DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
iii
CITY OF UKIAH
DEPARTMENT OF PUBLIC WORKS
OCTOBER 2021
TABLE OF CONTENTS
PAGE
NOTICE TO BIDDERS.................................................................................................................................. 1 INSTRUCTIONS TO BIDDERS.................................................................................................................... 4
GENERAL CONDITIONS
SECTION 1. PROPOSAL REQUIREMENTS AND GENERAL CONDITIONS............................................6 1-01. Definitions
1-02. Examinations of Plans, Special Provisions and Site of Work 1-03. Proposal
1-04. Withdrawal of Bids
1-05. Public Opening of Bids
1-06. Bid Guaranty
1-07. Qualification of Bidders
1-08. Disqualification of Bidders
1-09. Identification of Subcontractors
1-10. General Provisions of the Standard Specifications 1-11. Addenda
SECTION 2. AWARD AND EXECUTION OF CONTRACT ........................................................................ 8 2-01. Award of Contract
2-02. Return of Proposal Guaranties
2-03. Execution of Contract
SECTION 3. SCOPE AND INTENT OF CONTRACT ................................................................................. 8 3-01. Effect of Inspection and Payments
3-02. Effect of Extension of Time
3-03. Extra Work
3-04. Assignment of Contract
3-05. Subcontractors
3-06. Interpretation of Special Provisions and Drawings 3-07. Addenda
3-08. Liability of City Officials
3-09. Dispute Resolution
SECTION 4. BONDS ................................................................................................................................... 9 4-01. Faithful Performance Bond
4-02. Material and Labor Bond
4-03. Defective Material and Workmanship Bond
4-04. Notification of Surety Companies
SECTION 5. INSURANCE REQUIREMENTS FOR CONTRACTORS.....................................................10 5-01. Minimum Scope of Insurance
5-02. Minimum Limits of Insurance
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
iv
5-03. Deductibles and Self-Insured Retentions
5-04. Other Insurance Provisions
5-05. Acceptability of Insurers
5-06. Verification of Coverage
5-07. Subcontractors
SECTION 6. RESPONSIBILITIES AND RIGHTS OF CONTRACTOR.....................................................11 6-01. Legal Address of Contractor
6-02. Office of Contractor at Site
6-03. Attention to Work
6-04. Liability of Contractor
6-05. Protection of Persons and Property
6-06. Protection of City Against Patent Claims
6-07. Protection of Contractor's Work Property
6-08. Regulations and Permits
6-09. Construction Utilities
6-10. Approval of Contractor's Plans
6-11. Suggestions to the Contractor
6-12. Termination of Unsatisfactory Subcontracts
6-13. Preservation of Stakes and Marks
6-14. Assistance to Engineer
6-15. Removal of Condemned Materials and Structures
6-16. Proof of Compliance with Contract
6-17. Errors and Omissions
6-18. Cooperation
6-19. Right of Contractor to Stop Work
6-20. Hiring and Dismissal of Employees
6-21. Wage Rates
6-22. Cleaning Up
6-23. Guaranty
6-24. Public Notification
SECTION 7. RESPONSIBILITIES AND RIGHTS OF CITY......................................................................16 7-01. Authority of the Engineer
7-02. Inspection
7-03. Surveys
7-04. Rights-of-Way
7-05. Retention of Imperfect Work
7-06. Changes in the Work
7-07. Additional Drawings by City
7-08. Additional and Emergency Protection
7-09. Suspension of Work
7-10. Right of City to Terminate Contract
7-11. Use of Completed Portions
SECTION 8. WORKMANSHIP, MATERIALS AND EQUIPMENT............................................................18 8-01. General Quality
8-02. Quality in Absence of Detailed Specifications
8-03. Materials and Equipment Specified by Name
8-04. Source of Materials
8-05. Storage of Materials
8-06. Drawings, Samples and Tests
SECTION 9. PROSECUTION OF WORK .................................................................................................19
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
v
9-01. Equipment and Methods
9-02. Time of Completion
9-03. Avoidable Delays
9-04. Unavoidable Delays
9-05. Notice of Delays
9-06. Extension of Time
9-07. Unfavorable Weather and Other Conditions
9-08. Saturday, Sunday, Holiday and Night Work
9-09. Hours of Labor
SECTION 10. PAYMENT...........................................................................................................................20 10-01. Certification by Engineer
10-02. Progress Estimates and Payment
10-03. Substitution of Securities
10-04. Acceptance
10-05. Final Estimate and Payment
10-06. Delay Payments
10-07. Extra Work and Work Omitted
10-08. Compensation for Extra Work or Work Omitted
10-09. Compensation to the City for Extension of Time
10-10. Liquidated Damages for Delay
SECTION 11. MISCELLANEOUS.............................................................................................................23 11-01. Notice
11-02. Computation of Time
11-03 Claims Procedure Required by Public Contract Code Section 9204 11-04. Litigation and Forum Selection
11-05. Waiver
TECHNICAL SPECIFICATIONS
SECTION 12. GENERAL INFORMATION ................................................................................................26 12-01. Arrangement of Technical Specifications
12-02. Existing
12-03. Business Licenses
12-04. Permits
12-05. Standard Specifications and Standard Plans
12-06. Temporary Facilities
12-07. Public Convenience and Safety
12-08. Maintaining Traffic
12-09. Stream Pollution
12-10. Warranties
12-11. Utilities
12-12. Dust Control
12-13. Noise Control
12-14. Watering
12-15. Preconstruction Conference
12-16. Progress Schedule
12-17. Safety Requirements
SECTION 13. CONSTRUCTION DETAILS...............................................................................................29 13-01. Location and Scope of Work
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
vi
13-02. Preservation of Property
13-03. Watering
13-04. Traffic Control System for Street Closure
13-05. Adjust Existing Frames, Covers, Grates and Manholes to Grade 13-06. Roadway Excavation
13-07. Hot Mix Asphalt
13-08. Remove Unsuitable Material
13-09. Soil Stabilization Fabric
13-10. Class 2 Aggregate Base
13-11. Traffic Striping
13-12. Thermo X-Walk & Pavement Markings
13-13. Reflective Pavement Markers (Blue)
13-14. Minor Concrete
13-15. Remove and Replace Sign Post
13-16. Storm Drain Pipe
13-17. Drainage Structures
13-18. Water Main – 6” PVC Pipe
13-19. Water Services
13-20. Fire Hydrants
13-21. Temporary Blow Off
13-22. Abandon or Remove Water System Components
13-23. Trench Bracing and Shoring
13-24. Remove and Replace Existing Sanitary 8” Pipe
13-25. Remove Existing Sanitary Sewer Manhole
13-26. Install Sanitary Sewer Manhole
13-27. Install Inline Sanitary Sewer Cleanout
13-28. Sewer Laterals and Cleanouts
13-29. Mobilization and Demobilization
13-30. Construction Survey
13-31. Clearing and Grubbing
SECTION 14. EXCLUSIONS FROM GENERAL CONDITIONS...............................................................44 14-01. Provisions to be Excluded from General Conditions SECTION 15. AMENDMENTS TO GENERAL CONDITIONS..................................................................44 15-01. Provisions of General Conditions to be Amended
CERTIFICATES AND DOCUMENTS
BID SUBMITTAL CHECKLIST....................................................................................................................45 PROPOSAL ...........................................................................................................................................46 BIDDING SCHEDULE.................................................................................................................................47 FAIR EMPLOYMENT PRACTICES CERTIFICATION ...............................................................................51 WORKER'S COMPENSATION CERTIFICATE..........................................................................................52 CERTIFICATE OF NONDISCRIMINATION IN EMPLOYMENT.................................................................53 LIST OF PROPOSED SUBCONTRACTORS.............................................................................................54 STATEMENT OF EXPERIENCE OF BIDDER............................................................................................55 SIGNATURE OF BIDDER...........................................................................................................................56 BIDDER'S BOND ........................................................................................................................................57 NON-COLLUSION AFFIDAVIT...................................................................................................................58
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
vii
AGREEMENT ...........................................................................................................................................59 INDEMNIFICATION AGREEMENT ............................................................................................................63 EXAMPLE BOND FORMS..........................................................................................................................64 DIRECTIONS FOR PREPARATION OF PERFORMANCE AND MATERIAL AND LABOR BOND ..........68 DEFECTIVE MATERIAL AND WORKMANSHIP (MAINTENANCE) BOND ..............................................69
INSURANCE CERTIFICATES AND ENDORSEMENT FORMS
APPENDICES:
PLAN SHEETS - 30 PAGES
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
1 CITY OF UKIAH, MENDOCINO COUNTY, CALIFORNIA
NOTICE TO BIDDERS FOR DORA STREET UTILITY IMPROVEMENT PROJECT SPEC NO. 19-01 NOTICE IS HEREBY GIVEN that sealed standard proposals for DORA STREET UTILITY IMPROVEMENT PROJECT will be received at the Office of the City Clerk, Ukiah Civic Center, 300 Seminary Avenue, Ukiah California until 2:00 p.m. on XXXXX at which time, or as soon thereafter as possible, they will be publicly opened and read. Bids shall be addressed to the City Clerk and shall be endorsed “DORA STREET UTILITY IMPROVEMENT PROJECT" Bids are required for the entire work described herein. No fax bids will be accepted.
ENGINEER'S ESTIMATE OF QUANTITIES
ITEM
NO. DESCRIPTION QUANTITY UNIT
1 TRAFFIC CONTROL 1 LS
2 MOBILIZATION / DEMOBILIZATION 1 LS
3 CONSTRUCTION SURVEY 1 LS
4 PUBLIC NOTIFICATION 1 LS
5 ROADWAY EXCAVATION 10,838 CY
6 REMOVE UNSUITABLE MATERIAL 100 CY
7 SOIL STABILIZATION FABRIC 21,265 SY
8 CLASS 2 AGGREGATE BASE 7,225 CY
9 HOT MIX ASPHALT (TYPE A) 7,315 TN
10 REMOVE 6-INCH SEWER MAIN AND REPLACE WITH 8-INCH SEWER MAIN 2,059 LF
11 REMOVE AND REPLACE 6-INCH SEWER MAIN 144 LF
12 4 INCH SEWER LATERAL WITH CLEANOUT 23 EA
13 INSTALL INLINE 8" SEWER CLEANOUT 4 EA
14 INSTALL 48 INCH SANITARY SEWER MANHOLE 11 EA
15 REMOVE 48 INCH SANITARY SEWER MANHOLE 12 EA
16 TRENCH BRACING AND SHORING 1 LS
17 STORM DRAIN INLET - TYPE GO D73E 2 EA
18 STORM DRAIN INLET - MODEL 4AC 4 EA
19 STORM DRAIN INLET - MODEL 4AC WITH 6Y PELICAN FIBERGLASS COMPONENTS 1 EA
20 STORM DRAIN JUNCTION BOX - MODEL JB3636 2 EA
21 CONNECT 24" HDPE STORM DRAIN TO EXISTING BASIN 1 EA
22 STORM DRAIN - 12 INCH HDPE 32 LF
23 STORM DRAIN - 18 INCH HDPE 633 LF
24 STORM DRAIN - 24 INCH HDPE 567 LF
25 6 INCH PVC WATER MAIN CLASS 200 4,217 LF
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
2 ITEM
NO. DESCRIPTION QUANTITY UNIT
26 1" WATER SERVICE PLUMBED FOR 3/4" METER 31 EA
27 1" WATER SERVICE PLUMBED FOR 1" METER 3 EA
28 2" COMPOUND WATER METER 1 EA
29 6" FIRE SERVICE LINE 1 EA
30 FIRE HYDRANT AND LATERAL ASSEMBLY 8 EA
31 REMOVE AND SALVAGE EXISITING FIRE HYDRANT 8 EA
32 ABANDON OR REMOVE WATER SYSTEM COMPONENTS 1 LS
33 TEMPORARY BLOW OFF 2 EA
34 WATER MAIN TIE IN 21 EA
35 ADJUST MANHOLE TO GRADE 11 EA
36 ADJUST VALVE BOX TO GRADE 49 EA
37 REMOVE CONCRETE (CURB & GUTTER) 1,046 LF
38 REMOVE CONCRETE (SIDEWALK & FLATWORK 6,473 SF
39 REMOVE CONCRETE (VALLEY GUTTER) 3,634 SF
40 MINOR CONCRETE (CURB & GUTTER) 1,046 SF
41 MINOR CONCRETE (CURB RAMP) 5,117 SF
42 MINOR CONCRETE (SIDEWALK) 1,356 SF
43 MINOR CONCRETE (VALLEY GUTTER) 3,634 SF
44 MINOR CONCRETE (CURB) 28 SF
45 REMOVE & REPLACE ROADSIDE SIGN POST 17 EA
46 TRAFFIC STRIPE (DETAIL 1) 1,536 LF
47 TRAFFIC STRIPE (DETAIL 21) 1,200 LF
48 TRAFFIC STRIPE (DETAIL 27B) 4,225 LF
49 TRAFFIC STRIPE (DETAIL 39) 4,225 LF
50 TRAFFIC STRIPE (DETAIL 39A) 1,200 LF
51 THERMO X-WALK & PAVEMENT MARKING 3,223 SF
52 PAVEMENT MARKERS 15 EA
Plans and Special Provisions may also be downloaded at no charge from the City’s website at www.cityofukiah.com/purchasing. Contact Mary Horger, Financial Services Manager, City of Ukiah, 300 Seminary Avenue, Ukiah, California 95482-5400. No bid will be considered unless it is made on the forms furnished by the City and is made in accordance with the details of the Special Provisions. Each bidder must be licensed as required by law.
Further information regarding the work or these specifications can be obtained by calling Mary Horger at (707) 463-6233 or at fax phone (707) 313-3621.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
3 The City Council reserves the right to reject any or all bids and to determine which proposal is, in its opinion, the lowest responsive bid by a responsible bidder and which it deems in the best interest of the City to accept. The City Council also reserves the right, but not the obligation, to waive any irregularity or failure to strictly comply with the bidding requirements, that the City determines in the reasonable exercise of its discretion does not provide the bidder with a competitive advantage over other bidders.
No contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations (“DIR”) pursuant to Labor Code section 1725.5 except as allowed under Labor Code section 1771.1(a). The prime contractor shall be responsible for posting job site notices as prescribed by regulation.
This project is subject to compliance monitoring and enforcement by the DIR.
Pursuant to provisions of Section 1770, including amendments thereof, of the Labor Code of the State of California, the DIR Director has ascertained the general prevailing rate of wages for straight time, overtime, Saturdays, Sundays and Holidays including employer payment for health and welfare, vacation, pension and similar purposes for the City of Ukiah.
Copies of the General Prevailing Wage Determination are available on the Internet at web address:
http://www.dir.ca.gov/DLSR/PWD/ The prime contractor for the work herein shall possess a current, valid State of California, Class A (General Engineering) Contractor's License. Pursuant to California Public Contract Code §22300, this contract includes provisions that allow substitutions of certain types of securities in lieu of the City withholding a portion of the partial payments due the Contractor to insure performance under this contract.
By order of the City Council, City of Ukiah, County of Mendocino, State of California.
Dated:________________________ ________________________________________ Kristine Lawler, City Clerk, City of Ukiah, California
PUBLISH TWO TIMES: XXXXXXXXX
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
4 INSTRUCTIONS TO BIDDERS
DORA STREET UTILITY IMPROVEMENT PROJECT shall be performed in accordance with the Plans and Special Provisions therefor adopted, to which special reference is hereby made.
Each bidder must supply all the information required by the bid documents and Special Provisions.
Minority business enterprises will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color or national origin in consideration for an award of any contract entered into pursuant to this advertisement. Women will be afforded equal opportunity in all areas of employment. However, the employment of women shall not diminish the standards or requirements for the employment of minorities.
All proposals or bids shall be accompanied by a cashier's check or certified check payable to the order of the City of Ukiah amounting to 10 percent of the bid, or by a bond in said amount and signed by the bidder and a corporate surety, payable to said City. Said check shall be forfeited, or said bond shall become payable to said City in case the bidder depositing the same does not, within fifteen (15) days after written notice that the contract has been awarded to him: (a) enter into a contract with the City and (b) furnish certificates of insurance and endorsements, a bond of faithful performance and a payment bond as described in the Special Provisions.
No bidder shall withdraw his or her bid for a period of thirty (30) calendar days after the date set by the City for the opening thereof.
The Contractor and any subcontractors shall each possess a valid City of Ukiah Business License prior to the start of any work.
The Contractor shall furnish a project schedule to the Engineer prior to the start of any work and start work as scheduled.
The work is to be completed within one hundred and eighty (180) working days. The Contractor will pay to the City the sum of five hundred ($500.00) dollars per day for each and every calendar day's delay beyond the time prescribed.
The staff shall notify a bidder by telephone, email or fax, if it intends to recommend the rejection of the bidder’s bid.
Any bid protest must be filed with the City Clerk not more than five calendar days following the bid opening, or 2 calendar days following notice that staff is recommending the rejection of a bid. If any such timely written protest is filed, all bidders shall be provided a copy of the protest within 2 calendar days of its receipt, which may be delivered to the bidders as an email attachment or by fax. All such bidders may file with the City Manager a written objection or other response to the protest.
All objections or responses filed not more than 5 days after receipt of the written protest will be presented to the City Council at its next regular meeting occurring not less than 12 calendar days following the bid opening. The City Council will resolve the bid protest at that meeting based on the written protest, any staff recommendation and all timely written objections and responses. In accordance with the Brown Act, any person may address the City Council on this item during the meeting. The City Council action on the protest shall represent a final decision by the City on the protest.
Examination of Site, Drawings, Etc.
Each bidder shall visit the site of the proposed work and fully acquaint himself with local conditions, construction and labor required so that he or she may fully understand the facilities, difficulties and restrictions attending the execution of the work under the Contract. Bidders shall thoroughly examine and be familiar with the Plans and Special Provisions.
The failure of any bidder to receive or examine any form, instrument, addendum, or other document, or to visit the site and acquaint himself with conditions there existing, shall in no way relieve the bidder from any obligation with respect to his or her proposal or to the contract. The drawings for the work show conditions as they are supposed or believed by the Engineer to exist; but, it is neither intended nor shall it be inferred that the conditions as shown thereon constitute a representation by the Engineer, the City or its officers that such conditions are actually existent, nor shall the City, the Engineer or any of their officers or representatives be liable for any loss sustained by the Contractor as a result of a variance between the conditions shown on the drawings and the conditions actually revealed during the progress of the work or otherwise.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
5 The bidder's attention is directed to the possible existence of obstructions and public improvements within the limits of the work or adjacent thereto, which may or may not be shown on the Drawings. Any bid shall take into consideration that conditions may exist underground or otherwise that are not known to the City or easily detected during a site inspection that could impact the time or cost of completing the project. The City expects the bids to anticipate such conditions so that it can know for budgeting and other purposes the total cost to complete the project before accepting a bid and undertaking the legal obligation to construct the project. In awarding the contract the City relies on the contractor’s representation that its bid anticipates differing site conditions and the additional time or cost that such conditions may necessitate.
The bidder shall investigate to his or her satisfaction the conditions to be encountered, the character, quality and quantities of work to be performed and materials to be furnished and the requirements of the Plans, Special Provisions, Standard Specifications, Standard Plans, and Contract Documents. The submission of a proposal shall be considered conclusive evidence that the bidder has made such examination and has accepted the project workplace as a safe workplace to perform the work of the Contract.
Bidder Inquiries and Questions
Inquiries and questions must be submitted in writing via fax or email to the following designated contact person:
Mary Horger, Financial Services Manager
Fax: (707) 313-3621
Email: [email protected]
The City reserves the right to not respond to inquiries or questions submitted within 3 business days of the bid opening.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
6 Location of the Work
All of the work to be performed is within the City of Ukiah. Project is located at the following locations:
-Dora Street between West Mill Street and Grove Avenue
-West Clay Street from Dora Street to South Pine Street -Walnut Avenue from Dora Street to North Bush Street
-North Bush Street from Walnut Avenue to Grove Avenue
GENERAL CONDITIONS
SECTION 1. PROPOSAL REQUIREMENTS AND GENERAL CONDITIONS 1-01. Definitions. Whenever any word or expression defined in this section, or pronoun used in its stead, occurs in these contract documents, it shall have and is mutually understood to have the meaning given:
a. "City of Ukiah" or "City" shall mean the City of Ukiah, Mendocino County, California, acting through its City Council or any other board, body, official or officials to which or to whom the power belonging to the Council shall by virtue of any act or acts, hereafter pass or be held to appertain. b. "Engineer" shall mean the Engineer duly and officially appointed by the City to supervise and direct the work of construction under this contract, acting personally or through agents or assistants duly authorized by him, such agents or assistants acting within the scope of the particular duties entrusted to them.
c. "Inspector" shall mean the engineering or technical inspector or inspectors duly authorized or appointed by the Engineer, limited to the particular duties entrusted to him or her or them. d. "Contractor" shall mean the party entering into contract with the City of Ukiah for the performance of work covered by this contract and his or her authorized agents or legal representatives. e. "Date of signing of contract" or words equivalent thereto, shall mean the date upon which this contract, with the signature of the Contractor affixed, together with the prescribed bonds, shall be or shall have been delivered to the City or its duly authorized representatives. f. "Day" or "days", unless herein otherwise expressly defined, shall mean a calendar day or days of twentyfour hours each. g. "The work" shall mean and include all the work specified, indicated, shown or contemplated in the contract to construct the improvement, including all alterations, amendments or extensions thereto made by contract change order or other written orders of the Engineer. h. "Contract drawings", "drawings", "plans" shall mean and include 1) all drawings or plans which may have been prepared by or on behalf of the City, as a basis for proposals, when duly signed and made a part of this contract by incorporation or reference, 2) all drawings submitted in pursuance of the terms of this contract by the successful bidder with his or her proposal and by the Contractor to the City if and when approved by the Engineer and 3) all drawings submitted by the Engineer to the Contractor during the progress of the work as provided for herein.
i. Where "as shown", "as indicated", "as detailed" or words of similar import are used, it shall be understood that reference to the drawings accompanying these Special Provisions is made unless stated otherwise.
Where "as directed", "as permitted", "approved" or words of similar import are used, it shall be understood that the direction, requirements, permission, approval or acceptance of the Engineer is intended unless stated otherwise.
As used herein, "provide" or "install" shall be understood to mean "provide or install complete in place", that is, "furnish and install". "Shall" is mandatory; "may" is permissive.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
7 1-02. Examination of Plans, Special Provisions and Site of Work. The bidder shall examine carefully the Proposal, Plans, Special Provisions, Contract forms and the site of the work contemplated therefor. It will be assumed that the bidder has investigated to his or her satisfaction the conditions to be encountered and the character, quality and requirements of all Plans, Special Provisions, Standard Specifications, and Standard Plans involved. 1-03. Proposal. Bids shall be made on the blank forms prepared by the City. All bids shall give the prices bid, both in writing and in figures and shall be signed by the bidder or his or her authorized representative, with his or her address.
If the bid is made by an individual or partner, his or her name and the post office address of his or her business or partnership, along with his or her signature or the signature of one or more partners must be shown; if made by a corporation, the bid shall show the name of the state under the laws of which the corporation is chartered, the name of the corporation and the title of the person who signs on behalf of the corporation.
Each proposal shall be enclosed in a sealed envelope, endorsed as specified in the notice to bidders. Bidders are warned against making erasures or alterations of any kind and proposals which contain omissions, erasures, conditions, alterations, additions not called for, additional proposals or irregularities of any kind may be rejected. 1-04. Withdrawal of Bids. Any bid may be withdrawn at any time prior to the hour fixed in the notice to bidders for the openings of bids, provided that a request in writing, executed by the bidder or his or her duly authorized representative, for the withdrawal of such bid is filed with the City. The withdrawal of a bid will not prejudice the right of a bidder to file a new bid.
1-05. Public Opening of Bids. Bids will be opened and read publicly at the time and place indicated in the notice to bidders. Bidders or their agents are invited to be present. 1-06. Bid Guaranty. Each bid must be accompanied by a certified check, cashier's check or bidder's bond executed by an admitted surety insurer, payable to the order of the City of Ukiah in an amount not less than 10 percent of the bid as a guarantee that the bidder will enter into a contract, if awarded the work. 1-07. Qualification of Bidders. No contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)]. No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5. The prime contractor shall be responsible for posting job site notices as prescribed by regulation. This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.
Each bidder shall be licensed under the provisions of Chapter 9, Division 3 of the Business and Professions Code and shall be skilled and regularly engaged in the general class or type of work called for under this contract. A statement setting forth this experience and business standing shall be submitted by each bidder on the form provided herewith. It is the intention of the City to award a contract only to a bidder who furnishes satisfactory evidence that he or she has the requisite experience and ability and that he or she has sufficient capital, facilities and equipment to enable him or her to prosecute the work successfully and promptly within the time and in the manner agreed.
In determining the degree of responsibility to be credited to a bidder, the City may weigh evidence that the bidder or his or her personnel charged with the responsibility in the work, has performed satisfactorily other contracts of like nature and magnitude or comparable difficulty at similar rates of progress. 1-08. Disqualification of Bidders. More than one bid from an individual business, partnership, corporation or association, under the same or different names, will not be considered. Reasonable grounds for believing that any bidder is financially interested in more than one bid for the work will cause the rejection of all bids in which he or she is so interested. If there is reason to believe that collusion exists among the bidders, none of the participants in such collusion will be considered. Bids in which the prices obviously are unbalanced may be rejected. 1-09. Identification of Subcontractors. All bids shall comply with the Subletting and Subcontracting Fair Practices Act (Public Contract Code Section 4100 and following) and shall set forth:
(a) The name and the location of the place of business of each subcontractor who will perform work or labor, or render service to the prime contractor in or about the construction of the work, or to a subcontractor licensed by
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
8 the State of California who, under subcontract to the prime contractor, specially fabricates and installs a portion of the work according to detailed drawings contained in the plans and Special Provisions, in an amount in excess of one-half of 1 percent of the prime contractor's total bid. (b) The portion of the work which will be done by each such subcontractor. The prime contractor shall list only one subcontractor for each such portion defined by the prime contractor in his or her bid. 1-10. General Provisions of the Standard Specifications. All provisions of the General Provisions, Sections 1 through 11, of the Standard Specifications, shall be applicable to the contract except as modified by these Special Provisions. The Standard Specifications are set forth in Section 12-06 of these Special Provisions. 1-11. Addenda. If it becomes necessary to revise any part of these plans and specifications after they have been released, the City will issue an addendum containing the revision. All addenda will be posted on the City’s website at www.cityofukiah.com/purchasing with the rest of the bid documents. Anyone who intends to submit a bid in response to this Request for Bid must check the website frequently for any posted addenda. Anyone submitting a bid will be deemed to have seen and agreed to be bound by the posted addenda.
SECTION 2. AWARD AND EXECUTION OF CONTRACT
2-01. Award of Contract. Award of the contract, if it be awarded, will be to the lowest responsible bidder whose bid complies with all the specified requirements. The award, if made, will be made within thirty (30) days after opening of the bids. The City reserves the right to reject any and all bids and to waive any irregularity in the proposal not pertaining to cost.
2-02. Return of Proposal Guaranties. All bid guaranties will be held until the contract has been fully executed, after which they will be returned upon request to the respective bidders whose bids they accompany. 2-03. Execution of Contract. The contract agreement shall be executed in duplicate by the successful bidder and returned, together with the contract bonds, insurance certificates and endorsements, within fifteen (15) days after written notice of the award of the contract. After execution by the City; one copy shall be filed with the City and one copy shall be returned to the Contractor. If the bidder fails or refuses to enter into the contract agreement within the required time, then the bid guaranty accompanying the bid shall be forfeited to the City.
SECTION 3. SCOPE AND INTENT OF CONTRACT
3-01. Effect of Inspection and Payments. Neither the inspection by the Engineer or an inspector, nor any order, measurement or approved modification, nor certificate or payment of money, nor acceptance of any part or whole of the work, nor any extension of time, nor any possession by the City or its agents, shall operate as a waiver of any provision of this contract or of any power reserved therein to the City, or of any right to damages thereunder; nor shall any breach of this contract be held to be a waiver of any subsequent breach. All remedies shall be construed as cumulative. 3-02. Effect of Extension of Time. The granting of any extension of time on account of delays which, in the judgement of the City, are avoidable delays shall in no way operate as a waiver on the part of the City of its rights under this contract. 3-03. Extra Work. If extra work orders are given in accordance with provisions of this contract, such work shall be considered a part hereof and shall be subject to each and all of its terms and requirements. 3-04. Assignment of Contract. The contract may be assigned or sublet in whole or in part only upon the written consent of the City acting through its authorized agents. Consent will not be given to any proposed assignment which would relieve the original contractor or its surety of their responsibilities under the contract nor will the Engineer consent to any assignment of a part of the work under the contract. 3-05. Subcontractors. The Contractor shall be as fully responsible for the acts and omissions of his or her subcontractors and of persons either directly or indirectly employed by them, as he or she is for the acts and omissions of persons directly employed by him.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
9 The Contractor shall cause appropriate provisions to be inserted in all subcontracts relative to the work to bind subcontractors to the terms of this Contract which are applicable to the work of subcontractors.
Nothing contained in this contract shall be construed to create or shall be relied upon to create any contractual relationship between any subcontractor and the City and no action may be brought by any subcontractor against the City based on this contract.
3-06. Interpretation of Special Provisions and Drawings. The Special Provisions and the Contract Drawings are intended to be explanatory of each other. Any work indicated in the Contract Drawings and not in the Special Provisions, or vice versa, is to be executed as if indicated in both. In case of a discrepancy or conflict between the Technical Specifications and Contract Plans, the Technical Specifications shall govern. All work shown on the Contract Drawings, the dimensions of which are not figured, shall be accurately followed to the scale to which the drawings are made, but figured dimensions are in all cases to be followed, where given, though they differ from scaled measurements. Large scale drawings shall be followed in preference to small scale drawings. Should it appear that the work to be done, or any of the matters relative thereto, are not sufficiently detailed or explained in these contract documents, including the contract drawings, the Contractor shall apply to the Engineer for such further explanations as may be necessary and shall conform thereto as part of this contract, so far as may be consistent with the terms of this contract. In the event of any doubt or questions arising respecting the true meaning of the Special Provisions, reference shall be made to the Engineer and his or her decision thereon shall be final. If the Contractor believes that a clarification or interpretation justifies an increase in the contract price or contract time, the Contractor must comply with the written notice provisions of Sections 9-05 and 10-07 of these Special Provisions. Contractor’s attention is directed to Section 12-06 of the Technical Specifications regarding the Standard Specifications and Standard Plans. 3-07. Addenda. If it becomes necessary to revise any part of these plans and specifications after they have been released, the City will issue an addendum containing the revision. All addenda will be posted on the City’s website at www.cityofukiah.com/purchasing with the rest of the bid documents. Anyone who intends to submit a bid in response to this Request for Bid must check the website frequently for any posted addenda. Anyone submitting a bid will be deemed to have seen and agreed to be bound by the posted addenda. 3-08. Liability of City Officials. No city official, nor the Engineer, nor any authorized assistant of any of them, shall be personally responsible for any liability arising under this contract. 3-09. Dispute Resolution. Claims of $375,000 or less by the Contractor that arise under this Contract are subject to the mandatory dispute resolutions provisions in Public Contract Code Sections 20104-20104.6.
