City of Hermosa Beach
CIP 689- CLARK BUILDING RENOVATIONS CONSTRUCTION SCHEDULE 01 3213-13
shall be proportionally shared to benefit OWNER and CONTRACTOR. The use of any technique solely for the purpose of suppressing float will result in OWNER rejection of the submitted Monthly Schedule Update.
C. In the event CONTRACTOR believes the Project has suffered an adverse impact, CONTRACTOR may prepare a Time Extension Request by submitting a Schedule Fragnet and a written narrative outlining the detail of the impact. A Schedule Fragnet must demonstrate a critical path delay. Such a delay must adversely impact the Substantial Completion Date for CONTRACTOR to receive a time extension.
To demonstrate such an impact successfully, CONTRACTOR shall prepare a Schedule Fragnet based on a copy of OWNER accepted Monthly Schedule Update for the calendar month during which the adverse impact occurred. This “copy” of the OWNER accepted Monthly Schedule Update shall however first be updated (by OWNER and CONTRACTOR jointly) with both Percentages of Completion and Actual Dates up to the day the delay commenced. This process will provide the “pre-delay” project status. Once OWNER and CONTRACTOR have agreed to the “pre-delay” project status, CONTRACTOR should make a copy of this “pre-delay” schedule and this copy is to be the starting point for CONTRACTOR’S Schedule Fragnet development. OWNER will evaluate the activities, logic, durations, etcetera. The Fragnet shall also include CONTRACTOR-caused delays that affect the critical or near critical path in the network and should be accounted for in the Time Impact Analysis if overlapped at any point in time with OWNER-caused delay. If rain impact days were granted between the Start and Finish of OWNERcaused delay period, they should be accounted for in the Time Impact Analysis as well. Provided OWNER determines such an impact occurred, CONTRACTOR may be due a time extension equal to the number of proportioned days of variance/delay that resulted to the Substantial Completion Date.
D. Activities added into a Schedule Fragnet to demonstrate the impact of adverse event shall be assigned a unique activity code. The Schedule shall be organized by this unique activity code.
E. The Schedule Fragnet shall incorporate logic that accurately ties reflective of the adverse event to pre-event predecessor activities and post eventsuccessor activities.
F. It is crucial for the Fragnet to be submitted within the same month of discovery so it can be resolved during the monthly schedule update review. The notice shall be transmitted to OAR.
G. If OWNER accepts CONTRACTOR’S Schedule Fragnet and an extension is granted, a Change Order will be prepared. OWNER will advise what change order number the time extension will become. When CONTRACTOR receives this Change Order number, all the activities added to the Schedule Fragnet shall be given Activity Identification Numbers that corresponds with the Change Order number. CONTRACTOR shall cost load and resource-load the activities if required by OWNER. If resource loading is required, the resource loading shall include a breakdown of labor, material, and equipment quantities.
180730
City of Hermosa Beach
CIP 689- CLARK BUILDING RENOVATIONS CONSTRUCTION SCHEDULE 01 3213-14
H. If OWNER rejects CONTRACTOR’S Schedule Fragnet in part based on improper forecast logic or activity tasks then it shall be revised accordingly to conform to OWNER’S review comments and resubmitted. If the forecast logic and activity tasks cannot be agreed to then the pre-delay schedule outlined in Article 3.07-C shall be compared to the actual as-built data in the succeeding month of the encountering issue, event, condition, circumstance, and/or cause. The variance to the project between the pre-delay and post delay schedules shall be discussed in CONTRACTOR’S written narrative and proportioned between the different parties involved in the delay.
.
3.08 FAILURE TO COMPLY WITH REQUIREMENTS
A. At any time during the project if CONTRACTOR fails to comply with the specified requirements, OWNER reserves the right to engage independent estimating and scheduling consultants to fulfill these requirements. Upon notice to CONTRACTOR, OWNER shall assess against CONTRACTOR, incurred costs for these additional services.
B. In such an event, OWNER will require, and CONTRACTOR shall participate and provide requested information to ensure the resulting Milestones Schedule accurately reflects CONTRACTOR’s plan to execute the Work in compliance with the Contract Documents. If it becomes necessary for OWNER to recommend logic or duration revisions as a result of CONTRACTOR failure to furnish acceptable data, and if CONTRACTOR has objections to the recommendations, CONTRACTOR shall provide notice to OWNER within three days and CONTRACTOR shall provide an acceptable alternate plan. If CONTRACTOR fails to so note any objections and provide an acceptable alternate plan, or if CONTRACTOR implements the recommendations of OWNER without so noting any objections, CONTRACTOR will be deemed to have waived all objections and concurred with the recommended logic/duration revisions provided by ARCHITECT and/or OWNER.
C. Submittal of any Monthly Schedule Updates are subject to review and acceptance by OWNER. OWNER retains the right to withhold progress payments in whole or part until CONTRACTOR submits a Monthly Schedule Update acceptable to OWNER. If a Monthly Schedule Update is “Rejected” due to the OWNER not receiving a satisfactory schedule that accurately reflects the on-going work activities, the OWNER will mandate a separate meeting with the CONTRACTOR and approved Scheduler to remedy the non-conformance.
3.10 CONTRACTOR RESPONSIBILITY
A. Nothing in this Section shall be construed to be a usurpation of CONTRACTOR authority, responsibility, and obligation to plan and schedule Work as CONTRACTOR deems necessary, subject to all other requirements of the Contract Documents.
180730
City of Hermosa Beach
CIP 689- CLARK BUILDING RENOVATIONS CONSTRUCTION SCHEDULE 01 3213-15
B. CONTRACTOR shall involve the subcontractors, manufacturers, and suppliers in the development and periodic updating of the schedule.
3.11 RECORD DOCUMENTS / FINAL AS-BUILT SCHEDULE
A. Prior to Contract Completion of the Work, CONTRACTOR shall submit a final asbuilt schedule, and a time-scaled network diagram reflecting the actual dates of all activities. This shall be submitted prior to the final application of payment and prior to the request to release retention.
END OF SECTION
City of Hermosa Beach
CIP-689- Clark Building Renovations
GENERAL COMMISSIONING REQUIREMENTS
01 9113-1
SECTION 01 9113
GENERAL COMMISSIONING REQUIREMENTS
PART 1 – GENERAL
1.01 SECTION INCLUDES
A. This Section defines the Contractor's responsibilities with respect to Commissioning.
The Contractor shall include this scope in the bid. This includes administrative and procedural requirements as well as a detailed execution of Commissioning. This Section supplements Section 01 4523 – Testing and Inspection, Section -01 4525 Testing, Adjusting, and Balancing for HVAC, as well as the Divisions 22 - Plumbing, Division 23 – Mechanical, and Division 26 – Electrical sections which specify testing procedures.
For projects that have Specification Section 01 4516 or 01 4519, Contractor Construction Quality Control, the Commissioning schedule and activities as defined in the approved Commissioning Plan shall be incorporated by Contractor into the Construction Quality Control (CQC) plan. The Commissioning Services Provider will be part of the Owner’s Quality Assurance (QA) Team and participate in the review and execution of the Project Construction Quality Control (CQC) plan, along with the Contractor, Owner’s Authorized Representative (OAR), Project Inspector (PI), and Architect of Record (AOR).
1.02 DEFINITIONS
A. Commissioning (Cx): A systematic process which verifies that the building systems perform according to the Owner’s Design Intent/Basis of Design (ODI/BOD).
Commissioning includes system documentation, equipment startup, control system calibration, Testing, Adjusting and Balancing (TAB) verification, performance testing, and training.
B. Commissioning Services Provider (CxSP): A City of Hermosa Beach appointed entity that plans and coordinates all activities which implement Commissioning as outlined by the Owner’s Design Intent/Basis of Design (ODI/BOD). The CxSP has overall responsibility for planning and coordinating Commissioning. Commissioning activities that take place during construction shall be based on the Contractor’s construction schedule.
C. Commissioning Plan (CxP): A contract document that identifies the project Commissioning goals, Owner’s Design Intent/Basis of Design, commissioning milestones, coordination requirements, and project specific Pre-functional Equipment Checklists and Functional Performance Test Checklists. The CxP shall be incorporated by Contractor into the Construction Quality Control Plan.
City of Hermosa Beach
CIP-689- Clark Building Renovations
GENERAL COMMISSIONING REQUIREMENTS
01 9113-2
D. Pre-functional Equipment Checklist (PEC): A form for each piece of equipment referenced in ‘1.08 SYSTEMS TO BE COMMISSIONED’ that must be completed by the Contractor as a prerequisite to the equipment’s Functional Performance Test (FPT).
Sample checklists and PEC forms are included in the CxP. The checklists and forms are completed by the Contractor and verified by the CxSP.
E. Functional Performance Test (FPT): A documented test designed by the Commissioning Services Provider to verifies the dynamic functioning and operation of equipment and systems with the goal of verifying that the Owners’ Design Intent, Owner’s Project Requirements, and Basis of Design (BOD) are met. Sample testing requirements and forms are included in the CxP. Test procedures are performed by the Contractor and witnessed by the INSPECTOR and CxSP.
F. Acceptance - A formal action, taken by a person with appropriate authorization, to declare that some aspect of the project meets defined requirements – thereby permitting subsequent activities to proceed.
G. Checklists - Documents that are developed and used during all phases of commissioning to verify that the Owner’s intent is being achieved. This includes checklists for general verification, testing, training, and other specific requirements. Various checklists are prepared by the CxSP and the contractor to document completion of testing and/or commissioning of equipment and systems.
I. Coordination Drawings - Drawings showing the work of all trades to illustrate that equipment can be installed in the space allocated without compromising equipment function or access for maintenance and replacement. These drawings graphically illustrate and dimension manufacturers’ recommended maintenance clearances.
K. Control system – A component of an environmental, HVAC, electrical, lighting, or energy management system for the reporting, monitoring and/or issuing of commands to and/or from field devices.
L. Data logging -The monitoring and recording of flows, currents, status, pressures, etc., of equipment using stand-alone data recorders separate from the installed control system or the trending capabilities of those control systems.
M. Deficiency - A condition that is not in compliance with the contract documents relative to the installation or function of a component, piece of equipment, or system.
N. Factory Testing - Testing of equipment at the factory or on-site by factory personnel with, or without, an owner’s representative present.
O. Issues Log - A formal and ongoing record of problems or concerns – and their resolution – that have been raised by members of the commissioning team during the course of commissioning.
City of Hermosa Beach
CIP-689- Clark Building Renovations
GENERAL COMMISSIONING REQUIREMENTS
01 9113-3
P. Seasonal Performance Tests - Tests that are performed when weather conditions are comparable to the design conditions based or the design conditions can be simulated.
R. Simulated Condition - Condition that is created for the purpose of testing the response of a system (for example: raising/lowering the set point of a thermostat to see the response in a VAV box).
S. Startup - The initial starting or activating of dynamic equipment.
T. Systems Manual - A system-focused composite document that includes the operation manual, maintenance manual, manufacturer’s technical diagrams and additional information of use to the owner during facility occupancy and operation.
U. Test Procedure - A written protocol that defines methods, procedures, personnel, and expected outcomes for tests conducted on components, equipment, assemblies, systems, and interfaces among systems. The test procedures are specified in the Commissioning Plan and Technical Specifications sections of the contract documents and the CxP.
V. Training Plan - A written document that details the expectations, schedule, budget, and deliverables of commissioning activities related to the training of facility operating and maintenance personnel, users, and occupants.
X. Verification - The process by which specific documents, components, equipment, assemblies, systems, and interfaces among systems are confirmed to comply with the criteria described in the Owner’s Design Intent/Basis of Design. Verification testing is performed per the prescribed test procedure(s) by the contractor and witnessed by the INSPECTOR and CxSP.
Y, Trending – The analysis of system performance gathered over a period of time by a building management system or other electronic data gathering equipment.
1.03 RELATED REQUIREMENTS
A. Section 00 7300 – Supplementary Conditions.
B. Section 01 2513 – Product Substitution Procedures.
C. Section 01 3113 – Project Coordination.
D. Section 01 3119 – Project Meetings.
E. Section 01 3213 – Construction Schedule.
F. Section 01 3300 - Submittal Procedures.
G. Section 01 4516 or 01 4519 – Contractor Construction Quality Control.
City of Hermosa Beach
CIP-689- Clark Building Renovations
GENERAL COMMISSIONING REQUIREMENTS
01 9113-4
H. Section 01 4523 - Testing and Inspection.
I. Section 01 4525 - Testing, Adjusting, and Balancing for HVAC.
J. Section 01 5000 – Construction Facilities and Temporary Controls.
K. Section 01 7700 – Contract Close-Out.
L. Section 01 7836 – Warranties.
M. Section 01 7900 – Staff Demonstration and Training.
N. Section 23 0800 – HVAC Systems Commissioning.
O. Section 23 0813 – Environmental Controls and Energy Management Systems Commissioning.
P. Section 26 0800 – Electrical Systems Commissioning.
1.04 REFERENCES
A. Guideline 1.1-2007 -- HVAC&R Technical Requirements for the Commissioning Process.
B. Associated Air Balance Council Commissioning Guidelines.
C. CHPS Best Practices Manual, Volume V: Commissioning.
D. Sample Commissioning Plan Documentation.
1.05 COORDINATION
A. Items listed below require coordination between the Contractor, OAR, INSPECTOR, and CxSP. Details regarding each item are provided through out this Section and/or Sections 01 7900, 23 0800, 23 0813 and 26 0800.
1. Cx Schedule and Meeting Venue.
2. Commissioning Meeting Attendance.
3. Completion of Pre-functional Equipment Checklists (PEC).
4. Functional Performance Testing (FPT).
5. Operations & Maintenance Manual Submittal and Training.
6. Documentation of Pre-functional Equipment Checklists (PEC) & Functional Performance Testing (FPT) Inspections.
City of Hermosa Beach
CIP-689- Clark Building Renovations
GENERAL COMMISSIONING REQUIREMENTS
01 9113-5
B. For projects using Specification Section 01 4516 or 01 4519, the CxSP shall coordinate with the Contractor’s designated Quality Control representative, OAR and INSPECTOR.
1.06 SUBMITTALS
A. Submittal documentation required for the commissioning work will be identified by the CxSP and integrated into the normal submittal process and protocol of the construction team. At minimum, the CxSP’s documentation request will identify the manufacturer and model number, the manufacturer’s printed installation and detailed startup procedures, full sequences of operation, O&M data, performance data, any performance test procedures, control drawings and details of owner contracted tests. In addition, the installation and checkout materials that are actually shipped inside the equipment and the actual field checkout sheet forms to be used by the factory or field technicians shall be submitted. All such documentation will be included by subcontractors in their O&M manual submittals.
B. The CxSP will review and recommend acceptance or any required revision to the OAR for all submittals related to the commissioned equipment for conformance with the contract documents as they relate to commissioning, performance of the equipment, and their adequacy of test procedures. This review is intended primarily to aid in the development of performance procedures and only secondarily to verify compliance with equipment specifications. The CxSP will notify the OAR of items missing or areas that are not in conformance with contract documents and which require resubmission.
Submittal of O&M manual documentation does not constitute compliance. The CxSP will review all such document submittals and recommend to OAR their acceptance or any required revisions.
C. Submittal documentation specified in Specifications 23 0800, 23 0813 and 26 0800.
1.07 CONTRACTOR RESPONSIBILITIES
A. The general responsibilities of Contractor and Subcontractors in commissioning are defined in this section. The specific responsibilities are in the Division 22 and 23 and Division 26 Technical Specifications. All parties shall:
1. Follow the Commissioning Plan.
2. Attend commissioning meetings.
B. Contractor, its design team, subcontractors and vendors shall assign representatives with expertise and authority to act on their behalf and schedule them to participate in and perform required commissioning activities including, but not limited to, providing all tools, or the use of tools, to start, check-out and test equipment and systems, except for specified testing with portable data recorders which shall be supplied and installed by the CxSP. Contractor and subcontractors shall:
City of Hermosa Beach
CIP-689- Clark Building Renovations
GENERAL COMMISSIONING REQUIREMENTS
01 9113-6
1. Facilitate coordination of Commissioning.
2. Incorporate Commissioning activities (the CxP) into the Project Schedule.
3. Coordinate and direct Commissioning activities in a logical, sequential and efficient manner using consistent protocols and forms, centralized documentation, clear and regular communications and consultations with all necessary parties, frequently updated timelines and schedules and technical expertise.
4. Participate in up to three meetings specifically for Commissioning-related items as scheduled by the OAR.
5. Review and accept construction checklists developed by the CxSP.
6. Provide information required to perform commissioning tasks, including O&M materials, contractor startup and checkout lists.
7. No later than 60 days prior to startup of the first piece of major equipment, meet with the CxSP and OAR to finalize the detailed commissioning procedures and schedule.
8. Before startup, provide detailed startup procedures including current control sequences and interlocks to comply with the detailed functional test plans.
9. Provide one additional copy of all submittals required in Section 01 3300 for all systems being commissioned for review of compliance with commissioning needs by the CxSP.
10. Develop and coordinate a startup and initial systems checkout plan with subcontractors and ensure that all subcontractors and vendors execute their commissioning responsibilities according to the contract documents.
11. Review TAB execution plan.
12. Oversee sufficient testing of the control system before TAB is executed.
13. Evaluate performance deficiencies identified in test reports and, in collaboration with entity responsible for system and equipment installation, recommend corrective action.
14. Coordinate retesting as necessary until satisfactory performance is achieved
15. Complete checklists as work is completed and provide to OAR on a weekly basis.
16. Review equipment warranties to ensure that the owner’s responsibilities to keep warranties in force are clearly defined.
City of Hermosa Beach
CIP-689- Clark Building Renovations
GENERAL COMMISSIONING REQUIREMENTS
01 9113-7
17. Oversee and coordinate the training of the owner’s personnel.
18. Review and approve the preparation of the O&M manuals including clarifying and updating of original sequences of operation to as-built/as-tested conditions.
19. Coordinate development of a systems manual
1.08 SYSTEMS TO BE COMMISSIONED
A. Systems to be commissioned for this project include, but are not limited to, those for which Specifications are included in Contract Documents and as listed in:
1. Section 23 0800, Article 1.06 - Equipment And Systems To Be Commissioned.
2. Section 23 0813.
3. Section 26 0800, Paragraph 3.01.B.
PART 2 – PRODUCTS
1.01 TEST EQUIPMENT
A. Standard testing equipment required to perform startup and initial checkout and required performance testing shall be provided by the contractor for the equipment being tested.
This includes, but is not limited to, two-way radios and meters, etc. Testing specified as requiring portable data recorders will be performed with data recorders supplied and installed by the CxSP.
B. Testing equipment shall be of sufficient quality and accuracy to test and/or measure system performance within the tolerances specified in the specifications. If not otherwise noted, the following minimum requirements apply: Temperature sensors and digital thermometers shall have a current certified calibration to an accuracy of 0.5 degree F and a resolution of plus or minus 0.1 degree F. Pressure sensors shall have an accuracy of plus or minus 2.0 percent of the value range being measured (not full range of meter) and have been calibrated within the last year. All equipment shall be calibrated according to the manufacturer’s recommended intervals and when dropped or damaged.
Calibration tags shall be affixed or certificates readily available.
PART 3 – EXECUTION
1.02 MEETINGS
A. Commissioning Kick-off Meeting: Within 15 days following issuance of Notice-toProceed 1 (NTP 1), the OAR will schedule a Construction Quality Control kick-off meeting. The INSPECTOR, Cx team and Contractor Quality Control representative
City of Hermosa Beach
CIP-689- Clark Building Renovations
GENERAL COMMISSIONING REQUIREMENTS
01 9113-8
will be in attendance. CxSP shall prepare and distribute a list of commissioning topics to be placed on the meeting agenda. Attendance at this meeting and participation in the Commissioning topics is mandatory for the following Contractor personnel:
1. Contractor’s Quality Control Engineer and Commissioning Representative.
2. Contractor’s Project Scheduling personnel.
3. Mechanical Subcontractors.
4. Electrical Subcontractors.
5. TAB Subcontractor.
6. Controls Subcontractors.
B. Other Commissioning Meetings. Other Cx meetings will routinely be scheduled and generally be conducted in conjunction with regularly scheduled site meetings as the Construction progresses. The Commissioning portion of meetings will cover upcoming implementation and coordination of the CxP, deficiency resolution, and planning issues with particular subcontractors.
3.02 STARTUP, CONSTRUCTION CHECKLISTS, AND INITIAL CHECKOUT A. The following procedures apply to all equipment/systems to be commissioned:
1. General: Contractor shall use PECs to verify that the equipment and systems are fully connected and operational. PECs for a given system must be successfully completed and accepted prior to startup and formal performance testing of equipment or subsystems of the given system.
2. Startup and Checkout Plan: The CxSP will assist the project commissioning team members responsible for startup of any equipment. The primary role of the CxSP in this process is to ensure that there is written documentation and that each of the manufacturer-recommended procedures has been completed. The CxSP shall provide all the required pre-functional checklists and forms to be completed by Contractor in the CxP. The CxSP will ensure that the INSPECTOR and/or District Special Inspectors are informed as to the planned and scheduled startup and checkout procedures.
a. Sample Pre-Functional checklists are provided as an attachment to the CxP. These checklists indicate required procedures to be executed prior to equipment startup.
b. Contractor shall determine which trade is responsible for executing and documenting each of the line item tasks and transmit the checklists to
City of Hermosa Beach
CIP-689- Clark Building Renovations
GENERAL COMMISSIONING REQUIREMENTS
01 9113-9
the responsible subcontractors. Each form may have more than one trade responsible for its execution.
c. The contractor/subcontractor responsible for the purchase and/or installation of the equipment shall develop a comprehensive startup plan (with assistance from the CxSP) by combining the manufacturer’s detailed startup and checkout procedures and the pre-functional checklists.
d. The contractor/subcontractor shall submit the full startup plan to the CxSP for review and approval.
e. INSPECTOR will review and accept, based on CxSP recommendation, the procedures and the documentation format for reporting. The CxSP will return the procedures and the documentation format to Contractor through the OAR.
f. Contractor shall transmit the full startup plan to the subcontractors for their review and use.
B. Sensor and Actuator Calibration. All field-installed temperature, relative humidity, CO, CO2, refrigerant, O2, and/or pressure sensors and gages, and all actuators (dampers and valves) on all equipment shall be calibrated. Verify that all locations are appropriate and away from causes of erratic operation. Submit to the CxSP through the OAR the calibration methods and results. All test instruments shall have had a current certified calibration record. Sensors installed in the unit at the factory with calibration certification provided need not be field calibrated. Contractor to field verify all installed sensors.
1. Sensor Calibration Methods:
a. All Sensors: Verify that all sensor locations are appropriate and away from causes of erratic operation. Verify that sensors with shielded cable are grounded only at one end. For sensor pairs that are used to determine a temperature or pressure difference, make sure they are reading within
0.2 degrees F of each other for temperature and within a tolerance equal to 2 percent of the reading of each other for pressure. b. Sensors Without Transmitters: Standard Application. Make a reading with a calibrated test instrument within 6 inches of the site sensor. Verify that the sensor reading (via the permanent thermostat, gage or building automation system (BAS)) is within the tolerances in the table below of the instrument-measured value. If not, install offset in BAS, calibrate or replace sensor.
c. Sensors With Transmitters: Standard Application. Make a reading with a calibrated test instrument within 6 inches of the site sensor. Verify
City of Hermosa Beach
CIP-689- Clark Building Renovations
GENERAL COMMISSIONING REQUIREMENTS
01 9113-10
that the sensor reading (via the permanent thermostat, gage or building automation system (BAS)) is within the tolerances in the table below of the instrument-measured value. If not, install offset in BAS and calibrate or replace sensor.
2. Tolerances, Standard Applications:
Sensor
Required
Tolerance (+/-)
Cooling coil, chilled and condenser water
temps 0.4F
AHU wet bulb or dew point 2.0F
Hot water coil and boiler water temp 1.5F
Outside air, space air, duct air temps 0.4F
Watthour, voltage & amperage 1 percent of
design
Pressures, air, water and gas 3 percent of
design
Flow rates, air, water 10 percent of
design
Flow rates, water
Relative humidity
4 percent of
design
Combustion flue temps 5.0F
Oxygen or CO2 monitor 0.1 percent pts
CO monitor 0.01 percent pts
Natural gas and oil flow rate 1 percent of
design
Barometric pressure 0.1 inch of Hg
3. Valve and Damper Stroke Setup and Check EMS Readout: For all valve and damper actuator positions checked, verify the actual position against the BAS readout. Set pumps or fans to normal operating mode. With the command calve and damper closed, visually verify that the command valve or damper is closed and adjust output zero signal as required. With the command valve or damper open, visually verify that the position is full open and adjust output signal as required. Set command valve or damper to a few intermediate positions. If actual valve or damper position doesn’t reasonably correspond, repair or replace actuator.
4. Closure for heating coil valves (NO): Set heating set point 20 degrees F above room temperature. Visually observe valve open. Set heating set point to 20 degrees F below room temperature. Visually observe the valve close. Restore to normal.
City of Hermosa Beach
CIP-689- Clark Building Renovations
GENERAL COMMISSIONING REQUIREMENTS
01 9113-11
5. Closure for cooling coil valves (NC): Set cooling set point 20 degrees F above room temperature. Visually observe the valve close. Set cooling set point to 20°F below room temperature. Visually observe valve open. Restore to normal.
C. Execution of Construction Checklists and Startup:
1. Four weeks prior to the scheduled startup, Contractor shall coordinate startup and checkout with the INSPECTOR and CxSP. The execution and approval of the PECs, startup, and checkout shall be directed and performed by Contractor, subcontractor or vendor. Signatures are required of the applicable subcontractors for verification of completion of their work.
2. The INSPECTOR shall observe, as a minimum, the procedures performed for each piece of primary equipment, unless there are multiple units; in which case a sampling strategy may be used. The CxSP shall observe all testing.
3. For lower-level components of equipment, (e.g., sensors, controllers), the CxSP shall observe a sampling of the startup procedures.
4. Pre-functional checklist documentation, identified in the CxP, is to be used by the sub-contractor to document that equipment is ready for startup.
5. The subcontractors and vendors shall execute startup and provide the CxSP, through the OAR, with a signed and dated copy of the completed startup and construction checklists.
6. Only individuals of the contractor or sub-contractor (technicians, engineers, manufacturer’s representatives/vendors, supervisors, etc.) who have direct knowledge and have witnessed that a line item task on the construction checklist was actually performed shall check off that item.
D. Deficiencies, Non-Conformance, and Approval in Checklists and Startup (Issues Log):
1. The contractor shall ensure that the subcontractors clearly list any outstanding items of the initial startup and construction checklist procedures that were not completed successfully, on an attached sheet. The form and any outstanding deficiencies shall be provided, through the INSPECTOR, to the CxSP within two days of test completion.
2. The CxSP will review the report and issue either a non-compliance report or acceptance form, through the INSPECTOR, to Contractor. The installing subcontractors or vendors shall correct all areas that are deficient or incomplete in the checklists and tests in a timely manner, shall notify the INSPECTOR as soon as outstanding items have been corrected, and resubmit an updated startup report with a Statement of Correction on the original non-compliance
City of Hermosa Beach
CIP-689- Clark Building Renovations
GENERAL COMMISSIONING REQUIREMENTS
01 9113-12
report. When satisfactorily completed, the CxSP will recommend approval of the execution of the checklists and startup of each system.
3. Items left incomplete, which later cause deficiencies or delays during performance testing, may result in assessments to Contractor. Refer to Paragraph 3.05, herein, for details.
3.03 GENERAL REQUIREMENTS FOR TESTING
A. Complete the following at least two weeks prior to Functional Performance Testing:
1. Arrange for Commissioning observations to be performed by the CxSP.
2. Completion and acceptance of the Start-up Plan by the CxSP.
3. Correction of deficiencies identified during start-up.
4. Recording of pretest set points.
3.04 FUNCTIONAL PERFORMANCE TESTING (FTP)
A. Undertake functional testing after the testing requirements listed in Paragraph 3.02 are completed.
B. Equipment: Refer to Part 2 of this Section for test equipment requirements.
C. Perform FPT under the observation of the CxSP who will verify the results of the functional test procedures documented by Contractor.
D. Perform all specified tests according to approved testing procedures / plan.
1. Verify and test performance using actual conditions whenever possible.
2. Simulate conditions when it is not practical to test under actual conditions or when required seasonal testing conditions are not present. The procedure to be used shall be submitted to the OAR for INSPECTOR and CxSP review and acceptance at least one week before simulated testing is to occur. After test, return settings to normal operating conditions.
3. Alter set points when simulating conditions is not practical and when written approval to do so is received from OAR.
4. Override sensor values with a signal generator when actual or simulated conditions and altering set points are not practical. Do not use the sensor to act as the signal generator to simulate conditions or override values.
