of 60 Ldn or CNEL dBA and 45 dB CNEL, respectfully, for residential land uses.

The City codified this General Plan policy by requiring that the 60 Ldn or CNEL dB exterior noise level be met at the, property line, apparently assuming that the backyard outdoor activity area would share a common property line with the noise source (i.e. an arterial street).

The General Plan promotes the elimination of the use of sound walls and encourages the use of alternative noise mitigation measures such as berms, increased setbacks and other methods where feasible to promote more aesthetically attractive streetscapes and reduce the negative visual and access impacts of sound walls.

Therefore, the design of the Land Use Plan has shielded many of the rear yard outdoor activity areas behind the dwelling units and oriented the front of dwelling units onto frontage streets and parkways, which lie between the home and the arterial street noise source. . The acoustic engineer Brown – Buntin Associates, Inc. provided the following minimum distances from the center of the street rightof-way of each of the arterial streets surrounding the Central Area to a point where the 60 CNEL dB sound level would prevail if no intervening dwelling unit or sound wall is provided. . All noise attenuation mitigation (including any those specified in this section) must be in accordance the mitigations and requirements provided Central Area Specific Plan EIR and MMRP.

Location of Street
Center Line
of Street to
60 dB Level
Half Street
Right-of-Way
Distance from
Line to the Rightof-Way 60 dB
Level Without
Intervening
Sound Wall or
Dwelling Unit
Mitigation Required
Between Right-ofWay and Backyard
or as Required by
the CASP EIR
Natividad Rd - E. Boronda to
southerly greenway street 286’ 73’ 213’
8-foot high
sound wall or an
intervening home
with a 20-foot front
yard setback facing
onto a 50 to 54-foot
wide frontage
road parkway and
sidewalk adjacent to
Natividad Road
Natividad Rd - southerly
greenway to northerly greenway
streets
248’ 73’ 175’
Natividad Rd. northerly greenway
street to Russell Rd 217’ 73’ 144’
Russell Rd - Natividad Rd. to
Independence Blvd. 63’ 73’ 5’ None Required
Russell Rd - Independence Blvd. to
Hemingway Dr. 63’ 59’ 4’ None required
Russell Rd - Hemingway Dr. to Old
Stage Rd. 63’ 59’ 4’ None required
Old Stage Rd - Russell Rd. to
Constitution Blvd. (Note 1) 134’ 155’ 0’’ None Required Constitution Blvd - Old Stage Rd.
to northerly greenway street 49’ 63’ 0’’ None Required
Constitution Blvd - northerly
greenway street to southerly
greenway street
68’ 63’ 5’ None Required
Constitution Blvd - southerly
greenway street to
E. Boronda Road
94’ 63’ 31’ Open Space both
sides None required
78 City of Salinas | Final Central Area Specific Plan, November 2020 E. Boronda Rd –
Constitution to Hemingway 316’ 83’ 233’ 8-foot high
sound wall or an
intervening home
with a 20-foot front
yard setback facing
onto a 50 to 54-foot
wide frontage
road parkway and
sidewalk adjacent to
Natividad Road
E. Boronda Rd - Hemingway
to Independence 345’ 83’ 262’
E. Boronda Rd –
Independence to Natividad 373’ 83’ 290’
Note: The half street section is measured from center line of Old Stage Rd. to the south side of the PG&E tower line easement, plus the 50 to 54-foot wide frontage road.

Note: Even with a sound wall or intervening home, triple pane windows and mechanical ventilation or air conditioning must be provided for all residences placed within the above, “Distance from Centerline to 60 dB Level” - The interior noise level must not exceed 45 dBA CNEL. All sound attenuation must comply with the CASP EIR and MMRP. (19) In the two VC districts, an upper story arcade, balcony, bay window, eave, awning or similar architectural features may project up to 11-feet over the 15-foot wide public sidewalk and up to 14 feet over an 18 foot wide sidewalk, provided a minimum ten-foot wide clear walkway is maintained between the building and any column or post supporting the overhang and provided a ten-foot clear height is maintained or as provided in the CASP EIR.
(20) See Section 4.7(g) and Salinas Zoning Code Section 37-50.040: Building Projections into Yards for other allowable encroachments. (21) A Master Sign Program shall be required for all signage located in multifamily residential, Mixed Use, Flex Use, and non-residential developments in the Specific Plan and for any Subdivision entry signs. Timing of submittal shall be in accordance with Salinas Zoning Code Article V, Division 3: Signs.
(22) The Lot Size and Lot Area Per Unit shall be subject to the approval of the City Planner at the time of the Tentative or Vesting Subdivision Map creating the applicable lots. All lots shall meet the minimum and maximum density requirements of the Specific Plan described in Sectiond 3.7 through 3.11.
(23) To determine the allowable units per net acre on each block in each Zoning District refer to Sections 3.7 through 3.11 and Appendix G of this Specific Plan.
(24) Structures within the VC districts shall not intercept a 45 inclined plan inward starting from a height of twenty feet (20) above the existing grade at a non VC district rear or side property line.

Use Classifications and Development Regulations
79 Table 3-3: Usable Open Space Standards
Lot Area Dwelling Type Minimum Usable Open
Space Requirement Usable Open Space
Note (2) Descriptor Stories If Garage Faces: Descriptor Required SF Note (1) and (3) Alley Street Note (1) and (3)
1,000 to
1,799 SF MX & MF One or more
100 NA MX/MU 100
Notes (2), (5), (6), and (7)
1,800 to
2,099 SF MX & MF One or more
300 500 R-H-1.8 500
Notes (2), (4), (6) and (7)
2,100 to
2,899 SF SFD, SFA & MF One or more
300 500 R-H-2.1 500
Notes (2), (4), (6) and (7)
2,900 to
3,599 SF
SFD One 350 500 R-M-2.9 500
SFD Two or more 350 500
3,600 to
4,499 SF
SFD One 350 800 R-M-3.6 800
SFD Two or more 550 800
4,500 to
5,399 SF
SFD One 600 800 R-M-3.6 800
SFD Two or more 800 800
5,400 to
6,599 SF
SFD One 800 1,000 R-L 5,500 1,000
SFD Two or more 1,000 1,000
6,600 SF
or more
SFD One 1,000 1,000 R-L 5,500 1,000
SFD Two or more 1,000 1,000 R-L 5,500 1,000
Additional Usable Open Space Regulations
(1) SFD – Single-Family Detached
SFA – Single-Family Attached and Duplex Dwellings
MF – Multifamily and Courtyard Apartments
MX – Mixed Use and Flex Use
Note: Carriage Apartments and other Accessory Dwelling Units are exempt from the Open Space Regulations. (2) All dwelling units on a similar-size lot shall have the same Usable Open Space standards, whether rentals or ownership units. (3) Descriptors used in this Specific Plan and the City Zoning Code may vary. (4) Multifamily, Flex Use and Mixed Use projects located in the NG-B and NG-C, VC-A and VC-B districts with densities between 1 unit per 1,800 square feet and 1 unit per 2,899 square feet of lot area shall provide 300 square feet of usable open space per studio, one bedroom and two bedroom unit, and 400 square feet of usable open space per three or more bedroom unit provided each unit has a balcony or terrace of at least sixty square feet in size at least 6 feet deep directly accessible to the dwelling unit. The standard for multifamily projects in other districts shall be 400 square feet per unit.
(5) The minimum usable open space requirement for the MX and MF uses in the two VC districts for units with a densities between 1 unit per 1,000 square feet and 1 unit per 1,799 is 100 square feet per dwelling unit for studio, one bedroom and two bedroom dwelling units, plus 300 square feet per dwelling unit for three or more bedroom unit, provided each unit is provided with a balcony or terrace of at least sixty square feet in size at least 6 feet deep directly accessible to the dwelling unit. (6) No more than 30% of the total number of dwelling units in a development may have more than two bedrooms to receive the reduced open space incentives otherwise a minimum of 400 square feet of usable open space shall be required per unit. 80 City of Salinas | Final Central Area Specific Plan, November 2020

3.6 Development Submittals

3.6.1 Subdivision of Land – Development Regulations,
Design Standard and Density Conformance
All the lands within the Plan Area shall be subdivided as shown in Appendix G. All street locations, street widths, block widths and depths and location of all Zoning Districts should be carefully located and sized to match the Planning Subareas Map included in Appendix G.

All subdivisions establishing blocks and individual lots shall meet the requirements of the Specific Plan.

Block width and length may vary provided the center line of the street surrounding any block shall not exceed 2,000 linear feet and that the minimum and maximum density of said block shall be the same as the same area overlaid onto the Appendix G, Planning Subarea Map and the required variation in lot size per block are achieved. Computer Aided Design (CAD) files of the Appendix G land use map are on file with the Salinas Community Development Department.

3.6.2 Further Subdivision
Once a block is subdivided, in order to maintain the required densities, percentages, and variety of lot sizes within the Specific Plan, no further subdivision of lots within that block shall be allowed without a Specific Plan Amendment in accordance with Section 9.7.2 of the Specific Plan and any required CEQA evaluation.

3.7 Densities, Mix of Lots Sizes and Related
Requirements

3.7.1 Minimum and Maximum Average Density
The number of dwelling units within an individual lot (parcel) on a block shown on a Tentative Subdivision Map divided by that parcels net acreage may be less than or more than that Zoning District’s allowable minimum or maximum average dwelling units per net residential acre, provided the total number of dwelling units within all of the Zoning Districts within said block, shown on a Tentative Subdivision Map shall fall within the minimum and maximum allowable units for those Zoning Districts as required in this Chapter and Appendix G. Interpretations by the City Planner determining application compliance with the General Plan, this Specific Plan and the Zoning Code are included in the Interpretation Guide in Appendix T.

Use Classifications and Development Regulations
81 3.7.2 Number of Units
Each application for a Tentative Subdivision Map shall include a summary list of the proposed number of lots, proposed number of dwelling units and dwelling unit types, underlying zoning, and proposed density (see Appendix G). This list shall be included as a table on the map or as otherwise required by the City Planner and City Engineer.

3.7.3 Mix of Lot Sizes
In order to provide varied massing on each block and provide a wider range of dwelling unit sizes and price points, each zoning district on each block in the NE-A, NE-B, NG-A and NG-B districts shall contain a mix of lot widths and dwelling unit sizes. The NE-A, NE-B, NG-A and NG-B Zoning Districts on each block shall contain a mix of at least three lot widths, with the middle width lot at least five feet wider than the width of the smallest lot and five feet narrower than the width of the largest width lot (i.e. 55-feet, 60-feet and 65-feet wide. See Note 1, Table 3 2).

A combination of one-, two- and three-story homes is encouraged, but is not required.

3.7.4 Net Residential Acres and Average Density
“Net residential acres” are the private lands zoned for residential uses exclusive of streets, parks, and other public uses. “Average density” is the total number of dwelling units in that Zoning District divided by the net residential acres as approved in each Tentative Subdivision Map. “Average Dwelling Units per Net Residential Acre” is the total number of dwelling units within each Zoning District within each Tentative Map divided by the Net Residential Acres within that zoning district on that Tentative Subdivision Map.

3.7.5 Accessory Dwelling Units and Carriage Apartments
Accessory dwelling units (ADUs), and Carriage Apartments, on singlefamily detached lots shall be excluded when calculating the minimum and maximum number of allowable units in accordance with Salinas Zoning Code Section 37-50.250(g). Carriage units are to be constructed at the time the principle unit is constructed unless otherwise approved by the City Planner and are subject to the provisions found in Table 3 1, Footnote 6.

3.7.6 Proof of Conformance
The application for a tentative subdivision map shall include a chart demonstrating that the total number of proposed dwelling units, excluding ADUs, within each of the Zoning Districts within each block of the Tentative Map, divided by the total net residential acreage within each Zoning District within each block of the Tentative Map, will meet the density requirements of Section 3.8.3 of this Specific Plan and as described in Zoning Code Section 37-30.460. The application shall be consistent with Appendix G and Chapter 3 of this Specific Plan. The net acreage of 82 City of Salinas | Final Central Area Specific Plan, November 2020 each zoning district shown must substantially match the acreage shown in Appendix G. The Chart shall also demonstrate conformance with the minimum and maximum densities and density percentages required in the 2002 General Plan.

A Lot Standard Master Plan will also be required to be approved by the Community Development Department prior to recordation of any final map which creates any residential lot as provided in Section 9.3.1 of the Specific Plan.

3.8 MinimumRequiredandMaximumAllowable
Densities

3.8.1 Total Net Developable Residential Acres Within
Each Zoning District
NE-A NE-B NG-A NG-B NG-C VC-A VC-B Total
Net Acres (1) 108.59 89.33 56.94 31.46 33.23 27.35 17.08 363.98 Note 1: Refer to Appendix G

3.8.2 Average Number of Dwelling Units Per Net
Developable Residential Acre Required Within
Each Block in Each Zoning District
NE-A NE-B NG-A NG-B NG-C VC-A VC-B Average Units
Per Net Acre
Minimum 5 7 8 9 14 18 24 9.0
Maximum 6 8 9 10 16 24 31 10.7

3.8.3 Minimum and Maximum Total Allowable
Dwelling Units Required in Each Zoning District
NE-A NE-B NG-A NG-B NG-C VC-A VC-B Total Dwelling
Units
Minimum 543 625 456 283 465 492 410 3,274
Maximum 652 715 512 315 532 656 529 3,911
Remainder of page intentionally left blank
Use Classifications and Development Regulations
83 3.8.4 Allowable Floor Area Ratio (FAR) in all the NG-C, VC-A and VC-B Districts in the Central Area
The central portion of the North of Boronda FGA proposed Central Area Specific Plan has a General Plan allocation of approximately 489,700 square feet of commercial and mixed use (including Village Center [VC] residential). The Central Area Specific Plan permits the conversion of up to 214, 000 square feet of commercial floor area to residential use on the basis of 1,000 square feet of commercial floor area for one residential dwelling unit, without further CEQA review. These dwelling units can be sited within the Village Center districts. Conversion of this commercial floor area to residential dwelling units is subject to the approval of the property owners of the Village Center (VC) area and the City Planner.

The use of converted units will not count toward the overall high density unit count or the overall medium density unit count for the Specific Plan.

However, the General Plan required density mix shall still be met. The increased density, if used, is consistent with the New Urbanism goal of promoting a thriving Village Center.

3.8.5 Conversion Factor for Comparable Impacts of
Residential and Commercial Uses
The maximum amount of commercial mixed use square footage (floor area ) in the Plan Area is 489,000 square feet. Footnote 4 in the General Plan Table LU-2, on page LU-29 states;
“Residential development of comparable impact may be considered.

Comparable impact is considered to be the substitution of 1,000 square feet of non-residential commercial floor area for one residential unit. For this calculation, 40 dwelling units per net acre equals a floor area ratio of 1.0; 20 dwelling units equals a 0.5 FAR, etc.”
Therefore, if a building in the NG-C, VC-A and VC-B Zoning Districts is built to conform to the Flex Use requirements in Footnote 8 of Table 3 1, said building may initially, or at a later date substitute residential uses for the allowable square footage of commercial uses at the ratio of one residential unit per 1,000 square feet of allowable commercial use. The total residential and commercial square footage within the blocks shall not to exceed a 0.425 FAR in the NG-C District within the block, or a 0.65 FAR in the VC-A District within the blocks shown on the applicable development review application for the subject building, or a 0.85 FAR in the VC-B District within the blocks shown on the applicable development review application for the subject building, and may convert the residential use to a commercial use, or vice versa, at a later date, provided the minimum number of residential units per net acre required in Sections 3.9.3 remain in that District and the maximum residential units allowed in Section

3.9.3 are not exceeded on the blocks shown on the development review application for the subject building.
84 City of Salinas | Final Central Area Specific Plan, November 2020

3.8.6 Flex Use Buildings
The buildings in the NG-C, VC-A and VC-B districts may be any combination of office,retail, service, public and/orresidential uses (subject to approval by the City Planner), provided the minimum number of residential units per net acre required in Section 3.8.2 and 3.9.2 remain in the zoning district and the maximum residential units allowed in Section

3.8.2 and 3.9.2 are not exceeded on the blocks shown on the tentative map application within those districts.

3.8.7 Consistency with The General Plan
In order to make the Central Area consistent with all the different requirements in the General Plan, the following must be satisfied:
(a) using net residential acres in the Central Area as provided in Appendix G
(b) the minimum required 9 dwelling units per net residential acre must be provided (363.98 x 9.0=3,274 minimum dwelling units); (Section 3.9.4)
(c) 35% to 45% of the total dwelling units must be built at 7 to 14 units per net acre. Zoning Districts NE-B, NG-A and NG-B will provide dwelling units at 7 to 14 dwelling units per net acre, which would yield between 1,145 and 1,473 dwelling units in this range. (d) 15% to 25% of the total dwelling units must be built at 16 to 24 dwelling units per net acre. The VC-A District. Zoning District will provide dwelling units at 16 to 24 dwelling units per net acre which would yield between 491 and 819 dwelling units in this range.

Sections 3.8.3 and Appendix G of the Specific Plan establish the minimum required and maximum allowable dwelling units per net acre in each Zoning District for each Planning Subarea and owner in order to meet these General Plan requirements. See Appendix G, and Section 3.9.

Additionally, Appendix C, General Plan Consistency Table, for a full description of the Central Area Specific Plan compliance with General Plan goals and polices.

3.8.8 Compliance
No further proof of compliance will be required of a project applicant provided the application is in conformance with the required densities in Sections 3.9.1 through 3.9.7 of the Specific Plan, Appendix G and the minimum and maximum densities and density percentage in the General Plan.

Use Classifications and Development Regulations
85 3.9 SpecificPlan’sConformancewithTheGeneral
Plan’s Minimum Required and Maximum
Allowable Densities

3.9.1 General Plan Assumed Density Ranges

3.9.3 Compliance
To encourage a variety of lot sizes and housing types within the various Zoning Districts, neighborhoods, and blocks in the Central Area, the term “Lot Standard” refers to a single-family attached or detached dwelling unit (housing type) with varying lot sizes and development regulations achieving the neighborhood variety required in the General Plan, Subdivision Ordinance, and this Specific Plan. A Lot Standard Master Plan will be required to be submitted to the Community Development Department for approval by the City Planner prior to recordation of any final map which creates any residential lot.

No further proof of compliance will be required of a project applicant provided the application is in conformance with the required densities in sections 3.8.1 through 3.8.7 of the Specific Plan, the General Plan and Appendix G.

3.9.2 Specific Plan Conformance with the General Plan’s Required Density Ranges
General Plan Land Use
Designations Low Medium High Mixed Use
Min. to Max DU/Net Ac 6 to 8 9 to 15 16 to 24 10 to 50
General Plan Land Use
Designations Low Medium High Mixed Use
Specific Plan Zones NE-A
NE-B
NG-A
NG-B
NG-C
VC-A VC-B Total
Net Residential Acres 197.92 121.63 27.35 17.08 363.98
Minimum dwelling Units 1,168 1,204 492 410 3,274
Maximum dwelling Units 1,367 1,359 656 529 3,911
Average DU/Net Ac 6.5* 12* 21* 27.5* 9 to 10.7*
*See Section 37-30.460 of the Salinas Zoning Code. The parcel-specific requirements allow densities from 5 dwelling units per net residential acre to 8 dwelling units per net residential acre in the NE-A and NE-B Zoning Districts. These two districts combined have an average density of 6.5 dwelling units per net residential acre, which is consistent with the General Plan’s Residential Low Density designation. Similarly, the parcel-specific requirements in the NG-A, NG-B and NG-C Zoning Districts allow 8 dwelling units per net residential acre to 16 dwelling units per net residential acre. These three districts combined have an average density of 12 dwelling units per net residential acre, which is consistent with the General Plan’s Residential Medium Density designation of 9 to 15 dwelling units per net residential acres. The parcel-specific requirements allow from 18 to 24 dwelling units per net residential acre in the VC-A Zoning District. This district has an average density of 21 dwelling units per net residential acres which is consistent with the General Plan’s Residential High Density Designation.

Lastly VC-B Zoning District is consistent with the General Plan’s Mixed Use designations, which allows 1.0 FAR plus 10 dwelling units per net acre and the conversion of mixed use commercial floor area to dwelling units in accordance with 1,000 square feet of commercial floor area per one dwelling unit conversion rate. 86 City of Salinas | Final Central Area Specific Plan, November 2020

3.10 General Plan Required Percentage in Two
Density Ranges

3.10.1 General Plan Page LU-39 Requirements
The General Plan requires that:
“From 15% - 25% of the housing units in such developments shall fall within the density range of 16 -24 units per net residential developable acre, and 35% to 45% of the housing units shall fall within the density range of 7-14 units per net residential developable acre.”

3.10.2 Specific Plan Conformance to General Plan
Sections 3.9.1 through 3.9.6 require minimum and maximum average densities in each zoning district in the Central Area which result in the following percentages in the two density ranges.

3.10.3 Test of Density Mixes
Sections 3.9.9 and 3.11.3 together with Appendix G, demonstrates that the Central Area will meet the General Plan’s required percentages in the two specified density ranges.

3.10.4 Compliance
No further proof of compliance will be required of a project applicant provided the application is in conformance with the required densities in this Chapter.

3.10.5 General Plan Page LU-30
Page LU-30 of the General Plan states that, “For various reasons, many parcels in the community have not been developed to their maximum density or intensity. In the future, the maximum development potential described in this element can be expected to occur only on a limited number of parcels. Therefore, the overall future development of the City is anticipated to occur at the average level of development intensity or density indicated in Table LU-2.”
The General Plan includes the average density for the purposes of estimating population and employment capacity, but the average densities are not intended to be parcel specific. Because the General Plan states that the average density is not a parcel specific limitation, and it states that the maximum density values correspond with the maximum densities and intensities permitted within the Land Use Plan, the minimum and maximum density requirements included in Table LU-2, not the average density values, determine how much (or how little) development is allowed on an individual parcel. As discussed in Section 3.10, the densities permitted in the Central Area Specific Plan are consistent with the range of densities permitted by the Land Use designations in Table LU-2 of the General Plan.

Use Classifications and Development Regulations
87 3.10.6 Compliance
No further proof of compliance will be required of a project applicant provided the application is in conformance with the required densities in Sections 3.9.1 and 3.9.4 of the Specific Plan, and Appendix G.

3.11 Required Park Acres in the Central Area
Specific Plan
Parks are provided in accordance with the Quimby Act which requires a minimum of 3.0 acre of park per 1,000 of population. Population is calculated at 3.67 persons per dwelling unit in accordance with the Salinas General Plan and Section 31-802 of the City Subdivision Ordinance. See Appendix G for required park acreage calculations based on buildout scenarios and Table 4-1, Park Summary.

Remainder of page intentionally left blank
88 City of Salinas | Final Central Area Specific Plan, November 2020 This page is intentionally left blank.
89 Final Central Area Specific Plan
November 2020

4. Design Standards

4.1 Introduction
The Design Standards in this Chapter are intended to assist designers and developers understand and implement the City’s expectations and requirements for high quality, traditional neighborhood development in the Plan Area and shall serve as the design basis for all proposed development. These design standards complement the Development Regulations in Chapter 3 by providing examples of potential design solutions and concepts, and by providing design interpretations of the various mandatory regulations in Chapter 3. Where the word “shall” is used, the design standard is mandatory, where “encouraged” or “should” is used, an alternative design solution, which achieves a comparable result may be used if approved by the City Planner.

These standards are intended to ensure the highest level of design quality while providing the flexibility necessary to encourage creativity on the part of project designers. These standards are also intended to promote development which is pedestrianoriented, safe, sustainable and reflects traditional neighborhood design principles. The Central Area Specific Plan has further refined and delineated the design concepts and standards that shall apply to the Plan Area. The design standards are divided into design standard categories by zoning district to address the design standards for each of the various types of development in the Plan Area.

Design standards are essential to achieving the
desired aesthetic envisioned for the Central Area
Specific Plan.
90 City of Salinas | Final Central Area Specific Plan, November 2020

4.2 Applicable Central Area Design Standards
As noted in Section 3.3 of the Specific Plan, the requirements of Chapters 3 and 4 of the Central Area Specific Plan, including but not limited to, Table 3 1, Table 3 2, Table 3 3 and shall prevail where in conflict with the requirements in the Salinas Zoning Code Division 8 – New Urbanism (NU) Districts Regulations. Where there are no conflicts with the Specific Plan, inconsistencies or an issue is not addressed, the requirements of the Salinas Zoning Code Division 8, shall apply to land located in the Plan Area. For design standards that are not described in the Specific Plan, the Zoning Code shall apply.

All Planning Subareas references contained in this Chapter or elsewhere in the Specific Plan are to the Planning Subareas found on Figures 2-1, Specific Plan Land Use Map and in Appendix G.

4.3 Village Center A and B Districts

4.3.1 Village Center A and B Design Intent
(a) Concept. The Village Center (VC) Districts of the Central Area Specific Plan shall comprise a mix of office, commercial, and residential uses.

The Village Center (as referred to in this Chapter) consists of two Zoning Districts: The Village Center A (VC-A) and the Village Center B (VC-B). The VC-B District encompasses the primary core area of the Main Street and the area fronting the southernmost Village Green (Planning Subareas 153 through 157). The VC-A district generally encompasses the areas directly north of Boronda Road, located to the south and east of the VC-A District, (Planning Subareas 176 and 177) as well as the areas located north of the VC-B District, (Planning Subareas 159 through 162 and 306).
(b) Village Greens - Gathering Places. A Village Green is placed on the southeast side of Hemingway Drive and the southerly greenway street (Planning Subarea 170). A second Village Green is located on the southeast side of the Main Street and Russell Road (Planning Subarea 209). These two Village Greens will be primary focal points with public art, fountains or other elements and may also contain public amenities such as tot lots, benches, monuments, and kiosks. (c) Uses. The mixed use Village Center Districts will become an important destination for the Plan Area residents by providing a variety of offices, shops, services, restaurants, and civic facilities that serve the needs of the surrounding neighborhoods.
(d) Residential. The buildings (including but not limited to dwellings and accessory structures) fronting on the southernmost Village Green shall be flex use buildings to accommodate retail, office and residential uses on the ground floor and office or residential uses on the higher floors. Appropriate housing types for the remainder of the Village Center districts include stand-alone multifamily dwellings such as apartments and/or condominiums, senior housing, and some singleThe Specific Plan will include a mixed use Village Center
and residential areas of
varying densities.

Design Standards
91 family attached homes such as townhouses and live-work units.

Single-family detached dwellings are not appropriate housing types in the two Village Center Districts (see Table 3-1).
(e) Urban Design Character. Buildings in the VC-A, and VC-B shall be built predominantly to the back of the 15-foot wide sidewalks (except as provided below) measured from the face of curb with four foot recesses for outward swinging entries to form active street fronts (“street” herein may be a public street or private street which functions as a public street) and create other connecting pedestrian spaces. (See Table 3-2 Note 12 for detailed requirements). The sidewalk on the north side of the southerly greenway street, between Hemingway Drive and the library shall be 18 feet wide measured from the face of curb. The anchor grocery store and secondary stores which may be located adjacent to Boronda Road may be placed back from the street. The smaller stores which may be located across the streets from the southernmost Village Green (Planning Subarea 170) shall be placed adjacent to the sidewalk and shall front toward the Village Green. The size of all parking lots shall be reduced by breaking large parking lots into smaller blocks of parking and shall locate employee parking in less-used areas. On-street parking for customers and residents is encouraged.
(f) BuildingOrientationandAccess.Exceptforthe anchorgrocerystore building located within the VC-A district within Planning Subarea 176, buildings within the two VC districts shall have the primary entrance door(s) and windows facing the street in order to create an active street front. Primary ingress and egress for pedestrians shall be through the front of the building. Building placement and massing should provide visual interest and architectural variety while relating to nearby buildings.
(g) Pedestrian Connections to Rear Parking. Minimum 16-foot wide pedestrian connections from the sidewalk along the building frontage to the rear parking areas shall be provided approximately mid-block on Planning Subareas 153, 155 and 156 through 161 in order to increase access to the front of buildings from the parking in the rear. Pedestrian crosswalks on the Main Street shall be provided at all corners and where there is a pedestrian connection to the rear parking. The pedestrian crosswalks shall be aligned with the midblock pedestrian connections to the parking in the rear. Driveways to the rear parking areas shall only be allowed from the east/west cross streets and the rear streets parallel to the Main Street. Midblock crossings shall be subject to approval of the City Engineer. (h) Land UseTransitions.Zoning district boundary transitions between the Village Center and the abutting zoning district shall occur across streets, rather than within blocks.
92 City of Salinas | Final Central Area Specific Plan, November 2020 (i) Relationship of Buildings to Public Spaces. Buildings and streets should be designed to create safe, active, pleasant public spaces by providing an ordered variety of entries, windows, bays, and balconies along public ways. Buildings shall have pedestrian-scale details and massing. Buildings shall have frequent doors and windows along public ways.
(j) Building Transparency. Seventy-five percent of the building’s first floor façade for all of the retail and office uses in both VC districts, which face orfront the Village Greens, the Main Street orthe southerly greenway street, shall be transparent with a pattern of windows and doors with clear or lightly tinted glass allowing visibility into the structure and into display windows. At least 50 percent of the façade for retail and office uses facing the side streets and along the midblock pedestrian pathways (between buildings, connecting parking areas to the Main street) shall be transparent. The remainder of the façade shall include a variety of design elements, such as recesses, balconies, and overhangs to provide visual interest and maintain a pedestrian-friendly character (see footnotes in Table 3-2).

4.3.2 Village Center A and B Street Design
(a) Village Center Streets. In order to create an active Village Center, a 15-foot sidewalk (except for the 18-foot southerly greenway path/ sidewalk that traverses the Village Center) as described in Section

4.3.1(e) andsixtydegreeon-streetparkingshall abutthenorth, east, and south sides of the southernmost Village Green, both sides of the Main Street and both sides of the east/west cross streets within the Village Center districts. Subject to approval of the Owners Association (OA), controlled display of goods for sale, outdoor restaurant seating on the sidewalks in front of commercial uses, and street closures for events like farmers markets or street fairs are encouraged to create a vibrant, pedestrian environment. The sidewalks, on-street parking, and streets in the two VC districts shall be maintained by the abutting property owners through an OA (see Chapter 8). On-street parking in both VC districts shall count towards the required parking (see Table 3 2, note 9). Also see Chapter 7.0 for Stormwater Development Standards. (b) Main Street. The two Village Center districts create a mixed use commercial core area with a Village Green at each end of the Main Street. These districts will include:

1. Planning Subarea 176, which abuts Boronda Road, may have stand-alone one story retail buildings including an anchor grocery store with offices, smaller stores, and/or high density residential uses.

2. The north/south Main Street extends along the east side of the southernmost Village Green and continues north to Russell Road.

Design Standards
93 This Main Street may be bordered by mixed use, flex use and multi-story, multifamily buildings.

3. The first floor façade of Flex Use buildings must be designed and engineered to allow the provision of shop doors, display windows, and signage spaces above the first floor doors and windows to accommodate non-residential uses.
(c) Direct Local Connections. The east/west Village Center streets have been provided from surrounding neighborhoods to the Main Street so neighborhood residents do not need to use arterial streets to access the Village Center. This ensures that easy and direct pedestrian and bicycle access will be available to and from the surrounding neighborhood.
(d) Arterial Street Access. The Village Center opens to both Boronda Road and Russell Road (arterial streets) providing connectivity with the existing city circulation system. This connection to arterials assists in providing the neighborhood with a sense of place and identity and to provide residents from outside the Plan Area easy access to the shopping and entertainment along the Main Street and in and around the Village Greens.
(e) Integrations of the Transit Stop. The intersection of Hemingway Drive and the southerly greenway Street will provide a major stop on the local transit network. Monterey Salinas-Transit (MST) (see Appendix H) has tentatively approved a stop in this location. When developed, an MST-approved bus shelter and trash receptacle will be provided at this location by the developer. Design of the bus shelter and furnishings shall be subject to approval of the City Planner. (f) Pattern of Streets and Blocks. All streets in the Central Area are interconnected at the ends of each block and are scaled to the needs of pedestrians, bicyclists, and vehicles. Super blocks, dead-end streets, loop streets, and cul-de-sacs are not permitted.
(g) Block Size. Individual blocks along the Main Street shall be three hundred feet to nine hundred feet long and one hundred fifty feet to five hundred feet deep. The Main Street shall have corner and midblock pedestrian crossings with curb bulb-outs and mid-block access to the rear parking Blocks outside the VC District generally have no more than an 1,800-foot perimeter. See the Central Area Land Use Plan in Appendix G for block size information.
(h) Building Frontage. Buildings within the Village Center shall frame the public right-of-way and abut the sidewalks along the Main Street, the southerly greenway and northerly greenway streets and the east/west streets in the Village Center. See Chapter 3 Development Regulations for further requirements regarding building frontage.
(i) Pervious Hard Surfaces. Pervious hard surfaces (e.g. permeable colored concrete or decorative pavers) are encouraged to be used in 94 City of Salinas | Final Central Area Specific Plan, November 2020 the sidewalks, street parking, driveways, parking lots and plazas in the Village Center districts where approved by the City Engineer.

4.3.3 Village Center A and B Architecture
(a) Concept. Within the Village Center zoning districts, the mixed use, flex use, and stand-alone commercial buildings shall include the following:
(b) Natural Surveillance. Design and placement of buildings and other physical features shall maximize visibility and facilitate natural surveillance from public or private streets and other public areas.

This includes building orientation, placement of windows, doors and balconies, building and site entrances and exit locations, placement of parking, lighting, and refuse containers, placement and type of landscape materials, plazas, and other open space areas, location of walkways, types of walls, and fences (including the use of picket, wrought-iron, and similar materials to promote visibility), to promote Crime Prevention Through Environmental Design (CPTED).
(c) Relationship of Buildings to Streets. The primary facades (the primary customer entries) of all buildings located in the Village Center shall face a street or streets except for the anchor stand-alone grocery store located adjacent to Boronda Road. When a store abuts a street and the primary access is provided from a parking area other than the street, the rear parking lot facades and the street-facing facades of the store shall have prominent articulated customer entrances and provide pedestrian-scaled architectural features including windows and a significant entry feature. Whenever an elevation of a building fronts a street, the same architectural elements shall be incorporated on that elevation consistent with those found on the primary façade which provides access to the building.
(d) Primary Entries and Facades. Except for the anchor grocery store building that is set away from the Main Street the primary entrances of ground floor uses shall be visible and accessible directly from a public or private street. Architectural design shall be used to identify building entries. For example, greater height can be used to accentuate entries in the form of tower elements, tall voids, or a central mass at an entry plaza. Primary facades that front onto a street shall be built parallel or nearly parallel to the public right-of-way except for courtyards, plazas, and corner locations. Generally, the streetfacing facades shall stay within five feet of the back of the continuous sidewalk. Facades beyond five feet of the back of the continuous sidewalk are subject to approval by the City Planner.
(e) Street-facing Facades. Street-facing facades of retail and office uses should be lined with windows. Uninterrupted blank walls shall not occupy over 25% of a building’s street frontage along the Main Street and other streets in the Village Center unless otherwise approved Design Standards
95 by the City Planner. Blank walls shall not exceed twenty linear feet without being interrupted by a window, significant architectural feature, or entry. For the anchor grocery store and associated secondary stores on the same site, blank walls along frontages shall also not exceed 20-feet without being interrupted by a window or significant architectural feature. Architectural features may include landscaped setbacks, trellis elements, or similar decorative features.

Tables and chairs and display of merchandise is encouraged within building setbacks on Village Center streets and within five feet of the back of the street sidewalk as long as such activities do not interfere with accessible path and access requirements.
(f) Walkway-facing Facades. The main entrance of all buildings without street edge facades shall open directly onto a publicly accessible walkway. The walkway shall have colored concrete and must directly connect to an adjacent street’s sidewalk and the rear parking area. For the anchor grocery store not located on Main Street, parking may be directly in front of, or to the side of the building. In this case, the primary pedestrian entry and windows of the building shall be visible from the parking area and front onto a publicly accessible walkway that connects to the street sidewalk. If the anchor grocery store or secondary stores are accessed primarily from the rearoriented parking area they shall have an entry feature and pedestrian scaled architectural features on the building façade facing the parking lot, and if the store abuts the street, the facade of the store shall also include a customer entrance with a significant entry feature and other pedestrian-scaled architectural features including windows on the street façade of the building.
(g) Connecting Walkways. Walkways from the parking lots to the rear entries and to the mid-block connections to the Main Street must be clearly distinguished from the parking lot and have paved allweather surfaces meeting accessibility (ADA) requirements. Such areas shall be a minimum of 16-feet wide. Parking lot walkways shall be landscaped (with shade trees on both sides 30-feet to 40- feet on center) and shall be equipped with lighting unless otherwise approved by the City Engineer and City Planner. Lighting standards, a maximum of twenty-five feet in height, in the Village Center parking lots and a maximum of twenty-feet in height, along the walkways are required. Lighting standards shall be spaced to maintain an appropriate illumination level as determined by a photometric study in accordance with the City’s Zoning Code.
(h) Architecture.
(1) Projections. Trellises, canopies, blade signs, and fabric awnings may project up to five feet into the public rights-of-way, provided they are not less than eight feet clear above the sidewalk and are approved by the City Engineer. Balconies and bay windows may 96 City of Salinas | Final Central Area Specific Plan, November 2020 project over the sidewalk up to four feet from the face of curb. They may be supported by columns creating arcades which shall provide a continuous path of travel at least 10-feet wide and ceiling clear heights not less than 10-feet.
(2) Recesses. Up to 25 percent of a building frontage may be recessed up to 40-feet from the back of the sidewalk for the purpose of accommodating a patio or a plaza.
(3) Base. All facades shall have a recognizable minimum 16-inch high base, consisting of, but not limited to: thicker walls, richly textured materials, (e.g. tile or masonry treatments) composed of special materials such as ceramic tile, granite, or marble, or darker colored materials, and/or two-foot to four-foot wide planters (may be raised) with enriched landscaping that is permanently maintained. (4) Top. All facades shall have a recognizable top consisting of, but not limited to, cornice treatments; roof overhangs with or without brackets; stepped parapets; richly textured materials (e.g., tile or masonry treatments).
(5) Ground Level Bays. For mixed use areas, storefronts, and/or other office and commercial building, the bays shall be narrow enough to maintain visual interest and variety along the streetscape.

Projections and recessed bays should be not wider than 30 feet and should be defined by vertical architectural features such as columns, pilasters, doors, and windows.
(6) Storefronts. For the VC-A and VC-B districts, display windows in retail and office uses abutting the sidewalks along the Main Street, across from the southernmost Village Green and along the southerly greenway street, shall encompass a minimum of 75 percent of a storefront’s linear frontage. For the NG-C district, display windows in retail and office uses abutting the sidewalks shall encompass a minimum of 40 percent of a storefront’s linear frontage. This standard is not applicable to the side streets, or driveway frontages or residential uses.
(7) Entries. Primary pedestrian entries shall be clearly expressed and shall be recessed and/or framed.
(8) Windows. Windows shall be vertical in proportion (preferred ratio

1.62 high by 1.0 wide) and in character with the architectural style of the building. The use of mirrored glass or glass curtain wall construction is prohibited. Clear or lightly tinted glass must be used for storefront windows.
(9) Roof-mounted Mechanical Equipment. Roof-mounted mechanical equipment shall be fully screened behind parapets or by recessing equipment into hips, gables, parapets, or similar architectural features in accordance with the Salinas Zoning Code.

Design Standards
97 (10) Building Height. Variation in building height is encouraged to provide visual interest and variety (see Chapter 3 Development Regulations, Table 3 2 of the Specific Plan for height limitations).

Buildings higher than allowed in Chapter 3 of the Specific Plan may be considered through a Conditional Use Permit process. (11) Massing of Large Buildings. Buildings shall provide substantial variations in massing appropriate to the architectural style.

Variations in massing include changes in height and horizontal plane and should also include substantial architectural elements that either project up or away from the building, such as a tower, bay, lattice, or other architectural feature. Stepping elements of the building up or back or projecting them over the sidewall can also reduce the apparent scale of the building. Changes in mass should relate to the structural system(s) and the organization of interior space. Building roofs shall have a 6 inch or greater rise for every 12 inches of run, and clearly defined eves. Flat roofs within 10 feet of the building’s edges are not permitted.
(12) Materials. Buildings should reflect regional traditions and maintain a high level of craft in the process of construction.

Buildings shall have complementary and compatible materials, but not necessarily only one material and detail. Material changes shall not occur at external corners but may occur at reverse or interior corners or as a return from external corners, provided the return is of a sufficient depth to be consistent with and complement the architectural style of the building, as determined by the City Planner.

4.3.4 Village Center A and B Parking
(a) Vehicle Maneuvering Areas. Vehicle maneuvering areas such as drive-through lanes, service station or convenience store pump islands or service bays and similar vehicle related areas and associated uses are prohibited in the Specific Plan area except within the VC-A district located atthe northeast corner of BorondaRoad and HemingwayDrive (Subarea 182) and the Subarea 87. Uses with such maneuvering areas are subject to the approval of a Conditional Use Permit in accordance with the requirements of Table 3 1 and Table 3 2. In approving the CUP, the City Planner must make findings that the proposed use and related maneuvering areas will not compromise or unreasonably interfere with pedestrian access or movements or in any way degrade the pedestrian-friendly environment. At a minimum, drive-through travel lanes, roll-up service doors and gas pumps shall be screened from view of adjacent rights of way behind a building or with other screening features incorporated as required in the footnotes on Table 3 2 of the Specific Plan or as a condition of the CUP. Such uses that require screening may not be located between the sidewalk and the street facades of any buildings, except along Boronda Road and then only behind a minimum of six-foot high landscape screening with 98 City of Salinas | Final Central Area Specific Plan, November 2020 shrubs and trees between the use and the public sidewalk, and shall not take access directly from Boronda Road or Hemingway Drive and are not allowed to be located more than 230 feet from the northerly right-of-way line of Boronda Road.
(b) Parking Requirements. The parking requirements for the Village Center A and B Districts are contained in Chapter 3.0, Table 3 2, Note 9, Development Regulations, of the Specific Plan. All dimensional requirements for parking spaces, bicycle and accessible parking spaces, parking configuration and aisle dimensions, driveways and similar requirements shall be subject to the requirements of Division 2 of the Zoning Code. The size of all parking lots shall be reduced by breaking large parking lots into smaller blocks of parking, Employee parking may be located in less-used areas of parking lots. On-street parking for customers and residents is encouraged. All parking lots shall have orchard style landscaping planters as described below. See Subsection (h) below for vehicle charging station requirements. (c) Shared Parking. A mix of residential and commercial uses in the Village Center creates staggered periods of peak parking demand.

Shared parking shall be provided in accordance with Note 9 in Table 3 2 to reduce the total amount of required parking. At least one of the required residential parking spaces shall be in the rear of the residence, in an enclosed lockable garage or within a secured carport area. The second required residential parking space and all retail, office, and entertainment uses in mixed use buildings may share the street parking and the rear open parking areas within the Village Center districts. To the extent possible, the second residential parking space and all non-residential parking facilities should be located on the adjoining street on which the building abuts, and in shared lots behind the buildings to serve as many uses and activities as possible and to enable commercial customers to park once and be in close proximity to a variety of shops, services, and activities. (d) On-street Parking. Adjacent on-street parking (parking directly abutting the individual block on which the building occupies) shall be counted towards the parking requirement for adjacent buildings in the VC- A and B districts zones. A maximum of 50% of the required parking may be located on the streets adjacent to the building. It must, however, be acknowledged that this on-street parking may be subject to removal in the unlikely event traffic improvements are needed.

The amount of on-street parking shall be maximized with sixty (60˚) degree diagonal parking on the streets in the VC-A and VC-B districts where approved by the City Engineer.
(e) Reduce Scale of Parking Lots. Large surface parking lots should be visually and functionally segmented into several smaller lots by the use of drive aisles or walkways where possible.
(f) Parking Lot Landscaping (Orchard Parking Landscaping). Surface Design Standards
99 parking areas shall be planted with large canopy trees ata minimum ratio of one tree for every five parking spaces. Trees shall also be planted in all bio-retention planter areas and other planter areas in the parking lots, as applicable witha minimum dimension of nine feet (inclusion of the curb) and protected by four-inch-high curbs.

Features to enhance the parking area such as bollards or tree guards may also be incorporated into the site.A minimum nine-foot-wide (inclusive of the curb) landscape planter shall be provided at the end of each parking isle. In the parking lots in the NG-C, VC-A, and VC-B zoning districts, where two rows of parked cars face each other,a nine foot wide bio retention planter with six inch continuous curbs shall be provided. Alternative means of compliance with SWDS shall be subject to the approval of the City Engineer.
(g) StreetTrees intheVillage Center.Both sides oftheMain Street andthe east/west streets located within the VC-A and VC-B zoning districts, shall have 15-foot wide sidewalks (18-foot in specified locations, as described in Section 4.3.1(e)) and sixty (60˚) degree diagonal parking.

Large canopy trees witha minimum 50-foot foot spread at maturity shall be planted between every fourth and fifth parking space ina minimum ten-foot wide planter (inclusive of the curb) and protected bya four-inch-high curb. These trees shall be planted halfway (10-feet) between the sidewalk and the travel lane subject to the approval of the City Engineer. In addition, small species 25-foot spread at maturity decorative flowering trees shall be placed in the corner and mid-block bulb outs. Streetlights shall be centered 30-inches behind the face of the curb and located between the large street trees or as otherwise required in accordance with City standards.
(h) Vehicle Charging Facility and Priority Parking for Alternate Fuel Vehicles. Priority parking and charging stations for electric and/ or hybrid vehicles shall be provided in parking lots in accordance with applicable Building Codes. The lot owner or lease holder of the charging station may charge for the use of these charging stations. (i) Parking Lot Frontage. Parking lots shall not abut the Main Street, streets along the Village Greens, or the southerly or northerly greenway streets. Wherea portion ofa parking lot is located alonga side or rear street, landscaping shall be provided and maintained to minimize views of parked cars from the street. The landscaped edge of the parking lot at the street shall bea minimum of 10-feet wide measured from the back of the sidewalk to the parking lot (the vehicles may overhang the planter by three feet). Within the landscaped buffer, large species trees should be planteda minimum of 30-feet oncenter and four feet behind the sidewalk. In addition, the landscaped edge should includea screening feature six feet from the back of the sidewalk witha minimum height of 36-inches such asa short wall, fence, hedge, or equivalent feature.Absent this feature, plant materials shall be of sufficient quantity and ofa species to meet the minimum height requirement. The screening and landscape features shall not 100
City of Salinas | Final Central Area Specific Plan, November 2020 impact the required side to side visibility from the driveways and at corner locations. Bio-retention may be accomplished in these areas, subject to approval by the City Engineer.
(j) Shade Trees. Large species deciduous trees with a 50-foot average spread at maturity shall dominate the streets, parking areas and public plazas to provide shade in the summer and sun in the winter.

The dimensions of the planter where the tree is located shall be at least 9 feet exclusive of curbs unless otherwise approved by the City Planner. Evergreen trees may be appropriate as screening and accents in locations where year-round foliage is desirable and when needed to visually screen unsightly views such as utility infrastructure. (k) Screening. Private loading areas, transformers, heating units, and other ground-mounted equipment shall be fully screened from public view with six-foot -high masonry walls or fences as approved by the City Planner or fences designed to be architecturally compatible with the primary structure and plantings such as evergreen vines, shrubs, and trees in appropriately sized planters forthe plant materials. Trash enclosures and private loading areas shall be screen by masonry walls in accordance with the requirements of the zoning code. (l) Parking Lot Driveways. All parking lot driveway entrances shall have a minimum of eight feet of colored decorative textured pavers or colored concrete behind the sidewalk to slow and alert vehicles that they are about to cross the sidewalk.
(m) Benches, Street Furniture and Transit Shelter. These items shall be composed of durable and high quality materials that harmonize with the nearby buildings and complement the public realm. The following pages depict the design styles of the proposed street furniture for the Plan Area. Manufacturer and model numbers are provided in the Appendix O to provide guidance in regard to the type and style of benches, street furniture and transit shelters required in the Plan Area. Substitute designs and manufacturers may be provided if they substantially conform to the style shown and are approved by the City Planner. Bus shelters shall be black in color and meet the requirements of MST. All benches and street furniture shall also be painted black in color.

4.4 Neighborhood General C District

4.4.1 Neighborhood General C District Design Intent
(a) Concept. The Neighborhood General C District is established as a transitional primarily residential zone with lesser residential density than the Village Center but greater residential density than the Neighborhood General A and B districts. Neighborhood General C also allows for some very limited flex and mixed uses.
(b) Mix of Uses. The NG-C areas may include day care, senior care and Examples of Shade Trees
Design Standards
101
housing, religious assembly, recreation facilities, small businesses in a mixed use building and residential uses. The NG-C districts may include neighborhood-focused mixed use residential/office/ retail (i.e., small markets less than 6,000 square feet, a convenience store, deli, bakery, etc.) depending on the location of the subarea and the compatibility of the proposed use with the adjacent or surrounding residential uses. The appropriateness of these uses shall be subject to the approval of a minor (administrative) CUP unless otherwise determined by the City Planner. The buildings within each NG-C district may include flex use buildings that may initially be all residential occupancies. The flex use buildings may convert ground floor space to the commercial uses. Live-work units are also encouraged in the NG-C district. See Table 3 1, Use Classifications for allowable uses. The overall density and maximum units shall remain in accordance with the Chapter 3 and Appendix G.
(c) Pedestrian-oriented Design and Access. NG-C districts shall create pedestrian-oriented gathering places such as plazas that help establish the identity and character of the neighborhood. Truck-loading docks shall not be permitted in the VC-C districts, even in the rear of the buildings. Design of the NG-C districts should prioritize convenient and comfortable access for pedestrians and bicycles.

4.4.2 Neighborhood General C District Street Design
Refer to Section 4.3.2 for Village Center street design standards and Chapter 7.0 for Stormwater Development Standards. Refer to Appendix K for street design standards applicable to the NG-C District.

4.4.3 Neighborhood General C District Architecture
Refer to Section 4.3.3 for architecture standards applicable to the NG-C district.

4.4.4 Neighborhood General C District Parking
Refer to Section 4.3.4 for parking design standards applicable to the NG-C District except that only a maximum of 25% percent of the required parking may be located on the street adjacent to the building. Parking shall not be allowed between the public street and the building, except as allowed in Table 3 2, Note 10. Neighborhood General A and B Districts.

4.4.5 Neighborhood General A and B Districts Design
Intent
(a) Concept. The Neighborhood General A (NG-A) and Neighborhood General B (NG-B) districts are established to create an area for transitioning from the larger lot detached single-family dwellings (Neighborhood Edge A and B districts), to the more urban, higher density NG-C district. See Table 3 1, Use Classifications for allowable uses.
102
City of Salinas | Final Central Area Specific Plan, November 2020 (b) The density of dwelling units in each block in the Neighborhood General A and B districts shall become gradually less dense as one proceeds from the Village Center districts to the Neighborhood Edge districts. The overall density and maximum units shall remain in accordance with the requirements of Chapter 3 and Appendix G. (c) Variety. Each block in the NG-A and NG-B districts shall include a variety of lot sizes and housing styles in order to achieve the required variety and minimum/maximum density in each district (see Table 3 2).
(d) Scale. Housing shall be pedestrian-scale in massing, setbacks, and character. Residential developments should encourage structures that foster diversity in design and maintain the character of the community.
(e) Housing Types. In the NG-A and NG-B districts a variety of housing types may be considered including, but not limited to single-family detached dwelling units, alternative housing forms, such as small lot detached single-family homes, green court homes, townhouses, rowhomes, and courtyard apartments not larger than eight dwelling units, and accessory dwelling units over garages on appropriately wide alley served lots containing a detached single-family dwelling unit on the front of the lot. All these types assist to increase density and provide diversity of housing opportunities.
• Green court homes are typically single-family dwelling units (with garages accessing landscaped alleys behind the dwelling) which are sited on three sides of a common green area, which opens to the public street on the fourth side.
• Lane homes are typically single-family dwelling units (with garages accessing landscaped alleys behind the dwelling), which front a common area (minimum 20-foot in width) walkway, which runs from or extends between one public street to another public street.
• Courtyard Apartments typically consist of eight dwelling units clustered around a courtyard which opens to the street with all parking in enclosed garages under the rear or side of the apartment building.
• Row homes are detached single-family homes sited close to the street sidewalk with one-foot-six-inch setbacks to the side property line on both sides and with garages in the rear served off a rear alley.
(f) Design Considerations. The design of the single-family attached dwelling units and Courtyard Apartment multifamily dwellings in the NG-A and NG-B districts should include features typically associated with detached single-family dwelling units, including pedestrian-scaled architectural elements such as doors, windows, Design Standards
103
balconies, porches and other design features to provide interest and variety as well as a sense of individuality. The importance of the design and scaling in these districts must be emphasized, as the scale and the architectural articulation must reflect the detached singlefamily homes located on either side the Courtyard Apartments. This is critical for the successful integration of these multifamily dwellings into the neighborhood.

4.4.6 Neighborhood GeneralA and B Districts Street Design Refer to Appendix K for street sections and Appendix N for landscape design standards applicable to the NG-A and NG-B districts and Chapter 7 for Stormwater Development Standards.

4.4.7 Neighborhood General A and B Districts Architecture Refer to Section 4.7 for architecture design standards applicable to the NG-A and NG-B districts.

4.4.8 Neighborhood General A and B Districts Parking
Refer to Chapter 3 for parking standards applicable to the NG-A and NG-B districts. Parking shall not be allowed between the public street and the building, except as allowed in Table 3 2, Note 10.

4.5 Neighborhood Edge A and B Districts

4.5.1 Neighborhood Edge A and B Districts Design Intent (a) Concept. Neighborhood Edge (NE) districts are established to create a low-density edge for the Specific Plan area.
(b) Housing Types. These districts allow single-family detached dwellings as well as Carriage Apartments and accessory dwelling units are allowed in these two districts. A variety of lot widths, home sizes, and styles shall be included in each block. See Table 3 1, Use Classifications for allowable uses.

4.5.2 Neighborhood Edge A and B Districts Street Design See Appendix K for street sections and Appendix N for landscape Design Standards for the NE-A and NE-B districts and Chapter 7.0 for Stormwater Development Standards.

4.5.3 Neighborhood Edge A and B Districts Architecture
See Section 4.7, Housing Design and Orientation, forArchitecture Standards for the NE-A and NE-B districts.

4.5.4 Neighborhood Edge A and B Districts Parking
Two spaces per unit are required per dwelling unit. Required parking shall be provided in lockable garages with roll-up doors. All garages shall be pre-wired for 220 volts to allow for electric vehicle (EV) charging. Parking shall not be allowed between the public street and the building, except as allowed in Table 3 2, Note 10.
104
City of Salinas | Final Central Area Specific Plan, November 2020

4.6 Housing Design and Orientation
The following design standards shall apply to the NE-A, NE-B, NG-A, and NG-B districts, except as noted:
(a) New residential neighborhoods shall orient all buildings to the public streets, or to public walkways connecting two public streets. (b) Dwelling units shall be oriented to the local street system and public spaces with entries, balconies, porches, and architectural features facing the street or lane connecting two streets. This will enliven the public space, provide “eyes on the street”, and create safe and pleasant walking environments.
(c) Housing should be pedestrian-scale in massing, setbacks, and character. Residential developments shall provide structures that foster diversity in design and maintain the character of the community.
(d) The design of single-family attached dwellings and multifamily dwellings shall include features typically associated with detached single-family dwelling units, including pedestrian-scaled architectural elements such as doors, windows, balconies, porches and other design features facing the street to provide interest and variety as well as a sense of individuality and community. The Courtyard Apartments in the NG-A and B districts shall be carefully designed to generally appear from the street to be of similar height, width and massing of the single- family detached dwellings on the rest of the block. The scale and the architectural articulation are critical for successful integrating these multifamily residences into a predominately single-family neighborhood. The street façade of the courtyard apartments shall be scaled to appear to be two singlefamily homes with front entrance doors accessed from the street.

Multifamily residential garage access shall be provided only from alleys. No street-loaded garages will be permitted. Windows, porches, balconies, or similar elements shall be provided in front overlooking the street to promote visual interest and provide “eyes on the street.”
(e) Parking lots and carports serving multifamily dwellings shall not be allowed in the front and shall be accessed and located as unobtrusively as possible off alleys on the side and rear of the buildings or under the building (see Table 3 2, notes 9 and 10 for exceptions).
(f) To create a pedestrian-oriented, safe, livable environment, each neighborhood in the Plan Area shall demonstrate the following characteristics:
(1) The average residential densities per net residential acre are highest in the Village Center districts and decrease block Design Standards
105
to block through the adjoining neighborhoods and become exclusively a mix of low density residential uses in the Neighborhood Edge districts. See Table 3 2 Development
Regulations for additional details.
(2) The layout of each neighborhood will generally allow the majority of the residents to walk to the schools, library, and Village Center Main Street within five minutes.
(3) Front yard setbacks shall increase and the average residential densities per block shall decrease block to block from the Village Center district to the Neighborhood Edge districts.

See Table 3 2 Development Regulations.
(4) Neighborhood and small parks have been carefully placed throughout the Central area. The parks and school sites are easily accessible within a reasonable walk or bicycle ride (See Figure 2 2, Walkability Map).
(5) Where an open space corridor borders a Neighborhood Edge district, the dwelling units shall face onto a frontage road bordering the open space. See Table 3 2, Note 18 for noise mitigation requirements along the arterial roads.
(6) Where the Plan Area borders agricultural operations on the north side of Russell Road a combination of buffering techniques shall be used including minimum 30-feet front yard setbacks, the placement of the Perimeter Path between the front property line and the street (28-feet), the construction of a parking lane and two travel lanes for Russell Road (32 feet), a center median (22-feet), and dedication of an 88-foot wide “no agricultural use” temporary easement on the north side of Russell Road (30 ft + 28 ft + 32 ft + 22 ft + 88 ft = 200-ft).

