15.F.
49 | Page
Professional Engineering Services for
WARREN ROAD IMPROVEMENTS
Request for Proposal (RFP) for
Storm Channel improvements, and verification calculations for the existing San Diego Aqueduct wingwalls. All structure plan details will be reviewed by the check engineer for completeness and accuracy. A thorough review of the details will be performed for clarity, capacity, standards, and constructability issues. When the independent check is complete, the checker and designer will compare their results and resolve any differences. The calculations will be corrected so that they agree substantially with each other. Agreement is then reached regarding corrections to the plans. After plan corrections, both the designer and checker will review the corrected details to ensure all concerns have been addressed.
Subtask 4.6 100% Plans, Specifications, and Estimate: Dokken will review and respond to any City comments from the 90% PS&E submittal. Once all comments are addressed, we will continue with the preparation of the 100% signed and stamped PS&E package. This package will be the final construction document to build the project, including final plans, specifications, and cost estimates and will be revised sufficiently to present to City Council to receive authority to bid.
4.6.1 Phase 1, Stetson to Esplanade, 100% PS&E: We will prepare the 100% PS&E as described above.
4.6.2 Phase 2, Salt Creek Bridge to Stetson, 100% PS&E: We will prepare the 100% PS&E as described above.
4.6.3 Phase 3, Salt Creek Bridge Widening, 100% PS&E: We will prepare the 100% PS&E as described above.
Subtask 4.7 Traffic Signal Timing Plans: The Dokken Team will visit the Project area to document posted speeds and obtain existing timing plans from the signal cabinet. Utilize the traffic counts collected as part of the Level of Service (LOS) Analysis at the four potential signalized intersections (Warren/Simpson, Warren/Stetson, Warren/Devonshire, and Warren/Esplanade) with FHWA vehicle classifications. We will conduct pedestrian and bicycle counts. The pedestrian and bicycle counts will be conducted between the hours of 7:00 AM to 9:00 AM and 4:00 PM to 6:00 PM at the four potential signalized intersections (Warren/Simpson, Warren/Stetson, Warren/Devonshire, and Warren/Esplanade). Pedestrian counts include the number of traffic signal crosswalk activations and the number of pedestrian crossings. We will conduct Synchro analysis for preparation of local timing sheet applying the City parameters with the data collected from Task 1.2. Submit a copy of the local timing plan for the intersections of Warren/Simpson, Warren/Stetson, Warren/Devonshire, and Warren/Esplanade to the City for review.
Revise the local timing plan to address City comments and resubmit for review and approval. Provide signal timing turn-on and troubleshooting field support.
TASK 4 DELIVERABLES: Updated Basis of Design Memo; Updated Project Overview Exhibits; 30% Plans and Estimate Package; 60% Plans and Estimate Package; 90% PS&E Package; 100% PS&E Package; Response to Comments; QA/QC Docs; Final Signed Drawing Set; Final Cost Estimate; Final Specifications; Traffic Signal Timing Plans TASK 5 – BIDDING AND CONSTRUCTION SUPPORT SERVICES
Subtask 5.1 Bidding Support Services: Dokken will attend the Pre-Bid Meeting and will be available during the bidding phase of the project to assist the City with providing responses to bidder inquiries and an analysis of the bids as needed. Revisions to plans as needed to adequately address bidder inquiries are included in this task along with a final compilation of post-bid and pre-construction conformed plans for records.
• Pre-Bid Meetings (3): At the completion of each phase of the project, Dokken will work with the City to schedule and organize pre-bid meetings with all key personnel, prospective bidders, and stakeholder representatives on the project.
The purpose of this meeting will be to review the bid package and any bidder inquiries and ensures that bidders have all received the proper bid documents and have all their questions answered.
Subtask 5.2 Construction Support Services: Dokken will be available during the construction phase of the project to assist the City with providing responses to the Resident Engineer and Contractor requests for information (RFIs), Contractor submittal reviews, site visits, and preparation of contract change orders (CCOs) and plan revisions as needed.
Subtask 5.3 As-Built Drawings: Dokken will acquire the red lined plans from the contractor and the subcontractors and will prepare the As-built drawings upon completion of the project. Our team will coordinate with the Construction Management Team to review updated plan sheets. Final record drawings will be submitted in electronic (CAD/PDF) and hard copies.
TASK 5 DELIVERABLES: Pre-Bid Meeting Notes, Bidder Inquiry Responses, Bid Analysis, RFI Responses, Submittal Reviews, CCO Response Packages, As-Built Drawings
15.F.
SECTION IV –
FEE SCHEDULE
15.F.
50 | Page
Professional Engineering Services for
WARREN ROAD IMPROVEMENTS
Request for Proposal (RFP) for
Section IV – Fee Schedule
Dokken Engineering’s fee schedule has been submitted in a separate file per the RFP.
15.F.
Michael Greer, PE, TE
Project Manager
Mark Tarrall, PE
Principal in Charge /
QA/QC Manager
Justin Thornber, PE
Roadway Project Lead
Charles Tornaci, PE
Structures Project Lead
Ashley Orsaba-Finders, PE,
QSD/P
Drainage Lead
Joe Ostdiek, PE, TE
Traffic/Electrical Lead
Andrew Romero, EIT
Utilities Lead
Senior Engineer 3
Senior Engineer 2
Senior Engineer 1
Associate Engineer 2
Associate Engineer 1
Assistant Engineer 2
Assistant Engineer 1
Senior CAD
CAD / Detailer
Matt Britten (Sr. Civil Eng -
Crossings Lead)
Robert Williams (Sr. Civil
Eng - Crossings)
Kyle Ablan (Civil Eng III -
Crossings)
Isabela Barney (Civil Eng
III - Crossings)
Jana Nakamura (Document
Controls Specialist)
Principal
Senior Transportation
Engineer
Transportation Engineer
III
Transportation Engineer I
Senior Signal System
Specialist
Associate Principal
Transportation Engineer II
Engineering Associate II
BILLING RATES* $295 $365 $235 $295 $265 $265 $170 $295 $265 $235 $195 $180 $150 $130 $245 $155 $285 $285 $130 $119 $121 $298 $226 $200 $147 $200 $268 $171 $145 TASK 1 – PROJECT MANAGEMENT 216 144 36 28 16 24 48 512 $5,271 $135,431 4 4 8 $1,588
1.1 Meetings and Coordination 120 48 24 16 16 24 48 296 $2,939 $75,499 4 4 8 $1,5881.2 Project Administration 96 96 12 12 216 $2,333 $59,933 TASK 2 – DATA COLLECTION, UTILITY COORDINATION, AND SURVEYING/MAPPING 150 150 20 44 44 216 92 84 20 132 156 1108 $9,025 $36,000 $267,865 8 8 8 22 46 $230 $7,158
2.1 Data Collection and Field Review 60 60 8 20 20 60 20 60 20 60 388 $3,259 $83,719 8 8 16 $230 $3,5462.2 Utility Coordination and Conflict Resolution 72 72 12 24 24 144 72 72 144 636 $5,047 $36,000 $165,6672.3 Design Survey (Control, Aerial, and Topo) 6 6 6 12 30 $245 $6,3052.4 Right of Way Mapping and Engineering 12 12 6 24 54 $474 $12,174 8 22 30 $3,612 TASK 3 – PRELIMINARY ENGINEERING AND REPORTING 121 115 4 88 208 266 180 632 412 96 2113 $15,681 $402,876 38 234 48 24 344 $230 $86,769 6 18 70 4 6 104 $17,620
3.1 Conceptual Exhibits and Estimates for Alternative Analysis 96 96 96 192 192 96 768 $5,599 $143,8393.2 Traffic Data, Scoping, and Level of Service Analysis 12 3 $36 $921 6 18 70 4 6 104 $17,620
3.2.1 Data Collection and Research 4 2 6 $1,0903.2.2 Distribution and Assignment 4 4 $5883.2.3 Formulation of Future Traffic Volumes 2 24 26 $3,9283.2.4 Project Evaluation and Mitigation Analysis 2 16 18 $2,7523.2.5 Project Evaluation and Mitigation Analysis for Roadway Segments 2 2 2 6 $1,2903.2.6 Preparation of the Level of Service (LOS) Analysis Report 3 3 $36 $921 4 8 24 4 4 44 $7,972
3.3 Vehicle Miles Traveled (VMT) Analysis (Optional Task) 4 50 10 22 86 $14,984
3.4 CPUC Permit Application (GO-88B) (Optional Task) 38 234 48 24 344 $230 $86,769
3.5 Geotechnical Investigation Report 6 6 2 4 18 $184 $4,7343.6 Traffic Control Plans for Geotechnical Investigations (Optional Task)
3.7 Drainage Report 6 12 80 160 150 180 360 220 1,168 $8,604 $221,044
3.7.1 - Phase 1 2 4 30 60 50 80 120 80 426 $3,156 $81,0863.7.2 - Phase 2 2 4 40 100 80 100 200 120 646 $4,772 $122,6023.7.3 - Phase 3 2 4 10 20 40 20 96 $676 $17,356
3.8 - Bridge Design Hydraulic Report 1 1 2 8 48 16 80 156 $1,259 $32,339 TASK 4 – PLANS, SPECIFICATIONS, AND ESTIMATES (30%, 60%, 90%, AND 100% PS&E) 450 113 900 310 189 175 225 78 742 438 776 446 1600 876 580 1656 9554 $77,699 $1,996,184 26 12 96 12 146 $24,705 3 10 15 5 155 188 $37,889
4.1 30% Plans and Estimate 100 25 200 42 42 38 50 100 100 76 100 200 200 64 368 1,705 $13,740 $352,995 4 2 20 26 $4,303
4.1.1 Phase 1 30% Plans and Estimate 48 12 96 6 12 12 24 48 48 12 48 96 96 192 750 $5,870 $150,800 4 2 20 26 $4,3034.1.2 Phase 2 30% Plans and Estimate 36 9 72 12 18 18 18 36 36 24 36 72 72 24 144 627 $5,042 $129,5274.1.3 Phase 3 30% Plans and Estimate 16 4 32 24 12 8 8 16 16 40 16 32 32 40 32 328 $2,829 $72,669
4.2 60% Plans and Estimate 200 50 400 96 84 76 100 200 200 264 200 616 400 320 736 3,942 $31,725 $815,055 8 4 40 52 $8,607
4.2.1 Phase 1, Stetson to Esplanade, 60% Plans and Estimate 96 24 192 12 24 24 48 96 96 64 96 272 192 384 1,620 $12,541 $322,201 8 4 40 52 $8,607
4.2.2 Phase 2, Salt Creek Bridge to Stetson, 60% Plans and Estimate 72 18 144 24 36 36 36 72 72 40 72 184 144 80 288 1,318 $10,581 $271,831
4.2.3 Phase 3, Salt Creek Bridge Widening, 60% Plans and Estimate 32 8 64 60 24 16 16 32 32 160 32 160 64 240 64 1,004 $8,603 $221,023
4.3 90% Plans, Specifications, and Estimate (PS&E) 100 25 200 52 42 38 50 52 180 92 124 92 284 184 128 368 2,011 $16,645 $427,630 12 4 24 8 48 $8,622
4.3.1 Phase 1, Stetson to Esplanade, 90% PS&E 48 12 96 4 12 12 24 72 48 20 48 136 96 192 820 $6,410 $164,670 12 4 24 8 48 $8,622
4.3.2 Phase 2, Salt Creek Bridge to Stetson, 90% PS&E 36 9 72 8 18 18 18 12 60 36 44 36 112 72 48 144 743 $6,034 $155,0194.3.3 Phase 3, Salt Creek Bridge Widening, 90% PS&E 16 4 32 40 12 8 8 40 48 8 60 8 36 16 80 32 448 $4,201 $107,941
4.4 Structures Design Calculations 60 160 120 340 $2,709 $69,6094.5 Structures Independent Check 12 120 160 292 $2,403 $61,743
4.6 100% Plans, Specifications, and Estimate 50 13 100 48 21 19 25 26 142 46 152 46 220 92 68 184 1,252 $10,375 $266,550 2 2 12 4 20 $3,172
4.6.1 Phase 1, Stetson to Esplanade, 100% PS&E 24 6 48 2 6 6 12 28 24 20 24 68 48 96 412 $3,198 $82,158 2 2 12 4 20 $3,1724.6.2 Phase 2, Salt Creek Bridge to Stetson, 100% PS&E 18 5 36 6 9 9 9 6 34 18 32 18 52 36 28 72 388 $3,186 $81,8414.6.3 Phase 3, Salt Creek Bridge Widening, 100% PS&E 8 2 16 40 6 4 4 20 80 4 100 4 100 8 40 16 452 $3,992 $102,552
4.7 Traffic Signal Timing Plans 4 8 12 $101 $2,601 3 10 15 5 155 188 $37,889 TASK 5 – BIDDING AND CONSTRUCTION SUPPORT SERVICES 132 15 66 19 15 15 24 60 60 12 72 490 $4,599 $118,159
5.1 Bidding Support Services 24 3 12 3 3 3 48 $546 $14,0165.2 Construction Support Services 96 12 48 12 12 12 24 48 48 4 24 340 $3,247 $83,4275.3 As-Built Drawings 12 6 4 12 12 8 48 102 $806 $20,716 TOTAL HOURS WITHOUT OPTIONAL TASKS 1,069 128 1,375 389 364 250 489 78 950 498 1,134 710 2,252 1,528 592 1,980 13,777 26 20 104 20 22 192 5 14 33 25 155 -6 -18 6 214 TOTAL COST WITHOUT OPTIONAL TASKS $315,355 $46,720 $323,125 $114,755 $96,460 $66,250 $83,130 $23,010 $251,750 $117,030 $221,130 $127,800 $337,800 $198,640 $145,040 $306,900 $112,276 $36,000 $2,920,516 $7,404 $5,695 $13,493 $2,381 $2,660 $230 $31,863 $1,490 $3,164 $6,600 $3,675 $31,000 -$1,608 -$3,078 $870 $42,113 TOTAL HOURS WITH OPTIONAL TASKS 1,069 128 1,375 389 364 250 489 78 950 498 1,134 710 2,252 1,528 592 1,980 13,777 64 254 152 44 22 536 9 14 33 75 155 4 4 6 300 TOTAL COST WITH OPTIONAL TASKS $315,355 $46,720 $323,125 $114,755 $96,460 $66,250 $83,130 $23,010 $251,750 $117,030 $221,130 $127,800 $337,800 $198,640 $145,040 $306,900 $112,276 $36,000 $2,920,516 $18,225 $72,329 $19,720 $5,238 $2,660 $460 $118,632 $2,682 $3,164 $6,600 $11,025 $31,000 $1,072 $684 $870 $57,097 *Billing Rates will be adjusted in January of each Calendar year by 5%, rounded to the nearest multiple of $5.
TASK DESCRIPTION
LLG ENGINEERS
TOTAL
HOURS
OTHER
DIRECT
COST
TOTAL
COST
TOTAL
HOURS
TOTAL
COST
DOKKEN ENGINEERING
OTHER
DIRECT
COST
ESCALATI
ON TOTAL COST TOTAL HOURS OTHER DIRECT COST
RAILPROS
15.F.
BILLING RATES*
TASK 1 – PROJECT MANAGEMENT
1.1 Meetings and Coordination1.2 Project Administration TASK 2 – DATA COLLECTION, UTILITY COORDINATION, AND SURVEYING/MAPPING
2.1 Data Collection and Field Review2.2 Utility Coordination and Conflict Resolution2.3 Design Survey (Control, Aerial, and Topo)2.4 Right of Way Mapping and Engineering TASK 3 – PRELIMINARY ENGINEERING AND REPORTING
3.1 Conceptual Exhibits and Estimates for Alternative Analysis3.2 Traffic Data, Scoping, and Level of Service Analysis
3.2.1 Data Collection and Research3.2.2 Distribution and Assignment3.2.3 Formulation of Future Traffic Volumes3.2.4 Project Evaluation and Mitigation Analysis3.2.5 Project Evaluation and Mitigation Analysis for Roadway Segments3.2.6 Preparation of the Level of Service (LOS) Analysis Report
3.3 Vehicle Miles Traveled (VMT) Analysis (Optional Task)
3.4 CPUC Permit Application (GO-88B) (Optional Task)3.5 Geotechnical Investigation Report3.6 Traffic Control Plans for Geotechnical Investigations (Optional Task)3.7 Drainage Report
3.7.1 - Phase 13.7.2 - Phase 23.7.3 - Phase 3
3.8 - Bridge Design Hydraulic Report
TASK 4 – PLANS, SPECIFICATIONS, AND ESTIMATES (30%, 60%, 90%, AND 100% PS&E)
4.1 30% Plans and Estimate
4.1.1 Phase 1 30% Plans and Estimate4.1.2 Phase 2 30% Plans and Estimate4.1.3 Phase 3 30% Plans and Estimate
4.2 60% Plans and Estimate
4.2.1 Phase 1, Stetson to Esplanade, 60% Plans and Estimate4.2.2 Phase 2, Salt Creek Bridge to Stetson, 60% Plans and Estimate4.2.3 Phase 3, Salt Creek Bridge Widening, 60% Plans and Estimate
4.3 90% Plans, Specifications, and Estimate (PS&E)
4.3.1 Phase 1, Stetson to Esplanade, 90% PS&E4.3.2 Phase 2, Salt Creek Bridge to Stetson, 90% PS&E4.3.3 Phase 3, Salt Creek Bridge Widening, 90% PS&E
4.4 Structures Design Calculations4.5 Structures Independent Check4.6 100% Plans, Specifications, and Estimate
4.6.1 Phase 1, Stetson to Esplanade, 100% PS&E4.6.2 Phase 2, Salt Creek Bridge to Stetson, 100% PS&E4.6.3 Phase 3, Salt Creek Bridge Widening, 100% PS&E
4.7 Traffic Signal Timing Plans
TASK 5 – BIDDING AND CONSTRUCTION SUPPORT SERVICES
5.1 Bidding Support Services5.2 Construction Support Services5.3 As-Built Drawings
TOTAL HOURS WITHOUT OPTIONAL TASKS
TOTAL COST WITHOUT OPTIONAL TASKS
TOTAL HOURS WITH OPTIONAL TASKS
TOTAL COST WITH OPTIONAL TASKS
*Billing Rates will be adjusted in January of each Calendar year by 5%, rounded to the nearest multiple of $5.
TASK DESCRIPTION
Principal
Engineer/Geologist
Senior Engineer/Geologist
Staff Engineer/Geologist
Technical Illustrator/Cad
Operator
Atterberg Limits
Moisture Content and Dry
Density
Sieve Analysis
Expansion Index
R-Value
Direct Shear
Sulfate and Chloride
Content
pH and Resistivity
Unconfined Compression
Principal Landscape
Architect
Project Manager / Senior
Landscape Architect
CADD
Survey Manager
Senior Land Surveyor
Land Surveyor
Land Surveyor
Party Chief
Rodman
Survey Technician/Drafter
$275 $225 $180 $110 $225 $45 $155 $200 $300 $300 $130 $165 $85 $225 $185 $105 $254 $206 $154 $115 $255 $234 $92 520 $137,019304 $77,087216 $59,933
5 10 15 $80 $3,055 52 160 24 180 184 184 224 1008 $46,292 $227,465 2177 $82,602 $505,544 5 10 15 $80 $3,055 419 $310 $90,320
636 $36,000 $165,667
16 24 144 144 144 472 $46,292 $137,706 502 $46,292 $144,01136 160 180 40 40 80 536 $89,759 620 $105,546 24 121 336 56 10 50 20 10 12 10 19 19 6 693 $282,786 $405,566 6 12 24 42 $6,090 3,296 $283,016 $918,922 6 12 24 42 $6,090 810 $149,929
107 $18,541
6 $1,0904 $588
26 $3,92818 $2,752
6 $1,290
47 $8,89386 $14,984
344 $230 $86,769
24 121 336 56 10 50 20 10 12 10 19 19 6 693 $206,584 $329,364 711 $206,584 $334,098 $76,202 $76,202 $76,202 $76,202
1,168 $221,044
426 $81,086646 $122,602
96 $17,356
156 $32,339
103 412 824 1339 $185,915 11227 $2,244,692
27 108 216 351 $48,735 2,082 $406,03315 60 120 195 $27,075 971 $182,17812 48 96 156 $21,660 783 $151,187 328 $72,669
35 140 280 455 $63,175 4,449 $886,83720 80 160 260 $36,100 1,932 $366,90815 60 120 195 $27,075 1,513 $298,906 1,004 $221,023
27 108 216 351 $48,735 2,410 $484,98715 60 120 195 $27,075 1,063 $200,36712 48 96 156 $21,660 899 $176,679 448 $107,941340 $69,609292 $61,743
14 56 112 182 $25,270 1,454 $294,992
8 32 64 104 $14,440 536 $99,7706 24 48 78 $10,830 466 $92,671 452 $102,552200 $40,490
30 30 $6,750 12 24 40 76 $11,340 596 $136,24910 10 $2,250 2 4 6 $1,190 64 $17,45620 20 $4,500 4 8 16 28 $4,060 388 $91,987 6 12 24 42 $6,090 144 $26,806
24 151 336 56 10 50 20 10 12 10 19 19 6 723 126 458 888 1,472 955 955 955 955 955 955 955 955 17,386 $6,600 $33,975 $60,480 $6,160 $2,250 $2,250 $3,100 $2,000 $3,600 $3,000 $2,470 $3,135 $510 $206,584 $336,114 $28,350 $84,730 $93,240 $80 $206,400 $242,618 $196,405 $147,041 $110,283 $243,191 $223,632 $87,965 $46,292 $227,465 $289,186 $3,764,471 24 151 336 56 10 50 20 10 12 10 19 19 6 723 126 458 888 1,472 52 160 24 180 184 184 224 1,008 17,816 $6,600 $33,975 $60,480 $6,160 $2,250 $2,250 $3,100 $2,000 $3,600 $3,000 $2,470 $3,135 $510 $282,786 $412,316 $28,350 $84,730 $93,240 $80 $206,400 $13,211 $32,906 $3,695 $20,786 $46,856 $43,087 $20,633 $46,292 $227,465 $365,618 $3,942,427
COST PROPOSAL - HOURS BREAKDOWN BY TASK
CITY OF HEMET
WARREN ROAD IMPROVEMENTS
January 30, 2025
TOTAL
HOURS
OTHER
DIRECT
COST
TOTAL
COST
NOVA SERVICES, INC.
TOTAL
HOURS
OTHER
DIRECT
COST
TOTAL COST
RE SERVICES UNICO ENGINEERING, INC.
GRAND
TOTAL
COSTS
OTHER
DIRECT
COSTS
GRAND
TOTAL
HOURS
TOTAL
HOURS
OTHER
DIRECT
COST
TOTAL
COST
15.F.
SERVICES PROPOSAL
Professional Engineering
Services for Warren
Road Improvements
Submitted: January 30, 2025
15.F.
Local Office:
1861 W. Redlands Blvd.
Redlands, CA 92373
(909) 890-1255, [email protected]
Evaluation Period Contact:
Lori Askew
Project Manager
(909) 890-1255 x110
[email protected]
1861 W. Redlands Blvd. | Redlands, CA 92373
(909) 890-1255 | [email protected] | www.erscinc.com
January 30, 2025
City of Hemet
445 East Florida Avenue
Hemet, CA 92543
Attn: Candace Sunds
RE: SERVICES PROPOSAL - Professional Engineering Services for Warren Road Improvements Dear Ms. Sunds,
Engineering Resources of Southern California, Inc. (ERSC) is pleased to have the opportunity to submit our qualifications, in addition to those of our subconsultant, to the City of Hemet (City) as qualified and experienced consultants to provide Professional Engineering Services for the Subject Project. Based upon our review of the RFP, intimate knowledge of various aspects of development near and adjacent to Warren Avenue, site visits, and consultation of available supporting documents, we have developed a thorough understanding of the scope of services and are prepared to provide outstanding service to the City.
John “Matt” Brudin, P.E. - Principal-in-Charge
Matt Brudin will serve as ERSC’s Principal-in-Charge during the term of a potential agreement with the City. Mr. Brudin brings over 30 years of civil engineering experience in complex planning, design, and construction projects. His ability to effectively communicate with agency personnel and team members provides the vital link between client and consultant and ensures that the goals of each project are met. Mr. Brudin has a broad base of experience in various disciplines, including site development, streets and roads, grading and drainage, and flood control facilities. He will provide design guidance, QA/QC, and industry expertise to the ERSC team. Mr. Brudin has a long history of serving the City of Hemet, dating back to 1996 and including preparation of PS&E for State Street widening and Drainage Improvements, evaluation of storm drain alignments and flood plain analysis for Tract 31810, evaluation of various MDP lines, and preparation of a LOMR for Salt Creek Channel at Warren Road.
Lori Askew, Project Manager
Lori Askew will serve as ERSC’s Project Manager during the term of a potential agreement with the City. She has over 30 years of Civil Engineering design and management experience in Public Works projects. She spent 20 of those years as a municipal employee, so she understands the intricacies of working in a local agency. The City can be confident that this project will be executed under the supervision and guidance of highly trained professionals under Lori’s leadership. Ms. Askew has assisted the City of Hemet in various Entitlement reviews, including some that affect Warren Road within the project’s limits.
ERSC understands that the City wants to select the firm that best fits its goals. In selecting ERSC, the City will benefit from the following:
• Familiarity – ERSC has served the City of Hemet since 1996 and has extensive knowledge of several aspects of Warren Road. ERSC has provided similar services to numerous other municipal agencies, and our Project Manager has intimate knowledge of the workings of multiple municipalities.
• Experience – ERSC is proficient in all civil engineering disciplines. Our firm focuses solely on the public sector and public works projects.
• Partners – ERSC has worked closely with the partners listed in this proposal on other projects and selected them based on expertise and experience in the discipline.
By selecting ERSC, the City will benefit from our team’s wealth of knowledge and experience, and we are confident in our abilities to go above and beyond to deliver exceptional service to the City.
This proposal shall be valid for a period of not less than 90 calendar days from the closing date and time of the Request for Proposal.
ERSC takes no exceptions to the City’s Professional Services Agreement and will willingly enter into a contract under its terms and conditions.
We look forward to the possibility of working with the City and thank you for the opportunity to submit this proposal. If you have any questions or require additional information, please contact me at [email protected], (909) 890-1255, ext. 103, or Ms. Askew at ext. 110.
Respectfully submitted,
John M. Brudin, PE, QSD Lori J. Askew
President Page 66 of 248 Director of Engineering
15.F.
Table of Contents
SECTION I - Experience
SECTION II - Personnel
SECTION III - Project Scope
1 6
23
15.F.
SECTION I -
Experience
1
15.F.
<Section Title> SECTION I - Experience
Executive Summary
Engineering Resources of Southern California, Inc. (ERSC) was formed in 1996 with the asset purchase of NBS/Lowry, Inc. Since formation, ERSC has been committed to serving Special Districts, Regional Agencies, and Municipalities in Southern California’s public sector. Our team provides a comprehensive set of professional services and solutions for the life of any potential project.
ERSC Reliability
Our 28-year service record is a testimony to the quality of services we provide. Many of our clients continue to seek our services, and have done so since our first year of business. ERSC has also developed significant financial resources and organizational efficiencies that allow us to consistently exceed client expectations.
Professional &
General Liability
$5.0m Per Occurrence;
$5.0m Aggregate
Automobile $1.0m Combined Single Limit
Worker’s Comp Maintained as Required by Law
Vital Information ERSC Insurance Coverage Levels
CA Corporation
28 Years in Business
40 Employees
FEIN: 33-0718153
CA DIR: 1000017460
Project Contact
Lori Askew
Project Manager
Phone: (909) 890-1255
Fax: (909) 890-0995
[email protected]
Corporate Officers
John M. Brudin, PE - President
Moe Ahmadi, PE - Vice President
Trent Brudin, PE - Secretary
Craig Brudin - Treasurer
Our Locations
San Bernardino County
(Headquarters)
1861 W. Redlands Blvd.
Redlands, CA 92373
Southwest Riverside County
41593 Winchester Rd., Ste. 200
Temecula, CA 92590
Coachella Valley
77-564 Country Club Dr.
Palm Desert, CA 92211
R
P
T
ERSC Professionals
The strength behind ERSC is our qualified and experienced engineers, designers, construction observation personnel, and administrative support staff. We excel at matching the exceptional skills, technical abilities, character, and attitude of our team members to the needs of our clients. ERSC staff works daily to create client partnerships and transform projects from the broadest level of general scope to final planning, design, implementation, and construction resolution.
Many ERSC professionals have experience as municipal and public agency employees and can approach your project with first-hand knowledge of agency culture and how any agency envisions the planning and processing of a well-executed project.
Traffic and Transportation Capabilities
ERSC has provided traffic and transportation planning, design, and construction phase services since its inception. Our traffic and transportation clients include municipalities, government agencies, and special districts throughout the region. Many of these clients have extended service agreements to retain our services outside of the original contract period. These clients benefit from the expertise of our team as we have completed thousands of projects throughout our different clients in the region.
Hemet’s Engineering Resource
ERSC has significant experience in the City of Hemet. The City was home to our first office and was one of ERSC’s first clients. Our firm holds significant records from the City and many of our employees call the City and Valley home. In our experience in providing services to the area, we have noted the following that can enhance ERSC’s level of service compared to others:
Custodian of Hemet Historical Records
ERSC maintains an extensive survey records library with local copies of Riverside County Survey records. Within this collection ERSC has physical records of the Original Layout of the following local historic townsites communities in the Vicinity:
• Town of Florida
• The Hemet Land Company
• The Estudillo Tract
• The Fairview Tract
• Rancho Viejo Tract
• RCFCD
• EMWD
• San Jacinto Land Company
Local Staff
ERSC’s staff have extensive experience working within the City of Hemet. Our CEO and several team members have lived in Hemet, worked out of ERSC’s Hemet Office, and surveyed many projects in the City and nearby. Knowledge of local control, procedures, mapping efforts, and other specifics can allow our team to be exceptionally efficient. 2
15.F.
<Section Title> SECTION I - Experience
Overland Drive Widening | Project Term: 2020 - Ongoing | Contract Value (to date):
$344,276
ERSC provides professional services to complete plans, specifications and estimates related to the widening of Overland Drive from Jefferson Avenue to Commerce Center Drive. The widening project will include the installation of a new traffic signal and striping modifications, and installation of new street lighting including street light plan. ERSC’s project team will also prepare legal descriptions and plats in support of the right-ofway acquisition effort. ERSC will coordinate with the Rancho California and Eastern Municipal Water Districts for relocation and adjustment of water and sewer facilities, as well as various power and communications companies for the relocation of dry utilities impacted by the project.
