Item 10 Page 34 of 369
Angeles Regional Water Quality Control Board (LARWQCB) or the U.S. Environmental Protection Agency (U.S. EPA). Requests by environmental groups and the public shall be directed to the City.

D. Best Management Practices
The objective of the SWPPP is to identify potential sources of pollution that may reasonably affect the quality of storm water discharge associated with construction activities. The plan will describe and ensure the implementation of Best Management Practices (BMPs) which will be used to reduce pollutants in the storm water discharges from the construction site. A Best Management Practice is defined as any program, technology, process, operating method, measure, or device that controls, prevents, removes, or reduces pollution. The Contractor shall select appropriate BMPs from the California Stormwater BMP Handbook, Municipal, Industrial, New Development, and Construction Volumes (www.cabmphandbooks.com) in conjunction with all activities and construction operations. Copies of the California Stormwater BMP Handbooks may be obtained from:

California Stormwater Quality Association
P.O. Box 2313
Livermore, CA 94551
www.cabmphandbooks.com
Cashier
Los Angeles County DPW
900 South Fremont Avenue
Alhambra, CA 91803
Tel. No. (626) 458-6959
E. Implementation
The Contractor will be responsible throughout the duration of the Project for the installation, monitoring, inspection and maintenance of the BMPs included in the SWPPP and for removing and disposing of temporary BMPs. The Contractor may be required to implement additional BMPs as a result of changes in actual field conditions, contractor’s activities, or construction operations.

The Contractor shall demonstrate the ability and preparedness to fully deploy these SWPPP control measures to protect soil-disturbed areas of the project site before the onset of precipitation and shall maintain a detailed plan for the mobilization of sufficient labor and equipment to fully deploy these control measures.

Throughout the winter season, active soil-disturbed areas of the project site shall be fully protected at the end of each day with these control measures unless fair weather is predicted through the following day. The Contractor shall monitor daily weather forecasts. If precipitation is predicted prior to the end of the following workday, construction scheduling shall be modified, as required, and the Contractor shall deploy functioning control measures prior to the onset of the precipitation.

The City may order the suspension of construction operations which are creating water pollution if the Contractor fails to conform to the requirements of this Paragraph 2.17. Unless otherwise directed by the City, the Contractor’s responsibility for SWPPP implementation shall continue throughout any temporary suspension of the Work.

F. Sewage Spill Prevention. The Contractor’s attention is directed to the sewer bypass operation required during any sewer construction pursuant to the 2021 edition of the “Greenbook” Standard Specifications for Public Works Construction, Section 3-12.5 or as that section is subsequently amended.

The Contractor shall exercise extraordinary care to prevent the cause of events that may lead to a sewage spill. In the event of a sewage spill, the Contractor shall make arrangements for an R Dependable Const Inc.

Page 33 of 222 ends

.
.

Item 10 Page 35 of 369
emergency response unit comprised of emergency response equipment and trained personnel to be immediately dispatched to the project site.

The Contractor shall be fully responsible for preventing and containing sewage spills as well as recovering and properly disposing of raw sewage. In addition, the Contractor is responsible for any fines, penalties and liabilities arising from negligently causing a sewage spill. Any utility that is damaged by the contractor shall be immediately repaired at the Contractor’s expense. The Contractor shall take all measures necessary to prevent further damage or service interruption and to contain and clean up the sewage spills.

G. Sewage Spill Telephone Notification
Should a sewage spill occur, the Contractor shall immediately report the incident to both of these two City Departments:

Sewer Maintenance Services………………………….Vernon Control Center – (323) 826 -1461 Fire Department Dispatch Center ................................................................................. 911 The Contractor is encouraged to obtain telephone numbers, pager numbers and cellular telephone numbers of City representatives such as Project Managers and Inspectors. However, if these City representatives are not available, then the Contractor shall immediately call:

Kenneth Jackson, Facilities Maintenance Supervisor (323) 583-8811 x216 H. Sewage Spill Written Notification
The Contractor shall prepare and submit a written report to the Director within three (3) Working Days from the occurrence of a spill to the City. This report shall describe all of the following:

1. The exact location on the Thomas Guide map.

2. The nature and volume.

3. The date, time and duration.

4. The cause.

5. The type of remedial and/or cleanup measures taken and date and time implemented.

6. The corrective and preventive action taken.

7. The water body impacted and results of necessary monitoring.

I. Enforcement
The City is subject to enforcement actions by the LARWQCB, U.S. EPA, environmental groups and private citizens. The Contractor shall indemnify, defend and hold City, its officers, agents and employees harmless from Contractor’s failure to comply and/or fulfill the requirements set forth in this Paragraph 2.17. Contractor shall be responsible for all costs and liabilities imposed by law as result of Contractor’s failure to comply and/or fulfill the requirements set forth in this Paragraph 2.17.

The costs and liabilities include, but are not limited to fines, penalties and damages whether assessed against the City or the Contractor.

R Dependable Const Inc.

Page 34 of 222 ends

.
.

Item 10 Page 36 of 369
In addition to any remedy authorized by law, any money due to the Contractor under this contract shall be retained by the City until all costs and liabilities imposed by law against the City or Contractor have been satisfied.

J. Maintenance
The Contractor shall ensure the proper implementation and functioning of BMP control measures and shall regularly inspect and maintain the construction site for the BMPs identified in the SWPPP. The Contractor shall identify corrective actions and time frames in order to properly address any damaged measure, or reinitiate any BMPs that have been discontinued.

If the City identifies a deficiency in the deployment or functioning of identified control measures, the deficiency shall be corrected by the Contractor immediately or by a later date and time if agreed to by Director and if requested in writing, but not later than the onset of the subsequent precipitation events. The correction of deficiencies shall be at no additional cost to the City.

K. Payment
All costs involved in the implementation of the SWPPP, including furnishing all labor, materials, tools, equipment and all incidentals; and for doing all the work involved in installing, constructing, maintaining, removing, and disposing of control measures, except those that were installed as a part of another structure, shall be included in the unit prices bid for the various related items of work and no additional compensation will be made therefor.

2.18 SOLID WASTE DISPOSAL AND DIVERSION
The Contractor shall submit to the Director the following summary of solid waste generated by the Work, disposed in Class III landfills, or diverted from disposal through recycling. Report disposal in inert fill separately. This form must be accompanied by legible copies of weight tickets, receipts, or invoices that specifically identify the project generating the material. Said documents must be from recyclers and/or disposal site operators that are acceptable to the Director. Further, the documents must be submitted to the Director with each application for progress payment. Failure to submit the form and its supporting documentation will render the application for progress payment incomplete and delay progress payments.

R Dependable Const Inc.

Page 35 of 222 ends

.
.

Item 10 Page 37 of 369
SUMMARY OF SOLID WASTE DISPOSAL AND DiVERSION
Project TiUe: Vemon Citv Hall Third Floor Facilitres Renovations. Contract No.20260210 Form to be submitted to the City
SIGNATURE:

TITLE President/C
DATE 04t08t2026

LE AND RE LABLE P
IEND OF ARTICLE]

2.19 Type of Material (a) Disposed in
Class lll Landfllls
(b) Diverted from
Class lll Landfills by
(c) [Leave This
Column Blankl
(d) Disposed in lnert
Fills
Tons/CY Tons/CY
Asphalt N/A N/A N/A
Concrete N/A N/A N/A
lVeta I N/A N/A N/A
0ther Segregated
[/aterials (Describe)
Fntur..,{V.ll Tlbr(a) Ughl! - r
dlrpot l,nd.rt.l : l.$ thln I N/A N/A
Miscellaneous
Construction Waste
less than I/2 ton NiA N/A
Total Less than 1 ton N/A N/A
The Contractor is encouraged to propose recycled, reusable and recyclable products for use by the City.

Those items should be clearly identified. The City may require further information or documentation to ascerlain the suitability/appropriateness of a proposed product.

Tons/CY Tons/CY
R Dependable Const Inc.

Page 36 of 222 ends

.
.

Item 10 Page 38 of 369
ARTICLE 3 - TIME OF COMMENCEMENT AND COMPLETION

3.01 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
A. Notice to Proceed
The Contractor is not authorized to perform any Work the Contract Documents until he/she has received from the City an official notification to commence Work. The date on which the notification is received by the Contractor is herein referred to as the Notice to Proceed. The Contractor shall commence Work on the Date of Commencement established in the Notice to Proceed is issued. The Notice to Proceed shall be issued after the Contract is properly executed, bonds are furnished and approved, and insurance has been submitted and approved.

B. Prosecution of the Work
Work shall be continued at all times with such force and equipment as will be sufficient to complete it within the specified time. The Contractor expressly proposes that he/she has taken into consideration and made allowances for all ordinary delays and hindrances to the Work to be performed and that he/she will complete the Work within the specified time.

C. Required Contract Completion
Time is of the essence in the completion of this Contract. The Work shall be completed in its entirety and made ready for service within ninety (90) calendar days following the Date of Commencement established in the Notice to Proceed (“Contract Time”). By executing the Contract, Contractor confirms that the Contract Time is a reasonable period for performing the Work.

3.02 CITY'S DISCRETION TO EXTEND CONTRACT TIME
In the event the Work required hereunder is not satisfactorily completed in all parts and in compliance with the Contract Documents, City shall have the right, in its sole discretion, to increase the number of Working Days or not, as may seem best to serve the interest of City. A change order extending the Contract Time only will be issued by the City should the City decide to increase the number of Working Days.

3.03 SUBSTANTIAL COMPLETION
A. Contractor Request for Inspection and Punch List
When the Contractor considers that it has achieved Substantial Completion of the Work, or designated portion thereof, Contractor shall prepare and submit to the Director a request for inspection and a comprehensive punch list of items to be completed or corrected prior to Final Payment. Failure to include an item on such punch list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents.

B. City Inspection
Upon receipt of the Contractor's punch list, the Director will make an inspection to determine whether the Work or designated portion thereof is Substantially Complete. If the inspection discloses any item, whether or not included on the Contractor's punch list, which is not sufficiently complete in accordance with the Contract Documents so that the City can occupy or utilize the Work or designated portion thereof for its intended use, the Contractor shall, before City's issuance of the Certificate of Substantial Completion, complete or correct such item upon notification by City.

R Dependable Const Inc.

Page 37 of 222 ends

.
.

Item 10 Page 39 of 369
The Contractor shall then submit a request for another inspection by City to determine Substantial Completion.

C. Certificate of Substantial Completion
When the Work or designated portion thereof is substantially complete, the Director will prepare a Certificate of Substantial Completion which shall establish the date of Substantial Completion, shall establish responsibilities of the City and Contractor for security, maintenance, utilities, damage to the Work, and insurance, and shall fix the time within which the Contractor shall finish all items on the Contractor’s punch list accompanying the Certificate. Warranties required by the Contract Documents shall commence on the date of Substantial Completion of the Work. Contractor shall deliver to City all warranty and guarantee documents and policies.

3.04 DELAYS AND EXTENSIONS OF TIME FOR CONTRACTOR
A. The Contractor shall take reasonable precautions to foresee and prevent delays to the Work. In the event of any delay to the Work, the Contractor shall revise his/her sequence of operations, to the extent possible under the terms of the Contract, to offset the delay.

B. If any delay to the Work is caused by circumstances within the Contractor's control, it is not excusable and not compensable, and the Contractor will not be entitled to any extension of time or to any other compensation for damages resulting directly or indirectly therefrom.

C. If any delay having a direct effect on the Work is caused by circumstances beyond the control of the Contractor except for causes of delay specified in Paragraph 3.04-D., such delay may be excusable and may entitle the Contractor to an equivalent extension of time, but not to any other compensation.

Excusable but not compensable causes include but are not limited to labor disputes, weather conditions unfavorable for prosecution of the Work, and force majeure.

D. If any delay having a direct effect on the Work is caused by failure of the City to provide information as specified, or necessary instructions for carrying on the Work, or to provide the necessary right of way or site for installation, or failure of a utility to remove or relocate an existing facility such delay may be compensable and may entitle the Contractor to an equivalent extension of time, and to compensation for damages resulting directly from any of the causes of delay specified in this paragraph.

E. The Contractor shall notify the Director in writing of any delay having a direct effect on the Work and the causes thereof within 15 days from the beginning of such delay.

F. Any claim for an extension of time or for compensation for damages resulting from delay shall be made in writing to the Director not more than 30 days after the ending of such delay. The Contractor shall provide a written report evaluating the impact of the delay which shall include, at a minimum, all of the following:

1. a narrative description of the delay and its impact on the critical path to Substantial Completion of the Work or a portion of the Work designated by City;

2. a detailed breakdown of the Allowable Costs, if any, sought by Contractor due to the delay;

3. the number of days of extension sought by Contractor as an adjustment to the Contract time;

4. a statement that Contractor has complied with the requirements of the General Conditions for written notice of delays, along with the dates and copies of such notices;

5. the measures taken by Contractor and Subcontractors to prevent or minimize the delay; and R Dependable Const Inc.

Page 38 of 222 ends

.
.

Item 10 Page 40 of 369

6. the Contactor’s recommendations for reordering or re-sequencing the Work to avoid or minimize further delay.

No extension of time or compensation for damages resulting from delay will be granted unless the delay affects the timely completion of the overall Work under the Contract or the timely completion of a portion of the Work for which a time of completion is specified.

G. The Director will investigate the facts and ascertain the extent of the delay, and his/her findings thereon shall be final and conclusive.

H. Failure of the Contractor to give written notice of a delay, or to submit or document a claim for an extension of time or for damages resulting from delay in the manner and within the times stated above shall constitute a waiver of all claims thereto.

I. When a Contractor experiences two concurrent delays, one compensable and the other excusable, no compensation other than an extension of time will be allowed.

J. An extension of time must be approved by the Director to be effective, but an extension of time whether with or without consent of the sureties, shall not release the sureties from their obligations, which shall remain in full force until the discharge of the Contract.

3.05 CLIMATIC CONDITIONS
A. The Director may suspend the Work whenever weather conditions or conditions resulting from inclement weather are unfavorable for the prosecution of the Work. The delay caused by such suspension may entitle the Contractor to an extension of time but not to any other compensation.

B. If the Contractor believes that Work should be suspended under this Paragraph 3.05, he/she may request such suspension. The delay caused by such suspension may entitle the Contractor to an extension of time but not to any other compensation.

C. No extension of time will be granted for suspension of Work unless the suspension affects the timely completion of all Work under the Contract or the timely completion of a portion of the Work for which a time of completion is specified. Determination that the suspension for inclement weather conditions or conditions resulting from inclement weather affects timely completion and entitles the Contractor to an extension of time shall be made and agreed to in writing by the Director and the Contractor on each day that Work is suspended. In the event of failure to agree, the Contractor may protest under the provisions of Paragraph 7.07.

D. If Work is suspended and an extension of time is granted under this Paragraph 3.05 the Contractor will be entitled to a one day extension of time for each day that he/she is unable to Work at least one-half of his/her current normal Work day; and if the Work is suspended at the regular starting time on any Work day and the Contractor's Workforce is dismissed as a result thereof, then he/she will be entitled to a one day extension of time whether or not conditions change thereafter and the major portion of the day is suitable for Work.

3.06 COMPLETION AND ACCEPTANCE
A. Upon request by the Contractor, the Director shall conduct a final inspection of the Work. If, in the Director’s opinion, Final Completion has been achieved, the Director will accept the Work by issuing a “Notice of Completion” of the Work to the Contractor. Upon the issuance of the Notice of Completion the Contractor will be relieved from responsibility to protect the Work.

B. Within 15 calendar days after issuing the Notice of Completion, the Director will record the Notice of R Dependable Const Inc.

Page 39 of 222 ends

.
.

Item 10 Page 41 of 369
Completion with the County Recorder.

3.07 LIQUIDATED DAMAGES
A. Contractor and City agree to liquidate damages in the amount of two hundred and fifty dollars ($250.00) per day, with respect to Contractor’s failure to achieve Substantial Completion of the Work within the Contract Time. The Parties intend for the liquidated damages set forth herein to apply to this Contract as set forth in Government Code Section 53069.85. The Contractor acknowledges and agrees that the liquidated damages are intended to compensate City solely for the Contractor’s failure to meet the deadline for Substantial Completion and shall not excuse Contractor from liability from any other breach, including any failure of the Work to conform to the requirements of the Contract Documents.

B. In the event that Contractor fails to achieve Substantial Completion of the Work within the Contract Time, Contractor agrees to pay City the amount specified in the Contract form for each calendar day that Substantial Completion is delayed.

C. Contractor and City acknowledge and agree that the foregoing liquidated damages have been set based on an evaluation of damages that the City will incur in the event of late completion of the Work.

Contractor and City acknowledge and agree that the amount of such damages are impossible to ascertain as of the effective date hereof and have agreed to such liquidated damages to fix City’s damages and to avoid later disputes. It is understood and agreed by Contractor that liquidated damages payable pursuant to this Agreement are not a penalty and that such amount are not manifestly unreasonable under the circumstances existing as of the effective date of this Agreement.

D. It is further mutually agreed that City shall have the right to deduct liquidated damages against progress payments or retainage and that the City will issue a Construction Change Directive and reduce the Contract Sum accordingly. In the event the remaining unpaid Contract Sum is insufficient to cover the full amount of liquidated damages. Contractor shall pay the difference to City. [END OF ARTICLE]
R Dependable Const Inc.

Page 40 of 222 ends

.
.

Item 10 Page 42 of 369
ARTICLE 4 - CONSTRUCTION SCHEDULES

4.01 BASELINE PROJECT SCHEDULE
The Contractor shall submit his/her work Baseline Project Schedule, in electronic as well as hard-copy format, to the Director at the pre-construction meeting showing in detail how the Contractor plans to execute and coordinate the Work. The construction schedule shall show the sequence of work, critical path and estimated time for completion of each segment of work. This schedule must be reviewed and accepted by the Director before the Contractor will be permitted to begin work. In addition, the Contractor shall submit a detailed schedule forecasting two (2) weeks of work describing each day’s work. This schedule shall be updated and submitted to the City every other Monday during the construction period. The Contractor shall give 48 hours notice to the City Engineer prior to the start of the work.

A. Format

1. At a minimum, the Baseline Project Schedule activities shall be coded on a work discipline basis and by geographic area or location on the Project. The Baseline Project Schedule shall include a detailed description of each activity code. The Baseline Project Schedule shall be based on and incorporate contract milestone and completion dates specified in the Contract Documents. It shall depict events, jobs, and their interrelationships and shall recognize the progress that must be made on one task before subsequent tasks can begin. The schedule shall be comprehensive and shall include all logical interdependencies and interactions required to perform the Work of the Project.

2. Overall time of completion and time of completion for each milestone shown on the Schedule shall adhere to the specified Contract Time, unless an earlier (advanced) time of completion is requested by Contractor, agreed to by the City and formalized by Change Order.

3. Contractor shall use the latest version of Microsoft Project or equivalent software agreed to by the parties.

4. The City will review the submitted Baseline Project Schedule for conformance with these scheduling requirements. Within fourteen (14) calendar days after receipt, the City will accept the proposed Baseline Project Schedule or will return it with comments. If the proposed Baseline Project Schedule is accepted by the City, it shall be deemed part of the Contract Documents. If the Baseline Project Schedule is not accepted by City, Contractor shall revise the Baseline Project Schedule, in accordance with the recommendations of the City, and re-submit same for acceptance, no later than seven (7) calendar days after receipt of said recommendation.

5. Acceptance of Baseline Project Schedule by City, failure to include an element of work, or inaccuracy in Baseline Project Schedule shall not relieve Contractor from the responsibility for accomplishing the Work in accordance with the Contract Documents.

B. Float

1. Critical Work activities are defined as Work activities which, if delayed or extended, will delay the scheduled completion of the milestones and/or time of completion. All other Work activities are defined as non-critical Work activities and are considered to have float. Float is defined as the time that a non-critical Work activity can be delayed or extended without delaying the scheduled completion of the milestones and/or time of completion. Float is considered a Project resource available to either party or both parties as needed. Once identified, Contractor shall monitor, account for, and maintain float in accordance with Critical Path Methodology.

R Dependable Const Inc.

Page 41 of 222 ends

.
.

Item 10 Page 43 of 369

2. Delays of any non-critical Work shall not be the basis for an extension of Contract Time until the delays consume all float associated with that non-critical Work activity and cause the Work activity to become critical.

3. It is acknowledged that City-caused time savings (i.e., critical path submittal reviews returned in less time than allowed by the Contract Documents, approval of substitution requests which result in a savings of time for Contractor, etc.) create shared float. Accordingly, City-caused delays may be offset by City-caused time savings.

C. Weather (This section applies only to projects of one (1) year duration or longer) The completion time contemplated by this Contract anticipates zero (0) lost days (Work Days) due to normal weather conditions annually and prorated for any duration less than twelve months. Only unusual or extreme weather conditions, as determined by the National Oceanic and Atmospheric Administration, for the time of year will be considered as justification for an extension of time to complete the Project, and only after the zero (0) weather days have been utilized. Annual weather days are not cumulative, and unused days shall become “float” for the benefit of the project, and the schedule adjusted accordingly. The use of weather days by the Contractor shall be subject to all the conditions of claim for an extension of time. The Contractor shall notify the City in writing within ten (10) days of the commencement of each rain event.

D. Early Completion
While the Contractor may schedule completion of the Project earlier than the date established by the Contract Documents, no additional compensation shall become due the Contractor for the use of float time between the Contractor’s projected early completion date and the date for Substantial Completion established by the Contract Documents, unless an earlier (advanced) time of completion is requested by Contractor, agreed to by the City, and formalized by Change Order.

4.02 SCHEDULE UPDATES
A. With each Application for Payment submitted by Contractor (other than the final Application for Payment), the Contractor shall submit to the City an updated Project Schedule revised to indicate the Work completed, status of Work in progress, all progress slippages, corrective actions taken, or slippage carry-over, for all anticipated delays or difficulties, and all other information required to accurately present the actual status of the progress of the Work as of the date of the Application for Payment. If the Contractor does not submit an updated Project Schedule with an Application for Payment, City may withhold payment, in whole or in part, until the updated Project Schedule is submitted. In the event that an update to the Project Schedule indicates a delay to the Contract Time the Contractor shall propose an affirmative plan to correct each such delay, including overtime and/or additional labor, if necessary. In no event shall any Project Schedule update constitute an adjustment in the Contract Time, any deadline, or the Contract Sum unless any such adjustment is agreed to by the City and authorized pursuant to Change Order or Work Directive.

B. At no time shall historical data contained within the updated Project Schedule (i.e. completed activities) be removed and/or altered in any way. This historical data is to be preserved within each of the updated Project Schedules and submitted with the final schedule update to reflect the actual start and finish dates for each activity within the Schedule.

C. Any work stoppages within individual work activities that exceed seven (7) calendar days in duration shall be clearly indicated within the updated Project Schedule. In cases where unplanned activity work R Dependable Const Inc.

Page 42 of 222 ends

.
.

Item 10 Page 44 of 369
stoppages exceed seven (7) calendar days activities shall be added to the Project Schedule to clearly indicate the work stoppage period and identify forecasted resumption and completion of the activity where work has stopped. Contractor shall clearly note all schedule revisions when Project Schedule updates are submitted, as required in this Paragraph 4.02 above.

4.03 NONCOMPENSABLE EXTRAORDINARY MEASURES
A. Should the City determine, in its sole judgment, that the performance of the Work has not progressed to the level of completion required by the Contract Documents, City shall have the right to order the Contractor to take corrective measures to expedite the progress of construction, at no additional cost to the City, including, without limitation, the following:

1. Working additional shifts of overtime.

2. Supplying additional manpower, equipment, and/or facilities.

3. Reschedule activities to maximize practical concurrence of accomplishment of activities.

4. Submitting a Recovery Schedule discussed above, for resequencing performance of the Work or other similar measures.

5. Any other actions that may be necessary to mitigate delays.

B. Such Extraordinary Measures shall continue until the progress of the Work is no longer behind schedule and/or reaches the stage of completion required by the Contract Documents. Contractor shall not be entitled to an adjustment in the Contract Sum in connection with the performance of any such Extraordinary Measures required by the City under this Paragraph. The City may exercise the rights furnished the City pursuant to this Paragraph as frequently as the City deems necessary to ensure that the Contractor’s performance of the Work will comply with the Contract Time or interim completion dates set forth in the Contract Documents. If Contractor or its Subcontractors fail to implement or commence Extraordinary Measures within ten (10) calendar days of City’s written demand, City may, without prejudice to other remedies, take corrective action at the expense of the Contractor which shall reduce the Contract Sum accordingly.

4.04 CONDITION OF PAYMENT
Compliance by Contractor with the requirements of the Contract Documents pertaining to preparation, submission, revising and updating of the Schedule is a condition precedent to City’s obligation to make payment to Contractor of any or all sums that might otherwise be due to Contractor in the absence of such noncompliance.

Payment by City under circumstances in which City, for any reason, fails or elects not to assert its right to withhold payment for noncompliance with this Paragraph shall not be construed as a waiver of the right to withhold future payments on account of such noncompliance or any other noncompliance. [END OF ARTICLE]
R Dependable Const Inc.

Page 43 of 222 ends

.
.

Item 10 Page 45 of 369
ARTICLE 5 - SUSPENSION OR TERMINATION OF CONTRACT

5.01 TERMINATION BY THE CONTRACTOR
A. Contractor shall have the right to terminate its performance of the Contract only upon the occurrence of one of the following:

1. The Work is stopped for a period of ninety (90) consecutive days through no act or fault of the Contractor, any Subcontractor, Sub-subcontractor, their agents or employees, or any other persons or entities performing portions of the Work under direct or indirect contract with the Contractor, due to:
a. the issuance of an order of a court or other public authority having jurisdiction; or b. an act of government, such as a declaration of national emergency making material unavailable;
and Contractor has given City written notice within ten (10) days of the occurrence of such ground for termination, then the Contractor may, upon thirty (30) additional calendar days written notice to City, unless the reason has theretofore been cured, terminate its performance of the Work.

2. The Work is stopped for a period of 120 consecutive days through no act or fault of Contractor, any Subcontractor, Sub-subcontractor, their agents or employees, or any other persons or entities performing portions of the Work under direct or indirect contract with the Contractor, because the City has persistently failed to perform any material obligation under the Contract Documents and fails to cure such default within ninety (90) days after the receipt of notice from Contractor stating the nature of such default.

B. If Contractor terminates its performance of the Contract in accordance with this Paragraph 5.01, the City shall pay Contractor for the Work executed through the date of termination as set forth in Paragraph

5.04-C below.

5.02 TERMINATION BY THE CITY FOR CAUSE
A. Grounds
The City shall have the right to terminate the Contractor’s performance of the Contract, in whole or in part, without liability to City if:

1. Contractor fails promptly to begin the Work under the Contract Documents; or

2. Contractor refuses or fails to supply enough properly skilled workers or proper materials; or

3. Contractor fails to perform the Work in accordance with the Contract Documents, including conforming to applicable standards set forth therein in constructing the Project, or refuses to remove and replace rejected materials or unacceptable Work; or

4. Contractor discontinues the prosecution of the Work (exclusive of work stoppage: (a) due to termination by City; or (b) due to and during the continuance of a Force Majeure event or suspension by City); or
R Dependable Const Inc.

Page 44 of 222 ends

.
.

Item 10 Page 46 of 369

5. Contractor fails to resume performance of Work which has been suspended or stopped, within a reasonable time after receipt of notice from City to do so or (if applicable) after cessation of the event preventing performance; or

6. Any representation or warranty made by Contractor in the Contract Documents or any certificate, schedule, instrument, or other document delivered by Contractor pursuant to the Contract Documents shall have been false or materially misleading when made; or

7. Contractor fails to make payment to Subcontractors or Material Suppliers for materials or labor in accordance with the respective Contract Documents and applicable law; or

8. Contractor disregards laws, ordinances, or rules, regulations, or orders of a public authority having jurisdiction; or

9. Contractor is guilty of breach of a provision of the Contract Documents; or

10. Contractor becomes insolvent, is adjudicated bankrupt, or makes a general assignment for the benefit of creditors and fails to provide City with adequate assurances of Contractor’s ability to satisfy its contractual obligations.

A receiver, trustee, or other judicial officer shall not have any right, title, or interest in or to the Contract.

Upon that person’s appointment, City has, at its option and sole discretion, the right to immediately cancel the Contract and declare it null and void.

B. City’s Rights.

When any of the reasons specified in Paragraph 5.02-A exist, the City may, in addition to and without prejudice to any other rights or remedies of the City, and after giving the Contractor five (5) calendar days written notice, terminate Contractor’s performance of the Work, in whole or in part, and may:

1. Take possession of the site and all materials, equipment, tools, construction equipment, and machinery thereon owned by the Contractor;

2. Withhold from Contractor amounts unpaid hereunder and to offset such amounts against damages or losses incurred by City;

3. Accept assignment of subcontracts from Contractor, at the sole discretion of City, and

4. Finish the Work by whatever reasonable method the City may deem expedient.

Upon request of the Contractor, the City shall furnish to the Contractor a detailed accounting of the costs incurred by the City in finishing the Work.

C. Costs
If City’s costs to complete and damages incurred due to Contractor’s default exceed the unpaid Contract balance, the Contractor shall pay the difference to the City.

D. Wrongful Termination
If it has been adjudicated or otherwise determined that City has wrongfully terminated the Contractor R Dependable Const Inc.

Page 45 of 222 ends

.
.

Item 10 Page 47 of 369
for cause, then said termination shall be deemed converted to a termination for convenience as set forth in Paragraph 5.04 and Contractor’s remedy for wrongful termination in such event shall be limited to the recovery of the payments permitted for termination for convenience as set forth in Paragraph

5.04. 5.03 PARTIAL DELETION OR SUSPENSION OF WORK BY THE CITY A. Contractor agrees that the City may determine whether any or all of the Work described in the Contract Documents shall be deleted or performance suspended without electing to terminate the Contractor’s performance under the Contract and without any penalty being incurred by the City.

B. Any such partial deletion or suspension of the Work shall in no way void or invalidate the Contract nor shall it provide Contractor with any basis for seeking payment from City for Work deleted or suspended except to the extent such Work has already been performed and is otherwise compensable under the Contract.