The future center median of Russell Road and the Perimeter Path shall be landscaped. Also refer to Section 9.5 and Section

2.10 (Goal 5 - LU Policy 5-3) of this Specific Plan for additional requirements regarding agricultural buffers and easements. (7) Design and placement of buildings and other physical features are encouraged to maximize visibility and facilitate natural surveillance from public rights-of-way and other public areas. This includes building orientation, placement of windows,doors andbalconies, building andsite entrances and exits, placement of parking, lighting, and refuse containers, placement and type of landscape materials, plazas, and other open space areas, location of walkways, types of walls and fences (including the use of picket, wrought-iron, and similar materials to promote visibility), and other features that promote CPTED principles.
106
City of Salinas | Final Central Area Specific Plan, November 2020 (8) To encourage a variety of lot sizes and housing types within the various Zoning Districts, neighborhoods, and blocks in the Central Area, the term “Lot Standard” refers to a single- family attached or detached dwelling unit (housing type) with varying lot sizes and development regulations achieving the neighborhood variety required in the General Plan, Subdivision Ordinance, and this Specific Plan. A Lot Standard Master Plan will be required to be approved by the City Planner prior to recordation of any final map which creates any residential lot in accordance with Section 9.3.1. (g) Entrances: Entries and Porches. Residential front doors and front porches shall face and be visible from the streets, green courts, and walkways between public streets creating a relationship of the private home to the public street and public sidewalk. Entries shall incorporate a welcoming architectural feature such as a porch or covered entry appropriate to the architectural style of the dwelling. Some exceptions may be allowed to provide a variety of architectural types on a street, like the New England “salt box” architectural style which has a flush entry, subject to approval by the City Planner.
(1) Porches. Porches should be an integral architectural feature with the main structure (dwelling). All porches shall
incorporate railings into design. Porches shall be at least six feet deep (exclusive of the rail) and may project up to six feet into the required front yard setback.
(2) Entries. A recessed or projecting architectural entry feature such as a porch, shed, arch, or gable providing weather protection shall accompany most entries. The primary entry to any dwelling shall be an integral architectural feature compatible with the main structure’s architecture.
(h) Garage and Parking Lot Locations.
(1) All single-family attached and detached dwellings except accessory dwellings shall have a two-car garage. CarriageApartments shall have a one-car lockable garage. Other accessory structures shall provide parking in accordance with the Salinas Zoning Code. All garages shall have a roll-up door. The driveway of all street facing garages from the back of the sidewalk to the garage should be turf block or other large cell blocks planted with irrigated vegetation. (See Table 3 1 and Table 3 2 for other requirements).
(2) For homes on lots less than 50-feet in width and for all multifamily dwellings, duplexes, row homes, lane dwellings, and green court homes, the garage or other required parking shall be accessed from an alley located to the rear or the dwelling.
(3) For all uses, with limited exceptions, the garages, carports, and open parking lots shall be located at the rear of the building. No parking Design Standards
107
or driveways shall be permitted on the primary street side of the buildings except for the standard on-street parking. See Table 3 2 note 10 for exceptions.
(4) Alley-loaded (served) garages shall be set back a maximum of five feet from the back of curb of the 20-foot wide paved alley (measured from the back of the rolled curb) to accommodate the turning radius of a typical light duty vehicle. A minimum five-foot landscaped planter shall be provided between rear yard fences and the back of the curb for the alley travel way pavement. A five-foot landscaped area is also required behind the curb for the alley if the property line and alley run along the side of a home.
(5) The minimum interior clear dimension for a garage shall be 20-feet wide by 20-feet deep for a two-car garage and 30-feet wide by 20-feet deep for a three-car garage. The minimum interior clear measurement for a one-car garage shall be 20-feet deep by 10-feet wide. Any tandem garage shall have a minimum depth of 40-feet.

4.7 Schools
The following design standards are intended to help guide school districts as they plan and design the future schools that will be located in the Plan Area. These design standards are advisory in nature and not binding on the school districts.
(a) Elementary and middle schools serve as an important focal point for neighborhoods in the Plan Area. Along with the small and neighborhood parks and library, these facilities provide an identity, sense ofplace anda commongatheringplace forresidents andstudents alike. As such, all school buildings and facilities are encouraged to be sited and designed as prominent civic elements. Theirrecreation areas, gyms, multipurpose rooms, auditoriums, and other facilities should be designed and sited along with the parking in the rear or to the side of the main school building. The school’s main visitor and student entry should be architecturally significant and located adjacent to and fronting onto the primary street with landscaped planters between the street sidewalk and the buildings and not behind a parking lot, bus area, or drop off area. To complement the Plan Area’s black decorative streetlights, street signage, street furniture, and school fencing should be either black vinyl coated chain link, wrought iron or metal slotted fencing. An example of the desired type of black chain link fencing would be that installed at the Rancho San Juan High School, which is located in the adopted West Area Specific Plan off Rogge Road. Additionally, the design of the school facility should incorporate applicable pedestrian enhancing facilities and traffic calming measures, as appropriate. All school sites will be required to incorporate site parcel-based post construction best management practices (PCBMPs) to the maximum extent practicable (MEP) and comply with the City’s SWDS and NPDES Permit.
108
City of Salinas | Final Central Area Specific Plan, November 2020

4.8 Parks and Open Space

4.8.1 Park and Open Space Intent
(a) Concept. There are approximately 150 net acres of land within the Plan Area dedicated to parks and open space. Included within the Plan Area are a variety of park types and sizes and two large creek corridors. The parks range from large neighborhood sports parks with playfields to small parks, with courts and tot lots, and community gardens. There is also an extensive system of pedestrian paths. The diversity of park types provides a full range of recreational areas and aesthetic green spaces to be enjoyed by the Plan Area residents and the surrounding community.
(b) General Plan Goals and Policies for Parks. In designing parks in the Plan Area, the following General Plan Goals and Policies shall be considered.

Goal COS-7: Provide, develop, and maintain ample park and recreational facilities that offer a variety of recreational activities.

Policy COS-7.1: Develop a high-quality public park system that provides adequate space and facilities for a variety of recreational opportunities conveniently accessible to all Salinas residents.

Policy CD-3.1: Create and preserve distinct, identifiable neighborhoods that have traditional neighborhood development (TND) characteristics. Specifically, each neighborhood should have the following characteristics… small parks should be distributed throughout the neighborhood;
Policy COS-7.2: Maximize the use of built and natural features to develop a citywide network of parks and open spaces with Carr Lake, Gabilan Creek, and the Sherwood Park/Rodeo Grounds Complex as essential elements of the open space network.

Policy COS-7.9: Require new residential development to provide land and/or fees to achieve a minimum of 3.0 acres per additional 1,000 population for developed public parklands for community or neighborhood parks.

Policy COS-7.11: Develop and maintain an integrated system of open space corridors and trails along utility easements, powertransmission-line rights-of-way, the reclamation ditch, stream banks, drainage-ways, slopes, and other natural features.

Policy COS-7.13: Developments within Future Growth Areas shall be conditioned to provide all the land and improvements required to achieve the parkland standard of three acres of developed public parkland per 1,000 residents, to meet existing park acreage needs, as referenced in Table COS-5.

Design Standards
109
(c) Quantity of Public Park Acreage. In accordance with the General Plan and the Quimby Act, the Central Area will provide a minimum of three acres of developed public parkland per 1,000 projected population. Park improvements will be in accordance with the Salinas Park and Sport Facility Standards as approved by City.
(d) Park Types. The Plan Area provides approximately 44 acres of public parkland. Park types consist of Neighborhood and Small Parks ranging in size one-half acre to 11.63 acres. Amenities will vary depending on the size, location and type of the park site. Figure 4-5, Conceptual Park Improvements shows an example of concept park improvements. Park locations and amenities may vary somewhat in the final design phase. Improvements will be in accordance with the Salinas Park and Sports Facility standards. Table 4-1 contains a summary of the parks in the Plan Area. Appendix G provides the locations of the parks as well as a breakdown of the park acreage by property owner.

Seven Neighborhood Parks, range in size from approximately 2.01 net acres to 11.63 net acres and are designed to provide for sport fields as well as other recreational uses. Neighborhood Parks include both active and passive areas such as sport fields and courts, children’s playgrounds, picnic areas, pathways for walking, informally landscaped areas and PCBMPs. These parks are primarily designed for the adjacent neighborhoods with the intent of providing recreation amenities that are within easy walking distance most residents. The design also may accommodate multiple sports fields, see Figure 4-5.

Table 4-1: Park Summary
Park Type Approximate Acreage
Neighborhood Park CA 1 3.52
Neighborhood Park CA 2 5.66
Neighborhood Park CA 3 2.06
Neighborhood Park CA 4 4.45
Neighborhood Park CA 5 11.68
Neighborhood Park CA 6 3.55
Neighborhood Park CA 7 3.12
Small Park CS 1 .55
Small Park CS 2 1.09
Small Park CS 3 1.07
Small Park CS 4 1.52
Small Park CS 5 1.14
Small Park CS 6 .58
Small Park CS 7 1.25
Small Park CS 8 .55
Small Park CS 9 .55
Small Park CS 10 1.72
Total 44.06
110
City of Salinas | Final Central Area Specific Plan, November 2020 (e) Small Parks. In the Plan Area there are 10 small parks range in size from approximately 0.5 net acres to 1.67 net acres. Small parks are described in Table COS-2 of the General Plan as: “A small area for children up (to) the age of 7…for children, seniors, or all age groups. Play areas, quiet game areas, landscaping, and limited sports activities.” Small parks provide recreational (both active and passive) activities on a smaller scale within neighborhoods. Amenities may include but are not limited to tot lots, picnic areas, garden spaces, basketball courts, and barbecue pits. PCBMPs will also be included.

In the Community Design Element of the General Plan, Policy CD-3.1 states: “Specifically, each neighborhood should have the following characteristics: Small parks should be distributed throughout the neighborhood.”
The planning and design approach for Small Parks responds directly to the vision of the General Plan. Small parks of varying sizes and uses are included throughout the Plan Area. Small Parks will allow many different and individual designs, types and uses to help establish attractive and distinctive neighborhoods. Small parks maintenance is discussed in Chapter 8.
(f) Access. Pedestrian and bicycle paths and street connections have been sited to allow surrounding residents to easily and safely access parks, recreational facilities, and open space. Parks will also be designed to foster safety by implementing CPTED design principles (e.g., placing dwelling units and streets along parks and open spaces). (g) Open Space Facilities. The open space areas along the creeks will include paths. Tot lots, seating areas and other passive recreational uses may also be considered. These areas will also be used to store and treat stormwater runoff from the adjacent higher ground. Active recreational uses such as ball fields are generally not appropriate in open space areas. (h) Orientation of Homes. Dwelling units shall not back onto the parks or public open spaces in the Plan Area.
(i) Park and Open Space Linkages. The Plan Area features two 300-foot wide creek corridors (Natividad Creek and Gabilan Creek) over 1.4 miles in length. The carefully planned restoration of these denuded creeks will greatly improve their biologic function and will provide the Plan Area with a unique open space network for both passive and active recreation and outdoor education. The open space system will provide a common binding element in the Plan Area. The north/south creek side paths adjacent to the restored Natividad Creek and Gabilan Creek corridors will provide safe, enjoyable places to bike, sit, walk, or run.

The northerly and southerly greenway streets/paths running east and west through the Central Area will link these open space corridors to the residential neighborhoods and parks, schools, retail, and employment areas (in the Village Center) located in the Plan Area. See Figure 5 3, Design Standards
111
Bicycle & Pedestrian Circulation. The path system also provides pedestrian and bicycle linkages to the future growth areas located to the east and west of the Plan Area and to the existing neighborhoods to the south.
(j) Internal Parks and Green Spaces. Figure 4 1, Conceptual Park Map depicts the public parks and open space network in the Plan Area.

Developers for each individual project within neighborhoods will design and provide the green spaces, tot lots, play fields and courts, garden sitting/strolling areas, entry features, and other landscape elements within their developments according to landscape design regulations and guidelines and applicable City standards. Community centers, neighborhood recreation buildings, neighborhood monuments and other appropriate park-oriented structures are encouraged within the various parks and open spaces subject to the approval of the City. Plant and tree materials must be approved by the City Planner, PCBMP plant and tree materials shall conform to the SWDS Appendix C “LID Planting Zones and Plant List” unless otherwise approved by the City Engineer.

Incorporation of dramatic sightlines, viewsheds, and focal points throughout the community and neighborhoods is a critical component of the Central Area Specific Plan in keeping with classic New Urbanism design. Elements such as connecting road alignments, open space corridors, park locations, park shapes, and the geometrics of the Central Area physical layout shall all be orchestrated in a manner to reinforce a dramatic “sense of place” and pedestrian connectivity within this new community.

4.8.2 Parks Design Standards
(a) Park Design. All parks shall be designed by a licensed Landscape Architect or other licensed professional as determined by the City.

Parks shallbeimprovedinaccordancewiththeCityParkClassifications and Sports Facility Standards. Portions of the parks and most of the open space areas shall include native vegetation, where appropriate and practicable.
(b) Materials. Site furnishings shall incorporate recycled materials wherever possible. Innovative green materials, such as permeable reinforced crushed stone paving, recycled concrete, asphalt, and artificial turf are encouraged for the parking lots and pathways within the Plan Area park system. All chain link or metal fencing, on-site freestanding and building lighting, and similar features shall be painted black to match the color of the decorative street lighting. (c) Access. Parks in the Plan Area shall be accessible to all from abutting public streets and paths.
112
City of Salinas | Final Central Area Specific Plan, November 2020 (d) Orientation of Dwellings to Parks. No homes shall back onto a park or onto a public open space in the Plan Area. Dwelling units located on frontage streets bordering parks and open spaces will utilize CPTED principles, by orienting entries toward parks and open spaces providing natural surveillance.
(e) CPTED. The design of the parks (including but not limited to lighting) shall also incorporate CPTED principles.
(f) Turf. Parks shall minimize the use of managed turf areas to the extent feasible. Where provided, turf areas shall be directed into PCBMPs to provide for acceptable water quality, subject to approval by the City Engineer.

4.8.3 Open Space Design Standards
(a) Natividad and Gabilan Creek Corridors. The existing creek corridors running north to south through the Central Area shall be restored to add aesthetic, ecological, recreational components as well as provide stormwater quality and supplemental retention, and detention to the Plan Area. These creeks have been degraded into agricultural drainage ditches for most of their lengths within the Plan. Restoration of these creeks with predominantly native plants will provide new wetland habitat and pedestrian linkages between neighborhoods, parks, schools, and the Village Center. Paths, picnic areas, exercise circuits, game tables and other activity nodes shall be included within the creek corridors as part of the greenbelt system. Benefits provided by the creek corridors will include extensive areas for water quality improvements and passive recreation opportunities as previously discussed.
(b) Natural Features. Existing natural features including creeks, significant trees, and small wetlands shall be protected, enhanced, and expanded through sensitive site planning, landscaping, and other measures to ensure that these features benefit the entire community.

Natividad Creek and large portions of Gabilan Creek will need to be restored and enhanced to create the riparian corridors as part of the development of the Plan Area. Development within the vicinity of creeks shall comply with the top of bank setback requirements of Salinas NPDES Permit Section L.1.d by setting the homes outside the 300-foot wide open space corridor. Dwelling units and other uses shall not back up these natural features.

4.9 Streetscape Standards
The street network design for the Plan Area considered public safety, appropriate transit access and facilities, and pedestrian and bicycle connectivity.
(a) Hierarchy of Streets. The hierarchy of streets within the Plan Area (and the North of Boronda FGA) establishes a framework to create distinctidentifiableneighborhoods thathave traditionalneighborhood Design Standards
113
development (TND) characteristics and corresponding circulation systems. The street network within each neighborhood shall include the following characteristics:
(1) Compact individual blocks averaging less than six hundred feet in length and less than one thousand eight hundred feet in perimeter measured along the property line;
(2) Streets shall be organized into a comprehensive hierarchical interconnected grid pattern network;
(3) Cul-de-sac and closed loop streets are prohibited. (b) Street Network. The street network provides for the following roadway conditions:
(1) Arterial Streets. Arterial streets are the major high-volume roadways occurring at the perimeter of the Plan Area and include:

Boronda Road, Natividad Road, and Constitution Boulevard. (2) Noise Attenuation Walls. Noise attenuation walls are allowed where necessary for noise attenuation in the rear yard setback or as otherwise required in accordance with the CentralArea Specific Plan EIR and MMRP. Homes should not back up to an arterial road. Noise attenuation walls, when required to mitigate elevated noise levels, shall be constructed in accordance to City standards. (3) Village Center Streets. Main Street will serve as the focal point of the Village Center. East/west streets will cross Main Street and the other north/south streets to form the Village Center grid street network. These Village Center streets will have 15-foot wide paths/sidewalks (except for the southerly greenway street which will have an 18-foot wide path/sidewalk as it traverses through the Village Center) with 60-degree angle parking on both sides and one auto travel lane in each direction. The southerly greenway street and Hemingway Drive abutting the southernmost Village Green may have turn lanes and limited parking, subject to approval by the City Engineer. The intersections into the Village Center shall have bulb-outs at each corner and mid-block bulbout crossings. (4) Connector Streets. The northerly and southerly greenway streets extend in an east/west direction across the Plan Area and will connect to the adopted West Area Specific Plan and East Area Specific Plan. These streets are considered connector streets. The southerlygreenwaystreet(outside theVillageCenter)has aneightfoot-wide planter and a 12-foot-wide pedestrian/bike multimodal path on the north side. This street/path will link the various uses within the Specific Plan and will link to areas outside the Plan area. Independence Boulevard, Hemingway Drive, and the entry off Boronda Road, between Hemingway Drive and Constitution Boulevard also will function as north/south connectors within the 114
City of Salinas | Final Central Area Specific Plan, November 2020 Plan Area. They are restricted to two travel lanes (turn lanes may need to be added at major intersections, subject to approval by the City Engineer) with on-street parallel parking. Connector streets are integral components of a grid pattern neighborhood street network and help create a walkable and bikeable community. (5) Local Streets. The Central Area provides a basic conceptual network of interconnected local streets. These streets shall be as narrow as safety allows, typically curved, and lined with parallel parking and large shade trees. These features assist in reducing traffic speeds and increasing pedestrian safety.
(6) Streets Sections. Each area of the Specific Plan shall include street sections appropriately sized for the expected demands. The street sections are summarized in Table 5 2 and included as Appendix K. Circulation is discussed in detail in Chapter 5.0, Circulation.

All street sections are subject to the approval of the City Engineer. (c) Traffic-calming Features. The design of an interconnected grid street network must include provisions slow traffic on neighborhood connector and local streets. Traffic measures that restrict traffic at the expense of the overall interconnectedness of the Central Area should be avoided. While consideration must always be given to specific demands and conditions (e.g., traffic volume, proximity to larger roads, turning movements, special vehicle needs, and intersection spacing), examples of recommended traffic calming measures are addressed in Chapter 5 of the Specific Plan.
(d) Street Trees/Landscaping. The Central Area will be landscaped with a palette of large species street trees and landscaping to provide a cohesive theme for the area (see Appendix N, Master Landscaping Plan and Section 4.13). A master landscaping plan for all landscaping located in the parkways along streets, paths and promenades, open space areas, community entries, the greenway streets/paths, tower line easements and other applicable public areas shall be subject to the approval of the City Engineer and City Planner prior to installation.

This plan shall include a list of the approved trees and plant materials forthe PlanArea forlaterincorporation into the appendices. This plan will need to have a greenway street tree/landscape plan component to ensure consistency in the plant palette along the northerly and southerly greenway streets between the three specific plan areas (West Area, Central Area, and East Area). All residential and nonresidential development will also be required to submit landscaping plans for approval by the City Planner and City Engineer as part of the applicable development review application approval process. All landscaping and irrigation in the Specific Plan Area shall comply with the State Model Water Efficient Landscape Ordinance, City’s Water Conservation Ordinance (Chapter 36A of the Municipal Code), Salinas Zoning Code Landscaping and Irrigation requirements, and the City’s SWDS (in regard to plant material for LID and similar areas).

Design Standards
115
(1) Spacing. Street trees shall be planted on both sides of streets and generally be spaced no more than 30 to 40 feet on-center within the eight-foot wide park strip between the curb and sidewalk and in bulb-outs.
(2) Species. Each street should typically have one dominant species of street tree for the eight-foot-wide sidewalk parkway planting area, with additional street tree types for bulb-outs and any in-street planted medians. Large-canopy (greater than 50-foot spread) deep-root street trees shall be used on all streets. London Plane, Maple, and Elm are typical street trees used successfully in local traditional neighborhoods and are approved for use in the Central Area. All other street trees are subject to the approval of the City Engineer. The Village Center and Neighborhood Center with angled parking and 15-foot to 18-foot wide sidewalks should also have some 20-foot to 25-foot spread flowering trees planted in the bulb outs at pedestrian crossings. In the Village Center, largecanopy (50-foot + spread) trees shall be planted in minimum ninefoot wide planters between every fourth and fifth parked car, and they should be planted 10-feet from the face of the sidewalk curb.

These trees should be able to provide shade from the center of the adjoining street to the buildings within 20-years. A four-inch high curb is required around all tree’s planters. The tree planters should also be planted with colorful plants.
(3) Plant Materials. Landscaping shall be provided in parking lots, plazas, and in containers, pots, window boxes, and in street lighting flower baskets. In residential districts, a common palette of landscaping such as low-flowering plants is recommended for the eight-foot wide planter area between the curb and sidewalk. A judicious selection of plants includes consideration of site-specific conditions such as shade, wind, moisture, drought tolerance, and soils. All landscaping and irrigation plans within the street rightsof-way shall be prepared by a licensed landscape architect and are subject to the approval of the City Planner and City Engineer prior to installation in accordance with City Standards. (e) Streetlights. Decorative street lighting will create a sense of place, promote Traditional Neighborhood Design (TND) and provide a consistent and high-quality appearance throughout the Plan Area. All streetlights, signposts (e.g. for stop signs and other traffic signs, wayfinding signs, etc.) and traffic signal posts and arches shall be black in color. The poles of all streetlights shall also have base treatments that match the design of the fixture. See Appendix E for the specified decorative light standards authorized for the Plan Area. The following design standards and regulations shall also apply:
116
City of Salinas | Final Central Area Specific Plan, November 2020 (1) General Requirements. Street lighting standards (consisting of the fixture, pole, and base treatment) located on interior local and connector streets within the Plan Area shall be decorative, night sky rated, and pedestrian-scaled. A photometric plan shall be required to determine the appropriate spacing to achieve acceptable, reasonable lighting levels in accordance with City standards as approved by the City Engineer. All streetlights shall be LED (see section 4.14 (e) forfurther discussion). The decorative street lighting standards shall be a maximum height of 20 feet to the light source (maximum height of 25 feet including the pole) except as otherwise provided in this Specific Plan. The southerly and northerly greenway streets will have the same decorative streetlight standards along the length of these streets. These same decorative streetlights will also be used on these same streets as they extend into the adjacent specific plan areas.
(2) Arterial Streets. Street lighting standards along the exterior arterial streets, (e.g. Boronda Road and Natividad Road) will be the standard City “Cobra Head” light fixtures (except these standards will be black in color as described below) which relate to both vehicles and pedestrians at the edge of street, and shall be a maximum of 30-feet in height (including the pole and fixture) and spaced farther apart than those on local and connector streets within the Plan Area as approved by the City Engineer in accordance with City Standards.Arterial street lighting standards, traffic signal standards and appurtenant equipment as well as the poles of traffic signs shall also be black in color.
(3) Placement. To the extent feasible, street lighting standards shall be placed on both sides of the street in a triangulated pattern, except in the Village Center where fixtures may be placed across from each other to create a more formal appearance. In the Village Center the light standards shall be placed 30 inches behind the face of the curb and centered between the street trees. (f) Village Center Main Street, the NG-C district and the Southerly and Northerly Greenway Treatments, as applicable.
(1) Kiosks. Kiosks serve as information centers. Kiosk design for frequent users and visitors shall be complementary to the architectural style of surrounding buildings and shall be black in color.
(2) Newspaper Racks. Newspaper racks and other vending boxes should only occur adjacent to major pedestrian gathering areas.

The design should consolidate all newspaper vending boxes into a single rack. Rack construction should use metal construction that complements other site furnishings in the area or the architecture of adjacent buildings. The rack should be aesthetically attractive on all sides and properly anchored. Individual racks should not be permitted. The racks shall be black in color.

Design Standards
117
(3) Bicycle Racks. Bicycle racks shall be of durable material and visually subdued. Based on their performance, “wave type,” “loop racks,” and “ribbon bars” are recommended and shall be sized in accordance with City standards. The color of bicycle racks shall be black.
(4) Recycling and Solid Waste Disposal. Throughout the Village Center and NG-C districts (as well along the northerly and southerly greenways, where appropriate), solid waste and recycling receptacles with covers to prevent water from entering and not allowing wind to blow debris, shall be provided for the use of the public. Receptacles shall be metal or other durable materials and painted black. To avoid overflow, receptacles should be sized for at least a thirty-gallon capacity and should be properly anchored.
(5) Street Furnishing Finish. Multiple coats of a powder coating or comparable finish are recommended for durability for all street furnishings. Street furnishings shall be black in color unless an alternative is approved the City Planner.
(6) Raised Landscaping Planters. Raised landscaping planters should be simple in form. Round and square types are typically recommended. The material ofthe planter, itself should be durable and aesthetically attractive. Planters shall have a minimum diameter or dimension of 36-inches. Where planters are called for, group various sizes or raised landscaping planters in clusters to enrich streetscapes and plazas. All plants in such planters shall be on an automatic timed irrigation system.
(7) StreetPavingandFurnishings.Paving,plants,andsite furnishings should help set the character of the Village Center. These features should be consistent with the following recommendations:
(i) Paving. Pervious pavers are recommended in parks, and plazas. Pavers should be durable and of brick, stone, or other materials appropriate to the traditional style of the region. Interlocking pavers should be used to avoid uneven edges. Paving patterns should be simple and be a light color.

Pervious stamped and colored concrete is also an acceptable material. Stamped asphalt shall be avoided.
(ii) Tree Grates. Three-foot square metal tree grates should occur along monolithic sidewalks and in plazas where a wide walking surface is needed. Tree grate openings should be black in color and expandable to accommodate tree growth. (iii)Tree Guards. Tree guards may extend vertically from tree grates to protect trees in highly active areas. To relate to other site furnishings, tree guard bars should be narrow and vertical, and should be attached to the tree grate. Welds 118
City of Salinas | Final Central Area Specific Plan, November 2020 should not be visible. Tree guards should be approximately four feet in height with four-inch spacing between wrought iron pickets and shall be black in color.

4.10 Fencing, Walls, and Hedges
Fences and hedges help define the edges of yards and provide privacy. In the Plan Area, walls and fences are considered background elements that help highlight landscaping and architecture. Only well-designed black wrought iron and white picket non sight-obscuring (maximum four-inch wide pickets spaced a minimum of two inches apart) fences up to thirtysix inches in height are allowed in the front or corner side yard setback.

The following regulations apply to fencing as specified below. Nonresidential fencing shall be in accordance with the Salinas Zoning Code:
(a) Residential Fence Locations.
(1) Side yard fence shall be placed 90° to home and side yard and placed a minimum of four feet back from front building façade, perpendicular to the side of the dwelling unit.
(2) Side yard fences along streets shall be a minimum of five feet from the back of walk and five feet from the home.
(3) Alley fences shall be placed a minimum of one foot behind the face of the garage (minimum 16 feet from the center of the alley).

Alley fencing shall not obstruct visibility or the turning radius within the alley as determined by the City Engineer.
(b) Residential Fence Height.
(1) Fences and hedges in the rear and side yards may not exceed six feet in height.
(2) Maximum three-foot high fences are allowed in the front and corner side yards and along the first four feet of the sides of the dwelling. Exceptions to fence height for gates, entry arbors, and similar features shall be in accordance with Section 37-50.090(f)of the Salinas Zoning Code.
(c) Noise Mitigation. Noise mitigation is discussed in the Central Area Specific Plan EIR and MMRP. Sounds Walls shall be provided as required in the MMR (see Appendix D).
(d) Master Subdivision Wall Plan. A Master Subdivision Wall Plan (for the walls along the perimeter of the plan area) shall be approved by the City Planner and City Engineer prior to recordation of the Final Map for each subdivision. The Master Subdivision Wall Plan (once approved) shall be added to Appendix P of the Specific Plan. All walls abutting the surrounding Plan arterial streets shall be the same design, materials and color.

Design Standards
119
(e) Master Wall and Fencing Plan. A master wall and fencing plan shall be submitted to the Community Development Department for approval by the City Planner prior to construction of any wall or fences located on individual lots within the interior of each subdivision. Upon approval the master fence and wall plan establishing the fencing and walls (including the design, colors and materials) for each subdivision, it will be added to Appendix P.
(f) Visibility. All fences, wall and hedges shall be subject to the driveway and corner visibility requirements of Section 37-50.460 of the Zoning Code.
(g) Acceptable Materials. Side and rear yard privacy fences shall be wrought iron, redwood, cedar, vinyl, plastic-wood composite (e.g., Trex), or masonry (including veneer). Fences in the front yard setback or first four feet of the corner side yard setback may only be threefoot-high white non-sight obscuring pickets or black wrought iron. (h) Prohibited Fences. Chain link, barbed wire, razor, or electrified fencing is prohibited in the Plan Area. Black vinyl chain-link fencing is permitted for school and park fencing.

4.11 Utilities
(a) Utility facilities in the Plan area such as water wells, storage, water treatment and above ground conveyance facilities (e.g. booster and pumping stations), the PG&E substation and other non-residential above ground utility facilities shall be designed to be compatible with the surrounding neighborhood. Buildings and associated site improvements shall be designed to complement the surrounding neighborhood. Large landscaped buffers, decorative walls, or other buffering techniques, as appropriate, shall be used to ensure such facilities do not unnecessarily adversely impact adjacent uses. Such facilities shall be subject to approval of a CUP in accordance with the Zoning Code to ensure compatibility with adjacent uses and with Table 3 1 Use Classification and Table 3 2 Development Regulations of the Specific Plan. This CUP process will include the review and approval of details on the decorative masonry screen walls (minimum 8 feet in height), landscaping, noise attenuation, use of hazardous materials, if any, and drainage details (including water flows in the event of the malfunction of the well or treatment facility) and other architectural features to blend with and ensure compatibility with surrounding development. Minimum required setbacks will be maintained between infiltration features/practices and water wells in accordance with the City’s Stormwater Development Standards (SWDS), Table 1 of the City of Salinas SWDS. All utilities shall comply with the City’s current NPDES permit.
(b) The operators/property owners of such facilities shall be required (as a condition of approval) to provide regular maintenance for the life of such facilities (e.g., regular watering and care of vegetation 120
City of Salinas | Final Central Area Specific Plan, November 2020 (including replacement of any dead plant material or broken irrigation apparatus), trash and graffiti removal, and repair and replacement of any damaged or worn-out facilities within five working days or as otherwise approved by the City.

4.12 Landscaping
(a) Concept. Oneofthemajordrivingcriteriaforallaspectsofthelandscape design is selecting and using materials in a thoughtful and sustainable manner. The land use plan establishes a vibrant community that integrates living and working environments,recreation opportunities, open space and circulation and infrastructure. The arrangement of the uses on the land is a direct response to the site topography and landform, and site environmental factors.

The neighborhoods, retail and commercial centers, recreation and work environments are all linked together by an extensive network of pedestrian and bicycle paths along pedestrian and bike friendly slower speed streets, together creating an inviting and viable alternative to driving.

The desire to create a community in accordance with green building principles influences the decisions regarding the landscape design.

The selection of construction materials, planting, and irrigation design are also influenced by the need to design in response to the climate and environmental conditions present in the City of Salinas.

Plant materials shall have low water requirements and thrive in the coastal conditions present on the site. Extensive use of native species is encouraged, which will reduce water demands and adapt well to the soil and wind conditions in the Central Area. The plant palette will quickly establish the community as an integral part of Salinas, yielding benefits in terms of visual quality and biological integration.

All landscaping and irrigation in the Specific Plan Area shall comply with the State’s Model Water Efficient Landscape Ordinance, City’s Water Conservation Ordinance (Chapter 36A of the Municipal Code), Salinas Zoning Code Landscaping and Irrigation requirements, and the City’s SWDS (in regard to plant material for LID and similar areas) and is subject to the approval of the City Planner and City Engineer.

A biologist/botanist shall prepare the recommendations for riparian corridor plant species for the restored creek corridors, subject to approval by the City Engineer and City Planner.
(b) Irrigation Systems. All irrigation is subject to the approval of the City Planner and City Engineer, as applicable in accordance with the Salinas Zoning Code and other applicable Code requirements.

4.13 Green Building Standards
(a) Concept. Green building techniques can enhance the success of a sustainable community. A three-tiered approach to green building design and construction is envisioned for the Central Area. Building designs to consider orientation for solar access.

Design Standards
121
(b) Tier One. The first tier involves the design and construction of highprofile public spaces. Emphasis is placed on public space planning and design that considers the solar exposure (maximizing solar energy potential) to the public spaces. Materials and energy systems that are sustainable should be incorporated where feasible. (c) Tier Two. The second tier involves a commitment to sustainable green building techniques. The technology exists to create buildings that are smarter, more energy efficient, and healthier than those of the past. These technologies are likely to improve over time. Homes and commercial buildings within the Central Area will incorporate many of the available environmentally beneficial building and energy saving techniques. All new single-family homes will be constructed to meet the requirements of the California Building Code including CALGreen based upon applicable building codes at date of building permit submittal for energy efficiency and will, in addition, be equipped with a number of additional green building features. Green building techniques for the Plan Area which shall be included as standard features in all single-family dwellings include:
• Recirculating hot water systems to reduce water consumption. • Dishwashers
• High Efficiency Clothes Washers
• Low-flow Toilets.
• LED or better lighting fixtures.
• Vehicle charging stations and areas in the Village Center and multifamily developments shall be provided. Single-family dwellings shall also be designed to accommodate vehicle charging in garages.
• Multifamily and mixed use projects shall incorporate solar collection for the common area within their project.
(d) Tier Three. The third level involves a series of options provided to the home buyer. These options will include environmentally preferable upgrades that promote the use of recycled content materials, more energy efficient heating systems, which are not otherwise required in conformance with the California Building Code including CALGreen or required as mitigation or other measure incorporated to reduce greenhouse gas emissions. The options will include but are not limited to:
• Countertops of recycled glass, concrete, granite, or other natural bio-based products, etc.
• Floor coverings of bamboo, natural linoleum, salvaged wood, and recycled content carpets.
122
City of Salinas | Final Central Area Specific Plan, November 2020 • Heating, Ventilation, and Cooling (HVAC) system options for higher efficiency equipment.
• Photovoltaic system including an option of battery storage in garage. These shall be placed only on roofs of garages facing landscaped alleys, but not on the portion of the roof of the homes visible from the public streets.
• Low voltage exterior lighting.
• 220 volt wiring in garages and laundry rooms to provide opportunities for charging stations and electric or gas dryer. (e) LED Street Lighting. The street lighting design for the Plan Area shall provide a comfortable level of illumination that meets the community’s needs for use and safety. High efficiency LED “Dark Sky” rated fixtures and sophisticated optics are required to direct light where it is needed without creating excessive glare (see Appendix E for streetlight specifications).

Energy efficient lamps are used to minimize energy use and lamp replacement. The result is that the quantity of fixtures and the total energy required is reduced compared to previous standards. This contributes to a better quality of life, an improved aesthetic, while preserving energy and maintenance resources. All street lighting is subject to the approval of the City Engineer and City Planner in accordance with City Standards and those specific to the Plan Area.

4.14 Architecture

4.14.1 Architectural Standards
This section applies to all buildings (including but not limited to dwellings and accessory structures) within the Plan Area.
(a) Materials. New buildings should support regional traditions and maintain a high level of craft in construction and materials. Exterior finishes should be primarily wood, masonry, and/or stucco. In general, imitation materials should be avoided in favor of genuine materials.

Where this is not practical, materials (cement board siding, artificial stone, vinyl fencing, etc.) should be as close to their original models as possible. The use of renewable and sustainable building materials is encouraged.
(b) Windows. Windows should be vertical (1.62 feet in height by one foot in width is the preferred ratio) versus square or horizontal in shape and be compatible with the building design. Window placement should provide each room with natural light and effective cross-ventilation.

All single story buildings shall provide at least one window that looks out onto the street from a kitchen, living room, or other active room.

Additional windows shall be provided for each floor. This “eyes on the street” measure should make each neighborhood a safer place and provideconnectiontothestreetencouragingneighborhoodinteraction.

Design Standards
123
(c) Trim. Trim should provide architectural interest. Trim should be provided for corners, soffits, the edges of windows and doors, the edge of the roof, and the roof ridge, each with its own distinct type of trim. (1) Trim shall be applied consistently around the exterior of the building appropriate to its architectural style. Additionally, the back of buildings, which directly face arterial streets will have architectural or other decorative elements (e.g. shutters) to enhance their visual appearance as approved by the City Planner. (2) Trim shall be appropriately scaled to the size and style of the building.
(3) Trim shall be three dimensional. Horizontal trim bands should wrap outside corners and only terminate at inside corners. (d) Roofs. The form of the roof is one of the most memorable and characteristic elements of a building and should reflect the slope, type, and material generally associated with the building’s architectural style. The following design requirements apply to roofs:
(1) Keep the overall roof form simple, compact, and complementary to the architectural design (style) of the building.
(2) Provide visual variety with roof forms, overhangs, and shading devices that relate to the solar orientation of a lot.
(3) Roof materials should be appropriate to the architectural style of the building, roof form, and slope. Heavier or more complex roofingmaterials (tile or concrete tiles) shouldbeplacedon simpler roofs. More complex roofs, however, require monolithic, simpler materials (shingles). The allowable materials for roofs include tile, slate, treated wood, concrete tiles, and thicker architectural grade composition shingles. All structures on a lot shall utilize the same roofing materials. Roof flashing, rain gutters, downspouts, vents, and other roof protrusions shall be finished to complement or match the color of the adjacent roofing materials.
(e) Color. Exterior building and roofing colors shall draw from the historical reference of traditional neighborhood design and shall be appropriate to and generally compatible with the architectural style of the dwelling unit. Hue and color variation in exterior color of abutting homes or structures (including roofing materials) shall be provided to create diversity within the neighborhood. In general, unless appropriate to the architectural style of the structure, subdued colors are more appropriate on the body of a structure with bright or bold colors generally limited to architectural details and window and door trim. Garish or overly bold colors should be avoided. All structures on the lot shall have a compatible color scheme. CC& R’s shall include provision for architectural review including colors.
124
City of Salinas | Final Central Area Specific Plan, November 2020 (f) Variation in Structure Design. To reduce monotony, promote variety, and create a sense of place, differences in the massing, composition, color, materials (building and roofing) of dwelling units on each block shall be provided. Each street block shall include a variety of architectural styles, and elevations. The same elevation shall not be repeated more than once every four dwelling units on the same side of the street. The same elevation shall not face itself or be adjacent on the same block.
(g) Accessory Structures. The design of accessory structures shall be compatible with the principal residential structure through the use of complementary architectural style and elements, exterior building and roofing colors and materials, and landscaping.

4.14.2 Architectural Review
The drawings in this Chapter identify examples of some of the residential elevations which will beproposed withinthe CentralArea.All architectural elevations and styles of dwellings, offices, mixed use commercial/office and other buildings, shall be submitted to the City Planner for review and approval. Such elevations may be administratively approved if the City Planner determines that the architectural design/style would be consistent with the Design Standards of the Central Area Specific Plan. A materials and colors sample board for each home shall be submitted and approved by the City Planner as part of the applicable building permit review or development review application process for each residential or nonresidential development proposal.

Remainder of page intentionally left blank
Design Standards
125
This page is intentionally left blank.
126
City of Salinas | Final Central Area Specific Plan, November 2020 This page is intentionally left blank.
127
Design Standards
Figure 4-1: Conceptual Park Map
128
City of Salinas | Final Central Area Specific Plan, November 2020 Figure 4-2: Conceptual Entry Landscaping, Natividad Road at Southerly Greenway 129
Design Standards
Figure 4-3: Conceptual Entry Landscaping , Independence Boulevard & E. Boronda Road 130
City of Salinas | Final Central Area Specific Plan, November 2020 Figure 4-4: Conceptual Entry Landscaping, Village Center & Boronda Road 131
Design Standards
Figure 4-5: Conceptual Park Improvements
132
City of Salinas | Final Central Area Specific Plan, November 2020 Figure 4-6: Conceptual Tower Line Landscaping
133
Final Central Area Specific Plan
November 2020

5. Circulation

5.1 Introduction
This Chapter describes transportation and circulation plans for the Central Area Specific Plan. More specifically, this Chapter includes the following:
• Descriptions of all existing transportation facilities within and surrounding the Plan Area;
• Detailed descriptions of the major on-site and off-site transportation components provided by the specific Plan, including roadways, pedestrian and bicycle facilities, and public transit; and
• Policies, regulations, and design standards applicable to all transportation components; and the methods of achieving trip reduction in the Plan Area.

The Central Area Specific Plan circulation system includes a roadway network, a pedestrian and bicycle network, and public transit. Emphasis is placed on ensuring connectivity between uses and on creating a safe and efficient circulation system that complies with City and/or Specific Plan designs and policies. City street standards adopted for use in development of the North of Boronda FGA (see Chapter 1 for more detail on the North of Boronda FGA of the City) are the basis for street development standards in the Plan Area. However, the plan also emphasizes facilitating increased daily pedestrian trips by connecting 134
City of Salinas | Final Central Area Specific Plan, November 2020 residential neighborhoods to public facilities such as schools and parks, and to retail and employment areas and transit. As such, the street standards for the North of Boronda FGA are supplemented in this Specific Plan with wider sidewalks (herein also referred to as “paths”), landscaped parkways, and other pedestrian-friendly features.

The circulation system has been designed to link with existing City and regional circulation systems. It also provides standards for potential connections to development in the adjacent West Area Specific Plan (adopted but not built) and the future East Area Specific Plan and the extension of existing vehicular, pedestrian, and bicycle circulation systems to the south, west, east, and north. See Figures 5-1 and 5-5 for depictions of the proposed street system. All dimensions shown in figures or described in text for sidewalks, parkways, paths, travel lanes, and other street/pedestrian-related improvements shall constitute the minimum dimension required except as otherwise approved by the City Engineer.

The Salinas General Plan encourages the design, maintenance, and revitalization of residential neighborhoods that enhance quality of life.

In connection with this goal, another General Plan goal is to create a community that promotes a pedestrian-friendly and livable environment.

In accordance with these goals, the Specific Plan proposes an internal street system that encourages pedestrian and bicycle traffic and is integrated with the character of the proposed land uses, while also providing for motor vehicle traffic movement.

The proposed arterial roadways that border or bisect the Plan Area (i.e., Boronda, Russell, and Natividad Roads and Constitution Boulevard) are designed to be generally consistent with the street cross sections identified in the City of Salinas General Plan. The configurations of the proposed internal roadways are based on the anticipated Average Daily Traffic (ADT) and other important circulation planning objectives for the Plan Area (e.g., efficient vehicular movement, walkable neighborhoods, and pedestrian safety). To accommodate the anticipated traffic volumes and meet planning objectives, selected roadways deviate from the City’s standard street cross sections as provided for in the Subdivision Ordinance. The design of these roadways is consistent with the street sections contained in this Chapter.

The roadways entering the Plan Area, such as Hemingway Drive, are designed to handle the ADT generated by vehicles entering and exiting the Specific Plan Area. These roadways feature 12-foot lane widths and bicycle lanes to provide increased safety for bicyclists on these streets.

Traffic calming will also be required to slow traffic and promote bicycle and pedestrian-friendly streets on these and other streets within the Central Area.

Through a collaborative process with the City of Salinas, New Urbanism Street Standards for use in the development of the proposed West, Central, and East Area Specific Plans were established in Ordinance 2463, which created the New Urbanism Districts regulations. The various standard Circulation
135
street sections are linked to daily anticipated traffic levels, so narrower streets and rights-of-way (ROWs) are used where ADT are expected to be relatively low, and wider streets and ROWs are used where traffic levels are anticipated to be higher. With the extensive connectivity proposed in the North of Boronda FGA, it is expected that many local streets will have relatively low traffic volumes. The Central Area Specific Plan includes augmentations to these basic standards to accommodate more pedestrian features. Street sections are named to correspond with the standards described in this Chapter. The greenway streets are customdesigned ROWs for use in particular locations in the Plan Area, and do not closely relate to any of the other North of Boronda FGA street standards.

The use of Specific Plan street sections corresponds to anticipated future traffic levels. Therefore, the location of certain streets and street sections employed may change slightly based on more detailed traffic analysis as approved by the City Engineer.

The overall circulation plan is characterized by an interconnected street network that provides vehicle, bicycle, and pedestrian connectivity throughout the Plan Area and to adjacent existing and future neighborhoods.

5.2 Existing Facilities

5.2.1 Existing Roadway Network
There are currently no public roads within the Plan Area as it is undeveloped and used primarily for agricultural-related uses. However, existing roadways (Boronda Road, Natividad Road and Old Stage Road) border its southern, western and a portion of its northern boundaries. The existing primary roadways serving the project are listed below and shown in Figure 5 4, Existing Arterial Transportation Facilities.

Regional Roadways and Access
U.S. Highway 101
U.S. Highway 101 (herein also referred to as U.S. 101 or Hwy 101) is the major north-south roadway in the Salinas Valley region. It connects Salinas with San Jose and San Francisco to the north and with Los Angeles to the south. U.S. 101 is a four-lane freeway through Salinas, and a four-lane expressway north of the Boronda Road interchange. A major interchange improvement project (Russell Road and Espinosa Road) was recently completed on U.S. 101 and will provide primary regional access to the North of the Boronda FGA (and the Specific Plan) along with the Boronda Road/U.S. 101 interchange.

State Route (SR) 68
State Route (SR) 68 connects to U.S. 101 and provides access to the Monterey Peninsula. It is a four-lane highway between Salinas and the Toro Park area and becomes a two-lane highway from Toro Park to the Monterey Peninsula.
136
City of Salinas | Final Central Area Specific Plan, November 2020 State Route (SR) 156
State Route (SR) 156 runs between U.S. 101 and Highway 1 near Prunedale, providing a connection between Castroville, Salinas and the Monterey Peninsula, and the surrounding area. It is primarily a two-lane highway.

State Route (SR) 183
State Route (SR) 183 is a two-lane highway that also provides regional access to Salinas from Castroville, State Route 156 and Highway 1.

Local Roadways and Access
The following roadways provide local access to the Plan Area:

Boronda Road
Boronda Road is a two- to six-lane arterial road that crosses northern and eastern Salinas. This roadway forms the southern boundary of the Plan Area and connects the Plan Area to U.S. Highway 101 and nearby major retail centers. The City has initiated improvements to Boronda Road (Boronda Road Congestion Relief Project). The first improvement will occur with the West Area Specific Plan build out, which proposes to improve Boronda Road to four lanes between San Juan Grade Road, Dartmouth Way and Independence Boulevard with roundabouts at McKinnon Street, El Dorado Drive, Natividad Road, and Independence Boulevard. The Salinas General Plan proposes to widen Boronda Road to an ultimate condition of six lanes between San Juan Grade Road and Williams Road.

Old Stage Road
Old Stage Road is a two-lane east-west rural roadway that intersects Natividad Road and Williams Road. The Salinas General Plan proposes to widen Old Stage Road to four lanes along a short segment of the easterly portion of the site.

Rogge Road
Rogge Road is a two-lane east-west County designated arterial roadway that connectsNatividadRoad(justnorthofthePlanArea)toSanJuanGrade Road and North Main Street and U.S. Highway 101 further to the west.

Natividad Road
Natividad Road is a two-lane rural road north of Boronda Road which becomes a six-lane divided arterial after crossing Boronda Road to the south. It forms the eastern boundary of the Specific Plan Area. The Salinas General Plan proposes to widen Natividad Road from two to four lanes between Boronda Road and Rogge Road.

Independence Boulevard
Independence Boulevard is a two-lane north-south arterial that extends northerly from Constitution Boulevard along Gabilan Creek to Nantucket Boulevard, widening to a four-lane arterial street from Nantucket Boulevard to Boronda Road. Independence Boulevard is divided by Circulation
137
a raised median. Bicycle lanes are also provided on both sides of the roadway, as well as a sidewalk on the east side of the roadway. The posted speed limit along Independence Boulevard is 35 mph south of the project site. Independence Boulevard will be extended north across the Plan Area as a two-lane divided street on the east side of Gabilan Creek to a future extension of Russell Road.

Constitution Boulevard
Constitution Boulevard is a major north-south four-lane divided arterial with a raised median and left turn channelization. Constitution Boulevard extends from Laurel Drive on the South to Boronda Road on the north.

Sidewalks are provided on both sides of the street. In addition to two travel lanes in each direction, Constitution Boulevard includes a bicycle lane in each direction. The posted speed limit along Constitution Boulevard is 35 mph near the project site. Constitution Boulevard will be extended across the Plan Area site to intersect existing Old Stage Road as a twolane road and will be built out to four-lanes when the West Area Specific Plan develops.

Hemingway Drive
Hemingway Drive is a two-lane north-south road that begins at Fitzgerald Street and extends northerly to Boronda Road. The posted speed limit along Hemingway Drive is 25 mph near the project site. Hemingway Drive will be extended into the CentralArea past the southernmost Village Green to the southerly greenway street.

Williams Road
Williams Road is a four-lane north-south arterial road that transitions to 2-lanes in the vicinity of Boronda Road. Although located east of the Plan Area it provides access (via Boronda Road) to US Highway 101 and other areas located in the eastern portion of the City.

5.3 Planned Circulation Facilities

5.3.1 Circulation and Access Plan
The Salinas General Plan encourages the design of residential neighborhoods that enhance quality of life. Streets must be designed so that trucks, emergency vehicles, transit and automobiles can all safely share this public realm with pedestrians and bicyclists. The proposed vehicular circulation plan aims to slow traffic within the neighborhood while still allowing convenient and safe access to the new neighborhood, as well as provide linkages between the PlanArea and the existing City, see Figure 5-5, Future Arterial and Collector Roads & Vehicular Access Plan.

A number of different street sections are proposed for the Plan Area and are illustrated in Appendix K. All street design sections must incorporate post construction best management practices (PCBMPs) which are discussed in Chapter 7. All street sections and designs within the Plan Area shall be consistent with the Specific Plan and shall be built to City structural standards.
138
City of Salinas | Final Central Area Specific Plan, November 2020 Description Curb to Curb Park Lane
Two-Way
Travel
Lanes
Recommended
Maximum ADT
Local Residential Street 1 32 feet 7’
(both sides) 9’ 1,000
Local Residential Street 2 34 feet 7’
(both sides) 10’ 1,500
Local Residential Street 3 36 feet 7’
(both sides) 11’ 2,000
Local Residential Street 4 28 feet 7’
(both side) 10.5’ 2,000
Collector Street
without Bike Lanes 40 feet 8’(both sides) 12’ 3,000+
Source: Salinas Zoning Code Table 37-30.200
(1) Also See Table 5 2, Street Section Summary and Appendix K (2) The above street standards were field tested by Salinas City Staff including Public Works, Fire and Police were found to slow traffic, therefore are safer and yet still accessible to emergency vehicles.

Table 5-1: Proposed Future Growth Area Street Sections (1)(2) Figure 5-2 illustrates the concept for public transit routes in the Plan Area.

Figure 5-3 illustrates the bicycle circulation and community pathway plan that has been incorporated into the Central Area Specific Plan.

Both internal and external proposed street improvements are designed to accommodate the anticipated number of trips generated by development of the planning area. Consequently, the location and cross-sections of a roadway may be refined based on the traffic study prepared in conjunction with the CEQA analysis for the Specific Plan and any subsequent traffic analysis during the final design and final mapping process of each residential subdivision as approved by the City Traffic Engineer.

The overriding concept of the walkable neighborhood suggests that the safe movement of pedestrians is critical. Visitors, workers, and residents may arrive in the neighborhood in vehicles, but eventually enter the realm of the pedestrian, who moves no more than four miles per hour. Although the street design focus must be on the pedestrian and bicycle, many types of transportation must be accommodated and brought into balance within the proposed neighborhood streetscape. Limited lane widths, two-way traffic, on-street parking, tighter curb radii, narrow street crossings (bulb outs), traffic tables, small scale roundabouts, added stop signs, ample sidewalks, wide landscaped parks strips, homes and businesses facing and adjacent to the street, and minimizing driveways in front yards which interrupt the sidewalk, are all key elements of a walkable, pedestrian-first strategy. These standards were established in the rights-of-way of the Plan area in order to balance out its use by emergency responders, drivers, bicyclists, and pedestrians. In the transition between Village Center and neighborhood edge zones, the ingredients of the street design vary by location to generate a quality of place and a character that varies from place to place within the neighborhood.
139
Circulation
Street Type Type of Street Planter Sidewalk Planter Parking Bike Lane Travel Lanes Median Left Turn Travel Lanes Bike Lane Parking Planter Sidewalk Planter Total Rightof- Way A-1 Residential Alley – garage access both sides 0 0 5 0 10 10 0 5 0 0 30 A-2 Residential Alley – garage access one side 0 0 5 0 10 10 0 5 0 0 30 LS-1 Low Traffic – homes one side, open on other 0 5 8 7 10 10 0 3 Open Space 43 LS-2 Low Traffic – homes on both sides 0 5 8 7 10 10 7 8 5 0 60 LS-3 Low Traffic – school one side, homes other side 0 10 0 8 11 11 8 8 5 0 61 C-1 Southerly Greenway – Med. Traffic, school/homes 0 12 8 8 12 12 8 8 5 0 73 C-2 Northerly Greenway – Med. Traffic, homes/school 0 5 8 8 12 12 8 8 8 0 69 C-3 Southerly Greenway Entrance to CASP 0 12 8 8 12 22 12 8 8 5 0 95 C-4 Independence Blvd. Gabilan Creek 8 0 6 12 22 12 6 8 8 5 0 82 MS-1 Medium Traffic – Homes one side 0 5 8 8 11 11 0 3 0 0 46 MS-2 Medium Traffic – Homes both sides 0 5 8 8 11 11 8 8 5 0 64 VC-1 Village Center Street Mixed Use One Side 0 15 0 8 26 236 One way street around park 334 VC-2 Village Center Street Mixed Use Both Sides 0 15 0 20 12 12 20 0 15 0 94 ART-1 Russell Road (Interim west end) 138’ Agricultural Easement 6 12 12 6 8 10 8 0 200 ART-1 GPB Russell Road @ General Plan Buildout (west end) 44’ A.E. 8 10 8 6 24 22 24 6 8 10 8 0 200 ART-2 Russell Road (interim east end) 138’ Agricultural Easement 6 12 12 6 8 10 8 0 200 ART-2 GPB Russell Road @ General Plan Building (east end) 44’ A.E. 8 10 8 6 24 44 24 6 8 10 8 0 200 ART-3 Old State Road – existing county road 0 0 14 0 6 16 16 0 0 14 0 0 60 ART-3 GPB Old Stage Road (General Plan Building) 0 8 40 0 6 24 22 24 6 0 10 0 0 140 ART-4 Constitution Blvd (GPB – homes west side) 0 8 10 8 6 24 22 24 6 0 10 8 10 136 ART-4 Constitution Blvd (GPB – open space both sides) 0 8 10 0 6 24 22 24 6 0 20 8 0 118 ART-5 Boronda Road (General Plan Buildout) 10 8 10 0 6 36 22 36 6 0 0 8 2 144 ART-6 Natividad Road – General Plan Buildout 8 8 8 0 6 24 22 24 6 0 8 8 8 130 Table 5-2: Street Section Summary – All Street Sections are subject to the approval of the City Traffic Engineer. 140
City of Salinas | Final Central Area Specific Plan, November 2020 This page is intentionally left blank.

Circulation
141

5.4 Traffic Calming
The design of an interconnected street network must include provisions to discourage fast through-traffic on neighborhood connector and local streets.

Intersection treatments (i.e. bulb outs) shall be provided at intersections located adjacent to schools and parks to limit street crossing distances, calm traffic, and enhance pedestrian/bicycle safety. While consideration must always be given to specific demands and conditions (e.g., traffic volume, proximity to larger roads, turning movements, special vehicle needs, and intersection spacing),
Recommended traffic calming measures on connecting and local streets may include:
(1) Appropriate Street Widths. Street widths should be narrow (as proposed in the Specific Plan) to slow traffic while accommodating the estimated traffic demand (ADT) at a reduced speed and providing adequate emergency vehicle access.
(2) Traffic Circles. Where needed to slow traffic, small traffic circles may be placed at the center of intersections along the southerly greenway street, subjectto approval by the CityEngineer.These islands shall be landscaped and maintained to avoid obstructing drivers’ views. Small traffic circles function most efficiently when they are used without stop signs. (3) Median Islands. These islands are installed in the center of a street, and can serve to narrow and redirect traffic lanes, manage traffic movements, and provide a pedestrian crossing island by providing a safe area to pause in mid-street and provide opportunities for PCBMPs . (4) Bulb-outs, Textured Crosswalks and Raised Intersections. These features can be used singly or in combination with other features. Bulbouts with tight curb radius slow traffic and reduce pedestrian crossing distances by narrowing the curb-to-curb dimension of the street, either at an intersection or mid-block and provide opportunities for siting PCBMPs. Bulb-outs are typically created by eliminating the parking area next to the intersection when a turn lane is not needed. Crosswalks can be textured by means of special pavers or other treatment, to alert drivers to the presence of pedestrians.
(5) Curved Streets. A curved street reduces the distance a driver can see ahead, and studies show drivers reduce their speed when curved streets are used in combination with other traffic calming measures. (6) Lined Streets. Parked cars and a formal street tree planting (located in a minimum 8-foot wide planter) between the sidewalk and curb and in planted bulb outs, creates the feeling of a narrower street leading drivers to reduce their speed.
(7) “T” Intersections. Road alignments are generally offset at least 150 feet, forcing turning movements. If carefully sited, “T” intersections can also create prominent vistas to parks and civic features.

Example of a Traffic Circle
Example of Knockouts or
Bulb-outs
Example of Textured Crosswalk.

A combination of techniques
may be used in areas of heavy
pedestrians or bicyclist traffic to
effectively “tame” traffic.
142
City of Salinas | Final Central Area Specific Plan, November 2020 (8) Prohibited Traffic Calming Measures. Traffic-calming measures not permitted in the Plan Area include the following:
(A) Speed Bumps. Speed bumps traverse travel lanes with raised strips that are typically three to fourinches high. The need for speed bumps is symptomatic of excessively wide road designs. While offering a method for slowing traffic within pre-existing conditions, other methods for slowing traffic should be employed on new streets. (B) Cul-de-sacs, Loop Streets, Street Closures and Forced Turns.

Using cul-de-sacs, loop streets, street closures, permanent barriers and diverters work against the creation of an interconnected street network, which is inconsistent with the Specific Plan and the General Plan and shall not be used.

5.5 Public Transit
The largest public transit provider in Monterey County is Monterey-Salinas Transit (MST). MST operates from five key transit centers: the Monterey Transit Plaza, Salinas Transit Center, Watsonville Transit Center, Edgewater Transit Exchange in Seaside/Sand City, and Marina Transit Exchange. Each of these centers operates on a time-transfer pulse schedule providing easy connections and quick transfers to multiple routings.

Greyhound Bus Lines, a private company provides bus service throughout the United States and Canada. The bus terminal for the Salinas-Monterey area is located in downtown Salinas. Local service is provided between Salinas and cities northwest in Santa Cruz County, as well as to the Salinas Valley communities. Interregional services are provided from the SalinasMonterey area to every major city in the United States.

Passenger rail transportation is provided in the Salinas area by Amtrak.

Amtrak utilizes the railroad track that enters Monterey County from the north at Watsonville Junction via Castroville to Salinas and the track that continues southward through the Salinas Valley into San Luis Obispo County, and eventually to Los Angeles. An Amtrak station is located in downtown Salinas.

The City and the Transportation Agency for Monterey County (TAMC) are pursuing extending commuter rail service from the San Francisco Bay Area to Salinas. Currently, commuter rail service (Caltrain) terminates in Gilroy in Santa Clara County. In anticipation of such service, the City developed an intermodal transportation center at the existing Amtrak station. The Salinas Rail Extension was certified in the fall of 2006. Extended commuter rail service is anticipated to begin in or after 2020.

