REMODEL OF 501 SOUTH STATE STREET 10 Spec. No. 25-04
All property line fences and improvements in the vicinity of the work shall be protected by the Contractor and, if they are injured or destroyed, they and any other property injured by the Contractor, his or her employees or agents, shall be restored to a condition as good as when he or she entered upon the work. 6-06. Protection of City Against Patent Claims. All fees, royalties or claims for any patented invention, article or method that may be used upon or in any manner connected with the work under this contract shall be included in the price bid for the work and the Contractor and his or her sureties shall protect and hold the City, together with all of its officers, agents, servants and employees, harmless against any and all demands made for such fees or claims brought or made on account of this contract. The Contractor shall, if requested by the Engineer, furnish acceptable proof of a proper release from all such fees or classes.

Should the Contractor, his or her agents, servants or employees, or any of them be enjoined from furnishing or using any invention, article, material or appliance supplied or required to be supplied or used under this contract, the Contractor shall promptly substitute other articles, materials or appliance, in lieu thereof, of equal efficiency, quality, finish, suitability and market value and satisfactory in all respects to the Engineer. Or, in the event that the Engineer elects, in lieu of such substitution, to have supplied and to retain and use, any such invention, article, material or appliance, as may by this contract be required to be supplied, in that event the Contractor shall pay such royalties and secure such valid licenses as may be requisite and necessary for the City, its officers, agents, servants and employees, or any of them, to use such invention, article, material or appliance without being disturbed or in any way interfered with by any proceeding in law or equity on account thereof. Should the Contractor neglect or refuse to make the substitution promptly, or to pay such royalties and secure such licenses as may be necessary, then in that event the Engineer shall have the right to make such substitution, or the City may pay such royalties and secure such licenses and charge the cost thereof against any money due to the Contractor from the City or recover the amount thereof from him or her and his or her sureties notwithstanding final payment under this contract may have been made.
6-07. Protection of Contractor's Work Property. The Contractor shall protect his or her work, supplies and materials from damage due to the nature of the work, the action of the elements, trespassers, or any cause whatsoever under his or her control, until the completion and acceptance of the work. Neither the City nor any of its agents assumes any responsibility for collecting indemnity from any person or persons causing damage to the work of the Contractor.
6-08. Regulations and Permits. The Contractor shall secure and pay for all permits, give all notices and comply with all laws, ordinances, rules and regulations bearing on the conduct of the work as drawn and specified. If the Contractor observes that the Plans and Special Provisions are at variance therewith, he or she shall promptly notify the Engineer in writing and any necessary changes shall be adjusted as provided in the contract for changes in the work. The contractor and any subcontractors shall each secure and maintain a valid City of Ukiah Business License. The City of Ukiah will issue a no fee encroachment permit to the Contractor allowing him or her to perform work within City right of way or within City property after the Contract Documents have been executed and insurance certificates and endorsements have been approved by the City. 6-09. Construction Utilities. The Contractor shall be responsible for providing for and in behalf of his or her work under this contract, all necessary utilities, such as special connection to water supply, telephones, power lines, fences, roads, watchmen, suitable storage places, etc.
6-10. Approval of Contractor's Plans. The approval by the Engineer of any drawing or any method of work proposed by the Contractor in accordance with paragraph 8-06 shall not relieve the Contractor of any of his or her responsibility for his or her errors therein and shall not be regarded as any assumption of risk or liability by the City or any officer or employee thereof and the Contractor shall have no claim under this contract on account of the failure or partial failure or inefficiency of any plan or method so approved. Such approval shall be considered to mean merely that the Engineer has no objection to the Contractor's using, upon his or her own full responsibility the plan or method approved.
6-11. Suggestions to the Contractor. Any plan or method of work suggested by the Engineer to the Contractor, but not specified or required, if adopted or followed by the Contractor in whole or in part, shall be used at the risk and responsibility of the Contractor; and the Engineer and the City shall assume no responsibility thereof.

Page 276 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 11 Spec. No. 25-04
6-12. Termination of Unsatisfactory Subcontracts. Should any subcontractor fail to perform in a satisfactory manner the work undertaken by him, such subcontract shall be terminated immediately by the Contractor upon notice from the Engineer.
6-13. Preservation of Stakes and Marks. The Contractor shall preserve carefully bench marks, reference points and stakes and in case of destruction he or she shall replace his or her stakes, reference points and bench marks and shall be responsible for any mistakes that may be caused by their unnecessary loss or disturbance.

Contractor’s attention is directed to Section 7-03 of these Special Provisions. 6-14. Assistance to Engineer. At the request of the Engineer the Contractor shall provide men from his or her force and tools, stakes and other materials to assist the Engineer temporarily in making measurements and surveys and in establishing temporary or permanent reference marks. Payment for such materials and assistance will be made as provided for under the caption "Extra Work," provided, however, that the cost of setting stakes and marks carelessly lost or destroyed by the Contractor's employees will be assessed to the Contractor. 6-15. Removal of Condemned Materials and Structures. The Contractor shall remove from the site of the work, without delay, all rejected and condemned materials or structures of any kind brought to or incorporated in the work and upon his or her failure to do so, or to make satisfactory progress in so doing, within forty-eight (48) hours after the service of a written notice from the Engineer, the condemned material or work may be removed by the City and the cost of such removal shall be taken out of the money that may be due or may become due the Contractor on account of or by virtue of this contract. No such rejected or condemned material shall again be offered for use by the Contractor under this Contract.
6-16. Proof of Compliance with Contract. In order that the Engineer may determine whether the Contractor has complied with the requirements of this contract, not readily enforceable through inspection and tests of the work and materials, the Contractor shall, at any time when requested, submit to the Engineer properly authenticated documents or other satisfactory proofs as to his or her compliance with such requirements. 6-17. Errors and Omissions. If the Contractor, in the course of the work, finds any errors or omissions in plans or in the layout as given by survey points and instruction, or if he or she finds any discrepancy between the plans and the physical conditions of the locality, he or she shall immediately inform the Engineer, in writing and the Engineer shall promptly verify the same. Any work done after such discovery, until authorized, will be done at the Contractor's risk.
6-18. Cooperation. The Contractor shall cooperate with all other contractors who may be performing work in behalf of the City and workmen who may be employed by the City on any work in the vicinity of the work to be done under this contract with the work of such contractors or workmen. he or she shall make good promptly, at his or her own expense, any injury or damage that may be sustained by other contractors or employees of the City at his or her hands.

Any difference or conflict which may arise between the Contractor and other contractors, or between the contractor and workmen of the City in regard to their work shall be adjusted and determined by the Engineer. If the work of the Contractor is delayed because of any acts or omissions of any other contractor or of the City, the Contractor shall on that account have no claim against the City other than for an extension of time. 6-19. Right of Contractor to Stop Work. Under the following conditions the Contractor shall have the right, if he or she so desires, to stop the work and terminate the contract upon ten (10) days written notice to the Engineer and recover from the City payment for all work actually performed and for all satisfactory materials actually delivered to the site of the work for permanent incorporation therein, all as may be shown by the estimate of the Engineer.
(1) If the work is stopped under an order of any court or other competent public authority for a period of time of three (3) months through no act or fault of the Contractor or of anyone employed by him.
(2) If the Engineer fails to issue the monthly certificate for payment in accordance with the terms of this contract.

Page 277 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 12 Spec. No. 25-04
(3) If the City fails to pay the Contractor within sixty (60) days after it shall have become due, as provided by the terms of this contract, any sum certified by the Engineer or awarded by the City.

All provided that if such action to terminate the contract be not instituted by the Contractor within ten (10) days after the alleged existence of such condition and if written notice of such action be not at that time delivered to the City and the Engineer, then such right shall lapse until another occasion arises according to this section. 6-20. Hiring and Dismissal of Employees. The Contractor shall employ only such foremen, mechanics and laborers as are competent and skilled in their respective lines of work and whenever the Engineer shall notify the Contractor that any person on the work is, in his or her opinion, incompetent, unfaithful, intemperate or disorderly, or refuses to carry out the provisions of this contract, or uses threatening or abusive language to any person on the work representing the City, or is otherwise unsatisfactory, such person shall be discharged im mediately from the work and shall not be re-employed upon it except with the consent of the Engineer. 6-21. Wage Rates.

1. Contractor shall pay all mechanics and laborers employed or working upon the site of the work unconditionally and without subsequent deductions or rebate on any account the full amounts due at the time of payment at wage rates not less than those contained in the applicable prevailing wage determination, regardless of any contractual relationship which may be alleged to exist between the Contractor and subcontractors and such laborers and mechanics.

2. Contractor shall comply with the California Labor Code Section 1775. In accordance with said Section 1775, Contractor shall forfeit as a penalty to the Owner, $50.00 (or the higher minimum penalty as provided in Section 1775(B)(ii) – (iii)) for each calendar day or portion thereof, for each workman paid less than the stipulated prevailing rates for such work or craft in which such workman is employed for any work done under the Contract by him or her or by any subcontractor under him or her in violation of the provisions of the Labor Code and in particular, Labor Code Sections 1770 to 1780, inclusive. In addition to said penalty and pursuant to Section 1775, the difference between such stipulated prevailing wage rates and the amount paid to each workman for each calendar day or portion thereof for which each workman was paid less than the stipulated prevailing wage rate shall be paid to each workman by the Contractor.

3. Pursuant to the provision of Section 1770 of the Labor Code of the State of California, Owner has ascertained the general prevailing rate of wages (which rate includes employer payments for health and welfare, vacation, pension and similar purposes) applicable to the work to be done, for straight time work.

The holiday wage rate listed shall be applicable to all holidays recognized in the collective bargaining agreement of the particular craft, classification or type of workmen concerned. Copies of the General Prevailing Wage Determination are available on the Internet at web address:
http://www.dir.ca.gov/DLSR/PWD The Contractor shall post the wage determination at the site of work in a prominent place where it can easily be seen by the workers.

4. City will not recognize any claim for additional compensation because the Contractor has paid any rate in excess of the prevailing wage rate obtained by the Contractor. The possibility of wage increases is one of the elements to be considered by the Contractor in determining his or her bid and will not in any circumstances be considered as the basis for a claim against the City.

5. The Labor Commissioner through the Division of Labor Standards Enforcement (DLSE) may at any time require contractors and subcontractors to furnish electronic certified payroll records directly to DLSE.

