ADDENDA CONFIRMATION
Addendum #1
Confirmed Mar 10, 2025 9:58 AM by Kiley Sandoval
Addendum #2
Confirmed Mar 10, 2025 9:58 AM by Kiley Sandoval
QUESTIONNAIRE
1. Proposal (WITHOUT COST)*
Proposals shall be concise, well organized and demonstrate qualifications and applicable experience. Proposals shall be organized and include page numbers for all pages in the proposal. The proposal shall be uploaded here, in the following order and shall include:
A. Cover Letter
1. This letter should briefly introduce the firm, summarize the firm’s general qualifications, include an executive summary of the specific approach which will be used to deliver the work scope; and identify the individual(s) name, address and phone number authorized to negotiate Agreement terms and compensation.
B. Experience and Technical Competence
1. Background: Provide history of the firm’s consulting experience which specifically addresses the individual or firm’s experience with similar Service as described in this RFP.
2. References: The proposal shall include a list of recently completed projects that are similar in scope and function to this RFP. Provide a description of the project, client name, and the name, title, and telephone number of the primary contact person.
C. Firm Staffing and Key Personnel
610
[ARCHITERRA DESIGN GROUP] RESPONSE DOCUMENT REPORT
RFP No. 2024-RFP-156
Park and Trailhead Engineering and Design
[ARCHITERRA DESIGN GROUP] RESPONSE DOCUMENT REPORT
Request For Proposal - Park and Trailhead Engineering and Design
1. Staffing: Provide the number of staff to be assigned to perform the Services and the names/discipline/job title of each as well as your firm’s capacity to provide additional personnel as needed.
2. Key Personnel: Identify key persons that will be principally responsible for working with the City. Indicate the role and responsibility of each individual.
3. Team Organization: Describe proposed team organization, including identification and responsibilities of key personnel.
4. Subcontractors: The Proposer shall identify functions that are likely to be subcontracted and identify the subcontractor that is anticipated to perform each function.
D. Proposed Method to Accomplish the Work
1. Describe the technical and management approach to providing the Services to the City. Proposer should take into account the scope of the Services, and general functions required. Include a draft first year schedule of tasks, milestones, and deliverables that will provide for timely provision of the Services. In reviewing the scope of Services and goals described herein, the Proposer may identify additional necessary tasks and is invited to bring these to the City’s attention within the discussion of its proposed method to accomplish the work. 0318_25_City_of_Palm_Desert_Park_and_Trailhead_RFP_Architerra.pdf
2. Fee Proposal*
Please provide a lump-sum, not-to-exceed fee proposal for the scope of Services. The fee proposal shall include hourly rates for all personnel for “Additional Work” (as such term is defined in the proposed Agreement attached herein). 25_0318_City_of_Palm_Desert_Park_and_Trailhead_Fee_Architerra.pdf
3. Non-Collusion Declaration*
The undersigned declares:
I am an authorized representative of my company, the party making the foregoing Bid, to certify the following.
The Bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The Bid is genuine and not collusive or sham. The Bidder has not directly or indirectly induced or solicited any other Bidder to put in a false or sham bid. The Bidder has not directly or indirectly colluded, conspired, connived, or agreed with any Bidder or anyone 611
[ARCHITERRA DESIGN GROUP] RESPONSE DOCUMENT REPORT
RFP No. 2024-RFP-156
Park and Trailhead Engineering and Design
[ARCHITERRA DESIGN GROUP] RESPONSE DOCUMENT REPORT
Request For Proposal - Park and Trailhead Engineering and Design
else to put in a sham bid, or to refrain from bidding. The Bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the Bid Price of the Bidder or any other Bidder, or to fix any overhead, profit, or cost element of the Bid Price, or of that of any other Bidder. All statements contained in the Bid are true. The Bidder has not, directly or indirectly, submitted his or her Bid Price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a Bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the Bidder.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct.
Confirmed
4. SAM.gov*
Please enter your legal entity name for SAM.gov verification.
ARCHITERRA, INC.
Click to Verify Value will be copied to clipboard
5. Type of Business*
S Corporation (if corporation, two signatures are required)
6. Litigation*
Provide litigation history for any claims filed by your firm or against your firm related to the provision of Services in the last five (5) years (or type "N/A").
N/A
612
[ARCHITERRA DESIGN GROUP] RESPONSE DOCUMENT REPORT
RFP No. 2024-RFP-156
Park and Trailhead Engineering and Design
[ARCHITERRA DESIGN GROUP] RESPONSE DOCUMENT REPORT
Request For Proposal - Park and Trailhead Engineering and Design
7. Changes to Agreement*
The City standard professional services agreement contract is included as an attachment herein. The Proposer shall identify any objections to and/or request changes to the standard contract language in this section of the proposal (or type "N/A"). If you are identifying changes here ALSO upload a copy of the redlined Language/Agreement with your Proposal. Changes requested may affect theCity's decision to enter into an Agreement.
N/A
8. No Deviations from the RFP*
In submitting a proposal in response to this RFP, Proposer is certifying that it takes no exceptions to this RFP including, but not limited to, the Agreement. If any exceptions are taken, such exceptions must be clearly noted here, and may be reason for rejection of the proposal. As such, Proposer is directed to carefully review the proposed Agreement and, in particular, the insurance and indemnification provisions therein (or type "N/A").
N/A
9. Project Team Resumes*
Submit resumes of all key personnel/support staff that will produce work product for the Services. Describe their qualifications, education, and professional licensing.
Architerra_Resumes.pdf
10. List the Signatory(s) Authorized to Sign and Bind an Agreement.* (If two (2) signatures are required, include the following information for both signatories) A. Full Name
B. Title
C. Physical Business Address
D. Email Address
E. Phone Number
613
[ARCHITERRA DESIGN GROUP] RESPONSE DOCUMENT REPORT
RFP No. 2024-RFP-156
Park and Trailhead Engineering and Design
[ARCHITERRA DESIGN GROUP] RESPONSE DOCUMENT REPORT
Request For Proposal - Park and Trailhead Engineering and Design
GREGG DENSON, PRESIDENT
10221-A TRADEMARK STREET, RANCHO CUCAMONGA, CA 91730
[email protected]
909-484-2800
ANDREW KRUMWIEDE, VICE PRESIDENT
10221-A TRADEMARK STREET, RANCHO CUCAMONGA, CA 91730
[email protected]
909-484-2800
11. Conflict of Interest Disclosure*
The proposer understands that any and all relationships with construction firms that may submit bids for projects developed under this agreement will require full disclosure of any direct or indirect conflicts of interest, financial interests, relationships, and the nature of any relationships with any related project bid submitters; and that any violation of this provision may result in the immediate termination of the Agreement
Confirmed
12. Certification of Proposal*
The undersigned hereby submits its proposal and, by doing so, agrees to furnish services in accordance with the Request for Proposal (RFP), and to be bound by the terms and conditions of the RFP.
Confirmed
614
Melanie Slater, Management Analyst
73510 Fred Waring Drive, Palm Desert, CA, 92260
Email: [email protected]
Phone: (760) 776-6447
DIRECTED TO:
PROPOSAL FOR:
Park and Trailhead
Engineering and Design RFP
City of Palm Desert
March 18, 2025
ADG Project: Phil and Nell Soto Park
ADG Project: North Etiwanda Preserve
ADG Project: Route 66 Trail - Rialto
ADG Project: Hamilton Park
ADG Project: Desert View Area
ADG Project: Cucamonga Basin #6
615
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800 March 18, 2025
Melanie Slater, Management Analyst
73510 Fred Waring Drive
Palm Desert, CA 92260
(760) 776-6447
RE: LANDSCAPE ARCHITECTURAL SERVICES PROPOSAL, PARK AND TRAILHEAD ENGINEERING AND DESIGN, CITY OF PALM DESERT, CA.
Dear Ms. Slater,
We are pleased to submit this proposal for Landscape Architectural Services in connection with the project referenced above. This agreement is by and between Architerra Design Group, Inc. (ADG) and the City of Palm Desert (City).
Architerra has an extensive background in recreational trail, open space planning, and traditional park design, as evidenced by the relevant experience detailed within this proposal. The City can gain significant benefits from selecting our firm for its Park and Trailhead Design Projects. Leveraging over 33 years of industry experience, we offer specialized expertise and a demonstrable record of delivering exceptional results and experiences tailored to enhance recreational, scenic, and naturebased enjoyment. Our portfolio, which includes award-winning park and trail projects for numerous agencies analogous to your own, provides a foundation for confidence in our capabilities. These accomplishments underscore our unwavering commitment to excellence, professionalism, and a dedication to consistently surpassing client expectations.
Our firm is well-staffed with 17 professionals, including 6 licensed landscape architects and 4 project managers, ensuring that we have the necessary skills and manpower to meet the City’s needs in a timely manner. The team assembled for this project, including our subconsultants, Madole - Civil Engineering, JCA - Electrical Engineering, GeoTek- Geotechinical, SVA- Architect, California WatersWater Feature, AGI- Grant Writing, and ECORP - Environmental, have been meticulously selected based on their extensive experience in past projects similar to the Park and Trailhead Design Projects and their comprehensive understanding of all the City’s specified requirements.
Our expertise has consistently surpassed expectations, particularly in areas such as imaginative, well thought out design, collaborations with local communities, trailheads, playgrounds, water features, and interpretive signage. Our in-house staff excels in creating iconic designs, implementing creative design features including inclusive playgrounds for all ages, that provide high-quality outdoor experiences.
Our commitment to sustainability and preserving existing plants and trees ensures that every project respects and enhances the natural environment.
Furthermore, we have successfully partnered with numerous agencies similar to yours, facilitating community meetings (even with Spanish speaking audiences) to foster collaboration and ensure that projects progress smoothly and remain on schedule. In this proposal we are pursuing six of the seven potential projects, with Hovley Soccer Park being excluded.
We look forward to the possibility of working together with your agency, contributing to the enhancement of the City and success of the Park and Trailhead Design Projects. This proposal is valid for 90-days from the date of submittal. My California license, address, and telephone number are listed below.
Sincerely,
Gregg Denson, President, PLA #4302
[email protected]
(909) 484-2800 ext. 1015
616
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800 1 2 3
4 5 6
7 8
9 10
15 14
13 22 20 19 18 17 16
21 24
TABLE OF CONTENTS
A. Cover Letter........................................................................................
Table of Contents....................................................................................
B. Experience and Technical Competence
Intro and Background..................................................................
Similar Project Experience...........................................................
C. Firm Staffing and Key Personnel
Staffing...........................................................................................
Key Personnel................................................................................
Team Organization.......................................................................
Subcontractors.............................................................................
D. Proposed Method to Accomplish the Work
Homme Adams Park....................................................................
University Park...............................................................................
Washington Charter.....................................................................
Randall Henderson Trailhead......................................................
Freedom Park................................................................................
Ironwood Park...............................................................................
Appendices.............................................................................................
Project Schedules......................................................................... 2 3
4 5
10 11
17 18
20 26
31 36
42 47
Nichols Ranch - ADG Graphics
53 54
617
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
B. EXPERIENCE AND TECHNICAL COMPETENCE Page 4
The City of Palm Desert is a thriving community with big-city resources in a friendly, small-town setting, offering first class educational opportunities, safe and clean streets, as well as plentiful shopping and community events. As the geographical, educational and retail center of the Coachella Valley, updating and modernizing parks and trailheads is a paramount to ensuring high-quality outdoor experiences for its residences.
We understand the importance of this project. Architerra is dedicated to designing welcoming, inviting and enjoyable spaces for a variety of users. We have experience with creating conceptual designs, community engagement, preparation of construction documents, and construction support for a variety of trail and park projects. Architerra has the creative talent to create data-driven conceptual designs that meet the established community needs, while also capable of developing Management Plans to ensure long-term maintenance to the City’s standard. A recent project of note is Architerra’s preparation and creation of the Desert View Conservation Area’s (DVCA) Maintenance Manual, which is a comprehensive guide to the care of the built improvements within the DVCA in Joshua Tree, California.
Architerra Design Group (ADG), was established in 1991. ADG is a California S-corporation and SBE located in Rancho Cucamonga, CA.
Our office is located at: 10221-A Trademark Street, Rancho Cucamonga, CA 91730. The office phone number is (909) 484-2800.
Over our 33+ years of business Architerra strives to deliver high quality work that leaves a lasting impact that is not only beautiful but environmentally conscious for the everyday conditions that are present in the Southern California Area. In doing so we’ve fostered an environment of continuous learning to meet the needs of our clients for not only the time period we are in but also to push the envelope and show what is possible for our clients. The opportunity to work on any of the Park and Trailhead Design Projects is another chance to show Architerra has what it takes to create and implement exciting envelop pushing projects. We will demonstrate through our project examples in this proposal how we’ve built a portfolio that emphasizes the natural environment and brings together the community while providing iconic and unique experiences. Architerra has implented extensive Public Engagement Plans and Community Engagement Meetings for a variety of projects. A few to note are Ketchum-Libolt Park (a) in Costa Mesa, Cucamonga Basin #6 (b) in Upland, Wildomar 20-Acre Park (c) in Wildomar, the Desi House in Eastvale, Hillbrook Park in Signal Hill, Hamilton Park in Pomona, and Tierra Rejada Park in Moorpark. 618
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Approximately 1.3 miles long this multi-purpose trail is the Eastern most portion of the larger 22 mile regional Pacific Electric Trail which stretches from the border of Los Angeles County at Claremont to the terminus in Rialto, California. ADG designed a historically-themed trailhead utilizing the legacy of the site at the onset of the Pacific Electric Trail within the City and the location of the original “Mother Vineyard,” providing a safe and accessible entry for pedestrian, bicycle, and equestrian trail users, along with connection to the larger regional non-motorized, multi-use commuter and recreational trail system.
Pacific Electric Trail & Route 66 Trailhead Park, Client: City of Rancho Cucamonga Related Past Experience / Similar Projects
Bike and
Equestrian
Interpretive
Signs
Native
Trees & Plants
Irrigation &
Water Control
Community
Trailhead
Landmark
Aerial View
Winner of an ASLA Merit Award, the project is located in the fragile and important desert ecosystem of Joshua Tree. The trail system encourages sustainability and environmental stewardship while underscoring native and historic cultural elements. The interpretive goal of the project is to foster an understanding of how human impact affects the local flora and fauna ecology, educate locals and visitors about the diversity of the area and mitigate human effects by providing a guided trail to keep foot and other traffic away from sensitive areas.
Desert View Area - Joshua Tree, Client: SB County Special Districts Outdoor
Structure
Nature
Preserve
Collaboration
w/ Local Tribe
Bike, Hike,
Equestrian
Interpretive
Signs
Reference: John Hernandez, Project Manager, County of San Bernardino Special Districts (909) 386-8847.
Reference: Jerry Dyer, Project Engineer, City of Rancho Cucamonga, (909) 477-2740 ext. 4037.
TRAILS:
619
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Winner of the 2010 American Society of Landscape Architects (ASLA) “Honor Award” for Specialty Parks, this 1,200-acre natural open-space preserve is in San Bernardino County, north of the City of Rancho Cucamonga, CA. Located within proximity to a large and growing urban population, the trails of the North Etiwanda Preserve provide both active and passive recreational opportunities such as hiking, trail running, and bird and wildlife viewing.
North Etiwanda Preserve, Client: S.B. County Special Districts Related Past Experience / Similar Projects
Bike, Hike,
Equestrian
Interpretive
Signs
Nature
Preserve
Outdoor
Structure
TRAILS:
Reference: John Hernandez, Project Manager, County of San Bernardino Special Districts (909) 386-8847.
While built to provide flood protection and water quality control, this multi-agency project included habitat restoration and trail design creating open space recreation opportunities within the San Bernardino County Flood Control District. ADG took what would normally be viewed as an obtrusive “hole in the ground” and turned it into an award winning and groundbreaking facility protecting a newly constructed housing community from a 100-year flood in addition to offering a dynamic and self-perpetuating ecosystem providing residents unique recreational and educational opportunities.
Cucamonga Basin #6, Client: San Bernardino County, Flood Control District Irrigation &
Water Control
Community
Trailhead
Native
Trees & Plants
Community
Outreach
Nature
Preserve
Bike and
Equestrian
Reference: John Hernandez, Project Manager, County of San Bernardino Special Districts (909) 386-8847.
620
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
A park retrofit in Pomona, California, Architerra worked through multiple stages of community outreach to deliver a universally accessible & visually vibrant park space, that the community loves and utilizes daily.
Hamilton Park, Client: City of Pomona
Related Past Experience / Similar Projects
Native
Trees & Plants
Irrigation &
Water Control
Landmark
Aerial View
Outdoor
Structure Playground Community
Outreach
PARKS:
Reference: Shandy Dittman, Public Works Fiscal and Project Manager, City of Pomona, Public Works, 909-620-3797.
Phil and Nell Soto Park, Client: City of Pomona
The passive nature-oriented park was developed with extensive community input with the goal of creating a space that encouraged health, wellness, and nature-based educational opportunities. In addition, ADG conducted community outreach meetings with City staff, complete with our in-house Spanish-speaking translator.
Reference: Shandy Dittman, Public Works Fiscal and Project Manager, City of Pomona, Public Works, 909-620-3797.
Outdoor
Structure
Community
Outreach
Irrigation &
Water Control
Community
Trailhead
Native
Trees & Plants
Nature
Preserve
621
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT Related Past Experience / Similar Projects Page 8 SPLASH PADS AND WATER FEATURES:
ADG prepared the conceptual design, design development, construction documents, bidding assistance, and construction observation services for three splash pad areas at the Lake Gregory Regional Park in Crestline, CA. This project included a Toddler, Family, and Teen splash pad areas, allowing play for all ages.
Lake Gregory Zero Depth Water Playground, Client: County of San Bernardino, Special Districts Reference: John Hernandez, Project Manager, County of San Bernardino Special Districts (909) 386-8847.
ADG prepared the conceptual design, design development, and construction documents for the 40’ diameter splash pad in Ayala Park, Bloomington, CA. This project is fully ADA compliant, ensuring accessibility and opportunities for fun for all abilities.
Ayala Park Splashpad, Client: County of San Bernardino, Public Works, Special Districts Reference: Charles Hernandez, Project Manager, Department of Public Works, Special Districts 909-386-8832.
Irrigation &
Water Control
ADA
Accessible
Hardscape
& Walkways
Fence &
Windscreen
Water
Features
Irrigation &
Water Control
ADA
Accessible
Hardscape
& Walkways
Fence &
Windscreen Water
Features
622
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Our in-house Graphic Design staff produces interpretive signage for a majority of our projects.
Relevant examples are shown below:
Follow The Path Amphibians and Water Frogs are cool! Their presence is a sign of biodiversity, a strong ecosystem and everything worth protecting in our natural environment. Frog Walk is a visual reference trail featuring the life cycle of the frog. As most frogs require both land and water environments, the bioswale here will help to create an amphibian garden home.
Frogs are important to the water cycle and to humans. Tadpoles keep water sources clean by feeding on algae, while adult frogs eat pests and insects that can carry disease. Frogs are an important indicator species, meaning that a healthy population of frogs means a healthy natural environment.
Bioswales Bioswales capture storm water runo, as well as any excess water ow from landscape
irrigation. The sloping sides direct water into the swale where the gentle course slows the water, allowing it to percolate through the soil. Larger bioswales can help replenish groundwater resources, while smaller ones provide water for surrounding plants by retaining water on site rather than carrying it away through a storm drain system.
As you follow the life cycle of the frog to adulthood, look over to the bioswale and remember – we are all part of this circle of life and what we do to sustain ourselves and other species only makes the world a better, cleaner and healthier place to live. Frogs can help to teach us how we are all interconnected in this ecosystem we call Earth! Ecosystem An ecosystem is a community of living organisms plants, animals and microbes supported by nonliving components of their environment like air, water, minerals and soil. The interaction of these components provide nourishment and energy to sustain life. Ecosystems can come in any size, from small areas like this bioswale, to the entirety of planet Earth.
Look down! Frog eggs are dependent on a speci
c ecosystem, requiring both land and water. As
you begin this walk you will notice the growth cycle of the frog, and how this ecosystem beside you contributes to this bene
cial amphibian.
Water Cycle In the natural process of the "water cycle," water slowly moves its way through the landscape, as rain, melting ice and snow percolate into the groundwater table through streams and ponds, and all of this water
nally returns to the ocean. Natural vegetation helps to minimize soil disturbance and erosion,
ltering out sediment and debris.
Tadpoles grow and thrive in the water protected by the plants that grow along the banks of ponds, streams and other water sources. As you walk towards the tadpole, take notice of the landscape plants. It’s a frog garden, with all the resources to promote a healthy amphibian population.
Water Table Replenishment
Water is stored in the ground, is moving slowly and is still part of the water cycle. Most of the water in the ground comes from precipitation that in ltrates downward from the land
surface. The upper layer of the soil is the unsaturated zone, where water is present in varying amounts that change over time, but below this layer is the saturated zone, where all of the pores, cracks, and spaces between rock particles are saturated with water. The term groundwater is used to describe this area. Another term for groundwater is "aquifer." All of us need water, not just frogs. It is the most basic requirement of life. By encouraging systems that reuse and replenish our water, we are all helping to maintain a healthy water supply to help sustain life for generations to come.
Water Table Replenishment
Water is stored in the ground, is moving slowly and is still part of the water cycle. Most of the water in the ground comes from precipitation that in ltrates downward from the land
surface. The upper layer of the soil is the unsaturated zone, where water is present in varying amounts that change over time, but below this layer is the saturated zone, where all of the pores, cracks, and spaces between rock particles are saturated with water. The term groundwater is used to describe this area. Another term for groundwater is "aquifer." All of us need water, not just frogs. It is the most basic requirement of life. By encouraging systems that reuse and replenish our water, we are all helping to maintain a healthy water supply to help sustain life for generations to come.
FROG
FROG EGGS
TADPOLE
FROGLET
(FOUR LEGS)
TADPOLE FROG
(TWO LEGS)
Oak Woodland habitats typically occur on north-facing slopes and along riparian corridors where soil moisture is high and sun exposure is limited.
This area of Pomona is home to some long-standing oaks that date back long before European settlement of the area. Coast Live Oak and California Black Walnut trees are typically found around the local hills. This area of the park is home to drought-resistant and native plants that thrive in the oak woodland environment. Many wildlife species inhabit this plant community because of the abundant food supply and protective shelter. While not the official state tree, the oak’s nearly universal presence and cultural reverence throughout the state makes it an iconic symbol for all of California.
The Pollinator Garden was designed and planted specifically to attract butterflies, hummingbirds and other insects and animals that help nature reproduce and multiply. Butterflies and other insects move from flower to flower and as they do, pollen gets attached to their limbs. As they continue, they pollinate the flowers as is nature’s design, ensuring growth and propagation of the garden. In addition to the excitement and movement of the birds and insects, the flowers burst with color and provide a visual feast throughout spring and summer. This garden is a vital part of our local ecosystem.
Riparian woodland habitats are found
along both permanent and seasonal
watercourses. The stream beds that wind
through the park are designed to collect
rainwater and runoff. During the winter
months, rainwater collects in the stream
bed and provides additional moisture to
these species. Boulders and rocks
stabilize the stream banks and help
anchor the root systems. This habitat is
home to a variety of animal species,
including amphibians such as frogs and
salamanders. Larger mammals and birds
are attracted to this habitat as well.
The Meadow Grassland Garden is
populated with native grasses and
wildflowers much like you would find in
the foothills surrounding Pomona and the
greater San Gabriel Valley. During spring
and summer months, the meadow comes
to life with a spectacular display of color.
Annuals and perennials attract an
abundance of insects and animals adding
to the vibrancy of this ecosphere. The
Meadow Grassland Garden is more than a
turf substitute, it is a native plant
community highlighting California’s
unique perennial grasses and wildflowers.
Luiseños
TheOriginalPeople The name Luiseño was given to the area tribes by the Spanish who arrived in Southern California in the 17th century and were so named due to their proximity to the Mission San Luis Rey located in modern day Oceanside.
For over 10,000 years, the Luiseño or Payómkawichum as they are known in their native language – were spread out from what is now known as the southern part of Los Angeles County to northern San Diego County. They were hunter and gatherers with the men hunting deer, rabbits, small game, along with fishing in local streams and the ocean, while the women gathered an abundance of native acorns, nuts, beans, and fruits.
Today there are six federally recognized Luiseño bands. Recent legal victories on both the state and federal levels have assured their sovereignty leading to a renewed sense of purpose, self determination and prosperity.
Salvia apiana ‘White Sage,’ is an aromatic plant noted for its silvery gray to white foliage and beautiful white summer owers. Sage was widely used for its medicinal qualities as well as for use in Luiseño spiritual practices.
Muhlenbergia rigens ‘Deer Grass,’ was one of several plants used as for basket making. Other plants utilized included Sumac ‘Skunk Bush,’ and Juncus ‘Wire Grass.’ Basketry was one of the most cherished and important skills of the Luiseños.
Quercus agrifolia ‘Coast Live Oak,’ is a
revered indigenous tree that grows freely
throughout the area. The acorns were a
steady food source for the Luiseños.
This large rock served as a “Mortar” and the
Luiseños would use a “Pestle” to grind and
mash plants and minerals for medicinal and
food preparations.
This is a photograph of an early (circa 1900)
Luiseño home. The structure is made from natural
and traditional materials found locally, in much
the same way as their ancient ancestors.
Many examples of Luiseño culture and stories can be
found in local pictographs, still visible on rocks
throughout Mockingbird Canyon and many other
parts of what is now Riverside County.
Sweet Orange
Spanish Roots William Wolfskill (1798–1866) a native of Kentucky was a skilled hunter, trapper, herder, farmer and horticulturist. He became a Mexican citizen while fur trapping in New Mexico and moved to the Los Angeles area in the 1830s. He established farm and livestock operations in several ranchos around the region and at one time was the largest wine producer in the West.
He is most famous for being the “Father of the Citrus Industry,” and his profits from citrus was noted by an official with the Citrus Grower’s Union as having done more to “stimulate orange growth in Southern California” than any other factor. He is known for hybridizing and patenting the very popular sweet Orange known as the Valencia. Named for the Spanish City of the same name, the orange is a favorite of commercial growers and is known for its sweetness and its high vitamin C content as well as being the only commercial citrus crop to yield its harvest during the summer months.
William Wolfskill (1798–1866) a native of Kentucky was a skilled hunter, trapper, herder, farmer and horticulturist. He became a Mexican citizen while fur trapping in New Mexico and moved to the Los Angeles area in the 1830s. He established farm and livestock operations in several ranchos around the region and at one time was the largest wine producer in the West.
He is most famous for being the “Father of the Citrus Industry,” and his profits from citrus was noted by an official with the Citrus Grower’s Union as having done more to “stimulate orange growth in Southern California” than any other factor. He is known for hybridizing and patenting the very popular sweet Orange known as the Valencia. Named for the Spanish City of the same name, the orange is a favorite of commercial growers and is known for its sweetness and its high vitamin C content as well as being the only commercial citrus crop to yield its harvest during the summer months.
The climate is semi-arid Mediterranean and much like our home state requires well managed irrigation practices. Water rights and use disputes are decided by the Tribunal de las Aguas of Valencia which has been held in the same plaza for over 1000 years. *The answer is Spain, the photo is from an orange grove in Valencia.
Valencia lies in the Andalusia region of Spain, an area that was contested between the Christians of Northern Spain and the Moors of the Arabian Pennisula for hundreds of years. The architecture at Plaza de la Virgen shows both early Spanish and Moorish inuences.
Spanish tiles are sought after the world over,
including this moorish patterned design shown
above - found in one of the historic Valencian plazas.
The contemporary version of the the Tribunal de las
Aguas of Valencia meets every Thursday to settle
disputes and water issues at the Plaza de la Virgen.
California and Valencia are remarkably similar
looking and many of the same crops are grown in
both locations. Can you tell if this photo is from
Valencia Spain or California? *
Related Past Experience / Similar Projects
623
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
C. FIRM STAFFING AND KEY PERSONNEL Page 10
As one of the Inland Empire’s largest Landscape Architecture firms, our Clients have the advantage of working with an experienced principal and project team dedicated to your project from start to finish.
Currently the office is staffed with 17 full-time professional employees, 6 of whom are licensed landscape architects. The remainder of the office employees holds either a bachelor’s or master’s degree in Landscape Architecture, or other complimentary fields.
Project Management & Oversight
Gregg Denson will play a key role with the projects. He will participate in community outreach efforts and will contribute design solutions that reflect the needs and vision of stakeholders. His expertise will help ensure that the final design is both functional and responsive to community input.
One of our highly experienced project managers, Peter Dalman, Kay Kite, Ryan Skolny or Aaron Odland, will actively participate in community outreach, lead the design process, and oversee our design staff in preparing bid-ready documents. They will serve as the primary points of contact with city staff, ensuring clear communication and alignment with project goals. Additionally, they will provide coordination and oversight of our subconsultant team, providing seamless collaboration and project execution. The assignment of our California licensed landscape architect project managers will be based on the awarded project and scheduling.
Topographic Survey
To create accurate base sheets, we have included the preparation of a topographic survey for all the park and trailhead projects being bid on within this proposal, conducted by Madole & Associates, Inc.
This survey will locate above-ground improvements to support accurate planning and design. It is being included as an optional fee in the event the City requires these services.
Electrical Engineering & Lighting
JCA will provide electrical engineering services, including lighting design, electric design and construction documents for Homme Adams Park, University Park, Washington Center, Randall Henderson Trailhead, Freedom Park, and Ironwood Park, including lighting standards and enhancing park usability during evening hours.
Geotechnical Evaluation
Geo Tek will perform geotechnical and infiltration evaluations for 3 parks, providing critical soil and foundation assessments to support the design and construction process. (Homme Adams Park, Randall Henderson Trailhead, and Ironwood Park)
Water Feature Design
California Waters will assist with the design and preparation of construction documents for the water feature at Ironwood Park, ensuring a well-integrated and functional aquatic element.
DSA Approval for School Improvements
SVA Architects will support the project by assisting with the DSA (Division of the State Architect) approval process for planned improvements at Washington Charter, overseeing compliance with regulatory requirements.
Environmental Analysis
ECORP will conduct an environmental analysis for Homme Adams Park and Randall Henderson Trailhead, for compliance with environmental regulations and identifying potential project impacts.
Grant Writing
Avant Guarde Inc. (AGI) is avaliable for grant writing services for all projects, as needed.
With a strong team of experienced project managers and specialized subconsultants, we are confident in our ability to deliver a high-quality park design that meets the city’s vision and requirements. 624
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Relevant Project Experience
• Hamilton Park, Pomona, CA
Role: Director of Design Landscape Architect
City of Pomona | 2020
• Hillbrook Park, Signal Hill, CA
Role: Director of Design Landscape Architect
City of Signal Hill | 2023
• Cucamonga Basin #6, Upland, CA
Role: Director of Design Landscape Architect
San Bernardino Flood Control District | 2008
• North Etiwanda Preserve, Rancho Cucamonga, CA
Role: Director of Design Landscape Architect
San Bernardino County Special Districts | 2006
• Rails to Trails Route 66, Rancho Cucamonga / Rialto, CA Role: Director of Design Landscape Architect
City of RC and Rialto | 2014
• Desert Valley Conservation Area, Joshua Tree, CA
Role: Director of Design Landscape Architect
County of San Bernardino | 2011
Mr. Denson is responsible for overseeing all aspects of project design from inception to completion. His duties would include participation in client meetings, design development, and finalization of all formal design exhibits.
