CO-61 Park
March 2026
Section 01 10 00: Summary of Work
5. Lime treatment in planting areas;
6. and more.
1.16 Pre-final (Punch List) Review
A. Notify, in writing, to the Parks Construction Inspector, that the work is substantially complete. Substantially complete is defined as “the state of work where it may be used in a suitable and intended manner with exception of minor corrections”. Partial acceptances will not be granted. Items to be reviewed as a part of substantial completion include:
1. All construction items
2. Installation of all site furnishings, including lights and signs
3. All planting, including mulch installation and weed control of planted areas. a) For sodded turf, upon sod installation
b) For seeded turf, upon second mowing as described in Section 329000, Part 3.11.
4. The irrigation system is fully functioning as designed and as confirmed by the landscape irrigation audit.
B. Within five workings days of receipt of notification, the Parks Construction Inspector will confirm substantial completion. The Parks Construction Inspector will schedule the punch list walk (pre-final review) within five working days after the project has been determined as substantially complete. A formal punch list will be developed at the punch list walk. The Parks Construction Inspector will provide a copy of the formal punch list to the Contractor within five working days of punch list walk. Performance of the punch list walk does not automatically trigger the start of establishment.
1. If at any point during this review it becomes apparent the Contractor has not properly prepared for the site review, the inspection shall immediately be terminated and re-scheduled at such a time as the site has been readied for a review. Any costs for the re-scheduling of the review shall be the responsibility of the Contractor. Lack of site preparation could delay start of the establishment period.
C. Concurrent to the pre-final review, the City will make a formal request for all required turn-in items to be submitted to the City. All turn-in items shall be submitted in their entirety to the City’s Park Construction Inspector. Partial turnin packages will be rejected.
D. Once all turn-in items have been confirmed to be complete and accurate, the establishment period may be considered to begin. The City shall have sole discretion in determining the appropriateness of the commencement of the establishment period and shall notify the developer/contractor in writing of the
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 01 10 00: Summary of Work
start and end dates. Portions of the project will not be accepted for establishment prior to the substantial completion of the entire project.
1.17 Establishment Period
A. The duration of the establishment period shall be:
1. For seeded turf in parks: Ninety (90) calendar days, minimum, and until the Notice of Completion (NOC) for City-built parks has been approved by the City Council, or the deed transferring property ownership, has been recorded at the County for Developer-built parks.
2. For sodded turf in parks: Forty-five (45) calendar days commencing between March 1st and October 31st and sixty (60) calendar days commencing between November 1st and February 28th, and until the Notice of Completion (NOC) for City-built parks has been approved by the City Council, or the deed transferring property ownership, has been recorded at the County for Developer-built parks.
3. For streetscapes: Thirty (30) calendar days, minimum, and until final acceptance of all related street improvements subject to approval of a Notice of Completion by the City Council. The inclusion of large box trees (36” box and greater) may require an extended establishment period of ninety (90) calendar days, as noted on plans.
B. Active maintenance is required throughout the entire establishment period.
Active maintenance is defined as:
1. All areas within the project site shall be protected against damage including vandalism, erosion, trespass, rodents and other acts. Immediately repair all damaged areas.
2. All walkways and paved areas shall be kept clean and all debris within planting and turf areas shall be immediately removed.
3. Automatic irrigation controller shall be fully utilized and irrigation system monitored and adjusted as described in Section 32 84 00 4.03.
4. All plant and turf maintenance as described in Section 32 90 00 3.11 C. Prior to the start of the final thirty (30) days of establishment:
1. All punch list items shall be completed.
2. All certifications and testing shall be completed.
3. All plantings and turf shall be thriving and in a healthy condition.
4. The lack of active maintenance prior to the final thirty (30) days may constitute a delay in the start of the final thirty (30) days of the establishment period.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 01 10 00: Summary of Work
1.18 Final Review
A. One (1) week prior to the end of the establishment period, a final on-site review shall be conducted to review project readiness for final turn-over. All punch list items must be satisfactorily addressed prior to the final review.
B. The project shall be prepared and cleaned per Section 2 - 1.12 of the General Conditions; the turf shall be mowed; and the irrigation heads shall be adjusted appropriately one day prior to the scheduled final review.
C. Acceptance of the project shall be considered “field accepted” and a recommendation will be forwarded to the City Council for “final acceptance” per Section 7 - 1.01 of the General Conditions.
D. An unaccepted project shall extend the establishment period until such time as the unaccepted portions of the project have been reviewed and field accepted by the Inspector and Project Manager.
E. Turn over for City maintenance shall occur only after:
1. The specified duration of the establishment period has been successfully completed.
2. If required, the deed transferring property ownership, has been recorded at the County.
3. A Notice of Completion (NOC) for city-built parks and for streetscapes has been approved by the City Council.
F. Contractor shall provide a written guarantee covering all improvements associated with this project. See 1.19 – Warranties and Guarantees.
1.19 Record Documents
A. Record documents or as-built plans shall be maintained on-site and updated routinely as specified in Section 2 - 1.13 of the General Conditions. Record documents shall include all items under the contracted scope of work.
B. Record documents shall be submitted:
1. two sets 11 x 17 laminated reductions of the irrigation plan illustrating with colors the individual controller stations; and
2. Electronically submit PDF scanned images (in color) of the verified/initialed as-built drawings.
3. For City of Roseville CIP projects, SWPPP binder.
1.20 Warranties and Guarantees
A. Warranties are required under various Sections of these Specifications. Prior to final acceptance, the Contractor shall combine all warranties into a single electronically submitted PDF, . All warranties shall be clearly labeled and the number of years highlighted. Also, see Sections 7 - 1.10 and 7 - 1.11 of the General Conditions.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 01 10 00: Summary of Work
1. Warranties for equipment shall be submitted in the manufacturer’s standard form and shall be countersigned by the subcontractor or supplier and the Contractor.
2. All other warranties shall be provided in the following format, written on subcontractor’s or supplier’s letterhead, signed by the subcontractor or supplier and countersigned by the Contractor:
WARRANTY FOR YEARS
“We hereby warrant that the product which we have installed at project name has been done in accordance with the contract documents, and that the work, as installed will fulfill the warranty requirements included in the Specifications.
We agree to repair or replace any or all of our work, together with any other adjacent work which may be displaced by so doing, that may prove to be defective in its workmanship or material within the warranty period stated above commencing from the date of final acceptance of the above named project by the City of Roseville’s City Council, without additional expense to the City, ordinary wear and tear and unusual abuse or neglect excepted.
In the event of failure to comply with the above conditions within thirty (30) days of notification by the City, we collectively or separately do hereby authorize the City to proceed with the repairs or replacement of such defects at our expense. Payment of said costs and charges will be forwarded to the City upon demand.
Signed:
Subcontractor or Supplier Date
Countersigned:
Contractor Date
B. Guarantees shall be a minimum of one (1) year for all plant material, including trees and shrubs. The guarantee shall state that plant materials (trees & shrubs) to be free of all defects or disease and all plants are in a healthy and thriving condition at the completion of the contract. Deciduous plant material shall be warranted beyond the time of contract completion until such time as growth becomes evident.
PART 2 - PRODUCTS
Intentionally left blank.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 01 10 00: Summary of Work
PART 3 - EXECUTION
Intentionally left blank.
END OF SECTION
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 01 57 23: Storm Water Pollution Control
SECTION 01 57 23
STORM WATER POLLUTION CONTROL
PART 1 - GENERAL
1.01 General
A. The requirements set forth in the General Conditions shall be in addition to the standards provided herein.
B. The requirements set forth in the Special Conditions shall be in addition to the standards provided herein.
1.02 References
A. State Water Resources Control Board Order No. WQ 2022-0057 DWQ National Pollutant Discharge Elimination System General Permit No. CAS0000002, for Storm Water Discharges Associated with Construction and Land Disturbance Activities.
B. CASQA California Stormwater BMP Handbook – Construction, October 2024.
1.03 Definitions
A. NOI: Notice of Intent
B. NOT: Notice of Termination
C. QSP: Qualified SWPPP Practitioner
D. QSD: Qualified SWPPP Developer
E. SWPPP: Storm Water Pollution Prevention Plan
F. SWRCB: State Water Resources Control Board
G. NPDES: National Pollutant Discharge Elimination System H. WDID: Waste Discharger Identification number
I. BMP: Best Management Practices
PART 2 - PRODUCTS
Intentionally left blank.
PART 3 - EXECUTION
3.01 SWPPP
A. Comply with State Water Resources Control Board Order No. WQ 2022-0057- DWQ National Pollutant Discharge Elimination System General Permit No.
CAS000002, for Storm Water Discharges Associated with Construction and Land Disturbance Activities.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 01 57 23: Storm Water Pollution Control
B. A SWPPP has been developed for this project. The SWPPP is a dynamic document and will change as conditions (weather or construction phases) warrant.
C. Implementation of the SWPPP is the responsibility of the Contractor and a part of this project. Costs associated with implementation and maintenance of the BMPs per the SWPPP shall be included in the lump sum base bid.
D. Major changes to the SWPPP shall be reviewed by the City’s QSD prior to implementation. Cost associated with the major changes will be paid for using the unit cost listed in the Additions or Deletions Sheet of the Proposal E. The City’s QSD/QSP will perform weekly inspections of the jobsite.
Implementation of and minor changes to the SWPPP as directed by the City’s QSP shall be incidental to the Work. Contractor shall start all inspection corrective actions within 72 hours of observation, and complete as soon as possible.
F. All BMPs installed will be inspected by the City’s QSD/QSP for compliance with the SWPPP and BMP Fact Sheets. BMPs that are not in compliance shall be brought into compliance by the Contractor at no cost to the City.
G. An electronic copy of the SWPPP will be provided to the contractor. The contractor shall keep a binder on-site for inspection reports, and will make the inspection binder available upon request.
H. The SWPPP shall be readily available throughout the course of construction and until the NOT has been accepted by SWRCB. The SWPPP shall be made available upon request by a representative of the Regional Water Quality Control Board, State Water Resources Control Board, United States Environmental Protection Agency, or City’ storm water staff.
I. At the end of the establishment period, the Contractor shall submit copies of all inspection reports and sampling and analysis results to the City’s Project Manager.
3.02 Schedule
A. Contractor shall develop a Water Pollution Control Schedule that describes the timing of grading or other work activities that could affect water pollution. The schedule shall be updated by the Contractor to reflect changes in the Contractor’s operations that would affect the necessary implementation of water pollution control practices. The typical sequence of work shall be adjusted by the Contractor based on weather conditions and forecasted rain events. The schedule is considered an appropriate and applicable BMP.
3.03 Penalties and fines
A. Contractor is responsible for all penalties and fines assessed to or levied on the project related to the implementation of the SWPPP.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 01 57 23: Storm Water Pollution Control
B. In an effort to maintain compliance with the General Permit, the Contractor may be asked to make changes to the BMPs. If the Contractor is unable to perform these services in a timely manner the City reserves the right to address any areas of concern and deduct the cost from the contract.
3.04 BMP’s
A. Construction BMP’s shall be installed per the Erosion / Sediment Control Plan and project SWPPP, and in accordance with the CASQA California Stormwater BMP Handbook. Use of alternative BMP’s will be reviewed and accepted at the discretion of the City’s QSD.
3.05 Cleaning
A. Thoroughly clean all areas where work has occurred. Remove from the site excess material, debris and rubbish.
B. Take all precautions to protect completed work. Immediately repair or replace all damaged areas due to tire ruts, erosion, compaction failure, etc. Keep all erosion control measures intact.
END OF SECTION
FOR COUNCIL APPROVAL ONLY
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 03 30 00: Site Concrete
SECTION 03 30 00
SITE CONCRETE
PART 1 - GENERAL
1.01 General Requirements
A. The requirements set forth in the General Conditions shall be in addition to the standards provided herein.
B. The requirements set forth in the Supplemental Conditions shall be in addition to the standards provided herein.
C. The standards set forth in the City of Roseville Design and Construction Standards and the City of Roseville Parks Construction Standards, latest editions, shall be in addition to the standards provided herein.
1.02 Description
A. Furnish all labor, materials and equipment for the complete installation of all concrete work, flatwork and poured-in-place as shown in the Plans and as specified herein.
1.03 References
A. Caltrans Standard Specifications, latest edition.
B. California Building Code (CBC) and California Administrative Code (Title 24), latest editions.
1.04 Quality Assurance
A. For all flatwork, the Contractor shall pour a six-foot by six-foot (6’ x 6’) sample of each type of finish specified for review and acceptance by the Project Manager prior to pouring any concrete. The accepted samples shall remain onsite and intact until all concrete work has been completed. The quality of the concrete work shall be measured by the accepted samples.
B. During the course of construction, a qualified testing laboratory shall obtain samples as determined by the Inspector and conforming to federal and state codes and standards. Such costs shall be paid for by the City. Re-tests and removal of below acceptable strength concrete shall be borne by the Contractor.
The Contractor shall cooperate with the testing during the course of obtaining such samples.
C. Variances in surface grades of more than 1/8”, as measured by a straight edge ten feet (10‟) long, shall be corrected to the satisfaction of the Inspector.
Remove all areas where standing water occurs, including any surface irregularities.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 03 30 00: Site Concrete
1.05 Handling and Storage
A. Comply with ASTM C-94, “Specifications for Ready Mix Concrete” for the batch, mix and transport of concrete.
B. Mix and deliver only the amount that will be poured immediately.
1.06 Record Drawings
A. The Contractor shall keep an accurate record of the as-built conditions of the site concrete. These records shall be updated daily and kept at the construction site. At any time, the Inspector may examine the conditions of the “as-builts” to ensure compliance of the above.
PART 2 - PRODUCTS
2.01 Concrete
A. Concrete for play area curbs, sidewalks, and accessible ramps shall conform to the provisions of Section 90-2 “Minor Concrete” of the Caltrans Standard Specifications. Cementitious material shall be „Type II Modified” and shall contain no less than 505 pounds of cementitious material per cubic yard.
Aggregate shall be not greater than one-inch or smaller than 3/8-inch. Submit concrete analysis for review and acceptance prior to placement of concrete.
2.02 Fiber Reinforcement
A. Fibers for concrete shall conform to ASTM C1116 Type III and manufactured specifically for the secondary reinforcement of concrete. Fiber length to be 0.50” or 0.75”. Acceptable products include Fibermesh 150, as manufactured by Sika USA, or accepted equal.
2.03 Expansion Joint Material
A. Fiber expansion joint shall conform to ASTM-1751 and shall be a nonextruding resilient filler. Filler shall have preserve attributes and high quality bituminous materials.
B. Apply Sikaflex elastomeric sealant, or accepted equal, over all expansion joints.
2.04 Concrete Forms
A. All forms shall be new at the start of the project.. Minimum size lumber shall be 2 x 6.
B. Radius bends shall be formed by spring steel forms or laminated boards, as required.
C. Plywood shall be 5/8”, Class I, exterior grade as outlined in APA “Guide to Plywood Grades”. Omit mill oiling treatment.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 03 30 00: Site Concrete
PART 3 - EXECUTION
3.01 Poured-In-Place Concrete
A. Concrete for hardscape or flatwork shall be placed on subgrade compacted per geotechnical engineer recommendations.. Prior to placement of concrete, a soils compaction test must be performed by an accepted soils testing professional on a representative number of locations along the flatwork area.
The City or project owner shall provide the initial test. The results of these tests must be available and meet acceptable levels prior to pouring. Re-tests and rework of any area, as directed by the soils professional, shall be the responsibility of the Contractor.
B. Construct forms to conform to the shapes, dimensions and details shown on the Plans. All forms shall be true to lines, plumb, level and square.
C. Forms shall not leak, spread, shift or settle when concrete is placed.
D. All forms shall carry dead and live loads and shall not deflect more than 1/8” between supports after placement of concrete.
E. All forms shall be thoroughly soaked a minimum of twelve (12) hours prior to pouring of concrete. Forms shall be treated per manufacturer’s recommendations.
F. Reuse of forms may be allowed at the discretion of the Inspector. Reused forms shall be cleaned and free of defects that would affect the final concrete finish.
G. Concrete footings shall be formed only when excavations slump or cave in.
Over-excavate the trench or footing diameter to accommodate the forms’ installation and removal. Apply water to moisten soil. Do not allow water to create mud or ponding.
3.02 Fiber Reinforcement
A. Install per manufacturer’s instructions. Apply at the batch plant prior to delivery.
Thoroughly mix fiber material to avoid “clumping”.
3.03 Expansion Joints
A. Expansion joints shall be placed where vertical elements meet horizontal paving unless otherwise noted on the Plans. This shall include vertical expansion joints on play area curb walls, buildings, shade structures, walls and/or planters. The corners of the paving shall be tooled at the expansion joints. Trim exposed fibers which protrude above or beyond the finish surface of paving or the finish surface of the wall.
3.04 Control Joints for Concrete Sidewalks
A. Control joints shall be per Parks Standard Details with deep, straight and finished with rounded edges. Control joints shall be placed (on-center) a
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 03 30 00: Site Concrete
distance equal to the width of the concrete walkway, unless otherwise shown on the Plans. For example a ten-foot wide walkway shall have control joints placed ten feet on center. Control joints shall not dead-end into an adjacent panel, and shall not create acute angles that are prone to break off.
3.05 Sawcutting of control joints shall begin as soon as the concrete surface has hardened sufficiently to resist raveling.
3.06 Placement of Concrete
A. Do not pour concrete in weather below 40 degrees F. or when temperatures are predicted to fall below freezing within 24 hours, except with prior authorization.
B. Concrete shall be transit mixed according to ASTM C-94. Discharge readymixed concrete from transport vehicle while the concrete is still plastic and before stiffening occurs.
.
C. Concrete shall be deposited up to the finished height of the forms and up to the adjacent joint. No partial pours will be allowed. Excess material shall be dumped on-site and later removed by the Contractor.
D. Thoroughly consolidate the concrete by manually spading and tamping concrete into all corners of the forms and by utilizing a high-speed mechanical vibrator. Retain a standby vibrator on-site during the course of concrete work.
When utilizing the vibrator, take precautions to avoid impact on the forms.
E. After obtaining uniform consolidation, screen tamper all flatwork surfaces, screed and bull float to ensure that large aggregates are pushed below the surface. When it is practical to work on the surface, wood float, steel trowel paving to a uniform surface.
F. Concrete elements shall not exceed the following tolerances:
1. Linear: 1/8”
2. Slab deviation: 1/8” in 10’
3.07 Finishes
A. Finishes shall be as shown on the Plans and shall be consistent in quality throughout the project. No visible cracks or discoloration will be accepted.
Finishes on vertical surfaces shall be consistent throughout. Vertical expansion joints are spaced as identified on the plans and are smooth with the finish surfaces. All edges for flatwork and vertical surfaces shall be eased at a consistent radius.
B. Upon completion of float finishing, provide the final finish as follows:
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 03 30 00: Site Concrete
1. Medium Broom Finish: shall be accomplished by pulling a stiff bristle broom across a floated surface. The direction of the broom shall be perpendicular to the path of travel, unless otherwise shown on the Plans.
3.08 Removal of Forms
A. Form removal timing to be based on the concrete set strength and environmental conditions unless specifically called out on the drawings.
B. Remove all bolts, nails, ties, wires, etc. a minimum of one inch (1”) below the surface of the concrete. Remove imprints, irregularities or other such defects and patch as directed by the Inspector.
3.09 Curing and Protection
A. Allow adequate time for the concrete to cure. Contractor to take necessary steps to minimize evaporation and maximize the process of hydration.
B. Protect all concrete from damage during the curing period. Should damage occur, Contractor shall take immediate action to repair damage or replace damaged concrete to the satisfaction of the City.
3.10 Clean-Up
A. During the course of this work, the area shall be kept clear and free of debris as realistically as possible. Upon completion of concrete work, completely remove from the site all used forms, hardware, spillage, rejected work and other materials.
B. Remove from site furnishing posts all concrete “slobber”. Re-touch posts as necessary for a clean finish.
END OF SECTION
FOR COUNCIL APPROVAL ONLY
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 04 20 00: Unit Masonry (General)
FOR COUNCIL APPROVAL ONLY
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 05 12 00: Structural and Miscellaneous Steel (General)
FOR COUNCIL APPROVAL ONLY
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 09 91 00: Painting and Finishes (General)
FOR COUNCIL APPROVAL ONLY
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 12 93 00: Site Furnishing
SECTION 12 93 00
SITE FURNISHINGS
PART 1 - GENERAL
1.01 General Requirements
A. The requirements set forth in the General Conditions shall be in addition to the standards provided herein.
B. The requirements set forth in the Supplemental Conditions shall be in addition to the standards provided herein.
1.02 Description
A. Furnish all labor, materials and equipment for the complete installation of all site furniture, including play equipment and play surfacing, as shown on the Plans and as specified herein.
1.03 References
A. All play equipment shall meet or exceed the standards set forth by the Consumer Product Safety Commission (CPSC), comply with the Americans with Disabilities Act (ADA), meet all current ASTM standards and be consistent with State and local codes.
B. The play area surfacing shall meet or exceed the fall absorption/impact rates set forth by the CPSC guidelines and ASTM standards. The surfacing shall be an accessible surface and manufactured specifically for play areas.
C. Nothing in the Plans or Specifications is to be construed to permit work not conforming to regulating codes and standards. The Contractor shall furnish without extra charge any material and labor, when required, by the compliance with these rules and regulations, even though the work was not mentioned in these particular Specifications or shown on the Plans.
D. The product manufacturer shall supply complete Specifications for the installation of all site furnishings, including play equipment and play surfacing.
1.04 Submittals
A. Submittals for specified items are required. The Contractor shall submit a materials summary sheet indicating which items will be installed as specified and which items are proposed for substitutions. The Contractor shall submit proof of order within ten (10) working days of the Notice to Proceed, indicating all specified materials have been ordered, noting “as specified” or “substitution proposed”. For the following items, also provide:
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 12 93 00: Site Furnishing
1. Play Equipment and Swings submittals shall include color samples, manufacturer’s materials and parts list, and installation instructions.
2. Shade Shelter submittal shall include color samples, manufacturer’s materials and parts listed, and installation instructions.
3. All items with “color as selected by City” shall include color samples.
B. On the date of the Notice to Proceed, the Contractor shall immediately place the order to purchase all site furnishings, including the play equipment and play surfacing as specified on the Plans and as outlined herein. Proof of all orders shall be submitted to the Project Manager within ten (10) working days of the Notice to Proceed.
C. The Contractor shall submit a Certificate of Compliance from a third party certified playground inspector which verifies that the entire playground, including individual components, and surfacing meets or exceeds regulated requirements as described in Section 1.03 above.
1.05 Record Drawings
A. The Contractor shall keep an accurate record of the as-built conditions of the miscellaneous site amenities. These records shall be updated daily and kept at the construction site. At any time, the Inspector may examine the conditions of the “as-builts” to ensure compliance of the above.
PART 2 - PRODUCTS
2.01 Materials
A. Play Equipment shall be custom configuration as shown on the Plans and as specified herein. The equipment shall be as distributed by All About Play, contact Glen Wurster, 916-923-2180, and as manufactured by Little Tikes Commercial or accepted equal. Color as selected by the City.
B. Swings shall be the custom configuration as shown on the Plans as distributed by All About Play, contact Glen Wurster, 916-923-2180, and as manufactured by Little Tikes Commercial, or accepted equal. Color as selected by the City.
C. Engineered wood fiber shall be clean, engineered wood fiber, manufactured specifically for play areas.
1. Engineered wood fiber manufacturer shall provide testing certification by an independent testing agency that the results comply with CPSC guidelines and ASTM standards.
2. Engineered wood fiber shall meet the following requirements: ASTM F1951- 99 (ADA Compliance Test) and ASTM F 1292-96 (Shock Absorbency).
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 12 93 00: Site Furnishing
3. Manufacturer shall provide a Certificate of Insurance that shall provide coverage for products liability with the limit of liability not less than $1,000,000.
4. The manufacturer shall also provide written guarantee for three (3) years from the date of installation against decay and biochemical degradation calling for replacement of defective materials during the guarantee period.
5. Manufacturer certifies that the engineered wood fiber has been installed in not less than three (3) sites for periods of not less than three (3) years demonstrating the claims made with regard to these Specifications.
D. Picnic Tables shall be as shown on the Plans and as specified herein. The tables shall be as distributed by All About Play, contact Glen Wurster, 916-923- 2180,, and as manufactured by MyTCoat or accepted equal. Tables shall be in-ground mount and made of perforated steel. Color as selected by the City.
E. Benches shall be as shown on the Plans and as specified herein. The benches shall be as distributed by All About Play, contact Glen Wurster, 916-923-2180,, and as manufactured by MyTCoat or accepted equal. Benches shall be made of perforated steel and surface-mount, unless otherwise specified on plans. .
Color as selected by the City.
F. Drinking Fountain shall be MDF #10145 SM (bottle filler, dual bowl and accessible) and stainless steel surface carrier as distributed by Husbands and Associates (800) 821-9838 and as manufactured by Most Dependable Fountains or accepted equal. Color to be stainless powder coated black or as approved. Include recessed hose bib with locking cover, stainless steel control valves with O-rings, and external stainless steel surface mount carrier.
G. Park Identification Sign shall be fabricated by Quick Crete Products Corp., Norco, CA, (916) 447-8644, or by Outdoor Creations, Inc., Anderson, CA, (530) 365-6106, or accepted equal.
H. Play Area Age-Appropriate Signage shall contain the following language:
“This play area has been designed for the use of children aged 5-12 years of age.”
I. Park Namesake Plaque shall be a 24” by 18” digital high pressure laminate graphic panel fabricated or accepted equal. Plaque shall be mounted on a SlimLine single pedestal sign system or accepted equal. Manufacturer for the plaque and sign system (model # 2418 SL-SLP-AL) is KVO Industries (Chris Howell, (707) 573-6868). Installation location shall be verified in the field with the Project Manager.
J. Playground rules sign shall be as fabricated by Gopher Sign Company, (651) 698- 5095, or accepted equal.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 12 93 00: Site Furnishing
K. Line Paint (for basketball courts): Hawker - Laykold; Koch Materials - Decocolor; Extol - Color; L&M - Nova acrylic; California Products Corp - Plexicolor Laykold; or accepted equal.
L. Trash Receptacle shall be as shown on the Plans and as specified herein. The trash receptacle shall be as distributed by All About Play, contact Glen Wurster, 916-923-2180, and as manufactured by MyTCoat, model number RDW32-D02-002 or accepted equal.
M. Shade Shelter shall be as shown on the Plans and as specified herein. The Shade Shelter shall be as distributed by Miracle Play systems LLC, contact Shana Friesen, [email protected], and as manufactured by Poligon, or accepted equal. Color as selected by the City.
N. Basketball Standard shall be as shown on plans and as specified herein. The Basketball Standard shall be distributed by Miracle Playsystems LLC, contact Shana Friesen, [email protected] and as manufactured by Patterson Williams or accepted equal.
1. Post shall be Patterson Williams, model # 1513G, dual post, 3 ½” O.D. post, 6’ offset galvanized,
2. Backboard shall be Patterson Williams, model # 26 (LA-26), 45” H x 60” W rectangle backboard, heavy duty ¼” thick steel, powder coated white, with targe and perimeter
3. Rim shall be Patterson Williams, model # 44 (LA-44), heavy duty double rim for chain net with universal mount plate.
PART 3 - Net shall be Patterson Williams, model #35, super chain netEXECUTION
3.01 Installation
A. Contractor to provide experienced workers or subcontractors to install all site furnishings, including the play equipment and play surfacing described in these Specifications. The workers or subcontractor must demonstrate that at least five (5) similar play structures and five (5) play surface applications similar to that specified for this project have been installed in the last three (3) years.
B. All site furnishing, including play equipment shall be installed per manufacturer’s instructions.
C. Engineered wood fiber shall be blown in place to avoid damage to adjacent improvements unless specifically approved by City.
D. Heights of tables and benches shall be as follows, unless otherwise required by ADA; California Title 24 or other code requirements:
Description Height Above Finish Grade
Table Surface Height 34” Maximum
Knee Space Height 27” Minimum Clear Space
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 12 93 00: Site Furnishing
Knee Space Depth 17” Minimum from edge of table to nearest obstruction under table top
Width of Knee Space 30” Minimum clear width beneath table Bench Surface Height 16” Minimum, 18” Maximum
E. Heights for play equipment, including ramps and transfer decks shall comply with the approved recommendations by the U.S. Architectural and Transportation Barriers Compliance Board: Play Facilities Regulatory Negotiation Committee.
F. For play equipment, locate all footings prior to installation of drain lines. Adjust drain lines to accommodate play structure footings. Provide appropriate fall zones as shown on the Plans and per applicable codes and guidelines.
G. All footings shall be Class A concrete with 3/4” maximum size aggregate, unless otherwise noted. Footings shall be in accordance with Caltrans Standard Specifications, Section 90. Install all footings below finish surface. In paved areas, install paved surface over footing for a clean finished surface as shown on the Plans.
H. Carefully install all furnishings and equipment without disturbance to adjacent finishes. Contractor shall be responsible for the damage and subsequent repairs of damaged finished product.
I. Install park namesake plaque. Installation location shall be verified in the field with the Project Manager.
J. Install age-appropriate stickers on all play structures, per manufacturer’s instruction.
K. Install playground rules sign. Installation location shall be verified in the field with the Project Manager.
3.02 Cleaning
A. Thoroughly clean all areas where work has occurred. Remove from the site excess material, debris and rubbish.
B. Take all precautions to protect completed work. Immediately repair or replace all damaged areas due to tire ruts, erosion, compaction failure, etc. Keep all erosion control measures intact.
PART 4 - WARRANTY
4.01 General
A. Contractor shall warranty all site amenities included under this Section.
B. Contractor shall also provide a written warranty covering all materials, equipment and workmanship furnished by him to be free of all defects after installation is accepted, including all defective parts that may have been found.
C. Submit written warranty on company letterhead addressed to the City when providing As-built drawings.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 12 93 00: Site Furnishing
D. Contractor shall submit to the City, upon completion of work, a Certificate of Compliance by a third party certified playground inspector for the installation of the play structure and safety surfacing. Certification shall include testing for compliance of ASTM 1292 (Impact Attenuation of Surfacing Systems under and around Play Equipment). All tests, including re-tests, shall be the responsibility of the Contractor. Submit all test results to the City.
E. Submit maintenance manual for poured-in-place resilient surfacing.
F. Contractor shall submit to the City, upon completion of work, a Certificate of Compliance from the manufacturer of the play structure for the installation of the play structure.
G. Contractor shall submit to the City, upon completion of work, critical fall criterion used to certify all play surfacing material.
H. Attach cut sheets of installed items to the warranty.
END OF SECTION
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 26 00 00: Site Electrical
SECTION 26 00 00
SITE ELECTRICAL
PART 1 - GENERAL
1.01 General Requirements
A. The requirements set forth in the General Conditions shall be in addition to the standards provided herein.
B. The requirements set forth in the Special Conditions shall be in addition to the standards provided herein.
C. The standards set forth in the City of Roseville Design and Construction Standards, latest edition and requirements outlined by the City of Roseville Electric Department shall be in addition to the standards provided herein.
D. The standards set forth in the latest edition of the California Electrical Code (CEC), incorporating the latest edition of the NEC with City of Roseville amendments shall be in addition to the standards provided herein.
1.02 Description
A. Furnish all labor, materials and equipment for the complete installation of site electrical as shown in the Plans and as specified herein.
B. Submittals shall be required for requested substitutions or plan deviations ONLY. The Contractor shall install all specified electrical fixtures, poles and equipment, unless otherwise accepted and determined as an equivalent.
1.03 References
A. Conform to requirements outlined in the latest editions of the California Electrical Code (CEC), California Administrative Code (Title 24), California Building Code (CBC), California Administrative Code (Title 22) and other applicable codes.
B. Conform to requirements outlined in the latest edition of the Roseville Electric Specifications for Commercial Construction.
