Furthermore, he launched key initiatives to support department and County of Orange priorities including a Succession Development Program; Mentoring Initiative; employee driven recasting of the department’s Mission, Vision, and Values; Statement of Commitment from the leadership team to Orange County Public Works employees, Public Works Women’s Forum and instituted regular communications with staff in writing and through personal meetings. Ignacio provided key leadership role for the department and was its voice with elected officials and other agencies.

EUCLId ROAd wA Y & SEwE R RECONSTRUCTION PROjE CT, fUll ErTo n Ignacio provided Project Management services to the City of Fullerton. The project consisted of reconstructing or resurfacing approximately 3,700 linear feet of arterial streets between Fern Drive and Williamson Avenue and replacing approximately 1,700 feet of sewer mains between Malvern Avenue and Commonwealth Avenue. The sewer work included removing the existing 10-inch VCP and replacing it with new 12-inch VCP pipe between Commonwealth and Malvern and removing and replacing sewer north of Malvern to the end of the street project limits at Fern without upsizing. The worked also included removing the manholes at the center of the Euclid Street/Chapman Avenue intersection and establishing a new connection point approximately 50 feet to the east along Chapman Avenue as well as reconstructing the double barrel siphon and adjusting invert elevations to achieve a suitable slope. The design utilized a trenchless method to install the siphon beneath the OCPW Brea Creek Channel. Additional tasks included adjusting manhole elevations and reconnected service laterals, constructing new curb and gutter where gutter is absent, constructing ADA compliant curb ramps, and repairing curb, gutter, cross gutters, sidewalks and driveways where required. The City utilized SB1 funds for the road rehabilitation and local funds for the sewer improvements.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 43 255
dElfi no Co nS Un Ji , pe
proJe ct manager
37 years of
ex perience
fi elds
of
ex pertise ROADWAY TRAFFIC ADA RAMP RESIDENTS PAVEMENT
QUALiFiCATiONS
BS: Civil Engineering, University of the Philippines, 1986 ● pE : Professional Engineer #57908 ● CErT ifiCaTE: Engineering Management for Construction, UCLA Extension, 1991 ● CErTi fi CaT E: Building Construction & Management, AOTS Japan, 1990 ● CErTi fi CaT E: Inland Navigation & Management, IFIT Belgium, 1989 bA C kGROUN d
Delfino “Chino” Consunji is an experienced professional engineer specializing in the design, construction, project management and inspection of buildings, private development and public works projects. Chino’s experience includes working for engineering consultants, contractors, developers, construction management firms and municipal agencies. He has served as City Engineer for the Cities of La Habra, Norwalk, Brea, West Covina and Downey and as Public Works Director for West Covina and Downey. He has managed the design and construction of over 500 projects with a total contract amount of more than $500 million over the last 37 years. These projects included arterial highways and residential streets rehabilitation; intersection widening improvements; traffic signal upgrades and safety enhancements; water, sewer storm drain and NPDES improvements; building and facility improvements; and park improvement projects. Chino is a Registered Professional Engineer in the State of California.

ExPERIENCE
RESIdE NTIAL STREETS REHA bI LITATION PROGRAM, downEy
As Public Works Director/City Engineer, Chino oversaw the implementation of the City’s Pavement Management Program (PMP) and 10-year residential streets rehabilitation program. To develop a comprehensive and cost-effective 10-year street improvement program, the City was divided into 10 areas or residential neighborhoods with each year corresponding to rehabilitating a particular area or neighborhood. As directed by the City Council, in order to expedite implementation of the 10-year rehabilitation program and significantly increase the City’s overall network pavement condition index or PCI, Chino worked with the City Manager, Finance Director, financial and municipal bond consultants, and Los Angeles Metropolitan Transportation Authority (Metro) for the issuance and sale of $30 million in Measure M and Measure R Sales Tax Revenue Bonds that were used to fund these street improvements. The $30 million in bond proceeds were required to be expended with three years of bond issuance. Chino was responsible for preparing and sending out the Requests for Proposals (RFP) for the design of the 10 residential neighborhoods; administering the design contracts; overseeing the bid and contract award process and overseeing construction and inspection of these street improvement projects. These projects were completed way ahead of schedule. Over a period of 18 months, 600 residential streets or approximately 70 miles of asphalt pavement were rehabilitated with a total cost of $26.5 million. Rehabilitation included reconstruction, overlay, cape seal and slurry seal of the existing asphalt pavement. These projects included removal and replacement of damaged and/or uplifted concrete sidewalks and curb and gutter and reconstruction of curb access ramps in accordance with current Americans with Disabilities (ADA) requirements.

FY2019/2020 RESIdE NTIAL STREETS REHAbI LITATION, downEy As Public Works Director/City Engineer, Chino oversaw the design, bid and contract award process, construction and inspection of this project. This project rehabilitated 35 residential streets or approximately 7 miles of existing asphalt pavement in the south half of the City with a total cost of $2.8 million. Rehabilitation included reconstruction and overlay of the existing asphalt pavement. This project also included removal and replacement of damaged and/or uplifted concrete sidewalks and curb and gutter and reconstruction of curb access ramps in accordance with current ADA standards. Funding for this project came from Measure R, Senate Bill 1, Vehicle Impact Fees and Developer Funds.

FY2018/2019 RESIdE NTIAL STREETS REHAbI LITATION, downEy As Public Works Director/City Engineer, Chino oversaw the design, bid and contract award process, construction and inspection of this project. This project rehabilitated 43 residential streets or approximately 6 miles of existing asphalt pavement in the north half of the City with a total cost of $2.3 million. Rehabilitation included reconstruction and overlay of the existing asphalt pavement. This project also included removal and replacement of damaged and/or uplifted concrete sidewalks and curb and gutter and reconstruction of curb access ramps in accordance with current ADA standards. Funding for this project came from Measure R, Senate Bill 1 and Vehicle Impact Fees.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 44 256
FY2018/2019 & FY2019/2020 ANNUAL SLURRY SEAL PROGRAM, downEy As Public Works Director/City Engineer, Chino oversaw the design, bid and contract award process, construction and inspection of the Annual Slurry Seal Program. For FY2018/2019 and FY2019/2020, a total of 80 residential streets or approximately 15 miles of existing asphalt pavement throughout the City were slurry sealed with a total cost of $700,000.

Funding for this program came from Senate Bill 1 funds.

TELEGRAPH ROAd TRAFFiC THROUGHPUT ANd SAFETY E NHANCEMENTS , downEy As Public Works Director/City Engineer, Chino oversaw the design, bid and contract award process, construction and inspection of this project. This project reconstructed approximately 1.5 miles of existing asphalt pavement on Telegraph Road from east to west City limits. A joint project with the City of Pico Rivera, this project constructed landscaped median islands, upgraded traffic signals at two intersections, replaced damaged or uplifted concrete sidewalks and curb and gutter and reconstructed curb access ramps to comply with current ADA requirements. The total cost of the project was $8 million with funding coming from federal CMAQ, Measure M, Senate Bill 1, Proposition C and City of Pico Rivera’s share of costs. The project won the 2022 APWA B.E.S. T Project of the Year award in the Transportation category.

OLd Ri VER S CHOOL R OA d PA VEMENT R EHA bi Li TAT i ON , downE y As Public Works Director/City Engineer, Chino oversaw the design, bid and contract award process, construction and inspection of this project. This project reconstructed approximately 1.5 miles of existing asphalt pavement on Old River School Road from Imperial Highway to Arnett Street. This project included installation of fiber optic traffic signal interconnect system, replacement of damaged concrete sidewalks, curb and gutter, driveway approaches and reconstruction of curb access ramps to comply with current ADA requirements. This project also installed Class 2 bike lanes and Class 3 bike routes on Old River School Road within project limits. The total cost of the project was $2.8 million with funding coming from federal STPL and Metro federal earmark exchange funds, Measure M and Measure R. 3Rd STREET PA VEMENT R EHA bi Li TAT i ON , downE y
As Public Works Director/City Engineer, Chino oversaw the design, bid and contract award process, construction and inspection of this project. This project reconstructed 1 mile of existing asphalt pavement on 3rd Street from Old River School Road to Paramount Boulevard. This project included replacement of damaged concrete sidewalks, curb and gutter, driveway approaches and reconstruction of curb access ramps to comply with current ADA requirements. The total cost of the project was $700,000 with funding coming from the $30 million Measure and Measure R Bond Proceeds. 5TH S TREET PA VEMENT R EHA bi Li TAT i ON , downE y As Public Works Director/City Engineer, Chino oversaw the design, bid and contract award process, construction and inspection of this project. This project reconstructed approximately 0.5 mile of existing asphalt pavement on 5th Street from Lakewood Boulevard to Brookshire Avenue. This project included replacement of damaged concrete sidewalks, curb and gutter, driveway approaches and reconstruction of curb access ramps to comply with current ADA requirements. The total cost of the project was $610,000 with funding coming from the $30 million Measure and Measure R Bond Proceeds.

FiRESTONE bOULEV ARd PA VEMENT R EHA bi Li TAT i ON & T RAFFi C Si GNAL UPG RA d ES , downE y
As Public Works Director/City Engineer, Chino oversaw the design, bid and contract award process, construction and inspection of this project. This project rehabilitated approximately 0.6 mile of existing asphalt pavement on Firestone Boulevard from Old River School Road to west City limit. This project also installed a new traffic signal at Firestone Boulevard and Arnett Street, constructed landscaped median islands, installed a new entry monument sign, replaced damaged or uplifted concrete sidewalks and curb and gutter and reconstructed curb access ramps to comply with current ADA requirements. The total cost of the project was $2.6 million.

ANNUAL Mi SCELLANEOUS CONC RETE R EP A i RS & A dA I MPROVEMENTS, downE y In 2018, as required by the Americans with Disabilities Act (ADA), the City of Downey adopted the City’s ADA Transition Plan.

The ADA Transition Plan included an inventory of the City’s ADA-compliant infrastructure at City facilities and within the public right-of-way. The Plan also included a comprehensive list of City facilities and infrastructure that need to be upgraded and/or repaired in order to meet or comply with current ADA standards. In an effort to reduce backlog of ADA repairs and upgrades throughout the City and thereby minimize the City’s liability, the Public Works Department developed an Annual Miscellaneous Concrete Repairs and ADA Improvement Program. As Public Works Director/City Engineer, Chino oversaw the design, bid and contract award process, construction and inspection of these annual projects. These projects removed and replaced damaged and/or uplifted concrete sidewalks, curb and gutter and driveway approaches and constructed ADA-compliant curb access ramps in accordance with the City’s ADA Transition Plan. In addition, Public Works staff worked with Downey Unified School District in constructing concrete sidewalks and ADA-compliant curb access ramps along the frontage of elementary and middle schools. From 2018 to 2022, Public Works completed ADA upgrades and concrete repairs at 1,300 locations at a total cost of $3.5 million. Funding for these projects came from Senate Bill 1, TDA Article III and Downey Unified School District share of costs.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 45 257
JoE dyEr , pe
proJe ct manager & traffic engineer
45 years of
ex perience
fi elds
of
ex pertise roadway traffic pavement water signal
QUALiFiCATiONS
BSCE: Civil Engineering, Ohio State University, Ohio mS & p hd program: Virginia Polytechnic Institute & State University,Virginia pE #31626: Registered Civil Engineer TE #1200: Registered Traffic Engineer CErT ifiCaTE: Certified in Building & Facility Maintenance, 2005 bA C kGROUN d
Joe Dyer has achieved a milestone of 45 years of expansive experience serving a number of Southern California Cities including Chino Hills, Glendora, Bell Gardens and Whittier, along with work as a Junior Civil Engineer for the California Department of Transportation. His role on a litany of CIP projects involved working as a Transportation Planner, Senior Engineer, City Traffic Engineer, and as The Director of Public Works. In over 4 decades worth of time serving, he has perfected his skills in disciplines involving street maintenance and rehabilitation, water and storm drains, parks and public facilities, bridges, transit, sewer, design engineering, contract administration, residential development, environmental litigation, and federal regulations compliance, among many other disciplines and project variations. Joe additionally has great familiarity in coordinating with City officials and councils, utility owners, and has served as liason between stakeholders and governing bodies. Joe has worked with several developers, engineers, and City Councils, becoming well established in advocating for a City’s best interest.

ExPERIENCE
TRAFFiC MANAGEMENT MASTER PLAN, Ch I no h I llS
Joe developed the Master Plan for the purpose of a fiber optic traffic management system, along with a signal communication system for the City . He also prepared RFPs and sought proposals from traffic signal consultants. Budget:
$300K
TRAFFiC SiGNAL bACkPLATE IMPROVEMENTS, Ch I no h I llS
Joe served as the Plan Coordinator for the Traffic Signal Backplate Improvements Project. The work was with a signal contractor and involved installing retroreflective borders for a selected number of traffic signal locations. This project was funded through an HSIP grant and was budgeted at approximately $123K. bO YS REPU bL IC dRI VE AT CITY HALL PEdEST RIAN SIGNAL IMPROVEMENTS, Ch I no hIllS Joe provided plan, design and contract administration on the Boys Republic Drive at City Hall Pedestrian Signal Improvements Project. The work called for the installation of a H.A.W.K. signal for the purpose of enhancing pedestrian crossing, as well as effectively manage vehicular traffic at the intersection. Budget: $150K.

PEYTON dRI VE ANd EUCALYPTUS AVENUE TRAFFIC SIGNAL MOdI FICATION, Ch I no h I llS Joe provided plan, design, and contract administration for phasing modifications on the Peyton Drive and Eucalyptus Avenue Traffic Signal Modification Project. The phasing was located at the intersection of Peyton Drive and Eucalyptus Avenue with the purpose of providing protective left turns and overlap right turn indicators. Budget: $50K.

GRANd AVENUE/SR71 TRUNk RELIEF AT bO YS REPUbL IC dRI VE, Ch I no h I llS Joe provided plan, investigations, and schedule reconstruction on the Grand Avenue and SR71 Trunk Relief at Boys Republic Drive Project. The reconstruction involved an existing sewer trunk line with modified manhole to improve the flow efficiency.

Budget: $213K.

CITYwIdE wA STEwA TER MASTER PLAN STUdY , Ch I no h I llS For the Citywide Wastewater Master Plan Study, the City had retained a consultant to evaluated the City’s sewer collection system with its ability to meet projected demands for the upcoming years and identify needed capital improvements.

Budget: $650K.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 46 258
POMONA RINCON LIFT STATION, Ch I no h I llS
Joe provided contract administration for upgrading the existing Pomona Rincon Lift Station facility with new pumps, additional telemetry, level sensing systems, flow meter and modifications to wet well as identified in the Pomona Rincon Left Station Evaluation Study. Budget: $486K.

EUCALYPTUS AVENUE RECYCLEd wA TERLINE INSTALLATION & TRAFFIC IMPROVEMENTS, Ch I no h I llS
Joe provided plan, design, and contract administration for the installation of a recycled water line at Veterans Park, pavement rehabilitation for Eucalyptus Avenue, and the installation of a H.A.W.K. signal at the Galloping Hills Road Pedestrian Crosswalk. The project work included replacement of existing ADA ramps, adjust utility facilities, traffic striping and electrical work. Budget: $1.7M.
wA TER MAIN SA d dL E REPLACEMENT (PHASES I, II & III), Ch I no h I llS Joe provided plan, design and contract administration for over 1000 saddles and services replacement in residential neighborhoods on the Water Main Saddle Replacement Project - Phases I, II & III. Budget: $10M.

MAROON bE LL wI NCHESTER wA TER MAIN REPLACEMENT, Ch I no h I llS For the Maroon Bell Winchester Water Main Replacement Project, Joe provided plan, design and construction administration for replacing 4,700 feet of 8-inch steel water main line in the Maroon Bell neighborhood. The project work involved working with the local neighborhood Homeowners Association. The work also included refurbishing the pavement of 10 of the private streets. Budget: $1M.
1,2,3 TCP REMEdI ATION, Ch I no h I llS
This project was developed for the purpose of evaluating and remediating all of the City of Chino Hills’s water wells for 1,2,3 TCP contamination. Joe was tasked with evaluating proposals from consultants along with the construct of a TCP removal facility at the corner of Eucalyptus Avenue and Pipeline Avenue. Joe also negotiated property exchange with the local fire district, as well as supervised the construction administration activities.

RAMONA AVENUE wA TER MAIN REPLACEMENT, Ch I no h I llS
J o e p r o v i d e d p l a n , d e s i g n a n d c o o r d i n a t e d w o r k w i t h C i t y ’ s W a t e r D i v i s i o n o n t h e R a m o n a A v e n u e W a t e r R e p l a c e m e n t Project. The work called for the replacement of 680 feet of a 2-inch water main, along with 9 service lines. The construction was located at Ramona Avenue, from Bird Farm Road to Mesa Boulevard. Budget: $400K.

CITYwIdE STORM dR AIN MASTER PLAN STUdY , Ch I no h I llS Joe provided coordination and the retention of a consulting engineer to Update the Storm Drain Master Plan to develop the tools needed to plan, operate and maintain the City’s storm drain infrastructure. Budget: $848K.

VRAVIS CIRCLE dR AINAGE IMPROVEMENTS, Ch I no h I llS
Joe provided plan, survey, design, and contract administration to install a storm drain facility on Vravis Circle at Carriage Hills Lane to address the prevailing water issue at the intersection. Budget: $43K.

EUCALYPTUS AVENUE STORM dR AIN IMPROVEMENT, Ch I no h I llS Joe provided plan, design and contract administration for the replacement of an open trapezoidal channel with a storm drain pipe from Peyton Drive to Pipeline Avenue on the Eucalyptus Avenue Storm Drain Improvement Project. Further work called for the construction of a sidewalk and curb and gutter following the installation of the pipe. Budget: $2M.

LOS SERRANOS CHANNEL MITIGATION, Ch I no h I llS
Joe provided plan and contract administration on the Los Serranos Channel Mitigation Project. The purpose of the project was to create nine acres of wildlife habitat along the Los Serranos Channel area. Budget: $1.38M.

GATEwA Y MONUMENT AT CHINO HILLS PAR kwA Y, Ch I no h I llS Joe provided Design Engineering on the Gateway Monument at Chino Hills Parkway, along with coordinating with Caltrans.

The work required the construction of the City’s entry monument, new irrigation and landscaping in Caltrans’ center median. Budget: $80K.

GRANd A VENUE MONUMENT SIGN, Ch I no h I llS
Joe provided Design Engineering for the construction of a new City monument sign on Grand Avenue near Grand Avenue Park. Budget: $200K.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 47 259
JUSTi n SmE ETS , pe, pls, Qs d
proJe ct manager
18 years of
ex perience
fi elds
of
ex pertise roadway traffic LASER SCAN DRONE SURVEY signal QUALiFiCATiONS
BS: Civil Engineering, California State University, Fullerton, 2007 ● CErTi fi E d : AutoCAD Professional ● pE #78314:

Registered Civil Engineer ● plS #9293: Professional Land Surveyor ● qSd /q Sp # 00852: Qualified SWPPP Developer ● (prior) oC T a pav EmEnT CErTi fiECaTi on: Pavement Rehabilitation Evaluation bA C kGROUN d
Justin has 18 years of experience in civil engineering design, municipal engineering and facilities design, along with construction management, and construction administration. Using AutoCAD Civil 3D, Justin handles managing and developing engineering plans and specifications, mapping, executing land development and grading design projects, conducting earthwork calculations, and incorporating typical designs. He is proficient in federally funded projects and familiar with the Caltrans Local Assistance Procedures Manual. Justin has successfully taken multiple projects from the initial federal funding application, to the Preliminary Environmental Study, to E-76 approval, and all the way through construction of audited federally funded construction projects. He has experience managing construction projects and handles planning and running kickoff meetings with the contractor, reviewing project submittals, RFIs, CCOs, checking contractor invoices against field quantities, and coordinating daily construction details with the contractor and inspector.

He has completed multiple SWPPPs and erosion and sediment control plans per the latest Construction General Permit.

Justin is continuously increasing his skills in modern design software, and his knowledge of industry design standards.

ExPERIENCE
HARbO R bL Vd. & G ISLER AVENUE INTERSECTION wIdE NING PROjE CT, CoSTa mE Sa Justin was the Project Manager on the Harbor Blvd. & Gisler Avenue Intersection Widening project in the City of Costa Mesa.

Due to the close proximity of the intersection to the I-405 Harbor on-ramp, there were extremely high turn movements both eastbound on Gisler Avenue turning left onto Harbor Boulevard as well as southbound on Harbor. As a result, this created heavy congestion during peak traffic hours. In order to alleviate the congestion, phase I of the project included only eastbound improvements; converting the eastbound optional through-right lane to an optional through-left lane, and adding an eastbound right-turn lane. Phase II entailed a conceptual feasibility study and right-of-way acquisition requirements for both north and southbound improvements, including the addition of a southbound right-turn lane, and the extension of the northbound optional through-right lane. The scope of work also included installing an overhead freeway sign, which required working with SoCal Gas to relocate a gas line in conflict with footings for the overhead sign. A detailed field analysis, specifications, and plans were provided, including measurements and exhibits, in conformance with MUTCD, Caltrans, and City standards. Additionally, coordination with SAF-r-DIG and utility companies was essential to perform potholing and identify utility obstructions.

RESIdE NTIAL STREETS PAVEMENT REHA bI LITATION PROjE CT FOR AREAS 1, 2, & 4, downEy Justin is providing the City of Downey with Project Management services for the Residential Streets Pavement Rehabilitation Project for Areas 1, 2, and 4. The main objective is to improve the PCI of the area residential street segments in order to extend the street service life, improve safety, minimize costs and maintenance needs, and enhance aesthetics.

In order to accurately develop a scope of work and fees for the design services, OE conducted a detailed field evaluation, a thorough review of the City’s Pavement Management Plan, and approximated the costs for the construction activities to develop a final list of residential street segments. OE was then able to determine the quantity of streets that could be incorporated into the engineering design, which rehabilitation method to use and which method could be feasibly rehabilitated while adhering to the City’s available budget, along with providing recommendations and estimates. Upon approval by the City, the team then began to prepare separate PS&E packages for areas 1, 2 and 4. The work across the three zones covered nearly 29 miles of residential streets. On a number of segments OE is using straight grade between tie-in points at adjacent segments to maximized drainage slopes. A total of 164 Curb Ramps are being reconstructed to meet ADA compliance along with 85 total driveways, in addition to street widening and single-sided street parking construction.

Collaboration with Caltrans, LA City Flood Control District and Union Pacific Rail Road was also performed in order to acquire permit acquisitions on the segments. The work was completed on time within the assigned schedule and within the set budget.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 48 260
190TH STREET PAVEMENT REHAbI LITATION PROjE CT, Tor ran CE Justin was the Project Manager on the 190th Street Pavement Rehabilitation Project in the City of Torrance. The project included preparing PS&E, including a plan and profile, traffic striping and signing plans, traffic control, phasing plans and detour plans. The scope of work consisted of rehabilitating approximately 3,500 LF of roadway on 190th Street, Hawthorne Boulevard to Prairie Avenue. 190th St. is a major 6 lane arterial that runs parallel to the I-405 freeway and is a major gateway to the South Bay. The design included portions of grind and overlay, full depth reconstruction, AC cap, removal and replacement of curb gutter, and sidewalk, installing ADA-compliant ramps, and installing video detection systems at intersections, as well as various related improvements. The project required actively processing submittals through all reviewing agencies and ensuring the project design proceeded smoothly and successfully. bA LL ROA d & SUNk IST STREET wIdE NING PROjE CT, anahE I m Justin was the Project Manager on the Ball Rd. & Sunkist St. Widening Project for the City of Anaheim. Justin was responsible f or t he d r a i nage r e port , s i z i ng ca t c h b a s i n s, and pr e p ar i ng t he pr e l i m i nary S W P P P f or t he pr o j ect . T he pr o j ect i n v o l v ed widening at Ball Road and Sunkist Street to accommodate additional turn lanes on Sunkist Street, and additional thru-lanes along Ball Road, in order to maximize traffic flow approaching and exiting the 57 freeway. The widening created the need to relocate 3 catch basins. All 3 catch basin sizes were analyzed and adjusted based on hydrologic and hydraulic flows.

LOS SERRANOS wI d ENING AN d S I d E wA Lk IMP ROVEMENT PROj ECT, Ch In o hIl lS Justin was the Project Manager on the Los Serranos Infrastructure - ATP Project. The proposed project limits included the widening of ten rural residential streets in the Los Serranos area of Chino Hills. The project limits are located just west of the 71-freeway towards the east end of the City of Chino Hills. The project locations are surrounded by single family residential homes. The project is funded through the Active Transportation Program Project. Currently the Los Serranos area is very rural. The project limits include very minimal curb, gutter, and sidewalk. The ATP grant proposed provided funding for curb, gutter, and sidewalk on one side of each of the ten streets. The design included widening one side of the street on ten street segments within the City of Chino Hills.

SHOEMAkER AVENUE PAVEMENT REHAbI LITATION PROjE CT, norwalk Justin was the Project Manager for the City of Norwalk for this pavement rehabilitation and drainage improvement project.

The project limits on Shoemaker Avenue start on Rosecrans Avenue and ends at the Firestone Frontage Road. This 0.25-mile collector street segment was heavily distressed and showed block cracking, alligator cracking, and potholes. The scope of work included preparing plans, specifications and estimates for this 2,000 LF roadway. The project involved grind and overlay, full depth reconstruction, AC cap, sidewalk construction, cross-gutter construction, and drainage improvements.

Furthermore, the roadway and adjacent parkway had a major drainage issue; the most cost-effective solution was drawn up for the City to relieve water ponding and increase the safety of the residents. As a result of Caltrans’ impact on the I-5 Freeway widening, Caltrans designed and implemented the drainage improvements. 7 YEAR ANNUAL RESIdE NTIAL ROAd wA Y MAINTENANCE PROjE CTS, dI amond Ba r Ignacio served as the Construction Manager to the City of Diamond Bar on their annual arterial and residential roadway maintenance projects for an annual period of 7 years. Years 2010 and 2011 were awarded as separate contracts. The City awarded OE an additional 3-year contract for 2012–2014. In 2015, the City of Diamond Bar awarded OE yet another annual rehabilitation project. The project sizes and costs were: 2010: 11.8 miles of arterial & residential streets ($908 K ) , 2 0 1 1 : 1 9 m i l e s o f art e r i a l & r e s i de n t i a l st r ee t s ( $ 1 . 8 M ) , 2 0 1 2 : 1 0 m i l e s o f art e r i a l and r e s i de n t i a l st r ee t s ( $ 1 . 1 M ) , 2 0 1 3 :
1 3 m i l e s o f a r t e r i a l & r e s i d e n t i a l s t r e e t s ( $ 1 . 3 M ) , 2 0 1 4 : 1 4 . 5 m i l e s o f r e s i d e n t i a l , a r t e r i a l & c o l l e c t o r s t r e e t s ( $ 1 . 8 M ) , 2015: 14 miles of residential, arterial & collector streets ($1.75 M) and 2016/2017: 16.6 miles of residential and collector streets ($1.58 million). The general scope of work for each year’s project included localized R&R patching, grind and overlay, cape and slurry seal, traffic loops, traffic striping, and required heavy traffic phasing and traffic control review.

Justin assisted the City through the project bidding phase, developing text and stipulations for the bid package to ensure contractor availability during the desired working months. Due to the proximity to freeways, Justin also coordinated with Caltrans to obtain encroachment permits for the City for four of the projects, which was essential. bE NNETT AVENUE, wA SHINGTON AVENUE, wE STRIdG E AVENUE ANd bE NdE R AVENUE CUL- dE -SACS PRO jE CT, glEn dora
Justin served as Project Manager to the City of Glendora on the Bennett Avenue, Washington Avenue, Westridge Avenue and Bender Avenue Cul-De-Sacs Project. This includes the design of nearly 7,000 LF of new 8-inch ductile iron/C909 PVC water mains to improve flow, pressure and fire protection, along with 311,000 SF of streets requiring improvements. Other work includes a striping enhancement concept to incorporate marked class II bike lanes, repurposing crosswalk warning lights, reconstructing and replacing 16 ADA curb ramps for compliance, traffic signal inductive loop replacement, and water main appurtenance installation and replacement. A section of pipeline located at Bennett Avenue near Valencia Street passes beneath a storm drain, requiring directional drilling to facilitate new water main installation through the area. This was accompanied by assessments of fire hydrants, air and vacuum release valves, and water meters and services laterals.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 49 261
Jo na Tha n wU, pe, pmp, Qs d
constr Uc tion manager
30 years of
ex perience
fi elds
of
ex pertise roadway ada ramp pavement widening water QUALiFiCATiONS
m S C : Civil Engineering, University of Southern California, 1985 ● mS: Civil Engineering, University of Southern California, 1990 ● pE : #54747: Registered Civil Engineer ● pmp: Project Management Professional ● qSd # 25128: Qualified Stormwater Pollution Prevention Plan Developer

bA C kGROUN d
Jonathan is a registered Civil Engineer with over 29 years of public works experience. His credentials include Project Management Institute certification as a Project Management Professional (PMP), SWPPP Developer qualification, and graduating with both a Bachelor’s and a Master’s in Science Degree for Civil Engineering from the University of Southern California (USC). Jonathan’s workforce experience includes working for Caltrans as a Construction Manager and Resident Engineer, and in providing Construction Management to the Cities of Anaheim, Rancho Cucamonga, Diamond Bar, and Placentia, where his involvement produced the delivery of multi-million-dollar CIP projects. Jonathan has also performed as an interim City Engineer and Principal for the Cities of El Monte and Baldwin Park. Throughout his lengthy experience, Jonathan was responsible for supervising and managing on-site construction work in accordance with the contract documents, plans, specifications, and code requirements of the projects. He was also responsible for reviewing the daily, weekly, and critical path work schedule in search of any potential delays or conflicts and communicating potential issues to the contractor. Jonathan’s experience with the Cities extends to multi-agency coordination involving Caltrans, the County, and utility companies.

ExPERIENCE
STREET wIdEN ING/RR GRAdE SEPARATION/EASEMENT/UTILITY COORdI NATION, plaCEn TIa Jonathan was the Construction Manager for the City of Placentia and was in charge of the City’s Capital Improvement Project (CIP) program that held an annual budget of $5.5 million, with additional funding acquired from Caltrans and OCTA for specific projects. He was responsible for scheduling, budgeting, Right-of-Way negotiations, easement dedications, project and construction management in conforming to the requirements of federal and Caltrans funding and local assistance guidelines. He chaired utility coordination meetings with local utilities and the City for several grade separation projects on a quarterly and ad hoc basis. In addition, he negotiated with residents involving an easement dedication.

Jonathan assisted utilities in obtaining easements from residents for relocation of utility lines and was responsible for the planning and execution of full project life cycle tasks such as plan review, utility detection, and construction. Major projects included street widening, railroad grade separations, and undergrounding of utilities.

STREET & SLURRY SEAL REHAbI LITATION - PHASE III, lagUn a BEaCh Jonathan lent his skills in providing full Construction Management and Inspection Services for the City of Laguna Beach on Phase III of the Street and Slurry Seal Rehabilitation Project. The project covered the span of three phases in three years.

The project limits for phase III included two areas: Area A-Coast Royal, and Area B-South Laguna Village. These areas are in South Laguna Beach, in the neighborhoods between West Street and 10th Avenue/Sunset Avenue. The work included variable grind and overlay in some areas, and Type I Slurry Seal in other areas, along with new traffic signal poles. Lastly, the project encompassed parkway and curb and gutter improvements, and signage and striping. Due to local residents, OE provided an informative web page, web maps and a telephone hotline to provide necessary updates and information.

GRANd AVE. bE AUTIFICATION PROjE CT - FEdE RAL PROjE CT HPLUL-5455, dI amond Bar Jonathan provided Construction Management and Inspection services to the City of Diamond Bar on the Grand Avenue Beautification Project. The project consisted of traffic signal equipment replacement, landscape and irrigation improvements, decorative crosswalks, and asphalt pavement rehabilitation of Grand Avenue at Diamond Bar Boulevard and Grand Avenue at Longview Drive. New decorative traffic signal poles and mast arms were installed within in the existing right-of-way. Several signal foundations required removal and, due to utility locations, the placement of temporary signal equipment to place a new foundation in the same location. Two of the signal foundations required re-design and engineering calculations due to utility conflicts. A decorative City monument sign was installed east of the Longview Drive city limit, and decorative pre-cast concrete posts and wood rails were installed along the sidewalks and median islands. This SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 50 262
was tied together with irrigation, landscaping, tree wells with tree grates including in-ground up-lighting for the parkway trees, and median landscaping with decorative rocks set in a concrete bed. Work also included the installation of decorative sidewalks and ADA ramps with colored concrete and decorative pavers at each intersection. Due to the traffic volume on Grand Avenue, this work was scheduled and coordinated in two phases: inside and outside lanes over two weekends. The removals began on Friday evening, concrete was formed and poured on Saturday, pavers were installed on Sunday, and full traffic operations were restored for the Monday morning peak traffic.

OMNITRANS : bU S RAPId TR ANSIT PROjE CT: CONCRETE HARdS CAPING, Sa n BEr nard In o Omnitrans is the regional public transit authority in San Bernardino County, California, where Jonathan provided Construction Management services on the Bus Rapid Transit Project. This $197 million federally funded project featured a 16-mile-long bus lane and 16 stations with four park-and ride facilities. Jonathan oversaw the Construction Management team, QA/QC procedures, and safety & security management during the design, construction, and commissioning of the project. He was responsible for compliance with Federal Transit Administration (FTA) requirements and policies. In addition, he maintained communications with the public and internal stakeholders resolving any issues with the contractors, citizens and local businesses.

MORNING CANYON ROAd RECONSTRUCTION PROjE CT, dI amond Ba r Jonathan was a Project Manager on this project for the City of Diamond Bar. Morning Canyon Road is a two-lane residential road beginning at Diamond Bar Boulevard and ending with a cul-de-sac nearly 4,000 feet to the northwest. The initial scope of work entailed removing 16 large pine trees that were causing extensive root intrusion into the roadway section; PCC work included 1,637 SF of sidewalk, 120 LF of curb and gutter, new ADA access ramps, striping/pavement markings, and the reconstruction of a Los Angeles County Public Works (LACPW) maintained catch basin located at the Southwest corner of Diamond Bar Boulevard and Morning Canyon Road. However, after a community meeting to inform the public about the project, the residents requested the staff explore an alternative approach to preserve the mature existing trees. After exploring some new options, the new scope of work entailed realigning the curb and moving it 8 feet closer to the roadway centerline, resulting in the elimination of the existing parking lane, and preserving the existing trees. Furthermore, the innovative design included relocating the sidewalk to the new back of curb alignment, resulting in a wider parkway area being backfilled with Class A Top Soil and topped with 2 inches of mulch. Three new LACPW catch basins were required to be constructed, one at the beginning of the curb re-alignment, across from Stonepine Drive, the other on the south side of Presado Drive and the third at the end of the curb return alignment before Diamond Bar Boulevard. The fourth catch basin located at Canyon Park Drive and Morning Canyon Road was abandoned to preserve a tree across from Canyon Park Drive.

ANNUAL SLURRY SEAL, STREET, CURb RAMP, & dR AINAGE IMPROVEMENTS, El mon TE, Bal dw In park & hawa II an gardEnS
Jonathan performed City Engineering services at various times for the Cities of El Monte, Baldwin Park, and Hawaiian Gardens. His assigned tasks included reviewing design professional proposals to prepare project construction documents, coordinating and scheduling with staff, managing the Capital Improvement Program, overseeing the staff management through project completion, and providing analysis of requests for information, change orders, time/material verification and project close-outs. In regards to the engineering operations, Jonathan was responsible for managing the budgets of development and redevelopment projects, capital improvements, regulatory compliance, general engineering and traffic engineering, all while managing and utilizing department staff to ensure completion of the priority projects. Jonathan also performed general engineering duties for the Cities, which included procuring design professionals to prepare project construction documents, performing plan check services, initiating construction contract procurement procedures, providing analysis of RFI’s and change orders, time and material verification, and managing the projects to completion and project closeout. The type of project work included building construction and renovation, site designs, integration of private development improvements, street construction and improvements, storm drain improvements, underground water and sewer improvements, coordinating various funding sources, regulatory compliance, and managing the engineering and field staff of the Public Works Department.

FY 19/20 STREET & SANTIAGO bL Vd. RE HAbI LITATION PROjE CT, vIl la park Jonathan provided full Construction Management and inspection services for the City of Villa Park on the FY 19/20 Street Rehabilitation and Santiago Boulevard Rehabilitation Project. The project limits included various residential streets north of Taft Avenue as well as a 1.2 mile stretch of Santiago Boulevard from Sycamore Street to North Wanda Road. The project entailed both variable and full-width AC cold milling (depending on the location), and ARHM overlay, digouts for AC sections in poor condition, removal and reconstruction of PCC standard curb and gutters and rolled curbs, drainage improvements, adjusting existing manholes and water valves to grade, re-establishment of existing monuments, as well as striping and detector loop replacement.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 51 263
lUd wig SmE ETS , pe
constr Uc tion manager
40 years of
ex perience
fi elds
of
ex pertise ROADWAY TRAFFIC ADA RAMP SLURRY SEAL SURVEY
QUALiFiCATiONS
BS: Civil Engineering, California State University, Long Beach, 1979 ● ma: Military Science, Texas A & M, 1990 ● US army: Command & General Staff College, 1989 ● pE #37221: Registered Civil Engineer ● aCTvE mEmBEr : APWA, ASCE, NSPE, SAME bA C kGROUN d
Ludy has over 40 years of civil engineering experience with focus on Project Management and Construction Management.

He also has experience in the design of civil engineering projects such as street, sewer, water, and storm drain projects.

Ludy has management level experience working in public works departments in cities throughout Southern California. His experience includes public agency budgeting, project implementation, project design, PS&E development, contract bidding, award administration, construction management and project closure reporting. He has selected, directed and managed consultants, architects and engineers as required in order to meet public works department goals and objectives. He has supervised and trained City staff junior engineers. His many responsibilities included providing project management for federally funded projects, and state funded projects.

ExPERIENCE
bA LL R d. & S UNk IST ST. INTERSECTION wIdE NING & ROAd wA Y IMPROVEMENTS, anahE I m Ludy provided Construction Management services to the City of Anaheim on the Ball Road and Sunkist Street Intersection Widening & Roadway Improvements Project. Ball Road and Sunkist Street are designated as Primary and Secondary arterials, respectively, on the County’s Master Plan of Arterial Highways (MPAH). Ball Road was striped for 1 dual left and 3 through lanes in the eastbound direction and 2 left, 2 through and 1 right – turn lane in the westbound direction of travel.

Sunkist Street was striped for a single left and 2 through lanes per direction of travel. 4 public schools are located on or adjacent to Sunkist Street within the 1 mile stretch between Ball Road and South Street. The Design Phase consisted of the preparation of the contract plans, specifications and estimates for the improvement of the project. The Construction Phase consisted of excavation, clearing and grubbing, placement of new AC pavement, construction of concrete curb and gutter, driveways and access ramps, construction of concrete sidewalks, storm drain modifications, relocation of existing facilities, construction of a concrete bus pad, traffic signal modifications, striping, and CMU wall relocation and landscaping.

Proposed landscaping along the project roadways included drought-tolerant and low-maintenance plantings and trees. The Right-of-way Phase consisted of the acquisition of 9 partial takes totaling approximately 3,661 square feet and 11 Temporary Construction Easements totaling approximately 2,661 square feet of right-of-way. The length of these improvements was 0.44 centerline miles. Traffic to the schools, as well as traffic to and from the adjacent SR-57 freeway, resulted in a southbound left turn demand in the AM peak period that neared 500 vehicles. The intersection operated at service level “C” during the PM peak hours. The project corrected operational deficiencies at this intersection by widening Sunkist Street by 5 ft. along each of the east and west curbs, north and south of the intersection. This provided a dual southbound left -turn lane on Sunkist Street. In addition, the project widened Ball Road at the Sunkist Street intersection, providing an exclusive westbound right turn lane while converting the lane to a third westbound through lane. The proposed 3rd west bound thru lane mitigated vehicular queuing that consistently backed up to SR-57 southbound off-ramp during PM peak hours. With these improvements in place, the intersection service level improved from “D” (0.81) to “B” (0.64) during the PM peak hour.

PHASE 3 LOCAL STREETS REHAbI LITATION (zO NE 24, 27, & 32), norwalk Ludy provided Construction Management and inspection services to the City of Norwalk on the 3rd Stage of Construction of the Local Streets Rehabilitation Paving Improvements. The work included three separate City projects (No. 7924-Zone 24.

No. 7925-Zone 25, and No. 7926-Zone 32). Stage 1 of this project included concrete improvements, and Ludy was assigned as the construction manager for Zone 32 of that phase. Stage 3 included a variety of pavement rehabilitation methods including full-depth repair, grind and overlay, and slurry seal for Zones 24, 27, and 32. Twenty-one streets with a total of 3.6 centerline miles were included as part of this project. These limits were within the two blocks of Highdale Street between Elaine Avenue and Ibex Avenue which had a PCI rated less than 25 (very poor). The streets were also adjacent to Edmondson Elementary School, requiring careful coordination with the school. The replacement of the deteriorated pavement and accessibility ramps was important to improving the safety of the school zone and extending the useful life of the streets.

The rehabilitation work involved street repaving which included curb and gutter repairs, slotted cross gutter replacements and pedestrian accessibility ramps at intersection corners to meet current standards.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 52 264
ASSET MANAGEMENT PLAN, Sa n d IEg o
As the Project Manager for the Port District in San Diego, Ludy managed their Asset Management Plan. Asset management plan summarizes the current asset profile (e.g., installation, consumption, valuation, condition, and management strategies), levels of service, risk assessment and the recommended short and long term prediction of capital investment profile. The development of asset management plan involves the use of life-cycle costing and optimal decision-making methodologies. The categories of assets included the Port’s wharfs, piers, seawalls, bulkheads, marinas, docking facilities, marine transit facilities, storage tanks, parks, buildings, streets and parking lots, launch ramps, and electrical systems.

STREET & SLURRY SEAL REHAbI LITATION - PHASE III, lagUn a BEaCh Ludy lent his skills in providing full Construction Management and Inspection Services for the City of Laguna Beach on Phase III of the Street and Slurry Seal Rehabilitation Project. The third phase of this project covered the span of three phases in three years. The project limits for included two areas: Area A-Coast Royal, and Area B-South Laguna Village. These areas are in South Laguna Beach, from the neighborhoods between West Street and 10th Avenue/Sunset Avenue. The work included variable grind and overlay in some areas, and Type I Slurry Seal in other areas, along with new traffic signal poles. Lastly, the project encompassed parkway and curb and gutter improvements, and signage and striping. Due to local residents, OE provided an informative Web Page, Web Maps and a Telephone Hotline for updates and information.

ARROYO dRI VE NEIGHbO RHOOd IMPROVEMENTS, monTEBEll o
Ludy provided construction management services to the City of Montebello on the Arroyo Drive Improvement Project with limits on Arroyo Drive from Astra Drive to Glen Avenue. This project includes pavement rehabilitation (2”-3” grind and overlay), ADA ramp, curb and gutter, and driveway repairs, storm drain improvements, and associated improvements. The budget for this project is $1,239,085 made up of STPL Funds ($1,063,000) Measure R ($146,045) and Prop C ($30,040) funds, and full compliance with all applicable requirements was essential. The project limits on the north side are adjacent to the back-lot of St. Joseph’s Salesian Youth Retreat Center and Don Bosco Technical Institute. Coordination for parking access was vital. The Astra Drive neighborhood (cul-de-sac) and Potrero Heights Park and Community & Senior Center at the west end of the project limits also required coordination, since the parking lot and residential neighborhoods can only be accessed from Arroyo Drive.

Sk ETCHERS 2901 ANd TUNNEL PROjE CT, hEr mo Sa BE aCh
Ludy served as Construction Manager on the Sketchers 2901 and Tunnel Project for the City of Hermosa Beach. The purpose of the project was to construct a subterranean pedestrian tunnel connecting the 2901 PCH Building and the 3001 PCH Building currently under construction as a larger development project within the City for Skechers. The tunnel will run across 30th Street.

LOCAL STREETS REHAbI LITATION PROGRAM PHASE I - zO NE 3, norwalk Ludy served as Construction Manager on the Local Streets Rehabilitation Program Phase I (Concrete Improvements) in Zone 3, which is bound by the Union Pacific Railroad to the Northwest, the I-5 Freeway to the Northeast, Imperial Highway to the South, and Firestone Boulevard to Southwest. The project involved removal and replacement of sidewalk (3,000 SF); curb and gutter (2,600 LF); new and replacement ADA curb ramps (93 ramps and 10 truncated domes); driveway approach repairs (500 SF); cross gutter replacements (29 locations with associated curb ramps); including incidental asphalt work, utility relocations and traffic control.

NEwP ORT bO ULEVARd widE NiN G iM PROVEMENTS PROjE CT, CoSTa mE Sa Ludy lent his skills in providing Project Management for the City of Costa Mesa on the Newport Boulevard Widening Improvements Project. The project consists of widening a portion 77 Fair Drive of southbound Newport Boulevard to accommodate a fourth through lane and improve its Level of Service from the current “F” rating (ranging from

1.10 to 1.30). The section of roadway to be enhanced extends approximately 2,700 linear feet southwest from 19th Street to the Superior Avenue turn-off located northeast of 17th Street. The project is located within Caltrans jurisdiction and requires traffic signal modifications, utility and street light relocations, and right-of way acquisitions to accommodate the additional through lane and right-turn pockets.

ORANGE AVENUE STREET iM PROVEMENT PR OjE CT, long B E aCh Ludy provided Management services on this Orange Avenue Street Capital Improvement Project (CIP) for the City of Long Beach. The project included the design to widen and provide pavement reconstruction of 5,400 lineal feet of roadway.

Several options of improvements were provided. One option was to demolish the entire PCC pavement and replace with an asphalt over an aggregate base over subgrade. The second option was to merely crack seal the existing PCC and add a

2.5-inch AC overlay. The third option was to crack seal the number one lane in each direction, and then grind and pave the number two and parking lane to the edge of gutter entirely throughout this nearly one-mile street segment. The third option was constructed.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 53 265
raSh id SyEd , mpa
constr Uc tion manager
39 years of
ex perience
fi elds
of
ex pertise roadway ada ramp pavement widening bridge QUALiFiCATiONS
BS: Civil Engineering, Hyderabad Polytechnic Institute ● Ba: Public Administration, California State University, Long Beach ● mpa: Public Administration, California State University, Long Beach bA C kGROUN d
Rash possesses over 39 years of solid experience in the public works sector. Rash has a wide range of experience on a variety of Inspection and Construction Management projects. As an Associate Engineer, he provided public agencies with various tasks including design engineering, plan preparation, specification preparation, plan-checking services, inspection services, Construction Management and support, peer review, stakeholder coordination, public outreach, and staff support. He is proactive in identifying potential obstacles before they occur. Rash has successfully taken multiple projects from the initial Federal funding application, to the Preliminary Environmental Study, to E-76 approval, and all the way through construction of audited Federally Funded construction projects.

ExPERIENCE
dOwN TO wN PEdE STRIAN IMPROVEMENT PROjE CT, Tor ran CE Rash provided Inspection Services to the City of Torrance on this Downtown Pedestrian Improvement Project. The Downtown Pedestrian Improvement Project seeks to provide a more attractive pedestrian environment along Cravens Avenue from Carson Street to Torrance Boulevard. The work encompassed construction of uniform, spacious, and ADA- compliant sidewalks, new decorative LED street lights, improved landscaping, roadway pavement rehabilitation, new curb and gutter, benches, bike racks, and pedestrian signage. The water mainline located under the sidewalk was relocated under the roadway to provide improved access for future repair work. The work also included replacement of the sidewalk, curb and gutter, and curb ramps; roadway repair; and replacement of traffic signs.

ARTESIA bO ULEVAR d RECONSTRUCTION - PHASE I, CEr r IToS Rash served as a Project Manager & Construction Inspector for the Artesia Boulevard reconstruction project. The project limits were from Carmenita Road to Valley View Avenue. The scope of the work included removing and replacing damaged asphalt pavement, removing and replacing the damaged curb and gutter, and grind and overlay of the existing street. The project also required traffic striping and traffic control. This was federally funded project with an approximate construction cost of $530,000. Rash managed the project, meeting the federal requirements, including DBA requirements and certified payrolls. Rash was also involved is securing the federal funds, meetings with Caltrans, and having the project audited.

CARMENITA ROAd RECONSTRUCTION - PHASE I, CEr r IToS
Rash served as a Project Manager & Construction Inspector for the Carmenita Road Reconstruction Project, Phase I. The project limits were from Artesia Boulevard to Alondra Boulevard. The scope of the work included removing and replacing damaged asphalt pavement, removing and replacing the damaged curb and gutter, and grind and overlay of the existing street. The project also required traffic striping and traffic control. The approximate construction cost was $529,000.

CARMENITA ROAd RECONSTRUCTION - PHASE II, CEr r IToS
Rash served as a Project Manager & Construction Inspector for the Carmenita Road Reconstruction Project, Phase II. The project limits were from Artesia Boulevard to South Street. This street had existing median islands. The median curb was uplifted. The scope of the work included removing and replacing the uplifted median curb, damaged asphalt pavement, removing and replacing the damaged curb and gutter, and grind and overlay of the existing street. The project also required traffic striping and traffic control. Rash was also managing the design phase of the project, including project design review during the design phase.

CERRITOS PARk EAST IMPROVEMENTS, CEr r IToS
Rash provided inspection services on the Cerritos Park East made up of 32 acres. The park was split into two different parts:
the community center and the outdoor facilities. The community center included a 6,578 SF multi-purpose room, an activity room, dance room, game room, and large catering kitchen with a smaller community kitchen. The outdoor facilities included SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 54 266
3 baseball diamonds, 2 basketball courts, 4 handball courts, and 357 yards of jogging track, 4 tennis courts, and playground equipment. The facilities also included a spray pool, 3 picnic shelters, picnic tables, restroom, parking areas, and a snack bar. Furthermore, Rash was responsible for making improvements to the park’s facilities, installing safety lights throughout the park, installing new playground equipment, improving the playground, and making improvements to the athletic courts/ fields.
2018 STREET & SLURRY SEAL REHAbI LITATION - PHASE II, lagUn a BEaCh Rash provided inspection services for the City of Laguna Beach on Phase II of this project covering three phases in three years. The project limits covered three different regions - Area A: Canyon Acres Drive/Arroyo Drive/Woodland Drive/Laguna Canyon Frontage Road, Area B: Residential streets in downtown (Loma Terrace, Y Place), and Area C: streets between Thalia Street and Cress Street. The work included variable grind and overlay in some areas, and Type I Slurry Seal in other areas.

The specifications also called for new traffic signal poles. Lastly, the project encompassed parkway and curb and gutter improvements, signage and striping. Due to the residential element involved, OE provided an up-to-date informative Web Page, interactive Web Maps and a Project Hotline for affected residents, keeping them updated and informed through-out the life of the project.
195TH STREET RECONSTRUCTION, CEr r IToS
Rash served as a Project Manager & Construction Inspector for this project on 195th Street from Studebaker Road to Pioneer Boulevard. This project included constructing a median island, installation of reclaimed water line, planting of trees, and providing power to the sprinkler system. Because of the location of the project, the community was notified and received approval of the residents.

ARTESIA bO ULEVAR d RECONSTRUCTION - PHASE II, CEr r IToS Rash served as Project Manager & Construction Inspector on this project on Artesia Boulevard from Clarkdale Avenue to Norwalk Boulevard. This project was a multi-agency project with the City of Artesia. It was fully funded by the City of Cerritos, but the westerly boundary joined with the City of Artesia. Rash worked with the City of Artesia from beginning till end to obtain approval. The scope of the work included grind and overlay.

PIUMA AVENUE RECONSTRUCTION, CEr r IToS
Rash served as Project Manager & Construction Inspector for this $200,000 project with limits on Piuma Avenue from Alondra Boulevard to the Golf Course. Rash designed this project in house with the help of the City staff. The scope of the work including full reconstruction to repair the deteriorated roadway. Parkway improvements were also made as part of this project.

FLORA VISTA dO G PAR k, BEllfl ow Er
Rash provided inspection services on the Flora Vista Dog Park for the City of Bellflower. The park is located along the Bellflower bike trail and pedestrian path at the cul-de-sac on Flora Vista Street. The dog park offers an off-leash play area for large and small dogs and both areas are stationed with dog waste dispenser receptacles. The roaming area is bedded with decomposed granite which is a safe and sanitary option used commonly in community parks. The park entails special features which include: a custom drinking fountain for owners and dogs, drought tolerant landscaping and a dog bone shaped planter which doubles as seating. The scope of work involved installing fencing excavation, removal and replacement of PCC driveways, ramps, curb and gutter, and the construction of DG footpath and a sidewalk with decorative paw prints. Furthermore, the project entailed landscaping.

HERITAGE PARk IMPROVEMENTS, CEr r IToS
Rash was the Construction Manager for the Heritage Park project. Heritage Park is made up of 15 acres with a community center that includes a den with a kitchen and a multi-purpose room. The outdoor facilities included Adventure Island, a lake, softball diamond, 2 basketball courts, playground equipment, and 6 picnic areas with barbeques, restrooms, and parking areas. In addition, Rash was responsible for the design and construction of Adventure Island, gunite was applied to the whole lake, and new pumps and piping was installed. Furthermore, safety lights were installed throughout the park, LIbE RTY PAR k I MPROVEMENTS, CEr r IToS
Rash was the Construction Manager for the 34 acres that is Liberty Park in the City of Cerritos. Liberty Park is made up of 3 sections: the community center, the fitness center, and the outdoor facilities. The and a liberty lounge. The Fitness Center is a state-of-the-art workout facility featuring a multi-max station, treadmills, stair climbers and elliptical machines. The outdoor facilities included 3 racquetball courts, softball diamond, 6 tennis courts, 3 sand volleyball courts, and 330 yards of jogging track. It also entailed 2 playground areas, a plaza area, exercise stations, water play area, 3 picnic shelters, picnic tables, parking area, and restrooms. Furthermore, Rash was responsible for making improvements to the park as needed, installing safety lights, improving the playground and installing new equipment, and improved the athletic courts/fields and jogging track.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 55 267
ryan dEn niS , p. eng.
proJe ct engineer
18 years of
ex perience
fi elds
of
ex pertise roadway ada ramp pavement signal traffic QUALiFiCATiONS
BS: Civil Engineering, University of Calgary, Alberta, Canada, 2005 ● minor: Environmental Engineering, University of Calgary, Alberta, Canada, 2005 ● p Eng: apEg a: Registered Civil Engineer (Canada) ● CErTi fi Ed : AutoCAD & Civil 3D

bA C kGROUN d
As a Project Engineer for OE, Ryan leads the design team by performing and coordinating detailed designs on public works projects. Ryan has over 18 years of experience. He received his degree in Civil & Environmental Engineering from the University of Calgary and is a Registered Civil Engineer in Alberta, Canada. He possesses an ability to produce drawings, layouts, sketches, maps, and graphic representations of engineering designs. He also has extensive knowledge of AutoCAD Civil 3D. Ryan provides support during the overall engineering and design effort.

ExPERIENCE
NEwP ORT bO ULEVARd wIdE NING IMPROVEMENTS PROjE CT, CoSTa mE Sa Ryan served as Project Engineer for the City of Costa Mesa. The project consists of widening a portion 77 Fair Drive of southbound Newport Boulevard to accommodate a fourth through lane and improve its Level of Service from the current “F” rating (ranging from 1.10 to 1.30). The section of roadway to be enhanced extends approximately 2,700 linear feet southwest from 19th Street to the Superior Avenue turn-off located northeast of 17th Street. The project is located within Caltrans jurisdiction and requires traffic signal modifications, utility and street light relocations, and right-of way acquisitions to accommodate the additional through lane and right-turn pockets.

SPRING ST.-bEL LFLOwER /LAkEwO O d bL Vd. INTERSECTION IMPROVEMENT, long BEaCh Ryan was the Project Engineer for the City of Long Beach for two intersection widening projects along Spring Street. The first project is along Spring Street at Bellflower Boulevard and the other is along Spring Street at Lakewood Boulevard.

The goal of the project was to implement congestion management and reduction strategies at these intersections to improve capacity and movement for future volumes. The project included design work for raised medians, traffic signal modifications, turn pocket extensions, utility relocation and utility adjustments. The existing conditions at the intersection of Spring Street and Bellflower Boulevard included a single left turn lane in each direction, three through lanes in each direction, and dedicated right turn pockets for all intersection legs except for the west leg. The intent at this intersection was to extend the left turn pockets for the north, east and south legs. The project also extended the southbound right turn pocket. The existing conditions at the intersection of Spring Street and Lakewood Boulevard include Dual left turn pockets in all directions, three through lanes in all directions and dual right turn lanes from southbound Lakewood Boulevard to westbound Spring Street. The future capacity required an increase in pocket lengths for the left turn pockets in each direction on Spring Street along with an increased length of the dual right turn pockets on southbound Lakewood Boulevard.

RESIdE NTIAL STREETS PAVEMENT REHA bI LITATION FOR AREAS 1, 2, & 4, downEy Ryan was the Project Engineer for the City of Downey. The main objective is to improve the PCI of the area residential street segments in order to extend the street service life, improve safety, minimize costs and maintenance needs, and enhance aesthetics. In order to accurately develop a scope of work and fees for the design services, OE conducted a detailed field evaluation, a thorough review of the City’s Pavement Management Plan, and approximated the costs for the construction activities to develop a final list of residential street segments. OE was then able to determine the quantity of streets that could be incorporated into the engineering design, which rehabilitation method to use and which method could be feasibly rehabilitated while adhering to the City’s available budget, along with providing recommendations and estimates. Upon approval by the City, the team then began to prepare separate PS&E packages for areas 1, 2 and 4. The work across the three zones covered nearly 29 miles of residential streets. On a number of segments OE is using straight grade between tie-in points at adjacent segments to maximized drainage slopes. A total of 164 Curb Ramps are being reconstructed to meet ADA compliance along with 85 total driveways, in addition to street widening and single-sided street parking construction.

Collaboration with Caltrans, LA City Flood Control District and Union Pacific Rail Road was also performed in order to acquire permit acquisitions.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 56 268
SIdEwA L k/ PEdEST RIAN ACCESSIbI LITY - PHASE II, plaCEn TIa Ryan was the Project Engineer on the $245,000 CDBG Funded Project for the City of Placentia to field verify, design and prepare a bid package for the removal and replacement of non-ADA compliant curb ramps and sidewalk locations that are listed in the City’s ADA Transition Plan. This project entailed replacing a total of 71 curb ramps along Kraemer Blvd., McCormack Lane, and Yorba Linda Blvd. Additionally, the work included sidewalk/driveway improvements along Kraemer Blvd. within the curb ramp replacement limits. The project called for conducting field verification of each location and identified the necessary ADA compliance upgrades. The locations where there was critical geometry or grades were checked to identify the final removal and replacement limits. The project was designed to include all required CDBG Section 3 verbiage in the project specifications, and that the project scope/bid schedules were set up in such a way that maximized the City’s budget. This included setting up alternate bid schedules in the bid package to ensure that budgetary overrun did not occur and to ensure that the City spend the allocated amount.