Commencing with contracts awarded or after April 1, 2015, all contractors and subcontractors must furnish electronic certified payroll records directly to the DLSE.

6. Travel and Subsistence Payments.

Contractor shall make travel and subsistence payments to each workman needed to execute the work in accordance with the requirements in Section 1773.8 of the Labor Code (Chapter 880, Statutes of 1968).

7. Apprentices.

Page 278 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 13 Spec. No. 25-04
Attention is directed to the provisions in Sections 1777.5 (Chapter 1411, Statutes of 1968) and 1777.6 of the California Labor Code concerning the employment of apprentices by the Contractor or any subcontractor under him. Contractor and any subcontractor under him or her shall comply with the requirements of said sections in the employment of apprentices.

Information relative to apprenticeship standards, wage schedules and other requirements may be obtained from the Director of Industrial Relations, ex officio the Administrator of Apprenticeship, San Francisco, California, or from the Division of Apprenticeship Standards and its branch offices. 6-22. Cleaning Up. The Contractor shall not allow the site of the work to become littered with trash and waste material, but shall maintain the same in a neat and orderly condition throughout the construction period. The Engineer shall have the right to determine what is or is not waste material or rubbish and the place and manner of disposal.

On or before the completion of the work, the Contractor shall without charge therefore carefully clean out all pits, pipes, chambers or conduits and shall tear down and remove all temporary structures built by him or her and shall remove rubbish of all kind from any of the grounds which he or she has occupied and leave them in first class condition.
6-23. Guaranty. All work shall be guarantied for a period of one year from the date of acceptance by the City. The Contractor shall promptly make all needed repairs arising out of defective materials, workmanship and equipment.

The City is hereby authorized to make such repairs if within ten days after the mailing of a notice in writing to the Contractor or his or her agent, the Contractor shall neglect to make or undertake with due diligence the aforesaid repairs, provided, however, that in case of an emergency where, in the opinion of the City delay would cause serious loss or damage, repairs may be made without notice being sent to the Contractor and the Contractor shall pay the costs thereof.

Pursuant to the provisions of Section 4-03 of these Special Provisions, the Contractor shall furnish a Defective Material and Workmanship Bond in an amount not less than 5 percent of the final contract price, which shall be effective for a period of one (1) year after the completion and acceptance of the work.

SECTION 7. RESPONSIBILITIES AND RIGHTS OF CITY
7-01. Authority of the Engineer. All work done under this contract shall be done in a workmanlike manner and shall be performed to the reasonable satisfaction of the Engineer, who shall have general supervision of all work included hereunder. To prevent disputes and litigation, the Engineer (1) shall in all cases determine the amount, quality, acceptability and fitness of the several kinds of work and materials which are to be paid for under this contract, (2) shall decide all questions relative to the true construction, meaning and intent of the Special Provisions and Drawings, (3) shall decide all questions which may arise relative to the classifications and measurements of quantities and materials and the fulfillment of this contract and (4) shall have the power to reject or condemn all work or material which does not conform to the terms of this contract. his or her estimate and decision in all matters shall be a condition precedent to an appeal for arbitration, or the right of the Contractor to receive, demand, or claim any money or other compensation under this agreement and a condition precedent to any liability on the part of the City to the Contractor on account of this contract. Whenever the Engineer shall be unable to act, in consequence of absence or other cause, then such engineer as the Engineer or the City shall designate, shall perform any and all of the duties and be vested with any or all of the powers herein given to the Engineer.
7-02. Inspection. The City will provide engineering personnel for the inspection of the work.

The Engineer and his or her representatives shall at all times have access to the work whenever it is in preparation or progress and the Contractor shall provide proper facilities for such access and inspection.

If the Special Provisions, the Engineer's instruction, laws, ordinances, or any public authority require any work to be specially tested or approved, the Contractor shall give the Engineer timely notice of its readiness for inspection and, if the inspection is by an authority other than the Engineer, of the date fixed for such inspection. Inspections by the Engineer shall be promptly made at the source of supply where practicable. If any work shall be covered up

Page 279 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 14 Spec. No. 25-04
without approval or consent of the Engineer, it must, if required by the Engineer, be uncovered for examination and properly restored at the Contractor's expense.

Re-examination of any work may be ordered by the Engineer and, if so ordered, the work must be uncovered by the Contractor. If such work is found to be in accordance with the contract documents, the City shall pay the cost of re-examination and replacement. If such work is not in accordance with the contract documents, the Contractor shall pay such cost.

Properly authorized and accredited inspectors shall be considered to be the representatives of the City limited to the duties and powers entrusted to them. It will be their duty to inspect materials and workmanship of those portions of the work to which they are assigned, either individually or collectively, under instructions of the Engineer and to report any and all deviations from the Drawings, Special Provisions and other contract provisions which may come to their notice. Any inspector may be considered to have the right to order the work entrusted to his or her supervision stopped, if in his or her opinion such action becomes necessary, until the Engineer is notified and has determined and ordered that the work may proceed in due fulfillment of all contract requirements. 7-03. Surveys. Contractor shall furnish all land surveys, establish all base lines and bench marks and make sufficient detailed surveys needed for working points, lines and elevations. The Contractor shall develop all slope stakes and batter boards. Contractor shall also develop all additional working points, lines and elevations as he or she may desire to facilitate his or her methods and sequence of construction. 7-04. Rights-of-Way. The City will provide all necessary rights-of-way and easements in or beneath which work will be performed by the Contractor under this contract. 7-05. Retention of Imperfect Work. If any portion of the work done or material furnished under this contract shall prove defective and not in accordance with the Plans and Special Provisions, and if the imperfection in the same shall not be of sufficient magnitude or importance to make the work dangerous or undesirable, the Engineer shall have the right and authority to retain such work instead of requiring the imperfect work to be removed and reconstructed, but he or she shall make such deductions therefor in the payments due or to become due the Contractor as may be just and reasonable.
7-06. Changes in the Work. The Engineer shall have the right, in writing, to order additions to, omissions from, or corrections, alterations and modifications in the line, grade, form, dimensions, plan, or kind or amount of work or materials herein contemplated, or any part thereof, either before or after the beginning of construction. However, the arithmetical sum of the cost to the City of additions and subtractions from the work under this contract shall not exceed 10 percent of original contract amount or $10,000, whichever is the greater, unless based upon a supplementary agreement to be made therefore.

The order of such additions, omissions, corrections, alterations and modifications shall be in writing and signed by the Engineer and, in order, shall then be binding upon the Contractor. The Contractor shall proceed with the work as changed and the value of such change shall be determined as provided for in section 10-07 of these Special Provisions.

Such alterations shall in no way affect, vitiate, or make void this contract or any part thereof, except that which is necessarily affected by such alterations and is clearly the evident intention of the parties to this contract. 7-07. Additional Drawings by City. The drawings made a part of this contract at the time of its execution are intended to be fairly comprehensive and to indicate in more or less detail the scope of the work. In addition to these drawings, however, the Engineer shall furnish such additional drawings from time to time during the progress of the work as are necessary to make clear or to define in greater detail the intent of the Special Provisions and the contract drawings and the Contractor shall make his or her work conform to all such drawings. 7-08. Additional and Emergency Protection. Whenever, in the opinion of the Engineer, the Contractor has not taken sufficient precautions for the safety of the public or the protection of the works to be constructed under this contract, or of adjacent structures or property which may be injured by the processes of construction on account of such neglect and whenever, in the opinion of the Engineer, an emergency shall arise and immediate action shall be considered necessary in order to protect public or private, personal or property interest, then and in that event, the Engineer, with or without notice to the Contractor may provide suitable protection to the said interests by

Page 280 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 15 Spec. No. 25-04
causing such work to be done and such material to be furnished as shall provide such protection as the Engineer may consider necessary and adequate.

The cost and expense of such work and material so furnished shall be borne by the Contractor and, if the same shall not be paid on presentation of the bills therefor, then such costs shall be deducted from any amounts due or to become due the Contractor.

The performance of such emergency work under the direction of the Engineer shall in no way relieve the Contractor from any damages which may occur during or after such precaution has been taken by the Engineer. 7-09. Suspension of Work. The City may at any time suspend the work or any part thereof by giving five (5) days written notice to the Contractor. The work shall be resumed by the Contractor within ten (10) days after the date fixed in the written notice from the City to the Contractor so to do. The City shall reimburse the Contractor for expense incurred by the Contractor in connection with the work under this contract as a result of such suspension.

If the work, or any part thereof, shall be stopped by the notice in writing aforesaid and if the City does not give notice in writing to the Contractor to resume work at a date within ten (10) days of the date fixed in the written notice to suspend, then the Contractor may abandon that portion of the work so suspended and he or she will be entitled to the estimates and payments for all work done on the portions so abandoned, if any, plus 5 percent of the value of the work so abandoned, to compensate for loss of overhead, plant expense and anticipated profit. 7-10. Right of City to Terminate Contract. If the Contractor should be adjudged a bankrupt, or if he or she should make a general assignment for the benefit of his or her creditors, or if a receiver should be appointed on account of his or her insolvency, or if he or she should persistently or repeatedly refuse or should fail, except in cases for which extension of time is provided, to supply sufficient properly skilled workmen or proper materials, or if he or she should fail to make prompt payments to subcontractors or for material or labor, or persistently disregard laws, ordinances or the instructions of the Engineer, or otherwise be guilty of a substantial violation of any provision of the contract, then the City, upon the certificate of the Engineer that sufficient cause exists to justify such action, may, without prejudice to any other right or remedy and after giving the Contractor seven days written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances and finish the work by whatever method the City may deem expedient. In such case, the Contractor shall not be entitled to receive any further payment until the work is finished. If the unpaid balance of the contract price shall exceed the expense of finishing the work, including compensation for additional managerial and administrative services, such excess shall be paid to the Contractor. If such expense shall exceed such unpaid balance, the Contractor shall pay the difference to the City. The expense incurred by the City as herein provided and the damage incurred through the Contractor's default, shall be certified by the Engineer. In the event that a termination under this section is determined to be improper, such termination shall be deemed a constructive termination for convenience taken pursuant to section 7-12 below. 7-11. Use of Completed Portions. The City shall have the right to take possession of and use any completed or partially completed portions of the work, notwithstanding the time for completing the entire work or such portions which may not have expired; but such taking possession and using shall not be deemed an acceptance of any work not completed in accordance with the contract documents. If such prior use increases the cost of or delays the work, the Contractor shall be entitled to such extra compensation, or extension of time or both, as the Engineer may determine.
7-12. Right of City to Terminate Contract for Convenience. The City may terminate performance of the work called for by the contract documents in whole or, from time to time, in part, if the City determines that a termination is in the City’s best interest. The Contractor shall terminate all or any part of the work upon delivery to the Contractor of a notice of termination specifying that the termination is for the convenience of the City, the extent of termination, and the effective date of such termination. After receipt of notice of termination, and except as directed by the Engineer, the Contractor shall, regardless of any delay in determining or adjusting any amounts due under this termination for convenience clause, immediately proceed with the following obligations:

1. Stop work as specified in the notice.

2. Complete any work specified in the notice of termination in a least cost/shortest time manner while still maintaining the quality called for under the contract documents.

