City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699
SUMMARY OF WORK - RESTORATION 011110 - 2
exceed Engineer/Architect's estimate, Contractor shall obtain written authorization to proceed from Owner before executing Work required for that Work Item.

C. Measurement of quantities for individual Work Items will be performed by Contractor and reviewed by Engineer/Architect. Coordinate measurements with inspection as required in Section "Project Management and Coordination."
D. Cost of Work included in each Work Item for quantities as indicated in Contract Documents shall be included in Base Bid.

1. Additions to or deductions from lump sum price for quantities of each Work Item added to or deducted from Work respectively shall be at unit prices indicated in Bid Form and shall constitute payment or deductions in full for all material, equipment, labor, supervision and incidentals necessary to complete Work.

1.4 WORK SEQUENCE
A. Prior to commencement of work, meet with Engineer/Architect and Owner representatives to establish sequence and schedule of Work. Contractor shall give Owner notice of areas to be cleared of cars at least 2 working days in advance of actual Work.

B. Contractor shall notify Owner's representative at least 24 hrs prior to beginning any abrasive blasting operations.

C. Contractor shall remove all broken concrete and debris from Work area on daily basis and dispose of same at authorized dump sites.

D. Contractor shall remove dust and air transported sand/debris from remainder of facility at conclusion of operations in Work area.

1.5 CONTRACTOR USE OF PREMISES
A. General: During construction period Contractor shall have limited use of premises for construction operations. The City will continue to operate the other portions of the garage and building that are not being worked on.

B. General: Limit use of premises to construction activities in areas indicated; allow for Owner occupancy and use by public.

1. Confine operations to areas within Contract limits indicated. Portions of the site beyond areas in which construction operations are indicated are not to be disturbed.

2. Keep driveways and entrances serving the premises clear and available to the Owner and Owner's employees at all times. Do not use these areas for parking or

Page 632 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699
SUMMARY OF WORK - RESTORATION 011110 - 3
storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on site.

C. Contractor's use of premises shall not interfere with operation of same. Elevators shall not be used for transfer of materials or equipment.

D. Contractor's debris removal path shall be over non-repaired services unless physical restraints prevent use of such path.

E. Contractor shall confine its apparatus, materials, equipment, tool cribs, field offices and operations to areas designated by Owner and/or Engineer/Architect. Premises shall not be unreasonably encumbered with materials and equipment. Neat and orderly stockpiling and other operations shall be maintained and debris shall be regularly removed from site. Contractor shall not load or permit any part of structure to be loaded with weight that will endanger structural integrity or safety of facility. Contractor shall limit axle loads to maximum 4000 lb per axle and gross weight of 8000 lb, or stockpiling of materials and equipment to 50 lb per sq ft. Contractor to note existing height restrictions within parking structure.

F. Contractor Parking: Contractor's employees shall park within confines of work area or pay prevailing parking rates.

G. On-Site Storage: Contractor shall not store materials or equipment at site of Work for more than one week prior to time that materials or equipment are incorporated into Work.

1.6 BARRICADES
A. Provide positive barricading to separate Work areas from areas open to public and to prevent the need for washing cars parked adjacent to the work area. Minimum acceptable separation: 6 ft. 0 in. high temporary construction fence (or 4 ft. 0 in. high solid temporary barrier constructed of wood.) with tarpaulins or other barrier hung floor to ceiling to prevent damage to vehicles due to airborne debris. See "Temporary Facilities" for additional requirements.

1.7 TRAFFIC OFFICERS AND FLAGMEN
A. When, in Owner's opinion, it is necessary that uniformed police or security officers be used to protect and control pedestrian traffic, to direct vehicular traffic during construction and to keep traffic off any part of Work, or to protect public safety, a police/security detail will be obtained. All expenses for uniformed officers shall be assumed by Contractor.

Contractor to coordinate the use of flagmen or officers.

Page 633 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699
SUMMARY OF WORK - RESTORATION 011110 - 4

1.8 CLAIMS
A. Contractor shall promptly address all damages claims. Owner reserves right to resolve any claims not addressed by Contractor within 3 wks after claim is received by Contractor.

Any amounts paid by Owner will be deducted from Contractor's next progress payment.

PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 011110

Page 634 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SECTION 012900 - PAYMENT PROCEDURES
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general and special provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY
A. This Section specifies administrative and procedural requirements necessary to prepare and process Applications for Payment.

1.3 APPLICATIONS FOR PAYMENT
A. Each Application for Payment shall be consistent with previous applications and payments as certified by Construction Manager and paid for by Owner.

1. Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements.

B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction Work covered by each Application for Payment is the period indicated in the Agreement.

C. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Engineer will return incomplete applications without action.

1. Entries shall match data on the Schedule of Values and Contractor's Construction Schedule. Use updated schedules if revisions were made.

2. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

D. Transmittal: Submit Application for Payment to Construction Manager as directed by Owner. Include waivers of lien and similar attachments if required.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

E. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's liens from subcontractors, sub-subcontractors, and suppliers for construction period covered by the previous application.

Page 635 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PAYMENT PROCEDURES 012900 - 1

1. Submit partial waivers on each item for amount requested, before deduction for retainage, on each item.

2. When an application shows completion of an item, submit final or full waivers.

3. Owner reserves the right to designate which entities involved in the Work must submit waivers.

4. Waiver Delays: Submit each Application for Payment with Contractor's waiver of mechanic's lien for construction period covered by the application. a. Submit final Application for Payment with or preceded by final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien.

5. Waiver Forms: Submit waivers of lien on forms, executed in a manner acceptable to Owner.

F. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

3. Updated final statement, accounting for final changes to the Contract Sum.

4. "Contractor's Affidavit of Payment of Debts and Claims."

5. "Contractor's Affidavit of Release of Liens."

6. Evidence that claims have been settled.

PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 012900
PAYMENT PROCEDURES 012900 - 2

Page 636 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PROJECT MANAGEMENT AND COORDINATION 013100 - 1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general and special provisions of the Contract, including other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. General project coordination procedures.

2. Coordination Drawings.

3. Administrative and supervisory personnel.

4. Project meetings.

B. Related Sections: The following Sections contain requirements that relate to this Section:

1. Division 01 Section "Closeout Procedures" for coordinating Contract closeout.

1.3 COORDINATION
A. Coordination: Each contractor shall coordinate its construction operations with those of other contractors and entities to ensure efficient and orderly installation of each part of the Work. Each contractor shall coordinate its operations with operations, included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. If necessary, prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

Page 637 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PROJECT MANAGEMENT AND COORDINATION 013100 - 2

1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Project closeout activities.

1.4 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Engineer of scheduled meeting dates and times.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

3. Minutes: Record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner and Engineer, within 3 days of the meeting.

B. Preconstruction Conference: Schedule a preconstruction conference before starting construction, at a time convenient to Owner and Engineer, but no later than 15 days after execution of the Agreement. Hold the conference at Project site or another convenient location. Conduct the meeting to review responsibilities and personnel assignments.

1. Attendees: Authorized representatives of Owner, Engineer, and their consultants; Contractor and its superintendent; major subcontractors; manufacturers; suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

C. Progress Meetings: Conduct progress meetings at regular intervals. Coordinate dates of meetings with preparation of payment requests.

1. Attendees: In addition to representatives of Owner and Engineer, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be

Page 638 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PROJECT MANAGEMENT AND COORDINATION 013100 - 3
represented at these meetings. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present. Include a brief summary, in narrative form, of progress since the previous meeting and report.
a. Schedule Updating: Revise Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 013100

Page 639 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 1
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, Section 6 of the Special Provisions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY
A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following

1. Contractor's Construction Schedule.

2. Construction schedule updating reports.

3. Daily construction reports.

4. Material location reports.

5. Field condition reports.

6. Unusual event reports.

7. Construction photographs.

B. Related Sections include the following:

1. Division 01 Section "Project Management and Coordination" for submitting and distributing meeting and conference minutes.

2. Division 01 Section "Submittal Procedures" for submitting schedules and reports.

3. Division 01 Section "Photographic Documentation" for submitting construction photographs.

4. Division 01 Section "Quality Control" for submitting a schedule of tests and inspections.

1.3 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path that must start and finish on the planned early start and finish times.

2. Predecessor activity is an activity that precedes another activity in the network.

Page 640 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 2

3. Successor activity is an activity that follows another activity in the network. B.

Event: The starting or ending point of an activity.

C. Milestone: A key or critical point in time for reference or measurement.

1.4 INFORMATIONAL SUBMITTALS
A. Format for Submittals: Submit required submittals in the following format:

1. Working electronic copy of schedule file, where indicated.

2. PDF file.

B. Contractor's Construction Schedule: Initial schedule of size required to display entire schedule for entire construction period.

1. Submit a working digital copy of schedule, using software indicated and labeled to comply with requirements for submittals. Include type of schedule (Initial or Updated) and date on label.

C. Digital Photographs: Submit image files within three (3) days of taking photographs.

1. Submit photos by uploading to Walker. Include copy of key plan indicating each photograph's location and direction.

D. Construction Schedule Updating Reports: Submit with Application for Payment E. Daily Construction Reports: Submit at monthly intervals.

F. Unusual Event Reports: Submit at time of unusual event.

1.5 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.

B. Coordinate Contractor's Construction Schedule with the Schedule of Values, submittals schedule, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from parties involved.

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

Page 641 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 3

1.6 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Time Frame: Extend schedule from date established for Date of Commencement to Final Completion.

1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.

B. Activities: Treat each separate area as a separate numbered activity for each principal element of the Work. Comply with the following:

1. Submittal Review Time: Include review and resubmittal times indicated in Division 01 Section "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's Construction Schedule with Submittals Schedule.

2. Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for Engineer’s administrative procedures necessary for certification of Substantial Completion.

3. Punch List and Final Completion: Include not more than thirty (30) days for completion of punch list items and final completion.

C. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule with each monthly payment application.

1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.

2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.

3. As the Work progresses, indicate final completion percentage for each activity.

D. Distribution: Distribute copies of approved schedule to Engineer, Owner, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.

1. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.

1.7 GANTT-CHART SCHEDULE REQUIREMENTS
A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal, Ganttcharttype, Contractor's Construction Schedule within 15 days of date established for commencement of the Work.

Page 642 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 4

1. Base schedule on the startup construction schedule and additional information received since the start of Project.

B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line.

1.8 REPORTS
A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:

1. List of subcontractors at Project site.

2. Approximate count of personnel at Project site.

3. Material deliveries.

4. High and low temperatures and general weather conditions, including presence of rain or snow.

5. Testing and inspection.

6. Accidents.

7. Meetings and significant decisions.

8. Unusual events.

9. Stoppages, delays, shortages, and losses.

10. Orders and requests of authorities having jurisdiction.

11. Change Orders received and implemented.

12. Change Directives received and implemented.

B. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Request for Information. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.

C. Unusual Event Reports: When an event of an unusual and significant nature occurs at Project site, whether or not related directly to the Work, prepare and submit a special report. List chain of events, persons participating, responses by Contractor's personnel, evaluation of results or effects, and similar pertinent information. Advise Owner in advance when these events are known or predictable.

1. Submit unusual event reports directly to Owner within 1 day(s) of an occurrence.

Distribute copies of report to parties affected by the occurrence.

PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION

Page 643 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 5

3.1 CONSTRUCTION PHOTOGRAPHS
A. General: Take photographs with maximum depth of field and in focus.

1. Maintain key plan with each set of construction photographs that identifies each photographic location.

B. Periodic Construction Photographs: Take photographs to show status of construction and progress as work progresses.

END OF SECTION 013200

Page 644 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SUBMITTAL PROCEDURES 013300 - 1
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY
A. This Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

B. Related Requirements:

1. Division 01 Section "Payment Procedures” For submitting Applications for Payment and the schedule of values.

2. Division 01 Section "Project Management and Coordination" for submitting coordination drawings and subcontract list.

3. Division 01 Section "Construction Progress Documentation" for submitting schedules and reports, including Contractor's construction schedule.

4. Division 01 Section "Quality Requirements" for submitting test and inspection reports and schedule of tests and inspections.

5. Division 01 Section "Closeout Procedures" for submitting closeout submittals and maintenance material submittals.

6. Division 01 Section "Project Record Documents" for submitting Record Drawings, Record Specifications, and Record Product Data.

1.3 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that require responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."
B. Informational Submittals: Written and graphic information and physical samples that do not require Engineer's approval. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."
C. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.

Page 645 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SUBMITTAL PROCEDURES 013300 - 2

1.4 SUBMITTAL SCHEDULE
A. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Engineer and additional time for handling and reviewing submittals required by those corrections.

1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule.

2. Initial Submittal: Submit concurrently with startup construction schedule. Include submittals required during the first 60 days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.

3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule.
a. Submit revised submittal schedule to reflect changes in current status and timing for submittals.

4. Format: Arrange the following information in a tabular format:
a. Scheduled date for first submittal.
b. Specification Section number and title.
c. Submittal category: Action; informational.
d. Name of subcontractor.
e. Description of the Work covered.
f. Scheduled date for Engineer’s final release or approval. g. Scheduled dates for purchasing.
h. Scheduled date of fabrication.
i. Scheduled dates for installation.
j. Activity or event number.

1.5 SUBMITTAL FORMATS
A. Submittal Information: Include the following information in each submittal:

1. Project name.

2. Date.

3. Name of Engineer.

4. Name of Contractor.

5. Name of firm or entity that prepared submittal.

6. Names of subcontractor, manufacturer, and supplier.

7. Unique submittal number, including revision identifier. Include Specification Section number with sequential alphanumeric identifier, and alphanumeric suffix for resubmittals.

Page 646 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SUBMITTAL PROCEDURES 013300 - 3

8. Category and type of submittal.

9. Submittal purpose and description.

10. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.

11. Drawing number and detail references, as appropriate.

12. Indication of full or partial submittal.

13. Location(s) where product is to be installed, as appropriate.

14. Other necessary identification.

15. Remarks.

16. Signature of transmitter.

B. Options: Identify options requiring selection by Engineer.

C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by Engineer[ on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.

D. PDF Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.

1.6 SUBMITTAL PROCEDURES
A. Engineer’s Digital Data Files: Electronic digital data files of the Contract Drawings will be provided by Engineer for Contractor's use in preparing submittals.

1. Upon written request by the Contractor and execution of associated disclaimer forms and related documentation, the Contract Drawings will be provided to the Contractor for use in preparation of record drawings and submittals. Drawing files will be transmitted one time to the Contractor at the start of construction. This version of the drawings is provided only as a courtesy and convenience and Engineer makes no representations as to their accuracy or completeness as they relate to the Contract Documents.

B. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.

1. Email: Prepare submittals as PDF package and transmit to Engineer by sending via email. Include PDF transmittal form. Include information in email subject line as requested by Engineer.
a. Engineer will return annotated file. Annotate and retain one copy of file as a digital Project Record Document file.

Page 647 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SUBMITTAL PROCEDURES 013300 - 4
C. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.

4. Coordinate transmittal of submittals for related parts of the Work specified in different Sections so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Engineer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

D. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Engineer's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow (10) days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Engineer will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Resubmittal Review: Allow (7) days for review of each resubmittal.

E. Resubmittals: Engineer will review each of Contractor’s submittals the initial time and, should resubmittal be required, one additional time to verify that reasons for resubmittal have been addressed by Contractor and corrections made. Resubmittal changes/revisions/corrections shall be circled. Engineer will review only circled items and will not be responsible for non-circled changes/revisions/corrections and additions.

Should additional resubmittals be required, Contractor shall reimburse Owner for all costs incurred, including the cost of Engineer’s services made necessary to review such additional resubmittals. Owner will in turn reimburse Engineer.

1. Make resubmittals in same form and number of copies as initial submittal. a. Note date and content of previous submittal.
b. Note date and content of revision in label or title block and clearly indicate extent of revision.
c. Resubmit submittals until they are marked with approval notation from Engineer's action stamp.

Page 648 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SUBMITTAL PROCEDURES 013300 - 5
F. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

G. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Engineer's action stamp.

1.7 SUBMITTAL REQUIREMENTS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards. e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.

4. Submit Product Data before Shop Drawings, and before or concurrent with Samples.

B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data unless submittal based on Engineer's digital data drawing files is otherwise permitted.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement. f. Relationship and attachment to adjoining construction clearly indicated. g. Seal and signature of professional engineer if specified.

Page 649 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SUBMITTAL PROCEDURES 013300 - 6
C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other materials.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Identification: Permanently attach label on unexposed side of Samples that includes the following:
a. Project name and submittal number.
b. Generic description of Sample.
c. Product name and name of manufacturer.
d. Sample source.
e. Number and title of applicable Specification Section. f. Specification paragraph number and generic name of each item.

3. Email Transmittal: Provide PDF transmittal. Include digital image file illustrating Sample characteristics, and identification information for record.

4. Paper Transmittal: Include paper transmittal including complete submittal information indicated.

5. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.
a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use.
b. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the property of Contractor.

6. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
a. Number of Samples: Submit (1) full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Engineer will return submittal with options selected.

7. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.

Page 650 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SUBMITTAL PROCEDURES 013300 - 7
a. Number of Samples: Submit (3) sets of Samples. Engineer will retain (2) Sample sets; remainder will be returned.
b. Submit a single Sample where assembly details, workmanship, fabrication techniques, connections, operation, and other similar characteristics are to be demonstrated.
1) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least (3) sets of paired units that show approximate limits of variations.

D. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location.

Include the following information in tabular form:

1. Type of product. Include unique identifier for each product indicated in the Contract Documents or assigned by Contractor if none is indicated.

2. Manufacturer and product name, and model number if applicable.

3. Number and name of room or space.

4. Location within room or space.

E. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of Engineers and owners, and other information specified.

F. Design Data: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections.

Include list of assumptions and summary of loads. Include load diagrams if applicable.

Provide name and version of software, if any, used for calculations. Number each page of submittal. G. Certificates:

1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. Provide a notarized signature where indicated.

2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.

4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

6. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of

Page 651 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SUBMITTAL PROCEDURES 013300 - 8
Welding Procedure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified. H. Test and Research Reports:

1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

4. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.

5. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents.

Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

6. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:
a. Name of evaluation organization.
b. Date of evaluation.
c. Time period when report is in effect.
d. Product and manufacturers' names.
e. Description of product.
f. Test procedures and results.
g. Limitations of use.

1.8 DELEGATED-DESIGN SERVICES
A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.

1. If criteria indicated are insufficient to perform services or certification required, submit a written request for additional information to Engineer.

Page 652 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SUBMITTAL PROCEDURES 013300 - 9
B. Delegated-Design Services Certification: In addition to Shop Drawings, Product Data, and other required submittals, submit digitally signed PDF file signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.

1. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services.

1.9 REQUESTS FOR INFORMATION
A. Engineer reserves the right to reject, unprocessed, any Request for Information (RFI) that the Engineer, at its sole discretion, deems frivolous.

B. Engineer reserves the right to reject, unprocessed, any RFI that the Engineer, at its sole discretion, deems already answered in the Contract Documents.

C. RFI process shall not be used for requesting substitutions. Procedures for substitutions are clearly specified elsewhere in the contract documents.

1.10 CONTRACTOR'S REVIEW
A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Engineer
B. Project Closeout and Maintenance Material Submittals: See Requirements in Division 01 Section “Closeout Procedures.”
C. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform approval stamp. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

1. Engineer will not review submittals received from Contractor that do not have Contractor's review and approval.

1.11 ENGINEER'S ACTION
A. General: Engineer will not review submittals that do not bear Contractor's approval stamp and will return them without action.

B. Action Submittals: Engineer or its subconsultant will review each submittal, make marks to indicate corrections or revisions required, and return it.

Page 653 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SUBMITTAL PROCEDURES 013300 - 10

1. PDF Submittals: Engineer will indicate, via markup on each submittal, the appropriate action.
a. See Division 00, Section “Supplementary Conditions” for description of terminology on Engineer’s Stamp applied via markup to each submittal.

2. Paper Submittals: Engineer will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action.
a. See Division 00, Section “Supplementary Conditions” for description of terminology on Engineer’s Stamp.

C. Informational Submittals: Engineer will review each submittal and will not return it, or will return it if it does not comply with requirements. Engineer will forward each submittal to appropriate party.

D. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from Engineer.

E. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.

F. Engineer will discard submittals received from sources other than Contractor.

G. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 01 33 00

Page 654 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699
QUALITY CONTROL 014000 - 1
SECTION 014000 - QUALITY CONTROL
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY
A. This Section specifies administrative and procedural requirements for quality control services.

B. Quality control services include inspections, tests and related actions including reports, performed by independent agencies, governing authorities, and the Contractor. They do not include Contract enforcement activities performed by Engineer/Architect.

C. Inspection and testing services are required to verify compliance with requirements specified or indicated. These services do not relieve the Contractor of responsibility for compliance with Contract Document requirements.

D. Testing and inspection services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.

1. Specific quality-assurance and quality-control requirements for individual work results are specified in their respective Specification Sections. Requirements in individual Sections may also cover production of standard products.

2. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and quality-control procedures that facilitate compliance with the Contract Document requirements.

3. Requirements for Contractor to provide quality-assurance and quality-control services required by Architect, Owner or authorities having jurisdiction are not limited by provisions of this Section.

4. Specific test and inspection requirements are not specified in this Section.

1.3 DEFINITIONS
A. Experienced: When used with an entity or individual, "experienced" unless otherwise further described means having successfully completed a minimum of (5) previous projects similar in nature, size, and extent to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.

Page 655 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699
QUALITY CONTROL 014000 - 2
B. Field Quality-Control Tests: Tests and inspections that are performed on-site for installation of the Work and for completed Work.

C. Preconstruction Testing: Tests and inspections performed specifically for Project before products and materials are incorporated into the Work, to verify performance or compliance with specified criteria.

D. Product Tests: Tests and inspections that are performed by a nationally recognized testing laboratory (NRTL) according to 29 CFR 1910.7, by a testing agency accredited according to NIST's National Voluntary Laboratory Accreditation Program (NVLAP), or by a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with specified requirements.

E. Source Quality-Control Tests: Tests and inspections that are performed at the source; for example, plant, mill, factory, or shop.

F. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.

G. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.

H. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual product incorporated into the Work and completed construction comply with requirements. Contractor's quality-control services do not include contract administration activities performed by Engineer.

1.4 DELEGATED-DESIGN SERVICES
A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.

1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Engineer.

1.5 CONFLICTING REQUIREMENTS
A. Conflicting Standards and Other Requirements: If compliance with two or more standards or requirements are specified and the standards or requirements establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer conflicting requirements that are different, but apparently equal, to Engineer for direction before proceeding.

Page 656 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699
QUALITY CONTROL 014000 - 3
B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Engineer for a decision before proceeding.