5.5.1 Public Transit in the Plan Area
TheNewUrbanismapproachtoplanningtheNorthofBorondaFGAincludes planning for the extension of bus transit into this area. The interconnected street and path systems throughout this area will facilitate access to future transit service.

Example of a “T” Intersection
Circulation
143
MST currently provides limited bus transit service in the vicinity of the project site. Two standard transit routes currently pass by the project site: Routes 45 and 95. All of these routes primarily access the site along either Boronda Road or Natividad Road providing transit service from the northernareas oftheCity to the SalinasTransitCenterlocatedindowntown Salinas. The existing bus stops closest to the Plan Area are located along Independence Boulevard near Nantucket Boulevard and along E. Boronda Road near Natividad Road. These routes operate on weekdays, Saturdays and/or Sundays, and generally have one hour headway.

MST will continue to provide transit services to the project area. Transit access to the Plan Area is currently limited and indirect. The high density apartment and mixed use commercial components of the Village Center districts in the Plan Area will lead to an increased demand for transit in the immediate area. The project applicant has consulted with MST regarding future bus routes and potential bus stop/shelter locations within and surrounding the Plan Area. A letter and diagram outlining the MST approved bus routes and bus stop/shelter locations is been provided in Appendix L. With the addition of the new MST proposed bus routes, it will ensure that transit services are available within a 5-minute walk for 90% of CASP residents. MST-approved new transit routes and stops within and near the project site are also shown on Figure 5 2. MST has reserved the right to modify these routes in the future as deemed appropriate. The design of the bus stops/shelters will conform to the MST standard included in the report MST Designing for Transit and Land Use in Monterey County (Appendix D) or the current standard at the time of development as determined by MST.

5.6 Pedestrian Circulation
The Specific Plan is intended to develop a walkable community by providing accessible and safe movement of pedestrians within the Plan Area and to the adjacent surrounding neighborhoods. Paths (also referred herein as “sidewalks”) will be provided along both sides of all internal and perimeter streets, but not in alleyways. Design of the Village Center will accommodate pedestrian circulation with 15-foot wide sidewalks and safe access routes to all proposed parking areas. Pedestrians will be able to access all buildings and uses within the Project Area. Sidewalks will be a minimum of 5-feet wide in residential areas and 8-feet wide along school and park frontages except for the greenway streets and paths which will be wider. See Street Sections in Appendix K.

A 28-foot wide landscaped greenway promenade (the southerly greenway path) will be located along the entire length of the north side of the southerly greenway street. The southerly greenway promenade will have a share-use path connecting the library, parks, schools, open space, and the Village Center. The path will also extend and connect into the future East Area Specific Plan and the adopted West Area Specific Plan to the east and west of the Plan Area, respectively. Details of the southerly greenway promenade path is further described below.
144
City of Salinas | Final Central Area Specific Plan, November 2020 There will also be other sidewalks located around the perimeter of the Specific Plan with on-street bike lanes and 8-foot wide sidewalks. A 10-foot wide paved class I pedestrian/bicycle path will be included along the tower line easement and a seven-foot-wide sidewalk will be incorporated on the south side of the northerly greenway street. A 10-foot wide all weather (ADA compliant) pedestrian and bicycle path will also be provided to link to existing Natividad Creek pedestrian/bicycle paths south at E. Boronda Road.

The location, design, materials, width, and other features of all paths/ sidewalks shall be subject to the approval of the City Engineer in accordance with City standards and pedestrian needs. At a minimum, all sidewalks and paths shall be ADA-compliant and paved all-weather surfaces (with access ramps and curb returns as required by law and City/State standards) except where otherwise approved by the City Engineer. Appendix K shows the proposed street section for the greenway streets and related path. See Figure 5 3 the plan for bicycle and pedestrian circulation.

5.6.1 Greenways
The greenways refer to two paths/streets. One of the paths (the northerly greenway promenade), is located on the south side of northern collector street (commonly referred to as the “northerly greenway street.”) The other path (also referred to as the southerly greenway path ) is located on the north side of the southern collector street (commonly referred to as the “southerly greenway street”) as shown in the street sections in Appendix K and in Figure 5-3, Bicycle & Pedestrian Circulation. All lots abutting the greenways shall be afforded nonexclusive on-street parking along their frontage and direct pedestrian access. The north side of the southerly greenway street (the southerly greenway promenade) will be improved with the following: an 8-foot landscaped planter as measured from curb face to the edge of the path, a 12-foot, shared-use, paved all-weather (ADA-compliant) path and an 8-foot landscape easement from edge of the path (which is located within a 12-foot building setback area as measured from the street property line) except in the Village Center and along the proposed middle school site frontage, which will have an 18-foot wide path as provided for in the Specific Plan. No fences or buildings may be located within the landscape easement and no buildings may be located within the building setback. The southside of the northerly greenway street will be improved with a 7-foot minimum path and 8-foot landscaped planter between the path and the street curb.

To maintain all-weather (ADA-compliant) paths that are uninterrupted as possible, private driveway access across the two paths is prohibited on both the northerly and southerly greenway streets except in the Village Center where two driveways will be permitted: one driveway between Hemingway Street and the library site and one on the middle school site. Access to alleyways may be allowed in other limited locations across the paths as approved by the City Engineer. Appropriate striping, signage, and design will be utilized to ensure the safety of path users.

The southerly greenway street segment will have special treatments that include custom decorative street lighting (see Appendix E), additional Example of pedestrian-focused
and friendly greenway.

Circulation
145
greenwaypathlighting, streetfurniture (suchasbenches,trashreceptacles), and way-finding directional signage. These special treatments are to be consistent along the greenway segment as it extends through the Plan Area and into the future East Area Specific Plan Area and the adopted West Area Specific Plan as noted above. The northerly greenway street will have the same decorative street lighting (see Appendix E) as that used for the southerly greenway street since this street will also extend the length of the greater North of Boronda FGA.

5.7 Bicycle Circulation
The existing bicycle network in Salinas consists of more than 55 miles of Class I, II, III, and IV bikeways, which cover significant portions of north, south, and east Salinas. The classes of bikeways are as follows:
• Class I—Bike Path. A completely separated ROW for exclusive bicycle and pedestrian traffic with crossflow minimized. • Class II—Bike Lane. A striped lane for one-way bicycle travel on a street or highway. The bike lane typically includes signs placed along the street segment.
• Class III—Bike Route. The bike route provides use of the edge of a street segment shared with motor vehicle and possibly pedestrian traffic. It typically includes signs, but no striping or additional facilities.
• Class IV—Separated Bikeway. Separated bikeways are either on-street on-off-street facilities reserved for use by bicyclists with physicalseparationbetweenthebikewayandvehiculartravellanes.

In 2002, the City adopted the Salinas Bikeways Plan, which proposes additional bicycle lanes throughout the City. Once future improvements are completed in accordance with the Salinas Bikeways Plan, there will be approximately 95 miles of bikeways. A Class I shared use path currently exists adjacent to Natividad Creek and under the PG&E tower lines adjacent to Hemingway Drive. These Class I bike paths along Natividad Creek and underthe PG&E towerline will be extended across and through the Plan Area.

Existing Class II bike lanes will be extended into the Plan Area on Boronda Road, Constitution Boulevard, Independence Boulevard and Natividad Road.

Bike lanes are currently provided along both sides of Boronda Road, Natividad Road, Independence Boulevard, Hemingway Drive and Constitution Boulevard near the project area.

The Specific Plan endeavors to encourage the use of alternative modes of transportation by incorporating bicycle and pedestrian friendly designs through an integrated system of roads, pedestrian paths, and bikeways.

At the buildout of the Plan Area, bike lanes in the east-west direction are Example of a decorative
street lighting.
146
City of Salinas | Final Central Area Specific Plan, November 2020 to be provided along both sides of the future Russell Road and Old Stage Road. In the north-south direction, bike lanes are to be provided along the extensions of Independence Boulevard (0.7 miles) and Constitution Boulevard (1.1 miles). Boronda Road and Natividad Road are to be widened at the buildout of the study project (2.1 miles). These roadways will continue to provide bike lanes along both sides.

As previously noted, the southerly greenway promenade will have a minimum twelve-foot wide paved all-weather surface (ADA compliant) Class I shared use path installed across the entire width of the Plan Area (1.7 miles) and ultimately connect to paths in the greater North of Boronda FGA. Figure 5 3 shows the proposed shared use paths, bike lanes and routes for the Plan Area.

5.8 Circulation Plan Goals, Policies, and
Implementation Measures
The following goals, policies and implementation measures are in addition to those found in the Salinas General Plan and are specific to the Central Area Specific Plan.

Goal 1: Provide on-site circulation system that facilitates mobility and provides for all modes of transportation equally and safely and promotes New Urbanism, “Green Streets” and “Complete Streets” design principles
Circulation Policy 1-1: Provide a system of neighborhood roads that facilitate safe internal circulation.

Implementation Measures

1. The streets in the Plan area have been designed to promote New Urbanism and will incorporate green street (contained in Chapter 7) and complete street design principles and features to promote sustainability and comply with the City’s SWSP, NPDES Permit and the SWDS, and to provide a pedestrian, bicycle and transit friendly environment for residents and others.

At the time of development, project applicants and/or developers shall construct all internal roadways and alleys depicted in the Specific Plan and other applicable types of roadway improvements in accordance with City Standards, to serve the Plan Area as required in Chapter 9 (Public Facility Financing), other City traffic-related requirements, as applicable, the CASP EIR and MMRP, etc. Final street improvement plans shall be subject to review and approval of the City Engineer. All dimensions shown on figures or described in the Specific Plan or other applicable City standard for streets, alleys, sidewalks, parkways, paths, travel lanes, transit improvements and other street/pedestrianrelated improvements shall constitute the minimum dimensions required except as otherwise approved by the City Engineer.

Circulation
147
Circulation Policy 1-2: Traffic should operate at low speeds compatible with pedestrian and bicycle traffic through the use of speed control and traffic calming measures.

Implementation Measures

1. At the time of development, project applicants and/or developers shall build streets in accordance with street sections included in Table 5-1 and incorporate appropriate traffic calming as approved by the City Engineer.

Circulation Policy 1-3: Provide access to transit.

Implementation Measure

1. Ensure that future residents, employees and visitors can access via public transit. The Specific Plan shall be developed consistent with the Figure 5-2, Conceptual Public Transit Route Map or as otherwise requiredbyMST.Atthe time ofdevelopment, project applicants and/or developers shall consult with MST and TAMC to confirm the locations and types of required Plan Area project-wide transit improvements or other improvements, bus stop locations and spacing, pullouts and shelter design, signage, etc. Project applicants and/or developers shall prepare improvement plans that specify the required transit improvements. Project applicants and/or developers shall implement the plan for their respective phases or projects. Improvement plans (with the required transit improvements) for all individual phases or projects shall be subject to review and approval by the City Engineer and Salinas Permit Center.

Circulation Policy 1-4: Provide shade and landscaping on all streets and surface parking lots to improve pedestrian movement, calm traffic, improve project aesthetics and address urban heat island effects.

Implementation Measures

1. As a part of each improvement plan set, the project applicant and/or developer shall prepare a street tree planting and landscaping plan for all streets and alleys that describes tree spacing, landscaping, installation, and irrigation standards/improvements and post construction best management practices (PCBMPs). Sycamore, maple, elm, Monterey cypress, or similar large fast growing and deeprooted tree species shall be used for street trees subject to approval by the City Planner and City Engineer. The Plan shall be consistent with Specific Plan and 2013 (or current) Storm Water Development Standards (SWDS) Appendix C for PCBMPs standards and City landscaping, irrigation, and street tree requirements, and shall be subject to approval of the City Planner and City Engineer. Each project applicant and/or developer shall be responsible for financing and constructing improvements on the street and alley serving each block prior to approval of any occupancy permit on that block, except the planter, street trees, sidewalk and landscaping in front of the 148
City of Salinas | Final Central Area Specific Plan, November 2020 incomplete home may be delayed until the home nears completion, provided sufficient construction PCBMPs are installed and the delay is approved by the City Engineer.

Circulation Policy 1-5: Encourage pedestrian circulation by providing adequate width sidewalks (including minimum 8-foot wide landscape planters between the edge of curb and the sidewalk) as provided for in the Specific Plan and as approved by the City Engineer that connect neighborhoods, parks, recreation trails and facilities, mixed use commercial areas, and transit stops.

Implementation Measures

1. Project applicants and/or developers shall construct minimum 5-foot sidewalks (or as otherwise specified in the Specific Plan) and shall be separated from vehicular traffic (by a minimum 8-foot wide landscape planter) on all streets containing sidewalks consistent with the crosssection specifications shown in Appendix K.

2. Crosswalks, where required by the City Planner and the City Engineer, shall be white or yellow striped and surfaced with ½ inch raised red brick or pavers (rose color) between the stripes as approved by the City Engineer. Ladder striping or other related striping may be required where crosswalks are near or directly serve parks and schools. The City Engineer shall review the developer’s circulation and subdivision improvement plans to ensure this feature is included, prior to approval of the improvement plans.

3. Pedestrian seating and trash receptacles (black in color) shall be provided at a minimum in all parks, every one-quarter mile maximum along promenades and the greenways, on each block within the Village Center and at all transit stops/shelters as approved by the City Engineer.

4. Streets, paths/sidewalks, and promenades (but not creek-side paths unless otherwise required by the Police Department and City Engineer) shall have nighttime lighting that meets the City’s minimum illumination standards as determined by the City Engineer.

Spacing of the pedestrian and street lighting will depend on the following factors: photometric plan of the specific LED luminaire; luminaire’s mounting height: roadway width; and type of roadway surfacing: per recommendations by the Illuminating Engineering Society of North America (IESNA) PR-8-00.

Photometric plans and LEDluminaire specifications shall be submitted to the City Engineer for review and approval prior to installation of any street lighting.

Decorative street lighting fixtures and lighting design will be provided to create a sense of place, promote Traditional Neighborhood Development (TND) and Crime Prevention Through Environmental Circulation
149
Design (CPTED) principles and create pedestrian-friendly streetscapes in the Specific Plan and greater North of Boronda FGA.

All street lighting shall be consistent with Specific Plan (see Chapter 4, the Appendix and other applicable City standards). The City Engineer and City Planner shall review the developer’s improvement plans for consistency with these lighting standards prior to approval of any subdivision improvements, Development Review Application or building permit, as applicable.

Circ Policy 1-6: Encourage use of bicycles for internal trips and transit for local trips.

Implementation Measures

1. The developer shall include travel lanes in conformance with the street cross-section specifications and standards shown in Appendix K.

Deviations in lane width is subject to the approval of the City Engineer.

2. The developer shall ensure that every park/recreation facility, mixed use commercial, and office use shall conform to the City’s standard requirements for total number of required bicycle parking spaces.

Bicycle racks and accessible and multi passenger vehicle spaces shall be located near building entrances, if feasible. Future individual applications are encouraged to consider accommodating emerging trends at the time of submittal including but not limited to, bike share facilities. This requirement shall be reflected on improvement plans and be subject to review and approval of the City Engineer and City Planner prior to approval of any Development Review Application or building permit, as applicable.

Remainder of page intentionally left blank
150
City of Salinas | Final Central Area Specific Plan, November 2020 This page is intentionally left blank.
151
Circulation
Figure 5-1: Street Key
152
City of Salinas | Final Central Area Specific Plan, November 2020 Figure 5-2: Conceptual Public Transit Route Map
153
Circulation
Figure 5-3: Bicycle & Pedestrian Circulation
154
City of Salinas | Final Central Area Specific Plan, November 2020 Figure 5-4: Existing Arterial Transportation Facilities 155
Circulation
Figure 5-5: Future Arterial and Collector Roads & Vehicular Access Plan 156
City of Salinas | Final Central Area Specific Plan, November 2020 This page is intentionally left blank.
157
Final Central Area Specific Plan
November 2020

6. Infrastructure Plans

6.1 Introduction
This Chapter describes the existing utilities infrastructure, the required improvements to the existing infrastructure, and the proposed new infrastructure needed to support the development of the Central Area Specific Plan. Based upon input from the City of Salinas and other public and private utility providers. The development of the Plan Area will require the extension of public infrastructure to serve the future neighborhoods. For the purpose of this Specific Plan, this Chapter will address the following infrastructure:
• Public infrastructure refers to water supply, treatment, and distribution; wastewater (sanitary sewer) collection, treatment, and storage; and grading & drainage.
• Public services refer to services and facilities for schools, parks, public safety (police), fire protection and emergency services, libraries, and public transit (see Chapter 5 for discussion of transit).
• Public utilities refer to electricity, gas, telephone, dark fiber (fiber optic), cable television, and solid waste services. Note:

See Chapter 7, Stormwater, for the discussion of stormwater quality, retention, etc.
158
City of Salinas | Final Central Area Specific Plan, November 2020

6.2 Public Infrastructure

6.2.1 Domestic Water
Water Supply
This section provides an overview of the existing domestic water system pertinent to the proposed Central Area Specific Plan, including municipal drinking water wells, off-site water distribution systems, water treatment facilities and other drinking water supply considerations. It also describes the proposed on-site distribution system to meet potable water demands and fire flow requirements for the Plan Area. The Central Area Specific Plan EIR includes additional information and details regarding this topic.

The followingdocuments were referencedinthepreparationofthis section:

City of Salinas
• City Letter to Cal Water & ALCO RE: FGA Water Supply
(Sept. 22, 2006)
• North Future Growth Area Water System Study by P&D
Consultants (July 6, 2007 & August 20, 2007)
Cal Water
• Can and Will Serve Letters for the Western Half of the Central Specific Growth Area. California Water Service Company. (October 31, 2014 and July 30, 2019)
• 2015 Urban Water Management Plan and Appendices
• Water Supply Assessment for West, Central, and East Specific Plan Areas (August 16, 2007)
• Email to City Staff confirming the continued validity of the WSA/Can and Will Serve Letter (March 26, 2020 from Brenda Granillo, Cal Water)
• SB610 Water Supply Assessment for the Central Area Specific Plan (December 2014)
• SB610 Water Supply Assessment for the West Area Specific Plan (Dec. 15, 2015)
ALCO Water Service
• Can and Will Serve Letters for Central Future Growth Area, Alisal Water Corporation (February 10, 2014 and March 27, 2020) • Water Service Assessment [August 2007]
• Water Service Assessment (ALCO WSA) (October 2014)
• ALCO Letter from Robert T. Adcock discussing the Boronda Water Mains [July 6, 2007]
Example of a water well facility
designed to be compatible with
surrounding development.

Infrastructure Plans
159
The City of Salinas employed P&D Consultants to conduct a water system study forthe entire northern Future Growth Area. The results of this study are contained in the “City of Salinas North Future Growth Area Water System Study” report dated August 20, 2007. This report identified the onsite water facilities necessary to develop the North Future Growth Area for the City’s Sphere of Influence Amendment and Annexation process.

The conceptual unit count used in the P&D study is higher than the Specific Plan unit count. Therefore, the following water demands replace the preliminary water demands developed in the P&D Consultants study.

Water Purveyors
Salinas receives all its potable drinking water from wells. There are two residential water purveyors within the City of Salinas: Alisal Water Corporation (ALCO); and California Water Service Company (Cal Water). Much of the groundwater in the Salinas area, including the East Side Aquifer Subarea, is generated through recharge of the basin via the Salinas River. There are no other water supply sources in the area and water imports across regional boundaries are not financially or practically feasible at this time.

The preparation of the Specific Plan includes review and discussion with the City regarding the Salinas General Plan and its certified FEIR.

Discussions were also held with ALCO and Cal Water to identify specific future on-site and off-site water supply and distribution facilities. The preparation of this Specific Plan also included review of the requirements of the Salinas Urban Water Allocation Plan (City Council Resolution No. 15077). This allocation plan addressed water consumption from 1993 through 1996, requiring a 15% reduction from the 1987 consumption levels. The allocation plan accounted for conversion from agricultural to residential at 85% of the allowable pumping limit, and crediting for wastewater reclamation as well.

The current division of service areas splits the Plan Area in half along the PG&E towerline withALCOserving the eastern half and CalWater serving the western half. Table 6 1 shows the existing and conceptual facilities for Cal Water and ALCO. Both ALCO and Cal Water have produced Water Service Assessments (WSA) per the requirements of Senate Bill 610 and have issued will-serve letters for the project, which are on file at the City of Salinas Community Development Department.

ALCO Service Area
Alisal Water Corporation (dbaALCO Water Service) will provide domestic water service to the eastern half of the CentralArea, as shown in Figure 6 2.

ALCO draws all its water from the Salinas Valley Groundwater Basin, and more specifically the East Side Aquifer. As of the writing of this Specific Plan, ALCO has eleven wells dispersed throughout the Salinas service area; six are active, three are on standby due to water quality reasons, and two are drilled but not yet in service. ALCO has installed a 30 inch water main parallel to an existing 18 inch water main that runs through the center of the Plan Area, adjacent to the existing tower line easement. 160
City of Salinas | Final Central Area Specific Plan, November 2020 ALCO has approximately 205,000 gallons of existing storage, which is not adequate for peak hour and fire flow demands in the Plan Area.

However, ALCO has designated a new five-million-gallon storage tank for future construction to provide additional capacity during periods of high demand. The location is to be determined at a future date. It is anticipated that this 5-million-gallon storage tank will be installed once the Plan Area begins to develop. ALCO states in their October 2014 WSA they would be able to provide service to the entire Central and Eastern Future Growth Areas and their existing customers with the planned system upgrades. As previously indicated, ALCO has provided a “Can and Will Serve” letter dated February 10, 2014 and again on March 27, 2020 for the Plan Area. Refer to the CASP EIR for additional details with regard to water supply.

Cal Water Service Area
Cal Water will provide domestic water service to the western half of the Plan Area, see Figure 6 3 for the proposed domestic water distribution layout. Cal Water draws all of its water from the Salinas Valley Groundwater Basin, from two hydraulically connected sub-basins known as the East Side Aquifer and the western fluvial or pressure zone. Per the West Area Specific Plan SB610 Water Supply Assessment by California Water Service Salinas District, “a total of 28 wells supply the City of Salinas service area. The design capacity of active operations wells is 27,880 gallons per minute (gpm) or 40 million gallons per day (mgd) . . . of water”. In addition, Cal Water has three new wells being constructed. The capacity of these wells are anticipated to range from 500 to 2,000 gpm with an average design capacity of 1,200 gpm, for a total of 5.18 mgd additional water supply. Cal Water has been experiencing elevated levels of nitrates and volatile organic compounds (VOCs) in some of their supply wells. They have installed treatment facilities where practical and shut down wells where necessary to combat the problem.

They have also implemented monitoring programs at all their wells to aid in future water quality planning. Cal Water states in their December 2014 WSA they would be able to provide service to the entire North of Boronda FGA and their existing customers with the planned system upgrades which was confirmed to remain valid as of March 26, 2020 (email from Brenda Granillo, Cal Water). As previously indicated, Cal Water also issued a will-serve letter for the project on October 31, 2014 and again on July 30, 2019 both of which are on file at the City of Salinas Community Development Department.

Cal Water and ALCO Water Systems
The proposed distribution systems for the Plan Area consists of pipes ranging in size from 8-inch to 18-inch compliant with the American Water Works Association (AWWA) C900 or C905 PVC or high-density polyethylene (HDPE) pipe. It is expected that no ductile iron or steel pipe will be used due to highly corrosive onsite soils. Both distribution systems will be designed to meet following criteria:

Infrastructure Plans
161
• Minimum pressure during fire flow plus maximum daily demand = 20 pounds per square inch (psi).
• Minimum pressure during peak hour demand = 40 psi.
• Maximum desirable pressure = 80 psi.
• Residential fire flow = 1,500 gpm for duration of two hours. • Commercial fire flow = 2,500 gpm for duration of two hours. • Maximum desirable velocity 8 ft/s
• Maximum desirable head loss 10 ft per 1,000 feet.

Additionally, fire flows for buildings or portions of buildings and facilities shall be based on California Fire Code, Appendix B or the standard published by the Insurance Services Office latest edition of the “Guide for Determination of Required Fire Flow.” Verification that the water system meets requirements must be provided from the jurisdiction water utility company prior to any permit being issued.

Conditional Use Permit Required
Any of the wells, treatment, or other above ground conveyance facilities (including booster or pump stations) within either the Cal Water or ALCO Water District will be subject to approval of a Conditional Use Permit (CUP) through the City priorto installation. This CUP process will include, but not be limited to the review and approval of details for the decorative screening walls (8-foot minimum masonry walls or as otherwise required by the City Planner), landscaping, noise attenuation features, storage and use of hazardous materials, if any, drainage details (including water flows in the event of the malfunction of the applicable facility) and architectural features incorporated into the design of the applicable facility to ensure compatibility with and complement the surrounding built environment and land uses.

ALCO Water System
The existing nearby ALCO distribution system consists of the following pipes:
• 30-inch main and parallel 18-inch main running parallel to the PG&E electrical transmission towers and easement, west of Hemingway Drive.
• 12-inch main in Hemingway Drive running south
from Boronda Road.
• 12-inch main in Boronda Road from Hemingway Drive to
Constitution Boulevard.
• 12-inch main in Boronda Road running east from
Constitution Boulevard.
162
City of Salinas | Final Central Area Specific Plan, November 2020 • 12-inch main in Constitution Boulevard running south
from Boronda Road.

ALCO anticipates the need for two new booster pumping stations along the 30-inch main since they do not have a water supply source close to the site. As previously noted above, approval of a Conditional Use Permit will be required for all well and pumping station facilities within the Plan Area. These facilities will be designed to blend with adjacent uses through the use of architectural features and landscaping and will be screened by a masonry wall that is a minimum of 8-feet high. The final location and design are subject to the approval of the City Engineer and City Planner.

The conceptual locations for the stations are shown on Figure 6 2. The final locations for these facilities will be determined as part of the tentative map(s) process.

The 2014 ALCO WSA states: “. . . ALCO plans to construct a 5 milliongallon (MG) water storage tank at an elevation that will adequately provide pressure to its existing system and additional capacity for the future demand.” The ALCO report further states that developers are required to pay for all water system facility improvements necessary to provide water service to their projects. However, in the case of the 5MG reservoir, the WSA states: “The water utility, however, does finance the water system facilities and improvements for its existing water users. In the case of the 5MG storage reservoir, it will be built and paid for by the utility.” Project Water Demand within the ALCO service area is shown in Table 6-1 below.

Year 2005
Actual
2010
Actual 2015 2020 2025 2030 2034
District 1,557 1,498 1,466 1,411 1,411 1,411 1,411
Proposed Project N/A N/A 36 218 400 582 727
Total (2) N/A N/A 1,503 1,629 1,810 1,992 2,137
Source: Alco Water Service Water Service Assessment
(1) MG/Year = Million gallons per year
(2) Totals may not add up due to rounding.

Table 6-1: Projected Water Demand – ALCO Service Area (MG/ Year) (1) Cal Water System
The existing nearby Cal Water distribution system consists of the following pipes:
• 12-inch main in Boronda Road from San Juan Grade Road to Natividad Road.
• 8-inch main in Boronda Road from Independence Boulevard to the tower line west of Hemingway Drive.
• 12-inch main in Independence Drive running south
from Boronda Road.

Infrastructure Plans
163
Cal Water anticipates that two (2) new well sites will be required within the Plan Area to better serve the Future Growth Area. The conceptual location of the wells is shown on Figure 6-3. As previously noted above, approval of a Conditional Use Permit will be required for all well and pumping station facilities within the Plan Area. These facilities will be designed to blend with adjacent uses through the use of architectural features and landscaping and will be screened by a masonry wall that is a minimum of 8-feet high. The final location and design are subject to the approval of the City Engineer and City Planner.

ProjectWater Demand within the CalWater service area are projected to be:

Year 2005
Actual
2010
Actual 2015 2020 2025 2030 2035 2040
District 20,933 16,940 20,053 19,840 21,125 22,504 23,984 25,572 Proposed Project N/A N/A 0 71 249 427 605 605
Total N/A N/A 20,053 19,911 21,374 22,931 24,589 26,177 Source: Cal Water, SB 610 Water Supply Assessment
Notes:
(3) AFY = Acre-feet per year
Table 6-2: Water Demand Estimate– Cal Water Area (AFY)(1) Water Conservation
The developers of the Plan Area will be required to implement a Water Conservation Program that includes the use of low-flow toilets and shower heads, water-efficient dishwasher and washing machines and demandcontrolled irrigation systems on all apartments, mixed-use commercial and public buildings throughout the Plan Area and other measures as may be required by the City and the California Building Code.

Landscape plant materials have been selected that have low water requirements and that thrive in the conditions present on the site. See the appendices for the approved Master Landscaping Plan. Artificial turf may be used for appropriate areas/uses. Extensive use of native species is proposed, which willreduce water demands and adapt well to the soil and wind conditions. This plant palette will quickly establish the community as an integral part of Salinas, yielding benefits in terms of visual quality and biological integration and reducing Urban Warming impacts.

Landscaping for streetscapes, individual parcels and other outdoor areas shall be drought tolerant and utilize irrigation systems (drip/bubbler system where appropriate) that are designed to minimize water delivered to plants. Use of irrigated turf shall be limited in accordance with City and State requirements. Irrigation controls will be state-of-the-art in the public spaces to minimize water usage, such as evapotranspiration-based (ET) irrigation controllers. These provide localized available soil moisture information to control the application of irrigation water to match climatic requirements and plant needs. Evapotranspiration is the combination of the moisture evaporated and transpired by plants as a part of their 164
City of Salinas | Final Central Area Specific Plan, November 2020 metabolic process. The excess runs off or percolates below the root zone.

Significant amounts of water are conserved by irrigating at the rate and schedule required to meet a plant’s needs rather than the typical clock schedules now in common use. ET controllers are available from a variety of suppliers and will be installed in all residential, mixed use, commercial, and public facility applications, including parks. Single-family dwellings may have ET or other timed controls if approved by the City Planner.

A development of this scale provides an excellent opportunity to create irrigation systems for public spaces. Such systems can be managed in a very efficient manner including the use of centralized controllers, onsite weather information, water sensors, efficient emitters/spray nozzles, duration/cycles tailored to the soil and slope of each area.

All landscaping and irrigation in the Specific Plan area shall comply with the City’s Water Conservation Ordinance, Water Efficient Landscape Ordinance, Zoning Code Landscaping and Irrigation requirements and Appendix C of the SWDS for PCBMP related landscaping (in regard to plan materials for LID and similar areas as may be amended from time to time). A biologist and/or botanist shall prepare recommendations for the riparian corridor plant species for restoration corridors and/or natural creeks, inclusive of tributary streams.

6.2.2 Sanitary Sewer
The followingdocuments were referencedinthepreparationofthis section:
• Sanitary Sewer System Master Plan by CDM (August 2011) • North Future Growth Area Sewer System Study by PDM
(July 6, 2007)
• Technical Memorandum Re: Northern Salinas Development Evaluation for Sanitary Sewer from CDM to City of Salinas (January 24, 2007 – attached to P&D 2007 Sewer System Study) • Wastewater Treatment Capacity Analysis - Salinas Future Growth Area Wastewater Treatment Facility by Mark Thomas & Company, Inc. for PDM (July 2007)
This plan establishes policies to help facilitate the final sanitary sewer design to meet the needs of the development. The Plan Area conceptual on-site sanitary sewer layout, Figure 6 4, addresses the sewer needs the Specific Plan development. The City of Salinas provides and maintains their own sewer collection service to the Salinas pumping station located at the southwest limits of the City. The Monterey One Water(M1W) provides wastewatertreatment,recycling, and disposal forthe City of Salinas. M1W also maintains the Salinas Pumping Station and downstream conveyance system to the Regional Treatment Plant.

Infrastructure Plans
165
Sanitary Sewer Generation
Historical Calculations
2006/JULY 2007 P&D STUDY
The City of Salinas retained P&D Consultants to conduct a sewer system study for the entire northern Future Growth Area. The Administrative Draft was dated August 2006. The final results of this study are contained in the “City of Salinas North Future Growth Area Sewer System Study” report dated July 6, 2007. This report identified the onsite sewer facilities necessary to develop the Salinas North Future Growth Area for the City’s Sphere of Influence Amendment and Annexation process.

The total average and peak sewer generations determined by P&D Consultants based on land use assumptions at the time of the report are 1.64 and 2.96 million gallons per day (MGD) respectively for the entire Central Growth Area (Plan Area). Note that these flow projections no longer apply.

JANUARY 2007 CDM TECHNICAL MEMORANDUM (TM):

The City of Salinas hired CDM to conduct an initial evaluation of the impacts the entire North of Boronda Future Growth Area would have on the existing sanitary sewer system for the City’s Sphere of Influence Amendment and Annexation process. The results of this evaluation are presented in the “Northern Salinas Development Evaluation for Sanitary Sewer” Technical Memorandum (TM) dated January 24, 2007. The TM evaluated the flow projections from the P&D 2006 Administrative Draft CDM used the same land use and sewer generation assumptions as P&D Consultants to update the City’s 1998 HYDRA model.

The results of the CDM analysis yielded average and peak sewer generations of 1.96 and 3.54 MGD respectively for the Central Growth Area (Plan Area). The memo concluded that the difference in total flow rate between their and P&D’s calculations was due to the HYDRA model methodology for generating flows vs. previous methods of modeling.

Note that these flow projections no longer apply.

AUGUST 2011 SALINAS SANITARY SEWER MASTER PLAN:

The engineering firm CDM was retained by the City of Salinas to update their Sanitary Sewer Collection Master Study, which was completed and adopted in August 2011 (Sanitary Sewer Master Plan). The Master Plan sets the sewer generation rate by land use along with the required peaking factors, etc. This most recent document is the methodology used to calculate the Plan Area sanitary sewer generation.

CENTRALAREASANITARYSEWERGENERATIONCALCULATIONS:

Utilizing the acreages for each land use set forth in this Specific Plan and the sanitary sewer generation rates established in the 2011 Sanitary Sewer Master Plan, the Projected Sewer Generation for the Plan Area was 166
City of Salinas | Final Central Area Specific Plan, November 2020 calculated. The Central Area is projected to yield an average dry weather flow of 0.83 MGD and a peak wet weather flow of 2.29 MGD, as detailed in Table 6 3 below. The difference between these calculations and the historical calculations are mainly due to two items: a reduction in density in the current Specific Plan, and the use of the new sanitary sewer generation rates and methodology, as established in the 2011 SS Master Plan.

Land Use
Net
Area
(Acres)
Neighborhood
Density
Average
Flow Rate
(gpd)
Wet Weather
Flow (gpd)
Total Flow
(gpd)
Neighborhood Edge
(NE) 208.0 Low 291,214 228,811 520,025
Neighborhood
General (NG) 109.7 Medium 219,320 120,626 339,946
Village Center (VC) 50.5 High/Mixed Use 139,397 55,528 194,925 Public Facilities 60.7 Public 60,650 66,715 127,365
Public Parks 44.0 – 0 0 0
Public Open Space 103.0 – 0 0 0
Average 1.18 mgd
Peak 1.75 mgd
Source: Central Area Specific Plan, Section 6.0.
(4) The following sewer generation rates used are based on the City of Salinas Sanitary Sewer System Master Plan, Prepared by CDM, August 2011:
(5) Commercial/Mixed Use Flow = 1,200 gpd/acre; -Residential – High Density = 3,500 gpd/acre; -Residential – Medium Density = 2,000 gpd/acre; -Residential – Low Density = 1,400 gpd/acre; -Public Facility Flow – 1,000 gpd/acre; -Wet Weather Flow – 1,100 gpd/acre (10-year, 6-hour Design Storm) (6) Unsewered areas (open space, parks) do not contribute base flow to the system, i.e., zero unit flow rates.

Table 6-3: Projected Sewer Generation
Sanitary Sewer Collection and Conveyance
Figure 6-4 shows the conceptual Plan Area onsite sewer system. The sewer system will consist of 8-inch to 12-inch pipes designed in accordance with the City of Salinas design standards at the time of final design. The sewer mains will be located in public streets and private alleys with public service easements. The sewer mains will connect to the existing City of Salinas sewer system at two locations: the 10-inch sewer in Independence Boulevard, and the 18-inch sewer near Constitution Boulevard.

The sewer collection and conveyance system entail a minimum of four creek crossings: one for Gabilan Creek and three for Natividad Creek and its tributaries. These creek crossings may require the use of siphons.

The 2011 City of Salinas Sanitary Sewer System Master Plan analyzed the City collection system including the anticipated flows from the future growth area. Along the portion of the system that carries the flows form the Plan Area, only one improvement is recommended: capacity improvement to the Lake Street Pump Station. In addition, the project will require a sewer main extension from the existing 18-inch main south of Constitution Boulevard extending northerly to the Plan Area, southerly of Hemingway Drive.

Infrastructure Plans
167
Sanitary sewer mainlines shall be designed in accordance with standard engineering practices, the City Sanitary System Master Plan, and the City development standards as may be amended from time to time. Sanitary sewer mains shall be designed to discharge the expected peak flow when the pipe is running full. The pipe grade shall be sufficient to provide a minimum two feet per second flow velocity based on the anticipated peak rate of flow. Sanitary sewer discharges into manholes shall be oriented in the primary direction of flow to improve hydraulics, and minimize turbulence in manholes, pipes, or related structures.

A registered civil engineer in the State of California shall oversee the calculations (stamp and seal calculations) for the proposed sanitary sewer system to ensure it is designed to operate acceptably, without leading to surcharge. The backbone sanitary sewer system shall connect to the system south of E. Boronda Road, as identified in the City’s Sanitary Sewer Master Plan.

6.2.3 Grading & Drainage
Existing Topography
The Plan Area is currently undeveloped agricultural land consisting of row crop and orchard agriculture. Two creeks cross through the site:

Gabilan Creek to the west and Natividad Creek to the east. Natividad Creek has three tributaries that connect onsite and continue south.

The bluffs vary from approximately five feet to 30 feet above the creek floodplains. The bluffs slopes range between 20:1 and 4:1 (horizontal to vertical). However, the actual creek banks do experience slopes steeper than 4:1 in some instances. A 25-foot-high terrace near the middle of the Plan Area divides the two drainage basins. The site generally slopes from a northerly to southerly direction towards Boronda Road. The overall topographic relief is approximately 76-feet, with a maximum elevation of approximately 146-feet above sea level at the northeast corner on Old Stage Road, and a minimum elevation of approximately 70-feet above sea level in Natividad Creek at the Boronda Road crossing. Figure 6 5 shows the general topography across the Plan Area.

Existing Drainage
The existing drainage basins for the Plan Area were established using design-level aerial topography. Two creeks flow through the site from north to south: Gabilan Creek on the west and Natividad Creek on the east. The total onsite area tributary is approximately 290 acres to Gabilan and 449 acres to Natividad. Natividad Creek culvert crossings exist at Old Stage Road, Boronda Road, and nine agricultural roads. Gabilan Creek culvert crossings exist atBorondaRoadandtwo agriculturalroads.The two creeks continue south under Boronda Road and confluence at Carr Lake.

Carr Lake drains into the Reclamation Ditch No. 1665, which continues west, draining into Old Salinas River and, ultimately, Monterey Bay.

Gabilan Creek and Natividad Creek are designated as areas of one percent chance annual flood by the Federal Emergency Management 168
City of Salinas | Final Central Area Specific Plan, November 2020 Agency (FEMA) Flood Insurance Rate Maps (FIRMs) (Gabilan Creek is located in Flood Zone AE, and Natividad Creek is located in Flood Zone A, Flood Insurance Rate Map (FIRM) panels 06053C0226G, 06053C0228G, and 06053C0230G.). A FEMA map revision will be required to adjust the boundaries oftheAflooddesignationpriorto anydevelopmentin theflood zone. The remainder of the site is located in shaded or unshaded Zone X.

Federal Emergency Management Agency (FEMA) Flood Insurance Rate Maps (FIRM) and FEMA FIRM Panel Numbers are shown in Figure 6 6, FEMA Flood Zones. Since grading operations are planned within the existing flood zone as part of the creek restoration plan, further hydraulic studies and potential FEMA map revisions will be needed to ensure base flood elevations do not increase as a result of the proposed development to provide accurate Base Flood Elevations (BFEs) so structure and appurtenant serving utilities can be raised/floodproofed in accordance with the City’s Flood Plain Management Regulations.

The Rezone application associated with the Central Area Specific Plan will include extending the Salinas Flood (F) Overlay District into the Plan Area.

Proposed Grading
The preliminary grading plan for the Plan Area was created to provide a developable site while minimizing the quantity of earth moved, achieving a balanced earthwork condition, and maintaining existing drainage areas and positive overland release to the existing creeks. The existing topography varies greatly across the site as expressed above.

Development and street profile constraints require considerable cuts and fills at the transition slopes between the existing bluffs and at the creek enhancement corridor boundaries. Grading shall conform to the City’s Erosion and Grading Control Ordinance as may be amended.

Grading Plans shall be submitted to the City for review and approval prior to construction. Final grading plans shall include tie-in grading to existing improvements, as necessary. Flow lines in gutters shall have a minimum slope of 0.3%, and a maximum slope of 5%. Grading plans will generally show items such as the building envelope, proposed/existing contours and top of curb or centerline elevations throughout the development area, finished pad and finished floor elevations, and the interface of these site development grades with adjacent properties and other information as may be required by the City Engineer. Low impact development (LID) strategies shall comply with the City’s NPDES permit and SWDS requirements.

Final grading plans shall minimize grade differentials to the greatest degree possible, retain natural drainage patterns to the greatest extent possible, and keep the use of retaining walls to a minimum. Where retaining walls cannot be avoided and are 2-feet and higher, the walls shall be constructed of concrete, brick, or similar durable materials, approved by the Building Official and City Engineer. A soils report shall be prepared to address design requirements and compliance with NPDES parcel-scale development requirements.

Infrastructure Plans
169
Erosion control shall be provided on all site grading. Erosion control shall conform to Resolution No. 10836 (NCS). Applicable NPDES /SWPPP permits will be required and shall be obtained from the State Water Quality Control Board prior to any construction activities, in accordance with EPA regulations. Development shall comply with NPDES requirements in effect when construction begins.

The SWPPP shall include a plan indicating erosion control measures and Construction Best Management Practices (CBMPs) proposed for each subdivision. CBMPs shall include, but are not limited to: fiber rolls around the construction site, gravel bags or compost socks at all impacted inlets, rocked construction access to/from the site, agriculture water interceptor ditches and bio-treated runoff before discharging into any system, concrete washout facilities, and basins beneath temporary construction toilets.

Fill may also be required in the floodplain of the creeks to maintain positive overland release and for hydrologic mitigation, as proposed by Pacific Advanced Civil Engineering, Inc. (PACE). Figure 6 7, Conceptual Earthwork Design, shows the conceptual earthwork requirements with approximate maximum cuts and fills of 30-feet and as much as four million cubic yards of earth moved within the Plan Area. The grading plan for the Plan Area will be refined during the final design process to minimize changes to the existing topography to the maximum extent practicable per the requirements of the City of Salinas Development Standards.

The existing topography of the Plan Area slopes towards Gabilan and Natividad Creeks with a high ridge bluff dividing the two drainage areas.

Thecreeksflowfromnorthtosouththroughthesite.Theconceptualgrading plan seeks to maintain the overall drainage basin areas and direction of flow while creating a developable site for the proposed site plan.

In addition, Gabilan and Natividad Creeks have been severely degraded over the years due to farming operations. Grading operations are proposed to take place along these creeks to restore them to a more natural meandering, well-vegetated condition. Grading and restoration activities in creek areas may require the approval of City, State and federal agencies prior to any disturbance of these areas.

The site will conform to existing grades along the perimeter of the project boundary with grading conforms extending as much as 100 feet beyond the project boundary. The conceptual site grading will provide overland release to the existing drainage creeks and conform to conceptual grading plans for the adjacent future growth planning areas (West Area and East Area Specific Plans). It is expected that some retaining walls will be needed to absorb the elevation difference between many lots.

Proposed Drainage
The proposed grading and drainage plan will seek to maintain the existing shape and hydrologic properties of the existing Gabilan Creek and Natividad Creek drainage basins. This will be accomplished through the use of site/parcel-based uniformly decentralized controls including 170
City of Salinas | Final Central Area Specific Plan, November 2020 Low Impact Development strategies and PCBMP to the MEP. Where infiltration is proven infeasible, efficient onsite storm drain systems, supplemental detention, and retention facilities, and enhancing the existing creek corridors may be implemented, on a case-by-case basis, per the direction of the City Engineer. Parcel-based stormwater management will minimize the storm drain system. Figure 6 8 shows the conceptual storm drain system for the Plan Area. The final design configuration and locations for these facilities will be determined as part of the preparation and approval of each tentative map within the Plan Area.

The onsite (underground) storm drain system will consist of reinforced concrete orhigh-densitypolyethylene (HDPE)pipedesignedinaccordance with the latest City of Salinas design standards. The storm drain system will direct the runoff to the supplemental detention and retention facilities located along the edges of the Gabilan and Natividad Creek corridors.

Detention and retention facilities are needed to mitigate for increases in peak runoff flow rate and runoff volume due to development.

Water quality basins are needed to provide mitigation for increases in stormwater pollutants due to development. PACE has been retained to study the required hydrologic mitigation facilities and creek enhancement corridor. The hydrologic analysis was based on design criteria from the City of Salinas, Monterey County Water Resources Agency, and the Regional Water Quality Control Board. The potential hydrologic impacts to Carr Lake and the downstream reclamation ditch were also taken into account due to historical flooding issues. A de-silting basin will likely be required for Gabilan Creek, north of the future extension of Russell Road to minimize creek silting.

A landscape and maintenance plan for each basin shall be submitted with the tentative map creating said basin (retention or detention). Basins shall be designed to achieve an aesthetically attractive and natural vegetated appearance. The landscape and maintenance plan must be prepared by a qualified professional and is subject to approve by the City Engineer and the City Planner. See Chapter 7 for photo examples of natural vegetated basins and other applicable requirements (Note: will be inserted in the final document). All basins shall be maintained under the LLMD.

Stormwater Treatment
See Chapter 7, Stormwater and Water Quality Management, for the requirements for stormwater quality management.

6.3 Public Services and Utilities
This section provides an overview of the public services/facilities and utility providers in the City of Salinas including schools, parks, police services, fire services, library services, electricity, natural gas, and telecommunications. See Chapter 2, Land Use (for schools, parks, and library and fire services) and Chapter 8, Public Facility Financing of the Specific Plan for additional discussion on these topics.

LID and Supplemental Detention
basins and other green spaces
slow water flow rates, which is a
goal of stormwater management.

Infrastructure Plans
171
All utilities serving development within the Plan Area shall be installed underground,asshallmainutilitylineswithintheprojectboundariesunless otherwise approved by the City Engineer. Individual utilities services and infrastructure shall be provided to each individual dwelling unit or non-residential use being created by the respective maps or applicable development review application (i.e. each unit or non- residential use shall have an individual water, sanitary sewer, gas, electrical, telephone, cable television, and other standard utility services), in accordance with the Salinas Municipal Code.

A public utility plan will be required with each individual subdivision.

Said plans shall show the locations of all sanitary sewer and storm drain laterals/mains with connections to City mainlines, public utility mains and utility services (including utility boxes and structures), joint utility trenches, water and fire services, lights, driveways, fire hydrants, street trees, inlets/catch basins, and other structures within public rights-ofway and within the site’s common areas. All large utility boxes shall be located on side yards of buildings and/or hidden from public view to the greatest degree possible and screened with landscaping or other features.

Transformers shall be placed underground, unless otherwise approved by the City Engineer.

6.3.1 Existing Utilities and Easements
PG&E transmission towers and corresponding easement extend through the center of the site north of Hemingway Drive and border a portion of the site along the future extension of Russell Road and Old Stage Road.

The transmission easements will be landscaped and improved as part of the development, see Figure 4 6. The Central Area Specific Plan land use plan will not disturb or impede access to the transmission tower. In this regard, structures will not be allowed underneath or within the 40-feet wide (20-feet on each side) swing zone of the transmission lines.

Existing30inchand18inchALCOdomesticwatermainsandcorresponding easement run through the site parallel to the PG&E transmission towers.

California Water Service is planning the installation of a new well and storage tank to help serve the FGA. Various road, ingress/egress, and right-of-way easements exist on site.

Figure 6 9 shows the locations of the existing easements within the Plan Area. All utilities (including power lines) serving each lot within the Plan Area shall be installed underground, as shall main utility lines within and adjacent to the project boundaries unless otherwise approved by the City Engineer.

Schools
The Plan Area is currently located within the Salinas Union High School District (SUHSD), the Alisal Union School District (AUSD), and the Santa Rita Union School District (SRUSD). A total of three school sites are identified in the Central Area Specific Plan. These schools are intended to serve the needs of future students who will live in the Plan Area 172
City of Salinas | Final Central Area Specific Plan, November 2020 and the surrounding areas. Two of these school sites are owned by the applicable school district (SUHSD and AUSD, respectively). The purchase of school sites, not currently owned by the applicable school district, will be negotiated between the applicable District and the underlying property owner. The developer will pay the applicable school fees in effect at the time of building permit issuance.

The student generation rates (and the projected total number of students from the Plan Area) for each school district are shown on Table 6 4.

The AUSD has twelve K-6th grade schools in the East Salinas area. The District has indicated that their schools are currently at capacity. As noted above, the District currently owns a 12-acre elementary school site in the central portion of the Plan Area.

The SRUSD operates four K-5th grade elementary schools and two 6th -8th grade middle schools. The District has indicated that their existing schools are close to full capacity. An 18-acre site (east of Gabilan Creek) was designated in the Plan Area for a new K-8th grade elementary/middle school in the SRUSD.As of the date of this Specific Plan, a district boundary adjustment had been initiated between SRUSD, SUHSD and AUSD. If the districts finalize the boundary adjustment, SRUSD would relinquish that school site to the AUSD for the construction of an elementary school.

The Salinas Union High School District operates six high schools and four middle schools for the entire city, except within the SRUSD, which provides its own middle schools. All the schools are close to or exceeding their capacity. The District has purchased land for an 18-acre middle school site within the Plan Area just east of Hemingway Drive, adjacent to the southerly greenway street in the Plan Area. Additionally, the Salinas Union High School District recently completed the Rancho San Juan High School located in the West Area Specific Plan off Rogge Road.

Consultation with applicable school districts shall occur as described in Section 9.3, Project Review Procedures, under Tentative/Vesting Tentative Subdivision Maps, because the demand for new schools will gradually increase over the time period in which buildout of the Specific Plan gradually occurs. See Chapter 2 of the Specific Plan for an overview discussion of the school sites and student generation rates.

Public Safety: Police Protection Services
Remainder of page intentionally left blank
Infrastructure Plans
173
Dwelling Unit Type Education Level Generation Factors** Alisal Union School District (AUSD)
Single-Family (NE A-B)
and (NG A-B)
Elementary 0.4180
Middle N/A
High N/A
Multifamily Neighborhood General
(NG-C) and Village Center (VC A-B)
Elementary 0.2857
Middle N/A
High N/A
Santa Rita Union School District (SRUSD)
Single-Family (NE A-B)
and (NG A-B)
Elementary 0.3148
Middle 0.1955
High N/A
Multifamily Neighborhood General
(NG-C) and Village Center (VC A-B)
Elementary 0.5715
Middle 0.1892
High N/A
Salinas Union High School District (SUHSD)
Single-Family (NE A-B)
and (NG A-B)
Elementary N/A
Middle 0.114
High 0.137
Multifamily Neighborhood General
(NG-C) and Village Center (VC A-B)
Elementary N/A
Middle 0.028
High 0.011
Source: Salinas Union High School District: School Facility Needs Analysis for the Salinas Union High School District, May 2020; Santa Rita Union School District School Facilities Needs Analysis, March 6, 2018. Alisal Union School District School Facilities Needs Analysis, July 2, 2020.

Notes: AUSD only contains elementary schools; SRUSD only contains elementary and middle schools; SUHSD only contains middle and high schools.

Table 6-4: Student Generation Estimates
See Section 8.4 for discussion of Police Services
Fire Protection and Emergency Services
See Section 8.4 for discussion of Fire Protection and Emergency Services.

Library Services
See Section 8.4 for discussion of Library Services.

Electricity Services
In February of 2017, Monterey Bay Community Power (MBPC), a joint powers authority, was formed to provide locally-controlled, carbon-free electricity services to San Benito, Monterey and Santa Cruz counties through the Community Choice Energy (CCE) model established by the State of California. The MBCP serves as the primary electricity service provider for residential and business customers in the City of Salinas.

Prior to the formation of MBCP, Pacific Gas and Electric Company (PG&E) was the primary electricity service provider for the City.

MBCP provides various carbon-free electricity service offerings (with 174
City of Salinas | Final Central Area Specific Plan, November 2020 reducedgreenhouse sources suchas solar,wind, andhydroelectric).Residential and business customers located in the Plan Area will be automatically served by MBCP unless they specifically select PG&E to be their service provider.

PG&E continues to provide distribution of electricity. PG&E indicates that sufficient primary line power service exists in close proximity to the proposed development area. PG&E currently operates a 12 kV overhead power line along Old Stage Road and Williams Road. A 12 kV underground primary line exists along Boronda Road. PG&E also maintains 112 kV transmission lines and corresponding easements along the northwest side of Old Stage Road, westerly along the proposed Russell Road alignment, and southerly down the middle of the site as mentioned previously in Chapter 6. By agreement, MBCP is authorized to utilize this same primary line power distribution system to provide electivity services to its customers.

PG&E plans to install a substation near the intersection of the proposed Russell Road alignment and the central north to south transmission lines. The substation will be subject to the City’s approval of a CUP in accordance with Article 6, Division 8 of the Zoning Code to ensure compatibility with adjacent uses. Table 6 5 shows the estimated electricity demand for the Plan Area.

Electric vehicles charging stations will be provided at the Village Center, public facilities, and other locations.

Use Usage Factor (kwh) Project Estimated Monthly
Usage (kwh/month)
Retail/Services 1.35 kwh/sq.ft./month (1) 489,700 sq.ft. 661,095 Residential 867 kwh/unit/month (2) 3,911 unit 3,390,837 Schools 17,736 kwh/acre/month (3) 48 acres 851,328
Total 4,903,260
(7) 2012 U.S. Energy Information Administration Commercial Building Energy Consumption Survey (8) Average annual electricity consumption per residential customer, U.S. Energy Information Administration, 2017 (9) SUHSD New High School #5 Construction, Subsequent EIR Table 6-5: Estimated Electricity Demand
Remainder of page intentionally left blank
Infrastructure Plans
175
Natural Gas
PG&E provides natural gas service to the City of Salinas. A gas line exists along Williams Road. PG&E will extend their services to the Plan Area along E. Boronda Road in accordance with the franchise agreement with the City. There is also an existing 12-inch diameter transmission line in Natividad Road that operates at a maximum pressure of 350 pounds per square inch gauge (psig). PG&E has requested that a substation be constructed within the Plan Area.

Use Usage Factor (Therms) Project Estimated Monthly
Usage (Therms)
Retail/Services 0 .0225/sq.ft./month (1) 489,700 sq.ft. 11,018 Residential 40.25/unit/month (2) 3,911 unit 157,418
Schools 0.0225/sq.ft./month (3) 420,000 9,450
Total 177,886
(10) 2003 U.S. Energy Information Administration, Commercial Building Energy Consumption Survey (11)California Residential Natural Gas Consumption, California Energy Commission (12) School Estimated square feet: 85,000 sq.ft. for Elementary School, 125,000 sq.ft. for Middle School and 200,000 sq.ft. for High School.

Table 6-6: Estimated Natural Gas Demand
Telecommunication Services
Comcast provides cable television and internet service to the City of Salinas and will provide service to the Plan Area. AT&T/SBC and numerous other telecommunications companies provide telephone and cellular phone service to residents in the City of Salinas. Extension of existing underground cable networks within adjacent streets will be required to provide service to the Plan Area.

Communications infrastructure, including infrastructure necessary to support cable television, telephone, fiber optic networks, and wireless communications shall be installed throughout the Plan Area. Developer shall install empty (dark) fiber conduit within the public right-of-way in accordance with applicable City Standards, subject to review and approval by the City Engineer.

Solid Waste Management and Recycling
The Specific Plan will result in new mixed use commercial, residential and other development that will generate an increased demand for solid waste collection and disposal capacity. As shown on Table 6 7, Estimated Solid Waste Generation, the project will generate approximately 44,171 pounds of solid waste per day.

The Salinas Valley Solid Waste Authority (SVSWA) is currently the solid waste disposal service provider for the City of Salinas. SVSWA is a joint powers agency made up of the eastern half of unincorporated Monterey County and five cities, including the City of Salinas. SVSWA currently owns four landfills. Three of these landfills are closed and inactive while 176
City of Salinas | Final Central Area Specific Plan, November 2020 Johnson Canyon Landfill is currently in operation. This landfill is operated by and serves as the regional landfill for the Agency.

Solid waste generated within the incorporated boundaries of the City is currently collected by Republic Services of Salinas and delivered to the Salinas Solid Waste Authority Transfer Station and Republic Services Transfer Station, which then transport the collected refuse to the Johnson Canyon Landfill, which is owned and operated by SVSWA. The combined permit capacity of both transfer stations can support most or all the City’s waste stream transportation needs.

The Johnson Canyon Landfill is classified as a Class III refuse disposal facility by the Regional Water Quality Control Board (RWQCB). The site is permitted by the California Department of Resources Recycling and Recovery to accept a maximum of 1,574 tons of solid waste per day. The landfill’s approved filled area is approximately 96 acres in size and its total site capacity is approximately 14 million cubic yards. Approximately 213,714 tons of solid waste were landfilled at the Johnson Canyon Landfill in FY 2017-2018. According to SVSWA (2018), the Johnson Canyon Landfill will be filled to capacity in approximately 38-45 years based on a combination of current solid waste generation rates and new waste reduction/diversion programs.

SVSWA is currently responsible for overseeing future landfill siting or expansion to meet the area’s long-term solid waste disposal and resource recovery needs. SVSWA has proposed an approach to provide for the solid waste disposal and resource recovery needs for jurisdictions (that are located within its service area) for approximately 70 years or through approximately 2085. This approach includes increased waste diversion and materials recovery as well as the application of or contracting for advanced technologies for processing solid waste to provide sufficient long-term capacity and to help achieve the waste diversion mandates required by Assembly Bills (AB) 939, 341, and 1826, and Senate Bill (SB) 1383.

The California Green Building Standards Code (CALGreen), Chapter 14 of the City of Salinas Municipal Code and Zoning Code Section 37-50.200 and 210, which regulates the management of garbage, recyclables and other solid waste apply to the land uses/properties located in the incorporated boundaries of the City, including the Central Area Specific Plan.

On November 20, 2018, the Salinas City Council passed and approved resolution 21521 that authorizes the City Manager to deliver a one year written notice to the SVSWA of the City’s intent to withdraw from the Joint Powers Agreement Between the City of Salinas, the City of Gonzales, the City of Greenfield, the City of King, the City of Soledad, and the County of Monterey Creating the Salinas Valley Solid Waste Authority. Pursuant to section 19 of the Joint Powers Agreement, the City gave the one-year notice to the SVSWA in a letter dated December 6, 2018. This notice still remains in effect as of the writing of this Specific Plan.