1.04 Record Drawings
A. Record drawings are required as a part of this work. At all times, the Contractor shall maintain accurate information of the work in progress. Deviation in layout of conduit or other materials shall be recorded to the satisfaction of the Inspector. Upon completion of the project, as-builts shall be submitted to the City on reproducible plan sheets and shall depict all changes in a neat and legible manner.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 26 00 00: Site Electrical
PART 2 - PRODUCTS
2.01 Service Panels
A. Service panels shall meet the Roseville Electric approved sections of the EUSERC requirements. The list of acceptable panels can be found at https://the.euserc.org/s/Roseville-City-of-Acceptability-Pages.pdf B. Service panel shall be:
1. Built to UL508A standards
2. Metered
3. Single phase or three phase application
4. Rated for 120 to 480 volts
5. Color: Hunter Green
2.02 Electronic Astronomic Time Switch
A. Electronic Astronomic Time Switch shall be DWZ Model series, as manufactured by Tork, or accepted equal.
2.03 Conduit and Fittings
A. For primaries (12,000 volts), conform to Roseville Electric’s Specifications for Commercial Construction, latest edition.
B. All other conduit and fittings shall conform to the California Electric Code, latest edition.
2.04 Wires and Cables
A. Conform to the California Electric Code, latest edition.
B. All wires shall be copper only, 90-degree-C THHN/THWN insulation.
2.05 Wire Connections and Devices
A. Conform to the California Electric Code, latest edition.
B. Splices and joints for #10 AWG or smaller wiring shall be twisted together electrically and mechanically strong and insulated with approved type insulated electrical spring connectors, Scotchlok or Ideal. Joints and connections for #8 AWG or larger shall be made with Burndy, T & B, or approved equal, solderless tool applied pressure lugs and connectors. Uninsulated lugs and wire ends shall be insulated with layers of plastic tape equal to insulation of wire and with all irregular surfaces properly padded with "Scotchfil" putty prior to application of tape. Tape shall be equal to Scotch #33, General Electric #AW-1, or approved equal. Feeder splicing is not permitted.
C. Receptacles: 15 & 20 Amp 125 Volt receptacles shall be "Specification" grade, duplex, UL Listed, rated Weatherproof where installed outdoors or in damp or wet locations. Where only one receptacle is connected to a 20 ampere circuit, a 20 ampere receptacle shall be used. Receptacles to be Hubbell 5262 series,
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 26 00 00: Site Electrical
5362 series, or equal. Provide an equipment grounding jumper (pigtail) connecting the grounding terminal of the receptacle to the grounded box.
2.06 Outlet Boxes
A. Cast Metal boxes shall be cadmium plated, cast iron alloy by Crouse-Hinds Form 8 condulets, Appleton Form 35 Unilets or accepted equal.
B. Cast Metal Outlet boxes shall be four inch (4”) round, galvanized cast iron alloy with threaded hubs and mounting lugs as required. Boxes shall be furnished with cast cover plates of the same material as the box and neoprene gaskets by Crouse-Hinds VXF series, Appleton JBX series or accepted equal.
2.07 Pull and Junction Boxes
A. Per City of Roseville Electric Department’s Specifications for Commercial Construction, latest edition.
2.08 Parts Identification
A. Consistent with the City of Roseville Electric Department’s Specifications for Commercial Construction, latest edition.
2.09 Electrical Support Equipment
A. Concrete Fasteners shall be Philips “Red-Head” or accepted equal. Powder driven concrete pin fasteners, low velocity type shall be Remington, Ramset or accepted equal.
B. Conduit Straps shall be hot dipped galvanized, cast malleable iron, one hole type strap with cast clamp-backs and spacers (as required) by O-Z/Gedney No. 15-50G strap and #14G spacer, Efcor No. 231 strap and No.131 spacer or accepted equal.
C. Concrete Inserts shall be pressed galvanized steel, spot insert with oval slot capable of accepting support nuts of ¼ inch to ½ inch diameter thread by Unistrut No. M2506 series, Globestrut CSI series or accepted equal.
D. Construction Channel shall be 1-1/2 inch by 1-1/2 inch 12 gauge galvanized steel channel with 17/32 inch diameter bolt holes, 1-1/2 inch on center, in the base of the channel by Kindorf 905 series, Unistrut P-1000-HS or accepted equal.
E. Cable Ties and Clamps shall be one piece, nylon, reusable type lashing tiesby Thomas and Betts Co “Ty-Raps”, Panduit “Pan-Ty” or accepted equal.
F. General Fasteners shall be wood screws for fastening to work; machine screws for fastening to steel; toggle bolts for fastening to gypsum board or plaster walls; expansion anchors for attachments to pre-poured concrete.
G. GFI Outlet Cover shall be metal, lockable, and flush with the surface it is installed in. Cover must conform to the California Electric Code, latest edition.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 26 00 00: Site Electrical
2.10 Fixtures and Poles
A. Pathway/Security lights shall be:
1. LED: Hadco: RL54 B B N N 1 A W N N N A 2 N N N N SP1
2. Pod: die-cast aluminum housing with tool-less access
3. Globe: clear prismatic injection molded U.V. stabilized acrylic
4. Symmetric photometric distribution
5. Rated 120 volts
B. Poles shall be:
1. Whatley: TR34 16 DE BLK TXT 30-30 or accepted equal
2. Fiberglass, direct burial
3. Textured round, tapered
4. 16’ mounting height
5. Include –RC receptacle on select poles only, as shown on plans
2.11 Tracer Wire
A. Insulated solid copper wire, minimum #12 gauge.
PART 3 - EXECUTION
3.01 Installation
A. Install (luminaire and poles) in accordance to manufacturer’s instructions.
B. Ensure proper handling and installation of fixtures including hardware necessary for a complete installation. Fixtures (luminaire and poles) shall be clean, plumb and level.
C. All lamps shall be new and in operating condition. New lamps shall have less than 100 hours of operation on-site.
D. All splices in exterior fixtures or fixture outlet boxes shall be made watertight, using specified epoxy resin splicing kits.
E. Operate the entire system, once complete, in the presence of the Inspector.
Immediately correct any improper connections or other items.
F. Install concrete collars around light poles. Concrete collars shall be per the Parks Construction Standards, latest edition.
G. Install tracer wire on top of conduit for all up-lighting and sports field lighting.
3.02 Clean Up
A. At all times, maintain a safe and clean work site, free of debris and rubbish.
B. All electrical parts shall be clean of conductive and deleterious materials.
C. All enclosures shall be free of dirt and debris.
D. Clean all finishes and touch up damaged areas prior to pre-final inspection.
3.03 Excavation & Backfill
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 26 00 00: Site Electrical
A. Refer to Section 33 00 00 Utilities.
3.04 Equipment Pads
A. Concrete reinforced pads for mounting of equipment (i.e. switchboard, transformers, freestanding panels, etc.) shall be minimum 3000psi, 6" thick with #4 rebar at 12" on center each way. Rebar shall be centered in pad. Pad shall extend 2" beyond equipment and 1.5" above surrounding area. Backfill and compact to 95% maximum dry density at optimum moisture content in layers not to exceed 6" when compacted.
3.05 Grounding
A. Grounding and ground bonding of the electrical installation shall be in accordance with CEC Article 250, and any applicable codes. Ground fittings shall be approved manufactured type, installed and connected to conform with Code requirements.
B. Neutral conductors and noncurrent-carrying parts of equipment at each installation shall be grounded in accordance with applicable code. Ground conductor shall be copper having a current capacity sized in accordance with CEC.
C. All equipment cases, motor frames, etc., shall be completely grounded to satisfy requirements of CEC. Install bond wire in flexible conduit. Install copper bond wire, sized in accordance with CEC, in all nonmetallic raceways and bond to all metallic parts using approved fittings.
D. Service ground conductor shall be connected to a "Ufer" encased ground and bonded to the metallic cold water pipe system and to the metallic natural gas line. 5/8” x 10 ft copper clad ground rods may be used in lieu of the Ufer ground where no footing is available.
E. All connections shall be made with solderless connectors or molded fusionwelding process.
F. Equipment grounding conductors shall be insulated with a continuous green outer finish along its entire length. Conductors size #4 AWG and larger may be identified (with green electrical tape applied half-lapped) at each end and at every point where the conductor is accessible. Tape shall be applied from its point of entry to point of exit or termination.
G. Insulated grounded (neutral) conductors shall be identified with a continuous white outer finish along its entire length. Neutral conductors #4 AWG or larger can be identified by a distinctive white marking (applied half-lapped with white electrical tape) for the last 12 inches at each end.
3.06 Field Testing
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 26 00 00: Site Electrical
A. Perform Insulation Resistance (IR) "Megger" Testing per NETA Standards.
Submit test results. Provide testing for:
1. All feeders 100 Amps and higher.
2. Branch circuits 100 Amps and higher.
B. Each ground rod shall be tested. A ground rod which does not have a resistance to ground of 25 ohms or less shall be augmented by one additional ground rod at no less than 8 feet from each other.
3.07 Consultant to complete.
END OF SECTION
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 31 10 00: Clearing and Grubbing
SECTION 31 10 00
CLEARING AND GRUBBING
PART 1 - GENERAL
1.01 General Requirements
A. The requirements set forth in the General Conditions shall be in addition to the standards provided herein.
B. The requirements set forth in the Supplemental Conditions shall be in addition to the standards provided herein.
1.02 Description
A. Preserve and protect existing site amenities to remain, including, but not limited to, trees, shrubs, underground utilities and other improvements as shown on the Plans. Protection of work shall include affected improvements on adjoining properties.
B. Scope of work includes: site preparation, removal of debris, staging of equipment and materials and securing the site for construction.
1.03 Related Work
A. Section 31 20 00: Earthwork
B. Section 01 57 23: Storm Water Pollution Control
1.04 Protection/Replacement
A. Prior to demolition, erect protective fencing a minimum of one foot (1’) beyond the canopy of all trees to remain. The radius of the canopy shall be measured from the longest branch furthest from the trunk. Refer to the environmental document for additional requirements for protective fencing on other existing natural features. For work within or near protected trees, a tree permit may be required.
B. If public use is to be maintained on unaffected portions of the project site, the Contractor shall be responsible for directing pedestrian and vehicular traffic safely around the construction zone. Utilization of temporary fencing, barricades, signage, etc. shall be the responsibility of the Contractor. Safe detours shall be available to the general public at all times during the course of construction.
C. Protection of existing site improvements shown to remain, including, but not limited to, fencing, signs, benches, picnic tables, play structures, shade structures, drinking fountains, concrete paving, concrete wall and curbs,
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 31 10 00: Clearing and Grubbing
decomposed granite paving, asphalt concrete paving, recreational site improvements, etc. are to be protected and preserved.
D. The Contractor shall be responsible for any damage to and maintenance of all existing street improvements, drainage facilities and irrigation systems and to re-establish these improvements to their original condition as soon as possible after completion of the work in the area, to the complete satisfaction of the Project Manager and Inspector. Realignments or modifications to the existing facilities as shown on the plans are accepted.
E. Survey monuments and markers either shown on the Plans or encountered during the course of construction shall be protected and preserved. The Contractor shall notify the Inspector upon discovery of an unmarked monument, at which time, arrangements for the relocation or adjustment of the monument will be determined. All costs associated with the relocation or adjustment of these monuments shall be the Contractor’s responsibility.
F. Burning or burying removed material on-site is prohibited.
G. Where the removal of specific material creates an open hole, pit, trench or other depression, the Contractor shall immediately backfill and compact the areas consistent with requirements outlined in Section 31 20 00 of these Specifications.
H. All items identified in the Plans to remain or identified in the field to remain, removed in error by the Contractor, shall be repaired or replaced to match in equal or better construction, at no cost to the City. The quality of the repair or replacement shall be measured as that existing at contract award.
PART 2 - PRODUCTS
Intentionally left blank.
PART 3 - EXECUTION
3.01 Pre-Construction Site Review
A. Contractor shall review existing site conditions with the Inspector prior to start of construction and document any conditions which adversely affect the satisfactory execution of the work and final acceptance of the project.
B. Commencement of work constitutes acceptance of existing conditions. The Contractor shall, at his expense, be responsible for correcting all unsatisfactory and defective work.
3.02 Clearing
A. Completely remove trees, shrubs, stumps, vines, rubbish/debris, undergrowth, deadwood, structures, and other elements identified to be removed and/or which interfere with the construction as shown on the Plans and as specified.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 31 10 00: Clearing and Grubbing
B. Obtain verification from the Project Manager for non-identified items scheduled to be removed prior to actual removal.
3.03 Grubbing
A. Remove all stumps, roots, grasses and weeds in its entirety. Apply systemic weed killer. Confirm weed kill prior to removal.
B. For projects with native soils, once surface material is removed, the Contractor shall stockpile the top twelve inches (12”) of topsoil for use during the final grading phase of work. This soil shall be free of rocks, debris, roots and other undesirable material.
3.04 Utilities
A. Contact USA North 811 at (800) 642-2444, or submit an online ticket at USANorth811.org, prior to commencement of any demolition or excavation work. Provide a minimum of 48 hours’ notice. Verify all utilities entering into and their locations within the project site.
B. Where utilities lie within the project site, but are not a part of the project, the Contractor shall cooperate with the agency or utility company having jurisdiction to maintain its use and the integrity of the structure.
C. Where utilities enter into the project site and taps, connections to or extensions of the utility are identified in the Plans, the Contractor shall coordinate all work with the agency or utility company having jurisdiction to minimize or eliminate disruption of use by the adjacent properties.
D. Verify that all utilities, shown to be removed on the Plans, are inactive and turned off prior to disconnection and/or re-routing, prior to demolition.
3.05 Debris Removal
A. All materials removed as a part of this contract shall become the property of the Contractor and shall be legally disposed of off-site, unless otherwise noted on the Plans.
B. Where a portion of a concrete slab, curb or wall and asphalt concrete paving or curb is to be removed, the concrete shall be cut with a concrete saw at a 90 degree angle so that the edge of the remaining concrete shall form a neat, straight line. Conform to the City of Roseville Design and Construction Standards, latest edition.
END OF SECTION
FOR COUNCIL APPROVAL ONLY
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 31 20 00: Earthwork
SECTION 31 20 00
EARTHWORK
PART 1 - GENERAL
1.01 General Requirements
A. The requirements set forth in the General Conditions shall be in addition to the standards provided herein.
B. The requirements set forth in the Supplemental Conditions shall be in addition to the standards provided herein.
C. The standards set forth in the Caltrans Standard Specifications, latest edition, shall be in addition to the standards provided herein.
D. The requirements set forth by CAL OSHA shall be in addition to the standards provided herein.
1.02 Description
A. Provide all labor, operations and materials necessary for earthwork, including, but not limited to, staking and surveying, grading; excavating; installation of facilities necessary to perform excavation and subsequent removal of such facilities upon completion of work; subgrade preparation; backfilling; and other incidental items necessary for a complete project.
B. This project is a balanced cut and fill project.
C. The intent of the grading plan is to provide positive drainage and to maintain slopes on walkways as required by the Americans with Disabilities Act and California Title 24 throughout the project site. The Project Manager shall be notified immediately of any discrepancies between the Plans and actual field conditions and/or conflicts between the design and code requirements.
1.03 Related Work
A. Section 31 10 00: Clearing and Grubbing
B. Section 33 00 00: Utilities
C. Section 32 84 00: Irrigation System
D. Section 32 90 00: Planting
E. Section 26 00 00: Site Electrical
F. Section 01 57 23 Storm Water Pollution Control
1.04 Quality Assurance
A. All work shall conform to local codes and regulations, including standards set forth in the Standard Specifications of the State of California, Business and
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 31 20 00: Earthwork
Transportation Agency, Department of Transportation (Caltrans), Chapter 70 of the Uniform Building Code and ASTM.
B. Relative compaction shall be the in-place dry density of soil denoted as a percentage of the maximum dry density of the same material. This shall be as determined by ASTM 1557. The optimum moisture is measured by the water content which corresponds to the maximum dry density.
C. Upon discovery of unforeseen subsurface site conditions, the Contractor shall notify the Inspector immediately.
D. Upon discovery of hazardous materials, cease all activity and immediately contact the Fire Department.
1.05 Protection
A. Provide and install all supports, shoring, bracing, underpinning, sheet piling and other methods for the sides of excavations necessary for ensuring safe working conditions for the workmen and to protect adjacent improvements to remain.
B. Provide any and all protection measures necessary to ensure the protection of the workmen, the general public, including children and the project site. These protection requirements remain the Contractor’s sole responsibility throughout the duration of the project, including non-working hours.
C. Do not obstruct vehicular, bicycle or pedestrian thoroughfares, unless previously accepted by the City. Provide safe and adequate detours around the construction as required by City and State regulations.
D. Trenches shall be covered at all times when work directly associated with the trenches is not occurring, including non-work hours.
E. During the course of construction, the Contractor shall ensure surface drainage does not create a nuisance onto adjacent properties.
1.06 Erosion Control Measures
A. Construction sites shall have required erosion and sediment control measures in place as required by the SWPPP. If construction is in progress, the Contractor shall ensure the construction site is prepared prior to the onset of any storm. At a minimum, erosion control measures shall include:
1. Broadcast seed
2. Drainage area protection
3. Dust/mud control
4. Drain inlet filters
5. Silt fence and straw wattles
6. Slope protection
7. Straw bales
8. Silt controlling devices
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 31 20 00: Earthwork
PART 2 - PRODUCTS
2.01 Base Rock
A. Class 2 aggregate base per Caltrans Standard Specifications, latest edition.
2.02 Drain Rock
A. Drain rock shall be Class 2 permeable, washed, unbroken stone or gravel.
Material gradation shall conform to the following:
Sieve Size Percent Passing
1 inch 100
No. 4 20-50
No. 50 0-10
No. 200 0-5
2.03 Pea Gravel
A. Pea gravel shall be natural stone, free of clay, shale or organic matter, and shall conform to the following:
Sieve Size Percent Passing
3/8 inch 100
No. 4 47
No. 8 2
No. 16 1
2.04 Fill
A. Structural Fill shall conform to Caltrans Standard Specifications or the accepted site-specific geotechnical report generated for the project.
B. Fill for non-structural areas shall conform to the following standards:
1. Plasticity: ASTM D4318-84
2. Expansion Index: No greater than twenty (20)
3. Testing: UBC 29-9 and ASTM D422-72
4. Particle Size: No greater than one inch (1”)
2.05 Topsoil
A. The top eight to ten inches (8” – 10”) of native soil containing more than three percent (3%) organic material. Topsoil shall be free of rocks no larger than one inch (1”) in diameter, free from subsoil, roots, heavy or stiff clay, course sand, destructive seeds, noxious chemicals, brush, debris, litter and other undesirable materials.
B. For any import soil to be used in turf/planting areas, submit a soils analysis with soil amendment recommendations (for plant growth) for review and acceptance prior to placement on-site. Soils test information shall be as outlined in Section 32 90 00: Planting – 1.06.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 31 20 00: Earthwork
2.06 Soil Sterilant
A. Sterilizer shall be standard, quick-acting, short-lived and non-selective weed and grass killer, commonly used under roadway/transportation projects.
Application of the sterilant shall pose no short or long term health threats to the installer or the general public. Submit analysis for approval prior to applying.
2.07 Sand
A. Granular, fine, free of organic matter, mica, loam or clay material.
PART 3 - EXECUTION
3.01 Construction Staking
A. The layout of all work shall be performed by a California State licensed land surveyor provided by the Contractor.
B. Notify the Inspector immediately of any discrepancies between actual field conditions and the Plans. Minor field adjustments may be necessary in order to fulfill the intent of the Plans.
C. Non-notification of discrepancies between actual field conditions and the Plans by the Contractor, in writing, shall indicate his acceptance of such field conditions. Adjustments/modifications to the construction to accommodate the inconsistencies (without notification) shall be at no additional cost to the City.
3.02 Excavation
A. All excavations shall be as noted on the Plans. Excavations shall include accommodation of base material.
B. Do not over-excavate. Excavations shall provide appropriate space to install shoring, bracing, formwork, etc., as needed to ensure the safe and proper construction of the work.
C. Take every precaution to prevent water from entering, softening, and undercutting excavated areas, including, pits, footings, trenches, etc.
D. Notify the Inspector immediately upon discovery of unsatisfactory soils materials or unforeseen site conditions. Excavation shall include the complete removal of the unsatisfactory material and its legal disposal thereof.
3.03 Site Grading
A. A grading permit is required to be obtained by the Contractor prior to commencing any earthwork.
B. Grading shall include adjacent transition areas, new elevations/contours as shown on the Plans. All subgrade areas shall be graded parallel to the finish grades and contours and shall be uniform in slope. Transition areas shall provide a smooth connection between new and existing grades and shall not create additional drainage or ponding onto adjoining properties.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 31 20 00: Earthwork
C. Surface grades shall provide for positive drainage away from structures and footings, and shall be uniformly smooth throughout.
D. Rough grading shall:
1. Be graded to a tolerance of 0.10 feet, plus or minus for planted and turf areas.
2. Be graded with a tolerance less than .04’ from specified grade and cross section for subgrade in which pavement, curbs and other structural elements are to be placed immediately above.
3. Provide a subgrade surface free of exposed rocks, stones and boulders.
4. Provide a subgrade surface free of depressions, pits, etc., with proper backfill and compaction. See paragraph 3.04 below.
3.04 Placement of Fill Material
A. Prior to placement of fill material, the Contractor shall:
1. Obtain approval of the subgrade surface from the Inspector.
2. Scarify, dry and compact soft and/or wet areas.
3. Remove and replace unsuitable subgrade material to the satisfaction of the Inspector.
4. Take all necessary corrective action.
B. Do not use topsoil as fill or backfill material, unless otherwise accepted in writing.
C. Fill shall be placed in the following manner:
1. Accepted engineered fill material for structural slabs and areas to be paved shall be placed in six-inch (6”) loose thickness, uniform layers over the entire area.
2. Fill material in planted areas shall be placed in twenty-four inch (24”) maximum loose thickness throughout the areas to receive fill.
D. Aerate or water each lift to obtain the required compaction rate indicated on the Plans. Thoroughly mix material to ensure proper moisture content for compaction. Repeat the operations until grades, as shown on the Plans, are obtained. Jetting of trenches shall be reviewed and accepted by the Inspector prior to performance of work.
E. Do not place fill when the subgrade is frozen, muddy or wet. Allow conditions to thaw and dry out before resuming operations.
F. Use hand tampers or vibrating compactors around foundations walls, retaining walls and other structural elements. Do not use large equipment in these areas and do not begin compaction operations until the bearing surfaces have reached its design strength.
G. Fill around existing trees to remain shall not exceed twelve inches (12”).
1. Minor fill (6” or less) shall utilize topsoil and shall be placed by hand. Do not cover crown of trunk. Feather grades to the extent possible.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 31 20 00: Earthwork
2. Fills between 6” and 12” shall utilize 3/4” pea gravel on grade, placed up to three inches (3”) below finish grade. Apply topsoil, by hand, to meet finish grade elevations. Feather grades to the extent possible.
H. Construct mounds from on-site material. The core of the mound (1’ below finish elevations) shall be compacted to 90%. The top twelve inches (12”) shall be compacted to 85%. Place topsoil in the top twelve inches (12”).
I. Place topsoil in all turf and planting areas a minimum of twelve (12) inches deep.
See Section 31 10 00, 3.03-B: Clearing and Grubbing.
3.05 Trenching, Backfilling and Compacting
A. For trenches greater than five feet (5’) in depth, submit an OSHA permit related to the work.
B. All trenches shall be straight, true and cut vertical at 90 degrees to the surface plane.
C. For trenches through existing paved surfaces, use a concrete saw or other tool to achieve straight, clean lines. Replace paved surface to the same or better condition as existing prior to cut.
D. Do not over-excavate. Maintain bearing surfaces true, level and undisturbed to the extent possible.
E. Trenches shall be kept dry and frost-free. Do not allow standing water to collect.
F. Do not allow trenches to remain exposed at any time when work directly related is not occurring. Cover all trenches during non-work hours.
G. Bedding for all trenches to receive pipes shall be as follows:
1. Bedding material shall be consistent with the City of Roseville Design and Construction Standards, latest edition.
2. Pipe shall lie completely on bedding. Pipe fittings or joints shall not bear weight.
3. Bedding shall be uniform throughout the length of pipe.
H. Initial backfill for storm drains, sewer lines and electrical conduit shall conform to the applicable City standard set forth by the Department having jurisdiction.
I. Backfill beyond the initial operations shall be native soil, placed in twelve-inch (12”) lifts. Compaction for trenched areas shall be 95% for parking lot, driveway and roadway areas; 90% for hardscape (i.e. walkways, picnic pads basketball and tennis courts); and 85% in areas to be planted. Place topsoil over trenches in planted areas. Upon completion, all trenches shall be filled flush with adjacent finish grades.
J. Compaction tests shall be required for trenched areas, hardscape areas and areas where fill over two feet in depth will be placed. The Inspector shall determine the number of tests and the locations. Re-tests shall be the Contractor’s responsibility.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 31 20 00: Earthwork
K. Potholing shall be required in areas where existing utilities are indicated. Hand digging may be required.
3.06 Soil Sterilant
A. Soil sterilant shall be applied to areas where paving is to be installed. The worker applying the sterilant shall take every precaution to avoid overspray of sterilant onto areas to be planted. The sterilant shall be placed no further than six inches (6”) beyond the edge of pavement.
B. Soil sterilant shall not be applied in inclement weather and windy days.
3.07 Drainage Areas
A. All bare areas, regardless of slope, within 50 feet of natural drainages shall be covered with straw and pressed in place.
B. No grading or trenching, except as required for erosion or sediment control, shall occur within 35 feet from the centerline of perennial and intermittent drainage swales between October 5 and April 1 unless approved by the Engineering Division, as well as any other governmental agency which may have additional jurisdiction and/or requirements.
3.08 Dust/Mud Control
A. Adjacent Streets: Adjacent street frontages shall be swept at least once a day to remove silt and other dirt which is evident from construction activities.
B. Construction Vehicles: The Contractor is responsible for cleaning construction vehicles leaving the site on a daily basis to prevent dust, silt, mud and dirt from being released or tracked offsite. Adjacent streets shall be swept clean daily.
C. Grading Spoils: Dry stockpiles of soil shall be watered to prevent the generation of airborne dust. Trucks transporting dry soil shall be covered with tarpaulins.
D. Water: Water shall be sprayed on all exposed earth surfaces during clearing, grading, earth moving and other site preparation activities. The exposed earth shall be watered throughout the day to minimize dust. The Contractor shall obtain a hydrant permit from the Environmental Utilities Department.
E. Wind Allowances: Grading activities shall be restricted or halted when winds exceed 15 miles per hour as deemed necessary by the Public Works Inspector.
END OF SECTION
FOR COUNCIL APPROVAL ONLY
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 12 16: Asphalt Concrete Paving
SECTION 32 12 16
ASPHALT CONCRETE PAVING
PART 1 - GENERAL
1.01 General Requirements
A. The requirements set forth in the General Conditions shall be in addition to the standards provided herein.
B. The requirements set forth in the Supplemental Conditions shall be in addition to the standards provided herein.
C. The standards set forth in the City of Roseville Design and Construction Standards and the City of Roseville Parks Construction Standards, latest editions, shall be in addition to the standards provided herein.
D. The standards set forth in the State of California, Title 24, Americans with Disabilities Act, latest edition, shall be in addition to the standards provided herein.
1.02 Description
A. Furnish all labor, materials and equipment for the complete installation of asphalt concrete paving, including international disabled signs as shown in the City Standard, as shown on the Plans and as specified herein.
1.03 References
A. Caltrans Standard Specifications for asphaltic concrete, latest edition.
1.04 Tolerances
A. All surface areas shall drain. Ponding, puddling or birdbaths are not acceptable.
B. Surface grades shall conform to the following:
Description shall not exceed, ... from indicated
line, grade or thickness
Base Course 0.1 foot +/-
Finish Surface 0.05 foot +/-
Thickness of finished
pavement
0.01 foot less
C. Flatness: maximum variance of 1/8” as measured with a ten (10) foot straight edge.
1.05 Testing
A. Testing shall occur during the installation of pavement. The number and frequency of tests shall be as determined by the Inspector.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 12 16: Asphalt Concrete Paving
PART 2 - PRODUCTS
2.01 Aggregate Base
A. Conform to Caltrans Standard Specification, Section 26 paragraph 1.02B, Class 2.
2.02 Asphalt Concrete
A. Conform to Caltrans Standard Specification, Section 39 and the City of Roseville Design and Construction Standards, latest edition.
2.03 Soil Sterilant
A. Sterilizer shall be standard, quick-acting, short-lived and non-selective weed and grass killer, commonly used under roadway/transportation projects.
Application of the sterilant shall pose no short or long term health threats to the installer or the general public. Submit analysis for approval prior to applying.
2.04 Striping
A. Traffic marker paint, in accordance with Caltrans Standard Specifications, Section 83-3.02.
B. Thermoplastic marking tape in accordance with Caltrans Standard Specifications, Section 84-2.02. (Required for bike trails)
2.05 Header
A. Per City of Roseville Parks Construction Standards, latest edition.
PART 3 - EXECUTION
3.01 Preparation
A. Upon completion of grading operations, compact the subgrade at the required elevation to a relative compaction density of 95%, unless otherwise noted on the Plans. A load or performance test shall be conducted in the presence of the Inspector prior to the placement of AC.
B. Apply soil sterilant per manufacturer’s directions. Limit the work zone of the sterilant application to the area to receive paving plus three feet (3’) on each side.
C. Completely install redwood header as shown in the City of Roseville Parks Construction Standards, latest edition, if shown on the Plans.
D. No material shall be placed in muddy conditions, nor shall any material be placed during or immediately after inclement weather, i.e. rain storms, temperatures below 35 degrees F, etc.
E. In areas where soil conditions are less than optimal, geotechnical tests shall be performed to verify compaction rates. The Inspector shall determine the
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 12 16: Asphalt Concrete Paving
number of tests necessary in order to verify conditions. Initial tests will be provided by the City. Re-tests shall be the Contractor’s responsibility.
3.02 Installation
A. Spread aggregate base material in six-inch (6”) lifts.
B. Compact base surface to a relative compaction of 95% and in accordance to the Caltrans Standard Specifications, Section 26.
C. Spread asphalt concrete material in accordance to the Caltrans Standard Specifications, Section 39.
D. Upon completion, apply water to the finished surface and allow water to runoff. All areas of ponding, puddling or birdbaths shall be filled with asphalt and fine aggregate. Conform fill surface with adjacent surface to the point edges are not visible.
E. Take every precaution to protect adjacent amenities or structures from material spillage or damage. In case of spillage or damage, the Contractor shall immediately repair or replace the damaged area to the satisfaction of the City.
F. Clean and oil all manhole covers, grates and other surface structures within the pavement area.
G. Clean all surface structures that lie within the asphalt concrete area.
3.03 Striping
A. Conform to the City of Roseville Design and Construction Standards, latest edition.
B. Ensure that all pavement to receive striping is completely cured. Clean all pavement surfaces.
C. Accurately lay out all pavement markings, including, parking stripes, centerline stripes, international disabled parking logo, striping for disabled access ramp, directional arrows, game court lines and other pavement markings as shown on the Plans or as required by code.
D. All pavement lines, striping and lettering shall be four inches (4”) in width, unless otherwise indicated on the Plans.
E. Lines painted with traffic paint shall receive two coats of paint. Allow each coat to dry completely prior to applying the second coat.
F. Apply all pavement markings on clean, dry surfaces, during weather conditions where temperatures are higher than 35 degrees F, no rain is occurring or predicted within the next twenty-four (24) hours, and the humidity is less than
80. G. Remove all excess adhesives and tracking onto unmarked areas.
H. All pavement striping applications shall conform to Caltrans Standard Specifications, Sections 84 and 85.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 12 16: Asphalt Concrete Paving
3.04 Protection and Cleaning
A. Do not allow equipment or vehicles to park on new asphalt surfaces upon completion operations. At his discretion, the Contractor may allow the parking of equipment and vehicles on the asphalt concrete AFTER the asphalt concrete material has been laid, passing applicable compaction tests and PRIOR TO applications of striping.
END OF SECTION
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 15 40: Decomposed Granite Paving
SECTION 32 15 40
DECOMPOSED GRANITE PAVING
PART 1 - GENERAL
1.01 General Requirements
A. The requirements set forth in the General Conditions shall be in addition to the standards provided herein.
B. The requirements set forth in the Supplemental Conditions shall be in addition to the standards provided herein.
C. The standards set forth in the City of Roseville Design and Construction Standards and the City of Roseville Parks Construction Standards, latest editions, shall be in addition to the standards provided herein.