He has been involved with the design of some of the firm’s most challenging park, trail, and master planned projects. The talented design team he heads up works on projects focusing on sustainable design such as open space public gathering areas, retrofits of existing public facilities for resource conservation, specific plan developments for master planned communities, schools, mixed-use residential developments, trail planning, and open space preserve enhancement projects.
Gregg Denson, ASLA, PLA#4302
President/Director of Design Landscape Architect
Industry Experience
• 30 Yrs Industry Experience
• 25 Yrs with ARCHITERRA
Certifications & Licensing
• Registered Landscape
Architect California #4302
• ASLA
• CPRS
• California Native Plant
Landscape Program
Education
• B.S. Landscape Architecture;
California State Polytechnic
University, Pomona
Trail Design Open Space
Planning
Park
Design
Habitat
Restoration
Relevant Experience
C. FIRM STAFFING AND KEY PERSONNEL
625
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Mr. Dalman joined Architerra after nearly 20 years of professional experience providing landscape design and construction
management at some of the finest landscape architecture firms in Southern California, including Disney Imagineering Studios. His portfolio includes a wide variety of municipal, public agency and private development projects.
His duties include all facets of project management for a diverse portfolio of clients. He has been a project manager for public agency and commercial campus design; private and public schools and universities; public parks, streetscapes; master planned residential communities, model homes, and open space including trails and parks.
Peter Dalman, ASLA, PLA#5488
Project Manager
Industry Experience
• 25 Yrs Industry Experience
• 6 Yrs with ARCHITERRA
Certifications & Licensing
• Registered Landscape
Architect California #5488
• California Native Plant
Landscape Program
Education
• B.S. Landscape Architecture;
California State Polytechnic
University, Pomona
• Minor in Ornamental
Horticulture; California
State Polytechnic University,
Pomona
Trail Design Sportsfields
Design
Park
Design
Active and
Passive Design
Relevant Experience
Relevant Project Experience
• Hamilton Park, Pomona, CA
Role: Project Manager
City of Pomona | 2020
• Civic Center Amphitheater, Moreno Valley, CA
Role: Project Manager
City of Moreno Valley| 2023
• Sunset Park, Montclair, CA
Role: Project Manager
City of Montclair | 2022 - Present
• Dominguez Park, Redondo Beach, CA
Role: Project Manager
City of Redondo Beach | 2022 - Present
• Wildomar 20-acre Passive Park, Wildomar, CA
Role: Project Manager
City of Wildomar | 2023 - Present
• Saratoga Park, Montclair, CA
Role: Project Manager
L.D. King | 2023- Present
C. FIRM STAFFING AND KEY PERSONNEL
626
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Kay comes to ADG with over twenty-five years of practical and theoretical irrigation training as well as her experience as a senior Landscape Architect. Her practice includes site design, campus and urban planning, planting design, and project management. She specializes in water conservation, native plant palettes, and efficient irrigation designs.
Her experience includes designing projects that from small private residences, university campuses, parks of all sizes, along with commercial and industrial projects. She has worked directly with contractors and maintenance personnel both pre and post construction to provide site inspections and to assist and refine designs for longevity and practicality while maintaining the desired aesthetic.
Kay Kite, ASLA, PLA#6760, MLA, ASIC, CID, CLIA
Project Manager
Industry Experience
• 26+ Yrs Industry Experience
• 1.5 Yrs with ARCHITERRA
Certifications & Licensing
• Registered Landscape
Architect California #6760
• Certified Irrigation Designer
(CID)
• Certified Landscape
Irrigation Auditor (CLIA)
Education
• Master Landscape
Architecture (MLA)
from Cal Poly Pomona
• Certified Irrigation
Designer (CID) and a
Certified Landscape
Irrigation Auditor
(CLIA)
Trail Design Splash Pad
Design
Park
Design
Sports Court
Design
Relevant Experience
Relevant Project Experience
• Ayala Park Splash Pad, Bloomington, CA
Role: Project Manager
City of Bloomington | 2023-Present
• Ketchum-Libolt Park, Costa Mesa, CA
Role: Project Manager
City of Costa Mesa | 2023-Present
• MacKay Park Pickle Ball Courts, Lake Arrowhead, CA
Role: Project Manager
City of Lake Arrowhead | 2023-Present
• Four Elementary School “Greening” Projects, Los Angeles, CA Role: Project Manager
Los Angeles Unified School District (LAUSD) | 2023-Present C. FIRM STAFFING AND KEY PERSONNEL
627
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Ryan Skolny began with ADG in 2014, and advanced quickly to his current position because of his ability to manage projects, as well as identify and implement the design and planning process. Mr. Skolny is very familiar with trail system design and preparing conceptual plans and construction documents. He brings a wealth of knowledge in landscape architecture design and senior project manager expertise.
Mr. Skolny is very familiar with preparing bid ready documents for new projects and irrigation and planting drought tolerant retrofits and park planning.
Ryan Skolny, ASLA, PLA#6551
Project Manager
Industry Experience
• 21 Yrs Industry Experience
• 11 Yrs with ARCHITERRA
Certifications & Licensing
• Registered Landscape
Architect California #6551
Education
• Master of Science
in Landscape
Architecture, Cal Poly,
Pomona.
• BA Landscape
Architecture,
AA Landscape
Architecture
Trail Design
Water
Feature
Design
Park
Design
Local Desert
Designs
Relevant Experience
Relevant Project Experience
• Grand Park Splash Pad, Ontario, CA
Role: Project Manager
Lennar | 2020 - 2023
• Atwell Open-Space and Trails, Banning, CA
Role: Project Manager
Tri Pointe| 2022 - 2024
• Edenglen Dog Park, Ontario, CA
Role: Project Manager
Brookfield Properties | 2022 - Present
• Atwell Pickleball Courts and Parks, Banning, CA
Role: Project Manager
Tri Pointe | 2022 - 2024
• East Park in Parklane, Ontario, CA
Role: Project Manager
Lennar | 2023 - 2024
• Tiera Rejada Park and Playground Improvements, Moorpark, CA
Role: Project Manager
City of Moorpark | 2020 - 2023
C. FIRM STAFFING AND KEY PERSONNEL
628
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Mr. Odland has over 18 years of professional experience providing landscape design and construction management at national and state award winning landscape architecture firms in Southern California and Central Texas. His portfolio includes a wide variety of municipal, public agency and private development projects.
At Architerra, Mr. Odland’s duties include all facets of project management for a diverse portfolio of clients. In his career, he has been a project manager for public agency and commercial campus design; private and public schools and universities; public parks, streetscapes; master planned residential communities, model homes, and multi-family housing.
Aaron Odland, SITES AP Certified, PLA#7049
Project Manager
Industry Experience
• 18+ Yrs Industry Experience
• 1 Yr with ARCHITERRA
Certifications & Licensing
• Registered Landscape
Architect California #7049
• Registered Landscape
Architect Texas
Education
• Master of Landscape
Architecture, UC
Berkeley
• SITES AP Certified
Trail Design
Water
Feature
Design
Park
Design
Native Plant
Design
Relevant Experience
Relevant Project Experience
• MacArthur Park, Montclair, CA
Role: Project Manager
LD King, Civil Engineering | 2024 - Present
• Panorama Promenade Slope Trail, Signal Hill, CA
Role: Project Manager
City of Signal Hill | 2024 - Present
• Griffith Paseo Park, Round Rock, TX
Role: Project Manager
McKinney York Architects | 2023 - Present
• Plum Creek Cultural Trail, Kyle, TX
Role: Project Manager
Momark Developers | 2022 - Present
• Midtown Houston Park, Houston, TX
Role: Project Manager
Midtown District | 2022 - 2023
• La Verde Park and Splash Pad, Kyle, TX
Role: Project Manager
Momark Developers | 2022 - 2023
C. FIRM STAFFING AND KEY PERSONNEL
629
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Laura has been with ADG for 3 years, and has experience training new designers in drafting and design projects. Her practice includes planting design and water conservation, irrigation redlines and concepts and conceptual design.
Laura is from Peru, living there until college, and is a native Spanish speaker capable of being an interpretor for community outreach efforts and meetings.
Laura Vasquez, Spanish Interpretor
Landscape Designer
Industry Experience
• 5 Yrs Industry Experience
• 3 Yrs with ARCHITERRA
Education
• Master of Landscape
Architecture, UC
Berkeley
Trail Design Planting
Design IrrigationDesign
Native Plant
Design
Relevant Experience
Relevant Project Experience
• Atwell Open-Space and Trails, Banning, CA
Role: Landscape Designer
Tri Pointe| 2022 - 2024
• Wildomar 20-acre Passive Park, Wildomar, CA
Role: Landscape Designer
City of Wildomar | 2023 - Present
• Hillbrook Park, Signal Hill, CA
Role: Landscape Designer
City of Signal Hill | 2023
• Duarte City Hall, Duarte, CA
Role: Landscape Designer
City of Duarte | 2020
• Atwell Pickleball Courts and Parks, Banning, CA
Role: Landscape Designer
Tri Pointe | 2022 - 2024
C. FIRM STAFFING AND KEY PERSONNEL
630
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
ASSIGNED FOR PROJECT
IN-HOUSE PERSONNEL
SUBCONSULTANT
COLOR CODE LEGEND
TEAM ORGANIZATIONAL CHART
Team Organization
ADG Principals
Andrew Krumwiede, Gregg Denson
Consultant Firm
ARCHITERRA DESIGN GROUP
Administration Manager
Kiley Sandoval
Marketing Coordinator/ Graphic Designer
Clara Boline, MBA
Project Managers
Ryan Skolny - PLA #6551
Peter Dalman - PLA #5488
Kay Kite - PLA #6760, CID, CLIA
Aaron Odland - PLA #7049
Landscape Designers
Jennifer Lioy
Municipal Plan Check Coordinator
Michael Moreno
Jesus Fernandez
Juan Garcia
Daniel Jacobs
Raphael Tumbokon
Laura Vasquez
Michael Wagner
Valerie Alegre
Subconsultants
Madole & Associates, Inc
Civil Engineer
SVA, Inc
ARchitect
JCA Engineering
Electrical Engineering
California Waters
Water Features
ECORP
Environmental Consultants
AGI
Grant Writing
GeoTek
Geotechnical
Director of Design
Gregg Denson PLA #4302
631
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
GEOTECHNICAL
ELECTRICAL ENGINEERING
WATER FEATURES
Madole & Associates, Inc.
Mark Bertone
Principal
909-481-6322
[email protected]
GeoTek
Anna Scott
Project Geologist
951-710-1160
[email protected]
JCA Egineering Inc.
James Corns
Principal
909-864-0223
[email protected]
California Waters
Mark Pitman
President
949-528-0900x101
mpitman@
CaliforniaWaters.com
Subcontractors
CIVIL ENGINEERING
Madole Communities Group has provided engineering services throughout the Inland Empire for over thirty years, with their office located in Rancho Cucamonga.
Madole’s professionals plan and engineer communities where families live, play, learn, shop, and work. Their families are raised in the communities they develop, and they are personally vested in contributing to a higher quality of life, with economic and environmental sustainability. Madole’s vision of communities incorporates homes, parks, nature preserves, and schools, integrated with commercial development and effective transportation networks.
GEOTEK is a full service consulting firm specializing in geotechnical, construction materials testing and inspection services and environmental services since it was incorporated in 1997. Their services are provided by a diverse team of professional who are passionate about their careers and who carry a specialized knowledge of their profession. We approach every project with a team concept in mind, and our reputation for high quality and timely service at competitive rates has established us as an industry leader.
JCA Engineering is dedicated to providing efficient innovative architectural lighting design services, and state-of-the-art electrical engineering. JCA is a Certified Small Business Enterprise. Projects successfully completed within the last year represent total construction values exceeding thirty million dollars.
Those projects encompassed active and passive recreational sites, sports complexes, arenas, new and renovated educational facilities, efficient public works facilities, religious facilities, and streetscapes for community revitalization.
Since 1999, California Waters has been California’s leader in serving owners, developers, architects, engineers, general contractors, property managers, and public entities of high-end commercial and municipal recreational water features. We are uniquely qualified to provide services for the complete life cycle of a water feature, from the very first stage of germination all the way to a second-generation renovation.
Projects Collaboration with ADG
• Etiwanda Preserve Trail
Client: SB County Special District
• Nell Soto Park
Client: City of Pomona
Similar Project Experience
• Lakeland Village Community Center
Client: Riverside County
• Moreno Valley Amphitheater
Client: City of Moreno Valley
Projects Collaboration with ADG
• Moreno Valley Amphitheater
Client: City of Moreno Valley
• Phil and Nell Soto Park
Client: City of Pomona
Experience
• Enchanted Hills Splash Pad
Client: City of Perris
• Eagle Soar Splash Pad
Client: City of Temecula
Project Involvement:
All 7 Parks Listed Within Proposal
Project Involvement:
All 7 Parks Listed Within Proposal
Project Involvement:
Hommes Adams Park and
Trailhead, Ironwood Park
Project Involvement:
Ironwood Park
632
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
ENVIRONMENTAL
SVA Architects
Judy Cheng
Principal
949-809-3380
[email protected]
ECORP Consulting, Inc.
Scott Taylor
Senior Biological Program
Manager
909-307-0046
staylor@
ecorpconsulting.com
Avant Garde, Inc. (AGI)
Megan LeNoue
Manager
909-816-5126
[email protected]
Subcontractors
ARCHITECT
Since its founding in 2003, SVA Architects, Inc. has offered architectural planning and design services to civic and municipal clients across California and the western United States. SVA consistently provides an array of comprehensive architectural and master planning services, ranging from commercial, office and residential to hospitality, educational and numerous urban mixeduse designs. Throughout this time, SVA has been able to receive both new and repeat work commissions based on our reputation, client satisfaction, educational experience, design excellence, technical expertise, sustainable design approach, teamwork, and our overall commitment to our clients.
Established in 1987, ECORP Consulting, Inc. (ECORP) is a California “S” Corporation that specializes in assisting government agencies and private clients with a wide range of environmental services. ECORP brings an experienced team of more than 120 CEQA and NEPA specialists, terrestrial and aquatic biologists, wetlands specialists, paleontologists, archaeologists/cultural resource specialists, air quality/greenhouse gas specialists, noise analysis specialists, geographic information systems (GIS) specialists, and unmanned aerial systems (UAS) pilots.
Projects Collaboration with ADG
• Moreno Valley Amphitheater Restroom
Client: City of Moreno Valley
• Jurupa City Hall
Client: City of Jurupa
Experience in Palm Desert
• On-Call Environmental Services
Client: Coachella Valley Water District
• CV Link Multimodal Transportation Project
Client: Coachella Valley Association of Governments
Hillbrook Park, Signal Hill Grand Park, Ontario Riverbend Park, Jurupa Valley Project Involvement:
Washington Charter Park
GRANT WRITING
Avant-Garde specializes in government funding and grant sources with requirements ranging from basic applications and documentation to competitive project submittals. Our team has been instrumental in securing and managing millions of dollars for southern California projects. Services include program management, grands and funding administration, labor compliance, and community outreach.
Project Involvement:
Hommes Adams Park and
Trailhead, Randall Henderson
Trailhead
Project Involvement:
Available For All Projects, As Needed
633
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Homme Adams Park, Project No. CPK00005
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
PROJECT OVERVIEW:
ADG will provide professional services for the Trailhead and Park Revitalization at Homme Adams Park (and Trailhead) Project in the City of Palm Desert. Currently there are a number of amenities existing at the trailhead, including monument signage, two rail fencing, trash enclosures, educational signage, a small shade structure with seating, and a drinking fountain. Which while all functional are dated and the City wishes to update the amenities at the park and include a new disc gold course, to do this ADG anticipates:
• Additional parking to be implemented on site
• New amenities such as a pre-fabricated restroom, shade structure seating area and amenities identified during community engagement
• Disc Golf Course Design with tee boxes and disc baskets (total number of holes to be determined)
• New landscape around key areas like the parking areas and trailhead This retrofit will align with established park standards while promoting both functionality and visual appeal.
PROJECT APPROACH:
ADG, having already visited the site, has a solid understanding of the existing conditions and is prepared to meet with the City immediately upon selection.
ADG will engage with the City to discuss the proposed scope of work, initial budgets, project details, and an updated timeline based on realistic expectations and starting points. Following this meeting, ADG will conduct a comprehensive site analysis of the park site and surrounding conditions at Homme Adams Park.
The findings from this site analysis will help identify existing challenges and potential opportunities. These insights will be integrated into the public engagement plans using the TIERS methodology, ensuring a well-informed and community-driven approach.
ADG will facilitate three community engagement meetings as part of Task I: Public Engagement Phase. This will begin with an initial meeting with City and Parks and Recreation Staff to establish the approach for public engagement. Following this, ADG will conduct initial stakeholder and secondary stakeholder meetings, as well as broader community outreach efforts.
Simultaneously, Task II: Preliminary Planning and Conceptual Design Phase will progress in parallel to ensure that all necessary materials are prepared for these meetings.
After gathering community input, ADG will compile and analyze the feedback to develop a comprehensive report for the City Council. This report, which will include an overview of requested amenities and recommendations for any further input if needed, will be submitted no later than three months from the contract start date.
If no further input is required, ADG will proceed to Task III: Construction Document Phase.
This phase will include the development of:
634
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Homme Adams Park, Project No. CPK00005
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
• Demolition plans
• Construction plans
• Construction detailing
• Irrigation Plans
• Irrigation Detailing
• Irrigation Calculations
• Planting Plans
• Planting Detailing
• Cost estimating
• Lighting Plans (JCA)
• Grading Plans (Madole)
• Book Specifications
• Management Plan
Additionally, ADG will provide bidding and construction support as requested in the RFP from the City of Palm Desert, providing assistance during the construction of Homme Adams Park.
JCA, our Electrical Engineering consultant, will provide Electrical Engineering, Electrical Construction Documents, and Electrical Document support if new lighting is required by the City. Construction Observation is not included.
Madole, our Civil Engineering consultant, will provide an optional topographic survey if one is not available from the City, and a grading and drainage plan based off the approved design direction. Construction Observation is not included.
Geotek, our Geotechnical Engineering consultant, will provide the geotechnical analysis for the soils on site to provide accurate information for other engineering consultants and amenities manufacturers to use for site specific design standards their designs will need to account for.
Ecorp, our Environmental Planning consultant, shall provide all the required environmental and permitting studies that are required for the implementation of the proposed design features.
PROJECT ASSUMPTIONS:
• The Scope for Homme Adams Park as defined in the RFP shall be focused on the additional parking, a new shade structure, a dry well pre-fabrication restroom, additional park furnishing, a disc-golf course, and the possibility of some additional landscape. If the scope expands beyond this after Task I and Task II, ADG and its consultants reserve the right to adjust fees accordingly. • The City has indicated the possibility of providing topographic surveys but has requested an optional survey fee from our consultants for convenience. • If new lighting fixtures need to be added to the exiting lighting system, JCA has provided a separate fee for the City to consider.
• Structural engineering for various amenities are not included in this fee. It is anticipated the manufacturers will provide these, however if that is not the case or the scope expands during public engagement and amenities requiring engineering are to be implemented ADG will reach out to a structural engineer for an additional fee.
• Irrigation and Planting plans are included as requested in the RFP, however due to the natural state of the project site ADG anticipates the planting design, if any, will 635
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Homme Adams Park, Project No. CPK00005
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
lean towards the limited use of native and drought tolerant adapted plants, with a point-to-point irrigation system.
• During our site visit an on-site drinking fountain was discovered so it is assumed potable water is available on site.
• Per the Q & A electric and sewer connections are not anticipated to be available on site. The restroom is assumed to be a dry well and lighting will be solar powered. • A management plan has been requested in the RFP and a fee for this scope has been provided.
• 3D renderings for the site are not included in this proposal. If in the event they are required ADG can provide a fee for such services.
• The Restroom is assumed to be pre-fabricated and if in the event a custom restroom is desired ADG will request SVA, our subconsultant architect, to provide an additional fee.
Our Scope of Services are further detailed below and are listed in order of anticipated completion.
SCOPE OF SERVICES
ADG has reviewed the scope of service requirements identified in the RFP. Based on these requirements, ADG, and its team of consultants, agree to provide the following services for the park site as indicated below. All designs will be prepared in accordance with ADA guidelines. Subconsultant proposals are included in our separate fee envelope to provide further detail.
TASK I. Public Engagement
1. Project Kick Off Meeting (one in-person). This will be the time where ADG will collect preliminary information for the Public Engagement Plan in order to set the goals and objectives for the first, and subsequent public engagement meetings.
2. Site Field Visit to record existing conditions of project area and analyze opportunities and constraints. Soil Samples will be taken at this time for potential use in case project scope expands to include new landscaping.
3. Site Visit report to document the findings of the site field visit.
4. Timeline and Schedule creation following the project kick off meeting outlining each phase of the project for City approval.
5. Public Engagement Plan based off the TIERS Public Engagement Framework for City approval.
6. Presentation material creation for the three engagement meetings to accurately convey design ideas and get feedback.
7. Initial Public Engagement meeting with the City and Stakeholders to define the design direction for the conceptual design moving into the secondary public engagement meeting.
636
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Homme Adams Park, Project No. CPK00005
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
8. Secondary Public Engagement Meeting, where ADG shall present multiple design alternatives (two anticipated). ADG will collect feedback for both the designs to make design revisions and finalize the preferred design (one anticipated) with the feedback received.
9. Final Public Engagement meeting, where feedback from the City and Stakeholders, as approved by the City during the previous meeting, will be incorporated into the final design and presented during this meeting. Any final feedback will be incorporated after this meeting to provide a final concept for the City. At this time community engagement regarding a new name for the park (if applicable) will be decided per City of Palm Desert Resolution No. 2015-33.
10. Following the completion of each of the engagement meetings, a Public Engagement Report will be drafted reporting on each of the meetings findings. It is anticipated that three months after the contract start date this report will be finalized and completed for City review.
11. Monthly in-person meetings will be attended for an anticipated six months (six meetings). This will cover the conceptual design through construction documents. Monthly meetings in the construction phase are not anticipated.
12. Pre-Bid meeting prior to sending the plans out to bid. (one in-person meeting anticipated)
13. Pre-construction meeting prior to sending the plans out to bid. (one in-person meeting anticipated)
14. Project Administration/Telephone Coordination.
15. Consultant Coordination - Proactively initiate communications efforts between the design team to address key issues timely.
TASK II. Preliminary Planning and Conceptual Design
1. Optional Civil Engineering Topographic Survey should the City need it by Madole and Associates. This is to establish topography and existing utilities, and to assist in the preparation of accurate base sheets.
2. Overall Base Sheet Preparation one at 1”=80’ at 24” x 36” Format.
3. Enlargement Base Sheet preparation, two at 1”=20’ at 24” x 36” Format. One Enlargement for the southernmost parking lots, and another for the trailhead recreation area to the north.
4. Initial conceptual design following the first public engagement meeting, two designs anticipated. Each design will include an overall park plan and two conceptual enlargement plans.
5. Design revisions to conceptual design following presentation of the initial two designs during the Second Public Engagement meeting. The revision will be to the one preferred alternative to present during the final engagement meeting.
637
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Homme Adams Park, Project No. CPK00005
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
6. Final design revisions following the third public engagement meeting for providing a finalized concept for City approval.
7. Materials Board showing proposed amenities, materials, and design features.
8. Project research, utility review, and coordination with consultants as applicable.
9. Preliminary Cost Estimate for City review and input.
10. Project timeline adjustments following concept approval for City approval.
TASK III. Construction Documents
1. Title sheet preparation utilizing City of Palm Desert Title Block. (24”x36” sheet format, one sheet total)
2. Construction Document Base Sheet Preparation at 1” = 30’ scale. (24”x36” sheet format, three sheets total)
3. Demolition Plan prepared by ADG indicating all removals and items to remain. (three sheets total)
4. Fine grading plan coordination with Madole.
5. Construction Plan Preparation for layout and detailing of the proposed improvements.
6. Construction Detail Preparation for all proposed amenities.
7. Landscape Irrigation plans. Plans shall include irrigation components, architectural components, layout, and features. The plans shall be at a horizontal scale of 1” = 30’. Prepare documentation necessary to comply with the City’s Water Efficient Landscape Ordinance. Design irrigation water services from domestic mains. We will check existing services condition and provide recommendations or new connections to supply required irrigation
8. Prepare Water Efficiency Landscape Worksheet. *
9. Prepare 2 Irrigation Controller Charts. *
10. Landscape Planting plans. Plans shall include landscaping, plants and materials, architectural components, layout, and features. The plans shall be at a horizontal scale of 1” = 30’. Prepare documentation necessary to comply with the City’s Water Efficient Landscape Ordinance.
11. Irrigation and Planting Detail Preparation per City Standards.
12. Prepare Planting/Irrigation Hydro-zone Plan. *
13. Provide Soils Test and Soils Management Report. *
14. Prepare Annual Irrigation and Planting Maintenance Schedule. *
15. Prepare Construction, Irrigation, and Planting Specifications in book format at
8.5” x 11”.
16. Final cost estimate of all improvements specified on the construction plans. 638
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Homme Adams Park, Project No. CPK00005
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
17. Material furnishing selection.
18. Management Plan for the proposed built amenities and site improvements.
19. Package Coordination.
20. Plan Checking and Plan Check Corrections.
21. Project Administration and Telephone Consultation.
22. WQMP Plans by Madole.
23. Civil grading and drainage design plans by Madole. Plans will include all applicable grading requirements for a new playground and ADA compliance improvements.
24. Optional Electrical Engineering Plans Provided by JCA for new site lighting if desired from the community input meetings.
25. Geotechnical Engineering by Geotek.
26. Environmental Studies by E-Corp.
TASK IV. Bidding and Construction Support:
1. Respond to RFI’s during projects advertisement period.
2. Prepare project addenda for the City. (two anticipated)
3. Attend construction observation meetings during construction. (three anticipated)
4. Preparation of site review reports for submittal to City staff for review, and contractor for correction. (three reports total)
5. Review and provide response to contractor's requests for information (RFI) about the plans and specifications forwarded to the Consultant by the City.
6. Submittal review.
7. Review and approve shop drawings, as needed.
* Items required for AB 1881 California Water Efficient Landscape Ordinance. 639
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
University Park, Project No. CPK00006
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
PROJECT OVERVIEW:
ADG will provide professional services for the University Park Playground Retrofit Project in the City of Palm Desert. The existing playground equipment has experienced significant weathering due to prolonged exposure to high temperatures. To address this, an upgrade is recommended to:
• Restore the aesthetic appeal of the play area
• Provide consistency with the park’s other amenities
• Preserve the original recreational value
This retrofit will align with established park standards while promoting both functionality and visual appeal.
PROJECT APPROACH:
ADG, having already visited the site, has a solid understanding of the existing conditions and is prepared to meet with the City immediately upon selection.
ADG will engage with the City to discuss the proposed scope of work, initial budgets, project details, and an updated timeline based on realistic expectations and starting points. Following this meeting, ADG will conduct a comprehensive site analysis of the existing play equipment and surrounding conditions at University Park.
The findings from this site analysis will help identify existing challenges and potential opportunities. These insights will be integrated into the public engagement plans using the TIERS methodology, ensuring a well-informed and community-driven approach.
ADG will facilitate three community engagement meetings as part of Task I: Public Engagement Phase. This will begin with an initial meeting with City and Parks and Recreation Staff to establish the approach for public engagement. Following this, ADG will conduct initial stakeholder and secondary stakeholder meetings, as well as broader community outreach efforts.
Simultaneously, Task II: Preliminary Planning and Conceptual Design Phase will progress in parallel to ensure that all necessary materials are prepared for these meetings.
After gathering community input, ADG will compile and analyze the feedback to develop a comprehensive report for the City Council. This report, which will include an overview of requested amenities and recommendations for any further input if needed, will be submitted no later than three months from the contract start date.
If no further input is required, ADG will proceed to Task III: Construction Document Phase.
This phase will include the development of:
• Demolition plans
• Construction plans
• Construction detailing and
specifications
• Cost estimating
• Lighting Plan (JCA)
• Grading Plan (Madole)
640
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
University Park, Project No. CPK00006
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
Additionally, ADG will provide bidding and construction support as requested in the RFP from the City of Palm Desert, providing assistance during the construction of University Park.
JCA, our Electrical Engineering consultant, will provide Electrical Engineering, Electrical Construction Documents, and Electrical Document support if new lighting is required by the City.
Madole, our Civil Engineering consultant, will provide an optional topographic survey if one is not available from the City, and a grading and drainage plan based off the approved design direction.
PROJECT ASSUMPTIONS:
• The University Park Scope, as defined in the RFP, is limited to the playground area, including the installation of new play equipment and surfacing. If the scope expands beyond this after Task I and Task II, ADG and its consultants reserve the right to adjust fees accordingly. It is assumed that the existing shade structure over the playground will remain in place.
• The City has indicated the possibility of providing topographic surveys but has requested an optional survey fee from our consultants for convenience. • If new lighting fixtures need to be added to the exiting lighting system, JCA has provided a separate fee for the City to consider.
• Per the RFP and Q and A, the playground scope will not extend beyond the original play area footprint, and adjustments to adjacent hardscape are not anticipated.
• Structural engineering for various amenities are not included in this fee. It is anticipated the prefabricated elements/structures will be a deferred submittal.
The City’s selected contractor will be responsible for providing these. However if that is not the case or the scope expands during public engagement and amenities requiring engineering are to be implemented, ADG will reach out to a structural engineer for an additional fee.
• 3D renderings of the play equipment are also anticipated to be provided by the manufacturer. If unavailable, ADG can coordinate with 3DIkon to obtain a quote for rendering services.
Our Scope of Services are further detailed below and are listed in order of anticipated completion.
SCOPE OF SERVICES
ADG has reviewed the scope of service requirements identified in the RFP. Based on these requirements, ADG, and its team of consultants, agree to provide the following services for the park site as indicated below. All designs will be prepared in accordance with ADA guidelines. Subconsultant proposals are included in our separate fee envelope to provide further details.
641
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
University Park, Project No. CPK00006
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
TASK I. Public Engagement
1. Project Kick Off Meeting (one in-person). This will be the time where ADG will collect preliminary information for the Public Engagement Plan in order to set the goals and objectives for the first, and subsequent public engagement meetings.
2. Site Field Visit to record existing conditions of project area and analyze opportunities and constraints. Soil Samples will be taken at this time for potential use in case the project scope expands to include new landscaping.
3. Site Visit report to document the findings of the site field visit.
4. Timeline and Schedule creation following the project kick off meeting outlining each phase of the project for City approval.
5. Public Engagement Plan based off the Tiers Public Engagement Framework for City approval.
6. Presentation material creation for the three engagement meetings to accurately convey design ideas and get feedback.
7. Initial Public Engagement meeting with the City and Stakeholders to define the design direction for the conceptual design moving into the secondary public engagement meeting.