1.6 ACTION SUBMITTALS
A. Delegated-Design Services Submittal: In addition to Shop Drawings, Product Data, and other required submittals, submit a statement signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional, indicating that the products and systems are in compliance with performance and design criteria indicated. Include list of codes, loads, and other factors used in performing these services.

1.7 INFORMATIONAL SUBMITTALS
A. Contractor's Quality-Control Plan: For quality-assurance and quality-control activities and responsibilities.

B. Qualification Data: For Contractor's quality-control personnel.

C. Contractor's Statement of Responsibility: When required by authorities having jurisdiction, submit copy of written statement of responsibility submitted to authorities having jurisdiction before starting work on the following systems:

1. Seismic-force-resisting system, designated seismic system, or component listed in the Statement of Special Inspections.

2. Main wind-force-resisting system or a wind-resisting component listed in the Statement of Special Inspections.

D. Testing Agency Qualifications: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.

E. Schedule of Tests and Inspections: Prepare in tabular form and include the following:

1. Specification Section number and title.

2. Entity responsible for performing tests and inspections.

3. Description of test and inspection.

4. Identification of applicable standards.

5. Identification of test and inspection methods.

6. Number of tests and inspections required.

7. Time schedule or time span for tests and inspections.

Page 657 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699
QUALITY CONTROL 014000 - 4

8. Requirements for obtaining samples.

9. Unique characteristics of each quality-control service.

F. Reports: Prepare and submit certified written reports and documents as specified.

G. Permits, Licenses, and Certificates: For Owner's record, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work.

1.8 CONTRACTOR'S QUALITY-CONTROL PLAN
A. Quality-Control Plan, General: Submit quality-control plan within (10) days of Notice to Proceed, and not less than (5) days prior to preconstruction conference. Submit in format acceptable to Engineer. Identify personnel, procedures, controls, instructions, tests, records, and forms to be used to carry out Contractor's quality-assurance and qualitycontrol responsibilities. Coordinate with Contractor's Construction Schedule.

B. Quality-Control Personnel Qualifications: Engage qualified personnel trained and experienced in managing and executing quality-assurance and quality-control procedures similar in nature and extent to those required for Project.

1. Project quality-control manager [may also serve as Project superintendent] [shall not have other Project responsibilities].

2. <Insert qualifications appropriate to Project>.

C. Submittal Procedure: Describe procedures for ensuring compliance with requirements through review and management of submittal process. Indicate qualifications of personnel responsible for submittal review.

D. Testing and Inspection: In quality-control plan, include a comprehensive schedule of Work requiring testing or inspection, including the following:

1. Contractor-performed tests and inspections including Subcontractor-performed tests and inspections. Include required tests and inspections and Contractorelected tests and inspections. Distinguish source quality-control tests and inspections from field quality-control tests and inspections.

2. Special inspections required by authorities having jurisdiction and indicated on the Statement of Special Inspections.

3. Owner-performed tests and inspections indicated in the Contract Documents, including tests and inspections indicated to be performed by Commissioning Authority.

E. Continuous Inspection of Workmanship: Describe process for continuous inspection during construction to identify and correct deficiencies in workmanship in addition to testing and inspection specified. Indicate types of corrective actions to be required to

Page 658 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699
QUALITY CONTROL 014000 - 5
bring work into compliance with standards of workmanship established by Contract requirements and approved mockups.

F. Monitoring and Documentation: Maintain testing and inspection reports including log of approved and rejected results. Include work Engineer has indicated as nonconforming or defective. Indicate corrective actions taken to bring nonconforming work into compliance with requirements. Comply with requirements of authorities having jurisdiction.

1.9 REPORTS AND DOCUMENTS
A. Test and Inspection Reports: Prepare and submit certified written reports specified in other Sections. Include the following:

1. Date of issue.

2. Project title and number.

3. Name, address, telephone number, and email address of testing agency.

4. Dates and locations of samples and tests or inspections.

5. Names of individuals making tests and inspections.

6. Description of the Work and test and inspection method.

7. Identification of product and Specification Section.

8. Complete test or inspection data.

9. Test and inspection results and an interpretation of test results.

10. Record of temperature and weather conditions at time of sample taking and testing and inspection.

11. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements.

12. Name and signature of laboratory inspector.

13. Recommendations on retesting and reinspecting.

B. Manufacturer's Technical Representative's Field Reports: Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections. Include the following:

1. Name, address, telephone number, and email address of technical representative making report.

2. Statement on condition of substrates and their acceptability for installation of product.

3. Statement that products at Project site comply with requirements.

4. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken.

5. Results of operational and other tests and a statement of whether observed performance complies with requirements.

6. Statement whether conditions, products, and installation will affect warranty.

7. Other required items indicated in individual Specification Sections.

Page 659 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699
QUALITY CONTROL 014000 - 6
C. Factory-Authorized Service Representative's Reports: Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections. Include the following:

1. Name, address, telephone number, and email address of factory-authorized service representative making report.

2. Statement that equipment complies with requirements.

3. Results of operational and other tests and a statement of whether observed performance complies with requirements.

4. Statement whether conditions, products, and installation will affect warranty.

5. Other required items indicated in individual Specification Sections.

1.10 QUALITY ASSURANCE
A. General: Qualifications paragraphs in this article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.

B. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units. As applicable, procure products from manufacturers able to meet qualification requirements, warranty requirements, and technical or factory-authorized service representative requirements.

C. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

D. Installer Qualifications: A firm or individual experienced in installing, erecting, applying, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.

E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar in material, design, and extent to those indicated for this Project.

F. Specialists: Certain Specification Sections require that specific construction activities shall be performed by entities who are recognized experts in those operations.

Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.

1. Requirements of authorities having jurisdiction shall supersede requirements for specialists.

Page 660 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699
QUALITY CONTROL 014000 - 7
G. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspection indicated, as documented according to ASTM E 329; and with additional qualifications specified in individual Sections; and, where required by authorities having jurisdiction, that is acceptable to authorities.

H. Manufacturer's Technical Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to observe and inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.

I. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.

J. Preconstruction Testing: Where testing agency is indicated to perform preconstruction testing for compliance with specified requirements for performance and test methods, comply with the following:

1. Contractor responsibilities include the following:
a. Provide test specimens representative of proposed products and construction.
b. Submit specimens in a timely manner with sufficient time for testing and analyzing results to prevent delaying the Work

2. Testing Agency Responsibilities: Submit a certified written report of each test, inspection, and similar quality-assurance service to Engineer with copy to Contractor. Interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.

1.11 RESPONSIBILITIES
A. Owner Responsibilities: Where quality-control services are indicated as Owner's responsibility, Owner will engage a qualified testing agency to perform these services.

1. Owner will furnish Contractor with names, addresses, and telephone numbers of testing agencies engaged and a description of types of testing and inspection they are engaged to perform.

2. Payment for these services will be made from testing and inspection allowances, as authorized by Change Orders.

Page 661 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699
QUALITY CONTROL 014000 - 8

3. Costs for retesting and reinspecting construction that replaces or is necessitated by work that failed to comply with the Contract Documents will be charged to Contractor, and the Contract Sum will be adjusted by Change Order.

B. Contractor Responsibilities: Tests and inspections not explicitly assigned to Owner are Contractor's responsibility. Perform additional quality-control activities, whether specified or not, to verify and document that the Work complies with requirements.

1. Unless otherwise indicated, provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not.

2. Engage a qualified testing agency to perform quality-control services. a. Contractor shall not employ same entity engaged by Owner, unless agreed to in writing by Owner.

3. Notify testing agencies at least (24) hours in advance of time when Work that requires testing or inspection will be performed.

4. Where quality-control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality-control service.

5. Testing and inspection requested by Contractor and not required by the Contract Documents are Contractor's responsibility.

6. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.

C. Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that replaced Work that failed to comply with the Contract Documents.

D. Testing Agency Responsibilities: Cooperate with Engineer and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.

1. Notify Engineer and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.

2. Determine the locations from which test samples will be taken and in which in-situ tests are conducted.

3. Conduct and interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.

4. Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor.

5. Do not release, revoke, alter, or increase the Contract Document requirements or approve or accept any portion of the Work.

6. Do not perform duties of Contractor.

Page 662 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699
QUALITY CONTROL 014000 - 9
E. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing as specified in Division 01 Section "Submittal Procedures."
F. Manufacturer's Technical Services: Where indicated, engage a manufacturer's technical representative to observe and inspect the Work. Manufacturer's technical representative's services include participation in preinstallation conferences, examination of substrates and conditions, verification of materials, observation of Installer activities, inspection of completed portions of the Work, and submittal of written reports.

G. Associated Contractor Services: Cooperate with agencies and representatives performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:

1. Access to the Work.

2. Incidental labor and facilities necessary to facilitate tests and inspections.

3. Adequate quantities of representative samples of materials that require testing and inspection. Assist agency in obtaining samples.

4. Facilities for storage and field curing of test samples.

5. Delivery of samples to testing agencies.

6. Preliminary design mix proposed for use for material mixes that require control by testing agency.

7. Security and protection for samples and for testing and inspection equipment at Project site.

H. Coordination: Coordinate sequence of activities to accommodate required qualityassurance and quality-control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspection.

1. Schedule times for tests, inspections, obtaining samples, and similar activities.

I. Schedule of Tests and Inspections: Prepare a schedule of tests, inspections, and similar quality-control services required by the Contract Documents. Coordinate and submit concurrently with Contractor's Construction Schedule. Update as the Work progresses.

1. Distribution: Distribute schedule to Owner, Engineer testing agencies, and each party involved in performance of portions of the Work where tests and inspections are required.

Page 663 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699
QUALITY CONTROL 014000 - 10

1.12 SPECIAL TESTS AND INSPECTIONS
A. Special Tests and Inspections: Owner will engage a qualified testing agency to conduct special tests and inspections required by authorities having jurisdiction as the responsibility of Owner and as follows:

1. Verifying that manufacturer maintains detailed fabrication and quality-control procedures and reviewing the completeness and adequacy of those procedures to perform the Work.

2. Notifying Engineer and Contractor promptly of irregularities and deficiencies observed in the Work during performance of its services.

3. Submitting a certified written report of each test, inspection, and similar qualitycontrol service to Engineer with copy to Contractor and to authorities having jurisdiction.

4. Submitting a final report of special tests and inspections at Substantial Completion, which includes a list of unresolved deficiencies.

5. Interpreting tests and inspections and stating in each report whether tested and inspected work complies with or deviates from the Contract Documents.

6. Retesting and reinspecting corrected work.

PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION

3.1 TEST AND INSPECTION LOG
A. Test and Inspection Log: Prepare a record of tests and inspections. Include the following:

1. Date test or inspection was conducted.

2. Description of the Work tested or inspected.

3. Date test or inspection results were transmitted to Engineer.

4. Identification of testing agency or special inspector conducting test or inspection.

B. Maintain log at Project site. Post changes and revisions as they occur. Provide access to test and inspection log for Engineer's reference during normal working hours.

1. Submit log at Project closeout as part of Project Record Documents.

3.2 REPAIR AND PROTECTION
A. General: On completion of testing, inspection, sample taking, and similar services, repair damaged construction and restore substrates and finishes.

1. Provide materials and comply with installation requirements specified in other Specification Sections or matching existing substrates and finishes. Restore

Page 664 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699
QUALITY CONTROL 014000 - 11
patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible. Comply with the Contract Document requirements for cutting and patching in Division 01 Section "Execution." B. Protect construction exposed by or for quality-control service activities.

C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.

END OF SECTION 01 40 00

Page 665 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

REFERENCE STANDARDS AND DEFINITIONS 014210 - 1
SECTION 014210 - REFERENCE STANDARDS AND DEFINITIONS
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 DEFINITIONS
A. General: Basic contract definitions are included in the Conditions of the Contract.

B. "Indicated": The term "indicated" refers to graphic representations, notes, or schedules on the Drawings; or to other paragraphs or schedules in the Specifications and similar requirements in the Contract Documents. Terms such as "shown," "noted," "scheduled," and "specified" are used to help the user locate the reference. Location is not limited.

C. "Directed": Terms such as "directed," "requested," "authorized," "selected," "approved," "required," and "permitted" mean directed by the Design Professional, requested by the Design Professional, and similar phrases.

D. "Approved": The term "approved," when used in conjunction with the Design Professional's action on the Contractor's submittals, applications, and requests, is limited to the Design Professional's duties and responsibilities as stated in the Conditions of the Contract.

E. "Regulations": The term "regulations" includes laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, as well as rules, conventions, and agreements within the construction industry that control performance of the Work.

F. "Furnish": The term "furnish" means to supply and deliver to the Project site, ready for unloading, unpacking, assembly, installation, and similar operations.

G. "Install": The term "install" describes operations at the Project site including the actual unloading, temporary storage, unpacking, assembling, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations.

H. "Provide": The term "provide" means to furnish and install, complete and ready for the intended use.

I. "Installer": An installer is the Contractor or another entity engaged by the Contractor, either as an employee, subcontractor, or contractor of lower tier, to perform a particular

Page 666 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

REFERENCE STANDARDS AND DEFINITIONS 014210 - 2
construction activity, including installation, erection, application, or similar operations.

Installers are required to be experienced in the operations they are engaged to perform.

1. The term "experienced," when used with the term "installer," means having successfully completed a minimum of five previous projects similar in size and scope to this Project; being familiar with the special requirements indicated; and having complied with requirements of authorities having jurisdiction.

2. Trades: Using a term such as "carpentry" does not imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter." It also does not imply that requirements specified apply exclusively to tradespersons of the corresponding generic name.

3. Assigning Specialists: Certain Sections of the Specifications require that specific construction activities shall be performed by specialists who are recognized experts in those operations. The specialists must be engaged for those activities, and their assignments are requirements over which the Contractor has no option.

However, the ultimate responsibility for fulfilling contract requirements remains with the Contractor.
a. This requirement shall not be interpreted to conflict with enforcing building codes and similar regulations governing the Work. It is also not intended to interfere with local trade-union jurisdictional settlements and similar conventions.

J. "Project site" is the space available to the Contractor for performing construction activities, either exclusively or in conjunction with others performing other work as part of the Project. The extent of the Project site is shown on the Drawings and may or may not be identical with the description of the land on which the Project is to be built.

K. "Testing Agencies": A testing agency is an independent entity engaged to perform specific inspections or tests, either at the Project site or elsewhere, and to report on and, if required, to interpret results of those inspections or tests.

1.3 SPECIFICATION FORMAT AND CONTENT EXPLANATION
A. Specification Format: These Specifications are organized into Divisions and Sections based on the CSI/CSC's "MasterFormat" numbering system.

B. Specification Content: These Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be interpolated as the sense requires. Singular words shall be interpreted as plural and plural words interpreted as singular where applicable as the context of the Contract Documents indicates.

Page 667 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

REFERENCE STANDARDS AND DEFINITIONS 014210 - 3

2. Imperative mood and streamlined language are generally used in the Specifications. Requirements expressed in the imperative mood are to be performed by the Contractor. At certain locations in the Section Text, subjective language is used for clarity to describe responsibilities that must be fulfilled indirectly by the Contractor or by others when so noted. a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

1.4 INDUSTRY STANDARDS
A. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference.

B. Publication Dates: Comply with standards in effect as of the date of the Contract Documents.

C. Conflicting Requirements: Where compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to the Design Professional for a decision before proceeding.

1. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of the requirements. Refer uncertainties to the Design Professional for a decision before proceeding.

D. Copies of Standards: Each entity engaged in construction on the Project must be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents.

1. Where copies of standards are needed to perform a required construction activity, the Contractor shall obtain copies directly from the publication source and make them available on request.

E. Abbreviations and Names: Trade association names and titles of general standards are frequently abbreviated. Where abbreviations and acronyms are used in the Specifications or other Contract Documents, they mean the recognized name of the trade association, standards-producing organization, authorities having jurisdiction, or other entity applicable to the context of the text provision. Refer to Gale Research's

Page 668 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

REFERENCE STANDARDS AND DEFINITIONS 014210 - 4
"Encyclopedia of Associations" or Columbia Books' "National Trade & Professional Associations of the U.S.," which are available in most libraries.

1.5 SUBMITTALS
A. Permits, Licenses, and Certificates: For the Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.

PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 014210

Page 669 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

TEMPORARY FACILITIES & CONTROLS 015000 - 1
SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY
A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities.

B. Related Requirements:

1. Section 011000 "Summary" for work restrictions and limitations on utility interruptions.

1.3 USE CHARGES
A. General: Installation and removal of and use charges for temporary facilities shall be included in the Contract Sum unless otherwise indicated. Allow other entities engaged in the Project to use temporary services and facilities without cost, including, but not limited to, Owner's construction forces, Architect, occupants of Project, testing agencies, and authorities having jurisdiction.

B. Water Service: Owner will pay water-service use charges for water used by all entities for construction operations.

C. Electric Power Service: Owner will pay electric-power-service use charges for electricity used by all entities for construction operations.

1.4 INFORMATIONAL SUBMITTALS
A. Implementation and Termination Schedule: Within fifteen (15) days of date established for commencement of the Work, submit schedule indicating implementation and termination dates of each temporary utility.

B. Project Identification and Temporary Signs: Show fabrication and installation details, including plans, elevations, details, layouts, typestyles, graphic elements, and message content.

Page 670 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

TEMPORARY FACILITIES & CONTROLS 015000 - 2
C. Fire-Safety Program: Show compliance with requirements of NFPA 241 and authorities having jurisdiction. Indicate Contractor personnel responsible for management of fireprevention program.

D. Dust- and HVAC-Control Plan: Submit coordination drawing and narrative that indicates the dust- and HVAC-control measures proposed for use, proposed locations, and proposed time frame for their operation. Include the following:

1. Locations of dust-control partitions at each phase of work.

2. HVAC system isolation schematic drawing.

3. Location of proposed air-filtration system discharge.

4. Waste-handling procedures.

5. Other dust-control measures.

1.5 QUALITY ASSURANCE
A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.

B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.

C. Accessible Temporary Egress: Comply with applicable provisions in the United States Access Board's ADA-ABA Accessibility Guidelines.

1.6 PROJECT CONDITIONS
A. Temporary Use of Permanent Facilities: Engage Installer of each permanent service to assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Owner's acceptance, regardless of previously assigned responsibilities.

PART 2 - PRODUCTS

2.1 MATERIALS
A. Portable Chain-Link Fencing: Minimum 2-inch, 0.148-inch- thick, galvanized-steel, chainlink fabric fencing; minimum 6 feet high with galvanized-steel pipe posts; minimum 2-3/8- inch- OD line posts and 2-7/8-inch- OD corner and pull posts, with 1-5/8-inch- OD top and bottom rails. Provide concrete bases for supporting posts.

B. Fencing Windscreen Privacy Screen: Polyester fabric scrim with grommets for attachment to chain link fence, sized to height of fence, in color selected by Architect from manufacturer's standard colors.

Page 671 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

TEMPORARY FACILITIES & CONTROLS 015000 - 3
C. Polyethylene Sheet: Reinforced, fire-resistive sheet, 10-mil minimum thickness, with flame-spread rating of 15 or less per ASTM E 84 and passing NFPA 701 Test Method 2.

D. Dust-Control Adhesive-Surface Walk-Off Mats: Provide mats minimum 36 by 60 inches.

2.2 TEMPORARY FACILITIES
A. Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to accommodate materials and equipment for construction operations.

1. Store combustible materials apart from building.

2.3 EQUIPMENT
A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.

B. Air-Filtration Units: Primary and secondary HEPA-filter-equipped portable units with fourstage filtration. Provide single switch for emergency shutoff. Configure to run continuously.

PART 3 - EXECUTION

3.1 TEMPORARY FACILITIES, GENERAL
A. Conservation: Coordinate construction and use of temporary facilities with consideration given to conservation of energy, water, and materials. Coordinate use of temporary utilities to minimize waste.

1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. See other Sections for disposition of salvaged materials that are designated as Owner's property.

3.2 INSTALLATION, GENERAL
A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.

1. Locate facilities to limit site disturbance as specified in Division 1 Section "Summary."

Page 672 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

TEMPORARY FACILITIES & CONTROLS 015000 - 4
B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.

3.3 TEMPORARY UTILITY INSTALLATION
A. General: Install temporary service or connect to existing service.

1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.

B. Water Service: Connect to Owner's existing water service facilities. Clean and maintain water service facilities in a condition acceptable to Owner. At Substantial Completion, restore these facilities to condition existing before initial use.

C. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of construction personnel. Comply with requirements of authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.

D. Isolation of Work Areas in Occupied Facilities: Prevent dust, fumes, and odors from entering occupied areas.

1. Prior to commencing work, isolate the HVAC system in area where work is to be performed.
a. Disconnect supply and return ductwork in work area from HVAC systems servicing occupied areas.
b. Maintain negative air pressure within work area using HEPA-equipped airfiltration units, starting with commencement of temporary partition construction, and continuing until removal of temporary partitions is complete.

2. Maintain dust partitions during the Work. Use vacuum collection attachments on dust-producing equipment. Isolate limited work within occupied areas using portable dust-containment devices.

3. Perform daily construction cleanup and final cleanup using approved, HEPAfilterequipped vacuum equipment.

E. Electric Power Service: Connect to Owner's existing electric power service. Maintain equipment in a condition acceptable to Owner.

F. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions.

1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system.

G. Telephone Service: Provide supervisory construction personnel with cell phone access equipment.

Page 673 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

TEMPORARY FACILITIES & CONTROLS 015000 - 5

3.4 SUPPORT FACILITIES INSTALLATION
A. General: Comply with the following:

1. Provide construction for temporary offices, shops, and sheds located within construction area or within 30 feet of building lines that is noncombustible according to ASTM E 136. Comply with NFPA 241.

2. Maintain support facilities until Architect schedules Substantial Completion inspection. Remove before Substantial Completion. Personnel remaining after Substantial Completion will be permitted to use permanent facilities, under conditions acceptable to Owner.

B. Traffic Controls: Comply with requirements of authorities having jurisdiction.

1. Protect existing site improvements to remain including curbs, pavement, and utilities.

2. Maintain access for fire-fighting equipment and access to fire hydrants.

C. Parking: Use designated areas of Owner's existing parking areas for construction personnel.

D. Project Signs: Provide Project signs as indicated. Unauthorized signs are not permitted.

1. Identification Signs: Provide Project identification signs as indicated on Drawings.

2. Temporary Signs: Provide other signs as indicated and as required to inform public and individuals seeking entrance to Project.
a. Provide temporary, directional signs for construction personnel and visitors.

3. Maintain and touch up signs so they are legible at all times.

E. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction. Comply with progress cleaning requirements in Division 1 Section "Execution."
F. Lifts and Hoists: Provide facilities necessary for hoisting materials and personnel.

1. Truck cranes and similar devices used for hoisting materials are considered "tools and equipment" and not temporary facilities.