1.02 Description
A. Furnish all labor, materials and equipment for the complete installation of decomposed granite paving, including redwood headers as shown in the Plans and as specified herein.
1.03 References
A. Caltrans Standard Specifications, latest edition.
1.04 Submittals
A. Submittals for specified items are not required; however, submittals are required for any proposed substitutions or deviations from the Plans or Specifications. Additionally, submittals are required for the specific items listed below. The Contractor shall submit a materials summary sheet indicating which items will be installed as specified and which items are proposed for substitutions. The Contractor shall submit proof of order within ten (10) working days of the Notice to Proceed, indicating all specified materials have been ordered, noting “as specified” or “substitution proposed”. Submittals are required on the following items:
1. Decomposed granite material and binding material: provide a sample “brick” for review and approval.
PART 2 - PRODUCTS
2.01 Crushed Quarry Rock
A. Crushed rock, graded between #4 and #200. Rock shall be high quality and well-graded.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 15 40: Decomposed Granite Paving
B. Hastie’s Capitol Sand and Gravel, Roseville, CA (916) 989-4600 or accepted equal.
2.02 Header
A. 1”x6”or 2”x6” Redwood header board.
2.03 Binding Material
A. PolyPavement, Los Angeles, CA (323) 954-2240 or accepted equal.
PART 3 - EXECUTION
3.01 Preparation
A. Upon completion of grading operations, compact the subgrade at the required elevation to a relative compaction density of 95%, unless otherwise noted on the Plans.
B. Completely install redwood header as shown in the City of Roseville Parks Construction Standards.
C. No material shall be placed in muddy conditions, nor shall any material be placed during or immediately after inclement weather, i.e. rain storms, etc.
3.02 Installation
A. Provide a 10’ by specified width test sample, to be approved prior to installation.
This sample shall be the basis of overall approval.
B. Thoroughly combine binder per manufacturer recommendations.
C. Spread crushed granite fine/binder material in two (2) one and one half inch (1- 1/2”) lifts (thickness after compaction).
D. Wet and roll each lift to form a uniform, smooth surface with a cross slope of 2%. Compact each lift to a 95% relative compaction density.
E. Upon completion of the final lift, fill any depressions, holes or divots and re- roll using the above process.
F. Provide a Certificate of Compliance verifying the binder/stabilizer has been mixed per manufacturer’s recommendations.
3.03 Clean Up and Protection
A. Thoroughly clean all areas where work has occurred. Remove from site excess material, debris and rubbish.
B. Take all precautions to protect completed work. Immediately repair or replace all damaged areas due to tire ruts, erosion, compaction failure, etc.
END OF SECTION
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 31 13: Chain Link Fencing
SECTION 32 31 13
CHAIN LINK FENCING
PART 1 - GENERAL
1.01 General Requirements
A. The requirements set forth in the General Conditions shall be in addition to the standards provided herein.
B. The requirements set forth in the Special Conditions shall be in addition to the standards provided herein.
1.02 Description
A. Furnish all labor, materials and equipment for the complete installation of the chain link fence system, including gates as shown on the Plans and as specified herein.
1.03 References
A. Caltrans Standard Specifications, latest edition.
PART 2 - PRODUCTS
2.01 General
A. Wire used in the fabric shall be galvanized and shall have a tensile strength of 80,000 lbs. per square inch based on cross sectional areas of the wire. One sample shall be tested without removing bends caused by weaving of the wire with the mesh. A second test shall be conducted on a wire strand carefully straightened. The tensile strength is finally determined as the average reading between the two tests. Wire to match fabric selection.
B. Fabric shall be 1-3/4” 9-gauge nominal wire mesh, hot-dipped galvanized or black vinyl coated after weaving as shown on the plans. Conform to ASTM A392, with tensile strength as described in 2.01A above. Fabric shall be knuckled top and bottom with single width to full height of fence.
C. Ties/Fasteners shall be 9-gauge aluminum or black powder coated wire.
D. Fittings, clips, bolts, bands, bars, post tops/covers and other hardware necessary for a complete fence system shall be galvanized or black powder coated.
E. Where fencing is shown on the Plans to be black vinyl or powder coated, all appurtenances, including fabric, posts, rails, clips, bands, fittings, etc., necessary for a complete fence system shall be black vinyl or powder coated.
Vinyl or powder coating shall be the industry standard for this type of finish.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 31 13: Chain Link Fencing
2.02 Posts and Rails
A. Posts and rails shall be hot-dipped galvanized per ASTM A53 or black powder coated, to match fabric and as shown on the Plans. All posts shall be installed with moisture-proofed caps on the top.
B. Size and lengths of posts shall be as shown in the City of Roseville Design and Construction Standards PK-40, latest edition.
2.03 Gates
A. Fabric and finish to match fence.
B. Hinges and latches shall be industrial strength, heavy duty and shall fit snugly around post. Latches shall be lockable.
C. Size and lengths of posts shall be as shown in the City of Roseville Parks Standard Details, latest edition.
PART 3 - EXECUTION
3.01 Post Installation
A. Posts are to be spaced evenly as shown on the City Standard and set plumb and true to lines with the top line uniform as shown in the City of Roseville Design and Construction Standards PK-40, latest edition.
B. All posts shall be set in concrete as shown in the City of Roseville Design and Construction Standards PK-40, latest edition.
C. Where nicks on vinyl or powder coated finished occurs due to installation, the Contractor shall re-finish and patch damaged areas immediately.
3.02 Fabric
A. Attach fabric using fabric bands or clips spaced approximately 14” apart.
Connections to top rails and tension wires shall utilize wire ties placed 24” on center.
B. For corner and vertical end connections, install stretcher bars banded to posts and gate frames at 24” apart (maximum).
C. All fabric to be stretched tight, free from sags and bulges.
3.03 Rails
A. For splices along the top rail, provide couplings every 20’. The coupling shall produce a continuous brace from end to end of each stretch of fence. Install a heavy spring at every fifth coupling to allow for expansion or contraction.
B. Utilize the appropriate fittings to ensure that all rails are rigidly clamped to end and corner posts.
C. Clamp mid and bottom rails at each post.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 31 13: Chain Link Fencing
3.04 Gates
A. Gates shall be installed consistent with the City Standard detail. Verify grade conditions along the fence bottom to ensure proper use of the gate(s).
B. Gate openings shall be face-to-face dimensions and shall swing according to the Plans.
3.05 Cleaning
A. Thoroughly clean all areas where work has occurred. Remove from the site excess material, debris and rubbish.
B. Take all precautions to protect completed work. Immediately repair or replace all damaged areas due to tire ruts, erosion, compaction failure, etc. Keep all erosion control measures intact.
END OF SECTION
FOR COUNCIL APPROVAL ONLY
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 32 19: Modular Concrete Retaining Walls
FOR COUNCIL APPROVAL ONLY
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 84 00: Irrigation System
SECTION 32 84 00
IRRIGATION SYSTEM
PART 1 - GENERAL
1.01 General Requirements
A. The requirements set forth in the General Conditions shall be in addition to the standards provided herein.
B. The requirements set forth in the Supplemental Conditions shall be in addition to the standards provided herein.
1.02 Description
A. Furnish all labor, materials and equipment for the complete installation of an automated irrigation system, including all necessary appurtenances for proper operation, noted or implied, as shown on the Plans and as specified herein.
B. Water usage, meter costs, connection fees, testing and other associated utility costs are considered direct costs and is the responsibility of the Contractor until the project is accepted.
C. Installation of the water meter shall be by the City.
1.03 Related Work
A. Section 32 90 00: Planting
B. Section 26 00 00: Site Electrical
1.04 Quality Assurance
A. All work shall comply with local and state laws, codes, regulations and requirements which govern any portion or all of the work contained in this Section. These include, but are not limited to, the latest editions of:
1. City of Roseville Park Construction Standards,
2. City of Roseville Design and Construction Standards,
3. City of Roseville Electric Department Standard Specifications,
4. Local, state and federal electrical codes, manuals and guidelines, and
5. Local, state and federal plumbing codes, manuals and guidelines.
1.05 Submittals
A. Submittals for specified items are not required for Parks or Streetscape projects, unless specifically listed below. However, submittals are required for any proposed substitutions or deviations from the parks Plans or Specifications. For Streetscapes, no substitutions will be accepted. The Contractor shall submit a materials summary sheet indicating which items will be installed as specified
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 84 00: Irrigation System
and which items are proposed for substitutions. The Contractor shall submit proof of order within ten (10) working days of the Notice to Proceed, indicating all specified materials have been ordered, noting “as specified” or “substitution proposed”. Submittals are required on all irrigation items.
1.06 Explanation of Drawings
A. The drawings are diagrammatic and do not reflect all offsets, fittings and other miscellaneous items required for a complete and operable irrigation system. It shall be the Contractor’s responsibility to investigate all existing site conditions, become thoroughly familiar with the site, and provide all labor, materials and equipment required for the installation of the irrigation system.
B. Avoid conflicts between other trades and the installation of the irrigation system.
Minor adjustments to avoid such conflicts shall be made in the field. Major discrepancies between actual field conditions and the Plans shall be brought to the attention of the Project Manager. The lack of notification shall indicate the Contractor assumes full responsibility for any revision deemed necessary to ensure proper installation.
1.07 Product Delivery, Handling and Storage
A. All materials shall be delivered bearing manufacturer’s label with size, type and model number (if applicable) clearly marked.
B. All pipe shall be delivered in a vehicle which allows the material to lie flat without concentrated weight or stress at any point.
C. Unload all materials with care so as to avoid damage. Store materials in a covered area and do not expose PVC pipe to extreme sun or heat. Store pipe lying flat.
D. Do not install any material that has been damaged. Replace all material found to be damaged.
1.08 Record Drawings
A. The Contractor shall keep an accurate record of the as-built conditions of the irrigation system. These records shall be updated daily and kept at the construction site. At any time, the Inspector may examine the conditions of the “as-builts” to ensure compliance of the above.
B. Dimensions shall be recorded from two (2) permanent points of reference.
C. The City may at its discretion withhold progress payments to the Contractor if the as-built records are not updated to the satisfaction of the City.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 84 00: Irrigation System
PART 2 - PRODUCTS
2.01 General
A. All materials specified shall be new, bearing the brand name, type, serial numbers and model number as shown on the Plans and as specified herein, unless otherwise accepted in writing.
2.02 Backfill Material
A. Backfill shall be clean, screened, on-site material, free from organic material, large clods of earth and/or rock larger than one (1) inch in diameter, trash, debris, rubbish, tree trunks, broken concrete or asphalt and other unacceptable material.
B. Material larger than one (1) inch shall be removed from site and legally disposed. All removal shall be the responsibility of the Contractor.
2.03 Booster Pump
A. Customflow Quality Booster Pump by V-Power Equipment, Inc. (888) 830-8025.
B. Provide technical startup support, pump certification and 30 month warranty following delivery by V-Power Equipment, Inc.
C. Variable Frequency Drive Control Panel with Fuji Eco Drive, NEMA 12 enclosure, main disconnect, DC choke, panel cooling fan, HOA switch on panel door, 110 volt transformer for controls and external fan, Terminals for wire connections, (2) Pump start relays for irrigation controller controls, ET/U.L. 508A Listed and proprietary programmed for City of Roseville standard operation by Custom Pump & Power, Inc.
D. IFM Efector PA3224 transducer is rated for 0-145PSI and adjustable through the VFD.
E. Enclosures to be sized to fit pump, VFD, valves, bypass, transducer, and pump inserted Hot Stop temperature protection to be activated at 120 degree with manual reset mounted on the VFD panel door. Flange connection for inlet and outlet outside the enclosure. Standard enclosure to be fitted for padlock and have a shock assisted opening on the front. Larger enclosures with removable doors with built in lock with the 402 key. All enclosures to be steel and powder coated dark green.
F. Installation by licensed contractor as shown on plans and connect power wires from meter pedestal and 24-volt control wire from the controller to the VFD line connectors inside the enclosure.
2.04 Pipe
A. PVC Pressurized Mainline
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 84 00: Irrigation System
1. For lines three inch (3”) or larger: polyvinyl chloride (PVC) 1120-1220, SDR 21, Class 200 rubber gasketed pipe, and NSF accepted per Standard No. 14, Type I, Grade I. Conform to:
Material ASTM
Pipe D1784, D2241
Rubber Gasket F477
2. For lines two and one half inches (2-1/2”) or smaller: Schedule 40 polyvinyl chloride (PVC) 1120-1220, and NSF accepted per Standard No. 14, Type I, Grade I. Conform to:
Material ASTM
Pipe D1784, D1785
B. PVC Non-Pressurized Lateral Lines
1. Schedule 40 polyvinyl chloride (PVC) 1120-1220, SDR 21.0, NSF accepted per Standard No. 14, Type 1, Grade II.
C. Recycled Water
1. Pipes shall meet the standards outlined in Sections 2.08, A and B above, unless otherwise noted in the City of Roseville Design and Construction Standards for recycled water, latest edition.
2. All pipes containing recycled water shall be purple, NSF accepted and conform to the City of Roseville Design and Construction Standards, latest edition.
2.05 Fittings and Nipples
A. Fittings for Mainline Pipe:
1. For all control valves on mainlines three inches (3”) and larger, use painted, ductile iron saddle taps with double stainless steel straps and nuts. Model #202 by Romac Industries, Inc. or accepted equal.
2. For all other connections on mainlines three inches (3”) and larger mainline pipe, use glued schedule 80 fittings.
3. For all control valves on mainlines two and one half inches (2-1/2”) or smaller, use glued schedule 80 fittings.
4. For all other connections on mainlines two and one half inches (2-1/2”) or smaller, use glued schedule 40 fittings.
B. Fittings for Solvent Weld Pipe- Laterals:
1. Schedule 40 polyvinyl chloride (PVC), standard weight, conforming to ASTM D2466-73.
2. Weld-on #P-70 primer and Weld-on #711 gray glue or accepted equal.
3. Teflon tape for all threaded PVC fittings.
C. Plastic Nipples shall be Schedule 80, Type 1, Grade 1, polyvinyl chloride (PVC), threaded at both ends, and conforming to ASTM D1784 -85. Nipples shall be uniformly gray.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 84 00: Irrigation System
D. Fittings for Recycled Pipe:
1. Fittings shall meet the standards outlined in Sections 2.09, A, B and C above, unless otherwise noted in the City of Roseville Design and Construction Standards for recycled water, latest edition.
2.06 Swing Joints
A. Swings joints shall be as shown in the City Parks Construction Standard detail.
Schedule 40 threaded PVC triple swing joints or an accepted equal.
2.07 Electric Remote Control Valve
A. Sizes as shown on the Plans. All valves shall be Rainbird PEB series or accepted equal and shall contain the following:
1. a globe-type electric remote control, normally closed diaphragm type with slow opening and closing action,
2. encapsulated solenoid type actuation,
3. a minimum rating of twenty-four (24) volts,
4. sixty (60) cycle,
5. two to five (2-5) watts,
6. a manual flow adjustment with shut-off provisions,
7. provisions for an external “bleed” of the diaphragm chamber for manual operation.
8. a ball valve on the inlet.
9. Schedule 80 PVC threaded fittings from main line to valve.
B. Valve boxes shall be rectangular, rigid plastic valve boxes with lockable lids and extensions by Carson Industries, LLC or accepted equal. Valve box shall be sized appropriately to house entire valve assembly with space to accommodate maintenance access. Valves for drip zones require Jumbo size boxes.
1. Boxes shall be colored green in potable applications, and purple for recycled water applications.
2. Valve boxes used on recycled water systems shall be permanently colored purple through the manufacturer. Boxes painted purple will be rejected.
3. Label lids using heat branded identification, T:Turf, S:Shrubs, B:Bubblers C. Controller station identification number shall be standard yellow tags with permanent numbers by Christy or accepted equal.
2.08 Root Watering System
A. Provide pre-manufactured root watering system.
1. Pressure compensating bubbler. See irrigation sheets for flow rates.
2. Check valve where applicable to prevent low head drainage.
3. Swing joint assembly
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 84 00: Irrigation System
4. Locking grate top on semi-rigid mesh tube. Use purple grate for Recycled water systems
5. Filter fabric sleeve
2.09 Irrigation Heads
A. All irrigation heads shall conform to type, size, precipitation rate, gallons per minute discharge, pressure and throw radius as shown on the Plans, unless otherwise accepted in writing.
B. In all available models, all irrigation heads shall have stainless steel risers, unless otherwise approved in writing.
C. For recycled water applications, irrigation heads shall be colored purple, have debris pocket, and wiper seals with 3 touch points.
D. Irrigation heads shall have built-in pressure regulation for pop up sprays and/or water-efficient heads.
E. Include built-in check valve where applicable to prevent low head drainage.
2.10 Drip Irrigation
A. Sub-surface dripline.
1. Flexible polyethylene tubing shall have factory-installed pressurecompensating, inline emitters spaced evenly per listed spacing.
2. Emitter shall incorporate elemental or ionic copper root intrusion prevention technology, and shall be warranted by the manufacturer to be free of emitter plugging due to root intrusion for a period of fifteen (15) years minimum.
3. Emitter shall have a built-in check valve that will hold back, at minimum, an
8.5' column of water.
4. Dripline for use with recycled water systems shall be properly and permanently marked for non-potable use.
5. Acceptable products include Rainbird XFS-CV Series or Netafim Techline HCVXR Series, or approved equal.
B. All fittings shall be constructed of injection molded, brown plastic having a nominal outside dimension of 17mm (0.56”). Female and male threaded ends shall be capable of mating to standard PVC pipe with tapered threads.
C. Line flushing valve
1. Valve shall be schedule 40 PVC ball valve with brass hose thread adapter.
2. Valve box shall be rigid plastic, with lockable cover by Carson Industries, LLC or accepted equal. Boxes shall be colored green in potable applications, and purple for recycled water applications.
3. Drip system operation indicator shall be Rainbird 1812 Pop-up spray body with 4-VAN nozzle set to 0-degree pattern, with Rainbird SA-125050 swing assembly and XFF-TFA barbed bt ½” FIPT fitting, or accepted equal.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 84 00: Irrigation System
D. Pressure Regulating Filters shall be Rainbird PRB Pressure Regulating Basket Filter, or approved equal, and shall include: Basket style body and jar-top cap constructed of heavy-duty glass-filled, UV-resistant polypropylene, with 150 PSI (10,3 bar) operating pressure rating. Standard 200 mesh (75 micron) filter screen constructed of stainless steel attached to propylene frame. Normallyopen in-line pressure regulating device, constructed of durable, UV resistant non-corrosive material able to accommodate an inlet pressure rating of not less than 150 PSI (10,3 bar), with preset outlet pressure of approximately 40 PSI (2,8 bar).
2.11 Thrust Blocks
A. All thrust blocks shall be concrete. The size of the blocks shall be determined by the average safe soil-bearing load of 700 lbs. per square foot.
B. Polyethylene sheeting at thrust blocks shall be 6mil.
2.12 Quick Coupler Valves
A. For potable water, quick coupling valves shall be Rainbird #44LRC or accepted equal. For recycled water, quick coupling valves shall be Rainbird #44NP lockable or accepted equal. All quick coupling valves shall be:
1. brass or bronze with one (1) IPS female pipe connection,
2. two piece body with a removable upper portion (for replacement), and
3. durable yellow covers for potable and purple for recycled.
B. Valve keys shall be brass or bronze and shall be of the same manufacturer and size as the valve.
C. Valve box shall be rigid plastic, a minimum of ten inches (10”) in diameter with lockable cover by Carson Industries, LLC or accepted equal. Boxes shall be colored green in potable applications, and purple for recycled water applications.
D. Where recycled water is used, conform to the City of Roseville Design and Construction Standards.
2.13 Manual Valves
A. For pipe four inches (4”) and larger gate valves shall be:
1. located where shown on the Plans,
2. flanged with Class 125 cast iron body,
3. bronze trimmed with a non-rising stem,
4. square operating nut,
5. able to withstand a cold water pressure of 150 pounds per square inch, and
6. sized to match the pipeline which the valves serve, unless otherwise shown on the Plans.
B. For pipe three inches (3”) or smaller
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 84 00: Irrigation System
1. located where shown on plans
2. lead free
3. Able to withstand cold water pressure of 300 pounds per square inch
4. sized to match the pipeline which the valves serve, unless otherwise shown on the Plans.
5. Nibco T-113-LF or approved equal.
C. Pipes which feed directly into a remote control valve, ball valves shall be installed and shall:
1. allow for manual operations,
2. rapid on/off , drip-tight shut-off control,
3. be constructed of bronze or brass with heavy-duty handle,
4. operate up to 22 gallons per minute,
5. operate between 15 and 150 pounds per square inch, and
6. be sized to match the pipeline which the valves serve, unless otherwise shown on the Plans.
D. Valve box shall be rigid plastic, a minimum of ten inches (10”) in diameter with extensions and lockable cover by Carson Industries, LLC, as shown on the Plans or accepted equal. Boxes shall be colored green in potable applications, and purple for recycled water applications.
2.14 Automatic Irrigation Controller
A. Automatic controllers upgrade shall be per plans or as specified herin:
1. 3-CS3-8STA-KIT CS3000 station add on card,
2. CS3-EN Ethernet communications modem.
B. Third-Party Communications hardware required:
1. Sierra Wireless AirLink RV55 LTE-A PRO Router (#1104303)
2. Router AC Adapter (#2000579)
3. AT-5 (or higher) Ethernet Cable - 1ft (#A3L781-01-BLU)
2.15 Control Wires
A. Direct burial solid copper wire AWG-U.F. 600 volt.
B. Common wire and two spare wires shall be minimum #12-gauge.
C. Pilot wires shall be red, minimum #14-gauge. Wire gauge shall be, at minimum:
Wire Gauge #14 #12 #10 #8
Max. Distance (ft.) 2,500 3,250 4,000 4,800
D. Splices:
1. Wire connections at remote control valves only shall utilize 3M direct bury splice kit model #DBY (yellow) or model #DBR (red).
2. All other splices, including line splices, connections to flow meters and other sensors shall utilize 3M Scotchcast 3570G Connector Sealing Packs, no known equal.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 84 00: Irrigation System
E. Wiring colors shall be:
USE COLOR
Flow Yellow
Master Blue
Pump Black
Valves Red
Common White
Spare Orange
Tracer Green
2.16 Sleeves
A. Schedule 40 PVC 1120-1220 and two times the diameter of the pipe to be accommodated by the sleeve, one (1) for control wires and one (1) for main line, and one (1) for lateral lines.
B. Maximum one (1) line per sleeve.
C. Add one (1) spare, same size as largest.
2.17 Tracer Wire
A. Insulated solid copper wire, minimum #12 gauge. Color shall be green.
PART 3 - EXECUTION
3.01 Site Conditions
A. Prior to start of irrigation work, review the site conditions to verify that stub- outs, points of connections, sizes of the points of connections, water pressure and other essential items necessary for irrigation work to commence are as shown on the Plans and as indicated in the Specifications.
B. Notify the Inspector immediately of any existing conditions which are unacceptable for the commencement of irrigation work.
3.02 Coordination of Work
A. Coordinate all work with other trades.
B. The irrigation plan is diagrammatic. Whenever possible, locate all pipes in planted or turf areas. Do not scale off of the Plans. Where field conditions have changed, notify the Inspector immediately.
3.03 Excavation and Trenching
A. Trenches shall be dug straight and in such a manner as to completely support the pipe continuously along the bottom of the trench. In rocky conditions, overexcavation and placement of clean bedding material may be required to ensure protruding rocks do not place undue stress on pipes. Trench layout shall follow that shown on the Plans, except where accepted by the City.
B. The following minimum cover shall be provided for pipe:
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 84 00: Irrigation System
Pipe Type Minimum Cover
Pressurized Mainlines 24”
Non- Pressurized Lateral Lines 18”
Domestic Water Lines 24”
Control wires 24”
PVC Sleeves under Paving 18”
PVC Sleeves under Auto X-ings 24”
C. Install detection wire, looped in and out of valve boxes and attached to all irrigation mainlines.
D. High voltage wires shall not be installed in the same irrigation water line trench.
3.04 Testing and Flushing
A. Pressure Testing shall occur only when the following conditions can be fulfilled:
Item Description Condition
Quick coupler valves Installed and capped
Electric remote control valves Installed
Flow valve Installed and open
Ball/Gate valves Installed and open
Lateral lines Disconnected
Welded PVC joints Cured at least 24 hours
Pipe Center loaded with backfill
Concrete Thrust Blocks Installed and cured at least 48 hours Couplings and fittings Exposed
Detection wire Installed
B. A pressure gauge shall be installed at the lowest point of the line. Continuous pressure shall be applied at a rate of 125 psi for all mainlines. The pressure shall remain stable for a minimum of two hours with no detectable leakage.
Upon completion of the test, a complete examination of the line shall be conducted by the City. Leaks resulting from the test shall be repaired and the line shall be re-tested. This process shall be repeated until the line passes the leakage test.
C. All lines and risers shall be flushed prior to final installation of irrigation heads.
All control valves shall be left open during the flushing process.
3.05 Backfilling and Compacting
A. Backfilling of trenches shall not occur until all tests and reviews have been performed. See inspection record contained in the Parks Construction Standards, latest edition. Any trench that is prematurely backfilled may be required to be re-dug for review.
B. Compaction of the trenched areas shall meet the following compaction rates of 95% in areas to receive paving and 85% in areas to be planted.
C. Do not flood trenches unless otherwise accepted by the City.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 84 00: Irrigation System
D. Sunken trenches shall be re-finished flush with the adjacent grades.
3.06 Backflow Prevention Device and Enclosure
A. Install per local codes and manufacturer’s instructions.
3.07 Flow Meter Installation
A. Install per local codes and manufacturer’s instructions.
B. All flow meters shall be installed in ground.
C. Install 3/4" conduit from irrigation controller to flow meter valve box. Install a pull box every 100’.
D. Valve box lids shall be permanently marked identifying FM for flow meter and MV for master valve and GR for grounding rod with heat branding using stencils in a uniform location on all boxes throughout.
3.08 Booster Pump Installation
A. Install per local codes and per manufacture's instruction.
B. Furnish wires and conduits to connect electrical power, and 24-volt pump start controls to the VFD panel located inside the VFD panel
C. Ductile iron plumbing from the flanges above ground to the mainline.
D. Install level concrete housekeeping pad for the pump enclosure per plans, 4" thick, 1"above ground, with 1/2" tool edges
E. Thrust blocks to be installed per pump manufacturer’s and landscape architect’s requirements.
3.09 Pipe Installation
A. Install irrigation pipe in planted areas whenever possible.
B. All pipe and fittings shall be cleaned and free from dirt, dust and moisture.
C. Pipe may be assembled along the trench at grade to avoid undue strain on the pipe or the fittings. All solvent weld connections shall be primed before applying glue. Snake the pipe within the trench to compensate for expansion and contraction.
D. All PVC pipe and metal valve connections shall be made with threaded fittings consistent with drawings PK-15 and PK-16 of the City of Roseville Parks Construction Standards.
E. All PVC-to-PVC threaded connections shall be made with Teflon tape.
F. Install concrete thrust blocks in locations where rubber gasketed irrigation mainlines change directions, e.g. ells, tees; as required on other lines and fittings; and at the termination point of the mainline. Do not conduct a pressure test within 48 hours of the thrust block pours. The size of the thrust blocks shall be per manufacturer’s instructions and shall be adequate in size to absorb thrusts up to the maximum internal water pressure. Refer to 3.18 Thrust Blocks.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 84 00: Irrigation System
G. Use glued fittings for all connections inside of a sleeve and within 20’ of a sleeve.
H. When multiple pipes are in the same trench, provide a minimum 2” horizontal separation between pipes, or equal to diameter of pipe, whichever is larger. Do not stack pipes vertically.
3.10 Electric Remote Control Valves
A. Install per local codes, manufacturer’s instructions, City of Roseville Design and Construction Standards and as shown on the Plans.
B. Install one (1) electric remote control valve per box and whenever possible, group valve boxes together. Align boxes in a straight and neat row and flush to finish grade. Provide a minimum of six (6) inches between boxes.
C. All valves shall be tagged for easy identification of valve number. Valve box lids shall be permanently marked identifying valve number and controller letter with heat branding using stencils in a uniform location on all boxes throughout.
D. Each valve shall be separately saddle tapped. Manifolded valves shall be rejected.
E. Locate valve boxes outside of turf areas, adjacent to paving, i.e. sidewalks, hardscape, etc. except where shown on the Plans.
F. Provide a minimum of eighteen (18) inches of a complete set of spare control wires, looped, within all control valve boxes.
3.11 Irrigation Heads
A. Install all heads where shown on the Plans and as specified herein.
B. Turf rotary pop-up heads shall be placed two (2) inches from any edge of adjacent walkway, concrete mow band, concrete curb, header board or other hardscape edging, or as required by current WELO regulations.
C. Rotary pop-up heads shall be installed flush with the top of finish grades of turf or planting areas.
D. Sprinkler head riser nipples sizes shall match or be the same as the riser opening of the sprinkler body.
E. Install sprinkler heads with internal check valves where heads are located in low drainage areas, i.e. bottom of berms, bottom of drainage swales, toe of slopes, etc.
F. Install all heads perpendicular to ground surface with an offset from the edge of pavement as indicated in the details.
3.12 Drip Irrigation
A. Drip irrigation is to be installed in a grid pattern layout of equal spacing between rows, unless otherwise noted on approved plans.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 84 00: Irrigation System
B. All drip irrigation shall be installed sub-surface, per manufacturer’s specifications. Staple all tubing to soil at 5 feet on-center spacing prior to backfilling.
C. Drip line shall be installed prior to plant installation, with the exception of 15- gallon and larger plant container sizes, which may be installed first at the discretion of the contractor.
D. Line Flushing Valves are to be installed below grade, as detailed, in a valve box with bolt-down lid to allow for periodic inspection and flushing.
1. Minimum of One (1) Line Flushing Valve shall be installed for every fifteen (15) GPM of zone flow, and at every termination point within a zone, and shall be installed at a point farthest away from the source (typically on an exhaust header) as possible.
E. Pop-up drip system operation indicators shall be placed within eighteen inches (18”) of each Flush Valve and shall not be placed such that it will be obstructed by vegetation. Place minimum twelve (12) inches from adjacent hardscapes.
F. If required, Air/Vacuum Relief Valves shall be installed below grade in valve boxes to allow for periodic inspection.
G. Valve box lids shall be permanently marked identifying LF for Line Flush valve and AR for Air/vacuum Relief with heat branding using stencils in a uniform location on all boxes throughout.
3.13 Quick Coupler and Gate Valves
A. Install per local codes and manufacturer’s instructions.
B. Locate valve boxes flush with finish grade, twelve (12) inches from walkways, curbs, header boards, etc., and within planted area whenever possible.
C. Install one (1) valve per box.
D. For quick coupler valves, install at 100 feet on center to the extent possible.
Provide a 24” steel support staked adjacent to the riser using two (2) stainless steel clamps.
E. For gate valves, install at locations indicated on the Plans.
F. For valve boxes installed below grade, provide 3M ball markers.
G. Valve box lids shall be permanently marked identifying GV for gate valve and QC for quick couplers, and SB for splice boxes with heat branding using stencils in a uniform location on all boxes throughout.
3.14 Automatic Controller
A. Install per local codes and manufacturer’s instructions within the specified enclosure.
B. Provide single Paige Cable P-7171D installed in conduit between all controllers.
C. Provide all necessary wiring for a complete installation between the controller and the valves.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 84 00: Irrigation System
D. Above grade wiring shall be installed in metal conduit, unless otherwise accepted. Securely mount conduit onto enclosure or wall and paint to match the adjacent surface.
E. Provide a grounding rod and bonding for each enclosure as required for lightning protection. Grounding rod shall be consistent with drawing PK-1 of the City of Roseville Parks Construction Standards. Install separate grounding rods for each enclosure where bonding is impractical.
F. Label each controller, using permanent markings, with the letter identification indicated on the Plans. Affix label on the inside of the controller cabinet door.
G. Install 110V outlet (GFIC) inside controller enclosure.
H. Provide two (2) reduced as-built irrigation diagrams, laminated and colorcoded indicating controller letter, valve/station numbers, valve size, operating pressure, gallons per minute and type of planting for each valve. See Section 01 10 00: Summary of Work 1.15B.