GREENSTONE PAVEMENT RECONSTRUCTION PROjE CT, Sa n Ta f E SprIn gS Ryan was the Project Engineer for the City of Santa Fe Springs on the Greenstone Pavement Reconstruction Project. The project limits were Lakeland Avenue to Sunshine Ave and Sunshine Avenue from Greenstone to Shoemaker Avenue. The surrounding business included heavy commercial and industrial with mostly large truck traffic. The existing roadway was severely distressed asphalt that had alligator cracking throughout the roadway. Working with the city we came up with an alternative approach to give this roadway extended life. The method of reconstruction we used was Roller Compacted Concrete (RCC). Since we knew that we didn’t want to impact the businesses, then this method drastically reduces the cure time of traditional concrete down to hours instead of days. It uses a machine similar to an asphalt paving machine in order to place a low slump concrete that is then compacted with a roller. This method lowers the downtime for residents and businesses and because it uses paving machines then it can be completed quickly and at a much lower cost per square foot. The scope of work included 317,500 square feet of pavement reconstruction, 1,270 lineal feet of curb reconstruction, 2,700 square feet of sidewalk reconstruction, 1,510 square feet of cross gutter reconstruction, 6,800 square feet of driveway reconstruction and 26 manhole adjustments along with various other items of work.

CITYwIdE AdA C UR b RAMPS/PATH OF TRAVEL PEdEST RIAN ACCESSIbI LITY IMPROVEMENT, long BEaCh
Ryan is providing Project Engineering services to the City of Long Beach involving Citywide ADA Curb Ramps and Path of Travel Pedestrian Accessibility Improvements. The objective of the project is to design and construct at least 20,000 new ADA compliant curb ramps over the next 20 years in accordance with current State and Federal accessibility codes and standards. The project is to complete 1,000 of those ramps deemed most critical for accessibility. OE’s team utilizes AutoCAD Civil 3D on 3D surfaces for the designs in compliance with the Long Beach Standard Plan No. 122 in order to satisfy the maximum allowable slopes dictated in the most current version of Caltrans Standard Plan A88A, and has had to consider other accessibility standards due to occasional unavailability of a suitable ramp case and type. The project work entails the preparation of detailed individual curb ramp construction plans with the inclusion of horizontal geometrics, design elevations and dimensions, and utility appurtenance adjustments and relocations, along with concrete infrastructure such as curb, gutter, cross-gutters, and sidewalk. The necessary reconstruction is incorporated in order to accommodate the new curb ramps, meet accessibility requirements, and maintain drainage. Additional design elements have also required consideration, which involve constructing 32”x54” size flat landings next to each pedestrian push-button at signalized intersections and installing guardrails where retaining curbs adjoin walkable hard surfaces. Due to the large volume of ramps reconstructed each year, small batches of design details and construction of the ramps are being provided to the City at regular intervals through out a continuous process, with City submittals made on a monthly basis at a scaled frequency and quality.
dE L AMO bO ULEVAR d PAVEMENT REHAbI LITATION, CEr r IToS Ryan was the Project Engineer for the Del Amo Boulevard Project. Del Amo Boulevard is a major arterial oriented east/west and is used as a thoroughfare to adjacent cities. The project limits consist of a total of approximately 2,900 linear feet (approximately 0.55 miles) of Del Amo Boulevard between Pioneer Boulevard and Norwalk Boulevard. The south half is under the City of Lakewood’s jurisdiction. Requirements included rehabilitation of pavement, concrete removal and replacement of damaged curb, gutter and sidewalks, identifying and addressing storm water drainage concerns, retrofitting curb access ramps with the latest ADA standards, and updating signing, striping and traffic loops. Close collaboration with the selected landscape architect was necessary to ensure all issues regarding tree root infiltration are addressed to accommodate both the civil and landscape designs and to ensure that the City receives a cohesive package of civil, landscape, and irrigation plans. The plans also included Low Impact Development (LID) Improvements to divert urban run-off from the storm drain system.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 57 269
dayTo n low E
proJe ct engineer
30 years of
ex perience
fi elds
of
ex pertise roadway ada ramp pavement drainage drone QUALiFiCATiONS
CoUrS E w ork: Civil Engineering, Technology & Construction Management, Boward College ● oC T a CErTi fiE d:
(prior) Pavement Rehabilitation ● CErTi fi Ed : AutoCAD & Civil 3D bA C kGROUN d
As a Project Engineer for OE, Dayton performs and coordinates detailed designs on arterial roadways, utility coordination for major relocations on high profile projects and assistance in coordination efforts on multiple projects. He possesses an ability to produce drawings, layouts, sketches, maps, and graphic representations of engineering designs. He also has extensive knowledge of AutoCAD, Autodesk Civil 3D, Eagle Pointe Civil package and others. Dayton provides support during the overall engineering and design effort, including the preparation of design drawings and calculations. He is experienced in developing residential, commercial, and industrial conceptual site plans from the preliminary phase to final construction documents; knowledgeable in the design of gravity sanitary sewer systems; skilled in the design of sanitary sewer pump stations and force main systems; accomplished in the design of water mains for residential, commercial and industrial projects; practiced in the design of drainage systems; talented in preparing drainage calculations for effective and efficient drainage systems; and familiar in the design of grading plans for storm water drainage and ADA compliance. Dayton is also extremely proficient in preparing and submitting packages to governmental agencies to obtain required permits for construction and in the design of roadway layouts including intersections, roundabouts, turn and travel lanes.

ExPERIENCE
CITYwIdE A dA CURb R AMPS/PATH OF TRAVEL PEdE STRIAN ACCESSIbI LITY IMPROVEMENT, long B E aCh Dayton is the Project Engineer to the City of Long Beach involving Citywide ADA Curb Ramps and Path of Travel Pedestrian Accessibility Improvements. The objective of the project is to design and construct at least 20,000 new ADA compliant curb ramps over the next 20 years in accordance with current State and Federal accessibility codes and standards. The project is to complete 1,000 of those ramps deemed most critical for accessibility. OE’s team utilizes AutoCAD Civil 3D on 3D surfaces for the designs in compliance with the Long Beach Standard Plan No. 122 in order to satisfy the maximum allowable slopes dictated in the most current version of Caltrans Standard Plan A88A, and has had to consider other accessibility standards due to occasional unavailability of a suitable ramp case and type. The project work entails the preparation of detailed individual curb ramp construction plans with the inclusion of horizontal geometrics, design elevations and dimensions, and utility appurtenance adjustments and relocations, along with concrete infrastructure such as curb, gutter, cross-gutters, and sidewalk. The necessary reconstruction is incorporated in order to accommodate the new curb ramps, meet accessibility requirements, and maintain drainage. Additional design elements have also required consideration, which involve constructing 32”x54” size flat landings next to each pedestrian push-button at signalized intersections and installing guardrails where retaining curbs adjoin walkable hard surfaces. Due to the large volume of ramps reconstructed each year, small batches of design details and construction of the ramps are being provided to the City at regular intervals through out a continuous process, with City submittals made on a monthly basis at a scaled frequency and quality.ired consideration, which involve constructing 32”x54” size flat landings next to each pedestrian push-button at signalized intersections and installing guardrails where retaining curbs adjoin walkable hard surfaces. Due to the large volume of ramps reconstructed each year, small batches of design details and construction of the ramps are being provided to the City at regular intervals through out a continuous process, with City submittals made on a monthly basis at a scaled frequency and quality.

NEwP ORT bO ULEVARd wIdE NING IMPROVEMENTS, CoSTa mE Sa For the City of Costa Mesa, Dayton provided Project Engineering services. The project consists of widening a portion 77 Fair Drive of southbound Newport Boulevard to accommodate a fourth through lane and improve its Level of Service from the current “F” rating (ranging from 1.10 to 1.30). The section of roadway to be enhanced extends approximately 2,700 linear feet southwest from 19th Street to the Superior Avenue turn-off located northeast of 17th Street. The project is located within Caltrans jurisdiction and requires traffic signal modifications, utility and street light relocations, and right-of way acquisitions to accommodate the additional through lane and right-turn pockets.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 58 270
EUCLId ROAd wA Y ANd SEwE R RECONSTRUCTION PROjE CT, fUll ErTo n Dayton was the Project Engineer to the City of Fullerton on the Euclid Roadway and Sewer Reconstruction Project from Williamson to Fern Project. The project consisted of reconstructing or resurfacing approximately 3,700 linear feet of arterial streets between Fern Drive and Williamson Avenue and replacing approximately 1,700 feet of sewer mains between Malvern Avenue and Commonwealth Avenue. The sewer work included removing the existing 10-inch VCP and replacing it with new 12-inch VCP pipe between Commonwealth and Malvern and removing and replacing sewer north of Malvern to the end of the street project limits at Fern without upsizing. The worked also included removing the manholes at the center of the Euclid Street/Chapman Avenue intersection and establishing a new connection point approximately 50 feet to the east along Chapman Avenue as well as reconstructing the double barrel siphon and adjusting invert elevations to achieve a suitable slope. The design utilized a trenchless method to install the siphon beneath the OCPW Brea Creek Channel. Additional tasks included adjusting manhole elevations and reconnected service laterals, constructing new curb and gutter where gutter is absent, constructing ADA compliant curb ramps, and repairing curb, gutter, cross gutters, sidewalks and driveways where required. The City utilized SB1 funds for the road rehabilitation and local funds for the sewer improvements.
bE RRY STREET & IMPERIAL HIGH wA Y SEwE R MAIN REPLACEMENT PROjE CT, Br Ea Dayton provided Project Engineering services to the City of Brea for this sewer main replacement project.

The project spanned 3,000 LF from Lambert Road to Imperial Highway (within Caltrans right-of-way), and on Imperial Highway from Berry Street to the Orange County flood control channel. This project required coordinating with Union Pacific Railroad and filing for a Caltrans encroachment permit, due to the segment within Caltrans right-of-way. The design of this project was split into two phases to accelerate the portion on Lambert Road where a roadway overlay was separately planned. The ultimate design included the installation of 100 feet of 10-inch VCP , 2,570 feet of 12-inch VCP , 300 feet of 15-inch VCP , and a total of 15 new manholes. Special sewer bypass designs were required at the railroad crossings to maintain railroad access at all times. OE also coordinated utility relocations for Chevron, AT&T, and water department and storm drain lines in conflict with the proposed line.

To avoid future maintenance and access issues, OE also proposed a new alignment for the sewer main that would avoid encroachment in Caltrans right-of-way.with a uniform grind and asphalt overlay, and preparing striping and signage plans to encompass parking and no parking areas.

LOVEk ING bL Vd. & bA RNAR d ST. REHAbI LITATION, BlyTh E As Project Engineer on The Loveking Blvd., and Barnard St. Rehabilitation Project in the City of Blythe, Dayton’s duties entails services to rehabilitate two street segments, 66,403 SF of Lovekin Boulevard, from Hobson Way to Barnard Street; and 81,946 SF of Barnard Street, from the first alley easterly of Lovekin Boulevard to the west edge of Main Street. The combined length is approximately 2,795 linear feet (0.53 miles). The work also includes replacing existing curb ramps with ADA compliant curb ramps, concrete infrastructure repairs (i.e. curb, gutter, sidewalk, and driveways), adjusting or relocating utility appurtenances, and signing and striping replacement.

REd HILL AVENUE PAVEMENT REHAbI LITATION PROjE CT, Ir v In E Dayton provided Project Engineering services to the City of Irvine for this ARRA-funded project, which included preparing PS&E, plan and profile, striping and signing plans, traffic control and phasing plans and detour plans. The scope of work consisted of rehabilitating approximately 3,300 LF of roadway on Red Hill Avenue, from Deer Avenue to Reynolds Avenue. Red Hill Avenue is a major 6 lane arterial that runs parallel to the State Route 55 Freeway and serves as a non-freeway alternate route for commuters. Our design included portions of grind and overlay, full depth reconstruction, ARHM cap, removal and replacement of 4,500 LF of curb gutter, 1,500 SF of sidewalk, installing ADA-compliant ramps, and installing video detection systems at intersections, as well as various related improvements. To minimize extended traffic delays and expedite the construction schedule, OE designed a detour plan, routing commuter and truck traffic around the construction site. OE also coordinated with both the City of Irvine and the City of Santa Ana, whose jurisdiction included parts of Red Hill Avenue, to ensure equity in the project for both stakeholders and to gain project approval. The final plans included City of Irvine, City of Santa Ana and Caltrans Standards as applicable in each jurisdiction. OE processed submittals through all reviewing agencies and ensured the project design proceeded smoothly and successfully.

MA NHATTAN bEACH bL Vd . & SE PULVEdA bL Vd . wi dE NiN G, manhaT T an BEaCh Dayton is providing Project Engineering services to the City of Manhattan Beach on the Manhattan Beach Boulevard and Sepulveda Boulevard Widening project. The proposed project limits include the intersection of Manhattan Beach Boulevard and Sepulveda Boulevard to accommodate dual left turn lanes in the northbound to westbound, eastbound to southbound, and westbound to northbound directions. The City of Lawndale is east of the project area, the City of Redondo Beach is south of the intersection, El Segundo sits to the north, and the Pacific Ocean to the west.

Commercial businesses can be found throughout the project limits. The purpose of the project was to increase the operational capabilities of the intersection. This was accomplished by adding dual left turn lanes to the westbound, northbound and eastbound lanes. Northbound and southbound Sepulveda will have five travel lanes; two left turn lanes, and three through lanes. Eastbound and Westbound Manhattan Beach Boulevard will have five travel lanes; two left turn lanes, two through lanes and one dedicated right turn lane.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 59 271
david loria
proJe ct engineer
15 years of
ex perience
fi elds
of
ex pertise roadway drainage scanner drone survey
QUALiFiCATiONS
aS dEg r E E: 3D Computer Animation, Brooks College, Long Beach, 2004 ● CErTi fi E d : AutoCAD Professional ● faa liC E nS Ed #4 098277: Drone Remote Pilot ● aU T odE S k : AutoCAD, Civil 3D, Revit, 3D Max, Recap ● lEiCa gE oS T yS TEmS, Cyclone Point Cloud Processing Software ● TopCon: Scan Master Point Cloud Processing Software ● EoS SyS TE mS: PhotoModeler Motion-Photogrammetric Image Analysis/3D Modeling

bA C kGROUN d
David Loria has accumulated over 15 years of experience crafting his knowledge and skills in the survey and engineering industries that include CAD management, drafting and estimating, survey data and mapping, design analysis, base mapping, QA/QC checking, HD Laser scanning, 3D modeling and animation, forensic research, improving workflow pipeline methods, base maps, generating digital terrain models and accurate 3D line-work, and point cloud analysis and feature extraction, as well as advance photogrammetric modeling and analysis software. He has over 8 years of experience planning and performing site inspections and laser scans in the field, and analyzing, drafting, modeling and animating scenes for final presentations under strict deadlines. Other skills include drafting as-builts and record drawings for contract closeout submittals, and drafting base maps by combining survey data, Edison field inventory maps, public utility as-builts and other data for planning the removal, installation, replacement or repair of Edison electrical line, equipment or structures. David is proficient in multiple workflows depending on the needs and budget of a project to make sure it is completed on time and within budget.

ExPERIENCE
I-10 HOV wIdE NING ANd O THER IMPROVMENTS, monTClaIr & El mon TE David served as a Project Engineer in assisting with Riegal Mobile Laser Measurement Systems lidar scanning of the i-10 freeway, beginning from Mulberry Avenue in the City of Montclair, and ending at S. Mountain Avenue in the City of El Monte, a distance of approximately 41 miles, for HOV widening and other improvements. David then processed the piont cloud data and extracted bridge and utility clearances for use in design process.

LAk E FOREST dRI VE RESURFACING, FROM bAk E PAR kwA Y TO I-5, lakE forEST David served as a Project Engineer for the City of Lake Forest on this project to prepare full design plans, specifications and estimat es ( PS&E ) for this roadway resurfacing pro ject locat ed at Lak e F orest Driv e, between Bak e Parkway and the I-5 freeway. The project design plans were to be phased in order for the construction to be distributed into three phases as funding permitted. Along the approximately 5.5 mile stretch of road within the project limits, the phases required the construction of 152 ADA ramps and 22 ADA driveways in total and 7,105 linear feet of median curb height construction, along with the construction of bus pads, curb gutter and sidewalk repairs, and signing and striping replacement. The main objective is to improve the PCI of the street segments following our team’s professional assessment of the existing pavement conditions in order to extend the street service life, improve safety by upgrading to safer streets with better ride quality and pedestrian access, minimize future maintenance costs and enhance aesthetics. This project is funded through Measure M2, SB1 and Infrastructure Reserves Funds.

TRAbU CO ROA d RESURFACING, FROM PEACHwO Od TO bAk E PAR kwA Y, lakE forEST David served as a Project Engineer to the City of Lake Forest to prepare full design Plans, Specifications and Estimates (PS&E) to the City of Lake Forest on the Trabuco Road Resurfacing Project for road resurfacing on Trabuco Road, between Peachwood Parkway and Bake Parkway. The work required the construction of 11 ADA ramps and 2 ADA driveways in total, median curb height construction, along with curb gutter and sidewalk repairs, and signing and striping replacement.

The main objective is to improve the PCI for Trabuco Road following our team’s professional assessment of the existing pavement conditions in order to extend the useful service life of the streets, improve safety by upgrading to safer streets with better ride quality and pedestrian access, minimize future maintenance needs and costs, and enhance aesthetics.

NEwP ORT b LVd. wI d ENING IMPROVEMENTS PROj ECT, CoSTa mE Sa David worked as a Project Engineer to the City of Costa Mesa on the Newport Boulevard Widening Improvements Project, which consists of widening a portion 77 Fair Drive of southbound Newport Boulevard to accommodate a fourth through lane and improve its Level of Service from the current “F” rating (ranging from 1.10 to 1.30). The section of roadway to be enhanced SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 60 272
is approx. 2,700 linear feet southwest from 19th Street to the Superior Avenue turn-off located northeast of 17th Street. The project is within Caltrans jurisdiction and requires traffic signal modifications, utility and street light relocations, and right- of way acquisitions to accommodate the additional through lane and right-turn pockets. bE LLFLO wE R COMPLETE STREETS PROjE CT, BEllfl ow Er
David worked as a Project Engineer to the City of Costa Mesa on the Newport Boulevard Widening Improvements Project, which consists of widening a portion 77 Fair Drive of southbound Newport Boulevard to accommodate a fourth through lane and improve its Level of Service from the current “F” rating (ranging from 1.10 to 1.30).

The section of roadway to be enhanced is approx. 2,700 linear feet southwest from 19th Street to the Superior Avenue turn- off located northeast of 17th Street. The project is within Caltrans jurisdiction and requires traffic signal modifications, utility and street light relocations, and right-of way acquisitions to accommodate the additional through lane and right-turn pockets.

RESIdE NTIAL STREETS PAVEMENT REHA bI LITATION PROjE CTS-AREAS 1, 2, & 4, downEy David provided the City of Downey with Project Engineering services for the Residential Streets Pavement Rehabilitation Project for Areas 1, 2, and 4. The main objective was to improve the PCI of the area residential street segments in order to extend the street service life, improve safety, minimize costs and maintenance needs, and enhance aesthetics. In order to accurately develop a scope of work and fees for the design services, OE conducted a detailed field evaluation, a thorough review of the City’s Pavement Management Plan, and approximated the costs for the construction activities to develop a final list of residential street segments. OE was then able to determine the quantity of streets that could be incorporated into the engineering design, which rehabilitation method to use and which method could be feasibly rehabilitated while adhering to the City’s available budget, along with providing recommendations and estimates. Upon approval by the City, the team then began to prepare separate PS&E packages for each of the 3 zone areas. The resulting work required a total of 7, 500 feet of new and reconstructed curb, gutter and sidewalk along 21 residential street segments, with roadway improvements stretching .18 mile in Zone 1, 1.003 miles in Zone 2, and .22 mile in Zone 3. On a number of segments OE used straight grade between tie-in points at adjacent segments to maximized drainage slopes. A total of 164 Curb Ramps were reconstructed to meet ADA compliance along with 85 total driveways, in addition to street widening and single-sided street parking construction. Collaboration with Caltrans, LA County Flood Control District and Union Pacific Rail Road was also performed in order to acquire permit acquisitions on the segments.

CITYwIdE AdA CUR b RAMPS & PATH OF TRAVEL PEdES TRIAN ACCESSIbI LITY IMPROVEMENT, long B E aCh
David served as a Project Engineer to the City of Long Beach involving Citywide ADA Curb Ramps and Path of Travel Pedestrian Accessibility Improvements. The objective of the project is to design and construct at least 20,000 new ADA compliant curb ramps over the next 20 years in accordance with current State and Federal accessibility codes and standards. The project is to complete 1,000 of those ramps deemed most critical for accessibility. OE’s team utilizes AutoCAD Civil 3D on 3D surfaces for the designs in compliance with the Long Beach Standard Plan No. 122 in order to satisfy the maximum allowable slopes dictated in the most current version of Caltrans Standard Plan A88A, and has had to consider other accessibility standards due to occasional unavailability of a suitable ramp case and type. The project work entails the preparation of detailed individual curb ramp construction plans with the inclusion of horizontal geometrics, design elevations and dimensions, and utility appurtenance adjustments and relocations, along with concrete infrastructure such as curb, gutter, cross-gutters, and sidewalk. The necessary reconstruction is incorporated in order to accommodate the new curb ramps, meet accessibility requirements, and maintain drainage. Additional design elements have also required consideration, which involve constructing 32”x54” size flat landings next to each pedestrian push-button at signalized intersections and installing guardrails where retaining curbs adjoin walkable hard surfaces. Due to the large volume of ramps reconstructed each year, small batches of design details and construction of the ramps are being provided to the City at regular intervals through out a continuous process, with City submittals made on a monthly basis at a scaled frequency and quality.

EUCLid STREET REHAbiLiTATiON & R ESURFAC i NG , F ROM Edi NGER TO wARNER A VENUE , foUnTain vallEy
David served as a Project Engineer to the City of Fountain Valley on the Euclid Street Rehabilitation and Resurfacing Project, which was located on Euclid Street, from Edinger Avenue to Warner Avenue. Approximately 5,200 linear feet (1 mile) of roadway required rehabilitation which involved curb, gutter and sidewalk reconstruction, 8 curb returns with ADA curb ramp and 5 driveways to be replaced, signing and striping replacement, and utility appurtenance adjustments. Aerial photographs of the street were captured for use in base map features which included utility appurtenance locations, digout areas, street striping configurations, and pavement limits, along with a topographic survey. The construction budget of this project totaled approximately $1.7 million.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 61 273
JaSo n To
proJe ct engineer
5 years of
ex perience
fi elds
of
ex pertise roadway ada ramp pavement survey water main QUALiFiCATiONS
BS: Civil Engineering, California State University, Fullerton ● rolE S : CAD Designer 1, Lab Engineer 1, Technical Specialist, Construction Manager ● So f Tw ar E: AutoDesk, AutoCAD, RAM Structural Systems, ArcGIS

bA C kGROUN d
Jason To is an entheusastic Project Engineer and a recent graduate from Calfornia State University, Fullerton, earning a Bachelor’s of Science Degree in Civil Engineering. He quickly followed this by taking on the role of Lab Engineer 1 and Technical Specialist for RMS Energy Consulting, where he provided projects scheduling, data analysis, drafted standard testing procedures for energy efficient appliances, and configured, calibrated and tested thermal couples equipment energy appliances for energy efficiency. In this role, Jason gained a wide range of design experience beginning with Soil Mechanics, where he determined properties of soil required for foundation design, then in Reinforced Concrete Design, where he designed and analyzed reinforced concrete structures, followed by Structural Steel Design, where he designed and analyzed steel structures. Jason also gained experience in Engineering Surveying, where he learned how to properly survey and use surveying equipment, as well as in Construction Management in learning how to create a project schedule and cost estimates with safety and reliability considerations through MS Project. His most recent position at Advantage Engineers allowed him work as a CAD Designer 1, where he designed and drafted zoning and construction drawings, site plans, red-line corrections, etc. for the purpose of wireless siting, and communicated drawing status and schedule to the Project Manager and other Team members, making him a team player along with his acquired design and management skills in the field.

ExPERIENCE
FY 2022-23 ANNUAL PAVEMENT REHAbI LITATION PROjE CT, PHASES 1-4, whIT TIE r Jason is providing the City of Whittier with Project Engineering services through 4 phases of their FY 2022-2023 Annual Pavement Rehabilitation Project. The project purpose is to rehabilitate approximately 49,000 linear feet (9.3 miles) of 46 streets with a variety of slurry and cape seal, grind and overlay in order to achieve an extended pavement service life while minimizing future maintenance needs, improve safety and enhance aesthetics. The required work involved pavement, curb, gutter and sidewalk repair and rehabilitation, reconstructing 62 curb ramps (52 with missing truncated domes), replacing 9 cross gutters, utility appurtenance adjusting and relocating, signing and striping. The project also required Caltrans Encroachment Permits for streets around Whittier Boulevard, and for the Union Pacific Railroad (UPRR) due to street proximity to the right-of-way on the southwest end. OE’s in-house Laser Scanner was utilized to capture visible indications of surface utilities, trees, utility poles, luminaries, fencing, walls, sidewalks, hardscape, signs, and edge of pavement lying within the ramp locations, as well as lip of gutter, flow-line, top of curb, and back of walk elevations were documented. The survey also extended beyond the ramp’s BCRs/ECRs to ensure proper tie-in to the existing infrastructure.

RESIdE NTIAL STREETS PAVEMENT REHA bI LITATION PROjE CTS-AREAS 1, 2, & 4, downEy Jason provided the City of Downey with Project Engineering services for the Residential Streets Pavement Rehabilitation Project for Areas 1, 2, and 4. The main objective was to improve the PCI of the area residential street segments in order to extend the street service life, improve safety, minimize costs and maintenance needs, and enhance aesthetics. In order to accurately develop a scope of work and fees for the design services, OE conducted a detailed field evaluation, a thorough review of the City’s Pavement Management Plan, and approximated the costs for the construction activities to develop a final list of residential street segments. OE was then able to determine the quantity of streets that could be incorporated into the engineering design, which rehabilitation method to use and which method could be feasibly rehabilitated while adhering to the City’s available budget, along with providing recommendations and estimates. Upon approval by the City, the team then began to prepare separate PS&E packages for each of the 3 zone areas. The resulting work required a total of 7, 500 feet of new and reconstructed curb, gutter and sidewalk along 21 residential street segments, with roadway improvements stretching .18 mile in Zone 1, 1.003 miles in Zone 2, and .22 mile in Zone 3. On a number of segments OE used SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 62 274
straight grade between tie-in points at adjacent segments to maximized drainage slopes. A total of 164 Curb Ramps were reconstructed to meet ADA compliance along with 85 total driveways, in addition to street widening and single-sided street parking construction. Collaboration with Caltrans, LA County Flood Control District and Union Pacific Rail Road was also performed in order to acquire permit acquisitions on the segments. zON E 3 COLLECTOR ROA d I MPROVEMENTS, lagUn a B EaCh
Jason is providing Project Engineering services to the City of Laguna Beach for the development of Plans, Specifications & E st i ma t es f or st r ee t i mpr o v e me n t s o f P ar k A v e nue , fr om G l e nne yr e St r ee t t o W e ndt T e r r ace ; G l e nne yr e St r ee t , fr om Park Avenue to Thalia Street; and Thalia Street, from Temple Hills Drive to the South End The City. The project consists of rehabilitating approximately 3,200 linear feet of Park Avenue, 2,500 linear feet of Glenneyre Street, and 2,500 linear feet of Thalia Street. Additional tasks include analyzing crown slopes at pedestrian crossings to reduce crossfall and steep crowns, as needed, along with utility adjustments, a record of survey on Thalia Street, a two-phase set of traffic control plans, and signing and striping. Traffic control and detour plan phasing is also included in order to accommodate the summer moratorium and for Thalia Street, OE prepared and filed with the County of Orange a Record of Survey showing the existing centerline from Temple Hills Drive to the southwest end.

CLARk A VENUE REHA bI LITATION PROjE CT, BEllfl ow Er
Jason is providing Project Engineering services to the City of Bellflower on the Clark Avenue Rehabilitation project. The project spanned 2,200 LF of arterial roadway from Artesia Boulevard to the South City limits. The scope of work included an inverted grind and overlay to reduce the crown height and provide more gradual grads at the edge of the roadway. The project also entailed a full-width ARHM overlay, localized full-depth reconstruction, installing 22 traffic loops, adjusting 22 manholes and 35 valves, metal hand-railing, curb & gutter, PCC driveways, and 11 curb ramp replacements to meet ADA compliance, as well as necessary traffic striping. Due to the projects close proximity to the City of Lakewood, OE was required to coordinate with both the City of Bellflower and the City of Lakewood. 247TH STREET AREA wA TER MAIN REPLACEMENT PROjE CT, lomI T a Jason is providing Project Engineering services to The City of Lomita for the 247th Street Area Water Main Replacement Project. The project limits are on 246th Street, 247th Place, 248th Street, Western Avenue and Lomita Boulevard and involved the installation of 3,300 linear feet of new 6-inch PVC water mains to provide improved flow, pressure, and fire protection. The existing 4-inch/6-inch water main system was constructed between 1928 and 1930 and had exceeded its useful service life. The proposed water main was installed parallel to the existing main while keeping the old line in service to minimize downtime for the public. All fire hydrants, service laterals, valves, blow-offs, air release valves, and other associated water appurtenances were replaced, with sectional pavement, curb gutter and sidewalk were removed and reconstructed according to ADA standards and drainage patterns. Encroachment permits from Caltrans and the City of Los Angeles within their jurisdictions was secured. Funding was sourced from the City’s CIP Program and the FEMA Hazard Mitigation Grant Program.

CITYwIdE AdA CUR b RAMPS & PATH OF TRAVEL PEdES TRIAN ACCESSIbI LITY IMPROVEMENT, long B E aCh
Jason served as a Project Engineer to the City of Long Beach involving Citywide ADA Curb Ramps and Path of Travel Pedestrian Accessibility Improvements. The objective of the project is to design and construct at least 20,000 new ADA compliant curb ramps over the next 20 years in accordance with current State and Federal accessibility codes and standards. The project is to complete 1,000 of those ramps deemed most critical for accessibility. OE’s team utilizes AutoCAD Civil 3D on 3D surfaces for the designs in compliance with the Long Beach Standard Plan No. 122 in order to satisfy the maximum allowable slopes dictated in the most current version of Caltrans Standard Plan A88A, and has had to consider other accessibility standards due to occasional unavailability of a suitable ramp case and type. The project work entails the preparation of detailed individual curb ramp construction plans with the inclusion of horizontal geometrics, design elevations and dimensions, and utility appurtenance adjustments and relocations, along with concrete infrastructure such as curb, gutter, cross-gutters, and sidewalk. The necessary reconstruction is incorporated in order to accommodate the new curb ramps, meet accessibility requirements, and maintain drainage. Additional design elements have also required consideration, which involve constructing 32”x54” size flat landings next to each pedestrian push-button at signalized intersections and installing guardrails where retaining curbs adjoin walkable hard surfaces. Due to the large volume of ramps reconstructed each year, small batches of design details and construction of the ramps are being provided to the City at regular intervals through out a continuous process, with City submittals made on a monthly basis at a scaled frequency and quality.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 63 275
Ja r Ed SpEiC hEr , eit
proJe ct engineer
5 years of
ex perience
fi elds
of
ex pertise ROADWAY ADA RAMP SURVEY BIKE TRAIL PAVEMENT
QUALiFiCATiONS
BS: Civil Engineering, California State University, Long Beach ● EiT: # 179155: Engineer In Training ● So f Tw ar E: AutoCAD and Civil 3D, Infra Works, and Blue Beam bA C kGROUN d
Both ambitious and goal driven, Jared planned for and graduated from California State University, Long Beach with a Bachelor’s Degree in Civil Engineering, all the while excelling in extra curricular programs at the University. He was the Project Manager for CSULB’s ASCE Concrete Canoe Competition, providing team support toward the project’s critical path, and worked with faculty to improve funding and utilize available space. Jared also became an active member with the American Society of Civil Engineers, as well as with the InterFraternity Council, Associated Students, Inc., and with Greek Intervarsity. Jared then took on the role of Civil Engineering Associate, becoming skilled with BlueBeam and Civil3D software involving design site grading and utility plans design for coordination and construction. Concurrently he collaborated with consultants regarding project timelines of traffic, geotechnical investigations and topographic surveys, and he completed site constraint analysis to identify all financial, developmental, and environmental concerns, and assisted with the entitlement process and permitting. After following up in becomi0ng an EIT, Jared has continued adapting further skills in the field including site planning, project entitlements, SWPPP , scheduling, and material take off, along with collaborating with Project Managers and Superintendents for contract development, procurement, and scheduling, and has skills and experience in scope management during construction to ensure plans are built to specifications.

Civil Engineering from California State University-Long Beach.

ExPERIENCE
LOCAL STREETS REHAbI LITATION PHASE I (CONCRETE IMPROVEMENTS) zO NE 3, norwalk
Jared provided Project Engineering services on the Local Streets Rehabilitation Program Phase I (Concrete Improvements) in Zone 3, which is bound by the Union Pacific Railroad to the Northwest, the I-5 Freeway to the Northeast, Imperial Highway to the South, and Firestone Boulevard to Southwest. The project involved removal and replacement of sidewalk (3,000 SF); curb and gutter (2,600 LF); new and replacement ADA curb ramps (93 ramps and 10 truncated domes); driveway approach repairs (500 SF); cross gutter replacements (29 locations with associated curb ramps); including incidental asphalt work, utility relocations and traffic control.

TRAbU CO ROA d RESURFACING PRO jE CT (PEACH wO Od TO bAk E PAR kwA Y), lakE forEST
Jared served as Project Engineer for OE which was awarded this project and assigned the task to prepare full design Plans, Specifications and Estimates (PS&E) to the City of Lake Forest on the Trabuco Road Resurfacing Project for road resurfacing on Trabuco Road, between Peachwood Parkway and Bake Parkway. The work required the construction of 11 ADA ramps and 2 ADA driveways in total, median curb height construction, along with curb gutter and sidewalk repairs, and signing and striping replacement. The main objective is to improve the PCI for Trabuco Road following our team’s professional assessment of the existing pavement conditions in order to extend the useful service life of the streets, improve safety by upgrading to safer streets with better ride quality and pedestrian access, minimize future maintenance needs and costs, and enhance aesthetics.

LAk E FOREST dRI VE RESURFACING, FROM bAk E PAR kwA Y TO I-5 FREEwA Y, lakE forEST Jared served as Project Engineer for OE which was awarded this project and assigned the task to prepare full design plans, specifications and estimates (PS&E) for this roadway resurfacing project located at Lake Forest Drive, between Bake Parkway and the I-5 freeway. The project design plans were to be phased in order for the construction to be distributed into three phases as funding permitted. Along the approximately 5.5 mile stretch of road within the project limits, the phases required the construction of 152 ADA ramps and 22 ADA driveways in total and 7,105 linear feet of median curb height construction, along with the construction of bus pads, curb gutter and sidewalk repairs, and signing and striping replacement. The main objective was to improve the PCI of the street segments following our team’s professional assessment of the existing pavement conditions in order to extend the street service life, improve safety by upgrading to safer streets with better ride quality and pedestrian access, minimize future maintenance costs and enhance aesthetics.

This project was funded through Measure M2, SB1 and Infrastructure Reserves Funds.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 64 276
ARdE N dR . zO NE 3 STREET & bIk E LANE IMPROVEMENTS PROjE CT (CIP 053/058), El monTE
Jared provided Project Engineering design services for the City of El Monte on the Arden Drive Zone 3 Street and Bike Lane Improvements Project. The work called for the preparation of PS&E to rehabilitate pavement on Zone 3 streets and Arden Drive, as well as construct ADA ramps, repair damaged curb and reconstruct cross gutters where drainage was affected.

The pavement was treated with slurry seal, cape seal, milling and overlays. Failed pavement sections were treated with a deeper grind and a grindable fibrous interlayer to prevent reflective cracking in lieu of full depth reconstruction. Sidewalk was replaced in areas that did not meet ADA compliance, such as heaved sidewalk panels and minimum path widths. Damage due to tree root infiltration of 126 trees was also noted, requiring OE to assign a licensed arborist. Further enhancements were included in the design per the San Gabriel Valley Regional Bicycle Master Plan to include a Class II bike lane along Arden Drive and Class III bike lanes along Hickson Street, Esto Avenue, Marsen Street, Ranger Avenue, and Arden Way. OE subsequently updated the City’s Master Bike Plan with recommendations. OE also conducted public outreach activities to address concerns from local businesses, residents and stakeholders affected by the construction.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 65 277
Er i C UrSo , lsit
proJe ct engineer
10 years of
ex perience
fi elds
of
ex pertise ROADWAY ADA RAMP SURVEY BIKE TRAIL PAVEMENT
QUALiFiCATiONS
BS: Civil Engineering, The Citadel, The Military College of South Carolina ● mS: Geographic Information Science, California State University, Long Beach● lSiT: # 9297: Land Surveyor-In-Training ● So f Tw ar E: AutoCAD, SurveyCAD and Civil 3D
bA C kGROUN d
Eric found his passion in the Civil Engineering field over 10 years ago, graduating with a Bachelor of Science in Civil Engineering from The Citadel, The Military College of South Carolina, and very recently completing his Master’s program at California State University, Long Beach in Geographic Information Science (GIS). He has spent many years working in construction management. His time spent in construction management helped him understand many of the inner- workings of the industry . Lately , within the past year , Eric has focused his attention toward Land Surveying. In that role, he ha s pe rf or med t opog r aph i c su rv e y s, c on st ruct i on su rv e y s, bou nd ary su rv e y s, and c on st ruct i on st aki ng , w h i c h ha s sharpened his skills and increased his attention to detail, allowing for a more clear understanding when applying his skills and experience to CAD work, including proficiency with Pix4DMapper, ENVI and photogrammetry. Eric has now worked as a Land Surveyor on various projects for Los Angeles and Orange Counties. Such projects include the 6th Street Bridge in Downtown Los Angeles, Metro Purple Line Extension Section 3 in Century City, and 405 Highway Widening for Orange County Transportation Authority (OCTA). This work includes proficiency in using the Leica Total Station System and Data Collector and the use of GPS for traversing and establishing bench marks.

Civil Engineering from California State University-Long Beach. ExPERIENCE 247TH STREET AREA wA TER MAIN REPLACEMENT PROjE CT, lomI T a Eric served as Project Engineer to The City of Lomita for the 247th Street Area Water Main Replacement Project. The project limits were on 246th Street, 247th Place, 248th Street, Western Avenue and Lomita Boulevard and involved the installation of 3,300 linear feet of new 6-inch PVC water mains to provide improved flow, pressure, and fire protection. The existing 4-inch/6-inch water main systems were constructed between 1928 and 1930 and had exceeded its useful service life. The proposed water main was installed parallel to the existing main while keeping the old line in service to minimize downtime for the public. All fire hydrants, service laterals, valves, blow-offs, air release valves, and other associated water appurtenances were replaced, and sectional pavement, curb gutter and sidewalk were removed and reconstructed according to ADA standards and drainage patterns. Encroachment permits from Caltrans and the City of Los Angeles within their jurisdictions were secured. Funding was sourced from the City’s CIP Program and the FEMA Hazard Mitigation Grant Program.

EUCLId STREET REHAbI LITATION & RESURFACING, FROM EdI NGER TO wA RNER AVENUE, foUn TaIn vall Ey
Eric served as Project Engineer to the City of Fountain Valley on the Euclid Street Rehabilitation and Resurfacing Project, which was located on Euclid Street, from Edinger Avenue to Warner Avenue. Approximately 5200 linear feet (1 mile) of roadway required rehabilitation which involved curb, gutter and sidewalk reconstruction, 8 curb returns with ADA curb ramp and 5 driveways to be replaced, signing and striping replacement, and utility appurtenance adjustments. Aerial photographs of the street were captured for use in base map features which included utility appurtenance locations, digout areas, street striping configurations, and pavement limits, along with a topographic survey. The construction budget of this project totaled approximately $1.7 million.
bE NNETT AVENUE, wA SHINGTON AVENUE, wE STRIdG E AVENUE ANd bE NdE R AVENUE CUL-dE -SACS PRO jE CT, glEn dora
Eric served as Project Engineer on the Bennett Avenue, Washington Avenue, Westridge Avenue and Bender Avenue Cul- De-Sacs Project for the City of Glendora. This included the design of nearly 7,000 LF of new 8-inch ductile iron/C909 PVC water mains to improve flow, pressure and fire protection, along with 311,000 SF of streets requiring improvements. Other work included a striping enhancement concept to incorporate marked class II bike lanes, repurposing crosswalk warning lights, reconstructing and replacing 16 ADA curb ramps for compliance, traffic signal inductive loop replacement, and water main appurtenance installation and replacement. A section of pipeline located at Bennett Avenue near Valencia Street had passed beneath a storm drain, requiring directional drilling to facilitate new water main installation through the area. This was accompanied by assessments of fire hydrants, air and vacuum release valves, and water meters and services laterals.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 66 278
dU RFEE AVENUE & RAMONA bO ULEVAR d SIdEwA Lk I MPROVEMENTS PROjE CT, El mon TE Eric was the Project Engineer for the City of El Monte on the Durfee Avenue and Ramona Boulevard Sidewalk Improvements Project (CIP No. 002). The project limits included two areas. The first was south side of Ramona Boulevard, between the eastern city limit - west side of San Gabriel River Trail – and Durfee Avenue (1,115 linear feet). The second location was on both sides of Durfee Avenue, between Ramona Boulevard and the address of 4000 Durfee Avenue (2,525 linear feet). The project had five main objectives. (1) reconstruct sidewalks, driveways, and curb ramps within project limits as necessary to comply with current ADA requirements. (2) identify surface utilities preventing ADA compliance and provide design alternatives that include constructing around the interfering utilities or relocating them. (3) evaluate existing infrastructure (sidewalks, driveways, and curb ramps) for adherence to current ADA requirements. (4) construct new ADA compliant sidewalk where absent. (5) ensure all improvements are constructed within the existing right-of-way. zO NE 3 COLLECTOR ROA d IMPROVEMENTS PROjE CT, lagUn a B EaCh Eric served as Project Engineer to the City of Laguna Beach toward the development of Plans, Specifications & Estimates for street improvements of Park Avenue, from Glenneyre Street to Wendt Terrace; Glenneyre Street, from Park Avenue to Thalia Street; and Thalia Street, from Temple Hills Drive to the South End The City. The project consisted of rehabilitating approximately 3,200 linear feet of Park Avenue, 2,500 linear feet of Glenneyre Street, and 2,500 linear feet of Thalia Street.

Additional tasks include analyzing crown slopes at pedestrian crossings to reduce crossfall and steep crowns, as needed, along with utility adjustments, a record of survey on Thalia Street, a two-phase set of traffic control plans, and signing and striping. Traffic control and detour plan phasing was also included in order to accommodate the summer moratorium. For Thalia Street, OE prepared a Record of Survey and filed with the County of Orange illustrating the existing centerline from Temple Hills Drive to the southwest end. .

METRO wEST S IdE P URPLE LINE ExT ENSION PROjE CT, loS angElE S Eric processed and reviewed submittals and any transmittals necessary for decking and excavation work at La Brea, Fairfax, and La Cienega on the Metro West Side Purple Line Extension Project. In providing Metro with any support they needed, Eric’s duties encompassed public records inquiries, pay app reviews, RFI reviews, keeping up to date with SOE work which includes pile production and tracking, Geotech Instrumentation, tie back installation, coordination with surveyors, and participating in field visits when, necessary.

METRO dI VISION 20 PORTAL wIdE NING TURNbA Ck PROjE CT, loS angElE S On the Metro Division 20 Portal Widening Turnback Project for the City of Los Angeles, Eric processed and reviewed submittals, RFIs, and correspondence for construction services in Metro Rail Yard which consists of demolition, civil improvements, traction power substation, ductbanks, street improvements, support of excavation, and structural bridge reinforcement.
6TH STREET bRIdG E VIAdU CT REPLACEMENT PROjE CT, downTo wn loS angElE S Eric provided Project Engineering Services on the 6th Street Viaduct Replacement Project which replaces the original structure built in 1932. The new structure viaduct accommodates vehicles and pedestrians, as did the original, and provides dedicated lanes for bikes. A new 1 2 -acre public park running below the bridge, accessible by multiple stairways and a monumental helical bike ramp, provides access to much-needed recreational fields with restrooms and café, the LA River, public art, and a programmed arts plaza. The new viaduct, a tied arch bridge referred to as the “Ribbon of Light,” pays homage in its design to the 1932 bridge, which had two pairs of iconic arches over the LA River section of the structure. The new bridge employs a series of 10 pairs of sculptural arches with the tallest pairs placed adjacent to and framing the LA River where the original arches stood and another taller pair span the I-101 as a gateway on the east. The $588-million project was funded by the Federal Highway Administration, the state of California and the City of Los Angeles. The project was completed in the Summer of 2022.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 67 279
hEnr y l U
proJe ct engineer
5 years of
ex perience
fi elds
of
ex pertise roadway ada ramp pavement survey water main QUALiFiCATiONS
BS: Civil Engineering, University of Transport, Ho Chi Minh City, Vietnam ● So f Tw ar E: AutoCAD, Civil 3D, SewerGEMS, GEO-Slope ● Sk ill S: Design & Analysis for Roadway, Slope Stability & Drainage Design bA C kGROUN d
Henry is a skilled Project Engineer, able to handle a wide range of Civil Engineering Drafting with the use of AutoCAD. His Civil Drafting work experience has involved title sheets, general notes, existing conditions, and plans for site, utility, fire access, erosion control and parking in the field of Land Development; AL TA land titles, boundaries, topographics, pre- construction, commercial and residential surveys in the field of Land Surveys; plans for landscape, foundation, floor, and roof in the field of Architecture Drawings; As-Built Drawings, showing the changes during construction; and beams, columns, foundations, slabs, piles, and stairs in the field of Structural Drawings. His experience on plans extends to Public Improvement Construction, Site Improvement, and Final Development. His design drawings experience is lengthy, involving Plan and Profile Roadway Design, Finish Surface and Intersection, Subdivision and Curb Ramp Designs, Pland and Profile of Sanitary Storm Water, Sewer, Water Lines, Surface Model and Earthwork Calculations, Interference Check, Existing Surface Contour Analysis, Infraworks, and Topographic Surveying.

ExPERIENCE
PUEbL O STORAGE ROA d wA Y IMPROVEMENTS PROjE CT, napa
Henry provided Project Engineering services on the Pueblo Storage Roadway Improvements Project in the City of Napa, California. Located at Pueblo Avenue, the project consisted of 7 Buildings and Parking Lots on a parcel area totaling approximately 101,756 square feet of roadway at a width of 18 feet. Henry provided the construction and roadway design for the entire project, from survey to completion. Utilities were also included involving a 12 inch storm drain, a 1 inch water PVC, and a 4 inch sewer PVC SDR 26, and gas and electrical.

ROSECRANS RESIdE NCE ROAd wA Y IMPROVEMENTS PROjE CT, napa Henry provided Project Engineering services on the Rosecrans Residence Roadway Improvements Project in the City of Napa, California. The project was located at Steele Canyon Road and required new roadway design for a 37 .43 AC parcel area measuring 12 feet wide and 22,553 square foot (0.52 AC) long, along with utility design of an 18 inch storm drain, 6 inch PVC, an 8 inch wide sewer system, gas, electric, etc. A City of Napa Ladder Truck was utilized for a fire prevention plan.

MARIN wO OdS S Ub dI VISION NC HIGHwA Y 210 PROjE CT, Joh n Son, n C Henry served as the Project Engineer on the Marin Woods Subdivision NC Highway 210 Project in the City of Johnson, North Carolina. The project consisted of 143 proposed lots, 149,734 square feet of the 210 highway at 29 feet of length, 5 foot wide sidewalk, an 8 foot dip water main, and an 8 inch PVC sanitary sewer main. Henry was called upon to provide the needed construction drawings for the area and to provide the new designs for the utility systems.

ORANGEbU R d ROAd PROjE CT, PHASES I & II, dorCh ESTEr , nC Henry was the Project Engineer for Dorchester County on two phases of the Orangeburd Road Project. Henry provided the construction drawings for 132 lots and 60 feet of right-of-way, 4 foot wide sidewalk, an 8 inch C900 PVC and DIP water line, an 8 inch DIP & PVC sewer line, and a 15 inch to 36 inch storm drain line.

MILLARd CROSSING PROjE CT, norT h Ca rol In a
Henry provided Project Engineering services on the Millard Crossing Project in North Carolina. Henry provided the construction drawings for 95 lots and 60 feet of right-of-way, 5 foot wide sidewalk, and 15 inches to 24 inches of storm drain, an 8 inch PVC water pipe, and an 8 inch PVC sewer line.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 68 280
lEonard phUn g
constr Uc tion inspector
5 years of
ex perience
fi elds
of
ex pertise roadway ada ramp pavement survey water main QUALiFiCATiONS
BS: Civil Engineering, University of Transport, Ho Chi Minh City, Vietnam ● So f Tw ar E: AutoCAD, Civil 3D, SewerGEMS, GEO-Slope, InfraWork ● Sk ill S: Design & Analysis for Roadway, Slope Stability & Drainage Design bA C kGROUN d
Leonard is a skilled Project Engineer, able to handle a wide range of Civil Engineering Drafting with the use of AutoCAD.

His Civil Drafting work experience has involved title sheets, general notes, existing conditions, and plans for site, utility, fire access, erosion control and parking in the field of Land Development; ALTA land titles, boundaries, topographics, pre-construction, commercial and residential surveys in the field of Land Surveys; plans for landscape, foundation, floor, and roof in the field of Architecture Drawings; As-Built Drawings, showing the changes during construction; and beams, columns, foundations, slabs, piles, and stairs in the field of Structural Drawings. His experience on plans extends to Public Improvement Construction, Site Improvement, and Final Development. His design drawings experience is lengthy, involving Plan and Profile Roadway Design, Finish Surface and Intersection, Subdivision and Curb Ramp Designs, Pland and Profile of Sanitary Storm Water, Sewer, Water Lines, Surface Model and Earthwork Calculations, Interference Check, Existing Surface Contour Analysis, Infraworks, and Topographic Surveying.

ExPERIENCE
CECILE COURT SUb d IVISION PROjE CT-LLOYd dR IVE IMPROVEMENTS, napa Leonard provided Project Engineering services on the Cecile Court Subdivision Project-Lloyd Drive Improvements in the City of Napa, California. Located at 4060 Lloyd Drive, the project consisted of approximately 46,655 square feet of roadway at a width of 36 feet, 4 foot wide sidewalk, and a 30 foot radius cul-de-sac. Leonard provided the roadway improvement design for the entire project, from survey to completion. Utilities were also included, and involved a 6 inch PVC storm drain pipe and an 8 inch sewer PVC, and gas and electrical.

LOS RObL ES SUb dI VISION PROjE CT, napa
Leonard provided Project Engineering services on the Los Robles Subdivision Project in the City of Napa, California. The project was located at Seville/Los Robles Drive and required new roadway improvement plans design for 256,356 square feet of the roadway measuring 22 feet in width. The project also called for the design of 3 retaining walls at a max height of 5 feet for each wall, as well as utility design of an 18 inch storm drain, 8 inch PVC, an 8 inch wide sewer system, gas, electric, etc. A City of Napa Ladder Truck was utilized for a fire prevention plan. wE N dE LL FALLS ROA d wA Y & PUbL IC UTILITY IMPROVEMENT PROjE CT, wE ndE ll, nC Leonard served as the Project Engineer on the Wendell Falls Roadway and Public Utility Improvements Project in the City of Wendell, North Carolina. The project consisted of 38,068 square feet of roadway at 30 feet of length, 16,702 square feet of 5 foot wide sidewalk, 1,878 LF of water main, and 2,180 LF of sewer main. Leonard was called upon to provide the needed construction drawings for the area and to provide the new designs for the utility systems improvements.

HIGHLANd RIdG E SUb dI VISION PROjE CT, PHASES I - IV, angI E r , nC Leonard was the Project Engineer for the Highland Ridge Subdivision Project, Phases I thru IV in Angier, North Carolina. The project was located at Kennebec Road. Leonard provided the construction drawings for 256 lots and 60 feet of right-of-way, 5 foot wide sidewalk, an 8 inch C900 PVC and DIP water line, an 8 inch DIP & PVC sewer line, and a 15 inch to 36 inch storm drain line on all 4 phases. Leonard also provided erosion control plans design for the first three phases.

MILLARd CROSSING PROjE CT, norT h Ca rol In a
Henry provided Project Engineering services on the Millard Crossing Project in North Carolina. Henry provided the construction drawings for 95 lots and 60 feet of right-of-way, 5 foot wide sidewalk, and 15 inches to 24 inches of storm drain, an 8 inch PVC water pipe, and an 8 inch PVC sewer line.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 69 281
Ch ri S Bo r En
constr Uc tion inspector
17 years of
ex perience
fi elds
of
ex pertise ROADWAY ADA RAMP SLURRY SEAL BIKE TRAIL PAVEMENT QUALiFiCATiONS
lEvElS I & II: Public Works Inspector ● EXpEr i EnC E: Federally Funded Projects, California State Caltrans Projects bA C kGROUN d
Chris is a Construction Inspector at Onward Engineering. He has a variety of certifications and has taken part in multiple training programs over his 17 years of experience. His experience includes a plethora of projects, and he advocates safety and quality at the jobsite. His accuracy and efficiency in the field ensure a successful project. Chris’ work will always include making sure that the contractor is efficient with his time and acting in the best interest of the City as their advocate in the field.

ExPERIENCE
STORM dR AIN & PAVEMENT REHAbI LITATION PROjE CT, ranCh o C UCa monga Chris provided inspection services to the City of Rancho Cucamonga on the Ramona Avenue Storm Drain & Pavement Rehabilitation project. The project limits were from Foothill Boulevard to South of the Pacific Electrical Trail. The project included the installation of approximately 1,000 LF of 60” RCP , construction of 3 manhole structures, installation of 2 laterals and catch basins, as well as a junction structure.
19TH ST. HELLMAN AVE. PAVEMENT REHAbI LITATION, ranCh o C UCa monga Chris provided inspection services to the City of Rancho Cucamonga on the 19th St. Hellman Avenue Pavement Rehabilitation project. The project limits were from Haven Avenue to West City Limit, and Hellman Avenue from Baseline Road to 19th Street. The project included a Grind and Asphalt Rubber Hot Mix (ARHM) overlay, adjustments to manholes, water valves, and gas valves. It also included the installation of traffic loops, traffic signs, striping, and traffic signal video detection. In addition, the project called for traffic control for the duration of the project.

CHINO HILLS Pk wY ./CHINO AVE. REHAb ILITATION-STPL, ranCh o C UCa monga Chris was the construction inspector for the City of Diamond Bar for this STPL -funded project. The site spanned 1.25 miles along Chino Hills Parkway, from the north city limit to the south city limit, and Chino Avenue, from Chino Hills Parkway to the eastern city limit. The scope included grind and ARHM overlay, 783 SF of local R&R, and minimal PCC curb, gutter, and sidewalk replacements. A constructability review was conducted prior to construction commencing, and noted several additional reconstruction areas along with several ramp upgrades to add to the scope. In addition, paving was coordinated to be completed at night to minimize traffic congestion. bRI STO w PAR k NEIGHbO RHOOd REHAbI LITATION PROjE CT, Co mm ErC E Chris provided inspection services on this CDBG-funded project roadway project in the City of Commerce. The Bristow Park Neighborhood Rehabilitation Project was constricted by the I-5 Freeway to the north, BNSF Railroad to the south, the City of Los Angeles Boundary to the west and the 710 Freeway to the east. The project covered approximately 4,900 LF of roadway. During the design phase a cost-benefit analysis was conducted to provide the City with multiple rehabilitation alternatives, including conventional full-depth reconstruction, Asphalt Rubber Aggregate Membrane (ARAM), Asphalt Rubber Hot Mix (ARHM), Inter-layer Systems and Cold-In-Place Recycling (CIR)/Full Depth Reclamation. Multiple design coordination meetings were additionally held between the City, OE and other stakeholders during design to ensure the most complete design possible. A combination of full-depth reclamation and reconstruction and Grind & Overlay was the selected rehabilitation method. Construction also included replacing damaged sidewalk, installing 25 new ramps and upgrading 13 more to meet ADA compliance, reconstruction of cross-gutters, and replacing street signs, trimming tree roots and installing barriers.

CITYwIdE S TREET REHAbI LITATION - PHASE II (ARRA FUNdEd), BEl l gardEn S Chris provided construction inspection services on this ARRA-Funded project for the City of Bell Gardens on local and arterial streets. The scope of work included 187,468 SF of variable depth cold milling, construction 5 ADA compliant curb ramps, retrofitting 32 ADA compliant curb ramps, and constructing curb & gutter, sidewalk, alley approaches, and PCC bus pads. Furthermore, the project entailed localized full section removals, the installation of CMB materials, BMP implementation, and traffic control.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 70 282
RESIdE NTIAL AREA 1 b & ARTERIAL zO NE 7 ROAd MAINTENANCE, dI amond Ba r Chris was the Inspector in the City of Diamond Bar. Areas 1B and Zone 7 consisted of 8.9 miles of residential streets, 1.3 miles of collector streets, and 2.5 miles of arterial roadways. For the annual project OE was tasked with providing a design for rehabilitating the streets in a manner that meets the City’s tight budget. Each street was individually inspected to determine the most cost effective remedy. The scope of work entailed 29,000 SY of chip seal, type II slurry seal, 5,235 tons of AC overlay, 210,000 SF of cold milling the existing pavement to a variable-depth of 6’ from the edge of the gutter, removal and replacement of 2,249 tons of AC pavement, adjusting 127 manhole frames and covers, and 147 water & gas valve covers, and installing 6 traffic loop detectors. Furthermore, an elementary school was within the project limits, which made scheduling and phasing for both the pavement and striping operations essential in order to provide safety and accessibility from beginning and end of the school day.

CRENSHAw bL Vd. & LOMITA bL Vd. INTERSECTION IMPROVEMENT PROjE CT, lomI T a Chris provided inspection Services for this arterial roadway and intersection rehabilitation project in the Cities of Lomita and Torrance. As a joint agency project, it required extensive coordination with both the City of Lomita and Torrance in order to ensure success of the project. The project limits spanned 1,300 LF on Crenshaw Boulevard to the north and south of Lomita Blvd., and 2,900 LF on Lomita Blvd. from Crenshaw Blvd. to Narbonne Avenue. The construction included 4,800 tons of ARHM overlay, 1,500 tons of AC base paving, field identification and reconstruction of failed pavement areas, PCC curb ramp, sidewalk and curb and gutter replacements, traffic signal modifications including the installation of a new video detection system and the rewiring of the intersections, and roadway signing and striping improvements. The project also included chairing and presenting at a community coordination meeting in order to disseminate project information. In addition, the project required working with the Contractor and the City to negotiate field quantity reductions and change orders which created a large amount of project savings on the job.

ROSINI & ROSEwO Od REHAbI LITATION PROjE CT, BEl l gardEn S Chris provided inspection services to the City of Commerce on the Rosini & Rosewood Neighborhood Roadway Rehabilitation project. This politically-sensitive residential reconstruction project took place just south of I-5 and north of heavily traveled Washington Boulevard. During the design, a thorough pavement investigation was conducted, which included an inventory of potential parkway improvements which were prioritized to ensure maximum utilization of the City’s available budget. Our team presented several options to the City with a cost-benefit analysis. This heavily deteriorated roadway was reconstructed utilizing Full-Depth Reclamation, 14” of roadway was excavated, and a 10” section was treated with cement. The construction entailed replacing curb and gutter and sidewalk, as well as ensuring that ramps met ADA standards.

