City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix a - saMples
PRE-CON MEETING AGENDA
• Liquidated damages shall be $3,500 per calendar day of delay
V. PROJECT WORK AREA (Southstar)
• Permission r equired to use private property for storage or stockpiling • Dust control and project area appearance - certified PM10 is im portant • Traffic Control – Contractor to submit for approval if different than plans o Ensure traffic cones are new or like new
o Existing signs of any type must always be relocated, never removed or laid down.
o A minim um of 150 stalls per lot must be open/available at any given time. • Final clean up
o Black out USA marks on asphalt
o Remove USA marks from concrete
VI. COMMUNICATIONS & MEETINGS (Southstar)
• Weekly/monthly progress meetings TUESDAYS AT 9:00 a.m. (In-person AND Zoom)
• Contractor tracking software to be used (if any)? None. Emails only. • Communications protocols for contractor, CM, City, residents/businesses – Vanessa will create business cards with all project contact information and give to the contractor/subs. If approached by a member of the public, contractor/subs are to give the card and ask them to contact Vanessa.
• City approvals required for all notifications
• Project website = http://www.presidentsplazavision.com • Project camera – The camera will remain on San Pablo Phase 2 until July, then move it to Presidents’ Plaza – need to determine a location
VIII. Communications Plan
• Communications Plan overview
• Emergency contingencies – 24 hours a day
• Engaging property owners and business tenants
• Notif ications to Sunline, Burrtec, USPS, emergency services, etc.
IX. SUBMITTALS (Southstar)
• Emergency contact Information
• SWPPP and PM-10 - Done
• Materials – Mix designs submitted, under review
VIII. MONTHLY PROGRESS PAYMENTS (Southstar)
• Daily agreement with field inspector on all payable quantities and any extra work • Submit agreed upon billings by end of month
• Submit certified payroll records to DIR as required – Every two (2) weeks via email
• City review and payment (need to submit an Excel spreadsheet and PDF) • Extra work per specifications – No unauthorized work – need written direction from Southstar
17.B
Page xi
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix a - saMples
PRE-CON MEETING AGENDA
• Closing date and submittal frequency – Last day of calendar month
IX. SURVEYING AND SOILS TESTING (Southstar)
• Call- out procedure
• Leighton Group performing materials testing and special inspections – Prefer 48 hours minimum request lead time prior to materials testing • Tie-outs completed by DEA
• Protect existing monuments – or tie-out
• Construction staking – to be done by sub (Precision Surveying in Highland)
X. CHANGE ORDERS (Southstar and City)
• No unauthorized extra work
• Procedure for submitting RFI
• CCO Procedure (City) – Several steps:
o CM & Contr actor meet and discuss and agree on cost/scope changes o Randy will write a memo to the City Manager with det ails o The CCO form will be sent to the contractor to sign (2 copies) and send back to City
o City signs and sends fully executed copy to contractor via USPS
XI. UTILITY COORDINATION (Southstar)
• CVWD
• Southern California Edison – Final design submitted May 11, working toward final approval, which should be within one week +/-. Then project goes to bid and work generally starts 6-8 weeks after final design approved.
Southstar and H&H and SCE will coordinate together to ensure no delays occur to either project.
• Southern California Gas Company
• Charter/Spectrum – Ready to go, just need two week notice. • Frontier
• Other Issues
XII. NOTICE OF COMPLETION (Southstar)
• Issued by City Council upon staff recommendation – Project Acceptance
XIII. NEXT STEPS / FOLLOW UP NEEDED (see above)
17.B
Page xii
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix a - saMples
Shift Hours Start 13:30
INSPECTOR'S DAILY
to
0 0
15 28 20 Prime (P)
LS LS LF Sub - Item #15 (1)
0 0 0 Sub - Item #28 (2)
Sub - Item # (3)
Sub - Item # (4)
Sub - Item #20 (5)
(6)
0 0 0 < RT/OT
624J HG9F86 1 JD Front loader 8.00 P
Asphalt Zipper 1 Pulverize 5.00 3.00 P
330B AF3L39 1 Cat. Excavator 3.50 4.50 P
135C YA8E36 1 JD Excavator 5.00 3.00 P
JX6J68 1 CAT Backhoe 3.50 4.50 P
HW3T98 1 Bobcat-Sweeper 3.50 4.50 P
UT Truck 1 GMC 2500 HD 8.00 3.00 P
NA 1 FR water 5000 G 8.00 3.00 P
NA 1 CASE Backhoe 8.00 P
YM3M78 1 Small Compactor 8.00 P
HD B25D89J87 1 Loading truck 8.00 P
FB9J87 1 Loading truck 8.00 P
UT truck /Recycle GMC 2500 HD
UT truck/Trees Ford F 150
UT truck /Survey Ford F150
Work Truck 1 Chevy 5500 8.00 S
1 CAT Backhoe 8.00 S
S
Crew Truck 1 S
Mini Excavator 1 S
Dump Trailer 1 S
1 S
1 S
REG: 8.0 INTERMITTENT
OT: 1.0 INSPECTION
City of Palm Desert No. 758-14
Presidents' Plaza East/West
Parking Lot Improvements Project Date the Shift
Began: 9/30/21
JOB STAMP:
Report No.
Location: Station: Station: Line:
Federal ID No. N/A
5:00 Stop
THURSDAY
Remark: Rt/Lt of CL Rt/Lt of CL Working Day # Non-WD
REPORT
HOURS - ITEM NO. PARTY NAME OF FIRM
ITEM NO. >>
IDLE OR DOWN
H and H
ITEM UNIT >> H and H
DAILY ITEM QUANTITY >> Competitive Edge
H&H
EQUIPMENT AND/OR LABOR: Sub - Item # #N/A
EQPT. NO. NO.
MEN
DESCRIPTION
(OF EQUIP OR LABOR)
REMARKS
H&H
Weather-Temp:(109 -89)F Rain:0 Wind:7 #N/A
PCC and
Hardscape
Improvements
Install Electrical
Improvements
Install 1" Domestic
Water Pipe T&M
Laborer
Jason Young Laborer
Name Classification
John Carpenter Superintendent
Arturo Hernandez foreman
Eric Gonzales Laborer
Mike Proch foreman
Chris Grisham Laborer
Dalton Young Laborer
PRIME/
SUB
Julio Silva Operator
Jason Cranell laborer app.
Gustavo Marquez Laborer
Steve Faulkinstien Laborer
Tony Marquez Jr.
Matt Eddy Superintendent
Enrique Vasquez Laborer
Carlos Cartagena Laborer
Miguel Blanco Laborer
Ricardo Napoles Laborer
Kirk Mcmanis Shop Hand
Agustine Napoles Foreman
MATERIALS:
Insp. Hrs.
Oscar Hernandez Laborer
Construction Inspector
Mike Smith Title
Description of Operations:
Item #15- Inspected contractor H&H working in the East parking on cutting sub-grad and compacting for proposed sidewalk.
Item #28- Inspected sub-contractor Competitive Edge Electric on-site trenching and installing conduits for lighting in the sidewalk for the South side of the East parking lot.
Item #20- Inspected contractor H&H crew trenching and installing 1" lateral domestic water service pipe per plan in West lot.
NIGHTWORK
NIGHTWORK
SAMPLE DAILY REPORT
17.B
Page xiii
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix a - saMples
Shift Hours Start 13:30
Date the Shift
Began: 9/30/21City of Palm Desert No. 758-14
0Presidents' Plaza East/West
Parking Lot Improvements Project
JOB STAMP:
Report No.
Federal ID No. N/A
5:00 Stop
THURSDAY
Picture shows sub-contractor trenching and installing conduit for lighting in the sidewalk along the South side of the East lot.
Picture shows contractor H&H cutting sub-grade and compacting grade for proposed sidewalk South side of East lot.
Picture shows contractor H&H exposing existing water services to buildings and stubbing new lines next to old services.
Picture shows contractor H&H found existing water service to Spectacular Shades.
Picture shows contractor H&H exposed existing water service at Spectacular shades which was 3' off from stub up.
Picture shows contractor H&H trenching and installing domestic water services for Acupuncture building.
NIGHTWORK
17.B
Page xiv
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix a - saMples
Shift Hours Start 13:30
PREPARED BY:
APPROVED BY:
Report No. 0
Parking Lot Improvements Project
JOB STAMP:
Presidents' Plaza East/West Date the Shift
Began: 9/30/21
Federal ID No. N/A 5:00 Stop
City of Palm Desert No. 758-14 THURSDAY
Resident Engineer
Amr Abuelhassan Title Date
Construction Inspector 9/30/21
Mike Smith Title Date
Description of Operation:
Item #15- Inspected contractor H&H on-site cutting sub-grade for proposed sidewalk the South side of the East parking lot. Crew started at the far West end of the lot and working their way towards the East. Inspector reminded contactor H&H of the called out 4" section. Inspector made sure crew was cutting this called out section of 4" as well as grading the sub-grade to 2% or less on the cross fall to keep proposed sidewalk within ADA compliance.
Crew is still not able to do any grading for curb and gutter in front of the Rolex building. Note that the inspector and superintendent from H&H walked the entire job-site to check proposed cross-falls of sidewalks. It was shown when checking with a smart level that the sidewalkfrom Casuelas Cafe to the West at the tie-in to existing by Larkspur that the sidewalk has backfall to the building instead of the fall to the curb and gutter. It was also shown that the rental building to the East of the Rolex had more than the called out 2% cross-fall. Palm trees also in conflict with maintaining 4' ADA pathway between Pepe the Tailers to the Yoga building as well as the proposed sidewalk in front of building #73-941. There also needs to be added ADA ramps at Keddy's and Babaloo's.
Item #28- Inspected sub-contractor Competitive Edge Electric on-site trenching in the South side of the East parking lot for electrical improvements that will be used for lighting in the sidewalks for type B1 lighting fixtures. Crew is trenching from the West towards the East. Inspected crew trenching and setting 1" conduit at 18" below finish surface since not inside the roadway. Proposed lights in the sidewalk will have to beshifted to keep new sidewalk ADA compliant. Per survey, the light poles are in the middle of the sidewalk and will conflict with maintaining a 4' pathwayfor pedestrians on the sidewalk.
Item #20- Time and Material work- Inspected contractor H&H on-site trenching and installing added 1" SCH. 40 CL C-350 Domestic Water Pipeline to building #73-711, which is at the Acupuncture business. Crew is only trenching the lateral section today which completes the added line. Inspected crew trench and install a field measured 197' LF of 1" pipeline. Crew excavated and set the pipe at 30" below finish surface and within the new mainline trench that housed all the rest of the domestic water pipeline service feeds in the area. CVWD standards were 24" minimum coverage from finish surface. Inspected all joints being glued to make sure there is no leaks and proper application for the sections of pipe wasbeing completed.
Item #20- Inspected contractor H&H on-site trenching digging in the areas that was shown in the plans to expose the existing water services to each building in the East parking lot. Crew is digging to expose the existing water services to each building to make they know where the connections will need to take place with the new PVC domestic water pipes installed for the new services. Once the existing lines are exposed, contractor H&H is stubbing the new domestic water pipe up next to the existing line which will make for a quick connection once the time comes for the final connections of the new lines to the existing service lines. Contractor H&H was not able to find the existing services to the West of Sherry Mesa Salon added line, Birkram Yoga meter #9300957-I, and Goldfield Home meter #9681400-I . Inspector was notified by contractor H&H at this time that all the work taking place to locate the existing water service and stubbing up of the new domestic line next to the existing service line was going to be tracked and they want it to be paid under time and material. Inspector notified the Resident Engineer of what contractor H&H was saying and wanting to work to be under time and material. Inspector at this time told contractor H&H that he will tack the time and material that took place and were used but he is not agreeing with this work being a change order or under time and material.
Note: Contractor H&H using cold mix for ramps at this time. Inspector notified contractor H&H and cold mix and high heat ambient temperatures don't go together very well and the cold mix will have a hard time locking up and becoming hard. Crews placed turf grass at building that had complaints about the cold mix. Some of the public not wanting to use the ramps because they do not want to get the bottom of their shoes dirty. Inspector met with the owner of the French Cafe with contractor H&H. Owner wanted contractor H&H to fix the damaged grease trap since I was smelling really bad in the West lot. Inspected contractor H&H remove the broken grade ring and set the lid of the grease trap back in place. Ownerhappy with the fix.
SWPPP- Inspector notified contractor H&H of needing to place cold mix and asphalt material on top of plastic with a linear barrier and a cover.
Inspector also notified H&H of needing to place linear barrier and cover all stock piles in the West parking lot. ContractorH&H needing to load concrete and AC stock piles into dump trucks and have hauled off-site. Inspector notified contractor to have street sweeper on-site to clean up both parking lots since sediment is observed outside of the trenches and also need to clean the parking lots to prevent tracking of sediment and any sediment from leaving the site. Inspector requesting contactor H&H water the parking lots more to prevent dust.
Safety- Inspector notified H&H of needing to maintain caution tape and cones at excavated areas. Also told H&H to make sure pedestrians have access at all times to businesses and to make sure equipment is not blocking ADA ramps. Inspector notified contractor H&H to fill in pot holes in backfill trench areas throughout both the East and West parking lot. Inspector informed contractor to also make sure ADA compliant sidewalk and areas are back in place with the cold mix contractor is using in the sidewalks after removals and sewer cleanouts have been done. Inspector notified contractor H&H of needing to maintain cold mix at each entrance as well as caution tape off all areas outside of the temporary cold mix ramps to keep the public from only using the cold mix ramp areas to prevent anyone from falling in the uneven pavement areas outside of the cold mix ramps.
NIGHTWORK
17.B
Page xv
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix a - saMples
Shift Hours Start 13:30
JOB STAMP:
Report No.
Date the Shift
Began: 9/30/21City of Palm Desert No. 758-14
0Presidents' Plaza East/West
Parking Lot Improvements Project
Picture shows contractor H&H and Inspector found that there is two services off the existing meter at the Acupuncture building.
Picture shows crew trenching and installing pipe for water services add at the Acupuncture building in the West lot.
Federal ID No. N/A
5:00 Stop
THURSDAY
Picture shows contractor H&H and inspector found that the service per plan does not go to any existing service at Goldfield Home.
Picture shows sub-contractor trenching and installing 1" conduit for lighting in the sidewalk along South side of East lot.
Picture shows contractor H&H ran pipe to curb face but damaged curb at Spectacular Shades building for roof drains.
Picture shows contractor H&H installed turf at the entrance of building #73-900.
NIGHTWORK
17.B
Page xvi
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix a - saMples
SAMPLE QUANTITY CALCULATIONS
17.B
Page xvii
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix a - saMples
17.B
Page xviii
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix a - saMples
17.B
Page xix
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix a - saMples
17.B
Page xx
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix a - saMples
17.B
Page xxi
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix a - saMples
17.B
Engineering Trust Into Every Project
Appendix B
Key Staff Resumes
17.B
Page xxiii
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix b - Key staff resuMes
Jason B ennecke, PE, MBA, PMP | Principal-in-Charge
BIOGRAPHY
Bennecke has over 30 years of extensive civil engineering and management experience while working on large transportation projects in different capacities. As a full-time Project Manager at Caltrans District 8 from 2008-2014, he was responsible for successfully delivering and maintaining a project portfolio worth over $500 million, mostly interchange reconstructio n projects in various stages of PA/ED, PS&E, and Construction. He successfully guided ten (10) separate interchange projects in Riverside County through the project development and construction phases. His practical design experience includes design of roa dways, streets, street lighting, drainage channels, drainage structures, storm drains, sanitary sewer, and structural work. He has broad experience in project coordination with local agencies, funding partners, Local Assistance, Caltrans, utility companies, cities, state agencies, and private property owners.