Murrieta Creek Bridge, CNS Engineers | Project Term: 2019 - Ongoing | Contract Value (to date): $1.5M
As a partner to the CNS Engineers’ team, ERSC is providing engineering design services to the City of Temecula’s Overland/Murrieta Creek Bridge Project. The project will extend Overland Drive through Commerce Center Drive, Enterprise Circle West, over the Murrieta Creek, and connecting to the Avenida Alvarado at the Diaz Road intersection including the construction of two traffic signals at each of the intersections. This ongoing project holds many challenges due to the consolidation and incorporation of several City projects that have been either designed or partially developed. Hydraulic modeling of the creek was prepared to analyze the pre- and post-improvement conditions and impacts as part of the work. ERSC is also responsible for navigating permitting/coordination challenges through various agencies including the Army Corps of Engineers, Riverside County Flood Control District, Rancho California Water District, and Eastern Municipal Water District.
PW20-02 Fifth Street Improvements | Project Term: 2020 | Contract Value: $37,589 Under an on-call engineering agreement, ERSC provided survey and engineering services for preparation of street improvement plans for the north of side of Fifth Street from Front Street to the Murrieta Creek. This project is subject to the elements of the Old Town Specific plan and the design criteria therein. The specific plan requires on-street parking, a 12-foot pedestrian mall, and a round-a-bout. ERSC collected record data, performed survey data collection in the field with 25-foot street cross sections, drafted a conceptual design for approval, and prepared plan specifications and estimates for the project PW 19-11 Bike Lane & Trail Program - Temecula Creek South Side Trail | Project Term:
2020 - Ongoing | Contract Value (to date): $550,286
ERSC is providing the preliminary and final engineering services necessary to provide project scoping and final design for the Temecula Creek South Side Trail Project. The Temecula Creek South Side Trail is part of a larger trail loop identified in the City’s Multi-Use Trails and Bikeways Master Plan Update (Master Plan) as the Temecula Loop.
More specifically identified as Gap Closure Alternative 15(GCA 15). Services required to complete the project will be provided in two (2) phases, including an investigation and summary of the potential issues affecting the project and the development of contract documents including plans, specifications and estimates. The project will be located
CITY OF TEMECULA, CA
ERSC Project Team:
John M. Brudin, PE
Erik T. Howard, PE, PLS
Craig Brudin
Lori Askew
Trent Brudin, PE
Ben Booth, PE
Stephania Hernandez, EIT
Travis Moffatt, EIT
Katherine Hernandez
Laura Bragg, Project Manager
(951) 308-6367
[email protected]
Nino Abad, PE, Project Manager
(951) 308-6385
[email protected]
Chris White, Associate Enginer II
(951) 308-6388
[email protected]
References
The Golden Avenue Bridge at Carbon Canyon channel is located on Golden Avenue approximately 0.2 miles west of Rose Drive. Built in 1934, which is a two-lane reinforced concrete deck bridge with single span. The bridge has been determined to be functionally obsolete per the Bridge Inspection Report prepared by Caltrans.
The project required the removal of the existing bridge and replacement with a new four lane bridge along with appurtenant work including street widening, lighting, and drainage facilities at the bridge approaches as well as curb, gutter and sidewalk.
ERSC provided services for surrounding improvements. Approaching street section improvements, signing/ striping, hydraulic analysis, scour analysis, bridge abutment grading design, channel permitting with the Army Corps of Engineers, and right-of-way engineering.
GOLDEN AVENUE BRIDGE REPLACEMENT, CITY OF PLACENTIA, CA Project Term: 2016-Ongoing | Contract Value: $237,000
ERSC Project Team:
John M. Brudin, PE Katherine Hernandez
Masoud Sepahi, P.E., City Engineer
(714) 993-8148
[email protected]
3
15.F.
<Section Title> SECTION I - Experience
5th St/Greenspot Rd Bikeway Improvements | Project Term: 2013-19 | Contract Value:
$143,860
ERSC was retained by the City of Highland to engineering and construction services for the City’s widening of 5th Street/Greenspot road and bikeway improvements. As the City completed the new Greenspot Bridge over the Santa Ana River, it was necessary to widen the road and the old iron bridge would be access restricted to bicycle and pedestrian traffic. Upon completion 5th Street/Greenspot Road would be widened to accommodate 2 travel lanes in each direction with a painted center median and bike lanes. Total length of the widening was approximately 6,000LF. At Santa Ana Canyon Road, the Bikeway would be taken out of the Greenspot Road alignment and onto a new trail system. This trail would include a fully signed and striped bike/pedestrian trail that followed the previous alignment of Greenspot Road. This trail includes the historic Iron Bridge at Santa Ana Canyon Road. As a part of the project, ERSC designed the trail, signing/striping, and 30 way finding signs/access points along the alignment.
Tippecanoe Pavement Rehabilitation | Project Term: 2021 | Contract Value: $150,535 ERSC provided professional engineering services related to Cooperative City/County Pavement Rehabilitation Project, str20003 pavement rehabilitation of five street reaches covering four streets. For Tippecanoe Avenue, existing AC and native material was pulverized in place, a portion of the pulverized material removed, cement added to the remaining pulverized material, followed by placement of HMA and RHMA for the reach from 3rd to 6th.
Sector E Pavement Rehabilitation | Project Term: 2020-21 | Contract Value: $203,595 (to date)
ERSC was retained by the City of Highland to provide engineering services related to the City’s proposed Pavement Management Program, Sector E, Pavement Rehabilitation, str20001. The City has proposed rehabilitation of 15 streets in Sector E, located in the southeast portion of the City in an effort to complete implementation of its comprehensive 5-Year Pavement Management Program (PMP). The project is funded with SB – 1, local Measure I, and RAC grant funds.
The scope of work will also likely include design for features and/or replacements not yet identified nor quantified to protect the pavement investment from drainage damage and assure ADA compliance. Additionally, formal striping/marking plans are anticipated to be required for the single arterial street, Greenspot Road. A flood channel crossing of Webster Street is located in SBCFCD right-of-way, and therefore may also entail coordination/permitting from that agency.
ERSC will conduct site visits to assess condition/location of the drainage related issues and of ADA compliance issues concerning damaged or missing ramps. To further assist we will contract with a subconsultant geotechnical firm for a visual inspection of all streets and additional subsurface investigation for the single arterial, Greenspot Road. 2018-2019, 2019-2020 & 2020-2021 CDBG Pavement Improvements | Project Term:
2018-22 | Contract Value: $95,442
ERSC was retained by the City of Highland to provide engineering services for two CDBGfunded projects, for years 2018-19 and 2019-20. Both projects involve site inspection, pavement evaluation, review of drainage and ADA issues and preparation of construction documents for rehabilitation and repair. That for ola2018-2019 involves two streets, Elmwood Road, from Baseline to Fisher Street (1,800 linear feet); and Walker Street from Sterling Avenue to East end, (960 linear feet). Ola 2019-2020 includes two streets also,
CITY OF HIGHLAND, CA
ERSC Project Team:
John M. Brudin, PE
Trent Brudin, PE
Lori Askew
Carlos Zamano, P.E.
Assistant Public Works Director
(909) 864-6861
[email protected]
on the south side of Temecula Creek and consist of 2.5 Miles of Class I Bike Trail, ADA improvements, 6 community access points, and will replace a rip-rap low flow drop structure with a concrete structure to allow bike and pedestrian crossing of the creek.
Traffic Signal System – Rancho California Road & Tee Drive | Project Term: 2020-21 | Contract Value: $27,379
Under an on-call engineering agreement, the City of Temecula contracted with ERSC for the design a new traffic signal system at the intersection of Rancho California Road and Tee Drive, including a new power source. Aside from typical utilities, ERSC’s work included exploration and evaluation of several blow offs, valves and manholes valves within or adjacent the intersection that indicating there is water, recycled water and sewer in the vicinity, as well as overhead electrical lines along the south side of the intersection. In addition to the utilities, the proposed design will incorporate necessary features to facilitate bicycle crossings at the intersection per the City of Temecula’s Multiuse Trails and Bikeways Master Plan. 4
15.F.
<Section Title> SECTION I - Experience
Del Rosa Avenue from 4th Street to 5th Street (720 linear feet), and Elm Street, from 6th Street to 9th Street (2,040 linear feet).
Funding will be provided by the Community Development Block Grant Program (CDBG) administered by the County of San Bernardino Development and Housing Department.
Specification document, therefore, will include applicable federal requirements. ERSC will coordinate with a subconsultant firm to conduct field investigations and provide recommendations for pavement and rehabilitation methods and costs.
A preliminary site inspection and recent experience and City practice indicate that rehabilitation is expected to include repair of severely distressed areas by pavement removal and replacement, crack repair/seal, bump grind, edge repair, header cut and cold planing, repair of drainage issues that would compromise new paving, repair of soft or wet subgrade, and HMA overlay.
Paloma Wash Pedestrian Bridge | Project Term: 2022 - Ongoing | Contract Value (to date): $235,940
ERSC was contracted to prepare plans, specifications and cost estimates for the construction of a Pedestrian Bridge crossing the Paloma Wash. The approximate location of the bridge crossing is just southerly of Marketplace Road’s intersection with Haun Road, which is approximately 1,300 feet south of Newport Road. The bridge will provide access from the Countryside Marketplace located on the east side of Haun Road to the mixed use Town Center area and Central Park located on the west side of Haun Road. Work includes project management, preparation of Plans, Specifications, and Estimates (PS&E), preparation and submittals to environmental permitting agencies and environmental surveys as needed, utility coordination, coordination with other jurisdictional agencies, community outreach, and bidding and construction support.
CITY OF MENIFEE, CA
ERSC Project Team:
John M. Brudin, PE, QSD
Lori Askew
Reza Toorzani, PE
Robert Righetti
Moe Ahmadi, PE, QSD
Erik Howard, PE, PLS
Craig Brudin, QSP
Stephen Wilson, QSD
Katherine Hernandez
Nick Fidler, Director of Public Works/
Engineering
(951) 723-3703
[email protected]
5
15.F.
SECTION II -
Personnel
6
15.F.
<Section Title> SECTION II - Personnel
John M. Brudin, PE
Principal in Charge
Project Manager
Lori Askew
Project Team
Ben Booth, PE
Project Engineer - Roads
Katherine Hernandez
Design Engineer - Roads
Moe Ahmadi, PE
Project Engineer - Storm Drain/Hydrology
Stephania Hernandez, EIT
Design Engineer - Storm Drain/Hydrology
Robert Ollerton, PLS
Principal Surveyor - Survey & Mapping, Legals & Plats
Craig Brudin, QSP
STC Traffic, Inc.
Traffic Engineering
Community Works Design Group
Lanscape Architecture
Aragon Geotechnical, Inc.
Geotechnical Engineering
Biggs Cardosa Associates, Inc.
Bridge Engineers
Inland Aerial Surveys, Inc.
Aerial Topography
Subconsultants
Additional ERSC Team
Trent Brudin, PE, QSD
Engineering Manager
Reza Toorzani, PE
Principal Engineer
Erwin Fogerson, PE
Sr. Principal Engineer
Jeff Wall, PE
Sr. Principal Engineer
Robert Righetti
Principal Engineer
Travis Moffatt, EIT
Engineer II
Steve Wilson
Sr. Engineering Associate
John Ward
Sr. Engineering Associate
Jazz Goodie
Engineering Associate III
Joseph Wilkins
Engineering Associate III
Gabriela Rodriguez
Engineering Aide I
Nathan Shea, EIT
Engineer II
Marcus Popa, EIT
Engineer II
Zoey Dunmire
Engineer II
Isaac Gomez
Engineer IV
Mina Bishara
Engineer V
7
15.F.
Over the past 28 years, Mr. Brudin has been
involved in a number of complex planning,
design and construction projects. His ability
to effectively communicate with agency
personnel and team members provides
the vital link between client and consultant
and ensures that the goals of each project
are met. Mr. Brudin has a broad base of
experience in various disciplines including
water resources, site development, streets
and roads, grading and drainage and flood
control facilities.
Mr. Brudin has served as a District
Engineer for the Lake Hemet Municipal
Water District, City Engineer for the City
of Hemet, and 1as a Project Manager for
“as-needed” professional engineering
plan check services for several cities in
the Orange, Riverside and San Bernardino
County areas. Under these contracts, he
has managed construction inspection/
administration, development review, and
plan check services for land development
and capital projects, including grading,
water, sewer, drainage, traffic signal and
street improvement plans.
CA, Civil Engineer No. C41836
QSD/QSP No. 00707
BS, Civil Engineering, Loyola Marymount
University, Los Angeles, CA
American Public Works Assc.
Floodplain Management Assc.
Water/Wastewater Engineering
Flood Control Engineering
Project Management
Quality Control
Education
Affiliations
Areas of Expertise
Similar Project Experience:
Overland Bridge at Murrieta Creek, CNS Engineers, Temecula, CA - Principal in Charge responsible for technical and budget oversight, resource allocation and contract management throughout the assignment. Design of a bridge structure over and across Murrieta Creek connecting Avenida Alvarado at the intersection of Diaz to the west of the creek, with Overland Drive at the intersection of Enterprise Circle to the east of the creek.
Traffic Signal System – Rancho California Road and Tee Drive, City of Temecula, CA – Principal in Charge responsible for technical and budget oversight, resource allocation and contract management throughout the assignment. Design and utility coordination for a new traffic signal system, including a new power source. Exploration and evaluation of several blow offs, valves and manholes valves, as well as overhead electrical lines along the south side of the intersection. Staff are also exploring removing existing streetlights in the intersection and replacing with traffic signal safety lighting. The City is also currently undergoing streetlight conversions to LED as a part of the WRCOG Regional Streetlight Program. The proposed design will incorporate necessary features to facilitate bicycle crossings at the intersection per the City of Temecula’s Multi-use Trails and Bikeways Master Plan.
State Street Gap Closure Project, City of San Bernardino, CA – Principal in Charge responsible for technical and budget oversight, resource allocation and contract management throughout the assignment. Roadway design and environmental clearance for the Street; a vital transportation corridor. State Street will be a four-lane roadway with a center median and bike lanes connecting Baseline Street to State Route 210. 40th Street Widening Project, City of San Bernardino, CA – Principal in Charge responsible for technical and budget oversight, resource allocation and contract management throughout the assignment. Design of the 40th Street Widening Project in San Bernardino. 40th Street is to be widened to allow 4 travel lanes, new sidewalk, and drainage improvements. The project stretches from Victoria Ave to Kendall Drive. Also included is traffic signal modifications at Electric Ave. and drainage modifications.
Golden Avenue Bridge Replacement Project, Biggs Cardoza Associates, Placentia, CA - Principal in Charge responsible for technical and budget oversight, resource allocation and contract management throughout the assignment. Development of plans for the bridge replacement project in Orange County. ERSC coordinated plans for channel modification and permitting with ACOE.
Riverside Drive Street Widening, Signal Modifications, Signing and Striping, Lake Elsinore, CA - Principal in Charge responsible for technical and budget oversight, resource allocation and contract management throughout the assignment. Development of program documents and planning and design activities related to the reconstruction of an existing campground located along Riverside Drive on the westerly end of Lake Elsinore. Coordinated completion of all CalTrans requirements to facilitate completion of the project.
Washington Street at Fred Waring Drive Triple Left Turn Lanes Project, City of La Quinta, CA – Principal in Charge responsible for technical and budget oversight, resource allocation and contract management throughout the assignment. Design of intersection modifications incorporating a third left turn lane in each direction to reduce traffic during peak hours. The scope also included CEAQ document preparation, utility coordination and PS&E.
John M. Brudin, PE | President
8
15.F.
Ms. Askew has over 30 years of experience
in design and management of public and
private improvement projects. She has
spent the past 20 years as a local municipal
employee in Public Works with the last
eight years in an executive management
position overseeing various levels of
staff and consultants. She has managed
Capital Improvement Program projects
for streets, storm drains, water and sewer
in addition to large land development
projects with significant grading
challenges. She is very knowledgeable in
understanding the workings and challenges
of local government and comprehends the
constraints of various City funding sources
such as Gas Tax, Measure A and SB1.
Ms. Askew has been city liaison to Western
Riverside Council of Governments (WRCOG),
Riverside County Flood Control & Water
Conservation District, Caltrans, Riverside
County Transportation Commission (RCTC),
several water districts and school boards.
Land Development
Municipal Engineering
Traffic and Transportation
Airport Design
Areas of Expertise
BS, Civil Engineering, Michigan Technological
University, Houghton, MI
Education
Similar Project Experience:
City Engineering Support Services, Project Manager, City of Hemet, CA - Under ERSC’s employment, Lori has served the City of Hemet’s Engineering Department since January of 2023 in the review of proposed private development projects seeking Entitlement.
She reviews submitted documents and writes conditions of approval for submittal to the Planning Department in their preparation for staff reports to be presented to the Planning Commission.
Murrieta Creek Bridge, City of Temecula, CA - Project Manager responsible for day-today project guidance, team oversight, client contact, as well as schedule and budget management throughout the assignment. As a partner to the CNS Engineers’ team, ERSC designed a bridge structure over and across Murrieta Creek connecting Avenida Alvarado at the intersection of Diaz to the west of the creek, with Overland Drive at the intersection of Enterprise Circle to the east of the creek.
Overland Drive Widening, City of Temecula, CA - Project Manager responsible for dayto-day project guidance, team oversight, client contact, as well as schedule and budget management throughout the assignment. ERSC completed an analysis of the impacts related to the widening of Overland Drive from Jefferson Avenue to Commerce Center Drive. At Overland Drive and Commerce Center Drive, a previous project resulted in the installation of conduit and pull boxes associated with future traffic signal construction and the previously installed conduit and pull boxes, and the easterly leg of Overland Drive, require reconstruction. The widening project included the installation of a new traffic signal and striping modifications, and installation of new street lighting including street light plans developed per industry standards and City of Temecula standards and guidelines.
PW 19-11 Bike Lane and Trail Program, Temecula Creek South Side Trail, City of Temecula, CA - Project Manager responsible for day-to-day project guidance, team oversight, client contact, as well as schedule and budget management throughout the assignment. Under an on-call engineering agreement, ERSC compelted preliminary and final engineering services necessary to provide project scoping and final design. Services required to complete the project were provided in two (2) phases, including an investigation and summary of the potential issues affecting the project and the development of contract documents including plans, specifications and estimates.
State Street Gap Closure Project, City of San Bernardino, CA - Project Manager responsible for day-to-day project guidance, team oversight, client contact, as well as schedule and budget management throughout the assignment. Design for roadway design and environmental clearance for the Street; a vital transportation corridor. State Street will be a four-lane roadway with a center median and bike lanes connecting Baseline Street to State Route 210. The design includes a new roadway in the portion of the project where no transportation infrastructure exists, rehabilitating existing portions to updated standard, and ROW acquisition is required to complete the project.
Tippecanoe Pavement Rehabilitation Project, City of Highland, CA - Project Manager responsible for day-to-day project guidance, team oversight, client contact, as well as schedule and budget management throughout the assignment. Also assisted with survey tasks. ERSC provided professional engineering services related to Cooperative City/County Pavement Rehabilitation Project, str20003 pavement rehabilitation of five street reaches covering four streets. For Tippecanoe Avenue, existing AC and native material was pulverized in place, a portion of the pulverized material removed, cement added to the remaining pulverized material, followed by placement of HMA and RHMA for the reach from 3rd to 6th.
County Line Road Transportation Corridor Improvement Project: Project Manager for design and construction of street improvements including pavement widening to include bike lanes, installation of curb, gutter, sidewalk and construction of round-abouts at 4 intersections. Project is joint improvement project with adjacent city, as street centerline is City and County boundary. Project challenges include various funding sources through grants, coordination with adjacent city/county, right-of-way acquisitions, and construction in phases.
Third Street Improvement Project: Project Manager responsible for overseeing design Lori Askew | Principal Engineer
9
15.F.
Lori Askew | Principal Engineer
and construction of 3,300 linear feet of Third Street from Valley View Avenue to Corona Avenue which includes removal of existing asphalt street and replacement with full street improvements, within existing right-of-way, consisting of curb, gutter, asphalt pavement, equestrian trail with fence, replacement of private improvements to match new grades. Also included were storm drain improvements on Reservoir Drive, north and south of Third Street which involved installation of over 1,800 linear feet of 30-inch HDPE pipe and 400 linear feet of smaller size HDPE pipe.
Arrow Boulevard and Cypress Avenue Traffic Signal Project, City of Fontana, CA - Project Manager responsible for day-to-day project guidance, team oversight, client contact, as well as schedule and budget management throughout the assignment. Work included development of plans, specifications and estimates and other engineering services to signalize the intersection using traffic signal poles and mast arms, while constructing minor improvements including curb access return ramps to ultimate locations determined by the Hierarchy of Streets Plan, curb and gutter, extending and/or improving the existing concrete bus pads adjacent to the intersection, and an asphalt concrete transition to the existing asphalt concrete pavement.
Infrastructure and Roadway Improvements for Lake Park Drive, Soboba Band of Luiseño Indians - Project Manager responsible for day-to-day project guidance, team oversight, client contact, as well as schedule and budget management throughout the assignment.
Providing civil design services to Soboba Economic Development Corporation (EDC) for the site improvements including design and preparation of plans for onsite infrastructures and also road widening for Lake Park Drive.
Design of the Easton Street Sidewalk Improvements, City of Rialto, CA - Project Manager responsible for day-to-day project guidance, team oversight, client contact, as well as schedule and budget management throughout the assignment. Work includes engineering/ planning for the construction of Americans with Disabilities Act (ADA) compliant sidewalk and curb ramps along the north and south sides of Easton Street between Acacia Avenue and Sycamore Avenue; to additionally include general sidewalk repair between Sycamore Avenue and E. Highland Avenue and from the southeast corner of Easton Street and Acacia Avenue to approximately 250 feet south.
Hamner Avenue Widening Project: Project Manager responsible for overseeing the design and construction of 3,600 linear feet of Hamner Avenue from the north City boundary to north of the Hamner Avenue Bridge. Hamner Avenue was widened from a two-lane street to three lanes in each direction but currently striped for two in each direction. Improvements include curb, gutter, sidewalk, asphalt pavement, relocation of a City of Norco 20-inch potable waterline, installation of a 30-inch waterline owned by the Chino Desalter Authority (as part of their future expansion), and storm drain improvements. The traffic signal at Citrus Street was modified for a four-way intersection to accommodate the future Silverlakes Equestrian and Sports Park. A 42-foot-wide by 15-foot-high causeway was constructed under Hamner Avenue south of Citrus Street to provide flood relief from the adjacent Santa Ana River and also provide access to the adjacent park on the west side of Hamner Avenue located in the City of Eastvale. A detention basin was constructed as part of the project and resides on the west side of Hamner Avenue, south of Citrus Street and acts as a desilting basin for the 72” storm drain that discharges to it. Hamner Avenue design took into consideration the future replacement of the Hamner Avenue Bridge.
Cherry Valley Boulevard/I-10 Interchange: City Liaison to Riverside County Transportation Department who is acting as lead for the City of Calimesa on this project. The Project is the reconstruction of an interstate freeway interchange to accommodate significant residential and commercial growth surrounding the interchange. The Project is being processed through Caltrans with the Project Study Report having been completed and approved in 2018. It is now in the PA/ED phase. Interchange configuration alternatives being considered are Round-Abouts, Diverging Diamond and Partial Cloverleaf. Funding is secured up to the construction phase through Developer Impact Fees and credit agreements with the Western Riverside Council of Government’s (WRCOG) Traffic Uniform Mitigation Fee (TUMF) program.
Silverlakes Equestrian and Sports Park: Project Manager overseeing the concept creation, planning and construction of a City owned 122-acre parcel of land with a federal deed restriction over it for Park use only. Challenges included parcel being located in a flood zone adjacent to the Santa Ana River, working with the Army Corp of Engineers after a flooding of the property occurred during construction, development being funded privately by developer and crafting a 99-year lease to developer. Project has 25 soccer fields including natural and synthetic turf, competition horse arenas, paved and porous parking lots and eating facilities.
Bluff Street and Western Avenue Waterline Improvements: Project Manager for design of replacement of 3,200 linear feet of 16-inch CML & C waterline in Bluff Street and installation of 1,200 linear feet of 12-inch CML & C waterline in Western Avenue. The 16-inch waterline experienced several breaks over the past few years resulting in claims against the City. The line was originally constructed as a transmission line but over the years residential connections were allowed to be made to it. The installation of the water line in Western Avenue completed a loop system for the water system in the area.
Vine Street and Sagetree Lane Waterline Improvement Project: Project Manager responsible for overseeing design and construction of replacement of an 8-inch waterline in Vine Street with a 12-inch CML & C waterline from Bluff Street to Corydon Avenue and replacement of a 6-inch waterline in Sagetree Lane with an 8-inch CML & C waterline. Both lines had experience multiple break over the past few years. As the project was under construction it was decided to add replacement of a 10-inch waterline in Corydon Avenue that connects to the new 12-inch waterline at Vine Street. The replacement line was also upsized to 12-inch CML & C.
Second Street Improvement Project: Project Manager overseeing the design portion of the project which was done by a contract engineer beginning in late 2004. The project consisted of widening Second Street, a designated collector street, to its ultimate rightof-way between the I-15 Freeway and Corona Avenue, with full street improvement consisting of curb, gutter, asphalt pavement, pedestrian-equestrian trail with fence, realignment of the intersection with Valley View Avenue, storm drain improvements and utility relocations. Design also included pavement rehabilitation of Second Street from Corona Avenue to Hillside Avenue. Land acquisition 10
15.F.
Lori Askew | Principal Engineer
and coordination with Caltrans delayed construction of the project which did not begin until early 2011. Additional responsibilities for this project include construction management where I was responsible for overseeing all aspects of construction.
Calimesa Creek Storm Drain Improvements: Project manager overseeing design and construction for nearly 2,000 lf of 18” – 78” RCP storm drain pipe, 200lf of 6’ x 6’ concrete box structure and 53-acre-foot detention basin. Project will minimize erosion of Calimesa Creek by transitioning from an open channel system which currently discharges into Calimesa Creek, to a closed system. Only low flows will remain in the Creek, thus eliminating the need to mitigate significant acreage. Detention Basin upstream eliminates the need for existing pipe at downstream end of system to be enlarged under the I-10 freeway. Project is funded with EPA grant, Riverside County Flood Control & Water Conservation District Funds and City Development Impact Fees.
Navy to Norco College (RCC) Sewer Improvements: Project designer and project manager overseeing construction of 1,100 linear feet of 8-inch VCP sewer line and related appurtenances from a lift station located on Navy property to a city owned SSMH located on the Norco College Campus. The biggest challenges for the project was finding a route through the Norco College Campus that allowed the sewer line to flow by gravity and a construction schedule that minimized disruption to the Campus.
John Wayne Airport, Taxiway “L” Reconstruction, Santa Ana, CA: The project included the reconstruction of Taxiway “L” and a detailed phasing plan to minimize disruptions to air service. Responsible for geometric layout of service road, airfield lighting and signage and quantity take-offs.
Tucson International Airport Terminal Expansion, Tucson, AZ: Project Engineer responsible for the design of the revised Airport Roadway system. A new two-level roadway replaced the existing enplaning and deplaning roadway due to the expansion of the terminal. Several hundred feet of new MSE wall was incorporated at the beginning and end of the bridged upper roadway. Commercial roadways were expanded and relocated to provide for increased commuter parking. Additional responsibilities included site grading and drainage and coordination with all disciplines. Responsible for site geometry, demolition and phasing, along with production of drawings from concept to construction document level.
United Parcel Service Air Gateway and Parcel Distribution Facility, Long Beach, CA: Project Engineer responsible for all civil engineering aspects to develop a 7.5-acre site located at the long Beach Airport that would be the new location for UPS operations at the airport.
Responsibilities included site layout for two buildings, aircraft parking apron adjacent to Taxiway “L”, fire and domestic water, storm drainage and sewer. In addition, grading and drainage proved challenging as the site need to be maintained as a storm retention area.
Close coordination with City, State and Airport personnel was necessary to meet the tight design and construction schedule set by the owner to be in operation for their busy season.
Ontario International Airport Ground Transportation Center, Ontario, CA: Project Engineer in the design and development of a 35- acre consolidated rental car facility with a 15,000 square foot rental counter building, ready and return lots, and connector road to the airport. Responsible for road geometry, site grading, and drainage and all site wet utilities; processing plans through various government agencies and providing support during construction.
San Diego International Airport, Lindbergh Field, San Diego, CA: Principle designer in preparing site demolition plans including 100,000 cy of export; horizontal and vertical alignment of temporary haul routes; and coordination of existing site utilities. Principal designer for Concourse F – Terminal 2 which included horizontal and vertical roadway design water, sewer and storm drain design and setting apron pavement grades.
11
15.F.
Similar Project Experience:
Overland Bridge at Murrieta Creek, CNS Engineers, Temecula, CA - As a partner to the CNS Engineers’ team, served as Project Engineer during the design of a bridge structure over and across Murrieta Creek connecting Avenida Alvarado at the intersection of Diaz to the west of the creek, with Overland Drive at the intersection of Enterprise Circle to the east of the creek. The ERSC team was responsible for all ancillary improvements to the design of the bridge. Street improvements, drainage improvements, legals/plats, hydraulic/hydrology analysis, and WQAR were all facilitated in house by the ERSC team.
La Cadena and 8th Street Intersection Reconfiguration, City of Colton, CA – Project Engineer during reconfiguration of the La Cadena & 8th Street intersection. Staff created a concept considering the wishes of City staff and council members that would reconfigure the intersection. The new concept included a free right bypass lane protected by raised median for north west traffic on La Cadena. Traffic from surrounding residential streets would stop at the new intersection with turn restrictions and channeled through raised medians for additional traffic calming. The reconfiguration of the intersection also required reconfiguration of existing drainage improvements.
Pavement Management Program, Signing and Striping, City of Highland, CA – Engineer II in the development of street/signing & striping plans and engineering estimates for residential pavement rehabilitation in Highland and San Bernardino, CA. Benjamin assisted in the drafting of plans as well as the construction cost and quantity estimates.
State Street Gap Closure Project, City of San Bernardino, CA - Project Engineer during the design for roadway design and environmental clearance for the Street; a vital transportation corridor. State Street will be a four-lane roadway with a center median and bike lanes connecting Baseline Street to State Route 210. The design includes a new roadway in the portion of the project where no transportation infrastructure exists, rehabilitating existing portions to updated standard, and ROW acquisition is required to complete the project.
Golden Avenue Bridge, Placentia, CA – Project Engineer during the development of plans for the bridge replacement project in Orange County. Plan and profile views were created for the proposed bridge layout and the existing Carbon Creek flood control channel below. Considerations during geometric layout included aligning with existing streets, identification of existing utilities and storm drains, proposing new storm drain locations, an adequate bridge width to accommodate future traffic, pedestrian and bike flows, and the placement of the OC Bike Loop that is planned to run within the Carbon Creek channel which has entrance/exit ramps on either side of the bridge. Bridge design was provided by Biggs Cardosa Associates, Inc.