3. Leave the property upon which the Contractor was working and upon which the facility (or facilities) forming the basis of the contract documents is situated in a safe and sanitary manner such that it does not pose any threat to the public health or safety.

Page 281 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 16 Spec. No. 25-04

4. Terminate all subcontracts to the extent that they relate to the portions of the work terminated.

5. Place no further subcontracts or orders, except as necessary to complete the continued portion of the contract.

6. Submit to the Engineer, within ten (10) calendar days from the effective date of the notice of termination, all of the usual documentation called for by the contract documents to substantiate all costs incurred by the Contractor for labor, materials and equipment through the effective date of the notice of termination.

Any documentation substantiating costs incurred by the Contractor solely as a result of the City's exercise of its right to terminate this Contract pursuant to this clause, which costs the contractor is authorized under the contract documents to incur, shall: (1) be submitted to and received by the Engineer no later than 30 calendar days after the effective date of the notice of termination; (2) describe the costs incurred with particularity; and (3) be conspicuously identified as “Termination Costs occasioned by the City's Termination for Convenience.”
Termination of the contract shall not relieve Surety of its obligation for any just claims arising out of or relating to the work performed. In the event that the City exercises its right to terminate this contract pursuant to this clause, the City shall pay the Contractor, upon the Contractor's submission of the documentation required by this clause and other applicable provisions of the contract documents, the following amounts:

All actual reimbursable costs incurred according to the provisions of this contract.

1. A reasonable allowance for profit on the cost of the Work performed, provided Contractor establishes to the satisfaction of the Engineer that it is reasonably probable that Contractor would have made a profit had the contract been completed and provided further, that the profit allowed shall in no event exceed fifteen (15%) percent of the costs.

2. A reasonable allowance for Contractor's administrative costs in determining the amount payable due to termination of the contract under this Article.

Notwithstanding any other provision of this Article, when immediate action is necessary to protect life and safety or to reduce significant exposure or liability, the City may immediately order Contractor to cease work on the project until such safety or liability issues are addressed to the satisfaction of the City or the contract is terminated.

SECTION 8. WORKMANSHIP, MATERIALS and EQUIPMENT
8-01. General Quality. Materials and equipment shall be new and of a quality equal to that specified or approved.

Work shall be done and completed in a thorough and workmanlike manner. 8-02. Quality in Absence of Detailed Specifications. Whenever under this contract it is provided that the Contractor shall furnish materials or manufactured articles or shall do work for which no detailed specifications are set forth, the materials or manufactured articles shall be of the best grade in quality and workmanship obtainable in the market from firms of established good reputation, or, if not ordinarily carried in stock, shall conform to the usual standards for first-class materials or articles of the kind required, with due consideration of the use to which they are to be put. In general, the work performed shall be in full conformity and harmony with the intent to secure the best standard of construction and equipment of the work as a whole or in part. 8-03. Materials and Equipment Specified by Name. Whenever any material or equipment is indicated or specified by patent or proprietary name or by the name of the manufacturer, such specification shall be considered as used for the purpose of describing the material or equipment desired and shall be considered as followed by the words "or approved equal". The Contractor may offer any material or equipment which shall be equal in every respect to that specified, provided that written approval first is obtained from the Engineer. 8-04. Source of Materials. Price, fitness and quality being equal, preference shall be given by the Contractor for supplies grown, manufactured or produced in the State of California and, next, for such products partially produced in this State in accordance with Government Code Section 4332. 8-05. Storage of Materials. Materials shall be so stored to ensure the preservation of their quality and fitness for the work. They shall be so located and disposed that prompt and proper inspection thereof may be made. 8-06. Drawings, Samples and Tests. As soon as possible after execution of the contract, the Contractor shall submit to the Engineer, in quintuplicate, sufficient information including, if necessary, assembly and detail drawings to demonstrate fully that the equipment and materials to be furnished comply with the provisions and intent of these Special Provisions and Drawings. If the information thus submitted indicates the equipment or materials is

Page 282 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 17 Spec. No. 25-04
acceptable, the Engineer will return one copy stamped with his or her approval; otherwise, one copy will be returned with an explanation of why the equipment or material is unsatisfactory. The Contractor shall have no claims for damages or for extension of time on account of any delay due to the revision of drawings or rejection of material. Fabrication or other work performed in advance of approval shall be done entirely at the Contractor's risk.

After approval of equipment or material, the Contractor shall not deviate in any way from the design and specifications given without the written consent of the Engineer.

When requested by the Engineer, a sample or test specimens of the materials to be used or offered for use in connection with the work shall be prepared at the expense of the Contractor and furnished by him or her in such quantities and sizes as may be required for proper examination and tests, with all freight charges prepaid and with information as to their sources.

All samples shall be submitted before shipment and in ample time to permit the making of proper tests, analyses, or examination before the time at which it is desired to incorporate the material into the work. All tests of materials furnished by the Contractor shall be made by the Engineer. Samples shall be secured and tested whenever necessary to determine the quality of the material.

SECTION 9. PROSECUTION OF WORK
9-01. Equipment and Methods. The work under this contract shall be prosecuted with all materials, tools, machinery, apparatus and labor and by such methods as are necessary to the complete execution of everything described, shown, or reasonably implied. If at any time before the beginning or during the progress of the work, any part of the Contractor's plant or equipment, or any of his or her methods of execution of the work, appear to the Engineer to be unsafe, inefficient, or inadequate to insure the required quality or the rate of progress of the work, he or she may order the Contractor to increase or improve his or her facilities or methods and the Contractor shall comply promptly with such orders; but, neither compliance with such orders nor failure of the Engineer to issue such orders shall relieve the Contractor from his or her obligation to secure the degree of safety, the quality of the work and the rate of progress required of the Contractor. The Contractor alone shall be responsible for the safety, adequacy and efficiency of his or her plant, equipment and methods. 9-02. Time of Completion. The Contractor shall promptly begin the work under this contract and shall complete and make ready for full use all portions of the project made the subject of this contract within the time set forth in the agreement bound herewith.
9-03. Avoidable Delays. Avoidable delays in the prosecution or completion of the work shall include all delays which might have been avoided by the exercise of care, prudence, foresight and diligence on the part of the Contractor. The City will consider as avoidable delays within the meaning of this contract (1) delays in the prosecution of parts of the work, which may in themselves be unavoidable, but do not necessarily prevent or delay the prosecution of other parts of the work nor the completion of the whole work within the time herein specified, (2) reasonable loss of time resulting from the necessity of submitting plans to the Engineer for approval and from the making of surveys, measurements, inspections, and testing and (3) such interruptions as may occur in the prosecution of the work on account of the reasonable interference of other contractors employed by the City which do not necessarily prevent the completion of the whole work within the time herein specified. 9-04. Unavoidable Delays. Unavoidable delays in the prosecution or completion of the work under this contract shall include all delays which may result, through cause beyond the control of the Contractor and which he or she could not have provided against by the exercise of care, prudence, foresight and diligence. Orders issued by the City changing the amount of work to be done, the quantity of material to be furnished or the manner in which the work is to be prosecuted and unforeseen delays in the completion of the work of other contractors under contract with the City will be considered unavoidable delays, so far as they necessarily interfere with the Contractor's completion of the whole of the work. Delays due to normally adverse weather conditions will not be regarded as unavoidable delays. However, truly abnormal amounts of rainfall, temperatures or other weather conditions for the location of the work and time of year may be considered as unavoidable delays if those conditions necessarily cause a delay in the completion of the work.
9-05. Notice of Delays. Whenever the Contractor foresees any delay in the prosecution of the work and, in any event, immediately upon the occurrence of any delay which the contractor regards as an unavoidable delay, he or

Page 283 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 18 Spec. No. 25-04
she shall notify the Engineer in writing of the probability of the occurrence of such delay and its cause, in order that the Engineer may take immediate steps to prevent, if possible, the occurrence or continuance of the delay, or, if this cannot be done, may determine whether the delay is to be considered avoidable or unavoidable, how long it continues and to what extent the prosecution and completion of the work are to be delayed thereby. 9-06. Extension of Time. Should any delays occur which the Engineer may consider unavoidable, as herein defined, the Contractor shall, pursuant to his or her application, be allowed an extension of time proportional to said delay or delays, beyond the time herein set forth, in which to complete this contract; and liquidated damages for delay shall not be charged against the Contractor by the City during an extension of time granted because of unavoidable delay or delays.

Any claim by Contractor for a time extension based on unavoidable delays shall be based on written notice delivered to the Engineer within 15 days of the occurrence of the event giving rise to the claim. Failure to file said written notice within the time specified shall constitute a waiver of said claim. Notice of the full extent of the claim and all supporting data must be delivered to the Engineer within 45 days of the occurrence unless the Engineer specifies in writing a longer period. All claims for a time extension must be approved by the Engineer and incorporated into a written change order.
9-07. Unfavorable Weather and Other Conditions. During unfavorable weather and other conditions, the Contractor shall pursue only such portions of the work as shall not be damaged thereby. No portions of the work whose satisfactory quality or efficiency will be affected by any unfavorable conditions shall be constructed while these conditions remain, unless, by special means or precautions approved by the Engineer, the Contractor shall be able to overcome them.