Infrastructure Plans
177
If the City finds that maintaining its membership in the SVSWA is in the best long-range interests of its residents and businesses and the region, then the City may opt to rescind the notice and remain a member of the SVSWA Joint Powers authority. Whetherthe City remains with the SVSWA or ultimately chooses another service provider, the solid waste disposal, diversion and resource recovery needs of the Central Areas Specific Plan and the City will be fully met.

Land Use Generation Factor (1) Project Estimated Solid Waste Generation (lb./day)
Retail/Services 6 lb/1,000 sq.ft./day 489, 700 sq.ft 2,938 Residential 10 lb/unit/day 3,911 units 39,110
Schools 0.5 lb/student/day 4,246 students 2,123
Total 44,171
(13) CalRecycle 2016
Table 6-7: Estimated Solid Waste Generation

6.4 Infrastructure, Public Services & Utilities
Goals and Policies
The following goals and policies are found in the Salinas General Plan.

The following policy Implementation Measures are relevant only to the Plan Area.

6.4.1 Water Supply, Treatment and Distribution
Goal LU-6: Work with water suppliers and distributors such as Cal Water and ALCO to continue to provide quality water supply and treatment capacity to meet community needs.

Policy LU-6.1: Actively work with Cal Water and ALCO, as well as regional water suppliers and distributors, to ensure that high quality water is available for the community.

Policy LU-6.2: Review development proposals to ensure that adequate water supplies, treatment, and distribution capacity is available to meet the needs of the development without negatively impacting the existing community.

Policy LU-6.3: Participate in and support regional programs and projects that target the improvement and conservation of the region’s groundwater and surface water supply.

Policy LU-6.4: Actively promote water conservation by City residents, businesses and surrounding agricultural producers.

Implementation Measure
The Specific Plan will include the development of a water system to provide potable water to the Plan Area, which includes sufficient water pressure and fire hydrants as determined by the City to meet the needs 178
City of Salinas | Final Central Area Specific Plan, November 2020 of residents and the development. The Specific Plan will include water saving features, such as low-flow toilets, drip irrigation systems, tankless water heaters for appropriate uses, faucet water restrictions and droughttolerant landscaping and meet other City and State requirements related to water conservation including the City’s Water Conservation Ordinance, Water Efficient Landscape Ordinance, Zoning Code Landscaping and Irrigation requirements.

Policy LU-6.5: Review projects subject, such as residential projects with 500 or more units, for compliance with Sections 10910-10915 of the California Water Code.

Implementation Measure
Cal Water and ALCO agree to serve the Plan Area based upon Water Supply Assessments Reports that have been prepared for the Plan Area by the water purveyors that conclude there is an adequate water supply to serve the Plan Area.

6.4.2 Sewer Collection and Treatment
Goal LU-7: Provide sewer service and maintain sewer facilities to meet community need for sewer collection and treatment.

Policy LU-7.1: Provide a sewer system and improvements that comply with the City’s Sanitary Sewer Master Plan and meets the needs of the community for sewer collection and treatment and work with MRWPCA for sewer treatment needs.

Policy LU-7.2: City will review development proposals in accordance to ensure that adequate sewer collection and treatment facilities are available to meet the needs of the development without negatively impacting the existing community.

Policy LU-7.3: Maintain the existing sewer system to provide a high level of service to existing neighborhoods.

Implementation Measure
The development of the Plan Area will include provision of a sewer collection system and otherrequired upgrades that will convey wastewater to existing mains in the City and to the Monterey One Water treatment plant. It has been determined by the Monterey One Water that the treatment plant has capacity to serve the development of the Plan Area.

6.4.3 Flood Control
Goal LU-8: Work with Monterey County Water Resources Agency (MCWRA) to provide a level of flood control protection that meets the needs of the community.

Infrastructure Plans
179
Policy LU-8.1: Actively coordinate and work with MCWRA to provide and maintain necessary flood control facilities.

Policy LU-8.2: Apply appropriate development standards and fees to improve present drainage systems and provide adequate stormwater detention basins and sedimentation ponds with new construction as required by the City.

Implementation Measure
ThedevelopmentoftheSpecificPlanshallinclude a systemof supplemental stormwater detention and retention basins designed to supplement on-site/parcel-based LID PCBMP hydro modification mitigation and minimize impacts on MCWRA flood control facilities resulting from the urban development of the Specific Plan area.

Policy LU-8.3: Require new development, to the extent feasible, to provide flood control facilities that are aesthetically attractive, ecologically beneficial and require ongoing maintenance of the facilities through a maintenance district.

Implementation Measures
All basins and similar flood control facilities shall be designed to be ecologically beneficial and aesthetically attractive and have a natural vegetated appearance. In this regard, a landscape and maintenance plan for basins shall be submitted with the tentative map creating any basin (supplemental retention or detention). The landscape and maintenance plan must be preparedby a qualifiedprofessional andis subjectto approval by the City Engineer and the City Planner. Chapter 7 includes photo examples of natural vegetated basins and other applicable requirements.

All basins shall be maintained by a maintenance district such (e.g. LLMD).

6.4.4 Stormwater
Goal LU-8: Work with Monterey County Water Resources Agency (MCWRA) to provide a level of flood control protection that meets the needs of the community.

Goal LU-8.3: Require new development, to the extent feasible, to provide flood control facilities that are aesthetically attractive, ecologically beneficial and require ongoing maintenance of the facilities through a maintenance district.

Implementation Measure
The supplemental detention and retention areas and other flood control facilities inthe SpecificPlanwillbe installedbythedeveloper.Basins,where feasible should be designed as usable open space and recreation areas.

Groundwater quality will be handled by site/parcel-based PCBMP to the 180
City of Salinas | Final Central Area Specific Plan, November 2020 MEP. Basins will be supplemental to the amount of hydromodification mitigation where infiltration rates make total on-site disposal in feasible as part of the overall low impact development program. Also see the implementation for LU-8.1, 8.2, 8.3 under Flood Control above and Chapter 7, Stormwater and Water Quality Management for additional details on stormwater management and implementation.

6.4.5 Education/Schools
Goal LU-9: Work with local school districts and other educational organizations to ensure that a level of public education is provided that meets community educational needs.

Policy LU-9.1: Work in partnership with local school districts and assist them in identifying land needed for new school sites so that sufficient facilities are provided for students.

Policy LU-9.2: Considerimpacts of proposed projects on school enrollment and facilities when acting on annexation applications to ensure that public services and facilities service standards identified in Table LU-4 are met.

Policy LU-9.3: Support the development of career/professional schools that encourage a well-trained work force.

Policy LU-9.4: Work with Monterey Salinas Transit to provide transit routes to serve education institutions.

Implementation Measures
Development of the Central Area Specific Plan has included coordination with the Salinas Union High School District, the Alisal Union School District, and the Santa Rita Union Elementary School (by the City and the project applicants) to identify school sites that meet the needs of these Districts. Two of the school districts currently own school sites in the Plan Area. A third site identified in the plan will be reserved for acquisition by the appropriate school district in accordance with the requirements of the Subdivision Map Act.

Additional consultation with the applicable School Districts shall occur as described in Section 9.3, Project Review Procedures, under Tentative/ Vesting Tentative Subdivision Maps because the demand for new schools will gradually increase over the time period in which buildout of the Specific Plan occurs. See Chapter 6.3.1 and Table 6-4 of the Specific Plan for discussion of student generation rates.

Implementation Measures
The planning for the Plan Area has included coordination with Monterey Salinas Transit (MST) to determine appropriate transit routes that will serve not only educational institutions but other uses in the Plan Area and the greater Future Growth Area as well. The City will continue to ensure MST is consulted throughout the development of the Plan Area. The City will also work with the school districts to coordinate transit needs through Infrastructure Plans
181
MST as well. See Chapter 5 Circulation for further discussion of Transit.

6.4.6 Fire Protection, Emergency Services, and Code
Compliance
Goal LU-4: Provide effective and responsive fire protection and emergency response service.

Policy LU-4.1: Provide an effective and responsive level of fire protection, public education, and emergency response service (including facilities, personnel, and equipment) through the Salinas Fire Department.

Policy LU-4.2: Improve the enforcement ofregulations, such as Zoning Codes and building codes, to ensure existing and new development is constructed, occupied, and maintained to minimize potential fire and other hazards.

Implementation Measures
A new fire station site has been selected on the northeast corner of Natividad Road and the southerly greenway street in the PlanArea. The site was selected by the Salinas Fire Department to provide the most responsive access to the Plan Area and surrounding areas. The developers of the Plan Area shall pay their fair share of the City’s Public Facility Impact Fee Program to fund the cost of this new fire station.

All new residential and commercial structures constructed in the Plan Area will be equipped with automatic fire-extinguishing (fire sprinkler) systems as required by the California Fire Code as adopted and amended by the City of Salinas. Fire sprinkler systems eliminate, or greatly reduce the rate of growth of a fire, increase life safety of the occupants and the responders, and limit structural damage.

Policy LU-4.3: Support incentives and public education programs such as the Seismic Retrofit Program that encourage compliance with building code and fire safety requirements.

Implementation Measures
The Central Area Specific Plan is required to comply with the latest building codeandfirecoderulesandregulations includingseismic codesorregulations.

The California Building Code, Fire Code and other applicable codes adopted and enforced by the City in effect at the time of development shall apply.

Policy LU-5.1: Provide an effective and responsive level of police protection (including facilities, personnel, and equipment) through the Salinas Police Department in accordance with services levels identified in the General Plan.

Policy LU-5.2: Implement alternative policing methods, such as Community Policing, youth programs and crime awareness public education programs to reduce the incidence of crime within Salinas.
182
City of Salinas | Final Central Area Specific Plan, November 2020 Implementation Measures
The developers of the PlanArea shall pay theirfair share of the City’s Public Facility Impact Fee Program to fund the cost of police facilities necessary to serve the site. A new Police Headquarters facility was recently completed in March of 2020 in this regard. Additional police officers and staff will be added to existing police services and programs, as needed to serve the Plan Area and the greater Future Growth Area as determined by the City to ensure conformance with the Police Protection Service Standards contained in the General Plan.

The Specific Plan’s Design Standards require development to incorporate Crime Prevention Through Environmental Design Principles (CPTED), which promote pedestrian-oriented design and the use of windows, porches, and otherfeatures to promote “eyes on the street.” The PlanArea’s system of interconnecting streets and parks and community facilities surrounded by streets and sidewalks provide excellent access and visibility for police patrols to promote effective and responsive police protection.

6.4.7 Libraries
Goal LU-10: Provide a level of library facilities and services that meet the needs of the community.

Policy LU-10.1: Provide library services and facilities that meet:
• The Library Plan of Service
• The Library Department Mission
• The State of California guidelines for library facilities • The General Plan Public Services and Facilities Service Standard of

0.5 square feet of public use library space per capita; and • Library services within 2 miles of any residential use.

Policy LU-10.2: Maintain and continue to develop a high-quality library system that: enhances the cultural life of the community; is the repository of people’s ideas, knowledge, and thoughts; and is the information center for the community.

Policy LU-10.3: Improve the library system by building at least two branch libraries and by expanding current library facilities, with interim expansion of service achieved through alternative means such as bookmobiles, portable buildings, and joint-use facilities.

Policy LU-10.4: Explore the potential for coordination of public and school libraries, especially for the proposed McKinnon branch.

Policy LU-10.5: Develop a high quality library system that achieves the Library Department mission to be the focal point in the community for opening doors to lifelong learning and enjoyment, and the catalyst for promoting equal access to information.

Infrastructure Plans
183
Implementation Measures
The Plan Area includes a 2-acre site in the Village Center, adjacent to the middle school, for the construction of a new 22,000-square-foot library.

The developers of the Specific Plan will pay their fair share of the City’s Public Facilities Impact Fee program to fund the new library.

Remainder of page intentionally left blank
184
City of Salinas | Final Central Area Specific Plan, November 2020 This page is intentionally left blank.
185
Infrastructure Plans
Figure 6-1: Conceptual Domestic Water Distribution Layout 186
City of Salinas | Final Central Area Specific Plan, November 2020 Figure 6-2: ALCO Conceptual Domestic Water Distribution Layout 187
Infrastructure Plans
Figure 6-3: Cal Water Conceptual Domestic Water Distribution Layout 188
City of Salinas | Final Central Area Specific Plan, November 2020 Figure 6-4: Conceptual Sanitary Sewer Layout
189
Infrastructure Plans
Figure 6-5: Existing Site Topography
190
City of Salinas | Final Central Area Specific Plan, November 2020 Figure 6-6: FEMA Flood Zones
191
Infrastructure Plans
Figure 6-7: Conceptual Earthwork Design
192
City of Salinas | Final Central Area Specific Plan, November 2020 Figure 6-8: Conceptual Storm Drain Layout
193
Infrastructure Plans
Figure 6-9: Existing Easements
194
City of Salinas | Final Central Area Specific Plan, November 2020 Figure 6-10: Conceptual Supplemental Stormwater Basins
195
Final Central Area Specific Plan
November 2020

7. Stormwater and Water
Quality Management

7.1 Introduction
This Chapter addresses the stormwater and water quality management plan forthe CentralArea Specific Plan. Development of the Plan Area will require the support of well-planned stormwater infrastructure. This infrastructure will be designed to meet all the City of Salinas water quality, retention, and flow control requirements as well as other local, state and federal requirements in effect at the time of development. The general location of the project site is shown on Figure 7-1, Location Map.

The City of Salinas initially published draft Stormwater Development Standards (SWDS) in January 2013, to assist project applicants to comply with the City of Salinas NPDES Permit CA0049981 (Resolution No. R3-2012-0005) and the Central Coast Regional Water Quality Control Board’s (CCRWQCB)
Post-Construction Stormwater Management Requirements
for Development Projects in the Central Coast Region (PCRs) (Resolution No. R3-2012-0025; amended by Resolution No. R3- 2013-0032). The December 2013 edition of the SWDS is currently being updated to align with the City of Salinas’ 2019 NPDES Permit (Order R3-2019-0073).

The City of Salinas SWDS require new and redeveloped projects to apply Low Impact Development (LID) site design strategies and incorporate stormwater Best Management Practices (BMP) on a parcel/site basis to the Maximum Extent Practicable (MEP) 196
City of Salinas | Final Central Area Specific Plan, November 2020 to reduce the impacts of urban runoff on receiving waters and promote healthy watersheds. Project applicants are required to prepare and implement a Stormwater Control Plan (SWCP) to detail how stormwater runoff and associated pollutants will be managed. The SWCP is required to be prepared under the direction of a Professional Civil Engineer in the State of California, and shall provide sufficient information to evaluate the environmental characteristics of the project area, potential impacts of the proposed development on water resources, and the effectiveness and applicability of measures proposed for managing stormwater runoff.

The proposed Central Area Specific Plan (CASP) is a mixed use development within the City of Salinas North of Boronda Future Growth Area (FGA). The urban development will modify the existing hydrologic conditions of the watershed and introduce new pollutants to receiving waters. The purpose of this section is to outline development standards and guidelines applicable to the Specific Plan to comply with the requirements of the City of Salinas NPDES Permit and the latest edition of the City of Salinas SWDS.

7.1.1 Permit Compliance
This Specific Plan conforms to the requirements of the City of Salinas NPDES Permit CA0049981 ( herein also referred to as “ permit”) and the latest edition of the City of Salinas Stormwater Development Standards (SWDS). If any part of this or any other section of this Specific Plan conflicts with the permit and/or SWDS, the Permit/SWDS shall govern over this section, and this section shall govern over the remaining sections of the Specific Plan.

Nothing contained herein shall be construed to permit or allow nonconformance with the Permit/SWDS unless specifically allowed as provided under the Permit Provisions for Alternate Methods of Compliance and justified by sufficient “Technical Infeasibility ” as outlined in the PCRssection C and approved by the City of Salinas and the CCRWQB staff.

Projects in the PlanArea will manage rainfall at the source using uniformly distributed decentralized controls, natural treatment, and volume reduction BMPs (e.g., bioretention, vegetated swales, filter strips) as a first means of compliance for meeting the numeric criteria for stormwater management to the MEP under the permit and SWDS.

Upon approval the Salinas City Council, this Specific Plan and all subsequent development approved for the Plan Area shall meet or exceed the requirements of the latest version of the Permit (CA0049981) and SWDS in effect at the time of development.

Stormwater and Water Quality Management
197

7.2 References
Central CoastRegionalWater Quality Control Board,City of Salinas NPDES Permit NO. CA0049981, Order R-2019-0073, adopted September 20, 2019 City of Salinas, Stormwater Development Standards for New and Redevelopment Projects. December 2013 and update 2020.

Central Coast Regional Water Quality Control Board, Resolution No. R3- 2013-0032, Attachment 1, Post-Construction Stormwater Management Requirements for Development Projects in the Central Coast Region, July 12, 2013.

Earth Systems Pacific, Final Report of Soil Profiling and Percolation and Infiltrometer Testing. January 10, 2007
NaturalResourcesConservationService,Web Soil Survey 2.0,websoilsurvey. nrcs.usda.gov/app/WebSoilSurvey.aspx
PACE Technical Memorandum, Hydrologic Mitigation Requirements and Design Procedures Salinas Future Growth Area – East and Central Areas.

Ruggeri Jensen Azar & Associates, Draft - Engineers Report Central Area Specific Plan Salinas, California. March 7, 2008

7.3 Study Area Evaluation

7.3.1 Project Description
The Specific Plan is a multi-use development encompassing approximately 760 acres of land within the City’s designated North of Boronda Future Growth Area (FGA). Refer to Table 7-1 for general project information.

Remainder of page intentionally left blank
198
City of Salinas | Final Central Area Specific Plan, November 2020

7.3.2 Existing Site Conditions
The project site, as shown in Figure 7-2 consists primarily of cultivated farmland and grazing lands with a few residences, farmhouses, barns and gravel access roads. Two significant creeks run through the project site from north to south; Gabilan Creek and Natividad Creek. The creeks provide drainage for the Gabilan Mountains and are tributary to Carr Lake approximately 1.5 miles southwest of the Plan Area. Carr Lake serves as a natural detention facility and provides flood control for the Reclamation Ditch during large rainfall events. A 20 feet to 30 feet terrace near the middle of the site divides the two creek watersheds. Annual soil disturbance from agricultural operations has resulted in channelization of the creeks and reduced riparian buffer. There is no significant built storm drain infrastructure within the Plan Area.

Project Information Description
Project Name Central Area Specific Plan
Project Size Approximately 760.4-acres
Location
Located within City limits; bounded by the future extension of Russell Road on the north, East Boronda Road on the south, Natividad Road on the west, and future extension of Constitution Blvd on the east within the North of Boronda Future Growth Area.

Assessor’s
Parcel Numbers(APNs)
153-091-011, 153-091-014, 153-091-016, 211-013-007,
211-013-010, 211-013-003, 211-013-011, 211-013-012,
153-091-017, 153-091-008, 153-091-009, 153-091-010,
Existing Land Use Primarily cultivated farmland and grazing lands with a few residences, farmhouses, barns, and gravel access roads.

Existing Impervious Area +/- 10 acres (2%)
Proposed Land Use
Village Center Mixed Use (44.43 acres);
Residential Neighborhood (319.55 acres);
Public/Semi-Public Facilities (60.65 acres);
Parks (44.06 acres); Open Space (104.29 acres);
Streets (181.46 acres)
Proposed Impervious Area +/-368 acres (56%)
Site Features
Gabilan Creek and Natividad Creek cross through the site from north to south. A 20’-30’ bluff is located near the middle of the site and forms the watershed boundary for the two creeks.

There is minimal existing vegetation worthy of preservation.

Required Setbacks
100-foot setback area along Gabilan and Natividad Creeks or as allowed under the NPDES Permit/SWDS. Setback shall be
measured from the top of stream bank, or from the outside edge of riparian vegetation, whichever is furthest from stream.

Soil Classification
Site consists of lean clays to sandy silts. The NRCS soil classification is mainly Hydrologic Soil
Group C with some A, B and D.

Depth to Groundwater > 10 feet below ground surface
Table 7-1: General Project Information
Stormwater and Water Quality Management
199
Figure 7-3 reflects the soil classifications across the Plan Area. The existing ground generally slopes in a northerly to southerly direction towards BorondaRoad. NRCS soil maps identify the majority ofthe site as “Chualar loam”, which is considered Hydrologic Soil Group C. There are some regions of Hydrologic Soil Groups A and B, generally located closer to the creeks. There are also some pockets of Hydrologic Soil Group D. Earth Systems Pacific performed a geotechnical site investigation in November 2006, which included borings and test pits at 26 different locations within the project site. Results from the geotechnical borings revealed a layer of lean clay overlying interbedded layers of sands and lean clays of variable thicknesses. The investigation concluded there was no consistent trend in thickness or depth of the clay layers, and the composition of the clay layer may vary greatly over relatively short distances. The soils were generally moist to very moist at the time of the investigation. Zones of perched water were encountered at depths below 4 feet in three of the borings and test pits, and free subsurface water was encountered at an approximate depth of 13 feet in one test pit located near the confluence of a tributary stream entering Natividad Creek.

Percolation tests (46 total) performed by Earth Systems Pacific revealed highly variable results, with percolation rates ranging from 0.2 to 6 inches/hour (in/hrs). In general, the upper clay layer exhibited a very low potential for water absorption with percolation rates slower than 0.2 in/hr The underlying soil layers generally exhibited percolation rates of 0.6 in/hr to 6 in/hr. Infiltrometer tests (7 total) also had highly variable results, with inner ring infiltration rates ranging from 0.01 in/hr to 1.0 in/hr. In general, the faster rates were obtained in areas where the soil had recently been cultivated, while the slower rates were from more compacted locations.

Laboratory permeability tests (31 total) also had highly variable results.

The clay layers exhibited slow permeability with an average rate of 1x10- 7 cm/sec, while the silty sands exhibited a moderate permeability with an average rate of 1x10-4 cm/sec. It was observed that permeability rates increased when the soil sample was compacted to 90 to 95 percent of the soil’s maximum dry density. It is anticipated that bioretention facilities would be most effective if they are constructed as deep as practicable to intercept the sandy deposits. It is also recommended to design retention facilities with silt traps to reduce migration of fine-grained material in the facilities.

7.3.3 Existing Floodplain and Grading
See Section 6.2.3, Grading & Drainage and Figure 6-6, FEMA Flood Zones for discussion of the grading and floodplains (including the FEMA Flood Zones and Insurance Map Designations (FIRM)) for the Plan Area.

Pollutants of Concern
Stormwaterdischargesfromurbanareasaresignificantsourcesofpollutants attributed to impairment of water quality of receiving watercourses.

Pursuant to the Clean Water Act (CWA) section 303(d), the CCRWQCB has 200
City of Salinas | Final Central Area Specific Plan, November 2020 found the following pollutants present in Gabilan and Natividad Creeks as a result of municipal and agricultural stormwater discharge:
• Gabilan Creek. Fecal coliform (from natural, nonpoint, and urban runoff/sewer sources); Nitrate; Ammonia, un-ionized; Sediment toxicity; Turbidity; Altered pH levels.
• Natividad Creek. Nitrate; Ammonia; E. coli; Low dissolved oxygen; Sediment toxicity; Altered water temperature; Altered pH levels.

To attain water quality standards, specific early pollution control measures (Source Control) shall be implemented in conjunction with structural measures to ensure water quality is not compromised as a result of the Specific Plan development.

Opportunities and Constraints for Stormwater Control
The following is a summary of opportunities for stormwater quality:
• Riparian Setback. The project is required to implement riparian setbacks to Gabilan and Natividad Creeks. Stormwater management facilities, if required and designed to be consistent with the Permit/ SWDS, may be located in the riparian setback. Remedial planting within the buffer will also help improve creek health and provide beneficial habitat for wildlife.
• Soil Conditions. There are relatively well draining Hydrologic Soil Group A and B sandy silt soils along the Gabilan and Natividad Creek corridors. The project may take advantage of the moderate percolation rates by locating infiltrating stormwater BMPs at these locations to capture and dispose of stormwater runoff that cannot be completely infiltrated on site due to poor localized infiltration rates. • Groundwater. Groundwater levels appear to be greater than ten feet below ground surface, which is adequate for direct and indirect stormwater infiltration.
• Street Sections. Many of the Plan Area street sections include a planter strip between the street and sidewalk and some include landscape medians. These areas may be used for stormwater control measures. Street sections with reduced widths are proposed, which will generate less runoff.
• Open Space. The project includes approximately 107 acres of designated park and open space, which is +/-20% of the site. This limits impervious surface and provides opportunity for stormwater control measures.
• Maintenance/Public Outreach. The project Post Construction BMP (PCBMP) maintenance will be managed by Homeowner’s
Association (HOA) (condos and townhomes), private property owners (single-family and commercial sites), and maintenance districts (public improvements and other designated areas) which Stormwater and Water Quality Management
201
allow for consistent maintenance of stormwater facilities. These shall also provide educational information to future residents regarding water quality and BMPs, and implement Covenants, Conditions and Restrictions (CC&R’s) to control the generation and movement of stormwater pollutants.

The following is a summary of constraints for stormwater quality:
• Site Topography. Many areas of the site have relatively flat ground slopes, which may make surface drainage a challenge. The steep bluffs and terraces also present grading challenges with site planning and limiting earth movement.
• Soil Conditions. The majority of the site consists of lean clay soils designated as Hydrologic Soil Group C with slow permeability. This may limit the amount of infiltration possible as a stormwater control/ disposal strategy for much of the site.
• Easements and Utilities. The site contains existing easements and utilities including PG&E transmission towers and overhead lines and ALCO large diameter water mains. Cal Water also plans to install wells and storage tanks at two locations in the Plan Area. The placement of stormwater control measures within existing easements may be restricted. Also, infiltrating stormwater control measures require significant setbacks from water wells and storage facilities.

7.4 Stormwater Control Standards
The following sections identify stormwater control standards that are applicable to the PlanArea, including stormwater control goals, alternative compliance, riparian protection compliance, LID site design compliance, and project level permit compliance. These standards are based on the December 2013 edition of the City of Salinas SWDS.

7.4.1 Stormwater Control Goals
The PCRs and City of Salinas SWDS identify five performance requirement levels based on the characteristics of a particular project. The Plan Area is subject to performance requirements 1 through 4 and may be subject to performance requirement 5:
• Performance Requirement 1 – Site Design and Runoff Reduction • Performance Requirement 2 – Water Quality Treatment
• Performance Requirement 3 – Runoff Retention
• Performance Requirement 4 – Peak Management
• Performance Requirement 5 – Special Circumstances
Refer to the PCRs for a complete description of the various requirements. 202
City of Salinas | Final Central Area Specific Plan, November 2020 Supplemental Compliance
Due to the wide range of measured percolation, infiltration, and permeability rates, it is anticipated it may be difficult, or infeasible, to achieve the required amount of infiltration on a site/parcel basis.

In order to ensure the project meets Requirements 4 and 5 for runoff retention and peak flow management, the Specific Plan proposes to use a supplemental method of compliance to the City of Salinas SWDS and NPDES Permit. Pacific Advanced Civil Engineering, Inc. (PACE), the water resources engineering consultant for the Specific Plan, prepared a hydrologic mitigation analysis for the Plan Area in 2007, which is documented in a Technical Memorandum (see Appendix R). The memorandum addresses stormwater mitigation measures for the entire Plan Area, and considers three discrete design criteria:
• City of Salinas flood control criteria to limit the post-development 24hour,100yearpeakflowratetothe10yearpre-developmentrate; • Monterey County Water Resources Agency (MCWRA) flood
control criteria forthe 72hour, 100year stormeventtopreventflood impacts within the Carr Lake and Reclamation Ditch watershed; • Regional Water Quality Control Board hydromodification management criteria to mimic pre- development stormwater runoff volumes and durations through the use of continuous simulation modeling.

PACE used three hydrologic basin design procedures to evaluate the different criteria of the various agencies: 1) annual water mass balance analysis, 2) statistical single storm event analysis, and 3) continuous flow duration/volume analysis. The analyses were utilized to size the stormwater management facilities (detention/retention basins) assuming a single criterion, and then determine the facility size based on the governing criteria. PACE used a conservative permeability of 0.1788 feet/ day (0.1 in/hr) to analyze retention basins, which is based on the average results of the samples obtained by Earth Systems Pacific, the geotechnical engineering consultant for the Specific Plan.

The proposed control facility would be a dual basin facility located within the Gabilan and Natividad Creek riparian setback area that will have both supplemental detention and retention storage. A summary of the storage volume requirement per watershed is provided in Table 7-2 below.

Basin Type Total Basin Volume (Acre-Feet)
Gabilan Creek Natividad Creek
Detention 29.1 43.0
Retention 23.0 40.0
Table 7-2: Hydrologic Mitigation Basin Volumes
Stormwater and Water Quality Management
203
The infiltration rate used to determine the retention volume is conservative because basins are proposed to be located in an area where higher infiltration rates are expected. In addition, the analysis did not consider the use of LID features within the project. Therefore, the basin volumes are conservative and represent a maximum design requirement. Further analysis during final design may allow a reduction in basin volume.

This supplemental method of compliance only meets the goals of Requirement 3 (Runoff Retention) and 4 (Peak Management) of the Salinas PCRs by utilizing a regional approach to stormwater management to supplement on site infiltration and maximize ground water recharge.

Individual projects within the Plan Area will be required to provide parcel based mitigation. This may include but it not limited to integrating Performance Requirements 1 (Site Design and Runoff Retention), Performance Requirement 2 (Water Quality Treatment) and Performance Requirement 3 (Runoff Retention) into their site design, including LID site planning strategies, source control measures, and uniformly distributed decentralizedtreatment controlBMPs.While the supplemental compliance provides all required runoff reduction, project applicants shall design structural stormwater control measures to maximize infiltration and/or other volume reduction opportunities as required by the SWDS using a parcel or site-based approach to the MEP. Project applicants shall filter all stormwater runoff on site prior to infiltration or disposal unless captured for the re-use on-site in cisterns or part of a greywater system.

A landscape and maintenance plan for supplemental basins shall be submitted as part of the tentative map that creates the basin. Basins shall be designed to achieve an aesthetically attractive and natural vegetated appearance (see example photo illustrations included in Specific Plan).

The landscape and maintenance plan must be prepared by a qualified professional and is subject to approval by the City Engineer and the City Planner. Maintenance of the supplemental basins shall be provided by a maintenance district (LLMD).

Riparian Protection Measures
Riparian areas are vegetated buffers adjacent to water bodies that function as natural filters of nonpoint source pollutants. Preservation of natural riparian and vegetated areas are critical to manage water quality impacts associated with urban development. Two significant creeks run through the project site from north to south. Gabilan Creek has approximately 3,700 feet of length located in the western half of the Plan Area. Natividad Creek has approximately 7,000 feet of length located in the eastern half of the Plan Area, including two minor tributaries. The upper half of Natividad Creek has been converted from its natural state to an agricultural drainage ditch, and most of the vegetation surrounding Natividad Creek has been removed as a result of agricultural practices. The Gabilan Creek riparian area has also been degraded over time as a result of agricultural practices.

The Specific Plan intends to restore these creeks to a more natural state to provide aesthetic, ecological, recreational, and water quality value to the local setting, while also providing flood storm discharge capacity through 204
City of Salinas | Final Central Area Specific Plan, November 2020 the Plan Area. This will likely necessitate a flood plain analysis for FEMA review and approval to formally establish the one percent chance annual flood plain and flood way.

The Specific Plan (see Figures 7-4 and 7-5) provides conceptual riparian restoration plans for both the Gabilan and the Natividad Creek corridors.

The corridor widths will be 300-feet minimum but will exceed this width in many areas. A minimum 30-feet wide riparian buffer measured from the new top of bank/new mean high water mark to the outboard edge of the buffer of the realigned/reconstructed/rehabilitated creeks to minimize grading shall be provided. This setback is similarto the setback established downstream from previous development within the Creekbridge project area. The setback will vary to create an enhanced meandering creek alignment. Realignment of the creeks will require approval by the CCRWQCB, California Department of Fish and Wildlife, the Army Corp of Engineers, City of Salinas, MCWRA, US Fish and Wildlife Service, and FEMA. Passive improvements are anticipated within the riparian setback including recreational trails and regional stormwater management facilities (detention/retention/infiltration basins). The riparian corridor will implement a re-vegetation program to create beneficial riparian vegetation and create a buffer between land uses. The re-vegetation program shall be subject to the review and approval of the City Engineer and City Planner and others as determined by the NPDES Permit/SWDS.

The total riparian area reserved within the Plan Area is approximately 30 acres for Gabilan Creek and approximately 74 acres for Natividad Creek.

LID Site Design Compliance
The current NPDES Permit and SWDS require developments to implement LID site design strategies early in the site planning process. LID is a design approach that strives to protect water resources, by reducing runoff associated with urban development (source control) and filtering runoff and infiltrating it for disposal (structural control). The Specific Plan was developed using the principles of New Urbanism and Traditional Neighborhood Development. Goals associated with this strategy include walkability, connectivity, clustered development, smart transportation, and sustainability. The following LID site design principles are integrated into the Specific Plan and conceptual site layout:
• Conserve Natural Areas. The Specific Plan protects and enhances the existing Gabilan Creek and Natividad Creek drainage courses and riparian areas. There are no other natural areas to preserve since the remainder of the Plan Area is used for agricultural purposes and experiences annual disturbance.
• Minimize Disturbances to Natural Drainages. The Specific Plan protects and enhances the existing Gabilan Creek and Natividad Creek drainage courses and riparian areas. Refer to “Riparian Protection Measures” in Section 7.4 of the Specific Plan for more information.

Stormwater and Water Quality Management
205
• Avoid Excessive Grading and Disturbance to Soils. The layout of the Plan Area seeks to mimic existing topography to the extent feasible in an effort to minimize grading. However, development and street profile constraints may require significant cuts andfills atthe transition slopes between the existing bluffs and at the creek riparian corridor boundaries. The grading plan will be refined during the project level final design process to minimize changes to the existing topography to the MEP and provide a more natural appearance.
• Avoid Compaction and Impervious Cover in Zones that Allow Stormwater Infiltration. The Plan Area locates supplemental stormwater management facilities (detention/retention infiltration basins) within the Gabilan and Natividad Creek riparian areas to take advantage of in-situ soils that exhibit higher percolation rates for runoff that cannot be infiltrated onsite due to low infiltration rates.

Soil compaction will be minimized in these areas.
• Minimize Impervious Footprint. The layout of the PlanArea employs a clustered development approach in an attempt to increase open space and create a connected and walkable community. As a result, the Specific Plan provides approximately 148 acres of park and open space, which is 20% of the total site. The street design will employ curb bulb-outs as one means of traffic calming, stormwater mitigation, and minimizing impervious footprint. The Specific Plan will also employ the use of alternative permeable pavements, where applicable (e.g., walkways, alleys, driveways, parking stalls). The location and extent of permeable pavement use will be determined at the project level. Where practical, opportunities for shared driveways/parking to reduce impervious land coverage will be considered subject to the approval of the City Engineer.

Parking spaces will be eliminated and replaced with landscape, where possible. Streets widths will be reduced to the minimum required for public safety, and landscaping will be planted adjacent to streets where practical. Tree canopy will be maximized throughout the development area via fast-growing large canopy trees. The spacing and variety of such trees shall be subject to the approval of the City Engineer and City Planner.
• Disconnect Impervious Surfaces. All impervious surfaces will be disconnected, and runoff directed to distributed pervious areas as required by the SWDS. The location of pervious areas and method of conveyance will be determined at the project level.
• Specify Vehicular Zones to Minimum Widths. Street sections are designed with minimum lane widths as permitted by the City of Salinas and required for public safety. Collector streets and medium speed residential streets employ 11-foot travel lanes, while low speed residential streets employ 9-foot and 10-foot travel lanes. Parking stall size will be minimized as permitted by the City, including the use of compact parking stalls. Individual driveway widths for single-family dwellings will be 10-feet or as otherwise provided by this Specific Plan, while shared alleys will be 20-feet minimum.
206
City of Salinas | Final Central Area Specific Plan, November 2020 • Use Green Infrastructure for Conveying Stormwater Runoff. The Specific Plan seeks to maintain surface conveyance of runoff from impervious surfaces to pervious areas. The Specific Plan encourages the use of the bioswales and vegetated swales in place of traditional gutter and pipe conveyance.
• Manage Rainfall at the Source. The Specific Plan will employ distributed decentralized controls to the MEP that use LID design principles to manage stormwater runoff. In addition to site/parcel structural PCBMPs, supplemental stormwater management facilities will be provided to mitigate increases in runoff to supplement site/ parcel based PCBMP disposal due to inherently slow site infiltration rates. Future projects within the Plan Area will incorporate structural stormwater control BMPs that maximize infiltration and/or other volume reduction opportunities on a parcel/site basis. The layout and selection of stormwater BMPs will occur during the projectlevel design process. Examples of PCBMPs and typical locations/configurations are included later in this section.

7.5 Project Level Permit Compliance
Future project applicants are required to adhere to the processing requirements identified in the Salinas SWDS and this Specific Pan, as applicable. Project applicants shall follow the process described below to ensure full compliance with the NPDES permit and City approval:

1. Contact the City of Salinas Permit Center and provide basic project information, including but not limited to the assessor’s parcel number, type of development, and topographic survey.

2. Review fundamentalprinciples ofLIDdesignprovidedin the SWDS.

3. Develop a preliminary project layout utilizing LID design principles for site/parcel-based PCBMPs to the MEP and identifying supplemental stormwater management facilities as described in the Specific Plan.

4. Prepare a Conceptual Stormwater Control Plan (CSWCP) and submit it to the City for review concurrent with other entitlement documents (e.g., tentative map, architectural site review, etc.). The project applicant shall review the preliminary project layout with City staff prior to submitting the Conceptual Stormwater Control Plan for initial comment.

5. Develop final project layout and site improvement plans after approval of Conceptual Stormwater Control Plan and entitlements are received.

6. Prepare a final Stormwater Control Plan in conformance with the PCRs and SWDS. The Stormwater Control Plan shall include design for project level structural stormwater control BMPs and design, as well as design for supplemental stormwater management facilities being installed by the project.

Stormwater and Water Quality Management
207

7. Prepare an Operation and Maintenance Plan in conformance with the SWDS.

The following sections identify stormwater control standards and requirements for individual project level applications within the Plan Area, including LID site design requirements, source control measures, structural stormwater control BMPs, and site design examples.

7.5.1 LID Site Design
Project applicants are required to implement LID site design principles during the preliminary layout development process. LID is a design approachthat strives toprotectwaterresources,predominantlybyreducing runoff associated with urban development. LID site design strategies that are applicable for future projects within the Plan Area include:
• Avoid excessive grading and disturbance to soils;
• Avoid compaction and impervious cover in zones that allow stormwater infiltration;
• Preserve natural features such as significant trees and wetlands; • Minimize the impervious footprint of the project through the use of permeable pavement, reduced street and driveway widths, reduced parking stall dimensions, and reduced parking ratio requirements; • Disconnect impervious surfaces through the use of distributed pervious areas and/or cisterns;
• Use green infrastructure for conveying stormwater runoff, in place of conventional curb, gutter, and subgrade enclosed pipe systems, and in locations where it does not conflict with other development goals and requirements;
• Create bio-retention facilities able to capture and retain the 95th percentile rainfall depth (1.10-inches for Salinas), such as landscape areas with concave grading and amended soils;
• Implement a landscaping design that includes large canopy trees and shrubs to promote evapotranspiration and to provide shade, except where the type and placement could interfere with solar panel use.

All landscaping and irrigation systems shall be in accordance with City Standards and is subject to the approval of City Planner and City Engineer prior to installation.

In compliance with the NPDES Permit and PCRs/SWDS, each project within the Plan Area shall incorporate at least one of the following LID principles in the site layout.
• Direct roof runoff into cisterns or rain barrels for reuse; • Direct roof runoff onto vegetated areas safely away from building foundations and footings, consistent with California building code; 208
City of Salinas | Final Central Area Specific Plan, November 2020 • Directrunoff from sidewalks. Walkways, and/or patios onto vegetated areas safely away from building foundations and footings, consistent with California building code;
• Direct runoff from driveways and/or uncovered parking lots onto vegetated areas safely away from building foundations and footings, consistent with California building code;
• Construct bike lanes, driveways, uncovered parking lots, sidewalks, walkways and patios with permeable surfaces. More features may be required as the size/complexity of each site increased.

Source Control Measures
Project applicants are required to implement source control measures to reduce contact between potential pollutants and stormwater runoff.

Source control measures that are applicable for future development in the Plan Area include but are not limited to:
• Implement LID site design principles;
• Storm drain stenciling and signage;
• Landscaping that minimizes the use of pesticides and fertilizers; • Application methods of irrigation water that minimize runoff of excess irrigation water into the storm drain system;
• Appropriate covers, drains, and storage precautions for outdoor material storage areas, loading docks, repair/maintenance bays, and fueling areas;
• Trash storage areas (enclosures and compactors) designed to minimize the exposure of trash storage areas to stormwater runoff by either locating these indoors or protecting them with stormwater resistant coverings. All exterior non-residential and multifamily trash enclosures and trash compactors shall be in accordance with City code and shall also have a roof cover designed to be architecturally compatible with the primary structures on the site;
• Provide BMPs that prevent and effectively prohibit the following discharges from entering receiving waters or the municipal separate storm sewer system:
− Discharges from indoor floor mat/equipment/hood filter wash racks or outdoor wash racks for restaurants;
− Dumpster drips from trash and food compactor enclosures; − Discharges from outdoor wash areas for vehicles, equipment, and accessories;
− Swimming pool water that has not been de-chlorinated or debrominated; and − Fire sprinkler test water.
• Annual storm drain system and BMP inspection and maintenance; and • Routine litter control and street sweeping
Stormwater and Water Quality Management
209
Post Construction Best Management Practices (PCBMPs)
Where LID site design principles and source control measures are unable to fully manage stormwater quality goals, project applicants are required to integrate structural stormwater control BMPs into the site design. The goal of structural stormwater control BMPs is to treat stormwater runoff to an acceptable level prior to discharge to receiving streams. BMPs shall be designed per the guidelines of the PCRs/SWDS, and to maximize infiltration and/or other volume reduction opportunities where feasible.

BMPs that are applicable for future projects within the Plan Area include but are not limited to:
• Pervious pavement;
• Rain gardens/bioretention basins;
• Flow through planters;
• Infiltration trenches;
• Green roofs;
• Underground retention systems;
• Rain barrels/cisterns; and
• Bioswales/vegetated swales.

The following pages provide examples of some PCBMPs acceptable for use within the Plan Area. All photos and examples provided in this section are provided for illustrative purposes only and do not authorize deviations from other applicable Specific Plan or City Standards.

Infiltration Trench Infiltration Trench
San Mateo County Sustainable Green Streets and Parking Lots Design Guidebook First Edition | January 2009
210
City of Salinas | Final Central Area Specific Plan, November 2020 Green Street and Parking Design
Streets and parking lots are a significant source of pollutants for any urban development. Project applicants shall design streets and parking lots with appropriate stormwater BMPs to effectively treat stormwater on a site/ parcel basis to the MEP prior to discharge to the storm drain system.

BMPs that are applicable for future projects include:
• Rain gardens within curb bulb-outs;
• Flow through planters;
• Pervious pavement for parking stalls; and
• Large canopy trees.

The following pages provide examples of some PCBMPs acceptable for use within the Plan Area when designed in accordance with the SWDS.

Rain Garden Rain Garden
San Mateo County Sustainable Green Streets and Parking Lots Design Guidebook First Edition | January 2009
Disconnected Roof Drains Rain Garden
Remainder of page intentionally left blank
Stormwater and Water Quality Management
211
Pervious Pavement – Parking Lot
Pervious Pavement Construction
Pervious Pavement – Parking Lot
Pervious Pavement – Residential Street
San Mateo County Sustainable Green Streets and Parking Lots Design Guidebook First Edition | January 2009
Site Design Examples
The Specific Plan’s Land Use Plan integrates a mixture of land use densities and types to create a unique and pedestrian-friendly community. The residential land use designations for the Plan Area are described in greater detail in Chapter 2 of the Specific Plan.

Each land use type and corresponding specific residential lot type has unique characteristics, which may make certain stormwater control BMPs listedin the previous sections more applicable than others. Project applicants shall engage in the stormwater evaluation process described in Section 7.04, “Project Level Permit Compliance” to implement LID site design principles to the MEP and select site specific structural stormwater control BMPs.

Figure 7-6 through Figure 7-10 provide conceptual site design examples for a selection of land uses and residential lot types within the Plan Area to detail in concept how these stormwater standards and guidelines may be applied within a specific project. Alternate configurations may be proposed during final project/site design and considered for approval by the City, provided the alternate configurations/combination and size of the proposed PCBMPs comply with the PCRs/SWDS. An example would be substituting a combination of traditional pavement for high traffic areas combined with pervious pavements, the combination being in lieu of all pervious pavement.
212
City of Salinas | Final Central Area Specific Plan, November 2020 Figure 7-1: Location Map
213
Stormwater and Water Quality Management
Figure 7-2: Hydrological Existing Conditions
214
City of Salinas | Final Central Area Specific Plan, November 2020 Figure 7-3: NRCS Soil Classification
Stormwater and Water Quality Management
215
Figure 7-4: Gablian Creek Riparian Corridor
216
City of Salinas | Final Central Area Specific Plan, November 2020 Figure 7-5: Natividad Creek Riparian Corridor
Stormwater and Water Quality Management
217
Figure 7-6: Conceptual Site Design Examples, Large Single Family Homes 218
City of Salinas | Final Central Area Specific Plan, November 2020 Figure 7-7: Conceptual Site Design Examples, Standard Single Family Homes & Greencourt Dwellings 219
Final Central Area Specific Plan
November 2020

8. Public Facility
Financing

8.1 Introduction
This Chapter provides a general framework for the financing and maintenance of public and private improvements in the Central Area Specific Plan.

8.2 Purpose and Scope of Public Facility
Financing Plan
The Central Area Specific Plan is one of three adjoining specific plan areas (the West Area, the Central Area and the East Area) located in the northern portion of the City of Salinas. This Chapter describes how the infrastructure and improvements needed to support development in the Central Area Specific Plan will be financed. Accordingly, this Chapter identifies financing needed to create the infrastructure for the new neighborhoods described in the specific plan. This Chapter also provides a set of principles and policies regarding how these obligations should be met, identifies proposed financing mechanisms, and outlines an action plan for implementing the preferred financing approach.

The property owner is responsible for funding the improvement of their individual properties except as provided herein and/or determined by the development agreement.

This Chapter is provided in accordance with specific plan requirements of the California Government Code and
Salinas Zoning Code.
220
City of Salinas | Final Central Area Specific Plan, November 2020

8.3 Public Facilities
The Central Area Specific Plan comprises approximately 22 percent of Salinas future growth in the Salinas General Plan buildout scenario.

Although this Specific Plan relates only to the Central Area, collaboration and coordination with the other growth areas, the City, utility providers, and other government entities will be necessary to fund all needed public improvements. This comprehensive financing approach assigns improvements (or portions of improvements) to a particular financing Tier, depending on the size of the area the infrastructure improvement benefits. Five such Tiers are recognized as follows:
• Tier One – Regional Benefits. Improvements to a regional interstate highway essential for creating adequate highway capacity for both State and County growth shall be funded with a variety of sources, including federal, State, and regional sources, as well as TAMC Impact Fees collected from the Plan Area.
• Tier Two – Citywide Benefits. Infrastructure projects, including but not limited to major thoroughfare improvements, needed to support new development will be built by developers and/or funded through the City’s Traffic Fee Ordinance (TFO) in place at the time of permit issuance, or as otherwise determined in the development agreement. • Tier Three – North of Boronda FGA-wide Benefits. This Tier consists of projects that will benefit all the new development in the North of Boronda FGA. Beneficial projects for all the West, Central, and East Area Specific Plan areas may be funded by one or more assessment districts and/or impact fee programs that allocate costs to each owner based on benefit received. Examples of improvements that may be included in this funding Tier include, but are not limited to, area roads; sewer and water system expansions; storm drainage solutions; and extension of other utilities.
• Tier Four – Central Area-wide Benefits. Projects that will benefit only the new development in the Central Area will be funded by one or more 1913/15 Act Assessment Districts, Community Facilities Districts (CFDs), or other funding districts or fees applicable to the Plan Area, as requested by the owner and agreed to by the City, which will allocate costs to each owner based on benefit received, which will be calculated by identifying the increase in uses as a result of new or expanded services per State Law. Developers within the Central Area will be required to pay all engineering and financing costs associated with the formation and maintenance of any Assessment District. The types of items that may be included in this funding Tier are internal roads, sewer and water system expansion, storm drainage solutions and projects, open space, and parks. Costs will be allocated based on benefit received. Impact fee credits shall be given (where deemed appropriate by the City) to those who pay or are assessed costs included in City impact fee programs.

Public Facility Financing
221
• Tier Five – Subdivision Maps. Infrastructure improvements and required street dedications, City connection fees, schoolfees,Agricultural Mitigation Fees, and other fees not covered in Tiers 1 through 4 that will be required at the time of approval of each tentative map, or subdivision final maps/agreements and the required improvements will be funded at the owner’s choice by private financing, CFDs, Assessment Districts, or otherfunding alternatives available. Note: City Impact Fees, CentralArea Specific Plan Traffic Fee and Fair Share Traffic Conditions ofApproval Fee will be collected at certificate of occupancy for residential development and at building permit issuance for non-residential development.

It is anticipated that buildout of the Plan Area, along with the development of other areas of the City, will occur over an approximately 20 to 30 year time period. Thus, it is not necessary to build the arterial streets and other public facilities to their ultimate capacity initially unless required to mitigate a significant environmental impact in accordance with CEQA (as part of the Environmental Impact Report MMRP); or meet a General Plan Service Standard; or if applicable, comply with the Project’s Facilities Traffic Management Plan. Similarly, unless required to mitigate a significant environmental impact in accordance with CEQA (as part of the EIR MMRP); or meet a General Plan Service Standard; or comply with the City’s Transportation Management Plan, internal streets and other public facilities shall be constructed in phases as development occurs and the City’s various development impact mitigation fees or other funding alternatives become available, thereby creating the additional capacity as needed to maintain mandated levels of service. The owners/developers are responsible for funding the construction of all streets within the Plan Area (except as provided through the City’s traffic fee ordinance) or as otherwise provided for in this Specific Plan.

WithinthePlanArea,itisexpectedthatthefirstsegmentsofthemajorbackbone infrastructure, such as stormwater drainage improvements and water and sewer extensions, will need to be constructed as development commences, while more localized items such as internal roads will occur as needed to support the on-site residential and mixed use commercial developments.

8.4 Infrastructure and Improvements
The infrastructure requirements for the Plan Area are composed of a variety of infrastructure projects including roads, sewer, water, storm drainage, parks, open space, and other public facilities as discussed in prior chapters of this Specific Plan.
• Roads. Major arterial streets that abut the Plan Area include Boronda Road, Natividad Road, Constitution Boulevard, the future extension of Russell Road and Old Stage Road. These roads will be improved by the developer and/or shall be funded proportionately by the City’s Traffic Fee Ordinance in place at the time of permit issuance, unless otherwise determined by a development agreement.
222
City of Salinas | Final Central Area Specific Plan, November 2020 • Parks. The Central Area includes approximately 43 net acres of public parks and approximately 107 acres of creeks and open space. See Chapters 2, 4 and 9 of the Specific Plan for further discussion of parks and open space.
• Storm Drainage. Total storm drainage improvements will focus on on-site parcel-based and Plan Area shared neighborhood Low Impact Development to the maximum extent practicable. Supplemental retentionanddetentionfacilitiesmaybeusedonlyifon-site stormwater control measures (SCMs) are determined to be infeasible or are needed to provide all the mitigation required on-site due to unfavorable soil conditions from infiltration. Each site shall, at a minimum, provide SCMs for water quality and to maximize infiltration. The long-term maintenance of SCMs will be the responsibility of the property owner (site based), Maintenance Districts (CFDs), Landscape and Lighting Maintenance Districts (LLMDs), and/or assessment districts (public improvements) and/or other types of funding mechanisms, as agreed to by the property owner and the City. These improvements are considered Tier Four costs, specific to the Plan Area. See Chapter 7 for further discussion of stormwater and drainage improvements. • Schools. School facilities are discussed in Chapters 2, 4, 6 and 9. All residential units shall be subject to the payment of school impact fees in accordance with State law and local ordinance. Sites are to be reserved in accordance with the Subdivision Map Act and City Subdivision Ordinance.
• Sanitary Sewerage, Water, and Joint Trench. An array of both wet and dry utilities are planned to serve the Plan Area. This is expected to include water distribution lines, wastewater collection lines, and, in a joint trench, items such as electric distribution, telecommunications, and dark fiber optic conduit. See Chapter 6 for further discussion of utilities.
• Fire Protection and Emergency Services. The Salinas Fire Department provides fire protection and emergency services to properties located in the City limits of Salinas. The Salinas Fire Department is organized into six divisions: Suppression Division; Fire Prevention Bureau; Water Quality SCM Water Quality SCM
San Mateo County Sustainable Green Streets and Parking Lots Design Guidebook First Edition | January 2009
Public Facility Financing
223
Emergency Medical Services (EMS); Training Division; Vehicle Maintenance Division; and Hazmat Team.

The Fire Department currently has six fire stations from which personnel and equipment respond to emergency calls. The Fire Department headquarters is located downtown at 65 West Alisal Street. Station 5 is located on Rider Avenue near the proposed Central Area Specific Plan. The designated response area for Station 5 includes a large portion of the Plan Area. Station 6 is located on Bolivar Avenue near the West Area Specific Plan. The designated response area for Station 6 includes a portion of the Plan Area. The remaining portions of the Plan Area not located within the designated response area for either Station 5 or 6 will be served by a new fire station located in the Central Area.

General Plan Table LU-4 includes a fire protection and emergency services standard that calls for the provision of necessary fire protection facilities to achieve a 6-minute response (from receipt of a 911 call to arrival of first company) 90% of the time. In January 2015, the Fire Department conducted a Fire Station Needs Assessment for the North of Boronda FGA. The report concluded that based on current City standards that the Fire Department would need new fire station locations to cover the North of Boronda FGA. In this regard, a new fire station will need to be constructed on an approximate 2-acre site located at the northeast corner of Natividad Road and the southerly greenway street (within the Plan Area) as development occurs to meet the General Plan standard and serve both the Central Area Specific Plan and the West Area Specific Plan.

The developers of the Central Area Specific Plan and the West Area Specific Plan will contribute their fair share of the costs of acquiring the developed land and construction of the fire station through the payment of City Public Facilities Impact Fee program. A second fire station will need to be located and constructed in the proposed East Area Specific Plan Area if and when the East Area of the FGA is developed. The Public Facilities Fee has been adopted by the City of Salinas to finance these new fire station when future development warrants their construction.

It is expected that one truck company and one engine company (consisting of 23 firefighters) and associated equipment/vehicles is required to staff the proposed station on Natividad Road and maintain adequate service to the Specific Plan and greater North of Boronda FGA in accordance with General Plan Public Services and Facility Services Standards. According to the fiscal analysis prepared for the West and Central Area Specific Plan (2018), the tax revenue from the project will exceed the costs related to the provision of City services required for the project, including, without limitation, those related to fire services.
224
City of Salinas | Final Central Area Specific Plan, November 2020 New residential and commercial structures constructed in the West and Central Specific Plan Areas will be equipped with automatic fireextinguishing (fire sprinkler) systems as required by the California Fire Code as adopted and amended by the City of Salinas. Sprinkler systems reduce the spread of a fire or may extinguish minor fires.

Automatic fire-extinguishing (fire sprinkler) systems, as required by the California Fire Code, increase life safety, limit structural damage, and significantly increase the safety of the responding fire department personnel; however, these systems do not increase the allowable response time for Emergency Medical Services (EMS), which are also supplied by the City’s Fire Department. Consideration may be given to providing a home in the interim for an EMS team early in the development and a full service fire station will be built later in the development process.

An on-site water system capable of providing adequate fire flow (per Fire Marshal’s requirements) and in accordance with all applicable rules and regulations is required in the Specific Plan Area. The Salinas Fire Department shall review and approve the fire hydrant placement, pipe sizes, and emergency vehicle circulation with each tentative map. SFD shallreview and approve final improvement plans in conjunction with the final map and subdivision improvement plan review. Water main pressures shall be sufficient to serve fire sprinkler systems installed within structures. Unless otherwise required by the Fire Chief/ Fire Marshal, residential area fire hydrants shall be CLOW 950, while commercial area fire hydrants shall be CLOW 960 or as otherwise approved by the Fire Marshall at the time of development.

Fire apparatus access roads shall be provided and maintained in accordance with California Fire Code (Section 503.1.1 through 1.3 and Appendix D, or as may be subsequently amended), in effect at the time of building permit application. All fire apparatus access roads shall consist of all-weather surface consisting of asphalt, concrete, or other approved all-weather driving surface capable of supporting the imposed load of Salinas Fire Department fire apparatus weighing at least 67,000 pounds, or as approved by the City Engineer. At the time of construction, a construction vehicle access road capable of accommodating fire equipment loads and turning movements identified by the Fire Chief shall be provided before combustible materials can be delivered to the site. Provisions for on-site water and/or other fire suppression shall be addressed concurrently with the vehicle access.

Development in the Specific PlanArea shall be subject to the California Building Code and Fire Code requirements in effect at the time of submittal of a building or grading permit application.
• Police Services. The Salinas Police Department provides full municipal law enforcement services for the North of Boronda FGA, including the Plan Area.

Public Facility Financing
225
General Plan Table LU-4 includes a police protection public service and facility standard that calls for police facilities to provide an adequate level of service as determined by the City. The City of Salinas Police Department provides full municipal law enforcement services for the North of Boronda Future Growth Area including the Plan Area. The Police Department recently completed a new police headquarters on East Alisal Street in March of this year (2020) and will provide services for the Plan Area from that facility. In this regard, the City determined that the new single centralized police facility serving the entire City (including the Plan Area) was preferred over a police substation located in the North of Boronda FGA to serve the future growth in the northern portion of the City.

The Salinas Police Department is organized into three divisions:

Field Operations, Administration, and Investigations. The Police Department staffs three patrol shifts per day. The City is separated into 12 beats in four command areas for reporting and assignment purposes. Officers are normally assigned to work one or more beats within a command area. Currently, one to two officers are designated to serve the proposed project during the day shift, one to two officers during the swing shift and one to two officers during the graveyard shift.

It is expected that 17 additional police officers and associated equipment/ vehicles will be required to adequately serve the Plan Area and maintain adequate service levels to existing development in accordance with the applicable General Plan service standard.

According to the fiscal analysis prepared for the West and Central Areas (2018), the City’s revenue from the project will exceed the costs related to the provision of City services required for the project including, without limitation, those related to police services.

The Central Area will contribute its fair share of the costs of construction of the new central police facility through the payment of City Public Facilities Impact Fee program.
• Library Services. The City currently owns and operates three libraries, which serve City residents. The Steinbeck Library, the El Gabilan Library and the Cesar Chavez Library. General Plan Table LU-4 includes a library services and facilities standard that calls for 0.5 square feet of public use library space per capita and library services to be provided within two miles of any residential use.