C. The City shall have the right to later have any such suspended or deleted Work performed by Contractor or others without any penalty to the City.

D. In the event of any partial or complete deletion or suspension of Work, the City shall furnish Contractor with prompt written notice thereof, and the City shall be entitled to take possession of and have as its property all Record Documents, Accounting Records, and other data prepared by Contractor or its Subcontractors.

E. Suspension for Convenience.

1. The City may at any time and from time to time, without cause, order the Contractor, in writing, to suspend, delay, or interrupt the Work in whole or in part for such period of time as the City may determine. Such order shall be specifically identified as a “Work Suspension Directive” under this Section.

2. Upon receipt of a Work Suspension Directive, Contractor shall, at the City’s expense, comply with its terms and take all reasonable steps to minimize costs allocable to the Work covered by the Work Suspension Directive during the period of Work stoppage.

3. Within the period of suspension, or such extension to that period as is agreed upon by Contractor and the City, the City shall either cancel the Work Suspension Directive or delete the Work covered by such Work Suspension Directive by issuing a Change Order or Construction Change Directive.

4. If a Work Suspension Directive is cancelled or expires, Contractor shall continue the Work. A Change Order or Construction Change Directive will be issued to cover any adjustments of the Contract Sum and Contract Time necessarily caused by such suspension. No adjustment shall be made to the extent:
(a) That performance is, was, or would have been so suspended, delayed, or interrupted by another cause for which the Contractor is responsible; or (b) That an equitable adjustment is made or denied under another provision of the Contract.

F. Suspensions for Cause
City has the authority by written order to suspend the Work, in whole or in part, without liability to City R Dependable Const Inc.

Page 46 of 222 ends

.
.

Item 10 Page 48 of 369
for Contractor’s failure to:

1. Correct conditions unsafe for the Project personnel or general public, or

2. Carry out the Contract; or

3. Carry out orders of City.

G. Responsibilities of Contractor During Suspension Periods During periods that Work is suspended, Contractor shall continue to be responsible for the Work and shall prevent damage or injury to the Project, provide for drainage, and shall erect necessary temporary structures, signs or other facilities required to maintain the Project and continue to perform according to the Contract Documents.

5.04 TERMINATION BY THE CITY FOR CONVENIENCE
A. Grounds
Without limiting any rights which City may have by reason of any default by Contractor hereunder, City may terminate Contractor’s performance of the Contract, in whole or in part, at any time, for convenience upon fifteen (15) calendar days written notice to Contractor.

B. Contractor Actions
Upon receipt of such notice, Contractor shall perform the duties required by Paragraph 5.05 below.

At the election of and as directed by the City, any or all of the subcontracts and purchase orders entered in to by Contractor prior to the effective date of termination shall be terminated or shall be assigned to City.

C. Compensation

1. If the Parties are unable to agree on the amount of a termination settlement, the City shall pay the Contractor the following amounts:
a. For Work performed before the effective date of termination, the total (without duplication of any items) of:
i. The cost of the Work; and
ii. A sum, as overhead and profit on the cost of the Work, determined by the City to be fair and reasonable. In no event shall Contractor be entitled to recover overhead or profit on Work not performed.
b. The reasonable costs of settlement of the Work terminated, including:
i. Accounting, clerical, and other expenses reasonably necessary for the preparation of termination settlement proposals and supporting data, if any; and ii. Storage, transportation, and other costs reasonably necessary for the preservation, protection, or disposition of inventory.

R Dependable Const Inc.

Page 47 of 222 ends

.
.

Item 10 Page 49 of 369

2. Such payment shall be Contractor’s exclusive remedy for termination for convenience and will be due and payable on the same conditions as set forth for final payment to the extent applicable.

Upon receipt of such payment, the Contractor and City shall have no further obligations to each other except for Contractor’s obligations with respect to warranties, representations, indemnity, maintenance of insurance, and other obligations that survive termination or Final Completion as provided for herein.

3. It is understood and agreed that no fee, anticipated profit, compensation for lost opportunity costs, or other compensation or payment of any kind or character shall be due or payable for unperformed Work regardless of the basis of termination and the inclusion of this provision within this subparagraph shall in no way limit its application to termination under this Paragraph.

4. Contractor agrees that each of its subcontracts will reserve for the Contractor the same right of termination for convenience provided by this Paragraph 5.04.

D. No Consequential Damages
Under no circumstances shall Contractor be entitled to anticipatory or unearned profits or consequential or other damages as a result of a termination or partial termination under this Article 5. The payment to Contractor determined in accordance with this Article constitutes Contractor’s exclusive remedy for a termination hereunder.

5.05 CONTRACTOR’S DUTIES UPON TERMINATION FOR CAUSE OR CONVENIENCE If the City terminates Contractor’s performance of Work under the Contract, for cause or convenience or if Contractor terminates a Subcontractor with the City’s approval, Contractor shall:
(1) cease performance of the Work to the extent specified in the notice; (2) take actions necessary or that the City may direct, for the protection and preservation of the Work; (3) settle outstanding liabilities, as directed by City; (4) transfer title and deliver to City Work in progress, specialized equipment necessary to perform the Work; (5) submit all Record Documents, Accounting Records and other data prepared pursuant to the Contract by Contractor and/or its Subcontractors, as applicable, to the City with fifteen (15) calendar days after the City’s notice of termination in an organized, usable form, in both hard copy and electronic/digital form, with all items properly labeled to the degree of detail specified by the City; and, (6) except for Work directed by City to be performed prior to the effective date of termination stated in the notice, incur no further costs or expenses and enter into no further subcontracts and purchase orders.

No compensation shall be due Contractor, if any, until Contractor complies with the requirements of this Paragraph.
[END OF ARTICLE]
R Dependable Const Inc.

Page 48 of 222 ends

.
.

Item 10 Page 50 of 369
ARTICLE 6 – CHANGES

6.01 CITY'S RIGHT TO ORDER CHANGES
The City, without invalidating the Contract, may authorize changes in the Work consisting of additions, deletions, or other revisions, with the Contract Sum and Contract Time being adjusted accordingly, if necessary. All such changes in the Work shall be authorized by Change Order or Construction Change Directive and Contractor shall perform such changes in the Work according to the applicable requirements of the Contract Documents.

6.02 APPLICABLE PROVISIONS
Changes in the Work shall be performed under applicable provisions of the Contract Documents. The Contractor shall proceed promptly and diligently with the change, unless otherwise provided in the Change Order or Construction Change Directive. It is of the essence to this Contract that all scope changes in the Work that form the basis of an adjustment of the Contract Sum or Contract Time must be authorized in advance in writing through either a Change Order or Construction Change Directive. A change in the Contract Sum or the Contract Time shall be accomplished only by Change Order or Construction Change Directive.

Accordingly, no verbal directions, course of conduct or dealings between the Parties, express or implied acceptance of alterations or additions to the Work, or claim that the Contract has been abandoned or the City has been unjustly enriched by any alteration or addition to the Work shall be the basis of any claim for an increase in any amounts due under the Contract Documents or a change in any time period provided in the Contract Documents.

6.03 NOTICE OF SCOPE CHANGE
Contractor shall submit written notice of any change in scope to the Director if, in the Contractor’s opinion, any instruction, request, Drawings, Specifications, action, condition, omission, default, or other situation occurs that the Contractor believes constitutes a scope change or other matter resulting in Extra Work, for which Contractor believes it is entitled to an adjustment of the Contract Sum or Contract Time. Such notice shall be provided prior to performance of the Work affected by such occurrence and within seven (7) calendar days after the discovery date of the circumstances of such scope change or other matters. The written notice shall state the date, circumstances, extent of adjustment to the Contact Sum or the Contract Time, if any, requested. The mere presentation of such notice shall not establish the existence of any right by Contractor to adjustment of the Contract Sum or Contract Time. Failure to provide such timely written notice described herein shall constitute a waiver by Contractor of the right to any adjustment to the Contract Sum or Contract Time on account thereof.

6.04 CHANGE ORDERS
A. Computation
Methods used in determining adjustments to the Contract Sum by Change Order may include those listed in Paragraph 6.06 below.

B. Accord and Satisfaction
Agreement on any Change Order shall be a full compromise and settlement of all adjustments to Contract Time and Contract Sum, and compensation for any and all delay, extended or additional field and home office overhead, disruption, acceleration, inefficiencies, lost labor or equipment productivity, differing Site conditions, construction interferences and other extraordinary or R Dependable Const Inc.

Page 49 of 222 ends

.
.

Item 10 Page 51 of 369
consequential damages (hereinafter called "Impacts"), including any ripple or cumulative effects of said Impacts on the overall Work under the Contract arising directly or indirectly from the performance of Work described in the Change Order. By execution of any Change Order, Contractor agrees that the Change Order constitutes a complete accord and satisfaction with respect to all claims for schedule extension, Impacts, or any costs of whatever nature, character or kind arising out of or incidental to the Change Order. No action, conduct, omission, product failure or course of dealing by the City shall act to waive, modify, change, or alter the requirement that (i) Change Order's must be in writing, signed by the City and Contractor and; (ii) that such written Change Orders are the exclusive method for effectuating any change to the Contract Sum and/or Contract Time.

6.05 CONSTRUCTION CHANGE DIRECTIVE (FIELD DIRECTIVE)
A. A Construction Change Directive shall be used in the absence of total agreement on the terms of a Change Order. The City may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletion, or other revisions, the Contract Sum and Contract Time being adjusted accordingly.

B. If the Construction Change Directive provides for an adjustment to the Contract Sum, the adjustment shall be calculated in accordance with Paragraph 6.06 herein (Pricing Changes in the Work).

C. Upon receipt of the Construction Change Directive, the Contractor shall promptly proceed with the change in the Work involved and advise the City of the Contractor’s agreement or disagreement with the method, if any, provided in the Construction Change Directive, for determining the proposed adjustment in the Contract Sum or Contract Time.

D. If Contractor believes a Construction Change Directive constitutes a basis for adjustment to the Contract Sum or Contract Time, then Contractor shall give a Notice of Scope Change provided in Paragraph 6.03, followed by a submission of a Change Order Request as required by Paragraph

6.08. Contractor shall, if requested by City in such Construction Change Directive or in a subsequent Construction Change Directive, proceed with the performance of the Work as described in the Construction Change Directive. Failure of Contractor to proceed with the performance of Work, as described in the Construction Change Directive shall give the City the right to carry out the Work, as set forth in Paragraph 2.05.

E. A Construction Change Directive signed by the Contractor indicates the Contractor’s agreement therewith, including adjustment in Contract Sum and Contract Time or the method for determining them. Such agreement shall be effective immediately and shall be recorded as a Change Order.

F. If the Contractor does not respond promptly or disagrees with the method for adjustment in the Contract Sum, the method and the adjustment shall be determined by the City on the basis of reasonable expenditures and savings of those performing the Work attributable to the change, including, in the case of an increase in the Contract Sum, Allowable Mark-Ups in accordance with Paragraph 6.06(E) herein.

6.06 PRICING CHANGES IN THE WORK
A. Alternative Methods of Pricing
The amount of any adjustment by Change Order or Construction Change Directive increasing or decreasing the Contract Sum shall be determined by the Director using one or a combination of the following methods:

R Dependable Const Inc.

Page 50 of 222 ends

.
.

Item 10 Page 52 of 369

1. Lump Sum. By mutual acceptance of a lump sum proposal from Contractor properly itemized and supported by sufficient substantiating data to permit evaluation. Such proposal shall be based solely on Allowable Costs, as defined in Subparagraph 6.06-C, and Allowable Mark-Ups, as defined in Subparagraph 6.06-E, and shall not include any costs or expense that is not permitted by the terms of any provision of the Contract Documents.

2. Unit Prices. By unit prices contained in Contractor’s original Bid and incorporated in the Contract Documents or fixed by subsequent agreement between City and Contractor. Unless otherwise stated in the Bidding Documents, unit prices stated in the Contract Documents or agreed upon by the County and Contractor shall be deemed to include and encompass all Allowable Markups.

3. Time and Materials. By calculating the actual Allowable Costs directly incurred, plus a sum for Allowable Mark-Ups on such Allowable Costs.

4. Deletion of Work. By Unit Prices contained in Contractor’s original Bid and incorporated in the Contract Documents, or by using the Schedule of Values to determine the value of the decrease of the Contract Sum, less the value of any Work performed, plus a reasonable percentage of the decrease for the Contractor’s saved overhead unless the Schedule of Values allocates general conditions costs to individual line items, in which case no percentage of the decrease shall be added. When a change consists of both addition and deletion of Work, the added costs and deleted costs shall be calculated separately, and then added together, resulting in the net cost for the change. The Allowable Mark-Up shall be applied to this net cost.

B. Contractor Maintenance of Daily Records for Changes

1. In the event that Contractor is directed to perform any Extra Work, or should Contractor encounter conditions which the Contractor believes would obligate the City to adjust the Contract Sum and/or the Contract Time, Contractor shall maintain detailed records of the cost of such changes on a daily basis summarized in a daily report supplemented by back-up records. Such records shall include without limitation:
a. Labor. At the close of each day on which such Extra Work is performed, Contractor shall submit an Extra Work labor report, on forms provided by Director, to Director that sets forth a list of the actual hours spent in performing the Extra Work, that clearly differentiates between the labor expended on the Extra Work and other Work, and the Allowable Costs for such Extra Work performed that day showing the names of workers, their classifications, hours worked and hourly rates. b. Materials, Equipment. A list of Allowable Costs of materials and equipment consumed in the performance of the Extra Work on the day on which such Extra Work is performed, together with copies of applicable delivery tickets and unit prices for all materials and for all equipment used the type of equipment, identification number, hours of operation (including loading and transportation) and hourly/daily rates involved for that day.
c. Other Services or Expenditures. A list of other services and expenditures constituting Allowable Costs incurred in performance of the Extra Work on the day on which such Extra Work is performed, along with documentation verifying the amounts thereof in such detail as Director may require.

R Dependable Const Inc.

Page 51 of 222 ends

.
.

Item 10 Page 53 of 369

2. In the event that more than one change to the Work is performed by the Contractor in a calendar day, Contractor shall maintain separate records of labor, construction equipment, materials, and equipment for each such change. In the event that any Subcontractor of any tier shall provide or perform any portion of any change to the Work, Contractor shall require that each such Subcontractor maintain records in accordance with this Section.

3. Each daily record maintained hereunder shall be signed by Contractor; such signature shall be deemed Contractor’s representation and warranty that all information contained therein is true, accurate, complete, and relates only to the change referenced therein. All records maintained by Subcontractors of any tier, relating to the costs of a change in the Work shall be signed by such Subcontractor’s authorized project manager or superintendent.

All such records shall be forwarded to the Director on the day the Work is performed (same day) for independent verification. The Director shall attempt to review and reconcile costs for changes on a daily basis. Records not available on the day on which the Extra Work is performed, such as, but not limited to, material invoices, shall be submitted as soon as they are available but not later than five (5) calendar days after the earlier of the day of delivery or incorporation of the particular item of Extra Work at the Site.

4. The Director may additionally require authentication of all time and material tickets and invoices by persons designated by the Director for such purpose. In the event that Contractor shall fail or refuse, for any reason, to maintain or make available for inspection, review, and/or reproduction such records, adjustments to the Contract Sum or Contract Time, if any, on account of any change to the Work may be deemed waived for that day. Contractor’s obligation to maintain back-up records hereunder is in addition to, and not in lieu of, any other Contractor obligation under the Contract Documents with respect to changes to the Work.

5. Waiver by Contractor. Failure to submit such records as are required by this Paragraph daily shall waive any rights for recovery of Allowable Costs incurred for Extra Work performed that day. The failure of the Contractor to secure any required authentication shall, if the City elects in its sole discretion to treat it as such, constitute a waiver by the Contractor of any right to adjustment of the Contract Sum for the Allowable Cost of all or that portion of the Extra Work covered by such non-authenticated ticket or invoice.

C. Allowable Costs
The term “Allowable Costs” shall mean in the case of Extra Work actual costs incurred by Contractor and/or any Subcontractor, regardless of tier, and necessarily involved in direct performance of the Extra Work, or in the case of deleted work the actual costs that would have been incurred in performing deleted work by Contractor and/or any Subcontractor, regardless of tier, and shall be limited to the following costs:

1. Labor. Straight-time wages or salaries, and overtime wages and salaries specifically authorized by City in writing, for employees employed at the site, or at fabrication sites off the site, in the direct performance of the Extra Work or that would have been incurred in the direct performance of the deleted work, based on the actual cost for wages prevailing locally for each craft or type of workers at the time the Extra Work is done or the deleted work is ordered eliminated. Labor costs for equipment operators and helpers shall be reported only when such costs are not included in the invoice for equipment rental. The use of labor classification which would increase the Allowable Cost for Extra Work will not be permitted unless Contractor establishes the necessity for such additional costs.

R Dependable Const Inc.

Page 52 of 222 ends

.
.

Item 10 Page 54 of 369

2. Benefits. Payroll taxes, insurance, health and welfare, pension, vacation, apprenticeship funds and benefits required by lawful collective bargaining agreements for employees on straight-time wages or salaries, and on overtime wages and salaries specifically authorized by City in writing, for employees employed at the site, or at fabrication sites off the site, in the direct performance of the Extra Work or that would have been incurred in the direct performance of the deleted work.

3. Materials, Consumables. Costs of materials and consumable items which are furnished and incorporated into the Work, as approved by City, or that would have been incorporated into the Work in the case of deleted work shall be at the lowest price available to Contractor but in no event shall such costs exceed competitive wholesale prices obtainable from other Subcontractors, suppliers, manufacturers and distributors in the general vicinity of the site. If City determines, in its discretion, that the cost of materials is excessive, or if Contractor fails to furnish satisfactory evidence of the cost from the actual supplier thereof, then in either case the cost of the materials shall be deemed to be the lowest wholesale price at which similar materials are available in the quantities required at the time they were needed. The City reserves the right to furnish such materials as it deems advisable, and Contractor shall have no claim for costs or profits on materials so furnished. Material invoices must be included with the extra work report to obtain payment.

4. Taxes. Sales taxes on the costs of materials and consumable items described in Paragraph

5.04-C.3 above.

5. Tool, Equipment Rental. Rental charges for necessary machinery and equipment, whether owned or hired, as authorized in writing by City, exclusive of hand tools, used directly in the performance of the Extra Work or that would have been used in the direct performance of the deleted work. Regardless of ownership, such rental charges shall not exceed the hourly rate derived from the most recently published “Rental Rate Blue Book for Construction Equipment” or the “Rental Rate Blue Book for Older Construction Equipment,” as published by K-111, San Jose, California, which is in effect at the time of commencement of the changed work. The Contractor shall attach a copy of the rate schedule to the daily reports required by Paragraph

6.06-B, above. The charges for any machinery and equipment shall cease when the use thereof is no longer necessary for the Extra Work or deleted work. No charge shall be allowed for use of equipment or tools which have a replacement value of $500 or less. The allowable rental rates shall include the cost of fuel, power oil, lubrication, supplies, small tools, necessary attachments, loading, transportation, repairs and maintenance of any kind, depreciation, storage, insurance, and all incidentals. Notwithstanding the provisions of Paragraph 6.06-E below, no mark-up shall be allowed for overhead, profit or bond premiums for use of equipment if the equipment is supplied by an equipment rental firm. If equipment is used intermittently and, when not in use, could be returned to its rental source at less expense to City than holding it at the Site, it shall be returned, unless Contractor elects to keep it at the Site at no expense to City.

Costs incurred while equipment is inoperative due to breakdowns, regular maintenance, or for non-Working Days shall not be allowed. The rental time shall include the time required to move the equipment to the Work from the nearest available source for rental of such equipment and to return it to the source. If such equipment is not moved by its own power, then loading and transportation will be allowed. Neither moving time nor loading and transportation costs will be paid if the equipment is for use on the Project unrelated to the Extra Work. All equipment shall be acceptable to City, in good working condition, and suitable for the purpose for which it is to be used.

R Dependable Const Inc.

Page 53 of 222 ends

.
.

Item 10 Page 55 of 369

6. Royalties. Additional or saved costs of royalties due to the performance of the Extra Work or deleted work.

7. Insurance, Bonds. Additional or saved costs of insurance and bonds, provided, however, that for Extra Work such costs shall not exceed one percent (1%) of Items 1 through 6 above.

D. Costs Not Allowed
Allowable Costs shall not include any of the following:

1. Wages, salaries, fringe benefits and payroll taxes of Contractor’s and all Subcontractor’s noncraft labor (above a Foreman level);

2. Overhead (including home office overhead), administrative or general expenses of any kind including engineering, estimating, scheduling, drafting, detailing, etc., incurred in connection with Extra Work;

3. Vehicles not dedicated solely for the performance of the extra of deleted work;

4. Small tools (replacement value not exceeding $500);

5. Office expenses, including secretarial and administrative staff, materials and supplies;

6. On-site and off-site trailer and storage rental and expenses;

7. Site fencing;

8. Utilities, including gas, electric, sewer, water, telephone, telefax, copier equipment;

9. Computer and data processing personnel, equipment and software;

10. Federal, state of local business income and franchise taxes;

11. Losses of efficiency or productivity; and

12. Costs and expenses of any kind or item not specifically and expressly included in Paragraph

6.06-C.

E. Allowable Mark-Up

1. Extra Work by contractor (Markup): The following percentages shall be added to the Contractor’s costs and shall constitute the markup for all overhead and profits:

Labor 33%
Materials 15%
Equipment Rental 15%
Other Items and Expenditures 15%

2. Extra Work by Subcontractor (Markup): When all or any part of the extra work is performed by a Subcontractor, the markup provided for the Contractor in 6.06.E.1 shall apply to the Subcontractor’s actual costs. A markup of 5% on the subcontracted portion of each extra work may be added for the Contractor.

R Dependable Const Inc.

Page 54 of 222 ends

.
.

Item 10 Page 56 of 369
F. Net Allowable Costs
If anyone scope change involves both Extra Work and deleted work in the same portion of the Work and the additive allowable costs exceed the deductive allowable costs, the Allowable Markups on the Extra Work will be only the difference between the two amounts.

6.07 CITY ORIGINATED REQUEST FOR ITEMIZED CHANGE ORDER PROPOSAL REQUEST City may issue a Construction Change Directive or other written request to Contractor describing a proposed change to the Work and requesting the Contractor submit an itemized change order proposal in a format acceptable to City within ten (10) calendar days after City issues the request. The Contractor's change order proposal shall include an analysis of impacts to cost and time, if any, to perform additional work, change Work or delete Work, as applicable, including the effects and impacts, if any, on unchanged Work, estimates of costs (broken down by the cost categories listed in this Paragraph), and Contractor's proposed methods to minimize costs, delay, and disruption to the performance of the Work. If Contractor fails to submit a written change order proposal within such period of time, it shall be presumed that the change described in the City's original proposal request will not result in an increase to the Contract Sum or Contract Time and the change shall be performed by Contractor without additional compensation to Contractor. City's request for itemized change order proposal request does not authorize the Contractor to commence performance of the change.

If City desires that the proposed change be performed, the Work shall be authorized according to the Change Order or Construction Change Directive procedures set forth herein.

6.08 CONTRACTOR ORIGINATED CHANGE ORDER REQUEST (COR)
If the Contractor believes that instructions issued by the City after the effective date of the Contract will result in changes to the Contract Sum or Contract Time or if the Contractor otherwise becomes aware of the need for or desirability of a change in the Work, Contractor may submit a written Change Order Request ("COR") to the City in writing, in a format acceptable to City and in accordance with the notice provisions and other requirements of Article 7 below for Claims. The COR must specify the reasons for the proposed change, cost impacts and relevant circumstances and impacts on the Construction Schedule. The document shall be complete in its description of the Work, its material and labor quantities and detail, and must support and justify the costs and credits claimed by the Contractor. A Critical Path Method schedule Fragnet is required to support and justify any additional time of performance requested by the Contractor. The City will not review any COR which is incomplete. The Contractor may request additional compensation and/or time through a COR but not for instances that occurred more than ten (10) calendar days prior to the notice date. Contractor's failure to initiate a COR within this ten-day period or to provide detailed back-up documentation to substantiate the COR within thirty (30) calendar days of the initial written notice shall be deemed a waiver of the right to adjustment of the Contract Sum or the Contract Time for the alleged change. Any COR that is approved by the City shall be incorporated in a Change Order or Construction Change Directive. If the COR is denied but the Contractor believes that it does have merit, the Contractor shall proceed with the disputed Work and may submit a Claim in accordance with the procedures set forth herein.

6.09 ISSUANCE OF WORK DIRECTIVE (UNILATERAL).

In the event of a dispute as to whether or not Extra Work is required, City shall have the right to unilaterally issue a Work Directive; Contractor shall continue performance of disputed Work pending resolution and shall maintain and submit to City all accounting and cost data necessary to substantiate Contractor’s cost of such disputed Work.
[END OF ARTICLE]
R Dependable Const Inc.

Page 55 of 222 ends

.
.

Item 10 Page 57 of 369
ARTICLE 7 - CONTRACT PAYMENTS AND CLAIMS

7.01 GENERAL
A. Payment will be made at the price for each item listed on the bidding form or as Extra Work as provided in the General Conditions.

B. Initial progress payment will not be made prior to approval by the Director of the Schedule of Values, the Construction Progress Schedule, and the Schedule of Submittals.

C. No subsequent progress payment will be made prior to receipt by the Director of the monthly revision of the Construction Progress Schedule.

7.02 SCHEDULE OF VALUES FOR PAYMENTS
A. Submission
Upon City’s request, the three (3) lowest bidders shall complete and submit a Preliminary Schedule of Values, within seven (7) calendar days.

In addition, Contractor shall complete and furnish within seven (7) calendar days after receiving the Notice of Award of the Construction Contract a Final Schedule of Values giving a complete breakdown of the Contract Sum for each component of the Work.

B. Content
The Schedule of Values shall be in sufficient detail as the Director may, in its discretion, deem necessary to evaluate progress at any point in the performance of the Work. Unless otherwise specified in the Contract Documents, the Schedule of Values shall include, without limitation, a breakdown of the general categories of Subcontractor work, direct overhead, profit and contingency, and a further breakdown of the general categories of Subcontractor work into separate trade line items of costs for Subcontractor services, labor and material, which is based on actual Subcontractor contract, subcontract, purchase order or vendor prices. If requested by Director, Contractor shall revise the Schedule of Values to allocate sums for Contractor overhead, profit and/or contingency among the individual line items for trade portions of the Work. No amounts shall be reflected in the Schedule of Values or Application for Payment for Extra Work or Deleted Work for which a Change Order has not been executed by Contractor and City or for which a Construction Change Directive has not been issued by City. Amounts that have been mutually agreed to by Change Order or unilaterally determined by City pursuant to a Construction Change Directive shall be segregated from the cost of the base Contract Work and separately listed by line item in the Schedule of Values. The Schedule of Values must be prepared in sufficient detail and supported by sufficient data to substantiate its accuracy as the Director may require.

C. Applications for Payment
The Schedule of Values, when approved by the Director, shall be used as a basis for Contractor's Applications for Payment and may be considered as fixing a basis for adjustments to the Contract Sum.

R Dependable Const Inc.

Page 56 of 222 ends

.
.

Item 10 Page 58 of 369
D. Revisions
If, at any time, it is determined that the Schedule of Values does not allocate the Contract Sum in a manner that reasonably and fairly reflects the actual costs anticipated to be progressively incurred by Contractor, it shall be revised and resubmitted for the Director’s approval.

7.03 APPLICATIONS FOR PAYMENT
A. Marked Schedule of Values
Five (5) Days prior to the date set forth in Paragraph 7.03-B below for the monthly progress payment meeting, Contractor shall submit to Director a copy of the proposed Schedule of Values, marked to show the percentage of completion certified by Contractor for each line item in the Schedule of Values, including any stored materials approved for payment by City pursuant to Paragraph 7.03-D, below and any withholdings from Contractor proposed by Director.

B. Monthly Review
For the purpose of expediting the progress payment procedure, Contractor shall meet with the Director on or before the twentieth (20th) day of each month to review the Contractor's marked Schedule of Values prepared in accordance with Paragraph 7.03-A, above. The Director shall revise as appropriate and sign the marked Schedule of Values to verify such review. If any item in the marked Schedule of Values submitted for payment is disputed during this review, Contractor agrees to use its best efforts to resolve the disputed items with the Director before submitting its Application for Payment. If the Director and Contractor cannot agree, then the percentage completion shall be established at such percentage as the Director, in good faith, determines is appropriate to the actual progress of the Work. No inaccuracy or error in the Director’s good faith estimate shall operate to release Contractor or Surety from any responsibility or liability arising from or related to performance of the Work. The Director shall have the right subsequently to correct any error and dispute any item submitted in Contractor's Application for Payment, regardless of whether an item was identified as disputed in the review process provided for herein.

C. Certification
Each Application for Payment shall be signed and certified by Contractor under penalty of perjury to City that:

1. The data comprising the Application for Payment is accurate and the Work has progressed to the point indicated;

2. To the best of Contractor's knowledge, information and belief, the Work is in accordance with the Contract Documents;

3. Contractor is entitled to payment in the amount certified; and

4. All sums previously applied for by Contractor on account of Work performed by Subcontractors and that have been paid by City have been paid to the Subcontractors performing such Work, without any retention, withholding or back charge by Contractor.

R Dependable Const Inc.

Page 57 of 222 ends

.
.

Item 10 Page 59 of 369
D. Stored Materials
Payments may be made by City, at its discretion, on account of materials or equipment not incorporated into the Work but delivered on the ground at the Site and suitably stored by Contractor or stored off-Site under the control of City. Such payments shall only be considered upon submission by Contractor of satisfactory evidence that it has acquired title to same, that the material or equipment will be utilized in the Work and that the material is satisfactorily stored, protected and insured, and that such other procedures are in place satisfactory to City to protect City's interests. To be considered for payment, materials or equipment stored off-Site shall, in addition to the above requirements and unless otherwise specifically approved by City in writing, be stored in a bonded warehouse, fully insured, and available to City for inspection. City shall have sole discretion to determine the amount of material and equipment that may be stored on the Site at any given time.