PMP Sectors A, D and E Pavement Rehabilitation, City of Highland, CA - Construction Manager responsible for contract administration, progress meetings, material/RFI submittals, correspondence, labor compliance, and progress payment review. The project included pavement rehabilitation by pavement grinding, bump grind, pavement removal and replacement, crack sealing and repairs, asphalt pavement overlay, replacement of curb and gutter, and striping and markings of arterial, collector, and local streets throughout the City.
FY 2016/17 and FY 17/18 CDBG Pavement Rehabilitation, City of Highland, CA - Construction Manager responsible for contract administration, progress meetings, material/RFI submittals, correspondence, labor compliance, and progress payment review. The project included site inspection and preparation of construction documents for rehabilitation and repair of pavement on six streets. Rehabilitation included repair of severely distressed areas by removal and replacement, crack repair/seal and bump grind, edge repair, header cut and cold planing, repair of drainage issues that would compromise new paving, repair of soft or wet subgrade, and HMA overlay.
Sectors B, C, D, and E Pavement Rehabilitation and Preventative Maintenance Projects, City of Highland, CA - Construction Manager responsible for contract administration, progress meetings, material/RFI submittals, correspondence, labor compliance, and progress payment review. The projects included pavement preventative maintenance by bump grind, crack seal, slurry seal, and scrub seal of collector and local streets throughout the City and maintenance of City parking lots.
Mr. Booth has a broad base of experience
in various disciplines such as site
development, street improvements, and
grading and drainage, pavement rehab
design and construction, and utility design.
Mr. Booth is a recent graduate from Arizona
State University and interned with notable
companies such as Schuler Constructors,
PACE, and HDR during his undergraduate
studies. He worked for a local private
engineering consultant where he served as
a survey chairman and a design engineer.
Projects recently undertaken by Mr. Booth
involving the design and construction
services include the following significant
assignments.
CA, Professional Engineer No.92625
BS, Civil Engineering, Arizona State University,
Tempe, AZ
Pavement Rehabilitation Services
Utility Services
Land Development Services
Education
Areas of Expertise
Ben Booth, PE | Engineer V
12
15.F.
Similar Project Experience:
State Street Gap Closure Project, City of San Bernardino, CA, 2019-Present, $540k to date - Project Engineer for roadway design and environmental clearance this vital transportation corridor. State Street will be a four-lane roadway with a center median and bike lanes connecting Baseline Street to State Route 210. The design includes a new roadway in the portion of the project where no transportation infrastructure exists, rehabilitating existing portions to updated standard, and ROW acquisition is also required.
Washington Street at Fred Waring Drive Triple Left Turn Lanes, City of La Quinta, CA, 2019-21, $165k – Project Engineer assisting in design of improvements to this high traffic intersection by adding a third, left turn lane in each direction of the intersection in order to alleviate traffic congestion and improve traffic flow. Ms. Hernandez also assisted on the detailed project description, plans, bid schedules, bid item descriptions, payment methods, engineer’s estimate, special provisions, technical specifications, and any specification detail sheets and relevant standard plans.
Traffic Signal System, Rancho California Road and Tee Drive, City of Temecula, CA, 2020- 21, $27k - Project Engineer during the design and utility coordination for a new traffic signal system, including a new power source. Work includes exploration and evaluation of several blow offs, valves and manholes valves, as well as overhead electrical lines along the south side of the intersection. In addition to the utilities, the proposed design will incorporate necessary features to facilitate bicycle crossings at the intersection per the City of Temecula’s Multi-use Trails and Bikeways Master Plan.
Design of Murrieta Creek Bridge, City of Temecula, CA, 2020-Present, $316k to date – Assisting in the design of a bridge structure over Murrieta Creek connecting Overland Drive at the intersection of Enterprise Circle West on the east side of the Creek to Avenida Alvarado at the intersection of Diaz Road on the west side of the Creek. Ms. Hernandez also assists on the PS&E and utility research and coordination.
Aliso Creek Road Rehab from Aliso Viejo Parkway to SR-73, City of Aliso Viejo, CA, 2017-Present, $47k – Project Engineer on the design of this rehab project, which included the grind and overlay of the roadway, localized full depth replacements, signing and striping, traffic signal loops, traffic control and Caltrans Coordination. The project involved additional detailed design of ADA ramps at the SR-73 interchange and obtaining a Caltrans Encroachment permit.
Golden Avenue Bridge Replacement Project, Biggs Cardoza Associates, Placentia, CA, 2017-20, $107k - Project Engineer during the development of plans for the bridge replacement project in Orange County. ERSC coordinated plans for channel modification and permitting with ACOE. ERSC also provided geometric layout including aligning with existing streets, identification of existing utilities and storm drains, proposing new storm drain locations, an adequate bridge width to accommodate future traffic, pedestrian and bike flows, and the placement of the OC Bike Loop that is planned to run within the Carbon Creek channel.
Rancho Ave. A & N Street Intersection Improvements, City of Colton, CA, 2020-Present, $37k to date - Project Engineer during traffic and civil engineering services to the City of Colton to improve safety at the Rancho Avenue and N Street intersection. The new intersection will include reduced lanes from 2 to 1 approaching the intersection, signing/ striping improvements, permanent delineators, and a CalTrans High Tension Barrier System. Also provided services for design survey, pavement reconstruction, raised median, ADA, and curb and gutter improvements.
Katherine Hernandez | Engineer III
Ms. Hernandez is proficient in geographic
and environmental engineering, able to
identify and solve problems related to
environmental, geographical and territorial
resources, interrelated with social
processes and territorial ordering through
sustainable development. Qualified to make
cartography with modern technologies
related to geographic information systems
(GIS).
BS, Geographic and Environmental
Engineering, University of Applied and
Environmental Sciences (UDCA), Bogotà,
Colombia
Environmental Analysis
Water Resources
Planning
Education
Areas of Expertise
13
15.F.
Over the past 30 years Mr. Ahmadi has actively
participated in the preparation of numerous
feasibility studies, design reports, construction
plans, specifications and cost estimates for
drainage and flood control facilities throughout
Southern California. Mr. Ahmadi is experienced
with numerous computer programs including
AutoCAD 2019, CivilCAD Hydrology programs,
Water Surface Profile Gradient (WSPG), and
HEC-RAS flood plain analysis software.
He is also experienced in preparation of Storm
Water Prevention Plan (SWPPP) as required
by the NPDES Industrial General Permit and
the Construction General Permit (CGP), which
identify BMPs used to reduce or eliminate
potential pollutant discharges in storm water
runoff. Under his direction, plans for various
residential, commercial, and industrial projects
in the Counties of Riverside, San Bernardino,
and Orange have been prepared. As part of
the requirements of the CGP, Mr. Ahmadi
has provided SWPPP services to address new
requirements. This work included Data Submitter
services, conducting the risk assessment; an
evaluation of a project’s sediment risk and
receiving water risk, and then determining the
overall Risk Level for traditional projects, or
LUP Type for linear utility projects, and assisting
clients to register and submit applications in the
SMARTS System to obtain the applicable WDID
numbers from the SWQCB prior to construction.
Water Resources, Flood Control, Hydraulics
and Hydrology, Erosion Control
Areas of Expertise
American Society of Civil Engineers
National Society of Prof. Engineers
BS, Civil Engineering, Texas A&M University
College Station, TX
MS, Civil Engineering Construction
Management, Texas A&M University, College
Station, TX
Affiliations
Education
CA, Civil Engineer No. C58784
QSD/QSP No. 00706
Similar Project Experience:
East Drop Structure Repair Mitigation Within Whitewater River Channel, City Of Indian Wells, Indian Wells, CA – Project Manager for redesign of the East Drop Structure along the Whitewater River. Site analyses and development of potential replacement structures such as a concrete drop structure that incorporates a baffle chute at the outlet of the low flow channel, a USBR stilling basin or a drop structure similar to the one constructed in 1995 using materials sized to withstand the anticipated flows. Regulatory permitting and clearance for an RWQCB CWA Section 401 Water Quality Certification, CDFW 1602 Streambed Alteration Agreement, USACE Nationwide Section 404 Dredge and Fill Permit, and CEQA IS/ MND coordination.
CSPD Line 3-5, and Master Drainage Plan (MDP) Update, City of Colton, CA – Managing Engineer for a Master Plan Update and the design of a regional drainage facility to convey 1,000 cfs from a 2,045-acre area. The MDP included hydrology and hydraulic analysis, preliminary design and sizing of drainage facilities, cost estimates and a project report for the 3-5 and 3-8 watersheds within the City of Colton. The Project 3-5 required the installation of 11,500 feet of 108- and 120-inch reinforced concrete pipe from Valley Blvd south to the Santa Ana River, including the installation of approximately 1,700 feet of 108-inch RCP by boring and jacking methods at multiple locations.
Section 29 Stormwater Basin, City of Palm Desert, CA – Project engineer during design for the failed rock slope protection downstream of the existing spillway and collapsed slope that undermined a significant portion of the spillway crest. Work also included hydrology analysis of approximately 519 acres of drainage watershed, development of a unit hydrograph tributary to Mid-Valley Channel, flood routing through the existing drainage channels and Section 29 Retention Basin, hydraulic analysis for design and reconstruction of the rock slope protection, spillway, forensic analysis to investigate the cause of the failure, produce contract documents guiding the repair of the Section 29 Basin and an 18-inch basin inlet. Relocation of an existing 12-inch sewer line under the basin spillway.
MDP Lines 6A and 8, Laterals 20C and 20A, City of Palm Springs, CA – Project engineer during the design of the three major flood control projects commissioned by the City.
Line 6A and Line 8 along Sunrise Way resulted in the elimination of “down and under drains” and support commercial development between Via Escuela and Vista Chino Drive and Andreas Road and the Baristo Channel, respectively. Similarly, Laterals 20C and 20CA resulted in the elimination of “down and under drains” and support residential development along El Cielo and Baristo Road. Services included review and modification of master plan hydrology, design surveys, utility coordination, geotechnical engineering, alignment selection and analysis, hydraulic modeling and the development of plans, specifications and estimates.
San Jacinto Area Master Drainage Plan Line “E-2”, City of San Jacinto, CA – Managing Engineer to prepare construction plans for MDP Lines E-2 and E-2A in the City of San Jacinto and Hemet. The project reach for MDP Line E-2 is over 7100 feet along State Street between Menlo Avenue and MDP Line E and over 250 feet for MDP Line E-2A along Esplanade Avenue. The size of the storm drain facilities are from 36-inch to 72-inch diameter. Work included hydrology analysis to determine the 10-and 100-year storm runoff within the MDP facilities watershed. using CivilDesign software.
San Jacinto Area Master Drainage Plan Line “H”. City of San Jacinto, CA – Managing Engineer to prepare a feasibility study to evaluate alternative alignments for MDP Line H, H-2 and H-3 per the current City of San Jacinto MDP. Work also included preparation of construction plans for the most cost-effective alignment. The project included evaluation of the existing drainage facilities at the intersection of Ramona Expressway and State Street; to mitigate drainage deficiencies as required. It also includes Rational Method Hydrology using CivilDesign software to determine the 10- and 100-year storm runoff.
Sierra Way Storm Drain Project, City of San Bernardino, CA - Project Manager responsible for plan design and supporting analysis during the design of approximately 5,000 lf of 39” – 84” storm drain in the City. The project sought to eliminate surface drainage on the local streets and temporary lines that traversed private property.
Moe Ahmadi, PE | Vice President
14
15.F.
BS, Geographic and Environmental
Engineering, University of Applied and
Environmental Sciences (UDCA), Bogotà,
Colombia
Ms. Hernandez recently joined ERSC as an
Engineer I. She is proficient in identifying
and solving problems related to the use of
territory and its resources, able to cover
the programming and development of
environmental projects and sustainable
development. She is also efficient in the
planning and organization of geographical
space and in the use of modern cartographic
technologies and of Geographic Information
Systems (GIS).
Environmental Analysis
Water Resources
Planning
Areas of Expertise
Education
Similar Project Experience:
CIP Water Pipeline Replacement Project, City of Redlands, Redlands, CA - Assisted in the design of new water mains ranging from 8 inch to 12 inch ductile iron pipe (DIP). The purpose of the project was to eliminate undersized and aging infrastructure. The design included the reconnection of all water service laterals to the new main. The project includes approximately 55,000 linear feet of existing pipeline that need to be replaced.
Inundation Study for Mineral Hot Springs Lake, San Manuel Band of Mission Indians, San Bernardino, CA - Project Engineer during the decommissioning of Mineral Hot Springs Lake (MHSL). The Tribe wished to reclassify the lake to reduce the oversight of the State of California’s Department of Dam Safety. In decommissioning and reclassification, ERSC will work to redesign the weir and outlet structure to allow the lake to operate below 15 acre feet.
Soboba Band of Luiseño Indians, Master Drainage Plan (MDP) Storm Drain Improvements within EDC Commercial Retail Development - Project Engineer during preparation of a drainage study and improvement plans for construction of MDP Lines B1, B2, and B3 for the Horseshoe Development Site consistent with the current MDP Report.
Sewer Capacity Improvement Project C-3, City of Victorville, Victorville, CA – Assisted designer during the project that included upgrading of 6,550 of 18-inch pipe upgraded from 12-inch pipe. The project is generally located in residential areas and crosses a park in an easement. The City of Victorville has identified the potential to construct a new sewer main in the San Bernardino County Flood Control District’s (SBFCD) access road, next to the Oro Grande Wash from Austin Road to Seneca Road. This relocation eliminates a series of existing lines that traverse several properties, which requires the abandonment of any existing easements. This requires coordination with several residences, and the new alignment will require coordination with SBFCD and their approval. It is assumed that this has been discussed with SBFCD but will require appropriate reviews and permitting.
Aliso Creek Road Rehab from Aliso Viejo Parkway to SR-73, City of Aliso Viejo, CA - Project Engineer on the design of the Aliso Creek Road Rehab project, which included the grind and overlay of the roadway, localized full depth replacements, signing and striping, traffic signal loops, traffic control and Caltrans Coordination. The project involved additional detailed design of ADA ramps at the SR-73 interchange and obtaining a Caltrans Encroachment permit.
C Street Angled Parking, City of Ontario, Ontario, CA - Designer for the C Street angled parking. Work included reconfiguration of the existing roadway to allow for thirteen (13) angled stalls to accommodate parking for the existing Wells Fargo. 4th Street Apartments, City of Yucaipa, Yucaipa, CA - Assisted with the design of 18 apartment units on approximately 2.5 acres of land. Scope of work also includes production of the preliminary WQMP and hydrology calculations.
Washington Street at Fred Waring Drive Triple Left Turn Lanes, City of La Quinta, La Quinta, CA – Assisting in design of improvements to this high traffic intersection by adding a third, left turn lane in each direction of the intersection in order to alleviate traffic congestion and improve traffic flow. Ms. Hernandez also assisted on the detailed project description, plans, bid schedules, bid item descriptions, payment methods, engineer’s estimate, special provisions, technical specifications, and any specification detail sheets and relevant standard plans.
Design of Murrieta Creek Bridge, City of Temecula, Temecula, CA – Assisting in the design of a bridge structure over Murrieta Creek connecting Overland Drive at the intersection of Enterprise Circle West on the east side of the Creek to Avenida Alvarado at the intersection of Diaz Road on the west side of the Creek. Ms. Hernandez is also assisting on the PS&E and utility research and coordination.
Stephania Hernandez, EIT | Engineer IV
15
15.F.
Similar Project Experience:
Riverside County Surveyor - Under direction of the County Surveyor, checked tract maps for conformance with the Subdivision Map Act, County ordinances, and development standards. Reviewed records of surveys and corner records for conformance with the Land Surveyor’s Act. Managed on-call field surveying services for aerial mapping, control, topographic and construction surveys.
City Surveyor Services - Currently the acting City Surveyor for the Cities of Rialto, Lake Elsinore and Colton. Supervises the review of subdivision maps, parcel mergers, lot line adjustments, dedications and easements.
On-Call Engineering Plan Check Services, City of Palm Springs – Principal Surveyor responsible for oversight of review of survey documents during an on-call professional services agreement with the City of Palm Springs. ERSC provides plan and map checking for the City’s development projects. Specific tasks include the review of improvement plans, final subdivision maps, and other survey related documents as prepared by design consultants for accuracy and completeness, conformance to local codes, ordinances, and design standards.
General Plan Check Services, City of Chino – Principal Surveyor responsible for oversight of review of survey documents during general plan check services. In the City of Chino, ERSC is commissioned to provide the review of Rough and Precise Grading Plans, Wet Utility, Plans (e.g. Sewer, Water, Storm Drain), Street Improvement Plans, Street Light Plans and Voltage Drop Calculations, Hydrology Studies and Hydraulic Calculations, Water Quality Management Plans (WQMPs), Survey documents and maps, and Soils Reports, for private development and capital improvement projects throughout the City.
On-Call Plan Check, Inspection and Design Services, City of Beaumont – Principal Surveyor responsible for oversight of review of survey documents during civil engineering plan check, design, and inspection services. ERSC reviews development projects, CIP projects, and WQMPs. Development plans range from 1-million sqft commercial complexes to multiple lot subdivisions. As an on-call design consultant, ERSC is responsible for paving projects, survey projects, and drainage projects. Most recently, ERSC completed the Highland Springs/1st Drainage project to mitigate erosion and sedimentation issue near a local golf course.
On-Call Plan Check and Inspection Services, City of Banning – Principal Surveyor responsible for oversight of review of survey documents during plan check and inspection services of residential and development projects. Plan check services include review of maps, street, sewer, water, grading and storm drain projects, as well as review of construction drawings to assure compliance with City, State and Federal regulations.
ERSC also provides conditions of approvals for City projects, as needed.
On-Call Civil Engineering and Plan Check Services, City of Colton – Principal Surveyor responsible for oversight of review of survey documents during Engineering and Plan Check services. ERSC works closely with City staff in the review of grading, street improvements, hydrology studies, soils reports, WQMP, SWPPP, lot line adjustments, and parcel maps. ERSC also provides on-call engineering services, such as the design for the La Cadena and 8th Street Intersection Reconfiguration.
On-Call Plan Check and Construction Inspection Services, City of Highland – Principal Surveyor responsible for oversight of review of survey documents during an on-call professional services agreement. ERSC provides contract plan check and inspection services for the construction of public works and privately funded improvements, including site improvements, street improvements, paving, sidewalk, curb, gutter, grading, and earthwork. Work also included site review for compliance with City standards and traffic control requirements. ERSC also provides plan checking services for all parcel and tract maps, as well as hydrology review.
City of Hemet Public Works Department, Hemet, CA - Designed and implemented the City of Hemet’s PMS/GIS link project. The project involved linking the city’s pavement management tabular database with a street centerline shapefile developed by the Thomas Bros. Map Company. The data was used with ArcView to produce a graphical street network depicting the pavement condition of each city street. The PMS/GIS link provided a better method for city staff to evaluate the condition of the streets and analyze the best cost benefits of street maintenance and rehabilitation programs.
Robert Ollerton, PLS | Principal Surveyor
Robert has over 35 years of professional
experience in land surveying for municipal
agencies. He has managed a wide variety of
land survey projects including surveys for
topographic mapping, geodetic control, right
of-way, boundary, and construction projects.
Most recently, Robert’s responsibilities as the
Principal Surveyor include the management and
coordination of construction staking contracts
for civil engineering projects, boundary surveys,
title analysis, topographic mapping, detailed
design surveys, ALTA Surveys and mapping.
Since joining ERSC, Robert’s wide range of skills
and background have enabled ERSC to provide
clients with localized and personalized service,
keeping true to ERSC’s philosophy of dedication
to customer service and satisfaction.
CA, Land Surveyor No. 7731
Civil Engineering & Land Surveying
Coursework, University of California at
Riverside, Riverside, CA
Civil3D
MicroStation
ArcMap
Boundary Surveying
Right-Of-Way & Easements
Construction Surveying
Topographic Mapping
Consulting Surveyor to Municipal Agencies
Education
Areas of Expertise
16
15.F.
Similar Project Experience:
As-Needed Professional Land Surveyor Services, Eastern Municipal Water District - Project Engineer responsible for concept development, design recommendations, and special study drafting throughout the assignment. ERSC was contracted to provide professional land surveyor services on an as-needed basis for support of the District’s Capital Improvement Program (CIP), Annexation Program, and New Development Projects.
East Drop Structure Repair Mitigation Within Whitewater River Channel, City Of Indian Wells, Indian Wells, CA – Survey Party Chief responsible for oversight of field data collection and processing including data reduction and base mapping supervision during redesign of the East Drop Structure along the Whitewater River. Site analyses and development of potential replacement structures such as a concrete drop structure that incorporates a baffle chute at the outlet of the low flow channel, a USBR stilling basin or a drop structure similar to the one constructed in 1995 using materials sized to withstand the anticipated flows. Regulatory permitting and clearance for an RWQCB CWA Section 401 Water Quality Certification, CDFW 1602 Streambed Alteration Agreement, USACE Nationwide Section 404 Dredge and Fill Permit, and CEQA IS/MND coordination.
Winchester Property Land Survey Mapping Services, Soboba Band of Luiseno Indians, San Jacinto, CA - Project Surveyor responsible for field data collection, base map preparation, plat maps, and drafting of legal descriptions. ERSC was contracted to provide professional surveying and mapping services related to the Tribe’s property at the Northeast and Southeast corners of the intersection of Winchester Road and Domenigoni Parkway. 11th Street Pavement Rehabilitation Project, City of Chino - Project Surveyor responsible for field data collection, base map preparation, plat maps, and drafting of legal descriptions during design of a street pavement reconstruction, alley, and intersection accessibility project. Special considerations were paid to concurrent storm drain projects as well as potential impacts from asphalt conditions, existing utilities, and ADA requirements in affected alleyways.
Murrieta Inverted Sewer Siphon, Western Municipal Water District, Murrieta, CA- Project Surveyor responsible for field data collection, base map preparation, plat maps, and drafting of legal descriptions during the design of an upgrade an existing 8-inch sewer siphon. The project will upgrade the siphon from a single barrel to a larger diameter or a “double barrel” configuration where the line crosses below a Flood Control District owned channel. ERSC will develop a profile of the 8-inch inverted siphon using CCTV and prepare plan and profile drawings of this line.
Strawberry Creek Diversion Pipeline, Idyllwild, CA - Project Surveyor responsible for field data collection, base map preparation, plat maps, and drafting of legal descriptions. The existing pipeline begins at the diversion structure near the intersection of Strawberry Creek and Tahquitz Road. The pipeline paralleled the creek above ground for approximately 400 feet across private property and then below ground to the District’s well site on Fern Valley Road. To further complicate matters, the exiting pipeline crossed under an existing private residence. ERSC performed a topographic survey of the diversion structure and the pipeline alignment to the well site, legal documents for the portion of pipeline crossing private property, and design of new pipeline to avoid existing structures and above ground pipes.
Stagecoach and Substation Topographic Survey, On-Call Engineering & Design Services, City of Banning - Project Surveyor responsible for field data collection, base map preparation, plat maps, and drafting of legal descriptions as part of an on-call engineering agreement. ERSC was contracted for land surveying services related to the development of the Ivy Substation Project at 1581 Charles Street and the Stagecoach Substation Project located on Hargrave Street. ERSC performed boundary and topographic surveys of both sites to establish the boundary and locate the property corner monuments.
CV-Link Multipurpose Path, Coachella Valley Association of Governments, Coachella Valley, CA - Environmental planner responsible for GIS data creation and database management during the planning phases of the CV-Link Path. CV-Link is a 51 mile multiple use path stretching from Palm Springs to the Salton Sea. During the planning phase of the project, GIS mapping was conducted to analyze potential routes, land acquisition, land owners, access points, connectors, and challenges for the project. GIS data including imagery, contours, parcel data, land use data, easement information, and path alignments were maintained and modified throughout the planning phases.
Craig Brudin, QSP | Sr. Engineering Associate
Education
BS, Environmental Policy & Management
BA, Business Managerial Studies
Affiliations
CASQA
Areas of Expertise
Erosion and Sediment Control
Water Quality
Improvement Plan Check
Mr. Brudin has been with the ERSC team
since 2014. Since joining, he has become
a valuable member of ERSC’s project team
in both survey related tasks and plan and
map review services. While providing these
services he has gained extensive working
knowledge of the subdivision map act, local
grading manuals, ordinances and design
guidelines, the California Building Code,
local wet utility design guidelines and the
preparation and evaluation of erosion
control plans.
In various Cities, he is responsible for the
review of maps, legal documents, mass and
rough grading plans, residential precise
grading plans, grading plans for residential
development, commercial development
projects, sewer improvement plans, and
erosion control plans.
CA, QSP No. 26269
CESSWI No. 4852
17
15.F.
STC Traffic, Inc. | Traffic Engineering
STC Traffic | Key Staff Resumes
Relevant Experience
City of Menifee | On-Call Traffic Engineering Services | 2016-Present Project Manager. Tasks completed to date include signing and striping, traffic signal modifications, median improvements, speed feedback signs, traffic control, construction support, and plan review. As design lead, Christian oversees review of City traffic engineering design plans including traffic signal designs and modification plans, medians, pedestrian ramps, road widenings, signing & striping, and signal communications and operations. He has been responsible for producing bid ready design packages for two traffic signal modifications and intersection improvements for Murrieta and Scott Road.
City of Temecula | On-Call Traffic Engineering Services | 2016-Present Project Manager. Responsible for task orders issued by the City, along with various other standalone traffic engineering design projects. Christian leads design engineering task orders for utility coordination, preliminary and final engineering, specifications and estimates, bid assistance, as-builts, and QA/ QC. Projects he has led include the HSIP Fiber Optic Communications System Upgrade Project and Jedediah Smith Road and De Portola Roundabout preliminary design.
City of Lake Elsinore | On-Call Traffic Engineering Services | 2019-Present
Project Manager. Responsible for task orders issued by the City, along with various other standalone traffic engineering design projects. Led design of traffic signal upgrades at eight existing signals throughout the City. Design work included plans for traffic signal modifications such as new dilemma zone detection systems, signage and striping, and flashing beacons. Christian was responsible for day-to-day oversight of field review, environmental clearance, and PS&E at the 65%, 95%, and 100% levels.
City of Jurupa Valley | HSIP Citywide Traffic Signal Coordination and Safety Upgrades | 2023-Present
Project Manager. Led HSIP grant development for citywide traffic signal system safety improvements through improved traffic signal interconnect and signal timing, coordination, and operation and upgraded traffic signal heads with retroreflective back plates. Currently leading delivery of PS&E.
Additional On-Call Experience
City of Jurupa Valley, On-Call Traffic Engineering Services City of Perris, On-Call Traffic Engineering Services
City of Long Beach, On-Call Traffic Engineering Services City of Encinitas, On-Call Engineering and Project Management Services Christian has over 15
years of experience in the
management of traffic
engineering projects
throughout Southern
California, specializing in
traffic operation analysis
and design of traffic signals,
signing and striping,
traffic control, street
lighting, and traffic signal
interconnect. He pulls from
his years of experience in the
transportation industry to
develop PS&E that focuses
on constructability. has
supported engineering
efforts for nearly all of STC’s
on-call clients in Western
Riverside County.
Years of Experience:
15 Education
B.S. Civil Engineering,
Michigan State University,
East Lansing, 2009
Professional
Registrations
Professional Engineer
(Civil) CA, #86675
Professional Engineer
(Traffic) CA, #2927
Professional Traffic
Operations Engineer, USA,
#5180
SENIOR PROJECT MANAGER
Christian Lambarth PE, TE, PTOE
18
15.F.
Community Works Design Group | Landscape Architecture
RESUMES
Mr. Scott Rice is President and Managing Principal of Community Works Design Group (CWDG). He has managed over $150 million of park projects during his tenure at CWDG. Scott oversees the development of construction documents, plan checking, cost estimating, conceptual rendering, and construction observation and management.
Scott graduated with honors from Cal Poly Pomona, earning a Bachelor of Science Degree in Landscape Architecture. He is a full member of the American Society of Landscape Architects (ASLA). Additionally, Scott is a LEED Accredited Professional (LEED AP), as designated by the United States Green Building Council (USGBC), and a Certified Access Specialist (CASp) as issued by the State of California, Division of the State Architect. Scott is one of only three Landscape Architects in California that currently hold CASp Certification.
Scott also serves as the City Landscape Architect for the City of Highland, California, and has acted in that capacity since 2005. Scott also has served as a Contract Park Planner for Jurupa Community Services District (JCSD) since 2003 and Consultant Park Planner/ Plan Checker for Jurupa Area Recreation and Park District (JARPD) since 2015.
Mr. Rice draws on previous work experience in graphic design and golf course maintenance to integrate high aesthetic quality in balance with functional, cost-effective design. His focus is in Public Works projects for various municipalities throughout the State, including Park Planning of various scales, including Community, Neighborhood, Sports, and Pocket Parks, as well as median and parkway landscape, and LMD/ CFD planning. Specialized areas of involvement include Skate Parks, Dog Parks, and Accessible Play. In addition to Park Planning, Scott is seasoned in the landscape architectural development of Multi-family Housing, Planned Residential Communities, Highway Aesthetic Design, Custom Residential Planning, and various private/commercial ventures.
In addition to Scott’s 20+ year tenure with CWDG, Scott took a year-long hiatus in 2010 to co-manage the design division of an internationallyrecognized design/build firm, specializing in skate parks and action sports facilities throughout the world. When not in the office, Scott enjoys the fruits of his labor – parks and trails – with his wife and five children.
EDUCATION:
Bachelor of Science in
Landscape Architecture
California State Polytechnic University,
Pomona (2002)
Years of Experience: 25
Years with Firm: 20+
LICENSES + CERTIFICATES:
Licensed Landscape Architect
California #5111 (2005-current)
New York #2645 (2016-current)
Certified Access Specialist
California CASp-709 (2016-current)
AFFILIATIONS:
American Society of Landscape
Architects (ASLA)
Full Member
President Elect,
Southern CA Chapter (2020-present)
U.S. Green Building Council
LEED Accredited Professional
Certified Access Specialist Institute
Full Member
Building Industry Association
Riverside County Chapter Member,
Board of Directors
(2021-present)
Leaders of Tomorrow (LOT) Committee
2017 Chairman
SCOTT RICE ASLA, LEED AP, CASp
PRINCIPAL LANDSCAPE ARCHITECT
RESUMES
19
15.F.