SECTION 4. BONDS
4-01. Faithful Performance Bond. As a part of the execution of this contract, the Contractor shall furnish a bond of a surety company or other securities providing equivalent protection such as cash, letter of credit, or certificates of deposit, acceptable to the City, conditioned upon the faithful performance of all covenants and stipulations under this contract.
The amount of the bond shall be 100 percent of the total contract price, as this sum is set forth in the agreement. 4-02. Material and Labor Bond. As a part of the execution of this contract, the Contractor shall furnish a bond of a surety company or other securities providing equivalent protection such as cash, letter of credit or certificates of deposit acceptable to the City in a sum not less than 50 percent of the total contract price, as this sum is set forth in the agreement for the payment in full of all persons, companies or corporations who perform labor upon or furnish materials to be used in the work under this contract, in accordance with the provisions of Sections 3247 through 3252 inclusive of the Civil Code of the State of California and any acts amendatory thereof. 4-03. Defective Material and Workmanship Bond. As a condition precedent to the completion of this contract, the Contractor shall furnish a bond of a surety company acceptable to the City in an amount not less than 5 percent (5%) of the final contract price, to hold good for a period of one (1) year after the completion and acceptance of the work, to protect the City against the results of defective materials, workmanship and equipment during that time. This bond shall be delivered to the City before the final payment under this contract will be made. 4-04. Notification of Surety Companies. The surety companies shall familiarize themselves with all of the conditions and provisions of this contract and they waive the right of special notification of any change or modification of this contract or of extension of time, or decreased or increased work, or of the cancellation of the contract, or of any other act or acts
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
10 by the City or its authorized agents, under the terms of this contract; and failure to so notify the aforesaid surety companies of changes shall in no way relieve the surety companies of their obligation under this contract.
SECTION 5. INSURANCE REQUIREMENTS FOR CONTRACTORS
(WITH CONSTRUCTION RISKS)
Contractor shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the work hereunder by the Contractor, his or her agents, representatives, employees or subcontractors. 5-01. Minimum Scope of Insurance
Coverage shall be at least as broad as:
1. Insurance Services Office Commercial Liability Coverage (occurrence form CG 0001).
2. Insurance Services Office form number CA 0001 (Ed. 1/87) covering Automobile Liability, code 1 (any auto).
3. Worker's Compensation insurance as required by the State of California and Employer's Liability Insurance.
4. Course of Construction insurance covering for “all risks” of loss. 5-02. Minimum Limits of Insurance
Contractor shall maintain limits no less than:
1. General Liability: $2,000,000 per occurrence for bodily injury, personal injury and property damage including operations, products and completed operations. If Commercial General Liability Insurance or other form with a general aggregate limit is used, either the general aggregate limit shall apply separately to this project/location or the general aggregate limit shall be twice the required occurrence limit.
2. Automobile Liability: $2,000,000 per accident for bodily injury and property damage.
3. Employer's Liability: $1,000,000 per accident for bodily injury and property damage.
4. Course of Construction: Completed value of the project with no co-insurance penalty provisions. 5-03. Deductibles and Self-insured Retentions. Any deductibles or self-insured retentions must be declared to and approved by the City. At the option of the City, either: the insurer shall reduce or eliminate such deductibles or selfinsured retentions as respects the City, its officers, officials, employees and volunteers; or the Contractor shall provide a financial guarantee satisfactory to the City guaranteeing payment of losses and related investigations, claim administration and defense expenses.
5-04. Other Insurance Provisions
The general liability and automobile liability policies are to contain, or be endorsed to contain, the following provisions:
1. The City, its officers, officials, employees and volunteers are to be covered as Additional Insured with respect to liability arising out of automobiles owned, leased, hired or borrowed by or on behalf of the contractor; and with respect to liability arising out of work or operations performed by or on behalf of the Contractor including materials, parts or equipment furnished in connection with such work or operations. General liability coverage can be provided in the form of an endorsement to the Contractor's insurance, or as a separate owner's policy.
2. The workers’ compensation policy is to be endorsed with a waiver of subrogation. The insurance company, in its endorsement, agrees to waive all rights of subrogation against the City, its officers, officials, employees and volunteers for losses paid under the terms of this policy which arises from the work performed by the named insured for the City.
3. For any claims related to this project, the Contractor's insurance coverage shall be primary insurance as respects the City, its officers, officials, employees or volunteers. Any insurance or self-insurance maintained by the City,
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
11 its officers, officials, employees or volunteers shall be excess of the Contractor's insurance and shall not contribute with it.
4. Each insurance policy required by this clause shall be endorsed to state that coverage shall not be canceled by either party, except after thirty (30) days' prior written notice by certified mail, return receipt requested, has been given to the City.
5. Coverage shall not extend to any indemnity coverage for the active negligence of the additional insured in any case where an agreement to indemnify the additional insured would be invalid under Subdivision (b) of Section 2782 of Civil Code.
6. Course of Construction policies shall contain the following provisions:
a.) The City shall be named as loss payee.
b.) The insurer shall waive all rights of subrogation against the City. 5-05. Acceptability of Insurers
Insurance is to be placed with insurers with a current A.M. Best's rating of no less than the following:
A++ VII A- VIII
A+ VII B++ X
A VII B+ X
5-06. Verification of Coverage. Contractor shall furnish the City with original certificates and amendatory endorsements effecting coverage required by this clause. The endorsements shall be on forms provided by the City or on other than the City's forms, provided those endorsements or policies conform to the requirements. All certificates and endorsements are to be received within 15 days from written notice of contract award, and the work shall not commence until the certificates and endorsements have been approved by the City. The City reserves the right to require complete certified copies of all required insurance policies, including endorsements affecting the coverage required by these Special Provisions at any time.
5-07. Subcontractors. Contractor shall include all subcontractors as insureds under its policies or shall furnish separate certificates and endorsements for each subcontractor. All coverages for subcontractors shall be subject to all of the requirements stated herein.
SECTION 6. RESPONSIBILITIES AND RIGHTS OF CONTRACTOR
6-01. Legal Address of Contractor. Both the address given in the proposal and the Contractor's office in the vicinity of the work are hereby designated as places to either of which drawings, samples, notices, letters or other articles or communications to the Contractor may be mailed or delivered. The delivery at either of these places of any such thing from the City or its agents to the Contractor shall be deemed sufficient service thereof upon the Contractor and the date of such service shall be the date of such delivery. The address named in the proposal may be changed at any time by notice in writing from the Contractor to the City. Nothing herein contained shall be deemed to preclude or render inoperative the service of any drawing, sample, notice, letter or other article or communication to or upon the Contractor personally.
6-02. Office of Contractor at Site. During the performance of this contract, the Contractor shall maintain a suitable office at the site of the work which shall be the headquarters of a representative authorized to receive drawings and any such thing given to the said representatives or delivered at the Contractor's office at the site of work in his or her absence shall be deemed to have been given to the Contractor.
6-03. Attention to Work. The Contractor shall give his or her personal attention to and shall supervise the work to the end that it shall be prosecuted faithfully and when he or she is not personally present on the work, he or she shall at all reasonable times be represented by a competent superintendent or foreman who shall receive and obey all instructions or orders given under this contract and who shall have full authority to execute the same and to supply materials, tools and labor without delay and who shall be the legal representative of the Contractor. The Contractor shall be liable for the faithful observance of any instructions delivered to him or her or to his or her authorized representative.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
12 6-04. Liability of Contractor. The Contractor shall do all of the work and furnish all labor, materials, tools and appliances, except as otherwise herein expressly stipulated, necessary or proper for performing and completing the work herein required in the manner and within the time herein specified. The mention of any specific duty or liability imposed upon the Contractor shall not be construed as a limitation or restriction of any general liability or duty imposed upon the Contractor by this contract, said reference to any specific duty or liability being made herein merely for the purpose of explanation.
The right of general supervision by the City shall not make the Contractor an agent of the City and the liability of the Contractor for all damages to persons or to public or private property, arising from the Contractor's execution of the work, shall not be lessened because of such general supervision.
Until the completion and final acceptance by the City of all the work under and implied by this contract, the work shall be under the Contractor's responsible care and charge. The Contractor shall rebuild, repair, restore and make good all injuries, damages, re-erections and repairs, occasioned or rendered necessary by causes of any nature whatsoever, excepting only acts of God and none other, to all or any portions of the work, except as otherwise stipulated.
To the fullest extent permitted by law, Contractor shall indemnify and hold harmless the City and its officers, directors, agents and employees from and against all claims, damages, losses and expenses including but not limited to attorneys' fees, costs of suit, expert witness fees and expenses and fees and costs of any necessary private investigators arising out of or resulting from the performance of the work, provided that any such claim, damage, loss or expense (1) is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property, other than the work itself, including the loss of use resulting therefrom and (2) is caused in whole or in part by any act or omission of the Contractor, any subcontractor, or anyone directly or indirectly employed by any of them, or anyone for whose acts any of them may be liable, regardless of whether or not it is caused in part by a party indemnified hereunder, or by the negligence or omission of a party indemnified herein.
In any and all claims against the City or any of its agents or employees by any employee of the Contractor, any subcontractor, anyone directly or indirectly employed by any of them, or anyone for whose acts any of them may be liable, the indemnification obligation shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for the Contractor or any subcontractor under workers' or workmen's compensation acts, disability benefit acts, or other employee benefit acts. The obligation to indemnify shall extend to and include acts of the indemnified party which may be negligent or omissions which may cause negligence.
The City shall have the right to estimate the amount of such damage and to cause the City to pay the same and the amount so paid for such damage shall be deducted from the money due the Contractor under this contract; or the whole or so much of the money due or to become due the Contractor under this contract as may be considered necessary by the City, shall be retained by the City until such suits or claims for damages shall have been settled or otherwise disposed of and satisfactory evidence to that effect furnished to the City. 6-05. Protection of Persons and Property. The Contractor shall furnish such watchman, guards, fences, warning signs, walks and lights as shall be necessary and shall take all other necessary precautions to prevent damage or injury to persons or property.
All property line fences and improvements in the vicinity of the work shall be protected by the Contractor and, if they are injured or destroyed, they and any other property injured by the Contractor, his or her employees or agents, shall be restored to a condition as good as when he or she entered upon the work. 6-06. Protection of City Against Patent Claims. All fees, royalties or claims for any patented invention, article or method that may be used upon or in any manner connected with the work under this contract shall be included in the price bid for the work and the Contractor and his or her sureties shall protect and hold the City, together with all of its officers, agents, servants and employees, harmless against any and all demands made for such fees or claims brought or made on account of this contract. The Contractor shall, if requested by the Engineer, furnish acceptable proof of a proper release from all such fees or classes.
Should the Contractor, his or her agents, servants or employees, or any of them be enjoined from furnishing or using any invention, article, material or appliance supplied or required to be supplied or used under this contract, the Contractor shall promptly substitute other articles, materials or appliance, in lieu thereof, of equal efficiency, quality, finish, suitability and market value and satisfactory in all respects to the Engineer. Or, in the event that the Engineer elects, in lieu of such substitution, to have supplied and to retain and use, any such invention, article, material or appliance, as may by this
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
13 contract be required to be supplied, in that event the Contractor shall pay such royalties and secure such valid licenses as may be requisite and necessary for the City, its officers, agents, servants and employees, or any of them, to use such invention, article, material or appliance without being disturbed or in any way interfered with by any proceeding in law or equity on account thereof. Should the Contractor neglect or refuse to make the substitution promptly, or to pay such royalties and secure such licenses as may be necessary, then in that event the Engineer shall have the right to make such substitution, or the City may pay such royalties and secure such licenses and charge the cost thereof against any money due to the Contractor from the City or recover the amount thereof from him or her and his or her sureties notwithstanding final payment under this contract may have been made. 6-07. Protection of Contractor's Work Property. The Contractor shall protect his or her work, supplies and materials from damage due to the nature of the work, the action of the elements, trespassers, or any cause whatsoever under his or her control, until the completion and acceptance of the work. Neither the City nor any of its agents assumes any responsibility for collecting indemnity from any person or persons causing damage to the work of the Contractor. 6-08. Regulations and Permits. The Contractor shall secure and pay for all permits, give all notices and comply with all laws, ordinances, rules and regulations bearing on the conduct of the work as drawn and specified. If the Contractor observes that the Plans and Special Provisions are at variance therewith, he or she shall promptly notify the Engineer in writing and any necessary changes shall be adjusted as provided in the contract for changes in the work. The contractor and any subcontractors shall each secure and maintain a valid City of Ukiah Business License. The City of Ukiah will issue a no fee encroachment permit to the Contractor allowing him or her to perform work within City right of way or within City property after the Contract Documents have been executed and insurance certificates and endorsements have been approved by the City.
6-09. Construction Utilities. The Contractor shall be responsible for providing for and in behalf of his or her work under this contract, all necessary utilities, such as special connection to water supply, telephones, power lines, fences, roads, watchmen, suitable storage places, etc.
6-10. Approval of Contractor's Plans. The approval by the Engineer of any drawing or any method of work proposed by the Contractor in accordance with paragraph 8-06 shall not relieve the Contractor of any of his or her responsibility for his or her errors therein and shall not be regarded as any assumption of risk or liability by the City or any officer or employee thereof and the Contractor shall have no claim under this contract on account of the failure or partial failure or inefficiency of any plan or method so approved. Such approval shall be considered to mean merely that the Engineer has no objection to the Contractor's using, upon his or her own full responsibility the plan or method approved. 6-11. Suggestions to the Contractor. Any plan or method of work suggested by the Engineer to the Contractor, but not specified or required, if adopted or followed by the Contractor in whole or in part, shall be used at the risk and responsibility of the Contractor; and the Engineer and the City shall assume no responsibility thereof. 6-12. Termination of Unsatisfactory Subcontracts. Should any subcontractor fail to perform in a satisfactory manner the work undertaken by him, such subcontract shall be terminated immediately by the Contractor upon notice from the Engineer.
6-13. Preservation of Stakes and Marks. The Contractor shall preserve carefully bench marks, reference points and stakes and in case of destruction he or she shall replace his or her stakes, reference points and bench marks and shall be responsible for any mistakes that may be caused by their unnecessary loss or disturbance. Contractor’s attention is directed to Section 7-03 of these Special Provisions.
6-14. Assistance to Engineer. At the request of the Engineer the Contractor shall provide men from his or her force and tools, stakes and other materials to assist the Engineer temporarily in making measurements and surveys and in establishing temporary or permanent reference marks. Payment for such materials and assistance will be made as provided for under the caption "Extra Work," provided, however, that the cost of setting stakes and marks carelessly lost or destroyed by the Contractor's employees will be assessed to the Contractor. 6-15. Removal of Condemned Materials and Structures. The Contractor shall remove from the site of the work, without delay, all rejected and condemned materials or structures of any kind brought to or incorporated in the work and upon his or her failure to do so, or to make satisfactory progress in so doing, within forty-eight (48) hours after the service of a written notice from the Engineer, the condemned material or work may be removed by the City and the cost of such removal shall be taken out of the money that may be due or may become due the Contractor on account of or by virtue
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
14 of this contract. No such rejected or condemned material shall again be offered for use by the Contractor under this Contract.
6-16. Proof of Compliance with Contract. In order that the Engineer may determine whether the Contractor has complied with the requirements of this contract, not readily enforceable through inspection and tests of the work and materials, the Contractor shall, at any time when requested, submit to the Engineer properly authenticated documents or other satisfactory proofs as to his or her compliance with such requirements. 6-17. Errors and Omissions. If the Contractor, in the course of the work, finds any errors or omissions in plans or in the layout as given by survey points and instruction, or if he or she finds any discrepancy between the plans and the physical conditions of the locality, he or she shall immediately inform the Engineer, in writing and the Engineer shall promptly verify the same. Any work done after such discovery, until authorized, will be done at the Contractor's risk. 6-18. Cooperation. The Contractor shall cooperate with all other contractors who may be performing work in behalf of the City and workmen who may be employed by the City on any work in the vicinity of the work to be done under this contract with the work of such contractors or workmen. he or she shall make good promptly, at his or her own expense, any injury or damage that may be sustained by other contractors or employees of the City at his or her hands.
Any difference or conflict which may arise between the Contractor and other contractors, or between the contractor and workmen of the City in regard to their work shall be adjusted and determined by the Engineer. If the work of the Contractor is delayed because of any acts or omissions of any other contractor or of the City, the Contractor shall on that account have no claim against the City other than for an extension of time. 6-19. Right of Contractor to Stop Work. Under the following conditions the Contractor shall have the right, if he or she so desires, to stop the work and terminate the contract upon ten (10) days written notice to the Engineer and recover from the City payment for all work actually performed and for all satisfactory materials actually delivered to the site of the work for permanent incorporation therein, all as may be shown by the estimate of the Engineer. (1) If the work is stopped under an order of any court or other competent public authority for a period of time of three (3) months through no act or fault of the Contractor or of anyone employed by him. (2) If the Engineer fails to issue the monthly certificate for payment in accordance with the terms of this contract.
(3) If the City fails to pay the Contractor within sixty (60) days after it shall have become due, as provided by the terms of this contract, any sum certified by the Engineer or awarded by the City.
All provided that if such action to terminate the contract be not instituted by the Contractor within ten (10) days after the alleged existence of such condition and if written notice of such action be not at that time delivered to the City and the Engineer, then such right shall lapse until another occasion arises according to this section. 6-20. Hiring and Dismissal of Employees. The Contractor shall employ only such foremen, mechanics and laborers as are competent and skilled in their respective lines of work and whenever the Engineer shall notify the Contractor that any person on the work is, in his or her opinion, incompetent, unfaithful, intemperate or disorderly, or refuses to carry out the provisions of this contract, or uses threatening or abusive language to any person on the work representing the City, or is otherwise unsatisfactory, such person shall be discharged immediately from the work and shall not be reemployed upon it except with the consent of the Engineer. 6-21. Wage Rates.
1. Contractor shall pay all mechanics and laborers employed or working upon the site of the work unconditionally and without subsequent deductions or rebate on any account the full amounts due at the time of payment at wage rates not less than those contained in the applicable prevailing wage determination, regardless of any contractual relationship which may be alleged to exist between the Contractor and subcontractors and such laborers and mechanics.
2. Contractor shall comply with the California Labor Code Section 1775. In accordance with said Section 1775, Contractor shall forfeit as a penalty to the Owner, $50.00 (or the higher minimum penalty as provided in Section 1775(B)(ii) – (iii)) for each calendar day or portion thereof, for each workman paid less than the stipulated
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
15 prevailing rates for such work or craft in which such workman is employed for any work done under the Contract by him or her or by any subcontractor under him or her in violation of the provisions of the Labor Code and in particular, Labor Code Sections 1770 to 1780, inclusive. In addition to said penalty and pursuant to Section 1775, the difference between such stipulated prevailing wage rates and the amount paid to each workman for each calendar day or portion thereof for which each workman was paid less than the stipulated prevailing wage rate shall be paid to each workman by the Contractor.
3. Pursuant to the provision of Section 1770 of the Labor Code of the State of California, Owner has ascertained the general prevailing rate of wages (which rate includes employer payments for health and welfare, vacation, pension and similar purposes) applicable to the work to be done, for straight time work. The holiday wage rate listed shall be applicable to all holidays recognized in the collective bargaining agreement of the particular craft, classification or type of workmen concerned. Copies of the General Prevailing Wage Determination are available on the Internet at web address: http://www.dir.ca.gov/DLSR/PWD The Contractor shall post the wage determination at the site of work in a prominent place where it can easily be seen by the workers.
4. City will not recognize any claim for additional compensation because the Contractor has paid any rate in excess of the prevailing wage rate obtained by the Contractor. The possibility of wage increases is one of the elements to be considered by the Contractor in determining his or her bid and will not in any circumstances be considered as the basis for a claim against the City.
5. The Labor Commissioner through the Division of Labor Standards Enforcement (DLSE) may at any time require contractors and subcontractors to furnish electronic certified payroll records directly to DLSE. Commencing with contracts awarded or after April 1, 2015, all contractors and subcontractors must furnish electronic certified payroll records directly to the DLSE.
6. Travel and Subsistence Payments.
Contractor shall make travel and subsistence payments to each workman needed to execute the work in accordance with the requirements in Section 1773.8 of the Labor Code (Chapter 880, Statutes of 1968).
7. Apprentices.
Attention is directed to the provisions in Sections 1777.5 (Chapter 1411, Statutes of 1968) and 1777.6 of the California Labor Code concerning the employment of apprentices by the Contractor or any subcontractor under him. Contractor and any subcontractor under him or her shall comply with the requirements of said sections in the employment of apprentices.
Information relative to apprenticeship standards, wage schedules and other requirements may be obtained from the Director of Industrial Relations, ex officio the Administrator of Apprenticeship, San Francisco, California, or from the Division of Apprenticeship Standards and its branch offices. 6-22. Cleaning Up. The Contractor shall not allow the site of the work to become littered with trash and waste material, but shall maintain the same in a neat and orderly condition throughout the construction period. The Engineer shall have the right to determine what is or is not waste material or rubbish and the place and manner of disposal.
On or before the completion of the work, the Contractor shall without charge therefore carefully clean out all pits, pipes, chambers or conduits and shall tear down and remove all temporary structures built by him or her and shall remove rubbish of all kind from any of the grounds which he or she has occupied and leave them in first class condition. 6-23. Guaranty. All work shall be guarantied for a period of one year from the date of acceptance by the City. The Contractor shall promptly make all needed repairs arising out of defective materials, workmanship and equipment.
The City is hereby authorized to make such repairs if within ten days after the mailing of a notice in writing to the Contractor or his or her agent, the Contractor shall neglect to make or undertake with due diligence the aforesaid repairs, provided, however, that in case of an emergency where, in the opinion of the City delay would cause serious loss or damage, repairs may be made without notice being sent to the Contractor and the Contractor shall pay the costs thereof.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
16 Pursuant to the provisions of Section 4-03 of these Special Provisions, the Contractor shall furnish a Defective Material and Workmanship Bond in an amount not less than 5 percent of the final contract price, which shall be effective for a period of one (1) year after the completion and acceptance of the work. 6-24. Public Notification. The contractor shall be responsible for all public notification regarding construction work within the subject intersection, including detours, lane and street closures, hours of operations, and notification of effected commercial businesses within 1000 feet of the construction. For any business impacted by construction, the contractor shall provide adequate sized on-site signage indicating that businesses are open during construction for pedestrian traffic. The contractor shall prepare public noticing via the newspaper, radio announcements, notification of the emergency vehicle agencies, public transit, school buses, County of Mendocino offices, the high school, junior high school, elementary schools effected by potential detours and street closures, with recommended alternate routes of travel. Through street access from will be restricted to businesses and residents only during construction days. All proposed detours, closures and traffic control methods shall be submitted to the Engineer for approval prior to noticing the public. All public noticing shall be performed a minimum of one week prior to instituting traffic control, and lane or street closures.
The tentative construction schedule shall be included in the public noticing, and the use of temporary traffic signalization of the intersection shall be noted All road closures, detour routes, and traffic control including temporary lane closure plans shall be submitted by the Contractor to the City Engineer for approval prior to public noticing and use.
SECTION 7. RESPONSIBILITIES AND RIGHTS OF CITY
7-01. Authority of the Engineer. All work done under this contract shall be done in a workmanlike manner and shall be performed to the reasonable satisfaction of the Engineer, who shall have general supervision of all work included hereunder. To prevent disputes and litigation, the Engineer (1) shall in all cases determine the amount, quality, acceptability and fitness of the several kinds of work and materials which are to be paid for under this contract, (2) shall decide all questions relative to the true construction, meaning and intent of the Special Provisions and Drawings, (3) shall decide all questions which may arise relative to the classifications and measurements of quantities and materials and the fulfillment of this contract and (4) shall have the power to reject or condemn all work or material which does not conform to the terms of this contract. his or her estimate and decision in all matters shall be a condition precedent to an appeal for arbitration, or the right of the Contractor to receive, demand, or claim any money or other compensation under this agreement and a condition precedent to any liability on the part of the City to the Contractor on account of this contract. Whenever the Engineer shall be unable to act, in consequence of absence or other cause, then such engineer as the Engineer or the City shall designate, shall perform any and all of the duties and be vested with any or all of the powers herein given to the Engineer.
7-02. Inspection. The City will provide engineering personnel for the inspection of the work.
The Engineer and his or her representatives shall at all times have access to the work whenever it is in preparation or progress and the Contractor shall provide proper facilities for such access and inspection.
If the Special Provisions, the Engineer's instruction, laws, ordinances, or any public authority require any work to be specially tested or approved, the Contractor shall give the Engineer timely notice of its readiness for inspection and, if the inspection is by an authority other than the Engineer, of the date fixed for such inspection. Inspections by the Engineer shall be promptly made at the source of supply where practicable. If any work shall be covered up without approval or consent of the Engineer, it must, if required by the Engineer, be uncovered for examination and properly restored at the Contractor's expense.
Re-examination of any work may be ordered by the Engineer and, if so ordered, the work must be uncovered by the Contractor. If such work is found to be in accordance with the contract documents, the City shall pay the cost of reexamination and replacement. If such work is not in accordance with the contract documents, the Contractor shall pay such cost.
Properly authorized and accredited inspectors shall be considered to be the representatives of the City limited to the duties and powers entrusted to them. It will be their duty to inspect materials and workmanship of those portions of the work to which they are assigned, either individually or collectively, under instructions of the Engineer and to report any and all deviations from the Drawings, Special Provisions and other contract provisions which may come to their notice.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
17 Any inspector may be considered to have the right to order the work entrusted to his or her supervision stopped, if in his or her opinion such action becomes necessary, until the Engineer is notified and has determined and ordered that the work may proceed in due fulfillment of all contract requirements. 7-03. Surveys. Contractor shall furnish all land surveys, establish all base lines and bench marks and make sufficient detailed surveys needed for working points, lines and elevations. The Contractor shall develop all slope stakes and batter boards. Contractor shall also develop all additional working points, lines and elevations as he or she may desire to facilitate his or her methods and sequence of construction. 7-04. Rights-of-Way. The City will provide all necessary rights-of-way and easements in or beneath which work will be performed by the Contractor under this contract.
7-05. Retention of Imperfect Work. If any portion of the work done or material furnished under this contract shall prove defective and not in accordance with the Plans and Special Provisions, and if the imperfection in the same shall not be of sufficient magnitude or importance to make the work dangerous or undesirable, the Engineer shall have the right and authority to retain such work instead of requiring the imperfect work to be removed and reconstructed, but he or she shall make such deductions therefor in the payments due or to become due the Contractor as may be just and reasonable.
7-06. Changes in the Work. The Engineer shall have the right, in writing, to order additions to, omissions from, or corrections, alterations and modifications in the line, grade, form, dimensions, plan, or kind or amount of work or materials herein contemplated, or any part thereof, either before or after the beginning of construction. However, the arithmetical sum of the cost to the City of additions and subtractions from the work under this contract shall not exceed 10 percent of original contract amount or $5,000, whichever is the greater, unless based upon a supplementary agreement to be made therefore.
The order of such additions, omissions, corrections, alterations and modifications shall be in writing and signed by the Engineer and, in order, shall then be binding upon the Contractor. The Contractor shall proceed with the work as changed and the value of such change shall be determined as provided for in section 10-07 of these Special Provisions.
Such alterations shall in no way affect, vitiate, or make void this contract or any part thereof, except that which is necessarily affected by such alterations and is clearly the evident intention of the parties to this contract. 7-07. Additional Drawings by City. The drawings made a part of this contract at the time of its execution are intended to be fairly comprehensive and to indicate in more or less detail the scope of the work. In addition to these drawings, however, the Engineer shall furnish such additional drawings from time to time during the progress of the work as are necessary to make clear or to define in greater detail the intent of the Special Provisions and the contract drawings and the Contractor shall make his or her work conform to all such drawings. 7-08. Additional and Emergency Protection. Whenever, in the opinion of the Engineer, the Contractor has not taken sufficient precautions for the safety of the public or the protection of the works to be constructed under this contract, or of adjacent structures or property which may be injured by the processes of construction on account of such neglect and whenever, in the opinion of the Engineer, an emergency shall arise and immediate action shall be considered necessary in order to protect public or private, personal or property interest, then and in that event, the Engineer, with or without notice to the Contractor may provide suitable protection to the said interests by causing such work to be done and such material to be furnished as shall provide such protection as the Engineer may consider necessary and adequate.
The cost and expense of such work and material so furnished shall be borne by the Contractor and, if the same shall not be paid on presentation of the bills therefor, then such costs shall be deducted from any amounts due or to become due the Contractor.
The performance of such emergency work under the direction of the Engineer shall in no way relieve the Contractor from any damages which may occur during or after such precaution has been taken by the Engineer. 7-09. Suspension of Work. The City may at any time suspend the work or any part thereof by giving five (5) days written notice to the Contractor. The work shall be resumed by the Contractor within ten (10) days after the date fixed in the written notice from the City to the Contractor so to do. The City shall reimburse the Contractor for expense incurred by the Contractor in connection with the work under this contract as a result of such suspension.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
18 If the work, or any part thereof, shall be stopped by the notice in writing aforesaid and if the City does not give notice in writing to the Contractor to resume work at a date within ten (10) days of the date fixed in the written notice to suspend, then the Contractor may abandon that portion of the work so suspended and he or she will be entitled to the estimates and payments for all work done on the portions so abandoned, if any, plus 5 percent of the value of the work so abandoned, to compensate for loss of overhead, plant expense and anticipated profit. 7-10. Right of City to Terminate Contract. If the Contractor should be adjudged a bankrupt, or if he or she should make a general assignment for the benefit of his or her creditors, or if a receiver should be appointed on account of his or her insolvency, or if he or she should persistently or repeatedly refuse or should fail, except in cases for which extension of time is provided, to supply sufficient properly skilled workmen or proper materials, or if he or she should fail to make prompt payments to subcontractors or for material or labor, or persistently disregard laws, ordinances or the instructions of the Engineer, or otherwise be guilty of a substantial violation of any provision of the contract, then the City, upon the certificate of the Engineer that sufficient cause exists to justify such action, may, without prejudice to any other right or remedy and after giving the Contractor seven days written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances and finish the work by whatever method the City may deem expedient. In such case, the Contractor shall not be entitled to receive any further payment until the work is finished. If the unpaid balance of the contract price shall exceed the expense of finishing the work, including compensation for additional managerial and administrative services, such excess shall be paid to the Contractor. If such expense shall exceed such unpaid balance, the Contractor shall pay the difference to the City. The expense incurred by the City as herein provided and the damage incurred through the Contractor's default, shall be certified by the Engineer.
