West Yost – December 2024
270-30-23-22
01340 - 1
Requestsfor Information and Clarifications
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 01340
REQUESTS FOR INFORMATION AND CLARIFICATIONS
PART 1 - GENERAL
2.01 SECTION INCLUDES
A. Procedures for submitting requests for information and clarifications when Contractor discovers apparent conflicts, omissions, or errors in the Contract Documents, or upon having any questions concerning interpretation of the Contract Documents.
2.02 REFERENCED SECTIONS
A. The following Section is referenced in this Section
1. General Conditions
2.03 PROCEDURES
A. Notification:
1. Notify the City in writing and request interpretation, clarification, or additional detailed instructions concerning the Work.
2. Ask for clarification or request information immediately upon discovery, but no less than seven working days prior to the start date of the activities related to the clarification, based on the latest updated version ofthe official contractschedule.
B. Form:
1. Submit requests for clarification and/or additional information in writing to the City using the City’s Request for Information (RFI) form.
2. Provide a detailed statement indicating the nature of the information requested.
Reference specific Drawings and Specifications as appropriate.
3. Limit each written request to one topic.
4. Electronic (*.pdf) format RFIs are preferred. Prepare RFIs and any attachments in electronic format. Transmit electronic RFIs via email to the City. Break down RFIs that are larger than 10 megabytes into smaller sections, using logical division points to create sections.
5. Hard copy RFIs are an acceptable alternative to electronic RFIs if the Contractor demonstrates, to the satisfaction of the City, that electronic format presents a hardship.
C. Numbering:
1. Use consecutive numbers for each new form submitted. When RFI’s are re-submitted to request additional information on the same topic, add a letter A, B, C, etc. to the numbering system for each subsequent RFI until the subject is resolved.
West Yost – December 2024
270-30-23-22
01340 - 2
Requestsfor Information and Clarifications
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2.04 REASONS FOR SUBMITTING RFI
A. Submit an RFI if one of the following conditions occur:
1. An unforeseen condition or other circumstance that is not described in the Contract Documents.
2. An apparent conflict or discrepancy between portions of the Contract Documents.
3. An apparent omission from the Contract Documents.
4. Information presented in the Contract Documentsis unclear or additional details are needed to undertake the Work.
2.05 RESPONSE TIME
A. The City will resolve the RFI and issue instruction to the Contractor within ten (10) working days.
B. Response time may need to be lengthened; or shortened for emergency situations as mutually agreed upon by all parties.
C. Do not proceed with the affected work before receipt of a response from the City. Should the Contractor elect to proceed with the Work affected by the RFI, any portion of the Work that is not done in accordance with the City’s interpretation, clarifications, instructions or decisions will be subject to removal or replacement at the Contractor’s expense.
2.06 REJECTIONS
A. RFI’s submitted by the Contractor may be rejected by the City for the following reasons:
1. The RFI is submitted as a substitute for a submittal.
2. Under the pretense of a Contract Documents discrepancy or omission without thoroughly reviewing the documents.
3. In a manner that suggests that specific portions of the Contract Documents are assumed to be excluded or be taken as an isolated portion of the Contract Documents in part rather than whole.
4. In an untimely manner without proper coordination and scheduling of work or related trades.
2.07 ADDITIONAL DETAILED INSTRUCTIONS (CLARIFICATIONS)
A. The City may furnish additional detailed written instructions to further explain the Work and these instructions shall become part of the Contract Documents. Clarifications will be issued using the above RFI system.
B. When, in the opinion of the Contractor, the Engineer’s response in the RFI constitutes additional work beyond the scope of the Contract, the Contractor shall notify the City in writing following receipt of the RFI and prior to initiating the Work affected by the RFI. The process for submitting claims of additional Work shall be followed as defined in the General Conditions. Lack of compliance with this notification requirement will cause Contractor to forfeit any claim for additional compensation or extension of the schedule.
West Yost – December 2024
270-30-23-22
01340 - 3
Requestsfor Information and Clarifications
City of Milpitas
WellUpgrades Program
McCandless Well Facility
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION
West Yost – December 2024
270-30-23-22
01340 - 4
Requestsfor Information and Clarifications
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
West Yost – December 2024
270-30-23-22
01400 - 1
Construction Staking
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 01400
CONSTRUCTIONSTAKING
PART 1 - GENERAL
1.01 DATUM
A. Vertical and horizontal datum are based on the coordinates and benchmarks shown on the Drawings or as provided by the City prior to the start of construction. Locate and protect City’s furnished control points prior to starting the Work and preserve control points during construction. Re-establish control points disturbed by operations at no cost to the City.
B. Establish other vertical and horizontal control from these reference points as required to properly layout and construct the Work. Install connections based on actual elevations of existing structures to which connections are made.
1.02 ACCURACY OF INFORMATION
A. Dimensions for existing structures, piping, paving, and other nonstructural items are taken from the available information provided by the City. Field verifies dimensions and conditions in advance of any construction in the area. Any discrepancy between the field survey by the Contractor and the information indicated in the Contract Documents shall be immediately brought to Engineer’s attention by written notification.
1.03 LAYOUT AND MEASUREMENT TO BE PERFORMED BY CONTRACTOR A. Contractor is responsible for conducting field surveys required to lay out components of the Work at the proper alignment, elevation, grades, dimensions, and distances indicated on the Drawings.
B. Lay out the Work from the lines and grades provided by the City and from the dimensions and elevations provided on the Drawings. Contractor is responsible for measurements required for the execution of the Work.
C. Furnish stakes, equipment, tools, materials, and labor as required for layout work.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION
West Yost – December 2024
270-30-23-22
01400 - 2
Construction Staking
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
West Yost – December 2024
270-30-23-22
01500 - 1
Construction Facilities and Utilities
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 01500
CONSTRUCTION FACILITIES AND UTILITIES
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Requirements for Contractor’stemporary facilities at the job site and for the prosecution of the Work.
1.02 CONTRACTOR’S CONSTRUCTION OFFICE
A. Maintain a suitable office at the site.
B. Temporary office will be considered as the headquarters of the Contractor’s representative whom is authorized to receive drawings, instructions, or other communication or articles. Any communication given to the representative or delivered at Contractor’s temporary office at the site in his absence is deemed to have been delivered to the Contractor.
C. Maintain copies of the Drawings, Specifications, and other Contract documents at Contractor’s temporary office at the site and make these available for use at all times.
1.03 ACCESS ROADS AND PARKING AREAS
A. Access Road: The existing AC paved access roads through the Park from McCandless Drive to the well facility are intended to serve the well facility and be large enough to support fire department vehicles. Any damage to the access roads by the well facility contractor shall be repaired at well facility contractor cost.
B. Parking: Contractorshall assume that parking will not be available outside the Work Area.
1.04 STAGING AREA
A. Proposed Large Dog Park Play Area at north of the well site can be used as staging area for the construction of the well facility project. Before starting the work, submit a proposed plan and layout for all temporary offices, sanitary facilities, storage areas, temporary waterservice and distribution, and temporary power service and distribution.
B. Provide security and facilities to protect the work from unauthorized entry, vandalism, or theft. The contractor may choose to utilize the existing temporary fencing around the well site but is responsible for removing all temporary fencing at their own cost upon completion of the project. The City will not be held responsible for any missing or damaged equipment, tools, or personal belongings.
C. Store only those materials and equipment that are related to the construction within the staging area.
1.05 WORKSHOP AND STORAGE FACILITIES
A. The Contractorshall provide storage facilities for the protection of equipment, materials, supplies and tools, and shall insure that the facilities used for the storage of materials which deteriorate when exposed to moisture is moisture-proof. Workshops and storage facilities shall be located as designated by the City, and shall be clean and in proper order at all times.
West Yost – December 2024
270-30-23-22
01500 - 2
Construction Facilities and Utilities
City of Milpitas
WellUpgrades Program
McCandless Well Facility
1.06 SAFETY AND PROTECTIVE BARRIERS
A. Along shared existing AC paved access road: Install appropriate barriers such as temporary fencing, plastic drums, or concrete traffic barriers to protect public from construction areas and to protect workers and existing facilities from danger of passing vehicles.
B. Temporary Fences:
1. Prior to commencing construction, inspect the existing temporary fencing along the property boundary as shown in the drawing and confirm that it is structurally intact. Repair or replace any damaged or broken fencing as necessary.
2. Maintain work activities within the confines of the temporary fences.
3. Remove temporary fences when work in the vicinity issubstantially complete.
C. Provide protective concrete slabs, steel plates or encasements for existing buried facilities that may be damaged by Contractor’s equipment and vehicles.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.01 TEMPORARY ELECTRIC POWER
A. Contractor shall make provisions to obtain temporary electric power for use during construction. The Contractor shall be responsible for obtaining a source of electric power for construction.
B. Cost of electric power shall be borne by the Contractor.
C. The temporary electric power installation shall meet the construction safety requirements of OSHA, state, and other governing agencies.
3.02 TEMPORARY TELEPHONE SERVICE
A. Provide telephone service at the construction site office. Cellular telephone service is acceptable.
3.03 TEMPORARY SANITARY FACILITIES
A. Provide toilet and wash-up facilities for the construction work force at the site of work.
B. Facilities shall comply with applicable laws, ordinances, and regulations pertaining to the public health and sanitation of construction field offices, dwellings, and camps.
3.04 TEMPORARY WATER SUPPLY
A. Refer to Section 3.8.C – Construction Water in General Requirements for detail information.
END OF SECTION
West Yost – December 2024
270-30-23-22
01500 - 3
Construction Facilities and Utilities
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
West Yost – December 2024
270-30-23-22
01560 - 1
Environmental Controls
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 01560
ENVIRONMENTAL CONTROLS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Environmental controls to be maintained during construction.
1.02 APPLICABLE LAWS AND REGULATIONS
A. Comply with applicable Federal, State and local environmental, health and safety laws and regulations.
1.03 ENVIRONMENTAL IMPACT MITIGATION MEASURES
A. Comply with all environmental mitigation measures that are included in the Contract Documents. See General Requirements, Appendix B.
1.04 SITE CLEANLINESS
A. Maintain work sites, staging areas, public roadways and private property clean and free of rubbish and debris. Remove materials and equipment from the site when they are no longer necessary for the Work.
B. Keep buildings that are occupied by the Contractor clear of refuse and debris and in a reasonably neat condition.
C. Upon completion of the work and before final acceptance, clear work areas of equipment, unused materials, and rubbish to present a clean and neat appearance.
1.05 HAZARDOUS MATERIALS
A. Handle paints, solvents, and other construction materials with care to prevent contaminants from entering into sewers, storm drains, surface waters, or soils.
B. Develop an emergency response plan for spills of sewage, paint, oil, and other hazardous materials.
C. In the event of a spill, immediately notify the City and jurisdictional agencies. Take proper measures to clean up spills of hazardous materials in accordance with the emergency response plan, State, Federal, and local regulations and manufacturer’s recommendations.
1.06 AIR POLLUTION CONTROL
A. Contractorshall not discharge smoke, dust, and other contaminants into the atmosphere that violate the air pollution regulations for the area.
B. Do not idle internal combustion engines for prolonged periods of time.
C. Minimize dust nuisance by cleaning, sweeping and sprinkling work areas, exposed soil, and haul roads with water or by powered brushing.
1.07 NOISE CONTROL
A. Comply with local controls and noise level rules, regulations, and ordinances which apply to any work performed pursuant to the Contract. If the requirements of this Section are
West Yost – December 2024
270-30-23-22
01560 - 2
Environmental Controls
City of Milpitas
WellUpgrades Program
McCandless Well Facility
more restrictive than those of the local regulations, the requirements of this Section shall govern.
B. Minimize noise from construction equipment.
1. Whenever possible, utilize construction equipment powered by electric motors rather than diesel or gas driven engines.
2. Locate construction equipment such as compressors and generators as far from sensitive receptors as feasibly possible. Erect temporary sound blankets around noisy equipment to mitigate noise propagation.
3. Equip internal combustion engines with a muffler and provide a noise enclosure around stationary equipment such as engine-driven generators, welders, compressors, and pumps. Use “quiet package” and “hush” equipment.
4. Do not start-up machines or equipment prior to or after the specified construction work hours.
C. Noise Complaints: Should a specific noise impact complaint occur, Engineer has the prerogative to direct Contractor to implement one of the following noise mitigation measures at Contractor’s expense:
1. Relocate stationary construction equipment away from the affected property.
2. Shut off idling equipment.
3. Reschedule construction operations to avoid periods of noise annoyance identified in the complaint.
4. Install temporary or portable acoustic barriers around stationary construction noise sources.
5. Operate electric powered equipment using utility power.
D. Amplified sounds such as telephone, loudspeakers, and other forms of loud communication that constitute a nuisance and potential disturbance shall not be used.
E. See General Requirements, Appendix B for additional construction noise control measures.
1.08 DIRT AND MUD CONTROL
A. Contractor is responsible for preventing dirt, mud, and debris from accumulating on streets, sidewalks, parking areas, or other paved surfaces and for maintaining the cleanliness of these areas.
1. Track Out: Clean vehicle tires of mud and dirt before exiting the site.
2. Cover all dump truck loads and other loads that may result in debris falling from the vehicle.
3. Sweeping Paved Areas:
a. Maintain cleanliness of paved areas used by the Contractor for the duration of the project.
b. Sweep paved areas that have been used since the previous cleaning on at least a weekly basis, or more frequently when directed by the
West Yost – December 2024
270-30-23-22
01560 - 3
Environmental Controls
City of Milpitas
WellUpgrades Program
McCandless Well Facility
Engineer. Utilize regenerative air or vacuum pickup sweepers together with proper dust control methods to remove sediment, dust, dirt, and other matter from paved areas. Do not use excessive water resulting in mud on public streets.
1.09 OIL SPILL PREVENTION AND CONTROL
A. Store fuel and oil in accordance with requirements of the Uniform Fire Code and applicable National Fire Protection Association standards.
B. Assume responsibility for the prevention, containment, and cleanup of spilled oil, fuel, and other petroleum products used in the Contractor’s operations. Prevention, containment and cleanup costs shall be borne by the Contractor.
C. Periodically inspect fuel hoses, lubricating equipment, hydraulically operated equipment, oil drums, and other devices for drips, leaks or signs of damage. Maintain and properly store to prevent spills and vandalism.
D. Construct dikes around storage tanks, or locate tanks to prevent spills from escaping to surface waters or drainage ditches.
E. Remove oils on land using sand, clay, sawdust or other absorbent material and dispose in an acceptable manner. Store waste materials in drums or other leak proof containers after cleanup and during transport to disposal.
1.10 DISPOSAL OPERATIONS
A. Solid Waste Management
1. Store garbage in covered containers. Empty daily and dispose of waste in sanitary landfill.
2. Provide solid waste transfer containers. Take care to prevent trash from blowing onto adjacent property. Convey contents to a sanitary landfill regularly. Do not allow containers to overflow.
3. Washing of concrete containers where wastewater may reach adjacent property or natural water courses is not permitted. Remove any excess concrete to the sanitary landfill.
B. Chemical Waste
1. Provide containers to store spent chemicals used during construction and startup testing operations.
2. Dispose of chemicals and hazardous materials in accordance with applicable regulations.
C. Excavated Material
1. Comply with requirementsin Section 02300.
D.
1. Water used for testing and disinfection may be disposed of into the sanitary sewer through the sewer connection at the project site.
West Yost – December 2024
270-30-23-22
01560 - 4
Environmental Controls
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2. Water discharged into the sewer shall be metered. The discharged flow rate into the sewer shall not exceed 250 gpm to prevent overwhelming the sewer system.
Provide temporary holding tanks, flow meter, and throttle valves as needed to allow metering the water disposed into the sewer.
3. Under no circumstances shall the wastewater from testing and disinfection be discharged, bypassed, or spilled to creeks, drainage ditches, other waterways, storm drain system, or the ground surface.
a. In the event of accidental discharge or bypassing caused by the Contractor’s operations, the City shall immediately be entitled to employ others to stop the discharge or bypassing without written notice to the Contractor. All cost incurred by the City to stop or prevent the discharge or bypass shall be paid for by the Contractor.
b. Penalties imposed on and costs incurred by the City as a result of violations caused by the actions of the Contractor, his employees, or subcontractors, shall be borne in full by the Contractor, including legal fees and other expenses to the City resulting directly or indirectly from Contractor’s actions.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION
West Yost – December 2024
270-30-23-22
01600 - 1
Materials and Equipment
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 01600
MATERIALS AND EQUIPMENT
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Materials, equipment and products incorporated into the work.
1.02 MATERIAL AND EQUIPMENT REQUIREMENTS
A. Specified in individual specification Sections in Divisions 2 through 16.
B. Specifications are minimum requirements and manufacturers’ standard products may require modifications to meet the specified requirements.
C. Provide products and equipment with all accessories, trim, finish,safety guards and other devices needed for a complete and operational installation.
D. Products to be supplied in quantity shall be the same product from a single source to provide standardization and interchangeability.
1.03 DEFINITIONS
A. Named Products: Itemsidentified by manufacturer’s product name andmodel number as indicated in the manufacturer’s published product data.
B. Materials: Products that are shaped, cut, worked, finished or otherwise fabricated or installed to form a part of the Work.
C. Equipment: A product with working parts, whethermotorized or manually operated, that requires connections such as wiring or piping.
1.04 PACKAGING AND MARKING
A. Equipment shall be protected against damage from moisture, dust, handling, or other cause during transport from manufacturer’s premises to site. Each item or package shall be marked with the number unique to the specification reference covering the item.
B. Stiffeners shall be used where necessary to maintain shapes and to give rigidity. Parts of equipment shall be delivered in assembled or subassembled units where possible.
C. Bearing housings, vents and othertypes of openingsshall be wrapped or otherwise sealed to prevent contamination by dust and dirt.
1.05 SHIPPING AND DELIVERY
A. Plan, order, coordinate and deliver materials and equipment in accordance with the construction schedule to avoid delays and conflicts with the Work.
B. Deliver anchor bolts and bolt templatessufficiently early to permitsetting and placement in structural concrete.
C. Unload products in accordance with the manufacturer’s handling instructions. Promptly inspect for completeness and evidence of damage during shipment.
West Yost – December 2024
270-30-23-22
01600 - 2
Materials and Equipment
City of Milpitas
WellUpgrades Program
McCandless Well Facility
1.06 HANDLING AND STORAGE
A. During the interval between the delivery of equipment to the site and installation, all equipment, unless otherwise specified, shall be stored in an enclosed space affording protection from weather, dust and mechanical damage and providing favorable temperature, humidity and ventilation conditions to ensure against equipment deterioration. Manufacturer’s recommendations shall be adhered to in addition to these requirements.
B. Equipment and materials to be located outdoors may be stored outdoors if protected against moisture condensation. Equipment shall be stored at least 6 inches above ground.
Temporary power shall be provided to energize space heaters or other heat sources for control of moisture condensation. Space heaters or other heat sources shall be energized without disturbing the sealed enclosure.
C. Fabricated products, pipe and pipe appurtenancesshall be handled,stored off the ground on blocking or skids. Pipes with paint, tape coatings, linings or the like shall be stored to protect the coating or lining from physical damage or other deterioration. Pipes shipped with interior bracing shall have the bracing removed only when recommended by the pipe manufacturer.
D. Store loose granular products in well-drained area on a solid surface to prevent mixing with foreign matter. Cover products that are subject to erosion or deterioration with plastic sheeting.
E. Store electrical, instrumentation and control products in a water-tight enclosure to protect against damage from moisture, dust and corrosion.
1.07 PROTECTION OF EQUIPMENT AFTER INSTALLATION
A. After installation, protect equipment from damage from, including but not limited to, dust, abrasive particles, debris and dirt generated by the placement, chipping, sandblasting, cutting, finishing and grinding of new or existing concrete, terrazzo and metal; and from the fumes, particulate matter, and splatter from welding, brazing and painting of new or existing piping and equipment.
B. As a minimum, vacuum cleaning, blowers with filters, protective shielding, and other dust suppression methods will be required at all times to adequately protect all equipment.
C. When sandblasting or when finishing concrete, all equipment that may be affected by cement dust shall be completely covered. Electrical switchgear, substations and motor load centers shall not be installed until after all concrete work and sandblasting in those areas have been completed and accepted and the ventilation systems installed.
D. During painting operations, all grease fittings and similar openings shall be covered to prevent the entry of paint.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.01 INSPECTION
A. Prior to installation, inspect materials and equipment for signs of corrosion and other effects of storage. Do not install material or equipment showing such effects.
West Yost – December 2024
270-30-23-22
01600 - 3
Materials and Equipment
City of Milpitas
WellUpgrades Program
McCandless Well Facility
B. Remove damaged material from the site and expedite delivery of replacement material or equipment. Delays to the Work resulting from material or equipment damage that necessitates procurement of new products will be considered delays that are within the Contractor’s control.
3.02 INSTALLATION
A. Handle, install, connect, clean and adjust productsin accordance with the manufacturer’s instructions.
B. Fill lubricant reservoirs and grease bearings prior to starting equipment. Use lubricants recommended by the manufacturer of the equipment.
C. Recoat painted surfaces that are damaged prior to final acceptance of the Work.
END OF SECTION
West Yost – December 2024
270-30-23-22
01600 - 4
Materials and Equipment
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
PASE – December 2024
270-30-23-22
01610 - 1
Seismic Anchorage and Bracing
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 01610
SEISMIC ANCHORAGE AND BRACING
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Requirements for seismic anchorage and bracing for equipment, tanks, pipe, ducts, conduit and other nonstructural components.
1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section
1. Section 01330 – Submittals
2. Section 01611 – Seismic Design Requirements
3. Section 05501 – Anchor Bolts
1.03 AREAS OF DESIGN RESPONSIBILITY
A. The Contractor shall be responsible for:
1. Designing seismic attachments, braces, and anchors to the structure for tanks, mechanical equipment and electrical equipment included in the Work that weigh more than 20 pounds.
2. Design of seismic anchorage and bracing for piping systems and ventilation ducting.
B. Equipment manufacturers shall provide design calculations and details for their specific pieces of equipment as part of the submittal for that equipment.
1.04 REFERENCES
A. The following is a list of standards which may be referenced in thissection.
1. International Code Council (ICC)
2. California Building Code (CBC)
3. Evaluation Service (ICC-ES) Reports and Legacy Reports
4. American Society of Civil Engineers (ASCE): ASCE 7, Minimum Design Loads for Building and Other Structures.
1.05 SUBMITTALS
A. Comply with Section 01330.
B. Seismic Anchorage and Bracing Calculations
1. Submit manufacturer’s engineered seismic hardware data and installation requirements.
2. Provide calculations for seismic attachments, braces and anchorages clearly showing the criteria used for the design. Calculations for anchorage of components shall be sealed by a California registered Civil Engineer.
PASE – December 2024
270-30-23-22
01610 - 2
Seismic Anchorage and Bracing
City of Milpitas
WellUpgrades Program
McCandless Well Facility
C. Shop Drawings: Show details of seismic attachment assemblies including connection hardware, bracing, and anchor bolts.
1.06 DESIGN AND PERFORMANCE REQUIREMENTS
A. In accordance with CBC, tanks, mechanical and electrical components, and other elements of the Work that are permanently attached to structures shall be designed and constructed to transfer the component seismic forces specified in ASCE 7, Chapter 13 to the structure.
B. Seismic attachments, braces, and anchorages shall be designed in accordance with the provisions of the California Building Code and the site-specific criteria in Section 01611.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Attachments and supportstransferring seismic loadsto the structure shall be constructed of materials and products suitable for the application and designed and constructed in accordance with the design criteria shown on the Drawings and nationally recognized standards.
B. Powder driven fasteners and sleeve anchors shall not be used for seismic attachments and anchorage where resistance to tension loads is required.
C. Anchor Bolts: In accordance with Section 05501.
PART 3 - EXECUTION
3.01 GENERAL
A. Design seismic anchorage systems to provide restraint in all directions, for each component or system so anchored.
B. Tall and narrow equipment such as motor control centers and electrical control panels shall be anchored at the base and within 12 inches from the top of the equipment.
C. Mechanical and electrical components shall not be attached to more than one element of a building structure at a single restraint location where such elements may respond differently during a seismic event. Such attachments shall also not be made across building expansion and contraction joints.
D. Seismic attachments and braces shall be provided and installed by the Contractor in accordance with the size and number of braces determined by the design calculations prepared by the Contractor.
E. Anchor bolts and concrete and masonry anchors for the anchorage of equipment shall be provided and installed by the Contractor in accordance with the bolt sizing, minimum embedment, and spacing requirements determined by the calculations prepared by the Contractor.
END OF SECTION
PASE – December 2024
270-30-23-22
01611 - 1
Seismic Design Requirements
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 01611
SEISMIC DESIGN REQUIREMENTS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. The following primary and secondary structural system elements, non-structural components, and/or equipment supported by structures.
1. Pre-Engineered Metal Buildings and Canopies.
2. Mechanical, electrical, and plumbing equipment and appurtenances.
3. Conduit, piping, cable trays, raceways, ducts and similar systems.
4. Tanks and vessels (include contents), including support systems.
5. Storage racks, suspended ceilings, light fixtures, raised floors, partitions, storefronts, windows, louvers, architectural features and other non-structural components.
1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section
1. Section 01330 – Submittals
2. Section 05501 – Anchor Bolts
1.03 REFERENCES
A. 2022 California Building Code (CBC)
1.04 DEFINITIONS
A. Engineer of Record: The Engineer responsible forthe preparation of Contract Documents.
B. Specialty Engineer: Structural or Civil Engineer provided by the Contractor licensed in the State where the project is being built responsible for specific elements of the primary structural system, the secondary structural system, non-structural elements and/or equipment supported by structures.
1.05 GENERAL DESIGN REQUIREMENTS
A. The Contractor is responsible for producing designs that resist the total seismic forces in accordance with the seismic design criteria.
B. The Contractor is responsible for coordinating between the Engineer of Record and the Specialty Engineer.
C. The seismic design for non-structural components and equipment shall be in accordance with the CBC Chapter 16, and the required coefficients and factors for determining the total design seismic forces are provided in the Seismic Design Criteria in Paragraph E below.
D. Coordinate the layout so that adequate space is provided between items for relative motion. Provide additional supports and restraints between items of different systems when necessary to prevent seismic impacts or interaction.
PASE – December 2024
270-30-23-22
01611 - 2
Seismic Design Requirements
City of Milpitas
WellUpgrades Program
McCandless Well Facility
E. Seismic forces shall be determined in accordance with the following seismic design criteria:
1. Site-Specific Spectral Response Coefficients
a. Short Period Mapped Maximum Considered Earthquake, 5 Percent Damped: Ss = 1.833g
b. 1 Second Period Mapped Maximum Considered Earthquake, 5 Percent Damped: S1 = 0.698g
c. Short Period Design Spectral Response Acceleration, 5 percent Damped:
SDS = 1.077g
d. 1 Second Period Design Spectral Response Acceleration, 5 percent Damped: SD1 = 2.088g
2. Site Class: E
3. Seismic Design Category: D, unless noted otherwise
4. Risk Category: III, unless noted otherwise
5. Component Importance Factor, Ip:
a. Mechanical and Electrical Equipment: Use 1.5.
b. Tanks and Tank Anchorage: Use 1.5.
c. Components that contain hazardous materials: Use 1.5. d. Components that are required for life safety: Use 1.5. e. Components that must remain functional after an earthquake, such as fire protection sprinkler systems: Use 1.5.
6. Do not use more than 60 percent of the weight of tanks and mechanical and electrical equipment for designing anchors for resisting overturning due to seismic forces.
7. Do not use friction to resist sliding due to seismic forces.
1.06 DESIGN REQUIREMENTS FOR PIPING, CONDUIT, AND DUCTS A. The Contractor is responsible for producing designs for support of piping, conduit, duct or other systems to resist total seismic forces based on the seismic design criteria coefficients specified above, unless shown on the Contract Documents. Except where the technical specifications give specific exemption from resistance of seismic forces, all supports shall be designed to meet seismic criteria.
B. Where possible, pipes, conduit, and their connections shall be constructed of ductile materials (e.g., copper, ductile iron, steel or aluminum and brazed, welded or screwed connections). Pipes, conduits and their connections, constructed of nonductile materials (e.g., cast iron, no-hub pipe and plastic), shall have the brace spacing reduced to one-half of the spacing allowed for ductile material.
C. Seismic restraints may be omitted for the following conditions, where flexible connections are provided between components and the associated ductwork, piping and conduit:
1. Fuel piping less than 1-inch inside diameter.
PASE – December 2024
270-30-23-22
01611 - 3
Seismic Design Requirements
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2. All other piping less than 2.5-inches inside diameter or all piping suspended by individual hangers 12 inches or less in length from the top of the pipe to the bottom of the structuralsupport for the hanger or electrical conduit lessthan 2.5- inches trade size.
3. All rectangular air-handling ducts less than 6 square feet in cross-sectional area or all-round air-handling ducts less than 28-inches diameter or all ducts suspended by individual hangers 12 inches or less in length from the top of the duct to the bottom of the structural support for the hanger, where the hangers are detailed to avoid bending of the hangers and their connections.
D. All trapeze assemblies supporting pipes, ducts and conduit shall be braced to resist the total seismic forces considering the weight of the elements on the trapeze. Pipes, ducts and conduit supported by a trapeze where none of those elements would individually be braced need not be braced if connections to the pipe/conduit/ductwork or directional changes do not restrict the movement of the trapeze. If this flexibility is not provided, bracing will be required when the aggregate weight of the pipes and conduit exceed 10 pounds/foot. The weight shall be determined assuming all pipes and conduit are filled with water.