7.04 PROGRESS PAYMENTS
A. Conditions to Progress Payments
Contractor shall submit its Application for Payment to the Director, using such forms as required by City, once a month on or before the first (1st) Day of the month following the month in which the Work that is the subject of such Application for Payment was performed. Without limitation to any other provisions of the Contract Documents, the following shall be conditions precedent to a proper submission and to the Director approval of each Application for Payment:

1. Submission of a Schedule of Values that reflects the percentages of completion either agreed to or determined by Director in accordance with Paragraph 7.03-B, above;

2. Submission of the Contractor's certification required by Paragraph 7.03-C, above;

3. Submission of conditional releases of stop notice, if any, and bond rights upon progress payment, complying with California Civil Code Section 8132, for all Work performed during the time period covered by the current Application for Payment, signed by Contractor, its Subcontractors of every tier, and all material suppliers to each, and (2) forms of unconditional release of stop notice and bond rights upon progress payment, complying with California Civil Code Section 8134 for all Work performed during the time period covered by the previous Application for Payment, signed by Contractor, its Subcontractors of every tier and all material suppliers to each;

4. Compliance by Contractor with its obligation for maintenance of As-Builts as required by the Contract Documents;

5. Compliance by Contractor with its obligation for submission of monthly and daily reports as required by the Contract Documents;

6. Compliance by Contractor with its obligations for submission of scheduling information and updating of the Construction Schedule as required by Article 4, above and other provisions of the Contract Documents pertaining to preparation or updating of schedule information;

7. Submission of certified payroll records as required by the Contract Documents;

8. Submission of certifications by Contractor and each Subcontractor as required by applicable collective bargaining agreements certifying that all employee benefit contributions due and R Dependable Const Inc.

Page 58 of 222 ends

.
.

Item 10 Page 60 of 369
owed pursuant to any applicable collective bargaining agreement have been paid in full; and

9. Compliance by Contractor with all of its other obligations for submission of documentation or performance of conditions which, by the terms of the Contract Documents, constitute conditions to Contractor's right to receive payment for Work performed.

B. Payments by City
Pursuant to California Public Contract Code Section 20104.50, City shall make progress payment of undisputed sums due within thirty (30) Days after receipt by Director of an undisputed and properly submitted Application for Payment, calculated on the basis of ninety-five percent (95%) of value determined pursuant to Paragraph 7.03-B above of the following:

1. The portion of the Work permanently installed and in place;

2. Plus, the value of materials delivered on the ground or in storage as approved by City pursuant to Paragraph 7.03-D, above,

3. Less, the aggregate of previous payments, and

4. Less, any other withholdings authorized by the Contract Documents.

C. Rejection by City
Any Application for Payment determined not to be undisputed, proper and suitable for payment shall be returned to Contractor as soon as practicable, but not later than seven (7) Days, after receipt by City accompanied by an written explanation of the reasons why the payment request was rejected.

Failure by City or Director to either timely reject an Application for Payment or specify any grounds for rejection shall not constitute a waiver of any rights by City. Applications for Payment that are rejected shall be corrected and resubmitted within seven (7) Days after receipt by Contractor.

D. Interest
If City fails to make a progress payment to Contractor as required by Paragraph 7.04-B, above, City shall pay interest to Contractor equivalent to the legal rate set forth in subdivision (a) of California Code of Civil Procedure Section 685.010. The number of Days available to City to make payment pursuant to Paragraph 7.04-B, above without incurring interest pursuant to this Paragraph shall be reduced by the number of Days by which City exceeds the seven (7) Day return requirement applicable to City as set forth in Paragraph 7.04-C, above.

7.05 FINAL PAYMENT
A. Retention
ln addition to withholdings permitted by Paragraph 7.09 below, a sum equal to five percent (5%) of all sums otherwise due to Contractor as progress payments shall be withheld by city pursuant to Paragraph 7.04-B from each progress payment (“Retention”) and retained until such time as it is due as described herein. A higher Retention amount may be approved by the City Council where project is deemed “substantially complex” by City Council.

B. Conditions to Final Payment
R Dependable Const Inc.

Page 59 of 222 ends

.
.

Item 10 Page 61 of 369
Contractor shall submit its Application for Final Payment, using such forms as required by Director, prior to requesting a final inspection of the Work in accordance with Paragraph 3.06 above. Such Application for Final Payment shall be accompanied by all the following:

1. An affidavit that payrolls, bills for materials and equipment, and other indebtedness connected with the Project for which City or City's property or funds might be liable have been paid or otherwise satisfied;

2. Contractor’s certification as required by Paragraph 7.03-C, above;

3. Consent of surety, if any, to Final Payment;

4. A certificate evidencing that the insurance required by the Contract Documents is in force;

5. Conditional Waiver and Release Upon Final Payment in the form required by California Civil Code Section 8136 executed by Contractor, all Subcontractors of every tier and by all material suppliers of each, covering the final payment period;

6. Unconditional Waiver and Release Upon Progress Payment in the form required by California Civil Code Section 8136 executed by Contractor, all Subcontractors of every tier and by all material suppliers of each, covering the previous payment period;

7. All Record Documents (including, without limitation, complete and accurate As-Built drawings which shall be kept up to date during the performance of the Work);

8. Documentation that Contractor has inspected, tested, and adjusted performance if every system or facility of the Work to ensure that overall performance is in compliance with the terms of the Contract Documents;

9. Four (4) copies of all warranties from vendors and Subcontractors, operation and maintenance manuals, instructions and related agreements, and equipment certifications and similar documents;

10. Certifications by Contractor and each Subcontractor as required by applicable collective bargaining agreements that all employee benefit contributions due and owing pursuant to any applicable collective bargaining agreement have been paid in full;

11. Releases of rights and claims relating to patents and trademarks, as required by the Contract Documents; and

12. Any other documents or information required by the Contract Documents as a condition of Final Payment or Final Completion.

C. Final Payment
Pursuant to the Public Contract Code Section 7107, within sixty (60) Days after City issues the Notice R Dependable Const Inc.

Page 60 of 222 ends

.
.

Item 10 Page 62 of 369
of Completion to Contractor, the Final Payment, including Retention, shall be released to Contractor, subject to the City’s right to withhold 150% of any disputed amounts.

D. Disputed Amounts
Pursuant to California Public Contract Code 7107, City may deduct and withhold from the Final Payment due under Paragraph 7.05-C, above, an amount up to 150% of any disputed amounts, including, without limitation, amounts to protect City against any loss caused or threatened as a result of Contractor's failing to fully perform all of those obligations that are required to be fulfilled by Contractor as a condition to Final Completion and Final Payment. Alternatively, City may elect, in its sole discretion, to accept the Work without correction or completion and adjust the Contract Sum pursuant to the Contract Documents.

E. Acceptance of Final Payment
Acceptance of Final Payment by Contractor shall constitute a waiver of all rights by Contractor against City for recovery of any loss, excepting only those Claims that have been submitted by Contractor in the manner required by the Contract Documents prior to or at the time of the Final Payment.

7.06 MISCELLANEOUS
A. Joint Payment
City shall have the right, if deemed necessary in its sole discretion, to issue joint checks made payable to Contractor and any Subcontractor(s) of any Tier. The joint check payees shall be solely responsible for the allocation and disbursement of funds included as part of any such joint payment.

Endorsement on such check by a payee shall be conclusively presumed to constitute receipt of payment by such payee. In no event shall any joint check payment be construed to create any contract between City and a Subcontractor of any Tier, any obligation from City to such Subcontractor or any third party rights against City or Director.

B. Withholding/Duty to Proceed
The payment, withholding or retention of all or any portion of any payment claimed to be due and owing to Contractor shall not operate in any way to relieve Contractor from its obligations under the Contract Documents. Contractor shall continue diligently to prosecute the Work without reference to the payment, withholding or retention of any payment. The partial payment, withholding or retention by City in good faith of any disputed portion of a payment, whether ultimately determined to be correctly or incorrectly asserted, shall not constitute a breach by City of the Construction Contract and shall not be grounds for an adjustment of the Contract Sum or Contract Time.

C. No Acceptance
No payment by City or partial or entire use of the Work by City shall be construed as approval or acceptance of the Work, or any portion thereof.

D. Contractor Payment Warranty
Submission of an Application for Payment shall constitute a representation and warranty by Contractor that:

R Dependable Const Inc.

Page 61 of 222 ends

.
.

Item 10 Page 63 of 369

1. Title to Work covered by an Application for Payment will pass to City either by incorporation into the construction or upon receipt of payment by Contractor, whichever occurs first; and

2. Work covered by previous Applications for Payment are free and clear of liens, stop notices, claims, security interests or encumbrances imposed by the Contractor or any other person.

E. Corrections
No inaccuracy or error in any Application for Payment provided by Contractor shall operate to release Contractor from the error, or from losses arising from the Work, or from any obligation imposed by the Contract Documents. City retains the right to subsequently correct any error made in any previously approved Application for Payment, or progress payment issued, by adjustments to subsequent payments.

7.07 PAYMENTS BY CONTRACTOR
Contractor shall not include in its Applications for Payment sums on account of any Subcontractor's portion of the Work that it does not intend to pay to such Subcontractor. Upon receipt of payment from City, Contractor shall pay the Subcontractor performing Work on the Project, out of the amount paid to Contractor on account of such Subcontractor's portion of the Work, the amount to which said Subcontractor is entitled in accordance with the terms of its contract with Contractor and applicable laws, including, without limitation, California Public Contract Code Section 7107. Contractor shall remain responsible notwithstanding a withholding by City pursuant to the terms of these Contract Documents, to promptly satisfy from its own funds sums due to all Subcontractors who have performed Work that is included in Contractor's Application for Payment. Contractor shall, by appropriate agreement, require each Subcontractor to make payments to its subcontractors and material suppliers in similar manner. City shall have no obligation to pay or be responsible in any way for payment to a Subcontractor of any tier or material supplier.

7.08 PAYMENTS WITHHELD
A. Withholding by City
In addition to any other amounts which City may have the right to retain under the Contract Documents, City may withhold a sufficient amount of any payment otherwise due to Contractor as City, in its sole discretion, may deem necessary to cover actual or threatened loss due to any of the following:

1. Third Party Claims. Third-party claims or stop notices filed or reasonable evidence indicating probable filing of such claims or stop notices. City shall promptly inform Contractor of any third party claims related to this Contract;

2. Defective Work. Defective Work not remedied;

3. Nonpayment. Failure of Contractor to make proper payments to its Subcontractors for services, labor, materials or equipment;

4. Inability to Complete. Reasonable doubt that the Work can be completed for the then unpaid balance of the Contract Sum or within the Contract Time; R Dependable Const Inc.

Page 62 of 222 ends

.
.

Item 10 Page 64 of 369

5. Violation of Applicable Laws. Failure of Contractor or its Subcontractors to comply with applicable laws or lawful orders of governmental authorities;

6. Penalty. Any claim or penalty asserted against City by virtue of Contractor’s failure to comply with applicable laws or lawful orders of governmental authorities (including, without limitation labor laws);

7. Failure to Meet Contract Time. Any damages which may accrue as a result of Contractor failing to meet the Construction Schedule or failing to perform within the Contract Time;

8. Setoff. Any reason specified elsewhere in the Contract Documents as grounds for a withholding offset or set off or that would legally entitle City to a set-off or recoupment;

9. Consultant Services. Additional professional, consultant or inspection services required due to Contractor’s failure to comply with the Contract Documents;

10. Liquidated Damages. Liquidated damages assessed against Contractor;

11. Materials. Materials ordered by City pursuant to the Contract Documents;

12. Damages. Loss caused by Contractor or Subcontractor to City, Separate Contractors or any other person or entity under contract to City;

13. Clean Up. Clean up performed by City and chargeable to Contractor pursuant to the Contract Documents;

14. Employee Benefits. Failure of Contractor to pay contributions due and owing to employee benefits funds pursuant to any applicable collective bargaining agreement or trust agreement;

15. Required Documents. Failure of Contractor to submit on a timely basis, proper and sufficient documentation required by the Contract Documents, including, without limitation, Construction Schedule updates, ‘look ahead’ schedules, Submittals, Schedules of Values, information on Subcontractors, Change Orders, certifications and other required reports or documentation; and

16. Other Breach. A breach of any obligation or provision of the Contract Documents.

B. Release of Withholding
If and when City determines, in its sole discretion, that the above grounds for withholding have been removed and that all losses incurred or threatened have been paid, credited or otherwise satisfied, then payment shall be made for amounts withheld because of them.

C. Application of Withholding
City may apply sums withheld pursuant to Paragraph 7.08-A above, in payment of any loss or threatened loss as City determines, in its sole discretion, to be appropriate. Such payments may be made without a prior judicial determination of City’s actual rights with respect to such loss. Contractor agrees and hereby designates City as its agent for such purposes, and agrees that such payments shall be considered as payments made under Construction Contract by City to Contractor. City shall not be liable to Contractor for such payments made in good faith. City shall submit to Contractor an accounting of such funds disbursed on behalf of Contractor. As an alternative to such payment, City R Dependable Const Inc.

Page 63 of 222 ends

.
.

Item 10 Page 65 of 369
may, in its sole discretion, elect to exercise its right to adjust the Contract Sum as provided in the Contract Documents.

D. Continuous Performance
Provided City pays the undisputed portion, if any, of funds withheld in good faith, Contractor shall maintain continuous and uninterrupted performance of the Work during the pendency of any disputes or disagreements with City.

7.09 SUBSTITUTION OF SECURITIES
A. Public Contract Code
Pursuant to the requirements of California Public Contract Code Section 22300, upon Contractor’s request, City will make payment to Contractor of any funds withheld from payments to ensure performance under the Contract Documents if Contractor deposits with City, or in escrow with a California or federally chartered bank in California acceptable to City (“Escrow Agent”), securities eligible for the investment of State Funds under Government Code Section 16430, or bank or savings and loan certificates of deposit, interest-bearing demand deposit accounts, standby letters of credit, or any other security mutually agreed to by the Contractor and the City, upon the following conditions:

1. Contractor shall be the beneficial owner or any securities substituted for monies withheld for the purpose of receiving any interest thereon.

2. All expenses relating to the substitution of securities under Public Contract Code Section 22300 and under this Paragraph 7.04, including, but not limited to City’s overhead and administrative expenses, and expenses of Escrow Agent shall be the responsibility of Contractor.

3. Securities or certificates of deposit substituted for monies withheld shall be of a value of at least equivalent to the amounts of retention to be paid to Contractor pursuant to the Contract Documents.

4. If Contractor chooses to deposit securities in lieu of monies withheld with an Escrow Agent, Contractor, City and Escrow Agent shall, as a prerequisite to such deposit, enter into an escrow agreement, using the City’s form, “Escrow Agreement for Deposit of Securities in Lieu of Retention.”

5. Contactor shall obtain the written consent of Surety to such agreement.

6. Securities, if any, shall be returned to Contractor only upon satisfactory Final Completion of the Work.

B. Substitute Security
To minimize the expense caused by such substitution of securities, Contractor shall, prior to or at the time Contractor requests to substitute security, deposit sufficient security to cover the entire amount to be withheld. Should the current market value of such substituted security fall below the amount for which it was substituted, or any other amounts which the City withholds pursuant to the Contract Documents, Contractor shall immediately and at Contractor’s expense and at no cost to City deposit additional security qualifying under Public Contract Code Section 22300 until the current market value of the total security deposited is no less than the amount subject to withholding under the Contract R Dependable Const Inc.

Page 64 of 222 ends

.
.

Item 10 Page 66 of 369
Documents. Securities shall be valued as often as conditions of the securities market warrant, but in no case less frequently than once per month.

C. Deposit of Retentions
Alternatively, subject to the conditions set forth in Paragraph 7.04-A above, upon request of Contractor, City shall make payment of retentions directly to Escrow Agent at the expense of Contractor, provided that Contractor, City and Escrow Agent shall, as a prerequisite such payment, enter into an escrow agreement in the same form as prescribed in Part 4 of Paragraph A, above. At the expense of Contractor and at no cost to City, Contractor may direct the investment of the payments into securities and interest bearing accounts, and Contractor shall receive the interest earned on the investments. Escrow Agent shall hold such direct payments by City under the same terms provided herein for securities deposited by Contractor. Upon satisfactory Final Completion of the Work, Contractor shall receive from Escrow Agent all securities, interest and payments received by Escrow Agent from City, less escrow fees and charges of the Escrow Account, according to the terms of Public Contract Code Section 22300 and the Contract Documents.

D. Time for Election of Substitution of Securities
Notwithstanding the provision of 7.04 A, B, and C above and California Public Contract Code Section 22300, the failure of Contractor to request the Substitution of eligible securities for monies to be withheld by City within ten (10) days of the award of Contract to Contractor shall be deemed to be a waiver of all such rights.

7.10 CLAIMS
A. Arising of Claim.

1. Scope Change. When Contractor has a claim for an increase in the Contract Sum or Contract Time due to a scope change which has not yet become final, a “claim” will be deemed to arise once the Director has issued a decision denying, in whole or in part, the Contractor’s Change Order Request.

2. Other Claims. In the case of a Claim by Contractor that does not involve an adjustment to the Contract Sum or Contract Time due to a scope change and which has not become final, the Claim may be asserted if, and only if, Contractor gives written notice to City of intent to file the Claim within three (3) days of the date of discovery relative to such circumstances (even if Contractor has not yet been damaged or delayed). Such written notice of intent to file a Claim shall be valid if, and only if, it identifies the event or condition giving rise to the Claim, states its probable effect, if any with respect to Contractor's entitlement to an adjustment of the Contract Sum or Contract Time and complies with the requirements of Paragraph 7.11-B, below. For purposes of this Paragraph 7.11, a Claim for which such written notice is required and has been given by Contractor shall be deemed to arise on the date that such written notice is received by City.

B. Content of Claim
A Claim by Contractor must include all of the following:

1. A statement that it is a Claim and a request for a decision on the Claim; R Dependable Const Inc.

Page 65 of 222 ends

.
.

Item 10 Page 67 of 369

2. A detailed description of the act, error, omission, unforeseen condition, event or other circumstance giving rise to the Claim.

3. If the Claim involves an adjustment to the Contract Sum or Contract Time due to a change in scope, a statement demonstrating that all requisite notices were provided, including, without limitation, timely written notice and a Change Order Request as required by Article 6 of these General Conditions and timely notice of delay and request for extension of time in accordance with Article 3. If the Claim does not involve an adjustment to the Contract Sum or Contract Time due to a change in scope, a statement demonstrating that a notice of intent to file the Claim was timely submitted as required by Paragraph 7.10-A.2, above;

4. A detailed justification for any remedy or relief sought by the Claim including without limitation, a detailed cost breakdown in the form required for submittal of Change Order Requests and actual job cost records demonstrating that the costs have been incurred;

5. If the Claim involves a request for adjustment of the Contract Time, written documentation demonstrating that Contractor has complied with the requirements of the Contract Documents and written substantiation (including, without limitation, a Time Impact Analysis) demonstrating that Contractor is entitled to an extension of time under the Contract Documents; and

6. A written certification signed by a managing officer of Contractor's organization, who has the authority to sign contracts and purchase orders on behalf of Contractor and who has personally investigated and confirmed the truth and accuracy of the matters set forth in such certification, in the 'following form:
"I hereby certify under penalty of perjury that I am a managing officer of (Contractor's name) and that I have reviewed the Claim presented herewith on Contractor's behalf and/or on behalf of (Subcontractor's name) and that, to the best of my knowledge after conducting a diligent inquiry into the facts of the Claim, the following statements are true and correct:

The facts alleged in or that form the basis for the Claim are, to the best of my knowledge following diligent inquiry, true and accurate; and,
(a) I do not know of any facts or circumstances, not alleged in the Claim, that by reason of their not being alleged render any fact or statement alleged in the Claim materially misleading; and,
(b) I have, with respect to any request for money or damages alleged in or that forms the basis for the Claim, reviewed the job cost records (including those maintained by Contractor and by any Subcontractor, of any tier, that is asserting all or any portion of the Claim) and confirmed with reasonable certainty that the losses or damages suffered by Contractor and/or such Subcontractor were in fact suffered in the amounts and for the reasons alleged in the Claim; and, (c) I have, with respect to any request for extension of time or claim of delay, disruption, hindrance or interference alleged in or that forms the basis for the Claim, reviewed the job schedules (including those maintained by Contractor and the Subcontractor, of any tier, that is asserting all or any portion of the Claim) and confirmed on an event-by-event basis that the delays or disruption suffered by Contractor and/or such Subcontractor were in fact experienced for the durations, R Dependable Const Inc.

Page 66 of 222 ends

.
.

Item 10 Page 68 of 369
in the manner, and with the consequent effects on the time and/or sequence of R Dependable Const Inc.

Page 67 of 222 ends

.
.

Item 10 Page 69 of 369
performance of the Work, as alleged in the Claim; and,
(d) I have not received payment from City for, nor has Contractor previously released City from, any portion of the Claim.”
Signature: Date:

Name:

Title:

Company
C. Noncompliance
Failure to submit any of the information, documentation or certifications required by Paragraph 7.10- B, above, shall result in the Claim being returned to Contractor without any decision.

D. Submission of Claims

1. Director. Claims shall be first submitted to the City for decision by the Director.

2. Continuous Work. Notwithstanding the making of any Claim or the existence of any dispute regarding any Claim, unless otherwise directed by City, Contractor shall not delay, slow or stop performance of the Work, but shall diligently proceed with performance in accordance with the Contract Documents and City will continue, to make undisputed payments as by the Contract Documents.

3. Time for Filing. All Claims and supporting documentation and certifications must be filed within thirty (30) days after the Claim arises. No Claims shall be filed after Final Payment.

4. Conditions Precedent. No Claim may be asserted unless Contractor has strictly complied with the requirements of this Paragraph 7.10-D, which shall be considered conditions precedent to Contractor’s right to assert the Claim and to initiate the Dispute Resolution Process with respect to such Claim.

E. Response to Claims, Meet and Confer

1. Claims less than $50,000. Claims less than $50,000 shall be responded to by City in writing within forty-five (45) days of receipt of the Claim, unless City requests additional information or documentation of the Claim within thirty (30) days of receipt of the Claim, in which case City shall respond to the Claim within fifteen (15) days after receipt of the further information or documentation or within a period of time no greater than that taken by Contractor in producing the additional information or documentation, whichever is greater.

2. Claims $50,000 or more. Claims $50,000 or more shall be responded to by City in writing within (60) days of receipt of the Claim, unless City requests additional information or documentation of the Claim within thirty (30) days of receipt of the Claim, in which case City shall respond to the Claim within thirty (30) days after receipt of the further information or documentation or within a period of time no greater than that taken by Contractor in producing the additional information or documentation, whichever is greater.

R Dependable Const Inc.

Page 68 of 222 ends

.
.

Item 10 Page 70 of 369

3. Meet and Confer. If Contractor disputes City's response, or if City fails to respond within the prescribed time set forth in Paragraph 7.10-E.1 and 7.10-E.2, above, Contractor may so notify City, in writing, within fifteen (15) days of City's response, or within fifteen (15) days of City’s response due date in the event of a failure to respond, and demand an informal conference to meet and confer for settlement of the issues in dispute. Upon such demand, City shall schedule a meet and confer conference within thirty (30) days of such demand, for discussion of settlement of the dispute.

F. Finality of Decision
If Contractor disputes the Director’s decision under this Article, it shall commence the Dispute Resolution Process as set forth in Article 15 of these General Conditions by filing a Statement of Dispute within seven (7) days after receipt of the Director’s response.

G. Continuing Contract Performance/Duty to Proceed with Disputed Work Contractor shall not delay or postpone any Work pending resolution of any claims, disputes or disagreements. Pending final resolution of a claim, the Contactor shall proceed diligently with performance of the Contract and the City shall continue to make payments for undisputed Work in accordance with the Contract Documents. In the event of disputed Work, City shall have the right to unilaterally issue a Work Directive and Contractor shall continue performance pending resolution of the dispute and shall maintain the accounting and cost data to substantiate the cost of such disputed work. [END OF ARTICLE]
R Dependable Const Inc.

Page 69 of 222 ends

.
.

Item 10 Page 71 of 369
ARTICLE 8 - MATERIALS AND EQUIPMENT

8.01 GENERAL
A. The Contractor shall furnish all materials and equipment needed to complete the Work and installations required under the terms of this Contract, except those materials and equipment specified to be furnished by the City.

B. The Contractor shall submit satisfactory evidence that the materials and equipment to be furnished and used in the work are in compliance with the Specifications. Materials and equipment incorporated in the Work and not specifically covered in the Specifications shall be the best of their kind. Unless otherwise specified, all materials and equipment incorporated in the Work under the Contract shall be new.

8.02 QUALITY AND WORKMANSHIP
All material and equipment furnished by the Contractor shall be new, high grade, and free from defects and imperfections, unless otherwise hereinafter specified. Workmanship shall be in accordance with the best standard practices. All materials and equipment must be of the specified quality and equal to approved samples, if samples have been required. All Work shall be done and completed in a thorough, workmanlike manner, notwithstanding any omission from the Specifications or Drawings, and it shall be the duty of the Contractor to call attention to apparent errors or omissions and request instructions before proceeding with the Work. The Director may, by appropriate instructions, correct errors and supply omissions, which instructions shall be binding upon the Contractor as though contained in the original Specifications or Drawings. All Work performed under the Specifications will be inspected by the Director as provided in Paragraph 8.04. All materials and equipment furnished and all Work done must be satisfactory to the Director. Work, material, or equipment not in accordance with the Specifications, in the opinion of the Director shall be made to conform thereto. Unsatisfactory materials and equipment will be rejected, and if so ordered by the Director, shall, at the Contractor's expense, be immediately removed from the vicinity of the Work.

8.03 TRADE NAMES AND "OR APPROVED EQUAL" PROVISION
Whenever in the Specifications or Drawings the name or brand of a manufactured article is used it is intended to indicate a measure of quality and utility or a standard. Except in those instances where the product is designated to match others in use on a particular improvement either completed or in the course of completion, the Contractor may substitute any other brand or manufacture of equal appearance, quality, and utility on approval of the Director, provided the use of such brand or manufacture involves no additional cost to the City.

8.04 APPROVAL OF MATERIALS
A. The Contractor shall furnish without additional cost to the City such quantities of construction materials as may be required by the Director for test purposes. He/she shall place at the Director's disposal all available facilities for and cooperate with him in the sampling and testing of all materials and workmanship. The Contractor shall prepay all shipping charges on samples. No samples are to be submitted with the bids unless otherwise specified.

B. Each sample submitted shall be labeled. A letter, in duplicate, submitting each shipment of samples shall be mailed to the Director by the Contractor. Both the label on the sample and the letter of transmittal shall indicate the material represented, its place of origin, the names of the producer and the Contractor, the Specifications number and title, and a reference to the applicable Drawings and Specifications paragraphs.

R Dependable Const Inc.

Page 70 of 222 ends

.
.

Item 10 Page 72 of 369
C. Materials or equipment of which samples are required shall not be used on the Work until approval has been given by the Director in writing. Approval of any sample shall be only for the characteristics of the uses named in such approval and no other. No approval of a sample shall be taken in itself to change or modify any Contract requirement.

D. Failure of any material to pass the specified tests, including life cycle maintenance data may be sufficient cause for refusal to consider under this Contract, any further sample of the same brand or make of that material.

8.05 ORDERING MATERIALS AND EQUIPMENT
One copy of each of the Contractor's purchase orders for materials and equipment forming a portion of the Work must be furnished to the Director, if requested. Each such purchase order shall contain a statement that the materials and equipment included in the order are subject to inspection by the City. Materials and equipment purchased locally will, at the City’s discretion, be inspected at the point of manufacture or supply, and materials and equipment supplied from points outside the Los Angeles area will be inspected upon arrival at the job, except when other inspection requirements are provided for specific materials in other sections of the Contract Documents.

8.06 AUTHORITY OF THE DIRECTOR
A. On all questions concerning the acceptability of materials or machinery, the classification of materials, the execution of the Work, and conflicting interests of Contractors performing related work, the decision of the Director shall be final and binding.

B. The Director will make periodic observations of materials and completed work to observe their compliance with Drawings, Specifications, and design and planning concepts, but he/she is not responsible for the superintendence of construction processes, site conditions, operations, equipment, personnel, or the maintenance of a safe place to work or any safety in, on, or about the site of work.

8.07 INSPECTION
All materials furnished and work done under this Contract will be subject to rigid inspection. The Contractor shall furnish, without extra charge, the necessary test pieces and samples, including facilities and labor for obtaining them, as requested by the Director. The Director, or his/her authorized agent or agents, at all times shall have access to all parts of the shop and the works where such materials under his/her inspection is being manufactured or the work performed. Work or material that does not conform to the Specifications, although accepted through oversight, may be rejected at any stage of the Work. Whenever the Contractor is permitted or directed to do night work or to vary the period during which work is carried on each day, he/she shall give the Director due notice, so that inspection may be provided. Such work shall be done under regulations to be furnished in writing by the Director.

8.08 INFRINGEMENT OF PATENTS
The Contractor shall hold and save the City, its officers, agents, servants, and employees harmless from and against all and every demand or demands, of any nature or kind, for or on account of the use of any patented invention, process, equipment, article, or appliance employed in the execution of the Work or included in the materials or supplies agreed to be furnished under this Contract, and should the Contractor, his/her agents, servants, or employees, or any of them, be enjoined from furnishing or using any invention, process, equipment, article, materials, supplies or appliance supplied or required to be supplied or used under this Contract, the Contractor shall promptly substitute other inventions, processes, equipment, articles, materials, supplies, or R Dependable Const Inc.

Page 71 of 222 ends

.
.