I. Ground test to be conducted after installation. Test results shall not exceed 25 ohms.
3.15 Control Wires
A. Wherever possible, install control wires in common trenches with mainline. The wires shall be taped in bundles at ten (10) feet on center and laid to the side of the pipe. Provide slack between ties to allow for contraction.
B. Wire valve to controller as shown on the plans.
C. Where runs are long, provide an extra three (3) feet of extra common and control wires looped at 200’ intervals. Snake wires within trenches to allow for contraction.
D. Line splices shall occur in valve boxes at grade, label and allowed only on lengths greater than 2500’. Show locations on as-built plans.
E. Do not wrap wire around pipe or allow any wiring to be placed in concrete or concrete thrust blocks.
F. Install two (2) spare wires starting from the controller, looped to each valve box to the furthest valve box, without splices.
3.16 Tracer Wire
A. Install tracer wire on top of the mainline.
B. Provide a twelve-inch (12”) loop in and out of each valve box. Solder all splices.
C. Where potable water lines are placed in a separate trench, install a tracer wire on top of the potable water line per City of Roseville Design and Construction Standards
D. Tracer wire shall be tested during review and pressure test of the mainline.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 84 00: Irrigation System
3.17 Sleeves
A. Install sleeves under all pavement and as shown on the Plans.
B. Install sleeves at the depths indicated in Section 3.03B above.
C. Extend sleeves a minimum of twelve (12) inches beyond the edge of pavement.
D. At every sleeve location installed in roadways, provide a spare PVC sleeve capped at each end and marked with a 3M ball marker.
3.18 Thrust Blocks
A. Install polyethylene sheeting between mainline and concrete.
B. Thrust blocks shall be formed against a solid trench wall. The thrust block cavity shall be in undisturbed soil or previously placed compacted backfill that yields an acceptable allowable bearing pressure.
C. Concrete thrust blocks shall not be poured on valve wires.
3.19 Cross Connection Testing for Recycled Water Systems A. The Recycled Water System shall be tested for cross connection in accordance with Uniform Plumbing Code Appendix J prior to use.
B. All testing of Recycled Water Systems must be performed utilizing a potable water source via a construction water connection per City of Roseville Construction Standards. No Recycled Water may enter a Recycled Water System until all testing is successfully completed.
C. At the time a cross connection test is to be performed, construction on both the Potable and Recycled Water Systems being tested must be complete and both systems fully operational and functioning as designed.
D. Cross connection testing shall be performed in the system by City forces with the assistance of the contractor. The test must be coordinated through the Parks Department Inspector. Allow one week’s notice to schedule the crossconnection test. Depending on complexity of the site, a preliminary field meet may be required.
3.20 Coverage Test
A. Prior to planting, the Contractor shall perform a coverage test to confirm that water coverage is complete and adequate, and produces no overspray onto hardscapes. Irrigation pressure readings at the head or emission device may also be taken as part of the coverage test to confirm adequate system hydraulics.
B. The coverage test shall be performed on the entire irrigation system and shall be performed in the presence of the Parks Inspector. The irrigation system must be connected to the City water system through the water meter.
Temporary connections are not allowed. On recycled water systems, the
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 84 00: Irrigation System
coverage test shall take place only after successful completion of the crossconnection test, with the recycled water meter in place.
C. On Park projects containing turf, a comprehensive survey of the Distribution Uniformity (Low Quarter) of each irrigation zone containing turf shall be performed by a third-party, Certified Landscape Irrigation Auditor prior to planting of turf. The irrigation system must be 100% complete, including functionality of the irrigation controller and booster pump, if present. The irrigation auditor shall prepare and submit a report listing each zone’s Distribution Uniformity, including actual mapping data of individual catch cans recorded on irrigation plan sheets, and noting any potential deficiencies in the system leading to any inadequate findings. Reported deficiencies in Distribution Uniformity will be evaluated by the Project Manager and may require corrective measures prior to approval of turf planting. Deficiencies caused by improper installation shall be corrected at no additional cost to City.
3.21 Irrigation Audit
A. A landscape irrigation audit shall be performed after all landscape and irrigation is installed. The irrigation system must be 100% complete, including functionality of the irrigation controller and booster pump, if present.
B. All landscape irrigation audits shall be conducted by a third party certified landscape irrigation auditor. Landscape audits shall not be conducted by the person who designed the landscape or installed the landscape.
C. The water audit shall conform to the specific water audit requirements of the City of Roseville Environmental Utilities Department, and any supplemental requirements from the City of Roseville Parks, Recreation & Libraries Department. The contractor shall submit a comprehensive landscape irrigation audit. This shall include, but is not limited to:
1. A completed Irrigation Audit Report-(City of Roseville provided forms only)
2. Complete system evaluation, including site conditions, system and flow data.
3. Scheduling parameters used to set the irrigation controller.
4. An Irrigation schedule for the landscape provided to the owner.
D. A minimum of 25% of all zones shall be audited. The 25% minimum shall be a representative sample of each irrigation method present (i.e. Rotors, bubblers, rotary nozzles, drip, etc.), and is in addition to any turf zones audited during the coverage test.
E. Any deficiencies noted in the audit report such as, but not limited to, run-off, overspray, obstruction of spray patterns, etc., shall be corrected and signed off as such by the original irrigation auditor prior to submission of the report. Do not submit audit reports with uncorrected deficiencies.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 84 00: Irrigation System
3.22 Clean Up
A. Each phase of work shall be immediately cleaned up. Excess equipment, material, etc., shall be legally disposed of and removed from site. All concrete, asphalt and/or decomposed granite paving shall be kept free of soil. Damage to such surfaces shall be immediately repaired to the satisfaction of the City.
PART 4 - GUARANTEE
4.01 General
A. Contractor shall provide a written guarantee covering all materials, equipment and workmanship furnished by him to be free of all defects after installation is accepted, including all defective parts that may have been found.
B. All paved areas shall be swept clean and planted areas shall be weed-free.
C. All irrigation heads shall be properly adjusted. Debris and refuse shall be removed from site prior to inspection.
4.02 Pre-Final (Punch List) Review
A. See Section 01 10 00 1.16 - Summary of Work for notification process.
4.03 Establishment
A. Full automated utilization of the irrigation system shall be included as part of the maintenance of the project. See Section 329000: Planting for additional information.
B. Program and utilize the establishment schedule as submitted with the turn-in items.
C. Contractor to run the system in “quantity” mode or “time plus flow” for a minimum of one (1) week.
D. Check the irrigation system weekly to ensure proper operations. Make all necessary adjustments, including watering schedule to ensure proper and healthy plant growth. At no time shall pools of water be present within any part of the project. Conversely, at no point shall dry or under-watered spots be visible upon inspection. Improper irrigation management resulting in flooding or dry conditions to the detriment of plant material may constitute an extension of the establishment period, at no additional cost to the City.
4.04 Final Review
A. The Contractor shall demonstrate to the City, valve by valve, the entire irrigation system to be operable. All heads shall be adjusted/flushed and all drip zones shall be flushed prior to the on-site review. Any item requiring adjustments shall be completed immediately and to the satisfaction of the City.
B. Provide necessary training to City staff in the proper operations and maintenance of the booster pump.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 84 00: Irrigation System
C. The date of final acceptance by the City Council or the recordation of the property transfer shall signify the start date of the warranty period. Final acceptance shall include the project in total and will not segregate any specific item or trade included in the construction of the project.
END OF SECTION
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 90 00: Planting
SECTION 32 90 00
PLANTING
PART 1 - GENERAL
1.01 General Requirements
A. The requirements set forth in the General Conditions shall be in addition to the standards provided herein.
B. The requirements set forth in the Supplemental Conditions shall be in addition to the standards provided herein.
1.02 Description
A. Furnish all labor, materials and equipment for the complete installation of landscape items, including all trees, shrubs, groundcovers and turf; maintenance for the establishment of new plant materials; and all necessary appurtenances for proper planting, noted or implied, as shown on the Plans and as specified herein.
1.03 Related Work
A. Section 31 20 00: Earthwork
B. Section 32 84 00: Irrigation System
1.04 Quality Assurance
A. Provide an experienced foreman who shall directly supervise the work force during all work to be performed under this contract. The foreman shall be present during the time when work is to be performed.
B. Plant material shall conform to current “American Standards for Nursery Stock” and the State of California Grading Code of Nursery Stock, No. 1 grade. Use only nursery-grown stock.
C. All plant material shall be certified free of plant diseases and insect infestations from the County Agricultural Commissioner as required by law. Each shipment of plant material shall be required to have clearance certificates.
D. Prior to planting, a soils fertility test/analysis shall be conducted by an accepted and qualified testing laboratory. Test results shall contain existing nutrient levels, soil texture, cation exchange capacity, soluble salts, pH levels, infiltration rates and recommended soil amendments/fertilizers to ensure proper growth of the specified plantings.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 90 00: Planting
1.05 Submittals
A. Submittals for specified items are not required; however, submittals are required for any proposed substitutions or deviations from the Plans or Specifications. Additionally, submittals are required for the specific items listed below. The Contractor shall submit a materials summary sheet indicating which items will be installed as specified and which items are proposed for substitutions. The Contractor shall submit proof of order within ten (10) working days of the Notice to Proceed, indicating all specified materials have been ordered, noting “as specified” or “substitution proposed”. Submittals are required on the following items:
1. Bark mulch material,
2. Certificates of compliance for turf seed mix, soil amendments, fertilizers and hydroseed mix,
3. Sod-grown turf,
4. Soils test with soil amendment recommendations.
5. Trees
a) Submit for approval, plant sources including the names of nurseries proposed as sources of acceptable trees, and a list of the trees they will provide. The plant list shall include the botanical and common name and the size at the time of selection, including basal caliper and height. b) Submit all requests for substitutions of plant species or size for approval.
Request for substitution shall be accompanied with a list of nurseries contacted in the search for the required plant and a record of other attempts to locate the required material. Requests shall also include sources of plants found that may be of a smaller or larger size, or a different shape or habit than specified, or plants of the same genus and species but different cultivar origin, or which may otherwise not meet the requirements of the specifications, but which may be available for substitution.
1.06 Soil Testing
A. Native soil and in-place topsoil shall be tested for amendment determination.
Soil Tests shall include soil texture, macro nutrients, micro nutrients, lime, base saturation, pH, sodium, boron, salinity, Cation Exchange Capacity (CEC), and Organic content.
B. Submit soils report for review and approval after completion of grading operations. Soil Testing shall be performed by an agriculture-based lab, with detailed, written recommendations for soil amendments and fertilizers specific to ornamental landscape plants and turf.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 90 00: Planting
1.07 Product Delivery, Handling and Storage
A. All materials shall be delivered bearing nursery label with botanical, common names, including cultivars.
B. Carefully handle plant material to ensure that limbs are not broken during the planting or storage of the material.
C. Store plant material in a covered area on-site, protected from inclement or hot weather on-site. Keep root balls moist by frequent watering (during hot weather) of all accepted stock until such time as planting occurs.
1.08 Inspection of Plant Material
A. Notify the Project Manager a minimum of 48 hours prior to date of delivery. All plant material is subject to inspection at the time of delivery. A sample number of plants will be inspected for the following items:
If the sample.... then the plant shall be...
is healthy, shapely and well rooted accepted.
bears a strong central leader accepted.
is wilted, wind-blown or sunburned rejected.
is root-bound, restricted or deformed rejected.
does not bear a strong central leader or
has been severely pruned back
rejected.
B. Stock to be consistent with CALFIRE Nursery/Tree Quality Cue card and Root Management Cue Card. Inspector may require contractor to remove tree or plant stock from plant containers to examine roots.
C. 15 gal tree needs to have at least 1” in basal caliper, a 24” box tree needs to have at least 2” in basal caliper, a 36” box tree needs to have at least 3” in basal caliper. Basal caliper is measured as 6” above the ground.
D. Based on the sample inspection, the Project Manager or Inspector reserves the right to reject any or all of the plant material delivered. All rejected plant material shall be immediately disposed of off-site.
1.09 Record Drawings
A. The Contractor shall keep an accurate record of the as-built conditions of the landscaping. These records shall be updated daily and kept at the construction site. At any time, the Inspector may examine the conditions of the “as-builts” to ensure compliance of the above.
PART 2 - PRODUCTS
2.01 Plants
A. The material to be planted shall conform to that indicated on the plans, unless otherwise accepted. The quantity shown on the Plans is approximate and is
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 90 00: Planting
furnished for convenience only. Verify all quantities prior to ordering plant material.
2.02 Turf
A. Turf shall be seed or sod.
B. Seed –
1. 98% pure, weed-free mixture with a minimum of 95% germination. Deliver on-site unopened and in the original containers.
2. 100% Turf Saver RTF (Rhizomatous Tall Fescue) by Barenbrug or accepted equal.
3. Turf seed mix shall be Blue tag certified.
C. Sod – Tall fescue blend with named, improved turf-type varieties only. Blend shall contain a minimum 25% Lateral Spread, Rhizomatous, or Self-Repair type tall fescue. Sod shall be non-netted, and contain no more than 10% Bluegrass.
D. Seed / Sod must be submitted and accepted by the Project Manager prior to ordering.
2.03 Soil Amendment
A. As recommended by soils test report.
2.04 Mulch
A. Regular “Walk-on” fir bark as manufactured by Redi-Gro Corporation, Sacramento, CA (916) 381-6063, Mallard Creek, Inc, Rocklin, CA (916) 645- 1681, My Bark Company, Inc., Linden, CA (209) 649-4250 or accepted equal.
B. Decorative bark, shredded lumber or saw dust, and construction debris are not permitted. The mulch must be free of needles.
2.05 Topsoil
A. Stockpiled, on-site material.
B. Imported topsoil shall be natural, friable, well-draining, free from admixture of subsoil and foreign objects larger than one inch (1”) in diameter, free from toxins or any other harmful substance which may deter healthy plant growth.
C. Perform a soils test for all imported soil. Soil test shall comply with Section 1.06.
Submit soils report for review and approval prior to import activities.
2.06 Pre- and Post- Emergent Herbicide
A. Clean, and non-staining. Consult with a pesticide specialist.
2.07 Tree Stakes and Ties
A. Trees furnished in #15 nursery containers require 2” diameter stakes. Trees less than 8' in height require an 8' stake; trees 8' or greater in height require a 10' stake. Stakes shall be pine or Douglas fir (pressure or non-pressure treated).
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 90 00: Planting
B. Trees furnished in 24” boxes or larger require 3” diameter by 10’ long stakes.
Stakes shall be, pine or Douglas fir (pressure or non-pressure treated).
C. Tree ties and Tree Guying shall be Super Tree Tie, bursting strength 300psi, tensile strength 300lbs , 1” vinyl impregnated Nylon, waterproof, Manufactured by: Arthur Enterprises. Cut to length. Color to be Green.
2.08 Native Seed
A. Where required, native seed shall be applied as follows:
1. Upland areas
Elymus glaucus (Blue Wildrye) 10.0 lbs/acre
Nassella pulchra (Purple Needlegrass) 9.0 lbs/acre
Nassella cernua (Nodding Needlegrass) 6.0 lbs/acre
Melica caljfornica (Californiameljc) 3.0 lbs/acre
Vulpia microstachys (Small Fescue) 3.0 lbs/acre
Poa secunda (Native Pine Bluegrass) 3.0 lbs/acre
Bromus carinaws (California Brome) 2.0 lbs/acre
2. Wildflowers (addition to seed mix(es) above, if specified) Clarkia amoena (Farewell to Spring) 0.5 lbs/acre
Eschscholzia caljfornica (California Poppy) 2.0 lbs/acre Lupinus nanus {Sky Lupine) 3.5 lbs/acre
Nemophila menziesii (Baby Blue Eyes) 1.5 lbs/acre
Lasthenia californica (Common Goldfields) 1.5 lbs/acre
B. Areas with sandy, dry soil shall receive: Zorro Annual Fescue 6 lbs/acre, Rose Clover 9 lbs/acre
C. A fertilizer consisting of 15-15-15 shall be applied at a rate of one half pound per 1,000 square feet. Fertilizer shall be Natural-based, slow release, and balanced in N, P, & K.
D. Seed for creek banks shall conform to the latest requirements of the California Department of Fish and Game.
PART 3 - EXECUTION
3.01 Site Preparations
A. Prior to start of landscaping work, review the site conditions to verify final grades have been established, plant/turf beds are weed free, and the irrigation system is operational as shown on the Plans and as indicated in the Specifications.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 90 00: Planting
B. For landscaping within all street right-of-ways, conduct a soils analysis test of the existing soils and remove all lime-treated soils, aggregate base or other non-organic material to a minimum depth of two feet before planting or irrigation installation. Import topsoil to bring the finish grade to specified grades. Submit the soils analysis test results of the imported material prior to import.
C. Notify the Inspector immediately of any existing conditions which are unacceptable for the commencement of landscaping work.
3.02 Coordination of Work
A. Coordinate all work with other trades.
3.03 Preparation of Planting and Turf Areas
A. Upon completion of grading and underground activity, Contractor shall obtain a soils test as outlined in 1.06.
B. Place stockpiled topsoil in all areas to receive planting or turf to a minimum depth of twelve inches (12”).
C. Rip topsoil surface in two directions to a minimum depth of twelve inches (12”).
D. Spread soil amendments at the rates indicated in the soils report.
E. Rototill amendments to recommended depths. Till amendments to a depth of 6” or as recommended by soils report.
F. Remove all rock and debris which are greater than ½ inch in areas to receive turf and one inch (1”) in areas to be planted.
G. All planted and turf areas to be smooth and uniform in grade as shown on the Plans.
H. Planting areas to be sloped to drain as shown on the Plans.
3.04 Storage of Plants and Trees
A. Protect materials from deterioration during delivery and storage. Adequately protect plants from drying out, exposure of roots to sun, wind or extremes of heat and cold temperatures. If planting is delayed more than 24 hours after delivery, set plants in a location protected from sun and wind. Provide adequate water to the root ball package during the shipping and storage period, including weekends and Holidays.
B. Soil moisture shall be maintained above wilting point and below field capacity for the root ball substrate or soil.
C. All plant materials must be available for observation prior to planting. Any plants determined to damaged or distressed due to improper watering may be rejected by inspector and shall be replaced at no cost to City.
3.05 Plant Installation
A. Tree and Shrub Planting
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 90 00: Planting
1. Remove only those plants which will be planted the same day. Place such plants in the proposed locations for review and accepted by the City prior to actual planting. Notify the Inspector a minimum of 48 hours prior to day of planting.
2. Dig planting pits as shown on the Plans and as shown in the Parks Construction Standards. Scarify the sides and bottom of pit to prevent glazing. Fill pit completely with water and allow the water to completely drain from the pit prior to actual planting.
3. Relocate any plantings taller than 6” in height that fall in front of any irrigation head in order to ensure proper coverage of the irrigation system.
4. For pits that retain water, completely penetrate the hardpan layer at the bottom of the pit and backfill with topsoil. Fill pit with water to test and ensure proper drainage.
5. Prior to tree planting a central leader needs to be established by structural pruning, as necessary. Codominant leaders need to be removed or suppressed by structural pruning. Refer to the CALFIRE "Tree Training", "Tree Planting", and "Tree Quality" cue cards and "Tree and Plant Root Management Standard and Quality Expectations" contained in Section 5 of these Standards.
6. Plants shall be removed from their containers only at the time of placement within the plant pit. Perform root pruning on all four sides of the root ball by shaving and cutting away the root ball periphery to reduce the amount of circling roots. Starting from the top and then cutting/slicing down to the bottom of the root ball. On a 15 gal container at least 1-1.5 inches of the root ball periphery needs to be removed by slicing or shaving. On a 24” and 36”box tree at least 2 inches of the root ball periphery needs to be removed by slicing or shaving. A sharp hand pruning saw needs to be used for the slicing or shaving of the root ball. Refer to the CALFIRE "Root Management" cue card contained in Section 5 of these Standards. This process will remove many girdling and circling roots deflected by the container wall and allows for root penetration within the planting basin. Spread all roots to the side to allow proper root development. Add native backfill and amendments as shown in the Parks Construction Standards and as recommended by the soils testing laboratory.
7. Plant tree at least three inches (2”) above grade on mount to prevent bowl effect. The tree’s beginning root flare must be located at top of grade with installed sod.
8. Carefully place plant into the plant pit without damaging the root ball. Water the backfill until saturated. For trees, water in by hand after planting using at least ten (10) gallons of water, minimum.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 90 00: Planting
9. Where mowing will occur, provide an eight-foot (8’) minimum horizontal clearance between trees and other site improvements, including shrubs.
10.Tree ties should be installed via a figure eight loop and each tie shall be secured with a nail on the tree stake. Install two (2) Super Tree Ties at 2/3 of tree height and two (2) Super Tree Ties at ½ of tree height.
11.Tree stakes should be inserted into the ground to a minimum depth of 18".
B. Groundcover Planting
1. Place groundcover plants in neat, straight, and parallel rows, triangularly spaced as shown on the Plans and as indicated herein.
2. Start the first row of planting at a distance equal to the on-center spacing required per plan, minimum, from the edge of the adjacent hardscape, mow band or header board.
3. Groundcover shall be installed to the outside edge of the water basins of trees or shrubs.
3.06 Seeding- Turf and Native
(Hydroseeding for turf or natural areas)
A. Lightly scarify areas to be hydroseeded.
B. Tank, hose and associated apparatus must be thoroughly clean and free of debris or other material prior to placement/spraying of seed.
C. Hydroseed turf mix shall contain the following:
Material Application Rate
Turf Seed Per Manufacturer’s Recommendations
Wood Cellulose Fiber Mulch 60 lbs. per 1,000 SF
Binder Per Manufacturer’s Recommendation
Fungicide (turf only) 1/3 lb. per 1,000 SF
Fertilizer 15-15-15 All Purpose Fertilizer. Rate per
Manufacuter’s Recommendation
Soil Conditioner Per Soil Conditioner soils lab
recommendation and as approved by
Parks, Recreation & Libraries Department
D. Blend mix in a hydraulic mixer until all material is consistently blended.
E. Apply mix at a rate of 125 pounds per 1,000 square feet unless otherwise recommended by the manufacturer.
F. Spray mixture consistently over the area to be hydroseeded. Protect adjacent areas such as paving, walls, play areas and other from overspray.
G. At the end of each day of spraying operations, clean up all areas where overspray has occurred.
H. Once seed is placed, it should not be allowed to dry out.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 90 00: Planting
3.07 Sod- Turf
A. Remove all “humps” and depressions prior to sodding.
B. Keep all sod rolls shaded and moist prior to installation.
C. Do not store sod rolls more than one (1) day. Sod shall be laid upon delivery.
D. Unroll sod one at a time for immediate installation.
E. Provide tight seam between rolls of sod (less than 1/8” gaps).
F. Stagger rows so that the ends of sod rolls are stepped.
G. For turf areas where sod is partially provided, add topsoil at all transition edges to same as finish grade.
H. Sod planted during high Summer temperatures may require fungicide application(s) as a preventative measure. A Pest Control Advisor should be consulted for recommendations. Contractor is responsible for the continued health and establishment of sod and any costs of preventative treaments.
3.08 Mulch
A. Prior to placing mulch, apply post-emergent herbicide to any weeds present, per label directions. After achieving die-off, weeds shall be mechanically cut down or hand-pulled to allow for mulch installation.
B. Prior to placing mulch, apply pre-emergent herbicide in all planting areas, per label directions.
C. Apply three inches (3”) of mulch in all landscape planter areas.
D. Keep mulch a minimum of three inches (3”) away from the trunks of all woody shrubs and four inches (6”) away from all trees. Taper mulch profile away from this point to prevent subsequent collection of mulch against trunks.
3.09 Watering
A. Upon completion of each planting or turf area, irrigate appropriately to ensure proper health and growth.
B. Continually adjust the irrigation for plant needs regardless of air temperature.
3.10 Clean-up
A. Upon completion of planting operations, collect and remove from site all empty plant containers, debris, rubbish and other trash.
B. Sweep clean and wash all hardscape areas.
C. Clean up shall occur, at minimum of once a week, at the end of the work week.
D. Maintain the entire site in a clean condition to the satisfaction of the City.
3.11 Pre-Final (Punch List) Review
A. See Section 011000 1.16 of the Summary of Work for notification process.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 32 90 00: Planting
B. The following conditions must be met in order for planting to be considered towards substantial completion, as required to enter into the establishment period described in Section 011000, 1.16:
1. For seeded turf:
a. Upon completion of the second mowing of completely germinated turf.
Second mowing is defined as full coverage of turfed area 90% weed free. b. Root depth – Turf grass roots shall be healthy, creamy-white in color and be 4” or greater in length/depth as measured from the soil surface to root tip. This shall be consistent throughout turfed area.
c. Turf shall be of uniform green color with no visible signs of stress due to soil fertility, moisture, disease or pests.
2. For sodded turf:
a. Accepted installation of the sod.
b. Turf shall be of uniform green color with no visible signs of stress due to soil fertility, moisture, disease or pests.
3. For trees and shrubs:
a. Trees and shrubs shall be properly installed, and with no visible signs of stress due to soil fertility, moisture, disease or pests.
3.12 Establishment Period
A. Active maintenance is required throughout the entire establishment period:
1. Maintain turf to a height of two and one half inches (2-1/2”) for cool season turf varieties and one and one half inches (1-1/2”) for warm season turf varieties. Maintained height shall be measured from the surface of finish grade to the top of the leaf blade throughout the establishment period, and mowed as frequently as required to maintain said height. At no time shall the leaf blade be mowed or cut more than 1/3 of the length of the blade.
Root mass/depth must remain consistent as measured at the start of establishment or greater.
2. Edge all turf areas along hardscape edges.
3. Re-seed all bare areas within the turf as soon as evident.
4. Immediately replace all dead plants.
5. As necessary, raise all trees and shrubs which have sunk within the plant pit beyond the levels indicated in the Standard details.
6. Keep all areas free of weeds, pests and disease.
7. For trees located in turf areas, maintain a circle free of turf at a distance described in the Standard details
B. Prior to the start of the final thirty (30) days of establishment:
1. All plant replacements shall be completed.
2. All plantings and turf shall be thriving and in a healthy condition.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 32 90 00: Planting
3. The lack of active maintenance prior to the final thirty (30) days may constitute a delay in the start of the final thirty (30) days of the establishment period.
3.13 Final Review
A. The Inspector shall review the site for completion of items noted, but not limited to, “B” below. All corrective action is required to enter into the final thirty (30) days of establishment.
B. The site shall be prepared for review, by ensuring that:
1. All spray heads have been properly adjusted,
2. Dead plants have been replaced,
3. Planting areas have been weeded,
4. Turf areas have full germination, are consistent in green color and are weed-free,
5. Walkways and paved areas have been swept and washed, and
6. Turf roots meet standards outlined in 3.10
C. Failure to complete any one or all of the above items may constitute nonperformance of the final review and will require re-scheduling. In this case, the cost of the extended establishment period shall be at no additional cost to the City.
PART 4 - GUARANTEE
4.01 General
A. Contractor shall provide a written guarantee covering all plant materials (trees & shrubs) furnished by them to be free of all defects or disease and that all plants are in a healthy and thriving condition at the completion of the contract.
Deciduous plant material shall be warranted beyond the time of contract completion until such time as growth becomes evident.
B. All plants, except those provided by the City, shall be warrantied for a period of one (1) year, commencing on the date of final acceptance. The warranty shall be as outlined in Section 011000: Summary of Work, paragraph 1.19. (
END OF SECTION
FOR COUNCIL APPROVAL ONLY
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 33 00 00: Utilities
SECTION 33 00 00
UTILITIES
PART 1 - GENERAL
1.01 General Requirements
A. The requirements set forth in the General Conditions shall be in addition to the standards provided herein.
B. The requirements set forth in the Supplemental Conditions shall be in addition to the standards provided herein.
C. The standards set forth in the City of Roseville Design and Construction Standards, latest edition, for storm drainage throughout the project and for sanitary sewer installations within the public rights-of-ways, easements, or as shown on the improvement plans shall be in addition to the standards provided herein.
D. The standards set forth in the latest edition of the California Building Code (CBC) for sanitary sewer installation within the project site, outside of the public right-of-way or easement shall be in addition to the standards provided herein.
1.02 Description
A. Furnish all labor, materials and equipment for the complete installation of the storm drain system, and necessary appurtenances as shown on the Plans and as specified herein.
B. Submit a materials listing for review and approval prior to commencement of specified work.
1.03 Related Work
A. Section 31 10 00: Clearing and Grubbing
B. Section 31 20 00: Earthwork
1.04 Safety Requirements
A. Furnish, install and maintain required sheeting, shoring, bracing, and other methods to ensure complete and safe work environment for all workers. Upon completion of work, remove all bracing, shoring, etc. in its entirety, unless otherwise directed by the Inspector.
B. Prior to excavation or trenching, the Contractor shall contact USA Alert (800) C. 227-2600 to locate all known utilities a minimum of 48 hours prior to start of work. During the course of construction, the Contractor shall take every precaution to maintain and protect utilities noted to remain. Said utilities shall remain operational at all times, unless otherwise noted on the plans.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 33 00 00: Utilities
D. The existing utilities are shown on the Plans based on the information available at the time of contract document development. The City shall not assume responsibility for any inaccuracies or incompleteness of the Plans based on such information. The Contractor shall immediately notify, upon damage of any pipeline or facility, the Owner and/or its agents and take every action necessary to repair or replace damaged facilities to the satisfaction of the Inspector, and at no additional cost to the City.
E. Trenches, excavations and repair of pavement shall be consistent with Section 31 20 00: Earthwork.
1.05 Coordination
A. The piping system as shown on the Plans is diagrammatic. The Contractor shall make reasonable adjustments to the layout to avoid conflicts, based on actual field conditions. Said changes shall not interfere with the design intent of the system.
1.06 Tolerance
A. The allowable tolerance for the installation of pipe is 0.05 feet within grades or spot elevations indicated on the Plans.
1.07 Product Storage
A. Take every precaution to protect the materials and pipes from damage during the delivery, storage and installation of the pipe system. Store in a cool, contained area, protected from direct sunlight and per manufacturer’s recommendations. Pipe shall be supported on firm level ground at the site.
1.08 Record Drawings
A. The Contractor shall keep an accurate record of the as-built conditions of the storm drain and sanitary sewer system. These records shall be updated daily and kept at the construction site. At any time, the Inspector may examine the conditions of the “as-builts” to ensure compliance of the above.
PART 2 - PRODUCTS
2.01 General
A. All products shall conform to City of Roseville Design and Construction Standards, latest edition, except as noted below.
2.02 Drain Pipe
A. Solid drainpipe shall be PVC SDR 35 and shall conform to ASTM D1784, or accepted equal. Gasketed connections shall conform to ASTM F477.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 33 00 00: Utilities
B. Perforated drainpipe shall be smooth walled PVC, open per Caltrans Section 68-1.02K, or accepted equal.
2.03 Drain Rock
A. Drain rock shall be Class 2 washed, ¾” diameter.
2.04 Filter Fabric
A. Filter fabric shall be Mirafi 140N, or accepted equal.
2.05 Drains
A. Drain Inlets shall be pre-cast and a minimum size of twenty-four inches (24”) square or round by Jensen Precast, or accepted equal.
1. Grate shall be heavy duty, cast iron, walk-on, and bolt down.
2. Box extensions shall be Jensen Precast, or accepted equal.
3. The base shall be six inches (6”) thick.
4. Walls shall be six inches (6”) thick.
5. A “No Dumping” Metal Storm Drain Marker shall be affixed to the concrete color of each drain inlet (See Detail DR-20)
6. Contractor may install cast-in-place drain inlets in lieu of pre-cast drain inlets.
Submit shop drawings and concrete mix design for review and approval.
B. Channel Drains for baseball/softball backstop areas shall be Polycast 600 series pre-sloped trench drains with galvanized steel slotted grates or accepted equal.
C. Sanitary sewer clean outs shall be as specified in the City of Roseville, Design and Construction Standards, latest edition.
2.06 Manholes
A. Manholes shall have tongue and groove joints, be forty-eight inches (48”) minimum in diameter, meeting ASTM C-478.
B. Covers shall be cast iron.
C. All components shall conform to the City of Roseville Design and Construction Standards, latest edition.
2.07 Tracer Wire
A. Insulated solid copper wire, minimum #12 gauge. Color per City of Roseville Design and Construction Standards.
2.08 Potable Water Warning Tape
A. On sites with both Recycled water and potable water lines. Blue plastic tape, 3 inches wide, with the words “CAUTION: POTABLE WATERLINE” imprinted in minimum 1-inch high, black letters per City of Roseville Design and Construction Standards. Imprinting shall be continuous and permanent.