G. Existing Elevator Use: Use of Owner's existing elevators will be permitted, provided elevators are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore elevators to condition existing before initial use, including replacing worn cables, guide shoes, and similar items of limited life.

1. Do not load elevators beyond their rated weight capacity.

2. Provide protective coverings, barriers, devices, signs, or other procedures to protect elevator car and entrance doors and frame. If, despite such protection,

Page 674 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

TEMPORARY FACILITIES & CONTROLS 015000 - 6
elevators become damaged, engage elevator Installer to restore damaged work so no evidence remains of correction work. Return items that cannot be refinished in field to the shop, make required repairs and refinish entire unit, or provide new units as required.

H. Existing Stair Usage: Use of Owner's existing stairs will be permitted, provided stairs are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore stairs to condition existing before initial use.

1. Provide protective coverings, barriers, devices, signs, or other procedures to protect stairs and to maintain means of egress. If stairs become damaged, restore damaged areas so no evidence remains of correction work.

3.5 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other improvements at Project site and on adjacent properties, except those indicated to be removed or altered. Repair damage to existing facilities.

1. Where access to adjacent properties is required in order to affect protection of existing facilities, obtain written permission from adjacent property owner to access property for that purpose.

B. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

1. Comply with work restrictions specified in Division 1 Section "Summary." C. Site Enclosure Fence: Before construction operations begin furnish and install site enclosure fence in a manner that will prevent people from easily entering site except by entrance gates.

D. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.

E. Temporary Egress: Maintain temporary egress from existing occupied facilities as indicated and as required by authorities having jurisdiction.

F. Covered Walkway: Erect protective, covered walkway for passage of individuals through or adjacent to Project site. Coordinate with entrance gates, other facilities, and obstructions. Comply with regulations of authorities having jurisdiction.

1. Provide overhead decking, protective enclosure walls, handrails, barricades, warning signs, exit signs, lights, safe and well-drained walkways, and similar provisions for protection and safe passage.

Page 675 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

TEMPORARY FACILITIES & CONTROLS 015000 - 7

2. Paint and maintain appearance of walkway for duration of the Work.

G. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weathertight enclosure for building exterior.

1. Where heating or cooling is needed and permanent enclosure is incomplete, insulate temporary enclosures.

H. Temporary Partitions: Provide floor-to-ceiling dustproof partitions to limit dust and dirt migration and to separate areas occupied by Owner from fumes and noise.

1. Construct dustproof partitions with gypsum wallboard with joints taped on occupied side, and fire-retardant-treated plywood on construction operations side.

2. Construct dustproof partitions with two layers of 6-mil polyethylene sheet on each side. Cover floor with two layers of 6-mil polyethylene sheet, extending sheets 18 inches up the sidewalls. Overlap and tape full length of joints. Cover floor with fireretardant-treated plywood.
a. Construct vestibule and airlock at each entrance through temporary partition with not less than 48 inches between doors. Maintain water-dampened foot mats in vestibule.

3. Where fire-resistance-rated temporary partitions are indicated or are required by authorities having jurisdiction, construct partitions according to the rated assemblies.

4. Insulate partitions to control noise transmission to occupied areas.

5. Seal joints and perimeter. Equip partitions with gasketed dustproof doors and security locks where openings are required.

6. Protect air-handling equipment.

7. Provide walk-off mats at each entrance through temporary partition.

I. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses.

Comply with NFPA 241; manage fire-prevention program.

1. Prohibit smoking in construction areas. Comply with additional limits on smoking specified in other Sections.

2. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition according to requirements of authorities having jurisdiction.

3. Develop and supervise an overall fire-prevention and -protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings and information.

4. Provide temporary standpipes and hoses for fire protection. Hang hoses with a warning sign stating that hoses are for fire-protection purposes only and are not to be removed. Match hose size with outlet size and equip with suitable nozzles.

Page 676 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

TEMPORARY FACILITIES & CONTROLS 015000 - 8

3.6 OPERATION, TERMINATION, AND REMOVAL
A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses. B. Maintenance:

Maintain facilities in good operating condition until removal.

1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.

C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.

D. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.

1. Materials and facilities that constitute temporary facilities are property of Contractor. Owner reserves right to take possession of Project identification signs.

2. At Substantial Completion, repair, renovate, and clean permanent facilities used during construction period. Comply with final cleaning requirements specified in Section "Closeout Procedures."
END OF SECTION 015000

Page 677 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT REQUIREMENTS 016000 - 1
SECTION 016000 - PRODUCT REQUIREMENTS
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY
A. This Section specifies administrative and procedural requirements governing Contractor's selection of products for use in Project.

1. Multiple Prime Contracts: Provisions of this Section apply to construction activities of each prime Contractor. B. Related Requirements:

1. Division 01 Section “Allowances” for products selected under an allowance.

2. Division 01 Section “Alternates” for products selected under an alternate.

3. Division 01 Section "References" for applicable industry standards for products specified.

4. Division 01 Section "Submittal Procedures" specifies requirements for submittal of the Contractor's Construction Schedule and the Submittal Schedule.

5. Division 01 Section "Product Substitution Procedures" specifies administrative procedures for handling requests for substitutions made after award of the Contract.

1.3 DEFINITIONS
A. Products: Items obtained for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent.

B. Definitions used in this Article are not intended to change meaning of other terms used in Contract Documents, such as "specialties," "systems," "structure," "finishes," "accessories," and similar terms. Such terms such are self-explanatory and have well recognized meanings in construction industry.
a. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's published product literature that is current as of date of the Contract Documents.

Page 678 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT REQUIREMENTS 016000 - 2
b. New Products: Items that have not previously been incorporated into another project or facility. Products salvaged or recycled from other projects are not considered new products.
c. Comparable Product: Product that is demonstrated and approved by Engineer through submittal process to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.
d. "Foreign Products," as distinguished from "domestic products," are items substantially manufactured (50% or more of value) outside of United States and its possessions; or produced or supplied by entities substantially owned (more than 50%) by persons who are not citizens of nor living within United States and its possessions.

2. "Materials" are products that are substantially shaped, cut, worked, mixed, finished, refined or otherwise fabricated, processed, or installed to form part of Work.

3. "Equipment" is a product with operational parts, whether motorized or manually operated, that requires service connections such as wiring or piping.

C. Basis-of-Design Product Specification: A specification in which a single manufacturer's product is named and accompanied by the words "basis-of-design product," including make or model number or other designation. In addition to the basis-of-design product description, product attributes and characteristics may be listed to establish the significant qualities related to type, function, in-service performance and physical properties, weight, dimension, durability, visual characteristics, and other special features and requirements for purposes of evaluating comparable products of additional manufacturers named in the specification.

D. Subject to Compliance with Requirements: Where the phrase "Subject to compliance with requirements" introduces a product selection procedure in an individual Specification Section, provide products qualified under the specified product procedure.

In the event that a named product or product by a named manufacturer does not meet the other requirements of the specifications, select another named product or product from another named manufacturer that does meet the requirements of the specifications.

Submit a comparable product request, if applicable.

1.4 ACTION SUBMITTALS
A. Comparable Product Request Submittal: Submit request for consideration of each comparable product. Identify basis-of-design product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Include data to indicate compliance with the requirements specified in "Comparable Products" Article.

Page 679 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT REQUIREMENTS 016000 - 3

2. Engineer's Action: If necessary, Engineer will request additional information or documentation for evaluation within seven (7) days of receipt of a comparable product request. Engineer will notify Contractor of approval or rejection of proposed comparable product request within fifteen (15) days of receipt of request, or seven (7) days of receipt of additional information or documentation, whichever is later. a. Form of Engineer's Approval of Submittal: As specified in Section "Submittal Procedures."
b. Use product specified if Engineer does not issue a decision on use of a comparable product request within time allocated.

B. Basis-of-Design Product Specification Submittal: Comply with requirements in Section "Submittal Procedures." Show compliance with requirements.

1.5 QUALITY ASSURANCE
A. Compatibility of Options: If Contractor is given option of selecting between two or more products for use on Project, select product compatible with products previously selected, even if previously selected products were also options.

1. Each contractor is responsible for providing products and construction methods compatible with products and construction methods of other contractors.

2. If a dispute arises between contractors over concurrently selectable but incompatible products, Engineer will determine which products shall be used.

B. Identification of Products: Except for required labels and operating data, do not attach or imprint manufacturer or product names or trademarks on exposed surfaces of products or equipment that will be exposed to view in occupied spaces or on the exterior.

1. Labels: Locate required product labels and stamps on a concealed surface, or, where required for observation following installation, on a visually accessible surface that is not conspicuous.

2. Equipment Nameplates: Provide a permanent nameplate on each item of service connected or power-operated equipment. Locate on a visually accessible but inconspicuous surface. Include information essential for operation, including the following:
a. Name of product and manufacturer.
b. Model and serial number.
c. Capacity.
d. Speed.
e. Ratings.

3. See individual identification sections in Divisions 21, 22, 23, and 26 for additional identification requirements.

Page 680 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT REQUIREMENTS 016000 - 4
C. Foreign Product Limitations: Except under 1 or more of following conditions, provide domestic products, not foreign products, for inclusion in the Work:

1. No available domestic product complies with Contract Documents.

2. Domestic products that comply with Contract Document are only available at prices or terms that are substantially higher than foreign products that also comply with Contract Documents.

1.6 PRODUCT DELIVERY, STORAGE, AND HANDLING
A. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft and vandalism. Comply with manufacturer's written instructions.

B. Delivery and Handling:

1. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces.

2. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.

3. Deliver products to Project site in an undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.

4. Inspect products on delivery to determine compliance with the Contract Documents and to determine that products are undamaged and properly protected. C.

Storage:

1. Store products to allow for inspection and measurement of quantity or counting of units.

2. Store materials in a manner that will not endanger Project structure.

3. Store products that are subject to damage by the elements, under cover in a weathertight enclosure above ground, with ventilation adequate to prevent condensation.

4. Protect foam plastic from exposure to sunlight, except to extent necessary for period of installation and concealment.

5. Comply with product manufacturer's written instructions for temperature, humidity, ventilation, and weather-protection requirements for storage.

6. Protect stored products from damage and liquids from freezing.

7. Provide a secure location and enclosure at Project site for storage of materials and equipment by Owner's construction forces. Coordinate location with Owner.

Page 681 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT REQUIREMENTS 016000 - 5

1.7 PRODUCT WARRANTIES
A. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents.

1. Manufacturer's Warranty: Written warranty furnished by individual manufacturer for a particular product and specifically endorsed by manufacturer to Owner.

2. Special Warranty: Written warranty required by the Contract Documents to provide specific rights for Owner.

B. Special Warranties: Prepare a written document that contains appropriate terms and identification, ready for execution.

1. Manufacturer's Standard Form: Modified to include Project-specific information and properly executed.

2. Specified Form: When specified forms are included with the Specifications, prepare a written document using indicated form properly executed.

3. See other Sections for specific content requirements and particular requirements for submitting special warranties.

C. Submittal Time: Comply with requirements in Section "Closeout Procedures." PART 2 - PRODUCTS

2.1 PRODUCT SELECTION
A. General Product Requirements: Provide products that comply with the Contract Documents, are undamaged and, unless otherwise indicated, are new at time of installation.

1. Provide products complete with accessories, trim, finish, fasteners, and other items needed for a complete installation and indicated use and effect.

2. Standard Products: If available, and unless custom products or nonstandard options are specified, provide standard products of types that have been produced and used successfully in similar situations on other projects.

3. Owner reserves the right to limit selection to products with warranties meeting requirements of the Contract Documents.

4. Where products are accompanied by the term "as selected," Engineer will make selection.

5. Descriptive, performance, and reference standard requirements in the Specifications establish salient characteristics of products.

6. Or Equal: For products specified by name and accompanied by the term "or equal," or "or approved equal," or "or approved," comply with requirements in "Comparable Products" Article to obtain approval for use of an unnamed product.

Page 682 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT REQUIREMENTS 016000 - 6
a. Submit additional documentation required by Engineer in order to establish equivalency of proposed products. Evaluation of "or equal" product status is by the Engineer, whose determination is final. B. Product Selection Procedures:

1. Sole Product: Where Specifications name a single manufacturer and product, provide the named product that complies with requirements. Comparable products or substitutions for Contractor's convenience will not be considered. a. Sole product may be indicated by the phrase: "Subject to compliance with requirements, provide the following: …"

2. Sole Manufacturer/Source: Where Specifications name a single manufacturer or source, provide a product by the named manufacturer or source that complies with requirements. Comparable products or substitutions for Contractor's convenience will not be considered.
a. Sole manufacturer/source may be indicated by the phrase: "Subject to compliance with requirements, provide products by the following: …"

3. Limited List of Products: Where Specifications include a list of names of both manufacturers and products, provide one of the products listed that complies with requirements. Comparable products or substitutions for Contractor's convenience will not be considered unless otherwise indicated.
a. Limited list of products may be indicated by the phrase: "Subject to compliance with requirements, provide one of the following: …"

4. Non-Limited List of Products: Where Specifications include a list of names of both available manufacturers and products, provide one of the products listed, or an unnamed product, which complies with requirements.
a. Non-limited list of products is indicated by the phrase: "Subject to compliance with requirements, available products that may be incorporated in the Work include, but are not limited to, the following: …"

5. Limited List of Manufacturers: Where Specifications include a list of manufacturers' names, provide a product by one of the manufacturers listed that complies with requirements. Comparable products or substitutions for Contractor's convenience will not be considered unless otherwise indicated.
a. Limited list of manufacturers is indicated by the phrase: "Subject to compliance with requirements, provide products by one of the following: …"

6. Non-Limited List of Manufacturers: Where Specifications include a list of available manufacturers, provide a product by one of the manufacturers listed, or a product by an unnamed manufacturer, which complies with requirements. a. Non-limited list of manufacturers is indicated by the phrase: "Subject to compliance with requirements, available manufacturers whose products

Page 683 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT REQUIREMENTS 016000 - 7
may be incorporated in the Work include, but are not limited to, the following:
…"

7. Basis-of-Design Product: Where Specifications name a product, or refer to a product indicated on Drawings, and include a list of manufacturers, provide the specified or indicated product or a comparable product by one of the other named manufacturers. Drawings and Specifications indicate sizes, profiles, dimensions, and other characteristics that are based on the product named. Comply with requirements in "Comparable Products" Article for consideration of an unnamed product by one of the other named manufacturers.
a. For approval of products by unnamed manufacturers, comply with requirements in Section "Substitution Procedures" for substitutions for convenience.

C. Visual Matching Specification: Where Specifications require "match Engineer's sample," provide a product that complies with requirements and matches Engineer's sample. Engineer's decision will be final on whether a proposed product matches.

1. If no product available within specified category matches and complies with other specified requirements, comply with requirements in Section "Substitution Procedures" for proposal of product.

D. Visual Selection Specification: Where Specifications include the phrase "as selected by Engineer from manufacturer's full range" or similar phrase, select a product that complies with requirements. Engineer will select color, gloss, pattern, density, or texture from manufacturer's product line that includes both standard and premium items.

2.2 COMPARABLE PRODUCTS
A. Conditions for Consideration of Comparable Products: Engineer will consider Contractor's request for comparable product when the following conditions are satisfied.

If the following conditions are not satisfied, Engineer may return requests without action, except to record noncompliance with these requirements:

1. Evidence that proposed product does not require revisions to the Contract Documents, is consistent with the Contract Documents, will produce the indicated results, and is compatible with other portions of the Work. Detailed comparison of significant qualities of proposed product with those named in the Specifications.

Significant product qualities include attributes such as type, function, in-service performance and physical properties, weight, dimension, durability, visual characteristics, and other specific features and requirements.

2. Evidence that proposed product provides specified warranty.

3. List of similar installations for completed projects with project names and addresses and names and addresses of Engineers and owners, if requested.

4. Samples, if requested.

Page 684 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT REQUIREMENTS 016000 - 8
B. Submittal Requirements: Approval by the Engineer of Contractor's request for use of comparable product is not intended to satisfy other submittal requirements. Comply with specified submittal requirements.

PART 3 - EXECUTION

3.1 INSTALLATION OF PRODUCTS:

A. Comply with manufacturer's instructions and recommendations for installation of products in applications indicated. Anchor each product securely in place, accurately located and aligned with other Work.

1. Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.

END OF SECTION 016000

Page 685 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT SUBSTITUTION PROCEDURES 016010 - 1
SECTION 016010 - PRODUCT SUBSTITUTION PROCEDURES
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY
A. This Section specifies administrative and procedural requirements for handling requests for substitutions made after award of Contract. B. Related Requirements:

1. Division 01 Section "Allowances" for products selected under an allowance.

2. Division 01 Section "Alternates" for products selected under an alternate.

3. Division 01 Section "Reference Standards and Definitions" for applicability of industry standards to products specified

4. Division 01 Section "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

C. Engineer's policy is to reject requests for substitution unless paragraph "Substitutions" under Article "Definitions" applies. Vendors wishing inclusion in Engineer's master specification: contact Engineer for procedure.

1.3 DEFINITIONS
A. Definitions used in this Article are not intended to change or modify meaning of other terms used in Contract Documents.

B. Substitutions: Requests for changes in products, materials, equipment, and methods of construction required by Contract Documents proposed by Contractor after award of Contract are considered requests for "substitutions." Following are not considered substitutions:

1. Revisions to Contract Documents requested by Owner or Engineer.

2. Specified options of products and construction methods included in Contract Documents.

3. Contractor's determination of and compliance with governing regulations and orders issued by governing authorities.

Page 686 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT SUBSTITUTION PROCEDURES 016010 - 2

1.4 SUBMITTALS
A. Substitution Request Submittal: Requests for substitution will be considered if received within fifteen (15) days after commencement of Work. Requests received more than fifteen (15) days after commencement of Work may be considered or rejected at discretion of Engineer.

1. Submit 3 copies of each request for substitution for consideration. Submit requests on forms included at end of this Section and in accordance with procedures required for Change Order proposals.

2. Identify product, or fabrication or installation method to be replaced in each request. Include Specification Section number and title and Drawing numbers and titles. Provide complete documentation showing compliance with requirements for substitutions, and the following information, as appropriate:
a. Statement indicating why specified product or fabrication or installation method cannot be provided, if applicable.
b. Coordination of information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.
c. Detailed comparison of significant qualities of proposed substitutions with those of the Work specified. Include annotated copy of applicable Specification Section. Significant qualities may include attributes, such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified. d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable or requested. g. List of similar installations for completed projects, with project names and addresses as well as names and addresses of architects and owners. h. Material test reports from a qualified testing agency, indicating and interpreting test results for compliance with requirements indicated. i. Research reports evidencing compliance with building code in effect for Project.
j. Detailed comparison of Contractor's construction schedule using proposed substitutions with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
k. Cost information, including a proposal of change, if any, in the Contract Sum. l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents, except as indicated in substitution request, is compatible with related materials and is appropriate for applications indicated.

Page 687 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT SUBSTITUTION PROCEDURES 016010 - 3
m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. Engineer's Action: If necessary, Engineer will request additional information or documentation for evaluation within seven (7) days of receipt of a request for substitution. Engineer will notify Contractor of acceptance or rejection of proposed substitution within fifteen (15) days of receipt of request, or seven (7) days of receipt of additional information or documentation, whichever is later. a. Forms of Acceptance: Change Order, Construction Change Directive, or Engineer's Supplemental Instructions for minor changes in the Work. b. Use product specified if Engineer does not issue a decision on use of a proposed substitution within time allocated.

1.5 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.

1.6 PROCEDURES
A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.

1.7 SUBSTITUTIONS
A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than fifteen (15) days prior to time required for preparation and review of related submittals.

1. Conditions: Engineer will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Engineer will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution is consistent with the Contract Documents and will produce indicated results.
b. Substitution request is fully documented and properly submitted. c. Requested substitution will not adversely affect Contractor's construction schedule.
d. Requested substitution has received necessary approvals of authorities having jurisdiction.
e. Requested substitution is compatible with other portions of the Work.

Page 688 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT SUBSTITUTION PROCEDURES 016010 - 4
f. Requested substitution has been coordinated with other portions of the Work.
g. Requested substitution provides specified warranty.
h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: Engineer will consider requests for substitution if received within fifteen (15) days after commencement of the Work. Requests received after that time may be considered or rejected at discretion of Engineer.

1. Conditions: Engineer will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Engineer will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Engineer for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations. b. Requested substitution does not require extensive revisions to the Contract Documents.
c. Requested substitution is consistent with the Contract Documents and will produce indicated results.
d. Substitution request is fully documented and properly submitted. e. Requested substitution will not adversely affect Contractor's construction schedule.
f. Requested substitution has received necessary approvals of authorities having jurisdiction.
g. Requested substitution is compatible with other portions of the Work. h. Requested substitution has been coordinated with other portions of the Work.
i. Requested substitution provides specified warranty.
j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

C. Contractor's submittal and Engineer's acceptance of Shop Drawings, Product Data or Samples that relate to construction activities not complying with Contract Documents does not constitute an acceptable or valid request for substitution, nor does it constitute approval.

PART 2 - PRODUCTS (NOT APPLICABLE)

Page 689 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT SUBSTITUTION PROCEDURES 016010 - 5
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 016010

REQUEST FOR SUBSTITUTION
To:

Attention:

From:

Name of Company
Address
City, State, Zip Code
Phone
Fully answer all information requested below. Failure to answer any item may cause rejection of request for substitution. If requested by Engineer, submit information about manufacturer and vendor history, financial stability, distribution and support systems. Use one form for each product requested. Only first product listed will be considered on forms with more than one product listed.

Specification Section Number:

Drawing Number:

Para Number: Detail Number:

Specified Product:

Proposed Substitution:

Answer the following questions. Attach an explanation sheet on your company's letterhead when required.

Page 690 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT SUBSTITUTION PROCEDURES 016010 - 6
Does the proposed substitution affect dimensions indicated on Drawings? No Yes (If yes, explain below).

Does the proposed substitution require changes in Drawings and/or design or installation changes?
No Yes

If yes, is the cost of these changes included in the proposed amount? No Yes Does the proposed substitution affect other trades? No Yes

(If yes, explain who and how)

Page 691 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT SUBSTITUTION PROCEDURES 016010 - 7
If the proposed product does affect the work of other trades, has the cost impact on their work been included in the price of the proposed substitution? No Yes

Does the proposed product's guarantee differ from that of the specified product's? No Yes (If yes, explain below).

Why is this proposal for substitution being submitted? List reasons below.

Attach a listing of 3 projects using proposed substitution completed within the past 5 yrs in geographic and climatic region of Project. One of applications shall have been in service for at least 3 yrs.

Page 692 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PRODUCT SUBSTITUTION PROCEDURES 016010 - 8
Attach product data/brochures and Vendor Qualification Form for the specified and substitute product.