CITYwIdE S TREET REHAbI LITATION - PHASE I (ARRA FUNdEd), BEl l gardEn S Chris provided construction inspection services on this ARRA-Funded project for the City of Bell Gardens. The scope of work including approximately 1 mile of grind and overlay, 370,818 SF of variable depth cold milling, localized full section removals, and the installation of CMB materials. Furthermore, the project entailed constructing 19 ADA compliant curb ramps and retrofitting 21 ADA compliant curb ramps. The project required inspecting curb and gutter, driveway approaches, sidewalks, and local depressions, it also required adjusting sewer and storm drain manhole covers, water valves, traffic signal pull boxes, traffic striping, and traffic signal loop detectors. Chris also provided extensive traffic control for the duration of the project.

RAMONA “A” ROAd wA Y REHAbI LITATION - ARRA FUNdEd, Bal dw In park Chris provided construction inspection services on this ARRA funded project for the City of Baldwin Park on 4,285 SF of PCC roadway. The scope of work entailed 200,656 SF of cold milling, constructing 14 ADA compliant curb ramps, PCC roadway, spandrels, curb & gutter, driveway approaches, sidewalks, and stamped concrete. Furthermore, the project required sewer and storm drain manhole adjustments, water valve can adjustments, 16” to 24” diameter tree removal, installing six 2” water service and backflow device, and upgrading the existing irrigation systems and installing a new parkway irrigation system. bE VERLY bL Vd. RE HAbI LITATION PROjE CT - ARRA FUNdEd, pI C o rI v Er a Chris provided construction inspection services on this ARRA funded project for the City of Pico Rivera. The scope of work included a 1.3 mile grind and overlay, curb & gutter, sidewalk, driveway approaches, cross gutters, constructing 13 ADA compliant curb ramps, and retrofitting 3 ADA compliant ramps. Furthermore, the project required localized full section removals, installation of CMB materials, BMP implementation, and traffic control.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 71 283
JEf fr Ey EaTo n, Qs p
constr Uc tion inspector
35 years of
ex perience
fi elds
of
ex pertise CALTRANS BRIDGE ROADWAY ADA RAMP PAVEMENT
QUALiFiCATiONS
3 yEa r STUd y: Computer Science, California State University, Fullerton, 2004 ● aS: Construction Management, Santiago Canyon College ● qSp: Qualified SWPPP Practitioner ● 35 yEa r S: Public Works Construction, The County of Orange bA C kGROUN d
Jeffrey Eaton is a long-time experienced and motivated construction inspector, having acquired successful employment with many reputable companies. Jeffrey has also recently obtained an AS degree in Construction Management from Santiago Canyon College. Jeffrey has accumulated 35 years of experience in public works construction for the City of Orang alone, with 11+ years of that in serving as a construction inspector for City Capital Improvement Projects, which called for encroachment permits, subdivisions, job order contracts, and Caltrans projects. Jeffrey has recently come out of retirement, having last served as a Senior Construction Inspector with a current certificate for Qualified SWPPP Practitioner (QSP). In his previous experience involving with public works projects, Jeffrey was involved in/responsible for testing and inspecting construction materials, performing geotechnical investigations, and pavement design and rehabilitation.

ExPERIENCE
OSO PARkwA Y bRIdG E AT SR 241 CALTRANS PROjE CT, orangE C oUnTy Jeffrey served as the Lead Construction Inspector on Oso Parkway Bridge at SR 241 Caltrans Project for The County of Orange. The project involved the inspection of temporary traffic control, paving, grading, storm drain, traffic signals, striping, post construction BMP’s, temporary BMP’s, a concrete barrier, The Midwest Guardrail System, overhead sign structures, roadside signs, toll road booth structure removal, toll plaza construction (with jointed plane concrete pavement), bridge pile driving, temporary soil nail shoring, bridge abutment, and a bridge approach slab. Jeffrey additionally assisted the structure inspector for a bridge construction inspection. Other tasks Jeffrey performed included writing daily inspection reports, preparing weekly statement of working days, preparing monthly progress payments, and reviewing submittals and RFI’s, along with reviewiing extra work bills, and maintaining a professional working relationship with the Resident Engineer, Structure Inspector, Caltrans Permit Coordinator, Transportation Corridor Agency, Design Engineer, and the general public.
dA NA POINT HAR bO R dREdG ING PROjE CT, dana poInT
Jeffrey provided construction inspection services as the Lead inspector on the Dana Point Harbor Dredging Project in the City of Dana Point. The project required inspection work on dredging within Dana Point Harbor, the installation and removal of temporary pipeline from the harbor to Capistrano Beach for sediment deposit, the grading of dredged material at Capistrano Beach and Baby Beach (DPH), coordinating with OC Survey on calculating quantities, and inspecting temporary BMP’s.
dA NA POINT HAR bO R PAR k ING LOT OVERLAY PROjE CT, dana poInT Jeffrey provided Lead Inspection services on the Dana Point Harbor Parking Lot Overlay Project in the City of Dana Point, which was a job order contract. The project involveed pavement and curb removal and replacement, AC overlay, striping, and temporary BMP’s.

TRAbU CO CREE k PROjE CT - PHASE VII, Ir v In E
Jeffrey provided Lead Inspection services on phase VII of the Trabuco Creek Project. The main work detail included steel sheet pile installation (5,000+ LF), bike trail construction, CMU walls, down drain, and a cable fence.

OCPw C APITAL IMPROVEMENT PRO jE CTS, orangE C oUnTy
Jeffrey provided construction inspection services on Capital Improvement Projects for County of Orange Public Works (OCPW) on work that included arterial highway construction, storm drain construction, slurry seal, asphalt concrete overlay, landscaping, flood control construction, and structural concrete. Part of Jeffrey’s tasks required the review of plans, special provisions, and estimates for various types of projects, writing contract change orders, preparing progress payments with quantity calculations, reviewing contract submittals and RFI’s, reviewing extra work bills, preparing weekly statement of working days, and producing daily inspection reports. Jeffrey also conducted preconstruction meetings and weekly progress meetings, along with inspecting Job Order Contracting maintenance projects, and performing NPDES compliance inspections on all projects.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 72 284
RIGHT-OF-wA Y & PROPERTY PERMITS INSPECTION, orangE C oUnTy Jeffrey provided construction inspection services on public works construction projects involving work in The County of Orange Right-of-Way and County Property Permits. This included inspecting various permits for homeowners, utility companies, developers, and businesses. Jeffrey also reviewed engineering plans for permit construction, which required the use of the County’s CPP system. Jeffrey further inspected the subdivision work, which included curb and gutter, sidewalk, paving, storm drain, catch basins, landscaping, grading, and utility installment. Jeffrey also performed grading inspections in subdivision construction for private property projects, which included inspecting mass grading in subdivision, retaining walls, and building foundations, along with reviewing certificates of compliance from engineers and contractors, and reviewing grading plans and geotechnical reports. Jeffrey made sure to perform the daily entries into the department’s APPS system.

COUNTY PROPERTY PERMITS INSPECTIONS, orangE C oUnTy
Jeffrey provided construction inspection services for public works construction for work in County Right-of-Way for County Property Permits. This included inspecting various permits for homeowners, utility companies, developers, and businesses.

Jeffrey also review engineer plans for permit construction, being well versed in using the County’s CPP system. Jeffrey also inspected subdivision work for County of Orange, which included curb and gutter, sidewalk, paving, storm drain, catch basins, landscaping, grading, and utility installment, and he performed grading inspections in subdivision construction and private property. This included inspecting mass grading in subdivision, retaining walls, and building foundations.

Jeffrey further inspected certificates of compliance from engineers and contractors, and he reviewed grading plans and geotechnical reports, performed daily entries into the Department’s APPS system, and performed NPDES compliance inspections on all projects.

COUNTY RESURFACING PROjE CTS SUPERVISEd ENGINEERING TECHNICIAN II, orangE CoUnTy
Jeffrey supervised Engineering Technicians performing pavement analysis and investigations; performed pavement analysis using ground penetrating radar and falling weight deflectometer; designed overlay thicknesses for County resurfacing projects. Jeffrey reviewed plans and specifications for County public works projects, wrote geotechnical and materials reports for the County geotechnical engineer, which included designs by County standard plans and Greenbook specifications. Jeffrey further designed traffic control plans using the MUTCD, and performed geotechnical investigations with field techniques such as drilling, site reconnaissance, and visual inspection, and he assisted the geotechnical engineer and engineering geologist in inspecting the Seven Oaks Dam periodically from a geotechnical point of view.

REHAbI LITATION PRO jE CTS SUPERVISE d EN GINEERING TECHNICIAN III, orangE C oUnTy Jeffrey evaluated, analyzed, and designed road structural sections for rehabilitation; wrote Materials Reports for geotechnical projects, subdivisions, and arterial highways; wrote street rehabilitation reports for County road projects, including strategies for rehabilitation; mapped removals and replacements, including measuring quantities; designed and implemented various computer applications; drafted boring logs, project exhibits, and maps; performed engineering calculations.

PAVEMENT ANALYSIS & INVESTIGATIONS, SanTa ana
Jeffrey provided construction inspection services and supervised engineering technicians in the process of performing pavement analysis and investigations in the City of Santa Ana. Additional work for Jeffrey included performing the pavement analysis using ground penetrating radar and a falling weight deflectometer, and the design work for overlay thicknesses for the City’s resurfacing projects. Jeffrey also reviewed plans and specifications for The City Public Works Projects in which he wrote geotechnical and materials reports for the City geotechnical engineer , in which involved design work requiring compliance to The City Standard Plans and Greenbook Specifications. Further design work included traffic control plans using the MUTCD, and further geotechnical investigations involved field techniques such as drilling, site reconnaissance, and visual inspection. Lastly, Jeffrey assisted the geotechnical engineer and engineering geologist in inspecting the Seven Oaks Dam periodically, lending a geotechnical engineer point of view.

ROAd w A Y REHA bI LITATION dO CUMENTATION & dR AFT REPORTING, SanTa ana Jeffrey was tasked with evaluating and analyzing designed road structural sections for rehabilitation, writing Materials Reports for geotechnical projects, subdivisions, and arterial highways, and writing street rehabilitation reports for County and City road projects. This included reports on strategies for rehabilitation, along with mapping removals and replacements, including measuring quantities. Jeffrey was also involved in the design and implementation of various computer applications and drafting boring logs, project exhibits, and maps.Ω SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 73 285
Ca rlo S lo pE Z
constr Uc tion inspector
38 years of
ex perience
fi elds
of
ex pertise ROADWAY TRAFFIC ADA RAMP WIDENING BRIDGE
QUALiFiCATiONS
aa dEg r E E: Civil Engineering Technology, LA College ● ChannEl inSpEC Ti on: Drainage & Flood Control ● 4 yEarS: Supervising Inspector, County of Orange ● 23 yEarS: Senior Inspector, County of Orange bA C kGROUN d
Carlos is a Construction Inspector with 38 years of experience in public works inspection. Carlos has worked for 23 years as a Senior Construction Inspector and 4 years as a Supervising Construction Inspector for the City of Orange. His knowledge of the Orange City Standards & Construction Specifications Manual is unmatched. On each project, he was responsible for performing quality assurance inspections to achieve compliance with the contract documents, plans, and specifications on all phases of construction. His inspection work experience extends to roadway and heavy drainage, paving, structures, grading, sewer, water, electrical and sign installation, and landscaping items - many projects which have required extensive utility relocation coordination.

ExPERIENCE
bRE A CREE k CHANNEL FLOOd CONTROL-LAMbE RT R d. -CENTRAL AVE., orangE C oUnTy Carlos served as the Construction Inspector on this flood control channel project. Construction included replacing the earthen trapezoidal channel with a larger, higher capacity, vertical wall reinforced concrete channel, including transitions at the bridge undercrossing. Carlos performed all duties of inspector, including installation of H-beam steel plate shoring, earthwork, forms, reinforcing steel bar, concrete placement, measuring, calculating quantities for progress payments, and work site photos for project records. Carlos was responsible for performing quality assurance inspections to achieve compliance with the Contract Documents, plans, and specifications on all phases of construction such as paving, structures, grading, drainage, sewer, water, utility relocation, electrical installation, sign installation, and landscaping items. Carlos coordinated utility relocations to keep the project on schedule. He was charged with coordination of utility relocations being performed by utility companies, chairing regular coordination meetings that were held to discuss the schedule, coordination with construction activities, access, and traffic control, reviewing the Contract Documents, utility agreements, and utility relocation plans, and a matrix that includes delivery constraints for all utilities.

TUSTIN AVENUE & bRIdG E wIdE NING AT HANdY C REEk, orangE C oUnTy Carlos served as the Construction Inspector on this street and bridge widening project. The project entailed widening Tustin Ave. from Orangethorpe Ave. to 2,000’ south and widening the bridge at Handy Creek. Construction included curb and gutter, sidewalk, ADA ramps, bridge piles, abutment extensions, vertical wall reinforced concrete channel at bridge undercrossing, AC bridge approach to BNSF railroad crossing. Carlos performed all duties of inspector, including earthwork, line and grade for street improvements, driving of piles to specified bearing and tip elevation, forms, reinforcing steel bar, concrete placement for bridge structures, relocation of OCSD sewer main, coordination with OCSD Inspection, BNSF for work adjacent to tracks including obtaining BNSF safety card as required, measuring, calculating quantities for progress payments, work site photos for project records, provided Contract Change Order drafts to Resident Engineer for submittal.

C a r l o s c o o r d i n a t e d u t i l i t y r e l o c a t i o n s t o k e e p t h e p r o j e c t o n s c h e d u l e . I n a d d i t i o n t o i n s p e c t i n g t h e u t i l i t y r e l o c a t i o n s to ensure permit requirement compliance and proper horizontal and vertical locations, Carlos effectively coordinated meetings with affected utilities, provided management of construction activities, ensured traffic control, and reviewed utility agreements, and utility relocation plans, and identified critical delivery constraints for all utilities. For the drainage work on this project, Carlos reviewed the Contractor’s Haul Plan identifying the route for hauling material, traffic control, and ensured compliance with the Specifications and the MUTCD.

GLASSELL STREET bRIdG E wIdE NING, orangE C oUnTy
Carlos served as the Construction Inspector on this bridge widening project on Glassell Street over the Santa Ana River.

Construction included phased traffic detours, curb and gutter, sidewalks, steel piles, pile caps, abutment extensions, precast girders, bridge restrainers, decorative retaining walls, AC bridge approaches, bicycle/pedestrian bridge undercrossing, temporary and final relocation of irrigation main and lines. Carlos coordinated utility relocations to keep the project on schedule. He was tasked with coordination of extensive utility relocations. Carlos inspected the utility SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 74 286
relocations being performed by each respective utility company to ensure that they met applicable permit requirements and confirmed that the horizontal and vertical location of the utility was in accordance with the requirements of the utility agreement and the construction contract drawings. Carlos performed all duties of inspector, including diversion of river flows, installation of phased traffic detours, earthwork, line and grade for street improvements, driving of piles to specified bearing and tip elevation, forms, reinforcing steel bar, concrete placement for bridge structures, fabrication of concrete strength test specimens, measuring and calculating quantities for progress payments, coordination with OC Water District for river flow diversions, performing a force account analysis resulting in a savings to the County, and preparing Contract Change Order drafts.

LINCOLN bO ULEVAR d REPAVING PROjE CT-FEdE RAL GRANT, Sa n Ta monI Ca Carlos served as the Construction Inspector to the City of Santa Monica on the Lincoln Boulevard Paving Project which was funded utilizing Federal Transportation Grant. The project limits were at Lincoln Boulevard from the I-10, to the South City limits. Construction was done on Lincoln Boulevard, an undivided arterial roadway, which provides access through commercial portions of Santa Monica, intersecting other major arterials such as Pico Blvd. and Ocean Park Blvd., while also serving as a primary travel route through the City, carrying traffic to multiple points including Marina Del Rey, Pacific Palisades, and LAX. In addition to the roadway rehabilitation, the work entailed constructing a concrete bus lane on Lincoln Blvd., repairing the concrete sidewalks, driveways, and access ramps. The work also entailed enhanced striping and traffic signal installation. This project required extensive coordination with businesses and stakeholders as a result of the construction affecting them the most.

PALOS VERdES bO ULEVAR d REHAbI LITATION, I-121, Tor ran CE Carlos provided inspection services to the City of Torrance on the Palos Verdes Boulevard Rehabilitation Project. The scope of work included rehabilitating Palos Verdes Boulevard between Pacific Coast Highway (PCH) to the City of Torrance southern city limits. The roadway rehabilitation included variable depth cold-milling and overlay, and full-depth repairs on severely deteriorated areas. The project also included concrete improvements to curb, gutter, sidewalks, driveway aprons, cross-gutters, traffic signal upgrades, and new Class 2 bike lanes. Furthermore, the scope of work entailed repairing and lining a sewer pipe, catch basin modifications, landscaping, irrigation, cobblestone hardscape, ADA ramps, and traffic striping.

HARbO R bO ULEVAR d & AdA MS AVENUE IMPROVEMENT PROjE CT, CoSTa mE Sa Carlos was the Construction Inspector for the City of Costa Mesa on the Harbor Boulevard & Adams Avenue project and was funded by Measure 2, State-Local Partnership Program, and Traffic Impact Fee funds. The project required adding a third dedicated left-turn lane eastbound on Adams Avenue, a second dedicated right-turn southbound on Harbor Boulevard, and lastly, extending the northbound left-turn lane on Harbor Boulevard. It consisted of major widening along the southerly side of Adams Avenue near the intersection. The project also included decorative crosswalks at the Harbor Boulevard— Adams Avenue intersection, traffic signal modifications, median alterations, landscaping, and a general grind and overlay of the roadway. Harbor Blvd. & Adams Avenue are two heavily used arterial roads that provide access to multiple businesses and shopping centers, and access to the Orange Coast College, as a result of the construction heavy traffic control was required. This project was identified in a Memorandum of Understanding (MOU) executed by OCTA, Costa Mesa, Fountain Valley, and Huntington Beach for the Garfield Avenue—Gisler Avenue Bridge over the Santa Ana River. wI L dC AT wA Y REHAbI LITATION PROjE CT, Br Ea
Carlos provided inspection services on the Wildcat Way Rehabilitation Project in the City of Brea. The project limits are on Wildcat Way from Lambert Road to the Brea-Olinda High School driveway. The scope of work entailed removing and reconstructing curb ramps, installing three 8 ft. truncated domes on the existing curb ramp, installing a 4 ft. truncated dome on the existing curb ramp, 31,500 SF of variable depth from 0” to 2”, and 1,800 tons of rubberized asphalt overlay.

Furthermore, the project required removing and constructing 750 SF of sidewalk, furnishing and adjusting 11 water gate valves, adjusting 11 manhole frames and covers, traffic striping, and traffic control.

ATLANTIC bO ULEVAR d & FIRESTONE AVENUE REHAbI LITATION PROjE CT, SoU T h gaTE Carlos was an Inspector on this project for the City of South Gate. The project limits were on two arterial streets: Atlantic Avenue from Firestone Boulevard to Patata St. (~1,300 LF) and Firestone Boulevard, from Dorothy Avenue to Atlantic Ave. (~2,200 LF). The project involved the widening and realignment of the intersection to increase the number of thru, left turn lanes, the length of turn pockets, and right turn lanes. In addition to the widening, the scope entailed a concrete approach to the intersection; concrete intersection; grind and ARHM overlay; four legs of the intersection; 50,000 SF of sidewalk, 1,850 LF of curb and gutter, 2,100 LF of DIP waterline and 2,840 LF of recycled waterline, and 4,656 LF of median island curb with decorative landscaping and a city monument sign. This project was funded with Measure R, MTA and other state funding sources, and required the preparation of an award package and the continued upkeep of project files, invoices, reports and submittals in accordance with Caltrans’ LAPM.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 75 287
roB E rT vall E, Qs p , cI sec
constr Uc tion I n spector
30 years of
ex perience
fi elds
of
ex pertise ROADWAY ADA RAMP BRIDGE WIDENING PAVEMENT
QUALiFiCATiONS
Co UrSEw ork: Mathematics & Public Works ● qSp #26670: Qualified SWPPP Practitioner ● CiS EC #2075: Certified Inspector of Sediment & Erosion Control ● Co nfin Ed Sp aC E CErTi fiEd : Cal OSHA Construction Safety and Health bA C kGROUN d
Robert is a highly skilled Public Works inspector with over 30 years of experience. He emphasizes an attention to quality, detail and safety on various types of construction projects. His experience involves supplemental task orders and contract change orders; submittals and RFI’s review and response related to constructability; signatory on Notice to Proceed, Progress Payments, Notice of Completion, ensuring project documentation of inspector daily logs, photographs, concurrence of quantities with contractor for payment, and attending meetings with design engineers, stakeholders, and outside agencies. Robert has been responsible for inspector training related to construction, public relations and sa f e ty , and f or pr o j ect c on st ruct ab i l i ty pee r r e v i e w s o f P S & E . H e i s w e l l v e rs ed i n age nc y spec i a l pr o v i s i on t ha t i n v o l v e Caltrans Standards & Specifications, Standard Specifications for Public Works Construction (Greenbook), public works agency standards, CA MUTCD and WATCH Manual, Regulatory Permits, and NPDES Requirements, alongside document control. Robert also incorporates his skills and knowledge in managing public relations, and he is effective with adept communication toward project stakeholders. He has worked on projects involving road and arterial maintenance and rehabilitation, flood control and bridge repair, grind and overlay, slurry seal, traffic signal upgraids, PCC removal, ADA access ramps replacement, curb, gutter and sidewalk.

ExPERIENCE
STORM dR AIN, SEwE R & ROAd wA Y IMPROVEMENT-PHASES I, II, & III, wE ST m InS TEr As both the Construction Manager and Resident Engineer for the City of Westminster, Robert oversaw the complete demolition and reconstruction of the project existing roadway improvements on all curb and gutter, sidewalks, drive approaches, curb ramps and roadway paving. Essentially the existing roadway was lowered in elevation to provide a new 48-inch storm drain system (main and laterals), and 90 catch basins to eliminate the history of flooding within the affected neighborhood community. The project also included the relocation of water main and laterals and an existing 8-inch PVC sewer main, as well as 4-inch PVC sewer laterals. Coordination involved the City of Westminster, three separate water companies, OCSD, OC Survey, and the OCPW Public Information Officer. Robert attended the pre-construction community meeting which was held prior to the project. Robert additionally ensured that all NPDES requirements adhered to the project SWPPP Risk Level 1 and that all necessary BMPs were met, and he ensured that all material testing met the minimal test requirements. Traffic Control and phasing was managed to lessen the impact to the residents. Weekly meetings were held with the contractor and stakeholders (OCSD and Water Companies) to review the critical path and look-ahead schedules, and to review submittals, RFIs, progress payments and potential contract change orders.

SEGUNdA dE SHECHA CANAdA CHANNEL RECONSTRUCTION, orangE CoUnTy Robert served as the construction inspector on the Segunda Deshecha Canada Channel Reconstruction Project for the County of Orange. Robert was tasked with overseeing the demolition of 5 miles of the existing concrete trapezoidal channel and the construction of an open concrete rectangular channel including 300 feet of reinforced concrete box. The scope of work for this project called for reconnecting all existing inlets including structural and unclassified fill, crushed aggregate base maintenance road, rolled compacted concrete for slope stabilization, shoring for adjacent private property adjacent to removals, concrete ramps and steps for access, installation of breakaway trash boom debris liners, new fence and gates, and compliance with project SWPPP and BMPs, along with diversion per the State of California De Minimus permit. Robert additionally handled all of the project documentation including inspection daily logs, weekly statement of working days, project photographs (pre construction, during and post construction), submittal and RFI review and response, and backup for payments. The cost of this project was approximately $6 million.

O’NEILL REGIONAL PARk PAVEMENT REHAbI LITATION, orangE C oUnTy Robert served as the Construction Manager on the $1.1 million O’Neill Regional Park Pavement Rehabilitation Project for the County of Orange. This project utilized asphalt rubber hot mix for the remedial repair of curb ramps in order to meet ADA compliance, along with the reinforcement of fabric (glass pave), traffic control, phasing, wheel stops and striping and SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 76 288
stenciling. Robert assisted in coordination with the O’Neill Park Rangers and Park Vendors regarding the project phasing in order to minimize any inconveniences to the public park users. Robert also verified NPDES compliance utilizing proper BMPs, and implemented safety plans regarding work adjacent to park users, along with verifying that all compaction of subgrade, aggregate base, and asphalt concrete met the relative compaction minimum percentage requirements.

SAN jO AQUIN CHANNEL RESTORATION PRO jE CT, orangE C oUnTy Robert provided Construction Management services on the $1.9 million dollar San Joaquin Channel Restoration Project. The project goal was for the construction of the restore earthen channel line and to grade it to the original as-built conditions including water diversion and to meet the compliance for regulatory agencies permits and the State of California De Minimus Permit. Further work included re-establishing depleted rip rap lined sections of slopes; reconstruct structure concrete and reinforcing bars for inlets into the channel. Coordination with the City of Irvine relating to egress and ingress through the City Park was needed. In addition to that, Robert also participated in a neighborhood outreach to inform residents of the upcoming project, and he verified that all compaction of unclassified fill met the relative compaction minimum percentage requirements.

EAST bL UFF EROSION STORM dR AIN REPAIR PROjE CT, orangE CoUnTy Robert was the Construction Manager on the East Bluff Erosion Storm Drain Repair Project. The project detailed the removal and replacement of a 48-inch RCP storm drain from the top of East Bluff in Newport Beach to the bottom of the slope at Back Bay Road. Further tasks involved the construction of two new manholes and a vegetated mitigation site with an establishment and maintenance period. Robert participated in coordinating with OC Parks (land owner) and the City of Newport Beach (storm drain maintenance) throughout construction, which included submitting all project documentation to the City for acceptance. Robert also verified compliance with the project SWPPP which included all necessary reports, implementation and maintenance of all BMPs to prevent erosion and sediment loss into Back Bay, and he verified that all compaction of unclassified fill met the relative compaction minimum percentage requirements.

GILbE RT RETAR dI NG bA SIN REHAbI LITATION, orangE CoUnTy Robert served as Construction Manager on the Gilbert Retarding Basin Rehabilitation Project for the complete restoration of existing rip rap lined basin per the Standard Plans. The project set out to remove undersized existing rock cover and to excavate in order to place new rip rap per the Standard Plans, as well as re-establishing the line and grade. Compliance with regulatory agencies was also required, as Robert verified that all necessary NPDES BMPs were installed and maintained, and he also coordinated with the adjacent golf course for egress and ingress of the work area, along with the repair of existing chain link fencing.

SUNSET CHANNEL SLOPE REPAIR, orangE CoUnTy
Robert served as the Construction Manager on the $2.3 million dollar Sunset Channel Sope Repair Project. The work called for the construction of the complete restoration of earthen channel to re-establish as-built line and grades including gabion and rip rap slope protection, water diversion and compliance with regulatory agencies, permits and the State of California De Minimus Permit. The project also called for coordination with the City of Huntington Beach for traffic control on City streets for egress and ingress to channel. Robert verified that all necessary NPDES BMPs were installed and maintained, along with all compaction of unclassified fill meeting the relative compaction minimum percentage requirements. Robert also addressed tidal influence from downstream by implementing cofferdams to prevent ocean water from entering the channel.

CROwN V ALLEY ASPHALT OVERLAY/ARTERIAL STREET IMPROVEMENT, mI SSI on vIEJo Robert was the Construction Manager for the Crown Valley Parkway Asphalt Averlay and Arterial Street Improvements Project for the City of Mission Viejo. The work required on this major arterial highway required remedial repair of deteriorated pavement sections, curb & gutter, sidewalks, curb ramps for ADA compliance, traffic control (arterial), detour plans, NPDES compliance, utility adjustments of manholes and valves, and striping and stenciling. Robert lead the coordination with local schools, City of Mission Viejo and Ladera Civic Committee for phasing of the work to minimize inconvenience to the public residents. A portion of the work was within the City’s right of way, requiring City permits. Robert established that all compaction of subgrade, aggregate base, and asphalt concrete met the relative compaction minimum percentage requirements.

SANTIAGO CANYON ROAd wA Y IMPROVEMENTS PROjE CT, lakE forEST On the Santiago Canyon Roadway Improvements Project for the City of Lake Forest, Robert served as Construction Inspector in charge of the cold milling and asphalt concrete overlay of Santiago Canyon Road (5 miles) including striping/ stenciling, traffic control, and over side drains. Coordination with the City of Lake Forest. The project included remedial repair of deteriorated pavement sections. Robert was responsible for all project documentation including Inspection daily logs, weekly statement of working days, project photographs (before, during and post construction), submittal/RFI review and response, and backup for payments. Robert ensured that all NPDES requirements were met, including adherence to the project SWPPP and all necessary BMPs, and to ensure that all material testing met the specifications of the project.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 77 289
Ti mo Th y STa nl Ey
constr Uc tion inspector
32 years of
ex perience
fi elds
of
ex pertise ROADWAY ADA RAMP WIDENING PAVEMENT CALTRANS
QUALiFiCATiONS
CoUrS E w ork: Public Works Inspector, Business Administration & Computer Technology ● Ca l Tr an S CErTi fiEd :

CTm- 375 : AC Pavement In-Place Density, CTm- 201 : Sample Preparation, CTm- 539 : Concrete Sampling, CTm- 533 :

Ball Penetration
bA C kGROUN d
Tim is a Public Works Inspector with 32 years of experience working almost exclusively as a Public Works Inspector for a variety of cities including the cities of Anaheim, La Quinta, Murrieta, Mission Viejo, Fremont, and Hawthorne. Tim’s experience includes projects of all sizes. His accuracy and efficiency in the field ensures a successful and well-documented project, from construction through closeout. Tim’s work will always include making sure that the jobsite is safe and that the contractor is efficient with his time. He has worked on community facilities, and roadway projects including traffic signal, storm drain, sewer and water projects. His experience and familiarity with Caltrans makes him a valuable addition to any Public Works Inspection team.

ExPERIENCE
ARROw HIGHwA Y & LONE HILL AVENUE IMPROVEMENT, San dImaS Tim was the inspector on the City of San Dimas. The project limits included the Arrow Highway and Lone Hill Avenue intersection, Lone Hill Avenue from 500 feet north of Arrow Highway to Cienega Avenue, and Gladstone Street from Monte Vista Avenue to San Dimas Avenue. The scope of work included 2,364 CY of excavation, removing 1,268 LF of concrete curb and gutter, 6,229 SF of concrete sidewalk, and 965 LF of curb, constructing river rock cobble paving in the medians on Arrow Highway, installing 7,299 tons of asphalt concrete pavement, constructing Class II aggregate base, and cement-treated base. Furthermore, the project entailed 10,332 SF of cold-milling to 2-inch depth of asphalt concrete pavement, constructing 8 inches of PCC curb and gutter, 6 inches of PCC curb and gutter, a commercial driveway, 5-foot-wide PCC sidewalk, and 12 curb ramps. In addition, the work involved adjusting the landscape and irrigation system on the medians, installing traffic signals on Arrow Highway at the Lone Hill intersection, removing 5 trees, installing Asphalt Rubber Hot Mix, installing 31 traffic loops, adjusting water and gas valves and manholes to grade, relocating traffic signal pull boxes, and installing a catch basin.

ANTONIO PARk wA Y wIdE NING, orangE
Tim was a second Senior Inspector to the City of Orange. This $25 million project spanned 1.5 miles, from Ladera Ranch to 1,000 feet south of Ortega Highway, and included 1,000 LF of bridgework across San Juan Creek. Antonio Parkway was widened from four to six lanes. The bridge was widened by 40 feet to accommodate the two additional lanes of traffic.

Bridgework included parkway improvements, a raised median, channel bank revetment at the south abutment, compaction grouting, and structural testing. Roadway and bridge widening occurred concurrently and included grading and cement- treated soil, 3,691 LF of RCP storm drain, riprap for environmentally friendly drainage filtering, dry utility installations, 4,993 PVC pipe, utility conduits, 4 fire hydrants, traffic signal improvements and loops, signing and traffic striping, and 448 LF of retaining wall with 42,000 pounds of steel reinforcement.

AdA A CCESSI bI LITY RAMPS, PHASE II (Cd bG F UNdEd), plaCEn TIa Tim provided inspection services on Phase III of the ADA Accessible Ramps Project for the City of Placentia. The project called for removing and constructing sixty-six (66) ADA ramps, 14,000 SF of sidewalk, 1,600 LF of curb and gutter, two drive approaches and removal of 19 parkway trees. It was critical that the ramps be constructed in compliance with current Americans with Disability Act standards and requirements. Furthermore, design services included a site assessment and field gathering data for each ramp location, a design analysis and preparation of the Design Recommendation to achieve ADA compliance, a survey elevation for 20 identified locations, and the preparation of the project specifications. The project required working with the City staff to complete the construction documents on schedule. Moreover, the construction management and inspection phase included employee interviews, reviewing certified payrolls, checking all grades, and keeping the contractor on schedule and within budget for this federally funded CDBG project.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 78 290
SIdEwA L k REPAIR & HANdI CAPT ACCESSIbI LITY AT I-135, Tor ran CE Tim provided inspection services on the Sidewalk Repair for Handicap Accessibility Project for the City of Torrance. This project was CDBG funded and included 79,300 SF of sidewalk removal and construction of a 3 1/2” thick PCC sidewalk over 4” CMB, 5,300 LF of curb and gutter removal and replacement to match existing curb heights and gutter widths, restoration of 1 ft. wide AC pavement, 10,900 SF of driveway replacement and constructing 4” thick PCC driveway over 6” CMB, 180 LF of removing the existing corner radius curb and constructing a new variable height corner PCC curb. The project also entailed the removal of 11,870 SF of cross gutter with curb & gutter and subgrade, 1,900 SF of pavement replacement, furnishing and installing 285 parkway trees, and 310 locations of root pruning. Additionally, the work entailed periphery parkway improvements and 10 detectable warning surface panels at access ramps. Furthermore, the scope of work involved installing a landscaping and irrigation system, removing and replacing water meter utility covers, and pavement markings.

ELM STREET RESURFACING & wA TER LINE REPLACEMENT, Br Ea Tim was a Senior Inspector for the City of Brea. The project’s roadway improvements spanned 4,100 LF and included a 2-inch cold mill, 2.75-inch Type III-B2 base course, and a 2-inch ARHM overlay. The scope also included widening the street to accommodate 5-foot sidewalks, replacing access ramps to meet ADA standards, installing 2 new cross-gutters, repairing 2 additional cross-gutters, and replacing several homeowner driveways. Furthermore, the waterline improvements included abandoning a 6-inch main, connecting 7 side-street water lines to the existing 12-inch water main on Elm Street, installing 42 water valves ranging in size from 8-inch to 12-inch, connecting 62 existing water services to the 12-inch main, and installing 12 new fire hydrant assemblies. This project required heavy traffic control and coordination with residents.

AdA A CCESSI bI LITY RAMPS, PHASE II (Cd bG F UNdEd), plaCEn TIa Tim provided inspection services on Phase III of the ADA Accessible Ramps Project for the City of Placentia. The project called for removing and constructing sixty-six (66) ADA ramps, 14,000 SF of sidewalk, 1,600 LF of curb and gutter, two drive approaches and removal of 19 parkway trees. It was critical that the ramps be constructed in compliance with current Americans with Disability Act standards and requirements. Furthermore, design services included a site assessment and field gathering data for each ramp location, a design analysis and preparation of the Design Recommendation to achieve ADA compliance, a survey elevation for 20 identified locations, and the preparation of the project specifications. The project required working with the City staff to complete the construction documents on schedule. Moreover, the construction management and inspection phase included employee interviews, reviewing certified payrolls, checking all grades, and keeping the contractor on schedule and within budget for this federally funded CDBG project.

INGLEwO O d AVENUE & FLAGLER LANE RESURFACING, rEd ondo BE aCh Tim provided Construction Inspection services to the City of Redondo Beach on the Inglewood Avenue and Flagler Lane Resurfacing Projects. The project limits are on Inglewood Avenue between Grant Avenue and 190th Street (3,800 linear feet) and on Flagler Lane from 190th Street to Beryl Street (1,060 linear feet) adjacent to the Dominguez Park and Redondo Beach Dog Park. The project includes asphalt and concrete removals, street resurfacing, driveway and alley approaches, cross gutter and spandrel construction, ADA curb ramp construction, utility adjustment, cross gutter replacement, slot paving, signing and striping, tree removal and installation, seal coating, traffic loop detector installation, and other items per plans and specifications.

LA FLORESTA VILLAGE dE VELOPMENT PROjE CT, Br Ea
Tim served as inspector to the City of Brea for the La Floresta Village Development Project. The La Floresta development site encompasses approximately 120 acres, surrounded by Imperial Highway to the south, Valencia Avenue to the west, and Rose Drive to the east. The La Floresta site is a planned multi-use development, which includes single family homes, apartments and commercial properties. The core of the development site incorporated both residential and non-residential components. The residential product types vary, from 5.0 to 8.5 net dwelling units per acre, to 28.5 net dwelling units per acre. The corner of Valencia Avenue and Imperial Highway is designated for mostly non-residential use, although 150 residential units are incorporated into this area. The La Floresta Village has 1,088 residential units, 156,800 SF of mixed use commercial land, and 54 acres devoted to an active adult recreation center for residents. The La Floresta Village is part of a plan to build a community where residents can live, work, shop and play in a “small town” setting that is unique to the heritage and history of the City of Brea. Inspection services included roadway, storm drain, sewer and water installation.

CRENSHAw bO ULEVAR d RECONSTRUCTION PROjE CT, lomI T a T i m w a s t h e S e n i o r I n s p e c t o r t o t h e C i t y o f L o m i t a f o r t h e C r e n s h a w B o u l e v a r d a n d L o m i t a B o u l e v a r d I n t e r s e c t i o n Reconstruction and Lomita Boulevard Resurfacing Project. This project called for approximately 2,325 cubic yards of reconstruct in the intersection of Crenshaw Boulevard and Lomita Boulevard. A small portion of this intersection (west) was within the City of Torrance, so interagency coordination was essential. This project involved resurfacing on Crenshaw Boulevard in both directions, south (approximately 1,056 linear feet) and north (approximately 325 feet), and resurfacing on Lomita Boulevard from the Crenshaw Boulevard intersection east to Narbonne Avenue (around 2,700 feet).

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 79 291
JoE Za marripa
constr Uc tion inspector
30 years of
ex perience
fi elds
of
ex pertise ROADWAY DRAINAGE ADA RAMP RESIDENTS SLURRY SEAL QUALiFiCATiONS
CErTi fi Ed : Public Works Construction Inspector, Santiago Canyon College bA C kGROUN d
Joe is a Public Works Inspector with 30 years of experience in construction as an Inspector. His typical duties have included providing daily construction reports, documenting labor and equipment on-site each day and hours worked; measuring, calculating, and recording all construction quantities, and taking work and site photos. Joe’s experience includes projects of all sizes. His accuracy and efficiency in the field ensures a successful and well-documented project, from construction through closeout. His work includes making sure that the jobsite is safe and that the contractor is efficient with his time.

ExPERIENCE
NEIGHbO RHOO d SLURRY SEAL-AREA 1 PROjE CT-CIP NO, 2019-03, la m Ir ada Joe was the Inspector on this slurry seal project for the City of La Mirada. This project covers several residential streets within the City, including the Foster Park neighborhood and Imperial Highway, Neargrove Road, Jalisco Road, Florita Road, Crestoak Drive, Gara Drive, Ashgrove Drive, Excelsior Drive, Neartree Road, Bluefield Avenue, Stanleaf Drive, Figueras Road, and San Bruno Drive. Construction included Slurry Seal (Type) of the streets and some localized repairs.

COLLECTOR STREET SLURRY SEAL PROjE CT, la m Ir ada
Joe provided Construction Inspection services for the Collector Street Slurry Project (CIP No. 2018-09) . This neighborhood slurry seal project covers collector streets within the City including Biola Avenue, Stage Road, Escalona Road, Foster Road, Adelfa Drive, and Alicante Road. The construction included 1,367 elongated tons of Type II Slurry Seal on collector streets.

LOCAL STREETS REHAbI LITATION PROjE CT, norwalk
Joe served as the primary inspector in this Local Streets Rehabilitation Project for the City of Norwalk to rehabilitate multiple street segments within the City. Twenty-one streets with a total of 3.6 centerline miles were included as part of this project. These limits were within the two blocks of Highdale Street between Elaine Avenue and Ibex Avenue and had a PCI rated less than 25 (very poor). The streets were adjacent to Edmondson Elementary School. The replacement of the deteriorated pavement and accessibility ramps was important to improving the safety of the school zone and extending the useful life of the streets. The rehabilitation work involved street repaving which included curb and gutter repairs, slotted cross gutter replacements and pedestrian accessibility ramps at intersection corners to meet current standards. 55 UNIQUE AdA A CCESS RAMPS dES IGNS, ranCh o C UCa monga Joe provided construction inspection services for the City of Rancho Cucamonga on the 55 Unique ADA Access Ramps Project. This project includes approximately 55 ADA ramps which required custom designs for each ramp. The work on these ramps was completed on an expedited schedule and with short turnaround times.

CALTRANS HIGHwA Y 94 IMPROVEMENT PROjE CT, Sa n d IEg o Joe served as project inspector for the general contractor. The project construction included 3,950 LF of 16 feet high masonry soundwall, 125 LF of cast-in-place concrete barrier, hillside grading, new irrigation, and new landscaping. Joe was responsible for leading weekly safety meetings and the implementation of a safety plan. Special protective measures were put into place concerning Environmentally Sensitive Area (ESA), such as temporary orange fencing to deter workers and equipment from entering restricted area. All underground utilities were marked prior to excavation of soundwall footings and protected in place. Heavy coordination between Caltrans district manager, Caltrans inspectors, and effected residence allowed the project to be completed on time and within budget.

LAGUNA wO OdS bRIdG E REPLACEMENT PROjE CT, lagUn a woodS As the construction inspector, Joe was responsible for directing all phases of the project for the City of Laguna Woods, which included demolition, grading, trenching of footings, concrete formwork, falsework, steel rebar placement, and placing of concrete. A total of 270 cubic yards of concrete was placed. Construction included a 1,295 SF area of rock riprap on the upstream side of the bridge, and re-grading of a flood control channel. A comprehensive traffic control plan was in place which SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 80 292
included detour signs to redirect neighborhood residents. Extra care and consideration was provided to nearby residents considering the project was located within a gated retirement community.

ANNUAL STREET REHAbI LITATION & SLURRY SEAL PROjE CT, Ir v In E Joe served as inspector for the City of Irvine on this $7 .2-million-dollar capital improvement project. The scope of work included removal and replacement of 45 ADA ramps, 2,000 LF of curb and gutter, and 5,400 SF of city sidewalk. Also included in the project scope was grind and overlay, Type I and Type II RAP Slurry seal, adjusting 110 manholes and 464 valves, and installation of 50 traffic loops. Intensive traffic control along Barranca Parkway was necessary due to crossing intersections during grind and overlay operations. Due to the nature of this project, it was necessary to actively respond to all resident questions and addressed needs to the community and City.

COTTONwO O d EL EMENTARY SCHOOL AdA SwI TCHbA Ck R AMP PROjE CT, agUa nga Joe served as the inspector for this switchback ramp project. His responsibilities included layout of trenching for masonry retaining walls, grading, steel rebar placement, forming and placement of concrete ramps, landings, and ADA steps. Joe inspected all of the work to ensure it was performed according to the proejct plans and specifications. The project included 220 LF of 6 feet wide ADA switchback ramp, 4 sets of 8 foot wide concrete ADA compliant steps, and 560 LF of masonry retaining wall. Joe had weekly meetings with school district construction manager and school principal to coordinate material deliveries and operation of heavy equipment to ensure the safety of students and faculty, as school was in session during construction
ORANGE TERRACE COMMUNITY PARk PROjE CT, rI v ErS I dE
Joe was the inspector on the Orange Terrace Community Park Project in the City of Riverside. The scope of the project included 275 LF cast-in-place concrete retaining walls, sidewalks, 7 ADA ramps, 4-sets of concrete bleachers, 2 adult-sized baseball diamonds, 2 soccer fields, 2 playground areas with rubberized surface, and 2 parking lots. Joe inspected all work to ensure it was performed according to the project plans and specifications. Regular meetings with City of Riverside Public Works Project Manager and Publics Works Inspectors contributed to the success of this project. Heavy supervision was required to guarantee successful completion of the project and ensure resident satisfaction throughout the construction phase.

PAd k AT THE MAR k ET PLACE SITE wO R k PROjE CT, Ir v In E Joe was the construction inspector in charge of the Pad K at the Market Place Site Work Project for the City of Irvine involving grading, layout, forming, and placing of concrete. The project scope included 420 LF of curb and gutter, 620 LF of 6 feet wide ADA path of travel sidewalk, and 7 ADA ramps with truncated domes. A total of 130 cubic yards of concrete was placed. Joe was responsible for inspecting all work to ensure compliance with the project plans, specs, and ADA requirements prior to placement of the concrete. Coordinating with asphalt contractor and with the striping company was essential to ensure compliance in all ADA parking spaces and paths of travel throughout the parking lot.

PAd k AT THE MAR k ETPLACE CONCRETE FOUNdA TION (NEw bU ILdI NG), Ir v In E Joe was the construction inspector on the Pad K at the Marketplace Concrete Foundation (New Building) Project for the City of Irvine. Joe was responsible for grading, layout, steel rebar placement, and placement of concrete. Coordination with the General Contractor on issues regarding survey staking, layout, RFI’s, scheduling of underground excavations, plumbing, electrical, and erection of steel columns was essential. The project also included over-excavation or native soil at a depth of 5 feet, along with recompacting 15,600 SF of building pad.

PHASE 3 LOCAL STREETS REHAbI LITATION (zO NE 24, 27, & 32), norwalk Joe served as the construction inspector to the City of Norwalk on the 3rd Stage of Construction of the Local Streets Rehabilitation Paving Improvements. The work included three separate City projects (No. 7924-Zone 24. No. 7925-Zone 25, and No. 7926-Zone 32). Stage 1 of this project included concrete improvements, and OE provided CM and Inspection services for Zone 32 of that phase. Stage 3 included a variety of pavement rehabilitation methods including full-depth repair, grind and overlay, and slurry seal for Zones 24, 27, and 32. Twenty-one streets with a total of 3.6 centerline miles were included as part of this project. These limits were within the two blocks of Highdale Street between Elaine Avenue and Ibex Avenue which had a PCI rated less than 25 (very poor). The streets were also adjacent to Edmondson Elementary School, requiring careful coordination with the school. The replacement of the deteriorated pavement and accessibility ramps was important to improving the safety of the school zone and extending the useful life of the streets. The rehabilitation work involved street repaving which included curb and gutter repairs, slotted cross gutter replacements and pedestrian accessibility ramps at intersection corners to meet current standards.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 81 293
Jo rg E r oq U E
constr Uc tion inspector
44 years of
ex perience
fi elds
of
ex pertise ROADWAY TRAFFIC ADA RAMP RESIDENTS PAVEMENT
QUALiFiCATiONS
BS: Civil Engineering, Instituto Tecnologico Centro Americano, El Salvador

bA C kGROUN d
Jorge Roque has more than 44 years of experience in overseeing the design and engineering of street and highway improvement projects. As a Public Works Associate, he has managed Capital Improvement Projects for 14 years. In this time, Jorge supervised inspectors and managed project progress to ensure compliance with project quality assurance procedures. He prepared plans and specification for street and infrastructure improvements according to Public Works Standards. As a Permit Department Manager, Jorge performed work, calculating fees, and establishing permit conditions according to scope of work. Jorge additionally performed plan checking and reviews involving plans for street improvements, water main and sewer improvements, along with grading, calculated checks on grading, infrastructure, and roadway improvements projects.

ExPERIENCE
RESIdE NTIAL STORM dR AIN & SEwE R LINE INSTALLATION, monTEBEll o Jorge served as the construction inspector for the City of Montebello on the Storm Drain and Sewer Line Installation Project.

The project involved constructing 5,000 LF of sewer line and manholes along with 4,500 LF of 48” diameter corrugated storm drain pipe, 22 catch basins, and head walls for inlets and outlets with grouted 1 2” diameter rip rap rocks. This project was a part of a 1,200 residential unit (600 acres) construction effort within the City of Montebello in Montebello Hills, located east of Montebello Boulevard, from Michael Collins to San Gabriel Boulevard. In addition to verifying on-site safety, Jorge also observed and documented all aspects of the construction, including conducting inspections on required trench layout work, material allocation, pipe bedding, pipe laying, shoring, catch basins and pipes inverts that were also closely verified by the Surveyor.

CARLIN AVE. & LONG bE ACH bL Vd. wA TER MAIN UPGRAdE P ROjE CT, lynwood Jorge served as the Project Manager and coordinated the inspection for the maintenance of the City Water Distribution System in the City of Lynwood where frequent water ruptures occur in the area. Plans and specifications were prepared for Long Beach Boulevard from Carlin Avenue to Josephine and Carlin Avenue from Bullis Road to Bradfield Avenue. Similar project were done Citywide. The project consisted of replacing an existing 6” diameter asbestos cement pipe and constructing 4,700 lineal feet of a 6” diameter PVC-C900, along with installing 80-gate valves over existing 22-gate valves, and 16 fire hydrants.

Potholing was conducted in order to expose utilities in conflict with the installation of the new line. Jorge was in charge of approving the new lay out and proceeded with the saw cutting for excavation, shoring, preparation of bedding and laying new pipe with new fittings including gate valves and fire hydrants and water services. Following that, the 6” sand bedding and 12”sand on top of pipe was compacted by jetting it. After complying with the hydrostatic test (design pressure +50), the Contractor backfilled and repaired the trench and proceeded with the disinfection test and completed the project.

MONTEbELLO bLVd. bIkE LANE & SIdEwALk IMPROVEMENT, monTEBEllo Jorge served as construction inspector on the Montebello Boulevard Bike Lane and Sidewalk Improvement Project for the City of Montebello. The project limits were approximate 1.3 miles, from Lincoln Avenue to Paramount Boulevard. Jefferson Avenue to Paramount Boulevard involved street widening which included adding a bike lane that required an excavation of approximately 8,000 cubic yards of dirt and the construction of 750 LF of a 5-ft. high retaining wall along the easterly s i d e a t t h e C o s t c o W a y i n t e r s e c t i o n . T h i s a l s o i n v o v l e d t h e c o n s t r u c t i o n o f 2 , 5 0 0 L F o f 1 2 - i n c h d i a m e t e r C 9 0 0 P V C f o r reclaimed water, the construction of 6,000 LF of curb and gutter, 12,000 LF of a new raised median curb, 40, 000 square feet of sidewalk, along with upgrading 25 curb ramps for ADA compliance. A raised median was also installed, with a decorative river-rock dry stream as part of the percolation and storm water infiltration system at 22 locations, 18-in. wide decorative decomposed granite along the perimeter of medians with planting and drip irrigation system. Approximately 150 of 24” box trees were planted, along with 3,700 1-gallon trees and 5,500 SF of ground covers were also planted. Bus shelters were installed at two locations, and a reclaimed water line was constructed from Lincoln Avenue to Jefferson Avenue along with infrastructure, water line, gas line and streetlights relocations due to the street widening. Overall, approximately 500,000 SF of grind and overlay were ground and 10,000 tons of AC were installed. All of the surveying monuments were re-installed and recorded at the Los Angeles County surveying Department after paving.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 82 294
wASHINGTON bLVd. STREET IMPROVEMENT, wEST TO EAST CITY LIMIT-PHASE II, monTEBEllo
Jorge served as the inspector for this major arterial roadway improvement and pavement rehabilitation of Washington Boulevard, from the east City limit to the west City limit in the City of Montebello. The project had pavement rehabilitation, new landscaped median islands, a City monument sign, bus pads, ADA improvements, sidewalk and curb and gutter.

A l s o r oad w a y sa f e ty i mpr o v e me n t s and s i g n i ng and st r i p i ng . A p a v e me n t ana l y s i s w a s c onduct ed , a l ong w i t h a l t e r na t e rehabilitation strategies which included a budget analysis to complete as much of the street improvements as the fixed project budget would allow. Jorge was responsible for Notice-to-Proceed issuance, review of change orders and progress payments, as well as overseeing compliance with the project’s plans and specifications, along with compliance with the City’s requirements and ordinances (hours of work, noise ordinance, etc.). Jorge also oversaw the general performance of the Contractor, provided daily inspection reports and clearly identified the daily activities, work accomplished, number of employees and equipment on the job, and issues and concerns.

CORAk STREET STORM dRAIN PROjECT, BaldwIn park
Jorge served as construction inspector for the City of Baldwin Park involving installing 2,000 linear feet of 36” concrete storm drain line, 4 catch basins, various junction structures, the rehabilitation of roadway, construction of open channel drainage easements, and removal and replacement of private property structures, along with various ADA improvements.

Jorge was responsible for onsite construction management and contract administration, including review of change orders and progress payments as well overseeing compliance with the project plans and specifications, and verifying compliance with the City’s requirements and ordinances (hours of work, noise ordinance, etc.) along with verifying the general performance of the contractor. Jorge additionally provided daily inspection reports, which clearly identified daily activities, work accomplished, number of employees and equipment on the job, and issues and concerns during the project.

SEwER UPGRAdE ANd CITY-wIdE STREET IMPROVEMENT PROjECT, El monTE Jorge was tasked for construction inspection support for the City of El Monte on the Sewer Upgrade and Citywide Street Improvement Project. This project included 800 lineal feet of sewer line that were installed, which required sewer bypass during construction. The project work also called for utility covers adjustments, traffic striping, pavement marking, curb painting, the removal and replacement of broken sidewalk and driveways, the reconstruction of curb and gutters, upgrading curb ramps to meet ADA compliance, cross gutters removal and replacement, asphalt cold milling 2-inch-deep asphalt and installing 2 inches of asphalt. Jorge coordinated with the residents, along with the Contractor and the City on the progress and activities of the project, verified compliance with the plans, provided oversite of the Contractors safety program, monitored traffic control procedures, provided daily inspection reports and weekly statements and progress memos, reviewed payroll data, prepared stop work notices when needed, calculated bid quantities to actual work performed, maintained a digital photo log, and he provided close-out documents and punch-list work to be performed. bLUFF ROAd IMPROVEMENT PROjECT, monTEBEllo
Jorge provided construction inspection services to the City of Montebello on the Bluff Road Improvement Project. The project limits were from Sycamore Street to Oakwood Street. Jorge inspected compliance with the plans and specifications of the contract, oversaw traffic control, and provided daily log and inspection report entries, including pictures of the project. Jorge also reviewed and reported contractor claims, prepared weekly update reports, reviewed the contractor’s invoices, verified completed work, and approved all quantities. This project included the removal and replacement of broken concrete sidewalk, reconstruction of curb and gutters, an upgrade of 6 curb ramps to comply with ADA requirements, the removal and replacement of 100 LF of metal beam guard railing, dig outs on asphalt cold milling of existing 2-in.-deep asphalt and installing 2 inches of asphalt where approximately 1,100 tons of asphalt were being installed. The project also included the adjustment of utility covers, traffic striping, pavement markings and curb painting.

ELLINGbROOk dRIVE IMPROVEMENT PROjECT, monTEBEllo
Jorge provided inspection services to the City of Montebello from Firvale Avenue to the easterly end of the cul de sac.

Jorge provided compliance with the PS&E, along with overseeing traffic control, and provided daily log and inspection report entries, including pictures of the project. Jorge also reviewed and reported contractor claims, prepared weekly update reports, reviewed contractor’s invoices, verified completed work, and approved all quantities allocated. This project included the removal and replacement of broken 3,500 SF of sidewalk, removal and replacement of 900 SF of driveways, reconstruction of 220 LF of curb and gutters, upgrading 12 curb ramps to comply with ADA requirements, 84,000 SF of asphalt, cold milling 2-in.-deep asphalt and installing 2 inches of asphalt where approximate 1,250 tons of asphalt were installed. Jorge also oversaw the adjusting of utility covers, traffic striping, pavement markings & curb painting. 40 RESIdENTIAL UNITS IMPROVEMENT PROjECT, IrwIndalE
Jorge Served the City of Irwindale as the Public Works construction inspector involving 40 residential units to include 2300 LF of 8” VCP with manhole and sewer lateral improvements, approximately 700 LF of 18” RCP with 6 catch basins and laterals, curb and gutter, sidewalk, lots grading and compaction and roadway construction.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 83 295
kEvIn gr EEn
constr Uc tion I n spector
13 years of
ex perience
fi elds
of
ex pertise ROADWAY TRAFFIC ADA RAMP RESIDENTS PAVEMENT
QUALiFiCATiONS
BS: Psychology/Sociology/Business, La Sierra University ● Sw ppp CErTi fiEd : Stormwater Pollution Prevention Plan Developer ● CErTi fi Ed : Radiation Safety ● oSh a Tr aining: 10 & 30 MSHA & Nuclear Gauge/Rapid Set Concrete/ Trenching & Shoring Safety/Confined Workspace/Asbestos Awareness ● qSp /q Sd : 40 Hour Training Certification bA C kGROUN d
Kevin Green has accumulated over 13 years of experience in performing both construction inspection and construction management services on highway and public works construction projects for the interest of both state and local agencies.

His work experience over those years includes performing constructability reviews, field inspection, materials testing, documents control, and site management. The work involved on these projects required extensive roadway and highway construction and rehabilitation, emergency roadway repair and local street rehabilitations that encompassed earthwork, Jointed Plane Concrete and Rapid Set Concrete and Hot Mix Asphalt and Alternative Rubberized Asphalt Membrane paving and Cold foam-in-place recycle paving, barrier rail, concrete and electrical work, directional drilling, Cast-in-Drilled Hole for overhead sign foundations, pile driving, materials testing, and SWPPP/WPC and COZEP compliance. Further work that required both Kevin’s inspection review and management oversight include electrical, controllers, pull boxes, ramp meters, traffic signals, crosswalk push buttons and signals, ETTM systems, traffic loops, camera systems, hot mix asphalt, jointed plane/rapid strength/set concrete paving, median concrete barrier, electrical, striping, traffic control and construction liaison to the Caltrans Chief Public Information Officer. Kevin brings to the table a thorough knowledge of The Caltrans Standard Plans, Specifications and Construction Manual and of construction oversight.

ExPERIENCE
SANTA ANITA ACTIVE TRANSPORTATION CYCLE 5, El mon TE
Kevin is providing Construction Inspection services for the City of El Monte. The purpose of this project was to improve safety for roadway users and to improve conditions for non-motorized modes of travel, thereby promoting pedestrian cycle and transit use. In doing so, the intent was to improve neighborhood connectivity and livability, and to enhance the comfort of non-motorized users traveling to and from the El Monte Transit Center and Downtown El Monte. The work entailed roadway rehabilitation, parkway improvements-involving 51 ADA curb ramps, 4,000 square feet of sidewalk, 200 linear feet of curb and gutter-and upgrades to video detection and traffic signals at 7 intersections, along with wayfinding sign and bike rack installation at various intersections. The project was split into 3 phases. Phase I involved class II bike lane installation for 0.53 mile at Santa Anita Avenue, from Tyler Avenue to Lower Azusa Road; Phase II had pavement, curb and ramp upgrades at Tyler Avenue, from Ramona Boulevard to Santa Anita Boulevard for .97 mile; and Phase III entailed pavement, curb and ramp upgrades located at Ramona Boulevard, from Santa Anita Avenue to Tyler Avenue for .36 mile.