8. Secondary Public Engagement Meeting, where ADG shall present multiple design alternatives (two anticipated). ADG will collect feedback for both the designs to make design revisions and finalize the preferred design (one anticipated) with the feedback received.
9. Final Public Engagement meeting, where feedback from the City and Stakeholders, as approved by the City during the previous meeting, will be incorporated into the final design and presented during this meeting. Any final feedback will be incorporated after this meeting to provide a final concept for the City. At this time community engagement regarding a new name for the park (if applicable) will be decided per City of Palm Desert Resolution No. 2015-33.
10. Following the completion of each of the engagement meetings, a Public Engagement Report will be drafted reporting on each of the meeting’s findings. It is anticipated that three months after the contract start date this report will be finalized and completed for City review.
11. Monthly in-person meetings will be attended for an anticipated six months (six meetings). This will cover the conceptual design through construction documents. Monthly meetings in the construction phase are not anticipated.
12. Pre-Bid meeting prior to sending the plans out to bid. (one in-person meeting anticipated)
13. Pre-construction meeting prior to sending the plans out to bid. (one in-person meeting anticipated)
14. Project Administration/Telephone Coordination.
642
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
University Park, Project No. CPK00006
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
15. Consultant Coordination - Proactively initiate communications efforts between the design team to address key issues timely.
TASK II. Preliminary Planning and Conceptual Design
1. Optional Civil Engineering Topographic Survey should the City need it by Madole and Associates. This is to establish topography and existing utilities, and to assist in the preparation of accurate base sheets.
2. Base Sheet Preparation at 1”=10’-0” at 24” x 36” Format.
3. Initial conceptual design following the first public engagement meeting. (two designs anticipated)
4. Design revisions to conceptual design following presentation of the initial two designs during the Second Public Engagement meeting. The revision will be to the one preferred alternative to present during the final engagement meeting.
5. Final design revisions following the third public engagement meeting to provide a finalized concept for City approval.
6. Project research, utility review, and coordination with consultants as applicable.
7. Preliminary Cost Estimate for City review and input.
8. Project timeline adjustments following concept approval for City approval.
TASK III. Construction Documents
1. Title sheet preparation utilizing City of Palm Desert Title Block. (24”x36” sheet format, one sheet total)
2. Construction Document Base Sheet Preparation at 1” =10’ scale. (24”x36” sheet format, one sheet total)
3. Demolition Plan prepared by ADG indicating all removals and items to remain.
4. Fine grading plan coordination with Madole.
5. Construction Plan Preparation for layout and detailing of the new playground design.
6. Construction Detail Preparation for all proposed amenities.
7. Prepare Construction Specifications in book format at 8.5” x 11”.
8. Final cost estimate of all improvements specified in the construction plans.
9. Material furnishing selection.
10. Package Coordination.
11. Plan Checking and Plan Check Corrections.
12. Project Administration and Telephone Consultation.
643
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
University Park, Project No. CPK00006
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
13. Civil grading and drainage design plans by Madole. Plans will include all applicable grading requirements for a new playground and ADA compliance improvement.
14. Optional Electrical Engineering Plans Provided by JCA for new walkway lighting if desired from the community input meetings.
TASK IV. Bidding and Construction Support:
1. Respond to RFI’s during projects advertisement period.
2. Prepare project addenda for the City. (two anticipated)
3. Attend construction observation meetings during construction. (three anticipated)
4. Preparation of site review reports for submittal to City staff for review, and contractor for correction. (three reports total)
5. Review and provide response to contractor's requests for information (RFI) about the plans and specifications forwarded to the Consultant by the City.
6. Submittal review.
7. Review and approve shop drawings, as needed. JCA’s electric plans do not include construction observation.
644
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Washington Charter, Project No. CPK00008
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
PROJECT OVERVIEW:
ADG will provide professional services for the Washington Charter Playground Retrofit Project in the City of Palm Desert. The existing playground equipment has experienced significant weathering due to prolonged exposure to high temperatures. To address this, an upgrade is recommended to:
• Restore the aesthetic appeal of the play area
• Provide consistency with the park’s other amenities
• Preserve the original recreational value
This retrofit will align with established park standards while promoting both functionality and visual appeal.
PROJECT APPROACH:
ADG, having already visited the site, has a solid understanding of the existing conditions and is prepared to meet with the City immediately upon selection.
ADG will engage with the City to discuss the proposed scope of work, initial budgets, project details, and an updated timeline based on realistic expectations and starting points. Following this meeting, ADG will conduct a comprehensive site analysis of the existing play equipment and surrounding conditions at Washington Charter.
The findings from this site analysis will help identify existing challenges and potential opportunities. These insights will be integrated into the public engagement plans using the TIERS methodology, ensuring a well-informed and community-driven approach.
Public Engagement and Concept Development
ADG will facilitate three community engagement meetings as part of Task I: Public Engagement Phase. This will begin with an initial meeting with City and Parks and Recreation Staff to establish the approach for public engagement. Following this, ADG will conduct initial stakeholder and secondary stakeholder meetings, as well as broader community outreach efforts.
Simultaneously, Task II: Preliminary Planning and Conceptual Design Phase will progress in parallel to ensure that all necessary materials are prepared for these meetings.
After gathering community input, ADG will compile and analyze the feedback to develop a comprehensive report for the City Council. This report, which will include an overview of requested amenities and recommendations for any further input if needed, will be submitted no later than three months from the contract start date.
Final Design and Implementation
If no further input is required, ADG will proceed to Task III: Construction Document Phase.
This phase will include the development of:
• Demolition plans
• Construction plans
• Construction detailing and
specifications
• Cost estimating
645
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Washington Charter, Project No. CPK00008
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
• Lighting Plans (JCA) • Grading Plans (Madole)
Additionally, ADG will provide bidding and construction support as outlined in the RFP from the City of Palm Desert, providing oversight throughout the construction phase of Washington Charter.
JCA, our Electrical Engineering consultant, will provide Electrical Engineering, Electrical Construction Documents, and Electrical Document support if new lighting is required by the City.
Madole, our Civil Engineering consultant, will provide an optional topographic survey if one is not available from the City, and a grading and drainage plan based off the approved design direction.
SVA, our Architectural consultant, will support the project by assisting with the DSA (Division of the State Architect) approval process for the planned improvements at Washington Charter, overseeing compliance with regulatory requirements.
PROJECT ASSUMPTIONS:
• Due to the site's location on school grounds, a licensed Architect will coordinate with the DSA for park and playground improvements. SVA Architects, a member of our team, will provide this coordination if needed.
• The Washington Charter Scope, as defined in the RFP, is limited to the playground area, including the installation of new play equipment and surfacing. If the scope expands beyond this after Task I and Task II, ADG and its consultants reserve the right to adjust fees accordingly.
• The City has indicated the possibility of providing topographic surveys but has requested an optional survey fee from our consultants for convenience. • If additional lighting is required, JCA has provided a separate fee for the City to consider.
• Per the RFP and Q and A, the playground scope will not extend beyond the original play area footprint, and adjustments to adjacent hardscape are not anticipated.
• Structural engineering for playground equipment is not included in this fee, as it is expected to be provided by the playground manufacturer. • 3D renderings of the play equipment are also anticipated to be provided by the manufacturer. If unavailable, ADG can coordinate with 3DIkon to obtain a quote for rendering services.
Our Scope of Services are further detailed below and are listed in order of anticipated completion.
SCOPE OF SERVICES
ADG has reviewed the scope of service requirements identified in the RFP. Based on these requirements, ADG, and its team of consultants, agree to provide the following services for the park site as indicated below. All designs will be prepared in accordance with ADA 646
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Washington Charter, Project No. CPK00008
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
guidelines. Subconsultant proposals are included in our separate fee envelope to provide further details.
TASK I. Public Engagement
1. Project Kick Off Meeting (one in-person). This will be the time where ADG will collect preliminary information for the Public Engagement Plan in order to set the goals and objectives for the first, and subsequent public engagement meetings.
2. Site Field Visit to record existing conditions of project area and analyze opportunities and constraints. Soil Samples will be taken at this time for potential use in case the project scope expands to include new landscaping.
3. Site Visit report to document the findings of the site field visit.
4. Timeline and Schedule creation following the project kick off meeting outlining each phase of the project for City approval.
5. Public Engagement Plan based off the Tiers Public Engagement Framework for City approval.
6. Presentation material creation for the three engagement meetings to accurately convey design ideas and get feedback.
7. Initial Public Engagement meeting with the City and Stakeholders to define the design direction for the conceptual design moving into the secondary public engagement meeting.
8. Secondary Public Engagement Meeting, where ADG shall present multiple design alternatives (two anticipated). ADG will collect feedback for both the designs to make design revisions and finalize the preferred design (one anticipated) with the feedback received.
9. Final Public Engagement meeting, where feedback from the City and Stakeholders, as approved by the City during the previous meeting, will be incorporated into the final design and presented during this meeting. Any final feedback will be incorporated after this meeting to provide a final concept for the City. At this time community engagement regarding a new name for the park (if applicable) will be decided per City of Palm Desert Resolution No. 2015-33.
10. Following the completion of each of the engagement meetings, a Public Engagement Report will be drafted reporting on each of the meeting’s findings. It is anticipated that three months after the contract start date this report will be finalized and completed for City review.
11. Monthly in-person meetings will be attended for an anticipated six months (six meetings). This will cover the conceptual design through construction documents. Monthly meetings in the construction phase are not anticipated.
12. Pre-Bid meeting prior to sending the plans out to bid. (one in-person meeting anticipated)
647
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Washington Charter, Project No. CPK00008
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
13. Pre-construction meeting prior to sending the plans out to bid. (one in-person meeting anticipated)
14. Project Administration/Telephone Coordination.
15. Consultant Coordination - Proactively initiate communications efforts between the design team to address key issues timely.
TASK II. Preliminary Planning and Conceptual Design
1. Optional Civil Engineering Topographic Survey should the City need it by Madole and Associates. This is to establish topography and existing utilities, and to assist in the preparation of accurate base sheets.
2. Base Sheet Preparation at 1”=10’-0” at 24” x 36” Format.
3. Initial conceptual design following the first public engagement meeting. (two designs anticipated)
4. Design revisions to conceptual design following presentation of the initial two designs during the Second Public Engagement meeting. The revision will be to the one preferred alternative to present during the final engagement meeting.
5. Final design revisions following the third public engagement meeting to provide a finalized concept for City approval.
6. Project research, utility review, and coordination with consultants as applicable.
7. Preliminary Cost Estimate for City review and input.
8. Project timeline adjustments following concept approval for City approval.
TASK III. Public Engagement Construction Documents
1. Title sheet preparation utilizing City of Palm Desert Title Block. (24”x36” sheet format, one sheet total)
2. Construction Document Base Sheet Preparation at 1” =10’ (scale). (24”x36” sheet format, one sheet total)
3. Demolition Plan prepared by ADG indicating all removals and items to remain.
4. Fine grading plan coordination with Madole.
5. Construction Plan Preparation for layout and detailing of the new playground design.
6. Construction Detail Preparation for all proposed amenities.
7. Prepare Construction Specifications in book format at 8.5” x 11”.
8. Final cost estimate of all improvements specified in the construction plans.
9. Material furnishing selection.
10. Package Coordination.
648
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Washington Charter, Project No. CPK00008
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
11. Plan Checking and Plan Check Corrections.
12. Project Administration and Telephone Consultation.
13. Civil grading and drainage design plans by Madole. Plans will include all applicable grading requirements for a new playground and ADA compliance improvement.
14. Civil Engineering Water Quality Management Plan (WQMP) to manage quality and quantity of runoff from the site by Madole.
15. Optional Electrical Engineering Plans Provided by JCA for new walkway lighting if desired from the community input meetings.
16. Coordination with the DSA (Division of the State Architect) by SVA during the approval process for the planned improvements at Washington Charter, overseeing compliance with regulatory requirements.
TASK IV. Bidding and Construction Support:
1. Respond to RFI’s during projects advertisement period.
2. Prepare project addenda for the City. (two anticipated)
3. Attend construction observation meetings during construction. (three anticipated)
4. Preparation of site review reports for submittal to City staff for review, and contractor for correction. (three reports total)
5. Review and provide response to contractor's requests for information (RFI) about the plans and specifications forwarded to the Consultant by the City.
6. Submittal review.
7. Review and approve shop drawings, as needed. JCA’s electric plans do not include construction observation.
649
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Randall Henderson Trailhead, Project No. CPK00009
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
PROJECT OVERVIEW:
ADG will provide professional services for the Trailhead Revitalization at Randall Henderson Trailhead Project in the City of Palm Desert. Currently there are a number of amenities existing at the trailhead, including monument signage, existing parking, trash enclosures, bench seating, and trail access. Which, while all are still functional they are dated and the City wishes to update the amenities at the trailhead, to do this ADG anticipates:
• Additional parking to be implemented on site.
• New amenities such as a pre-fabricated restroom, shade structure seating area and amenities identified during community engagement.
• New landscape around key areas like the parking areas and trailhead.
This retrofit will align with established park standards while promoting both functionality and visual appeal.
PROJECT APPROACH:
ADG, having already visited the site, has a solid understanding of the existing conditions and is prepared to meet with the City immediately upon selection.
ADG will engage with the City to discuss the proposed scope of work, initial budgets, project details, and an updated timeline based on realistic expectations and starting points. Following this meeting, ADG will conduct a comprehensive site analysis of the existing play equipment and surrounding conditions at Randall Henderson Trailhead.
The findings from this site analysis will help identify existing challenges and potential opportunities. These insights will be integrated into the public engagement plans using the TIERS methodology, ensuring a well-informed and community-driven approach.
ADG will facilitate three community engagement meetings as part of Task I: Public Engagement Phase. This will begin with an initial meeting with City and Parks and Recreation Staff to establish the approach for public engagement. Following this, ADG will conduct initial stakeholder and secondary stakeholder meetings, as well as broader community outreach efforts.
Simultaneously, Task II: Preliminary Planning and Conceptual Design Phase will progress in parallel to ensure that all necessary materials are prepared for these meetings.
After gathering community input, ADG will compile and analyze the feedback to develop a comprehensive report for the City Council. This report, which will include an overview of requested amenities and recommendations for any further input if needed, will be submitted no later than three months from the contract start date.
If no further input is required, ADG will proceed to Task III: Construction Document Phase.
This phase will include the development of:
• Demolition plans
• Construction plans
• Construction detailing
• Irrigation Plans
• Irrigation Detailing
• Irrigation Calculations
650
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Randall Henderson Trailhead, Project No. CPK00009
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
• Planting Plans
• Planting Detailing
• Cost estimating
• Lighting Plans (JCA)
• Grading Plans (Madole)
• Book Specifications
• Management Plan
Additionally, ADG will provide bidding and construction support as requested in the RFP from the City of Palm Desert, providing assistance during the construction of Freedom Park.
JCA, our Electrical Engineering consultant, will provide Electrical Engineering, Electrical Construction Documents, and Electrical Document support if new lighting is required by the City. Construction Observation is not included.
Madole, our Civil Engineering consultant, will provide an optional topographic survey if one is not available from the City, and a grading and drainage plan based off the approved design direction. Construction Observation is not included.
Geotek, our Geotechnical Engineering consultant, will provide the geotechnical analysis for the soils on site to provide accurate information for other engineering consultants and amenities manufacturers to use for site specific design standards their designs will need to account for.
Ecorp, our Environmental Planning consultant, shall provide all the required environmental and permitting studies that are required for the implementation of the proposed design features.
PROJECT ASSUMPTIONS:
• The Scope for Randall Henderson Trailhead as defined in the RFP shall be focused on the additional parking, a new shade structure, a restroom which may or may not be a dry well pre-fabrication, additional park furnishing, and the possibility of some additional landscape. If the scope expands beyond this after Task I and Task II, ADG and its consultants reserve the right to adjust fees accordingly. • The City has indicated the possibility of providing topographic surveys but has requested an optional survey fee from our consultants for convenience. • If additional lighting is required, JCA has provided a separate fee for the City to consider.
• Structural engineering for various amenities are not included in this fee. It is anticipated the prefabricated elements/structures will be a deferred submittal.
The City’s selected contractor will be responsible for providing these. However if that is not the case or the scope expands during public engagement and amenities requiring engineering are to be implemented, ADG will reach out to a structural engineer for an additional fee.
• Irrigation and Planting plans are included as requested in the RFP, however due to the natural state of the project site ADG anticipates the planting design, if any, will lean towards the limited use of native and drought tolerant adapted plants, with a point-to-point irrigation system.
651
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Randall Henderson Trailhead, Project No. CPK00009
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
• The Q & A stated that dry and wet utilities are available on site. However, the location of the utilities is unknown. We therefore have assumed the restroom to be a prefabricated dry-vault type. If the public engagement phase determines that the pre-fabricated restroom building, requires full sewer and water connections, then we can reach out to our subconsultant Madole & Associated to provide a fee. • A management plan has been requested in the RFP and a fee for this scope has been provided.
• 3D renderings for the site are not included in this proposal. If in the event they are required ADG can reach out to our sub consultant 3DIkon to provide a fee for such services.
• The Restroom is assumed to be pre-fabricated and if in the event a custom restroom is desired ADG will request SVA to provide an additional fee.
Our Scope of Services are further detailed below and are listed in order of anticipated completion.
SCOPE OF SERVICES
ADG has reviewed the scope of service requirements identified in the RFP. Based on these requirements, ADG, and its team of consultants, agree to provide the following services for the park site as indicated below. All designs will be prepared in accordance with ADA guidelines. Subconsultant proposals are included in our separate fee envelope to provide further detail.
TASK I. Public Engagement
1. Project Kick Off Meeting (one in-person). This will be the time where ADG will collect preliminary information for the Public Engagement Plan in order to set the goals and objectives for the first, and subsequent public engagement meetings.
2. Site Field Visit to record existing conditions of project area and analyze opportunities and constraints. Soil Samples will be taken at this time for potential use in case project scope expands to include new landscaping.
3. Site Visit report to document the findings of the site field visit.
4. Timeline and Schedule creation following the project kick off meeting outlining each phase of the project for City approval.
5. Public Engagement Plan based off the TIERS Public Engagement Framework for City approval.
6. Presentation material creation for the three engagement meetings to accurately convey design ideas and get feedback.
7. Initial Public Engagement meeting with the City and Stakeholders to define the design direction for the conceptual design moving into the secondary public engagement meeting.
8. Secondary Public Engagement Meeting, where ADG shall present multiple design alternatives (two anticipated). ADG will collect feedback for both the 652
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Randall Henderson Trailhead, Project No. CPK00009
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
designs to make design revisions and finalize the preferred design (one anticipated) with the feedback received.
9. Final Public Engagement meeting, where feedback from the City and Stakeholders, as approved by the City during the previous meeting, will be incorporated into the final design and presented during this meeting. Any final feedback will be incorporated after this meeting to provide a final concept for the City. At this time community engagement regarding a new name for the park (if applicable) will be decided per City of Palm Desert Resolution No. 2015-33.
10. Following the completion of each of the engagement meetings, a Public Engagement Report will be drafted reporting on each of the meetings findings. It is anticipated that three months after the contract start date this report will be finalized and completed for City review.
11. Monthly in-person meetings will be attended for an anticipated six months (six meetings). This will cover the conceptual design through construction documents. Monthly meetings in the construction phase are not anticipated.
12. Pre-Bid meeting prior to sending the plans out to bid. (one in-person meeting anticipated)
13. Pre-construction meeting prior to sending the plans out to bid. (one in-person meeting anticipated)
14. Project Administration/Telephone Coordination.
15. Consultant Coordination - Proactively initiate communications efforts between the design team to address key issues timely.
TASK II. Preliminary Planning and Conceptual Design
1. Optional Civil Engineering Topographic Survey should the City need it by Madole and Associates. This is to establish topography and existing utilities, and to assist in the preparation of accurate base sheets.
2. Overall Base Sheet Preparation one at 1”=60’ at 24” x 36” Format.
3. Enlargement Base Sheet preparation, one at 1”=30’ at 24” x 36” format. One Enlargement for the southern most parking lots, and another for the trailhead recreation area to the north.
4. Initial conceptual design following the first public engagement meeting, two designs anticipated. Each design will include an overall trailhead plan and one conceptual enlargement plan.
5. Design revisions to conceptual design following presentation of the initial two designs during the Second Public Engagement meeting. The revision will be to the one preferred alternative to present during the final engagement meeting.
6. Final design revisions following the third public engagement meeting to provide a finalized concept for City approval.
653
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Randall Henderson Trailhead, Project No. CPK00009
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
7. Materials Board showing proposed amenities, materials, and design features.
8. Project research, utility review, and coordination with consultants as applicable.
9. Preliminary Cost Estimate for City review and input.
10. Project timeline adjustments following concept approval for City approval.
TASK III. Construction Documents
1. Title sheet preparation utilizing City of Palm Desert Title Block. (24”x36” sheet format, one sheet total)
2. Construction Document Base Sheet Preparation at 1” =60’ scale. (24”x36” sheet format, one sheet total) and one sheet at 1”=30’ scale. (24”x36” sheet format, two sheets total)
3. Demolition Plan prepared by ADG indicating all removals and items to remain. (three sheets total)
4. Fine grading plan coordination with Madole.
5. Construction Plan Preparation for layout and detailing of the proposed improvements. The Overall 60-scale plan will show trail connections and the larger area outside the parking area and trailhead for anticipated improvements in the interior of the trail. The 30-scale enlargement will show the anticipated improvements directly adjacent to the trail head and improved parking.
6. Construction Detail Preparation for all proposed amenities.
7. Landscape Irrigation plans. Plans shall include irrigation components, architectural components, layout, and features. The plans shall be at a horizontal scale of 1” = 30’. Prepare documentation necessary to comply with the City’s Water Efficient Landscape Ordinance. Design irrigation water services from domestic mains. We will check existing services condition and provide recommendations or new connections to supply required irrigation
8. Prepare Water Efficiency Landscape Worksheet. *
9. Prepare 2 Irrigation Controller Charts. *
10. Landscape Planting plans. Plans shall include landscaping, plants and materials, architectural components, layout, and features. The plans shall be at a horizontal scale of 1” = 30’. Prepare documentation necessary to comply with the City’s Water Efficient Landscape Ordinance.
11. Irrigation and Planting Detail Preparation per City Standards.
12. Prepare Planting/Irrigation Hydro-zone Plan. *
13. Provide Soils Test and Soils Management Report. *
14. Prepare Annual Irrigation and Planting Maintenance Schedule. *
15. Prepare Construction, Irrigation, and Planting Specifications in book format at
8.5” x 11”.
654
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Randall Henderson Trailhead, Project No. CPK00009
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
16. Final cost estimate of all improvements specified on the construction plans.
17. Material furnishing selection.
18. Management Plan for the proposed built amenities and site improvements.
19. Package Coordination.
20. Plan Checking and Plan Check Corrections.
21. Project Administration and Telephone Consultation.
22. WQMP Plans by Madole.
23. Civil grading and drainage design plans by Madole. Plans will include all applicable grading requirements for a new playground and ADA compliance improvements.
24. Optional Electrical Engineering Plans Provided by JCA for new site lighting if desired from the community input meetings.
25. Geotechnical Engineering by Geotek.
26. Environmental Studies by E-Corp.
TASK IV. Bidding and Construction Support:
1. Respond to RFI’s during projects advertisement period.
2. Prepare project addenda for the City. (two anticipated)
3. Attend construction observation meetings during construction. (three anticipated)
4. Preparation of site review reports for submittal to City staff for review, and contractor for correction. (three reports total)
5. Review and provide response to contractor's requests for information (RFI) about the plans and specifications forwarded to the Consultant by the City.
6. Submittal review.
7. Review and approve shop drawings, as needed.
* Items required for AB 1881 California Water Efficient Landscape Ordinance. 655
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Freedom Park, Project No. MPK00001
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
PROJECT OVERVIEW:
ADG will provide professional services for the Freedom Park Playground Retrofit Project in the City of Palm Desert. The existing playground equipment has experienced significant weathering due to prolonged exposure to high temperatures. To address this, an upgrade is recommended to:
• Restore the aesthetic appeal of the play area
• Provide consistency with the park’s other amenities
• Preserve the original recreational value
This retrofit will align with established park standards while promoting both functionality and visual appeal.
PROJECT APPROACH:
ADG, having already visited the site, has a solid understanding of the existing conditions and is prepared to meet with the City immediately upon selection.
ADG will engage with the City to discuss the proposed scope of work, initial budgets, project details, and an updated timeline based on realistic expectations and starting points. Following this meeting, ADG will conduct a comprehensive site analysis of the existing play equipment and surrounding conditions at Freedom Park.
The findings from this site analysis will help identify existing challenges and potential opportunities. These insights will be integrated into the public engagement plans using the TIERS methodology, ensuring a well-informed and community-driven approach.
ADG will facilitate three community engagement meetings as part of Task I: Public Engagement Phase. This will begin with an initial meeting with City and Parks and Recreation Staff to establish the approach for public engagement. Following this, ADG will conduct initial stakeholder and secondary stakeholder meetings, as well as broader community outreach efforts.
Simultaneously, Task II: Preliminary Planning and Conceptual Design Phase will progress in parallel to ensure that all necessary materials are prepared for these meetings.
After gathering community input, ADG will compile and analyze the feedback to develop a comprehensive report for the City Council. This report, which will include an overview of requested amenities and recommendations for any further input if needed, will be submitted no later than three months from the contract start date.
If no further input is required, ADG will proceed to Task III: Construction Document Phase.
This phase will include the development of:
• Demolition plans
• Construction plans
• Construction detailing and
specifications
• Cost estimating
• Lighting Plan (JCA)
• Grading Plan (Madole)
656
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Freedom Park, Project No. MPK00001
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
Additionally, ADG will provide bidding and construction support as requested in the RFP from the City of Palm Desert, providing assistance during the construction of Freedom Park.
JCA, our Electrical Engineering consultant, will provide Electrical Engineering, Electrical Construction Documents, and Electrical Document support if new lighting is required by the City.
Madole, our Civil Engineering consultant, will provide an optional topographic survey if one is not available from the City, and a grading and drainage plan based off the approved design direction.
PROJECT ASSUMPTIONS:
• The Freedom Park Scope, as defined in the RFP, is limited to the playground area, including the installation of new play equipment and surfacing. If the scope expands beyond this after Task I and Task II, ADG and its consultants reserve the right to adjust fees accordingly.
• The City has indicated the possibility of providing topographic surveys but has requested an optional survey fee from our consultants for convenience. • If new lighting fixtures need to be added to the exiting lighting system, JCA has provided a separate fee for the City to consider.
• Per the RFP and Q and A, the playground scope will not extend beyond the original play area footprint, and adjustments to adjacent hardscape are not anticipated.
• Structural engineering for various amenities are not included in this fee. It is anticipated the prefabricated elements/structures will be a deferred submittal.
The City’s selected contractor will be responsible for providing these. However if that is not the case or the scope expands during public engagement and amenities requiring engineering are to be implemented, ADG will reach out to a structural engineer for an additional fee.
• 3D renderings of the play equipment are also anticipated to be provided by the manufacturer. If unavailable, ADG can coordinate with 3DIkon to obtain a quote for rendering services.
Our Scope of Services are further detailed below and are listed in order of anticipated completion.
SCOPE OF SERVICES
ADG has reviewed the scope of service requirements identified in the RFP. Based on these requirements, ADG, and its team of consultants, agree to provide the following services for the park site as indicated below.
All designs will be prepared in accordance with ADA guidelines. Subconsultant proposals are included in our separate fee envelope to provide further details. 657
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Freedom Park, Project No. MPK00001
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
TASK I. Public Engagement
1. Project Kick Off Meeting (one in-person). This will be the time where ADG will collect preliminary information for the Public Engagement Plan in order to set the goals and objectives for the first, and subsequent public engagement meetings.
2. Site Field Visit to record existing conditions of project area and analyze opportunities and constraints. Soil Samples will be taken at this time for potential use in case the project scope expands to include new landscaping.
3. Site Visit report to document the findings of the site field visit.
4. Timeline and Schedule creation following the project kick off meeting outlining each phase of the project for City approval.
5. Public Engagement Plan based off the Tiers Public Engagement Framework for City approval.
6. Presentation material creation for the three engagement meetings to accurately convey design ideas and get feedback.
7. Initial Public Engagement meeting with the City and Stakeholders to define the design direction for the conceptual design moving into the secondary public engagement meeting.
8. Secondary Public Engagement Meeting, where ADG shall present multiple design alternatives (two anticipated). ADG will collect feedback for both the designs to make design revisions and finalize the preferred design (one anticipated) with the feedback received.
9. Final Public Engagement meeting, where feedback from the City and Stakeholders, as approved by the City during the previous meeting, will be incorporated into the final design and presented during this meeting. Any final feedback will be incorporated after this meeting to provide a final concept for the City. At this time community engagement regarding a new name for the park (if applicable) will be decided per City of Palm Desert Resolution No. 2015-
33. 10. Following the completion of each of the engagement meetings, a Public Engagement Report will be drafted reporting on each of the meetings findings.
It is anticipated that three months after the contract start date this report will be finalized and completed for City review.
11. Monthly in-person meetings will be attended for an anticipated six months (six meetings). This will cover the conceptual design through construction documents. Monthly meetings in the construction phase are not anticipated.
12. Pre-Bid meeting prior to sending the plans out to bid. (one in-person meeting anticipated)
13. Pre-construction meeting prior to sending the plans out to bid. (one in-person meeting anticipated)
14. Project Administration/Telephone Coordination.
658
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Freedom Park, Project No. MPK00001
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
15. Consultant Coordination - Proactively initiate communications efforts between the design team to address key issues timely.
TASK II. Preliminary Planning and Conceptual Design
1. Optional Civil Engineering Topographic Survey should the City need it by Madole and Associates. This is to establish topography and existing utilities, and to assist in the preparation of accurate base sheets.
2. Base Sheet Preparation at 1”=10’-0” at 24” x 36” Format.
3. Initial conceptual design following the first public engagement meeting. (two designs anticipated)
4. Design revisions to conceptual design following presentation of the initial two designs during the Second Public Engagement meeting. The revision will be to the one preferred alternative to present during the final engagement meeting.
5. Final design revisions following the third public engagement meeting for providing a finalized concept for City approval.
6. Project research, utility review, and coordination with consultants as applicable.
7. Preliminary Cost Estimate for City review and input.
8. Project timeline adjustments following concept approval for City approval.
TASK III. Construction Documents
1. Title sheet preparation utilizing City of Palm Desert Title Block. (24”x36” sheet format, one sheet total)
2. Construction Document Base Sheet Preparation at 1” =10’ (scale). (24”x36” sheet format, one sheet total)
3. Demolition Plan prepared by ADG indicating all removals and items to remain.
4. Fine grading plan coordination with Madole.
5. Construction Plan Preparation for layout and detailing of the new playground design.
6. Construction Detail Preparation for all proposed amenities.
7. Prepare Construction Specifications in book format at 8.5” x 11”.
8. Final cost estimate of all improvements specified on the construction plans.
9. Material furnishing selection.
10. Package Coordination.
11. Plan Checking and Plan Check Corrections.
12. Project Administration and Telephone Consultation.
13. Civil grading and drainage design plans by Madole. Plans will include all applicable grading requirements for a new playground and ADA compliance improvement.