E. As an alternative to designing the supports and anchorage, where an approved national standard provides a basis for the earthquake-resistant design, submit standard, data, and details for piping, conduit, duct or other systems:
1. For ductwork, mechanical piping, process piping and electrical conduits, follow Guidelines for Seismic Restraints of Mechanical Systems by SMACNA modified as follows:
a. Seismically brace piping regardless of size or location. Provide transverse braces at all changes in direction and at the end of all pipe runs. Space transverse braces not more than 20 feet apart. Provide longitudinal braces at 40-foot centers.
b. Seismically brace all ductwork regardless of size or location. Provide transverse braces at all changesin direction and at each end of run. Space braces not over 20 feet apart. Provide longitudinal braces at 40-foot centers.
2. For fire protection systems, follow NFPA 13 modified as in Paragraph 1.b above.
Ensure that no seismic interaction occurs with items of other systems.
1.07 DESIGN REQUIREMENTS FOR UNDERWATER ITEMS
A. To allow for water sloshing, design rigid items such as piping or equipment supports for twice the lateral force, computed as if the item were above water.
B. Design flexible items to accommodate sloshing motions without damage to rigid machinery.
C. Provide retainers to hold items from falling and damaging rotating equipment below, if bolted connections will fail because of ground motion displacing the supports.
1.08 SUBMITTALS
A. Comply with Section 01330.
PASE – December 2024
270-30-23-22
01611 - 4
Seismic Design Requirements
City of Milpitas
WellUpgrades Program
McCandless Well Facility
B. Shop Drawings
1. Submit signed and sealed structural calculations and detailed drawings for the following listed elements and where required in Divisions 2 through 16 of the primary structuralsystem and their attachments, the secondary structuralsystem and their attachments, permanent non-structural components and their attachments, and the attachments and anchorage for all permanent equipment supported by the structures.
C. Structural calculations and detailed drawings shall be prepared by a Specialty Engineer licensed in the State where the project is being built.
D. Structural calculations and detailed drawings shall clearly show the total design seismic forces which will be transferred from the elements of the structural system, nonstructural components, and/or equipment and their attachments to the primary structure.
E. The Engineer's review of items within a Specification Section cannot be completed until all related items have been coordinated and submitted for review.
F. Quality Assurance Submittals
1. Test Reports: Submit test reports for tension testing of anchors.
2. Where required in the equipment specifications in Divisions 2 through 16 submit certification that the equipment itself is designed to resist all internal seismic forces based on the seismic design criteria for the project.
3. Where required in the equipmentspecificationsin Divisions 2 through 16, submit signed and sealed structural calculations and detailed drawings from a specialty Structural or Civil Engineer licensed in the State where the project is being built for the attachments and anchorage to the primary structure.
4. Where required in the equipmentspecificationsin Divisions 2 through 16, submit certification that the attachments and anchorage are designed to resist allseismic forces based on the seismic design criteria for the project.
1.09 QUALITY ASSURANCE
A. Qualifications: The Contractor is responsible for submitting signed and sealed structural calculations and detailed drawings from a Specialty Structural or Civil Engineer licensed in the State where the project is being built.
B. Regulatory Requirements: Comply with the State of California adopted and amended versions of CBC Chapter 16 - Earthquake Design plus clarifications and additions specified in this Section.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.01 FIELD QUALITY CONTROL
A. Site Tests: Tension testing of expansion or adhesive anchors utilized for anchorage shall be done in the presence of the special inspector and a report of the test results shall be submitted. See Specification Section 05501 for additional requirements.
PASE – December 2024
270-30-23-22
01611 - 5
Seismic Design Requirements
City of Milpitas
WellUpgrades Program
McCandless Well Facility
B. Inspection: Special inspection shall be provided for high strength bolting or bolts installed in concrete. See Specification Section 05501 for additional requirements.
END OF SECTION
PASE – December 2024
270-30-23-22
01611 - 6
Seismic Design Requirements
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
West Yost – December 2024
270-30-23-22
01770 - 1
Contract Closeout Procedures
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 01770
CONTRACT CLOSEOUT PROCEDURES
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Administrative and procedural requirements for contract closeout.
1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section
1. General Conditions
2. Section 01780 – Record Documents
3. Section 01782 – Operation and Maintenance Information
1.03 FINAL CLEANING
A. Immediately prior to request for final inspection, clean the project site and make ready for City’s use and occupancy.
B. Employ experienced workers or professional cleanersfor final cleaning.
C. Complete the following cleaning operations:
1. Clean the project site, yard and grounds which were disturbed by construction activities. Remove rubbish, waste material, litter and other foreign material.
2. Sweep paved areas, remove oil stains, grease, dust and dirt.
3. Remove tools, construction equipment, machinery, storage sheds, temporary fences and surplus material.
4. Broom clean sidewalks and concrete floors.
5. Vacuum carpets, spot clean or if necessary, shampoo to remove visible soil or stains.
6. Clean glass in doors and windows, remove glazing compounds, replace chipped and broken glass, clean door and window frames.
7. Patch, touch up and repair marred surfaces and finishes. Replace finishes and surfaces that cannot be satisfactorily repaired or restored.
8. Wipe surfaces of mechanical and electrical equipment, remove excess lubrication, paint splatter and mortar droppings.
9. Clean plumbing fixtures and mirrors.
10. Clean light fixtures, lamps and bulbs. Replace burned-out bulbs and defective or noisy starters in fluorescent and mercury vapor fixtures.
1.04 FINAL INSPECTION
A. Complete final cleaning operations before requesting final inspection.
West Yost – December 2024
270-30-23-22
01770 - 2
Contract Closeout Procedures
City of Milpitas
WellUpgrades Program
McCandless Well Facility
B. Prior to requesting final inspection, complete and submit the following:
1. List of items to be completed or corrected (punch list). Organize list by facility, space, system and piece of equipment.
2. Specific warranties, bonds, maintenance service agreements, final certifications and similar documents.
3. Delivery of spare parts, special tools, extra materials and similar items to designated locations.
4. Make final changeover of permanent locks and deliver keys to City.
C. During Final Inspection:
1. City, Engineer and Contractorshall jointly walk throughand inspectthe project site to determine whether the Work is satisfactory and Substantially Complete.
2. The Contractor’s punch list will be reviewed and additional itemsidentified during the inspection requiring corrective actions will be added to the list as determined by the inspection.
1.05 FINAL COMPLETION
A. Final Completion Submittals:
1. Prior to submitting final Application for Payment, complete and submit the following:
a. Project Record Drawings. Refer to Section 01780.
b. Guaranty and Warranties.
c. Operation and Maintenance Information. Refer to Section 01782. d. Punch List with all corrective actions completed and ready for Final Inspection.
e. Releases from Agreements with property Citys or public agencies. f. Releases or Waivers of Liens and Claims.
g. Evidence of final, continuing insurance coverage complying with insurance requirements.
h. Consent of Surety to Final Payment.
B. Final Acceptance:
1. Engineer will either proceed with the inspection or advise Contractor of unfulfilled requirements.
2. City will execute and file a Notice of Completion with the County of Santa Clara, constituting final acceptance and completion of the Project.
1.06 FINAL APPLICATION FOR PAYMENT
A. Following a satisfactory Final Inspection and Notice of Completion, Contractor shall submit the final Application for Payment in accordance with the procedures and requirements specified in the General Conditions, Article 43 (C) – Final Payment.
PART 2 - PRODUCTS (NOT USED)
West Yost – December 2024
270-30-23-22
01770 - 3
Contract Closeout Procedures
City of Milpitas
WellUpgrades Program
McCandless Well Facility
PART 3 - EXECUTION (NOT USED)
END OF SECTION
West Yost – December 2024
270-30-23-22
01770 - 4
Contract Closeout Procedures
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
West Yost – December 2024
270-30-23-22
01780 - 1
Record Documents
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 01780
RECORD DOCUMENTS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Requirements for maintaining a set of Record Documents, including maintaining Record Drawings that are regularly updated to depict actual conditions in the field and changes in the work.
1.02 REFERENCED SECTIONS
A. The following Section is referenced in this Section:
1. Section 01330 – Submittals
1.03 SUBMITTALS
A. Comply with Section 01330.
B. Submit Record Drawings for review upon request for Substantial Completion.
C. Submit Project Record Documentsin accordance with Paragraph 1.07.
1.04 GENERAL REQUIREMENTS
A. The Contractor shall maintain Project Record Documents to provide up-to-date, factual information regarding all aspects of the Work, both concealed and visible.
B. Record Drawings shall be updated weekly. Progress payments may be delayed until Record Drawings are updated to meet requirements to date and provided progress Record Drawings upon pay request.
1.05 MAINTENANCE OF RECORD DOCUMENTS
A. Maintain at the Project site, available to the City and Engineer, one (1) copy of following record documentsto be turned over to the City upon request for Substantial Completion:
1. Record copy of Contract Documents.
2. Change Orders and other modificationsto the Contract.
3. Requests for Information.
4. Clarification Letters.
5. Field Instructions and other written instructions from City's Representative.
6. Reviewed shop drawings, product data, and samples.
7. Test reports.
8. Training material.
9. Claims.
B. Store record documents and samples in Contractor's field office apart from documents used for construction. Label documents with “RECORD DOCUMENTS” in neat, large, printed letters.
West Yost – December 2024
270-30-23-22
01780 - 2
Record Documents
City of Milpitas
WellUpgrades Program
McCandless Well Facility
C. File documents and samples in a manner acceptable to the City’s Representative.
D. Make documents and samples available at all times for inspection by the City’s Representative.
1.06 MAINTENANCE OF RECORD DRAWINGS
A. Record Drawings are documents maintained and annotated by the Contractor during construction to illustrate the final Work, as constructed.
B. Record Drawings shall be full size and maintained in a clean and legible condition.
C. Do not use the Record Drawing set for construction purposes.
D. Marking of the Record Drawings shall be kept current and shall be done at the time the material and equipment are installed.
1. Record actual depths, horizontal and vertical locations of underground pipes, duct banks, or other buried utilities. Reference dimensions to permanent surface features.
E. Mark on the Record Drawings any field changes and detailed information contained in submittals and change orders. Update the document within 24 hours after receiving information that a change has occurred, or clarification has been issued.
F. When the configuration and arrangement of the Work is changed from that indicated on the Contract Drawings or specified in the Project Manual, the authorizing document for the change, such as a Request for Information, Change Order, Shop Drawing, or Field Order, shall be clearly referenced on the Record Drawings as a comment.
G. Make annotationsin erasable colored pencils conforming to the following color code:
1. Additions: Red
2. Deletions: Green
3. Comments: Blue
4. Dimensions: Graphite
H. "Cloud" all affected areas.
I. Supplement the Record Drawings with detailed layout sketches, schedules, installation drawings and fabrication drawings.
1.07 FINAL PROJECT RECORD DOCUMENTS
A. Submit a copy of the Record Drawings to the City upon request for Final Completion.
B. Participate in review meetings with the City and Engineer, asrequired.
C. Promptly incorporate any changes to the Record Drawings.
D. Submit the final Project Record Documents to the City.
1. Accompany submittal with transmittal letter as specified in Section 01330.
2. Include a signed certification that each document, as submitted, is complete and accurate.
West Yost – December 2024
270-30-23-22
01780 - 3
Record Documents
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3. Stamp each sheet of the Final Record Drawings with the following information:
a. Project Record Document.
b. Prepared by: Contractor's name, permanent address.
c. Date prepared.
d. Contractor'ssignature.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION
West Yost – December 2024
270-30-23-22
01780 - 4
Record Documents
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
West Yost – December 2024
270-30-23-22
01782 - 1
Operations and Maintenance Information
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 01782
OPERATIONS AND MAINTENANCE INFORMATION
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Operation and maintenance (O&M) information to be provided for each maintainable piece of equipment, equipment assembly or subassembly, and materials included in the Work.
1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section
1. Section 01330 – Submittals
2. Section 01820 – Training
3. Section 01999 – Reference Forms
1.03 SUBMITTALS
A. Submit in accordance with Section 01330.
B. Submit preliminary O&M manuals in electronic format.
1. Refer to “Format Requirements – Electronic Copies” below.
2. Include all material in final O&M manual except startup and field testing information.
3. Engineer and City will review manuals. Make additions and revisions in accordance with review comments.
C. Submit final O&M manuals in hard-copy and in electronic format on CD or DVD.
1. Include startup and field testing information.
2. Submit two (2) final hard copy O&M Manuals and one (1) electronic copy on CD or DVD for review. Hard copies will be returned to Contractor.
3. Provide five (5) approved O&M manuals and two (2) copies on CD or DVD to City.
D. O&M Manuals must be submitted and accepted before on-site training, specified in Section 01820, may start.
E. Submittals that are not fully indexed and tabbed with sequentially numbered pages may be returned without review.
F. Complete and submit O&M Information Transmittal (See Section 01999) with each Manual.
G. Deferred submittal parts, which need not be included with final manuals, but shall be included with approved manuals:
1. Master Volume Index as specified in Paragraph 2.01
2. Include test reports as specified in Paragraph 2.05 in final O&M manuals.
West Yost – December 2024
270-30-23-22
01782 - 2
Operations and Maintenance Information
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3. Include forms required during startup and training in final O&M manuals.
4. Include completed Equipment Record Forms with equipment serial numbers, as specified in Paragraph 2.02, in final O&M manuals.
PART 2 - PRODUCTS
2.01 GENERAL
A. Each O&M Manual shall provide instructions and procedures for all aspects of equipment installation, operation, and maintenance including: delivery, handling, storage, maintenance during storage, assembly, erection, installation, startup, adjusting, testing, operating, shutdown, troubleshooting, maintenance, and as may otherwise be required.
B. Organize information in a consistent format under separate headings for each different procedure, with a logical sequence of instructions for each procedure.
C. Where manufacturers’standard pre-printed manuals are included in O&M Manuals, mark to reflect only the model or series of equipment used on the Project. Neatly cross out non-applicable material.
D. Master Volume Index
1. Provide a neatly typewritten master index of all O&M manuals.
2. List each manual as Volume of .
3. Include a copy of the index at the front of eachmanual. Clearly call outthe manual in the index.
2.02 FORMAT REQUIREMENTS – GENERAL
A. Cover: Provide a cover page and include the following information:
1. OPERATION AND MAINTENANCE MANUAL, VOLUME NO. _ OF _
2. Project Name
3. City Project Number
4. Specification Number(s)
5. Equipment Name(s)
6. Equipment Tag Numbers
B. Title Page: Provide a title page at the front of each Equipment O&M Manual containing the following information:
1. City Name and Project Name
2. Equipment Name
3. Specification Section
4. Equipment Tag Numbers
5. Equipment Model Numbers
6. Equipment Serial Numbers
West Yost – December 2024
270-30-23-22
01782 - 3
Operations and Maintenance Information
City of Milpitas
WellUpgrades Program
McCandless Well Facility
7. Names, addresses, telephone numbers and individuals to contact for the manufacturer, the nearest representative of the manufacturer, and the nearest supplier of the manufacturer’s equipment and parts
8. Engineer name, address, and telephone number
9. Contractor, name of responsible principal, address, and telephone number.
10. Date
C. Table of Contents
1. Number each page of O&M Manuals and provide a typed table of contents with page numbers at the front of each O&M Manual.
2. Divide the O&M Manuals into major sections and subsections, to allow easy location of material. At a minimum, list each major section in the table of contents.
3. Provide a fly sheet for each major section listed in the table of contents, with section title printed on fly sheet.
D. Section 1: Reserve Section 1 of the manual for the following:
1. Equipment Record Forms (Section 01999 and Division 16) a. Fill out by machine. Hand entries will not be allowed. b. Include all required information. The Equipment Record Form isintended as an easily accessible quick reference for plant operation and maintenance personnel.
c. Equipment record sheet for electrical/instrumentation equipment shall be as specified in Division 16. Include a complete list of items supplied, including serial numbers, ranges, options, and other pertinent data necessary for ordering replacement parts.
2. Startup formsrequired by individualspecification sections. These may include but are not limited to the following forms in Section 01999:
a. Equipment Test Report
b. Manufacturer’s Representative Service Report
c. Manufacturer’sInstallation Certification Form
d. Manufacturer’sInstruction Certification Form
E. Presentation of Data
1. Include only those sheets that are pertinent to the specific product.
2. Annotate each sheet to:
a. Clearly identify the specific project or part installed. b. Clearly identify the data applicable to the installation. c. Cross-out references to inapplicable information.
3. Identify each product by product name and other identifying numbers orsymbols as set forth in Contract Documents.
West Yost – December 2024
270-30-23-22
01782 - 4
Operations and Maintenance Information
City of Milpitas
WellUpgrades Program
McCandless Well Facility
4. Material shall be suitable for reproduction, with quality equal to original. No scanned or faxed copies of standard published manuals and product data available from manufacturers will be allowed.
F. Text
1. Manufacturer’s printed data properly edited for project. Cross out all data that does not apply to the equipment to be furnished. Clearly annotate to identify applicable product, part, or data.
2. Documents shall be machine typed; hand written documents are not acceptable.
Documents shall be legible and original size, documents that cannot be read or have been reduced will be returned for correction.
2.03 FORMAT REQUIREMENTS – HARD COPIES
A. Binders
1. Bind Equipment O&M Manuals in heavy duty hard cover three-ring “Slant D” binders with clear vinyl overlay pocket on binder front and spine, Avery Dennison, Heavy Duty, EZD, View Binder or equal.
2. Insert cover page specified above into clear pocket on the front of each binder.
3. Provide with heavy plastic-coated section dividers with numbered plastic index tabs.
4. Include plastic sheet lifters prior to first page and following last page.
B. Spine Label
1. Provide a spine label to be inserted into the clear pocket on the spine of each binder. Include the following information on the spine label:
a. Equipment Name(s)
b. Specification Number(s)
c. Equipment Tag Numbers.
d. Appendix number and/or volume number
C. Drawings
1. Drawings reduced to 11-inch by 17-inch are acceptable if they are clear and readable, and are neatly and individually double-folded to 8-1/2-inch by 11-inch size. Drawing title shall be visible in lower right hand corner of the original and folded drawing. Reinforce binding edge with clear Mylar strip.
2. Larger drawings or illustrations are acceptable if neatly folded and individually placed in an 8-1/2-inch by 11-inch clear plastic pocket which fits in the binder.
Only one drawing or illustration shall be placed in each pocket. Drawing title shall be visible in lower right hand corner of the original and folded drawing.
D. Additional formatting requirements:
1. Paper Size: 8-1/2 inches by 11 inches, except as noted below.
2. Paper: 20-pound minimum, white for typed pages.
West Yost – December 2024
270-30-23-22
01782 - 5
Operations and Maintenance Information
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3. Arrange printing so that punched holes do not obliterate data and use hole reinforcements for bound in plan sheets.
2.04 FORMAT REQUIREMENTS - ELECTRONIC COPIES
A. Include all information in the hard-copy Operation and Maintenance Manuals.
B. Insert fly sheets as specified above at the location of tabbed section dividers.
C. Provide as a single, searchable PDF file. Generate PDF files from original documents to enable text searches.
D. The files shall become the property of the City for use in training programs and other uses.
2.05 CONTENTS OF MANUALS
A. Product Data
1. Provide manufacturer’s catalog data indicating equipment and accessories provided for the Project. Include only those sheets that are pertinent to the products supplied and delete references to inapplicable information.
2. Supplement product data with drawings as necessary to clearly illustrate relations of component parts of equipment and systems.
3. Provide “As Constructed” submittal shop documents, data sheets, and drawings, including all items in the electrical/instrumentation system as specified in Division
16. Contract documents shall not be used as “As Constructed” drawings.
B. Drawings
1. Supplement product data with drawings as necessary to clearly illustrate:
a. Relations of component parts of equipment and systems. Include individual parts list with exploded views for all equipment. b. Control and flow diagrams.
2. Coordinate drawings with information in project contract documents to assure correct illustration of completed installation.
C. Equipment Description
1. Theory of Operation.
2. Description: Provide description of unit and component parts functions, normal operating characteristics, and limiting conditions.
a. Include descriptive bulletins, brochures, or catalog sheets to describe the equipment.
b. Include performance curves, engineering data, and test results.
D. Procedures
1. Safety Procedures: Manufacturer’s safety procedures for operating and maintaining all equipment and materials used. List personnel hazards and safety precautions for all operating conditions.
West Yost – December 2024
270-30-23-22
01782 - 6
Operations and Maintenance Information
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2. Shipping and Installation Procedures
a. Receiving and handling.
b. Short-term storage, long-term storage and maintenance during storage. c. Complete step-by-step installation instructionsfor all components. d. Startup, adjusting and testing.
E. Operating Instructions
1. Provide complete, detailed, written description of the sequence of operations for all operations in all modes. Prepare specifically for this work and reference to control diagrams and system components.
a. Recommended step-by-step pre-start, startup, adjustment, calibration, and break-in operating instructions.
b. Recommended step-by-step regulation and control instructions for routine operation. Include summer and winter operating instructions as applicable. Include any special operating instructions. c. Recommended step-by-step stopping, shut-down, and post-shutdown instructions.
2. Staff Service Requirements: Provide instructions for services to be performed by the staff such as lubrication, adjustments, and inspection.
3. Current and desired control settings.
4. Emergency Procedures.
a. Provide emergency procedures for equipment malfunctions to permit a short period of continued operation or to shut down the equipment to prevent further damage to systems and equipment.
b. Include emergency shutdown instructions for fire, explosion, spills, or other foreseeable contingencies.
F. Preventive Maintenance Information
1. Preventive Maintenance Plan and Schedule
a. Provide manufacturer's schedule for routine preventive maintenance, inspections, tests, and adjustments required to ensure proper and economical operation and to minimize corrective maintenance and repair.
b. Providemanufacturer's projection of preventive maintenance man-hours on a daily, weekly, monthly, and annual basis.
2. Lubrication information
a. Lubrication schedule showing service interval frequency b. Table showing recommended lubricants for specific temperature ranges and applications
1) For each required lubricant, provide a list of acceptable equivalents from at least one different major manufacturer whose products are locally available.
West Yost – December 2024
270-30-23-22
01782 - 7
Operations and Maintenance Information
City of Milpitas
WellUpgrades Program
McCandless Well Facility
c. Include a schematic diagram of the equipment showing lubrication points, recommended types and grades of lubricants, and capacities
3. Additional requirements
a. Include procedures for disassembly, assembly, alignment, adjusting, and checking.
b. Provide manufacturer’s printed maintenance instructions. c. Include illustrations, assembly drawings, and diagrams required for maintenance.
G. Corrective Maintenance Information
1. Corrective maintenance to include disassembly, repair, overhaul and reassembly.
2. Provide manufacturer’s step-by-step trouble shooting and diagnostic procedures to promptly isolate the cause of typical malfunctions. Describe clearly why the checkout is performed and what conditions are to be sought. Identify tests or inspections and test equipment required to determine whether parts and equipment may be reused or require replacement
3. Provide manufacturer’s step-by-step procedures and list required tools and supplies for removal, replacement, disassembly, and assembly of components, assemblies, subassemblies, accessories, and attachments. Provide tolerances, dimensions, settings, and adjustments required. Instructions shall include a combination of text and illustrations
4. Wiring diagrams and control diagrams shall be point-to-point drawings of wiring and control circuits including factory-field interfaces. Provide a complete and accurate depiction of the actual job-specific wiring and control work. On diagrams, number electrical and electronic wiring and pneumatic control tubing and the terminals for each type identically to actual installation numbering.
5. Provide manufacturer’s instructions and list tools required to restore product or equipment to proper condition or operating standards
6. Provide manufacturer's projection of corrective maintenance man-hours including craft requirements by type of craft.
H. Electrical and Instrumentation Information
1. Electrical & Instrumentation Drawings shall include as-built information per Division 16 for the project. As-built drawings shall be signed and stamped by an electrical engineer registered in the State of California.
2. Complete software ladder logic printouts.
3. Record of all settings or parameters for all programmable devices.
4. At the end of the project these manuals shall be updated to show “as-built” or “as-installed” conditions, including any field changes.
West Yost – December 2024
270-30-23-22
01782 - 8
Operations and Maintenance Information
City of Milpitas
WellUpgrades Program
McCandless Well Facility
I. Parts Identification
1. Provide full identification and listing of all parts of each component, assembly, subassembly, and accessory.
a. Identify parts by make, model, serial number, and source of supply to allow reordering without further identification.
b. Provide clear and legible illustrations, drawings, and exploded views to enable easy identification of the items. When illustrations omit the part numbers and description, both the illustrations and separate listing shall show the index, reference, or key number which will cross reference the illustrated part to the listed part.
2. Include schematic diagrams of all electronic devices. Provide a complete partslist with stock numbers for the components that make up the assembly.
3. Include special hardware requirements,such asrequirementto use high-strength bolts and nuts.
4. Include control and flow diagrams and panel wiring diagrams.
5. Coordinate drawingsto ensure correct illustration of completed installation.
J. Spare Parts
1. Provide lists of spare parts and supplies required for maintenance and repair to ensure continued service or operation without unreasonable delays. a. Manufacturer’s recommended spare parts list with manufacturer’s current prices.
b. Include complete nomenclature and commercial numbers of replaceable parts.
c. List spare parts and supplies that have a long lead-time to obtain. d. Provide a table showing the predicted life of parts subject to wear.
2. Include the spare parts list on Equipment Record Forms A and B (Section 01999).
K. Test Data
a. Provide copies of factory test reports as specified in the applicable equipment sections.
b. After field testing is completed, include field test data. c. Include performance curves and engineering data.
L. Additional Information
1. Provide any information not specified in the preceding paragraphs but pertinent to the maintenance or operation of the product or equipment. Examplesinclude:
a. Information on test equipment required to perform specified tests and on special tools needed for the operation, maintenance, and repair of components.
b. Instances that might affect the validity of Warranties or Bonds
West Yost – December 2024
270-30-23-22
01782 - 9
Operations and Maintenance Information
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2.06 APPENDICES
A. Submittals
1. Include a copy of all approved submittals.
B. Warranty Information
1. List and explain the various warranties and include the servicing and technical precautions prescribed by the manufacturers or contract documents to keep warranties in force.
C. Personnel Training
1. Provide information available from the manufacturers to use in training designated personnel to operate and maintain the equipment and systems properly.
2. Refer to Section 01820 for additional training information.
2.07 COMPUTERIZED MAINTENANCE MANAGEMENT SYSTEM
A. Collate and submit information on the new and modified equipment, specialties, electrical, and instrumentation installed during the Project, for potential import into a Computerized Maintenance Management System (CMMS).
B. Data Format
1. Submit equipment and instrument information in a database file format suitable for direct import to an SQL-based relational database management system, without additional data manipulation.
2. The acceptable format is Microsoft Excel file format.
3. Format data in row (equipment name or tag) and column (equipment, name, tag, description, and various features as noted herein) so that it can be added to the SCADA database.
C. Data Content
1. Maintenance information to be provided shall include all equipment information relevant to a reliability-centered maintenance program.
2. File and file name of electronic (PDF version) of equipment manual.
3. The spreadsheet information shall include, but is not limited to, the following:
a. General information required for all equipment:
1) Equipment or instrument name, model number, serial number 2) Equipment or instrument tag numbers
3) Description
4) Equipment cost
5) Manufacturer and local representative name and contact information
6) Dates of purchase, installation and commissioning
West Yost – December 2024
270-30-23-22
01782 - 10
Operations and Maintenance Information
City of Milpitas
WellUpgrades Program
McCandless Well Facility
7) List of spare parts, including part number, quantity, name and cost
8) Required inspections and frequency
9) Required preventive maintenance procedures and frequency b. Mechanical equipment information:
1) Lubrication information, including lubrication points, frequency of lubrication, and recommended lubricants
2) Replaceable wear components and recommended replacement intervals
c. Electric motor information:
1) Frame number
2) Horsepower
3) Amperages
4) Voltage, frequency, number of phases
5) RPM
6) Service factor
7) Duty
8) NEMA design code
9) Insulation class
10) Ambient temperature rating
11) Temperature rise
D. Submittal Requirements
1. Submit a complete draft electronic copy of the equipment and instrument information database for City review at least three (3) months prior to the project acceptance.
2. The City will provide comments on the draft database within then (10) Working Days of receipt. City comments on subsequent drafts of the equipment and instrument information database will be provided within five (5) Working Days of receipt, provided that major revisions requiring additional review time have not occurred.
3. The equipment and instrument information database shall not be considered complete until approved by the City. Approval will not be unreasonably withheld.
4. Following review and approval, the Contractor shall submit one (1) electronic copy of the equipment and instrument information database to the City.
PART 3 - EXECUTION (NOT USED)
END OF SECTION
West Yost – December 2024
270-30-23-22
01810 - 1
Starting and Adjusting
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 01810
STARTINGAND ADJUSTING
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Requirementsfor start-up, adjusting, and process/functional testing.
1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section
1. Section 01330 – Submittals
2. Section 01820 – Training
3. Section 01825 – Equipment and System Testing
4. Section 01999 – Reference Forms
5. Section 16010 – Electrical
1.03 DEFINITIONS
A. Manufacturer’s Representative – Authorized service division employee ofthe manufacturer.
1.04 SUBMITTALS
A. Comply with Section 01330.
B. Start-up Plan, Forms, and Schedule: Prepare a facility start-up plan and schedule. The plan shall include test methods and procedures, list of data that will be recorded and records that will be kept, and sample forms for recording test data. Submit facility start-up plans for approval no less than 21 days before initial start-up of equipment or systems begin.
C. Forms and Certifications: Submit the following forms and certifications:
1. Supplement 01810-A, “Process Control Test Certification”
2. Supplement 01810-B, “Functional Test Certification”
3. Instrumentation Data and Calibration Test Form and testing instrument certification. (Section 01999)
4. Manufacturer’s Installation Certification Form after the manufacturer’s Field Representative has completed the specified field services and testing. Submit the certification prior to Manufacturer's Representative leaving the plant site. (Section 01999)
1.05 START-UP PLAN
A. Develop a specific plan and schedule for testing and start-up activities required for the project and submit to the City for approval no less than 21 days before the initial start-up of equipment begins.