The Contractor shall be granted a time extension of one day for each unfavorable weather day which prevents him or her from placing concrete forms or placing and finishing concrete or asphalt concrete. Such unfavorable weather day is defined as a rain day where precipitation prevents the contractor from performing the work more than four (4) continuous hours within the authorized work period or a temperature day where the ambient temperature is below that specified for the placement of materials associated with the controlling work item for more than four (4) continuous work hours of the authorized work period.
9-08. Saturday, Sunday, Holiday and Night Work. No work shall be done between the hours of 6 p.m. and 7 a.m., nor on Saturdays, Sundays or legal holidays except such work as is necessary for the proper care and protection of work already performed, or except in cases of absolute necessity and in any case only with the permission of the Engineer.

It is understood, however, that night work may be established as a regular procedure by the Contractor if he or she first obtains the written permission of the Engineer and that such permission may be revoked at any time by the Engineer if the Contractor fails to maintain at night adequate force and equipment for reasonable prosecution and to justify inspection of the work.
9-09. Hours of Labor. Eight (8) hours of labor shall constitute a legal day's work and the Contractor or any subcontractor shall not require or permit more than eight hours of labor in a day from any person employed by him or her in the performance of the work under this contract, unless paying compensation for all hours worked in excess of eight (8) hours per day at not less than 1½ times the basic rate of pay. The Contractor shall forfeit to the City, as a penalty, the sum of twenty-five dollars ($25.00) for each workman employed in the execution of the contract by him or her or by any subcontractor, for each calendar day during which such laborer, workman, or mechanic is required or permitted to labor more than eight hours in violation of the provisions of Section 1810 to 1816, inclusive, (Article 3, Chapter 1, Part 7, Division 2) of the Labor Code of the State of California and any acts amendatory thereof.

SECTION 10. PAYMENT
10-01. Certification by Engineer. All payments under this contract shall be made upon the presentation of certificates in writing from the Engineer and shall show that the work covered by the payments has been done and the payments thereof are due in accordance with this contract.

Page 284 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 19 Spec. No. 25-04
10-02. Progress Estimates and Payment. The Engineer shall, within the first seven (7) days of each month, make an estimate of the value of the work performed in accordance with this contract during the previous calendar month.

The first estimate shall be of the value of the work satisfactorily completed in place and meeting the requirements of the contract. And every subsequent estimate, except the final estimate, shall be of the value of the work satisfactorily completed in place since the last preceding estimate was made; provided, however, that should the Contractor fail to adhere to the program of completion fixed in this contract, the Engineer shall deduct from the next and all subsequent estimates the full calculated accruing amount of the liquidated damages to the date of said estimate, until such time as the compliance with the program has been restored.

The estimate shall be signed by the Engineer and, after approval, the City shall pay or cause to be paid to the Contractor in the manner provided by law, an amount equal to 95 percent of the estimated value of the work satisfactorily performed and complete in place.
10-03. Substitution of Securities.

1. At such times that Pubic Contract Code Section 22300 is in effect Contractor may propose the substitution of securities of at least equal market value for any moneys to be withheld to ensure performance under the Contract.

Market value shall be determined as of the day prior to the date such substitution is to take place. Such substitution shall be made at the request and expense of the Contractor. The securities shall be one or more of the following types:
(a) Bonds or interest-bearing notes or obligations of the United States, or those for which the faith and credit of the United States are pledged for the payment of principal and interest. (b) Bonds or interest-bearing notes on obligations that are guaranteed as to principal and interest by a federal agency of the United States.
(c) Bonds of the State of California, or those for which the faith and credit of the State of California are pledged for the payment of principal and interest.
(d) Bonds or warrants, including, but not limited to, revenue warrants, of any county, city, metropolitan water district, California water district, California water storage district, irrigation district in the State of California, municipal utility district, or school district of the State of California, which are rated by Moody's or Standard and Poor as A or better.
(e) Bonds, consolidated bonds, collateral trust debentures, consolidated debentures, or other obligations issued by federal land banks or federal intermediate credit banks established under the Federal Farm Loan Act, as amended; debentures and consolidated debentures issued by the Central Bank for Cooperatives and banks for cooperatives established under the Farm Credit Act of 1933, as amended; bonds, or debentures of the Federal Home Loan Bank Board established under the Federal Home Loan Bank Act; and stock, bonds, debentures and other obligations of the Federal National Mortgage Association established under the National Housing Act as amended and bonds of any Federal Home Loan Mortgage Corporation.
(f) Commercial paper of "prime" quality as defined by a nationally recognized organization which rates such securities. Eligible paper is further limited to issuing corporations: (1) organized and operating within the United States; (2) having total assets in excess of five hundred million dollars ($500,000,000); and (3) approved by the Pooled Money Investment Board of the State of California. Purchases of eligible commercial paper may not exceed 180 days' maturity, nor represent more than 10 percent of the outstanding paper of an issuing corporation.
(g) Bills of exchange or time drafts on and accepted by a commercial bank, otherwise known as bankers acceptances, which are eligible for purchase by the Federal Reserve System. (h) Certificates of deposits issued by a nationally or state-chartered bank or savings and loan association.

Page 285 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 20 Spec. No. 25-04
(i) The portion of bank loans and obligations guaranteed by the United States Small Business Administration or the United States Farmers Home Administration. (j) Student loan notes insured under the Guaranteed Student Loan Program established pursuant to the Higher Education Act of 1965, as amended (20 U.S.C. 1001, et seq.) and eligible for resale to the Student Loan Marketing Association established pursuant to Section 133 of the Education Amendments of 1972, as amended (20 U.S.C. 1087-2).
(k) Obligations issued, assumed or guaranteed by International Bank for Reconstruction and Development, the Inter-American Development Bank, the Asian Development Bank, or the Government Development Bank of Puerto Rico.
(l) Bonds, debentures and notes issued by corporations organized and operating within the United States.

Such securities eligible for substitution shall be within the top three ratings of a nationally recognized rating service.

2. The securities shall be deposited with City or with any commercial bank as escrow agent, who shall arrange for transfer of such securities to the Contractor upon satisfactory completion of the contract. Any interest accrued or paid on such securities shall belong to the Contractor and shall be paid upon satisfactory completion of the contract.

The market value of the securities deposited shall at all times be maintained in an amount at least equal, in the sole judgment of City, to the moneys to be withheld pursuant to the Contract Documents to ensure performance of the Contract. In order to comply with this condition, Contractor shall deposit additional securities as necessary upon request by City or the escrow agent.

3. Upon acceptance of any Proposal that includes substituting securities for amounts withheld to ensure performance, a separate escrow agreement satisfactory in form and substance to City shall be prepared and executed by City, the Contractor and the escrow agent, which may be City. The escrow agreement shall specify, among other matters, value of securities to be deposited; procedures for valuing the securities and for adding or withdrawing securities to maintain the market value of the deposited securities at least equal to the amount of moneys which would otherwise be withheld; the terms and conditions of conversion to cash in case of the default by the Contractor; and terms, conditions and procedure for termination of the escrow. City shall have no obligation to enter any such Agreement that does not provide the City with the unilateral right to convert securities to cash and to gain immediate possession of the cash.
10-04. Acceptance. The work must be accepted by vote of the City Council of the City of Ukiah when the whole shall have been completed satisfactorily. The Contractor shall notify the Engineer, in writing, of the completion of the work, whereupon the Engineer shall promptly, by personal inspection, satisfy himself as to the actual completion of the work in accordance with the terms of the contract and shall thereupon recommend acceptance by the City Council.
10-05. Final Estimate and Payment. The Engineer shall, as soon as practicable after the final acceptance of the work done under this contract, make a final estimate of the amount of work done thereunder and the value thereof.

Such final estimate shall be signed by the Engineer, and after approval, the City shall pay or cause to be paid to the Contractor, in the manner provided by law, the entire sum so found to be due hereunder, after deducting therefrom all previous payments and such other lawful amounts as the terms of this contract prescribe.

In no case will final payment be made in less than thirty-five (35) days after the filing of the notice of completion with the County Recorder.
10-06. Delay Payments. Should any payment due the Contractor or any estimate be delayed, through fault of the City beyond the time stipulated, such delay shall not constitute a breach of contract or be the basis for a claim for damages, but the City shall pay the Contractor interest on the amount of the payment at the rate of 6 percent per annum for the period of such delay. The terms for which interest will be paid shall be reckoned, in the case of any monthly or progress payment, from the twentieth day of the month next succeeding the month in which the work was performed to the date of payment of the estimate; and in the case of the final estimate, from the forty-fifth day after acceptance to the date of payment of the final estimate.

Page 286 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 21 Spec. No. 25-04
The date of payment of any estimate shall be considered the day on which the payment is offered or mailed as evidenced by the records of the Treasurer of the City. If interest shall become due on any delayed payment, the amount thereof, as determined by the City, shall be added to a succeeding payment. If the interest shall become due on the final payment, it shall be paid on a supplementary voucher to interest or any sum or sums which, by the terms of this contract, the City is authorized to reserve or retain. 10-07. Extra Work and Work Omitted. Whenever corrections, alterations, or modifications of the work under this contract ordered by the Engineer and approved by the City increase the amount of work to be done, such added work shall be known as "extra work"; and when such corrections, alterations, or modifications decrease the amount of work to be done, such subtracted work shall be known as "work omitted".

When the Contractor considers that any changes ordered involve extra work, he or she shall immediately notify the Engineer in writing and subsequently keep him or her informed as to when and where extra work is to be performed and shall make claim for compensation therefor each month not later than the first day of the month following that in which the work claimed to be extra work was performed and he or she shall submit a daily complete statement of materials and labor used and expenses incurred on account of extra work performed, showing allocation of all materials, labor and expenses.

All such claims shall state the date of the Engineer's written order and the date of approval by the City authorizing the work on account of which claim is made. Unless such notification is made in writing within the time specified and unless complete statements of materials used and expenses incurred on account of such extra work are furnished as above required, the Contractor shall not be entitled to payment on account of extra work and Contractor shall be deemed to have waived the right to make any future claims for compensation for such extra work.

When changes decrease the amount of work to be done, they shall not constitute a claim for damages on account of anticipated profits on the work that may be omitted. 10-08. Compensation for Extra Work or Work Omitted. Whenever corrections, additions, or modifications in the work under this contract change the amount of work to be done or the amount of compensation due the Contractor, excepting increases or decreases in contract items having unit contract prices for each measurable quantity installed in place, and such changes have been ordered in writing by the Engineer and approved by the City prior to the Contractor performing the extra work, then a price may be agreed upon. Failing such an agreement in price, the Contractor shall be compensated for performing extra work pursuant to the provisions of Section 4-1.03 D,"Extra Work", and Section 9-1.03,"Force Account Payment" of the Standard Specifications.