7-11. Use of Completed Portions. The City shall have the right to take possession of and use any completed or partially completed portions of the work, notwithstanding the time for completing the entire work or such portions which may not have expired; but such taking possession and using shall not be deemed an acceptance of any work not completed in accordance with the contract documents. If such prior use increases the cost of or delays the work, the Contractor shall be entitled to such extra compensation, or extension of time or both, as the Engineer may determine.
SECTION 8. WORKMANSHIP, MATERIALS and EQUIPMENT
8-01. General Quality. Materials and equipment shall be new and of a quality equal to that specified or approved. Work shall be done and completed in a thorough and workmanlike manner. 8-02. Quality in Absence of Detailed Specifications. Whenever under this contract it is provided that the Contractor shall furnish materials or manufactured articles or shall do work for which no detailed specifications are set forth, the materials or manufactured articles shall be of the best grade in quality and workmanship obtainable in the market from firms of established good reputation, or, if not ordinarily carried in stock, shall conform to the usual standards for firstclass materials or articles of the kind required, with due consideration of the use to which they are to be put. In general, the work performed shall be in full conformity and harmony with the intent to secure the best standard of construction and equipment of the work as a whole or in part.
8-03. Materials and Equipment Specified by Name. Whenever any material or equipment is indicated or specified by patent or proprietary name or by the name of the manufacturer, such specification shall be considered as used for the purpose of describing the material or equipment desired and shall be considered as followed by the words "or approved equal". The Contractor may offer any material or equipment which shall be equal in every respect to that specified, provided that written approval first is obtained from the Engineer. 8-04. Source of Materials. Price, fitness and quality being equal, preference shall be given by the Contractor for supplies grown, manufactured or produced in the State of California and, next, for such products partially produced in this State in accordance with Government Code Section 4332. 8-05. Storage of Materials. Materials shall be so stored to ensure the preservation of their quality and fitness for the work. They shall be so located and disposed that prompt and proper inspection thereof may be made. 8-06. Drawings, Samples and Tests. As soon as possible after execution of the contract, the Contractor shall submit to the Engineer, in quintuplicate, sufficient information including, if necessary, assembly and detail drawings to demonstrate fully that the equipment and materials to be furnished comply with the provisions and intent of these Special Provisions and Drawings. If the information thus submitted indicates the equipment or materials is acceptable, the
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
19 Engineer will return one copy stamped with his or her approval; otherwise, one copy will be returned with an explanation of why the equipment or material is unsatisfactory. The Contractor shall have no claims for damages or for extension of time on account of any delay due to the revision of drawings or rejection of material. Fabrication or other work performed in advance of approval shall be done entirely at the Contractor's risk. After approval of equipment or material, the Contractor shall not deviate in any way from the design and specifications given without the written consent of the Engineer.
When requested by the Engineer, a sample or test specimens of the materials to be used or offered for use in connection with the work shall be prepared at the expense of the Contractor and furnished by him or her in such quantities and sizes as may be required for proper examination and tests, with all freight charges prepaid and with information as to their sources.
All samples shall be submitted before shipment and in ample time to permit the making of proper tests, analyses, or examination before the time at which it is desired to incorporate the material into the work. All tests of materials furnished by the Contractor shall be made by the Engineer. Samples shall be secured and tested whenever necessary to determine the quality of the material.
SECTION 9. PROSECUTION OF WORK
9-01. Equipment and Methods. The work under this contract shall be prosecuted with all materials, tools, machinery, apparatus and labor and by such methods as are necessary to the complete execution of everything described, shown, or reasonably implied. If at any time before the beginning or during the progress of the work, any part of the Contractor's plant or equipment, or any of his or her methods of execution of the work, appear to the Engineer to be unsafe, inefficient, or inadequate to insure the required quality or the rate of progress of the work, he or she may order the Contractor to increase or improve his or her facilities or methods and the Contractor shall comply promptly with such orders; but, neither compliance with such orders nor failure of the Engineer to issue such orders shall relieve the Contractor from his or her obligation to secure the degree of safety, the quality of the work and the rate of progress required of the Contractor.
The Contractor alone shall be responsible for the safety, adequacy and efficiency of his or her plant, equipment and methods.
9-02. Time of Completion. The Contractor shall promptly begin the work under this contract and shall complete and make ready for full use all portions of the project made the subject of this contract within the time set forth in the agreement bound herewith.
9-03. Avoidable Delays. Avoidable delays in the prosecution or completion of the work shall include all delays which might have been avoided by the exercise of care, prudence, foresight and diligence on the part of the Contractor. The City will consider as avoidable delays within the meaning of this contract (1) delays in the prosecution of parts of the work, which may in themselves be unavoidable, but do not necessarily prevent or delay the prosecution of other parts of the work nor the completion of the whole work within the time herein specified, (2) reasonable loss of time resulting from the necessity of submitting plans to the Engineer for approval and from the making of surveys, measurements, inspections, and testing and (3) such interruptions as may occur in the prosecution of the work on account of the reasonable interference of other contractors employed by the City which do not necessarily prevent the completion of the whole work within the time herein specified.
9-04. Unavoidable Delays. Unavoidable delays in the prosecution or completion of the work under this contract shall include all delays which may result, through cause beyond the control of the Contractor and which he or she could not have provided against by the exercise of care, prudence, foresight and diligence. Orders issued by the City changing the amount of work to be done, the quantity of material to be furnished or the manner in which the work is to be prosecuted and unforeseen delays in the completion of the work of other contractors under contract with the City will be considered unavoidable delays, so far as they necessarily interfere with the Contractor's completion of the whole of the work. Delays due to normally adverse weather conditions will not be regarded as unavoidable delays. However, truly abnormal amounts of rainfall, temperatures or other weather conditions for the location of the work and time of year may be considered as unavoidable delays if those conditions necessarily cause a delay in the completion of the work. 9-05. Notice of Delays. Whenever the Contractor foresees any delay in the prosecution of the work and, in any event, immediately upon the occurrence of any delay which the contractor regards as an unavoidable delay, he or she shall notify the Engineer in writing of the probability of the occurrence of such delay and its cause, in order that the Engineer may take immediate steps to prevent, if possible, the occurrence or continuance of the delay, or, if this cannot be done,
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
20 may determine whether the delay is to be considered avoidable or unavoidable, how long it continues and to what extent the prosecution and completion of the work are to be delayed thereby. 9-06. Extension of Time. Should any delays occur which the Engineer may consider unavoidable, as herein defined, the Contractor shall, pursuant to his or her application, be allowed an extension of time proportional to said delay or delays, beyond the time herein set forth, in which to complete this contract; and liquidated damages for delay shall not be charged against the Contractor by the City during an extension of time granted because of unavoidable delay or delays.
Any claim by Contractor for a time extension based on unavoidable delays shall be based on written notice delivered to the Engineer within 15 days of the occurrence of the event giving rise to the claim. Failure to file said written notice within the time specified shall constitute a waiver of said claim. Notice of the full extent of the claim and all supporting data must be delivered to the Engineer within 45 days of the occurrence unless the Engineer specifies in writing a longer period. All claims for a time extension must be approved by the Engineer and incorporated into a written change order. 9-07. Unfavorable Weather and Other Conditions. During unfavorable weather and other conditions, the Contractor shall pursue only such portions of the work as shall not be damaged thereby. No portions of the work whose satisfactory quality or efficiency will be affected by any unfavorable conditions shall be constructed while these conditions remain, unless, by special means or precautions approved by the Engineer, the Contractor shall be able to overcome them.
The Contractor shall be granted a time extension of one day for each unfavorable weather day which prevents him or her from placing concrete forms or placing and finishing concrete or asphalt concrete. Such unfavorable weather day is defined as a rain day where precipitation prevents the contractor from performing the work more than four (4) continuous hours within the authorized work period or a temperature day where the ambient temperature is below that specified for the placement of materials associated with the controlling work item for more than four (4) continuous work hours of the authorized work period.
9-08. Saturday, Sunday, Holiday and Night Work. No work shall be done between the hours of 6 p.m. and 7 a.m., nor on Saturdays, Sundays or legal holidays except such work as is necessary for the proper care and protection of work already performed, or except in cases of absolute necessity and in any case only with the permission of the Engineer.
It is understood, however, that night work may be established as a regular procedure by the Contractor if he or she first obtains the written permission of the Engineer and that such permission may be revoked at any time by the Engineer if the Contractor fails to maintain at night adequate force and equipment for reasonable prosecution and to justify inspection of the work.
9-09. Hours of Labor. Eight (8) hours of labor shall constitute a legal day's work and the Contractor or any subcontractor shall not require or permit more than eight hours of labor in a day from any person employed by him or her in the performance of the work under this contract, unless paying compensation for all hours worked in excess of eight (8) hours per day at not less than 1½ times the basic rate of pay. The Contractor shall forfeit to the City, as a penalty, the sum of twenty-five dollars ($25.00) for each workman employed in the execution of the contract by him or her or by any subcontractor, for each calendar day during which such laborer, workman, or mechanic is required or permitted to labor more than eight hours in violation of the provisions of Section 1810 to 1816, inclusive, (Article 3, Chapter 1, Part 7, Division 2) of the Labor Code of the State of California and any acts amendatory thereof.
SECTION 10. PAYMENT
10-01. Certification by Engineer. All payments under this contract shall be made upon the presentation of certificates in writing from the Engineer and shall show that the work covered by the payments has been done and the payments thereof are due in accordance with this contract.
10-02. Progress Estimates and Payment. The Engineer shall, within the first seven (7) days of each month, make an estimate of the value of the work performed in accordance with this contract during the previous calendar month.
The first estimate shall be of the value of the work satisfactorily completed in place and meeting the requirements of the contract. And every subsequent estimate, except the final estimate, shall be of the value of the work satisfactorily completed in place since the last preceding estimate was made; provided, however, that should the Contractor fail to adhere to the program of completion fixed in this contract, the Engineer shall deduct from the next and all subsequent
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
21 estimates the full calculated accruing amount of the liquidated damages to the date of said estimate, until such time as the compliance with the program has been restored.
The estimate shall be signed by the Engineer and, after approval, the City shall pay or cause to be paid to the Contractor in the manner provided by law, an amount equal to 95 percent of the estimated value of the work satisfactorily performed and complete in place.
10-03. Substitution of Securities.
1. At such times that Pubic Contract Code Section 22300 is in effect Contractor may propose the substitution of securities of at least equal market value for any moneys to be withheld to ensure performance under the Contract. Market value shall be determined as of the day prior to the date such substitution is to take place. Such substitution shall be made at the request and expense of the Contractor. The securities shall be one or more of the following types:
(a) Bonds or interest-bearing notes or obligations of the United States, or those for which the faith and credit of the United States are pledged for the payment of principal and interest. (b) Bonds or interest-bearing notes on obligations that are guaranteed as to principal and interest by a federal agency of the United States.
(c) Bonds of the State of California, or those for which the faith and credit of the State of California are pledged for the payment of principal and interest.
(d) Bonds or warrants, including, but not limited to, revenue warrants, of any county, city, metropolitan water district, California water district, California water storage district, irrigation district in the State of California, municipal utility district, or school district of the State of California, which are rated by Moody's or Standard and Poor as A or better.
(e) Bonds, consolidated bonds, collateral trust debentures, consolidated debentures, or other obligations issued by federal land banks or federal intermediate credit banks established under the Federal Farm Loan Act, as amended; debentures and consolidated debentures issued by the Central Bank for Cooperatives and banks for cooperatives established under the Farm Credit Act of 1933, as amended; bonds, or debentures of the Federal Home Loan Bank Board established under the Federal Home Loan Bank Act; and stock, bonds, debentures and other obligations of the Federal National Mortgage Association established under the National Housing Act as amended and bonds of any Federal Home Loan Mortgage Corporation. (f) Commercial paper of "prime" quality as defined by a nationally recognized organization which rates such securities. Eligible paper is further limited to issuing corporations: (1) organized and operating within the United States; (2) having total assets in excess of five hundred million dollars ($500,000,000); and (3) approved by the Pooled Money Investment Board of the State of California. Purchases of eligible commercial paper may not exceed 180 days' maturity, nor represent more than 10 percent of the outstanding paper of an issuing corporation.
(g) Bills of exchange or time drafts on and accepted by a commercial bank, otherwise known as bankers acceptances, which are eligible for purchase by the Federal Reserve System. (h) Certificates of deposits issued by a nationally or state-chartered bank or savings and loan association. (i) The portion of bank loans and obligations guaranteed by the United States Small Business Administration or the United States Farmers Home Administration.
(j) Student loan notes insured under the Guaranteed Student Loan Program established pursuant to the Higher Education Act of 1965, as amended (20 U.S.C. 1001, et seq.) and eligible for resale to the Student Loan Marketing Association established pursuant to Section 133 of the Education Amendments of 1972, as amended (20 U.S.C. 1087-2).
(k) Obligations issued, assumed or guaranteed by International Bank for Reconstruction and Development, the Inter-American Development Bank, the Asian Development Bank, or the Government Development Bank of Puerto Rico.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
22 (l) Bonds, debentures and notes issued by corporations organized and operating within the United States. Such securities eligible for substitution shall be within the top three ratings of a nationally recognized rating service.
2. The securities shall be deposited with City or with any commercial bank as escrow agent, who shall arrange for transfer of such securities to the Contractor upon satisfactory completion of the contract. Any interest accrued or paid on such securities shall belong to the Contractor and shall be paid upon satisfactory completion of the contract.
The market value of the securities deposited shall at all times be maintained in an amount at least equal, in the sole judgment of City, to the moneys to be withheld pursuant to the Contract Documents to ensure performance of the Contract. In order to comply with this condition, Contractor shall deposit additional securities as necessary upon request by City or the escrow agent.
3. Upon acceptance of any Proposal that includes substituting securities for amounts withheld to ensure performance, a separate escrow agreement satisfactory in form and substance to City shall be prepared and executed by City, the Contractor and the escrow agent, which may be City. The escrow agreement shall specify, among other matters, value of securities to be deposited; procedures for valuing the securities and for adding or withdrawing securities to maintain the market value of the deposited securities at least equal to the amount of moneys which would otherwise be withheld; the terms and conditions of conversion to cash in case of the default by the Contractor; and terms, conditions and procedure for termination of the escrow. City shall have no obligation to enter any such Agreement that does not provide the City with the unilateral right to convert securities to cash and to gain immediate possession of the cash. 10-04. Acceptance. The work must be accepted by vote of the City Council of the City of Ukiah when the whole shall have been completed satisfactorily. The Contractor shall notify the Engineer, in writing, of the completion of the work, whereupon the Engineer shall promptly, by personal inspection, satisfy himself as to the actual completion of the work in accordance with the terms of the contract and shall thereupon recommend acceptance by the City Council. 10-05. Final Estimate and Payment. The Engineer shall, as soon as practicable after the final acceptance of the work done under this contract, make a final estimate of the amount of work done thereunder and the value thereof.
Such final estimate shall be signed by the Engineer, and after approval, the City shall pay or cause to be paid to the Contractor, in the manner provided by law, the entire sum so found to be due hereunder, after deducting therefrom all previous payments and such other lawful amounts as the terms of this contract prescribe.
In no case will final payment be made in less than thirty-five (35) days after the filing of the notice of completion with the County Recorder.
10-06. Delay Payments. Should any payment due the Contractor or any estimate be delayed, through fault of the City beyond the time stipulated, such delay shall not constitute a breach of contract or be the basis for a claim for damages, but the City shall pay the Contractor interest on the amount of the payment at the rate of 6 percent per annum for the period of such delay. The terms for which interest will be paid shall be reckoned, in the case of any monthly or progress payment, from the twentieth day of the month next succeeding the month in which the work was performed to the date of payment of the estimate; and in the case of the final estimate, from the forty-fifth day after acceptance to the date of payment of the final estimate.
The date of payment of any estimate shall be considered the day on which the payment is offered or mailed as evidenced by the records of the Treasurer of the City. If interest shall become due on any delayed payment, the amount thereof, as determined by the City, shall be added to a succeeding payment. If the interest shall become due on the final payment, it shall be paid on a supplementary voucher to interest or any sum or sums which, by the terms of this contract, the City is authorized to reserve or retain.
10-07. Extra Work and Work Omitted. Whenever corrections, alterations, or modifications of the work under this contract ordered by the Engineer and approved by the City increase the amount of work to be done, such added work shall be known as "extra work"; and when such corrections, alterations, or modifications decrease the amount of work to be done, such subtracted work shall be known as "work omitted".
When the Contractor considers that any changes ordered involve extra work, he or she shall immediately notify the Engineer in writing and subsequently keep him or her informed as to when and where extra work is to be performed and shall make claim for compensation therefor each month not later than the first day of the month following that in which
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
23 the work claimed to be extra work was performed and he or she shall submit a daily complete statement of materials and labor used and expenses incurred on account of extra work performed, showing allocation of all materials, labor and expenses.
All such claims shall state the date of the Engineer's written order and the date of approval by the City authorizing the work on account of which claim is made. Unless such notification is made in writing within the time specified and unless complete statements of materials used and expenses incurred on account of such extra work are furnished as above required, the Contractor shall not be entitled to payment on account of extra work and Contractor shall be deemed to have waived the right to make any future claims for compensation for such extra work.
When changes decrease the amount of work to be done, they shall not constitute a claim for damages on account of anticipated profits on the work that may be omitted.
10-08. Compensation for Extra Work or Work Omitted. Whenever corrections, additions, or modifications in the work under this contract change the amount of work to be done or the amount of compensation due the Contractor, excepting increases or decreases in contract items having unit contract prices for each measurable quantity installed in place, and such changes have been ordered in writing by the Engineer and approved by the City prior to the Contractor performing the extra work, then a price may be agreed upon. Failing such an agreement in price, the Contractor shall be compensated for performing extra work pursuant to the provisions of Section 4-1.03 D,"Extra Work", and Section 9-
1.03,"Force Account Payment" of the Standard Specifications.
This method of determining the price of work shall not apply to the performance of any work which is required or reasonably implied to be performed or furnished under this contract. 10-09. Compensation to the City for Extension of Time. In case the work called for under this contract is not completed within the time limit stipulated herein, the City shall have the right as provided hereinabove, to extend the time of completion thereof. If the time limit be so extended, the City shall have the right to charge to the Contractor and to deduct from the final payment for the work the actual cost to the City of engineering, inspection, superintendence and other overhead expenses which are directly chargeable to the contract and which accrue during the period of such extension, except that the cost of final unavoidable delays shall not be included in such charges. 10-10. Liquidated Damages for Delay. It is agreed by the parties to the contract that time is of the essence and that, in case all the work is not completed before or upon the expiration of the time limit as set forth, damage, other than those cost items identified in section 10-09, will be sustained by the City and that it is and will be impracticable to determine the actual amount of damage by reason of such delay; and it is therefore agreed that the Contractor will pay to the City the sum of five hundred dollars ($500.00) per day for each and every calendar day's delay beyond the time prescribed.
SECTION 11. MISCELLANEOUS
11-01. Notice. Whenever any provision of the contract documents requires the giving of written notice, it shall be deemed to have been validly given if delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended, or if delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. If mailed, the notice shall be deemed received on the date of delivery stated in the return receipt.
11-02. Computation of Time. When any period of time is referred to in the Contract Documents by days, it shall be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day shall be omitted from the computation.
11-03. Claims Procedure Required by Public Contract Code Section 9204. This section shall apply to any claim by the Contractor arising in connection with this project in accordance with Public Contract Code Section 9204. a. For purposes of this section "Claim" means a separate demand by the Contractor sent by registered mail or certified mail with return receipt requested, for one or more of the following:
(A) A time extension, including, without limitation, for relief from damages or penalties for delay assessed by the City under this contract.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
24 (B) Payment by the City of money or damages arising from work done by, or on behalf of, the Contractor pursuant to this contract and payment for which is not otherwise expressly provided or to which the Contractor is not otherwise entitled.
(C) Payment of an amount that is disputed by the City.
b.
(A) Upon receipt of a claim pursuant to this section, the City shall conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide the Contractor a written statement identifying what portion of the claim is disputed and what portion is undisputed. Upon receipt of a claim, a public entity and the contractor may, by mutual agreement, extend the time period provided in this subdivision. (B) The Contractor shall furnish reasonable documentation to support the claim. (C) If the City needs approval from its governing body to provide the Contractor a written statement identifying the disputed portion and the undisputed portion of the claim, and the governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, the City shall have up to three days following the next duly publicly noticed meeting of the governing body after the 45-day period, or extension, expires to provide the claimant a written statement identifying the disputed portion and the undisputed portion. (D) Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the City issues its written statement. If the City fails to issue a written statement, paragraph (3) shall apply. (2)
(A) If the Contractor disputes the City's written response, or if the City fails to respond to a claim issued pursuant to this section within the time prescribed, the Contractor may demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the City shall schedule a meet and confer conference within 30 days for settlement of the dispute.
(B) Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the City shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. Any disputed portion of the claim, as identified by the contractor in writing, shall be submitted to nonbinding mediation, with the City and the Contractor sharing the associated costs equally. The City and Contractor shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject to applicable procedures outside this section. (C) For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.
(D) Unless otherwise agreed to in writing by the City and the Contractor, the mediation conducted pursuant to this section shall excuse any further obligation under Public Contract Code Section 20104.4 to mediate after litigation has been commenced.
(3) Failure by the City to respond to a claim from the Contractor within the time periods described in this subdivision or to otherwise meet the time requirements of this section shall result in the claim being deemed rejected in its entirety. A claim that is denied by reason of the public entity's failure to have responded to a claim, or its failure to
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
25 otherwise meet the time requirements of this section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the Contractor. (4) Amounts not paid in a timely manner as required by this section shall bear interest at 7 percent per annum. (5) If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against a public entity because privity of contract does not exist, the Contractor may present to the public entity a claim on behalf of a subcontractor or lower tier subcontractor. A subcontractor may request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the Contractor present a claim for work which was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor. The subcontractor requesting that the claim be presented to the public entity shall furnish reasonable documentation to support the claim. Within 45 days of receipt of this written request, the Contractor shall notify the subcontractor in writing as to whether the Contractor presented the claim to the public entity and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not having done so.
c. A waiver of the rights granted by this section is void and contrary to public policy, provided, however, that (1) upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration, as applicable; and (2) the City may prescribe reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section. 11-04. Litigation and Forum Selection. Contractor and City stipulate and agree that any litigation relating to the enforcement or interpretation of this contract, arising out of Contractor's performance or relating in any way to the work shall be brought in Mendocino County and that venue will lie in Mendocino County.
Except as otherwise expressly provided by law, the parties waive any objections they might otherwise have to the propriety of jurisdiction or venue in the state courts in Mendocino County and agree that California law shall govern any such litigation.
The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto and, in particular but without limitation, the warranties, guaranties and obligations imposed upon the Contractor and all of the rights and remedies available to the City thereunder, shall be in addition to and shall not be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by law or contract, by special warranty or guaranty, or by other provisions of the contract documents and the provisions of this paragraph shall be as effective as if repeated specifically in the contract documents in connection with each particular duty, obligation, right and remedy to which they apply. All warranties and guaranties made in the contract document shall survive final payment and termination or completion of this contract. The City disclaims an express or implied warranty that the plans and specifications identify all site conditions that could affect the time or cost to complete the Work.
11-05. Waiver. The Contractor shall strictly comply with all notices and other contract requirements. Waiver by the City of any failure of the Contractor to comply with any term of the contract, including the notice provisions, shall not be deemed a waiver of a subsequent breach.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
26 TECHNICAL SPECIFICATIONS
SECTION 12. GENERAL INFORMATION
12-01. Arrangement of Technical Specifications. The Technical Specifications are arranged in sections covering the various phases of work as follows:
Section No. Title
12 General Information
13 Construction Details
14 Exclusions from General Conditions
15 Amendments to General Conditions
12-02. Arrangement of Plans. The Plans consist of thirty (30) sheets and they are hereby made a part of the Contract Documents.
12-03. Business Licenses. The Contractor and any subcontractors shall each secure and maintain a valid City of Ukiah Business License prior to the start of any portion of the work. 12-04. Permits. The Contractor shall obtain and pay for all permits required to complete this work except the required encroachment permit. The Contractor shall obtain an encroachment permit from the Public Works Department at no cost prior to the start of the Work. The encroachment permit will not be issued until the Contract Agreement and bonds have been executed, submitted, and accepted by the City and all insurance endorsements have been submitted to and accepted by the City’s Risk Manager.
12-05. Standard Specifications and Standard Plans. The Standard Specifications and Standard Plans of the California State Department of Transportation, 2010, are hereby made a part of these Technical Specifications, and are hereinafter referred to as "Standard Specifications" and "Standard Plans." Whenever the following terms are used in the Standard Specifications and the Standard Plans, they shall be understood to mean and refer to the following:
Department or Department of Transportation - The City Council.
Director of Public Works - The City of Ukiah Director of Public Works/City Engineer.
Engineer - The Engineer, designated by the Director of Public Works, acting either directly or through properly authorized agents, such agents acting within the scope of the particular duties entrusted to them.
Laboratory - The designated laboratory authorized by the City of Ukiah to test materials and work involved in the contract.
State - The City of Ukiah
Other terms appearing in the California Standard Specifications and the California Standard Plans shall have the intent and meaning specified in Section I, Definition of Terms of the California Standard Specifications.
In case of discrepancy between the contract documents, the order of precedence from the highest to lowest is as follows:
1. (City) Special Provisions (Technical Specifications)
2. (City) Project Plans
3. City Standard Plans and Details
4. California Standard Plans
5. California Standard Specifications
12-06. Temporary Facilities. All temporary facilities are the responsibility of the Contractor and the removal of said facilities shall be the responsibility of the Contractor. The Contractor shall be responsible for any and all damages to existing facilities which are a result of the installation and removal of the Contractor’s temporary facilities. 12-07. Public Convenience and Safety. The Contractor shall conduct operations so as to cause the least possible obstruction and inconvenience to public traffic. The Contractor shall, at his or her expense, furnish such flag persons and furnish, erect, construct and maintain such fences, barriers, lights, signs, detours, pedestrian walkways, driveway ramps and bridging as may be necessary to give adequate warning to the public that work is in progress and that dangerous conditions exist, to provide access to abutting properties and to permit the flow of pedestrian and vehicular traffic to safely and expeditiously pass through the work.
The Contractor shall post notice(s) at the job sites a minimum of 72 hours in advance of working at the site, indicating the date and times that street parking will be prohibited. This notice shall be placed in obvious locations and be spaced no further than 250 feet apart along the length of the project site and on each side of the affected street. The Contractor shall also provide and place door hangers at all houses adjacent to working area. The door hanger notification shall be in writing and it shall be submitted to the Engineer for approval a minimum of 5 working days prior to the proposed public notification. Full cost for “Public Convenience and Safety“ shall be considered as included in the various items of work and no additional compensation will be made.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
27 12-08. Maintaining Traffic. Attention is directed to Section 7-1.08, "Public Convenience," 7-1.09, "Public Safety," 7-
1.092, "Lane Closure," and 7-1.095, "Flagging Costs," of the California Standard Specifications.
Streets shall be open to through vehicular traffic during non-working hours. All public traffic shall be permitted to pass through the work with as little inconvenience and delay as possible.
Full costs for "Maintaining Traffic", including "Flagging Costs", shall be considered as included in the various items of work and no additional compensation will be made.
Street Closures shall conform to the provisions in the section of these Special Provisions entitled “Traffic Control System for Street Closure.”
When leaving a work area and entering a roadway carrying public traffic, the Contractor’s equipment, whether empty or loaded, shall in all cases yield to public traffic.
The full width of the traveled way shall be opened for use by public traffic on Saturdays, Sundays, and designated City holidays, after 3:00 p.m. Fridays and the day preceding designated City holidays, and when construction operations are not actively in progress.
Designated City holidays are: January 1st, the third Monday in January, the third Monday in February, the last Monday in May, July 4th, the first Monday in September, the second Monday in October, the second Monday in November, Thanksgiving Day, the day following Thanksgiving Day, December 24th, December 25th, December 30th, December 31st.
When a designated City holiday falls on a Sunday, the following Monday shall be a designated City holiday. When a designated City holiday falls on a Saturday, the preceding Friday shall be a designated City holiday.
Minor deviations from the requirements of this section concerning hours of work which do not significantly change the cost of the work may be permitted upon the written request of the Contractor if in the opinion of the Engineer public traffic will be better served and the work expedited. Such deviations shall not be adopted until the Engineer has indicated his written approval. All other modifications will be made by contract change order.
The fences, temporary railing (Type K), barricades, lights, signs, and other devices furnished and installed by the Contractor, at his expense, to conform to the provisions in said Section 7-1.09, and in addition to any construction area traffic control devices for which payment is provided for elsewhere in the specifications.
At the end of each working day if a difference in excess of 2 inches exists between the elevation of the existing pavement between lines, the contractor shall furnish and place portable delineators along said drop-off. “Do Not Pass” signs shall also be placed at 500 feet intervals when delineators are required. Full compensation for furnishing and placing delineators and signs shall be considered as included in the various items of work and no additional compensation will be allowed.
The fences, temporary railing (Type K), barricades, lights, signs, and other devices furnished and installed by the Contractor, at his expense, to conform to the provisions in said Section 7-1.09, and in addition to any construction area traffic control devices for which payment is provided for elsewhere in the specifications.
Payment. Full costs for “Maintaining Traffic”, including “Flagging Costs” shall be considered as part of the lump sum payment for Traffic Control System and no additional compensation will be made. 12-09. Stream Pollution. The Contractor shall exercise precaution to limit the muddying or silting of live streams and drainage channels to the maximum extent practicable, and the Contractor's attention is called to the fact that the terms of this contract do not relieve him or her of responsibility for compliance with Sections 5650 and 12015 of the Fish and Game Code or other applicable statutes relating to pollution prevention or abatement.
The Contractor’s attention is also directed to Section 7-1.01G, “Water Pollution,” of the Standard Specifications and to Section 13, “Water Pollution Control”, of the Construction Details Section concerning the requirement for submittal to the Engineer for approval a written program for the control of pollution to adjacent drainage courses during the construction of the project. Said written program shall include the erosion control provisions required by Section 13, “Temporary Erosion Control”, of these Construction Details.”