City of Hermosa Beach
CIP-689- Clark Building Renovations
GENERAL COMMISSIONING REQUIREMENTS
01 9113-13
E. Functional Performance Testing (FPT) Documentation: This Section specifies the general description of the minimum Divisions 22, 23 and 26 Functional Performance Testing documentation requirements that the Contractor shall provide. The CxSP will develop testing procedures in accordance to the requirements of this Section and incorporate into the Cx Plan that Contractor must follow and document. The testing documentation must include the following information:
1. Test number.
2. Date and time of the test.
3. Indication of whether the record is for a first test or retest following correction of a problem or issue.
4. Identification of the system, subsystem, assembly, or equipment.
5. Conditions under which the test was conducted, including (as applicable) ambient conditions, set points, override conditions, and status and operating conditions that impact the results of the test.
6. Expected performance of the systems and assemblies at each step of the test.
7. Narrative description of observed performance of the system, equipment, or assembly.
8. Notation to indicate whether the observed performance at each step meets the expected results.
9. Issue number, if any, generated as the result of the test.
10. Dated signatures of the person performing the test and a witness.
F. The CxSP and INSPECTOR will review and OAR, if applicable, accept functional testing results. Deficiencies found during testing shall be submitted to the OAR and, if required, based on the recommendation of INSPECTOR, by the OAR, corrected by the Contractor and retested. Where there is a dispute over a deficiency, OAR, based on the recommendation of ARCHITECT and INSPECTOR, shall be the final authority.
G. Problem Solving: The burden of responsibility to solve, correct and retest problems is with the Contractor and the design team with OAR, based on the recommendations of the ARCHITECT, CxSP and INSPECTOR, having final responsibility for acceptance of the Work.
H. Substantial Completion: All testing, retesting, and acceptance of Functional Performance Testing shall be completed prior to issuing the Certificate of Substantial Completion. FPT may be conducted following building occupancy; however, all
City of Hermosa Beach
CIP-689- Clark Building Renovations
GENERAL COMMISSIONING REQUIREMENTS
01 9113-14
associated and reasonable additional costs incurred by the CxSP shall be assessed against Contractor Retention or Withhold funds.
I. Deficiencies in the Cx Plan Functional Performance Test Checklist: If there is any Functional Performance Test Checklist missing for any particular piece of equipment, the Contractor shall inform the CxSP and ask for an updated Functional Performance Test Checklist.
3.05 RETESTING
A. Retesting shall be required when a specific Pre-functional Checklist or Start-up test item, reported to have been successfully completed by Contractor or determined during functional testing to be faulty or incomplete, is identified.
B. Contractor shall be provided one retest opportunity at no additional cost when Contractor can make corrections within two hours of identification of the need to retest.
Costs for retesting beyond one retest, or when Contractor cannot make corrections within two hours of identification of the need to retest, will be assessed against Contractor funds if OAR determines, based upon the recommendation of the INSPECTOR and CxSP, that the Contractor is responsible for the deficiency. These costs shall include all reasonable expenses incurred by the CxSP.
C. For a deficiency identified during functional testing, but not included in the approved Start-up Plan, OAR will direct retesting of the equipment with no costs assessed against Contractor for this initial retesting. Costs for retesting, when Contractor cannot effect corrections within two hours of identification of the need to retest, will be assessed against Contractor funds if OAR determines, based upon the recommendation of the INSPECTOR and CxSP, that the Contractor is responsible for the deficiency. These costs shall include all reasonable expenses incurred by the CxSP.
D. Retesting shall not be considered a reason for a claim of delay or for a time extension by the Contractor.
3.06 DEFERRED TESTING
A Unforeseen Deferred Tests: Checks or tests not completed due to the incomplete Work, required occupancy conditions, or other conditions may be delayed upon approval of the OAR based upon the recommendation of the INSPECTOR and CxSP.
These tests may be conducted in the same manner as the seasonal tests.
B. Seasonal Testing: Complete seasonal testing, when weather or other testing conditions do not emulate the system’s design conditions, employing simulated conditions acceptable to OAR based upon the recommendation of the INSPECTOR and CxSP. The OAR will coordinate with Contractor, and CxSP validate, this activity. Tests shall be executed, documented and deficiencies corrected by the Contractor, with the
City of Hermosa Beach
CIP-689- Clark Building Renovations
GENERAL COMMISSIONING REQUIREMENTS
01 9113-15
INSPECTOR and the CxSP witnessing. The Contractor shall make adjustments to the Operations and Maintenance Data, as necessary.
3.07 DOCUMENT REVIEW
A. General: See paragraph 1.06 for submittal requirements.
B. Operations and Maintenance Manuals: Refer to Section 01 7900 for specific requirements.
3.08 OPERATOR TRAINING
A. The CxSP, under the direction of the OAR, coordinates and verifies training completion as shown in Section 01 7900. Forms and procedures are also described in the CxP.
END OF SECTION
120727
City of Hermosa Beach
CIP 689- Clark Building Renovations
PROGRESS PAYMENT PROCEDURES
01 2976-1
SECTION 01 2976
PROGRESS PAYMENT PROCEDURES
PART 1 - GENERAL
1.01 SECTION INCLUDES:
A. This Section specifies administrative and procedural requirements for a certified Application for Payment.
1. Coordinate the certified Schedule of Values and certified Application for Payment with, but not limited to, the Construction Schedule, submittal log, and list of Subcontractors.
1.02 RELATED REQUIREMENTS:
A. Section 01 2100: Allowances.
B. Section 01 2300: Alternates (Bid Items).
C. Section 01 2973: Schedule of Values.
D. Section 01 3213: Construction Schedule.
E. Section 01 3229: Project Forms.
F. Section 01 7700: Contract Closeout.
PART 2 - PRODUCTS (Not used)
PART 3 - EXECUTION
3.01 APPLICATION FOR PAYMENT
A. Each certified Application for Payment shall be consistent with previous applications and payments as reviewed by OAR, paid for by OWNER, and:
1. The initial Application for Payment and Final Application for Payment at time of Substantial Completion involve additional requirements.
B. Payment Application Times: The period of Work covered by each Application for Payment is payment date for each progress payment as specified in the Special Provisions Section 7. The period covered by each Application for Payment is previous month.
120727
City of Hermosa Beach
CIP 689- Clark Building Renovations
PROGRESS PAYMENT PROCEDURES
01 2976-2
C. Payment Application Forms: Use OWNER provided forms for the Application for Payment.
D. Application Preparation: Complete every entry on the form. Include execution by a person authorized to sign legal documents on behalf of CONTRACTOR. OAR will return incomplete applications without action.
E. Transmittal: Submit a minimum of four signed and original copies of each certified Application for Payment to OAR. All copies shall be complete, including releases and similar attachments.
1. Transmit each copy with a transmittal form listing attachments and recording appropriate information related to the application, in a manner acceptable to OAR.
F. Initial Application for Payment within 60 days of issuance of Notice to Proceed:
Administrative actions and submittals, that must precede or coincide with submittal for first certified Application for Payment include, but are not limited to, the following:
1. Certified Schedule of Values.
2. Performance and payment bonds.
3. List of principal suppliers and fabricators.
4. Worker Compensation certificates, if applicable.
5. Auto Insurance, if applicable.
6. Hazardous Material Insurance Certificates, if applicable.
7. Construction Schedule.
8. Submittal Schedule.
9. Emergency Contact List.
10. Copies of authorizations and licenses from governing authorities for performance of Work.
11. Certified Payroll (Submitted directly to Labor Compliance in electronic format as specified by OWNER including hard copy).
12. Storm Water Pollution Prevention Plan (SWPPP).
13. Certification of Compliance with CEQA Mitigations.
120727
City of Hermosa Beach
CIP 689- Clark Building Renovations
PROGRESS PAYMENT PROCEDURES
01 2976-3
G. Applications for Payment: Administrative actions and submittals that must precede or coincide with submittal of Progress Applications for Payment include, but are not limited to, the following:
1. Certified Payroll (submitted directly to Labor Compliance in electronic format as specified by OWNER including hard copy).
2. Updated and current Project Record Drawings (as-built).
3. Monthly Construction Schedule (updated, submitted and approved).
4. Approved Schedule of Values.
5. List of Subcontractors (Payments Summary).
6. Storm Water Pollution Prevention (SWPP) – Site Monitoring Report.
7. Certification of Compliance with CEQA Mitigations.
H. Final Application for Payment at Substantial Completion: Following OAR issuance of certificate of Substantial Completion, submit an Application for Payment:
1. Administrative actions, submittals and/or Work that shall precede or coincide with this application include:
a. Occupancy permits and similar approvals by authorities having legal jurisdiction over Work.
b. Removal of temporary facilities and services.
c. Testing, adjusting and balance records.
d. Removal of surplus materials, rubbish, and similar elements. e. Meter readings.
f. Start-up performance reports.
g. OWNER training and orientations.
h. Operating and maintenance instruction manuals.
i. Preliminary Warranties, guarantees and maintenance agreements. j. Delivery of extra materials, products and or stock.
k. Change over information related to OWNER occupancy, use, operation, and maintenance.
120727
City of Hermosa Beach
CIP 689- Clark Building Renovations
PROGRESS PAYMENT PROCEDURES
01 2976-4
l. Final cleaning.
m. Ensure that Work is completed.
n. Advise on shifting insurance coverage.
o. List of defective Work, recognized as exceptions to certificate of Substantial Completion.
p. Change of door locks, including keys, to OWNER system. q. Certified Payroll (submitted directly to Labor Compliance in electronic format as specified by the OWNER including hard copy). r. Certification that all benefit contributions due and owing to appropriate union trusts has been paid by CONTRACTOR and Subcontractors, as specified by the Project Stabilization Agreement (PSA) and Article 6.49 of the General Conditions.
s. Storm Water Pollution Prevention – Site Monitoring Reports, SWPP revisions, compliance certifications, and Notice of Termination (NOT) (see Section 01 7416).
t. Certification of Compliance with CEQA Mitigations.
u. Waivers and releases for CONTRACTOR.
END OF SECTION
180730
City of Hermosa Beach
CIP 689- Clark Building Renovations
PROJECT MEETINGS
01 3119-1
SECTION 01 3119
PROJECT MEETINGS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. This Section specifies administrative and procedural requirements for Project meetings, including but not limited to, the following:
1. Pre-Construction meeting.
2. Pre-installation conferences.
3. Progress meetings.
4. Meetings as required by OAR.
1.02 RELATED REQUIREMENTS
A. Section 01 3113: Project Coordination.
B. Section 01 3213: Construction Schedule.
C. Section 01 3229: Project Forms.
D. Section 01 3300: Submittal Procedures.
PART 2 – PRODUCTS (Not used)
PART 3 - EXECUTION
3.01 PRE-CONSTRUCTION MEETING
A. The OAR will schedule a pre-construction meeting before starting the Work, at a time and date determined by OAR. Meeting shall be held at the Project site or another location as determined by OAR. Meeting will be held in order to review responsibilities, procedures, and other administrative requirements contained within the Contract Documents.
B. Authorized representatives of OWNER, INSPECTOR, ARCHITECT, CONTRACTOR and other parties shall attend the meeting. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
180730
City of Hermosa Beach
CIP 689- Clark Building Renovations
PROJECT MEETINGS
01 3119-2
C. Agenda items shall include significant items which could affect progress of the Work, including, but not limited to the following:
1. Preliminary Construction Schedule.
2. Critical work sequencing.
3. Designation of responsible personnel.
4. Identification of OAR.
5. Procedures for processing field decisions.
6. Request for Proposal.
7. Request for Clarification.
8. Construction Directive and Change Order.
9. Procedures for processing Applications for Payment.
10. Prevailing wages.
11. Submittal and review of Shop Drawings, Product Data, material lists, and Samples.
12. Preparation of project record documents.
13. Use of the Project site and/or premises.
14. Parking availability.
15. Office, work, and storage areas.
16. Equipment deliveries and priorities.
17. Safety procedures.
18. First Aid.
19. Security.
20. Housekeeping.
21. Working hours.
22. Contract Compliance Officer.
23. Insurance Services including OCIP.
180730
City of Hermosa Beach
CIP 689- Clark Building Renovations
PROJECT MEETINGS
01 3119-3
24. Environmental Health and Safety.
25. Substantial Completion, Administrative Closeout and Contract Completion requirements and procedures.
26. Procedures for Mandatory Dispute and Claim Resolution.
27. Storm Water Pollution Prevention Plan (SWPPP).
D. OAR shall prepare and issue meeting minutes to attendees and interested parties no later than five calendar days after the meeting date.
3.02 PRE-INSTALLATION CONFERENCES
A. CONTRACTOR shall coordinate and conduct pre-installation conferences at the Project site as required by related Sections of the Contract Documents.
B. CONTRACTOR, manufacturers, and fabricators involved in or affected by the installation and its coordination or integration with other preceding and/or subsequent installations of Work shall attend the meeting. CONTRACTOR shall advise OAR, INSPECTOR, and ARCHITECT of scheduled meeting dates in order to secure their attendance.
1. CONTRACTOR shall review the progress of construction activities and preparations for the particular activity under consideration at each preinstallation conference, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related Construction Directives and Change Orders.
d. Purchases.
e. Deliveries.
f. Shop Drawings, Product Data, and quality-control samples. g. Review of mockups.
h. Possible conflicts.
i. Compatibility problems.
j. Time schedules.
k. Weather limitations.
180730
City of Hermosa Beach
CIP 689- Clark Building Renovations
PROJECT MEETINGS
01 3119-4
l. Manufacturer’s recommendations.
m. Warranty requirements.
n. Compatibility of materials.
o. Acceptability of substrates.
p. Temporary facilities.
q. Space and access limitations.
r. Governing regulations.
s. Safety.
t. Inspecting and testing requirements.
u. Required performance results.
v. Recording requirements.
w. Protection.
2. CONTRACTOR shall record significant discussions and directives received from each conference. CONTRACTOR shall, within three (3) calendar days after the meeting date, distribute the minutes of the meeting to all concerned parties, including but not limited to, OAR, INSPECTOR, and ARCHITECT.
3.03 PROGRESS MEETINGS
A. Progress meetings will be held at the Project site at regular intervals, typically weekly, as determined by the OAR.
B. In addition to representatives of CONTRACTOR, OWNER, and ARCHITECT, each Subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of the Work shall, if requested by OAR, be represented at these meetings. All participants at the conference shall be familiar with the Project and authorized to conclude all matters relating to the Work.
C. Failure of CONTRACTOR to be so represented at any progress meeting which is held at a mutually agreed time or for which a written notice is given, shall not relieve CONTRACTOR from abiding by any and all OAR determinations or directives issued at such meeting.
180730
City of Hermosa Beach
CIP 689- Clark Building Renovations
PROJECT MEETINGS
01 3119-5
D. OAR will review and correct or approve minutes of the previous progress meeting and will review other significant items affecting progress. Topics for discussion as appropriate to the status of the Project include but are not limited to:
1. Interface requirements.
2. Construction Schedule.
3. Sequence and coordination.
4. Status of submittals / RFCs.
5. Deliveries.
6. Off-site fabrication.
7. Access.
8. Site utilization.
9. Temporary Construction Facilities and Controls.
10. Hours of work.
11. Hazards and risks.
12. Housekeeping.
13. Quality of materials, fabrication, and execution.
14. Unforeseen conditions.
15. Testing and Inspection.
16. Defective Work.
17. Construction Directive.
18. Request for Proposal.
19. Change Order Proposals and Change Orders.
20. Documentation of information for payment requests.
21. Application for Payment.
22. Other items as required or as brought forth..
180730
City of Hermosa Beach
CIP 689- Clark Building Renovations
PROJECT MEETINGS
01 3119-6
23. Initial Notice of Start of Issue, Event, Condition, Circumstance, or Cause of Perceived Delay, Disruption, Interference, Hindrance, Acceleration. (Article 12.2.1 of the General Conditions).
24. Final Notice of End of Issue, Event, Condition, Circumstance, or Cause of Perceived Delay, Disruption, Interference, Hindrance, Acceleration (Article
12.2.2 of the General Conditions).
25. Storm Water Pollution Prevention.
26. CEQA Compliance.
E. No later than three (3) calendar days after each progress meeting, OAR will prepare and distribute minutes of the meeting to each present and absent party. Include a brief summary, in narrative form, of progress, decisions, directives, actions taken, and all other issues since the previous meeting and report.
1. Schedule Updating: CONTRACTOR shall revise the Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized, and issue the revised schedule at the next scheduled progress meeting.
3.04 ADDITIONAL MEETINGS
A. OAR, upon giving notice to the intended parties and without further obligation, may require additional meetings to discuss Work and/or Project related activities.
3.05 OWNER’S RIGHT TO RECORD
A. CONTRACTOR agrees on behalf of itself and all its subcontractors that the OWNER may audiotape or videotape any meetings, training and any work at any time during the Project
END OF SECTION
180730
City of Hermosa Beach
CIP 689- Clark Building Renovations
REQUEST FOR CLARIFICATION
01 2613 -1
SECTION 01 2613
REQUEST FOR CLARIFICATION
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Procedure for requesting clarification of the intent of the Contract Documents.
1.02 RELATED REQUIREMENTS
A. Section 01 1100: Summary of Work.
B. Section 01 3113: Project Coordination.
C. Section 01 3213: Construction Schedule.
D. Section 01 7700: Contract Closeout.
PART 2 - PRODUCTS (Not used)
PART 3 - EXECUTION
3.01 PROCEDURE
A. CONTRACTOR shall prepare a Request for Clarification and transmit the Request for Clarification to ARCHITECT with a concurrent copy to the OAR.
B. ARCHITECT response is a clarification of the intent of the Contract Documents and does not authorize changes in the Contract Amount, Milestones and/or Contract Time.
C. A Request for Clarification may be returned with a stamp or notation "Not Reviewed," if:
1. The requested clarification is ambiguous or unclear.
2. The requested clarification is equally available to the requesting party by researching and/or examining the Contract Documents.
3. CONTRACTOR has not reviewed the Request for Clarification prior to submittal.
D. Allow a minimum of nine days for review and response time, after receipt by ARCHITECT and OAR. CONTRACTOR shall verify and is responsible in verifying ARCHITECT and OAR receipt of a Request for Clarification.
E. Changes or alterations to the approved drawings or specifications shall be made by means of addenda or change orders as per section 4-338 of the California Building Standards Commission’s, California Administrative Code.
180730
City of Hermosa Beach
CIP 689- Clark Building Renovations
REQUEST FOR CLARIFICATION
01 2613 -2
END OF SECTION
130117
City of Hermosa Beach
CIP 689- Clark Building Renovations
SCHEDULE OF VALUES
01 2973-1
SECTION 01 2973
SCHEDULE OF VALUES
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Procedure for submission of a certified Schedule of Values for review and approval by the OAR.
1.02 RELATED REQUIREMENTS
A. Section 01 2976: Progress Payment Procedures.
B. Section 01 3113: Project Coordination.
C. Section 01 3300: Submittal Procedures.
PART 2 - PRODUCTS (Not used)
PART 3 - EXECUTION
3.01 PREPARATION
A. Upon receipt of the Notice of Intent to Award, CONTRACTOR shall commence preparation of a Schedule of Values.
B. CONTRACTOR shall coordinate the preparation of a Schedule of Values with preparation of the Construction Schedule as set forth in Section 01 3213. The corresponding values from the specification division totals on cost loaded schedule shall match with the approved Schedule of Values.
C. Include the following Project identification on a certified Schedule of Values:
1. Project name and location.
2. Project Number.
3. Contract #.
4. CONTRACTOR name.
5. Date of Submittal.
130117
City of Hermosa Beach
CIP 689- Clark Building Renovations
SCHEDULE OF VALUES
01 2973-2
D. The Schedule of Values shall be in tabular form with separate columns and shall include the following items:
1. Related Specification Section and Division.
2. Description of Work.
3. Name of Subcontractor, manufacturer or supplier.
4. Dollar value, quantity and unit of measure of each line item.
5. Percentage of Contract amount to nearest one-hundredth percent, adjusted to total 100 percent.
E. Round amounts to the nearest whole dollar; the total shall equal the Contract Amount.
F. Provide a breakdown of the Contract Amount in enough detail acceptable to OAR to facilitate continued evaluation of Application for Payment and progress reports. Provide line items for subcontract amounts, where appropriate.
G. Provide separate line items for items in the Schedule of Values for total installed value of that part of the Work.
H. Provide separate line item for labor and material when required by the OAR.
I. Each item in the Schedule of Values and Applications for Payment shall be complete.
Include total cost and proportionate share of general overhead and profit for each item except the amounts shown as separate line items.
J. Temporary facilities and other cost items that are not direct cost of actual work-in- place shall be shown as separate line items.
K. An approved certified Schedule of Values shall serve as the basis for the monthly certified Application for Payment.
L. If at any time, OWNER determines, in its reasonable discretion, that the schedule of Values does not approximate the actual cost being incurred by CONTRACTOR to perform the Work, CONTRACTOR shall prepare, for OAR approval, a revised Schedule of Values, which then shall be used as the basis for future progress payments.
Without changing the Contract Amount, OWNER reserves the right to require CONTRACTOR:
1. To increase or decrease amounts within the line items in the Schedule of Values; and,
2. To conform the price breakdown to OWNER accounting practice.
3.02 SUBMITTAL
130117
City of Hermosa Beach
CIP 689- Clark Building Renovations
SCHEDULE OF VALUES
01 2973-3
A. CONTRACTOR shall submit five certified copies of a Schedule of Values for review and approval by the OAR at least 14 days before the first Application for Payment.
B. OAR will review and if necessary, return the submitted Schedule of Values with summary comments noting items not in compliance with the requirements of the Contract Documents. CONTRACTOR shall revise the submitted Schedule of Values and return five copies within three days of receipt of summary comments.
C. Signature by OAR shall constitute acceptance of the submitted Schedule of Values.
D. An approved copy of the Schedule of Values by OAR will be transmitted to CONTRACTOR, and Inspector.
END OF SECTION
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-1
SECTION 01 4525
TESTING, ADJUSTING, AND BALANCING FOR HVAC
PART 1 – GENERAL
1.01 SUMMARY
A. SECTION INCLUDES
1. This Section specifies the requirements for test and balance of HVAC and related systems.
B. RELATED REQUIREMENTS
1. Section 01 1100: Summary of Work.
2. Section 01 3113: Project Coordination.
3. Section 01 3213: Construction Schedule.
4. Section 01 3300: Submittal Procedures.
5. Section 01 7700: Contract Closeout.
6. Section 23 0500: Common Work Results for HVAC.
7. Section 23 0513: Basic HVAC Materials and Methods.
8. Section 23 0548: HVAC Sound, Vibration and Seismic Control.
9. Section 23 0900: HVAC Instrumentation and Controls.
10. Section 23 0923: Environmental Control and Energy Management Systems (Only include when DDC Energy Management and Control Systems are provided).
11. Section 23 2013: HVAC Piping.
12. Section 23 3000: Air Distribution.
13. Section 23 3813: Kitchen Ventilation System.
14. Section 23 5000: Central Heating Equipment
15. Section 23 6416: Oil Lubricated Centrifugal Water Chillers.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-2
16. Section 23 6418: Oil Free Centrifugal Water Chillers.
17. Section 23 6423: Scroll Water Chillers.
18. Section 23 6426: Rotary-Screw Water Chillers.
19. Section 23 6428: Air-Cooled Rotary Screw Chillers.
20. Section 23 6500: Cooling Towers.
21. Section 23 8000: Heating, Ventilating and Air Conditioning Equipment.
22. Section 28 3149: Carbon Monoxide Detection and Alarm Systems.
PART 2 – PRODUCTS (Not used)
PART 3 – EXECUTION
3.01 DEFINITIONS AND APPLICABLE PUBLICATIONS
A. For the purposes of this Section definitions are as indicated in applicable publications of AABC, NEBB, TABB, ASHRAE, ANSI and SMACNA.
1. TAB: Testing, Adjusting and Balancing.
2. TABB: Testing, Adjusting and Balancing Bureau.
3. AABC: Associated Air Balance Council.
4. NEBB: National Environmental Balancing Bureau.
5. ASHRAE: American Society of Heating, Refrigerating and Air-Conditioning Engineers.
6. ANSI: American National Standards Institute.
7. SMACNA: Sheet Metal and Air Conditioning Contractors’ National Association.
8. OAR: OWNER’S Authorized Representative
3.02 QUALITY ASSURANCE
A. The General Contractor shall contract directly with the test and balance agency. Tests performed by testing agencies contracted with the system’s subcontractor will not be accepted. The qualifications of the agency shall comply with Article 3.02, Quality Assurance. The agency shall be responsible for furnishing labor, instruments, and tools required to test, adjust, and balance the heating, ventilating, and air conditioning
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-3
(HVAC) systems and related plumbing systems, as described and/or as indicated in the Contract Documents.
B. CONTRACTOR shall obtain services of an independent, qualified testing agency acceptable to Architect to perform testing and balancing Work as specified and as follows:
1. Agency shall be currently certified by either the Associated Air Balance Council (AABC), the National Environmental Balancing Bureau (NEBB), or the Testing, Adjusting and Balancing Bureau (TABB). NEBB or TABB certification shall be for Air and Hydronic Testing, Adjusting and Balancing and Sound and Vibration Measurement.
2. Work shall be in accordance with the latest edition of the AABC, NEBB, or TABB National Standards. Where the requirements of the two standards are different, the more stringent requirements shall prevail. Also, if the Contract Documents impose a more stringent standard, then the Contract Documents shall prevail.
C. Performance Criteria: Work of this Section shall be performed in accordance with approved Testing, Adjusting, and Balancing agenda.
D. Test Equipment Criteria: Basic instrumentation requirements and accuracy/calibration required by Section Two of the AABC, Section II of the NEBB, or TABB Procedural Standards for Testing, Adjusting and Balancing of Environmental Systems.
E. Verification: The Test and Balance Agency shall recheck 10 percent (minimum 10) of the measurements listed in the report. The locations shall be selected by PROJECT INSPECTOR or OAR. The recheck will be witnessed by PROJECT INSPECTOR or OAR. If 20 percent of the measurements that are retested differ from the report and are also out of the specified range, an additional 10 percent will be tested. If 20 percent fall outside the specified range, the report will be considered invalid and all test and balance work shall be repeated.
F. Due to more stringent acoustical requirements in the educational environment, the Test and Balance Agency shall recheck the air systems where the sound level is higher than the specified requirements and demonstrate compliance with the methodology specified in this document with emphasis on fan speed adjustment and balancing for optimum acoustical performance. The recheck will be witnessed by PROJECT INSPECTOR or OAR. When there are multiple air systems, a system selected by PROJECT INSPECTOR or OAR shall be rechecked. If this system is found to be not in compliance, a second system shall be checked. If the second system if also found to be not in compliance, the report will be considered invalid, and all test and balance work shall be repeated.
3.03 SUBMITTALS
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-4
A. Submit name of agency to perform the Work. Include in the submittal the certified qualifications of all persons responsible for supervising and performing actual Work of this Section. Agency shall submit a minimum of five commercial or industrial HVAC system TAB projects of similar type, size, and degree of difficulty completed within the last two years. Agency shall provide name and telephone number of contact person for each listed project.
B. Submit, for approval, 6 copies of the Agenda as indicated in Article 3.06 to test and balance all mechanical and relevant plumbing systems.
C. Preliminary Report: Review the Contract Documents, examine Work installations and submit a written report to ARCHITECT, PROJECT INSPECTOR and OAR indicating deficiencies in Work precluding proper testing and balancing of the Work.
D. Final TAB Report: Submit the final TAB report for review by ARCHITECT, PROJECT INSPECTOR, and OAR outlining the conditions and Work completed on each HVAC system. All outlets, devices, HVAC equipment, etc. shall be identified, along with a numbering system corresponding to report unit identification.
E. Submit an AABC “National Project Performance Guaranty” or “NEBB Quality Assurance Certification”, assuring the Project systems were tested, adjusted, and balanced in accordance with the Specifications and AABC, NEBB, or TABB National Standards.
F. CAD drawings: Submit single line, multi-color CAD drawings indicating outside return and supply air, volume control boxes, each outlet and inlet, room numbers, duct sizes at traverse locations, temperatures and pressures, systems balanced, components changed, and CONTRACTOR installed access points. In addition, drawings shall identify controls, equipment settings, including manual damper quadrant positions, manual valve indicators, fan speed control levers, and similar controls, and devices shall be marked on the drawings to show final settings. CAD files shall be submitted on CDROM upon final submittal of TAB report. Reports shall identify discrepancies between completed Work and the Contract Documents affecting the performance and longevity of the system.
3.04 GENERAL SCOPE OF WORK
A. The general scope of Work shall include but not be limited to the following:
1. Measure airflow rates of HVAC systems and make adjustments to achieve design airflow rates, tabulate results, and submit reports.
2. Measure water-flow rates of HVAC systems and make adjustments to achieve design water flow rates, tabulate results, and submit reports.
3. Measure flow velocities, temperatures, static pressures or head, rotational speed, and electrical power demand of fans, pumps, and other related HVAC system components, tabulate results, and submit reports.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-5
4. Measure sound levels in each conditioned space, tabulate results, and submit reports.
5. Measure ambient sound levels of outdoor HVAC units and system components such as chillers and cooling towers, tabulate results, and submit reports.