Item 10 Page 73 of 369
appliances in lieu thereof, of equal efficiency, quality, finish, suitability, and market value, and satisfactory in all respects to the Director. Or in the event that the Director elects, in lieu of such substitution, to have, supplied, and to retain and use, any such invention, process, equipment, article, materials, supplies, or appliances, as may by this Contract be required to be supplied and used, in that event the Contractor shall at his/her expense pay such royalties and secure such valid licenses as may be requisite and necessary to enable the City, its officers, agents, servants, and employees, or any of them, to use such invention, process, equipment, article, materials, supplies, or appliances without being disturbed or in way interfered with by any proceeding in law or equity on account thereof. Should the Contractor neglect or refuse promptly to make the substitution hereinbefore required, or to pay such royalties and secure such licenses as may be necessary and requisite for the purpose aforesaid, then in that event the Director shall have the right to make such substitution, or the City may pay such royalties and secure such licenses and charge the cost thereof against any money due the Contractor from the City, or recover the amount thereof from him/her and his/her surety, notwithstanding final payment under this Contract may have been made.
[END OF ARTICLE]
R Dependable Const Inc.

Page 72 of 222 ends

.
.

Item 10 Page 74 of 369
ARTICLE 9 – SUBMITTALS

9.01 GENERAL
A. The Contractor shall submit samples, drawings, and data for the Director's approval which demonstrate fully that the construction, and the materials and equipment to be furnished will comply with the provisions and intent of the Drawings and Specifications.

B. Specific items to be covered by the submittals shall include, as a minimum, the following:

1. For structures, submit all shop, setting, equipment, miscellaneous iron and reinforcement drawings and schedules necessary.

2. For conduits, submit a detailed layout of the conduit with details of bends and fabricated specials and furnish any other details necessary. Show location of shop and field welds.

3. For equipment which requires electrical service, submit detailed information to show power supply requirements, wiring diagrams, control and protection schematics, shop test data, operation and maintenance procedures, outline drawings, and manufacturer's recommendation of the interface/interlock among the equipment.

4. For mechanical equipment submit all data pertinent to the installation and maintenance of the equipment including shop drawings, manufacturer's recommended installation procedure, detailed installation drawings, test data and curves, maintenance manuals, and other details necessary.

5. Samples

6. Colors

7. Substitutions

8. Manuals

9. As-built drawings

10. Safety plans required by Article 10

9.02 PRODUCT HANDLING
A. Submittals shall be accompanied by a letter of transmittal and shall be in strict accordance with the provisions of this Article.

B. Submit priority of processing when appropriate.

9.03 SCHEDULE OF SUBMITTALS
A. The Contractor shall prepare and submit a schedule of submittals. The schedule of submittals shall be in the form of a submittal log. Refer to Paragraph 9.12.

R Dependable Const Inc.

Page 73 of 222 ends

.
.

Item 10 Page 75 of 369

9.04 SHOP DRAWINGS
A. All shop drawings shall be produced to a scale sufficiently large to show all pertinent features of the item and its method of connection to the Work.

B. All shop drawing prints shall be made in blue or black line on white background. Reproductions of City/Contract Drawings are not acceptable.

C. The overall dimensions of each drawing submitted to the Director shall be equal to one of the City's standard sheet sizes as listed below. The title block shall be located in the lower right hand corner of each drawing and shall be clear of all line Work, dimensions, details, and notes.

Sheet Sizes
Height X Width
11" X 8 1/2"
11" X 17"
24" X 36"
30” X 42”

9.05 COLORS
Unless the precise color and pattern are specified elsewhere, submit accurate color charts and pattern charts to the Director for his/her review and selection whenever a choice of color or pattern is available in a specified product. Label each chart naming the source, the proposed location of use on the project, and the project.

9.06 MANUFACTURERS' LITERATURE
Where contents of submitted literature from manufacturers includes data not pertinent to the submittal, clearly show which portions of the contents are being submitted for review.

9.07 SUBSTITUTIONS
A. The Contract is based on the materials, equipment, and methods described in the Contract Documents.

Any Contractor proposed substitutions are subject to the Director’s approval.

The Director will consider proposals for substitution of materials, equipment, and methods only when such proposals are accompanied by full and complete technical data, and all other information, including life cycle maintenance data, required by the Director to evaluate the proposed substitution.

B. Any requests for substitutions by the Contractor must be made within forty-five (45) calendar days from the Issuance Date on the Notice to Proceed. Otherwise, such requests will not be considered.

C. Trade names and "or approved equal" provision as set forth in Paragraph 8.03.

9.08 MANUALS
A. When manuals are required to be submitted covering items included in this Work, prepare and submit such manuals in approximately 8-1/2" X 11" format in durable plastic binders. In addition, manuals shall be submitted in electronic format. Manuals shall contain at least the following:

1. Identification on, or readable through, the front cover stating general nature of the manual.

R Dependable Const Inc.

Page 74 of 222 ends

.
.

Item 10 Page 76 of 369

2. Neatly typewritten index near the front of the manual, furnishing immediate information as to location in the manual of all emergency data regarding the installation.

3. Complete instructions regarding operation and maintenance of all equipment involved.

4. Complete nomenclature of all replaceable parts, their part numbers, current cost, and name and address of nearest vendor of parts.

5. Copy of all guarantees and warranties issued.

6. Copy of drawings with all data concerning changes made during construction.

B. Where contents of manuals include manufacturers' catalog pages, clearly indicate the precise items included in this installation and delete, or otherwise clearly indicate, all manufacturers' data with which this installation is not concerned.

9.09 AS-BUILT DRAWINGS
A. When required to be submitted covering items included in this Work, the Contractor shall deliver to the City one complete set of final As-Built hard copy drawings together with a set of AutoCAD drawing files in electronic format showing completed building, “as-built” for City records before the Contract will be accepted by the City.

B. The drawings shall be duplicates and at the same size and dimensional scale as the originals. They shall be on a polyester translucent base material with a minimum sheet thickness of .003 inch (.08mm).

C. The legibility and contrast of each drawing submitted to the City shall be such that every line, number, letter, and character is clearly readable in a full size blow back from a 35 mm microfilm negative of the drawing.

9.10 SUBMITTALS QUANTITIES
A. Submit one (1) copy via email to [email protected] of all data and drawings unless specified otherwise.

B. Submit all samples, unless specified otherwise, in the quantity to be returned, plus two, which will be retained by the Director.

9.11 IDENTIFICATION OF SUBMITTALS
Completely identify each submittal and re-submittal by showing at least the following information:

A. Name and address of submitter, plus name and telephone number of the individual who may be contacted for further information.

B. Name of project as it appears in the Contract Documents and Specification No.

C. Drawing number and Specifications section number other than this section to which the submittal applies.

D. Whether this is an original submittal or re-submittal.

R Dependable Const Inc.

Page 75 of 222 ends

.
.

Item 10 Page 77 of 369
E. For samples, indicate the source of the sample.

9.12 SCHEDULE OF SUBMITTALS
A. Submit initial schedule of submittals within five (5) Working Days after the Issuance Date on Notice to Proceed.

B. Submit revised schedule of submittals within five (5) Working Days after date of request from the Director.

C. The Director will review schedule of submittals and will notify Contractor that schedule is acceptable or not acceptable within five (5) Working Days after receipt.

9.13 COORDINATION OF SUBMITTALS
A. Prior to submittal for the Director’s review, use all means necessary to fully coordinate all material, including the following procedures:

1. Determine and verify all field dimensions and conditions, materials, catalog numbers, and similar data.

2. Coordinate as required with all trades and with all public agencies involved.

3. Secure all necessary approvals from public agencies and others and signify by stamp, or other means, that they have been secured.

4. Clearly indicate all deviations from the Specifications.

B. Unless otherwise specifically permitted by the Director, make all submittals in groups containing all associated items; the Director may reject partial submittals as not complying with the provisions of the Specifications.

9.14 TIMING FOR SUBMITTALS
A. Make all submittals far enough in advance of scheduled dates of installation to provide all required time for reviews, for securing necessary approvals, for possible revision and re-submittal, and for placing orders and securing delivery.

B. In scheduling, allow at least 15 Working Days for the Director’s review, plus the transit time to and from the City office.

C. Manuals shall be submitted prior to performing functional tests.

9.15 APPROVAL BY CITY
A. Each submittal, except manuals, schedule of costs for progress payments, and as-built drawings will be returned to the Contractor marked "No Exceptions Taken," “Make Corrections Noted - Do Not Resubmit,” or “Make Corrections Noted - Resubmit.” Manuals, schedule of costs, and as-built drawings will be returned to Contractor via email for re-submittal if incomplete or unacceptable.

B. Submittals marked "Approved as Noted" need not be resubmitted, but the notes shall be followed.

R Dependable Const Inc.

Page 76 of 222 ends

.
.

Item 10 Page 78 of 369
C. If submittal is returned for correction, it will be marked to indicate what is unsatisfactory.

D. Resubmit one (1) original hard copy and one (1) electronic copy (via email to [email protected]) of the revised drawings or data as indicated.

E. Approval of each submittal by the Director will be general only and shall not be construed as:

1. Permitting any departures from the Specifications requirements.

2. Relieving the Contractor of the responsibility for any errors and omissions in details, dimensions, or of other nature that may exist.

3. Approving departures from additional details or instructions previously furnished by the Director.

9.16 CHANGES TO APPROVED SUBMITTALS
A. A re-submittal is required for any proposed change to an approved submittal. Changes which require re-submittal include, but are not necessarily limited to, drawing revisions, changes in materials and equipment, installation procedures and test data. All re-submittals shall include an explanation of the necessity for the change.

B. Minor corrections to an approved submittal may be accomplished by submitting a "Corrected Copy". [END OF ARTICLE]
R Dependable Const Inc.

Page 77 of 222 ends

.
.

Item 10 Page 79 of 369
ARTICLE 10 – SAFETY

10.01 PROTECTION OF PERSONS AND PROPERTY
A. Contractor's Responsibility: Notwithstanding any other provision of the Contract Documents, the Contractor shall be solely and completely responsible for conditions of the job site, including safety of all persons and property, during performance of the Work. This requirement will apply continuously and will not be limited to normal working hours. Safety and sanitary provisions shall conform to all applicable Federal, State, County, and local laws, regulations, ordinances, standards, and codes. Where any of these are in conflict, the more stringent requirement shall be followed.

B. Sanitary Facilities. The Contractor shall furnish and maintain sanitary facilities by the worksites for the entire construction period.

C. Protection of the Public. The Contractor shall take such steps and precautions as his/her operations warrant to protect the public from danger, loss of life, loss of property or interruption of public services.

Unforeseen conditions may arise which will require that immediate provisions be made to protect the public from danger or loss, or damage to life and property, due directly or indirectly to prosecution of work under this contract. Whenever, in the opinion of the Director, a condition exists which the Contractor has not taken sufficient precaution of public safety, protection of utilities and/or protection of adjacent structures or property, the Director will order the Contractor to provide a remedy for the condition. If the Contractor fails to act on the situation within a reasonable time period as determined by the Director, or in the event of an emergency situation, the Director may provide suitable protection by causing such work to be done and material to be furnished as, in the opinion of the Director, may seem reasonable and necessary. The cost and expense of all repairs (including labor and materials) as are deemed necessary, shall be borne by the Contractor. All expenses incurred by the City for emergency repairs will be deducted from the final payment due to the Contractor.

10.02 PROTECTION FROM HAZARDS
A. Trench Excavation
Excavation for any trench four (4) feet or more in depth shall not begin until the Contractor has received approval from the Director of the Contractor's detailed plan for worker protection from the hazards of caving ground during the excavation of such trench. Such plan shall show the details of the design of shoring, bracing, sloping or other provisions to be made for worker protection during such excavation.

No such plan shall allow the use of shoring, sloping or protective system less effective than that required by the Construction Safety Orders of the Division of Occupational Safety and Health, and if such plan varies from the shoring system standards established by the Construction Safety Orders, the plan shall be prepared and signed by an engineer who is registered as a Civil or Structural Director in the State of California.

B. Confined Spaces
Contractor shall comply with all of the provisions of General Industry Safety Orders of the California Code of Regulations. Entry of a confined space shall not be allowed until the Contractor has received approval from the Director of the Contractor’s program for confined space entry. Confined space means a space that (1) Is large enough and so configured that an employee can bodily enter and perform assigned Work; and (2) Has limited or restricted means for entry or exit (for example, tanks, vessels, silos, storage bins, hoppers, vaults, and pits are spaces that may have limited means of entry); and (3) Is not designed for continuous employee occupancy. Failure to submit a confined space entry program R Dependable Const Inc.

Page 78 of 222 ends

.
.

Item 10 Page 80 of 369
may result in actions as provided in Article 5: “Suspension or Termination of Contract.” C. Material Safety Data Sheet
Contractor shall comply with all of the provisions of General Industry Safety Orders of the California Administrative Code. The Contractor shall submit to the Director a Material Safety Data Sheet (MSDS) for each hazardous substance proposed to be used, ten (10) days prior to the delivery of such materials to the job site or use of such materials at a manufacturing plant where the Director is to perform an inspection. For materials which are to be tested in City laboratories, the MSDS shall be submitted with the sample(s). Hazardous substance is defined as any substance included in the list (Director's List) of hazardous substances prepared by the Director, California Department of Industrial Relations, pursuant to Labor Code Section 6382. Failure to submit an MSDS for any hazardous substance may result in actions as provided in Article 5, "Suspension or Termination of Contract".

10.03 DIFFERING SITE CONDITIONS
A. Differing Site Conditions Defined. The Contractor shall promptly, and before such conditions are disturbed, notify the Director in writing of any Differing Site Conditions. Differing Site Conditions are those conditions, located at the project site or in existing improvements and not otherwise ascertainable by Contractor through the exercise of due diligence in the performance of its inspection obligations in the Contract Documents, encountered by Contractor in digging trenches or other excavations(s) that extend deeper than four feet below the surface of the ground that constitute:

1. Material that the Contractor believes may be material that is hazardous waste as defined in Section 25117 of the Health and Safety Code, which is required to be removed to a Class I, Class II, or Class III disposal site in accordance with provisions of existing law.

2. Subsurface or latent physical conditions at the site differing materially from those indicated in these Contract Documents.

3. Unknown physical conditions at the site, of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in Work of the character provided for in these Contract Documents.

B. Notice by Contractor. If the Contractor encounters conditions it believes constitute Differing Site Conditions, then notice of such conditions shall, before such conditions are disturbed, be promptly reported to the Director followed within twenty-four (24) hours by a further written notice stating a detailed description of the conditions encountered.

C. The Director will promptly investigate the conditions and If he/she finds that such conditions do materially differ, or do involve hazardous waste, and do cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work under this Contract, an equitable adjustment will be made, as determined by the Director.

D. Change Order Request. If Contractor intends to seek an adjustment to the Contract Sum or Contract Time based upon Differing Site Conditions, it must, within ten (10) Days after the Discovery Date relative to such conditions, submit a Change Order Request setting forth a detailed cost breakdown and Time Impact Analysis, in the form required by Article 6 of these General Conditions, of the additional Allowable Costs and Excusable Delay resulting from such Differing Site Conditions.

E. Failure to Comply. Failure by Contractor to strictly comply with the requirements of this Paragraph R Dependable Const Inc.

Page 79 of 222 ends

.
.

Item 10 Page 81 of 369

10.03 concerning the timing and content of any notice of Differing Site Conditions or request for adjustment in Contract Sum or Contract Time based on Differing Site Conditions shall be deemed waiver of any right by the Contractor for an adjustment in the Contract Sum or Contract Time by reason of such conditions.

F. Final Completion. No claim by the Contractor for additional compensation for Differing Site Conditions shall be allowed if asserted after Final Payment.

G. In the event of disagreement between the Contractor and the Director whether the conditions do materially differ or whether a hazardous waste is involved or whether the conditions cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, the Contractor shall not be excused from any completion date required by the Contract, but shall proceed with all Work to be performed under the Contract Documents.

H. The Contractor shall retain all rights provided by, and shall be subject to all requirements of, this Contract which pertain to the resolution of disputes and protests.

I. Contractor Responsibility. Except as otherwise provided in this Paragraph 10.03 for Differing Site Conditions, Contractor agrees to solely bear the risk of additional cost and Delay due to concealed or unknown conditions, surface or subsurface, at the Site or in Existing Improvements, without adjustment to the Contract Sum or Contract Time.

10.04 TRAFFIC REGULATION
A. During the performance of the Work the Contractor shall erect and maintain necessary temporary fences, bridges, railings, lights, signals, barriers, or other safeguards as shall be appropriate under the circumstance in his/her judgment for the prevention of accidents; and he/she shall take other precautions as necessary for public safety including, but not limited to, traffic control. Traffic control shall be conducted in accordance with the latest edition of the California Manual on Uniform Traffic Control Devices (MUTCD), published by BNi Books, and as directed and approved by the City Engineer.

B. Contractor shall submit at least ten (10) Working Days prior to Work a detailed traffic control plan, that is approved by all agencies having jurisdiction and that conforms to all requirements of the Specifications.

C. No changes or deviations from the approved detailed traffic control plan shall be made, except temporary changes in emergency situations, without prior approval of the City Engineer and all agencies having jurisdiction.

Contractor shall immediately notify the Director, the City Engineer and the agencies having jurisdiction of occurrences that necessitate modification of the approved traffic control plan.

D. Contractor’s failure to comply with this provision may result in actions as provided in Article 5:
“Suspension or Termination of Contract” of these General Conditions.

10.05 TRAFFIC CONTROL DEVICES
A. Traffic signs, flashing lights, barricades and other traffic safety devices used to control traffic shall conform to the requirements of the California Manual on Uniform Traffic Control Devices (MUTCD) R Dependable Const Inc.

Page 80 of 222 ends

.
.

Item 10 Page 82 of 369
and as approved by the City Engineer.

1. Portable signals shall not be used unless permission is given in writing by the agency having jurisdiction.

2. Warning signs used for nighttime conditions shall be reflectorized or illuminated. "Reflectorized signs" shall have a reflectorized background and shall conform to the current State of California Department of Transportation specification for reflective sheeting on highway signs.

B. If the Contractor fails to provide and install any of the signs or traffic control devices required herby or ordered by the City staff, staff may cause such signs or traffic control devices to be placed by others, charge the costs therefore against the Contractor, and deduct the same from the next progress payment.

10.06 EXECUTION
A. The Contractor shall provide written notification to the Police Department, Traffic Bureau (323) 587- 5171, at least two (2) weeks prior to the beginning of construction at any particular location. Notification will include the specific location, project dates, what lanes of the roadway will be closed and when. Also the construction project manager’s name and business phone number and the construction inspector’s name and business phone number.

B. The Contractor shall notify, by telephone, the Police Department, (323) 587-5171 at the completion of any posting of temporary no parking signs. Notification will include the times, dates and locations of the posting. When vehicles must be towed for violation of temporary no parking signs, the person who actually posted the signs, or on-view supervisor of that posting, will be present to answer pertinent questions that may be asked by the parking enforcement officer or police officer towing the vehicles.

C. The Contractor shall notify the Fire Department, on a daily basis during the entire period that construction is in progress whenever roadways are reduced in width or blocked. Notification shall be made to the Fire Dispatch (323) 881-6183 and the Contractor shall provide the information required to identify which roadways would have accessibility problems due to his/her operations. The Contractor shall submit to Fire Department schedule of Work for their use and files.

D. Roads subject to interference from the Work covered by this Contract shall be kept open, and the fences subject to interference shall be kept up by the Contractor until the Work is finished. Except where public roads have been approved for closure, traffic shall be permitted to pass through designated traffic lanes with as little inconvenience and delay as possible.

E. Where alternating one-way traffic has been authorized, the maximum time that traffic will be delayed shall be posted at each end of the one-way traffic section. The maximum delay time shall be approved by the agency having jurisdiction.

F. Contractor shall install temporary traffic markings where required to direct the flow of traffic and shall maintain the traffic markings for the duration of need. Contractor shall remove the markings by abrasive blasting when no longer required.

G. Convenient access to driveways and buildings in the vicinity of Work shall be maintained as much as possible. Temporary approaches to, and crossing of, intersecting traffic lanes shall be provided and R Dependable Const Inc.

Page 81 of 222 ends

.
.

Item 10 Page 83 of 369
kept in good condition.

H. When leaving a Work area and entering a roadway carrying public traffic, the Contractor's equipment, whether empty or loaded, shall in all cases yield to public traffic.

10.07 FLAGGING
A. Contractor shall provide flaggers to control traffic where required by the approved traffic control plan.

1. Flaggers shall perform their duties and shall be provided with the necessary equipment in accordance with the current "Instructions to Flaggers" of the State of California Department of Transportation.

2. Flaggers shall be employed full time on traffic control and shall have no other duties.

10.08 PEDESTRIAN CANOPIES OR BARRICADE IMPROVEMENTS
Refer to City of Vernon for requirements for building or access road safety improvements that the Contractor shall construct during construction period. These devices or improvements, as the City deems necessary or prudent, shall be at the expense of the Contractor.
[END OF ARTICLE]
R Dependable Const Inc.

Page 82 of 222 ends

.
.

Item 10 Page 84 of 369
ARTICLE 11 - INDEMNITY

11.01 INDEMNITY
To the maximum extent permitted by law, the Contractor shall fully indemnify, hold harmless, protect, and defend the City, its officers, employees, agents, representatives and their successors and assigns (“Indemnitees”) from and against any and all demands, liability, loss, suit, claim, action, cause of action, damage, cost, judgment, settlement, decree, arbitration award, stop notice, penalty, loss of revenue, and expense (including any fees of accountants, attorneys, experts or other professionals, and costs of investigation, mediation, arbitration, litigation and appeal), in law or in equity, of every kind and nature whatsoever, arising out of or in connection with, resulting from or related to, or claimed to be arising out of the Work performed by Contractor, or any of its officers, agents, employees, Subcontractors, Sub-Subcontractors, design consultants or any person for whose acts any of them may be liable, regardless of whether such claim, suit or demand is caused, or alleged to be caused, in part, by an Indemnitee, including but not limited to:

A. Bodily injury, emotional injury, sickness or disease, or death to any persons; B. Infringement of any patent rights, licenses, copyrights or intellectual property which may be brought against the Contractor or City arising out of Contractor’s Work, for which the Contractor is responsible; C. Stop notices and claims for labor performed or materials used or furnished to be used in the Work, including all incidental or consequential damages resulting to City from such stop notices and claims; D. Failure of Contractor or its Subcontractors to comply with the provisions for insurance; E. Failure to comply with any Governmental Approval or similar authorization or order; F. Misrepresentation, misstatement, or omission with respect to any statement made in or any document furnished by the Contractor in connection therewith;
G. Breach of any duty, obligation, or requirement under the Contract Documents; H. Failure to provide notice to any Party as required under the Contract Documents; I. Failure to protect the property of any utility provider or adjacent property owner; or J. Failure to make payment of all employee benefits.

This indemnity provision is effective regardless of any prior, concurrent, or subsequent active or passive negligence by Indemnitees, except that, to the limited extent mandated by California Civil Code Section 2782, the Contractor shall not be responsible for liabilities which arise from the sole negligence or willful misconduct of Indemnitees or arise from the active negligence of City.

11.02 ENFORCEMENT
Contractor’s obligations under this Article extend to claims occurring after termination of the Contractor’s performance of the Contract or Final Payment to Contractor. The obligations apply regardless of any actual or alleged negligent act or omission of Indemnitees. Contractor, however, shall not be obligated under this Agreement to indemnify an Indemnitee for claims arising from the sole active negligence or willful misconduct of the Indemnitee or independent contractors who are directly responsible to Indemnitees. Contractor’s obligations under this Article are in addition to any other rights or remedies which the Indemnitees may have under the law R Dependable Const Inc.

Page 83 of 222 ends

.
.

Item 10 Page 85 of 369
or under the Contract Documents. In the event of any claim, suit or demand made against any Indemnitees, the City may in its sole discretion reserve, retain or apply any monies due to the Contractor under the Contract for the purpose of resolving such claims; provided, however, that the City may release such funds if the Contractor provides the City with reasonable assurance of protection of the City’s interests. The City shall in its sole discretion determine whether such assurances are reasonable.

11.03 NO LIMITATIONS
Contractor’s indemnification and defense obligations set forth in this Article are separate and independent from the insurance provisions set forth in Article 12 herein; and do not limit, in any way, the applicability, scope, or obligations set forth in those insurance provisions. In claims, suits, or demands against any Indemnitee by an employee of the Contractor, a Subcontractor, anyone directly or indirectly employed by them, or anyone for whose acts they may be liable, the Contractor’s indemnification and defense obligations shall not be limited by a limitation on amount or type of damages, compensation, or benefits payable by or for the Contractor or a Subcontractor under workers’ compensation acts, disability benefits acts, or other employee benefits acts. [END OF ARTICLE]
R Dependable Const Inc.

Page 84 of 222 ends

.
.

Item 10 Page 86 of 369
ARTICLE 12 – INSURANCE

12.01 CONDITION TO COMMENCEMENT
Contractor shall not commence Work under this Contract until Contractor has obtained all insurance required hereunder from a company or companies acceptable to City, nor shall the Contractor allow any Subcontractor to commence Work on a subcontract until all insurance required of said Subcontractor has been obtained. Proof of insurance including insurance certificates and endorsements as set forth in Exhibit 4 must be submitted by the Contractor prior to the City’s execution of the Contract.

12.02 MINIMUM COVERAGE AND LIMITS
Contractor shall maintain the insurance coverage as set forth in Exhibit 4 throughout the term of the Contract.

12.03 CONDITIONS REGARDING INSURANCE COVERAGE AND LIMITS City and Contractor agree as follows:

A. All insurance coverage and limits provided pursuant to the Contract Documents shall apply to the full extent of the policies involved, available or applicable. Nothing contained in the Contract Documents or any other agreement relating to City or its operations limits the application of such insurance coverage.

B. None of the policies required by this Contract shall be in compliance with these requirements if they include any limiting endorsement that has not been first submitted to City and approved in writing by the City’s Risk Manager.

12.04 INSURANCE OBLIGATION IS SEPARATE FROM INDEMNITY OBLIGATION This Agreement’s insurance provisions:

A. Are separate and independent from the indemnification and defense provisions in Article 12 of the Agreement; and
B. Do not limit, in any way, the applicability, scope, or obligations of the indemnification and defense provisions in Article 12 of the Agreement.
[END OF ARTICLE]
R Dependable Const Inc.

Page 85 of 222 ends

.
.

Item 10 Page 87 of 369
ARTICLE 13 – BONDS

13.01 REQUIRED BONDS
A. Contractor shall furnish the following bonds:

1. A Performance Bond in an amount equal to one hundred percent (100%) of the total Contract price in the form shown in Exhibit "1" attached hereto.

2. A Payment Bond (Labor and Material) in an amount equal to one hundred percent (100%) of the total Contract price in the form shown in Exhibit "2" attached hereto.

3. A Maintenance Bond in an amount equal to ten percent (10%) of the total Contract price in the form shown in Exhibit "3" attached hereto.

13.02 POWER OF ATTORNEY
All bonds shall be accompanied by a power of attorney from the surety company authorizing the person executing the bond to sign on behalf of the company. If the bonds are executed outside the State of California, all copies of the bonds must be countersigned by a California representative of the surety. The signature of the person executing the bond on behalf of Surety shall be acknowledged by a Notary Public as the signature of the person designated in the power of attorney.

13.03 APPROVED SURETY
All bonds must be issued by a California admitted surety insurer with the minimum A.M Best Company Financial strength rating of “A: VII”, or better. Bonds issued by a California admitted surety not listed on Treasury Circular 570 will be deemed accepted unless specifically rejected by the City. Bonds issued from admitted surety insurers not listed in Treasury Circular 570 must be accompanied by all documents enumerated in California Code of Civil Procedure Section 995.660. All such bonds must be accompanied by a power of attorney from the surety company authorizing the person executing the bond to sign on behalf of the company. If the bonds are executed outside the State of California, all copies of the bonds must be countersigned by a California representative of the surety. The signature of the person executing the bond on behalf of Surety must be acknowledged by a Notary Public as the signature of the person designated in the power of attorney.

13.04 REQUIRED PROVISIONS
Every bond must display the surety’s bond number and incorporate the Contract for construction of the Work by reference. The terms of the bonds shall provide that the surety agrees that no change, extension of time, alteration, or modification of the Contract Documents or the Work to be performed thereunder shall in any way affect its obligations and shall waive notice of any such change, extension of time, alteration, or modification of the Contract Documents.

13.05 NEW OR ADDITIONAL SURETIES
If, during the continuance of the Contract, any of the sureties, in the opinion of the City, are or become nonresponsible or otherwise unacceptable to City, City may require other new or additional sureties, which the Contractor shall furnish to the satisfaction of City within ten (10) days after notice, and in default thereof the Contract may be suspended and the materials may be purchased or the Work completed as provided in Article 5 herein.

R Dependable Const Inc.

Page 86 of 222 ends

.
.

Item 10 Page 88 of 369

13.06 WAIVER OF MODIFICATIONS AND ALTERATIONS
No modifications or alterations made in the Work to be performed under the Contract or the time of performance shall operate to release any surety from liability on any bond or bonds required to be given herein. Notice of such events shall be waived by the surety.

13.07 APPROVAL OF BONDS
The Contract will not be executed by City nor the Notice to Proceed issued until the required bonds have been received and approved by City. City's decision as to the acceptability of all sureties and bonds is final. No substitution of the form of the documents will be permitted without the prior written consent of City. [END OF ARTICLE]
R Dependable Const Inc.

Page 87 of 222 ends

.
.

Item 10 Page 89 of 369
ARTICLE 14 - LABOR PROVISIONS

14.01 WORKING HOURS
A. Work or activity of any kind shall be limited to the hours from 7:00 a.m. to 7:00 p.m. No construction noise shall be permitted between the hours of 7:00 p.m. and 7:00 a.m. of the next day.

B. Work in excess of eight (8) hours per day, on Saturdays, Sundays, or on City holidays requires prior consent of the Director and is subject to Cost of Overtime Construction Inspection.