12-10. Warranties. Unless otherwise indicated, the Contractor shall warrant all materials provided and work performed under this contract for a period of one year from the date of final acceptance. The Contractor shall replace promptly and at his own expense any materials and/or workmanship that are faulty or defective during this warranty period.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
28 12-11. Utilities. The owner will not arrange water, sewer or electrical services for construction. It is the Contractor's sole responsibility to arrange such services as necessary with the applicable utility provider(s). 12-12. Dust Control. Dust control shall conform to the provisions of Section 10 of the Standard Specifications. Full compensation for dust control shall be considered as included in the prices paid for the various contract items and no additional compensation will be made therefore. This includes the application of water for the purpose of controlling dust caused by public traffic within the project area. The Contractor may at his option use dust palliative in accordance with the provisions of Section 18, “Dust Palliative’” of the Standard Specifications except that the full compensation for applying dust palliative shall be considered as included in the prices paid for the various contract items of work and no additional compensation will be made therefore.
All active construction areas shall be watered at least twice daily and more often during hot or windy periods. The active areas adjacent to the apartment complexes shall be kept damp at all times. Hauling trucks shall be covered or at least a two-foot freeboard shall be maintained.
Unpaved access roads, parking areas for construction equipment and construction employee vehicles, staging areas, and storage areas shall be paved or shall receive the application of either water twice daily or non-toxic soil stabilizers.
All paved access roads, parking areas, staging areas, storage areas, and public roads impacted by the work of the project shall be swept daily with street sweepers equipped with water spray to remove soil materials that have been deposited on these surfaces by reason of the work.
The Contractor shall enclose, cover, or water twice daily or apply non-toxic soil stabilizers or install erosion control blankets to or on exposed stockpiles, embankment slopes, and cut slopes. Traffic speeds on unpaved surfaces shall be limited to a maximum speed of 15 mph
12-13. Noise Control. The Contractor’s attention is directed to the provisions of section 7.1.01I, “Sound Control Requirements", of the Standard Specifications and Section 9.08, Saturday, Sunday, Holiday, and Night Work, of these General Conditions concerning the control of noise emissions and authorized work hours and days. Between 7:00 a.m. and 7:00 p.m., noise from Contractor’s operations shall not exceed limits established by applicable laws or regulations and in no event shall exceed 86 dB at a distance of 50 feet from the noise source.
The City shall provide a Noise Disturbance Coordinator who shall be responsible for acting on any local complaints concerning the construction noise being generated by reason of the work of the project. The Contractor shall conspicuously post a telephone number for the Noise Disturbance Coordinator at the construction site and he shall include it in the construction schedule notice to be provided to the residents. The Noise Disturbance Coordinator shall investigate the noise complaint allegations and shall require the Contractor to implement reasonable measures to mitigate the noise level in accordance with the requirements of these General Conditions and of the Standard Specifications.
The Contractor shall locate all stationary noise generating construction equipment such as air compressors and generators as far as practical from the nearby residences and other noise sensitive land uses. The noise source shall be acoustically shielded when practical. The Contractor shall prohibit unnecessary idling of internal combustion engines. 12-14. Watering. The application of water and the developing of a water supply shall be performed in accordance with the provisions of Section 17, “Watering,” of the Standard Specifications except as modified by these Special Provisions.
Full compensation for applying water where called for or as directed by the Engineer and for developing the water supply shall be considered as included in the prices paid for the various contract items and no additional compensation will be made therefore. The Contractor is advised that water may be obtained from fire hydrants within the project area under permit with the City’s Public Works Department and upon the payment of a meter deposit. Permit application and inquiry as to the water usage fees are to be made at the City of Ukiah, 300 Seminary Avenue, phone (707) 463-6228. 12-15. Preconstruction Conference. A preconstruction conference will be held before any work will be allowed to commence. This meeting will cover inspection, work schedule, and among other items, the responsibilities and procedures of each of the interested parties to assure that the project will be completed in accordance with the contract documents.
12-16. Progress Schedule. Progress schedules will be required for this contract and shall conform to the provisions in Section 8-1.04, "Progress Schedule," of the Standard Specifications.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
29 12-19. Safety Requirements. The Contractor shall comply with all pertinent provisions of the Department of Labor "Safety and Health Regulations for Construction (29 FCS Part 1518, 36 CFR 7340)", with additions or modifications thereto, in effect during construction of this project.
SECTION 13 - CONSTRUCTION DETAILS
13-01. Location and Scope of Work.
All of the work to be performed is within the City of Ukiah. Project is located at the following locations:
-Dora Street between West Mill Street and Grove Avenue
-West Clay Street from Dora Street to South Pine Street -Walnut Avenue from Dora Street to North Bush Street
-North Bush Street from Walnut Avenue to Grove Avenue
The Contractor should familiarize himself with the local conditions of the project site. Failure to do so will in no way relieve him of the responsibility for performing any of the work or operations required as a part of this contract. Further information regarding the work or these specifications can be obtained from Mary Horger at (707) 463-6233. 13-02. Preservation of Property. The contractor shall conform to the provisions of Section 7-1.11, “Preservation of Property” of the Standard Specifications and to these Special Provisions. All costs to the Contractor for protecting, removing, modifying, relocating and restoring existing improvements shall be considered as included in the contract prices paid for the various items of work and no additional allowances will be made therefore.
Payment Full compensation for complying with this section of the Special Provisions shall be considered as included in the prices paid for the various contract items of work, and no additional compensation will be allowed therefore.
13-03. Watering. Developing water supply and applying shall conform to the provisions in Section 17 of the Standard Specifications and these Special Provisions. Water shall not be obtained from any of the nearby property owners without their written permission.
Payment. Full compensation for developing and applying water conforming to the above requirements shall be considered as included in the prices paid for the various contract items of work requiring water, and no additional compensation will be allowed therefore.
13-04. Traffic Control System for Street Closure. A traffic control system shall consist of closing streets in accordance with the Caltrans Manual of Traffic Controls for Construction and Maintenance Work Zones, the provisions of Section 12, “Construction Area Traffic Control Devices,” of the Standard Specifications, and provisions under “Maintaining Traffic” elsewhere in these Special Provisions.
The provisions in this section will not relieve the Contractor of their responsibilities that may be necessary to comply with the provisions in Section 12-08, “Public Safety”, of the Standard Specifications.
The base material of construction area signs may be plywood in City Right-of-Way, but shall not be plywood in the State Right-of Way.
The contractor shall develop and submit to the Engineer for approval a Traffic Control Plan a minimum of one week before beginning construction. The Traffic Control Plan shall show the planned method of traffic control during construction.
The following information shall be included in the Traffic Control Plan:
• Sequencing of construction
• Street layout, with street names and direction of flow • Location and types of construction area signs (including pedestrian notification) • Locations of barriers or other traffic control devices • Location of flaggers
• A contingency plan for how to handle emergency vehicles
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
30 The Contractor shall not begin construction at the site until the Traffic Control Plan is reviewed and approved by the Engineer. The City reserves the right to delay the contractor’s operations until such time that a Traffic Control Plan has been reviewed and approved by the Engineer.
If any component in the traffic control system is damaged, displaced, or ceases to operate or function as specified, from any cause, during the progress of the work, the Contractor shall immediately repair said component to its original condition or replace said component and shall restore the component to its original location.
When street closures are made for work periods only, at the end of each work period, all components of the traffic control system shall be removed from the traveled way and shoulder. If the contractor so elects, said components may be stored at select central locations, approved by the Engineer, within the limits of the street right-of-way.
Payment. The contract lump sum price paid for traffic control shall include full compensation for furnishing a Traffic Control Plan, furnishing all labor, materials (including signs), tools, equipment, and incidentals and for doing all the work involved in placing, removing, storing, maintaining and moving to new locations, replacing, and disposing of the components of the traffic control system as shown on the plans, as specified in the Standard Specifications and these Special Provisions, and as directed by the Engineer. 13-05. Adjust Existing Frames, Covers, Grates and Manholes to Grade. This work shall consist of raising or adjusting existing utility facilities and replacing surface utility facilities, such as sewer and storm drain manhole frames and covers, water valve covers, gas valve covers, water meter boxes and covers, monument covers, sewer cleanouts, and monitoring well covers to the finished grade of the resurfaced asphalt pavement.
On roadways to be milled, facilities shall first be lowered prior to cold planing and then adjusted to finish grade after completion of the resurfacing work (refer to Section 13-08 “Cold Plane Asphalt Concrete Pavement” of these Construction Details). At various locations a monument box and cover shall be installed at the finish grade over any unprotected, existing monumentation in the paved roadway.
All such work shall conform to the applicable provisions of the Standard Specifications, these Construction Details, the Plans and typical sections and as directed by the engineer.
Unless specifically allowed by the Engineer, grade rings shall not be used to adjust utility covers. The Contractor shall properly locate and tie all existing facilities to be raised in advance of paving operations. 13-05.1 Construction. Care shall be taken to keep frames and covers clean. The Contractor shall completely protect with heavy plastic or other suitable material all utility covers or other items which are visible on the surface and will be covered by his operations. This shall be completed prior the start of operations and approved by the Engineer.
Any materials that adhere to the frames and covers shall be removed.
Contractor shall exercise care during the work of lowering and raising covers to avoid any construction debris from entering into the manhole chamber. Any material which enters the manhole or connecting pipes shall be removed at the expense of the Contractor to the satisfaction of the City. In the event that a problem is reported, Contractor shall have on hand the necessary equipment and manpower, including traffic control devices and crew if deemed necessary, to open lids that are requested for review by the Engineer, at no additional cost to the City.
Facilities damaged by the Contractor shall be replaced at the Contractor’s expense. Facilities (box and lid or frame and cover) found existing in a damaged condition, and reported to the Engineer before disturbing, shall be replaced by the Contractor with materials furnished by the Owner.
All facilities on active systems shall be accessible at all times to City personnel unless otherwise stated in these Special Provisions or approved by the Engineer.
After placement of the finish course of asphalt concrete the Contractor shall mark all overlaid manholes, valve boxes, mainline cleanouts and monuments, whether new or existing, with white paint by the end of that working day.
All new and existing manholes, valve boxes, mainline cleanouts and monuments shall be adjusted to grade
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
31 within 48 hours after placement of the finish course of asphalt concrete. Final grade adjustments and installation of concrete collars shall be done on the same working day. Final paving around manholes, valve boxes, mainline cleanouts and monuments shall be completed no later than the following working day. All manhole frames and covers being adjusted to grade, but left with exposed concrete collars shall have steel plate covers with hot mix asphalt tapers maintained until final asphalt concrete paving is placed. 13-05.2 Manholes. Prior to removal of an existing manhole frame, a platform to prevent debris from entering the sewer, storm drain or communication vault, shall be placed in the manhole above the top of the sewer or storm drain. The platform shall remain in place until all work on the manhole has been completed, the asphalt concrete has been placed around the manhole and all dirt and debris is removed from the platform.
The Contractor shall be responsible for the removal of any dirt and debris that falls into the manhole, and any damage to the facility or downstream facilities. Trimming of manhole cones (tapered section) will not be permitted.
All sections of the manhole grade rings shall be set in cement mortar and all joints smoothly grouted inside and out. The top of the completed manhole shall contain at least one three (3) inch grade adjustment ring. All manhole frames and covers shall be adjusted to grade after placement of the finish course of hot mix asphalt.
Existing grade adjustment rings removed in the adjustment of manhole frames shall become the property of the Contractor. If undamaged and thoroughly cleaned of mortar, the grade rings may be reused in the work. If not so used, they shall be disposed of away from the work site at the expense of the Contractor.
Manhole frames shall be reinstalled to align directly over the grade rings. Any frames misaligned by more than ½ inch shall be removed and reinstalled.
All silt and debris shall be removed from finished structures. This shall include all existing silt and debris plus material caused by the Contractor's operation.
All grade rings shall be set in cement mortar the same day they are placed. All joints shall be smoothly plastered inside and out.
The Contractor shall accurately locate and record the location of all manhole covers to be raised to grade.
The Contractor shall furnish the Engineer a copy of said record prior to resurfacing the street. Where shown on the Plans and specified in these construction details, utility vaults, manholes and boxes will be adjusted to grade by the utility company that owns the facility. The Contractor shall coordinate with utility companies in advance of scheduled work to provide adequate time for determination of work. 13-05.3 Valve Frame and Cover. Existing water valve frames and covers, gas valve frames and covers, monitoring well covers and hand holes shown on the Plans to be adjusted to grade shall be adjusted to final pavement grade in conformance with the details on the Plans.
The Contractor shall accurately locate and record the location of all valve covers to be adjusted to grade and shall furnish the Engineer a copy of said record prior to resurfacing.
After a street has been overlaid, all valve boxes shall be marked in white paint before the close of that workday. Within 48 hours of paving, all valve boxes shall be brought to grade, cleaned out and inspected by the Contractor.
13-05.4 Sawcut Pavement. Where no joint exists between concrete or asphalt concrete to be removed and concrete or asphalt concrete to remain in place, the concrete or asphalt concrete shall be cut in a neat line to a minimum depth of 0.25-foot with a power driven saw before the concrete or asphalt concrete is removed. 13-05.5 Tolerances. The concrete around these adjusted facilities shall be left two (2”) inches lower than the adjacent pavement. The concrete surface shall be tack coated with 0.10 gallons per square yard and paved with ½ inch Type A HMA.
The surface adjusted facilities shall be true to the new pavement surface to within one-eighth inch (1/8”) deviation. This tolerance shall apply in a single direction only, either up or down. In addition, the adjusted facility shall not vary by the high tolerance on one side and the low tolerance on the other (i.e. the total aggregated tolerance on both sides shall be limited to the 1/8” inch variation). This variation shall apply to the
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
32 adjacent patch paving around the facility as well such that neither the paving nor the facility vary by more than the stated tolerance.
Measurement and Payment. Full compensation for Adjust Existing Manhole/Valve/SSCO Cover to Grade will be measured and paid for at the contract unit price per each and shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals for performing all work involved in adjusting existing valve covers and sanitary sewer cleanout covers, to new finish grades, including but not limited to excavation, backfill, concrete, grade rings, debris platforms, cleaning, asphalt or concrete pavement and mortar throughout the project limits and all other related work specified on the Plans, in these Construction Details, the Standard Specifications and as directed by the Engineer and no additional allowances will be made therefor. Lowering valve and cleanout covers prior to cold planning shall be paid for under “Cold Plane Asphalt Concrete”, as further described in these Construction Details.
13-06. Roadway Excavation. Full compensation for Roadway Excavation will be measured and paid for at the contract unit price per cubic yard for the final pay quantity in the Engineer’s Estimate, which price shall include full compensation for furnishing all plant, labor, materials, tools, equipment, transportation, and incidentals for performing all work required for the roadway excavation as described in this section within the limits shown on the Plans, removing asphalt concrete pavement, base, sub-base, subgrade, cutting and pruning tree roots encountered during excavation, spreading and compacting subgrade material to achieve required subgrade elevation, backfilling as required to achieve design subgrades and finish grades, and scarifying, moisture conditioning and compacting subgrade as specified in Section 19 of the Standard Specifications and these Construction Details, including, preparation of subgrade in all roadway, curb and gutter, sidewalk, driveway and ramp areas, proofrolling, scarification, moisture conditioning, and compaction and no additional allowances will be made therefor.
Removal of existing bituminous pavement and base materials will be paid for as roadway excavation.
Measurement. Roadway Excavation shall be measured by the calculated in place cubic yards removed based on the pavement surface area and the depth of pavement removal. Roadway Excavation in excess of the depth as shown on the plans or as directed by the Engineer will not be paid for.
Payment. The contract price paid per cubic yard for Roadway Excavation shall include full compensation for furnishing all labor, materials, tools and equipment, and doing all work necessary, including modifying the depth of grinding as specified above, any required handwork, sweeping and the disposal of the materials to complete this item as specified, and no additional compensation will be allowed therefore. 13-07. Hot Mix Asphalt.
13-07.1 General. HMA shall contain high tensile strength aramid fiber reinforcement. HMA shall be provided in accordance with the Standard HMA construction process and conform to Section 39 of the Standard Specifications and as detailed in this specification.
Fiber reinforced HMA is mixture of hot mix asphalt and a high tensile strength aramid fiber blend that has greater resistance to rutting, thermal cracking, fatigue cracking, and reflective cracking as compared to conventional non-fiber asphalt mixes.
13-07.2 Quality Control Plan. Contractor shall establish, implement and maintain a Quality Control Plan (QCP) to ensure materials and work comply with the specifications and the corrective actions required to control the quality of work. The QCP shall comply with these specifications and Section 39-2.02 “Contractor Quality Control” of the Standard Specifications.
Contractor shall attend a pre-paving conference with the Engineer to discuss methods of performing the production and paving work and how quality control will be performed throughout.
Qualifications of workers: Provide sufficient skilled workers and supervisors who shall be present at all times during execution of this portion of the Work and who shall be thoroughly familiar with the type of construction involved and the materials and techniques specified.
Codes, standards and definitions:
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
33 1. Wherever a test method is referenced in this section, it shall be made in accordance with the most current test method in use by Caltrans in the State Standard Specifications, unless otherwise noted in this section.
2. ASTM D2172, Standard Test Methods for Quantitative Extraction of Bitumen from Bituminous Paving Mixtures
3. ASTM D6931, Standard Test Method for Indirect Tensile (IDT) Strength of Bituminous Mixtures.
4. AASHTO T322, Determining the Creep Compliance and Strength of Hot-Mix Asphalt (HMA) Using the Indirect Tensile Test Device.
5. Zeiada, W., Underwood, S., Stempihar, J., “Extraction of Aramid Fibers from Fiber Reinforced Asphalt Concrete – Special Test Method”, Arizona State University, May 11, 2016.
6. Aramid Dispersion State Ratio (ADSR): The mass of aramid in the individual state compared to the total mass of extracted aramid fibers, expressed as a percentage. 13-07.3 Submittals. The Contractor shall provide the Engineer with the following information a minimum of 10 days prior to commencing the Work:
1. Hot mix asphalt job mix formula (JMF) in accordance with Caltrans Standard Specifications. a. Proposed JMF on Form CEM-3511: Include percentage of reclaimed asphalt pavement (RAP) b. Representative reinforcing fiber product sample.
c. Reinforcing fiber product data sheet and certification from the Manufacturer that the fiber product supplied meets the requirements of this specification.
d. Reinforcing fiber manufacturer’s instructions and general recommendations. e. Past performance test results of IDT testing from a minimum of three separate laboratory trials. f. Past performance test results of ADSR testing from a minimum of two tests. g. Submit a minimum of five project examples and references where the reinforcing fiber product was used for roadways in the State of California.
h. Mix design documentation, data and aggregate quality on Form CEM-3512 dated within 12 months of submittal.
i. JMF verification on Form CEM-3513, if applicable
j. JMF renewal on Form CEM-3514, if applicable
k. Materials Safety Data Sheets (MSDS) for:
• Asphalt binder
• Supplemental fine aggregate except fines from dust collectors • Antistrip additives
2. Written confirmation from the supplier that the JMF to be supplied meets all specified requirements.
Performance testing for reinforcing fiber product must be from laboratory trials at a fiber dosage rate equal to the rate proposed for the project. Tests must be performed by an AASHTO accredited laboratory or nationally recognized university testing lab and must be reviewed and approved by the project engineer.
Indirect Tensile (IDT) Strength Tests from a minimum of three (3) separate laboratory trials.
1. Perform indirect tensile tests using the protocol from AASHTO T322 or ASTM D6931
2. Tests results shall include a control and a fiber reinforced mix. FRAC mix shall be identical to control mix except for the inclusion of fibers added at the same dosage as proposed on the project.
3. Indirect tensile test results from fiber specimens shall show an average tensile strength increase of 20 percent over control specimen with no less than 15 percent increase of average tensile strength.
Aramid Dispersion State Ratio (ADSR) Tests from a minimum of two (2) separate laboratory trials.
1. Perform ADSR test based on modified ASTM D2172 procedures as provided in the document entitled “Extraction of Aramid Fibers from Fiber Reinforced Asphalt Concrete – Special Test Method”. A copy of the modified extraction methodology can be obtained by making an inquiry to the Pavement and Materials Laboratory at Arizona State University at [email protected].
2. To validate ADSR results, average extracted aramid fiber quantity must equal 0.007 percent by total sample weight with no individual result less than 0.005 percent of the total sample weight.
3. All tested fiber mixes must achieve a minimum ADSR of 85%.
Tack Coat: Contractor shall submit asphalt binder tack coat and asphaltic emulsion tack coat.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
34 The Contractor shall develop and submit a Quality Control Plan for the project. This shall, at a minimum, cover the areas or subjects contained in Section 39-2 of the Standard Specifications. The Contractor shall not begin hot mix asphalt production or placement without written approval from the Engineer of the QCP and an approved JMF. Approval of the QCP and JMF by the Engineer does not relieve the contractor of responsibility for quality control or work methods. 13-07.4 Engineer’s Acceptance. Quality control sampling and acceptance testing will be performed by the City. The City reserves the right to perform acceptance testing at frequencies that differ from those specified in the Standard Specifications.
A minimum of one sample for Rice Specific Gravity may be taken by each day at the plant during placement of HMA.
The Rice Specific Gravity test will be in accordance with ASTM D 2041. Any changes to the JMF requested by the Engineer shall be implemented by the Contractor or a new JMF resubmitted for approval prior to continuing work.
In place density tests per CT 375 Nuclear Gage field test may be performed during HMA operations to verify compaction requirements per Standard Specifications. The frequency of testing may be in accordance with CT 375.
Should any test specified in Paragraph 13-15.4 of this Section fail to meet density requirements, the City may take density core samples to verify density results and pavement thickness. Contractor shall be responsible for patching the cores with hot mix asphalt at no additional expense to the City. for patching the cores with hot mix asphalt at no additional expense to the City. 13-07.5 Products. Tack Coat shall be Grade PG 64-16, conforming to the provisions of Sections 39 and 92 of the Standard Specifications and shall be used between layers of each lift of HMA, and on curbs, gutters and construction joints.
Asphalt binder and tack coat shall be Grade PG 64-16, conforming to the provisions of Sections 39 and 92 of the Standard Specifications.
Aggregate shall be clean and free from deleterious substances and shall meet the gradation and quality for 3/4-inch HMA Type A for initial course and 1/2-inch HMA Type A for the final course.
Hot Mix Asphalt shall be 3/4-inch HMA Type A for the first course and 1/2-inch HMA Type A for the final course and conform to Section 39 of the Standard Specifications.
Provide a reinforcing fiber blend of virgin polyolefins and virgin aramids that meets the requirements in the tables below.
Reinforcing Fiber Material Properties
Property Test Method Polyolefin Aramid
Form
Manufacturer
Certification Serrated Monofilament
Nominal Specific Gravity ASTM D276 0.91 1.44
Tensile Strength (psi) ASTM D7269 NA1 400,000
Length (in) Manufacturer
Certification 0.75 0.75
1. Polyolefin fibers will melt or become plastically deformed during production Reinforcing Fiber Performance Properties
Performance Test Test Method Requirement
Indirect Tensile Strength (IDT) AASHTO T322 or
ASTM D6931 ≥ 20% increase
Aramid Dispersion State Ratio (ADSR) Modified ASTM
D2172 ≥ 85%
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
35 Reinforcing fiber blend shall be Forta-Fi
®, provided by the Forta Corporation, or approved equivalent. If a different aramid-based fiber blend is proposed, performance test results complying with the requirements of Section 13-15.3 must be submitted at least two weeks prior to bid date for approval by engineer.
HMA batch plant shall be Department-qualified under the Department’s Materials Plant Quality Program of the Standard Specifications.
Reclaimed asphalt pavement shall be acceptable in accordance with the Standard Specifications not exceeding 15.0 percent of the aggregate blend.
13-07.6 Construction. During the entire construction period, the Contractor shall take care to protect existing pavement and concrete surfaces. Surfaces scarred by cleanup or equipment shall be repaired in a manner satisfactory to the Engineer. Any and all damage caused by the Contractor's operations to existing roads and streets shall be repaired by the Contractor to at least the original condition and to the satisfaction of the Engineer, at no additional cost to the City.
13-07.6.1 Preparation. If pavement is damaged (excessive loading, grouser marking, scarring/scraping of pavement, etc.) outside the limits of the work, a full lane width grinding and overlay will be required as directed by the Engineer at no additional compensation to the Contractor.
Ensure the area is clean and dry. All material accumulations which would interfere with the adhesion of the tack coat or with the placing and performance of the HMA shall be removed, including dust, loose aggregate, soil, leaves, and pieces or lumps of other foreign material deposited on the surface. 13-07.6.2 Tack Coat. A tack coat shall be applied to existing pavement including planed surfaces, between HMA layers, and to vertical surfaces of curbs, gutters and construction joints at the minimum residual rates specified in Section 39-1.09C “Tack Coat” of the Standard Specifications.
Before placing HMA, a tack coat shall be furnished and applied uniformly to contact surfaces of all cold pavement joints, curbs, gutters, pavement reinforcing fabric and all existing pavement to be surfaced in conformance with Section 39 of the Standard Specifications.
Tack coat shall be applied to any course in advance of spreading the next course unless the surface temperature is at least 140 °F.
Hot mix asphalt shall not be placed until tack coat has cured. 13-07.6.3 Fiber Reinforced HMA Production. Provide manufacturer’s technical representative at HMA plant during HMA production.
Deliver fiber-reinforcement in sealed, undamaged containers with labels intact and legible, indicating material name and lot number. Deliver fiber-reinforcement to location where it will be added to each batch or loaded into the mixer. Store materials covered and off the ground. Keep sand and dust out of boxes and do not allow boxes to become wet.
Add aramid and polyolefin reinforcing fiber blends at a dosage rate of one (1) pound fiber per one (1) ton of asphalt.
Add alternative aramid fiber blends at a rate proposed by the manufacturer that achieves the IDT and ADSR results required.
Have a fiber manufacturer’s representative on site during mixing and production. This requirement can be waived if fiber manufacturer and asphalt producer can supply evidence of manufacturer’s brand of fiber being successfully produced a minimum of three times at the asphalt plant to be used for the project.
Batch Plant. When a batch plant is used, add fiber to the aggregate in the weigh hopper and increase both dry and wet mixing times. Ensure that the fiber is uniformly distributed before the injection of asphalt cement into the mixture.
Drum Plant: Inject fibers through the RAP collar by placing fibers on the RAP belt for by feeding them with a blower tube system. Rate the feeding of fibers with the rate the plant is producing asphalt mix. If there is any evidence of fiber
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
36 balls at the discharge chute, increase the mixing time and/or temperature or change the angle of the fiber feeder line to increase dry mixing time.
For manual feeding, place fibers on the RAP belt at intervals based on the plant production rate.
When using a blower tube system, add fibers continuously and in a steady uniform manner. Provide automated proportioning devices and control delivery within ±10% of the mass of the fibers required. Perform an equipment calibration to the satisfaction of the fiber manufacturer’s representative to show that the fiber is being accurately metered and uniformly distributed into the mix.
Include the following with the blower tube system:
1. Low level indicators
2. No-flow indicators
3. A printout of feed rate status in pounds/minute
4. A section of transparent pipe in the fiber supply line for observing consistency of flow or feed.
5. Manufacturer’s representative’s approval of fiber addition system 13-07.6.4 Spreading and Compacting. Compaction test subgrade prior to placing HMA to ensure a firm and stable subgrade. After compaction testing and immediately in advance of placing HMA, apply additional tack coat to damaged areas or where loose or extraneous material is removed.
Close areas receiving tack coat to traffic. Do not track tack coat onto pavement surfaces beyond the job site. HMA surfacing shall conform to the provisions of Section 39 of the Standard Specifications and fiber manufacturer. Placing HMA shall be done under suitable weather conditions for such operations. Rain, snow or other inclement weather will be cause for discontinuing paving Work. Only spread and compact if the atmospheric temperature is at least 55 degrees F and rising and the surface temperature is at least 60 degrees F and rising. The Engineer shall have the authority for determining whether weather conditions are sufficient cause to postpone work.
Spreading and compacting shall be performed in accordance with Section 39-1.10 and Section 39-1.11 of the Standard Specifications.
Visually observe fiber reinforced HMA mix in the back of first three trucks and every tenth truck thereafter to confirm adequate blending of the fiber. Remove any observed fiber balls from placed mixture and adjust operations per the manufacturer’s recommendation to eliminate future fiber ball development.
Longitudinal joints in the top layer must match specified lane edges shown on the striping Plans. Longitudinal joints in lower HMA layers shall be offset at least 0.5 feet from each side of the specified lane edges.
Finish rolling shall be completed before pavement surface temperature is below 150 degrees F.
Traffic shall not be allowed on HMA until mid-depth temperature is below 160 degrees F and the pavement surface temperature is below 140 degrees F.
The completed surfacing shall be true to grade and cross section, of uniform smoothness and texture, compacted firmly and free from depressions, humps or irregularities.
Dikes shall be shaped and compacted with equipment capable of shaping and compacting the material to the required cross section.
The exact rate of application of the paint binder will be determined by the Engineer during construction.
Measurement. Full compensation for Hot Mix Asphalt (Type A) will be measured and paid for at the contract unit price per ton which price shall include full compensation for furnishing all plant, labor, materials, tools, equipment, transportation, and incidentals for performing all work under “Hot Mix Asphalt,” including but not limited fiber reinforced HMA, fiber reinforced leveling course, fiber reinforced HMA overlay, tack coat, subgrade proof rolling, compaction, testing and other incidentals as shown on the Plans and specified in the
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
37 Standard Specification, these Construction Details, and as directed by the Engineer, and no additional allowances will be made therefor.
Payment. The contract price paid per ton shall include full compensation for furnishing all labor, material, tools, equipment and incidentals, and for doing all the work involved in placing asphalt. 13-08. Remove Unsuitable Material. Full compensation for Remove Unsuitable Material will be measured and paid for at the contract unit price per cubic yard, which price shall include full compensation for furnishing all plant, labor, materials, tools, equipment, transportation, and incidentals for performing all work required for the excavation and removal of unsuitable material, providing Class 2 aggregate base material on subgrade enhancement geotextile, and compacting subgrade and base material as specified in Section 19 of the Standard Specifications and these Construction Details, and no additional allowances will be made therefor. 13-09. Soil Stabilization Fabric. Full compensation for Geosynthetic Pavement Interlayer (Paving Fabric) will be measured and paid for at the contract unit price per square yard which price shall include full compensation for furnishing all plant, labor, materials, tools, equipment, transportation, and incidentals for installing paving fabric including but not limited to crack cleaning, crack sealing, installing paving fabric, and other incidentals as shown on the Plans and specified in the Standard Specifications, these Construction Details, and as directed by the Engineer, and no additional allowances will be made therefor.