Aragon Geotechnical, Inc. | Geotechnical Engineering
C. FERNANDO ARAGÓN, M.S., P.E., G.E.
CIVIL ENGINEER, GEOTECHNICAL ENGINEER
16801 Van Buren Blvd., Bldg. B
Riverside, CA 92504
Tel: 951.776.0345 ● Fax: 951.776.0395
www.aragongeo.com
EDUCATION
• Loyola Marymount University of Los Angeles, B.S., Civil Engineering • University of California, Berkeley, M.S., Civil Engineering with emphasis in Geo Engineering
PROFESSIONAL REGISTRATIONS
• Registered Civil Engineer, California, No. 72277 [Exp. 6/30/20] • Registered Geotechnical Engineer, California, No. 2994 [Exp. 6/30/20] • California Department of Transportation, Certificate of Proficiency, Expires: 9/2019
• Governor’s Office of Emergency Services – Disaster Services Worker – Volunteer
PROFESSIONAL AFFILIATIONS AND HONORS
• American Society of Civil Engineers
• ASTM International – Participating Member
• Member of Tau Beta Pi National Engineering Honor Society • Member of Chi Epsilon National Civil Engineering Honor Society • Association of Drilled Shaft Contractors (ADSC), The International Association of Foundation Drilling, 2004-2005 graduate student scholarship recipient • University of California at Berkeley, 2004-2005 graduate fellowship
PROFESSIONAL HISTORY
1997-Present: Aragón Geotechnical Inc., Riverside, California; Soils Technician (Laboratory and Field) to Engineering Assistant, Staff Engineer, Project Engineer to President.
5/2002-8/2002: Kiewit Pacific Company, Santa Fe Springs, California; Engineering Field Intern.
1996-1997: Aragón Geotechnical Consultants, Inc., Riverside and Lake Arrowhead, California; Engineering Assistant; Soils Technician (Laboratory and Field.)
20
15.F.
Biggs Cardosa Associates, Inc. | Bridge Engineers
Biggs Cardosa Associates, Inc.
Years in business 39
Business Type California Corporation
Offices San Jose, CA (Headquarters), San Francisco, Oakland, Fresno, Orange and Olympia, WA Number of Employees 108
Biggs Cardosa Associates, Inc. is a leading, award-winning California engineering firm that provides structural design, consulting, and construction management services. Biggs Cardosa provides structural engineering design services for all structure types including bridges and other transportation structures; buildings, pump stations & hydraulic structures, as well as supporting infrastructures including soundwalls, retaining walls, and foundations.
Biggs Cardosa has been reshaping California highways and skylines for 39 years through innovative and effective design of bridges, transportation structures, buildings and supporting infrastructure facilities. The firm provides structural engineering design, seismic retrofit, modification and rehabilitation of these structures.
Biggs Cardosa is known for the quality of its work, active principal involvement, responsiveness to clients’ needs, and innovative solutions to complex project issues.
Listening to their clients and consultants allows Biggs Cardosa to collaborate to achieve project success through active principal and senior staff involvement. Biggs Cardosa is known for responsiveness to the needs of clients and the development of innovative solutions to complex project challenges. They have established a reputation for reliability and prompt response with easily constructible designs. Biggs Cardosa’s staff of over 100 includes 48 licensed Civil Engineers and 14 licensed Structural Engineers. We have the depth of staff resources to deliver any project in an effective and timely manner.
Biggs Cardosa provides a wide range of structural engineering services including feasibility studies, conceptual design, structural design, and structural engineering consulting. Biggs Cardosa has provided services for over 100 California Public Agencies including 24 counties, 60 cities and over 20 other agencies (towns, redevelopment agencies, water districts, transportation agencies).
Services and Capabilities
• Structural Engineering
• Structural Assessment, Evaluation, Analysis & Seismic Retrofit • Peer Review
• Value Engineering
• Constructability Review
• Construction Management & Inspections
• Cost Estimating
• QA/QC
21
15.F.
Inland Aerial Surveys, Inc. | Aerial Topography
DEREK C. HOOD, PLS
California Professional Land Surveyor #6799
President / Principal of Inland Aerial Surveys, Inc.
Mr. Hood began his Land Surveying career in 1979. He has worked on projects for both the public and private sectors. In 2000, Mr. Hood became Principal and President of Inland Aerial Surveys, Inc. and during this time has been managing the company operations. Inland Aerial Surveys, Inc. provides aerial photogrammetry services. Past experience has included, Survey Party Chief, Survey Dept. Management, Photogrammetic map compilation and Aerial Camera Operator.
INLAND AERIAL SURVEYS, INC. - Corporate Profile
Since our beginning in 1970, Inland Aerial Surveys, Inc. (IAS) has continued to serve an expanding number of clients in both the private and public sector. We offer all photogrammetric services, while specializing in the compilation of aerial topographic digital data.
Since its inception, IAS has been located in Riverside, CA. From this location, IAS has completed projects throughout California. Projects range from design scale 1”=20’ to small scale mapping at 1”=500’.
Services include:
Aerial Photography
Black & White or Color
Vertical and Oblique Photography (with large or small format) Digital Ortho-Photos
Direct Digital Mapping
Analytical Triangulation
Topographic & ALTA Mapping
Digital Terrain Modeling
INLAND AERIAL SURVEYS, INC COMPANY OWNED EQUIPMENT
1 - CESSNA TU206 AIRPLANE EQUIPED WITH A LEICA RC 30 FMC AERIAL CAMERA 6 – SOFTCOPY WORK STATIONS
1- WHERLI PHOTOGRAMMETRIC SCANNER
3- COMPUTER WORK STATIONS WITH AUTOCAD, MICROSTATION & TERRA MODEL. 22
15.F.
SECTION III -
Project Scope
23
15.F.
<Section Title> SECTION III - Project Scope
PURPOSE:
ERSC has reviewed the City of Hemet’s
request for proposal “Professional
Engineering Services for Warren Road
Improvement,” visited the site to review
and document any possible challenges
that may be faced in the design process,
reviewed available reference material, and
obtained drone footage by flying the entire
length of the project to review up to date
conditions. Our team has prior knowledge
of future proposed developments at
various locations along the project limits
gleaned from supplying Entitlement
reviews for the City and producing several
reports and PS&E for CIP projects over the
past 20+ years. Our review demonstrates
the level of commitment ERSC’s team
has to the City of Hemet and highlights
our understanding of the project and our
approach to solving any unique challenges
a project of this nature may have.
ERSC staff visited the site by driving the
limits, walking certain portions, taking
pictures to document items for discussion,
observing vehicular travel characteristics,
noting grade challenges, and identifying
existing improvements to be joined or
removed. We reviewed City-supplied
underlying improvement plans in addition
to those in ERSC possession from prior
projects, maps to identify right-of-way
constraints such as power poles and storm
drain appurtenances, and the effects that
widening of the roadway will have upon
them. Photos were shared with ERSCs’
subconsultants, and discussions were held
to ensure all work proposals understand
the entire project and not just a single
component.
ERSC understands the scope of the project
is to prepare plans, specifications, and
cost estimates for the construction of
improvements to be made to Warren Road
from Esplanade Avenue to Domenigoni
Parkway, which will involve widening of
the current roadway to its ultimate width,
which is classified as Secondary 4U with an
88-foot right-of-way and 64-foot curb to
curb dimension.
The following Street Classification Typical
Section is taken from Figure 4.2 of the City’s
General Plan. The 94’ ultimate right of way
will be reduced to 88’ for this project.
Project Limits
24
15.F.
<Section Title> SECTION III - Project Scope
The project PS&E will be broken into three
phases, these being:
• Phase 1 – Esplanade Avenue to
Stetson Avenue
• Phase 2 – Stetson Avenue to Salt
Creek Bridge
• Phase 3 - Salt Creek Bridge Widening
With the proposed improvements identified, it is understood that there is a necessity for the City to acquire property. Half-street rightof-way of 44 feet will be required on both sides of Warren Road, with the possibility of additional right-of-way being required where traffic signals will be proposed to accommodate turn-lanes.
The road improvements will consist of installation of curb and gutter, AC pavement, sidewalk, landscaping, striping, and traffic signals where warranted. Existing storm drain facilities crossing or adjacent to the project site will be modified to accommodate the street widening. Additionally, improvements will be proposed to the existing Salt Creek Bridge, which will be widened to accommodate the additional two lanes of traffic plus sidewalk.
The process and procedure of preparing the Plans, Specifications, and Estimates for the aforementioned Project will follow in the Scope of Work.
SCOPE OF WORK:
TASK 1 – PROJECT MANAGEMENT
ERSC has assembled a highly skilled team to perform the tasks outlined in the City’s RFP. All subconsultants have performed work of this nature numerous times and have the necessary expertise to complete the tasks identified expeditiously. The ERSC Project Manager has assembled a Team that has worked with the selected subconsultants on a variety of projects and selected them for their knowledge, ease of collaboration, adaptability to varying situations, and moral purpose to complete a job within budget and on time. The key to this project will be regular two-way communications within the Team from Notice to Proceed to final plan submittal.
While the Project Manager will oversee the Team, each team member is equally committed to moving their part of the project forward by keeping tasks on schedule, foreseeing possible hold-ups and coming up with solutions, and being available to answer questions or bring team members together to find the right solution and providing the answer for the overall successful outcome of the Project.
ERSC’s Project Manager will work with the City to schedule a project kickoff meeting that includes each subconsultant’s Project Manager. This will allow our team to understand any special requirements the City may request as a part of this project. ERSC believes that early coordination leads to successful projects, and we intend to be ahead of any issues to ensure a smooth project. At the kickoff meeting, identifying points of contact with each agency/company will be extremely important to avoid delays later on when trying to reach a party for any issue that may arise. ERSC will want to know individuals’ names and contact information within the various departments at the City from which needed information may be obtained.
In addition, ERSC believes continued coordination is essential and has included regular monthly and milestone meetings to discuss project progress or relevant issues related to the project. These meetings may be held in the field, office, or via teleconference, as directed by the City.
Once regular monthly meeting dates are determined, ERSC will prepare the meeting agenda, chair the meeting, take minutes, identify future action items, review and update the project schedule, and circulate meeting minutes for review and concurrence by the Team.
Subconsultant Project Managers or key staff will attend these meetings.
Staffing personnel and hours are based on current availability and projections of future workloads. The Project Schedule will be provided after the kickoff meeting, taking into consideration all coordination issues presented by the City. If Task deadlines affect ERSC staffing workloads, ERSC commits to adjusting staff workloads to keep this project on track. Should personnel changes be necessary to accommodate the schedule, ERSC will notify the City and obtain permission before making such changes.
Street Classification Typical Section
QA/QC
ERSC’s size makes the firm flexible and adaptable to our clients’ preferred project, budget, and schedule management methods. Summarized below is ERSC’s typical approach to managing the many facets of a successful project, which will be in effect for the project’s duration.
Involvement
Part of any successful project at ERSC is a Project Manager tasked with constant involvement, project familiarity, open communication with clients and team members, and participation in major design decisions. All project disciplines are kept informed of any changes in design, schedule, or other tasks to ensure conflicts do not arise by regularly occurring meetings and thorough correspondence measures. These basic principles ensure delivery of a complete project that is mindful of overall goals, impacts to the community, and constructability of the final design. 25
15.F.
<Section Title> SECTION III - Project Scope
Budget
The budget for any project is a function of the work plan and tasks within that plan. ERSC approaches a budget the same way we approach a work plan and Fee Schedule. Projects are loaded into our accounting and time tracking program, Deltek Ajera, and broken down by task. Each task is preloaded identically to the work plan and Fee Schedule with the time allotted per billing rate and the total project budget. Employees working within the project can account for their hours billed to a project and remaining hours available for a task. Accountability and ease of access to this information help mitigate overruns. ERSC finds that an extra set of eyes watching each facet of a project helps eliminate potential budget problems.
Schedule
Schedule maintenance can be as simple as ensuring adequate resources are dedicated to the project. At ERSC, project teams are developed on a project-by-project basis from a pool of engineers and technicians. Regular staff meetings are held to discuss project needs and deadlines for a given period. Staff is maintained or enhanced for projects on an as-needed basis to ensure that project schedules are upheld. Staff assigned to a particular project will always have the necessary experience. Our goal is to maintain continuity within a given project team at all times. ERSC schedules are tied directly to our budget which lends all employees the incentive to remain at or ahead of any project schedule. QA/QC reviews occur throughout the project duration but officially at major milestone submittals.
Quality Control/Quality Assurance
An additional and important facet is the quality of the work submitted. Quality design and calculations, which are checked, corrected, and back-checked, will result in accurate bidding, minimized change orders, and ensured on-schedule completion. QA/QC staff will sign and date all draft and final documents submitted to the City for review. The adjacent flow chart summarizes the ERSC QA/QC process.
This task will include the management of the project, including but not limited to invoicing, filing, schedule updates, and various administrative tasks.
Deliverables:
• Meeting Agenda and Minutes
• Monthly Invoices with Progress Reports
• Schedule Updates
TASK 2 – DATA COLLECTION
Task 2.1 - As-Built Research, Investigation & Field Review ERSC will research all record data available within and around the project boundary, including as-built documents, survey data, utility contact information, and any other available record data. Our team will coordinate with the City to obtain any record drawings for the project area not already shared as part of the RFP Q & A process, including but not limited to Street Improvements, Drainage Improvements, Signing and Striping, and any construction drawings associated with Master Planned Developments adjacent to the project site. Our team will utilize this data in the design of the project and incorporate it into the project drawings for record purposes.
Team members will conduct a detailed field review once the information is incorporated into the plans to verify existing utilities and infrastructure. Field notes and photos will be taken to document any discrepancies on the plans with field conditions.
Deliverables:
• Correspondence regarding any potential conflicts between as-builts and existing conditions.
Task 2.2 - Utility Coordination, Research & Notification ERSC has obtained several underlying utility maps for the Project limits but will still perform full utility research by obtaining all utility information within the project limits. All utility notices will include a vicinity map and be prepared on City letterhead and delivered to staff for the City Engineer’s signature and mailing.
Correspondence will be documented and filed in the project files. Record maps will be used to show horizontal and vertical locations of all utilities on the plans for below-grade utilities. Survey topography shots will identify the above-ground utility. Existing Warren Road Bridge plans identify GTE conduits and casing for SoCalGas main in the cells of the bridge in addition to electrical conduit and cable TV ducts on the bridge surface. These will be confirmed with the appropriate purveyor.
ERSC will provide further field investigations to locate, identify, verify locations, and determine the status of existing utilities. In addition, our team will obtain and review all applicable base map plans, atlas maps, substructure maps, specifications, reports, and record data for all existing utilities, agencies, and companies involved in the project area.
All utility research shall be incorporated into the plan and applicable details as part of a comprehensive construction plan.
The overhead SCE lines will be of particular consideration. Transmission and distribution lines exist for most project limits, paralleling or traversing Warren Road. It is assumed Transmission Line
26
15.F.
<Section Title> SECTION III - Project Scope
that the Transmission lines will remain in their current location as relocating them will most likely be cost-prohibitive and very time-consuming. The distribution line locations will be reviewed versus widened road location, and unless the poles fall within the street limit, it will be recommended they remain in their current location, and sidewalk will be routed around the poles.
Proposed finish grades will attempt to be as close to existing as possible to eliminate the need for pole reinforcement or compromising clearance limits under the utility lines.
Poles that fall within street pavement limits will be documented and reviewed with the City for alternatives (i.e., remain, relocate, place underground, etc.).
Also requiring special consideration is the High-Pressure Gas line located in Domenigoni Pkwy at the northeast corner of Warren Rd.
Deliverables:
• Copies of all correspondence/notices with affected utility agencies • Copies of maps and record data provided by the affected utility agencies. • Copies of correspondence regarding utility relocations (if any).
High Pressure Gas Warning
Task 2.3 - Survey & Mapping
ERSC will provide the aerial targets required for Inland Aerial Surveys, Inc. (IAS), which will fly the project and produce the survey at a 1” = 40’ scale with a 1’ contour interval. IAS will furnish one set of color digital files of the aerial images and a digital data file in AutoCAD .dwg format. ERSC will research available record information pertaining to the project area, including Tract Maps, Records of Survey, Parcel Maps, and Right-of-Way maps to prepare the base maps on which the street design will be based. The project site will be flown to provide an approximate 500-foot-wide strip centered on Warren Road.
ERSC will provide ground survey/topography at 50’ stations, or closer, within the right-of-way for the project limits. All surface features, including centerline, grade breaks, edge of pavement, catch basins, manholes, striping, AC berm, curb and gutter TC/FL elevations, etc., within the survey area will be located and labeled. ERSC’s team will work together prior to performing survey to create criteria to identify items that are not typically included in a survey, such as broken curb/gutter, raised sidewalk due to tree root intrusion, missing sidewalk panels, and overhead utilities. In addition, ERSC will require additional survey shots at intersecting streets, all existing sidewalk ramps to check for conformance with ADA requirements, and anticipated pavement join locations to create necessary profiles and ensure smooth join locations. If any private improvements are located within the public right-of-way, these items will be identified for the City to determine their disposition.
All survey will be downloaded and generate one-foot contours, centerlines, right-of-way, and fronting property lines from record information.
Deliverables:
• Topography in .dwg format. (1” =40’)
• Digital Terrain Model (DTM) surface
Task 2.4 - Geotechnical Analysis and Report
ERSC is partnering with Aragon Geotechnical, Inc. (AGI) to provide geotechnical engineering services for this project. Aragon has worked on numerous successful projects with ERSC and has a recent history of geotechnical work near the City of Hemet.
AGI’s investigation for Phases 1 and 2 north of Salt Creek will focus on (1) Characterizing native-soil support conditions for new pavement structural sections and bordering concrete curbs and sidewalks; (2) Evaluations of bearing-zone soils for RCP drainage pipes, catch basins, and culverts; (3) Evaluations of ground conditions for CIDH shafts at signalized intersections; (4) Identifying any significant soil chemistry influences on construction materials; (5) Creating sample earthwork specifications for mass grading; (6) Design of preliminary pavement structural sections; and (7) Supplying recommended soil parameters needed for “D-load” pipe design methods for RCP storm drains. AGI would prefer to work with an early-stage (30%) concept plan so that investigation sites can be partially tailored to proposed cuts, fills, and structures. A 1:1,200 or larger scale alignment topographic map would be desired. Neither will be absolute necessities, however. Phases 1 and 2 will be included in one preliminary geotechnical investigation report.
The Salt Creek bridge investigation (Phase 3) is proposed as a concurrent field study but will entail a separate geotechnical design report as our deliverable. Codes and standards we must address are different. Adding to the topics enumerated above, shallow and deep foundation options will be assessed for feasibility and design loads. Geological hazard potentials will be analyzed. We can accommodate design standards of either or both Caltrans and AASHTO when calculating static or dynamic resistance of the local soils on embedded structural foundations.
Twenty-four hours of drilling rig time is budgeted for ordinary Phase 1-2 roadway. AGI proposes borings every 1,200-1,500 linear feet of roadway on average, with an estimated count of 24 to 28 explorations total. Soil boring locations will be guided by possible structure sites and mapped zones of extremely weak soils with low R-values that impose requirements for enhanced pavement section depths. Drilling will also examine a 200-foot-long segment of future roadway located ~1,400 feet north of Devonshire Avenue, where granite outcroppings hint at hard-rock conditions. Targeted termination depths will normally range from 7 to 20 feet or 10 feet below structures when applicable. AGI expects to place all Phase 1-2 soil borings beside the existing pavement in road shoulder areas. Coring of existing pavement is excluded. After DigAlert notifications, a truck-mounted hollow-stem auger rig will advance the holes. If precise survey coordinates are required for the as-drilled hole locations, they shall be supplied by ERSC. 27
15.F.
<Section Title> SECTION III - Project Scope
The Phase 3 bridge area will conclude the field portion of AGI studies. The same drilling rig will be used if ground is hard. A specialty track rig will be selected if ground is soft. Access may be a problem. We believe one soil boring per abutment and bridge bent will be adequate at Salt Creek. Targeted termination material will be decomposed granite. Based on reviewed test boring data, predicted exploration depths range from 65 to 80 feet. Bridge drilling could require three days.
A qualified engineer or geologist will supervise drilling and soil sampling. Samples composed of both “undisturbed” ring-lined barrel recoveries and disturbed Standard Penetration Test drive recoveries will be classified. An encroachment permit will be obtained from the City for regular road ROW. AGI understands that RCFCWCD controls the Salt Creek channel. The agency will demand a separate permit. Work in the channel is very likely to require environmental clearance by the District. This is often but not always given “overthe-counter” without a detailed field review. If required, costs for District biological clearances (Flood Control staff time) are not included in AGI’s geotechnical budget and are assumed to be handled through the City’s Environmental Consultant. Drilling excludes any work within the State Hwy 74 (Florida Avenue) ROW, although we can get “close” if necessary. AGI expects to avoid traffic lane closures. AGI technical staff will manage warnings of our work zones while the drilling crew is onsite with suitable signage and cones that meet City requirements.
Laboratory soil testing will comprise determinations of in-place density and water content, shear strength, compaction criteria, particle gradation, expansion index, Atterberg limits, and corrosion potential. Based on regional soils maps we have budgeted 8 R-value determinations for preliminary pavement design.
One seismic refraction line spread performed north of Devonshire Avenue will supplement our soil borings. AGI’s engineering geologist will compile a detailed field geologic map for later analyses of rock discontinuities and excavatability. The geologist will perform risk assessments for geological hazards at the Salt Creek crossing, including but not limited to strong motion, liquefaction, and permanent ground deformation phenomena such as lateral spread at channel sidewalls.
AGI will prepare two preliminary written reports (Phase 1-2 and bridge Phase 3) documenting the preliminary soils investigation findings, recommended grading specifications, and bridge design criteria. Subsections will be included discussing local geologic conditions, seismic design coefficients, and/or spectral response. Recommendations for temporary excavation backcut slopes, concrete mixes, and dewatering requirements will be covered. Caltrans-type HMA design methods would be utilized for ordinary asphalt-base-subgrade sections. Close coordination with the bridge structural designer is expected to ensure our foundation design responses will be adequate for the prospective foundation system.
Deliverables:
• Geotechnical Exploration Reports (Phase 1-2 and Bridge Phase 3), including appendices with graphical boring logs, summaries of laboratory tests, and map of core locations – Electronic .pdf and 4 Bound Copies TASK 3 – ENVIRONMENTAL REPORTING AND COORDINATION
Technical Studies/Coordination
The RFP and Q&A indicated that the City has an environmental consultant. The ERSC Team will prepare the necessary technical reports as identified below and coordinate with the environmental consultant so a complete CEQA document is prepared in order to obtain clearances for construction. Based on current project understanding, the technical approach for each report will be defined in the discipline of where the study is prepared in the following scope of services. The reports identified will comply with standard City environmental procedures.
• Project Description
• Geotechnical Analysis
• Hydrology & Hydraulics Analysis
• VMT Traffic Analysis (Screening Evaluation and/or Full Traffic Analysis) • SWPPP
If the City determines additional studies beyond what is referenced below are required for the environmental approval, a modified scope of work and cost proposal will be submitted.
TASK 4 – RIGHT-OF-WAY ENGINEERING
Task 4.1 – Right-of-Way Requirement Map
With the widening of Warren Road to ultimate roadway classification of Secondary 4U, there will be the need to acquire additional right-of-way adjacent to Warren Road where right-of-way is less than the required 44-foot half-street right-of-way. Based upon our review of Assessor Parcel Maps, Warren Road has minimally 44-foot half-street right-of-way from Esplanade Avenue to south of Florida Avenue. Southerly of Florida Ave, the half-street right-of-way varies on both sides of the street. ERSC has identified twenty-two (22) parcels that will require acquisition of some measure of right-of-way for the street widening along Warren Road and five other parcels that may require a portion of their property for necessary clearances at the intersections where traffic signals are proposed to be installed. Also of note, the current right-of-way for Warren Road crossing Salt Creek Channel is 100 feet. Depending upon the bridge widening structure selected, there may be a need to obtain more right-of-way from RCFC. ERSC will meet with the City and confirm road layout and the effects on these properties. Upon gaining approval from the City, ERSC will prepare the necessary Right-of-Way Requirement map identifying the road alignment or traffic signal appurtenance’s location and the area required for acquisition or easement. These maps will be signed and sealed by a California-licensed land surveyor. 28
15.F.
<Section Title> SECTION III - Project Scope
Right-of-Way Parcel Acquisition
Task 4.2 – Legal Description
and Plat
ERSC will also prepare the individual
plat maps and legal descriptions for the
proposed parcel acquisitions needed to
construct the project and per the approved
right-of-way requirements. These maps
and legal descriptions will be prepared
by or under the direction and signed by a
California-licensed land surveyor.
Task 4.3 – Title Reports
Q&A for this RFP indicated to include
providing title reports for the properties
needing right-of-way. ERSC will contact a
Title Company and acquire Preliminary
Title Reports for the agreed-upon
properties.
Task 4.4 – Temporary
Construction Easements
(Optional)
It is assumed that each property adjacent
to the side of the Warren Road where
construction is to occur will require a
Temporary Construction Easement (TCE)
prior to the beginning of construction.
Utilizing the Title Reports obtained
for the acquisition task and obtaining
an additional eight Title Reports as
necessary, ERSC will prepare a legal and
plat identifying the area required outside
of ultimate street right-of-way that is
required for the contractor to perform his
work. TCEs may be recorded with the TCE
expiring upon the Notice of Completion for
the Project. There is the possibility the City
may pursue a “Right to Enter” for those
properties, thus removing the need for a
TCE and saving the City significant costs.
If requested, ERSC will prepare a form
letter identifying the property address/
APN and the extent of the area to which
the Contractor will be granted access. The
letters could contain a blanket request,
i.e., “‘the front 10’ of property adjacent
to City right-of-way,” but not have a legal
and plat prepared. These letters would be
signed by the City and property owner and
would not be recorded.
It is understood that neither acquisition
nor appraisal services are part of this
Project’s scope of services.
Deliverables: • Right-of-Way Requirement Map • Copies of all Title Reports – 27 for acquisition, additional 11 for TCEs
• Legal and Plat for Portion of Parcel
requiring Acquisition – 27 parcels
• Legal and Plat for TCE (Optional) - 38
parcels
29
15.F.
<Section Title> SECTION III - Project Scope
San Diego Canal (looking north)
Drainage Structure Under Salt Creek Channel Bridge -
Looking North
Salt Creek Channel Bridge - Looking West
TASK 5 – PERMITTING
Riverside County Flood Control
and Water Conservation
District
It is understood that permitting through
Riverside County Flood Control and Water
Conservation District (District) will be
required. With the widening of Warren
Road Bridge over Salt Creek, modifications
will be proposed to Salt Creek Channel
with the addition of new piers, bridge
footings and abutments. In addition, the
existing storm drain connections into the
channel near Warren Road will require
modifications. ERSC has worked numerous
times with the District, understands their
Encroachment Permitting process, and
is currently performing similar design
services for the Overland Drive Bridge over
Murrieta Creek in the City of Temecula.
Early coordination with District staff on
the project scope and preparing items per
their Encroachment Permit requirements
will result in the most expeditious process.
It is anticipated that the District will
also require an Encroachment Permit to
perform Geotechnical Exploration within
Salt Creek Channel. ERSC’s Team will
process applications, but it is assumed
permit fees will be paid or directly
reimbursed by the City.
Metropolitan Water District
The San Diego Canal (California Aqueduct),
which parallels Warren Road south of
Warren Road’s intersection with Esplanade
Avenue to Devonshire Avenue, is owned
by Metropolitan Water District (MWD).
ERSC will need to obtain an Entry Permit
for survey work within MWD right-of-way/
easement. ERSC will also need to prepare
the necessary exhibits to be included in
the application for the requisite permit.
In addition, if any improvements are
proposed to be constructed within MWD
right-of-way, submittal must be made to
MWD for their Project Review Committee
(PRC) to review and determine if there are
impacts to MWD facilities.
TASK 6 – CONSTRUCTION
DOCUMENTS
Task 6.1 - Street Improvement
Plans:
Using data collected in the previous tasks,
ERSC’s team will create base sheets for all
disciplines of improvement plans. All toscale plans are anticipated to be prepared at a 1” = 40’ scale unless larger scale is
necessary to provide clarity. Warren Road
30
15.F.
<Section Title> SECTION III - Project Scope
Street Improvement Plans will be prepared with plan and profile for its entire length. It is anticipated that existing centerline profile will be shown on all plan and profile sheets. Portions of Warren Rd that require widening on both sides will have the profile of existing edge of pavement plotted for each side. Where widening is only required on one side, that side’s existing edge of pavement profile will be shown. Existing TC will be shown for the other side of the street to be used as information/reference. Where widening is to occur, proposed top of curb profiles will be generated, in addition to FG at Right-of-Way. This will assist in determining the need for retaining walls or “grade to drain” joins at right-of-way with existing grades.
Typical sections will be generated for various segments of roadway along Warren Road. They will identify the portion of the roadway pavement to remain, sawcut and join location, and new pavement section limits with type and thickness, all following the Geotechnical Report recommendations. Sheets containing cross-sections at 50-foot intervals shall be generated for use in design and City review but will only be incorporated into the project plans if requested.
All curb returns where ADA ramps are to be constructed or modified due to new Traffic Signal installation will be shown and detailed at a 1” = 10’ scale. Clearance and ramp dimensions, slopes, and spot elevations to confirm slopes will be provided. Details will follow City Standard No. C-215, C-216, C216A and C216B. If conditions do not allow for these ramp standards, Greenbook standards will be followed, with City concurrence.
Hemet-Ryan Airport (HMT) is a General Aviation public airport owned and operated by the County of Riverside. It has fixed-base operators that provide ground support services, on-field fuel services, maintenance and aircraft storage, ground transportation, maintenance services, and hangars for most general aviation aircraft, ranging from single-engine to corporate jets. The airport has two runways, one for aviation and a secondary runway for sailplanes only.
Airport Layout Plan for Hemet-Ryan Airport
Warren Road - General Plan Amendment
31
15.F.
<Section Title> SECTION III - Project Scope
Per the Airport Layout Plan (ALP), Runway 5’s existing Runway Protection Zone (RPZ) extends 1,000 feet from the end of the runway with a 20:1 Approach Slope. This places the northwesterly end of the RPZ over Warren Road. ERSC will confirm that no improvement is constructed that projects into this approach slope, which at the point over Warren Road will be 50 feet in height from the elevation of the end of the runway. The ALP identifies the future lengthening of Runway 5 and the future location of its RPZ. This will not be addressed in the current scope of work. Should the City/County desire to have this analyzed, an additional scope and fee will be prepared.