FOR COUNCIL APPROVAL ONLY
Project
Date
Section 33 00 00: Utilities
PART 3 - EXECUTION
3.01 General
A. All pipes shall slope uniformly from given elevations shown on the Plans.
B. All pipes shall be accurately laid true to line and grade, utilizing accepted construction methods.
C. Damaged or cracked pipe and fittings shall not be installed and shall be removed from site.
D. Install all pipe in locations shown on the Plans, except where existing conditions necessitate minor changes.
E. All pipe and fittings shall be kept clean and closed throughout the course of construction.
F. Connections to existing sanitary sewer stubs shall be “TV-ed” and air tested prior to the start of construction per the City of Roseville Design and Construction Standards, latest edition.
3.02 Installation
A. Installation of the specified pipe lines shall conform to the City of Roseville Design and Construction Standards, latest edition.
B. Notify the Inspector a minimum of 48 hours prior to covering of work to ensure timely inspections.
C. Cutting of AC or concrete paving shall be clean, vertical and straight, using a saw, or other tool specific to this application. Replace paving to existing or better condition prior to work.
D. Trench and backfill shall be per City of Roseville Design and Construction Standards, latest edition.
E. Catch basins and drain inlets shall be installed with a concrete collar with “No Dumping” message and fish symbol depressed into the concrete or bolted in place, consistent with Drawing DR-20 the City of Roseville Design and Construction Standards, latest edition.
F. Drain inlets installed in mulched planter areas shall have a 12-inch wide collar of 2- to 6-inch river cobble placed over filter fabric.
G. Channel drains shall be set per manufacturer’s instructions. Place slotted grates along the entire length of the backstop, including wing fencing, wherever concrete is placed adjacent to the backstop system. Provide a below grade piped connection at all gate openings into the infield area. Do not install grated drain sections at these entry/exit points.
H. Manholes shall be per City of Roseville Design and Construction Standards, latest edition. Install grate flush with finish grade.
FOR COUNCIL APPROVAL ONLY
CO-61 Park
March 2026
Section 33 00 00: Utilities
I. Sanitary Sewer Clean-outs shall be installed with 3M ball markers and shall be located within planted or turf areas, whenever possible. Place clean-outs at 100’ intervals throughout the project. Clean-outs shall not be located within play areas. Install per City of Roseville Design and Construction Standards, latest edition.
J. Upon completion, thoroughly flush storm drain system in the presence of the Parks Inspector.
3.03 Tracer Wire
A. Install tracer wire on top of the potable water lines B. Tracer wire shall be continuous with no splices.
3.04 Potable Water Warning Tape
A. To be used on all potable water piping installed within the same project limits as on-site recycled water piping.
B. Install plastic warning tape in pipe backfill, six inches above pipe, for the entire length of the pipe.
3.05 Cleaning
A. Keep site clean at all times. Remove from the site all debris and rubbish and legally dispose.
END OF SECTION
FOR COUNCIL APPROVAL ONLY
DRAW
[B:\City Attorney\agreement\form agreements\Project Manuals\buildings & grounds.docx; 1/4/2024]
DRAWINGS
Project: __________________________
FOR COUNCIL APPROVAL ONLY
AB 626 - 1
[B:\City Attorney\agreement\form agreements\Project Manuals\buildings & grounds.docx; 1/4/2024] TEXT OF AB 626
Assembly Bill No. 626
CHAPTER 810
An act to add and repeal Section 9204 of the Public Contract Code, relating to public contracts.
[Approved by Governor September 29, 2016. Filed with Secretary of State September 29, 2016.]
LEGISLATIVE COUNSEL’S DIGEST
AB 626, Chiu. Public contracts: claim resolution.
Existing law prescribes various requirements regarding the formation, content, and enforcement of state and local public contracts. Existing law applicable to state public contracts generally requires that the resolution of claims related to those contracts be subject to arbitration.
Existing law applicable to local agency contracts prescribes a process for the resolution of claims related to those contracts of $375,000 or less.
This bill would establish, for contracts entered into on or after January 1, 2017, a claim resolution process applicable to any claim by a contractor in connection with a public works project. The bill would define a claim as a separate demand by the contractor for one or more of the following: a time extension for relief from damages or penalties for delay, payment of money or damages arising from work done pursuant to the contract for a public work, or payment of an amount disputed by the public entity, as specified.
This bill would require a public entity, defined to exclude certain state entities, upon receipt of a claim sent by registered or certified mail, to review it and, within 45 days, provide a written statement identifying the disputed and undisputed portions of the claim. The bill would authorize the 45-day period to be extended by mutual agreement. The bill would require any payment due on an undisputed portion of the claim to be processed within 60 days, as specified. The bill would require that the claim be deemed rejected in its entirety if the public entity fails to issue the written statement.
This bill would authorize, if the claimant disputes the public entity’s written response or if the public entity fails to respond to a claim within the time prescribed, the claimant to demand to meet and confer for settlement of the issues in dispute. The bill would require any disputed portion of the claim that remains in dispute after the meet and confer conference to be subject to nonbinding mediation, as specified. The bill would provide that unpaid claim amounts accrue interest at 7% per annum. The bill would prescribe a procedure by which a subcontractor or lower tier contractor may make a claim through the contractor.
This bill would require the text of these provisions, or a summary, to be set forth in the plans or specifications for any public work which may give rise to a claim. The bill would specify that a waiver of these rights is void and contrary to public policy, except as specified. The bill would also specify that it does not impose liability on a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
FOR COUNCIL APPROVAL ONLY
AB 626 - 2
[B:\City Attorney\agreement\form agreements\Project Manuals\buildings & grounds.docx; 1/4/2024] By increasing the duties of local agencies and officials, this bill would impose a statemandated local program.
This bill would, on January 1, 2020, repeal the provision establishing the claim resolution process.
This bill would specify that these provisions constitute a matter of statewide concern.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that, if the Commission on State Mandates determines that the bill contains costs mandated by the state, reimbursement for those costs shall be made pursuant to these statutory provisions.
The people of the State of California do enact as follows:
SECTION 1. Section 9204 is added to the Public Contract Code, to read:
9204. (a) The Legislature finds and declares that it is in the best interests of the state and its citizens to ensure that all construction business performed on a public works project in the state that is complete and not in dispute is paid in full and in a timely manner.
(b) Notwithstanding any other law, including, but not limited to, Article 7.1 (commencing with Section 10240) of Chapter 1 of Part 2, Chapter 10 (commencing with Section 19100) of Part 2, and Article 1.5 (commencing with Section 20104) of Chapter 1 of Part 3, this section shall apply to any claim by a contractor in connection with a public works project. (c) For purposes of this section:
(1) ”Claim” means a separate demand by a contractor sent by registered mail or certified mail with return receipt requested, for one or more of the following:
(A) A time extension, including, without limitation, for relief from damages or penalties for delay assessed by a public entity under a contract for a public works project. (B) Payment by the public entity of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a public works project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled. (C) Payment of an amount that is disputed by the public entity. (2) ”Contractor” means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who has entered into a direct contract with a public entity for a public works project. (3) (A) ”Public entity” means, without limitation, except as provided in subparagraph (B), a state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a charter city, county, including a charter county, city and county, including a charter city and county, district, special district, public authority, political subdivision, public corporation, or nonprofit transit corporation wholly owned by a public agency and formed to carry out the purposes of the public agency. (B) ”Public entity” shall not include the following:
(i) The Department of Water Resources as to any project under the jurisdiction of that department.
(ii) The Department of Transportation as to any project under the jurisdiction of that department.
FOR COUNCIL APPROVAL ONLY
AB 626 - 3
[B:\City Attorney\agreement\form agreements\Project Manuals\buildings & grounds.docx; 1/4/2024] (iii) The Department of Parks and Recreation as to any project under the jurisdiction of that department.
(iv) The Department of Corrections and Rehabilitation with respect to any project under its jurisdiction pursuant to Chapter 11 (commencing with Section 7000) of Title 7 of Part 3 of the Penal Code.
(v) The Military Department as to any project under the jurisdiction of that department. (vi) The Department of General Services as to all other projects. (vii) The High-Speed Rail Authority.
(4) ”Public works project” means the erection, construction, alteration, repair, or improvement of any public structure, building, road, or other public improvement of any kind. (5) ”Subcontractor” means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who either is in direct contract with a contractor or is a lower tier subcontractor. (d) (1) (A) Upon receipt of a claim pursuant to this section, the public entity to which the claim applies shall conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide the claimant a written statement identifying what portion of the claim is disputed and what portion is undisputed. Upon receipt of a claim, a public entity and a contractor may, by mutual agreement, extend the time period provided in this subdivision. (B) The claimant shall furnish reasonable documentation to support the claim. (C) If the public entity needs approval from its governing body to provide the claimant a written statement identifying the disputed portion and the undisputed portion of the claim, and the governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, the public entity shall have up to three days following the next duly publicly noticed meeting of the governing body after the 45-day period, or extension, expires to provide the claimant a written statement identifying the disputed portion and the undisputed portion. (D) Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. If the public entity fails to issue a written statement, paragraph (3) shall apply.
(2) (A) If the claimant disputes the public entity’s written response, or if the public entity fails to respond to a claim issued pursuant to this section within the time prescribed, the claimant may demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the public entity shall schedule a meet and confer conference within 30 days for settlement of the dispute.
(B) Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the public entity shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. Any disputed portion of the claim, as identified by the contractor in writing, shall be submitted to nonbinding mediation, with the public entity and the claimant sharing the associated costs equally. The public entity and claimant shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each
FOR COUNCIL APPROVAL ONLY
AB 626 - 4
[B:\City Attorney\agreement\form agreements\Project Manuals\buildings & grounds.docx; 1/4/2024] party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject to applicable procedures outside this section. (C) For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section. (D) Unless otherwise agreed to by the public entity and the contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced. (E) This section does not preclude a public entity from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program, if mediation under this section does not resolve the parties’ dispute.
(3) Failure by the public entity to respond to a claim from a contractor within the time periods described in this subdivision or to otherwise meet the time requirements of this section shall result in the claim being deemed rejected in its entirety. A claim that is denied by reason of the public entity’s failure to have responded to a claim, or its failure to otherwise meet the time requirements of this section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claimant. (4) Amounts not paid in a timely manner as required by this section shall bear interest at 7 percent per annum.
(5) If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against a public entity because privity of contract does not exist, the contractor may present to the public entity a claim on behalf of a subcontractor or lower tier subcontractor. A subcontractor may request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work which was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor. The subcontractor requesting that the claim be presented to the public entity shall furnish reasonable documentation to support the claim. Within 45 days of receipt of this written request, the contractor shall notify the subcontractor in writing as to whether the contractor presented the claim to the public entity and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not having done so.
(e) The text of this section or a summary of it shall be set forth in the plans or specifications for any public works project that may give rise to a claim under this section. (f) A waiver of the rights granted by this section is void and contrary to public policy, provided, however, that (1) upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration, as applicable; and (2) a public entity may prescribe reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section.
(g) This section applies to contracts entered into on or after January 1, 2017. (h) Nothing in this section shall impose liability upon a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
(i) This section shall remain in effect only until January 1, 2020, and as of that date is
FOR COUNCIL APPROVAL ONLY
AB 626 - 5
[B:\City Attorney\agreement\form agreements\Project Manuals\buildings & grounds.docx; 1/4/2024] repealed, unless a later enacted statute, that is enacted before January 1, 2020, deletes or extends that date.
SECTION 2.
The Legislature finds and declares that it is of statewide concern to require a charter city, charter county, or charter city and county to follow a prescribed claims resolution process to ensure there are uniform and equitable procurement practices.
SECTION 3.
If the Commission on State Mandates determines that this act contains costs mandated by the state, reimbursement to local agencies and school districts for those costs shall be made pursuant to Part 7 (commencing with Section 17500) of Division 4 of Title 2 of the Government Code.
FOR COUNCIL APPROVAL ONLY
APPENDIX A - SOIL REPORT
FOR COUNCIL APPROVAL ONLY
DECEMBER 2025
PREPARED FOR:
CALLANDER ASSOCIATES
12150 TRIBUTARY POINT DRIVE, SUITE 140
GOLD RIVER, CALIFORNIA 95670
PREPARED BY:
GEOCON CONSULTANTS, INC.
3160 GOLD VALLEY DRIVE, SUITE 800
RANCHO CORDOVA, CALIFORNIA 95742
GEOCON PROJECT NO. S3134-05-01
GEOTECHNICAL INVESTIGATION
City of Roseville CO-61 Park
5125 Ashbrook Street
Roseville, California
FOR COUNCIL APPROVAL ONLY
Project No. S3134-05-01
December 3, 2025
VIA ELECTRONIC MAIL
Amanda Miller
Callander Associates
12150 Tributary Point Drive, Suite 140
Gold River, California 95670
Subject: GEOTECHNICAL INVESTIGATION
CITY OF ROSEVILLE CO-61 PARK
6200 CAMPUS PARKWAY
ROSEVILLE, CALIFORNIA
Ms. Miller:
In accordance with your authorization of our proposal (Geocon Proposal No. SA-25-0458-P-GT, dated July 2, 2025), we performed a geotechnical investigation for the subject project located at 6200 Campus Parkway in Roseville, California.
The accompanying report presents our findings, conclusions, and recommendations for the proposed renovations at the project site. In our opinion, no adverse geotechnical conditions were encountered that would preclude the projects provided recommendations of this report are incorporated into design and construction.
Please contact us if you have any questions regarding this report or if we may be of further service.
Respectfully Submitted,
GEOCON CONSULTANTS, INC.
Brenda P. Fernandez, EIT Jeremy J. Zorne, PE, GE
Senior Staff Engineer Senior Engineer
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
TABLE OF CONTENTS
GEOTECHNICAL INVESTIGATION PAGE
1.0 PURPOSE AND SCOPE................................................................................................................... 1
2.0 SITE AND PROJECT DESCRIPTION................................................................................................. 2
3.0 SOIL AND GEOLOGIC CONDITIONS............................................................................................... 2
3.1 Fill.................................................................................................................................... 2
3.2 Alluvium (Turlock Lake Formation)................................................................................. 3
3.3 Landscape Soil Suitability................................................................................................ 3
4.0 GROUNDWATER........................................................................................................................... 3
5.0 SEISMICITY AND GEOLOGIC HAZARDS ......................................................................................... 4
5.1 Regional Active Faults..................................................................................................... 4
5.2 Historical Earthquakes and Ground Shaking................................................................... 4
5.3 Liquefaction..................................................................................................................... 4
5.4 Expansive Soil.................................................................................................................. 5
5.5 Soil Corrosion Screening ................................................................................................. 5
6.0 CONCLUSIONS AND RECOMMENDATIONS.................................................................................. 8
6.1 General............................................................................................................................ 8
6.2 Seismic Design Criteria.................................................................................................... 8
6.3 Soil and Excavation Characteristics...............................................................................10
6.4 Materials for Fill ............................................................................................................11
6.5 Grading..........................................................................................................................11
6.6 Foundations – Spread Footings / CIDH Concrete Piers.................................................13
6.7 Concrete Sidewalks and Flatwork .................................................................................14
6.8 Pavement - Hot Mix Asphalt .........................................................................................15
6.9 Pavement - Rigid Concrete............................................................................................16
6.10 Site Drainage and Moisture Protection ........................................................................17
7.0 FURTHER GEOTECHNICAL SERVICES ..........................................................................................18
7.1 Plan and Specification Review ......................................................................................18
7.2 Testing and Observation Services.................................................................................18
8.0 LIMITATIONS AND UNIFORMITY OF CONDITIONS .....................................................................19
9.0 REFERENCES ...............................................................................................................................20
FIGURES
Figure 1, Vicinity Map
Figure 2, Site Plan
Figure 3, Proposed Development Plan
APPENDIX A
FIELD EXPLORATION
Key to Logs
Logs of Test Pits (TP1 through TP4)
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
TABLE OF CONTENTS (Continued)
APPENDIX B
LABORATORY TESTING PROGRAM
Table B1, Expansion Index Test Results
Table B2, R-Value Test Results
Laboratory Results Summary
Atterberg Limits Test Results
Gradation Report
Compaction Test Report
APPENDIX C
Landscape Soil Suitability Test Results (Sunland Analytical Laboratory)
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 1 - December 3, 2025
GEOTECHNICAL INVESTIGATION
1.0 PURPOSE AND SCOPE
This report presents the results of our geotechnical investigation for the proposed CO-61 Park project located at 6200 Campus Parkway in Roseville, California. The approximate site location is depicted on the Vicinity Map, Figure 1.
The purpose of our investigation was to evaluate subsurface soil and geologic conditions at the site and provide conclusions and recommendations relative to the geotechnical aspects of designing and constructing the project as presently proposed.
To prepare this report, we performed the following scope of services:
• Performed a limited geologic literature review to aid in evaluating the geologic conditions present at the site. A list of referenced material is included in Section 9.0 of this report. • Performed a site reconnaissance to review project limits, determine exploration equipment access, and mark out exploratory excavation locations.
• Notified subscribing utility companies via Underground Service Alert (USA) a minimum of two business days (as required by law) prior to performing test pits at the site. • Excavated four (4) test pits (TP1 through TP4) at the site with a rubber-tire backhoe equipped with an 18-inch-wide bucket to depths of approximately 10½ and 11½ feet, each. • Obtained representative disturbed samples from the test pits. Additionally, we used a hand-driven core sampler with a 10-pound slide hammer to obtain relatively undisturbed soil samples from Test Pit TP4.
• Logged the test pits in accordance with the Unified Soil Classification System (USCS). • Upon completion, backfilled the test pits with the excavated soil. • Performed laboratory tests to evaluate pertinent geotechnical parameters. • Prepared this report to summarize our findings, conclusions, and recommendations with respect to design and construction of the project.
Approximate locations of the test pits are shown on the Site Plan, Figure 2 and Proposed Development Plan, Figure 3. Details of our field exploration program including exploratory logs are presented in Appendix A.
Details of our laboratory testing program and test results are summarized in Appendix B. Landscape soil suitability test results performed by Sunland Analytical Laboratory are presented in Appendix C.
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 2 - December 3, 2025
2.0 SITE AND PROJECT DESCRIPTION
The irregular-shaped site encompasses a total area of approximately 5.75 acres. The site consists of one parcel identified as Placer County Assessor Parcel Number 481-270-079-000. The site is bounded by Ashbrook Street on the north, Knightsbridge Lane on the east, and undeveloped land on the south and west. Review of historical aerial photographs indicates that the site has been undeveloped since at least 1985. In the aerial photographs, a drainage swale is visible meandering across the site to at least April of 2023. Aerial photographs suggest that the drainage swale drains from near the northeast corner of the site towards the southwest corner and into an adjacent pond. Review of an aerial photograph taken in November of 2023 indicates that the drainage swale is no longer present which may suggest that the swale was backfilled. The site configuration and approximate former drainage swale boundaries are shown on the Site Plan, Figure 2.
The project consists of constructing a new park at the site which will include a half basketball court, a picnic area with a shade structure, a play structure with a shade canopy, landscaping, turf grass areas, underground utilities, a bike trail, and flatwork throughout the park. The new play structure and shade canopy/structures will likely be supported on spread footings or cast-in-drilled-hole (CIDH) concrete piers. New pavements will likely consist of hot-mix-asphalt (HMA) and/or rigid Portland cement concrete (PCC). Based on the master grading plans (Morton & Pitalo, Inc., 2023), the site will include maximum excavations and fills on the order of one to three feet. The proposed site configuration is shown on the Proposed Development Plan, Figure 3.
3.0 SOIL AND GEOLOGIC CONDITIONS
We identified geologic and soil conditions by observing and sampling test pits and reviewing the referenced geotechnical and geologic literature (Section 9.0). Soil descriptions below include the USCS symbol where applicable. Site geology is mapped as Alluvium, Turlock Lake Formation (map symbol Qtl) based on the Preliminary Geologic Map of the Sacramento 30’x60’ Quadrangle, California, (California Geological Survey, 2011).
3.1 Fill
We encountered undocumented fill in Test Pit TP4 from the ground surface to a depth of approximately 3 feet. The fill generally consists of medium dense clayey sand (SC). Based on in-place dry density test results of representative samples of the fill, the relative compaction is greater than 90%. Therefore, over-excavation and re-compaction of the fill is not necessary. Recommendations for scarification, moisture-conditioning, and re-compaction of the top 12 inches of soil are provided in this report.
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 3 - December 3, 2025
3.2 Alluvium (Turlock Lake Formation)
Below 3 feet in Test Pit TP4 and below the ground surface in Test Pits TP1 through TP3, we encountered alluvium to the maximum explored depth of approximately 11½ feet. The alluvium generally consists of interbedded layers of very stiff to hard lean clay with sand (CL) and sandy lean clay (CL), and medium to very dense clayey sand (SC) and poorly graded sand (SP).
Soil conditions described in the previous paragraph are generalized. The boring logs included in Appendix A detail soil type, color, moisture, consistency, and USCS classification of the soils encountered at specific locations and elevations.
3.3 Landscape Soil Suitability
We submitted a near-surface bulk soil sample (TP3-Bulk) to Sunland Analytical of Rancho Cordova, California to be tested for landscape soil suitability analyses. The sample was placed in re-sealable plastic bag, labeled, and transported to Sunland Analytical Laboratory in Rancho Cordova, California.
The laboratory analytical report, prepared by Sunland Analytical, is attached as Appendix C.
4.0 GROUNDWATER
We did not encounter groundwater in our test pits excavated to depths of approximately 10½ to 11½ feet on September 9, 2025.
We reviewed available depth-to-groundwater data on the California Department of Water Resources (DWR) Sustainable Groundwater Management Act (SGMA) Data Viewer (https://sgma.water.ca.gov/webgis/?appid=SGMADataViewer#gwlevels). The SGMA Data Viewer website indicates that depth to groundwater at the site ranges from approximately 90 to 100 feet (Spring 2024).
It should be noted that fluctuations in the level of groundwater may occur due to variations in rainfall, temperature, and other factors. Depth to groundwater can also vary significantly due to localized pumping, irrigation practices, and seasonal fluctuations. Therefore, it is possible that groundwater may be higher or lower than the levels observed during our investigation.
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 4 - December 3, 2025
5.0 SEISMICITY AND GEOLOGIC HAZARDS
5.1 Regional Active Faults
The site is not located within an Alquist-Priolo Earthquake Fault Zone as established by the State Geologist around known active faults. Local field reconnaissance did not reveal overt indications of an active fault trace at the site. Review of available literature indicates there are no active fault traces within 1,000 feet of the project location. The USGS Quaternary Fault and Fold Database maps the nearest active (“Historical” and “Latest Quaternary”) fault as the Foothills Fault System located approximately 14 miles to the northeast of the project location. Therefore, we consider the potential for ground rupture due to onsite active faulting to be low.
5.2 Historical Earthquakes and Ground Shaking
We used the United States Geological Survey (USGS) Unified Hazard Tool (https://earthquake.usgs.gov/hazards/interactive/) to determine the deaggregated seismic source parameters including controlling magnitude and fault distance. The USGS estimated modal magnitude is 6.5 and the estimated Peak Ground Acceleration (PGA) for the Maximum Considered Earthquake (MCE) with a 2,475-year return period is 0.25g.
While listing PGA is useful for comparison of potential effects of fault activity in a region, other considerations are important in seismic design, including frequency and duration of motion and soil conditions underlying the site.
5.3 Liquefaction
Liquefaction is a phenomenon in which loose, saturated, cohesionless soil deposits located beneath the groundwater table lose strength when subjected to intense and prolonged ground shaking. The seismic excitation increases pore water pressure creating a buoyant effect of the loose soil. When liquefaction occurs, building foundations may sink or tilt and differential ground settlement may occur. Other effects include sand boils (ground loss) and lateral spreading if the liquefiable soil is located adjacent to a steep free face. The areas that have the greatest potential for liquefaction are those in which the water table is less than 50 feet below ground surface and the soils are predominately clean, poorly graded sand deposits of loose to medium-dense relative density.
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 5 - December 3, 2025
The site is not located in a currently established State of California Seismic Hazard Zone for liquefaction.
Based on the subsurface conditions encountered at the site, including predominantly clayey soils and lack of groundwater within the top 50 feet, liquefaction potential is expected to be low during seismic events.
Mitigation and specific design measures with respect to liquefaction is not necessary for the project.
5.4 Expansive Soil
Laboratory Plasticity Index and Expansion Index tests on selected near-surface soil samples indicate low to medium plasticity and corresponding low expansion potential. Mitigation and/or special design considerations with respect to expansive soil is not necessary for the project.
5.5 Soil Corrosion Screening
We submitted a soil sample to Sunland Analytical of Rancho Cordova, California to be tested for pH, resistivity, chloride, and sulfate to generally evaluate the corrosion potential of the soil with respect to proposed subsurface structures. These tests were performed in accordance with California Test Method (CTM) Nos. 643, 422, and 417. The results are presented in Table 5.5A and should be considered for design of underground structures.
TABLE 5.5A
SOIL CORROSION PARAMETER TEST RESULTS
(CALIFORNIA TEST METHODS 643, 417, AND 422)
Sample No. Sample
Depth (ft.) pH
Minimum
Resistivity
(Ohm-cm)
Chloride
(ppm)
Sulfate
(ppm)
TP2-Bulk 0 – 5 5.6 3,750 6.3 11.2
Notes: 1. ppm = parts per million
Soil with a low pH (higher acidity) is considered corrosive as it can react with lime in cement to leach out soluble reaction products and result in a more porous and weaker concrete. Per Caltrans Corrosion Guidelines (Caltrans, 2021), soil with a pH of 5.5 or lower may be corrosive to concrete or steel in contact with the ground.
Soil resistivity is the measure of the soil’s ability to transmit electric current. Corrosion of buried ferrous metal is proportional to the resistivity of the soil. A lower resistivity indicates a higher propensity for transmitting electric currents that can cause corrosion of buried ferrous metal items. In general, the higher the resistivity, the lower the rate for corrosion. Per Caltrans Corrosion Guidelines (Caltrans, 2021), resistivity serves as an indicator parameter for the possible presence of soluble salts and it is not
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 6 - December 3, 2025
included as a parameter to define a corrosive area for structures. A minimum resistivity value for soil less than 1,100 ohm-cm may indicate the presence of high quantities of soluble salts and a higher propensity for corrosion. Based on the laboratory minimum resistivity test results and Caltrans criteria, soil at the location tested does not have a higher propensity for corrosion.
Table 5.5B presents a summary of concrete requirements set forth by the California Building Code (CBC) Section 1904 and American Concrete Institute (ACI) 318 for possible chloride exposure. Chlorides can break down the protective oxide layer on steel surfaces resulting in corrosion. Sources of chloride include, but are not limited to, deicing chemicals, salt, brackish water, seawater, or spray from these sources.
TABLE 5.5B
REQUIREMENTS FOR CONCRETE EXPOSED TO CHLORIDE-CONTAINING SOLUTIONS (AFTER ACI 318 TABLES 19.3.1.1 and 19.3.2.1)
Chloride
Severity
Exposure
Class Condition
Maximum Water
to Cement Ratio
by Weight
Minimum
Compressive
Strength (psi)
Not
Applicable C0 Concrete dry or protected from moisture N/A 2,500 Moderate C1 Concrete exposed to moisture but not
to external sources of chlorides N/A 2,500
Severe C2 Concrete exposed to moisture and an
external source of chlorides 0.40 5,000
The appropriate Chloride Severity/Exposure Class should be determined by the project designer based on the specific conditions at the location of the proposed structure. Further guidance is provided in ACI 318. Per Caltrans Corrosion Guidelines, soil with a chloride concentration of 500 ppm or higher may be corrosive to steel structures or steel reinforcement in concrete. Based on Caltrans criteria, soil at the location tested is not corrosive with respect to chloride content.
Table 5.5C presents a summary of concrete requirements set forth by CBC Section 1904 and ACI 318 for sulfate exposure. Similar to chlorides, sulfates can break down the protective oxide layer on steel leading to corrosion. Sulfates can also react with lime in cement to soften and crack concrete.
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 7 - December 3, 2025
TABLE 5.5C
REQUIREMENTS FOR CONCRETE EXPOSED TO SULFATE-CONTAINING SOLUTIONS (AFTER ACI 318 TABLES 19.3.1.1 and 19.3.2.1)
Sulfate
Severity
Exposure
Class
Water-Soluble Sulfate
(SO4) Content Cement
Type
(ASTM
C 150)
Maximum
Water to
Cement
Ratio by
Weight1
Minimum
Compressive
Strength
(psi)
Percent By
Mass
Parts Per Million
(ppm)
Not
Applicable S0 SO4 < 0.10 SO4 < 1,000 No Type Restriction N/A 2,500 Moderate S1 0.10 < SO4 <
0.20 1,000 < SO4 < 2,000 II 0.50 4,000
Severe S2 0.20 < SO4 <
2.00 2,000 < SO4 <
20,000 V 0.45 4,500
Very
Severe S3 SO4 > 2.00 SO4 > 20,000 V+Pozzolan
or Slag 0.45 4,500
Notes: 1. Maximum water to cement ratio limits are different for lightweight concrete, see ACI 318 for details.
Based on the laboratory test results, the Sulfate Severity is classified as “Not Applicable” and the Exposure Class is S0. The concrete mix design(s) should be developed accordingly. The presence of water-soluble sulfates is not a visually discernible characteristic; therefore, other soil samples from the site could yield different concentrations. Additionally, over time landscaping activities (i.e., addition of fertilizers and other soil nutrients) may affect the concentration.
Geocon does not practice in the field of corrosion engineering and the above information is provided as screening criteria only. If corrosion sensitive improvements are planned, we recommend that further evaluations by a corrosion engineer be performed to incorporate the necessary precautions to avoid premature corrosion on buried metal pipes and metal or concrete structures in direct contact with the soils.
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 8 - December 3, 2025
6.0 CONCLUSIONS AND RECOMMENDATIONS
6.1 General
6.1.1 No soil or geologic conditions were encountered during our investigation that would preclude the proposed renovations at the sites as planned, provided the recommendations contained in this report are incorporated into the design and construction of the projects.
6.1.2 Conclusions and recommendations provided in this report are based on our review of referenced literature, analysis of data obtained from our field exploration, laboratory testing program, and our understanding of the proposed development at this time. We should review the project plans as they develop further, provide engineering consultation as needed during final design, and perform geotechnical observation and testing services during construction.
6.2 Seismic Design Criteria
6.2.1 Seismic design of structures should be performed in accordance with the provisions of the 2022 CBC which is based on the American Society of Civil Engineers (ASCE)/Structural Engineering Institute (SEI) publication: ASCE/SEI 7-16, Minimum Design Loads and Associated Criteria for Buildings and Other Structures (ASCE/SEI, 2017). We used the Structural Engineers Association of California (SEAOC) and Office of Statewide Health Planning and Development (OSHPD) web application Seismic Design Maps (https://seismicmaps.org/) to evaluate site-specific seismic design parameters in accordance with ASCE 7-16.
For seismic design purposes, sites are classified as Site Class “A” through “F” as follows:
• Site Class A – Hard Rock;
• Site Class B – Rock;
• Site Class C – Very Dense Soil and Soft Rock;
• Site Class D – Stiff Soil;
• Site Class E – Soft Clay Soil; and
• Site Class F – Soils Requiring Site Response Analysis.
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 9 - December 3, 2025
Based on the subsurface conditions at the site, the Site Classification is Site Class “D – Stiff Soil” per Table 20.3-1 of ASCE/SEI 7-16. For the purpose of evaluating code-based seismic parameters for design, we assumed a seismic Risk Category I, II, or III (per the CBC) for the project. Results are summarized in Table 6.2.1.