659
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Freedom Park, Project No. MPK00001
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
14. Optional Electrical Engineering Plans Provided by JCA for new walkway lighting if desired from the community input meetings.
TASK IV. Bidding and Construction Support:
1. Respond to RFI’s during projects advertisement period.
2. Prepare project addenda for the City. (two anticipated)
3. Attend construction observation meetings during construction. (Three anticipated)
4. Preparation of site review reports for submittal to City staff for review, and contractor for correction. (three reports total)
5. Review and provide response to contractor's requests for information (RFI) about the plans and specifications forwarded to the Consultant by the City.
6. Submittal review.
7. Review and approve shop drawings, as needed. JCA’s electric plans do not include construction observation.
660
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Ironwood Park, Project No. MPK00008
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
PROJECT OVERVIEW:
ADG will provide professional services for the Ironwood Park Water Feature or Splash Pad and Shade Structure Project in the City of Palm Desert. The existing park features a substantial turf area, and a playground equipped with shade sails. Based on insights gathered from community engagement sessions, a specific water feature or splash pad will be selected for integration into the park. To incorporate the new amenities, we will:
• Collaborate with the Community, City, and California Waters to deliver an exciting new water feature or splash pad.
• Design the shade structure within the water feature area to mitigate high temperatures
• Maintain shade and accessibility for year-round use
These new features will align with established park standards while promoting both functionality and visual appeal.
PROJECT APPROACH:
ADG, having already visited the site, has a solid understanding of the existing conditions and is prepared to meet with the City immediately upon selection.
ADG will engage with the City to discuss the proposed scope of work, initial budgets, project details, and an updated timeline based on realistic expectations and starting points. Following this meeting, ADG will conduct a comprehensive site analysis of the existing play equipment and surrounding conditions at Ironwood Park.
The findings from this site analysis will help identify existing challenges and potential opportunities. These insights will be integrated into the public engagement plans using the TIERS methodology, ensuring a well-informed and community-driven approach.
ADG will facilitate three community engagement meetings as part of Task I: Public Engagement Phase. This will begin with an initial meeting with City and Parks and Recreation Staff to establish the approach for public engagement. Following this, ADG will conduct initial stakeholder and secondary stakeholder meetings, as well as broader community outreach efforts.
Simultaneously, Task II: Preliminary Planning and Conceptual Design Phase will progress in parallel to ensure that all necessary materials are prepared for these meetings.
After gathering community input, ADG will compile and analyze the feedback to develop a comprehensive report for the City Council. This report, which will include an overview of requested amenities and recommendations for any further input if needed, will be submitted no later than three months from the contract start date.
If no further input is required, ADG will proceed to Task III: Construction Document Phase.
This phase will include the development of:
661
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Ironwood Park, Project No. MPK00008
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
• Demolition plans
• Construction plans
• Construction detailing and
specifications
• Cost estimating
• Lighting Plan (JCA)
• Grading Plan (Madole)
Additionally, ADG will provide bidding and construction support as requested in the RFP from the City of Palm Desert, providing assistance during the construction of Ironwood Park.
JCA, our Electrical Engineering consultant, will provide Electrical Engineering, Electrical Construction Documents, and Electrical Document support for the new water feature and if new lighting is required by the City.
Madole, our Civil Engineering consultant, will provide an optional topographic survey if one is not available from the City, and a grading and drainage plan based off the approved design direction.
California Waters, our Water Feature consultant, will assist with the design and preparation of construction documents for the water feature at the park, ensuring a well-integrated and functional aquatic element.
PROJECT ASSUMPTIONS:
• Given the site's high temperatures and the existing, well-maintained shade infrastructure, the planned water feature or splash pad will include a shade structure, creating a comfortably shaded space for year-round use. • The Ironwood Park Scope, as defined in the RFP, is limited to the installation of a new water feature or splash pad and shade structure. If the scope expands beyond this after Task I and Task II, ADG and its consultants reserve the right to adjust fees accordingly.
• The City has indicated the possibility of providing topographic surveys but has requested an optional survey fee from our consultants for convenience. • If new lighting fixtures need to be added to the exiting lighting system, JCA has provided a separate fee for the City to consider.
• Per the RFP and Q and A, the scope is limited to the installation of a new water feature or splash pad and shade structure, and adjustments to adjacent existing hardscape are not anticipated.
• Structural engineering for various amenities are not included in this fee. It is anticipated the prefabricated elements/structures will be a deferred submittal.
The City’s selected contractor will be responsible for providing these. However if that is not the case or the scope expands during public engagement and amenities requiring engineering are to be implemented, ADG will reach out to a structural engineer for an additional fee.
• The water feature or splash pad is assumed to have its water point of connection off the potable water meter that feeds the restroom building and will not utilize a landscape water meter.
662
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Ironwood Park, Project No. MPK00008
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
• We anticipate there are no existing showers on site, and as such new showers will need to be included with any water feature that encourages active play like a splash pad. We assume this requirement will be met with pole type shower & no improvements will be made to the existing restroom.
• The existing restroom on site is not a part of the scope, and if the water feature is active play like a splash pad, then the number of restroom stalls & fixtures will drive the overall design and size of the feature to meet CBC requirements. • We do not anticipate any above ground housing for the pump equipment. Pump equipment will be housed in underground vaults.
• 3D renderings of the splash pad features are also anticipated to be provided by the manufacturer. If unavailable, ADG can coordinate provide a quote for rendering services. 3D renderings of water features that are not a splash pad are not included.
Our Scope of Services are further detailed below and are listed in order of anticipated completion.
SCOPE OF SERVICES
ADG has reviewed the scope of service requirements identified in the RFP. Based on these requirements, ADG, and its team of consultants, agree to provide the following services for the park site as indicated below. All designs will be prepared in accordance with ADA guidelines. Subconsultant proposals are included in our separate fee envelope to provide further details.
TASK I. Public Engagement
1. Project Kick Off Meeting (one in Person). This will be the time where ADG will collect preliminary information for the Public Engagement Plan in order to set the goals and objectives for the first, and subsequent public engagement meetings.
2. Site Field Visit to record existing conditions of project area and analyze opportunities and constraints. Soil Samples will be taken at this time for potential use in case the project scope expands to include new landscaping.
3. Site Visit report to document the findings of the site field visit.
4. Timeline and Schedule creation following the project kick off meeting outlining each phase of the project for City approval.
5. Public Engagement Plan based off the Tiers Public Engagement Framework for City approval.
6. Presentation material creation for the three engagement meetings to accurately convey design ideas and get feedback.
7. Initial Public Engagement meeting with the City and Stakeholders to define the design direction for the conceptual design moving into the secondary public engagement meeting.
663
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Ironwood Park, Project No. MPK00008
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
8. Secondary Public Engagement Meeting, where ADG shall present multiple design alternatives (two anticipated). ADG will collect feedback for both the designs to make design revisions and finalize the preferred design (one anticipated) with the feedback received.
9. Final Public Engagement meeting, where feedback from the City and Stakeholders, as approved by the City during the previous meeting, will be incorporated into the final design and presented during this meeting. Any final feedback will be incorporated after this meeting to provide a final concept for the City. At this time community engagement regarding a new name for the park (if applicable) will be decided per City of Palm Desert Resolution No. 2015-33.
10. Following the completion of each of the engagement meetings, a Public Engagement Report will be drafted reporting on each of the meeting’s findings. It is anticipated that three months after the contract start date this report will be finalized and completed for City review.
11. Monthly in-person meetings will be attended for an anticipated six months (six meetings). This will cover the conceptual design through construction documents. Monthly meetings in the construction phase are not anticipated.
12. Pre-Bid meeting prior to sending the plans out to bid. (anticipated one inperson meeting)
13. Pre-construction meeting prior to sending the plans out to bid. (anticipated one in-person meeting)
14. Project Administration/Telephone Coordination.
15. Consultant Coordination - Proactively initiate communications efforts between the design team to address key issues timely.
TASK II. Preliminary Planning and Conceptual Design
1. Optional Civil Engineering Topographic Survey should the City need it by Madole and Associates. This is to establish topography and existing utilities, and to assist in the preparation of accurate base sheets.
2. Coordination meeting with California Waters in association with the design of the water feature.
3. Base Sheet Preparation at 1”=20’-0” at 24” x 36” Format.
4. Initial conceptual design following the first public engagement meeting, two designs anticipated.
5. Design revisions to conceptual design following presentation of the initial two designs during the Second Public Engagement meeting. The revision will be to the one preferred alternative to present during the final engagement meeting.
6. Final design revisions following the third public engagement meeting to provide a finalized concept for City approval.
664
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Ironwood Park, Project No. MPK00008
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
7. Project research, utility review, and coordination with consultants as applicable.
8. Preliminary Cost Estimate for City review and input.
9. Project timeline adjustments following concept approval for City approval.
TASK III. Construction Documents
1. Title sheet preparation utilizing City of Palm Desert Title Block. (24”x36” sheet format, one sheet total)
2. Construction Document Base Sheet Preparation at 1” =20’ (scale). (24”x36” sheet format, one sheet total)
3. Demolition Plan prepared by ADG indicating all removals and items to remain.
4. Fine grading plan coordination with Madole.
5. Construction Plan Preparation for layout and detailing of the new playground design.
6. Construction Detail Preparation for all proposed amenities.
7. Prepare Construction Specifications in book format at 8.5” x 11”.
8. Final cost estimate of all improvements specified in the construction plans.
9. Material furnishing selection.
10. Package Coordination.
11. Plan Checking and Plan Check Corrections.
12. Project Administration and Telephone Consultation.
13. Civil grading and drainage design plans by Madole. Plans will include all applicable grading requirements for a new playground and ADA compliance improvement.
14. Optional Electrical Engineering Plans Provided by JCA for new walkway lighting if desired from the community input meetings.
15. Water Feature or splash pad construction documents assistance provided by California Waters.
TASK IV. Bidding and Construction Support:
1. Respond to RFI’s during projects advertisement period.
2. Prepare project addenda for the City. (two anticipated)
3. Attend construction observation meetings during construction. (three anticipated)
4. Preparation of site review reports for submittal to City staff for review, and contractor for correction. (three reports total)
5. Review and provide response to contractor's requests for information (RFI) about the plans and specifications forwarded to the Consultant by the City. 665
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
Ironwood Park, Project No. MPK00008
D. PROPOSED METHOD TO ACCOMPLISH THE WORK
6. Submittal review.
7. Review and approve shop drawings, as needed. JCA’s electric plans do not include construction observation.
8. California Waters Bidding and Construction Support for the Water Feature or Splash Pad.
666
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800
PARK AND TRAILHEAD (RFP)
CITY OF PALM DESERT
APPENDICES
PROJECT SCHEDULES
APPENDICES
667
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800 668
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800 669
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800 670
10221-A Trademark St., Rancho Cucamonga, CA 909-484-2800 671
LANDSCAPE ARCHITECTURAL SERVICES FOR PARK AND TRAILHEAD ENGINEERING AND DESIGN 2024-RFP-156
FEE PROPOSAL
Homme Adams Park (CPK00005)
TASK I. Public Engagement $18,710.00
TASK II. Preliminary Planning and Conceptual Design $22,575.00 TASK III. Construction Documents $216,385.00
TASK IV. Bidding and Construction Support $5,940.00
Professional Fee Total: $263,610.00
Estimated Reimbursable Expense Allowance: * $1,500.00
GRAND TOTAL: $265,110.00
University Park (CPK00006)
TASK I. Public Engagement $18,190.00
TASK II. Preliminary Planning and Conceptual Design $14,056.00 TASK III. Construction Documents $26,920.00
TASK IV. Bidding and Construction Support $4,725.00
Professional Fee Total: $63,891.00
Estimated Reimbursable Expense Allowance: * $1,500.00
GRAND TOTAL: $65,391.00
Washington Charter (CPK00008)
TASK I. Public Engagement $18,190.00
TASK II. Preliminary Planning and Conceptual Design $14,720.00 TASK III. Construction Documents $44,173.00
TASK IV. Bidding and Construction Support $4,725.00
Professional Fee Total: $81,808.00
Estimated Reimbursable Expense Allowance: * $1,500.00
GRAND TOTAL: $83,308.00
672
Randall Henderson Trailhead (CPK00009)
TASK I. Public Engagement $18,710.00
TASK II. Preliminary Planning and Conceptual Design $22,125.00 TASK III. Construction Documents $209,509.00
TASK IV. Bidding and Construction Support $5,940.00
Professional Fee Total: $256,284.00
Estimated Reimbursable Expense Allowance: * $1,500.00
GRAND TOTAL: $257,784.00
Freedom Park (MPK00001)
TASK I. Public Engagement $18,190.00
TASK II. Preliminary Planning and Conceptual Design $16,440.00 TASK III. Construction Documents $23,986.00
TASK IV. Bidding and Construction Support $4,725.00
Professional Fee Total: $63,341.00
Estimated Reimbursable Expense Allowance: * $1,500.00
GRAND TOTAL: $64,841.00
Ironwood Park (MPK00008)
TASK I. Public Engagement $18,190.00
TASK II. Preliminary Planning and Conceptual Design $16,626.00 TASK III. Construction Documents $75,258.00
TASK IV. Bidding and Construction Support $7,725.00
Professional Fee Total: $117,799.00
Estimated Reimbursable Expense Allowance: * $1,500.00
GRAND TOTAL: $119,299.00
Landscape Architect - Architerra Design Group Hourly Billing Rates:
Principal $200.00/Hour
Director $175.00/Hour
Project Manager $135.00/Hour
Landscape Designer $120.00/Hour
CADD Designer $100.00/Hour
Clerical $65.00/Hour
673
Reimbursable Expenses *
The following costs shall be reimbursed at cost, as needed, and are based on the demands of the project for items such as:
• Expense of outside reprographic reproductions for generation of original drawings, plan check submittals and construction bidding, including printing, plotting, photo reproductions, display photo boards and handouts.
• All automobile mileage shall be paid at the standard rate for business automobile use as set forth by the Internal Revenue Service.
• Cost of postage and shipping expenses other than first class mail. • Photographic services, film and processing.
• Third party soil testing, as required by California Water Efficient Landscape Ordinance AB 1881. (agronomic soil testing)
674
Homme Adams Park
Architerra Design Group PAGE 1 OF 3
ARCHITERRA DESIGN GROUP
HOUR & COST PROJECTION
JOB NAME: Homme Adams Park (CPK00005)
CLIENT: City of Palm Desert
CONTACT: Melanie Slater
DATE: 03/18/2025
PREPARED BY: ARK
TASK I. PUBLIC ENGAGEMENT PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
PROJECT KICK OFF MEETING (1 In-Person) 3 3 6 930.00 $
SITE VISIT (SOIL SAMPLE COLLECTED AT THIS TIME) 4 4 540.00 $ SITE VISIT REPORT 6 6 12 1,560.00 $
TIMELINE & SCHEDULE CREATION 2 2 270.00 $
PUBLIC ENGAGEMENT PLAN 4 4 8 1,240.00 $
PRESENTATION MATERIAL CREATION FOR ENGAGEMENT MEETINGS 4 8 12 24 2,320.00 $ PUBLIC ENGAGEMENT MEETING, INITIAL 4 4 8 1,240.00 $
PUBLIC ENGAGEMENT MEETINGS, SECONDARY 4 4 8 1,240.00 $
PUBLIC ENGAGEMENT MEETINGS, FINAL FOR PARKS & REC 4 4 8 1,240.00 $ PUBLIC ENGAGEMENT REPORT 1 8 4 13 1,515.00 $
MONTHLY MEETINGS (ASSUME 6 IN PERSON OVER 6 MO.) 24 24 3,240.00 $ PRE BID MEETING 4 4 540.00 $
PRE CONSTRUCTION MEETING 4 4 540.00 $
PROJECT ADMINISTRATION/TELEPHONE CONSULTATION 8 8 1,080.00 $ SUB. COORDINATION, JCA, MADOLE, & PLAY (3HRS EA) 9 9 1,215.00 $ TOTALS 0 20 92 14 0 16 142 18,710.00 $
TASK II. PRELIMINARY PLANNING AND
CONCEPTUAL DESIGN PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
MADOLE & ASSOCIATES (CIVIL) TOPO IF REQUIRED ALLOW 10,450.00 $ BASE SHEET DEVELOPMENT 1 SHT 1"=80' AT 24 X 36 & 2 AT 20 SC 2 6 8 870.00 $ INITIAL CONCEPT AFTER 1ST PUBLIC ENGMT. (2 DESIGNS) 2 3 24 3 32 4,055.00 $ INITIAL CONCEPT REVISIONS FOR 2ND OUTREACH. (1 DESIGN) 2 2 12 2 18 2,320.00 $ FINAL CONCEPT REVISIONS FOR 3RD OUTREACH. (1 DESIGN) 2 2 12 2 18 2,320.00 $ MATERIALS BOARD 2 4 6 770.00 $
PROJECT RESEARCH, UTILITY REVIEW AND COORDINATION 3 3 405.00 $ PRELIMINARY COST ESTIMATE 1 2 4 7 845.00 $
PROJECT TIMELINE ADJUSTMENTS, FOR EACH PHASE W/ COST) 4 4 540.00 $ TOTALS 0 7 20 52 17 0 96 22,575.00 $
675
Homme Adams Park
Architerra Design Group PAGE 2 OF 3
TASK III. CONSTRUCTION DOCUMENTS PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
TITLE SHEET/PROJECT INFO. 1 3 4 435.00 $
CAD BASE SHEET DEVELOPMENT (4 HRS/ 3 SHTS) 3 9 12 1,305.00 $ DEMOLITION PLAN (7 HRS/ 3 SHTS) 3 18 21 2,205.00 $
GRADING MARK UP COORDINATION 6 6 1,050.00 $
CONSTRUCTION PLAN (12 HRS/ 3 SHTS) 8 24 32 3,480.00 $
CONSTRUCTION AND GRADING DETAILS 2 4 32 10 48 5,890.00 $ IRRIGATION PLAN (18 HRS/3 SHTS) 12 42 54 5,820.00 $
IRRIGATION DETAILS 1 2 3 335.00 $
WATER EFFICIENT LANDSCAPE WORKSHEET * 0.5 1.5 2 217.50 $ TWO IRRIGATION CONTROLLER CHARTS * 0.5 1.5 2 217.50 $
PLANTING PLAN (12HRS/3 SHTS) 2 6 28 36 3,960.00 $
PLANTING DETAILS 0.5 1 1.5 167.50 $
PLANTING/IRRG. HYDRO ZONE PLAN* 2 2 4 470.00 $
SOILS TEST & REPORT TIME * 1 1 135.00 $
ANNUAL IRRIGATION & PLANTING MAINTENANCE SCH. * 0.5 0.5 1 117.50 $ CONSTRUCTION, IRRIGATION, & PLANTING SPECIFICATIONS (BOOK) 4 4 8 1,240.00 $ COST ESTIMATE (FINAL) 3 6 9 1,005.00 $
MATERIAL / FURNISHING SELECTION 4 4 8 1,040.00 $
MANAGEMENT PLAN 10 84 30 124 15,040.00 $
PACKAGE COORDINATION 2 2 270.00 $
PLAN CHECKING 6 4 12 22 2,790.00 $
PROJECT ADMINISTRATION 10 10 1,350.00 $
TELEPHONE CONSULTATION 6 6 810.00 $
CONSULTANT COORDINATION 100 100 13,500.00 $
MADOLE & ASSOCIATES (CIVIL) WQMP ALLOW 7,440.00 $
MADOLE & ASSOCIATES (CIVIL) Grading & Specs ALLOW 9,136.00 $ JCA (ELECTRICAL ENGINEER) Lighting Plan and Building Electric ALLOW 18,900.00 $ GEOTEK (GEOTECHNIAL) GEOTECHNICAL PLAN ALLOW 18,267.00 $ ECORP (ENVIRONMENTAL) ENVIRONMENTAL REPORTS ALLOW 99,792.00 $ TOTALS 0 30 260 36 160.5 30 516.5 $216,385.00
TASK IV. BIDDING AND CONSTRUCTION
SUPPORT PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
ANSWER RFI'S DURING ADVERTISEMENT PERIOD 4 4 540.00 $
PREPARE PROJECT ADDENDA FOR CITY (ASSUME 2) 4 4 540.00 $ CONSTRUCTION OBSERVATION (ASSUME 3 @ 5 HOURS EACH) 15 15 2,025.00 $ PREPARATION OF SITE REVIEW REPORTS ( ASSUME 3) 3 3 405.00 $ ANSWER RFI'S AFTER CONSTRUCTION BID AWARD 6 6 810.00 $
676
Homme Adams Park
Architerra Design Group PAGE 3 OF 3
SUBMITTAL REVIEW 8 8 1,080.00 $
SHOP DRAWING REVIEW 4 4 540.00 $
TOTALS 0 0 44 0 0 0 44 5,940.00 $
PROFESSIONAL SERVICES TOTAL 263,610.00 $
ESTIMATED REIMBURSABLE ALLOWANCE (STATE REQUIRED THIRD-PARTY SOIL TESTING, IRS MILEAGE FOR SITE VISITS) 1,500.00 $ GRAND TOTAL 265,110.00 $
TEAM
ARCHITERRA (LANDSCAPE ARCHITECT) 99,625.00 $
MADOLE (CIVIL ENGINEER) 27,026.00 $
JCA (ELECTRICAL ENGINEER) 18,900.00 $
GEOTEK (GEOTECHNICAL ENGINEER) 18,267.00 $
ECORP (ENVIRONMENTAL) 99,792.00 $
TOTAL 263,610.00 $
677
University Park
Architerra Design Group PAGE 1 OF 2
ARCHITERRA DESIGN GROUP
HOUR & COST PROJECTION
JOB NAME: University Park (CPK00006)
CLIENT: City of Palm Desert
CONTACT: Melanie Slater
DATE: 03/18/2025
PREPARED BY: ARK
TASK I. PUBLIC ENGAGEMENT PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
PROJECT KICK OFF MEETING (1 In-Person) 3 3 6 930.00 $
SITE VISIT (SOIL SAMPLE COLLECTED AT THIS TIME) 4 4 540.00 $ SITE VISIT REPORT 4 4 8 1,040.00 $
TIMELINE & SCHEDULE CREATION 2 2 270.00 $
PUBLIC ENGAGEMENT PLAN 4 4 8 1,240.00 $
PRESENTATION MATERIAL CREATION FOR ENGAGEMENT MEETINGS 4 8 12 24 2,320.00 $ PUBLIC ENGAGEMENT MEETING, INITIAL 4 4 8 1,240.00 $
PUBLIC ENGAGEMENT MEETINGS, SECONDARY 4 4 8 1,240.00 $
PUBLIC ENGAGEMENT MEETINGS, FINAL FOR PARKS & REC 4 4 8 1,240.00 $ PUBLIC ENGAGEMENT REPORT 1 8 4 13 1,515.00 $
MONTHLY MEETINGS (ASSUME 6 IN PERSON OVER 6 MO.) 24 24 3,240.00 $ PRE BID MEETING 4 4 540.00 $
PRE CONSTRUCTION MEETING 4 4 540.00 $
PROJECT ADMINISTRATION/TELEPHONE CONSULTATION 8 8 1,080.00 $ SUB. COORDINATION, JCA, MADOLE, & PLAY (3HRS EA) 9 9 1,215.00 $ TOTALS 0 20 90 12 0 16 138 18,190.00 $
TASK II. PRELIMINARY PLANNING AND
CONCEPTUAL DESIGN PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
MADOLE & ASSOCIATES (CIVIL) TOPO *OPTIONAL ALLOW 6,216.00 $ CIVIL COORDINATION 5 5 675.00 $
BASE SHEET DEVELOPMENT 1"=10' AT 24 X 36 2 4 6 670.00 $ INITIAL CONCEPT AFTER 1ST PUBLIC ENGMT. (2 DESIGNS) 2 16 2 20 2,470.00 $ INITIAL CONCEPT REVISIONS FOR 2ND OUTREACH. (1 DESIGN) 1 8 1 10 1,235.00 $ FINAL CONCEPT REVISIONS FOR 3RD OUTREACH. (1 DESIGN) 1 8 1 10 1,235.00 $ PROJECT RESEARCH, UTILITY REVIEW AND COORDINATION 3 3 405.00 $ PRELIMINARY COST ESTIMATE 1 1 3 5 610.00 $
PROJECT TIMELINE ADJUSTMENTS, FOR EACH PHASE W/ COST) 4 4 540.00 $ TOTALS 0 1 19 32 11 0 63 14,056.00 $
678
University Park
Architerra Design Group PAGE 2 OF 2
TASK III. CONSTRUCTION DOCUMENTS PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
TITLE SHEET/PROJECT INFO. 1 3 4 435.00 $
CONSTRUCTION DOCUMENT BASE SHEET SCALE: 1"=10' (24"x 36") 1 3 4 435.00 $ DEMOLITION PLAN 1.5 6.5 8 852.50 $
GRADING MARK UP COORDINATION 2 2 4 620.00 $
CONSTRUCTION PLAN (8 HRS/SHT) 4 12 16 1,740.00 $
CONSTRUCTION AND GRADING DETAILS (including rubber layout) 2 6 8 870.00 $ CONSTRUCTION SPECIFICATIONS (BOOK) 1 3 4 580.00 $
COST ESTIMATE (FINAL) 1 4 5 535.00 $
MATERIAL / FURNISHING SELECTION 0.5 1 2 3.5 472.50 $
PACKAGE COORDINATION 2 2 270.00 $
PLAN CHECKING 4 2 8 14 1,770.00 $
PROJECT ADMINISTRATION & TELEPHONE CONSULTATION 4 4 540.00 $ CONSULTANT COORDINATION 12 12 1,620.00 $
MADOLE & ASSOCIATES (CIVIL) Grading & Specs ALLOW 6,480.00 $ JCA (ELECTRICAL ENGINEER) Lighting Plan and Building Electric ALLOW 9,700.00 $ TOTALS 0 7.5 36.5 2 42.5 0 88.5 $26,920.00
TASK IV. BIDDING AND CONSTRUCTION
SUPPORT PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
ANSWER RFI'S DURING ADVERTISEMENT PERIOD 4 4 540.00 $
PREPARE PROJECT ADDENDA FOR CITY (ASSUME 2) 4 4 540.00 $ CONSTRUCTION OBSERVATION (ASSUME 3 @ 3.5 HOURS EACH) 10 10 1,350.00 $ PREPARATION OF SITE REVIEW REPORTS ( ASSUME 3) 3 3 405.00 $ ANSWER RFI'S AFTER CONSTRUCTION BID AWARD 4 4 540.00 $