14 CFR Part 77 requires proponents of construction or alteration on or near an airport to give the FAA timely notification, which will serve as the FAA’s basis for evaluating the effects of the proposed construction or alteration on safety, air navigation, and airport traffic capacity at public-use airports. ERSC will contact the FAA and prepare the necessary documentation for submittal to the FAA for their review with the intent of obtaining a “Determination of No Hazard to Air Navigation.” Deliverables:
• One Title Sheet, Detail Sheets, and Street Improvement Design Plan and Profile Sheets (assuming 22 sheets), Cross-Sections (30%, 60%, 90%, 100%)
• FAA Notification
ERSC is partnering with STC Traffic, Inc. (STC) to prepare the required traffic-related documents.
Task 6.2 - Traffic Signal Warrant Analysis Study (Draft and Final) STC will prepare Traffic Signal Warrant Analysis for the following non-signalized intersections: Warren Road & Simpson Road, Warren Road & Stetson Avenue, Warren Road & Devonshire Avenue, and Warren Road & Esplanade Avenue.
This analysis will document the existing vehicle traffic and pedestrian and bicycle volumes. The 24-hour approach counts and peakhour turning movement counts will be collected at these four intersections and used in the warrant study. CA MUTCD Section 4C will be used for traffic signal warrant evaluation. STC will prepare a technical memo to provide a recommendation to the City as to whether additional new traffic signals satisfy Caltrans Traffic Signal Warrants.
Deliverables:
• Technical Memorandum summarizing Traffic Signal Warrant Results at Four (4) New Intersections • Vehicle, Pedestrian & Bicycle Traffic Data Collection for 24-Hour Approach and Turning Movement Counts Task 6.3 - Traffic Signal Design Plans
STC will prepare the traffic signal modification design plans at a scale of 1” = 20’ for the following four (4) existing traffic signal intersections: Warren Road & Domenigoni Parkway, Warren Road & Mustang Way, Warren Road & Auto Boulevard, and Warren Road & Florida Avenue. It is anticipated that four (4) additional non-signalized intersections may satisfy Caltrans signal warrants. STC will prepare new traffic signal design plans at the following intersections: Warren Road & Simpson Road, Warren Road & Stetson Avenue, Warren Road & Devonshire Avenue, and Warren Road & Esplanade Avenue.
Traffic signal design plans will be at a scale of 1” = 20’ on City of Hemet standard title block sheets and follow City of Hemet standard plans and specifications, Greenbook, and Caltrans standards and specifications. The plan will show existing right-of-way lines, roadway centerlines, curb, gutter and sidewalk, existing signs and traffic controls, and utilities of record. All traffic signal components will be drafted using the latest CAD standards for traffic signal design. Plans will include general notes, construction notes, phase diagrams, pole and equipment schedules, conduit and conductor schedules, legend listing each utility symbol, and details for traffic signal controller cabinet assembly location, type of controller, pole locations and foundations, pull boxes, conduits, loops, and splicing. Other design elements will include EVP Opticom systems, pole and mast-arm signage, APS and countdown signal heads, battery backup systems within the controller cabinet, and LED safety lighting.
STC will work with the City of Hemet to coordinate with utility companies following the first plan submittal to begin utility conflict checks. STC will work with the City and utility companies, as necessary, to facilitate the relocation of any utilities found to conflict with proposed Traffic Signal improvements. STC will work with the City to prepare final utility notices and submit approved plans to the utility companies within the project limits. STC will coordinate with the City and Southern California Edison (SCE) for installation of the new type III-BF electrical service pedestal and addressing and determining service point locations. STC will compile the SCE work order request and work with the City for submittal to SCE. From previous experience, it is important to start this process early to reduce the risk of schedule and budget impacts. STC will work with the City to submit the SCE work order request following the 60% design plans.
Modifications to existing street lighting that is in conflict with/redundant to proposed traffic signal safety lighting will be removed and/ or relocated as needed. These modifications will be reflected on the plans with references for SCE coordination.
Deliverables:
• One Title Sheet, Four Traffic Signal Modification Plan Sheets, Four New Traffic Signal Plan Sheets (30%, 60%, 90%, 100%) Task 6.4 - Signing and Striping Design Plans
STC will prepare signing and striping plans for Warren Road and at each existing and proposed traffic signal intersection along Warran Road within the project limits. STC will utilize survey, civil, and utility base files prepared by ERSC. The signing and striping plans on Warren Road will extend from Esplanade Avenue to Domenigoni Parkway and include existing and proposed traffic signals, including up to 500 feet along the signalized side streets. The signing and striping plans will be prepared at 1” = 40’ scale and use City of Hemet standard title block sheets and follow Hemet standard plans and specifications, Greenbook, and Caltrans standards and specifications.
The plans will incorporate all aspects of the existing and proposed signing and striping design and show curb markings, required removals, required signs to be protected in place, and proposed improvements for the ultimate alignment. 32
15.F.
<Section Title> SECTION III - Project Scope
Deliverables:
• One Title Sheet, One Detail Sheet, and 20 Signing and Striping Design Plan Sheets (30%, 60%, 90%, 100%) Task 6.5 - Street Lighting/Electrical Design Plans
STC will prepare street lighting improvement plans at a scale of 1” = 40’. The base plan will show existing right-of-way lines, roadway centerlines, curb, gutter and sidewalk, utilities of record, and existing and proposed street light infrastructure (pull boxes, conduits, conductors, poles, service locations, etc.) along the Warren Road corridor. Plans will include general notes, construction notes, pole and equipment schedules, conduit and conductor schedules, panel schedules, voltage drop tables, and details for pole locations and foundations, pull boxes, conduits, and service locations. The design will be developed in accordance with the City of Hemet’s Design Standards, Ordinances and Regulations, Caltrans Standard Plans and Specifications, and Illuminating Engineering Society (IES) guidelines.
Deliverables:
• One Title Sheet, One Detail Plan Sheet, and 12 Street Lighting Plan Sheets (30%, 60%, 90% and 100%) Task 6.6 - Traffic Signal Fiber Optic Interconnect Design Plans (Optional Task) STC will prepare a separate fiber optic interconnect plan at 1” = 40’ scale on Warren Road between Esplanade Avenue and Domenigoni Parkway. It is anticipated that there will be a total of eight (8) traffic signals, four (4) existing and four (4) new signals. The design will include the locations of conduit, pull box, fiber splice diagrams, and call out for necessary equipment at each existing and new traffic signal. It is anticipated that there will be a total of 17 plan sheets.
Deliverables:
• One Title Sheet, Two Detail Plan Sheets, Two Splice Diagram Plan Sheets, and 12 Interconnect Design Plan Sheets (30%, 60%, 90% and 100%)
Task 6.7 - Traffic Control Phasing Plans (Optional Task) STC will work with the project team to develop engineered traffic control plans that aim to minimize traffic disruption, provide safe travel through the construction work zone for all modes of travel, and provide safety to construction workers. Concept traffic control plans will be developed first and clearly show traffic control staging that safely navigates vehicles, pedestrians, and bicyclists through each respective work zone stage. The traffic control plans will show schematic locations of work zones to illustrate the anticipated construction zones and the limits of traffic control for each phase of construction. The concept traffic control plans will be submitted to the City for acceptance prior to developing detailed traffic control plans. Construction along Warren Road may result in disruption to traffic, road narrowing, lane/parking restrictions, and potential detours. It is imperative to develop traffic control plans that garner stakeholder agreement to minimize traffic disruptions and impacts on the community.
STC will submit traffic control plans at a concept stage (30%) and 60%, 90%, and 100% levels. Plans will be prepared at a scale of 1” = 40’ in AutoCAD format in accordance with the City’s design guidelines and the California Manual of Uniform Traffic Control Devices (CA MUTCD). Following each submittal review, STC will coordinate with the City on comments received to streamline the process. It is assumed for this scope that Warren Road will be constructed in three phases with a total of 60 traffic control sheets.
Deliverables:
• 60 Traffic Control Sheets at concept level at 30% and 60%, 90% and 100% levels Task 6.8 - VMT Traffic Analysis Screening Evaluation
STC will prepare a Vehicle Miles Traveled (VMT) Traffic Analysis as required by Senate Bill 743 (SB743), implemented throughout California on July 1, 2020. This legislation requires that transportation analysis conducted under the California Environmental Quality Act (CEQA) be conducted using VMT or other similar performance measures rather than vehicle level of service and delay, which was the traditional performance measure. SB 743 applies to both land development and transportation projects that increase roadway capacity.
STC will produce a VMT Screening Evaluation, which will provide justification, consistent with the General Plan Circulation Element and City’s guidelines, that the project screens out from a full VMT Analysis, and a less than significant VMT impact may be presumed. This task assumes that the project design will provide sufficient pedestrian, bicycle, and multi-modal improvements to satisfy the screening criteria in the City’s VMT guidelines and that a complete VMT Analysis is not required.
Deliverables:
• VMT Screening Evaluation
Task 6.9 - Full VMT Traffic Analysis (Optional)
If the project cannot be screened out, a full VMT Traffic Analysis will be provided by STC utilizing the RIVCOM traffic model assessment reflecting General Plan Buildout conditions. STC will appoint a 3rd party vendor to conduct the RIVCOM traffic model runs, and the results and model extracts will be provided.
Findings and recommendations of the VMT Traffic Analysis will be summarized in a draft report, which will be supported by graphics and analysis results tables. STC will address two (2) rounds of comments from the City of Hemet. Should comments received cause the foundational elements of the project to be modified, STC will work with the City to amend our scope of work to address these items.
After addressing comments, STC will prepare and deliver the final report, which will be used to guide the project design and support the required CEQA document for the project.
Should the results determine a significant VMT impact, mitigation recommendations will be provided consistent with the City of Hemet 33
15.F.
<Section Title> SECTION III - Project Scope
Traffic Impact Analysis Guidelines for CEQA & VMT (May 2021), OPR Technical Advisory on Evaluating Transportation Impacts in CEQA (December 2018), and the CAPCOA Handbook for Analyzing Greenhouse Gas Emission Reductions, Assessing Climate Vulnerabilities, and Advancing Health and Equity (October 2024).
Deliverables:
• Full VMT Analysis (Draft and Final)
• Mitigation Recommendations (if applicable)
Task 6.10 - Storm Drain Plans
Warren Road has several storm drainage features that will need consideration. These include the Hemet Storm Channel with multiple pipes crossing under Warren Rd south of Stetson Ave.; the existing double 8’W x 4’H box culvert crossing under Warren Rd from Tract No. 35393, south of Mustang Way; and finally, Salt Creek Channel which the proposed bridge widening will cross. In addition to these major MDP facilities, dirt drainage ditches run parallel to Warren Road along undeveloped properties. ERSC will prepare the necessary Storm Drainage plans following design standards of Riverside County Flood Control and Water Conservation District (District).
Hemet Storm Channel is a District MDP facility that parallels an inactive railroad track and is a trapezoidal dirt facility at the crossing of Warren Road. There are currently two 60” CMP 10 gage pipes, as well as one 36” RCP Class II and one 18” RCP Class II pipe carrying and/or discharging runoff on the downstream side of the crossing. Plate 83 of the Hemet Master Drainage Plan identifies this confluence point with Line A of Southwest Hemet MDP and a total Q100 of 3,400 cfs. ERSC will confer with the District on planned improvements for this location, and the roadway design will incorporate appropriate and agreed-upon District and City improvements.
Hemet Storm Channel - Warren Road
Hemet Storm Channel - Warren Road
Downstream Crossing Looking East
SW Hemet MDP Line B was improved to an 8’W by 4’ H double box structure as part of the improvements for Tract No 35393. It appears the headwall placement on the west side of Warren Avenue takes into consideration the future widening of the street. ERSC will discuss with the City to confirm this assumption.
Salt Creek Channel is an earthen trapezoidal channel with bottom width of 230 feet and 14:1 side slopes residing in a 500-foot right-of-way owned and maintained by the District. The flow of the channel at the Warren Road crossing is a Q100 = 9,200 cfs. There are several SW Lines discharging into Salt Creek above and below the Warren Road crossing which will be included in the Hydrology and Hydraulic analysis for the Bridge.
ERSC has performed analysis on Salt Creek, inclusive of Warren Road bridge, by preparing an LOMR with an Effective Date of February 18, 2000. For this project, ERSC will utilize record data utilized in the preparation of the LOMR in addition to various FEMA Forms for comparison purposes and validation of effects on Salt Creek Channel with the proposed bridge structure.
With the design for widening Warren Road, it is assumed there will be low points along the profile. ERSC will identify these locations and, if appropriate, have low spots picked up via catch basin, which will discharge to existing drainage structures. If no drainage structures exist or are not contemplated for construction, existing drainage patterns will be reviewed to confirm acceptance of the ponding flow and no negative impact on existing improvements. As part of the Storm Drain preparation, hydrology and hydraulic calculations will support the sizing of the catch basin and lateral, whether connecting to a City or District facility. All sizing will be summarized and placed in a Report for submittal to the City and/or District.
Storm drain plans will identify locations of catch basins, local depressions, lateral pipe connections to mainlines, pipe extensions of existing storm drains, and any other storm drain-related appurtenances. Plans will clearly show whether the facility is to be City or District Maintained.
Deliverables:
• One Title Sheet, One Detail Sheet, and Storm Drain Design Plan Sheets (60%, 90%, 100%)
Task 6.11 – Potholing
Utility potholing for this Project will occur once all utilities have been mapped and siteverified at the surface and Improvement Plans are at 60% complete. The proposed design will be reviewed and areas of conflict will be identified. Besides looking for physical conflicts, grade change will be looked at to see if minimum/maximum cover criteria for the various Utilities is compromised.
SW Hemet MDP Line B
SW Hemet MDP Line B - East Side of
Warren Road Looking West
Salt Creek Channel at Domenigoni
Parkway - Looking East
34
15.F.
<Section Title> SECTION III - Project Scope
The City of Hemet’s Traffic Signal Notes requires potholing for all signal pole equipment per Engineer’s direction. Since a 4-legged traffic signal intersection has two poles per corner or eight poles per intersection, it is recommended the traffic signal plans allow for 38 potholes. Other areas of potential conflict may be new utility crossing of existing utilities such as storm drains. The amount of potholes needed for these conflicts is unknown, so an additional 12 potholes will be added to the lump sum amount.
Once areas of conflict are determined, a map will be generated for pothole location and submitted to at least three Pothole companies to obtain competitive bids. ERSC will work with the pothole contractor to pull a City No-Fee Encroachment Permit from the City.
Our fee estimate includes a lump sum cost for potholing work by a utility pothole company and/or contractor.
ERSC will generate a Pothole Map for ERSC’s Survey Team to field locate the utilities to be potholed.
Deliverables:
• Pothole Map
• Pothole Final Report
Assumptions:
• Potholing within City right-of-way will be granted with a No-Fee Encroachment Permit by City or fee will be reimbursable Task 6.12 - Bridge Hydrology & Hydraulics Analysis
ERSC shall perform a hydrologic analysis for the 100-year protection of the selected bridge structure and any impacts upon the existing bridge structures. ERSC will utilize Riverside County Rational Methods for computing peak flows on small, mostly urban watersheds.
The interface includes the capacity to combine runoff from multiple basins. ERSC shall perform hydraulic backwater model analysis using HEC-RAS River System Surface Profiles in rivers (Corps of Engineers) Computer Program for Salt Creek Channel. The analysis shall include the existing conditions model through the project site (Warren Road bridge crossing) and the post-project conditions model.
The analysis compares the water surface elevations calculated for the 100-year flood (Q100) and Q50 for the two conditions.
ERSC shall prepare a scour analysis for the type of bridge proposed, consisting of Contraction scour, Long-Term scour, and Abutment scour through the bridge openings. ERSC shall prepare the necessary studies, plans, and investigation as required to obtain a waterway permit for the new structure. This task will include coordination with RCFC & WCD.
Deliverables:
• Hydrologic Analysis Report
• Hydraulic Analysis of the Proposed Bridge
• Scour Analysis Report
Task 6.13 - Landscaping and Irrigation Plans
ERSC has partnered with Community Works Design Group (CWDG) to provide Landscape and Irrigation within the parkways for the length of the street improvements. The CWDG team brings vast experience developing durable streetscapes within wildland interface areas within the inland regions, with many parallels to Warren Road. They will aim to create an aesthetically pleasing, unifying character to the landscape areas within this important street improvement project. CWDG will strive to complement the native landscape following the City’s Community Design Element and the Scenic Highway Setback Manual.
CWDG will meet on-site with ERSC staff
and City representatives to discuss
the intended outcome of the finished
project, relating to ongoing maintenance,
preferred irrigation components, and
preferred planting selections in addition
to aesthetics and amenities along the
connector the Cit wishes to include. The
CWDG team will collect a soil sample
for Agronomic Soil Testing and meet onsite with the City’s Maintenance team to review existing irrigation and possible
points(s) of connection for the irrigation
system.
CWDG will review the schematic
plans prepared by ERSC and develop a
corresponding conceptual landscape plan
for the scenic highway enhancements. We
will include a conceptual planting plan for parkway adjustments as needed for the Warren Road Improvements.
Upon the City’s feedback from ERSC’s Conceptual Design Submittal, CWDG will begin preparation of the Construction Documents (PS&E) and will make its first submittal at the 65% level, followed by 90% and 100% submittals following subsequent City reviews.
IRRIGATION PLANS: CWDG will prepare irrigation demolition and tie-in plans for the optimal watering of the parkway where it is being modified to accommodate the trail, utilizing City preferred equipment and tying into an existing point of connection where possible.
CWDG will include MWELO Calculations if needed as well.
Warren Avenue - Streetscape
35
15.F.
<Section Title> SECTION III - Project Scope
PLANTING PLANS: CWDG will prepare soil preparation and planting plans for the scope areas. Plant suitability, slope stabilization, maintainability, drought resistance, and reliability will be primary concerns for the Warren Road improvements. We will collect an agronomic soils test.
CWDG will prepare corresponding cost estimates based on real-time industry costs derived from recent bids and product/labor quotes captured by our office from comparable projects and will plan on identifying value engineering and phasing options for the City’s consideration. As the conceptual level drawings progress into design development and construction document level graphics, the inhouse Certified Irrigation Designer will prepare irrigation plans, which will be prepared for full compliance with EMWD standards (of which CWDG has extensive experience in preparing). Specifications will be tailored for compatibility with Greenbook standard format.
CWDG will update plans, specifications, and estimates at the 60% and 90% levels to correlate to the street improvement plans and adjust as needed to match the City’s expectations and available budget. We will promptly finalize the plans to the 100% level for final approval prior to competitive bidding of the project.
Deliverables:
• 30% Concept Design – 24” x 36” at 20’ scale
• 65%, 90%, 100% and Final Planting & Irrigation Plans
• 65%, 90%, 100% and Final Specifications & Cost Estimate ERSC is partnering with Biggs Cardosa Associates, Inc. (BCA) to prepare the required Bridge design documents.
Task 6.14 - Bridge Design Plans
Bridge Considerations
The existing Warren Road Bridge over Salt Creek Channel is a cast-in-place (CIP) post-tension concrete box girder bridge. The bridge is about 30 years old. It is a 5-span structure supported by concrete pier walls on small-diameter cast-in-drilled-hole (CIDH) piles. The bridge carries two lanes of traffic, as well as cyclists and pedestrians. The City desires to increase the capacity of this crossing to four total lanes (two in each direction), along with pedestrian and cyclist facilities along both edges, to conform with the ultimate section of the widened Warren Road.
Alternatives Analysis: Widening vs Separate Structure
The RFP calls for widening of the existing bridge. BCA has performed preliminary structural and cost analyses and concluded that while feasible, structural widening may not be the highest value alternative for adding the desired capacity. Rather, constructing a standalone structure adjacent to the existing bridge would likely capture more long-term value.
One major impediment to widening is the presence of the existing pier walls. As our industry’s understanding of structural seismic behavior has progressed in recent years, the use of walls as substructure elements has increasingly fallen out of favor. This is because discrete columns perform in a more desirable and ductile manner under transverse seismic loading. In fact, Caltrans discourages the use of pier walls altogether for new structures. Where there is a pressing hydraulic need for a continuous wall-like support, Caltrans guidance is to use columns with sacrificial guide walls in between, to mimic the hydraulic profile of pier walls without the undesirable seismic behavior. These sacrificial walls do not contribute any structural capacity.
Unfortunately, it would not be possible to use sacrificial pier walls or simple multi-column supports for the widening alternative to work. This is due to the inherent flexibility of these supports, which undergo more movement under seismic loading (this is key to their desirable seismic behavior). If a flexible structure (columns) is tied to a rigid structure (pier walls) via a continuous deck, the natural seismic movement of the flexible structure will, in effect, be resisted by the rigid structure, potentially causing the rigid structure to be overloaded.
Rather, the widening (“2025 widening”) would be forced to use “true” pier wall supports to induce compatible seismic behavior with the existing bridge. While Caltrans does allow the use of pier walls for widenings, the question arises: What do we do when the original structure needs to be replaced? Upon completion of this project, the original structure will have about 40 years of remaining design life, while the widened portion will have 75 years. Once the time has come to take the original bridge out of service, a thorny issue is revealed: the replacement of the original portion will need to be a widening (of the remaining 2025 portion) on pier walls for seismic compatibility or a separate standalone structure. But this time, proceeding with a standalone structure is much more complicated because the remaining 2025 portion is not wide enough to itself be a standalone bridge. Thus, the 2025 portion must also be removed and replaced with a single wider structure, or the 2025 portion can be kept in service and widened to serve in tandem with a new, narrower, separate structure. At this point, we are essentially painted into a corner – all available options bear enormous inefficiency. 36
15.F.
<Section Title> SECTION III - Project Scope
A better long-term value proposition would be to construct a separate standalone structure now so that the replacement timelines and substructure types of the two structures are decoupled. Although the initial cost may be slightly higher (this will be assessed as part of this project), total lifetime cost will most likely be lower since the long-term inefficiencies and complications associated with widening are completely avoided.
Bridge Lifecycle Cost Analysis
BCA’s team will use Bridge Life Cycle Cost Analysis (BLCCA) to help determine the best-value alternative. BLCCA is an important tool for assessing the relative values of alternatives with dissimilar time horizons and costs, such as new construction v. widening. The life-cycle cost of a bridge consists of the total investment throughout the life of the bridge. This investment includes the initial construction costs, mitigation costs, repair and rehabilitation costs, all anticipated maintenance costs, and future replacement costs. BLCCA synthesizes cost, anticipated service life, and economic factors to reveal the best-value alternative.
BCA’s team is adept at performing this analysis and intends to work with the City to form a value determination that is a key part of our alternatives analysis.
Span Configuration
As part of the Type Selection process, BCA will discuss various span configurations and structure types for both the “widening” and “separate structure” alternatives to arrive at the preferred alternative. For the widening alternative, BCA will replicate the existing bridge span configuration and structure depth. For the “separate structure” alternative, BCA will match the existing span configuration if hydraulically necessary but will assess whether using longer spans and fewer intermediate supports can decrease costs while providing sufficient hydraulic performance. For instance, a four-span structure would have controlling span lengths of about 130 feet, which is not excessive. The new supports would be offset from the existing pier walls, and the structure would need to be about 1’-6” deeper than the existing bridge. BCA will assess whether the extra depth can be accommodated by extending downward into the existing freeboard or upward via profile modifications.
Structure Types
BCA anticipates that prestressed concrete construction will be the ideal construction type for this crossing. The two predominant branches of prestressed concrete, Precast-Prestressed (PC/PS) Concrete Girder construction and Cast-in-Place Post-Tension Concrete Box Girder construction, each carry their own advantages. 37
15.F.
<Section Title> SECTION III - Project Scope
BCA has designed many Precast/Prestressed (PC/PS) girder bridges, so our engineers understand how to maximize the advantages of this structure type. PC/PS girder bridges have grown in popularity in recent years. They are economical and quick to construct and are a great option for crossings over waterways—the girders are erected with cranes, so very little falsework is required, and impacts to the waterway are minimized.
The concrete box girder is the most common bridge type in California. Construction is straightforward and economical. Bridge contractors prefer this structure type. Since all concrete work is formed and all rebar is placed ahead of time, the contractor has ample time to work out any kinks before their work is “set in stone.” This often results in more competitive bidding. Extensive falsework would be needed within the riverbed, which will receive scrutiny from permitting agencies. The BCA team has recent experience designing and permitting CIP/PT bridges in the area (Caltrans District 8) and is well-positioned to shepherd this project through all approvals.
Substructure Type & Hydraulic Considerations
Given the anticipated granular soils at the project area and based on our team’s experience with similar sites, cast-in-drilled-hole (CIDH) concrete piles will likely be the ideal substructure type. Compared to driven piles, CIDH piles offer advantages in constructability, scour resistance, and seismic performance in alluvium. Small-diameter CIDH piles may be used (similar to the existing bridge), or largediameter column extensions may prove more advantageous. BCA’s team will assess these options and the cost and feasibility of driven piles to determine the best value foundation type.
Bridge Aesthetic Considerations:
BCA’s team will thoughtfully consider public input in developing an aesthetic scheme that “belongs” to the local community, minimizes maintenance, and deters vandalism. Bridge barriers present a great opportunity to imbue a bridge with a distinct architectural feel at a low cost. Caltrans has recently taken a step forward in aesthetics by developing some standard, open-style vehicular barriers that are quite handsome (Type 85, Type CA ST-75). BCA’s team can also provide custom decorative pedestrian barriers since it is anticipated that a separated walkway will be required (due to design speed over 45 mph). Aesthetic enhancements will be selected in close coordination with the City to achieve a scheme that is impactful, uncluttered, and low-maintenance.
Task 6.14.1 - 35% Bridge PS&E
A Structure Type Selection Report will be prepared for the Warren Road Bridge widening. The report will include a discussion of foundation and falsework requirements, seismic and aesthetic considerations, traffic handling requirements, staging, and construction costs. Anticipated construction methods for delivering precast members and lifting them into place will be identified in the Type Selection process and verified against site and delivery route constraints. BCA will submit Type Selection documents to ERSC for review and approval. BCA shall prepare a preliminary cost estimate for each structural alternative to be included in the Structure Type Selection Report. BCA shall perform a Bridge Lifecycle Cost Analysis (BLCCA) to aid in identifying the best-value alternative.
Upon receipt of comments on the draft Structure Type Selection Report, BCA will provide written responses to any structures-related comments from the City and other review agencies. An updated/final Structure Type Selection Report will be prepared and submitted.
Deliverables:
• Structure Type Selection Report in pdf format (Draft and Final) Task 6.14.2 - 65% Bridge PS&E
BCA shall produce a bridge design package in accordance with the latest Caltrans and City practices. The design package shall include 65% bridge draft structural plans, draft specifications and special provisions, and a 65% preliminary engineer’s construction cost estimate for structures-related items.
All plans, specifications, and estimates shall conform to the criteria, policies, procedures, and standards of Caltrans and the City and shall be made available to the City and ERSC at 65% submittal and upon request.
The 65% structural plans produced by BCA will be consistent with the preferred alternative from the Structure Type Selection Report.
At the outset of the project, structure Specifications shall follow the 2024 Caltrans Standard Specifications, and 2024 Caltrans Standard Plans shall be incorporated by reference into the structural plans.
Structural Design will be per AASHTO Bridge Design Specifications (8th Edition) with California Amendments, and Caltrans technical design manuals, guidelines, and criteria. Seismic design will be per Caltrans Seismic Design Criteria (SDC) 2.0. As stated in SDC, standard seismic design may need to be supplemented with a more detailed analysis due to the classification of pier walls as a “nonstandard bridge feature.” The methodology of this supplemental analysis will be determined internally by BCA.
Structural plans shall include no more than one (1) sheet dedicated to aesthetic details.
Structural plans shall include no more than one (1) sheet dedicated to removal and/or modification of existing bridge elements to facilitate widening.
Structural plans shall include no more than one (1) sheet dedicated to rock slope protection details. It is assumed that rock-slope protection will be designed by the Hydraulics Engineer and drafted into the bridge plans by BCA per the Hydraulics Engineer’s recommendations.
Structural plans will include design of a deck drain system that serves the widening portion only. Design will be based on Caltrans guidelines and either rainfall data provided by others in a drainage report or conservative assumptions of rainfall intensity as prescribed by Caltrans. If it is not permissible to allow runoff to flow freely into the creek below, the design of the system will include pipes that run past the back face of abutment, at which point the drainage design (by others) will govern conveyance of the runoff away from the bridge.
38
15.F.
<Section Title> SECTION III - Project Scope
BCA will provide written responses to comments on the 65% design package from the City and other review agencies.
Deliverables:
• Up to ten (10) 11”x17” hard copy sets of 65% bridge structural plans (unsigned). • Electronic copies of the 65% Design Plans (unsigned) in PDF form, 65% Structural Cost Estimate in PDF and MS Excel form, and Draft Structure Specifications and Special Provisions in PDF and MS Word form.
Task 6.14.3 - 95% Bridge PS&E
BCA shall produce a bridge design package in accordance with the latest Caltrans and City practices. The design package shall include 95% plans for bridge and approach retaining walls, edited specifications and special provisions, design calculations, and a 95% engineer’s construction cost estimate for bridge and support structures.
All plans, specifications, calculations, and estimates shall conform to criteria, policies, procedures and standards of Caltrans and the City. They shall be made available to the City and ERSC at 95% submittal and upon request.
Structural calculations shall be provided for the bridge and any retaining walls that are not covered by Caltrans Standard Plans or that are manufacturer/contractor-designed retaining walls.
Design of structures shall be governed by the same codes and specifications as the previous design submittal.
Retaining wall design shall include layout of retaining walls.
Structure Specifications shall follow the 2024 Caltrans Standard Specifications, and the 2024 Caltrans Standard Plans shall be incorporated by reference into the structural plans.
BCA will provide written responses to comments on the 95% design package from the City and other review agencies.
Deliverables:
• Up to ten (10) 11”x17” hard copy sets of 95% bridge structural plans (unsigned). • Up to one (1) hard copy of each of the 95% Structural Cost Estimate, and Edited Structure Specifications and Special Provisions, 95% Design Calculations. • Electronic copies of the 95% Design Plans (unsigned) in PDF form, 95% Structural Cost Estimate in PDF or MS Excel form, Edited Structure Specifications and Special Provisions in PDF and MS Word form, and 95% Design Calculations in PDF form Task 6.14.4 - Bridge Independent Check
BCA will perform an Independent Design Check between the 65% and 95% milestones. The 95% PS&E package will have incorporated all design check comments to the satisfaction of the lead Independent Check Engineer, who will be a Registered Professional Engineer in the State of California and will initial the “checked by” box in the 95% plans.
The independent check shall include “constructability” comments/suggestions intended to improve ease of construction.
The independent checker shall verify the designer’s methodology, including the following work:
• Review relevant background and supporting information; • Verify member capacities;
• Review plans for completeness and consistency with the design; • Resolve design issues with the designer – final design will reflect agreement between the designer and checker; • Check the corrected plans for conformance with prior comments; • Review project special provisions to ensure all bridge items and associated items of work are adequately addressed, and; • Prepare independent quantity calculations as needed to verify the accuracy of the construction estimate.