C. Night, Sunday and Holiday Work. No Work shall be performed at night, Sunday, or the fourteen (14) observed holidays to wit: New Year’s Day, Martin Luther King, Jr. Day, President’s Day, Cesar Chavez Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Indigenous People’s Day, Veteran’s Day, Thanksgiving Day, Christmas Eve, Christmas Day and New Year’s Eve, except Work pertaining to the public safety or with the permission of the Director, and accordance with such regulations as he/she shall furnish in writing. Before performing any Work at said times, except Work pertaining to the public safety, the Contractor shall give written notice to the Director so that proper inspection may be provided. “Night” as used in this paragraph shall be deemed to include the hours from 7:00 P.M. to 7:00 A.M. of the next succeeding day.

14.02 COST OF OVERTIME CONSTRUCTION SERVICES AND INSPECTIONS A. Overtime construction Work performed at the option of, or for the convenience of, the Contractor will be inspected by the City at the expense of the Contractor. For any such overtime beyond the regular 8-hour day and for any time worked on Saturday, Sunday, or holidays the charges will be determined by the City, and submitted to the Contractor for payment.

B. Equipment, materials, or services provided by the City, in connection with Contractor-initiated overtime construction Work described in Paragraph 14.02(A), will also be at the expense of the Contractor. The charges will be determined by the City, and submitted to the Contractor for payment.

C. There will be no charges to the Contractor for the inspection of overtime Work ordered by the Director or required by the Contract Documents.

14.03 COMPLIANCE WITH STATE LABOR CODE
A. Contractor shall comply with the provisions of the Labor Code of the State of California and any amendments thereof.

1. The time of service of any worker employed upon the Work shall be limited and restricted to eight (8) hours during any one-calendar day, and 40 hours during any one-calendar week.

2. Work performed by employees of the Contractor in excess of eight (8) hours per day, and 40 hours during any one calendar week, shall be permitted upon compensation for all hours worked in excess of eight (8) hours per day at not less than one and one-half times the basic rate of pay.

3. The Contractor and every Subcontractor shall keep an accurate record showing the name of and the actual hours worked each calendar day and each calendar week by each worker employed by him/her in connection with the Work; the record shall be kept open at all reasonable hours to the inspection of the City and to the Division of Labor Standards Enforcement of the State of California.

R Dependable Const Inc.

Page 88 of 222 ends

.
.

Item 10 Page 90 of 369

4. In the event City deems Contractor is in violation of this Paragraph 14.03, the Contractor shall, as a penalty, forfeit Fifty Dollars ($50.00) for each worker employed in the execution of the Contract by the Contractor or by any Subcontractor for each calendar day for which the employee was underpaid in addition to an amount sufficient to recover underpaid wages. For each subsequent violation, a (one hundred dollar) $100 penalty shall apply for each underpaid employee for each pay period for which the employee was underpaid in addition to an amount sufficient to cover underpaid wages. This subparagraph is effective to the extent it does not directly conflict with the overtime penalty provision of California Labor Code Section 558. In the event of such conflict, the California Labor Code governs over this Paragraph 14.03(A)(4).

14.04 WAGE RATES
A. Prevailing Wages

1. Contractor shall comply with the general prevailing rates of per diem wages and the general prevailing rates for holiday and overtime Work in the locality in which the Work is to be performed, for each craft, classification, or type of worker needed to execute the Contract. The Director of the Department of Industrial Relations of the State of California (pursuant to California Labor Code) and the United States Secretary of Labor (pursuant to the Davis-Bacon Act) have determined the general prevailing rates of wages in the locality in which the Work is to be performed. The rates are available from the City at its Department of Public Works, which shall be made available to any interested party upon request; or online at www.dir.ca.gov/DLSR/PWD/.

To the extent that there are any differences in the federal and state prevailing wage rates for similar classifications of labor, the Contractor and its Subcontractors shall pay the highest wage rate.

2. The Contractor shall post a copy of the general prevailing rate of per diem wages at the job site.

3. The Contractor and any Subcontractor under him/her shall pay not less than the specified prevailing rate of wages to all workers employed in the execution of the Contract.

4. The holidays upon which such rates shall be paid shall be all holidays recognized in the collective bargaining Contract applicable to the particular craft, classification, or type of worker employed on the project.

5. The Contractor shall, as a penalty to the State or the City, forfeit not more than Fifty Dollars ($50) for each calendar day, or portion thereof, for each worker paid less than the prevailing rates for the Work or craft in which the worker is employed under the Contract by the Contractor or by any Subcontractor under him. The difference between the prevailing wage rates and the amount paid to each worker for each calendar day or portion thereof for which such worker was paid less than the stipulated prevailing wage rate shall be paid to such worker by the Contractor.

6. The specified wage rates are minimum rates only and the City will not consider and shall not be liable for any claims for additional compensation made by the Contractor because of payment by him/her of any wage rate in excess of the general prevailing rates. All disputes in regard to the payment of wages in excess of those specified herein shall be adjusted by the Contractor at his/her own expense.

B. Payroll Records

1. Pursuant to California Labor Code Section 1776, the Contractor and each Subcontractor shall R Dependable Const Inc.

Page 89 of 222 ends

.
.

Item 10 Page 91 of 369
keep an accurate payroll record, showing the name, address, social security number, Work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker or other employee employed in connection with the Work. The payroll records shall be certified and shall be available for inspection.

2. The Contractor shall inform the City of the location of the payroll records, including the street address, city and county, and shall, within five (5) Working Days, provide a notice of change in location and address.

3. Upon request by the Director, the Contractor shall provide a copy of the certified payroll records along with a statement of compliance.

14.05 APPRENTICESHIP STANDARDS
A. Compliance with California Labor Code Section 1777.5 et seq. requires all public works contractors and subcontractors to:

1. Prior to commencing work on a public works contract, submit Contract Award information to the applicable joint apprenticeship committee, including an estimate of the journeyman hours to be performed under the Contract, the number of apprentices to be employed, and the approximate dates the apprentices will be employed. Use Form DAS-140 from the State Department of Industrial Relations. The City reserves the right to require Contractor and Subcontractors to submit a copy of said forms to the City.

2. Employ apprentices for the public work at a ratio of no less than one (1) hour or apprentice work for every five (5) hours or labor performed by a journeyman. To request dispatch of apprentices, use Form DAS-142 from the State Department of Industrial Relations. The City reserves the right to require Contractor and Subcontractors to submit a copy of said forms to the City.

3. Pay the apprentice rate on public works projects only to those apprentices who are registered, as defined in Labor Code Section 3077.

4. Contribute to the training fund in the amount identified in the Prevailing Wage Rate publication for journeyman and apprentices. Contractors who choose not to contribute to the local training trust fund must make their contributions to the California Apprenticeship Council, P.O. Box 420603, San Francisco, CA 94142.

B. California Labor Code Section 1777.7, subdivision (g), provides that the interpretation of Section 1777.5 shall be in accordance with the regulations of the California Apprenticeship Council, with which Contractor must also comply.

C. Failure to comply with the provisions of California Labor Code Section 1777.5 et seq. may result in the loss of the right to bid or perform work on all public works projects for a period of one to three years and the imposition of a civil penalty of One Hundred Dollars ($100.00) for each calendar day of noncompliance for the first violation and up to Three Hundred Dollars ($300.00) for each calendar day of noncompliance for a second or subsequent violation. Contractor should make a separate copy of this material for each of his/her Subcontractors.

R Dependable Const Inc.

Page 90 of 222 ends

.
.

Item 10 Page 92 of 369
D. Payroll Records. The Contractor and each Subcontractor shall keep an accurate payroll record, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman apprentice, worker or other employee employed in connection with the work. The payroll records shall be certified and shall be submitted to the Project Manager every two weeks.

E. Statement of Employer Fringe Benefit Payments. Within five (5) calendar days of signing the Contract or Subcontract, as applicable, the Statement of Employer Payments (DLSE Form PW 26 from the State Department of Industrial Relations) shall be completed for each Contractor and Subcontractor of any tier who pays benefits to a third party trust, plan or fund for health and welfare benefits, vacation funds or makes pension contributions. The form must contain, for each worker classification, the fund, plan or trust name, address, administrator, the amount per hour contributed and the frequency of contributions. Training fund contributions shall also be reported in this form.

City reserves the right to require Contractors and Subcontractors to submit a copy of said forms to the City.

14.06 EMPLOYMENT OF APPRENTICES
A. In the performance of this Contract, the Contractor and any Subcontractor shall comply with the provisions concerning the employment of apprentices in the Labor Code of the State of California and any amendments thereof, including but not limited to Labor Code Sections 1776, 1777.5, 1777.6 and 1777.7.

B. In the event the Contractor or any Subcontractor willfully fails to comply with the aforesaid provisions of the Labor Code, such Contractor or Subcontractor shall be subject to the penalties for noncompliance in the Labor Code of the State of California and any amendments thereof.

14.07 REGISTRATION WITH THE STATE DEPARTMENT OF INDUSTRIAL RELATIONS In the performance of this Contract, Contractor and/or any Subcontractor must be currently registered and qualified (including payment of any required fee) with the State Department of Industrial Relations pursuant to Labor Code section 1725.5. This project is subject to compliance monitoring and enforcement by the State Department of Industrial Relations.

14.08 CHARACTER OF WORKERS
The Contractor shall not allow his/her agents or employees, Subcontractors, or any agent or employee thereof, to trespass on premises or lands in the vicinity of the Work. Only skilled supervisors and workers shall be employed on Work requiring special qualifications, and when required by the Director, the Contractor shall discharge any person who commits trespass, or in the opinion of the Director, acts in a disorderly, dangerous, insubordinate, incompetent, or otherwise objectionable manner. Any employee being intoxicated or bringing or having intoxicating liquors or controlled substances on the Work shall be discharged. Such discharge shall not be the basis of any claim for compensation of damages against the City or any of its officers, agents, and employees.

14.09 NO SMOKING – STATE LABOR CODE SECTION 6404.5
The Contractor and its agents, employees, Subcontractors, representatives, and any person under Contractor’s control, are prohibited from smoking in— or within a 20-foot distance from— the Site, which is a "place of employment" under California Labor Code § 6404.5.

R Dependable Const Inc.

Page 91 of 222 ends

.
.

Item 10 Page 93 of 369
[END OF ARTICLE]
R Dependable Const Inc.

Page 92 of 222 ends

.
.

Item 10 Page 94 of 369
ARTICLE 15 - DISPUTE RESOLUTION

15.01 SUBMISSION OF CLAIMS
A. By Contractor
Contractor’s right to commence the Claims Dispute Resolution Process shall arise upon the Director’s written response denying all or part of a Claim. Contractor shall submit a written Statement of Dispute to the Director within seven (7) Days after the Director rejects all or a portion of Contractor’s Claim.

Contractor’s Statement of Dispute shall be signed under penalty of perjury and shall state with specificity the events or circumstances giving rise to the Claim, the dates of their occurrence and the effect, if any, on the compensation due or performance obligations of Contractor under the Construction Contract. Such Statement of Dispute shall include adequate supporting data to substantiate the disputed Claim. Adequate supporting data for a Claim relating to the adjustment of the Contractor’s obligations relative to time of performance shall include a detailed, event-by-event description of the impact of each delay on Contractor’s time for performance. Adequate supporting data to a Statement of Dispute submitted by Contractor involving Contractor’s compensation shall include a detailed cost breakdown and supporting cost data in such form and including such detailed information and other supporting data as required to demonstrate the grounds for, and precise amount of, the Claim.

B. By City
City’s right to commence the Claims Dispute Resolution Process shall arise at any time following the City’s actual discovery of the circumstances giving rise to the Claim. Nothing contained herein shall preclude City from asserting Claims in response to a Claim asserted by Contractor. A Statement of Dispute submitted by City shall state the events or circumstances giving rise to the Claim, the dates of their occurrence and the damages or other relief claimed by City as a result of such events.

C. Claims Defined
The term “claims” as used herein shall be as defined in California Public Contract Code § 9204(c)(1).

15.02 CLAIMS DISPUTE RESOLUTION PROCESS
The parties shall utilize each of the following steps in the Claims Dispute Resolution Process in the sequence they appear below. Each party shall participate fully and in good faith in each step in the Claims Dispute Resolution Process, which good faith effort shall be a condition precedent to the right of each party to proceed to the next step in the Claims Dispute Resolution Process.

A. Direct Negotiations
Designated representatives of City and Contractor shall meet as soon as possible (but not later than ten (10) Days after receipt of the Statement of Dispute) in a good faith effort to negotiate a resolution to the Claim. Each party shall be represented in such negotiations by an authorized representative with full knowledge of the details of the Claim or defenses being asserted by such party, and with full authority to resolve such Claim then and there, subject only to City’s right and obligation to obtain City Council [or other City official] approval of any agreed settlement or resolution. In the Claim involves the assertion of a right or claim by a Subcontractor against Contractor that is in turn being asserted by Contractor against City, then such Subcontractor shall also have a representative attend such negotiations, with the same authority and knowledge as just described. Upon completion of the meeting, if the Claim is not resolved, the parties may either continue the negotiations or either party R Dependable Const Inc.

Page 93 of 222 ends

.
.

Item 10 Page 95 of 369
may declare negotiations ended. All discussions that occur during such negotiations and all documents prepared solely for the purpose of such negotiations shall be confidential and privileged pursuant to California Evidence Code Sections 1119 and 1152.

B. Deferral of Claims
Following the completion of the negotiations required by Paragraph 15.02-A., all unresolved Claims, except those that do not involve parties other than the Contractor and City, shall be deferred pending Final Completion of the Work, subject to City’s right, in its sole and absolute discretion, to require that the claims Dispute Resolution Process proceed prior to Final Completion. In the event that City does not elect to proceed with the Claims Dispute Resolution Process prior to Final Completion of the Work, all Claims that have been deferred until such Final Completion shall be consolidated within a reasonable time after such Final Completion and thereafter pursued to resolution pursuant to the Claims Dispute Resolution Process. Nothing contained in this Article 15 shall be interpreted as limiting the parties’ rights to continue informal negotiations of Claims that have been deferred until such Final Completion; provided, however, that such informal negotiations shall not be interpreted as altering the provisions of this Article 15 deferring final determination and resolution of unresolved Claims until after Final Completion of the Work.

C. Required Provisions On Contract Claim Resolution Under California Law If a Claim is not resolved by the steps described in this Article 15(A) and 15(B), Public Contract Code Section 9204 specifies required provisions on resolving contract Claims of any size, and Public Contract Code Section 20104, et seq., specifies required provisions on resolving contract Claims less than $375,000. Those statutes constitute a part of this Contract. In the event any other Contract provision violates such statutes, the applicable statute controls. Public Contract Code Section 9204 provides:
• For the purposes of this section, “Claim” means a separate demand by Contractor for (1) a time extension, (2) payment or money or damages arising from Work done by or on behalf of Contractor arising under the contract documents and payment of which is not otherwise expressly provided for or the claimant is not otherwise entitled to, or (3) an amount the payment of which is disputed by the City.
• Upon receipt of a Claim the City shall conduct a reasonable review of the Claim and within 45 days, or if the City’s governing body must approve the City’s response to the Claim and the governing body has not met within the 45 days, then within three (3) days of the Agency’s meeting, shall provide Contractor with a written statement identifying what portion of the Claim is disputed and what portion is undisputed. Should the City take no action on the Claim within 45 days of submission, it shall be deemed denied.
• If the Contractor disputes the City’s response to its Claim, including a failure to respond, it may submit via registered mail or certified mail, return receipt requested, a written demand for an informal conference to meet and confer for settlement of the issues in dispute. The City shall schedule such a meet and confer conference within 30 days for settlement of the dispute. Within ten (10) days of the meet and confer conference the City shall provide Contractor with a written statement identifying the portion of the Claim that remains in dispute and the portion that is undisputed. If the Contractor disputes the City’s statement, it shall inform the City and they shall mutually agree to a mediator within 10 business days of the written statement. • The City shall pay the undisputed portions of the Claim within 60 days of the issuance of a written statement identifying an undisputed portion.

R Dependable Const Inc.

Page 94 of 222 ends

.
.

Item 10 Page 96 of 369
• Any disputed portion of the Claim, as identified by the Contractor in writing, shall be submitted to nonbinding mediation, with the City and the Contractor sharing the associated costs equally. The City and Contractor shall mutually agree to a mediator within 10 business days after the disputed portion of the Claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the Claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator.

If mediation is unsuccessful, the parts of the Claim remaining in dispute shall be subject to applicable procedures outside this section.
• For Claims under $375,000, unless the parties agree otherwise in writing, mediation pursuant to these provisions shall excuse the mediation obligation under Public Contracting Code section 20104.4(a).
• The parties may mutually agree, in writing, to waive the mediation requirements of this subsection and proceed to the commencement of a civil action.
• Failure by the City to respond to a Claim from Contractor within the time periods described in this subdivision or to otherwise meet the time requirements of this section shall result in the Claim being deemed rejected in its entirety. A Claim that is denied by reason of the City’s failure to have responded to a Claim, or its failure to otherwise meet the time requirements of this section, shall not constitute an adverse finding with regard to the merits of the Claim or the responsibility or qualifications of the Contractor.
• Amounts not paid in a timely manner as required by this section shall bear interest at 7 percent per annum.
• If a Subcontractor or a lower tier subcontractor lacks legal standing to assert a Claim against the City because privity of contract does not exist, the Contractor may present to the City a Claim on behalf of a Subcontractor or lower tier subcontractor. A Subcontractor may request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the Contractor present a Claim for work which was performed by the Subcontractor or by a lower tier subcontractor on behalf of the Subcontractor. The Subcontractor requesting that the Claim be presented to the public entity shall furnish reasonable documentation to support the Claim. Within 45 days of receipt of this written request, the Contractor shall notify the Subcontractor in writing as to whether the Contractor presented the Claim to the City and, if the original Contractor did not present the Claim, provide the Subcontractor with a statement of the reasons for not having done so. • Nothing in this section shall impose liability upon the City that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.

Public Contract Code Section 20104, et seq., provides:
• For the purposes of this section, “Claim” means a separate demand by Contractor of $375,000 or less for (1) a time extension, (2) payment or money or damages arising from Work done by or on behalf of Contractor arising under the Contract Documents and payment of which is not otherwise expressly provided for or the claimant is not otherwise entitled to, or (3) an amount the payment of which is disputed by the City. Claims that together total more than $375,000 do not qualify as a “separate demand of $375,000 or less,” and are not subject to this section.

R Dependable Const Inc.

Page 95 of 222 ends

.
.

Item 10 Page 97 of 369
• A voucher, invoice, payment application, or other routine or authorized form of request for payment is not a Claim for purposes of this section. If such request is disputed as to liability or amount, then the disputed portion of the submission may be converted to a Claim under this section by submitting a separate Claim in compliance with Contract Documents Claim submission requirements.
• Caution. This section does not apply to tort Claims, and nothing in this section is intended nor shall be construed to change the time periods for filing tort Claims or actions specified by Chapter 1 and Chapter 2 of Part 3 of Division 3.6 of Title 1 of the California Government Code. • The Claim must be in writing, submitted in compliance with all requirements of the Contract Documents.
• For Claims of fifty thousand dollars ($50,000) or less, the City shall respond in writing within fortyfive (45) days of receipt of the Claim, or the City may request in writing within thirty (30) days of receipt of the Claim, any additional documentation supporting the Claim or relating to any defenses or Claims the City may have against claimant. If additional information is thereafter required, it shall be requested and provided in accordance with this section upon mutual agreement of the City and claimant. The City’s written response to the Claim, as further documented, shall be submitted to claimant within fifteen (15) days after receipt of further documentation or within a period of time no greater than taken by claimant in producing the additional information, whichever is greater. • For Claims over Fifty Thousand Dollars ($50,000) and less than or equal to $375,000: the City shall respond in writing within sixty (60) days of receipt of the Claim, or the City may request in writing within thirty (30) days of receipt of the Claim, any additional documentation supporting the Claim or relating to any defenses or Claims the City may have against claimant. If additional information is thereafter required, it shall be requested and provided in accordance with this section, upon mutual agreement of the City and claimant; the City’s written response to the Claim, as further documented, shall be submitted to claimant within thirty (30) days after receipt of further documentation or within a period of time no greater than taken by claimant in producing the additional information, whichever is greater.
• Meet and Confer: If claimant disputes the City’s written response, or the City fails to respond within the time prescribed above, claimant shall notify the City, in writing, either within fifteen (15) days of receipt of the City’s response or within fifteen (15) days of the City’s failure to timely respond, and demand an informal conference to meet and confer for settlement of the issues in dispute. Upon demand the City will schedule a meet and confer conference within thirty (30) days for settlement of the dispute.

Following the meet and confer conference described herein, if the Claim or any portion remains in dispute, claimant may file a Claim as provided in Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the California Government Code.

For purposes of those provisions, the running of the period of time within which a Claim must be filed shall be tolled from the time claimant submits its written Claim as set forth herein, until the time that Claim is denied as a result of the meet and confer process, including any period of time utilized by the meet and confer process.

R Dependable Const Inc.

Page 96 of 222 ends

.
.

Item 10 Page 98 of 369
D. Legal Proceedings
If the Claim is not resolved by the procedures described in this Article 15 (A), 15 (B) and 15 (C) above, then the party wishing to further pursue resolution or determination of the Claim may submit the Claim for determination by commencing legal proceedings in a court of competent jurisdiction.

15.03 NO WAIVER
Participation in the Claims Dispute Resolution Process shall not constitute a waiver, release or compromise of any defense of either party, including, without limitation, any defense based on the assertion that the rights of Contractor that are the basis of a Claim were previously waived by Contractor due to failure to comply with the Contract Documents, including, without limitation, Contractor’s failure to comply with any time periods for providing notices or for submission or supporting documentation of Claims. [END OF ARTICLE]
R Dependable Const Inc.

Page 97 of 222 ends

.
.

Item 10 Page 99 of 369
ARTICLE 16 - ACCOUNTING RECORDS

16.01 MAINTENANCE OF RECORDS
Contractor shall keep, and shall include in its contracts with its Subcontractors, provisions requiring its Subcontractors to keep full and detailed books and records in accordance with the requirements of the Contract Documents, including the following: all information, materials and data of every kind and character (hard copy, as well as computer readable data if it exists), that have any bearing on or pertain to any matters, rights, duties or obligations relating to the Project or the performance of the Work, including, without limitation, agreements, purchase orders, leases, contracts, commitments, arrangements, notes, change orders, change order requests, estimates, field orders, schedules, diaries, logs, reports, shop drawings, samples, exemplars, Drawings, Specifications, invoices, delivery tickets, receipts, vouchers, cancelled checks, memoranda; accounting records; job cost reports; job cost files (including complete documentation covering negotiated settlements); backcharge; general ledgers; documentation of cash and trade discounts earned; insurance rebates and dividends, and other documents relating in way to Claims or Change Orders, Construction Change Directives, Work Directives, or other claims for payment related to the Project asserted by Contractor or any Subcontractor (“Accounting Records”). Contractor shall exercise such controls as may be necessary for proper financial management of the Work. Such accounting and control systems shall comply with prevailing custom and practice for similar projects, be satisfactory to City and shall include preservation of such records for a period of five (5) years after approval of the Notice of Completion and Acceptance by City, or for such longer period as may be required by applicable laws.

16.02 ACCESS TO RECORDS
Contractor shall allow, and shall include in its contracts with its Subcontractors provisions requiring its Subcontractors to allow, City and its authorized representative(s), auditors, attorneys and accountants, upon twenty-four (24) hours notice to Contractor, full access to inspect and copy all books and records relating to the Project that Contractor is required to maintain pursuant to Paragraph 16.01, above.

16.03 CONTRACTOR NONCOMPLIANCE, WITHHOLDING
Contractor's compliance with Paragraphs 16.01 and 16.02, above, shall be a condition precedent to maintenance of any legal action or arbitration by Contractor against City. In addition to and without limitation upon City's other rights and remedies for breach, including any other provisions for withholding set forth in the Contract Documents, City shall have the right, exercised in its sole discretion, to withhold from any payment to Contractor due under a current Application for Payment an additional sum of up to ten percent (10%) of the total amount set forth in such Application for Payment, until Contractor and its Subcontractors have complied with any outstanding and unsatisfied request by City under this Article 16. Upon such compliance with this Article 16, any additional monies withheld pursuant to this Paragraph 16.03 shall be released to Contractor.

16.04 SPECIFIC ENFORCEMENT BY CITY
Contractor agrees that any failure by Contractor or any Subcontractor to provide access to its books and records as required by this Article 16 shall be specifically enforceable, by issuance of a preliminary and/or permanent mandatory injunction by a court of competent jurisdiction based on affidavits submitted to such court and without the necessity of oral testimony, to compel Contractor to permit access, inspection, audits and/or reproduction of such books and records or to require delivery of such books and records to City for inspection, audit and/or reproduction.
[END OF ARTICLE]
R Dependable Const Inc.

Page 98 of 222 ends

.
.

Item 10 Page 100 of 369
ARTICLE 17-MISCELLANEOUS PROVISIONS

17.01 COMPLIANCE WITH APPLICABLE LAWS
A. Notices, Compliance
Contractor shall give all notices required by governmental authorities and comply with all applicable laws and lawful orders of governmental authorities, including but not limited to the provisions of the California Code of Regulations applicable to contractors performing construction and all laws, ordinances, rules, regulations and lawful orders relating to safety, prevailing wage and equal employment opportunities.

B. Taxes, Employee Benefits
Contractor shall pay at its own expense, at no cost to the City and without adjustment to the Contract Sum, all local, state and federal taxes, including, without limitation all sales, consumer, business license, use and similar taxes on materials, labor or other items furnished for the Work or portions thereof provided by Contractor or Subcontractors, all taxes arising out of its operations under the Contract Documents and all benefits, insurance, taxes and contributions for social security and unemployment insurance which are measured by wages, salaries or other remuneration paid to Contractor's employees. If under federal excise tax law any transaction hereunder constitutes a sale on which a federal excise tax is imposed and the sale is exempt from such excise tax because it is a sale for its exclusive use, then City, upon request, will execute documents necessary to show that is a political subdivision of the State for the purposes of such exemption and that the sale is for the exclusive use of the City, in which case no excise tax for such materials shall be included in the Bid or Contract Sum.

C. Notice of Violations
Contractor shall immediately notify the City and Director in writing of any instruction received from the City, Director, Architect or other person or entity that, if implemented, would cause a violation of any applicable law or lawful order of a governmental authority. If Contractor fails to provide such notice, then Director shall be entitled to assume that such instruction is in compliance with applicable laws and lawful orders of governmental authorities. If Contractor observes that any portion of the Drawings and Specifications or Work are at variance with applicable laws or lawful orders of governmental authorities, or should Contractor become aware of conditions not covered by the Contract Documents which will result in Work being at variance therewith, Contractor shall promptly notify Director in writing. If, without such notice to Director, Contractor or any Subcontractor performs any Work which it knew, or through the exercise of reasonable care should have known, was contrary to lawful orders of governmental authorities or applicable laws, then Contractor shall bear all resulting losses at its own expense, at no cost to City and without adjustment to the Contract Sum.

17.02 OWNERSHIP OF DESIGN DOCUMENTS
A. Property of City
All Design Documents, Contract Documents and Submittals (including, without limitation, all copies thereof) and all designs and building designs depicted therein are and shall remain the sole and exclusive property of the City and the City shall solely and exclusively hold all copyrights thereto.

Without derogation the City’s rights under this Paragraph, the Contractor and Subcontractors are R Dependable Const Inc.

Page 99 of 222 ends

.
.

Item 10 Page 101 of 369
granted a limited, non-exclusive license, revocable at will of City, to use and reproduce applicable portions of the Contract Documents and Submittals as appropriate to and for use in the execution of the Work and for no other purpose.

B. Documents on Site
Contractor shall keep on the Project site, at all times and for use by City, Director, Inspectors of Record and City’s Consultants, a complete set of the Contract Documents that have been approved by applicable Governmental Authorities.

C. Delivery to City
All Design Documents, Contract Documents and Submittals in the possession of Contractor or Subcontractors shall be returned to the City upon the earlier of Final Completion or termination of the Construction Contract; provided, however, that Contractor and each Subcontractor shall have the right to retain one (1) copy of the Contract Documents and Submittals for its permanent records.

D. Subcontractors
Contractor shall take all necessary steps to assure that a provision is included in all subcontracts with Subcontractors, of every tier, who perform Work on the Project establishing, protecting and preserving the, City’s rights set forth in this Paragraph.

17.03 AMENDMENTS
The Contract Documents may be amended only by a written instrument duly executed by the parties or their respective successors or assigns.

17.04 WAIVER
Either party's waiver of any breach or failure to enforce any of the terms, covenants, conditions or other provisions of the Contract Documents at any time shall not in any way limit or waive that party's right thereafter to enforce or compel strict compliance with every term, covenant, condition or other provision, any course of dealing or custom of the trade notwithstanding. Furthermore, if the parties make and implement any interpretation of the Contract Documents without documenting such interpretation by an instrument in writing signed by both parties, such interpretation and implementation thereof will not be binding in the event of any future disputes.

17.05 INDEPENDENT CONTRACTOR
Contractor is an independent contractor, and nothing contained in the Contract Documents shall be construed as constituting any relationship with City other than that of Project owner and independent contractor. In no event shall the relationship between City and Contractor be construed as creating any relationship whatsoever between City and Contractor's employees. Neither Contractor nor any of its employees is or shall be deemed to be an employee of City. Except as otherwise specified in the Contract Documents, Contractor has sole authority and responsibility to employ, discharge and otherwise control its employees and has complete and sole responsibility as a principal for its agents, for all Subcontractors and for all other Persons that Contractor or any Subcontractor hires to perform or assist in performing the Work.

R Dependable Const Inc.

Page 100 of 222 ends

.
.

Item 10 Page 102 of 369

17.06 SUCCESSORS AND ASSIGNS
The Contract Documents shall be binding upon and inure to the benefit of City and Contractor and their permitted successors, assigns and legal representatives.

A. City may assign all or part of its right, title and interest in and to any Contract Documents, including rights with respect to the Payment and Performance Bonds, to (a) any other governmental person as permitted by governmental rules, provided that the successor or assignee has assumed all of City's obligations, duties and liabilities under the Contract Document then in effect; and (b) any other Person with the prior written approval of Contractor.