The City has identified a two net acre site in the Central Area between the Village Center and the middle school for a new branch library to serve the East, Central, and West areas of the North of Boronda FGA.

Based on the two-mile service area prescribed in the General Plan, the new branch library will also service existing residents in areas of the City south of Boronda Road.
226
City of Salinas | Final Central Area Specific Plan, November 2020 Additional library staff will be required to staff the proposed facility and maintain adequate service to existing development in accordance with General Plan Public Services and Facility Services Standards.

The fiscal analysis prepared for the West and Central Areas (2018), the revenue from the project will exceed the costs related to the provision of City services required for the project including, without limitation, those related to library services. The Specific Plan provides that the Plan Area will also contribute its fair share of the costs of construction of the new library facility through the City Public Facilities Impact Fee program.
• Recreation Center(s). The City seeks to develop one or more recreation centers within the community park in the adopted West Area Specific Plan and within a neighborhood park in the Central Area Specific Plan and future East Area Specific Plan. The precise location, configuration, and staffing of these recreation centers are yet to be determined by the City. Staffing needs may be one full-time coordinator and up to 10 temporary employees, depending on the size, type, and services of the recreation center. The timing and phasing of construction of the recreation centers will be determined by the City. According to the fiscal analysis prepared for the West Area and Central Areas (2018), the tax revenue from the project will exceed the costs related to the provision of City services required for the project, including, without limitation, those related to recreation services.

The Plan Area will contribute its fair share of the costs of construction of the recreation centers through the City Public Facilities Impact Fee program.

8.5 Public Facilities Financing
The City shall provide a similar level of municipal services in the Plan Area as provided elsewhere in the existing City, except as required by the General Plan or noted in the Central Area Specific Plan.

Many of the public facilities proposed to serve the North of Boronda FGA (for example, the new fire/EMS station, the proposed branch library, construction of a new police station, and new recreation centers) are facilities that will serve existing City residents and residents of other new neighborhoods. As a result, these facilities will also address existing facility or service level deficiencies.

New development within the Central Area will contribute their fair share to the cost of new public facilities by way of impact fees. A City-wide Public Facilities Nexus Study was prepared and approved by the City of Salinas in 2014, which established the methodology and criteria to be used to determine the impact fees for these facilities (e.g., police, fire, library, and recreation centers). In other cases, impact fee programs for other public facilities (including but not limited to roads, sewers, storm drains) have already been adopted. New development within the Plan Area will be required to pay the fees in effect at the time of Certificate of Occupancy Public Facility Financing
227
for residential development and at building permit issuance for other types of development in accordance with City policy, or as specified in the Development Agreement. Property owners will be responsible for service and/or connection fees for water, sewer, schools, electricity and gas, telecommunications, and solid waste and recycling.

As discussed in Section 8.4, new development is subject to the payment of school fees in effect at the time of building permit issuance.

8.5.1 Financing of Street Improvements
Traffic Fee Ordinance (TFO) Financed Streets
Three of the major arterials adjacent to the Central Area are major arterials serving areas of Salinas (serving both the plan area and other areas outside the Plan Area); these are Boronda Road, Natividad Road, and Constitution Boulevard between Boronda Road. The future extension of Russell Road will also serve the Plan Area and areas beyond upon construction. Each of these existing roads are designated in the General Plan as an expressway or an arterial. A fourth arterial road, Old Stage Road, serves the Plan Area, the northern portion of the FGA and the County land to the east and north.

Each of the arterial streets is a non-access road, meaning direct access to abutting property is not allowed. On-street parking is also prohibited on these arterial streets.

Developer fair share costs of roadway improvements, not included in the TFO or which are otherwise the responsibility of the developer may be funded by a Central Area Specific Plan Traffic Fee or the Fair Share Traffic Conditions of Approval Fee, as applicable (see Appendix B, Definitions for explanation of these fees) or as otherwise determined by the Development Agreement.

8.5.2 Developer Financed Streets
Abutting Street Improvements
City of Salinas Ordinance No. 2585 requires that each property owner provide frontage improvements as follows: “The frontage of each lot shall be improved to its ultimate adopted geometric section, including, but not limited to, street, structural section, curbs, gutters, sidewalks, driveway approaches, and transitions.” Resolution No. 18729 requires that a minimum of half of the abutting street be improved, but in no case shall less than 20-feet of pavement from the gutter lip be improved. Therefore, all Central Area owners are required to dedicate and improve or be assessed for land and improvements in accordance with the requirements of Resolution No. 18729. Where there are non-access roads adjacent to the Central Area boundaries, they shall be improved in accordance with the requirements of Resolution No. 18729 and funded by the Central Area Specific Plan Traffic Fee.

Where streets front on public facilities and public parks, the cost of the land and improvements for the half of the abutting street along the 228
City of Salinas | Final Central Area Specific Plan, November 2020 frontage of all such public facilities and parks shall be funded by the same funding method used to acquire and improve the abutting public facility or public park except the developer shall be responsibility for the full cost of the land and the half of the abutting street if dedicating the land to the City and constructing a public park in lieu of the paying the Central Area Park Impact Fee (CAPIF) for the said park or as otherwise specified in the Development Agreement.

Greenways
“Greenways” means the south side of the northerly greenway street (and the northerly greenway path/sidewalk) and the north side of the southerly greenway street (and the southerly greenway promenade/path) as shown in Figure 2-1, Specific Plan Land Use Map, Figure 5-4, Existing Arterial Transportation Facilities and Appendix K. These greenways streets and paths/sidewalks will be constructed by the developer as part of the applicable phase, or as otherwise required the City Engineer. The streets are generally afforded non-exclusive on-street parking along their frontage and direct pedestrian access with only very limited driveway or alley access across both the southerly and northerly greenway paths as specifically provided for in the Specific Plan and approved by the City Engineer.

The southerly greenway street will have special treatments that include custom decorative street lighting, landscape planters, street furniture (such as benches, trash receptacles), way-finding directional signage and other features as provided by the Specific Plan. These special treatments are to be consistent along this greenway segment as it extends through the Plan Area. The northerly greenway street will have the same decorative street lighting as that used for the southerly greenway street, since this street/path will also extend the length of the Plan Area. See Chapter 5 for additional discussion regarding these greenway
Phasing of Facilities
Buildout of the Plan Area, and the resulting need for public facilities, will occur over an extended period of time that will be influenced by market conditions, including demand and need for housing and services, and willingness of owners within the Plan Area to participate in the development process. As development occurs, each application will have to demonstrate that the need for public facilities and the General Plan service standards are being met. Consequently, it will not be necessary to build the public facilities to their ultimate capacity at the outset of the development. Development of the public facilities can be phased as development goes forward and creates the need for additional capacity and as the funds become available through the payment of the Public Facilities Impact Fees. The fire station, the branch library (located in the Plan Area), and the recreation center are examples of facilities that can be constructed in phases as determined appropriate by the City to serve the gradual growth of the population and service needs in the Plan Area.

Public Facility Financing
229
Review of tentative map applications in the Plan Area will provide both the City of Salinas and developer(s) opportunities to assess current and future needs of the Plan Area.

Financing of Public Parks
Each subdivision within the Plan Area is responsible for land dedication and improvements for parks or the payment of Park Impact Fees per the State Quimby Act, to provide the equivalent of three acres of developed park land per 1,000 population, as set forth in the City’s General Plan and Section 31-802 of the City Subdivision Ordinance. Dedication of park land shall occur concurrently with the recording of final subdivision maps.

Park improvements will be provided in accordance with the conditions of approval on the first final subdivision map.

The City’s current City-wide park impact fee is not adequate to cover the cost of acquisition and development of the neighborhood parks and small parks needed to meet park requirements within the Plan Area. The City agrees to adopt a new Central Area Park Impact Fee (CAPIF), which shall be assessed against the properties designated for park lands and facilities inside the Plan Area. The fee shall be set to generate sufficient funds forthe acquisition and development of the neighborhood parks and small parks within the Plan Area. The fee shall include costs to be acquire the land, cost of park improvements, the half of the abutting streets that abut the parks, Low Impact Development SCMs to meet the requirements of the SWDS, decorative street lighting, and utilities. Park improvements shall be required in accordance with the City’s Park and Sport Facility Standards.

The Plan Area owners shall not be required to pay the Citywide Park Impact Fee upon adoption of the CAPIF by the City. Developers may elect to either fully improve (including the cost of park improvements, the half of the abutting streets that abut the parks, LID SCMs to meet the requirements of the SWDS, decorative street lighting, and utilities) and dedicate parks to the City as described above or pay the CAPIF. If a developer fully improves and dedicates parkland as described above to meet his parkland obligations for the applicable subdivision, they will have been deemed to fully satisfy their parkland obligation and no payment of the CAPIF is required.

Alsosee Section9.2.2,Parks Implementationforfurtherdiscussionofparks.

8.6 Funding Policies
The following policies govern the funding of infrastructure and public facilities for the Central Area Specific Plan, unless otherwise provided for in the Development Agreement. The policies shall guide future decisions regarding formation of financing entities, adoption of financing mechanisms, and project approvals.
• Policy 1: The Financing methods shall be consistent with and serve to reinforce the Land Use Plan and subsequent development of the Plan Area.
230
City of Salinas | Final Central Area Specific Plan, November 2020 • Policy 2: If Assessment District financing is requested by an owner or developer, a detailed financial analysis that estimates the costs of improvements and how the infrastructure costs will be allocated and the estimated bonding ability shall be prepared by an engineer approved by the City and the developer for each proposed Central Area Specific Plan assessment district. The owner or developer is responsible for funding the cost of the financial analysis and all costs of forming the district.
• Policy 3: The City shall require dedication of land for internal road improvements that allow on-street parking and direct pedestrian and vehicle access to the abutting property, if an LLMD will be maintaining the right-of-way improvements. The City may require dedication of land as described above if a homeowners or owners association (for private roads only) will be maintaining the right-of-way improvements on such streets. If not dedicated, the City will require an emergency and maintenance access easement for any private street.

If a LLMD is not maintaining the right-of-way improvements, the dedication of road improvements and other required infrastructure shall be in accordance with City Resolution 18729. and other required infrastructure shall be installed in accordance with City standards. • Policy 4: Landowners may be subject to assessments to pay for Plan Area infrastructure facilities only if benefit is received and only in proportion to the benefit received. The property owners will also be required to pay the cost for related nexus and engineering studies as required by the City Engineer.
• Policy 5: Developer will pay City development impact fees at Certificate of Occupancy for residential development and at building permit issuance for other types of development in accordance with City policy. School development impact fees in effect at that time will be paid at building permit issuance, and all school sites shall be reserved in accordance with the Subdivision Map Act and the City Subdivision Ordinance.
• Policy 6: Infrastructure and public facilities triggered by development within the Plan Area that provide benefits beyond the Plan Area and which are listed in a City, County or School District Impact Fee program may be funded through the appropriate development impact fee fund, only if said funds are available and the legislative body approves the allocation of funding for such purpose. • Policy 7: If an Assessment District is formed, infrastructure costs shall be proportionately allocated among Central properties based on the principle of “benefit received”. If an Assessment District is used, Impact Fee Credits may be distributed to those who are assessed for Impact Fee-related costs as determined appropriate by the City. • Policy 8: A mechanism(s) for securing the financial obligation for an equitable share of infrastructure costs on all benefiting property Public Facility Financing
231
owners shall be included in Assessment Districts and Impact Fees established in the Central Area.
• Policy 9: The City may establish Assessment District(s) within the Plan Area pursuant to related statutory authority and procedures if requested by the owners of a majority of the land proposed to be assessed.
• Policy 10: A CentralArea Park Impact Fee (CAPIF), shall be established by the City pursuant to the provisions of California Government Code Section 66000. This fee, upon adoption, replaces the Citywide Park Impact Fee. Alternately to paying this fee, project proponent shall dedicate and improve the park(s) and half of the abutting streets that abut the park(s) shown on their land in Appendix G.
• Policy 11: To ensure timely funding of infrastructure development and achieving other public benefits, the City may require subsequent development agreements with landowners and/or developers, pursuant to City policy and ordinances in effect at the time the development agreement is entered into.
• Policy 12: Utility and other infrastructure costs that are determined to benefit properties outside an owner’s or developer’s lands shall be reimbursed through assessments against the benefiting properties or as otherwise provided in accordance with provisions of the City of Salinas Resolution No. 12963 or 18729, as applicable.
• Policy 13: If a CAPIF is adopted, the City shall establish a mechanism within the ordinance that credits the cost against subsequent fee obligations if a developer or the CAPIF builds infrastructure items that are included in a City-wide Impact Fee program.
• Policy 14:TheCityshallformaCentralAreaLLMDand/ormaintenance CFDs concurrent with recording of the first final subdivision map. • Policy 15: The City may pursue outside funding for infrastructure improvements serving the Plan Area, e.g., State and federal funding sources, etc. for improvements.
• Policy 16: The City and developer(s) shall work cooperatively to secure Central Area Specific Plan infrastructure financing through allocation of appropriate funds (e.g., Impact Fees, Traffic Fee Ordinance) and establishment of necessary financing entities and arrangements (e.g., an assessment district, LLMD, etc.).
• Policy 17: To ensure timely funding of infrastructure development, one or more property owners and the City may establish development agreement(s) to confer development entitlements.
• Policy 18: The City may establish an Assessment District to provide necessary land-secured debt financing if requested by one or more property owners within the boundary of the proposed district, or as otherwise required by state law.
232
City of Salinas | Final Central Area Specific Plan, November 2020

8.7 Financing Mechanisms and Resources
A number of financing mechanisms may be used to fund the public services, facilities, and infrastructure associated with the Plan Area. Table 8-1 provides a conceptual summary of costs and possible funding sources and funding mechanisms. The ultimate mix of financing mechanisms will be determined in the implementation process, based on final technical analyses of costs, benefits, and burdens, and on deliberations involving City staff, property owners, developers, elected officials, bond counsel, underwriters, and finance experts at that time. There may also be new financing mechanisms that evolve at the State or federal level and nothing in this Plan limits the consideration of those new mechanisms by the City and/or the developers or owners.

8.8 Maintenance Responsibilities
Inadditiontotheobligationtofundconstructionofbackbone infrastructure and Citywide improvements through development impact fees, the property owners within the Central Area Specific Plan will fund certain recurring City costs for maintenance. This Financing Plan identifies and incorporates provisions for funding certain City maintenance activities within the Plan Area.

The City, through the draft Public Services and Public Facilities Financing Plan – Salinas Future Growth Area (November 2, 2007), has suggested the establishment of a Community Facilities District (CFD) and/or LLMD Cost Category
Proposed Funding Source
Developer
Debt
Financing (1)
City Fee
Programs (2)
School
District Fee
TAMC and State
and Federal (3)
Arterial Streets X X X
Neighborhood
Streets X
Landscape X
Storm Drainage (4) X X
Water X
Sanitary Sewer X X
Joint Trench X
Grading X
Schools X X
Recreation Center X
Public Parks X X
(1) Developer may propose the use of Assessment Districts or special districts for certain public facilities and receive fee credits.
(2) Certain facilities may be funded through City development impact fees. Credit against fees may be available for facilities included in a fee program where applicable and approved by the City. (3) Funding may be available from regional, State and/or federal sources. (4) If LID PCBMPs are installed on a site/parcel basis then Storm Drainage impact fees will not be charged.

Table 8-1: Proposed Funding Sources (or as per Development Agreement) Public Facility Financing
233
to provide public maintenance services to the North of Boronda FGA in excess of service levels elsewhere in the City.A higherlevel of maintenance may be desired for the North of Boronda FGA and the residents living in the area would pay for that enhanced service through an LLMD or a maintenance CFD. An LLMD would be formed to pay for other maintenance as specified below. The maintenance of other public facilities not addressed in this section of the Specific Plan will be addressed in the Development Agreement.

8.8.1 Landscape and Lighting Maintenance District
The Central Area LLMD will be formed to pay for the following costs within the Central Area Specific Plan:
e) Maintenance of public parks less than two net acres in size and maintenance of all open space areas allowing public access. f) Operation and maintenance (including replacements as needed) of all street and path lighting.
g) Maintenance of all LID areas within public or Owners Association streets/parcels and ROWs and in supplemental detention and retention basins/open space creek corridors.
h) Slurry coating of all interior streets and alleys as determined by the City Engineer, but not less than every five to seven years depending on the deterioration of the asphalt.
i) Maintenance and replacement of the public paths/sidewalks, decorative street furniture and traffic/street signs.
j) Maintenance of all traffic calming devices such as the center median islands, roundabouts, bulb-outs, and traffic circles, including landscaping.
k) Maintenance of the landscaping and walls in the ROW within the abutting half of the ROW of the arterial streets surrounding the Plan Area.
l) Maintenance of alleys (including paving) and adjacent landscaping within alley ROWs or easements.
m) Maintenance of landscaping located within the public ROW and landscape easement of the northerly and southerly greenway streets. n) Maintenance, trimming, and replacement of all trees including street trees on all public property including small parks.

If an LLMD is used to maintain the public area, the City shall administer the Central Area LLMD as follows:
a) Prepare and make available an annual accounting of all LLMD revenue and expenditures and reserve deposits and expenditures. b) Prepare the annual estimate of operating costs and required capital replacement reserves, allocation of benefits, and assessment for the LLMD, and process the same through City Council approval as paid for by the LLMD. The Central Area LLMD shall pay for the annual 234
City of Salinas | Final Central Area Specific Plan, November 2020 Engineer Report of the projected costs and Maintenance District Map/ property changes as subdivisions are approved; along with staff costs to manage the LLMD. The annual report shall also be provided to any Homeowners’ Association established within the Plan Area. c) Administer the contracts for operation of the LLMD, including bidding, preparation of contracts (which shall require a high standard of workmanship and maintenance), and management of the contractors, including inspection of their work on a regular basis to ensure contractor compliance with the scope of work.
d) Collect LLMD revenues and process and pay all legitimate invoices of each LLMD in a timely manner.
e) The City shall be reimbursed for the direct labor costs for the staff needed to perform the City’s required contract administration and contractor supervision and inspection, plus a standard percentage of the direct labor cost to cover the City annual adopted overhead rate and administration.
f) Establish a reserve account to be used to pay the costs of the LLMD between the beginning of the fiscal year and the LLMD’s receipt of the first increment of assessments. A six-month operating reserve, required at the beginning of each fiscal year, is to be replenished each year throughout the life of the LLMD.
g) Operating reserves at the end of each fiscal year in excess of 50 percent of the estimated operating costs for the forthcoming year shall be carried forward to reduce the assessment for the forthcoming year. h) Assessment district costs shall be assessed against the benefitting property at the time they become due.
i) A Major Repair and replacement Reserve Fund shall be established by the LLMD to fund items such as major repairs and equipment replacements, which have a useful life longerthan one year(examples:
future replacement of playground equipment, street lights, street overlay, and future slurry coating of streets). The required replacement reserve balance shall be calculated each year by dividing the current cost of each item by its original useful life and then multiplying the result by the number of years the item will have been in service by the end of that fiscal year. The portion of the assessment for replacement reserves shall be deposited and maintained in a separate interestearning replacement reserve account and shall not be commingled with other funds.
j) All LLMD work shall be performed by qualified and licensed private contractors. Contracts shall be awarded to the lowest responsible bidder, after competitive bidding. In a time-critical or emergency situation, the City staff may perform the work and the LLMD shall reimburse theCityforits costs,includingoverheadandadministration. k) The maximum assessment rate may be adjusted by the greater of three percent, the percentage increase in the Consumer Price Index (“CPI”), or the percentage increase in the Engineering News Record (“ENR”) Public Facility Financing
235
cost index. Each year, the City shall compute the percentage difference between the CPI on December 31st for the most recent year and the CPI for the previous December 31st as determined by the Bureau of Labor Statistics forthe San Francisco/Oakland/San JoseArea.A similar computation will be performed by the City using the ENR April issue cost index. The cost will be increased each year based on the average of the common labor and materials costs in ENR’s April issue. The greater of three percent of the percentage change in indices shall then establish the range of increased assessments allowed for the current fiscal year. The maximum allowable increase may be exceeded with a positive vote of a simple majority of the parcel owners weighted by the amount to be assessed against each parcel, or as otherwise prescribed by law.
l) The cost of alley maintenance, including maintenance of the landscaping and paving, shall be charged only to the parcels served by alleys.
m) An LLMD shall be formed by the City for the Plan Area as soon as possible after the first final subdivision map is approved within the Central Area. The LLMD shall include only the area within the first final Subdivision Map. The area within each subsequent Final Subdivision Map shall be annexed to the first LLMD.
n) The LLMD may be voted out of existence under State law, and in such a case, the City of Salinas will require that, prior to the dissolution of the LLMD, a Home Owners’ Association or other responsible entity is established and becomes legally obligated to maintain the same improvements at an equal or greater level as the LLMD proposed for dissolution.

8.9 Reimbursements
The City enacted a reimbursement ordinance, applicable to the Central Area Specific Plan (effective date June 3, 2014, no. 2549, and amendment no. 2590 on February 21, 2017) whereby the City and owners or developers of lands within the Plan Area who have advanced more than their fair share of the costs of annexation and preparation and processing of the Specific Plan (including CEQA compliance documents) on behalf of all of the owners of lands within the Central Area will be reimbursed fairly and proportionately for those identified costs. The reimbursement ordinance establishes the method to reimburse a person or the City for financing the City Costs, the Annexation Costs, and the Entitlement Costs. It is to be used to mitigate the cost of financing such activities by distributing those costs fairly and proportionately among the owners of property within the North of Boronda FGA, at the time those benefitted property owners exercise their development rights under one of the specific plans or otherwise make use of the preparation and approval of any of the specific plans. Reimbursements shall be in accordance with the City’s Reimbursement Ordinance. The Reimbursement Ordinance is included as Appendix M to this Specific Plan.
236
City of Salinas | Final Central Area Specific Plan, November 2020 Remainder of page intentionally left blank

8.10 Fiscal Analysis
A fiscal analysis (2018) for the project was prepared by Economic & Planning Systems, Inc. (EPS) and is on file at the Salinas Community Development Department located at 65 West Alisal Street. 237
Final Central Area Specific Plan
November 2020

9. Implementation and
Administration

9.1 Introduction
This Chapter of the Central Area Specific Plan describes mechanisms forimplementing the Specific Plan and the systematic development of land within the boundaries of the Plan Area.

The Chapter should be consulted prior to preparing entitlement applications and whenever a question arises concerning plan implementation. Because the City of Salinas is the public agency responsible for the administration of the Specific Plan, the tools and procedures described in this Chapter are to be implemented in a manner consistent with federal, State as well as City rules, regulations, and policies.

This Chapter also summarizes the Specific Plan entitlement process and approvals. Actions needed to implement the
Plan are generally of three types: (i) those needed to obtain entitlement approvals; (ii) implementation actions described in association with policies contained in the Specific Plan including mitigation measures contained in the Central Area Specific Plan EIR and MMRP; and (iii) development phasing and financing mechanisms discussed in Chapters 8 and 9 of this Specific Plan.

The mitigation measures identified in the 2002 Salinas General Plan Final Environmental Impact Report (FEIR) and the 2007 Final Supplement for the Salinas General Plan Program EIR shall also apply to the project and are incorporated herein by reference. 238
City of Salinas | Final Central Area Specific Plan, November 2020

9.2 Specific Plan Authority and Implementation
The Central Area Specific Plan, upon approval by the Salinas City Council and certification of the FEIR, will constitute the basis for the review of all subsequent entitlements in the Plan Area. As a regulatory document, the Specific Plan establishes the land use and associated development, design, and infrastructure standards that must be met to successfully implement the project.

Through the inclusion of development regulations, design, and infrastructure standards, and incorporation by reference of the applicable Salinas Zoning Code provisions, the Specific Plan creates zoning regulations and standards specifically applicable to the Plan Area. As a regulatory document, all subsequent design documents and development activities in the Plan Area are required to be consistent with this Plan. The Specific Plan identifies development regulations that are different from current Salinas Zoning Code requirements where it is necessary to achieve General Plan consistency and intent, and, by extension, Specific Plan goals for the Plan Area. In instances where the requirements of this Plan conflict with the applicable Salinas Zoning Code or other City standards (except for federal and/or State Building Code, Fire Code, and Stormwater Program requirements [including NPDES Permit/SWDS/SWSPS]), the Central Area Specific Plan shall control. Conversely, if this Specific Plan is silent on an issue, the applicable Salinas Zoning Code regulations or other adopted City standards and regulations shall prevail, as determined by the City Planner.

9.2.1 City Administration
The City of Salinas shall be the public agency responsible for the administration, implementation, and enforcement of the Central Area Specific Plan, except for the administration, enforcement and implementation of private property maintenance agreements (excluding NPDES maintenance requirements), covenants, conditions and restrictions (CC&Rs) or reciprocal easement agreements (REAs), which will be the responsibility of a Home Owners Association, Business or Owners Association, or other private entity as approved by the City.

The following sections describe the review and entitlement procedures for subsequent projects within the Plan Area.

The one exception to these policies is school facilities. Per State law, the applicable school district shall determine the need for such facilities and shall regulate the development of school sites.

Applicability of the Specific Plan to the Settrini, Igaz Ranch and Garcia Properties
As previously discussed in Chapter 1, the properties (or lands) which make up the Central Area Specific Plan area were annexed into the City of Salinas in 2008, except for approximately 85 gross acres located in the northwestern portion of the Plan Area. These lands (currently known as Implementation and Administration
239
the Settrini, Igaz Ranch and Garcia properties, respectively) are located within the City’s Sphere of Influence (SOI) but not within City limits. As such, the Central Area Specific Plan will not be applicable to or govern the future development of these properties until such time that 1) the property owners desire to annex the subject properties into the City, 2) all applicable project entitlements (Annexation, Pre-Zone, Development Agreement, etc.) and any required CEQA review have been approved by the Salinas City Council, and 3) the Local Agency Formation Commission (LAFCO) of Monterey County approves the annexation request. For these reasons, all figures and text in the Central Area Specific Plan (as they pertain to these properties) have been provided for conceptual planning purposes only.

Following annexation of these properties, any development proposed for these properties shall be in accordance with this Specific Plan. In the event that these property owners (or subsequent owners) do not wish to develop their properties in accordance with the Central Area Specific Plan, a Specific Plan Amendment or new Specific Plan, as applicable, will be required and be subject to the approval of the City Council before these properties are annexed into or developed within City limits.

9.2.2 Parks Implementation
The following provisions shall apply unless otherwise specified in the Development Agreement. For a discussion of parks financing, refer to Chapter 8.

Neighborhood and Small Parks
The Central Area Specific Plan includes the requirement for seven neighborhood parks and ten small parks comprising approximately 44 acres of parkland. The design, implementation, and funding of the improvements to the neighborhood and small parks are guided by the following policies:
• Land and Improvement. Each property owner/developer shall design and improve the park and half of the abutting streets that abut the park on that property owner’s land and shall dedicate the park to the City or shall pay the Central Area Park Improvement Fee (CAPIF). An LLMD shall be formed for the maintenance of small park maintenance (see Section 8.8).
• Timing. Dedication of neighborhood and small parks shall occur concurrently with the recording of final subdivision maps, and all park improvements will be provided in accordance with the City requirements.
• Land Acquisition.
− Where not required by the City to be dedicated and improved or where the property owner elects to dedicate and build the parks and half of the abutting streets that abut the parks in lieu of paying the CAPIF, the land for the neighborhood and small parks shall be acquired by the City using funding from the CAPIF.
− Property owners acquiring, dedicating, or advancing funds for 240
City of Salinas | Final Central Area Specific Plan, November 2020 acquisition of any part of neighborhood and/or small park land and the abutting fully improved streets prior to acquisition by the City shall provide the net park acres that property owner/developer must provide in accordance with Table 4 1 Park Summary. − If the value of the land acquired or dedicated exceeds the amount of CAPIF fee credits usable by the owner making the acquisition or dedication, the City shall enter into a reimbursement agreement with the property owner whereby the acquiring or dedicating owner will be reimbursed from future CAPIF for the difference between the park fee credits received and the value of the land acquired or dedicated, with interest where determined by the City that such fee credit and reimbursement is appropriate or as otherwise specified in the Development Agreement. The fee credit forland will be a maximum of $250,000 per acre and will be adjusted annually by the construction cost index change as published by the Engineering News Record in April unless otherwise specified in the Development Agreement.
− No fee credits will be due to the property owner or developer if they elect to dedicate and the build the park and half of the abutting streets that abut the park in lieu of paying the CAPIF. • Improvements.
− The improvements constructed in the neighborhood and small parks shall be not less than those required by the State Quimby Act, City Subdivision Ordinance, the City’s Park Classifications and Sport Facility Standards and other applicable City regulations and are subject to the approval of the City before dedication and/ or acceptance.
− The cost of neighborhood and small park improvements shall be funded by the property owner or developer of the park as provided in this Specific Plan and shown in Appendix G.
− Property owners/developers constructing neighborhood and small park improvements prior to funding by the City from the CAPIF shall receive CAPIF credits equal to the costs of the improvements installed by the owner, where the City determines a credit is appropriate. No credits shall be due prior to inspection and acceptance of park improvements by City. No fee credits will be due to the property owner or developer if they elect to dedicate and build the park and half of the abutting streets that abut the parks to fully meet their park obligations in lieu of paying the CAPIF. • Financing.
− The City shall enact a new CAPIF pursuant to the Mitigation Fee Act (Government Code Section 66000 et seq.) sufficient to fund the acquisition and improvement of the neighborhood and small parks in the Central Area (see Chapter 8, Section 8.5, Financing of Parks). − The land for the neighborhood and small parks and for the half of the abutting streets that abut the parks shall be acquired from Implementation and Administration
241
the property owners using accumulated CAPIFs, unless such parks and half of the abutting streets that abut the parks are improved and dedicated by the property owner/developer without using accumulated CAPIFs, in which case a CAPIF credit would not be issued.

CAPIF Credit – All Parks
A CAPIF credit shall be assigned to each property owner for land dedicated and improved, neighborhood parks, and small parks, based upon the estimated acreage of the land being dedicated at the time of the dedication, and the cost of improvements provided thereon as provided herein, including the cost of the half of the abutting streets that abut the parks, LID SCMs to meet the requirements of the SWDS, and decorative street lighting and utilities, unless the property owner elects to dedicate the land and fully improve build the applicable park and half of the abutting streets that abut the park rather than pay the CAPIF to satisfy their Quimby parkland requirement or as otherwise specified in the Development Agreement.

9.3 Project Review Procedures
Individual development projects within the PlanArea are subject to review and approval by the City of Salinas. Application, fee, and processing requirements shall be in accordance with the City’s Municipal Code and other regulations in effect at the time of the application submittal, unless modified by this Specific Plan or a Development Agreement. The City may impose conditions as are reasonably necessary to protect the public health, safety and welfare of the public, when acting to approve a subsequent project or permit, to ensure that the proposed project is in compliance with the Specific Plan and all applicable laws and regulations.

After application submittal, the City will conduct a review of the project application for completeness and consistency with the adopted Specific Plan, Salinas General Plan, Salinas Zoning Code, Subdivision Ordinance and other requirements, as applicable. Upon completion of the City’s review of the application, applicants are to be advised by City staff of any application deficiencies that must be rectified in order for the application to be deemed complete (for applications subject to the State Permit Streamlining Act) or for the City to further process the application, as applicable.

9.3.1 Consistency Checklist
Project applications shall be reviewed according to a consistency checklist, prepared by the City as a means of ensuring consistency with all pertinent development regulations, design standards, FEIR mitigation measures, and other applicable conditions of approval adopted as part of the Specific Plan. Development review applications, such as administrative permits (signs, home occupations, etc.), site plan reviews, conditional use permits, lot line adjustments, parcel maps, tentative subdivision maps, planned unit developments, and variances, will be reviewed by the City 242
City of Salinas | Final Central Area Specific Plan, November 2020 in accordance with established procedures as contained in the Salinas Zoning Code (Article VI) and the Subdivision Ordinance, as applicable.

Available strategies for project specific compliance with the California Environmental Quality Act (CEQA) are set forth in detail in Section 9.6 and 1.3.4. Compliance with CEQA is discussed in Sections 9.6 of this Specific Plan. All subsequent development projects, public improvements, and other activities shall be consistent with this Specific Plan, Municipal Code (including the Salinas Zoning Code), Subdivision Ordinance, SWDS, and NPDES permits. As indicated previously, in acting to approve a project application or permit, the City may impose conditions as are reasonably necessary. Amendments to the Specific Plan shall be processed in accordance with the procedures described in Section 9.7.

The project processing requirements described in this Specific Plan apply to all development proposed within the Plan Area. This description addresses only entitlements the City of Salinas has authority to grant.

Permits from other governmental agencies may be required, and the City assumes no responsibility for identifying or pursuing these permits on behalf of any applicant. The appropriate federal, State, and other local agency approvals are required prior to any project approvals within the Plan Area or prior to implementation as may be the case.

Parcel Maps
Divisions of all or part of the land within the Plan Area for the purpose of creating master parcels for development or further subdivision consistent with the Specific Plan may be processed by a parcel map as provided in the State Subdivision Map Act and the City’s Subdivision Ordinance.

Tentative/Vesting Tentative Maps
Tentative subdivision maps and vesting tentative maps shall be processed in accordance with the provisions of the State Subdivision Map Act and the City’s Subdivision Ordinance. Notwithstanding the provisions of Section 31-312 of the City’s Subdivision Ordinance orfurther extensions as authorized by the State Subdivision Map Act, the approval or conditional approval of a tentative or vesting tentative map shall expire five (5) years after the date of the resolution adopted by the City Council approving or conditionally approving the tentative map. Requests for extensions thereof shall be considered by the City Planner and City Engineer per the State Subdivision Map Act and the City Subdivision Ordinance.

A variety of lot sizes and housing styles (see Chapter 3) are encouraged within the various Zoning Districts, neighborhoods, and blocks in the Plan Area. Pursuant to the General Plan and Section 31-903 of the City Subdivision Ordinance, clustering a large group of any single housing types in several large blocks shall be avoided. As a condition of each tentative or vesting tentative subdivision map, a Lot Standard Master Plan shall be submitted to the Community and Development Department identifying each Lot Standard (as provided for in Chapter 3 of the Specific Plan) within the subdivision. This plan shall be approved by the City Planner and City Engineer prior to recordation of any final map that Implementation and Administration
243
creates any residential lot. This information shall be entered into the City’s GIS, Trakit database or other applicable database that may be subsequently used by the City to track such data.

The Salinas Fire Department shall review and conditionally approve the fire hydrant placement, pipe sizes, and emergency vehicle circulation with each tentative map. The Salinas Fire Department (SFD) shall review and approve improvement plans in conjunction with the final map and subdivision improvement plan review. An on-site water system capable of providing adequate fire flow (per Fire Marshal’s requirements) and in accordance with all applicable rules and regulations shall be provided. Water main pressures shall be sufficient to accommodate fire sprinkler systems installed within structures. Unless otherwise required by the Fire Chief/Fire Marshal, fire hydrants shall be CLOW 950 hydrants for residential areas and CLOW 960 for commercial areas or as may be subsequently adopted by the City as a standard.

Because the demand for new schools will gradually increase over the time period in which buildout of the Specific Plan occurs, the City is committed to consulting with the Alisal Union High School District, the Santa Rita Union School District, and the Salinas Union High School District, as may be applicable as part of the City’s process for considering proposed tentative subdivision maps within the Specific Plan area. Such consultations will allow the City to keep the school districts apprised of the project proponents’ progress in seeking and obtaining entitlements for incremental amounts of new development within the Specific Plan area, thereby helping the districts to keep pace with new residential development as it occurs. Over time, as the Plan Area gradually builds out, the districts might reassess their needs or consider new or different sites for their proposed facilities, depending on factors such as the number of potential students living within newly developed areas and the number of additional students projected to live within the Plan Area at buildout. These tentative map consultations, then, will provide a kind of development phasing that will allow the districts to proactively plan for obtaining the sites and construction funds they will need to allow for the timely construction of new schools as the demands for them materialize over time.

Lot Line Adjustments
Property lines between adjacent lots or parcels of land within the Plan Area may be adjusted in accordance with Article VI, Division 6 of the Salinas Zoning Code and Section 31-1100 of the City Subdivision Ordinance.

Final Maps
Prior to the expiration of a tentative or vesting tentative map, a final map based on a qualified engineering survey shall be submitted to the Public Works Department for review and approval. Complete subdivision improvement plans are required to be submitted with each final map. As specified in Section 66474.1 of the California Government Code, the final map must be approved if found to be in substantial compliance with the approved tentative map and all conditions of approval.A public utility plan is 244
City of Salinas | Final Central Area Specific Plan, November 2020 required with each individual subdivision. Fire Department requirements with regard to fire flow requirements, etc., are identified in the Tentative Maps section. To maintain the required densities percentages and variety of lot sizes in the NE-A, NE-B, NG-A, NG-B, and NG-C zoning districts, once subdivided into individual lots, no further subdivision of these lots shall be allowed without a major Specific Plan amendment and applicable CEQA evaluation. Prior to recordation, final maps and subdivision agreement shall be approved by City Council.

See Lot Standard Master Plan requirement as noted in the Tentative Maps section above.

Rezoning
Actions of the City to zone the property within the Specific Plan Area consistent with the goals, objectives, and policies of this Specific Plan are deemed administrative acts, intended to implement the legislative purposes and conditions prescribed by this Specific Plan, and are therefore not subject to referendum (Lincoln Property Co. v. Law [1975] 45 CA3d 230; Southwest Diversified, Inc. v. City of Brisbane [1991] 229 CA3d 1548).

Annexation and Prezoning
Approval of an annexation (by the City and LAFCO), and prezoning (by the City) will be required for the Settrini/Igaz Ranch/Garcia properties prior to the Specific Plan being applicable to these properties. See Section

9.2.1 for further discussion of this issue.

Development Review Applications and Building Permits
Following approval of each final map, project applicants within the Plan Area may apply for the applicable development review process or building permit through the Community Development Department and Salinas Permit Center, as applicable. Building Permits may not be issued until approval of the final map and the applicable Development Review Application process (SPR, CUP, etc.) is completed. All projects must be consistent with the approved Specific Plan, the Salinas General Plan, City NPDES Permit/SWDS/SWSP requirements, final map, and applicable Salinas Zoning Code requirements and must comply with all California Building Code (including CALGreen) and Fire Code requirements and all other applicable codes adopted and enforced by the City. The applicable California Building Code and Fire Code (as may be amended) shall be those in effect at the time of the building permit submittal.

Fire apparatus access roads shall be provided and maintained in accordance with the version of California Fire Code Section 503.1.1 through 1.3, in effect at the time of the building permit application (or as may be subsequently amended), and Appendix D of the Specific Plan. All fire apparatus access roads shall consist of all-weather surface consisting of asphalt, concrete, or other approved all-weather driving surface capable of supporting the imposed load of Salinas Fire Department fire apparatus weighing at least 67,000 pounds, and as approved by the City Engineer and Fire Marshal. At the time of construction, a construction Implementation and Administration
245
vehicle access road capable of accommodating fire equipment loads and turning movements, identified by the Fire Chief, shall be provided before combustible materials can be delivered to the site. Provisions for on-site water and/or other fire suppression shall be addressed concurrently with vehicle access roads.

Grading Permits
Grading permits are subject to the approval of the City Engineer. Grading permits may be issued prior to improvement plan and/or final map approval if deemed appropriate by the City Engineer and if said plans comply with the Specific Plan, tentative map, conditions of approval and the City NPDES Permit/SWDS/SWSP.

Sales Office and Model Unit Permits
Permits for subdivision sales offices and model residential units may be issued prior to final map approval (in accordance with City requirements, Zoning Code Section 37-50.300 and as provided in the Subdivision Map Act) subject to the approval of the City Planner, City Engineer, Building Official and Fire Marshal. Individual submittals for model homes fall under the applicable Building and Fire Code in effect at the date of the application submittal. If a model plan approach is utilized, the model plans will be required to be updated as the applicable codes are amended.

Subsequent permits issued upon those plans are required to meet the applicable code requirements at time of issuance.

9.4 Phasing Plan
At the time of adoption of the Specific Plan, the Plan Area was owned by twelve entities, identified in Table 1 1 Central Area Owner’s List. Two of these entities are school districts, the remaining entities are individual ownerships. Three of these property owners (Settrini, Igaz Ranch, and Garcia) own parcels that are currently located outside of City limits but are located in the City’s SOI. As previously discussed in Section 9.2.1, these parcels willrequire annexation before any development can occur on these parcels within the Plan Area. Because of the multiple ownerships, there is no specific phasing plan proposed at this time. Each of the ownerships border one or more existing public streets that contain or are planned to contain most utility infrastructure necessary to support development. The Specific Plan is designed such that each current institutional or individual private owner may develop their property independent of development by other property owners. An agreement may be required among two or more property owners to allow for this independent development. Any developing ownership may need to obtain from the adjoining ownerships, the access, and easements necessary for roadways or utilities to support development of their individual property. This agreement must occur prior to recordation of a final map, unless otherwise approved by the City Engineer.

Public schools and public facilities will be constructed based on projections of the need for these facilities in the Specific Plan Area and surrounding 246
City of Salinas | Final Central Area Specific Plan, November 2020 area. The applicable school district will determine and control the phasing of their facilities. Similarly, the Village Center will be constructed based on local and regional market demand for such retail and commercial services.

It is estimated that full buildout will take place over approximately 20 to 30 years. In general, phasing of development within these individual ownerships is projected to proceed from Boronda Road northward.

However, exceptions to this can occur for the development of a public school, parks, ordevelopment of a specific property or public improvement subject to the approval of the City. In such instances, roads and utility infrastructure shall be extended to serve those projects.

At this time, there is no specific phasing plan established; however, each development or phase thereof will require grading and all erosion control measures will be required to be installed in accordance with a Stormwater Pollution Prevention Plan (SWPPP) or sediment and erosion control plan as applicable. Infrastructure improvements required for each final map or phase thereof shall include, but are not limited to, all frontage improvements, storm drainage, sanitary sewer, waterline, and wet and dry utilities, and other improvements as determined by the City to serve the needs of the subject phase and/or comply with the CASP EIR and MMRP.

Phasing of the parks and certain public improvements shall be determined by the City and/or as otherwise provided in a Development Agreement.

9.5 Agricultural Land Preservation
The City’s Agricultural Land Preservation Program (ALPP) was adopted on April 8, 2008. The Central Area Specific Plan, by virtue of being part of the Salinas Future Growth Annexation and Sphere of Influence (SOI) Area, is a Greater Salinas Area Memorandum of Understanding (GSAMOU) identified growth area as defined in the ALPP.

9.5.1 Right to Farm Notices
All development within the Plan Area shall comply with the provisions of Section 37-50.220(c) of the Salinas Zoning Code requiring the recordation of a deed restriction containing the Notice of Right to Farm prior to the recordation of a final map or issuance of the first building permit for any project located within one thousand (1,000) feet of agricultural land, agricultural processing, or agricultural farming operations whether located within or outside of the Plan Area.

Farm vehicles shall be precluded from using public streets in the Specific Plan Area for access unless appropriate access stabilization and street cleaning measures are incorporated into design and approved by the City Engineer.

Buffers between Agricultural and Non-Agricultural Uses
The ALPP calls for the City to implement General Plan Policy COS-10, which encourages the provision and maintenance of buffer zones such as roadways, topographic features, and other physical boundaries to prevent incompatibilities between agricultural and non-agricultural land uses.

Implementation and Administration
247
The ALPP states that a number of factors shall be used to determine the appropriate buffer, including type of agricultural use, topography, and pesticide and machinery use, among others. In the case of the Plan Area, the agricultural lands to be protected by buffers are those on the north side of the future Russell Road (the Protected Lands). See Chapter 4.0 for a description of the 200-foot required buffer.

Buffer easements shall be temporary. The obligation to provide or maintain the buffers shall cease when the adjacent protected lands cease to be permanently used for agricultural purposes.

Buffers shall only be required along those portions of a development project that front on or are immediately adjacent to (adjoin) the protected lands. The parkways of the arterial streets located adjacent to farmlands shall contain enhanced landscaping with increased number of trees to buffer the adjacent agricultural lands, in accordance with General Plan Policy COS-3.4.

Within the Specific Plan Area, it is assumed that interim agricultural operations will continue to occur during the buildout of the development.

To reduce the potential for on-site land use conflicts with the Central Area, the agricultural operators shall maintain a minimum 100-foot temporary buffer setback between the interim agricultural operations or support activities and any completed development.

Required construction of Plan Area roadways or utilities through active farmland is not viewed as isolating farmland.

Agricultural Land Conservation Easements
The Central Area Specific Plan is a GSA-MOU-identified growth area as defined in the ALPP and as such, no agricultural mitigation easements shall be required for the lands within the Plan Area.

Agricultural Land Mitigation Fee
Agricultural land mitigation fees will be assessed in accordance with City Resolution No. 19422; these fees fund activities designed to preserve and promote agricultural programs in the Salinas area. As provided in the ALPP, lands within the Central Area Specific Plan are subject to payment (to the City) of an agricultural land mitigation fee in the amount of $750 per acre of converted land designated by the California Department of Conservation’s Farmland Mapping and Monitoring Program as “Prime” or “of Statewide Importance” (Designated Farmland).

In connection with the approval of any development project within the Plan Area (tentative subdivision map, parcel map or vesting entitlement, as applicable), the City shall determine the number of acres of Designated Farmland proposed for conversion within the project, and calculate the per-unit mitigation fee by dividing the total mitigation fee for the project (number of converted acres of Designated Farmland x $750/acre) by the number of residential units or in case of non-residential development by multiplying by the gross acreage of the converted land. The fee so 248
City of Salinas | Final Central Area Specific Plan, November 2020 calculated shall be made a condition of the tentative or vesting tentative map (or other project approval, if there is no map) and shall be required to be paid concurrently with the approval of the subdivision agreement for each final map (or at the time of first certificate of occupancy if there is no map) unless otherwise determined by the City Planner and City Engineer.

9.6 Environmental Review
The Central Area Specific Plan and its proposed development was evaluated at a General Plan level in the certified Final EIR for the Salinas General Plan Environmental Impact Report (2002), and in the 2007 EIR Supplement for the Salinas General Plan EIR certified in connection with the annexation of the North of Boronda FGA. In connection with the approval of the Central Area Specific Plan, a programmatic EIR has been prepared and certified by the City Council prior to the approval of the Specific Plan document. The Central Area Specific Plan EIR serves as the base environmental document for all subsequent entitlements within the Plan Area. All subsequent Development Review Applications are to be reviewed on a project-by-project basis to determine consistency with the Central Area Specific Plan EIR. The need for additional site-specific environmental review, if any, is to be determined through one of the processes described below.

State CEQA Guidelines identify several types of EIRs, each applicable to different project circumstances. The EIR for the Specific Plan was prepared as a Program EIR pursuant to CEQA Guidelines Section 15168.

The program-level analysis considers the broad environmental effects of the proposed project as a whole.

The Specific Plan provides a very high level of design detail for certain components of the project. To the extent that sufficient detail is available in the Specific Plan, a full project-level analysis is provided in the Program EIR. Topics such as Biological Resources, Cultural Resources, and Hydrology/Water Quality are analyzed at a project-level analysis in the EIR given that these are physical environmental resources, and the area of impact is fully defined. Additionally, the Specific Plan includes a substantial level of detailed information that allows for a project- level analysis of topics such as Air Quality, Greenhouse Gases and Climate Change, Noise, Population and Housing, Transportation and Circulation, and Utilities. The analysis for these topics is driven by the number of units and square footage of development, which are detailed in the land use design and development projections. In some cases, there may be specific commercial uses that have design details developed at a later date that cannot reasonably be analyzed at a project-level at this time. Additionally, the design of the school facilities and other public facilities are not known at this time, so they are not able to be analyzed at a project-level.

TheProgramEIRexamines theplanning, construction, andoperation ofthe SpecificPlan.Theprogram-levelapproach,withsomeproject-levelanalysis, was appropriate for the Specific Plan because it allows comprehensive consideration of the reasonably anticipated scope of the development Implementation and Administration
249
plan; however, not all design aspects of the future development phases are known at the Specific Plan stage in the planning process. Subsequent individual development that requires further discretionary approvals will be examined in light of the Program EIR to determine whether additional environmental documentation must be prepared.

CEQA Guidelines Section 15168(a) states that a program EIR is an EIR which may be prepared on a series of actions that can be characterized as one large project and are related either:

1. Geographically,

2. As logical parts in the chain of contemplated actions,

3. In connection with issuance of rules, regulations, plans or other general criteria to govern the conduct of a continuing program, or

4. As individual activities carried out under the same authorizing statutory or regulatory authority and having generally similar environmental effects which can be mitigated in similar ways.

According to CEQA Guidelines Section 15168, subdivision (c)(5), “[a] programEIRwillbemosthelpfulindealingwithlateractivities ifitprovides a description of planned activities that would implement the program and deals with the effects of the program as specifically and comprehensively as possible.” Later environmental documents (EIRs, mitigated negative declarations, or negative declarations) can incorporate by reference materials from the program EIR regarding regional influences, secondary impacts, cumulative impacts, broad alternatives, and other factors (CEQA Guidelines Section 15168[d][2]). These later documents need only focus on new impacts that have not been considered before (CEQA Guidelines Section 15168[d][3]).

Section 15168(c), entitled “Use with Later Activities,” provides, in pertinent part, as follows:

Later activities in the program must be examined in the light of the program EIR to determine whether an additional environmental document must be prepared:
(1) If a later activity would have effects that were not examined in the program EIR, a new Initial Study would need to be prepared leading to either an EIR or a Negative Declaration.

That later analysis may tier from the program EIR as provided in Section 15152.
(2) If the agency finds that pursuant to Section 15162, no subsequent EIR would be required, the agency can approve the activities as being within the scope of the project covered by the program EIR, and no new environmental document would be required.Whether a later activity is within the scope of a program EIR is a factual question that the lead agency determines based on substantial evidence in the record. Factors that an agency may consider 250
City of Salinas | Final Central Area Specific Plan, November 2020 in making that determination include, but are not limited to, consistency of the later activity with the type of allowable land use, overall planned density and building intensity, geographic area analyzed for environmental impacts, and covered infrastructure, as described in the program EIR.
(3) An agency shall incorporate feasible mitigation measures and alternatives developed in the program EIR into later activities in the program.
(4) Where the later activities involve site specific operations, the agency should use a written checklist or similar device to document the evaluation of the site and the activity to determine whether the environmental effects of the operation were within the scope of the program EIR.

Here, the City anticipates preparing a written checklist or similar device whenever project proponents within the Plan Area submit applications for site-specific approvals, such as tentative maps, conditional use permits, or other discretionary entitlements. With respect to certain types of environmental resources, the effects to which would not differ regardless of the exact kind of land use that is proposed (e.g., agricultural resources, culturalresources, geology, soils, and paleontologicalresources), the City’s expectation is that the written checklists will conclude that no further analysis of such effects beyond that found in this program EIR will be necessary. Thus, the new analyses for these site-specific actions will focus on issues and impacts regarding which this program EIR lacks detailed site-specific information, and for which specific project proposals could have site-specific effects not wholly anticipated in this EIR. (See also CEQA Guidelines Section 15063, subd.(b)(1)(C).)
Future site-specific approvalsmayalsobenarrowedpursuanttothe rules for tiering set forth in CEQA Guidelines Section 15152. “‘[T]iering is a process by which agencies can adopt programs, plans, policies, or ordinances with EIRs focusing on ‘the big picture,’ and can then use streamlined CEQA review for individual projects that are consistent with such…[first tier decisions] and are…consistent with local agencies’ governing general plans and zoning.’” (Koster v. County of San Joaquin (1996) 47 Cal.App.4th 29, 36.) Before deciding to rely in part on a first- tier EIR in connection with a site-specific project, the lead agency must prepare an “initial study or other analysis” to assist it in determining whether the project may cause any significant impacts that were not “adequately addressed” in a prior EIR. (CEQA Guidelines, § 15152, subd. (f); Pub. Resources Code, § 21094, subd. (c).) Where this analysis finds such potentially significant impacts, an EIR is required for the later project. In contrast, “[a] negative declaration or mitigated negative declaration shall be required” where there is no substantial evidence that the project may have significant impacts not adequately addressed in the prior EIR or where project revisions accepted by the proponent avoid any such new significant impacts or mitigate them “to a point where clearly” they are not significant.

Implementation and Administration
251
Section 15152 further provides that, where a first-tier EIR has “adequately addressed” the subject of cumulative impacts, such impacts need not be revisited in second- and third-tier documents. Furthermore, secondand third-tier documents may limit the examination of impacts to those that “were not examined as significant effects” in the prior EIR or “[a]re susceptible to substantial reduction or avoidance by the choice of specific revisions in the project, by the imposition of conditions, or other means.” In general, significant environmental effects have been “adequately addressed” if the lead agency determines that:

A. They have been mitigated or avoided as a result of the prior environmental impact report and findings adopted in connection with that prior environmental impact report; or
B. They have been examined at a sufficient level of detail in the prior environmental impact report to enable those effects to be mitigated or avoided by site specific revisions, the imposition of conditions, or by other means in connection with the approval of the later project.

Similarly, as previously noted, the City anticipates preparing a written checklist or similar device whenever project proponents within the Specific Plan area submit applications for site-specific approvals, or other discretionary entitlements. In preparing these analyses, the City will assess, among other things, whether any of the significant environmental impacts identified in this program/first-tier EIR have been “adequately addressed.” Thus, the new analyses for these site-specific actions will focus on impacts that cannot be “avoided or mitigated” by mitigation measures that either (i) were adopted in connection with the Specific Plan or (ii) were formulated based on information in this EIR.

In addition, because the EIR addresses the effects of rezoning the land within the proposed Specific Plan area, future environmental review can also be streamlined pursuant to Public Resources Code Section 21083.3 and CEQA Guidelines Section 15183. These provisions, which are similar but not identical to the tiering provisions, generally limit the scope of necessary environmental review for site-specific approvals following the preparation of an EIR for a “zoning action.” For such site-specific approvals, CEQA generally applies only to impacts that are “peculiar to the parcel orto the project” and have not been previously disclosed, except where “substantial new information” shows that previously identified impacts would be more significant than previously assumed. Notably, impacts are considered not to be “peculiar to the parcel or to the project” if they can be substantially mitigated pursuant to previously adopted, uniformly applied development policies or standards. As noted above, the City anticipates that, in assessing the extent to which the Specific Plan EIR has previously addressed significant impacts that might occur with individual projects, the City may conclude that in some instances (e.g., with respect to agricultural resources, cultural resources, geology, soils, and paleontological resources), no further analysis beyond that found in the program EIR will be necessary.
252
City of Salinas | Final Central Area Specific Plan, November 2020 Finally, for purely residential projects consistent with the Specific Plan, the City intends to preserve its ability to treat such projects as exempt from CEQA pursuant to Government Code Section 65457. Subdivision (a) of that statute provides that “[a]ny residential development project, including any subdivision, or any zoning change that is undertaken to implement and is consistent with a specific plan for which an [EIR] has been certified after January 1, 1980, is exempt from the requirements of [CEQA].” The statutes goes on to say, moreover, that “if after adoption of the specific plan, an event as specified in Section 21166 of the Public Resources Code occurs, the exemption provided by this subdivision does not apply unless and until a supplemental [EIR] for the specific plan is prepared and certified in accordance with the provisions of [CEQA]. After a supplemental [EIR] is certified, the exemption … applies to projects undertaken pursuant to the specific plan.” (See also CEQA Guidelines Section 15182.)
When purely residential projects are proposed, the City will consider whether they qualify for this exemption or whether the Central Area EIR must be updated through a supplement to this EIR or a subsequent EIR as required by Public Resources Code Section 21166 and CEQA Guidelines Sections 15162 and 15163.

In approving the Central Area Specific Plan, the City Council adopted a Mitigation Monitoring and Reporting Program (MMRP) in accordance with CEQA Guidelines Section 15097 to ensure implementation of the Central Area Specific Plan EIR mitigation measures. As applicable, future developments within the Specific Plan Area will be required to implement the mitigation measures in the MMRP as specified. The MMRP includes mitigation measures from prior EIRs (2002 Salinas General Plan FEIR and the 2007 Final Supplement for the Salinas General Plan Program EIR) that are applicable to the Central Area. A mitigation monitoring fee may be imposed.

Additionally, in approving the Central Area Specific Plan, the City Council included Conditions of Approval to ensure level of service (LOS) standards are met in accordance with the Salinas General Plan transportation standards. These conditions of approval are included in the associated EIR and Appendix Q to this Specific Plan. The Conditions of Approval included therein shall not be modified and shall remain in force and effect for the life of the project.

9.7 Minor Revisions and Specific Plan
Amendment Procedures
California Government Code Section 65453 states that a Specific Plan may be amended as often as deemed necessary by the legislative body (City Council). Changes to this plan may be initiated by a developer, property owner or the City. The Central Area Specific Plan may need to be amended to respond to changing conditions and expectations during the course of its implementation. To address this possibility, this Specific Implementation and Administration
253
Plan provides for minor revisions in addition to more encompassing Specific Plan Amendments. By adopting this Specific Plan, the City Council has delegated (except where otherwise noted below) to the City Planner the authority to make “minor revisions” as described below. Such minor revisions do not rise to the level of importance to justify Planning Commission and City Council review, and staff-level approval will facilitate timely implementation of the Specific Plan.

Upon submittal of an application for a change to the Specific Plan, the City Planner shall determine if the proposed change is a minor revision or a Specific Plan Amendment. The processing requirements for both minor revisions and Specific Plan Amendments are described as follows.

9.7.1 Minor Revisions
Minor revisions to the Central Area Specific Plan include but are not limited to the following examples:
a. Addition of new or updated information that does not substantially change the Specific Plan or result in new or intensified environmental impacts not previously analyzed.
b. Minor changes in building location, architectural design, FAR (which does not exceed the maximum permitted in the Specific Plan or Salinas Zoning Code, as applicable), and/or floor plan.
c. Amendments that do not involve a change of use, density, or intensity of development beyond the provisions of this Specific Plan or Salinas Zoning Code as applicable, or the introduction of new or intensified significant environmental impacts not previously analyzed, and do not change the character of the project.
d. Adjustments to land use area boundaries within the locations of facilities and street alignments established by the Specific Plan, where the overall land use pattern remains consistent with the Specific Plan objectives (the land use must be one currently allowed in the Specific Plan).
e. Minor modifications to architectural details, building color, landscape treatments or materials, fencing, lighting, paths, signage, parking or driveway location, and entry monumentation, which are consistent with the intent, vision, and character of the Specific Plan, Salinas Zoning Code, and SWDS requirements.
f. Transfer of dwelling units between density categories, provided such transfers and/or modifications continue to be in conformance with the General Plan provisions regarding density and mix of densities. g. Transfer of dwelling units between density categories, provided such transfers and/or modifications do not create conditions where the maximum permissible dwelling-unit count is exceeded except as specifically provided for in this Specific Plan (see Chapter 3). 254
City of Salinas | Final Central Area Specific Plan, November 2020 h. The addition of new development regulations to accommodate future, alternative, or custom dwelling housing types (including but not limited to tiny homes and other new and innovative housing types) not currently contemplated in the Specific Plan, but which are consistent with the intent, vision and character of the Specific Plan, New Urbanism Principles, the Salinas General Plan and SWDS.
i. Future Modifications resulting from the Boronda Road Roundabout Improvement projects, in the future, the site design of the Village Center, location of land uses within the Village Center, and/or access/ turn movements from Boronda Road may be modified pursuant to this section provided that the proposed modification does not substantially alter the type, intensity, or distribution of the land uses, or introduce new environmental impacts.
j. Conversion of an unneeded school site to a permitted or conditional use allowed in the NG-A district. If additional residential uses are proposed in accordance with the NG-A district for a school site (in lieu of a school), additional park space based on the additional population will be required.
k. The requirement for a minimum of 600 lineal feet of frontage of nonresidentialoccupanciesonthefirstfloorofthebuildingsdescribedinTable 3 1 (footnote 8a) may be reduced where the applicant has demonstrated to the satisfaction of the City Planner that sufficient reasonable efforts were made to rent the space to non-residential uses and that insufficient tenants were secured to fill the required 600 lineal feet of frontage.