Undersigned has examined Construction Documents, is familiar with specified product, understands indicated application of product, and understands design intent of Engineer.

Undersigned states that proposed substitution complies with Construction Documents and will perform at least equally to specified product within limitations stated above. Undersigned accepts responsibility for coordinating application and installation of proposed substitution and waives all claims for additional costs resulting from incorporation of proposed substitution into Project or its subsequent failure to perform according to specified requirements.

Submitted By:

Typed Signature
Date:

Page 693 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

EXECUTION 017300 - 1
SECTION 017300 - EXECUTION
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY
A. This Section includes general procedural requirements governing execution of the Work including, but not limited to, the following:

1. Installation of the Work.

2. Cutting and patching.

3. Progress cleaning.

4. Protection of installed construction. B. Related Requirements:

1. Division 01 Section "Project Management and Coordination" for procedures for coordinating field engineering with other construction activities.

2. Division 01 Section "Submittal Procedures" for submitting surveys.

3. Division 01 Section "Closeout Procedures" for submitting final property survey with Project Record Documents, recording of Owner-accepted deviations from indicated lines and levels, and final cleaning.

4. Division 02 Section “Work Items” for coordinating restoration construction activities to maintain Owner’s operations during construction.

1.3 DEFINITIONS
A. Cutting: Removal of in-place construction necessary to permit installation or performance of subsequent work.

B. Patching: Fitting and repair work required to restore construction to original conditions after installation of subsequent work.

1.4 PREINSTALLATION MEETINGS
A. Cutting and Patching Conference: Conduct conference at Project site.

1. Prior to commencing work requiring cutting and patching, review extent of cutting and patching anticipated and examine procedures for ensuring satisfactory result

Page 694 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

EXECUTION 017300 - 2
from cutting and patching work. Require representatives of each entity directly concerned with cutting and patching to attend, including the following:
a. Contractor's superintendent.
b. Trade supervisor responsible for cutting operations. c. Trade supervisor(s) responsible for patching of each type of substrate. d. Mechanical, electrical, and utilities subcontractors' supervisors, to the extent each trade is affecting by cutting and patching operations.

2. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding.

1.5 INFORMATIONAL SUBMITTALS
A. Cutting and Patching Plan: Submit plan describing procedures at least ten (10) days prior to the time cutting and patching will be performed. Include the following information:

1. Extent: Describe reason for and extent of each occurrence of cutting and patching.

2. Changes to In-Place Construction: Describe anticipated results. Include changes to structural elements and operating components as well as changes in building appearance and other significant visual elements.

3. Products: List products to be used for patching and firms or entities that will perform patching work.

4. Dates: Indicate when cutting and patching will be performed.

5. Utilities and Mechanical and Electrical Systems: List services and systems that cutting and patching procedures will disturb or affect. List services and systems that will be relocated and those that will be temporarily out of service. Indicate length of time permanent services and systems will be disrupted. a. Include description of provisions for temporary services and systems during interruption of permanent services and systems.

B. Landfill Receipts: Submit copy of receipts issued by a landfill facility, licensed to accept hazardous materials, for hazardous waste disposal.

1.6 QUALITY ASSURANCE
A. Cutting and Patching: Comply with requirements for and limitations on cutting and patching of construction elements.

1. Structural Elements: When cutting and patching structural elements, notify Engineer of locations and details of cutting and await directions from Engineer before proceeding. Shore, brace, and support structural elements during cutting and patching. Do not cut and patch structural elements in a manner that could change their load-carrying capacity or increase deflection.

2. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as

Page 695 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

EXECUTION 017300 - 3
intended or that results in increased maintenance or decreased operational life or safety.

3. Other Construction Elements: Do not cut and patch other construction elements or components in a manner that could change their load-carrying capacity, that results in reducing their capacity to perform as intended, or that results in increased maintenance or decreased operational life or safety.

4. Visual Elements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch exposed construction in a manner that would, in Engineer's opinion, reduce the building's aesthetic qualities. Remove and replace construction that has been cut and patched in a visually unsatisfactory manner.

B. Manufacturer's Installation Instructions: Obtain and maintain on-site manufacturer's written recommendations and instructions for installation of products and equipment.

PART 2 - PRODUCTS

2.1 MATERIALS
A. General: Comply with requirements specified in other Sections.

1. For projects requiring compliance with sustainable design and construction practices and procedures, use products for patching that comply with sustainable design requirements.

B. In-Place Materials: Use materials for patching identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible.

1. If identical materials are unavailable or cannot be used, use materials that, when installed, will provide a match acceptable to Engineer for the visual and functional performance of in-place materials.

PART 3 - EXECUTION

3.1 EXAMINATION
A. Existing Conditions: The existence and location of site improvements, utilities, and other construction indicated as existing are not guaranteed. Before beginning work, investigate and verify the existence and location of mechanical and electrical systems and other construction affecting the Work.

B. Examination and Acceptance of Conditions: Before proceeding with each component of the Work, examine substrates, areas, and conditions, with Installer or Applicator present

Page 696 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

EXECUTION 017300 - 4
where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations.

1. Examine roughing-in for mechanical and electrical systems to verify actual locations of connections before equipment and fixture installation.

2. Examine walls, floors, and roofs for suitable conditions where products and systems are to be installed.

3. Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers.

C. Written Report: Where a written report listing conditions detrimental to performance of the Work is required by other Sections, include the following:

1. Description of the Work.

2. List of detrimental conditions, including substrates.

3. List of unacceptable installation tolerances.

4. Recommended corrections.

D. Proceed with installation only after unsatisfactory conditions have been corrected.

Proceeding with the Work indicates acceptance of surfaces and conditions.

3.2 PREPARATION
A. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Engineer and Owner not less than two days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Engineer’s and Owner’s written permission.

B. Field Measurements: Take field measurements as required to fit the Work properly.

Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work.

C. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.

D. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents caused by differing field conditions outside the control of Contractor, submit a request for information to Engineer according to requirements in Section 013100 "Project Management and Coordination."

Page 697 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

EXECUTION 017300 - 5

3.3 INSTALLATION
A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

1. Make vertical work plumb and make horizontal work level.

2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.

3. Conceal pipes, ducts, and wiring in finished areas, unless otherwise indicated.

4. Maintain minimum headroom clearance of eight (8) feet occupied and unoccupied spaces.

B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.

C. Install products at the time and under conditions that will ensure the best possible results.

Maintain conditions required for product performance until Substantial Completion.

D. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy.

E. Tools and Equipment: Where possible, select tools or equipment that minimize production of excessive noise levels
F. Attachment: Provide blocking and attachment plates and anchors and fasteners of adequate size and number to securely anchor each component in place, accurately located and aligned with other portions of the Work. Where size and type of attachments are not indicated, verify size and type required for load conditions.

1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by Engineer.

2. Allow for building movement, including thermal expansion and contraction.

3. Coordinate installation of anchorages. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.

G. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.

H. Repair or remove and replace damaged, defective, or nonconforming Work.

1. Comply with Section "Closeout Procedures" for repairing or removing and replacing defective Work.

Page 698 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

EXECUTION 017300 - 6

3.4 CUTTING AND PATCHING
A. Cutting and Patching, General: Employ skilled workers to perform cutting and patching.

Proceed with cutting and patching at the earliest feasible time, and complete without delay.

1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.

B. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during installation or cutting and patching operations, by methods and with materials so as not to void existing warranties.

C. Temporary Support: Provide temporary support of work to be cut.

D. Protection: Protect in-place construction during cutting and patching to prevent damage.

Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.

E. Adjacent Occupied Areas: Where interference with use of adjoining areas or interruption of free passage to adjoining areas is unavoidable, coordinate cutting and patching according to requirements in Section 011000 "Summary."
F. Existing Utility Services and Mechanical/Electrical Systems: Where existing services/systems are required to be removed, relocated, or abandoned, bypass such services/systems before cutting to prevent interruption to occupied areas.

G. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations.

1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots neatly to minimum size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.

2. Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces.

3. Concrete and Masonry: Cut using a cutting machine, such as an abrasive saw or a diamond-core drill.

4. Mechanical and Electrical Services: Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after cutting.

5. Proceed with patching after construction operations requiring cutting are complete.

H. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other work. Patch with durable seams that are as

Page 699 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

EXECUTION 017300 - 7
invisible as practicable. Provide materials and comply with installation requirements specified in other Sections, where applicable.

1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate physical integrity of installation.

2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will minimize evidence of patching and refinishing.
a. Clean piping, conduit, and similar features before applying paint or other finishing materials.
b. Restore damaged pipe covering to its original condition.

3. Floors and Walls: Where walls or partitions that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space.

Provide an even surface of uniform finish, color, texture, and appearance. Remove in-place floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.
a. Where patching occurs in a painted surface, prepare substrate and apply primer and intermediate paint coats appropriate for substrate over the patch, and apply final paint coat over entire unbroken surface containing the patch.

Provide additional coats until patch blends with adjacent surfaces.

4. Ceilings: Patch, repair, or rehang in-place ceilings as necessary to provide an even-plane surface of uniform appearance.

5. Exterior Building Enclosure: Patch components in a manner that restores enclosure to a weathertight condition and ensures thermal and moisture integrity of building enclosure.

I. Cleaning: Clean areas and spaces where cutting and patching are performed. Remove paint, mortar, oils, putty, and similar materials from adjacent finished surfaces.

3.5 PROGRESS CLEANING
A. General: Clean Project site and work areas daily, including common areas. Coordinate progress cleaning for joint-use areas where more than one installer has worked. Enforce requirements strictly. Dispose of materials lawfully.

1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.

2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C).

3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.

4. Coordinate progress cleaning for joint-use areas where Contractor and other contractors are working concurrently.

Page 700 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

EXECUTION 017300 - 8
B. Site: Maintain Project site free of waste materials and debris.

C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.

1. Remove liquid spills promptly.

2. Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area, as appropriate.

D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.

E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space.

F. Exposed Surfaces: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.

G. Cutting and Patching: Clean areas and spaces where cutting and patching are performed. Completely remove paint, mortar, oils, putty, and similar materials.

1. Thoroughly clean piping, conduit, and similar features before applying paint or other finishing materials. Restore damaged pipe covering to its original condition.

H. Waste Disposal: Do not bury or burn waste materials on-site. Do not wash waste materials down sewers or into waterways. Comply with waste disposal requirements in Section 015000 "Temporary Facilities and Controls."
I. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.

J. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

K. Limiting Exposures: Supervise construction operations to assure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.

3.6 PROTECTION OF INSTALLED CONSTRUCTION
A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.

Page 701 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

EXECUTION 017300 - 9
B. Protection of Existing Items: Provide protection and ensure that existing items to remain undisturbed by construction are maintained in condition that existed at commencement of the Work.

C. Comply with manufacturer's written instructions for temperature and relative humidity.

END OF SECTION 017300

Page 702 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CLOSEOUT PROCEDURES 017700 - 1
SECTION 017700 - CLOSEOUT PROCEDURES
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY
A. This Section specifies administrative and procedural requirements for project closeout, including but not limited to:

1. Substantial Completion procedures.

2. Final completion procedures.

3. Warranties.

4. Final cleaning.

5. Repair of the Work. B. Related Requirements:

1. Division 01 Section "Project Record Documents" for submitting Record Drawings, Record Specifications, and Record Product Data.

2. Closeout requirements for specific construction activities are included in appropriate Sections in Divisions 02 through 14, 21-27, and 31-33.

1.3 ACTION SUBMITTALS
A. Product Data: For each type of cleaning agent.

B. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion.

C. Certified List of Incomplete Items: Final submittal at final completion.

1.4 CLOSEOUT SUBMITTALS
A. Certificates of Release: From authorities having jurisdiction.

1.5 MAINTENANCE MATERIAL SUBMITTALS
A. Schedule of Maintenance Material Items: For maintenance material submittal items specified in other Sections.

Page 703 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CLOSEOUT PROCEDURES 017700 - 2

1.6 SUBSTANTIAL COMPLETION PROCEDURES
A. Contractor's List of Incomplete Items: Prepare and submit a list of items to be completed and corrected (Contractor's punch list), indicating the value of each item on the list and reasons why the Work is incomplete.

B. Submittals Prior to Substantial Completion: Complete the following a minimum of ten (10) days prior to requesting inspection for determining date of Substantial Completion.

List items below that are incomplete at time of request.

1. Certificates of Release: Obtain and submit releases from authorities having jurisdiction permitting Owner unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases.

2. Submit closeout submittals specified in other Division 01 Sections, including project record documents, operation and maintenance manuals, damage or settlement surveys, property surveys, and similar final record information.

3. Submit closeout submittals specified in individual Sections, including specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents.

4. Submit maintenance material submittals specified in individual Sections, including tools, spare parts, extra materials, and similar items, and deliver to location designated by Engineer. Label with manufacturer's name and model number.

5. Submit testing, adjusting, and balancing records.

C. Procedures Prior to Substantial Completion: Complete the following a minimum of ten (10) days prior to requesting inspection for determining date of Substantial Completion.

List items below that are incomplete at time of request.

1. Complete startup and testing of systems and equipment.

2. Perform preventive maintenance on equipment used prior to Substantial Completion.

3. Participate with Owner in conducting inspection and walkthrough with local emergency responders.

4. Terminate and remove temporary facilities from Project site, along with mockups, construction tools, and similar elements.

5. Complete final cleaning requirements.

6. Touch up paint and otherwise repair and restore marred exposed finishes to eliminate visual defects.

D. Inspection: Submit a written request for inspection to determine Substantial Completion a minimum of ten (10) days prior to date the Work will be completed and ready for final inspection and tests. On receipt of request, Engineer will either proceed with inspection or notify Contractor of unfulfilled requirements. Engineer will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by Engineer, that must be completed or corrected before certificate will be issued.

Page 704 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CLOSEOUT PROCEDURES 017700 - 3

1. Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for final completion.

1.7 FINAL COMPLETION PROCEDURES
A. Submittals Prior to Final Completion: Before requesting final inspection for determining final completion, complete the following:

1. Submit a final Application for Payment according to Section 012900 "Payment Procedures."

2. Certified List of Incomplete Items: Submit certified copy of Engineer's Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by Engineer. Certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.

3. Certificate of Insurance: Submit evidence of final, continuing insurance coverage complying with insurance requirements.

4. Submit pest-control final inspection report.

5. Submit final completion photographic documentation.

B. Inspection: Submit a written request for final inspection to determine acceptance a minimum of 10 days prior to date the work will be completed and ready for final inspection and tests. On receipt of request, Engineer will either proceed with inspection or notify Contractor of unfulfilled requirements. Engineer will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.
a. Engineer will provide one repeat inspection under its contract with Owner.

Subsequent inspections shall be at Contractor's expense. b. Upon completion of reinspection, Engineer will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued. c. If necessary, reinspection will be repeated.

1.8 LIST OF INCOMPLETE ITEMS (PUNCH LIST)
A. Organization of List: Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.

Page 705 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CLOSEOUT PROCEDURES 017700 - 4

1. Organize list of spaces in sequential order, starting with exterior areas first and proceeding from lowest floor to highest floor.

2. Organize items applying to each space by major element, including categories for ceiling, individual walls, floors, equipment, and building systems.

3. Include the following information at the top of each page:
a. Project name.
b. Date.
c. Name of Engineer.
d. Name of Contractor.
e. Page number.

4. Submit list of incomplete items in the following format:
a. PDF electronic file. Engineer will return annotated file.

1.9 SUBMITTAL OF PROJECT WARRANTIES
A. Time of Submittal: Submit written warranties on request of Engineer for designated portions of the Work where warranties are indicated to commence on dates other than date of Substantial Completion, or when delay in submittal of warranties might limit Owner's rights under warranty.

B. Partial Occupancy: Submit properly executed warranties within fifteen (15) days of completion of designated portions of the Work that are completed and occupied or used by Owner during construction period by separate agreement with Contractor.

C. Organize warranty documents into an orderly sequence based on the table of contents of Project Manual.

D. Warranty Electronic File: Provide warranties and bonds in PDF format. Assemble complete warranty and bond submittal package into a single electronic PDF file with bookmarks enabling navigation to each item. Provide bookmarked table of contents at beginning of document.

E. Warranties in Paper Form:

1. Bind warranties and bonds in heavy-duty, three-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch paper.

2. Provide heavy paper dividers with plastic-covered tabs for each separate warranty.

Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.

3. Identify each binder on the front and spine with the typed or printed title "WARRANTIES," Project name, and name of Contractor.

Page 706 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CLOSEOUT PROCEDURES 017700 - 5
F. Provide additional copies of each warranty to include in operation and maintenance manuals.

PART 2 - PRODUCTS (NOT APPLICABLE).

2.1 MATERIALS
A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

1. Use cleaning products that comply with Green Seal's GS-37, or if GS-37 is not applicable, use products that comply with the California Code of Regulations maximum allowable VOC levels.

PART 3 - EXECUTION

3.1 FINAL CLEANING
A. General: Perform final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program. Comply with manufacturer's written instructions.

1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a designated portion of Project:
a. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.
b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.
c. Rake grounds that are not planted, mulched, or paved to a smooth, eventextured surface.
d. Remove tools, construction equipment, machinery, and surplus material from Project site.
e. Remove snow and ice to provide safe access to building. f. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid

Page 707 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CLOSEOUT PROCEDURES 017700 - 6
disturbing natural weathering of exterior surfaces. Restore reflective surfaces to their original condition.
g. Remove debris and surface dust from limited access spaces, including roofs, plenums, shafts, trenches, equipment vaults, manholes, attics, and similar spaces.
h. Sweep concrete floors broom clean in unoccupied spaces. i. Clean transparent materials, including mirrors and glass in doors and windows. Remove glazing compounds and other noticeable, visionobscuring materials. Polish mirrors and glass, taking care not to scratch surfaces. j. Remove labels that are not permanent.
k. Wipe surfaces of mechanical and electrical equipment and similar equipment. Remove excess lubrication, paint and mortar droppings, and other foreign substances.
l. Clean plumbing fixtures to a sanitary condition, free of stains, including stains resulting from water exposure.
m. Replace disposable air filters and clean permanent air filters. Clean exposed surfaces of diffusers, registers, and grills.
n. Clean light fixtures, lamps, globes, and reflectors to function with full efficiency.
o. Leave Project clean and ready for occupancy.

C. Construction Waste Disposal: Comply with waste disposal requirements in Division 01 Section "Temporary Facilities and Controls."

3.2 REPAIR OF THE WORK
A. Complete repair and restoration operations before requesting inspection for determination of Substantial Completion.

B. Repair, or remove and replace, defective construction. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment. Where damaged or worn items cannot be repaired or restored, provide replacements. Remove and replace operating components that cannot be repaired. Restore damaged construction and permanent facilities used during construction to specified condition.

1. Remove and replace chipped, scratched, and broken glass, reflective surfaces, and other damaged transparent materials.

2. Touch up and otherwise repair and restore marred or exposed finishes and surfaces. Replace finishes and surfaces that that already show evidence of repair or restoration.
a. Do not paint over "UL" and other required labels and identification, including mechanical and electrical nameplates. Remove paint applied to required labels and identification.

Page 708 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CLOSEOUT PROCEDURES 017700 - 7

3. Replace parts subject to operating conditions during construction that may impede operation or reduce longevity.

4. Replace burned-out bulbs, bulbs noticeably dimmed by hours of use, and defective and noisy starters in fluorescent and mercury vapor fixtures to comply with requirements for new fixtures.

END OF SECTION 017700

Page 709 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PROJECT RECORD DOCUMENTS 017839-1
SECTION 017839 - PROJECT RECORD DOCUMENTS
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY
A. Section includes administrative and procedural requirements for Project Record Documents, including the following:

1. Record Drawings and Work Item Unit Quantity Drawings.

2. Record Specifications.

3. Record Product Data. B. Related Requirements:

1. Section "Closeout Procedures" for general closeout procedures and maintenance manual requirements.

2. Divisions 02 through 5,7, 9, 22 26, Sections for specific requirements for Project Record Documents of products in those Sections.

1.3 CLOSEOUT SUBMITTALS
A. Record Drawings: Comply with the following:

1. Number of Copies: Submit PDF electronic files of marked-up scanned record prints and one (1) file prints.

B. Record Specifications: Submit annotated PDF electronic files of Project's Specifications, including addenda and contract modifications.

C. Record Product Data: Submit annotated PDF electronic files and directories of each submittal.

1. Where record Product Data are required as part of operation and maintenance manuals, submit duplicate marked-up Product Data as a component of manual.

D. Reports: Submit written report weekly indicating items incorporated into project record documents concurrent with progress of the Work, including revisions, concealed conditions, field changes, product selections, and other notations incorporated.

Page 710 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PROJECT RECORD DOCUMENTS 017839-2

1.4 RECORD DRAWINGS
A. Record Prints: Maintain one set of marked-up paper copies of the Contract Drawings and Shop Drawings, incorporating new and revised drawings as modifications are issued.

1. Preparation: Mark record prints to show the actual installation and unit quantity where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to provide information for preparation of corresponding markedup record prints.
a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.
b. Accurately record information in an acceptable drawing technique. c. Record data as soon as possible after obtaining it.
d. Record and check the markup before enclosing concealed installations. e. Cross-reference record prints to corresponding
photographic documentation.

2. Content: Types of items requiring marking include, but are not limited to, the following:
a. Dimensional changes to Drawings.
b. Revisions to details shown on Drawings.
c. Locations of concealed internal utilities.
d. Changes made following Engineer/Architect's written orders. e. Details not on the original Contract Drawings.
f. Field records for variable and concealed conditions. g. Record information on the Work that is shown only schematically. h. Actual location and quantity of unit price items of the Work.

3. Mark the Contract Drawings and Shop Drawings completely and accurately. Use personnel proficient at recording graphic information in production of marked-up record prints.

4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.

5. Mark important additional information that was either shown schematically or omitted from original Drawings.

6. Note Construction Change Directive numbers, alternate numbers, Change Order numbers, and similar identification, where applicable.

B. Format: Identify and date each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location.

1. Record Prints: Organize record prints into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.

Page 711 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PROJECT RECORD DOCUMENTS 017839-3

2. Format: Annotated PDF electronic file with comment function enabled.

3. Record Digital Data Files: Organize digital data information into separate electronic files that correspond to each sheet of the Contract Drawings. Name each file with the sheet identification. Include identification in each digital data file.

4. Identification: As follows:
a. Project name.
b. Date.
c. Designation "PROJECT RECORD DRAWINGS."
d. Name of Engineer/Architect.
e. Name of Contractor.

1.5 RECORD SPECIFICATIONS
A. Preparation: Mark Specifications to indicate the actual product installation where installation varies from that indicated in Specifications, addenda, and contract modifications.

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Mark copy with the proprietary name and model number of products, materials, and equipment furnished, including substitutions and product options selected.