LACMTA - METRO GOLd LINE FOOTHILL ExT ENSION PHASE 2A, orangE C oUnTy Kevin provided Construction Inspection services on the LACMTA - Metro Gold Line Foothill Extension Phase 2A Project. The Metro Gold Line Foothill Extension Construction Authority (Construction Authority), was created in 1998 as an independent agency by the California State Legislature to specifically address the planning, designing and construction of the Los Angeles County Metropolitan Transportation Authority (LACMTA) Gold Line, from Los Angeles to Pasadena. Since then, further extensions have been planned with the ultimate goal of reaching Ontario Airport in 2019. The purpose of the project was to address a 11.5 mile segment from Pasadena to Azusa by way of an extension of the Gold Line that would occupy a portion of previously abandoned Burlington Northern Santa Fe Railway (BNSF) trackage now owned and operated by Southern California Regional Rail Authority (SCRRA). Within the project limits of Phase 2A were six at-grade crossings with movement on freight and light rail tracks. Each of these crossings improved Automatic Highway Warning Systems (AHWS) to further enhance the safety of the public. The implemented design also improved upon the existing Automatic Block System present today. Project Highlights included interfacing of freight and light rail crossing systems, meeting railroad signal standards, freight crossing and wayside signal design, technical specifications per SCRRA standards, construction phasing plans, program development, in-service testing of freight signal system, and full signal system “as-built” drawings. Kevin was tasked with the responsibility in providing concrete inspections on concrete mix designs, the Quality Control plans, and to verify a variety of sampling to meet the requirements of ACI. This project lasted for approximately a three year period.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 84 296
I-710 & HObA RT YAR d bRIdG E PAVEMENT REHAbI LITATION & wIdE NING, orangE C oUnTy Kevin served as the Construction Inspector on the I-710 Freeway and Hobart Yard Bridge Pavement Rehabilitation and Widening Project. The project spanned a 3.5 mile stretch of I-710 through the City of Commerce, City of Vernon, City of Bell, and the unincorporated area of East Los Angeles, from Slauson Avenue to Route 60. The project also included concrete pavement rehabilitation and jointed plain concrete pavement(JPCP-RS) and continuously reinforced concrete pavement(CRCP-RS), as well as bridge approach slab repairs on several bridges along the corridor. All northbound lanes between Bandini Boulevard and the I-5/I-710 Interchange were replaced with JPCP-RS. The median shoulders were repaved with JPCP-RS, and the median barrier was upgraded to meet current standards. The project further included installing new overhead sign structures and changeable message sign, and upgrades to drainage. A significant scope element of the project was the widening of the Hobart Yard Bridge in both directions for 1,300 LF over 18 sets of railroad tracks. Additionally, existing barriers and overhangs were demolished and the bridge widening was constructed at six other locations. Work included installation of girders, forming, and pouring of diaphragm and backwalls and deck construction. The purpose of the project was to widen and rehabilitate the north and southbound lanes of Route 710 in seven stages. The project was completed 18 months ahead of schedule thanks to innovative solutions as a result of collaborative partnering. To achieve this, Kevin and the team relied on open and transparent communication and partnering strategies focused on delivering ideas from each team member. Advanced planning efforts also re-sequenced project staging to complete construction within 61% of the contracted schedule window with no claims or disputes. For his tasks at hand, Kevin monitored the removal of curbs and gutters and the grading of the I-710 freeway bridges, along with overseeing the construction of MSE walls, retaining walls, backfill asphalt paving, concrete, storm drain installation and vaults. The project was completed with no lost time incidents in a period of almost 2 years
I-22 & I-57 FREEwA Y OVERPASS RETROFIT PROjE CT, orangE C oUnTy Kevin provided Construction Inspection services to the County of Orange on the I-22 Freeway and I-57 Freeway Overpass Retrofit Project. His required tasks included overseeing the testing and sampling of concrete during the placement for footing columns, along with verifying the placement of reinforcing steel. Upon the time of the final inspections, Kevin maintained communication and coordination with Caltrans and the project-assigned consultants. This project spanned a period of approximately 3 years.

I-405 CIVIL ROAd wA Y & ELECTRICAL CONSTRUCTION, orangE C oUnTy Kevin performed as the Lead Construction Inspector on the I-405 Civil Roadway and Electrical Construction Project for the County of Orange. His assigned duties included supervising four construction inspectors and two technical analysts in the midst of having to perform concrete inspection services and also while overseeing the removal of curbs and gutters, the grading of freeway bridges, MSE walls, retaining walls, backfill, HMA paving, concrete, and storm drains and vaults for this job. This fast-paced project continued on for a 3-year period.

I-91 FREEwA Y STATE ROUTE PROjE CT, orangE C oUnTy
Kevin served the County of Orange as construction inspector on the I-91 Freeway State Route Project where he performed concrete inspection services for this job. This 3-year long project consisted of 32 cast in place and retrofit bridges, MSE walls, and retaining and sound walls. Kevin performed coordination with Caltrans along with their consultants in completing the final inspections.

RIALTO CEMETARY PROjE CT, rI alTo
Kevin provided construction inspection services to the City of Rialto on the Rialto Cemetary Project. The purpose of the project was to perform value engineering on a catch basin, drain line, and curb and gutters to improve drainage for the project, and adding additional sidewalk repairs for ADA compliance. Time was spent for the preparation, administration, inspection, and negotiation for Change Orders #01 and #02. Further services provided included engineering support, and negotiating with the Contractor for a fair cost and to bring value for the City to amend deficiencies noted during construction without impacting the overall construction schedule and to achieve cost savings for the City. 2022 RESIdE NTIAL SLURRY SEAL PROjE CT, EaS T v al E
Kevin provided construction inspection services on this 2022 Residential Slurry Seal project in the City of Eastvale, which entailed slurry seal in 12 zones within the City (Areas A-L). The project construction involved a whopping 3.9 million SF of Type II Slurry, crack sealing, and various striping.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 85 297
Ji m pri Zio ,
constrUc tion inspector 30
years of
ex perience
fields of
expertise

BUILDING ROADWAY PAVEMENT BRIDGE
bA C kGROUN d
Over the past 30 years Jim has developed a swath of industry strengths and acquired knowledge in his role as a Superintendent for general contractors. In working for both Los Angeles and Orange Counties, and alongside the Inland Empire, Jim has gained a wealth of understanding for City approved plans and standards. Jim’s experience involved fulfilling public works construction requirements such as verifying SWPPP compliance, verifying traffic control plans, monitoring for safety compliance involving both the public and for the workers, and supervising the installation of offsite and onsite wet and dry utilities. Jim excelled in his role as supervisor, having worked within City Public Works departments where he developed knowledge and understanding of City codes, enforcements, and City safety-related issues. Jim further supervised projects with miscellaneous street work and utility tie-ins. Cities that have retained Jim for use of his skills include San Clemente, Santa Ana, Anaheim, Orange and Costa Mesa.

ExPERIENCE
CASMALIA STREET IMPROVEMENTS, rI alTo
Jim was the Project Supervisor for the City of Rialto on the Casmalia Street Improvements Project. The project was located at and around the cross streets of Casmalia and Linden. His supervisor duties revolved around installing new signal loops and new ADA compliant curb ramps, work on RCP pipe installations with complete catch basin and a sewer that tied into the street. There were also water pipe tie-ins for hydrants, fire services, and domestic and irrigation elements with back flow devices, along with gutter, three driveway approaches and City sidewalks. For Rule 20 work, new streetlights, including foundations and conduits, were installed. This resulted in the required repair of asphalt trenchs, slot patchs and grind and overlay.

PANATTONI dE VELOPMENT PROjE CT, onTa r Io
Jim was the Project Supervisor on the Panattoni Development Project in Ontario. The project involved the development of three buildings totaling 380,000 square feet, 2,600 LN feet of 12” CMLC pipeline with 3 fire services, 10 hydrants, domestic water taps, and 1,400 LN feet of RCP with complete catch basins and head wall reconfiguration at Day Creek Chanel. This also included 800 LN feet of bio swale, along with three commercial drive approaches, slot patches, grind and overlay.

PANATTONI dE VELOPMENT PROjE CT, Ir v In E
As the Project Superintendent, Jim oversaw the construction of 3 drive approaches, the modification of 200 City LN feet of sidewalk, and street storm drain and sewer tie-ins on the Panattoni Development Project for the City of Irvine. All onsite wet and dry utilities were established for 8 buildings. Jim oversaw all of the new construction.

VOIT dE VELOPMENT PRO jE CT, TUSTIn
Jim supervised the 2,000 LN Feet of 12” water service, 10 fire services, 12 fire hydrants and domestic water taps for the City of Tustin. The project entailed a 500 foot-long cul-de-sac street with 4 drivway approaches, City sidewalk, water services and streetlights. The project work involved a water pipe bore leading underneath a railroad track siding with a complete loop system which required the removal of Santa Ana water to property sewer tie-into the OC sanitation Redhill relive 24 inch pipeline that included a rechanneled manhole base.

VOIT dE VELOPMENT PRO jE CT, Br Ea
As the Project Supervisor on this job, Jim supervised the construction of 4 drive approaches and 1,000 feet of new sidewalks. This also included slot patch grind and overlay, and landscape and irrigation at edge of the new sidewalk.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 86 298
mark lUE ra
constr Uc tion inspector
16 years of
ex perience
fi elds
of
ex pertise ROADWAY ADA RAMP RESIDENTS BIKE TRAIL PAVEMENT QUALiFiCATiONS
CoUrS E w ork: Public Works Plan Interpretation & Estimating, Citrus College ● rEgUl a Ti onS & Co dE S: City of Orange, City of Chino, & Multiple Cities & Municipalities bA C kGROUN d
Mark Luera is a public works inspector with over 16 years of experience involving a variety of public works projects. His education at Citrus College involved coursework on Public Works Plan Interpretation and Estimations which entailed plans and estimate time interpretation alongside public works material, labor and equipment standards and requirements. He is thoroughly familiar with City of Orange Public Works regulations, codes and process. His experience also includes working for the City of Chino and City of Manhattan Beach as an Inspector, delivering exceptional multi-tasking capabilities with effective time management techniques. His responsibilities involved inspection of roadway, catch basin and storm drain reconstruction and repair, verifying conformity to plans and specifications, retrieving samples, compiling and reviewing materials, labor records, preparing test specimens and assisting and conducting field tests. Mark additional handled the inspection of concrete and asphalt installation, responded to contractor submittals, schedules, and requests, and verified compliance of pollution measures for the interest of public safety. Mark concurrently worked in the field permit offices, issuing permits for encroachments within the City right-of-way, where he interacted with the public, developing public outreach experience by answering questions and resolving complaints and providing input for local and public agencies.

ExPERIENCE
LA SEdA P AVEMENT SLURRY SEAL & SCRUb PROjE CT - PHASES I & II, loS angElE S pU B lI C workS
On the La Seda Pavement, Slurry and Scrub Project, Mark served as Construction Inspector for the City of Chino Public Works Department. The primary objective of this project was to preserve 5 miles of residential roads, located at the South San Jose Hills community, bounded by Giano Avenue, City of West Covina, La Seda Road, and Valley Boulevard. The project was constructed in two phases. Phase 1 included pavement, sidewalk and crosswalk, rehabilitation and repair on all concrete related works including the preparation and installation of missing sidewalks. Phase 2 included pavement preservation treatments. Additional project work requirements included cost estimating, Document Preparation, ADA curb ramp repair, signing and striping.

LOTUS AVENUE PAVEMENT PRESERVATION PROjE CT, loS angElE S pU BlI C workS Mark served as Construction Inspector for the City of Chino Public Works Department on the Lotus Avenue Pavement Preservation Project. The goal of the project was to preserve 8.9 miles of residential roads located in the community of East Pasadena bounded by Del Mar Boulevard, Rosemead Boulevard, Huntington Drive, and the Cities of San Marino and Pasadena. The scope included pavement prep-work, parkway improvements, concrete panels along roadways and driveway approaches, and curb ramps upgrades. The proposed construction work involved micro-milling to improve road ride-ability, scrub seal to seal existing cracks, and slurry seal to preserve the pavement and provide a smoother, more finished driving surface. Mark provided project cost estimations, document preparation including environmental study documents, and preliminary design.

PELLISER VILLAGE CONCRETE RESTORATION PROjE CT, loS angElE S pU BlI C workS Mark served as Construction Inspector for the City of Chino Public Works Department on the Pelliser Village Concrete Restoration Project, located at Banducci Road, from Stallion Springs Drive to Pelliser Road. Mark was responsible with overseeing project cost estimations, pavement and striping installation, rehabilitation, repair and improvement, and document preparation. This safety and complete street component project consisted, in general, of paving approximately

1.3 miles of roadway shoulders. The goal of the project was to help alleviate the PM-10 problem in the area, create added safety for motorists and avoid potential accident-risk situations by providing a paved surface that would allow for easier vehicle handling, while also providing additional driving correction roadway and reduce “run off the road” type of accidents.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 87 299
COwA N HEIGHTS PCC & AC REME dI AL REPAIR PROjE CT, orangE pU BlI C workS Mark served as Construction Inspector to the City of Orange on the Cowan Heights PCC and AC Remedial Repair Project.

Project site work was located within a number of Orange City streets, including Brighton Drive, Cowan Heights Drive, Highcliff Drive, Huntsman Road, Kimberwick Drive, La Sierra Place, Overhill Drive, Rangeview Drive, Saddlery Road, and Sirrine Drive. Mark’s inspection services focused on road maintenance project work being performed under The City of Orange Construction’s Job Order Contract. The scope of work for the project included removing existing striping and pavement markings, grinding operations, placement of base materials, asphalt concrete placement, fabrication of structural steel, erection of falsework, placement of concrete, application of a “slurry seal” and re-establishing pavement markings and related work, forms and documentation.

OCEAN VIEw CHANNEL REHAbILITATION, orangE pUBlIC workS
Mark served as Construction Inspector to the City of Orange Public Works Department on The Ocean View Channel Rehabilitation Project. The project required the construction of a 2,200 foot reinforced concrete trapezoidal channel that lined the existing earthen channel. Key tasks that Mark was involved with included inspecting the channel to establish horizontal and vertical control, calculating earthwork quantities for use in conducting earthwork operations and dewatering operations, the installation of steel rebar, the placing of concrete along the walls and invert of the channel, the paving of the access road, the mobilization and demobilization of operations and site preparations. The project was completed on time, within budget, and with acceptable quality control while adhering to all engineer’s safety requirements.

LIbE RTY VILLAGE NEIGH bO RHOOd & MARINE AVENUE PAVEMENT REHAbI LITATION, manhaT T an B EaCh
Mark served as Construction Inspector for the City of Manhattan Beach for the rehabilitation of approximately 20,600 feet of pavement on the Liberty Village Neighborhood and Marine Avenue Pavement Rehabilitation Project. Mark’s inspection work consisted of verifying the cold milling of existing pavement and overlay with rubberized asphalt, AC paving, traffic striping and markings, and traffic loop replacement. In addition, the project involved concrete repair, which including sixty (60) ADA access ramp installations within the Liberty Village and twenty-one (21) along Marine Avenue which also required curb repairs, sidewalk and cross gutter replacements.
wEST P UENTE VALLEY FAIRGROVE AVENUE PAVEMENT RESTORATION, loS angElE S pU B lI C workS
Mark provided Construction Inspection services on the West Puente Valley Fairgrove Avenue Pavement Restoration Project, located at the West Puente Valley community bounded by the City of La Puente, Sunset Avenue, Fairgrove Avenue and Willow Avenue. The goal of the project was to preserve 6 miles of residential roads and included sidewalk, crosswalk and landscape safety rehabilitation and repair, pavement rehabilitation, new ADA curb ramp installation, pavement prep-work and preservation, parkway improvements, curb ramps upgrades, and traffic signal, lighting and signage rehabilitation and repair. The proposed work included micro-milling to improve road ride-ability, scrub seal to seal cracks, and slurry seal to preserve the pavement and provide a smoother, more finished driving surface. 2020-21 RESURFACING PROjE CT, AVENIdA bA R bO SA & bU ENA VISTA ST. FROM AVENIdA bA R bO SA TO CITY LIMITS - P-1026, Ir w Ind al E
Mark served as the Construction Inspector for the City of Irwindale on this grind and overlay project with project limits located at Avenida Barbosa (between Buena Vista Street and Arrow Highway) and Buena Vista (from Avenida Barbosa to the City Limits around Village Road). Construction entails separate bid schedules for the work on Buena Vista Street and Avenida Barbosa (2” grind and overlay with associated striping) as well as an alternate bid for an additional 1” grind and overlay on the Avenida Barbosa project limits. This project had a construction cost of $600,000.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 88 300
rU BE n roCh a, acI
constr Uc tion I n spector
17 years of
ex perience
fi elds
of
ex pertise ROADWAY ADA RAMP LASER SCAN DRONE SURVEY
QUALiFiCATiONS
CErTi fi Ed General Construction Inspector, Traffic Signal Inspector, ADA Curb Ramp Inspector ● CErTi fi Ed Nuclear Gauge ● aC I CE rT IfI Ed: Field Technician Level I Aggregate Testing Lab Technician Level I Trenching & Excavation Awareness ● oSh a CErTi fiEd 40-Hour Hazwoper | 10-Hour Safety Training | Confined Space Safety in Construction ● Ca l Tr an S CErTi fiEd 125: Sampling Highway Materials/Products. | 216 & 231: Relative Compaction, Soils & Aggregates (Nuclear). | 504: Air Content, Freshly Mixed Concrete, & Pressure. | 518: Density of Fresh Concrete. | 523 & 524: Method of Test for Flexural Strength of Concrete & Rapid Set Concrete. | 533:

Ball Penetration in Fresh Portland Cement Concrete. | 539: Sampling Freshly Fixed Concrete. | 540: PCC Cylinder Fabrication. | 552: Method of Test for Relative Compaction of Polymer Concrete w/ Nuclear Gages. | 556 & 557: Slump & Temperature of Freshly Mixed Cement Concrete. ● gEn Er al EdU CaTi on, BUSi n ESS a dminiS Tr aTi on/ managEmEnT Mt. San Jacinto College, Menifee, 2006

bA C kGROUN d
Ruben Rocha has over 17 years of experience as a construction inspector as both a Lead inspector and Materials Inspector and technician, with work relating to large large rail, civil and structural transportation projects. His experience on this work involved interpreting and implementing construction plans, compliance with local, State and Federal regulations, ensuring the quality and functionality of concrete and earthwork for road and bridge structures, and he has performed inspections for ADA compliance, piers, reinforcing steel, pier caps, coping for MSE wall, abutments and decks. Ruben has supervised site activities to procure quality deliverables, on time and within budget, and he has performed routine inspections for compliance with regulatory agencies (Caltrans, FDOT & ODOT) to ensure structures met project specifications. Ruben has been responsible for coordinating material testing and performing field inspections, and overseeing conformance of construction work and materials to generally accepted engineering practices and principles, contract documents, geotechnical (soils) reports, and construction plans and specifications. Ruben works well with complex information and can establish and maintain a cooperative and effective working relationship with construction management teams, clients, and the public.

ExPERIENCE
HAwT HORNE & PCH wA TER MAIN REPLACEMENT PROjE CT, Tor ran CE Ruben served as the Water Main Construction Lead Inspector on the Hawthorne and PCH Water Main Replacement Project for the City of Torrance. The project had an estimated budget of $1 million and lasted from January to August of 2020. Ruben provided inspections for the replacement of existing potable water mains including valves, fire hydrants, and service connections where he was responsible for ensuring all work activities were within compliance with the plans and specifications of the project. He also provided inspection of traffic control, demolition, trench excavation, pipe laying, sidewalk reconstruction, streetlights, and traffic signal systems. In addition, Ruben coordinated with the Contractors, City of Torrance personnel, utility companies, surveyors, and stakeholders, and he documented all activity in daily logs, maintained photo records, and recorded all relevant data such as material quantities to the City’s Project Manager.

ANNUAL wA TER MAIN REPLACEMENT PROjE CT, Sa n Ta monI C a On the Annual Water Main Replacement Project, Ruben served as the Construction Inspector to the City of Santa Monica.

His task was to ensure that the work was within compliance with the project plans and specifications. The project involved replacing existing water mains, and then grinding and capping the roadway with rubberized hot mix asphalt, while complying with the inspection and services per Caltrans requirements. Ruben additionally wrote daily reports and kept proper documentation. The approximate cost was $6 million between May, 2019 and January 2020.

ROUTE 47 GERALd dES MONd bRIdG E REPLACEMENT, long BEaCh Ruben served as construction inspector on the Route 47 Gerald Desmond Bridge Replacement Project for the City of Long Beach. The project purpose was to replace the existing Gerald Desmond Bridge, connecting Route 710 to Terminal Island, in order to provide sufficient roadway capacity to accommodate current and future traffic demand, reduce approach grades, SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 89 301
provide a structurally sound and seismically resistant bridge, and provide vertical clearance that would allow for existing container ships and new-generation vessels currently being constructed to pass through the Back Channel. Rubens tasks involved the review of the construction plans, provide oversight of concrete testing that included procurement of cylinders, slump, and air content field tests, maintain daily inspector reports and material quantity records through out the construction stages, monitor the construction schedule over the course of construction, and verify that all deliveries had accurate tickets and were from approved suppliers. Ruben additionally reviewed the accuracy of the reported concrete and asphalt yields, issued notices to the Contractor , recorded time and materials in case of disputed work, lead discussions with local homeowners to resolve their concerns, reviewed plans for sewer systems and expansions, served as a liaison between the municipal client, engineers, and contractors, examined road and utility repairs completed by the contractor and utility company for compliance with the project plans and specifications, and ensured that building plans, materials, safety procedures, and other variables followed Federal, State, and local City codes.

STREET ENHANCEMENT PROjE CT, hUn TIn g To n park
Ruben provided Lead Construction Inspector services to the City of Huntington Park on the Street Enhancement Project.

The scope of work included construction improvements of damaged, lifted, broken, and raised curbs, gutters, and cross gutters, the removal and replacement of non-compliant ADA pedestrian ramps, adjustment of existing utilities to finish grade, pavement markings and striping and signage, isolated areas of roadway structural section repair, asphalt concrete pavement grinding, and overlay. Ruben coordinated schedules for trade subcontractors to obtain a smooth and adequate workflow. In addition, he conducted ongoing inspections of the work-in-process to ensure that the final product met drawings and specifications. He also reviewed, inspected and approved traffic control systems in accordance with Caltrans and City standards and requirements, and he assisted the Resident Engineer in all aspects of field work for the project including: inspection of construction operations, along with conducting field labor compliance interviews. Ruben provided support with the contract change orders, tracked weekly statements of working days, prepared service contract documents, kept logs for submittals, RFIs, RFCs, and RFQs, review extra work bills submitted by contractors, and more. The project cost was approximately $2.1 million between the periods of October, 2020 to May, 2021.

MId- COAST TROLLY PRO j ECT, San dIEg o
Ruben was the Construction Inspector and Material Tester on the City of San Diego’s Mid-Coast Trolly Project. The Mid- Coast Trolley extended the Blue Line Trolley service from the Santa Fe Depot in Downtown San Diego to the University City community, serving major activity centers such as Old Town, UC San Diego, and Westfield UTC. On this project, Ruben coordinated schedules for trade subcontractors to obtain a smooth and adequate workflow. In addition, he conducted an ongoing inspection of work-in-process to ensure that the final product met drawings and specifications. Ruben also reviewed, inspected and approved traffic control systems in accordance with Caltrans standards and requirements, and he assist the Resident Engineer in all aspects of field work for the project including: inspection of nonstructural construction operations, change order preparation, etc. The project had an approximate cost of $2.1 billion and ran from February, 2018 to May 2019.

SR-58 HINkL EY ROAd wA Y wI d ENING, Sa n BEr nard In o Ruben provided construction inspection services to The California Department of Transportation (CALTRANS) in widening and realigning a portion of State Route 58 (SR-58) from a two-lane highway to a four-lane expressway, extending from 2.4 miles west of Hidden River Road to 0.7 mile east of Lenwood Road, near the Community of Hinkley, in San Bernardino County.

The project proposed access to non-motorized transportation modes (i.e. pedestrian/bikes/equestrian) by providing 6-foot wide sidewalks as well as standard 8-foot shoulders across the two overcrossing bridges at Lenwood and Hinkley Roads.

The expressway included 12-foot standard traveled way lanes, 10-foot standard shoulder widths and a 78-foot-wide median.

Ruben coordinated with contractors and subcontractors to ensure quality compliance, reviewed plans and specifications, and supported construction record-keeping. He also provided on-site monitoring and visual inspection of materials at receipt and installation, as well as coordinated third-party agency testing and sampling activities Two interchanges were constructed on the widened and realigned portion of SR-58 and was constructed as an expressway. One at Hinkley Road, and the other at Lenwood Road. All entrance ramps had two lanes that transitioned to a single lane prior to merging onto the expressway, and all exit ramps had three-way stops at the exit ramp intersections. ADA compliant curb ramps were included.

Lenwood Road involved improvements to accommodate the Burlington Northern Santa Fe (BNSF) rail line. A short length of the existing SR-58 at the east end of the project were realigned to tie in to the Lenwood Road westbound entrance and exit ramps. The expressway was on elevated sections of a roadway, and all retaining walls and bridge structures included aesthetic/architectural treatment to prevent graffiti.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 90 302
mI C haEl ngUy En
constr Uc tion I n spector
33 years of
ex perience
fi elds
of
ex pertise WIDENING BRIDGE ROADWAY ADA RAMP SLURRY SEAL QUALiFiCATiONS
aa dEg r E E: Industrial Technology, California Polytechnic University, Pomona ● 60 Un i T S : Mechanical Engineering, California Polytechnic University, Pomona ● 16 yEa r S: Construction Inspection for the County of Orange bA C kGROUN d
Michael worked for 16 years as a Construction Inspector to a Supervising Construction Inspector for the City of Orange, the highest attainable position in the City’s inspection series (Principal Construction Inspector was converted to Administration Manager I recently). His typical duties include providing daily construction reports, documenting labor and equipment on- site each day and hours worked; measuring, calculating, and recording all construction measurements and quantities, ensuring safety for construction site and NPDES compliance for State/Regional Water Quality Control Boards, and taking work in progress and site photos. While at the City of Orange, he was known as the Slurry King due to his ability to document and track quantities in a precise way.

ExPERIENCE
MId w A Y CITY STREET & STORM dR AIN IMPROVEMENTS, PHASES I & II, orangE C oUnTy Michael served as Supervising Construction Inspector on this $10 million project. The work consisted of street and drainage improvements within the neighborhood of Midway City, included the following streets: Adams Street, Jackson Street, Van Buren Street, Monroe Street, Jefferson Street, Wilson Street, Harper Street, Washington Avenue, Madison Avenue, Roosevelt Avenue, and Hazard Avenue. A portion of the project, Hazard Avenue between Monroe Street and Wilson Street and the north-south alleyway parallel to and adjacent to Beach Boulevard, lies within the City of Westminster. The work included removal of existing facilities, site clearance, grading and reconstruction of roadway pavement, curb and gutters, sidewalk, driveway approaches, curb ramps, catch basins, storm drains, pre-cast RCB, junction structures, and tree replacement. Drainage improvements join the existing Bolsa Avenue storm drain as an interim condition.

NORCO CHANNEL RESTORATION AT LAGUNA NIGUEL REGIONAL PARk, orangE C oUnTy On this $905,491 dollar project, Michael served as the construction inspector at the Laguna Niguel Regional Park’s Norco Channel. The goal of the project was to restore the water quality by reducing bacteria, nutrient and sediment loads.

This effort was achieved by restoring a portion of the channel and wetlands and establishing various riparian plants and shrubs both within and along the banks of the channel to act as a filter and capture sediment and debris, as well as to absorb dissolved minerals and nutrients. The restoration work included clearing and grubbing, water diversion, NPDES BMPs installation, unclassified excavation, chain link fence installation, grouted rip-rap rock revetment, irrigation system, planting of trees and shrubs on channel banks, debris net and posts removal and installation. An additional nine months of maintenance and BMP implemmenation was required. Michael ensured the drafting of change orders, resonded to RFI’s, submitted daily reports, and processed progress payments, among other duties and tasks.

ALTON PARkwA Y ExT ENSION FROM IRVINE bO ULEVAR d TO COMMERCENTRE dRI VE, Ir v InE & lakE forE ST
Michael served as the construction inspector on the Alton Parkway Extension Project, from Irvine Boulevard to Commercentre Drive within the Cities of Irvine and Lake Forest. All improvements along Alton Parkway, Commercentre Drive and Irvine Boulevard within the City of Lake Forest were considered deleteable as they were constructed by the same Prime Consultant/Contractor, Inspector, and Resident Engineer. The work consisted of street and drainage improvements, grading and construction. 5,600 LF of Alton Parkway required the construction of asphalt pavement with aggregate base, curb and gutters, sidewalks, street lights, fencing, driveways, and small animal crossings. Grading consisted of removing unsuitable material, unclassified excavation, and unclassified fill. Drainage Facilities were also included, with RCP , junction structures, water quality facilities, lined and unlined drainage swales, headwalls, and dissipation elements. Intersection improvements and reconstruction were required for both Alton Parkway as well as 1,300 LF of Irvine Boulevard along the eastern roadway section consisting of raised median improvements and general street improvements for widening the northbound lane of Irvine Boulevard, new pavement and overlays, aggregate base, sidewalks, and curb and gutters, landscape restoration, and new traffic signal installation involving signing, striping and traffic control. Deleteable work for 600 LF of Commercentre SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 91 303
Drive was additionally required, consisting of grading, street, and drainage improvements from Alton Parkway to the existing roadway limit of Commercentre Drive. In addition to the roadwork, 1,700 LF of a Wildlife Corridor required the construction of a planted and irrigated earthen corridor with a meandering channel bottom, drop structures, slope reinforcement, fencing, realigning Magazine Road, and a new maintenance road for access to FAA property. The realigned Magazine Road required removal of a portion of existing Magazine Road, and fence removal. The new maintenance road required new pavement and aggregate base shoulder construction. Along with the Wildlife Corridor, the Borrego Wash Channel required grading with the removal of unsuitable material, unclassified excavation, unclassified fill, utility protection, shoring, asphalt, concrete, fencing and utility removals and relocations to facilitate grading operations. The Borrego Wash Channel additionally required constructing a 1, 582 LF cast-in-place, underground reinforced concrete double box structure entrance, reinforced concrete channel with diversion “Splitter” structure for a total channel length of 1,767 LF . The channel also included riprap, road pavement maintenance, aggregate base material, parapet walls, a chain link fence and gates. Lastly, the Irvine Ranch Water District (IRWD) required sanitary sewer, domestic water and reclaimed water facilities, and all fittings and appurtenances installations, testing, phasing and protection of IRWD facilities within the project area. This portion of the project was constructed in accordance to IRWD’s Project Manual. Michael was actively involved with County and consultant Resident Engineers and Inspectors in seeing the work to completion.

EL TORO ROAd ASPHALT OVERLAY & RESURFACING PROjE CT, orangE CoUnTy Michael served as construction inspector on the El Toro Road Asphalt Overlay & Resurfacing Project. The project limits were along El Toro Road, from Glenn Ranch Road to Ridgeline Road, with residential areas located within the project limits. The scope involved remedial asphalt repair work to include hand patching, removal and replacement of the damaged sections of asphalt concrete pavement, cold milling, tree trimming, spray vegetation, placing asphalt concrete level course and overlay, fog sealing new and existing asphalt concrete berms, applying traffic striping and stenciling, placing raised pavement markers, reshaping shoulders, adjusting manholes, water valves, and other utility boxes, surveying monument wells, and the reinstallation of traffic detector loops. Michael aided in the traffic signal operations coordination efforts, which was essential to complete the project, and intensive traffic control on El Toro Road was also necessary while placing concrete overlay. Notices to residents were hand-delivered and no parking signs were posted prior to the start of work. Michael additionally performed daily reports and processed progress payments.

ASPHALT OVERLAY RESURFACING, CHAPMAN AVENUE TO CLIFFwA Y & EQUESTRIAN dR IVE, orangE C oUnTy
Michael served as the Construction Inspector on this project. The asphalt overlay resurfacing consisted of remedial asphalt repair work to include hand patching and removal and replacement of the damaged sections of asphalt concrete pavement, cold milling, tree trimming, placing asphalt concrete level course, placing asphalt concrete overlay, constructing asphalt concrete berm, fog sealing new and existing asphalt concrete berms, applying traffic striping and stenciling, placing raised pavement markers, reshaping shoulders, adjusting manholes, traffic control pull-boxes, and survey monument wells, and the reinstallation of traffic detector loops. Notices to Residents were hand-delivered and no parking signs were posted prior to start of work. Michael coordinated involvement of Traffic Signal Operations, performed daily reports, and processed progress payments with justification backup data.

ASPHALT OVERLAY RESURFACING OF VARIOUS STREETS-PHASES I-IV, orangE CoUnTy Michael served as construction inspector on phases one through four of this project for the asphalt overlay and resurfacing of various roads located in unincorporated portions of Orange County. The scope of work for all of the locations consisted of hand patching and removal and replacement of the damaged sections of asphalt concrete pavement, cold milling, placing asphalt concrete leveling course, pavement fabric and asphalt concrete, CRM Binder, Asphalt Rubber Hot-Mix (ARHM), Tire Modified Asphalt Concrete (TMAC) overlay, constructing asphalt concrete berms, reshaping shoulders, tree trimming, adjusting manholes, water valves, sewer clean-outs, meter boxes, and survey monument wells. The areas in Phase I were located within the Cities of Placentia, Yorba Linda, Rossmoor, Midway City, Anaheim, North Irvine, Aliso Viejo, and the canyon areas. The areas in Phase II were located within the Cities of Anaheim, Cowan Heights, El Modena, Fountain Valley, Fullerton, Midway City and Tustin and additionally involved the reinstallation of traffic detector loops. The areas in Phase III were located within the Cities of Red Hill, Santiago Canyon, and Tustin Foothills. The areas in Phase IV were located within the Cities of Anaheim, Buena Park, El Modena, Garden Grove, Olive Heights, Orange Park Acres, and Yorba Linda and additionally consisted of constructing and retrofitting access ramps and the reinstallation of traffic detector loops. Notices to Residents were hand-delivered and no parking signs were posted prior to start of work. Michael coordinated with local law enforcement for no parking violations within construction zones, performed daily reports, and processed progress payments.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 92 304
mUha mmad a Ta ya, mpa
commUn ity o Utr each 15
years
of
ex perience
fi elds
of
ex pertise
roadway ada ramp pavement signal sewer
QUALiFiCATiONS
BS: Political Science, California State University, Long Beach, 2008 ● mpa: Public Administration, California State University, Long Beach, 2010 ● CErTi fi CaTi on: Construction Management, University of California, Los Angeles, 2010 bA C kGROUN d
Muhammad received his BS in Political Science and Masters in Public Administration from California State University, Long Beach. As the Operations Manager for Onward Engineering, Muhammad is responsible for improving the operational systems, processes, and policies in support of the OE mission, managing and increasing the effectiveness and efficiency of the OE staff, and overseeing and training the OE administrative staff. Additionally, as the head of OE’s Business Development team, Muhammad directs the efforts of the OE proposal writing team and develops marketing programs and campaigns.

Muhammad also provides public outreach services for select high-profile projects. This includes managing communication with businesses, residents, and stakeholders using a multitude of information dissemination methods.

ExPERIENCE
NEIGHbO RHOO d RESIdE NTIAL STREETS IMPROVEMENT - PHASES I & II, anahE I m Muhammad provided Public Outreach for the City of Anaheim on this project which encompassed street improvements on a number of residential neighborhoods. The goal of this project was to restore surface integrity, improve the ride quality and safety of the residential streets, and mitigate any potential trip and fall hazards. These large-scale residential neighborhood rehabilitation projects involved parkway improvements by resurfacing the pavement, removal and replacement of ADA access ramps, sidewalk, curb, cross gutters and concrete aprons, pavement markings, signage and driveway approaches.

The project limits for phase I were split into thirteen neighborhood areas: 1 The Athena-Omega Neighborhood, with a population of 1,977 residents, is bordered by Ball Road to the north, Sunkist Street to the east, Winston Road to the south, and State College Boulevard to the west. The scope involved 191,416 sf of asphalt reconstruction and 63,422 sf of slurry seal; 2 The Biscanye Neighborhood, with a population of 578 residents, is bound by Crestwood Lane to the north, Brookhurst Street to the east, Katella Avenue to the south, and Gilbert Street to the west. The scope included 109,760 sf of asphalt reconstruction and 110,483 sf of slurry seal;
3 T h e D e v o n s h i r e N e i g h b o r h o o d , w i t h a r e s i d e n t i a l p o p u l a t i o n o f 1 , 5 5 1 , i s bound by by Buckingham Street and the Riverside I-91 Freeway to the north, Gilbert Street to the east, and the Santa Ana I-5 Freeway to the south. The scope included 245,498 sf of asphalt reconstruction; 4 The Jerillee Lane neighborhood, with a
population of 1,365 residents, is bordered by the I-91 freeway to the north, Imperial Highway to the east, Santa Ana Canyon Road to the south, and Lakeview Avenue to the west. The scope of work included 312,892 sf of asphalt reconstruction and 63,422 sf of slurry seal;
5 The K ey Lane /W estchester Neighborhood, with a population of 7 , 33 2 residents, is bound by Orange Avenue to the north, Western Avenue to the east, Ball Road to the south, and Knott Avenue to the west. The scope included 933,402 sf of asphalt reconstruction and 664,515 sf of slurry seal; 6 The La R e i na Ne i ghborhood has a population of 3,415 residents and is bordered by Crescent Avenue to the north, Gilbert Street to the east, Lincoln Avenue to the south, and Dale Avenue to the west. The scope included 554,186 sf of asphalt reconstruction; 7 The Rowland
Neighborhood is bordered by Broadway to the north, Magnolia to the east, Rowland to the south, and Kenmore to the west.

The scope of work involved 48,714 sf of asphalt-reconstruction, and pavement resurfacing; 8 The West- Westmont Drive Neighborhood, with a population of 8,426 residents, is bordered by La Palma Avenue to the north, Harbor Boulevard to the east, Lincoln Boulevard to the south, and Loara Street to the west. The scope involved 1,795,739 sf of slurry seal, and 756,645 sf of asphalt reconstruction; 9 The T anglewood Neighborhood is bound
by Imperial Highway to the north, Yosemite Drive to the west, Kellog to the east, and Orangethorpe Avenue to the south. The scope included 339,901 sf of asphalt reconstruction, 358,598 sf of slurry seal, and 18,255 sf o f s i d e w a l k i m p r o v e m e n t s . I n a d d i t i o n , 6 5 n e w t r e e s a n d 3 0 t r e e r e m o v a l s w e r e m a d e f o r t h e i n t e r e s t o f t h i s neighborhood;
10 The Rio Bravo neighborhood is bordered by Camino Manzana, Calle Granada, and Calle Tampico t o t h e n o r t h , E u c a l y p t u s D r i v e t o t h e e a s t , S a n t a A n a C a n y o n R o a d t o t h e s o u t h , a n d V i a C o r t e z t o t h e w e s t . T h e scope included 306,997 sf of asphalt reconstruction, 294,712 sf of slurry seal, 14,029 sf of sidewalk improvements, 51 new trees and 24 removals;
11 The Academy/Bel Air Neighborhood is bound by Lincoln Avenue to the north, Dale Avenue to the east, Orange Avenue to the south, and Beach Boulevard to the west. The scope included SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 93 305
263,302 sf of asphalt reconstruction, 201,012 sf of slurry seal, 4,256 sf of sidewalk, 30 new trees and 6 removed; 12 The Gaymont/Elm Lawn Neighborhood is bound by Orange Avenue, Stonybrook Drive, and Ball Road to the north; Dale Avenue, Magnolia Avenue, and Gilbert Street to the east; the Anaheim City Limit to the south; and Beach Boulevard to the west. The scope included 397,521 sf of asphalt reconstruction, 201,012 sf of slurry seal; 12,842 sf of sidewalk, 3,187 lf of curb and gutter, and 71 new trees along with 15 removals; 13 The Greenleaf-Hampton Neighborhood is bound by La Palma Avenue to the north, Gilbert Street to the east, Crescent Avenue to the south, and the Anaheim City Limit to the west. The scope included 1,073,430 sf. of reconstruction, 494 tree trimmings, 15 removals and 75 new trees.

The project limits for phase II were split into three neighborhood areas, which were:
1 The Kings
Court Neighborhood is bound by Ball Road to the north, Euclid Street to the east, Katella Avenue to the south, and Brookhurst Street to the west. The scope included 1.1 million sf of grind and cap and

1.1 million sf of slurry seal; 2 The Velare Neighborhood is bound by Orange Avenue to the north, Gilbert Street to the east, Ball Road to the south, and Magnolia Avenue to the west. The scope included 260,677 sf of grind and cap and 327,499 sf of slurry seal; 3 The Sabina Neighborhood is bound by La Palma A venue to the north, Harbor Boulevard to the east, Sycamore to the south, and the Anaheim Boulevard to the west. The scope included 152,605 sf of grind and cap, 185,494 sf of slurry seal. Coordinating with the local residents was essential on these projects.

STREET & SLURRY SEAL REHAbI LITATION PROjE CT - PHASES I, II & III, lagUn a B EaCh M u h a m m a d p r o v i d e d P u b l i c O u t r e a c h s e rv i c e s f o r t h e C i t y o f L a g u n a B e a c h . T h e p r o j e c t l i m i t s f o r P h a s e I ( 2 0 1 7 ) w e r e split into three areas: Area A (Skyline) included 934,523 sf, Area B (Lower Bluebird Canyon) included 158,057 sf, and Area C (Summit Drive) included 185,961 sf. The project limits for Phase II (2018) covered three different regions: Area A: Canyon Acres Drive/Arroyo Drive/Woodland Drive Laguna Canyon Frontage Road, Area B: Residential streets in downtown (Loma Terrace, Y Place), and Area C: streets between Thalia Street and Cress Street. The project limits for Phase III (2019) included two areas, Area A: Coast Royal, and Area B: South Laguna Village. These areas are in South Laguna Beach, from the neighborhoods between West Street and 10th Avenue/Sunset Avenue. The work included variable grind and overlay in some areas, and Type I Slurry Seal in other areas. There was 2,562 square feet of French Drain that was installed in Area A. A 4-inch drain line was connected to a catch basin in Area A as well. The specifications also called for new traffic signal poles at the Skyline Drive, Crestview Drive, and Fern Street Intersections. Lastly, the project encompassed parkway and curb and gutter improvements, signage and striping. Due to the residential element involved, Muhammad provided Web Maps and a Project Hotline for affected residents, keeping them updated and informed .

ATLANTIC AVENUE & FIRESTONE bO ULEVAR d INTERSECTION wIdE NING, SoU T h gaTE Muhammad provided Public Outreach services for the the City of South Gate. The project limits were on two arterial streets:

Atlantic Avenue from Firestone Boulevard to Patata St. (~1,300 LF) and Firestone Boulevard, from Dorothy Avenue to Atlantic Ave. ( ~2,200 LF). The project involved the widening and realignment of the intersection to increase the number of thru, left turn lanes, the length of turn pockets, and right turn lanes. In addition to the widening, the scope entailed a concrete approach to the intersection; concrete intersection; grind and ARHM overlay; four legs of the intersection; 50,000 SF of sidewalk, 1,850 LF of curb and gutter, 2,100 LF of DIP waterline and 2,840 LF of recycled waterline, and 4,656 LF of median island curb with decorative landscaping and a city monument sign. This project was funded with Measure R, MTA and other state funding sources, and required the preparation of an award package and the continued upkeep of project files, invoices, reports and submittals in accordance with Caltrans’ LAPM.

SANTA ANITA ACTIVE TRANSPORTATION CYCLE 5, El mon TE
Muhammad provided Public Outreach services for the City of El Monte. The purpose of this project was to improve safety for roadway users and to improve conditions for non-motorized modes of travel, thereby promoting pedestrian cycle and transit use. In doing so, the intent was to improve neighborhood connectivity and livability, and to enhance the comfort of non-motorized users traveling to and from the El Monte Transit Center and Downtown El Monte. The work entailed roadway rehabilitation, parkway improvements-involving 51 ADA curb ramps, 4,000 square feet of sidewalk, 200 linear feet of curb and gutter-and upgrades to video detection and traffic signals at 7 intersections, along with wayfinding sign and bike rack installation at various intersections. The project was split into 3 phases. Phase I involved class II bike lane installation for

0.53 mile at Santa Anita Avenue, from Tyler Avenue to Lower Azusa Road; Phase II had pavement, curb and ramp upgrades at Tyler Avenue, from Ramona Boulevard to Santa Anita Boulevard for .97 mile; and Phase III entailed pavement, curb and ramp upgrades located at Ramona Boulevard, from Santa Anita Avenue to Tyler Avenue for .36 mile.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 94 306
geotechnical investigation & materials testing
(951) 264-9023
[email protected]
16817 Rainy Vale Avenue, Riverside, CA 92503
NoorzayGeoNoorzayGeo
Noorzay Geotechnical Services Inc. has developed pavement design recommendations in accordance with Caltrans Highway Design Manual and the latest edition of the “Greenbook”. Noorzay has the capabilities to obtain encroachment permits, core at representative locations, and perform the necessary laboratory testing to provide an economical design for the project. Noorzay is adept at slope stability issues, foundation recommendations, settlement or expansive soils, and more. Noorzay utilizes certified technicians for compaction testing during grading, subgrade preparation, trench backfill, aggregate base placement, and hot mix asphalt paving. They can also provide ACI certified technicians for concrete testing in the field and sampling for compressive strength testing. For over the past 15 years, Noorzay has provided pavement evaluations, compaction testing, soils reports, along with all other geotechnical needs. company e xperience
GREEN TREE bO ULEVAR d TO YATES ROAd ExT ENSION PROjE CT The City of viC T o rvill E NoorzayGeo prepared the Materials Report in Victorville. The project extended from 500 feet west of Green Tree Boulevard from its intersection with Hesperia Road and continued east over the BNSF railroad tracks to merge with Ridgecrest Road and Yates Road. At the western limit, the alignment also included a portion of Hesperia Road from approximately 400 feet north of its intersection with Green Tree Boulevard to Coad Road to the south. At the eastern limit, the project alignment split and continued onto Yates Road, heading north to its intersection with Park Road and extending south on Ridgecrest Road to approximately 1,000 feet south of Chinquapin Drive. The project scope of services included reviewing available reports prepared by project personnel, a field investigation and associated laboratory testing, engineering analysis and preparation of the Materials Report for submission to Caltrans.

LENwO O d ROAd GRAdE S EPARATION PROjE CT The City of Ba r STo w NoorzayGeo provided Quality Assurance on this $32 million dollar Grade Separation Project as part of the Alameda Rail Corridor East Project for the City of Barstow. The project was intended to facilitate the flow of both vehicular and freight rail traffic though the City of Barstow. This project developed a grade separated crossing along Lenwood Road over the existing BNSF tracks. The improvements include the widening of Lenwood Road from two lanes to four lanes between Main Street and Jasper Road. The grade separation allowed for improved emergency response time and reduced congestion and in turn improved the air quality of the surrounding area. Maihan provided Quality Assurance management involving testing services for construction materials at the direction of the Project Managers of Simon Wong Engineering. The scope of work included compaction, concrete and materials testing of many aspects of the project such as mechanically stabilized earth walls, structural fill and embankment, and sewer improvements. bRIdG E AT RANCHERO ROA d OVER THE I-15 FREE wA Y The City of hESpEri a NoorzayGeo provided QA Management for thje City of Hesperia. This project consisted of a bridge at Ranchero Road over the I-15 freeway in Hesperia, CA. The Noorzay team supervised the Quality Assurance Materials Testing and Inspection services in accordance with the Caltrans construction manual as well as the project special provisions. Administered and oversaw the hot mix asphalt QC/QA program including the coordination and verification of the contractors QC laboratory testing.

Served as QA Project Manager for this project and his daily responsibilities included reviewing daily reports, presenting lab and field test data, and offering technical guidance. Prepared the invoices using the SANBAG templates and categorizes and files all test data. Performed review and acceptance of hot-mix asphalt (HMA) mix designs, material submittals including JPCP and PCC mix design submittals, and Quality Control plans provided by others. This project met Caltrans expectations for each audit.

SUB-Co n SUlTa nT S
SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 95 307
environmental consUl ting
(909) 307-0046
[email protected]
215 North 5th Street, Redlands, CA 92374
ECORP Consulting, Inc. (ECORP) is a California “S” Corporation that specializes in assisting government agencies and private clients with a wide range of environmental services including technical expertise in land use planning; biological, cultural, and water resources; and regulatory compliance with California Environmental Quality Act (CEQA) and National Environmental Policy Act (NEPA), Clean Water Act, federal and state Endangered Species Acts, NHPA, and other laws and regulations. ECORP provides support over the life of a project, from initial baseline studies; to environmental planning, documentation, and review; permit negotiation, liaison with resource agencies, and mitigation design; and through to construction supervision, monitoring, and compliance reporting. ECORP is a Federal Small Business. company experIe nce
SAN GAbRI EL RIVER wA TERSHEd PROjE CT CEQA & RAMP REVIE w The County of loS a ng ElE S
ECORP reviewed the IS/MN and Adaptive Management Plan (AMP) for the San Gabriel River Watershed Project to Reduce River Discharge in Support of Increased Recycled Water Reuse. ECORP’s focus was limited to biological resources and those specific thresholds of significance in the CEQA checklist, specifically on the reported conclusions in the IS/MND regarding the potential impacts of diverted water on riparian habitat supporting the least Bell’s vireo, the benthic environs, and the overall habitat. ECORP’s review focused on evaluating the existing and future annual daily average discharge from approximately 16 million gallons per day (MGD) to a minimum monthly average of approximately five (5) MGD at the San Jose Creek Water Reclamation Plant (WRP), which discharges to sensitive habitat. In addition, ECORP considered the AMP within the context of the significance finding.

CALTRANS ASSISTANCE ROAd wIdE NING & TRAFFIC
The County of morEn o vall Ey
This Caltrans Local Assistance Project for the City of Moreno Valley for road widening and traffic requirements included a 1.5-acre transportation corridor in a 9-acre area at SR-60 and Redlands Boulevard in Moreno Valley in support of the proposed installationof a traffic signal and the widening of Redlands Boulevard from approximately 600 feet north of toapproximately 600 feet south of the eastbound SR- 60 on/off ramps. Following an evaluation of therecords search results, an intensive field survey of the project area was conducted. No cultural resourceswere identified within the project area as a result of the records search or field survey. A historic structure was identified just outside the eastern edge of the project area and was recommended to be evaluated for CRHR eligibility if any disturbances or visual impacts from road improvements and traffic signal construction affecting the structure. wEST RI dG E GOLF COURSE GROUN d wA TER ExT RACTION
The City of la haBr a
On this Westridge Golf Course Groundwater Extraction Project for the City of La Habra, an IS/MND was prepared by ECORP for the construction and operation of a 500-foot-deep well to extract groundwater for use at the existing Westridge Golf Course. An approximately 50-foot buried pipeline would be constructed to connect the well to the existing irrigation system. The project was located in the golf course parking lot and landscaped areas adjacent to a residential development.

The IS/MND included an air quality/climate change technical report and detailed analysis, with an emphasis on impacts to air quality, biological resources (nesting birds), hydrology/groundwater, and greenhouse gas emissions.

ON-CALL MASTER SERVICES AGREEMENT FOR ENVIRONMENTAL SERVICES The Counties of Sa n BEr nardino & riv ErSi dE
ECORP is provided on-call environmental services for water and wastewater projects in the cities of Yucaipa and Calimesa with the Yucaipa Valley Water District. Under this contract, ECORP is responsible for determining the appropriate environmental documentation and studies needed to comply with CEQA and to obtain the appropriate environmental permits for YVWD projects. Task orders completed under this on-call contract include the preparation and filing of categorical exemptions for small projects, the preparation of IS/MNDs for potable and non-potable pipelines and reservoirs, and construction monitoring.

SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 96 308
GEOTECHNiC AL iN VEST iG AT iO N & MATERiA LS/S OiL TEST iN G Steve Koch, PE
(714) 632-2999
[email protected]
2992 E. La Palma Ave., Ste. A, Anaheim, CA 92806
MTGL, Inc. is a California corporation and is a registered woman-owned, minority owned, and community business enterprise (WBE/MBE/CBE). MTGL provides geotechnical engineering, soils/materials inspections, and laboratory testing services. MTGL was formed in 1993 by a group of seasoned professionals and they provide Geotechnical Investigations and Construction Quality Control/Assurance. As an independent third party, MTGL ensures that the current standards and codes are followed. MTGL furnishes field, site and plant inspections for all construction materials. They conduct physical laboratory testing for all of the materials that are placed during these inspections and investigations. Their laboratories currently operate in compliance with ASTM standards, and the company is certified by the DSA, CBC, CCRL, AASHTO, County and City of Los Angeles, and Caltrans.

Co mpany EXpEr iEnC E & rEfErEnC ES
I-215 & SR74 INTERCHANGE PROjE CT
The City of Cor ona
MTGL on this project included the construction of a new over crossing structure to replace the existing SR-74 and I-215 interchange. Work included the realignment, reconstruction and widening of ramps, reconfiguration of the 4th Street and Redlands Avenue Intersection and widening of 4th Street. Also included in the project is the construction of retaining and sound walls. The project was federally funded, began in Spring of 2010 and was completed five months ahead of schedule.

MTGL provided Soils Observation and Testing in addition to Materials Testing and Field Inspection Services. All testing and inspection was completed in accordance with Caltrans Test Methods, Standards and Guidelines.

PACIFIC STREET bRIdG E PROjE CT
The City of oC E anSi dE
The Pacific Street Bridge is an $18 million dollar project in Oceanside that crosses the San Luis Rey River and links the harbor to Oceanside’s downtown. MTGL began construction of the 600-foot- long bridge with existing traffic lane, bike lane and a sidewalk in each direction, connecting Pacific Street on the south side with Harbor Drive on the north side. The bridge construction is an environmentally friendly project and includes trash and oil filters at storm drain outlets, river roosting rafts for pelicans, and removal of the old “low-water” crossing and restoration of beach sand areas. It also features landscaped slopes with native plant species to control erosion.

MTGL was contracted for this project and provided the Geotechnical, Materials Inspections and Laboratory Testing Services for the Pacific Street Bridge project. Testing was completed in accordance with Greenbook and Caltrans Standards.

AGUA MANSA ROAd IMP ROVEMENT/wI d ENING PROj ECT
The City of ColTon
The Agua Mansa Road Improvement Project is a much needed improvement and widening of the Agua Mansa Road for future development, provided by MTGL. The project consists of preparing the road for widening by grading, trenching and placing pipe for new utilities. The quality control needs for this project relied heavily on the testing of Recycled Rubberized Asphalt. Due to MTGL Inc.’s experience in this type of work, the Agua Mansa improvement has been another quality project.

MTGL provided Quality Control Services by performing precise grading observation, testing, sampling and analysis of soil and asphalt, special inspections and testing of concrete, reinforcing steel, masonry, and structural steel components.

REFERENCE

GARY TOMASETTI
Jacobs Project
Management
(714) 412-2262
5757 Plaza Dr.

Suite 100
Cypress, CA 90630

REFERENCE
MR. CRAIG JOHNSON
Harris & Associates
(714) 742-6020
34 Executive Park ,
Suite 150
Irvine, CA 92614

REFERENCE

REGGIE TORRES
(909) 370-5065
650 N La Cadena Dr,
Colton, CA 92324
SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 97 309
landscaping cons Ul tant
(657) 217.6169
[email protected]
323 N. Resh Street, Anaheim, CA 92805
Sitio Landscape Architecture Inc. is a design studio focused on applying the principles of landscape architecture to outdoor design at all scales. Sitio exists as a collection of designers, trades and supporters. Each providing their talents and time to build a company that reflects their professional goals. Sitio’s success is rooted in their professional relationships. Sitio’s designers have worked on a variety of project types with other landscape architecture firms, past and present. Private residential, public parks, multi-family housing, master planned communities, municipality projects, education, medical and religious campuses, commercial and retail centers, and complete streets initiatives are all within their capabilities and can be developed from the schematic phase, through concept planning and on to construction documentation. Sitio also provides landscape construction administration. Landscape Architect, Pablo Cortez (PLA# 6373) leads Sitio with his own varied experience and organizational skills to help design and create living, vibrant outdoor spaces.

COMPANY ExP ERiEN CE
kIdST REAM OUT dO OR PLAY SPACE
Sitio provided site plan development
& construction documentation.

RIVERSIdE SINGLE FAMILY dE TACHE d E NTITLEMENT
SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 98 310
SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 99 rECo mm En daT ion l ETTErS
311
SECTION 5
: Qualifications of Proposed Personnel

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 100

CITY OF MANHATTAN BEACH PUBLIC WORKS
3621 Bell Avenue, Manhattan Beach, CA 90266

www.manhattanbeach.gov • [email protected] • (310) 802-5368

January 23, 2023

To Whom It May Concern,
I am writing to highly recommend Onward Engineering for construction management and inspection services. I have had the pleasure of working with Onward Engineering on several projects over the past 7 years, and I have been consistently impressed with the level of professionalism, expertise, and attention to detail that they bring to every project.

In my experience, Onward Engineering has proven to be an invaluable partner in the construction process. They have a deep understanding of the local building codes and regulations, and they are able to provide insightful and practical solutions to any challenges that may arise. Their team is highly skilled, and they are able to manage all aspects of the construction process, from pre-construction planning and design to final inspection and closeout. In addition to their technical expertise, Onward Engineering is also known for their excellent communication skills. They are responsive and easy to work with, and they always keep the project stakeholders informed of progress and any issues that may arise. This level of transparency and collaboration is key to ensuring a successful project, and I have always appreciated Onward's willingness to go above and beyond to ensure that our projects are completed on time and within budget.

I would highly recommend Onward Engineering to any organization in need of construction management and inspection services in Southern California. They are a team of highly skilled professionals who consistently deliver high-quality work, and they have always been a pleasure to work with.

Please do not hesitate to contact me if you have any further questions or would like additional information.

Sincerely,

Tim Birthisel, P. E.

Senior Civil Engineer
312
Onward Engineering holds no exceptions to The City of Lynwood’s Professional Services Agreement and agree with and will execute all terms and conditions therein, and we assure proper and applicable insurance coverage (see next page for document).

AGREEMENT TO CONTRACT TERMS & INSURANCE77
SECTION 7
: Agreement to City Contract Terms & Ability to Obtain Insurance

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 101
313

ANY PROPRIETOR/PARTNER/EXECUTIVE
OFFICER/MEMBER EXCLUDED?