13-10. Class 2 Aggregate Base. Full compensation for Class 2 Aggregate Base will be measured and paid for at the contract unit price per cubic yard for the final pay quantity in the Engineer’s Estimate, which price shall include full compensation for furnishing all plant, labor, materials, tools, equipment, transportation, and incidentals for performing all work required for the hauling, constructing, placing, spreading, moisture conditioning and compacting of aggregate base, and Class 2 permeable material to finish grade or subgrade elevations within the limits shown on the Plans, as specified in Section 26 of the Standard Specifications and these Construction Details, and no additional allowances will be made therefor.
13-11 Traffic Striping. All pavement legends and traffic striping shall conform to the forms and dimensions in the Caltrans Standard Plans and Specification, 2018 Edition, and the California Manual on Uniform Traffic Control Devices, latest edition, and be thermoplastic, unless otherwise noted.
The Contractor shall physically tie down the location of the beginning and ending of each paint or thermoplastic marking type in the adjacent curb top. The marking location shall not exceed fifty square inches each. Any locations exceeding this limit shall be removed by the Contractor prior to acceptance of the work. The Contractor shall contact the Engineer for review of tie downs.
The Contractor shall be responsible for accurately referencing out and replacing the lines and positions of all traffic lines, directional lines, arrows, and other markings in accordance with the Plans.
Temporary tab markers shall be placed not more than six (6’) feet apart on curves nor more than twelve (12’) feet apart on straight segments.
Temporary tab markers (floppies) shall be the same color as the permanent traffic stripe that they are replacing, shall measure two (2”) inches tall by three and one-half (3-1/2”) inches wide, and have a reflective lens across the width of the marker. Temporary tab markers shall be placed before the lane is opened to traffic, unless otherwise approved by the Inspector.
Prior to application of permanent striping and markers, the Contractor shall call for review and approval of the proposed striping by the Engineer. The Engineer shall have the right to make changes in the location and alignment of line stripes.
Striping and traffic markings shall not be applied until after approval is granted by the Engineer. The Contractor shall allow a minimum of three (3) working days for review of the layout by the Engineer.
Permanent traffic striping and markings including legends and arrows shall be placed within twenty-one (21) days after paving or surfacing, unless otherwise directed by the Engineer.
Temporary marking tape or temporary tab markers denoting crosswalks shall be placed the same day that the pavement surfacing is placed. Temporary tab markers denoting crosswalks or limit lines shall be placed at intervals not to exceed
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
38 three (3’) feet.
Failure to comply with these requirements shall result in a liquidated damage of $150 per day for each street that has not received permanent installation of the required raised pavement markers, traffic striping, and markings.
In areas adjacent to the reconstructed surfacing where existing striping must be changed to conform to a revised striping pattern, conflicting striping shall be removed by sand blasting, grinding, or other methods as specified in the Standard Specifications or by the Engineer. Removal of existing striping and markings shall not materially damage the underlying pavement.
Existing striping and markings that are to remain in place shall be protected from damage in accordance with Section 84-1.03B of the Standard Specifications. The Contractor shall replace all striping which has been damaged or obliterated by or during the work. This shall include striping replacement completely across the street even in the event that the Contractor’s work may not extend that far. Both lines of each crosswalk shall be completely repainted even if only a portion of a line has been obliterated.
When the Contractor’s work removes or reduces the visual appearance of a lane or center line, the Contractor shall replace all striping between the adjacent intersections in both directions. Where a median exists, this work will be required only in the roadway where the work has occurred, unless a detour which altered the pavement markings occurred in the other roadway. In such cases, the striping will be replaced in both directions.
Measurement. Full compensation for Traffic Stripe (Detail XX) will be measured and paid for at the contract unit price per linear foot, which price shall include full compensation for furnishing all plant, labor, materials, tools and equipment and doing all the work necessary for the installation of traffic stripe per the Standard Detail, including but not limited to surface preparation, establishing layout and alignment, thermoplastic, adhesive, pavement markers, and temporary striping, as shown on the Plans and Standard Plans, and specified in the Standard Specifications and these Construction Details, and no additional allowances will be made therefor.
Payment. The contract price paid per linear foot for painted traffic stripes shall include full compensation for furnishing all labor, material, tools, equipment and incidentals, and for doing all the work involved in painting traffic stripes.
13-12 Thermo X-Walk & Pavement Markings. The Contractor shall furnish and apply traffic stripes, characters, arrows, pavement markers, and other delineations and markings. These shall be reapplied in the original pattern on all roads except as shown on the striping plans, as specified herein, or as directed by the Engineer. Contractor shall install traffic striping and markers in accordance with Sections 84, “Traffic Stripes and Pavement Markings” and Section 85 “Pavement Markers” of the Standard Specifications.
Pavement markings which include bicycle lane notification, stencils, “STOP” and turn arrows shall be painted and shall have glass beads applied as per the plans in accordance with Section 84, “Traffic Stripes and Pavement Markings” of the Standard Specifications except as provided herein, the Standard Plans, and these Special Provisions. Contractor shall reference all existing pavement markings prior to pavement grinding on those streets that have pavement markings.
All pavement legends and traffic striping shall be applied in thermoplastic unless otherwise noted.
Measurement. Pavement marking shall be measured as a square foot price.
Payment. The square foot price paid for Pavement Marking shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, referencing the existing pavement marking and doing all the work involved in painting pavement marking as designated by the Plans, and no additional compensation will be allowed therefore.
13-13. Reflective Pavement Markers (Blue). Blue, reflective, pavement markers shall be placed across from city fire hydrants, and conform to the provisions in section 3B-03 of the California Manual on Uniform Traffic Control Devices and the attached figure 3B-102 (CA). All pavement makers shall also conform to the provisions in Section 85 of the California Standard Specifications. Pavement Adhesive used to install pavement markers shall conform to the requirements of Section 85 of the California Standard Specifications.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
39 Measurement. Placing pavement markers will be measured as each.
Payment. The contract price paid per each for pavement markers shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in placing pavement markers.
13-14. Minor Concrete. This work consists of constructing A1-6 curb, curb and gutter, sidewalks and wheelchair ramps.
All concrete shall be Class B containing not less than 470 pounds of Portland cement per cubic yard of concrete (5 Sack) as specified in Section 90 of the California Standard Specification.
Contractors attention is directed to the requirements of each ramp detail drawing and the following Standard Drawings:
No. 101 “Score Mark Details, Sidewalk, Curb and Gutter”, and No. 111 “Wheelchair Ramp Detail”.
Remove Concrete (Curb & Gutter). The contractor shall remove existing asphalt and concrete to provide forms for the lip of the gutter.
Measurement. Removal of Concrete (Curb and Gutter) will be measured by the linear foot, in place along the face of curb.
Payment. The contract price will be paid per linear foot and shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals for performing all work involved in the removal of existing concrete curb and gutter including but not limited to saw cutting, removal of concrete, sand and base rock, excavation, stockpiling removed materials, hauling and disposal of removed materials, and cleaning of materials, as specified in these Construction Details and shown on the Plans, and no additional allowances will be made therefor.
Curb and Gutter. Gutter width varies from site to site and Contractor should carefully review the Project Plans.
All curb and gutter shall be measured and paid for as if it were standard curb and gutter per Standard Drawing No. 102. Curb and gutter shall not be poured monolithic with the sidewalk unless otherwise approved by the Engineer.
Measurement. Curb and gutter will be measured by the linear foot, in place along the face of curb.
Payment. The contract price paid per linear foot for curb and gutter shall include full compensation for furnishing all labor, materials, tools, and equipment, and doing all the work involved in constructing curb and gutter as specified including furnishing and placing aggregate base, and preparing subgrade, and no additional compensation will be allowed therefore.
Remove Concrete (Sidewalk & Flatwork). The contractor shall remove existing curb ramps and flatwork sidewalk.
Measurement. Removal of Concrete (Sidewalk & Flatwork) will be measured by the square foot, in place.
Payment. The contract price will be paid per square foot and shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals for performing all work involved in the removal of existing concrete sidewalk, pedestrian ramps and driveways, clearing and grubbing of existing vegetation and including but not limited to saw cutting, removal of concrete, sand and base rock, excavation, stockpiling removed materials, hauling and disposal of removed materials, and cleaning of materials, as specified in these Construction Details and shown on the Plans, and no additional allowances will be made therefor.
Curb ramps. Curb and gutter may be poured monolithic with the curb ramp.
Curb Ramp Detectable Warning Surface: Pedestrian ramp detectable warning surface shall consist of raised truncated domes constructed with pedestrian ramps in conformance with the details shown on the plans and these special provisions. The detectable warning surface shall be Armor-Tile cast-in-place detectable warning surface or approved equal. The color of the detectable warning shall be yellow conforming to Federal Standard 595B, Color No. 33538.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
40 The finished surfaces of the detectable warning surface shall be free from blemishes. Installation will be per manufacturer’s instructions or as directed by the Engineer.
The manufacturer shall provide a written 5-year warranty for prefabricated detectable warning surfaces, guaranteeing replacement when there is a defect in the dome shape, color, fastness, sound-on-cane acoustic quality, resilience, or attachment. The warranty period shall begin upon final acceptance of the project.
Full compensation for furnishing, constructing, and installing curb ramp detectable warning surfaces shall be considered as included in the contract price paid for Wheelchair Ramp installation and no additional allowance will be made therefor.
Measurement. Curb ramps will be measured by the square foot in place. Curb and gutter adjacent to curb ramps will be measured and paid for as curb and gutter.
Payment. The contract price paid per square foot of curb ramps shall include full compensation for furnishing all labor, materials, tools, and equipment, and doing all the work involved in constructing curb ramps as specified including furnishing and placing aggregate base, preparing subgrade, and protecting existing traffic sign poles and foundations, and no additional compensation will be allowed therefore.
Sidewalks. Sidewalks shall be constructed in accordance with City Standard Drawing No. 102. Sidewalks shall not be poured monolithic with the curb and gutter unless otherwise approved by the Engineer.
Measurement. Sidewalks will be measured by the square foot in place. Curb and gutter, or vertical concrete retaining curb adjacent to sidewalks will be measured and paid for as curb and gutter, or retaining curb.
Payment. The contract price paid per square foot for sidewalks shall include full compensation for furnishing all labor, materials, tools, and equipment, and doing all the work involved in constructing sidewalks as specified including furnishing and placing aggregate base, preparing subgrade, and protecting existing traffic sign poles and foundations, and no additional compensation will be allowed therefore.
Valley Gutters. Valley gutters shall be poured with a cold joint at the connection to the existing valley gutter.
Valley gutters shall be constructed a minimum of nine (9) inches thick at the center and a minimum of nine and one half (9.5) inches thick at the outer edges.
Measurement. Valley gutters will be measured by the square foot in place.
Payment. The contract price paid per square foot for valley gutters shall include full compensation for furnishing all labor, materials, tools, and equipment, and doing all the work involved in constructing valley gutters as specified, including furnishing and placing aggregate base, and preparing subgrade, and no additional compensation will be allowed therefore.
Saw Cut Concrete. This work shall include saw cutting Portland Cement Concrete (PCC) sidewalks, driveway approaches, curb and gutters, and valley gutters at the locations shown on the Project Plans and at locations as directed by the Engineer. Except where the plans call for a full depth cut, the concrete shall be cut in a neat line to a minimum depth of 0.17 foot with a power driven saw before concrete is removed.
Payment. Full compensation for complying with this section of the Special Provisions shall be considered as included in the prices paid for the various contract items of work, and no additional compensation will be allowed therefore.
13-15. Remove and Replace Sign Post. This work shall include removal of existing sign posts within the new concrete construction area and reinstalling new removable sign post sleeves per detail and cast in the new concrete as directed at the locations shown on the Project Plans and at locations as directed by the Engineer. The City of Ukiah will provide the signs to the contractor to be installed on the new post.
Payment. Full compensation for complying with this section of the Special Provisions shall be paid as each including the post and base as a single unit.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
41 13-16. Storm Drain Pipe. All storm drains and related appurtenances shall be constructed in accordance with the Standard Specifications, the City of Ukiah Standard Plans, the Plans and these Special Provisions.
Materials. Storm drain pipe shall conform to the provisions of the Standard Specifications, the City of Ukiah Specifications, the Plans and these Special Provisions.
Storm drain pipe shall be High Density Polyethylene (HDPE). HDPE storm drain pipe shall conform to the provisions of Section 64, “Plastic Pipe” of the Standard Specifications. HDPE pipe shall be type S corrugated polyethylene pipe with a smooth inner lining and corrugated outer wall.
Excavation and Backfill. Excavation and backfill shall be in accordance with the Standard Specifications, the City of Ukiah Standard Plans, the Plans, these Special Provisions and as directed by the Engineer.
Prior to the start of excavation for storm drain installation, the contractor shall pothole to determine the exact horizontal and vertical location of all crossing utilities. Potholing shall consist of excavating with hand tools to whatever depth necessary in the proposed trench line for a distance of up to two feet on either side of the apparent utility crossings as indicated by the plans and by the USA mark-outs until the exact location of all utilities is established. If a marked utility cannot be located within four feet on either side of the USA mark-out, the Contractor shall immediately contact Underground Service Alert to re-mark the utility and notify the Engineer.
Trenches shall not be open longer than the time required to place the pipe and backfill to the adjoining grade. Trenches shall be backfilled the same day within allowable working hours.
If, during excavation for any storm drain pipe, material is encountered which is unsuitable as a foundation for such culvert or structure, such unsuitable material shall be removed to a depth as required by the Engineer and the resulting space shall be refilled with approved material.
Laying Pipe: Unless otherwise specifically permitted by the Engineer, all pipes shall be laid upgrade.
All pipe joints shall be sealed with use of a rubber gasket. A joint lubricant recommended by the pipe manufacturer shall be used on gasket sealed pipe.
Video Inspection of Storm Drain Pipe: All new and modified storm drain pipes and structures shall be inspected by video inspection completed by or provided by the contractor as witnessed by City inspection.
Measurement. Storm drain pipe, of the various types and sizes, will be measured by the lineal foot from center of structure to center of structure of connection point.
No separate measurement will be made for video inspection.
Payment. Storm Drain will be paid for at the contract price per lineal foot for specified types and sizes as installed, which price shall include full compensation for furnishing all labor, materials, tools, and equipment and doing all the work involved in placing storm drain as specified.
Full compensation for removing and disposal of existing storm drain pipe to be replaced as shown on the plans shall be considered as included in the contract prices paid per lineal foot for storm drain pipe and no additional allowance will be made therefore.
13-17. Drainage Structures. Drainage structures shall conform to the provisions in Section 70, “Miscellaneous Facilities,” of the Standard Specifications, City Standards and these Special Provisions.
Storm drain catch basin construction shall conform to the requirements of City Standard Nos. 403, 406 and 408, or as specified on the Plans. At the option of the Contractor, catch basins bases may be poured in place or furnished and install as precast units at the option of the Contractor.
Drop inlets shall be of the type and size as specified on the Plans. At the option of the Contractor, drop inlets and bases may be poured in place or furnished and installed as precast units.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
42 Concrete used for drainage structures shall conform to the provisions in Section 90-10, “Minor Concrete,” of the Standard Specifications. Portland Cement Concrete shall be Class A, conforming to the provision of Section 90, “Portland Cement Concrete,” of the Standard Specifications. Reinforcement shall be Grade 60 conforming to the provisions of Section 52, “Reinforcement,” of the Standard Specifications.
Connection of storm drain lines to existing storm drain structures shall conform to the requirements of Section 51-1.135, “Mortar,” of the Standard Specifications and these Special Provisions.
The Contractor shall break into the side of existing structures using a roto-hammer or other device approved by the Engineer. Sufficient concrete shall be removed to adequately connect the new storm drain without removing excess concrete material. No damage shall be done beyond the tie-in location as shown on the plans. Bar reinforcing and/or wire mesh reinforcing shall be neatly cut and removed. All waste concrete and reinforcing shall be removed in accordance with Section 7-1.13, “Disposal of Materials Outside the Highway Right-of-Way,” of the Standard Specifications.
The new storm drain line shall be installed such that it does not protrude into the existing drainage structure. The void around the new storm drain line shall be filled with mortar. The mortar inside the existing drainage structure shall be troweled smooth so there is a clean smooth connection.
Measurement. Drainage Structures, of various types, will be measured by each. No separate measurement will be made for connecting storm drain lines to existing drainage structures, miscellaneous iron and steel, and Class 2 aggregate base under drainage structures.
Payment. Drainage Structures, of the various types, will be paid for at the contract price per each for specified types and sizes as installed, which price shall include full compensation for furnishing all labor, materials, tools, and equipment and doing all the work involved in placing drainage structures as specified. 13-18. Water Main - 6” PVC Pipe – C900 Class 200. Full compensation will be measured and paid for at the contract unit price per linear foot, which price shall include full compensation for furnishing all labor, materials, tools and equipment and doing all the work involved in furnishing and installing water pipe including all pipe fittings and valves, concrete thrust blocks & pipe restraint as show on the plans, complete in place, all excavation & disposal of excavated material; hand digging to protect roots; root pruning; abandonment, temporary connections, removal and disposal of existing materials; connecting to new or existing pipe; dewatering and ground water disposal; controlled low strength material if used; temporary and permanent trench paving; obtaining and disposing of construction water; swabbing, disinfecting and testing; and any other items when required by the work or shown on the Plans, not specifically enumerated in the Plans or these specifications and no additional allowance will be made therefor. 13-19. Water Services. Full compensation for all 1” water service laterals, single meters and service connections will be measured and paid for at the contract unit price per item, which price shall include full compensation for furnishing all labor, materials, tools and equipment and doing all the work involved in furnishing and installing water lateral pipe, water meters and service connections including all pipe fittings, as show on the plans, complete in place; all excavation & disposal of excavated material; hand digging to protect roots; root pruning; abandonment, temporary connections, removal and disposal of existing materials; connecting to new or existing pipe; identifying, locating and connecting to the existing building water service connection 1-ft from the property boundary; dewatering and ground water disposal; controlled low strength material if used; temporary and permanent trench paving and any other items when required by the work or shown on the Plans, not specifically enumerated in the Plans or these specifications and no additional allowance will be made therefor.
13-20. Fire Hydrants. Full compensation for fire hydrants and laterals will be measured and paid for at the contract unit price per item, which price shall include full compensation for furnishing all labor, materials, tools and equipment and doing all the work involved in furnishing and installing fire hydrants including all pipe fittings, concrete thrust blocks & pipe restraint as show on the plans, complete in place, all excavation & disposal of excavated material; hand digging to protect roots; root pruning; abandonment, temporary connections, removal and disposal of existing materials; connecting to new or existing pipe; dewatering and ground water disposal; controlled low strength material if used; temporary and permanent trench paving; testing; and any other items when required by the work or shown on the Plans, not specifically enumerated in the Plans or these specifications and no additional allowance will be made therefor. 13-21. Temporary Blow Off. Full compensation for Temporary Blow Off will be measured and paid for at the contract unit price per item, which price shall include full compensation for furnishing all labor, materials, enclosures, labels,
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
43 coatings, concrete pads, temporary thrust restraint, hardware, tools and equipment and doing all the work involved in furnishing and installing temporary blow offs including all pipe fittings, as shown on the plans, complete in place; all excavation & disposal of excavated material; hand digging to protect roots; root pruning; abandonment, temporary connections, removal and disposal of existing materials; connecting to new or existing pipe; dewatering and ground water disposal; controlled low strength material if used; testing; and any other items when required by the work or shown on the Plans, not specifically enumerated in the Plans or these specifications and no additional allowance will be made therefor.
13-22. Abandon or Remove Water System Components. Full compensation for Abandon or Remove Water System Components (valves, pipelines, laterals) will be measured and paid for at the contract lump sum price, which price shall include full compensation for furnishing all labor, materials, tools and equipment, and doing all work involved in demolition and disposal of redundant water system components in conflict with the new construction, and no additional allowance will be made therefor.
13-23. Trench Bracing and Shoring. Full compensation for Trench Bracing and Shoring will be measured and paid for at the contract lump sum price, which price shall include full compensation for furnishing all labor, materials, tools and equipment, and doing all work involved in trench bracing and shoring, and no additional allowance will be made therefor.
13-24. Remove and Replace Existing Sanitary Sewer 8” Pipe. Full compensation for all 8” PVC Pipe – SDR 26 sanitary sewer pipe will be measured and paid for at the contract unit price per linear foot, which price shall include full compensation for furnishing all labor, materials, tools and equipment and doing all the work involved in furnishing and installing the sanitary sewer pipe, including all pipe fittings, as shown on the plans, complete in place; all excavation & disposal of excavated materials; connecting to new or existing pipe or manholes; dewatering and groundwater disposal; controlled low strength material if used; temporary and permanent trench paving; testing; CCTV inspection; and any other items when required by the work or shown on the Plans, not specifically enumerated in the Plans or these specifications, and no allowance will be made therefor.
Full compensation for Remove Existing Sanitary Sewer Pipe will be included in the installation of new sewer main as remove and replace. Full compensation for removal of existing sanitary sewer pipe shall be considered as included in the prices paid for the various contract items of work and no additional allowance will be made therefore. 13-25. Remove Existing Sanitary Sewer Manhole. Full compensation for Removal of Existing Sanitary Sewer Manhole will be measured and paid for at the contract unit price per each, which price shall include full compensation for furnishing all labor, materials, tools and equipment, and doing all the work involved in removing, demolishing and disposal of existing sanitary sewer manhole, and no additional allowance will be made therefor. 13-26. Install Sanitary Sewer Manhole. Full compensation for all 48” sanitary sewer manholes will be measured and paid for at the contract unit price per item, which price shall include full compensation for furnishing all labor, materials, tools and equipment and doing all the work involved in furnishing and installing the sanitary sewer manholes, as shown on the plans, complete in place; all excavation & disposal of excavated materials; connecting to new or existing pipe; dewatering and groundwater disposal; controlled low strength material if used; frames and covers; testing; and any other items when required by the work or shown on the Plans, not specifically enumerated in the Plans or these specifications, and no allowance will be made therefor.
13-27. Install Inline Sanitary Sewer Cleanout. Full compensation for all sanitary sewer inline cleanouts will be measured and paid for at the contract unit price per item, which price shall include full compensation for furnishing all labor, materials, tools and equipment and doing all the work involved in furnishing and installing the sanitary sewer laterals and cleanouts, including all pipe fittings, as shown on the plans, complete in place; all excavation & disposal of excavated materials; connecting to new or existing sewer main; all cleanouts frames and covers; dewatering and groundwater disposal; controlled low strength material if used; temporary and permanent trench paving; testing; and any other items when required by the work or shown on the Plans, not specifically enumerated in the Plans or these specifications, and no allowance will be made therefor. 13-28. Sewer Laterals and Cleanouts. Full compensation for all 4” sanitary sewer laterals and cleanouts will be measured and paid for at the contract unit price per item, which price shall include full compensation for furnishing all labor, materials, tools and equipment and doing all the work involved in furnishing and installing the sanitary sewer laterals and cleanouts, including inspecting existing live laterals and marking the alignment back to the point of connection to the building; all pipe fittings, as shown on the plans, complete in place; all excavation & disposal of
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
44 excavated materials; connecting to sanitary sewer main; connecting to existing sanitary sewer lateral 1-ft from the property boundary; all cleanouts frames and covers; dewatering and groundwater disposal; controlled low strength material if used; temporary and permanent trench paving; testing; and any other items when required by the work or shown on the Plans, not specifically enumerated in the Plans or these specifications, and no allowance will be made therefor.
13-29. Mobilization and Demobilization. Full compensation for Mobilization, Demobilization and Final Cleanup will be made in two (2) equal payments at the lump sum allowance in the Bid Schedule, which price shall constitute full compensation for all such work. The scope of work for mobilization shall include, but not limited to, obtaining all bonds, insurance and permits, moving onto the site of all plant and equipment, submittal and approval of a schedule of values for lump sum items, and obtaining approval for all shop drawings and materials. Payment for demobilization and final cleanup shall occur when all required items per the Contract are fulfilled and the site is free of equipment and clean and ready for use by the public. The bid amount for Mobilization, Demobilization and Final Cleanup items shall not exceed 2.5% of the total construction contract sub-total bid price. 13-30. Construction Surveying. Construction surveying including horizontal and vertical control and staking shall be the responsibility of the Contractor. Vertical and horizontal control is to be established from the existing Control Points shown on the Plans. Vertical Control Points are shown on the Plans.
Measurement and Payment. Full compensation for Construction Survey will be measured and paid for at the contract lump sum price and shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals for performing all work involved in establishing and maintaining vertical control and horizontal control, staking, and related construction surveying required to perform the Work, and no additional allowances will be made therefor.
13-31. Clearing and Grubbing. Clearing and grubbing shall conform to the provisions in Section 16, “Clearing and Grubbing,” of the Caltrans Standard Specifications, the City Standards and these Special Provisions. Concrete removal shall conform to applicable provisions of Section 15-3 of the Standard Specifications and these Special Provisions.
The Contractor’s attention is directed to Section 7-1.11, “Preservation of Property” of the Caltrans Standard Specifications.
All concrete which is to be removed from sidewalk, curb, gutter, and gutter pan, shall be removed to the nearest score mark or construction joint as directed by the Engineer unless otherwise noted on plans.
All trimming and/or removal of trees, bushes or other vegetation within project limits will be completed as part of the line item work included with removal and construction of concrete.
Reinforcing steel may be encountered in portions of concrete to be removed and no additional allowance will be made for the removal of such steel.
All improvements which are not planned to be removed as part of this work, but are damaged or destroyed by reason of the Contractor’s operations shall be replaced in kind or restored to a condition as good as when the Contractor encountered the work at the Contractor’s expense.
The Contractor shall dispose of all debris off site and in a legal manner.
Payment: Full compensation for clearing and grubbing shall be considered as included in the prices paid for the various contract items of work and no additional allowance will be made therefore.
SECTION 14. EXCLUSIONS FROM GENERAL CONDITIONS
14-01. Provisions to be Excluded from General Conditions. The following designated provisions of the General Conditions are hereby determined to be inapplicable to the proposed work and, therefore, are hereby excluded from the terms of the Notice to Bidders, Proposal, Agreement and other contract documents as though entirely omitted from said General Conditions:
(1) Section 6-02. Office at the Site
(2) Section 7-03. Surveys
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
45 No other exclusions.
SECTION 15. AMENDMENTS TO GENERAL CONDITIONS
15-01. Sections of General Conditions to be Amended.
The following designated sections of the Special Provisions are hereby amended to read as follows:
No amendments.
BID SUBMITTAL CHECKLIST
The following is a checklist to assist you in your submission of your bid documents. Please make sure you include the following when submitting your bid documents to reduce the risk of having your bid rejected:
Did you include?...
o Proposal (Page 48)
Unit prices filled out clearly.
Extended prices filled out clearly and calculated correctly Total bid amount filled out clearly and calculated correctly Sign the proposal, and provide complete information
CLSB No. and expiration date
Department of Industrial Relations Public Works Contractor Registration Number o Fair Employment Practices Certification (Page 51)
Filled out completely per instruction
o Worker’s Compensation Certificate (Page 52)
Filled out completely per instruction
o Certification of Non-Discrimination in Employment (Page 53) Filled out completely per instruction
o List of Proposed Subcontractors (Page 54)
Filled out completely per instruction
o Statement of Experience (Page 55)
o Signature of Bidder (Page 56)
Filled out completely per instruction
Authorized signature provided
o Bidder’s Bond (Page 57)
Filled out completely per instruction
o Non-Collusion Affidavit (Page 58)
Filled out completely per instruction
Notarized
o Addenda Issued
Check the City website for any addenda issued: www.cityofukiah.com/purchasing.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
46 CITY OF UKIAH
MENDOCINO COUNTY, CALIFORNIA
PROPOSAL
FOR
DORA STREET UTILITY IMPROVEMENT PROJECT
SPECIFICATION NO. 19-01
The undersigned, as bidder, declares that he or she has examined thoroughly all of the contract documents herein contained, that this proposal is made without collusion with any other person, firm or corporation and that all laws and ordinances relating to the interest of public officers in this contract have been complied with in every respect.
AND he or she proposes and agrees, if this proposal is accepted, 1) that he or she will contract with the City of Ukiah, Mendocino County, California, in the form of the copy of the agreement herein contained
a) to provide all necessary machinery, tools, apparatus and other means of construction; b) to furnish all materials;
c) to provide all superintendence, overhead expenses and all labor and expenses of whatever nature necessary to complete the job in conformity with the specifications and drawings and other contract provisions herein or reasonably implied hereby or as necessary to complete the work in the manner and within the time named herein and according to the requirements and to the reasonable satisfaction of the City Engineer;
d) to pay all charges of freight transportation and hauling; 2) that he or she indemnifies the City against any loss or damage arising from any act of the undersigned as Contractor; and
3) that he or she will accept as full payment therefor the following sums:
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
47 BIDDING SCHEDULE
In the case of any discrepancy between the unit price and the total set forth for the item, the unit price shall prevail; provided, however, that if the amount set forth as a unit price is ambiguous, unintelligible or uncertain for any reason, or is omitted, or in the case of lump sum items, is not the same amount as the entry in the “Total” column, then the amount set forth in the “Total” column for the item shall prevail in accordance with the following:
1. As to lump sum items, the amount set forth in the “Total” column shall be the unit price;
2. As to unit basis items, the amount set forth in the “Total” column shall be divided by the estimated quantity for the item and the price thus obtained shall be the unit price.
The Total Base Bid shall be the sum of the items in the “Total” column. In case of discrepancy between the sum of the items in the “Total” column and the amount entered as Total Base Bid, the sum of the “Total” column items shall prevail.
The bid comparison will be based on the sum of the items in the “total” column for each bidder.
The Unit prices for the various Construction Items below include all costs associated with the General Conditions, Special Provisions, Requirements of the Construction Contract, and represent the total, complete, in-place cost for each specific Construction Item in accordance with the Construction Documents, including all elements, work components, accessories, and connections, shown in applicable details or required to yield a complete, sound and functional component or system appropriate for its intended function, whether or not such is specifically described or listed in any description of measurement or payment. The total amount of the Construction items below shall represent the total and complete cost of the fully functional Project. All work not specifically listed below be required to complete the work of the various construction items and the cost of such shall be considered as included throughout the various unit prices indicated.