This method of determining the price of work shall not apply to the performance of any work which is required or reasonably implied to be performed or furnished under this contract. 10-09. Compensation to the City for Extension of Time. In case the work called for under this contract is not completed within the time limit stipulated herein, the City shall have the right as provided hereinabove, to extend the time of completion thereof. If the time limit be so extended, the City shall have the right to charge to the Contractor and to deduct from the final payment for the work the actual cost to the City of engineering, inspection, superintendence and other overhead expenses which are directly chargeable to the contract and which accrue during the period of such extension, except that the cost of final unavoidable delays shall not be included in such charges.
10-10. Liquidated Damages for Delay. It is agreed by the parties to the contract that time is of the essence and that, in case all the work is not completed before or upon the expiration of the time limit as set forth, damage, other than those cost items identified in section 10-09, will be sustained by the City and that it is and will be impracticable to determine the actual amount of damage by reason of such delay; and it is therefore agreed that the Contractor will pay to the City the sum of five hundred dollars ($500.00) per day for each and every calendar day's delay beyond the time prescribed.

In compliance with the provisions of California Public Contract Code § 7102, the Contractor will be compensated for damages incurred due to delays in completing the work due solely to the fault of the City, where such delay is unreasonable under the circumstances and not contemplated by the parties. The Contractor and City agree that determining actual damages is impracticable and extremely difficult. As such, the Contractor shall be entitled to the

Page 287 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 22 Spec. No. 25-04
appropriate time extension and to payment of liquidated damages in the sum of $250 per day of delay in excess of the time specified for the completion of the work. Such amount shall constitute the only payment allowed and shall necessarily include all overhead (direct or indirect), all profit, all administrative costs, all bond costs, all labor, materials, equipment and rental costs, and any other costs, expenses and fees incurred or sustained as a result of such delay. The Contractor expressly agrees to be limited solely to the liquidated damages for all such delays as defined in this subsection.

SECTION 11. MISCELLANEOUS
11-01. Notice. Whenever any provision of the contract documents requires the giving of written notice, it shall be deemed to have been validly given if delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended, or if delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. If mailed, the notice shall be deemed received on the date of delivery stated in the return receipt.
11-02. Computation of Time. When any period of time is referred to in the Contract Documents by days, it shall be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day shall be omitted from the computation.
11-03. Claims Procedure
Contractor shall timely comply with all notices and requests for changes to the contract time or contract price, as a prerequisite to filing any claim governed by this Article. The failure to timely submit a notice of delay or notice of change, or to timely request a change to the contract time or contract price, or to timely provide any other notice or request required herein shall constitute a waiver of the right to further pursue the claim under the contract or at law.

A. Intent. Effective January 1, 1991, Section 20104 et seq., of the California Public Contract Code prescribes a process utilizing informal conferences, non-binding judicial supervised mediation, and judicial arbitration to resolve disputes on construction claims of $375,000 or less. Effective January 1, 2017, Section 9204 of the Public Contract Code prescribes a process for negotiation and mediation to resolve disputes on construction claims. The intent of this Article is to implement Sections 20104 et seq. and Section 9204 of the California Public Contract Code. This Article shall be construed to be consistent with said statutes.

B. Claims. For purposes of this Article, “Claim” means a separate demand by the Contractor, for (A) a time extension, (B) payment of money or damages arising from work done by or on behalf of the Contractor pursuant to the Contract, or (C) an amount the payment of which is disputed by the District.

Claims governed by this Article may not be filed unless and until the Contractor completes all procedures for giving notice of delay or change and for the requesting of a time extension or change order. Claims governed by this Article must be filed no later than the date of final payment. The claim shall be submitted in writing to the District and shall include on its first page the following in 16 point capital font: “THIS IS A CLAIM.” Furthermore, the claim shall include the documents necessary to substantiate the claim. Nothing herein is intended to extend the time limit or supersede notice requirements otherwise provided by contract for the filing of claims, including all requirements pertaining to compensation or payment for extra work, disputed work, and/or changed conditions.

Failure to follow such contractual requirements shall bar any claims or subsequent lawsuits for compensation or payment thereon.

C. Supporting Documentation. The Contractor shall submit all claims in the following format:

Summary of claim merit and price, reference Contract Document provisions pursuant to which the claim is made
List of documents relating to claim:

Specifications
Drawings
Clarifications (Requests for Information)
Schedules

Page 288 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 23 Spec. No. 25-04
Other
Chronology of events and correspondence
Analysis of claim merit
Analysis of claim cost
Time impact analysis in CPM format
If Contractor’s claim is based in whole or in part on an allegation of errors or omissions in the Drawings or Specifications for the project, Contractor shall provide a summary of the percentage of the claim subject to design errors or omissions and shall obtain a certificate of merit in support of the claim of design errors and omissions.

D. City’s Response. Upon receipt of a claim pursuant to this Article, City shall conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide the Contractor a written statement identifying what portion of the claim is disputed and what portion is undisputed. Any payment due on an undisputed portion of the claim will be processed and made within 60 days after the City issues its written statement.

If the City needs approval from its governing body to provide the Contractor a written statement identifying the disputed portion and the undisputed portion of the claim, and the City’s governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, the City shall have up to three days following the next duly publicly noticed meeting of the City’s governing body after the 45-day period, or extension, expires to provide the Contractor a written statement identifying the disputed portion and the undisputed portion.

Within 30 days of receipt of a claim, the City may request in writing additional documentation supporting the claim or relating to defenses or claims the District may have against the Contractor. If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of City and the Contractor. The City’s written response to the claim, as further documented, shall be submitted to the Contractor within 30 days (if the claim is less than $15,000, within 15 days) after receipt of the further documentation, or within a period of time no greater than that taken by the Contractor in producing the additional information or requested documentation, whichever is greater.

E. Meet and Confer. If the Contractor disputes the City’s written response, or the City fails to respond within the time prescribed, the Contractor may so notify the City, in writing, either within 15 days of receipt of the City’s response or within 15 days of the City’s failure to respond within the time prescribed, respectively, and demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand, the City shall schedule a meet and confer conference within 30 days for settlement of the dispute.

F. Mediation. Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the City shall provide the Contractor a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the City issues its written statement. Any disputed portion of the claim, as identified by the Contractor in writing, shall be submitted to nonbinding mediation, with the City and the Contractor sharing the associated costs equally. The City and Contractor shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing, unless the parties agree to select a mediator at a later time.

If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator.

For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.

Unless otherwise agreed to by the City and the Contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Public Contract Code Section 20104.4 to mediate after litigation has been commenced.

Page 289 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 24 Spec. No. 25-04
The mediation shall be held no earlier than the date the Contractor completes the work or the date that the Contractor last performs work, whichever is earlier. All unresolved claims shall be considered jointly in a single mediation, unless a new unrelated claim arises after mediation is completed.

G. Procedures After Mediation. If following the mediation, the claim or any portion remains in dispute, the Contractor must file a claim pursuant to Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code prior to initiating litigation. For purposes of those provisions, the running of the period of time within which a claim must be filed shall be tolled from the time the Contractor submits his or her written claim pursuant to subdivision (a) until the time the claim is denied, including any period of time utilized by the meet and confer conference.

H. Civil Actions. The following procedures are established for all civil actions filed to resolve claims of $375,000 or less:

Within 60 days, but no earlier than 30 days, following the filing or responsive pleadings, the court shall submit the matter to non-binding mediation unless waived by mutual stipulation of both parties or unless mediation was held prior to commencement of the action in accordance with Public Contract Code section 9204 and the terms of this Contract. The mediation process shall provide for the selection within 15 days by both parties of a disinterested third person as mediator, shall be commenced within 30 days of the submittal, and shall be concluded within 15 days from the commencement of the mediation unless a time requirement is extended upon a good cause showing to the court.

If the matter remains in dispute, the case shall be submitted to judicial arbitration pursuant to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, notwithstanding Section 1114.11 of that code. The Civil Discovery Act of 1986 (Article 3 (commencing with Section 2016) of Chapter 3 of Title 3 of Part 4 of the Code of Civil Procedure) shall apply to any proceeding brought under this subdivision consistent with the rules pertaining to judicial arbitration. In addition to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, (A) arbitrators shall, when possible, be experienced in construction law, and (B) any party appealing an arbitration award who does not obtain a more favorable judgment shall, in addition to payment of costs and fees under that chapter, also pay the attorney’s fees on appeal of the other party.

I. Government Code Claims. In addition to any and all contract requirements pertaining to notices of and requests for compensation or payment for extra work, disputed work, construction claims and/or changed conditions, the Contractor must comply with the claim procedures set forth in Government Code Sections 900, et seq. prior to filing any lawsuit against the City. Such Government Code claims and any subsequent lawsuit based upon the Government Code claims shall be limited to those matters that remain unresolved after all procedures pertaining to extra work, disputed work, construction claims, and/or changed conditions have been followed by Contractor. If no such Government Code claim is submitted, or if the prerequisite contractual requirements are not satisfied, no action against the City may be filed. A Government Code claim must be filed no earlier than the date the work is completed or the date the Contractor last performs work on the project, whichever occurs first. A Government Code claim shall be inclusive of all unresolved claims unless a new unrelated claim arises after the Government Code claim is submitted.

J. Non-Waiver. The City’s failure to respond to a claim from the Contractor within the time periods described in this Article or to otherwise meet the time requirements of this Article shall result in the claim being deemed rejected in its entirety.
11-04. Litigation and Forum Selection. Contractor and City stipulate and agree that any litigation relating to the enforcement or interpretation of this contract, arising out of Contractor's performance or relating in any way to the work shall be brought in Mendocino County and that venue will lie in Mendocino County.

Except as otherwise expressly provided by law, the parties waive any objections they might otherwise have to the propriety of jurisdiction or venue in the state courts in Mendocino County and agree that California law shall govern any such litigation.