INSR ADDL SUBR

LTR INSD WVD

PRODUCER CONTACT
NAME:

FAXPHONE
(A/C, No):(A/C, No, Ext):

E-MAIL
ADDRESS:

INSURER A :

INSURED INSURER B :

INSURER C :

INSURER D :

INSURER E :

INSURER F :

POLICY NUMBER POLICY EFF POLICY EXPTYPE OF INSURANCE LIMITS(MM/DD/YYYY) (MM/DD/YYYY)

AUTOMOBILE LIABILITY

UMBRELLA LIAB

EXCESS LIAB

WORKERS COMPENSATION

AND EMPLOYERS' LIABILITY
DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (ACORD 101, Additional Remarks Schedule, may be attached if more space is required)

AUTHORIZED REPRESENTATIVE
EACH OCCURRENCE $
DAMAGE TO RENTEDCLAIMS-MADE OCCUR $PREMISES (Ea occurrence) MED EXP (Any one person) $
PERSONAL & ADV INJURY $
GEN'L AGGREGATE LIMIT APPLIES PER: GENERAL AGGREGATE $

PRO-POLICY LOC PRODUCTS - COMP/OP AGGJECT
OTHER: $

COMBINED SINGLE LIMIT
$(Ea accident)
ANY AUTO BODILY INJURY (Per person) $

OWNED SCHEDULED
BODILY INJURY (Per accident) $AUTOS ONLY AUTOS

HIRED NON-OWNED PROPERTY DAMAGE
$AUTOS ONLY AUTOS ONLY (Per accident)
$

OCCUR EACH OCCURRENCE
CLAIMS-MADE AGGREGATE $
DED RETENTION $

PER OTH-

STATUTE ER
E.L. EACH ACCIDENT
E.L. DISEASE - EA EMPLOYEE $
If yes, describe under
E.L. DISEASE - POLICY LIMITDESCRIPTION OF OPERATIONS below INSURER(S) AFFORDING COVERAGE NAIC #

COMMERCIAL GENERAL LIABILITY
Y / N
N / A
(Mandatory in NH)

SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE

THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS.

THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS

CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.

THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS

CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.

IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must have ADDITIONAL INSURED provisions or be endorsed.

If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).

COVERAGES CERTIFICATE NUMBER: REVISION NUMBER:

CERTIFICATE HOLDER CANCELLATION
© 1988-2015 ACORD CORPORATION. All rights reserved.ACORD 25 (2016/03)

CERTIFICATE OF LIABILITY INSURANCE

DATE (MM/DD/YYYY)
$
$
$
$
$The ACORD name and logo are registered marks of ACORD
8/4/2023
(949) 583-0300
11000
Onward Engineering
300 S. Harbor Blvd. Ste. #814
Anaheim, CA 92805
A 2,000,000
X 72SBABF1830 8/7/2023 8/7/2024 1,000,000
10,000
2,000,000
4,000,000
4,000,000
DRONE 25,000
1,000,000
B
72UECZN1275 8/7/2023 8/7/2024
1,000,000A
72SBABF1830 8/7/2023 8/7/2024 1,000,000
10,000
C
ONWC411292 8/7/2023 8/7/2024 1,000,000
1,000,000
1,000,000
D Professional Liab V331E4230201 8/7/2023 Per Claim 2,000,000 D Deductible $25K V331E4230201 8/7/2023 8/7/2024 Aggregate 2,000,000 certificate holder is named as additional insured per attached endorsement.

ONWAENG-01 SHAEM1
Solomon & Solomon Insurance Brokers
A Division of Patriot of California Insurance Services, LLC 24461 Ridge Route Drive, Suite A230
Laguna Hills, CA 92653
Sentinel Insurance Company
Hartford Accident & Indemnity
Berkshire Hathaway Homestate
Beazley Insurance Company
X
8/7/2024
X
X
X
X
X
X
X
314
Onward Engineering holds a stable financial history. Onward Engineering has the financial stability and depth of resources to ensure the successful completion of its assignments. Onward Engineering does not have any conditions – including bankruptcy, planned office closures, pending or settled claims or litigations, or impending mergers-that would impede its ability to perform for the City of Lynwood.

LEGAL ISSUES88
SECTION 8
: Legal Issues

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 103
315
Onward Engineering is not, nor has it ever been, the subject of any investigation by the County, State, and/or Federal agencies within the past 5 years.

DISCLOSURES99
SECTION 9
: Disclosures

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 104
316
Onward Engineering vowes to adhere to all Federal, State, County and the City of Lynwood’s Regulations.

Onward Engineering vowes to allow authorized Federal, State, County and the City of Lynwood’s official’s access to its place of work, books, documents, papers, fiscal, payroll materials, and other relevant contract records pertinent to this Project, and to retain all relevant records for at least three (3) years.

Onward Engineering vowes to not discriminate against any employee or applicant for employment because of race, color, religion, sex or national origin.

Onward Engineering vowes to comply with the California Labor Code pursuant to said regulations entitled: Federal Labor Standards provisions; Federal Prevailing Wage Decision; and State of California Prevailing Wage Rates, respectively.

ADDITIONAL ST A TEMENTS1010
SECTION 10
: Additional Statements

Request for Qualifications for Professional Civil Engineering On-Call Services for the City of LYNWOOD 105
317
design smarter. build better.
300 S. Harbor Blvd.

Suite 814
Anaheim, CA 92805
(714) 533.3050
www.oe-eng.com
hoUr ly raT ES
CIvIl En g In EErIn g
role cost (hourly)
Principal-in-Charge $250.00
QA/QC Manager $225.00
Project Manager $185.00
Project Engineer $150.00
Co n S T rU CTIo n managEmEn T & InSp ECTIo n
role cost (hourly)
Construction Manager $185.00
Construction Inspector* $140.00 ( OT $170, DT $195 )
Public Outreach $95.00
admIn ISTr aT Io n
role cost (hourly)
Administration $90.00
The hourly rates above are our fee schedule. Any additional work will be negotiated utilizing those hourly rates.

OE pays all Construction Inspectors prevailing wage rates in compliance with the requirements set forth by the Department of Industrial Relations (DIR) State prevailing wages under Labor Code § 1770 et seq. Labor Code §§ 1775 and 1777.7 along with the Davis-Bacon and Related Acts (DBRA) under the standards of the Community Development Block Grant (CDBG) funding as administered by the U.S. Housing and Urban Development (HUD) Department. 318
City of Lynwood, CA
Professional Civil Engineering
On - Call Services
Statement of Qualifications
Submitted by:

Sid Mousavi, MSCE, PE, Senior Principal
Infrastructure Engineers, a Bowman company
3060 Saturn Street, Suite 250
Brea, CA 92821
714.940.0100 | [email protected] | bowman.com
Submitted to:

Julian Lee, Director of Public Works
City of Lynwood
11750 Alameda Street
Lynwood, CA 90262
November 13, 2023
319
Table of Contents
TAB # SECTION PAGE #
1 Cover Letter 2
2 Firm Organization, Credentials and Background 4
3 Approach to the Project 9
4 Project Experience 30
5 Qualifications of Proposed Personnel 50
6 Readiness to Provide Services 94
7 Agreement to City Contract Terms and Ability to Obtain Insurance 95 8 Legal Issues 96
9 Disclosures 97
10 Additional Statements 98
11 Fee Proposal 99
320
01 Cover Letter
321
November 13, 2023
Julian Lee
Director of Public Works
City of Lynwood
11750 Alameda Street
Lynwood, CA 90262
RE: Professional Civil Engineering On - Call Services
Dear Mr. Lee:

Infrastructure Engineers (IE), a Bowman company, understands the need for help from time to time; hence the wisdom of developing a consultant on - call list of qualified engineering firms for the City of Lynwood to choose from. Providing as - needed services to municipalities is our forte, IE was founded on the premise of assisting cities when our services are needed.

Public works projects enhance the overall quality of life in cities by improving the physical structures, systems, and facilities that provide services to the community. Some projects can be large and expensive, and the assets they install, replace, or rehabilitate will likely be required to last for decades of public use. Therefore, you will want an engineering consultant that not only takes to heart the substantial financial investment involved, but also has the capabilities to undertake the varied anticipated projects and that knows the particular needs and expectations of the City of Lynwood.

It is a privilege to provide our qualifications for the Professional Civil Engineering Services On - Call Services for the City of Lynwood. At IE we do offer a full range of engineering services all under one umbrella, thus, we are submitting for all categories: General Engineering, Utility Engineering, Traffic Engineering and Architectural Services. We have established a reputation of meeting the expectations of our clients by employing experienced staff members who not only understand civil engineering, but also have a solid foundation of the inner workings of the municipal office and public works process. More than 90% of our staff, as part of their professional development, have worked for city governments as employees. As a result, our company is known for providing responsive, quality recommendations and solutions to a wide variety of civil and traffic design projects. We believe that successful projects are the result of a well - managed and motivated team, committed to being accountable and sharing ownership in the product or service that the IE team collectively provides.

We believe IE is your best choice to provide the requested civil / traffic / utility engineering services for the following reasons:

Qualified and Experienced Management Team - We are proposing Mr. Farzad Dorrani, MS as our Program Director and the main point of contact for delivery of every project that IE is assigned to perform. Mr. Dorrani will work with our designated project managers, for each of the categories of services that IE is assigned to undertake. We believe that this arrangement will best serve the city by having one person to process and assign work amongst IE’s management team. Our project manager responsible for Civil Design, Mr. Aidan Mousavi, 3060 Saturn Street, Suite 250, Brea, California 92821
714.940.0100
infrastructure-engineers.com | bowman.com
322
MBA, PE, QSP / QSD has more than 12 years of experience in various civil and traffic engineering disciplines.

He also has experience with contract administration, design, and regulatory compliance. Aidan has worked in various cities serving as their CIP manager gaining a set of skills that not only assists municipalities with projects but helps keep them within budget as well. Our Construction Manager, Mr. Masoud Sepahi, PE, LEED GA has over 30 years of experience in delivery of many complex CIP projects throughout Southern California. Mr. Sepahi has served in many leadership positions, such City Engineer for the City of Placentia for over 6 years, Director of Construction Management for the Los Angeles Metro and the City of Los Angeles for 10 years. Mr. Sepahi’s construction management team is ready and very eager to assist the city with all of the city’s construction support needs. Other key project / design mangers, include, Mr. Christopher Ley, PE who will be leading the Utility Engineering group and Mr. Amir Farahani, TE, PE who will be managing the Traffic Engineering projects.

Knowledge of the City of Lynwood - IE staff exclusively service local agencies and have an extensive history of successfully providing a wide range of services. In fact, we have been assisting the City of Lynwood with these services for over 15 years. Our experience and intimate knowledge of the City of Lynwood and numerous other cities that we have served minimizes training time and provides seamless project delivery, all of which results in cost savings to the city.

We encourage the city to contact our references and confirm our successful track record.

We Deliver Projects on Schedule and On Budget - We understand the city is often faced with budget constraints. IE has a history of successfully delivering projects with very limited budgets. We are committed to working with the city to keep your project on time and within budget.

Due to our experience dealing with many complex development projects, we bring fresh, new ideas to solve complex development projects. Each project, by its nature, is different from all others and it has its own unique challenges and solutions. Our staff rises to these occasions by working collaboratively to find sound engineering design solutions.

We possess the talent and capabilities to provide the City of Lynwood with the engineering, design, and review services described in the RFQ while maintaining your strict budgeting priorities.

Our office nearest to the City of Lynwood is located at 13200 Crossroads Parkway North, Suite 400, Industry, CA 91746. We will provide the proposed services from our headquarters located at 3060 Saturn Street, Suite 250, Brea, CA 92821.

As an officer of the firm, I am the authorized to negotiate, contractually bind and extend the terms of our Statement of Qualifications (SOQ). This SOQ will remain valid for a period of not less than 90 days from the date of submittal. Farzad Dorrani, a principal of our company, will serve as the Program Director, main point of contact throughout the duration of the contract and will be responsible for the services listed in the RFQ. Farzad can be reached by phone at 714.940.0100, by fax at 714.940.0700, or by email at [email protected]. We thank you for this opportunity to continue being of service to the City of Lynwood.

Sincerely,
Sid Mousavi, MSCE, PE
Senior Principal
infrastructure-engineers.com | bowman.com
323
02 Firm Organization, Credentials and Background
324
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 4 Firm Organization, Credentials and Background
Infrastructure Engineers (IE), a Bowman company is a corporation that was founded in 1994. IE’s mission is to provide professional engineering, planning, environmental and municipal services to cities and counties throughout Southern and Central California. As a results driven engineering service provider focused on public sector assignments, IE provides services that include civil design, construction management, traffic engineering, community development planning, environmental services, water / wastewater engineering, and staff augmentation for municipal and state agencies. IE is of sound financial condition and has no pending conditions that may impede our ability to provide the requested / proposed services. IE has no alleged significant prior or ongoing contract failures, any civil or criminal litigation or investigation pending which involves the IE or in which the IE has been judged guilty or liable. 56 Years in Business
Combined
$277
Current Revenue Pace (Millions)
83 Offices Nationwide
2,000
Number of Employees (Approx.)
IE will provide the proposed services to the City
of Lynwood from our Brea, CA headquarters.

IE provides a breadth of professional
engineering, planning, environmental,
geospatial and municipal infrastructure services
to cities and counties throughout Southern and
Central California.

As of June 13, 2023, Infrastructure Engineers
has officially joined Bowman. This change
provides a strong foundation for us to merge
our comprehensive skillsets while offering the
same level of commitment to our clients and
employees.

Our History
• Building & Safety
• ADA Compliance
• Building Inspection
• Plan Check
• Civil Engineering
• Land Use Planning
• Environmental Consulting
• Water / Wastewater
• Construction Management
• Traffic Engineering
• Survey & Geospatial
Services
• Municipal
• Industrial
• Water / Wastewater
• Technology / Data Centers
• Residential
• Parks & Recreation
Markets
325
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 55 Firm Organization, Credentials and Background (cont.) National Footprint ...One Team!
With more than 80 offices nationwide, we
continue to add staff, services, and locations to
continue to provide the best development and
infrastructure services to our clients.
2,000+ Employees
120+ Fully Equipped Field Survey Crews
300+ Professional Engineers
60+ Professional Surveyors
100+ Right-of-Way and Land Professionals
13 Environmental Specialists
90+ Planners and Designers
20+ Registered Landscape Architects
Team Members Awards
Zweig Group - Hot Firm’s List - #9 (2023)
Engineering News Record
#87 - Top 500 Design Firms (2023)
#69 - Top 500 Design Firms Pure Designers (2023)
#22 - Mid-Atlantic - Top Design Firms (2023)
#44 - Southeast - Top Design Firms (2023)
#78 - New York - Top Design Firms (2023)
#57 - Texas & Louisiana - Top Design Firms (2023)
National Business Journals
#8 - Washington Bus. Journal Largest Engineering Firm (2023) #5 - Washington Bus. Journal Largest Landscape Architecture (2023) #18 - Louisville Business First Largest Engineering Firm (2023) #12 - Philadelphia Business Journal Largest Engineering Firm (2023) #17 - Phoenix Business Journal Largest Engineering Firm (2023) #42 - Dallas Business Journal Largest Engineering Firm (2023) MEP Giants - #88 (2022)
Bowman has grown not for the sake of
growth, but on behalf of our customers.

Our clients know their industry, their product
and their end-user. It’s our job to know our clients, their project drivers and how to achieve them. By leveraging
the expertise of our local teams and the extensive knowledge of our national resources, Bowman stands ready to deliver innovative development strategies, design concepts and
technological advancements to your next project.
326
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 6 Firm Organization, Credentials and Background (cont.)

PRINCIPALS OF THE FIRM

SID MOUSAVI, MSCE, PE - SENIOR PRINCIPAL AT INFRASTRUCTURE ENGINEERS (IE), A BOWMAN

COMPANY
Sid has over 35 years of experience in engineering projects covering a wide range of municipal management, civil engineering, transportation, public works, construction management, traffic engineering, community development and redevelopment, parks and recreation facilities, and public and private land development. Sid is responsible for the direction and administration of internal services, civil engineering design, city services and other corporate management responsibilities and matters. Prior to joining IE, Sid’s accomplishments included serving as City Manager, Director of Public Works, and City Engineer for various cities in Southern California, with responsibilities for directing and administering such functional elements as engineering, planning, building and safety, facilities and equipment, landscaping, streets, environmental services, transportation, transit and other municipal services. Responsibilities also included communication with city councils, city commissions, other city departments and governmental regulatory agencies, utility companies, contractors, consultants, and the general public. Sid has performed the entire spectrum of engineering activities, which include engineering investigations, conceptual and feasibility studies, planning / scheduling, design, specifications, cost analysis, cost estimating, contract negotiations, construction management and engineering support services. Sid has served as the contract City Engineer for the Cities of Bell Gardens, Montebello, Irwindale, La Puente and Baldwin Park.

FARZAD DORRANI, MS - PRINCIPAL OF OPERATIONS AT INFRASTRUCTURE ENGINEERS (IE), A

BOWMAN COMPANY
Farzad has over 30 years of experience in a variety of civil engineering projects. He has worked extensively on major infrastructure and public works improvement and rehabilitation projects throughout southern California for various agencies, such as the cities of La Puente, Montebello, Anaheim, Irwindale, Malibu, as well as the Alameda Corridor - East Construction Authority. Farzad’s experience includes roadway design projects, parks, and downtown revitalization design projects, contract procurement, construction management, project management and administration.

AIDAN MOUSAVI, MBA, PE, QSP / QSD - PRINCIPAL OF DESIGN SERVICES AT INFRASTRUCTURE

ENGINEERS (IE), A BOWMAN COMPANY
Aidan’s professional focus is primarily in the field of city engineering and environmental infrastructure by providing civil engineering assistance to Public Works and Engineering Departments. He works closely with cities to ensure compliance with the National Pollutant Discharge Elimination System (NPDES). Aidan has developed strategies for the efficient use of Best Management Practices (BMPs), thus gaining a set of skills that not only assists municipalities with compliance but helps keep them under budget as well. Aidan is familiar with municipal protocols and works within these structures to conduct field inspections and develop annual compliance reports. As an MBA graduate, Aidan brings his academic knowledge to IE to work with the firm’s Operations Manager to manage all Capital Improvement Program (CIP) and non - CIP projects.

MASOUD SEPAHI, PE, LEED GA - PRINCIPAL OF CONSTRUCTION MANAGEMENT SERVICES AT

INFRASTRUCTURE ENGINEERS (IE), A BOWMAN COMPANY
Masoud offers more than 30 years of construction management and design experience covering a wide range of civil, buildings, utilities, airports, and many other challenging and complex infrastructure projects. Most recently, as the City Engineer for the City of Placentia, Masoud managed the delivery of numerous CIP projects, including many similar projects, currently planned by the City of Lynwood. Masoud’s construction management experience includes many iconic programs and projects, such as the Police Administration Building and the Los Angeles Convention Center Expansion projects in downtown Los Angeles, the Crenshaw / LAX Transit Line, the Purple Line’s Advanced Utility Relocation and many Roadway 327
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 7 Firm Organization, Credentials and Background (cont.) Improvement Programs for the City of Los Angeles. Masoud has gained valuable knowledge of the local policies and procedures in addition to codes and regulations through recent interactions with various city and private utility agencies.

Masoud stands ready and eager to assist the City of Lynwood with delivery of the upcoming CIP projects.

JAY SHIH, MS, PE, CASP , CBO, QSP / QSD - PRINCIPAL OF BUILDING AND SAFETY SERVICES AT

INFRASTRUCTURE ENGINEERS (IE), A BOWMAN COMPANY
Jay is a veteran civil engineer, building official, construction manager, access specialist, structural and engineering designer and plan checker with 35 years of experience. Jay has spent his career working for public agencies and consulting companies providing highly skilled design, building and engineering plan check and construction management of buildings, sewers, storm drains, streets, sidewalk, curb ramps, grading and stormwater management.

SUBCONSUL TANTS
Dennis Janda, Inc. (DJI) - Land Surveying
DJI is a private corporation providing land surveying and mapping services and is a Certified Small Business Enterprise in the state of California. The owners and managers of DJI have worked together for both public and private sectors clients, throughout Southern California since 1997. DJI’s core staff has their roots in the traditional disciplines of land planning, civil engineering, land surveying and mapping mainly working on development and public works projects throughout California. This experience using and participating in the evolution of surveying and mapping practices has helped in their ability to contribute in time and cost saving practices and processes from project conception through the development, to recording. Upon this foundation DJI added a diverse team of professionals using the best use of equipment and technology to contribute to their client’s specific project goals and schedules.

Associated Soils Engineering, Inc. (ASE) - Geotechnical Engineering Since 1990, Associated Soils Engineering, Inc. (ASE) has provided geotechnical design, geology, and material and construction testing services throughout southern California. Their in - house laboratory is one of the most complete and efficient in the industry. ASE provides services to a vast range of clients including private industrial and commercial owners, city and county public works, residential home builders, architects, construction managers, school districts and universities.

Location of Office to Provide Services
42164 Remington Avenue
Temecula, CA 92590
Legal Entity
Corporation
Year Established
1997
Location of Office to Provide Services
2860 Walnut Avenue
Signal Hill, CA 90755
Legal Entity
Corporation
Year Established
1990
328
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 8 Firm Organization, Credentials and Background (cont.)

SUBCONSUL TANTS
Infrastructure Architects, Inc. (iArch) - Architectural Services iArch was incorporated in 2017 in the state of California. The fundamental line of business for Infrastructure Architect is facilities for municipalities. iArch has successfully worked with several municipalities helping with design of new parks, renovating and upgrading existing parks, planning and designing concepts for community centers, senior centers, retrofitting and tenant improvements for re - purposing the city offices, designing new and retrofitting existing restroom facilities, roof and HVAC renovations and other types of facility for municipalities. A small portion of their work involves developers and national corporation such as Chevron and Shell corporations. Their staff is made of seasoned professionals that have many years of experience working with municipalities and private developers. They take pride in partnering with the municipalities to create a better condition for the city residents as that is their ultimate goal and accomplishment. Their objective is to create a positive change anywhere that they provide their professional services.

Location of Office to Provide Services
222 S. Harbor Boulevard, Suite 705
Anaheim, CA 92805
Legal Entity
Corporation
Year Established
2017
329
03 Approach to the Project
330
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 9 Approach to the Project
We understand that public agencies often have ongoing needs for engineering services that may exceed their staff’s availability, or the agency may prefer to engage firms that offer a broad spectrum of services, with the ability to take projects from the feasibility stage through 100% design, bid and award and on to completion. Rather than going through a separate selection process each time the need for such services arises, the on - call contract provides a quick solution to get those needed services completed.

IE has had the pleasure of working with the City of Lynwood in a similar capacity for more than a dozen years. As such, we understand the nature of the on - call process, one element of which is responding quickly when you need us. In addition, we understand your expectations and preferences by having worked alongside your staff and being involved in your organization. Ultimately, the city needs a firm that can engage and manage the members of its organization as extensions of the city staff. IE team members continue to gain the respect and confidence of the city staff and stand ready to carry on this important responsibility for the term of the contract.

Understanding the city’s budgeting format, procedures and practices is vital for any consultant. Our staff have worked directly with city staff, at the city’s offices, for several years. We have established relationships, and we know your organization and your expectations; thus, there will be no learning curve or coming up to speed – we are already here and fully committed.

APPROACH
This section provides our approach to the delivery of each individual service needed by the city and as outlined in the RFP . For all disciplines, each project is launched in a prescribed manner that provides the basis for constant and consistent communication with the city - to keep you informed during all phases.

For all disciplines, IE will serve as an extension of city staff. This includes working with city’s project representatives regularly and remaining in constant communication with the entire design and construction management team to ensure successful and timely delivery of every project.
• Meetings will be conducted for which agenda notices will be distributed at least two working days before each meeting. • Meeting minutes will be distributed within one week of the meeting, identifying action items assignments and due dates. • Bi - weekly Project Status Reports will be provided, identifying tasks completed and planned, issues to be resolved, project schedule update and project trends. These reports will serve as a primary tool in monitoring project progress and keeping the city’s staff informed.
• Progress review meetings will be held internally by IE on a regular basis to update the project team on project development and critical tasks.
• Prior to releasing any document to the city or other agencies, an extensive review will be performed by both the Project Manager and QA / QC Team.

IMPLEMENTATION PLAN
IE’s approach to all projects follows a proven path of work elements and tasks that ensure a successful project. Working directly with the city’s Project Manager, IE’s Program Director, Mr. Farzad Dorrani and IE’s management team will formulate a resource allocation plan and a proposal for the city’s review and approval. Upon approval of the work plan, IE’s design / construction team will commence work immediately to meet the delivery of each task. For any of the design projects, Aidan Mousavi will be the lead. Once the project has been accepted by the city and it’s ready to move into the construction phase, Masoud Sepahi, the Director of Construction Management Services will take over by taking the project through bid / award process and the construction phase. This is our overall project implementation approach, which can be modified or rearranged to the satisfaction of the city. Upon issuance of the Notice to Proceed, IE will review the project objectives and 331
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 10 Approach to the Project (cont.)
requirements, schedule a kick - off meeting with the city staff and task leaders to discuss scope of work, project budget, and schedule. IE will prepare a work plan and assign team members to each task for maximum efficiency of resources and when project activities need to be handled simultaneously. Once team assignments are complete, a team coordination meeting will be held to identify key components of the project. As a part of this process, the project will be reviewed to ensure that all project elements meet the requirements of the funding source. In addition, all current design standards impacting the project, including federal and state ADA requirements, will be identified to be included in the project. IE’s team members will also be encouraged to think outside the box to identify the challenges of the project and develop and implement innovative design strategies to create cost efficiencies. All of IE’s projects are designed to ensure that project impacts to the public are minimized. IE is committed to providing the City of Lynwood with the highest level of quality and we will continuously work with the city to update the proposed work plan to fit within the city’s schedule and all other requirements. The following flow - chart summarizes our approach for delivery of each CIP project, being assigned to the IE team of Designers and Construction Managers.
332
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 11 Approach to the Project (cont.)

ENGINEERING DESIGN SERVICES
IE will provide full engineering design services in support of public works projects. Our team of engineers will take the following approach for every project that we design for our clients:
• For a typical CIP project, the process consists of conducting a project kick - off meeting with city personnel to learn and document the precise scope of the project, background, budget and schedule. This will allow our team to formulate and prepare a work plan including all the resources that are needed for a successful delivery of the project. During this meeting, the IE team will discuss specific design criteria along with preferred project strategies, cost limitations and, most importantly, potential issues, challenges and opportunities associated with each project that IE manages. Upon learning more on the project scope and timelines, IE will develop a master schedule and budget for all phases of the project being assigned including clear identification of milestones for all facets of work. • As part of IE’s internal project procedures, all project staff participate in a monthly project status meeting with key staff.

This meeting serves as an additional quality control check to ensure that all aspects of the project move forward seamlessly ahead of schedule, and to ensure that resources are allocated as needed. • Useful records pertaining to the proposed work may exist, such as existing improvement plans, maps, as - built drawings, utility plans, reports, studies, and other pertinent information within the projects’ limits. Additionally, there may be proposed improvements that will affect the design of the project. The design team will review these existing records and incorporate them into the design of the project, as appropriate. The city, county and utility companies will be contacted, and all information gathered regarding, existing utilities, easements, obstructions, etc. will be used as a part of the base map.
• Throughout the entire design phase, IE’s project manager will maintain communication with the city, by preparing a monthly status report, in addition to conducting a meeting, with city staff. IE will prepare and submit Plans, Specifications and Cost Estimates (PS&E) to the city at different intervals; 35%, 65%, 95% and 100% levels of completion. Although monthly reports will be provided, IE will proactively keep the city’s Project Manager informed of any new developments, issues or factors involved in the project and offer alternatives to solve any unforeseen conditions discovered during the design phase.
• For every meeting that IE conducts, staff will prepare agendas of special items that warrant discussion at the meetings and prepares and distributes minutes with action items to all involved parties. • On projects, where either land surveying, or boundary surveying is required, IE will arrange for conducting a full survey. Mr.

Dennis Janda, PLS of Dennis Janda, Inc., brings a wealth of geodesic and spatial surveying experience and will complement our team by assisting with all right - of - way and surveying services needed for the projects. • IE team will perform a site investigation to evaluate the existing condition of items pertaining to the design. During this investigation, locations of damaged or distressed features will be inspected. As part of this investigation, IE will also inspect the project site for compliance with the Americans with Disabilities Act (ADA) accessibility non - compliant features will be identified and noted. Existing drainage patterns will also be investigated and reviewed to determine any adverse slopes that may exist for every street improvement projects to eliminate any potential ponding issues. • IE will also conduct fieldwork to verify the locations of surface utility features within the project limits. During the field investigation, we will validate the locations of other special features and items such as traffic signal loops, overhead cables, potential encroachments, such as fences, walls, etc. In conjunction with all the information researched, IE will notify affected utility companies of the impending project and we will arrange for meetings to coordinate any necessary relocations that may be necessary. Surface features requiring adjustment will be identified and properly coordinated with the corresponding utility company.
333
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 12 Approach to the Project (cont.)
• If the proposed improvements interfere with existing utilities, we will arrange to have potholes taken by the utility companies. If the utility company has prior rights, we will negotiate with a contractor to pothole the utilities to obtain elevations and pinpoint the locations of the utilities. We will provide the city with copies of all correspondence with the utility companies compiled in a book report at the submittal of 95% plan completion, to ensure due diligence and follow - through with the utility companies.
• IE will review all available existing analysis reports. Based on review of these reports, we will recommend to the city if additional, supplemental or completely new reports or analysis will be needed. Our subconsultant for geotechnical Engineering is Associated Soils Engineering, Inc. (ASE). They will provide all the necessary geotechnical investigations including, pavement testing and subsurface analyses, by taking samples and laboratory testing. In addition, ASE will assist the team with taking core samples of the pavement to determine the thickness and the condition of the Asphalt Concrete (A / C) pavement for use in our design of the roadway rehabilitation projects. • A base map will be prepared and used for the preparation of construction drawings. This will show existing features necessary to depict the intended work within the project. As - built plans, field measurements and field survey work will be used for the compilation. The field survey work will be limited to those items and areas necessary for the proposed design.

This includes obtaining adequate topography and cross sections in areas of street widening or water or sewer line projects.

This approach is anticipated to present cost savings to the city while maintaining the intent and quality of the design work. • IE will prepare all plans to the city’s standards, utilizing base mapping based upon the agreed concepts presented to the city for all types of improvements. IE will utilize the codes, standards, regulations, which have been adopted by the city, in addition to the Standard Specifications for Public Works Construction, which is the standard norm, used by major municipalities. IE continues to update and incorporate new technologies used in our design and construction practices. IE staff are active members of the ASCE, APWA and other organizations, which always strive to introduce and promote new methods and standards for public works projects throughout the country. • IE will prepare a comprehensive set of technical specifications in addition to a complete list of bid items required to thoroughly cover items described in the project plans and bidding instructions. IE will review and incorporate on every contract, the general conditions and special provisions in the bid package, to address, labor compliance, Federal Grant Funding provisions and any other special requirement that the city might have.

In some cases , IE will include Additive Alternatives for items on the bids, that the city may want to include, either as additional work items, or pricing for inclusion of certain items that the city may want to add to the scope of the project.

IE will prepare construction cost estimates for verification of project budget and assistance during the contractors bidding process. Measurement of units will be contained in the specifications with additional details for lump sum items, as necessary.

Unit prices will be derived from current bid information on similar work within the project area. • IE will prepare PS&E submittal package for city’s review at certain milestones, depending on the scope of work for each project. The PS&E deliverables are scheduled for delivery at 35%, 65%, 95% and 100% packages. A final set of signed Mylar plans, along with specifications and estimates, will be submitted to the city for bidding purposes. • Upon completion of PS&E, IE will coordinate with the City Clerk Office’s to present the final design to City Council for approval. All council meeting agendas and staff reports will be coordinated through the city’s Project Manager. • In addition to the initial Project Definition and Program Development Meetings, continuous coordination and updates will be required between the design team, the city’s Project Manager and other stakeholders, including utility agencies, permitting agencies, and any other funding source coordinators. Progress reports will be provided at appropriate intervals and, as necessary, to document project status.
• IE will prepare as - built plans based on the red mark - up plans provided by the contractor at the end of construction and submits them to the city for their retention and filing. 334
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 13 Approach to the Project (cont.)

TRAFFIC ENGINEERING
Providing traffic engineering services is one of IE’s core disciplines. We have the know - how to produce warrants assessments, traffic signal design and synchronization, system integration, construction management of signal installation, and funding opportunities. Our team is knowledgeable in standards and guidelines for Caltrans, the County of Los Angeles, the California Manual on Uniform Traffic Control Devices (CA - MUTCD) and other relevant traffic standards and methodologies, including the State of California vehicle code. Our extensive traffic engineering knowledge sharply honed technical skills, and decades of combined experience make us invaluable to our client cities as we help them keep the roads safer and assist them with implementing new technologies and renovations.

Traffic Engineering Studies, Designs and Surveys
The team that we are proposing for the city possess all the qualifications required in the RFP to prepare and supervise the production of all manner of traffic studies, including traffic impact analysis, warrant studies for new traffic signals, all - way stop controls and left - turn phasing analyses, various street improvement and traffic impact mitigations, accident analysis reports, and engineering and traffic surveys. All of which is needed to update the city’s posted speed limits per California Manual of Traffic Control Devices (CA - MUTCD). Our proposed staff of professionally registered traffic engineers and civil engineers will also prepare design plans for street improvements in addition to reviewing designs prepared by other public or private consultants.

For traffic studies prepared for public and private projects, our professionally registered traffic engineers and transportation planners will review and comment on traffic studies at the start of the study’s scope of work determination phase. Our experienced team have prepared countless traffic study reports and are highly knowledgeable of local and regional guidelines and policy / procedures, ensuring a thorough and quality report. Our traffic engineer will review the study for the data, assumptions and methodology used and completeness per scope. The traffic engineer will manually check critical calculations in addition to employing the latest traffic engineering software available when needed. A revised study that addresses precise comments will be recommended to be prepared, if needed. The final review will be completed upon submittal of any revised study and a recommendation letter will be prepared for the study’s approval or corrections within one week. Our traffic engineer will also represent the city in any community meetings, planning commission and City Council meetings and hearings on projects. Our team of professionals have experience in all aspects of traffic engineering listed below.

Traffic Signal Design and Modification Traffic / Transportation Feasibility Transportation Planning Traffic Signal Synchronization Traffic Impact Analysis (TIA) Local Transportation Traffic Signal Construction Management ITS Development, Design and Implementation Regional Transportation Community and Neighborhood Traffic Issues Safety Studies Multi - Modal Transportation Plans CIP Project Development, Design and Implementation School Route Analysis Staff Augmentation Traffic Studies Traffic Engineering City Traffic Engineer Speed Survey Transportation Planning Assistant Traffic Engineer EIR Studies / CEQA / NEPA MTA Call - For - Projects Process (Funding) Overflow Workload Traffic Circulation Studies Traffic Engineering Design Rail Grade Crossing Project Reports (PR) Traffic Signal and System Design ITS Design and Implementation Project Study Reports (PSR) Interconnect Design Traffic Control and Detour Plans Traffic Calming Studies Signing and Striping Bike Lane Assessment & Improvements 335
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 14 Approach to the Project (cont.)
Traffic Warrant Studies
Our team of registered traffic engineer can be on hand to perform warrant studies in conformance with all federal, state, and local regulations, CA - MUTCD requirements and per city standards, ordinances and regulations for traffic signal or stop sign installations. They conduct a comprehensive field investigation and collect all field data required for each type of warrant. This data typically includes collision history from Statewide Integrated Traffic Records System (SWITRS) of California Highway Patrol and Transportation Injury Mapping System (TIMS) of University of California at Berkeley. Additionally, 24 - hour average daily traffic (ADT) volumes, peak - period turn movement counts of vehicular, pedestrian and bicyclist traffic and vehicular traffic speed data can also be collected.

After a thorough review, our team will determine if the relevant warrants satisfy signal or stop sign controls. After analyzing all relevant data, the warrant study will be prepared. All associated reports, documents, plans and maps will include the registered engineer’s stamp and wet signature to certify the accuracy and adequacy of the study. Upon completion, our traffic engineer will present the studies to the appropriate department, commission, or council meeting. Following the presentation of our findings, our traffic engineer will proceed to prepare design plans, cost estimates and specifications for any improvements upon direction from city’s Traffic Engineer.

Intersection Design Plans, Including Traffic Signal Plan When creating intersection design plans and traffic signal plans, our registered traffic engineers will collect all relevant traffic control needs and roadway safety information required for specific intersections prior to the preparation of traffic signal, street improvement and traffic control and detour plans. The CA - MUTCD and other Caltrans Standard Plans and Standard Specifications will be adhered to, and the final plans will have our registered engineer’s stamp and wet signature to certify the accuracy and adequacy.

Staff Reports for City Council or Planning Commission Meetings Our team of engineers prepare traffic - related staff reports for presentation at Planning Commission and City Council meetings as directed by client Cities. The reports contain data and information gathered from staff records and collected by our personnel. The reports are submitted to the Cities two weeks prior to any meetings, offering ample time for the Planning Commission and City Council members to thoroughly review the information in advance of the meetings. Our team is available to answer any questions posed by the city regarding these reports and attend the meetings to address any public comments.

Meetings with Public Works Staff and Other City Departments Our proposed Project Manager, in addition to our knowledgeable staff, can be available to meet with city’ public works staff and any other department staff to provide timely information and promptly respond to community concerns while addressing public inquiries. Our team can provide professional and pragmatic recommendations for traffic and parking improvements to meet the city’s long - term needs while addressing short - term concerns.

Meetings with Project Applicants and Developer
Our professionally registered Traffic Engineer (TE), or another appropriate engineer, can be available to meet with the applicant or developer’s representatives of any development projects, per direction of the city; and we will provide professional input and written comments on the items discussed in the meetings.

Attendance at the City’s D / ERC, Planning Commission or City Council Meetings If requested, we can have our Traffic Engineer attend the city’s scheduled Development / Environmental Review Committee meetings as well as Planning Commission and City Council meetings, and we will actively participate and provide written comments on traffic engineering items discussed. 336
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 15 Approach to the Project (cont.)
Meetings with the Staff of SBCTA and Caltrans
Our Traffic Engineer can attend meetings held at regional agencies - such as San Bernardino County Transportation Authority and Caltrans District 8 - as a representative of the city. We will provide the city professional input and written comments on the items discussed in the meetings.

Review and Comments on Plans and Studies by Others
Our professionally registered Traffic Engineer and transportation planners can review and comment on traffic studies prepared for public and private projects. They have prepared numerous traffic studies and are well - versed with all local and regional guidelines and policies and procedures, including the latest State - mandated CEQA - required Vehicle Miles Traveled (VMT) analysis procedures (per SB 743) for Transportation Impacts determination. Our team can outline all key requirements and issues to be addressed in the study and clearly communicate the requirements to the applicant to ensure all expectations are fully met when the study is delivered for review. The Traffic Engineer can then prepare a list of precise comments to be addressed in a revised study, if needed. The final review can be completed upon submittal of any revised study and a recommendation letter can be prepared for the study’s approval or corrections within a week. Our Traffic Engineer can also represent the city in any community meetings, Planning Commission, and City Council meetings or hearings regarding the reports.

Determine Need for Traffic Controls and Recommendations for Traffic Ordinances, Resolutions and Traffic Impact Mitigation
Our traffic engineer can review and determine needs for specific traffic controls at intersections or street segments, including traffic signals, traffic and parking control signs and markings, posting of speed control signs, etc. Our traffic engineer can prepare recommendations for any traffic ordinance or City Council or Planning Commission resolutions, as requested. Our traffic engineer can also review any traffic impact mitigation plans, strategies or programs proposed by private developers. The engineer can prepare written recommendations on the effectiveness and implementation of the proposed plans, strategies, and programs.

Other Duties as Assigned by City Traffic Engineer
Our Traffic Engineer can be available to assist the city’s Traffic Engineer as requested for any traffic engineering project. The description of some typical additional services IE provide are shown in the following:

GIS Mapping
Our assigned civil engineer is an experienced design engineer and highly skilled at creating GIS data and maps. Our GIS mapping services can create databases and exhibits of citywide roadway networks for application in Pavement Management System (PMS) reports, citywide bus shelter locations, and other location maps. For PMS report map exhibits, citywide inventories of existing roadways can be color - coded to differentiate varying roadway conditions based on pavement condition index (PCI) scores. Our GIS staff regularly use the respective County’s GIS Data Portal to download and manipulate data on ArcMap for the purpose of locating underground utilities as well as verifying right - of - way and parcel information.

Conceptual Engineering and Presentation for Grants and Regional Transportation Planning IE staff have extensive project - specific experience in writing grant applications and securing funding for municipalities and local agencies over the years. We can prepare engineering conceptual plans, reports and documents under city’s direction and guidance for submittal and presentations to grant agencies, including SBCTA, Caltrans, Southern California Association of Governments (SCAG) and other regional transportation planning agencies. 337
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 16 Approach to the Project (cont.)
Traffic Control Plans for Capital Improvement Projects
IE staff have a proven record of successfully managing capital improvement projects and other roadway and traffic engineering construction projects for several Southern California cities and municipalities. Our registered Traffic Engineer has prepared numerous traffic control and detour plans for construction projects while prioritizing traffic and pedestrian convenience and safety. The Traffic Engineer assigned to these tasks for the city will promptly collect all relevant traffic control needs and roadway safety information upon a request from the city and prepare the appropriate plans for application to the specific projects. The CA - MUTCD and Caltrans Standard Plans and Standard Specifications will be used in preparing these plans. The plans will have the registered engineer’s stamp and wet signature certifying accuracy and adequacy.

UTILITY ENGINEERING
It is our understanding that the City of Lynwood is soliciting proposals from municipal engineering consultants to provide engineering design services for water, sewer, and possibly storm drain utility projects on an as - needed basis. Many of the anticipated projects are from the city’s CIP while other projects outside this program have also been identified. IE specializes in providing engineering and construction management services on on - call contracts. We know how to mobilize quickly to provide a full spectrum of services required. We understand and will provide all services for the city’s water, wastewater, and stormwater projects, including environmental reporting and compliance, traffic and detour engineering, surveying, mapping, legal descriptions, staking, geotechnical, and structural services. The City of Lynwood is committed to providing exemplary utility services to the community and, therefore, the consultant selected must have the necessary experience and qualification to be considered.

IE will serve as an extension to the city staff. This includes meeting with city project representatives regularly and remaining in constant communication with them to ensure successful and timely delivery of the project. Bi - Weekly Project Status Reports will be issued by IE. Meetings, as necessary, will be conducted for which agenda notices will be distributed at least two working days before each meeting. Meeting minutes will be distributed within one week of the meeting identifying action items assignment and due dates. The Bi - Weekly Project Status Reports will identify tasks completed and planned, issues to be resolved, project schedule update, and project trends. These reports will serve as a primary tool in monitoring project progress and keeping the city’s staff informed.

IE also intends to meet and / or communicate with city staff, city administration and Council, utility companies, Caltrans, and / or other agencies (as necessary) to coordinate the project design. For each meeting an agenda and notes will be prepared by IE to summarize issues discussed and for distribution to city and others at each meeting.

Approach
IE’s approach to project management and production is based on a strong commitment to total quality assurance. The design approach follows a proven path of work elements and tasks ensuring a successful project. Working directly with the city’s Project Manager, our Senior Engineer, Christopher Ley, will lead the Utility Design team through the entire design production.

Upon issuance of the Notice to Proceed, Christopher will review the requirements, prepare a work plan and make team assignments for maximum efficiency of resources. Christopher will assume the role of coordinator and will develop a project management plan for the project for IE’s staff and for our survey subconsultant. The project management plan will include the development of a comprehensive management and control system, which will ensure the project is completed on time and within budget. To ensure accurate monitoring and tracking of plans, revisions and progress, a document tracking and control system will be established. The steps to project development and completion will follow the steps outlined here. 338
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 17 Approach to the Project (cont.)
Task 1: Project Meetings
IE will schedule a kickoff meeting with city staff to initiate the project. At that meeting, coordination and scheduling between IE and the city will be discussed and the methods of communication decided upon. The city’s goals and objectives will be reviewed. IE will review information provided by the city prior to the meeting and will discuss any questions or clarifications needed. A project time schedule will be reviewed with the city and incorporated into a final time schedule to be prepared by IE. Subsequent monthly progress / submittal meeting dates will be agreed upon. IE will be responsible for preparing the agendas and minutes of each meeting. At the subsequent meetings, IE will report on project progress, both in writing and orally. Forthcoming activities and anticipated deliverables will be discussed at these meetings, as well as the city’s comments on documents previously submitted by IE.

Task 2: Research
The IE team will conduct research of available information, maps, data on the existing sewer system, and of any previous hydraulic analysis and modeling, including the most recent Master Plan for the project area. In addition, other factors will be reviewed and addressed including, but not limited to a review of tentative construction phasing provided by the city to evaluate and provide any recommendations on the most efficient and cost - effective contracting strategy, especially in areas that have a high potential for conflicts (e.g., near high traffic areas); traffic control, particularly on main arterial streets and where access will be an issue; and research on possible conflicts with existing utilities and other services (e.g., trash pickup).

Task 3: Modeling
As needed, IE will provide modeling based on assembled information on the existing system. Results of the modeling and recommendations by IE for project solutions will then be submitted to the city for review and approval. IE will be using Hydra for all sewer system and storm drain modeling work and production of data tabulations.

Task 4: Surveying
Upon receipt of the city’s Notice to Proceed, the IE surveyor will begin field survey work for all open - cut remove - and - replace segments. All possible alignments will be surveyed and base maps will be prepared and submitted in AutoCAD format. Surveying will include dipping all utilities manholes and will also take into account curbs and gutters, sidewalks, rights - of - way, water, street lights / pull boxes, retaining walls, structures, and catch basins. All local physical culture features will be surveyed for preparation and design of the plans that will be needed for construction of the new or replacement water, storm drain, or sewer lines in the existing paved streets.

Task 5: Geotechnical
Upon receipt of the Notice to Proceed, the geotechnical investigation work will begin with soil borings on all open - cut remove - and - replace segments to determine thickness and condition of street pavements and the sub - base soil conditions.

Borings will be drilled to a minimum of three ft deeper than the lowest required invert. A report on the investigation findings will be prepared and submitted to the city for review at the 30% - level of submittal. The report will contain recommendations for construction of the water, storm drain, or sewer lines by open - shored trenching and, where appropriate, trench - less construction and replacement of the street section to meet city standards. The report will also include recommendations on pipe bedding for the pipe to be used.

Task 6: Utility and Other Agency Coordination (Caltrans, etc.) Upon initiation of the surveying and geotechnical work, IE will begin the utility coordination process of notifying the known utilities and other substructure owners of the project and requesting plans for their facilities. Once alignments of water, storm drain, or sewer lines have been verified, the utilities / substructures will be plotted to determine if any conflicts exist within the preliminary route and alignment. With the alignment plans showing any potential utility / substructure, the preliminary plans will be submitted to the city as plans at the 60% - level of completion. Should there be any utility / substructure conflicts that cannot be resolved by design efforts, meeting(s) and discussions will be held with the utility / substructure owners to obtain resolution of the conflict.
339
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 18 Approach to the Project (cont.)
Task 7: Environmental
The IE environmental specialist, B / BEP , will review and assess the proposed project by use of the California Environmental Quality Act (CEQA), National Environmental Protection Act (NEPA), and city environmental guidelines to identify any specific items of environmental concern. B / BEP will discuss the environmental assessment with city project staff and city personnel responsible for environmental matters and policies. Based on the city’s review and determination, the appropriate document will be drafted and submitted at the 30% - level of submittal. Note: should the city - required document be at the level of an Environmental Impact Report, IE will require a fee adjustment to prepare the EIR and to process and circulate the EIR. For lower levels of documents, B / BEP will prepare the necessary document for the proposed fee and, after circulation, will have it certified and adopted by the city.

Task 8: Potholing (if needed)
IE uses C - Below to perform any potholing services on a time - and - material cost basis once the need for identification data is determined. IE would prepare a plan for potholing work and obtain city approval to proceed. C - Below would obtain all needed street excavation permits and prepare and submit Traffic Control Plans to the city, as needed. C - Below is a highly experienced utility contractor that operates throughout the southland.

Task 9: Preliminary Design – 60% PS&E
At this point in the design process, IE will submit a 60% package of documents for the city’s review. The following is a list of the documents to be included.
• Survey base maps
• Geotechnical report
• Modeling report
• Utility coordination report
• Traffic control plans
• Temporary and Permanent Signing and Striping Plans
• Preliminary plans, specifications, and estimated cost of construction (PS&E) • Preliminary construction staging plan
The specifications will be prepared by use of city standards and boilerplate for construction of water or sewer pipe along the recommended alignment (previously reviewed by the city). The traffic control plans will be prepared by IE unless otherwise directed by the city.

IE will apply for and obtain any needed permits from other agencies such as Caltrans, Los Angeles County, Sanitation Districts of the Los Angeles County, Los Angeles Regional Water Quality Control Board, and other agencies, as needed.

If utility relocations are needed, a time allotment will be added to the construction schedule at this submission.

Task 10: Design - 100% PS&E
Upon receipt of the city’s review comments on the 60% PS&E and other related documents, IE will proceed to incorporate any needed changes and bring the PS&E package up to a level of 90% completion for submittal to the city.

Task 11: Design - Final 100% PS&E
Upon incorporation of city review comments on the 100% - level PS&E, the PS&E will be finalized and originals in either vellum or Mylar will be signed by the IE Project Manager. The final environmental document will be certified. 340
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 19 Approach to the Project (cont.)
Task 12: Assistance During Bidding
IE will provide bidding assistance to the city including preparing city use responses to any Requests for Information (RFIs) from prospective bidders. As needed and directed by the city, IE will prepare addenda of project changes and notices to bidders for issuance by the city. Upon receipt of bids, IE will review the bids and can perform bid analysis or normal assistance services such as checking of references for the city.

Task 13: Construction Assistance / Observations (Optional) As requested by the city, IE can review contractor’s material submittals, traffic control plans, etc. IE can also make periodic field observations of construction progress and provide reports to the city.

Enhancements or Innovations
There are a number of new and innovative design procedures that we could consider for various utilities improvement projects in the city. The following presents a brief list of some considerations. • 3 - dimensional (3 - D) surveying and laser scanning of existing surface structures to provide a comprehensive design considering all possible conflicts with existing surface improvements. • Underground locating, detection, and mapping to verify existing underground utilities locations, depth, and alignments. • Design of the proposed utilities in 3 - D so any possible conflict with the existing utilities or other proposed utilities will be avoided during the design phase and prior to construction. • Utilizing the newest construction methods for utilities to minimize impacts on surface improvements, traffic, businesses, and residents, such as pipe jacking, auger boring, and micro tunneling for trenchless installation of utilities. • Utilizing the latest methods for trenchless sewer repairs to minimize construction cost and duration, such as sliplining, pipelining, pipebursting and cured - in - place pipe.

Project Controls
Upon selection for an On - Call Utility Engineering contract and award of a project, the Project Manager establishes the budget for the project and hours needed for each staff member to complete the assigned tasks. Every week it is the Project Manager’s responsibility to review staff hours in correlation to percent of completion of each task and assignment. Every month, attached to the billing, the city will receive a report outlining staff hours and percent of completion and these relationships to the authorized budget. The IE Project Manager monitors accomplishments and budgets. Schedule and budget are two very critical responsibilities of the Project Manager. At 30% completion, a cost estimate of construction will be provided to the city to ensure that the project cost is in line with the budget assumed for that project. Also, at 60% and 100% cost estimates will ensure the city has adequate funds to bidding the construction plan.

On the third Tuesday of every month, all Project Managers must report their project budgets and schedules to the IE Director of Operations. It is the Director’s responsibility to facilitate operation needs of the Project Managers.

Quality Assurance / Quality Control
Quality Assurance and Quality Control (QA / QC) are top priority for IE. Our QA / QC practice involves a comprehensive process to ensure delivery of quality product and services to your satisfaction. The Program Manager, together with a designated QA / QC team, provides the leadership and guidance to obtain the comprehensive and complete design documents of the city’s expected quality, meeting all industry standards. These documents will result in minimal claims and RFIs during construction phase. Key elements of our quality control are the assignment of skilled and experienced personnel, effective communications, and monitoring. The quality control process includes the following:
• Assignment of skilled professionals instituting a comprehensive and interactive orientation on the project goals, and the means of achieving these goals.
341
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 20 Approach to the Project (cont.)
• Daily contact by the Project Manager with each on - going activity to provide support and guidance, to maintain focus and momentum, and to monitor the quality of work.
• Maintaining regularly scheduled project staff meetings for reviewing work status, reviewing technical elements of the project, coordinating and interfacing of activities, reviewing budget parameters, and discussing upcoming activities and responsibilities.
• Internal (peer review) audits of municipal services for quality, accuracy, and completeness. • Strictly and rigorously following IE - developed QA / QC standards and guidelines. • Review by the Program Manager prior to submittal to assure services meet all standards and codes, project goals and objectives, and contract requirements.
• Design QA / QC will be carried out by our highly experienced and licensed professional civil engineers. • The constructability review during the design phase will be carried out by our highly experienced construction managers and inspectors.

CONSTRUCTION MANAGEMENT AND SUPPORT SERVICES
Pre Construction Phase Services
IE’s team has the advantage of having all services under one umbrella. Our construction managers work with our civil design group throughout the entire design development process and have multiple opportunities to conduct in - house constructability reviews. This approach has allowed our team to prepare and deliver quality design and successful projects, with least amount of change orders encountered during construction. The following are some of the key issues that our construction management team will ensure to preview, prior to the completion of final design on every project that we manage.

Project Scope and Understanding:

We have studied the city’s 5 - year CIP program and budgets. We are glad to inform the city that IE has all the necessary expertise and experience in each of the 7 categories of projects listed in the CIP program. Our construction management and inspection staff have the right experience in each one of the categories, listed on the city’s CIP list. The following table shows our collective experience with the City of Lynwood and other municipalities, where we have delivered similar services as listed on the City of Lynwood’s CIP program.
342
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 21 Approach to the Project (cont.)
CM and Inspection Mobilization
For every category of the project that IE has been assigned to, will arrange a kick - off meeting with the city staff, the designers, and key stakeholders to learn more about the project background and any pertinent information that the CM team should know about. In our experience, coordination with various city staff and departments in addition to the outside influencers is key to a successful start. Following the city’s directions, we will establish the main contact matrix, with roles and responsibilities and chain of command for each phase of the project. As a standard practice, IE team including the construction manager, inspectors and all the subconsultants will conduct a full review of the plans, specifications, and other contract and construction - related documents.

ADA Compliance
Some of the other reviews by the IE team during the pre - construction phase will include evaluation of the project scope to see if the city will desire to update and repair such items as ADA curb ramps, ADA facility compliance, curb / gutter and sidewalk evaluation and repairs. Other services can include energy audits, solar power, EV charging stations, and other types of specialty projects. Working on similar projects, we have found that inclusion of such items will benefit the city and it will cut down on long - term costs.

Client
Water
Improvements
Street
Improvements
Park / Recreation
Improvements
Sewer
Improvements
Facilities
Improvements
Traffic
Improvements
Sidewalk
Improvements
City of Baldwin Park       
City of Bell Gardens       
City of Brea    
City of Compton   
City of El Monte       
City of Glendale     
City of Glendora 
City of Hawaiian Gardens       
City of Huntington Park       
City of La Palma 
City of Lawndale  
City of Lynwood       
City of Manhattan Beach    
City of Maywood     
City of Montebello       
City of Pico Rivera   
City of San Bernardino   
City of Villa Park   
343
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 22 Approach to the Project (cont.)
Cost Estimating
IE will review the plans and the specifications and the Engineer’s Estimates and the Bid Schedules to determine the cost based on the latest unit pricing and bids received on other recent projects. IE will compare these estimates against the city’s standing budget and schedule and will make recommendations for making adjustments on the costs and budgets if the city deems them necessary. IE team understands the challenges with the recent bidding environment and sees this step as a key element of the pre - construction phase services.

Market Conditions
One of the challenges currently facing projects is the cost escalation and availability of materials. The current market condition and price escalations have made it more challenging for Cities to establish appropriate budgets and timelines for delivery of various CIP projects. The bidding environment has been very dynamic over the last few years, due to many uncertainties over price escalations and availability of materials. This situation has improved slightly, but early determination of long - lead materials and equipment is needed for each project to ensure that the projects will not be impacted or delayed.

After understanding the city’s needs and priorities, IE will review and adjust durations for each activity and milestones to paint a true picture of the project delivery schedule, based on the current market conditions. If necessary, IE will prepare and recommend early material purchasing and delivery separately from the main contract to avoid potential delays during the construction. IE will also review the project delivery schedule and cost estimates to determine any issues, prior to contractors bidding on the project. We will make sure that our schedules are realistic and all the bid items on the bid schedules have been vetted and are complete and accurate.

Right - of - Way
It is critical to identify and resolve any right - of - way issues that may exist on any type of CIP projects. There are many ways to determine if there are ROW issues on a project, starting with a review of available as - built plans, County maps, GIS maps, title report search and conducting a boundary / property survey of the properties in question. IE team can work with the city during the pre - construction phase to identify and clarify any potential issues on the property boundaries and prepare the appropriate legal documents, such as easements, dedications, and lot line adjustments. As part of the IE team, our subconsultant, Epic Land Solutions, is also ready to assist in case property appraisals and acquisitions are needed.

Utility Conflicts
It is very important to identify and show all the existing utilities on the plans and bid documents. It is as important to include provisions in the contract documents for the contractor to conduct potholing of all the utilities within 5 - ft of the proposed work, after the utilities have been marked and in advance of the start of any excavation work. We will review the contract documents to ensure that there are safeguards to protect the city from claims when encountering unforeseen conditions during construction. We can introduce various types of allowances for items that the contractor may encounter during the construction for removal of unknown utilities and for special types of shoring that may be required.

Unforeseen Soil Conditions
Another provision necessary for all underground excavation is to identify the soil’s conditions and types during the design, so that appropriate shoring methods can be included in the bid documents. This will require an investigation of the site by the construction management team to review and evaluate the field conditions, by first looking at previous soil’s reports conducted near the project site, and then formulate a geotechnical investigation to address the site conditions. We have performed similar types of investigations for other Cities and found that this approach will avoid potential claims on unknown field conditions by the contractors.

We use an electronic project
management system that will allow
seamless transfer of information
between the project team, including
architects, engineers, construction
management team and contractor.
344
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 23 Approach to the Project (cont.)
Bid and Award
We are happy to see that the city is utilizing Planetbids for managing the bidding and award process. This system has worked very well in the past on many other projects, ensuring that all questions, addenda, and project information are processed quickly and accurately. This system also reduces the chances of information not being delivered to potential bidders. After the project is uploaded on Planetbids, and once questions are received from the bidders, IE will determine the responsible parties for providing proper responses. In case design questions are received, the engineer of the record, or the architect will be informed to provide proper responses. Regarding questions and clarifications related to the budget and schedules and other administrative questions, the city will be contacted to get the proper responses. In each case, IE will make sure to secure a proper response to each question received and to prepare and upload the addendum quickly and completely.

CONSTRUCTION PHASE SERVICES
Managing projects over the last 30 years, we have learned that each project is unique and requires a different approach, however, there are certain traits, which are common to most projects and should be considered and examined. The following is a general work plan based on our understanding of the city’s needs for managing each type of project listed in the RFP and on the city’s CIP list:

Our approach to management of construction will be to collaborate and coordinate all our activities with the city’s project manager and other stakeholders and at the same time introduce many of the lessons learned from our past projects and the experience that we have gained working on the City of Lynwood’s projects. Prior to start of any construction project and / or activity, IE will meet with the city to formulate a work plan and a resource allocation matrix for each individual project to build a robust team to administer and manage construction contracts, in accordance with the city’s needs and budget.