Lowest bid will be based on the lowest Base Bid.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
48 NAME OF BIDDER:
SPEC #: 19-01
PROJECT NAME: DORA STREET UTILITY IMPROVEMENT PROJECT
ITEM
NO. DESCRIPTION UNIT QUANTITY UNIT PRICE EXTENDED PRICE 1 TRAFFIC CONTROL LS 1
2 MOBILIZATION / DEMOBILIZATION LS 1
3 CONSTRUCTION SURVEY LS 1
4 PUBLIC NOTIFICATION LS 1
5 ROADWAY EXCAVATION CY 10,838
6 REMOVE UNSUITABLE MATERIAL CY 100
7 SOIL STABILIZATION FABRIC SY 21,265
8 CLASS 2 AGGREGATE BASE CY 7,225
9 HOT MIX ASPHALT (TYPE A) TN 7,315
10 REMOVE 6-INCH SEWER MAIN
AND REPLACE WITH 8-INCH
SEWER MAIN
LF 2,059
11 REMOVE AND REPLACE 6-INCH
SEWER MAIN LF 144
12 4 INCH SEWER LATERAL WITH
CLEANOUT EA 23
13 INSTALL INLINE 8" SEWER
CLEANOUT EA 4
14 INSTALL 48 INCH SANITARY
SEWER MANHOLE EA 11
15 REMOVE 48 INCH SANITARY
SEWER MANHOLE EA 12
16 TRENCH BRACING AND SHORING LS 1
17 STORM DRAIN INLET - TYPE GO
D73E EA 2
18 STORM DRAIN INLET - MODEL 4AC EA 4
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
49 ITEM
NO. DESCRIPTION UNIT QUANTITY UNIT PRICE EXTENDED PRICE 19 STORM DRAIN INLET - MODEL 4AC
WITH 6Y PELICAN FIBERGLASS
COMPONENTS
EA 1
20 STORM DRAIN JUNCTION BOX -
MODEL JB3636 EA 2
21 CONNECT 24" HDPE STORM
DRAIN TO EXISTING BASIN EA 1
22 STORM DRAIN - 12 INCH HDPE LF 32
23 STORM DRAIN - 18 INCH HDPE LF 633
24 STORM DRAIN - 24 INCH HDPE LF 567
25 6 INCH PVC WATER MAIN CLASS
200 LF 4,217
26 1" WATER SERVICE PLUMBED
FOR 3/4" METER EA 31
27 1" WATER SERVICE PLUMBED
FOR 1" METER EA 3
28 2" COMPOUND WATER METER EA 1
29 6" FIRE SERVICE LINE EA 1
30 FIRE HYDRANT AND LATERAL
ASSEMBLY EA 8
31 REMOVE AND SALVAGE
EXISITING FIRE HYDRANT EA 8
32 ABANDON OR REMOVE WATER
SYSTEM COMPONENTS LS 1
33 TEMPORARY BLOW OFF EA 2
34 WATER MAIN TIE IN EA 21
35 ADJUST MANHOLE TO GRADE EA 11
36 ADJUST VALVE BOX TO GRADE EA 49
37 REMOVE CONCRETE (CURB &
GUTTER) LF 1,046
38 REMOVE CONCRETE (SIDEWALK
& FLATWORK SF 6,473
39 REMOVE CONCRETE (VALLEY
GUTTER) SF 3,634
40 MINOR CONCRETE (CURB &
GUTTER) SF 1,046
41 MINOR CONCRETE (CURB RAMP) SF 5,117
42 MINOR CONCRETE (SIDEWALK) SF 1,356
43 MINOR CONCRETE (VALLEY
GUTTER) SF 3,634
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
50 ITEM
NO. DESCRIPTION UNIT QUANTITY UNIT PRICE EXTENDED PRICE 44 MINOR CONCRETE (CURB) SF 28
45 REMOVE & REPLACE ROADSIDE
SIGN POST EA 17
46 TRAFFIC STRIPE (DETAIL 1) LF 1,536
47 TRAFFIC STRIPE (DETAIL 21) LF 1,200
48 TRAFFIC STRIPE (DETAIL 27B) LF 4,225
49 TRAFFIC STRIPE (DETAIL 39) LF 4,225
50 TRAFFIC STRIPE (DETAIL 39A) LF 1,200
51 THERMO X-WALK & PAVEMENT
MARKING SF 3,223
52 PAVEMENT MARKERS EA 15
TOTAL BID PRICE $
We, the undersigned, acknowledge that the City Council has reserved the right to reject any or all bids and to determine which proposal is, in its opinion, the lowest responsive bid from a responsible bidder and that which it deems in the best interest of the City to accept. We, the undersigned, further agree, if this proposal shall be accepted, to sign the agreement and to furnish the required bonds with satisfactory surety, or sureties, within fifteen (15) calendar days after written notice that the contract is ready for signature; and, if the undersigned shall fail to contract, as aforesaid, it shall be understood that he or she has abandoned the contract and that, therefore, this proposal shall be null and void and the proposal guaranty accompanying this proposal, or the amount of said guaranty, shall be forfeited to and become the property of the City. Otherwise, the proposal guaranty accompanying this proposal shall be returned to the undersigned.
Witness our hands this day of ___________________, 20____.
Licensed in accordance with an act providing for the registration of California Contractors License No. ___________, expiration date _____________.
THE CONTRACTOR'S LICENSE NUMBER AND EXPIRATION DATE STATED HEREIN ARE MADE UNDER PENALTY OF PERJURY.
Department of Industrial Relations Public Works Contractor Registration Number:_____________________ Signature of bidder or bidders, with business name, address, phone number and fax number:
_________________________________________________________________ _________________________________________________________________ _________________________________________________________________ _________________________________________________________________ Notice: In the case of a corporation, give below the addresses of the principal office thereof and names and addresses of the President, Secretary, Treasurer.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
51 _________________________________________________________________ _________________________________________________________________ _________________________________________________________________
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
52 FAIR EMPLOYMENT PRACTICES CERTIFICATION
TO:_____________________________________________________________ ________________________________________________________________ The undersigned, in submitting a bid for performing the following work by Contract, hereby certifies that he or she has or will meet the standards of affirmative compliance with the Fair Employment Practices requirements of the Special Provisions contained herein.
DORA STREET UTILITY IMPROVEMENT PROJECT
________________________________________________________________ (Signature of Bidder)
Business Mailing Address:
_________________________________________________
_________________________________________________
_________________________________________________
Business Location:
_________________________________________________
_________________________________________________
(The bidder shall execute the certification of this page prior to submitting his or her proposal.)
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
53 WORKER'S COMPENSATION CERTIFICATE
I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for Worker's Compensation or undertake self-insurance in accordance with the provisions of that code and I will comply with such provisions before commencing the performance of the work of this contract.
Witness my hand this________ day of _______________, 20____ Signature of Bidder, with Business Address:
__________________________________________________
__________________________________________________
__________________________________________________
__________________________________________________
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
54 CERTIFICATION OF NONDISCRIMINATION IN EMPLOYMENT
The bidder represents that he or she has/has not, participated in a previous contract or subcontract subject to either the equal opportunity clause herein or the clause contained in Section 301 of Executive Order 10925; that he or she has/has not, filed all required compliance reports; and that representations indicating submission of required compliance prior to subcontract awards.
Signature and address of Bidder:
__________________________________________________ Date_____________ __________________________________________________
__________________________________________________
__________________________________________________
(This certification shall be executed by the bidder in accordance with Section 60-1.6 of the Regulations of the President's Committee on Equal Employment Opportunity for implementing Executive Orders 10925 and 11114.)
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
55 LIST OF PROPOSED SUBCONTRACTORS
In compliance with the provisions of Sections 4100-4108 of the California Public Contract Code and any amendments thereof, each bidder shall set forth (a) the name and location of the place of business of each subcontractor who will perform work or labor or render service in or about the construction site or a subcontractor licensed by the State of California who, under subcontract to the prime contractor, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications in an amount in excess of onehalf of 1 percent of the total bid and (b) the California Contractor License Number for each subcontractor, and (c) the portion of the work to be done by each subcontractor.(See General Conditions Section 1-09.) Include with the name of each sub-contractor their Department of Industrial Relations Public Works Contractor Registration Number.
SUBCONTRACTOR
NAME
SUBCONTRACTOR
LICENSE NUMBER
SUBCONTRACTOR
DIR REGISTRATION
NUMBER
SUBCONTRACTOR
BUSINESS
ADDRESS
DESCRIPTION OF WORK
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
56 STATEMENT OF EXPERIENCE OF BIDDER
The bidder is required to state below what work of similar magnitude or character he or she has done and to give references that will enable the City Council to judge of his or her experience, skill and business standing and his or her ability to conduct work as completely and rapidly as required under the terms of the contract. ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
57 SIGNATURE(S) OF BIDDER
Accompanying this proposal is ___________________________________ (insert the words "cash ($)", "cashier's check" or "bidder's bond", as the case may be) in an amount equal to at least 10 percent of the bid.
The names of all persons interested in the foregoing proposal as principals are as follows:
IMPORTANT NOTICE: If bidder or other interested person is a corporation, provide the legal name of corporation and also the names of the president, secretary, treasurer and manager thereof. If a co-partnership, provide the true name of firm and also the names of all individual co-partners composing the firm. If bidder or other interested person is an individual, provide the first and last names in full.
_________________________________________________________________ _________________________________________________________________ _________________________________________________________________ Licensed in accordance with an act providing for the registration of Contractors:
License No. ______________________________, License Expiration Date .
Signature(s) of Bidder: ______________________________________________ ______________________________________________
______________________________________________
NOTE: If bidder is a corporation, the legal name of the corporation shall be set forth above together with the signature of the officer or officers authorized to sign contracts on behalf of the corporation; if bidder is a copartnership, the true name of the firm shall be set forth above together with the signature of the partner or partners authorized to sign contracts in behalf of the co-partnership; and if bidder is an individual, his or her signature shall be placed above. If a member of a partnership, a Power of Attorney must be on file with the Department prior to opening bids or submitted with the bid; otherwise, the bid will be disregarded as irregular and unauthorized.
Business address: ___________________________________________________ ___________________________________________________
Place of residence: ___________________________________________________ ___________________________________________________
Dated: __________________
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
58 CITY OF UKIAH
Mendocino County, California
BIDDER'S BOND
KNOW ALL MEN BY THESE PRESENTS,
That we, ______________________________________________________________ ________________________________________________________________, as PRINCIPAL and ________________________________________________________________ ________________________________________________________________, as SURETY, are held and firmly bound unto the City of Ukiah in the penal sum of 10 PERCENT OF THE TOTAL AMOUNT OF THE BID of the Principal above named, submitted by said Principal to the City of Ukiah, as the case may be, for the work described below, for the payment of which sum in lawful money of the United States, well and truly to be made, to the City Clerk to which said bid was submitted, we bind ourselves, our heirs, executors, administrators and successors jointly and severally, firmly by these presents. In no case shall the liability of the surety hereunder exceed the sum of $____________________
THE CONDITION OF THIS OBLIGATION IS SUCH,
That whereas the Principal has submitted the above mentioned bid to the City of Ukiah, as aforesaid, for certain construction specifically described as follows, for which bids are to be opened at the Office of the City Clerk, Ukiah Civic Center, Ukiah, California, on xxxxxxxx for DORA STREET UTILITY IMPROVEMENT PROJECT.
NOW, THEREFORE, If the aforesaid Principal is awarded the contract and, within the time and manner required under the specifications, after the prescribed forms are presented to him or her for signatures, enters into a written contract, in the prescribed form, in accordance with the bid and files two bonds with the City of Ukiah, one to guarantee faithful performance and the other to guarantee payment for labor and materials, as required by law, then this obligation shall be null and void; otherwise, it shall be and remain in full force and virtue.
IN WITNESS WHEREOF, we have hereunto set our hands and seals on this ______ day of ________________, A.D. 20_____.
__________________________________________________(Seal) __________________________________________________(Seal) __________________________________________________(Seal) Principal
__________________________________________________(Seal) __________________________________________________(Seal) __________________________________________________(Seal) Surety
Address: __________________________________________________________ __________________________________________________________ __________________________________________________________
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
59 NON-COLLUSION AFFIDAVIT
Note: Bidder shall execute the affidavit on this page prior to submitting his or her bid.
To City Council, City of Ukiah:
The undersigned in submitting a bid for performing DORA STREET UTILITY IMPROVEMENT PROJECT by contract, being duly sworn, deposes and says:
that he or she has not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with such contract.
__________________________________________________
__________________________________________________
__________________________________________________
Signature(s) of Bidder
Business Address:__________________________________________________ __________________________________________________
__________________________________________________
Place of Residence:__________________________________________________ __________________________________________________
__________________________________________________
NOTARIZATION
Subscribed and sworn to before me this ______ day of _________, 20____. __________________________________________________
Notary Public in and for the County of______________________________, State of California.
My Commission Expires ________________________, 20 ____.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
60 CITY OF UKIAH
Mendocino County, California
AGREEMENT
FOR
DORA STREET UTILITY IMPROVEMENT PROJECT
SPECIFICATION NO. 19-01
THIS AGREEMENT, made this ______ day of ___________________, 20____, by and between the City of Ukiah, Mendocino County, California, hereinafter called the City and _______________________ hereinafter called the Contractor,
WITNESSETH:
WHEREAS, the City has caused to be prepared in accordance with law, specifications, drawings and other contract documents for the work herein described and shown and has approved and adopted these contract documents, specifications and drawings and has caused to be published in the manner and for the time required by law a notice to bidders inviting sealed proposals for doing the work in accordance with the terms of this contract and
WHEREAS, the Contractor, in response to the notice to bidders, has submitted to the City a sealed proposal accompanied by a proposal guaranty in an amount of not less than 10 percent of the bid price for the construction of the proposed work in accordance with the terms of this contract and WHEREAS, the City, in the manner prescribed by law, has publicly opened, examined and canvassed the proposals submitted and as a result has determined and declared the Contractor to be the lowest and best regular responsible bidder for the work and for the sums named in the proposal, NOW, THEREFORE, THIS AGREEMENT WITNESSETH:
Article 1. Work to be Done and Contract Days Allowed.
That the Contractor shall provide all necessary machinery, tools, apparatus and other means of construction; shall furnish all materials, superintendence, overhead, expenses, all labor and expenses of whatever nature necessary for completion of the work in conformity with the Special Provisions and other contract documents hereto attached and according to such instructions as may be given by the Engineer. The Contractor shall complete the work within one hundred eighty (180) working days. Contract days shall be counted starting with the 10th day following receipt of notice that the contract has been executed by the City. Contractor, at his or her option, may begin work prior to start of counting contract days, however, in no event shall the Contractor start work without giving notification to the Engineer at least 72 hours prior to the start of work, without obtaining an encroachment permit from the City, or without having submitted certificates of insurance that have been accepted and approved by the Engineer
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
61 Article II. Contract Prices.
That the City shall pay the Contractor the prices stated in the proposal submitted by the Contractor, for complete performance of the contract by the Contractor. The Contractor hereby agrees to accept the prices as full compensation for all material and appliances necessary to the work, for all labor and use of tools and other implements necessary to execute the work contemplated in this contract; for all loss or damage arising out of the nature of the work or from the action of the elements, or from any unforeseen obstructions or difficulties which may be encountered in the prosecution of the work; for all risks of every description connected therewith; for all expenses of the work, as herein specified; for all liability and other insurance, for all overhead and other expenses incident to the work; all according to the Contract Drawings, the Special Provisions, the Details, the instructions and the requirements of the City.
Article III. Labor Discrimination.
Attention is directed to Section 1735 of the Labor Code, which reads as follows:
"No discrimination shall be made in the employment of persons upon public works because of the race, color, national origin or ancestry, or religion of such persons and every contractor for public works violating this section is subject to all the penalties imposed for a violation of this chapter." In connection with the performance of work under this contract, the Contractor agrees as follows:
(a) The Contractor will not willfully discriminate against any employee or an applicant for employment because of race, color, religion, ancestry, or national origin. The Contractor will take affirmative action to ensure that applicants are employed and that employees are treated during employment without regard to their race, color, religion, ancestry, or national origin. Such action shall include, but not be limited to, the following: employment, upgrading, demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided by the awarding authority setting forth the provisions of this Fair Employment Practice section. (b) The Contractor will send to each labor union or representative of workers with which he or she has a collective bargaining agreement or other contract or understanding, a notice, to be provided by the awarding authority, advising the said labor union or worker's representative of the Contractor's commitments under this section, to employees and applicants for employment. (c) The Contractor will permit access to his or her records of employment, employment advertisements, application forms and other pertinent data and records by the Fair Employment Practices Commission, City of Ukiah or any other appropriate agency of the State of California designated by the awarding authority, for the purposes of investigation to ascertain compliance with the Fair Employment Practices section of this contract. (d) A finding of willful violation of the Fair Employment Practices section of this Contract or of the Fair Employment Practices Act shall be regarded by the awarding authority as a basis for determining the Contractor to be not a "responsible bidder" as to future contracts for which such Contractor may submit bids, for revoking the Contractor's pre-qualification rating, if any and for refusing to establish, reestablish or renew a pre-qualification rating for the Contractor.
The City of Ukiah shall deem a finding of willful receipt of written notice from the Fair Employment Practices Act to have occurred upon that it has investigated and determined that the Contractor has violated the Fair Employment Practices Act and has issued an order under Labor Code Section 1426 or obtained an injunction under Labor Code Section 1429.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
62 Upon receipt of such written notice from the Fair Employment Practices Commission, the City shall notify the Contractor that unless he or she demonstrates to the satisfaction of the awarding authority within a stated period that the violation has been corrected, his or her pre-qualification rating will be revoked at the expiration of such period. (e) The Contractor agrees that should the City determine that the Contractor has not complied with the Fair Employment Practices section of this Contract, then pursuant to Labor Code Section 1735 and 1775 the Contractor shall, as a penalty to the City, forfeit for each calendar day or portion thereof, for each person who was denied employment as a result of such non-compliance, the penalties provided in the Labor Code for violation of prevailing wage rates. Such monies may be recovered from the Contractor. The City may deduct any such damages from any monies due the Contractor. (f) Nothing contained in this Fair Employment Practices section shall be construed in any manner of fashion so as to prevent the City or the State of California from pursuing any other remedies that may be available at law.
(g) Prior to awarding the Contract, the Contractor shall certify to the awarding authority that he or she has or will meet the following standards for affirmative compliance, which shall be evaluated in each case by the awarding authority:
(1) The Contractor shall provide evidence, as required by the City that he or she has notified all supervisors, foremen and other personnel officers in writing of the content of the anti-discrimination clause and their responsibilities under it.
(2) The Contractor shall provide evidence, as required by the City, that he or she has notified all sources of employees’ referrals (including unions, employment agencies, advertisements, Department of Employment) of the content of the anti-discrimination clause. (3) The Contractor shall file a basic compliance report, as required by the City. Willfully false statements made in such reports shall be punishable as provided by law. The compliance report shall also spell out the sources of the work force and who has the responsibility for determining whom to hire, or whether or not to hire.
(4) Personally, or through his or her representatives, the Contractor shall, through negotiations with the unions with whom he or she has agreements, attempt to develop an agreement which will:
a. Spell out responsibilities for nondiscrimination in hiring, referral, upgrading and training. b. Otherwise implement an affirmative anti-discrimination program in terms of the unions' specific areas of skill and geography to the end that qualified minority workers will be available and given and equal opportunity for employment.
(5) The Contractor shall notify the City of opposition to the anti-discrimination clause by individuals, firms or organizations during the period of its pre-qualification. (h) The Contractor will include the provisions of the foregoing paragraphs 1 through 5 in every first tier subcontract so that such provisions will be binding upon each such subcontractor. (i) The "Fair Employment Practices Certification" must be completed and signed prior to the time of submitting the bid.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
63 Article IV. Parts of the Contract.
That the complete contract consists of the following documents, all of which shall be considered a part of this agreement.
1. Notice to Bidders
2. Wage Rates
3. General Conditions
4. Technical Specifications
5. Proposal
6. Fair Employment Practices Certification
7. Agreement
8. Contract Bonds
9. Contract Drawings and Construction Details
10. Standard Drawings
11. Indemnification Agreement
IN WITNESS WHEREOF, this contract being executed in duplicate and the parties having caused their names to be signed by authority of their duly authorized office this _____ day of _____________, 20____.
CITY OF UKIAH, MENDOCINO COUNTY, CALIFORNIA
By: ______________________________________________________________
CITY MANAGER, CITY OF UKIAH
Attest: ______________________________________________________________
CITY CLERK, CITY OF UKIAH
By: ______________________________________________________________
CONTRACTOR
Attest: ______________________________________________________________ Title: ______________________________________________________________ The foregoing contract is approved as to form and legality this ______ day of ______________, 20 ____. __________________________________________________
CITY ATTORNEY, CITY OF UKIAH
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
64 INDEMNIFICATION AGREEMENT
This Indemnification Agreement is made and entered in Ukiah, California, on _________________, 20____, by and between the City of Ukiah (Ukiah) and ______________________________________ (Contractor).
Contractor is
_________________________________________________________________________________ ___________________________________________ for Ukiah.
As a condition of issuing the work order, attached hereto, Ukiah requires assurance that Contractor will protect Ukiah from damage or damage claims which arise from its performance of the work.
Accordingly, Contractor agrees as follows:
1. Indemnification. Contractor shall indemnify and hold harmless Ukiah and its officers, agents, and employees from and against any claim, loss, or damage, including the legal and other costs of defending against any claim of damage or loss which arises out of the Contractor’s negligent or wrongful performance under the work order attached hereto, except for claims, losses, or damages resulting from the sole and exclusive negligence or other wrongful conduct of Ukiah or its officers, agents and employees.
CONTRACTOR
BY: _______________________________________________
TITLE: _______________________________________________
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
65 CITY OF UKIAH
Mendocino County, California
FAITHFUL PERFORMANCE BOND
KNOW ALL MEN BY THESE PRESENTS,
That we the undersigned, ______________________________________________________________ __________________________________________________________________________________, AS PRINCIPAL, and
__________________________________________________________________________________,
AS SURETY,
are held firmly bound unto THE CITY OF UKIAH, hereinafter called the “City”, in the penal sum of dollars ($____________________)
for the payment of which sum we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally.
WHEREAS, the Principal has entered into a certain Contract with the City, dated __________, 20_____, a copy of which is hereto attached and made a part hereof, NOW, THEREFORE, the condition of this obligation is such that if the Principal shall in all respects fully perform the Contract and all duly authorized modifications thereof, during its original term and any extensions thereof that may be granted and during any guaranty period for which the Contract provides, and if the Principal shall fully satisfy all claims, arising out of the prosecution of the work under the Contract and shall fully indemnify the City for all expenses which it may incur by reason of such claims, including its attorney's fees and court costs, and if the Principal shall make full payment to all persons supplying labor, services, materials, or equipment in the prosecution of the work under the Contract, in default of which such persons shall have a direct right of action hereupon; and if the Principal shall pay or cause to be paid all sales and use taxes payable as a result of the performance of the Contract as well as payment of gasoline and special motor fuels taxes in the performance of the Contract and all motor vehicle fees required for commercial motor vehicles used in connection with the performance of the Contract, then this obligation shall be void; otherwise, it shall remain in full force and effect.
No modification of the Contract or extension of the term thereof, nor any forbearance on the part of the City shall in any way release the Principal or the Surety from liability hereunder. Notice to the Surety of any such modification, extension, or forbearance is hereby waived.
IN WITNESS WHEREOF, the aforesaid Principal and Surety have executed this instrument and affixed their seals hereto, this ________ day of _______________,20_______.
In the presence of:
WITNESS:
_________________________________
________________________________(SEAL)
(Individual Principal)
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
66 WITNESS:
____________________________________
______________________________(SEAL)
(Corporate Principal)
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)
ATTEST:
________________________________
(Corporate Principal) Affix
Corporate
Seal
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)
ATTEST:
____________________________ ________________________________ Affix (Corporate Surety) Corporate
Seal
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)
The rate of premium on this bond is $___________________________ per thousand.
The total amount of premium charges is $____________________________.. (The above is to be filled in by Surety Company). (Power of Attorney of person signing for Surety Company must be attached).
(CERTIFICATE AS TO CORPORATE PRINCIPAL)
I,_________________________________________, certify that I am the ______________________________ Secretary of the corporation named as Principal in the foregoing bond; that _______________________________________, who signed the said bond on behalf of the Principal, was then ____________________________________________ of said corporation; that I know his signature, and that his signature thereto is genuine; and that said bond was duly signed, sealed, and attested to for and in behalf of said corporation by authority of its governing body. ____________________________________________ Affix Corporate Seal
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
67 CITY OF UKIAH
Mendocino County, California
MATERIAL AND LABOR BOND
KNOW ALL MEN BY THESE PRESENTS,
That we the undersigned, ______________________________________________________ __________________________________________________________________________, AS PRINCIPAL, and
__________________________________________________________________________ __________________________________________________________________________, AS SURETY, are held firmly bound unto THE CITY OF UKIAH, hereinafter called the “City” in the penal sum of dollars ($____________________) for the payment of which sum we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally.
WHEREAS, the Principal has entered into a certain Contract with the City, dated _________________, 20_____, a copy of which is hereto attached and made a part hereof, NOW, THEREFORE, the condition of this obligation is such that if the Principal shall in all respects fully perform the Contract and all duly authorized modifications thereof, during its original term and any extensions thereof that may be granted and during any guaranty period for which the Contract provides, and if the Principal shall fully satisfy all claims, arising out of the prosecution of the work under the Contract and shall fully indemnify the City for all expenses which it may incur by reason of such claims, including its attorney's fees and court costs, and if the Principal shall make full payment to all persons supplying labor, services, materials, or equipment in the prosecution of the work under the Contract, in default of which such persons shall have a direct right of action hereupon; and if the Principal shall pay or cause to be paid all sales and use taxes payable as a result of the performance of the Contract as well as payment of gasoline and special motor fuels taxes in the performance of the Contract and all motor vehicle fees required for commercial motor vehicles used in connection with the performance of the Contract, then this obligation shall be void; otherwise, it shall remain in full force and effect.
No modification of the Contract or extension of the term thereof, nor any forbearance on the part of the City shall in any way release the Principal or the Surety from liability hereunder. Notice to the Surety of any such modification, extension, or forbearance is hereby waived.
IN WITNESS WHEREOF, the aforesaid Principal and Surety have executed this instrument and affixed their seals hereto, this ________ day of _______________,20_______.
In the presence of:
WITNESS:
____________________________________
________________________________(SEAL)
(Individual Principal)
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
68 WITNESS:
____________________________________
______________________________(SEAL)
(Corporate Principal)
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)
ATTEST:
________________________________
(Corporate Principal) Affix
Corporate
Seal
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)
ATTEST:
____________________________ ________________________________ Affix (Corporate Surety) Corporate
Seal
___________________________________
(Business Address)
___________________________________
(City/State/Zip Code)
The rate of premium on this bond is $___________________________ per thousand.
The total amount of premium charges is $____________________________.. (The above is to be filled in by Surety Company). (Power of Attorney of person signing for Surety Company must be attached).
(CERTIFICATE AS TO CORPORATE PRINCIPAL)
I,_________________________________________, certify that I am the ______________________________ Secretary of the corporation named as Principal in the foregoing bond; that _______________________________________, who signed the said bond on behalf of the Principal, was then ____________________________________________ of said corporation; that I know his signature, and that his signature thereto is genuine; and that said bond was duly signed, sealed, and attested to for and in behalf of said corporation by authority of its governing body. ____________________________________________ Affix Corporate Seal
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
69 DIRECTIONS FOR PREPARATION OF PERFORMANCE AND MATERIAL AND LABOR BOND
1. Individual sureties, partnerships, or corporations not in the surety business will not be acceptable.
2. The name of the Principal shall be shown exactly as it appears in the Contract.
3. The penal sum shall not be less than required by the Specifications.
4. If the Principals are partners or joint venturers, each member shall execute the bond as an individual and state his place of residence.
5. If the Principal is a corporation, the bond shall be executed under its corporate seal.
If the corporation has no corporate seal, it shall so state and affix a scroll or adhesive seal following the corporate name.
6. The official character and authority of the person(s) executing the bond for the Principal, if a corporation, shall be certified by the Secretary or Assistant Secretary thereof under the corporate seal, or copies attached to such records of the corporation as will evidence the official character and authority of the officer signing, duly certified by the Secretary or Assistant Secretary, under the corporate seal, to be true copies.
7. The current power-of-attorney of the person signing for the surety company must be attached to the bond.
8. The date of the bond must not be prior to the date of the Contract.
9. The following information must be placed on the bond by the surety company:
a. The rate of premium in dollars per thousand; and
b. The total dollar amount of premium charged.
10. The signature of a witness shall appear in the appropriate place attending to the signature of each party of the bond.
11. Type or print the name underneath each signature appearing on the bond.
12. An executed copy of the bond must be attached to each copy of the Contract (original counterpart) intended for signing.
DORA STREET UTILITY IMPROVEMENT PROJECT Spec NO. 19-01
70 CITY OF UKIAH
Mendocino County, California
DEFECTIVE MATERIAL AND WORKMANSHIP (MAINTENANCE) BOND
KNOW ALL MEN BY THESE PRESENTS,
That we, _____________________________________________________________________ __________________________________________________________________, as PRINCIPAL and__________________________________________________________________________ ___________________________________________________________________, as SURETY, are held and firmly bound unto the City of Ukiah as Obligee, in the penal sum of ___________________________________________________________________________________ _________________________________________________________($____________________), (5 PERCENT OF THE FINAL CONTRACT AMOUNT)
to which payment well and truly to be made, we do bind ourselves, our and each of our heirs, executors, administrators, successors and assigns jointly and severally, firmly by these presents.
WHEREAS, the said Principal entered into a Contract with the City Of Ukiah dated_________________________
for _________________________________________________________________________________ ____________________________________________________________________________________ WHEREAS, said Contract has been completed, and was approved on the ______ day of ___________, _________,
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal shall guarantee that the work will be free of any defective materials or workmanship which become apparent during the period of one (1) year following completion of the Contract, then this obligation shall be void, otherwise to remain in full force and effect, provided however, any additional warranty or guarantee whether expressed or implied is extended by the Principal or Manufacturer only, and the surety assumes no liability for such a guarantee.
Signed, sealed, and dated this __________ day of ____________, 20_____. __________________________________________________(Seal) BY:_______________________________________________(Seal) __________________________________________________(Seal) Principal
__________________________________________________(Seal) BY:_______________________________________________(Seal) __________________________________________________(Seal) Surety
Please return to:
CITY OF UKIAH
300 Seminary Avenue
Ukiah, California 95482-5400
(707) 463-6200
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN:
1. That the project described as: Dora Overlay Project, Specification No. 2019-01
2. That the nature of the title to the transportation, pedestrian and utility improvements on Dora Street between Mill Street and Grove Avenue
3. That on the 9th day of February 2023, the Contract work for this project was actually completed.
4. That the name and address of the Contractor is Ghilotti Construction Co., 246 Ghilotti Avenue, Santa Rosa, CA 95407.
5. That the real property herein referred to is situated in the County of Mendocino, State of California, and is described as follows: City-owned property identified as Dora Street.
I hereby certify under penalty of perjury that the forgoing is true and correct:
City Council Approval CITY OF UKIAH, a Municipal Corporation _________________ By: __________
Date Kristine Lawler, City Clerk Date
State of California
County of Mendocino
Exempt from recording fees pursuant to Government Code Section 27383 ATTACHMENT 2
Agenda Item No: 8.f.