3. Record the name of manufacturer, supplier, Installer, and other information necessary to provide a record of selections made.

4. For each principal product, indicate whether Record Product Data has been submitted in operation and maintenance manuals instead of submitted as Record Product Data.

5. Note related Change Orders, Record Drawings, and record Product Data, and record Drawings where applicable.

B. Format: Submit record Specifications as annotated PDF electronic file.

1.6 RECORD PRODUCT DATA
A. Recording: Maintain one copy of each submittal during the construction period for project record document purposes. Post changes and revisions to project record documents as they occur; do not wait until end of Project.

B. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal.

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation.

Page 712 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

PROJECT RECORD DOCUMENTS 017839-4

1.7 MISCELLANEOUS RECORD SUBMITTALS
A. Assemble miscellaneous records required by other Specification Sections for miscellaneous record keeping and submittal in connection with actual performance of the Work. Bind or file miscellaneous records and identify each, ready for continued use and reference.

B. Format: Submit miscellaneous record submittals as PDF electronic file.

1. Include miscellaneous record submittals directory organized by Specification Section number and title, electronically linked to each item of miscellaneous record submittals.

PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 017839

Page 713 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 1
SECTION 020010 - WORK ITEMS
PART 1 - GENERAL

1.1 RELATED DOCUMENT
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Divisions 1 – 9 Specification Sections apply to this Section.

PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION
WI 1.0 GENERAL REQUIREMENTS
A. Scope of Work

1. Work consists of performing all tasks, specifically required and incidental, which are not identified under separate Work Item designation, but necessary to perform the work identified in this project. This work includes, but is not limited to the following items:

WI 1.1 - Mobilization
WI 1.2 - Concrete Formwork
WI 1.3 - Concrete Shores and Reshores
WI 1.4 - Concrete Reinforcement
WI 1.5 – Overhead Protection/Temporary Signage/Traffic Control WI 1.1 PROJECT MOBILIZATION
A. Scope of Work

1. Work consists of coordinating, scheduling, obtaining and assembling at construction site all equipment, materials, permits, supplies, manpower and other essentials and incidentals necessary to perform Work defined in this Contract.

Payment of lump sum amount for mobilization shall be according to following schedule and shall be based on percentage of original contract amount earned.

B. Materials

1. None
C. Execution

Page 714 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 2

1. At execution of agreement by all parties, mobilization payment shall not be more than 25% of mobilization lump sum amount.

2. When billing amount earned is greater than 10% but less than 25% of original contract amount, total payment for mobilization shall not be more than 50% of mobilization lump sum amount.

3. When billing amount earned is equal to or greater than 25% but less than 50% of original contract amount, total payment for mobilization shall not be more than 75% of mobilization lump sum amount.

4. When billing amount earned is equal to or greater than 50% of original contract amount, total payment for mobilization shall be 100% of mobilization lump sum amount.

WI 1.2 CONCRETE FORMWORK
A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision, and incidentals necessary to install formwork as required for cast-in-place concrete.

B. Materials

1. Forms for Exposed Finish Concrete: Plywood, metal, metal-framed plywood faced, or other acceptable panel-type materials, to provide continuous, straight, smooth, exposed surfaces. Furnish in largest practicable sizes to minimize number of joints and to conform to joint system shown on Drawings. a. Use overlaid plywood complying with U.S. Product Standard PS-1 "A-C or B-B High Density Overlaid Concrete Form," Class I
b. Use plywood complying with U.S. Product Standard PS-1 "B-B (Concrete Form) Plywood," Class I, Exterior Grade or better, mill-oiled and edgesealed, with each piece bearing legible inspection trademark.

2. Forms for Unexposed Finish Concrete: Plywood, lumber, metal, or other acceptable material. Provide lumber dressed on at least 2 edges and one side for tight fit.

3. Form Coatings: Provide commercial formulation form-coating compounds with a maximum VOC meeting local requirements that will not bond with, stain, or adversely affect concrete surfaces and will not impair subsequent treatments of concrete surfaces, including but not limited to water-curing, curing compound, stains, or paints.

4. Form Ties: Factory-fabricated, adjustable-length, removable or snap-off metal form ties, designed to prevent form deflection and to prevent spalling concrete upon removal. Provide units that will leave no metal closer than 1.5 in. to exposed surface.
a. Provide ties that, when removed, will leave holes not larger than 1.0 in.

Page 715 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 3
diameter in concrete surface.

5. Shores:
a. Nail Ellis clamps, if used with wood shores, to shores with minimum of two nails to prevent slipping.
b. Wedges: Hardwood or steel. Softwood wedges prohibited.

C. Execution

1. Work shall conform to requirements of latest edition of ACI 301 “Standard Specifications for Structural Concrete,” ACI 302.1 R “Guide for Concrete Floor Slab Construction,” ACI 318 “Building Code Requirements for Reinforced Concrete,” and ACI 347 “Recommended Practice for Concrete Formwork” except as modified by the following paragraphs.

2. Store all formwork and formwork materials clear of ground, protected, so as to preclude damage.

3. Construct forms to sizes, shapes, lines, and dimensions shown and to obtain accurate alignment, location, grades, level, and plumb work in finished structures.

Provide for openings, offsets, sinkages, keyways, recesses, moldings, rustications, reglets, chamfers, blocking, screeds, bulkheads, anchorages and inserts, and other features required in work. Use selected materials to obtain required finishes. Solidly butt joints and provide backup at joints to prevent leakage of cement paste.

4. Fabricate forms for easy removal without hammering or prying against concrete surfaces. Provide crush plates or wrecking plates where stripping may damage cast concrete surfaces. Provide top forms for inclined surfaces where slope is too steep to place concrete with bottom forms only. Kerf wood inserts for forming keyways, reglets, recesses, and the like, for easy removal.

5. Provide temporary openings where interior area of formwork is inaccessible for cleanout, for inspection before concrete placement, and for placement of concrete.

Securely brace temporary openings and set tightly to forms to prevent loss of concrete mortar. Locate temporary openings in forms at inconspicuous locations.

6. Chamfer exposed corners and edges as indicated, using wood, metal, PVC, or rubber chamfer strips fabricated to produce uniform smooth lines and tight edge joints.

7. Provisions for Other Trades: Provide openings in concrete formwork to accommodate work of other trades. Determine size and location of openings, recesses, and chases from trades providing such items. Accurately place and securely support items built into forms.

8. Cleaning and Tightening: Thoroughly clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust, dirt, or other debris just before concrete is placed. Retighten forms and bracing before concrete placement as required to prevent mortar leaks and maintain proper alignment.

9. Set edge forms or bulkheads and intermediate screed strips for slabs to obtain required elevations and contours in finished slab surface. Provide and secure units sufficiently strong to support types of screed strips by use of strike-off templates or accepted compacting type screeds.

Page 716 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 4

10. Coat contact surfaces of forms with accepted, nonresidual, low-VOC form-coating compound before reinforcement is placed.

11. Coat steel forms with non-staining, rust-preventive form oil or otherwise protect against rusting. Rust-stained steel formwork not acceptable.

12. For post-tensioned concrete, formwork shall remain in place until post-tensioning has been completed. Do not place additional loads on structure until concrete has been properly reshored.

13. For non-post-tensioned concrete, formwork shall remain in place until concrete has reached minimum two-thirds of 28-day strength. Do not place additional loads on structure until concrete has been properly reshored.

14. Clean and repair surfaces of forms to be re-used in Work. Split, frayed, delaminated or otherwise damaged form facing material will not be acceptable for exposed surfaces. Apply new form coating compound as specified for new formwork.

15. When forms are extended for successive concrete placement, thoroughly clean surfaces, remove fins and laitance, and tighten forms to close joints. Align and secure joint to avoid offsets. Do not use "patched" forms for exposed concrete surfaces, except as acceptable to Engineer/Architect.

WI 1.3 CONCRETE SHORES AND RESHORES
A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision, and incidentals necessary to install temporary shoring and to maintain shores in place until Work requiring shores is complete and associated concrete has properly cured.

B. Materials

1. Shores shall be steel, rated at a minimum allowable load of 4,500 lb at 12 ft extension or steel shoring towers rated at a minimum allowable load of 40,000 lbs per four leg tower (based on two 20,000 lb crossed braced frames.).

C. Execution

1. Comply with ACI 301 and ACI 347 for shoring and reshoring in multi-story construction, except as modified in this Section.

2. For purpose of calculations: Construction Load = 50 psf; Dead Load varies throughout the structure. Contractor and Contractor’s Engineer are responsible for calculating the dead load for shoring at each location.

3. Shore/reshore load limits may be adjusted after conducting calculation analysis for specific project conditions. check bearing [aci 318] and punching shear [aci 318].

4. Shore/Reshore loads on the structure shall not exceed 40 psf distributed load on the slab, and concentrated loads shall not exceed posted wheel loads or 2,000

Page 717 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 5
lbs., whichever is less. Concentrated bearing pressures shall not exceed 1,200 psi.

5. Shore/Reshore loads on concrete slab-on-grade shall be distributed by steel grillage or timber grillage so as not to exceed soil bearing capacity or 1,500 psf, whichever is smaller.

6. Shore/Reshore loads shall be distributed horizontally and/or distributed to more than one level to meet shore/reshore load limitations.

7. Shore/Reshore loads shall be distributed to multiple framing members (beams/joists/double tee stems) and extend beyond the immediate work area to ensure proper distribution of loads throughout the structure.

8. Prior to installation of shores, Contractor shall submit shoring scheme prepared and sealed by Licensed Structural Engineer in Massachusetts.

9. Engineer/Architect will review shoring scheme for general conformance to requirements stated herein. If it does not conform, Contractor will be informed to resubmit another shoring scheme.

10. Remove shores and reshore in planned sequence to avoid damage to partially cured concrete. Locate and provide adequate reshoring to safely support Work without excessive stress or deflection.

11. Keep reshores in place as required until heavy loads due to construction operations have been removed.

12. If during construction, modifications are necessary to accommodate other trades, revise and resubmit erection plan to Engineer/Architect for review.

WI 1.4 CONCRETE REINFORCEMENT
A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision, and incidentals necessary to fabricate and install all mild steel reinforcement and epoxy coated reinforcement.

B. Materials

1. Reinforcement materials shall be as specified in ACI 301 “Standard Specifications for Structural Concrete.”

2. Welded wire reinforcement: provide mats only. Roll stock prohibited.

3. Epoxy Coating Materials for Reinforcement: ASTM A775 and A884:

4. Supplier shall be certified currently under CRSI Fusion Bonded Epoxy Coating Applicator Plant Certification Program.

5. Provide one of following epoxy coatings for reinforcement and steel accessories as noted on the Drawings:
a. “Scotchkote 413,” by 3M Company, St. Paul, MN.
b. "Nap-Gard 7-2719,” by Axalta Coating Systems LLC.

Page 718 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 6

6. Use patching material recommended by epoxy powder manufacturer, compatible with epoxy coating and inert in concrete. Acceptable materials are as follows:
a. “Scotchkote 413/215,” by 3M Company, St. Paul, MN.
b. “MasterEmaco P124,” by BASF Building Systems, Shakopee, MN. c. “Duralprep AC,” by The Euclid Chemical Company, Cleveland, OH. d. “Sika Armatec 110 EpoCem,” by Sika Corporation, Lyndhurst NJ.

7. Corrosion Inhibiting Coating for Existing Exposed Non-prestressed Steel Reinforcement or Welded wire reinforcement:
a. “MasterEmaco ADH 326,” by BASF Building Systems, Shakopee, MN. b. “Euco 452”, or “Duralcrete Series” by The Euclid Chemical Company, Cleveland, OH.
c. “Sikadur 32 Hi-Mod LPL," by Sika Corporation, Lyndhurst, NJ. d. “Sika Armatec 110 EpoCem,” by Sika Corporation, Lyndhurst NJ.

C. Execution

1. Work shall conform to requirements of latest edition of ACI 301 “Standard Specifications for Structural Concrete,” ACI 315 “Details and Detailing of Concrete Reinforcement,” ACI 318 “Building Code Requirements for Reinforced Concrete,” and Concrete Reinforcing Steel Institute (CRSI), “Manual of Standard Practice.”

2. Submittals required include: Product data for proprietary materials and items, including reinforcement and forming accessories, admixtures, patching compounds, waterstops, joint systems, curing compounds, and others as requested by Engineer/Architect including, but not limited to:
a. Manufacturer's product data and installation instructions for proprietary form coatings, manufactured form systems, ties, and accessories. b. Steel producer's certificates of mill analysis, tensile tests, and bend tests. c. Manufacturer's product data, specifications, and installation instructions for proprietary materials, welded and mechanical splices, and reinforcement accessories.
d. Corrosion Inhibitor for Reinforcement:
1) Written certification from coating manufacturer that coating resin for reinforcement has been approved by National Bureau of Standards. 2) Written information from coating manufacturer on proper use and application of coating resin.
3) Coating applicator's written certification of results of quality control program.
e. Submit all materials and methods for concrete curing to Engineer/Architect for approval before beginning concreting Work. Include certification of curing compound allowable moisture loss.

Page 719 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 7

3. Store concrete reinforcement materials at site to prevent damage and accumulation of dirt or excessive rust.

4. Epoxy Coated Reinforcement:
a. Contact areas of handling and hoisting systems shall be padded or be made of nylon or other acceptable material.
b. Use spreader bars to lift bundles of coated steel to prevent bar-to-bar abrasion.
c. Pad bundling bands or fabricate of nylon or other acceptable material. d. Store coated steel on padded or wooden cribbing.
e. Do not drag coated steel members.
f. After placement, restrict traffic on coated steel to prevent damage.

5. Reinforcement with any of following defects will be rejected:
a. Lengths, depths and bends exceeding CRSI fabrication tolerances. b. Bends or kinks not indicated on Drawings or final Shop Drawings. c. Reduced cross-section due to excessive rusting or other cause.

6. General: Comply with Concrete Reinforcing Steel Institute's recommended practice for "Placing Reinforcing Bars," for details and methods of reinforcement placement and supports and as herein specified.
a. Avoiding cutting or puncturing vapor retarder during reinforcement placement and concreting operations.
b. Examine conditions under which concrete reinforcement is to be placed, and immediately notify Engineer/Architect in writing of unsatisfactory conditions.

Do not proceed with Work until unsatisfactory conditions have been corrected in acceptable manner.
c. Clean reinforcement of loose rust and mill scale, earth, ice, and other materials that reduce or destroy bond with concrete.
d. Fabricate reinforcement to conform to required shapes and dimensions, with fabrication tolerances complying with CRSI MSP. In case of fabricating errors, do not re-bend or straighten reinforcement in manner that will injure or weaken material.
e. Bends in reinforcement are standard 90 bends unless noted otherwise. f. Reinforcement with any of following defects will be rejected:
1) Lengths, depths and bends exceeding CRSI fabrication tolerances. 2) Bends or kinks not indicated on Drawings or final Shop Drawings. 3) Reduced cross-section due to excessive rusting or other cause. g. Perform all welding of mild steel reinforcement, metal inserts and connections with low hydrogen welding electrodes in accordance with AWS D1.4.
h. Epoxy coated reinforcement: Fabricator and applicator to provide installer with written instructions to handle, store and place epoxy coated reinforcement to prevent damage to coating.

Page 720 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 8
i. Comply with ACI 301, Chapter 3 for placing reinforcement. j. Use rebar chairs and accessories to hold all reinforcing positively in place.

Provide rebar chairs at all formed surfaces, both vertical and horizontal, to maintain minimum specified cover. Set wire ties so ends are directed into concrete, not toward exposed concrete surfaces. Maximum spacing of chairs and accessories shall be per CRSI Manual of Standard Practice. In situations not covered by CRSI, provide support at 4 ft on center maximum each way. k. Install welded wire reinforcement in as long lengths as practicable. Lap adjoining pieces at least one full mesh and lace splices with wire. Offset laps of adjoining widths to prevent continuous laps in either direction. l. Splices:
1) Provide standard reinforcement splices by lapping ends, placing bars in contact, and tying tightly with wire. Comply with requirements of ACI 318 for minimum lap of spliced bars.
2) For mechanical tension splices of reinforcement:
a) Column bar lengths shall not exceed 30 ft between splices. In any bar, no splices shall occur at any floor level.
b) Exercise care to assure that no reduction of cross-sectional area of reinforcement occurs.
c) Use Barsplice Products, Inc., Bar-Grip or Grip-Twist, NMB Splice Sleeve, or Erico LENTON splices.
d) For all mechanical splices, perform splicing in strict accordance with manufacturer's requirements and instructions.
e) All splices to develop 125% of specified yield strength of bars, or of smaller bar in transition splices.
f) Stagger splices in adjacent bars.
g) Except where shown on Drawings, welding of reinforcement prohibited without prior written authorization by Engineer/ Architect.
3) Compression splices: Mechanically coupled splices in accordance with ACI 318.
m. Epoxy Coated Reinforcement:
1) Rest epoxy coated steel members supported from formwork on coated wire bar supports, or on bar supports made of dielectric material or other suitable material.
2) Coat wire bar supports with dielectric material for minimum distance of 2 in. from point of contact with coated steel member.
3) Fasten epoxy-coated steel members with nylon-, epoxy-, or plasticcoated tie wire, or other suitable material acceptable to Engineer/Architect.
4) Mechanical connections, when required, shall be installed in accordance with splice device manufacturer's recommendations.

Repair any damage to coating.

Page 721 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 9
5) All parts of mechanical connections on epoxy-coated steel, including steel splice sleeves, bolts, and nuts shall be coated with same material used for repair of coating damage.
6) Do not cut epoxy-coated steel unless permitted by Engineer/ Architect.

When cut, coat ends with material used for repair of coating damage. 7) All welding of epoxy-coated steel shall conform to AWS D1.4. 8) Adequate ventilation shall be provided when welding epoxy-coated steel.
9) After welding, repair coating damage.

WI 1.5 OVERHEAD PROTECTION/TEMPORARY SIGNAGE/TRAFFIC CONTROL A. Scope of Work

1. This work consists of furnishing all labor, materials, equipment, supervision and incidentals necessary to: provide, erect, maintain and remove following completion of project overhead protection for vehicles and pedestrians, necessary to protect and control traffic circulation through drive lane areas where traffic flow must be maintained for operational use of other garage areas. Contractor shall provide and install and remove following completion of project, temporary signage, traffic control barricades/fences, and all other traffic controls as required for vehicular and pedestrian traffic control and user information during construction and as required by Owner and Engineer/Architect.

B. Materials

1. Temporary signage shall meet following minimum requirements:
a. Minimum size: 48” x 48”
b. Backing material: 0.5 in. medium density overlay plywood. c. Colors:
1) Background: medium orange or white.
2) Symbols/Lettering: black
d. Lettering: silk screened or die-cut.
1) Font Style: Helvetica or similar.
2) Size: 2 in. high minimum for pedestrian information; 4 in. high minimum for traffic information.

2. Barricades/barriers shall at minimum 4 ft. 0 in. high solid temporary barrier constructed of wood or concrete to separate Work areas from areas open to public.

C. Execution

Page 722 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 10

1. Contractor shall submit a detailed action plan to Owner and Engineer for temporary signage and traffic control prior to mobilizing for general conformance and informational purposes only.

2. Erect overhead protection as required to make project site safe for public. Under no circumstances shall construction work be performed without site protection in place to safeguard public.

3. Temporary signage and appropriate barricades for traffic control shall be provided to the satisfaction of the Owner to adequately inform the public (pedestrians and vehicles) of construction operations and how they are to proceed in and around the building site.

4. Signage mounting height: 5 ft. to bottom of sign. Provide mounting brackets as required.

5. Contractor shall submit shop drawings detailing sign size, layout, colors, and mounting schemes for approval prior to fabricating signs and mounting brackets.

6. Typical regulatory signs (that is, STOP, YIELD, etc.) and "Handicap" signs shall conform to all Federal, state, and local requirements for sizes, materials, and colors.

7. After removal of overhead protection/temporary signage/traffic controls, clean areas affected by these elements to condition prior to installation.

WI 2.0 FLOOR SURFACE PREPARATION
A. Scope of Work

1. This Work consists of furnishing all labor, materials, equipment, supervision and incidentals necessary to locate existing spalls, locate and remove delaminated and unsound concrete and prepare cavities for repair and/or overlay. Refer to Detail Series 2.0 for specific requirements.

B. Materials/Equipment (NOT APPLICABLE)
C. Execution

1. Locating, removals and preparation of deteriorated floor surface concrete shall be performed as specified in Division 02 Section "Surface Preparation for Patching and Overlay.”

2. Concrete removals shall be as square or rectangular shaped as practical.

3. All concrete shall be removed from within deterioration area boundaries until sound concrete is reached on all sides.

4. All exposed steel within cavities shall be cleaned by sandblasting and damaged and defective reinforcement replaced as specified

5. Contractor shall allow for Engineer/Architect inspection of all cavities for condition as specified.

WI 2.1 FLOOR PRPERATION - SCARIFICATION

Page 723 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 11

ADD TEXT
WI 2.6 FLOOR PREPARATION - TRAFFIC TOPPING/MEMBRANE REMOVAL A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision and incidentals necessary to remove and dispose of traffic toppings or other bonded waterproofing membrane from concrete floor slab as shown on Drawings.

B. Materials/Equipment

1. Equipment used shall not exceed weight or clearance restrictions currently in force for structure. No equipment may be used which, in opinion of Owner or Engineer/Architect, will damage existing structural system.

2. Equipment used shall leave a surface profile acceptable for specified use of newly exposed concrete slab, including exposed concrete, waterproofing membrane reapplication, or bonded concrete overlay.

C. Execution

1. Remove existing traffic topping/membrane from concrete floor slab by mechanical means.

2. Clean final slab surface after removals so slab can be inspected and determine repair areas. All debris incidental to removal and surface cleaning shall be removed from deck and properly disposed of before inspection begins.

3. Damage to floor slab caused by removal operations shall be corrected to satisfaction of Engineer/Architect at no additional cost to Owner.

4. Preparation of spall and delamination cavities prior to placement of concrete patch or overlay materials is not part of Work of this Work Item.

WI 3.0 CONCRETE FLOOR REPAIR
A. Scope of Work

1. This Work consists of furnishing all labor, materials, equipment, supervision and incidentals including shoring necessary to locate existing spalls, locate and remove delaminated and unsound floor concrete, prepare cavities and install new concrete and reinforcing (as required) materials to restore concrete floor to original condition and appearance. Refer to Detail Series 3.0 for specific requirements.

B. Materials

1. Concrete repair materials shall be as specified in Division 03 Section “Cast-inPlace Concrete Restoration” and/or Division 03 Section “Prepackaged Repair Mortar”.

