouse-No Rail Electric Fireplaces 0 0 91 / 100 Page 529 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Land Use Hearth Type Unmitigated (number) Mitigated (number) Unrefrigerated Warehouse-No Rail No Fireplaces 0 0
Unrefrigerated Warehouse-No Rail Conventional Wood Stoves 0 0 Unrefrigerated Warehouse-No Rail Catalytic Wood Stoves 0 0 Unrefrigerated Warehouse-No Rail Non-Catalytic Wood Stoves 0 0 Unrefrigerated Warehouse-No Rail Pellet Wood Stoves 0 0

5.10.2. Architectural Coatings
Residential Interior Area Coated (sq
ft)
Residential Exterior Area Coated
(sq ft)
Non-Residential Interior Area
Coated (sq ft)
Non-Residential Exterior Area
Coated (sq ft)
Parking Area Coated (sq ft)

0.00000 0.00000 15,000.0 5,000.00 —

5.10.3. Landscape Equipment
Season Unit Value
Snow Days day/yr 0.00000
Summer Days day/yr 180.000

5.11. Operational Energy Consumption

5.11.1. Unmitigated
Electricity (kWh/yr) and CO2 and CH4 and N2O and Natural Gas (kBTU/yr) Land Use Electricity (kWh/yr) CO2 CH4 N2O Natural Gas (kBTU/yr) General Office Building 209,293 203.983 0.0330 0.0040 288,690 92 / 100 Page 530 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Land Use Electricity (kWh/yr) CO2 CH4 N2O Natural Gas (kBTU/yr) Unrefrigerated Warehouse-No Rail0.00000 203.983 0.0330 0.0040 0.00000

5.12. Operational Water and Wastewater Consumption

5.12.1. Unmitigated
Land Use Indoor Water (gal/year) Outdoor Water (gal/year) General Office Building 1,777,337 0.00000
Unrefrigerated Warehouse-No Rail 670,625 0.00000

5.13. Operational Waste Generation

5.13.1. Unmitigated
Land Use Waste (ton/year) Cogeneration (kWh/year)
General Office Building 9.30000 0.00000
Unrefrigerated Warehouse-No Rail 2.72600 0.00000

5.14. Operational Refrigeration and Air Conditioning Equipment

5.14.1. Unmitigated
93 / 100 Page 531 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Land Use Equipment Type Refrigerant GWP Quantity (kg) Operations Leak Rate Service Leak Rate Times Serviced General Office
Building
Household
refrigerators and/or
freezers
R-134a 1,430.00 0.01679 0.60000 0.00000 1.000000
General Office
Building
Other commercial A/
C and heat pumps
R-410A 2,088.00 0.00180 4.00000 4.00000 18.0000

5.15. Operational Off-Road Equipment

5.15.1. Unmitigated
Equipment Type Fuel Type Engine Tier Number per Day Hours Per Day Horsepower Load Factor Pumps Electric Average 3.00000 24.0000 50.0000 0.74000

5.16. Stationary Sources

5.16.1. Emergency Generators and Fire Pumps
Equipment Type Fuel Type Number per Day Hours per Day Hours per Year Horsepower Load Factor Emergency Generator Diesel 2.00000 1.000000 50.0000 1,800.00 0.73000

5.16.2. Process Boilers

5.17. User Defined

5.18. Vegetation
94 / 100 Page 532 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

5.18.1. Land Use Change

5.18.1.1. Unmitigated
Vegetation Land Use Type Vegetation Soil Type Initial Acres Final Acres

5.18.1. Biomass Cover Type

5.18.1.1. Unmitigated
Biomass Cover Type Initial Acres Final Acres

5.18.2. Sequestration

5.18.2.1. Unmitigated
Tree Type Number Electricity Saved (kWh/year) Natural Gas Saved (btu/year)

8. User Changes to Default Data

8.1. Justifications
Screen Justification
Land Use Total acreage adjusted to reflect the maximum total disturbance area (57.48 acres).

Construction: Off-Road Equipment Equipment added to match project-specific list Construction: Dust From Material Movement Material export was calculated to account for: 3 new ozone basins, 3 flocculation/ sedimentation basins, equalization basin, and 2 sludge lagoons. 95 / 100 Page 533 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Screen Justification
Operations: Vehicle Data Trips applied to the General Office Building land use represent expanded staffing requirements (up to 17 new staff, so maximum of 34 new one-way trips per day).

Trips applied to Warehouse land use represent chemical delivery trips (up to 550 per year [~1.5 per day], so maximum of 3 new one-way delivery trips per day).

Operations: Fleet Mix All modeled chemical delivery trips are assumed to be HHDT.

Operations: Refrigerants No refrigeration equipment required.

Operations: Off-Road Equipment Assumed 24/7 use of water pumps.