SUBMITTAL REVIEW 6 6 810.00 $
SHOP DRAWING REVIEW 4 4 540.00 $
TOTALS 0 0 35 0 0 0 35 4,725.00 $
PROFESSIONAL SERVICES TOTAL 63,891.00 $
ESTIMATED REIMBURSABLE ALLOWANCE (STATE REQUIRED THIRD-PARTY SOIL TESTING, IRS MILEAGE FOR SITE VISITS) 1,500.00 $ GRAND TOTAL 65,391.00 $
TEAM
ARCHITERRA (LANDSCAPE ARCHITECT) 41,495.00 $
MADOLE (CIVIL ENGINEER) 12,696.00 $
JCA (ELECTRICAL ENGINEER) 9,700.00 $
TOTAL 63,891.00 $
679
Washington Charter
Architerra Design Group PAGE 1 OF 2
ARCHITERRA DESIGN GROUP
HOUR & COST PROJECTION
JOB NAME: Washington Charter (CPK00008)
CLIENT: City of Palm Desert
CONTACT: Melanie Slater
DATE: 03/18/2025
PREPARED BY: ARK
TASK I. PUBLIC ENGAGEMENT PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
PROJECT KICK OFF MEETING (1 In-Person) 3 3 6 930.00 $
SITE VISIT (SOIL SAMPLE COLLECTED AT THIS TIME) 4 4 540.00 $ SITE VISIT REPORT 4 4 8 1,040.00 $
TIMELINE & SCHEDULE CREATION 2 2 270.00 $
PUBLIC ENGAGEMENT PLAN 4 4 8 1,240.00 $
PRESENTATION MATERIAL CREATION FOR ENGAGEMENT MEETINGS 4 8 12 24 2,320.00 $ PUBLIC ENGAGEMENT MEETING, INITIAL 4 4 8 1,240.00 $
PUBLIC ENGAGEMENT MEETINGS, SECONDARY 4 4 8 1,240.00 $
PUBLIC ENGAGEMENT MEETINGS, FINAL FOR PARKS & REC 4 4 8 1,240.00 $ PUBLIC ENGAGEMENT REPORT 1 8 4 13 1,515.00 $
MONTHLY MEETINGS (ASSUME 6 IN PERSON OVER 6 MO.) 24 24 3,240.00 $ PRE BID MEETING 4 4 540.00 $
PRE CONSTRUCTION MEETING 4 4 540.00 $
PROJECT ADMINISTRATION/TELEPHONE CONSULTATION 8 8 1,080.00 $ SUB. COORDINATION, JCA, MADOLE, & PLAY (3HRS EA) 9 9 1,215.00 $ TOTALS 0 20 90 12 0 16 138 18,190.00 $
TASK II. PRELIMINARY PLANNING AND
CONCEPTUAL DESIGN PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
MADOLE & ASSOCIATES (CIVIL) TOPO IF REQUIRED ALLOW 6,880.00 $ COORDINATION WITH CIVIL 5 5 675.00 $
BASE SHEET DEVELOPMENT 1"=10' AT 24 X 36 2 4 6 670.00 $ INITIAL CONCEPT AFTER 1ST PUBLIC ENGMT. (2 DESIGNS) 2 16 2 20 2,470.00 $ INITIAL CONCEPT REVISIONS FOR 2ND OUTREACH. (1 DESIGN) 1 8 1 10 1,235.00 $ FINAL CONCEPT REVISIONS FOR 3RD OUTREACH. (1 DESIGN) 1 8 1 10 1,235.00 $ PROJECT RESEARCH, UTILITY REVIEW AND COORDINATION 3 3 405.00 $ PRELIMINARY COST ESTIMATE 1 1 3 5 610.00 $
PROJECT TIMELINE ADJUSTMENTS, FOR EACH PHASE W/ COST) 4 4 540.00 $ TOTALS 0 1 19 32 11 0 63 14,720.00 $
680
Washington Charter
Architerra Design Group PAGE 2 OF 2
TASK III. CONSTRUCTION DOCUMENTS PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
TITLE SHEET/PROJECT INFO. 1 3 4 435.00 $
CONSTRUCTION DOCUMENT BASE SHEET PREP. 1 3 4 435.00 $
DEMOLITION PLAN 1.5 6.5 8 852.50 $
GRADING MARK UP COORDINATION 2 2 4 620.00 $
CONSTRUCTION PLAN (8 HRS/SHT) 4 12 16 1,740.00 $
CONSTRUCTION AND GRADING DETAILS (including rubber layout) 2 6 8 870.00 $ CONSTRUCTION SPECIFICATIONS (BOOK) 1 3 4 580.00 $
COST ESTIMATE (FINAL) 1 4 5 535.00 $
MATERIAL / FURNISHING SELECTION 0.5 1 2 3.5 472.50 $
PACKAGE COORDINATION 2 2 270.00 $
PLAN CHECKING 4 2 8 14 1,770.00 $
PROJECT ADMINISTRATION & TELEPHONE CONSULTATION 4 4 540.00 $ CONSULTANT COORDINATION 23 23 3,105.00 $
MADOLE & ASSOCIATES (CIVIL) Grading & Specs ALLOW 7,808.00 $ MADOLE & ASSOCIATES (CIVIL) WQMP ALLOW 7,440.00 $
JCA (ELECTRICAL ENGINEER) Lighting Plan and Building Electric ALLOW 9,700.00 $ SVA (ARCHITECT) Coordination with DSA ALLOW 7,000.00 $
TOTALS 0 7.5 47.5 2 42.5 0 99.5 $44,173.00
AB 1881 COMPLIANCE ITEMS *
TASK IV. BIDDING AND CONSTRUCTION
SUPPORT PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
ANSWER RFI'S DURING ADVERTISEMENT PERIOD 4 4 540.00 $
PREPARE PROJECT ADDENDA FOR CITY (ASSUME 2) 4 4 540.00 $ CONSTRUCTION OBSERVATION (ASSUME 3 @ 3.5 HOURS EACH) 10 10 1,350.00 $ PREPARATION OF SITE REVIEW REPORTS ( ASSUME 3) 3 3 405.00 $ ANSWER RFI'S AFTER CONSTRUCTION BID AWARD 4 4 540.00 $
SUBMITTAL REVIEW 6 6 810.00 $
SHOP DRAWING REVIEW 4 4 540.00 $
TOTALS 0 0 35 0 0 0 35 4,725.00 $
PROFESSIONAL SERVICES TOTAL 81,808.00 $
ESTIMATED REIMBURSABLE ALLOWANCE (STATE REQUIRED THIRD-PARTY SOIL TESTING, IRS MILEAGE FOR SITE VISITS) 1,500.00 $ GRAND TOTAL 83,308.00 $
TEAM
ARCHITERRA (LANDSCAPE ARCHITECT) 42,980.00 $
MADOLE (CIVIL ENGINEER) 22,128.00 $
JCA (ELECTRICAL ENGINEER) 9,700.00 $
SVA (ARCHITECT) 7,000.00 $
TOTAL 81,808.00 $
681
Randall Henderson Trailhead
Architerra Design Group PAGE 1 OF 3
ARCHITERRA DESIGN GROUP
HOUR & COST PROJECTION
JOB NAME: Randall Henderson Trailhead (CPK00009)
CLIENT: City of Palm Desert
CONTACT: Melanie Slater
DATE: 03/18/2025
PREPARED BY: ARK
TASK I. PUBLIC ENGAGEMENT PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
PROJECT KICK OFF MEETING (1 In Person) 3 3 6 930.00 $
SITE VISIT (SOIL SAMPLE COLLECTED AT THIS TIME) 4 4 540.00 $ SITE VISIT REPORT 6 6 12 1,560.00 $
TIMELINE & SCHEDULE CREATION 2 2 270.00 $
PUBLIC ENGAGEMENT PLAN 4 4 8 1,240.00 $
PRESENTATION MATERIAL CREATION FOR ENGAGEMENT MEETINGS 4 8 12 24 2,320.00 $ PUBLIC ENGAGEMENT MEETING, INITIAL 4 4 8 1,240.00 $
PUBLIC ENGAGEMENT MEETINGS, SECONDARY 4 4 8 1,240.00 $
PUBLIC ENGAGEMENT MEETINGS, FINAL FOR PARKS & REC 4 4 8 1,240.00 $ PUBLIC ENGAGEMENT REPORT 1 8 4 13 1,515.00 $
MONTHLY MEETINGS (ASSUME 6 IN PERSON OVER 6 MO.) 24 24 3,240.00 $ PRE BID MEETING 4 4 540.00 $
PRE CONSTRUCTION MEETING 4 4 540.00 $
PROJECT ADMINISTRATION/TELEPHONE CONSULTATION 8 8 1,080.00 $ SUB. COORDINATION, JCA, MADOLE, & PLAY (3HRS EA) 9 9 1,215.00 $ TOTALS 0 20 92 14 0 16 142 18,710.00 $
TASK II. PRELIMINARY PLANNING AND
CONCEPTUAL DESIGN PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
MADOLE & ASSOCIATES (CIVIL) TOPO IF REQUIRED ALLOW 10,200.00 $ SCALE: 1"=80'-0" (1 SHT) & 1"= 20'-0" (2 SHTS) 2 4 6 670.00 $ INITIAL CONCEPT AFTER 1ST PUBLIC ENGMT. (2 DESIGNS) 2 3 24 3 32 4,055.00 $ INITIAL CONCEPT REVISIONS FOR 2ND OUTREACH. (1 DESIGN) 2 2 12 2 18 2,320.00 $ FINAL CONCEPT REVISIONS FOR 3RD OUTREACH. (1 DESIGN) 2 2 12 2 18 2,320.00 $ MATERIALS BOARD 2 4 6 770.00 $
PROJECT RESEARCH, UTILITY REVIEW AND COORDINATION 3 3 405.00 $ PRELIMINARY COST ESTIMATE 1 2 4 7 845.00 $
PROJECT TIMELINE ADJUSTMENTS, FOR EACH PHASE W/ COST) 4 4 540.00 $ TOTALS 0 7 20 52 15 0 94 22,125.00 $
682
Randall Henderson Trailhead
Architerra Design Group PAGE 2 OF 3
TASK III. CONSTRUCTION DOCUMENTS PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
TITLE SHEET/PROJECT INFO. 1 3 4 435.00 $
CAD BASE SHEET DEVELOPMENT (4 HRS/ 2 SHTS) 2 6 8 870.00 $ DEMOLITION PLAN (7 HRS/ 2 SHTS) 2 12 14 1,470.00 $
GRADING MARK UP COORDINATION 6 6 1,050.00 $
CONSTRUCTION PLAN (12 HRS/ 2 SHTS) 6 18 24 2,610.00 $
CONSTRUCTION AND GRADING DETAILS 2 4 32 10 48 5,890.00 $ IRRIGATION PLAN (22 HRS/1 SHTS) 4 18 22 2,340.00 $
IRRIGATION DETAILS 1 2 3 335.00 $
WATER EFFICIENT LANDSCAPE WORKSHEET * 0.5 1.5 2 217.50 $ TWO IRRIGATION CONTROLLER CHARTS * 0.5 1.5 2 217.50 $
PLANTING PLAN (16HRS/1 SHT) 1 3 12 16 1,780.00 $
PLANTING DETAILS 0.5 1 1.5 167.50 $
PLANTING/IRRG. HYDRO ZONE PLAN* 1 1.5 2.5 285.00 $
SOILS TEST & REPORT TIME * 1 1 135.00 $
ANNUAL IRRIGATION & PLANTING MAINTENANCE SCH. * 0.5 0.5 50.00 $ CONSTRUCTION, IRRIGATION, & PLANTING SPECIFICATIONS (BOOK) 4 4 8 1,240.00 $ COST ESTIMATE (FINAL) 3 6 9 1,005.00 $
MATERIAL / FURNISHING SELECTION 0.5 4 4 8.5 1,127.50 $
MANAGEMENT PLAN 10 84 30 124 15,040.00 $
PACKAGE COORDINATION 2 2 270.00 $
PLAN CHECKING 5 4 12 21 2,615.00 $
PROJECT ADMINISTRATION 10 10 1,350.00 $
TELEPHONE CONSULTATION 6 6 810.00 $
CONSULTANT COORDINATION 100 100 13,500.00 $
MADOLE & ASSOCIATES (CIVIL) WQMP ALLOW 7,440.00 $
MADOLE & ASSOCIATES (CIVIL) Grading & Specs ALLOW 10,300.00 $ JCA (ELECTRICAL ENGINEER) Lighting Plan and Building Electric ALLOW 18,900.00 $ GEOTEK (GEOTECHNIAL) GEOTECHNICAL PLAN ALLOW 18,267.00 $ ECORP (ENVIRONMENTAL) ENVIRONMENTAL REPORTS ALLOW 99,792.00 $ TOTALS 0 28.5 243.5 36 105 30 443 209,509.00 $
TASK IV. BIDDING AND CONSTRUCTION
SUPPORT PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
ANSWER RFI'S DURING ADVERTISEMENT PERIOD 4 4 540.00 $
PREPARE PROJECT ADDENDA FOR CITY (ASSUME 2) 4 4 540.00 $ CONSTRUCTION OBSERVATION (ASSUME 3 @ 5 HOURS EACH) 15 15 2,025.00 $ PREPARATION OF SITE REVIEW REPORTS ( ASSUME 3) 3 3 405.00 $ ANSWER RFI'S AFTER CONSTRUCTION BID AWARD 6 6 810.00 $
SUBMITTAL REVIEW 8 8 1,080.00 $
683
Randall Henderson Trailhead
Architerra Design Group PAGE 3 OF 3
SHOP DRAWING REVIEW 4 4 540.00 $
TOTALS 0 0 44 0 0 0 44 5,940.00 $
PROFESSIONAL SERVICES TOTAL 256,284.00 $
ESTIMATED REIMBURSABLE ALLOWANCE (STATE REQUIRED THIRD-PARTY SOIL TESTING, IRS MILEAGE FOR SITE VISITS) 1,500.00 $ GRAND TOTAL 257,784.00 $
TEAM
ARCHITERRA (LANDSCAPE ARCHITECT) 91,385.00 $
MADOLE (CIVIL ENGINEER) 27,940.00 $
JCA (ELECTRICAL ENGINEER) 18,900.00 $
GEOTEK (GEOTECHNICAL ENGINEER) 18,267.00 $
ECORP (ENVIRONMENTAL) 99,792.00 $
TOTAL 256,284.00 $
684
Freedom Park
Architerra Design Group PAGE 1 OF 2
ARCHITERRA DESIGN GROUP
HOUR & COST PROJECTION
JOB NAME: Freedom Park (MPK00001)
CLIENT: City of Palm Desert
CONTACT: Melanie Slater
DATE: 03/18/2025
PREPARED BY: ARK
TASK I. PUBLIC ENGAGEMENT PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
PROJECT KICK OFF MEETING (1 In Person) 3 3 6 930.00 $
SITE VISIT (SOIL SAMPLE COLLECTED AT THIS TIME) 4 4 540.00 $ SITE VISIT REPORT 4 4 8 1,040.00 $
TIMELINE & SCHEDULE CREATION 2 2 270.00 $
PUBLIC ENGAGEMENT PLAN 4 4 8 1,240.00 $
PRESENTATION MATERIAL CREATION FOR ENGAGEMENT MEETINGS 4 8 12 24 2,320.00 $ PUBLIC ENGAGEMENT MEETING, INITIAL 4 4 8 1,240.00 $
PUBLIC ENGAGEMENT MEETINGS, SECONDARY 4 4 8 1,240.00 $
PUBLIC ENGAGEMENT MEETINGS, FINAL FOR PARKS & REC 4 4 8 1,240.00 $ PUBLIC ENGAGEMENT REPORT 1 8 4 13 1,515.00 $
MONTHLY MEETINGS (ASSUME 6 IN PERSON OVER 6 MO.) 24 24 3,240.00 $ PRE BID MEETING 4 4 540.00 $
PRE CONSTRUCTION MEETING 4 4 540.00 $
PROJECT ADMINISTRATION/TELEPHONE CONSULTATION 8 8 1,080.00 $ SUB. COORDINATION, JCA, MADOLE, & PLAY (3HRS EA) 9 9 1,215.00 $ TOTALS 0 20 90 12 0 16 138 18,190.00 $
TASK II. PRELIMINARY PLANNING AND
CONCEPTUAL DESIGN PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
"OPTIONAL" MADOLE & ASSOCIATES (CIVIL) TOPO IF REQUIRED ALLOW 6,880.00 $ CIVIL COORDINATION WITH TOPO 5 5 675.00 $
BASE SHEET DEVELOPMENT 1"=10' AT 24 X 36 2 4 6 670.00 $ INITIAL CONCEPT AFTER 1ST PUBLIC ENGMT. 2 16 2 20 2,470.00 $ INITIAL CONCEPT FOR 2ND OUTREACH. (2 DESIGN) 1 8 1 10 1,235.00 $ FINAL CONCEPT REVISIONS FOR 3RD OUTREACH. (1 DESIGN) 1 8 1 10 1,235.00 $ FINAL CONCEPT REVISIONS BASED ON THIRD OUTREACH 0.5 3.5 4 505.00 $ REPORT & FINAL DESIGN PRESENTATION (ASSUME 2) 8 8 1,080.00 $ PROJECT RESEARCH, UTILITY REVIEW AND COORDINATION 3 3 405.00 $ PRELIMINARY COST ESTIMATE 1 2 3 6 745.00 $
PROJECT TIMELINE ADJUSTMENTS, FOR EACH PHASE W/ COST) 4 4 540.00 $ TOTALS 0 1 28.5 35.5 11 0 76 16,440.00 $
685
Freedom Park
Architerra Design Group PAGE 2 OF 2
TASK III. CONSTRUCTION DOCUMENTS PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
TITLE SHEET/PROJECT INFO. 1 3 4 435.00 $
CAD BASE SHEET DEVELOPMENT (4 HRS/SHT) 1 3 4 435.00 $
DEMOLITION PLAN 1.5 6.5 8 852.50 $
GRADING MARK UP COORDINATION 2 2 4 620.00 $
CONSTRUCTION PLAN (8 HRS/SHT) 4 12 16 1,740.00 $
CONSTRUCTION AND GRADING DETAILS (including rubber layout) 2 6 8 870.00 $ CONSTRUCTION SPECIFICATIONS (BOOK) 1 3 4 580.00 $
COST ESTIMATE (FINAL) 1 4 5 535.00 $
MATERIAL / FURNISHING SELECTION 0.5 1 2 3.5 472.50 $
PACKAGE COORDINATION 2 2 270.00 $
PLAN CHECKING AND PLAN CHECK CORRECTIONS 4 2 8 14 1,770.00 $ PROJECT ADMINISTRATION/TELEPHONE CONSULTATION 4 4 540.00 $ CONSULTANT COORDINATION 10 10 1,350.00 $
MADOLE & ASSOCIATES (CIVIL) Grading & Specs ALLOW 5,816.00 $ JCA (ELECTRICAL ENGINEER) Lighting Plan and Building Electric ALLOW 7,700.00 $ TOTALS 0 7.5 34.5 2 42.5 0 86.5 $23,986.00
TASK IV. BIDDING AND CONSTRUCTION
SUPPORT PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS COST PER TASK
ANSWER RFI'S DURING ADVERTISEMENT PERIOD 4 4 540.00 $
PREPARE PROJECT ADDENDA FOR CITY (ASSUME 2) 4 4 540.00 $ CONSTRUCTION OBSERVATION (ASSUME 3 @ 3.5 HOURS EACH) 10 10 1,350.00 $ PREPARATION OF SITE REVIEW REPORTS ( ASSUME 3) 3 3 405.00 $ ANSWER RFI'S AFTER CONSTRUCTION BID AWARD 4 4 540.00 $
SUBMITTAL REVIEW 6 6 810.00 $
SHOP DRAWING REVIEW 4 4 540.00 $
TOTALS 0 0 35 0 0 0 35 4,725.00 $
PROFESSIONAL SERVICES TOTAL 63,341.00 $
ESTIMATED REIMBURSABLE ALLOWANCE (STATE REQUIRED THIRD-PARTY SOIL TESTING, IRS MILEAGE FOR SITE VISITS) 1,500.00 $ GRAND TOTAL 64,841.00 $
TEAM
ARCHITERRA (LANDSCAPE ARCHITECT) 42,945.00 $
MADOLE (CIVIL ENGINEER) 12,696.00 $
JCA (ELECTRICAL ENGINEER) 7,700.00 $
TOTAL 63,341.00 $
686
Ironwood Park
ARCHITERRA DESIGN GROUP
HOUR & COST PROJECTION
JOB NAME: Ironwood Park (MPK00008)
CLIENT: City of Palm Desert
CONTACT: Melanie Slater
DATE: 03/18/2025
PREPARED BY: ARK
TASK I. PUBLIC ENGAGEMENT PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS
COST PER
TASK
PROJECT KICK OFF MEETING (1 In Person) 3 3 6 930.00 $
SITE VISIT (SOIL SAMPLE COLLECTED AT THIS TIME) 4 4 540.00 $ SITE VISIT REPORT 4 4 8 1,040.00 $
TIMELINE & SCHEDULE CREATION 2 2 270.00 $
PUBLIC ENGAGEMENT PLAN 4 4 8 1,240.00 $
PRESENTATION MATERIAL CREATION FOR ENGAGEMENT MEETINGS 4 8 12 24 2,320.00 $ PUBLIC ENGAGEMENT MEETING, INITIAL 4 4 8 1,240.00 $
PUBLIC ENGAGEMENT MEETINGS, SECONDARY 4 4 8 1,240.00 $
PUBLIC ENGAGEMENT MEETINGS, FINAL FOR PARKS & REC 4 4 8 1,240.00 $ PUBLIC ENGAGEMENT REPORT 1 8 4 13 1,515.00 $
MONTHLY MEETINGS (ASSUME 6 IN PERSON OVER 6 MO.) 24 24 3,240.00 $ PRE BID MEETING 4 4 540.00 $
PRE CONSTRUCTION MEETING 4 4 540.00 $
PROJECT ADMINISTRATION/TELEPHONE CONSULTATION 8 8 1,080.00 $ SUB. COORDINATION, JCA, MADOLE, & PLAY (3HRS EA) 9 9 1,215.00 $ TOTALS 0 20 90 12 0 16 138 18,190.00 $
TASK II. PRELIMINARY PLANNING AND CONCEPTUAL
DESIGN PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS
COST PER
TASK
MADOLE & ASSOCIATES (CIVIL) TOPO *OPTIONAL ALLOW 6,216.00 $ Coordination with Cal Waters for the Water Feature ALLOW 2,000.00 $ CONSULTANT COORDINATION 6 6 810.00 $
BASE SHEET DEVELOPMENT 1"=10' AT 24 X 36 2 6 8 870.00 $ INITIAL CONCEPT AFTER 1ST PUBLIC ENGMT. (2 DESIGNS) 2 16 2 20 2,470.00 $ INITIAL CONCEPT REVISIONS FOR 2ND OUTREACH. (1 DESIGN) 1 8 1 10 1,235.00 $ FINAL CONCEPT REVISIONS FOR 3RD OUTREACH. (1 DESIGN) 1 8 1 10 1,235.00 $ PROJECT RESEARCH, UTILITY REVIEW AND COORDINATION 4 4 540.00 $ PRELIMINARY COST ESTIMATE 1 1 4 6 710.00 $
PROJECT TIMELINE ADJUSTMENTS, FOR EACH PHASE W/ COST) 4 4 540.00 $ TOTALS 0 1 21 32 14 0 68 16,626.00 $
687
Ironwood Park
TASK III. CONSTRUCTION DOCUMENTS PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS
COST PER
TASK
TITLE SHEET/PROJECT INFO. 1 3 4 435.00 $
CONSTRUCTION DOCUMENT BASE SHEET PREP. 1 3 4 435.00 $
DEMOLITION PLAN 4 12 16 1,740.00 $
GRADING MARK UP COORDINATION 3 3 6 930.00 $
CONSTRUCTION PLAN (8 HRS/SHT) 6 14 20 2,210.00 $
CONSTRUCTION AND GRADING DETAILS (including rubber layout) 4 8 12 1,340.00 $ CONSTRUCTION SPECIFICATIONS (BOOK) 1 3 4 580.00 $
COST ESTIMATE (FINAL) 1 4 5 535.00 $
MATERIAL / FURNISHING SELECTION 1 2 3 385.00 $
PACKAGE COORDINATION 2 2 270.00 $
PLAN CHECKING (15 MINUTES A SHEET) 5-8 ANTICIPATED 4 2 10 16 1,970.00 $ PROJECT ADMINISTRATION & TELEPHONE CONSULTATION 4 4 540.00 $ CONSULTANT COORDINATION 43 43 5,805.00 $
MADOLE & ASSOCIATES (CIVIL) Grading & Specs ALLOW 5,816.00 $ JCA (ELECTRICAL ENGINEER) Lighting Plan and Building Electric ALLOW 11,500.00 $ GEOTEK (GEOTECHNICAL) ALLOW 18,267.00 $
Cal Waters Construction Document Assistance ALLOW 22,500.00 $ TOTALS 0 8 75 2 54 0 139 75,258.00 $
TASK IV. BIDDING AND CONSTRUCTION SUPPORT PRINCIPAL DIRECTOR
PROJECT
MANAGER DESIGNER CAD CLERICAL
TOTAL
HOURS
COST PER
TASK
ANSWER RFI'S DURING ADVERTISEMENT PERIOD 4 4 540.00 $
PREPARE PROJECT ADDENDA FOR CITY (ASSUME 2) 4 4 540.00 $ CONSTRUCTION OBSERVATION (ASSUME 3 @ 3.5 HOURS EACH) 10 10 1,350.00 $ PREPARATION OF SITE REVIEW REPORTS ( ASSUME 3) 3 3 405.00 $ ANSWER RFI'S AFTER CONSTRUCTION BID AWARD 4 4 540.00 $
SUBMITTAL REVIEW 4 4 540.00 $
SHOP DRAWING REVIEW 4 4 540.00 $
Cal Waters Bidding and Construction Support ALLOW 3,000.00 $ CONSULTANT COORDINATION 2 2 270.00 $
TOTALS 0 0 35 0 0 0 35 7,725.00 $
PROFESSIONAL SERVICES TOTAL 117,799.00 $
ESTIMATED REIMBURSABLE ALLOWANCE (STATE REQUIRED THIRD-PARTY SOIL TESTING, IRS MILEAGE FOR SITE VISITS) 1,500.00 $ GRAND TOTAL 119,299.00 $
TEAM
ARCHITERRA (LANDSCAPE ARCHITECT) 48,500.00 $
MADOLE (CIVIL ENGINEER) 12,032.00 $
JCA (ELECTRICAL ENGINEER) 11,500.00 $
GEOTEK (GEOTECHNICAL ENGINEER) 18,267.00 $
CAL WATERS (SPLASH PAD CONSULTANT) 27,500.00 $
TOTAL 117,799.00 $
688
807 S. Lemon Ave, Diamond Bar, CA 91789
tel: 909.895-7146 • fax: 909.859.3881 • www.agi.com.co
HOURLY RATE SCHEDULE
Avant-Garde offers the following hourly rates for all services proposed under this RFQ.
Effective through June 30, 2027
Program Director............................................$150 Program Manager......................................... $135 Senior Program Coordinator......................... $125 Program Coordinator..................................... $110 Program Assistant......................................... $100 Effective through June 30, 2029
Program Director........................................... $158 Program Manager......................................... $142 Senior Program Coordinator......................... $131 Program Coordinator..................................... $115 Program Assistant......................................... $105 689
Page | 1
SENT VIA EMAIL TO: [email protected] March 12, 2025
Andrew Krumwiede
ARCHITERRA DESIGN GROUP
10221-A Trademark Street
Rancho Cucamonga, CA 91730
ENGINEERING & SURVEY PROPOSAL
Hommes Adams Park (Trailhead) - Palm Desert, CA
Dear Drew:
Madole and Associates, Inc. are pleased to submit this fixed fee proposal in the amount of $27,026.00 for civil engineering at the above-referenced park located in Palm Desert, California. Our proposed scope of work and compensation schedule are as follows:
SCOPE OF WORK:
Task 4000: Aerial Topographic Survey: Provide a topographic survey of the project site with one (1)- foot contour, and physical features will be illustrated from an aerial topographic survey. Spot elevations of hardscape, sidewalks, and curbs, along with locations of utility appurtenances, will be obtained from a conventional survey. Topography and color orthophoto, along with property lines of the project site will be provided in AutoCAD format. FEE: $10,450.00 Task 0530: WQMP: Prepare and process a Water Quality Management Plan (WQMP). FEE: $7,440.00 Task 1100: Precise Grading Plan: Prepare 60%, 90%, and 100% submittal precise grading documents for additional parking and trailhead improvements and ADA compliance improvements within the project site. FEE: $9,136.00
Fees are based on the rates outlined in our standard billing rate schedule, provided as Exhibit “A.” Hourly-based fees are estimates only; you will be billed based on the actual time spent.
We appreciate the opportunity to prepare this proposal for you. Please do not hesitate to call if you have questions or need clarification.
Sincerely,
Mark Bertone, President
690
Page | 2
EXHIBIT “A”
STANDARD BILLING RATE SCHEDULE
OFFICE TECHNICAL PERSONNEL:
PRINCIPAL $ 250.00 PER HOUR
PROJECT MANAGER $ 208.00 PER HOUR
DESIGNER $ 186.00 PER HOUR
DRAFTER $ 166.00 PER HOUR
FIELD:
TWO (2) MAN SURVEY CREW $ 340.00 PER HOUR
ONE (1) MAN SURVEY $ 208.00 PER HOUR
TWO (2) MAN TRAVEL TIME RATE $ 252.00 PER HOUR
ONE (1) MAN TRAVEL TIME RATE $ 126.00 PER HOUR
ADDITIONAL SERVICES:
Additional office engineering tasks not specifically outlined in this proposal require a change order.
Survey field time for all extra work will be billed in 4,6, and 8-hour increments and may incur travel time.
OUTSIDE SERVICES:
CLIENT shall pay the costs of all agency fees, permits, bond premiums, title company charges, delivery charges, blueprints and reproductions, and all other outside charges and expenses.
REIMBURSABLE EXPENSES: The following costs shall be reimbursed at the cost invoiced to us plus 15% and are not included in the hourly rates for services:
• Expense of reproductions for generation of original drawings, plan check submittals, and construction bidding, including printing, plotting, copying, and photo reproduction. • Cost of shipping expenses other than first class mail. 691
Page | 1
SENT VIA EMAIL TO: [email protected] March 12, 2025
Andrew Krumwiede
ARCHITERRA DESIGN GROUP
10221-A Trademark Street
Rancho Cucamonga, CA 91730
ENGINEERING & SURVEY PROPOSAL
University Park - Palm Desert, CA
Dear Drew:
Madole and Associates, Inc. is pleased to submit this fixed fee proposal in the amount of $12,696.00 for civil engineering at the above-referenced park located in Palm Desert, California. Our proposed scope of work and compensation schedule are as follows:
SCOPE OF WORK:
Task 4000: Aerial Topographic Survey: Provide a topographic survey of the project site with one (1)- foot contour, and physical features will be illustrated from an aerial topographic survey. Spot elevations of hardscape, sidewalks, and curbs, along with locations of utility appurtenances, will be obtained from a conventional survey. Topography and color orthophoto, along with property lines of the project site, will be provided in AutoCAD format. FEE: $6,216.00 Task 1100: Precise Grading Plan: Prepare 60%, 90%, and 100% submittal precise grading documents for playground improvements and ADA compliance improvements within the project site.
FEE: $6,480.00
Fees are based on the rates outlined in our standard billing rate schedule, provided as Exhibit “A.” Hourly-based fees are estimates only; you will be billed based on the actual time spent.
We appreciate the opportunity to prepare this proposal for you. Please do not hesitate to call if you have questions or need clarification.
Sincerely,
Mark Bertone, President
692
Page | 2
EXHIBIT “A”
STANDARD BILLING RATE SCHEDULE
OFFICE TECHNICAL PERSONNEL:
PRINCIPAL $ 250.00 PER HOUR
PROJECT MANAGER $ 208.00 PER HOUR
DESIGNER $ 186.00 PER HOUR
DRAFTER $ 166.00 PER HOUR
FIELD:
TWO (2) MAN SURVEY CREW $ 340.00 PER HOUR
ONE (1) MAN SURVEY $ 208.00 PER HOUR
TWO (2) MAN TRAVEL TIME RATE $ 252.00 PER HOUR
ONE (1) MAN TRAVEL TIME RATE $ 126.00 PER HOUR
ADDITIONAL SERVICES:
Additional office engineering tasks not specifically outlined in this proposal require a change order.
Survey field time for all extra work will be billed in 4,6, and 8-hour increments and may incur travel time.
OUTSIDE SERVICES:
CLIENT shall pay the costs of all agency fees, permits, bond premiums, title company charges, delivery charges, blueprints and reproductions, and all other outside charges and expenses.
REIMBURSABLE EXPENSES: The following costs shall be reimbursed at the cost invoiced to us plus 15% and are not included in the hourly rates for services:
• Expense of reproductions for generation of original drawings, plan check submittals, and construction bidding, including printing, plotting, copying, and photo reproduction. • Cost of shipping expenses other than first class mail. 693
Page | 1
SENT VIA EMAIL TO: [email protected] March 12, 2025
Andrew Krumwiede
ARCHITERRA DESIGN GROUP
10221-A Trademark Street
Rancho Cucamonga, CA 91730
ENGINEERING & SURVEY PROPOSAL
Washington Charter Park - Palm Desert, CA
Dear Drew:
Madole and Associates, Inc. are pleased to submit this fixed fee proposal in the amount of $22,128.00 for civil engineering at the above-referenced park located in Palm Desert, California. Our proposed scope of work and compensation schedule are as follows:
SCOPE OF WORK:
Task 4000: Aerial Topographic Survey: Provide a topographic survey of the project site with one (1)- foot contour, and physical features will be illustrated from an aerial topographic survey. Spot elevations of hardscape, sidewalks, and curbs, along with locations of utility appurtenances, will be obtained from a conventional survey. Topography and color orthophoto, along with property lines of the project site will be provided in AutoCAD format. FEE: $6,880.00 Task 0530: WQMP: Prepare and process a Water Quality Management Plan (WQMP). FEE: $7,440.00 Task 1100: Precise Grading Plan: Prepare 60%, 90%, and 100% submittal precise grading documents for additional playground improvements and ADA compliance improvements within the project site. FEE: $7,808.00
Fees are based on the rates outlined in our standard billing rate schedule, provided as Exhibit “A.” Hourly-based fees are estimates only; you will be billed based on the actual time spent.
We appreciate the opportunity to prepare this proposal for you. Please do not hesitate to call if you have questions or need clarification.
Sincerely,
Mark Bertone, President
694
Page | 2
EXHIBIT “A”
STANDARD BILLING RATE SCHEDULE
OFFICE TECHNICAL PERSONNEL:
PRINCIPAL $ 250.00 PER HOUR
PROJECT MANAGER $ 208.00 PER HOUR
DESIGNER $ 186.00 PER HOUR
DRAFTER $ 166.00 PER HOUR
FIELD:
TWO (2) MAN SURVEY CREW $ 340.00 PER HOUR
ONE (1) MAN SURVEY $ 208.00 PER HOUR
TWO (2) MAN TRAVEL TIME RATE $ 252.00 PER HOUR
ONE (1) MAN TRAVEL TIME RATE $ 126.00 PER HOUR
ADDITIONAL SERVICES:
Additional office engineering tasks not specifically outlined in this proposal require a change order.
Survey field time for all extra work will be billed in 4,6, and 8-hour increments and may incur travel time.
OUTSIDE SERVICES:
CLIENT shall pay the costs of all agency fees, permits, bond premiums, title company charges, delivery charges, blueprints and reproductions, and all other outside charges and expenses.