IE will also establish the individual needs of the project for other necessary services, such as field survey, geotechnical investigations, materials testing, SWPPP , NPDES Permitting and monitoring, environmental investigations and testing, deputy inspections and other specialty items as required. IE will arrange and organize the CM team encompassing specialty services, for materials testing, deputy inspections, prior to awarding a contract. The following is a general work plan based on our understanding of the city’s needs for managing each type of projects listed in the RFP and on the city’s CIP list:
• Filing Systems - IE will set up an electronic filing system (CMIS), to address all funding requirements by the Federal, State, County and OCTA for securing grants and outside fundings. IE will ensure to follow all grants funding requirements and will monitor contractor’s compliance with these requirements to ensure compliance with prevailing wage regulations and documentation.
• Submittals and Schedules - IE will review and process contractor’s submittals by first preparing a submittal - list for each Contract. All submittals and deliverables that are required by the contract will be logged through the IE’s electronic project management system and routed to the project’s architect and engineers for review and approval. IE will ensure that proper warranties are stipulated for certain items per the city’s needs to ensure that the maintenance and longevity of these systems are secured over the long haul.
• Pre - Construction Meeting - IE will arrange and conduct pre - Construction meetings with the Contractors, designers, inspectors and other key stakeholders. We will ensure to invite all city personnel that may be involved with the project, in addition to representatives from regulatory agencies that may be involved with permitting and grant funding. We will also request that subcontractors be present at the pre - construction meeting. We have found that it is important for the subcontractors to be also present to learn firsthand about the conditions on the project and the overall scope of work. IE will arrange for a weekly progress meeting, to review the project status, request for information (RFI) log, change orders, project issues, etc. The minutes for these meetings will be prepared within 24 hours of the meeting, to ensure that all parties are aware of the project issues and any action items that were identified during these meetings. 345
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 24 Approach to the Project (cont.)
• Inspection and Field Activities - Daily construction logs shall be provided for the city review on the IE’s web - based virtual project management software. The project inspector will review construction progress schedules on a regular basis to verify that the project is on schedule and on track with project milestones. If the project falls behind, IE will identify the project deficiencies and ask the contractor for recovery schedules to ensure that corrective actions are taken to bring projects back on schedule. We have vast experience with installing utility work and will monitor the contractor’s excavation work to prevent and minimize utility conflict delays and potential need for utility relocations. We will achieve this by conducting potholing, which will be required by the contract documents, and by a thorough review of the as - build drawings. We will coordinate field meetings with the utility agencies and will make sure that they are present during the excavation, near their utility lines. IE will prepare and submit to contractor a “Weekly Statement of Calendar / Working Days” report to ensure that the Contractor is fully aware of the schedule and the critical path activities, that may be in jeopardy.
• Health and Safety - We at IE take safety very seriously. We know that even one incident on the project will taint the project.

As a standard practice, at the beginning of each meeting, we draw attention to a safety moment. This is to ensure that all parties and the construction team make safety on the job a priority. We believe that safety must be built into the culture of the construction team, and it must be the underlying condition for conducting any type of construction work. IE will make sure that the latest CAL - OSHA provisions have been incorporated into the contract documents and we will monitor the job daily to ensure that all safety precautions have been placed at the job site every day. At the pre - construction meetings, IE will ask to see the Contractor’s Health and Safety plan and makes sure that a Safety Offices has been identified by the Contractor, in addition to the subcontractors.
• Quality Control and Materials Testing - To control the quality of work on any construction project, a few provisions must be built into the Contract Documents. In addition to the requirements by the Standard Specifications for Public Works Construction (Green Book), which sets the minimum requirements for controlling the quality at the job site, IE will evaluate and determine individual needs of the projects for a robust QA / QC program. These provisions will need to be written into the contract documents, so that the contractors provide an adequate testing program, necessary for meeting the requirements of the project. As part of our monthly reporting, a section will be dedicated to the QA / QC program, summarizing the testing and a review of the contractor’s performance, on a regular basis. IE team will evaluate the contractor’s performance and will recommend changes as necessary. IE inspectors are provided with the latest technology for documenting and reporting daily activities and are dedicated and trained to make sure the construction work is being conducted in a safe and expeditious manner.

POST–CONSTRUCTION SERVICES
IE will start planning on project close - out weeks before the completion of the project. This is to ensure that the contractor is aware of the city’s expectations for compiling the work and to allow ample time for any type of commissioning, testing, and balancing that may be required. In addition, the project may need staff training, which requires advanced planning. The close - out activities will include final inspection / walk through with the city staff, maintenance / service personnel and the project’s architect / design consultant. IE will issue a preliminary punch - list to put the contractor on notice of any outstanding item, followed by a final punch list, including schedule for punch list completion. IE will monitor the repairs and follow through “Other inspection activities include
conducting field construction employee
interviews to comply with Equal Employment
Opportunity Law and Davis Bacon Act. ”
“Control of the quality at the job - site also
requires a true and dedicated inspection staff.

IE will provide daily inspection for projects
by introducing a qualified inspector, who has
many years of experience with public works
and CIP construction projects. “
346
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 25 Approach to the Project (cont.)
with the contractor, until all items on the punch list are 100% complete. IE will gather and transmit all required guarantees, certifications, affidavits, leases, easement deeds, operating and maintenance manuals, warranties, and other documents as stipulated in contract documents for submittal to the city.

APPROACH TO MANAGING RESOURCES
Our approach to management of resources is first to work with the city to devise a staffing plan based on the city’s unique and precise needs, followed by keen and proactive management to deliver every project and task on time and on budget.

Our VP for Construction Management Services, Mr. Sepahi will first meet with the city to learn about the unique needs of the project, the priorities, budgets and schedules. He will then prepare a preliminary staffing plan and a cost proposal for providing CM and inspection services to present to the city’s project manager. As every project is different and requires a different approach, we will provide a unique plan to address the needs of the project within the city’s desired cost and budget. Our standard team makeup usually includes a part - time construction manager, a full - time inspector, complemented by an array of experts in all aspects of construction, only when they are needed. The city will benefit from IE’s flexibility to mobilize and de - mobilize project staff quickly, and efficiently. . We have included seasoned construction managers and inspectors to assist the city with any type of CM services that may be needed. Our Director of Construction Manager will oversee and monitor the construction activities, to ensure that the CM team has the resources and to guide the team, when outside help may be needed.

The IE team will be complemented by Associated Soils Engineering, Inc. (ASE) for geotechnical investigations and materials testing, in addition to Dennis Janda, Inc. (DJI), boundary and property surveying work, needed on establishing property lines, easements and dedications.

OTHER SERVICES
The following are optional services IE can provide to the City of Lynwood. We have included them into this proposal in case such services are required by the city.

Program Management
Our Program Management team will ensure full cooperation of its assigned program with other consultant teams and all stakeholders. We will be engaged to contribute to the completion of a successful project through meeting the project goals, schedule deadlines, budget management, monitoring and execution of specific program requirements. Program Management services the IE team provides include the following:
• Coordination and Master Schedule.
• Consultant Contract Selection Process.
• Preparation of Contacts.
• Monitor Contract Services.
• Strategic Planning.
• Fiscal Budget Management.
• Fund Administration.
• Labor Compliance.
• Program Implementation.
• Staff Augmentation.
347
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 26 Approach to the Project (cont.)
Architectural and Facilities Design
iArch’s approach to this type of project starts with a detailed site visit with the client and reviewing the proposed scope of work and improvements, ensuring a complete agreement by the client for the proposed improvements. Once iArch is done with the site visit, a scope of work is prepared, a detailed work plan and schedule are to be shared with the client for concurrence. The said work plan will include all the milestones and critical deadlines to ensure that the project will stay on schedule and within budget. Upon agreement between parties of the scope and approach and schedule, iArch will hold weekly project status report in house and we’ll prepare updates based on the progress of our work and submit to the city bi - weekly. Additionally, iArch will request to meet with this city’s project manager, at least once a month to share the progress of the work up - to - date and receive any additional instructions or modification that may maybe required by the city. Based on our recent experiences with other similar restroom upgrade facilities, the details of the proposed improvement need to be shared with the city on an ongoing basis to ensure that the final design plans for the renovation and remodeling of the restrooms reflect city’s desire and it accomplishes to stay within the budget and be compliant with the ADA requirements.

Additionally, iArch will put each set of plans through a Constructability Review and Quality Control Review. The purpose of these reviews is to ensure the design plan can be built with the material identified and also it is a complete set to ensure minimizing any possible change orders.

Initial Task: Concept Plans
The primary objective of the project is to prepare a complete PS&E (plans, specifications, and estimates) approved by all involved jurisdictional and regulatory agencies and that will be ready for construction bidding for the improvements. After the kickoff meeting for the project, iArch will prepare a concept for the renovation and remodeling of said facilities. The concept developed for the renovation and remodeling would either be based on our field measurements of the building and your directions during the kickoff meeting. The concept will adhere to the ADA requirements. Upon the city’s review of the concept and any revisions, iArch will update the concept and after city’s concurrence, iArch will prepare renderings of the said approved concepts for the city’s review and approval.

Task 1: Project Management
a. iArch will attend a pre - design (kickoff ) meeting with city staff after the award of the contract to conduct introductions, discuss scope of work, information needed from various city departments, overall schedule, and the implementation process.
b. iArch will coordinate bi - weekly progress conference calls with city staff to update the city of the project progress, and schedule status. iArch will notify the city of any design issues encountered including all options to address. c. iArch will schedule meetings with the city staff to review the preliminary design, 60%, 90% and 100% submittals. d. iArch will prepare and provide a detailed project schedule with continuous updates, and an executive summary of project status that will be submitted with each monthly invoice. e. iArch will be vigilant of all the tasks involved with the design and make adjustments as necessary to meet the project schedule.

Task 2: Preliminary Engineering
a. Research and Base Map: iArch will review the base data documents including as - built improvement plans, utility information, survey information, and other available record data to create the base maps. b. Field Survey: iArch will conduct necessary field surveys to assess existing conditions of the project area. c. Preliminary Design Plans: Based on the information gathered and the city’s input, iArch will develop the preliminary design plans for the city’s review and comments.
348
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 27 Approach to the Project (cont.)
d. Project Estimate: iArch will prepare the preliminary cost estimate based on the survey and will identify any potential problem areas to address them early to ensure that construction does not get interrupted. e. Specifications: iArch will prepare the preliminary technical specifications. f. Environmental: Based on the type of project, iArch will determine if the project is categorically exempt. g. Utility Research: iArch will obtain all the available as - built drawings for the plumbing from the city and reflect them on project plans.

Task 3: Final PS&E
a. iArch will prepare the Plans, Specifications and Estimate (PS&E) and submit them to the city at 60%, 90% and 100%. b. iArch will coordinate with the city to receive the review comments at the 60%, and 90% design phases. c. Upon receiving comments from the city and other agencies with jurisdiction, iArch will modify the construction plans, specification and estimate address all the comments to be submitted to the city for final review. It is expected that the sub plans meet the city approvals for bidding purposes. d. iArch will prepare the specifications in compliance with construction plans using the latest edition of Microsoft Word for Windows. The said specification will be prepared based on all the California building code standards as well as APWA and Caltrans requirements.
e. Based on the proposed improvements, iArch will prepare the estimate which shall be prepared in spreadsheet format using Microsoft Excel.
f. As a part of the project management, iArch will develop a tracking method for the comments received and how they were addressed for the duration of the design process. The said spreadsheet will be submitted with each progress submittal.

Task 4: Bidding and Construction Support
a. During the bidding process, iArch will PROMPTLY respond to all Requests for Information (RFIs) during the project advertisement period, and iArch log all the RFI’s and responses. b. iArch will prepare the project addenda, as needed.
c. iArch will attend the pre - construction meeting, job walk, and job - site meetings when requested by the city over the course of the construction schedule (assumed five meetings). d. iArch will provide responses to the contractor’s RFIs about the plans and specifications when requested by the city. e. iArch will promptly respond to all requests and upon help with the approval of the contractor’s submittals for materials and shop drawings when requested by the city.

Task 5: Prepare Record Drawings (As - Builts)
a. During the construction, iArch will work with the contractor to ensure that all the modifications and changes are documented in a set of plans. At the end of the construction and after the punch list, iArch will use the field mark - ups to create the as - built plans to be delivered to the city. 349
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 28 Approach to the Project (cont.)
Task 6: Submittal Format of Documents
a. All submittals to city will be made via electronic submittals. b. All project submittals will be in PDF format.
c. Final submittals will be in DWG format (AutoCAD) for plans with wet signed mylars, specifications in MS Word, Estimates in Excel, and all other documents in PDF.

Planning and Development
Our Urban Planning and Development division allows us to assist our city clients with direction and planning for development and economic growth. We engage local communities to capture their needs and expectations, identify development opportunities that optimize the use of resources and meet the requirements of local codes. Planning services the IE team provides include the following:
• General Plans and Updates.
• Neighborhood Revitalization Plans.
• Current / Advance Planning.
• Corridor Studies.
• Cannabis Program Services.
• Master Planning.
• Environmental Compliance and Documentation.
• Economic Development Strategies.
• Specific Plans.

PROJECT TIMELINE AND BUDGET CONTROL
IE’s ability to maintain project control is validated by our track record of completing projects on schedule and within budget.

Our strategy for project management begins by determining ahead of time how long each leg of the project should take. To determine the time frame, IE staff begin by mapping out what needs to be done and then sequencing each milestone in the project. Our project managers then determine the maximum and minimum amount of time each event will take from start to finish using the Critical Path Method or mapping out the most important tasks in any project and using that to estimate the project completion date. This enables our team to carefully analyze which events depend on other events to allow for effective project management.

Our project managers use a set of internal control measures to control costs, provide accurate and timely invoices and to maintain the integrity of the promised schedule. These methods include approaching all projects by following these steps:
• Define the problem, then understand our clients’ expectations and preferences and project goals. • Measure key tasks of the current project and review the relevant information, such as long - lead items or tasks that involve subconsultants and their timing and costs.
• Analyze this ‘data’ to determine cause - and - effect on the project schedule and budget. • Make any necessary adjustments to address and improve the current process to meet the project goals. • Maintain control of the process to ensure that any possible deviations from the project’s goals are corrected before they result in cost or schedule creep.
350
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 29 Approach to the Project (cont.)
We take full advantage of these proven techniques because they help us better serve our clients by providing increased productivity, improved quality, reduced operation costs, higher client satisfaction and improved communication among all team members.

SPECIAL IDEAS, TECHNIQUES OR SUGGESTIONS
IE firmly believes maintaining regular communications among key city staff, stakeholders, public representatives, if any, and project task leaders is key to timely and successfully completing a project. To that end, as a part of our tasks, we regularly schedule a weekly or biweekly teleconference to discuss issues and progress concerning a project among the parties involved. In all our recent engagements with City of Lynwood projects, we conducted such regular teleconferences in a consistent manner, and this has been proven to be a truly effective strategy for the success of these projects. For as - needed, on - call assignments, we suggest that regular weekly or biweekly teleconferences be held between our project manager, key task leaders and the city’s designated staff to discuss progress status and issues on any and all ongoing projects.

QUALITY CONTROL AND QUALITY ASSURANCE PROCESS
Quality assurance and quality control (QA / QC) are top priorities for IE. To ensure the highest quality of the design, IE will implement a comprehensive QA / QC program. Our QA / QC manager, Masoud Sepahi, has extensive experience in providing and overseeing the implementation of IE’s QA / QC program. He will review the design drawings, estimates, specifications, reports, and any other documents being delivered to the city for accuracy and completeness. Our Constructability Reviewer, Arjan Idnani, will assure constructability and compliance with the City of Lynwood’s and other agency requirements. In addition, Aidan will provide daily supervision and guidance to the design team. (Please see Quality Assurance / Quality Control section for more details).

Key elements of our quality control are the assignment of skilled personnel who are experienced in the specific disciplines, effective and constant communications, and monitoring of project progress. The quality control process includes the following principles:
• Assignment of skilled professionals instituting a comprehensive and interactive orientation of the project goals and the means of achieving these goals.
• Daily contact by the Project Manager with each on - going activity to provide support and guidance, to maintain focus and momentum, and to monitor the quality of work.
• Maintaining regularly scheduled project staff meetings for reviewing work status, reviewing technical elements of the project, coordinating and interfacing of activities, reviewing budget parameters, and discussing upcoming activities and responsibilities.
• Internal (peer review) audits of municipal services for quality, accuracy, and completeness. • Strictly and rigorously following IE - developed QA / QC standards and guidelines. • Review by the Project Manager prior to submittal to assure services meet all standards and codes, project goals and objectives, and contract requirements.
• Design QA / QC are carried out by our highly experienced and licensed professional civil engineers. • Constructability reviews during the design phase are carried out by our experienced construction managers and inspectors. 351
04 Project Experience
352
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 30 Client
City of Bell Gardens, CA
Michael B. O’Kelly
City Manager
7100 Garfield Avenue
Bell Gardens, CA 90201
562.806.7702
[email protected]
Schedule
2008 - Present
Construction Cost
T&M
Design Fee
T&M
Overall Project Budget
T&M
Civil Engineering Services
Bell Gardens, CA
Summary of Services Provided
As an exclusive municipal contract provider to the City of Bell Gardens for the past 15 years, IE provides a number of services to the city, including inspection and plan checking, municipal engineering, SWPPP / NPDES / MS4 compliance and reviews, staff augmentation, program management, and construction management. Specifically, plan review and building inspection services have been provided for the Bicycle Casino Hotel, a seven - story, 117,907 - sq. ft. hotel, as well as numerous new and redeveloped residential units, commercial buildings, and restaurants. We also provide subdivision map checking, improvement plan checking, building and structural plan checking, and review of various engineering reports. Plan check services have been provided for Eastern Avenue Widening, Street Improvement Designs (Measure R), several phases of miscellaneous CIP street improvement phases under various federal grants, and numerous alley and street resurfacing projects. We have set up an urban stormwater program for commercial and industrial IC / ID inspections; upgrades to the John Anson Ford Sports Complex (irrigation and turf replacements); and a city water system evaluation. We also provide subdivision map checking, improvement plan checking, building and structural plan checking, and review of various engineering reports. All projects are currently on schedule and within budgets.

Project Manager: Aidan Mousavi
General Engineering Project Experience
353
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 31 Client
City of Baldwin Park, CA
Sam Gutierrez
Director of Public Works
14403 Pacific Avenue
Baldwin Park, CA 91706
626.960.4011
[email protected]
Schedule
2018 - 2022
Construction Cost
$1.6M
Design Fee
$106,510
Overall Project Budget
$1.7M
San Gabriel River Commuter Bikeway Project
Baldwin Park, CA
Summary of Services Provided
This project involved engineering design services for a 2.5 - mile class I bicycle and pedestrian path. The entire project is built on rights - of - way controlled by the city, Los Angeles County Department of Public Works, Los Angeles County Flood Control District and Caltrans, and being acquired by the city or through a Land Use Agreement with the Los Angeles County Department of Public Works and Permits from Caltrans District 7. The design phase of the project includes project management and meetings, data collection and record research, utility research and agency coordination, surveying, hydraulic and hydrology analysis, and 80%, 100% and final plan, specifications and cost estimate. The city subsequently engaged IE to provide Categorical Exemption documentation and Notice of Exemption; a biological assessment of the project area, including review of relevant data and site reconnaissance to identify the potential for occurrence of any listed or special status species within the project area; a Natural Environmental Study Minimal Impact (NES(MI)); Caltrans Encroachment Permit; Los Angeles County Flood Control District Encroachment Permit; Storm Water Pollution Prevention Plan / Notice of Intent / Notice of Termination and a Cultural Resources review. The project was completed on time and within budget.

Project Manager: Aidan Mousavi
General Engineering Project Experience (cont.)
354
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 32 Client
City of Huntington Park, CA
Cesar Roldan
Public Works Director
6550 Miles Avenue
Huntington Park, CA 90255
323.584.6274
[email protected]
Schedule
2018 - 2019
Construction Cost
$3.75M
Design Fee
$262,280
Overall Project Budget
$4M
Linear Greenway
Huntington Park, CA
Summary of Services Provided
IE assisted with the City of Huntington Park to obtain a $3.5M grant for urban greening to construct and revitalize ten contiguous parcels within the City of Los Angeles Department of Water and Power right of way. IE prepared design plans and specifications for the work to be performed associated with the grant requirements.

Scope included mass grading, pavement and concrete improvements, designated bike path, planting and landscaping, irrigation, dry stream beds and various site amenities.

Project Manager: Aidan Mousavi
General Engineering Project Experience (cont.)
355
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 33 Client
City of Lynwood, CA
Julian Lee
Director of Public Works
11750 Alameda Street
Lynwood, CA 90262
310.603.0220
[email protected]
Schedule
2022 - 2023
Construction Cost
$6.4M
Construction
Management &
Inspection Fee
$371,056
Overall Project Budget
$6.7M
Urban Bike Trail
Lynwood, CA
Summary of Services Provided
“2023 American Public Works Association (APWA) Project of the Y ear” award winner.

The work encompassed by the project is more specifically defined in the Contract Documents, but in general consists of, but is not limited to, the following work:
construction of HMA bike path, curb and gutters, curb ramps, retaining walls, concrete swales, concrete box culverts, chain link fence, permeable pavers, installation of removable bollards, gates, traffic signing and striping. Once construction began, we provided construction management and construction inspection for this project.

Project Manager: Douglas Benash
General Engineering Project Experience (cont.)
356
General Engineering Project Experience (cont.)
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 34 Client
City of Montebello
Danilo Batson
Former Director of Public Works
1600 W. Beverly Boulevard
Montebello, CA 90640
323.889.9976
Schedule
01/2017 - 07/2018
Construction Cost
N/A
Design Fee
N/A
Construction
Management &
Inspection Fee
$254,980
Home 2 Suites Construction Management and Inspection
Montebello, CA
Summary of Services Provided
IE provided review of the project location, utilities, relocation of maintenance facility, site development standards, traffic circulation, grading, drainage and the draft Mitigated Negative Declaration environmental report. Once construction began, we provided construction management, construction inspection, plan check services and building inspection services for this 203 - room, eight - story hotel. The hotel is owned by the city and operated by Hilton. The hotel is expected to generate more than $1M to the city’s general fund each year.

Project Manager: Farzad Dorrani
357
Utility Engineering Project Experience
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 35 Client
City of Bell Gardens, CA
Michael B. O’Kelly
City Manager
7100 Garfield Avenue
Bell Gardens, CA 90201
562.806.7702
[email protected]
Schedule
2018 - 2020
Construction Cost
$10M
Design Fee
$139,016
Overall Project Budget
$10.1M
Water Well #1, Booster Stations and Reservoir
Bell Gardens, CA
Summary of Services Provided
The scope of work provided by IE provides the development of well improvements and piping to a new reservoir with subsequent booster station to deliver water at a constant pressure to the customers. The new reservoir provides needed fire flow and operational benefits to the customers mitigating the need for imported MWD water. Within the last six (6) months, the city’s well was turned off due to reaching the notification limits for PFOS. IE is working with the State to obtain funding for a total project including treatment for the well water prior to entering the reservoir, then booster station. This shows how projects can change due to impacts of regulations.

The work involves direct coordination with the State and DDW for compliance with permitting and operational permits. All work is being funded by the State through a grant. The city is utilizing Besst and Q3 services on this project.

Project Manager: Aidan Mousavi
358
Utility Engineering Project Experience (cont.)
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 36 Client
City of La Palma, CA
Andy Ramirez
Public Works / Community
Services Director
7822 Walker Street
La Palma, CA 90623
714.690.3310
[email protected]
Schedule
2022 - 2023
Thelma Avenue Water Main Installation
La Palma, CA
Summary of Services Provided
The scope of work provided by IE under the contract for City Engineer services, was to coordinate for the design, health department coordination, coordination with the City of Buena Park, and construction management and inspection. The work also included direct coordination with City of La Palma staff to ensure the interconnect was modeled and provided a benefit for La Palma along with providing emergency water to the City of Buena Park. The project constructed 1,200 LF of transmission main with 600 LF encased due to Health Department clearance requirements along with a new vault for the interconnect valve, pressure activated Cla - Val, and devices for future connection to each jurisdictions SCADA systems. Construction was completed within schedule and budget.

Project Manager: Aidan Mousavi
359
Utility Engineering Project Experience (cont.)
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 37 Client
City of Huntington Park, CA
Cesar Roldan
Public Works Director
6550 Miles Avenue
Huntington Park, CA 90255
323.584.6274
[email protected]
Schedule
2020 - 2021
Construction Cost
$3.6M
Design Fee
$222,236
Overall Project Budget
$3.9M
Water Main Replacement Project FY 20 / 21
Huntington Park, CA
Summary of Services Provided
The City of Huntington Park selected IE’s proposal for the design of a water main replacement project. IE provided geotechnical and potholing reports to the city to best avoid conflicting utilities for the redesign of one of the largest water mains in the city.

Project Manager: Aidan Mousavi
360
Utility Engineering Project Experience (cont.)
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 38 Client
City of Baldwin Park, CA
Sam Gutierrez
Director of Public Works
14403 Pacific Avenue
Baldwin Park, CA 91706
626.960.4011
[email protected]
Schedule
2020 - 2022
Construction Cost
$852,845
Design Fee
$90,023
Overall Project Budget
$942,868
Foster Avenue and Pedestrian Rail Crossing Drainage Improvement Baldwin Park, CA
Summary of Services Provided
Scope of work included pavement rehabilitation, various concrete improvements, new 24 - in storm polypropylene pipe with new catch basins, dry wells and modular storm chamber system. Percolation tests were conducted to size the modular storm chamber system to alleviate flooding.

Project Manager: Aidan Mousavi
361
Utility Engineering Project Experience (cont.)
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 39 Client
City of Lynwood, CA
Julian Lee
Director of Public Works
11750 Alameda Street
Lynwood, CA 90262
310.603.0220
[email protected]
Schedule
2019 - 2021
Construction Cost
$1.3M
Design Fee
$52,197
Overall Project Budget
$1.4M
Street Rehabilitation and Storm Drain Improvements
Lynwood, CA
Summary of Services Provided
Our design team delivered PS&E for the improvements on Lilita Street and Eve Avenue in the City of Lynwood. The project consisted of a comprehensive rehabilitation of the streets, including new pavement sections, localized concrete repairs, a new storm drain chamber to alleviate the flooding in the area, a new water main and localized sewer repairs. All of the proposed improvements were based on hydrology / hydraulic reports, a geotechnical report, the city’s water master plan and sanitary sewer CCTV footage. The medium - sized BMP was deemed the best option from four different recommendations our design team provided to the city.

Project Manager: Aidan Mousavi
362
Traffic Engineering Project Experience
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 40 Client
City of Montebello, CA
Danilo Batson
Former Director of Public Works
1600 W. Beverly Boulevard
Montebello, CA 90640
323.889.9976
Schedule
2017 - 2020
Construction Cost
$2.7M
Design Fee
$674,288
Overall Project Budget
$5.87M
Montebello Boulevard Widening Project
Montebello, CA
Summary of Services Provided
“2021 American Public Works Association (APWA) Project of the Y ear” award winner.

The scope of work under Phase II of the Montebello Boulevard Bike Lane and Sidewalk Improvement project included design, preparation of PS&E for roadway improvements and widening, pavement rehabilitation, concrete improvements, sidewalk improvement, utility adjustments, ADA improvements, Class II bike lane, traffic signal improvements, pedestrian lighting, and landscaping, bioswales along center medians and irrigation improvements. IE also provided project management, contract administration and construction management and inspection services, preparation of daily reports, review of change orders and progress payment requests, and coordinate soils testing services. IE delivered this successful project that was aimed at benefiting the underprivileged community to encourage residents to practice a healthy and active lifestyle.

Project Manager: Aidan Mousavi
363
Traffic Engineering Project Experience (cont.)
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 41 Client
City of Lynwood, CA
Julian Lee
Director of Public Works
11750 Alameda Street
Lynwood, CA 90262
310.603.0220
[email protected]
Schedule
2017 - 2020
Construction Cost
$2.9M
Design Fee
$220,000
Overall Project Budget
$3.1M
Long Beach Boulevard Improvement Project
Lynwood, CA
Summary of Services Provided
“2020 American Public Works Association (APWA) Project of the Y ear” award winner.

The IE team provided construction management, inspection, and labor compliance for the resurfacing of 192,779 sq. ft. of roadway in Lynwood, CA. Additional activities included renovating sidewalks, driveway approaches, curbs and gutters, and constructing six new bus pads. Beautification enhancements included the removal and replacement of 23 trees, construction of landscaping in median islands with irrigation systems, and the installation of a city monument sign. Additionally, existing streetlights were relocated, and traffic signals were improved at two intersections.

Project Manager: Aidan Mousavi
364
Traffic Engineering Project Experience (cont.)
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 42 Client
City of Huntington Park, CA
Cesar Roldan
Public Works Director
6550 Miles Avenue
Huntington Park, CA 90255
323.584.6274
[email protected]
Schedule
2020 - 2023
Construction Cost
$5.8M
Design Fee
$558,145
Overall Project Budget
$6.4M
Slauson Congestion Relief Project
Huntington Park, CA
Summary of Services Provided
Utilized Synchro modeling for signal and timing improvement. Upgraded traffic signal equipment, enhanced phasing operations, street widening, concrete improvements, coordination with Los Angeles county and various railroad agencies. The goal of the project was to study and design improvements along the Slauson corridor to increase capacity, reduce congestion and improve traffic flow. Design plans have been finalized.

Project Manager: Aidan Mousavi
365
Traffic Engineering Project Experience (cont.)
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 43 Client
City of Baldwin Park, CA
Sam Gutierrez
Director of Public Works
14403 Pacific Avenue
Baldwin Park, CA 91706
626.960.4011
[email protected]
Schedule
2017 - 2020
Construction Cost
$1.9M
Design Fee
$176,144
Overall Project Budget
$2.1M
Maine Avenue Complete Streets Project
Baldwin Park, CA
Summary of Services Provided
The Maine Avenue Complete Streets project consisted of bicycle, pedestrian and street improvements involving construction, installation and enhancement of safety features and measures. IE provided PS&E for Phase 1B. The improvements include a road reconfiguration via the reduction of vehicle travel lanes from four to two with a shared center left - turn lane and key intersection bulb - outs, widening and extension of sidewalks, ADA accessible curb ramps, high visibility crosswalks, new signage, catch basin relocations, drought tolerant landscaping, smart irrigation, water capture systems, traffic signal adjustments, striping and marking enhancements for Class II bike paths. We also designed a roundabout feature and coordinated major water infrastructure relocations.

Project Manager: Aidan Mousavi
366
Traffic Engineering Project Experience (cont.)
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 44 Client
City of Bell Gardens, CA
Michael B. O’Kelly
City Manager
7100 Garfield Avenue
Bell Gardens, CA 90201
562.806.7702
[email protected]
Schedule
2020 - 2022
Construction Cost
$551,770
Design Fee
$42,240
Overall Project Budget
$594,010
HSIP Cycle 8 - Various Intersection Improvements
Bell Gardens, CA
Summary of Services Provided
CM&I services for modification of existing signal systems including installation of conduits, pull boxes, new signal heads, sensor units, reprogramming of signal controller, traffic striping, markings, and traffic control; hauling and disposal; and all appurtenant equipment and work. Preparation of staff reports, Notice to Proceed issuance, and recommendations for change orders and progress payments.

Prepared daily reports, reviewed change orders and progress payment requests, and coordinated soils testing.

Project Manager: Farzad Dorrani
367
Architectural Services Project Experience
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 45 Client
City of Bell Gardens, CA
Michael B. O’Kelly
City Manager
7100 Garfield Avenue
Bell Gardens, CA 90201
562.806.7702
[email protected]
Schedule
2021
Construction Cost
$195,000
Design Fee
$68,000
Overall Project Budget
$263,000
Ford Park Restroom Project
Bell Gardens, CA
Summary of Services Provided
Ford Park is used extensively by the local community kids and adults. There are multiple play fields that are used often for recreational activities for the residents of the city. However, there were no bathrooms for the use of the community and therefore, it created a problem for the users. Therefore, the city decided to incorporate a new restroom within the existing facility. iArch designed a prefab bathroom that found to be the best alternative for the situation. The reason for the selection of a prefabricated bathroom was that the construction cost was lower than building the bathroom and the duration of construction.

Project Manager: Alex Serafin
368
Architectural Services Project Experience (cont.)
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 46 Client
City of Hawaiian Gardens, CA
Neema Ghanbari
Public Works Manager
21815 Pioneer Boulevard
Hawaiian Gardens, CA 90716
562.420.2641
[email protected]
Schedule
2023
Construction Cost
$78,600
Design Fee
$46,500
Overall Project Budget
$125,100
Lee Ware Health Restroom Building Remodel
Hawaiian Gardens, CA
Summary of Services Provided
Lee Ware Restroom is located at the City Hall and is used by the connecting sports center and senior center. The client requested iArch make all upgrades to include all ADA requirements.

Above is iArch’s concept design. iArch provided fixtures quantity as required by code and convenience. The proposed space is ADA accessible. iArch revised the location of the security gate to allow additional clearance and better flow.

Project Manager: Alex Serafin
369
Architectural Services Project Experience (cont.)
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 47 Client
City of Baldwin Park, CA
Sam Gutierrez
Director of Public Works
14403 Pacific Avenue
Baldwin Park, CA 91706
626.960.4011
[email protected]
Schedule
2020
Construction Cost
$117,900
Design Fee
$58,400
Overall Project Budget
$176,300
City Hall Renovation, Second Floor
Baldwin Park, CA
Summary of Services Provided
Engineering Division Redesign and TI improvements. The second floor of the City Hall houses the engineering division. The building was designed and built many decades ago. The layout of the engineering division did not match the current format of services for the city. Therefore, the city hired iArch to re - imagine the engineering division to ensure the proper flow of work and customers when they arrive at the city for business. The new design is much more efficient and creates better workspace for the employees.

Project Manager: Alex Serafin
370
Architectural Services Project Experience (cont.)
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 48 Client
City of Montebello, CA
Sam Kouri
Former City Engineer
1600 W. Beverly Boulevard
Montebello, CA 90640
562.243.1506
Schedule
2019
Construction Cost
$133,994
Design Fee
$12,806
Overall Project Budget
$148,800
Taylor Ranch Park
Montebello, CA
Summary of Services Provided
This was an old park that was planned to be converted into a Community Center.

However, due to lack of funds, the city decided to create an interim use for it.

Therefore, iArch designed a community garden that will create recreational opportunities for the residents and was very cost effective. Also, the design was prepared such that most of the improvements will be reused once the city has the available funds to build the community center.

Project Manager: Alex Serafin
371
Architectural Services Project Experience (cont.)
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 49 Client
City of La Puente, CA
John DiMario
CD Director
15900 Main Street
La Puente, CA 91744
626.855.1517
[email protected]
Schedule
2023
Construction Cost
$190,200
Design Fee
$46,500
Overall Project Budget
$236,700
La Puente Athletic Park Restroom Building Remodel
La Puente, CA
Summary of Services Provided
The city allowed iArch the opportunity to remodel the existing Men and Women’s Restroom Building. The client has requested iArch make all upgrades to include all ADA requirements. The roof structure was slightly modified to allow positive drainage at the peak. This roof originally had damaged skylights with a screen at top.

Project Manager: Alex Serafin
372
05 Qualifications of Proposed Personnel
373
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 50 Qualifications of Proposed Personnel
IE has been fortunate to engage some of the brightest and most experienced engineering staff. Without exception, our staff are dedicated to excellence in engineering design and service.

The organization chart on the following page illustrates our proposed team for this on - call contract. Many of these staff have worked on projects for the City of Lynwood in the past, and they are eager to continue providing services on your future projects. Resumes for our key staff follow the organization chart.

Our proposed Program Director, Farzad Dorrani, will be the primary contact person to represent our firm. Farzad Dorrani has 30 years of experience in a variety of civil engineering projects. He has worked extensively on major infrastructure and public works improvement and rehabilitation projects throughout southern California for various agencies, such as the cities of La Puente, Montebello, Anaheim, Irwindale, Malibu, as well as the Alameda Corridor - East Construction Authority. Farzad’s experience includes roadway design projects, parks, and downtown revitalization design projects, contract procurement, construction management, project management and administration. 374
KEY
Management
Support Staff
Subconsultants
Key Personnel
Staff
• Arjan Idnani, MSCE
• Nathan Kirby
• Hormoz Vahid
• Imad Zureiqat, EIT
Architectural Engineering
Infrastructure
Architects, Inc.

Staff
• Shawn Mousavi, MSCE, PE, QSP / QSD
• Hamed Habibi, MS
Land Surveying
Dennis Janda, PLS
Program Director
Farzad Dorrani, MS
Principal - in - Charge
Sid Mousavi, MSCE, PE
Project Manager
Aidan Mousavi, MBA, PE, QSP / QSD
Civil Design
Construction Manager
Masoud Sepahi, PE, LEED GA
Construction Management and Inspection
Staff
• Christopher Ley, PE
• Jaelin Murray, EIT
• Shawn Mousavi, MSCE, PE, QSP / QSD
• Shawnt Babakhanian
• Annie Li
Senior Engineer
Christopher Ley, PE
Staff
• Charlie Marr, PE
• Bahar Baradaran, EIT
• Michael Dela Cruz, EIT
• Shawnt Babakhanian
Senior Traffic Engineer
Amir Farahani, TE, PE
Utility Engineering Traffic Engineering
Geotechnical Engineering
Associated Soils
Engineering, Inc.

General Engineering
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 51 Organizational Chart375
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 52 Experience
Various Capital Projects | City of South El Monte, CA
Principal in Charge responsible for contract oversight of capital projects for the city, which include the Safe Route to School Project – Pedestrian Improvement Project, Durfee Avenue Project – Street and Median Improvement Project, Thienes Avenue Project – Street Improvement Project, and the New Temple Park Improvements – Prefabricated Modular Restroom.

City Engineer | City of Bell Gardens, CA
City Engineer responsible for approving all capital projects for the city and providing cost estimates and budgets for new and upcoming projects. Supervised various IE projects as the designated Principal - in - Charge. Participated in development meetings and provides support for various land development projects by establishing conditions for approval of projects. Supervised and directed traffic engineering and water engineering activities of the city. Attended City Council meetings and provides reports of engineering projects to the City Council. Oversaw the city’s NPDES program and MS4 Permit compliance.

Professional Service | City of Brea, CA
Principal in Charge responsible for oversight of performance of professional services to provide plans, specifications and estimates for rehabilitation of alleys east of Brea Boulevard and south of Imperial Highway to Date Street, Downtown Parking Structure 1 Sewer Line Upgrade, and Sewer Main Repair in Alley west of Brea Boulevard and south of Imperial Highway.

Various Street Improvements | City of Lynwood, CA
Principal - in - Charge who provided oversight of design, construction management, and inspection of street improvements for Linden Street, Virginia Avenue. Walnut Avenue, Redwood Avenue, Elmwood Avenue, Olanda Avenue, and Las Flores Boulevard. The project included topographic surveying to address the drainage issues, removal, and replacement of broken or missing gutters and curbs, subsurface investigation of the existing asphalt structure, replacement of existing damaged or substandard driveways, removal and replacement of trees that have caused damage, design of ADA - compliant ramps, and repair or placement of sidewalks, where necessary. IE also provided bid administration, construction management services, and inspection for these projects.

Interim City Manager, Director of Public Works and Planning and City Engineer | City of Baldwin Park, CA
Served as Interim City Manager during a 14 - month vacancy at the City of Baldwin Park, Responsible for the development of the $40M annual operating and capital budgets, including the identification of new revenue sources for the city.

Involved in labor negotiation with seven city labor groups. Also responsible for the Sid Mousavi, MSCE, PE
Principal - in - Charge
Education
M.S. Civil Engineering, California State
Polytechnic University, Pomona
B.S. Civil Engineering, California State
Polytechnic University, Pomona
B.S. Irrigation Engineering, Azerbaijan
University, Iran
Registrations
Professional Civil Engineer:

California (#42645)
*Experience prior to joining the firm
376
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 53 enhancement of the city’s public information and public relations materials, policy development and implementation, and general administrative oversight of the city’s six departments and more than 300 employees. As Executive Director to the city’s Community Development Commission, directed the city’s redevelopment activities.

Also served as Executive Director of the Baldwin Park Housing Authority, which provided housing services for Baldwin Park as well as the cities of Duarte, El Monte, Monrovia, and West Covina.

City Engineer | City of Bell Gardens, CA
Served as the City Engineer under a general contract to provide City Engineer services. Responsible for all capital improvement programs, land development, traffic engineering, water engineering and redevelopment engineering.

City Engineer | City of Montebello, CA
City Engineer responsible for all the city’s engineering issues and projects, including overseeing the city’s engineering staff. Also served as secretary to the Traffic Commission, preparing all reports and projects to the Engineering Division.

City Engineer | City of La Puente, CA
City Engineer who directed all the city’s engineering issues and projects. Responsible for the engineer’s budget and all engineering staff who were IE employees working in City Hall. In addition, developed capital improvement programs, approved designs, and implemented projects.

Interim City Manager, Director of Public Works and Planning and City Engineer | City of Baldwin Park, CA
Responsible for the direction and administration of a staff of 373 and budget of over $33M. Responsible for such achievements as: reorganization of departments, employee development program, construction of Metrolink station, construction of 9 - acre park facility, pavement management program, energy management system, eradication of graffiti within city, bridge rehabilitation, transit program and signal synchronization.

Director of Public Works and City Engineer | City of Diamond Bar, CA Upon the city’s incorporation, Sid was hired to set up the Public Works Department, with responsibility for direction and supervision of all public works functions. While with the City of Diamond Bar, interfaced with official offices such as City Council, City Commissions, City Manager’s office, and other city departments and staff. Additional agency coordination included working with Caltrans, Los Angeles County agencies, Air Quality Management District, Walnut Unified School District, and community citizens and businesses.

Sid Mousavi, MSCE, PE (cont.)
Principal - in - Charge
377
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 54 Farzad Dorrani has 30 years of experience in a variety of civil engineering projects.

He has worked extensively on major infrastructure and public works improvement and rehabilitation projects throughout southern California for various agencies, such as the cities of La Puente, Montebello, Anaheim, Irwindale, Malibu, as well as the Alameda Corridor - East Construction Authority. Farzad’s experience includes roadway design projects, parks, and downtown revitalization design projects, contract procurement, construction management, project management and administration.

Experience
Lincoln Park Improvement | City of Anaheim, CA
Principal - in - Charge. Responsible for project management and design review for this project that improved the park’s traffic movement, parking, pedestrian access, drainage, roadway pavement, install a raised median with a park monument sign, and provide infrastructure for a future restroom building.

HSIP Cycle 8 - Various Intersection Improvements | City of Bell Gardens, CA Principal - in - Charge. Responsible for high - lever oversight of the preparation of PS&E, project management, administration, construction management and inspection, fund administration and labor compliance for the intersections at Eastern Avenue and Lubec Street and Garfield Avenue and Loveland Street. The project also included the addition of video detection on all intersection approaches and the reconstruction of the pavement within the intersection with concrete. The signal design included field surveys, signing and striping, geotechnical investigations. Bid package was prepared and submitted to city.

HSIP Cycle 7 Project - Various Intersections Improvements | City of Montebello, CA Principal - in - Charge. IE provided the preparation of PS&E for roadway improvements, pavement rehabilitation, concrete improvements, ADA improvements and utility adjustments at three intersections: Garfield Avenue and Whittier Boulevard, Garfield Avenue and Via Campo, and Via Campo and Findlay Avenue.

ATPL Federally Funded Project, ATPL 5373, Citywide Safety Enhancement | City of Bell Gardens, CA
Project Manager. This project involved safety improvements to the intersections at Eastern Avenue and Lubec Street Intersection and Garfield Avenue and Loveland Street Intersection. IE provided PS&E, project management, administration, construction management and inspection, fund administration and labor compliance for this project.

Arroyo Drive Improvements | City of Montebello, CA
QA / QC Reviewer and Project Manager. IE provided design, project management, bidding of contract, construction management and inspection, as well as federal fund administration for this project that involves removal of existing AC paving and paving of AC pavement and concrete improvement reconstruction, including Farzad Dorrani, MS
Program Director
Education
M.S. Civil Engineering, Queen’s
University of Belfast, U.K.

B.S. Civil Engineering, University of
Ulster, U.K.
378
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 55 replacing existing curb and gutter, sidewalk, driveway approaches, access ramps, and adjustment of utility covers, traffic striping, markers, pavement markings and curb painting. The project ran from Arroyo Drive from Astra Drive to Rose Glen Ave.

Pavement Repairs and Skin Patch of Various Streets CDBG Zone | City of Montebello, CA
QA / QC Reviewer and Project Manager. Responsible for oversight of design, project management, bidding, award of contract, construction management and inspection as well as federal fund administration and labor compliance of various streets pavement repairing and skin patching as agreed with the city to complete as much of the street improvements within the fixed project budget.

Eastern Avenue and Florence Avenue Regional Surface Transportation Improvements | City of Bell Gardens, CA
Project Manager. The project was the construction of two westbound left - turn lanes with a new west - bound dedicated right - turn lane to increase the intersection capacity in the westbound direction. The westbound leg is the only leg without dual left - turn lanes or dedicated right - turn lane. The intersection underwent new pavement reconstruction. The existing 7 - in asphalt concrete (AC) over a 10 - in aggregate base (AB) section was upgraded to a 10 - in Portland Cement Concrete (PCC) pavement over 12 - in AB section; increasing the service life and structural capacity of the intersection. Traffic signal system components for the intersection were upgraded as well. The existing traffic signal poles were upgraded from 80 mph design poles to 100 mph design poles (current Caltrans standard), a new P cabinet will be installed as well as new luminaries and full intersection video detection for all traffic movements.

ATP Cycle 2 Community Linkages to Civic Center and Long Beach Boulevard | City of Lynwood, CA
Principal - in - Charge. The project involves many pedestrian improvements, including sidewalk widening, crosswalk enhancements, landscaping, and street lighting.

Health, educational, and recreational facilities are located nearby the study area.

The project will likely benefit pedestrians walking in the corridor for recreation as well as those accessing the nearby facilities. The corridor also connects to a Metro Green Line station, so pedestrians may use the corridor as a means to access public transportation. The project will also include speed trailers to enforce the speed limit in nearby school zones. IE is providing project management during the entire course of the project. This has included a kick - off meeting, project development and design review meetings, preparation of design documents for the city to obtain funding approval, progress meetings, preparation of agendas and minutes, preparation and updates of project schedule, and project cost management.

Farzad Dorrani, MS (cont.)
Program Director
379
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 56 Experience
Lilita Street and Eve Avenue Storm Drain Improvement | City of Lynwood, CA Conducted a field investigation to identify cause of flooding issue. Drafted a hydrology and hydraulics report to identify issues and provided two solutions to alleviate flooding. Developed plans to address flooding through use of drywells and developed alternative plans to direct connect proposed storm tank to existing storm drain main line.

Connector Pipe Screen (CPS) | City of Bell Gardens, CA
Conducted a field investigation of all public and private catch basins citywide.

Developed a GIS based log utilizing MS4Front software. Developed plans and applied for permitting through LA county to retrofit catch basins citywide by installing CPS units. Hosted pre - construction meeting with contractor, city staff and LA county.

Gertrude Drive Street Improvements | City of Lynwood, CA Developed Plans, Specifications and Estimate (PS&E) package for water improvement along Gertrude Drive. Designing 8 - in D.I.P Water Main complete with tees, service lines, water meters, water boxes, wedge gate valves, transition couplings, thrust blocks, reducers etc. Plans included asphalt and concrete repairs along with plan and profile for curb and gutter drainage.

Virginia Avenue Street Improvements | City of Lynwood, CA Developed Plans, Specifications and Estimate (PS&E) package for water improvement along Virginia Avenue. Designing 8 - in D.I.P Water Main complete with tees, service lines, water meters, water boxes, wedge gate valves, transition couplings, thrust blocks, reducers etc. Plans included asphalt and concrete repairs along with plan and profile for curb and gutter drainage.

Asmus Park Catch Basin Evaluation and Feasibility Study | City of Bell Gardens, CA Responsible for alleviating severe flooding issue at Asmus Park by identifying issues through a field investigation and a hydrology and hydraulics analysis to identify volume of water needed to divert and treat. Developed conceptual plans of dry wells at parks to recharge ground water.

Slauson Avenue Congestion Relief Improvement Project | Huntington Park, CA Project Manager. Responsible for hydrology and hydraulics analysis to divert and treat runoff from two - mile long corridor along Slauson Avenue. Design BMPs to treat runoff and make street into a green street. Run Synchro Simulation for ten signalized intersections for LOS analysis, coordination, and timing. Design plans and specifications for signal system upgrades and street widening.

San Gabriel River Bikeway Environmental Services and Permits | Baldwin Park, CA Engineering Supervisor. Responsible for developing and approving SWPPP so all pollutants and their sources, including sources of sediment associated with Aidan Mousavi, MBA, PE, QSP / QSD
Project Manager
Education
M.B.A., General, California State
Polytechnic University, Pomona
B.S., Civil Engineering, California State
Polytechnic University, Pomona
Registrations
Professional Civil Engineer:

California (#91136)
Qualified SWPPP Practitioner (QSP)
/ Qualified SWPPP Developer (QSD):

California (#91136)
*Experience prior to joining the firm
380
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 57 construction site erosion and all other activities associated with construction activity are controlled. All discharges are identified and either eliminated, controlled, or treated. BMPs selected that are effective and result in the reduction or elimination of pollutants in stormwater discharges. Post - construction BMPs are identified and installed during construction that are intended to reduce or eliminate pollutants after construction is completed. Developed methods to implement BMP inspection, visual monitoring, Rain Even Action Plan (REAP) and Construction Site Monitoring Program (CSMP).

NPDES Storm Water Program Inspection | Baldwin Park, CA Inspector. As required under the state’s Regional Water Quality Control Board regulations and city ordinances permitting inspection programs, the City of Baldwin Park has enlisted IE to conduct a routine visual inspection for point - source pollution control. The goal of this inspection is to prevent the discharge of pollutants associated with business activities from entering the city’s storm drain system. Aidan conducted all necessary inspections for the city and provided the appropriate reports.

NPDES Annual Report | Montebello, CA
Project Manager. As mandated by the Trash Total Maximum Daily Loads (TMDLs) for the Los Angeles river watershed, each city within the Los Angeles River watershed is required to submit a compliance report for the Los Angeles River trash TMDL to the Regional Water Quality Control Board. With the collaboration of engineering, code enforcement, building, street maintenance, planning, and relevant contracted services, Aidan developed the Annual Report for the city, identifying methods used to meet compliance as well as providing calculations for scientific justification.

NPDES Watershed Management Plan and Integrated Monitoring Program Coordination | Bell Gardens, CA
Project Manager. NPDES permit, authorized by the Clean Water Act, was issued by the Regional Water Quality Control Board. The purpose is to ensure the MS4 permits in the county of Los Angeles are not causing or contributing to exceedances of water quality objectives set to protect the beneficial uses in the receiving waters in the Los Angeles region. Aidan worked with a variety of agencies to customize the City of Montebello’s storm water programs by using BMPs to achieve compliance. He assisted with training and presentation of the requirements of the MS4 Permit to all maintenance staff and inspectors. Aidan coordinated with the Los Angeles County Flood Control District and seven other cities in Los Angeles County and worked on developing the strategy, design, and implementation of a Watershed Management Program and a Coordinated Integrated Monitoring Program. Aidan attended all regular watershed meetings, representing the City of Bell Gardens, as requested by the city. He also provided commercial and industrial permit inspections for all eligible businesses in the City of Bell Gardens; he provided the businesses with educational material and advised them on how to comply with the MS4 permit. Aidan also conducted audits and provided the reports, as required by the permit.

Aidan Mousavi, MBA, PE, QSP / QSD (cont.)
Project Manager
381
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 58 Masoud has over 35 years of experience working for both public agencies in addition to the private sector, managing a variety of large and complex public works and capital improvement projects. He has held various leadership positions in managing a variety of projects for major public works programs. As the City Engineer for the City of Placentia, he was responsible for delivery of many projects. As the Director of Construction Management for the Los Angeles Metropolitan Transportation Authority, Masoud was responsible for the southern portion of the Crenshaw / LAX Transit Project. During his tenure with LA Metro, Masoud was responsible for management of all construction on the Southern segment of the project, including major utility relocations. Working for the City of Los Angeles for 10 years, Masoud held various positions, managing many types of public improvement projects as well. The following is a partial list of projects that Masoud has successfully managed over the last 35 years.

Experience
City Engineer | City of Placentia, CA*
Masoud’s responsibilities included management and processing of all public works encroachment permits in addition to all other city engineering and management functions. Masoud was responsible for plan check, design review, and inspections associated with private developments throughout the city. He assisted the Director of Public Works with preparation of the Capital Improvement Program (CIP) budgets and monitored the expenditures in conformance with the Department’s goals and objectives. He managed all design and construction contracts associated with the public works CIP program to ensure delivery of projects on time and on budget.

Masoud supervised and assigned work to in - house engineering, maintenance staff and consultant staff associated with CIP and plan - checking activities. His responsibilities also included negotiating and enforcing design and construction contracts, cooperative agreements, interacting with other cities and agencies, license agreements, lease agreements, schedules, and work plans to ensure projects were completed within expected timelines, material specifications, and budget.

He reviewed change orders, evaluated budgets, costs, and technical feasibility.

Conducted staff meetings with city personnel; attended meetings with other city departments, government agencies, private developers, contractors, and consultants to coordinate various projects and programs. Prepared schedules and budgets for various projects and assist with preparation of the CIP and grant applications.

Reviewed and approved tract maps, parcel maps, lot - line adjustments and provided advice to the City Administrator, planning and City Council regarding engineering and administrative issues. Prepared Agenda Reports on various actions required by the City Council. Attended City Council, Planning Commission, Traffic Commission, and other public meetings and made presentations on various engineering and construction proposals, contracts, engineering reports, and staff recommendations.

Masoud Sepahi, PE, LEED GA
Construction Manager
Education
B.S. Civil Engineering, Loyola
Marymount University
Structural / Civil Engineering,
California State University, Northridge
Registrations
Professional Civil Engineer:

California (#52786)
Leadership in Energy and
Environmental Design Green Associate
(LEED GA)
*Experience prior to joining the firm
382
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 59 Los Angeles Metropolitan Transportation Authority | City of Los Angeles, CA* As the Director of Construction Management, Masoud was responsible for the southerly portion of the Crenshaw / LAX Transit Project. This project was an eight - and - a - half - mile light - rail line, which connects the Expo Line on Exposition Boulevard to the Metro’s Green Line at the Los Angeles International Airport. This $2B project consisted of 8 Stations, 8 aerial bridges over major streets and the I - 405 Freeway. During his tenure with LA Metro, Masoud was responsible for management of all construction on the Southern segment of the project, extending from the Greenline station to the outside of City of Inglewood. His responsibilities included management of the entire construction staff, reporting to executive management on construction progress and issues in addition to interfacing with the city officials, utility agencies, contractors, and designers. Also, working for Metro, Masoud was responsible for the management of three major Advanced Utility Relocation Contracts as part of the Purple Line Corridor Project. This project extended the terminus at Wilshire / Western westward for about nine miles with seven new stations.

He performed Resident Engineering for three major contracts under this $4B transit project. Responsible for all of the utility relocations at three major intersections, La Brea and Fairfax in the City of Los Angeles and La Cienega at the City of Beverly Hills.

Duties included management of construction and design staff, interaction with utility agencies, contractors, designers and city officials. The advance utility contracts paved the way for mass excavation of the subway stations. The relocation of over 150 major utility lines had to be designed and constructed within a very aggressive schedule to allow for the next phases of the project to start. As the Director of Construction Manager, Masoud was responsible for delivery and relocation of major storm drains, sanitary sewer, electrical power lines, telecommunication, water, gas, and many other utilities, which had to be relocated within a very aggressive schedule.

MARRS Services | Fullerton, CA*
Principal. As the principal for MARRS’ facilities, and transit divisions, Masoud was responsible for managing construction management staff and multiple contracts with various public agencies. His responsibilities included management of multiple civil engineering projects, reporting to executive management and interaction with clients. His other responsibilities included development and implementation of marketing strategies, preparation of staffing plans, preparation and analysis of company budgets and finances in addition to interaction with existing and potential new clients. Some of the major projects under his management included: LAX / Crenshaw Transit Corridor, Advanced Utility Studies, LAWA Water Systems modeling, LAX 2nd Level Roadway and Deck Repair, Metro On - call bus Facility construction management, Cesar Chavez Roundabout Project, LAX South Runway Improvements in addition to many other infrastructure improvement projects.

Masoud Sepahi, PE, LEED GA (cont.)
Construction Manager
383
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 60 GKK Works | Irvine, CA*
As Program Director, Masoud was responsible for GKK’s Construction Management for various public works facility projects. Some of these projects included: Police Administration Building, San Bernardino International Airport Facility Improvements Program, Third party review for all new developments for the Inland Valley Development Agency (IVDA.), runway drainage studies, conceptual design and modifications for terminal buildings, facility and site assessment, demolition of buildings and facilities at the airport, master planning, and third - party reviewer for construction of large warehouses for the IVDA. On behalf of IVDA, he also worked with private developers for development of large cargo storage and distribution centers near the airport.

Kellogg Brown and Root (KBR) | CA*
As the KBR’s Construction / Design manager for the West - coast region, he was responsible for KBR’s projects in the Southern California Region. His duties included contract negotiations with clients and subconsultants, managing and administering projects in addition to managing engineering staff and subconsultants. As the design manager for the Airside Improvement Program (AIP) at Bush Intercontinental Airport, he was responsible for the management and supervision of the design staff and up to 100 subconsultants. His responsibilities also included management of multiple design contracts to ensure compliance with the project budget and schedule in addition to the Client’s guidelines and regulations. Provided routine project status reporting on the work performance and productivity of designers and their subconsultants. He also reviewed and approved designer’s invoice for compliance with provisions in the Contract including minority participation requirements. He managed the design and construction of many projects, under the AIP program
Project / Construction Manager | City of Los Angeles, CA* As a City of Los Angeles Engineering staff, Masoud worked on many infrastructure programs and projects, some of which include the Police Bond Program, Los Angeles Convention Center Expansion, Tom Bradley Terminal at LAX and many other small to large municipal facility construction and renovations. Masoud worked at the Departments of Public Works and Building and Safety, where he was responsible for plan check activities for Public Works improvements in addition to residential and commercial buildings. He was responsible for reviewing and evaluating the work of professional and technical employees engaged in the preparation of designs, plans, specifications, estimates, environmental studies, budgeting, scheduling and reports on major engineering projects. Supervised and directed engineering staff and activities in connection with design, construction, maintenance, inspection, and operation of a wide variety of engineering projects. As part of the Earthquake Recovery Division, Masoud managed the recovery and renovation of buildings after the Northridge earthquake in the San Fernando Valley.

Masoud Sepahi, PE, LEED GA (cont.)
Construction Manager
384
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 61 Christopher Ley has over 15 years design and engineering experience. His expertise includes CAD and graphic design, civil engineering design including street layout, hydrology, drainage, sewer design and grading for residential and commercial projects.

Experience
Walden and Associates | Irvine, CA*
Project Engineer. Christopher was responsible for civil engineering design including street layout, hydrology, drainage, sewer design and grading for residential and commercial projects. Skilled in developing plans and survey data sets using AutoCAD Civil 3D 2012 and 2016. Production of reports using Microsoft Word and Excel, Bentley WaterCAD, and Bluebeam.

WWD / L&S Engineering | Monterey, CA*
Staff Engineer / CAD Manager. Responsible for civil engineering design including street layout, hydrology, drainage, sewer design and grading for residential and commercial projects. Skilled in developing plans and survey data sets using AutoCAD Land Desktop 2006 and AutoCAD Civil 3D 2011. Responsible for company’s migration from Land Desktop 2006 to Civil 3D 2011. Subsequent duties as CAD Manager, responsible for all training in Civil 3D after initial off - site classes, development of comprehensive styles and description key sets, and implementing transitions to Civil 3D standards from Land Desktop. Also developed training aids and curriculum for transition. Responsible for conversion of Civil 3D files for Revit.