8.3. Land Use
Model Parameter Units Default Value New Value
Lot Area acre 0.22957 56.1100
Landscape Area sq. ft — 0.00000

8.4. Construction

8.4.4. Dust from Material Movement
Phase Name Model Parameter Units Default Value New Value Grading Material Exported Cubic Yards — 22,763.0
Grading Total Acres Graded acres 330.000 2.00000

8.5. Operations

8.5.1. Mobile Sources
96 / 100 Page 534 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026

8.5.1.1. Vehicle Data
Land Use Model Parameter Units Default Value New Value
General Office Building Weekday Trip Rate size/day 9.74000 3.40000 General Office Building Saturday Trip Rate size/day 2.21000 3.40000 General Office Building Sunday Trip Rate size/day 0.70000 3.40000 Unrefrigerated Warehouse-No Rail Weekday Trip Rate size/day 1.74000 1.04000 Unrefrigerated Warehouse-No Rail Saturday Trip Rate size/day 1.74000 1.04000 Unrefrigerated Warehouse-No Rail Sunday Trip Rate size/day 1.74000 1.04000

8.5.1.2. Fleet Mix
Land Use Season Model Parameter Units Default Value New Value Unrefrigerated Warehouse-No RailA Heavy-Heavy-Duty Trucks % 1% 100% Unrefrigerated Warehouse-No RailA Passenger Cars % 52% 0% Unrefrigerated Warehouse-No RailA Light-Duty Trucks 1 % 3% 0% Unrefrigerated Warehouse-No RailA Light-Duty Trucks 2 % 21% 0% Unrefrigerated Warehouse-No RailA Light Heavy-Duty Trucks 1 % 3% 0% Unrefrigerated Warehouse-No RailA Light Heavy-Duty Trucks 2 % 1% 0% Unrefrigerated Warehouse-No RailA Motorcycles % 2% 0%
97 / 100 Page 535 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Land Use Season Model Parameter Units Default Value New Value Unrefrigerated Warehouse-No RailA Medium-Duty Trucks % 14% 0% Unrefrigerated Warehouse-No RailA Motor Homes % < 0.5% 0% Unrefrigerated Warehouse-No RailA Medium-Heavy-Duty Trucks % 1% 0% Unrefrigerated Warehouse-No RailA Other Buses % < 0.5% 0% Unrefrigerated Warehouse-No RailA School Buses % < 0.5% 0% Unrefrigerated Warehouse-No RailA Urban Buses % < 0.5% 0% Unrefrigerated Warehouse-No RailS Heavy-Heavy-Duty Trucks % 1% 100% Unrefrigerated Warehouse-No RailS Passenger Cars % 52% 0% Unrefrigerated Warehouse-No RailS Light-Duty Trucks 1 % 3% 0% Unrefrigerated Warehouse-No RailS Light-Duty Trucks 2 % 21% 0% Unrefrigerated Warehouse-No RailS Light Heavy-Duty Trucks 1 % 3% 0% Unrefrigerated Warehouse-No RailS Light Heavy-Duty Trucks 2 % 1% 0% Unrefrigerated Warehouse-No RailS Motorcycles % 2% 0%
Unrefrigerated Warehouse-No RailS Medium-Duty Trucks % 14% 0% 98 / 100 Page 536 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Land Use Season Model Parameter Units Default Value New Value Unrefrigerated Warehouse-No RailS Motor Homes % < 0.5% 0% Unrefrigerated Warehouse-No RailS Medium-Heavy-Duty Trucks % 1% 0% Unrefrigerated Warehouse-No RailS Other Buses % < 0.5% 0% Unrefrigerated Warehouse-No RailS School Buses % < 0.5% 0% Unrefrigerated Warehouse-No RailS Urban Buses % < 0.5% 0% Unrefrigerated Warehouse-No RailW Heavy-Heavy-Duty Trucks % 1% 100% Unrefrigerated Warehouse-No RailW Passenger Cars % 52% 0% Unrefrigerated Warehouse-No RailW Light-Duty Trucks 1 % 3% 0% Unrefrigerated Warehouse-No RailW Light-Duty Trucks 2 % 21% 0% Unrefrigerated Warehouse-No RailW Light Heavy-Duty Trucks 1 % 3% 0% Unrefrigerated Warehouse-No RailW Light Heavy-Duty Trucks 2 % 1% 0% Unrefrigerated Warehouse-No RailW Motorcycles % 2% 0%
Unrefrigerated Warehouse-No RailW Medium-Duty Trucks % 14% 0% Unrefrigerated Warehouse-No RailW Motor Homes % < 0.5% 0% 99 / 100 Page 537 of 1497
Fairfield-Vacaville Water Works Project v5 Custom Report, 9/28/2026 Land Use Season Model Parameter Units Default Value New Value Unrefrigerated Warehouse-No RailW Medium-Heavy-Duty Trucks % 1% 0% Unrefrigerated Warehouse-No RailW Other Buses % < 0.5% 0% Unrefrigerated Warehouse-No RailW School Buses % < 0.5% 0% Unrefrigerated Warehouse-No RailW Urban Buses % < 0.5% 0%

8.5.7. Off-Road Equipment

8.5.7.1. Off-Road Equipment
Equipment Type Model Parameter Default Value New Value
Pumps Fuel Type Diesel Electric
Pumps Hours/Day 8.00000 24.0000
Pumps Days/Year 260.000 365.000
Pumps Horsepower 11.0000 50.0000
100 / 100 Page 538 of 1497

MITIGATION MONITORING AND REPORTING P ROGRAM
OCTOBER 2026

NORTH B AY REGIONAL WATER T REATMENT PLANT ,

F AIRFIELD -V ACAVILLE WATER WORKS P ROJECT

F AIRFIELD , C ALIFORNIA
\\aznasunifiler2\projects\2025\20252567.02_West Yost North Regional WTP\PRODUCT\CEQA\Final\North Bay Regional ISMND.docx (10/06/26)

APPENDIX B

AQUATIC RESOURCES DELINEATION AND

BIOLOGICAL RESOURCES REPORT

Page 539 of 1497 ends
← All documents from this meeting