CV
EEdduuccaattiioonn • Master of Business Administration, Corporate Management, CSUSB • BS, Civil Engineering, Cal Poly Pomona
PPrrooffeessssiioonnaall
RReeggiissttrraattiioonnss
• Professional Civil Engineer, CA #58808
• CA General Building Contractor, #921267CA
• Real Estate Broker, Lic #01332170
• Certified Project Management Professional, PMP #1443915 EExxppeerriieennccee • 14 Years with Southstar | 30+ Years in Role BBeenneeffiittss ttoo tthhee PPrroojjeecctt
• Significant experience on large scale paving, highway and bridge construction projects • Significant experience with risk mitigation and constructability reviews • 30 years working with and for Caltrans District 8 in San Bernardino, resulting in extensive knowledge of Caltrans procedures and policies
• Extensive claims resolution experience
PROJECT EXPERIENCE
II--1155//CCaajjaallccoo IInntteerrcchhaannggee CCoorroonnaa Corona, CA – Project Manager
Mr. Bennecke was responsible for guiding this $50 million project which has reconstructed the interchange located on Interstate 15 (I-15) at Cajalco Road from Temescal Canyon Road to Bedford Canyon Road. The $50 million dollar investment included the widening of Cajalco Road from a two-lane bridge to a six-lane overcrossing bridge on a new alignment north of the existing bridge. In addition, the bridge included a striped median, outside shoulders and a sidewalk on the southern side.
Mr. B ennecke was able to successfully deliver this project despite its external challenges such as local mountain fires.
Nonetheless, the project was still delivered ahead of schedule saving the City of Corona unnecessary costs.
SSaann PPaabblloo AAvvee SSttrreeeettssccaappee PPhhaasseess II && IIII PPrroojjeeccttss Palm Desert, CA – Project Manager
As project manager, Mr. Bennecke was responsible for providing project management for these two construction management and inspection services projects. The projects were fully funded with City Funds, however, Mr. Bennecke ensured to document the project construction and progress payments in sufficient detail to comply with Caltrans Construction Manual, the Construction Manual Supplement for Local agency Resident Engineers, the Local Assistance Procedures Manual (LAPM) and the Local Agency Structure Representative Guidelines requirements and as directed by the City Engineer.
LLaa QQuuiinnttaa CCoommpplleettee SSttrreeeettss IImmpprroovveemmeennttss PPrroojjeecctt La Quinta, CA – Project Manager
Mr. Bennecke was responsible for providing project management services for this construction management, inspection, survey, and materials testing project. The project was partially funded with State O nly Active Transportation Funds, and therefore we documented the Project construction and progress payments in sufficient detail to comply with Caltrans Construction Manual and the Local Assistance Procedures Manual (LAPM) requirements and as directed by the City Engineer.
Careful consideration was taken to develop a construction schedule based on the approved Stage Construction plans. The construction staging and schedule was developed to minimize impacts to the businesses and school during the season (November to April) and to minimize detours and closures to keep traffic flowing at all times. As such, the Project was broken down into three phases.
17.B
Page xxiv
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix b - Key staff resuMes
Amr Abuelhassan, MS, PE, QSD |Supervising Resident Engineer
BIOGRAPHY
Mr. Abuelhassan has over 30 years of experience in project management, construction management, and civil engineering. His extensive construction management and administration experience and knowledge provides a solid foundation for the delivery of projects from inception to completion of construction.
Mr. Abuelhassan’s experience includes working for Caltrans District 8 delivering projects on various routes within the District as a Project Manager and as a Resident Engineer. Mr. Abuelhassan’s experience also includes working for the County of San Bernardino Department of Public Works as a Resident Engineer where he performed the duties of construction manager on several successful projects. During his tenure, as Resident Engineer at the County of San Bernardino Department of Public Works, Mr. Abuelhassan delivered the largest transportation construction project in the County’s history, Ft. Irwin Road Widening and Rehabilitation Project.
CV
EEdduuccaattiioonn
• Master of Science, Civil Engineering, California State University, Fullerton, 1997 • Bachelor of Science, Civil Engineering, California State Polytechnic University Pomona, 1991 • Caltrans RE Academy 2001
PPrrooffeessssiioonnaall
RReeggiissttrraattiioonnss
• Professional Engineer, CA #C57817
• Qualified SWPPP Developer (QSD) #23428
EExxppeerriieennccee • 13 Years with Southstar | 30 Years in Role BBeenneeffiittss ttoo tthhee
PPrroojjeecctt
• Former Caltrans Project Manager and Resident Engineer • Has managed multiple public works projects throughout Southern California • Significant experience in Federally Funded Transportation Projects • Experienced Resident Engineer of similar projects
• Expert on roadway, highway, and bridge construction projects • Significant Experience in Delivering Transportation Projects under Caltrans Oversight
PROJECT EXPERIENCE
SSaann PPaabblloo AAvvee SSttrreeeettssccaappee PPhhaassee II PPrroojjeecctt Palm Desert, CA – Resident Engineer
As resident engineer, Mr. Abuelhassan was responsible for providing construction management and inspection services. The project is fully funded with City Funds, however, Mr. Bennecke ensured to document the project construction and progress payments in su fficient detail to comply with Caltrans Construction Manual, the Construction Manual Supplement for Local agency Resident Engineers, the Local Assistance Procedures Manual (LAPM) and the Local Agency Structure Representative Guidelines requirements and as directed by the City Engineer. Mr. Abuelhassan is responsible for ensuring construction activities are continuous and no delay is encountered as a result of field conflicts.
LLaa QQuuiinnttaa CCoommpplleettee SSttrreeeettss IImmpprroovveemmeennttss PPrroojjeecctt La Quinta, CA – Resident Engineer
The Southstar Team le d by Mr. Abuelhassan has been responsible for providing construction management, inspection, survey, and material testing services. He ensured construction activities were continuous and that no delays were encountered as a result of field conflicts. The project was partially funded with State Only Active Transportation Funds, and therefore the Project construction and progress payments were documented in sufficient detail to comply with Caltrans Construction Manual and the Local Assistance Procedures Manual (LAPM) requirements and as directed by the City Engineer. The project was constructed in three phases split into 3 stages each.
SSttaattee RRoouuttee 9911 AAuuxxiilliiaarryy LLaanneess PPrroojjeecctt Riverside, CA – Resident Engineer
Served as the Caltrans resident engineer for this project and was responsible for the construction of five auxiliary lanes on State Route 91 through the City of Riverside. The project included over 100,000 cubic meters of roadway and structure excavation, one million kilograms of reinforcing steel, 10,000 cubic meters of structural concrete and 20,000 cubic meters of Portland cement concrete pavement placed on the project.
17.B
Page xxv
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix b - Key staff resuMes
Philip Hannawi, PE, QSD | Construction Manager/Resident Engineer/Office Engineer BIOGRAPHY Mr. Hannawi is a Professional Civil Engineer in the State of California with over 40 years of experience in project management, municipal civil engineering, and construction management. He has served as construction manager for highways, numerous streets widening and extensions, grade separations, and pavement rehabilitations. His experience also includes design and drafting of several projects involving street widening and extension, grade separations, pavement rehabilitation, sewer, storm drain and airport design.
CV
EEdduuccaattiioonn • MS Civil Engineering – 1984 University of Illinois • Master of Engineering Management – 1988 Northwestern University PPrrooffeessssiioonnaall
RReeggiissttrraattiioonnss
• Professional Engineer Civil No. 44747, CA
• Qualified SWPPP Practitioner (QSP) #23429
EExxppeerriieennccee • 11 Year with Southstar | 44 Years in Role
PROJECT EXPERIENCE
LLaa QQuuiinnttaa CCoommpplleettee SSttrreeeettss PPrroojjeecctt La Quinta, CA - Assistant Resident Engineer/Office Engineer The La Quinta Village is located between Eisenhower Drive to the west, Calle Tampico to the north, Washington Street to the east, and Calle Sinaloa/Avenue 52 to the south. The Project consisted of road diet improvements along the following streets: Calle Tampico from Washington Street to Eisenhower Drive, Eisenhower Drive from just north of Calle Tampico to Calle Sinaloa, Calle Sinaloa/Avenue 52 from Eisenhower Drive to Desert Club Drive. These streets had four lanes of traffic with signalized intersections. To promote a more pedestrian and bicycle friendly atmosphere, the Project reduced the number of through travel lanes from four to two and provided bicycle/golf cart lanes, by way of installing roundabouts at the following five intersections: Calle Tampico at Desert Club Drive, Calle Tampico at Avenida Bermudas, Calle Tampico at Eisenhower Drive, Eisenhower Drive at Avenida Montezuma, Calle Sinaloa/Avenue 52 at Avenida Bermudas. Along Calle Tampico, the Project reduced the roadway width by placing new curb and gutter, landscaping and/or bioretention facilities between the back of new curb and the old back of curb. Along Eisenhower Drive and Calle Sinaloa, the existing curb and gutter at the time remained and the width reduction were done by striping only. Some of Mr. Hannawi’s responsibilities included tracking daily diaries, weekly status reports, labor compliance interviews, certified payrolls, logs for submittals, RFls, CCOs, contingency balances, survey requests, materials testing results correspondence and agreements, progress schedule, Weekly Statement of Working Days (WSWDs), weekly meeting minutes, progress pay estimates and quantities, Lane Closures, Monthly Reports, Public Notices, Permits and environmental agreements, Quality control records, Testing Results.
SSaann PPaabblloo AAvveennuuee PPhhaassee II SSttrreeeettssccaappee IImmpprroovveemmeennttss Palm Desert, CA - Assistant Resident Engineer/Office Engineer The proposed project included the 2,600-foot segment of San Pablo Avenue from Highway 111 to Fred Waring Drive. The project reduced the existing number of lanes through a road diet, which introduced improved bikeway facilities along the corridor, enhanced pedestrian accommodations, new landscaping, beautification of existing community gardens, on- street parking, and a roundabout intersection at San Gorgonio Way. His duties consisted of: Reviewing RE Pending Files, Project History, Background with Designer, assemble staff, prepare project Safety Plan and QA/QC Plan and conduct safety training.
He set up project files using Caltrans Project Development Uniform Filing System, coordinated utility relocations with private owners and complete before issuing the NTP, conduct meetings with affected stakeholders and utility companies, conduct pre-construction meetings with the City, contractor, design engineer, and utilities and agencies.
RRiivveerrssiiddee MMuunniicciippaall AAiirrppoorrtt TTaaxxiiwwaayy PPaavveemmeenntt RReehhaabbiilliittaattiioonn Riverside, CA - Principal Design Engineer
Mr. Hannawi served as Principal Design Engineer for this project. Project included pavement rehabilitation of the taxiway. Scope of work included following FAA requirements and some drainage work where there were problems at several airport hangers.
CCiittyy ooff RRiivveerrssiiddee,, SSttrreeeetteerr AAvveennuuee GGrraaddee SSeeppaarraattiioonn Riverside, CA - Assistant Resident Engineer
Mr. Hannawi served as Assistant Resident Engineer/Office Engineer for this project. The project consisted of construction of a railroad bridge, a highway bridge, utility relocations, extensive earthwork and construction of a storm water pump station.
He was responsible for performing the inspection and compliance monitoring of the Storm Water Pollution Prevention Plans (SWPPP)/Best Management Practices (BMP).
17.B
Page xxvi
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix b - Key staff resuMes
Mike S mith, QSP, CESSWI | Roadway Inspector
BIOGRAPHY
Mr. Smith offers over 15 years of experience providing inspection services for roadway, grade separations, bridge replacements, demolition of existing bridges, and underground and structures construction. He was the lead field inspector for the City of Riverside’s Magnolia Avenue Grade Separation Project, City of Corona’s I-15 Cajalco Interchange Improvements Project, and he is currently leading SBCTA’s SR-60 Archibald Avenue Interchange Improvements Project. His inspection experience includes: observing the installation and testing of underground utilities including sewer, water, electrical, storm drain lines, and associated structures such as manholes, CIDH piles, falsework, bridge structure, catch basins, headwalls, barrier rail, retaining walls, MSE walls, white paving (JPCP), PCC intersections, median islands, curb and gutter, cross-walks and culverts. He is also intimately familiar with Caltrans Construction Manual, Greenbook, SWPPP, ADA requirements, Caltrans Standard Plans and Standard Specifications, and holds extensive knowledge of State of California Construction Safety Orders (CalOSHA) and traffic control practices as specified in the Work Area Traffic Control Handbook (WATCH).
CV
EEdduuccaattiioonn • BA, Liberal Studies, Point Loma University, CA PPrrooffeessssiioonnaall
RReeggiissttrraattiioonnss
• Qualified SWPPP Practitioner (QSP) No. 24130
• Certified Erosion, Sediment, and Storm Water Inspector (CESSWI) No. 3406 • Concrete Testing and Sampling ASTM
• Asphalt Concrete Testing and Sampling
• Environmental Awareness Mitigation
EExxppeerriieennccee • 10 Years with Southstar | 17 Years in Role
PROJECT EXPERIENCE
SSBBCCTTAA,, SSRR--6600 // AArrcchhiibbaalldd AAvveennuuee IInntteerrcchhaannggee IImmpprroovveemmeennttss PPrroojjeecctt Ontario, CA – Lead Construction Inspector
This $15 million project will improve Archibald Avenue between East Oak Hill Drive and Monticello Place at the State Route 60 (SR 60) interchange, located in the City of Ontario in San Bernardino County. The proposed improvements include widening Archibald Avenue to add a northbound left-turn lane to the westbound on-ramp and an additional southbound left-turn lane to the eastbound on-ramp. As lead construction inspector, Mr. Smith has been responsible for construction inspection to ensure all work conforms to the project documents. He performs daily on-site observations of the progress and quality of construction to determine if the work being performed is in general conformance with the contract documents. Some of his assignments included: Paving and subgrade inspection, sub-surface & finish surface drainage inspection, structures and foundation inspection, signing and striping inspection, quantity calculations, checking grade and alignment, construction traffic control and other assignments as deemed necessary for completion of the project.
II--1155//CCaajjaallccoo RRooaadd IInntteerrcchhaannggee IImmpprroovveemmeenntt PPrroojjeecctt Corona, CA – Senior Construction Inspector
Mr. Smith is served as Senior Construction Inspector for this $50 Million pr oject. The project reconstructed the interchange located on Interstate 15 at Cajalco Road in the City of Corona. The proposed improvements will increase the capacity of the overcrossing and ramps in order to reduce congestion and accommodate projected deve lopment and growth in the area. A six-lane overcrossing bridge will be constructed on a new alignment north of the existing bridge. The four existing ramps will be realigned, and one new loop ramp will be constructed, for a total of five new and modified r amps.