B. Contractor may collaterally assign its rights to receive payment under the Contract Documents.

Contractor may not delegate any of its duties hereunder, except to Subcontractors as expressly otherwise permitted in the Contract Documents. Contractor's assignment or delegation of any of its Work under the Contract Documents shall be ineffective to relieve Contractor of its responsibility for the Work assigned or delegated, unless City, in its sole discretion, has approved such relief from responsibility.

Any assignment of money shall be subject to all proper set-offs and withholdings in favor of City and to all deductions provided for in the Contract. All money withheld, whether assigned or not, shall be subject to being used by City for completion of the Work, should Contractor be in default.

C. Except for the limited circumstances set forth in Paragraph 17.06-B, above, Contractor may not, without the prior written consent of City in its sole discretion, voluntarily or involuntarily assign, convey, transfer, pledge, mortgage or otherwise encumber its rights or interests under the Contract Documents. No partner, joint venturer, member or shareholder of Contractor may assign, convey, transfer, pledge, mortgage or otherwise encumber its ownership interest in Contractor without the prior written consent of City, in City’s sole discretion.

17.07 SURVIVAL
Contractor’s representations and warranties, the dispute resolution provisions contained in Article 15, and all other provisions which by their inherent character should survive termination of the Contract and/or Final Acceptance, shall survive the termination of the Contract and the Final Acceptance Date.

17.08 LIMITATION ON THIRD PARTY BENEFICIARIES
It is not intended by any of the provisions of the Contract Documents to create any third party beneficiary hereunder or to authorize anyone not a party hereto to maintain a suit for personal injury or property damage pursuant to the terms or provisions hereof, except to the extent that specific provisions (such as the warranty and indemnity provisions) identify third parties and state that they are entitled to benefits hereunder. The duties, obligations and responsibilities of the parties to the Contract Documents with respect to such third parties shall remain as imposed by law. The Contract Documents shall not be construed to create a contractual relationship of any kind between City and a Subcontractor or any other Person except Contractor.

17.09 PERSONAL LIABILITY OF CITY EMPLOYEES
City’s authorized representatives are acting solely as agents and representatives of City when carrying out the provisions of or exercising the power or authority granted to them under the Contract. They shall not be liable either personally or as employees of City for actions in their ordinary course of employment.

R Dependable Const Inc.

Page 101 of 222 ends

.
.

Item 10 Page 103 of 369
No agent, consultant, Council member, officer or authorized employee of City, shall be personally responsible for any liability arising under the Contract.

17.10 NO ESTOPPEL
City shall not, nor shall any officer thereof, be precluded or estopped by any measurement, estimate or certificate made or given by the City representative or other officer, agent, or employee of City under any provisions of the Contract from at any time (either before or after the final completion and acceptance of the Work and payment therefor) pursuant to any such measurement, estimate or certificate showing the true and correct amount and character of the work done, and materials furnished by Contractor or any person under the Contract or from showing at any time that any such measurement, estimate or certificate is untrue and incorrect, or improperly made in any particular, or that the work and materials, or any part thereof, do not in fact conform to the Contract Documents. Notwithstanding any such measurement, estimate or certificate, or payment made in accordance therewith, City shall not be precluded or estopped from recovering from Contractor and its Sureties such damages as City may sustain by reason of Contractor’s failure to comply or to have complied with the Contract Documents.

17.11 GOVERNING LAW
The laws of the State of California govern the construction and interpretation of the Contract Documents, without regard to conflict of law principles. Unless the Contract Documents provide otherwise, any reference to laws, ordinances, rules, or regulations include their later amendment, modifications, and successor legislation. If Contractor or City brings a lawsuit to enforce or interpret one or more provisions of the Contract Documents, jurisdiction is in the Superior Court of the County of Los Angeles, California, or where otherwise appropriate, in the United States District Court, Central District of California. Contractor and City acknowledge that the Contract Documents were negotiated, entered into, and executed—and the Work was performed—in the City of Vernon, California.

17.12 FURTHER ASSURANCES
Contractor shall promptly execute and deliver to City all such instruments and other documents and assurances as are reasonably requested by City to further evidence the obligations of Contractor hereunder, including assurances regarding assignments of Subcontractors contained herein.

17.13 SEVERABILITY
If any clause, provision, section, paragraph or part of the Contract is ruled invalid by a court having proper jurisdiction, then the parties shall: (a) promptly meet and negotiate a substitute for such clause, provision, section, paragraph or part, which shall, to the greatest extent legally permissible, effect the original intent of the parties, including an equitable adjustment to the Contract Price to account for any change in the Work resulting from such invalidated portion; and (b) if necessary or desirable, apply to the court or other decision maker (as applicable) which declared such invalidity for an interpretation of the invalidated portion to guide the negotiations. The invalidity or unenforceability of any such clause, provision, section, paragraph or part shall not affect the validity or enforceability of the balance of the Contract, which shall be construed and enforced as if the Contract did not contain such invalid or unenforceable clause, provision, section, paragraph or part.

R Dependable Const Inc.

Page 102 of 222 ends

.
.

Item 10 Page 104 of 369

17.14 HEADINGS
The captions of the sections of the Contract are for convenience only and shall not be deemed part of the Contract or considered in construing the Contract.

17.15 ENTIRE AGREEMENT
The Contract Documents contain the entire understanding of the parties with respect to the subject matter hereof and supersede all prior agreements, understandings, statements, representations and negotiations between the parties with respect to its subject matter.

17.16 COUNTERPARTS
This instrument may be executed in two or more counterparts, each of which shall be deemed an original, but all of which together shall constitute one and the same instrument. [END OF ARTICLE]
R Dependable Const Inc.

Page 103 of 222 ends

.
.

Item 10 Page 105 of 369
Bond No.: 18L006826
Premium Amount: $ 3,276.00
Bond's Effective Date: 4/2/2026

PERFORMANCE BOND
8Ee[4!g:

1. The Crty of Vemon, Califomia ('Cit/), has awaded to
R Deoendable Const lnc- 1019W 3rd Street. Ste B. San Bernardino. CA92410 (909) 381-2310 (Name, address, and telephone of Contracto0
('Principal'), a
Contracl (the 'Contract") for the Work descriH as
follows:

THEREFoRE, lor value received, We, Principal and
The Ohio Casualty lnsurance Company- 100 Liberty Way, Dover, New Hampshire 03820 (206\ 473-6210 (Name. address, and telephone of Surety)
("Surety'), a duly
By this Bond, We jointly and severally obligate and bind ourselves, and our respective heirs, executors, administrators, successors, and assigns to pay City the penal surn s1 One Hundred Twenty Six Thousand and no/100 Dollars ($ 126,000.00 )(the Bonded Sum"), this amount
comprising not less than lhe total Contract Sum, in lawful money of the United States of America The Licensed Agent lor Surety is:

Diamond Valley lnsurance Services, lnc-41856 lvy Street#'108 Murrieta, CA 92562 (951) 553-7400 (Name, address, and telephone)
Registered Agent's Calilomia Department of lnsurance License No. 0H94716 THE CoND|Tl0N OF THIS EOND'S oBLIGATION lS THAT, if Principal promptly and faithtully perrorms tre undertakings, terms, covenants, conditions, and agreements in the Conkacl and Contracl Documents (induding all their amendments and supplements), all wihin the time and in the manner hat those documents specify, then this obligation bemmes null and void. Otherwise, his Bond remains in full force and effecl, and he following terms and condilions apply to his Bond:

1. This Bond specifcally guarantees Principal's performance of each obligation and all obligations under the Contract and Contract Documents, asthey may be amended and supplemented including, but not limited to, Principal's liabilityfor liquidated damages, Warranties, Guarantees, Conection, and Maintenance obligations as specified in the Contract and Conkaci Contract No 202602'10: Vernon Citv Hall Third Floor Facilities Renovations in Vernon, CA.

2. Principal is requircd under the terms of the Contract and all mntract dooments referenced in it ('Contracl Documents') to fumish a bond guaranteeing Principal's taihful performance of the Work.

3. The Contract and Contract Documents, including all their amendments and supplements, are incorporated into this Bond and made a parl of it by this reference.

OBLIGATION:
admitted surety insurer under Califomia's laws, agree as follows:

EXHIBIT 1
R Dependable Const Inc.

Page 104 of 222 ends

.
.

Item 10 Page 106 of 369
Documents except lhat Surety's total obligation. as described here, will not exceed the Bonded Sum

4. An alteration, modifcation, dange, addition, deletion, omission, agreement, or supplement to the Contracl, Contracl Documents, or the nature of the Work performed under the Contract or Contracl Dodments including, without limitation, an extension ol time for perlormance does not, in any way, affecl Surety's obligations under his Bond. Surety waives any notice ol alteration, modification, change, addition, deletion, omission, agreement, supplement, or extension of time.

5. Surety's obligations underthis Bond are separate. independent from, and notcontingent upon anyother surety's guarante€ing Principal's faithful performance of the Work.

6. No right of action accrues on this Bond to any entity other than City or its successors and assigns

7. lfan aclion al lawor in equity is necessary to enforce or interpretthis Bond's terms, Surety must pay in addition to the Bonded Sum City's reasonable attomeys' fees and litigation costs, in an amount the murt fixes.

8. Surety shall mail City written notice at least 30 days before: (a) the effeclive date on which the Surety will cancel, terminate, or withdraw from this Bond; or (b) this Bond becomes void or unenforceable for any reason.

2. For those obligations of Principalthat survive FinalCompletion of the Work described in the Contracl and Contracl Documents, the guarantees in this Bond also survive Final Completion of the Work.

3. When City declares that Principal is in default under the Contract, or Contract Documents, or both, Surety shall promptly: (a) remedy the default, (b)complete the Projecl according to the Contracl Doflments' terms and conditions then in eflecl; or (c) using a procurement methodology approved by City, select a contractor or contractors acceptable to City to mmplete all of the Work, and anange lor a conkact betv'/een the conkacto(s) and City. Surety shall make available, as the Worl progresses, sufticientfunds to pay the cost of mmpletion less the balance of the Contract Sum, and to pay and perform all obligations of Principal under the Contract and Contract Doorments including other costs and damages for which Surety is liable under this Bond except that Surety's total obligation, as described here, will not exceed the Bonded Sum. lsignatures to this Exhibit 1, Performance Bond, Begin on Next Pagel R Dependable Const Inc.

Page 105 of 222 ends

.
.

Item 10 Page 107 of 369
On the date set forth below, Principal and Surety duly executed this below and signed by its representative(s) under the authority of its goveming body oa.€ Aptil 2,2026

PRINCIPAL
R Dependable Const Inc
with the name of each party appearing
SURETY
The Ohio Casualty lnsurance Company
ature)
By:
(Name and Title)
Address for Serving Notices or oher Documents
100 Liberty Way
8y
(Signature
Rosemary Padil dent
San Bernardino, CA 92410 Dover, NH 03820

CORPORATE SEAL
THIS BOND MUST BE XECUTED IN IRIH.IAIE.

EVIDENCE MUST BE ATTACHED OF THE AU|HORITY OF ANY PERSOIV S/GN/NG AS ATTORNEY-iIV-FACI.

THE ATTffiNEY.,IN+ACIS S/GIVAIURE MUST tr NOTARIZED,
A CORPORATE SE/( MUSI EE /MPRESSED ON THIS F@M WEN THE PRII'ICIPN- OR IHE SUREry OR NTH, ARE A CORPORANA{

APPROVED AS TO SURETY AND
AMOUNT OF BONOED SUM:

APPROVED AS TO FORI\4
By: By
Daniel S. Wall, oirector of Public Works / City Engineer Zaynah l\,loussa-i4ilward, City Attomey Karen A. Eby, Attorney-in-Fact
(Company Name)
(Name and Tille)
Address for Serving Noties or Olher Doorments:
1019 W. 3rd Street, Ste B.

CORPORATE SEAL
R Dependable Const Inc.

Page 106 of 222 ends

.
.

Item 10 Page 108 of 369

BOND ACKNOWLEDGMENT
FOR
SURETY'S ATTORNEY.IN.FACT

STATE OF CALIFORNIA

COUNTY OF
0n this _ day of _,20-,
before me, iname), a Notary Public for said County, pemonally appeared (name), who proved to me on the basis of
satisfactory evidence to be the person whose name is subscnbed to this instrument as the attorney in fact of and acknowledged to me that heishe subscribed the
name of thereto as principal, and his/he own name as
attorney in fact

SEE ATTACHED
Notary Public
SEAL
SS
I certi{y under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
)
)
)
R Dependable Const Inc.

Page 107 of 222 ends

.
.

Item 10 Page 109 of 369
Thi6 Por.r o, Atiomey limiL th. .cl5 ol thore n.med herein, and thay haya no authority to bind the Company ercept in the mannor and to the d&nt herein 3Gtad.

KllOWtl ALL PERSOiIS BY THESE PRESENTS: That The Ohio Casually lasurance Company is a @rporation duly organized under th6 law6 of lhe Slale of New Hampshire that tsaker.l\arcn A t,b\ K\le I llakcr Irmorh!( llakcr
all of he cjty ol state ol oad individually if here be mo(e han one named. ils t ue and lawful attom6y'in -fact lo make, of h€s€ p@s€nb aod sha[ be ao binding upoo he Companies as if hey have been duly signod by Ule Fesrd@t aod atesbd by hs sscrelry ot ho Compani€s h har own proper p€,sq|s.

N WfrIESS WHEREOF, his Pow€r ol Attomey has b€€n subs(iibed by an auho.ized oficor or oficial of $e Cornp€nies 8nd fto corporste sesls ol h6 Coopani6 hav€ b€€n afixed he,eto tis I I th day of May , 2022
Libertv
Mutudl. Certfficate No 8208023-987721

SU RETY
nsulanca Company
alty lnsurdnce Cocpany
lns!rance Cnnpany
By
David lt{ Carey Assistant Secretary
Sbte of PENNSYLVANIA
County of ITONTGOMERY
SS
Or t s I llh day oI May , -?!3L b€lore me persoally appeared Davij M. Car6y, who ackno$ledged hims€ll to b€ the ksislant S€.fetary ol Uberty l'&tual lnsuranco Colnpany, Tho Ohao Casualty Company, and W€6t Ameflcln lnsuran@ Company, and that he, as sudr, being authoriz€d so to do, er€@to the toregoing instrument for tle porpo6es h€rein coriainod by sbning oi behalf ol he corporaliois by himself as a duly autho.ized offc€r N WfTilESS WIiEREOF, I hale hereunlo s!b6{nb€d my name and aftu6d my nobdal seal al King of Prussia, Pennsy'vania, on he day and year flst abo,re writlen.

Lberty lttutual I
The ohio Casu
Cdil!1@fi ol P.nn.rvs6 . irobry Sdl
I.@ Pet€{., iJot ry Puhl'c
Mdtgoffiy Cou y
My @m6sbn exp'6 ira.n 28, m25
Cqrrltlss rumt 112@ar
By /-r/L
M.tr'td P s,1v . asr6 oi r.r.r,6 eresa Pastella Nolary Puuic This Povr€( ol Atkrney is made and erecut€d purslant lo and by auhority ol he lollowing By]aws and Auhorizaticns ol The Ohio Casualty lnsunncs Company, Lib€rty Mufual lnsurance Company 6nd West Amdican lnlurance Coanpany whidr resolutions are now in full lorce and efiect reading as follons:

ARTICLE lV - oFFICERS: Sectioo 1 2. Por6r ol Aromey.

Any omce( or oth€r offoal ol be Corpo.aton auhoriz€d fo. tlat purpc€ in writng by he Chairman q the Pr€6ident and subj€d to sudr limitaion as $e Channan or lhe Presld€nl may p.esaribe, shall appont sudr atto.n€ys'in-hd, as may be necessar to acl an behalf of lhe Coaporalioi lo male, exeorle, seal, acknoxledge and deliver as sorev have full pouer to bmd he Corporation by her s0naturc and oxeortoi of any sudr instuments and lo attadr hereto he soal ol the Corporation. !ryhen so ereqrted, sudr iostrumenk shall be as binding as if signed by the President and atlosled lo by $e S€crgtary Any porver or authority g€nted to any rpr6entativs or attomeyjn-facl under lhe provisions of tis artide may be revoled at any tme by he Bosrd. lhe Chaiman, bo Presidenl or by fie oficar or oficers grantng slch porver or aulho.ity ARTICLE Xlll - Etecution of Contactl kioo 5 Slrety Bonds and Und€rtakirEs.

Any ofcer of he Co,npany auho.rzed for hat purpGe in rriting by he dairman or be president, and sub,ed lo sudr lim atons as he chajtman or oie pretijat may presoibe, shall appornt sudr attomeys-in'lad as may b€ n€c€ssary to act in behaf ol he Company lo male, ercorto, se3l, adnord€dgo and deliver as sur€ty any and all undertakings, Company by heir signaturc and exeqrtoi of any such instrumenls and to attach thBreto hs soal ol lhe Company. When so exeorlod Surh indruments shall be as binding as il signed by the president and attested by he soqotary.
obligallons.
tle same lorce and effed as tDugh manually aftued
has nol been revoked
Itl TESTIMONY WHEREOF, lhsve hereunlo set my hand and affixed lheseals of said Companies has lnd day of April 2026 1S'12 t
\NS
1919
.i
199't
\NS
t
q)
o)
c
g
N
f
o
::
o
o
-
!
E
o
o
(E
o
o
c
o
(E
l
o
oo
0)
_q
c
(o
_9
o,)
o
c
o,)
c')
C, o) E
o
E
p
o
I PAs
U;E qe
=ECF
EE
o (cl, >dz
*,--
dLJ
--q6
o;
<5
E*
+36o
o=
oo
,(E5,a
LL O.
1912 I
't919 a
*l
LMS-I2873 LMIC OClC WAIC Mult co 0221
By:

Renee , Assislant Secretary
Liberty Mutual lnsurance Company
The Ohio Casualty lnsurance Company
West Americ€n lnsurance Company

POWER OF ATTORNEY
1991
R Dependable Const Inc.

Page 108 of 222 ends

.
.

Item 10 Page 110 of 369
GALIFORNIA ALL. PURPOSE

CERTIFICATE OF ACKNOWLEDGMENT
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.

State of California
Riverside
On 2nd Aptil2026 before me. Marco Emmanuel Vega. Notary Public @
personally appeared Karen A. Eby
who proved to me on the basis of satisfactory evidence to be the persor(s) whose name(e) is/are subscribed to the within instrument and acknowledged to me that -helshe/they executed the same in+idherlthek authorized capacity(ies), and that by -hie/herAheir signature(e) on the instrument the person(s), or the entity upon behalf of which the person(€) acted, executed the instrument.

I certiff under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correcl.

WTNESS my hand and oflicial seal
rrrco EnA [Et rrEo^ w.1wr16
t{ot^Fl PUE rc . ctlrfosr^
FIVER}IOE @I'NTY
Itcol EpTRES JIIUfiY 25 2!O
qt
='o
N ublic Sig (Notary Public Seal)
ADDITIONAL OPTIONAL INFORMATION INSI'RI.JCTIONS F'OR COMPLETINC I'HIS FORM thtslot t co,tpli.tirt M. Calilorniastottt s rcgedrng mtat vcdt,g @td, if n .d.d. sleuu b. con*kd @td ottqLt to te bc1ai.n. Acb, Ldtn atr Iton o.ls ttar.s nat b. .@tpLkdfot docui.nts b.ng En! to tlet ttot. e lory cs th. |9o.diq da.s rut rcqurc e Calihnta ,ptoy to violoE Califotuo noiay . Srare aJld County information must be lh€ Slale and County where the deum€nl signe(s) personally rppearcd b€forc lhe norar-y public for acknowledgmenl . Date ofnohnzarrcn musl b€ rhe date lhat lhe srgner(s) peEonally app.arcd which musl also be lhe sam€ dale thc acknowledgmenl rscompleted . The nolary public musl prinl his or her nane as rl app€ars wirhin his or her commission tbllowcd by a comma and lh€n your lille (notary publrc) . Prinr fie namqs) of documenl signe(s) who pcrsonally aprrear al lhe trme of . Indicale rhe correct singular or pluEl foms by crossinS oll incor.ecl foms (i c hc/she/rhet:
's
/6.. ) or circling lhe correcl foms Farlur€ to coneclly rndrcalelhas inlbrrnarion may lcad lo re.jc.xon ofd$umeni recording
. The Dotary seal impression mu$ bc clear aDd pholoSraphically r€produciblc lmpressron must not cover lexl or lin€s. If*al imprcssion smudgcs. rc'*al if a sufficienr ar.a pcrmils, olhesr$complele a differcnl aclnowl€d8meni form . Signalurc oflhe nolary publE musl malch fie siSnalure on filc wilh lhc oflice of C Addrnonal rnformation is nol r€quired bul (ould help lo ensur€ lhrs acknowl€dgmcnl is nol mtsused or alached lo a dilIerenl do.umenl. + lndicale Iille or type ofaltachcd documenl, number of pages and date 3 lndicale th€ capacity claimed by th€ srgncr. If lhe claimed capacitv is a corporale officer, indicale lhe lille (ie Cli(). CFO. Secrelary) . Securely atrach lhrs documenl lo thc signed documcnl wilh a st pl€

DESCRIPTION OF THE ATTACHED DOCUMENT
(Tille or descipton ol allached doarmenl)
(Ti[e or descflplon ot attach€d docunpnl conl]nLred)
Number of Pages _ Document Dale_
2015 VeBion Lvtvw.NotaryClass8 com 80G8719865
County of
)
)

CAPACIW CLAIMED BY THE SIGNER
tr lndividual(s)
E Corporate ofricer
-fiifie-l-- D Partne(s)
X Anomey-in-Facl
B Trustee(s)
- Other
R Dependable Const Inc.

Page 109 of 222 ends

.
.

Item 10 Page 111 of 369
A notary public or other officer completing this certificate verifies only the identity of the indMdual who signed the document to which this certificate is attached, and not the truthfi,rlness, accuracy, or validity ofthat document.

State of Califomia
County of San Bemardino
Qn April 6l}:,. 2026 before me. Damaris Abigail Lara Ramos (Here insert name and title ofthe otficer)
personally appeared Roscmary Padilla
who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in hisiher/their authorized capacity(ies), and that by his,4rer/their signature(s) on the instrument the person(s), or the entity upon behalfof which the person(s) acted, executed the instrument.

I certiff under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and corrcct.

WITN hand and ofli al. DAljARIS AB]GA1L LARA RAIIIOS
coMM. #244A47 3 my
(Norary Seal)
IIOTARY PUBI.IC " CAI.IFORTJIA
SA BTNI'IAROIiIOCOUNTY
My &mn ixprres lray i0, 2027
S
CALIFORNIA ALL.PURPOSE

CERTIFICATE OF ACKNOWLEDGMENT

DESCRIPTION OF THE ATTACHED DOCUMENT
Performance Bond
(Title or descriplion of atlached document)
(Title or description of atiached documeDt contidued)
Number ofPages _ Document Date_
Nor. Two riSFr@s dc b.inS.olead wrthin. rnsle demenr
( Addnronal rnlbrmarion)

ADDITIONAL OPTIONAL INFORMATION

INSTRUCTIONS FOR COMPLETING THIS FORM
A t ackfiotelcdgfient conpleted ih Calilornia nust contain rerbiage e:\ac r ts appears above it the notan lsection or a separate acknowledgment lbrn must be properlv conpleted and anached to that docwnent The onlt etception is d o document i.t b be recorded outside oJ Colilbnia. In such instances, anr ahenative acknowledgment verbiage as naj be pinted on such a documenr so long as the vthiage does not rcquire rhe noran' to do somethins that is illegal lor a notary in Calilornia (i.c. cefiif|hg the authorized Lapdcir^ of the signet). Plcase check tlrc docunent carelully lor proper notiriul rordu't and uroch this forn Irequirud. . State and County information musl be lhe Slate and County where the document signe(s) personally appeared before the notary public for acknowledgmenl. . Datc ofnotarization must bc lhe datc lhal thc signcr(s) pcrsonally appcarcd which must also bc the same datc the ackno\rledgment is complctcd. . Thc notary public must print his or hcr namc as it appcars withio his or her commission followed by a comma and then your title (notary public). . Print the name(s) of document signc(s) who pcNonally appear at thc time of notarizatron.
. lndicate the correct singular or pluml forms by crossing off incorrect forms (i.e. he/she/rl*y- rs ere ) or circling thc conect tbrrns. Failurc lo correcdy indicatc ihis inlbrmation may lcad to rcjection ofdocumcnt rccording. . Thc notary seal imprcssion must be clcar and photographically reproducible. lmprcssion must not covcr text or lines If seal imprcssion smudgcs. re-scal ifa sufficienl area permits, otherwise complete a different acknowledgmenl form. . SigEturc ofthe nolary public must match the signature on file with lhe office of lhe county clerk.
* Additional information is not required but could help to ensure this acknowlcdgmcnt is not misused or attachcd to a differcnt documenl. .l Indicate tille or type ofallached document, numb€r ofpaSes and date. .! Indicsle the capacity claimed by the signer. Ifthe claimed capacity is a corporatc officer, indicate thc tillc (i.e. CEO. CFO. Sccreury). . Securely attach this document to the signed document

CAPACITY CLAIMED BY THE SIGNER
tr Individual (s)
n Corporate Officer
(Tirle)
n Partner(s)
fl Aftomey-in-Fact
E Trustee(s)
E other
2008 Version CAPA vl2-10.07 tl00-871-9865 www.NotaryClasses.com R Dependable Const Inc.

Page 110 of 222 ends

.
.

Item 10 Page 112 of 369
EXHIBIT 2
Bond No: 181006826

PAYMENT BOND
(LABOR ANO MAIERIALS)

RECITALS

1. The City of Vernon, California ('City"), has awarded to R Oependable Const lnc- 1019 W 3rd Street, Ste B. San Bernardino, cA 92410 (909) 381-2310 (Name, address, and telephone of Design-Builder)
(.Principal'), a
Contract (the "Contracl") for the Work described as follows:

Contract No. 202602'10: Vemon Citv Hall Third Floor Facilities Renovations in Vemon, CA

2. Principalis requted under California ejyi!eldg Sections 9550-9566 and the terms ofthe Contract and allcontracl documents referenced in it ("Contracl Documents') to fumish a bond guaranteeing Principal's paying claims, demands, liens, or suits for any u,ork, labor, services, materials, or equipment fumished or used in the Work.

3. The Contract and Contracl Documents, including all their amendments and supplements, are incorporated into this Bond and made a part of it by ttris reference.

OBLIGATION:

THEREFORE, Ior value received, We, Principal and
The Ohio Casualty lnsuranc€ Company- 100 Liberty Way, Dover, New Hampshire 03820 (206)473-6210 {Name, address, and telephone of Surety)
and assigns to pay City the penal sum of One Hundred Twenty Six Thousand and no/100 Dollars ($ 126.000.00 ) (.the Bonded Sum"), this amount comprising not less than the total Contracl Sum, in la$/fu| money of the United States of America.

The Lic€nsed Agent for Surety is:

Diamond Valley lnsurance Services, lnc.-41856 lvy Street# 108 Munieta, CA92562 (951) ss3-7400 (Name, address, and telephone)
Registered Agent's California Departm entof lnsurance Licenss lrlq. 0H94716 THE CONDITION 0F THIS BOND'S OBLIGATION lS THAT, if Principal or a subcontractor fails to pay (a) any person named in Califomia Civil Code Section 9100, or any successor legislation; (b) any amount due under California's Unemployment lnsurance Qgglg, or any successor legislation, for wcrk or labor performed under the Contract or Contract Documents; or (c) any amount under.U!!.gtrpL9yEgltL0s.glalE @!q Seclion 13020, or any successor legislation, that Principal or a subcontraclor must deduct. withhold, and pay over to the Employment Development Department from the wages ol its employees, tor work or labor performed under the Contract or Conkact Documents, then Surety shall pay for the same in an amount nolto€xceed the Bonded fum.

Ohenvise, his obligation becomes null and void. While this Bond remains in full force and efiec1, the following terms and conditions apply to this Bond:

Premium Amount: S 3,276 00
Bond s Etfeclive Date: 41212026
("Surety"), a duly
admitted surety insurer under Califomia's laws, agree as follows:

Bythis Bond, We jointly and severally obligate and bind ourselves, and our respective heirs, executors, administrators, successorli, R Dependable Const Inc.

Page 111 of 222 ends

.
.

Item 10 Page 113 of 369

1. Tlis Bond inures to he benefit of any of the persons named in Calilomia Civil Code Section 3181, or any successor legblation, givhg hose peGons or hdr assigns a rEht d adion h any suit hught upon his Bond, unl€ss Califomia Civil Code S€clion 3267, or any successor legislation, applies.

2. An alteration, modification, drange, addition, deletion, omission, agreement, or supdement to the Contract, Confad Documents, or the nature of the Work performed under the Contract or Contracl Documents including, without limitation, an extension of time for perlormance does not, in any way, affect Surety's obligations under his Bond. Surety waives any notice of alteration, modification, change, addition, deletion, omission, agreement, supplement, or extension of time.

3. Surety's obligations underthis Bond are separate, independent from, and not contingent upon any other surety's paying clarms, demands, liens, or suits for any work, labor, services, materials, or equipment fumished or used in the Work.

4. lf an aclion at law or in equity is nec€ssary to enlorce or interpret tris Bond's terms, Surety must pay in addition to the Bonded Sum City's reasonable attomeys' fees and litigation costs, in an amount the court frxes.

5. Surety shall mail City witten notice at least 30 days before: (a) the effective date on whicir the Surety will cancel, terminale, or withdraw from this Bond; or (b) this Bond becomes void or unenforceable for any reason. to this on Next
R Dependable Const Inc.

Page 112 of 222 ends

.
.