6. Reports shall contain sufficient data for the system designer to evaluate system performance and solve installation problems such as system pressure profiles and pressure drops across system components
3.05 SPECIFIC SCOPE OF WORK
A. The specific scope of Work shall include the following HVAC system components as indicated on the Drawings:
1. Air Handling Units.
2. Air Conditioning Units.
3. Heating and Ventilating Units.
4. Heating and Cooling Coils.
5. Supply, Return, Relief and Exhaust Fans.
6. Outside Air and Return Air Plenums.
7. Outside Air Intakes.
8. All Supply and Return Ductwork.
9. All associated Air Terminal Devices, i.e. Supply Diffusers, Return Registers, etc.
10. Mixing Boxes and Variable Air Volume (VAV) boxes.
11. Reheat Coils (Electric or Hot Water).
12. Exhaust Duct Systems.
13. Fire and Fire/Smoke Dampers.
14. Kitchen Hoods.
15. Laboratory Hoods.
16. Heat Exchangers.
17. Chillers.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-6
18. Cooling Towers.
19. Boilers.
20. Chilled water, heating hot water and cooling tower water pumps.
3.06 TESTING, ADJUSTING, AND BALANCING AGENDA
A. Provide proposed materials, methods, procedures, forms, diagrams, and reports for test and balance Work.
B. Agenda to be completed by the test and balance agency and submitted to ARCHITECT, PROJECT INSPECTOR, and OAR for review and approval.
C. Agenda shall include one complete set of AABC, NEBB, or TABB publications listed in Sub-paragraph 3.02.B.2, applicable publications, or, in case of other test and balance agencies and or organizations, comparable publications to establish an approved, systematic, and uniform set of procedures.
D. Agenda shall also include the following detailed narrative procedures, system diagrams, and forms for test results:
1. Specific standard procedures required and proposed for each system of the Work.
2. Specified test forms for recording each procedure and for recording sound and vibration measurements.
3. Systems diagrams for each air, water, and steam system. Diagrams may be single line.
E. In addition to information recorded for standard AABC, NEBB, or TABB procedures, the following information is required:
1. Fan data.
2. System number, location, manufacturer, model, and serial number.
3. Fan wheel type and size.
4. Motor horse power, type, and rpm.
5. Sheave size, type, number of grooves, and open turns on Variable Pitch Sheave.
6. Number and size of belts, motor and fan shaft sizes, center-to-center of shafts in inches, and adjustment available motor data, including nameplate data, actual amps, rated, and actual motor rpm, volts, phase, hp, kW, starter heater size, and capacity.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-7
7. Fan design airflow and service (supply, return, outdoor air or exhaust).
8. Fan static pressure, suction/discharge, static profile, and static control point.
F. The following traverse data is required:
1. Traverse location, size of duct (inside dimensions), and area of duct in square feet.
2. Column for each hole traversed/lines for each reading.
3. Barometric pressure.
4. Temperature/Static pressure in the duct.
5. Actual CFM corrected to SCFM.
6. Notes.
G. The following air distribution data is required:
1. Room identification.
2. Outlet or intake balance sequence number.
3. Size of outlet or inlet.
4. AK Factor.
5. Design and Actual FPM and CFM.
6. Notes.
H. The following hydronic coil data is required:
1. Air flow through the coil in CFM.
2. Dry bulb and wet bulb temperatures entering/leaving coil.
3. Enthalpy or total heat differences in BTU/pound.
4. Capacity in BTU/hour at time of test.
5. Water temperature and pressure entering/leaving coil.
6. Flow (in GPM) through coil.
7. Air pressure drop across coil.
8. Water head drop across coil.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-8
9. Notes.
I. The following DX coil data is required:
1. Air flow through the coil in CFM.
2. Dry and wet bulb temperatures entering/leaving coil.
3. Enthalpy or total heat difference across coil in BTU/ pound.
4. Capacity in BTU/hour at time of test.
5. Air pressure drop across coil.
6. Notes.
J. The following data is required for steam to water heat exchangers for heat and/or domestic generation:
1. Exchanger identification number.
2. Nameplate data; manufacturer, model, and serial number.
3. Temperature entering/leaving unit.
4. Flow through unit in GPM.
5. Pressure drop through unit.
6. Entering steam pressure.
7. Notes.
K. The following electric heating coil data is required:
1. Heating coil identification number.
2. Nameplate data; manufacturer, model and serial number.
3. Amperage/Voltage on each phase.
4. Phase, kW, and Stages.
5. Safety device installed.
6. Air pressure drop across coil.
7. Notes.
L. The following water-cooled chiller data is required:
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-9
1. Identification number.
2. Nameplate data; manufacturer, model and serial number.
3. Chilled water flow through evaporator in GPM.
4. Water temperature entering/leaving evaporator.
5. Pressure drop through evaporator.
6. Condenser water flow through.
7. Pressure drop through condenser.
8. Water temperature entering/leaving condenser.
9. Motor data, amps, volts, rpm, starter type, overload protection type, phase, hertz, nameplate, and actual measured kW input.
10. Type of refrigerant.
11. Notes.
M. The following cooling tower data is required:
1. Identification number.
2. Nameplate data; manufacturer, model and serial number.
3. Performance test results for rated capacity.
4. Water flow through the tower in GPM.
5. Water temperature entering/leaving tower.
6. Outside Air dry and wet bulb temperatures.
7. Motor data, amps, volts, phase, hertz, and kW input.
8. Starter size and type and heater size and capacity.
9. Water droplets leaving tower - yes/no.
10. Water balanced across tower pans and basins.
11. Airflow across the tower within design rating according to fan curves.
12. Notes.
N. The following boiler and domestic water heater data is required:
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-10
1. Performance test results for rated capacity.
2. Boiler identification number.
3. Nameplate data; manufacturer, model, and serial number.
4. Water temperature entering/leaving the boiler.
5. Outside conditions: temperature, humidity, general cloud cover.
6. Barometric pressure.
O. The following air-cooled split system condensing unit data is required:
1. Performance test results for rated capacity.
2. Unit identification number.
3. Nameplate data, manufacturer, model, and serial number.
4. Compressor nameplate and actual amps, volts, phase, and hertz.
5. RPM of motors, where applicable.
6. Refrigerant type.
7. Suction/Discharge pressure when gage installed.
8. Number of stages.
9. Low-pressure/High-pressure control setting.
10. Condenser fan sequence stages.
11. Crankcase heater watts (nameplate).
12. Hot gas bypass installed - yes/no.
13. SCFM Air Flow Measurement vs. Design CFM.
P. The following air-cooled split system heat pump data is required:
1. Performance test results for rated heating and cooling capacities.
2. Unit identification number.
3. Nameplate data, manufacturer, model, and serial number.
4. Compressor nameplate and actual amps, volts, phase, and hertz.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-11
5. RPM of motors, where applicable.
6. Refrigerant type.
7. Suction/Discharge pressure for both heating and cooling modes when gage installed.
8. Number of stages.
9. Low-pressure/High-pressure control setting.
10. Condenser fan sequence stages.
11. Crankcase heater watts (nameplate).
12. Hot gas bypass installed - yes/no.
13. SCFM Air Flow Measurement vs. Design CFM.
Q. The following sound test data is required:
1. Area or location.
2. Sound level in dB(A) as specified in Article 3.19.
3. Sound level at the center band frequencies of eight non-weighted octaves with equipment on and off for 5 rooms selected by the OAR/PROJECT INSPECTOR.
4. Plot of corrected sound-level reading on Noise Criteria (NC) curve for the measurements in Q 3 above.
R. The following vibration test data is required:
1. Equipment identification number.
2. Vibration levels at all accessible bearings, motors, fans, pumps, casings, and isolators.
3. Measurements in mils deflection and velocity in inches per second.
4. Each measurement taken in horizontal, vertical, and axial planes as accessible.
S. The following mixing damper leakage test data is required:
1. Equipment identification number (unit, box, zone, etc.).
2. Dry bulb temperature in the cold/hot (or bypass) deck.
3. Dry bulb temperature in the mixed air stream.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-12
4. Calculated percent leakage.
5. Data above taken in the full cool and full heat (or bypass) mode.
6. Notes.
T. The following airflow station data is required:
1. Station identification number.
2. Nameplate data including effective area.
3. Differential test pressure or velocity.
4. Calculated CFM.
5. Actual CFM (from Pitot-tube traverse form).
6. Read out CFM.
7. Notes
U. The following unit heater data is required:
1. Equipment identification number.
2. Nameplate data; manufacturer, model, and serial number.
3. Test CFM (use manufacturer rated CFM if not ducted).
4. Heat test data per applicable procedure (hot water, electric, etc.).
5. Notes.
V. The following fan coil and unit ventilator data is required:
1. Equipment identification number.
2. Nameplate data; manufacturer, model, and serial number.
3. Tested supply CFM or manufacturer rated CFM if not ducted.
4. Tested outside air in CFM.
5. Motor data and actual amps and volts.
6. Cooling/Heating test data.
7. Static pressure.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-13
8. Notes.
W. The following kitchen hood data is required:
1. Hood identification number.
2. Nameplate data; manufacturer, model, and serial number.
3. Pitot-tube traverse total air flow.
4. Exhaust and supply (when part of hood) CFM.
5. Exhaust and supply (when part of hood) test velocities shown on hood face diagram.
6. Face velocities.
7. Hood opening dimensions.
8. Notes (turbulence and flow patterns at the face and inside the hood).
X. The following laboratory hood data is required:
1. Hood identification number.
2. Nameplate data; manufacturer, model, and serial number.
3. Pitot-tube traverse total air flow.
4. Exhaust and supply (when part of hood) CFM.
5. Exhaust and supply (when part of hood) test velocities shown on hood face diagram.
6. Face velocities.
7. Hood opening dimensions.
8. Notes (turbulence and flow patterns at the face and inside the hood).
Y The following data for water-to-water heat exchangers for domestic and/or heating is required:
1. Exchanger identification number.
2. Nameplate data; manufacturer, model, and serial number.
3. GPM and Pressure drop through each side.
4. Capacity of each side.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-14
5. Notes.
Z. The following pump data, including but not limited to, chilled water, heating hot water, cooling tower water, boiler feed, domestic hot water booster, domestic hot water circulation, sewage ejectors, sump pumps and domestic hot water booster is required:
1. Pump number.
2. Nameplate data; manufacturer, model, and serial number.
3. Motor data including nameplate data, actual amps, volts, RPM, horsepower, starter heater size, and capacity.
4. Pump discharge and suction pressure along with total dynamic head in the following modes.
5. Shut-off head FT, Wide open Head FT, and Final operating Head FT.
6. Final GPM Test plotted on a pump curve.
7. Notes.
AA. The following water flow station data is required:
1. Station identification number.
2. Nameplate data; manufacturer, model, and serial number.
3. Design and actual GPM.
4. Differential test pressure.
5. Setting (open turns, degree, etc.) if required GPM.
6. Notes.
BB. The following terminal box data is required:
1. Box identification number.
2. Node, address, or designation on system.
3. Box size.
4. Cooling CFM.
5. Minimum CFM (if applicable).
6. Heating CFM (if applicable).
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-15
7. Box fan amps and volts (if applicable).
8. For DDC controlled boxes, record computer readout maximum, minimum, and heat, along with box correction factor for calibrating to true CFM.
9. Notes.
3.07 PROCEDURES
A. Schedule the Work of this Section in order for test and balance activities to be completed prior to the date of Substantial Completion. CONTRACTOR shall place all heating, ventilating, and air conditioning equipment into operation during each day and until all HVAC adjusting, balancing, testing, demonstrations, and instructions on systems are completed. Agency shall prepare and submit reports within ten (10) days from completion of the Work of this Section to allow sufficient time for corrective measures to be completed before Substantial Completion of the Work. When an individual building or portion thereof is ready for occupancy, all equipment relative to such portion of Work shall be put into service, tested, and balanced.
B. Prior to the date of Substantial Completion, and upon completion of test and balance Work, place all exhaust fans in operation, force all air handling units, and air conditioning units into a 100 percent outdoor air economizer mode with heating and cooling locked out and flush the building continuously for a period of fourteen (14) days.
C. Coordinate test and balance procedures with any phased Project requirements so test and balance procedures on each phased portion of the Work will be completed prior to completion of said designated phase.
3.08 FIELD EXAMINATION
A. Before the commencement of test and balance Work, CONTRACTOR shall ascertain that following conditions are fulfilled:
1. Ensure that all water heating and water cooling systems have been flushed, cleaned, and filled and high points vented.
2. Boilers(steam and hot water) are filled.
3. Refrigerant systems are fully charged with specified refrigerant.
4. Over-voltage and current protection have been provided for motors.
5. Equipment has been labeled asrequired.
6. Curves and descriptive data on each piece of equipment to be tested and adjusted are available as required.
7. Operations and maintenance manuals have been supplied.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-16
8. Controls manufacturer and boiler-burner representatives shall be available for consultation and supervision of adjustments during tests.
9. Verify that heating and cooling coil fins are cleaned, combed and air filters clean, and installed.
10. Verify that duct systems are clean of debris and leakage is minimized, access doors are closed and duct end caps are in place, and fire and volume dampers are in place and open.
11. Automatic control systems are completed and operating.
12. Start up and initial commissioning of all HVAC equipment except fans shall be by the manufacturer.
B. In addition to the above, CONTRACTOR shall establish a specific, coordinated plan which details how each area of existing building will be balanced during the various phases of the Work. The evaluation shall address, at a minimum, the following concerns:
1. OWNER operations.
2. Building safety and security policies. Prior to any fire safety or security systems shutdown at any time during the Work, CONTRACTOR shall first advise and coordinate with OWNER to ensure all concerned parties are notified.
3. Protecting furniture, computers, photocopiers, and other office equipment.
4. Protecting classroom fixtures and equipment.
5. Concerns specific and unique to building related issues.
6. Downtime required for each Air Handling Unit including projected time to return each portion of the building back to its normal occupancy temperature and humidity.
7. Shutdown and reactivation of the fire alarm system to avoid accidental alarms during test and balance and related Work.
3.09 TEST AND BALANCE
A. For each heating, ventilating, or air conditioning system the following shall be performed, recorded, and submitted in an approved format for review. Make, type, and model of unit, and location of each piece of equipment shall be included in the report.
Readings shall include but not be limited to following:
1. Air Systems:
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-17
a. General
1) Verify all ductwork, dampers, grilles, registers, and diffusers have been installed per design and set in the full open position.
Agency shall perform the following TAB procedures in
accordance with AABC or NEBB National Standards. Where the requirements of the two standards are different, the more stringent requirements shall prevail. Also, if the Contract Documents impose a more stringent standard then the Contract Documents shall prevail.
b. Zone, Branch, and Main Ducts:
1) Adjust ducts to within design CFM requirements by means of Pitot-tube duct traverse.
c. Supply Fans:
1) Fan Speeds: Test and adjust fan RPM to achieve maximum or design CFM. CONTRACTOR shall provide new belt pulleys
when required.
2) Current and Voltage: Test and record motor voltage and amperage, and compare data with the nameplate limits. Ensure fan motor is not in or above the service factor as published by the motor manufacturer.
3) Pitot-Tube Traverse: Perform a Pitot-tube traverse of main supply and return ducts, record total CFM.
4) Outside Air: Test and adjust the outside air using Pitot-tube traverse.
5) Static Pressure: Test and record system static profile of each supply fan.
6) Current and Voltage: Test and record motor voltage and amperage, and compare data with the nameplate limits. Ensure fan motor is not in or above the service factor as published by the motor manufacturer.
d. Return, Relief, and Exhaust Fans:
1) Fan Speeds: Test and adjust fan RPM to achieve maximum or design CFM. CONTRACTOR shall provide new belt pulleys
where required.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-18
2) Pitot-Tube Traverse: Perform a Pitot-tube traverse of the main return ducts to obtain total CFM.
3. Static Pressure: Test and record system static profile of each fan.
e. VAV Systems:
1) Set volume regulators on all terminal boxes to meet design maximum and minimum CFM requirements.
2) Identification: Identify the type, location, and size of each terminal box. This information shall be recorded on terminal box data sheets.
f. Diffusers, Registers and Grilles:
1) Tolerances: Test and balance each diffuser, grille, and register to within 5 percent of design requirements.
2) Identification: Identify the type, location, and size of each grille, diffuser, and register. This information shall be recorded on air outlet data sheets.
g. Coils: Air Temperature: Once airflow is set to acceptable limits, agency shall take wet bulb and dry bulb air temperatures on the entering and leaving side of each cooling coil. Dry-bulb temperature shall be taken on the entering and leaving side of each heating coil.
h. Duct Leakage Testing:
1) On existing ductwork, agency shall calculate duct leakage by traversing the unit and reading associated diffusers.
2) On new installations each and every section of the entire air distribution system (all supply, return, exhaust, and relief ductwork) shall be tested at 1.5 times design static pressure. All ducts shall demonstrate 5 percent leakage maximum (per CBC). i. Air Handling Units:
1) Prepare pressure profile and show design and actual CFM (outside air, return air, and supply air).
2) Measure and record each mode (minimum OA and 100 percent OA) where economizer cycle is specified.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-19
3) Record pressure drops of all components (coils, filters, sound attenuators, louvers, dampers, and fans) and compare with design values.
4) Pressure profile and component pressure drops are performance indicators and are not to be used for flow measurements. j. System Pressure Profiles:
1) Prepare pressure profiles from fan (supply, return, and exhaust) or air handling unit to extremities of system.
2) As a minimum, show pressure at each floor, main branch, and airflow measuring device.
3) Make pitot-tube traverses of all trunk lines and major branch lines where required for analysis of distribution system. Airflow measuring devices installed in ductwork, if available, may be utilized.
4) Record residual pressures at inlets of volume controlled terminals at ends of system.
5) Show actual pressures at all static pressure control points utilized for constant or variable flow systems.
k. Fan speed adjustments and balancing for optimum acoustical performance:
1) As the very first step, the speed of all fans (supply, return, and exhaust inside packaged equipment or air handling units) shall be adjusted to deliver the required fan total air quantity with all volume dampers and other flow rate control devices fully open.
Adjustments shall be made with the outdoor air intake dampers, return air dampers, and relief air dampers in the minimum outdoor air position. The adjustments shall be made again in the 100 percent outdoor air position in systems with 100 percent outdoor air economizers.
2) The above adjustment shall be done with wet cooling coils, where cooling coils are provided.
3) The airflow rates at each branch duct shall be adjusted as the second step with air with all volume dampers and other flow rate control devices fully open.
4) The airflow rates at each air inlet and outlet shall be adjusted as the final step. The volume damper in the branch duct shall be
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-20
used for balancing. Opposed blade dampers at air inlets and outlets where provided shall only be used for fine adjustments and shall not be closed beyond 60 percent open or when the dampers start to generate audible noise.
5) CONTRACTOR shall provide the labor and materials for all dampers, pulleys, and belt changes required for balancing. The design documents indicate the worst-case scenario with safety factors in fan static pressures for contingency. Properly coordinated and installed air systems may require a lower static pressure and a reduction in fan speed.
2. Water Systems: CONTRACTOR shall confirm all equipment, piping, and coils have been filled and purged, strainers are clean, and all balancing valves (except bypass valves) are set full open. Agency shall perform the following TAB procedures in accordance with the AABC, TABB, or NEBB National Standards:
B. Pumps:
1. Test and adjust chilled water, hot water, and condenser water pumps to achieve maximum or design GPM.
2. Measure and record suction and discharge pressures.
3. Check pumps for proper operation. Pumps shall be free of vibration and cavitation.
4. Current and Voltage: Agency shall test and record motor voltage and amperage and compare data with the nameplate limits. Ensure pump motor is not in or above the service factor as published by the motor manufacturer.
5. Adjust pump flow by adjusting and setting balancing valves to obtain amperage reading on a clamp-on ammeter that corresponds to amperage indicated on pump's curves for required flow.
6. Verify that the motor is not drawing more current than indicated on motor plate rating. When actual flows of primary pumps are found by test to vary more than 5 percent from specified amount, system shall be re-balanced to regulate flow within this tolerance. When a flow indicating device(s) is in circuit, it shall be used to verify pump flows.
7. When testing is completed, a pump capacity chart with pump number and location indicated shall be marked indicating operating point of pump on the curve. Chart shall then be included in the report.
C. Cooling Towers:
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-21
1. Test and balance water flows, balance tower cells, and flows between towers.
2. Test and record temperature profiles for water and airside operation.
3. Outside Climatic Conditions: Outside air dry bulb (DB) temperature, wet bulb (WB) temperature, and atmospheric conditions, during temperature profile runs.
D. Chillers: (Start-up and initial commissioning by manufacturer only.)
1. Test and balance chiller water flowsto achieve maximum or design GPM.
2. Current and Voltage: Test and record motor voltage and amperage, and compare data with the nameplate limits. Ensure compressor motor is not in or above the service factor as published by the motor manufacturer.
3. Test and record temperature and pressure profiles of chillers. a. Inlet and outlet water temperature.
b. Inlet and outlet water pressure.
c. Evaporator temperature.
d. Condensing temperature pressure.
e. Purge pressure.
f. Oil temperature and pressure.
4. Outside Climatic Conditions: Outside air DB temperature, WB temperature, and atmospheric conditions, during temperature profile runs.
E. Boilers: (Start-up and initial commissioning by manufacturer only.) Test and balance boilers only after test and balance of pumps have been completed. Boilers shall not be initially operated or tests performed with students or faculty on the Project site. Boilers shall be tested for the following:
1. Heating Hot Water Boilers and Domestic Hot Water Boilers:
a. Current and Voltage: Test and record motor voltage and amperage, and compare data with the nameplate limits. Ensure motor is not in or above the service factor.
b. Test and balance water flow through water boilers.
c. Test and record temperature and pressure profiles of water and/or steam boilers.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-22
d. Upon completion of tests, controls and devices shall be returned to their normal operating condition and boiler shall remain in service.
2. Steam Boilers: Start-up and initial commissioning by manufacturer only.
F. Heat Exchangers:
1. Steam to Hot Water Heat Exchanger: Steam pressure, entering and leaving hot water temperatures, gpm flow, pressure drop, and control set point.
2. Water to Water Heat Exchanger:
a. Primary Heating Water: Entering and leaving hot water temperatures, gpm flow, and pressure drop.
b. Secondary Heated Water: Entering and leaving hot water temperatures, gpm flow, pressure drop, and control set point.
G. Coils:
1. Tolerances: Test and balance all chilled-water and hot-water coils within 5 percent of design requirements.
2. Verify the type, location, final pressure drop, and GPM of each coil.
H. System Mains and Branches including chilled water, heating hot water, cooling tower water, domestic hot water and domestic cold water:
1. Balance water flow in pipesto achieve maximum or design GPM.
I. Steam Heating Systems:
1. Heating Coils: Steam pressure at coils, cfm, coil pressure drop, entering and leaving air dry bulb temperatures.
2. Boilers:
a. Steam pressure, temperature, and quantity of feed-water (see Testing and Adjusting procedures).
b. Make, type,serial number, and rated capacity.
c. Flue gas temperature at boiler outlet ahead of back-draft diverter. d. Percent carbon dioxide in flue gas.
e. Condensate quantities and temperatures.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-23
3. Air Conditioning Units: (Start-up and initial commissioning by manufacturer only.)
a. Suction pressure and temperature.
b. Discharge pressure and temperature.
c. Amps and volts.
d. Make, type, and model of unit, capacity rating.
e. Ambient temperature: WB, DB.
f. Supply, return, relief, and exhaust fans shall be balanced as indicated in Section 3.09, A, 1, Air Systems.
g. Proper operation of controls: Temperature controllers and safety devices shall be tested during operating tests, with all other controls and devices, except one under test, being by-passed.
h. Upon completion of tests, controls and devices shall be returned to their normal operating condition and boiler shall remain in service.
4. Condensing and Refrigerating Units: (Start-up and initial commissioning by manufacturer only.)
a. Suction pressure and temperature.
b. Discharge pressure and temperature.
c. Amps and volts.
d. Make, type, and model of unit, capacity rating.
e. Ambient temperature: WB, DB.
f. Proper operation of controls: Temperature controllers and safety devices shall be tested during operating tests, with all other controls and devices, except one under test, being by-passed.
g. Upon completion of tests, controls and devices shall be returned to their normal operating condition and boiler shall remain in service.
5. Split System Heat Pump Units: (Start-up and initial commissioning by manufacturer only.)
a. Suction pressure and temperature.
b. Discharge pressure and temperature.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-24
c. Amps and volts.
d. Make, type, and model of unit, capacity rating.
e. Ambient temperature: WB, DB.
f. Supply, return, relief and exhaust fans shall be balanced as indicated in Sub-paragraph 3.09.A.1, Air Systems.
g. Proper operation of controls: Temperature controllers and safety devices shall be tested during operating tests, with all other controls and devices, (except one under test) being by-passed.
h. Upon completion of tests, controls and devices shall be returned to their normal operating condition and boiler shall remain in service.
6. MISCELLANEOUS:
a. Electric Heaters:
1. Amperage.
2. Voltage.
3. Make, type, model, and name plate capacity rating.
3.10 VERIFICATION OF HVAC CONTROLS
A. Agency shall verify in conjunction with CONTRACTOR all control components are installed in accordance with the intent of the Contract Documents and are functioning according to the design intent, including all electrical interlocks, damper sequences, air and water resets, fire stats, and other safety devices.
B. CONTRACTOR shall verify all control components are calibrated and set for design operating conditions and intent.
3.11 TEMPERATURE TESTING
A. To verify system control and operation, agency shall perform a series of three temperature tests taken at approximately two hour intervals in each separately controlled zone. The resulting temperatures shall not vary more than two degrees Fahrenheit from the thermostat or control set point during the tests. Outside temperature and humidity shall also be recorded during the testing periods.
3.12 KITCHEN HOOD TESTING
A. Agency shall test and adjust hood total airflow by duct Pitot-tube traverse. If a Pitottube traverse is not practical, an explanation of why a traverse was not made must be made in writing to Architect and subsequently appear on the appropriate data sheet.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-25
Face velocities shall be tested under design operating conditions using a maximum of a one square foot grid pattern across the entire open face. CONTRACTOR shall set sash height on hoods to obtain face velocities within 20 percent of 100 feet per minute unless specified otherwise. Agency shall test and adjust exhaust airflows and make-up air flows to maintain design hood pressures and face velocities and design room pressurization.
Agency shall test for turbulence and proper air flow patterns at the face and inside the hoods using a hand-held smoke puffer or other approved smoke- emitting device.
3.13 FUME HOOD TESTING
A. Agency shall test and adjust fume hood total airflow by duct Pitot-tube traverse. If a Pitot-tube traverse is not practical, an explanation of why a traverse was not made must be made in writing to Architect and subsequently appear on the appropriate data sheet.
Face velocities shall be tested under design operating conditions using a maximum of a one square foot grid pattern across the entire open face. CONTRACTOR shall set sash height on hoods to obtain face velocities within 20 percent of 100 feet per minute unless specified otherwise. Agency shall test and adjust VAV controllers to obtain design exhaust airflows and make-up air flows to maintain design hood pressures and face velocities and design room pressurization. Agency shall test for turbulence and proper air flow patterns at the face and inside the hoods using a hand-held smoke puffer or other approved smoke-emitting device.
3.14 BUILDING/ZONE PRESSURIZATION
A. Agency shall test and adjust building/zone pressurization by setting the design flows to meet the required flow direction and pressure differentials. Positive/Negative area(s) supply air shall be set to design flow and exhaust air rates adjusted to obtain the required pressure differential(s).
3.15 FIRE AND SMOKE DAMPER TESTING
A. This work is to be performed by OWNER and State Fire Marshall. Do not include in agency scope of work.
3.16 LIFE SAFETY CONTROLS TESTING
A. This work is to be performed by OWNER and State Fire Marshall. Do not include in agency scope of Work.
3.17 FINAL TABULATION
A. After heating, ventilating, and air conditioning components are satisfactorily tested and balanced, entire system shall be put into operation and all pressures, temperatures, gpm, cfm, velocities, etc., shall be recorded and checked against design schedules. Design requirements shall be listed on reports and final tabulation shall be within a tolerance of plus or minus five percent of design requirements.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-26
B. Readings at various locations as described herein will be made every hour for four (4) hours, during normal working hours for three (3) days. Boilers, forced air furnaces, and chillers shall be started up far enough in advance to meet design conditions during period of testing.
3.18 VIBRATION TESTING
A. Furnish instruments and perform vibration measurements if specified in Division 23.
Provide measurements for all rotating HVAC equipment half horsepower and larger, including reciprocating/centrifugal/screw/scroll compressors, pumps, fans, and motors.
B. Record initial and final measurements for each unit of equipment on test forms. Where vibration readings exceed allowable tolerance and efforts to make corrections have proved unsuccessful, forward a separate report to ARCHITECT.
3.19 SOUND TESTING
A. Perform and record sound measurements as specified in this Section and in Section 23 0548: HVAC Sound, Vibration and Seismic Control. Take additional readings if required by ARCHITECT.
B. Measuring equipment and methods shall comply with the current requirements of the AABC, NEBB, TABB and ANSI S12.60. Take measurements with a calibrated Type 1 sound level meter and octave band analyzer.
C. Sound reference levels, formulae, and coefficients shall be according to ASHRAE Handbook: HVAC Applications, Chapter on Sound and Vibration Control.