SSuunnnnyymmeeaadd BBeeaauuttiiffiiccaattiioonn PPrroojjeecctt PPhhaassee 22 Moreno Valley, CA – Senior Construction Manager Administrator/Inspector Mr. Smith served as Senior CM Administrator/Construction Inspector for this $12 million “makeover” of Sunnymead Blvd.
As part of this revitalization, Moreno Valley’s first commercial area and original Highway 60 beautification improvements along the two-mile stretch from Frederick St. to Perris Blvd. The sections are Frederick St. to Graham St., Graham St. to Heacock St., Heacock St. to Indian St., and Indian St. to Perris Blvd. Planned improvements include new, six -foot wide colored sidewalk (including where sidewalk is currently missing), colored pavement in the center turn lane, colored concrete at intersections and crosswalks, medians at the intersections to improve traffic safety, and planter areas between Fredrick’s Street and Perris Blvd. The project is meant to provide an economic boost to the Boulevard. Mr. Smith’s duties include inspecting traffic control measures to make sure they conform to WATCH Manual and Traffic Control plans; interpreting construction plans and specifications, inspecting installation of PCC Median Nots, Median islands, irrigation, planting paving, striping and PCC intersections including cross-walks, working on as-builts plans; writing daily reports; and maintaining photographic records of construction activities
17.B
Engineering Trust Into Every Project
Appendix C
Forms
17.B
Page xxviii
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
PROPOSER’S SIGNATURE PAGE
By signing this form, the Consultant states that the firm(s) has sufficient staff resources and capability to perform the work contained within this Request for Proposal within the specified timeframe.
PROPOSER:
(Consultant Name)
ADDRESS:
TELEPHONE NUMBER(S):
PRINT NAME:
SIGNATURE:
TITLE: DATE:
SIGNING INSTRUCTIONS TO THE CONSULTANT
This Proposal must have a valid signature above and be delivered as required or it will be considered non-responsive (CCP 1933).
Proposer’s Signature Page to be accompanied by notary certificates attached following this pag e. Note the description of the docume nt on the notary certificate and attach notary certificates immediately following this page.
General Partners must sign on behalf of the partnership.
In the event that the c onsulting firm is a corporation, two (2) corp orate officers having authority from the corporation MUST sign (two (2) signatures total). If the corporation has a corporate resolution stating that one person is authorized to sign on behalf of all officers, attach co rporate resolution immediately following the notary certificates. Corporate Seal may be affixed hereto.
10/24/2022
Southstar Engineering & Consulting, Inc.
1945 Chicago Ave. Suite C-2 Riverside, CA 92507 951-342-3120
Jason Bennecke, PE, MBA, PMP
Executive Vice President/CAO
SOUTHSTAR SIGNATURE PAGE
17.B
Page xxix
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
NON-COLLUSION AFFIDAVIT
Made to: City of Hemet
10/24/[email protected]
Jason Bennecke, PE, MBA, PMP
Southstar Engineering & Consulting, Inc. 951-342-3120
1945 Chicago Ave. Unit C2 Riverside, CA 92507
SOUTHSTAR NON-COLLUSION AFFADAVIT
17.B
Page xxx
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
49 CFR Part 29 - Appendix A
CERTIFICATION REGARDING DEBARMENT, SUSPENSION, AND OTHER
RESPONSIBILITY MATTERS--PRIMARY COVERED TRANSACTIONS
Instructions For Certification
1. By signing and submitting this proposal, the prospective primary participant is providing the certification set out below.
2. The inability of a person to provide the certification required below will not necessarily result in denial of participation in this covered transaction. The prospective participant shall submit an explanation of why it cannot provide the certification set out below. The certification or explanation will be considered in connection with the department or agency's determination whether to enter into this transaction. However, failure of the prospective primary participant to furnish a certification or an explanation shall disqualify such person from participation in this transaction.
3. The certification in this clause is a material representation of fact upon which reliance was placed when the department or agency determined to enter into this transaction. If it is later determined that the prospective primary participant knowingly rendered an erroneous certification, in addition to other remedies available to the Federal Government, the department or agency may terminate this transaction for cause or default.
4. The prospective primary participant shall provide immediate written notice to the department or agency to which this proposal is submitted if at any time the prospective primary participant learns that its certification was erroneous when submitted or has become erroneous by reason of changed circumstances.
5. The terms covered transaction, debarred, suspended, ineligible, lower tier covered transaction, participant, person, primary covered transaction, principal, proposal, and voluntarily excluded, as used in this clause, have the meanings set out in the Definitions and Coverage sections of the rules implementing Executive Order 12549. You may contact the department or agency to which this proposal is being submitted for assistance in obtaining a copy of those regulations.
6. The prospective primary participant agrees by submitting this proposal that, should the proposed covered transaction be entered into, it shall not knowingly enter into any lower tier covered transaction with a person who is proposed for debarment under 48 CFR part 9, subpart 9.4, debarred, suspended, declared ineligible, or voluntarily excluded from participation in this covered transaction, unless authorized by the department or agency entering into this transaction.
SOUTHSTAR DEBARMENT AND SUSPENSION CERTIFICATION
17.B
Page xxxi
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
7. The prospective primary participant further agrees by submitting this proposal that it will include the clause titled ``Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion- Lower Tier Covered Transaction,'' provided by the department or agency entering into this covered transaction, without modification, in all lower tier covered transactions and in all solicitations for lower tier covered transactions.
8. A participant in a covered transaction may rely upon a certification of a prospective participant in a lower tier covered transaction that it is not proposed for debarment under 48 CFR part 9, subpart 9.4, debarred, suspended, ineligible, or voluntarily excluded from the covered transaction, unless it knows that the certification is erroneous. A participant may decide the method and frequency by which it determines the eligibility of its principals. Each participant may, but is not required to, check the List of Parties Excluded from Federal Procurement and Nonprocurement Programs.
9. Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to render in good faith the certification required by this clause. The knowledge and information of a participant is not required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.
10. Except for transactions authorized under paragraph 6 of these instructions, if a participant in a covered transaction knowingly enters into a lower tier covered transaction with a person who is proposed for debarment under 48 CFR part 9, subpart 9.4, suspended, debarred, ineligible, or voluntarily excluded from participation in this transaction, in addition to other remedies available to the Federal Government, the department or agency may terminate this transaction for cause or default.
17.B
Page xxxii
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
CERTIFICATION REGARDING DEBARMENT, SUSPENSION, AND OTHER
RESPONSIBILITY MATTERS--PRIMARY COVERED TRANSACTIONS
(1) The prospective primary participant certifies to the best of its knowledge and belief, that it and its principals:
(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded by any Federal department or agency; (b) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, or receiving stolen property;
(c) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State or local) with commission of any of the offenses enumerated in paragraph (1)(b) of this certification;
(d) Have not within a three-year period preceding this application/proposal had one or more public transactions (Federal, State or local) terminated for cause or default. (2) Where the prospective primary participant is unable to certify to any of the statements in this certification, such prospective participant shall attach an explanation to this proposal. ____________________________________ _______________________________ Signature/Authorized Certifying Official Typed Name and Title ____________________________________ ________________________________ Applicant/Organization Date Signed
Southstar Engineering & Consulting, Inc.
Jason Bennecke, PE, MBA, PMP
- Executive Vice President/CAO
10/24/2022
17.B
Page xxxiii
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
Contractor Information
Legal Entity Name
SOUTHSTAR ENGINEERING & CONSULTING, INC.
Legal Entity Type
Corporation
Status
Active
Registration Number
1000017294
Registration effective date
07/01/22
Registration expiration date
06/30/23
Mailing Address
1945 CHICAGO AVE., UNIT C-2 RIVERSIDE 92507 CA Unit…
Physical Address
1945 CHICAGO AVE., UNIT C-2 RIVERSIDE 92507 CA Unit…
Email Address
[email protected]
Trade Name/DBA
License Number (s)
Registration History
Effective Date Expiration Date
06/22/18 06/30/19
05/10/17 06/30/18
08/11/16 06/30/17
12/10/15 06/30/16
03/30/15 06/30/15
08/08/19 06/30/20
08/05/20 06/30/22
07/01/22 06/30/23
Legal Entity Information
Corporation Entity Number: C2926615
Federal Employment Identification Number: 205648626
President Name: Yvette Kirrin
Vice President Name: Jason Bennecke
Treasurer Name: Amr Abuelhassan
Secretary Name:
CEO Name: Daniel Ciacchella
Agency for Service:
Agent of Service Name: Amr Abuelhassan
Agent of Service Mailing Address: 1945 Chicago Ave, C-2 Riverside 92507-2369 CA United States of America Worker's Compensation
Do you lease employees through Professional Employer Organization (PEO)?: No Please provide your current worker's compensation insurance information below:
PEO InformationPEO
Name
PEO
Phone
PEO
Email
Insured by Carrier
Policy Holder Name: SOUTHSTAR ENGINEERING & CONSULTING, INC.
Insurance Carrier: The Insurance Company of the west Indies Limited Policy Number: WSD 5064219 00
Inception date: 06/09/22
Expiration Date: 06/09/23
1 of 1
DIR REGISTRATION - SOUTHSTAR
17.B
Page xxxiv
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
Contractor Information
Legal Entity Name
RT ENGINEERING & ASSOCIATES, INC.
Legal Entity Type
Corporation
Status
Active
Registration Number
1000020251
Registration effective date
08/04/22
Registration expiration date
06/30/23
Mailing Address
202 E. Airport Dr Ste 140 San Bernardino 92408 CA Unite… Physical Address
1901 1ST AVENUE, SUITE 217G SAN DIEGO 92101 CA Uni…
Email Address
[email protected]
Trade Name/DBA
License Number (s)
PUC:12040001
Other:59264 CA PROF CIVIL ENGINEER
Other:59264
Registration History
Effective Date Expiration Date
06/21/18 06/30/19
06/26/17 06/30/18
08/29/16 06/30/17
07/21/15 06/30/16
04/27/15 06/30/15
10/08/19 06/30/20
07/01/20 06/30/21
07/01/21 06/30/22
08/04/22 06/30/23
Legal Entity Information
Corporation Entity Number:
Federal Employment Identification Number:
President Name:
Vice President Name:
Treasurer Name:
Secretary Name:
CEO Name:
Agency for Service:
Agent of Service Name:
Agent of Service Mailing Address:
C3372623
542110604
Regina Talamantez, PE
Regina Talamantez, PE
Regina Talamantez
202 E. Airport Drive, Suite 140
San Bernardino 92408 CA United States of America
Worker's Compensation
Do you lease employees through Professional Employer Organization (PEO)?:
Please provide your current worker's compensation insurance information below:
PEO InformationPEO
Name
PEO
Phone
PEO
Email
Insured by Carrier
Policy Holder Name:
Insurance Carrier:
Policy Number:
Inception date:
Expiration Date:
No
RT ENGINEERING & ASSOCIATES, INC.
HARTFORD UNDERWRITERS INSURANCE COMPANY
84SBWPF0379
10/12/14
09/30/23
DIR REGISTRATION - RTEA
17.B
Page xxxv
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
Contractor Information
Legal Entity Name
R M A GROUP
Legal Entity Type
Corporation
Status
Active
Registration Number
1000006493
Registration effective date
07/01/22
Registration expiration date
06/30/25
Mailing Address
12130 SANTA MARGARITA COURT RANCHO CUCAMONGA 917…
Physical Address
12130 SANTA MARGARITA COURT RANCHO CUCAMONGA 917…
Email Address
[email protected]
Trade Name/DBA
SiteScan
License Number (s)
Other:GE2362
Registration History
Effective Date Expiration Date
06/18/18 06/30/19
06/22/17 06/30/18
06/22/16 06/30/17
06/11/15 06/30/16
01/22/15 06/30/15
07/01/19 06/30/22
07/01/22 06/30/25
Legal Entity Information
Corporation Entity Number: C0604784
Federal Employment Identification Number: 952657590
President Name: Ed Lyon
Vice President Name:
Treasurer Name:
Secretary Name:
CEO Name:
Agency for Service:
Agent of Service Name:
Agent of Service Mailing Address:
Ed Lyon
12130 Santa Margarita Rancho Cucamonga 91730 CA
United States of America
Worker's Compensation
Do you lease employees through Professional Employer Organization (PEO)?:
Please provide your current worker's compensation insurance information below:
PEO
Phone
PEO
Email
PEO InformationPEO
Name
Insured by Carrier
Policy Holder Name:
Insurance Carrier:
Policy Number:
Inception date:
Expiration Date:
No
R M A GROUP
National Union Fire Insurance Company of
Pittsburg, PA
WC 014-12-2658
03/01/22
03/01/23
DIR REGISTRATION - RMA GROUP
17.B
Page xxxvi
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
Local Assistance Procedures Manual Exhibit 10-O1
Consultant Proposal DBE Commitment
EXHIBIT 10-O1 CONSULTANT PROPOSAL DBE COMMITMENT
1. Local Agency: 2. Contract DBE Goal:
3. Project Description:
4. Project Location:
5. Consultant's Name: 6. Prime Certified DBE:
7. Description of Work, Service, or Materials
Supplied
8. DBE
Certification
Number
10. DBE %
%
Local Agency to Complete this Section
17. Local Agency Contract Number:
18. Federal-Aid Project Number:
19. Proposed Contract Execution Date:
20. Consultant’s Ranking after Evaluation: __________________________ Local Agency certifies that all DBE certifications are valid and information on this form is complete and accurate.
9. DBE Contact Information
11. TOTAL CLAIMED DBE PARTICIPATION
IMPORTANT: Identify all DBE firms being claimed for credit, regardless of tier. Written confirmation of each listed DBE is required.
12. Preparer's Signature 13. Date
14. Preparer's Name 15. Phone
16. Preparer's Title
DISTRIBUTION: Original – Included with consultant’s proposal to local agency.
ADA Notice: For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) 654-6410 or TDD (916) 654- 3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento, CA 95814.
LPP 18-01 Page 1 of 2
January 2019
City of Hemet 15%
Hemet Valley Bikeway Project - CIP 5696 Federal Project No. 5186(018) Hemet, CA
Southstar Engineering & Consulting, Inc.
Utilities Inspection, Electrical Inspection & Labor Compliance CUCP 40430 RT Engineering & Associates, Inc. 15 1901 1st Ave. Suite 217 San Diego, CA 92101
909-855-1807
10/24/2022
Jason Bennecke 951-342-3120
Exec. Vice President
15 Reset Form
SOUTHSTAR EXHIBIT 10-O1
17.B
Page xxxvii
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
DBE CERTIFICATION - RTEA
17.B
Page xxxviii
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
Local Assistance Procedures Manual Exhibit 15-H
Proposer/Contractor Good Faith Effort
EXHIBIT 15-H: PROPOSER/CONTRACTOR GOOD FAITH EFFORTS
Cost Proposal Due Date ___________________ PE/CE
Federal-aid Project No(s). _____________________ Bid Opening Date ___________________ CON The established a Disadvantaged Business Enterprise (DBE) goal of ______ for this contract. The information provided herein shows the required good faith efforts to meet or exceed the DBE contract goal.