Page 724 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 12

2. Conventional steel reinforcement shall be as specified in Division 03 Section “Castin-Place Concrete Restoration” and/or Work Item 1.4, “Concrete Reinforcement.”
C. Execution

1. Locating, marking, removal, preparation, and inspection of deteriorated concrete and reinforcing steel preparation, repair and installation shall be performed as specified in Division 02 Section "Surface Preparation for Patching and Overlay.”

2. Final surface preparation, concrete placement, finishing and curing shall be performed as specified in concrete repair material specification. Manufacturer specifications/requirements for these issues shall also be followed in the event proprietary bag mix repair materials are used.

WI 3.1 FLOOR REPAIR – PARTIAL DEPTH
A. Refer to Work Item 3.0, "Concrete Floor Repair" for scope of Work, materials and Execution procedure associated with this Work Item. Refer to Detail 3.1 for specific requirements.

WI 3.2 FLOOR REPAIR – PROTECT EXPOSED TENDON
A. Refer to Work Item 3.0, "Concrete Floor Repair" for scope of Work, materials and Execution procedure associated with this Work Item. Refer to Detail 3.2 for specific requirements.

WI 3.3 FLOOR REPAIR - FULL DEPTH (EDGE REPAIR)
A. Refer to Work Item 3.0, “Concrete Floor Repair” for Scope of Work, Material and Execution procedures associated with this Work Item. Refer to Detail 3.3 for specific requirements.

WI 3.4 FLOOR REPAIR – CONCRETE CURB
A. Refer to Work Item 3.0, "Concrete Floor Repair" for scope of Work, materials and Execution procedure associated with this Work Item. Refer to Detail 3.4 for specific requirements.

WI 3.10 FLOOR REPAIR – STAIR NOSING REPAIR
A. Refer to Work Item 3.0, “Concrete Floor Repair” for Scope of Work, Material and Execution procedures associated with this Work Item. Refer to Detail 3.10 for specific requirements.

WI 3.11 FLOOR REPAIR – SLAB-ON-GRADE

Page 725 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 13
A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment. Supervision and incidentals necessary to locate and remove delaminated slab-on-grade concrete, re-establish subbase material, and install new concrete. Refer to Detail 3.11 for specific requirements.

B. Materials

1. Concrete repair materials shall be as specified in Division 03 Section “Prepackaged Repair Mortar."
C. Execution

1. Locating, marking, removal, preparation, and inspection of deteriorated floor surface concrete and reinforcing steel preparation, repair and installation shall be performed as specified in Division 02 Section "Surface Preparation for Patching and Overlay.”

2. Properly compact subbase as required. Provide new subbase material as necessary.

3. Final surface preparation, concrete placement, finishing and curing shall be performed as specified in concrete repair material specification. Manufacturer specifications/requirements for these issues shall also be followed in the event proprietary bag mix repair materials are used.

WI 4.0 CONCRETE CEILING REPAIR
A. Scope of Work

1. This Work consists of furnishing all labor, materials, equipment, supervision and incidentals including shoring necessary to locate existing spalls, locate and remove delaminated and unsound overhead concrete, prepare cavities and install new concrete and reinforcing (as required) materials to restore overhead concrete to original condition and appearance. Refer to Detail Series 4.0 for specific requirements.

B. Materials

1. Trowel applied patching material shall be as specified in Division 03 Section "Prepackaged Repair Mortar." Trowel applied material may only be used per Engineers approval for repair application where repair depth is less than 1” deep.

C. Execution

1. Locating, marking, removal, preparation, and inspection of deteriorated concrete and reinforcing steel preparation, repair and installation shall be performed as specified in Division 02 Section "Surface Preparation for Patching and Overlay.”

Page 726 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 14

2. Final surface preparation, concrete placement, finishing and curing shall be performed as specified in concrete repair material specification. Manufacturer specifications/requirements on these issues shall also be followed in the event proprietary bag mix repair materials are used.

WI 4.1 CEILING REPAIR - PARTIAL DEPTH/SHALLOW
A. Refer to Work Item 4.0, "Concrete Ceiling Repair" for Scope of Work, materials and procedure associated with this Work Item. Refer to Detail 4.1 for specific requirements.

WI 5.0 CONCRETE BEAM REPAIR
A. Scope of Work

1. This Work consists of furnishing all labor, materials, equipment, supervision and incidentals including shoring necessary to locate existing spalls, locate and remove delaminated and unsound overhead concrete, prepare cavities and install new concrete and reinforcing (as required) materials to restore concrete beams and joists to original condition and appearance. Refer to Detail Series 5.0 for specific requirements.

B. Materials

1. Cast-in-place concrete repair materials shall be as specified in Division 03 Section “Cast-in-Place Concrete Restoration” and/or Division 03 Section “Prepackaged Repair Mortar”.

2. Conventional steel reinforcement shall be as specified in Division 03 Section “Castin-Place Concrete Restoration” and/or Work Item 1.4, “Concrete Reinforcement.”

3. Trowel applied patching material shall be as specified in Division 03 Section "Prepackaged Repair Mortar." This material may be used for shallow removal and repair Work Items only.

C. Execution

1. Locating, marking, removal, preparation, and inspection of deteriorated concrete and reinforcing steel preparation, repair and installation shall be performed as specified in Division 02 Section "Surface Preparation for Patching and Overlay.” Install shoring at repair locations where required per the Construction Documents prior to starting removals.

2. Final surface preparation, concrete placement, finishing and curing shall be performed as specified in concrete repair material specification. Manufacturer specifications/requirements on these issues shall also be followed in the event proprietary bag mix repair materials are used.

WI 5.1 BEAM REPAIR - PARTIAL DEPTH/SHALLOW

Page 727 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 15
A. Refer to Work Item 5.0, "Concrete Beam and Joist Repair" for scope of Work, materials and procedure associated with this Work Item. Refer to Detail 5.1 for specific requirements.

WI 5.2 CONCRETE STAIR – EDGE SPALL
A. Refer to Work Item 5.0, "Concrete Beam and Joist Repair" for scope of Work, materials and procedure associated with this Work Item. Refer to Detail 5.2 for specific requirements.

WI 6.0 CONCRETE COLUMN REPAIR
A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision and incidentals including shoring necessary to locate existing spalls, locate and remove delaminated and unsound concrete, prepare cavities and install concrete and reinforcing (as required) materials to restore concrete columns to original condition and appearance. Refer to Detail Series 6.0 for specific requirements.

B. Materials

1. Cast-in-place concrete repair materials shall be as specified in Division 03 Section “Cast-in-Place Concrete Restoration” and/or Division 03 Section “Prepackaged Repair Mortar”.

2. Conventional steel reinforcement shall be as specified in Division 03 Section “Castin-Place Concrete Restoration” and/or Work Item 1.4, “Concrete Reinforcement.”

3. Trowel applied patching material shall be as specified in Division 03 Section "Prepackaged Repair Mortar." This material may be used for shallow removal and repair Work Items only.

C. Execution

1. Locating, marking, removal, preparation, and inspection of deteriorated concrete and reinforcing steel preparation, repair and installation shall be performed as specified in Division 02 Section "Surface Preparation for Patching and Overlay.” Install shoring at repair locations where required per the Construction Documents prior to starting removals.

2. Final surface preparation, concrete placement, finishing and curing shall be performed as specified in concrete repair material specification. Manufacturer specifications/requirements on these issues shall also be followed in the event proprietary bag mix repair materials are used.

WI 6.1 COLUMN REPAIR – PARTIAL DEPTH /SHALLOW
A. Refer to Work Item 6.0, "Concrete Column Repair" for scope of Work, materials and procedure associated with this Work Item. Refer to Detail 6.1 for specific requirements.

Page 728 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 16
WI 7.0 CONCRETE WALL REPAIR
A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision and incidentals necessary to locate existing spalls, locate and remove delaminated and unsound concrete, prepare cavities and place patching materials to restore concrete walls to original condition and appearance. Refer to Detail Series 7.0 for specific requirements.

B. Materials

1. Trowel applied patching material shall be as specified in Section "Prepackaged Repair Mortar." This material may be used for shallow removal and repair Work Item only.

2. Concrete repair materials shall be as specified in Section "Cast-in-Place Concrete Restoration”, and/or Section “Prepackaged Repair Mortar." C. Execution

1. Contractor shall locate and mark all Work areas as specified in Section "Surface Preparation for Patching," Article "Inspection."

2. Procedure for delaminated, spalled and unsound concrete removal shall be as specified in Section "Surface Preparation for Patching," Article "Preparation."

3. Engineer/Architect shall inspect all cavities for condition according to Section "Surface Preparation for Patching," Article "Inspection of Repair Preparation."

4. All steel exposed within cavities shall be cleaned to bare metal by mechanical means according to Section "Surface Preparation for Patching," Article "Cleaning of Reinforcement within Delamination and Spall Cavities," and damaged and defective reinforcement replaced as specified in Section "Surface Preparation for Patching," Article "Reinforcement and Embedded Materials in Repair Areas." Exposed steel shall be epoxy coated with an approved epoxy resin as specified in Work Item "Concrete Reinforcement."

5. Contractor shall prepare cavities for patch placement as specified in Section "Surface Preparation for Patching," Article "Preparation of Cavity for Patch Placement."

6. Patch materials and associated reference specifications are listed in Work Item "Concrete Wall Repair," Article "Materials," above. Patch installation procedures shall be in accordance with referenced specifications for selected material.

WI 7.1 WALL REPAIR - PARTIAL DEPTH / SHALLOW

Page 729 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 17
A. Refer to Work Item "Concrete Wall Repair" for scope of Work, materials and procedure associated with this Work Item. Refer to Detail 7.1 for specific requirements.

WI 11.0 CRACK AND JOINT REPAIR
WI 11.1 ROUT & SEAL CRACKS
A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision and incidentals necessary to locate, prepare and seal unsealed construction and control joints in concrete floor and/or topping. Refer to Detail 11.1 for specific requirements.

B. Materials

1. Approved materials for use in this Work are specified in Division 07 Section "Concrete Joint Sealants."
C. Execution

1. Contractor shall thoroughly clean and inspect concrete slabs and/or topping for cracks and unsealed construction and control joints. Those identified as either greater than 0.03 in. wide or showing evidence of water leakage and/or salt staining on ceiling below shall be sealed. All cracks and joints identified for repair shall be marked with chalk to aid in precision routing. Obtain depths to top reinforcing bars and P-T tendons in area of repair by use of a pachometer (rebar locator). Determine depth of electrical conduit (metal or plastic). Do not exceed this depth of routing where the crack to be repaired crosses the embedded items.

Damage to embedded items will require repair or replacement at no cost to the Owner.

2. Cracks and construction joints shall be ground or sawcut to an adequate width and depth as required by Work Item Detail. Routing shall be performed by mechanized device that has positive mechanical control over depth and alignment of cut. Hand held power grinders with abrasive disks shall not be used on control/construction joints, but may be used on random cracks.

3. Cavities shall be thoroughly cleaned by either sandblasting or grinding to remove all laitance, unsound concrete and curing compounds which may interfere with adhesion. Groove shall be air blasted to remove remaining debris.

4. Sealant materials and installation procedures shall be in accordance with referenced specifications for selected material.

5. Traffic topping manufacturer shall verify in writing that joint sealant is compatible with traffic topping. Crack and joint sealant work shall be incidental to traffic topping system.

Page 730 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 18
WI 11.2 JOINT SEALANT REPAIR
A. Refer to Work Item 11.0, "Crack and Joint Repair" for scope of Work, materials and procedure associated with this Work Item. Refer to Detail 11.2 for specific requirements.

WI 11.3 VERTICAL JOINT SEALANT
A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision and incidentals necessary to locate and mark failed vertical joint sealant, remove existing sealant, prepare edges and reseal vertical joints. Refer to Detail 11.3 for specific requirements.

B. Materials

1. Approved materials for use in this Work are specified in Division 07 Section "Concrete Joint Sealants."

2. Materials used shall be as specified in Division 07 Section "Architectural Joint Sealants."
C. Execution

1. Contractor shall locate failed crack/joint sealant by visual inspection.

2. Contractor shall remove existing sealant from joints and/or cracks.

3. When existing joint dimensions do not conform to Detail 11.3, joints shall be routed or sawcut to an adequate width and depth to match Work Item Detail. Routing shall be performed by mechanized device that has positive mechanical control over depth and alignment of cut.

4. Cavities shall be thoroughly cleaned by either sandblasting or grinding to remove all remaining sealant and unsound concrete which may interfere with adhesion.

Groove shall also be air blasted to remove remaining debris.

5. Sealant materials and installation procedures shall be in accordance with referenced specifications for selected material.

6. Tool as necessary.

7. If traffic topping will contact vertical joint sealant, traffic topping manufacturer shall verify in writing that joint sealant is compatible with traffic topping.

WI 11.5 EPOXY INJECTION
A. Scope of Work

Page 731 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 19

1. Work consists of furnishing all labor, materials, equipment, supervision and incidentals necessary to locate cracks and obtain approval by the Engineer for crack injection, prepare and pressure inject cracks with an epoxy resin so as to create waterproof barrier and/or structural repair as indicated in the Drawings. Refer to Detail 11.5 for specific requirements.

B. Materials

1. Epoxy injection materials shall be as specified in Division 03 Section “Epoxy Injection Systems.”
C. Execution

1. Epoxy injection work and materials shall be performed in accordance with Division 03 Section "Epoxy Injection Systems."

2. Contractor is responsible for location of all locations requiring epoxy injection prior to start of Work.

3. Contractor shall allow for Engineer/Architect inspection of all epoxy injection sites for condition as specified.

4. No payment will be allowed for Work executed without Engineer/Architect inspection and verification.

5. Remove and patch all ports, holes, temporary seal materials to match existing conditions. This is considered incidental to the Work.

6. Clean and paint the repair area limited to the disturbed surfaces to match existing surfaces.

WI 11.7 COVE SEALANT
A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision and incidentals necessary to prepare concrete surfaces and install cove sealant between floor and vertical surfaces as shown on Drawings. Refer to Detail 11.7 for specific requirements.

B. Materials

1. Joint sealant materials shall be as specified in Division 07 Section Concrete Joint Sealants."
C. Execution

1. Intersection to be sealed shall be thoroughly cleaned by sandblasting to remove all contaminants and foreign material.

2. Entire Work area shall then be cleaned with compressed air to assure that all loose particles have been removed and that intersection is dry.

Page 732 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 20

3. Properly prepared intersection shall be coated evenly and completely with joint primer material on each of intersecting faces in accordance with sealant manufacturer's recommendations.

4. After primer has cured, apply cove sealant to intersection such that sealant extends 0.75 in. onto each of intersecting faces.

5. Work cove sealant into joint so that all air is removed and tool to concave shape such that minimum throat dimension of no less than 0.5 in. is maintained.

6. Remove excess sealant and allow to cure.

WI 16.0 TRAFFIC TOPPING
A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision and incidentals, including installation of joint sealant materials, necessary to prepare existing floor surfaces and install traffic topping. Coating of all vertical surfaces within Work limits shall be incidental to installation of traffic topping. Refer to Detail series 16.0 for specific requirements.

B. Materials

1. Traffic topping materials shall be as specified in Division 07 Section "Traffic Coatings."
C. Execution

1. Floor surface preparation shall be performed by coating system licensed applicator or under its direct supervision.

2. Shotblast surface preparation is required for floors.

3. Coating system shall be installed by licensed applicators in strict accordance with manufacturer's recommendations and referenced specification section.

4. Crack preparation, including installation of sealant material where required, is incidental to traffic topping work.

5. Coating system shall be thoroughly cured prior to Work areas being returned to service.

WI 16.1 TRAFFIC TOPPING - VEHICULAR
A. Refer to Work Item 16.0, "Traffic Topping" for Scope of Work, materials and procedure associated with this Work Item. Refer to Detail 16.1 for specific requirements.

WI 21.0 P/T- REPAIR

Page 733 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 21
WI 21.1 INSPECT P/T TENDON ANCHORAGE & REPAIR AT SLAB EDGE A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision and incidentals necessary to expose tendon anchors for Engineer review of damage or deterioration to the anchorage assembly. Concrete work performed in association with this work will be paid separately under Work Item series 3.0. Refer to Detail

21.1 for specific requirements.

B. Materials (Not Used)
C. Execution

1. Remove concrete at anchorage locations in accordance with Work Item series 3.0 sufficient to permit clear viewing of the anchorage. Remove concrete only as shown and to the limits detailed at the anchorages.

2. Clean exposed tendon and anchorage assembly for inspection and condition documentation. Notify Engineer at least 48 hours before exposing anchorages, do not patch exposed tendon or anchorage until Engineer’s inspection is complete and Engineer gives approval to proceed with patching.

3. Clean and epoxy coat exposed reinforcing steel and anchor plate per Work Item series 3.0.

4. Re-cast concrete at anchorage locations in accordance with Work Item series 3.0 to match surrounding concrete. Concrete work performed in association with this work will be paid separately under Work Item series 3.0.

WI 21.2 PROTECT EXPOSED P/T TENDON(S)
A. Scope of Work

1. This work consists of furnishing all labor, materials, equipment, supervision and incidentals necessary to remove damaged tendon sheathing, re-grease (or epoxy coat tendons as approved by Engineer) in damaged area and install new sheathing. Concrete work performed in association with this work will be paid separately under Work Item series 3.0. Refer to Detail 21.20 for specific requirements.

B. Materials

1. Material shall be as specified in Division 03 Section “Unbonded Post-Tensioned Concrete.”
C. Execution

Page 734 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 22

1. Remove damaged sheathing materials from exposed tendon.

2. Grease coating:
a. Apply additional corrosion-inhibiting grease over the damaged area to completely fill any void or surface depression caused by the sheathing damage.

3. Epoxy coating option (use only as approved by Engineer). a. Clean tendon to remove grease residue from exposed tendon. b. Apply uniform coating of epoxy to exposed tendon.

4. Install split sheathing over exposed tendon. Sheathing shall overlap existing sheathing by at least two inches at each end. Sheathing shall be oriented such that the split is toward the bottom.

5. Tape entire length of repair, spirally wrapping tape around sheathing to provide at least two layers of tape. Taping shall overlap existing sheathing by 2 in. at each end.

WI 25.0 MECHANICAL
WI 25.1 MECHANICAL – ALLOWANCE
A. Scope of Work

1. Mechanical allowance shall be all related utility work (drain lines, sprinkler lines, electrical conduit, junction boxes, etc.) associated with interruptions of these utilities to repair existing structural areas.

2. All utilities removed during Work shall be reinstalled in accordance with latest edition of electrical and mechanical codes in effect. Work ineligible for allowance includes Work covered by or incidental to Work Items within this Specification or for Work required through Contractor's negligence.

B. Method of Payment

1. Mechanical work as approved in writing by Engineer/Architect prior to implementation, shall be paid for by Contractor. Contractor shall provide written documentation of costs for work performed, including invoices from subcontractors with any General Contractor's markup, to Engineer/Architect with each pay request. Contractor shall attach documentation and invoices to written authorization. At completion of project, any variation between allowance and actual cost documentation will be reflected in an adjustment of allowance amount.

Page 735 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 23
WI 30.0 ELECTRICAL – LIGHTING
WI 30.1 ELECTRICAL ALLOWANCE
A. Scope of Work

1. Electrical allowance shall be all related utility work (drain lines, sprinkler lines, electrical conduit, junction boxes, etc.) associated with interruptions of these utilities to repair existing structural areas.

2. All utilities removed during Work shall be reinstalled in accordance with latest edition of electrical and mechanical codes in effect. Work ineligible for allowance includes Work covered by or incidental to Work Items within this Specification or for Work required through Contractor's negligence.

B. Method of Payment

1. Electrical work as approved in writing by Engineer/Architect prior to implementation, shall be paid for by Contractor. Contractor shall provide written documentation of costs for work performed, including invoices from subcontractors with any General Contractor's markup, to Engineer/Architect with each pay request. Contractor shall attach documentation and invoices to written authorization. At completion of project, any variation between allowance and actual cost documentation will be reflected in an adjustment of allowance amount.

WI 30.11 REPLACE LIGHT FIXTURES
A. Scope of Work

1. Replace existing surface mounted and pole mounted light fixtures per Sheets E5, E6, and E7 of the project plans.

WI 30.2 REMOVE AND REPLACE FIRE EXTINGUISHER CABINET
A. Refer to Work Item 30.2 for Scope of Work, Material and Execution procedures associated with this Work Item. Refer to Detail 30.2 for specific requirements.

WI 40.0 CONNECTIONS/BEARINGS
WI 40.6 REMOVE EXISTING GUARDRAIL
A. Refer to Work Item 40.6 for Scope of Work, Material and Execution procedures associated with this Work Item. Refer to Detail 40.6 for specific requirements.

WI 40.7 INSTALL NEW BARRIER CABLE
A. Refer to Work Item 40.7 for Scope of Work, Material and Execution procedures associated with this Work Item. Refer to Detail 40.7 for specific requirements.

Page 736 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 24
WI 43.0 MISCELLANEOUS METALS
WI 43.2 REMOVE SALVAGE AND INSTALL GUARDRAIL
A. Refer to Work Item 43.2 for Scope of Work, Material and Execution procedures associated with this Work Item. Refer to Detail 43.2 for specific requirements.

WI 43.4 REPAIR EXISTING BARRIER CABLE
A. Refer to Work Item 43.4 “Repair Existing Barrier Cable” for Scope of Work, Material and Execution procedures associated with this Work Item. Refer to Detail 43.4 for specific requirements.

WI 43.5 INSTALL NEW BOLLARD
A. Refer to Work Item 43.5 “Install New Bollard” for Scope of Work, Material and Execution procedures associated with this Work Item. Refer to Detail 43.5 for specific requirements.

WI 43.6 INSTALL STAIR #1 CANOPY CORRUGATED METAL COVER
A. Refer to Work Item 43.6“Install Stair #1 Canopy Corrugated Metal Cover” for Scope of Work, Material and Execution procedures associated with this Work Item. Refer to Detail

43.6 for specific requirements.

WI 43.7 SOUTH ENTRANCE IMPACT DAMAGE
A. Refer to Work Item 43.7 for Scope of Work, Material and Execution procedures associated with this Work Item. Refer to Detail 43.7 for specific requirements.

WI 45.0 PAINTING
WI 45.1 PAINT TRAFFIC MARKINGS
A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision and incidentals necessary to locate, layout and paint exit ramp curbs and all other required pavement markings.

B. Materials

Page 737 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 25

1. Painting materials shall be as specified in Division 09 Section "Pavement Marking - Restoration."
C. Execution

1. Unless otherwise indicated in the Construction Documents, stripes and paint color shall match all existing marks and be provided at same locations.

2. Where new striping layout is described in the Construction Documents that conflicts with existing striping layout, remove existing stripes in those locations where they conflict with new striping layout. See referenced specification section for removal requirements.