D. Where sound pressure levels are specified as noise criteria or room criteria in Section 23 0548: HVAC Sound, Vibration and Seismic Control determine compliance with the Contract Documents as follows:
1. Reduce background noise as much as possible by shutting off unrelated audible equipment.
2. Measure octave band sound pressure levels with specified equipment "off".
3. Measure octave band sound pressure levels with specified equipment "on".
4. Use difference in corresponding readings to determine sound pressure due to equipment. Sound pressure level, due to equipment equals sound pressure level with equipment "on" minus factor.
DIFF.: 0 1 2 3 4 5 9-10 or More
FACTOR: 10 7 4 3 2 1 0
5. Plot octave bands of sound pressure level due to equipment for typical rooms, on a graph, which also shows, noise criteria (NC) curves.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING, ADJUSTING, AND BALANCING FOR HVAC
01 4525-27
E. Where sound levels are required in dbA, measure sound levels using the A-frequencyweighting of meter. Single value readings will be used instead of octave band analysis.
F. Measure sound levels at each octave band as NC or RC (room criteria) if indicated in the Drawings or other Spec Sections. Where measured sound levels exceed specified level, CONTRACTOR shall take all remedial action and necessary sound tests shall be repeated. Sound tests after remedial action shall be in octave band in NC or RC for the room and also at each diffuser, grille, or register in occupied areas. Sound levels shall be measured approximately five feet above floor on a line approximately 45 degrees to center of opening, on the A- and C-frequency-weighting of the measuring instrument.
G. Measure and record sound levelsin decibels for each room per current ANSI S12.60.
H. Report shall include ambient sound levels, taken without air-handling equipment operating, of rooms in which above openings are located. A report shall also be made of any noise caused by mechanical vibration.
END OF SECTION
City of Hermosa Beach
CIP 689- Clark Building Renovations
WATER POLLUTION CONTROL
01 7418-1
SECTION 01 7418
WATER POLLUTION CONTROL
FOR PROJECTS WITH LAND DISTURBANCE OF LESS THAN ONE ACRE PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
1. Control runoff and pollutants from the site during construction activities.
2. Preparation, implementation, and maintenance of construction BMPs.
B. Related Requirements:
1. Division 01 – General Requirements.
1.02 ACRONYMS AND DEFINITIONS
BMP Best Management Practice.
CAN Corrective Action Notice.
CASQA California Stormwater Quality Association.
CGP NPDES General Permit for Storm Water Discharges Associated with Construction Activities.
DWQ Division of Water Quality.
LARWQCB Los Angeles Regional Water Quality Control Board.
NPDES National Pollutant Discharge Elimination System.
OEHS LAUSD Office of Environmental Health and Safety.
SWPPP Storm Water Pollution Prevention.
SWRCB State Water Resources Control Board.
WPCD Water Pollution Control Drawing.
1.03 REQUIREMENTS
A. CONTRACTOR shall:
1. Implement, install and maintain BMPs. Ensure that BMPs are designed to protect all exposed portions of the site, including:
a. Erosion, Sediment, Tracking, and Wind Erosion Control BMPs. b. Preservation of natural features, vegetation, soil, and buffers around surface waters.
City of Hermosa Beach
CIP 689- Clark Building Renovations
WATER POLLUTION CONTROL
01 7418-2
c. Drainage swales or lined ditches to control stormwater flow. d. Mulching or hydroseeding to stabilize disturbed soils. e. Erosion control to protect slopes.
f. Protection of storm drain inlets (gravel bags or catch basin inserts). g. Perimeter sediment control (perimeter silt fence, fiber rolls). h. Sediment trap or sediment basin to retain sediment on site. i. Stabilized construction exits.
2. Implement Good Site Management "Housekeeping" BMPs to manage construction equipment, materials, non-stormwater discharges, and wastes.
BMPs that should be considered for implementation as appropriate for each project include, but are not limited to, the following:
a. Dewatering activities.
b. Material handling and waste management.
c. Building materials stockpile management.
d. Management of washout areas (concrete, paints, stucco, etc.). e. Control of vehicle/equipment fueling to staging area. f. Vehicle and equipment cleaning performed off site.
g. Spill prevention and control.
3. Incorporate BMP activities into the Project Schedule. Schedule construction activity during dry weather, when possible.
4. Inform CONTRACTOR and Subcontractors personnel on the BMP procedures to prevent pollutants from entering the storm drain system, before the start of construction activities. Keep personnel informed of the BMP implementation process and of changes to the procedures. Provide record to OAR of stormwater topics discussed.
5. Conduct site inspections, at least weekly, of pollution prevention controls and repair or provide additional BMPs as required.
6. Pay fines and penalties from regulatory agencies against OWNER due to CONTRACTOR’S non-compliance with stormwater regulations. OWNER shall recover costs of fines and penalties by appropriate OWNER assessment. Review of the BMPs by OAR shall not relieve CONTRACTOR from liabilities arising from non-compliance of storm water pollution regulations.
B. Project Inspector and OEHS Inspector will conduct inspection and examination of site storm water regulation compliance.
C. At substantial completion, conduct post-construction BMP training of OWNER personnel and submit any post-construction BMP maintenance information.
City of Hermosa Beach
CIP 689- Clark Building Renovations
WATER POLLUTION CONTROL
01 7418-3
1.04 SUBMITTALS
A. BMP material quality, grade, type as specified in the CASCA BMP Handbook.
B. Water Pollution Control Drawing (WPCD).
C. BMP Implementation Schedule.
1.05 QUALITY ASSURANCE
A. Comply with the following regulatory requirements:
1. National Pollutant Discharge Elimination System (NPDES) General Permit for Storm Water Discharges Associated with Construction and Lands Disturbance Activities; ORDER NO. 2009-0009-DWQ; NPDES NO.
CAS000002, adopted by the State Water Resources Control Board.
2. Regulations of the California Environmental Protection Agency, State Water Resources Control Board; Los Angeles Regional Water Control Board, and local ordinances.
3. CASQA Stormwater Best Management Practice Handbook for Construction Activity (BMP Handbook) current adopted edition.
4. Local jurisdiction stormwater management (SWPPP) and erosion control ordinances.
1.06 STORAGE AND PROTECTION
A. Provide proper storage of materials and equipment to prevent rain and storm water runoff to come in contact with pollutants, such as soil stabilizers, paint or fluids from vehicles.
PART 2 – PRODUCTS
2.01 MATERIALS
A. Provide quality, grade and type of materials as specified in CASQA Stormwater Best Management Practice, Handbook.
PART 3 – EXECUTION
3.01 IMPLEMENTATION
A. Install perimeter controls prior to starting Work at the Project site.
B. Contain on-site stormwater on the Projectsite. Provide storm drain inlet protection.
Do not drain on-site water directly into the storm drain without proper BMP in place.
C. Prevent pollutant discharges into the storm drain system. Prevent stormwater from coming into contact with pollutants, such as sediment, material spills, or leakage from
City of Hermosa Beach
CIP 689- Clark Building Renovations
WATER POLLUTION CONTROL
01 7418-4
storage tanks, waste containers or transfer areas. In the event contamination is found CONTRACTOR shall immediately notify OAR who will contact the OEHS.
D. Protect exposed dirt,such asstockpiles, landscaping areas, and hillsides.
E. Properly manage non-stormwater dischargessuch as ground water, broken utility lines and fire hydrant testing.
F. Adjust BMP’s locations and layouts in accordance to construction progress to assure compliance to regulations.
G. Conduct inspections of pollution prevention controls and provide Site Monitoring Report to OAR immediately if pollutants are discharged into the site runoff.
CONTRACTOR shall remediate contaminated water.
H. Upon Substantial Completion: Maintain and leave post-construction stormwater pollution prevention controls in place and remove those that are not needed as determined by the OAR.
3.02 CLOSEOUT
A. Verify the following prior to Substantial Completion:
1. Final stabilization of site has been demonstrated.
2. There is no potential for construction related stormwater pollutants to be discharged into site runoff.
3. Construction related equipment and temporary BMP have been removed from site.
4. Rubbish, debris, and waste materials have been removed and legally disposed of off the Project site.
5. OEHS CAN items have been closed and signed-off.
6. Post-Construction BMP Maintenance Plan has been established.
END OF SECTION
City of Hermosa Beach
CIP 689- Clark Building Renovations CONTRACT CLOSEOUT
01 7700-1
SECTION 01 7700
CONTRACT CLOSEOUT
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. This Section includes administrative and procedural requirements for Contract Closeout, including but not limited to, the following:
1. Inspection procedures.
2. Project record documents submittal.
3. Operation and maintenance manual submittal.
4. OWNER orientation and instruction.
5. Final cleaning.
1.02 RELATED REQUIREMENTS:
1. Section 01 2976 - Progress Payment Procedures.
2. Section 01 3213 - Construction Schedule.
3. Section 01 3229 - Project Forms.
4. Section 01 3300 - Submittal Procedures.
5. Section 01 4525- Testing, Adjusting, and Balancing of HVAC.
6. Section 01 5000 - Construction Facilities and Temporary Controls.
7. Section 01 7836 - Warranties.
PART 2 – PRODUCTS (Not used)
PART 3 - EXECUTION
3.01 SUBSTANTIAL COMPLETION
City of Hermosa Beach
CIP 689- Clark Building Renovations CONTRACT CLOSEOUT
01 7700-2
A. Inspection Procedures: On receipt of the Request For Certificate of Substantial Completion, OAR will authorize commencement of inspection. INSPECTOR, OAR, CONTRACTOR and ARCHITECT will inspect the Work.
1. If after inspection of the Work, OAR does not consider the Work substantially complete, OAR will notify CONTRACTOR.
2. If after inspection, OAR considers the Work substantially complete, INSPECTOR shall prepare a comprehensive Punch List of items to be corrected.
a. INSPECTOR may repeat inspection to assure the Work is corrected.
b. Results of the completed inspection will form a partial basis of the requirements for Release of Retention.
3.02 ADMINISTRATIVE CLOSEOUT
A. Re-inspection Procedures: INSPECTOR, OAR, CONTRACTOR and ARCHITECT may inspect the Work upon notice, including final inspection of Punch List items from earlier inspections, has been corrected, except for items whose completion is delayed under circumstances acceptable to OAR.
1. OWNER has the right to preclude CONTRACTOR from Punch List correction and documents submittals after the Contract Completion date; unless OWNER elects to authorize CONTRACTOR to extend
Administrative Contract duration. CONTRACTOR will be assessed actual cost for the unsettled items. Withholds amounts exceeding actual costs to correct or to obtain deliverable will be released.
2. If allowed by the OAR, re-inspection will be repeated, but may be assessed against CONTRACTOR if OWNER is subject to additional professional service and or additional costs of inspection.
3.03 PROJECT RECORD DOCUMENT SUBMITTAL
A. General: Do not use project record documents for construction purposes. Protect record documents from deterioration and loss. Provide access to record documents for ARCHITECT, INSPECTOR and OAR reference during normal working hours.
Project record document shall be updated on a weekly basis. Prior to submitting each application for payment, secure INSPECTOR and ARCHITECT approval of project record documents.
B. Record Drawings: Maintain a clean, undamaged set of prints of Drawings and Shop Drawings. Mark the set to show the actual installation where the installation varies substantially from the Work as originally shown. Mark the Drawing that is
City of Hermosa Beach
CIP 689- Clark Building Renovations CONTRACT CLOSEOUT
01 7700-3
most capable of showing conditions fully and accurately. Where Shop Drawings are used, record a cross-reference at the corresponding location on the Drawings.
Provide detailed and accurate field dimensions for concealed elements that would be difficult to measure and record at a later date.
1. Mark record sets with red erasable pencil. Use other colors to distinguish between variations in separate categories of the Work. Date and number entries in the same format as submitted. Call attention to entry by a “cloud” around the affected areas.
2. Mark new information important to OWNER but was not shown on Drawings or Shop Drawings.
3. Utility location and depth below finished grade and above ceilings and attic spaces shall be fully dimensioned and indicated on record drawings.
Dimensions shall be measured from building lines or permanent landmarks and shall be triangulated to those features.
4. Note related Change Order or Construction Directive numbers where applicable. RFC submissions shall be referenced on each affected sheet, Drawing and Shop Drawing.
5. Organize record drawing sheets into manageable sets. Bind sets with durable-paper cover sheets; print suitable titles, dates, and other identification on the cover of each set.
6. Prior to Contract Completion of the Work, review of the project record drawings by ARCHITECT; prepare a final set of project record drawings using reproducible vellum. Submit final set of transparencies to ARCHITECT.
C. Record Specifications: Maintain two complete copies of the Specifications, including Addenda. Include with the Specifications two copies of other written Contract Documents, such as Change Orders or Construction Directives issued during construction.
1. Mark these record documents to show substantial variations in actual Work performed in comparison with the text of the Specifications and modifications.
2. Give particular attention to substitutions and selection of options and information on concealed Work that cannot otherwise be readily discerned later by direct observation.
3. Note related record document information with Product Data.
City of Hermosa Beach
CIP 689- Clark Building Renovations CONTRACT CLOSEOUT
01 7700-4
4. Prior to Contract Completion of the Work, submit record Specifications to ARCHITECT for OWNER records.
D. Record Product Data: Maintain two copies of each Product Data submittal. Note related Change Orders and Construction Directives and mark-up of record drawings and Specifications.
1. Mark these documents to illustrate significant variations in actual Work performed in comparison with information submitted. Include variations in products delivered to the Project site and from the manufacturer’s installation instructions and recommendations.
2. Provide detailed and accurate information regarding concealed products and portions of Work that cannot otherwise be readily discerned later by direct observation.
3. Prior to Contract Completion, submit complete set of record Product Data to ARCHITECT for OWNER records.
E. Record Samples: Immediately prior to Substantial Completion, CONTRACTOR shall meet with ARCHITECT and OAR at the Project site to determine which Samples are to be transmitted to OWNER for record purposes. Comply with OAR instructions regarding delivery to OWNER storage area.
F. Miscellaneous Records: Refer to other Specification sections for requirements of miscellaneous record keeping and submittals in connection with actual performance of the Work. Prior to the date of Contract Completion, complete and compile miscellaneous records and place in good order. Identify miscellaneous records properly and bind or file, ready for continued use and reference. Submit to Architect for OWNER records.
G. Maintenance Manuals: Prior to Substantial Completion, organize operation and maintenance data into suitable two sets of manageable size. Bind properly indexed data in individual, heavy-duty, two to three-inch 3-ring, vinyl-covered binders, with pocket folders for folded sheet information. Mark appropriate identification on front and spine of each binder. Submit to ARCHITECT for OWNER records.
Include the following types of information.
1. Emergency instructions.
2. Spare parts list.
3. Copies of warranties.
4. Wiring diagrams.
5. Recommended “turn-around” cycles.
City of Hermosa Beach
CIP 689- Clark Building Renovations CONTRACT CLOSEOUT
01 7700-5
6. Inspection procedures.
7. Shop Drawings and Product Data.
8. Fixture lamping schedule.
H. Verified Reports: Construction progress of the Work shall be reported to DSA via a duly verified report as per Title 24, Part 1, Sections 4-336 and 4-343.c of the California Building Standards Commission’s, California Administrative Code.
3.04 OPERATION AND MAINTENANCE:
A. Operation and Maintenance Instructions: Prior to Substantial Completion, arrange for each installer of equipment that requires regular operation and maintenance to meet with designated OWNER personnel to provide instruction in proper operation and maintenance. Provide instruction by manufacturer’srepresentatives if installers are not experienced in operation and maintenance procedures. Include a detailed review of the following items:
1. Maintenance manuals.
2. Spare parts and materials.
3. Tools.
4. Lubricants.
5. Fuels.
6. Identification systems.
7. Control sequences.
8. Hazards.
9. Cleaning.
10. Warranties and bonds.
11. Maintenance agreements and similar continuing commitments.
B. As part of instruction for operating equipment, demonstrate the following procedures:
1. Start-up.
2. Shutdown.
City of Hermosa Beach
CIP 689- Clark Building Renovations CONTRACT CLOSEOUT
01 7700-6
3. Emergency operations.
4. Noise and vibration adjustments.
5. Safety procedures.
6. Economy and efficiency adjustments.
7. Effective energy utilization.
C. Notice Of Termination: CONTRACTOR shall submit a Notice of Termination (NOT) to the local Regional Water Quality Control Board, RWQCB. Provide a copy of NOT to OAR.
3.05 FINAL CLEANING
A. General: Related sections of the Contract Documents specify general cleaning during performance of the Work. General cleaning is included in Division 01 Section “Construction Facilities and Temporary Controls”.
B. Cleaning: Employ experienced workers or professional cleaners for final cleaning.
Clean each surface or unit to the condition expected in a normal, commercial building cleaning and maintenance program. Comply with manufacturer’s instructions.
1. Complete the following cleaning operations before requesting inspection for a certificate of Substantial Completion.
a. Remove labels that are not permanent labels.
b. Clean transparent materials, including mirrors and glass in doors and windows. Remove glazing compounds and other substances that are noticeable vision-obscuring materials. Replace chipped or broken glass and other damaged transparent materials.
c. Clean exposed exterior and interior hard-surfaced finished to a dustfree condition, free of stains, films, and similar foreign substances.
Restore reflective surfaces to their original condition. Leave concrete floors broom clean. Vacuum carpeted surfaces.
d. Wipe surfaces of mechanical and electrical equipment. Remove excess lubrication and other substances. Clean plumbing fixtures to a sanitary condition. Clean light fixtures and lamps.
e. Clean the Project site, including landscape development areas, of rubbish, litter, and other foreign substances. Sweep paved areas broom clean; remove stains, spills, and other foreign deposits.
City of Hermosa Beach
CIP 689- Clark Building Renovations CONTRACT CLOSEOUT
01 7700-7
Rake grounds that are neither paved nor planted to a smooth, eventextured surface.
END OF SECTION
City of Hermosa Beach
CIP 689- Clark Building Renovations
CUTTING AND PATCHING
01 7329-1
SECTION 01 7329
CUTTING AND PATCHING
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. This Section specifies procedural requirements for cutting and patching.
1.02 RELATED REQUIREMENTS
A. Section 01 2973 - Schedule of Values.
B. Section 01 3113 - Project Coordination.
C. Section 01 3119 - Project Meetings.
D. Section 01 3213 - Construction Schedule.
E. Section 01 3300 - Submittal Procedures.
F. Section 01 7123 - Field Engineering.
G. Section 01 7836 - Warranties.
H. Section 01 4525 - Testing, Adjusting, and Balancing of HVAC.
1.03 SUBMITTALS
A. The word “cutting” as used in the Contract Documents includes, but is not limited to, cutting, drilling, chopping, and other similar operations and the word “patching” includes, but is not limited to, patching, rebuilding, reinforcing, repairing, refurbishing, restoring, replacing, or other similar operations.
B. Cutting and Patching Proposal: CONTRACTOR shall submit a proposal describing procedures well in advance of the time cutting and patching will be performed if the Contract Documents requires approval of these procedures before proceeding.
Include the following information, as applicable, in the proposal:
City of Hermosa Beach
CIP 689- Clark Building Renovations
CUTTING AND PATCHING
01 7329-2
1. Describe the extent of cutting and patching required. Denote how it will be performed and indicate why it cannot be avoided.
2. Describe anticipated results in terms of changes to existing construction.
Include changes to structural elements and operating components as well as changes in the building’s appearance or other significant visual elements.
3. List products to be used and firms or entities that will perform this Work.
4. Indicate dates when cutting and patching will be performed.
5. Utilities: List utilities that cutting and patching operations will disturb or affect. List utilities to be relocated and those that will be temporarily outof-service. Indicate how long service will be disrupted.
6. Where cutting and patching involves adding reinforcement to structural elements, submit details and engineering calculations showing integration of reinforcement with the original structure.
7. Review by ARCHITECT and DSA prior to proceeding with cutting and patching does not waive ARCHITECT right to later require complete removal and replacement of defective Work.
1.04 QUALITY ASSURANCE
A. Requirements for structural Work: Do not cut and patch structural elements in a manner that would change their load-carrying capacity or load-deflection ratio.
1. Obtain approval from ARCHITECT and DSA of the cutting and patching proposal before cutting and patching the following structural elements:
a. Foundation construction.
b. Bearing and retaining walls.
c. Structural concrete.
d. Structural steel.
e. Lintels.
f. Timber and primary wood framing.
g. Structural decking.
h. Stair systems.
City of Hermosa Beach
CIP 689- Clark Building Renovations
CUTTING AND PATCHING
01 7329-3
i. Miscellaneous structural metals.
j. Exterior curtain-wall construction.
k. Equipment supports.
l. Piping, ductwork, vessels, and equipment.
m. Structural systems of special construction in Division 13 Sections.
B. Operational Limitations: Do not cut and patch operating elements or related components in a manner that would result in reducing their capacity to perform as intended. Do not cut and patch operating elements or related components in a manner that would result in increased maintenance or decreased operational life or safely.
1. Obtain review of the cutting and patching proposal before cutting and patching the following operating elements or safety related systems:
a. Primary operational systems and equipment.
b. Air or smoke barriers.
c. Water, moisture, or vapor barriers.
d. Membranes and flashings.
e. Fire protection systems.
f. Noise and vibration control elements and systems.
g. Control systems.
h. Communication and/or data systems.
i. Conveying systems.
j. Electrical wiring systems.
k. Operating systems of special construction in Division 13 Sections.
C. Visual Requirements: Do not cut and patch construction exposed on the exterior or in occupied spaces in a manner that would, in the opinion of ARCHITECT, reduce the building’s aesthetic qualities. Do not cut and patch construction in a manner that would result in visual evidence of cutting and patching. Remove and replace Work cut and patched in a visually unsatisfactory manner.
City of Hermosa Beach
CIP 689- Clark Building Renovations
CUTTING AND PATCHING
01 7329-4
1. If possible, retain the original installer or fabricator to cut and patch the exposed Work listed below. If it is impossible to engage the original installer or fabricator, engage another recognized experienced and specialized firm.
a. Firestopping.
b. Acoustical ceilings.
c. Acoustical panels.
d. Finished wood flooring.
e. Synthetic sports flooring.
f. Carpeting.
g. HVAC enclosures, cabinets, or covers.
h. Ceramic and quarry tile.
i. Gypsum board.
j. Masonry (exterior and interior where exposed).
k. Tack boards.
l. Casework.
m. Finish carpentry.
1.05 WARRANTY
A. Existing Warranties: Replace, patch, and repair material and surfaces cut or damaged by methods and with materials in such a manner as not to void any warranties required or existing.
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION
3.01 INSPECTION
A. Examine surfaces to be cut and patched and conditions under which cutting and patching is to be performed before cutting. If unsafe or unsatisfactory conditions are encountered, take corrective action before proceeding.
City of Hermosa Beach
CIP 689- Clark Building Renovations
CUTTING AND PATCHING
01 7329-5
1. Before proceeding, meet at the Project site with parties involved in cutting and patching, including mechanical and electrical trades. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding.
3.02 PREPARATION
A. Temporary support: Provide adequate temporary support of existing improvements or Work to be cut.
B. Protection: Protect existing improvements and Work during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of existing improvements or Work that might be exposed during cutting and patching operations.
C. Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.
D. Where the Work requires sandblasting of existing surfaces in order to receive new materials secured by cementitious, adhesive or chemical bond, completely remove existing finishes, stains, oil, grease, bitumen, mastic and adhesives or other substances deleterious to the new bonding or fastening of new Work. Utilize wet sand blasting for interior surfaces and for exterior surfaces where necessary to prevent objectionable production of dust.
3.03 PERFORMANCE
A. General: Employ skilled workmen to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time and complete without delay.
Carefully remove existing Work to be salvaged and/or reinstalled. Protect and store for reuse into the Work. Verify compatibility and suitability of existing substrates before starting the Work.
B. Cutting: Cut existing construction using methods least likely to damage elements retained or adjoining Work. Where possible, review proposed procedures with the original installer; comply with the original installer’s recommendations.
1. In general, where cutting, use hand or small power tools designed for sawing or grinding, not hammering and chopping. Cut holes and slots as small as possible, neatly to size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.
2. To avoid marring existing finished surfaces, cut or drill from the exposed or finished side into concealed surfaces.
3. Cut through concrete and masonry using a cutting machine, such as a carborundum saw or a diamond-core drill. Saw cut reinforcing bars and
City of Hermosa Beach
CIP 689- Clark Building Renovations
CUTTING AND PATCHING
01 7329-6
paint ends with bituminous paint except where bonded into new concrete or masonry.
4. Comply with requirements of applicable Sections of Divisions 31, 32, and 33 where cutting and patching requires excavating, backfill, and re-compaction.
5. Woodwork: Cut and or remove to a panel or joint line.
6. Sheet Metal: Remove back to joint, lap, or connection. Secure loose or unfastened ends or edges and seal watertight.
7. Glass: Remove cracked, broken, or damaged glass and clean rebates and stops of setting materials.
8. Plaster: Cut back to sound plaster on straight lines, and back bevel edges of remaining plaster. Trim existing lath and prepare for new lath.
9. Gypsum Wallboard: Cut back on straight lines to undamaged surfaces with at least two opposite cut edges centered on supports.
10. Acoustical ceilings: Remove hanger wires and related appurtenances where ceilings are not scheduled to be installed.
11. Tile: Cut back to sound tile and backing on joint lines.
12. Flooring: Completely remove flooring and clean backing of prior adhesive.
Carefully remove wood flooring for patching and repairing of existing wood flooring scheduled to remain.
C. Patching: Patch with durable seams that are as invisible as possible. Comply with required tolerances.
1. Where feasible, inspect and test patched areas to demonstrate integrity of the installation. Verify conditions of existing substrates prior to executing Work.
2. Restore exposed finishes of patched areas and extend finish restoration into retaining adjoining construction in a manner that will eliminate all evidence of patching and refinishing.
3. Concrete: Maintain cut edges in a moist condition for twenty four hours prior to the placement of new concrete. In lieu of this an epoxy adhesive may be provided. Finish placed concrete to match existing unless noted otherwise. Concrete shall have a compressive strength of 3,000 psi where installed to repair and match existing improvements, unless noted otherwise.
City of Hermosa Beach
CIP 689- Clark Building Renovations
CUTTING AND PATCHING
01 7329-7
4. Metal Fabrications: Items to remain exposed shall have their edges cut and ground smooth and rounded.
5. Sheet Metal: Replace removed or damaged sheet metal items for new Work.
6. Glass: Install matching glass and re-seal exterior window assemblies.
7. Lath and Plaster: Install new lath materials to match existing and fasten to supports at 6-inch centers. Provide a 6-inch lap where new lath to adjoins existing lath. Fasten new lath as required for new Work. Restore paper backings as required. Apply a bonding agent on cut edges of existing plaster.
Apply three coat plaster of the type, thickness, finish, texture, and color to match existing.
8. Gypsum Wallboard: Fasten cut edges of wallboard. Install patches with at least two opposite edges centered on supports and secure at 6-inch centers.
Tape and finish joints and fastener heads. Patching shall be non-apparent when painted or finished.
9. Acoustical Ceilings: Comply with the requirements for new Work specified in related sections of the Contract Documents.
10. Resilient Flooring: Completely remove flooring and prepare substrate for new material.
11. Painting: Prepare areas to be patched, patch and paint as specified under related sections of the Contract Documents.
3.04 CLEANING
A. Clean areas and spaces where cutting and patching are performed. Completely remove paint, mortar, oils, putty, and similar items. Thoroughly clean piping, conduit, and similar features before applying paint or other finishing materials.
Restore damaged coverings to their original condition.
END OF SECTION
City of Hermosa Beach
CIP 689 - Clark Building Renovations
MAINTENANCE AND OPERATIONS & COMMUNITY SERVICES
DEMONSTRATION AND TRAINING
01 7900-1
SECTION 01 7900
MAINTENANCE AND OPERATIONS & COMMUNITY SERVICES DEPARTEMENT
STAFF DEMONSTRATION AND TRAINING
PART 1 – GENERAL
1.01 SECTION INCLUDES
A. Administrative and procedural requirements for training OWNER’s personnel.
1. Demonstration of operations of systems, subsystems and equipment.
2. Training in operation and maintenance of systems, subsystems, and equipment.
1.02 RELATED REQUIREMENTS
A. Project Commissioning Plan (C&P).
B. CHPS Best Practices Manual.
C. CAL/OSHA Minimum Ventilation Standard, Title 8, Section 5142.
D. California Building Code, Chapter 12.
E. Division 01 - General Requirements.
F. Division 22 - Plumbing.
G. Division 23 – Heating Ventilating and Air Conditioning.
H. Division 26 - Electrical.
I. Division 27 – Communications.
1.03 SUBMITTALS
A. Submittals, including training modules, require the Commissioning Services Provider’s (CxSP) review and OAR acceptance prior to implementation.
B. Upon completion of training, submit two complete training manuals for OWNER’s use including materials in the complete training manual in the Adobe PDF format. Each manual shall contain specific training and instruction manuals and hand-outs for the following designated end-users:
City of Hermosa Beach
CIP 689 - Clark Building Renovations
MAINTENANCE AND OPERATIONS & COMMUNITY SERVICES
DEMONSTRATION AND TRAINING
01 7900-2
1. OWNER Maintenance and Operations (M&O) Personnel.
2. OWNER Community Services Department Personnel
C. Demonstration and Training Video: CONTRACTOR shall video record each training and demonstration session and submit a copy at end of each training module.