REIMBURSABLE EXPENSES: The following costs shall be reimbursed at the cost invoiced to us plus 15% and are not included in the hourly rates for services:
• Expense of reproductions for generation of original drawings, plan check submittals, and construction bidding, including printing, plotting, copying, and photo reproduction. • Cost of shipping expenses other than first class mail. 695
Page | 1
SENT VIA EMAIL TO: [email protected] March 12, 2025
Andrew Krumwiede
ARCHITERRA DESIGN GROUP
10221-A Trademark Street
Rancho Cucamonga, CA 91730
ENGINEERING & SURVEY PROPOSAL
Randall Henderson Trailhead - Palm Desert, CA
Dear Drew:
Madole and Associates, Inc. are pleased to submit this fixed fee proposal in the amount of $27,940.00 for civil engineering at the above-referenced park located in Palm Desert, California. Our proposed scope of work and compensation schedule are as follows:
SCOPE OF WORK:
Task 4000: Aerial Topographic Survey: Provide a topographic survey of the project site with one (1)- foot contour, and physical features will be illustrated from an aerial topographic survey. Spot elevations of hardscape, sidewalks, and curbs, along with locations of utility appurtenances, will be obtained from a conventional survey. Topography and color orthophoto, along with property lines of the project site will be provided in AutoCAD format. FEE: $10,200.00 Task 0530: WQMP: Prepare and process a Water Quality Management Plan (WQMP). FEE: $7,440.00 Task 1100: Precise Grading Plan: Prepare 60%, 90%, and 100% submittal precise grading documents for additional parking and restroom improvements, and ADA compliance improvements within the project site. FEE: $10,300.00
Fees are based on the rates outlined in our standard billing rate schedule, provided as Exhibit “A.” Hourly-based fees are estimates only; you will be billed based on the actual time spent.
We appreciate the opportunity to prepare this proposal for you. Please do not hesitate to call if you have questions or need clarification.
Sincerely,
Mark Bertone, President
696
Page | 2
EXHIBIT “A”
STANDARD BILLING RATE SCHEDULE
OFFICE TECHNICAL PERSONNEL:
PRINCIPAL $ 250.00 PER HOUR
PROJECT MANAGER $ 208.00 PER HOUR
DESIGNER $ 186.00 PER HOUR
DRAFTER $ 166.00 PER HOUR
FIELD:
TWO (2) MAN SURVEY CREW $ 340.00 PER HOUR
ONE (1) MAN SURVEY $ 208.00 PER HOUR
TWO (2) MAN TRAVEL TIME RATE $ 252.00 PER HOUR
ONE (1) MAN TRAVEL TIME RATE $ 126.00 PER HOUR
ADDITIONAL SERVICES:
Additional office engineering tasks not specifically outlined in this proposal require a change order.
Survey field time for all extra work will be billed in 4,6, and 8-hour increments and may incur travel time.
OUTSIDE SERVICES:
CLIENT shall pay the costs of all agency fees, permits, bond premiums, title company charges, delivery charges, blueprints and reproductions, and all other outside charges and expenses.
REIMBURSABLE EXPENSES: The following costs shall be reimbursed at the cost invoiced to us plus 15% and are not included in the hourly rates for services:
• Expense of reproductions for generation of original drawings, plan check submittals, and construction bidding, including printing, plotting, copying, and photo reproduction. • Cost of shipping expenses other than first class mail. 697
Page | 1
SENT VIA EMAIL TO: [email protected] March 12, 2025
Andrew Krumwiede
ARCHITERRA DESIGN GROUP
10221-A Trademark Street
Rancho Cucamonga, CA 91730
ENGINEERING & SURVEY PROPOSAL
Freedom Park - Palm Desert, CA
Dear Drew:
Madole and Associates, Inc. is pleased to submit this fixed fee proposal in the amount of $12,696.00 for civil engineering at the above-referenced park located in Palm Desert, California. Our proposed scope of work and compensation schedule are as follows:
SCOPE OF WORK:
Task 4000: Aerial Topographic Survey: Provide a topographic survey of the project site with one (1)- foot contour, and physical features will be illustrated from an aerial topographic survey. Spot elevations of hardscape, sidewalks, and curbs, along with locations of utility appurtenances, will be obtained from a conventional survey. Topography and color orthophoto, along with property lines of the project site, will be provided in AutoCAD format. FEE: $6,880.00 Task 1100: Precise Grading Plan: Prepare 60%, 90%, and 100% submittal precise grading documents for playground improvements and ADA compliance improvements within the project site.
FEE: $5,816.00
Fees are based on the rates outlined in our standard billing rate schedule, provided as Exhibit “A.” Hourly-based fees are estimates only; you will be billed based on the actual time spent.
We appreciate the opportunity to prepare this proposal for you. Please do not hesitate to call if you have questions or need clarification.
Sincerely,
Mark Bertone, President
698
Page | 2
EXHIBIT “A”
STANDARD BILLING RATE SCHEDULE
OFFICE TECHNICAL PERSONNEL:
PRINCIPAL $ 250.00 PER HOUR
PROJECT MANAGER $ 208.00 PER HOUR
DESIGNER $ 186.00 PER HOUR
DRAFTER $ 166.00 PER HOUR
FIELD:
TWO (2) MAN SURVEY CREW $ 340.00 PER HOUR
ONE (1) MAN SURVEY $ 208.00 PER HOUR
TWO (2) MAN TRAVEL TIME RATE $ 252.00 PER HOUR
ONE (1) MAN TRAVEL TIME RATE $ 126.00 PER HOUR
ADDITIONAL SERVICES:
Additional office engineering tasks not specifically outlined in this proposal require a change order.
Survey field time for all extra work will be billed in 4,6, and 8-hour increments and may incur travel time.
OUTSIDE SERVICES:
CLIENT shall pay the costs of all agency fees, permits, bond premiums, title company charges, delivery charges, blueprints and reproductions, and all other outside charges and expenses.
REIMBURSABLE EXPENSES: The following costs shall be reimbursed at the cost invoiced to us plus 15% and are not included in the hourly rates for services:
• Expense of reproductions for generation of original drawings, plan check submittals, and construction bidding, including printing, plotting, copying, and photo reproduction. • Cost of shipping expenses other than first class mail. 699
Page | 1
SENT VIA EMAIL TO: [email protected] March 12, 2025
Andrew Krumwiede
ARCHITERRA DESIGN GROUP
10221-A Trademark Street
Rancho Cucamonga, CA 91730
ENGINEERING & SURVEY PROPOSAL
Ironwood Park - Palm Desert, CA
Dear Drew:
Madole and Associates, Inc. is pleased to submit this fixed fee proposal in the amount of $12,032.00 for civil engineering at the above-referenced park located in Palm Desert, California. Our proposed scope of work and compensation schedule are as follows:
SCOPE OF WORK:
Task 4000: Aerial Topographic Survey: Provide a topographic survey of the project site with one (1)- foot contour, and physical features will be illustrated from an aerial topographic survey. Spot elevations of hardscape, sidewalks, and curbs, along with locations of utility appurtenances, will be obtained from a conventional survey. Topography and color orthophoto, along with property lines of the project site, will be provided in AutoCAD format. FEE: $6,216.00 Task 1100: Precise Grading Plan: Prepare 60%, 90%, and 100% submittal precise grading documents for additional park improvements and ADA compliance improvements within the project site.
FEE: $5,816.00
Fees are based on the rates outlined in our standard billing rate schedule, provided as Exhibit “A.” Hourly-based fees are estimates only; you will be billed based on the actual time spent.
We appreciate the opportunity to prepare this proposal for you. Please do not hesitate to call if you have questions or need clarification.
Sincerely,
Mark Bertone, President
700
Page | 2
EXHIBIT “A”
STANDARD BILLING RATE SCHEDULE
OFFICE TECHNICAL PERSONNEL:
PRINCIPAL $ 250.00 PER HOUR
PROJECT MANAGER $ 208.00 PER HOUR
DESIGNER $ 186.00 PER HOUR
DRAFTER $ 166.00 PER HOUR
FIELD:
TWO (2) MAN SURVEY CREW $ 340.00 PER HOUR
ONE (1) MAN SURVEY $ 208.00 PER HOUR
TWO (2) MAN TRAVEL TIME RATE $ 252.00 PER HOUR
ONE (1) MAN TRAVEL TIME RATE $ 126.00 PER HOUR
ADDITIONAL SERVICES:
Additional office engineering tasks not specifically outlined in this proposal require a change order.
Survey field time for all extra work will be billed in 4,6, and 8-hour increments and may incur travel time.
OUTSIDE SERVICES:
CLIENT shall pay the costs of all agency fees, permits, bond premiums, title company charges, delivery charges, blueprints and reproductions, and all other outside charges and expenses.
REIMBURSABLE EXPENSES: The following costs shall be reimbursed at the cost invoiced to us plus 15% and are not included in the hourly rates for services:
• Expense of reproductions for generation of original drawings, plan check submittals, and construction bidding, including printing, plotting, copying, and photo reproduction. • Cost of shipping expenses other than first class mail. 701
25-3138.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 1 8048 Palm Ave.
Highland, CA
92346
909.864.0223
Fax 909.864.0280
[email protected]
SERVICE AUTHORIZATION AND AGREEMENT
Date: 03/04/2025
Requested By: Andrew Krumwiede
Company: ARCHITERRA Design Group, Inc. JCA File # 25-3138.0
Address: 10221-A Trademark
Rancho Cucamonga, CA 91730
Telephone: (909) 484-2800
Fax: (909) 484-2802
Project Name: Homme Adams Park
Location: City of Palm Desert, California
Project Description: Provide Electrical Construction documents reflecting new metered service, new walkway lighting, new parking lot lighting and new shade structure power/lighting existing park.
This proposal is based on preliminary assumptions based on the current RFP, and may be subject to scope and fee adjustments once the final design is approved by the city.
FEE SCHEDULE:
For electrical engineering services per “Exhibit A” and “Exhibit B” attached made a part hereof Fixed Fee of Eighteen Thousand Nine Hundred Dollars ($ 18,900.00) for Electrical Engineering, Electrical Construction Documents and Electrical Document Support
CLIENT APPROVAL
Acceptance copy of this service authorization shall be signed and returned prior to commencement of work. The undersigned accepts the terms of this agreement, “Exhibit A-Scope of Services”, and “Exhibit B - Terms of Agreement for Engineering Services”, articles 1 through 10, attached as part hereof.
CLIENT
SIGNATURE:
DATE:
NAME
:
Client P.O. / Project #
NAME: James J. Corns FOR: JCA Engineering Inc.
CONSULTANT: DATE: 03/04/2025
Acknowledgment copy – Please sign and return
J Engineering Inc.
CA
Electrical Engineering & Consulting
702
25-3138.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 2 “EXHIBIT A”
SCOPE OF SERVICES
1. Design all new power system including main switchboard and distribution panels to meet minimum owner’s standards electrical requirements.
2. Provide all required paperwork and electronic files to Owner to submit to local power, telephone and cable utility companies for service requirements, new off-site point of connection and other requirements.
3. Design new security walkway lighting to meet all building codes presently adopted by the authority having jurisdiction.
4. Design new parking lot lighting to meet all building codes presently adopted by the authority having jurisdiction
5. Design general power/lighting for new shade shelters.
6. Design power connection to irrigation controller
7. Design power connection to pre-fabricated restroom building
8. Provide structural pole base calculations for parking lot and walkway light poles (maximum of two calculations)
9. Provide photometric illumination plan for parking lot and walkway, if required.
10. Provide exterior Title 24 calculations for parking lot and walkway, if required.
11. Provide revisions necessary as a part of Building Department review; submit construction documents for bid issue and construction.
12. Respond to requests for information.
13. Prepare any addenda as necessary.
14 Review all shop drawings relating to the electrical work for compliance with the construction documents.
15. Provide licensed California electrical engineer’s stamp and signature.
SERVICES NOT INCLUDED:
1. Soils testing and reports. Client shall provide to Consultant for use in structural calculations.
2. Design of new street lighting or structural pole base calculations.
3. Fees, submittals, processing or approval of electrical drawings with local Building Department.
4. Fabrication of electronic site plan, Client shall provide scaled electronic site plan.
5. Design of headend, active components, raceways, cabling, power outlets or devices for video surveillance, data, integrated communications, access control, site sound system, site/open covered arena annunciation system, open covered arena theatrical lighting system, video system, door locking or wireless Wi-Fi.
6. Design of Future Solar Power System headend, equipment, cabling, solar panels or connection to existing site main service.
703
25-3138.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 3 7. Design circuit breaker(s), connection and raceways for electric car charger(s) and future electric car charger(s).
8. Submittal, fees drawings, coordination and approved drawings from local power, telephone and cable utility company for new service. Per utility company standards there shall only be one contact person (Owner) for complete process. JCA to provide all electrical, telephone and cable information on forms, electrical PDF drawings and AutoCAD site plan for Owner’s submittal process
9. Control of timeline for power company designed drawings. Estimated timeline for utility company red line drawings is twelve to sixteen weeks. If project is to bid prior to arrival of utility company red lines JCA will design for the worst case.
10. Design of site low voltage raceways from certain poles to central location for future camera system 11 Design of 120 volt power distribution from new site sub-panel to poles with future cameras over 300’ from future camera system headend unit.
12. Design of new lighting or power for any other part of site
13. Design of remedial electrical work where existing conditions are in violation of California Electric Code. (C.E.C.)
14. Advertisement or hard copy sets for bidding purposes. Owner shall provide all advertising, bid sets and book specification, including fees, for bid.
15 Providing Boiler plate specifications or conducting bid process. Owner shall be responsible for all bid items.
17. Design of special event, equipment or dedicated power for new covered open arena
18. Provide interior Title 24 calculations for new building, if required. “EXHIBIT B”
TERMS OF AGREEMENT FOR ENGINEERING SERVICE
Article 1 BASIC SERVICES
1.1 Consultant shall coordinate with Client with respect to the Consultant's services in such a way that Consultant's duties and responsibilities shall be co-extensive with those of Client.
Consultant shall perform his services in character, sequence, and timing so that they will be coordinated with services of Client and other Consultants for the project. Consultant’s services will proceed after adequate base sheets and/or Client furnishes other information necessary. The Consultant's services shall conform to the original schedule and budget for the project as provided by the Client. The relationship of Consultant to the Client shall be that of an independent contractor performing professional services for Client in accordance with this Agreement.
1.2 Consultant shall comply with all Electrical Building Department rules and regulations that will affect this design on this project.
1.3 Consultant shall provide a complete set of design documents including all schedules, details, diagrams, legends and specifications (if required). Consultant shall furnish at his client all progress prints and specifications required.
1.4 Consultant shall review all electrically related shop drawings as submitted by the Electrical Contractor to ensure compliance with specifications.
1.5 Consultant shall perform the services as set forth on "Exhibit A", attached. 704
25-3138.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 4 Article 2 DOCUMENT SUPPORT
2.1 Document support shall include Building Department or Division of State Architects review changes, Building Department or Division of State Architects responses and request for information during bid.
2.2 Document support shall be considered as part of the contract, if required, regardless of the extensiveness of support required on the project.
Article 3 WORK NOT INCLUDED / EXTRA SERVICES
3.1 All Building Department Fees: Consultant shall provide drawings as required to submit electrical construction documents for the Building Department plan check. Client shall pay all Building Department fees.
3.2 Printing: Client shall furnish at his expense information and progress prints of the work required for this project. Prints required by reviewing agencies. Documents required for bidding and construction shall be paid for by Client or Consultant shall pay for blueprinting and Client will reimburse. Client shall pay for final prints and specifications furnished to Consultant. Mylar final prints shall be paid for by Client or Consultant shall pay and Client will reimburse. Reimbursable invoice for additional prints shall include blueprint cost, plus 15% for any applicable governmental fees, outside vender reproduction cost, in house reproduction costs, mileage and delivery or messenger services incurred on client’s behalf
3.3 Additional work/revisions: No additional services shall be performed without written direction from Client. Consultant shall be paid by Client for any additional work resulting from changes or revisions made by the Client or Project Owner and also for any additional work not specifically mentioned in Articles 1 and 2 above, as provided in paragraph 5.1.
Article 4 COMPENSATION
4.1 Client shall pay Consultant amount stated in “FEE SCHEDULE”, page 1.
4.2 Client shall pay Consultant for Article 3 "Work Not Included/Extra Services/Construction Support" for changes or revisions per paragraph 3.3 at the hourly rates as set forth in paragraph 4.3.
4.3 For the purposes of hourly services and/or revisions for the basic services, the Consultant shall invoice the Client at the following rates:
Project Engineer/Manager $ 230.00
Designer $ 180.00
Drafting/CADD $ 165.00
Clerical/Delivery/Accounting $ 150.00
These hourly rates shall be adjusted annually based on increases in product cost, the cost of living and fuel prices.
Article 5 INVOICE AND PAYMENTS
5.1 At Design Development submittal Design Development Documents shall be considered 100%. Consultant shall tender an 100% invoice to Client setting forth all amounts due.
5.2 At Building Department or Division of State Architects submittal Construction Documents shall be considered 80%. Consultant shall tender an 80% invoice to Client setting forth all amounts due. Client shall completely pay 80% invoice prior to final building department or division of state architects submittal or electrical drawings will not be stamped or wet signed
5.3 When project is approved by the Building Department, Division of State Architects or published for bid the Electrical Construction Documents shall be considered 100%.
Consultant shall tender a 20% invoice (Total amount for Construction Documents 100%) to Client setting forth all amounts due.
5.4 During design and construction phase Consultant shall tender an invoice to Client setting forth the amounts due for Construction Administration and reimbursable expenses. 705
25-3138.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 5 5.5 Projects that do not require Construction Administration shall not be invoiced.
5.6 At completion of project Client shall provide written notification to Consultant when they are doing final billings to Owner. Closing out project without written notification to Consultant does not relieve Client of complete payment of all amounts. After notification Consultant shall tender an invoice to Client setting forth the final amounts due for Construction Administration and reimbursable expenses, as required.
5.7 Client shall pay to consultant the total amount due under invoice within thirty days after receipt of invoice, or within five (5) days of receiving payment from owner (if other than client) whichever date occurs first. Client shall pay a service charge of 1.50% per month on all unpaid balances. Consultant may suspend all work on the project when accounts are over 60 days delinquent.
Article 6 ABANDONMENT
In the event the project is abandoned, Client shall advise immediately by written notice, Consultant to stop work. Client shall pay consultant for all outstanding invoices for service performed and for services completed at that time on the project. Work shall be suspended until Client advises Consultant in writing to continue work.
Article 7 ELECTRICAL DOCUMENTS
7.1 All electronic files, drawings and copies furnished by JCA Engineering Inc. are and shall remain its property. They are to be used only with respect to the above-mentioned project and are not to be used on any other project. Submission or distribution to meet official regulatory requirements or for other purposes in connection with this project is not to be construed as publication in derogation of JCA Engineering Inc. common law copyright or other reserved rights.
7.2 Client agrees not to make changes to any of the Consultants documents without Consultants written agreement.
7.3 Electrical plans are diagrammatic only. Architectural drawings, elevations, details or sections shall denote all electrical devices locations that need exact mounting requirements.
7.4 Upon request Consultant shall provide the Client with electronic files after all fees have been completely paid and JCA’s affidavit has been signed and returned. Time required to process request will be billed to Owner or Client at the above hourly rates.
7.5 Electrical design on documents is guaranteed for a 180 day period. Projects that have not started construction prior to the guarantee period shall be subject to additional electrical fees to investigate and change any items on the drawings related to the current electrical and fire code at that time.
Article 8 SCOPE OF AGREEMENT AND ACCEPTANCE
8.1 This document contains the entire agreement of the parties relating to the rights granted and obligations assumed in this document. Any oral modifications or representations concerning this document shall be of no effect unless contained in a subsequent written modification signed by the party to be charged.
8.2 The electrical fees shown above shall be reviewed and adjusted if the project has not commenced within 180 days of signing of this contract.
Article 9 INSURANCE
Each party to this Agreement shall carry and maintain insurance to protect him from claims arising out of the performance of his professional services caused by the acts, errors or omissions of each party's legally responsible.
706
25-3138.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 6 Article 10 ARBITRATION
All questions in dispute under this Agreement shall be submitted to arbitration in accordance with the provision of the Construction Industry rules of the American Arbitration Association. Consultant cannot be sued for a greater amount than the fee. The prevailing party shall be entitled to reasonable attorney's fees to be awarded by the Arbitrator. If there are judicial proceedings instead of arbitration, reasonable attorney's fees shall be fixed by the court.
END OF DOCUMENT
707
25-3139.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 1 8048 Palm Ave.
Highland, CA
92346
909.864.0223
Fax 909.864.0280
[email protected]
SERVICE AUTHORIZATION AND AGREEMENT
Date: 03/04/2025
Requested By: Andrew Krumwiede
Company: ARCHITERRA Design Group, Inc. JCA File # 25-3139.0
Address: 10221-A Trademark
Rancho Cucamonga, CA 91730
Telephone: (909) 484-2800
Fax: (909) 484-2802
Project Name: University Park
Location: City of Palm Desert, California
Project Description: Provide Electrical Construction documents reflecting new walkway lighting and new playground lighting at existing park.
This proposal is based on preliminary assumptions based on the current RFP, and may be subject to scope and fee adjustments once the final design is approved by the city.
FEE SCHEDULE:
For electrical engineering services per “Exhibit A” and “Exhibit B” attached made a part hereof Fixed Fee of Nine Thousand Seven Hundred Dollars ($ 9,700.00) for Electrical Engineering, Electrical Construction Documents and Electrical Document Support
CLIENT APPROVAL
Acceptance copy of this service authorization shall be signed and returned prior to commencement of work. The undersigned accepts the terms of this agreement, “Exhibit A-Scope of Services”, and “Exhibit B - Terms of Agreement for Engineering Services”, articles 1 through 10, attached as part hereof.
CLIENT
SIGNATURE:
DATE:
NAME
:
Client P.O. / Project #
NAME: James J. Corns FOR: JCA Engineering Inc.
CONSULTANT: DATE: 03/04/2025
Acknowledgment copy – Please sign and return
J Engineering Inc.
CA
Electrical Engineering & Consulting
708
25-3139.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 2 “EXHIBIT A”
SCOPE OF SERVICES
1. Provide one site visit during design phase for investigation and documentation of existing conditions, as required
2. Design of power distribution from existing service and sub-panels to each new light fixture including electrical controls.
3. Design new security walkway lighting to meet all building codes presently adopted by the authority having jurisdiction.
4. Design new playground lighting (same light fixture as walkway) to meet all building codes presently adopted by the authority having jurisdiction
5. Design power connection to irrigation controller
7. Provide structural pole base calculations for walkway/playground light pole (maximum of one calculations)
8. Provide photometric illumination plan for walkway and playground, if required.
9. Provide exterior Title 24 calculations for walkway and playground, if required.
10. Provide revisions necessary as a part of Building Department review; submit construction documents for bid issue and construction.
11. Respond to requests for information.
12. Prepare any addenda as necessary.
13 Review all shop drawings relating to the electrical work for compliance with the construction documents.
14. Provide licensed California electrical engineer’s stamp and signature.
SERVICES NOT INCLUDED:
1. Soils testing and reports. Client shall provide to Consultant for use in structural calculations.
2. Design of new street lighting or structural pole base calculations.
3. Fees, submittals, processing or approval of electrical drawings with local Building Department.
4. Fabrication of electronic site plan, Client shall provide scaled electronic site plan.
5. Design of headend, active components, raceways, cabling, power outlets or devices for video surveillance, data, integrated communications, access control, site sound system, site/open covered arena annunciation system, open covered arena theatrical lighting system, video system, door locking or wireless Wi-Fi.
6. Design of Future Solar Power System headend, equipment, cabling, solar panels or connection to existing site main service.
7. Design circuit breaker(s), connection and raceways for electric car charger(s) and future electric car charger(s).
8. Design of new site electrical metered service if existing is inadequate to handle new loads 709
25-3139.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 3 9. Design site low voltage raceways from certain poles to central location for future camera system 10 Design of 120 volt power distribution from new site sub-panel to poles with future cameras over 300’ from future camera system headend unit.
11. Design general power/lighting for covered shelters
12. Design of new lighting or power for any other part of site
13. Design of remedial electrical work where existing conditions are in violation of California Electric Code. (C.E.C.)
14. Advertisement or hard copy sets for bidding purposes. Owner shall provide all advertising, bid sets and book specification, including fees, for bid.
15 Providing Boiler plate specifications or conducting bid process. Owner shall be responsible for all bid items.
16. Electrical Construction Administration
“EXHIBIT B”
TERMS OF AGREEMENT FOR ENGINEERING SERVICE
Article 1 BASIC SERVICES
1.1 Consultant shall coordinate with Client with respect to the Consultant's services in such a way that Consultant's duties and responsibilities shall be co-extensive with those of Client.
Consultant shall perform his services in character, sequence, and timing so that they will be coordinated with services of Client and other Consultants for the project. Consultant’s services will proceed after adequate base sheets and/or Client furnishes other information necessary. The Consultant's services shall conform to the original schedule and budget for the project as provided by the Client. The relationship of Consultant to the Client shall be that of an independent contractor performing professional services for Client in accordance with this Agreement.
1.2 Consultant shall comply with all Electrical Building Department rules and regulations that will affect this design on this project.
1.3 Consultant shall provide a complete set of design documents including all schedules, details, diagrams, legends and specifications (if required). Consultant shall furnish at his client all progress prints and specifications required.
1.4 Consultant shall review all electrically related shop drawings as submitted by the Electrical Contractor to ensure compliance with specifications.
1.5 Consultant shall perform the services as set forth on "Exhibit A", attached.
Article 2 DOCUMENT SUPPORT
2.1 Document support shall include Building Department or Division of State Architects review changes, Building Department or Division of State Architects responses and request for information during bid.
2.2 Document support shall be considered as part of the contract, if required, regardless of the extensiveness of support required on the project.
710
25-3139.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 4 Article 3 WORK NOT INCLUDED / EXTRA SERVICES
3.1 All Building Department Fees: Consultant shall provide drawings as required to submit electrical construction documents for the Building Department plan check. Client shall pay all Building Department fees.
3.2 Printing: Client shall furnish at his expense information and progress prints of the work required for this project. Prints required by reviewing agencies. Documents required for bidding and construction shall be paid for by Client or Consultant shall pay for blueprinting and Client will reimburse. Client shall pay for final prints and specifications furnished to Consultant. Mylar final prints shall be paid for by Client or Consultant shall pay and Client will reimburse. Reimbursable invoice for additional prints shall include blueprint cost, plus 15% for any applicable governmental fees, outside vender reproduction cost, in house reproduction costs, mileage and delivery or messenger services incurred on client’s behalf
3.3 Additional work/revisions: No additional services shall be performed without written direction from Client. Consultant shall be paid by Client for any additional work resulting from changes or revisions made by the Client or Project Owner and also for any additional work not specifically mentioned in Articles 1 and 2 above, as provided in paragraph 5.1.
Article 4 COMPENSATION
4.1 Client shall pay Consultant amount stated in “FEE SCHEDULE”, page 1.
4.2 Client shall pay Consultant for Article 3 "Work Not Included/Extra Services/Construction Support" for changes or revisions per paragraph 3.3 at the hourly rates as set forth in paragraph 4.3.
4.3 For the purposes of hourly services and/or revisions for the basic services, the Consultant shall invoice the Client at the following rates:
Project Engineer/Manager $ 230.00
Designer $ 180.00
Drafting/CADD $ 165.00
Clerical/Delivery/Accounting $ 150.00
These hourly rates shall be adjusted annually based on increases in product cost, the cost of living and fuel prices.
Article 5 INVOICE AND PAYMENTS
5.1 At Design Development submittal Design Development Documents shall be considered 100%. Consultant shall tender an 100% invoice to Client setting forth all amounts due.
5.2 At Building Department or Division of State Architects submittal Construction Documents shall be considered 80%. Consultant shall tender an 80% invoice to Client setting forth all amounts due. Client shall completely pay 80% invoice prior to final building department or division of state architects submittal or electrical drawings will not be stamped or wet signed
5.3 When project is approved by the Building Department, Division of State Architects or published for bid the Electrical Construction Documents shall be considered 100%.
Consultant shall tender a 20% invoice (Total amount for Construction Documents 100%) to Client setting forth all amounts due.
5.4 During design and construction phase Consultant shall tender an invoice to Client setting forth the amounts due for Construction Administration and reimbursable expenses.
5.5 Projects that do not require Construction Administration shall not be invoiced.
5.6 At completion of project Client shall provide written notification to Consultant when they are doing final billings to Owner. Closing out project without written notification to Consultant does not relieve Client of complete payment of all amounts. After notification Consultant shall tender an invoice to Client setting forth the final amounts due for Construction Administration and reimbursable expenses, as required.
711
25-3139.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 5 5.7 Client shall pay to consultant the total amount due under invoice within thirty days after receipt of invoice, or within five (5) days of receiving payment from owner (if other than client) whichever date occurs first. Client shall pay a service charge of 1.50% per month on all unpaid balances. Consultant may suspend all work on the project when accounts are over 60 days delinquent.
Article 6 ABANDONMENT
In the event the project is abandoned, Client shall advise immediately by written notice, Consultant to stop work. Client shall pay consultant for all outstanding invoices for service performed and for services completed at that time on the project. Work shall be suspended until Client advises Consultant in writing to continue work.
Article 7 ELECTRICAL DOCUMENTS
7.1 All electronic files, drawings and copies furnished by JCA Engineering Inc. are and shall remain its property. They are to be used only with respect to the above-mentioned project and are not to be used on any other project. Submission or distribution to meet official regulatory requirements or for other purposes in connection with this project is not to be construed as publication in derogation of JCA Engineering Inc. common law copyright or other reserved rights.
7.2 Client agrees not to make changes to any of the Consultants documents without Consultants written agreement.
7.3 Electrical plans are diagrammatic only. Architectural drawings, elevations, details or sections shall denote all electrical devices locations that need exact mounting requirements.
7.4 Upon request Consultant shall provide the Client with electronic files after all fees have been completely paid and JCA’s affidavit has been signed and returned. Time required to process request will be billed to Owner or Client at the above hourly rates.
7.5 Electrical design on documents is guaranteed for a 180 day period. Projects that have not started construction prior to the guarantee period shall be subject to additional electrical fees to investigate and change any items on the drawings related to the current electrical and fire code at that time.
Article 8 SCOPE OF AGREEMENT AND ACCEPTANCE
8.1 This document contains the entire agreement of the parties relating to the rights granted and obligations assumed in this document. Any oral modifications or representations concerning this document shall be of no effect unless contained in a subsequent written modification signed by the party to be charged.
8.2 The electrical fees shown above shall be reviewed and adjusted if the project has not commenced within 180 days of signing of this contract.
Article 9 INSURANCE
Each party to this Agreement shall carry and maintain insurance to protect him from claims arising out of the performance of his professional services caused by the acts, errors or omissions of each party's legally responsible.
Article 10 ARBITRATION
All questions in dispute under this Agreement shall be submitted to arbitration in accordance with the provision of the Construction Industry rules of the American Arbitration Association. Consultant cannot be sued for a greater amount than the fee. The prevailing party shall be entitled to reasonable attorney's fees to be awarded by the Arbitrator. If there are judicial proceedings instead of arbitration, reasonable attorney's fees shall be fixed by the court.