Item 10 Page 114 of 369
on the date set forth below, Principal and Surety duly executed this f, witfr ttre name of each party appearing below and signed by its representative(s) under the authorjty of its goveming body. grq. April 2, 2026
SURETY:

The Ohio Casualty lnsurance Company
(Company Name)
(Signatu
Rosemary Padilla, resident
N
ature)
By By: Karen A. Eby, Attorney-in-Fact
(Name and Title)
Address br Serving Notbes or oher Documenb
1019 W. 3rd Street, Ste B.
(Name and Title)
AddEss for Serving llotbes or Qher Doarrnenb
100 Liberty Way
San Bernardino, CA 92410 Dover, NH 03820

CORPORATE SEAL CORPORATE SEAL
7HIS 8oND MUST BE xECUTED IN TRIftlUTE
EVIDENCE MUST BE ATTACI,ED ff THE AUIHORIry OF ANY PERSOV S/G'V/'VG AS ATTOR'VEYJN+ACii IHE ATTffiNEY.IN-FACTS $G/VAIURE MUST BE NOTARIED,
A CORPOR4IE SE4t MUSI EE IMPRESSED OI THS FqM WHEN THE PRINCIPAI- OR IHE SURET}1 OR WTH, ARE A ffircRATION.

APPROVED AS TO SURETY AND
AIIOUNT OF BONDED SUM:

APPROVED AS TO FORM
By: By
Daniel S. Wall, Director of Public Works / City Engineer Zaynah Moussa-Milward, City Attomey PRINCIPAL:

R Dependable Const lnc
R Dependable Const Inc.

Page 113 of 222 ends

.
.

Item 10 Page 115 of 369

BOND ACKNOWLEDGMENT
FOR

SURETY'S ATTORNEY-IN-FACT

STATE OF CALIFORNIA

COUNTY OF
On this _ day of _,20-,
before me, lname), a Notary Public for said County, pensonally appeared (name), who proved to me on the basis of
satisfactory evidence to be the person whose name is subscribed to this instrument as the attorney in fact of, andacknowledgedtomethathe/shesUbscnbedthenameoI-thereto as principal, and his/he own name as attorney in fact.

I certify under PENALTY 0F PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

SEE ATTACHED
Notary Public
SEAL
SS
)
)
)
R Dependable Const Inc.

Page 114 of 222 ends

.
.

Item 10 Page 116 of 369
Libertv
Mutudl.

Thii Pover of Attomey limits the acts ofthose lamed herein, and they have no authorityto bindthe Company ercept in the ftanner andto theertent herein slaled.

Liberty Mutual lnsurance Company
The Ohio Casualty lnsurance Company
West American lnsurance Company

POWER OF ATTORNEY
certrfc€teNo 8208023-987721
SURETY
K[Oml ALL PERSOIIS 8Y IHESE PRESErTS: ftat The Ohio C6ualty lnsurancs C{.npany is a corporatjon duly organized unde. tle la93 of he Slate of Nsn H.mpshir6, hat under ths Lws ol U|e Slsb of lndiana (hqsn cdleciively €lled h€'Companiss"), Brrsuarl to and by auhority hedn s€t rorh, does hereby name, cqElilute and appont, Ashlcr- N Baker. [aren A Eb]. K] le I' Baker. 'l rmoth\ C Bakcr
all ol he oty of slate ol eadr individualt d tlere be mde han one naned it5 true and larful attom€y.ln-fad lo make of h€se Fe.€nb and shall be as bindrrE upoi 0le Compa[6 as rf h€y have b€ei duly soned by fE F6id€ht and at€sbd by tl6 ssqetary ol he Compar es in hdr own prq€r p€rsqls.
lta WTTIIESS VYHEREOF, h6 Po{er ot Atomey has b€ql sub6dib6d by ar auho.ized oficei or offcial of he Cornpanies and he corporab s€als of f€ Companios have beei afted hereto tis I lrh dayof N,lar l{)l:

Uberty ifutral lnsurance Compay
'Ihe ohio C6ualty lnsurance Company
West Ameican lnsurance Coflpa ny
David M. Carey Assistanl Secretary
Slate of PENNSYLVANIA
County oTMONTGOMERY
SS
On his I I th day of May , 20, bebrc me porso.rally appeared oavid M Carey, who aclnovJedged hims€lf to be the As5istant S€qetary of Liberty ltubd lnsurance herein conhin€d by signing on HEll of lh€ corpo{atios by himsollas a duly authoriz6d oficer.

N Wf ESS WHEREOF, I have horarnto subsdibod my name and alfixed my notaial seal at King of Prussia, Pennsylvania, on 6e day and year first aborro written Cmll]l)MalIn o{ Pcnnsyrv 6 - l.Lrary S€.1
T6cs Paletta. Nota, PublE
Mdrom6ry counry
My @mr!s et,'6 lracr' 28 2025
ComisM .ufib€. 11250,t4
By: /-fr/L
M.n$.r. P.msyrv.n,. A!@h onro&B eresa Pastella, Notary Public lnsuran@ Compary, and W6t fundic€n lnsurance Ccrnpany rhidr r€6dutians are no,l jn full fdce and efiect reading as fdlo,vs:

ARTICLE N-OFFICERS: S€clim 12. Pder ol Attorney.

Any ofica, or odler olfual of 0|€ Cdporatioo autroailed lor hat Firpoe6 in writrru by he Chaiman or fE Pr6ident and subjed to sudr limrlation as he Chairman o, he Pr6id€nt may Fosoibo, shall appdnt sud storney+injad, as may be n€aaasary lo acl in bdlalt of he Corpoaaliq to make, BxsqJte, s€al, acknotlodge and ddiver as $rrety have full poll€( to Und fie Corpo.atql by hei sEnatre and ereolion of any $dr insuumenb ad to atladl tr(eto tre s€81 of tle Corpor.lioo. When .o exeqJted, slldr provisiois of tis dlide may be revoked al aly tm€ by tlo Board. tE Charrman, he Pr€sid€nt or by he ofic€r oa oficers granting $rdr po*!a o( autffiy.

ARIICLE Xlll - Er.cutior ol Cod.ct r S€c1ici 5. Suroty Eords and Undertakings shall appcrl sud! altorneyemjact as may be necsss€ry to ad io bdlaf of he Company to make, eredrle, sed, aa*nq*ledge and ogiver as s{,rety ati and all undertslings, stnod b, h€ E€srd€rlt and at€sted by 016 se.,etary
odEalbns.
he same lorce aM efiect as hoogh manually affxed.
l, Renee C Llfl€ilF, he und€rsigoed. fusbtant S€detary, The Ohio Casualty lnsurance Company, Lib€fty Mutual lnsurance Company, and We6t Amencan lnsurance Company do has nol b€en r6voked.
lN TESTIIilONY WHEREOF, I hsw her€unlo ssl my hand and afirod lh6 s€als ot said Companies hb 2nd day of April ,2026 \l'lS
I
1919 1991
\NS
oq)
c
o
go, (JO
.(tr 6>
ES
-13
=639
do
CE
Oor 9f Itr !u o);i
cLo)
o(E
!>.
(E. >o
o=zd
e
PAs
uiE oo
:=q
AE
.-J
CF:

EEEE
(r, (dl >d
*,-^
[(J
q6
.96 <6
:o
;e
66 !=
o(D
6_q LL O.
1912 t
\NS
1919
1Y \NSU
u
LMS-12873 LMICOCIC WAIC Mult Co 02/21
enee yn
By:
1912
1991
By:

R Dependable Const Inc.

Page 115 of 222 ends

.
.

Item 10 Page 117 of 369
CALIFORNIA ALL. PURPOSE

CERTIFICATE OF ACKNOWLEDGMENT
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document. )
County of )
Riverside
On 2nd Aptil2026 before me, Malgg Ernmanlg! Vega, Notary Public lFoE n*nnm &dtFdlto-liar
personally appeared Karen A. Eby
I certify under PENALry OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct
WTNESS my hand and official seal.
r rco EHAXLEL VEOA O I.rr2tlot6 r€lrtt Pt t lc . c{tFomtu ST'C CdJNTY
ttflED|Bu*JlfrY6,20!
q, I
lfuodtfu
NoErt Public Sigry[(?E (Notary Public Seel)
ADDITIONAL OPTIONAL INFORMATION INSTRT]CTIONS FOR COMPLEI'ING I'IIIS lroRM IhBlod coDtplies rrth t tu Caliloraa statu.s t.gordrng rcto7 vorAng ard. {n..d.4 shotld be .odplct d o,td otocld to E do.1,?t nt. Act ovledsn.ds lfon onu tbtcs nq be codpLtedfo. drln. s b.ingsent to d,at s,ale so lo.W as ls w<*dtry dd! Nt requre tt Cal'[Mo Mtoy to rolor. Cdforuo not@y . Slaie and Coutu_
'nlbmalion
mun be lhc Slale and Counlv where lhe dorumenl
DESCRIPTION OF THE ATTACHED DOCUI\,4ENT
(Tille or des.ipliofl oI att&hed documenl)
(Ti0e 0r desdiplion ol afached doclfirnt continued)
Number of Pages _ Document Dale_
siSne(s) pe6on.lly app€arEd befoE lhe nolary public for acknowledgnenl t at€ ofnolarizaiion musl bc lhe dale lhai lhe signe(s) peEonally appeared *.ltich mu$al$b€ the same dalc the actnowledgment rscompleled
Thc nolary publac musi p.int his or her nme as n app€ars withrn h6 or hcr commilsjon followed by acomma and then your liile(noiary public) Pnnr lhe namqs) of documenr surE(s) sho personallv app€ar ar Ihe rime of lndicare lhe corrccl srngular or plural fomx by crossing olT incorftcl foms 0 c hcshe/@- is /e€ ) orcirclrnS rhe corre(I forms l-ailure ro correcrly indicat€ lhis informalion may lead to rejoction ofdocumcnl r€cording. 'I-he nolary seal impression mu$ be clear and phorographically reproducible Impftssrcn musl nol cov€r lexl or lrnes ltseal rmpressron smud8e! re'$al if a sufficrentarea pemlils, otherwisc complclc a dificrent acknowl€dgmenr Ibrm SrSnalurc ofth€ norary public musr malch the signalure or lile wrrh the offce of I Add onal rntbrmation is nol .cqutcd but could help lo ensurc lhis acknowledSmenr is nor msusd or atEched roadillcr€nr dGumenr a lndicarerirlc or typc ofanached dffumenl, number ofpagcs and date + lndicde lhe capacily clarmed by lhe siSncr If lhc clarm.d capacrlv is a corpoate offic€r. indicare lhe iirle (r € CIjO. Cl-O. Secrelary) Securely atrach rhisdocume ro rhe siSncd docunr€ntwith s stapl..

CAPACITY CLAIMED BY THE SIGNER
0 lndividual (s)
E Corporate Ofricer
(ri{Er
Partner(s)
Attomeyin-Fact
Trustee(s)
Other
tr
x
tr
tr
2015 Version w\iu,v. NotaryClasses. com 80()-873-9865
State of California
who proved to me on the basis of satisfactory evidence to be the person(9 whose name(e) is/are subscribed to the within instrument and acknowledged to me that -helshe/they executed the same in-his;/herltheir authorized capacity(es), and that by -his/herltheir signature(s) on the instrument the person(s), or the entity upon behalf of which the person(+acted, executed the instrument.

R Dependable Const Inc.

Page 116 of 222 ends

.
.

Item 10 Page 118 of 369
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certilicate is attached, and not the truthlirlness, accuracy, or validity of that document.

State of Califomia
County s6 San Bemardino
Q1 April 6$.2026 before me, Damaris Abigail Lara Ramos
(Here insert dame and title ofthe officer)
personally appsa1q6 Rosemary Padilla
who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capaciry(ies), and that by his,/her/their signature(s) on the instrument the person(s), or the entity upon behalfof which the person(s) acted, executed the instrument.

I certifu under PENALTY OF PERJURY under the laws of the State of Califomia that the foregoing paragraph is true and correct.

WITN S my hand an seal DAI\IARiS ABIGAIL LARA RAillt)S
(Notary Seal)
coMM. #2448473
II{)'IARY PUBI-IC - CALIT{]RIIIA
SAll EtRr\AEl,)ll'{0,.lCUiliY
fily Conll1. Irl]i,rs ]",l y i1) 2127

ADDITIONAL OPTIONAL INFORMATION

DESCRIPTION OF THE ATTACHED DOCUNIENT
Payment Bond
(Title or description of attached documen,
(Title or descriptioD of a(ached document continued)
Number ofPages _ Document Date_
Note: T$o jgDlws e beins mldzed wirhr ae'ngl€d@denr
(Additional information)

CAPACITY CLAIMED BY THE SIGNER
n Individual (s)
n Corporate Officer
(Title)
tr Partner(s)
n Attomey-in-Fact
tr Trustee(s)
n Other

INSTRUCTIONS FOR COMPLETING THIS FORM
,4nt achlowledgment completed in Calilbrnia nust conhin verbiage e ctl,r as appears abow in the not.try section or o teparate dcknowledgnent lbm nust be prcperly completed and attached to that .locunent. The onb' exception is il a docunent is to be recorded outside of Calilinia. In such instances, any oltematiye acknovledgment verbiage as nay be pnnted on such a document so long as rhe vethiage doe: not require the notan, to do somethihg thot is illegal for a norary in Caldornia (i.e. certil\itg the authoized .apaciry- of the signe4. Pledse Lheck the docu,nent cnrclillly lbr proper noturial $ording onl duch this forn if rett iretl.

State and County information must be the State and County where the document signer(s) persoDally appeared before the notary public for acknowledgment.

Datc ofnotanzation must bc thc datc that thc signcr(s) pcrsonally appcarcd which must also be the same date the acknowledgment is completed.

The notary public must print his or her name as it appears within his or hcr commission fbllowed by a conma and then your title (notary public).

Pint thc namc(s) of documcnt signc(s) who personally appear at the time of notarization.
. Indicate the cofiect singular or plural forms by crossing off incorrect forms (i.e. he/she/rheyr is ,are ) or circling the correct fbrms. Failurc to corrcctly indicate this inforrnation may lead to rejection ofdocumcnt rccording. . The notary seal impression must be clear and photo$aphically reproducible. lmpression must not covcr tcxt or lincs. lf scal impression smudgcs. rc-scal if a sufficient area permits, othenvise complete a differenl acknowledgment form. . Signature ofrhe notary public must match the signature on file with the oflice of the county clerk.
* Additional information is not required but could help to ensure this acknowlcdgmcnt is not misuscd or attached to a different documcnt. .,. Indicate title or type ofattached document. number ofpages and date. .8. Indicate the capacily claimed by the sigrer. If the claimed capacity is a corpomlc officcr. indicate the title (i.e. CEO. CFO. Sccrctary). . Securely atlach this document to the signed document
CALIFORNIA ALL.PURPOSE

CERTIFICATE OF ACKNOWLEDGMENT
2008 Version CAPA v12.10.07 800-873-9865 www-NotaryClasses.com R Dependable Const Inc.

Page 117 of 222 ends

.
.

Item 10 Page 119 of 369
EXHIBIT 3
Bond No: 18L006826
Premium Amount: S 3 276 00
Bond's Effective Date: 4/2/2026

MAINTENANCE BOND
RECITALS:

1. The City of Vemon, California ("City'), has awarded to R Depe4llable Cotst lnc- 1019W.3rd Street, Ste B. San Bemardino, CA92410 (909) 381-2310 {Name, address, and telephone of Contracto0
("Principal'),
a Contract (the 'Contract') lor the Work described as follo\,vs:

Contract No. 20260210: Vemon Citv Hall Third Floor Facilities Renovations in Vemon, CA

2. Principal is required under the terms of the Contract- and all contract documents referenced in it ("Contract oocuments"F alter completion of the Work and before the filing and recordation of a Notice of Completion forthe Work, to fumish a bond to secure claims for Maintenance equal to ten percent ('10%) of the total amount of the Contracl Which shall hold good for a period of one (1) year from the date the City's Notice of Completion and Acceptance of the Work is filed with the County Recorder, to protect the City against the result of faulty material or workmanship during that time.

3. The Contract and Contracl Documents, including all their amendments and supplements, are incorporated into this Bond and made a part of it by this reference.

OBLIGATION
THEREFoRE, for value received, We, Principal and
The Ohio Casualty lnsurance Company- 100 Liberty Way, Dover, New Hampshire 03820 (206) 473-6210 (Name, address, and telephone of Surety)
admitted surety insurer under Califomia's laws, agree as follows By this Bond, We jointly and severally obligate and bind ourselves, and our respective heirs, executors, administrators, successors, and assigns to pay City the penalsum of Twelve Thousand Six Hundred and no/100 Dollars ($ 12 600.0 ("the Bonded Sum'), this
amount comprising not less than ten percent (10%) of the total Contract Sum, in lawful money of the United States of America The Licensed Agent for Surety is
Diamond Valley lnsurance Services, lnc.-41856 lwStreet#108 M urrieta, cA 92562 (951) 553-7400 (Name, address, and lelephone)
Registered Agent's Califomia Department of lnsurance License No OH94716 THE CONDIII0N 0F THIS BOND'S OBLIGATI0N lS THAT ifthe said Principalor anyof his or her or its subcontraclors, orthe heirs, executors, administrators, successors, or assigns or assigns of any, all, or either of them, shall fail to exeGrte wi$in a reasonable amount of time, or fail to respond within seven (7) days with a written schedule acceptable to the City for same, repair or replacement of any and all Work, together with any other adjacent Work which may be displaced by so doing, that proves to be defective in its workmanship or material for the period of one (1) year (except wtren otherwise required in the Contract to be for a longer period) from the date the City's Notice of Completion and Acceptance, or equivalent, is filed with the County Recorder, ordinary 'r'/ear and tear and unusual abuse or neglecl excepted with respect to such Work and labor, the Surety herein shall pay for be same, in an amount not exceeding lhe sum specified in tris Bond.
("Surety"), a duly
R Dependable Const Inc.

Page 118 of 222 ends

.
.

Item 10 Page 120 of 369
When City declares that Principal is in default under the Contract, or Contract Documents, or both, Surety shall promptly remedy the default using a procurement methodology approved by City, select a mntractor or contractors acceptable to City to complete all of the Work, and anange for a contracl between the conlractor(s) and City. Surety shall make available sufficient funds to pay the cost ofrepair or replacement of any and allWork and to pay and perform all obligations of Principal under the Contract and Contracl Documents including other costs and damages for rryhich Surety is liable under this Bond except that Surety's total obligation, as described here, will not exceed the Bonded Sum.

2. Should the condition of this bond be fully performed, then this obligation shall become null and void, othen ise it shall be and remain in full force and effed.

3. Surety, for value received, hereby stipulates and agrees that no change, extension oftime, alteration, or addition to the terms of said Contract or to the Work to be performed thereunder or the specifications accompanying the same shall in any manner aflect its obligations on this bond, and it does hereby waive notice of any such change, e(ension, alteration, or addition.

4. Surety's obligations underthis Bond are separate, independent from, and not contingent upon any other surety's guaranteeing Principal's faithful performance of the Work.

5. No right of action accrues on this Bond to any entity other than City or its successors and assigns.

6. lf an action at law or in equity is necessaryto enforce or interpret this Bond's terms, Surety must pay, in addition to the Bonded Sum, City's reasonable attorneys' fees.and litigation costs, in an amount the courl fixes.

7. Surety shall mail Ci9 written noti6€ at least 30 days before: (a) the effective date on which the Surety will cancel, terminate, or withdraw from this Bond; or (b) this Bond bemmes void or unenforceable for any reason.

8. Deah ofthe Principal shall not relieve Surety of its obligations hereunder to this
R Dependable Const Inc.

Page 119 of 222 ends

.
.

Item 10 Page 121 of 369
on the date set lorth below, Principal and Surety duly executed tnls I, with the name of each party appearing below and signed by its representative(s) under the authority of its governing body. gr1. April 2, 2026
PRINCIPAL:

R Dependable Const lnc
SI.JRETY:

The Ohio Casualty lnsurance Company
(Company Name)
(Signature)
a N
By: Rosemary Padilla, P nt
gnature)
By Karen A. Eby, Attorney-in-Fact
(Name and Title)
Address for Serving Notic€s or Oher Docurnents:
'100 Liberty Way
Dover, NH 03820
(Name and Title)
Address br SeMng Notices or Otrer Docurnents:
1019 W. 3rd Street, Ste B.

CORPORATE SEAL
. IHIS EOIVD MUST BE xECUTED IN TRIftIUTE
. EV1DENCE MUST * ATTAC|IED OF IHE AUIHORTTY OF ANY trRSOt't S/GNINGAS ArrORNEYlrVfACll . THE ATTORNEY-1N+AC]"S S/GN/rURE MUST BE NOTARTZED.
. A @RpoRAIE SEA- MUST BE TMPRESSED ON THIS FffiM WHEN THE PRINCIPN- OR THE SUREry, OR NTH, ARE A CORrcRANAN.
oaniel S. Wall, Director of Public Works / City Engineer APPROVE0 AS T0 FORi\4
Zaynah Moussa-Milward, City Attorney
By By
San Bernardino, CA 92410

CORPORATE SEAL

APPROVED AS TO SURETY AND
AMOUNT OF BONDED SUM:

R Dependable Const Inc.

Page 120 of 222 ends

.
.

Item 10 Page 122 of 369
BOND ACKNOWLEDGI\4ENT
FOR
SURETY'S ATTORNEY.IN-FACT

STATE OF CALIFORNIA

COUNTY OF
SS
On this _ day ol _,20-.,
before me, (name), a Notary Public for said County, personally appeared name), who proved to me on the basis of
satislactory evidence to be the person whose name is subscribed to this instrument as the attomey in fact of and acknowledged to me that he/she subscribed the
name ol thereto as principal, and his/he own name as
attorney in fact.

I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

SEE ATTACHED
Notary Public
SEAL
)
)
)
R Dependable Const Inc.

Page 121 of 222 ends

.
.

Item 10 Page 123 of 369
Libertv
Mutuil"
SUREIY
This Porrr of Attomey limit! the actr of thote nlmad horoin, and lhey haya no authority to bind tho Company6tclpt in the manner and to tha 6tLnt herain atated.

Liberty Mutual lnsurance Company
The Ohio Casualty lnsurance Company
West American lnsurance Company

POWER OF ATTORNEY
certlicare No E208023-987721
Kl{OW}l ALL PERSOT{S BY THESE PRESEiITS: That Th6 Ohio Casualty lnsurance Coopany is a coeo.alion duly organizod under the lars ol he Slalo of New Hamp6hre, hat tlaker. [aren A Eby-. Kvle f Baker.-Iimorhy C Ba*er
all of fle city of MunEta shte of CA eadr individudly if here be mo.e han one named, ib lrue and la*tu| atomey'in-fad to make, of hese Fesenb and shat b€ as tinding upql he Companies as if hey have been duly sgned by lhe prcsid€nt and alteabd by he s€qotary ol he Companies in h6ir own prop€r peisoars
N WrIIESS WHEREOF, h6 Pow€r of Attomey ha3 b€€n subs.rib€d by an auho.rzed offcer o. offcial of he Compani6 aod lhe corpo.ale seals of he Companies hav6 been afued tle eto his l lrh day of May 2012
Liberty Mufual lnsuranco Company
The Ohro Casualty lnsurance Company
West Amencan lnsurance Cofipany
By:

David M Carey, Arsistant Sec,etary
Shte o, PENNSYLVANIA
County ol MONTGOIIEnv $
Or his I lrh day ol Nla , 2012 b€tre me p€Gonaily apgearod Davi, M Carey, vrto acknododged hims€fi to be he Assistant S€crelary ol Liberty l4utual lnslraoce Cornpany, Tle Ohio Casualty Coopany, and We6t Arnedcan lnsu€nce Company, and lhal he, as sudl being authonzed so to do, qeole the forogoing msttumenl for he purpos€s herein contained by siJning o0 behaf of he coeoratons by himsell as a duly authonzed ofticer lN IYrTNESS WHEREOF, lhave hereunto subscrib€d my name and alfred my notaflals€alal King of Prussia Pennsylvsnia, oo heday and year flsl above wnnen Cdiiui.dr' ol Pa..rtr6. ikr..y S.d i.@ ParNdi6. ilolry Put*.

Mdtl.my Csnt
ily 6m'3s e4i6 M.rd' 28. 2025
Crlrrrss rumb.r I 1260ar
/-f//.
r,r6bd P.ni.yr!mL. &srto o, NobG eress Pastella Notary Public 1912 :
\l.ls
1991
s
z
o
o
E
-a
=op6,
oc)
:f:66>
6S
-D
39 cio 6q) cp
oP3
E,E6EF. :.9o(E
p>
oc> lt)
-!-
a- <)
E
o
I
6 =
E
!
e6
.96 <b
o
N
o
(o
t!
o)
o
o
=q
=
o
o
i
o
c
o
c
o
-o
o
LL
1912 E
\t{s
1919
\NSa,
-
LMSI2873 LM|C OC1C WA|C Muti Co O2l21
By
C Lle*ellyn, AssEtanl
8y:

Ihis Porv€{ ol Attorn€y is made and ereoJled purslant to and by auhonty o, Ule hllowing By'lars and Auhorizaoons ol The ofiio Casualty lnsu6nce Company, Lrb€.ty Mufal lnsurance Cornpany, and West Amdican lnsuaance Company whidr resdutions arc non in full foace and efiecl rcading as ulorrs:

ARTICLE lv - OFFICERS: S€clioo 12 Pow€r ol Atomey
Any oftcer or o$lea offajal of the Coapoaalbn au$orted toa hal porpoG€ in writrng by he Chairman o( he Pr6iden[ and subj€cl h sudr hmitalion as he Charman or he have tull po{rer to Und he Corporatoi by her signaturc and exeqJlion of any sudr mstumsnts and lo attadr tEreto he seal ol the Corporaton. Wlei so greq]ted, sudr Fovisions ol E s artide may be revoked al any tme by he 8oard, lhe Chairman, tre Pr6idenl oa by he ofrcer or oficers grantrng $dr po*e. or auho.rty ARTICLE Xlll - Er.cution of Conlr.cL: Sectoi 5. Surety Bonds and undertakings shall apponl sudt attorners{-lact as may be n€@ssary lo ad ifl bollalt of he C,o.npaoy lo fiEke, ereorte, seal. &{norlodge aod ddiyer as surety any and all underlakings, Company by &err sEnafurc and er€qrtim ol any sudl inslrumenls and lo attach thergto tle s€al of he Company. Wheri so ereorled soch instruftents siall b€ as binding as il stJned by he presrd€nt and at€sted by he se.,etary.
bd as may be n€c€ssary to acl oo behdf of he Co.npany to make, ereqrle, seal, ackno*€dge and d€liver 6 surty any and all underbkrl|gs. bonds, ecognrzangs and dher sureq obl(ratons.
he samo forca and etlect as thorrgh manually affued.
has nol been rcvoied.
ll{ IESTlirc}lY IVHEREOF, I have herarnto set my hand and aftred the seals ol said Co.npanies hrs lnd day ot Apnt 2026 1919
1991
R Dependable Const Inc.

Page 122 of 222 ends

.
.

Item 10 Page 124 of 369
CALIFORNIA ALL. PURPOSE

CERTIFICATE OF ACKNOWLEDGMENT
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the trulhfulness, accuracy, or validity of that document.

State of California )
County of )
Riverside
before me, Marco Emmanuel V a, Notary Public
personally appeared Karen A. Eby
who proved to me on the basis of satisfaclory evidence to be the person(s) whose name(e) is/ar€ subscribed to the within instrument and acknowledged to me that -hebhe/they executed the same in-his,/herltheir authorized capacity(ies), and that by -his/herAheir signature{€) on the instrument the person(€}, or the entity upon behalf of which the person(€) acted, executed the instrument.

I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

WTNESS my h nd and ofiicial seal
I rcO Afl NtEL VECA
O(II. t llt€rlo [olfl PUeJc - cauFo8i ivtBrr co,rNTY ^
MUl.8EJl,rjlFY232m
<t,
=!
Nota U (Notary Public Seal)
ADDITIONAL OPTIONAL INFORMATION INSI'RUCTIONS FOR COMPI,I]TING llIIS !'ORM Tlnslom co pli.swith cun.nr Calilonn stahtcs tegoding muryvo ng ud, {n .&4 rlaald b. @dpLEd od aoacLd to E &M.nt.lcb@tLdgd.,tts Iron odv ttatcs rat b. co,t pLkdld b16.nl? b.iry fl"t to thd ttat tu loig at th. wotdw do.^s Mt.equ.e u Califo, a notoy to liolzt Colilo,rua norq.a . Slatc and County informanon musl br the Stale ard County wh€re the d{xumcnl signe(s) pcrsonally appeared beforc the notary publ'c for ack nowledgmenr . Darc ofnolarirrrion musl br lhe datc lhat lhe sisner(s) peFonally appcar.d which musi also be thc samedare rhe acknowledgment iscompleled . Ihe nolary public musr pnnr his or h€r namc ar il appca$ wilhrn hrs or hrr comm'ssion follow€d by a comma and then your tatl€ (nolan public) . Pnnr the nanrc(s) of do.ume srSne(s) who peuonally apptd at lhe rime oI DESCRIPTION OF THE ATTACHED DOCUi/ENT
(Title o. desdiplon ol atlaclcd doornpnl)
(Tille or descrlption oi atached documenl contrnued)
Number of Pages _ oocumenl Date_
. lndicare lhe conect singular or plural forms by crossinS ofI mconEct forms (i€ L/sh€r'*qr
's
h+. )orcirclingfiecorre.t forms Failure to con€cdy rndicalelhis rnformalion may l.ad to rc.icclion ofdocument recording. . The nolary seal impression must be cl.ar and photographically rcpmducible Imp.ession musl noi cover rexl or hnes Ifs€al imprcssron smudges. rc-s€al ifa sufliciml area permits, oih€rwise complere a differcnl acknoeledgment form . Signarur€ ofrhe norary public musl malch ihe si8naturc on fite wilh th€ ofiice of C Addrlronal informalion rs not r€quircd but could help to ensure lhrs aclnowledgmeni is nol misuscd or anacH lo a differ€m documcnl + Indicatettl€ or typ€ of ahachcd docuinent. nmberof pages and dare. + Indicate the capacity claim€d by lhe si8nr. If the ctaimed capaciry is a corpomle officer, indicatc thc lltle (ie CEO. CFO. Sccrelarr) . Securcly atlach rhi! do.umenr lo lhe srSned do(umc wilh a srapl..