B. The plan shall, as a minimum, incorporate the activities itemized below.
1. Complete all work associated with the installations of the unit and related processes before start-up activities begin.
West Yost – December 2024
270-30-23-22
01810 - 2
Starting and Adjusting
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2. Manufacturer’srepresentative shall certify the installation meets manufacturer’s recommendations and instructions.
3. Manufacturer’s representative shall certify equipment operates as specified and as shown in the Contract Documents.
4. Calibrate instruments. Submit an Instrumentation Data and Calibration Test Form. See Section 01999 for a sample form showing the format and level of detail required for the documentation form. Submit certification that test instruments used in the testing procedure have been calibrated to an acceptable and recognized standard.
5. Contractor’s independent process control test certification verification.
6. Contractor’s demonstration of the process control test certification to the Engineer. Operation and maintenance manuals shall be available during this activity.
7. Contractor’sindependent functional test certification verification.
8. Contractor’s demonstration of the functional test certification to the Engineer.
9. Submit records kept during start-up and adjusting activities.
10. Submit Manufacturer's Installation Certification Forms (Section 01999) after the manufacturer's Field Representative has completed the specified field services and testing and prior to Manufacturer's Representative leaving the plant site.
11. Show Trainings, Commission Test, and Operational Test on the schedule included in the Start-up Plan. See Section 01820 and Section 01825.
12. Contractorshall provide sufficient time in the progressschedule to accommodate the start-up sequences.
C. Include forms for recording test data.
1.06 MANUFACTURER’S REPRESENTATIVE RESPONSIBILITIES
A. Manufacturer’s representative shall inspect the installation and certify with a written report that the installation meets the requirements of the Contract Documents as well as the Manufacturer’s recommendations. This shall be done before the equipment is energized.
B. At completion of a manufacturer’s representatives’ start-up and testing activities, they each shall furnish a written report certifying the equipment installation meets the following conditions.
1. Has been properly installed to meet the IBC seismic requirements and has been adjusted, aligned and lubricated as required.
2. Is free of any stresses imposed by connecting piping or anchor bolts.
3. Issuitable for satisfactory full time operation under full load conditions.
4. Operates within the allowable limits for vibration.
5. Controls, protective devices, instrumentation and control panels furnished as part of the equipment package are properly installed, calibrated and functioning.
West Yost – December 2024
270-30-23-22
01810 - 3
Starting and Adjusting
City of Milpitas
WellUpgrades Program
McCandless Well Facility
6. Control logic for start-up, shutdown, sequencing, interlocks and emergency shutdowns have been tested and are functioning properly.
PART 2 - PRODUCTS – NOT USED
PART 3 - EXECUTION
3.01 GENERAL REQUIREMENTS
A. Demonstrate proper function of all equipment,systems and control devices. Each item of mechanical, electrical, and instrumentation equipment installed under this Contract shall be tested by the Contractor to demonstrate compliance with the performance requirements of this project.
B. Furnish labor, process medium, chemicals, tools, equipment, instruments, and services required for, and incidental to, completing start-up and adjusting activities. Furnish and install temporary valves, gauges, piping, and other materials required to conduct the specified tests.
C. Manufacturer’s representative shall provide assistance for assembly and installation as well astesting guidance and troubleshooting during the start-up and adjusting activities.
D. Complete Supplement 01810-A, “Process Control Test Certification” and submit the completed form to the Engineer for approval. The submission and approval of this form isrequired prior to commencing with the Contractor’s demonstration to the Engineer that each process itemized in the Process Control Test Certification operates as specified and designed.
3.02 MECHANICAL, ELECTRICAL, AND INSTRUMENTATION ADJUSTMENTS A. Complete the following mechanical adjustments prior to, or during, the Contractor’s initialstart-up and adjusting activities and before demonstration to the Engineer.
1. Remove rust preventatives and oils applied to protect equipment during construction.
2. Flush lubrication systems and dispose of flushing oils. Recharge lubrication system with lubricant recommended by manufacturer.
3. Install and adjust packing, mechanical seals, O-rings, and other seals. Replace defective seals.
4. Remove temporary supports, bracing and other foreign objects installed to prevent damage during shipment, storage and erection.
5. Check rotating machinery for correct direction of rotation and for freedom of moving parts before connecting driver.
6. Perform cold alignment and hot alignment to manufacturer’stolerances.
7. Adjust belt tension and variable pitch sheaves.
8. Inspect hand and motorized valvesfor proper adjustment. Tighten packing glands to ensure no leakage, but permit valve stems to rotate without galling. Verify valve seats are positioned for proper flow direction.
West Yost – December 2024
270-30-23-22
01810 - 4
Starting and Adjusting
City of Milpitas
WellUpgrades Program
McCandless Well Facility
9. Tighten leaking flanges or replace flange gasket. Inspect screwed joints for leakage.
10. Install gratings, safety chains, handrails, shaft guards and sidewalks prior to operational testing.
B. Complete the following electrical and control adjustments prior to, or during, the Contractor’s initial start-up and adjusting activities and before demonstration to the Engineer.
1. Perform insulation resistance tests on all conductors operating at or above 200 volts.
2. Perform continuity tests on all conductors.
3. Test and set circuit breaker relays and circuit breaker trip settings for proper operation. Coordinate the trip settings for all circuit breakers.
4. Check and record motors for actual full load amperage draw on each phase and compare to nameplate value. Submit results to Engineer.
C. Complete the following instrumentation adjustments prior to, or during, the Contractor’s initialstart-up and adjusting activities and before demonstration to the Engineer.
1. Field calibrate instruments and make required adjustments and control point settings.
2. Leak test pneumatic controls and instrument air piping.
3. Energize transmitting and controlsignalsystems, verify proper operations,ranges and settings.
3.03 CONTRACTOR’S INDEPENDENT PROCESS CONTROL TEST CERTIFICATION VERIFICATION A. Verify the equipment provided is installed correctly and functions properly.
B. Complete Supplement 01810-A, “Process Control Test Certification” pursuant to the following.
1. The supplement is not intended as a replacement for a systematic check of all the requirements specified.
2. Complete the tests outlined in the Supplement, fill out the form and sign it certifying that the tests have been successfully performed and the results recorded.
3. Where it is not possible to test a function without the software furnished, the Contractor shall verify the inputs/outputs (I/O’s) are terminated correctly by simulating the process as closely and to the extent possible and checking the I/O terminations for voltage and continuity.
C. Submission of the completed Supplement to the Engineer and approval of the submission are a prerequisite to the Contractor’s demonstration of process control test certification to the Engineer.
West Yost – December 2024
270-30-23-22
01810 - 5
Starting and Adjusting
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3.04 CONTRACTOR’S DEMONSTRATION OF PROCESS CONTROL TEST CERTIFICATION TO THE ENGINEER A. The intent of the demonstration of the operation to the Engineer is to ascertain the installation, including the hardwired control, are in compliance with the Contract Documents. Successful completion of this step will facilitate efficient demonstration of the complete operations of the facilities when the configured control software is installed and tested as part of the Functional Test Certification.
B. Demonstrate compliance with the items listed in Supplement 01810-A.
C. Engineer may require the Contractor to demonstrate functions or processes in addition to those itemized in Supplement 01810-A.
D. Engineer’s approval of the demonstration of the process control test certification is required before the Functional Test Certification phase commences.
3.05 CONTRACTOR’S INDEPENDENT FUNCTIONAL TEST CERTIFICATION VERIFICATION A. Complete Supplement 01810-B, “Functional Test Certification” pursuant to the following.
1. Complete the tests outlined in the Supplement, fill out the form and sign it certifying that the tests have been successfully performed and the results recorded.
2. This test will be conducted with the configured software installed and functional.
Alarms, data logging, trending and control functions shall be verified B. Submission of the completed Supplement to the Engineer and approval of the submission are a prerequisite to the Contractor’s demonstration of functional test certification to the Engineer.
3.06 CONTRACTOR’S DEMONSTRATION OF THE FUNCTIONAL TEST CERTIFICATION TO THE ENGINEER A. The intent of the demonstration of the Functional Test Certification to the Engineer is to ascertain the installation, including the configured software program, is in compliance with the Contract Documents.
B. Demonstrate items listed in Supplement 01810-B, “Functional Test Certification” to the Engineer.
C. Engineer may require the Contractor to demonstrate functions or processes in addition to those itemized in Supplement 01810-B.
D. Engineer’s approval of the demonstration of the Functional Test Certification is a prerequisite to beginning the commissioning phase.
3.07 RECORD KEEPING
A. Contractor shall maintain, as a minimum, the following records generated during the start-up and adjusting activities.
1. Daily logs of equipment and processtesting, identifying all tests conducted and a summary of the results.
2. Logs oftime spent with manufacturer’srepresentatives providing servicesfor the project.
3. Equipment lubrication records.
West Yost – December 2024
270-30-23-22
01810 - 6
Starting and Adjusting
City of Milpitas
WellUpgrades Program
McCandless Well Facility
4. Electrical phase voltage and amperage measurementsfor all equipment.
5. Insulation resistance measurements.
B. All completed test forms specified in Section 16010.
3.08 SUPPLEMENTS
A. Supplement 01810-A, “City of Milpitas McCandless Well Facility Process Control Test Certification”.
B. Supplement 01810-B, “City of Milpitas McCandless Well Facility Functional Test Certification”.
END OF SECTION
West Yost – December 2024
270-30-23-22
01810 - 7
Starting and Adjusting
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SUPPLEMENT 01810-A
CITY OF MILPITAS MCCANDLESS WELL FACILITY
PROCESS CONTROL TEST CERTIFICATION
# Description Pass Fail Comments
1 2
3 4
5 6
7 8
9 END OF SUPPLEMENT A
West Yost – December 2024
270-30-23-22
01810 - 8
Starting and Adjusting
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SUPPLEMENT 01810-B
CITY OF MILPITAS MCCANDLESS WELL FACILITY
FUNCTIONAL TEST CERTIFICATION
# Description Pass Fail Comments
1 2
3 4
5 6
7 8
9 END OF SUPPLEMENT B
West Yost – December 2024
270-30-23-22
01820 - 1
Training
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 01820
TRAINING
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Requirements for training City’s personnel, by persons retained by the Contractor specifically for the purpose, in the proper operation and maintenance of the equipment and systems installed under this Contract.
1.02 REFERENCED SECTIONS
A. The following Section is referenced in this Section
1. Section 01330 – Submittals
2. Section 01810 – Starting and Adjusting
1.03 SUBMITTALS
A. Comply with Section 01330.
B. Submit an overall training schedule with date, time, and subject of each training session.
C. Submit a training plan that includes the following items. The Contractor may prepare separate submittals for individual equipment items and systems.
1. Qualifications of individual(s) to be conducting the training.
2. Date, time, and subject of each training session.
3. Lesson plan for each training session.
4. Training materialsfor each training session, including training manuals, handouts, visual aids, and other reference materials.
1.04 GENERAL REQUIREMENTS
A. Where required by the detailed specifications, provide on-the-job training of City’s personnel, which will include plant operations personnel, mechanics, electricians, and electronics technicians.
B. The Contractorshall coordinate with the equipmentsuppliersfor all training activities and provide additional labor, services, and materials as required to complete training.
C. The training sessions shall be conducted by qualified, experienced (2 years minimum), manufacturer’s factory-trained representatives (not sales representatives) of the various equipment manufacturers.
D. Field training sessions shall take place at the project site. Classroom training facility shall be provided at the site by the Contractor.
1.05 FORMAT AND CONTENT
A. The content of the training session shall be specific to the products installed.
B. Include instruction in both equipment operation and preventive maintenance.
West Yost – December 2024
270-30-23-22
01820 - 2
Training
City of Milpitas
WellUpgrades Program
McCandless Well Facility
C. Classes shall be structured such that classroom sessions are interspersed with field instruction in logical sequence. Each training session shall be comprised of time spent both in the classroom and at the specific location of the subject equipment or system.
D. The following services shall be provided for each item of equipment or system. Additional servicesshall be provided, where specifically required in individualspecification sections.
1. At a minimum, classroom equipment training shall include:
a. Using slides and drawings, discuss the equipment’s specific location in the plant and an operational overview.
b. Purpose and plant function of the equipment.
c. A working knowledge of the operating theory of the equipment. d. Start-up, shutdown, normal operation, and emergency operating procedures, including a discussion on system integration and electrical interlocks, if any.
e. Identify and discusssafety items and procedures.
f. Routine preventative maintenance, including specific details on lubrication and maintenance of corrosion protection components. g. Routine and long-term calibration procedures.
h. Operator detection, without test instruments, of specific equipment trouble symptoms.
i. Required equipment exercise procedures and intervals. j. Routine disassembly and assembly of equipment if applicable (as judged by the City on a case-by-case basis) for purposes such as operator inspection of equipment.
k. Normal and major repair procedures.
l. Recommended maintenance documentation for warranty purposes.
2. At a minimum, hands-on equipment training shall include:
a. Identify location of equipment and review the purpose. b. Identifying piping and flow options.
c. Identifying valves and their purpose.
d. Identifying instrumentation:
1) Location of primary element.
2) Location of instrument readout.
3) Discuss purpose, basic operation, andinformation interpretation. e. Discuss, demonstrate, and perform standard operating procedures and round checks.
f. Discuss and perform the preventative maintenance activities. g. Discuss and perform start-up and shutdown procedures. h. Perform the required equipment exercise procedures.
i. Perform routine disassembly and assembly of equipment if applicable. j. Identify and review safety items and perform safety procedures, if feasible.
West Yost – December 2024
270-30-23-22
01820 - 3
Training
City of Milpitas
WellUpgrades Program
McCandless Well Facility
1.06 TIMING OF TRAINING SESSIONS
A. The Contractor shall coordinate the scheduling of training sessions with the operations superintendent.
B. No training sessions shall be scheduled for Mondays, Fridays, Saturdays, Sundays, or holidays.
C. Consolidate short training sessions into combined sessions so that staff time is more efficiently used. The minimum combined session length should be 1.5 to 2 hours. The maximum single or combined session length shall be 4 hours. The Contractorshall arrange to have the training conducted on consecutive days, with no more than 4 hours of classes scheduled for any one day.
D. Commencement of training sessions will be authorized only after successful completion of Starting and Adjusting activities. See Section 01810.
E. Conduct and complete training sessions before starting the Commissioning Test.
F. Operation and maintenance manuals shall be approved and ready for distribution to the City’s personnel at least thirty (30) days prior to the date scheduled for the individual training session.
G. Training materialsshall be reviewed and accepted by the Engineer at least three (3) weeks prior to the date scheduled for the individual training session.
PART 2 - PRODUCTS
2.01 LESSON PLANS
A. Prepare a formal written lesson plans for each training session. Lesson plansshall contain an outline of the subjects to be presented, time allocation for each subject, and a brief description of the material that will be covered for each subject.
B. Furnish ten copies of the lesson plan, training manuals, handouts, and reference materials and one copy of necessary visual aids at least 1 week prior to each training session. These materials shall remain the property of the City and shall be suitably bound for proper organization and easy reproduction.
2.02 VIDEO RECORDING
A. The City may record, or retain the services of a commercial video taping service to record, each training session. After taping, the material may be edited and supplemented with professionally produced graphics to provide a permanent record.
PART 3 - EXECUTION (NOT USED)
END OF SECTION
West Yost – December 2024
270-30-23-22
01820 - 4
Training
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
West Yost – December 2024
270-30-23-22
01825 - 1
Equipment and System Testing
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 01825
EQUIPMENT AND SYSTEM TESTING
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Requirements for the Contractor’s testing of mechanical, electrical, and instrumentation and control systems provided under this Contract.
B. The requirements contained in this Section supplement, but do not supersede, specific testing requirements found elsewhere in the Contract Documents.
1.02 DEFINITIONS
A. Commissioning Test: A confirmation that equipment, systems, and facilities satisfy the detailed requirements of the technical specifications. The duration of the Commissioning period shall be not less than seven (7) consecutive days.
B. Operational Test: Operation of the system under typical plant operating conditions to confirm that the system operates in accordance with the design intent. The duration of the Operational Testing period shall be not less than thirty (30) consecutive days.
C. Significant Interruption: Significant interruption may include any of the following events:
1. Failure of Contractor to maintain qualified on-site start-up personnel as specified.
2. Failure of critical equipment unit, system, or sub-system furnished under this Contract that is not satisfactorily corrected within two (2) hours after the failure.
3. Failure of non-critical equipment unit,system, orsub-system furnished under this Contract that is not satisfactorily corrected within twenty-four (24) hours after the failure.
4. Unplanned halting of operations for any reason related to the facilities constructed or the equipment furnished under this Contract.
1.03 REFERENCED SECTIONS
A. The following Section is referenced in this Section
1. Section 01330 – Submittals
2. Section 01560 – Environmental Controls
1.04 SUBMITTALS
A. Prepare and submit in accordance with Section 01330.
B. Independent Testing Labs: When testing by an independent laboratory is specified, provide credentials and certifications to demonstrate capabilities.
C. Testing Plan and Schedule
1. Submit a testing schedule and updates as appropriate. Submit at least 20 working days prior to the scheduled start of testing. Confirm the test schedule, or provide an updated schedule at least four (4) days prior to the start of testing.
West Yost – December 2024
270-30-23-22
01825 - 2
Equipment and System Testing
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2. Describe step by step procedure that will be utilized to systematically test equipment and systems.
D. Submit the following test results:
1. Results of the Commissioning Test.
2. Results of the Operational Tests.
1.05 COORDINATION
A. Coordinate the activities of subcontractors and equipment suppliers to implement the requirements of this Section. Minimum levels of on-site testing assistance required of the equipment suppliers is described in separate Sections.
1.06 DOCUMENTATION REQUIREMENTS
A. Develop and implement a record keeping system to document compliance with the requirements of this Section.
B. Document date of test, nature of test (performance or operational), test objectives, test results, and test instruments used during the test. Provide signature spaces for the Engineer and the Contractor.
1.07 TEST PLANS
A. Identify participants in the tests, including subcontractors and manufacturer’s representative. List the names of the participants, contact information, roles and responsibilities, and dates the participant will be present during the test periods.
B. Identify testing conditions and durationsfor the conditions. Undertake performance tests under extreme design conditions, as well as normal operating conditions that will be encountered.
C. Identify materials needed and quantities of materials needed for tests, including materials to be supplied by the City.
D. Identify data that will be recorded during the tests, the method of data collection, test instruments used for data collection, and the frequency the data will be collected. Prepare report forms for data collection.
E. Identify plan for storing, reusing, and disposing of water produced during the testing period.
1.08 TESTING SCHEDULE
A. Prepare a testing schedule setting forth the sequence contemplated for performing the test work. Identify the contemplated start date, duration of the test, and completion of each test.
1.09 TEST RESULTS
A. Test results shall be within the tolerances set forth in the detailed specification sections of the Contract Documents. If no tolerances have been specified, test results shall conform to tolerances established by recognized industry practice.
B. Retesting: If any portion of the work should fail to fulfill the Contract requirements and is adjusted, altered, renewed, or replaced, tests on that portion, together with all other
West Yost – December 2024
270-30-23-22
01825 - 3
Equipment and System Testing
City of Milpitas
WellUpgrades Program
McCandless Well Facility
portions of the work as are affected thereby, shall be repeated within reasonable time and in accordance with the specified conditions.
PART 2 - (NOT USED)
PART 3 - EXECUTION
3.01 GENERAL
A. The objective of the testing program is to demonstrate, to the Engineer’s complete satisfaction, that the systems and equipment provided under this Contract meet the specified performance requirements.
B. Testing program also provides a base-line operating condition for the City to use in a preventative maintenance program.
C. The testing sequence shall consist of Commission Testing followed by Operational Testing.
D. Provide labor, outside services, materials, test equipment, and other items required to complete the specified testing. Furnish fuel, oil, grease, and other materials needed to conduct the specified tests.
E. Remove all temporary installations used for Starting and Adjusting activities before beginning the Commissioning and Operational Tests.
F. Correct defects in material and workmanship immediately following their discovery.
G. The Commissioning Test shall be completed prior to Substantial Completion.
H. Provide for maintenance of materials, equipment, and systems furnished under this Contract until Substantial Completion. This includes required maintenance activities during the Commissioning Test period.
I. As of the date of Substantial Completion, the City’s staff will be responsible for operation and maintenance of new facilities. This excludes any issues identified as warranty matters.
J. Dispose of water produced during the test in accordance with the requirementsin Section 01560.
3.02 COMMISSIONING TEST
A. The Commissioning Test shall commence only after completion of the following:
1. Successful completion of all individual system testing.
2. Successful completion of Starting and Adjusting activities.
3. Disinfection of systems.
4. Correction of punch list deficiencies.
5. Submittal of O&M Manuals.
6. Completion of required Training.
West Yost – December 2024
270-30-23-22
01825 - 4
Equipment and System Testing
City of Milpitas
WellUpgrades Program
McCandless Well Facility
B. The purpose of the Commissioning Test isto:
1. Conduct performance testing to verify that the system complies with the performance requirements contained in the individual equipmentspecifications.
2. Expose flaws or defects in workmanship, equipment, or materials, not previously discovered that are the responsibility of the Contractor to repair, correct, modify, or replace prior to Substantial Completion.
C. Conduct Commissioning Test for a period of seven (7) days without significant interruptions.
D. Should the Commissioning Test be halted due to a significant interruption event, the test shall be repeated until the specified continuous period has been accomplished without interruption.
E. The Contractorshall be responsible for coordinating all Commissioning Test activities. The Contractor shall operate the equipment and systems furnished under this Contract. City staff will operate existing equipment and systems as needed for the Commissioning Test.
3.03 OPERATIONAL TEST
A. The Operational Test may begin after successful completion and acceptance of the Commissioning Test.
B. The purpose of this Operational Test isto:
1. Provide the environment by which the City’s O&M staff can place equipment and systems into service.
2. Expose flaws or defects in workmanship, equipment, or materials, not previously discovered that are the responsibility of the Contractor to repair, correct, modify, or replace prior to Final Acceptance.
C. Conduct the Operational Test for a period of thirty (30) days without significant interruptions.
D. All equipment furnished under this Contract must operate properly for the test period. If any item malfunctions during the test, the item shall be repaired, and the test restarted at day zero with no credit given for the operating time before the malfunction.
E. The Contractor shall operate the equipment and systems furnished under this Contract for five (5) consecutive days beginning with the first day of the Operational Test Period.
For the remainder of the Operational Test Period, City’s staff will operate the facility, and the Contractor shall provide personnel on a 24-hour per day, “on-call” basis, to adjust, repair, and correct deficiencies as required to keep the facilities in operation.
END OF SECTION
West Yost – December 2024
270-30-23-22
01890 - 1
Restoration of Improvements
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 01890
RESTORATION OF IMPROVEMENTS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Restoration of work areas after installation and construction of new facilities.
1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section
1. Section 02740 – Asphalt Paving
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.01 STRUCTURES
A. Take precautions to protect the integrity and usefulness of existing facilities.
B. If necessary, remove existing structures including curbs, gutters, pipelines, and utility poles, as necessary for the performance of the work.
1. Repair existing structures that are damaged as a result of the Work under this contract
2. Rebuild or replace the structures in as good a condition as originally found.
3.02 ROADS AND STREETS
A. Asphalt pavement that has been removed, broken, or damaged, or in which the ground has caved orsettled during the work underthis contract,shall be brought to original grade and section and resurfaced.
B. Before resurfacing material is placed, sawcut edges of pavement to provide clean solid vertical faces.
C. Complete pavement repair in accordance with Section 02740 and in accordance with the requirements of the affected agencies and parties.
3.03 CULTIVATED AREAS AND OTHER SURFACE IMPROVEMENTS
A. Restore cultivated or planted areas and other surface improvements damaged by construction as nearly as possible to their original condition.
B. Repair existing guard posts, barricades, and fencesthat are damaged.
C. Replace damaged plantings with new plantings of the same type or as acceptable to the City.
END OF SECTION
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
West Yost – December 2024 01890 - 2 City of Milpitas
270-30-23-22 Restoration of Improvements Well Upgrades Program
West Yost – December 2024
270-30-23-22
01999 - 1
Reference Forms
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 01999
REFERENCE FORMS
The forms listed below and included in this section are referenced from other sections of the project manual. Contractor may submit equivalent forms for City’s approval prior to use. If the City does not approve substitute form, Contractor must use forms found in this Section. City will provide Contractor electronic files of prescribed forms upon request.
Referenced Section Title of Form
01782 Equipment Record Form - A
01782 Equipment Record Form - B
01782 Equipment Test Report
09960, 11060 Extended Warranty Form
01810 Instrumentation Data and Calibration Record Test Form 01782, 01810, 11000, 11342,11364,
11475, 13216, 15736, 15805 Manufacturer’s Installation Certification Form 01782 Manufacturer’s Instruction Certification Form
01782 Manufacturer’s Representative Service Report
11060, 11342 Motor Data Form
01782 Operating and Maintenance Information Transmittal 15951, 15996 Pipe Test Record Form
11342 Training Certification Form
09960, 11342 Unit Responsibility Certificate
West Yost – December 2024
270-30-23-22
01999 - 2
Reference Forms
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
Equipment Record Form A
EQUIPMENT RECORD FORM A (Electrical or Motorized Mechanical Equipment):
Equip. Description: Equip. Loc.:
Equip. No. Shop Dwg. No. Date Inst.: Cost:
Mfgr.: Mfgr Contact
Mfgr. Address: Phone:
Vendor : Vendor Contact:
Vendor Address: Phone:
MAINTENANCE REQUIREMENTS D W M Q S A Hours
Lubricants: Recommended
Alternative:
Misc. Notes:
Recommended Spare Parts Electrical Nameplate Data
Part
No.
Qty Part Name Cost Equip
Make
Serial No. Id. No.
Model No. Frame No.
HP V Amp Hz
pH RPM SF Duty
Code Ins. Cl. DES Type
NEMA DES C Amb. Temp Rise Rating
Misc.
Equipment Record Form A
Recommended Spare Parts Mechanical Nameplate Data
Part
No.
Qty Part Name Cost Equip
Make
Serial No. Id. No.
Model No. Frame No.
HP V Amp Hz
pH RPM SF Duty
Code Ins. Cl. DES Type
NEMA DES C Amb. Temp Rise Rating
Misc.
Equipment Record Form B
EQUIPMENT RECORD FORM B (Electrical or Non-Motorized Mechanical Equipment):
Equip. Description: Equip. Loc.:
Equip. No. Shop Dwg. No. Date Inst.: Cost:
Mfgr.: Mfgr Contact
Mfgr. Address: Phone:
Vendor : Vendor Contact:
Vendor Address: Phone:
MAINTENANCE REQUIREMENTS D W M Q S A Hours
(THIS PAGE LEFT BLANK INTENTIONALLY)
Equipment Test Report
EQUIPMENT TEST REPORT
NOTE:
This example equipment test report is provided for the benefit of the Supplier and is not specific to any piece of equipment to be installed as a part of this project. The example is furnished as a means of illustrating the level of detail required for the preparation of equipment test report forms for this project.
Project:
City
Contractor:
Supplier:
Equipment Name:
Equipment Number:
Specification Ref:
PRE-OPERATIONAL CHECKLIST
Supplier Engineer
Verified Date Verified Date
Mechanical
Lubrication
Alignment
Anchor bolts
Pump/mechanical equipment vibration testing
Seal water system operational
Equipment rotates freely
Safety guards
Valves operational
O&M manual information complete
Supplier’s installation certificate complete
Electrical (Circuit ring-out and high-pot tests)
Circuits:
Power to MCC
Control to HOA
Equipment Test Report
Supplier Engineer
Verified Date Verified Date
Indicators at MCC:
Red (running)
Green (power)
Amber (auto)
Indicators at local control panel
Wiring labels complete
Nameplates:
MCC
Control station
Control panel
Electrical equipment grounding verification
Equipment bumped for rotation
Piping Systems
Cleaned and flushed
Suction
Discharge
Pressure tests
Temporary piping screens in place
Thrust restraint and pipe supports in place
Instrumentation and Controls
Flow meter calibration
Calibration Report No.
Flow recorder calibrated against transmitter
VFD speed indicator calibrated against independent
reference
Discharge overpressure shutdown switch calibration
Simulate discharge overpressure shutdown
I/C equipment grounding verification
Equipment Test Report
FUNCTIONAL TESTS
Supplier Engineer
Verified Date Verified Date
Mechanical
Motor operation temperature satisfactory
Pump operating temperature satisfactory
Unusual noise, etc?
Pump operation: gpm/ psig
Pump Measurement:
Flow/Pressure
Test gage number
Alignment hot
Doweled in
Pump/mechanical equipment vibration testing
Remarks:
Electrical
Local switch function:
Runs in HAND
No control power in OFF
Timer control in AUTO
Overpressure protection switch PS2502C
functional in both HAND and AUTO
Overpressure protection switch PS2502C
set at 75 psig
PLC 2500 set at 24 hr cycle, 25 min ON
Motor amperage draw test
Equipment Test Report
OPERATIONAL TEST
Supplier Engineer
Verified Date Verified Date
48-hour continuous test:
pump cycles as specified
indicators functional
controls functional
pump maintains capacity
overpressure protection remains functional
hour meter functional
RECOMMENDED FOR BENEFICIAL OCCUPANCY
Engineer Date
ACCEPTED FOR BENEFICIAL OCCUPANCY
City’s Representative Date
Extended Warranty Form
EXTENDED WARRANTY FORM
(For Equipment, Material, Process)
Extended Warranty For: Product Name
Specification Section No.