Proposers or bidders submit the following information to document their good faith efforts within five (5) calendar days from cost proposal due date or bid opening. Proposers and bidders are recommended to submit the following information even if the Exhibit 10-O1: Consultant Proposal DBE Commitments or Exhibit 15-G:
Construction Contract DBE Commitment indicate that the proposer or bidder has met the DBE goal. This form protects the proposer’s or bidder’s eligibility for award of the contract if the administering agency determines that the bidder failed to meet the goal for various reasons, e.g., a DBE firm was not certified at bid opening, or the bidder made a mathematical error.
The following items are listed in the Section entitled “Submission of DBE Commitment” of the Special Provisions, please attach additional sheets as needed:
A. The names and dates of each publication in which a request for DBE participation for this project was placed by the bidder (please attach copies of advertisements or proofs of publication):
Publications Dates of Advertisement
B. The names and dates of written notices sent to certified DBEs soliciting bids for this project and the dates and methods used for following up initial solicitations to determine with certainty whether the DBEs were interested (please attach copies of solicitations, telephone records, fax confirmations, etc.):
Names of DBEs Solicited Date of Initial Solicitation Follow Up Methods and Dates
May 2020
10/24/2022
5186(018) 10/03/2022
City of Hemet
15.00%
N/A
Southstar has teamed with a DBE certified subconsultant to meet the 15% DBE goal.
N/A
Southstar has teamed with a
DBE certified subconsultant
to meet the 15% DBE goal.
SOUTHSTAR - EXHIBIT 15-H
17.B
Page xxxix
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
Local Assistance Procedures Manual Exhibit 15-H
Proposer/Contractor Good Faith Effort
C. The items of work made available to DBE firms including those unbundled contract work items into economically feasible units to facilitate DBE participation. It is the bidder's responsibility to demonstrate that sufficient work to facilitate DBE participation in order to meet or exceed the DBE contract goal.
Items of Proposer or Bidder Breakdown of Amount Percentage Work Normally Performs Item Items ($) Of
(Y/N) Contract
D. The names, addresses and phone numbers of rejected DBE firms, the reasons for the bidder's rejection of the DBEs, the firms selected for that work (please attach copies of quotes from the firms involved), and the price difference for each DBE if the selected firm is not a DBE:
Names, addresses and phone numbers of rejected DBEs and the reasons for the bidder's rejection of the DBEs:
Names, addresses and phone numbers of firms selected for the work above:
E. Efforts (e.g. in advertisements and solicitations) made to assist interested DBEs in obtaining information related to the plans, specifications and requirements for the work which was provided to DBEs:
May 2020
Pick
Yes
0.00%N/A
0.00%Pick
Yes
0.00%
Pick
Yes
0.00%
Pick
Yes
N/A - There were no rejected firms because Southstar has teamed with a DBE certified subconsultant to meet the 15% DBE goal.
RT Engineering & Associates - 1901 1st Ave. Suite 217 San Diego, CA 92101 909-855-1807 N/A - Southstar has teamed with a DBE certified subconsultant to meet the 15% DBE goal.
17.B
Page xl
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
Local Assistance Procedures Manual Exhibit 15-H
Proposer/Contractor Good Faith Effort
F. Efforts ( e.g. in advertisements and solicitations) made to assist interested DBEs in obtaining bonding, lines of credit or insurance, necessary equipment, supplies, materials, or related assistance or services, excluding supplies and equipment the DBE subcontractor purchases or leases from the prime contractor or its affiliate:
G. The names of agencies, organizations or groups contacted to provide assistance in contacting, recruiting and using DBE firms (please attach copies of requests to agencies and any responses received, i.e., lists, Internet page download, etc.):
Name of Agency/Organization Method/Date of Contact Results H. Any additional data to support a demonstration of good faith efforts:
May 2020
N/A
Southstar has teamed with a
DBE certified subconsultant
to meet the 15% DBE goal.
N/A - Southstar has teamed with a DBE certified subconsultant to meet the 15% DBE goal.
N/A - Southstar has teamed with a DBE certified subconsultant to meet the 15% DBE goal.
17.B
Page xli
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
Local Assistance Procedures Manual EXHBIT 10-Q
Disclosure of Lobbying Activities
EXHIBIT 10-Q D ISCLOSURE OF LOBBYING ACTIVITIES
COMPLETE THIS FORM TO DISCLOSE LOBBYING ACTIVITIES PURSUANT TO 31 U.S.C. 1352
1. Type of Federal Action: 2. Status of Federal Action: 3. Report Type:
a. contract a. bid/offer/application a. initial
b. grant b. initial award b. material change
c. cooperative agreement c. post -award
d. loan For Material Change Only:
e. loan guarantee year ____ quarter _________
f. loan insurance date of last report __________
4. Name and Address of Reporting Entity 5. If Reporting Entity in No. 4 is Subawardee, Enter Name and Address of Prime:
Prime Subawardee
Tier _______ , if known
Congressional District, if known Congressional District, if known
6. Federal Department/Agency: 7. Federal Program Name/Description:
CFDA Number, if applicable ____________________
8. Federal Action Number, if known: 9. Award Amount, if known:
10. Name and Address of Lobby Entity 11. Individuals Performing Services (If individual, last name, first name, MI) (including address if different from No. 10) (last name, first name, MI)
(attach Continuation Sheet(s) if necessary)
12. Amount of Payment (check all that apply) 14. Type of Payment (check all that apply) $ _____________ actual planned a. retainer
b. one -time fee
13. Form of Payment (check all that apply): c. commission a. cash d. contingent fee
b. in -kind; specify: nature _______________ e deferred Value _____________ f. other, specify _________________________
15. Brief Description of Services Performed or to be performed and Date(s) of Service, including officer(s), employee(s), or member(s) contacted, for Payment Indicated in Item 12:
(attach Continuation Sheet(s) if necessary)
16. Continuation Sheet(s) attached: Yes No
17. Information requested through this form is authorized by Title 31 U.S.C. Section 1352. This disclosure of lobbying reliance was placed by the tier above when his transaction was made or entered into. This disclosure is required pursuant to 31 U.S.C. 1352. This information will be reported to Congress
semiannually and will be available for public inspection. Any person who fails to file the required disclosure shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.
Signature: ________________________________________
Print Name: _______________________________________
Title: ____________________________________________
Telephone No.: ____________________ Date:___________
Authorized for Local Reproduction
Federal Use Only: Standard Form - LLL
Standard Form LLL Rev. 04-28-06
Distribution: Orig- Local Agency Project Files
LPP 13-01 May 8, 2013
NOT APPLICABLE
Jason Bennecke
Executive Vice President/CAO
951-342-3120 10/24/22
/uni2714
SOUTHSTAR - EXHIBIT 10-Q
17.B
Page xlii
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
Local Assistance Procedures Manual EXHBIT 10-Q
Disclosure of Lobbying Activities
EXHIBIT 10-Q D ISCLOSURE OF LOBBYING ACTIVITIES
COMPLETE THIS FORM TO DISCLOSE LOBBYING ACTIVITIES PURSUANT TO 31 U.S.C. 1352
1. Type of Federal Action: 2. Status of Federal Action: 3. Report Type:
a. contract a. bid/offer/application a. initial
b. grant b. initial award b. material change
c. cooperative agreement c. post -award
d. loan For Material Change Only:
e. loan guarantee year ____ quarter _________
f. loan insurance date of last report __________
4. Name and Address of Reporting Entity 5. If Reporting Entity in No. 4 is Subawardee, Enter Name and Address of Prime:
Prime Subawardee
Tier _______ , if known
Congressional District, if known Congressional District, if known
6. Federal Department/Agency: 7. Federal Program Name/Description:
CFDA Number, if applicable ____________________
8. Federal Action Number, if known: 9. Award Amount, if known:
10. Name and Address of Lobby Entity 11. Individuals Performing Services (If individual, last name, first name, MI) (including address if different from No. 10) (last name, first name, MI)
(attach Continuation Sheet(s) if necessary)
12. Amount of Payment (check all that apply) 14. Type of Payment (check all that apply) $ _____________ actual planned a. retainer
b. one -time fee
13. Form of Payment (check all that apply): c. commission a. cash d. contingent fee
b. in -kind; specify: nature _______________ e deferred Value _____________ f. other, specify _________________________
15. Brief Description of Services Performed or to be performed and Date(s) of Service, including officer(s), employee(s), or member(s) contacted, for Payment Indicated in Item 12:
(attach Continuation Sheet(s) if necessary)
16. Continuation Sheet(s) attached: Yes No
17. Information requested through this form is authorized by Title 31 U.S.C. Section 1352. This disclosure of lobbying reliance was placed by the tier above when his transaction was made or entered into. This disclosure is required pursuant to 31 U.S.C. 1352. This information will be reported to Congress
semiannually and will be available for public inspection. Any person who fails to file the required disclosure shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.
Signature: ________________________________________
Print Name: _______________________________________
Title: ____________________________________________
Telephone No.: ____________________ Date:___________
Authorized for Local Reproduction
Federal Use Only: Standard Form - LLL
Standard Form LLL Rev. 04-28-06
Distribution: Orig- Local Agency Project Files
LPP 13-01 May 8, 2013
N/A N/A N/A
N/A
N/A
N/A
N/A
N/AN/A
N/A N/A
N/A
N/A
N/A
N/A
Regina Talamantez, PE
President / CEO
909-855-1807 10/17/2022
NOT APPLICABLE
/uni2714
RTEA - EXHIBIT 10-Q
17.B
Page xliii
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
Local Assistance Procedures Manual EXHBIT 10-Q
Disclosure of Lobbying Activities
EXHIBIT 10-Q D ISCLOSURE OF LOBBYING ACTIVITIES
COMPLETE THIS FORM TO DISCLOSE LOBBYING ACTIVITIES PURSUANT TO 31 U.S.C. 1352
1. Type of Federal Action: 2. Status of Federal Action: 3. Report Type:
a. contract a. bid/offer/application a. initial
b. grant b. initial award b. material change
c. cooperative agreement c. post -award
d. loan For Material Change Only:
e. loan guarantee year ____ quarter _________
f. loan insurance date of last report __________
4. Name and Address of Reporting Entity 5. If Reporting Entity in No. 4 is Subawardee, Enter Name and Address of Prime:
Prime Subawardee
Tier _______ , if known
Congressional District, if known Congressional District, if known
6. Federal Department/Agency: 7. Federal Program Name/Description:
CFDA Number, if applicable ____________________
8. Federal Action Number, if known: 9. Award Amount, if known:
10. Name and Address of Lobby Entity 11. Individuals Performing Services (If individual, last name, first name, MI) (including address if different from No. 10) (last name, first name, MI)
(attach Continuation Sheet(s) if necessary)
12. Amount of Payment (check all that apply) 14. Type of Payment (check all that apply) $ _____________ actual planned a. retainer
b. one -time fee
13. Form of Payment (check all that apply): c. commission a. cash d. contingent fee
b. in -kind; specify: nature _______________ e deferred Value _____________ f. other, specify _________________________
15. Brief Description of Services Performed or to be performed and Date(s) of Service, including officer(s), employee(s), or member(s) contacted, for Payment Indicated in Item 12:
(attach Continuation Sheet(s) if necessary)
16. Continuation Sheet(s) attached: Yes No
17. Information requested through this form is authorized by Title 31 U.S.C. Section 1352. This disclosure of lobbying reliance was placed by the tier above when his transaction was made or entered into. This disclosure is required pursuant to 31 U.S.C. 1352. This information will be reported to Congress
semiannually and will be available for public inspection. Any person who fails to file the required disclosure shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.
Signature: ________________________________________
Print Name: _______________________________________
Title: ____________________________________________
Telephone No.: ____________________ Date:___________
Authorized for Local Reproduction
Federal Use Only: Standard Form - LLL
Standard Form LLL Rev. 04-28-06
Distribution: Orig- Local Agency Project Files
LPP 13-01 May 8, 2013
Slawek Dymerski, PE GE
Vice President
909.989.1751 10/19/2022
NOT APPLICABLE
RMA - EXHIBIT 10-Q
17.B
Page xliv
City of Hemet - Proposal for CM and Inspection Services Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) appendix C - forMs
October 20, 2022
Noah Rau, PE
Public Works Director/City Engineer
City of Hemet - Engineering Department
445 E. Florida Avenue
Hemet, CA 95243
Subject: Non-discrimination Statement – City of Hemet | Construction Management and Inspection Services for Hemet Valley Bikeway Project CIP 5696 - Federal Project No. 5186(018) Dear Mr. Rau,
Due to the fact that Southstar Engineering & Consulting, Inc. (Southstar) has less than 50 employees, we are exempt from the Non-discrimination Statement requirement for this RFP.
Thank you for the opportunity to participate on your team for this project. Please contact me at 951-342-3120 or [email protected] if you any questions or need additional information.
Sincerely,
Jason Bennecke, PE, MBA, PMP
Executive Vice President
SOUTHSTAR AFFIRMATIVE ACTION PROGRAM
17.B
ConstruCtion ManageMent and inspeCtion
serviCes
FOR THE
City of Hemet
CITYWIDE SEWER MAIN REPLACEMENT AND RE-LINING
CIP 5653B
1945 Chicago Avenue, Suite C-2
Riverside, CA 92507
951.342.3120
southstareng.com
WORK PROPOSAL FOR: JUNE 7, 2022
1945 Chicago Avenue, Suite C-2
Riverside, CA 92507
951.342.3120
southstareng.com
1945 Chicago Avenue, Suite C-2
Riverside, CA 92507
951.342.3120
southstareng.com
17.B
October 24, 2022
Noah Rau, P.E.
Public Works Director/City Engineer
City of Hemet, Engineering Department
445 E. Florida Avenue
Hemet, CA 95243
Subject: Willdan Engineering Technical Proposal for CM and Inspection Services for Hemet Valley Bikeway
Dear Noah Rau:
Willdan Engineering (Willdan) is especially qualified to provide construction management and construction observation services for the City of Hemet’s Valley Bikeway Project. Our firm has 58 years of experience providing similar services to client cities and districts throughout California.
Our staff is exceptionally qualified and experienced in providing professional construction management and observation services for street improvement projects. The following are just a number of advantages Willdan brings to the City:
Bikeway Project Experience. Willdan’s experience and corresponding reputation for reliable service, quality workmanship, use of good judgment, fair and equitable treatment, and adherence to our corporate integrity are foremost in the Project and Construction Management industry.
We are currently working on a federally-funded bikeway and street improvement project for the City of La Canada Flintridge and San Fernando. We have previously worked on a Federally Funded bikeway and street improvement project for the City of Long Beach. Our experience with these types of projects makes us particularly strong as a partner on this important endeavor.
Federal Project Expertise. Willdan has extensive experience working with federal-funded projects. Although each project may encompass different components and requirements, the general process remains the same – following the Greenbook and Caltrans Local Assistance Procedures Manual (LAPM). Over 28 years ago, Willdan adopted Caltrans' Construction Manual (LAPM) as our in-house quality standard and have incorporated Caltrans' prescribed standards and procedures into our everyday inspection routine.