3. Where existing traffic marking layout is to be maintained, Contractor shall prepare drawing of existing traffic marking layout in work areas prior to starting with repairs.

Contractor shall note stall width, angle of parking, directional traffic arrows and all other existing pavement markings.

4. Contractor shall submit striping plan for Engineer/Architect's review.

5. Engineer/Architect may inspect all layout and surface preparation for conditions in accordance with Division 09 Section "Pavement Marking-Restoration." WI 45.6 PAINT STRUCTURAL STEEL
A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision and incidentals necessary to contain, with full height barriers, preparation debris and paint during operations and prepare, prime and paint all structural steel and miscellaneous metal items as located on Drawings.

B. Materials

1. Paint materials shall be as specified in Division 09 Section “Exterior Painting.” C.

Execution

1. Contractor shall locate and verify with Engineer/Architect all Work areas.

2. Contractor shall verify color selection with Owner prior to start of Work.

3. Contractor shall take all necessary measures to contain, with full height barriers, sandblasting debris and paint to immediate Work area to protect public from injury and property from damage.

4. Contractor shall solvent clean any surface area with oil or grease build-up prior to receiving additional preparation in accordance with SSPC-SP1 and Division 09 Section "Exterior Painting."

5. Contractor shall prepare all surfaces with surface corrosion in accordance with SSPC-SP10 “Near White Metal Blast Cleaning” or SSPC-SP11 “Power Tool Cleaning to Bare Metal” and Division 09 Section "Exterior Painting."

Page 738 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 26

6. Contractor shall remove all debris from Work area prior to application of primer or paint.

7. Contractor shall apply primer to all prepared metal surfaces on same day (within 8 hrs) as preparation operations. Apply primer and Paints according to Division 09 Section "Exterior Painting" and in strict accordance with manufacturer's recommendations.

WI 45.7 CLEAN AND PAINT STAIR RAILINGS
A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision and incidentals necessary to contain debris, with full height barriers, cleaning, preparation and paint during operations and prepare, prime and paint all structural steel and miscellaneous metal items as located on Drawings.

B. Materials

1. Paint materials shall be as specified in Division 09 Section “Exterior Painting.” C.

Execution

1. Contractor shall locate and verify with Engineer/Architect all Work areas.

2. Contractor shall verify color selection with Owner prior to start of Work.

3. Contractor shall take all necessary measures to contain, with full height barriers, sandblasting debris and paint to immediate Work area to protect public from injury and property from damage.

4. Contractor shall solvent clean any surface area with oil or grease build-up prior to receiving additional preparation in accordance with SSPC-SP1 and Division 09 Section "Exterior Painting."

5. Contractor shall prepare all surfaces with surface corrosion in accordance with SSPC-SP10 “Near White Metal Blast Cleaning” or SSPC-SP11 “Power Tool Cleaning to Bare Metal” and Division 09 Section "Exterior Painting."

6. Contractor shall remove all debris from Work area prior to application of primer or paint.

7. Contractor shall apply primer to all prepared metal surfaces on same day (within 8 hrs) as preparation operations. Apply primer and Paints according to Division 09 Section "Exterior Painting" and in strict accordance with manufacturer's recommendations.

WI 49.1 CATHODIC PROTECTION – DISCRETE ANODES
A Scope of Work

Page 739 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

WORK ITEMS 020010 - 27

1. This Work consists of furnishing all labor, materials, equipment, supervision and incidentals necessary to install galvanic anodes in concrete repair patches for various concrete repair Work Items as shown on Drawings. Refer to Detail 49.1 for specific requirements.

B. Materials

1. Materials shall be as specified in Division 03 Section “Galvanic Anode Corrosion Protection System.”
C. Execution

1. Concrete demolition and patching shall be in accordance with appropriate repair Work Item and is not a part of this Work Item.

2. Contractor shall install discrete anodes at (16) inches on center (maximum) in each patch around the perimeter of the repair. Final anode installation locations will vary, based on existing reinforcing steel layout; determine final installation layout with Engineer input in field.

3. Unless noted otherwise, Contractor shall install discrete anodes on mild reinforcing steel only. Post-tension tendons shall not receive anodes.

4. Discrete anodes are to be installed per Specifications to the reinforcing bar to clean/bare metal. Orient anodes towards center of concrete members where possible to maximize concrete cover.

5. Confirm electrical connection between anode tie wire and reinforcing steel by measuring DC resistance (ohm) with a multi-meter. Connection is acceptable if DC resistance is less than 1 ohm

6. For highly resistive repair concrete (latex, microsilica/pozzolan enhanced, etc.), bridging mortar between discrete anode and existing concrete substrate shall be installed to provide a proper electrically conductive path.

7. Coating of reinforcing steel and anode connection wires is not to occur until after unit is installed to existing steel. Discrete anode is not to be coated with epoxy.

END OF SECTION 020010

Page 740 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SECTION 025130 - GENERAL CONCRETE SURFACE PREPARATION
PART 1 - GENERAL

1.1 DEFINITIONS
A. DELAMINATIONS: Fracture planes, "internal cracks," within concrete. Typically, these fractures are parallel to the member face and vary in depth.

B. NEAR-VERTICAL CHIPPED EDGES: Provide an edge dressed to within 20o of perpendicular of finished surface.

C. SPALLS: Potholes, cavities or voids in concrete. Usually result of delamination migrating to face of concrete member. When fracture finally reaches surface, concrete encompassed by delamination breaks away, resulting in spall.

D. UNSOUND CONCRETE: Concrete exhibiting one or more of:

1. Incipient fractures present beneath existing delaminated or spalled surfaces.

2. Honeycombing.

3. Friable or punky areas.

4. Deterioration from freeze-thaw action.

E. SCALING: Deterioration which attacks mortar fraction (paste) of concrete mix. First appears as minor flaking and disintegration of concrete surface. Scaling eventually progresses deeper into concrete, exposing aggregate which breaks away.

F. SHOTBLASTING: Scarification of concrete surfaces using an abraded metal shotrebound. See ICRI Guideline 03732 “Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings, and Polymer Overlays.” PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 025130

Page 741 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

GENERAL CONCRETE SURFACE PREPARATION 025130 - 1 THIS PAGE LEFT INTENTIONALLY BLANK.

GENERAL CONCRETE SURFACE PREPARATION 025130 - 1

Page 742 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SURFACE PREPARATION FOR PATCHING AND OVERLAY 025140 - 1 SECTION 025140 - SURFACE PREPARATION FOR PATCHING AND OVERLAY PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 01 Specification Sections apply to this Section.

1.2 SUMMARY
A. This Section includes the provision of all labor, materials, equipment, supervision and incidentals necessary to locate and remove all delaminated and unsound concrete, all existing failed patches, all existing surface spalls and potholes, and preparation of cavities created by removal to receive concrete patching material.

B. This Section includes the provision of all labor, materials, equipment, supervision and incidentals necessary to prepare existing sound concrete slab surfaces to receive bonded concrete overlay.

C. Related Sections: Following Sections contain requirements that relate to this Section:

1. Division 02 Section “Work Items”

2. Division 03 Section “Cast-in-Place Concrete – Restoration”

3. Division 03 Section “Prepackaged Repair Mortar”

1.3 REFERENCES
A. "Specifications for Structural Concrete for Buildings" (ACI 301) by American Concrete Institute, herein referred to as ACI 301, is included in total as specification for this structure except as otherwise specified herein.

B. Comply with provisions of following codes, specifications and standards except where more stringent requirements are shown on Drawings or specified herein:

1. ”Concrete Repair Guide” (ACI 546R-04)
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION

Page 743 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SURFACE PREPARATION FOR PATCHING AND OVERLAY 025140 - 2

3.1 INSPECTION
A. Floor Slabs:

1. Floor slab delaminations: locate by sounding surface with hammer, rod, or chain drag.

2. When delaminated area is struck, distinct hollow sound is heard.

3. Contractor: sound all designated floors for delaminations.

4. Certain structural systems that contain thin slab thicknesses with Welded Wire Reinforcement or other small diameter reinforcing, such as waffle slab or precast tees, may have significant deterioration without evidence of delaminations. These structural systems require qualified personnel to provide additional inspections, primarily visual in nature, to define the extent of deterioration.

5. Contractor: Visually inspect thin slab thicknesses with small diameter reinforcing for deterioration.

B. Vertical and Overhead Surfaces:

1. Vertical and overhead surface delaminations: locate by sounding appropriate member with hammer or rod.

2. Cracks, usually horizontal in orientation along beam faces, and vertical in orientation near column corners are indicators of delaminated concrete.

3. Contractor: sound only vertical and overhead surfaces that show evidence of cracking and/or salt and water staining.

C. Delaminated areas, once located by Contractor, shall be further sounded to define limits.

Mark limits with chalk or paint.

D. Contractor: locate spalls by visual inspection and mark boundaries with chalk or paint after sounding surface.

E. Engineer/Architect will define and mark additional unsound concrete areas for removal, if required.

F. Areas to be removed shall be as straight and rectangular as practical to encompass repair and provide neat patch.

G. Contractor: Locate and determine depth of all embedded REINFORCEMENT, and ELECTRICAL CONDUIT in repair area and mark these locations for reference during concrete removal. Do NOT nick or cut any embeds unless approved by Engineer/Architect.

H. For overlay installation, boundaries of overlay areas will be as defined in project drawings and verified by Engineer/Architect.

Page 744 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SURFACE PREPARATION FOR PATCHING AND OVERLAY 025140 - 3

3.2 PREPARATION
A. Temporary shoring may be required at concrete floor repair areas exceeding 5 sq ft and at any beam, joist, or column repair. Contractor: Review all marked removal and preparation areas and request clarification by Engineer/Architect of shoring requirements in questionable areas. Shores shall be in place prior to concrete removal and cavity preparation in any area requiring shores.

B. Delaminated, spalled and unsound concrete floor areas: mark boundaries. All concrete shall be removed from within marked boundary to minimum depth of 0.75 in. using 15 to 30 lb chipping hammers equipped with chisel point bits. When directed by Engineer/Architect, chipping hammers less than 15 lb shall be used to minimize damage to sound concrete. Near vertical chipped edge shall be provided along perimeter of repair area where shown on drawings. Areas to be removed shall encompass repair and proved uniform cavity surface. If delaminations exist beyond minimum removal depth, chipping shall continue until all unsound and delaminated concrete has been removed from cavity.

C. Where embedded reinforcement or electrical conduit is exposed by concrete removal, exercise extra caution to avoid damaging it during removal of unsound concrete. If bond between exposed embedded reinforcement and adjacent concrete is impaired by Contractor's removal operations, Contractor shall perform additional removal around and beyond perimeter of reinforcement for minimum of 0.75 in. along entire length affected at no cost to Owner.

D. If rust is present on embedded reinforcement where it enters sound concrete, additional removal of concrete along and beneath reinforcement required. Additional removal shall continue until non-rusted reinforcement is exposed or may be terminated as Engineer/Architect directs.

E. Sawcut patch and overlay boundaries to depth of 0.75 in. into floor slab, unless otherwise noted. No sawcutting required at overlay boundaries abutting existing vertical surface (wall, beam, curb, etc.). For vertical and overhead surfaces marked boundary may be sawcut, ground or chipped to depth of 0.5 in. to 0.625 in. into existing concrete, measured from original surface. All edges shall be straight and patch areas square or rectangularshaped. Diamond blade saw or grinder with abrasive disk suitable for cutting concrete is acceptable for performing work. Edge cut at boundary shall be dressed perpendicular to member face. It shall also be of uniform depth, for entire length of cut. Exercise extra caution during sawcutting to avoid damaging existing reinforcement (ESPECIALLY POST-TENSIONING TENDONS AND SHEATHING) and electrical conduit and any other embedded items near surface of concrete. Any damage to existing reinforcement, posttensioning tendons or sheathing during removals shall be repaired by Contractor with Engineer/Architect-approved methods at no additional cost to Owner.

3.3 INSPECTION OF REPAIR PREPARATION
A. After removals are complete, but prior to final cleaning, exposed concrete surfaces and exposed reinforcement shall be inspected by Contractor and verified by

Page 745 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SURFACE PREPARATION FOR PATCHING AND OVERLAY 025140 - 4 Engineer/Architect for compliance with requirements of this Section. Where Engineer/Architect finds unsatisfactory surface or cavity preparation, Engineer/ Architect shall direct Contractor to perform additional removals. Engineer/Architect shall verify areas after additional removals.

B. Contractor shall inspect embedded reinforcement and conduits exposed within cavity for defects due to corrosion or damage resulting from removal operations. Contractor shall notify Engineer/Architect of all defective and damaged reinforcement or conduits.

Replacement of damaged or defective reinforcement or conduits shall be performed according to this Section and as directed by Engineer/Architect.

C. After inspections of exposed surfaces and reinforcement are complete, Engineer/ Architect and Contractor shall measure and document removal and replacement quantities for payment, as required.

3.4 REINFORCEMENT AND EMBEDDED MATERIALS IN REPAIR AREAS A. All embedded reinforcement exposed during surface preparation that has lost more than 15% (10% if 2 or more consecutive parallel bars and/or tendons are affected) of original cross-section due to corrosion shall be considered DEFECTIVE. All non-defective exposed reinforcement that has lost section to extent specified above as direct result of Contractor's removal operations shall be considered DAMAGED.

B. Embedded materials including, but not limited to, electrical conduit, corrosion protection systems and snow/ice melting equipment shall be protected by Contractor during removal operations. Damage due to removal operations shall be repaired by Contractor in accordance with national code requirements at no cost to Owner. Embedded materials which are defective due to pre-existing conditions may be repaired or replaced by Contractor or abandoned at Owner's option and cost.

C. Supplement defective or damaged embedded reinforcement by addition of reinforcement of equal diameter with Class "B" minimum splice per ACI 318 beyond damaged portion of reinforcement. Secure new reinforcement to existing reinforcement with wire ties and/or approved anchors. Supplemental reinforcement shall be ASTM A615 Grade 60 steel installed in accordance with Division 03 specification Sections.

Tendon supplement or repair materials, when applicable, shall be as required by Section "Work Items."
D. Loose and supplemental reinforcement exposed during surface preparation shall be securely anchored prior to concrete placement. Loose reinforcement shall be adequately secured by wire ties to bonded reinforcement or shall have drilled-in anchors installed to original concrete substrate. Drilled-in anchors shall be Powers “Tie-Wire Lok-Bolt” anchors, ITW Ramset/Red Head “TW-1400” anchor, or approved equivalent.

Supplemental reinforcing needed to be held off substrate shall be adequately secured by drilled-in anchors installed to original concrete substrate with Powers “Tie-Wire Spike”, ITW Ramset/Red Head Redi-Drive “TD4-112” anchors, or approved equivalent.

Engineer/Architect will determine adequacy of wire ties and approve other anchoring

Page 746 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SURFACE PREPARATION FOR PATCHING AND OVERLAY 025140 - 5 devices prior to their use. Securing loose and supplemental reinforcement is incidental to surface preparation and no extras will be allowed for this Work.

E. Concrete shall be removed to provide minimum of 3/4 in. clearance on all sides of defective or damaged exposed embedded reinforcement that is left in place. Minimum of 1.5-in. concrete cover shall be provided over all new and existing reinforcement.

Concrete cover over reinforcement may be reduced to 1 in. with Engineer/Architect's approval if coated with an approved epoxy resin.

F. Supplemental reinforcement and concrete removals required for repairs of defective or damaged reinforcement shall be paid for as follows:

1. Concrete removals and supplemental reinforcement required for repairs of DEFECTIVE reinforcement shall be paid for by Owner at unit price bid.

2. Concrete removals and supplemental reinforcement required for repairs of DAMAGED reinforcement shall be paid for by Contractor.

3.5 CLEANING OF REINFORCEMENT WITH DELAMINATION AND SPALL CAVITIES A. All exposed steel shall be cleaned of rust to bare metal by sandblasting. Cleaning shall be completed immediately before concrete placement to insure that base metal is not exposed to elements and further rusting for extended periods of time. Clean entire bar diameter be cleaned.

B. After all sandblasting operations and cleanup are completed, paint all exposed steel with an approved epoxy. Protect prepared surfaces from damage prior to and during concrete placement.

3.6 PREPARATION OF CAVITY FOR PATCH PLACEMENT
A. Floor slab and cavity surfaces will be examined prior to commencement of concrete placement operations. Sounding surface shall be part of examination. Any delamination noted during sounding shall be removed as specified in this Section.

B. Cavities prepared by chipping or other impact methods shall be sandblasted to remove material that may impair concrete bonding. Sound concrete surfaces shall be prepared by shotblasting as previously specified in this section. Airblasting is required as final step to remove all debris including sand and dust. All debris shall be removed from site prior to commencement of concrete placement, bonding agent preparation, etc. as specified in Division 03 Sections.

Page 747 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

SURFACE PREPARATION FOR PATCHING AND OVERLAY 025140 - 6 END OF SECTION 025140
THIS PAGE LEFT INTENTIONALLY BLANK.

Page 748 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

GALVANIC ANODE CORROSION PROTECTION SYSTEM 032117 - 1
SECTION 032117 – GALVANIC ANODE CORROSION PROTECTION SYSTEM PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY
A. This Section includes furnishing all labor, tools, materials, equipment and services necessary to properly install embedded galvanic anodes.

B. Embedded galvanic anodes are designed to provide localized corrosion protection to mild steel reinforcement that is located within a partial or full depth concrete repair.

When placed at appropriate spacing, as recommended by the product manufacturer, along the perimeter of concrete patches or interface between new and existing concrete, galvanic anodes help control active corrosion and mitigate formation of new corrosion sites.

C. Related Section: Following Sections contain requirements that relate to this Section:

1. Division 02 Section "General Concrete Surface Preparation."

2. Division 02 Section "Surface Preparation for Patching."

3. Division 03 Section "Cast-In-Place Concrete - Restoration.”

4. Division 03 Section “Prepackaged Repair Mortar”

1.3 QUALITY ASSURANCE
A. The contractor shall provide submittals confirming the chloride penetration resistance of the repair material or bridging mortar by an independent testing laboratory prior to beginning work.

1. Concrete repair material or Bridging Mortar shall have a Rapid Chloride Penetration Resistance (ASTM C1202) above 1350 Coulombs or Bulk Electrical Resistivity (ASTM C1760) below 15,000 Ohm-cm as measured after 28-day wet-cure.

B. Embedded galvanic anodes shall utilize chemical enhancement to keep the zinc active over the anode design life. Alkali-activated anodes shall have a pH of 14 or greater.

Page 749 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

GALVANIC ANODE CORROSION PROTECTION SYSTEM 032117 - 2
C. Insulating materials such as epoxy bonding agents shall not be used[in any patch or concrete placement protected by galvanic anodes. D. Testing Agency:

1. Independent testing laboratory provided by Contractor and acceptable to Engineer/Architect.

2. Testing laboratory shall submit documented proof of ability to perform required tests.

3. Testing Agency is responsible for conducting, monitoring and reporting results of all tests required under this Section. Testing Agency has authority to reject material not meeting Specifications.

4. Testing of repair locations shall be performed by testing agency representatives that are NACE certified to CP2, CP3 or CP4.

5. Testing Agency shall submit the following information for Field Testing of Material unless modified in writing by Engineer/Architect:
a. Project name and location.
b. Contractor's name.
c. Testing Agency's name, address and phone number.
d. Anode manufacturer.
e. Date of report.
f. Testing Agency technician's name .
g. Placement location within structure.
h. Weather data:
1) Air temperatures.
2) Weather.
3) Wind speed.
i. Date, time, and place of test.
j. Related test data as required in Section “Field Quality Control by Testing Agency.”

1.4 REFERENCES
A. Comply with provisions of following codes, specifications and standards except where more stringent requirements are shown on Drawings or specified herein:

1. ACI/ICRI: Concrete Repair Manual.

2. ACI Guideline No. 222R: – Corrosion of Metals in Concrete

3. ACI 562: Code Requirements for Evaluation, Repair and Rehabilitation of Concrete Buildings.

4. ACI RAP-8: Repair Application Procedure: Installation of Embedded Galvanic Anodes

5. ICRI Guideline 310.1R: Guide for Surface Preparation for the Repair of Deteriorated Concrete resulting from Reinforcing Steel Corrosion.

Page 750 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

GALVANIC ANODE CORROSION PROTECTION SYSTEM 032117 - 3

6. ASTM A615/A615M: Standard Specification for Deformed and Plain CarbonSteel Bar for Concrete Reinforcement.

7. ASTM A82: Specification for Plain Steel Wire for Concrete Reinforcement.

8. ASTM B6-09 - Standard Specification for Zinc.

9. ASTM B418: Standard Specification for Cast and Wrought Galvanic Zinc Anodes.

10. ASTM C1202: Standard Test Method for an Electrical Indication of Concrete Ability to Resist Chloride Ion Penetration,

11. ASTM C1760: Standard Test Method for Bulk Electrical Conductivity of Hardened Concrete.”

1.5 DELIVERY, STORAGE, AND HANDLING
A. Deliver all materials to site in original, unopened containers, bearing following information:

1. Name of product.

2. Name of manufacturer.

3. Batch number

4. Date of manufacture
B. Store materials in unopened boxes in dry conditions and protect from extremes in temperature and humidity. Replace packages or materials showing any signs of damage with new material at no additional cost to Owner.

1.6 WARRANTY
A. System manufacturer and Contractor shall furnish Owner written single source performance guarantee that the embedded galvanic anodes will remain electrochemically active, producing galvanic current and provide corrosion protection for a period of five years starting from the date of substantial completion of the project.

PART 2 - PRODUCTS

2.1 MATERIALS
A. Embedded galvanic anodes shall utilize zinc in compliance in compliance with ASTM B418 Type II (Z13000) and ASTM B6 Special High Grade (Z13001) with iron content less than 15 ppm.

B. Embedded galvanic anodes shall be pre-manufactured, and contain sufficient quantity of metallic zinc to mitigate corrosion for a period of fifteen (15) years.

Page 751 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

GALVANIC ANODE CORROSION PROTECTION SYSTEM 032117 - 4
Minimum amount of zinc shall be at least 100 grams. Amount of zinc shall be at least 200% of amount needed to satisfy anticipated service life based on electrochemical theory (Faraday’s Law) and based on currents that are expected to flow in anodes.

Zinc shall be cast around steel tie wires to provide a durable zinc / steel connection as per NACE practice. Anodes shall be supplied with integral unspliced tie wires for direct connection to reinforcing steel.

C. Embedded galvanic anodes shall be evaluated and certified by an independent organization.

D. Embedded galvanic anodes shall have verifiable record with a minimum of 5 projects of similar size showing minimum five years satisfactory performance in similar field environment. Records shall demonstrate satisfactory flow of protective current throughout three-year period; including at least 0.2 mA after 1 year, and at least 0.1 mA after 3 years. Significant cathodic polarization of surrounding reinforcing steel shall be documented throughout this period.