Product Manufacturer
Project:
Location:
We hereby guarantee the Product Name that we have constructed for a period of # of Years (#) year(s), as specified in the Section noted above, from Date, the date of acceptance of the work/substantial completion and the assumption of occupancy and beneficial use by the Name of City.
The following are excluded from the provisions of this warranty:
We agree that if any of the equipment, material, or process designated for Product Name should fail due to any reason other than improper maintenance or improper operation, or should any portion of the work fail to fulfill any of the requirements of the Specifications, we will, within ten days after written notice of such defects, commence to repair or replace the same together with any other work which may be damaged or displaced in so doing.
In the event of our failure to comply with the above mentioned conditions within a reasonable time after being notified, or should exigent circumstances require repairs or replacements to be made before we can be notified or respond to notification, we do hereby authorize the Name of City to proceed to have the defect repaired and made good at our expense, and we will pay the cost therefor upon demand.
The warranty provided herein shall not be in lieu of, but shall be in addition to any warranties or other obligations otherwise imposed by the Contract Documents and by law.
Manufacturer: Contractor:
Signed: Signed:
Title: Title:
Date: Date:
Phone: Phone:
E-mail: E-mail:
Instrumentation Data and Calibration Test Form
INSTRUMENTATION DATA AND CALIBRATION RECORD TEST FORM
Component Description
Component Tag Name
Manufacturer Location
Name Site
Model
Serial # Equip
Range Unit General Notes
1) Attach Calibration Curves for dp Flowmeters
2) Include mounting elevations for level Instruments
3) All entries within solid box to be typed in prior to start of test
Indicator Range
Input Range
Output Range
Designed Calibration Measured Calibration
Input
Signal Output
Eng.
Value Input Output Comments
Notes:
Tested by Witnessed by
(print name) (print name)
Signature Signature
Date Date
Manufacturer’s Installation Certification
MANUFACTURER'S INSTALLATION CERTIFICATION FORM
Contract No: Specification Section:
Equipment Name
Contractor:
Manufacturer of Equipment Item:
The undersigned manufacturer of the equipment item described above hereby certifies that he has checked the installation of the equipment and that the equipment, as specified in the project manual, has been provided in accordance with the manufacturer's recommendations and that the trial operation of the equipment item has been satisfactory.
Date Manufacturer
Signature of
Authorized Representative
Date Contractor
Signature of
Authorized Representative
Comments:
Manufacturer’s Instruction Certification
MANUFACTURER’S INSTRUCTION CERTIFICATION FORM
Contract No: Specification Section:
Equipment Name:
Contractor:
Manufacturer of Equipment Item:
The undersigned manufacturer certifies that a service engineer has instructed the City’s staff in the proper maintenance and operation of the equipment designated herein.
Operations Check List (check appropriate spaces)
Start-up procedure reviewed ☐
Shutdown procedure reviewed ☐
Normal operation procedure reviewed ☐
Others:
☐
☐
Maintenance Check List (check appropriate spaces)
Described normal oil changes (frequency) ☐
Described special tools required ☐
Described normal items to be reviewed for wear ☐
Described preventive maintenance instructions ☐
Described greasing frequency ☐
Others
☐
☐
Manufacturer:
Date Signature of Authorized Representative
Date Signature of City's Representative
Date Signature of Contractor's Representative
Manufacturer’s Representative Service Report
MANUFACTURER’S REPRESENTATIVE SERVICE REPORT
City: File No.
Project: Date:
Project No.
This form should be completed and returned by the manufacturer’s representative prior to leaving the site.
Manufacturer: MRSR No.
Supplier: Contract/P.O. No.
Manufacturer’s Representative
Company
Equipment/Material:
Work performed and tests made on equipment:
Factory errors corrected:
Field errors corrected:
The above equipment is
Remarks:
is not ready to be placed in operation.
Arrival onsite AM PM Department from Site AM PM
Date Time Date Time
Actual total duration onsite was hours for period covered by this report.
Manufacturer’s Representative
Signature Date
Address:
Phone No.
Report Received By:
Signature Date
Distribution:
Motor Data Form
MOTOR DATA FORM
Equipment Name: Equipment Number:
Site Location:
Nameplate Markings
Mfr Mfr Model Frame HP
Volts Phase RPM Service Factor
FLA LRA Freq Amb temp rating degrees C
Time rating Design letter
(NEMA MG1-10.35) (NEMA MG-1.16)
KVA code letter Insulation class
The following information is required for explosionproof motors only:
A. Approved by UL for installation in Class , Div
B. UL frame temperature code , Group Atmosphere
(NEC Tables 500-2 and 500-2(b))
The following information is required for high efficiency motors only:
A. Guaranteed minimum efficiency at full load or NEMA efficiency index (NEMA MG1-12.53b)
B. Nameplate or nominal efficiency
Data Not Necessarily Marked on Nameplate
Type of enclosure Enclosure material
Temp rise degrees C (NEMA MG1-12.41,42)
Space heater included? Yes No, if Yes watts volts
Type of motor winding overtemperature protection, if specified:
Use the space below to provide additional information on other motor modifications, if specified:
O&M Information Transmittal
OPERATING AND MAINTENANCE INFORMATION TRANSMITTAL
Submittal Description: Submittal No. # Copies:
1st Submission Re-Submittal
Spec Section
City:
Routing Date
Sent
Date
Received
Contractor/CM
Project: CM/Design Consultant
Design Consultant/CM
Contractor: CM/Contractor
Supplier Name: Supplier Review Design Consultant Review Checklist Satisfactory N/A Accept Deficient
1. Table of Contents
2. Equipment Record Forms
3. Supplier/Vendor Contact Information
4. Safety Precautions
5. Operator Pre-Start
6. Start-up, Shutdown/Post-Shutdown Procedures
7. Normal Operations
8. Emergency Operations
9. Operator Service Requirements
10. Environmental Conditions
11. Lubrication Data
12. Preventative Maintenance Plan/Schedule
13. Troubleshooting Guide/Diagnostic Techniques
14. Wiring Diagrams and Control Diagrams
15. Maintenance and Repair Procedures
16. Removal and Replacement Procedures
17. Spare Parts and Supply List
18. Corrective Maintenance Man-hours
19. Parts Identification
20. Warranty Information
21. Personnel Training Requirements
22. Testing Equipment and Special Tool Information
(Contractor’s Signature) (Supplier’s Signature)
Remarks:
Pipe Test Record
PIPE TEST RECORD
Date:
Project Name: Project No.:
Contractor:
Pipeline Size & Name Pipe Type Pipe Location/Description (SL), SN, IA, etc.) (DI, PVC, Steel, Copper, etc.) (Attach sketch if needed) Section Tested:
From:
To:
First Test ☐
Or
Re-Test ☐
Length of Pipe Tested:
Ft.
Test Specifications Actual Test Results
Type of Test: Start pressure:
Type of Test: End Pressure:
Start time Stop time Duration
Duration:
Allowable loss: Actual loss:
Comments:
Test Passes ☐
Test Fails ☐
Tested By:
Contractor
Test Witnessed By:
Construction Inspector
Training Certification Form
TRAINING CERTIFICATION FORM
Contract No: Specification Section:
Equipment Name:
Contractor:
Manufacturer of Equipment Item:
The undersigned manufacturer certifies that a qualified factory-trained representative with a minimum of two years experience has instructed the City’s staff in the proper maintenance and operation of the equipment designated herein. The undersigned manufacturer (or equipment supplier) also agrees to conduct an eight (8) hour follow-up training session(s) after the equipment has been installed and continually operated by the City for at least three (3) months but prior to expiration of the one year warranty period.
Operations Check List (check appropriate spaces)
Start-up procedure reviewed ☐
Shutdown procedure reviewed ☐
Normal operation procedure reviewed ☐
Others:
☐
☐
Maintenance Check List (check appropriate spaces)
Described normal oil changes (frequency) ☐
Described special tools required ☐
Described normal items to be reviewed for wear ☐
Described preventive maintenance instructions ☐
Described greasing frequency ☐
Others
☐
☐
Manufacturer
Date Signature of Authorized Representative
Date Signature of City's Representative
Date Signature of Contractor's Representative
Unit Responsibility Certificate
Name of City
CERTIFICATE OF UNIT RESPONSIBILITY
For Specification Section
Section Number and Title
In accordance with the contract documents, the undersigned manufacturer accepts unit responsibility for all components of equipment furnished under specification Section Section #. We hereby certify that these components are compatible and comprise a functional unit suitable for the specified performance and design requirements.
Name of Corporation
Street Address
City, State and Zip Code
By:
Notary Public Duly Authorized Official
Commission Expiration Date Name
Title
Seal: Date:
West Yost – December 2024
270-30-23-22
02071 - 1
Geotextile Fabric
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 02071
GEOTEXTILE FABRIC
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Geotextile fabric.
1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section
1. Section 01330 – Submittals
2. Section 02300 – Earthwork
1.03 SUBMITTALS
A. Comply with Section 01330.
B. Manufacturer’s Data:
1. Manufacturer’s name and product information
2. Certificate of Compliance
3. Minimum Average Roll Values (MARV)
1.04 DEFINITIONS
A. Geosynthetic – A planar product manufactured from polymeric material used with soil, aggregate, or other geotechnical engineering materials as an integral part of a civil engineering project.
B. Geotextile – a permeable geosynthetic comprised solely of textile materials (nonwoven or woven comprised of various synthetic polymers and manufactured by numerous processes).
1.05 FUNCTION
A. Subgrade Enhancement Geotextile:
1. Located beneath aggregate base of both paved and unpaved roadways. Used as solids separation barrier for below grade structures.
1.06 QUALITY ASSURANCE
A. Treat geotextiles to resist degradation from exposure to sunlight.
1.07 DELIVERY, STORAGE AND HANDLING
A. Deliver, unload, and store geotextile fabric in manufacturer's wrapping with a minimum amount of handling.
B. Protect geotextile rollsfrom excessive dust, moisture, rainfall, mud, ultraviolet exposure, and debris.
C. Follow manufacturer’srecommendationsregarding storage.
West Yost – December 2024
270-30-23-22
02071 - 2
Geotextile Fabric
City of Milpitas
WellUpgrades Program
McCandless Well Facility
PART 2 - PRODUCTS
2.01 MANUFACTURERS
A. One of the following or equal:
1. TenCate Mirafi
2. US Fabrics
2.02 MATERIALS
A. General
1. Fabric values are based on the State of California Department of Transportation Specifications (Section 96) except for Geomembrane Support Fabric.
B. Subgrade Enhancement Fabric
1. Polyester or polypropylene.
2. When tested under the referenced ASTMs, the properties must have the values shown in the following table.
Subgrade Enhancement Geotextile (Caltrans 96-1.02O)
Quality Characteristic Test Method
Requirement(a)
Class
A1
Class
A2
Class
B1
Class
B2
Class
B3
Elongation at break, (percent) ASTM D4632 <50 ≥50 <50 <50 ≥50 Grab Breaking Load, 1-inch grip in each
direction, (min, lb) ASTM D4632 250 160 -- 320 200
Wide width tensile strength at 5 percent
strain, (min, lb/ft) ASTM D4595 -- -- 2,000 -- --
Wide width tensile strength at ultimate
strength, (min, lb/ft) ASTM D4595 -- -- 4,800 -- --
Tearstrength, (min, lb) ASTM D4533 90 60 -- 120 80
Puncture strength, (min, lb) ASTM D6241 500 310 620 620 430 Permittivity, (min,sec-1) ASTM D4491 0.05 0.05 0.20 0.20 0.20 Apparent opening size, (min, inches) ASTM D4751 0.012 0.012 0.024 0.012 0.012 UV Resistance, retained grab breaking load,
500 hours, (min, percent) ASTM D4355 70 70 70 70 70
(a) Values are based on minimum average roll value in the weaker principal direction except apparent opening size is based on maximum average roll value.
PART 3 - EXECUTION
3.01 PREPARATION
A. Subgrade and earthwork asspecified in Section 02300.
3.02 INSTALLATION
A. Roll Length: Sized to fit area of use. Minimum length of 300 feet for areaslarger than 300 feet long.
West Yost – December 2024
270-30-23-22
02071 - 3
Geotextile Fabric
City of Milpitas
WellUpgrades Program
McCandless Well Facility
B. Handle geotextile fabric in a manner that will not damage fabric.
C. Place geotextile with no wrinkles or folds.
D. If the fabric is joined with overlap joints, the adjacent borders of the fabric must be overlapped be at least 24-inches. Overlap in the same directions that the cover material is placed.
E. Install as shown on the Drawings and per manufacturer’s installation instructions.
END OF SECTION
West Yost – December 2024
270-30-23-22
02071 - 4
Geotextile Fabric
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
West Yost – December 2024
270-30-23-22
02085 - 1
Precast Concrete Utility Structures
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 02085
PRECAST CONCRETE UTILITY STRUCTURES
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Precast concrete manholes and catch basins(storm inlets).
B. Manhole and catch basin vault frames and covers.
C. Manhole accessories.
1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section
1. Section 01330 – Submittals
2. Section 01611 – Seismic
3. Section 15951 – Testing Gravity Flow Pipelines
1.03 SUBMITTALS
A. Prepare and submit in accordance with Section 01330.
B. Product Data:
1. Manhole barrels, bases, cones, grade rings, tops, frames, and covers.
2. Rubber boot-type pipe connectors for connecting piping to manholes.
3. Catch basin sections, basins, tops, frames, and grates.
C. Utility Structure Details:
1. Manufacturer’s standard shop drawings for each size and type of precast utility structure.
a. Provide dimensions of structure.
b. Identify location of each type of insert cast into the structure.
2. Illustrate construction details related to joints between precast sections, method of connecting pipe to the structure, size and location of pipe penetrations, reinforcement details and concrete mix design.
D. Structural Design:
1. Laboratory results verifying compressive strength of concrete mix design used in the manufacture of precast concrete utility structures.
2. Calculations and related sketches prepared, stamped and signed by a civil or structural Professional Engineer licensed to practice in the state of California.
1.04 DESIGN REQUIREMENTS
A. Manholes:
1. Concrete Mix Design: See City Standard Detail and Specifications.
West Yost – December 2024
270-30-23-22
02085 - 2
Precast Concrete Utility Structures
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2. Risers, Conical Tapered Sections, Grade Rings and Flat Top Sections: See City Standard Detail and Specifications.
B. Catch Basins:
1. Concrete Mix Design:
a. Minimum Compressive Strength: 4,000 psi at 28 days.
b. Cement: Type II low alkali Portland cement meeting requirements of ASTM C150.
c. Fly Ash: Class C or Class F meeting requirements of ASTM C618, not to exceed 25 percent by weight.
d. Aggregates: Conform to requirements of ASTM C33.
2. Conform to ASTM C858.
3. Base design andmanufacture to A-16 (HS 20-44) loading in accordance with ASTM C857.
1.05 COORDINATION
A. Coordinate layout and installation of utility structures with the final arrangement of other utilities, site grading, and surface features as determined in the field.
PART 2 - PRODUCTS
2.01 PRECAST CONCRETE MANHOLES
A. Precast reinforced concrete manholes shall be constructed in accordance with design, size, shape, form and details indicated on the City Standard Detail and Specifications.
B. Accessories:
1. Rubber Boot Pipe Connectors:
a. Manufacturers: One of the following or equal:
1) “Kor-N-Seal” flexible rubber boot with stainlesssteel accessories as manufactured by NPC, Inc.
2) “Z-LOK XP” or “A-LOK” flexible connector as manufactured by ALOK Products, Inc.
2. Joint Sealing Compound: See City Standard Specifications.
3. Manhole Frame and Cover Sets: See City Standard Detail and Specifications.
2.02 PRECAST CONCRETE CATCH BASINS
A. Provide precast concrete catch basins, drop inlets, curb inlets or other storm drain inlets as indicated on the Drawings.
B. Manufacturers: One of the following or equal:
1. Oldcastle Precast
2. Christy Concrete Products.
3. Utility Concrete Products.
West Yost – December 2024
270-30-23-22
02085 - 3
Precast Concrete Utility Structures
City of Milpitas
WellUpgrades Program
McCandless Well Facility
C. Description:
1. Factory-fabricated, reinforced concrete box with frame and grate.
2. Open or integral closed bottom as indicated on the Drawings or as scheduled.
3. Monolithically poured walls and bottom, unless open-bottom vaults are indicated on the Drawings or scheduled.
D. Materials
1. Concrete: 5,000 psi at 28 days
2. Reinforcing steel: ASTM A615 grade 60
3. Mesh: Welded wire fabric ASTM A185 grade 65
E. Frame and Grate
1. As indicated on the City Standard Detail.
PART 3 - EXECUTION
3.01 MANUFACTURE
A. Utilize a central batching facility to ensure accurate weighing and mixing of materials to consistently obtain a suitable concrete mix.
B. Concrete Batching: Properly proportion sand, aggregate and cement with sufficient water to produce a concrete mix of uniform quality and slump.
C. Concrete Compaction: Use either external or internal mechanical vibration during placement of the concrete mix within the forms.
D. Curing: Steam cure concrete while still in the forms and after an initialset hastaken place.
1. Steam temperature: Not to exceed 160 degrees F, nor raised from normal ambient temperature at a rate exceeding 40 degrees F per hour.
2. Terminate steam curing after sufficient time has elapsed to produce adequate strength to withstand any structural strain that may occur during the form stripping operation.
3. Additional curing may be applied by means of waterspraying or membrane curing compound to reach the ultimate strength requirements.
E. Reinforcing Steel: Position within the forms as required for design loads. Tie reinforcing steel sufficiently to withstand displacement during the pouring operation.
3.02 INSTALLATION
A. Concrete Manholes:
1. Manhole Invert: Construct with smooth transitions to provide an unobstructed flow path through the manhole. Remove sharp edges and rough sections. a. When a fullsection of pipe islaid through the manhole, break out the top portion of the pipe. Cover the exposed edge of pipe with mortar and trowel smooth.
West Yost – December 2024
270-30-23-22
02085 - 4
Precast Concrete Utility Structures
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2. Manhole Sections:
a. Set each manhole section plumb.
b. Use sections of various heights and adjustment rings in order to bring top of manhole ring and cover to required elevation.
3. Joints in Manhole Sections:
a. Seal joints with jointsealing compound.
b. Clean joints with brush, prime and apply sealing compound in accordance with manufacture’s printed instructions.
c. Seal joints watertight.
B. Manhole Frame and Cover Sets:
1. Location and Grade:
a. In Paved Areas: Set cover flush with pavement ± 0.25 inch b. In Open Areas: Set cover above surrounding grade in accordance with the details indicated on the Drawings ± 1 inch
c. In existing roadside ditches or unpaved, untraveled right-of-way: Set cover approximately 12 inches above existing ground surface ±2 inches
2. Setting Frames:
a. Clean bearing surfaces and provide uniform contact.
b. Set manhole frames at required grade and securely attach to top of precast manhole shaft unit or on adjustment rings, using cement mortar.
3. Setting Covers: After frames are securely set in place, install covers and perform necessary cleaning and scraping of foreign materials from frames and covers as necessary to assure proper fit. Replace frames and covers that create noise when passed over by traffic.
C. Catch Basins:
1. Install catch basins level and plumb and with orientation and depth coordinated with connecting pipes.
2. Support catch basin on a level bed of aggregate base material, 6 inches deep and compacted to 95 percent of maximum density.
3. Seal joints with jointsealing compound. Clean joints and apply sealing compound in accordance with the manufacturer’s requirements.
4. Finish Elevations of Catch Basins: As indicated on Drawings.
5. Covers: Install covers and perform necessary cleaning and scraping of foreign materials from frames and covers as necessary to assure proper fit. Replace frames and covers that create noise when passed over by traffic.
3.03 PIPE CONNECTIONS
A. Install connecting pipe at the required alignment and grade.
B. Set connecting pipes through the full thickness of the manhole wall, flush with the inner face of the wall.
West Yost – December 2024
270-30-23-22
02085 - 5
Precast Concrete Utility Structures
City of Milpitas
WellUpgrades Program
McCandless Well Facility
C. Use standard flexible pipe connector boots, specifically manufactured for the intended service, to connect pipe to the manhole. When concrete pipe is used, grout pipe to the manhole so that the connection is watertight.
D. Plugging pipes provided for future connections:
1. Pipe 18-inches or less in diameter; Plug with concrete, extend minimum 8 inches into pipe.
2. Pipe greater than 18-inches in diameter: Construct plug using brick, concrete block or concrete, mortar exposed face of plugs constructed of brick and concrete block.
3.04 CLEANING
A. Upon completion, clean each structure of all silt, debris, and foreign matter.
3.05 TESTING
A. Test manholes for leakage in accordance with Section 15951.
END OF SECTION
West Yost – December 2024
270-30-23-22
02085 - 6
Precast Concrete Utility Structures
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
West Yost – December 2024
270-30-23-22
02300 - 1
Earthwork
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 02300
EARTHWORK
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Earthwork requirements for sitework, structures, roads and general earthwork, including excavation, fill, backfill, grading, and compaction; import of material; and disposal of surplus and unsuitable materials.
1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section
1. Section 01330 – Submittals
2. Section 01560 – Environmental Controls
1.03 DEFINITIONS
A. Backfill: Earthwork necessary to add fill between new structures and the excavation up to the sub or finish grade.
B. Bedding Zone: The area from the trench subgrade to the bottom of the pipe.
C. Borrow Area: Area identified from which to obtain earthwork materials.
D. Cut: Earthwork necessary to remove existing material to lower the existing grade in elevation to sub or finish grade.
E. Embankment: Materials placed to form the subgrade for roadways orsite improvements.
F. Embedment or Pipe Zone: The area from the top of the Bedding Zone to the bottom of the Trench Zone as indicated on the Drawings.
G. Excavation: Earthwork necessary to remove existing material for the installation of structures.
H. Fill: Earthwork necessary to add material to bring the existing grade up in elevation to sub or finish grade.
I. Finish Grade: Final surface following placement of surfacing, if any, as indicated.
J. Pavement Section: The upper portion of the trench within paved areas comprising the base and finished surface materials.
K. Spoils: Unsuitable or excess excavated materials.
L. Subgrade: The surface of the earthwork on which pavement,surfacing, base, subbase, or a layer of any other material is placed.
M. Trench Backfill: Materials used to backfill the trench including bedding zone, pipe zone, and trench zone backfill.
N. Trench Zone: The area from the top of the Pipe Zone to the bottom of the pavement base (subgrade), ground surface or other surface material over the trench excavation.
West Yost – December 2024
270-30-23-22
02300 - 2
Earthwork
City of Milpitas
WellUpgrades Program
McCandless Well Facility
1.04 SUBMITTALS
A. Prepare submittals and submit in accordance with Section 01330.
B. Material Data: Submit the following for each material type imported to the site. All material submittals must be dated to less than 1 year prior to Notice-to-Proceed.
1. Material source.
2. Gradation.
3. Moisture-density curves.
4. Permeability tests(for clay material).
C. For imported materials, provide certification and source.
D. For excavations 5 feet or deeper: Submit detailed plan of allshoring, bracing,side sloping, or other provisions for worker protection against the hazard of caving ground during excavations.
E. Submit name and qualifications of materials testing lab for Contractor furnished testing.
1.05 QUALITY ASSURANCE
A. Material Testing Standards:
1. Particle size analysis ofsoils and aggregates: ASTM D422 – Standard Test Method for Particle-Size Analysis of Soils.
2. Determination of sand equivalent value: ASTM D2419 – Standard Test Method for Sand Equivalent Value of Soils and Fine Aggregate.
3. Liquid limit, plastic limit, and plasticity index: ASTM D4318 – Standard Test Method for Liquid Limit, Plastic Limit, and Plasticity Index of Soils.
4. The testing for organic matter: ASTM D2974 – Standard Test methods for Moisture, Ash, and Organic Matter of Peat and Other Organic Soils.
5. Testing for percentage of fractured particles: ASTM D5821.
6. Referencesin thissection to soil classification types and standards: Meanings and definitions indicated in ASTM D2487 – Classification of Soils for Engineering Purposes.
B. Compaction Testing Standards
1. In-place Density of Compacted Fill Material: Density determined in the field in accordance with ASTM D6938 – Standard Test Methods for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth).
2. Maximum Dry Density of Compacted Material: Determined in the laboratory in accordance with:
a. Cohesive Soils: Method C of ASTM D1557-12e1 – Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3)).
b. Cohesionless, Free Draining Soils: ASTM D4253 – Standard Test Methods for Maximum Index Density of Soils Using a Vibratory Table and D4254 –
West Yost – December 2024
270-30-23-22
02300 - 3
Earthwork
City of Milpitas
WellUpgrades Program
McCandless Well Facility
Standard Test Methods for Maximum Index Density of Soils and Calculation of Relative Density.
C. References in this Section to soil classification types and standards shall have the meanings and definitions indicated in ASTM D2487 – Standard Practice for Classification of Soils for Engineering Purposes. Contractor shall be bound by all applicable provisions of ASTM D2487 in the interpretation of soil classifications.
1.06 SUBSURFACE INVESTIGATIONS
A. Geotechnical investigations for design purposes for this project were made by RHG Consultants in a report dated June 4, 2019.
B. This report is available for examination from the City upon request by bidders.
1.07 REFERENCE SPECIFICATIONS
A. Whenever the words "Standard Specifications" are referred to, the reference is to the State of California, Department of Transportation, latest edition.
1.08 CONTRACTOR SAFETY RESPONSIBILITIES
A. The Contractor shall be solely responsible for maintaining safe excavations:
1. Comply fully with 29 CFR Part 1926 OSHA Subpart P Excavations and Trenches requirements.
2. Provide necessary support to the sides of excavations.
3. Provide safe access to the Engineer’s sampling and testing within the excavation.
4. Provide safe access for backfill, compaction, and compaction testing.
5. Maintain excavations in a safe manner that shall not endanger property, life, health, or the project schedule.
B. All earthwork shall be performed in strict accordance with applicable law, including local ordinances, applicable OSHA, CalOSHA, California Civil Code, and California Department of Industrial Safety requirements.
PART 2 - PRODUCTS
2.01 MATERIALS
A. General Fill, Backfill, and Embankment Materials
1. Selected or processed clean earth, rock, or sand, free from grass, roots, brush, other vegetation, corrosive and hazardous materials, manmade objects, and debris.
2. Materials not defined as unsuitable as indicated below, except some materials listed as unsuitable may be used, if indicated on the Drawings or when acceptable to the Engineer, when thoroughly mixed with suitable materials to form a stable composite.
3. Obtain suitable materials from one or more of the following:
a. Onsite excavations and designated borrow areas.
b. Processed on-site materials.
West Yost – December 2024
270-30-23-22
02300 - 4
Earthwork
City of Milpitas
WellUpgrades Program
McCandless Well Facility
c. Imported from offsite borrow areas and processing plants.
4. If imported materials are required by this Section, or to meet the quantity requirements of the Project, provide the imported materials at no additional expense to the Cityr, unless a unit price item is included for imported materials in the Bidding Schedule.
5. Further condition fill, backfill, and embedment materials as described below or as indicated on the Drawings.
B. Engineered Fill Material
1. Free of organic material
2. Granular, low to non-expansive soil.
3. Plasticity index 12 or less.
4. Liquid limit 30 or less.
5. R-Value (ASTM D2844): 10 minimum.
6. Complying with the grading shown in the following table:
Sieve Size Percentage Passing
6-inch 100
4-inch 90-100
No. 200 10-60
7. Class 2 Aggregate Base Course Material may be used as Engineered Fill Material.
The aggregate base material shall comply with the requirement specified herein for Aggregate Base Course Material.
C. Aggregate Base Course Material
1. Clean, hard, durable particles consisting of the any combination of the following:
a. Broken stone
b. Crushed gravel
c. Natural rough surfaced gravel
d. Sand
e. Processed reclaimed asphalt concrete, portland cement concrete (PCC), lean concrete base (LCB), or cement treated base (CTB).
2. Use either 1-1/2-inch unless otherwise indicated. Do not change grading without authorization from the Engineer.
3. Conform to the following gradation when tested in accordance with ASTM C136:
Sieve Sizes
(Square Openings)
Percent by Weight
Passing Sieve
1-1/2” Maximum
2” 100
1-1/2” 90-100
West Yost – December 2024
270-30-23-22
02300 - 5
Earthwork
City of Milpitas
WellUpgrades Program
McCandless Well Facility
Sieve Sizes
(Square Openings)
Percent by Weight
Passing Sieve
1-1/2” Maximum
1-inch -
3/4-inch 50-85
No. 4 25-45
No. 30 10-25
No. 200 2-9
4. Durability Index (ASTM D3744): 35 minimum.
5. Sand Equivalent (ASTM D2419): 25 minimum.
6. R-Value (ASTM D2844): 78 minimum.
D. Crushed Rock
1. Manufactured, angular, crushed stone with a minimum sand equivalent value of
75. 2. Clean, hard, sound, durable, uniform in quality, and free of soft, friable, thin, elongated or laminated pieces, and disintegrated material.
3. Have 100 percent of its particles with at least one fractured face on a weight basis, when tested for crushed particles per ASTM D5821.
4. Complying with the grading shown in the following table:
Percentage Passing
Sieve Size 1-inch 3/4-inch 1/2-inch
1-1/2-inch 100 - -
1-inch 90-100 100 -
3/4-inch 30-60 90-100 100
1/2-inch 0-20 30-60 90-100
3/8-inch - 0-20 20-60
No. 4 0-5 0-5 0-15
No. 8 - 0-5
2.02 UNSUITABLE MATERIALS
A. Unsuitable materials include the materials listed below:
1. Soils which, when classified under ASTM D2487, fall in the classifications of Pt, OH, CH, MH, or OL, or in a classification that contains Pt, OH, CH, MH, or OL in combination with any other letter designation, such as CH/CL.