TABLE 6.2.1
ASCE 7-16 (CODE-BASED) SEISMIC DESIGN PARAMETERS
SITE CLASS “D” – STIFF SOIL
Parameter Value ASCE 7-16
Reference
MCER Ground Motion Spectral Response
Acceleration – Class B (short), SS
0.448g Figure 22-1
MCER Ground Motion Spectral Response
Acceleration – Class B (1 sec), S1
0.224g Figure 22-2
Site Coefficient, FA 1.441 Table 11.4-1
Site Coefficient, FV 2.152 Table 11.4-2
Site Class Modified MCER Spectral Response
Acceleration (short), SMS
0.646g Eq. 11.4-1
Site Class Modified MCER Spectral Response
Acceleration (1 sec), SM1
0.723g* Eq. 11.4-2
5% Damped Design
Spectral Response Acceleration (short), SDS
0.431g Eq. 11.4-3
5% Damped Design
Spectral Response Acceleration (1 sec), SD1
0.482g* Eq. 11.4-4
* Per Supplement 3 of ASCE 7-16 (effective November 5, 2021), a ground motion hazard analysis (GMHA) shall be performed for projects on Site Class “D” sites with 1-second spectral acceleration (S1) greater than or equal to 0.2g, which is true for this site. However, Supplement 3 of ASCE 7-16 provides an exception stating that that the GMHA may be waived provided that the parameter SM1 is increased by 50% for all applications of SM1. The values for parameters SM1 and SD1 presented above have been increased in accordance with Supplement 3 of ASCE 7-16.
6.2.2 Table 6.2.2 presents additional seismic design parameters for projects with Seismic Design Categories of D through F in accordance with ASCE 7-16 for the mapped maximum considered geometric mean (MCEG).
TABLE 6.2.2
ASCE 7-16 SITE ACCELERATION DESIGN PARAMETERS
Parameter Value ASCE 7-16 Reference
Mapped MCEG Peak Ground Acceleration, PGA 0.19g Figure 22-7 Site Coefficient, FPGA 1.419 Table 11.8-1
Site Class Modified MCEG Peak Ground
Acceleration, PGAM
0.27g Section 11.8.3 (Eq. 11.8-1)
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 10 - December 3, 2025
6.2.3 Conformance to the criteria presented in Tables 6.2.1 and 6.2.2 for seismic design does not constitute any kind of guarantee or assurance that significant structural damage or ground failure will not occur if a maximum level earthquake occurs. The primary goal of seismic design is to protect life and not to avoid structural damage, since such design may be economically prohibitive.
6.3 Soil and Excavation Characteristics
6.3.1 In our opinion, grading and excavations at the site may be accomplished with standard to moderate effort using heavy-duty grading/excavation equipment. We do not anticipate project excavations to generate oversized rock material (greater than 6 inches in dimension).
6.3.2 We anticipate that temporary excavations such as footings and utility trenches may experience sloughing/caving at variable depths. Temporary excavations must meet Cal-OSHA requirements as appropriate. Excavation sloping, benching, the use of trench shields, and the placement of trench spoils should conform to the latest applicable Cal-OSHA standards. The contractor should have a Cal-OSHA-approved “competent person” onsite during excavation to evaluate trench conditions and to make appropriate recommendations where necessary. It is the contractor’s responsibility to provide sufficient and safe excavation support as well as protecting nearby utilities, structures, and other improvements which may be damaged by earth movements.
6.3.3 The excavation support recommendations provided by Cal-OSHA are generally geared towards protecting human life and not necessarily towards preventing damage to nearby structures or surface improvements. The contractor should be responsible for using the proper active shoring systems or sloping to prevent damage to any structure or improvements near underground excavations.
6.3.4 If grading occurs during or after the wet season (typically winter and spring), or in periods of precipitation, in-place and excavated soils will likely be wet. In addition, soil below existing pavements are often wet, regardless of the time of year. Earthwork contractors should be aware of moisture sensitivity of site soils and potential compaction/workability difficulties.
6.3.5 Earthwork and pad preparation operations in these conditions will likely be difficult with low productivity. Often, a period of at least one month of warm and dry weather is necessary to allow the site to dry sufficiently so that heavy grading equipment can operate effectively.
Conversely, during dry summer and fall months, dry clay soils may require additional grading effort (discing, mixing, or other means) to attain proper moisture conditioning.
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 11 - December 3, 2025
6.3.6 Based on laboratory testing, in-situ moisture content of site soils ranges from about 8% to 15%, which on average is higher than optimum moisture content, which is approximately 10%. Due to the fine-grained nature of the soils and measured in-situ moisture contents above optimum, additional drying effort to attain moisture contents suitable for compaction should be anticipated regardless of the time of year. Mitigation alternatives may include aerating/drying the exposed soils (assuming favorable weather conditions), or chemical treatment (e.g. lime treatment). Unstable excavation bottoms may require overexcavating 12 to 18 inches and placing geotextile fabric/geogrid covered with aggregate, for stabilization. We can provide specific recommendations during construction based on conditions encountered.
6.4 Materials for Fill
6.4.1 Excavated soils generated from cut operations at the site are suitable for use as fill in structural areas provided they do not contain deleterious matter, organic material, or cementations larger than six inches in maximum dimension.
6.4.2 Import fill material should be primarily granular with a “very low” expansion potential (Expansion Index less than 20), a Liquid Limit less than 50, Plasticity Index less than 15, be free of organic material and construction debris, and not contain rock/cementations larger than six inches in greatest dimension. Import material should also contain sufficient fines to act as a binder (generally 15 percent fines or higher).
6.4.3 Environmental characteristics and corrosion potential of import soil materials should also be considered. Proposed import materials should be sampled, tested, and approved by Geocon prior to its transportation to the site.
6.5 Grading
6.5.1 All earthwork operations should be observed and all fills tested for recommended compaction and moisture content by a representative of Geocon.
6.5.2 References to relative compaction and optimum moisture content in this report are based on the latest American Society for Testing and Materials (ASTM) D1557 Test Procedure.
Structural building pad areas should extend a minimum of five feet horizontally beyond the outside dimensions of structures, including footings and overhangs carrying structural loads.
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 12 - December 3, 2025
6.5.3 Prior to commencing grading, a pre-construction conference with representatives of the client, grading contractor, and Geocon should be held at the site. Site preparation, soil handling and/or the grading plans should be discussed at the pre-construction conference.
6.5.4 Site preparation within proposed improvement areas should begin with removal of grass and organic-rich topsoil. Excavations or depressions resulting from site clearing operations, or other existing excavations or depressions, should be restored with engineered fill in accordance with the recommendations of this report.
6.5.5 Proposed improvement areas, cut bottoms, areas to receive fill, or areas left at-grade should be thoroughly scarified at least 10 to 12 inches, moisture conditioned at or near the optimum moisture content, and uniformly compacted to at least 90% relative compaction at or above optimum moisture content. Our representative should observe site clearing, scarification, watering, and re-compaction operations to evaluate performance of the subgrade under compaction equipment loading and to identify any areas that may require additional removals.
6.5.6 Engineered fill should be compacted in horizontal lifts not exceeding eight inches (loose thickness) and brought to final design elevations. Each lift should be thoroughly moisture conditioned at or near optimum moisture content and uniformly compacted to at least 90% relative compaction.
6.5.7 The upper 12 inches of soil subgrade in flatwork / hardscape areas, whether completed at-grade, by excavation, or by filling, should be uniformly moisture-conditioned at or above optimum moisture content and compacted to at least 90% relative compaction.
6.5.8 Final pavement subgrade, whether completed at-grade, by excavation, or by filling, should be uniformly moisture conditioned at or near optimum moisture content, uniformly compacted to at least 95% relative compaction, and be stable. The 95% relative compaction requirement applies to the top six inches of pavement area subgrade; however, underlying materials must be sufficiently compacted and stable. We recommend proof-rolling the subgrade with a loaded water truck (or similar equipment with high contact pressure) to verify the stability of the subgrade prior to placing aggregate base (AB). We note that deeper scarification, moisture-conditioning, and compaction efforts may be required in order to achieve overall stability and compaction.
6.5.9 Underground utility trenches within structural areas should be backfilled with properly compacted material. Pipe bedding, shading, and backfill should conform to the requirements of the appropriate utility authority. Material excavated from trenches should be adequate for
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 13 - December 3, 2025
use as general backfill above shading provided it does not contain deleterious matter, vegetation or cementations larger than six inches in maximum dimension. Trench backfill should be placed in loose lifts not exceeding eight inches. Lifts should be compacted to a minimum of 90% relative compaction at or above optimum moisture content. Compaction should be performed by mechanical means only; jetting of trench backfill is not recommended.
6.6 Foundations – Spread Footings / CIDH Concrete Piers
6.6.1 The proposed play equipment and shade structures/canopies may be supported on conventional spread footings or CIDH concrete piers. Given the variably granular (sandy) soil conditions in the top 5 feet, spread footings may be preferable since sloughing and caving may occur in CIDH pier excavations.
6.6.2 Spread footings should be at least 18 inches square and be embedded at least 18 inches below lowest adjacent pad grade. Underground utilities running parallel to footings should not be constructed in the zone of influence of footings. The zone of influence may be taken to be the area within 18 inches laterally of the footing, beneath the footings, and within a 1H:1V plane extending out and down from the bottom corner of the footing.
6.6.3 Spread footings may be designed using an allowable “net” soil bearing capacity of 2,000 pounds per square foot (psf) for combined dead plus live loads. This value may be increased by one-third to evaluate all loads, including wind or seismic forces.
6.6.4 Allowable passive pressure used to resist lateral movement of footings may be assumed to be equal to a fluid weighing 300 pounds per cubic foot (pcf). The allowable coefficient of friction to resist sliding of footings is 0.30 for concrete against soil. Combined passive resistance and friction may be utilized for footing design provided that the frictional resistance is reduced by 50%.
6.6.5 A Geocon representative should observe foundation excavations prior to placing reinforcing steel or concrete to observe that the exposed soil conditions are consistent with those anticipated. If unanticipated soil conditions are encountered, foundation modifications may be required.
6.6.6 CIDH concrete piers should have a minimum diameter of 18 inches, a minimum embedment depth of 6 feet, and be designed using an allowable unit skin friction of 400 psf to resist vertical downward loads. An allowable unit skin friction of 275 psf plus the
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 14 - December 3, 2025
weight of the pier may be used to resist uplift loads. The allowable downward capacity and allowable uplift capacity may be increased by one-third when considering transient wind or seismic loads. Piers should have a minimum center-to-center spacing of at least three pier diameters. The top 12 inches of embedment should be neglected when calculating axial compression and tension capacities.
6.6.7 Allowable passive pressure used to resist lateral movement of the piers may be assumed to be equal to a fluid weighing 300 pcf with a maximum earth pressure of 3,000 psf. The allowable passive pressure may be applied over two pier diameters for isolated piers with a minimum center-to-center spacing of at least three pier diameters. The allowable passive pressure assumes a horizontal surface extending at least 5 feet or three times the surface generating the passive pressure, whichever is greater. The upper 12 inches of embedment should not be included in the design for lateral resistance.
6.6.8 The bottom of pier excavations should be cleaned of loose cuttings prior to the placement of steel and concrete. Experience indicates that backspinning the auger does not remove loose material, and a flat cleanout plate is necessary. Concrete should be placed within the excavation as soon as possible after the auger/cleanout plate is withdrawn to reduce the potential for caving.
6.6.9 A Geocon representative should be present during pier drilling to confirm that subsurface conditions encountered are consistent with those expected. If unexpected conditions are encountered, foundation modifications may be required.
6.7 Concrete Sidewalks and Flatwork
6.7.1 Sidewalk, curb, and gutter within County right-of-way should be designed and constructed in accordance with the latest City of Roseville standards and details as applicable.
6.7.2 On-site exterior concrete flatwork will likely experience seasonal movement. Therefore, some cracking and/or vertical offset should be anticipated. We are providing the following recommendations to reduce distress to concrete flatwork. Recommendations include moisture conditioning subgrade soils and providing adequate construction and control joints.
It should be noted that even with implementation of these measures, slab movement or cracking could still occur.
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 15 - December 3, 2025
• Concrete flatwork and sidewalks should be at least six inches thick and may be placed directly on subgrade soil compacted to at least 90 percent relative compaction. If desired, a 4-inch layer of Class 2 AB compacted to 95 percent relative compaction may be placed below the concrete flatwork in order to provide a firm base. In addition, doweling could be provided at joints to reduce the potential for vertical offset. • The upper six inches of subgrade soil for exterior flatwork and sidewalks should be uniformly moisture-conditioned at or above optimum moisture content and compacted to at least 90 percent relative compaction prior to placing AB (if used). • We recommend using construction and control joints in accordance with ACI and/or PCA guidelines. Construction joints that abut building foundations should include a felt strip, or approved equivalent, that extends the full depth of the exterior slab. Exterior slabs should be structurally independent of building foundations except at doorways, where vertical movement could impact doorway operation.
6.8 Pavement - Hot Mix Asphalt
6.8.1 We performed Resistance-Value (R-Value) testing on representative bulk soil sample at the site in accordance with California Test Method (CTM) 301. Our testing resulted in an R-Value of 39. To account for subgrade soil variability resulting from site grading, we recommend using a maximum R-Value of 30 for pavement design.
6.8.2 The project civil engineer should determine the appropriate Traffic Index (TI) for pavement design. Table 6.8.2 provides alternative pavement sections based on the design methods of Caltrans’ Highway Design Manual for various TIs. We can provide additional section designs upon request.
TABLE 6.8.2
FLEXIBLE PAVEMENT SECTIONS
Traffic Index 5.0 6.0 6.5 7.0
HMA (in.) 3.0 3.5 4.5 5.5
AB (in.) 5.0 7.0 7.0 7.0
Total Section
Thickness (in.) 8.0 10.5 11.5 12.5
6.8.3 The recommended alternative pavement sections are based on the following assumptions:
1. Subgrade soil has an R-Value of at least 30.
2. Class 2 AB has a minimum R-Value of 78 and meets the requirements of Section 26 of Caltrans’ latest Standard Specifications.
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 16 - December 3, 2025
3. Class 2 AB is compacted to 95 percent or higher relative compaction at or near optimum moisture content. Prior to placing HMA, the AB should be proof rolled with a loaded water truck to verify stability.
4. Pavement subgrade should be compacted in accordance with the recommendations presented in this report.
5. HMA should conform to Section 39 of Caltrans’ latest Standard Specifications.
6. Periodic maintenance of HMA pavements is performed.
6.8.4 To reduce the potential for water from landscaped areas migrating under pavement into the AB, consideration should be given to using full-depth curbs in areas where pavement abuts irrigated landscaping. The full-depth curbs should extend at least six inches or more into the soil subgrade beneath the AB. Alternatively, modified drop-inlets that contain weepholes may be used to encourage accumulated water to drain from beneath the pavement.
6.9 Pavement - Rigid Concrete
6.9.1 If rigid Portland Concrete Cement (PCC) pavement is used in automobile and light-truck traffic areas, we recommend that the concrete be at least 6 inches thick. PCC pavement should be underlain by at least 6 inches of Class 2 AB meeting the requirements of Section 26 of Caltrans’ Standard Specifications and compacted to at least 95% relative compaction.
Subgrade soils should be prepared and compacted in accordance with the recommendations of this report.
6.9.2 Steel reinforcement, if used, should be detailed in accordance with PCA, ACI, or similar guidelines.
Alternatively, macro synthetic fibers (Euclid Chemical Tuf-Strand SF or equivalent) mixed into the concrete mix may be considered in lieu of conventional steel reinforcement provided it meets the requirements of ASTM C1116 and ASTM D7508 for Type III Synthetic Fibers.
6.9.3 Adequate dowels should also be used at joints to facilitate load transfer and reduce vertical offset. In addition, the recommendations in Section 6.10 pertaining to adequate drainage apply to concrete pavements, sidewalks, and flatwork, as well as asphalt pavements.
6.9.4 In general, we recommend that concrete pavements be detailed, designed, constructed, and maintained in accordance with industry standards such as those provided by the ACI and PCA.
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 17 - December 3, 2025
6.10 Site Drainage and Moisture Protection
6.10.1 Adequate site drainage is critical to reduce the potential for differential soil movement, soil expansion, erosion and subsurface seepage. Under no circumstances should water be allowed to pond adjacent to building foundations. The site should be graded and maintained such that surface drainage is directed away from structures in accordance with the 2022 CBC or other applicable standards. In addition, surface drainage should be directed away from the top of slopes into swales or other controlled drainage devices.
6.10.2 Underground utilities should be leak free. Utility and irrigation lines should be checked periodically for leaks, and detected leaks should be repaired promptly. Detrimental soil movement could occur if water is allowed to infiltrate the soil for prolonged periods of time.
6.10.3 We recommend use of area drains to collect excess irrigation water and transmit it to drainage structures or impervious above-grade planter boxes. In addition, where landscaping is planned adjacent to the pavement or flatwork, we recommend construction of a cutoff wall (deepened curb) along the edge of the pavement/flatwork that extends at least four inches into the soil subgrade below the bottom of the base material.
6.10.4 Experience has shown that even with these provisions, subsurface seepage may develop in areas where no such water conditions existed prior to site development. This is particularly true where a substantial increase in surface water infiltration has resulted from an increase in landscape irrigation.
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 18 - December 3, 2025
7.0 FURTHER GEOTECHNICAL SERVICES
7.1 Plan and Specification Review
7.1.1 Geocon should review the foundation and grading plans prior to final design submittal to assess whether our recommendations have been properly implemented and evaluate if additional analysis and/or recommendations are required.
7.2 Testing and Observation Services
7.2.1 The recommendations provided in this report are based on the assumption that we will continue as Geotechnical Engineer of Record (GER) throughout the construction phase and provide construction observation and testing services. Providing these services during construction are important in order to maintain continuity of geotechnical interpretation and confirm that field conditions encountered are similar to those anticipated during design. If we are not retained for these services, we cannot assume any responsibility for other’s interpretation of our recommendations or the future performance of the project.
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 19 - December 3, 2025
8.0 LIMITATIONS AND UNIFORMITY OF CONDITIONS
The recommendations of this report pertain only to the site investigated and are based upon the assumption that the soil conditions do not deviate from those disclosed in the investigation. If any variations or undesirable conditions are encountered during construction, or if the proposed construction will differ from that anticipated herein, we should be notified so that supplemental recommendations can be given. The evaluation or identification of the potential presence of hazardous materials or environmental contamination was not part of our scope of services.
This report is issued with the understanding that it is the responsibility of the owner or their representative to ensure that the information and recommendations contained herein are brought to the attention of the design team for the project and incorporated into the plans and specifications and the necessary steps are taken to see that the contractor and subcontractors carry out such recommendations in the field.
The recommendations contained in this report are preliminary until verified during construction by representatives of our firm. Changes in the conditions of a property can occur with the passage of time, whether they are due to natural processes or the works of man on this or adjacent properties.
Additionally, changes in applicable or appropriate standards may occur, whether they result from legislation or the broadening of knowledge. Accordingly, the findings of this report may be invalidated partially or wholly by changes outside our control. Therefore, this report is subject to review and should not be relied upon after a period of three years.
Our professional services were performed, our findings obtained, and our recommendations prepared in accordance with generally accepted geotechnical engineering principles and practices used in the site area at this time. No warranty is provided, express or implied.
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
Geocon Project No. S3134-05-01 - 20 - December 3, 2025
9.0 REFERENCES
1. American Concrete Institute, ACI 318-19, Building Code Requirements for Structural Concrete and Commentary, 2019.
2. American Society of Civil Engineers, ASCE 7-16 Minimum Design Loads for Buildings and Other Structures, 2017.
3. California Building Standards Commission, 2022 California Building Code, based on 2021 International Building Code, International Code Council.
4. California Department of Transportation (Caltrans), Corrosion Guidelines (Version 3.2), May 2021.
5. Caltrans, Standard Specifications, Section 26, 2024.
6. City of Roseville, CO-61 Masterplan, Drawn by: J.R.C., March 2025.
7. Gutierrez, C.I. (compilation and digital preparation), Preliminary Geologic Map of the Sacramento 30’ x 60’ Quadrangle, California, California Geological Survey, 2011.
8. Hart, Earl W., Bryant, William A. “Alquist-Priolo Earthquake Fault Zone Program.” California Division of Mines and Geology, 1999.
9. Jennings, C.W. (compiler), Fault Map of California, California Division of Mines and Geology, 1982.
10. Moron & Pitalo, Inc., Grading Only Plans for CO-61 Park Grading, HP Master Plan, Roseville, California, Sheets C-1 through C-3, March 22, 2023.
11. Portland Cement Association, Concrete Floors on Ground, 2001.
12. Structural Engineers Association of California (SEAOC) and Office of Statewide Health Planning and Development (OSHPD), Seismic Design Maps, https://seismicmaps.org/, accessed November 3, 2025.
13. United States Geological Survey, Unified Hazard Tool https://earthquake.usgs.gov/hazards/interactive/.
14. Unpublished reports, aerial photographs, and maps on file with Geocon.
FOR COUNCIL APPROVAL ONLY
ROSEVILLE
ROCKLIN
PROJECT
SITE
Diamond Oaks
Park
Mahany
Nature
Preserve
Morgan Creek
Golf Club
Sierra View
Country Club
PA RK DR
N H
AYDEN PKWY
VINEYARD RD
RANCH
VIEW DR
CREST DR
B OB D O YLE DR
COOK RIOLO RD
STANFOR D
RAN
C H
DR
SUNSET BLVD
BASELINE RD MAIN ST
ELEFA ST
H AYDE N P KWY
W
H
IT NEY
O AKS
DR
WALERGA RD
PAC I FIC
ST
R
E SERV
E
DR
T O
PAZ
AVE
S P R I NG VIEW
DR
F AIRWAY DR
MIDAS AVE
F
OOTHILLS BLVD
WASH
N
I
G
TON BLVD
COUNTRY
CLUB
D
R
WE ST OAKS B LVD
WI
LDCAT BLVD
RO SEVILL E PKWY
GALLERIA BLVD
VERNON ST
B LU E OA KS
BLVD
GIBSON
D
R
SHAST A ST
RIVERSIDE AVE
RA WHIDE
RD
PFE RD
C
DOUGLAS BLVD
HURCH S T
MARKET
S
T
ATKINSON ST
FIDDYMENT RD
ELM ST
E A STRIDGE DR
ALY
INDU
S
T
RIAL AVE
WHITNEY RANCH PKWY
ATHENS AVE
CENTRAL AVE
UN
I VE
RSIT Y
AVE
DEL W EB B
BLV
D
JUNCTION BLVD
E CATLETT RD
SUNSET BLVD W
F
OOTHI
LLS BLVD
N
CINCINNATI AVE
Dry Creek
Boardman
Canal
Curry
Creek
Pleasant
Grove Creek
Orchard Creek
Clover
ValleyCreek
A
ntelope
Creek
Cirby Creek
Miners Ravine
Secr et Ravine
Kaseberg Creek
CONSULTANTS, INC.
3 1 6 0 G O L D VA L L E Y D R - S U I T E 8 0 0 - R A N C H O C O R D O VA , C A 9 5 7 4 2 PH O N E 9 1 6 . 8 5 2 . 9 1 1 8 - FA X 9 1 6 . 8 5 2 . 9 1 3 2 S3134-05-01 December 2025 Figure 1
VICINITY MAP
5125 Ashbrook Street
Roseville, California
City of Roseville CO-61 Park
GEOCON 12/1/2025 USER Brown M PATH R:\FIGURES\GIS_Projects\S3134-05-01_City_of_Roseville_CO-61_Park\01_ReportMaps\Figure_1_Vicinity_Map.aprx 0 1
Scale in Miles
N
SAN SACRAMENTO
FRANCISCO
LOS ANGELES
SAN DIEGO
PROJECT
LOCATION
REDDING
BAKERSFIELD
FRESNO
FOR COUNCIL APPROVAL ONLY
Former Drainage Swale
é
é
é
é
é
é
é
é
TP4
TP2
TP3
TP1
ASHBROOK ST
TS DOOWARRET
NL EGDIRBSTHGINK
CAMPUS PKWY
YWKP SUPMAC
GEOCON 11/3/2025 USER Goins B PATH C:\Users\Goins B\OneDrive - Geocon, Inc\GIS\Projects\S3134-05-01_City_of_Roseville_CO-61_Park\01_ReportMaps\Figure_2_Site_Plan.aprx CONSULTANTS, INC.
3160 GOLD VALLEY DR - SUITE 800 - RANCHO CORDOVA, CA 95742 PHONE 916.852.9118 - FAX 916.852.9132
S3134-05-01 December 2025 Figure 2
SITE PLAN
5125 Ashbrook Street
Roseville, California
City of Roseville CO-61 Park
0 80
Scale in Feet
!(¹
N
Legend
éé
Approximate Test Pit Location
Approximate Site Boundary
TP4
FOR COUNCIL APPROVAL ONLY
BOUNDARY BERM
POST AND CABLE FENCE
ADDITIONAL TURF AREA
AS FUNDING ALLOWS
SHADED PICNIC AREA
SIZE AS FUNDING ALLOWS
SHADE OVER THE PLAY
STRUCTURE AS FUNDING ALLOWS
PLAY AREA
picnic
table
CONSULTANTS, INC.
3160 GOLD VALLEY DR - SUITE 800 - RANCHO CORDOVA, CA 95742 PHONE 916.852.9118 - FAX 916.852.9132
S3134-05-01 December 2025 Figure 3
PROPOSED DEVELOPMENT PLAN
5125 Ashbrook Street
Roseville, California
City of Roseville CO-61 Park 0 80
Scale in Feet
Legend
Approximate Test Pit Location
Approximate Site Boundary
TP4
GEOCON 9/24/2025 USER Goins B PATH C:\Users\Goins B\OneDrive - Geocon, Inc\GIS\Projects\S3134-05-01_City_of_Roseville_CO-61_Park\01_ReportMaps\Figure_2_Site_Plan.aprx Proposed Development Plan by J.R.C (03/2025)
TP4
TP2
TP3
TP1
Former Drainage Swale
FOR COUNCIL APPROVAL ONLY
APPENDIX A
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
APPENDIX A
FIELD EXPLORATION
We performed our geotechnical field exploration on September 9, 2025. Our field exploration program consisted of performing four test pits (TP1 through TP4) at the approximate locations depicted on the Site Plan, Figure 2 and Proposed Development Plan, Figure 3.
The test pits were excavated using a rubber-tire John Deere 310G backhoe equipped with an 18-inch-wide bucket. Upon completion, the test pits were backfilled with the excavated soil.
We visually examined, classified, and logged the subsurface conditions in the test pits in general accordance with the American Society for Testing and Materials (ASTM) Practice for Description and Identification of Soils (Visual-Manual Procedure D2488-17). This system uses the Unified Soil Classification System (USCS) for soil designations. The logs depict soil and geologic conditions encountered and depths at which we obtained samples. The logs also include our interpretation of the conditions between sampling intervals. Therefore, the logs contain both observed and interpreted data. We determined the lines designating the interface between soil materials on the logs using visual observations, drill rig penetration rates, excavation characteristics, and other factors. The transition between materials may be abrupt or gradual. Where applicable, we revised the field logs based on subsequent laboratory testing. Logs of test pits are presented herein.