Page 290 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 25 Spec. No. 25-04
The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto and, in particular but without limitation, the warranties, guaranties and obligations imposed upon the Contractor and all of the rights and remedies available to the City thereunder, shall be in addition to and shall not be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by law or contract, by special warranty or guaranty, or by other provisions of the contract documents and the provisions of this paragraph shall be as effective as if repeated specifically in the contract documents in connection with each particular duty, obligation, right and remedy to which they apply. All warranties and guaranties made in the contract document shall survive final payment and termination or completion of this contract. The City disclaims an express or implied warranty that the plans and specifications identify all site conditions that could affect the time or cost to complete the Work. 11-05. Waiver. The Contractor shall strictly comply with all notices and other contract requirements. Waiver by the City of any failure of the Contractor to comply with any term of the contract, including the notice provisions, shall not be deemed a waiver of a subsequent breach.

Page 291 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 26 Spec. No. 25-04

TECHNICAL SPECIFICATIONS
SECTION 12. GENERAL INFORMATION
12-01. Location and Scope of Work. All of the work to be performed is within the City of Ukiah and consists of a comprehensive remodel of the former Bank of America building located at 501 South State Street in Ukiah, California. The remodel will modernize the facility, enhance functionality, and address updates to the interior and exterior spaces. This includes structural improvements, mechanical, electrical, and plumbing upgrades, and refinishing work to ensure the building meets contemporary standards.

The remodel will incorporate the construction of new interior spaces, installation of modern systems, and repair of structural elements to create a functional and aesthetically appealing environment.

The remodel will include the following work:

The existing interior spaces will be upgraded with new restrooms, complete with modern fixtures, partitions, grab bars, and finishes. A new service counter will be installed, designed to enhance customer service and workflow efficiency. Doorways will be reconfigured, with new doors and hardware installed to improve access and functionality throughout the building. The interior will also include a new staff sink in designated areas and the installation of an elevator to provide access between floors. New fire extinguisher cabinets, updated signage throughout the facility, and repairs to interior stairs will ensure compliance with modern standards and improve overall safety. Flooring surfaces throughout the building will be leveled and refinished, providing a smooth and visually appealing result.

Exterior improvements will include upgrades to the site’s parking areas and construction of ramps to enhance access. Grading and paving work will be conducted as needed to address slopes and transitions, ensuring a seamless and updated exterior environment.

Mechanical, electrical, and plumbing work will include updates to plumbing systems with the installation of new domestic water piping, sanitary waste systems, and fixtures. The HVAC system will be modified to accommodate the remodeled layout, with adjustments to ductwork and insulation. Electrical upgrades will involve installing new circuits, wiring, and lighting systems for both the interior and exterior, ensuring sufficient power and lighting throughout the building. Internet access will be provided for new building systems, ensuring connectivity and operational efficiency.

Deferred submittals will include detailed plans for review and approval of specific items such as non-structural seismic supports and systems related to the remodel. All work will be conducted per approved plans, specifications, and applicable building codes, ensuring a high standard of construction quality.

Mock-ups will be provided for review and approval of critical finishes, including paint, tile, and other materials.

Inspections will be coordinated at key stages to verify compliance with project specifications. Detailed "as-built" drawings will be maintained, and training manuals for new systems will be provided upon completion. A final walkthrough will confirm compliance with all project requirements, addressing any remaining items on the punch list.

At the conclusion of the project, all required documentation, including warranties, maintenance manuals, and final "as-built" drawings, will be submitted. The site will be turned over in a clean and orderly condition, ensuring the building is fully operational and ready for use as specified.

General locations of the work are 501 South State Street, Ukiah CA 95482.

The Contractor should familiarize himself with the local conditions of the project sites. Failure to do so will in no way relieve him of the responsibility for performing any of the work or operations required as a part of this contract.

Further information regarding the work or these specifications can be obtained from Myles Fisette at (707) 463- 6225.

Page 292 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 27 Spec. No. 25-04
12-02. Arrangement of Technical Specifications. The Technical Specifications are provided as Appendix A, arranged in sections covering the various phases of work as follows:

DIVISION 0 – PROCUREMENT AND CONTRACTING REQUIREMENTS
DIVISION 1 – GENERAL REQUIREMENTS
DIVISION 2 – EXISTING CONDITIONS
DIVISION 3 – CONCRETE
DIVISION 4 – MASONRY
DIVISION 5 – METALS
DIVISION 6 – WOOD AND PLASTICS
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
DIVISION 8 – DOORS AND WINDOWS
DIVISION 9 – FINISHES
DIVISION 10 – SPECIALTIES
DIVISION 11 – EQUIPMENT
DIVISION 12 – FURNISHINGS
DIVISION 13 – SPECIAL CONSTRUCTION
DIVISION 14 – CONVEYING SYSTEMS
DIVISION 21 – FIRE SUPPRESSION
DIVISION 22 – PLUMBING
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) DIVISION 26 – ELECTRICAL
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
DIVISION 31 – EARTHWORK
DIVISION 32 – EXTERIOR IMPROVEMENTS
DIVISION 33 – WATER UTILITIES
12-03. Arrangement of Plans. General locations and linear quantities of the work are shown in Appendix "A". A map will be provided to the successful bidder showing the exact locations of the work to be done. 12-04. Business Licenses. The Contractor and any subcontractors shall each secure and maintain a valid City of Ukiah Business License prior to the start of any portion of the work. 12-05. Permits. The Contractor shall provide, procure, and pay for all permits required to complete this work. 12-06. Standard Specifications and Standard Plans. The Standard Specifications and Standard Plans of the California State Department of Transportation, 2018, are hereby made a part of these Special Provisions and are hereinafter referred to as "California Standard Specifications" and "California Standard Plans." Whenever in the California Standard Specifications and the California Standard Plans the following terms are used, they shall be understood to mean and refer to the following:

Department of Transportation - The City Council.

Director of Public Works - The City of Ukiah Director of Public Works.

Engineer - The Engineer, designated by the City Council, acting either directly or through properly authorized agents, such agents acting within the scope of the particular duties entrusted to them.

Laboratory - The designated laboratory authorized by the City of Ukiah to test materials and work involved in the contract.

State - The City of Ukiah
Other terms appearing in the California Standard Specifications and the California Standard Plans shall have the intent and meaning specified in Section I, Definition of Terms of the California Standard Specifications.

Page 293 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 28 Spec. No. 25-04
In case of discrepancy between the contract documents, the order of precedence from the highest to lowest is as follows:

1. (City) Special Provisions

2. (City) Project Plans

3. City Standard Plans and Details

4. California Standard Plans

5. California Standard Specifications
12-07. Temporary Facilities. All temporary facilities are the responsibility of the Contractor. The removal of said facilities shall be the responsibility of the Contractor. The Contractor shall be responsible for any and all damages to existing facilities which are a result of the work.
12-08. Public Convenience and Safety. The Contractor shall conduct operations so as to cause the least possible obstruction and inconvenience to public traffic. The Contractor shall, at his or her expense, furnish such flag persons and furnish, erect, construct and maintain such fences, barriers, lights, signs, detours, pedestrian walkways, driveway ramps and bridging as may be necessary to give adequate warning to the public that work is in progress and that dangerous conditions exist, to provide access to abutting properties and to permit the flow of pedestrian and vehicular traffic to safely and expeditiously pass the work. 12-09. Maintaining Traffic. Attention is directed to Section 7-1.08, "Public Convenience," 7-1.09, "Public Safety," 7-1.092, "Lane Closure," and 7-1.095, "Flagging Costs," of the California Standard Specifications.

Streets shall be open to through vehicular traffic during non-working hours. All public traffic shall be permitted to pass through the work with as little inconvenience and delay as possible.

Full costs for "Maintaining Traffic", including "Flagging Costs", shall be considered as included in the various items of work and no additional compensation will be made.

12.10. Stream Pollution. The Contractor shall exercise every reasonable precaution to prevent muddying or silting of live streams, and the Contractor's attention is called to the fact that the terms of this contract do not relieve him or her of responsibility for compliance with Sections 5650 and 12015 of the Fish and Game Code or other applicable statutes relating to pollution prevention or abatement. 12-11. Warranties. Unless otherwise indicated, the Contractor shall warrant all materials provided and work performed under this contract for a period of one year from the date of final acceptance. He shall replace promptly and at his own expense any materials and/or workmanship which fail during this warranty period. 12-12. Utilities. No water, sewer or electrical services will be provided by the owner. It is the Contractor's sole responsibility to arrange such services as necessary.
12-13. Preconstruction Conference. A preconstruction conference will be held before any work will be allowed to commence. This meeting will cover inspection, schedule for work, and among other items, the responsibilities and procedures of each of the interested parties to assure that the project will be completed in accordance with the contract documents.
12-14. Safety Requirements. The Contractor shall comply with all pertinent provisions of the Department of Labor "Safety and Health Regulations for Construction (29 FCS Part 1518, 36 CFR 7340)", with additions or modifications thereto, in effect during construction of this project.

Page 294 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 29 Spec. No. 25-04
SECTION 13 - CONSTRUCTION DETAILS
13-01. Technical Specifications. See Appendix A.

13-02. Project Drawings. See Attachment A.

SECTION 14. EXCLUSIONS FROM GENERAL CONDITIONS
14-01. Provisions to be Excluded from General Conditions. The following designated provisions of the General Conditions are hereby determined to be inapplicable to the proposed work and, therefore, are hereby excluded from the terms of the Notice to Bidders, Proposal, Agreement and other contract documents as though entirely omitted from said General Conditions:
(1) Section 6-02. Office at the Site
(2) Section 7-03. Surveys
No other exclusions.

SECTION 15. AMENDMENTS TO GENERAL CONDITIONS
15-01. Sections of General Conditions to be Amended.

The following designated sections of the Special Provisions are hereby amended to read as follows:

No amendments.

Page 295 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 30 Spec. No. 25-04

BID SUBMITTAL CHECKLIST
The following is a checklist to assist you in your submission of your bid documents. Please make sure you include the following when submitting your bid documents to reduce the risk of having your bid rejected:

Did you include?...
o Proposal (Page 31)
 Unit prices filled out clearly.
 Extended prices filled out clearly and calculated correctly  Total bid amount filled out clearly and calculated correctly  Sign the proposal, and provide complete information
 CLSB No. and expiration date
 Department of Industrial Relations Public Works Contractor Registration Number o Fair Employment Practices Certification (Page 41)
 Filled out completely per instruction
o Worker’s Compensation Certificate (Page 42)
 Filled out completely per instruction
o Certification of Non-Discrimination in Employment (Page 43)  Filled out completely per instruction
o List of Proposed Subcontractors (Page 44)
 Filled out completely per instruction
o Statement of Experience (Page 45)
o Signature of Bidder (Page 46)
 Filled out completely per instruction
 Authorized signature provided
o Bidder’s Bond (Page 47)
 Filled out completely per instruction
o Non-Collusion Affidavit (Page 48)
 Filled out completely per instruction
 Notarized
o Addenda Issued
 Check the City website for any addenda issued: www.cityofukiah.com/purchasing Please note that actual acknowledgment of addenda is not required to submit with your bid. Refer to Section 1-11 and 3-07 of the General Conditions.