2. Soils which cannot be compacted sufficiently to achieve the density specified for the intended use, or are unstable or pump regardless of the degree of compaction.
West Yost – December 2024
270-30-23-22
02300 - 6
Earthwork
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3. Materials that contain hazardous or designated waste materials including petroleum hydrocarbons, pesticides, heavy metals, and any material which may be classified as hazardous or toxic according to applicable regulations.
4. Soils that contain greater concentrations of chloride or sulfate ions, or have a soil resistivity or pH less than the average values for existing onsite soils.
5. Topsoil, sludge and sludge-entrained soils.
6. Rocks, stones, and boulders larger than allowed for use as fill and backfill materials.
2.03 SOURCE QUALITY CONTROL
A. Materials source testing will be performed by a testing laboratory by the Contractor.
B. Minimum Frequency of Sampling:
1. Fill, backfill and embankment material generated from earthwork activities:
a. Two soil samples every 500 cubic yard of material used. b. Two soil samples whenever the character of the soil changes. c. One soil sample when directed by the Engineer.
d. Obtain samplesthat represent the predominate character ofthe soil that is encountered.
2. Sampling of Imported Material
a. Obtain representative samples of product from supplier. b. After demonstrating through initial testing that the proposed borrow material meets the specified requirements, obtain and test one additional sample for every 500 cubic yard of imported material.
C. Testing:
1. Test all materials used in the Work to confirm they meet the requirements indicated.
2. Prepare moisture-density curves for use in determining the optimum moisture content and in-place density of the compacted backfill.
PART 3 - EXECUTION
3.01 CONTROL OF WATER
A. All excavations shall be kept free from water and all construction shall be in the dry.
1. It should be presumed that the presence of groundwater will require dewatering operations. Furnish, install, maintain, and operate all necessary pumping and other equipment for dewatering all excavations. At all times have on the project sufficient pumping equipment for immediate use, including standby pumps for use in case other pumps become inoperable.
2. Provide a sufficient number of pumps so as to hold the groundwater level at an elevation of not less than 1 foot below the lowest elevation of the pipe, duct or other material to be placed.
West Yost – December 2024
270-30-23-22
02300 - 7
Earthwork
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3. Dispose of water in such a manner as to cause no injury or nuisance to public or private property, or be a menace to the public health.
4. The dewatering operation shall be continuous, so that the excavated areas shall be kept free from water during construction, while concrete is setting and achieves full strength, and until backfill has been placed to a sufficient height to anchor the work against possible flotation.
5. Continue dewatering during backfilling operations such that the groundwater is at least 1 foot below the level of the compaction effort at all times. No compaction of saturated materials will be allowed.
6. Dewatering devices must be adequately filtered to prevent the removal of fines from the soil.
7. The Contractor shall be responsible for any damage to the foundations or any other parts of existing structures or of the new work caused by failure of any part of the Contractor's protective works. After temporary protective works are no longer needed for dewatering purposes, they shall be removed by the Contractor.
8. If pumping is required on a 24-hour basis, requiring engine drives, then engines shall be equipped in a manner to keep noise to a minimum. Refer to Section 01560 for noise control requirements.
9. Prevent disposal of sediments from the soils to adjacent lands or waterways by employing whatever methods are necessary, including settling basins.
B. The Contractor shall be responsible for furnishing temporary drainage facilities to convey and dispose of surface water falling on or passing over the site.
3.02 EXISTING UTILITIES
A. Existing Underground Utilities:
1. Known existing underground utilities are generally shown on the Drawings in their approximate locations based on information of varying accuracy.
2. Review the design drawings, maps, and other sources of information and identify existing facilities at the site to determine and mark the approximate locations of underground facilities
3. Conduct field explorations to locate all underground utilities in the vicinity of the Earthwork activities. Perform field investigations prior to preparation of Shop Drawings for underground piping, and prior to excavation for installation of any underground facilities.
4. Exercise care to avoid damage to all existing utilities whether shown or not.
5. Alert the Engineer of the presence of existing utilities that are not shown on the Drawings or are in locations different than those shown on the Drawings.
B. Existing Overhead Utilities: There may be existing overhead utilities in the vicinity of the Work which may or may not be shown on the Drawings. Identify existing overhead utilities, if any, and use extreme caution when working in the vicinity of overhead utilities.
West Yost – December 2024
270-30-23-22
02300 - 8
Earthwork
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3.03 EXCAVATION – GENERAL
A. Excavation includes the removal of all materials of whatever nature encountered, including all obstructions of any nature.
B. Excavation shall conform to the lines and grades indicated on the Drawings.
C. Excavation Stability
1. Slope excavated faces or otherwise support in a safe manner in accordance with applicable State safety requirements and the requirements of OSHA Safety and Health Standards for Construction (29CFR1926).
2. Stability of temporary cut slopes, such as those constructed during the installation of underground utilities, are the responsibility of the Contractor. Cut slopes shall be excavated to 2H:1V or flatter.
3. Furnish, place, and maintain supports and shoring required to maintain stability of the sides of excavations.
D. Notify Engineer at least 1 working day in advance of completion of any structure excavation to allow inspection of the exposed subgrade before it is covered with backfill or with any construction materials.
E. Erosion Control:
1. Maintain earthwork surfaces true and smooth and protected from erosion.
2. Construct erosion control measures as required in the Technical Provisions, Article E-16.
3.04 EXCAVATION FOR FILLS AND EMBANKMENTS
A. Subgrade Preparation:
1. Subgrade Beneath Embankments:
a. Expose competent native soil within the planned new embankment footprint.
b. Scarify the exposed subgrade to a depth of 6 inches, moisture condition as necessary and re-compact.
2. Subgrade Beneath Paved Areas:
a. Excavate to the subgrade soils beneath the bottom ofthe aggregate base or to the subbase, if such subbase is indicated.
b. Scarify the top 6 inches of subgrade soils, moisture condition as necessary, and re-compact.
c. Finished subgrade shall be even, self-draining, and in conformance with the slope of the finished pavement.
3. Subgrade Beneath Structures:
a. Excavate to the subgrade soils beneath the bottom of the structure or bottom of crushed rock layer where indicated.
b. Scarify the top 12 inches of subgrade soils, moisture condition as necessary, and re-compact.
West Yost – December 2024
270-30-23-22
02300 - 9
Earthwork
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3.05 TRENCH EXCAVATION
A. Excavate trenches and maintain excavation such that pipe and pipeline accessories are installed in an open trench.
B. Excavate to subgrade elevation and to trench width dimensions indicated on the Drawings.
C. Excavate all materials of whatever nature encountered, including all obstructions of any nature that would interfere with the proper execution of the trenching Work unless otherwise indicated.
D. Where pipelines are to be installed in embankments, fills, or structure backfills, construct fill to a level at least one foot above the top of the pipe before the trench is excavated.
E. Trench shield:
1. If a moveable trench shield is used during excavation operations widen the trench width so that the shield is free to be lifted and then moved longitudinally without binding against the trench sidewalls.
2. If the trench walls cave in or slough, the trench shall be excavated as an open cut excavation with sloped sidewalls or with trench shoring, as indicated and as required by the pipe structural design.
F. Trench Bottom: Excavate and shape trench bottoms to provide uniform subgrade for placement of Bedding Material.
1. Unsuitable Hard Trench Bottom: If bottom of excavation is found to consist of rock or anymaterialthat cannot be excavated to provide uniform bearing surface:
a. Notify Engineer of the conditions encountered and obtain concurrence that an unsuitable trench bottom condition is present.
b. Remove such rock or other material to a depth of not less than 6 inches below the original design elevation of the bottom of the trench. c. Place bedding material or aggregate base course material to restore the trench bottom to the original design elevation. Place in lifts not exceeding 8 inches in un-compacted thickness and compact to 90 percent of maximum dry density.
2. Unsuitable Soft Trench Bottom: If bottom of excavation isfound to consist ofsoft or unstable material which is incapable of properly supporting pipe:
a. Notify Engineer of the condition encountered and obtain concurrence that an unsuitable trench bottom condition is present.
b. Remove such material to a depth and for the length required, as determined by the Engineer.
c. Place bedding material or aggregate base course material to restore the trench bottom to the original design elevation. Place in lifts not exceeding 8 inches in un-compacted thickness and compact to 90 percent of maximum dry density.
West Yost – December 2024
270-30-23-22
02300 - 10
Earthwork
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3.06 EXCAVATION FOR STRUCTURES
A. Unless otherwise indicated, provide excavationssufficient to leave at least 12 inches clear between structure outer surfaces and the face of the excavation or any shoring which may be used to support the face of the excavation.
B. Excavate to the subgrade soils beneath the bottom of the structure or bottom of crushed rock layer where indicated.
C. Scarify the top subgrade soils to a depth of 6 inches, moisture condition, and re-compact to 90 percent of maximum dry density.
3.07 OVER-EXCAVATION NOT ORDERED OR INDICATED
A. Backfill areas over-excavated with the materialsindicated for the backfill above the overexcavation or Aggregate Base.
B. Backfill the over-excavation to restore the required subgrade elevation and compact.
C. Any over-excavation carried below the grade indicated on the Drawings will be at no additional cost to the City.
3.08 OVER-EXCAVATION WHERE ORDERED BY ENGINEER
A. Where ordered by the Engineer, over-excavate beyond the depth of subgrade indicated to the dimensions ordered.
B. Backfill areas over-excavated with the materialsindicated for the backfill above the overexcavation or Aggregate Base.
C. Backfill the over-excavation to restore the required subgrade elevation.
D. Over-excavation less than 6 inches below the limits indicated: At no increase in cost to the City.
E. Over-excavation greater than 6 inches below the limits indicated: Payment will be made under separate unit price bid items for over-excavation if such bid items have been established. Otherwise, payment will be made in accordance with a negotiated price.
F. Measurement and Payment
1. Measurement of quantities for payment of over-excavation: By calculation by Engineer of the volume of materials removed as over-excavation based on the difference between the excavation dimensions before and after the overexcavation work. No compensation will be made for removal of materials beyond the limits of the additional excavation ordered by Engineer or for materials which may come into the excavation from outside the designated limits. No compensation will be made for removal of materials that are outside of the minimum horizontal dimensions indicated.
2. Payment for over-excavation will be made by the cubic yard. The payment shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in excavating and backfilling the over-excavation completely. Paymentshall also include full compensation for the removal and disposal of the excavated materials, import and installation of backfill materials, control of water in the excavation, excavation support, and all costs associated with interruption of construction operations during the review
West Yost – December 2024
270-30-23-22
02300 - 11
Earthwork
City of Milpitas
WellUpgrades Program
McCandless Well Facility
of the foundations, over-excavation, backfill, and all other operations required for, or as a result of, over-excavation.
3.09 DISPOSAL OF UNSUITABLE, EXCESS EXCAVATED AND OTHER MATERIALS A. Dispose unsuitable or excess excavated materials at an appropriate site selected by Contractor unless otherwise indicated.
B. Obtain required permits, landCity, and agency approvals for disposal of unsuitable and excess excavated materials and pay costs associated with the removal and disposal of the materials.
3.10 FILL AND EMBANKMENT CONSTRUCTION
A. Scarify foundation soils for fills and embankments bring to optimum moisture content, and re-compact with heavy compaction equipment to obtain compaction indicated.
B. Place and compact fill and embankments in horizontal layers so that when compacted layers to not exceed thickness indicated.
C. Provide keyways or benches where an embankment or fill is to be placed against slopes, hillsides, or fill slopes.
D. Slopes: Construct slopes as indicated except construct no permanent fill or embankment slopes with slope inclinations that exceed [2:1] (horizontal: vertical) unless specifically indicated otherwise
E. Over-construct fills and embankments to greater horizontal dimensions than indicated.
Cut back slope following placement and compaction to expose well compacted fill.
F. Construct the first 3 feet of embankment or fills over pipelines using placement and compaction equipment that do not damage the pipe. Keep heavy construction equipment aminimum distance ofthe edge ofthe trench equalto the depthofthe trench until at least 3 feet of fill over the pipe has been completed.
3.11 TRENCH BACKFILL
A. Place bedding and backfill materials true to the lines, grades, and cross-sections indicated on the Drawings and compacted to the degree specified on the Drawings. Place bedding and backfill materials in horizontal lifts not to exceed 6 inches in thickness measured before compaction. The difference in level on either side of a pipe shall not exceed 4 inches.
B. Backfill material shall not be placed over the pipe or conduit until after the joints have been completed and inspected by the Engineer.
C. It shall be incumbent upon the Contractor to protect the pipe or conduit from damage during the construction period. It shall be the Contractor’s responsibility to repair broken or damaged pipe at no extra cost to the City. Carefully place backfill around and over the pipe. Tamping of backfill over the pipe shall be done with tampers, vibratory rollers and other machines that will not injure or disturb the pipe.
D. Do not allow construction traffic nor highway traffic over the pipe trench until the trench backfill has been brought back even with existing adjacent grade.
West Yost – December 2024
270-30-23-22
02300 - 12
Earthwork
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3.12 STRUCTURE BACKFILL
A. Provide Structure Backfillmaterial within 12-inches of allstructuresto be backfilled unless otherwise indicated.
B. Place a 6-inch layer of 3/4-inch or 1-inch Crushed Rock below all structures, unless otherwise indicated.
C. Do not drop backfill upon any structure or pipe.
D. Confirm concrete structures have attained sufficient strength to withstand the backfill loads imposed.
E. Do not place backfill around water retaining structures until structures have been tested and approved for backfill. Fill structures with water during backfill operations.
F. Place backfill after all water has been removed from the excavation and the excavation sidewalls and subgrade soils have dried to a moisture content suitable for compaction.
G. Remove all loose, sloughing, or caving soils and rock materials prior to placement of backfill.
H. Place geotextile fabric as indicated.
I. Place backfill and spread evenly in layers so that when compacted layers do not exceed thickness indicated.
J. Thoroughly mix layers as necessary to promote uniformity of material in each layer.
K. Add water to backfill material where moisture content is below the optimum moisture content and mix with the soil until the proper moisture content is achieved throughout the soil layer.
L. Where backfill material moisture content is too high to permit the specified degree of compaction, dry backfill material until moisture content is satisfactory.
3.13 COMPACTION OF FILL, BACKFILL, AND EMBANKMENT MATERIALS A. Adjust moisture condition of soils to achieve a water content of 3 percent, plus or minus
0.5 percent, above the optimum moisture content as determined through laboratory testing of the soil.
B. Compact each layer in a uniform and systematic manner.
C. For materials with less than 10 percent passing the No. 4 sieve, compact by means of at least 2 passes from a flat plate vibratory compactor.
D. For materials with 10 percent or more passing the No. 4 sieve, mechanically compact to the indicated percentage of density each layer of backfill materials.
1. Use equipment that is consistently capable of achieving the required degree of compaction.
2. Compact each layer over its entire area while the material is at the required moisture content.
E. Do not use flooding, ponding, or jetting as a method of compaction.
West Yost – December 2024
270-30-23-22
02300 - 13
Earthwork
City of Milpitas
WellUpgrades Program
McCandless Well Facility
F. Do not use equipment weighing more than 10,000 lbs closer to structure walls than a horizontal distance equal to the depth of the fill at the time. Use hand operated power compaction equipment where use of heavier equipment is impractical or restricted due to weight limitations.
G. Compaction Requirements:
1. Where agency or utility company requirements govern, the highest compaction standards shall apply.
H. Compact finish and subgrades in compliance with the following table:
Location or Use of Fill Limit/Layer Thickness
Percentage of
Maximum Dry Density
of Compacted Material
per ASTM D1557
Embankment fill 12 in. Layers 90
Trench backfill 8 in. Layers 90
Upper 6 in. 95
Subgrade beneath embankments or fill areas Upper 6 in. 90 Subgrade beneath paved areas Upper 6 in. 95
Subgrade beneath slab-on-grade Upper 6 in. 95
Subgrade beneath buildings Upper 12 in. 95
3.14 FIELD QUALITY CONTROL AND TESTING
A. Field quality control testing for compaction confirmation will be done by a testing laboratory of the City’s choice at the City’s expense except as indicated below.
B. Ifrequested by the City,remove soil above the level at which the City wishesto test.
Backfill and re-compact material after testing is completed.
C. If compaction fails to meetspecified requirements, perform remedial work by one of the following methods:
1. Remove and replace backfill at proper density.
2. Bring density up to specified level by other means acceptable to City.
3. Retesting:
a. Costs for conducting additional tests to confirm and verify that remedial work has brought compaction within specified requirements shall be borne by the Contractor.
b. Conduct compaction tests at twice as frequently specified for the initial confirmation tests.
D. Where soil compaction is specified as a percentage of maximum dry density, determine the maximum dry density at optimum moisture content by laboratory testing in accordance with Method C of ASTM D1557.
West Yost – December 2024
270-30-23-22
02300 - 14
Earthwork
City of Milpitas
WellUpgrades Program
McCandless Well Facility
E. Where compaction of cohesionless, free draining soil is specified as a percentage of relative density, determine relative density by laboratory testing in accordance with ASTM D4253 and D4254.
F. Determine In-Place Density of Compacted Fill Material by performing field tests of soil density in accordance with ASTM D6938.
G. Frequency of Compaction Confirmation Testing at intervals not less than as follows:
1. Embankments and Fills: 2 tests.
2. Structure Backfill: 3 tests(under building foundation, under tank foundation, and under filter foundation).
3. Trench Backfill: 2 tests(in different trenches).
3.15 FINISH GRADES
A. Surface: Reasonably smooth and free of grade breaks, irregular surface changes, protrusions and other defects.
B. Restore un-improved areas back to pre-construction grades.
C. Backfill topsoil in all areas where the topsoil was removed as part of the site preparation.
D. Restore drainage swales and water courses to their pre-construction alignments and grades unless otherwise modified by the Work. Grade surface to drain away from structures. Direct drainage to collection points.
E. Provide smooth transitionsto existing grades.
F. Repair and reestablish grades to required elevations and slopes due to any settlement or erosion that may occur prior to final acceptance.
G. Vertical Tolerance:
1. Subgrade under paved areas: 0.0 feet above and 0.08 feet below.
2. Subgrade under structures: 0.0 feet above and 0.08 feet below.
3. Landscaped areas: 0.1 feet above and 0.1 feet below.
4. Unimproved areas: 0.1 feet above and 0.1 feet below.
END OF SECTION
West Yost – December 2024
270-30-23-22
02740 - 1
Asphalt Paving
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 02740
ASPHALT PAVING
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Requirementsfor constructing asphalt paving shown.
B. Work includes, but is not necessarily limited to, earthwork, scarifying and preparing the subgrade, placing and compacting aggregate base, applying prime coat and tack coat, placing and compacting asphalt concrete, and all related work.
1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section
1. Section 01330 – Submittals
2. Section 02300 – Earthwork
1.03 REFERENCED STANDARDS
A. State of California Department of Transportation Standard Specifications(Caltrans) 2024.
B. City of Milpitas Standard Specifications
1.04 SUBMITTALS
A. Comply with Section 01330.
B. Manufacturer’s Data or Certificate of Compliance
1. Aggregate base
2. Tack coat
3. Asphalt design mix
4. Seal coat
5. Independent test laboratory hired by the Contractor
C. Furnish a certificate of compliance signed by the manufacturer prior to the use of any asphalt materials.
1. The certificate shall state that the material complies with the requirements of these Specifications.
2. Furnish a certificate with each lot of material delivered to the site with the lot certified clearly identified in the certificate.
3. Provide certificates of compliance for each type of asphalt product used.
PART 2 - PRODUCTS
2.01 GENERAL
A. Provide materials in accordance with:
1. Caltrans Specifications, as modified by this Section.
West Yost – December 2024
270-30-23-22
02740 - 2
Asphalt Paving
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2. City of Milpitas Standard Specifications, as modified by this Section.
2.02 CLASS 2 AGGREGATE BASE
A. Class 2 aggregate base: As specified in Section 02300.
2.03 TACK COAT
A. Caltrans Specification, Section 39 and 94
B. Grade SS-1h asphalt emulsion.
2.04 ASPHALT CONCRETE
A. Hot Mixed Asphalt Concrete Job Mix Formula: Caltrans Specifications, Section 39 for Type A, Asphalt Concrete (1/2-inch maximum aggregate, medium grading).
B. Asphalt Binder: Caltrans paving asphalt, Caltrans Specifications, Section 92
1. PG 64-10
2.05 SEAL COAT
A. Caltrans Specification, Section 37 and 94
B. Grade SS-1 asphalt emulsion.
PART 3 - EXECUTION
3.01 PAVEMENT
A. Construct to the line, grade, and section indicated on the Drawings and in accordance with referenced State Specifications.
B. Sawcut existing asphalt paving that is adjacent to new pavement.
C. Prepare subgrade material per Section 02300.
D. Install geotextile in accordance with Section 02071.
E. Prepare aggregate base course in accordance with Section 02300.
F. Apply tack coat at a minimum residual rate specified for the underlying surface condition as shown in Caltrans Specifications, Section 39. Apply tack coat to all adjoin vertical surfaces no more than 8 hours prior to paving.
G. Place asphalt concrete to the requirements of Caltrans Specifications, Section 39, and Section 22.
1. Install in lifts a minimum of 2-inches thick unless otherwise indicated.
2. Install final lift at a maximum thickness of 2 inches.
H. Density of finished paving: not less than 91% nor greater than 97% of maximum theoretical density as determined by California Test 309 (CTM 309) I. Tolerance of final grade
1. Not more than 0.05 foot from the elevations indicated on the drawings
2. All areas graded to drain
West Yost – December 2024
270-30-23-22
02740 - 3
Asphalt Paving
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3.02 FOG SEAL
A. Apply asphaltic emulsion for fog seal coat to the requirements of Caltrans Specifications, Section 37 and Section 22.
3.03 TESTING
A. Contractor to provide the following Quality Control Testing
1. Aggregate Gradation
a. Test Method: California Test 202
b. Minimum sampling and testing frequency: 1 per 500 tons but no lessthan per day.
c. Point of Sampling: California Test 125
2. Asphalt binder content %
a. Test Method: California Test 379 or 382
b. Minimum sampling and testing frequency: 1 per 1000 tons but no less than per day.
c. Point of Sampling: Loose mix behind paver, see California Test 125.
B. Smoothness
1. Contractorto test in conformance to the requirements of Caltrans Specifications, Section 39-2.01.
2. City may conduct parallel smoothness testing.
3. If the top layer of pavement does not comply with the smoothnessspecifications, Contractor to correct in conformance with Caltrans Specifications, Section 39-
2.01. No compensation will be made for smoothness correction.
C. Pavement Density Nuclear Gage Method
1. Contractor to provide quality control testing at locations based on a random sampling plan with not less than one test per five hundred (500) tons.
2. If the density does not fall within the density range, the Contractor may test at two additional locations within the same 500 tons and average the results of the three tests. This averaged result shall fall within the above-specified range.
3. Contractorshall notify the City prior to paving and provide contact information for Contractor’s testing personnel.
4. City may conduct parallel quality assurance testing at its discretion in accordance with Caltrans test methods, 308, 309, and 375.
END OF SECTION
West Yost – December 2024
270-30-23-22
02740 - 4
Asphalt Paving
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
West Yost – December 2024
270-30-23-22
02821 - 1
Chain Link Fences and Gates
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 02821
CHAIN LINK FENCES AND GATES
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Chain link fences and gates.
1.02 SUBMITTALS
A. Product Data: Submit construction details, material descriptions, gate hardware, and other data completely describing products.
B. Shop Drawings: Submit drawings showing fence and gate details. Include gate elevation drawings, post anchorage details, bracing details, extension arms, and accessories
1.03 REFERENCE SPECIFICATIONS
A. Furnish chain link gate and materials in compliance with City specifications. Where City specifications and thisspecification conflict, City specification take precedence.
1.04 QUALITY ASSURANCE
A. Manufacturer: Specializing in the manufacturer of chain link fence products with at least 5 years of experience.
B. Fence installer: Company with demonstrated successful experience installing similar projects and products in accordance with ASTM F567 and having at least 5 years of experience installing chain link fencing.
C. Tolerances: Current published edition of ASTM specificationstolerances apply.
1.05 DELIVERY, STORAGE, AND HANDLING
A. Storage and Handling: Unload, store, and protect new and existing materials such that they are not damaged.
1.06 SEQUENCE AND SCHEDULING
A. Fences and Gates: May be constructed at any time after earthwork, pipe work, and structures to which fence is related have been completed, but prior to erosion control application.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Steel Chain Link Fabric
1. Height: As indicated
2. Mesh: 1 inch
3. Size Wire: 9 gauge
4. Coating:
a. Provide coating as indicated.
West Yost – December 2024
270-30-23-22
02821 - 2
Chain Link Fences and Gates
City of Milpitas
WellUpgrades Program
McCandless Well Facility
b. Zinc coated Steel Fabric, ASTM A392 hot dipped galvanized before or after weaving,
1) Class 2 (2.0 oz/sf).
c. Polymer Coated (Vinyl) Steel Fabric: ASTM F668.
1) Class 2a extruded and adhered.
2) Color: Black in compliance with ASTM F934
5. Fabric Selvage:
a. Knuckle finish top and bottom.
B. Steel Pipe Fence Framework
1. Steel Pipe and Rail:
a. Schedule 40 standard weight pipe in accordance with ASTM A1088 b. Minimum 1.8 oz/sf hot dip galvanized zinc interior and exterior coating c. Minimum steel yield strength: 30,000 psi
2. Line Posts:
a. 2.375-inch outside diameter, 3.65 pounds per linear foot
3. End, Corner, Pull post:
a. 2.875-inch outside diameter, 5.79 pounds per linear foot
4. Top, Brace, Bottom and Intermediate Rails:
a. 1.90-inch outside diameter, 2.27 pounds per linear foot
5. Polymer Coated Pipe:
a. Provide polymer coated pipe where polymer coated fabric is used. b. Coating: Polyester power coating, fused and adhered to exterior zinc coating in accordance with ASTM F1043.
c. Minimum Coating Thickness: 3 mils minimum.
d. Color: match fabric color.
C. Tension Wire
1. Metallic Coated Steel Marcelled Tension Wire
a. 7-gauge marcelled wire complying with ASTM A824
b. Zinc Coated, ASTM A871 Class 5 (2.0 oz/sf)
c. Galvanized coil spring wire.
2. Polymer Coated Steel Tension Wire
a. Provide polymer coated tension wire where polymer coated fabric is indicated.
b. 7-gauge wire complying with ASTM F1664. Wire gauge specified is the core wire gauge.
c. Provide polymer coated wire where polymer coated fabric is used. 1) Class 2a extruded and adhered.
d. Color: match fabric color.
West Yost – December 2024
270-30-23-22
02821 - 3
Chain Link Fences and Gates
City of Milpitas
WellUpgrades Program
McCandless Well Facility
D. Fittings
1. Tension and Brace Bands: Galvanized pressed steel complying with ASTM F626, minimum steel thickness of 12 gauge, minimum width of 3/4 inch and minimum zinc coating of 1.20 oz/sf. Secure bands with 5/16inch galvanized steel carriage bolts.
2. Terminal Post Caps, Line Post Loop Tops, Rail and Brace Ends, Boulevard Clamps, Rail Sleeves: In compliance to ASTM F626, pressed steel galvanized after fabrication having a minimum zinc coating of 1.20 oz/sf.
3. Truss Rod Assembly: In compliance with ASTM F626, 3/8-inch diametersteel truss rod with a pressed steel tightener, minimum zinc coating of 1.2 oz/sf, assembly capable of withstanding a tension of 2,000 lbs.
4. Tension Bars: In compliance with ASTM F626. Galvanized steel one-piece length 2 inch less than the fabric height. Minimum zinc coating 1.2 oz. /sf. a. Bars for 1 in. mesh shall have a cross section of 1/4 inch by 3/8 inch
5. Polymer Coated Color Fittings: In compliance with ASTM F626, PVC or Polyolefin coating minimum thickness 0.006 in. fused and adhered to the zinc coated fittings, match color to fence system
E. Tie Wire and Hog Rings
1. Galvanized minimum zinc coating 1.20 oz/sf, 9-gauge steel wire in compliance with ASTM F626.
2. 9-gauge aluminum alloy hog rings available for metallic coated fabric.
3. Polymer coated, match the coating, class and color to that of the chain link fabric.
F. Swing Gates
1. Galvanized steel pipe welded fabrication in compliance with ASTM F900.
2. Gate frame members 1.900-inch OD 2.72 lb/lf ASTM F1083 schedule 40 galvanized steel pipe.
3. Frame members spaced no greater than 8 feet. apart vertically and horizontally.
4. Welded joints protected by applying zinc-rich paint in accordance with ASTM Practice A780.
5. Positive locking gate latch, pressed steel galvanized after fabrication.
6. Galvanized malleable iron or heavy gauge pressed steel post and frame hinges.
7. Provide lockable drop bar and gate holdbacks with double gates.
8. Match gate fabric to that of the fence system.
9. Extend gate posts and frame members above the top of the chain link fabric at both ends of gate frame to provide support for barbed wire where barbed wire is indicated.
10. Polymer coated gate frames; match the coating type and color to that specified for the fence framework. Moveable parts such as hinges, latches and drop rods may be field coated using a liquid polymer touch up.