Willdan can be contacted at the following address:
Willdan Engineering
13191
Crossroads Parkway North, Suite 405, Industry, CA 91746 Ch
ris Baca, RCI, CESSWI
Director of CM and Inspection
562.364.8198 | [email protected]
Duration: Our proposal terms shall remain in effect for ninety (90) days following the date the proposal submittal is due.
Affirmative Action Plan: Willdan Group, Inc., (WGI) recognizes the diversity in our society and places high value on the positive effects gained from maintaining an equally diverse workplace. On an ongoing basis, the company monitors its policies and practices to ensure that the workplace is a supportive environment for all of its employees, affiliates, and clients. WGI believes that all persons are entitled to equal
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
2 employment opportunity and does not discriminate against employees or applicants during any phase of the employer-employee relationship. Employees who find that a disability interferes with the successful completion of their performance are encouraged to request accommodation through their managers or through Human Resources.
DIR Registration: Willdan Engineering has an active DIR Registration Number 1000033392.
Conflict of Interest: Willdan is unaware of any conflict or potential conflict of interest that could occur due to individual or organizational activities occurring with the City of Hemet.
Standard Agreement: Willdan Engineering’s attorney has reviewed the sample agreement and accepts the terms and conditions contained in the sample Consultant Services Agreement.
Debarment and Suspension Certification: Willdan Engineering, to our knowledge, has never been debarred. We will furnish a completed Debarment and Suspension Certification upon request.
Addendums: Willdan Engineering is in receipt of Addendum No. 1 dated October 4, 2022, Addendum No. 2 dated October 5, 2022, and Addendum No. 3 dated October 17, 2022.
We are confident that our construction engineering services, coupled with our recent City of Hemet experience, provide the best advantage for the City as you take on this important project. If there are any questions regarding this submittal or our qualifications, please contact me at the above mentioned information.
Respectfully submitted,
WILLDAN ENGINEERING
Chris Baca, RCI, CESSWI
Director of Construction Management and Inspection Se rvices
910005/WW.00.40/P22-339_23842
17.B
City of Hemet
H
emet Valley Bikeway
CM Services
3 1. Corporate Profile
Willdan Engineering, a California corporation since 1964, is a subsidiary of Willdan Group, Inc., a publicly-traded Delaware corporation. Services are provided to nationwide clientele through our subsidiary firms – Willdan Engineering, Willdan Energy Solutions, and Willdan Financial Services – that offer a portfolio of diversified capabilities. Willdan provides civil, special district, and structural engineering; planning; financial and economic consulting; geology and geotechnical engineering; environmental health and safety; and energy efficiency solutions services. Willdan specializes in solutions tailored to the un
ique needs of municipalities and other local government agencies.
Se
rvices range from full-time, in-house staffing to interim or part-time assistance on a project-by-project basis.
Management Structure
Willdan’s legal name is Willdan Engineering and is a subsidiary of Willdan Group, Inc. which previously w
ent by the name of Willdan Associates. Willdan Engineering, a California corporation since 1964, is a subsidiary of Willdan Group, Inc., a publicly traded Delaware corporation. Willdan Group, Inc. holds 100% of the shares of Willdan Engineering.
Willdan Engineering Slate of Officers are as follows:
Thomas D. Brisbin .................................................. C hairman of the Board Michael A. Bieber .................................................. P resident Vanessa Muñoz..................................................... . President of Willdan Engineering Creighton Early .................................................... .. Chief Financial Officer, Treasurer Kate Nguyen .................................................... ...... Secretary Cathleen D. Steele ................................................. As sistant Secretary
A project specific organizational chart will be included in the Project Team section of this proposal.
Willdan's staffing resources have grown from 637 in 2014 to over 1,350 employees in 56 offices. The diversity of our staff's experience combines the strength of our local personnel with experts nationwide.
Our local office is located at 13191 Crossroads Parkway, North Ste 405, Industry, CA 91746 and houses an estimated 42 employees.
Willdan Engineering does not hold controlling or financial interests in any other organization.
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
4 Construction Engineering Services
Willdan provides expertise in all areas of project and
c
onstruction management, construction
administration, construction inspection and
observation, geotechnical engineering and material
testing, grant funding administration and compliance,
labor compliance, and community relations. We
specialize in partnering with clients to maintain good
community relations with residents and businesses
affected by construction.
Our resident engineers, construction managers,
construction observers, geotechnical engineers, labor
compliance officers, and support staff offer reliable
service, quality workmanship, use of good judgment,
fair and equitable treatment, and adherence to our
corporate integrity.
These experienced team members identify and correct
discrepancies, ambiguities, omissions, or conflicts in
plans, specifications, and bid schedules that might
generate misinterpretation and/or lead to agency and
contractor disagreements.
Our professionals are adept at anticipating issues
before they arise through continual review of project
plans, specifications, contractors’ schedules, and
contract documents. Potential problems are brought to
the attention of the City's Project Manager and/or the
contractor, along with constructive recommendations
for solutions, so that costly delays and negative impacts to the public and the project are avoided.
Willdan will be the City’s single point of
co
ntact and be the responsible party
representing the City with the
Contractor.
WILLDAN ENGINEERING
at a glance
LOCAL OFFICE
650 E. Hospitality Lane, Suite 400
San Bernardino, CA 92408-3586
Tel: 909.386.0200 | Fax: 909.888.5107
Email: [email protected]
CONSTRUCTION ENGINEERING SERVICES
Construction Management
Resident Engineering
Construction Administration
Construction Inspection
Public Outreach
Bidding Assistance
Claims Review and Investigation
Labor Compliance
Grant Administration
Material Testing and Inspection
EXPERTISE
58 Years of Construction Management
Experience
Federally Funded Projects
Over 100 Successful Caltrans Audits
LAPM Adopted as part of our internal
QA/QC
RESOURCES
55+ offices across 25+ States
Complete Construction Management
Services In-House
Key Staff with a collective 160 years’
experience
Pool of 40+ Inspectors to assist the City
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
5 2. Statement of Qualifications
Willdan is thoroughly familiar with regulatory agency permitting requirements and environmental, design, and construction procedures and requirements for capital improvement and private land development projects. Although each project may encompass different components and requirements, the general process remains the same – following the Greenbook and Caltrans Local Assistance Procedures Manual (LAPM). Over 28 years ago, Willdan adopted Caltrans' Construction Manual (LAPM) as our in-house
quality standard and have incorporated Caltrans' prescribed standards and procedures into our everyday inspection routine.
In addition to our vast knowledge of LAPM guidelines, Willdan, also, has a deep understanding of Federal, State, and Local guidelines. The chart below illustrates our team’s knowledge in these types of funding sources.
W
illdan has provided construction management services to an extensive number of federal-funded projects such as:
City of San Fernando - Pacoima Wash Bikeway/Pedestrian Path, Phase I, Federal Project No. ATPL- 5202(020)
City of La Cañada Flintridge - Foothill Boulevard Link Bikeway and Pedestrian Greenbelt Project, Federal-Aid Project No. CML-547(021)
City of Long Beach – Third Street Broadway and Cycle Track Improvements City of Ridgecrest – Dolphin Avenue Improvements, CML-5385(064)
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
6 3. Relevant Experience
City of San Fernando
117 Macneil Street, San Fernando, CA 91340
The City of San Fernando’s Pacoima Wash Bikeway and Pedestrian Path Federal Project No. ATPL- 5202(020) Job No. 7615, Plan No. P-737, is a project that consists of a 12-foot wide, 1.34-mile-long Class 1 asphalt concrete bikeway within the Pacoima Wash, constructing ramps, retaining wall, installing fence, guardrail, prefabricated bridge, lighting, rectangular rapid flashing beacons, striping, markings, signage, bollards, and miscellaneous appurtenant work. The cost of this project is estimated at $4,319,140.00 and expected to take 340 working days to complete.
City of La Cañada Flintridge
One Civic Center Drive, La Cañada Flintridge, CA 91011
The City of La Cañada Flintridge’s Foothill Boulevard Link Bikeway and Pedestrian Greenbelt Project, F
ederal-Aid Project No. CML-547(021) consists of the construction of approximately a half mile Class I bicycle and pedestrian path, and two miles of Class II bike lane and bicycle amenities; raised medians; a bus stop; cold milling existing pavement and re-paving with Asphalt Rubber Hot Mix (ARHM); removal and installation of traffic striping and raised pavement marking; replacement of curb and gutter and other drainage improvements; traffic signal improvements to include new equipment, bicycle signal detection, and bicycle/pedestrian push buttons; street lighting; illuminated street name sign; and streetscape beautification with narrowed travel lanes to enhance bike and pedestrian mobility and safety. The project is being funded by several funding streams: federal – CMAQ and STP-L, Metro – Measure R, State and Local funds.
Service Dates Key Personnel
2 022 – Present
Mike Bustos
J ane Freij
Amanda Perez
Lani Alfonso
Specific Role
Construction Management
I nspection
Labor Compliance
Materials Testing
Federal Funding Admin
Service Dates Key Personnel
2 021 – Present
Mike Bustos
J ane Freij
Amanda Perez
Lani Alfonso
Specific Role
Construction Management
I nspection
Labor Compliance
Materials Testing – DBE Sub
Federal Funding Admin
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
7 City of Long Beach
411 W. Ocean Blvd., Long Beach, CA 90802
The City of Long Beach’s 3 rd Street and Broadway Cycle Track Improvements Project consisted of ADA s
idewalk improvements and traffic calming measures for traffic exiting the I-710 to make neighborhood streets safer for pedestrians and bicyclists. The project ran along Broadway and 3 rd Streets, east of the I
nterstate 710 and west of Alamitos Avenue.
City of Ridgecrest
100 W California Ave, Ridgecrest, CA 93555
The City of Ridgecrest’s Dolphin Avenue Improvements, CML-5385(064) consists of paving dirt roadway, in
cluding hot mix asphalt, arch culvert and headwall installation, and striping along Dolphin Avenue between China Lake Boulevard and College Heights Boulevard.
Service Dates Key Personnel
2 019 – 2019
Chris Baca
A manda Perez
Specific Role
Construction Management
I nspection
Public Outreach
Service Dates Key Personnel
2 020 – 2020
Mike Bustos
J ane Freij
Amanda Perez
Lani Alfonso
Specific Role
Construction Management
I nspection
Labor Compliance
Materials Testing – DBE Sub
Federal Funding Admin
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
8 4. References
5. Project Team
W
illdan offers the City of Hemet a highly qualified team of professionals with the technical qualifications and diverse capabilities necessary to undertake construction management services for the proposed Hemet Valley Bikeway project. Willdan understands that key personnel assigned on projects shall not be reassigned without prior written approval from the City.
Brief qualifications have been provided for our team on the following page. Resumes for our team members have been provided in the appendix of this proposal.
Christina Curiel
P
ublic Works
Project Manager
626.812.5247
Willdan Engineering
ju
st sucessfully
completely a federal
audit for one of the
City's projects.
City of
A
zusa
Travis Reed
P
ublic Works
Director
661.478.1965
Willdan Engineering
h
as been a trusted
consultant for the City
of Ridgecrest and has
worked extensively
with the City for over
10 years.
City of
R
idgecrest
Onofre Ramirez,
P
.E.
Senior Civil
Engineer
562.570.6183
Willdan Engineering
h
as been a trusted
consultant for the City
of Long Beach and has
worked extensively
with the City for over
15 years.
City of
L
ong
Beach
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
9 Project Team Identification
Name and Role
Relevant Certifications
Construction Management
Mike Bustos, PE, ENV SP
Project Manager/ Resident
Engineer
23 Years’ Experience
BS, Civil Engineering, California Polytechnic State U niversity, San Luis Obispo
Caltrans Resident Engineer Academy Civil Engineer, Ca lifornia No. 73173
Envision Sustainability Professional, Institute for Su stainable Infrastructure
Joe Putrino
Construction Manager
34 Years’ Experience
Uniform Building Code, Fire Code, and ADA Codes, Berge n Community College
Construction Management, Architectural Drafting, and Blueprint Reading Courses
Certified Building Inspector, International Code Coun cil Certified Plumbing Inspector, International Code Coun cil Certified Mechanical Inspector, International Code Co uncil Contractor License Class A and B, No. 636747
Public Works Observation
Mike Paieri
Public Works Observer
38 Years’ Experience
Possesses excellent communication and leadership skills and works effectively with engineers, design teams, client representatives, contractors, managers and other public works personnel. Works jointly with the client to review job progress and address outstanding issues to provide the highest level of service to clients and ensure project success.
Labor Compliance
Jane Freij
Labor Compliance Manager
30 Years’ Experience
BA, Linguistics, University of Kansas
Attorney Assistant Training Program, Litigation/ Corp orations, University of California, Los Angeles
Amanda Perez
Labor Compliance Specialist
13 Years’ Experience
AS, Human Resources Management, Mount San Antonio Colle ge AS, Business Administration, Mount San Antonio College Certificate of Achievement, Business Management I-III Certificate of Achievement, Human Resources Managemen t I-III Certificate of Achievement, International Business I
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
10 Trusted Subconsultant
Established in 2017, Sierra Geotech offers a full scope of geotechnical c
onsulting services, ranging from site reconnaissance and subsurface explorations to detailed geotechnical engineering design, geotechnical report preparation, materials testing and special inspections during construction. We believe smart and economical geotechnical solutions help projects break ground successfully and help bring project visions to life.
From our headquarters in Rocklin, California, we serve several public agencies in surrounding counties. Using remote and field-based mapping and investigation techniques, we gather geotechnical data that help our clients plan, design, and construct many types of public infrastructure, such as roads, bridges, buildings, and water conveyance facilities.
Our strong focus on engineering geology and geotechnical services is complemented by our environmental services including Phase I & II Environmental Site Assessments, Aerially Deposited Lead (ADL) and Asbestos Containing Material (ACM) studies.
Trusted Subconsultant
Sierra Geotech is a certified
DBE and DVBE. Willdan has
worked on a number of
projects with Sierra Geotech
which has become a trusted
Subconsultant.
DBE: #46066, DVBE: 2006414
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
11 6. Description of Services
Willdan’s reputation for providing construction management a
nd observation services is well known within the construction industry. Our staff possesses the required registrations and certifications to provide comprehensive support to its clients.
We have the capability to work on any type of street
improvement and bike lane enhancement project. Willdan understands the City is seeking a remotely-located
Construction Manager/Project Engineer and one full-time construction observer to perform observation services for the projects. Willdan understands all documentation will be controlled utilizing VPM.
Willdan understands the project for the Hemet Bike improvement program constructs bicycle improvements along a four-mile route that extends from the northern City limit to a new transportation mobility station located along the NMTP Salt Creek Corridor. The project will provide a needed connection to activity centers within the City. Project elements include Class II and III facilities, bicycle detection, bike boxes, bike lockers, and bike repair stations. A transportation mobility station provides bicycle staging areas and linkages to regional trails. Other proposed improvements include pavement rehabilitation, street widening, improved signage, lane striping, curb, gutter, sidewalk, and ADA ramps. Missing sidewalks, faded striping, inadequate signage, and an overall lack of amenities currently discourage active transportation as a mobility option.