FOR COUNCIL APPROVAL ONLY
INORGANIC SILTS, MICACEOUS OR
DIATOMACEOUS, FINE SANDY OR SILTY
SOILS, ELASTIC SILTS
WELL GRADED GRAVELS WITH OR WITHOUT
SAND, LITTLE OR NO FINES
TYPICAL NAMES
POORLY GRADED GRAVELS WITH OR
WITHOUT SAND, LITTLE OR NO FINES
SILTY GRAVELS, SILTY GRAVELS WITH SAND
CLAYEY GRAVELS, CLAYEY GRAVELS WITH
SAND
WELL GRADED SANDS WITH OR WITHOUT
GRAVEL, LITTLE OR NO FINES
SILTY SANDS WITH OR WITHOUT GRAVEL
CLAYEY SANDS WITH OR WITHOUT GRAVEL
INORGANIC SILTS AND VERY FINE SANDS,
ROCK FLOUR, SILTS WITH SANDS AND
GRAVELS
INORGANIC CLAYS OF LOW TO MEDIUM
PLASTICITY, CLAYS WITH SANDS AND
GRAVELS, LEAN CLAYS
ORGANIC SILTS OR CLAYS OF LOW
PLASTICITY
POORLY GRADED SANDS WITH OR
WITHOUT GRAVEL, LITTLE OR NO FINES
INORGANIC CLAYS OF HIGH PLASTICITY, FAT
CLAYS
ORGANIC CLAYS OR CLAYS OF MEDIUM TO
HIGH PLASTICITY
PEAT AND OTHER HIGHLY ORGANIC SOILS
GW
GP
GM
GC
SW
SP
SM
SC
ML
CL
OL
MH
CH
OH
PT
MAJOR DIVISIONS
CLEAN GRAVELS WITH
LITTLE OR NO FINES
GRAVELS WITH OVER
12% FINES
CLEAN SANDS WITH
LITTLE OR NO FINES
SANDS WITH OVER 12%
FINES
MORE THAN HALF
COARSE FRACTION IS
LARGER THAN NO.4
SIEVE SIZE
GRAVELS
MORE THAN HALF
COARSE FRACTION IS
SMALLER THAN NO.4
SIEVE SIZE
SANDS
LIQUID LIMIT 50% OR LESS
SILTS AND CLAYS
LIQUID LIMIT GREATER THAN 50%
SILTS AND CLAYS
HIGHLY ORGANIC SOILS
MORE THAN HALF IS COARSER THAN
NO. 200 SIEVE
COARSE-GRAINED SOILS
MORE THAN HALF IS FINER
THAN NO. 200 SIEVE
FINE-GRAINED SOILS
UNIFIED SOIL CLASSIFICATION
BORING/TRENCH LOG LEGEND
Shelby Tube Sample (ST)
Bulk Sample (B)
Standard Penetra�on
Test Sample (SPT)
Modified California
Sample (MC)
Groundwater Level
(At Time of Drilling)
Groundwater Level
(A�er Drilling)
PENETRATION RESISTANCE
SAND AND GRAVEL
RELATIVE
DENSITY
BLOWS
PER FOOT
(SPT)*
BLOWS
PER FOOT
(MOD-CAL)*
VERY LOOSE 0 - 4 0 - 6
LOOSE 5 - 10 7 - 16
MEDIUM
DENSE 11 - 30 17 - 48
DENSE 31 - 50 49 - 79
VERY DENSE OVER
50 OVER79
SILT AND CLAY
CONSISTENCY
BLOWS
PER FOOT
(SPT)*
BLOWS
PER FOOT
(MOD-CAL)* COMPRESSIVE
STRENGTH (tsf)
*NUMBER OF BLOWS OF 140 LB HAMMER FALLING 30 INCHES
TO DRIVE LAST 12 INCHES
VERY SOFT
SOFT
MEDIUM STIFF
STIFF
VERY STIFF
3 - 4
5 - 8
9 - 15
16 - 30
4 - 6
7 - 13
14 - 24
25 - 48
0.25 - 0.50
0.50 - 1.0
1.0 - 2.0
2.0 - 4.0
HARD OVER
30 OVER48 OVER4.0
0 - 2 0 - 3 0 - 0.25
MOISTURE DESCRIPTIONS
FIELD TEST APPROX. DEGREE OF
SATURATION, S (%)
NO INDICATION OF MOISTURE; DRY TO THE TOUCH S<25
25<S<50
50<S<75
75<S<100
100
DESCRIPTION
DRY
DAMP
MOIST
WET
SATURATED
SLIGHT INDICATION OF MOISTURE
INDICATION OF MOISTURE; NO VISIBLE WATER
MINOR VISIBLE FREE WATER
VISIBLE FREE WATER
QUANTITY DESCRIPTIONS
APPROX. ESTIMATED PERCENT DESCRIPTION
<5% TRACE
5 - 10% FEW
11 - 25% LITTLE
26 - 50% SOME
>50% MOSTLY
No Recovery (NOREC)
GRAVEL/COBBLE/BOULDER DESCRIPTIONS
CRITERIA DESCRIPTION
PASS THROUGH A 3-INCH SIEVE AND BE RETAINED ON A NO. 4 SIEVE (#4 TO 3") GRAVEL PASS A 12-INCH SQUARE OPENING AND BE RETAINED ON A 3-INCH SIEVE (3"-12") COBBLE WILL NOT PASS A 12-INCH SQUARE OPENING (>12") BOULDER
CEMENTATION/INDURATION DESCRIPTIONS
FIELD TEST DESCRIPTION
CRUMBLES OR BREAKS WITH HANDLING OR LITTLE FINGER PRESSURE WEAKLY CEMENTED/INDURATED
CRUMBLES OR BREAKS WITH CONSIDERABLE FINGER PRESSURE MODERATELY CEMENTED/INDURATED
WILL NOT CRUMBLE OR BREAK WITH FINGER PRESSURE STRONGLY CEMENTED/INDURATED
IGNEOUS/METAMORPHIC ROCK STRENGTH DESCRIPTIONS
FIELD TEST DESCRIPTION
MATERIAL CRUMBLES WITH BARE HAND WEAK
MATERIAL CRUMBLES UNDER BLOWS FROM GEOLOGY HAMMER MODERATELY WEAK 1 8-INCH INDENTATIONS WITH SHARP END FROM GEOLOGY HAMMER MODERATELY STRONG
HAND-HELD SPECIMEN CAN BE BROKEN WITH ONE BLOW FROM GEOLOGY
HAMMER STRONG
HAND-HELD SPECIMEN CAN BE BROKEN WITH COUPLE BLOWS FROM
GEOLOGY HAMMER VERY STRONG
HAND-HELD SPECIMEN CAN BE BROKEN WITH MANY BLOWS FROM GEOLOGY
HAMMER EXTREMELY STRONG
IGNEOUS/METAMORPHIC ROCK JOINT/FRACTURE DESCRIPTIONS
FIELD TEST DESCRIPTION
NO OBSERVED FRACTURES UNFRACTURED/UNJOINTED
MAJORITY OF JOINTS/FRACTURES SPACED AT 1 TO 3 FOOT INTERVALS SLIGHTLY FRACTURED/JOINTED MAJORITY OF JOINTS/FRACTURES SPACED AT 4-INCH TO 1 FOOT INTERVALS MODERATELY FRACTURED/JOINTED MAJORITY OF JOINTS/FRACTURES SPACED AT 1-INCH TO 4-INCH INTERVALS
WITH SCATTERED FRAGMENTED INTERVALS INTENSELY FRACTURED/JOINTED MAJORITY OF JOINTS/FRACTURES SPACED AT LESS THAN 1-INCH INTERVALS;
MOSTLY RECOVERED AS CHIPS AND FRAGMENTS
VERY INTENSELY FRACTURED/JOINTED
BEDDING SPACING DESCRIPTIONS
THICKNESS/SPACING DESCRIPTOR
GREATER THAN 10 FEET MASSIVE
3 TO 10 FEET VERY THICKLY BEDDED
1 TO 3 FEET THICKLY BEDDED
3 58-INCH TO 1 FOOT MODERATELY BEDDED
1 1 4-INCH TO 3 5
8-INCH THINLY BEDDED
3 8-INCH TO 1 1 4-INCH VERY THINLY BEDDED
LESS THAN 3
8-INCH LAMINATED
IGNEOUS/METAMORPHIC ROCK WEATHERING DESCRIPTIONS
DEGREE OF
DECOMPOSITION FIELD RECOGNITION
SOIL DISCOLORED, CHANGED TO SOIL, FABRIC DESTROYED
ENGINEERING
PROPERTIES
EASY TO DIG
EXCAVATED BY
HAND OR RIPPING
(Saprolite)
EXCAVATED BY
HAND OR RIPPING, WITH SLIGHT
DIFFICULTY
COMPLETELY WEATHERED
HIGHLY WEATHERED
MODERATELY WEATHERED
DISCOLORED, CHANGED TO SOIL, FABRIC MAINLY PRESERVED
DISCOLORED, HIGHLY FRACTURED, FABRIC ALTERED AROUND FRACTURES
EXCAVATED WITH DIFFICULTY
WITHOUT
EXPLOSIVES
DISCOLORED, FRACTURES, INTACT ROCK-NOTICEABLY WEAKER THAN FRESH ROCK
SLIGHTLY WEATHERED
REQUIRES EXPLOSIVES FOR
EXCAVATION, WITH
PERMEABLE JOINTS
AND FRACTURES
MAY BE DISCOLORED, SOME FRACTURES, INTACT
ROCK-NOT NOTICEABLY WEAKER THAN FRESH ROCK
FRESH NO DISCOLORATION, OR LOSS OF STRENGTH REQUIRES
EXPLOSIVES
STRUCTURE DESCRIPTIONS
CRITERIA
ALTERNATING LAYERS OF VARYING MATERIAL OR COLOR WITH LAYERS AT LEAST 1 4-INCH THICK
DESCRIPTION
STRATIFIED
LAMINATED ALTERNATING LAYERS OF VARYING MATERIAL OR COLOR WITH LAYERS LESS THAN 1 4-INCH THICK
BREAKS ALONG DEFINITE PLANES OF FRACTURE WITH LITTLE RESISTANCE TO FRACTURING FISSURED
FRACTURE PLANES APPEAR POLISHED OR GLOSSY, SOMETIMES STRIATED SLICKENSIDED
COHESIVE SOIL THAT CAN BE BROKEN DOWN INTO SMALLER ANGULAR LUMPS WHICH RESIST FURTHER BREAKDOWN BLOCKY
INCLUSION OF SMALL POCKETS OF DIFFERENT SOIL, SUCH AS SMALL LENSES OF SAND SCATTERED THROUGH A MASS OF CLAY LENSED
SAME COLOR AND MATERIAL THROUGHOUT HOMOGENOUS
Groundwater Level
(Seepage Encountered)
Con�nuous
Push (CP)
Chunk Sample (CHK)
KEY TO LOGS
Plotted:09/20/2024 2:38PM | By:RUBEN AGUILAR | File Location:Y:\Key to Logs-Boring and Trench Log Descriptions\KeyToLogs_GeoconLegend-Soil&RockDescriptions.dwg
FOR COUNCIL APPROVAL ONLY
!" #$$%&'()*!+,-!., /
&0112343 #5/%6#$5/%178974 3:;81;2<72 %=%3<>3<>;3;4 #%3<>3<>;3;4 %?384@ =/A#B5C3<8<@ #5D.EF**: G 5$'13HI! %5##5$A5
HJ,
,.K*L,L.:M,J ?
'
?%NJ"O &5$%5
?
P5$?
&QA5##
?%RSJEL-.F* ?
% ITLOUVW
4 3 H!TOFJX Y0
0 0
X
0 0 ZL!XE*.
[L!F*I.J!FT\, ##/B5/
[-FK]-,.:-!):*FOL^!_,:`abb=%: c,LJ!.!F,- I]TL[F.L [F.L d!).\e:]F.L:!):=afgb##':c, LJ!.!F,-:_FLOL!J!E*:c,LJ!. !F,-h!,FJ.-! M,J!.F,.,-iK,\L):L!J!L*L. I,.LE!)-,.:-]T:^!_,_FLO^*J" ]j*F,:`abb=%:c,LJ!. !F,-:_"*)J],L-hO!-T, I,.:]F.L:^!_,:kk `b$
agg=%: c,LJ!.!F,-:_FLOL!J!E*:c,L ]-FK]!F,- ZFLO(!J*,J*) (.LFL(!]F,L- 0]T*M,!]\, 0]T*H!TOFJ 0]T*()T NK*"
NK*"
NK*" 0]T*lK]^!
(NK*"
(; (2
(784 N*_
K,L.> m ,L!\,D.F.L,J U^*_.>LW
X^!L!)D.K*L. [F.LK!
,L,LUnW
48
Pa
#o` l!_L!,JK,L!-,3<>3<
l
(Rp(+RX
H
q0YN0YDqG
R
lIM(M
l00+
ZlGXMR0
lXr(
(+R0R
MqM
N
DMlH
D(DRl
+X
G(M
lG((+RIG(RMlIM
G(RIGlI[MH+(l
(DRDR0Rl(0YN0YDqG
R
lIM(M
l0G(
(+RDX
G(M
l0
D(M[R08(+R0(DG(MHDG+rDR0Rl(RIDRDR0Rl(0(+RGD sM[G(RN
YlIGDrNR(ZRRl0
MX(rR0h(+R0R(DGl0M(M
l0
YXINRt FOR COUNCIL APPROVAL ONLY
!" #$$%&'()*!+,-!., /
&0112343 #5/%6#$5/%178974219:;81;412; %<%3=>3=>;3;4 #%3=>3=>;3;4 %?384@ </A#B5C;83@ #5D.EF**: G 5$'13HI! %5##5$A5
HJ,
,.K*L,L.:M,J ?
'
?%NJ"O &5$%5
?
P5$?
&QA5##
?%RSJEL-.F* ?
% ITLOUVW
4 3 H!TOFJX Y0
0 0
X0
ZL!XE*.
[L!F*I.J!FT\, ##/B5/
[-FK]-,.:-!):*FOL^!_,:`abb<%: c,LJ!.!F,- I]T:^!_, [F.L d!).\e:]F.L:^!_,:##':_FLO.,-: c,!F,- [-FK]-,.:]F.L:*FE^!_,:`abb <%:c,LJ!.!F,- I,.LE!)-,.:_"*)L]-!L*) J],L-fO!-T,:SJEL.F,.]**JOK,". *FE^!_,_FLO!)fF,J!.F,]F.LK! J,L,L (.LFL(!]F,L- 0]T*M,!]\, 0]T*H!TOFJ 0]T*()T NK*"
NK*"
NK*" NK*" 0]T*gK]^!
(;NK*"
(;1 (;284 (;984 (;=84 N*_
K,L.> h ,L!\,D.F.L,J U^*_.>LW
X^!L!)D.K*L. [F.LK!
,L,LUiW 78 ijF,.
998= Gk!^!XF]FL.XXl29 Ml;
Pa
#m` g!_L!,JK,L!-,3=>3=
g
(Rl(+RX
H
j0YN0YDjG
R
gIM(M
g00+
ZgGXMR0
gXn(
(+R0R
MjM
N
DMgH
D(DRg
+X
G(M
gG((+RIG(RMgIM
G(RIGgI[MH+(g
(DRDR0Rg(0YN0YDjG
R
gIM(M
g0G(
(+RDX
G(M
g0
D(M[R08(+R0(DG(MHDG+nDR0Rg(RIDRDR0Rg(0(+RGD oM[G(RN
YgIGDnNR(ZRRg0
MX(nR0f(+R0R(DGg0M(M
g0
YXINRp FOR COUNCIL APPROVAL ONLY
!" #$$%&'()*!+,-!., /
&0112343 #5/%6#$5/%178974 :1;<81<4<1< %=%3:>3:><3<4 #%3:>3:><3<4 %?84@ =/A#B5C84@ #5D.EF**; G 5$'13HI! %5##5$A5
HJ,
,.K*L,L.;M,J ?
'
?%NJ"O &5$%5
?
P5$?
&QA5##
?%RSJEL-.F* ?
% ITLOUVW
4 3 H!TOFJX Y0
0 0
X ZL!XE*.
[L!F*I.J!FT\, ##/B5/
[-FK]-,.;-!);*FOL^!_,;`abb=%;c,L J!.!F,-;_FLOL!J!E*;c,!F,- [F.L;^!_, I]T;!--F.O^!_,
d!).\eLE!)O!-;]F.L;!);=afgb##';c, !F,-;_FLOL!J!E*;c,!F,- (.LFL(!]F,L- 0]T*M,!]\, 0]T*H!TOFJ 0]T*()T NK*"
NK*"
NK*" 0]T*hK]^!
(1NK*"
(11
(384 N*_
K,L.> i ,L!\,D.F.L,J U^*_.>LW
Pa
#j` h!_L!,JK,L!-,3:>3:
h
(Rk(+RX
H
l0YN0YDlG
R
hIM(M
h00+
ZhGXMR0
hXm(
(+R0R
MlM
N
DMhH
D(DRh
+X
G(M
hG((+RIG(RMhIM
G(RIGhI[MH+(h
(DRDR0Rh(0YN0YDlG
R
hIM(M
h0G(
(+RDX
G(M
h0
D(M[R08(+R0(DG(MHDG+mDR0Rh(RIDRDR0Rh(0(+RGD nM[G(RN
YhIGDmNR(ZRRh0
MX(mR0o(+R0R(DGh0M(M
h0
YXINRp FOR COUNCIL APPROVAL ONLY
!" #$$%&'()*!+,-!., /
&0112343 #5/%6#$5/%17897411:;:81:4 33 %<%3=>3=>:3:4 #%3=>3=>:3:4 %?384@ </A#B5C87@ #5D.EF**; G 5$'13HI! %5##5$A5
HJ,
,.K*L,L.;M,J ?
'
?%NJ"O &5$%5
?
P5$?
&QA5##
?%RSJEL-.F* ?
% ITLOUVW
4 3 H!TOFJX Y0
0 0
X
0 ZL!XE*.
[L!F*I.J!FT\, /%/
%A5## [-FK]-,.;-!);*FOL^!_,;`abb<% ##/B5/ c!).\d;]F.L;-!"^!_,;<aefb# #';g,!F,- +!-h+!-T, I,.;]F.L;*FE^!_,_FLO!);`abb <%;g,LJ!.!F,- (.LFL(!]F,L-
0]T*M,!]\, 0]T*H!TOFJ 0]T*()T NK*"
[-Fg-
GNK*" 0]T*iK]^!
(2NK*"
(2:;:84 (2 84 N*_
K,L.> j ,L!\,D.F.L,J U^*_.>LW
X^!L!)D.K*L. I!)I,.FL)UTJW
18 [F.LK!
,L,LUkW182
Pa
#l` i!_L!,JK,L!-,3=>3=
i
(Rm(+RX
H
n0YN0YDnG
R
iIM(M
i00+
ZiGXMR0
iXo(
(+R0R
MnM
N
DMiH
D(DRi
+X
G(M
iG((+RIG(RMiIM
G(RIGiI[MH+(i
(DRDR0Ri(0YN0YDnG
R
iIM(M
i0G(
(+RDX
G(M
i0
D(M[R08(+R0(DG(MHDG+oDR0Ri(RIDRDR0Ri(0(+RGD pM[G(RN
YiIGDoNR(ZRRi0
MX(oR0h(+R0R(DGi0M(M
i0
YXINRq FOR COUNCIL APPROVAL ONLY
APPENDIX B
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
APPENDIX B
LABORATORY TESTING PROGRAM
Laboratory tests were performed in accordance with generally accepted test methods of the American Society for Testing and Materials (ASTM) or other suggested procedures. Selected soil samples were tested for their in-place dry density and natural moisture content, plasticity index, grain size distribution, corrosion potential, expansion potential, pavement support characteristics, and moisturedensity relationship. The results of the laboratory tests are presented below and on the following pages.
TABLE B1
EXPANSION INDEX TEST RESULTS
ASTM D4829
Sample Number Depth
(feet)
Moisture Content (%) Expansion
Index Classification*
Before Test After Test
TP2-Bulk 0 – 5 8.6 15 8 Very Low
*Expansion Potential Classification per ASTM D4829.
TABLE B2
RESISTANCE VALUE TEST RESULTS
ASTM D2844
Sample Number Depth
(feet)
Average Dry
Density
(pcf)
Average Moisture
Content (%) R-Value
TP1-Bulk 0 – 5 112.5 14.4 39
FOR COUNCIL APPROVAL ONLY
Laboratory Results Summary
PROJECT CO-61 Park PROJECT NO. S3134-05-01
LOCATION Roseville, CA CLIENT Callander Associates
Boring ID
TP2
TP4
TP4
TP1
TP2
Sample ID
TP2-4.5
TP4-2.5
TP4-2
TP1-2
TP2-3
Depth (ft)
4.5 2.5
2 2
3 Moisture Content (%)
8.2 13.4
15.1 8.6
LL
47 PL
21 PI
26 % Fines
77.91 Dry Density (pcf)
113.57
Geocon Consultants | 3160 Gold Valley Drive Suite 800 | Rancho Cordova, California | 9168529118 | www.geoconinc.com
FOR COUNCIL APPROVAL ONLY
ATTERBERG LIMITS TEST RESULTS
PROJECT CO-61 Park PROJECT NO. S3134-05-01
LOCATION Roseville, CA CLIENT Callander Associates Plasticity Index, PI 0 10
20 30
40 50
60 70
A-Line
U-Line
CL-ML MH
CL
CH
ML
0 10 20 30 40 50 60 70 80 90 100 110 1
Liquid Limit, LL
ICON EXPLORATION
NUMBER
SAMPLE
NUMBER
DEPTH
(Feet)
USCS GROUP
NAME
USCS
SYMBOL
LL PL PI FINES
(%)
TP2 TP2-4.5 4.5 LEAN CLAY with Sand CL 47 21 26 77.91
Geocon Consultants | 3160 Gold Valley Drive Suite 800 | Rancho Cordova, California | 9168529118 | www.geoconinc.com
FOR COUNCIL APPROVAL ONLY
Gradation Report
CO-61 Park
Roseville, CA
SIEVE ANALYSIS HYDROMETER ANALYSIS
SIZE OF MESH OPENINGS IN INCHES NO OF MESH OPENINGS PER INCH, U.S STANDARD GRAIN SIZE IN MILLIMETERS 12" 3" 3/4" #4 #10 #40 #200 0.01 0.001
PERCENT FINER BY WEIGHT
0 10
20 30
40 50
60 70
80 90
100 0
10 20
30 40
50 60
70 80
90 100
PERCENT COARSER BY WEIGHT
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
COBBLES
GRAVEL SAND
COARSE FINE COARSE MEDIUM FINE
FINES
SILT CLAY
EXPLORATION
NUMBER
SAMPLE
NUMBER
DEPTH USCS
GROUP NAME
USCS
SYMBOL
COBBLE
(%)
GRAVEL (%) SAND
(%)
FINES
(%)
CF
(%)
NAT
WC…
LLPLI D10 D1530D50 D60758D90 D100CU CC TES
BYSTD
NOT
TP2 TP2-4.5 4.5 LEAN CLAY with Sand CL 0.00 22.09 77.91 47216 0.130.21 4.75 Bre Fern
D42
Geocon Consultants | 3160 Gold Valley Drive Suite 800 | Rancho Cordova, California | 9168529118 | www.geoconinc.com
FOR COUNCIL APPROVAL ONLY
COMPACTION TEST REPORT
Dry density, pcf
117
119
121
123
125
127
Water content, %
5 7 9 11 13 15 17
9.7%, 123.4 pcf
ZAV SpG
2.70 123456
Curve No.
TP4-Bulk
Test Specification:
TESTING DATA
TEST RESULTS Material Description
Remarks:
Project No. Client:
Project:
Sample Number: Curve 1 Checked by:
GEOCON CONSULTANTS, INC.
Title:
Figure
ASTM 1557 Method A 2024 Mold PM8
10 18
5 25
0.0332 cu. ft.
#4
2.7 LM
MR
Light Brown Lean CLAY
S3134-05-01
MR
LM
Preparation Method
Hammer Wt.
Hammer Drop
Number of Layers
Blows per Layer
Mold Size
Test Performed on Material
Passing Sieve
NM LL PI
Sp.G. (ASTM D 854)
%>#4 %<No.200
USCS AASHTO
Date Sampled
Date Tested
Tested By
WM + WS
WM
WW + T #1
WD + T #1
TARE #1
WW + T #2
WD + T #2
TARE #2
MOISTURE
DRY DENSITY
4062.0 4041.0 4050.0 3971.0
2018.0 2018.0 2018.0 2018.0
2552.0 2513.0 2543.0 2436.0
2330.5 2265.4 2366.8 2302.8
512.0 495.0 492.0 492.0
12.2 14.0 9.4 7.4
121.0 117.9 123.3 120.8
Maximum dry density = 123.4 pcf
Optimum moisture = 9.7 %
CO-61 Park
FOR COUNCIL APPROVAL ONLY
APPENDIX C
FOR COUNCIL APPROVAL ONLY
City of Roseville CO-61 Park
Geotechnical Investigation
APPENDIX C
LANDSCAPE SOIL SUITABILITY TEST RESULTS
SUNLAND ANALYTICAL LABORATORY
FOR COUNCIL APPROVAL ONLY
FOR COUNCIL APPROVAL ONLY
FOR COUNCIL APPROVAL ONLY
FOR COUNCIL APPROVAL ONLY
FOR COUNCIL APPROVAL ONLY
FOR COUNCIL APPROVAL ONLY
File Path: T:\Projects\2025\25034_CO61Park\3_ConstructionDocuments\25034_CV.dwg Plot Date: 2/9/26 Saved By: Cma Copyright © 2020 Callander Associates Landscape Architecture, Inc. www.callanderassociates.com 12150 Tributary Point Drive, Suite 140 Gold River, CA 95670 T 916.985.4366 ROSEVILLE, CA 95747 PROJECT NO: DRAWN BY: CHECKED BY: SCALE: SHEET TITLE 25034 CM/DS BW As Shown SHEETOF 28 REVISION DATE SUBMITTAL DATE 30% Submittal 09/30/25 CO-61 PARK
5125 ASHBBROOK ST, Know what'sbelow. Call before you dig.
R 99% Submittal 11/18/25 100% Submittal 02/09/26 COVER SHEET WITH CALCULATIONS 1 GENERAL NOTES 1. ALL CONSTRUCTION AND MATERIALS SHALL CONFORM TO THESE PLANS AND THE LATEST EDITION AND AMENDMENTS OF THE CITY OF ROSEVILLE DESIGN AND CONSTRUCTION STANDARDS. 2. THE CITY OF ROSEVILLE IS A MEMBER OF THE UNDERGROUND SERVICE ALERT (U.S.A.) ONE-CALL SYSTEM. THE CONTRACTORS SHALL NOTIFY THE U.S.A. CENTER 48 HOURS IN ADVANCE OF PERFORMING ANY EXCAVATION WORK BY CALLING 1-800-227-2600. 3. THE CONTRACTOR SHALL MARK IN WHITE PAINT ALL AREAS TO BE EXCAVATED PRIOR TO CONTACTING U.S.A. ANY AREAS NOT MARKED WILL NOT BE SUBJECT TO U.S.A., AND THE CONTRACTOR SHALL BE RESPONSIBLE FOR ANY DAMAGE RESULTING FROM EXCAVATION. 4. THE CONTRACTOR SHALL EXPOSE AND VERIFY LOCATIONS AND ELEVATIONS OF EXISTING UNDERGROUND UTILITIES PRIOR TO CONSTRUCTION OF THE NEW IMPROVEMENTS CONNECTING TO OR IN THE VICINITY OF THE SAME. 5. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE PROTECTION OF ALL EXISTING MONUMENTS AND OTHER SURVEY MARKERS ON THE JOB SITE. 6. THE CONTRACTOR SHALL PLACE BOXED SURVEY MONUMENTS WITH 1-1/2" BRONZE HEAD SET IN CONCRETE (STD. DWG. ST-36) AT LOCATIONS SHOWN ON THESE PLANS. 7. A.C. SURFACE SHALL BE CUT TO A NEAT, STRAIGHT LINE PARALLEL WITH THE STREET CENTERLINE AND THE EXPOSED EDGE SHALL BE TACKED WITH EMULSION PRIOR TO PAVING. THE EXPOSED BASE MATERIAL SHALL BE GRADED, RE-COMPACTED, AND RESEALED PRIOR TO PAVING. 8. ANY EXISTING CONCRETE SURFACE TO BE REMOVED SHALL BE SAW CUT TO A NEAT, STRAIGHT LINE. 9. THE CONTRACTOR SHALL SUBMIT A TRAFFIC CONTROL PLAN THAT SHALL BE ACCEPTED BY THE ENGINEERING DIVISION OF PUBLIC WORKS BEFORE START OF WORK IN RIGHT-OF-WAY AND SHALL BE IN ACCORDANCE WITH CALIFORNIA MUTCD LATEST EDITION. AT LEAST ONE LANE IN EACH DIRECTION SHALL REMAIN OPEN TO TRAFFIC UNLESS OTHERWISE SHOWN ON THE PLANS. TRAFFIC CONTROL HOURS ARE SUBJECT TO LIMITATION BY THE CITY. TRAFFIC CONTROL WITH LANE CLOSURES THAT AFFECT TRAFFIC FLOW MAY REQUIRE NIGHT WORK. IF, AS A PART OF TRAFFIC CONTROL MEASURES, A ROADWAY CLOSURE HAS BEEN APPROVED, THE CONTRACTOR SHALL NOTIFY DEVELOPMENT SERVICES CONSTRUCTION INSPECTOR 72 HOURS IN ADVANCE OF SETTING UP THIS CLOSURE. 10. CURB RAMPS CONFORMING TO ALL ADA AND TITLE 24 REQUIREMENTS SHALL BE PLACED AT ALL NEW STANDARD CURB RETURNS (STANDARD DRAWING ST-27) AND STANDARD TYPE A-7 DRIVEWAYS. WHERE EXISTING RAMPS DO NOT MEET CURRENT ADA AND TITLE 24 REQUIREMENTS, THE RAMPS SHALL BE UPGRADED IN CONFORMANCE WITH MINIMUM TITLE 24 REQUIREMENTS. WHERE EXISTING RAMPS DO NOT INCLUDE DETECTABLE WARNING PANELS (TRUNCATED DOMES), PANELS SHALL BE RETROFITTED PER THE CONSTRUCTION STANDARDS. 11. DRAIN INLETS NOT WITHIN A PAVED AREA SHALL HAVE A 12" WIDE COLLAR OF 6" THICK P.C.C. OR 2" THICK A.C. 12. PRIOR TO THE CERTIFICATE OF COMPLETION ON ALL SINGLE-FAMILY RESIDENTIAL SUBDIVISIONS, THE DEVELOPER SHALL SUBMIT A LETTER FROM THE POST OFFICE STATING THAT ITS REQUIREMENTS FOR MAILBOX CLUSTER PADS HAVE BEEN SATISFIED. 13. ALL UNDERGROUND UTILITIES WITHIN EXISTING OR PROPOSED CITY OF ROSEVILLE EASEMENTS SHALL REQUIRE A MINIMUM OF 90% COMPACTION ON THE TRENCH BACKFILL. COMPACTION OF BACKFILL BY JETTING IS NOT PERMITTED IN CITY OF ROSEVILLE RIGHT OF WAY AND EASEMENT AREAS OR WITHIN DEDICATED RECLAIMED WATER, STORM, SEWER OR WATER EASEMENTS AND MAINS. 14. THE CONTRACTOR SHALL CONDUCT A PRE-CONSTRUCTION MEETING ONE-WEEK PRIOR TO STARTING WORK. MEMBERS OF THE CITY OF ROSEVILLE DEVELOPMENT SERVICES DEPARTMENT, ENVIRONMENTAL UTILITIES DEPARTMENT AND ALL OTHER UTILITY REPRESENTATIVES SHALL BE NOTIFIED BY THE CONTRACTOR AS TO THE DATE AND LOCATION OF THE MEETING. 15. PRIOR TO EXCAVATION OF TRENCHES 5 FEET OR DEEPER, THE CONTRACTOR SHALL SUBMIT TO THE DEVELOPMENT SERVICES DEPARTMENT OR ENVIRONMENTAL UTILITIES DEPARTMENT INSPECTOR A COPY OF THE COMPANY'S ANNUAL CALOSHA TRENCHING PERMIT AND A COPY OF THE COMPANY'S LETTER INFORMING CALOSHA OF THE TIME THE TRENCHING IS COMMENCING AND THE LOCATION OF THE WORK. 16. ALL PAINTED TRAFFIC STRIPES, ARROWS, AND PAVEMENT MARKINGS SHALL BE CONSTRUCTED WITH THERMOPLASTIC MATERIAL TO THE SPECIFICATIONS SET FORTH IN CHAPTER 3 OF THE CALIFORNIA MUTCD LATEST EDITION. NON-REFLECTIVE PAVEMENT MARKERS SHALL CONSIST OF CERAMIC MARKERS ONLY CONFORMING TO CHAPTER 3 OF THE CALIFORNIA MUTCD LATEST EDITION. 17. THE CONTRACTOR SHALL TAKE EXTREME CARE TO PROTECT EXISTING SITE AND ADJACENT IMPROVEMENTS FROM DAMAGE. THE CONTRACTOR SHALL BE RESPONSIBLE TO REPAIR OR MAKE REPLACEMENT OF ALL CRACKED AND OTHERWISE PRE-EXISTING DAMAGED PUBLIC IMPROVEMENTS ALONG THE FRONTAGE OF THE PROJECT SITE AND ANY DAMAGE RESULTING FROM CONSTRUCTION TO CURRENT CITY STANDARDS AND AT THEIR OWN EXPENSE. THE EXTENT OF THE REPAIRS SHALL BE DETERMINED BY THE DEVELOPMENT SERVICES CONSTRUCTION INSPECTOR AND SHALL BE COMPLETED PRIOR TO THE CITY ACCEPTANCE OF THE IMPROVEMENTS. 18. WHERE COMBINATIONS OF SIDEWALK OR CURB AND GUTTER ARE PLACED CONTIGUOUS TO EXISTING, ALL ADJOINING EXISTING CONCRETE VERTICAL FACES SHALL BE DOWELED. ALL ABUTTING SIDEWALK ENDS SHALL BE DOWELED MID-SECTION VERTICALLY WITH TWO DOWELS FOR FOUR THROUGH SIX-FOOT WIDE SIDEWALK AND THREE DOWELS FOR WIDER SIDEWALK. ABUTTING CURB AND GUTTER ENDS SHALL BE DOWELED TWICE, 18 INCHES APART AT GUTTER PAN MID-SECTION. DOWEL CONNECTIONS OF LONGITUDINAL RUNS OF SIDEWALK TO BACK OF CURB SHALL BE THREE FEET ON CENTER. ALL DOWELS SHALL BE 16 INCHES LONG, GRADE 60; #4 REBAR PENETRATING FOUR INCHES. THE DOWEL HOLE SHALL BE 5/8-INCH DIAMETER AT A SLIGHT HORIZONTAL ANGLE FROM PERPENDICULAR. THE PENETRATING PORTION OF THE DOWEL AND THE ENTIRE (CLEANED) VERTICAL SURFACE OF THE ADJOINING, EXISTING CONCRETE SHALL BE THOROUGHLY COATED WITH STATE STANDARD TWO-PART EPOXY. 19. WHEN SAWCUTTING WITHIN THE STREET FOR TRENCHING OR OTHER PURPOSES, CONTRACTOR SHALL GRIND 1½” OF PAVEMENT BETWEEN THE LANE LINES (FROM LANE STRIPE TO LANE STRIPE) UPON COMPLETION OF THE SAWCUTTING AND OR TRENCHING WORK. WHERE THE SAWCUTTING OCCURS BETWEEN THE CURB AND GUTTER AND NEAREST LANE STRIPE (INCLUDING BIKE LANES), THE SAME 1 ½” GRIND SHALL BE REQUIRED. CONTRACTOR TO PLACE A PETROMAT FABRIC OR APPROVED EQUAL BY THE CITY OF ROSEVILLE AND OVERLAY FROM LANE STRIPE TO LANE STRIPE, OR CURB TO LANE STRIPE AND RESTRIPE OR REPLACE ANY DELINEATORS REMOVED DURING THE GRIND. 