West Yost – December 2024
270-30-23-22
02821 - 4
Chain Link Fences and Gates
City of Milpitas
WellUpgrades Program
McCandless Well Facility
G. Gate Posts and Concrete Foundations for Gate Posts:
1. Gateposts per ASTM F1083 schedule 40 galvanized steel pipe.
Gate Leaf Widths, feet
Posts Foundations
O.D., inches
Ounces
per Lin Ft Diameter, inches Depth, feet
Gates with fence fabric up to and including 6 ft in height 0 to 4 2.375 3.56 12 3
Over 4 to 10 2.875 5.79 12 4
Over 6 to 18 4.000 9.11 18 3
Gates with fence fabric over 6 ft to 12 ft in height
0 to 6 2.875 5.79 12 4
Over 6 to 12 4.000 9.11 18 3
Over 12 to 18 6.625 18.97 18 4
Over 18 to 25 8.625 28.58 18 4.5
2. Polymer coated gate posts; match the coating type and color to that specified for the fence framework.
H. Concrete: Minimum 28-day compressive strength of 2,500 psi.
I. Fence Grounding:
1. Conductors: Bare, solid copper wire No. 6 AWG.
2. Connectors: Metal ground connectors, suitable for connecting to the ground rod and the metal fence post.
3. Ground rods: Copper clad, 5/8-inch diameter by 96-inch long.
PART 3 - EXECUTION
3.01 EXAMINATION
A. Verify field conditions prior to construction.
3.02 GENERAL
A. Install chain link fence and gates as indicated on the Drawings and specified in this Section.
B. Provide fence systems that are plumb, taut, true to line and grade, and complete in all details.
C. Install fencing to generally follow finish grade of ground and provide pull posts at points where required to conform to change in grade.
D. Install fencing such thatspace between bottom of fence and finish grade does not exceed 1 inch.
E. Unless otherwise indicated install fence with top rail and bottom tension wire.
West Yost – December 2024
270-30-23-22
02821 - 5
Chain Link Fences and Gates
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3.03 CLEARING FENCE LINE
A. Survey, clear, grub, grade and remove debris for installation of the fence line or required clear areas adjacent to the fence as indicated. Where no requirements are indicated, provide minimum 10 feet wide cleared and graded area centered on the fence line.
3.04 INSTALLATION
A. Posts:
1. Set posts plumb in concrete footings in accordance with ASTM F567.
2. Unless otherwise indicated:
a. Set minimum footing depth, 24 inches plus an additional 3-inch depth for each 1 foot increase in the fence height over 4 feet.
b. Minimum footing diameter four times the largest cross section of the post up to a 4.00 inches outside diameter and three times the largest cross section of post greater than a 4.00 inches outside diameter. c. Top of concrete footing to be at grade, crowned to shed water away from the post.
d. Line posts installed at intervals not exceeding 10 ft. (3.05 m) on center.
3. Finish top of concrete footings in a workmanlike manner.
B. Top Rail:
1. Install top rail in 21 foot lengths of rail continuous thru the line post or barb arm loop top.
2. Splice rail using top rail sleeves minimum 6-inches long.
3. Secure rail shall to terminal post by a brace band and rail end.
C. Bottom/Intermediate Rail:
1. Field cut and secure rail to line posts using boulevard clamps or brace band with rail end.
D. Terminal posts:
1. Brace and truss end, corner, pull and gate posts for fence 6 feet and higher and for fences 5 feet in height not having a top rail.
2. Install horizontal brace rail and diagonal trussrod in accordance with ASTM F567.
E. Tension wire:
1. Install tension wire 4 inches up from the bottom of the fabric.
2. Install tension wire 4 inches down from the top of the fabric where fence does not have a top rail.
3. Stretch tension wire taut, independently and prior to the fabric, between the terminal posts and secure to the terminal post using a brace band.
4. Secure the tension wire to each line post with a tie wire.
West Yost – December 2024
270-30-23-22
02821 - 6
Chain Link Fences and Gates
City of Milpitas
WellUpgrades Program
McCandless Well Facility
F. Chain Link Fabric:
1. Install fabric to outside of the framework.
2. Attach fabric to the terminal post by threading the tension bar through the fabric; secure the tension bar to the terminal post with tension bands and 5/16-inch carriage bolts spaced no greater than 12 inches on center.
3. Small mesh fabric less than 1 inch, attach to terminal post by sandwiching the mesh between the post and a vertical 2-inch-wide by 3/16-inch galvanized steel strap using carriage bolts, bolted thru the bar, mesh and post spaced 15 inches on center.
4. Stretch chain link fabric taut free of sag.
5. Secure fabric to line posts with tie wires spaced no greater than 12 inches on center and to horizontal rail spaced no greater than18 inches on center.
6. Secure fabric to the tension wire with hog rings spaced no greater than 18 inches on center.
7. Secure tie wires:
a. Wrap tie wire around the post or rail and attach to the fabric wire picket on each side by twisting the tie wire around the fabric wire picket two full turns.
b. Cut off excess wire and bend over to prevent injury.
G. Gate Installation
1. Swing Gates:
a. Installswing gates and gateposts in compliance with ASTM F567. b. Direction of swing: as indicated.
c. Install gates plumb in the closed position having a maximum bottom clearance of 2 inches.
d. Install gates with hinge and latch offset opening no greater than 3 inches in the closed position.
e. Install double gate drop bar receivers in a concrete footing minimum 8- inch diameter by 16 inch deep.
f. Install gate leaf holdbacks for all double gates.
g. Install electrically operated gates in compliance with ASTM F2200 and UL 325.
2. Nuts and Bolts
a. Install carriage bolts with the head on the secure side of the fence. b. Peen over end of all bolts to prevent removal of the nut.
3.05 ADJUSTING
A. Adjust gate travel, stops, and operator position to meet field conditions.
West Yost – December 2024
270-30-23-22
02821 - 7
Chain Link Fences and Gates
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3.06 FENCE GROUNDING
A. Install fence grounding where high-tension power lines cross fence line, fencing is within 150 feet horizontally of high-tension power lines or as indicated.
B. Grounding locations:
1. Power line crossing: At nearest fence post to crossing, nearest fence post each side of crossing at 150 feet from crossing, and at each gate within 150 feet of crossing.
2. Power line parallel: At nearest fence post to 150 foot intervals and at each gate.
C. Grounding method.
1. At each grounding location, drive ground rod vertically next to fence post until top is flush with finish grade.
2. Connect conductor to ground rod, fence post and fence fabric with metal connector.
3. Bond each gate with a flexible grounding strap.
3.07 CLEANING
A. Leave the area of the fencing neat and free of debris caused by the installation of the fence.
3.08 PROTECTION
A. Protect installed fences and gates against damage and, if damaged, repair prior to final acceptance.
END OF SECTION
West Yost – December 2024
270-30-23-22
02821 - 8
Chain Link Fences and Gates
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
PASE – December 2024
270-30-23-22
03301 - 1
Cast-In-Place Concrete
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 03301
CAST-IN-PLACE CONCRETE
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Requirements for cast-in-place concrete work.
1.02 REFERENCED SECTIONS
A. The following Section is referenced in this Section
1. Section 01330 – Submittals
1.03 SUBMITTALS
A. Comply with Section 01330.
B. Shop Drawings
1. Reinforcing Steel: Prepare shop fabrication and field installation drawings in accordance with CRSI Manual of Standard Practice and ACI SP.
2. Layout drawings for construction joints.
C. Product Data: Waterstops, curing compound data.
D. Concrete Mix Design: Data on the concrete mix, including aggregate gradations and admixtures, in accordance with ASTM C94.
E. Quality Control Submittals
1. Manufacturer’s application instructionsfor curing compound.
2. Ready-mix delivery tickets for each truck in accordance with ASTM C94.
1.04 QUALITY ASSURANCE
A. Supplier Qualifications: A minimum of 5 years’ experience manufacturing ready-mixed concrete and that complies with ASTM C94 for production facilities and equipment.
B. Source Limitations: Use the same brand of cement from the same manufacturer's plant, obtain aggregate from one source, and obtain admixtures through one source from a single manufacturer.
C. Concrete and Reinforcement: Unless otherwise specified, meet the requirements of ACI 301 and 318.
D. Hot Weather Concreting: Conform to ACI 305R.
PART 2 - PRODUCTS
2.01 FORMWORK
A. Exposed Areas: Use hard plastic finished plywood.
B. Unexposed Areas: Use new ship lap or plywood.
C. Earth cuts may be used for forming footings.
PASE – December 2024
270-30-23-22
03301 - 2
Cast-In-Place Concrete
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2.02 CONCRETE
A. Ready-mixed meeting ASTM C94, Option A.
B. Portland Cement: ASTM C150, Type II.
C. Aggregates: Furnish from one source.
1. Natural Aggregates
a. Free from deleterious coatings and substances in accordance with ASTM C33, except as modified herein.
b. Free of materials and aggregate types causing pop outs, discoloration, staining, or other defects on surface of concrete.
2. Non-Potentially Reactive: In accordance with ASTM C33, Appendix XI, paragraph X1.1.
3. Aggregate Soundness: Test for fine and coarse aggregates in accordance with ASTM C33 and ASTM C88 using sodium sulfate solution.
4. Fine Aggregates
a. Clean,sharp, naturalsand.
b. ASTM C33.
c. Materials Passing 200 Sieve: 4 percent maximum.
d. Limit deleterious substances in accordance with ASTM C33, Table 1 with material finer than 200 sieve limited to 3 percent, coal and lignite limited to 0.5 percent.
5. Coarse Aggregate
a. Natural gravels, combination of gravels and crushed gravels, crushed stone, or combination of these materials containing no more than 15 percent flat or elongated particles (long dimension more than five times the short dimension).
b. Materials Passing 200 Sieve: 0.5 percent maximum.
D. Admixtures: Do not use admixtures that contribute water-soluble chloride ions exceeding those permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride.
1. Air-Entraining: ASTM C260.
2. Water-Reducing: ASTM C494, Type A or D.
3. Superplasticizers: ASTM C494, Type F or G.
4. Fly Ash: ASTM C618, Class C or F.
5. Color Pigments: Inert mineral or metal oxide pigments, natural or synthetic; resistant to lime and other alkalies.
E. Concrete Mix Design
1. Minimum Compressive Field Strength: 4,000 psi at 28 days when cured and tested in accordance with ASTM C31 and C39.
PASE – December 2024
270-30-23-22
03301 - 3
Cast-In-Place Concrete
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2. Coarse Aggregate Size: 1-1/2 inches and smaller.
3. Slump Range: 3 to 5 inches.
4. Air Entrainment: Between 1 and 3 percent by volume.
5. Water Reducers: Use in concrete without plasticizers.
F. Proportions
1. Design mix to meet aesthetic and structural concrete requirements.
2. Water-cement ratio (water-cement plus fly ash ratio) shall control amount of total water added to concrete as follows:
Coarse Aggregate Size W/C Ratio
1-1/2 inch 0.50
1 inch 0.45
3. Minimum Cement Content (Combined Cement Plus Fly Ash Content):
a. 541 pounds per cubic yard for concrete with 1½ inch maximum size aggregate.
b. 564 pounds per cubic yard for 1 inch maximum size aggregate.
4. Increase cement content (combined cement plus fly ash content), as required meeting strength requirements and water-cement ratio.
5. Fly Ash Content: minimum 20 percent, maximum 50 percent by weight of total cement content.
G. Mixing: Minimum 70 and maximum 270 revolutions of mixing drum. Non-agitating equipment is not allowed.
2.03 REINFORCING STEEL
A. Deformed Bars: ASTM A615, Grade 60. Reinforcing steel to be welded shall be ASTM A706, Grade 60.
B. Welded Wire Reinforcement: ASTM A1064, fabricated from as-drawn steel wire into flat sheets.
C. Bar Supports:
1. For Slab Rebar: Concrete blocks or plastic bar supports.
2. For Rebar in Walls, Beams, Columns, and Slabs Exposed to View: Galvanized steel chairs with plastic tips or plastic bar supports and side form spacers.
2.04 ANCILLARY MATERIALS
A. Curing Compound
1. Material: Water-based product in accordance with ASTM C309, Type 1, Class A.
2. Manufacturers and Products
a. W. R. Meadows, Inc.; 1300-CLEAR
PASE – December 2024
270-30-23-22
03301 - 4
Cast-In-Place Concrete
City of Milpitas
WellUpgrades Program
McCandless Well Facility
b. Euclid Chemical Co.; Kurex DR VOX
B. Epoxy Bonding Agent and Adhesives(for Binding New Concrete to Existing Concrete)
1. Epoxies: Two component material for use on dry or damp surfaces and conforming to the requirements of ASTM C881, Type II, Grade 2, Class C.
2. Apply in accordance with manufacturer’s recommendations.
3. Manufacturers: One of the following or equal:
a. Sika Corporation; Sikadur-2 Hi-Mod LPL
b. Euclid Chemical Co.; DURAL LPL MV
C. Waterstops
1. General: Place hydrophilic and/or rubber dumbbell type or center bulb type waterstops at construction joints and other joints as specified and indicated on the Drawings.
2. Hydrophilic Waterstops:
a. Use: For concrete repairs or when attaching new concrete to existing structures.
b. Manufacturers: One of the following or equal:
1) Greenstreak, Hydrotite CJ.
2) Tremco, Parastop II.
c. Installation: As indicated on the Drawings and in accordance with manufacturer’sinstructions.
3. Rubber Waterstops
a. Use: At new construction joints where indicated on the Drawings. b. Material: PVC or rubber waterstops manufactured by one of the following, or equal:
1) Greenstreak.
2) Progress Unlimited.
3) Williams Products.
c. Size:
1) Construction and Contraction Joints. 6-inch flat dumbbell type. 2) Expansion Joints: 9-inch wide dumbbell with hollow center bulb.
D. Expansion Joint Filler: ASTM D994, 1/2-inch thick, or as shown.
E. Surface Hardener
1. Premixed, noncolored, nonmetallic Master Builders, Mastercron; Sonneborn, Harcol; A. C. Horn Inc., Durafax; Burke Company Non-Metallic Floor Hardner; or equal.
2. Apply in accordance with manufacturer'sinstructions.
PASE – December 2024
270-30-23-22
03301 - 5
Cast-In-Place Concrete
City of Milpitas
WellUpgrades Program
McCandless Well Facility
F. Concrete for Electrical Conduits
1. Concrete encasement for electrical conduit shall contain 3 pounds of red oxide per sack of cement.
G. Vapor Barrier
1. Material: 15 mil, multilayer plastic, 0.01 minimum permeance rating.
2. Manufacturers: One of the following or equal:
a. StegoWrap, Stego Industries.
b. Premoulded Membrane Vapor Seal with Plasmatic Corel, W. R. Meadows.
PART 3 - EXECUTION
3.01 FORMWORK
A. Design, construct, erect, brace and maintain formwork in accordance with ACI 301.
B. Form Ties
1. Fixed conical or spherical type inserts that remain in contact with forming material and allow for dry packing of form tie holes.
2. Space ties to withstand pressures and to limit deflection of forms to acceptable limits.
3. Wire ties are not acceptable.
C. Construction
1. In accordance with ACI 347.
2. Make joints tight to prevent escape of mortar and to avoid formation of fins.
3. Brace as required to prevent distortion during concrete placement.
4. On exposed surfaces locate form ties in uniform pattern or asshown.
5. Construct so ties remain embedded in the wall with no metal within 1-inch of concrete surface when forms, inserts, and tie ends are removed.
D. Form Removal
1. Remove after concrete has attained 28 day strength, or approval is obtained in writing from Engineer.
2. Remove forms with care to prevent scarring and damaging the surface.
3.02 PLACING REINFORCING STEEL
A. Place reinforcing steel in accordance with CRSI Recommended Practice for Placing Reinforcing Bars.
B. Field bending or welding of reinforcing bars will not be allowed.
C. Bar Supports: Provide in sufficient quantity to preventsagging and to support bars during concrete placement.
PASE – December 2024
270-30-23-22
03301 - 6
Cast-In-Place Concrete
City of Milpitas
WellUpgrades Program
McCandless Well Facility
D. Splices and Laps
1. Top Bars: Horizontal bars placed such that 12 inches of fresh concrete is cast below in single placement.
2. Horizontal wall bars are considered top bars.
3. Bar lap splices shall conform to General Structural Notes on the Drawings.
4. Tie splices with 18-gauge annealed wire as specified in CRSI Standard.
3.03 PLACING CONCRETE
A. Place concrete in accordance with ACI 301.
B. Before placing concrete:
1. Check reinforcing steel for proper placement and correct discrepancies.
2. Remove excessive rust, millscale, dirt, oil and other material from rebarthat may adversely affect bonding to concrete.
3. Remove water from excavation and debris and foreign material from forms.
C. Before depositing new concrete on existing concrete, clean surface using sandblast or other mechanical means to obtain a 1/4-inch rough profile, and apply epoxy bonding agent in accordance with the manufacturer’s instructions.
D. Place concrete as soon as possible after leaving mixer, without segregation or loss of ingredients, without splashing forms or steel above, and in layers not over 2 feet deep.
Place within 1-1/2 hours after adding cement to mix.
E. Placement Limitations: 8 feet maximum vertical drop to final placement, when not guided with chutes or other devices to prevent segregation due to impact with reinforcing.
F. Hot Weather
1. Prepare ingredients, mix, place, cure, and protect in accordance with ACI 305R.
2. Maintain concrete temperature below 80 degrees F at time of placement, or furnish test data or provide other proof that admixtures and mix ingredients do not produce flash set plastic shrinkage, or cracking due to heat of hydration.
Ingredients may be cooled before mixing to maintain fresh concrete temperatures at 80 degrees F or less.
3. Make provisions for windbreaks, shading, fog spraying, sprinkling, ice, or wet cover, or other means to provide concrete with temperature specified.
4. Maximum allowable temperature differential between reinforcing steel and concrete: Not greater than 20 degrees F at the time of concrete placement.
3.04 COMPACTION
A. Vibrate concrete as follows:
1. Apply approved vibrator at points spaced not farther apart than vibrator’s effective radius.
2. Apply close enough to forms to vibrate surface effectively but not damage form surfaces.
PASE – December 2024
270-30-23-22
03301 - 7
Cast-In-Place Concrete
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3. Vibrate until concrete becomes uniformly plastic.
4. Vibrator must penetrate fresh placed concrete and into previous layer of fresh concrete below.
3.05 CONSTRUCTION JOINTS
A. Locate as shown or as approved.
B. Maximum Spacing Between Construction Joints: 40 feet, unless otherwise indicated.
3.06 CRACK CONTROL JOINTS
A. Provide crack control jointsin concrete slabs on grade, curbs, gutters,sidewalks and other concrete flatwork as follows:
1. Install crack control joints by use of grooving tool on fresh concrete or saw-cut by use of a saw designed for crack control joints as soon as the concrete hardens sufficiently to support the saw, however, no longer than 12 hours after concrete placement.
2. Depth: 1/4 the thickness of the slab.
3. Frequency: Unless otherwise indicated,
a. Maximum spacing of 2.5 times the slab thickness in feet (6-inch slab ≤ 15 feet on center).
b. Rectangular slabs: Maximum 1½ to 1 ratio of side lengths.
3.07 SLAB FINISHES
A. General
1. The finishesspecified herein include surface finishes, treatments and toppingsfor floors and slabs. Floors shall be sloped to drain uniformly. Unless otherwise specified,slope shall be minimum 1/8 inch per foot towards nearest drain. Where finish is not specified, floor slabs shall receive steel troweling. Dry cement shall not be used on new concrete surfaces to absorb excess moisture. Edges shall be rounded to a radius of 1/2 inch. Joints shall be grooved to a radius and depth of 1/2 inch each. Uneven-slope tolerance is 1/4-inch in 10 feet.
B. Float Finish
1. Conform to ACI 301, Section 11.7.2. Floating shall be performed with a hand or power-driven float. Floating of any one area shall be the minimum necessary to produce the finish specified. Floating shall compact and smooth the surface and close any cracks and checking of surfaces.
C. Broomed Finish
1. Conform to ACI 301, Section 11.7.4. Broomed finish shall be provided for walks, slabs on grade exposed to atmosphere, and where otherwise indicated or specified. Apply float finish, then a light broom finish to produce a profile that is parallel to the slab drainage.
PASE – December 2024
270-30-23-22
03301 - 8
Cast-In-Place Concrete
City of Milpitas
WellUpgrades Program
McCandless Well Facility
D. Steel Trowel Finish
1. Conform to ACI 301, Section 11.7.3. Immediately afterfinal troweling, the surface shall be cured and protected. Steel trowel finish shall be provided on chemical room floor unless specified otherwise. Surface hardener shall be troweled into the finished surface.
3.08 FINISHING AND PATCHING FORMED SURFACES
A. Unexposed Surfaces: Provide rough-formed concrete texture as imparted by form-facing material, fill form tie holes with nonshrink grout and grind off projections, fins, and rough spots.
B. Exposed Surfaces: Provide smooth-formed concrete texture as imparted by form-facing material, arranged in an orderly and systematic manner with a minimum number of seams. Fill form tie holes with nonshrink grout and grind off projections, fins, and rough spots. Where scheduled, apply rubbed surface as follows:
1. Smooth Rubbed Finish: Not later than one day after form removal, moisten concrete surfaces and rub with carborundum brick or another abrasive to produce a uniform color and texture. Do not apply cement grout other than that created by the rubbing process.
2. Grout-Cleaned Finish: Wet concrete surfaces and apply grout of a consistency of thick paint to coat surfaces and fill small holes.
a. Mix one part portland cement to one and one-half parts fine sand with a 1:1 mixture of bonding admixture and water. Add white portland cement in amounts determined by trial patches so color of dry grout will match adjacent surfaces.
b. Scrub grout into voids and remove excess grout. When grout whitens, rub surface with clean burlap and keep surface damp by fog spray for at least 36 hours.
3. Cork-Floated Finish: Wet concrete surfaces and apply a stiff grout. a. Mix one part portland cement and one part fine sand with a 1:1 mixture of bonding agent and water. Add white portland cement in amounts determined by trial patches so color of dry grout will match adjacent surfaces.
b. Compress grout into voids by grinding the concrete surface in a swirling motion, then finish the surface with a cork float.
C. Patching Defective Areas: Patch defective areas and repair rough spots resulting from form release agent failure or other reasons to provide smooth uniform appearance.
1. Cut out honeycombed and defective areas.
2. Cut edges perpendicular to surface at least 1-inch deep. Do not feather edges.
Soak area with water for 24 hours.
3. Finish surfaces to match adjacent concrete.
4. Keep patches damp for minimum 7 days or spray with curing compound to minimize shrinking.
PASE – December 2024
270-30-23-22
03301 - 9
Cast-In-Place Concrete
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3.09 PROTECTION AND CURING
A. Protect fresh concrete from direct rays of sunlight, drying winds, and wash by rain.
B. Keep concrete slabs continuously wet for a 7 day period. Intermittent wetting is not acceptable.
C. Use curing compound only where approved by Engineer. Cure formed surfaces with curing compound applied in accordance with manufacturer’s directions as soon as forms are removed and finishing is complete.
1. Do not use curing compound on concrete surfaces that will be painted.
D. Remove and replace concrete damaged by freezing.
3.10 FIELD QUALITY CONTROL
A. Concrete Samples:
1. Provide concrete for making composite samples for testing slump, air content, and for making cylinders for determination of compressive strength.
2. Prepare samples in accordance with ASTM C172. Select trucks or batches of concrete on a random basis.
3. Samples may be obtained at the discharge chute of the truck or at the point of discharge into forms.
B. Sampling Frequency: One composite sample for each 100 cubic yards of structural concrete, or fraction thereof, of each concrete mixture placed in any one day.
C. Evaluation will be in accordance with ACI 301, Chapter 17 and Specifications.
D. Slump tests and concrete cylinders will be made by the City. City will handle cured test cylinders, transport to the testing laboratory and pay testing costs.
E. Enforcement of Compressive Strength Requirements:
1. Compressive strength of concrete will be considered acceptable if the following conditions are satisfied:
a. Averages of all sets of 3 consecutive strength test results are greater or equal to the specified compressive strength.
b. No individual strength test (average of 2 cylinders) falls below specified compressive strength by more than 500 pounds per square inch.
2. Whenever one, or both, of 2 conditions stated above is not satisfied, provide additional curing of affected portion of structure, then obtain test cores from the affected area.
a. Obtain 3 test cores in accordance with ASTM C 42 and ACI 318. b. Concrete will be considered acceptable if the average compressive strength of the 3 test coresis equal to at least 90 percent of the specified 28-day compressive strength and no single core is lessthan 80 percent of the specified 28-day compressive strength.
c. Concrete will be designated as defective when the specified conditions are not achieved.
PASE – December 2024
270-30-23-22
03301 - 10
Cast-In-Place Concrete
City of Milpitas
WellUpgrades Program
McCandless Well Facility
d. Fill core holes with concrete.
3. Engineer may require the Contractor to strengthen defective concrete by means of additional concrete, additional reinforcing steel, or replacement of defective concrete, all of the Contractor's expense.
END OF SECTION
PASE – December 2024
270-30-23-22
03600 - 1
Grout
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 03600
GROUT
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Grout for uses other than masonry.
1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section
1. Section 01330 – Submittals
2. Section 03301 – Cast-In-Place Concrete
1.03 SUBMITTALS
A. Comply with Section 01330.
B. Manufacturer’s Data
1. Provided for the following:
a. Dry pack grout
b. Cement grout
c. Nonshrink grout, non-metallic
d. Nonshrink grout, metallic
e. Pressure grout
f. Epoxy grout
g. Polymer concrete
C. Laboratory Test Reposts
1. Test reports on previously tested materials shall be accompanied by the manufacturer's statement that the previously tested material is the same type, quality, manufacture, and make as that proposed for use in this project.
2. Test reports are required for the following:
a. Cement
b. Aggregates
c. Bonding compounds
d. Admixtures
PART 2 - PRODUCTS
2.01 MATERIALS
A. Cement
1. Portland cement: ASTM C150 Type II or Type V, low alkali, containing less than
0.60 percent alkalis.
PASE – December 2024
270-30-23-22
03600 - 2
Grout
City of Milpitas
WellUpgrades Program
McCandless Well Facility
B. Aggregate
1. General
a. Nonreactive and washed before use.
b. When sources of aggregate are changed, provide test reportsfor the new material.
c. Perform the tests specified prior to commencing grout work.
2. Fine Aggregate
a. Hard, dense, durable particles of either sand or crushed stone regularly graded from coarse to fine and shall conform to ASTM C33 as modified herein.
b. When tested in accordance with ASTM C136, gradation shall be such that 100 percent by weight will pass a standard No. 8 mesh sleeve and no less than 45 percent by weight will pass a standard No. 40 mesh sieve.
3. Variation from the specified gradationsin individual tests will be acceptable if the average of three consecutive tests is within the specified limits and the variation is within the permissible variation listed below:
US standard sieve size
Permissible variation in individual
tests, percent
30 or coarser 2.0
50 or finer 0.5
4. Other tests shall be in accordance with the following specifications:
Test Test Method Requirements
Organic Impurities ASTM C40 Color lighter than standard Amount of Material Passing No. 200
Sieve ASTM C117 3% maximum by weight
Soundness ASTM C88 10% maximum loss with sodium sulfate Reactivity ASTM C289 Innocuous aggregate
Sand Equivalent ASTM D2419 Minimum 80
C. Admixtures
1. General
a. Compatible with the grout.
b. Calcium chloride or admixtures containing calcium chloride are not acceptable.
c. Used in accordance with the manufacturer's recommendations and added separately to the grout mix.
2. Water Reducing Retarder
a. ASTM C494 Type D.
b. Master Builders Pozzolith 300-R, Sika Corporation Plastiment, or equal.
PASE – December 2024
270-30-23-22
03600 - 3
Grout
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3. Lubricant for Cement Pressure Grouting
a. Lubricant additive for cement pressure grouting shall be Intrusion Prepakt Intrusion Aid, Sika Intraplast N, or equal.
D. Water
1. Water for washing aggregate, for mixing and for curing shall be free from oil and deleterious amounts of acids, alkalis, and organic materials; shall not contain more than 500 mg/1 of chlorides as Cl, nor more than 800 mg/1 of sulfates as SO4; and shall not contain an amount of impurities that may cause a change of more than 25 percent in the setting time of the cement nor a reduction of more than five percent in the compressive strength of the grout at 14 days when compared with the result obtained with distilled water.
2. Additionally, water used for curing shall not contain an amount of impurities sufficient to discolor the grout.
2.02 GROUT
A. Drypack Grout
1. A mixture of approximately one part cement, 1-1/2 to 2 parts sand, water reducing retarder, and sufficient water to make a stiff workable mix.
B. Cement Grout
1. A mixture of one part cement, two parts sand, proportioned by volume, admixtures for pressure grouting, and sufficient water to form a workable mix.
C. Nonshrink Grout, Non-Metallic
1. Nonshrink, nonmetallic aggregate grout shall be Five Star Products, Inc. Five Star Grout, Master Builders Masterflow 928, Euclid Chemical Co. High-Flow Grout, or equal.
D. Nonshrink grout, Metallic
1. Nonshrink, metallic grout shall be Master Builders MasterFlow 885, Euclid Chemical Co. High-Flow Metallic Grout, or equal.
E. Epoxy Grout for Crack Repair
1. Except as noted below, epoxy grout shall be a high modulus, two-component, moisture insensitive, 100 percent solids, thermosetting modified polyamide epoxy compound.
a. The consistency shall be a paste form capable of not sagging in horizontal or overhead anchoring configurations.
b. Material shall conform to ASTM C881 Type 1, Grade 3, such as Master Builders MasterEmaco ADH 327, Sika Corporation Sikadur Hi-Mod Series, Adhesive Technology Corporation Solidbond 200 or equal, and shall have a heat deflection temperature in excess of 130 degrees F.
2. Epoxy for pressure grouting/crack injection shall be a two-component, moisture insensitive, high modulus, injection grade, 100 percent solids, blend of epoxyresin compounds.