CONTRACTOR shall include a copy of manufacturer training video materials presented during training and demonstration session.
1.04 COORDINATION
A. Coordinate instruction schedule with the OAR, CxSP, and OWNER’s M&O personnel.
Adjust schedule as required to reasonably accommodate the schedules of participants and to minimize disrupting OWNER operations.
B. Coordinate with instructors, including providing notification of scheduled dates, times, length of instruction time and course content.
C. Coordinate content of training modules with content of approved Emergency Manual and Operations and Maintenance Manual. Do not submit instruction program until manual has been reviewed and accepted by the OAR.
1.05 INSTRUCTION PROGRAM
A. Program Structure: Develop instruction program that includes individual demonstration and training modules for the operation, maintenance, minor repair (completion in under two hours) and calibration of systems and components in the system as required by Section 01 9113, Divisions 22, 23 and Division 26 and as specified in Part 3 of this Section, “DEMONSTRATION AND TRAINING”.
B. For each module, include instruction for the following:
1. Basis of System Design (for OWNER Operations and Maintenance Personnel), Operational Requirements and Criteria, including, but not limited to:
a. System, subsystem and equipment descriptions.
b. Performance and design criteria if CONTRACTOR is delegated design responsibility.
c. Operating standards.
d. Regulatory requirements.
e. Equipment function.
f. Operating characteristics.
City of Hermosa Beach
CIP 689 - Clark Building Renovations
MAINTENANCE AND OPERATIONS & COMMUNITY SERVICES
DEMONSTRATION AND TRAINING
01 7900-3
g. Limiting conditions.
h. Performance curves.
2. Documentation (for OWNER) Review in detail the following documentation:
a. Emergency manuals.
b. Operations manuals.
c. Maintenance manuals.
d. Project Record Documents.
e. Identification systems.
f. Warranties.
g. Maintenance service agreements and similar continuing commitments.
3. Emergencies (for OWNER): Review, without limitation, the following, as applicable:
a. Instructions on meaning of warnings, trouble indications, and error messages.
b. Instructions on stopping.
c. Shutdown instructions for each type of emergency.
d. Operating instructions for conditions outside of normal operating limits.
e. Sequences for electric or electronic systems.
f. Special operating instructions and procedures.
4. Operations (for OWNER): Review, without limitation, the following as applicable:
a. Startup procedures.
b. Equipment or system break-in procedures.
c. Routine and normal operating instructions.
d. Regulation and control procedures.
e. Control sequences.
City of Hermosa Beach
CIP 689 - Clark Building Renovations
MAINTENANCE AND OPERATIONS & COMMUNITY SERVICES
DEMONSTRATION AND TRAINING
01 7900-4
f. Safety procedures.
g. Instructions on stopping.
h. Normal shutdown instructions.
i. Operating procedures for system, subsystem or equipment failure. j. Seasonal and weekend operating instructions.
k. Required sequences for electric or electronic systems. l. Special operating instructions and procedures.
5. Adjustments (for OWNER): Review, without limitation, the following as applicable:
a. Alignments.
b. Checking adjustments.
c. Noise and vibration adjustments.
d. Economy and efficiency adjustments.
6. Troubleshooting (for OWNER): Review, without limitation, the following as applicable:
a. Diagnostic instructions.
b. Test and inspection procedures.
7. Maintenance (for OWNER): M&O Review, without limitation, the following, as applicable:
a. Inspection procedures.
b. Types of cleaning agents to be used and methods of cleaning. c. List of cleaning agents and methods of cleaning detrimental to product. d. Procedures for routine cleaning.
e. Procedures for preventative maintenance.
f. Procedures for routine maintenance.
g. Instruction on use of special tools.
City of Hermosa Beach
CIP 689 - Clark Building Renovations
MAINTENANCE AND OPERATIONS & COMMUNITY SERVICES
DEMONSTRATION AND TRAINING
01 7900-5
8. Repairs (for OWNER): Review, without limitation, the following as applicable:
a. Diagnostic instructions.
b. Repair instructions.
c. Disassembly; component removal, repair and replacement and reassembly instructions.
d. Instructions for identifying parts and components.
e. Review of parts needed for operation and maintenance.
1.06 PREPARATION
A. Training Facilitator: Engage qualified training facilitator no later than 120 days prior to start of training to prepare instruction program and training modules, to coordinate instructors, and to coordinate between CONTRACTOR, OAR and CxSP for number of participants, instruction times and location.
B. Training Instructor: Engage qualified training instructors to instruct OWNER’s personnel to adjust, operate and maintain systems, subsystems and equipment not part of a system no later than 30 days prior to start of training of assigned modules.
C. Scheduling: Provide instruction at mutually agreed on times.
1. Schedule training with OWNER, through OAR, with at least two weeks advance notice.
2. Schedule training to conform to personnel availability at Site.
3. Conduct training(s) after the execution of commissioning Pre-functional and Functional Tests are completed.
4. Base duration of training on hours specified in the applicable specifications or minimums defined in Article 1.08.
D. Familiarize OWNER staff regarding CAL/OSHA Title 8, section 5142 Requirements.
1.07 OPERATIONS AND MAINTENANCE MANUALS
A. CONTRACTOR shall direct Subcontractors to compile and prepare M&O Manuals and other required documentation for the equipment and systems that are provided and/or installed per their scope of work for submittal to OAR prior to project closeout.
B. The OAR shall receive a copy of the Operations and Maintenance manuals prior to initiation of demonstration and training for review and acceptance or rejection.
City of Hermosa Beach
CIP 689 - Clark Building Renovations
MAINTENANCE AND OPERATIONS & COMMUNITY SERVICES
DEMONSTRATION AND TRAINING
01 7900-6
C. Operations and Maintenance manuals shall meet the respective requirements of Divisions 22,23 and Division 26; and comply with the following:
1. Quantity: Two.
2. Format: 8 ½ by 11 loose leaf binders. Each binder shall be clearly labeled on the spine and meet the requirements of Section 01 7700. Dividers shall be made of card stock with permanently marked index tabs to separate each section and sub section. Tab labels shall not be handwritten. Binders will meet other formatting requirements as outlined in DIVISIONS 02 to 49, as applicable.
3. Contents: There shall be a title page and table of contents at the beginning of each binder. The table of contents shall be an outline that identifies the equipment or systems documentation included in the binder and references the specification sections relating to the equipment and systems that are being included in each part of the binder. Each part of the binder shall contain the information described below, in the following order.
a. CONTRACTOR. The first page shall contain the name, address, and telephone number of the manufacturer and installing CONTRACTOR, as well as the 24-hour number for emergency service for each piece of equipment identified in this section.
b. Preventive Maintenance Instructions. This section shall list the location of preventative maintenance instructions. The list shall show the piece of equipment, the Operations and Maintenance document name, and the O&M document page number that contains the instructions. c. Submittal and Product Data. This section shall include product data not covered by manufacturer's Operations and Maintenance instructions and associated shop drawings.
d. Warranty and Service Contracts. This section shall include the following for each piece of equipment, as applicable:
1) Copy of the equipment warranty information provided as part of Section 01 7836.
2) Additional Warranties in accordance with Warranty
requirements in DIVISIONS 02 to 49, as applicable. Equipment Warranties shall clearly list requirements to maintain the Warranty in effect, conditions or acts that would invalidate or void the Warranty, and Warranty expiration date.
3) Service contracts issued. Contracts shall clearly indicate contract dates and scope of work included.
City of Hermosa Beach
CIP 689 - Clark Building Renovations
MAINTENANCE AND OPERATIONS & COMMUNITY SERVICES
DEMONSTRATION AND TRAINING
01 7900-7
e. Operation and Maintenance Instructions. These shall be the written manufacturer's maintenance and operating instructions with the model number and features of the installed equipment or system clearly identified. This section shall include applicable data on the following:
1) Installation, startup, and break-in instructions.
2) Starting, normal shutdown, emergency shutdown, manual operation, seasonal changeover and normal operating procedures and data, including any special limitations.
3) Operations and Maintenance and installation instructions that were shipped with the unit.
4) Preventative maintenance and service procedures and schedules. 5) Troubleshooting procedures.
6) A parts list, edited to omit reference to items which do not apply to this installation.
7) A list of any special tools required to service or maintain the equipment.
8) Performance data, ratings, and curves.
f. Control Drawings. This section contains controls drawings and the final sequence of operations, set points, and schedules as set during the Commissioning Process. If shop drawings, portions of the project manual, or record drawings clearly show this information, a copy of this information may be inserted. Otherwise, original drawings shall be generated and included in this section.
D. Division 23 Special Water and Air Balance Documentation. The Balancing Subcontractor will compile and submit the following with other documentation that may be specified elsewhere in the Project Specifications.
1. Final report containing an explanation of the methodology, assumptions, test conditions, and the results in a clear format with designations of all uncommon abbreviations and column headings.
2. The Balancing Subcontractor shall mark on the drawings where all traverse and other critical measurements were taken and cross reference the location in the Test and Balance report.
1.08 DEMONSTRATION AND TRAINING SCHEDULE
City of Hermosa Beach
CIP 689 - Clark Building Renovations
MAINTENANCE AND OPERATIONS & COMMUNITY SERVICES
DEMONSTRATION AND TRAINING
01 7900-8
A. The following applies to the minimum duration of demonstration and training provided City of Hermosa Beach Maintenance Division and Community Services Department Personnel.
1. Heat Generation:
2. Water Distribution Piping: Minimum Refrigerant Systems:
a. Condensers
b. Pumps
c. Distribution Piping
3. HVAC Systems:
a. Air-handling Equipment:
b. Air Distribution Systems
4. HVAC Instrumentation and Controls
5. Lighting Systems and Controls
PART 2 – PRODUCTS – N/A
PART 3 – EXECUTION – N/A
END OF SECTION
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING AND INSPECTION
01 4523-1
SECTION 01 4523
TESTING AND INSPECTION
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Testing and inspection services to meet requirements of the California Building Code (CBC).
B. Related Requirements:
1. Section 03 2000 – Concrete Reinforcing.
2. Section 03 3000 – Cast-in-Place Concrete.
3. Section 04 2200 – Concrete Unit Masonry.
4. Section 05 1200 – Structural Steel Framing.
5. Section 06 1000 – Rough Carpentry.
1.02 REFERENCES
A. American Concrete Institute (ACI):
1. ACI 318 – Building Code Requirements for Structural Concrete and Commentary.
B. American Institute of Steel Construction (AISC):
1. AISC 360 – Specification for Structural Steel Buildings.
2. AISC 341 – Seismic Provisions for Structural Steel Buildings.
C. ASTM International (ASTM):
1. ASTM A108 – Standard Specification for Steel Bar, Carbon and Alloy, Cold-Finished.
2. ASTM A370 – Standard Test Methods and Definitions for Mechanical Testing of Steel Products.
3. ASTM A706 – Standard Specification for Deformed and Plain Low-Alloy Steel Bars for Concrete Reinforcement.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING AND INSPECTION
01 4523-2
4. ASTM C31 - Standard Practice for Making and Curing Concrete Test Specimens in the Field.
5. ASTM C172 - Standard Practice for Sampling Freshly Mixed Concrete.
6. ASTM C780 - Standard Test Method for Preconstruction and Construction Evaluation of Mortars for Plain and Reinforced Unit Masonry.
7. ASTM C1140 - Standard Practice for Preparing and Testing Specimens from Shotcrete Test Panels.
8. ASTM C1314 - Standard Test Method for Compressive Strength of Masonry Prisms.
9. ASTM C1604 - Standard Test Method for Obtaining and Testing Drilled Cores of Shotcrete.
10. ASTM E164 - Standard Practice for Contact Ultrasonic Testing of Weldments.
11. ASTM E488 - Standard Test Methods for Strength of Anchors in Concrete Elements.
12. ASTM E543 - Standard Specification for Agencies Performing Nondestructive Testing.
13. ASTM E605 - Standard Test Methods for Thickness and Density of Sprayed Fire-Resistive Material (SFRM) Applied to Structural Members.
14. ASTM E1444 - Standard Practice for Magnetic Particle Testing.
15. ASTM F606 - Standard Test Methods for Determining the Mechanical Properties of Externally and Internally Threaded Fasteners, Washers, Direct Tension Indicators, and Rivets.
D. Association of the Wall and Ceiling Industry (AWCI):
1. AWCI Technical Manual 12-B - Standard Practice for the Testing and Inspection of Field Applied Thin Film Intumescent Fire-Resistive Materials; an Annotated Guide.
E. American Welding Society (AWS):
1. AWS D1.1 – Structural Welding Code.
2. AWS D1.4 – Structural Welding Code – Reinforcing Steel.
3. AWS D1.8 – Structural Welding Code – Seismic Supplement.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING AND INSPECTION
01 4523-3
1.03 REGULATORY REQUIREMENTS
A. Laboratories performing testing shall have the City of Hermosa Beach approval prior to providing material testing or special inspection services.
B. Tests of materials and inspections shall be in accordance to Section 4-213 through 4-219 of the California Building Standards Commission’s, California Administrative Code.
C. Required material testing, inspections and special inspections are indicated on the Building Permit issued by the City of Hermosa Beach.
1.04 TESTS
A. OWNER will contract with an approved testing laboratory to perform the testing indicated on the Contract Documents, including the Tests and Special Inspections (T&I) list.
B. Selection of material to be tested shall be by the Testing Laboratory and not by CONTRACTOR.
C. Any material shipped from the source of supply prior to having satisfactorily passed such testing and inspection, or prior to the receipt of notice from Project Inspector such testing and inspection is not required, shall not be incorporated into the Work.
D. OWNER will select, and directly reimburse, the Testing Laboratory for costs of all required tests and inspections.
E. The Testing Laboratory is not authorized to release, revoke, alter, or enlarge requirements of the Contract Documents or approve or accept any portion of the Work.
F. The Testing Laboratory shall not perform any duties of CONTRACTOR.
1.05 TEST REPORTS
A. Test reports shall include all tests performed, regardless of whether such tests indicate the material is satisfactory or unsatisfactory. Samples taken but not tested shall also be reported. Records of special sampling operations, when and as required, shall also be reported. Reports shall indicate the material (or materials) was sampled and tested in accordance with requirements of CBC, Title 24, Parts 1 and 2, as indicated on the Contract Documents. Test reports shall indicate specified design strength and specifically state whether or not the material (or materials) tested comply with the specified requirements.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING AND INSPECTION
01 4523-4
1.06 VERIFICATION OF TEST REPORTS
A. Each Testing Laboratory shall submit to the City of Hermosa Beach , in duplicate, a verified report covering all tests required to be performed by that agency during the progress of the Work. Such report, covering all required tests, shall be furnished prior to Substantial Completion and/or, when construction on the Work is suspended, covering all tests up to the time of Work suspension.
1.07 INSPECTION BY OWNER
A. OWNER, and its representatives, shall have access, for purposes of inspection, at all times to all parts of the Work and to all shops wherein the Work is in preparation.
CONTRACTOR shall, at all times, maintain proper facilities and provide safe access for such inspection.
B. OAR shall have the right to reject materials and/or workmanship deemed defective Work and to require correction. Defective workmanship shall be corrected in a satisfactory manner and defective materials shall be removed from the premises and legally disposed of without charge to OWNER. If CONTRACTOR does not correct such defective Work within a reasonable time, fixed by written notice and in accordance with the terms and conditions of the Contract Documents, OWNER may correct such defective Work and proceed in accordance with related Articles of the Contract Documents.
C. CONTRACTOR is responsible for compliance to all applicable local, state, and federal regulations regarding codes, regulations, ordinances, restrictions, and requirements.
1.08 PROJECT INSPECTOR
A. A Project Inspector will be employed by the City of Hermosa Beach in accordance with requirements of Title 24 of the California Code of Regulations with their duties specifically defined therein.
B. Inspection of Work shall not relieve CONTRACTOR from any obligation to fulfill all terms and conditions of the Contract Documents.
C. CONTRACTOR shall be responsible for scheduling times of inspection, tests, sample taking, and similar activities of the Work.
1.09 STRUCTURAL TESTS AND SPECIAL INSPECTIONS
1. Retaining Walls:
a. Continuous inspections by Geotechnical Engineer:
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING AND INSPECTION
01 4523-5
1) Placement, compaction and inspection of soil per CBC Section 1705A.6.1 for fills supporting foundations.
2) Segmental retaining walls; inspect placement of units, dowels, connectors, etc.
b. Concrete Retaining Walls: Provide tests and inspections as indicated on paragraphs below for concrete.
c. Masonry Retaining Walls: Provide tests and inspections as indicated on paragraphs below for masonry.
A. Concrete:
1. Cast in Place Concrete: Inspection and testing in conformance to CBC Table 1705A.3:
a. Inspection of reinforcement, including prestressing tendons and verification of placement, per ACI 318, sections 25.2, 25.2, 25.5.1 through 26.5.3.
b. Reinforcing bar welding: Inspect per AWS D1.4, ACI 318 26.5.4. 1) Verification of weldability of reinforcing bars other than ASTM A706.
2) Inspect single-pass fillet welds, maximum 5/16”.
3) Inspect all other welds.
c. Inspect anchors cast in concrete per ACI 318, section 17.8.2. d. Inspect anchors post-installed in hardened concrete members:
1) Continuous inspection of adhesive anchors installed in horizontally or upwardly inclined orientations to resist sustained tension loads, per ACI 318, section 17.8.2.4. 2) Mechanical anchors and adhesive anchors, not defined in previous paragraph, per ACI 318, section 17.8.2.
e. Design Mix:
1) Verify use of required mix, per ACI 318, chapter 19 and sections 26.4.3 and 26.4.4.
2) Batch Plant Inspection: The quality and quantity of materials used in transit-mixed concrete and in batched
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING AND INSPECTION
01 4523-6
aggregates shall be continuously inspected as required by CBC section 1705A.3.2. If approved by DSA, batch plant
inspection may be reduced to periodic if plant complies with CBC section 1705A3.3.1, item 1, and requires first batch inspection, weightmaster, and batch tickets.
f. Prior to concrete placement, fabricate specimens for strength tests, perform slump and air content tests, and determine the temperature of the concrete, per ASTM C172, ASTM C31, ACI 318, sections
26.4.5 and 26.12.
g. Inspect concrete and shotcrete placement for proper application techniques, per ACI 318, section 26.4.5.
h. Verify maintenance of specified curing temperature and techniques per ACI 318 sections 26.4.7 through 26.4.9 and CBC section 1908.9. i. Inspect prestressed concrete for:
1) Application of prestressing forces, per ACI 318 section
26.9.2.1 2) Grouting of bonded prestressing tendons per ACI 318 section 26.9.2.3.
j. Inspection of erection of precast concrete members per ACI 318 chapter 26.8.
k. Verify in-situ concrete strength, prior to stressing of tendons in posttensioned concrete and prior to removal of shores and forms from beams and structural slabs per ACI 318 section 26.10.1.b. l. Sampling and testing of reinforcing steel per ASTM A370, DSA IR 17-10 and CBC section 1910A.2. CONTRACTOR shallsubmit mill certificate indicating compliance with requirements for reinforcement, anchors, ties, and metal accessories.
2. Post-installed Anchors:
a. Special Inspector will inspect installation of post-installed anchors in hardened concrete members as required by CBC table 1705A.3, item 4.
1) Adhesive anchors installed in horizontally or upwardly inclined orientations to resist sustained tension loads, per ACI 318, section 17.8.2.4.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING AND INSPECTION
01 4523-7
2) Mechanical anchors and adhesive anchors not defined
above, per ACI 318, section 17.8.2.
b. Testing Laboratory will test post-installed anchors in conformance to CBC section 1905A and ASTM E488.
B. Structural Masonry:
1. Material Verification and Testing:
a. Sampling and testing of reinforcing steel per ASTM A370, DSA IR 17-10 and CBC section 1910A.2. CONTRACTOR shallsubmit mill certificate indicating compliance with requirements for reinforcement, anchors, ties, and metal accessories.
b. Submit manufacturer’s certificate of compliance for masonry units, mortar and grout materials. Test masonry units, mortar and grout (unit strength method).
c. Testing Laboratory will test masonry prisms in conformance with ASTM C1314.
d. Special Inspector will verify proportions of site-prepared, premixed or preblended mortar and grout, per ASTM C780. e. Testing Laboratory will test core-drilled samples in conformance with CBC 2114.6.2.
2. Inspection:
a. Special Inspector will continuously inspect preparation of prisms per ASTM C1314.
b. Special inspector will verify size, location and condition of dowels and construction supporting masonry.
c. Special inspector will verify size specified size, grade and type of reinforcement.
d. Special inspector will verify weldability of reinforcing bars other than ASTM A706. Special inspector to inspect reinforcing bar welding: Inspection to be in conformance with AWS D1.4, ACI 318
26.5.4. e. Special inspector will inspect placement of reinforcement, connectors, masonry units and construction of mortar joints.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING AND INSPECTION
01 4523-8
f. Special inspector will verify protection of masonry during cold weather temperature (temperature below 40o F) or hot weather (temperature above 90o F).
g. Special inspector will inspect type, size and location of anchors and all other items to be embedded in masonry, including other details of anchorage of masonry to structural members, frames and other construction.
h. Special inspector will inspect grout space prior to grouting and placement of grout.
3. Post-installed Anchors in Masonry:
a. Special inspector will inspect anchors cast in concrete per ACI 318, section 17.8.2.
b. Special inspector will inspect anchors post-installed in hardened concrete members:
1) Continuous inspection of adhesive anchors installed in horizontally or upwardly inclined orientations to resist sustained tension loads, per ACI 318, section 17.8.2.4. 2) Mechanical anchors and adhesive anchors, not defined in previous paragraph, per ACI 318, section 17.8.2.
c. Testing Laboratory will test post-installed anchors in conformance to CBC section 1905A and ASTM E488.
C. Structural Steel:
1. Special inspector will verify that all materials are properly marked in conformance with AISC 360, Section 3.3 and applicable ASTM standards. a. Mill certificates indicating material properties that comply with requirements.
b. Materials, sizes, types and grades complying with requirements.
2. Testing Laboratory will test unidentified materials in conformance with ASTM A370.
3. Special inspector will examine seam welds of HSS shapes in conformance with DSA IR-17-3.
4. Special inspections and non-destructive testing of structural steel elements shall be in conformance to CBC section 1705A.2.1.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING AND INSPECTION
01 4523-9
D. High Strength Bolts:
1. Special inspector will verify identification markings and manufacturer’s certificates of compliance conform to ASTM standards specified in the Contract Documents, per DSA IR 17-9.
2. Testing Laboratory will test high-strength bolts, nuts and washers in conformance with ASTM F606, ASTM A370 and DSA IR 17-8.
3. Special inspector will inspect bearing-type (“snug tight”) bolt connections in conformance with AISC 360, section M2.5 and DSA IR 17-9.
4. Special inspector will inspect slip-critical bolt connections in conformance with AISC 360, section M2.5.
E. Welding:
1. Verification of Materials, Equipment and Welders:
a. Special inspector will verify weld filler material identification markings per AWS designation listed on the Contract Documents and the WPS.
b. Special inspector will verify material manufacturer’s certificate of compliance.
c. Special inspector will verify WPS, welder qualifications and equipment in conformance to DSA IR 17-3.
2. Shop Welding: Special inspector will inspect the following, per CBC 1705A.2.1, AISC 360 (and AISC 341, as applicable) and DSA IR 17-3:
a. Groove, multi-pass fillet welds larger than 5/16”, plug and slot welds.
b. Single-pass fillet welds equal or less than 5/16”.
c. Inspect welding of stairs and railing systems.
d. Verification of reinforcing steel weldability.
e. Welding of reinforcing steel, per AWS D1.4.
3. Field Welding: Special inspector will inspect the following, per CBC 1705A.2.1, AISC 360 (and AISC 341, as applicable) and DSA IR 17-3:
a. Groove, multi-pass fillet welds larger than 5/16”, plug and slot welds.
City of Hermosa Beach
CIP 689- Clark Building Renovations
TESTING AND INSPECTION
01 4523-10
b. Single-pass fillet welds equal or less than 5/16”.
c. End welded studs (ASTM A108) installation, including bend test. d. Floor and roof deck welds.
e. Welding of structural cold-formed steel.
f. Welding of stairs and railing systems.
g. Verification of reinforcing steel weldability.
h. Inspect welding of reinforcing steel.
4. Non-Destructive Testing: Testing Laboratory will test perform ultrasonic and magnetic particle testing in conformance to AISC 360 section N5.5, AISC 341 appendix Q5.2, AWS D1.1, AWS D1.8, ASTM E543, ASTM E1444, ASTM E164 and DSA IR 17-2.
F. Steel Joists and Trusses: Continuous inspection, special inspector will verify size, type and grade for all chord and web members as well as connectors and weld filler material, verify joist profile, dimensions and chamber (if applicable); verify all weld locations, lengths and profiles; mark or tag each joist, in conformance with CBC section 2207.1 and DSA IR 22-3.
G. Anchor Bolts, Anchor Rods and Other Steel:
1. Testing Laboratory will sample and test not readily identifiable anchor bolts and anchor rods in accordance with DSA IR 17-11.
2. Testing Laboratory will sample and test not readily identifiable threaded rod not used for foundation anchorage per procedures noted in DSA IR 17-11.
PART 2 – PRODUCTS (Not used).
PART 3 – EXECUTION (Not used).
END OF SECTION
City of Hermosa Beach
CIP 689- Clark Building Renovations
WARRANTIES
01 7836-1
SECTION 01 7836
WARRANTIES
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. This Section includes administrative and procedural requirements for warranties, including manufacturers and installer’s standard warranties on products and special product warranties.
1. Refer to the General Conditions for terms of the guarantee period for the Work.
1.02 RELATED REQUIREMENTS
A. Section 01 6000 - Product Requirements.
B. Section 01 7329 - Cutting and Patching.
C. Section 01 7700 - Contract Closeout.
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION
3.01 WARRANTY REQUIREMENTS
A. Disclaimers and Limitations: Manufacturer’s disclaimers and limitations on product warranties shall not relieve CONTACTOR of the warranty of the Work incorporating such materials, products, and equipment. Manufacturer’s disclaimers and limitations on warranties do not relieve suppliers, manufacturers, installers, and Subcontractors of the requirement to countersign special warranties with CONTRACTOR.
B. Standard warranties are preprinted written warranties published by individual manufacturers for particular products and are specifically endorsed by the manufacturer to OWNER.
C. Special warranties are written warranties required by or incorporated in the Contract Documents, either to extend time limits provided by standard warranties or to provide greater rights for OWNER.
City of Hermosa Beach
CIP 689- Clark Building Renovations
WARRANTIES
01 7836-2
D. Related Damages and Losses: When correcting failed or defective warranted Work, remove and replace Work that has been damaged as a result of such failure or which must be removed and replaced to provide access for correction of warranted Work.
E. Reinstatement of Warranty: When Work covered by a warranty has failed and been corrected by replacement or rebuilding, reinstate the warranty by written endorsement with the reinstated warranty equal to the original warranty.
F. Replacement Cost: Upon determination the Work covered by a warranty has failed and/or is defective, replace or rebuild the Work to an acceptable condition complying with requirements of the Contract Documents. CONTRACTOR is responsible for the cost of replacing or rebuilding defective Work regardless of whether OWNER has benefited from use of the Work through a portion of its anticipated useful service life.
G. OWNER Recourse: Expressed warranties made to OWNER are in addition to implied warranties and shall not limit the duties, obligations, rights, and remedies otherwise available under the law. Expressed warranty periods shall not be interpreted as limitations on the time in which OWNER can enforce such other duties, obligations, rights, or remedies.
H. Rejection of Warranties: OAR reserves the right to reject warranties and to limit selection to products with warranties not in conflict with requirements of the Contract Documents.
I. Where the Contract Documents require a special warranty, or similar commitment on the Work or part of the Work, OAR reserves the right to refuse to accept the Work until CONTRACTOR presents evidence the entities required to countersign such commitments have done so.
3.02 SUBMITTALS
A. Submit written preliminary warranties prior to Substantial Completion and final warranties prior to Contract Completion. If the certificate of Substantial Completion designates a commencement date for warranties other than the date of Substantial Completion for the Work, submit written warranties as set forth in the certificate of Substantial Completion.
1. When a designated portion of the Work is partially used and/or occupied by OWNER, submit properly executed warranties to ARCHITECT within fifteen days of the Partial Use or Occupancy of the designated portion of the Work.
B. When the Contract Documents require CONTRACTOR, or CONTRACTOR and a Subcontractor, installer, supplier or manufacturer to execute a special warranty, prepare a written document containing appropriate terms and identification, ready
City of Hermosa Beach
CIP 689- Clark Building Renovations
WARRANTIES
01 7836-3
for execution by the required parties. Submit a draft to OAR, through the ARCHITECT, for approval prior to final execution.
1. Refer to Divisions 02 through 49 for specific content requirements and particular requirements for submitting special warranties.
C. Form of Submittal: Prior to Contract Completion, compile two copies of each required final warranty properly executed by CONTRACTOR, or by CONTRACTOR and Subcontractor, installer, supplier, or manufacturer. Organize the warranty documents into an orderly sequence based on the Specifications.