20. ALL PUBLICLY MAINTAINED STORM DRAIN ON PRIVATE PROPERTY SHALL BE A MINIMUM OF 12 INCHES IN DIAMETER AND SHALL BE RCP CL IV, UNLESS OTHERWISE APPROVED BY THE CITY ENGINEER. 21. FOR RESIDENTIAL SUBDIVISIONS, UNLESS OTHERWISE APPROVED BY DEVELOPMENT SERVICES ENGINEERING, THE FINAL GRADING OF THE PROJECT SITE SHALL BE CONSTRUCTED TO ACCOMMODATE A MAXIMUM DRIVEWAY SLOPE OF 14% FOR EACH RESIDENTIAL LOT, AS MEASURED FROM THE BACK OF THE SIDEWALK TO THE GARAGE (20-FT SET BACK). IT WILL REMAIN THE RESPONSIBILITY OF THE BUILDERS/DEVELOPER TO DESIGN A HOUSE THAT PROVIDES SUITABLE ACCESS TO THE PARCEL. 22. THE CONTRACTOR SHALL PLACE FILTER FABRIC BETWEEN THE INITIAL BEDDING AND BACKFILL AND THE TRENCH BACKFILL FOR SANITARY SEWERS DEPTH GREATER THAN 15 FEET MEASURED TO THE PIPE INVERT. 23. COMPOSITE BASE SHEET: THE PROPOSED IMPROVEMENTS SHOWN ON THESE DRAWINGS ARE SUPERIMPOSED ON A BASE SHEET. THIS BASE SHEET IS COMPILED FROM THE TOPOGRAPHIC SURVEY, OTHER ARCHITECTURAL AND/OR ENGINEERING DOCUMENTS, AND OTHER DATA AS MADE AVAILABLE TO THE LANDSCAPE ARCHITECT. THIS BASE SHEET INFORMATION IS SHOWN IN HALF TONE ON THE PLANS. THE LANDSCAPE ARCHITECT SHALL NOT BE HELD LIABLE FOR CHANGES, INACCURACIES, OMISSIONS, OR OTHER ERRORS ON THESE DOCUMENTS. THE COMPOSITE BASE SHEET IS PROVIDED AS AN AID ONLY AND THE CONTRACTOR SHALL BE RESPONSIBLE FOR REVIEWING THESE DOCUMENTS AND INCORPORATING/INTEGRATING ALL CONSTRUCTION AS REQUIRED TO ACCOMMODATE SAME. THE BASE SHEET SOURCE FOR THESE DRAWINGS IS: CO-61 PARK AS-BUILT EXHIBIT (CO61RG) 24. IN ACCORDANCE WITH THE CITY’S NOISE ORDINANCE, THE HOURS OF PROJECT CONSTRUCTION SHALL BE LIMITED TO THE FOLLOWING: 7:00 A.M. TO 7:00 P.M. (MONDAY THROUGH FRIDAY) 8:00 A.M. TO 8:00 P.M. (SATURDAY, SUNDAY, AND HOLIDAYS). 25. PRIOR TO COMMENCEMENT OF GRADING ACTIVITIES, THE CONTRACTOR SHALL HAVE THE EXISTING DRY UTILITIES POT HOLED FOR VERIFICATION OF LOCATION AND DEPTH. AT SUCH TIME, POT HOLE DATA SHALL BE PROVIDED TO THE ENGINEER FOR DETERMINATION OF ADEQUATE CLEARANCE AND SEPARATION. 26. PRIOR TO THE COMMENCEMENT OF GRADING OPERATIONS, THE CONTRACTOR SHALL IDENTIFY THE SITE WHERE THE EXCESS/BORROW EARTHEN MATERIAL SHALL BE IMPORTED/DEPOSITED. IF THE BORROW/DEPOSIT SITE IS WITHIN THE CITY OF ROSEVILLE, THE CONTRACTOR SHALL PRODUCE A REPORT ISSUED BY A GEOTECHNICAL ENGINEER TO VERIFY THAT THE EXPORTED MATERIALS ARE SUITABLE FOR THE INTENDED FILL, AND SHALL SHOW PROOF OF ALL APPROVED GRADING PLANS. HAUL ROUTES TO BE USED SHALL BE SPECIFIED. 27. CITY OF ROSEVILLE BENCHMARK: BENCHMARK 96, NAVD 29, 3 1 4" BRASS DISK STAMPED 2018 PLS 8278, TOP OF CURB 1 FOOT SOUTH OF D.I. AT THE SOUTHWEST CORNER OF THE INTERSECTION OF BLUE OAKS BLVD. AND WOODCREEK OAKS BLVD. (2012 B.M.96 DATUM NGVD88 ELEV= 1114.97, PLS5978) CITY ENGINEER ACCEPTED BY: DATE DEPT. OF DEVELOPMENT SERVICES MODEL CODES ALL WORK SHALL CONFORM TO THE FOLLOWING CODES: 2025 CALIFORNIA BUILDING CODE WITH CITY OF ROSEVILLE AMENDMENTS (CBC) 2025 CALIFORNIA GREEN BUILDING STANDARDS CODE (CGBSC) 2025 CALIFORNIA ELECTRICAL CODE WITH CITY AMENDMENTS (CEC) 2025 CALIFORNIA ENERGY CODE (CEC PART 6) 2025 CALIFORNIA FIRE CODE WITH CITY OF ROSEVILLE AMENDMENTS (RFC) 2025 CALIFORNIA PLUMBING CODE (CPC) 2025 CALIFORNIA MECHANICAL CODE (CMC) CURRENT VERSION CITY OF ROSEVILLE PARKS DESIGN AND CONSTRUCTION STANDARDS CITY OF ROSEVILLE CWJ#: 500353 EN#: EN25-0621 BD#: WDID#: ROSEVILLE, CA 95747 CO-61 PARK 02/09/2026 SHEET SCHEDULE SHEET DESCRIPTION 1.0 COVER SHEET WITH CALCULATIONS 1.1 CITY OF ROSEVILLE STANDARD NOTES 1.2 BASE BID SCOPE OF WORK PLAN & SITE ACCESSIBILITY PLAN 1.3 ALL ALTERNATES SCOPE OF WORK PLAN & SITE ACCESSIBILITY PLAN 2.0 DEMOLITION PLAN 3.0 GRADING & DRAINAGE PLAN 4.0 - 4.1 EROSION CONTROL PLAN 5.0 - 5.1 LAYOUT PLAN 6.0 IRRIGATION PLAN - BASE BID 6.1 IRRIGATION PLAN - ADD ALTERNATES 6.2 IRRIGATION NOTES 7.0 PLANTING PLAN - BASE BID 7.1 PLANTING PLAN- ADD ALTERNATES 8.0 - 8.6 LANDSCAPE DETAILS E0.1 ELECTRICAL SHEET INDEX, SYMBOL LIST, ABBREVIATIONS, AND GENERAL NOTES E1.1 SITE PLAN - REMODEL - ELECTRICAL E3.1 ONE-LINE POWER DIAGRAM AND PANEL SCHEDULE E.4.1 ELECTRICAL DETAILS E5.1 TITLE 24 - OUTDOOR LIGHTING COMPLIANCE FORMS E5.2 TITLE 24 - ELECTRICAL POWER DISTRIBUTION COMPLIANCE FORMS LANDSCAPE ARCHITECT Callander Associates Landscape Architecture, Inc. 12150 Tributary Point Drive, Suite 140 Gold River, CA 95670 Phone: (916) 985-4366 ELECTRICAL ENGINEER M. Neil's Engineering, Inc. 100 Howe Ave., Ste. 235N Sacramento, CA 95825-8217 Phone: (916) 923-4400 GEOTECH ENGINEER Geocon Consultants Inc 3160 Gold Valley Drive, Suite 800 Phone: (916) 852 - 9118 City of Roseville 316 Vernon Street, Ste. 400 Roseville, CA 95678 UTILITY COMPANY CONTACT PHONE USA - - 1-800-642-2444 ELECTRICITY ROSEVILLE ELECTRIC KEITH LITTS 916-580-9405 WATER CITY OF ROSEVILLE SEAN BIGLEY 916-774-5750 SEWER CITY OF ROSEVILLE ENVIRONMENTAL UTILITIES 916-774-5750 DRAINAGE DEVELOPMENT SERVICES ENGINEERING ENGINEERING 916-774-5339 VICINITY MAP LOCATION MAP PREPARED BY UTILITY REPRESENTATIVES PREPARED FOR BID ALTERNATES ADD ALTERNATE #1: 2 BAY SWING WITH BUCKET SEATS AND SEATING AREA ADD ALTERNATE #2: HALF BASKETBALL COURT WITH POST AND CABLE FENCE AND ADD ALTERNATE #3: SHADED PICNIC AREA ADD ALTERNATE #4: ADDITIONAL LAWN AREA ADD ALTERNATE #5: BIKE TRAIL CONNECTION ADD ALTERNATE #6: SHADE STRUCTURE AT PLAY AREA BUILDING DEPT. REVIEW TO BE COMPLETED WITH NEXT SUBMITTTAL ALL IMPROVEMENTS WHICH FALL UNDER THE PURVIEW OF THE CBC ARE SHOWN HEREON FOR REFERENCE ONLY AND SHALL REQUIRE A SEPARATE BUILDING PERMIT. PLEASE CONTACT THE CITY OF ROSEVILLE BUILDING DEPARTMENT FOR FURTHER INFORMATION. 65 BLUE OAKS BLVD
FOOTSHILLS BLVD
ROSEVILLE PKWY PROJECT SITE
WOODCREEKOAKS BLVD
FIDDYMENT RD 65 BLUE OAKS BLVD
ROSEVILLE PKWY PROJECT SITE
BLUE DOG DR
FOOTSHILLS BLVD NORTH N.T.S. N.T.S. NORTH CUT & FILL CALCULATIONS DISTURBED ACRES: 5.05 AC EARTHWORK CALCULATIONS VOLUME CUT: 1645 CY VOLUME FILL: 1617 CY NET CUT: 28 CY 1.0 DEFERRED SUBMITTALS TO BE COMPLETED WITH NEXT SUBMITTTAL SPECIAL INSPECTIONS TO BE COMPLETED WITH NEXT SUBMITTTAL SURVEYOR ACCEPTED BY: DATE CERTIFICATE OF COMPLIANCE
FOR COUNCIL APPROVAL ONLY
File Path: T:\Projects\2025\25034_CO61Park\3_ConstructionDocuments\25034_CV.dwg Plot Date: 2/9/26 Saved By: Cma Copyright © 2020 Callander Associates Landscape Architecture, Inc. www.callanderassociates.com 12150 Tributary Point Drive, Suite 140 Gold River, CA 95670 T 916.985.4366 ROSEVILLE, CA 95747 PROJECT NO: DRAWN BY: CHECKED BY: SCALE: SHEET TITLE 25034 CM/DS BW As Shown SHEETOF 28 REVISION DATE SUBMITTAL DATE 30% Submittal 09/30/25 CO-61 PARK
5125 ASHBBROOK ST, 99% Submittal 11/18/25 100% Submittal 02/09/26 CITY OF ROSEVILLE STANDARD NOTES 2 1.1 CITY OF ROSEVILLE EROSION CONTROL NOTES 1. THE STATE'S GENERAL PERMIT FOR STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY (WQD 99-080-DWQ) REQUIRES THE PREPARATION OF A STORMWATER POLLUTION PREVENTION PLAN (SWPPP) FOR SITES WITH SOIL DISTURBANCES GREATER THAN OR EQUAL TO ONE ACRE, OR FROM SITES SMALLER THAN ONE ACRE IF THE CONSTRUCTION ACTIVITY IS PART OF A LARGER PLAN OF DEVELOPMENT OR SALE THAT DISTURBS ONE ACRE OR MORE. CONSTRUCTION ACTIVITY SHALL NOT COMMENCE, NOR A PRE-CONSTRUCTION MEETING PERMITTED TO BE SCHEDULED, PRIOR TO THE SWPPP BEING ACCEPTED BY THE CITY. FOR MORE INFORMATION SEE; http://www.roseville.ca.us/eu/stormwater_management 2. THE PROJECT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) IS INCORPORATED BY REFERENCE INTO THIS SET OF PLANS. THE SWPPP IS CONSIDERED A DYNAMIC DOCUMENT AND WILL CHANGE AS CONDITIONS WARRANT. PERMANENT EROSION AND SEDIMENT CONTROL MEASURES WILL BE CONSTRUCTED AS SHOWN ON THESE PLANS. 3. A COPY OF THE SWPPP SHALL BE KEPT AT THE PROJECT SITE AT ALL TIMES. 4. ALL EROSION AND SEDIMENT CONTROL MEASURES SHALL BE IMPLEMENTED AS SPECIFIED IN THE SWPPP AND/OR AS DIRECTED BY CITY INSPECTOR. 5. NO GRADING OR TRENCHING, EXCEPT AS REQUIRED FOR EROSION OR SEDIMENT CONTROL, SHALL OCCUR WITHIN 35 FEET FROM THE CENTERLINE OF PERENNIAL AND INTERMITTENT DRAINAGE SWALES BETWEEN OCTOBER 15 AND APRIL 15 EXCEPT AS APPROVED BY THE DEPARTMENT OF FISH AND GAME. 6. ALL EROSION AND SEDIMENT CONTROL MEASURES SHALL BE MAINTAINED IN ACCORDANCE WITH THE SWPPP. 7. THE CONTRACTOR SHALL ESTABLISH A SPECIFIC SITE WITHIN THE DEVELOPMENT FOR MAINTENANCE AND STORAGE OF EQUIPMENT OR ANY OTHER ACTIVITY THAT MAY ADVERSELY CONTRIBUTE TO THE WATER QUALITY OF THE RUNOFF IN ACCORDANCE WITH THE SWPPP. REV. 6-16-05 1. GRADING SHALL CONFORM TO APPENDIX CHAPTER 33 UBC, LATEST EDITION, AND TO THE RECOMMENDATIONS OF THE GEOTECHNICAL ENGINEERING REPORT BY(ENGINEERING DIV. FILE NO. 308-961) 2. ALL EROSION AND SEDIMENT CONTROL MEASURES SHALL BE IMPLEMENTED AS SPECIFIED IN THE STORMWATER POLLUTION PREVENTION PLAN (SWPPP) FOR THIS PROJECT OR AS DETERMINED BY THE CITY INSPECTOR. THE SWPPP IS CONSIDERED A DYNAMIC DOCUMENT AND WILL CHANGE AS CONDITIONS WARRANT. PERMANENT EROSION AND SEDIMENT CONTROL MEASURES WILL BE CONSTRUCTED AS SHOWN ON THE SWPPP PLAN. 3. LOTS SHALL BE GRADED WITH A CONSTANT SLOPE ALONG THE FRONTAGE OF THE RIGHT-OF-WAY, FROM BUILDING SETBACK LINE TO BACK OF SIDEWALK. ALL TEMPORARY AND PERMANENT SLOPES STEEPER THAN 4:1 ALONG THIS FRONTAGE SHALL HAVE EROSION NETTING INSTALLED. 4. ALL REAR LOT CORNER ELEVATIONS SHALL BE EQUAL TO OR GREATER THAN THE HIGHEST ADJACENT PAD GRADE UNLESS SPECIFICALLY SHOWN ON THESE PLANS AND APPROVED BY ENGINEERING DIVISION. 5. NON-POTABLE WATER SHALL BE SPRAYED ON ALL EXPOSED EARTH SURFACES DURING CLEARING GRADING, EARTH MOVING, AND OTHER SITE PREPARATION ACTIVITIES. THE EXPOSED EARTH SHALL BE WATERED THROUGHOUT THE DAY TO MINIMIZE DUST. 6. TARPAULINS OR OTHER EFFECTIVE COVERS SHALL BE USED ON ALL STOCKPILED EARTH MATERIAL AND ON HAUL TRUCKS TO MINIMIZE DUST. 7. THE CITY SHALL HAVE THE AUTHORITY TO STOP ALL GRADING OPERATIONS, IF, IN OPINION OF CITY STAFF, INADEQUATE DUST CONTROL MEASURES ARE BEING PRACTICED OR EXCESSIVE WIND CONDITIONS CONTRIBUTE TO FUGITIVE DUST EMISSIONS. 8. ADJACENT STREET FRONTAGES SHALL BE SWEPT AT LEAST ONCE A DAY TO REMOVE SILT AND OTHER DIRT WHICH IS EVIDENT FROM CONSTRUCTION ACTIVITIES. REFER TO SCHEDULES WITHIN SWPPP. 9. THE CONTRACTOR SHALL BE RESPONSIBLE FOR CLEANING CONSTRUCTION VEHICLES LEAVING THE SITE ON A DAILY BASIS TO PREVENT DUST, SILT AND DIRT FROM BEING RELEASED OR TRACKED OFFSITE. REFER TO SWPPP FOR SPECIFIC REQUIREMENTS. 10.CONSTRUCTION SHALL STOP IF CULTURAL RESOURCES ARE SUSPECTED. IT IS POSSIBLE THAT PREVIOUS ACTIVITIES HAVE OBSCURED SURFACE EVIDENCE OF CULTURAL RESOURCES. IF SIGNS OF AN ARCHEOLOGICAL SITE, SUCH AS ANY UNUSUAL AMOUNTS OF STONE, BONE, OR SHELL, ARE UNCOVERED DURING GRADING OR OTHER CONSTRUCTION ACTIVITIES, WORK SHALL BE HALTED WITHIN 100 FEET OF THE FIND AND THE ROSEVILLE COMMUNITY DEVELOPMENT DEPARTMENT SHALL BE NOTIFIED. A QUALIFIED ARCHEOLOGIST SHALL BE CONSULTED FOR AN ON-SITE EVALUATION. THE ARCHEOLOGIST MAY REQUIRE ADDITIONAL MITIGATION. 11. SHOULD GRADING OPERATIONS UNCOVER HAZARDOUS MATERIALS, OR WHAT APPEARS TO BE HAZARDOUS MATERIALS, THE FIRE DEPARTMENT SHALL BE CONTACTED IMMEDIATELY AT (916) 774-5820. THE AREA, WHICH CONTAINS THE HAZARDOUS MATERIALS, SHALL BE MARKED OFF UNTIL AN INVESTIGATION BY A MEMBER OF THE FIRE DEPARTMENT IS CONDUCTED. 12.GRADES SHOWN OUTSIDE OF THE PUBLIC RIGHT OF WAY WITHIN THE APPROVED GRADING PLAN ARE SUBJECT TO FURTHER REVIEW AND MODIFICATION BY THE BUILDING DIVISION FOR COMPLIANCE WITH THE UNIFORM BUILDING CODE AND STATE OF CALIFORNIA TITLE 24 HANDICAP ACCESSIBILITY REQUIREMENTS. 13. THE CONTRACTOR/DEVELOPER IS EXPECTED TO COMPLY WITH THE FUGITIVE DUST CONTROL REQUIREMENTS FROM THE PLACER COUNTY AIR POLLUTION CONTROL DISTRICT: WWW.PLACER.CA.GOV/APCD 14.CONTAMINATED SOIL - DEVELOPER AGREES TO PROPERLY ADHERE TO ALL THEN CURRENT STATE AND FEDERAL REQUIREMENTS WHEN ANY EVIDENCE OF TOXIC, HAZARDOUS OR CONTAMINATED SOILS ARE ENCOUNTERED DURING ANY AND ALL EXCAVATION OR GRADING OPERATIONS, AND TO INDEMNIFY, DEFEND AND HOLD HARMLESS THE CITY OR ROSEVILLE, ITS OFFICERS, AGENTS AND EMPLOYEES, FROM ANY AND ALL LIABILITY, COSTS, CLAIMS, FEES, FINES, PENALTIES AND CLAIMS OF OR DAMAGE OF ANY TYPE WHATSOEVER. EXTRA COSTS FOR REMEDIATION AND/OR REMOVAL OF SOIL SHALL BE BOURN SOLELY BY THE DEVELOPER. THE PARTIES INTEND THAT THIS PROVISION BE BROADLY CONSTRUED. REV. 04/28/2009 CITY OF ROSEVILLE GRADING & DRAINAGE NOTES TREE PRESERVATION: 1. GRADING AROUND TREES TO BE LIMITED TO OUTSIDE THE DRIPLINE. ANY TREE WELL GRADED SHOULD BE DRAINED TO SOME OUTFALL OR SWALE. 2. THE FOLLOWING CONDITIONS SHALL APPLY TO ENSURE THE PRESERVATION OF TREES: A.EACH TREE OR GROUP OF TREES TO BE SAVED SHALL BE FENCED BY A CHAIN-LINK FENCE PRIOR TO ANY GRADING OR MOVEMENT OF HEAVY EQUIPMENT OR ISSUANCE OF ANY PERMITS. B. FENCING SHALL BE LOCATED ONE FOOT (1') OUTSIDE THE DRIPLINE OF THE TREE OR TREES. C.SIGNS SHALL BE POSTED ON ALL SIDES OF SAID FENCES STATING: WARNING: THIS FENCE SHALL NOT BE REMOVED OR RELOCATED WITHOUT WRITTEN AUTHORIZATION FROM THE PLANING DEPARTMENT 3. THE GRADING PLAN FOR THE PROJECT HAS BEEN DESIGNED FOR NO GRADING TO OCCUR WITHIN THE DRIPLINE OF ANY OAK TREE UNLESS SPECIFICALLY APPROVED BY PLANNING DEPARTMENT AND SHOWN ON THESE PLANS. NO GRADES SHALL BE MODIFIED WITHOUT THE APPROVAL OF THE CIVIL ENGINEER AND THE CITY OF ROSEVILLE. 4. NO TRENCHING SHALL OCCUR BENEATH THE DRIPLINE OF ANY OAK TREE TO BE SAVED UNLESS STATED ON THESE PLANS "TRENCHING UNDER THIS TREE IS APPROVED". 5. PARKING OF VEHICLES AND EQUIPMENT OR STORAGE OF MATERIALS UNDER THE DRIPLINE OF TREES SHALL NOT OCCUR AT ANY TIME. REV. 2/23/05 CITY OF ROSEVILLE TREE PRESERVATION NOTES
FOR COUNCIL APPROVAL ONLY
119.45 119.10 12"W10"S 117.71 FL
117.85
117.43 FL
117.43 FL 48"D 12"W 12"W 6"D
1.5"RW 6"S 6"S 1.5"RW 10"S 10"S 30"D 12"W 30"D 30" D 30"D 18"D 6"D 6"D 1"W 24"D 12"W 24"D 24"D 12"W 12"W 12"W 6"RW 36"D 24"D 6"D 10"S 30"D 60" D
18"D 113 113 114 114 116 117 118 116 117 118 119 112 113 114 111 109 108 107 111 110 115 107 108 109 111 112 113 114 116
117 118 115 113 113 114 114 114 116 117
118 118 36"D 36"D W
KNIGHTSBRIDGE LANE ASHBROOK STREET ASHBROOK STREET LIMIT OF WORK LIMIT OF WORK LIMIT OF WORK LIMIT OF WORK 24 32 16 8 EXISTING BASIN PER CAMPUS OAKS CO-2 / EN21-0224 PLANS EXISTING BASIN PER CAMPUS OAKS CO-2 / EN21-0224 PLANS BASIN OVERFLOW P.A. P.A. P.A. AD-01 AD-03 P.A. AD-02 AD-03 P.A. PLANTING AREA PROPOSED TREE, REFER TO PLANTING PLAN 7.0 ACCESSIBLE PATH OF TRAVEL POST AND CABLE FENCE SYMBOL DESCRIPTION CONCRETE PAVEMENT PLAY AREA WOOD FIBER COMPACTED AGGREGATE BASE TURF AREA NATIVE SEED AREA File Path: T:\Projects\2025\25034_CO61Park\3_ConstructionDocuments\25034_SCO.dwg Plot Date: 2/9/26 Saved By: Cma Copyright © 2020 Callander Associates Landscape Architecture, Inc. www.callanderassociates.com 12150 Tributary Point Drive, Suite 140 Gold River, CA 95670 T 916.985.4366 ROSEVILLE, CA 95747 PROJECT NO: DRAWN BY: CHECKED BY: SCALE: SHEET TITLE 25034 CM/DS BW As Shown SHEETOF 28 REVISION DATE SUBMITTAL DATE 30% Submittal 09/30/25 CO-61 PARK
5125 ASHBBROOK ST, Know what'sbelow. Call before you dig. R 99% Submittal 11/18/25 100% Submittal 02/09/26 1.2 3BASE BID SCOPE OF WORK PLAN & SITE ACCESSIBILITY PLAN 0 30 feet 1"=30' 60 NORTH LEGEND CODE DESCRIPTION ACCESSIBILITY KEYNOTES PICNIC PAD, INCLUDING (1) ACCESSIBLE PICNIC TABLE (1) ADA ACCESSIBLE DRINKING FOUNTAIN COMPANION SEATING AREA AD-01 AD-02 AD-03 REFERENCE NOTES SCHEDULE
FOR COUNCIL APPROVAL ONLY
119.45 119.10 12"W10"S 117.71 FL
117.85
117.43 FL
117.43 FL 48"D 12"W 12"W 6"D
1.5"RW 6"S 6"S 1.5"RW 10"S 10"S 30"D 12"W 30"D 30" D 30"D 18"D 6"D 6"D 1"W 24"D 12"W 24"D 24"D 12"W 12"W 12"W 6"RW 36"D 24"D 6"D 10"S 30"D 60" D
18"D 110 115 107 108 109 111
112 113 114 116
117 118 115 113 113 114 114 114 116 117
118 118 36"D 36"D W
KNIGHTSBRIDGE LANE ASHBROOK STREET ASHBROOK STREET LIMIT OF WORK LIMIT OF WORK LIMIT OF WORK LIMIT OF WORK 24 32 16 8 EXISTING BASIN PER CAMPUS OAKS CO-2 / EN21-0224 PLANS EXISTING BASIN PER CAMPUS OAKS CO-2 / EN21-0224 PLANS BASIN OVERFLOW ADD ALTERNATE #1: 2 BAY SWING WITH BUCKET SEATS AND SEATING AREA ADD ALTERNATE #2: HALF BASKETBALL COURT ADD ALTERNATE #3: SHADED PICNIC AREA ADD ALTERNATE #4: ADDITIONAL LAWN AREA DETAIL CONCRETE PAVEMENT PLAY AREA WOOD FIBER FERENCE NOTES SCHEDULE ADD ALTERNATE #6: SHADED PLAY AREA SYMBOL DESCRIPTION CONCRETE PAVEMENT PLAY AREA WOOD FIBER DECOMPOSED GRANITE AGGREGATE BASE ASPHALT PAVEMENT TURF AREA P.A. PLANTING AREA PROPOSED TREE, REFER TO PLANTING PLAN 7.1 File Path: T:\Projects\2025\25034_CO61Park\3_ConstructionDocuments\25034_SCO_ALT.dwg Plot Date: 2/9/26 Saved By: Cma Copyright © 2020 Callander Associates Landscape Architecture, Inc. www.callanderassociates.com 12150 Tributary Point Drive, Suite 140 Gold River, CA 95670 T 916.985.4366 ROSEVILLE, CA 95747 PROJECT NO: DRAWN BY: CHECKED BY: SCALE: SHEET TITLE 25034 CM/DS BW As Shown SHEETOF 28 REVISION DATE SUBMITTAL DATE 30% Submittal 09/30/25 CO-61 PARK
5125 ASHBBROOK ST, Know what'sbelow. Call before you dig. R 99% Submittal 11/18/25 100% Submittal 02/09/26 1.3 4ALL ALTERNATES: SCOPE OF WORK PLAN & SITE ACCESSIBILITY PLAN 0 30 feet 1"=30' 60 NORTH ADD ALTERNATE #5: BIKE TRAIL CONNECTION LEGEND BID ALTERNATE SCHEDULE TITLE DESCRIPTION ADDITIVE ALTERNATE #1 2 BAY SWING W/ BUCKET SEATS AND SEATING AREA ADDITIVE ALTERNATE #2 HALF BASKETBALL COURT ADDITIVE ALTERNATE #3 SHADED PICNIC AREA ADDITIVE ALTERNATE #4 ADDITIONAL LAWN AREA ADDITIVE ALTERNATE #5 BIKE TRAIL CONNECTION ADDITIVE ALTERNATE #6 SHADED PLAY AREA DEDUCT MULCH, SHRUBS, AND IRRIGATION. ADD CONCRETE PAVEMENT, BENCH, PLAY AREA CURB, PLAY AREA WOOD FIBER, PLAY RAMP, AND TWO BAY SWING SET. DEDUCT MULCH, SHRUBS, AND IRRIGATION. ADD CONCRETE PAVEMENT, BENCHES, AND BASKETBALL GOAL. ADD 12'x20' PICNIC SHADE SHELTER. DEDUCT MULCH, NATIVE SEED MIX, AND 12" MOWBAND. ADD TURF FROM SEED, TURF IRRIGATION, AND 12" MOWBAND. DEDUCT NATIVE SEED MIX AND 8'-0" WIDE AGGREGATE BASE PATH. ADD ASPHALT PAVEMENT, 2' AB SHOULDER AND 2' DG SHOULDER. ADD PLAY STRUCTURE SHADE CANOPY.
FOR COUNCIL APPROVAL ONLY
119.45 119.10 1.5% 12"W10"S 117.71 FL
117.85
117.43 FL
117.43 FL 48"D 12"W 12"W 6"D
1.5"RW 6"S 6"S 1.5"RW 10"S 10"S 30"D 12"W 30"D 30" D 30"D 18"D 6"D 6"D 1"W 24"D 12"W 24"D 24"D 12"W 12"W 12"W 6"RW 36"D 24"D 6"D 10"S 30"D 60" D
18"D 113 113 114 114 116 117 118 2.51% 0.99% 2.80% 1.41% 2.14%
2.82%
2.50%
3.28%
2.23%
1.62% 1.47% 1.10% 2.06% 1.67% 1.44% 1.55%
2.64%
2.31%
1.52%
1.61%
1.41% 1.11% 1.21% 1.72%
1.84%
1.60%
3.28%
1.46%
1.49% 3.26% 3.15% 116 117 118 119 112 113 114 111 109 108 107 111 110 115 107 108 109 111 112 113 114 116
117 118 115 113 113 114 114 114 116 117
118 118 36"D 36"D W
KNIGHTSBRIDGE LANE ASHBROOK STREET ASHBROOK STREET EXISTING BASIN PER CAMPUS OAKS CO-2 / EN21-0224 PLANS EXISTING BASIN PER CAMPUS OAKS CO-2 / EN21-0224 PLANS D-01 D-01 D-01 D-02 LIMIT OF WORK D-03 D-03 D-04 D-04 LIMIT OF WORK LIMIT OF WORK LIMIT OF WORK D-05 D-05 D-05 MV FS C BF D-02 D-06 D-07 112.64 112 File Path: T:\Projects\2025\25034_CO61Park\3_ConstructionDocuments\25034_DM.dwg Plot Date: 2/9/26 Saved By: Cma Copyright © 2020 Callander Associates Landscape Architecture, Inc. www.callanderassociates.com 12150 Tributary Point Drive, Suite 140 Gold River, CA 95670 T 916.985.4366 ROSEVILLE, CA 95747 PROJECT NO: DRAWN BY: CHECKED BY: SCALE: SHEET TITLE 25034 CM/DS BW As Shown SHEETOF 28 REVISION DATE SUBMITTAL DATE 30% Submittal 09/30/25 CO-61 PARK
5125 ASHBBROOK ST, Know what'sbelow. Call before you dig. R 99% Submittal 11/18/25 100% Submittal 02/09/26 2.0 5DEMOLITION PLAN 0 30 feet 1"=30' 60 NORTH DEMOLITION LEGEND CLEAR AND GRUB TO LIMITS OF DEMOLITION AND GRADING ACTIVITIES. REMOVE EXISTING ASPHALT PAVEMENT AND AGGREGATE BASE, ASSUME 12" DEPTH. SAWCUT EXISTING SURFACE, SEE DEMOLITION KEYNOTE D-07 CONSTRUCTION FENCING, PER SPECS REMOVE AND DISPOSE OF ITEM DEMOLITION NOTES 1. CLEAR AND GRUB: CONTRACTOR SHALL CLEAR AND GRUB ALL EXISTING VEGETATION, UNLESS OTHERWISE INDICATED, AS REQUIRED FOR THE SITE CONSTRUCTION, IRRIGATION, AND PLANTING OPERATIONS. LIMITS OF CLEARING SHALL BE REVIEWED WITH OWNER PRIOR TO COMMENCEMENT OF WORK. STRIP ALL ORGANIC MATTER TO A SUFFICIENT DEPTH TO COMPLETELY REMOVE SUCH MATERIAL. CONTRACTOR SHALL REVIEW DEMOLITION, CLEARING AND GRUBBING REQUIREMENTS ON SITE WITH LANDSCAPE ARCHITECT PRIOR TO COMMENCING DEMOLITION OPERATIONS. CODE DESCRIPTION DETAIL DEMOLITION KEYNOTES LIGHT POLE TO REMAIN, PROTECT IN PLACE IRRIGATION EQUIPMENT TO REMAIN, PROTECT IN PLACE AND ADJUST TO GRADE FIRE HYDRANT TO REMAIN, PROTECT IN PLACE SIGN TO REMAIN, PROTECT IN PLACE EXISTING FENCE TO REMAIN SAWCUT REMOVE EIXSITNG CURB AND CONCRETE PAVEMENT D-01 D-02 D-03 D-04 D-05 D-06 D-07 REFERENCE NOTES SCHEDULE EXISTING SYMBOLS LIGHT POLE FIRE HYDRANT VALVE SIGNAGE DRAIN INLET STORM DRAIN MANHOLE SPOT ELEVATION CONTOURS (1-FT INTERVALS) EXISTING FENCE D-07
FOR COUNCIL APPROVAL ONLY