E. Repair mortars, concrete and bonding agents shall be Portland cement-based materials with volumetric resistivity below 15,000 ohm-cm, as measured after 28day wet cure and in saturated condition. Contractor shall provide submittals confirming the resistivity of repair materials prior to beginning work. Non-conductive repair materials such as epoxy, urethane, or magnesium phosphate shall not be permitted.

F. Deformed bars for reinforcement shall be hot-rolled steel in accordance with ASTM A615/A615M-00, Grade 60 (Grade 400).

G. Deliver, store, and handle all materials in accordance with manufacturer’s instructions.

H. Available Products: Subject to compliance with the requirements, products that may be incorporated into the Work include, but are not limited to the following: Acceptable Products (Minimum Zinc Content 100 grams) are as follows:

1. Alkali Activated Embedded Galvanic Anodes:
a. “Galvashield XP2 or XP4,” by Sika Corporation, Lyndhurst, NJ or by Vector Corrosion Technologies, Winnipeg Canada.
b. Engineer approved equal.

PART 3 - EXECUTION

3.1 CONCRETE REMOVAL AND PREPARATION
A. Concrete removal, preparation of the concrete surface for patching shall be conducted under appropriate concrete partial or full depth repair work item and according to Section “Surface Preparation for Patching.”

Page 752 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

GALVANIC ANODE CORROSION PROTECTION SYSTEM 032117 - 5

3.2 CLEANING AND REPAIR OF REINFORCING STEEL
A. Clean exposed reinforcing steel of rust, mortar, etc. to provide sufficient electrical connection prior to installation of anodes.

B. Secure loose reinforcing steel by tying tightly to other bars with steel tie wire. Newly secured reinforcing steel shall be tested to insure electrical continuity according to Section “Galvanic Anode Installation: Electrical Continuity” below.

3.3 GALVANIC ANODE INSTALLATION
A. Galvanic anodes shall be installed along perimeter of repair or interface with spacing as indicated in Project Documents and in accordance with manufacturer recommendations.

1. In no case shall distance between anodes exceed 30 inches (760 mm).

2. Handle and install anodes in accordance with manufacturer’s written instructions.

3. Provide sufficient clearance between anodes and substrate to allow repair material to encase anode.

4. Install galvanic anodes immediately following preparation and cleaning of steel reinforcement.

5. Galvanic anodes shall be installed to provide minimum 2 inches (50 mm) concrete cover over the anodes. If less than 2 inches (50 mm) of concrete cover is expected, place anode behind bar and secure to clean reinforcing steel.

6. Secure galvanic anodes within 4 in (100 mm) of patch edge using anode tie wires, preferably Tie wires shall be wrapped at least one full turn in opposite directions around cleaned reinforcing steel and twisted tight to allow little or no free movement. Anode may be tied to a single bar or may be placed at an intersection between two bars and secured to each clean bar.

B. Electrical Continuity

1. At all anode locations, Contractor to confirm and report electrical continuity between anode tie wire and reinforcing steel and between exposed reinforcing steel within the repair area by using a multi-meter on the lowest DC mV scale.

Electrical continuity is acceptable if the DC mV difference between test points is equal to or less than 1 mV. Document testing and submit in accordance with Section “Submittals.”

2. If electrical continuity does not exist between anode unit and reinforcing steel, remove the anode, clean the steel, reinstall the anode and retest. If electrical continuity does not exist between reinforcing steel within the repair area, connect discontinuous steel to continuous steel by wrapping tightly with steel tie wire to provide electrical continuity.

Page 753 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

GALVANIC ANODE CORROSION PROTECTION SYSTEM 032117 - 6

3.4 CONCRETE REPLACEMENT
A. Provide bridging mortar completing surrounding anode and forming a connection to patch perimeter.

B. Complete repair in accordance with appropriate work item.

C. Do not damage the anode during concrete replacement or allow anode to be soaked with water greater than 20 minutes.

3.5 FIELD QUALITY CONTROL BY TESTING AGENCY
A. Field Observations.

1. Presence of insulating materials.

2. Confirmation of material type installed.

3. Confirmation of material spacing and attachment.

4. Confirmation of material installation in accordance to manufacturer requirements. and as indicated in Contract Documents.

5. Confirm continuity of at least 10 anode locations or up to 5% of repair quantity identified by the Contractor as ready for concrete placement.

END OF SECTION 032117

Page 754 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CAST-IN-PLACE CONCRETE RESTORATION 033021 - 1
SECTION 033021 - CAST-IN-PLACE CONCRETE - RESTORATION
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY
A. This Section specifies cast-in-place concrete, including reinforcement, concrete materials, mix design, placement procedures, and finishes. B. Work in other Sections related to Cast-in-Place Concrete:

1. Division 1 Section “Project Management and Coordination.”

2. Division 1 Section “Quality Control.”

3. Division 1 Section "Submittal Procedures."

4. Division 2 Section "Work Items."

5. Division 2 Section "General Concrete Surface Preparation."

6. Division 2 Section "Surface Preparation for Patching."

7. Division 7 Section “Traffic Coatings.”

8. Division 7 Section “Concrete Joint Sealants.”

9. Division 9 Section “Pavement Marking.”

1.3 DEFINITIONS
A. Cementitious Materials: Portland cement alone or in combination with one or more of blended hydraulic cement, fly ash and other pozzolans, ground granulated blast-furnace slag, and silica fume.

1.4 SUBMITTALS
A. General: In addition to the following, comply with submittal requirements in ACI 301.

B. Product Data: For each type of manufactured material and product indicated.

C. Design Mixes: For each concrete mix. Use form at end of this Section.

D. Testing Agency: Promptly report all field concrete test results to Engineer, Contractor and Concrete Supplier.

Page 755 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CAST-IN-PLACE CONCRETE RESTORATION 033021 - 2

1.5 QUALITY ASSURANCE
A. Installer Qualifications: An experienced installer who has completed concrete work similar in material, design, and extent to that indicated for this Project and whose work has resulted in construction with a record of successful in-service performance.

B. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products complying with ASTM C 94 requirements for production facilities and equipment.

C. Source Limitations: Obtain each type of cement of the same brand from the same manufacturer's plant, each aggregate from one source, and each admixture from the same manufacturer.

D. Comply with ACI 301, "Specification for Structural Concrete," including the following, unless modified by the requirements of the Contract Documents.

1. General requirements, including submittals, quality assurance, acceptance of structure, and protection of in-place concrete.

2. Formwork and form accessories.

3. Steel reinforcement and supports.

4. Concrete mixtures.

5. Handling, placing, and constructing concrete. E. Testing Agency Qualifications:

1. Independent agency, acceptable to authorities having jurisdiction, and acceptable to engineer, qualified according to ASTM C 1077 and ASTM E 329 for testing indicated.

F. Testing Agency is responsible for conducting, monitoring and reporting results of all tests required under this Section. Testing Agency shall immediately report test results showing properties that do not conform to Project Specification requirements to Contractor’s authorized on-site representative and to Owner’s authorized on-site representative.

G. Testing Agency: Submit following Field Test information for Project Concrete unless modified in writing by Engineer:

1. Project name and location.

2. Contractor’s name.

3. Testing Agency’s name, address, and phone number.

4. Concrete supplier.

5. Date of report.

6. Testing Agency technician’s name (sampling and testing).

7. Placement location within structure.

8. Time of batching.

Page 756 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CAST-IN-PLACE CONCRETE RESTORATION 033021 - 3

9. Time of testing.

10. Elapsed time from batching at plant to discharge from truck at site.

11. Concrete mixture identification number.

12. Weather data:
a. Air temperatures.
b. Weather.

13. Field test data:
a. Date, time and place of test.
b. Slump.
c. Concrete Temperature.
d. Slump flow (for SCC).
e. Air content.

14. Compressive test data:
a. Cylinder number.
b. Age of concrete when tested.
c. Date and time of cylinder test.
d. Curing time (field and lab).
e. Cross-sectional area of cylinder.
f. Compressive strength.
g. Type of failure (at break).

1.6 REFERENCES
A. American Concrete Institute (ACI):

1. ACI 117, “Standard Specifications for Tolerances for Concrete Construction and Materials.”

2. ACI 214R, “Evaluation of Strength Test Results of Concrete.”

3. ACI 301, “Specifications for Structural Concrete.”

4. ACI 302.1R, “Guide for Concrete Floor and Slab Construction.”

5. ACI 305R, “Hot Weather Concreting.”

6. ACI 306.1, “Cold Weather Concreting.”

7. ACI 308R, “Guide to Curing Concrete.”

8. ACI 308.1, “Standard Specifications for Curing Concrete.”

9. ACI 318, “Building Code Requirements for Structural Concrete & Commentary.”

10. ACI 347, “Guide to Formwork for Concrete.”

11. ACI 347.2 “Guide to Shoring/Reshoring of Concrete Multistory Buildings.” B.

American Society for Testing and Materials (ASTM):

1. ASTM A 36, “Standard Specification for Carbon Structural Steel.”

Page 757 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CAST-IN-PLACE CONCRETE RESTORATION 033021 - 4

2. ASTM A 185, “Standard Specification for Steel Welded Wire Reinforcement, Plain, for Concrete Reinforcement.”

3. ASTM A 615, “Standard Specification for Deformed and Plain Carbon -Steel Bars for Concrete Reinforcement.”

4. ASTM A 706, “Standard Specification for Low-Alloy Steel Deformed and Plain Bars for Concrete Reinforcement.”

5. ASTM A 775, “Standard Specification for Epoxy-Coated Steel Reinforcing Bars.”

6. ASTM A 884, “Standard Specification for Epoxy-Coated Steel Wire and Welded Wire Reinforcement for Reinforcement.”

7. ASTM C 31, “Standard Practice for Making and Curing Concrete Test Specimens in the Field.”

8. ASTM C 33, “Standard Specification for Concrete Aggregates.”

9. ASTM C 39, “Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens.”

10. ASTM C 94, “Standard Specification for Ready-Mixed Concrete.”

11. ASTM C 138, “Standard Test Method for Unit Weight, Yield, and Air Content (Gravimetric) of Concrete.”

12. ASTM C 143, “Standard Test Method for Slump of Hydraulic Cement Concrete.”

13. ASTM C 150, “Standard Specification for Portland Cement.”

14. ASTM C 171, “Standard Specification for Sheet Materials for Curing Concrete.”

15. ASTM C 172, “Standard Practice for Sampling Freshly Mixed Concrete.”

16. ASTM C 173, “Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method.”

17. ASTM C 231, “Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method.”

18. ASTM C 260, “Standard Specification for Air-Entraining Admixtures for Concrete.”

19. ASTM C 309, “Standard Specification for Liquid Membrane-Forming Compounds for Curing Concrete.”

20. ASTM C 494, “Standard Specifications for Chemical Admixtures for Concrete.”

21. ASTM C 567, “Standard Test Method for Determining the Density of Structural Lightweight Concrete.”

22. ASTM C 618, “Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete.”

23. ASTM C 989, “Standard Specification for Ground Granulated Blast-Furnace Slag for Use in Concrete and Mortars.”

24. ASTM C 1218, “Standard Test Method for Water Soluble Chloride Ion in Mortar and Concrete.”

25. ASTM C 1315, “Standard Specification for Liquid Membrane-Forming Compounds Having Special Properties for Curing and Sealing Concrete.”

26. ASTM C 1611/C 1611M, “Standard Test Method for Slump Flow of SelfConsolidating Concrete.” PART 2 - PRODUCTS

Page 758 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CAST-IN-PLACE CONCRETE RESTORATION 033021 - 5

2.1 FORMWORK
A. Furnish formwork and form accessories according to ACI 301, ACI 347, and ACI 347.2.

2.2 STEEL REINFORCEMENT
A. Epoxy-coated Reinforcing Bars: ASTM A775
B. Epoxy-Coated Welded Wire Fabric: ASTM A884, fabricated from as-drawn steel wire into flat sheets, mats only. Roll stock prohibited.

C. Provide bar supports according to CRSI’s “Manual of Standard Practice.” Use all-plastic bar supports when in contact with exposed concrete surface.

2.3 CONCRETE MATERIALS
A. Ready Mixed Concrete: Obtain concrete from plant with current certification from:

1. Concrete Materials Engineering Council.

2. Massachusetts Department of Transportation.

3. National Ready Mixed Concrete Association.

4. Prestressed Concrete Institute.

B. Portland Cement: ASTM C 150, Types I or II or Type I/II.

C. Fly Ash: ASTM C618, Class C or Class F.

D. Ground-Granulated Blast Furnace Slag: ASTM C989, Gr. 100 or higher.

E. Silica Fume: ASTM C1240.

F. Normal-Weight Coarse Aggregate: ASTM C 33, Crushed and graded limestone or approved equivalent, Class 5S uniformly graded, not exceeding 3/4-inch nominal size.

No cherts, opaline or crushed hydraulic-cement concrete is permitted.

1. Combine Aggregate Gradation: Well graded from coarsest to finest with not more than 18 percent and not less than 8 percent retained on an individual sieve, except that less than 8 percent may be retained on coarsest sieve and on No. 50 sieve, and less than 8 percent may be retained on sieves finer that No. 50.

G. Normal-Weight Fine Aggregate: Natural sand conforming to ASTM C 33 and having preferred grading shown for normal weight aggregate in ACI 302.1R, Table 5.1. H. Water:

Potable and complying with ASTM C 1602.

2.4 ADMIXTURES

Page 759 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CAST-IN-PLACE CONCRETE RESTORATION 033021 - 6
A. General: Admixtures certified by manufacturer to contain no more than 0.1 percent water-soluble chloride ions by mass of cement and to be compatible with other admixtures. Do not use admixtures containing calcium chloride.

B. General: Admixtures certified by manufacturer that all admixtures used are mutually compatible.

C. Admixtures: Use admixtures according to manufacturer's written instructions.

1. Use water-reducing or high-range water reducing admixture in concrete, as required, for placement and workability.

2. Use water-reducing and retarding admixture when required by high temperatures, low humidity, or other adverse placement conditions.

3. Use high-range water-reducing admixture in pumped concrete, concrete for heavyuse industrial slabs, fiber reinforced concrete, and parking structure slabs, concrete required to be watertight, and concrete with a water-cementitious materials ratio below 0.45.

4. Use non-corrosive accelerator for all concrete, less than 8 inches thick, placed at air temperatures below 50 degrees Fahrenheit.

5. Use high range water reducing admixture and viscosity modifying admixture, where required, in Self-Consolidating Concrete (SCC).

6. Use corrosion-inhibiting admixture in parking structure slabs and other areas noted on drawings.

D. Normal Water-Reducing Admixture: ASTM C 494, Type A.

1. Products: Subject to compliance with requirements, provide one of following:
a. “Eucon Series,” Euclid Chemical Co.
b. “WRDA Series,” W.R. Grace & Co.
c. “Master Pozzolith Series,” or “Master PolyHeed Series,” BASF Corporation.
d. “Plastocrete Series”, Sika Corporation.
e. “OptiFlo Series” or “EcoFlo Series,” Premiere Concrete Admixtures. f. “Polychem Series” or “KB Series,” General Resource Technology. g. “LC-400 Series” or “LC-500 Series,” Russ Tech Admixtures, Inc. E.

Mid-Range Water-Reducing Admixture: ASTM C 494, Type A.

1. Subject to compliance with requirements, provide one of following:
a. “Eucon MR” or “Eucon X-15 and X-20,” Euclid Chemical Co. b. “Daracem Series” or “MIRA Series,” W.R. Grace & Co.
c. “Master Polyheed Series,” BASF Corporation.
d. “Sikaplast Series” or “Plastocrete Series”, Sika Corporation. e. “Polychem 1000” or “KB Series,” General Resource Technology. f. “Finishease-NC,” Russ Tech Admixtures, Inc.

Page 760 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CAST-IN-PLACE CONCRETE RESTORATION 033021 - 7
g. “OptiFlo Series” or “EcoFlo Series,” Premiere Concrete Admixtures.

F. High-Range, Water-Reducing Admixture (Superplasticizer): ASTM C 494, Type F.

1. Products: Subject to compliance with requirements, provide one of following:
a. “Eucon 37” or “Eucon SP-Series” or “Plastol Series,” Euclid Chemical Co. b. “Daracem Series” or “ADVA Series,” W.R. Grace & Co.
c. “Master Rheobuild 1000”, “PS 1466” or “Master Glenium Series,” BASF Corporation.
d. “Sikament Series” or “Sika ViscoCrete Series,” Sika Corporation. e. “Melchem Series,” General Resource Technology.
f. “Superflo 443” or “Superflo 2000 Series,” Russ Tech Admixtures, Inc. g. “EcoFlo Series” or “UltraFlo Series,” Premiere Concrete Admixtures.

G. Water-Reducing and Retarding Admixture: ASTM C 494, Type B or D.

1. Products: Subject to compliance with requirements, provide one of following:
a. “Eucon Retarder-75”, “Eucon DS” or “Eucon Stasis.” Euclid Chemical Co. b. “Daratard-17” or “Recover,” W.R. Grace & Co.
c. “MasterSet R Series” or “MasterSet Delvo Series,” BASF Corporation. d. “Sikatard Series,” or “Plastiment Series” or “Plastocrete Series,” Sika Corporation.
e. “Polychem R,” General Resource Technology.
f. “LC-400 Series” or “LC-500 Series,” Russ Tech Admixtures, Inc. g. “OptiFlo Series,” Premiere Concrete Admixtures. H. Air Entraining Admixture: ASTM C260.

1. Products: Subject to compliance with requirements, provide one of following:
a. “Air-Mix,” “Eucon Air-Series” or “AEA-92,” Euclid Chemical Co. b. “Daravair Series” or “Darex Series,” W.R. Grace & Co. c. “Master Air AE90”, or Master Air AE 200”, or “Master Air VR10,” BASF Corporation.
d. “Sika AEA Series,” or “Sika AIR Series,” Sika Corporation. e. “ConAir Series,” Premiere Concrete Admixtures.
f. Polychem “VR” or “VRC” or “Polychem AE,” General Resource Technology. g. “RSA-10,” Russ Tech Admixtures, Inc.

I. Non-Chloride, Non-Corrosive Water-Reducing, Accelerating Admixture: ASTM C 494, Type C or E.

1. Products: Subject to compliance with requirements, provide one of following:

Page 761 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CAST-IN-PLACE CONCRETE RESTORATION 033021 - 8
a. “Eucon AcN-Series,” “Accelguard 80,” “Accelguard NCA,” or “Accelguard 90,” by Euclid Chemical Company.
b. “DCI,” “PolaraSet,” “Lubricon NCA,” “Daraset” or “Gilco,” by W.R. Grace & Co.
c. “MasterSet FP 20” or “MasterSet AC 534,” by BASF Corporation. d. “Sika Set NC,” “Plastocrete 161FL”, or “Sika Rapid-1,” by Sika Corporation. e. “Catexol 2000 RHE,” by Axim Concrete Technologies.
f. “Polychem NCA” or “Polychem Super Set,” General Resource Technology. g. “LCNC-166,” Russ Tech Admixtures, Inc.

J. Corrosion Inhibiting Admixture shall be capable of forming a protective barrier and minimizing chloride reactions with steel reinforcement in concrete.

1. Products: Subject to compliance with requirements, provide one of the following:
a. “Eucon CIA” or “Eucon BCN,” Euclid Chemical Company. b. “DCI” or “DCI-S,” W.R. Grace.
c. “MasterLife CI 30,” BASF Corporation.
d. “Sika CNI,” Sika Corporation.
e. “Catexol 1000 CN-CI,” Axim Concrete Technologies.
f. “Polychem CI,” General Resource Technology.
g. “Russ Tech RCI,” Russ Tech Admixtures, Inc.

2. Add at rate of 3 gal/cu yd. of concrete, which shall inhibit corrosion to 9.9 lb of chloride ions per cu. yd. of concrete. Calcium Nitrite based corrosion inhibitor shall have a concentration of 30 percent, plus or minus 2 percent of solids content.

2.5 CURING MATERIALS
A. Evaporation Retarder: Waterborne, monomolecular film forming, manufactured for application to fresh concrete.

1. Evaporation Retarder:
a. AquaFilm J74 by Dayton Superior Corporation, Miamisburg, OH b. Eucobar; Euclid Chemical Co.
c. E-Con; L&M Construction Chemicals, Inc.
d. MasterKure ER 50; BASF Corporation.
e. SikaFilm; Sika Corporation.
f. Sure-Film (J-74); Dayton Superior Corporation.
g. “EVRT”, Russ Tech Admixtures, Inc.
h. “Barrier,” Premiere Concrete Solutions.

B. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. (305 g/sq. m) dry. Materials must be free of harmful substances, such as sugar or fertilizer, or substances that may discolor the concrete. To

Page 762 of 1055 ends

City Of Hermosa Beach Construction Document
Parking Structure Lot “C” Improvements January 2025
C.I.P No. 699

CAST-IN-PLACE CONCRETE RESTORATION 033021 - 9
remove soluble substances, burlap should be thoroughly rinsed in water before placing it on the concrete.

C. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.

D. Water: Potable.

2.6 CONCRETE MIXTURES
A. Proportion mixtures determined by either laboratory trial mix or field test data bases, as follows:

1. Proportion normal-weight concrete according to ACI 211.1 and ACI 301.

2. Provide different mixtures as the season warrants, as well as each type and strength of concrete or for different placing methods.

B. Use a qualified independent testing agency for preparing and reporting proposed Mixture Proportions for the laboratory trial mix basis.

C. Requirements for normal-weight concrete mix are shown on Drawings:

1. Compressive strength

2. Slump

3. Water-cementitious materials ratio

4. Air content
D. Supplementary cementitious materials: For concrete exposed to deicers, limit percentage, by weight, of cementitious materials according to ACI 318 requirements. E. Air Entrainment:

1. See General Notes on Drawings for total average air content (percent by volume).

2. Average air content shall exceed value stated in General Notes on Drawings.

3. Permissible variation for any one test result from specified average total air content: plus or minus 1.5 percent unless noted otherwise on General Notes on Drawings.

4. Hardened concrete shall have an air void spacing factor of 0.0080 in. maximum.

Specific surface (surface area of air voids) shall be 600 in2 per cu in. of air-void volume, or greater. Concrete mixes not meeting these values as determined by ASTM C 457 may require adjustments unless accepted in writing by Engineer.” F.

Chloride Ion Content of Mixture:

1. Water soluble chloride ion content of concrete shall not exceed 0.06 percent by weight of cement for pre-stressed concrete and 0.15 percent for reinforced concrete. (ACI 318 Chapter 4 Table 4.4.1“Maximum Chloride Ion Content for Corrosion Protection of Reinforcement”) Testing procedure to determine chloride ion content shall conform to ASTM C 1218.

Page 763 of 1055 ends