D. Bind warranties and bonds in heavy-duty, commercial-quality, durable three ring, vinyl-covered loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8½ by 11 paper.
1. Provide heavy paper dividers with celluloid covered tabs for each separate warranty. Mark the tab to identify the item or installation. Provide a typed description of the product or installation, including the name of the product, and the name, address, and telephone number of the installer.
2. Identify each binder on the front and spine with the typed or printed title “WARRANTIES,” Project title and/or name, and name of CONTRACTOR.
3. When warranted Work requires operation and maintenance manuals, provide additional copies of each required warranty, as necessary, for inclusion in each required manual.
END OF SECTION
CIP 689 - Clark Building Renovations
ABATEMENT OF HAZARDOUS MATERIALS 022600 -1
SECTION 02 2600 - ABATEMENT OF HAZARDOUS MATERIALS
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
1. Abatement of hazardous materials identified in the Hazardous Materials Phase I Assessment Report, except for underground storage tanks, contaminated soil or groundwater. Furnish labor, materials, supplies, and incidentals required, protect Project site personnel and the surrounding public from exposure to potentially hazardous substances, and prevent the spread of potentially contaminated or hazardous substances.
2. The furnishing of labor, supervision, materials, equipment, tools, permits, manifesting, and services required in the characterization, transportation, and disposal of identified or suspected hazardous substances. The suspect substance may be in drums, containers, stockpiled, or may exist as debris piles on the Project site.
B. Related Requirements:
1. Section 00 3126 - Existing Hazardous Materials Information.
2. Division 01 - General Requirements.
3. Section 02 4119 – Selective Demolition
4. Section 02 8213 - Asbestos Abatement
5. Section 02 8333 - Lead Abatement and Lead Related Construction Work.
C. Regulatory Requirements shall include, but not be limited to: Comply with laws, ordinances, codes, rules, and regulations of the Federal, State and local authorities having jurisdiction over any of the Work specified herein. Comply with federal EPA and state Department of Transportation regulations for shipping of hazardous substances to offsite disposal facilities.
Comply with any regulatory requirements imposed by the treatment, storage, and disposal facility. Regulations pertaining to the transport and disposal of hazardous substances/materials include, but are not limited to, the following:
1. Department of Transportation 49 CFR 172 through 179.
2. Department of Transportation 49 CFR 387 (46 FR 30974, 47073).
3. Department of Transportation DOT-E 8876.
4. Environmental Protection Agency 40 CFR 136 (41 FR 52779).
5. Environmental Protection Agency 40 CFR 261, 262 and 761.
CIP 689 - Clark Building Renovations
ABATEMENT OF HAZARDOUS MATERIALS 022600 -2
6. Resource Conservation and Recovery Act (RCRA).
D. Any transporter of hazardous substancesshall be licensed in the state in which handling and transportation will take place in accordance with applicable regulations.
E. Comply with OSHA (Occupational Safety and Health Administration) Standards and Regulations contained in Title 29 Code of Federal Regulations, Part 1910.120 "Hazardous Waste Operations and Emergency Response."
F. Where reference is made to one of the above standards, the revision in effect at the time of bid opening shall apply.
1.02 QUALITY ASSURANCE
A. The Work of this Section shall be performed by an entity possessing the following minimum qualifications:
1. Contractors License in the state where the Work is performed, supplemented by a Hazardous Waste specialty license, where applicable (i.e., California).
2. MCS 90 Endorsement on Liability Insurance.
3. Pollution Liability Insurance in the amount of $2,000,000 occurrence.
4. Forty-hour OSHA Training and site-specific health and safety plan for its employees proposed to work at the Project site as defined in 29 CFR 1910.120.
5. A Comprehensive Quality Assurance Plan on file with the California Environmental Protection Agency.
6. Project site personnel shall wear personal protective equipment and protective clothing consistent with the levels of protection required for this Work as specified by OSHA (29 CFR Part 1910.120).
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.01 ABATEMENT OF HAZARDOUS MATERIALS
A. Abate hazardous materials including hazardous materials identified in the Phase I Assessment Report.
B. The Work of this section does not include the removal of underground storage tanks, contaminated soil or groundwater, unless specifically authorized in writing by the OAR.
3.02 CONTAINMENT OF RELEASED SUBSTANCES
A. If a hazardous material appears to be leaking or otherwise spreading, contain the release of the material. Provide measures to prevent the release of the material to the environment and protect Project site personnel, adjacent properties and occupants, and the general public from potential exposure.
CIP 689 - Clark Building Renovations
ABATEMENT OF HAZARDOUS MATERIALS 022600 -3
B. During the course of substance containment or evacuation of Project site personnel, protect personnel (onsite workers, non-workers, or the general public) from contact with or exposure to the released substances.
C. The abatement or evaluation of any suspected hazardous material shall only be performed by properly trained and/or certified personnel.
3.03 HEALTH AND SAFETY
A. In an emergency or imminent hazard situation the health and safety of personnel on or near the Project site are the responsibility of the Work of this section. Immediately notify the Owner office of Environmental Health and Safety (OEHS) and the OAR designated representative of the Owner Consultant. Owner representatives will notify Federal, State and Local regulatory authorities, if required.
B. Project site personnel or members of the general public who have been exposed to or have come in contact with any hazardous materials or chemicals shall be immediately transported to the nearest hospital.
3.04 TESTING, TRANSPORT, AND DISPOSAL OF HAZARDOUS SUBSTANCES A. Collect one composite sample from each media type (solid, liquid, or sludge) of potentially hazardous substance stored in drums, stockpiled, or otherwise identified at the Project site for the purposes of obtaining approvals for proper transport and disposal of the suspect materials. Submit analytical results to a representative of the Owner Consultant, as designated by the OAR.
B. If required, overpack any leaking or deteriorated drums to prevent leaks or spills, and pack small 5-gallon containers into larger new 55-gallon drums. Cover solid waste materials and stockpiled soils with an HDPE liner to prevent storm water runoff from contaminating surrounding areas.
C. Prepare manifests, material profiles, and submit lab analysis for drums/containers and any other documentation required by the receiving facility for signature by a representative of the Owner Consultant and/or Owner, as designated by the OAR. Copies of waste profiles, manifests, and disposal documentation shall be submitted to the OAR designated representative of the Owner, prior to disposal and/or transporting of hazardous substances.
D. Coordinate waste sampling and analysis requirements with the disposal facility and properly complete profiling and transport documents prior to loading and transport.
E. A State registered “Hazardous Waste Hauler” shall transport the waste to a lawfully permitted and Owner approved facility.
F. Prior to transport, a copy of the hazardous waste manifest shall be transmitted by facsimile, through the Projectsite Owner Consultant, to the Owner Office of Environmental Health and Safety (OEHS) for review and approval.
G. Load, handle, and transport 55-gallon drums and other waste containers to the appropriate disposal facility in accordance with Federal and State regulations.
H. Transport documentation from the receiving facility verifying acceptance and receipt of drums/containers at the facility and sampling and associated test resultsshall be submitted to
CIP 689 - Clark Building Renovations
ABATEMENT OF HAZARDOUS MATERIALS 022600 -4
the representative of the Owner Consultant, as designated by the OAR, within fifteen days following receipt of hazardous substances to the disposal facility.
I. Materials identified as hazardous wastes under RCRA are not permitted to remain at the Project site more than 30 days after being deemed to be a hazardous waste. During this period of Project site storage, provide precautions to contain and prevent the release of hazardous or potentially hazardous materials to the environment.
END OF SECTION
CIP 689 - Clark Building Renovations
SELECTIVE DEMOLITION 024119 -1
SECTION 024119 - SELECTIVE DEMOLITION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes the following:
1. Demolition and removal of selected portions of building orstructure.
2. Demolition and removal of selected site elements.
3. Salvage of existing items to be reused or recycled.
1.3 DEFINITIONS
A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.
B. Remove and Salvage: Detach items from existing construction and deliver them to Owner.
C. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated.
D. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.
1.4 SUBMITTALS
A. Qualification Data: For demolition firm.
B. Schedule of Selective Demolition Activities: Indicate the following:
1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. Ensure Owner's on-site operations are uninterrupted.
2. Interruption of utility services. Indicate how long utility services will be interrupted.
3. Coordination for shutoff, capping, and continuation of utility services.
4. Use of elevator and stairs.
5. Locations of proposed dust- and noise-control temporary partitions and means of egress.
6. Coordination of Owner's continuing occupancy of portions of existing building and of Owner's partial occupancy of completed Work.
7. Means of protection for items to remain and items in path of waste removal from building.
CIP 689 - Clark Building Renovations
SELECTIVE DEMOLITION 024119 -2
C. Inventory: After selective demolition is complete, submit a list of items that have been removed and salvaged.
D. Landfill Records: Indicate receipt and acceptance of hazardous wastes by a landfill facility licensed to accept hazardous wastes.
1. Comply with submittal requirements in Division 1 Section "Construction Waste Management."
1.5 QUALITY ASSURANCE
A. Demolition Firm Qualifications: An experienced firm that has specialized in demolition work similar in material and extent to that indicated for this Project.
B. Refrigerant Recovery Technician Qualifications: Certified by an EPA-approved certification program.
C. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
D. Standards: Comply with ANSI A10.6 and NFPA 241.
E. Pre-demolition Conference: Conduct conference at Project site to comply with requirements in Division 1 Section "Project Management and Coordination." Review methods and procedures related to selective demolition including, but not limited to, the following:
1. Inspect and discuss condition of construction to be selectively demolished.
2. Review structural load limitations of existing structure.
3. Review and finalize selective demolition schedule and verify availability of materials, demolition personnel, equipment, and facilities needed to make progress and avoid delays.
4. Review requirements of work performed by other trades that rely on substrates exposed by selective demolition operations.
5. Review areas where existing construction is to remain and requires protection.
1.6 PROJECT CONDITIONS
A. Notify Architect of discrepancies between existing conditions and Drawings before proceeding with selective demolition.
B. Hazardous Materials: It is known hazardous materials will be encountered in theWork.
1. Remove hazardous materials as part of this contract.
2. See Appendix for following Reports:
a. Asbestos Building Inspection
b. Lead Building Inspection
c. Asbestos Sample Analysis
C. Storage or sale of removed items or materials on-site is not permitted.
CIP 689 - Clark Building Renovations
SELECTIVE DEMOLITION 024119 -3
D. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.
1. Maintain fire-protection facilities in service during selective demolition operations.
1.7 WARRANTY
A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials so as not to void existingwarranties.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that utilities have been disconnected and capped.
B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.
C. Inventory and record the condition of itemsto be removed and reinstalled and itemsto be removed and salvaged.
D. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict.
Promptly submit a written report to Architect.
E. Engage a professional engineer to survey condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective demolition operations.
F. Perform surveys as the Work progresses to detect hazards resulting from selective demolition activities.
3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS
A. Existing Services/Systems: Maintain services/systems indicated to remain and protect them against damage during selective demolition operations.
1. Comply with requirements for existing services/systems interruptions specified in Division 1 Section "Summary."
B. Service/System Requirements: Locate, identify, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished.
1. Arrange to shut off indicated utilities with utility companies.
2. If services/systems are required to be removed, relocated, or abandoned, before proceeding with selective demolition provide temporary services/systems that bypass
CIP 689 - Clark Building Renovations
SELECTIVE DEMOLITION 024119 -4
area of selective demolition and that maintain continuity of services/systems to other parts of building.
3. Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit after bypassing.
a. Where entire wall is to be removed, existing services/systems may be removed with removal of the wall.
3.3 PREPARATION
A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Comply with requirements for access and protection specified in Division 1 Section "Temporary Facilities and Controls."
B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
1. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building.
2. Provide temporary weather protection, during interval between selective demolition of existing construction on exterior surfaces and new construction, to prevent water leakage and damage to structure and interior areas.
3. Protect walls, ceilings, floors, and other existing finish work that are to remain or that are exposed during selective demolition operations.
4. Cover and protect furniture, furnishings, and equipment that have not been removed.
5. Comply with requirements for temporary enclosures, dust control, heating, and cooling specified in Division 1 Section "Temporary Facilities and Controls." C. Temporary Shoring: Provide and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.
1. Strengthen or add new supports when required during progress of selective demolition.
3.4 SELECTIVE DEMOLITION, GENERAL
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:
1. Proceed with selective demolition systematically, from higher to lower level. Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level.
2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping, to minimize disturbance of adjacent surfaces. Temporarily cover openings to remain.
3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.
CIP 689 - Clark Building Renovations
SELECTIVE DEMOLITION 024119 -5
4. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain fire watch and portable fire- suppression devices during flame-cutting operations.
5. Maintain adequate ventilation when using cutting torches.
6. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and promptly dispose of off-site.
7. Remove structural framing members and lower to ground by method suitable to avoid free fall and to prevent ground impact or dust generation.
8. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.
9. Dispose of demolished items and materials promptly. Comply with requirements in Division 1 Section "Construction Waste Management."
B. Removed and Salvaged Items:
1. Clean salvaged items.
2. Pack or crate items after cleaning. Identify contents of containers.
3. Store items in a secure area until delivery to Owner.
4. Transport items to Owner's storage area designated by Owner.
5. Protect items from damage during transport and storage.
C. Removed and Reinstalled Items:
1. Clean and repair items to functional condition adequate for intended reuse. Paint equipment to match new equipment.
2. Pack or crate items after cleaning and repairing. Identify contents of containers.
3. Protect items from damage during transport and storage.
4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.
D. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Architect, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.
3.5 DISPOSAL OF DEMOLISHED MATERIALS
A. General: Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Owner's property, remove demolished materials from Project site and legally dispose of them in an EPA-approved landfill.
1. Do not allow demolished materials to accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
3. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.
4. Comply with requirements specified in Division 1 Section "Construction Waste Management."
B. Burning: Do not burn demolished materials.
CIP 689 - Clark Building Renovations
SELECTIVE DEMOLITION 024119 -6
C. Disposal: Transport demolished materials off Owner's property and legally dispose of them.
3.6 CLEANING
A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.
END OF SECTION 024119
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -1 SECTION 02 8213 - ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE PART 1 – GENERAL
1.01 SUMMARY
A. Section Includes:
1. Abatement of building and/or structure related Asbestos.
2. Removal of building and/or structure related Asbestos.
3. Disturbance of building and/or structure related Asbestos.
B. Related Requirements:
1. Section 00 3126 - Existing Hazardous Material Information
2. Division 01 - General Requirements.
3. U.S. Environmental Protection Agency Regulations for Asbestos (Title 40, Code of Federal Regulations, Part 61, Subparts A and B, and Part 763, Subpart E.)
4. Title 8, Article 4, California Code of Regulations Construction Industry Safety Orders, Section 1529 "Asbestos" or current revised California regulations.
5. South Coast Air Quality Management District (SCAQMD) Rule 1403.
1.02 SECTION DEFINITIONS AND ACRONYMS
A. Abatement – Procedures to control fiber release from Asbestos Containing Materials or Asbestos Containing Construction Materials. Includes Removal, Encapsulation, Enclosures, Repair, Demolition, and Renovation activities but does not include Asbestos Related Disturbance.
B. AHERA - Asbestos Hazard Emergency Response Act, 40 CFR, Part 763, Subpart E, and subsequent amendments.
C. Air Filtration and Ventilation System - A portable exhaust system, equipped with HEPA filtration, and capable of maintaining a constant air flow into a Regulated Area from adjacent areas and exhausted outside the Regulated Area.
D. Amended Water - Water to which a surfactant (wetting agent) has been added.
E. ANSI - American National Standards Institute.
F. Asbestos - Means the asbestiform varieties of chrysotile (Serpentine); crocidolite (Riebecktite); amosite (cummingtonitegrunerite); anthophyllite; tremolite; and actinolite.
G. Asbestos Containing Construction Material (ACCM) – Means any manufactured construction material which contains more than one tenth of one percent (0.1 percent) Asbestos by weight.
H. Asbestos Containing Material (ACM) – Means any material containing more than one percent (1 percent) Asbestos.
I. Asbestos Containing Waste (Non-hazardous) – Non-Friable Asbestos Containing Material including, but not limited to, floor covering, roofing materials and cementitious materials requiring disposal.
J. Asbestos Containing Waste (Hazardous) – Friable Asbestos Containing Materials and Asbestos contaminated objects and debris requiring disposal.
K. Asbestos Related Disturbance – is the drilling, coring, removal or similar disturbance of ACCM or ACM not to exceed three square feet in any one opening and not to disturb 100 square feet or greater cumulatively on any one project (contract).
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -2 L. ASTM - American Society for Testing and Materials.
M. Building ID Number or Code - A six-digit alphanumeric identification code assigned to each building on an Owner site, also referred to as the insurance code, ID number or similar terms.
N. Bulk Samples - Samples of building or other materials collected for analysis to determine the presence and quantities of Asbestos.
O. Class I, II, III, and IV asbestos work has the meaning as defined in California Code of Regulations Title 8, Section 1529.
P. Clean Room - An uncontaminated area or room, which is a part of the worker Decontamination Enclosure System with provisions for storage of worker's street clothes and clean protective equipment.
Q. Competent Person - Has the same meaning as defined in the California Code of Regulations Title 8, as it relates to, "Competent Person."
R. Controlled Disturbance – An activity by which a contractor disturbs an asbestos containing material or an asbestos containing construction material using the work practices allowed for in this specification and in compliance with regulatory limitations.
S. Curtained Doorway – A device to allow ingress and egress from one room to another while permitting minimal air movement between the rooms, typically constructed by placing two overlapping sheets of plastic over an exiting or temporarily framed doorway, securing each along the top of the doorway, securing the vertical edge of one sheet along one vertical side of the doorway and securing the vertical edge of the other sheet along the opposite vertical side of the doorway. Other effective designs may be submitted for review.
T. Decontamination – The process of eliminating Asbestos contamination from building surfaces, objects, and property, by cloths, mops, or other utensils dampened with water and disposed of afterwards as Asbestos contaminated waste.
U. Decontamination Enclosure System – Means an enclosed area, which is adjacent and connected to the Regulated Area, consisting of an Equipment Room, Shower Room, and Clean Room for the Decontamination of workers, materials, and equipment contaminated with Asbestos.
V. Demolition - The wrecking or taking out of any load supporting structural member of a facility together with any related handling operations.
W. DOSH - Division of Occupational Safety & Health or Cal/OSHA.
X. DOT – Department of Transportation.
Y. DTSC – Department of Toxic Substances Control.
Z. Encapsulating Material - A liquid material applied to Asbestos Containing Materials which controls the possible release of Asbestos fibers from the material either by creating a membrane over the surface (bridging agent) or by penetrating into the material and binding its components together (penetrating Encapsulating Material).
AA. Encapsulation - The application of an Encapsulating Material to Asbestos Containing Materials to prevent the release of Asbestos fibers into the air.
BB. Enclosure - The construction or application of an airtight, impermeable, permanent barrier around Asbestos Containing Material to control the release of Asbestos fibers into the air.
CC. Equipment Room - A room within the worker Decontamination Enclosure System with provisions for storage of used clothing and equipment and for controlled transfer of materials and equipment into and out of the regulated area.
DD. Facility Component – Means any part of a facility including equipment.
EE. FETU - Facilities Environmental Technical Unit.
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -3 FF. Fixed Object - A piece of equipment, furniture, or improvement in the Work area, which cannot be removed from the Work area.
GG. Friable Asbestos - Asbestos Containing Material which, when dry, can be crumbled, pulverized or reduced to a powder by hand pressure or as defined by current regulations.
HH. Glove Bag Technique - A method with limited applications for removing small amounts of Asbestos Containing Material from short piping runs, valves, joints, elbows, and other non-planar surfaces in a Work area. The glove bag assembly is a manufactured or fabricated device consisting of a glove bag (typically constructed of 6 mil transparent polyethylene or polyvinyl chloride plastic), two inward projecting long sleeves gloves, an internal tool pouch, and labeled for Asbestos waste. The glove bag is constructed and installed in such a manner that it surrounds the object or material to be removed and contains asbestos fibers released during the process. Workers who are permitted to perform the Glove Bag Technique shall be thoroughly trained, experienced, and skilled in this method.
II. Hazardous Waste - Means Friable Asbestos generated and prepared for waste disposal. Does not include non-friable material or materials containing one-percent or less of Asbestos as determined by PLM and/or the point counting method.
JJ. HEPA Filter - Means a filtering system capable of trapping and retaining at least 99.97 percent of monodispersed particles 0.3 microns in diameter or larger. For respirators this shall include NIOSH rated P100 cartridges only.
KK. HEPA Vacuum - A vacuum system furnished with HEPA filtration.
LL. High Volume Vacuum - A vacuum system with the capacity to collect material through a four inch diameter hose a minimum distance of 150 feet. This system shall be furnished with HEPA Filter at the air exhaust port and water applicators within the hopper.
MM. HVAC – Heating, Ventilation, and Air Conditioning System.
NN. Location Code - Refers to a unique four digit numeric code assigned by the Owner to each of its Project sites.
OO. Lockdown Coat – A material applied to surfaces where Asbestos has been completely removed. The manufacturer shall determine the concentration of this material.
PP. Member – A component part of a structure complete in itself.
QQ. Movable Object - A portable piece of equipment or furniture in the Work area, which can be removed from the Work area.
RR. NESHAP - National Emission Standards for Hazardous Air Pollutants (40 CFR Part 61).
SS. NIOSH - National Institute for Occupational Safety and Health.
TT. Outside Air - Air outside of buildings and structures.
UU. Owner Consultant (OC) - Refers to the firm, company or individual designated by the Owner.
VV. PCM - Phase Contrast Microscopy as it relates to clearance air, personnel exposure assessment, and ambient air monitoring. This procedure must follow the NIOSH Method 7400, Asbestos Fibers by PCM.
WW. PLM - Polarized Light Microscopy used for bulk sample analysis with dispersion staining for the determination and quantifying of Asbestos in Bulk Samples building materials.
XX. Regulated Area - Designated rooms, spaces or areas of the Project in which asbestos Abatement actions are to be performed or which may become contaminated as a result of Abatement activities. A contained Work area is a Work area, which has been sealed and furnished with a Decontamination Enclosure System. A non-contained Work area is an isolated or controlled access Work area, which has not been sealed or furnished with a Decontamination Enclosure System.
YY. Removal – Means operations where ACM and/or PACM is removed or stripped from structures or substrates including Demolition.
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -4 ZZ. Renovation – Means the modifying of any existing structure, facility, or portion thereof.
AAA. SCAQMD – South Coast Air Quality Management District.
BBB. Shower Room - A room between the Clean Room and the Equipment Room in the worker Decontamination Enclosure System furnished with hot and cold running water controllable at the tap, and suitably arranged for complete showering during Decontamination.
CCC. Small Scale Short Duration – Such work not to exceed amounts greater than those which can be contained in a single glove bag or may not exceed amounts which can be contained in a single prefabricated minienclosure. Such an enclosure shall conform spatially and geometrically to the localized work area, in order to perform its intended containment function, and as completely defined in 40CFR, 763, Subpart E, Appendix C.
DDD. Staging Area - Areas near the Waste Transfer Airlock where containerized Asbestos waste is temporarily placed prior to permanent removal from the Work area.
EEE. Surfactant - A chemical wetting agent added to water.
FFF. TEM - Transmission Electron Microscopy as defined for Asbestos clearance air monitoring within AHERA. This procedure must follow the NIOSH Method 7402, Asbestos Fibers by TEM.
GGG. TSI - Thermal System Insulation as defined in AHERA.
HHH. USEPA or EPA – United States Environmental Protection Agency.
III. Visible Emissions - Any emissions from a known or suspected Asbestos Containing Material that is visually discernible.
JJJ. Waste Transfer Airlock - A Decontamination system provided for transferring containerized waste from inside to outside of the Work area.
1.03 POLICIES AND PROCEDURES
A. The Owner has a zero-tolerance policy for uncontrolled Asbestos releases during construction or Abatement Work. An Asbestos release requiring an emergency response is any uncontrolled release of Asbestos Containing Construction Materials. The Owner shall be immediately notified of such uncontrolled releases.
B. Pre-qualified Asbestos Abatement Subcontractors are not permitted to subcontract any Abatement work to a lower tier Subcontractor without the prior written approval of the Owner.
C. Where ACM is damaged or disturbed, except during Controlled Disturbance or Abatement, Work in that room shall cease, the room be vacated immediately, the Owner Consultant notified of the disturbance with corrective action provided as required by the Owner Consultant.
1.04 ROLES AND RESPONSIBILITIES
A. Roles and Functions:
1. Coordinate the Work of this section directly with the Owner and/or Owner Consultant.
2. Work under this section shall be performed in strict accordance with applicable Federal, State, and Local regulations, standards, and codes governing asbestos Abatement and any other Work performed in conjunction with the Asbestos Abatement Work.
3. The most recent edition of any relevant regulation, standard, document, or code is in effect.
Where conflict among the requirements or with this Specification exists, the most stringent requirement shall be provided.
1.05 SITE SECURITY
A. The Work area shall be restricted to authorized, trained, and protected personnel. A list of authorized personnel shall be established by the Owner Consultant prior to commencement of the Work and posted at the entrance of the Regulated Area.
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -5 B. Report to the Owner Consultant any unauthorized entry into the Regulated Area. Following notification, a written report of the incident shall be provided to the Owner Consultant.
C. A logbook shall be maintained at the entrance of the Regulated Area. Persons entering the Regulated area shall record their name, company affiliation, time in, and time out for each entry and exit.
D. Access to the contained area shall be through the worker Decontamination Enclosure System or other room established when worker Decontamination Enclosure System is not required. Other means of access shall be blocked or locked to prevent entry to or exit from the Work area. The only exceptions are the waste pass-out airlock, which shall be sealed except during the Removal of containerized Asbestos waste from the Work area, and emergency exits in case of fire or accident. Emergency exits shall be operable from inside the Work area; however they shall be sealed with polyethylene sheeting and tape.
E. Maintain Regulated Area security during Abatement Work. Regulated Areas and ancillary equipment accessible to non-authorized personnel shall be protected from unauthorized access by constructing a minimum barrier of 3/8 inch CDX plywood supported by 2 by 4 studs, 16 inches on center. Height shall be as required to safely access Regulated Area. An access door shall be provided with hasp and padlock sufficient to prevent unauthorized entry. A key shall be provided to the Owner and Owner Consultant.
Required barriers within an occupied building shall be furnished with sheathing as required by state and local fire protection regulations.
F. The protective barrier for a High Volume Vacuum shall be a minimum of eight feet in height. Barriers for these systems may be constructed of chain link type fencing instead of the specified barriers. Such fencing, if provided, shall be covered with an opaque covering resistant to environmental conditions.
This barrier system shall be maintained at times while the enclosed equipment is on the Project site.
G. Unless otherwise specified, remove barriers upon completion of the Work of this section. Repair and/or replace to original condition, damage resulting from installation, use, and removal of the barriers.
1.06 EMERGENCY PLANNING
A. Emergency planning and procedures shall be developed, submitted, reviewed, and agreed to by the Owner prior to the commencement of Abatement Work.
B. Emergency procedures shall be provided in the written languages understood by employees working on the Project and shall be prominently posted at the entrance of the Decontamination Enclosure System.
Prior to entering the Work area, parties must read and sign these procedures to acknowledge receipt and understanding of the Work site layout, location of emergency exits, and emergency procedures.
C. Emergency planning shall consider the effects of fire, explosion, toxic atmospheres, electrical hazards, slips, trips and falls, confined spaces, and heat related injury. Develop and provide written procedures and training to employees.
D. Employees shall be trained in evacuation procedures in the event of workplace emergencies.
E. In the event of non-life-threatening situations requiring medical treatment, injured or otherwise incapacitated employees shall decontaminate following normal procedures with assistance from fellow workers if necessary, before exiting the Work area.
F. In the event of life-threatening injury or illness requiring immediate medical treatment, worker Decontamination shall be given minimum priority. Provide measures to stabilize the injured worker, remove them from the Work area and secure proper medical treatment.
G. Telephone numbers of emergency response personnel shall be prominently posted at the entrance of the Decontamination Enclosure System along with the location of the nearest telephone. In addition to the 911 emergency number, post the address and telephone number of the nearest emergency medical services provider.
H. Provide at least one employee on the Project site at times during progress of Abatement work that is trained and certified in first aid and cardiopulmonary resuscitation (CPR). This employee shall be
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -6 identified by name and proof of training shall be provided to the Owner Consultant prior to the commencement of the Work of this section.
I. Provide at least one 4A/60BC dry chemical extinguisher in the Equipment Room and one at each corner of contained areas in excess of 1,000 square feet. Workers shall be trained in the proper operation of fire extinguishers.
J. Emergency exits shall be provided and clearly marked with arrows or other clearly visible markings to permit easy identification from anywhere within the Work area. Exits shall be secured to prevent access from uncontaminated areas while still permitting emergency egress. Exits shall be properly sealed with polyethylene sheeting, which can be cut to permit emergency egress. Emergency exits may lead through the worker Decontamination Enclosure, the waste removal airlock or other alternative exits as required by fire officials.