The City Planner may approve a minor revision to the Specific Plan administratively except as otherwise noted. To approve the minor revision, the City Planner must find the revision does not create or intensify environmental impacts not previously analyzed and does not change the intent, vision, and character of the Specific Plan, and is in substantial conformance with all of the following:
• The Planning Objectives of the Specific Plan;
• The City of Salinas General Plan;
• The Salinas Municipal Code including but not limited to the Zoning Code and Subdivision Ordinance;
• Salinas SWDS/ NPDES Permit (a modification may require compliance with the SWDS/NPDES in effect at the time the modification is approved); and
• The Central Area Specific Plan and the certified EIR and Mitigation Measures.

Minor Revisions may be approved administratively by the City Planner through the applicable development review process required for the subject application/use without the necessity of a separate application or process.

The Specific Plan document will be revised to reflect the Minor Revision unless otherwise approved by the City Planner.

Implementation and Administration
255
TheCityPlannermayrefer anyMinorRevisiontothePlanningCommission for consideration. Any determination or action taken by the City Planner may be appealed in accordance with Article VI, Division 17 of the Salinas Zoning Code. If any of the aforementioned decision-makers finds that the proposed revision does not meet the above criteria, the Minor Revision shall be deemed denied and a Specific Plan Amendment shall be required.

9.7.2 Specific Plan Amendments
Proposed changes to a Specific Plan that are not deemed a Minor Revision by the City Planner are classified as amendments to the Specific Plan and shall be processed in the same manner as the initial Specific Plan adoption, requiring review by the Planning Commission and action by the City Council pursuant to Section 37-60.1240 of the Salinas Zoning Code.

Fair Share Traffic Conditions of Approval contained in the project EIR and this Specific Plan related to traffic and circulation improvements (see Appendix Q) may not be amended and shall remain in force and effect for the life of the project unless approved by the City Council upon the recommendation of the City Engineer. Modifications to the Fair Share Traffic Conditions of Approval may require further CEQA analysis.

9.8 Development Agreement
The Central Area project proponents and the City of Salinas may enter into one or more development agreements covering all or any part of the Plan Area. Approval and implementation of development agreements shall be pursuant to Article 2.5, Chapter 4, Title 7 of the Government Code (Section 65864 et seq.) and Article VI, Division 11 of the Salinas Zoning Code. The project description includes development agreement(s) and was considered as part of the Central Area Specific Plan EIR.

9.9 Enforcement
The Central Area Specific Plan carries with it a number of development regulations, conditions of approval, and environmental mitigation measures (collectively “regulations”). Adequate enforcement mechanisms must be in place to ensure compliance with all adopted regulations.

Enforcement andpenalties relatedto provisions ofthe SalinasZoning Code or Specific Plan shall be in accordance with Article VI, Division 18 of the Salinas Zoning Code, or other applicable sections of the Municipal Code.

If the City determines that activity or development is occurring or has occurred that is not in compliance with this Specific Plan of other City requirement, the City may initiate procedures to ensure compliance.

Enforcement activities may include any of the following actions or others as deemed necessary and appropriate by the City:
• Issuance of a stop work order;
• Exercise of the remedies provided by any City enforcement ordinance based upon the police power to protect the public’s health, 256
City of Salinas | Final Central Area Specific Plan, November 2020 safety, and welfare;
• Requirement of performance bonds;
• Revocation or suspension of entitlements;
• Denial or postponement of subsequent project entitlements for the non-compliant developer/builder; and
• Legal action.

9.10 Project Financing
Government Code Section 65451 requires a specific plan to include “a program implementation measure, including public works projects and financing measures to carry out the plan.” See Chapter 8 for a detailed discussion of the project financing for the Central Area Specific Plan.

Remainder of page intentionally left blank
257
Final Central Area Specific Plan
November 2020

10. Appendices
A Acronyms
B Definitions
C General Plan Consistency
D Mitigation Monitoring and Reporting Program
E Light Standards
F Facilities, Traffic Management, and Trip Reduction Plan G Land Use Density Summary
H MST Correspondence
I Affordable Housing Component (Inclusionary Housing Plan) J Boronda Road Cross Sections
K Street Sections
L Fehr and Peers Memo
M Reimbursement Ordinance
N Master Landscaping Plan
O Street Furnishings
P Master Fence and Wall Plan
Q Conditions of Approval (Traffic Mitigations)
R Pacific Advanced Civil Engineering, Inc. (PACE), hydrologic mitigation analysis, Technical Memorandum
S 2006 Salinas Zoning Code
T Interpretation Guide
U FGA Acreage City Finance Table
258
City of Salinas | Final Central Area Specific Plan, November 2020 Appendix A:

Acronyms
Appendices
259
Appendix A- Acronyms
ADA Americans with Disabilities Act
ADU Accessory Dwelling Unit
ADT Average Daily Traffic
ADWF Average Daily Wastewater Flow
AFY acre feet per year
Alco Alisal Water Corporation
ALPP Agricultural Land Preservation Program
APN Assessor’s Parcel Number
AWWA American Water Works Association
Cal EPA California Environmental Protection Agency
Cal Water California Water Company
CAPIF Central Area Park Impact Fee
CASP Central Area Specific Plan
CC&Rs Covenants, Codes and Restrictions
CCRWQCB Central Coast Regional Water Quality Control Board CEQA California Environmental Quality Act
CFD Community Facilities District
City City of Salinas
CUP Conditional Use Permit
CPI Consumer Price Index
CPT Cone Penetration
CPTED Crime Prevention through Environmental Design
CUP Conditional Use Permit
DIP ductile iron pipe
du/nra dwelling units per net residential acre
EIR Environmental Impact Report
EMS Emergency Medical Services
ENR Engineering News Record
ESA Environmental Site Assessment
ET evapotranspiration-based
FAR Floor Area Ratio
FEMA Federal Emergency Management Administration
FGA Future Growth Area
FIRM Flood Insurance Rate Map
General Plan City of Salinas General Plan
GPA General Plan Amendment
gdp gallons per day
gpd/acre gallons per day per acre
gpm gallons per minute
GSA-MOU Greater Salinas Area Memorandum of Understanding HDPE High-Density Polyethylene
HVAC heating, ventilation, and cooling
in/hr inches per hour
kv kilovolt
LAFCO Local Area Formation Commission
LED light emitting diode
260
City of Salinas | Final Central Area Specific Plan, November 2020 LEED Leadership in Energy and Environmental Design
lf linear feet
LID Low Impact Development
LLMD Landscaping and Lighting Maintenance District
LOMA Letter of Map Amendment
LOMR Letter of Map Revision
M1W Monterey One Water (formerly Monterey County Water Resources Agency /

MRWPCA)
MEP maximum extent practicable
mg/year million gallons per year
mgd million gallons per day
MLD most likely descendent
MMRP Mitigation Monitoring and Reporting Program
MOU Memorandum of Understanding
mph miles per hour
MRWPCA Monterey Regional Water Pollution Control Agency (now M1W) MST Monterey-Salinas Transit
MTBE methyl tert-butyl ether
NAHC Native American Heritage Commission
NE Neighborhood Edge
NG Neighborhood General
NFIP National Flood Insurance Program
NI New Urbanism Interim
NPDES National Pollutant Discharge Elimination System
NRCS National Resources Conservation Service
NTS Not to Scale
OA Owners Association
PCBMP Post-construction best management practices
P&D P&D Consultants
PG&E Pacific Gas and Electric
Plan Area Central Area Specific Plan Area
PRG Preliminary Remediation Goal
psi pounds per square inch
psig pounds per square inch gage
PWWF Peak Waste Water Flow
REC Recognized Environmental Condition
ROW right-of-way
RWQCB Regional Water Quality Control Board
ROW right-of-way
SCM Stormwater Control Measure
SFHA Special Flood Hazard Area
SMC Salinas Municipal Code
SSMP Sanitary Sewer Master Plan
SOI Sphere of Influence
SOISS City of Salinas Sphere of Influence Study
SOIWS City of Salinas Sphere of Influence Water Study
SPA Specific Plan Area
Specific Plan Central Area Specific Plan
Appendices
261
SPR Site Plan Review
SR State Route
SVSWA Salinas Valley Solid Waste Authority
SVBGSA Salinas Valley Basin Groundwater Sustainability Agency SWDS Stormwater Development Standards
SWM Stormwater Management
SWSPS Stormwater Standard Plans
TAMC Transportation Agency for Monterey County
TF-SP Trickling Filters – Solid Process
TFO Traffic Fee Ordinance
TM technical memorandum
TND Traditional Neighborhood Development
TTLC Total Threshold Limit Concentration
U.S. 101 U.S. Highway 101
USEPA United States Environmental Protection Agency
VC Village Center
VOC volatile organic compound
VTM Vesting Tentative Map
WSA water service assessment
262
City of Salinas | Final Central Area Specific Plan, November 2020 Appendix B:

Definitions
Appendices
263
Accessory Dwelling
Unit
Refers to an attached or a detached residential dwelling unit which provides complete independent living facilities for one or more persons, including permanent provisions for living, sleeping, eating, cooking, and sanitation, which is located on the same parcel as a single-family detached dwelling unit, as described in the Salinas Zoning Code. Accessory dwelling unit may be abbreviated as ADU and may also be known as a Carriage Unit or Second Dwelling Unit.

Average Density Refers to the total number of dwelling units in that Zoning District divided by the net residential acres as approved in each Tentative Map
Average Dwelling
Units per Net
Residential Acre
Refers to the total number of dwelling units within each Zoning District within each Tentative Map divided by the Net Residential Acres within that zoning district on that Tentative Map.

Back of sidewalk Refers to the right-of-way property line Boronda Road Refers to East Boronda Road
Central Area Refers to the geographic area to be governed by the Central Area Specific Plan (CASP) CASP Traffic Fee Refers to a funding mechanism the project proponents may implement to equalize cost of traffic improvements required by City of Salinas Resolution 12963 or traffic improvements that are 100% project reasonability in accordance with the CASP EIR Courtyard Apartment Eight multifamily dwelling units clustered around a courtyard which opens to the street with all parking in enclosed garages to the rear and one side Fair Share Traffic
Conditions of
Approval Fee
Refers to the project EIR traffic conditions of approval improvements for which project proponents shall pay individual fair share with each subsequent application and paid in the same manner as the City Traffic Fee Ordinance (trip calculation).

Flex Use Space Refers to the ground floor of buildings located in the VC districts and the NG-C which may change from residential to non-residential uses and back to a residential use upon the City Planner’s approval of a SPR authorizing the change. A minimum of 600 lineal feet of the approximately 1,800 lineal feet of frontage along the main street shall be offered for rent exclusively to and occupied by non-residential uses.

General Plan Refers to the Salinas General Plan
Greenway /
Greenway Street
Refers to the Northerly and Southerly Greenway streets as shown on Figure 5-3 and described in Section 5.6.1
Green court Home Single family detached dwellings with garages accessed on landscaped alleys behind which are sited on three sides of a common green area and the public street on the fourth side.

Lane dwelling Single family detached dwellings with garages accessed on landscaped alleys behind which face both sides of a common area (minimum 20-foot wide) with a walkway which runs from one public street to another public street.

Net Residential Acre Refers to the private lands zoned for residential uses exclusive of streets, parks, and other public uses.

Net Residential
Developable Acre
Refers to same as Net Residential Acre.

Plan Area Same as Central Area
Promenade Walkway, path, sidewalk
Row Home Detached single family dwellings sited with shallow front yard setbacks and one-foot-six-inch setbacks to the side property line on both sides and with garages in the rear accessed off of an alley.

Site Coverage All impervious surfaces of a site/lot including building footprint, parking areas, walkaways, and similar features
Street Refers to a public street or private street which functions as a public street Specific Plan Refers to same as Central Area
Subareas This refers to the column title “RJA Numbers” in appendix G Village Center Refers to the area that includes both the Village Center A and Village Center B zoning districts Village Green Refers to the two parks located at the south and north edges of the Village Center Districts 264
City of Salinas | Final Central Area Specific Plan, November 2020 Appendix C:

General Plan
Consistency
Appendices
265
B-1

APPENDIX C

CENTRAL AREA SPECIFIC PLAN

GENERAL PLAN POLICY CONSISTENCY
MARCH 2020
Salinas General Plan Policy Consistent Discussion
Land Use Element
Policy LU-1.1: Achieve a
balance of land uses to
provide for a range of housing,
jobs, educational facilities,
and recreational opportunities
that allow residents to live,
work, shop, learn, and play in
the community.

Yes The Specific Plan is consistent with the range of
housing required by the General Plan with
approximately 652 low residential (17%), 1,542
medium residential (39%), and 656 high residential
(17%). At full buildout of the Specific Plan area the
office and retail/service commercial will generate
approximately 1,469 jobs (at an average of 3
employees per 1,000 S.F.). Within the Specific Plan
area are schools with grades K through 8. The Plan
includes creek corridor open space, seven
neighborhood parks and 10 small parks. These
facilities are interconnected by a local street and
pedestrian path system.

Policy LU-1.3: Make
provision in residential areas
for institutional uses that are
needed near homes or which
benefit from a residential
environment, including places
of religious assembly, day-care
homes, homes for physically
or developmentally disabled
persons, and care facilities in
accordance with the
provisions of State law.

Yes Institutional uses such as places of religious assembly, day care homes, homes for physically or
developmentally disabled persons, care facilities, and
similar uses are permitted in Specific Plan residential and commercial areas subject to the normal City
permit and approval process for the specific proposed
use. Due to the unpredictability of the need for specific institutional uses no specific sites are indicated in the Specific Plan. However, the CASP land use plan
establishes a Public and Semipublic land use
comprising 61 net acres of the plan area, which could
be occupied by the institutional land uses mentioned in Policy LU-1.3.

Policy LU-1.4: Create and
preserve distinct, identifiable
neighborhoods that have
traditional neighborhood
development (TND)
characteristics. Specifically
development should.

Connect in as many locations
as possible to adjacent
Yes The Specific Plan neighborhoods are focused around
local parks (see above). Local streets with widened
sidewalks and parkways focus on these community
facilities. Transect zoning provides a mix of low,
medium, and high density residential unit types. Small
parks within approximately 660 feet (3-minute walk) of
almost all housing units provides communal active and
passive recreation spaces enhancing neighborhood
identity. Additionally neighborhood parks including a
larger 11.63 acre neighborhood park is located near the 266
City of Salinas | Final Central Area Specific Plan, November 2020

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-2
Salinas General Plan Policy Consistent Discussion
development, arterial streets,
and thoroughfares;
Provide a balanced mix of
housing, workplaces,
shopping, recreational
opportunities, and
institutional uses, including
mixed-use structures
(combining residential and
non-residential uses), that help
reduce vehicular trips;
Provide natural amenities that
are fronted by thoroughfares
or public spaces, and not
privatized behind backyards;
Commercial buildings should
directly front on the sidewalk,
with ample landscaping as a
buffer between the building
and the sidewalk, and parking
lots are to be located behind
the buildings;
Allow flexible parking
requirements and
arrangements within the
neighborhood activity centers
to minimize the impact of the
automobile and foster a
pedestrian oriented
streetscape;
Provide second stories on
commercial buildings to
provide for other uses and
encourage residential use;
Allow small ancillary dwelling
units in the rear yard for
residential areas; and
village center and serves as one of the primary focal
points of the Specific Plan area.

The local serving commercial buildings and other uses
are located in the Village Center, which is easily
accessible from the internal local street system and
pathway network. The predominantly two-story
buildings are configured as a Main Street
perpendicular to Boronda Road stretching nearly to
Russell Road with residential uses also provided. The
Village Center will be developed consistent with
General Plan policy and the applicable New Urbanism
District standards.

The local street system connects to the surrounding
arterial streets at the maximum number of points
consistent with intersection spacing requirements
necessary to maintain the traffic flow function of these arterial streets.

Higher density residential products are located
generally located adjacent to the Village Center and
adjacent to schools and parks. These products have
reduced front, rear, and side yard setbacks to provide
more compact development envisioned for the Village
Center. Ancillary units are permitted in some
residential product types.

Narrower streets, traffic calming, decorative
pedestrian-friendly lighting and other pedestrian
amenities are provided throughout the planning area.

Architectural housing types promote the use of porches
and other features typically found in TND areas.

Appendices
267

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-3
Salinas General Plan Policy Consistent Discussion
Decrease the front yard
setbacks moving from
neighborhood edge to
neighborhood center.

Policy LU-2.1: Minimize
disruption of agriculture by
maintaining a compact city
form and directing urban
expansion to the North and
East, away from the most
productive agricultural land.

Yes The Specific Plan area is located to the north of the City away from the most productive agricultural land
and has a net residential density of more than 9
DU/AC in accordance with the Greater Salinas Area
Memorandum of Understanding between the City and
the County of Monterey.

Policy LU-2.3: Encourage
clustering of development on
sites within the Future
Growth Area to minimize
impacts on agricultural and
open space resources.

Yes The Specific Plan area is wholly within the City’s
designated Future Growth Area. The plan is designed
in accordance with the principles of New Urbanism,
which calls for compact pedestrian oriented
neighborhoods. The net residential density is over 9
DU/AC.

Policy LU-2.5: Ensure that
negative impacts of future
growth on environmental
quality and quality of life are
minimized and adequate
levels and quality of urban
services and facilities are
maintained.

Yes The Specific Plan has been designed to minimize the negative impacts of growth and provide adequate
levels of urban services. Examples include the plan of
the detention, retention and treatment of storm water
to minimize pollution and downstream impacts;
requirements for landscaping and street trees; and the
provision of parkland at the 3 acre per 1,000
population standard which will be a higher level of
parkland than currently exist for the other portions of the Salinas community.

Policy LU-3.8: Encourage the
production of housing that
meets the needs of agricultural
and other essential workers
within the community.

Yes The residential development within the Specific Plan will be in conformance with the affordable housing
requirements of the City. Such housing will be
integrated into the Plan Area with a focus on
proximity to schools, parks, and local retail services.

Policy LU-4.1: Provide an
effective and responsive level
of fire protection … through
the Salinas Fire Department.

Yes The Specific Plan identifies a site for a new fire station located on the east side of Natividad Road. The site
was selected by the Salinas Fire Department to provide
the most responsive access to all areas of the Future
Growth Area. The project will contribute its fair share of the cost of the new fire station through the payment of the City’s Public Facility Impact Fee.
268
City of Salinas | Final Central Area Specific Plan, November 2020

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-4
Salinas General Plan Policy Consistent Discussion
Policy LU-5.1: Provide an
effective and responsive level
of police protection …
through the Salinas Police
Department.

Yes The Specific Plan with its system of interconnecting streets and streets surrounding parks and community
facilities provide excellent access and visibility for
police patrols and helps ensure effective police
protection. No police station or facility has been
identified as needed within the Specific Plan area.

However, the project will contribute its fair share of the cost of a new centralized police facility through the
payment of the City’s Public Facility Impact Fee.

Policy LU-6.1: Actively work
with Cal Water and Alco … to
ensure that high quality water
is available for the
community.

Yes The Specific Plan area will be served by Alco and Cal Water. Water Supply Assessment Reports and willserve letters have been prepared by Alco and Cal Water for the Specific Plan.

Policy LU-6.4: Actively
promote water conservation
by City residents, businesses
and surrounding agricultural
producers.

Yes The commercial and residential developments within
the Specific Plan will all utilize water conserving
plumbing fixtures which substantially reduce water
use. The parks and open space shall utilize state of the art automatic controllers with master valve capabilities and low precipitation rate equipment. The irrigation
system shall be separated per micro climate and plant
zones to achieve maximum water efficiency in
accordance with City requirements. Drought tolerant
and low water demand plant material shall be utilized
in accordance with the City’s Water Efficient
Landscaping Ordinance, the City’s Water
Conservation Ordinance, Zoning Code Landscaping
and Irrigation requirements and the City’s SWDS (in
regard to plant material for LID and similar areas).

Policy LU-7.1: Provide a
sewer system that meets the
needs of the community for
sewer collection and treatment
and work with MRWPCA for
sewer treatment needs.

Yes The development of the Specific Plan area will include provision of a sewer collection system that will convey wastewater to new and existing mains in the City and
to the Monterey One Water (formerly MRWPCA)
treatment plant. It has been determined that the
treatment plant has capacity to serve the development
of the Specific Plan area.

Policy LU-8.1: Actively
coordinate and work with
MCWRA to provide and
maintain necessary flood
control facilities.

Yes The Specific Plan includes a system of supplemental storm water detention and retention basins designed to
minimize impact on MCWRA flood control facilities
resulting from the urban development of the Specific
Plan area. These may be integrated into the creek
corridors.

Policy LU-8.3: Require new
development, to the extent
Yes The creek restoration and the supplemental detention and retention areas of the Specific Plan will be
Appendices
269

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-5
Salinas General Plan Policy Consistent Discussion
feasible, to provide flood
control facilities that are
visually attractive and
ecologically beneficial and
require on-going maintenance
of the facilities by the
development through a
maintenance district.
landscaped with suitable plant material to make them
visually attractive. These flood control facilities will be maintained by an appropriate maintenance district.

Policy LU-9.1: Work in
partnership with local school
districts and assist them in
identifying land needed for
new school sites so that
sufficient facilities are
provided for students
Yes The planning for the Specific Plan area has included coordination with the Santa Rita Elementary School
and Alisal Union School Districts to determine school
sites that will meet their needs. Alisal Union School
District acquired their site and the Santa Rita School
site is identified but has not acquired the site; the
districts are considering a boundary adjustment as of
the writing of this Specific Plan. The Salinas Union
High School District has acquired the site for a new
middle school within the Specific Plan area. Section

9.3 of this specific plan describes consultation
requirements with applicable school districts as project build out occurs.

Policy LU-9.4: Work with
Monterey Salinas Transit to
provide transit routes to serve
educational institutions.

Yes The Specific Plan design effort has coordinated with Monterey Salinas Transit to identify the most likely
route through the Specific Plan area and the stop
locations. This includes stops/shelters in the vicinity of some school facilities. The interconnected collector
and local street system allows MST to easily modify
the original transit route to accommodate additional
educational trip making needs.

Policy LU-10: Provide a level
of library facilities and services
that meet the needs of the
community
Yes The Specific Plan designates a two-acre site for the development of a new library, which would be up to
22,500 square feet in size.

Policy LU-11.3: As the City
grows, the need for additional
neighborhood, senior, youth,
and day-care centers should be
evaluated and facilities
provided as needed.

Yes The Specific Plan includes sites for two new
elementary schools, new middle school, and 43 acres
of new parks, as well as additional sites zoned for
Public and Semipublic land use to provide the
opportunity for development of specific facilities for
seniors and youth of all ages.

Community Design Element
Policy CD-1.2: Maintain
Salinas as a city with sharply
Yes The Specific Plan area is located adjacent to Boronda Road, Russell Road and Old Stage Road which are
three of the existing sharply defined edges of existing 270
City of Salinas | Final Central Area Specific Plan, November 2020

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-6
Salinas General Plan Policy Consistent Discussion
defined edges between urban
use and agricultural activities.
development in the city. With the buildout of the
Specific Plan the edge will be Russell Road and Old
Stage Road.

Policy CD-1.3: Maintain the
distinction of the City’s
urban/rural interface by using
roadway segments and/or
natural features and tree
plantings to form the
boundary between urban
development and open space
or agriculture.

Yes The Specific Plan area, when developed, will abut
agriculture and open space land uses on the north and
the east. The existing agricultural areas to the west will be developed as part of the West Area Specific Plan. A
segment of Russell Road and Old Stage Road form the
boundary between the Specific Plan urban
development and agricultural uses. Landscaped
parkway will have trees to provide a buffer between the uses. Additionally, a deed restriction shall be recorded on any property located within the Specific Plan
notifying the owner of the Right to Farm.

Policy CD-1.4: Use
landscaping, design schemes
and signing to improve the
image and distinct identity of
the city, and its neighborhoods
and its major gateways.

Yes The entrances to the Specific Plan area will include consistently designed entry features; decorative lighting and pedestrian amenities and the varied setbacks from
the surrounding roadways, as a result of landscaping,
and creek restoration, will provide a distinct Specific Plan identity. Key streets will have designated street
tree types. Commercial buildings of the Village Center
front a main street providing distinct identity for this community focal point.

Policy CD-1.5: Create a
“park-like” atmosphere for the
City with greenways,
landscaped streets and
medians and parks distributed
through the community at
convenient locations.

Yes The parks and greenways within the Specific Plan are the visual focal point of a system of local streets and pathways that extend throughout the community. The
land use plan includes two greenway streets that run
west to east across the plan area, and 43 acres of parks of varying sizes.

Policy CD-1.6: Locate and
design water retention areas
and preserve important
wildlife habitat areas to
contribute to the visual quality
of the city’s open space
system.

Yes The Specific Plan encompasses the drainage tributaries of Natividad Creek and Gabilan Creek running north
to south through the Central Area currently exist as
agricultural ditches for most of their lengths. These
corridors shall be greatly enlarged, restored and
improved to add aesthetic, ecological, recreational and stormwater retention and detention (riparian areas)
and infiltration enhancement to the local setting and
provide new open space and pathway linkages to the
various land uses in the Plan area. Picnic areas,
exercise circuits, game tables and other activity nodes may be included in these corridors where they cross
the southerly and northerly greenway streets as well as Appendices
271

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-7
Salinas General Plan Policy Consistent Discussion
along other parts of the pedestrian/bike path system.

As these areas are planned, consultation with qualified biotic and ecological experts will be required to ensure the proper balance between habitat creation/protection
and recreation design.

Policy CD-1.10: Require a
balance of housing types and
designs to avoid both
monotony and visual chaos.

Yes The Specific Plan contains a balance of housing types in accordance with the provisions of the General Plan.

Extensive use of varied designs, elevations, setbacks,
details, and color will be used to avoid the uniformity characteristic of some conventional residential
subdivisions.

Policy CD-2.1: Maximize a
strong sense of neighborhood
identity and harmony by
implementing architectural
design and community layout
techniques, such as building
location and spacing,
landscaping features, and
lighting that create distinct
neighborhoods, encourage
interactions among residents,
and facilitate safe street life.

Yes The Specific Plan neighborhood identity is focused on the communal open space areas and the pedestrian
oriented streets that interconnect the communal
spaces. The varied designs of the parks give each the
neighborhoods and sub- areas its own identity.

Decorative lighting, street furniture, neighborhood
identification signs, pedestrian amenities and other
features will also be provided to promote distinctive
neighborhoods and encourage a safe and active street
life.

Policy CD-2.5: Encourage the
use of design features to create
an environment that
maximizes the number of
“eyes on the street” and
reduces potential criminal
activity.

Yes The Specific Plan is designed to maximize “eyes on the street” and “eyes on the public realm.” Residential
units will be designed with entryways and first and
second story windows oriented to the street. Parks are
generally surrounded by streets on two or more sides
by streets. In addition, residential units face toward
these parks adding to the visual security.

Policy CD-2.7: Minimize the
use and visual effect of sound
attenuation walls.

Yes Alternatives to sound walls are encouraged in the
Specific Plan. For example, frontage streets with
landscaped parkways assist with reduce sound levels in
rear yards. Sound attenuation walls are often required
along arterial streets and may be required in some
areas of the Specific Plan. To minimize the visual
effect of any sound walls the parkways and open space
along surrounding arterial streets are a minimum of 24- 28 feet and often visually expands to much larger areas when the parkway is adjacent to the supplemental
detention, and retention basins. The use of areas along the major surrounding roads for small, midsize, and
large scale LID features allows for a varied residential 272
City of Salinas | Final Central Area Specific Plan, November 2020

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-8
Salinas General Plan Policy Consistent Discussion
setback and reduces the need for sound attenuation
walls and where they may be required the length is
minimized and they are screened with landscaping.

Policy CD-2.8: Avoid large
un-landscaped parking areas
and blank building walls
facing streets and adjoining
properties.

Yes The parking areas are visually divided into smaller areas by landscaping and planting islands which are
included throughout the parking area. The larger
buildings and parking areas will be set back from the
major streets and partially screened from view by
smaller scale buildings fronting the street, parking lot trees and other landscape features.

Policy CD-3.1: Create and
preserve distinct, identifiable
neighborhoods that have
traditional neighborhood
development (TND)
characteristics …
Yes The Specific Plan will be developed in accordance with the New Urbanism District Standards of the City’s
Zoning Code(except where modified standards apply
in the Specific Plan), which is based on TND
principles and the provision of the Specific Plan that
identify how each neighborhood is to be developed
with its own TND characteristics (see response to
Policy LU-1.4).

Policy CD-3.4: Actively
encourage mixed-use
development in order to
provide a greater spectrum of
housing near businesses,
alternative modes of
transportation and other
activity areas.

Yes The Village Center and the immediately adjacent
residential areas contain some of the highest densities in the Specific Plan area. This concentration of
residences and commercial in both horizontal and
vertical mixed use developments facilitate walking for
some daily trips and to the planned transit stop within the Village Center.

Policy CD-3.6: Promote and
maintain a pedestrian friendly
atmosphere by encouraging
“pedestrian zones” with
increased landscaping, use of
traffic-calming techniques on
local streets, adequate
separation from automobile
traffic and the inclusion of
amenities, such as lighted
sidewalks and increased
lighting along sidewalks.

Yes The Specific Plan area includes an interconnected
system of pedestrian zones in the form of Small and
Neighborhood Parks, as well as open space creek
corridors. Each creates a different kind of pedestrian
zone ranging from expansive areas of sports fields and
other active and passive park areas to the small scale
green spaces primarily serving a local residential area.

Some intersections along the pathways system may use
“bulb-outs” to slow vehicular traffic and facilitate safe pedestrian crossings. Sidewalks with 8-foot parkways
(between the curb and the pathway) with street trees
provide separation from automobile traffic and
promote a pedestrian friendly environment. A 12-feet
wide off-street shared use pedestrian path (the
southerly greenway) will also be provided which will
connect to the greater North of Boronda Future
Growth Area (FGA) located to the west and east. This
Appendices
273

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-9
Salinas General Plan Policy Consistent Discussion
will provide east-west pedestrian and bicycle access
across the entire length of the Specific Plan and the
greater North of Boronda FGA. A 7-feet wide
northerly greenway pedestrian path will also be
provided along this same length.

Policy CD-3.8: Promote the
use of alternative modes of
transportation, including bus,
rail, bicycling, and walking.

Yes The Specific Plan provides an extensive system of
paths connecting schools, parks, and Village Center
that promotes the use of walking and bicycles for some
daily trips. The paths also facilitate access to the bus stops/bus shelters expected to be located in the Village Center and other areas of the Specific Plan. Supportive bicycle parking will be installed. Pathways will also
link to the adjacent West and East FGAs.

Policy CD-3.9: Group
neighborhood shopping
centers, schools, civic and
recreational uses, parks, and
public transit opportunities
together in new
neighborhoods to create an
activity center focal point for
the neighborhoods they serve.

Yes The Village Center, Community Park, and all schools are located along local collector roadways that may be
used by transit depending on the final route plan
determined by MST. In particular, the highest transit
generating uses are located in the Village Center and
are anticipated to be potential transit routes as
illustrated in Figure 5-2.

Housing Element
Policy H-1.1: Encourage a
variety of housing types,
designs, and prices throughout
the City to maintain housing
choice and enable households
of all types and incomes levels
the opportunity to find
suitable ownership or rental
housing that supports healthy
living. Support the
development of cost effective
innovations such as micro
units, smaller houses on
smaller sites,
coliving/cohousing,
construction from repurposed
shipping containers, and
Single Room Occupancy
(SRO) units.

Yes The Specific Plan is consistent with the range of
housing required by the General Plan with
approximately 652 low residential (17%), 1,542
medium residential (39%), and 656 high residential
(17%). The Specific Plan will provide a program of
affordable housing in accordance with City
requirements.

The overall density of the Specific Plan and the
development standards facilitate cost effective
innovations in housing.
274
City of Salinas | Final Central Area Specific Plan, November 2020

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-10
Salinas General Plan Policy Consistent Discussion
Policy H-1.2: Consistent with
State law, continue to regulate
transitional and supportive
housing as a residential use to
be subject only to the same
development regulations and
standards of similar uses in the
same zone.

Yes Any transitional and supportive housing within the
Specific Plan would be subject to the same
development regulations as other housing.

Policy H-1.3: New residential
development shall be
adequately served by services
and facilities, including park
and recreation areas, libraries,
sanitary and storm sewers,
transportation, public safety
and other services. Continue
to ensure impact fees are
adequate to provide these
services and facilities to
residential development
through periodic review and
updating.

Yes The Specific Plan includes a Village Center, which
includes retail, housing, commercial, and professional
office uses. Within the immediate vicinity of the
Village Center are additional higher density residential areas. In addition, the Specific Plan has a network of
paths that connect residential to parks, schools, and the Village Center and to the greater North of Boronda
FGA.

The development of the Specific Plan will include the
payment of appropriate impact fees that the City will
be periodically reviewing and updating.

Policy H-1.4: Identify
adequate sites to facilitate and
encourage housing production
for the existing and projected
housing needs of the City.

Yes The Specific Plan allows up to 3,911 housing units
with approximately 652 low residential (17%), 1,542
medium residential (39%), and 656 high residential
(17%).

Policy H-1.5: Support the
concept of “aging in place” by
providing a range of housing
types and tenure that allows
people to remain in the
community as their housing
needs change.

Yes The Specific Plan, in conformance with General Plan requirements, provides housing at low, medium, and
high densities to respond to the varying needs of
families and individuals at any point in their life and as their housing needs may change over time. In addition
a variety of housing will be built in each of the density categories providing further opportunities for
purchasers or renters to obtain housing suitable for
their circumstances. Single level housing units will also accommodate people with disabilities and declining
health. The location of several higher density housing
products adjacent to the Village Center provides senior housing opportunities in close walking distance to
transit, commercial, office and personal services, and
potentially to health services which may locate in the
Village Center.

Appendices
275

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-11
Salinas General Plan Policy Consistent Discussion
Policy H-1.6: Encourage
diverse, mixed-income
neighborhoods throughout the
City through the geographic
dispersal of units affordable to
lower and moderate income
households, increased location
choice for voucher recipients,
and continue to follow state
and federal fair housing
requirements (including City
contracts with housing and
public services recipients).

Yes The Specific Plan includes a Village Center, which
includes retail, housing, commercial, and professional
office uses. A minimum of 410 residential units will be located within the Village Center. Within the
immediate vicinity of the Village Center are additional higher density residential areas. In addition, the
Specific Plan has a network of paths that connect
residential to parks, schools, and the Village Center
and greater North of Boronda FGA.

The Specific Plan will provide a program of affordable
housing in accordance with City requirements.

Policy H-1.7: Ensure that new
residential development and
reuse/revitalization projects
are compatible with
surrounding neighborhoods by
requiring new developments
to comply with the City’s
Zoning Code development
regulations and design
standards.

Yes The Specific Plan is designed to be compatible with existing residential neighborhoods to the south and
west with roadway connections to those
neighborhoods to facilitate internal travel. Included in the Specific Plan are development regulations
consistent with the intent that this area be developed
using the principles of Division 8 of the Zoning Code.

Policy H-1.9: Encourage the
development of higher density
apartments, townhomes, and
condominiums in locations
that are served by major
transit corridors and have
good pedestrian and cyclist
facilities, continue to use
Crime Prevention Through
Environmental Design
principles as part of housing
design and construction,
and/or are within walking
distance to neighborhoodserving retail and key
destinations (parks, schools,
childcare, stores with healthy
food options, employment,
Yes The Specific Plan includes a Village Center and
Planning Areas designated for higher density
residential located along Boronda Road which is a
transit corridor. In addition, the Specific Plan has a
network of paths that connect residential to parks,
schools, and the Village Center and existing and future projected transit stops. Crime Prevention Through
Environmental Design principles have been part of the
overall Specific Plan layout and will be part of future individual project design.
276
City of Salinas | Final Central Area Specific Plan, November 2020

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-12
Salinas General Plan Policy Consistent Discussion
social services, and health
care, etc.).

Policy H-1.10: Promote the
development of mixed-use
neighborhoods designed to
encourage travel by walking,
bicycling, and mass transit.

Yes The Specific Plan locates the higher density residential land uses within or adjacent to the Village Center
which is also the location of the expected MST transit
corridor through the Future Growth Area. In addition,
the Specific Plan has a network of pathways that
connect residential to parks, schools, and the Village
Center and to the greater North of Boronda FGA to
the east.

Policy H-1.11: In Future
Growth Areas ensure that
each Specific Plan includes a
range of housing types by
requiring new residential
developments of over 1,000
units to include a mix of
densities.

Yes The Specific Plan is consistent with the range of
housing required by the General Plan with
approximately 652 low residential (17%), 1,542
medium residential (39%), and 656 high residential
(17%).

Policy H-1.12: In Future
Growth Areas, promote
mixed use development to
increase housing opportunities
by requiring commercial and
professional office
development to incorporate
housing opportunities on site
or in close proximity, unless
the City Council makes a
finding that it would be
inappropriate to require onsite housing in a proposed
new commercial or
professional office
development and in that case
shall require equivalent
housing to be constructed at
an off-site location.

Yes The Specific Plan includes a Village Center, which
includes retail, housing, commercial, and professional
office uses. A minimum of 410 residential units will be located within the Village Center. Within the
immediate vicinity of the Village Center are additional higher density residential areas.

The Specific Plan also includes several higher density
housing sites adjacent to the Village Center which
provides housing opportunities in close walking
distance to transit, commercial, office and personal
services, and potentially to health services which may
locate in the Village Center
Policy H-2.6: Ensure new
residential developments are
compatible (e.g., scale, size,
design and appearance) with
surrounding uses through
Yes The Specific Plan is designed to be compatible with existing residential neighborhoods to the south and
west with roadway connections to those
neighborhoods to facilitate internal travel. Included in the Specific Plan are development regulations
Appendices
277

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-13
Salinas General Plan Policy Consistent Discussion
implementation of the City’s
Zoning Code development
regulations and design
standards.
consistent with the intent that this area be developed
using the principles of Division 8 of the Zoning Code.

Policy H-2.8: Encourage
developers to maximize
energy conservation and
exceed the provisions of Title
24 of the California Building
Code through green building
techniques and materials.

Yes In addition to conforming to Title 24 of the California Building Code the Specific Plan includes provisions to
meet the objectives of the American Planning
Association Policy Guide on Planning for
Sustainability.

Policy H-3.1: Assist in the
production and conservation
of housing affordable to
extremely low, very low, low,
and moderate income
households, with a focus on
the need for housing for the
local workforce and workers
essential to our community.

Yes The Specific Plan will provide a program of affordable housing in accordance with City requirements.

Policy H-3.2: Continue to
encourage the development of
affordable housing units with
three or more bedrooms,
adequate to accommodate
large households.

Yes The Specific Plan will provide a program of affordable housing in accordance with City requirements which
will respond to various household sizes.

Policy H-3.3: Encourage and
support the development of
senior housing and assisted
living facilities on sites within
proximity to public
transportation and services.

Yes The Specific Plan includes several higher density
residential Planning Areas adjacent to the Village
Center .These Planning Areas provide senior housing
opportunities in close walking distance to transit,
commercial, office, personal services, and potentially
to health services.

The Specific Plan, in conformance with General Plan
requirements, provides housing at low, medium, and
high densities to respond to the varying needs of
families and individuals at any point in their life and as their housing needs may change over time. In addition
a variety of housing will be built in each of the density categories providing further opportunities for
purchasers or renters to obtain housing suitable for
their circumstances. Single level housing units will also 278
City of Salinas | Final Central Area Specific Plan, November 2020

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-14
Salinas General Plan Policy Consistent Discussion
accommodate people with disabilities and declining
health. The location of several higher density housing
products adjacent to the Village Center provides senior housing opportunities in close walking distance to
transit, commercial, office and personal services, and
potentially to health services which may locate in the
Village Center.

Policy H-3.4: Encourage and
support the provision of safe
and decent housing for lower
income households and those
with special needs within
proximity of public
transportation and services.

Yes The Specific Plan will provide a program of affordable housing in accordance with City requirements.

The Specific Plan will provide single level housing
units generally seen as the most appropriate for persons with physical disabilities. These units will typically be part of the higher density residential Planning Areas
within or adjacent to the Central Community core.

These residential sites are also in proximity to transit, shopping and other community services facilitating
access to those uses by disabled residents.

Policy H-3.7: Facilitate the
development of affordable
housing through regulatory
incentives, density bonuses,
inclusionary housing, and
financial assistance.

Yes Within the Specific Plan individual housing projects that include affordable housing will respond to the
available state and local incentives and financial
assistance to the extent feasible.

Policy H-3.9: Support
activities and participate in
planning of initiatives such as
Monterey County’s Health in
All Policies (HiAP), Building
Healthy Communities (BHC)–
East Salinas, Crime
Prevention Through
Environmental Design
(CPTED) program,
AMBAG’s Sustainable
Communities Strategy, and
the City’s Urban Greening
Plan that contribute to the
quality of community and
neighborhood environments.

Yes Crime Prevention Through Environmental Design
principles have been part of the overall Specific Plan
layout and will be part of future individual project
design.

In addition to conforming to Title 24 of the California Building Code the Specific Plan includes provisions to
meet the objectives of the American Planning
Association Policy Guide on Planning for
Sustainability.

Appendices
279

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-15
Salinas General Plan Policy Consistent Discussion
Policy H-3.14: Encourage the
development of housing and
mixed uses that foster
supportive environments for
single parent female-headed
households, such as on-site
childcare and after school
programs.

Yes The Specific Plan, in conformance with General Plan requirements, provides housing at low, medium, and
high densities to respond to the varying needs of
families and individuals at any point in their life and as their housing needs may change over time. In addition
a variety of housing will be built in each of the density categories providing further opportunities for
purchasers or renters to obtain housing suitable for
their circumstances.

The Specific Plan includes 3 school sites serving grades K-8. These schools are located within or adjacent to
residential neighborhoods and connected by the
community trail system facilitating participation in
after school programs.

Conservation/Open Space Element
Policy COS-1.1: Work with
regional and local water
providers to ensure that
adequate supplies of water are
available to meet existing and
future demand.

Yes The Specific Plan area has coordinated with Cal Water and ALCO, which are the designated water providers.

A Water Supply Assessment Reports have been
completed and the report has concluded that adequate
supplies of water are available.

Policy COS-1.4: Maintain and
restore natural watersheds to
recharge aquifers and ensure
the viability of the ground
water resources.

Yes The natural drainage tributaries of Natividad Creek and Gabilan Creek running north to south through the
Central Area currently exist as agricultural ditches for most of their lengths. These corridors shall be greatly enlarged, restored and improved to add aesthetic,
ecological, recreational and stormwater retention and
detention (riparian areas) and infiltration enhancement to the local setting and provide new open space and
pathway linkages to the various land uses in the Plan
area.

Policy COS-2.1: Participate in
and implement local and
regional programs that
promote water conservation.

Yes All development within the Specific Plan will utilize water conserving plumbing fixtures, landscape
irrigation techniques and other technologies and design features consistent with City, local and regional water conservation programs and ordinances.

Policy COS-2.3: Apply
standards that promote water
conservation in agricultural,
residential and non-residential
uses.

Yes All development The within the Specific Plan will
utilize water conserving plumbing fixtures, landscape
irrigation techniques and other technologies and design features that will significantly reduce the per capita
water use in accordance with the requirements
(Ordinances) of the City. In addition, automatic
280
City of Salinas | Final Central Area Specific Plan, November 2020

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-16
Salinas General Plan Policy Consistent Discussion
controllers with master valve capabilities and low
precipitation rate equipment. The irrigation system
shall be separated per micro climate and plant zones to achieve maximum water efficiency. Drought tolerant
and low water demand plant material shall be used in
accordance with the City’s Water Efficient
Landscaping Ordinance, the City’s Water
Conservation Ordinance, Zoning Code Landscaping
and Irrigation requirements and the City’s SWDS (in
regard to plant material for LID and similar areas).

Policy COS-3.1: Maintain a
compact urban form, locating
growth areas to minimize the
loss of important agricultural
resources while allowing for
the reasonable expansion of
the City to address projected
population growth.

Yes The Specific Plan area is located on the north side of the City, which has been determined to be away from
the most productive agricultural land in accordance
with the Greater Salinas Area Memorandum of
Understanding between the City and County of
Monterey. The overall net residential density is over 9 DU/AC in accordance with the requirements of the
General Plan.

Policy COS-3.4: Minimize
conflicts between agricultural
and urban uses through the
use of buffer zones, roads and
other physical boundaries.

In In the case of the Central area, the agricultural lands to be protected by buffers are those on the north side of
the future Russell road (the Protected Lands). Buffers
will occur where residential uses located along the
south side of Russell Road from the continuing
agricultural uses on their lands on the north side of
Russell Road by dedicating a temporary 200-foot wide
buffer along the northerly boundary between the front
of the homes on the south side of Russel Road and the
agricultural uses on the north side of Russell Road and shall not access their farm lands from Russell Road
unless dirt/mud mitigation features are provided and
approved by the City Engineer
Policy COS-5.1: Protect and
enhance creeks, river
corridors, the reclamation
ditch, sloughs, wetlands and
other potentially significant
biological resources for their
value in providing visual
amenity, flood protection,
habitat for wildlife and
recreational opportunities.

Yes The natural drainage tributaries of Natividad Creek and Gabilan Creek running north to south through the
Central Area currently exist as agricultural ditches for most of their lengths. These corridors shall be greatly enlarged, restored and improved to add aesthetic,
ecological, recreational and stormwater retention and
detention (riparian areas) and infiltration enhancement to the local setting and provide new open space and
pathway linkages to the various land uses in the Plan
area.

Policy COS-6.3: Encourage
development design that
The mixed use character of the Specific Plan including
neighborhood and community parks, K through 8
Appendices
281

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-17
Salinas General Plan Policy Consistent Discussion
maintains air quality and
reduces direct and indirect
emissions of air contaminants.
schools and a locally serving mixed use center (Village Center) will significantly reduce the vehicle miles
traveled by residents and contribute to reduced air
contaminants from vehicles.

Policy COS-6.4: Support
alternative modes of
transportation, such as
walking, biking and public
transit, and develop bike and
pedestrian-friendly
neighborhoods to reduce
emissions associated with
automobile use.

Yes The Specific Plan includes a network of pathways that connect residential areas to parks, schools, and the
Village Center. This will facilitate walking, bicycling, and public transit for some daily trips. The proximity
of public and commercial facilities will also reduce the length of automobile trips, further reducing emissions
associated with automobile use.

Policy COS-7.1: Develop a
high quality public park
system that provides adequate
space and facilities for a
variety of recreational
opportunities conveniently
accessible to all Salinas
residents.

Yes The Specific Plan includes local neighborhood and
small parks slightly in excess of that required by the
Quimby Act located so as to have maximum
accessibility. In particular the neighborhood and small parks are centrally located in each neighborhood to be
convenient to local residents.

Policy COS-7.3: Plan park
and recreation facilities in
cooperation with concerned
public and private agencies
and organizations, particularly
school districts and
neighborhood residents.

Yes The Specific Plan parks and recreation facilities have been sited in coordination with the City. The Specific
Plan cites a range of potential recreational facilities that can be included within parks, but the final
program of facilities will be determined at a later date by the City Parks staff and City Park and Sports
Facility and other park standards. The sizes and
configuration of the parks have been determined to
ensure they can accommodate the active sport fields
that will be required to meet the needs of the residents in the CASP (See Figure 4-1).

Policy COS-7.6: Work with all
school districts in planning for
parks and recreation facilities
to maximize community
recreation opportunities
through joint use.

Yes The Specific Plan has planned the school and park sites in coordination with the Santa Rita Elementary School
District, Alisal Union School District and Salinas
Union High School District. Neighborhood parks are
located near the elementary school sites and joint use
opportunities continue to be available. Pedestrian
connections will be provided to the school sites to
facilitate resident access to the school from the
surrounding neighborhoods.

Policy COS-7.10: Consider
formation of special districts,
Yes The City, through the draft Public Services and Public Facilities Financing Plan – Salinas Future Growth
282
City of Salinas | Final Central Area Specific Plan, November 2020

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-18
Salinas General Plan Policy Consistent Discussion
issuance of bonds and other
means for financing large
urban parks and facilities
serving all of Salinas.

Area (November 2, 2007), has suggested the
establishment of a Community Facilities District
(CFD) and/or LLMD to provide public maintenance
services to the North of Boronda FGA in excess of
service levels elsewhere in the City. A higher level of maintenance may be desired for the North of Boronda
FGA and the residents living in the area would pay for
that enhanced service through an LLMD or a
maintenance CFD as agreed to by the owner and the
City. An LLMD would be formed to pay for other
maintenance as specified below.

Policy COS-7.11: Develop
and maintain an integrated
system of open space corridors
and trails along utility
easements, power
transmission-line rights of
way, the reclamation ditch,
stream banks, drainage-ways,
slopes and other natural
features.

Yes The natural drainage tributaries of Natividad Creek and Gabilan Creek running north to south through the
Central Area currently exist as agricultural ditches for most of their lengths. These corridors shall be greatly enlarged, restored and improved to add aesthetic,
ecological, recreational and stormwater retention and
detention (riparian areas) and infiltration enhancement to the local setting and provide new open space and
pathway linkages to the various land uses in the Plan
area.

Policy COS-7.12: Link activity
center, recreation
opportunities, transit nodes
and other services to the
integrated trails network.

Yes The Specific Plan pathways network links the
residential areas to the schools, parks and Village
Center.

Policy COS-7.13:

Developments within Future
Growth Areas shall be
conditioned to provide all the
land and improvements
required to achieve the
parkland standard of three
acres of developed public
parkland per 1,000 residents,
to meet existing park acreage
needs, as referenced in Table
COS-5. All new parks
constructed within the City
shall meet, at a minimum, the
park standards established in
Table COS-2.

Yes The Specific Plan includes designated park sites
totaling approximately 44.06 acres. At a standard of 3
acres per 1,000 population, the park requirement
would be 43.06 acres. The Specific Plan is providing
approximately one acre of parks beyond the standard
of 3 acres per 1,000 residents. The Specific Plan
identifies a range of park sizes configured differently than the three parks standards currently shown in the
General Plan. This is consistent with the New
Urbanism approach that places park facilities within
easy walking distance of residents.

Appendices
283

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-19
Salinas General Plan Policy Consistent Discussion
Policy COS-8.2: Apply
standards that promote energy
conservation in new and
existing developments.

Yes The commercial and residential developments within
the Specific Plan area will utilize energy efficient
equipment to the greatest extent feasible. This will
include energy efficient appliances, vehicle charging
opportunities, heating and cooling systems, and energy
saving insulation in all structures.

Policy COS-8.6: Encourage
the creation and retention of
neighborhood-level services
(e.g., family medical offices,
dry cleaners, grocery stores,
drug stores) throughout the
City in order to reduce energy
consumption through
automobile use.

Yes The Specific Plan has a Village Center on Boronda
Road that will contain a wide range of local and
community serving retail and personal services. It is
accessible to all residents of the Specific Plan area via pathways and local neighborhood streets. The Specific
Plan also includes neighborhood level services
including K through 8 education and recreation
facilities and parks.

Circulation Element
Policy C-1.1: Create and
preserve distinct, identifiable
neighborhoods that have
traditional neighborhood
development (TND)
characteristics and
corresponding circulation
systems. Specifically, the street
network should have the
following characteristics:
➢ Individual blocks should
average less than 600 feet
in length and less the 1,800
feet in perimeter;
➢ Streets should be organized
in a comprehensive
hierarchical network that
manifests the structure of
the neighborhood;
➢ Cul-de-sacs should be
avoided unless natural
conditions demand them;
➢ The street network should
be interconnected; and
➢ Transit access, passenger
safety, and transit facilities
Yes The Specific Plan has designed neighborhoods focused on local parks. Local streets with widened sidewalks
and parkways focus on these community facilities.

Individual blocks vary in length but average less than
600 feet in length and 1800 feet in perimeter. The
interior streets are an interconnected system of
residential collectors and local residential streets. The plan is very adaptable for transit with a transit stop
proposed for the Village Center and potentially at the
community park. Cul-de-sacs are avoided.
284
City of Salinas | Final Central Area Specific Plan, November 2020

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-20
Salinas General Plan Policy Consistent Discussion
should be included in the
street network design.

Policy C-1.2: Strive to
maintain traffic Level of
Service (LOS) D or better for
all intersections and
roadways.

Yes Based on the traffic study for the Specific Plan
prepared by Fehr and Peers, all internal intersections of the Specific Plan will maintain a Level of Service of D or better. External intersection deficiencies will be
addressed in the EIR.

Policy C-1.6: Discourage
diversion of traffic to local
streets by providing maximum
capacity on arterial streets and
locating high traffic generating
uses on or near arterial
frontages.

Yes The Village Center is located on Boronda Road to
allow and facilitate access for drive-by traffic on that major 6-lane arterial street. The Village Center is also connected via local roads to all the residents of the
Specific Plan area so they do not have to use the
arterial streets to access the center. Vehicle related uses and the anchor grocery store are located on the
subareas nearest to Boronda Road.

Policy C-1.7: Design roadway
capacities to adequately serve
planned land uses.

Yes The Specific Plan internal roadways are sized to
accommodate the planned land uses but also not
oversized to encourage higher speed and excessive cutthrough traffic. The paved widths of local residential streets are 32 feet, 34 feet, and 36 feet paved sections based on the ADT projected for that local street and in accordance with the New Urbanism District residential
street standards.

Policy C-1.9: Use traffic
calming methods within
residential areas where
necessary to create a
pedestrian-friendly circulation
system.

Yes The Specific Plan will use bulb-outs, raised
intersections, traffic circles, and other traffic calming devices to slow traffic and promote pedestrian-friendly streets.

Policy C-3.2: Design
development and
reuse/revitalization projects to
be transit oriented to promote
the use of alternative modes of
transit and support higher
levels of transit service.

Yes The Specific Plan contains an interconnected system of collector roadways that support various alignments of
future transit through the area. The Village Center is
expected to have a transit stop.

Policy C-4.1: Continue to
develop a network of on- and
off-street bicycle routes to
encourage and facilitate the
use of bicycles for commute,
recreational, and other trips.

The existing Class II bicycle lanes are located on
Boronda Road.. As shown on Table 5-1, bike lanes are
proposed . These bike lanes, and the internal plan area path system, will augment the bicycle lanes on the
surrounding arterial streets of Boronda Road, Russell
Road, Old Stage Road and Natividad Road. The
Appendices
285

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-21
Salinas General Plan Policy Consistent Discussion
Eliminate gaps and provide
connection between existing
bicycle routes.
interconnected local street system of a New Urbanism
plan results in lower volume lower speed vehicular
traffic that is compatible with mixed flow bicycles and vehicles. The off-street bicycle travel is incorporated in the network of pathways. A 12-feet wide off-street
shared use path will be provided along the entire length of the Specific Plan and greater North of Boronda
FGA located to the east.

Policy C-4.2: Increase
availability of facilities such as
bicycle racks and wellmaintained and well-lit bike
lanes, that promote bicycling.

Yes Bicycle racks are included in the expected facilities program for the small and neighborhood parks. Bicycle
racks will also be provided in the Village Center in the vicinity of Main Street and village greens. The school
district facilities also typically provide bicycle racks for those students and staff who ride bicycles.

Policy C-4.3: Encourage
existing businesses and require
new construction to provide
on-premise facilities to aid
bicycle commuters, such as
on-site safe bicycle parking.

Yes The new commercial businesses in the Specific Plan
will be located within the Mixed Use Village Center.

Bicycle racks will be provided in one or more highly
visible locations to provide a convenient and secure
facility for bicycle commuters.

Policy C-4.4: Improve the
biking environment by
providing safe and attractive
cut-throughs, bike lanes, and
bike paths for both
recreational and commuting
purposes.

Yes The Specific Plan interconnected local street system is the primary bicycle environment for recreation and
commuting purposes. These relatively low volume,
low speed streets are suitable for bicycles sharing the road with vehicles and some contain multi-use
pathways for bicycle use .

Policy C-4.5: Where possible,
ensure that roadway
improvements (i.e., widening
and re-striping), as well a new
overpasses, allow for safe onstreet bike lanes or adequate right lane space for bicycles.

Yes The CASP endeavors to encourage the use of
alternative modes of transportation by incorporating
bicycle and pedestrian friendly designs through an
integrated system of roads, pedestrian paths, and
bikeways. At the buildout of the project, bike lanes in the east-west direction are to be provided along both
sides of the future Russell Road and Old Stage Road.

In the north-south direction, bike lanes are to be
provided along the extensions of Independence
Boulevard (0.7 miles) and Constitution Boulevard (1.1
miles). Boronda Road and Natividad Road are to be
widened at the buildout of the study project (2.1
miles). These roadways will continue to provide bike
lanes along both sides.
286
City of Salinas | Final Central Area Specific Plan, November 2020

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-22
Salinas General Plan Policy Consistent Discussion
Policy C-4.6: Ensure that all
pedestrian and bicycle route
improvements meet the
Americans with Disabilities
Act (ADA) standards for
accessibility, and Caltrans
standards for design.

Yes The Specific Plan identifies that all pedestrians and bicycle route improvements will be ADA compliant
and in accordance with Caltrans standards for design.

The details of these improvements will be part of
subsequent Tentative Maps and Site Development
Plans.

Policy C-4.7: Encourage
parking lot designs that
provide for safe and secure
bicycle parking.

Yes The Specific Plan includes one area with large parking lots in the Village Center on Boronda Road. The
illustrative plan for the Village Center allows for areas suitable for bicycle parking near the large parking lots serving the Main Street and village green area.

Policy C-5.2: Encourage all
new bus stops and changes in
existing bus stops to take
pedestrian access into
consideration.

Yes The currently planned route of the MST transit service and the proposed stops is illustrated in Figure 5-2. The primary pedestrian pathways system that connects to
these stops as well as to the educational, park and
commercial facilities is illustrated in Figure 5-3.

Policy C-5.3: Ensure that all
pedestrian route
improvements meet with
ADA standards for
accessibility.

Yes The Specific Plan identifies that all pedestrian route improvements are ADA compliant.