Page 296 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 31 Spec. No. 25-04

CITY OF UKIAH

MENDOCINO COUNTY, CALIFORNIA

PROPOSAL
FOR
REMODEL OF 501 SOUTH STATE STREET
Specification No. 25-04
The undersigned, as bidder,
declares that he or she has examined thoroughly all of the contract documents herein contained, that this proposal is made without collusion with any other person, firm or corporation and that all laws and ordinances relating to the interest of public officers in this contract have been complied with in every respect.

AND he or she proposes and agrees, if this proposal is accepted, 1) that he or she will contract with the City of Ukiah, Mendocino County, California, in the form of the copy of the agreement herein contained
a) to provide all necessary machinery, tools, apparatus and other means of construction; b) to furnish all materials;
c) to provide all superintendence, overhead expenses and all labor and expenses of whatever nature necessary to complete the job in conformity with the specifications and drawings and other contract provisions herein or reasonably implied hereby or as necessary to complete the work in the manner and within the time named herein and according to the requirements and to the reasonable satisfaction of the City Engineer;
d) to pay all charges of freight transportation and hauling; 2) that he or she indemnifies the City against any loss or damage arising from any act of the undersigned as Contractor; and
3) that he or she will accept as full payment therefor the following sums:

Page 297 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 32 Spec. No. 25-04

BIDDING SCHEDULE
In the case of any discrepancy between the unit price and the total set forth for the item, the unit price shall prevail; provided, however, that if the amount set forth as a unit price is ambiguous, unintelligible or uncertain for any reason, or is omitted, or in the case of lump sum items, is not the same amount as the entry in the “Total” column, then the amount set forth in the “Total” column for the item shall prevail in accordance with the following:

1. As to lump sum items, the amount set forth in the “Total” column shall be the unit price;

2. As to unit basis items, the amount set forth in the “Total” column shall be divided by the estimated quantity for the item and the price thus obtained shall be the unit price.

The Total Base Bid shall be the sum of the items in the “Total” column. In case of discrepancy between the sum of the items in the “Total” column and the amount entered as Total Base Bid, the sum of the “Total” column items shall prevail. The bid comparison will be based on the sum of the items in the “total” column for each bidder.

The Unit prices for the various Construction Items below include all costs associated with the General Conditions, Special Provisions, Requirements of the Construction Contract, and represent the total, complete, in-place cost for each specific Construction Item in accordance with the Construction Documents, including all elements, work components, accessories, and connections, shown in applicable details or required to yield a complete, sound and functional component or system appropriate for its intended function, whether or not such is specifically described or listed in any description of measurement or payment. The total amount of the Construction items below shall represent the total and complete cost of the fully functional Project. All work not specifically listed below be required to complete the work of the various construction items and the cost of such shall be considered as included throughout the various unit prices indicated.

Lowest bid will be based on the lowest Base Bid.

Page 298 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 33 Spec. No. 25-04
NAME OF BIDDER:

SPEC #: 25-04
PROJECT NAME: REMODEL OF 501 SOUTH STATE STREET
ITEM# DESCRIPTION UNIT OF

MEASURE

QUANTITY UNIT PRICE TOTAL
1 Temporary Controls, Fencing & Signage LS 1
$__________ $__________________
2 Mobilization LS 1
$__________ $__________________
3 Div 02 - Demolition LS 1
$__________ $__________________
4 Div 03 - Concrete LS 1
$__________ $__________________
5 Div 05 - Metal Fabrications LS 1
$__________ $__________________
6 Div 06 - Wood LS 1
$__________ $__________________
7 Div 07 - Insulation & Waterproofing LS 1
$__________ $__________________
8 Div 08 - Doors & Windows LS 1
$__________ $__________________
9 Div 09 - Finishes LS 1
$__________ $__________________
10 Div 10 - Signage & Accessories LS 1
$__________ $__________________
11 Div 13 - Non-Structural Seismic Restraints LS 1
$__________ $__________________
12 Div 14 - Elevator LS 1
$__________ $__________________
13 Div 21 - Wet Pipe Sprinkler Systems LS 1
$__________ $__________________
14 Div 22 - Plumbing LS 1
$__________ $__________________
15 Div 23 - Mechanical LS 1
$__________ $__________________
16 Div 26 - Electrical LS 1
$__________ $__________________
17 Div 28 - Access Control LS 1
$__________ $__________________

Page 299 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 34 Spec. No. 25-04
18 Div 31 - Earthwork LS 1
$__________ $__________________
19 Div 32 - Site Improvements LS 1
$__________ $__________________
20 Div 33 - Sanitary Sewer LS 1
$__________ $__________________
ABI 1 New Transformer - including Demo of
Existing Transformer & Site Work
LS 1
$__________ $__________________
TOTAL BID ==>> $__________________
We, the undersigned, acknowledge that the City Council has reserved the right to reject any or all bids and to determine which proposal is, in its opinion, the lowest responsive bid from a responsible bidder and that which it deems in the best interest of the City to accept. We, the undersigned, further agree, if this proposal shall be accepted, to sign the agreement and to furnish the required bonds with satisfactory surety, or sureties, within fifteen (15) calendar days after written notice that the contract is ready for signature; and, if the undersigned shall fail to contract, as aforesaid, it shall be understood that he or she has abandoned the contract and that, therefore, this proposal shall be null and void and the proposal guaranty accompanying this proposal, or the amount of said guaranty, shall be forfeited to and become the property of the City. Otherwise, the proposal guaranty accompanying this proposal shall be returned to the undersigned.

Witness our hands this day of ___________________, 20____.

Licensed in accordance with an act providing for the registration of California Contractors License No. ___________, expiration date _____________.

THE CONTRACTOR'S LICENSE NUMBER AND EXPIRATION DATE STATED HEREIN ARE MADE UNDER PENALTY OF PERJURY.

Department of Industrial Relations Public Works Contractor Registration Number:_____________________ Signature of bidder or bidders, with business name, address, phone number and fax number:
_________________________________________________________________ _________________________________________________________________ _________________________________________________________________ _________________________________________________________________ Notice: In the case of a corporation, give below the addresses of the principal office thereof and names and addresses of the President, Secretary, Treasurer.
_________________________________________________________________ _________________________________________________________________ _________________________________________________________________

Page 300 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 35 Spec. No. 25-04

FAIR EMPLOYMENT PRACTICES CERTIFICATION
TO:_____________________________________________________________ ________________________________________________________________ The undersigned, in submitting a bid for performing the following work by Contract, hereby certifies that he or she has or will meet the standards of affirmative compliance with the Fair Employment Practices requirements of the Special Provisions contained herein.

REMODEL OF 501 SOUTH STATE STREET
________________________________________________________________ (Signature of Bidder)
Business Mailing Address:
_________________________________________________
_________________________________________________
_________________________________________________
Business Location:
_________________________________________________
_________________________________________________
(The bidder shall execute the certification of this page prior to submitting his or her proposal.)

Page 301 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 36 Spec. No. 25-04

WORKER'S COMPENSATION CERTIFICATE
I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for Worker's Compensation or undertake self-insurance in accordance with the provisions of that code and I will comply with such provisions before commencing the performance of the work of this contract.

Witness my hand this________ day of _______________, 200____ Signature of Bidder, with Business Address:
__________________________________________________
__________________________________________________
__________________________________________________
__________________________________________________

Page 302 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 37 Spec. No. 25-04

CERTIFICATION OF NONDISCRIMINATION IN EMPLOYMENT
The bidder represents that he or she has/has not, participated in a previous contract or subcontract subject to either the equal opportunity clause herein or the clause contained in Section 301 of Executive Order 10925; that he or she has/has not, filed all required compliance reports; and that representations indicating submission of required compliance prior to subcontract awards.

Signature and address of Bidder:
__________________________________________________ Date_____________ __________________________________________________
__________________________________________________
__________________________________________________
(This certification shall be executed by the bidder in accordance with Section 60-1.6 of the Regulations of the President's Committee on Equal Employment Opportunity for implementing Executive Orders 10925 and 11114.)

Page 303 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 38 Spec. No. 25-04

LIST OF PROPOSED SUBCONTRACTORS
In compliance with the provisions of Sections 4100-4108 of the California Public Contract Code and any amendments thereof, each bidder shall set forth (a) the name and location of the place of business of each subcontractor who will perform work or labor or render service in or about the construction site or a subcontractor licensed by the State of California who, under subcontract to the prime contractor, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications in an amount in excess of one-half of 1 percent of the total bid and (b) the California Contractor License Number for each subcontractor, and (c) the portion of the work to be done by each subcontractor.(See General Conditions Section 1-09.) Include with the name of each sub-contractor their Department of Industrial Relations Public Works Contractor Registration Number.

SUBCONTRACTOR
NAME

SUBCONTRACTOR

LICENSE NUMBER

SUBCONTRACTOR
DIR

REGISTRATION
NUMBER

SUBCONTRACTOR

BUSINESS

ADDRESS

DESCRIPTION

OF WORK

Page 304 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 39 Spec. No. 25-04

STATEMENT OF EXPERIENCE OF BIDDER
The bidder is required to state below what work of similar magnitude or character he or she has done and to give references that will enable the City Council to judge of his or her experience, skill and business standing and his or her ability to conduct work as completely and rapidly as required under the terms of the contract. ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________

Page 305 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 40 Spec. No. 25-04

SIGNATURE(S) OF BIDDER
Accompanying this proposal is ___________________________________ (insert the words "cash ($)", "cashier's check" or "bidder's bond", as the case may be) in an amount equal to at least 10 percent of the bid.

The names of all persons interested in the foregoing proposal as principals are as follows:

IMPORTANT NOTICE: If bidder or other interested person is a corporation, provide the legal name of corporation and also the names of the president, secretary, treasurer and manager thereof. If a co-partnership, provide the true name of firm and also the names of all individual co-partners composing the firm. If bidder or other interested person is an individual, provide the first and last names in full. _________________________________________________________________ _________________________________________________________________ _________________________________________________________________ Licensed in accordance with an act providing for the registration of Contractors:

License No. ______________________________, License Expiration Date .