1.07 LICENSING
A. The Work of this section shall be performed by an entity duly licensed in the State of California in accordance with the provisions of Chapter 9 of Division 3 of the Business and Professions Code, as amended. The Abatement work of this section shall be performed by an entity holding a license with an “ABS” Asbestos Certification as issued by the Contractors State License Board.
B. The entity performing the Work of this section, other than Asbestos Related Disturbance involving less than 100 square feet shall be registered with the Department of Industrial Relations in accordance with the provisions of Section 6501.5 of the California Labor Code.
1.08 ASBESTOS RELATED REQUIREMENTS
A. Qualifications:
1. Comply with the provisions of the California Labor Code, Division 5, Part 1, as it pertains to safety in employment and the applicable provisions of Title 8, Chapter 4, Subchapters 1 through 21, California Code of Regulations (CCR) as it pertains to Occupational Safety and Health, and Subchapter 7, Section 5208 Article 4, and Section 1529, Asbestos regulations.
2. Where Electrical Work is required in a Regulated Area this work shall be performed as required in Division 16 and personnel who enter a Contained and Regulated Class I and II Asbestos work area are required to possess a current EPA certification as an Asbestos worker.
Personnel who enter a Class III Asbestos Related Disturbance work area shall require personnel trained in accordance with AHERA Operations and Maintenance training requirements.
B. Abatement Activities:
1. The Asbestos Abatement work shall be performed by persons who comply with applicable Federal, State, and local regulations including AHERA certified training.
2. Supply labor, materials, services, insurance, permits, and equipment necessary to perform the Work in accordance with applicable Federal, State, and Local regulations and this Specification.
3. For Class I asbestos work, collect pre-Abatement air samples. Results shall be submitted prior to commencement of the Work of this section. Include location of Samples, name of air sampling professional, equipment, and methods utilized for sampling and analysis.
4. Submit weekly job progress reports detailing Abatement activities for Projects with schedules that exceed thirty days of Abatement work. Include review of progress with respect to previously established Milestones and schedules, major problems and action taken, injury reports, equipment breakdown, and air sampling results.
5. Within five workdays of transport and/or disposal, submit copies of transport manifests, disposal receipts, and weight certificates for Asbestos waste removed from the Work area
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -7 during the Abatement process. Weight certificates shall indicate in pounds the net weight of waste disposed from the Project site as indicated on the manifest.
6. Submit copies on a daily basis of the Work site entry logbooks.
7. Submit logs on a weekly basis documenting filter changes on respirators, HEPA Vacuums, HEPA Filtered ventilation units, water filtration units, and other approved engineering controls.
8. Submit results of materials testing conducted during Asbestos Abatement work for purposes of utilization during such activities. (i.e., depth test, substitution materials, etcetera).
9. Where Decontamination Enclosure System is required, post at the entrance a list containing the names, addresses, and telephone numbers of the entity performing the Work of this section, designated Competent Person, the Owner and/or Owner Consultant, the testing laboratory and any other personnel who may be required to access the Work area or perform services during the Abatement Work.
10. For employee review, post at the entry of the Work area a copy of the scope of Work, special conditions, the current standard Specifications, and the applicable prevailing wage.
C. Asbestos Related Disturbance:
1. The Asbestos Related Disturbance Work shall be performed by persons who comply with applicable Federal, State, and local regulations including AHERA certified training.
2. Within ten days of analysis, submit results of air sampling data collected for Cal/OSHA compliance air monitoring during the course of the Asbestos Related Disturbance (Class III asbestos work). If this data is used to discontinue use of employee protective equipment then the data shall be provided before discontinuing use of protective equipment.
3. Within five workdays of transport and/or disposal of Asbestos Containing Waste, submit copies of transport manifests and/or disposal receipts.
1.09 SUBMITTALS
A. Provide in accordance with Division 01 and this section.
B. Prior to commencement of the Asbestos Abatement work of this section, submit the following notices, documentation, Shop Drawings, and Product Data:
1. For Projects involving Asbestos Containing Materials 100 square feet or more, provide a typed written notification in accordance with Rule 1403 of SCAQMD and 40 CFR Part 61.146 of Subpart M to the SCAQMD, and to and in accordance with the Division of Occupational Safety and Health prior to start of the Work.
2. Submit to the Owner, satisfactory proof the required permits, site location, and arrangements for transport and disposal of Asbestos Containing Waste materials have been completed in accordance with California Health and Safety Code, Section 25143.7. Obtain and submit a copy of handling procedures and a list of protective equipment utilized for Asbestos disposal at the landfill.
3. Submit to the Owner satisfactory documentation that employees, including foremen, supervisors, and any other company personnel or agents who may be exposed to airborne Asbestos fibers or who may be responsible for any aspects of Asbestos Abatement work or Asbestos Related Disturbance have received adequate training that includes, at a minimum, information as described within this section and as required by AHERA.
4. Prior to commencement of Abatement Work, personnel required to construct and enter the Work area or handle containerized Asbestos Containing Materials shall have received adequate training, in accordance with the requirements of this Specification and by 40 CFR, Part 763, Subpart E (AHERA) and Title 8, Section 1529, of the California Code of Regulations applies.
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -8
5. Special Project site training for equipment and procedures unique to this Project site shall be provided as required.
6. Training in emergency response and evacuation procedures shall be provided to personnel performing Asbestos Abatement work of this section.
7. Submit documentation from a physician certifying that employees are medically monitored and are physically capable of working while wearing the required respiratory protection without suffering adverse health effects as required by California D.O.S.H regulations. Where such documentation is required, the certification shall state that the employee or agent is approved to work with Asbestos and wear a respiratory protection without restrictions.
Provide information to the examining physician about unusual conditions in the workplace environment that may impact on the employee's ability to perform Abatement Work activities.
8. Submit Shop Drawings for layout and construction of Decontamination Enclosure Systems and barriers for isolation of the contained Asbestos Abatement work area as detailed in this Specification and required by applicable regulations.
9. When used, submit manufacturer's certification that HEPA Vacuums, air filtration units, and other local exhaust ventilation equipment complies with ANSI Z9.2.
10. Submit Product Data verifying that air filtration devices (i.e., air filtration units and vacuums) for use on this project have been registered or certified, as applicable, in compliance with the SCAQMD Rules.
11. If rental equipment is to be furnished in Abatement Work areas or to transport Asbestos contaminated waste, written notification concerning the intended use of the rental equipment shall be provided to the rental agency with a copy submitted to the Owner.
12. Document NIOSH approvals for respiratory protective devices furnished as required by the Work. Include manufacturer certification of HEPA filtration capabilities for cartridges and filters.
13. Submit documentation of respirator fit testing for employees and agents entering the Abatement work area or areas where respiratory protection is required. This fit testing shall be performed in accordance with DOSH regulations.
14. Submit a Sample of forms to be used in documenting required items to be submitted and/or reviewed.
C. Provide other required submittals specified as part of the Work of this section.
1.10 PRE-ABATEMENT MEETING
A. Attend a meeting to be held prior to the commencement of Abatement Work. Attending this meeting shall be representatives of the Owner, the Owner Consultant if applicable, and the testing/monitoring personnel who shall actually participate in the testing/monitoring program. Secure the attendance of the individual who will be the Project site Competent Person for the Abatement Work.
B. Included in the general preconstruction meeting will be a discussion of requirements and submittals for Asbestos Related Disturbance, where such applies.
C. At this meeting provide required submittals except for those to be submitted during progress of the Work.
In addition, provide detailed information concerning:
1. Preparation of Work area and Shop Drawings. (Abatement Only).
2. Personal protective equipment, including respiratory protection and protective clothing. (Abatement, and Asbestos Related Disturbance if required).
3. Employees who will participate in the Project, including delineation of experience, training, and assigned responsibilities during the Work. (Abatement and Asbestos Related Disturbance).
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -9
4. Decontamination procedures for personnel, Work area, and equipment. (Abatement and Asbestos Related Disturbance).
5. Abatement methods and procedures to be provided. (Abatement Only).
6. Required air monitoring procedures (pre-Abatement and SCAQMD requirement [Abatement Only], and Cal/OSHA mandatory [Abatement and Asbestos Related Disturbance]).
7. Procedures for handling and disposing of waste materials, including disposal facility. (Abatement and Asbestos Related Disturbance).
8. Procedures for final Decontamination and cleanup. (Abatement Only).
9. A sequence of Work activities and performance schedule. (Abatement Only).
10. Procedures for dealing with heat stress. (Abatement Only).
11. Emergency procedures. (Abatement Only).
1.11 CLOSE OUT DOCUMENTATION
A. Provide the following close out documentation:
1. Filter change logs for air filtration units, water filtration units and respirators. (Abatement Only).
2. Foreman's daily job reports. (Abatement Only).
3. Employee entry/exit logs for containment. (Abatement Only).
4. Visitor entry/exit logs for containment. (Abatement Only).
5. Manometer printout reports for applicable containment. (Abatement Only).
6. Air sample results for personnel (Abatement and Asbestos Related Disturbance).
7. Air Samples for Abatement Work areas and air filtration units. (Abatement Only).
8. Copies of hazardous and non-Hazardous Waste manifests. (Abatement and Asbestos Related Disturbance).
9. Hazardous Waste weight tickets. (Abatement Only).
10. Signed Daily Personnel Report Forms. (Abatement Only).
11. Signed code of conduct form from each employee working on a Project. (Abatement Only).
12. Signed asbestos Abatement Project Personnel Logs. (Abatement Only).
B. Receipt of the last workday attendance log and the daily personal monitoring results shall be submitted within two days upon completion of the Abatement Work of this section.
PART 2 – PRODUCTS
2.01 Materials and Equipment:
A. Materials
1. Products: The following products have been specifically approved for use as encapsulants/lockdown or bridging agents for Owner asbestos abatement and asbestos related construction projects and lead abatement and lead related construction projects. Products not approved by the Owner shall not be used.
a. Asbestos Removal Encapsulant: Foster 32-60 blue by Foster Products Corporation; removal, lock down or penetrating with dilution.
b. Asbestos Bridging Encapsulant: Foster 32-80 by Foster Products Corporation; for pipe covering and boiler lagging.
c. A-B-C Fiberspray 6410 and 6422SP by Fiberlock Technologies, Inc.; for coring, small jobs and gloves bags.
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -10 d. A-B-C Asbestos Binding Compound 6421, 6422 and 6423 by Fiberlock Technologies, Inc.; for general use, removal, lock down, penetrating and bridging; good for soils. e. Fiberset PM 7475 clear by Fiberlock Technologies, Inc.; compatible with flooring. f. Fiberset PM 7470 white by Fiberlock Technologies, Inc.; compatible with flooring. g. Lag-Kote by Fiberlock Technologies, Inc.; multi-use product including fireproofing and thermal system insulation.
h. Lag-Klothe by Fiberlock Technologies, Inc.;water activated repair cloth for pipes, boilers and breaching.
2. General:
a. Deliver materials in the original sealed packages, containers, or bundles bearing the name of the manufacturer and brand name.
b. Store materials subject to damage off the ground, away from wet or damp surfaces, and under cover sufficient enough to prevent damage or contamination. Replacement materials shall be stored outside of the Abatement Work area until area is cleared for normal occupancy.
c. Damaged, deteriorating or previously used materials shall not be furnished and shall be removed from the Project site and legally disposed of.
d. A sufficient supply of disposable mops, rags, and sponges for Abatement Work area Decontamination shall be provided.
e. Unless otherwise specified, the Owner will provide water and power for construction purposes. Connect to existing system as required.
3. Asbestos Related:
a. Plastic, polyethylene sheeting or visqueen shall be a fire retardant type. Provide documentation from the manufacturer verifying compliance with this requirement. b. Where a contained work area is required for Abatement Work, a minimum of two layers of 4-mil polyethylene sheeting shall be installed for walls. For floors and other installations, polyethylene sheeting of at least 6-mil thickness shall be furnished in sufficient widths to minimize the frequency of joints.
c. Method of attaching polyethylene sheeting shall be reviewed prior to installation and/or commencement of Abatement Work. Method of attaching polyethylene sheeting shall not cause damage to equipment, finish surfaces, or other property. d. Polyethylene sheeting furnished for the Decontamination Enclosure System shall be opaque white or black in color and shall be a minimum of 6-mil thick. e. Disposal bags shall be of 6-mil polyethylene, with the outer bag pre-printed with labels as required by SCAQMD and applicable Cal/OSHA and DOT requirements at a minimum.
f. Apply labels as per SCAQMD, Cal/OSHA, and DOT requirements for disposal containers.
g. Provide warning signs as required by CAL/OSHA.
h. Surfactant (wetting agent) shall be a material that, when tested, demonstrates a surface tension of 29 dynes/cm as tested in its properly mixed concentration, using ASTM method D1331 - Surface and Interfacial Tension of Solutions of Surface Active Agents.
Where Work area temperature may cause freezing of the Amended Water solution, the addition of approved antifreeze in a manufacturer recommended amount is permitted.
B. Equipment
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -11
1. General:
a. Equipment delivered to the Project site shall be free of Asbestos and/or fibrous debris.
No equipment with Asbestos and/or fibrous debris in or on it is permitted on Owner properties.
b. Provide sufficient lighting to illuminate the Work area for safe visual working conditions and to clearly examine surfaces.
c. Provide a sufficient supply of scaffolds, ladders, lifts, and hand tools that meet applicable Federal, State, and local regulations.
d. Provide non-metallic dustpans, squeegees, and shovels for cleanup.
2. Asbestos Related:
a. A sufficient quantity of air filtration ventilation units furnished with HEPA filtration and operated in accordance with ANSI Z9.2-79 and EPA guidance documents shall be furnished to provide one workplace air change every 15 minutes creating -0.02 column inches of water pressure differential everywhere within the contained area when compared to the pressure outside the area. For small Enclosures and glove bags, a HEPA Filtered vacuum system may be furnished to provide the pressure differential. A log documenting the filter change history of each unit is required before use. Any unit without this log shall have filters changed and the unit decontaminated. b. Provide a printable manometer for determining and recording the pressure differential within the isolated Work area as compared with the ambient environment. A printed record is required for the duration of the Project. The manometer shall operate 24 hours per day with a printed differential reading not to exceed fifteen minute intervals. c. High volume vacuum equipment shall be provided during soil Removal operations unless otherwise specified.
d. Provide sprayers with pumps in a quantity capable of providing Amended Water in sufficient quantities to adequately wet materials during Asbestos Abatement activities.
Provide spray bottles or adequate equipment necessary to keep materials impacted by Asbestos Related Disturbance adequately wet.
e. Non-skid footwear shall be worn by Abatement workers. Disposable clothing shall be adequately sealed to the footwear to prevent body contamination. f. Provide other required safety equipment to workers and authorized visitors. g. When roll-off disposal containers are delivered to a Project site, four wheels of each container shall be moved and rested upon a sheet of plywood no smaller than four-foot by four-foot by ¾ inch minimum.
2.02 EMPLOYEE PERSONAL PROTECTIVE EQUIPMENT
A. Respiratory Protection:
1. Where respirators are required these shall be provided for protection from particulate contaminants as required by the National Institute of Occupational Safety and Health.
2. The respirators provided shall furnish a protection factor as required by CCR Title 8, Section 1529 for the fiber concentration in the work area. When powered air purifying respirators are provided, a sufficient supply of charged replacement batteries, filters, and a flow test meter shall be provided in the Clean Room area. Air purifying respirators with dual HEPA Filters may be provided during Work area preparation activities.
3. Provide spectacle kits and eyeglasses for employees who wear glasses and must wear full-face respirators.
B. Fit Testing:
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -12
1. Workers must perform positive and negative air pressure fit tests each time a respirator is donned, whenever the respirator design so permits. Powered air purifying respirators shall be tested for adequate flow as specified by the manufacturer.
2. Workers shall be undergo a qualitative fit test in accordance with procedures detailed in the D.O.S.H. requirements for respirators provided to comply with the requirements of this Project.
An appropriately administered quantitative fit test may be substituted for the qualitative fit test.
3. Where respirators are required, documentation of adequate respirator fit must be provided to the Owner Consultant.
4. No one wearing a beard shall be permitted to don a respirator and enter the Work area.
5. Where respirators are required, a minimum of two additional respirators of each type and training on their donning and use must be provided at the Work site for authorized visitors required to enter the Work area.
C. Protective Clothing:
1. Where protective clothing is required, full body disposable protective clothing, including head, body, and foot coverings, shall be provided to workers and authorized visitors in sizes adequate to accommodate movement without tearing.
2. Disposable clothing including head, foot, and full body protection shall be provided in sufficient quantities and adequate sizes for workers and authorized visitors.
3. A new suit shall be donned upon each entry to the Abatement Work area or area where the permissible exposure level will be exceeded.
4. Hard hats, protective eye wear, gloves, rubber boots and/or other footwear shall be provided as required for workers and authorized visitors. Safety shoes may be required and shall be provided.
PART 3 - EXECUTION
3.01 ABATEMENT PROCEDURES AND WORK AREA PREPARATION
A. Work Area Preparation
1. For Class I and II asbestos work, shut down and lock out heating, cooling and air conditioning system (HVAC) components that are located in, supply, or pass through the Work area. Seal intakes and exhaust vents in the Work area with tape and 6-mil polyethylene. Seal seams in any system components that pass through the Work area.
2. Provide and postsigns at locations and approachesto the Regulated Area. The signsshall comply with Cal/OSHA regulations.
3. In conjunction with the Owner, shut down and lock out/tag out electric power to Class I and II asbestos work areas. Provide equipment for temporary power with ground fault interrupters and lighting sources. Temporary power sources and equipment shall comply with applicable electrical code requirements and Cal/OSHA requirements for temporary electrical systems. The Owner shall perform electrical connections of electrical cable and equipment provided as part of the Work of this section to existing Owner systems. The Owner shall pay for the costs of electric power consumed during performance of the Work of thissection, unless otherwise noted.
4. For Class I and II asbestos work, clean and seal off windows, doorways, elevator openings, corridor entrances, drains, ducts, grills, grates, diffusers, skylights, and any other openings between the Abatement Work area and areas outside of the Abatement Work area with 6-mil polyethylene sheeting and tape prior to proceeding with required cleaning.
5. Clean Movable Objects within the Abatement Work area with a HEPA Filtered vacuum and wet cleaning methods. After cleaning, these objects shall be removed from the Abatement work area and carefully stored in a location designated by the Owner.
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -13
6. Clean Fixed Objects in the Abatement Work area with a HEPA Filtered vacuums and wet cleaning methods. Careful attention shall be given to machinery behind grills or gratings where access may be difficult but contamination is present. Cleaning of walls, floors, and ceilings behind fixed items is required. After cleaning, enclose Fixed Objects in 6-mil polyethylene sheeting and seal securely in place with durable tape.
7. Clean surfaces in the Abatement Work area with a HEPA Filtered vacuums and wet cleaning methods. Do not utilize any methods, such as dry sweeping or vacuuming, with equipment not furnished with HEPA Filters thereby creating airborne dust and particulates. Do not disturb Asbestos Containing Materials during this cleaning phase.
8. For Class I and II asbestos work, floors shall be covered with two layers of 6-mil (minimum) polyethylene sheeting. Additional layers of sheeting may be furnished as drop cloths for cleanup of bulk materials.
9. Polyethylene sheeting shall be sized and installed to minimize seams. If the floor area to be covered requires seaming, seams on successive layers of polyethylene sheeting shall be staggered a minimum of six feet between each seam to reduce the potential for water penetration into the existing flooring. Do not install seams at the junction between a wall and floor.
10. Polyethylene sheeting installed on a floor shall extend at least 12 inches up the sidewalls of the Abatement Work area.
11. Polyethylene sheeting shall be installed so as to prevent slippage between successive layers of installed material.
12. For Class I and II asbestos work, walls shall be covered with two layers of 4-mil minimum thickness polyethylene sheeting.
13. Polyethylene sheeting installed on a wallshall overlap floorsheeting by at least 12 inches beyond the wall/floor joint to provide a seal against water damage.
14. Polyethylene sheeting installed on a wall shall be adequately fastened to prevent it from falling away from the walls. Provide additional support/attachment when air filtration ventilation systems are provided.
15. For Class I and II asbestos work with porous, dropped, or perforated ceilings, those ceilings shall be covered with one layer 4-mil minimum thickness polyethylene sheeting.
16. Polyethylene sheeting installed on ceilings shall be adequately fastened to prevent it from falling away from the ceiling.
17. Provide one layer of 3-mil maximum, polyethylene sheeting (non-fire retardant type) for isolation of fire sprinkler devices. Installed taping shall not impede the normal function of the fire sprinkler device. Approved wire sprinkler guards shall be furnished in conjunction with isolation.
18. Where required, install and operate air filtration equipment to provide one air change in the Abatement Work area every 15 minutes. Openings made in the Enclosure System to accommodate these units shall be made airtight with durable tape and/or caulking as needed. If more than one unit is installed, they shall be turned on one at a time, checking the integrity of barriers after each unit is started. Insure that adequate power supply is available to satisfy the requirements of the air filtration units. Exhaust from these units shall be directed to the outside of the building whenever feasible. They shall not be exhausted into occupied areas of the buildings. Exhaust duct shall be extended from the Abatement Work area to the outside as required. Careful installation and daily inspections shall be performed to verify the exhaust ducts do not discharge into any areas of the building.
19. Once the Enclosure system is constructed and reinforced with air filtration units in operation as required, test the Enclosure for leakage utilizing smoke tubes. Repair, replace or reconstruct as required.
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -14
20. Following completion of the construction of polyethylene barriers and Decontamination Enclosure System, operate the air filtration units overnight to insure the barriers will remain intact and secured to walls and fixtures before beginning actual Abatement Work.
21. Commencement of the Work of this section shall not occur until:
a. The entire containmentsystem has been constructed and inspected by Owner Consultant in accordance with the required Shop Drawings.
b. Air filtration units are functioning within the requirements of this section. c. Air filtration units are functioning within the requirements of this section. d. Pre-Abatement submittals, notifications, postings, and permits have been provided and reviewed by the Owner Consultant.
e. Equipment for Abatement, Decontamination, and disposal are on the Project site. f. Worker training, respirator fit testing, and medical surveillance has been provided and reviewed by the Owner Consultant.
g. A Notice to Proceed is transmitted by the Owner.
3.02 ASBESTOS RELATED DISTURBANCE WORK PRACTICES (Small-Scale, Short Duration – SSSD)
A. For Class III work, shut off air handling equipment to rooms work will occur in.
B. Provide and post signs at the entrance to the work area affected. The signs shall comply with Cal/OSHA regulations.
C. For Class III work clean the area immediately under the location to be disturbed.
D. For Class III work move any moveable furniture or objects from immediately beneath the area to be disturbed.
E. Provide an enclosure around the area of disturbance. This may include, but is not limited to:
1. Mini-enclosure where not more than two persons may occupy for the purpose cutting holes up to three square feet in walls or ceilings.
2. For drilling, coring, sawing or similar disturbance, an enclosure shall be placed over the area of disturbance of sufficient size to cover that area and contain the tools used. This can include drilling with a shroud, through a wet sponge, through a plastic enclosure, or similar designs which will ensure control of Asbestos fibers and other dust. Drilling or coring with the use of a vacuum collection device shall be equipped with a HEPA filtered vacuum.
F. Class III work performed without a HEPA vacuum collection device shall have surfaces of disturbance adequately wet to control fiber release.
G. Clean by wet method the surfaces disturbed, the enclosure device and/or materials used, and any tools used during the disturbance operation.
H. Clean up by wet method and/or HEPA vacuum any debris that may have escaped outside the enclosure required by this section.
3.03 DECONTAMINATION ENCLOSURE SYSTEM FOR ABATEMENT WORK A. Decontamination Enclosure Systems shall be provided at locations where workers will enter or exit the Abatement Work area of Class I and II asbestos work prior to any other set up. Only one system at a single location for each Regulated Area is required. At least one individual shall be stationed at the entrance of each system at times Abatement Work is in progress.
B. These systems may consist of existing rooms outside of the Abatement Work area, if the layout permits, and that can be enclosed in polyethylene sheeting, and are accessible from the Abatement Work area. If
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -15 this intended layout is not feasible, given existing site conditions, Enclosure systems may be constructed out of metal, wood, or plastic support as required.
C. Decontamination Enclosure Systems constructed at the Project site shall be furnished with 6-mil opaque white or black polyethylene sheeting or other approved materials for privacy. Detailed descriptions of portable, prefabricated units, if furnished, shall be submitted for review. Shop Drawings must include floor plan with dimensions, materials, size, thickness, plumbing, and electrical utilities.
D. Decontamination Enclosure System shall consist of at least a Clean Room, a Shower Room, and an equipment room, each separated from the other, from the Abatement Work area and from the non-Work area by "Z-flaps" at a minimum. The system shall be furnished with, at a minimum, two layers of 6-mil polyethylene sheeting on the floors, walls, and ceiling.
E. Clean room shall be of adequate size to accommodate the Abatement crew. Clean work clothes, clean disposable clothing, replacement filters for respirators, disposable towels, and other necessary items shall be provided for in adequate supply adjacent to the Clean Room. A location for posting notices shall also be provided adjacent to this area. When required, a lockable door shall be furnished to control access into the Clean Room from outside the Abatement Work area. Comfort lighting, heat, and electricity shall be provided as required. The Clean Room shall not be used for storage of tools, equipment, materials, or as office space.
F. Shower room shall contain one or more showers as required to adequately accommodate workers. Each showerhead shall be supplied with hot and cold water adjustable at the tap. The shower Enclosure shall be constructed to ensure against any kind of leakage. Provide an adequate supply of soap, shampoo, and disposable towels, available at times. Shower water shall be drained, collected, and progressively filtered through a system achieving a maximum particle size of 1.0 microns.
G. The Equipment Room shall be used for storage of equipment and tools at the end of a shift. These shall have been cleaned using a HEPA Filtered vacuum and wet cleaning methods. A container lined with a labeled 6-mil polyethylene bag for collection of disposable clothing shall be located in this room.
Reusable footwear shall be stored in this area after being cleaned.
3.04 WASTE CONTAINER REMOVAL AIRLOCK AND EMERGENCY EXITS A. The waste container pass-out airlock shall be constructed away from the Decontamination Enclosure System. This airlock shall be in a location that provides direct access from Abatement Work area to the outside of the building if possible.
B. This system shall consist of an airlock, container Staging Area, and another airlock providing access to outside Abatement Work area.
C. The waste container airlock shall be constructed in similar fashion with similar materials as the Decontamination Enclosure System.
D. This airlock system shall not be used to enter or exit the Abatement Work area.
3.05 ALTERNATIVE PROCEDURES
A. Soil Removal
1. Required Asbestos Abatement shall be performed prior to soil Removal.
2. If soil Removal is specified, debris within or upon the soil shall be considered part of the soil and shall be removed as a contaminated waste. Debris includes, but is not limited to, fabric, paper, and other fibrous or porous materials.
3. It is not the intention of this section to require the Removal of large rocks, abandoned nonAsbestos-containing pipe, lumber, and similar debris. If these conditions are encountered, clean and encapsulate these materials instead of removing them as a contaminated waste, provided Asbestos contamination is not ingrained within and/or affixed to them. Any such materials remaining shall be stacked to one side to allow for access to the soil below for removal purposes.
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -16
4. Unless otherwise specified, soil shall be removed with a High Volume Vacuum system. Soil shall be removed to the hard pan unless otherwise specified or required.
5. After soil Removal has been completed, the Owner Consultant shall inspect the Work. Approval of the Removal Work is required prior to lock down and Encapsulation.
6. Soil requires Encapsulation following Asbestos Removal, including but not limited to, High Volume Vacuum removal. Apply a continuous even coat of encapsulating material at the rate of no more than fifty square feet per gallon. Other structural surfacesshall receive an evenly applied coat of lock down material.
B. Other:
1. High Volume Vacuum systems shall be provided with an Enclosure constructed at the waste discharge port. This Enclosure shall be of sufficient size to accommodate the workers and disposal containers necessary for the Project. The Enclosure shall be constructed of one layer, 6-mil minimum, of polyethylene sheeting. An air filtration unit shall be furnished during operation of the High Volume Vacuum.
2. Where pipe insulation is to be removed in a crawl space and/or attic space a single layer of 6- mil polyethylene sheeting with a minimum width of four feet shall be placed centered under the Removal surfaces.
3. If specified procedures cannot be furnished, a written request shall be provided to the Owner outlining details of the problem encountered and recommended alternative solutions.
4. Alternative procedures shall provide equivalent or greater protection than the specified and/or required procedures.
5. Any alternative procedure requires the written approval of the Owner prior to implementation.
3.06 WORKPLACE ENTRY AND EXIT PROCEDURES
A. Before entering the Regulated Area personnel shall read and be familiar with posted regulations, personal protection requirements, and emergency procedures. A signature sheet shall be posted for signatory acknowledgement these have been reviewed and understood by personnel prior to entry.
B. Workers and other authorized personnel shall enter the Abatement Work area through the Decontamination Enclosure System or other room required when Decontamination Enclosure System is not required.
C. Personnel who enter or exit the Regulated Area shall sign the entry and exit log located adjacent to the Clean Room.
D. Personnel shall proceed first to the Clean Room, don respirator, and washable and/or disposable clothing.
E. General construction area equipment including, but not limited to, hard hats, eye protection, and gloves shall also be provided as required. Clean respirator and cartridges, and protective clothing shall be provided and utilized by each person for each separate entry into the Regulated Area.