Administrative assistant duties during slow periods, including accounting, filing and office development. IT duties when necessary, including rebuilding network after incomplete implementation by consultant. WWD became L&S in August 2012.

Saroyan Masterbuilders | Sand City, CA*
CAD Manager / Senior Draftsman. Responsible for residential and commercial design and drafting while ensuring ADA compliance, egress requirements and coordination of plans from various disciplines into a single set. Was responsible for implementation of AutoCAD 2006 system, training of 2 supervisors, development of CAD standards and overseeing transition from hand drafting.

Greenway Design | Marina, CA*
Drafting and Engineering Manager. Residential design and drafting including determination of code compliance for lateral stability and egress. Extensive experience with Microstation V8 and Triforma production drafting of residential structures, including application of engineering notes.

Lindal Cedar Homes, Inc. | Seattle, WA*
Senior Draftsman. Responsible for residential design and drafting, including determination of code compliance for lateral stability and egress. Instrumental in creating structural designs of posts and beams for a variety of vertical and lateral Christopher Ley, PE
Senior Civil Engineer
Education
B.S. Civil Engineering, Oregon State
University
Registrations
Professional Civil Engineer:

California (#80620)
*Experience prior to joining the firm
385
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 62 loads. Pioneered development of various charts as aids in design of structural elements. Directly involved in the implementation of Microstation Triforma 3D, and developed methods of aligning non - planar elements that were subsequently used by Microstation in their official training programs.

Baker Engineers, Inc. | Lynwood, WA*
Staff Engineer. Duties included structural design including wind and seismic analysis, gravity design, rigid frame foundation design and pin pile foundation design.

Production and structural detail drawings and drafting foundation plans.

Christopher Ley, PE (cont.)
Senior Civil Engineer
386
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 63 Amir Farahani has more than 30 years of experience in various traffic, transportation and civil engineering disciplines. He has experience with contract administration, design experience and regulatory compliance. He has worked with IE for the past two years as a Principal Engineer. He has been in charge of various traffic and transportation studies; design of traffic signals, high - intensity activated crosswalk (HAWK) signals and Rectangular Rapid Flashing Beacon (RRFB) for pedestrian crossings. In working with the City of Orange, as an Engineering Tech. II and eventually as a City Traffic Engineer / Traffic and Transportation Manager, he has been involved in all aspects of the projects the city has designed and constructed.

This includes coordinating with local, county, state, and federal agencies and various utilities to ensure successful project completion. Amir understands the level of detail and problem - solving skills required to complete high - profile projects on time and within budget.

Experience
Slauson Avenue Congestion Relief Improvements Project | City of Huntington Park, CA
Project Manager. Conducting traffic signal left turn phasing for five intersections in the project limits and recommending protected permissive left turn phasing with flashing yellow left turn arrow. Designed the subject traffic signals accordingly and prepared PS&E.

ATP Cycle V - Safe Routes and Childhood Obesity Project | City of Huntington Park, CA
Project Manager. In charge of various traffic related works such as design of HAWK beacon system for three pedestrian crossings; design of pedestrian scramble crosswalk striping; traffic signal modifications to create a separate pedestrian scramble cycle; restriping of existing crosswalks with a high - visibility continental design; realignment of existing crosswalks to align with the proposed conversion of Hood Avenue into a one - way street and prepared the project PS&E.

Imperial HWY and Ruth Avenue Traffic Signal Improvements Project | City of Lynwood, CA
The work to be done, in general, consists of, but is not limited to the following:
mobilization, traffic control, remove existing crosswalks, warning lights, and streetlights; removal and construction of concrete sidewalks, curb and gutters, curb ramps; furnish and install traffic signal system, battery backup system, pull boxes, traffic signal loop detectors and connect DLC to pull box, relocate fire hydrant and water valve, providing construction survey, and traffic signing, striping and markings as shown on the plans and noted in these special provisions.

Amir Farahani, TE, PE
Senior Traffic Engineer
Education
B.S. Civil Engineering, California State
University, Los Angeles
Registrations
Professional Traffic Engineer:

California (#T2363)
Professional Civil Engineer:

California (#C54235)
*Experience prior to joining the firm
387
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 64 Senior Traffic Engineer / Manager - Transportation Services / City Traffic Engineer | City of Orange, CA*
Amir utilized his many years of experience to manage various traffic and civil engineering projects. He also managed traffic and civil construction projects during his employment with the City of Orange. Amir planned, managed, and provided oversight of the daily functions, operations and activities of traffic and transportation division of the City of Orange, including Traffic Management Center (TMC), traffic signal timing, operation and maintenance, review of residential and commercial developments; and was responsible for leading the traffic operation and transportation planning team. Amir also managed and participated in the development and implementation of goals, objectives, policies and priorities for the division. He also provided recommendations within departmental policy regarding appropriate service and staffing levels.

Oversaw and participated in the development and administration of the operation and capital improvement division annual budget; participated in the forecast of funds needed for staffing, equipment, materials, and supplies; monitored and approved expenditures; implemented adjustments. Attended and participated as City Traffic Engineer at city council, commissions, committees, and other agency meetings as required. Prepared and presented technical information, analysis, and recommendations. Oversaw the development of consultant requests for proposals for professional and construction services and the advertising and bid processes; evaluated proposals and recommended project award; administered contracts after award.

Collaborated with other city departments, police, fire, Caltrans, OCTA and other outside agencies to plan, implement and complete projects and initiatives to improve traffic safety and mobility around the city. Identified outside funding sources for city traffic and transportation programs, directed and prepared funding applications.

Responded to traffic and transportation related resident and commuters’ inquiries and requests. Oversaw traffic signal plans preparation and coordination programs, developed and approved traffic engineering standards and policies for the city.

Reviewed and analyzed studies, environmental impact reports, proposals, and negotiations with other agencies to secure projects and policies favorable to the city.

Senior Civil Engineer / Associate Civil Engineer / Assistant Civil Engineer / Engineering Tech. II | City of Orange, CA*
Planned, prioritized, assigned, supervised, reviewed and participated in the work of staff responsible for providing traffic engineering services within the assigned section. Developed and prepared construction plans, specifications, and estimates for various in - house design projects including traffic, streets, sewers and storm drains. Participated in the selection of engineering staff; provided or coordinated staff training; worked with employees to correct deficiencies; implemented Amir Farahani, TE, PE (cont.)
Senior Traffic Engineer
388
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 65 discipline procedures. Reviewed and prepared transportation and traffic engineering studies; prepared requests for proposals; reviewed environmental impact reports; reviewed transportation models. Performed project management for the design and construction of capital improvement projects for city departments including public works, community services, economic development and fire. Ensured conformance with state, federal, and local standards and procedures in carrying out projects.

Prepared and applied for project funding from federal, state, and utility grant programs including Highway Bridges Rehabilitation and Replacement (HBRR), Arterial Highway Rehabilitation Program (AHRP), Safe Route to Schools (SR2S / SRTS), Highway Safety Improvement Program (HSIP), Transportation Enhancement Activities (TEA), Orange County Sanitation District Cooperative Projects, State - Local Transportation Partnership Program (SLTPP), Community Development Block Grant (CDBG) and City Engineers Flood Control Advisory Committee (CEFCAC).

Interacted and communicated with the public, city management and departments, contractors, consultants and other governmental agencies to resolve issues.

Prepared and processed various documents including council agenda reports, consultant agreements, hydrology and hydraulic studies, requests for proposals, plan check, consultant selection, bid evaluation, insurance certificates, environmental compliance, encroachment permits, right - of - way and reimbursement packages.

Revised and maintained city standard plans and specifications.

Amir Farahani, TE, PE (cont.)
Senior Traffic Engineer
389
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 66 Shawnt Babakhanian has 30 years of experience in the preparation of contract drawings for a variety of civil engineering, transportation engineering and structural engineering projects. He also has extensive knowledge and expertise in both IT and CAD management.

Experience
Bartlett Avenue Rehabilitation Project | City of Adelanto, CA CAD Manager. Responsible for overseeing the project’s drafting, design, cost estimates, and specifications for improvements to the asphalt pavement, cross gutter, ADA curb ramps, and water main replacement. The project was not only completed according to the client’s requirements but also finished on schedule and well within the budget. In addition, oversaw drafting quality assurance and quality control to meet the standards and requirements set forth by the City of Adelanto.

Bellflower Street Rehabilitation Project | City of Adelanto, CA CAD Manager. Improvements to the asphalt pavement, cross gutter, ADA curb ramps, and water main replacement. Responsible for reviewing the project’s specifications and cost projections, as well as the design and drafting. In addition, responsible for drafting quality assurance and quality control to meet the standards and requirements set forth by the City of Adelanto.

SB1Street Enhancement Project | City of Huntington Park, CA Designer / Drafter. Sanitary sewer, water, and street improvement plans, including plan and profile, cross - sections, construction details, utility, and traffic striping plans.

Was also involved in preparing specifications and cost estimate for the project, which required the replacement of the old sanitary sewer and water system with a newer system that was up to standards. In addition, was responsible for quality assurance / quality control for drafting of civil plans during the project.

Water Main Replacement Project | City of Huntington Park, CA Designer / Drafter. Main water line, fire hydrants, water meters, and backflow prevention element of the project. Also in charge of the field investigation, specifications, and cost estimate. In addition, was responsible for quality assurance / quality control for project plans and details during the project. The project was completed per standard details, on time, and within budget.

Various Residential Street Improvements (FY 20 - 21)| City of Hawaiian Gardens, CA Designer / Drafter. Street improvements, signing and striping, and utility plans. In addition, was involved in design, specifications and cost estimates preparation.

Responsible for quality assurance / quality control for project plans and details to ensure the project was completed while adhering to city requirements. The project was completed on time and within budget.

Shawnt Babakhanian
CAD Manager
Education
AutoCAD, Glendale College
AutoCAD Civil 3D, Westech College
Microstation, Westech College
Land Development Desktop, Westech
College
*Experience prior to joining the firm
390
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 67 Schmidt Road Street Improvement Project | City of El Monte, CA Designer / Drafter. Street improvements, signing and striping plans. In addition, was involved in specifications and cost estimates preparation. He was responsible for quality assurance / quality control for project plans and details to ensure the project was completed while adhering to city requirements. The project was completed on time and within budget.

Alley Improvement, Various Street Rehabilitations and Water Main Replacement Project | City of Brea, CA
Designer / Drafter / Utility Coordinator. Responsible for designing / drafting alley pavement, longitudinal gutter, street improvements, signing and striping and utility improvements within the project area. In charge of drafting the main water line system, fire hydrants, fire services, water meters and backflow prevention for the project. Also, responsible for acquiring and verifying utility plans by coordinating with utility agencies. Shawnt oversaw quality control for the project to ensure that it was completed while observing city requirements.

Alley and Industrial Street Rehabilitation Project | City of Brea, CA Designer / Drafter. Responsible for the preparation of plans, profiles, and details, and involved with the field investigation that included field surveys of the asphalt pavement, sidewalks, curbs and gutters, driveways, and curb ramps. Also involved in specifications and cost estimate preparation. Responsible for quality assurance / quality control for the project’s plans and details to ensure that the project was completed while adhering to city requirements. The project was completed on time and within budget.

Lincoln Park Improvement | City of Anaheim, CA
Designer / Drafter. Project included construction of roadway improvements, including removal of existing improvements including AC pavement, concrete sidewalk, curbs and gutters, storm drain improvements and landscaping, and construction of new street and sidewalk improvements, including new concrete curb and gutter, concrete sidewalk, storm drain catch basins, drainage inlet modifications and AC pavement sections. In addition, was responsible for quality assurance / quality control for drafting of civil plans during the project.

Safe Routes to School - Pleasant View, Vineland and Tracy Elementary Schools | City of Baldwin Park, CA
Designer / Drafter. Preparation of PS&E for new signing and striping, curb extensions, new curb and gutter, sidewalks, ADA - compliant ramps, and pavement. Other improvements include the installation of detectable warning surfaces. The project consists of work on nine intersections.

Shawnt Babakhanian (cont.)
CAD Manager
391
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 68 Bahar Baradaran has four years of experience in civil engineering that includes roadway infrastructure projects.

Experience
Bellflower Street Rehabilitation Project | City of Adelanto, CA Engineering Assistant for designing and planning the primary pavement rehabilitation, water main and sanitary sewer lines. Also designed the pavement based on the geotechnical report and was responsible for coordinating with geotechnical investigators to identify the pavement design and requirements.

Prepared plans, profiles, specifications and cost estimate for this project. Also sent utility notices and coordinated with Edison, water and gas companies.

Bartlett Avenue Rehabilitation Project | City of Adelanto, CA Engineering Assistant who gathered data from survey and site inspections to design and plan the main water and sewer lines. Collaborated with client to develop water and sewer improvement plans and profiles in compliance with city regulations.

Conducted extensive research and analysis of existing infrastructure, topography and environmental factors to develop effective solutions. Designed and drafted detailed plans and profiles using Civil 3D. Managed project timelines and prepared cost estimate to ensure it was within budget limits and provided the best value.

SB1 Santa Fe Avenue and Miles Avenue | City of Huntington Park, CA Engineering Assistant who was instrumental in sketching plans for sanitary sewer, water and street enhancements. This included detailed plan, cross - sectional views and traffic striping. Played an essential role in helping with specifications and calculating the cost estimate for the project, which entailed updating the outdated water and sanitary sewer systems to meet current standards.

CIP Priority 2B Street Improvement Project | City of Lynwood, CA Engineering Assistant who created all sheets for improvements and utility relocations for the city’s Phase 2 CIP Street Improvement Project. Tasks included coordinating with utility companies and conducting field investigations to obtain measurements of existing site and proposed improvements. Prepared specification package per Greenbook and has developed quantities for removals and improvements for cost estimation.

ATP Cycle 2 Lynwood Community Linkages to Civic Center and Long Beach Boulevard | City of Lynwood, CA
Engineering Assistant responsible for creating the signing and striping sheets for the project. Work involved creating the construction notes and designing the new striping on AutoCAD.

Bahar Baradaran, EIT
Engineering Assistant
Education
M.S. Civil and Environmental
Engineering with a focus on Water
Resources, California State University,
Fullerton
B.S. Civil Engineering, University of
Science and Culture, Iran
Registrations
Engineer in Training (EIT):

California (#178797)
*Experience prior to joining the firm
392
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 69 Street Rehabilitation Project | City of Bell Gardens, CA Engineering Assistant responsible for developing street cross section and base map; performed field reconnaissance to inspect and verify surface indications of utilities.

IE is providing design, project management, bidding of contract, construction management and inspection, as well as federal fund administration for this project that involves removal of existing AC paving and paving of AC pavement and concrete improvement reconstruction, including replacing existing curb and gutter, sidewalk, driveway approaches, access ramps, and adjustment of utility covers, traffic striping, markers, pavement markings and curb painting.

Internship | City of Irvine, CA*
Intern who acted as a sustainability manager assistant. Aided in the development of plans on drainage, road, and residential projects and helped with environmental studies, permitting and alternative analyses. Observed the preparation, function and process of tender and contract documents in action and assisted civil engineers to fulfill these. Also collaborated with research on other projects as a team member.

Internship at William Simpson and Associates | City of Lake Forest, CA* Intern who drafted detail of sections, plans, and elevations with AutoCAD. She handled cost of materials estimations, report and document tracking, project documentation, on - site project visits, and building permit applications. Bahar shadowed senior civil engineer on a project to determinate the on - going stability of concrete stabilized footpath around a commercial center.

Bahar Baradaran, EIT (cont.)
Engineering Assistant
393
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 70 Experience
Infrastructure Engineers, a Bowman company | Brea, CA
Engineering Assistant. Performed tasks contributing to the completion of various public works projects under the supervision of a professional civil engineer registered in the State of California. These tasks include CAD drafting / design; grading and drainage design, preparation of plans, specifications, and estimates (PS&E); submittal and plan check coordination with agencies, clients, and subconsultants; preparation of Standard Urban Stormwater Mitigation Plans (SUSMP) and Water Quality Management Plans (WQMP); quantity takeoff, earthwork calculations, and field checks.

Bellflower Avenue Rehabilitation Project | City of Adelanto, CA Engineering Assistant. Assisted in the development of preliminary Plans, Specifications and Estimate (PS&E) for full - depth asphalt pavement rehabilitation, including redesigning curb ramps to meet ADA compliance. Pavement design was based on geotechnical recommendations and city requirements. Coordinated with land surveyor to identify limits of right - of - way and required dedication.

Bartlett Avenue Rehabilitation Project | City of Adelanto, CA Engineering Assistant. Assisted in the development of Plans, Specifications and Estimate (PS&E) for full - depth asphalt pavement rehabilitation, including redesigning curb ramps to meet ADA compliance. Pavement design was based on geotechnical recommendations and city requirements. Coordinated with land surveyor to identify limits of right - of - way and required dedication.

San Gabriel River Greenway and Neighborhood Connection Project | City of Baldwin Park, CA
Engineering Assistant. Assisted in the development of Plans, Specifications and Estimate (PS&E) for the landscaping of a 2.3 - mile shared - use bike trail currently under construction. Coordinated for plan review and project compliance on behalf of the City of Baldwin Park with various governmental agencies, including United States Army Corps of Engineers (USACE), Los Angeles County Flood Control District (LACFCD), and Los Angeles County Department of Public Works (LACDPW). Contacted vendors to incorporate project elements crucial to the project scope. Coordinated with the Landscape Architectural subconsultant to ensure landscape and irrigation plans comply with requirements of the aforementioned agencies.

Big Dalton Wash Greenway and Neighborhood Connection Project | City of Baldwin Park, CA
Engineering Assistant. Assisted in the development of Plans, Specifications and Estimate (PS&E) for a 2.8 - mile shared - use bike trail. Coordinated for plan review and project compliance on behalf of the City of Baldwin Park with various governmental agencies, including United States Army Corps of Engineers (USACE), Los Angeles Michael Dela Cruz, EIT
Engineering Assistant
Education
B.S. Civil Engineering, California State
University, Los Angeles
Registrations
Engineer in Training (EIT):

California
*Experience prior to joining the firm
394
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 71 County Flood Control District (LACFCD), Los Angeles County Department of Public Works (LACDPW), Southern California Regional Rail Authority (SCRRA) and neighboring municipalities. Contacted vendors to incorporate project elements crucial to the project scope.

P .A. Arca Engineering, Inc. | City of Carson, CA
Junior Civil Engineer. Performed tasks contributing to the completion of various private land development and public works projects under the supervision of a professional civil engineer registered in the State of California. These tasks include:

CAD drafting / design, grading and drainage design, low impact development (LID) design, preparation of SUSMP and WQMP , preparation of Storm Water Pollution Prevention Plan (SWPPP) reports, SWPPP inspections, hydrology studies, cost estimate, quantity takeoff, earthwork calculations, construction administration and support, sewer area studies, slope density analysis, and field checks.

Michael Dela Cruz, EIT (cont.)
Engineering Assistant
395
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 72 Jaelin Murray has two years of experience in civil engineering which includes roadway and stormwater projects.

Experience
ATP Cycle 5 Citywide Complete Street Improvements Project | City of Bell Gardens, CA
Engineering Assistant. Jaelin was instrumental in drafting base maps from survey and assessor maps. Also responsible for creating existing utility maps and creating plan cut sheets.

South Verdugo Road Pavement Rehabilitation | City of Glendale, CA Engineering Assistant. Played an essential role in conducting field project walks utilizing GIS to identify damaged or hazardous utilities, concrete and pavement. She also checked and identified sidewalks, driveways and ramps for proper width, height and slope. Prepared plan sheets for improvements, designing driveways and ramps.

Industrial Commercial Facilities Program Project | City of Bell Gardens, CA Engineering Assistant. Responsible for creating inventory and gathering data on each commercial and industrial facility that meets need for a NPDES permit. Tasks also included coordinating appointments for inspection, conducting stormwater pollution prevention inspections of facilities, and record keeping photos, inspection forms, and notes.

Infrastructure Engineers, a Bowman company | Brea, CA
Intern. Aided development of plans for beautification and rehabilitation projects.

Jaelin also aided in the development of specifications packages. Coordinated utility notices for traffic and rehabilitation projects. Handled quantities and subsequent cost estimates for various roadway improvements and beautifications. Drafted preliminary design of retaining ring wall design.

Internship | City of Dana Point, CA*
Capital Improvement Project Intern. Drafted project exhibits and utility maps with AutoCAD. She streamlined records of city property inventory, construction budgeting and bid scheduling. Aided in the development of roadway project plans and as - builts. Accompanied, conducted field walks for topography, drainage, and roadway damage assessment. Navigated records requests for right of way, building plans and utility maps.

Jaelin Murray, EIT
Engineering Assistant
Education
B.S. Civil Engineering with a
specialization in Structural
Engineering, University of California,
Irvine
Registrations
Engineer in Training (EIT):

California (#178483)
*Experience prior to joining the firm
396
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 73 Hamed Habibi has 12 years of experience in traffic engineering, especially in Traffic Signal Planning, Actuated Traffic Signal Systems, and ITS systems. His experience includes drafting, and designing traffic signal plans, writing traffic signal warrants and stop sign warrant reports, creating cost estimates, generating specifications, designing street overlays, and generating conceptual imagery for exhibits in different projects.

Experience
Quiet Zone Preparation of PS&E for 12 Railroad HWY Crossings | City of Covina, CA Engineering Assistant. Responsible for preparation of proposed Improvement plans for 12 highway / railroad crossings including quadratic gates, medians, pavement, traffic striping, markings and signage in accordance with CA - MUTCD and Metrolink Standards.

Left Turn Warrant Studies for Five Intersections at Slauson Avenue | City of Huntington Park, CA
Engineering Assistant. Responsible for creating the left turn warrants report and verifying the warrant conditions satisfied on the CA - MUTCD. Designed a collision diagram, conducted an analysis on the collision history of the intersections, simulated these five intersections in Synchro for five different scenarios, conducted pedestrian safety analysis and provided a field review of existing conditions.

All - Way Stop Sign Warrant Analysis – Florence Place and Scout Avenue Intersection | City of Bell Gardens, CA
Engineering Assistant. Responsible for creating the all - way stop warrant report and verifying the warrant conditions satisfied on the CA - MUTCD. Designed a collision diagram, conducted an analysis on the collision history of the intersection, Sight Distance Evaluation and provided a field review of the existing conditions.

All - Way Stop Sign Warrant Analysis – Jaboneria Road and Gotham Street Intersection | City of Bell Gardens, CA
Engineering Assistant. Responsible for creating the all - way stop warrant report and verifying the warrant conditions satisfied on the CA - MUTCD. Designed a collision diagram, conducted an analysis on the collision history of the intersection, Sight Distance Evaluation and provided a field review of the existing conditions.

Speed Zone Survey and Speed Limit Study for Garfield Avenue | City of Bell Gardens, CA
Engineering Assistant. Responsible for creating Speed Survey Analysis report in accordance with CA - MUTCD and CVC. Conducted an analysis on the collision history of the intersection, Road Condition Analysis and provided a field review for achieving the efficient speed limit.

Hamed Habibi, MS
Engineering Assistant
Education
M.S. Transportation Planning,
International University of Qazvin, Iran
B.S. Civil Engineering, Sharif University
of Technology, Tehran, Iran
Registrations
SCATS Training Course / RTA / New
South Wales - Sydney - Australia
*Experience prior to joining the firm
397
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 74 Transportation Assessment for the Rancho Adelanto City Center Project | City of Bell Gardens, CA
Engineering Assistant. Responsible for creating the Transportation Assessment report including Project Trip Generation based on ITE - Trip Generation Manual (last edition), Project Trip Distribution and Trip Assignment, Vehicle Miles Traveled (VMT) Assessment, Traffic Signal Warrants Study, analysis of other modes of transportation (non - automobile facilities) for the project. This involved using AutoCAD to create the Conceptual Traffic Signal Plan and Access Improvement for the proposed intersection.

All - Way Stop Sign Warrant Analysis – Bellflower Street and Lawson Avenue Intersection | City of Adelanto, CA
Engineering Assistant. Responsible for creating the all - way stop warrant report and verifying the warrant conditions satisfied on the CA - MUTCD. Designed a collision diagram, conducted an analysis on the collision history of the intersection, Sight Distance Evaluation and provided a field review of the existing conditions.

All - Way Stop Sign Warrant Analysis – Stevens Street and Bartlett Avenue Intersection | City of Adelanto, CA
Engineering Assistant. Responsible for creating the all - way stop warrant report and verifying the warrant conditions satisfied on the CA - MUTCD. Designed a collision diagram, conducted an analysis on the collision history of the intersection, Sight Distance Evaluation and provided a field review of the existing conditions.

All - Way Stop Sign Warrant Analysis – Stevens Street and Kemper Avenue Intersection | City of Adelanto, CA
Engineering Assistant. Responsible for creating the all - way stop warrant report and verifying the warrant conditions satisfied on the CA - MUTCD. Designed a collision diagram, conducted an analysis on the collision history of the intersection, Sight Distance Evaluation and provided a field review of the existing conditions.

New Traffic Signal at Imperial Hwy and Ruth Avenue Intersection | City of Lynwood, CA
Engineering Assistant. Responsible for the design of the traffic signal, striping plans, specifications, and cost estimate for the new traffic signal intersection. This involved using AutoCAD to create the general notes, construction notes, conductor schedule, traffic signal plan and phase diagram for this project.

Pedestrian Hybrid Beacon(HAWK), All - Way Stop Sign and Traffic Signal Warrant Analysis at Santa Fe Avenue and Weber Avenue Intersection | City of Lynwood, CA Engineering Assistant. Responsible for creating the PHB, all - way stop sign, and traffic signal warrant report and verifying the warrant conditions satisfied on the CA - MUTCD. Designed a collision diagram, conducted an analysis on the collision history of the intersection, Sight Distance Evaluation and provided a field review of the existing conditions.

Hamed Habibi, MS (cont.)
Engineering Assistant
398
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 75 Experience
Bill Carr Surveys, Inc. | Anaheim, CA*
CAD Drafter. Anchor bolt sheet preparation. Provided coordinates to locate U.S. Site location. Checked dimensions, scaled and aligned the drawings, changed layer colors and dim to start a new drawing or match previous. Page setup, pdf and plot, export all the cogo pnts data out. Imported all the data into excel spreadsheet, data entry grids, bbp, pattern types info, extract data and processed them into AB Report. Sent to client.

GKC Engineering Corp. | Irwindale, CA*
CAD / System Manager. Drew rough and detailed scale plans using computer - assisted drafting (CAD) equipment and software in the design of foundations, buildings, and structures from start to finish, based on preliminary concepts, sketches, survey points, engineering calculations, specification sheets, and other data, in support of engineering. Prepared professional sheets, drawings, and documents, meeting contractor specifications and compliant with industry standards, legal requirements, municipal codes, and regulations. Developed plans for grading, exterior buildings, parking lots, storm drains, street improvements, and street lighting within the confines of the property; some residential experience. Generated cross section views; edited existing ground profiles and finished ground profiles. Surveyed construction documents from points to drawing. Worked closely with designers and drafters and supported engineering staff to ensure coordination with interior design. Collected and processed information and data for engineering development by researching and obtaining standards / codes required by client and jurisdiction through interaction with necessary personnel to accurately and efficiently develop plans
CAD Operator | CA*
Drew rough and detailed scale plans using computer - assisted drafting (CAD) equipment and software in the design of foundations, buildings, and structures from start to finish, based on preliminary concepts, sketches, engineering calculations, specification sheets, and other data, in support of engineering. Prepared professional sheets, drawings, and documents, meeting contractor specifications and compliant with industry standards, legal requirements, municipal codes, and regulations.

Developed plans for grading, exterior buildings, parking lots, storm drains, street improvements, and street lighting within the confines of the property; some residential experience. Generated cross section views; edited existing ground profiles and finished ground profiles. Worked closely with designers and drafters and support engineering staff. Collected and process information and data for engineering.

Annie Li
CAD Technician
Education
B.S. Electronics, Suzhou Advanced
Electronic College, Suzhou, China
Certifications
Drafting - Computer Aided Technical
Modeling and Animation Certificate,
Pasadena City College
*Experience prior to joining the firm
399
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 76 Shawn Mousavi has seven years of experience in civil engineering as a consultant and designer. His experience includes drafting, designing traffic signal and pedestrian hybrid beacon plans, writing traffic signal warrant and stop sign warrant reports, writing engineering and traffic surveys, preparing parking studies, preparing left - turn studies, developing systemic safety analysis report program (SSARP), analyzing Level of Service (LOS) through Synchro program, creating cost estimates, generating specifications, designing street overlays, creating GIS maps and databases, generating conceptual imagery for exhibits, using PAVER for data analysis of the street networks, preparing pavement management system (PMS) report, and managing and hiring new interns and civil engineering assistants.

Experience
Slauson Avenue Congestion Relief Improvement Project | City of Huntington Park, CA
Engineering Associate. Created traffic signal modification plans for six signalized intersections. Placed video detection equipment, updated cabinets and signal equipment, installed new conduits and conductors, new traffic signal poles at the intersections and prepared specifications and cost estimate.

Traffic Signal Warrant Analysis on Olympic Boulevard and Allston Street / Hereford Drive Intersection | City of Montebello, CA
Supervising Engineer. Responsible for creating the signal warrant report and verifying the warrant conditions satisfied on the CA - MUTCD. Designed a collision diagram, conducted an analysis on the collision history of the intersection and provided a field review of the existing conditions.

Engineering and Traffic Survey | City of Montebello, CA Supervising Engineer. Updated the engineering and traffic survey to determine the posted speed limits throughout the city. Conducted a field investigation, analyzed SWITRS data, created speed survey maps, analyzed the speed and traffic data in accordance with the CVC code, and prepared a final report.

Pavement Management System (PMS) Update Report | City of Montebello, CA Supervising Engineer. Responsible for inspecting and creating an inventory of the conditions within the City of Montebello’s roadway network. Work included generating excel inventory, creating a GIS map and database, preparing a five - year budget to raise the overall pavement condition index within the city, and creating a comprehensive report.

All Way Stop Warrants at 6th Street and West Harding Avenue | City of Montebello, CA
Supervising Engineer. Responsible for creating the all - way stop warrant report and verifying the warrant conditions satisfied on the CA - MUTCD. Designed a collision diagram, conducted an analysis on the collision history of the intersection, and provided a field review of the existing conditions.

Shawn Mousavi, MSCE, PE, QSP / QSD
Associate Engineer
Education
M.S. Civil Engineering, California State
Polytechnic University, Pomona
B.S. Civil Engineering, California State
Polytechnic University, Pomona
Registrations
Professional Civil Engineer:

California (#91696)
QSP / QSD: California (#91696)
*Experience prior to joining the firm
400
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 77 Corridor Traffic Study Along Lincoln Avenue Between Wilcox Avenue and Montebello Boulevard | City of Montebello, CA
Engineering Associate. Prepared a traffic calming report throughout the Lincoln corridor. Analyze the existing peak hour intersection capacity and parking capacity, review three - year collision history and intersection sight distance, evaluate vehicular speeds and calming measures, prepare future capacity analysis with conceptual roundabout design, and determine the future capacity of on - street parking.

All Way Stop Sign Warrant Analysis 4th Street and Mines Avenue | City of Montebello, CA
Engineering Assistant. Responsible for creating the all - way stop warrant report and verifying the warrant conditions satisfied on the CA - MUTCD. Designed a collision diagram, conducted an analysis on the collision history of the intersection and provided a field review of the existing conditions.

HSIP Cycle 7 Project - Various Intersections Improvements | City of Montebello, CA Engineering Assistant. Upgrade the signal hardware and improve signal timing for the three intersections. This included changing the phase diagram to protective - permissive and relocating existing k - rails to improve traffic flow and safety.

Responsible for the design, specification, and cost estimate of the three traffic signal intersections.

Beverly Blvd Street Improvements Project | City of Montebello, CA Engineering Assistant. Responsible for preparing plans, specification, and cost estimates. Specific work included detailed field observations, design of necessary street improvements, implementing AC pavement and sidewalk repairs, updating ramps to become ADA compliant and maximizing use of federal funds.

Arroyo Drive Street Improvements | City of Montebello, CA Engineering Assistant. Responsible for developing street cross section and base map; performed field reconnaissance to inspect and verify surface indications of utilities. IE provided design, project management, bidding of contract, construction management and inspection, as well as federal fund administration for this project that involves removal of existing AC paving and paving of AC pavement and concrete improvement reconstruction, including replacing existing curb and gutter, sidewalk, driveway approaches, access ramps, and adjustment of utility covers, traffic striping, markers, pavement markings and curb painting. The project runs from Arroyo Drive from Astra Drive to Rose Glen Ave.

Shawn Mousavi, MSCE, PE, QSP / QSD (cont.)
Associate Engineer
401
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 78 Arjan Idnani worked on major infrastructure projects and on public works improvement and rehabilitation projects throughout California. His experience includes work on land development projects, capital improvement projects, construction management, project management, and administration. Arjan’s experience also includes street improvement projects, water main line replacements, slurry seal improvements, traffic signal improvements, and sanitary sewer improvements in Cities of Bell Gardens, Montebello, Baldwin Park, South Gate, and South El Monte.

Experience
Construction of SB1 Street Enhancement Project | City of Huntington Park, CA Project Manager. This project consisted of trenching, pipe layout, backfilling, pipe abandonment, pipe lining, demolition of existing improvements, relocation of utilities, construction of concrete improvements like sidewalks, curb and gutters, curb ramps, driveways, cold milling, concrete and asphalt paving, and placement and connection of traffic signal equipment.

Construction of Annual Street Rehabilitation Project Phase 2B | City of Compton, CA
Project Manager. This project consisted of edge milling of existing pavement, 4 in of cold - in - place - recycling (CIR), material testing, 1 - 1 / 2 in to 2 in asphalt rubber hot mix (ARHM) overlay, removal and reconstruction of damaged PCC sidewalks, curbs and gutters, cross gutters, local depressions, driveway approaches, added medians, future irrigation conduit installation, ADA curb ramps; utility adjustments, reconnecting existing curb drains, installation of new water meter, traffic loop replacement, replace traffic signing, thermoplastic striping and pavement markings; and traffic control and other associate elements of work.

Construction of Urban Bicycle Project | City of Lynwood, CA Project Manager. This project included the construction of HMA Bike Path, curb and gutters, curb ramps, retaining walls, concrete swales, concrete box culverts, chain link fence, permeable pavers, installation of removable bollards, gates, main waterline, irrigation, install trees and shrubs, mulch, install single and dual ARM Pedestrian, lighting poles and luminaire, furnish and install way finding and interpretive signs, bicycle racks, fountains, and striping.

Construction of Central Park West | City of Baldwin Park, CA Project Manager. This project included the construction of Irrigation System and Landscaping, security lighting system, improvement of park area, construction of restroom / storage area, installation of storm drain, sewer and domestic water system, construction of playground area and tot lot areas with playground equipment, construction of volleyball and basketball courts and installation of bicycle rack, shade structures, BBQ’s, picnic tables and drinking fountains.

Arjan Idnani, MSCE
Construction Assistant Manager
Education
M.S. Civil Engineering, California State
University, San Jose
B.S. Civil Engineering, California State
Polytechnic University, Pomona
*Experience prior to joining the firm
402
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 79 Civil Engineer | City of South El Monte, CA
Arjan operated as a permitting engineer for the city, issuing building permits and conducting Inspections for permits and off - site improvements for buildings and tract maps. He wrote and reviewed RFPs and provided project management staff reports for City Council meetings. Some projects he was involved with included the pool plaster project (including removal of existing plaster, tiles, and railings and installing new plaster and tiles and railings); skate park construction (including removal of existing curb and gutter, sidewalk, and benches, and construction of curb ant gutter, sidewalk, ramp, drain and trellis); and Farmer Avenue Patch project, which included removal of existing pavement, compacting existing base rock, and installing 4 - in asphalt.

Santa Anita Traffic Signal Modification | City of South El Monte, CA Construction Manager. This project included installation of new traffic signal poles, a new equipment cabinet, and a video camera and removing and replacing access ramps and striping.

Construction Manager | City of Montebello, CA
• Bluff Road Improvements. This project included cold milling existing 2 - in - deep asphalt and installing 2 - in of asphalt overlay along Bluff Road. In addition, construction of new curbs and gutters, sidewalks, and driveways and access ramps were performed as well as installing traffic loops and striping. • Via Compo Improvements. This project included cold milling existing 3 - in - deep asphalt and installing 3 - in of asphalt overlay. Also removed and replaced damaged curbs and gutters, sidewalks, and driveways, and installed traffic loops and striped.
• Beverly Boulevard Improvements. This federally funded project included cold milling existing 3 - in - deep asphalt and installing an overlay of 3 - in of asphalt, removing and replacing damaged curbs and gutters, sidewalk, and driveway, and access ramps; pruned trees, installed traffic loops, raised manholes, striped and constructed bus pads.
• Flotilla Avenue Improvements. This project included replacement of damaged 12 - in clay sewer pipe in several locations as well as cold milling existing 2 - in - deep asphalt and installing an overlay of 2 in of asphalt. Removed and replaced damaged curbs and gutters, sidewalk driveways, and access ramps. Raised manholes, installed traffic loops, and striped.
• Garfield Avenue Improvements. This project included cold milling existing 3 - in - deep asphalt and installing an overlay of 3 in of asphalt, removing, and replacing damaged curbs and gutters, sidewalks, and driveways, and access ramps.

Constructed bus pads, installed traffic loops, and striped.

Arjan Idnani, MSCE (cont.)
Construction Assistant Manager
403
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 80 Most of Nathan Kirby’s career has been spent in service to municipalities in Los Angeles County. He has held positions in which he has been responsible for administrative duties related to public works projects, construction and quality control.

Experience
Complete Street Improvements on Maine Avenue Project | City of Baldwin Park, CA Served as project assistant. Scope of work included removal and replacement of sidewalk, curb and gutter, driveway approach, catch basins, and manholes, rain garden, landscape, new pavement, which included manhole adjusting and streetlight system. Responsible for preparations and / or organization of all construction documents including Contract Change Orders, Meeting Agendas, Progress Payments, Project Budgets, RFI’s, Right of Way Maps, Daily Reports and Weekly Statements.

Garfield Avenue Improvements Project | City of Bell Gardens, CA Served as project assistant. Scope of work included removal and replacement of sidewalk, curb and gutter, traffic loops, regulatory signs, curb ramps, and new pavement, which included manhole and valve adjusting. Responsible for preparations and / or organization of all construction documents including Contract Change Orders, Meeting Agendas, Progress Payments, Project Budgets, RFI’s, Right of Way Maps, Daily Reports and Weekly Statements.

ATP Cycle 2 Uncontrolled Crosswalk Pedestrian Safety Enhancements Improvements Project | City of Huntington Park, CA
Served as project assistant. Scope of work included removal and replacement of traffic signal systems, vehicle and pedestrian heads, cabinets, controllers, pedestrian push buttons, curb and gutter, curb ramps, flashing beacon, HAWK signal, street name signs, traffic striping and tree removal. Responsible for preparations and / or organization of all construction documents including Contract Change Orders, Meeting Agendas, Progress Payments, Project Budgets, RFI’s, Right of Way Maps, Daily Reports and Weekly Statements.

Water Main Replacement Project | City of Huntington Park, CA Served as project assistant. Scope of work included removal and replacement of concrete sidewalk, curb and gutter, driveway approaches, curb ramps, 8 - in and 10 - in water main line, water meters, water service lines, tree pruning, and new pavement, which included manhole and valve adjusting. Responsible for preparations and / or organization of all construction documents including Contract Change Orders, Meeting Agendas, Progress Payments, Project Budgets, RFI’s, Right of Way Maps, Daily Reports and Weekly Statements.

Nathan Kirby
Construction Project Coordinator
Education
Business Administration, Cypress
College, Cypress, CA
*Experience prior to joining the firm
404
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 81 Imad Zureiqat has more than 40 years of experience in construction inspection and resident engineer tasks. He has been responsible for preparation of plans, cross - sections, details, and specifications for various civil and landscape projects. Imad has coordinated with other engineering disciplines, responded to plan check comments, and prepared material, take - off and cost estimates.

Experience
Urban Bicycle Project | City of Lynwood, CA
This project included construction of HMA bike path, curb and gutters, curb ramps, retaining walls, concrete swales, concrete box culverts, chain link fence, permeable pavers, installation of removable bollards, gates, main waterline, irrigation, installation of trees and shrubs, mulch, single and dual ARM Pedestrian, lighting poles and luminaire, furnishing and installing way - finding and interpretive signs, bicycle racks, fountains and striping.

Maine Avenue Improvement Project | City of Baldwin Park, CA Provided construction inspection of this project. The purpose of the project was to create neighborhood - friendly pedestrian and bicycle linkages serving the areas surrounding Maine Avenue. The sidewalks were widened by 2 ft, continuously on each side of the roadway; parking lanes have curb extensions at intersections and intermittent locations. Utilities were placed underground, and the driveway ramps were reconstructed to provide flat sidewalk paths across driveways. Lighting was improved and included pedestrian - scale lighting every 75 ft. Intersections were improved with new crosswalk markings, signal improvements, ADA Ramps, and a roundabout at Main Avenue / Olive Street with safety islands for pedestrians and bicyclists.

Long Beach Boulevard | City of Lynwood, CA
Provided compliance with plans, specifications, and the contract; oversaw traffic control, and provided daily log and inspection report entries, including pictures of the project. Reviewed and reported contractor claims, prepared weekly update reports, and reviewed contractor’s invoices, verified completed work and approved all quantities. IE provided construction management, inspection, and labor compliance that included roadway resurfacing of 192,779 sq. ft. with a section of 2 - in AC top course and 1 - in AC leveling course and 40,000 sq. ft. with a section of 2 - in of asphalt rubber hot mix (ARHM) over 1 / 2 - in SAMI sealant and 1 - in leveling course. Concrete improvements included 4 - in sidewalk, driveway approaches, cross gutters, curb and gutter, curb ramps, installation of 16 detectable warning surfaces on existing curb ramps and construction of six new bus pads.

Imad Zureiqat, EIT
Inspector
Education
M.S. Engineering, Moscow Civil
Engineering Institute
Registrations
Engineer - in - Training (EIT), California
General Building Contractor License
(B)
Certifications
Special Inspector Certificates:

Commercial Building Inspector
Structural Masonry
Reinforced Concrete
Prestressed Concrete Special Inspector
Associate
ACI Field Technician Grade 1
Division of the State Architect (DSA)
Regulations and Procedures (Part I, II,
III)
Languages
English (native / professional
proficiency)
Arabic (native / professional
proficiency)
Russian (elementary proficiency)
*Experience prior to joining the firm
405
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 82 Pacific Pedestrian & Transportation Improvement Project | City of Huntington Park, CA
Provided construction inspection, preparation of daily reports, review of change orders and progress payment requests, coordinated soils testing service and assisted with labor compliance.

Mines Avenue Street Improvements | City of Montebello, CA Construction management and inspection services included construction inspection, preparation of daily reports, review of change orders and progress payment requests, and coordinating soils testing services. The project involved roadway improvements, and pavement rehabilitation with concrete improvements of Frankel Avenue from Bluff Road to 5th Street and 16th Street from Madison Avenue to Harding Avenue.

Home 2 Suites | City of Montebello, CA
Provided construction inspection for this 203 - room, eight - story hotel. The hotel will be owned by the city and operated by Hilton. The hotel is expected to generate more than $1M to the city’s general fund each year.

City Sanitary Sewer System 20% CCTV Project | City of Montebello, CA Responsible for inspection of this project, including preparation of daily reports, review of change orders and progress payment requests. The project involved televising and rating of the condition of 20% of the city’s sanitary sewer system, including possible as - needed cleaning and draining.

Bluff Road Street Improvement | City of Montebello, CA
IE was retained by the city to provide design, project management, bidding, award of contract, construction management and inspection of the Bluff Road Street Improvement project from Sycamore Street to Date Street (.45 mile).

Maple Ave Street Improvements | City of Montebello, CA
Provided construction inspection of this roadway improvement project. IE prepared plans, specifications and estimates for roadway improvements, pavement rehabilitation, concrete improvements, ADA improvements and utility adjustments of Maple Avenue from Washington Boulevard to Mines Avenue. The pavement analysis and alternate rehabilitation strategies included budget analysis to complete as much of the street improvements within the fixed project budget.

Bicknell Park Pump Station Project | City of Montebello, CA IE provided project management, bidding, award of contract, construction management and inspection for the construction phase of Bicknell Park pump station. Imad was responsible for construction inspection, preparation of daily reports, review of change orders and progress payment requests.

Imad Zureiqat, EIT (cont.)
Inspector
406
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 83 Hormoz Vahid has more than 30 years of experience on a wide range of public works projects throughout Southern California. His experience covers both design and field engineering, including site preparation grading and drainage, roadways and streets, water and wastewater systems, utilities, storm water facilities, and construction inspection and administration. As a public works inspector, Hormoz works with the development and construction community to ensure compliance with municipal codes, standards, and specifications. Hormoz’s responsibilities also include research and implementation of new construction techniques and materials, and recommendations for specification changes, when warranted. He provides inspection services on capital improvement projects, subdivision development, and construction permit work. During his three decades of experience, Hormoz has developed comprehensive skills in site supervision, management techniques, report writing, research techniques, budget preparation, and administration. In addition, Hormoz has acquired exceptional knowledge of city, county, and federal laws on the public and private construction process.

Experience
Capital Improvements Projects | City of Montebello, CA
Hormoz has assisted the City of Montebello with various Capital Improvement Projects (CIP) and engineering tasks for over a decade.

Bluff Road Improvements | City of Montebello, CA
As CIP Manager Hormoz’s responsibilities included review of bid proposals, contract agreements, performance and material bonds, issuing addenda, scheduling pre - construction conferences, preparation of change orders, and reviewing certified payroll and billing. Prepared staff reports to be presented to city council. Project construction cost was $200,000, and the project was completed with a savings of $10,000.

Via Campo Street Improvements | City of Montebello, CA
Responsibilities included review of bid proposals, contract agreements, performance and material bonds, issuing addenda, scheduling pre - construction conferences, preparation of change orders, and reviewing certified payroll and billing. Prepared staff reports to be presented to city council. Project construction cost was $303,000, and the project was completed on time, with a savings of $12,000.

Garfield Avenue Improvements | City of Montebello, CA
Responsibilities included monitoring compliance with plans and specifications, attending meetings and preparing daily inspection reports, measuring field quantities, monitoring traffic control, monitoring extra work and assisting in the processing of change orders, and developing a punch list. Project construction cost was $784,000 and the project was completed on time with a savings of $20,000.

Hormoz Vahid
Inspector
Education
B.S. Civil Engineering, Texas A&M
University
Registrations
40 Hr. HAZWOPER, Certificate
(#2401404)
Deputy Inspector #561, City of Irvine
(concrete, steel, masonry, and asphalt)
Moisture Density Nuclear Gauge
Certification - Troxler Laboratories
Final Inspection Orientation
Certificate, California Governor’s Office
of Emergency Services
*Experience prior to joining the firm
407
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 84 Beverly Boulevard Improvements | City of Montebello, CA Responsibilities consisted of inspection of daily construction activities, monitoring compliance with approved plans and specifications, conducting contractor interviews, preparing change orders, verifying quantities, and reviewing billings.

Project construction cost was $418,000; the project was completed on time with savings of $1,500.

Public Works Inspector / Permit Engineer | City of Bell Gardens, CA Under the general supervision of the City Engineer, Hormoz was responsible for processing public works permits and conducting inspections. He was responsible for investigating public works construction - related citizen complaints, reporting observed safety violations to City Risk Manager, and reviewing and verifying a variety of construction documents, such as plans and specifications, permits, and estimates.

He was also tasked with ensuring that all the permits given to construction are in accordance with legal contracts and for maintaining the uniform traffic control devices. Monitored all public complaints regarding construction and resolved them efficiently.

Lotus Consulting Engineers, Inc. | Los Alamitos, CA*
Under supervision of Licensed Land Surveyor, performed site surveying and construction surveying. Performed soils and asphalt testing.

Hormoz Vahid (cont.)
Inspector
408
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 85 Subconsultants Information
Company Name
Dennis Janda, Inc.

Project Function
Land Surveying
Company Address
42164 Remington Avenue
Temecula, CA 92590
Contact Name
Dennis Janda
Contact Information
951.699.8874
Roles and Responsibilities
• Perform topographical.
• Survey for CIP projects.

Company Name
Associated Soils Engineering, Inc.

Project Function
Geotechnical Engineering
Company Address
2860 Walnut Avenue
Signal Hill, CA 90755
Contact Name
Edward C. (Ted) Riddell
Contact Information
562.426.7990
Roles and Responsibilities
• Perform geotechnical and pavement
investigation and recommendations.

Company Name
Infrastructure Architects, Inc.

Project Function
Architectural Services
Company Address
222 S. Harbor Boulevard, Suite 705
Anaheim, CA 92805
Contact Name
Raymond Abassi
Contact Information
714.982.5045
Roles and Responsibilities
• Perform architectural.
• Design support and services.
409
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 86 Dennis Janda, Inc. (DJI) is a private corporation providing land surveying and mapping services and is a Certified Small Business Enterprise in the state of California.

The owners and managers of DJI have worked together for both public and private sectors clients throughout Southern California since 1997.

DJI’s core staff has their roots in the traditional disciplines of land planning, civil engineering, land surveying and mapping mainly working on development and public works projects throughout California. This experience using and participating in the evolution of surveying and mapping practices has helped in our ability to contribute in time and cost saving practices and processes from project conception through the development, to recording. Upon this foundation we added a diverse team of professionals using the best use of equipment and technology to contribute to our client’s specific project goals and schedules. DJI’s staff has been working with municipalities and utility districts providing these services for 25 years.

Experience
On - Call Surveying Services | City of Jurupa Valley, CA Contract City Surveyor. Provided on call Survey Map review and Field Survey Services for the city from February 2013 to present. DJI has also participated in the development of the survey plan check standards and forms. Services included all aspects of survey and mapping including processing review of over 160 Dedications, easements, Lot Line Adjustments, Vacations and Certificates of Compliance, together with the review and process of Tentative Maps, Tract maps and Parcel Maps. DJI also provided field surveys, Including Right of Way and Easement Surveys, Utility Surveys, cross sections surveys, topographic and photogrammetry surveys. Prepare Roadway Dedications, Vacation Packages including signature sheets legal and plats.

On - Call Surveying Services | City of Menifee, CA
Contract City Surveyor. Provided on call Survey Map review and Field Survey Services for the city from February 2010 to present. During that time, DJI has participated in development of the survey plan check standards and forms. Services included all aspects of survey and mapping including processing review of over 500 Dedications, easements, Lot Line Adjustments, Vacations and Certificates of Compliance, together with the review and processing Tentative Maps, Tract Maps and Parcel Maps. DJI also provided field surveys, Including Right of Way and Easement Surveys, Utility Surveys, cross sections surveys, topographic and photogrammetry surveys. Prepare Roadway Dedications, Vacation Packages including signature sheets legal and plats.

On - Call Surveying Services | City of Pomona, CA
Subconsultant to Prime. Provided Survey Services for the city from February 2016 to present. Services included all aspects of survey mapping including processing review of Dedications, easements, Lot Line Adjustments, Vacations and Certificates of Compliance, together with the review and process of Tract maps and Parcel Maps. DJI also researched and locate right of ways and utility easements for the city.

Dennis Janda, PLS
Professional Land Surveyor
Education
Palomar College Surveying
Registrations
Professional Land Surveyor (PLS) :

California (#6359)
Certified Federal Surveyor (CFS):
(#1379)
Certifications
Certificate in GPS Survey
Certificate in AutoCAD
Certificate in ESRI Software
G.I.S. Certificate Program, University of
California, Riverside
G.P .S. Certificate Program, University of
California, Riverside
Associations
California Land Surveyors Association
(CLSA) member
American Congress on Surveying and
Mapping (ACSM) member
410
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 87 Ted Riddell has been the President and Principal Engineering Geologist of ASE since the year 2000. He has over 35 years experience in all phases of geotechnical projects.

Ted manages ASE projects for the public and private sectors including planning, budgeting, geologic mapping, coordinating, conducting and writing preliminary investigations in seismic hazard zones, landslide areas and Alquist Priolo Earthquake Fault Zones. His project management skills include supervision, direction of field personnel and site inspections during grading to final drafting and report writing of projects. As the President of the firm, Ted is responsible for making quick decisions that enable smooth accomplishments of day to day tasks in the field, laboratory and office.

Experience
Beverly Manor Drive | City of Seal Beach, CA
Project Manager / Engineering Geologist for Pavement Rehabilitation / Reconstruction of Beverly Manor Drive, existing pavement evaluation and recommendations for Full Depth Reclamation (FDR), coordinate AC coring and soil borings, analyze laboratory data, preparation of report including evaluation of sub - grade soils, pavement overlays and new pavement sections, followed by management of the operations of the geotechnical personnel (field and Lab) during the reclamation and new pavement overlay for the project.

City Streets | City of Garden Grove, CA
Project Manager / Engineering Geologist for Pavement Rehabilitation / Reconstruction of eight city Streets varying from local residential streets to collectors and arterials, existing pavement evaluation and recommendations for rehabilitation or replacement, visual evaluation of pavements, coordinate AC coring and soil borings, analyze laboratory data, preparation of report including evaluation of sub - grade soils, pavement overlays and new pavement sections.

Commercial / Light Industrial Streets | City of Santa Fe Springs, CA Project Manager / Engineering Geologist for Pavement Rehabilitation / Reconstruction of 10 Commercial / Light Industrial Streets, existing pavement evaluation and recommendations for rehabilitation or replacement, visual evaluation of pavements, coordinate AC coring and soil borings, analyze laboratory data, preparation of report including evaluation of sub - grade soils, options for pavement overlays and / or new pavement sections.

Edward C. (Ted) Riddell, PG, CEG
Engineering Geologist
Education
B.A. University of California, Santa
Barbara
Registrations
Professional Geologist:

California (#5657)
Certifications
Certified Engineering Geologist:

California (#1775)
411
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 88 Lawrence J.D. Chang joined ASE in 2005 and has been the Vice President and Principal Engineer of ASE since the year 2012. He has over 35 years of experience in all phases of geotechnical projects. Lawrence manages ASE projects for the public and private sectors including planning, budgeting, geotechnical investigation, laboratory testing, engineering analysis and design, writing of geotechnical investigation reports for all categories of geotechnical projects, and third party peer review. His project management skills include coordination with project team, supervision and direction of field personnel, site inspection and meeting, and analysis and recommendations of mitigative measures for projects. As the Vice President of the firm, Lawrence is responsible for overseeing daily operations that enable timely and adequate coverage and completion of all tasks in the field, laboratory and office.

Experience
Pavement Rehabilitation / Reconstruction Projects | City of Cerritos, CA Project Manager / Geotechnical Engineer for multiple Pavement Rehabilitation / Reconstruction Projects throughout the city since 2016 that include existing pavement evaluation and recommendations for pavement rehabilitation and re - construction, evaluate AC coring and soil borings, analyze laboratory data, preparation of report including evaluation of sub - grade soils, pavement overlays and new pavement sections, followed by management of the operations of the geotechnical personnel (field and lab and batch plant) during the pavement rehabilitation projects.

Pavement Rehabilitation / Reconstruction Projects / Slurry Seal | City of Garden Grove, CA
Project Manager / Geotechnical Engineer for Pavement Rehabilitation / Reconstruction / Slurry Seal of multiple city streets since 2012 varying from local residential streets to collectors and arterials, existing pavement evaluation and recommendations for rehabilitation, replacement or Full Depth Reclamation (FDR), evaluate AC coring and soil borings, analyze laboratory data, preparation of report including evaluation of sub - grade soils, FDR mix design study, pavement overlays and new pavement sections, followed by management of the operations of the geotechnical personnel (field and lab and batch plant) during the pavement rehabilitation / reconstruction / repair projects.

Pavement Rehabilitation / Reconstruction Projects | City of Lakewood, CA Project Manager / Geotechnical Engineer for Pavement Rehabilitation / Reconstruction of multiple local residential streets, collectors and arterials since 2005, existing pavement evaluation and recommendations for rehabilitation or replacement, visual evaluation of pavements, coordinate AC coring and soil borings, analyze laboratory data, preparation of report including evaluation of sub - grade soils, options for pavement overlays and / or new pavement sections, followed by management of the operations of the geotechnical personnel (field and lab) during the pavement rehabilitation / reconstruction projects.

Lawrence J.D. Chang, PE, GE
Engineering Geologist
Education
PhD Candidate Geotechnical
Engineering, Nanyang Technical
University, Singapore
M.S. Geotechnical Engineering,
University of California, Davis
B.A. Civil Engineering, Chung Yuan
Christian University, Chung - Li, Taiwan
Registrations
Professional Civil Engineer:

California (#67987)
Professional Geotechnical Engineer:

California (#2881)
412
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 89 Pavement Rehabilitation / Reconstruction Projects | City of Hawthorne, CA Project Manager / Geotechnical Engineer for Pavement Rehabilitation / Reconstruction of multiple local residential streets, collectors and arterials since 2010, existing pavement evaluation and recommendations for rehabilitation or replacement, visual evaluation of pavements, coordinate AC coring and soil borings, analyze laboratory data, preparation of report including evaluation of sub - grade soils, options for pavement overlays and / or new pavement sections, followed by management of the operations of the geotechnical personnel (field and lab) during the pavement rehabilitation / reconstruction projects.

Palm Drive Pavement Reconstruction | City of Signal Hill, CA Project Manager / Geotechnical Engineer for Pavement Reconstruction of Palm Drive in 2023, including visual evaluation of pavements, site meetings, mitigative measures assessment and formulation, laboratory testing data analysis, preparation of recommendations, followed by management of the operations of the geotechnical personnel (field and lab) during the pavement reconstruction / repair of the project.

Pavement Rehabilitation / Reconstruction Projects | City of Bellflower, CA Project Manager / Geotechnical Engineer for Pavement Rehabilitation / Reconstruction of multiple local residential streets, collectors and arterials since 2020, existing pavement evaluation and recommendations for rehabilitation or replacement, visual evaluation of pavements, coordinate AC coring and soil borings, analyze laboratory data, preparation of report including evaluation of sub - grade soils, options for pavement overlays and / or new pavement sections, followed by management of the operations of the geotechnical personnel (field and lab) during the pavement rehabilitation / reconstruction projects.

Lawrence J.D. Chang, PE, GE (cont.)
Engineering Geologist
413
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 90 Alex has over 30 years of architectural experience acting on behalf of owners and organizations managing new and remodel projects from project conception to agency review, construction documentation preparation and construction completion. This expertise was developed while working on project types such as residential, commercial, hospitality, liturgical design, retail, health care facilities, institutional projects (K - 12 and higher education). Site planning, and fuel station design. Alex is also bilingual so he can help during community meetings to help with presentation and questions and answers about the project.

Experience
Infrastructure Architects | Anaheim, CA
Project Manager. Manages project schedules and staff. Oversees project budgets and project schedules. Leads teams on conceptual designs, design development and interior design. He has recently been involved with multiple restroom renovation including the Cities of Glendale, Hawaiian Gardens, Adelanto, Bell Gardens, La Puente, Montebello, and other cities.

Greenberg Farrow Architects | Irvine, CA
Associate / Project Manager. Worked on various commercial projects such Panda Express, Honey Birdette, Home Depot, and a broad range of tenant improvements.

Developed construction documents for permitting.

Daniel D. White Architects | Covina, CA
Project Manager for the institutional branch (church design) from Armando Ruiz and Associates. Developed construction documents for permitting.