Policy C-5.4: Encourage
parking lot design that
promote pedestrian access and
safety.

Yes The concept for the Village Center shows parking lots that provide for pedestrian circulation and minimize
major conflicts between pedestrians and vehicular
traffic.

Policy C-5.5: Improve the
walking environment by
providing safe and attractive
sidewalks, cut-throughs, and
walkways, for both
recreational and commuting
purposes.

Yes The Specific Plan contains a network of pathways
comprised of widened sidewalks and parkways that
interconnect all the schools, parks, shopping, and
employment areas. All streets within the development
will include ADA-compliant paths along all street
frontages and access ramp at curb returns and other
locations required by law and City/State standards.

Safety Element
Policy S-2.1: Apply design
techniques and standards that
are aimed at reducing criminal
activity in new development
and reuse/revitalization
projects.

Yes The Specific Plan design includes public spaces such as schools and parks that are surrounded on most sides by
local streets. This improves the visibility into these
facilities, thus providing visual security. The pathways network is mostly along the local streets system also
providing “eyes-on-the-street.” Individual homes will
include first and second story front facing windows
that facilitate views to the street, also improving visual Appendices
287

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-23
Salinas General Plan Policy Consistent Discussion
security. Detailed designs will be reviewed according
to CPTED principles.

Policy S-2.2: Ensure that
adequate street and property
lighting is provided and
maintained in order to protect
public health and safety.

Yes The street and property lighting will provide
appropriate illumination for public health and safety in accordance with CPTED principles, City
standards/requirements and will be shown on the
subsequent Tentative Maps and Site Development
Plans.

Policy S-2.3: Encourage
development designs and land
use mixtures that serve to
focus eyes and attention on
public areas.

Yes The Specific Plan street system is designed to focus eyes and attention on the public areas. Parks are often located at the visual termination of local streets and
schools are surrounded on 2 or more sides by local
streets to increase visibility into the sites.

Policy S-4.3: Design flood
control system in new
development areas to avoid
increasing flood hazard
elsewhere.

Yes Individual projects within the CASP will be required to provide parcel based mitigation. This may include but
is not limited to integrating Requirements 1 (Common
Requirements), 2 (Additional Source Controls) and 3
(Stormwater Treatment) into their site design,
including LID site planning strategies, source control
measures, and uniformly distributed decentralized
treatment control BMPs.

Gabilan Creek and Natividad Creek are designated as
areas of one percent chance annual flood by the
Federal Emergency Management Agency (FEMA)
Flood Insurance Rate Maps (FIRMs) (Gabilan Creek
is located in Flood Zone AE, and Natividad Creek is
located in Flood Zone “A”, Flood Insurance Rate Map
(FIRM) panels 06053C0226G, 06053C0228G, and
06053C0230G.). A FEMA map revision will be
required to adjust the boundaries of the “A” flood
designation prior to any development in the flood
zone. The remainder of the site is located in unshaded
Zone X.

Policy S-4.4: Maintain open
areas needed to retain
stormwater and prevent
flooding of urban and
agricultural land.

Yes The Specific Plan maintains specific creek corridors and open space areas for the supplemental detention
and retention facilities noted above combined with
site/parcel based PCBMPs to the MEP to prevent
flooding of downstream urban and agricultural areas.

Policy S-4.5: Provide stormwater retention capacity
consistent with Reclamation
Ditch capacity to avoid
Yes The Specific Plan includes a system of supplemental storm water detention and retention basins and
site/parcel based PCBPs to the MEP designed to
eliminate impact on the Reclamation Ditch resulting
from the urban development of the Specific Plan area.
288
City of Salinas | Final Central Area Specific Plan, November 2020

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-24
Salinas General Plan Policy Consistent Discussion
damage to urban development
as a result of a 100-year flood.

Policy S-5.2: Ensure that street
widths and clearance areas are
sufficient to accommodate fire
protection equipment and
emergency vehicles.

Yes The three specific plans which comprise the Future
Growth Area (FGA) and the City have jointly
completed a study to assure the narrower street widths
and curb radii of the FGA are adequate for emergency
vehicles. That study conducted by Fehr and Peers was
completed in October 2005. It is attached in
Appendix L
Noise Element
Policy N-1.1: Ensure that new
development can be made
compatible with the noise
environment by using
noise/land use compatibility
standards and the Noise
Contours Map as a guide for
future planning and
development decisions.

Yes The Specific Plan area is potentially impacted by noise from the surrounding arterial roadways. Residential
development is set back from these roadways by
widened parkways and landscaping and water quality
filtration areas.. In some cases limited sound walls
with appropriate landscaping may be necessary to
mitigate noise impacts from surrounding roads.

Policy N-1.2: Require the
inclusion of noise-reducing
design features in
development and
reuse/revitalization projects to
address the impact of noise on
residential development.

Yes The Specific Plan area is potentially impacted by noise from the surrounding arterial roadways. Residential
development is set back from these roadways by
widened parkways and landscaping and water quality
filtration areas. In some cases limited sound walls with appropriate landscaping may be necessary to mitigate
noise impacts from surrounding roads.

Policy N-2.1: Ensure noise
impacts generated by
vehicular sources are
minimized through the use of
noise control measures (e.g.,
earthen berms, landscaped
walls, lowered streets).

Yes The Specific Plan area is potentially impacted by noise from the surrounding arterial roadways. Residential
development is set back from these roadways by
widened parkways and landscaping and water quality
filtration areas. In some cases limited sound walls with appropriate landscaping may be necessary to mitigate
noise impacts from surrounding roads.

Policy N-2.2: Control truck
traffic routing to reduce
transportation –related noise
impacts on sensitive land uses.

Yes The Specific Plan area contains few land uses that will require routine truck traffic. The Village Center will
require truck deliveries. Primary truck access to the
Village Center is from Boronda Road.

Economic Development Element
Policy ED-LU-1.6: Facilitate
the review and approval of the
North of Boronda Future
Growth Area Specific Plans to
Yes The Specific Plan has been created to allow the
discretionary action by the City as the key step in
creating a high quality residential and mixed use
Appendices
289

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-25
Salinas General Plan Policy Consistent Discussion
create high-quality residential
and mixed-use housing
opportunities to meet the
housing needs of an
expanding community
workforce (Economic
Opportunity Area I and a
portion of H).
development in the North of Boronda Future Growth
Area.

Policy ED-C-2.14: Utilize
roundabouts, where feasible,
to promote improved traffic
operations and to enrich the
driving experience. Utilize the
center of the roundabouts for
special signage, traffic
features, and public art.

Yes The Specific Plan includes the design of an
interconnected grid street network must include
provisions slow traffic on neighborhood connector and
local streets. Traffic calming features include: narrow streets, traffic circles, median islands, bulb outs, and textured sidewalks,
Policy ED-N-1.1: Attract a
wide range of residential and
residentially compatible
investment types that support
neighborhood character.

Yes The Specific Plan is consistent with the range of
housing required by the General Plan with
approximately 652 low residential (17%), 1,542
medium residential (39%), and 656 high residential
(17%). This will provide wide range of opportunities to attract compatible investment types supportive of
neighborhood character.

Policy ED-N-2.1: Define and
promote the unique identity of
residential neighborhoods
through use of neighborhood
identity and design standards.

Yes The Specific Plan will foster the creation of distinct identifiable neighborhoods that have traditional
neighborhood development (TND) design
characteristics. Crime Prevention through
Environmental Design (CPTED) design principles as
expressed in the Salinas General Plan have been
incorporated into the Specific Plan to promote a safer
built environment. Design principles and standards
promoting Health in all Policies, Smart Growth, and
Green Building have also been included to ensure the
development of a healthy, compact, vital, and wellbalanced community.

Policy ED-N-2.2: Improve
neighborhood streetscapes to
enhance walkability and
support a safe and attractive
pedestrian environment
Yes The Specific Plan contains a network of pathways
comprised of widened sidewalks and parkways that
interconnect all the schools, parks, shopping, and
employment areas.
290
City of Salinas | Final Central Area Specific Plan, November 2020

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-26
Salinas General Plan Policy Consistent Discussion
through the Community
Design Element.

Policy ED-QL-1.2: Increase
safety and reduce crime by
regulating the design of the
residentially built environment
and implementing
recommendations put forth in
the CASP strategy. Ensure the
design of public spaces and
private developments are
conducive to eyes on the
street/natural surveillance
while enhancing the aesthetic
appeal and usability of a
space.

Yes The Specific Plan design includes public spaces such as schools and parks that are surrounded on most sides by
local streets. This improves the visibility into these
facilities, thus providing visual security. The pathways network is mostly along the local streets system also
providing “eyes-on-the-street.” Individual homes will
include first and second story front facing windows
that facilitate views to the street, also improving visual security. Detailed designs will be reviewed according
to CPTED principles.

Policy ED-QL-3.1: Create
new park space, connect
existing and future parks and
open space areas/corridors,
encourage public art
throughout the City, and
include this policy and action
items in the Community
Design Element.

Yes The Specific Plan includes designated park sites
totaling approximately 44.06 acres. At a standard of 3
acres per 1,000 population, the park requirement
would be 43.06 acres. The Specific Plan is providing
approximately one acre of parks beyond the standard
of 3 acres per 1,000 residents. The Specific Plan
identifies a range of park sizes configured differently than the three parks standards currently shown in the
General Plan. This is consistent with the New
Urbanism approach that places park facilities within
easy walking distance of residents.

Policy ED-QL-3.3: Strive to
create development patterns
such that the majority of
residents are within one-half
mile walking distance of a
park, greenway, public plaza
or recreation center (in more
urbanized areas of the City).

Yes The Specific Plan includes a “Walkability” figure that shows virtually all residents are within reasonable
walking distance of a park. See Figure 2-2.

Policy ED-QL-3.4: Better
integrate parks into
neighborhood fabric to blur
the boundary between
neighborhood, sidewalk, and
park perimeters to better
Yes The Specific Plan 44 parks that are integrated within the neighborhoods and provide a focal point for
community activities.

Appendices
291

CENTRAL AREA SPECIFIC PLAN GENERAL PLAN CONSISTENCY
B-27
Salinas General Plan Policy Consistent Discussion
integrate parks into
neighborhood fabric.
292
City of Salinas | Final Central Area Specific Plan, November 2020 Appendix D:

Mitigation Monitoring
and Reporting Program
Appendices
293













ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦͳ
This document is the Final Mitigation Monitoring and Reporting Program (FMMRP) for the Salinas Central Area Specific Plan Project (Project). This FMMRP has been prepared pursuant to Section 21081.6 of the California Public Resources Code, which requires public agencies to “adopt a reporting and monitoring program for the changes made to the project or conditions of project approval, adopted in order to mitigate or avoid significant effects on the environment.” A FMMRP is required for the proposed project because the EIR has identified significant adverse impacts, and measures have been identified to mitigate those impacts.

The numbering of the individual mitigation measures follows the numbering sequence as found in the Draft EIR, some of which were revised after the Draft EIR were prepared. These revisions are shown in Chapter 3.0 of the Final EIR. All revisions to mitigation measures that were necessary as a result of responding to public comments and incorporating staff-initiated revisions have been incorporated into this FMMRP. The FMMRP also includes mitigation measures which are required by the Final Environmental Impact Report, Salinas General Plan (Cotton Bridges Associates 2002) and the Final Supplement for the Salinas General Plan Final Program EIR (EDAW, 2007).

ͶǤͳ 










The FMMRP, as outlined in the following table, describes mitigation timing, monitoring responsibilities, and compliance verification responsibility for all mitigation measures identified in this Final EIR.

The City of Salinas will be the primary agency responsible for implementing the mitigation measures and will continue to monitor mitigation measures that are required to be implemented during the operation of the Project.

The FMMRP is presented in tabular form on the following pages. The components of the FMMRP are described briefly below:
• Mitigation Measures: The mitigation measures are taken from the Draft EIR in the same order that they appear in that document.
• Mitigation Timing: Identifies at which stage of the Project mitigation must be completed. • Monitoring Responsibility: Identifies the agency that is responsible for mitigation monitoring.
• Compliance Verification: This is a space that is available for the monitor to date and initial when the monitoring or mitigation implementation took place. 294
City of Salinas | Final Central Area Specific Plan, November 2020 ͶǤͲ











Ǧʹ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ
This page left intentionally blank.











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦ͵
TABLE 4.0-1: MITIGATION MONITORING AND REPORTING PROGRAM

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)




’ƒ
– ͵ǤͳǦʹǣ ”‘Œ‡
– ‘’‡”ƒ–‹‘
Šƒ• –Ї ’‘–‡–‹ƒŽ –‘
ƒ—•‡ ƒ
˜‹‘Žƒ–‹‘ ‘ˆ ƒ ƒ‹” “—ƒŽ‹–›
•–ƒ†ƒ”† ‘”
‘–”‹„—–‡
•—„•–ƒ–‹ƒŽŽ› –‘ ƒ ‡š‹•–‹‰ ‘”
’”‘Œ‡
–‡†ƒ‹”“—ƒŽ‹–›˜‹‘Žƒ–‹‘
Mitigation Measure 3.1-1: Prior to approval of tentative maps, conditional use permits or site plan review, the project applicant(s) shall incorporate the following features into project plans and specifications, as directed by the City of Salinas:
• Provide traffic calming measures (such as speed bumps, traffic circles, and/or other standard measures) on at least 50% of streets and intersections within the Plan Area;
• Require the parking lots or parking structures for new commercial, office, retail, and multifamily development to provide enough parking spaces for carpools and vanpools to accommodate reasonably foreseeable consumer demand at the time of the approval of such development, consistent with State of California laws and policies intended to encourage the use of carpools and vanpools;
• Require the use of low-VOC paint for all new building architectural coatings within the Plan Area, consistent with or better than, what is required by the City’s Municipal Code.

Mitigation Measure 3.1-2: Prior to approval of development review permit(s), the project applicant(s) shall incorporate effective methods to facilitate the use of cleaner alternative fuel (e.g., electric vehicles, carpooling, etc.) within the Plan Area. Effective methods may include the installation of alternative fuel (e.g. electric) charging stations at locations spaced throughout the Plan Area including but not limited to those specified in this Draft EIR, as applicable, consistent with or better than what is required by the City’s Municipal Code and Specific Plan. Additionally, this can be achieved by providing preferential parking for alternatively-powered vehicles, including electric cars, and/or by providing carpool/vanpool parking spaces.

Mitigation Measure 3.1-3: Prior to approval of development review permit(s), the project applicant(s) shall incorporate the use of alternative ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
”‹‘”–‘
ƒ’’”‘˜ƒŽ‘ˆ
–‡–ƒ–‹˜‡ƒ’•ǡ

‘†‹–‹‘ƒŽ—•‡
’‡”‹–•‘”•‹–‡
’Žƒ”‡˜‹‡™
”‹‘”–‘
ƒ’’”‘˜ƒŽ‘ˆ
†‡˜‡Ž‘’‡–
”‡˜‹‡™
’‡”‹–ȋ•Ȍ
”‹‘”–‘
Appendices
295
ͶǤͲ











ͶǤͲǦͶ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
energy for the residential and mixed use/commercial developments, including by implementing alternative energy (e.g. PV solar) building requirements, consistent with or better than, what is required by the City’s Municipal Code and State requirements (e.g. the 2019 California Solar Mandate). Project applicant(s) shall also ensure that pre-installed electrical hookups and/or charging stations, as applicable, are incorporated into all project plans and specifications.

Mitigation Measure 3.1-4: Prior to the issuance of building permits, the project applicant(s) shall provide plans that demonstrate that low-flow (high-efficiency) indoor water fixtures will be installed throughout the Plan Area, including for bathroom and kitchen faucets, toilet fixtures, and showers, in both residential and non-residential buildings, in compliance with or better than the standards required within the most recent version of the California Green Building Standards Code.

Mitigation Measure 3.1-5: Prior to the issuance of building permits, the project applicant(s) shall provide plans that demonstrate that water-efficient irrigation systems will be installed throughout the Plan Area, consistent with or better than the requirements contained within the State’s Model Water Efficient Landscape Ordinance, the City’s Water Conservation Ordinance and the Salinas Zoning Code Landscaping and Irrigation requirements.

Mitigation Measure 3.1-6: Prior to approval of improvement plans or development review permits, as applicable, the project applicant(s) shall ensure that pedestrian/bicycle facilities (e.g. pedestrian paths, outdoor bike racks, etc.) are provided within the Specific Plan Area, in coordination with and subject to approval by the City of Salinas. The project proponent shall also provide bicycling parking near the entrance to commercial establishments within the Specific Plan Area, consistent with or better than the requirements contained within the City’s Municipal Code.

Mitigation Measure 3.1-7: Prior to the issuance of development review permit(s), the project applicant(s) shall incorporate the following additional Plan Area requirements, as applicable:
• Install secured bicycle storage facilities (bike lockers, cages, interior ‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
ƒ’’”‘˜ƒŽ‘ˆ
†‡˜‡Ž‘’‡–
”‡˜‹‡™
’‡”‹–ȋ•Ȍ
”‹‘”–‘–Ї
‹••—ƒ
‡‘ˆ
„—‹Ž†‹‰
’‡”‹–•
”‹‘”–‘–Ї
‹••—ƒ
‡‘ˆ
„—‹Ž†‹‰
’‡”‹–•
”‹‘”–‘
ƒ’’”‘˜ƒŽ‘ˆ
‹’”‘˜‡‡–
’Žƒ•‘”
†‡˜‡Ž‘’‡–
”‡˜‹‡™’‡”‹–•ǡ
ƒ•ƒ’’Ž‹
ƒ„އ
”‹‘”–‘
ƒ’’”‘˜ƒŽ‘ˆ
†‡˜‡Ž‘’‡–
”‡˜‹‡™
296
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦͷ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
space, or similar as approved by the City Engineer) at all commercial and public facilities with 50 employees or more;
• Incorporate park-and-ride lots.
• Install Level 2 electric vehicle (EV) charge stations at workplace sites with 50 or more employees (10% or more of total available parking spaces, dependent on the existing and anticipated overall electric vehicle fleet mix in Monterey County at time of development); and • Install publicly-available dual post Level 2 charge stations within the VC or NG zones, and/or other zones as deemed acceptable by the City of Salinas. (Note: The 'level' of the charging station refers to the voltage that the electric vehicle charger uses. Level 1 charging is your typical traditional home outlet, while level 2 is a 240 Volt Portable Cordset or Wall-mounted Charging Station (2-10 hours charging).

Mitigation Measure 3.1-8: Prior to the approval of individual phases (i.e. tentative maps, site plan review, etc.), the project applicant(s) shall develop a reasonably feasible offsite mitigation program that provides funding to offset the project-generated air emissions that are still above the Air District’s operational criteria pollutant thresholds after the adoption of other applicable air quality mitigation measures. The offsite mitigation program is subject to the review and approval of the Air District and the City of Salinas on a project-by-project basis (of phase-by-phase), and is intended to be in addition to offsets that are obtained through any on-site mitigation measures. Example projects that could be included in the offsite mitigation program may include, but are not limited to, the following:
• Replace existing agricultural combustion-based generators/pumps with electric agricultural water pumps (in place of
generators/pumps;
• Replace combustion school buses with electric school buses within the local community;
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
’‡”‹–ȋ•Ȍ
”‹‘”–‘
ƒ’’”‘˜ƒŽ‘ˆ
‹†‹˜‹†—ƒŽ
’Šƒ•‡•ȋ‹Ǥ‡Ǥ
–‡–ƒ–‹˜‡ƒ’•ǡ
•‹–‡’Žƒ
”‡˜‹‡™ǡ‡–
ǤȌ
Appendices
297
ͶǤͲ











ͶǤͲǦ͸ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
• Install adaptive traffic control systems;
Install solar photovoltaic (PV) systems.

’ƒ
– ͵ǤͳǦ͵ǣ ”‘Œ‡
–

‘•–”—
–‹‘Šƒ• –Ї’‘–‡–‹ƒŽ –‘

ƒ—•‡ƒ˜‹‘Žƒ–‹‘‘ˆƒƒ‹”“—ƒŽ‹–›
•–ƒ†ƒ”† ‘”
‘–”‹„—–‡
•—„•–ƒ–‹ƒŽŽ› –‘ ƒ ‡š‹•–‹‰ ‘”
’”‘Œ‡
–‡†ƒ‹”“—ƒŽ‹–›˜‹‘Žƒ–‹‘
Mitigation Measure 3.1-9: Prior to the issuance of grading permits, the project applicant shall prepare a grading plan subject to review and approval by the City. In the event that ground-disturbance exceeds 2.2 acres per day for initial site preparation activities that involve extensive earthmoving activities (e.g., grubbing, excavation, rough grading), and 8.1 acres per day for activities that involve minimal earth-moving (e.g., finish grading), the required grading plans shall include the following measures to be implemented as needed to prevent visible dust emissions:
• Water all active construction sites to prevent visible dust emissions.

Frequency should be based on the type of operation, soil, and wind exposure;
• Prohibit grading and earthmoving activities, and cover stock piles, during periods of high wind (over 15 mph);
• Limit vehicle speed on construction sites to 15 mph.
• Apply chemical soil stabilizers on inactive construction areas (disturbed lands within construction projects that are unused for at least four consecutive days);
• Apply non-toxic binders (e.g., latex acrylic copolymer) to exposed areas after cut and fill operations and hydroseed area; • Maintain at least 1-foot of freeboard in each haul truck; • Provide windbreaks on the windward perimeter of construction projects where adjacent to open land;
• Cover inactive storage piles;
• Sweep streets if visible soil material is carried out from the construction site; and/or
• Post a publicly visible sign written in English and Spanish which specifies the telephone number and person to contact regarding dust complaints. This person shall respond to complaints and take corrective action within 48 hours. The phone number of the Monterey Bay Air Resources District (MBARD) shall be visible to ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
‘–‡”‡›ƒ›
‹”‡•‘—”
‡•
‹•–”‹
–
”‹‘”–‘–Ї
‹••—ƒ
‡‘ˆ
‰”ƒ†‹‰
’‡”‹–•
298
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦ͹

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
ensure compliance with Rule 402 (Nuisance). The sign shall be in accordance with MBARD and/or City requirements, as applicable • Use cleaner construction equipment that conforms to EPA’s second or first-most stringent Tier emission standards (e.g. Tier 3 or Tier 4 emission standards in 2019), or better; and/or
• Further, where reasonably feasible, construction equipment should include the use of alternative fuels such as compressed natural gas (CNG), propane, electricity or biodiesel.

’ƒ
– ͵ǤͳǦͷǣ Ї ’”‘’‘•‡†
’”‘Œ‡
– Šƒ• –Ї ’‘–‡–‹ƒŽ ˆ‘”
’—„Ž‹
 ‡š’‘•—”‡ –‘ –‘š‹
 ƒ‹”

‘–ƒ‹ƒ–•
Mitigation Measure 3.1-10: Prior to issuance of building permits or commencing operation of any commercial building/use that would emit toxic air contaminants (such as gas stations or dry cleaning operations), the project applicant shall, at a minimum, perform prioritization screening in accordance with the Air Toxics "Hot Spots" Program, Facility Prioritization Guidelines (July 1990) and the Air Toxics "Hot Spots" Information and Assessment Act. The prioritization screening shall be performed in accordance with the California Air Pollution Control Officers Association Air Toxic “Hot Spots” Program guidance. The prioritization screening shall also be conducted consistent with the guidance provided by the Monterey Bay Air Resources District, which will be responsible for determining which facilities based on their prioritization screening score, must perform a health risk assessment. In determining the need to prepare a health risk assessment, the Monterey Bay Air Resources District considers the potency, toxicity, quantity, and volume of hazardous materials released from the facility, the proximity of the facility to potential receptors, and any other factors specific to the facility that indicate that it may pose a significant health risk.

If a health risk assessment is warranted for a facility based on its prioritization score, the project applicant shall assess the facilities for the potential to expose the public to toxic air contaminants in excess of the applicable thresholds (utilizing an air dispersion modelling program such as AERMOD). As of the time of this writing, the commonly accepted threshold for cancer risk is 10 in a million for carcinogens, and the reference exposure level for non-carcinogens (HI = 1). Facilities that exceed the applicable threshold(s) have the potential to expose the public to toxic air contaminants ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
‘–‡”‡›ƒ›
‹”‡•‘—”
‡•
‹•–”‹
–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
„—‹Ž†‹‰
’‡”‹–•‘”

‘‡
‹‰
‘’‡”ƒ–‹‘‘ˆ
ƒ›
‘‡”
‹ƒŽ
„—‹Ž†‹‰Ȁ—•‡
–Šƒ–™‘—ކ‡‹–
–‘š‹
ƒ‹”

‘–ƒ‹ƒ–•
ȋ•—
Šƒ•‰ƒ•
•–ƒ–‹‘•‘”†”›

އƒ‹‰
‘’‡”ƒ–‹‘•Ȍ
Appendices
299
ͶǤͲ











ͶǤͲǦͺ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
levels that would be considered significant. Facilities that exceed the applicable threshold(s) must incorporate mitigation to reduce the risks from emission of toxic air contaminants to an acceptable level (i.e., to a level that does not exceed the applicable threshold[s]). Potential mitigation includes:
reducing the size of the facility area; rearranging the site to reduce the potential for impacts on the nearest sensitive receptors; and utilizing products that reduce the level of toxic air contaminants, or removal of such products from the operational phase of the project.

’ƒ
– ͵ǤͳǦ͹ǣ ——Žƒ–‹˜‡‹’ƒ
–
on the region’s air quality
Implement Mitigation Measures 3.1-1 through 3.1-10. ‡‡‹–‹‰ƒ–‹‘ ‡ƒ•—”‡•͵ǤͳǦͳ
–Š”‘—‰Š ͵ǤͳǦͺ
‡‡‹–‹‰ƒ–‹‘
‡ƒ•—”‡•͵ǤͳǦͳ
–Š”‘—‰Š͵ǤͳǦͺ





’ƒ
– ͵ǤʹǦʹǣ Ї ’”‘’‘•‡†
’”‘Œ‡
– Šƒ• –Ї ’‘–‡–‹ƒŽ –‘ǡ
†‹”‡
–Ž› ‘” ‹†‹”‡
–Ž›ǡ Šƒ˜‡ ƒ
•—„•–ƒ–‹ƒŽ ƒ†˜‡”•‡ ‡ˆˆ‡
–
–Š”‘—‰Š Šƒ„‹–ƒ–‘†‹ˆ‹
ƒ–‹‘• ‘”
”‡†—
–‹‘•ǡ
ƒ—•‡ ’‘’—Žƒ–‹‘• –‘
†”‘’„‡Ž‘™•‡ŽˆǦ•—•–ƒ‹‹‰އ˜‡Ž•ǡ
•—„•–ƒ–‹ƒŽŽ› ‡Ž‹‹ƒ–‡ ƒ

‘—‹–›ǡ ‘” •—„•–ƒ–‹ƒŽŽ›
”‡†—
‡–Ї—„‡”‘ˆǡ‘””‡•–”‹
–
–Ї”ƒ‰‡‘ˆǡƒ‡†ƒ‰‡”‡†ǡ”ƒ”‡
‘” –Š”‡ƒ–‡‡† •’‡
‹‡•ǡ ‹
Ž—†‹‰
–Š‘•‡
‘•‹†‡”‡†
ƒ†‹†ƒ–‡ǡ
•‡•‹–‹˜‡ǡ ‘” •’‡
‹ƒŽ •–ƒ–—• ‹
Ž‘
ƒŽ ‘” ”‡‰‹‘ƒŽ ’Žƒ•ǡ ’‘Ž‹
‹‡•ǡ
”‡‰—Žƒ–‹‘•ǡ ‘” „› –Ї   ‘”
 Ǧ ‡’–‹Ž‡ƒ†’Š‹„‹ƒ
Mitigation Measure 3.2-1: Prior to issuance of grading and/or building permits, the project applicant, assisted by a qualified biologist, shall consult with the USFWS and CDFW to obtain the appropriate regulatory approvals and authorizations regarding CTS. It is anticipated that the applicant would need to coordinate with the USFWS and CDFW on any additional survey needs, beyond the surveys, assessments, and genetic testing that has already been performed on this site for this species, during the consultation process.

The surveys, assessments, and genetic testing that has already been performed, in addition to any additional survey needs, will inform what, if any, take authorization is required from CDFW to comply with CESA.

Consultation with CDFW and the USFWS shall be conducted well in advance of beginning the surveys and prior to any planned vegetation- or grounddisturbing activities.

The regulatory approvals are anticipated to include the need to submit an application for incidental take to both the USFWS (Section 7 Consultation) and CDFW (2081 incidental take permit). The project applicant’s qualified biologist shall report the conclusions reached through such consultation to the City’s Community Development Director. If either USFWS or CDFW determines that an incidental take permit is required, the project applicant shall obtain such a permit before engaging in any grading or other site- ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
ƒŽ‹ˆ‘”‹ƒ
‡’ƒ”–‡–‘ˆ
‹•Šƒ†
‹Ž†Ž‹ˆ‡
ǤǤ ‹•Šƒ†
‹Ž†Ž‹ˆ‡‡”˜‹
‡
—ƒŽ‹ˆ‹‡†
‹‘Ž‘‰‹•–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‰”ƒ†‹‰ƒ†Ȁ‘”
„—‹Ž†‹‰
’‡”‹–•
300
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦͻ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
treatment activities in areas deemed to be viable CTS habitat.

It is anticipated that compensatory mitigation will be necessary for the loss of aquatic habitat associated with the 0.25-acre agricultural basin located on the east side of Natividad Road, approximately 0.4 miles north of East Boronda Road. At a minimum, the restoration and habitat creation of up to 30 acres along Gabilan Creek and 74 acres along Natividad Creek (net of any recreational amenities and public facilities required to facilitate the project) shall include ponded/basin areas that provide aquatic breeding habitat opportunities for CTS within the Specific Plan Area. The required amount of ponded/basin areas shall not be less than the 0.25 acres which is equivalent to the anticipated habitat loss, but the final calculation of aquatic habitat needed to compensate for that loss shall be determined by the USFWS and/or CDFW through the permit process. Additionally, the replacement aquatic habitat shall be designed with similar characteristics as the known 0.25-acre breeding pond including depths of at least five feet, and establishment of submergent and emergent vegetation around the perimeter of the pond/basin. All submergent and emergent vegetation around the pond/basin shall be from mature plantings to ensure that significant vegetation is established in the first year (i.e. no seeding or hydroseeding).

CTS migration and dispersal functions between breeding and aestivation sites shall be appropriately considered when designing and locating new aquatic breeding habitat within the creek corridors. The final restoration and habitat creation design shall be subject to the approval of the USFWS and CDFW.

Mitigation Measure 3.2-2: Prior to issuance of grading and/or building permits, in order to avoid and minimize impacts to California tiger salamander to the extent feasible, the proposed project activities shall be compliant with all Avoidance and Minimization Measures imposed by the USFWS and CDFW during Construction Activities. Examples of standard avoidance and minimization measures include: 1) conducting environmental education training for all construction personnel, 2) having a biologist with an incidental take permit (ITP) for CTS to be responsible for overseeing any hand excavation of burrows using hand-trowels and spades per the ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
ƒŽ‹ˆ‘”‹ƒ
‡’ƒ”–‡–‘ˆ
‹•Šƒ†
‹Ž†Ž‹ˆ‡
ǤǤ ‹•Šƒ†
‹Ž†Ž‹ˆ‡‡”˜‹
‡
—ƒŽ‹ˆ‹‡†
‹‘Ž‘‰‹•–
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‰”ƒ†‹‰ƒ†Ȁ‘”
„—‹Ž†‹‰
’‡”‹–•
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‰”ƒ†‹‰ƒ†Ȁ‘”
Appendices
301
ͶǤͲ











ͶǤͲǦͳͲ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
regulatory agency protocols, 3) erecting drift fencing around the work areas if occurring during the migration/breeding season, 4) inspection of drift fencing by biologist with an ITP every 72 hours during the migration/breeding season 5) installation of pit traps to capture CTS migrating during the rain events with a check twice daily (morning prior to construction start and evening after construction ends), 6) relocation of any CTS found immediately to a site designated by the USFWS and CDFW per protocol; and 7) post construction report. Any disturbance/decommissioning of the basin that is a known breeding site, shall be performed under the direction of the USFWS and/or CDFW. The decommissioning of this basin shall be performed during the non-breeding season.

In addition, the project applicant shall consult with the CDFW to determine if the Project can avoid take. If take cannot be avoided, take authorization would be required prior to initiating ground-disturbing activities to comply with CESA. Take authorization would occur through issuance of an ITP by CDFW pursuant to Fish and Game Code section 2081(b). In the absence of protocol surveys, the applicant can assume presence of CTS within the Plan Area and obtain an ITP from CDFW.

Mitigation Measure 3.2-3: Prior to issuance of grading and/or building permits, the project applicant, assisted by a qualified biologist, shall consult with the USFWS and CDFW to obtain the appropriate regulatory approvals and authorizations regarding CRLF. This is anticipated to include the need to submit an application for incidental take to both the USFWS (Section 7 Consultation) and CDFW (2081 incidental take permit). The project applicant’s qualified biologist shall report the conclusions reached through such consultation to the City’s Community Development Director. If either USFWS or CDFW determines that an incidental take permit is required, the project applicant shall obtain such a permit before engaging in any grading or other site-treatment activities in areas deemed to be viable CRLF habitat.

The Gabilan and Natividad Creek are CRLF habitat and both are anticipated to be expanded through habitat creation/restoration. The restoration and habitat creation include up to 30 acres along Gabilan Creek and 74 acres (net of any recreational amenities and public facilities required to facilitate the project) along Natividad Creek. Given that the creation/restoration is an ‡’ƒ”–‡–
ƒŽ‹ˆ‘”‹ƒ
‡’ƒ”–‡–‘ˆ
‹•Šƒ†
‹Ž†Ž‹ˆ‡
ǤǤ ‹•Šƒ†
‹Ž†Ž‹ˆ‡‡”˜‹
‡
—ƒŽ‹ˆ‹‡†
‹‘Ž‘‰‹•–
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
ƒŽ‹ˆ‘”‹ƒ
‡’ƒ”–‡–‘ˆ
‹•Šƒ†
‹Ž†Ž‹ˆ‡
ǤǤ ‹•Šƒ†
‹Ž†Ž‹ˆ‡‡”˜‹
‡
—ƒŽ‹ˆ‹‡†
‹‘Ž‘‰‹•–
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
„—‹Ž†‹‰
’‡”‹–•
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‰”ƒ†‹‰ƒ†Ȁ‘”
„—‹Ž†‹‰
’‡”‹–•
”‹‘”–‘
‹••—ƒ
‡‘ˆ
302
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦͳͳ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
expansion of habitat beyond what exists presently, it is anticipated that there would be a net increase in CRLF habitat. There is, however, the potential for temporary impacts to CRLF during the creation/restoration effort. The final restoration and habitat creation design shall be subject to the approval of the USFWS and CDFW.

Mitigation Measure 3.2-4: Prior to issuance of grading and/or building permits, in order to avoid and minimize impacts to CRLF to the extent feasible, the proposed project activities shall be compliant with all Avoidance and Minimization Measures imposed by the USFWS and CDFW during Construction Activities. Examples of standard avoidance and minimization measures include: 1) conducting environmental education training for all construction personnel, 2) having a biologist with a scientific collecting permit for CRLF to be responsible for overseeing any hand excavation of burrows using hand-trowels and spades per the regulatory agency protocols, 3) erecting drift fencing around the work areas if occurring during the migration/breeding season, 4) inspection of drift fencing by biologist with a scientific collecting permit every 72 hours during the migration/breeding season 5) installation of pit traps to capture CRLF migrating during the rain events with a check twice daily (morning prior to construction start and evening after construction ends), 6) relocation of any CRLF found immediately to a site designated by the USFWS and CDFW per protocol; and 7) post construction report.

Mitigation Measure 3.2-5: Prior to issuance of grading and/or building permits, in order to avoid and minimize impacts to WPT to the extent feasible, the proposed project activities shall be compliant with the following Avoidance and Minimization Measures: 1) conduct environmental education training for all construction personnel, 2) conduct western pond turtle surveys within creek corridors, ponded/basin areas, and irrigation ditches by a qualified biologist, 3) survey upland areas within 0.5 miles of the aquatic features for evidence of nests as well as individual turtles, 4) make a reasonable effort to capture and relocate as many western pond turtles as possible to minimize take, 5) if a nest is observed, move eggs to a suitable location or facility for incubation, and release hatchlings into the creek corridor the following autumn, 6) design habitat elements within the creek corridor to benefit western pond turtle (i.e. include logs or rafts for emergent basking sites, and upland areas adjacent to ponds in a relatively open condition), and 7) post construction report. All survey and/or handling of WPT shall be performed by a qualified biologist in consultation with the ‡˜‡Ž‘’‡–
‡’ƒ”–‡–
ƒŽ‹ˆ‘”‹ƒ
‡’ƒ”–‡–‘ˆ
‹•Šƒ†
‹Ž†Ž‹ˆ‡
ǤǤ ‹•Šƒ†
‹Ž†Ž‹ˆ‡‡”˜‹
‡
—ƒŽ‹ˆ‹‡†
‹‘Ž‘‰‹•–
‰”ƒ†‹‰ƒ†Ȁ‘”
„—‹Ž†‹‰
’‡”‹–•
Appendices
303
ͶǤͲ











ͶǤͲǦͳʹ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
CDFW.

’ƒ
– ͵ǤʹǦ͵ǣ Ї ’”‘’‘•‡†
’”‘Œ‡
– Šƒ• –Ї ’‘–‡–‹ƒŽ –‘ǡ
†‹”‡
–Ž› ‘” ‹†‹”‡
–Ž›ǡ Šƒ˜‡ ƒ
•—„•–ƒ–‹ƒŽ ƒ†˜‡”•‡ ‡ˆˆ‡
–
–Š”‘—‰Š Šƒ„‹–ƒ–‘†‹ˆ‹
ƒ–‹‘• ‘”
”‡†—
–‹‘•ǡ
ƒ—•‡ ’‘’—Žƒ–‹‘• –‘
†”‘’„‡Ž‘™•‡ŽˆǦ•—•–ƒ‹‹‰އ˜‡Ž•ǡ
•—„•–ƒ–‹ƒŽŽ› ‡Ž‹‹ƒ–‡ ƒ

‘—‹–›ǡ ‘” •—„•–ƒ–‹ƒŽŽ›
”‡†—
‡–Ї—„‡”‘ˆǡ‘””‡•–”‹
–
–Ї”ƒ‰‡‘ˆǡƒ‡†ƒ‰‡”‡†ǡ”ƒ”‡
‘” –Š”‡ƒ–‡‡† •’‡
‹‡•ǡ ‹
Ž—†‹‰
–Š‘•‡
‘•‹†‡”‡†
ƒ†‹†ƒ–‡ǡ
•‡•‹–‹˜‡ǡ ‘” •’‡
‹ƒŽ •–ƒ–—• ‹
Ž‘
ƒŽ ‘” ”‡‰‹‘ƒŽ ’Žƒ•ǡ ’‘Ž‹
‹‡•ǡ
”‡‰—Žƒ–‹‘•ǡ ‘” „› –Ї   ‘”
 Ǧ ‹”†•
Mitigation Measure 3.2-6: Building and grading permits and plans issued for development in the project area shall note the following: If construction activities occur during the avian breeding season (February 1 – September 15) then the project proponent shall conduct pre-construction surveys to prevent impacts to nesting birds. No more than 15 days prior to the start of construction a bird survey shall be conducted by a qualified biologist to identify any active nests within the Specific Plan Area, and shall be submitted to the City. If construction stops for a period of 15 days or more during the avian breeding season than an additional bird survey shall be conducted. The biologist will conduct a survey in the Specific Plan Area for all special-status birds protected by the federal and state ESA, MBTA and CFGC. The biologist shall map all nests that are within, and visible from, the Specific Plan Area. If nests are identified, the biologist shall map the location and establish a minimum 300-foot buffer zone around active nests. Construction activity shall be prohibited within the buffer zones until the young have fledged. Nests shall be monitored at least twice per week during the nesting season and a report submitted to the City and CDFW monthly.
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
—ƒŽ‹ˆ‹‡†
‹‘Ž‘‰‹•–
ƒŽ‹ˆ‘”‹ƒ
‡’ƒ”–‡–‘ˆ
‹•Šƒ†
‹Ž†Ž‹ˆ‡


‘Œ—
–‹‘
™‹–Š‹••—ƒ
‡
‘ˆ„—‹Ž†‹‰ƒ†
‰”ƒ†‹‰
’‡”‹–•ƒ†
’Žƒ•

’ƒ
– ͵ǤʹǦͷǣ Ї ’”‘’‘•‡†
’”‘Œ‡
– Šƒ• –Ї ’‘–‡–‹ƒŽ –‘ǡ
†‹”‡
–Ž› ‘” ‹†‹”‡
–Ž›ǡ Šƒ˜‡ ƒ
•—„•–ƒ–‹ƒŽ ƒ†˜‡”•‡ ‡ˆˆ‡
–
–Š”‘—‰Š Šƒ„‹–ƒ–‘†‹ˆ‹
ƒ–‹‘• ‘”
”‡†—
–‹‘•ǡ
ƒ—•‡ ’‘’—Žƒ–‹‘• –‘
†”‘’„‡Ž‘™•‡ŽˆǦ•—•–ƒ‹‹‰އ˜‡Ž•ǡ
•—„•–ƒ–‹ƒŽŽ› ‡Ž‹‹ƒ–‡ ƒ

‘—‹–›ǡ ‘” •—„•–ƒ–‹ƒŽŽ›
”‡†—
‡–Ї—„‡”‘ˆǡ‘””‡•–”‹
–
–Ї”ƒ‰‡‘ˆǡƒ‡†ƒ‰‡”‡†ǡ”ƒ”‡
‘” –Š”‡ƒ–‡‡† •’‡
‹‡•ǡ ‹
Ž—†‹‰
–Š‘•‡
‘•‹†‡”‡†
ƒ†‹†ƒ–‡ǡ
•‡•‹–‹˜‡ǡ ‘” •’‡
‹ƒŽ •–ƒ–—• ‹
Ž‘
ƒŽ ‘” ”‡‰‹‘ƒŽ ’Žƒ•ǡ ’‘Ž‹
‹‡•ǡ
”‡‰—Žƒ–‹‘•ǡ ‘” „› –Ї   ‘”
Mitigation Measure 3.2-7: Grading and/or building permits and plans issued for development in the project area shall note the following:
• Monterey Dusky-Footed Woodrat: Any vegetation/ground
disturbance to the Gabilan Creek associated with the crossings or restoration should be conducted when woodrats are least likely to breed in October through November. No more than 30 days prior to construction located within 50-feet of Gabilan Creek, a qualified biologist shall conduct a preconstruction survey for Monterey dusky-footed woodrat middens. At the discretion of a qualified biologist, an exclusion buffer shall be established around any woodrat middens that can be avoided, and these exclusion zones shall be fenced as Environmentally Sensitive Areas to protect the nest. If a woodrat midden cannot be avoided, potential dismantling and relocation strategies shall be developed and presented to the ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
—ƒŽ‹ˆ‹‡†
‹‘Ž‘‰‹•–


‘Œ—
–‹‘
™‹–Š‹••—ƒ
‡
‘ˆ„—‹Ž†‹‰
ƒ†Ȁ‘”‰”ƒ†‹‰
’‡”‹–•ƒ†
’Žƒ•
304
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦͳ͵

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
 Ǧ ƒƒŽ• City of Salinas Community Development Department by a qualified biologist for review and/or approval. Potential dismantling and relocation strategies may include hiring a qualified biologist to dismantle the middens by hand for relocation within the restored/created habitat along Gabilan and Natividad Creeks, or outside of the project site as appropriate. If approved by the City, a qualified wildlife biologist may dismantle only middens within the project site that would be disturbed by construction activities. If young are encountered during dismantling of the midden, any removed material may be replaced and a 50-foot no-disturbance buffer would be established around the active midden. The buffer would remain until young are weaned and are able to disperse on their own accord (typically for a period of 14 days). All removed midden substrate would be collected and relocated to suitable woodland habitat outside of the project footprint. Appropriate personal protective equipment (e.g., respirator, gloves, and Tyvek suit) shall be used while dismantling and relocating woodrat nest material to protect against disease carried by rodents (e.g. hantavirus).
• Bats: Fifteen days prior to construction activities within 200 feet of potential bat roosting habitat, the project applicant shall retain a qualified biologist familiar with bat biology to perform a preconstruction survey for roosting special-status bats, which shall be submitted to the City. The areas with potential bat roosting habitat include: 1) the three residential complexes located between Natividad Road and Gabilan Creek, 2) the outbuildings/structures located throughout the Specific Plan Area, and 3) Gabilan Creek.

The survey shall include a minimum of one daytime and one evening survey. The survey shall cover the trees, structures, and debris located within these complexes. If active roosting is observed, removal of the tree or building shall be avoided until the bats can be excluded. All active non-maternity roosting sites shall be fitted with passive exclusion devices, such as one-way flaps or doors, and all bats shall be allowed to leave voluntarily. Once it is confirmed that all bats have left the roost (minimum of five days), crews shall be allowed to continue work in the area. If a maternity roosting site is discovered, a minimum 50-foot buffer shall be established around Appendices
305
ͶǤͲ











ͶǤͲǦͳͶ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
the roost. The project applicant shall consult with the qualified biologist in order to determine if a greater buffer is warranted based on the bat species, roost location, and specific construction activities to be performed in the vicinity. The buffer shall stay in effect until all young are determined to be volant (i.e., able to fly and feed independently) by a qualified biologist. Once it is determined that all young are volant (generally by August 1st), passive exclusion devices shall be installed and all bats shall be allowed to leave voluntarily. Once it is determined by the qualified biologist that all bats have left the roost (minimum of five days), crews shall be allowed to work within the buffer zone. Project Improvement Plans will include this measure as a note in the plans.

’ƒ
– ͵ǤʹǦ͹ǣ Ї ’”‘’‘•‡†
’”‘Œ‡
– Šƒ• –Ї ’‘–‡–‹ƒŽ –‘ Šƒ˜‡
•—„•–ƒ–‹ƒŽ ƒ†˜‡”•‡ ‡ˆˆ‡
– ‘
ˆ‡†‡”ƒŽŽ› Ǧ ‘” •–ƒ–‡Ǧ ’”‘–‡
–‡†
™‡–Žƒ†• ȋ‹
Ž—†‹‰ǡ „—– ‘–
Ž‹‹–‡† –‘ǡ ƒ”•Šǡ ˜‡”ƒŽ ’‘‘Žǡ

‘ƒ•–ƒŽǡ ‡–
ǤȌ –Š”‘—‰Š †‹”‡
–
”‡‘˜ƒŽǡ ˆ‹ŽŽ‹‰ǡ Š›†”‘Ž‘‰‹
ƒŽ
‹–‡””—’–‹‘ǡ‘”‘–Ї”‡ƒ•
Mitigation Measure 3.2-8: Prior to grading/building permit issuance in an area that would disturb the Gabilan Creek, Natividad Creek (and its tributaries), the project applicant shall obtain jurisdictional determinations from the USACE, RWQCB, and CDFW for the creeks and ditches that are proposed to be disturbed. The creeks are confirmed jurisdictional and authorization for fill from the regulatory agencies (USACE-404 permit, RWQCB-Procedures for the Discharge of Dredged or Fill Material to Waters of the State and 401 certification, CDFW-1600 Streambed Alteration Agreement) will be necessary. The irrigation ditches are anticipated to be exempt. If these regulatory agencies concur that these irrigation ditches are exempt, then no further mitigation is necessary for the irrigation ditches. If it is determined that these ditches are not exempt, authorization for fill from the regulatory agencies (USACE-404 permit, RWQCB-Procedures for the Discharge of Dredged or Fill Material to Waters of the State and 401 certification, 1600 Streambed Alteration Agreement) will be necessary. At a minimum, the project applicant shall replace on a “no net loss” basis (minimum 1:1 ratio) the acreage and function of all wetlands and other waters that would be removed, lost, or degraded as a result of project implementation or operations, although a higher mitigation measure may be required by the USACE, RWQCB, and CDFW through their permitting processes. It is anticipated that the restoration of Gabilan and Natividad Creeks will result in up to 104 acres of wetland and riparian habitat creation (net of any recreational amenities and public facilities required to facilitate the project), which will serve as onsite mitigation; however, a mitigation plan must be submitted and approved by the USACE, RWQCB, and CDFW through the permitting processes conducted pursuant to Clean Water Act Sections 401 and 404, Fish and Game Code Section 1600, and State Water Board ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
ǤǤ”›
‘”’•‘ˆ
‰‹‡‡”•
‡‰‹‘ƒŽƒ–‡”
—ƒŽ‹–›‘–”‘Ž
‘ƒ”†
ƒŽ‹ˆ‘”‹ƒ
‡’ƒ”–‡–‘ˆ
‹•Šƒ†
‹Ž†Ž‹ˆ‡
”‹‘”–‘‰”ƒ†‹‰
Ȁ„—‹Ž†‹‰
’‡”‹–‹••—ƒ
‡
‹ƒƒ”‡ƒ–Šƒ–
™‘—ކ†‹•–—”„
–Ї
ƒ„‹Žƒ
”‡‡ǡ
ƒ–‹˜‹†ƒ†
”‡‡
306
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦͳͷ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
Procedures for the Discharge of Dredged or Fill Material to Waters of the State.



’ƒ
– ͵Ǥ͵Ǧͳǣ ”‘Œ‡
–
‹’އ‡–ƒ–‹‘ ƒ›
ƒ—•‡ ƒ
•—„•–ƒ–‹ƒŽƒ†˜‡”•‡
Šƒ‰‡‹–Ї
•‹‰‹ˆ‹
ƒ
‡ ‘ˆ ƒ Š‹•–‘”‹
ƒŽ
”‡•‘—”
‡ ƒ• †‡ˆ‹‡† ‹ 

—‹†‡Ž‹‡•ȚͳͷͲ͸ͶǤͷ
Mitigation Measure 3.3-1: Grading and/or building permits and plans for development in the project area shall note the following: In the event that evidence of archaeological or historical features or deposits (e.g., ceramic shard, trash scatters, lithic scatters) are uncovered (discovered) during excavation and/or grading, all work shall stop in the area of the find until an appropriate avoidance or data recovery program can be developed and implemented by a qualified archaeologist. This archaeologist shall determine whether the uncovered deposits or features qualify as either “historical resources” within the meaning of CEQA Guidelines section 15064.5, subdivision (a), “unique archaeological resources” as defined in Public Resources Code section 21083.2, subdivision (g), or “tribal cultural resources,” as defined in Public Resources Code section 21074. If historical resources, unique archaeological resources, or tribal cultural resources are present, the project proponent shall preserve any such resources in place if feasible as determined by the City Planner and/or implement any other feasible mitigation measures identified by the archaeologist and approve and imposed by the City. In assessing whether avoidance is feasible, the City Planner shall consider project design, logistics, and cost considerations. All costs associated with the City’s Planner’s determination of project design, logistics and cost considerations shall be borne by the developer/applicant.

Avoidance is infeasible where it would preclude the construction of important structures or infrastructure or require exorbitant expenditures.

Recommended mitigation measures shall be reviewed by the City Planner and shall be approved if feasible in light of project design, logistics, and cost considerations and, if approved, shall be implemented and completed prior to commencing further work for which grading or building permits were issued, unless otherwise directed by the City Planner. Data recovery, including photo documentation, excavation and recovery, laboratory analysis, etc., shall be an option if preservation in place is infeasible. Where resources have been determined to be “unique archaeological resources” but not “historical resources” or “tribal cultural resources,” the project proponent’s obligations shall be limited as set forth in Public Resources Code section 21083.2, subdivisions (d), (e), and (f). Grading/building permits and plans shall note this measure.
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
—ƒŽ‹ˆ‹‡†
”
Šƒ‡‘Ž‘‰‹•–

–Ї‡˜‡–
–Šƒ–‡˜‹†‡
‡‘ˆ
ƒ”
Šƒ‡‘Ž‘‰‹
ƒŽ
‘”Š‹•–‘”‹
ƒŽ
ˆ‡ƒ–—”‡•‘”
†‡’‘•‹–•ȋ‡Ǥ‰Ǥǡ

‡”ƒ‹
•Šƒ”†ǡ
–”ƒ•Š•
ƒ––‡”•ǡ
Ž‹–Š‹
•
ƒ––‡”•Ȍ
ƒ”‡—
‘˜‡”‡†
ȋ†‹•
‘˜‡”‡†Ȍ
†—”‹‰
‡š
ƒ˜ƒ–‹‘
ƒ†Ȁ‘”‰”ƒ†‹‰
Appendices
307
ͶǤͲ











ͶǤͲǦͳ͸ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)

’ƒ
– ͵Ǥ͵Ǧʹǣ ”‘Œ‡
–
‹’އ‡–ƒ–‹‘ ƒ›
ƒ—•‡ ƒ
•—„•–ƒ–‹ƒŽƒ†˜‡”•‡
Šƒ‰‡‹–Ї
•‹‰‹ˆ‹
ƒ
‡ ‘ˆ ƒ”
Šƒ‡‘Ž‘‰‹
ƒŽ
”‡•‘—”
‡ ’—”•—ƒ– –‘ 

—‹†‡Ž‹‡•ȚͳͷͲ͸ͶǤͷ
Implement Mitigation Measure 3.3-1. ‡‡‹–‹‰ƒ–‹‘
‡ƒ•—”‡͵Ǥ͵Ǧͳ
‡‡‹–‹‰ƒ–‹‘
‡ƒ•—”‡͵Ǥ͵Ǧͳ

’ƒ
– ͵Ǥ͵Ǧ͵ǣ ”‘Œ‡
–
‹’އ‡–ƒ–‹‘ ƒ› †‹”‡
–Ž› ‘”
‹†‹”‡
–Ž› †‡•–”‘› ƒ —‹“—‡
’ƒŽ‡‘–‘Ž‘‰‹
ƒŽ”‡•‘—”
‡
Mitigation Measure 3.3-2:
”ƒ†‹‰ƒ†Ȁ‘”„—‹Ž†‹‰’‡”‹–• ƒ†’Žƒ• ˆ‘”
†‡˜‡Ž‘’‡–‹–Ї ’”‘Œ‡
–ƒ”‡ƒ •ŠƒŽŽ‘–‡–Їˆ‘ŽŽ‘™‹‰ǣIf paleontological
resources are discovered during the course of construction, work shall be halted immediately within 50 meters (165 feet) of the discovery, the City of Salinas shall be notified, and a qualified paleontologist shall be retained to determine the significance of the discovery. If the paleontological resource is considered significant, it should be excavated by a qualified paleontologist and given to a local agency, State University, or other applicable institution, where the resource could be curated and displayed for public education purposes.
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
—ƒŽ‹ˆ‹‡†
ƒŽ‡‘–‘Ž‘‰‹•–

ˆ
’ƒŽ‡‘–‘Ž‘‰‹
ƒŽ
”‡•‘—”
‡•ƒ”‡
†‹•
‘˜‡”‡†
†—”‹‰–Ї

‘—”•‡‘ˆ

‘•–”—
–‹‘

’ƒ
– ͵Ǥ͵ǦͶǣ ”‘Œ‡
–
‹’އ‡–ƒ–‹‘ ƒ› †‹•–—”„
Š—ƒ ”‡ƒ‹•ǡ ‹
Ž—†‹‰ –Š‘•‡
‹–‡””‡† ‘—–•‹†‡ ‘ˆ ˆ‘”ƒŽ

‡‡–‡”‹‡•
Mitigation Measure 3.3-3: Grading and/or building permits and plans for development in the project area shall note the following: If human remains are found during construction within the Specific Plan Area, or at off-site infrastructure improvement locations, there shall be no further excavation or disturbance of the area of the find or any nearby area reasonably suspected to overlie adjacent human remains until a qualified archeological monitor and the coroner of Monterey County are contacted. If it is determined that the remains are Native American, the coroner shall contact the Native American Heritage Commission within 24 hours. The Native American Heritage Commission shall identify the person or persons it believes to be the most likely descendent (MLD) from the deceased Native American. The MLD may then make recommendations to the landowner or the person responsible for the excavation work, for means of treating or disposing of, with appropriate dignity, the human remains and associated grave goods as provided in Public Resources Code section 5097.98. The landowner or his authorized representative shall rebury the Native American human remains and associated grave goods with appropriate dignity on the property in a location not subject to further disturbance if:
a) the Native American Heritage Commission is unable to identify a ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
‘–‡”‡›
‘—–›‘”‘‡”
ƒ–‹˜‡
‡”‹
ƒ

‡”‹–ƒ‰‡
‘‹••‹‘

ˆŠ—ƒ
”‡ƒ‹•ƒ”‡
†‹•
‘˜‡”‡†
†—”‹‰–Ї

‘—”•‡‘ˆ

‘•–”—
–‹‘
™‹–Š‹–Ї
’‡
‹ˆ‹
Žƒ
”‡ƒ
308
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦͳ͹

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
MLD or the MLD failed to make a recommendation within 48 hours after being notified by the commission;
b) the descendent identified fails to make a recommendation; or c) the landowner or his authorized representative rejects the recommendation of the descendent, and the mediation by the Native American Heritage Commission fails to provide measures acceptable to the landowner.

’ƒ
– ͵Ǥ͵Ǧͷǣ ”‘Œ‡
–
‹’އ‡–ƒ–‹‘ ƒ›
ƒ—•‡ ƒ
•—„•–ƒ–‹ƒŽƒ†˜‡”•‡
Šƒ‰‡‹–Ї
•‹‰‹ˆ‹
ƒ
‡ ‘ˆ ƒ –”‹„ƒŽ
—Ž–—”ƒŽ
”‡•‘—”
‡
Implement mitigation measures 3.3-1 through 3.3-3. ‡‡‹–‹‰ƒ–‹‘ ‡ƒ•—”‡• ͵Ǥ͵Ǧ͵
ƒ†͵Ǥ͵ǦͶ
‡‡‹–‹‰ƒ–‹‘
‡ƒ•—”‡• ͵Ǥ͵Ǧ͵
ƒ†͵Ǥ͵ǦͶ








’ƒ
– ͵ǤͶǦͳǣ ‘–‡–‹ƒŽ –‘
‰‡‡”ƒ–‡ ‰”‡‡Š‘—•‡ ‰ƒ•
‡‹••‹‘•ǡ ‡‹–Ї” †‹”‡
–Ž› ‘”
‹†‹”‡
–Ž›ǡ –Šƒ– ƒ› Šƒ˜‡ ƒ
•‹‰‹ˆ‹
ƒ– ‹’ƒ
– ‘ –Ї
‡˜‹”‘‡–
Mitigation Measure 3.4-1: Prior to the approval of the tentative maps, conditional use permits or site plan review, as applicable, the project applicant shall prepare a Greenhouse Gas Reduction Plan (GGRP) aimed at achieving specific performance standards. The GGRP may be prepared pursuant to CEQA Guidelines section 15183.5(b) and shall include the following:
1) The GGRP shall, if feasible, achieve a per capita operational emissions level of 1.44 MT CO2e/service population/year by year 2040, and 0.80 MT CO2e/service population/year by year 2050. 2) Calculation of GHG emissions projection using an acceptable modeling tool such as the most recent version of CalEEMod.

