Read from the councils' own documents — check the source. Each figure was copied from a staff report, budget, financial statement or set of minutes, by a person or by a language model whose quote had to be found word for word in the document. Every figure links to the passage it came from; the city's original file is the official record. Updated 2026-10-20.
9figures
The city's own electricity
| Date | CCA | Figure | What it is | Source |
|---|---|---|---|---|
| 2025-12-16 | MCE | $623,492.15 a year · city pays · actual / audited | Pinole's total electricity cost across its 821 municipal accounts over the past 12 months, currently on MCE Light Green, was about $623,492.15. product: Light Green | passage · city original |
Grants and projects paid by the CCA
| Date | CCA | Figure | What it is | Source |
|---|---|---|---|---|
| 2026-10-20 | MCE | $131,000 city receives · estimate / proposal | MCE rebates totaling $131,000 for heat pump water heaters at Pinole's Public Safety Building, Swim Center and Senior Center, paid to contractors directly, if the city reserves them by October 30, 2026. | passage · city original |
| 2026-10-20 | MCE | $53,000 city receives · estimate / proposal | MCE heat pump water heater incentive of $53,000 for Pinole's Public Safety Building, part of $131,000 in rebates the council is reserving by October 30, 2026. product: MCE heat pump water heater rebate | passage · city original |
| 2026-10-20 | MCE | $26,000 city receives · estimate / proposal | MCE offers rebates of up to $26,000 per heat pump water heater unit for Pinole city facilities; reservations are due by October 30, 2026. | passage · city original |
| 2026-05-19 | MCE | $6,196 a year · city saves · estimate / proposal | Estimated annual benefit to Pinole's Youth Center from rate optimization, a 100 kWh battery, and MCE Virtual Power Plant revenue, combining bill savings and VPP payments. | passage · city original |
| 2026-05-19 | MCE | 38.14% a year · city saves · estimate / proposal | Estimated 38.14% reduction in Pinole Youth Center's net energy costs from battery storage, rate optimization and MCE Virtual Power Plant revenue, about $6,196 per year. | passage · city original |
| 2026-05-05 | MCE | $340,000 city receives · actual / audited | Pinole secured up to $340,000 in MCE grant funding for backup batteries at the Youth Center and Tiny Tots/Swim Center, reported as a FY 2025/26 accomplishment. | passage · city original |
| 2025-01-21 | MCE | $7,500 city receives · estimate / proposal | Pinole's council is asked to accept a $7,500 Community Partnership Program award from MCE, awarded October 2024, to fund community engagement and outreach under its Climate Action plan. | passage · city original |
| 2024-12-03 | MCE | $30,000 city receives · actual / audited | The City of Pinole received a $30,000 competitive grant from MCE's Community Partnership Program, reported by the City Manager at the December 3, 2024 meeting. | passage · city original |