END OF DOCUMENT
712
25-3140.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 1 8048 Palm Ave.
Highland, CA
92346
909.864.0223
Fax 909.864.0280
[email protected]
SERVICE AUTHORIZATION AND AGREEMENT
Date: 03/04/2025
Requested By: Andrew Krumwiede
Company: ARCHITERRA Design Group, Inc. JCA File # 25-3140.0
Address: 10221-A Trademark
Rancho Cucamonga, CA 91730
Telephone: (909) 484-2800
Fax: (909) 484-2802
Project Name: Washington Charter Park
Location: City of Palm Desert, California
Project Description: Provide Electrical Construction documents reflecting new walkway lighting and new playground lighting at existing park.
This proposal is based on preliminary assumptions based on the current RFP, and may be subject to scope and fee adjustments once the final design is approved by the city.
FEE SCHEDULE:
For electrical engineering services per “Exhibit A” and “Exhibit B” attached made a part hereof Fixed Fee of Nine Thousand Seven Hundred Dollars ($ 9,700.00) for Electrical Engineering, Electrical Construction Documents and Electrical Document Support
CLIENT APPROVAL
Acceptance copy of this service authorization shall be signed and returned prior to commencement of work. The undersigned accepts the terms of this agreement, “Exhibit A-Scope of Services”, and “Exhibit B - Terms of Agreement for Engineering Services”, articles 1 through 10, attached as part hereof.
CLIENT
SIGNATURE:
DATE:
NAME
:
Client P.O. / Project #
NAME: James J. Corns FOR: JCA Engineering Inc.
CONSULTANT: DATE: 03/04/2025
Acknowledgment copy – Please sign and return
J Engineering Inc.
CA
Electrical Engineering & Consulting
713
25-3140.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 2 “EXHIBIT A”
SCOPE OF SERVICES
1. Provide one site visit during design phase for investigation and documentation of existing conditions, as required
2. Design of power distribution from existing service and sub-panels to each new light fixture including electrical controls.
3. Design new security walkway lighting to meet all building codes presently adopted by the authority having jurisdiction.
4. Design new playground lighting (same light fixture as walkway) to meet all building codes presently adopted by the authority having jurisdiction
5. Design power connection to irrigation controller
7. Provide structural pole base calculations for walkway/playground light pole (maximum of one calculations)
8. Provide photometric illumination plan for walkway and playground, if required.
9. Provide exterior Title 24 calculations for walkway and playground, if required.
10. Provide revisions necessary as a part of Building Department review; submit construction documents for bid issue and construction.
11. Respond to requests for information.
12. Prepare any addenda as necessary.
13 Review all shop drawings relating to the electrical work for compliance with the construction documents.
14. Provide licensed California electrical engineer’s stamp and signature.
SERVICES NOT INCLUDED:
1. Soils testing and reports. Client shall provide to Consultant for use in structural calculations.
2. Design of new street lighting or structural pole base calculations.
3. Fees, submittals, processing or approval of electrical drawings with local Building Department.
4. Fabrication of electronic site plan, Client shall provide scaled electronic site plan.
5. Design of headend, active components, raceways, cabling, power outlets or devices for video surveillance, data, integrated communications, access control, site sound system, site/open covered arena annunciation system, open covered arena theatrical lighting system, video system, door locking or wireless Wi-Fi.
6. Design of Future Solar Power System headend, equipment, cabling, solar panels or connection to existing site main service.
7. Design circuit breaker(s), connection and raceways for electric car charger(s) and future electric car charger(s).
8. Design of new site electrical metered service if existing is inadequate to handle new loads 714
25-3140.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 3 9. Design site low voltage raceways from certain poles to central location for future camera system 10 Design of 120 volt power distribution from new site sub-panel to poles with future cameras over 300’ from future camera system headend unit.
11. Design general power/lighting for covered shelters
12. Design of new lighting or power for any other part of site
13. Design of remedial electrical work where existing conditions are in violation of California Electric Code. (C.E.C.)
14. Advertisement or hard copy sets for bidding purposes. Owner shall provide all advertising, bid sets and book specification, including fees, for bid.
15 Providing Boiler plate specifications or conducting bid process. Owner shall be responsible for all bid items.
16. Electrical Construction Administration
“EXHIBIT B”
TERMS OF AGREEMENT FOR ENGINEERING SERVICE
Article 1 BASIC SERVICES
1.1 Consultant shall coordinate with Client with respect to the Consultant's services in such a way that Consultant's duties and responsibilities shall be co-extensive with those of Client.
Consultant shall perform his services in character, sequence, and timing so that they will be coordinated with services of Client and other Consultants for the project. Consultant’s services will proceed after adequate base sheets and/or Client furnishes other information necessary. The Consultant's services shall conform to the original schedule and budget for the project as provided by the Client. The relationship of Consultant to the Client shall be that of an independent contractor performing professional services for Client in accordance with this Agreement.
1.2 Consultant shall comply with all Electrical Building Department rules and regulations that will affect this design on this project.
1.3 Consultant shall provide a complete set of design documents including all schedules, details, diagrams, legends and specifications (if required). Consultant shall furnish at his client all progress prints and specifications required.
1.4 Consultant shall review all electrically related shop drawings as submitted by the Electrical Contractor to ensure compliance with specifications.
1.5 Consultant shall perform the services as set forth on "Exhibit A", attached.
Article 2 DOCUMENT SUPPORT
2.1 Document support shall include Building Department or Division of State Architects review changes, Building Department or Division of State Architects responses and request for information during bid.
2.2 Document support shall be considered as part of the contract, if required, regardless of the extensiveness of support required on the project.
Article 3 WORK NOT INCLUDED / EXTRA SERVICES
3.1 All Building Department Fees: Consultant shall provide drawings as required to submit electrical construction documents for the Building Department plan check. Client shall pay all Building Department fees.
715
25-3140.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 4 3.2 Printing: Client shall furnish at his expense information and progress prints of the work required for this project. Prints required by reviewing agencies. Documents required for bidding and construction shall be paid for by Client or Consultant shall pay for blueprinting and Client will reimburse. Client shall pay for final prints and specifications furnished to Consultant. Mylar final prints shall be paid for by Client or Consultant shall pay and Client will reimburse. Reimbursable invoice for additional prints shall include blueprint cost, plus 15% for any applicable governmental fees, outside vender reproduction cost, in house reproduction costs, mileage and delivery or messenger services incurred on client’s behalf
3.3 Additional work/revisions: No additional services shall be performed without written direction from Client. Consultant shall be paid by Client for any additional work resulting from changes or revisions made by the Client or Project Owner and also for any additional work not specifically mentioned in Articles 1 and 2 above, as provided in paragraph 5.1.
Article 4 COMPENSATION
4.1 Client shall pay Consultant amount stated in “FEE SCHEDULE”, page 1.
4.2 Client shall pay Consultant for Article 3 "Work Not Included/Extra Services/Construction Support" for changes or revisions per paragraph 3.3 at the hourly rates as set forth in paragraph 4.3.
4.3 For the purposes of hourly services and/or revisions for the basic services, the Consultant shall invoice the Client at the following rates:
Project Engineer/Manager $ 230.00
Designer $ 180.00
Drafting/CADD $ 165.00
Clerical/Delivery/Accounting $ 150.00
These hourly rates shall be adjusted annually based on increases in product cost, the cost of living and fuel prices.
Article 5 INVOICE AND PAYMENTS
5.1 At Design Development submittal Design Development Documents shall be considered 100%. Consultant shall tender an 100% invoice to Client setting forth all amounts due.
5.2 At Building Department or Division of State Architects submittal Construction Documents shall be considered 80%. Consultant shall tender an 80% invoice to Client setting forth all amounts due. Client shall completely pay 80% invoice prior to final building department or division of state architects submittal or electrical drawings will not be stamped or wet signed
5.3 When project is approved by the Building Department, Division of State Architects or published for bid the Electrical Construction Documents shall be considered 100%.
Consultant shall tender a 20% invoice (Total amount for Construction Documents 100%) to Client setting forth all amounts due.
5.4 During design and construction phase Consultant shall tender an invoice to Client setting forth the amounts due for Construction Administration and reimbursable expenses.
5.5 Projects that do not require Construction Administration shall not be invoiced.
5.6 At completion of project Client shall provide written notification to Consultant when they are doing final billings to Owner. Closing out project without written notification to Consultant does not relieve Client of complete payment of all amounts. After notification Consultant shall tender an invoice to Client setting forth the final amounts due for Construction Administration and reimbursable expenses, as required.
5.7 Client shall pay to consultant the total amount due under invoice within thirty days after receipt of invoice, or within five (5) days of receiving payment from owner (if other than client) whichever date occurs first. Client shall pay a service charge of 1.50% per month on all unpaid balances. Consultant may suspend all work on the project when accounts are over 60 days delinquent.
716
25-3140.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 5 Article 6 ABANDONMENT
In the event the project is abandoned, Client shall advise immediately by written notice, Consultant to stop work. Client shall pay consultant for all outstanding invoices for service performed and for services completed at that time on the project. Work shall be suspended until Client advises Consultant in writing to continue work.
Article 7 ELECTRICAL DOCUMENTS
7.1 All electronic files, drawings and copies furnished by JCA Engineering Inc. are and shall remain its property. They are to be used only with respect to the above-mentioned project and are not to be used on any other project. Submission or distribution to meet official regulatory requirements or for other purposes in connection with this project is not to be construed as publication in derogation of JCA Engineering Inc. common law copyright or other reserved rights.
7.2 Client agrees not to make changes to any of the Consultants documents without Consultants written agreement.
7.3 Electrical plans are diagrammatic only. Architectural drawings, elevations, details or sections shall denote all electrical devices locations that need exact mounting requirements.
7.4 Upon request Consultant shall provide the Client with electronic files after all fees have been completely paid and JCA’s affidavit has been signed and returned. Time required to process request will be billed to Owner or Client at the above hourly rates.
7.5 Electrical design on documents is guaranteed for a 180 day period. Projects that have not started construction prior to the guarantee period shall be subject to additional electrical fees to investigate and change any items on the drawings related to the current electrical and fire code at that time.
Article 8 SCOPE OF AGREEMENT AND ACCEPTANCE
8.1 This document contains the entire agreement of the parties relating to the rights granted and obligations assumed in this document. Any oral modifications or representations concerning this document shall be of no effect unless contained in a subsequent written modification signed by the party to be charged.
8.2 The electrical fees shown above shall be reviewed and adjusted if the project has not commenced within 180 days of signing of this contract.
Article 9 INSURANCE
Each party to this Agreement shall carry and maintain insurance to protect him from claims arising out of the performance of his professional services caused by the acts, errors or omissions of each party's legally responsible.
Article 10 ARBITRATION
All questions in dispute under this Agreement shall be submitted to arbitration in accordance with the provision of the Construction Industry rules of the American Arbitration Association. Consultant cannot be sued for a greater amount than the fee. The prevailing party shall be entitled to reasonable attorney's fees to be awarded by the Arbitrator. If there are judicial proceedings instead of arbitration, reasonable attorney's fees shall be fixed by the court.
END OF DOCUMENT
717
25-3141.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 1 8048 Palm Ave.
Highland, CA
92346
909.864.0223
Fax 909.864.0280
[email protected]
SERVICE AUTHORIZATION AND AGREEMENT
Date: 03/04/2025
Requested By: Andrew Krumwiede
Company: ARCHITERRA Design Group, Inc. JCA File # 25-3141.0
Address: 10221-A Trademark
Rancho Cucamonga, CA 91730
Telephone: (909) 484-2800
Fax: (909) 484-2802
Project Name: Randall Henderson Trailhead
Location: City of Palm Desert, California
Project Description: Provide Electrical Construction documents reflecting new metered service, new walkway lighting, new parking lot lighting and new shade structure power/lighting existing park.
This proposal is based on preliminary assumptions based on the current RFP, and may be subject to scope and fee adjustments once the final design is approved by the city.
FEE SCHEDULE:
For electrical engineering services per “Exhibit A” and “Exhibit B” attached made a part hereof Fixed Fee of Eighteen Thousand Nine Hundred Dollars ($ 18,900.00) for Electrical Engineering, Electrical Construction Documents and Electrical Document Support
CLIENT APPROVAL
Acceptance copy of this service authorization shall be signed and returned prior to commencement of work. The undersigned accepts the terms of this agreement, “Exhibit A-Scope of Services”, and “Exhibit B - Terms of Agreement for Engineering Services”, articles 1 through 10, attached as part hereof.
CLIENT
SIGNATURE:
DATE:
NAME
:
Client P.O. / Project #
NAME: James J. Corns FOR: JCA Engineering Inc.
CONSULTANT: DATE: 03/04/2025
Acknowledgment copy – Please sign and return
J Engineering Inc.
CA
Electrical Engineering & Consulting
718
25-3141.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 2 “EXHIBIT A”
SCOPE OF SERVICES
1. Design all new power system including main switchboard and distribution panels to meet minimum owner’s standards electrical requirements.
2. Provide all required paperwork and electronic files to Owner to submit to local power, telephone and cable utility companies for service requirements, new off-site point of connection and other requirements.
3. Design new security walkway lighting to meet all building codes presently adopted by the authority having jurisdiction.
4. Design new parking lot lighting to meet all building codes presently adopted by the authority having jurisdiction
5. Design general power/lighting for new shade shelters.
6. Design power connection to irrigation controller
7. Design power connection to pre-fabricated restroom building
8. Provide structural pole base calculations for parking lot and walkway light poles (maximum of two calculations)
9. Provide photometric illumination plan for parking lot and walkway, if required.
10. Provide exterior Title 24 calculations for parking lot and walkway, if required.
11. Provide revisions necessary as a part of Building Department review; submit construction documents for bid issue and construction.
12. Respond to requests for information.
13. Prepare any addenda as necessary.
14 Review all shop drawings relating to the electrical work for compliance with the construction documents.
15. Provide licensed California electrical engineer’s stamp and signature.
SERVICES NOT INCLUDED:
1. Soils testing and reports. Client shall provide to Consultant for use in structural calculations.
2. Design of new street lighting or structural pole base calculations.
3. Fees, submittals, processing or approval of electrical drawings with local Building Department.
4. Fabrication of electronic site plan, Client shall provide scaled electronic site plan.
5. Design of headend, active components, raceways, cabling, power outlets or devices for video surveillance, data, integrated communications, access control, site sound system, site/open covered arena annunciation system, open covered arena theatrical lighting system, video system, door locking or wireless Wi-Fi.
6. Design of Future Solar Power System headend, equipment, cabling, solar panels or connection to existing site main service.
719
25-3141.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 3 7. Design circuit breaker(s), connection and raceways for electric car charger(s) and future electric car charger(s).
8. Submittal, fees drawings, coordination and approved drawings from local power, telephone and cable utility company for new service. Per utility company standards there shall only be one contact person (Owner) for complete process. JCA to provide all electrical, telephone and cable information on forms, electrical PDF drawings and AutoCAD site plan for Owner’s submittal process
9. Control of timeline for power company designed drawings. Estimated timeline for utility company red line drawings is twelve to sixteen weeks. If project is to bid prior to arrival of utility company red lines JCA will design for the worst case.
10. Design of site low voltage raceways from certain poles to central location for future camera system 11 Design of 120 volt power distribution from new site sub-panel to poles with future cameras over 300’ from future camera system headend unit.
12. Design of new lighting or power for any other part of site
13. Design of remedial electrical work where existing conditions are in violation of California Electric Code. (C.E.C.)
14. Advertisement or hard copy sets for bidding purposes. Owner shall provide all advertising, bid sets and book specification, including fees, for bid.
15 Providing Boiler plate specifications or conducting bid process. Owner shall be responsible for all bid items.
17. Design of special event, equipment or dedicated power for new covered open arena
18. Provide interior Title 24 calculations for new building, if required.
19. Electrical Construction Administration
“EXHIBIT B”
TERMS OF AGREEMENT FOR ENGINEERING SERVICE
Article 1 BASIC SERVICES
1.1 Consultant shall coordinate with Client with respect to the Consultant's services in such a way that Consultant's duties and responsibilities shall be co-extensive with those of Client.
Consultant shall perform his services in character, sequence, and timing so that they will be coordinated with services of Client and other Consultants for the project. Consultant’s services will proceed after adequate base sheets and/or Client furnishes other information necessary. The Consultant's services shall conform to the original schedule and budget for the project as provided by the Client. The relationship of Consultant to the Client shall be that of an independent contractor performing professional services for Client in accordance with this Agreement.
1.2 Consultant shall comply with all Electrical Building Department rules and regulations that will affect this design on this project.
1.3 Consultant shall provide a complete set of design documents including all schedules, details, diagrams, legends and specifications (if required). Consultant shall furnish at his client all progress prints and specifications required.
1.4 Consultant shall review all electrically related shop drawings as submitted by the Electrical Contractor to ensure compliance with specifications.
720
25-3141.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 4 1.5 Consultant shall perform the services as set forth on "Exhibit A", attached.
Article 2 DOCUMENT SUPPORT
2.1 Document support shall include Building Department or Division of State Architects review changes, Building Department or Division of State Architects responses and request for information during bid.
2.2 Document support shall be considered as part of the contract, if required, regardless of the extensiveness of support required on the project.
Article 3 WORK NOT INCLUDED / EXTRA SERVICES
3.1 All Building Department Fees: Consultant shall provide drawings as required to submit electrical construction documents for the Building Department plan check. Client shall pay all Building Department fees.
3.2 Printing: Client shall furnish at his expense information and progress prints of the work required for this project. Prints required by reviewing agencies. Documents required for bidding and construction shall be paid for by Client or Consultant shall pay for blueprinting and Client will reimburse. Client shall pay for final prints and specifications furnished to Consultant. Mylar final prints shall be paid for by Client or Consultant shall pay and Client will reimburse. Reimbursable invoice for additional prints shall include blueprint cost, plus 15% for any applicable governmental fees, outside vender reproduction cost, in house reproduction costs, mileage and delivery or messenger services incurred on client’s behalf
3.3 Additional work/revisions: No additional services shall be performed without written direction from Client. Consultant shall be paid by Client for any additional work resulting from changes or revisions made by the Client or Project Owner and also for any additional work not specifically mentioned in Articles 1 and 2 above, as provided in paragraph 5.1.
Article 4 COMPENSATION
4.1 Client shall pay Consultant amount stated in “FEE SCHEDULE”, page 1.
4.2 Client shall pay Consultant for Article 3 "Work Not Included/Extra Services/Construction Support" for changes or revisions per paragraph 3.3 at the hourly rates as set forth in paragraph 4.3.
4.3 For the purposes of hourly services and/or revisions for the basic services, the Consultant shall invoice the Client at the following rates:
Project Engineer/Manager $ 230.00
Designer $ 180.00
Drafting/CADD $ 165.00
Clerical/Delivery/Accounting $ 150.00
These hourly rates shall be adjusted annually based on increases in product cost, the cost of living and fuel prices.
Article 5 INVOICE AND PAYMENTS
5.1 At Design Development submittal Design Development Documents shall be considered 100%. Consultant shall tender an 100% invoice to Client setting forth all amounts due.
5.2 At Building Department or Division of State Architects submittal Construction Documents shall be considered 80%. Consultant shall tender an 80% invoice to Client setting forth all amounts due. Client shall completely pay 80% invoice prior to final building department or division of state architects submittal or electrical drawings will not be stamped or wet signed
5.3 When project is approved by the Building Department, Division of State Architects or published for bid the Electrical Construction Documents shall be considered 100%.
Consultant shall tender a 20% invoice (Total amount for Construction Documents 100%) to Client setting forth all amounts due.
721
25-3141.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 5 5.4 During design and construction phase Consultant shall tender an invoice to Client setting forth the amounts due for Construction Administration and reimbursable expenses.
5.5 Projects that do not require Construction Administration shall not be invoiced.
5.6 At completion of project Client shall provide written notification to Consultant when they are doing final billings to Owner. Closing out project without written notification to Consultant does not relieve Client of complete payment of all amounts. After notification Consultant shall tender an invoice to Client setting forth the final amounts due for Construction Administration and reimbursable expenses, as required.
5.7 Client shall pay to consultant the total amount due under invoice within thirty days after receipt of invoice, or within five (5) days of receiving payment from owner (if other than client) whichever date occurs first. Client shall pay a service charge of 1.50% per month on all unpaid balances. Consultant may suspend all work on the project when accounts are over 60 days delinquent.
Article 6 ABANDONMENT
In the event the project is abandoned, Client shall advise immediately by written notice, Consultant to stop work. Client shall pay consultant for all outstanding invoices for service performed and for services completed at that time on the project. Work shall be suspended until Client advises Consultant in writing to continue work.
Article 7 ELECTRICAL DOCUMENTS
7.1 All electronic files, drawings and copies furnished by JCA Engineering Inc. are and shall remain its property. They are to be used only with respect to the above-mentioned project and are not to be used on any other project. Submission or distribution to meet official regulatory requirements or for other purposes in connection with this project is not to be construed as publication in derogation of JCA Engineering Inc. common law copyright or other reserved rights.
7.2 Client agrees not to make changes to any of the Consultants documents without Consultants written agreement.
7.3 Electrical plans are diagrammatic only. Architectural drawings, elevations, details or sections shall denote all electrical devices locations that need exact mounting requirements.
7.4 Upon request Consultant shall provide the Client with electronic files after all fees have been completely paid and JCA’s affidavit has been signed and returned. Time required to process request will be billed to Owner or Client at the above hourly rates.
7.5 Electrical design on documents is guaranteed for a 180 day period. Projects that have not started construction prior to the guarantee period shall be subject to additional electrical fees to investigate and change any items on the drawings related to the current electrical and fire code at that time.
Article 8 SCOPE OF AGREEMENT AND ACCEPTANCE
8.1 This document contains the entire agreement of the parties relating to the rights granted and obligations assumed in this document. Any oral modifications or representations concerning this document shall be of no effect unless contained in a subsequent written modification signed by the party to be charged.
8.2 The electrical fees shown above shall be reviewed and adjusted if the project has not commenced within 180 days of signing of this contract.
Article 9 INSURANCE
Each party to this Agreement shall carry and maintain insurance to protect him from claims arising out of the performance of his professional services caused by the acts, errors or omissions of each party's legally responsible.
722
25-3141.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 6 Article 10 ARBITRATION
All questions in dispute under this Agreement shall be submitted to arbitration in accordance with the provision of the Construction Industry rules of the American Arbitration Association. Consultant cannot be sued for a greater amount than the fee. The prevailing party shall be entitled to reasonable attorney's fees to be awarded by the Arbitrator. If there are judicial proceedings instead of arbitration, reasonable attorney's fees shall be fixed by the court.
END OF DOCUMENT
723
25-3142.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 1 8048 Palm Ave.
Highland, CA
92346
909.864.0223
Fax 909.864.0280
[email protected]
SERVICE AUTHORIZATION AND AGREEMENT
Date: 03/04/2025
Requested By: Andrew Krumwiede
Company: ARCHITERRA Design Group, Inc. JCA File # 25-3142.0
Address: 10221-A Trademark
Rancho Cucamonga, CA 91730
Telephone: (909) 484-2800
Fax: (909) 484-2802
Project Name: Freedom Park
Location: City of Palm Desert, California
Project Description: Provide Electrical Construction documents reflecting new playground lighting at existing park.
This proposal is based on preliminary assumptions based on the current RFP, and may be subject to scope and fee adjustments once the final design is approved by the city.
FEE SCHEDULE:
For electrical engineering services per “Exhibit A” and “Exhibit B” attached made a part hereof Fixed Fee of Seven Thousand Seven Hundred Dollars ($ 7,700.00) for Electrical Engineering, Electrical Construction Documents and Electrical Document Support
CLIENT APPROVAL
Acceptance copy of this service authorization shall be signed and returned prior to commencement of work. The undersigned accepts the terms of this agreement, “Exhibit A-Scope of Services”, and “Exhibit B - Terms of Agreement for Engineering Services”, articles 1 through 10, attached as part hereof.
CLIENT
SIGNATURE:
DATE:
NAME
:
Client P.O. / Project #
NAME: James J. Corns FOR: JCA Engineering Inc.
CONSULTANT: DATE: 03/04/2025
Acknowledgment copy – Please sign and return
J Engineering Inc.
CA
Electrical Engineering & Consulting
724
25-3142.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 2 “EXHIBIT A”
SCOPE OF SERVICES
1. Provide one site visit during design phase for investigation and documentation of existing conditions, as required
2. Design of power distribution from existing service and sub-panels to each new light fixture including electrical controls.
3. Design new playground lighting to meet all building codes presently adopted by the authority having jurisdiction
4. Design power connection to irrigation controller
5. Provide structural pole base calculations for playground light pole (maximum of one calculations)
6. Provide photometric illumination plan for playground, if required.
7. Provide exterior Title 24 calculations for playground, if required.
8. Provide revisions necessary as a part of Building Department review; submit construction documents for bid issue and construction.
9. Respond to requests for information.
10. Prepare any addenda as necessary.
11 Review all shop drawings relating to the electrical work for compliance with the construction documents.
12. Provide licensed California electrical engineer’s stamp and signature.
SERVICES NOT INCLUDED:
1. Soils testing and reports. Client shall provide to Consultant for use in structural calculations.
2. Design of new street lighting or structural pole base calculations.
3. Fees, submittals, processing or approval of electrical drawings with local Building Department.
4. Fabrication of electronic site plan, Client shall provide scaled electronic site plan.
5. Design of headend, active components, raceways, cabling, power outlets or devices for video surveillance, data, integrated communications, access control, site sound system, site/open covered arena annunciation system, open covered arena theatrical lighting system, video system, door locking or wireless Wi-Fi.
6. Design of Future Solar Power System headend, equipment, cabling, solar panels or connection to existing site main service.
7. Design circuit breaker(s), connection and raceways for electric car charger(s) and future electric car charger(s).
8. Design of new site electrical metered service if existing is inadequate to handle new loads
9. Design site low voltage raceways from certain poles to central location for future camera system 725
25-3142.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 3 10 Design of 120 volt power distribution from new site sub-panel to poles with future cameras over 300’ from future camera system headend unit.
11. Design general power/lighting for covered shelters
12. Design of new lighting or power for any other part of site
13. Design of remedial electrical work where existing conditions are in violation of California Electric Code. (C.E.C.)
14. Advertisement or hard copy sets for bidding purposes. Owner shall provide all advertising, bid sets and book specification, including fees, for bid.
15 Providing Boiler plate specifications or conducting bid process. Owner shall be responsible for all bid items.
16. Electrical Construction Administration
“EXHIBIT B”
TERMS OF AGREEMENT FOR ENGINEERING SERVICE
Article 1 BASIC SERVICES
1.1 Consultant shall coordinate with Client with respect to the Consultant's services in such a way that Consultant's duties and responsibilities shall be co-extensive with those of Client.
Consultant shall perform his services in character, sequence, and timing so that they will be coordinated with services of Client and other Consultants for the project. Consultant’s services will proceed after adequate base sheets and/or Client furnishes other information necessary. The Consultant's services shall conform to the original schedule and budget for the project as provided by the Client. The relationship of Consultant to the Client shall be that of an independent contractor performing professional services for Client in accordance with this Agreement.
1.2 Consultant shall comply with all Electrical Building Department rules and regulations that will affect this design on this project.
1.3 Consultant shall provide a complete set of design documents including all schedules, details, diagrams, legends and specifications (if required). Consultant shall furnish at his client all progress prints and specifications required.
1.4 Consultant shall review all electrically related shop drawings as submitted by the Electrical Contractor to ensure compliance with specifications.
1.5 Consultant shall perform the services as set forth on "Exhibit A", attached.
Article 2 DOCUMENT SUPPORT
2.1 Document support shall include Building Department or Division of State Architects review changes, Building Department or Division of State Architects responses and request for information during bid.
2.2 Document support shall be considered as part of the contract, if required, regardless of the extensiveness of support required on the project.
Article 3 WORK NOT INCLUDED / EXTRA SERVICES
3.1 All Building Department Fees: Consultant shall provide drawings as required to submit electrical construction documents for the Building Department plan check. Client shall pay all Building Department fees.
726
25-3142.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 4 3.2 Printing: Client shall furnish at his expense information and progress prints of the work required for this project. Prints required by reviewing agencies. Documents required for bidding and construction shall be paid for by Client or Consultant shall pay for blueprinting and Client will reimburse. Client shall pay for final prints and specifications furnished to Consultant. Mylar final prints shall be paid for by Client or Consultant shall pay and Client will reimburse. Reimbursable invoice for additional prints shall include blueprint cost, plus 15% for any applicable governmental fees, outside vender reproduction cost, in house reproduction costs, mileage and delivery or messenger services incurred on client’s behalf
3.3 Additional work/revisions: No additional services shall be performed without written direction from Client. Consultant shall be paid by Client for any additional work resulting from changes or revisions made by the Client or Project Owner and also for any additional work not specifically mentioned in Articles 1 and 2 above, as provided in paragraph 5.1.
Article 4 COMPENSATION
4.1 Client shall pay Consultant amount stated in “FEE SCHEDULE”, page 1.
4.2 Client shall pay Consultant for Article 3 "Work Not Included/Extra Services/Construction Support" for changes or revisions per paragraph 3.3 at the hourly rates as set forth in paragraph 4.3.
4.3 For the purposes of hourly services and/or revisions for the basic services, the Consultant shall invoice the Client at the following rates:
Project Engineer/Manager $ 230.00
Designer $ 180.00
Drafting/CADD $ 165.00
Clerical/Delivery/Accounting $ 150.00
These hourly rates shall be adjusted annually based on increases in product cost, the cost of living and fuel prices.
Article 5 INVOICE AND PAYMENTS
5.1 At Design Development submittal Design Development Documents shall be considered 100%. Consultant shall tender an 100% invoice to Client setting forth all amounts due.
5.2 At Building Department or Division of State Architects submittal Construction Documents shall be considered 80%. Consultant shall tender an 80% invoice to Client setting forth all amounts due. Client shall completely pay 80% invoice prior to final building department or division of state architects submittal or electrical drawings will not be stamped or wet signed
5.3 When project is approved by the Building Department, Division of State Architects or published for bid the Electrical Construction Documents shall be considered 100%.
Consultant shall tender a 20% invoice (Total amount for Construction Documents 100%) to Client setting forth all amounts due.
5.4 During design and construction phase Consultant shall tender an invoice to Client setting forth the amounts due for Construction Administration and reimbursable expenses.
5.5 Projects that do not require Construction Administration shall not be invoiced.
5.6 At completion of project Client shall provide written notification to Consultant when they are doing final billings to Owner. Closing out project without written notification to Consultant does not relieve Client of complete payment of all amounts. After notification Consultant shall tender an invoice to Client setting forth the final amounts due for Construction Administration and reimbursable expenses, as required.
5.7 Client shall pay to consultant the total amount due under invoice within thirty days after receipt of invoice, or within five (5) days of receiving payment from owner (if other than client) whichever date occurs first. Client shall pay a service charge of 1.50% per month on all unpaid balances. Consultant may suspend all work on the project when accounts are over 60 days delinquent.