I
I
-
i.,

CAPACITY CLAIMEO BY THE SIGNER
tr lndividual (s)
B Corporate Officer
(IirteF
Partne(s)
Attomey-in-Facl
Trustee(s)
Other
n
6 tr
tr
201 5 Version w$ryv.NotaryClasses.com 80G.873-9865
On 2nd Aptll2026
R Dependable Const Inc.

Page 123 of 222 ends

.
.

Item 10 Page 125 of 369
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certilicate is attached, and not the truthfulness, accuracy, or validity ofthat document.

State of Califomia
County of San Bernardino
gp April 6th. 2026 before me, Damaris Abigail Lara Ramos (Here inset name and tide ofthe ofncer)
personally appq6psd Rosemary Padilla
who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalfof which the person(s) acted, executed the instrument.

I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

WI S my hand a seal. DAii,llAiiS AEI6AII LARA R
coMM. #24 48473
(Notary Seal)
ti0ItRY PUB!|C - CAUf0RUtA
sA!{ BEttlARDfl 0 CCUiiIY
My Cl),nln [)(plles l\iay :J0 2027
S
CALIFORNIA ALL.PURPOSE

CERTIFICATE OF ACKNOWLEDGMENT

DESCRIPTION OF THE ATTACHED DOCUMENT
Maitenance Bond
(Tille or description of attached document)
(Title or description of atrached docum€nt continued)
Number ofPages _ Document Date_
Nore T*o ,gDalu$ e b.ing noEnzd * hb a nngl. &x@enr
(Additional information)
ADDITIONAL OPTIONAL INFOR,\,IATION

TNSTRUCTIONS FOR COMPLETING THIS FORM
Anr acknotlledgfient conpleted in Calilonia n6t contain vcrhiage eracd'- &t appears above in the notun section or a separdte acknowlelgmenr forn nust be properly conplered and otrached to that docunent. The onlr e:rcep,ion k 4 o document it to be recorded outside of Colilomia. In such instances, anr ahemotire acknowledgment verbiage as ay be printed on such o docunent so long as the vrhioge does not requirc rhc notan to do something that is illegal for a notan in Calilomio (i.e. certifiing the outho/ized rupacih of the signer) Pleue thect thc &tcwnent carefullt hr proper notarial wordin{ and attuch thislorm tfrequired. . State and Counly informatior musr be the State and County where the documcnr sigtre(s) penonauy appeared before the Dotary public for acknowledgment. . Date ofnotarization must bc the darc thar rhc signcr(s) personally appcared whtch must also be the same datc thc acknowledgmcnt is completed. . The notary publc musl pnnt his or her name as rt app€ars withio his or hcr cornrnission fbllo*ed by a comma and then your title (notary public). . Prinl ihc name{s) of documcnt signe(s) who pcrsonally appcar at thc time of notarization.
. Indicate the correct singular or plural forms by crcssing oft incorrect tbrms (i.e. h€r'she/tbelr is sre ) or crrcling thc correct forms- Failure to correcd) indicatc this infonnation may lcad to rcjection ofdocumcnt recording. . Thc notary seal imprcssion must be clcar and photographically rcproduciblc.

Imprcssion musl not covcr text or lincs. If scal imprcssion smudgcs. rc-scal if a sufficient area permits. otherwise complete a different acknowledgmenr form. . Signature ofthe notary public must match rhe signature on file with the ofEce of lhe county clerk.
* Additional information is not rcquired bur could help to ensure rhis acknowlcdgment is not misused or atachcd to a diffcrcnt documcnt. , Indicate title or type ofattached document. numb€r ofpages and date. t Indicale the capacily claimed by lhe signer. Ifthe claimed capacity is a corporatc officer, indicalc thc titte (i.c. CEO, CFO, Sccretary). . Securely attach rhis document to the signed document

CAPACITY CLAIMED BY THE SICNER
n Individual (s)
E Corporate Officer
(Tirte)
! Partner(s)
! Anorney-in-Fact
n Trustee(s)
! Other
2008 Version CAPA v12.10.07 800-873-9865 w*.w.Notarvctasses_com R Dependable Const Inc.

Page 124 of 222 ends

.
.

Item 10 Page 126 of 369
EXHIBIT 4

INSURANCE REQUIREMENTS

1.0 REQUIRED INSURANCE POLICIES
At its own expense, Contractor shall obtain, pay for, and maintain – and shall require each of its Subcontractors to obtain and maintain – for the duration of the Agreement including any warranty or correction period, policies of insurance meeting the following requirements: The policy shall be endorsed to waive all rights of subrogation against City, its directors, commissioners, officers, employees, and volunteers for losses arising from performance of this Contract.

A. Workers’ Compensation/Employer’s Liability Insurance shall provide workers’ compensation statutory benefits as required by law. A waiver of subrogation endorsement in favor of the City shall be provided.

1. Employer’s Liability insurance shall be in an amount not less than:
(a) ONE MILLION DOLLARS ($1,000,000) per accident for bodily injury or disease; (b) ONE MILLION DOLLARS ($1,000,000) per employee for bodily injury or disease; and
(c) ONE MILLION DOLLARS ($1,000,000) policy limit.

B. Commercial General Liability (“CGL”) (primary). City and its employees and agents shall be added as additional insureds, not limiting coverage for the additional insured to “ongoing operations” or in any way excluding coverage for completed operations, and broad form property damage. The policy shall be endorsed to include a waiver of subrogation in favor of the City. Coverage shall apply on a primary, non-contributing basis in relation to any other insurance or self-insurance, primary or excess, available to City or any employee, representative or agent of City.

Coverage shall not be limited to the vicarious liability or supervisory role of any additional insured. Coverage shall contain no contractors’ limitation or other endorsement limiting the scope of coverage for liability arising from explosion, collapse, or underground property damage.

1. CGL insurance must not be written for less than the limits of liability specified as follows:
(a) TWO MILLION DOLLARS ($2,000,000) per occurrence for bodily injury (including accidental death) to any one person;
(b) TWO MILLION DOLLARS ($2,000,000) per occurrence for personal and advertising injury to any one person;
(c) TWO MILLION DOLLARS ($2,000,000) per occurrence for property damage; and (d) FOUR MILLION DOLLARS ($4,000,000) general aggregate limit.

2. CGL insurance must include all major divisions of coverage and must cover:
(a) Premises Operations (including Explosion, Collapse, and Underground [“X,C,U”] coverages as applicable);
(b) Independent Contractor’s Protective;
R Dependable Const Inc.

Page 125 of 222 ends

.
.

Item 10 Page 127 of 369
(c) Independent Contractors;
(d) Products and Completed Operations (maintain same limits as above until five (5) years after recordation of Notice of Completion);
(e) Personal and Advertising Injury (with Employer’s Liability Exclusion deleted); (f) Contractual Liability (including specified provision for Contractor’s obligation under Article 11 of the General Conditions); and
(g) Broad Form Property Damage.
.

C. Business Automobile Liability Insurance

1. Business Automobile Liability Insurance must cover all vehicles, whether rented, leased, hired, scheduled, owned or non-owned. The City shall be named as additional insured, and a waiver of subrogation endorsement shall be provided. If Contractor does not own any vehicles, this requirement may be satisfied by a non-owned vehicle endorsement to the general and umbrella liability policies. Business Automobile Liability Insurance coverage amounts shall not be less than the following:
(a) ONE MILLION DOLLARS ($1,000,000) per occurrence for bodily injury (including accidental death) to any one person; and
(b) ONE MILLION DOLLARS ($1,000,000) per occurrence for property damage; or (c) ONE MILLION DOLLARS ($1,000,000) combined single limit.

D. Contractors Pollution Liability Insurance (CPL) and/or Asbestos Pollution Liability and/or Errors & Omissions applicable to work being performed.

1. Contractor or Subcontractor shall obtain, pay for, and maintain for the duration of the Contract Contractors Pollution Liability insurance that provides coverage for liability caused by pollution conditions arising out of the operations of the Contractor. Coverage shall be included on behalf of the insured for covered claims arising out of the actions of independent contractors. If the insured is using Subcontractors, the policy must include work performed “by or on behalf” of the insured.

2. The policy limit shall provide coverage of no less than one million dollars ($1,000,000) per claim and in the aggregate. Coverage shall apply to bodily injury; property damage, including loss of use of damaged property or of property that has not been physically inured; cleanup costs; and costs of defense, including costs and expenses incurred in the R Dependable Const Inc.

Page 126 of 222 ends

.
.

Item 10 Page 128 of 369
investigation, defense, or settlement of claims.

3. All activities contemplated in the Contract shall be specifically scheduled on the CPL policy as “covered operations.” In addition, the policy shall provide coverage for the hauling of waste from the Project site to the final disposal location, including non-owned disposal sites.

4. The policy shall specifically provide for a duty to defend on the part of the insurer. City, its officers, employees and agents shall be added to the policy as additional insureds by endorsement.

E. Builder’s Risk Insurance

1. Builder’s Risk Insurance covering all real and personal property for “all risks” of loss or “comprehensive perils” coverage including but not limited to the perils of earth movement including earthquake and flood for all buildings, structures, fixtures, materials, supplies, machinery and equipment to be used in or incidental to the construction at the site, off site, or in transit, for the full replacement value of such properties. Coverage shall be included for property of others in the care, custody or control of the insured for which any insured may be liable.

F. Umbrella or Excess Liability Policy (over primary), if provided Contractor may use an umbrella or excess policies to provide the liability limits as required in the Contract. This form of insurance will be acceptable, provided that all of the primary and umbrella or excess policies shall provide all of the insurance coverages herein required, including, but not limited to, primary and non-contributory, additional insured, Self-Insured Retentions (SIRs), indemnity, and defense requirements. The umbrella or excess policies shall be provided on a true “following form” or broader coverage basis, with coverage at least as broad as provided on the underlying Commercial General Liability Insurance.

G. If Contractor maintains broader coverage and/or higher limits than the minimums shown above, City requires and shall be entitled to the broader coverage and/or the higher limits maintained by the Contractor. Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to the City.

2.0 GENERAL REQUIREMENTS—ALL POLICIES
A. Qualifications of Insurer. At all times during the term of this Contract, Contractor’s insurance company must meet all of the following requirements:

1. “Admitted” insurer by the State of California Department of Insurance or be listed on the California Department of Insurance’s “List of Surplus Line Insurers” (“LESLI”), or nonadmitted insurer approved by the City.

2. Domiciled within, and organized under the laws of, a State of the United States; and

3. Carry an A.M. Best & Company minimum rating of “A:VIII”.

R Dependable Const Inc.

Page 127 of 222 ends

.
.

Item 10 Page 129 of 369
B. Continuation Coverage. For insurance coverages that are required to remain in force after the Final Payment, and if reasonably available, Contractor shall submit to City, with the final Application for Payment, all certificates and additional insured endorsements evidencing the continuation of such coverage.

C. Deductibles or Self-Insured Retentions. All deductibles or self-insured retentions are subject to City’s review and approval, in its sole discretion.

D. Commercial General Liability and Business Automobile insurance policies must be written on an “occurrence” basis and must add the City of Vernon and its officers, agents, employees and representatives as additional insureds.

E. Contractor’s Insurance Primary. Other insurance (whether primary, excess, contingent or selfinsurance, or any other basis) available to City, or its representatives, or both, is excess over Contractor’s insurance.

City’s insurance, or self-insurance, or both, will not contribute with Contractor’s insurance policy.

F. Waiver of Subrogation Endorsement. Contractor and Contractor’s insurance company waive— and shall not exercise— any right of recovery or subrogation that Contractor or the insurer may have against City, or its representatives, or both.

G. Separation of Insureds. Contractor’s insurance policy applies separately to each insured or additional insured who is seeking coverage, or against whom a claim is made or suit is brought, except that the naming of multiple insureds will not increase an insurance company’s limits of liability.

H. Claims by Other Insureds. Contractor’s insurance policy applies to a claim or suit brought by an additional insured against a Named Insured or other insured, arising out of bodily injury, personal injury, advertising injury, or property damage.

I. Premiums. City is not liable for a premium payment or another expense under Contractor’s policy J. At any time during the duration of this Contract, City may do any one or more of the following:

1. Review this Agreement’s insurance coverage requirements;

2. Require that Contractor obtain, pay for, and maintain more insurance depending on City’s assessment of any one or more of the following factors:
(a) City’s risk of liability or exposure arising out of, or in any way connected with, the services of Contractor under this Agreement;
(b) The nature or number of accidents, claims, or lawsuits arising out of, or in any way connected with, the services of Contractor under this Agreement; or (c) The availability, or affordability, or both, of increased liability insurance coverage.

3. Required the Contractor to obtain, pay for, or maintain a bond (as a replacement for an insurance coverage) from a California corporate surety, guaranteeing payment to City for liability, or costs, or both, that City incurs during City’s investigation, administration, or defense of a claim or a suit arising out of this Agreement; or R Dependable Const Inc.

Page 128 of 222 ends

.
.

Item 10 Page 130 of 369
K. Contractor shall maintain the insurance policy without interruption, from the Project’s commencement date to the Final Payment date, or until a date that City specifies for any coverage that Contractor must maintain after the Final Payment.

L. Contractor shall not allow any insurance to expire, cancel, terminate, lapse, or non-renew.

Contractor’s insurance company shall mail City written notice at least thirty (30) days in advance of the policy’s cancellation, termination, non-renewal, or reduction in coverage and ten (10) days before its insurance policy’s expiration, cancellation, termination, or non-renewal, Contractor shall deliver to City evidence of the required coverage as proof that Contractor’s insurance policy has been renewed or replaced with another insurance policy which, during the duration of this Agreement, meets all of this Agreement’s insurance requirements.

M. At any time, upon City’s request, Contractor shall furnish satisfactory proof of each type of insurance coverage required— including a certified copy of the insurance policy or policies; certificates, endorsements, renewals, or replacements; and documents comprising Contractor’s self-insurance program— all in a form and content acceptable to the City Attorney or City’s Risk Manager.

N. If Contractor hires, employs, or uses one or more Subcontractor(s) to perform work, services, operations, or activities on Contractor’s behalf, Contractor shall ensure that the Subcontractor complies with the following.

1. Meets, and fully complies with, this Agreement’s insurance requirements; and

2. Furnishes City at any time upon its request, with a complete copy of the Subcontractor’s insurance policy or policies for City’s review, or approval, or both. Failure of City to request copies of such documents shall not impose any liability on City, or its employees.

O. Contractor’s failure to comply with an insurance provision in this Agreement constitutes a material breach upon which City may immediately terminate or suspend Contractor’s performance of this Agreement, or invoke another remedy that this Agreement or the law allows. At its discretion and without waiving any other rights it may have pursuant to law, City has the right but not a duty to obtain or renew the insurance and pay all or part of the premiums. Upon demand, Contractor shall repay City for all sums or monies that City paid to obtain, renew, or reinstate the insurance, or City may offset the cost of the premium against any sums or monies that City may owe Contractor.

3.0 CONTRACTOR’S SUBMITTAL OF CERTIFICATES AND ENDORSEMENTS A. Contractor shall have its insurance carrier(s) or self-insurance administrator(s) complete and execute the following insurance documents and shall deliver said documents at the same time Contractor delivers this Agreement to City. City will neither sign this Agreement nor issue a “Notice to Proceed” until the City Attorney or City’s Risk Manager has reviewed and approved all insurance documents. City's decision as to the acceptability of all insurance documents is final.

B. Required Submittals for Commercial General Liability and Business Automobile Insurance and Contractor’s Pollution Liability Insurance. The following submittals must be on forms satisfactory to the City Attorney or City’s Risk Manager, and signed by the insurance carrier or its authorized representative – which fully meet the requirements of, and contain provisions entirely consistent with, all of the insurance requirements set forth herein.

1. “Certificate of Insurance”

2. “Additional Insured Endorsement”

3. Waiver of Subrogation Endorsement: “Waiver of Transfer to Rights of Recover Against Others” Both Certificates of Insurance and Additional Insured Endorsements must read as follows: “The City of Vernon, R Dependable Const Inc.

Page 129 of 222 ends

.
.

Item 10 Page 131 of 369
and its officers, agents, employees and representatives are included as additional insureds under the policy(s). This insurance is primary to all other insurance of the City. The City’s insurance and self-insurance will apply in excess of, and will not contribute with this insurance. This insurance applies separately to each insured or additional insured who is seeking coverage, or against whom a claim is made or a suit is brought. The issuing company shall mail thirty (30) days advance notice to the City for any policy cancellation, termination, non-renewal, or reduction in coverage.” C. Required Submittals for Workers’ Compensation Insurance. Contractor shall provide City with a certificate of insurance and a subrogation endorsement on forms satisfactory to the City Attorney or City’s Risk Manager, and signed by the insurance carrier or its authorized representative – which fully meet the requirements of, and contain provisions entirely consistent with, this Contract’s workers compensation insurance requirements. If Contractor is self-insured for workers’ compensation, a copy of the “Certificate of Consent to Self-insure” from the State of California is required; or if Contractor is lawfully exempt from workers’ compensation laws, an “Affirmation of Exemption from Labor Code §3700” form is required.

D. Required Evidence of Builder’s Risk Coverage. Contractor will provide a certificate of insurance and a declarations page on a form satisfactory to the City Attorney or City’s Risk Manager, and signed by the insurance carrier or its authorized representative. The policy terms must fully meet the requirements of, and contain provisions entirely consistent with, all of the insurance requirements set forth herein. The City shall be named as a loss payee on the insurance policy for the full replacement value of all buildings, structures, fixtures and materials to be constructed, maintained, repaired or supplied pursuant to this Contract.

E. Contractor agrees to monitor and review all such coverage and assumes all responsibility for ensuring that all required coverage is provided. Contractor agrees to obtain certificates evidencing such coverage.

F. Contractor agrees to provide immediate notice to City of any claim or loss against Contractor that includes City or any other indemnitee as a defendant. City assumes no obligation or liability by such notice, but has the right (but not the duty) to monitor the handling of any such claim or claims if they are likely to involve City.

G. No liability policy shall contain any provision or definition that would serve to eliminate so-called “third party action over” claims, including any exclusion for bodily injury to an employee of the insured or of any contractor or subcontractor.

H. Any “self-insured retention” must be declared and approved by City. City reserves the right to require the self-insured retention to be eliminated or replaced by a deductible as approved by the City. Self-funding, policy fronting or other mechanisms to avoid risk transfer are not acceptable. If Contractor has such a program, Contractor must fully disclose such program to City.

R Dependable Const Inc.

Page 130 of 222 ends

.
.

Item 10 Page 132 of 369
EXHIBIT 5
Statement of lntent to Complv with Minimum Reo uirements of lhe Stormwater Permit Permit Number N/A
CIry OF VERNON
Department of Public Works
Conskuction Stormwater Program
Dale 0410812026
phone.909-381-2310 Applicant: Rosemary Padilla
Project Address: 4 05 Santa F Av n Vernon Calilornia 90058 Property glvns1 4305 Santa Fe Avenue, Vernon, California, 90058 Contractor: R Dependable Const lnc
Contractor's Address: 1019 West 3rd Street San Bernardino cA 92410 The National Pollutant Discharge Elimination System (NPDES) is a portion of the Clean Water Act that applies to the protection of receiving waters. Under permits from the Los Angeles Regional Water Quality Control Board (RWOCB), certain activities are subject to RWQCB enforcement. To meet the standards of the Waste Discharge Requirements for Municipal Separate Slorm Sewer System (MS4) Discharges within the Coastal Watershed of Los Angeles County, Except those Discharges Originating from the City of Long Beach MS4 (CAS004001), the City of Vernon has adopted minimum standards for stormwater runoff from development construction activities.

These minimum standards require the implementation of an effective combination of erosion and sediment conhol Best Management Praclices (BMPs) to prevent erosion and sediment loss, and the discharge of conskuction waste at each site. At a minimum, the construction activity associated with the construction prolect identified above shall be conducted in such a manner that:

Note: The Stormwater BMP Construction Handbook sheets developed by the California Stormwater Quality Association shall be used as guidance in determining and implemenling required BMPs. The BMP sheets may be reviewed at the Department of Public Works counter during regular business hours. A General Construction Permit shall be obtained and maintained for all conskuction sites one (1) acre or greater. Additional conditions may be required for these sites.

L Prevents illicit construction-related discharges of pollutants into the MS4 and receiving waters. i lmplements and maintains structural and non-structural BlVtPs to reduce pollutants in stormwater runoff from construction sites. ), Reduces construction site discharges of pollutants to the MS4 to the maximum extent practicable. ) Prevents construction site discharges to the MS4 from causing or contributing to a violation of water quality standards.

R Dependable Const Inc.

Page 131 of 222 ends

.
.

Item 10 Page 133 of 369
I have read and understand the requirements listed above and certify that I will comply with the minimum requiremenls above. )
Signature:

Print Name: Rose Padil
Title: President
Property Owner: City of Vernon
R Dependable Const Inc.

Page 132 of 222 ends

.
.

Item 10 Page 134 of 369
EXHIBIT 6

CITY OF VERNON
Department of Public Works
4305 Santa Fe Avenue Vernon Californ ia 90058
Property Owner: 4305 Santa Fe Avenue, Vernon , California, 90058 Contractor: R Dependable Const lnc
Contractor's Address: 1 01 9 West 3rd Street San Bernardino, CA 92410 The latest COVID-19 industry guidelines can be accessed at the following web address httos J/www.dir.ca.qov/dosh/coronavirus/Guidance-bv-lndustrv.html This document provides guidance for the construction industry to support a safe, clean environment lor workers. The guidance is not rntended to revoke or repeal any worker rights, either statutory, regulatory or collectively bargained, and is not exhaustive, as it does not include county health orders, nor is it a substitute for any existing safety and health-related regulatory requirements such as those of CalioSHA.l Stay current on changes to public health guidance and state/local orders, as the CoVID-19 situation continues. Cal/0SHA has more safety and health guidance on their Cal/OSHA COVID-19 lnfection Prevention for Construction 2 Employers and Workers webpage.

CDC has additional guidance for businesses and employers.

I have read and understand the requirements listed above and certify that lwill comp ly with the minimum requrreme above
Signature Date: 0410812026
Print Name: Rosemary Padi
Title: President
Stalement of lnlent to Complv wilh lvinimum Requirements of the Califomia Covid-19 lndustry Guidance: Construction
Prolect Address:

R Dependable Const Inc.

Page 133 of 222 ends

.
.

Item 10 Page 135 of 369

Page 182 of 184 ends

EXHIBIT B

SPECIAL PROVISIONS

SPECIFIC FOR THIS PROJECT
R Dependable Const Inc.

Page 134 of 222 ends

.
.

Item 10 Page 136 of 369
EXHIBIT B – SPECIAL PROVISIONS
1 EXHIBIT B – SPECIAL PROVISIONS

SPECIFIC FOR THIS PROJECT
Vernon City Hall Third Floor Facilities
Renovations
Contract No. 20260210
R Dependable Const Inc.

Page 135 of 222 ends

.
.

Item 10 Page 137 of 369
EXHIBIT B – SPECIAL PROVISIONS
2 Table of Contents
A. General .................................................................................................................................................. 3

1. Scope of Work .................................................................................................................................. 3

2. Contract Specifications ......................................................................................................................... 4

3. Specifications ........................................................................................................................................ 4

4. Length of Contract ................................................................................................................................ 4

5. Liquidated Damages .............................................................................................................................. 4

6. Delays and Extensions of time .............................................................................................................. 4

7. Quality of Work ..................................................................................................................................... 5

8. Unit Prices ............................................................................................................................................. 5

9. Extra Work ............................................................................................................................................ 5

10. Compliance with Laws, Regulations, and Safe Practices .................................................................... 5 B. Construction Phase Specifications ........................................................................................................ 5

1. Scheduling of Work .......................................................................................................................... 5

2. Material Submittals .......................................................................................................................... 6

3. Construction Hours .......................................................................................................................... 6

4. Protection of the Public ................................................................................................................... 6

5. Noise Restrictions ............................................................................................................................ 7

6. Construction Order of Work ............................................................................................................ 7

7. Character of Workers ....................................................................................................................... 7

8. Examination of Site .......................................................................................................................... 7

9. Mobilization ..................................................................................................................................... 7

10. Dust Control ..................................................................................................................................... 7

11. Sanitary Facilities ............................................................................................................................. 8

12. Contractor Responsibility ................................................................................................................. 8

R Dependable Const Inc.

Page 136 of 222 ends

.
.

Item 10 Page 138 of 369
EXHIBIT B – SPECIAL PROVISIONS
3 A. General

1. Scope of Work
This project consists of the demolition, remodeling, and refurbishing of a men’s and women’s restroom space on the third floor at the Vernon City Hall, located at 4305 Santa Fe Ave., Vernon, CA 90058, and shall be completely finished as shown on drawings and these specifications.

The interior of the building may contain materials to be hazardous. The Contractor will be required to properly remove and dispose of all hazardous materials in accordance with State and Federal guidelines. The Contractor will be required to work with the City’s Public Works and Health Departments to ensure that the building has been cleared of hazardous materials before additional work can commence.

The interior work includes removal, patching, repair, and installation of partitions, drywall, T-bar ceiling tiles and framing, metal stud kickers/braces, installation of texture and painting of walls and ceilings, removal and replacement of metal and door casings and base molds, replacement of all interior doors, removal and replacement of carpeting, installation of floor and wall tile, bathroom cabinets, fixtures, cabinets, countertops, replacement and installation of new electronics and office furniture. All interior work must comply with the 2022 California Building Code.

Electrical work includes completely new wiring, new interior light fixtures, outlets, conduits, and wiring to meet current electrical code requirements, new wired smoke and carbon monoxide detectors. All electrical work must comply with the 2022 California Electrical Code.

Mechanical work includes removal and installation of HVAC systems, which includes ductwork, new supply and return diffusors/registers, suspended strap attachments, and new HVAC unit. All mechanical work must comply with the 2022 California Mechanical Code.

Plumbing work includes replacement of complete sanitary drainage system with PVC piping, repiping all water lines from meter to fixtures with copper type L piping, and any other re-piping required to complete the work. All plumbing work must comply with the 2022 California Plumbing Code.

Cost for the installation of appliances shall be included in the various bid items and no additional compensation will be paid to the contractor for this work.

The work shall be done in accordance with City Hall Third Floor Bathroom Renovation Plans. In the event of any conflicts, refer to the Procedure of Contract Documents” contained in General Conditions, Section 1.10.

R Dependable Const Inc.

Page 137 of 222 ends

.
.

Item 10 Page 139 of 369
EXHIBIT B – SPECIAL PROVISIONS
4 2. Contract Specifications
The details and the exact limits for the asphalt and concrete work in this project are shown on the City of Vernon sheet drawings, incorporated into this Agreement by this reference:

Sheet No. Plan
No.

Description
1 B2801 Title Sheet & Notes
2-5 B2801 Plans & Details

3. Specifications
Installation for all the work shall conform to the 2022 California Building Code, California Plumbing Code, California Mechanical Code, California Electrical Code, California Energy Code, and California Green Building Standards Code. , and the City of Vernon Standard Plans.

4. Length of Contract
All work in this project shall be completed within ninety (90) calendar days as specified in the Bidder's Proposal.

5. Liquidated Damages
In accordance with Section 6-9 of the Standard Specifications, for each consecutive calendar day in excess of the time specified for completion of the work, as adjusted in accordance with Section 6-9 of the Standards Specifications, the Contractor shall pay to the agency, or have withheld from monies due it, the sum of two hundred and fifty ($250) per calendar day.

6. Delays and Extensions of time
The provisions of Section 6-4 entitled "Delays and Extensions of Time" of the Standard Specifications shall apply except as modified and supplemented below. The second paragraph of subsection 6-4.1 is hereby deleted and the following paragraph shall be inserted in its place:

No extension of time will be granted for a delay caused by the inability of the Contractor to obtain materials, equipment and labor, except as authorized by the City's Project Manager. The length of contract time stipulated includes any time which may be required to obtain materials, equipment and labor, and the Contractor in submitting a bid shall be deemed to have ascertained the availability of materials, equipment and labor and considered same in his/her proposed construction schedule.

R Dependable Const Inc.

Page 138 of 222 ends

.
.

Item 10 Page 140 of 369
EXHIBIT B – SPECIAL PROVISIONS
5 7. Quality of Work
The provisions of Section 3 entitled "Control of the Work" of the Standard Specifications shall apply. In addition, any work deemed unacceptable by the City's Project Manager, whether a cause is determined or not shall be repaired or replaced by the Contractor at his/her expense.

8. Unit Prices
All costs not covered by specific unit prices but required for a complete job in place, shall be included in the items most related to the work.

9. Extra Work
In the event the City and the Contractor are unable to negotiate an agreed price for extra work, which is acceptable to both parties, payment shall be made based on time and materials as follows:
 Work by the Contractor: The following percentages shall be added to the Contractor's cost and shall constitute the markup for all overhead and profits:

1. Labor 33%

2. Materials 15%

3. Equipment Rental 15%

4. Other Items and Expenditures 15%
 Work by the Subcontractor: When all or any part of the extra work is performed by a subcontractor, the markup provided by the Contractor as mentioned above shall apply to the subcontractor’s actual costs. A markup of 5% of the subcontracted portion of each extra work may be added for the Contractor.

10. Compliance with Laws, Regulations, and Safe Practices The Contractor shall perform all work in a safe, competent manner and in accordance with all federal, state, and local statues, regulations, ordinances, rules, and governmental orders. The Contractor will be solely and completely responsible for the conditions of the job site, including safety of all persons and property during performance of the work. This requirement will apply continuously and not be limited to normal working hours. Inspection of the Contractor's performance by the City, its agents, or employees is not intended to include review of the adequacy of the Contractor's safety measures in or near the job site.

B. Construction Phase Specifications

1. Scheduling of Work
The Contractor shall submit his/her work schedule to the City's Project Manager prior to the preconstruction meeting. The construction schedule shall show the sequence of work, critical path and estimated time for completion of each segment of work. This schedule must be reviewed R Dependable Const Inc.

Page 139 of 222 ends