GHG reduction measures may include building and site energy reduction measures, measures to reduce project-generated vehicle miles traveled, or other measures. Off-site measures such as participation in a community-wide GHG reduction program(s), if any are adopted, or payment of GHG reduction fees (carbon offsets) into a qualified existing program, may be considered after all feasible on-site reduction measures are considered. Any carbon offsets must be real, quantifiable, permanent, verifiable, enforceable, and additional, consistent with the standards set forth in Health and Safety Code section 38562, subdivisions (d)(1) and (d)(2). Such offsets shall be based on protocols ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ–Ї
–‡–ƒ–‹˜‡ƒ’•
ƒ†
†‡˜‡Ž‘’‡–
”‡˜‹‡™’‡”‹–•
Appendices
309
ͶǤͲ











ͶǤͲǦͳͺ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
consistent with the criteria set forth Section 95972, subdivision (a) of Title 17 of the California Code of Regulations, and shall not include offsets originating outside of California, except to the extent that the quality of the offsets, and their sufficiency under the standards set forth herein, can be verified by the City and/or the Monterey Bay Air Resources District (MBARD). Such credits must be purchased through one of the following: (i) a CARB-approved registry, such as the Climate Action Reserve, the American Carbon Registry, and the Verified Carbon Standard; (ii) any registry approved by CARB to act as a registry under the California Cap and Trade program; or (iii) through the CAPCOA GHG Rx and any program adopted the MBARD. The effectiveness of the GHG reduction measures included in the GGRP must be verifiable based on evidence presented in the GGRP. Representative GHG reduction measures which may be considered may include, but are not limited to:
• Measures identified by the California Air Pollution Control Officers’ Association in Quantifying Greenhouse Gas Mitigation Measures: A Resource for Local Government to Assess Emission Reductions from Greenhouse Gas Mitigation Measures or updates to this document as may occur from time to time.
• Applicable measures identified in guidance from MBARD, if any, and/or in guidance provided by the California Air Resources Board, other regional air districts such as the Bay Area Air Quality Management District, Sacramento Metropolitan Air Quality Management District, San Luis Obispo County Air Pollution Control District, or other agencies with adopted GHG reduction guidance that is applicable on the date the project application is deemed complete by the City.

If the project applicant concludes that sufficient feasible GHG reduction measures are unavailable to reduce GHG emissions to below the threshold of significance (i.e., per capita operational emissions level of 1.44 MT CO2e/service population/year by 2040, and 0.80 MT CO2e/service population/year by 2050), the project applicant shall include substantial evidence in the GGRP to this effect. The GGRP shall be subject to review and approval of the City of Salinas Community Development Department prior to 310
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦͳͻ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
approval of the tentative map or development review application, as applicable. Where the applicant concludes that the GGRP meets the threshold of significance, the Community Development Department shall determine whether, in its independent judgment, the GGRP actually does meet the threshold of significance, and shall ensure that all proposed measures will be effective and enforceable. In determining whether, as the applicant may assert, sufficient feasible GHG reduction measures are unavailable to reduce GHG emissions to below the threshold of significance, the Community Development Department shall determine, in its independent judgment, whether there might be additional feasible measures, including qualifying carbon offsets, available to meet the thresholds of significance. In making this determination, the Community Development Department shall consider the feasibility of imposing additional measures, including requiring the applicant to purchase any additional qualifying carbon offsets that might be available in the marketplace or through development of a local or regional program that could produce additional qualifying offsets. “Feasibility” in this context shall focus on the technical viability and overall cost of such additional measures, including carbon offsets, and, specifically, whether such measures (i) are technologically feasible, (ii) would substantially increase the cost of proposed housing, or (iii) would render the proposed project economically infeasible within the meaning of CEQA case law such as Uphold Our Heritage v. Town of Woodside (2007) 147 Cal.App.4th 587, 598-601. After the Community Development Department has approved a GGRP, the GGRP shall be forwarded to the City Planning Commission for its consideration and potential approval. The Planning Commission shall consider the GGRP at a noticed public hearing or meeting at which public testimony shall be considered. Any decision of the Planning Commission approving, conditioning, or denying a GGRP may be appealed to the City Council within 10 days of the Planning Commission decision. Upon appeal, the City Council shall consider the GGRP at a noticed public hearing or meeting at which public testimony shall be considered.

Implementation of this mitigation measure shall not be required if the City has a qualified GHG reduction plan in place on the date a future individual project application subject to the GHG reduction plan is deemed complete, the qualified GHG reduction plan reflects the most recent legislativelyadopted GHG reduction targets (e.g., the 2030 target set by SB 32), includes Appendices
311
ͶǤͲ











ͶǤͲǦʹͲ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
an inventory of projected GHG emissions from development within the Plan Area, and includes GHG reduction measures applicable to development within the Plan Area whose implementation is required as a condition of approval of such projects.

’ƒ
–͵ǤͶǦʹǣ‘–‡–‹ƒŽ–‘
‘ˆŽ‹
–
™‹–Š ƒ ƒ’’Ž‹
ƒ„އ ’Žƒǡ ’‘Ž‹
›ǡ
‘” ”‡‰—Žƒ–‹‘ ƒ†‘’–‡† ˆ‘” –Ї
’—”’‘•‡ ‘ˆ ”‡†—
‹‰ –Ї
‡‹••‹‘•‘ˆ‰”‡‡Š‘—•‡‰ƒ•‡•
Implement Mitigation Measure 3.4-1. ‡‡‹–‹‰ƒ–‹‘
‡ƒ•—”‡• ͵ǤͶǦͳ
‡‡‹–‹‰ƒ–‹‘
‡ƒ•—”‡• ͵ǤͶǦͳ

’ƒ
– ͵ǤͶǦͶǣ ——Žƒ–‹˜‡‹’ƒ
–
‘
Ž‹ƒ–‡
Šƒ‰‡ ˆ”‘
‹
”‡ƒ•‡† ’”‘Œ‡
–Ǧ”‡Žƒ–‡†
‰”‡‡Š‘—•‡‰ƒ•‡‹••‹‘
‡‡‹–‹‰ƒ–‹‘
‡ƒ•—”‡• ͵ǤͶǦͳ
‡‡‹–‹‰ƒ–‹‘
‡ƒ•—”‡• ͵ǤͶǦͳ







’ƒ
– ͵ǤͷǦͳǣ ‘–‡–‹ƒŽ –‘ „‡
Ž‘
ƒ–‡† ‘ ƒ •‹–‡ ™Š‹
Š ‹•
‹
Ž—†‡† ‘ ƒ Ž‹•– ‘ˆ Šƒœƒ”†‘—•
ƒ–‡”‹ƒŽ• •‹–‡•
‘’‹Ž‡†
’—”•—ƒ– –‘
‘˜‡”‡– ‘†‡
‡
–‹‘ ͸ͷͻ͸ʹǤͷƒ†ǡƒ•ƒ ”‡•—Ž–ǡ
™‘—ކ ‹–
”‡ƒ–‡ ƒ •‹‰‹ˆ‹
ƒ–
Šƒœƒ”† –‘ –Ї ’—„Ž‹
 ‘” –Ї
‡˜‹”‘‡–
Mitigation Measure 3.5-1: Prior to issuance of grading permits or building permits, (including the issuance of demolition permits for agricultural support buildings) as applicable, the applicant shall hire a qualified consultant to:
1) Provide a final evaluation of the soils around the agricultural operations support buildings (residences, warehouses, barns, etc.) before they are demolished. If toxic levels of residual agrichemicals or surface staining are found, the contaminated soil shall be excavated and disposed of at an off-site disposal facility permitted to accept such waste. Any contaminated areas shall be remediated by the project applicant in accordance with recommendations made by the Monterey County Health Department Hazardous Materials Management Services, Regional Water Quality Control Board, Department of Toxic Substances Control, or other appropriate federal, State, or local regulatory agencies.
2) Investigate structures for asbestos-containing materials and lead. If asbestos-containing materials and/or lead are found in the buildings, or around the perimeters of the foundations if structures have ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‰”ƒ†‹‰
’‡”‹–•‘”
„—‹Ž†‹‰
’‡”‹–•ǡ
ȋ‹
Ž—†‹‰–Ї
‹••—ƒ
‡‘ˆ
†‡‘Ž‹–‹‘
’‡”‹–•ˆ‘”
ƒ‰”‹
—Ž–—”ƒŽ
•—’’‘”–
„—‹Ž†‹‰•Ȍƒ•
ƒ’’Ž‹
ƒ„އ
312
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦʹͳ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
already been removed, a Cal-OSHA certified ACBM and lead based paint contractor shall be retained to remove the asbestos-containing materials and lead in accordance with U.S. EPA and California Occupational Safety and Health Administration (Cal/OSHA) standards. In addition, all activities (construction or demolition) in the vicinity of these materials shall comply with Cal/OSHA asbestos and lead worker construction standards. Any ACBM and lead shall be disposed of properly at an appropriate offsite disposal facility.

In addition, any construction activity that involves the disturbance or removal of building materials or structures must be thoroughly inspected for asbestos by a California Certified Asbestos Consultant (CAC) prior to the construction activity, as regulated by the Federal EPA Asbestos NESHAP (National Emission Standards of Hazardous Air Pollutants) and Air District Rule 424. Work to remove any regulated quantities of asbestos must be notified to the Air District at least 10 working days prior to the beginning of work.

Any load-bearing removal in the structures is defined as a demolition activity by the Federal EPA Asbestos NESHAP regulation and District Rule 424. This activity must also be notified to the Air District at least 10 working days prior to the beginning of work.
3) The two known gasoline USTs located on APNs 211-013-003 or -010 and -011 and APN 153-091-001 shall require proper removal in accordance with Monterey County permit requirements prior to planned development. Any unused fuel and oil ASTs and containers located in the vicinity of the agricultural buildings and equipment yards shall be properly removed and recycled or disposed of. Any associated petroleum hydrocarbon subsurface impacts associated with the USTs, ASTs and fuel and oil containers/storage areas shall require proper removal in accordance with all applicable regulatory requirements and recommendations by the Monterey County Health Department Hazardous Materials Management Services, Regional Water Quality Control Board, Department of Toxic Substances Appendices
313
ͶǤͲ











ͶǤͲǦʹʹ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
Control, or other appropriate federal, State, or local regulatory agencies.
4) Investigation and reporting for Polychlorinated biphenyls (PCBs) related soil impacts (associated with pole-mounted transformers) at the fenced former substation located on the southern portion of APN 211-013-012 shall be required prior to disturbance of the area. Soil sampling and analytical testing shall be required to determine if subsurface impacts require further assessment or remediation prior to planned development. If the investigation and analytical results of the soil samples determines the soils contain threshold levels of PCBs, materials must be disposed of as a hazardous waste and shall require proper removal in accordance with all applicable regulatory requirements and recommendations by the Monterey County Health Department Hazardous Materials Management Services, Regional Water Quality Control Board, Department of Toxic Substances Control, or other appropriate federal, State, or local regulatory agencies.
5) Observations and a screening level Phase II ESA soil sampling and analytical testing shall be completed for APNs 211-013-003, -007, - 010 and -011 prior to any development approvals. Any
contaminated areas shall be remediated by the project applicant in accordance with recommendations made by the Monterey County Health Department Hazardous Materials Management Services, Regional Water Quality Control Board, Department of Toxic Substances Control, or other appropriate federal, State, or local regulatory agencies.

Mitigation Measure 3.5-2: Prior to the issuance of grading permits, existing water wells within the grading area shall be destroyed under permit from the City of Salinas and/or the Monterey County Health Department, as applicable. Any destruction of these facilities shall be in accordance with the Monterey County Well Standards for Abandonment/Destruction. The project applicant shall provide the City of Salinas with a copy of the permit and a report or other information documenting the appropriate destruction of ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
‘–‡”‡›
‘—–›
‡ƒŽ–Š
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
‘–‡”‡›
‘—–›
‡ƒŽ–Š
‡’ƒ”–‡–
”‹‘”–‘–Ї
‹••—ƒ
‡‘ˆ
‰”ƒ†‹‰
’‡”‹–•
”‹‘”–‘–Ї
‹••—ƒ
‡‘ˆ
„—‹Ž†‹‰
’‡”‹–•
314
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦʹ͵

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
these facilities.

Mitigation Measure 3.5-3: Prior to the issuance of building permits, the water well or wells that will be providing water for the applicable portion of the Specific Plan Area, shall be constructed and tested for water quality under permit from the Monterey County Health Department. The project applicant shall provide the City of Salinas with a copy of the permit and a report or other information documenting the appropriate construction and operation of these facilities.

’ƒ
–͵ǤͷǦʹǣ”‡ƒ–‡ƒ•‹‰‹ˆ‹
ƒ–
Šƒœƒ”† –‘ •
Š‘‘Ž •‹–‡• †—‡ –‘
•‹–‹‰ ‘” –Ї ’Žƒ
‡‡– ‘ˆ
‹ˆ”ƒ•–”—
–—”‡
Mitigation Measure 3.5-4: The property line of all school sites (even if it is a joint use agreement as described in subsection (o) of § 14010) shall be at least the following distance from the edge of respective power line easements as identified in the California Code of Regulations Title 5, Article 2. School Sites § 14010, Standards for School Site Selection (c):
• 100 feet for power lines that are between 50 and 133 kV. ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
”‹‘”–‘
ƒ’’”‘˜ƒŽ ‘ˆ
‹’”‘˜‡‡–
’Žƒ•ˆ‘”ƒ›
•
Š‘‘Ž•‹–‡






’ƒ
– ͵Ǥ͸Ǧͳǣ Ї ’”‘’‘•‡†
’”‘Œ‡
– Šƒ• –Ї ’‘–‡–‹ƒŽ –‘
˜‹‘Žƒ–‡ ™ƒ–‡” “—ƒŽ‹–› •–ƒ†ƒ”†•
‘”™ƒ•–‡†‹•
Šƒ”‰‡”‡“—‹”‡‡–•
†—”‹‰
‘•–”—
–‹‘
Mitigation Measure 3.6-1: Prior to issuance of grading permits, the project proponent shall submit a Notice of Intent (NOI) and Storm Water Pollution Prevention Plan (SWPPP) to the City of Salinas prior to submitting to the RWQCB to obtain coverage under the General Permit for Discharges of Storm Water Associated with Construction Activity (Construction General Permit Order 2009-0009-DWQ amended by 2010-0014-DWQ & 2012-0006-DWQ).

The SWPPP shall be designed with Best Management Practices (BMPs) that the RWQCB has deemed to be effective at reducing erosion, controlling sediment, and managing runoff. These include: covering disturbed areas with mulch, temporary seeding, soil stabilizers, binders, fiber rolls or blankets, temporary vegetation, and permanent seeding. Sediment control BMPs, installing silt fences or placing straw wattles below slopes, installing berms and other temporary run-on and runoff diversions. These BMPs are only examples of what should be considered and shall not preclude the use of equally or more effective new or innovative approaches currently available or being developed. Final selection of BMPs will be subject to approval by City of Salinas. The SWPPP will be kept on site during construction activity and will be made available upon request to representatives of the RWQCB or the ‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‡‰‹‘ƒŽƒ–‡”
—ƒŽ‹–›‘–”‘Ž
‘ƒ”†
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‰”ƒ†‹‰
’‡”‹–•
Appendices
315
ͶǤͲ











ͶǤͲǦʹͶ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
City of Salinas.

’ƒ
– ͵Ǥ͸Ǧʹǣ Ї ’”‘’‘•‡†
’”‘Œ‡
– Šƒ• –Ї ’‘–‡–‹ƒŽ –‘
˜‹‘Žƒ–‡ ™ƒ–‡” “—ƒŽ‹–› •–ƒ†ƒ”†•
‘”™ƒ•–‡†‹•
Šƒ”‰‡”‡“—‹”‡‡–•
†—”‹‰‘’‡”ƒ–‹‘
Mitigation Measure 3.6-2: Prior to the issuance of grading permits, the project proponent shall submit to the Salinas Public Works Department the project Improvement Plans. The Improvement Plans shall be consistent with the City’s Development Standards, Standard Plans, and current NPDES permit requirements at the time of permitting. The NPDES permit granted to the City of Salinas by the Central Coast RWQCB (RWQCB – Central Coast Region, 2019) requires the following:

I. Erosion and Sediment Control BMPs – Erosion control and sediment control BMPs shall be designed, installed, and maintained to reduce the discharge of pollutants from construction sites to the maximum extent practical (MEP) and protect water quality;
II. Erosion and sediment from slopes and channels shall be controlled by implementing an effective combination of erosion control (source control) and other sediment control BMPs; and
III. Soil Stabilization – Stabilization of disturbed areas shall, at a minimum, be initiated immediately whenever any clearing, grading, excavating, or other earth disturbing activities have permanently ceased.

Additionally, the Improvement Plans shall be consistent with the requirements of the City’s most current Stormwater Development Standards for New and Redevelopment Projects. The City of Salinas Stormwater Standards for New and Redevelopment Projects (City of Salinas, 2013) require the following practices:

I. Limit disturbance of creeks and natural drainage features and provide setbacks according to the City’s latest NPDES permit; II. Minimize compaction of highly permeable soils; and
III. Limit clearing and grading of native vegetation to the minimum needed to build the project and provide fire
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
”‹‘”–‘–Ї
‹••—ƒ
‡‘ˆ
‰”ƒ†‹‰
’‡”‹–•
316
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦʹͷ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
protection.

Mitigation Measure 3.6-3: Prior to the approval of site improvement plans, the project applicant shall submit to the Salinas Public Works Department a Stormwater Control Plan detailing plans and calculations for water quality best management practices (BMPs) and water quality detention/retention basins designed to meet the applicable regulatory requirements and to reduce contaminant loadings to receiving waters to the maximum extent practicable.

The approved Stormwater Control Plans shall be submitted to the Central Coast RWQCB through SMARTS as part of the project’s SWPPP permit documents.

Mitigation Measure 3.6-4: Prior to the approval of site improvement plans, the project applicant shall submit to the Salinas Public Works Department a Stormwater Control Plan detailing plans and calculations for operational water quality best management practices (BMPs) and water quality detention basins designed to prevent to the maximum extent practicable the creation of new sources of polluted runoff. Operational water quality BMPs may include extended detention basins, wet ponds/detention basins, porous pavement, inlet filters, vegetative BMPs, underground infiltration systems, vegetative swales, or storm drain stenciling and posting of signage. The detailed plans and calculations shall be subject to review and approval by the Salinas Public Works Department.

Mitigation Measure 3.6-5: Prior to the approval of site improvement plans, the project applicant shall submit a Hydrologic study as part of the Stormwater Control Plan to the Salinas Public Works Department detailed plans and calculations for supplemental retention and peak flow control.

BMPs will be designed to meet regulatory requirements and to reduce peak flows during storm events below peak flows under pre-project conditions. The detailed plans and calculations shall be subject to review and approval by the Salinas Public Works Department.
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
’Žƒ•
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
’Žƒ•
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
’Žƒ•
Appendices
317
ͶǤͲ











ͶǤͲǦʹ͸ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)

’ƒ
– ͵Ǥ͸Ǧ͵ǣ Ї ’”‘’‘•‡†
’”‘Œ‡
– Šƒ• –Ї ’‘–‡–‹ƒŽ –‘
•—„•–ƒ–‹ƒŽŽ› †‡’އ–‡
‰”‘—†™ƒ–‡” •—’’Ž‹‡• ‘”
‹–‡”ˆ‡”‡ •—„•–ƒ–‹ƒŽŽ› ™‹–Š
‰”‘—†™ƒ–‡””‡
Šƒ”‰‡
Mitigation Measure 3.6-6: Prior to the approval of site improvement plans, the project applicant shall site, and design and include an Operation and Maintenance Plan for stormwater retention/infiltration basins and infiltration promoting BMPs sufficient to assure that there is no reduction in groundwater recharge. In order to assure there is no reduction in recharge, the plan shall result in circumstances which maintain infiltration to support baseflow and interflow to wetlands and surface waters, and deep vertical infiltration to groundwater. The site, design, and installation shall be consistent with the requirements of the City’s Stormwater Development Standards for New and Redevelopment Projects. The contents of the site, landscaping (ground cover, bushes and trees, etc.) and irrigation (as applicable), design, and installation shall be included in a Stormwater Control Plan. The Stormwater Control Plan shall be reflected on the Improvement Plans and subject to review and approval by the Salinas Public Works Department and the City Planner. All basins shall be designed to have a natural appearance through the use of varied bank slopes (through grading) and appropriate landscaping (ground cover, bushes, trees, etc.) and irrigation (as applicable). A landscaping plan, irrigation plan and maintenance plan (all prepared by a qualified professional) shall be submitted for the review and approval of the Public Works Department and the City Planner.

Mitigation Measure 3.6-7: Prior to the approval of site improvement plans, the project applicant shall site, design, and include an Operation and Maintenance Plan for post-construction BMPs and supplemental stormwater detention basins in accordance with City of Salinas stormwater development standards. Maintenance procedures (including frequency of procedure, cleaning schedules, applicant responsibility for each procedure, performance standards, or other means) and funding mechanisms shall be established for those facilities to assure adequate long-term performance and success in treating the water and controlling infiltration into the groundwater. The Improvement Plans and Operation and Maintenance Plan shall be subject to review and approval by the Salinas Public Works Department. ‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
’Žƒ•
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
’Žƒ•

’ƒ
– ͵Ǥ͸Ǧ͸ǣ Žƒ
‡ Š‘—•‹‰ ‘”
•–”—
–—”‡• –Šƒ– ™‘—ކ
‹’‡†‡Ȁ”‡†‹”‡
– ˆŽ‘™• ™‹–Š‹ ƒ
ͳͲͲǦ›‡ƒ”ǡ ‘” ʹͲͲǦ›‡ƒ” ˆŽ‘‘†
Mitigation Measure 3.6-8: Prior to the approval of site improvement plans, the project applicant shall submit an application for a letter of map revision based on fill (LOMR-F) to the City of Salinas floodplain administrator and FEMA with pertinent information and studies for approval that indicates no ‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
318
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦʹ͹

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
Šƒœƒ”† ƒ”‡ƒ ƒ• ƒ’’‡† ‘ ƒ
ˆ‡†‡”ƒŽ Ž‘‘†
ƒœƒ”† ‘—†ƒ”›
‘” Ž‘‘†
•—”ƒ
‡ ƒ–‡ ƒ’ ‘”
‘–Ї” ˆŽ‘‘† Šƒœƒ”† †‡Ž‹‡ƒ–‹‘
ƒ’
building construction would take place within remapped FEMA flood zones AE and A and that no changes to the regulated floodway will result in an increase in the base flood elevation or impact the downstream waterways.

Mitigation Measure 3.6-9: Prior to the approval of site improvement plans, the project applicant shall submit for review and approval by the Salinas Public Works Department detailed grading plans and calculations designed to place enough fill onto the shaded Zone X area as to raise the land surface elevation above the base flood elevation so that flooding hazards are minimized to a FEMA flood standard. The project applicant shall submit an application for a LOMR-F to the City of Salinas floodplain administrator and FEMA with pertinent information for approval.

Mitigation Measure 3.6-10: Prior to the approval of site improvement plans, the project applicant shall submit for review and approval by the Salinas Public Works Department and the City Planner, detailed plans, calculations, landscaping (and irrigation, as applicable) plans, and design basis reports for creek corridor restoration, including detention/retention/water quality basins, within the flood hazard extents identified as Zones A and AE that provide assurances that during large storm events, creek flows and sediment transport from upstream sources are not impeded at the same time as when the adjacent basins are at or near capacity. The design basis reports for creek corridor restoration shall also be submitted to the USACE, USFWS, and RWQCB and any required permitting processed prior to City approval. All basins shall be designed to have a natural appearance through the use of varied bank slopes (through grading) and appropriate landscaping (ground cover, bushes, trees, etc.) and irrigation (as applicable). A landscaping plan, irrigation plan and maintenance plan (all prepared by a qualified professional) shall be submitted for review and approval of the Public Works Department and the City Planner.

Mitigation Measure 3.6-11: Prior to the approval of site improvement plans, the project applicant shall submit a Stormwater Control Plan that provides sufficient supporting documentation and calculations to the Salinas Public Works Department to address sediment transport issues of finegrained materials from upstream and local sources that could clog ‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
’Žƒ•
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
’Žƒ•
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
’Žƒ•
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
Appendices
319
ͶǤͲ











ͶǤͲǦʹͺ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
infiltration capacities and could fill required storage space within the stormwater basins at the downstream boundaries of the project area to the extent practicable.

The calculations to address these sediment transport issues may include:
• A streamflow and sediment transport (bedload and suspended sediment) data collection monitoring program that begins one- to two-years pre-construction and continues through a mandated postproject timeframe and would provide volumetric information for calculations related to the potential for sediment deposition. • Pre-project measurements could be used to estimate sediment loading, which could inform the design of mitigation measures and enable estimates of maintenance frequencies needed ensure ongoing efficacy of the measures. During project execution and after project completion, measurements of bedload and suspended sediment in the channel at the downstream boundary of the project could be used to verify performance of sediment management measures and avoidance of associated sediment transport impacts.
• The United States Geological Survey gage record on Gabilan Creek (#11152600) contains limited suspended sediment data that was collected in March and April of 2017. These data could be used to compare to and/or validate measurements obtained via field data collection.

Strategies and measures to address these sediment transport issues may include:
• Bioretention Basins: Bioretention basin features provide multiple water quality functions for stormwater systems, including performing as depositional areas for sediments that settle and get trapped in the bioretention media.

An operations and maintenance plan shall be used to address specific ’Žƒ•
320
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦʹͻ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
maintenance requirements related to sediment accumulation, such that basin media remediation would take place when a threshold condition (such as a certain amount of sediment accumulation on the basin floor) is reached. For instance, if sediment deposition exceeds a depth of 2-inches, even a small patch, the sediment would require removal to keep the basin functioning properly.

Furthermore, the functional lifespan of bioretention media (mulch, soils, drain rock, underdrain) is generally about 15 years. Annual monitoring reports could be used to track basin performance under varying wet season conditions and used to guide media replacement timing.
• Treatment Wetlands: Treatment wetlands are designed to mimic the natural infiltration, nutrient cycling, habitat, and a myriad of other important ecological functions provided by natural wetlands.

Treatment wetlands could be constructed at storm drain outfall locations or adjacent to or off-channel from a creek channel.

Wetlands could vary between those that are highly designed and may need relatively high levels of maintenance to more naturally based designs that may need more limited maintenance, each with varying levels of treatment potential.

Treatment performance is a function of wetland to watershed ratio, wetland treatment design, area hydrology, hydraulic residence time, and source pollutants. The preferred residence time through wetlands varies based on vegetation type and quantity, water depth, temperature, and design flow rates. Having a lower design flow rate can result in longer hydraulic residence time, which is preferred particularly at the start of a rainy season, since the “first flush” volume of stormwater runoff will generally contain the highest concentrations of pollutants. Treatment wetland design generally considers dry season irrigation return flows and first flush principles. • Vegetated Banks/Riparian Corridor: Trees and other riparian corridor vegetation appropriate to the environment, such as willows, could Appendices
321
ͶǤͲ











ͶǤͲǦ͵Ͳ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
grow rapidly on channel banks and trap sediments, removing sediment from streamflows as well as from local surface runoff. • Floodplains: Floodplains provide one of the most important storage spaces for sediment as it moves discontinuously through a watershed. Naturally functioning floodplains generally extend laterally past the immediate riparian buffer zone into relatively flat areas. Floodplain access could be provided by bank and channel grading at specified design storm flows. The rate of sediment deposition on floodplains is largely dependent on the frequency of inundating flows, the suspended sediment loads in the river, available floodplain area, and presence of vegetation.

Mitigation Measure 3.6-12: Prior to the approval of site improvement plans, the project applicant shall provide an Operation and Maintenance Plan as part of the Stormwater Control Plan with sufficient supporting documentation and calculations for review and approval by the Salinas Public Works Department demonstrating that risks associated with reduction of infiltration capacity in the detention/retention/water quality basins shall be minimized to the maximum extent practicable.

Mitigation Measure 3.6-13: Prior to the approval of site improvement plans, the project applicant shall provide the Salinas Public Works Department with sufficient supporting documentation and calculations that the risks associated with basin embankment side slope failure because of the non-cohesive nature of Gabilan and Natividad Creek corridor sediments will be minimized to the extent practicable.

Mitigation Measure 3.6-14: Prior to the approval of site improvement plans, the project applicant shall provide operations, maintenance, and SWPPP procedures for review and approval by the Salinas Public Works Department such that any detention/retention/water quality basin issues associated with sedimentation or loss of infiltration capacities are addressed by the operations, maintenance, and SWPPP procedures. Should the Salinas Public Works Department find that sedimentation or loss of infiltration capacities are addressed and subsequently approve the operations, ‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
’Žƒ•
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
’Žƒ•
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
’Žƒ•
322
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦ͵ͳ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
maintenance, and SWPPP procedures, the applicant shall implement the procedures through the lifetime of the project.

Mitigation Measure 3.6-15: Prior to the approval of site improvement plans, the project applicant shall provide the Salinas Public Works Department with operations, maintenance, and SWPPP procedures such that any detention/retention/water quality basin issues associated with embankment side slope failures are addressed by the operations, maintenance, and SWPPP procedures. Should the Salinas Public Works Department find that any detention/retention/water quality basin issues associated with embankment side slope failures are addressed and subsequently approve the operations, maintenance, and SWPPP procedures, the applicant shall implement the procedures through the lifetime of the project.

All basins shall be designed to have a natural appearance through the use of varied bank slopes (through grading) and appropriate landscaping (ground cover, bushes, trees, etc.) and irrigation (as applicable). A landscaping plan, irrigation plan and maintenance plan (all prepared by a qualified professional) shall be submitted for review and approval of the Public Works Department and the City Planner.
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
’Žƒ•
Appendices
323
ͶǤͲ











ͶǤͲǦ͵ʹ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)



’ƒ
– ͵Ǥ͹Ǧʹǣ Ї ’”‘’‘•‡†
’”‘Œ‡
– Šƒ• –Ї ’‘–‡–‹ƒŽ –‘
‹
”‡ƒ•‡ ‘‹•‡ އ˜‡Ž• ƒ••‘
‹ƒ–‡†
™‹–Š
‘•–”—
–‹‘ƒ
–‹˜‹–‹‡•
Mitigation Measure 3.7-1: Prior to the approval of site improvement plans and respective permits, plans shall note that construction activities shall adhere to the requirements of the City of Salinas Municipal Code with respect to hours of operation.

Mitigation Measure 3.7-2: Prior to the approval of site improvement plans and respective permits, plans shall note that all equipment shall be fitted with factory equipped mufflers and in good working order. All stationary noise generating equipment (i.e. generators) shall be located at least 200 feet from a sensitive receptor. All construction staging areas shall be located at least 200 feet from a sensitive receptor.
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
’Žƒ•
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
’Žƒ•

’ƒ
– ͵Ǥ͹ǦͶǣ Ї ’”‘’‘•‡†
’”‘Œ‡
– Šƒ• –Ї ’‘–‡–‹ƒŽ –‘
‡š’‘•‡ ‡™ •‡•‹–‹˜‡ ”‡
‡’–‘”•
–‘‡š
‡••‹˜‡–”ƒ•’‘”–ƒ–‹‘‘‹•‡
Mitigation Measure 3.7-3: Prior to the approval of site improvement plans and respective permits, the plans shall note the location, design, and construction details of the eight-foot to nine-foot tall sound walls and/or landscaped berm/wall combinations, as applicable, that will be constructed along the primary Specific Plan Area roadways, adjacent to proposed residential dwellings, in order to achieve the City’s exterior noise standards.

At the City’s discretion, wall heights which achieve the City’s conditionally acceptable 60-70 dB Ldn noise standard may be allowed. See the Draft EIR Table 3.7-14 for specific noise barrier/wall heights along each roadway.

Additionally, at the City’s discretion, alternative noise reduction measures which achieve the City’s conditionally acceptable 60-70 dB Ldn noise standard may be allowed. Alternative noise reduction measures, such as building orientation and use of noise-attenuating features, can be utilized provided that a site-specific acoustical analysis is conducted that demonstrates that the alternative methods would ensure that noise levels do not exceed the City’s conditionally acceptable 60-70 dB Ldn noise standard.

Noise barrier walls shall be constructed of concrete panels, concrete masonry units, stucco or manufactured materials (with a density of four pounds per square foot or greater), earthen landscaped berms, or any combination of these materials as determined appropriate by the City of Salinas based upon the standards contained in the Central Area Specific Plan and the Salinas Zoning Code, as applicable. The design/appearance of the wall is subject to ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
”‹‘”–‘
ƒ’’”‘˜ƒŽ‘ˆ
‹’”‘˜‡‡–
’Žƒ•ƒ†
”‡•’‡
–‹˜‡
’‡”‹–•
324
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦ͵͵

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
the design approval by the City of Salinas to ensure that it is visually pleasing. Wood is not permitted due to eventual warping and degradation of acoustical performance. The walls shall not have gaps or penetrations which allow sound to flank through or around the walls. Small gaps which may occur using materials such as "keystone" blocks shall be avoided.

Additionally, in accordance with Section 5-03.19 of the City’s Municipal Code, best management practices shall be incorporated into the sound wall design in order to control graffiti and/or mitigate the potential impacts of graffiti.

These graffiti prevention best management practices may include, without limitation:
(1) The use or the installation and maintenance of ant-graffiti materials and surface treatments approved by the City on likely graffiti-attracting surfaces.
(2) Installation and maintenance of landscaping to discourage defacement of and/or protect likely graffiti-attracting surfaces. (3) Installation and maintenance of lighting to protect likely graffitiattracting surfaces. (4) Immediate removal of graffiti by appropriate means within seventy-two hours.
(5) Incorporation of architectural or design elements or features to discourage graffiti defacement in accordance with the principles of Crime Prevention Through Environmental Design (CPTED).
(6) Authorizing right of access by city employees or contract agents to remove graffiti if not removed within specified time periods. (7) Supplying the city at its request with paint (of the appropriate color and type), cleaning agents, and/or other materials acceptable to the city to abate or to deter graffiti.
(8) Other requirements, as deemed reasonably feasible by the city planner, to deter, to protect or to reduce the potential for graffiti Appendices
325
ͶǤͲ











ͶǤͲǦ͵Ͷ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
defacement.

Mitigation Measure 3.7-4: Prior to the approval of building permits, the first row of residential dwellings located along E. Boronda Road and Constitution Boulevard shall include windows having a Sound Transmission Class (STC) 35, or higher, rating installed in second floor facades and rooms that have windows or doors that abut or face E. Boronda Road and/or Constitution Boulevard. Exterior walls shall also require 3-coat stucco and RC-channels, sheathing, or another acceptable construction application that effectively attenuates noise intrusion to the interior of the house. The exterior wall specifications would specifically apply to the first row of homes that abut or face E. Boronda Road and/or Constitution Boulevard and only apply to the facades facing these roadways. The specifications do not apply to single story homes, or the first floor of a two-story home, both of which are attenuated by the sound wall. These requirements shall be included in the building plans for the specific dwelling units and noted on the building permits. A detailed analysis of any additional interior mitigation measures shall be conducted when building plans are available and prior to building permit issuance to verify these requirements. These requirements shall also be noted in the site improvement plans prior to approval by the City.

Mitigation Measure 3.7-5: Prior to the approval of building permits, mechanical ventilation shall be required in the first row of all residential dwellings that abut E. Boronda Road and Constitution Boulevard, as desired for acoustical isolation, to keep their doors and windows closed and still maintain acceptable interior temperature and noise levels. This requirement shall be included in the building plans for the specific dwelling units and noted on the building permits. This requirement shall also be noted in the site improvement plans prior to approval by the City.
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
”‹‘”–‘
ƒ’’”‘˜ƒŽ‘ˆ
„—‹Ž†‹‰
’‡”‹–•
”‹‘”–‘
ƒ’’”‘˜ƒŽ‘ˆ
„—‹Ž†‹‰
’‡”‹–•

’ƒ
– ͵Ǥ͹Ǧͷǣ Ї ’”‘’‘•‡†
’”‘Œ‡
– Šƒ• –Ї ’‘–‡–‹ƒŽ –‘
‡š’‘•‡ •‡•‹–‹˜‡ ”‡
‡’–‘”• –‘
•—„•–ƒ–‹ƒŽ ‘‹•‡ ˆ”‘ ’”‘’‘•‡†
’ƒ”ƒ†•
Š‘‘Ž—•‡•
Mitigation Measure 3.7-6: Prior to the approval of site improvement plans, as applicable, when parks or play areas are located near residential uses, the center of active play areas, such as football fields, soccer fields or other athletic fields, shall be located at a minimum distance of 90-feet from the nearest residential property lines. Large active play areas shall comply with the 60 dB Leq and 70 dB Lmax standards, and shall include these further noise level evaluations during the design phases of future park areas. ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ•‹–‡
‹’”‘˜‡‡–
’Žƒ•
326
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦ͵ͷ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
Parks shall be designed such that residences front, or side in limited locations where approved by the City Planner, to the park. Minimum 6-foot tall sound walls and/or landscaped berms shall be constructed where school site directly abuts a residential property line in instances where site design (i.e., minimum distances, siting of activity areas, etc.) cannot achieve the 60 dB Leq and 70 dB Lmax noise standards. No wall shall be required where residential uses are fronted towards a park or school site and separated by a roadway or a walkway.

Noise barrier walls shall be constructed of concrete panels, concrete masonry units, stucco or manufactured materials (with a density of four pounds per square foot or greater), earthen landscaped berms, or any combination of these materials as determined appropriate by the Salinas Public Works Department and the City Planner. The design/appearance of the walls is subject to the design approval by the Salinas Public Works Department and the City Planner based upon the standards contained in the Central Area Specific Plan and the Salinas Zoning Code, as applicable to ensure that it is visually pleasing. Wood is not permitted due to eventual warping and degradation of acoustical performance. The walls shall not have gaps or penetrations which allow sound to flank through or around the walls. Small gaps which may occur using materials such as "keystone" blocks shall be avoided. Additionally, in accordance with Section 5-03.19 of the City’s Municipal Code, best management practices shall be incorporated into the sound wall design in order to control graffiti and/or mitigate the potential impacts of graffiti (see Mitigation Measure 3.7-3 for further discussion of best management practices).

’ƒ
– ͵Ǥ͹Ǧ͸ǣ Ї ’”‘’‘•‡†
’”‘Œ‡
– Šƒ• –Ї ’‘–‡–‹ƒŽ –‘
‡š’‘•‡ •‡•‹–‹˜‡ ”‡
‡’–‘”• –‘
•—„•–ƒ–‹ƒŽ ‘‹•‡ ˆ”‘ ’”‘’‘•‡†

‘‡”
‹ƒŽ‹š‡†Ǧ—•‡•
Mitigation Measure 3.7-7: Prior to the approval of development review permits, the plans shall demonstrate: where mixed use commercial, business professional, office, or similar uses face residential uses or where loading docks or truck circulation routes face residential areas, the following measures shall be included in the project design:
• All HVAC equipment shall be located within mechanical rooms where possible or shielded from view with solid or grated barriers; • Emergency generators shall comply with the City’s noise criteria at the nearest noise-sensitive receivers;
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
”‹‘”–‘–Ї
ƒ’’”‘˜ƒŽ‘ˆ
†‡˜‡Ž‘’‡–
”‡˜‹‡™’‡”‹–•
Appendices
327
ͶǤͲ











ͶǤͲǦ͵͸ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
• Delivery/loading activities shall comply with the Salinas Zoning Code standards and regulations; and
The applicant shall submit a noise study to verify that the appropriate noise control measures have been incorporated into the project design and will achieve compliance with the City’s noise level standards.

’ƒ
– ͵Ǥ͹Ǧ͹ǣ Ї ’”‘’‘•‡†
’”‘Œ‡
– Šƒ• –Ї ’‘–‡–‹ƒŽ –‘
‡š’‘•‡ •‡•‹–‹˜‡ ”‡
‡’–‘”• –‘
•—„•–ƒ–‹ƒŽ ‘‹•‡ ˆ”‘ ’”‘’‘•‡†
™‡ŽŽ•‹–‡•
Mitigation Measure 3.7-8: The potential well sites are shown in the Specific Plan. The actual wells are subject to the approval of a Conditional Use Permit (CUP) by the City pursuant to the requirements of the Salinas Zoning Code and the Central Area Specific Plan. The potential well sites and the CUP requirement for said facilities shall be clearly noted on the site improvement plans.

Prior to approval of the CUP and subsequent issuance of the building permits for the wells, the plans shall demonstrate that the following measures shall be included in the project design:
• The wells have been designed and will be built to not exceed a noise level of 55 dB Leq at the nearest residential or school property line during normal operation of the facilities;
• The generators shall not be permitted to exceed the City’s daytime noise standard of 60 dB Leq;
• The generators shall be tested only during daytime hours; and Additionally, that the wells have been designed (in accordance with the Central Area Specific Plan) to incorporate decorative screen walls, landscaping and other features to ensure compatibility with surrounding land uses. ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
”‹‘”–‘
ƒ’’”‘˜ƒŽ‘ˆ–Ї
ƒ†
•—„•‡“—‡–
‹••—ƒ
‡‘ˆ–Ї
„—‹Ž†‹‰
’‡”‹–•ˆ‘”–Ї
™‡ŽŽƒ†
–”‡ƒ–‡– ’Žƒ–
ˆƒ
‹Ž‹–‹‡•





’ƒ
– ͵ǤͻǦͳǣ Ї ’”‘’‘•‡†
’”‘Œ‡
– ƒ› ”‡“—‹”‡ –Ї

‘•–”—
–‹‘ ‘ˆ ˆ‹”‡ †‡’ƒ”–‡–
ˆƒ
‹Ž‹–‹‡• ™Š‹
Š ƒ›
ƒ—•‡
•—„•–ƒ–‹ƒŽ ƒ†˜‡”•‡ ’Š›•‹
ƒŽ
Mitigation Measure 3.9-1: Prior to the issuance of a Certificate of Occupancy for each dwelling unit (and prior to issuance of building permits for non-residential uses), the applicant shall pay all applicable project impact fees per the impact fee schedule.
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
”‹‘”–‘–Ї
‹••—ƒ
‡‘ˆƒ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
‡ƒ
І™‡ŽŽ‹‰
328
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦ͵͹

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
‡˜‹”‘‡–ƒŽ‹’ƒ
–• —‹–ȋƒ†’”‹‘”
–‘‹••—ƒ
‡‘ˆ
„—‹Ž†‹‰
’‡”‹–•ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
—•‡•Ȍ

’ƒ
– ͵ǤͻǦ͵ǣ ”‘Œ‡
–
‹’އ‡–ƒ–‹‘ƒ›”‡•—Ž–‹ –Ї
‡‡†ˆ‘” –Ї
‘•–”—
–‹‘‘ˆ‡™
•
Š‘‘Ž•ǡ ™Š‹
Š Šƒ• –Ї ’‘–‡–‹ƒŽ
–‘
ƒ—•‡ •—„•–ƒ–‹ƒŽ ƒ†˜‡”•‡
’Š›•‹
ƒŽ‡˜‹”‘‡–ƒŽ‹’ƒ
–•
Mitigation Measure 3.9-2: Prior to the issuance of building permits for each dwelling unit, the applicant shall pay applicable school fees mandated by SB 50 to the Salinas Union High School District (SUHSD), Alisal Union School District (AUSD), and/or Santa Rita Union School District (SRUSD) (only required for the SRUSD if the school district boundary adjustment between the SRUSD and the AUSD is not completed as anticipated) and provide documentation of said payment to the City.
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
”‹‘”–‘–Ї
‹••—ƒ
‡‘ˆ
„—‹Ž†‹‰
’‡”‹–•ˆ‘”
‡ƒ
І™‡ŽŽ‹‰
—‹–





’ƒ
– ͵ǤͳͲǦͳǣ †‡” š‹•–‹‰
Ž—• ”‘Œ‡
–
‘†‹–‹‘•ǡ
‹’އ‡–ƒ–‹‘ ‘ˆ –Ї ’”‘’‘•‡†
’‡
‹ˆ‹
Žƒ™‘—ކ
‘ˆŽ‹
–™‹–Š
–Ї ’‡”ˆ‘”ƒ
‡ ‡ƒ•—”‡•
‡•–ƒ„Ž‹•Ї†„›–Ї‹–›‘ˆƒŽ‹ƒ•ǡ
‘–‡”‡›‘—–›ǡƒ†ƒŽ–”ƒ•
Recommended Condition of Approval 3.10-1: Each project applicant for development within the Specific Plan Area shall provide its fair-share funding for the optimization of existing signal timings at North Main Street/Laurel Drive, in proportion to the area planned for development by such project applicant, in accordance with City policies (payable prior to issuance of Certificate of Occupancy for residential and prior to building permit issuance for non-residential development). Total fees shall be determined by the City of Salinas. The final improvement plans shall note this improvement and the fair-share funding requirement. This condition shall include the use of currently available Adaptive Traffic Control Systems (ATCS) in the intersection design.

Recommended Condition of Approval 3.10-2: Each project applicant for development within the Specific Plan Area shall provide its fair-share funding for the widening of the intersection at Natividad Road/East Laurel Drive to add additional northbound and southbound through lanes, in proportion to the area planned for development by such project applicant, in accordance with City policies (payable prior to issuance of Certificate of Occupancy for residential and prior to building permit issuance for non-residential development). This improvement is part of the City’s Traffic Improvement Program. Total fees shall be determined by the City of Salinas. The final ‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
‹••—ƒ
‡ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
†‡˜‡Ž‘’‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
‹••—ƒ
‡ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
Appendices
329
ͶǤͲ











ͶǤͲǦ͵ͺ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
improvement plans shall note this improvement and the fair-share funding requirement.

Recommended Condition of Approval 3.10-3: Each project applicant for development within the Specific Plan Area shall provide its fair-share funding for the installation of a roundabout at the intersection of North Sanborn Road/East Boronda Road, in proportion to the area planned for development by such project applicant, in accordance with City policies (payable prior to issuance of Certificate of Occupancy for residential and prior to building permit issuance for non-residential development). Total fees shall be determined by the City of Salinas. The final improvement plans shall note this improvement and the fair-share funding requirement.

Recommended Condition of Approval 3.10-4: Each project applicant for development within the Specific Plan Area shall provide its fair-share funding for the optimization of existing signal timings and to add an eastbound left turn pocket at the intersection of Sherwood Drive/Natividad Road & East Bernal Drive/La Posada Way, in proportion to the area planned for development by such project applicant, in accordance with City policies (payable prior to issuance of Certificate of Occupancy for residential and prior to building permit issuance for non-residential development). Total fees shall be determined by the City of Salinas. This condition includes the addition of an eastbound left turn pocket and optimization of the existing signal timing to better accommodate the expected changes in traffic distribution and volume with implementation of the proposed project. The final improvement plans shall note this improvement and the fair-share funding requirement. This condition shall include the use of currently available Adaptive Traffic Control Systems (ATCS) in the intersection design.

Recommended Condition of Approval 3.10-5: Each project applicant for development within the Specific Plan Area shall provide its fair-share funding for the optimization of existing signal timings and splits at the South Sanborn/North Sanborn/John Street intersection, in proportion to the area planned for development by such project applicant, in accordance with City policies (payable prior to issuance of Certificate of Occupancy for residential and prior to building permit issuance for non-residential development). Total fees shall be determined by the City of Salinas. The final improvement plans ‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
†‡˜‡Ž‘’‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
‹••—ƒ
‡ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
†‡˜‡Ž‘’‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
‹••—ƒ
‡ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
†‡˜‡Ž‘’‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
330
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦ͵ͻ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
shall note this improvement and the fair-share funding requirement. This condition shall include the use of currently available Adaptive Traffic Control Systems (ATCS) in the intersection design.

Recommended Condition of Approval 3.10-6: Prior to the approval of final improvement plans for each tentative map, each project applicant for development within the Specific Plan Area shall contribute its fair-share funding to the Transportation Agency for Monterey County (TAMC) Regional Development Impact Fee (RDIF) Program and the City of Salinas’ Traffic Impact Fee (TIF) Program, as determined by the TAMC and the City of Salinas, respectively, in proportion to the area planned for development by such project applicant. These programs include improvements to U.S. 101 that would improve mainline and ramp junction operations, which would mitigate the proposed project’s impact to the U.S. 101 ramp junctions affected by the proposed project (i.e. the Northbound Boronda Road OffRamp and Northbound West Laurel Drive Off-Ramp. ‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹••—ƒ
‡ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
†‡˜‡Ž‘’‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
‹••—ƒ
‡ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
†‡˜‡Ž‘’‡–

’ƒ
– ͵ǤͳͲǦʹǣ †‡” š‹•–‹‰
Ž—• ”‘Œ‡
– ƒ† ‡–”ƒŽ ”‡ƒ
’‡
‹ˆ‹
 Žƒ
‘†‹–‹‘•ǡ
‹’އ‡–ƒ–‹‘ ‘ˆ –Ї ’”‘’‘•‡†
’‡
‹ˆ‹
 Žƒ ƒ›
‘ˆŽ‹
– ™‹–Š
–Ї ’‡”ˆ‘”ƒ
‡ ‡ƒ•—”‡•
‡•–ƒ„Ž‹•Ї†„›–Ї‹–›‘ˆƒŽ‹ƒ•ǡ
‘–‡”‡›‘—–›ǡƒ†ƒŽ–”ƒ•
Recommended Condition of Approval 3.10-7: Each project applicant for development within the Specific Plan Area shall provide its fair-share funding for the installation of a traffic signal at San Juan Grade Road/Van Buren Avenue, in proportion to the area planned for development by such project applicant, in accordance with City policies (payable prior to issuance of Certificate of Occupancy for residential and prior to building permit issuance for non-residential development). Total fees shall be determined by the City of Salinas. The final improvement plans for each stage of project development shall note this improvement and the fair-share funding requirement. This condition shall include the use of currently available Adaptive Traffic Control Systems (ATCS) in the intersection design, as specified by the City of Salinas Public Works Department.

Recommended Condition of Approval 3.10-8: Each project applicant for development within the Specific Plan Area shall provide its fair-share of funding to optimize the existing traffic signal timing and splits at intersection of North Main Street/East Boronda Road, in proportion to the area planned for development by such project applicant, in accordance with City policies (payable prior to issuance of Certificate of Occupancy for residential and prior to building permit issuance for non-residential development). Total fees shall be determined by the City of Salinas. The final improvement plans shall ‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
‹••—ƒ
‡ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
†‡˜‡Ž‘’‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
‹••—ƒ
‡ˆ‘”
Appendices
331
ͶǤͲ











ͶǤͲǦͶͲ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
note this improvement and the fair-share funding requirement. This condition shall include the use of currently available Adaptive Traffic Control Systems (ATCS) in the intersection design, as specified by the City of Salinas Public Works Department.

Recommended Condition of Approval 3.10-9: Each project applicant for development within the Specific Plan Area shall provide its fair-share funding for the optimization of the existing signal timing at San Juan Grade Road/East Boronda Road, in proportion to the area planned for development by such project applicant, in accordance with City policies (payable prior to issuance of Certificate of Occupancy for residential and prior to building permit issuance for non-residential development). Total fees shall be determined by the City of Salinas. The final improvement plans shall note this improvement and the fair-share funding requirement. This condition shall include the use of currently available Adaptive Traffic Control Systems (ATCS) in the intersection design, as specified by the City of Salinas Public Works Department.

Recommended Condition of Approval 3.10-10: Each project applicant for development within the Specific Plan Area shall provide its fair-share of funding to convert the eastbound right turn lane to a shared through-right turn lane at Natividad Road/East Laurel Drive, in proportion to the area planned for development by such project applicant, in accordance with City policies (payable prior to issuance of Certificate of Occupancy for residential and prior to building permit issuance for non-residential development). Total fees shall be determined by the City of Salinas. The final improvement plans shall note this improvement and the fair-share funding requirement. This condition shall include the use of currently available Adaptive Traffic Control Systems (ATCS) in the intersection design, as specified by the City of Salinas Public Works Department.

Recommended Condition of Approval 3.10-11: Each project applicant for development within the Specific Plan Area shall provide its fair-share of funding for the installation of a roundabout at the intersection of North Sanborn Road/East Boronda Road, in proportion to the area planned for development by such project applicant, in accordance with City policies (payable prior to issuance of Certificate of Occupancy for residential and ‹–›‘ˆƒŽ‹ƒ•
‘—‹–›
‡˜‡Ž‘’‡–
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‘Ǧ”‡•‹†‡–‹ƒŽ
†‡˜‡Ž‘’‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰ ’‡”‹–
‹••—ƒ
‡ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
†‡˜‡Ž‘’‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
‹••—ƒ
‡ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
†‡˜‡Ž‘’‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
332
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦͶͳ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
prior to building permit issuance for non-residential development). Total fees shall be determined by the City of Salinas. The final improvement plans shall note this improvement and the fair-share funding requirement. This condition shall include the use of currently available Adaptive Traffic Control Systems (ATCS) in the intersection design.

Recommended Condition of Approval 3.10-12: Each project applicant for development within the Specific Plan Area shall provide its fair-share of funding for the installation of a traffic signal at the intersection of Williams Road/East Boronda Road, in proportion to the area planned for development by such project applicant, in accordance with City policies (payable prior to issuance of Certificate of Occupancy for residential and prior to building permit issuance for non-residential development). Total fees shall be determined by the City of Salinas. The final improvement plans shall note this improvement and the fair-share funding requirement. This condition shall include the use of currently available Adaptive Traffic Control Systems (ATCS) in the intersection design.

Recommended Condition of Approval 3.10-13: Each project applicant for development within the Specific Plan Area shall provide its fair-share of funding to add a southbound left turn pocket and optimize traffic signal timings at the traffic signal at Salinas Street/North Main Street/West Market Street/East Market Street, in proportion to the area planned for development by such project applicant, in accordance with City policies (payable prior to issuance of Certificate of Occupancy for residential and prior to building permit issuance for non-residential development). Total fees shall be determined by the City of Salinas. The final improvement plans shall note this improvement and the fair-share funding requirement. This condition shall include the use of currently available Adaptive Traffic Control Systems (ATCS) in the intersection design. This condition shall include the use of currently available Adaptive Traffic Control Systems (ATCS) in the intersection design, as specified by the City of Salinas Public Works Department.
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
‹••—ƒ
‡ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
†‡˜‡Ž‘’‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
‹••—ƒ
‡ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
†‡˜‡Ž‘’‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
‹••—ƒ
‡ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
†‡˜‡Ž‘’‡–

’ƒ
–͵ǤͳͲǦ͵ǣ†‡”——Žƒ–‹˜‡
Ž—• ”‘Œ‡
–
‘†‹–‹‘•ǡ
‹’އ‡–ƒ–‹‘ ‘ˆ –Ї ’”‘’‘•‡†
’‡
‹ˆ‹
 Žƒ ƒ›
‘ˆŽ‹
– ™‹–Š
–Ї –”ƒ•’‘”–ƒ–‹‘ ’‡”ˆ‘”ƒ
‡
Recommended Condition of Approval 3.10-14: Each project applicant for development within the Specific Plan Area shall contribute its fair-share of funding to the TAMC Regional Development Impact Fee to provide improvements addressing this impact identified as the installation of a ‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
Appendices
333
ͶǤͲ











ͶǤͲǦͶʹ ‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
‡ƒ•—”‡•‡•–ƒ„Ž‹•Ї†„›–Ї‹–›
‘ˆ ƒŽ‹ƒ•ǡ‘–‡”‡›‘—–›ǡƒ†
ƒŽ–”ƒ•
traffic signal at intersection of U.S. 101 Southbound Ramps/Echo Valley Road/Crazy Horse Canyon Road. Regional fees shall be determined by the City of Salinas in consultation with TAMC. This condition shall include the use of currently available Adaptive Traffic Control Systems (ATCS) in the intersection design, as specified by the City of Salinas Public Works Department.

Recommended Condition of Approval 3.10-15: Each project applicant for development within the Specific Plan Area shall contribute its fair-share of the TAMC Regional Development Impact Fee to provide improvements addressing this impact identified as the installation of a traffic signal at intersection of U.S. 101 Northbound Ramps/Crazy Horse Canyon Road. Total fees shall be determined by the City of Salinas in consultation with TAMC.

Fees are payable prior to final improvement plans for each tentative map.

Recommended Condition of Approval 3.10-16: Prior to the approval of final improvement plans for each tentative map, each project applicant for development within the Specific Plan Area shall provide its fair-share contribution for the installation of a traffic signal at intersection of Crazy Horse Canyon Road/San Juan Grade Road, in proportion to the area planned for development by such project applicant. Total fees shall be determined by the City of Salinas. The final improvement plans shall note this improvement and the fair-share funding requirement. This condition shall consider the use of currently available Adaptive Traffic Control Systems (ATCS) in the intersection design, as specified by the City of Salinas Public Works Department.

Recommended Condition of Approval 3.10-17: Each project applicant for development within the Specific Plan Area shall provide its fair-share contribution for the installation of a traffic signal at intersection of Natividad Road/Rogge Road, in proportion to the area planned for development by such project applicant, in accordance with City policies (payable prior to issuance of Certificate of Occupancy for residential and prior to building permit issuance for non-residential development). Total fees shall be determined by the City of Salinas. The final improvement plans shall note this improvement and the fair-share funding requirement. This condition shall consider the use of currently available Adaptive Traffic Control Systems ‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
‹–›‘ˆƒŽ‹ƒ•
—„Ž‹
‘”•
‡’ƒ”–‡–
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
‹••—ƒ
‡ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
†‡˜‡Ž‘’‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
‹••—ƒ
‡ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
†‡˜‡Ž‘’‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
‹••—ƒ
‡ˆ‘”
‘Ǧ”‡•‹†‡–‹ƒŽ
†‡˜‡Ž‘’‡–
”‹‘”–‘
‹••—ƒ
‡‘ˆ
‡”–‹ˆ‹
ƒ–‡‘ˆ


—’ƒ
›ˆ‘”
”‡•‹†‡–‹ƒŽƒ†
’”‹‘”–‘
„—‹Ž†‹‰’‡”‹–
334
City of Salinas | Final Central Area Specific Plan, November 2020











 ͶǤͲ
‹ƒŽ˜‹”‘‡–ƒŽ
’ƒ
–‡’‘”–– ƒŽ‹ƒ• ‡–”ƒŽ ”‡ƒ’‡
‹ˆ‹
Žƒ ͶǤͲǦͶ͵

ENVIRONMENTAL IMPACT MITIGATION MEASURE

MONITORING

RESPONSIBILITY
TIMING

VERIFICATION
(DATE/INITIALS)
(ATCS) in the intersection design, as specified by the City of Salinas Public Works Department.

Recommended Condition of Approval 3.10-18: Each project applicant for development within the Specific Plan Area shall provide its fair-share contribution for the installation of a traffic signal at intersection of Natividad Road/Russell Road, in proportion to the area planned for development by such project applicant, in accordance with City policies (payable prior to issuance of Certificate of Occupancy for residential and prior to building permit issuance for non-residential development). Total fees shall be determined by the City of Salinas. The final improvement plans shall note this improvement and the fair-share funding requirement. This condition shall include the use of currently available Adaptive Traffic Control Systems (ATCS) in the intersection design, as specified by the City of Salinas Public Works Department.