Task 6.14.5 - 100% Bridge Final PS&E
BCA shall incorporate changes due to comments received from the City and other agencies’ review of the 95% submittal materials to produce 100% Final design materials. The design package shall include 100% plans for bridge and approach retaining walls, edited specifications and special provisions, design calculations, and a 100% engineer’s construction cost estimate for bridge and support structures, including independently reviewed structural quantities.
All plans, specifications, calculations, and estimates shall conform to criteria, policies, procedures, and standards of Caltrans and the City. They shall be made available to the City and ERSC at 100% submittal and upon request.
Structural calculations shall be provided for the bridge and any retaining walls that are not covered by Caltrans Standard Plans or that are manufacturer/contractor-designed retaining walls.
Design of structures shall be governed by the same codes and specifications as the previous design submittal.
Structural plans shall include no more than one (1) sheet dedicated to aesthetic details.
Structure Specifications shall follow the 2024 Caltrans Standard Specifications, and the 2024 Caltrans Standard Plans shall be incorporated by reference into the structural plans. If the 2024 standards have lapsed, the design package may be updated to the most current standards. One (1) standards update is included in this scope. 39
15.F.
<Section Title> SECTION III - Project Scope
Deliverables:
• Up to four (4) 11”x17” hard copy sets of 100% bridge structural plans. • Up to one (1) full-size hard copy set of 100% bridge structural plans. • Up to two (2) hard copies of each of the 100% Structural Cost Estimate and Final Quantities. • Up to four (4) hard copies of the Final Structure Specifications and Special Provisions. • Electronic copies of the 100% Design Plans (unsigned) in PDF form, 100% Structural Cost Estimate in PDF and MS Excel form, Edited Structure Specifications and Special Provisions in PDF and MS Word form, 100% Design Calculations in PDF form, and Final Quantities in pdf form.
Task 6.15 - NOI/SWPPP
As plans are prepared for 60% submittal, ERSC will prepare a Notice of Intent (NOI) and a Storm Water Pollution Prevention Plan (SWPPP) for the project and submit a draft version for the City to review. Comments will be incorporated into the plan for final submittal to the Regional Water Quality Control Board.
ERSC will prepare the SWPPP Permit Registration Documents (PRD) and upload to the State Water Board’s Stormwater Multiple Application and Report Tracking System (SMARTS). The task of preparing the SWPPP includes the preparation of the Notice of Intent, the plan document, location map, GIS-based mapping, erosion control plans, post-construction BMP requirements, and other associated graphics, specified exhibits, and appendices.
Final SWPPP includes discussions of the purpose and objective, source identification, potential pollutants and source identification, structural and non-structural Best Management Practices (BMP), erosion and sediment control maintenance procedures, inspection and repair, related permits, and monitoring and reporting.
SWPPP Documents prepared by ERSC will, as specified in the General Permit, address and fulfill the following objectives and requirements:
• All pollutants and their sources, including sources of sediment associated with construction, construction site erosion, and all other activities associated with construction activity, are controlled; • Where not otherwise required to be under a Regional Water Board permit, all non-stormwater discharges are identified and either eliminated, controlled or treated;
• Site BMPs are effective and result in the reduction or elimination of pollutants in stormwater discharges and authorized nonstormwater discharges from control activity to the BAT/BCT standard; • Calculations and design details, as well as BMP controls for site run-on, are complete and correct, and; • Stabilization BMPs installed to reduce or eliminate pollutants after construction are completed. • To demonstrate compliance with the requirements of the General Permit, the QSD shall include information in the SWPPP that supports the conclusions, selections, use, and maintenance of BMPs.
Following issuance of the Waste Discharge Identification Number (WDID) by the State Water Resource Control Board (SWRCB) and onset of construction, if the City desires, services by the ERSC team may then include weekly site inspection services, monitoring of contractor’s erosion control devices installation and maintenance, provide visual observation of non-stormwater discharges, prepare required documentation, sample run-off water and test for quality during qualified wet weather events, and preparation of all documentation and paperwork required. At the conclusion of construction, ERSC will prepare the Notice of Termination (NOT) to the SWRCB certifying compliance with the General Permit or a letter describing items to be resolved. NOT documents will be uploaded to SMARTS. Services included in this task are only for preparation and upload of the SWPPP. Construction inspections and NOT services are not included but may be negotiated separately if the City desires.
Deliverables:
• Notice of Intent
• Storm Water Pollution Prevention Plan (Draft and Final) Post Development WQMP
The RFP indicated City Staff will prepare a Water Quality Management Plan (WQMP) for the project.
TASK 7 - SPECIFICATIONS & ESTIMATES
Task 7.1 – Specifications
Project Specifications will be prepared utilizing the City’s current boilerplate bid package, Special Provisions, and the latest editions of AASHTO, Greenbook for Public Works Construction, Caltrans Specifications, City Standards, and appropriate Agency Standards. The bid package will be prepared in Microsoft Word and remain in the City’s boilerplate font and format. All additions or changes to the boilerplate shall be highlighted in yellow for each respective first plan check submittal. The project specifications and bid documents will include the detailed project description, preparation of bid schedules, bid item descriptions, special provisions, technical specifications, and specification detail sheets or standard plans, as needed.
Deliverables:
• 60%, 90% and 100% Bid Package in Word format
40
15.F.
<Section Title> SECTION III - Project Scope
Task 7.2 – Cost Estimate
The ERSC Team will provide an itemized Engineer’s Cost Estimate at the 60%, 90%, and 100% levels of design for all proposed improvements. The estimates will be detailed with unit prices and quantities for individual line items of work and specified equipment based on the historical cost index.
Cost estimate details, including items and descriptions, will be consistent with bid items and specification sections.
Deliverables:
• 60%, 90% and 100% Engineer’s Cost Estimate in Excel format TASK 8 – BIDDING SUPPORT & CONSTRUCTION PHASE SUPPORT
Task 8.1 – Bidding Support Phase
Our Project Manager and key personnel shall attend Pre-Bid Construction Meetings and other office and field meetings necessary to clarify any design questions raised and found from the plans prior to construction beginning on the project. ERSC will work closely with City staff to respond to all bid inquiries and questions relating to the plans and specifications during the bid period. Should addenda be required, our team will assist the City with their preparation. All written responses to Contractor inquiries will be provided within two (2) working days of receipt of the Contractor’s request. Along with this support, we will also be available to attend the bid opening. If requested, our staff will conduct a review of the bids and supporting documentation to confirm the lowest responsive and responsible bidder. Once this review is complete, we will make a recommendation and assist the City with the acceptance and award or with a rebid of the project if determined necessary.
Deliverables:
• Written responses to all inquiries and questions within two (2) working days • Preparation and assistance in Bid Addenda
Task 8.2 – Construction Support Phase
ERSC’s Project Manager and key personnel will provide review of shop drawings and materials/product submittals for conformance with the plans and specifications prior to and during construction. In addition, our staff will be available to review and respond to Contractor’s Requests for Information (RFIs), review any change orders (COs), and provide clarification of design intent when necessary.
ERSC will also assist in the preparation of addenda and any plan revisions due to construction changes.
Within thirty (30) days following the completion and acceptance of the Project, ERSC will furnish a complete set of As-Builts on Bond paper to the City. Revisions will be solely based upon as-built information provided to the City and ERSC by the City’s Construction Manager and the Contractor. Upon approval of bond copy of plans by the City, ERSC will plot the As-Builts on Mylar for submittal to the City for their records.
Deliverables:
• Review and written approval of materials/product submittals • Written responses to RFIs and COs
• Preparation of addenda
• Final “as-built” drawings reflecting construction changes (“D” size on Mylar, plus electronic copy in AutoCAD and PDF format) 41
15.F.
15.F.
COST PROPOSAL
Professional Engineering
Services for Warren
Road Improvements
Submitted: January 30, 2025
15.F.
Local Office:
1861 W. Redlands Blvd.
Redlands, CA 92373
(909) 890-1255, [email protected]
Evaluation Period Contact:
Lori Askew
Project Manager
(909) 890-1255 x110
[email protected]
1861 W. Redlands Blvd. | Redlands, CA 92373
(909) 890-1255 | [email protected] | www.erscinc.com
January 30, 2025
City of Hemet
445 East Florida Avenue
Hemet, CA 92543
Attn: Candace Sunds
RE: COST PROPOSAL - Professional Engineering Services for Warren Road Improvements Dear Ms. Sunds:
Engineering Resources of Southern California (ERSC) is committed to addressing our clients’ needs in a responsive, budget-conscious, focused, and technically sound manner. In response to the City’s Request for Proposal, ERSC hereby submits our fee schedule for Proposal to Provide Professional Engineering Services for Warren Road Improvements.
ERSC’s services are based on the enclosed Fee Schedule of Hourly Billing Rates. The rates will remain the same throughout the PSA agreement.
We look forward to the possibility of continuing to work with the City of Hemet and thank you for the opportunity to submit a proposal.
If you have any questions or require additional information, please contact me at [email protected] or (909) 890-1255, ext. 103. I am authorized to bind the firm in a potential agreement.
Respectfully submitted,
John M. Brudin, PE Lori Askew
President Project Manager
15.F.
DESCRIPTION
Principal in Charge,
President
Matt Brudin, PE, QSD
Project Manager,
Sr. Principal Engineer
Lori Askew
Project Engineer,
Vice President
Moe Ahmadi, PE
Project Engineer,
Engineer V
Ben Booth, PE
Design Engineer,
Engineer IV
Stephania Hernandez
Design Engineer,
Engineer III
Katherine Hernandez
Principal Surveyor
Robert Ollerton, PLS
2-Man Survey Crew
Senior Engineering
Associate
Craig Brudin
Engineer II
ERSC SUBTOTAL
Inland Aerial Survey
Aragon Geotchnical, Inc.
Biggs Cardosa, Assoc.
Community Works
Design Group
STC Traffic, Inc.
Potholing
Title Reports
SUBCONSULTANT
SUBTOTAL
TOTAL
$305 $255 $260 $195 $175 $160 $215 $320 $190 $145
Project Management, Coordination, Meetings 6 96 8 8 8 8 4 - 4 8 $ 35,410.00 $ - $ 918.75 $ 25,032.00 $ 8,820.00 $ 21,210.00 $ - $ 55,980.75 $ 91,390.75 SUBTOTAL $ 1,830.00 $ 24,480.00 $ 2,080.00 $ 1,560.00 $ 1,400.00 $ 1,280.00 $ 860.00 $ - $ 760.00 $ 1,160.00 $ 35,410.00 $ - $ 918.75 $ 25,032.00 $ 8,820.00 $ 21,210.00 $ - $ 55,980.75 $ 91,390.75
2.1 As-Built Research, Investigation & Review 4 8 4 12 12 12 - - 24 $ 14,140.00 $ - $ - $ 30,765.00 $ - $ 8,862.00 $ - $ 39,627.00 $ 53,767.00
2.2 Utility Coordination, Research & Notification 2 2 2 4 4 - 16 $ 5,380.00 $ - $ - $ 5,380.00
2.3 Survey & Mapping 2 - 8 24 104 240 76 284 $ 160,690.00 $ 33,495.00 $ - $ 33,495.00 $ 194,185.00
2.4 Geotechnical Analysis & Report 1 2 $ 775.00 $ 101,850.00 $ - $ 101,850.00 $ 102,625.00 SUBTOTAL $ 1,830.00 $ 3,315.00 $ 2,080.00 $ 4,680.00 $ 2,100.00 $ 6,400.00 $ 22,360.00 $ 76,800.00 $ 14,440.00 $ 46,980.00 $ 180,985.00 $ 33,495.00 $ 101,850.00 $ 30,765.00 $ - $ 8,862.00 $ - $ 174,972.00 $ 355,957.00
ENVIRONMENTAL REPORTING AND COORDINATION
Technical Studies/Coordination 2 8 4 16 4 4 $ 8,150.00 $ - $ 8,150.00 SUBTOTAL $ 610.00 $ 2,040.00 $ 1,040.00 $ 3,120.00 $ 700.00 $ 640.00 $ - $ - $ - $ - $ 8,150.00 $ - $ - $ - $ - $ - $ - $ 8,150.00
RIGHT OF WAY ENGINEERING
4.1 Right of Way Requirement Map 2 8 16 40 2 40 $ 18,400.00 $ - $ 18,400.00
4.2 Legal and Plat - 27 parcels 8 12 24 162 378 $ 97,860.00 $ - $ 97,860.00
4.3 Title Reports - 27 2 2 4 8 $ 2,700.00 $ 28,350.00 $ 28,350.00 $ 31,050.00
4.4 TCE (Optional) - 38 Parcels 4 8 16 228 532 $ 131,300.00 $ 11,550.00 $ 11,550.00 $ 142,850.00 SUBTOTAL $ 610.00 $ 5,610.00 $ - $ 7,410.00 $ - $ 13,440.00 $ 84,280.00 $ - $ - $138,910.00 $ 250,260.00 $ 39,900.00 $ 39,900.00 $ 290,160.00
PERMITTING
Agency Permitting 4 24 8 40 24 - - 24 $ 24,540.00 $ - $ - $ - $ - $ - $ - $ 24,540.00 SUBTOTAL $ 1,220.00 $ 6,120.00 $ 2,080.00 $ 7,800.00 $ - $ 3,840.00 $ - $ - $ - $ 3,480.00 $ 24,540.00 $ - $ - $ - $ - $ - $ - $ 24,540.00
CONSTRUCTION DOCUMENTS
6.1 Street Improvement Plans 4 12 36 80 80 - - 360 $ 94,240.00 $ - $ - $ - $ - $ - $ - $ 94,240.00
6.2 Traffic Signal Warrant Analysis Study 1 2 $ 645.00 $ 24,738.00 $ 24,738.00 $ 25,383.00
6.3 Traffic Signal Design Plans 1 - 4 8 - $ 2,315.00 $ - $ - $ 207,648.00 $ - $ 207,648.00 $ 209,963.00
6.4 Signing & Striping Design Plans - 2 - 4 8 $ 2,570.00 $ 165,984.00 $ 165,984.00 $ 168,554.00
6.5 Street Lighting/Electrical Design Plans - 2 - 4 8 $ 2,570.00 $ 126,756.00 $ 126,756.00 $ 129,326.00
6.6 Traffic Signal Fiber Optic Interconnect Desig Plans (Optional) 2 - 8 8 $ 3,350.00 $ 103,908.00 $ 103,908.00 $ 107,258.00
6.7 Traffic Control Phasing Plans (Optional) 2 4 16 16 - $ 7,310.00 $ 220,689.00 $ 220,689.00 $ 227,999.00
6.8 VMT Traffic Analysis Screening Evaluation - 2 - 2 $ 900.00 $ 8,400.00 $ 8,400.00 $ 9,300.00
6.9 Full VMT Traffic Analysis (Optional) 2 2 $ 900.00 $ 21,000.00 $ 21,000.00 $ 21,900.00
6.10 Storm Drain Improvement Plans 8 16 40 40 60 40 80 $ 53,220.00 $ - $ 53,220.00
6.11 Potholing - 50 potholes 4 24 16 2 16 4 16 $ 16,890.00 $ 73,500.00 $ 73,500.00 $ 90,390.00
6.12 Bridge Hydrology & Hydraulics Analysis 16 36 48 24 24 40 $ 36,640.00 $ - $ 36,640.00
6.13 Landscaping & Irrigation Plans 2 4 8 $ 2,570.00 $ 77,007.00 $ 77,007.00 $ 79,577.00
6.14 Bridge Design Plans 2 8 8 16 16 8 $ 11,570.00 $ - $ 11,570.00
6.14.1 35% Bridge Submittal - Structure Type Selection Report $ - $ 79,044.00 $ 79,044.00 $ 79,044.00
6.14.2 65% Bridge Submittal $ - $ 275,310.00 $ 275,310.00 $ 275,310.00
6.14.3 95% Bridge Submittal $ - $ 111,069.00 $ 111,069.00 $ 111,069.00
6.14.4 Independent Check $ - $ 40,792.50 $ 40,792.50 $ 40,792.50
6.14.5 100% Final Bridge Submittal $ - $ 48,153.00 $ 48,153.00 $ 48,153.00
6.15 NOI/SWPPP 2 4 8 40 56 40 $ 27,110.00 $ - $ 27,110.00 SUBTOTAL $ 5,490.00 $ 19,890.00 $ 33,280.00 $ 57,330.00 $ 24,500.00 $ 37,120.00 $ 430.00 $ 5,120.00 $ 760.00 $ 78,880.00 $ 262,800.00 $ - $ - $ 554,368.50 $ 77,007.00 $ 879,123.00 $ 73,500.00 $ - $ 1,583,998.50 $ 1,846,798.50
CONSTRUCTION COST ESTIMATE & SPECIFICATIONS
7.1 Specifications 1 24 16 48 60 0 $ 29,545.00 $ - $ - $ - $ - $ 9,492.00 $ - $ 9,492.00 $ 39,037.00
7.2 Cost Estimate 2 8 8 24 48 24 $ 20,570.00 $ 7,434.00 $ 7,434.00 $ 28,004.00 SUBTOTAL $ 915.00 $ 8,160.00 $ 6,240.00 $ 14,040.00 $ - $ 17,280.00 $ - $ - $ - $ 3,480.00 $ 50,115.00 $ - $ - $ - $ - $ 16,926.00 $ - $ - $ 16,926.00 $ 67,041.00
BIDDING SUPPORT & CONSTRUCTION SUPPORT
8.1 Bidding Support Phase 2 8 8 24 8 8 - - - $ 12,090.00 $ - $ - $ 17,598.00 $ 8,400.00 $ 7,350.00 $ - $ - $ 33,348.00 $ 45,438.00
8.2 Construction Support Phase 4 8 16 24 8 16 $ 16,060.00 $ 119,196.00 $ 8,400.00 $ 7,266.00 $ - $ - $ 134,862.00 $ 150,922.00 SUBTOTAL $ 1,830.00 $ 4,080.00 $ 6,240.00 $ 9,360.00 $ 2,800.00 $ 3,840.00 $ - $ - $ - $ - $ 28,150.00 $ - $ - $ 136,794.00 $ 16,800.00 $ 14,616.00 $ - $ - $ 168,210.00 $ 196,360.00 $ 2,500.00 $ - $ - $ 1,843.80 $ 3,675.00 $ - $ - $ 5,519 $ 8,018.80 $ 842,910.00 $ 33,495.00 $ 102,768.75 $ 748,803.30 $ 106,302.00 $ 940,737.00 $ 73,500.00 $ 39,900.00 $ 2,045,506.05 $ 2,888,416.05 $ 2,888,416.05
$ 2,388,409.05
Optional costs are identified in italics
Task 2 DATA COLLECTION
Task 4
Task 5
FEE SCHEDULE
City of Hemet
Design Services for Warren Road Improvements
TASK NO.
Task 1 PROJECT MANAGEMENT
Task 3
Task 6
PROJECT TOTAL/NOT - TO - EXCEED (Excluding Optional Costs) Task 7
PROJECT TOTAL/NOT - TO - EXCEED (Including Optional Costs) Reimbursable Expenses (Repro, Plotting, Shipping, Mailing and Mileage; RCFC EPs) TOTALS
Task 8
15.F.
<Section Title> <Section Title> ### Engineering Resources of Southern California, Inc. | Schedule of Rates Professional Staff
President ........................................................................... $305.00 Vice President.................................................................... $260.00 Sr. Principal Engineer......................................................... $255.00 Principal Engineer.............................................................. $230.00 Assistant Principal Engineer .............................................. $215.00 Engineer V ......................................................................... $195.00 Engineer IV ........................................................................ $175.00 Engineer III ........................................................................ $160.00 Engineer II ......................................................................... $145.00 Engineer I .......................................................................... $130.00 Engineering Staff
Principal Engineering Associate......................................... $210.00 Senior Engineering Associate ............................................ $190.00 Engineering Associate V .................................................... $165.00 Engineering Associate IV ................................................... $145.00 Engineering Associate III.................................................... $135.00 Engineering Associate II..................................................... $120.00 Engineering Associate I...................................................... $115.00 Engineering Aide II .............................................................. $65.00 Engineering Aide I ............................................................... $60.00 Survey Staff and Services
Principal Surveyor.............................................................. $215.00 Senior Surveyor................................................................. $175.00 Surveyor III ........................................................................ $140.00 Surveyor II ......................................................................... $125.00 Surveyor I .......................................................................... $105.00 2-Man Survey Crew (Std Equipment/Truck)...................... $320.00 1-Man Survey Crew (Std Equipment/Truck)...................... $250.00 3rd Man on Survey Crew................................................... $140.00 Construction Support Staff
Construction Manager....................................................... $215.00 Chief Construction Inspector............................................. $165.00 Sr. Construction Inspector................................................. $155.00 Construction Inspector...................................................... $145.00 Inspector Overtime (Hours 8-12/Saturdays) ..................... $200.00 Inspector Overtime (Hours 12+/Sundays)......................... $235.00 Administrative Staff
Operations Manager ......................................................... $120.00 Operations Specialist......................................................... $100.00 Administrative Assistant II ................................................... $90.00 Administrative Assistant I .................................................... $80.00 Other Direct Expenses
Vehicle Mileage ................................................ $0.70/Mile Subconsultant................................................... Cost + 20% Reimbursable Expenses/Charges ..................... Cost + 15% Forensic Analysis ................................. Standard Rate X 2 Expert Witness .................................... Standard Rate X 3 NOTE: All rates hereon are subject to automatic increase upon July 1st of each year. Rates will be adjusted by the percent increase in California Consumer Price Index-All Urban Consumers for the twelve-month period ending February as calculated by the California Department of Industrial Relations (CADIR) California Consumer Price Index Calculator. Prevailing Wage Rates are dictated by the CADIR. All classifications which are subject to Prevailing Wages will be adjusted when revised determinations are published by the CADIR.
Unless otherwise established by contractual agreement,
payment is due and payable upon receipt. Payment is considered delinquent if not paid within 30 days of invoice date. If payment is not completed within agreed terms, Client agrees to pay a service charge on the amount past due at the rate of 1.5% per month (18% per annum).
March 1, 2024
15.F.
15.F.
Prepared for:
City of Hemet
445 East Florida Avenue,
Hemet, CA 92543
Contact: Candace Sunds
Phone: (951) 765-2345
E-mail: [email protected]
Prepared by:
TKE Engineering, Inc.
2305 Chicago Avenue
Riverside, CA 92507
Contact: Terry Renner, P.E., P.L.S., Q.S.D
Phone: (951) 680-0440
E-mail: [email protected]
TABLE OF CONTENTS
Cover Letter
Section I | Experience
Section II | Personnel
Section III | Project Scope
Section IV | Fee Schedule
15.F.
Page |1
COVER LETTER
January 30, 2025
Candace Sunds
Procurement Administrator
City of Hemet
445 East Florida Avenue
Hemet, CA 92543
Subject: Request for Proposal for Warren Road Improvements Dear Ms. Sunds,
Thank you for the opportunity to present TKE Engineering, Inc. (TKE)’s proposal to provide professional engineering services to the City of Hemet (City). We have been providing numerous cities with street improvementservices over the past 25 years on highly visible arterial corridors and are highly qualified to perform the design services necessary.
TKE has worked with the City on other past projects and can fully meet the requirements of the City’s Professional Service Agreement. All the elements of the request for proposal have been reviewed and understood, and TKE is enthusiastic about the opportunity to assist the City with these services.
Why should the City choose TKE to provide professional engineering services? Please consider the following:
A. Firm Identification – TKE, a California Corporation, is a full service, multi-disciplinary consulting corporation located at 2305 Chicago Avenue, Riverside, California 92507 and can be found online at www.tkeengineering.com or reached by phone (951) 680-0440. We have 25 years of experience with providing street and bridge widening, transportation, traffic, and drainage design engineering services to public agencies and are highly qualified to perform the services necessary for project delivery.
B. Key Contact – Terry Renner, P.E., P.L.S., Q.S.D., Principal-In-Charge, is an authorized signatory of the firm and will be TKE’s contact person for the duration of the proposal evaluation and contract. He can be contacted at 2305 Chicago Avenue, Riverside, CA 92507 or reached by telephone at (951) 680-0440 and e-mailed at [email protected].
C. Our Experience and Qualifications – TKE is a firm capable of managing and delivering the services presented in the RFP. We specialize in design, project management and construction administration of transportation and traffic improvement public works projects. TKE’s broad range of successful services includes turnkey programs, project management, and delivery for a diverse array of median construction, transportation, bridge widening, and street widening projects. A list of projects that TKE has successfully completed is presented in our proposal. The City will benefit from our broad range of experience through our intimate understanding of the common pitfalls for each project variation, and our past history of successfully overcoming these challenges. TKE’s extensive design experience is identified in the proposal and will also greatly benefit the City.
D. Our Commitment and Availability – TKE is committed to providing high quality, efficient services to meet all of the City’s needs. Upon notice to proceed, Mr. Renner will meet with staff regularly to discuss requirements and scheduling needs. In addition, he will be in contact with others as required to keep projects proceeding efficiently, on schedule and within allocated budgets. It is this personal touch and contact that define our “local service” approach. We consider ourselves community builders and take ownership of projects assigned to TKE, ensuring that our personnel will be allocated on an as needed basis in order to complete all projects on schedule and within budget.
Our broad array of services and in-house team provide the City a trusted consultant to turn to in any challenge, no matter how simple or complex. We pride ourselves in the management and completion of special, atypical projects
15.F.
Page |2
COVER LETTER
and thrive on challenging budgets and deadlines. It is this commitment to service and diverse array of offerings that makes us unique and drives our long-standing relationships with our client base, and it is these qualities that make us “the right fit” for the City. Understanding that all aspects of the project are important, our team brings TKE management level professionals to the project ensuring that every aspect receives full consideration.
E. Our Value – TKE’s management team and staff are fundamentally committed to creating value in each task that we perform. As such, we have created a professional culture wherein each member of our staff constantly strives for increased efficiency, ultimately allowing us to provide highly professional services at competitive rates.
This culture of constant value creation and increased efficiencies ensures that the services contracted to and provided by TKE will always mean good stewardship of public resources.
F. Exceptions & Authorizations - TKE does not have any exceptions to the RFP and the Professional Service Agreement. TKE’s Senior Vice President, Terry Renner, P.E., P.L.S., Q.S.D. is authorized to sign and bind the proposal.
Thank you for your consideration. TKE would very much appreciate the opportunity to provide traffic engineering services. If you have any questions, please call me at (951) 680-0440.
Sincerely,
Terry Renner, P.E., P.L.S., Q.S.D.
Senior Vice President
TKE Engineering, Inc.
Phone: (951) 680-0440
Fax: (951) 680-0490
15.F.
Page |3
SECTION I | EXPERIENCE
SECTION I | EXPERIENCE
A. COMPANY OVERVIEW
TKE Engineering, Inc. (TKE), a California Corporation, was established in June 2000, and in the last twenty-five years has developed into one of Southern California’s premier full-service consulting engineering firms. TKE was
established with the goal of providing turnkey services for municipal projects in order to benefit our community. As a result of the focus of a firm on this mission, TKE has earned a reputation for thoroughness, rapid turnaround, cost efficiency and, overall quality of work. We are a
highly motivated, dynamic firm with the goal of being the City of Hemet’s preferred consultant.
TKE provides turnkey consulting engineering services to several municipalities throughout Southern California.
The following is a listing of services provided by TKE which are required for successful completion of a street
construction and widening project:
P ROJECT M ANAGEMENT
Project management is the most critical element for
successful completion of any design project and is
especially important for this project since we will be
coordinating with subconsultants for appraisals,
acquisitions, environmental compliance, regulatory
permitting and utility coordination/relocations.
TKE provides effective project management services to a variety of clients. We have successfully delivered
extensive and highly visible street improvement, street widening and drainage improvement projects throughout
Southern California and more particular Riverside County for the Cities of Wildomar, Moreno Valley, Riverside,
Calimesa, and Corona. TKE’s approach has consistently
allowed our partner agencies to fulfill their missions of delivering the best value for the public’ investment.
TKE’s management approach includes:
Δ Monthly Progress Reports - TKE documents
project progress for all project assigned to TKE by a
comprehensive project management summary. The
summary includes project name and related number,
description of progress, budget status, schedule
compliance, and anticipated upcoming accomplishments.
Δ Communication - Communications with agencies’ staff
and developers is another important component to
effective project management. In addition to the monthly TKE Engineering, Inc. | AT A GLANCE
City/District Engineer
City/District Engineer in 5
Cities/Districts
Size of Organization
67 Professional Engineers, Project
Managers, Surveyors, Plan Checkers,
Inspectors, Designers, Construction
Managers, and Support Staff
Location of Office
2305 Chicago Avenue
Riverside, CA 92507
Years in Business
TKE has conducted business for the
past 25 years and has 24 years of
experience in providing engineering
design services for pavement
rehabilitation projects.
Company Structure
TKE is a California Corporation
founded in June 2000. TKE is not a
subsidiary. California Business
License Number: 00109901
Firm Owners
Michael P. Thornton, P.E., P.L.S., M.S. –
President
Terry Renner, P.E., P.L.S., Q.S.D. –
Senior Vice President
Steven W. Ledbetter, P.E., Q.S.D. - Vice
President
City of Hemet
Point of Contact
Terry Renner, P.E., P.L.S., Q.S.D.
2305 Chicago Ave.,
Riverside, CA 92507
Phone: (951) 680-0440
Email: [email protected]
15.F.
Page |4
Warren Road Improvements
City of Hemet
SECTION I | EXPERIENCE
progress reports, TKE meets with clients and developer as needed to ensure the projects are proceeding as
anticipated. We document each discussion or meeting
with notes and electronically mail them to the project
team within three days of the meeting/conference
indicating action items and a schedule for completion of these items.
Δ Record Keeping-TKE keeps records in an organized
filing system both in hard copy and electronic forms.
This organized filing system allows TKE to access
records immediately should they be needed.
Δ Team Meeting-Team meetings include all
subconsultants and City parties that have any interest
in the project development. In particular, the City’s
Engineering and Planning Department will be a close
working partner with the TKE and our subconsultants
in development of project processing and
environmental compliance. TKE routinely develops
working partnerships with members of the City’s
engineering and planning staff and will effectively
work with them to complete expediting project
processing.
Δ Public Meetings-TKE meets with project stakeholders
as needed including City Council, the public,
permitting agencies, utilities, etc. We meet with
them at the project’s onset and throughout the
course of project development to ensure all
stakeholder project needs are considered in the
project design. All meeting preparation (City Staff
Reports, agendas, exhibits, slide shows, etc.) will be
prepared by TKE for each meeting. Again, meetings
will be documented. TKE has provided numerous
similar presentations to Councils (closed sessions,
council meetings, community meetings, etc.).