Project Approach
Willdan provides expertise in all areas of construction management, inspection, labor compliance, grant a
dministration, as well as community relations to residents and businesses affected by construction. Our experienced team members serve as construction managers, resident engineers, and inspectors and provide significant insight for identifying and correcting discrepancies, ambiguities, omissions, or conflicts in contract documents that could generate misinterpretation and/or disagreements between the City and the contractor.
Willdan has experience in managing projects that span heavily used, congested roadways, as well as low- volume residential streets, and has experience in best practices to avoid potential conflicts and avoid or mitigate any hazards during construction. Our goal is to anticipate or diminish potential problems before they arise through continual review of project plans, specifications, contractor’s schedule, and other contract documents.
Our team is adept at:
Anticipating job site problems
Calling job site problems to the project manager’s and/or c
ontractor’s attention
Offering constructive recommendations and achieving cooperation f
rom the contractor
Dealing with issues in a professional, straightforward fashion Addressing concerns of the public
Our approach to issue resolution is to:
Obtain and document the facts surrounding the issue
Develop reasonable solutions in conjunction with the contractor a
nd City project manager
Respond quickly and effectively so that job progress and quality do n
ot suffer
Through close communication with the City’s project staff, timely corrective action is taken to alleviate potential adverse impacts of work progress, costly change orders, and construction claims.
Basic Principles to Project Approach
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
12 Willdan’s staff reviewed the plans and specifications for the project and has determined challenges the City may face on their upcoming projects along with Willdan’s approach and solution to these challenges.
Challenges and Solutions
Challenge 1
Maintain ingress
a
nd egress to
affected school
driveways
Willdan’s proposed inspector will work closely with the Contractor to ensure maximum access is always maintained. In addition, the inspector will make regular visits to the affected schools to coordinate vital deliveries.
Challenge 2
Traffic Control at
schools and mobile
home parks
Willdan’s inspector will work closely with the Contractor to maintain maximum traffic flow and will ensure traffic control measures meet MUTCD requirements. This is especially important during the construction of the ADA ramps and bulb-outs near the mobile home parks and schools.
Challenge 3 Public Outreach
W
illdan has extensive experience with similar City’s Street Improvement Project and recommends the City implement a vigorous public outreach campaign to the mobile home parks and schools prior, during, and post construction. Contractor will be required to maintain ingress, egress, and parking. The Contractor must limit the no parking to active construction zones.
Communication Approach
Willdan recognizes that effective, ongoing,
co
operative communication between all parties
over the course of any project is essential to
successful completion. This communication
starts with a project kick-off meeting where the
objectives and expectations of the City for the
project are clearly articulated and understood by
Willdan. In addition, agreed-upon methods and
scheduling of formal reporting are established
with identification of individuals to be involved
in the project's decision-making process. This
sets forth accountability and responsibility for
informing and facilitating the project.
As the project progresses, communication
continues through regular correspondence, teleconference discussions, and meetings with City staff to obtain direction on issues that may arise and keep City staff apprised of the project status. Clear and concise progress updates are provided. Emails and teleconferences are utilized whenever possible and appropriate to minimize City staff time spent in meetings.
Our ultimate goal is to surpass our clients' expectat i ons and provide a completed project that
benefits City staff, Council members, business owners, and residents.
Scope of Services
Construction Management
1. As sist City with public awareness and information program to keep residents and local stakeholders advised of project status along with impacts to traffic flow circulation, including answering public’s questions about project.
2. Prepare construction file.
3. Ensure contractor distributes public construction notices and places construction and information signs.
4. Prepare special concerns to be presented at preconstruction conference.
5. Conduct preconstruction meeting, prepare meeting minutes, and distribute to attendees.
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
13 6. Review contractor’s safety program in consultation with City staff.
7. Through Willdan’s system of project control, monitor activities related to project such that project is constructed in timely fashion pursuant to contract documents and LAPM.
8. Log, track, review, and process submittals, RFIs, releases for construction (RFCs), contract change orders (CCOs), field directives, notices of proposed change (NOPCs), non-conformance reports (NCRs), construction schedule, and detailed traffic control plan.
9. Prepare clear and concise letters and memoranda, as needed. Establish a solid paper trail.
10. Review the construction schedule and enforce requirements for updating schedules and maintaining appropriate progress of the work.
11. Closely review schedule and advise contractor to take action on schedule slippage.
12. Document contractor’s 20-day notices, mechanic’s liens, and stop notices.
13. Assume responsibility for coordination with inspection staff and City staff.
14. Monitor and coordinate activities of design engineering support, surveying, testing, and work by utilities or other agencies.
15. Coordinate contractor’s field work with utility companies and other agencies.
16. Prepare weekly statement of working days and submit to contractor and City.
17. Establish and conduct weekly construction progress meetings to:
a. Resolve all old business issues to maximum extent possible b. Address all items of new business as presented by any party c. Review project schedule and address any deviations
d. Review submittal log in terms of items needed and resubmittals required and review RFI, RFC, CCO, NCR, and NPC logs
e. List status of construction items recently undertaken or ongoing f. List planned construction items for next two weeks (two-week look ahead schedule) g. Review SWPPP issues
h. Review contractor’s safety program
18. Prepare minutes for weekly construction progress meeting.
19. Provide claims mitigation monitoring, including proactively applying foresight to discover unforeseen conflicts prior to contractor encounter.
20. Evaluate and respond to contractor’s requests for clarification of plans and specifications.
21. Ensure that all questions, conflicts, and issues are immediately brought to City’s attention and addressed with appropriate directives to contractor.
22. Conduct special site meetings, when necessary, with contractor and City staff to review job progress, scheduling, and coordination.
23. Perform quantity, time, and cost analyses required for negotiation of contract changes.
24. Negotiate and prepare change orders, including memorandum of explanation and cost estimates, to substantiate change order and send to City for review.
25. Monitor and perform immediate and thorough analysis of validity of all potential claims that arise.
26. Maintain all data for change orders and record information concerning time of dispute, time of notification by contractor, and action taken by inspector.
27. Monitor materials documentation and testing results and enforce corrections.
28. Review for approval contractor’s progress payment requests, including verifying LAPM compliance status and impact on payment; negotiate differences over amount with contractor; and process payments through City's Project Manager.
29. Monitor preparation of punch list at substantial completion and follow up.
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
14 30. Routinely review construction files to ensure conformance to City standards and good construction management practices.
Construction Inspection
1. Re view plans, specifications, and all other contract- and construction-related documents.
2. Conduct a field investigation of the project area to become familiar with the existing facilities and the project environment.
3. Become familiar with traffic control plans, construction schedule, construction sequence, and permit requirements from other agencies.
4. Verify that the contractor conforms to the design survey line and grades.
5. Attend weekly progress meetings with the construction manager, contractor, and subcontractors.
6. Provide full-time and as-needed construction inspection of the work to monitor materials and methods for compliance with plans, specifications, and contract documents; and address and document non-conforming items as they are discovered.
7. Monitor compliance with Cal OSHA requirements and compliance with all local, state, and federal regulations.
Although Willdan will monitor the activities, it is the contractor’s sole responsibility to provide workers with a safe working environment.
8. If necessary, provide the labor compliance manager with labor and equipment reports, labor classification interviews, and assist with certified payroll review.
9. Monitor compliance with the Clean Air Act and the Clean Water Act (National Pollutant Discharge Elimination System – NPDES best management practices). Also, monitor the contractor’s compliance with approved SWPPP.
10. Meet with the contractor at the beginning of each day and review the proposed work plan, including specific details that may affect progress.
11. Conduct daily measurements of quantities of work with the contractor.
12. Review actual contractor performance throughout the day and discuss discrepancies with the contractor as they occur.
13. Assist in coordination of engineering support, surveying, specialty inspections, and fieldwork by utility companies.
14. Coordinate with Contractor and utility companies to assist in the identification of unknown utilities and possible relocation of interfering structures or lines.
15. Ensure contractor restores centerline ties and provides updated centerline tie-out notes, if any are disturbed.
16. Ensure compliance of Underground Service Alert notification/delineation.
17. Evaluate the contractor’s operation and production with respect to quality and progress and report to the construction manager.
18. Photograph continuous property frontages along the street alignment, once prior to construction and once immediately following construction. Maintain a photographic record of key elements of each major operation of work each day, with increased detail in situations of potential changes or claims.
19. Closely monitor testing results and require the contractor to provide corrective measures to achieve compliance.
20. Closely monitor required bac-t and chlorination testing.
21. Maintain copies of all permits needed to construct the projects and enforce special requirements of each.
22. Prepare and maintain detailed daily diary inspector reports on construction progress.
23. Prepare clear and concise letters and memoranda, as needed. Establish a solid paper trail.
24. Assist with the review and evaluation of change order work.
25. Provide complete measurements and calculations documentation to administer progress payments.
26. Maintain and submit a clean set of plans marked in red for as-built corrections on record drawings to be filed with the City.
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
15 27. Prepare a punch list at substantial completion and follow up with the contractor regarding progress of corrections.
Labor Compliance
1. Re view and update federal labor compliance components of project specifications to ensure adherence to current labor regulations and requirements.
2. If applicable, attend pre-bid conference to present general requirements of bid preparation for the project.
3. Verify applicable wage determination ten (10) days prior to bid opening; document verification as required. If wage determination has changed from what appears in project specifications, provide addendum and proof of receipt by plan holders.
4. Verify eligibility of selected contractor and its subcontractors to receive contract awards by confirming current, active license status with Contractors State License Board; current registration with California Department of Industrial Relations; current, valid contractor’s bond and workers’ compensation coverage; non-appearance on Federal List of Parties Excluded and State Division of Labor Standards Enforcement debarment lists.
5. Attend preconstruction conference to present federal labor compliance requirements to contractor and subcontractors; prepare minutes and attendance record thereof.
6. Verify and document job-site posting of wage rate information and labor compliance posters.
7. Receive and review labor compliance documentation from public works observers or inspectors and compare with contractor-submitted documents. Monitor contractor-submitted payroll documentation on a continuous basis, including weekly certified payroll reports, fringe benefit statements, apprenticeship documentation, and payroll deduction authorizations.
8. Follow up with contractor by telephone, email, and/or certified mail regarding required document submittals and payroll discrepancies and deficiencies. Provide detailed description of alleged deficiencies; outline corrective action to be taken; and enforce regulatory deadlines for compliance.
9. Receive, pursue, and document labor complaints; prepare violation reports to oversight agencies as required; recommend special action to be taken if contractor continuously fails to comply with requests and requirements.
10. Coordinate with City staff the withholding of progress and/or retention payments if contractor fails to abide by labor compliance requirements.
11. Maintain content and format of federal labor compliance file in conformance with applicable government requirements.
12. Coordinate project file reviews by authorized county, state, and federal agencies.
13. Submit complete federal labor compliance file to City for retention.
Federal Funding Administration (Optional)
1. P
rior to award or after contract award but not later than the first invoice, verify that the City has completed LAPM Exhibit 10-C A&E Consultant Contract Database online, submitted copies of LAPM Exhibits 10-O1 Local Agency Proposer DBE Commitment (Consultant Contracts) and 10-O2 Local Agency Proposer DBE Information (Consultant Contracts) to the Caltrans DLAE, and for consultant contracts over $150,000 submitted LAPM Exhibits 10-A A&E Consultant Financial Document Review Request and 10-K Consultant Certification of Contract Costs and Financial Management System to Caltrans IOAI.
2. Monitor the Caltrans Local Assistance website for City projects with inactive obligations and notify City staff.
3. Prepare and submit to the Caltrans DLAE LAPM Exhibit 5-A Local Agency Invoice at least once every 6 months based on the following items provided by the City: consultant invoices, contractor’s contract progress payments, copies of cancelled checks, and for the first construction invoice only, a copy of LAPM Exhibit 15-L Local Agency Contract Award Checklist.
4. If a post-award adjustment to the Finance Letter is needed prior to submitting the Final Invoice, prepare and submit to the Caltrans DLAE for approval a request including revised LAPM Exhibits 3-A Project Authorization/Adjustment Request and 17-E Change Order Summary based on the final construction and consultant costs.
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
16 5. Prepare and submit to the Caltrans DLAE the Federal Report of Expenditures (FROE) and Final Invoice including LAPM Exhibits 17-A Federal Report of Expenditures Letter and the Report of Expenditures Checklist, 17-C Local Agency Final Inspection Form, 17-G Materials Certificate, 5-A Local Agency Invoice, 15-M Final Detail Estimate and Summary, and 17-E Change Order Summary based on the following items provided by the City: consultant final invoices, contractor’s final contract payment (retention) or letter from Escrow, copies of cancelled checks, 17-F Final Report - Utilization of DBE, First Tier Subcontractors and 17-O DBE Certification Status Change.
Project Closeout
1. Re view, finalize, and transmit the contractor’s approved record drawings (as-built) to the City.
2. Schedule a final inspection with the City and applicable agencies; prepare, distribute, and inspect corrections to the final punch list for completion; and recommend final acceptance.
3. Secure and transmit required guarantees, affidavits, releases, waivers, and operation manuals to the City’s Project Manager.
4. Finalize contract bid items, claims, change orders, and punch list items.
5. Prepare documentation for final payment to the contractor.
6. Prepare all final reports including report of completion for acceptance of the projects.
7. Finalize and deliver all construction files to the City ready for archiving in both electronic and hard copies.
8. Assist the City’s Project Manager with resolving any unresolved issues, including, but not limited to, change orders, claims, etc.
9. Complete documentation required by various funding sources and other regulatory authorities.
Time of Work
17.B
City of Hemet
H
emet Valley Bikeway
CM Services
17 7. Resource of Allocation
Team Availability
Key Staff
Member
Availability
Percentage Projects and Contact Information
Mike Bustos,
P
E, ENV SP
Project
Manager/
Resident
Engineer
25%
(1) Ca
ltrans Auditor
Seree Yenjai | (916) 205-9088 | [email protected] (2) City of Ridgecrest – On Call Construction Management Services Travis Reed | (760) 499-5081 | [email protected]
(3) City of Inglewood – On Call Professional Services
Peter Puglese | [email protected]
(4) City of Downey – On-Call Construction Management and Inspection Lorena Powell | (562) 904-7110 | [email protected]
Joe Putrino
Construction
Manager
50%
(1) City of Grand Terrace – Pavement Rehabilitation Barton Road / Van Buren Street Kamran Dadbeh | (909) 954-5192 | [email protected] (2) City of Rancho Cucamonga – Center Avenue Pavement Rehabilitation Romeo David | (909) 774-4070 | [email protected]
(3) City of Hemet – Citywide Sewer Main Replacement & Relining CIP 5653B Noah Rau | [email protected]
Mike Paieri
Inspector 100%
(1) Ci
ty of Newport Beach – On-Call Inspection Services
Robert Silva | (949) 270.8131 | [email protected] (2) City of Norwalk – On Call Inspection Services
Randy Hillman | (562) 929-5719 | [email protected]
Jane Freij
Labor
Compliance
Manager
50%
(1) City of Lakewood – On Call Labor Compliance
Max Withrow | (562) 866-9771 | [email protected] (2) City of Cerritos – On Call Labor Compliance
Albert Arteaga | (562) 916-1229 | [email protected]
(3) City of Ridgecrest – On Call Labor Compliance
Travis Reed | (760) 499-5080 | [email protected]
Amanda Perez
Labor
Compliance
Specialist
50%
(1) Ci
ty of Brea – Skate Park Improvements
Raymond Contreras | (714) 671.4411 | [email protected] (2) City of South Lake Tahoe – Lake Tahoe Blvd. Class I Bicycle Trail Randy Carlson | (530) 542.6033 | [email protected]
(3) City of La Puente - Street Improvements on Various City Streets (HSIP) John Di Mario | (626) 855-1517 | [email protected]
17.B
City of Hemet
H
emet Valley Bikeway
CM Services
18 8. Quality Assurance/Control
Willdan will perform Quality Assurance and Quality Control of this project through a diligent review of all work and documentation. Quality
Assurance and Quality Control will begin with the
pre-construction meeting, at which time the scope of the project and control requirements will be reviewed with
the General Contractor. Once construction begins, the
next step in the Quality Control process will be the
verification of materials and components to be installed.