MEETING DATE/TIME: 3/15/2023
ITEM NO: 2023-2458
AGENDA SUMMARY REPORT
SUBJECT: Approve the Plans and Specifications for Thickening and Dewatering Improvements, Specification 23-02, and Authorize Staff to Issue Bids.
DEPARTMENT: Public Works PREPARED BY: Seth Strader, Administrative Analyst PRESENTER: Sean White, Director of Water and Sewer
ATTACHMENTS:
1. Screw Press and SAF Staff Report
2. Ukiah Screw Press & SAF Plans
3. Bid Specification
Summary: Staff is requesting City Council Approval of the Plans and Specifications for the Thickening and Dewatering Improvement, Specification 23-02, and authorize Staff to issue bids.
Background: In early 2022 the City purchased a Dewatering System from FKC Co and Suspended Air Floatation (SAF) Thickening System from Heron Innovators. See Attachment 1. Both of these machines are to be installed at the Waste Water Treatment Plant along with the construction of other site improvements.
Discussion: The engineering firm West Yost was contracted to design and engineer the new machine's installation and tie-in to existing equipment at the plant as well as construction management to facilitate an efficient and smooth transition to the SAF and screw press. City Staff and West Yost have completed the plans (Attachment 2) and specification (Attachment 3) for the project.
The Thickening and Dewatering Improvements replace the existing dewatering system at the Wastewater Treatment Plant that is inefficient and in a state of disrepair. The screw press paired with the SAF provides the Plant with an effective process of disposing of solids. Currently, nearly $80,000 is spent annually for Ukiah Waste Solutions to pick up and dispose of the byproduct of this process. With the new system, a nonhazardous byproduct will be produced, allowing the City further savings on hazardous waste disposal.
Recommended Action: Approval of the Plans and Specifications for the Thickening and Dewatering Improvement, Specification 23-02 and authorize Staff to issue bids.
BUDGET AMENDMENT REQUIRED: NO
CURRENT BUDGET AMOUNT: 84027225.80100.18130: $825,000
PROPOSED BUDGET AMOUNT:
FINANCING SOURCE:
PREVIOUS CONTRACT/PURCHASE ORDER NO.:
COORDINATED WITH: Jason Benson, Senior Engineer, Sean White, Director of Water and Sewer, Tim Eriksen, Director of Public Works
DIVERSITY-EQUITY INITIATIVES (DEI):
CLIMATE INITIATIVES (CI):
Agenda Item No: 7.j.
MEETING DATE/TIME: 4/20/2022
ITEM NO: 2022-1573
AGENDA SUMMARY REPORT
SUBJECT: Approve the Purchase of a BHX 700 Dewatering System in the Amount of $397,455 from FKC CO, Ltd, as Approved in the Fiscal Year 2021-2022 Capital Budget.
DEPARTMENT: Public Works PREPARED BY: Seth Strader, Administrative Analyst PRESENTER: Sean White, Water Resources Director.
ATTACHMENTS:
1. BHX 700 Proposal
Summary: Council will consider approving the purchase of a BHX 700 Dewatering System from FKC CO, Ltd in the amount of $397,455, as approved in the Fiscal Year 2021-2022 Capital Budget.
Background: The belt filter press (BFT) at the Wastewater Treatment Plant (WWTP) is in need of replacement. Replacement of the BFT was approved and adopted in the FY 21/22 budget.
Discussion: The BFP is a critical piece of infrastructure at the WWTP. The BFP de-waters sludge leaving the digester so it is in a form that can be hauled away. The WWTP field tested a number of potential replacements at the plant between 2018 and 2020. Other products that were tested included presses from Coombs-Hopkins, Muniquip, PW Tech, and Andritz. Staff is recommending the FKC for three reasons: 1) The FKC unit is very compact and performed exceptionally. 2) The design is very simple, robust and easy to service. 3) The FKC is the only unit with a steam port that could facilitate the ability to produce Class A biosolids. Upgrading from Class B biosolids could allow our biosolids to be used locally as a soil amendment which could eventually eliminate the need for landfill disposal and trucking. Last year the WWTP spent $86,713.81 on hauling and landfill disposal. FKC Co. Ltd.'s proposal is Attachment 1.
Recommended Action: Approve the purchase of a BHX 700 Dewatering System from FKC CO, Ltd in the amount of $397,455, as approved in the Fiscal Year 2021-2022 Capital Budget.
BUDGET AMENDMENT REQUIRED: NO
CURRENT BUDGET AMOUNT: 84027225.80100.18130: $1,000,000 PROPOSED BUDGET AMOUNT: N/A
FINANCING SOURCE: Sewer Fund
PREVIOUS CONTRACT/PURCHASE ORDER NO.: N/A
COORDINATED WITH: Tim Eriksen, Director of Public Works, Sean White, Director of Water & Sewer and Jason Benson, Senior Engineer
ATTACHMENT 1
Agenda Item No: 7.e.
MEETING DATE/TIME: 5/4/2022
ITEM NO: 2022-1630
AGENDA SUMMARY REPORT
SUBJECT: Approval of Purchase of a Suspended Air Floatation System in the Amount of $298,920 plus tax and shipping from Heron Innovators, as Approved in the Fiscal Year 2021-2022 Capital Budget, and Approval of Corresponding Budget Amendment Using Wastewater Reserve Funds.
DEPARTMENT: Public Works PREPARED BY: Seth Strader, Administrative Analyst PRESENTER: Sean White, Director of Water & Sewer
ATTACHMENTS:
1. Heron Proposal
Summary: Council will consider approving the purchase of a Suspended Air Flotation System from Heron Innovators in the amount of $298,920, as approved in the Fiscal Year 2021-2022 Capital Budget, and possible approval of a corresponding budget amendment using Wastewater Reserve Funds.
Background: In preparation for the 21/22 Fiscal Year budget, Staff prepared and presented, which was subsequently approved and adopted in the budget, a proposal for the replacement of a dissolved air flotation (DAF) system, housed at the Wastewater Treatment Plant.
Discussion: The DAF is a critical piece of infrastructure at the WWTP. The DAF thickens biosolids before entering the digesters thru the injection of pressurized air. In the summer of 2021 the pressure vessel for the DAF began to fail from internal corrosion.
Water Resources Staff compared the cost of a direct replacement to other alternatives. After comparing costs, and several site visits at similar facilities utilizing alternative technologies, Staff is recommending replacing the DAF with a Suspended Air Flotation (SAF) system.
The SAF uses a proprietary frothing agent developed at UC Davis instead of air. This will allow the plant to no longer need three air compressors as well as three 40 horsepower motors. This will greatly reduce maintenance and energy costs. In addition the SAF is significantly more effective at thickening.
Provided as Attachment 1 is the proposal from Heron Innovators. It is Staff’s recommendation for Council to approve the purchase of a SAF System from Heron Innovators in the amount of $298,920.00 and approve a budget amendment in the amount of $48,920.00 using Wastewater Reserve Funds. The sole source purchase is recommended based upon the unique and specialized operational needs specific of the City's facility and the Department's evaluation of the SAF System from Heron Innovators as compared to other alternatives.
Recommended Action: Approve the purchase of a SAF System from Heron Innovators in the amount of $298,920 plus tax and shipping, as approved in the Fiscal Year 2021-2022 Capital Budget, and approve corresponding budget amendment using Wastewater Reserve Funds.
BUDGET AMENDMENT REQUIRED: YES
CURRENT BUDGET AMOUNT: 84027225.80100.18248: $250,000
PROPOSED BUDGET AMOUNT: 84027225.80100.18248: $330,075
FINANCING SOURCE: Wastewater Reserve Funds
PREVIOUS CONTRACT/PURCHASE ORDER NO.:
COORDINATED WITH: Sean White, Director of Water & Sewer and Jason Benson, Senior Civic Enginer
CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 G001 TITLE SHEET, LOCATION AND VICINITY MAPS 1 CITY OF UKIAH MENDICINO COUNTY, CALIFORNIA THICKENING AND DEWATERING IMPROVEMENTS MARCH 2023 Location VICINITY MAP Location LOCATION MAP ATTACHMENT 2
CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 G002 DRAWING LIST AND DESIGN CRITERIA 2 DESIGN CRITERIA FLOWS & LOADING FLOWS ADWF PWDWF AWWF PWWWF PHWWF AVERAGE DRY WEATHER PEAK WEEK DRY WEATHER AVERAGE WET WEATHER PEAK WEEK WET WEATHER PEAK HOUR WET WEATHER MGD MGD MGD MGD MGD 3.01 3.40 6.89 15.8 24.5 SOLIDS THICKENING MECHANICAL THICKENING EQUIPMENT (NEW) TYPE NO. PERFORMANCE FLOC TUBE SIZE WW FLOW, EA. PS FLOW, EA. WWS FLOW, EA. PSC FLOW, EA. FLOW RANGE, EA. MAXIMUM TSS OPERATING DAYS OPERATING HOURS CONTINUOUS INTERMITTENT CONTINUOUS INTERMITTENT %INCHES GPM GPM GPM GPM GPM MG/L DAYS/WEEK HRS/DAY SUSPENDED AIR FLOATATION 24 TO 7 10<500 150 10 - 30, MAX 250 150 150 - 500 2,000 724 TYPE NO. DETENTION TIME MOTOR SIZE TOTE NON-POTABLE / PLANT EFFLUENT SHP CLEARMIXER 23 TO 6 1 MECHANICAL THICKENING FROTH GENERATOR (NEW) TYPE NO. CHEMICAL STORAGE AIR VOLUME DISCHARGE PRESSURE (MAXIMUM) GENERATOR FLOW CAPACITY, EA. WATER REQUIREMENT WATER PRESSURE MOTOR SIZE %PSIG GPM GPM PSIG HP MICRO-BUBBLE EMULSION 2130 - 40 20137.5 405 MECHANICAL THICKENING POLYMER SYSTEM (NEW) DELUTED POLYMER STORAGE TOTE EMULSION POLYMER BLENDING UNIT NO. DOSE DILUTION WATER CAPACITY METERING PUMP 20.95 120 - 1,200 120 - 1,200 0.15 - 3.0 PRIMARY MIXING POST DILUTION NEAT POLYMER GPH GPH GPH GPH SOLIDS DEWATERING MECHANICAL DEWATERING EQUIPMENT (NEW) TYPE NO. INLET CAPACITY INLET CONSISTENCY HYDRAULIC CAPACITY OUTLET CONSISTENCY SOLIDS CAPTURE NO. OF WATER SPRAY NOZZLES WASH WATER FLOW RATE OPERATING DAYS OPERATING HOURS DRY LB/HR %GAL %%DAYS/WEEK HRS/DAY SCREW PRESS 1250 230,000 - 40,000 @ 25 GPM 2092 - 96 66650 GPD @ 40 PSI 724 FLOCCULATION TANK NO. MIXER MOTOR SIZE TANK CAPACITY HPGAL 11100 PRIMARY MIXING POST DILUTION NEAT POLYMER MECHANICAL DEWATERING POLYMER SYSTEM (NEW) DILUTED POLYMER STORAGE GPH GPH GPH EMULSION POLYMER BLENDING UNIT NO. DILUTION WATER CAPACITY METERING PUMP TOTE 1120 - 1,200 120 - 1,200 0.15 - 3.0
CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 G003 LEGEND, SYMBOLS, AND ABBREVIATIONS3 LEGEND - PIPING S LEGEND:CIVIL CIVIL/MECHANICAL MECHANICAL M ABBREVIATIONS PIPING SYSTEM ABBREVIATIONS SECTION & DETAIL DESIGNATIONS FOR CIVIL, MECHANICAL & ARCHITECTURAL DRAWINGS PIPING DESIGNATIONS
OWNER PRE-PURCHASED SCREW PRESS STORAGE LOCATION CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 C001 SITE PLAN 4 N
OR CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 CD001 CIVIL DETAILS 5 DETAIL EXISTING AC OR CONCRETE PAVING DETAIL DETAIL
DXXX CAP 6" AFE CAP 6" AFE DEMO PRESSURIZATION PUMPS, CONC. PADS, & PIPING DEMO SATURATION TANK, APPURTENANCES AND CONCRETE EQUIPMENT PAD (TYP OF 2) DEMO AIR SUPPLY AND NITROGEN PURGE SYSTEM DEMO TARGET BAFFLE (TYP OF 8) DEMO POLYMER RING (TYP OF 2) 1" POL DEMO 8" WW DEMO DEMO 6" MS 8" WW DEMO DEMO 4" PSC 6" AFE DEMO 6" AFE DEMO 6" AFE DEMO 6'-0" EQUIPMENT GUARD, TYPCAP 6" AFE SEAL WATER SYSTEM 1 FLOW GAUGE, TYP 6" MS DEMO DEMOLISH POLE MOUNTED LIGHT, TYP OF 2 CAP 6" AFE DEMOLISH CONCRETE DRAIN INLETS, TYP OF 3 6" CAP LIMITS OF CONCRETE DEMOLITION LIMITS OF CONCRETE DEMOLITION REPAIR OPENING IN CONCRETE FROM PIPE PENETRATION REMOVAL PER DETAIL 03159/00-S-005, TYP OF 8 LOCATIONS. SEE 70-D-016 CAP 8" AFE CAP 8" AFE CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-001 DEMOLITION AND MODIFICATION 1 DAFT PLAN 6 DEMOLISH CONCRETE PAD IN THIS AREA AND REPLACE WITH NEW CONCRETE PAD. SEE DETAIL 03074/00-S-004. NOTES: 1. FIELD VERIFY INFORMATION SHOWN ON THIS DRAWING. THIS DRAWING IS NOT AN "AS-BUILT" DRAWING. 2. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS.
PATCH CONCRETE HOLE, TYP CAP 112" SA CAP 1" POL INSTALL FLOOR DRAIN DEMO SATURATION TANK, APPURTENANCES, AND CONCRETE EQUIPMENT PAD DEMO AIR SUPPLY AND NITROGEN PURGE PANEL DEMO POLYMER RINGDEMO 6" MS 4" PSC DEMO 8" WW DEMO 1 2 3 4 DEMO NOTES: 1. FIELD VERIFY INFORMATION SHOWN ON THIS DRAWING. THIS DRAWING IS NOT AN "AS-BUILT" DRAWING. 2. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS. CAP 8" AFECAP 6" AFE DEMOLISH WALL PIPE AND WALL PENETRATIONS, TYP OF 8. REPAIR CONCRETE OPENINGS PER DETAIL 03159/00-S-005. SEE 70-D-016 CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-002 DEMOLITION AND MODIFICATION 2 DAFT SECTION 1 7 1 2 3 4
CAP 8" AFE CAP 6" AFEDEMO 6" AFE DEMO (E) POLYMER RING DEMO SATURATION TANK, APPURTENANCES, AND CONCRETE EQUIPMENT PAD DEMO AIR SUPPLY NITROGEN PURGE PANEL DEMO (E) 8" WW DEMO (E) 6" PF DEMO 4" PSC 8" WW 6" MSDEMO DEMO DEMO PRESSURIZATION PUMP DEMO PRESSURIZATION PUMPS SEAL WATER SYSTEMEQUIPMENT GUARD 1 2 3 3 3 DRAIN 4 6" AFE PIPING 6 MAGNETIC LEVEL INDICATOR 5 DEMO DEMO DEMO DEMO DEMOLISH CONCRETE PAD IN THIS AREA AND REPLACE WITH NEW CONCRETE. SEE DETAIL 03074/00-S-004. DEMOLISH CONCRETE PAD IN THIS AREA AND REPLACE WITH NEW CONCRETE. SEE DETAIL 03074/00-S-004. DEMOLISH WALL PIPE AND WALL PENETRATIONS, TYP OF 8. REPAIR CONCRETE OPENINGS PER DETAIL 03159/00-S-005. SEE 70-D-016 CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-003 DEMOLITION AND MODIFICATION 3 DAFT SECTION 2 8 1 2 3 4 5 6 NOTES: 1. FIELD VERIFY INFORMATION ON THIS DRAWING. THIS DRAWING IS NOT AN "AS-BUILT" DRAWING. 2. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS.
- - - - - - - - CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-004 DEMOLITION AND MODIFICATION 4 SATURATION TANK PARTIAL PLAN, SECTIONS AND DETAIL 9 ALL ITEMS ON THIS SHEET ARE TO BE DEMOLISHED. THIS SHEET PROVIDES INFORMATION ON THE SATURATION TANK. NOTES: 1. FIELD VERIFY INFORMATION ON THIS DRAWING. THIS DRAWING IS NOT AN "AS-BUILT" DRAWING. 2. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS.
- - - - CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-005 DEMOLITION AND MODIFICATION 5 - DISSOLVED AIR FLOTATION THICKENERS SECTION AND DETAILS10 ALL ITEMS ON THIS SHEET ARE TO BE DEMOLISHED. THIS SHEET PROVIDES INFORMATION ON THE POLYMER RING. NOTES: 1. FIELD VERIFY INFORMATION ON THIS DRAWING. THIS DRAWING IS NOT AN "AS-BUILT" DRAWING. 2. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS.
CAP 1-12" SA DEMO CONCRETE PAD, SALVAGE AIR COMPRESSOR (TYP OF 3) DEMO CONCRETE PAD, TYP OF 4. SEE DETAIL 03153/00-S-005 AND 70-D-017 REMOVE (E) POLYMER SYSTEM, DEMO CONCRETE PAD - SEE DETAIL 03153/00-S-005 AND 70-D-017 KEEP IN PLACE METAL STAND INCLUDED TO RAISE ELEVATION OF TOTE, TYP POLYMER TOTE BASES SEE NOTES 1 & 2 REMOVE (E) POLYMER SYSTEM AND INSTALL (N) POLYMER BLENDING SYSTEM, SEE NOTE 3 TO SAF UNIT CONNECT TO (E) 1" POL PIPE, SEE NOTE 4 NEW POLYMER TOTE BASES SEE NOTES 1 & 2 1" POL DEMO DEMOLISH DRAIN INLET, TYP OF 4. CAP 2" DRAIN FLUSH WITH FLOOR 1.5" SA DEMO A 70-D-007 B 70-D-007 CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-006 DEMOLITION AND MODIFICATION 6 - DAFT EQUIPMENT BUILDING PLAN AND PARTIAL PLANS11 NOTES: 1. FIELD VERIFY INFORMATION ON THIS DRAWING. THIS DRAWING IS NOT AN "AS-BUILT" DRAWING. 2. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS. NOTES: 1. PROVIDE TWO 45.5" WIDE BY 52" LONG BY 26.5" HIGH TOTE STANDS, PIG IBC TOTE DISPENSING STAND, OR EQUAL. 2. LOCATE TOTE DISPENSING STAND ON CONCRETE PAD. 3. PROVIDE 1" PVC FLEXIBLE HOSES FROM POLYMER TOTE TO NEW POLYMER BLENDING SYSTEM. PROVIDE TWO 1" PVC BALL VALVES. 4. PROVIDE 1" PVC FLEXIBLE HOSES FROM POLYMER BLENDING SYSTEM TO CONNECTION AT EXISTING 1" POL PIPE. PROVIDE TWO 1" PVC BALL VALVES. 5. FIELD VERIFY INFORMATION ON THIS DRAWING. THIS DRAWING IS NOT AN "AS BUILT" DRAWING. 6. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS.
NEW POLYMER TOTE BASE. SEE NOTES 1 AND 2 CAP 1-12" SA DEMO CONCRETE PADS, TYP OF 4, SEE DETAIL 03153/00-S-005 AND 70-D-017 - A 70-D-006 SECTION B 70-D-006 SECTION ROUTE 1" RCW TO NEW POLYMER BLENDING SYSTEMS 2" RCW INSTALL NEW POLYMER BLENDING SYSTEMS ON EXISTING CONCRETE PADS. SEE NOTE 3 CONNECT TO (E) 1" POL PIPE, SEE NOTE 4 ROUTE 1" RCW TO NEW POLYMER MIXING SYSTEM CONNECT TO (E) 1" POL PIPE, SEE NOTE 4 18" TYP
OF 4 PADS
18"
24"
18"
24"
18" CAP 2" DRAIN FLUSH WITH FLOOR, TYP DEMO DEMO NEW POLYMER TOTE BASE. SEE NOTES 1 AND 2 DEMOLISH CONCRETE EQUIPMENT BASE. SEE DETAIL 03153/00-S-005 AND 70-D-017 DEMO CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-007 DEMOLITION AND MODIFICATION 7 DAFT EQUIPMENT BUILDING SECTIONS 12 NOTES: 1. PROVIDE TWO 45.5" WIDE BY 52" LONG BY 26.5" HIGH TOTE STANDS, PIG IBC TOTE DISPENSING STAND, OR EQUAL. 2. LOCATE TOTE DISPENSING STAND ON CONCRETE PAD. 3. PROVIDE 1" PVC FLEXIBLE HOSES FROM POLYMER TOTE TO NEW POLYMER BLENDING SYSTEM. PROVIDE TWO 1" PVC BALL VALVES. 4. PROVIDE 1" PVC FLEXIBLE HOSES FROM POLYMER BLENDING SYSTEM TO CONNECTION AT EXISTING 1" POL PIPE. PROVIDE TWO 1" PVC BALL VALVES. 5. FIELD VERIFY INFORMATION ON THIS DRAWING. THIS DRAWING IS NOT AN "AS BUILT" DRAWING. 6. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS.
CAP 6" AFE CAP 1" POL CAP 6" PF (ABANDONED) CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-008 DEMOLITION AND MODIFICATION 8 - DISSOLVED AIR FLOTATION THICKENER 1 P&ID 13 NOTES: 1. FIELD VERIFY INFORMATION ON THIS DRAWING. THIS DRAWING IS NOT AN "AS-BUILT" DRAWING. 2. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS.
CAP 6" AFE CAP 1" POL CAP 6" PF (ABANDONED) CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-009 DEMOLITION AND MODIFICATION 9 - DISSOLVED AIR FLOTATION THICKENER 2 P&ID 14 NOTES: 1. FIELD VERIFY INFORMATION ON THIS DRAWING. THIS DRAWING IS NOT AN "AS-BUILT" DRAWING. 2. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS.
CAP 1-12" SA CAP 1-12" SA CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-010 DEMOLITION AND MODIFICATION 10 - DAFT EQUIPMENT BUILDING DAFT AIR COMPRESSOR SYSTEM 1 OF 2 P&ID15 NOTES: 1. FIELD VERIFY INFORMATION ON THIS DRAWING. THIS DRAWING IS NOT AN "AS-BUILT" DRAWING. 2. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS. 3. AIR COMPRESSORS SHALL BE SALVAGED TO THE CITY.
CAP 1-12" SA CAP 1-12" SA (ABANDONED)
(ABANDONED) CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-011 DEMOLITION AND MODIFICATION 11 - DAFT EQUIPMENT BUILDING DAFT AIR COMPRESSOR SYSTEM 2 OF 2 P&ID16 NOTES: 1. FIELD VERIFY INFORMATION ON THIS DRAWING. THIS DRAWING IS NOT AN "AS-BUILT" DRAWING. 2. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS. 3. AIR COMPRESSORS SHALL BE SALVAGED TO THE CITY.
CAP 8" AFE CAP 6" AFE CAP 6" AFE
(ABANDONED)
(ABANDONED) CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-012 DEMOLITION AND MODIFICATION 12 - DAFT EQUIPMENT BUILDING DAFT AIR COMPRESSOR SYSTEM 2 OF 2 P&ID17 NOTES: 1. FIELD VERIFY INFORMATION ON THIS DRAWING. THIS DRAWING IS NOT AN "AS-BUILT" DRAWING. 2. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS.
CAP 6" AFE CAP 1-12" SA CAP 6" PF CAP 6" AFE CAP 1-12" SA CAP 6" PF (ABANDONED) (ABANDONED) CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-013 DEMOLITION AND MODIFICATION 13 - DAFT EQUIPMENT BUILDING DAFT SATURATION SYSTEM P&ID 18 NOTES: 1. FIELD VERIFY INFORMATION ON THIS DRAWING. THIS DRAWING IS NOT AN "AS-BUILT" DRAWING. 2. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS.
CAP 1" POL CAP 2" RCW CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-014 DEMOLITION AND MODIFICATION 14 - DAFT EQUIPMENT BUILDING POLYMER BLENDING SYSTEM 1 P&ID 19 NOTES: 1. FIELD VERIFY INFORMATION ON THIS DRAWING. THIS DRAWING IS NOT AN "AS-BUILT" DRAWING. 2. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS.
CAP 1" POL CAP 2" RCW CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-015 DEMOLITION AND MODIFICATION 15 - DAFT EQUIPMENT BUILDING POLYMER BLENDING SYSTEM 2 P&ID 20 NOTES: 1. FIELD VERIFY INFORMATION ON THIS DRAWING. THIS DRAWING IS NOT AN "AS-BUILT" DRAWING. 2. SEE DRAWING 70-D-016 PHOTOS FOR ADDITIONAL DEMOLITION REQUIREMENTS.
DAFT DEMO DETAIL 1 DAFT DEMO DETAIL 2 DAFT DEMO DETAIL 3 DAFT DEMO DETAIL 4 CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-016 DAFT DEMO PHOTO DETAILS 21
CHEM ROOM DEMO DETAIL A CHEM ROOM DEMO DETAIL B CHEM ROOM DEMO DETAIL C CHEM ROOM DEMO DETAIL D CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 70-D-017 DAFT POLYMER ROOM DEMO PHOTO DETAILS 22
DEMOLISH BELT FILTER PRESS AND PLATFORM DEMOLISH POLYMER SYSTEM AND ASSOCIATED PIPING TO BELT FILTER PRESS. REUSE (E) POLYMER TOTE STAND 1'-6.25" 12"
3'-0" 1'-9"
1'-9" POLYMER LINE 1 2 CONC. PAD LxWxHxT IS 14'-8"x10'-10"x6"x6" 3 HEATER 1 3 4 ROUTE TEMPORARY DEWATERING PIPING UNDER ROLL-UP DOOR LOCATION OF TEMPORARY DEWATERING SYSTEM, SEE DRAWING C001. SEE NOTES 1 TO 6 DEMOLISH 6" FM DEMOLISH 6" DIP 3" RECLAIMED WATER PIPE DEMOLISH CONCRETE. SEE 75-S-001 FOR LIMITS OF DEMOLITION NOTES: 1. PROVIDE TEMPORARY DEWATERING SYSTEM DURING THE DEMOLITION OF BELT FILTER PRESS AND INSTALLATION OF THE NEW SCREW PRESS. 2. DEWATREING SYSTEM SHALL BE LOCATED NORTH OF THE SLUDGE DEWATERING SYSTEM, SEE DRAWING C001. 3. DEWATERING SYSTEM SHALL BE DESIGNED FOR 25 GPM CONTINUOUS FLOW AT 2% DIGESTED SLUDGE. A MAXIMUM OF THREE DAYS STOARGE IS AVAILABLE. 4. DISPOSE OF DEWATERED SLUDGE AT A PERMITTED OFF-SITE LOCATION. PROVIDE ALL SAMPLES AND LABORATORY ANALYSIS TO DISPOSE OF BIOSOLIDS. OBTAIN ALL PERMITS NECESSARY FOR DISPOSAL OF BIOSOLIDS. 5. PROVIDE A PROJECT PLAN THAT INCLUDES A BIOSOLIDS SPILL RESPONSE AND PREVENTION PLAN, TRAFFIC PLAN AND SAFETY PLAN. 6. PROVIDE SPILL CONTAINMENT. 4'-0" 14'-8" CONNECTION FOR TEMPORARY DEWATERING SYSTEM DEMOLISH POLYMER LINE DEMOLISH 6" SLDEMOLISH PIPING DEMOLISH PANEL REUSE EXISTING POLYMER TOTE STAND CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 75-D-001 SLUDGE DEWATERING BUILDING PLAN AND SECTIONS 23
BELT PRESS DEMO DETAIL A BELT PRESS DEMO DETAIL B BELT PRESS DEMO DETAIL C BELT PRESS DEMO DETAIL D BELT PRESS DEMO DETAIL E CITY OF UKIAH THICKENING AND DEWATERING IMPROVEMENTS 89 No. C60715 75-D-003 BELT PRESS DEMO PHOTO DETAILS 24
USE OR OCCUPANCY UNIFORM
LOAD (psf) CONCENTRATEDLOAD (lbs) EQUIPMENT FLOOR AREAS 100 300 EQUIPMENT ROOM FLOORS 250 - CATWALKS FOR MAINTENANCE ACCESS 100 - FOUNDATION TYPE ALLOWABLE BEARING CAPACITY (1) FOR DL + LL MAT FOUNDATION 1,000 psf
AT REST (1) (pcf) ACTIVE (1) (pcf) PASSIVE (1) (pcf) SOIL CONDITION w/o GW (2) w/ GW (2) w/o GW (2) w/ GW (2) w/o GW (2) w/ GW (2) CLASS 2 AGG. BASE 55 93 35 83 300 210 USCS "CL" MATERIAL 100 145 - - 100 70 SEISMIC IMPORTANCE FACTOR (IE) 1.0 RISK CATEGORY: III MAPPED SPECTRAL RESPONSE ACCELERATIONS: SS
= 1.865g, S1 = 0.712g SITE CLASS D
SPECTRAL RESPONSE COEFFICIENTS: SDS = 1.492g, SD1 = 0.807g SEISMIC DESIGN CATEGORY: E DESIGN BASE SHEAR: V = 0.47 W SEISMIC RESPONSE COEFFICIENT: CS = 0.47 RESPONSE MODIFICATION FACTOR: R = 2.5 ANALYSIS PROCEDURE USED: ASCE 7, CHAPTER 13 GROUND SNOW LOAD (Pg): 16 PSF
FLAT-ROOF SNOW LOAD (Pf): 15 PSF SNOW EXPOSURE FACTOR (Ce): 0.9 SNOW LOAD IMPORTANCE FACTOR (Is): 1.1 THERMAL FACTOR (Ct): 1.2
STRUCTURAL NOTES
GENERAL
1. ALL STRUCTURAL DRAWINGS SHALL BE USED IN CONJUNCTION WITH THE CIVIL, ARCHITECTURAL, MECHANICAL, ELECTRICAL, AND SHOP DRAWINGS AND THE PROJECT SPECIFICATIONS (IF ANY). 2. CONSTRUCTION SHALL MEET THE REQUIREMENTS OF THE 2022 CALIFORNIA BUILDING CODE (CBC). THE CBC SHALL GOVERN EXCEPT WHERE OTHER APPLICABLE CODES OR THESE DOCUMENTS ARE MORE RESTRICTIVE. 3. NOTHING SHOWN OR OMITTED FROM THESE DOCUMENTS SHALL RELIEVE
THE CONTRACTOR FROM FULL COMPLIANCE WITH ALL APPLICABLE CODES AND ORDINANCES. 4. THE CONTRACTOR ALONE IS RESPONSIBLE FOR JOB SITE SAFETY. SITE REVIEW OF THE CONSTRUCTION BY THE ENGINEER IS TO DETERMINE CONFORMANCE WITH THE PLANS AND SPECIFICATIONS. IT DOES NOT ENCOMPASS SAFETY PROCEDURES OR OPERATIONS. 5. WITHOUT EXCLUSION OF ANY REFERENCE IN THE CONSTRUCTION DOCUMENTS TO ANY RULE OR REGULATION, THE ENGINEER IS NOT ASSUMING ANY PROVISIONS OF SUPERVISION OF CONSTRUCTION METHODS OR PROCESSES. 6. STRUCTURES HAVE BEEN DESIGNED FOR OPERATIONAL LOADS ON THE COMPLETED STRUCTURES. DURING CONSTRUCTION, BRACING OR SHORING SHALL SUPPORT STRUCTURES WHEREVER EXCESSIVE CONSTRUCTION LOADS MAY OCCUR. 7. SEE ALL OTHER PROJECT DOCUMENTS FOR REGLETS, PIPE SLEEVES, CONDUITS AND OTHER ITEMS TO BE EMBEDDED OR PASSED THROUGH THE CONCRETE. 8. PENETRATIONS THROUGH WALLS OR SLABS LESS THAN 12 INCHES IN DIAMETER MAY NOT BE SHOWN ON THE STRUCTURAL DRAWINGS. REFER TO ASSOCIATED DRAWINGS FOR LOCATIONS. 9. THE MINIMUM CLEAR DISTANCE BETWEEN PIPE AND CONDUIT PENETRATIONS SHALL BE 3 TIMES THE DIAMETER OF THE PENETRATION OR 8 INCHES, WHICHEVER IS SMALLER. 10. WRITTEN DIMENSIONS SHALL BE USED FOR CONSTRUCTION. DO NOT SCALE DRAWINGS. 11. STRUCTURAL DIMENSIONS CONTROLLED BY OR RELATED TO MECHANICAL AND/OR ELECTRICAL EQUIPMENT SHALL BE VERIFIED BY THE CONTRACTOR PRIOR TO CONSTRUCTION. 12. MECHANICAL AND ELECTRICAL EQUIPMENT SUPPORTS, ANCHORAGES,
OPENINGS, RECESSES AND EMBEDMENTS NOT SHOWN ON THE DRAWINGS SHALL BE PROVIDED BY THE CONTRACTOR PRIOR TO PLACING CONCRETE. 13. DIMENSIONS INDICATED WITH AN * SHALL BE COORDINATED WITH MECHANICAL AND/OR ELECTRICAL DRAWINGS AND EQUIPMENT SUPPLIED. 14. ALL DIMENSIONS SHALL BE FIELD VERIFIED BY THE CONTRACTOR. SHOULD
CONFLICTS OR INTERFERENCE OCCUR, THEY SHALL BE RESOLVED WITH THE ENGINEER AT NO ADDITIONAL COST TO THE OWNER. EXISTING FIELD
CONDITIONS AT VARIANCE WITH THE PLANS SHALL BE BROUGHT TO THE ATTENTION OF THE ENGINEER BEFORE ANY WORK IS PERFORMED. 15. USE PERTINENT STANDARD DETAILS SHOWN, EVEN THOUGH THEY MAY NOT BE CALLED OUT AT LOCATIONS WHERE THEY APPLY. 16. CONDITIONS NOT SPECIFICALLY SHOWN OR INDICATED SHALL BE CONSTRUCTED SIMILAR TO DETAILS SHOWN FOR THE RESPECTIVE MATERIALS OR CONDITIONS.