F. Before leaving the Regulated Area for Class I and II asbestos work personnel shall remove gross contamination from the outside of respirators and protective clothing by vacuuming and/or wet wiping methods. Each person shall clean protective footwear just prior to entering the Equipment Room.
1. Personnel shall proceed to Equipment Room where they remove protective equipment except respirators. Deposit disposable clothing into appropriately labeled containers.
2. Still wearing respirator, personnel shall proceed to the shower area, clean the outside of the respirators and the exposed face area under running water prior to removal of respirator then shower and shampoo to remove residual Asbestos contamination. Various types of respirators will require slight modification of these procedures. A powered air purifying respirator face piece will have to be disconnected from the filter/power pack assembly when such is not
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -17 waterproof, upon entering the shower. A dual cartridge respirator may be worn into the shower and cartridges shall be replaced for each new entry into the Work area.
3. After showering and drying off, proceed to the Clean Room and don clean clothing.
G. At no time shall any personnel exit an Abatement Work area into a space occupied by staff or students without being completely dressed. Any violation of this requirement will result in the permanent removal of the person from the Project site.
3.07 REMOVAL PROCEDURES
A. Brushes furnished for removing loose Asbestos Containing Material during detail cleaning of substrate shall be furnished with nylon or fiber bristles. Metal or wire brushes are not permitted. Brushes used during this process shall be disposed as contaminated waste when use of the brush for this work is completed.
B. A sufficient supply of HEPA Filtered vacuum systems shall be provided during cleanup of Abatement Work. Brush attachments are not permitted for use with vacuum systems.
C. Barriers constructed to isolate the Regulated Area from other areas shall be inspected at least three times per shift; prior to the start of Abatement activities; half way into the shift; and following the completion of the Abatement activities at the end of the shift. Inspect and document observations in the daily Project log.
D. Damage and defects in the Enclosure system shall be repaired immediately upon discovery.
E. At any time during Abatement Work, following barrier installation, if visible debris is observed outside of the Regulated Area or damage occurs to the barriers, stop Work immediately. Repairs shall be performed to the barriers and debris/residue shall be cleaned up with appropriate HEPA Vacuuming and wet wiping methods. These incidents shall be recorded in the daily Project log.
F. If air samples collected outside of the Work area during Abatement Work indicate airborne fiber concentrations greater than 0.01 f/cc or the pre-measured background levels (whichever is lower) Work shall stop immediately. An inspection and repair of barriers shall be performed as required. Surface cleaning with HEPA Vacuums and wet wiping methods of areas outside of the Work area may be required by the Owner. Findings, observations, and corrective actions shall be documented in the daily Project log.
3.08 ENCAPSULATION AND BRIDGING AGENTS
A. Clean and isolate the Work area in accordance with "Work Area Preparation" of this Section.
B. Repair damaged and missing areas of existing materials with non-Asbestos containing substitutes.
Material shall adhere adequately to existing surfaces and provide an adequate base for application of Encapsulating Material. Filler material shall be installed in accordance with manufacturers recommended specifications.
C. Remove loose or hanging Asbestos Containing Materials in accordance with the requirements of "Removal Procedures" in this Section.
D. Lockdown and Encapsulating Material, and bridging agents shall be reviewed by the Owner Consultant prior to the commencement of the Work of this section.
E. Encapsulating Material shall be sprayed applied with airless spray equipment. Nozzle pressure shall be adjustable within a range of 400 to 1500 PSI.
F. Lock down coat shall be spray applied with low pressure providing a continuous even coat.
G. Bridging agents shall be a palm or brush grade.
H. Colorless lock down materials, Encapsulating Material, and bridging agents shall be furnished with a compatible color additive. A different colorshall be furnished for each separate coat of applied material.
I. Install penetrating type Encapsulating Material to penetrate existing sprayed applied Asbestos Containing Materials to a depth as required.
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -18 J. During installation of the penetrating type Encapsulating Material; remove selected random core samples of the Asbestos Containing Materials in the presence of the Owner Consultant to verify depth of penetration.
K. Lock down coating and Encapsulating Material for installation on hot water, steam, or any other high temperature equipment shall be manufactured and recommended for installation on high temperature systems.
3.09 CLEAN UP PROCEDURES
A. Asbestos Clean Up Procedures:
1. Unless decontaminated daily, reusable footwear and kneepads shall be stored in the Equipment Room when not in the Work area. Upon completion of Abatement Work, these shall be disposed of as Asbestos contaminated waste or may be decontaminated at the completion of Abatement Work.
2. Remove and containerize visible accumulations of Asbestos Containing Material and Asbestos contaminated debris with rubber dustpans and rubber squeegees. Do not use metal shovels to pick up or move accumulated waste. Special care shall be taken to minimize damage to flooring materials.
3. Remove containerized waste from the Abatement Work area and the waste container airlock.
4. Wet wipe surfaces in the Regulated Area with clean rags, mops, and sponges as appropriate.
5. After cleaning remove the top layer of polyethylene sheeting from walls and floors.
6. Clean the second layer of polyethylene sheeting by wet wipe and HEPA Vacuuming. Windows, doors, HVAC system vents, and other critical seals shall remain sealed until the Abatement Work area passes final clearance. The air filtration units shall remain in continuous operation and the Decontamination Enclosure System shall remain in place and be utilized.
7. Decontaminate tools and equipment and remove at the appropriate time in the cleaning process.
8. Provide notification to the Owner at least one day in advance when Abatement Work will be completed and ready for final visual inspection. If, upon inspection, Abatement Work is not completed or the area does not pass final visual inspection, finish or correct the Abatement Work as required before notifying the Owner. Subsequent inspections shall commence not later than one day following notice.
9. The Owner Consultant shall inspect the Work area for visible residue. If residue is observed, it shall be deemed to contain Asbestos and the cleaning process shall be repeated. The lock down coatshall be applied only after inspection by the Owner Consultant and during non-school hours.
10. The second layer of isolation shall only be removed after the Owner Consultant inspects the lock down coat or installed Encapsulation, but in no case prior to overnight drying of lock down coat or Encapsulation.
11. Following completion of air clearance monitoring the remaining barriers shall be removed and properly disposed of. A final visual inspection by the Owner Consultant shall be performed to verify that no contamination remains in the Abatement Work area. Unsatisfactory conditions may require additional cleaning and air monitoring.
3.10 WASTE HANDLING AND TRANSPORTATION
A. Asbestos Waste Handling
1. As the Work progresses, to prevent exceeding available storage capacity on the Project site, sealed and labeled containers of Asbestos Containing Waste shall be removed and transported to the prearranged disposal location.
2. Waste disposal shall occur at an authorized site in accordance with regulatory requirements of NESHAP and applicable State and Local regulations.
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -19
3. Once the drums, bags, and/or wrapped components have been removed from the Work area, they shall be loaded into an enclosed truck for transportation.
4. Waste shall not be transported from the work are to the storage container or waste hauler’s vehicle while students or staff are present in the path of travel. Where a path of travel cannot be cordoned off the movement of waste must be completed prior to or after the presence on site of students and staff.
5. Personnel loading Asbestos waste shall be protected with disposable clothing and at a minimum half-face, air purifying, dual cartridge respirators furnished with HEPA Filters.
3.11 TRANSPORTATION OF NON HAZARDOUS WASTE
A. Waste shall be containerized, labeled, and transported in accordance with federal, state, and local regulations.
B. Waste shall be transported under cover a non-Hazardous Waste manifest.
C. Containers shall be enclosed during transportation.
3.12 TRANSPORTATION OF HAZARDOUS WASTE
A. Dump receipts; trip tickets, transportation manifests, weight certificates or other documentation of disposal shall be delivered to the Owner Consultant within 48 hours of disposal. As the material and responsibility for the material changes hands, the generator or designee, the transporter(s), and the Disposal Site Operator shall sign the Uniform Hazardous Waste Manifest. If a separate waste hauler is employed, the name, address, U.S.E.P.A. ID number, and signature of the transporter shall also be affixed onto the manifest.
B. The enclosed cargo area of trucks or containers shall be free of debris and lined with 6 mil polyethylene sheeting to prevent contamination from leaking or spilled containers. Floor sheeting shall be installed first and extend up the sidewalls. Wall sheeting shall be overlapped and taped into place.
C. Drums shall be placed on level surfaces in the cargo area and packed tightly together to prevent shifting and tipping. Large structural components shall be secured to prevent shifting, with bags placed on top.
D. Access openings on large metal containers, which are used for storing or transporting Asbestos waste, shall have doors and tops that can be closed and locked. Materials not properly bagged shall not be placed in these containers nor shall these containers be used for non-Asbestos waste or nonhazardous asbestos waste. Bags shall be placed, not thrown, into these containers to avoid damage.
3.13 MONITORING
A. Abatement Project Management and Inspection:
1. Owner has the right to perform air and performance monitoring at any time.
2. The Owner has unlimited access to the regulated and surrounding areas at times during progress of the Work, including, but not limited to, use of ladders, scaffolds, and other equipment required to gain access to the Work surfaces.
B. Work Area Monitoring:
1. Visual inspections and air testing may be performed at any time during the progress of the Abatement Work. Provide corrective measures as required to maintain the Work area in compliance with this Specification and regulatory requirements.
C. Contractor’s Employee – Personal Air Monitoring:
1. Provide air monitoring as required California Code of Regulations, Title 8, Section 1529. Results shall be provided to the Owner Consultant within ten working days of sampling. Negative Exposure Assessments utilizing prior project monitoring require submittal of applicable data for approval before work proceeds.
D. Clearance Air Monitoring:
CIP 689 - Clark Building Renovations
ASBESTOS ABATEMENT AND ASBESTOS RELATED DISTURBANCE 028213 -20
1. Following the completion of Abatement Work and clean up operations, lock down coat application, and visual inspection by the Owner, clearance air monitoring shall be performed by the Owner Consultant.
2. The Owner Consultant shall arrange for sampling of the air in the Abatement Work area for airborne fiber concentrations. Unauthorized interference or tampering with air sampling equipment may result in termination of the Contract and/or removal of the Abatement Contractor from the List of Prequalified Abatement Contractors.
3. If air-sampling results are within the limits of 40 CFR, Part 763, Subpart E (AHERA), the Abatement Work area shall be released for occupancy.
4. Areas failing clearance monitoring shall be cleaned as required in article 3.09, CLEAN UP PROCEDURES, and tested until satisfactory levels are provided in accordance with this Specification where required.
3.14 RE-ESTABLISHMENT OF THE WORK AREA AND SYSTEMS
A. Reestablishment of the Work area shall only occur following the completion of final inspection and clearance air monitoring.
B. Critical barriers shall be removed at this time.
C. Accompanied by the Owner Consultant, visually inspect the Abatement Work area for any remaining visible residue. Evidence of contamination will require additional cleaning requirements.
D. Install and secure Moveable Objects.
E. Relocate Moveable Objects that were removed to temporary locations back to their original positions.
F. Reestablish HVAC, mechanical, and electrical systems to the condition prior to commencement of the Work of this section.
G. Repair areas of damage deemed to be a result of the Abatement Work.
H. Restore the Work area and auxiliary areas utilized during the Abatement to conditions equal to or better than original. Any damage caused during the performance of Abatement Work, including, but not limited to, damage caused by tape, adhesive, staples, nails, water, Encapsulating Material, or any other material shall be repaired as required.
I. Prior to occupancy of a space following clearance monitoring, HVAC systems filters associated with the Work area shall be removed and disposed of as Asbestos waste. Decontaminate filter assembly and surrounding area with HEPA Vacuums and wet cleaning methods.
END OF SECTION
CIP 689 - Clark Building Renovations
LEAD ABATEMENT AND LEAD RELATED CONSTRUCTION WORK 028333 -1 SECTION 02 8333 - LEAD ABATEMENT AND LEAD RELATED CONSTRUCTION WORK PART 1 – GENERAL
1.01 SUMMARY
A. Section Includes:
1. Abatement, Lead Related Construction Work or painting of lead-containing materials and/or Lead Based Paint.
2. Transportation and disposal of lead-containing materials and/or Lead Based Paint.
B. Related Requirements:
1. Section 00 3126 - Existing Hazardous Materials Information.
2. Division 01 - General Requirements.
3. Cal/OSHA Title 8, California Code of Regulations (CCR).
4. California Air Resources Board Ambient Air Quality Standard, Title 24 CCR.
5. California Department of Public Health, Title 17, CCR.
6. Cal/EPA, Title 22 CCR.
7. California Labor Code, Division 5, Part 1, as it pertains to safety in employment and with the applicable provisions of the Title 8, CCR as it pertains to Occupational Safety and Health in the work place.
8. Environmental Protection Agency, 40CFR, Part 745.
9. UD – Title X, Residential Lead-Based Paint Hazard Reduction Act of 1992.
10. Los Angeles County Public Health Code (Chapter 11).
1.02 DEFINITIONS AND ACRONYMS
A. AAS - Atomic Absorption Spectrophotometry used for lead paint chip and dust wipe sample analysis.
B. Abatement – Any set of measures designed to reduce or eliminate lead hazards or Lead Based Paint for public and residential buildings, but does not include containment or cleaning.
C. Action Level – Means the Action Level as defined in Title 8, California Code of Regulations, Section 1532.1.
D. ANSI – American National Standards Institute.
E. ASTM – American Society for Testing and Materials.
CIP 689 - Clark Building Renovations
LEAD ABATEMENT AND LEAD RELATED CONSTRUCTION WORK 028333 -2 F. Building ID number or code (Maximo) – A six digit alphanumeric identification code assigned to each building on an Owner site, also referred to as the insurance code, ID number or similar terms.
G. Certificate – Means the document issued by CDPH to an individual meeting the certification requirements as described in CCR Title 17, Sections 35083, 35085, 35087, 35089, or 35091.
H. Clean Room – An uncontaminated area or room which is a part of the worker Decontamination Enclosure System with provisions for storage of worker's street clothes and clean protective equipment.
I. Clearance Inspection – Means visual examination and, as applicable, collection of environmental samples upon completion of the Work of this section.
J. Component – Means a structural element or fixture, including but not limited to, walls, floors, ceilings, doors, window molding, trim, trestles, tanks, stairs, railings, cabinets, gutters, or downspouts.
K. Curtained doorway – A device to allow ingress and egress from one room to another while permitting minimal air movement between the rooms, typically constructed by placing two overlapping sheets of plastic over an exiting or temporarily framed doorway, securing each along the top of the doorway, securing the vertical edge of one sheet along one vertical side of the doorway and securing the vertical edge of the other sheet along the opposite vertical side of the doorway. Other effective designs may be submitted for review.
L. Decontamination – The process of eliminating lead contamination from building surfaces, and property by cloths, mops, or other utensils dampened with water and disposed of as lead contaminated waste.
M. Decontamination Enclosure System – A minimum two-stage Decontamination unit consisting of a compartment for Decontamination, and a Clean Room. Unless otherwise specified, it shall be adjacent to the Abatement area.
N. Demolition – The wrecking or taking out of any load supporting structural member of a facility together with any related handling operations.
O. Deteriorated Lead Based Paint – Means Lead Based Paint or a surface coating that is cracking, chalking, flaking, chipping, peeling, non-intact, failed, or otherwise separating from the substrate to which it is applied to.
P. CDPH– California Department of Public Health.
Q. CDPH-Approved Course – Means any lead construction course that satisfies the requirements specified in CCR Title 17, Sections 35056, 35061, 35066, or 35067 as determined by CDPH pursuant to Sections 35076 and 35078.
R. DOSH – California Division of Occupational Safety & Health or Cal/OSHA.
S. DOT – Department of Transportation.
T. DTSC – California Department of Toxic Substances Control.
U. Encapsulating Material – Are coatings or rigid materials adhesively applied to Lead Based Painted surfaces in the Encapsulation process.
CIP 689 - Clark Building Renovations
LEAD ABATEMENT AND LEAD RELATED CONSTRUCTION WORK 028333 -3 V. Encapsulation – The application of an Encapsulating Material to Lead Based Paint to provide a barrier between the Lead Based Paint and the environment.
W. Enclosure – A rigid durable barrier mechanically attached to building Component, with edges and seams sealed with caulk or other sealant.
X. EPA; Renovation, Repair and Painting (RRP) – Means a lead-related construction course that satisfies the requirements specified in 40 CFR, Part 745, Section 745.90.
Y. FETU – Facilities Environmental Technical Unit.
Z. Firm – Means a company, partnership, corporation, sole proprietorship or individual doing business, association, or other business entity; a Federal, State, Tribal, or local government agency; or a nonprofit organization and satisfies the requirements specified in 40 CFR, Part 745, Section 745.89.
AA. Fixed Object – A piece of equipment, furniture, or improvement in the Work Area, which cannot be removed from the Work Area.
BB. Hazardous Waste – Means any waste stream determined by an Owner approved laboratory to exceed the regulatory thresholds for lead hazardous waste.
CC. HEPA Filter – Means a filtering system capable of trapping and retaining at least 99.97 percent of mono-dispersed particles 0.3 micrometers in diameter or larger.
DD. HEPA Vacuum – A vacuum system furnished with HEPA filtration.
EE. HUD – United States Department of Housing and Urban Development FF. HVAC – Heating, Ventilation, and Air Conditioning system.
GG. ICP-AES – Means Inductively Coupled Plasma-Atomic Emission Spectroscopy used for heavy metal analysis, including lead.
HH. Lead Based Paint – Means paint or other surface coatings that contain an amount of lead equal to or greater than 0.7 milligrams per square centimeter (0.7 mg/cm2 ) or equal to or greater than 0.5
percent by weight.
I. Lead Containing Paint – Means paint or other surface coatings that contain lead in an amount equal to or greater than 0.06 percent lead dry weight (600 ppm) but does not meet the definition of Lead Based Paint. In the absence of paint chip or surface coating bulk sample results, any surface coating shall be assumed to be above 0.06 percent lead dry weight (600 ppm) until surface coating samples are collected and analyzed that indicate otherwise. Lead concentration shall be determined by a method that has an accuracy of not less than plus or minus 25 percent at 0.06 percent lead dry weight, to a confidence level of 95 percent.
JJ. Lead Contaminated Dust – Means dust that contains an amount of lead equal to, or greater than, forty micrograms per square foot (40 µg/ft2
) for interior floor surfaces; two hundred and fifty
micrograms per square foot (250 µg/ft2
) for interior horizontal window surfaces; and eight
hundred micrograms persquare foot (800 µg/ft2
) for exterior floor and exterior horizontal window
surfaces.
KK. Lead Contaminated Soil – Means bare soil that contains an amount of lead equal to, or greater than, four hundred parts per million (400ppm).
CIP 689 - Clark Building Renovations
LEAD ABATEMENT AND LEAD RELATED CONSTRUCTION WORK 028333 -4 LL. Lead Hazard – Means deteriorated Lead Based Paint, Lead Contaminated Dust, Lead Contaminated Soil, the disturbance of Lead Based Paint or Presumed Lead Based Paint without containment, or any other operation that may result in persistent and quantifiable lead exposure.
MM. Lead Inspection – Means a surface by surface investigation to determine the presence of Lead Based Paint as described in Chapter 7: Lead Based Paint Inspection, “ Guidelines for the Evaluation and Control of Lead Based Paint Hazards in Housing,” U.S. Department of Housing and Urban Development, 1997 Revision.
NN. Lead Related Construction Work – Means any construction, alteration, painting, Demolition, salvage, Renovation, repair, or maintenance of any residential or public building, including preparation and cleanup that, by using or disturbing lead-containing material or soil, may result in significant exposure of adults or children to lead.
OO. Lead Safe Schools Program – Means the training program for lead safe working practices as developed by the Labor Occupational Health Program at U.C. Berkley.
PP. Location Code (Maximo) – Refers to a unique four digit numeric code assigned by the Owner to each of its Project sites.
QQ. Member – A Component part of a structure complete in itself.
RR. Movable Object – A piece of portable equipment or furniture in the Work Area, which can be removed from the Work Area.
SS. NESHAP – The National Emission Standardsfor Hazardous Air Pollutants (40 CFR Part 50.12).
TT. NIOSH – The National Institute for Occupational Safety and Health.
UU. Owner Consultant (OC) – Refers to the firm, company or individual designated by the Owner.
VV. Painting Contract – For purposes of this section, a painting contract is a Contract with the Owner to perform painting on existing facilities where Lead Based Paint, Lead Containing Paint, Presumed Lead Based or Presumed Lead Containing Paint will be disturbed or abated.
WW. P.E.L. – Means permissible exposure limits as defined in Title 8, California Code of Regulations, Section 1532.1.
XX. Plasticize – To cover floors, walls, and equipment with plastic sheeting as specified herein.
YY. Portable Mechanical Ventilation System – A portable exhaust system furnished with HEPA filtration and capable of providing a constant air flow into regulated Work Area from adjacent areas and exhausted outside the regulated area.
ZZ. Presumed Lead Based Paint – Means paint or surface coating affixed to a Component in or on a structure, excluding paint or surface coating affixed to a Component in or on a residential dwelling constructed on or after January 1, 1979, or a school constructed on or after January 1, 1993.
AAA. Removal – Means operations where Lead Based Paint is removed or stripped from structures or substrates including Demolition.
BBB. Renovation – Means the modifying of any existing structure, facility, or portion thereof.
CIP 689 - Clark Building Renovations
LEAD ABATEMENT AND LEAD RELATED CONSTRUCTION WORK 028333 -5 CCC. Replacement – Means Removal of an entire building Component coated with Lead Based Paint and replacing it with a lead free Component.
DDD. SCAQMD – South Coast Air Quality Management District.
EEE. STLC – Means Soluble Threshold Limit Concentration used in the State of California in conjunction with TTLC to determine lead hazardous waste limits. If the STLC result is equal to or exceeds 5 mg/L the waste is deemed to be hazardous.
FFF. Surfactant - A chemical wetting agent added to water.
GGG. TCLP – Means Toxicity Characteristic Leaching Procedure used to determine the federal Resources Conservation Recovery Act (RCRA) lead hazardous waste limits. If the results equal or exceed 5 mg/L the waste is deemed to be hazardous.
HHH. TTLC – Means Total Threshold Limit Concentration used in the State of California in conjunction with STLC to determine lead hazardous waste limits. If the results are equal to or exceeds 1000 mg/kg, the waste is deemed to be hazardous.
II. Visible Emissions – Any emissions from a known or suspected lead-containing material that is visually discernible.
JJJ. Wet Cleaning – The process of eliminating lead contamination from building surfaces and/or objects by cloths, mops, or other utensils dampened with amended water and afterwards being disposed of as hazardous waste.
KKK. Work Area – Means an area where known or Presumed Lead Based Paint is disturbed or Abatement is conducted.
LLL. X-Ray Fluorescense (XRF) Analyzer – Means a direct reading instrument that determinesthe lead content of the surface coatings in milligrams per square centimeter (mg/cm2 ) using the principle
of x-ray fluorescence.
1.03 POLICIES AND PROCEDURES
A. The Owner has a zero-tolerance policy for uncontrolled lead releases during Lead Related Construction Work, Lead Containing Paint disturbance, or Abatement activities. A lead release requiring an emergency response is any disturbance resulting in the uncontrolled release of lead containing materials. Upon observation of any visual emissions, immediately stop the Work, vacate the Work Area, and provide written notification to the Owner Consultant.
B. Pre-qualified Abatement Subcontractors are not permitted to subcontract any Abatement Work to a lower tier Subcontractor without the prior written approval of the Owner.
C. Do not furnish a reduced pressurization and filtration system in violation of, or in infringement upon, any patent.
D. Owner Consultant shall provide oversight for Projects that have the potential to disturb lead containing or Lead Based Paint. Prior to the commencement of such Work, provide written notification to the Owner Consultant.
E. The following paragraph regarding impacts to coated surfaces shall be part of the contract:
CIP 689 - Clark Building Renovations
LEAD ABATEMENT AND LEAD RELATED CONSTRUCTION WORK 028333 -6
1. “Renovation, repair or painting work performed on buildings constructed prior to 1978 require special handling and environmental monitoring when coated surfaces including, but not limited to, painted, varnished, and glazed surfaces are impacted. Coated surfaces applied prior to 1978 are assumed to be lead-based. All work shall be performed in compliance with Specification, Section 02 8333, “Lead Abatement and Lead Related Construction Work.” XRF testing methodology is not acceptable in determining negative for lead content for Cal/OSHA compliance purposes, except for notification requirements. XRF may be used in determining lead-based paint for compliance with the U.S.E.P.A. Renovator, Repair, and Painting Rule. Disturbance of coated surfaces by contractors will be monitored by qualified District staff or Environmental Consultant sufficient to ensure that proper training and work procedures, cleanup, and waste handling are employed.”
1.04 COORDINATION
A. Coordinate the Work of this section directly with the Owner and/or Owner Consultant.
1.05 SITE SECURITY
A. The Work Area is restricted to authorized, trained, and protected personnel. A list of authorized personnel shall be established and posted at the entrance of the Work Area by the Owner Consultant prior to commencement of the Work.
B. Report to the Owner Consultant any unauthorized entry into the Work Area. Following notification, a written report of the incident shall be provided to the Owner Consultant.
C. A logbook shall be maintained at the entrance of the Work Area. Persons entering the Work Area shall record name, company affiliation, time in, and time out for each entry and exit.
D. Access to the Abatement Work Area shall be through the Decontamination Enclosure System only. Other means of access shall be blocked or locked so as to prevent entry to or exit from the Work Area. Emergency exits shall be operable from inside the Work Area.
E. Maintain Work Area security during Abatement and/or Lead Related Construction Work. Work Areas and ancillary equipment accessible to non-authorized personnel shall be protected from unauthorized access by constructing a minimum barrier of 3/8 inch CDX plywood supported by 2 by 4 studs, 16 inches on center. An access door shall be provided with hasp and padlock sufficient to prevent unauthorized entry. A key shall be provided to the Owner and Owner Consultant. Required barriers within an occupied building shall be furnished with sheathing as required by state and local fire protection regulations.
F. Remove barriers upon the completion of the Work of this section and unless otherwise specified, repair and/or replace to its original condition, damage resulting from installation, use, and removal of the barriers.
1.06 EMERGENCY PLANNING
A. Emergency planning and procedures shall be developed, submitted, reviewed, and agreed to by the Owner Consultant prior to the commencement of lead-related construction and/or Abatement Work.
B. Emergency procedures shall be provided in the written languages understood by employees working on the Project and shall be prominently posted at the entrance of the Decontamination
CIP 689 - Clark Building Renovations
LEAD ABATEMENT AND LEAD RELATED CONSTRUCTION WORK 028333 -7 Enclosure System. Prior to entering the Work Area, parties must read and sign these procedures to acknowledge receipt and understanding of the Work Area layout, location of emergency exits, and emergency procedures.
C. Emergency planning shall consider the effects of fire, explosion, toxic atmospheres, electrical hazards, slips, trips and falls, confined spaces, and heat related injury. Develop and provide written procedures and training to employees.
D. Employees shall be trained in evacuation procedures in the event of workplace emergencies.
E. In the event of non-life threatening situations requiring medical treatment, injured or otherwise incapacitated employees shall decontaminate following normal procedures with assistance from fellow workers if necessary, before exiting the Work Area.
F. In the event of life threatening injury or illness requiring immediate medical treatment, worker Decontamination shall be given minimum priority. Provide measures to stabilize the injured worker remove them from the Work Area and secure proper medical treatment.
G. Telephone numbers of emergency response personnel shall be prominently posted at the entrance of the Decontamination Enclosure System along with the location of the nearest telephone. In addition to the 911 emergency number, post the address and telephone number of the nearest emergency medical services provider.
H. Provide at least one employee on the Project site at times during progress of the Work that is trained and certified in first aid and cardiopulmonary resuscitation (CPR). This employee shall be identified by name and proof of training shall be provided to the Owner Consultant prior to the commencement of the Work of this section.
I. Provide at least one 4A/60BC dry chemical extinguisher in the Decontamination compartment.
Workers shall be trained in the proper operation of fire extinguishers.
J. Emergency exits shall be provided and clearly marked with arrows or other clearly visible markings to permit easy identification from anywhere within the Work Area. Exits shall be secured to prevent access from uncontaminated areas while still permitting emergency egress.
Exits shall be properly sealed with polyethylene sheeting, which can be cut to permit emergency egress. Emergency exits may lead through the Decontamination Enclosure System or other alternative exits as required by fire officials.
1.07 LICENSING
A. The Work of this section shall be performed by an entity duly licensed in the State of California in accordance with the provisions of Chapter 9 of Division 3 of the Business and Professions Code, as amended.
1.08 QUALIFICATIONS
A. Only safety pre-qualified bidders on the pre-approved bidders list are qualified to be awarded an Abatement Contract or Painting Contract be listed as a Subcontractor for lead Abatement Work or Painting Contract.
B. Where the scope of the Work includes the painting and/or refinishing of existing surfaces, only safety pre-qualified bidders on the pre-approved bidderslist are qualified to be awarded a painting Contract or be listed as a Subcontractor for painting Work.