Once the material and components arrive onsite, Willdan Construction Managers and Inspectors will spot-check
these materials and components to verify they match the construction documents. They will maintain a detailed
record of samples, tests, and material releases, and
certificate of compliance for the project.
Willdan Construction Managers and Inspectors closely
monitor projects to ensure compliance with all contract requirements. Many of our staff are certified QSPs and QSDs and are provided with the latest information concerning the implementation of the State Water Board permit. Willdan’s Construction Managers and Inspectors have knowledge of basic soil dynamics and are highly cognizant of the crucial role of soils compaction in construction. They are also familiar with the needs for general material testing for asphalt and concrete. The basic goal of the quality assurance plan is to provide quality work delivered on time and within budget. We do this by adhering to the following steps.
Willdan adopted Caltrans' Construction Manual (LAPM) as our in-house quality standard and has incorporated Caltrans' prescribed standards and procedures into our everyday inspection routine. This ensures we meet federal and state guidelines from the start.
Project Budgeting
The budget control system is prepared in accordance with the work breakdown structure. The b
udget becomes the control against which performance is measured. The budget is time phased by combining project master scheduling data with budget data. Actual costs are compared with budgeted costs and variances analyzed. Deviations between planned and actual cost can then be evaluated to forecast and control future work. Beginning with electronic timekeeping, project hours are assigned to the appropriate tasks and subtasks and booked as work-in-process. Pre-bill reports are Address contractor
c
oordination issues
Identify key dates
t
o maintain the
project schedule
Investigate
c
onstructability
Discuss project
s
equencing
Track progress
Quality Control Methodology
Willdan’s team is unique in that it is
structured as an integrated unit with
close communication between team
members and interlocking
responsibilities that provide good
coverage of all elements of construction
engineering, while at the same time
having minimal overlap of duties to
avoid misunderstandings of assigned
responsibilities and reduce costs. This
structure provides a natural quality
assurance/control system for the team.
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
19 generated that identify the hours to be billed along with any other direct charges to the project. This information is used to determine each month's invoicing. Once hours and charges are billed, they are shifted from Work-in-Process to Accounts Receivable to ensure that billed hours are inactivated.
Monitoring is easily accomplished through team member progress updates and comparisons between the scope of work, schedule, and budget.
Scheduling
A critical path method master schedule will be prepared following the notice to proceed. The s
chedule will identify major items of work and will be the vehicle for monitoring, controlling, and tracking progress. The schedule will be updated monthly to reflect actual and forecasted completions. This allows our project managers to anticipate and forecast potential issues and develop an advanced strategy to proactively mitigate problems before they impact the schedule. As part of our effort to meet the City of Hemet’s performance expectations and meet project deadlines, common scheduling alerts will be set up using the notifications application in iOS or Outlook Calendar to alert the Project Manager and Construction Manager of deadlines for the project. Of course, not all projects can meet strict processing deadlines due to complex issues that might, for example, require an approval or information from an outside agency. Under such circumstances, the City Project Manager will be immediately notified of any potential project delay. Strategies will be developed and implemented to resolve project challenges and expedite the approval of the affected projects. As the Project Manager, Mr. Bustos will monitor all progress on a weekly basis.
Contractor Compliance
Our staff has extensive experience with a myriad of public works projects and has a clear u
nderstanding of the issues surrounding inspection of the work. For example, when constructing sidewalks and ADA-compliant ramps, our team will ensure adequate subgrade compaction has been achieved. They will monitor the work for conformance with the plans, specifications, and ADA requirements. The concrete tickets will be checked to ensure materials match the approved mix design. A smart level will be used to check forms and the contractor will not be allowed to place concrete until the work meets all City and other applicable standards. Willdan’s team will monitor the contractor’s operations for conformance with City compaction standards by working with the City’s approved material testing lab and will not accept any trench backfill or allow any pavement repair until proper compaction is verified by the lab.
Document Control
The submittal requirements and format for consistent monthly reporting of project costs and s
tatus will be confirmed with the Commission during project start-up. The status report will contain a project performance summary, action items, outstanding items to be resolved, an updated schedule, and a comparison and narrative of budgeted costs versus actual costs.
Customer Service
To meet and often exceed the expectations of our clients, Willdan fosters and instills a corporate c
ulture of Customer-First among our staff and in our day-to-day work environment. Looking out for our customer’s best interests is at the forefront of everything we do. Our customer-focused philosophy is particularly evident when dealing with complex situations and difficult to resolve challenges. Willdan's corporate goal is to exceed the City of Hemet’s expectations.
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
20 9. Appendix
Required Forms
The following pages contain the required forms per the City’s RFP:
Proposer’s Signature Page – two forms have been attached, one for each officer required. Non-Collusion Affidavit – Willdan Engineering
LAPM Exhibit 10-O1 Consultant Proposal DBE Commitment – Willdan Engineering LAPM Exhibit 10-Q Disclosure of Lobbying Activities – Willdan Engineering LAPM Exhibit 10-Q Disclosure of Lobbying Activities – Sierra Geotech
F
ollowing the forms are our key team members’ resumes and a sample of our pre-construction agenda, meeting minutes, sample daily log inspection report and sample quantity calculations.
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
21 Proposer’s Signature Page
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
22
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
23
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
24
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
25 Non-Collusion Affidavit
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
26 LAPM Exhibit 10-O1 Consultant Proposal DBE Commitment – Willdan Engineering
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
27 LAPM Exhibit 10-Q Disclosure of Lobbying Activities – Willdan Engineering
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
28 LAPM Exhibit 10-Q Disclosure of Lobbying Activities – Sierra Geotech
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
29 Resumes
Michael D. Bustos, PE, ENV SP
Deputy Director of Construction Management and Inspection Services P
roject Role: Construction Manager/Project Engineer
Profile Summary
Education: BS, Civil Engineering, California Polytechnic State University, San Luis Obispo Caltrans Resident Engineer Academy
Registration: Civil Engineer, California No. 73173
Envision Sustainability Professional, Institute for Sustainable Infrastructure Experience: 23 Years
Mr. Michael Bustos is responsible for design and construction management of projects such as utility installations and relocations, water wells, pipelines, pipeline rehabilitation, water treatment systems, roadway reconstructions, drainage improvements, pavement rehabilitation, bikeway improvements, street improvements, and grading. Mr. Bustos has served as resident engineer for over a dozen federally- and state- funded projects over the last five years. He has gained valuable experience in on-site construction management, off-site construction administration, inspection, design, and plan checking during his 23 years with Willdan.
Relevant Project Experience
Foothill Boulevard Link Bikeway and Pedestrian Greenbelt Project, City of La Canada Flintridge, C
alifornia. Resident Engineer/Construction Manager. This federally funded project consists of the construction of approximately a half mile Class I bicycle and pedestrian path and two miles of Class II bike lane and bicycle amenities; raised medians; a bus stop; cold milling existing pavement and re-paving with Asphalt Rubber Hot Mix (ARHM); removal and installation of traffic striping and raised pavement marking; replacement of curb and gutter and other drainage improvements; traffic signal improvements to include new equipment, bicycle signal detection, and bicycle/pedestrian push buttons; street lighting; illuminated street name sign; and streetscape beautification with narrowed travel lanes to enhance bike and pedestrian mobility and safety.
West Highland Bikeways Infrastructure and Base Line Pavement Improvement, City of Highland, California.
Resident Engineer. Through our on-call engineering contract, Willdan provided construction management, inspection, and materials testing services for this $3 million project. The project involved cold milling and street pavement overlay; removal and replacement of concrete curb and gutters, sidewalk, driveway approaches, and handicap ramps; construction of new concrete bus pads; and installation of striping, pavement markings, and signage on Base Line from Del Rosa Drive to Cole Avenue and Bounder Avenue to Church Street.
CP13-32 Phase 1 Bicycle Corridors, City of Palm Springs, California. Resident Engineer. Willdan provided construction management, inspection, and materials testing services for this $1.2 million project to construct new green-back bicycle lanes on El Cielo Drive, Alejo Road, Belardo Drive, and Calle Encilia. The project included micro-milling, Rubber Polymer Modified Slurry Seal, hot mix asphalt concrete overlay, removal and replacement of existing traffic striping, pavement markings and delineation, installation of thermoplastic bike lane lines, thermoplastic bike lane markings, thermoplastic crosswalks, curb painting, and signs.
East Side of Downs Street Improvements, City of Ridgecrest, California. Construction Manager/Resident Engineer. Willdan was retained to provide construction management, inspection, labor compliance, and resident engineering. Material testing services were provided by Sequoia Consultants for the City of Ridgecrest’s federally funded East Side of Downs Street Widening project. The project was split into two phases – east and west – for funding purposes. The project’s goal was to widen the narrow street segment to an ultimate width to match the other previously widened segments at both ends. The east side widening involves new curb, gutter, sidewalk, curb ramps, driveway approaches, drainage culvert and headwall cement treatment, ARHM overlay, and other improvements.
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
30 Ridgecrest Boulevard Reconstruction and Widening Project, City of Ridgecrest, California. Construction Manager/Resident Engineer. Willdan was retained to provide construction management and inspection services for the City of Ridgecrest’s federally funded Ridgecrest Boulevard reconstruction and widening project.
Willdan provided construction management, inspection, labor compliance, quality assurance, materials testing, utility coordination, and federal funding compliance for full depth reclamation and full street reconstruction of a 1.5-mile segment of Ridgecrest Boulevard. The project included widening the road by 50 feet while lowering the street centerline elevation and flattening the streets crossfall. The project filled in all gaps in ADA compliant travel ways and Class II bike lanes. Numerous utility relocations, including power poles, new traffic signals, street lighting, median improvements, and landscaping and irrigation were major components of this street widening and reconstruction project. Kern Council of Governments selected the Ridgecrest Boulevard Project to receive the Regional Award of Merit in the Transportation Category.
Dolphin Ave Improvements, City of Ridgecrest, California. C onstruction Manager/Resident Engineer.
Willdan provided construction management, inspection, labor compliance, material testing, federal funding administration, and project administration for coordination; tracking progress log, submittals, RFIs, RFCs, and CCOs; reporting and field inspections for construction. Sequoia Consultants provided materials testing for the project. The location for the work is Dolphin Avenue between China Lake Boulevard and College Heights Boulevard. The work involves the paving of an existing dirt roadway, including hot mix asphalt, arch culvert and headwall installation and striping along Dolphin Avenue between China Lake Boulevard and College Heights Boulevard. The project completed construction in 2020. Project Closeout and Labor Compliance services are still ongoing. Project is federally funded (FHWA/Caltrans).
Old River School Road Pavement Rehabilitation, City of Downey, California. Resident Engineer. Willdan is providing construction management, resident engineering, inspection, and material testing services for the federally funded Old River School Road Pavement Rehabilitation Project. The work to be performed under the Old River School Road Pavement Rehabilitation Project, between Imperial Highway and Arnett Street, generally consists of the installation of traffic signal communications conduit and 32,000 LF of fiber-optic cables, pull boxes and termination panels; rehabilitation of existing pavement, including removal and reconstruction of asphalt concrete base course, cold milling existing asphalt pavement, placement of asphalt concrete leveling course and rubberized asphalt concrete overlay; replacement of non-standard curb ramps and uplifted or damaged curb and gutter and sidewalk in compliance with the Americans with Disabilities Act (ADA) requirements; implementation of Class II and Class III bike facilities; and replacement of incidental striping and signage.
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
31 Joseph Putrino
Construction Manager/Senior Public Works Observer
Profile Summary
Ed
ucation: College of the Desert, Palm Desert
Uniform Building Code, Fire Code, and ADA Codes, Bergen Community College Construction Management, Architectural Drafting, and Blueprint Reading Courses
Registration: Certified Building Inspector, International Code Council Certified Plumbing Inspector, International Code Council Certified Mechanical Inspector, International Code Council Contractor License Class A and B, No. 636747
Experience: 34 Years
Mr. Joseph Putrino is experienced in all aspects of public works construction projects. He possesses extensive experience with estimating project costs, progress schedules, bid preparation, and complete project administration.
Relevant Project Experience
Ca
pital Improvement Paving Project 21/22-04, City of Los Alamitos, California. Construction Manager/Public Works Inspector. Willdan provides construction management, public works inspection, and labor compliance for the City’s 21/22-04 Paving Project. 22200 Barton Road, City of Grand Terrace, California. Public Works Inspector. The project includes public works inspection for the public improvements associated with the construction of the new 5,342 SF multi- tenant building located at 22200 Barton Road.
North Park Improvement Project, Town of Yucca Valley, California. Construction Manager. This project includes construction management services for the City’s North Park Improvement Project. The improvements include demolition, traffic control, erosion control, unclassified excavation and fill, AC pavement, aggregate base, rip rap, signs and striping, curb stops, new water service, septic tank and system, prefabricated rest room building, grade walking trail and electrical.
Sector E Pavement Rehabilitation Project, City Project No. str20001, City of Highland, California .
Construction Manager/Inspector. This project includes pavement rehabilitation including pavement grinding, cold central plant recycling, pavement removal and replacement, and asphalt rubber overlay.
The scope of work includes minor removal and replacement of damaged concrete sidewalk, curb and gutter, gross gutter, grinding raised sidewalk panels; slurry seal, crack repair, crack seal; adjusting valve covers to final grade, protection of manholes; and installation of striping and markings.
Parking Lot 22038 Van Buren Street, City of Grand Terrace, California. Public Works Inspector. This project includes public works inspection for the public improvements associated with the reconstruction of the existing parking lot located at 22038 Van Buren Street.
La Puente Community Park Public Works Yard and Various Street Projects, City of La Puente, California.
Willdan provides construction observation, project management, material testing and labor compliance services for the street improvements on various street for FY 2020-2021 SB1 and Bond Funds, as well as La Puente Community Park Public Works Yard access road. 23400 Westwood Rough Grading Project, City of Grand Terrace, California. Public Works Inspector. The project included construction of new on and off-site improvements at the remodeled San Bernardino Indian Health Center. The project involved the installation of new curb/gutter, rough grading and finish grading of new parking lot, drainage structures, asphalt repair, and other appurtenant work.