C IVIL E NGINEERING
TKE’s Civil Engineering projects have included:
Δ Transportation Infrastructure Funding, Planning,
Design, Bidding and Construction
Δ ADA Experts for Pedestrian Facility
Improvements (CBC 11B-Division 4)
Δ Pavement Rehabilitation Strategy Analysis and
Implementation
Δ Drainage Infrastructure Funding, Planning,
Design, Bidding and Construction
Δ Hydrologic Studies/Hydraulic Design
Δ Storm Water Pollution Prevention Plans (SWPPP)
Δ Sediment and Erosion Control Facilities
Δ Hydromodification Studies/Water Quality
Management Plans (WQMPs)
Δ Water, Sanitary Sewer and Recycled Water
Infrastructure Funding, Planning, Design, Bidding
and Construction
Δ Sewer and Water System Hydraulic Analysis
S URVEYING /M APPING /R IGHT - OF - W AY
E NGINEERING
TKE provides Land Analysis services for many projects:
Δ Public Improvements (major or minor)
Δ Land and Real Estate Developments
Our Surveying and Mapping experts provide these
services:
Δ Construction Layout/Staking
Δ Right-of-Way Engineering
Δ Boundary Surveys
Δ Construction Surveys
Δ Design Surveys
Δ Legal Description Surveys
Δ Aerial Mapping
Δ A.L.T.A. Surveys
Δ Topographic Surveys
Δ Control Surveys
Δ Easement Surveys
C OMMUNITY O UTREACH / P UBLIC
R ELATIONS
Depending on the City’s needs, TKE’s strategies are
designed to reach, inform and involve constituents and
stakeholders of planning proposals, projects and
programs. If requested, we can provide opportunities for interested parties to comments, enabling actionable
analysis of feedback received. TKE’s outreach methods
result in building greater consensus and public buy-in.
Services include the design, planning and execution of:
Δ Marketing campaigns
15.F.
Page |5
Warren Road Improvements
City of Hemet
SECTION I | EXPERIENCE
Δ Public information meetings/Groundbreaking
ceremonies
Δ Project branding
Δ Project website design and construction
Δ Project collateral materials (brochures,
presentation boards, etc.)
Δ Graphic design
Q UALITY A SSURANCE /Q UALITY
C ONTROL
TKE takes pride in our reputation for thoroughness, rapid turnaround, cost efficiency and overall quality of work, and believes that a high level of quality is needed on all PS&E packages. High quality design yields the following tangible results:
Δ Ease of oversight
Δ Smoother processing
Δ Healthy number of bidders
Δ Consistent bids
Δ Minimized construction support cost
Δ Absence of design-related change orders
Δ Reduced claims and dispute resolution costs
TKE believes that the most successful quality assurance program is one that is applied inherently throughout the entire design process and all design activities. This
program requires not only formal procedures for
checking, but encourages the conscientious effort of
experienced people to always “create quality” in every
task performed throughout the design process.
This program has become a natural element in all aspects of TKE’s design and management activities, and will guide our work on this contract:
Δ Staff training and development
Δ Assignment of experienced staff
Δ Continuity of staffing
Δ Project-specific work plan
Δ Schedule compliance
Δ Comprehensive field review and compilation of
site data
Δ Established design procedures
Δ Established detailing standards
Δ Established checking procedures, including
independent in-house QA/QC review
Δ Dual (independent) quantity estimates
Δ Review by Constructability expert
This Quality Assurance/Quality Control program is in
place to ensure that PS&E documents prepared by TKE
continue to exceed the standards of our clients and that we will deliver the project on schedule and within budget.
R ESOURCES
TKE’s project team is committed to providing services as presented herein. In addition, TKE maintains state of the art engineering resources that ensure complete
compatibility with our clients resources including
computer software compatibility, filing protocol,
communications protocol, and survey data. Our office
location in Riverside is only 30 minutes from the City and will permit TKE staff to respond to requested meetings or field reviews within a moment’s notice.
TKE will respond to the City’s needs as they arise. Being solely based in Southern California, all of our clients are given the utmost attention. TKE commitment will ensure
that all of the City’s needs are met. We strongly
encourage the City to verify our performance history with our references. Because of TKE proactive management
approach, TKE rarely experiences ‘crisis’ project delivery needs. When requested by our clients, TKE adds
resources, commits extended work hours, develops an
efficient implementation plan and other efforts as
needed.
E XPERIENCE
TKE has extensive experience with an excellent reputation in both the design of and construction support of street widening improvement projects. Throughout our history
of twenty-four years serving Southern California, we have provided design and construction support services for
over 100 miles of street widening, pedestrian
enhancements and drainage facility projects. We have
successfully completed complex and challenging projects for a variety of municipal agencies who have continued to request that we partner with them in delivering projects to their communities.
Our street and drainage improvement projects have
included the full services of civil engineering design,
15.F.
Page |6
Warren Road Improvements
City of Hemet
SECTION I | EXPERIENCE
including coordination with environmental, appraisal,
acquisition, geotechnical, landscape, electrical, and
structural engineers and other consultants necessary for the completion of challenging projects.
We are sure that the successful results of our past
performance in the delivery of drainage improvement
projects, along with our firm’s proven ability to utilize our experience for a complete and well-engineered project,
will provide a valuable resource to the City.
B. SUBCONSULTANTS
TKE has acquired the services of Aragón Geotechnical, Inc. to provide geotechnical investigation.
Aragón Geotechnical Inc. (AGI) is a
highly qualified geotechnical and
construction materials testing firm
with significant experience in
providing services similar to those being requested. AGI is committed to providing geotechnical, materials
testing, and construction field inspection services with a superior degree of professional excellence and
proficiency. They offer clients individual attention and provide innovative solutions at a competitive cost.
AGI traces its roots to the year 1973, followed soon after by the establishment of the present headquarters office in the Woodcrest area of Riverside County. The firm will apply decades of experience acquired by talented
professionals in the fields of geotechnical engineering, engineering geology, hydrogeology, earthquake
engineering, and materials engineering and testing to the project team. Their staff regularly attends scientific
conferences and specialty training sessions to stay
abreast of cutting-edge technologies and new
developments in our disciplines.
Community Works Design Group
(CWDG) draws from the knowledge of
over thirty years of broad, regional
experience with a variety of public and
private projects including community and
regional parks, recreation facilities, streetscape
programs, planned community developments, model
homes, and commercial and institutional developments.
CWDG has the experience and capabilities that will
produce creative and functional design solutions.
They have built our reputation on timely completion of
our contractual obligations and our ability to meet our clients' needs and project schedules. Their staff and
resources are such that we are able to meet the project schedules established by the client.
Their services in the past have stressed the development of precise, thorough, and accurate documents. They feel this policy will be particularly important in the
development of this project in order to meet the client's goals, requirements and schedules.
Vela Engineering
was founded with the
goal of providing innovative electrical solutions
catered to each of our clients’ current needs. We have
extensive experience with electrical systems and low
voltage technology in multiple sectors. The firm holds
professional licenses in multiple states including
California, Washington and Hawaii. Our expertise includes municipal, educational, commercial, medical and
government electrical infrastructure designs. From
lighting and power to substation and grounding designs, our team has the capabilities to create a code compliant design with the end users’ best interest in mind. We strive to handle all the small details in order to provide a safe installation that is both technically sound and pleasing to the eyes.
Richard Brady & Associates, Inc.
(Brady) will serve as our Reservoir
Structural Analysis and Design
subconsultant on an as-needed
basis. Brady was founded in 1999 as a professional
services firm specializing in the design and construction management of water and wastewater facilities.
BRADY is a Southern California based multi – disciplined engineering and construction management firm. BRADY
serves public agencies, the federal government, utilities, and the private sector with a locally-based team of
engineers, CADD designers, environmental scientists,
geologists and support staff. We focus on water, sewer, and recycled water engineering; civil, structural, and
electrical engineering; water quality and treatment
services; subsurface utility engineering; electrical,
instrumentation, and control services; and private
development plan checking.
Brady’s Civil, Structural, and Electrical Engineering Group is a highly qualified and extremely experienced in
complex and diverse water and wastewater projects.
Brady’s engineers have completed dozens of projects,
including both design and design-build. BRADY’s
15.F.
Page |7
Warren Road Improvements
City of Hemet
SECTION I | EXPERIENCE
experience in the design-build world gives us a significant and unique advantage of understanding the challenges of developing designs with constructability in mind. A higher degree of constructability incorporated in the design
phase leads to fewer change orders and less time in the field during the construction phase.
15.F.
Page |7
Warren Road Improvements
City of Hemet
SECTION I | EXPERIENCE
C. PROJECT EXPERIENCE
COUNTY LINE ROAD TRANSPORTATION CORRIDOR (LPP)
City of Calimesa, CA
Client Contact: Will Kolbow
Phone Number: (909) 795-9801
Email: [email protected]
Project Cost: $10.1 million ($3.7 million grant)
Completion Date: Ongoing
DESCRIPTION
TKE prepared and obtained a grant for the City of Calimesa through the Road Repair and Accountability Act of 2017 (SB1) Local Partnership Program (LPP). TKE is preparing street widening and roundabout improvements for the construction of the County Line Road Transportation Corridor. The Project includes four (4) single-lane and one (1) multi-lane roundabouts, together with street, pedestrian, and bicycle improvements, to improve safety and efficiency throughout the corridor. The innovative approach to implement roundabout intersection throughout the corridor provides adequate capacity and level of service to remain a two-lane street; thus, significantly reducing right-of-way and construction costs to construct a four-lane corridor.
SERVICES
Services include grant coordination and management, design, topographic survey, right-of-way engineering, environmental assistance, roadway safety analysis, preparation of exhibits, cost estimates, coordination with California Transportation Commission, construction management, inspection, and construction staking.
KEY STAFF
Michael Thornton, P.E., P.L.S., Terry Renner, P.E., P.L.S., Q.S.D., Steven Ledbetter, P.E., Q.S.D., Octavio Parada, Ron Musser, P.L.S., Monae Pugh, Justin Schlaefli, P.E., T.E., P.T.O.E. Jeff Lantosh, C.P.I.I., Brian McDuffie
SIERRA AVENUE WIDENING PROJECT
City of Fontana, CA
Client Contact: Phillip Burum |
City Manager
Phone Number: (909) 350-6727
Email: [email protected]
Project Cost: $11.3M
Completion Date: Current
DESCRIPTION
The Sierra Avenue widening improvements project is located in the City of Fontana north of Interstate 10 Freeway between Foothill Boulevard and Baseline Road. The project is approximately 1 mile of widening for the City’s primary north-south arterial street, expanding the roadway from 4 lanes to 6 lanes. The project includes street widening, raised landscape median, new sewer main installation, traffic signal installation and modifications, traffic signal interconnect and fiber optic cable installation, and extensive utility coordination for water main replacement, Rule 20A and Rule 20B undergrounding work. The project also includes right-of-way acquisition for 76 parcels, traffic analysis, review of construction plans, coordination with project design consultants, construction management and construction staking services. TKE represents the City with other agencies, represented engineering with the City’s management personnel and other meetings, managed engineering budgets and project schedules.
SERVICES
Services include design, topographic survey, right-of-way engineering and acquisition, roadway safety analysis, preparation of exhibits, cost estimates, utility coordination, construction management, and construction staking.
KEY STAFF
Michael P. Thornton, P.E., L.S., Terry Renner, P.E., P.L.S., Q.S.D., Steven Ledbetter, P.E., Q.S.D., Octavio Parada, Ron Musser, L.S., Monae Pugh
RELEVANCE TO HEMET
• Major Arterial Roadway Widening
• Traffic Signal Modification/Design
• Sewer Design
• Right-of-Way Acquisition
• Extensive Utility Relocations
• Various Pavement Strategies
RELEVANCE TO HEMET
• Project & Construction
Management
• Grant Funded
• Street/Pedestrian Design
• Design Survey
• Right-of-Way Engineering
• Caltrans Local Assistance
15.F.
Page |8
Warren Road Improvements
City of Hemet
SECTION I | EXPERIENCE
CLINTON KEITH ROAD STREET WIDENING
City of Wildomar, CA
Client Contact: Jason Farag
Phone Number: (951) 677-7751
Email: [email protected]
Project Cost: $14.3 million
Completion Date: On-going
DESCRIPTION
The Clinton Keith Street Widening Project is a local funded project located along Clinton Keith Road from Hidden Springs Road to Copper Craft Drive in the City of Wildomar. The project included approximately two miles of sidewalk connectivity, ultimate street widening, storm drain, striping, and private property restoration that required full depth removal and placement of AC pavement; removal and reconstruction of concrete curbs and gutters, ADA ramps, cross-gutters, sidewalks; construction of concrete sidewalks, curbs and gutters, cross-gutters, ADA ramps, medians, and driveway approaches; construction of CMU retaining walls and significant regrading along hillsides; construction of catch basins, rock bioswales, headwalls, and storm drains; installation of a new traffic signal system at Elizabeth Lane and relocation of miscellaneous utilities; modification to traffic signal systems; raising of various utility manholes/valves and installation of traffic signing, striping and loop detectors.
SERVICES
Services included conventional ground survey, design documents, construction staking, and construction inspection were provided by TKE for approximately 11,000 linear feet of paving and miscellaneous street improvements.
KEY STAFF
Terry Renner, P.E., P.L.S., Q.S.D., Chance Renner, E.I.T., Daniel Melero, E.I.T., Ron Musser P.L.S., Brett Enscoe
BOULDER AVENUE IMPROVEMENTS PROJECT
City of Highland, CA
Client Contact: Carlos Zamano
Phone Number: (909) 964-6861
Email: [email protected]
Project Cost: $3.3M
Completion Date: 2023
DESCRIPTION
Boulder Avenue is a major collector street with 2 lanes each direction separated by a median. The scope of the project includes but is not limited to: removal of curb, gutter, asphalt concrete pavement, signage, striping and construction of PCC curbs, gutters, curb ramps, driveways, asphalt concrete pavement, irrigation, median curb, landscaping, hardscape, in-road bicycle detection, decorative way findings signs, street lighting, trail lighting, anti-graffiti coating, architectural treatment on existing sound wall and cape seal located on Boulder Avenue from Greenspot Road to San Manual Village Plaza(Highland Avenue) with in the City of Highland, in the county of San Bernardino, California.
SERVICES
Services include full-service construction management during the construction of the project, coordination, scheduling, administration, inspection, construction surveying and staking, geotechnical services, and materials testing along with biological monitoring and utility coordination for the project.
KEY STAFF
Terry Renner, P.E., P.L.S., Q.S.D., Jose Hernandez, Brian McDuffie, Nelson Blackwell, C.P.I.I., Monae Pugh
RELEVANCE TO HEMET
• Project Management
• Coordination with Multiple
Agencies
RELEVANCE TO HEMET
• Street Widening and Pedestrian
Improvements
• Landscape and Irrigation
• Drainage Culvert Crossings
• Utility Relocations/Coordination
15.F.
Page |9
Warren Road Improvements
City of Hemet
SECTION I | EXPERIENCE
D . REFERENCES
Please see the Table below for a small, but representative list of agencies who have and continue to request TKE to assist them in delivering valuable projects to their communities. We respectfully request that you verify our qualifications with the listed references.
AGENCY CONTACT NAME PHONE NUMBER/EMAIL
DATES SERVICES
PROVIDED
(FROM/THROUGH)
City of Calimesa
908 Park Avenue
Calimesa, Ca 92320
Will Kolbow
City Manager
P: (909) 795-9801
[email protected] 2012-Present
City of Fontana
8353 Sierra Avenue
Fontana, CA 92335
Phil Burum
Deputy City Manager
P: (909) 350-6724
[email protected] 2000-Present
City of Wildomar
23873 Clinton Keith
Road, Suite 201
Wildomar, CA 92595
Jason Farag
Public Works Director
P: (951) 677-7751
[email protected] 2013 – Present
City of Highland
27225 Baseline
Highland, CA 92346
Octavio Duran
Public Works Director
P: (909) 864-6861
[email protected]
2014 – Present
City of Upland
1370 N. Benson
Avenue
Upland, CA 91786
Bob Critchfield
Engineering Manager
P: (909) 291-2946
[email protected]
2000 – Present
City of Palm Desert
73510 Fred Waring
Drive
Palm Desert, CA
92260
Ryan Gayler
Capital Project Manager
P: (760) 776-6393
[email protected] 2021 – Present
15.F.
Page |10
Warren Road Improvements
City of Hemet
SECTION II | PERSONNEL
SECTION II | PERSONNEL
A. MEET THE
PROJECT TEAM
Terry Renner, P.E., P.L.S.,
Q.S.D.
Principal in Charge
R.C.E. No. 69984
Q.S.D. Certification No. 24329
Mr. Renner has 25 years of
engineering and surveying
experience and also has experience as a Plan Checker
and Project Manager. Mr. Renner is a Registered Civil
Engineer in the State of California. He has extensive
experience in the design and construction of street
widening, traffic signal, pavement rehabilitation and
storm drain public works improvement projects,
including project management, design engineering,
construction management and surveying services. In
addition, as detailed on Mr. Renner’s resume, he has
experience with drainage studies preparation, design
and construction engineering for street, sewer and
drainage system improvement projects. Mr. Renner is
well trained in the use of computerized drawing
software. He will assist with various tasks throughout
the course of providing engineering services, such as
base construction drawings, design and construction
estimates.
Mr. Renner’s role on the team will be to manage design
review, compliance with standards and regulations and
perform quality assurance and quality control on all
documents.
Octavio Parada.
Project Manager
Mr. Parada has over 28 years of
progressive experience in civil
engineering in the public works
sector as well as the private
sector. He is result-driven,
proactive and detail-oriented
with a proven track record of successfully handling and delivering a wide variety of complex and challenging
projects. He is dedicated to ensure that projects exceed industry standards and consistently finishing under
budget and schedule. Throughout his career, Octavio has accumulated extensive experience in planning, designing and project completion for more than 30 miles of
roadways, street widening, medians, traffic calming,
roundabouts, signing and striping modifications, bicycle lanes, pedestrian facilities for major corridors, arterials, collectors and residential streets, drainage
improvements, grading plans and computerized system
modeling for drainage master plans. Finally, Octavio has worked in the private sector for commercial and
industrial development as technical director managing
projects from the conceptual stage, through planning,
designing, bidding, construction, and project completion under project specifications and exceeding client
expectations.
Steven W. Ledbetter, P.E.,
Q.S.D.
Project Engineer
R.C.E. No. 84044
Mr. Ledbetter has over 24 years
of professional experience in
the civil engineering
industry. He has handled
various critical and challenging projects from planning through design and implementation; all while ensuring
that projects are executed as per specification in the
stipulated time with quality. He has a well-rounded
background with experience in preparation and analysis
of street and utility improvement plans and
specifications, potable and non-potable water,
wastewater, and drainage; utility master planning
including computer modeling, analysis, and report
preparation; water supply planning including feasibility studies, urban water management plans, water supply
assessments, and verifications; storm water compliance
reporting including water quality management plans
and, storm water pollution prevention plans, permitting and grant writing for various State and Federal agencies.
15.F.
Page |11
Warren Road Improvements
City of Hemet
SECTION II | PERSONNEL
Justin Schlaefli, P.E., T.E.,
P.T.O.E.
Traffic Engineer
Justin has 25 years of experience
in the transportation field. He is
responsible for managing
projects on a day-to-day basis as
well as interfacing with other
project team members and decision makers/
government staff and Contractors. He specializes in
Transportation Projects, Intelligent Transportation
Systems, Transportation Planning, Construction, Traffic Engineering and Traffic Operations. He has experience
working on both public sector projects as well as private sector design. His experience ranges from design,
construction management and inspection to operations
and maintenance. He also has experience conducting
traffic studies, specialized access analysis, parking
studies, trip generation studies, traffic micro-simulation, signal operations, signal timing, traffic control and
design/build of ITS solutions. In addition, Justin has
served as a subject matter expert in court, for the State of California and for vendors in the transportation
industry. He is also a proud alumnus of San Diego State University where he has guest lecturer and has taught
Transportation Engineering, helping to mentor the next
generation in his field.
Monae Pugh
Traffic Engineering Specialist
Ms. Pugh has over 37 years of
Municipal and Public Agency
engineering experience with a
wide range of responsibilities
and projects emphasizing the
discipline of Transportation and
Traffic Engineering and has been with TKE for 10 years.
Prior to joining TKE, she worked at the City of Fontana managing both its Land Development and Traffic
Engineering Departments. Other prior experience
includes over 17 years in the County of Riverside Traffic Engineering Department. Ms. Pugh currently services
the cities of Calimesa and Corona as a traffic engineering specialist. Ms. Pugh will be responsible for providing
technical assistance to the traffic committee, study
reviews and the design review of all traffic signal
services.
Ron Musser, P.L.S.
Director of Survey/Right-ofWay Engineering
Professional Land Surveyor, LS
4230 (CA)
Mr. Musser has 50+ years of
experience in performing field
and office surveying and plan
checking services for public and
private projects including roadway and highway projects.
He has performed design topographic surveying and
construction staking on all of TKE’s respective design and construction management projects and map checking
over the past 15 years. In addition, he has prepared
records of survey, parcel maps and tract maps in Orange County, Los Angeles County, San Bernardino County,
Riverside County, and San Diego County. He has
performed boundary, topographic, ALTA, and precise
level surveys as well as Global Positioning Surveys. Mr.
Musser has prepared legals and plats for more than 500
parcels on street widening projects.
Chance Renner
Permitting/Utility Coordinator
California E.I.T.
Mr. Renner has over 7 years of
experience working for TKE
Engineering. He has experience in
civil engineering design and
construction of infrastructure projects, including sewer and water improvements, drainage improvements,
transportation improvements, facilities improvements,
and construction methods. Mr. Renner has been
responsible for assistance with design of water and
sewer plan/profile, lift stations, treatment plant
facilities, preliminary design exhibits, and cost estimates.
He has delivered projects for Mission Springs Water
District and the Cities of Glendora, Adelanto, Chino,
Fontana, Hesperia, Highland, Needles, and Rialto.
15.F.
Page |12
Warren Road Improvements
City of Hemet
SECTION II | PERSONNEL
Traffic Engineer
Justin Schlaefli, P.E., T.E.,
P.T.O.E.
Permitting/Utility
Coordinator
Chance Renner
Principal In Charge
Terry Renner, P.E.,
Q.S.D.
Project Engineer
Steven Ledbetter,
P.E., Q.S.D.
Director of Survey/Right of
Way Engineering
Ron Musser
P.L.S.
Project Manager
Octavio Parada
Traffic Engineering
Specialist
Monae Pugh
B . ORGANIZATIONAL CHART
SUPPORT TEAM
( 6 0+ Members)
15.F.
Page |13
Warren Road Improvements
City of Hemet
SECTION III | PROJECT SCOPE
SECTION III | PROJECT SCOPE
A. PRO JECT
UNDERSTANDING
The City of Hemet (City) desires to retain professional engineering design services for construction of the
widening of Warren Road from Esplanade Avenue to
Domenigoni. The project will consist of widening the
existing 2-lane road to a 4-lane corridor with curb, gutter and sidewalk through two different segments and
widening of the Salt Creek Bridge. The project will also install traffic signals, street lighting, sidewalk, ADA ramps and potential retaining wall or slope grading along the McCall Boulevard.
Services include but are not limited to:
Δ Project management
Δ Preliminary and final Engineering including
preparation of plans
Δ Plans, Specifications and Estimates (PS&E)
Δ CEQA Environmental Assistance
Δ Utility coordination
Δ Coordination with other jurisdictional agencies
Δ ROW acquisition
Δ Community outreach
Δ Bidding and Construction Support
TKE has a long history of delivering street widening
improvement projects for numerous of the surrounding
communities in which we live and work on a daily basis.
From our first project in 2000 to our latest project of this type, TKE has always understood the importance of
these projects to the local community. TKE commits to
staying on time and budget through creative engineering techniques and a collaborative effort between the public agencies and the community. Our team has
demonstrated the ability to build project coalitions time and time again.
Finally, it doesn’t matter how much community support
that’s developed if the project isn’t delivered! We
understand how important time and budget are to this
project. Since the City has desires to enhance public
improvements, it is important to have a proactive
approach to project completion. This way, alternative
design methods can be explored and implemented to
keep the project within budget and on schedule.
B. PROJECT APPROACH
Successful project delivery is our goal. Our definition of successful project delivery is:
Δ Project completion that meets all project
requirements
Δ Project completion within budget
Δ Project completion on schedule
Our goal is not limited to the design of the project only, but includes the incorporation of value engineering and constructability review. Through the examination of
specific design alternatives, we will identify the most cost-effective project alternative that meets design
requirements and will provide for the greatest
opportunity for expedited construction, which allows us to consistently deliver projects that use public resources in a very wise and responsible manner. We have
developed this project approach in order to maintain an expertise in our core business of projects with tight
budgetary constraints.
With street widening projects, our experience tells us
that there must be a proactive approach to completing
the work in order to meet scheduling and community
requirements. This approach includes early
identification of critical design elements, familiarity with permitting requirements, early community coordination
for acquisition and relocation coordination and accurate cost estimating throughout the entire process. In
preparing this proposal, our team spent numerous hours
reviewing the project site, existing infrastructure, City goals and project constraints to establish key issues so we can be prepared to mobilize on a moment’s notice to
assist you.
C. CRITICAL ISSUES
TKE’s understanding of the project requirements is the
key to successfully overcoming project challenges within the proposed project schedule. TKE has worked with
similar street and bridge widening project for the past 25 years. Our experience allows TKE to develop a much
greater project understanding and will allow TKE to
begin work on critical issues immediately after the
project is awarded.
R IGHT - OF - W AY
Based on our review of the proposed alignment, the
project will require approximately 9 right-of-way
acquisitions of permanent right-of-way
dedication. Additional temporary construction
15.F.
Page |14
Warren Road Improvements
City of Hemet
SECTION III | PROJECT SCOPE
easements or rights-of-entry may be required for parcels where significant grading will be required to allow for improvement transitions.
Once the base mapping is prepared for the entire reach
of the project limits, TKE will immediately begin work on identifying right-of-way requirements and begin
communications with each property owner to identify if
private improvements will be part of the
negotiations. Right-of-way is usually a critical path item and this will provide an extensive head start and shorten overall project delivery time.
S TREET , D RIVEWAY AND P ROPERTY
T RANSITIONS
For street widening projects, transitions to existing
improvements are typically the most challenging
component of design. Street transitions will require
that improvements be constructed at ultimate locations
with interim design being implemented. Therefore, the
improvements must be constructed so that no
reconstruction of permanent improvements will be
required and interim transitions are safe and functional.
Many of the adjacent properties have significant vertical elevation differences and will require significant grading to accommodate proper transitions to the proposed
improvements. Using the topographic mapping, TKE will
prepare multiple vertical alignment designs that will
analyze environmental impacts, impacts to adjacent
properties and developments, impacts to adjacent
streets, conveyance of offsite drainage, street drainage, earthwork, utility relocations, slope and temporary
construction easements, traffic impacts, constructability reviews along the proposed Warren Road
alignment. The analysis will include a report identifying potential impacts, mitigation requirements and
quantities as appropriate for each item listed above and will include preliminary profiling for each alternative.
For driveways, grades will require special
attention. Street widening normally lowers flow lines
grades to ensure desired street cross-sections can be
developed. In addition, the widening reduces the
transition lengths. The combination of the two may
create excessive grades if not appropriately
designed. To ensure such does not occur, TKE will review survey data well into the properties and recommend
construction of improvements beyond street right-ofway, to minimize street widening impacts on private driveway grades.
For private improvements, private improvements such
as fences, walls, and landscaping will be impacted by
street widening. TKE will identify such impacts early
during project design and will develop an action plan for working with properties that may be impacted.
D RAINAGE
Design of drainage systems must be developed early
during design to identify locations of structures. In
particular, catch basins must be identified to eliminate potential conflicts. In addition, hydrology and hydraulic calculations must be performed early to adequately size the required drainage structures in accordance with the City’s master plan.
U TILITY C OORDINATION
Based on field review, various utilities will require
relocation. These facilities include power poles, risers and utility vaults. We will identify these facilities early in project design to begin coordination at the earliest opportunity. TKE has extensive experience coordinating
with SCE for the relocation and undergrounding of
existing power poles. Agencies that maintain private
utilities can be cumbersome and early coordination will prevent project delays.
P AVEMENT R EHABILITATION
Review of the pavement conditions on McCall Boulevard
indicate that pavement conditions vary from fair to
complete structural failure. TKE will review the
pavement conditions and offer alternatives which have
varying life expectancies, upon the City’s
request. Included with the Geotechnical services
presented in the scope of services is pavement
design. Samples will be taken in the street subgrade for laboratory testing to determine the correct section for street design.
A CCURATE C OST E STIMATING
Because of the limited budget, it is vital to keep costs controlled. Our approach to controlling costs is to
provide frequent and accurate cost estimates by using
TKE’s detailed cost estimating database. In addition to using this database, TKE utilizes our considerable
experience with Construction Management to assist in
providing constructability reviews and cost estimating
based on current information from our on-going
projects. Finally, with the current economic climate,
construction costs are widely varying. We will also
15.F.
Page |15
Warren Road Improvements
City of Hemet
SECTION III | PROJECT SCOPE
discuss the project’s elements with local contractors to assure that we have the most current construction
information available so that the City can get the most “bang for their buck”.
DETAILED WORK PLAN
T ASK N O . 1 P ROJECT M ANAGEMENT
TKE’s Project Manager will be responsible for the entire project team. He will attend all meetings, prepare
agendas and corresponding meeting minutes together
with collection of signatures for meeting attendees
(sign-in sheets). He will meet with the City at
appropriate times and will meet as needed with
agencies, residents, property owners, and utilities in
addition to the meetings presented below. He will also
update the project budget and schedule prior to each
City meeting for discussion with staff.
T ASK N O . 2 I NITIAL ‘ K ICK - O FF ’
M EETING
Prior to commencement of services, we propose to
meet City staff to review project obligations and to
discuss all project requirements in detail. TKE’s Project Manager and \Engineer will attend the meeting to
determine project protocol and obtain City record
drawings.
T ASK N O . 3 R ECORDS R ESEARC H
We will thoroughly research existing utility records and acquire copies of all available records. The purpose of the records research is to assemble survey records to
establish locations of street centerlines, street rightsof-way, and easements and determine locations of all existing utilities and improvements. The research will
consist of assembling copies of assessors’ maps, tract
maps, parcel maps, easement documents, monument
ties, benchmark data, corner records, street and storm
drain improvement plans, and utility drawings. We will
request the City provide copies of available pertinent
City records, such as survey ties, benchmarks, and
street, sewer and storm drain improvement plans.