API Consultants | La Jolla, CA
Project Manager. Institutional (USC campus). Developed construction documents for permitting.

KSP Studio | Lake Forest, CA
Project Manager. Retail projects (Home Depot). Developed construction documents for permitting.

Lundstrom & Associates | Irvine, CA
Project Coordinator / Institutional (USC campus). Developed construction documents for permitting.

Steven Langford Architects, Inc. | Irvine, CA
Project Manager / Project Coordinator for hospitality projects. Developed construction documents for permitting.

Ruhnau Clarke Architects | Riverside, CA
Project Coordinator / Institutional (USD campus). Developed construction documents for permitting.

Alex Serafin
Architectural Director
Education
B.A. Art, California State University,
Fullerton
Certifications
Revit 2021 Certificate
414
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 91 As Senior Project Architect and QA / QC, Mark is responsible for project design, design development, construction document preparation and coordination, and construction administration. Mark is the code expert for all aspects of iARCH projects regardless of occupancy, and has developed internal courses, checklists, and drawing templates for code analysis. As a certified instructor through the California Architects Board, Mark has also written and taught courses for Accessibility Continuing Education Requirements for license renewal for California State Architecture licensure.

Experience
Infrastructure Architects | Anaheim, CA
As the Quality Assurance / Quality Control Manager at iArch, Mark brings over forty years of experience and knowledge to the company. Mark conducts weekly project meetings with IE team members and managers and leads projects for our client cities.

Mark has worked on various types of projects and shares his extensive knowledge with our team.

LPA, Inc. | Irvine, CA
Project Manager. Projects: Murrieta Healthcare Resort. Skilled Nursing Facility, 63,500 sq. ft., two story building ($26M project), Various healthcare projects - construction administration.

Ware Malcomb | El Monte, CA
Project Manager. Projects: Longo Lexus / Toyota Campus remodel - Six buildings, 50,000 sq. ft., ground - up and tenant improvement construction including the new service pavilion building, site upgrades, landscaping, and multiple existing building renovations ($20M project), Huntington Beach medical office building - shell only, Hyland’s Pharmaceutical manufacturing plant - building retrofit, Porsche Experience driving school facility - construction administration.

Northwest Tower and Central Plant, St. Jude Medical Center | Fullerton, CA Project Manager. St. Joseph Health System Fullerton, California. 250,000 sq. ft., four story tower. $300M construction cost. The tower holds 120 - beds, private and semi - private, across four nursing units; 14 operating rooms, including robotic surgical suites; a pre - op / post - op anesthesia care unit; dining; pharmacy, including robotics; sterile processing; physician and staff lounges; and patient and staff healing gardens.

Central Utility Plant. 14,000 sq. ft.

Anderson Medical Pavilion | La Jolla, CA
Project Manager. Scripps Health La Jolla, California, 175,000 sq. ft., seven story tower. $250M construction cost. New construction, outpatient, design - build. The clinic features office and administration space, diagnostic facilities and roughly 15 medical procedure departments.

Mark Dwyer, NCARB
Quality Assurance / Quality Control Manager
Education
B.S. Architecture, California State
Polytechnic University, Pomona
Registrations
California Architects License C 23283
National Council of Architectural
Registration Boards
415
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 92 Mehran Golestan
Senior Designer
Education
B.A. Architecture, Shahid Beheshti
University, Tehran, Iran
Registrations
California Architects License C 23283
National Council of Architectural
Registration Boards
Mehran Golestan is a highly experienced professional with over 35 years of expertise in the field of architecture and interior design. He has an exceptional track record in designing and delivering a wide range of residential, hotels, commercial, and other construction projects.

Throughout his career, he has worked on numerous high - profile projects, including luxury hotels, high - end residential developments, and commercial buildings. He is recognized for his creative approach to design, his attention to detail, and his ability to incorporate the latest technologies into his projects. Mehran is adept at balancing the aesthetic and functional requirements of a project and can manage complex projects with ease. He is committed to delivering projects that exceed his client’s expectations and is highly respected in the industry for his professionalism and dedication. He has extensive experience in overseeing the design and construction of buildings, ensuring that they meet all safety, environmental, and regulatory requirements. From 2011 to 2017 Mehran held the positions of the board of director and lecturer at TAFE, Box Hill Institute, Australia based in Tehran.

Experience
Magnolia Crossing Residential Development | 100,000 sq. ft. | Riverside, CA Senior Center | 20,000 sq. ft. | City of Adelanto, CA
Park Design | 3 acres | City of Adelanto, CA
Fire Station Restroom Remodel | City of Adelanto, CA
Restroom Remodel | City of Hawaiian Gardens, CA
Taghe Kasra Residential Complex | 450,000 sq. ft.

Taghe Kasra Residential Complex | 450,000 sq. ft.

Shahr Kord Parisian Hotel | 50,000 sq. ft.

Baku VIP Hotel | 50,000 sq. ft.

Siemens Factory | 200,000 sq. ft.

Safaiye Hotel | 80,000 sq. ft.

Laavan Sport Center | 38,000 sq. ft.

Bahregan Sport and Culture Center | 40,000 sq. ft.

Namak Abrood Residential Complex | 360,000 sq. ft.

Psychophysics Laboratory | 50,000 sq. ft.

ABFA Main Administration Building | 140,000 sq. ft.

Siry Airport Terminal Passenger | 34,000 sq. ft.

Noory University | 220,000 sq. ft.

Ice Tower Mall and Hotel | 220,000 sq. ft.

AOC Trail, Commercial and Hotel | 2,000,000 sq. ft.

Almaty Sports Center | 100,000 sq. ft.
416
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 93 Rosa Anaya
Senior Job Captain
Education
B.A. Architecture, Monterrey Institute
of Technology, Capus Queretaro,
Mexico
Certifications
Interior Design Certificate, University
of California Los Angeles (UCLA)
Rosa is responsible for various tasks in the development of construction documents.

Rosa has over seventeen (17) years of experience and obtained her BA in Architecture.

Rosa is involved in dealing with client’s needs, coordination of the project and consultants. She initiates project research for the development of construction documents.

Experience
Infrastructure Architects | Anaheim, CA
Senior Job Captain. Rosa prepared presentation and construction documents conforming to codes and zoning regulations for new and tenant improvements for commercial, retail, and fast - food projects such as Raising Cane’s, Super Star Car Wash, etc. Coordinated construction drawings with Structural, Electrical, Mechanical, Plumbing and Civil disciplines. Prepared and coordinated city submittal packages for building permits and plan check corrections. Distributed hard copies and electronic drawings to clients and consultants. Conducted site visits and prepared as - built drawings. Assisted Project Architect / Project Manager. Maintained specific and scheduled deadlines for client submittals. Construction administration for Chase Bank projects: RFIs and shop drawings submittals.

Greenberg Farrow | Irvine, CA
Project Captain. Rosa prepared presentation and construction documents conforming to codes and zoning regulations for several commercial, retail, office space, restaurant, and fast - food projects such as Marshalls, 7 - Eleven, Walgreens, Savers, Unisource, Garbanzo Mediterranean Grill, Five Guys, Starbucks, etc. Coordinated construction drawings with Structural, Electrical, Mechanical, Plumbing and Civil disciplines.

Prepared and coordinated city submittal packages for building permits and plan check corrections. Checked and coordinated shop drawings. Distributed hard copies and electronic drawings to clients and consultants. Conducted site visits and prepared as - built drawings. Assisted Project Architect / Project Manager. Maintained specific and scheduled deadlines for client submittals. Space planning and design of fast casual restaurants.
417
06 Readiness to Provide Services
418
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 94 Readiness to Provide Services
IE’s project manager, key task leaders and staff designated to perform City of Lynwood’s On - Call Professional Engineering Services have been involved in various capacities on a number of various engineering, planning building and safety, plan check, and construction management projects. We are very familiar with the urgency and priority of any upcoming agency - funded and other capital improvement projects to be completed in the city. Our staff and other resources can be very quickly assigned to any service needs as soon as a request for service is issued by the city. We have a proven record of completing expeditiously any time - sensitive project assignment, e.g., submittal of PS&E and right - of - way certification packages to Caltrans local assistance department for authorization for construction. Our team is comprised of staff and subconsultants competent in completing every aspect of a typical agency - funded project and they are available immediately to take assignments from the city.
419
07 Agreement to City Contract Terms and Ability to
Obtain Insurance
420
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 95 Agreement to City Contract Terms and Ability to Obtain Insurance
IE has the ability to execute the city’s Professional Services Agreement (Appendix A) for the Project.

IE has the ability to secure insurance that meets the city’s requirements. An example of our insurance is attached below. 07/06/2023
Klein Agency, LLC
P.O. Box 219
Timonium MD 21094
(410)832-7600 (410)832-1849
[email protected]
Infrastructure Engineers, a Bowman Company
3060 Saturn Street
Suite 250
Brea CA 92821
Charter Oak Fire Insurance Co 25615
Travelers Property Casualty Co. of America 25674
Berkley Insurance Company
22-23 Infrastructure Engi
A Contractual Liability 6306J047645 08/31/2022 08/31/2023 1,000,000
1,000,000
10,000
1,000,000
2,000,000
2,000,000
B 8108T020400 08/31/2022 08/31/2023
1,000,000
B CUP6J395074 08/31/2022 08/31/2023
25,000,000
25,000,000
B N UB6J317115 08/31/2022 08/31/2023
1,000,000
1,000,000
1,000,000
C
Primary Professional & Pollution Liab /
Excess Professional & Pollution Liability AEC905795802/V3349C220101 08/31/2022 08/31/2023 Each Claim/Aggregate 5,000,000
Excess Each Claim/Aggr. 5,000,000
Total Limits: 10,000,000
If required by an insured written contract, executed prior to any loss, the certificate holder is an Additional Insured on a primary and non-contributory basis under the General and Auto Liability Policies. If required by an insured written contract, executed prior to any loss, Waiver of Subrogation is provided for General, Auto, and Workers Compensation Policies. Umbrella Policy follows form over General, Auto, and Employer's Liability Policies. 30 day notice of cancellation, 10 day for non-payment.
* Evidence of Coverage *

SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE

THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS.

INSURER(S) AFFORDING COVERAGE
INSURER F :

INSURER E :

INSURER D :

INSURER C :

INSURER B :

INSURER A :

NAIC #
NAME:

CONTACT
(A/C, No):

FAX
E-MAIL
ADDRESS:

PRODUCER
(A/C, No, Ext):

PHONE

INSURED
REVISION NUMBER:CERTIFICATE NUMBER:COVERAGES
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must have ADDITIONAL INSURED provisions or be endorsed.

If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).

THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS

CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.

OTHER:
(Per accident)
(Ea accident)
$
$
N / A
SUBR
WVD
ADDL
INSD

THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS

CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. $
$
$
$PROPERTY DAMAGE
BODILY INJURY (Per accident)
BODILY INJURY (Per person)

COMBINED SINGLE LIMIT

AUTOS ONLY

AUTOSAUTOS ONLY

NON-OWNED

SCHEDULEDOWNED

ANY AUTO

AUTOMOBILE LIABILITY
Y / N

WORKERS COMPENSATION

AND EMPLOYERS' LIABILITY
OFFICER/MEMBER EXCLUDED?
(Mandatory in NH)
DESCRIPTION OF OPERATIONS below
If yes, describe under

ANY PROPRIETOR/PARTNER/EXECUTIVE
$
$
$
E.L. DISEASE - POLICY LIMIT
E.L. DISEASE - EA EMPLOYEE
E.L. EACH ACCIDENT
ER
OTH-

STATUTE
PER

LIMITS(MM/DD/YYYY)

POLICY EXP
(MM/DD/YYYY)

POLICY EFF

POLICY NUMBERTYPE OF INSURANCELTR
INSR
DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (ACORD 101, Additional Remarks Schedule, may be attached if more space is required)

EXCESS LIAB
UMBRELLA LIAB $EACH OCCURRENCE
$AGGREGATE
$
OCCUR

CLAIMS-MADE
DED RETENTION $
$PRODUCTS - COMP/OP AGG
$GENERAL AGGREGATE
$PERSONAL & ADV INJURY
$MED EXP (Any one person)
$EACH OCCURRENCE

DAMAGE TO RENTED
$PREMISES (Ea occurrence)

COMMERCIAL GENERAL LIABILITY

CLAIMS-MADE OCCUR
GEN'L AGGREGATE LIMIT APPLIES PER:

POLICY PRO-

JECT LOC

CERTIFICATE OF LIABILITY INSURANCE

DATE (MM/DD/YYYY)

CANCELLATION

AUTHORIZED REPRESENTATIVE
ACORD 25 (2016/03)
© 1988-2015 ACORD CORPORATION. All rights reserved.

CERTIFICATE HOLDER
The ACORD name and logo are registered marks of ACORD
HIRED

AUTOS ONLY
421
08 Legal Issues
422
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 96 Legal Issues
Neither IE nor any of its proposed subconsultants have past or pending litigation or claims filed against our firms, our principals or any of our key consultants, related to services performed for public agencies, or in actions that may affect performance under a contract with the city.

We have no litigation history (including open or pending matters) for the last five years. 423
09 Disclosures
424
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 97 Disclosures
Neither IE nor any of its proposed subconsultants nor any principals of the firms have been, or currently are, the subject of any investigation by the county, state and / or federal agencies within the past five years. 425
10 Additional Statements
426
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 98 Additional Statements
IE shall adhere to all federal laws, state, and local laws and regulations.

IE shall allow authorized federal, state, county, and the city’s official’s access to place of work, books, documents, papers, fiscal, payroll materials, and other relevant contract records pertinent to the project. All relevant records shall be retained for at least three years.

IE will not discriminate against any employee or applicant for employment because of race, color, religion, sex or national origin.

IE shall comply with the California Labor Code. Pursuant to said regulations entitled: Federal Labor Standards provisions; Federal Prevailing Wage Decision; and State of California Prevailing Wage Rates, respectively. 427
11 Fee Proposal
428
Infrastructure Engineers, a Bowman company | Professional Civil Engineering On-Call Services | November 13, 2023 99 Fee Proposal
CCoommmmuunniittyy DDeevveellooppmmeenntt——
EEnnvviirroonnmmeennttaall && PPllaannnniinngg
DDiirreeccttoorr $$119955
DDeevveellooppmmeenntt SSeerrvviicceess MMaannaaggeerr $$118899 PPrroojjeecctt MMaannaaggeerr $$117733
PPllaannnniinngg MMaannaaggeerr $$116677
PPrriinncciippaall PPllaannnneerr $$116633
SSeenniioorr PPllaannnneerr $$115533
AAssssoocciiaattee PPllaannnneerr $$113399
AAssssiissttaanntt PPllaannnneerr $$112299
PPllaannnniinngg TTeecchhnniicciiaann $$9988
CCEEQQAA//NNEEPPAA SSppeecciiaalliisstt $$117755
EEnnvviirroonnmmeennttaall SSppeecciiaalliisstt $$117700 SSeenniioorr EEnnvviirroonnmmeennttaall PPllaannnneerr $$116655 EEnnvviirroonnmmeennttaall PPllaannnneerr IIII $$115555 EEnnvviirroonnmmeennttaall PPllaannnneerr II $$114444 EEnnvviirroonnmmeennttaall TTeecchhnniicciiaann $$ 110000 MMuunniicciippaall EEnnggiinneeeerriinngg SSuuppppoorrtt IInntteerriimm CCiittyy MMaannaaggeerr $$222200
AAssssiissttaanntt//DDeeppuuttyy CCiittyy MMaannaaggeerr $$119977 CCiittyy EEnnggiinneeeerr $$117788
CCiittyy TTrraafffificc EEnnggiinneeeerr $$116699
DDeeppuuttyy CCiittyy EEnnggiinneeeerr $$116699
DDeeppuuttyy CCiittyy TTrraafffificc EEnnggiinneeeerr $$116611 PPllaann CChheecckk EEnnggiinneeeerr $$117788
PPllaann EExxaammiinneerr $$115555
CCIIPP MMaannaaggeerr $$117788
AAssssoocciiaattee EEnnggiinneeeerr $$114499
EEnnggiinneeeerriinngg AAssssoocciiaattee $$114422
EEnnggiinneeeerriinngg AAssssiissttaanntt $$111188
EEnnggiinneeeerriinngg TTeecchhnniicciiaann $$110066
BBuuiillddiinngg && SSaaffeettyy
BBuuiillddiinngg OOfffificciiaall $$117755
PPllaann CChheecckk EEnnggiinneeeerr $$116655
LLaannddssccaappee PPllaann CChheecckkeerr $$116622
SSeenniioorr CCeerrttiififieedd AAcccceessss SSppeecciiaalliisstt $$116655 CCeerrttiififieedd AAcccceessss SSppeecciiaalliisstt $$115555 PPllaannss EExxaammiinneerr $$114455
CCooddee EEnnffoorrcceemmeenntt MMaannaaggeerr $$114455 CCooddee EEnnffoorrcceemmeenntt OOfffificceerr $$112277 SSeenniioorr BBuuiillddiinngg IInnssppeeccttoorr $$112277 BBuuiillddiinngg IInnssppeeccttoorr $$112200
GGrraaddiinngg IInnssppeeccttoorr $$112200
CCoouunntteerr TTeecchhnniicciiaann $$110055
2022-2023 HOURLY RATE SCHEDULE
(effective March 1, 2022)
Additional billing classifications may be added to the above list throughout the year as new positions are created. The above schedule is for straight time. Overtime will be charged at 1.5 times. Sundays and Holidays are charged at 2.0 times the standard time. Deposition and court appearances will be charged at 1.5 times the listed billing rates.

Hourly rates and the retainer fees are subject to increases at the annual Consumer Price Index for All Urban Consumers (CPI-U), Los Angeles County area increase rates or a 5% increase, whichever is greater, effective July 1, 2024, and all subsequent years. We will inform the city of the rate increase by April of each succeeding year. 3060 Saturn Street, Suite 250 ⚫ Brea, CA 92821 ⚫ Tel: (714) 940-0100 ⚫ Fax: (714) 940-0700 ⚫ www.infrastructure-engineers.com PPrriinncciippaall iinn CChhaarrggee $$223388
CCiivviill EEnnggiinneeeerriinngg//TTrraafffificc EEnnggiinneeeerriinngg PPrroojjeecctt MMaannaaggeerr $$118855
PPrriinncciippaall EEnnggiinneeeerr $$118800
SSeenniioorr EEnnggiinneeeerr $$117700
SSeenniioorr PPllaann CChheecckk EEnnggiinneeeerr $$117755 PPllaann CChheecckk EEnnggiinneeeerr $$116655
AAssssoocciiaattee EEnnggiinneeeerr $$115555
AAssssiissttaanntt EEnnggiinneeeerr $$114455
EEnnggiinneeeerriinngg AAssssoocciiaattee $$113355
EEnnggiinneeeerriinngg AAssssiissttaanntt $$111155
GGIISS AAnnaallyysstt $$115500
CCAADD MMaannaaggeerr $$113355
CCAADD DDeessiiggnneerr $$111100
CCAADD TTeecchhnniicciiaann $$110000
EEnnggiinneeeerriinngg TTeecchhnniicciiaann $$110055
PPrriinncciippaall TTrraafffificc EEnnggiinneeeerr $$118855 SSeenniioorr TTrraafffificc EEnnggiinneeeerr $$117700 TTrraafffificc EEnnggiinneeeerr $$115500
WWaatteerr//WWaasstteewwaatteerr//NNPPDDEESS
SSeenniioorr WWaatteerr EEnnggiinneeeerr $$116677
WWaatteerr EEnnggiinneeeerr $$115588
PPrrooggrraamm MMaannaaggeerr ((NNPPDDEESS)) $$116688 IInnssppeeccttoorr ((NNPPDDEESS)) $$111100
EEnnvviirroonnmmeennttaall SScciieennttiisstt $$110055 SSuurrvveeyyiinngg
PPrroojjeecctt MMaannaaggeerr $$118855
PPllaann CChheecckkeerr $$116622
((SSuubbddiivviissiioonn && SSuurrvveeyy DDooccuummeenntt)) SSuurrvveeyy AAnnaallyysstt $$115500
SSuurrvveeyy CCrreeww ((22--mmaann)) $$223366
SSuurrvveeyy CCrreeww $$227788
((22--mmaann,, pprreevvaaiilliinngg wwaaggeess))
CCoonnssttrruuccttiioonn MMaannaaggeemmeenntt
CCoonnssttrruuccttiioonn MMaannaaggeerr $$118888
RReessiiddeenntt EEnnggiinneeeerr $$118888
SScchheedduulleerr//CCoonnttrroolllleerr $$116633
UUttiilliittiieess CCoooorrddiinnaattoorr $$113388
SSeenniioorr PPWW OObbsseerrvveerr//IInnssppeeccttoorr $$113300 SSeenniioorr PPWW OObbsseerrvveerr//IInnssppeeccttoorr $$119911 ((pprreevvaaiilliinngg wwaaggeess))
PPWW OObbsseerrvveerr//IInnssppeeccttoorr $$111133
PPWW OObbsseerrvveerr//IInnssppeeccttoorr $$115599
((pprreevvaaiilliinngg wwaaggeess))
FFiirree PPrreevveennttiioonn
FFiirree MMaarrsshhaall $$116655
FFiirree IInnvveessttiiggaattoorr $$115544
FFiirree PPllaannss EExxaammiinneerr $$114433
SSeenniioorr FFiirree IInnssppeeccttoorr $$113388
FFiirree IInnssppeeccttoorr $$112200
CCoouunntteerr TTeecchhnniicciiaann $$9933
AArrcchhiitteeccttuurraall SSeerrvviicceess
DDiirreeccttoorr $$220000
SSttuuddiioo MMaannaaggeerr $$118844
SSeenniioorr PPrroojjeecctt MMaannaaggeerr// $$117766 SSeenniioorr AArrcchhiitteecctt
PPrroojjeecctt MMaannaaggeerr//PPrroojjeecctt AArrcchhiitteecctt $$115555 SSeenniioorr JJoobb CCaappttaaiinn $$112266
JJoobb CCaappttaaiinn $$110055
DDrraafftteerr $$9900
PPrrooggrraamm MMaannaaggeemmeenntt//PPuubblliicc OOuuttrreeaacchh PPrrooggrraamm DDiirreeccttoorr $$118844
WWeebb DDeessiiggnneerr $$115500
MMeeddiiaa SSppeecciiaalliisstt $$114455
PPrrooggrraamm CCoooorrddiinnaattoorr $$113355
PPhhoottooggrraapphheerr $$112288
OOuuttrreeaacchh SSppeecciiaalliisstt $$112255
IInntteerrpprreetteerr//TTrraannssllaattoorr $$112255
PPrroodduuccttiioonn AAssssiissttaanntt $$8855
FFuunndd AAddmmiinniissttrraattoorr $$113388
LLaabboorr CCoommpplliiaannccee CCoooorrddiinnaattoorr $$110055 AAddmmiinniissttrraattiivvee && CClleerriiccaall SSeerrvviicceess OOrrggaanniizzeerr//SSuuppeerrvviissoorr $$110088
AAddmmiinniissttrraattiivvee AAssssiissttaanntt $$9900 CClleerrkk TTyyppiisstt $$8800
OOtthheerr CChhaarrggeess
DDeelliivveerryy $$111100
MMiilleeaaggee ((CCuurrrreenntt ffeeddeerraall gguuiiddeelliinnee rraattee @@ ttiimmee ooff bbiilllliinngg))//MMiillee TTrraavveell CCoosstt ++ 1155%%
RReeiimmbbuurrsseemmeennttss CCoosstt ++ 1155%%
City of Lynwood
429
submitted by
EXP U.S. Services Inc.
330 N Brand Blvd, #950 | Glendale, CA 91203
t: +1.818.903.2954
On-Call
Engineering
Services
City of Lynwood
Date: November 13, 2023 at 10am

STATEMENT OF QUALIFICATIONS
430

TABLE OF

CONTENTS
1 COVER LETTER 1
2 FIRM ORGANIZATION, CREDENTIALS AND BACKGROUND 3
3 APPROACH TO THE PROJECT 6
4 PROJECT EXPERIENCE 10
5 QUALIFICATIONS OF PROPOSED PERSONNEL 24
6 READINESS TO PROVIDE SERVICES 66
7 AGREEMENT TO CITY CONTRACT TERMS AND ABILITY TO
OBTAIN INSURANCE 67
8 LEGAL ISSUES 68
9 DISCLOSURES 69
10 ADDITIONAL STATEMENTS 70
11 FEE PROPOSAL 71
431
01 Cover letter
432
EXP U.S. Services Inc.
330 N Brand Blvd, #950
Glendale, CA 91203 | USA
t: +1.818.903.2954 | exp • com
November 13, 2023
City of Lynwood
Public Works Department
Mr. Julian Lee, Director of Public Works
11330 Bullis Road
Lynwood, CA 90262
RE: ON-CALL GENERAL ENGINEERING, UTILITY ENGINEERING, TRAFFIC ENGINEERING, & AR CHITECTURAL SERVICES
Dear Mr. Lee,
We, at EXP U.S. Services Inc. (EXP), are pleased to submit our Statement of Qualifications to the City of Lynwood to provide General Engineering and Traffic Engineering Services and related support services to the City supporting cost effective and expeditious delivery of the City’s projects.

We have assembled a strong and highly experienced team of professionals with local, regional, and State agency experience led by our seasoned Team Leader Abdollah Ansari to help achieve the City’s goals.

The EXP Key Staff leading various functions in this contract are:

The EXP Team managers are former Metro, Caltrans, and local city division managers with solid track records of having delivered numerous small to multi-million-dollar projects on local streets and State highways. We understand the City’s concerns, urgencies, and priorities, and will work with the City, other agencies, and our subconsultants to deliver the projects assigned to us timely and cost-effectively. We are currently providing as-needed engineering and project/program management services to the City of Los Angeles Bureau of Engineering, the City of Seal Beach, and the California Department of Transportation (Caltrans).

KEY EXP STAFF RESPONSIBILITY AREA
Abdollah Ansari Principal-In-Charge, Contract Management; City’s Main Point of Contact; Multi-Agency Coordination; Outreach; Risk Assessment Syed Raza, PE Program/Project Management
Gabriel Rodriguez, PE Roadway Engineering
Mohammad Muqtadir, PE Structural Engineering
Luis Betancourt, PE Quality Assurance/Control
Portia Gonzalez, PE, QSD/QSP Drainage Studies and Engineering Ben Hashemloo, PTOE Traffic Studies and Engineering, Signals, ITS Anh Case, PE, CCM Construction Management
#25
TOP 500 DESIGN FIRMS
ENR, 2023
#19

TRANSPORTATION

TOP DESIGN FIRMS IN

TRANSPORTATION
ENR, 2023
#22
MASS TRANSIT + RAIL

TOP DESIGN FIRMS IN

TRANSPORTATION
ENR, 2023
#16

HIGHWAYS

TOP DESIGN FIRMS IN

TRANSPORTATION
ENR, 2023
#16

BRIDGES

TOP DESIGN FIRMS IN

TRANSPORTATION
ENR, 2023
433
EXP
City of Lynwood
Re: Professional Engineering On-Call Services
Date: 11/13/2023 at 10AM
EXP is submitting this Statement of Qualifications for the following service disciplines:

No. Category

1. General Engineering

3. Traffic Engineering Services
Our subconsultants are highly credible in their expertise areas and have been our partners for decades on agency contracts.

In compliance with the City’s requirement, this proposal will be valid for a period of 2.5 years from January 1, 2024, or the actual date of award of contract. We declare that all information submitted in this Statement of Qualifications is true and correct and that the person signing this letter is authorized to represent the firm in all matters related to the solicitation and any contract subsequently awarded.

Our closest office to Lynwood is at 330 North Brand Boulevard, Suite 950, Glendale, CA 91203. Assigned work will be done in the Glendale office as well as the San Bernardino office located at 451 East Vanderbilt Way Suite 375, San Bernardino, California, 92408.

The undersigned will be the point of contact with the City and may be reached at +1.818.903.2954 and/or [email protected] at all times.

We are looking forward to providing unmatched professional services to the City of Lynwood. Please contact the undersigned for any matters related to this RFQ.

Respectfully Submitted,

Abdollah Ansari
Principal-in-Charge | Vice President, Client Services
Area Manager, Los Angeles County
t : +1.818.903.2954 | e : [email protected]
Nassim Elias
Task Order Manager
Caltrans District 8 PM On-Call 2019, and Re-compete Contract 2022 EXP is a Great team and great company. We really enjoy having THE EXP team on our side to assist in all tasks that we ask them to do. They are courteous professional and provide our department (PPM) added value help. We feel that they are an extension of our employees in performing any task related to program project management. Highly recommended for any entity to hire.” “
434
02 Firm organization,
Credentials, & Background
435
FIRM ORGANIZATION, CREDENTIALS, & BACKGROUND | 3
City of Lynwood
On-Call Engineering Services
EXP’S Profile

Firm Name: EXP U.S. Services Inc.

Office Location Performing Work: 330 North Brand Boulevard, Suite 950, Glendale, CA 91203; 451 E Vanderbilt Way, Suite 375 San Bernardino, CA 92408
Legal Entity: Private Corporation
Contact Person: Abdollah Ansari, Principal-in-Charge
t : +1.818.903.2954 | e : [email protected]
With a mission to understand, innovate, partner, and deliver, EXP provides engineering, architecture, design, and consulting services to its valued clients. Our heritage dates to 1906, when the earliest of EXP’s predecessor companies started the engineering infrastructure practice. Today, over 4,000 creative EXP professionals provide the knowledge, passion, and experience needed to deliver successful projects for our clients.

EXP is a private corporation with over 100 offices in North America, including 30+ offices across the United States. Our California offices are in Glendale, San Bernardino, San Diego, and San Francisco.

We have worked with numerous local agencies and municipalities to provide multidisciplinary services for public works projects in urban environments. We bring a full range of services from planning and feasibility studies through design and construction management, as well as overall program management.

With consistent recognition by our clients and industry, we ranked #25 in the Top 500 Design Firms by ENR in 2023.
117
years infrastructure
experience
100+
year history in
highway/roadway
projects
50+
years experience
15+
years construction
management

SUSTAINABILITY AT EXP
Sustainability is embedded in everything we do at EXP. Whether for our clients, in the workplace or in our communities, we are driven to educate, improve and take action towards building a sustainable future.

LEED
Proven Provider
Envision
Qualified Company +
Charter Member
UN
Global Compact
Signatory
02 | FIRM ORGANIZATION, CREDENTIALS, & BACKGROUND
FIRM ORGANIZATION, CREDENTIALS, & BACKGROUND | 3 436
FIRM ORGANIZATION, CREDENTIALS, & BACKGROUND | 4
City of Lynwood
On-Call Engineering Services
EXP Directors and Officers
TABLE 2.1 | Directors and Officers
Directors
Ivan Dvorak
Mark Dvorak
Timothy Neumann
Officers Position
Ivan Dvorak Chairman of the Board & Chief Executive Officer Mark Dvorak President & Chief Operating Officer
Deborah Walters Chief Financial Officer & Treasurer
Hae-Jin (Priscilla) Ahn Secretary
Timothy Neumann Executive Vice President
Anthony Caruso Senior Vice President
Byron Danley Vice President
William McGuire Vice President
R. Shankar Nair Vice President
Khalil Saba Vice President
Rachel Sampson Principal
Kathy Weise Vice President
437
FIRM ORGANIZATION, CREDENTIALS, & BACKGROUND | 5
City of Lynwood
On-Call Engineering Services
Subconsultant Team
TABLE 2.2 | Subconsultants
Firm Role Legal Entity Date Firm
Established
Arellano Associates, LLC Public/Stakeholder Outreach LLC 1994 Counts Unlimited, Inc. Traffic Surveys Corporation 1990 Geo-Advantec, Inc. Geotechnical Engineering/Material Testing Corporation 2012 Guida Surveying, Inc. Surveying and Mapping Corporation 1995 JSE4 Engineering, Inc. Specifications, Cost Estimating, ADA, Quality Management
S-Corporation 2022
MARRS Services Inc. Utilities Coordination Corporation 1989 Rubicon Engineering
Corporation
Environmental Engineering S-Corporation 2004
SHA Analytics, LLC Risk Assessment/Management LLC 2014
Tatsumi and Partners, Inc. Landscape Architecture Corporation 1985 Tovar Geospatial GIS, Aerial/Drone Photography Sole Proprietor 2016 Financial Condition
EXP has around 100 offices throughout North America with some of the largest offices located in the Toronto metro area, Montreal, Chicago, and Orlando. EXP has over 3,500 professionals throughout North America and over 4,000 employees worldwide. The firm is financially stable with $157 million CAD in Shareholder’s Equity as of the nine months ending December 30, 2022. The current debt to EBITDA ratio on trailing twelve month revenue as of December 30, 2022 is under

1.0 at 0.51. The firm’s other financial ratios are strong as well with a current ratio of 1.29 and a debt ratio of 0.72, when considering all liabilities and assets in the calculation. EXP is not in any conditions such as bankruptcy, pending litigation, planned office closures nor impeding mergers that may impede on our ability to complete the project. If you have additional questions, please contact: Deborah Walters, Chief Financial Officer, e: [email protected]. 438
03 Approach to project
439
EXP Team is prepared to deliver the services called for in the Scope of Services section of the RFQ. The following is an outline of the responsibilities expected to be assigned to EXP under this contract and examples of where we have successfully delivered our assignments.

Project Development Services
EXP will provide complete Plans, Specifications, and
Estimates (PS&E) for the assigned projects in compliance with the City and the APA standards as well as Caltrans standards where applicable.

The EXP Team management is comprised of former
Metro, Caltrans, and local city division managers with
solid track records of having delivered a range of small to multi-million-dollar projects on local streets and State highways. We understand the City’s concerns, urgencies, and priorities, and will work with the City, other agencies, and our subconsultants to deliver the projects assigned to us timely and cost-effectively. We strongly believe in early coordination with all parties, identification of constraints, and alternatives to go around those, assessment and
anticipation of risk, clarification of roles and responsibilities, securing commitments of all parties for joint ownership of projects and collective efforts to deliver the projects successfully, having back up plans in the event commitments may be affected by the unexpected (i.e.: utility relocation schedules affected by utility owners’ seasonal emergencies), and other considerations that will contribute to the
successful completion of projects.

As the first step in the project development process for each project, we will,
• Meet with the City staff to understand the need
for the project and the benefits expected by its
implementation. Based on the City’s input/responses,
the scope of the project will be finalized.
• Set the schedule and identify budget, availability and sources of funds, and the timing of the availability of funds for the project and plan all activities to ensure project delivery within the set schedule and available
budget. In the event grants are involved in projects,
we will schedule early coordination with the funding
agency (Caltrans, LA Metro, others) to identify the
agency contact(s) and schedule all necessary activities, communications, and coordination for agreements,
reporting, and invoicing throughout the development
and implementation of projects.
• Identify the agencies/entities with review, approval, and permitting authorities and a point of contact for each
for coordination throughout the life of each project.

A Project Development Team (PDT) comprised of the
staff from the City, EXP team, other agencies, utility
owners, and others will be formed for each project, a
“life of project” meeting schedule will be developed and focused meetings will be added as needed.

At the start of technical work, we will.
• Research all available records for every assigned
project to understand the history of issues and
improvements/changes and build an information library
of all documented issues and improvements within or
affecting the project limits.
• Field check the project site to document the existing conditions and validate consistency between the records and the actual field conditions; photograph the existing conditions for future reference and records; and perform any other necessary work to build a strong information
database reflecting the existing conditions. We will
identify the utilities and other facilities owned by others, identify the owners, and add them to the list of project stakeholders to coordinate with throughout the project
development process.
• Schedule a project kick-off meeting with all project
partners and stakeholders, share the project information, identify levels of engagement, prepare a list of contacts for the project file and share with all parties, discuss and set tentative schedule of all reviews and approvals, document the communication and agreements, prepare the notes
and share with all parties. Any reasonable deviations not jeopardizing the project delivery process and agreed to by all affected parties will be sent to all in writing.
• Conduct all other necessary work to verify and validate the current conditions, secure all third-party as-builts and other relevant documents/information, and other
preparatory work as necessary.
03 | APPROACH TO PROJECT
City of Lynwood
On-Call Engineering Services
APPROACH TO PROJECT | 6
440
During the design process, we will,
• Review the PSR, PR, environmental documents, surveys, and other work done earlier and validate/update the
information/documents.
• Prepare the preliminary PS&E (30%+), prepare all
supporting technical studies, conduct all necessary
coordination and data collection, ensure utmost accuracy in the draft PS&E, and circulate the package for review and comment.
• Collect feedback from internal and external reviewers and advance the design to 60% - 90% depending on the
size and complexity of the project and the extent of the details that must be addressed and circulate again for
review and comment/conceptual approval. For smaller-
scale projects, we will make every effort to deliver this round at 90%+ to cut schedule and cost.
• Implement all final changes after receiving feedback, if any, and finalize the PS&E.

Our design and construction management staff will conduct comprehensive reviews of our design work and work done
by others to ensure the thoroughness and quality of work, accuracy of information, compliance with applicable industry standards and guidelines, constructability and sustainability of the built project, convenience to traffic during construction, avoidance and/or mitigation of impacts, compliance with all City requirements, and inclusion of adequate measures of public/user safety.

Syed Raza, Gabriel Rodriguez, Anh Case, and Luis Betancourt of EXP will lead this work with assistance from our technical staff. Our competent services to our clients and their
testimonies included elsewhere in this proposal attest to the quality of our services.

We will provide engineering support services for projects in construction by assessing the need for additional or modification of the components included in the approved design for all possible safety and functional enhancements. We will ensure continuous evaluation of projects in construction, early detection of issues, quick start of modifications/change orders, and timely approvals to prevent/minimize delays and cost overruns to the extent possible.

We are currently doing this work for the City of Los Angeles for the 7th Street Improvements Project. Our work includes design modifications for the bus stops, coordination with the City and LA Metro in configuration of joint stop locations, addition of landscaping and irrigation lines, elimination of old elevator accesses on sidewalks and sidewalk gap closures, and other enhancement work.

Constructability Reviews/Construction
Management/Construction Support
Services
The EXP Construction Management Team prides itself
in delivering projects from cradle to grave. Our services begin with constructability reviews for projects that will be anticipated to go to bid. Our thorough reviews include our findings, potential solutions, and any impacts to the contract.

We will meet with the engineering team to rectify any matters that may come up, so we ultimately have solid bid documents.

We provided constructability review services to the San Gabriel Valley Council of Governments (SGVCOG) for the
Turnbull Grade Separation Project and to the City of Carson for the Sepulveda Bridge Widening Project. Anh case and her construction management team provided over 300
constructability-related comments for the Turnbull Grade Separation project leading to much more clarity in scope and procedures and a more buildable and biddable project.

EXP staff also provided engineering support services
during construction for the City of Los Angeles’ 7th Street improvements project, including identification and addition of many items missed by other consultants during design.

Our services continue throughout the bid phase where we can summarize and validate the bids for the projects. Once bids are received, EXP will perform a bid analysis with the use of a Bid Summary spreadsheet to assess the most responsive bidder and determine the lowest cost bidder. We will also assist the City in the preparation of the contract award package and agenda items for City Council meetings. We will also support the City in preparing for the Pre-Construction meetings.

Upon commencement of work, we will,
• Closely monitor the progress of assigned projects in
construction, conduct risk assessment studies at critical milestones to confirm the project progress, expenditures to date, and that the remaining work and cost stay as
originally envisioned and fit within the project budget (including the authorized contingency).
• Monitor each project’s critical path and arrange for
accelerations where possible and necessary to stay on
schedule, accelerate all functions that can be accelerated and assign the “freed-up” resources to support other
functions to keep the cost and schedule controlled to the extent possible.
• Assist the City PW staff in drafting the scopes of
additional services/change orders and negotiating the
costs with the contractors.

APPROACH TO PROJECT | 7
City of Lynwood
On-Call Engineering Services
441
• Provide services including but not limited to roadway and structures inspection, answering RFI’s, submittal services, review of shop plans, drafting change orders, claims
support, scheduling, and review of pay estimates.

In addition to transportation projects, we will provide construction bid advertising, bid administration, inspection, and construction management services for water treatment facilities, sewer and water lines, storm drain systems, traffic signals, street improvement, paving, striping, and other projects.

We successfully managed the construction of the Mountain View Bridge Project and the Hesperia Ranchero Widening
Project for the Inland Valley Development Agency’s
(IVDA). For the Mountain View Bridge Project, we provided recommendations for workarounds to the contractor and
avoided the impacts of the adjacent SBCTA Redlands Rail Project on our delivery schedule.

Project Close Out
Our team is committed to closing out most projects within 2 months. This includes as-built drawings, providing all documents for the City’s archiving. All documents will be provided both in a hard-copy format as well as electronic copies in an external hard drive for the City’s usage.

Reports
EXP will,
• Prepare and/or support the preparation of staff reports for City Council, various committees, and advisory bodies. • Prepare and/or oversee the preparation of technical
reports and designs for approval/acceptance by the City Engineer.
• Prepare and/or oversee the preparation of reports and designs for third-party reviews and approvals.
• Prepare other needed reports.

Abdollah Ansari’s experience in transportation management includes positions as Sr. Executive Officer leading the LA Metro’s multi-billion-dollar Countywide Highway Programs; Manager, Traffic & Transportation Bureau of the City of Long Beach; Acting Chief, Caltrans District 7 Advance Planning Division; and Caltrans District 7 Senior Transportation/ Environmental Planner. In those positions, Abdollah prepared, reviewed, and approved a wide range of technical and
administrative reports for major transportation projects and programs. He will apply this experience to the work assigned under this contract and will assist the City in successfully advancing and securing approvals for its projects.

Syed Raza, former Caltrans Deputy District Director for Project/Program Management, has significant experience and is well-versed in the agency/project reporting processes, the expected level of detail, clarity and accuracy of the message, and solid arguments supporting the information and requests for various approvals. Syed has used his skill set to help the City of Chino with their federally funded $50M Pine Avenue Extension Project through Caltrans Office of Local Assistance, coordinating with various stakeholders including City of Chino Hills, San Bernardino County Flood Control District, U.S. Army Corp of Engineer, Southern California Edison and other resource agencies. His proactive program management approach, communication and problem-solving skills, ability to build consensus and strong leadership skills has helped RTPAs, counties and cities deliver their portfolio of projects on and off State Highway System.

Gabriel Rodriguez, EXP’s engineering lead, and Anh Case, our construction management lead on this team, will guide the preparation of all technical reports, design, and other documents for all assigned projects and check the reports for accuracy and relevance prior to final signatures. They also will review or assign qualified team members to review the design and documents prepared by others for various projects in the City.

Outside Agency Coordination
EXP staff will assist the City staff in all discussions, coordinations, plan check, negotiations, agreements, processing paperwork, permits, and other efforts involving Caltrans Local Assistance, Permits, Right-of-Way, Project Development, Project Management, and other departments; County of Los Angeles; LA Metro; and other agencies for federal and state funded projects.

Long and solid relationships between some of EXP managers and these agencies and our deep knowledge of their processes, procedures, constraints, and expectations will be extremely useful to the City of Lynwood in having quick as-needed communication and answers and will help the City get to the desired results. In discussions of funding, plan and document checks, permit approvals, and other collaborations, these professional relationships will work to all parties’ advantage.

We will also help the City staff in communication with
State and federal agencies. We will review correspondence with those agencies and provide input and assistance with responses and follow up communication where needed.

Abdollah Ansari and Syed Raza have successfully conducted inter-agency coordination and negotiations with local, State, and federal agencies to support timely and cost-effective delivery of local and State projects.

APPROACH TO PROJECT | 8
City of Lynwood
On-Call Engineering Services
442
In his role as the project/contract manager leading the implementation of an emergency roadway reconstruction
project for the City of LA, Abdollah successfully managed utility relocation efforts with the LADWP an Southern
California Gas Company, for relocation of water, power, and gas lines to accommodate timely implementation of projects.

As well, Abdollah, while leading the LA Metro Highway
Programs, successfully managed multi-agency coordination with local, regional, State, and federal agencies for the implementation of several major freeway improvement
projects funded by Measure R an M sales tax funds.

Quality Assurance/Quality Control
Quality Assurance and Quality Control (QA/QC) apply to
all types and phases of work assigned in this contract. As several EXP managers are former Agency managers, the “client expectations” concept is well understood and embedded in our services and is one of our core values.

We implement a rigorous and effective QA/QC Plan for all projects irrespective of size or complexity. EXP prepares a comprehensive project specific Quality Management Plan
(QMP) for every project to demonstrate its commitment to quality. The QMP outlines an effective and efficient process for the development, review, and approval of all project deliverables, sets quality and document control requirements, and defines the timing and procedures for technical peer reviews and draft plan and document checks including
engineering reports. It also provides consistency to the Quality Review Process and highlights the standards to use throughout the life of the project. The QMPs for the projects assigned to EXP will be prepared by Luis Betancourt, Former Caltrans Headquarters’ QA/QC manager responsible for Districts’
production and will be submitted to the City for review and approval within two weeks of receiving the Notice To Proceed for every project. Luis’ decades of experience with design and quality management of complex transportation projects will be of high value to the City of Lynwood.

Luis, Abdollah Ansari, Syed Raza, and EXP functional leads will closely collaborate to ensure all requirements for quality production are met. We will apply the same QA/QC concepts and procedures to the focused work assigned to the specialty area subconsultant on our team. At the award of a focused work task order to one of our subconsultants, we will identify a QA/QC manager from the subconsultant firm, share the
guidelines and requirements with them, and maintain regularly scheduled meetings and communication with them to the
completion of work prior to final approvals.

In his role as Caltrans Project Delivery Coordinator, Luis provided advice/guidance for major highway improvement
projects at the project initiation stage and throughout the PS&E phase. He reviewed and approved the QA/QC process
for capital improvement projects by various Caltrans District offices and ensured the uniform application of geometric design standards, procedures, guidelines, and practices.

Luis’ efforts led to the development of high quality and cost effective major highway capital projects within the programmed allocations and established schedules.

We have selected subconsultant firms that we have worked with in the past years/decades, who provided services to those of us who were on the Agency side and delivered beyond expectations. We have already tested these firms and trust their expertise and focus on quality of the services they provide to their clients.

APPROACH TO PROJECT | 9
City of Lynwood
On-Call Engineering Services
443
04 project Experience
444
04 | PROJECT EXPERIENCE
Project REFERENCES
Table 4.1 below shows references for recently completed projects by EXP as either a prime consultant or sub-consultant. All of the completed projects were on-call contracts with the City of Chino, Caltrans Districts 8, Caltrans District 12 and Orange County Public Works. EXP has successfully managed and/or completed a total of 18 task orders with these clients over the past five years. The type of work performed included staff augmentation, project management, risk management, freeway maintenance agreements, roadway design, drainage design, traffic signals, construction staging, traffic handling, pavement delineation, signing, striping, ADA curb ramps, curb & gutter, sidewalks and bike lanes. The successful completion of these task orders demonstrates EXP’s ability to respond to the on-call contracts quickly and assign the right number and mix of resources to get the job done efficiently and expeditiously. Following the table are related, select and more detailed project examples.

TABLE 4.1 | Project References

SERVICE DISCIPLINE LEGEND:
1: GENERAL ENGINEERING | 3:TRAFFIC ENGINEERING SERVICES CLIENT | PROJECT NAME

SERVICE DISCIPLINE(S)

SERVICES PROVIDED YEAR COMPLETED
1 . CONSTRUCTION
COST

2. DESIGN FEE

3. OVERALL

PROJECT BUDGET

CONTACT

INFORMATION
EXP’S PROJECT

MANAGER
City of Los Angeles,
Department of Public
Works - Bureau of
Engineering, On-Call
Kinney Street
Improvements and
Emergency Repairs/
Reconstruction
7th Street Improvements
Project - Roadway and
Transit Improvements
SERVICE DISCIPLINE(S): 1, 3
Project management, civil
engineering, drainage engineering,
CAD/drafting, agency/utilities
coordination, design correction
during construction for work done
by others, Traffic (MOT)
On-Going 1. Varies. Tasks
assigned
are design,
design during
construction,
project
management,
and construction
management.

Estimated
construction cost
for the Kinney St.

Emergency Repairs
project is $4
million.

2. $2.5M for all
task orders

3. $4.5M for all task
orders (includes
design, project
management,
and construction
management fees)
Bureau of Engineering
Street Improvement
Division, Department of
Public Works
Arsen Voskerchyan, PE
Principal Civil Engineer
t: 213.923.4963
Abdollah Ansari
City of Lynwood
On-Call Engineering Services
PROJECT EXPERIENCE | 10PROJECT EXPERIENCE | 10
445
CLIENT | PROJECT NAME

SERVICE DISCIPLINE(S)

SERVICES PROVIDED YEAR COMPLETED

1. CONSTRUCTION
COST

2. DESIGN FEE

3. OVERALL

PROJECT BUDGET

CONTACT

INFORMATION
EXP’S PROJECT

MANAGER
Caltrans District 8
PM On-Call
SERVICE DISCIPLINE(S): 1
Project/program management,
PM Support Services (Project
Management, Quality
Management, Risk Management,
Freeway Maintenance Agreements,
Freeway Agreements)
First contract
ended in 2023. EXP
was selected again
for the period of
2023-2026.

1. N/A (PM Contract)

2. $3.5M(Contract 1)
$4M (Contract 2)

3. $200M per
contract.

Caltrans District 8
Bahar Bakhtar, Contract
Manager
t: 310.402.8179
Khalil Saba
City of Chino
Pine Avenue Ramp
Widening Project
SERVICE DISCIPLINE(S): 1, 3
Traffic Study, Traffic Simulation,
Signal Design, Lighting Design,
Communication Design, Signing/
Striping Plans, Traffic Control Plans,
Project Management,
Technical Studies, Drainage System
Design, Right of Way, Utilities
On-Going 1. $3.5M

2. $1M

3. $4.6M
City of Chino
Michele Hindersinn, PE,

QSD/QSP
Public Works Department
t: 909.334.3513
Syed Raza
City of Temecula
Santa Gertrudis Creek
Phase II
SERVICE DISCIPLINE(S): 1
Technical Studies, Hydraulic
Analysis, Structures, Scour Analysis.

On-Going 1. $2.3M

2. $420K

3. $2.7M
City of Temecula
Will Becerra Jr., Associate
Engineer
t: 951.693.3963
Gabriel Rodriguez
San Bernardino County
Transportation Authority
(SBCTA)
SR-210 Waterman Ave
Interchange
SERVICE DISCIPLINE(S): 1, 3
Traffic Engineering (Traffic Study,
Signal Design, Ramp Metering
Design, Signing/Striping Plans, and
Traffic Control Plans), Roadway and
Structural engineering, Drainage,
environmental, geotechnical,
surveying, and utility coordination.

On-Going 1. $5.8M

2. $644K

3. $6.5M
San Bernardino County
Transportation Authority
(SBCTA)
Paul Melocoton, Project
Manager
t: 909.884.8276
Syed Raza
City of Seal Beach
Engineering On-Call
Task Order: Marina Drive
Resurfacing Project
SERVICE DISCIPLINE(S): 1, 3
Pavement Improvements,
Resurfacing, Intersection and
Roadway Rehabilitation, Traffic
Engineering (MOT)
On-Going 1. $550K

2. $34K

3. $590K
City of Seal Beach
Iris Lee, Deputy Public
Works Director/City
Engineer
t: 562.431.2527
Gabriel Rodriguez
Caltrans D59
D8 & D9 Construction
Management On-Call
SERVICE DISCIPLINE(S): 1
Construction Management and
Inspection services to Caltrans in
District 8 and District 9.

On-Going 1. $900M (I-10 |
Contract 1)

2. $350K (CM)

3. Sub to Falcon
- Overall Budget
Unknown
Caltrans D59
Scott A. Gueltzow, PE
Area Senior Bridge
Engineer (BCE)
Engineering Services -
Structure Construction
t: 951.830.6695
Anh Case
Caltrans District 12
Pacific Coast Highway
(SR1) Traffic Signal
Upgrades
Pacific Coast Highway
(SR1) Pavement
Rehabilitation
SERVICE DISCIPLINE(S): 1, 3
Drainage Design, Hydrology and
Hydraulics, Stormwater Data
Report, Temporary Water Pollution
Control
Drainage Design, Hydrology and
Hydraulics, Stormwater Data
Report, Temporary Water Pollution
Control
2022 1. $25M

2. $151K (Signal) |
$48K (Pavement)

3. Sub to ACT -
Overall Budget
Unknown
Caltrans District 12
Phi Dinh
Chief, Hydraulics Branch
t: 657.328.6172
Portia Gonzalez
TABLE 4.1 | Project References (CONTINUED)
PROJECT EXPERIENCE | 11
City of Lynwood
On-Call Engineering Services
446
CLIENT | PROJECT NAME

SERVICE DISCIPLINE(S)

SERVICES PROVIDED YEAR COMPLETED

1. CONSTRUCTION
COST

2. DESIGN FEE

3. OVERALL

PROJECT BUDGET

CONTACT

INFORMATION
EXP’S PROJECT

MANAGER
City of Jurupa Valley
Pacific Avenue Pedestrian
& Bicycle Improvements
SERVICE DISCIPLINE(S): 1, 3
Roadway Design, Shared Bike
Lanes, Pavement Rehabilitation,
Drainage, Traffic Signal
Modification, Signing and
Striping, ADA Curb Ramps, Utility
Relocation
2023 1. $2M

2. $144K

3. $2.3M
City of Jurupa Valley
Octavio Duran Jr., PE
t: 951.332.6464 ext 242
Portia Gonzalez
City of Beaumont
On Call Professional
Traffic Engineering
Services
SERVICE DISCIPLINE(S): 3
Traffic Engineering
On-Going 1. N/ A

2. $100K

3. $100K
City of Beaumont
Richard Godsey
Permit Engineer
t: 951.769.8520 ext. 344
Syed Raza
City of Chino
On-Call Civil Engineering
Services for Public Works
CIP Projects
SERVICE DISCIPLINE(S): 1, 3
Civil Engineering, Traffic
Engineering (Traffic Analysis,
Signing and Striping)
On-Going 1. N/ A

2. $100K

3. $100K
City of Chino
Michele Hindersinn, PE,

QSD/QSP
Public Works Department
t: 909.334.3513
Syed Raza
TABLE 4.1 | Project References (CONTINUED)
PROJECT EXPERIENCE | 12
City of Lynwood
On-Call Engineering Services
447
EXP was selected by the City of Los Angeles Bureau of Engineering to provide as-needed professional services to assist in delivery of the City’s projects. We were assigned to the 7th Street Improvements Project to provide engineering and coordination services during construction including providing risk preventive/ corrective design modifications and supporting third-party coordination during construction. The items of concern included providing power to the bus pads, installing planters on the pads, design adjustments to ensure the pads are not in conflict with turning vehicles, identifying potential conflicts between sidewalk improvements and building basements/chambers under sidewalks, coordination with the LA Metro on installation of bus stop signs, benches, canopies, and other work.

Client
City of Los Angeles Bureau of
Engineering
Arsen Voskerchyan, PE
Street Improvement Division
Manager - Principal Civil Engineer
t: +1.213.923.4963
Timeline
May 2023 - Ongoing
Key Staff
• Abdollah Ansari
• Ju Kim, PE
Relevance
• Project Management
• Engineering Support During
Construction
• Agency Coordination
7th Street Roadway and Transit Improvements
Los Angeles, CA
Service Category(s):

General Engineering
+ Traffic Engineering
PROJECT EXPERIENCE | 13
City of Lynwood
On-Call Engineering Services
448
Client
City of Los Angeles Bureau of
Engineering
Arsen Voskerchyan, PE
Street Improvement Division
Manager - Principal Civil Engineer
t: +1.213.923.4963
Timeline
May 2023 - January 2024
Key Staff
• Abdollah Ansari
• Portia Gonzalez, PE, QSD/QSP
• Mohammad Muqtadir, PhD, PE
• Ben Hashemloo, PTOE
• Mitsuru Tanaka, PTOE, PTP
Relevance
• Project Management
• General Engineering
• Roadway Improvements/
Reconstruction
• Drainage Studies/Engineering
• Traffic Engineering
• Utility Relocation
EXP is providing roadway and retaining walls design, drainage studies and engineering, community coordination/briefing support, utility coordination, and other services to the LABOE.

There are two projects in progress at this time:

Project 1: Geometric design corrections to widen part of the road, modify the longitudinal and cross slopes of the road and widen/flatten a steep bend on the street to improve vehicular movement and safety at this location. This project has been promised to the community for a long time and is the first phase of a larger project to improve the street. Our team is on schedule for the PS&E delivery.

Project 2: Widening, geometric design improvements, retaining walls, and drainage improvements for a section of the road that has settled/failed due to rain seepage, weakness of the underlayers, and heavy loading/heavy vehicles. The slopes on the south/west side of the road are also moderately eroded and further failure of the roadway is imminent. This project is scheduled to be constructed before the upcoming storm season. Coordinations with the Southern California Gas Co. and the LADWP are in progress an relocations are being scheduled. Our team is on schedule to finish the final design and accommodate the construction of the project before the rain season.

Kinney Street Improvements and Emergency Repairs
Reconstruction
Los Angeles, CA
Service Category(s):

General Engineering
+ Traffic Engineering
PROJECT EXPERIENCE | 14
City of Lynwood
On-Call Engineering Services
449
EXP is providing consultation, research, professional and technical services required for Program/Project Management Services on an “as-needed” basis to support Caltrans, Division of Program/Project Management (PPM), District 8.

EXP is providing services to Caltrans including, but not limited to, integration management; scope management; time management; cost management; quality management; resource management; communication management; risk management; project scheduling; project coordination; PM developments and project resource estimating services.

The projects involved varies in scope and size and encompass any type of improvement for the State transportation system including, but not limited to, roadway rehabilitation, widening and/or realignment of existing facilities, relocation of existing facilities, and construction of new facilities.

Service Category(s):

General Engineering
Client
Caltrans District 8
Bahar Bakhtar
Caltrans Contract Manager
t: +1.310.402.8179
Timeline
May 2020 - June 2023
Recompete: September 2023 -
September 2026
Key Staff
• Syed Raza, PE
• Christine Brown, PE
• Gabriel Rodrigue, PE
• Portia Gonzalez, PE, QSD/QSP
Relevance
• Project Management
• General Engineering
Program/Project Management Support Services
San Bernardino, CA
PROJECT EXPERIENCE | 15
City of Lynwood
On-Call Engineering Services
450
EXP is providing comprehensive professional civil engineering services on an on-call/as-needed basis that include developing plans, technical specifications and estimates, bid support, construction management, survey, geotechnical, community outreach, and processing required permits and agreements.

Task Orders
Main Street Pavement Improvements
The City of Seal Beach proposed to Mill and Overlay four residential streets as well Main Street which intersects the Major State Highway Pacific Coast Highway. The existing asphalt was sub-standard with multiple areas with alligator crack failures.

EXP developed plans, technical specifications and estimates for these streets as part of the City’s Annual Paving Program and was instrumental in providing the IFB package on schedule for the City’s procurement of a contractor. Services include roadway geometric design, Traffic Control Plan, and plan production.

Marina Drive Resurfacing Project
The project proposed to rehabilitate the existing asphalt paving on Marina Drive between 1st Street and State Route (SR) 1. EXP prepared plans, specifications, and an estimate that included milling and overlay, full depth structural section replacement, ADA improvements, cross gutter and driveway replacements, and signing and striping. EXP also obtained an encroachment permit from Caltrans District 12 for traffic control on SR-1. Construction was completed in the summer of 2021.