PASE – December 2024
270-30-23-22
03600 - 4
Grout
City of Milpitas
WellUpgrades Program
McCandless Well Facility
a. The consistency shall be as required to achieve complete penetration in hairline cracks and larger.
b. Material shall conform to ASTM C881 Type 1 Grade 1, such as Sika Corporation Sikadur 52, Master Builders MasterInject 1500, Adhesive Technology Corporation SLV 300 series, or equal.
F. Polymer Concrete (For Resurfacing or Patching)
1. Polymer concrete (for resurfacing or patching) shall consist of a liquid binder and dry aggregate mixed together to make a mortar or grout of a consistency as required for the application.
2. The liquid binder shall be a chemical and oil resistant, stress relieved, low modulus, moisture insensitive, two-component epoxy-resin compound.
3. The consistency shall be similar to lightweight oil for proper mixing with aggregate.
4. Material shall conform to ASTM C881 Type 3 Grade 1, such as Sika Corporation Sikadur Lo-Mod series, Master Builders MasterSeal 350, Adhesive Technology Corporation 400 series, or equal.
5. The aggregate shall be oven dry in sealed packages until time of mixing, and shall be of size and consistency compatible with recommendations of manufacturer of liquid binder for intended application.
2.03 PRESSURE GROUTING EQUIPMENT
A. Pressure grouting equipment shall include a mixer and holdover agitator tanks and shall be designed to place grout at pressures up to 50 psi.
B. Provide gages to indicate pressure used.
C. The mixer shall be provided with a meter capable of indicating to one-tenth of a cubic foot the volume of grout used.
PART 3 - EXECUTION
3.01 GENERAL
A. Bonding compound for use with grout isspecified in Section 03301. Primer, if required for polymer concrete, shall be provided per manufacturer's recommendation.
3.02 DRYPACK GROUT
A. Use drypack grout for built-up surfaces, setting miscellaneous metal items and minor repairs.
B. Surfaces required to be built up with drypack grout shall be roughened by brushing, cleaned, and coated with the bonding compound specified in Section 03301 before the application of the grout.
C. Apply drypack grout immediately following the application of the bonding compound in bands orstripsto form a covering of the required thickness. The covering shall be smooth.
D. Construction joints in the grout shall be sloped and shall be cleaned and wetted before application is resumed.
PASE – December 2024
270-30-23-22
03600 - 5
Grout
City of Milpitas
WellUpgrades Program
McCandless Well Facility
E. Cure drypack grout in accordance with Section 03301.
F. Grout shall not be placed during freezing weather unless adequate protection is provided.
3.03 CEMENT GROUT
A. Use cement grout for filling nonbearing portions of equipment pads and pressure grouting.
B. Except for the specialized equipment for pressure grouting, mixing and placing apparatus shall be similar to that normally used for cast-in-place concrete.
C. Mix grout for a period of at least 1 minute.
D. Agitate diluted grout to keep ingredients mixed.
3.04 NONSHRINK GROUT
A. Nonshrink, metallic aggregate grout shall be used for the bearing surfaces of machinery and equipment bases, column base plates and bearing plates at dry, interior locations.
B. Nonshrink, non-metallic aggregate grout shall be used for the bearing surfaces of machinery and equipment bases, column base plates, and bearing plates at damp or exterior locations as well as for setting handrail, guardrail, or fence posts in pipe sleeves.
Grout shall meet the requirements of CRD-C621 and shall be placed in accordance with manufacturer's instructions.
3.05 EPOXY GROUT
A. Epoxy grout shall be used for repairing cracks by pressure grouting or gravity flow and for repairing structural concrete.
B. Concrete shall be primed in accordance with the grout manufacturer'sinstructions.
3.06 PRESSURE GROUTING
A. Prior to grouting, systems and holes to be grouted shall be washed clean.
B. Washing is not required for grouting soil voids outside pipe cylinders or casing pipes.
C. Grouting, once commenced, shall be completed without stoppage.
D. In case of breakdown of equipment, wash out the grouting system sufficiently to ensure fresh grout and adequate bond and penetration will occur upon restarting the grouting operation.
E. Maintain grout pressure until grout has set.
END OF SECTION
PASE – December 2024
270-30-23-22
03600 - 6
Grout
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
PASE – December 2024
270-30-23-22
04200 - 1
Concrete Masonry Units
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 04200
CONCRETE MASONRY UNITS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Concrete masonry units, mortar, grout, and reinforced masonry construction.
1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section
1. Section 01330 – Submittals
2. Section 09900 – Coating Systems
1.03 SUBMITTALS
A. Comply with Section 01330.
B. Product Data: For each type of masonry unit, masonry accessory, and admixture to be incorporated into the Work.
C. Shop Drawings: Submit reinforcement placing drawings with details of bond beams and lintels. Comply with ACI 315, "Details and Detailing of Concrete Reinforcement." Show elevations of reinforced walls with locations of control joints and wall penetrations.
D. Samples for each type and color of exposed masonry units and colored mortars.
E. Material Certificates: For each type of product indicated. Include statements of material properties indicating compliance with requirements including compliance with standards and type designations within standards.
F. Mix Designs: For each type of mortar and grout. Include description of type and proportions of ingredients.
1.04 QUALITY ASSURANCE
A. Preconstruction Testing Service: Contractor shall engage a qualified independent testing agency to perform preconstruction testing indicated below. Payment for these services shall be made by Contractor.
1. Concrete Masonry Unit Test: For each type of unit required, per ASTM C140.
2. Mortar Test (Property Specification): For each mix required, per ASTM C780.
3. Grout Test (Compressive Strength): For each mix required, per ASTM C1019.
B. Sample Panels: Build sample panels to verify selections made under sample submittals and to demonstrate aesthetic effects. Build sample panels for typical exterior wall in sizes approximately 48 inches long by 48 inches high.
1.05 PROJECT CONDITIONS
A. Cold-Weather Requirements: Do not use frozen materials or materials mixed or coated with ice or frost. Do not build on frozen substrates. Remove and replace unit masonry damaged by frost or by freezing conditions. Comply with cold-weather construction requirements contained in ACI 530.1/ASCE 6/TMS 602.
PASE – December 2024
270-30-23-22
04200 - 2
Concrete Masonry Units
City of Milpitas
WellUpgrades Program
McCandless Well Facility
B. Hot-Weather Requirements: Comply with hot-weather construction requirements contained in ACI 530.1/ASCE 6/TMS 602.
PART 2 - PRODUCTS
2.01 CONCRETE MASONRY UNITS
A. General
1. Modular dimensions and air, water, or steam cured.
2. Surface Texture: Provide split-face,scored split-face, or ground-face blocks where indicated on the Drawings. At other locations, provide precision masonry units with comparatively smooth and uniform surface texture.
B. Hollow Load Bearing Concrete Masonry Units
1. Provide hollow load-bearing units conforming to ASTM C90, made with lightweight aggregate.
2. Provide load-bearing units unless otherwise specified.
3. Unit Compressive Strength: Provide units with minimum average net-area compressive strength of 2,000 psi.
4. Weight Classification: Light weight.
C. Special Shapes: Provide special shapes for lintels, corners, jambs, sashes, movement joints, headers, bonding, and other special conditions.
D. Size and Color: Nominal 16-inch long by 8-inch wide by 8-inch tall units arranged to form a running bond pattern as indicated on the Drawings. Color to be the Manufacturer’s standard Tan color or asselected by City from submitted color palette.
E. Water Repellent and Anti-Graffiti Coatings: As indicated in Section 09900.
2.02 MORTAR MATERIALS
A. Cementitious Materials
1. Portland Cement: Conforming to ASTM C150, Type I orII. Type III may be used for cold-weather construction upon approval of the Engineer.
2. Hydrated Lime: Conforming to ASTM C207, Type S.
3. Mortar Cement: Conforming to ASTM C1329.
B. Sand for Mortar: Conforming to ASTM C144.
1. For jointslessthan 1/4 inch thick, use aggregate graded with 100 percent passing the No. 16 sieve.
C. Water-Repellent Admixture: Liquid water-repellent mortar admixture intended for use with concrete masonry units and formulated to minimize efflorescence while enhancing the bond between the mortar and masonry units.
1. Products: One of the following, or equal:
a. Addiment Incorporated; Mortar Tite.
b. Grace Construction Products; Dry-Block Mortar Admixture.
PASE – December 2024
270-30-23-22
04200 - 3
Concrete Masonry Units
City of Milpitas
WellUpgrades Program
McCandless Well Facility
c. Master Builders, Inc.; Color Cure Mortar Admix or Rheomix Rheopel.
D. Water: Use potable water.
2.03 GROUT MATERIALS
A. Cementitious Materials
1. Portland Cement: Conforming to ASTM C150, Type I orII. Type III may be used for cold-weather construction upon approval of the Engineer.
2. Hydrated Lime: Conforming to ASTM C207, Type S.
B. Fine and Coarse Aggregates: Conforming to ASTM C404.
C. Water: Use potable water.
2.04 MORTAR AND GROUT MIXES
A. Mortar for Unit Masonry: Comply with ASTM C270, Property Specification, Type S.
B. Grout for Unit Masonry: Proportion by volume in accordance with ASTM C476 to achieve a minimum compressive strength of 2,500 psi.
1. Use grout of type indicated or, if not otherwise indicated, of type (fine or coarse) that will comply with Table 1.15.1 in ACI 530.1/ASCE 6/TMS 602 for dimensions of grout spaces and pour height.
2. Provide grout with a slump of 8 to 11 inches as measured according to ASTM C143.
C. Epoxy Pointing Mortar: Mix epoxy pointing mortar to comply with mortar manufacturer's written instructions.
2.05 REINFORCEMENT
A. Uncoated Steel Reinforcing Bars: Conforming to ASTM A615, Grade 60.
B. Horizontal Joint Reinforcement
1. Cold drawn steel wire conforming to ASTM A82, hot dipped galvanized after fabrication in accordance with ASTM A153.
2. Acceptable Configurations:
a. Truss type with two or more longitudinal wires welded to a continuous diagonal cross wire.
b. Ladder type with perpendicular cross wires not more than 1 inch on center.
3. Dimensions:
a. Provide in 10-foot long flatsections.
b. Preformed Tees and Cornerreinforcement: Approximately 30 incheslong. c. Overall Width: Approximately 2 inches less than the nominal wall thickness.
PASE – December 2024
270-30-23-22
04200 - 4
Concrete Masonry Units
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2.06 MISCELLANEOUS MASONRY ACCESSORIES
A. Compressible Filler: Premolded filler strips complying with ASTM D1056, Grade 2A1; compressible up to 35 percent; formulated from neoprene.
B. Preformed Control-Joint Gaskets: Made from styrene-butadiene-rubber compound, complying with ASTM D2000, Designation M2AA-805 and designed to fit standard sash block and to maintain lateral stability in masonry wall.
C. Bond-Breaker Strips: Asphalt-saturated, organic roofing felt complying with ASTM D226, Type I (No. 15 asphalt felt).
2.07 MASONRY CLEANERS
A. Acidic Cleaner: Manufacturer's standard-strength cleaner designed for removing mortar/grout stains from new masonry without damaging masonry. Use product approved for intended use by cleaner manufacturer and manufacturer of masonry units being cleaned.
B. Manufacturers: One of the following or equal:
1. Diedrich Technologies, Inc.
2. EaCo Chem, Inc.
3. ProSoCo, Inc.
PART 3 - EXECUTION
3.01 INSTALLATION, GENERAL
A. Use full-size units without cutting if possible. If cutting is required, cut units with motordriven saws; provide clean, sharp, unchipped edges. Allow units to dry before laying unless wetting of unitsis specified. Install cut units with cut surfaces and, where possible, cut edges concealed.
B. Select and arrange units for exposed unit masonry to produce a uniform blend of colors and textures.
C. Comply with tolerances in ACI 530.1/ASCE 6/TMS 602 and with the following:
1. For conspicuous vertical lines, such as external corners, door jambs, reveals, and expansion and control joints, do not vary from plumb by more than 1/8 inch in 10 feet, 1/4 inch in 20 feet, or 1/2 inch maximum.
2. For conspicuous horizontal lines, such as lintels, sills, parapets, and reveals, do not vary from level by more than 1/8 inch in 10 feet, 1/4 inch in 20 feet, or 1/2 inch maximum.
3.02 LAYING MASONRY WALLS
A. Lay out walls in advance for accurate spacing of surface bond patterns with uniform joint thicknesses and for accurate location of openings, movement-type joints, returns, and offsets. Avoid using less-than-half-size units, particularly at corners, jambs, and, where possible, at other locations.
PASE – December 2024
270-30-23-22
04200 - 5
Concrete Masonry Units
City of Milpitas
WellUpgrades Program
McCandless Well Facility
B. Bond Pattern for Exposed Masonry: Unless otherwise indicated, lay exposed masonry in running bond; do not use units with less than nominal 4-inch horizontal face dimensions at corners or jambs.
C. Step back unfinished walls for joining with new walls, toothing will not be permitted.
D. Built-in Work: Build in door and window frames, fan and louver openings, pipe and conduit sleeves, and other items as the masonry construction progresses. Fill in solidly with masonry around built-in items.
E. Fill space between steel frames and masonry solidly with mortar, unless otherwise indicated.
F. Completely fill all cores in hollow concrete masonry units with grout.
3.03 MORTAR BEDDING AND JOINTING
A. Lay hollow concrete masonry units asfollows:
1. With face shellsfully bedded in mortar and with head joints of depth equal to bed joints.
2. With webs fully bedded in mortar in grouted masonry, including starting course on footings.
B. Lay solid masonry units with completely filled bed and head joints; butter ends with sufficient mortar to fill head joints and shove into place. Do not deeply furrow bed joints or slush head joints.
C. Tool exposed joints slightly concave when thumbprint hard, using a jointer larger than joint thickness, unless otherwise indicated.
D. Cut joints flush for masonry wallsto receive plaster or other direct-applied finishes (other than paint), unless otherwise indicated.
3.04 REINFORCED UNIT MASONRY INSTALLATION
A. Temporary Formwork and Shores: Construct formwork and shores as needed to support reinforced masonry elements during construction.
1. Construct formwork to provide shape, line, and dimensions of completed masonry as indicated. Make forms sufficiently tight to prevent leakage of mortar and grout. Brace, tie, and support forms to maintain position and shape during construction and curing of reinforced masonry.
2. Do not remove forms and shores until reinforced masonry members have hardened sufficiently to carry their own weight and other temporary loads that may be placed on them during construction.
B. Placing Reinforcement: Comply with ACI 530.1/ASCE 6/TMS 602.
C. Grouting
1. Grout Types:
a. Use fine grout in grout spaces that are lessthan 2 inchesin any horizontal dimension after deducting the thickness of horizontal reinforcement.
PASE – December 2024
270-30-23-22
04200 - 6
Concrete Masonry Units
City of Milpitas
WellUpgrades Program
McCandless Well Facility
b. Use fine grout in grout spaces where clearance between the reinforcing bars and the masonry is less than 3/4-inch.
c. Use coarse grout in all other locations.
2. Do not place grout until entire height of masonry to be grouted has attained enough strength to resist grout pressure.
3. Comply with requirements in ACI 530.1/ASCE 6/TMS 602 for cleanouts and for grout placement, including minimum grout space and maximum pour height.
4. Limit height of vertical grout pours to not more than 60 inches.
5. Place grout in a continuous pour and agitate to eliminate voids. If masonry units are dislodged or displaced by the grouting operation, remove masonry units and relay in alignment with fresh mortar.
3.05 TOLERANCES
A. Complete masonry work within the following tolerances:
1. Face of Concrete Masonry Unit: 1/16-inch from face of adjacent unit.
2. Variation from True Plane: 1/4-inch in 10 feet and 1/2-inch maximum in 20 feet or more.
3. Variation from Plumb: 1/4-inch in each story, noncumulative and 1/2-inch maximum in two stories or more.
4. Variation from Level: 1/8-inch in 3 feet, 1/4-inch in 10 feet, and 1/2-inch maximum.
5. Variation in Wall Thickness: plus or minus 1/4-inch.
3.06 FIELD QUALITY CONTROL
A. Special Inspection and Testing of masonry construction shall be performed by the City’s Testing Laboratory. The Contractor shall allow inspectors access to scaffolding and work areas as needed to perform inspections.
B. Place grout only after inspectors have verified compliance of grout spaces and grades, sizes, and locations of reinforcement.
C. Masonry Work to Receive Special Inspection: All masonry work shall receive Special Inspection in accordance with the requirements of California Building Code. Boltsinstalled in masonry require Special Inspection. Review Inspection protocol with City.
D. Three representative full-size sample masonry units showing full range of color, texture, finish, and dimensions are to be submitted for review.
E. Testing Frequency: One set of tests for each 5,000 sq. ft. of wall area or portion thereof.
F. Concrete Masonry Unit Test: For each type of unit provided, per ASTM C140.
G. Mortar Test (Property Specification): For each mix provided, per ASTM C780. Test mortar for mortar air content and compressive strength.
H. Grout Test (Compressive Strength): For each mix provided, per ASTM C1019.
PASE – December 2024
270-30-23-22
04200 - 7
Concrete Masonry Units
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3.07 CLEANING
A. In-Progress Cleaning: Clean unit masonry as work progresses by dry brushing to remove mortar fins and smears before tooling joints.
B. Final Cleaning: After mortar is thoroughly set and cured, clean exposed masonry as follows:
1. Test cleaning methods on sample wall panel; leave one-half of panel uncleaned for comparison purposes.
2. Protect adjacent surfaces from contact with cleaner.
3. Wet wallsurfaces with water before applying cleaners;remove cleaners promptly by rinsing surfaces thoroughly with clear water.
4. Clean masonry by bucket-and-brush hand-cleaning method described in BIA Technical Notes 20.
5. Clean masonry with a proprietary acidic cleaner applied according to manufacturer's written instructions.
END OF SECTION
PASE – December 2024
270-30-23-22
04200 - 8
Concrete Masonry Units
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
PASE – December 2024
270-30-23-22
05300 - 1
Metal Decking
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 05300
METAL DECKING
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Furnishing and installing preformed metal deck as shown on the Plans and as specified herein.
1.02 REFERENCED SECTION
A. The following Section is referenced in this Section
1. Section 01330 – Submittals
1.03 QUALITY ASSURANCE
A. All materials shall be new and free from defects impairing strength, durability and appearance, of best commercial quality for purpose intended.
B. Steel deck and accessories shall be products of a manufacturer regularly engaged in manufacture of steel decks.
1.04 SUBMITTALS
A. Submit the following in accordance with Section 01330
1. Shop drawings showing complete details of all fabricated items. a. Shop drawings shall show complete plan view layout of decking, location of openings, and extra members and other information necessary for the erection of the metal decking.
2. Manufacturer’sinstallation recommendations.
1.05 PRODUCT HANDLING, STORAGE AND DELIVERY
A. Deliver materials in manufacturer’s original unopened containers with labels intact and legible.
B. Store material in dry, clean and safe manner. Replace all damaged material with new material
PART 2 - PRODUCTS
2.01 METAL DECK
A. The steel roof deck units shall be fabricated from steel conforming to Section A3 of the American Iron and Steel Institute, Specifications for the Design of Cold-Formed Steel Structural Members.
B. Steel roof deck shall be galvanized, 1-5/16 inches depth with a minimum design thickness of 20 gage, and shall be designed in accordance with and comply with the standard load tables of the Roof Deck Specifications of the SDI.
C. Galvanized roof deck and accessories shall conform to the following:
PASE – December 2024
270-30-23-22
05300 - 2
Metal Decking
City of Milpitas
WellUpgrades Program
McCandless Well Facility
1. The steel roof deck shall be manufactured from steel conforming to ASTM A653 SS Grade 80. Minimum yield strength shall be 80 ksi.
2. Galvanizing shall conform to ASTM A924 with a minimum coating class of G60 as defined in A653.
3. Sheet steel for roof deck accessories shall be manufactured from galvanized steel conforming to ASTM A653 SS Grade 33 minimum.
D. The deck manufacturer shall furnish ridge and valley plates, flat plates at change of deck direction and sump pans, as shown on plans to provide a finished surface for the application of roof insulation and roof covering.
E. Acceptable products:
1. Vercor, Verco Mfg. Co., Phoenix, AZ. Tel: (602) 272-1347.
2. Or approved equal.
PART 3 - EXECUTION
3.01 MEASUREMENTS
A. Verify all dimensions given on the Plans and make such field measurements as are necessary to lay out the work properly.
3.02 INSTALLATION OF METAL DECKING
A. Install deck panels and accessories according to SDI Specifications, SDI Manual of Construction with Steel Deck, and in accordance with the placement plans, and requirements of this section.
B. The metal deck shall be installed at right angles to the supporting members unless shown otherwise, and shall be installed according to the manufacturer’s recommendations, the details shown, using the manufacturer’s standard fasteners for this type of material.
C. Minimum bearing of decking on supports shall be 2 inches.
D. Meal deck shall be cut and fitted around roof openings. Sheets shall extend over two spans, where shown. End laps shall be a minimum of 2 inches and shall be staggered.
Furnish and install all closure plates and accessories.
E. Steel deck shall be securely fastened to the steel supporting members with screws as shown on the Drawings. Sidelaps shall also be screwed as shown on the Drawings. Screws shall be TEK screws as manufactured by ITW Buildex, Itasca, IL. Screw size, length, and tip type shall be as shown on the Drawings. Install screws such that they tightly pull together all plies within the connection.
F. The installed roof deck panels shall be smooth, free from buckles and irregularities, and free of unnecessary openings, holes, or crevices.
G. Before placement of roof insulation and roof covering, the deck shall be inspected for tears, dents or other damage that may prevent the deck from acting as a structural roof base.
END OF SECTION
PASE – December 2024
270-30-23-22
05500 - 1
Miscellaneous Metal
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 05500
MISCELLANEOUS METAL
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Furnishing material, supplies, equipment, tools, transportation and facilities and performing labor and services necessary for, required in connection with or properly incidental to furnishing and installing miscellaneous metal, as described in this Section of the Specifications, shown on the accompanying Plans, or reasonably implied therefrom.
1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section
1. Section 01330 – Submittals
2. Section 09900 – Coating Systems
1.03 SUBMITTALS
A. Comply with Section 01330.
B. Certified test reports: Before delivery of any miscellaneous metalwork, provide certificates which attest to material compliance with these specifications.
C. Layout or installation shop drawingsfor allmiscellaneous metals, including but notlimited to, seat angles, brackets, flashing, pipe supports.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Wide Flange Beams: ASTM A992.
B. Structural Steel Shapes (other than Wide Flange Beams) and Plates: ASTM A36.
C. Structural Tubing (HSS): ASTM A500, Grade B.
D. Structural Pipe: ASTM A53, Grade B or ASTM A501.
E. Stainless Steel: ASTM A320, Type 316, as specified
F. Machine Bolts, Nuts, and Washers: ASTM A307.
G. High Strength Bolts: ASTM A325 bearing-type connections.
H. Hardened Steel Washers: ASTM F436.
I. Heavy Hex Nuts: ASTM A563.
J. Welded Headed Studs: ASTM A108.
K. Welding Materials: AWS D1.1 and D1.3; type required for materials being welded.
L. Cold-Formed Steel
1. Framing including stud and track sections, clips, light gauge angles and break shapes.
PASE – December 2024
270-30-23-22
05500 - 2
Miscellaneous Metal
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2. Material shall be supplied by a manufacturer who is a member of the Steel Stud Manufacturer’s Association (SSMA) and shall be ASTM A 653 Grade 33 for 18 GA and thinner material and ASTM A 653 Grade 50 for 16 GA and thicker material.
3. Wood Construction Connectors and Fasteners: Simpson Strong-Tie Company Inc. or approved equal.
4. Self-Drilling Sheet Metal Fasteners: Tek Screws by ITW Buildex or equal.
M. Steel Bar Grating: Steel bar grating shall be as manufactured by Grating Pacific, Inc. or approved equal. Bar depth, width and spacing shall be as shown on the Plans. All grating sections shall be banded. Steel bar grating shall be hot dip galvanized.
N. Metal Strut, Fasteners and Accessories: Cooper B-Line, Unistrut or equal.
2.02 FABRICATION
A. Fabricate structural steel members in accordance with AISC Specification.
B. Conform to Chapter 22, California Building Code; 2022 Edition (CBC).
C. Welding
1. Welder qualification requirements, welding procedures, etc. according to AWS D1.1 and D1.3. Employ only certified welders.
2. Butt welds: Full penetration welds unless otherwise noted.
3. Arc welding electrodes: E70 Series.
4. All welds on hand and guardrails are to be ground smooth.
5. Tie plates: Welded as shown on the Plans.
D. Holes for bolts or rivets shall be punched or drilled 1/16-inch larger than normal bolt.
Holes in column base plates may be 5/16-inch larger than anchor bolt diameter only if washers field welded to the base plate are provided under the nuts.
E. Zinc coating material: As specified in ASTM A153.
F. Zinc dust-zinc oxide coating: Conform to MILLSPEC DOD-P-20135.
G. Coating: As manufactured by Z.R.C. Chemical Products Co., Galvicon Co., or equal.
2.03 MISCELLANEOUS STEEL METALWORK
A. Other miscellaneous steel metalwork including embedded and non-embedded steel metalwork, hangers, and inserts shall be as specified on the Plans and shall be hot-dip galvanized after fabrication unless otherwise specified.
2.04 COATING REQUIREMENTS
A. Hot-dip galvanize fabricated material where specified on the Plans and in this Section of the Specifications.
B. Clean, prepare and shop prime other steel work in accordance with Section 09900.
C. Do not prime surfaces to be field welded.
D. Touch-up primer in the field after welding is complete. Apply finish coats in the field in accordance with Section 09900.
PASE – December 2024
270-30-23-22
05500 - 3
Miscellaneous Metal
City of Milpitas
WellUpgrades Program
McCandless Well Facility
E. Coatings in contact with potable water shall be NSF-61 approved for potable water applications.
PART 3 - EXECUTION
3.01 STEEL ERECTION
A. Erectstructuralsteel in accordance with AISC Specification.
B. Make provision for erection loads, and for sufficient temporary bracing to maintain structure safe, plumb and in true alignment until completion of erection and installation of permanent bracing.
C. Do not field cut or alter structural members without approval of Engineer.
D. After erection, prime welds, abrasions, and surfaces not shop primed, galvanized, except surfaces to be in contact with concrete. Use a primer consistent with shop coat. Use primer recommended for galvanized surfaces.
E. Bolting: Securely bolt or weld the work as erection progressesto provide for all dead load, lateral forces and erection stresses.
3.02 MISCELLANEOUS METALWORK
A. General
1. Fieldwork shall not be permitted on galvanized items. Drilling of bolts or enlargement of holes to correct misalignment will not be allowed.
2. Protect dissimilar metals from galvanic corrosion by means of pressure tapes, coatings or isolators. Protect aluminum in contact with concrete or grout with a heavy coat of bituminous paint.
3. Metalwork to be embedded in concrete:
a. Placed accurately and held in correct position while the concrete is placed or, if specified, recesses or blockouts shall be formed in the concrete. b. The surfaces of metalwork in contact with or embedded in concrete shall be thoroughly cleaned.
c. If accepted, recesses may be neatly cored in the concrete after it has attained its design strength and the metalwork grouted in place.
B. Seat Angles, Supports, and Guides
1. Setseat anglesfor grating and supportsfor floor platesso that they are flush with the floor and also maintain the grating and floor plates flush with the floor.
C. Fabrication
1. Holes shall be punched 1/6-inch larger than the nominal size of the bolts, unless otherwise specified. Whenever needed, because of the thickness of the metal, holes shall be subpunched and reamed or shall be drilled.
2. Fabrication including cutting, drilling, punching, threading and tapping required for miscellaneous metal or adjacent work shall be performed prior to hot-dip galvanizing.
PASE – December 2024
270-30-23-22
05500 - 4
Miscellaneous Metal
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3.03 FABRICATIONS REQUIREMENTS
A. Steel members, fabrications and assemblies: Galvanized after fabrication in accordance with ASTM A123.
B. Steel items weighing 100 pounds or less: Hot-dip zinc coated.
C. Anchor bolts and nuts 5/8 inch and larger: Hot-dip zinc coated in accordance with ASTM A153.
D. Anchor bolts and nutssmaller than 5/8-inch and all other bolts,screws, nuts, washers and other minor steel fasteners: Mechanically zinc coated.
E. Fabrication practices for products to be galvanized: In accordance with applicable portions of ASTM A143, A384 and A385.
3.04 REPAIR OF DEFECTIVE GALVANIZED COATING
A. Where zinc coating has been damaged after installation, substrate surface shall be first cleaned and then repaired with zinc dust-zinc oxide coating in accordance with ASTM A780. Application shall be as recommended by the zinc dust-zinc oxide coating manufacturer. Coating shall consist of multiple coats to dry film thickness of eight mils.
B. Remove items not physically damaged, but which have insufficient or deteriorating zinc coatings, and items damaged in shipment or prior to installation from the project site for repair by the hot-dip zinc coating method.
3.05 CLEANING
A. After installation, damaged surfaces of shop primed metals shall be cleaned and touched up with the same material used for the shop coat.
END OF SECTION
PASE – December 2024
270-30-23-22
05501 - 1
Anchor Bolts
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 05501
ANCHOR BOLTS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Anchor bolts complete with washers and nuts. Type 316 stainless steel, unless otherwise specified.