We will notify Underground Service Alert to acquire a
complete list of underground utility purveyors. The
utility drawings will include existing drawings from the City, and drawings and/or atlas maps from all private
utility companies, and/or agencies. We will confer and
coordinate with the following agencies as well as any
additional agencies listed in the Underground Service
Alert:
Δ Metropolitan Water District
Δ Caltrans
Δ City of Hemet Water Department
Δ Frontier
Δ AT&T
Δ Sprint
Δ Southern California Gas Co.
Δ Southern California Edison
Δ Spectrum
We will send first utility notice letters to all listed utility companies and agencies requesting their data. We will
maintain copies of the letters and correspondence for
future reference. We shall also provide the City with a complete copy of all correspondence with all utility
companies.
T ASK N O . 4 D ESIGN S URVEY
TKE will conduct a conventional design survey of the
sidewalk and ramp construction project areas due to
the level of detail needed for precise grading design.
Our field survey crews will collect appropriate detail as required to prepare a topographic map for all areas
where grading improvements are required. The
topographic map shall be a minimum of 120-feet wide
and shall extend 100-feet beyond end of centerline. In
addition, we will collect 50-foot cross sections with
shots extending to right-of-way and 10-feet beyond
right-of-way on each side where possible. Survey data
will include trees over 2-inches in diameter, buildings, walkways, sidewalks, driveways, curbs, gutters, cross
gutters, fire hydrants, water valves, manholes, water
meters, signs, street lights, power poles, fences,
structure, traffic signal poles and all other visible
features.
Our crews will set 100-foot stationing along street
centerlines and collect existing topography as needed
to provide sufficient level of detail for precise design.
The crew will also measure invert, top of cone and rim
15.F.
Page |16
Warren Road Improvements
City of Hemet
SECTION III | PROJECT SCOPE
elevations for all existing manholes in the project area and invert and rim elevations for all drainage facilities.
The crew will set temporary benchmarks within the
project limits and each will be shown on the drawings.
T ASK N O . 5 T OPOGRAPHIC
M A P /S URVEY C ONTROL P LAN
We will prepare a topographic map for the entire reach
of sidewalk replacement and ramp construction areas.
The topographic map shall be prepared in AutoCAD
format at 1”=40’ scale and shall include 1 foot
contours. For areas of striping improvements only a
topographic survey will not be performed
A survey control plan shall be prepared and shall show
all existing found monumentation, benchmarks, ties
and temporary control points. All found
monumentation will include descriptions and tie-out
information.
The survey control plan will be provided to the City in hard copy (mylar) and digital (AutoCAD and PDF)
formats.
T ASK N O . 6 B ASE C ONSTRUCTION
D RAWINGS
We will prepare the base construction drawings on 24”
by 36” sheets with the City’s standard title block using AutoCAD 2020 software, at a drawing scale of 1”=40’.
The base construction drawings will include a plan view based on the accumulated conventional survey data. We
will add the sheet north arrow, graphic scale, existing improvements and utilities (based on both assembled
records and field data), property lines, public and private right-of-way, easement areas, assessor parcel numbers,
street centerline, street names, building locations, water service location; sewer manhole lids and water valve lids; cross gutters; driveways, pedestrian ramps; traffic
stripes and legends; curb returns; details of private
improvements, fences, gates, irrigation systems,
mailboxes, trees and landscaping, and survey data to the drawings. Once the base drawings are complete, we will
perform a careful field review to ensure all underground facilities are shown correctly.
T ASK N O . 7 C OMPOSITE U TILITY
P LAN
TKE will prepare a composite utility plan which
identifies all existing utilities within the proposed rightof-way and all utilities affected by the proposed street and traffic signal improvements and requiring
relocation. The plan shall show all above and below
ground utilities including all laterals. The utility plan will be for City use in coordinating with utility
companies.
For all facilities to be potholed, we propose to verify the horizontal and vertical alignments by locating the
facilities. We will request that Underground Service
Alert (USA) notify USA members to attend a field
meeting to review locations to be excavated. We will
mark critical utility locations as defined by TKE and
approved by City staff in the field.
We will conduct a field meeting to request that utility representatives mark their facilities within specified
locations. We will document meeting attendees for
future reference. We will retain C Below to excavate
each utility. We will measure all utilities that are
excavated to record their horizontal and vertical
alignments.
T ASK N O . 8 G EOTECHNICAL
We would propose to retain Aragon Geotechnical Inc.
(AGI) as a sub consultant to provide Geotechnical
services for the project. AGI will first review historical geotechnical reports. Scope of services includes,
mobilization with truck mounted drilling equipment,
boring locations/elevations, utility locates, traffic control during drilling, drill and sample borings, Shelby Tube
samples or blow counts in all borings at 5-foot intervals, laboratory testing, engineering analysis, and electronic boring logs.
Prior to the field investigation, AGI will prepare a plan showing the proposed boring locations. The plan will be submitted to the CITY for obtaining an encroachment
permit to perform the borings. Traffic control may be
necessary when drilling. AGI will follow the CITY traffic control guidelines if required. They will also perform the following:
Δ Drilling, sampling and logging of necessary
borings along roadway and below proposed
culvert. AGI will notify Underground Service
15.F.
Page |17
Warren Road Improvements
City of Hemet
SECTION III | PROJECT SCOPE
Alert. Borings include, the asphalt pavement
thickness and base thickness will be noted
during the boring operations.
Δ Design of street structural section using City
provided traffic indices.
Δ Laboratory testing of representative soil
samples to evaluate in-situ moisture content,
density tests, infiltration rates, max density and
optimum tests, sieve analysis, R-value, direct
shear tests, consolidation and collapse tests and
corrosivity characteristics of the on-site soils.
Δ Data compilation and geotechnical analysis of
existing geotechnical maps, reports, and field
and laboratory data to provide
recommendations for pavement design.
Analysis will include recommendations for new
pavement section alternatives, based on the
traffic indices and R-value testing.
Preparation of a report presenting findings, conclusions and recommendations pertaining to design, compaction
requirements, subgrade preparation, and
earthwork/embankment recommendations. In addition,
the report will provide recommendations for asphalt
pavement recycling and other recommendations, which
would include cost saving treatment methods.
The report will also include
Δ Settlement and slope stability analysis for
roadway fill areas and culverts and (updates
there to)
Δ Suitability of existing soils to be excavated for
reuse as embankment fill
T ASK N O . 9 P RELIMINARY
E NGINEERING
Using the topographic mapping, TKE will prepare
preliminary design concepts for geometric alignment
that will analyze impacts to adjacent properties and
developments, impacts to adjacent streets,
conveyance of offsite drainage, street drainage,
earthwork, utility relocations, slope and temporary
construction easements, traffic impacts,
constructability reviews and future street
improvements. Preliminary geometric design will be
performed to establish ultimate improvements to
minimize removals of improvements constructed with
future projects. The analysis will include an exhibit
identifying potential impacts, mitigation requirements
and quantities as appropriate for each item listed
above and will include preliminary engineer’s
estimate. TKE will attend two meetings for review and
approval of the geometric alignment design.
In addition, TKE will prepare hydrology and hydraulic
analysis of the project area to determine culvert
and/or low water crossing flowrates and size
requirements.
TKE will prepare preliminary alignments for all curb,
gutter, sidewalk and striping improvements and
present the alternatives to the City in a Geometric
Alignment Design (GAD). The GAD will be reviewed
with City Staff to determine the desired alignments for all improvements and a final approved design will be
accepted during this process.
T ASK N O . 10 R IGHT - OF - W A Y
After 30% design is complete, we will prepare and
maintain a right-of-way acquisition map and will update it as right-of-way progresses. The map will show all
required rights-of-way for project construction. The map will be prepared on a 24” by 36” sheet with City Standard title block at an appropriate drawing scale. All parcels will be identified with Assessor Parcel Number, width of required right-of-way acquisition and total acquisition area.
TKE will prepare all necessary final right-of-way
documents for the project including permanent and
temporary construction right-of-way deeds and
easements. We will prepare legal descriptions and plats for each parcel requiring acquisition and, working with the City, we will attend two negotiation meetings with
each property owner to negotiate the acquisition. If after two meetings a negotiated position has not been
reached, the City will need to provide additional
direction. TKE anticipates right-of-way document
preparation for all four corner properties at the
proposed roundabout intersections, approximately 40
parcels. Right-of-way documents would be prepared in
accordance with the City requirements.
T ASK N O . 1 1 60% D ESI G N
15.F.
Page |18
Warren Road Improvements
City of Hemet
SECTION III | PROJECT SCOPE
60% Design will include preparation geometric roadway
improvement exhibits, preliminary construction
drawings, preliminary technical specifications,
preliminary construction estimates, and completed
geotechnical report.
Construction drawings will show proposed street
geometrics including locations of proposed asphalt
concrete pavement, curb and gutters, sidewalk, ramps,
drive approaches, and bike lanes. In addition,
preliminary street and sidewalk grades will be prepared to establish project grading requirements. Proposed
improvements will be designed in accordance with the
City’s current street design standards and specifications.
The proposed improvements will be designed to
minimize removals, grading and earthwork.
For the drawings, we will prepare a title sheet (1),
construction notes sheet (2), demolition sheets (14),
plan/profile sheets (27), drainage sheets (10), bridge
widening sheets (traffic signal sheets (6), signing and striping sheets (14), street light sheets (14), and
necessary detail sheets.
The title sheet shall include the title of the job, a vicinity map showing the City in relationship to surrounding
communities, a location map showing the project limits, a list of abbreviations used, benchmark data, general
notes, construction notes and quantities, an index for
the drawings, list of utilities with phone numbers, and references on the City’s standard title block.
The construction note sheet will show general
construction notes and project specific requirements.
The demolition sheet will show existing improvement
demolition including limits of pavement removal, saw
cutting locations and limits and concrete cross gutters and curbs, if required. In addition, the plan will specify relocation of private improvements such as mailboxes
fences, drive approaches, etc. as required.
Plan/profile sheets will show proposed improvements at
1”=40’ scale including curb and gutter, sidewalk, ramps, driveways, pavement limits, existing utility relocations, water service relocations, and manhole, valve, and vault cover grade adjustments. For the profile portion of the drawings, we will show existing and proposed pavement
elevations at centerline top of curb and centerline with appropriate design data. The construction details will
include connections and abandonment details, all at
appropriate drawing scales.
Bridge design will include review of the existing bridge as-built plans to determine feasible methods for
widening the existing bridge. Bridge plans will include structural calculations and plan preparation to identify all required structural steel and reinforced concrete
members to widen the existing bridge abutments, piers
and decking for the proposed 4 lane roadway.
The drainage sheets will be prepared in accordance with City standards and requirements. The sheet will be
prepared at a 1”=20’ scale and will show existing rightof-way, curb, gutter, sidewalk, existing utilities, existing right-of-way, curb, gutter, sidewalk, existing utilities, existing drainage improvements and all proposed
improvements including catch basins, pipe and
connections. Storm drain sheets will show top of pipe,
flowline, structures utility crossings and ground surface.
The street cross-sections sheets will show street sections at appropriate drawing scales. The sections will be
dimensioned and construction and demolition notes will
be shown. In addition, rights-of-way and limits of work will be shown.
Street lighting sheets will be prepared in accordance
with City standards and requirements. The sheets will be prepared at a 1”=40’ scale and will show existing rightof-way, curb, gutter, sidewalk, existing utilities, existing right-of-way, curb, gutter, sidewalk, existing utilities, existing and proposed street light improvements and all proposed modifications including conduit extension and
head replacements.
The electrical sheets will include design for decorative lighting at each roundabout intersection, including
splitter islands to accommodate pedestrian warning
lighting. The sheets will be prepared at a 1”=20’ scale and will show existing right-of-way, curb, gutter, sidewalk, existing utilities, existing right-of-way, curb, gutter, sidewalk, existing utilities, existing and proposed
electrical improvements and connections.
Traffic signal sheet will be prepared in accordance with City traffic standards and requirements. The sheets will be prepared at a 1”=20’ scale and will show existing
right-of-way, curb, gutter, sidewalk, existing utilities, existing traffic signal improvements and all proposed
installation including poles, loop or video placement and conduit placement.
The signing and striping sheets will include all required pavement markings, lane stripes and signage in
15.F.
Page |19
Warren Road Improvements
City of Hemet
SECTION III | PROJECT SCOPE
accordance with the MUTCD, California supplement and
all other applicable City requirements, for the project limits. The sheets will be prepared at 1”=40’ scale and include full geometrical layouts at each intersection.
Landscape and irrigation sheets will include design for the landscaping within the proposed raised median. The
sheets will include the point of connection, irrigation layout and planting materials to be installed and shall be in conformance with city standards, specifications,
ordinances, regulations and requirements.
For the specifications, we will amend the City Standards Technical Provisions as required for the projects. The
construction specifications will be prepared in Microsoft Word (2020 Version) format in accordance with City
standards.
In addition, we will prepare quantity estimates for all proposed improvements prepared using an excel
spreadsheet showing an itemized construction cost
breakdown. Descriptions of work, unit prices, and
quantities will be included in the spreadsheet.
T ASK N O . 1 2 C OORDINATION W ITH
A GENCIES /U TILITIES
After 60% design is complete, plans will be sent to
agencies having facilities in the project areas requesting that they verify their facilities are shown correctly and that they furnish any construction requirements they
desire. We will highlight each agency’s facilities and
advise each of potential conflicts and relocation
requirements. We will request that they respond within
two weeks and we will follow up with telephone calls to confirm all agency requirements have been
incorporated. We will document all conferences with
utilities and agencies and copy the City via e-mail.
T ASK N O . 1 3 P ERMITTING
TKE will prepare permit applications with the following agencies as required for approval of the project design and construction.
Δ Metropolitan Water District
Δ Caltrans Encroachment Permit
Δ County of Riverside Encroachment Permit
Δ Riverside County Flood Control
Δ AT&SF Encroachment Permit
TKE will coordinate with all agencies to address any
comments or concerns and track the permit process
throughout approval.
T ASK N O . 1 4 D ESIGN R EVIEW
M EETINGS
After the City has completed its review, we will meet
with City staff to acquire Staff’s comments.
T ASK N O . 1 5 90% D ESIGN
After the City has completed its review, we will meet
with City staff to acquire Staff’s comments.
T ASK N O . 1 6 90% D ESIGN R EVIEW
M EETINGS
After the City has completed its review, we will meet
with City staff to acquire Staff’s comments.
T ASK N O . 1 7 100% D ES IGN
100% design will include incorporation of City
comments, final plans, specifications, and estimates,
ready for public bidding. Final documents will include
mylars and hard copy specifications with signatures and electronic copies of final documents.
100% Design will be submitted with a project summary
memorandum together with an updated project
schedule, additional stakeholder meeting summary, and
internal plan review documentation.
T ASK N O . 1 8 F INAL C OORDINATION
W ITH A GENCIES /U TILITIES
After the final drawings are approved by the City, we
will again submit them to all agencies/utilities having underground facilities in the project area requesting
that they verify their facilities are shown correctly and we will advise them of the project construction
schedule and relocation requirements. In addition, we
will coordinate final relocation construction prior to
project bidding. We will document all meetings and
conferences with utilities and agencies.
15.F.
Page |20
Warren Road Improvements
City of Hemet
SECTION III | PROJECT SCOPE
T ASK N O . 1 9 C ONSTRUCTION S UPPORT
P HASE
After the final drawings are approved by the City, we will again submit them to all agencies/utilities having
underground facilities in the project area requesting
that they verify their facilities are shown correctly and we will advise them of the project construction schedule and relocation requirements. In addition, we will
coordinate final relocation construction prior to project bidding. We will document all meetings and conferences
with utilities and agencies.
15.F.
Page
|21
Warren Road Improvements
City of Hemet
SECTION IV|FEE SCHEDULE
SECTION IV| FEE SCHEDULE
15.F.
Subconsultants Total
Task No. Task Hours $ Hours $ Hours $ Hours $ Hours $ Hours $ Hours $ Hours $ $ $
1. Project Management 20 $ 3,700 160 $ 28,000 40 $ 7,400 40 $ 6,600 $ - 8 $ 1,400 40 $ 3,600 $ - $ 50,700
2. Initial "Kick Off" Meeting 2 $ 370 4 $ 700 4 $ 740 4 $ 660 $ - $ - 2 $ 180 $ - $ 2,650
3. Records Research $ - $ - 16 $ 2,960 $ - 16 $ 2,320 $ - 32 $ 2,880 $ - $ 8,160
4. Design Survey $ - 2 $ 350 2 $ 370 $ - $ - $ - $ - 260 $ 67,600 $ 68,320
5. Topographic Map/Survey Control Plan $ - $ - 4 $ 740 8 $ 1,320 16 $ 2,320 8 $ 1,400 $ - $ - $ 5,780
6. Base Construction Drawings $ - 8 $ 1,400 8 $ 1,480 120 $ 19,800 240 $ 34,800 40 $ 7,000 $ - $ - $ 64,480
7. Composite Utility Plan 2.) $ - $ - 4 $ 740 16 $ 2,640 40 $ 5,800 $ - $ - 24 $ 6,240 $ 55,000 $ 70,420
8. Geotechnical Investigation 8 $ 1,480 16 $ 2,800 $ - 16 $ 2,640 24 $ 3,480 $ - $ - $ - $ 106,700 $ 117,100
9. Preliminary Engineering 16 $ 2,960 80 $ 14,000 40 $ 7,400 120 $ 19,800 240 $ 34,800 16 $ 2,800 40 $ 3,600 $ - $ 110,000 $ 195,360
10. Right-of-Way 24 $ 4,440 64 $ 11,200 $ - $ - 300 $ 43,500 200 $ 35,000 40 $ 3,600 $ - $ 97,740
11. 60% Design 24 $ 4,440 80 $ 14,000 64 $ 11,840 200 $ 33,000 400 $ 58,000 40 $ 7,000 80 $ 7,200 $ - $ 368,280 $ 503,760
12. Coordination with Agencies/Utilities/Permitting $ - 16 $ 2,800 24 $ 4,440 24 $ 3,960 24 $ 3,480 24 $ 4,200 8 $ 720 $ - $ 19,600
13. Permitting $ - 24 $ 4,200 $ - 80 $ 13,200 160 $ 23,200 $ - 80 $ 7,200 $ - $ 47,800
14. 60% Design Review Meeting $ - 4 $ 700 4 $ 740 4 $ 660 $ - $ - 2 $ 180 $ - $ 2,280
15. 90% Design 16 $ 2,960 64 $ 11,200 40 $ 7,400 150 $ 24,750 300 $ 43,500 150 $ 26,250 64 $ 5,760 $ - $ 184,140 $ 305,960
16. 90% Design Review Meeting $ - 4 $ 700 4 $ 740 4 $ 660 $ - $ - 2 $ 180 $ - $ 2,280
17. 100% Design 8 $ 1,480 32 $ 5,600 24 $ 4,440 80 $ 13,200 150 $ 21,750 80 $ 14,000 32 $ 2,880 $ - $ 61,380 $ 124,730
18. Final Coordination with Agencies/Utilities $ - 16 $ 2,800 24 $ 4,440 24 $ 3,960 24 $ 3,480 24 $ 4,200 8 $ 720 $ - $ 19,600
19. Construction Support $ - 40 $ 7,000 24 $ 4,440 80 $ 13,200 80 $ 11,600 16 $ 2,800 40 $ 3,600 $ - $ 42,640 Subtotal: 118 $ 21,830 614 $ 107,450 326 $ 60,310 970 $ 160,050 2,014 $ 292,030 606 $ 106,050 470 $ 42,300 284 $ 73,840 $ 1,749,360 Reimbursables (@5%)1.): $ 87,468
Total: $ 1,836,828
Notes: Rounded Total: $ 1,836,800
Rates: 1.) Reimbursables Include Cost for Prints, Copies, Mileage, Etc.
Principal in Charge $ 185 /HR 2.) Subconsultant Fee for C Below for 20 Potholes Project Manager $ 175 /HR 3.) Subconsultant Fee for Aragon Geotechnical Traffic Engineer $ 185 /HR 4.) Subconsultant Fee for CWDG for Landscape and Irrigation Project Engineer $ 165 /HR 5.) Subconsultant Fee for Brady for Structural Assistant Engineer/Designer $ 145 /HR
Senior Survey $ 175 /HR
Clerical $ 90 /HR
2-Man Survey Crew $ 260 /HR TKE Engineering, Inc.
Principal in
Charge
City of Hemet
Professional Engineering Services for Warren Road Improvements Fee Schedule Breakdown
Project Manager Traffic Engineer
Assistant
Design Engineer Engineer/Designer Senior Surveyor Clerical Survey Crew
15.F.
Prepared for:
City of Hemet
Proposal to Provide Professional Engineering Services for
WARREN ROAD
IMPROVEMENTS
January 30, 2025
webbassociates.com
15.F.
Candace Sunds
City of Hemet
Community Development Department
445 East Florida Ave.
Hemet, CA 92543
RE: Request for Proposal for Professional Engineering Services for Warren Road Improvements Dear Ms. Sunds,
Warren Road serves as a critical north-south connector in Hemet. However, narrow shoulders, substandard curves, and limited pedestrian and bicycle access create mobility and safety challenges. Through thoughtful planning and phased implementation, the City can transform Warren Road into a modern, efficient arterial that enhances regional connectivity.
Albert A. Webb Associates (WEBB) is prepared to support this effort with technical expertise, deep regional knowledge, and a proactive approach to project delivery.
Delivering a Strategic, Phased Approach
The City’s vision for Warren Road includes a four-lane arterial from Esplanade Avenue to Domenigoni Parkway, constructed in three phases:
• Phase 1: Esplanade Avenue to Stetson Avenue
• Phase 2: Stetson Avenue to Salt Creek Bridge
• Phase 3: Salt Creek Bridge Widening
Successfully delivering this project requires careful phasing, strategic funding alignment, and proactive coordination.
WEBB’s approach is rooted in detailed planning, risk mitigation, and streamlined execution:
• Project Scope & Alignment: Our team will develop a phased design that integrates key infrastructure components while aligning with available funding.
• Budget & Schedule Control: We will implement cost-effective strategies to keep the project on schedule and within budget while addressing potential funding constraints. • Quality Assurance & Milestone-Based Reviews: A rigorous quality control process at major milestones— Preliminary Design, 60%, 90%, and Final Bid Documents—ensures accuracy, compliance, and constructability. • Clear Communication & Stakeholder Coordination: Transparent, proactive communication with the City, utility agencies, and environmental consultants will ensure timely decisions and seamless project integration. • Risk Management & Problem-Solving: Identifying risks early—right-of-way constraints, utility conflicts, drainage issues, and phasing complexities—allows us to develop targeted mitigation strategies and ensure smooth execution.
COVER LETTER
3788 McCray Street, Riverside, CA 92506 | P:951.686.1070 | F:951.788.1256 | www.webbassociates.com
15.F.
Expert Team, Seamless Execution
WEBB has assembled a highly skilled team to manage the complexities of this project:
• Dilesh Sheth, PE, TE – Project Manager, leading roadway and traffic engineering efforts. • Eric Hays – Back-Up Project Manager, ensuring seamless project execution.
Our multidisciplinary team includes roadway engineering, drainage, traffic, right-of-way, geotechnical, and utility coordination specialists. Key team members include:
• Joseph Caldwell (WEBB) & Joe Castaneda (JLC Engineering & Consulting) – Drainage specialists providing hydrology and stormwater management solutions.
• Mark Thomas & Co. – Transportation engineering experts supporting bridge widening and roadway design.
Key Project Considerations & Solutions
With our experience in arterial roadway and bridge widening projects, we are prepared to address key challenges:
• Phasing Determination: Conducting a Preliminary Assessment and Phasing Analysis to align construction with funding and feasibility.
• Preferred Roadway Alignment: Evaluating right-of-way, utility relocation, and environmental factors to select the most efficient, cost-effective alignment.
• Drainage Improvements: Developing a comprehensive stormwater management strategy in coordination with adjacent developments.
• Salt Creek Bridge Widening: Providing low-impact, cost-effective design alternatives that ensure structural integrity and environmental compliance.
• Utility Relocation: Coordinating extensively with utility providers to minimize conflicts, streamline relocation, and prevent costly delays.
A Trusted Partner for the City of Hemet
WEBB has successfully delivered high-profile roadway improvement projects across Riverside County, ensuring costeffective solutions, regulatory compliance, and long-term infrastructure resilience. With deep regional expertise and a commitment to quality, we are ready to support the City of Hemet in transforming Warren Road into a safer, more efficient corridor.
We appreciate your consideration and look forward to the opportunity to collaborate. Please get in touch with me at 951.830.4305 or [email protected] if you have any questions.
Sincerely,
Dilesh Sheth, PE, TE
Senior Vice President
[email protected] | 951.830.4305
3788 McCray Street, Riverside, CA 92506 | P:951.686.1070 | F:951.788.1256 | www.webbassociates.com
15.F.
TABLE OF CONTENTS
PROPOSAL TO PROVIDE PROFESSIONAL ENGINEERING SERVICES FOR
WARREN ROAD IMPROVEMENTS
SECTION I. Experience.........................................................................................................1 SECTION II. Personnel................................................................9 SECTION III. Project Scope ....................................................42
15.F.
SECTION
I.
1 EXPERIENCE
15.F.
2 City of Hemet
Warren Road Improvements
Albert A. Webb Associates (WEBB), established in 1945, has provided consistent multidisciplinary consulting services including planning and environmental services across California’s public sector. Our experience managing projects utilizing TUMF and DIF funding ensures smooth compliance with financing requirements. This allows us to strategically align design solutions for cost-effective project delivery. Our long-standing financial stability reflects our ability to navigate economic challenges, ensuring reliable support throughout project lifecycles.
As a mid-sized consulting firm with offices in Riverside and Murrieta, we are well-positioned to serve a diverse range of clients. WEBB offers comprehensive in-house services, working with public and private sector clients across Inland Southern California. We cater to cities, counties, water districts, and regional agencies, covering every stage of a project - from development and planning to design, permitting, construction management, and inspection.
With decades of experience, financial strength, and strategically located offices, WEBB is the go-to choice for public sector entities in California seeking cost-conscious, phased infrastructure solutions. We are dedicated to delivering excellence and fostering successful client partnerships. Dilesh Sheth, PE, TE, is WEBB’s authorized representative for this project.
For detailed information on our services, simply click
on the corresponding icons for more insights or visit
webbassociates.com/services.
Construction
Management &
Inspection
Land Development
Planning &
Entitlement
Environmental
Services
Land Survey &
Mapping
Services
Land Development
Engineering
Traffic &
Transportation
Water
Resources
Landscape
Architecture
1945
Founding Year Number of Employees
180
Licensed Professionals
40+
Firm Specifics
Corporate Headquarters
3788 McCray Street
Riverside, CA 92506
951.686.1070
Murrieta
41870 Kalmia Street #160
Murrieta, CA 92562
951.686.1070
Our Services
WEBB OVERVIEW
15.F.
3 City of Hemet
Warren Road Improvements
IDI Logistics retained WEBB to improve approximately four miles of roadway and drainage improvements, including
a bridge widening, three railroad crossings, interchange improvements, traffic signal, bicycle lanes, and trail
improvements with a construction cost of over $50 million.
The PLC North project was conditioned to construct
part of the infrastructure prior to the occupancy permit in November 2023. WEBB was able to prepare plans,
provide bidding support, and construction management
to complete improvements before the occupancy permit.
WEBB provided the following scope of services:
1. Environmental Documents
2. Regulatory Compliance
3. Drainage Study/WQMP
4. Civil Engineering for Storm Drain, Street
Improvement Plans, and Bridge Widening
5. Conceptual and Final Landscape and Irrigation Plans
6. Utility Coordination
7. Prepare of Legal and Plats
8. Survey
9. Potholing
10. ROW Service
11. Waterline Reconstruction
12. Signing & Striping Plans
13. Street Light Plans
14. Traffic Signal Plans
15. Railroad Crossing
16. Interchange Improvements – Caltrans Encroachment
Permit
17. Construction Management and Inspection
18. TUMF and DIF reimbursements
Challenges: City/Caltrans/RCTC/Metrolink/RCA/SCE
coordination. Accelerated schedule.Complex Case
Road Bridge widening.
Final Result: Successfully completed phased project
to minimize impact to public and obtained the building
occupancy.
REFERENCE: John Pourkazemi, City Engineer
City of Perris
[email protected] / 951.943.6100 Ext. 116
DURATION: 2020 - Ongoing
PROJECT TEAM: Dilesh Sheth, PE, TE, Joseph
Caldwell, PE, CPSWQ, QSD, QSP, CFM, Joseph
Castaneda, PE, Nick Lowe, PE, TE, Son Le, Myung
Choo, PE, TE
PLC NORTH - OFFSITE INFRASTRUCTURE PROJECT - CITY OF
PERRIS
IDI LOGISTICS
REFERENCES
15.F.
4 City of Hemet
Warren Road Improvements
Madison Street Improvement Project, managed by
WEBB, involved a series of environmental, engineering,
and right-of-way services. The project spanned one
mile between Avenue 50 and 52. WEBB’s contributions
included an alignment study, environmental services,
utility relocation, right-of-way acquisition, a roundabout feasibility study, and coordination with multiple
entities. The project addressed the non-compliance of
Madison Street’s typical section with the General Plan
Circulation Elements of both cities and facilitated the installation of a double box culvert on the Coachella
Valley Water District’s Canal. The project also dealt
with several residential tracts and El Dorado/Empire
Polo Club properties, necessitating different alignments for additional right-of-way. Effective communication
with property owners was crucial for this project.
The project faced challenges due to shared right-ofways by multiple agencies, leading to conflicts due to existing utilities and potential conflicts with proposed improvements. It was essential to establish senior
rights within the shared right-of-way. WEBB’s research
proved that the City of La Quinta had senior rights,
leading to IID accepting shared responsibility for 37
transmission lines, saving the project over $2 million.
A double-box culvert was previously installed over
the Coachella Canal on Madison Street. An alignment
study and geometrics analysis were conducted to
avoid reconstructing the box culvert’s headwall,
successfully meeting the ultimate geometrics need.
The project was constructed in three phases.
Challenges: City/CVWD/IID/Property Owner coordination.
Coachella Music Festivals construction restrictions.
Final Result: Successfully completed three phases
without impacting the festivals.
REFERENCE: Tim Wassil, Public Works Director
[email protected] / 760.391.4018
City of Indio
DURATION: 2014 - 2019
PROJECT TEAM: Dilesh Sheth, PE, TE, Myung
Choo, PE, TE Joseph Caldwell, PE, CPSWQ, QSD,
QSP, CFM
MADISON STREET IMPROVEMENT PROJECT FROM AVENUE 50 TO 52
CITY OF INDIO