DEFERRED SUBMITTALS
1. THE FOLLOWING PORTIONS OF THE PROJECT ARE DEFERRED SUBMITTAL ITEMS. DEFERRED SUBMITTALS LISTED BELOW ARE THE RESPONSIBILITY OF THE CONTRACTOR. DEFERRED SUBMITTAL ITEMS HAVE NOT BEEN DESIGNED BY THE ENGINEER OF RECORD. REFER TO CONTRACT DOCUMENTS FOR ADDITIONAL INFORMATION. a) FRP GRATING PLATFORM SYSTEMS b) MECHANICAL EQUIPMENT STANCHIONS/RAILS
c) PIPE FRAME SUPPORTS
2. UNLESS OTHERWISE NOTED, DEFERRED SUBMITTAL ITEMS SHALL BE STAMPED AND SIGNED BY A PROFESSIONAL CIVIL OR STRUCTURAL ENGINEER REGISTERED IN THE STATE OF CALIFORNIA. 3. DEFERRED SUBMITTAL ITEMS SHALL BE SUBMITTED TO THE OWNER FOR APPROVAL DURING THE CONSTRUCTION PHASE OF THE PROJECT. 4. DEFERRED SUBMITTAL ITEMS SHALL NOT BE FABRICATED UNTIL THE
ENGINEER OF RECORD HAS REVIEWED THE SUBMITTAL DOCUMENTS AND
INDICATED THAT THEY HAVE BEEN REVIEWED AND THAT THEY HAVE BEEN FOUND TO BE IN GENERAL CONFORMANCE WITH THE CONTRACT DOCUMENTS. 5. DEFERRED SUBMITTAL ITEMS SHALL NOT BE FABRICATED UNTIL THEIR
DESIGN AND SUBMITTAL DOCUMENTS HAVE BEEN FAVORABLY REVIEWED BY THE OWNER. DESIGN LOADS
1. LIVE LOADS:
2. WIND:
3. SEISMIC:
4. SNOW:
SOIL PARAMETERS
1. ALLOWABLE SOIL BEARING CAPACITY:
(1) ALLOWABLE BEARING VALUES MAY BE INCREASED BY 1/3 FOR LOAD CASES INCLUDING WIND AND/OR SEISMIC. (2) PRESUMPTIVE LOAD BEARING VALUES, CBC TABLE 1806.2; USCS "CL". 2. LATERAL EARTH PRESSURES:
(1) EQUIVALENT FLUID DENSITY
(2) GROUNDWATER (GW) TABLE AT GRADE. 3. COEFFICIENT OF FRICTION: A COEFFICIENT OF SLIDING FRICTION OF 0.25 MAY BE ADDED TO PASSIVE RESISTANCE.
BASIC WIND SPEED Vult (3-SECOND GUST): 99 MPH
RISK CATEGORY: III WIND EXPOSURE CATEGORY: C
CITY OF UKIAH
THICKENING AND DEWATERING
IMPROVEMENTS
89 3/7/23
00-S-001
STRUCTURAL GENERAL NOTES I 25
ITEM CONCRETE INSPECTIONS AND VERIFICATION
FREQUENCY
CONTINUOUS PERIODIC
1. INSPECTION OF REINFORCING STEEL, INCLUDING PRESTRESSING TENDONS, AND PLACEMENT. X
2. INSPECTION OF REINFORCING STEEL WELDING IN ACCORDANCE WITH TABLE 1705.3, ITEM 2. 3. INSPECTION OF ANCHORS CAST IN CONCRETE WHERE ALLOWABLE LOADS HAVE BEEN INCREASED OR WHERE STRENGTH DESIGN IS USED.
X
5. VERIFYING USE OF REQUIRED DESIGN MIX. X
6. AT THE TIME FRESH CONCRETE IS SAMPLED TO FABRICATE SPECIMENSFOR STRENGTH TESTS, PERFORM SLUMP AND AIR CONTENT TESTS, AND DETERMINE THE TEMPERATURE OF THE CONCRETE. X
7. INSPECTION OF CONCRETE AND SHOTCRETE PLACEMENT FOR PROPER APPLICATION TECHNIQUES. 8. INSPECTION FOR MAINTENANCE OF SPECIFIED CURING TEMPERATURE AND TECHNIQUES. 9. INSPECT FORMWORK FOR SHAPE, LOCATION AND DIMENSIONS OF THE CONCRETE MEMBER BEING FORMED. SPECIAL PROVISIONS FOR SEISMIC RESISTANCE
4. INSPECTION OF ANCHORS POST-INSTALLED IN HARDENED CONCRETE MEMBERS.
10. TEST ASTM A 615 REINFORCING STEEL THAT IS TO BE WELDED, CHEMICAL TESTS SHALL BE PERFORMED TO DETERMINE WELDABILITY IN ACCORDANCE WITH SECTION 26.6.4.1 OF ACI 318. X
SPECIAL INSPECTION
1. SPECIAL INSPECTION SHALL BE CONDUCTED IN ACCORDANCE WITH THE REQUIREMENTS SET FORTH IN CHAPTER 17 OF THE CBC. UNLESS OTHERWISE
NOTED IN THE PROJECT SPECIFICATIONS, SPECIAL INSPECTION SHALL BE PROVIDED BY AND PAID FOR BY THE DISTRICT. THE FOLLOWING ITEMS, AS A MINIMUM, SHALL RECEIVE SPECIAL INSPECTION:
X
X
X
X
X
ITEM FOUNDATION INSPECTIONS AND VERIFICATION
FREQUENCY
CONTINUOUS PERIODIC SOILS
1. VERIFY SUBGRADE MATERIALS BELOW THE FOOTING FOR DESIGN BEARING CAPACITY. X
2. VERIFY DEPTH OF EXCAVATION AND TYPE OF SUBGRADE MATERIALS REACHED. 3. PERFORM CLASSIFICATION AND COMPACTION TESTING OF CONTROLLED BACKFILL MATERIALS. X
4. VERIFY MATERIALS USED, LAYERED THICKNESSES AND COMPACTION OF BACK FILLS. X
5. VERIFY THE SUBGRADE AND SITE PREPARATIONS FOR CONTROLLED FILL.
X
X
NOTATION:
“X” DENOTES EITHER CONTINUOUS OR PERIODIC INSPECTIONS. “---“ DENOTES AN ACTIVITY THAT IS EITHER A ONE TIME ACTIVITY OR ONE WHOSE FREQUENCY IS DEFINED IN SOME OTHER MANNER DEFINITIONS: CONTINUOUS - SPECIAL INSPECTION BY THE SPECIAL INSPECTOR WHO IS PRESENT WHEN AND WHERE THE WORK TO BE INSPECTED IS BEING PERFORMED (CBC, SECTION 202) PERIODIC - SPECIAL INSPECTION BY THE SPECIAL INSPECTOR WHO IS INTERMITTENTLY PRESENT WHERE THE WORK TO BE INSPECTED IS BEING PERFORMED (CBC, SECTION 202) SPECIAL INSPECTOR - A QUALIFIED PERSON EMPLOYED OR RETAINED BY THE OWNER AND APPROVED BY
THE AUTHORITY HAVING JURISDICTION AS HAVING THE COMPETENCE NECESSARY TO INSPECT A PARTICULAR TYPE OF CONSTRUCTION REQUIRING SPECIAL INSPECTION.
ITEM INSPECTIONS AND VERIFICATION FOR SEISMIC
RESISTANCE IN OTHER BUILDING SYSTEMS
FREQUENCY
CONTINUOUS PERIODIC MECHANICAL & ELECTRICAL COMPONENTS
1. PIPING SYSTEMS INTENDED TO CARRY FLAMMABLE, COMBUSTIBLE OR
HIGHLY TOXIC CONTENTS AND THEIR ASSOCIATED MECHANICAL UNITS IN STRUCTURES ASSIGNED TO SEISMIC DESIGN CATEGORY C, D, E OR F. X
CITY OF UKIAH
THICKENING AND DEWATERING
IMPROVEMENTS
89 3/7/23
SITE WORK
1. A GEOTECHNICAL REPORT WAS NOT AVAILABLE FOR THIS PROJECT. SOIL DESIGN PARAMETERS ARE BASED ON VALUES PRESENTED IN CHAPTER 18 OF THE CBC FOR A CLASS 3 (3, 4, OR 5) MATERIAL. 2. EXCAVATION FOR PADS AS SHOWN ON THE DRAWINGS: THE BOTTOMS OF ALL EXCAVATIONS SHALL BE LEVEL, TAMPED FIRM, CLEAN AND FREE FROM ALL DEBRIS OR FOREIGN MATTER. 3. OVER-EXCAVATION SHALL EXTEND LATERALLY BEYOND THE OUTSIDE EDGE OF FOOTINGS BY A MINIMUM OF 1/2 THE DEPTH OF OVER-EXCAVATION BELOW THE FOOTING OR 12-INCHES. 4. WHERE PRACTICABLE, SIDES OF FOOTINGS SHALL BE CUT NEAT AND CONCRETE POURED DIRECTLY AGAINST THE EXCAVATION. IF FORMING IS REQUIRED, THE
TRENCHES SHALL BE EXCAVATED WIDE ENOUGH TO PERMIT THE ERECTION AND REMOVAL OF FORMS. 5. THE BOTTOM OF ALL EXCAVATIONS SHALL BE SCARIFIED TO A DEPTH OF 8 INCHES, MOISTURE CONDITIONED TO WITHIN 5 PERCENT (±1 PERCENT) OVER THE OPTIMUM MOISTURE CONTENT, AND COMPACTED TO A LEAST 89 PERCENT (±1 PERCENT) RELATIVE COMPACTION. 6. CLASS 2 AGGREGATE BASEROCK SHALL CONSIST OF MATERIAL FREE FROM DEBRIS AND ORGANIC OR OTHER DELETERIOUS MATERIALS. BACKFILL MATERIAL SHALL BE PLACED IN 8-INCH LAYERS, LEVELED, RAMMED AND TAMPED IN PLACE. COMPACTION OF ALL LAYERS SHALL BE A MINIMUM OF 95 PERCENT MAXIMUM DRY DENSITY IN ACCORDANCE WITH ASTM D1557. 00-S-002
STRUCTURAL GENERAL NOTES II 26
LOCATION MIN 28 DAY
STRENGTH
(psi) STRUCTURAL CONCRETE 4,000 CONCRETE FILL 2,500
CONCRETE
1. REINFORCED CONCRETE SHALL CONFORM TO ACI 318. 2. PORTLAND CEMENT SHALL CONFORM TO ASTM C150 TYPE II. ONE BRAND OF CEMENT SHALL BE USED THROUGHOUT THE WORK. 3. USE OF UP TO 25% POZZOLAN (FLY, ASH, CLASS F) CONTENT OF TOTAL CEMENTITIOUS MATERIAL IS PERMITTED. 4. USE OF GRANULATED GROUND BLAST FURACE SLAG (GGBFS) IN THE CONCRETE IS NOT PERMISSIBLE. 5. ALL AGGREGATES SHALL CONFORM TO ASTM C33. THE MAXIMUM SIZE AGGREGATE SHALL BE 1 INCH. USE OF RECYCLED CONCRETE, AGGREGATE OR OTHER RECYCLABLE MATERIALS IS NOT PERMISSIBLE. 6. CONCRETE COMPRESSIVE STRENGTH SHALL MEET THE MINIMUM REQUIREMENTS LISTED BELOW.
7. ADDITIONAL BENEFITS OF INCREASED COHESION, IMPROVED
COMPACTION, REDUCED SCALING AND ENHANCED LONG TERM QUALITY
AND DURABILITY, ALL CONCRETE SHALL HAVE AIR CONTENT
(ENTRAPPED + ENTRAINED) OF 5.0 - 7.0 PERCENT. 8. CONSTRUCTION JOINTS SHALL NOT BE PLACED AT LOCATIONS OTHER
THAN THOSE SHOWN ON THE DRAWINGS WITHOUT THE PRIOR
APPROVAL OF THE ENGINEER OF RECORD. 9. ALL EXPOSED CORNERS OF CONCRETE SHALL HAVE 3/4” MINIMUM CHAMFER, UNLESS NOTED OTHERWISE.
CONCRETE FINISHING, CURING AND PATCHING
1. AS SOON AS CONCRETE IN SLABS HAS SET SUFFICIENTLY TO BE WORKABLE, IT SHALL BE HAND FLOATED WITH A WOOD FLOAT. FINAL TROWELING OF THE INTERIOR SLABS AND WALL PANELS SHALL BE DONE WITH A STEEL TROWEL EXCEPT WHERE DRAWINGS SPECIFICALLY CALL FOR ANOTHER TYPE OF FINISH. ALL EXTERIOR SLABS, INCLUDING SIDEWALKS, SHALL BE GIVEN A LIGHT BROOM NON-SLIP FINISH UNLESS OTHERWISE NOTED ON THE DRAWINGS. 2. FINISHED SURFACES OF ALL SLABS AND PANELS SHALL BE TRUE AND FLAT IN ACCORDANCE WITH ELEVATIONS AND SLOPES SHOWN ON THE DRAWINGS. THE MAXIMUM VARIATION ALLOWED FROM THE SPECIFIED SLOPES AND SURFACES SHALL BE 1/8 INCH WITH NOT MORE THAN 1/8-INCH VARIATION IN ANY 10-FOOT LENGTH. 3. CONCRETE SLABS AND PANELS SHALL BE CURED BY MEANS OF AN APPROVED CURING COMPOUND APPLIED IN ACCORDANCE WITH THE MANUFACTURER'S INSTRUCTIONS. 4. EDGE FORMS 8 INCHES OR LESS IN HEIGHT AT SLABS AND PANELS SHALL REMAIN IN PLACE 24 HOURS AFTER PLACEMENT. AT CAST-IN-PLACE WALLS, BEAMS AND COLUMNS, FORMS SHALL NOT BE REMOVED UNTIL CONCRETE HAS SET ADEQUATELY TO PREVENT DAMAGE DURING AND AFTER REMOVAL. 5. IMMEDIATELY AFTER FORM REMOVAL, FORM TIES SHALL BE REMOVED
FROM EXPOSED SURFACES AND HOLES AND OTHER VOIDS SHALL BE
POINTED FLUSH WITH MORTAR COMPOSED OF ONE PART PORTLAND CEMENT AND TWO PARTS SAND. FINS, BURRS, ETC. SHALL BE REMOVED WHILE THE CONCRETE IS STILL GREEN. VOIDS, POCKETS, AND
HONEYCOMBS WHICH WOULD EITHER WEAKEN CONCRETE OR DISFIGURE EXPOSED SURFACES SHALL BE SIMILARLY PATCHED. IF, IN THE
ENGINEER'S OPINION, HONEYCOMBING IS SUCH THAT THE STRENGTH OF THE STRUCTURE IS IMPAIRED, WHOLE SECTIONS OF THE WORK MAY BE REQUIRED BY THE ENGINEER TO BE REMOVED AND REPLACED AS DIRECTED, AT THE CONTRACTOR'S EXPENSE. 6. GROUT TOPPING SHALL BE TWO COMPONENT POLYMER-MODIFIED, PORTLAND CEMENT, FAST SETTING TROWEL-GRADE MORTAR WITH MIGRATING CORROSION INHIBITOR.
CONCRETE REINFORCING
1. REINFORCING STEEL SHALL CONFORM TO THE LATEST EDITION OF ASTM SPECIFICATION A706 OR A615, GRADE 60. 2. REINFORCING STEEL FABRICATION SHALL BE IN ACCORDANCE WITH THE LATEST EDITION OF CRSI MANUAL OF STANDARD PRACTICE. 3. REINFORCING SHALL HAVE THE FOLLOWING CLEAR CONCRETE COVER, UNLESS OTHERWISE NOTED ON THE DRAWINGS.
4. SPLICED BARS SHALL HAVE A MINIMUM CLASS B CONTACT LAP AS SPECIFIED IN THE LATEST EDITION OF ACI 315 DETAILING MANUAL AND ACI 318 UNLESS OTHERWISE NOTED ON THE DRAWINGS. WHERE SHOWN ON THE DRAWINGS, ld = DEVELOPMENT LENGTH AS DEFINED IN THE STANDARD DETAILS OF THESE DRAWINGS. HOOKS OF REINFORCING STEEL SHALL COMPLY WITH ACI 318. 5. WRITTEN SPACING AND LOCATION OF REINFORCING SHALL TAKE PRECEDENCE OVER DEPICTED SPACING AND LOCATION. 6. UNLESS OTHERWISE NOTED ON THE DRAWINGS, REINFORCING BARS SHOWN
TERMINATING WITH A HOOK SHALL BE FABRICATED WITH A STANDARD HOOK AS DEFINED WITHIN ACI 318. WHERE SECTION THICKNESS DOES NOT ALLOW FOR FULL HOOK EXTENSION, TILT HOOK UNTIL HOOK FITS. ALTERNATIVELY CONTRACTOR MAY USE 180° HOOK OR TWO SMALLER HOOKED BARS OF EQUIVALENT AREA OF STEEL. 7. IN CASES WHERE REINFORCING BARS CANNOT BE EXTENDED AS FAR AS REQUIRED DUE TO THE LIMITED EXTENT OF THE ADJACENT CONCRETE
STRUCTURE, THE BARS SHALL EXTEND AS FAR AS POSSIBLE AND BE TERMINATED WITH A STANDARD HOOK. 8. AT FOOTING CORNERS AND INTERSECTIONS, EXTEND BARS AROUND CORNERS AND LAP A MINIMUM OF 40 BAR DIAMETERS.
CONDITION COVER
(INCHES) UNFORMED SURFACES IN CONTACT WITH EARTH 3 FORMED SURFACES EXPOSED TO EARTH, WATER AND/OR WEATHER 2 BOTTOM SURFACES FOR SLAB OVER WATER 2 CONCRETE SURFACES FOR DRY CONDITIONS - WALLS, SLABS AND JOISTS 1 1/2
- BEAMS AND COLUMNS:
- PRIMARY REINFORCING 2
- STIRRUPS, SPIRALS AND TIES 1 1/2
CONDUITS AND PIPES EMBEDDED IN CONCRETE
1. CONDUIT, PIPES, AND SLEEVES OF ANY MATERIAL NOT HARMFUL TO CONCRETE AND WITHIN LIMITATIONS OF THE PROJECT DRAWINGS AND SPECIFICATIONS, AND ACI 318 MAY BE PERMITTED TO BE EMBEDDED IN CONCRETE SUBJECT TO PRIOR APPROVAL BY THE ENGINEER OF RECORD, PROVIDED THEY ARE NOT CONSIDERED, BY THE
ENGINEER OF RECORD, TO DISPLACE STRUCTURAL CONCRETE, EXCEPT AS PROVIDED HEREIN. 2. CONDUITS AND PIPES OF ALUMINUM SHALL NOT BE EMBEDDED IN STRUCTURAL CONCRETE. 3. CONDUITS AND PIPES, WITH THEIR FITTINGS, EMBEDDED WITHIN A COLUMN SHALL NOT DISPLACE MORE THAN 4-PERCENT OF THE AREA OF THE CROSS SECTION ON WHICH THE STRENGTH IS CALCULATED OR WHICH IS REQUIRED FOR FIRE PROTECTION. THE ENGINEER OF RECORD SHALL DETERMINE IF THE STRENGTH OF THE CONSTRUCTION HAS BEEN SIGNIFICANTLY IMPAIRED. 4. CONDUITS AND PIPES EMBEDDED WITHIN A SLAB, WALL, OR BEAM SHALL SATISFY THE FOLLOWING: a) THEY SHALL NOT BE LARGER IN OUTSIDE DIAMETER THAN 1/3 THE OVERALL THICKNESS OF SLAB, WALL, OR BEAM IN WHICH THEY ARE EMBEDDED. b) MINIMUM CENTER-TO-CENTER SPACING BETWEEN CONDUIT AND/OR PIPING RUNS SHALL BE 3 TIMES OUTSIDE DIAMETER OR WIDTH. c) THEY SHALL BE LOCATED IN SUCH A MANNER AS TO MAINTAIN A MINIMUM OF 1-INCH CLEAR SPACE BETWEEN THE EMBEDDED ITEM AND PRIMARY REINFORCEMENT. d) THEY SHALL NOT SIGNIFICANTLY IMPAIR THE STRENGTH OF THE CONSTRUCTION. THE ENGINEER OF RECORD SHALL DETERMINE IF THE STRENGTH OF THE CONSTRUCTION HAS BEEN SIGNIFICANTLY IMPAIRED. 5. NO LIQUIDS, GAS, OR VAPOR, EXCEPT WATER NOT EXCEEDING 90 DEGREES FAHRENHEIT NOR 50 PSI, SHALL BE PLACED IN THE PIPES UNTIL THE CONCRETE HAS ATTAINED ITS DESIGN STRENGTH. 6. IN SOLID SLABS, CONDUITS AND/OR PIPING SHALL BE PLACED BETWEEN THE TOP AND BOTTOM REINFORCEMENT AT THE CENTERLINE OF THE SLAB. AT A MINIMUM, THEY SHALL BE LOCATED IN SUCH A MANNER AS TO MAINTAIN A MINIMUM OF 1-INCH CLEAR SPACE BETWEEN THE EMBEDDED ITEM AND PRIMARY REINFORCEMENT. 7. CONCRETE COVER FOR PIPES, CONDUITS, AND FITTINGS SHALL NOT BE LESS THAN 2-INCHES FOR CONCRETE EXPOSED TO EARTH, CONTAINED LIQUIDS, OR WEATHER, NOR LESS THAN 1-INCH FOR CONCRETE NOT EXPOSED TO CONTAINED LIQUIDS, WEATHER OR IN CONTACT WITH GROUND. 8. ADDITIONAL REINFORCEMENT WITH AN AREA NOT LESS THAN 0.002 TIMES THE AREA OF CONCRETE SECTION SHALL BE PROVIDED NORMAL TO THE CONDUIT AND/OR PIPING. 9. CONDUITS AND/OR PIPING SHALL BE SO FABRICATED AND INSTALLED THAT CUTTING,
BENDING, OR DISPLACEMENT OF PRIMARY REINFORCEMENT FROM ITS PROPER LOCATION WILL NOT BE REQUIRED. 10. PIPES PASSING THROUGH WALLS OF A LIQUID - CONTAINING STRUCTURE SHALL INCLUDE AN INTEGRAL WATERSTOP. CONCRETE ANCHORS
1. CAST-IN ANCHOR RODS/BOLTS SHALL BE STAINLESS STEEL. TYPE 304 FOR INTERIOR DRY CONDITIONS AND TYPE 316 FOR INTERIOR WET, EXTERIOR OR SUBMERGED CONDITIONS. 2. POST-INSTALLED CONCRETE ANCHORS, INCLUDING ADHESIVE AND EXPANSION
ANCHORS, SHALL CONFORM TO MANUFACTURER'S RECOMMENDATIONS AND THE APPROPRIATE EVALUATION REPORT. ANCHORS WITHOUT A CURRENT ICC-ES ESR, IAPMO-UES ER OR EQUAL SHALL NOT BE USED. 3. UNLESS OTHERWISE INDICATED, ALL ADHESIVE AND EXPANSION ANCHORS FOR
INSTALLATION IN CONCRETE SHALL HAVE SATISFIED THE REQUIREMENTS OF THE SIMULATED SEISMIC TESTS OF ACI 355.4 OR ACI 355.2, NO SUBSTITUTION SHALL BE ALLOWED. 4. CONTRACTOR SHALL LOCATE EXISTING REBAR USING NON-DESTRUCTIVE METHODS PRIOR TO DRILLING HOLES FOR POST-INSTALLED ANCHORS. ADJUST SPACING OF ANCHORS TO MISS EXISTING REINFORCING. TOTAL NUMBER OF ANCHORS PROVIDED SHALL BE EQUAL TO THAT SHOWN ON THE DRAWINGS. 5. ADHESIVE ANCHORS SHALL CONSIST OF A TWO-COMPONENT RESIN ADHESIVE. THE PACKAGES CONTAINING EACH COMPONENT SHALL BE ATTACHED TO A DISPENSING MANIFOLD. AN AUGER STYLE NOZZLE SHALL BE ATTACHED FOR PROPER MIXING OF THE ADHESIVE COMPONENTS. WHERE THREADED RODS ARE REQUIRED, RODS SHALL CONFORM TO ASTM A193 GRADE B7. WHERE STAINLESS STEEL IS CALLED FOR ON THE DRAWINGS, STAINLESS STEEL SHALL BE TYPE 316. 6. WHERE THE DESIGN OF THE ANCHORAGE REQUIRES ADDITIONAL SUPPLEMENTAL CONCRETE REINFORCING STEEL TO PROTECT AGAINST CONCRETE FAILURE MODES, THE DESIGN OF THE ADDITIONAL SUPPLEMENTAL REINFORCING STEEL SHALL BE INCLUDED AS PART OF THE SUBMITTED ANCHORAGE CALCULATIONS. THE ADDITIONAL SUPPLEMENTAL CONCRETE REINFORCING STEEL SHALL BE TREATED AS PART OF THE REQUIRED BUILDING AND/OR EQUIPMENT ANCHORAGE AND SHALL BE PROVIDED AND INSTALLED AT NO ADDITIONAL COST TO THE DISTRICT.
CONCRETE JOINTS
1. REINFORCING STEEL SHOWN IS FOR CLARITY ONLY. SEE PLANS AND SECTIONS FOR REINFORCING SIZES, SPACING, LOCATIONS AND DETAILS. 2. ALL SURFACES SHALL BE PREPARED IN ACCORDANCE WITH SPECIFICATION SECTION 03150. 3. EXCEPT WHERE OTHERWISE NOTED ON THE DETAILS JUNCTION BARS (JB) SHALL BE THE SAME SIZE AS THE LARGER OF WALL OR SLAB REINFORCING. 4. ALL LAP SPLICES SHALL BE CLASS B TENSION CONTACT LAP. 5. UNLESS OTHERWISE NOTED, SEALANT SHALL BE PROVIDED IN JOINTS WHERE SHOWN ON THE DRAWINGS AND WHERE INDICATED BY THE FOLLOWING: a) CONTROL JOINTS FOR WALLS AND SLABS IN LIQUID CONTAINMENT STRUCTURES SHALL HAVE SEALANT APPLIED TO THE LIQUID SIDE(S) OF THE JOINT. b) EXPANSION JOINTS SHALL HAVE SEALANT APPLIED TO BOTH SIDES OF THE JOINT, EXCEPT FOR THE SOIL SIDE OF A JOINT FOR A BASE SLAB. c) CONSTRUCTION JOINTS WILL NOT REQUIRE SEALANT, UNLESS OTHERWISE NOTED ON THE DRAWINGS. 6. UNLESS OTHERWISE NOTED, WATERSTOPS SHALL BE PROVIDED IN JOINTS WHERE SHOWN ON THE DRAWINGS AND WHERE INDICATED BY THE FOLLOWING: a) IN ALL JOINTS IN WALLS AND SLABS OF LIQUID CONTAINMENT STRUCTURES TO PREVENT EXFILTRATION OF LIQUID INTO SOIL OR DRY AREAS OF THE STRUCTURE. b) IN ALL BELOW-GRADE JOINTS IN WALLS AND SLABS TO PREVENT INFILTRATION OF GROUNDWATER INTO STRUCTURE.