727
25-3142.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 5 Article 6 ABANDONMENT
In the event the project is abandoned, Client shall advise immediately by written notice, Consultant to stop work. Client shall pay consultant for all outstanding invoices for service performed and for services completed at that time on the project. Work shall be suspended until Client advises Consultant in writing to continue work.
Article 7 ELECTRICAL DOCUMENTS
7.1 All electronic files, drawings and copies furnished by JCA Engineering Inc. are and shall remain its property. They are to be used only with respect to the above-mentioned project and are not to be used on any other project. Submission or distribution to meet official regulatory requirements or for other purposes in connection with this project is not to be construed as publication in derogation of JCA Engineering Inc. common law copyright or other reserved rights.
7.2 Client agrees not to make changes to any of the Consultants documents without Consultants written agreement.
7.3 Electrical plans are diagrammatic only. Architectural drawings, elevations, details or sections shall denote all electrical devices locations that need exact mounting requirements.
7.4 Upon request Consultant shall provide the Client with electronic files after all fees have been completely paid and JCA’s affidavit has been signed and returned. Time required to process request will be billed to Owner or Client at the above hourly rates.
7.5 Electrical design on documents is guaranteed for a 180 day period. Projects that have not started construction prior to the guarantee period shall be subject to additional electrical fees to investigate and change any items on the drawings related to the current electrical and fire code at that time.
Article 8 SCOPE OF AGREEMENT AND ACCEPTANCE
8.1 This document contains the entire agreement of the parties relating to the rights granted and obligations assumed in this document. Any oral modifications or representations concerning this document shall be of no effect unless contained in a subsequent written modification signed by the party to be charged.
8.2 The electrical fees shown above shall be reviewed and adjusted if the project has not commenced within 180 days of signing of this contract.
Article 9 INSURANCE
Each party to this Agreement shall carry and maintain insurance to protect him from claims arising out of the performance of his professional services caused by the acts, errors or omissions of each party's legally responsible.
Article 10 ARBITRATION
All questions in dispute under this Agreement shall be submitted to arbitration in accordance with the provision of the Construction Industry rules of the American Arbitration Association. Consultant cannot be sued for a greater amount than the fee. The prevailing party shall be entitled to reasonable attorney's fees to be awarded by the Arbitrator. If there are judicial proceedings instead of arbitration, reasonable attorney's fees shall be fixed by the court.
END OF DOCUMENT
728
25-3143.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 1 8048 Palm Ave.
Highland, CA
92346
909.864.0223
Fax 909.864.0280
[email protected]
SERVICE AUTHORIZATION AND AGREEMENT
Date: 03/04/2025
Requested By: Andrew Krumwiede
Company: ARCHITERRA Design Group, Inc. JCA File # 25-3143.0
Address: 10221-A Trademark
Rancho Cucamonga, CA 91730
Telephone: (909) 484-2800
Fax: (909) 484-2802
Project Name: Ironwood Park
Location: City of Palm Desert, California
Project Description: Provide Electrical Construction documents reflecting new shade structure power/lighting and power connection to new water feature at existing park.
This proposal is based on preliminary assumptions based on the current RFP, and may be subject to scope and fee adjustments once the final design is approved by the city.
FEE SCHEDULE:
For electrical engineering services per “Exhibit A” and “Exhibit B” attached made a part hereof Fixed Fee of Eleven Thousand Five Hundred Dollars ($ 11,500.00) for Electrical Engineering, Electrical Construction Documents and Electrical Document Support
CLIENT APPROVAL
Acceptance copy of this service authorization shall be signed and returned prior to commencement of work. The undersigned accepts the terms of this agreement, “Exhibit A-Scope of Services”, and “Exhibit B - Terms of Agreement for Engineering Services”, articles 1 through 10, attached as part hereof.
CLIENT
SIGNATURE:
DATE:
NAME
:
Client P.O. / Project #
NAME: James J. Corns FOR: JCA Engineering Inc.
CONSULTANT: DATE: 03/04/2025
Acknowledgment copy – Please sign and return
J Engineering Inc.
CA
Electrical Engineering & Consulting
729
25-3143.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 2 “EXHIBIT A”
SCOPE OF SERVICES
1. Provide one site visit during design phase for investigation and documentation of existing conditions, as required
2. Design of power distribution from existing service and sub-panels to each new light fixture including electrical controls.
3. Design general power/lighting for new shade shelters.
4. Design power connection to irrigation controller
5. Design power connection to water feature system.
6. Provide revisions necessary as a part of Building Department review; submit construction documents for bid issue and construction.
7. Respond to requests for information.
8. Prepare any addenda as necessary.
9 Review all shop drawings relating to the electrical work for compliance with the construction documents.
10. Provide licensed California electrical engineer’s stamp and signature.
SERVICES NOT INCLUDED:
1. Soils testing and reports. Client shall provide to Consultant for use in structural calculations.
2. Design of new street lighting or structural pole base calculations.
3. Fees, submittals, processing or approval of electrical drawings with local Building Department.
4. Fabrication of electronic site plan, Client shall provide scaled electronic site plan.
5. Design of headend, active components, raceways, cabling, power outlets or devices for video surveillance, data, integrated communications, access control, site sound system, site/open covered arena annunciation system, open covered arena theatrical lighting system, video system, door locking or wireless Wi-Fi.
6. Design of Future Solar Power System headend, equipment, cabling, solar panels or connection to existing site main service.
7. Design circuit breaker(s), connection and raceways for electric car charger(s) and future electric car charger(s).
8. Design of new site electrical metered service if existing is inadequate to handle new loads
9. Design site low voltage raceways from certain poles to central location for future camera system 10 Design of 120 volt power distribution from new site sub-panel to poles with future cameras over 300’ from future camera system headend unit.
11. Design of new lighting or power for any other part of site 730
25-3143.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 3 12. Design of remedial electrical work where existing conditions are in violation of California Electric Code. (C.E.C.)
13. Advertisement or hard copy sets for bidding purposes. Owner shall provide all advertising, bid sets and book specification, including fees, for bid.
14 Providing Boiler plate specifications or conducting bid process. Owner shall be responsible for all bid items.
15. Electrical Construction Administration
“EXHIBIT B”
TERMS OF AGREEMENT FOR ENGINEERING SERVICE
Article 1 BASIC SERVICES
1.1 Consultant shall coordinate with Client with respect to the Consultant's services in such a way that Consultant's duties and responsibilities shall be co-extensive with those of Client.
Consultant shall perform his services in character, sequence, and timing so that they will be coordinated with services of Client and other Consultants for the project. Consultant’s services will proceed after adequate base sheets and/or Client furnishes other information necessary. The Consultant's services shall conform to the original schedule and budget for the project as provided by the Client. The relationship of Consultant to the Client shall be that of an independent contractor performing professional services for Client in accordance with this Agreement.
1.2 Consultant shall comply with all Electrical Building Department rules and regulations that will affect this design on this project.
1.3 Consultant shall provide a complete set of design documents including all schedules, details, diagrams, legends and specifications (if required). Consultant shall furnish at his client all progress prints and specifications required.
1.4 Consultant shall review all electrically related shop drawings as submitted by the Electrical Contractor to ensure compliance with specifications.
1.5 Consultant shall perform the services as set forth on "Exhibit A", attached.
Article 2 DOCUMENT SUPPORT
2.1 Document support shall include Building Department or Division of State Architects review changes, Building Department or Division of State Architects responses and request for information during bid.
2.2 Document support shall be considered as part of the contract, if required, regardless of the extensiveness of support required on the project.
Article 3 WORK NOT INCLUDED / EXTRA SERVICES
3.1 All Building Department Fees: Consultant shall provide drawings as required to submit electrical construction documents for the Building Department plan check. Client shall pay all Building Department fees.
3.2 Printing: Client shall furnish at his expense information and progress prints of the work required for this project. Prints required by reviewing agencies. Documents required for bidding and construction shall be paid for by Client or Consultant shall pay for blueprinting and Client will reimburse. Client shall pay for final prints and specifications furnished to Consultant. Mylar final prints shall be paid for by Client or Consultant shall pay and Client will reimburse. Reimbursable invoice for additional prints shall include blueprint cost, plus 15% for any applicable governmental fees, outside vender reproduction cost, in house reproduction costs, mileage and delivery or messenger services incurred on client’s behalf 731
25-3143.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 4 3.3 Additional work/revisions: No additional services shall be performed without written direction from Client. Consultant shall be paid by Client for any additional work resulting from changes or revisions made by the Client or Project Owner and also for any additional work not specifically mentioned in Articles 1 and 2 above, as provided in paragraph 5.1.
Article 4 COMPENSATION
4.1 Client shall pay Consultant amount stated in “FEE SCHEDULE”, page 1.
4.2 Client shall pay Consultant for Article 3 "Work Not Included/Extra Services/Construction Support" for changes or revisions per paragraph 3.3 at the hourly rates as set forth in paragraph 4.3.
4.3 For the purposes of hourly services and/or revisions for the basic services, the Consultant shall invoice the Client at the following rates:
Project Engineer/Manager $ 230.00
Designer $ 180.00
Drafting/CADD $ 165.00
Clerical/Delivery/Accounting $ 150.00
These hourly rates shall be adjusted annually based on increases in product cost, the cost of living and fuel prices.
Article 5 INVOICE AND PAYMENTS
5.1 At Design Development submittal Design Development Documents shall be considered 100%. Consultant shall tender an 100% invoice to Client setting forth all amounts due.
5.2 At Building Department or Division of State Architects submittal Construction Documents shall be considered 80%. Consultant shall tender an 80% invoice to Client setting forth all amounts due. Client shall completely pay 80% invoice prior to final building department or division of state architects submittal or electrical drawings will not be stamped or wet signed
5.3 When project is approved by the Building Department, Division of State Architects or published for bid the Electrical Construction Documents shall be considered 100%.
Consultant shall tender a 20% invoice (Total amount for Construction Documents 100%) to Client setting forth all amounts due.
5.4 During design and construction phase Consultant shall tender an invoice to Client setting forth the amounts due for Construction Administration and reimbursable expenses.
5.5 Projects that do not require Construction Administration shall not be invoiced.
5.6 At completion of project Client shall provide written notification to Consultant when they are doing final billings to Owner. Closing out project without written notification to Consultant does not relieve Client of complete payment of all amounts. After notification Consultant shall tender an invoice to Client setting forth the final amounts due for Construction Administration and reimbursable expenses, as required.
5.7 Client shall pay to consultant the total amount due under invoice within thirty days after receipt of invoice, or within five (5) days of receiving payment from owner (if other than client) whichever date occurs first. Client shall pay a service charge of 1.50% per month on all unpaid balances. Consultant may suspend all work on the project when accounts are over 60 days delinquent.
Article 6 ABANDONMENT
In the event the project is abandoned, Client shall advise immediately by written notice, Consultant to stop work. Client shall pay consultant for all outstanding invoices for service performed and for services completed at that time on the project. Work shall be suspended until Client advises Consultant in writing to continue work.
732
25-3143.0
8048 Palm Ave. Highland, CA 92346 – Phone 909 864-0223 Fax 909 864-0280 5 Article 7 ELECTRICAL DOCUMENTS
7.1 All electronic files, drawings and copies furnished by JCA Engineering Inc. are and shall remain its property. They are to be used only with respect to the above-mentioned project and are not to be used on any other project. Submission or distribution to meet official regulatory requirements or for other purposes in connection with this project is not to be construed as publication in derogation of JCA Engineering Inc. common law copyright or other reserved rights.
7.2 Client agrees not to make changes to any of the Consultants documents without Consultants written agreement.
7.3 Electrical plans are diagrammatic only. Architectural drawings, elevations, details or sections shall denote all electrical devices locations that need exact mounting requirements.
7.4 Upon request Consultant shall provide the Client with electronic files after all fees have been completely paid and JCA’s affidavit has been signed and returned. Time required to process request will be billed to Owner or Client at the above hourly rates.
7.5 Electrical design on documents is guaranteed for a 180 day period. Projects that have not started construction prior to the guarantee period shall be subject to additional electrical fees to investigate and change any items on the drawings related to the current electrical and fire code at that time.
Article 8 SCOPE OF AGREEMENT AND ACCEPTANCE
8.1 This document contains the entire agreement of the parties relating to the rights granted and obligations assumed in this document. Any oral modifications or representations concerning this document shall be of no effect unless contained in a subsequent written modification signed by the party to be charged.
8.2 The electrical fees shown above shall be reviewed and adjusted if the project has not commenced within 180 days of signing of this contract.
Article 9 INSURANCE
Each party to this Agreement shall carry and maintain insurance to protect him from claims arising out of the performance of his professional services caused by the acts, errors or omissions of each party's legally responsible.
Article 10 ARBITRATION
All questions in dispute under this Agreement shall be submitted to arbitration in accordance with the provision of the Construction Industry rules of the American Arbitration Association. Consultant cannot be sued for a greater amount than the fee. The prevailing party shall be entitled to reasonable attorney's fees to be awarded by the Arbitrator. If there are judicial proceedings instead of arbitration, reasonable attorney's fees shall be fixed by the court.
END OF DOCUMENT
733
March 3, 2025
Proposal No. P-0300325-CR
Architerra Design Group
10221-A Trademark Street
Rancho Cucamonga, California 91730
Attention: Mr. Andrew Krumwiede
Subject: Proposal for Geotechnical and Infiltration Evaluations City of Palm Desert Park and Trailhead Engineering and Design Seven (7) Project Sites
City of Palm Desert, Riverside County, California
Dear Mr. Krumwiede:
As requested, GeoTek, Inc. (GeoTek) is pleased to submit this proposal to possibly prepare a Geotechnical and Infiltration Evaluation for seven (7) projects located in the City of Palm Desert, California. This proposal has been prepared based on the information provided and GeoTek’s experience with these types of projects.
Site and Project Description
The project consists of various improvements at seven (7) existing parks in the City of Palm Desert, Riverside County, California as indicated in the following table.
Site Name Address Proposed Improvements
Hovley Soccer Park 74735 Hovley Lane East
Sports fields, landscape and
playground
Homme Adams Park 72500 Thrush Road
Parking, shade structure,
restroom, park furnishings,
landscape
University Park 74902 University Circle Playground
Washington Center 45768 Portola Avenue Playground
Randall Henderson Trailhead
Randall Henderson Trailhead and
Highway 74
Parking, shade structure,
restroom, park furnishings,
landscape
Freedom Park 77400 Country Club Drive Playground
Ironwood Park 47800 Chia Drive Shade structure, water feature GEOTECHNICAL | ENVIRONMENTAL | MATERIALS 734
Architerra Design Group Proposal No. P-0300325-CR
Proposal for Geotechnical and Infiltration Evaluations March 3, 2025 Palm Desert, Riverside County, California Page 2
For the purposes of this proposal, it is assumed that any structures will be wood-framed, onestory and will be supported by conventional shallow spread footings and will most likely include conventional slab on-grade floor systems. Minimal cuts and fills are anticipated to be required during construction.
Based on review of published geologic maps, Hovley Soccer Park and Freedom Park are underlain by sand deposits. Homme Adams Park and Randall Henderson Trailhead are underlain by alluvium and granitic bedrock. University Park, Washington Charter and Ironwood Park are underlain by alluvium. Some surficial fills are most likely to be present at each of the facilities due to the existing improvements.
No active or potentially active faults are known to exist at any of the park sites, nor are any of the park sites situated within an “Alquist-Priolo” Earthquake Fault Zone. None of the park sites are located within areas identified by the State of California as having a potential for liquefaction.
Proposed Scope of Work
Since the proposed improvements for University Park, Washington Charter and Freedom Park include only playgrounds at this time, costs for a geotechnical and infiltration evaluation for each of these three (3) sites are not included in this proposal. If the proposed conceptual design for these three (3) park sites are amended, or require geotechnical design parameters for design and construction, a cost proposal can be provided at a later date.
It is GeoTek’s understanding that the final design for each of the remaining four (4) project sites (i.e., Hovley Soccer Park, Homme Adams Park, Randall Henderson Trailhead and Ironwood Park) is not yet completed. Costs and/or services by GeoTek can be amended at a later date when the final design for each of these four (4) projects becomes available.
In order to characterize the subsurface soil conditions at each of the Hovley Soccer Park, Homme Adams Park, Randall Henderson Trailhead and Ironwood Park sites, GeoTek will perform a reconnaissance of the sites. Permission/approval to enter the facilities and coordination to drill on the properties will need to be provided by Architerra Design Group.
GeoTek will excavate a minimum of six (6) exploratory hollow stem auger borings with the aid of a track mounted drill rig at each of the four (4) park sites (i.e., Hovley Soccer Park, Homme Adams Park, Randall Henderson Trailhead and Ironwood Park). Four (4) of the borings will be for geotechnical purposes and two (2) of the borings will be for infiltration testing purposes.
The geotechnical borings will be excavated within the area of the proposed improvements. 735
Architerra Design Group Proposal No. P-0300325-CR
Proposal for Geotechnical and Infiltration Evaluations March 3, 2025 Palm Desert, Riverside County, California Page 3
One (1) of the borings will be excavated to a minimum depth of 50 feet, or refusal, whichever occurs first, for any new sports lighting that may be required (i.e., Hovley Soccer Park). The remaining borings will be excavated to a maximum depth of approximately 15 to 20 feet, or refusal, whichever occurs first. Two (2) infiltration borings will be excavated to depths of approximately five (5) feet below existing grades and will subsequently utilized for infiltration testing. The locations of the infiltration borings should be provided to GeoTek prior to the field exploration. The infiltration testing will be completed in general conformance with County of Riverside guidelines.
Once the drilling operations are completed, the boreholes will be backfilled with the soil cuttings and capped with cold patch asphalt concrete for the boring locations in paved parking/flatwork areas and native soil for the boring locations in landscaped/soil areas. Costs to remove any excess soils from the borings at the project sites have been not included in this proposal. If the excess soils are required to be removed from the project sites, additional costs will be incurred.
Prior to performing the field investigation, a representative of GeoTek will stake or spray paint the proposed exploration locations. Please be advised that GeoTek will not commence the field investigation until a representative of each facility has reviewed the proposed exploration locations and has verified that those locations are clear of buried utility lines. Prior to conducting the field explorations, GeoTek will contact Underground Service Alert (USA) to identify buried utilities that may be in the vicinity of the proposed exploration locations. This service does not mark locations of privately owned utilities. The fee for a private utility locator has been included in the costs of this proposal to identify possible private utilities within the proposed areas of work which would not be marked by the public utility locator. Regardless of the use of a private utility locator, GeoTek will not be responsible for damage to unmarked subsurface structures or appurtenances as a result of the field activities.
GeoTek will not be responsible for repairs to any landscaping or irrigation lines that may be damaged as part of the field activities.
The fee estimate presented includes trips to the various sites to locate the test borings, to perform the actual exploration operations and conduct infiltration tests.
California Prevailing Wage requirements are considered applicable for these projects. This proposal is based on the understanding that the field explorations will be conducted during regular weekday business hours and that the boring locations are accessible by a regular-sized track-mounted drill rig.
736
Architerra Design Group Proposal No. P-0300325-CR
Proposal for Geotechnical and Infiltration Evaluations March 3, 2025 Palm Desert, Riverside County, California Page 4
Samples of soils encountered in the explorations will be obtained for subsequent laboratory testing. The laboratory testing will likely include in-situ moisture densities, maximum density/optimum moisture content, direct shear, and expansion index and corrosion testing.
Subsequent to the completion of the field work and laboratory testing, a geotechnical report will be prepared for each park site. The report will include, but not necessarily be limited to:
overall feasibility of the proposed improvements from a geotechnical standpoint; exploration logs including descriptions of materials encountered; an exploration location map; geologic setting; site seismic criteria; depth to groundwater if encountered; geotechnical hazards; corrosivity and soluble sulfate test results; foundation recommendations; infiltration test results; and geotechnical recommendations for grading and construction.
The estimated cost for each site is provided in the table below. A more detailed breakdown of the costs is included in the fee estimate tables attached to this proposal.
Park Site Cost ($)
Hovley Soccer Park 18,267
Homme Adams Park 18,267
Randall Henderson Trailhead 18,267
Ironwood Park 18,267
TOTAL $73,068
Final costs should be based on the final conceptual design for each of the seven (7) project sites.
A final report for each site can be submitted within approximately 20 working days following completion of the site exploration. It is estimated that work can commence as soon as written authorization is received. Assuming thre are no delays due to availability of exploration equipment, site accessibility and inclement weather, it is anticipated that the field phase of the study will commence promptly once authorized by the client.
CLOSURE
The fees covered by the above estimate are limited to the stated scope and do not include any response to jurisdictional review questions, construction-related services, additional meetings or consultations that may be requested. Services beyond those outlined in this proposal and requested/authorized will be invoiced at the prevailing hourly rates, as indicated on the attached Work Authorization and Agreement.
Please sign and return a copy of the enclosed "Work Authorization and Agreement" form to this office.
$54,801
737
Architerra Design Group Proposal No. P-0300325-CR
Proposal for Geotechnical and Infiltration Evaluations March 3, 2025 Palm Desert, Riverside County, California Page 5
If GeoTek receives a request to proceed (whether verbal, in writing or in the form of a Work Order or Purchase Order) with any or all of the services described in this proposal prior to receiving a signed copy of the attached Work Authorization and Agreement, and GeoTek provides any or all of the services, GeoTek and Architerra Design Group expressly agree that the terms of this proposal, the attached fee schedule and the terms and conditions set forth in the attached Work Authorization and Agreement form shall govern all the services performed.
GeoTek appreciates the opportunity of submitting this proposal and have included a contract for the scope of services. GeoTek looks forward to working with Architerra Design Group towards the successful completion of this project. If you have any questions, please do not hesitate to contact the undersigned.
Respectfully submitted,
GeoTek, Inc.
Anna M. Scott Bruce A. Hick
Project Geologist GE 2284, Exp. 12/31/26
Geotechnical Engineer
Edward H. LaMont
CEG 1892, Exp. 07/31/26
Principal Geologist
Enclosures: Breakdown of Costs
Work Authorization and Agreement
https://geotekusa.sharepoint.com/teams/Corona_Branch/Shared Documents/Proposal/GeoTek Inc/2025/P0300325 ADG City of Palm Desert GEO/P-0300325-CR ADG Palm Desert GEO INFILT.doc
738
TASK RATE TOTAL Notes
TASK NO. 1 SCHEDULING AND PROJECT COORDINATION
Staff Engineer/Geologist 2 Hours $ 167 $ 334
$ 334
TASK NO. 1 SUBSURFACE INVESTIGATION
Private Utility Locator* 4 Hours $ 420 $ 1,680
Mobilization/Demobilization (Private Utility) 3 Hours $ 222 $ 666 Hollow Stem Auger Track Mounted Drill Rig* 8 Hours $ 570 $ 4,560 Mobilization/Demobilization (Drill Rig) 3 Hours $ 360 $ 1,080 Field Engineer/Geologist 28 Hours $ 140 $ 3,920
Includes USA marking, boring logging and
infiltration testing
Field Supplies 10 Feet $ 30 $ 300 Pipe, rock, gravel and water $ 12,206
TASK NO. 3 LABORATORY TESTING
Moisture/Density Rings 16 Each $ 40 $ 640
Expansion Index 1 Each $ 202 $ 202
Corrosion Suite Testing with Sulfates 2 Each $ 270 $ 540 Direct Shear 4 Each $ 320 $ 1,280
Proctor - Moisture Density Curve 1 Each $ 260 $ 260
Collapse 3 Each $ 127 $ 381
$ 3,303
TASK NO. 4 ENGINEERING AND REPORT PREPARATION
Office Services/Drafting 4 Hours $ 82 $ 328
Staff Engineer/Geologist 10 Hours $ 167 $ 1,670
Geotechnical Engineer 2 Hours $ 213 $ 426
$ 2,424
$ 18,267
* Denotes Prevailing Wage Rate
QTY
Appendix A
Breakdown of Costs for a Geotechnical and Infiltration Evaluation Hovley Soccer Park - 74735 Hovley Lane East
Palm Desert, Riverside County, California
SUBTOTAL:
SUBTOTAL:
TOTAL:
SUBTOTAL:
SUBTOTAL:
739
TASK RATE TOTAL Notes
TASK NO. 1 SCHEDULING AND PROJECT COORDINATION
Staff Engineer/Geologist 2 Hours $ 167 $ 334
$ 334
TASK NO. 1 SUBSURFACE INVESTIGATION
Private Utility Locator* 4 Hours $ 420 $ 1,680
Mobilization/Demobilization (Private Utility) 3 Hours $ 222 $ 666 Hollow Stem Auger Track Mounted Drill Rig* 8 Hours $ 570 $ 4,560 Mobilization/Demobilization (Drill Rig) 3 Hours $ 360 $ 1,080 Field Engineer/Geologist 28 Hours $ 140 $ 3,920
Includes USA marking, boring logging and
infiltration testing
Field Supplies 10 Feet $ 30 $ 300 Pipe, rock, gravel and water $ 12,206
TASK NO. 3 LABORATORY TESTING
Moisture/Density Rings 16 Each $ 40 $ 640
Expansion Index 1 Each $ 202 $ 202
Corrosion Suite Testing with Sulfates 2 Each $ 270 $ 540 Direct Shear 4 Each $ 320 $ 1,280
Proctor - Moisture Density Curve 1 Each $ 260 $ 260
Collapse 3 Each $ 127 $ 381
$ 3,303
TASK NO. 4 ENGINEERING AND REPORT PREPARATION
Office Services/Drafting 4 Hours $ 82 $ 328
Staff Engineer/Geologist 10 Hours $ 167 $ 1,670
Geotechnical Engineer 2 Hours $ 213 $ 426
$ 2,424
$ 18,267
* Denotes Prevailing Wage Rate
QTY
Appendix A
Breakdown of Costs for a Geotechnical and Infiltration Evaluation Homme Adams Park - 72500 Thrush Road
Palm Desert, Riverside County, California
SUBTOTAL:
SUBTOTAL:
SUBTOTAL:
SUBTOTAL:
TOTAL:
740
TASK RATE TOTAL Notes
TASK NO. 1 SCHEDULING AND PROJECT COORDINATION
Staff Engineer/Geologist 2 Hours $ 167 $ 334
$ 334
TASK NO. 1 SUBSURFACE INVESTIGATION
Private Utility Locator* 4 Hours $ 420 $ 1,680
Mobilization/Demobilization (Private Utility) 3 Hours $ 222 $ 666 Hollow Stem Auger Track Mounted Drill Rig* 8 Hours $ 570 $ 4,560 Mobilization/Demobilization (Drill Rig) 3 Hours $ 360 $ 1,080 Field Engineer/Geologist 28 Hours $ 140 $ 3,920
Includes USA marking, boring logging and
infiltration testing
Field Supplies 10 Feet $ 30 $ 300 Pipe, rock, gravel and water $ 12,206
TASK NO. 3 LABORATORY TESTING
Moisture/Density Rings 16 Each $ 40 $ 640
Expansion Index 1 Each $ 202 $ 202
Corrosion Suite Testing with Sulfates 2 Each $ 270 $ 540 Direct Shear 4 Each $ 320 $ 1,280
Proctor - Moisture Density Curve 1 Each $ 260 $ 260
Collapse 3 Each $ 127 $ 381
$ 3,303
TASK NO. 4 ENGINEERING AND REPORT PREPARATION
Office Services/Drafting 4 Hours $ 82 $ 328
Staff Engineer/Geologist 10 Hours $ 167 $ 1,670
Geotechnical Engineer 2 Hours $ 213 $ 426
$ 2,424
$ 18,267
* Denotes Prevailing Wage Rate
QTY
Appendix A
Breakdown of Costs for a Geotechnical and Infiltration Evaluation Randall Henderson Trailhead - Highway 74 and Randall Henderson Trail Palm Desert, Riverside County, California
SUBTOTAL:
SUBTOTAL:
SUBTOTAL:
SUBTOTAL:
TOTAL:
741
TASK RATE TOTAL Notes
TASK NO. 1 SCHEDULING AND PROJECT COORDINATION
Staff Engineer/Geologist 2 Hours $ 167 $ 334
$ 334
TASK NO. 1 SUBSURFACE INVESTIGATION
Private Utility Locator* 4 Hours $ 420 $ 1,680
Mobilization/Demobilization (Private Utility) 3 Hours $ 222 $ 666 Hollow Stem Auger Track Mounted Drill Rig* 8 Hours $ 570 $ 4,560 Mobilization/Demobilization (Drill Rig) 3 Hours $ 360 $ 1,080 Field Engineer/Geologist 28 Hours $ 140 $ 3,920
Includes USA marking, boring logging and
infiltration testing
Field Supplies 10 Feet $ 30 $ 300 Pipe, rock, gravel and water $ 12,206
TASK NO. 3 LABORATORY TESTING
Moisture/Density Rings 16 Each $ 40 $ 640
Expansion Index 1 Each $ 202 $ 202
Corrosion Suite Testing with Sulfates 2 Each $ 270 $ 540 Direct Shear 4 Each $ 320 $ 1,280
Proctor - Moisture Density Curve 1 Each $ 260 $ 260
Collapse 3 Each $ 127 $ 381
$ 3,303
TASK NO. 4 ENGINEERING AND REPORT PREPARATION
Office Services/Drafting 4 Hours $ 82 $ 328
Staff Engineer/Geologist 10 Hours $ 167 $ 1,670
Geotechnical Engineer 2 Hours $ 213 $ 426
$ 2,424
$ 18,267
* Denotes Prevailing Wage Rate
QTY
Appendix A
Breakdown of Costs for a Geotechnical and Infiltration Evaluation Ironwood Park - 47800 Chia Drive
Palm Desert, Riverside County, California
SUBTOTAL:
SUBTOTAL:
SUBTOTAL:
SUBTOTAL:
TOTAL:
742
GeoTek, Inc. Work Authorization And Agreement
PROJECT INFORMATION
Proposal No:
Retainer:
Reimbursable Expenses not in fee Estimate:
Special Instructions:
CLIENT INFORMATION
Ext:
State: Zip: 91730
TERMS AND CONDITIONS
1) AGREEMENT. This Work Authorization and Agreement together with the proposal 4) ADDITIONAL SERVICES. Client acknowledges that it is impossible to predict what changes to the Services will be necessary as requirements for changes come from many sources beyond GeoTek's control. In the event changes become necessary, any services that are not specifically set forth in either GeoTek’s proposal or this Agreement but are requested by Client, its agents, representatives, or designees, either verbally or in writing, will be considered “Additional Services”. If Client, its agents, representatives, or designees request any Additional Services, GeoTek may issue Client a Change Order for Additional Services (“Change Order”) confirming Client’s authorization to proceed with such Additional Services. If GeoTek issues Client a Change Order, Client must notify GeoTek of any disagreements with or amendments to any of the terms of the Change Order within twenty-four hours of receipt. Client’s failure to provide GeoTek with such timely notice will constitute acceptance of the terms of the Change Order and Client will be responsible for all additional charges, costs, fees and expenses incurred by GeoTek for such Additional Services. Fax transmissions and email are acceptable modes of confirmation. The Terms and Conditions of this Agreement and most recent fee schedule will apply to all Additional Services regardless of whether GeoTek issues a Change Order or not.