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
32 Mike Paieri
Public Works Inspector
Profile Summary
Experience: 38 Years
Mr. Michael Paieri is a public works inspector with more than 38 years of construction project management experience, directing a broad range of multi-million-dollar projects, involving new installations, renovation of existing utilities, design-build, value engineering, extensive traffic control, dewatering/treatment, major shut down/tie-ends, and hazard site mediation. He has proven success completing projects within time, budget and quality requirements and goals. He has strong in-depth knowledge of building practices, guidelines, and regulatory compliance. He is qualified to evaluate bid documents, cost estimates, chart projections, and write and negotiate contracts. Mr. Paieri possesses excellent communication and leadership skills and works effectively with engineers, design teams, client representatives, contractors, managers and other public works personnel. He works jointly with the client to review job progress and address outstanding issues to provide the highest level of service to clients and ensure project success.
Relevant Project Experience
Various Permitted and Capital Improvement Projects, C ity of Newport Beach, California. Public Works Inspector. Willdan is providing construction management and inspections on various permitted and capital improvement projects throughout the City of Newport Beach.
Capital Improvement Projects FY 20/21, City of Westlake Village, California. Public Works Inspector.
Willdan provided inspection services for CIP Projects FY 20/21 for the City of Westlake Village.
Paramount Neighborhood Street Improvements, City of Paramount, California. Public Works Inspector. Mr. Paieri is providing construction observation for the City’s Neighborhood Street Improvements Project.
Alosta Avenue, City of Azusa, California. Public Works Inspector. Mr. Paieri is providing construction observation for the federally funded street improvement project. The project includes traffic control, cold milling, asphalt concrete overlay, asphalt concrete digouts, curb ramps, adjustments of survey monuments, manholes and valve covers to grade, installation of loop detectors, paving striping, markings and markers.
Project and Inspection Services for Astaldi Construction. As Project Superintendent, Mr. Paieri oversaw the design and construction of a heavy highway project which included $7 million worth of utility replacement in seven cities, involving CMCL pipe, HDPE pipe and C-900 pipe, as well as $49 million worth of 160,000 LF of drainage facilities from 8’ HPDE up to 60” RCP with large box culverts from 3’x2’ up to triple 12’x12’, along with challenging water diversion. Total contract value was $1.2 billion.
Project and Inspection Services for ARB, Inc. As Project Superintendent, Mr. Paieri oversaw four projects. Project 1 was budgeted at $600,000 and included the replacement of 2-30” valves with installation of advance SCADA system along with 12” bypass. Project 2 was a $700,000 project involving hydro test of 2 miles of 30” pipeline. This project was accelerated to meet the goals of the owner and it exceeded expectations and received recognition of excellent workmanship. Project 3 involved installation of 8” high pressure line on an offshore island which involved the challenge of scheduling personnel, equipment and material to be shipped offshore. This project was a $2.3 million project. Project 4 was a $25 million project involving installation of 24” pipeline along with three bores and involved hazardous soils and ground water.
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
33 Jane Freij
Labor Compliance Manager
P
roject Role: Labor Compliance Manager
Profile Summary
Education: BA, Linguistics (Summa Cum Laude), University of Kansas Member, Phi Beta Kappa
Registration: Attorney Assistant Training Program, Litigation/Corporations Certificate (with honors), U
niversity of California, Los Angeles
Experience: 30 Years
Ms. Jane Freij is an experienced Project Manager with a proven record of profitability achieved through effective management of time and budget. Key areas of expertise include project needs analyses, scheduling and budgeting, contract administration/negotiation, legal documentation, policy and procedure development, and writing and editing. As a Supervising Labor Compliance Manager, Ms. Freij provides oversight of labor compliance monitoring and enforcement services for various federally funded projects under HUD, FHWA, FTA, EPA, as well as various state, county, local, and privately funded projects.
She has written, edited, and updated the Willdan Engineering labor compliance manual and has assisted various agencies in developing their internal procedure manuals for federal and state labor compliance.
She has specialized training in reporting requirements, fraud detection and prevention procedures for federally funded projects, as well as Disadvantaged Business Enterprise (DBE) Program implementation and administration.
Experience prior to joining Willdan includes 4 years with Edison Enterprises, where Ms. Freij served as Contract Administrator, developing and negotiating contracts for products and services, monitoring and enforcing contractual compliance, serving as risk management liaison, and managing a multi-state licensing project for an energy services subsidiary.
Relevant Project Experience
Foothill Boulevard Link Bikeway and Pedestrian Greenb elt Project, City of La Cañada Flintridge, CA.
Ms. Freij is the City’s Labor Compliance Officer, providing compliance monitoring and enforcement services on this $4-million project, funded by an FHWA/Caltrans grant with local matching funds, involving the construction of 2½ miles of Class I and Class II bike route.
La Brea Avenue Pavement Reconstruction, Phases II and III, City of Inglewood, CA. Ms. Freij was the Labor Compliance Officer for these federally funded projects, with a combined construction cost of $12 million, funded through the Federal Highway Administration (FHWA) and administered through the California Department of Transportation (Caltrans). The projects involved full pavement removal, AC overlay, PCC improvements (sidewalks, driveways, median curbs, utility frame cover adjustments, bus pads and ADA-compliant curb ramps), landscaping, an irrigation system, and signing and striping. Ms.
Freij was responsible for enforcing compliance with prevailing wage and DBE requirements.
Pacific Electric Inland Empire Bicycle Trail (“Rails to Trails”), City of Rialto, CA. Ms. Freij was the City’s Labor Compliance Officer for this $3.5 million project to construct the final slightly over one-mile portion of a 21-mile bicycle trail linking six cities along the abandoned Pacific Electric Railroad Line. The project was funded through FHWA with Caltrans oversight and involved the construction of an 11-foot-wide bicycle trail with a two-foot shoulder on each side, including hardscaping and landscaping, drainage and utility improvements, and lighting and pedestrian crossings.
Alosta Avenue Street Improvements, Azusa, CA. Ms. Freij served as the third-party labor compliance officer and consulting DBE officer for this project, with a construction cost of approximately $800,000 and FHWA/Caltrans funding. She was responsible for monitoring and enforcing labor laws and DBE requirements and assisted the City in a post-construction project audit with Caltrans.
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
34 Amanda Perez
Labor Compliance Specialist/CM Asst.
P
roject Role: Labor Compliance Specialist
Profile Summary
Education: AS, Human Resources Management, Mount San Antonio College AS, Business Administration, Mount San Antonio College Registration: Certificate of Achievement, Business Management I-III Certificate of Achievement, Human Resources Management I-III Certificate of Achievement, International Business I
Experience: 13 Years
Ms. Perez currently performs labor compliance monitoring and enforcement services on a variety of local, county, state, and federally funded projects. She verifies that all primary and subcontractors possess active licenses and certifications. She establishes communication with primary contractor(s) concerning prevailing wage requirements and documentation requirements. She monitors that all certified payrolls are submitted on a timely basis, as well as audits payrolls during the life of the project for compliance and discrepancies concerning prevailing wage, certifications, non-performance, underpayments, and journeyman to apprentice ratios, and use of job classifications. She ascertains the submittal of training fund contributions and audits fringe benefits statements to ensure proper payment. Ms. Perez responds to inquiries concerning labor compliance rules and requirements and resolves all compliance-related issues. She reviews forms and reports from field personnel to ascertain missing CPRs, correct usage of classifications, and apprentice / journeyman ratios, as well as maintains files and all required documentation in accordance with applicable governmental requirements and organizes and prepares labor compliance files for submission to clients.
Ms. Perez also supports the Construction Management and Inspection Department and is responsible for issuing invoicing, progress payments, and schedules and for maintaining detailed, accurate records. She conducts comprehensive audits of projects for accuracy and compliance.
Relevant Project Experience
Lake Tahoe Boulevard Class I Bike Improvement Project , City of South Lake Tahoe, California. Labor Compliance Specialist. Willdan Engineering is providing Labor Compliance Monitoring for the City’s Class I Bike Improvement project between Viking Way and US50/SR89. The project is federally funded, using FHWA funds.
CDBG Pavement Improvements – Section E, City of Highland, California . Labor Compliance Specialist.
Willdan is providing project management, construction administration, and labor compliance services on this $700,000 HUD/CDBG project. This project involves pavement rehabilitation including pavement grinding, cold central plant recycling, pavement removal and replacement, and asphalt rubber overlay.
Downs Street Widening, City of Ridgecrest, California. Labor Compliance Specialist. Willdan provided civil and traffic engineering design, environmental compliance, right-of-way acquisition, and bidding assistance and is providing resident engineering, construction management, inspection, quality assurance materials testing, federal funding administration, and labor compliance services for widening improvements to close a 1,500-foot gap between Ridgecrest Boulevard and Upjohn Avenue. The project's goal was to widen the narrow street segment to an ultimate width to match the other previously widened segments at both ends. The project was split into two phases – east and west – for funding purposes.
Dolphin Avenue Improvements, CML-5385 (064), City of Ridgecrest, California. Labor Compliance Specialist. Willdan is providing project management, contract administration, construction observation, utility coordination, material testing and labor compliance services for the Dolphin Avenue Improvements Project, CML-5385 (064).
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
35
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
36
17.B
City of Hemet
H
emet Valley Bikeway
CM Services
37 Sample Documents – Precon Meeting Minutes
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
38
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
39
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
40
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
41
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
42
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
43
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
44 Sample Documents – Daily Inspection Report
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
45
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
46 Sample Documents – Calculated Quantities
17.B
City of Hemet
Hemet Valley Bikeway
CM Services
47
17.B
[):x11m:JI1M7:
APPLIOIIJLE
STATEOFCALIFORNIA-THERESOURCESAGENCYDEPARTMENTOFFISHANDGAMEENVIRONMENTALFILINGFEECASHRECEIPT Receipt#:21-563276StateClearinghouse#(ifapplicable):
LeadAgency.-CITYOFHEMET Dare:11/19/2021CauntyAgencyofFiling:RIVERSIDE E-202101256ProjectTitle:HEMETV ALLEYBIKEW AYCONNECTcmrPROJECTNO.5595ProjectApplicanlName.'CITYOFHEMET Pl1or2Number:(951)765-2456Pr0J'€clAPP1icamAddress-'445EFLORIDAA VEHEMETCA92543Projempplicanr:LOCALPUBLICAGENCY $50.00
TotalReceived$50.00
CHECKFEES:BEnvironmentalImpactReportDNegativeDeclarationD/ipplicationFeeWaterDiversion(StateWaIerResourcesC0ntroIBoara'0nly)UProjectSubjecttoCertifiedRegulatoryProgramsMCountyAdministrationFeeDProjectthatisexempt?omfees(DFGNoE?ectDetermination(FormAttached))NProjectthatisexemptfromfees(NoticeofExemption) Signatureandtitleofpersonreceivingpayment
Notes:
17.B
§T7'1’§}%§?ao2:4sPHFun:550-MF I ofIm_,,,\\\v\Iz\,,.766759?’3D-vulv l
Rlnlov
ll?.‘?§l!I“S:I‘¥f!'ldF1iii1£I‘|!\!u|!i‘«Xlf!IFI
HEME|'MUNICIPALCODE
I CommuniivDevelopmentDiredor (951)765-2456/’u:(.’|/(ang 445E.FLORIDAA VENUEHEMET,CALIFORNIA92543(951)765-2375COMMUNITYDEVELOPMENTDEPT'°”‘”""”G FILED/POSTEDCountyofRiverside:§§:§s:.1-c-'33:.-ltyClerk-RecorderNOTICEOFEXEMPTIONNovember15,2021TO: MaryAnnMeyerRIVERSIDECOUNTYCLERKP0BOX751Riverside,CA92502-0751SUBJECT:FILINGOFNOTICEOFEXEMPTIONFROMREQUIREMENTSOFTHECALIFORNIAENVIRONMENTALQUALITYACT(CEQA)PROJECTTITLE HemetValleyBikewayConnectCityProjectNo.5696APPLICANTNAME&ADDRESS:CityofHemet445E.FloridaAve.Hemet,CA92543PROJECTLOCATIONIAREA:PalmAve—JohnstontoEsplanade,WhittierAve—PalmtoGilbert,JohnstonAve-PalmtoGilbert,GilbertSt—WhittiertoChambers,ChambersSt— GilberttoStateintheCityofHemet.PROJECTDESCRIPTION:PavementrehabilitationonPalmAvebetweenWhittierandFlorida,Installationofin?llcurb,gutter,andsidewalkthroughouttheprojectlimits,constructionlupgradeofADAaccessrampsandcurbextensions.EXEMPTSTATUS:__ Ministerial(Sec.21080(b)(1);15268)DeclaredEmergency(Sec.2180(b)(3);15269(a))__ EmergencyProject(Sec.21080(b)(4);15269(b)(c))X CategoricalExemption-(Class1Section15301(c)) Reasonswhyprojectisexempt:Thereisnopossibilitythatthisprojectwillhaveasigni?canteffectontheenvironmentasitisanexistingfacilitythatisbeingmaintainedorupgradedandisexpresslyexemptedundertheabovereferencedGovernmentCode.DateofProjectApproval:November15,2020 DateReceivedforFiling:APPEAL:THEDETERMINATIONSETFORTHHEREINABOVESHALLBEFINAL30DAYSAFTERTHERENDITIONOFSAIDDETERMINATIONSUNLESSAPPEALEDWITHINSAIDTIME.ANYNOTICEOFAPPEALSHALLBEFILEDINCOMPLIANCEWITHALLPROVISIONSOFSECTION90-44OFTHE ,REGARDINGTHEFILINGOFSUCHAPPEALS.
Title TelephoneNumber
17.B
Hemet City Council
CIP 5696- Hemet Valley Bikeway
Public Works Department
February 14, 2023
17.B
CIP 5696- Proposed Hemet Valley Bikeway
• Federal Active Transportation Program (ATP) funded
project from FY 17/18 cycle 3.
• Provides Class II and Class III Bike Lanes from Esplanade to Chambers.
17.B
CIP 5696- Proposed Hemet Valley Bikeway
• Full street width 2” grind and overlay on Palm
Ave from Whittier to Florida Ave.
• Install 15 bike repair and comfort stations
• Construct 12 curb extensions “bump outs”
• Remove existing and reconstruct curb, curb &
gutter, sidewalk, driveways, and cross gutter.
• Parking lot with amenities on State.
• Signing & Striping
17.B
CIP 5696- Proposed Hemet Valley Bikeway
• The City investment into the project to-date is approximately $240K • Project construction contracts must be awarded by 2/28/23 to meet grant requirements.
Construction Contract $3,032,303
Construction Contingency $303,230
Construction Management & Inspection $211,113.60
Project Management $25,000
Total Construction Costs $3,571,646.60
Available ATP Funds for Construction $1,990,000
Construction Funds Needed to Proceed $1,581,616.60
• If the Council decides the project is in
the best interest of the Community at
the current construction costs, staff
recommends re-appropriating ARPA
funds to this project.
• CIP 5743 – Citywide Roadway
Improvement has $1,800,000 of
ARPA funds appropriated
17.B
Strategic Plan Integration
Quality of Life Organizational
Effectiveness
Community
Engagement
The decision before you relates to these strategic plan goals
17.B
Discussion & Follow Up
17.B