1.02 REFERENCED SECTIONS
A. The following Sections are referenced in this Section
1. Section 01330 – Submittals
2. Section 03301 – Cast-In-Place Concrete
3. Section 11002 – Equipment Mounting
1.03 SUBMITTALS
A. Comply with Section 01330 and include the following information:
1. Data indicating load capacities.
2. Chemical resistance.
3. Temperature limitations.
4. Installation instructions.
5. Evaluation Report for expansion type anchors asspecified in Paragraph 3.04.
6. Design calculationsin accordance with Paragraph 2.03.
7. Manufacturer’s data and catalog numbers.
PART 2 - PRODUCTS
2.01 GENERAL
A. Anchor bolt holes in equipment support frames shall not exceed the bolt diameters by more than 25 percent up to a limiting maximum oversizing of 1/8-inch. Minimum anchor bolt diameter shall be 1/2-inch. Anchor bolts for equipment mounting shall be provided as specified in Section 11002.
B. Tapered washersshall be provided where mating surface is not square with the nut.
C. Expansion or adhesive anchors set in holes drilled in the concrete after the concrete is placed will not be permitted in substitution for anchor bolts except where otherwise specified. Upset threads shall not be acceptable.
2.02 MATERIALS
A. Anchor bolt materials: as specified below unless otherwise specified.
B. All equipment anchor bolts and anchor bolts that are submerged or above the water surface shall be Type 316 stainless steel.
PASE – December 2024
270-30-23-22
05501 - 2
Anchor Bolts
City of Milpitas
WellUpgrades Program
McCandless Well Facility
Material Specification
Carbon steel bolts:
Structures ASTM A307, Grade A, hot-dip galvanized
Equipment ASTM A449, Type 1, hot-dip galvanized
Stainless steel bolts, nuts, washers ASTM A320 Type 316 Expansion anchors (concrete) Simpson Strong-Bolt 2, Hilti Kwik Bolt TZ2, or equal Expansion anchors (masonry) Simpson Strong-Bolt 2, Hilti Kwik Bolt TZ2, or equal Adhesive anchors (concrete) Simpson SET-3G, Hilti HIT-HY 200 V3, or equal Adhesive anchors (masonry) Simpson SET-3G, Hilti HIT-HY 270, or equal
2.03 DESIGN
A. Design anchor bolts for equipment frames and foundations in accordance with the CBC for Seismic Design Category D and Site Class E.
1. This force shall be considered acting at the center of gravity of the piece under consideration.
2. A basic wind speed of 100 miles per hour, Exposure Category C, shall be used if applicable.
B. Submit calculations and shop drawings with the equipment submittal in accordance with Paragraph 1.03 and Section 01330 for all anchorage details.
1. All calculations shall be prepared and signed by a civil or structural engineer currently registered in the State of California.
PART 3 - EXECUTION
3.01 GENERAL
A. Fieldwork, including cutting and threading, shall not be permitted on galvanized items.
B. Dissimilar metals shall be protected from galvanic corrosion by means of pressure tapes, coatings or isolators.
C. Allstainlesssteel anchor bolts and fastenersshall be assembled with a stainlesssteel antiseize compound such as molycote.
3.02 CAST-IN-PLACE ANCHOR BOLTS
A. Anchor bolts to be embedded in concrete and concrete unit masonry shall be placed accurately and held in correct position while the concrete or grout is placed or, if specified, recesses or blockouts shall be formed in the concrete and the metalwork shall be grouted in place in accordance with Section 03301.
B. The surfaces of metalwork in contact with concrete shall be thoroughly cleaned.
3.03 ADHESIVE ANCHOR BOLTS
A. Use shall be limited to locations where exposure, on an intermittent or continuous basis, to acid concentrations higher than ten percent, to chlorine gas, or to machine or diesel oils, is extremely unlikely.
PASE – December 2024
270-30-23-22
05501 - 3
Anchor Bolts
City of Milpitas
WellUpgrades Program
McCandless Well Facility
B. Use shall be limited to applications where exposure to fire or exposure to concrete or rod temperature above 120 degrees F is extremely unlikely. Overhead applications (such as pipe supports) because of the above concerns, shall be disallowed.
C. Approval from Engineer for specific application and from supplier of equipment to be anchored, if applicable.
D. Anchor diameter and grade of steel shall be per contract documents or per equipment supplier specifications. Anchor shall be threaded or deformed full length of embedment and shall be free of rust, scale, grease, and oils.
E. Embedment depth shall be as specified on the Drawings.
F. All installation recommendations by the anchor system manufacturer shall be followed carefully, including maximum hole diameter.
G. Holesshall have rough surfaces, such as can be achieved using a rotary percussion drill.
H. Holesshall be blown clean with compressed air and be free of dust orstanding water prior to installation.
I. Anchor shall be left undisturbed and unloaded for full adhesive curing period.
J. Concrete temperature (not air temperature) shall be compatible with curing requirements of adhesives per adhesive manufacturer. Anchors shall not be placed in concrete below 25ºF.
3.04 EXPANSION ANCHORS
A. Use of expansion type anchors shall be subject to Conditions B-C and F-H specified in Paragraph 3.03 and approval by the Engineer.
B. The Contractor shall supply the Engineer with the current evaluation report from the International Code Council – Evaluation Service for the particular brand of expansion anchors to be used.
END OF SECTION
PASE – December 2024
270-30-23-22
05501 - 4
Anchor Bolts
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
PASE – December 2024
270-30-23-22
05550 - 1
Prefabricated Metal Roof Trusses
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 05550
PREFABRICATED METAL ROOF TRUSSES
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Prefabricated metal roof trusses.
B. Cold-formed steel framing accessories.
1.02 REFERENCED SECTIONS
A. The following Section is referenced in this Section
1. Section 01330 – Submittals
1.03 DEFINITIONS
A. Truss Component Manufacturer: The maker of the components that will be assembled into trusses by the Truss Fabricator. See MANUFACTURERS for acceptable Truss Component Manufacturer.
B. Truss Fabricator: The manufacturer who assembles the Truss Component Manufacturer's components into completed trusses. See MANUFACTURERS for acceptable Truss Fabricators.
C. Truss Designer: The design professional, individual or organization, having responsibility for the design of the trusses. In this case, the Truss Designer is the Truss Component Manufacturer.
1.04 DESIGN, MANUFACTURE, AND INSTALLATION STANDARDS AND SPECIFICATIONS A. AISI S100-07/S2-10: North American Specification for the Design of Cold-Formed Steel Structural Members, with Supplement No. 2; American Iron and Steel Institute; 2007 Edition.
B. AISIS200-07: North American Standard for Cold-Formed Steel Framing - General Provisions; 2007 Edition.
C. AISI S214-07: North American Standard for Cold-Formed Steel Framing - Truss Design, with Supplement No. 2; 2007 Edition.
D. AISI S202-11: Code of Standard Practice for Cold-Formed Steel Structural Framing; 2011.
E. ASTM A 370-14 - Standard Test Methods and Definitions for Mechanical Testing of Steel Products; 2014.
F. ASTM A 500-13 - Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes; 2013.
G. ASTM A 653-13 - Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or ZincIron Alloy-Coated (Galvannealed) by the Hot-Dip Process; 2013.
H. LGSEA - Field Installation Guide for Cold-Formed Steel Roof Trusses; Light Gauge Steel Engineers Association; October 1999.
PASE – December 2024
270-30-23-22
05550 - 2
Prefabricated Metal Roof Trusses
City of Milpitas
WellUpgrades Program
McCandless Well Facility
I. LGSEA Technical Note 551d - Design Guide for Construction Bracing of Cold-Formed Steel Trusses; Light Gauge Steel Engineers Association; February 1997.
J. LGSEA Technical Note 551e - Design Guide for Permanent Bracing of Cold-Formed Steel Trusses; Light Gauge Steel Engineers Association; February 1998.
1.05 SUBMITTALS
A. Submittals shall be in accordance with Section 01330.
B. Product Data: Truss Component Manufacturer's descriptive literature for each item of cold-formed metal framing and each accessory specified in this section.
C. Shop Drawings: Detailed drawings prepared by the Truss Designer and stamped and signed by a Professional Civil Engineer registered in the State of California that:
1. Indicate special components and installations not fully detailed in product data.
2. Indicate in the layout placement drawings the number, types, location, and spacing of trusses and other framing members.
3. Indicate details of truss loading, reactions, uplifts, support locations, material sizes and gauges, permanent truss web bracing, and splices as required for a complete installation.
D. Design Calculations
1. Results of the design analysis by the Truss Designer.
2. Calculations for all truss members and connections shall be performed given the loads stated in this specification section and on the Drawings.
3. Calculations shall show all resulting stresses and deflections and compare them with the corresponding allowable stresses and deflection limits.
4. Design calculations shall be stamped and signed by a Professional Civil Engineer registered in the State of California.
E. Installation Instructions: Truss Component Manufacturer's printed instructions for handling, storage, and installation of each item of cold-formed metal framing and each accessory specified in this section.
1.06 QUALITY ASSURANCE
A. Pre-Installation Meeting: Meet at the job site prior to the scheduled beginning of installation to review requirements:
1. Attendees: Require attendance by representatives of the following:
a. Truss Fabricator, if requested by installer.
b. Installer of this section.
c. Other entities directly affecting, or affected by, construction activities of this section, including but not limited to, the following:
1) Installer of trusssupport framing.
2) Installer of corrugated metal deck.
3) Installer of mechanical, electrical, and plumbing systems.
PASE – December 2024
270-30-23-22
05550 - 3
Prefabricated Metal Roof Trusses
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2. Review potential interface conflicts; coordinate layout and support provisions.
1.07 DELIVERY, STORAGE, AND HANDLING
A. Pack, ship, handle, unload, and lift shop products in accordance with Truss Component Manufacturer's recommendations and in manner necessary to prevent damage or distortion.
B. Store and protect products in accordance with Truss Component Manufacturer's recommendations and in manner necessary to prevent damage, distortion and moisture buildup.
PART 2 - PRODUCTS
2.01 MANUFACTURERS
A. Acceptable Truss Component Manufacturer: Alpine TrusSteel Products from ITW Company, Inc., 6750 Forum Drive, Suite 305, Orlando, FL 32821. Tel: (888) 565-9181. www.trussteel.com.
B. Acceptable Truss Fabricators: Truss components shall be fabricated into completed trusses by one of the following fabricators:
1. Steel Truss & Supply, 22533 Bridlewood Lane, Palo Cedro, CA 96073. Tel: (530) 365-3700. www.steeltrusssupply.com.
2. Gecko Steel Truss, LLC, 699 West 17th Street, Yuma, AZ 85364. Tel: (928) 726- 8748. www.geckosteeltruss.net.
C. Requestsfor substitutions will be considered in accordance with the following:
1. Allsubstitutions must be approved in writing by the Engineer-of-Record.
2. All applications for substitution must include samples and technical data.
2.02 COMPONENTS
A. Prefabricated Cold-Formed Steel Trusses: Alpine TrusSteel truss component system by ITW Company, Inc. providing a complete horizontal framing system, ready for deck installation, meeting specified requirements.
1. Truss type, spacing, span, and height: As indicated on the Drawings.
2. Comply with requirements of Paragraph 1.04 and the 2022 California Building Code.
3. Design loads: As indicated on the Drawings.
4. Deflection under live loads: 1/360th of span, maximum.
5. Deflection under total load: 1/240th of span, maximum.
6. Shop fabricate in accordance with shop drawings, using jigging systemsto ensure consistent component placement and alignment of components, and to maintain specified tolerances. Field fabrication is strictly prohibited unless performed by authorized Truss Fabricator using Truss Fabricator's shop assemblers and proper jigging systems.
PASE – December 2024
270-30-23-22
05550 - 4
Prefabricated Metal Roof Trusses
City of Milpitas
WellUpgrades Program
McCandless Well Facility
7. Shop fabrication of other cold-formed steel framing components into assemblies prior to erection is permitted. Fabricate assemblies in accordance with shop drawings.
8. Fasten connections within truss assembly with Truss Component Manufacturer's screws only and asshown on the shop drawings. Welding and other fasteners are prohibited.
9. Fabricate straight, level, and true, without rack, and to the following tolerances:
a. Trusses up to 30 feet long: Maximum 1/2 inch variation from design length.
b. Trusses over 30 feet long: Maximum 3/4 inch variation from design length.
c. Trusses up to 5 feet high: Maximum 1/4 inch variation from design height. d. Trusses over 5 feet high: Maximum 1/2 inch variation from design height.
B. Truss Chord and Web Components: Alpine TrusSteel components, with rolled or closed edges to minimize the danger of cutting during handling; chord and web components without rolled edges are prohibited.
1. Shapes, Sizes, and Thicknesses: As required to suit design and as indicated on shop drawings.
2. Chords: Cold-formed from ASTM A 653/A 653M galvanized steel sheet, minimum G60 coating; minimum yield strength of 55,000 psi for 22, 20, 18 and 16 GA components or 50,000 psi for 14 GA and 12 GA components. Top chord shall be 16 GA minimum.
a. Nominal 28 mil (22 GA) members:
1) Minimum bare metal thickness: 0.0284 inch.
2) Maximum design thickness: 0.0299 inch.
b. Nominal 33 mil (20 GA) members:
1) Minimum bare metal thickness: 0.0329 inch.
2) Maximum design thickness: 0.0346 inch.
c. Nominal 43 mil (18 GA) members:
1) Minimum bare metal thickness: 0.0428 inch.
2) Maximum design thickness: 0.0451 inch.
d. Nominal 54 mil (16 GA) members:
1) Minimum bare metal thickness: 0.0538 inch.
2) Maximum design thickness: 0.0566 inch.
e. Nominal 68 mil (14 GA) members:
1) Minimum bare metal thickness: 0.0677 inch.
2) Maximum design thickness: 0.0713 inch.
f. Nominal 97 mil (12 GA) members:
1) Minimum bare metal thickness: 0.0966 inch.
2) Maximum design thickness: 0.1017 inch.
PASE – December 2024
270-30-23-22
05550 - 5
Prefabricated Metal Roof Trusses
City of Milpitas
WellUpgrades Program
McCandless Well Facility
3. Webs: Cold-formed ASTM A500 steel structural tubing; minimum yield strength of 45,000 psi.
a. Nominal 33 mil (20 GA) members:
1) Minimum bare metal thickness: 0.033 inch.
2) Maximum design thickness: 0.035 inch.
b. Nominal 47 mil (18 GA) members:
1) Minimum bare metal thickness: 0.047 inch.
2) Maximum design thickness: 0.049 inch.
c. Nominal 63 mil (16 GA) members:
1) Minimum bare metal thickness: 0.063 inch.
2) Maximum design thickness: 0.065 inch.
C. Fasteners Used in Fabricating Trusses: Fasteners as recommended by Truss Component Manufacturer, bearing stamp of Truss Component Manufacturer for ready identification.
PART 3 - EXECUTION
3.01 EXAMINATION
A. Verify that all utilitiesthat will penetrate the plane of the trusses are accounted for in the design of the trusses and will not conflict with truss, bracing, or bridging members.
B. Verify that bearing surfaces and substrates are ready to receive steel trusses.
C. Verify that truss bearing surfaces are within the following tolerances:
1. Variation from Level or Specified Plane: Maximum 1/8 inch in 10 feet.
2. Variation from Specified Position: Maximum 1/4 inch.
D. Inspect conditions under which installation is to be performed and submit written notification if such conditions are unacceptable to installer.
1. Notify Engineer-of-Record within 24 hours of inspection.
2. Beginning construction activities of this section before shop drawings have been approved or unacceptable conditions have been corrected is prohibited.
3. Beginning construction activities of thissection indicates installer's acceptance of conditions.
3.02 INSTALLATION
A. Install trussesin accordance with Truss Component Manufacturer'sinstructions and Truss Fabricator's shop drawings. Use correct fasteners as previously described.
B. Place components at spacings indicated on the shop drawings.
C. Install all erection (temporary installation) bracing and permanent bracing and bridging before application of any loads; follow recommendations of LGSEA Field Installation Guide for Cold-Formed Steel Roof Trusses.
McCandless Well Facility
D. Install erection bracing - follow recommendations of LGSEA Field Installation Guide for Cold-Formed Steel Roof Trusses.
1. Provide bracing that holds trusses straight and plumb and in safe condition until decking and permanent truss bracing has been fastened to form a structurally sound framing system.
2. All sub-contractors shall employ proper construction procedures to insure adequate distribution of temporary construction loads so that the carrying capacity of any single truss or group of trusses is not exceeded.
E. Install permanent bracing and bridging as shown in the Engineer-of-Record's drawings and notes and as shown in the Truss Fabricator's shop drawings.
F. Removal, cutting, or alteration of any truss chord, web or bracing member in the field is prohibited, unless approved in advance in writing by the Engineer-of-Record and the Truss Designer.
G. Repair or replace damaged chords, webs, and complete trusses as directed and approved in writing in advance by the Engineer-of-Record and the Truss Component Manufacturer.
END OF SECTION
PASE – December 2024 05550 - 6 City of Milpitas
270-30-23-22 Prefabricated Metal Roof Trusses Well Upgrades Program
PASE – December 2024
270−30−23−22
06200− 1
Finish Carpentry
City of Milpitas
Well Upgrades Program
McCandless Well Facility
SECTION 06200
FINISH CARPENTRY
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Furnishing all material, supplies, equipment, tools, transportation and facilities and performing all labor and services necessary for, required in connection with or properly incidental to furnishing and installing finish carpentry, as described in this section of the specifications, shown on the accompanying drawings, or reasonably implied therefrom.
B. Work Included
1. Furnishing and installing miscellaneous wood trim.
1.02 REFERENCED SECTION
A. The following Section is included in this Section
1. Section 09900 – Coating Systems
1.03 QUALITY ASSURANCE
A. Codes and Standards
1. Comply with all Federal, State and Local Codes and Safety Regulations. In addition, comply with the provisions of the following codes, specifications, and standards, except where more stringent requirements are shown or specified:
a. California Building Code, 2022 Edition (CBC).
b. National Forest Products Association, “National Design Specification for Wood Construction”, 2015 Edition.
c. American Plywood Association, “U.S. Product Standard PS 1”. d. All plywood shall be identified as to species, grade, and glue type and shall bear the identification grade mark of the American Plywood Association.
1.04 DELIVERY STORAGE AND HANDLING
A. Deliver and store lumber on sleepers and cover for protection. See general conditions for additional delivery and storage requirements.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Quality Standard: Comply with WIC “Manual of Millwork”, Section 6.
B. Lumber Species: B & Better Grade Cedar, smooth finish for paint finish as specified in Section 09900.
C. Wood Moisture Content: Comply with requirements of referenced quality standard for moisture content of lumber in relation to relative humidity conditions existing during time of fabrication and in installation areas.
McCandless Well Facility
D. Cedar plywood shall conform to U.S. Product Standard PS 1−09, American Plywood Association. Each sheet shall be stamped with the PS and/or APA grade mark. Cedar plywood shall be five−ply exterior type, Group Identification Index 32/16, Species Group 2 or better.
E. Nails: hot−dip galvanized or stainless steel.
PART 3 - EXECUTION
3.01 GENERAL REQUIREMENTS
A. Center joints of plywood accurately over supports and nail into solid wood. Protect all plywood from moisture by use of all required waterproof covering until the plywood has in turn been covered by the next succeeding component or finish.
B. Remove lumber not grade stamped, and lumber of improper grade, from the job site, and immediately replace with grade stamped lumber of the proper grade.
C. All other lumber materials, not specifically described but required for the proper completion of the work, shall be new, first quality of their respective kinds and subject to the approval of the Engineer.
D. All carpentry shall produce joints true, tight, and well nailed with all members assembled in accordance with the Drawings and with all pertinent regulations. Fabricate woodwork to dimensions, profiles, and details indicated. Ease edges in accordance with WIC standards.
END OF SECTION
PASE – December 2024 06200− 2 City of Milpitas
270−30−23−22 Finish Carpentry Well Upgrades Program
PASE – December 2024
270-30-23-22
07210 - 1
Thermal Insulation
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 07210
THERMAL INSULATION
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Thermal building insulation.
1.02 REFERENCED SECTION
A. The following Section is referenced in this Section
1. Section 01330 – Submittals
1.03 SUBMITTALS
A. Comply with Section 01330.
B. Provide manufacturer’s complete product data sheets.
PART 2 - PRODUCTS
2.01 THERMAL BUILDING INSULATION
A. Thermal building insulation shall be flame-resistant, formaldehyde-free thermal and acoustical fiber glass batt insulation as manufactured by Johns Manville, Owens Corning, or approved equal.
B. Thermal resistance “R” value of the insulation shall be R19.
C. The insulation shall be faced and shall have an FHC (Fire Hazard Classification) rating of 25/50 or less.
D. Insulation stops shall be fabricated from galvanized sheet metal.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Thermal Building Insulation
1. Install thermal building insulation in accordance with the manufacturer’s recommendations.
2. Insulation shall be installed with the facing toward the interior of the building.
3. Insulation shall be installed snugly against adjacent pieces and against all obstructions.
4. Cutting and fitting shall be performed as required to leave no voids.
5. Install insulation stops at locationsshown on the Drawings.
END OF SECTION
PASE – December 2024
270-30-23-22
07210 - 2
Thermal Insulation
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
PASE – December 2024
270-30-23-22
07260 - 1
Vapor Retarders
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 07260
VAPOR RETARDERS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Vapor barrier.
1.02 REFERENCED SECTION
A. The following Section is referenced in this Section
1. Section 01330 – Submittals
1.03 SUBMITTALS
A. Comply with Section 01330.
B. Provide manufacturer’s complete product data sheets.
PART 2 - PRODUCTS
2.01 VAPOR BARRIER
A. Multilayer plastic membrane for moisture proofing underlay shall be polyethylene film with a thickness of 15 mils.
B. Pressure sensitive tape shall be 2-inch wide polyethylene tape.
C. Manufacturers: One of the following or equal:
1. StegoWrap, Stego Industries.
2. Premoulded Membrane Vapor Seal with Plasmatic Corel, W. R. Meadows.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Vapor Barrier
1. Unless otherwise specified, moisture proofing underlay shall be provided under concrete floors or floating slabs-on-grade including those deposited on drain rock. a. Backfilled surfaces to receive moisture proofing underlay shall be leveled off and smoothed over to minimize contact with sharp edges.
2. At joints, moisture proofing member shall be lapped 6 inches and sealed with pressure sensitive tape.
a. Where pipes and conduits pass through the membrane, they shall be wrapped tightly with separate sheets of membrane which shall then be sealed with tape to the main membrane.
b. Support reinforcing steel or wire mesh by chairs with flat bases to protect the membrane.
END OF SECTION
PASE – December 2024
270-30-23-22
07260 - 2
Vapor Retarders
City of Milpitas
WellUpgrades Program
McCandless Well Facility
(THIS PAGE LEFT BLANK INTENTIONALLY)
PASE – December 2024
270-30-23-22
07411 - 1
Metal Roofing Panels
City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 07411
METAL ROOFING PANELS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Engineered metal roof: prefinished standing seam metal roofing, flashing and soffits.
B. Clips, angles, corners, fasteners, anchors, purlins, beams, and all necessary accessories for a complete watertight system.
C. Installation.
1.02 REFERENCED SECTION
A. The following Section is referenced in this Section
1. Section 01330 – Submittals
1.03 SUBMITTALS
A. Submit for approval in accordance with Section 01330.
B. Manufacturer’s Data
1. Panel sheet steel
2. Sheet steel corners, angles, and closure strips
3. Sheet steel coatings
4. Fastener clips, screws, and pop rivets
5. Sealant
6. Installation instructions
7. UL 580 conformance
8. Colorsto be selected by the City after submittal.
C. Shop Drawings: Produced by the roofing manufacturer based on the Drawings clearly showing the design, dimensions, materials, methods of construction, details and installation of each piece to be installed.
D. Samples: Submit a 2″ x 3″ sample of metal roof and soffit.
E. Warranty
1. Submit manufacturer’s warranty for 20 years covering paint finish, chipping, and fading.
2. After completion submit a warranty stating that the roofing system and metal flashings will properly shed water and protect the building from rain damage for a period of two years.
PASE – December 2024
270-30-23-22
07411 - 2
Metal Roofing Panels
City of Milpitas
WellUpgrades Program
McCandless Well Facility
PART 2 - PRODUCTS
2.01 ACCEPTABLE MANUFACTURERS
A. Structuralsheetsteelshall be manufactured by AEP Span, 10905 Beech Avenue, Fontana, CA; or approved equal.
2.02 SHEET METAL ROOF AND SOFFIT
A. Sheet metal roof shall be Design Span hp Metal Roofing by AEP Span or approved equal.
Panels shall be 16” wide with added wide batten cap.
B. Panelsshall be 22 gauge zinc-aluminum coated steel and conform to ASTM A792.
C. Panels shall be shop pre-coated with DuraTech 5000 coating of selected color, with factory installed sealant.
D. City to select color from manufacturer’s list of at least 22 standard colors.
E. Install panels per manufacturer’s recommendations.
F. Roof system shall conform to UL580 for uplift class 90.
G. Sheet Metal Soffit
1. Sheet metalsoffit shall be Flush Panel Metal Wall Panels by AEP Span or approved equal. Panels shall be 12” wide.
2. Panelsshall be 22 gauge zinc-aluminum coated steel and conform to ASTM A792.
3. Panels shall be vented to provide 7.8% open area (11.3 in2/ft2 panel).
4. Panels shall be shop pre-coated with DuraTech 5000 coating of selected color.
5. City to select color from manufacturer’s list of at least 22 standard colors.
6. Install panels per manufacturer’s recommendations.
2.03 FASTENERS
A. Clips shall be by the same manufacturer as the panels. Screws for attachment of clips to metal decking shall be zinc plated, Phillips drive screws with pancake head, size as recommended by roofing manufacturer (minimum #10 x 1″ long).
B. Screws for connection of components of the roofing system shall be 316 stainless steel, type S-12, self-drilling, self-tapping screws.
C. Install fasteners per installer’s location schedule.
2.04 ACCESSORY MATERIAL
A. Cleats, corners, angles, closure, and starter strips shall be of same material as sheet furnished by the panel manufacturer.
2.05 FLASHING
A. Panel penetration flashing: As recommended by Panel Manufacturer to satisfy conditions of use.
B. Other Flashing: Material and finish to match panels. Lead or copper will not be allowed.
PASE – December 2024
270-30-23-22
07411 - 3
Metal Roofing Panels
City of Milpitas
WellUpgrades Program
McCandless Well Facility
2.06 SEALANTS
A. Gunnable Grade Caulking: Single component polyurethane caulk.
B. Tape Sealant: Butyl.
PART 3 - EXECUTION
3.01 STORAGE AND HANDLING
A. Store metal roofing out of weather in a clean and dry location.
B. Stack preformed and prefinished material to prevent twisting, bending, or abrasion, and to provide ventilation.
C. Prevent contact with materials and metals during storage which may cause discoloration or staining.
3.02 SHOP DRAWINGS
A. Take field measurements for the preparation of shop drawings.
B. Install panels full length and width with no horizontal joints.
C. Submit and obtain approval of shop drawings before panel fabrication.
3.03 INSTALLATION
A. Executemetal work in accordance with the Sheet Metal and Air Conditioning Contractor’s National Association (SMACNA) standards and manufacturer’sinstructions.
B. Lap, lock, cleat,seam, and seal all joints. Use rubber asphalt bedding compound for joints between metal and bitumen or metal and felts.
C. Installstarter and edge strips, and cleats before starting installation of roofing sheets.
D. Do not install panels or trim in contact with dissimilar materials.
E. Do not allow foot traffic on the completed roof.
3.04 FASTENERS AND SEALANTS
A. Install panel fastener clips on 18″ centers and within 6″ from the ends. Install other fasteners as recommended by the panel manufacturer.
B. Install flashing and panels to avoid all contact between dissimilar metals. Install sealant as shown on the Drawings and as recommended by the panel manufacturer.
3.05 CLEAN-UP AND CLOSE-OUT
A. Touch-up damaged paint surfaces with an air dry touch-up paint provided by the manufacturer. Small brush application only.
B. Cleaning and Repairing
1. At the completion of each day’s work and at completion of work, sweep panels, flashing, downspouts, and gutters clean.
2. Do not allow fasteners, cuttings, fillings, or scraps to accumulate.
3. Remove all debris from project.
END OF SECTION
PASE – December 2024
270-30-23-22
- 1 City of Milpitas
WellUpgrades Program
McCandless Well Facility
SECTION 07600
FLASHING AND SHEET METAL
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Installation of sheet metal flashing and gutters.
B. General Notes on the Drawings are part of these Specifications.
1.02 REFERENCED SECTION
A. The following Section is referenced in this Section
1. Section 07900 – Sealants and Caulking
1.03 STORAGE AND HANDLING
A. Store galvanized metal under dry conditions in such a manner as to prevent twisting, bending, or abrasion, and to provide ventilation.
PART 2 - PRODUCTS
2.01 SHEET MATERIALS
A. Flashing: Zinc-aluminum coated steel; 24 gauge core steel, with AZ-50 coating per ASTM A924/A792.
B. Gutters: 20 gauge zinc-aluminum coated steel conforming to ASTM A924/A792. Gutters shall be shop pre-coated with Kynar 500 coating of selected color. Color and style to be selected by the City from manufacturer’s list of standard colors and styles.
2.02 ACCESSORIES
A. Fasteners: Same material and finish as flashing metal.
B. Sealant: Butyl type, specified in Section 07900.
C. Reglets: Surface mounted zinc-aluminum coated steel.
D. Cleats and Stiffeners: As required to make allsectionsrigid.
2.03 FABRICATION
A. Form components true to shape, accurate in size, square, and free from distortion or defects. Form pieces in longest practical lengths.
B. Hem exposed edges on underside 1/2"; miter and seam corners. Fabricate vertical faces with bottom edge formed outward 1/4" and hemmed to form drip.
PART 3 - EXECUTION
3.01 EXAMINATION AND PREPARATION
A. Verify roof openings, curbs, or vents through roof are solidly set, reglets in place, and nailing strips located.