Signature(s) of Bidder: ______________________________________________ ______________________________________________
______________________________________________
NOTE: If bidder is a corporation, the legal name of the corporation shall be set forth above together with the signature of the officer or officers authorized to sign contracts on behalf of the corporation; if bidder is a co-partnership, the true name of the firm shall be set forth above together with the signature of the partner or partners authorized to sign contracts in behalf of the co-partnership; and if bidder is an individual, his or her signature shall be placed above. If a member of a partnership, a Power of Attorney must be on file with the Department prior to opening bids or submitted with the bid; otherwise, the bid will be disregarded as irregular and unauthorized.

Business address: ___________________________________________________ ___________________________________________________
Place of residence: ___________________________________________________ ___________________________________________________
Dated: __________________

Page 306 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 41 Spec. No. 25-04

CITY OF UKIAH
Mendocino County, California

BIDDER'S BOND

KNOW ALL MEN BY THESE PRESENTS,
That we, ______________________________________________________________ ________________________________________________________________, as PRINCIPAL and ________________________________________________________________ ________________________________________________________________, as SURETY, are held and firmly bound unto the City of Ukiah in the penal sum of 10 PERCENT OF THE TOTAL AMOUNT OF THE BID of the Principal above named, submitted by said Principal to the City of Ukiah, as the case may be, for the work described below, for the payment of which sum in lawful money of the United States, well and truly to be made, to the City Clerk to which said bid was submitted, we bind ourselves, our heirs, executors, administrators and successors jointly and severally, firmly by these presents. In no case shall the liability of the surety hereunder exceed the sum of $____________________

THE CONDITION OF THIS OBLIGATION IS SUCH,
That whereas the Principal has submitted the above mentioned bid to the City of Ukiah, as aforesaid, for certain construction specifically described as follows, for which bids are to be opened at the Office of the City Clerk, Ukiah Civic Center, Ukiah, California, on TBD for REMODEL OF 501 SOUTH STATE STREET.

NOW, THEREFORE, If the aforesaid Principal is awarded the contract and, within the time and manner required under the specifications, after the prescribed forms are presented to him or her for signatures, enters into a written contract, in the prescribed form, in accordance with the bid and files two bonds with the City of Ukiah, one to guarantee faithful performance and the other to guarantee payment for labor and materials, as required by law, then this obligation shall be null and void; otherwise, it shall be and remain in full force and virtue.

IN WITNESS WHEREOF, we have hereunto set our hands and seals on this ______ day of ________________, A.D. 20_____.
__________________________________________________(Seal) __________________________________________________(Seal) __________________________________________________(Seal) Principal
__________________________________________________(Seal) __________________________________________________(Seal) __________________________________________________(Seal) Surety
Address: __________________________________________________________ __________________________________________________________ __________________________________________________________

Page 307 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 42 Spec. No. 25-04

NON-COLLUSION AFFIDAVIT
Note: Bidder shall execute the affidavit on this page prior to submitting his or her bid.

To City Council, City of Ukiah:

The undersigned in submitting a bid for performing REMODEL OF 501 SOUTH STATE STREET by contract, being duly sworn, deposes and says:
that he or she has not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with such contract.
__________________________________________________
__________________________________________________
__________________________________________________
Signature(s) of Bidder
Business Address:__________________________________________________ __________________________________________________
__________________________________________________
Place of Residence:__________________________________________________ __________________________________________________
__________________________________________________

NOTARIZATION
Subscribed and sworn to before me this ______ day of _________, 20____. __________________________________________________
Notary Public in and for the County of______________________________, State of California.

My Commission Expires ________________________, 20 ____.

Page 308 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 43 Spec. No. 25-04

CITY OF UKIAH
Mendocino County, California

AGREEMENT
FOR
REMODEL OF 501 SOUTH STATE STREET
Specification No. 25-04
THIS AGREEMENT, made this ______ day of ___________________, 20____, by and between the City of Ukiah, Mendocino County, California, hereinafter called the City and _______________________ hereinafter called the Contractor,
WITNESSETH:

WHEREAS, the City has caused to be prepared in accordance with law, specifications, drawings and other contract documents for the work herein described and shown and has approved and adopted these contract documents, specifications and drawings and has caused to be published in the manner and for the time required by law a notice to bidders inviting sealed proposals for doing the work in accordance with the terms of this contract and
WHEREAS, the Contractor, in response to the notice to bidders, has submitted to the City a sealed proposal accompanied by a proposal guaranty in an amount of not less than 10 percent of the bid price for the construction of the proposed work in accordance with the terms of this contract and WHEREAS, the City, in the manner prescribed by law, has publicly opened, examined and canvassed the proposals submitted and as a result has determined and declared the Contractor to be the lowest and best regular responsible bidder for the work and for the sums named in the proposal, NOW, THEREFORE, THIS AGREEMENT WITNESSETH:

Article 1. Work to be Done and Contract Days Allowed.

That the Contractor shall provide all necessary machinery, tools, apparatus and other means of construction; shall furnish all materials, superintendence, overhead, expenses, all labor and expenses of whatever nature necessary for completion of the work in conformity with the Special Provisions and other contract documents hereto attached and according to such instructions as may be given by the Engineer. The Contractor shall complete the work within TWO HUNDRED AND FORTY (240) working days. Contract days shall be counted starting with the 10th day following receipt of notice that the contract has been executed by the City. Contractor, at his or her option, may begin work prior to start of counting contract days, however, in no event shall the Contractor start work without giving notification to the Engineer at least 72 hours prior to the start of work, without obtaining an encroachment permit from the City, or without having submitted certificates of insurance that have been accepted and approved by the Engineer

Page 309 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 44 Spec. No. 25-04
Article II. Contract Prices.

That the City shall pay the Contractor the prices stated in the proposal submitted by the Contractor, for complete performance of the contract by the Contractor. The Contractor hereby agrees to accept the prices as full compensation for all material and appliances necessary to the work, for all labor and use of tools and other implements necessary to execute the work contemplated in this contract; for all loss or damage arising out of the nature of the work or from the action of the elements, or from any unforeseen obstructions or difficulties which may be encountered in the prosecution of the work; for all risks of every description connected therewith; for all expenses of the work, as herein specified; for all liability and other insurance, for all overhead and other expenses incident to the work; all according to the Contract Drawings, the Special Provisions, the Details, the instructions and the requirements of the City.

Article III. Labor Discrimination.

Attention is directed to Section 1735 of the Labor Code, which reads as follows:
"No discrimination shall be made in the employment of persons upon public works because of the race, color, national origin or ancestry, or religion of such persons and every contractor for public works violating this section is subject to all the penalties imposed for a violation of this chapter." In connection with the performance of work under this contract, the Contractor agrees as follows:
(a) The Contractor will not willfully discriminate against any employee or an applicant for employment because of race, color, religion, ancestry, or national origin. The Contractor will take affirmative action to ensure that applicants are employed and that employees are treated during employment without regard to their race, color, religion, ancestry, or national origin. Such action shall include, but not be limited to, the following: employment, upgrading, demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided by the awarding authority setting forth the provisions of this Fair Employment Practice section. (b) The Contractor will send to each labor union or representative of workers with which he or she has a collective bargaining agreement or other contract or understanding, a notice, to be provided by the awarding authority, advising the said labor union or worker's representative of the Contractor's commitments under this section, to employees and applicants for employment. (c) The Contractor will permit access to his or her records of employment, employment advertisements, application forms and other pertinent data and records by the Fair Employment Practices Commission, City of Ukiah or any other appropriate agency of the State of California designated by the awarding authority, for the purposes of investigation to ascertain compliance with the Fair Employment Practices section of this contract.
(d) A finding of willful violation of the Fair Employment Practices section of this Contract or of the Fair Employment Practices Act shall be regarded by the awarding authority as a basis for determining the Contractor to be not a "responsible bidder" as to future contracts for which such Contractor may submit bids, for revoking the Contractor's pre-qualification rating, if any and for refusing to establish, reestablish or renew a pre-qualification rating for the Contractor.

The City of Ukiah shall deem a finding of willful receipt of written notice from the Fair Employment Practices Act to have occurred upon that it has investigated and determined that the Contractor has

Page 310 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 45 Spec. No. 25-04
violated the Fair Employment Practices Act and has issued an order under Labor Code Section 1426 or obtained an injunction under Labor Code Section 1429.

Upon receipt of such written notice from the Fair Employment Practices Commission, the City shall notify the Contractor that unless he or she demonstrates to the satisfaction of the awarding authority within a stated period that the violation has been corrected, his or her pre-qualification rating will be revoked at the expiration of such period.
(e) The Contractor agrees that should the City determine that the Contractor has not complied with the Fair Employment Practices section of this Contract, then pursuant to Labor Code Section 1735 and 1775 the Contractor shall, as a penalty to the City, forfeit for each calendar day or portion thereof, for each person who was denied employment as a result of such non-compliance, the penalties provided in the Labor Code for violation of prevailing wage rates. Such monies may be recovered from the Contractor. The City may deduct any such damages from any monies due the Contractor. (f) Nothing contained in this Fair Employment Practices section shall be construed in any manner of fashion so as to prevent the City or the State of California from pursuing any other remedies that may be available at law.
(g) Prior to awarding the Contract, the Contractor shall certify to the awarding authority that he or she has or will meet the following standards for affirmative compliance, which shall be evaluated in each case by the awarding authority:
(1) The Contractor shall provide evidence, as required by the City that he or she has notified all supervisors, foremen and other personnel officers in writing of the content of the anti-discrimination clause and their responsibilities under it.
(2) The Contractor shall provide evidence, as required by the City, that he or she has notified all sources of employees’ referrals (including unions, employment agencies, advertisements, Department of Employment) of the content of the anti-discrimination clause. (3) The Contractor shall file a basic compliance report, as required by the City. Willfully false statements made in such reports shall be punishable as provided by law. The compliance report shall also spell out the sources of the work force and who has the responsibility for determining whom to hire, or whether or not to hire.
(4) Personally, or through his or her representatives, the Contractor shall, through negotiations with the unions with whom he or she has agreements, attempt to develop an agreement which will:
a. Spell out responsibilities for nondiscrimination in hiring, referral, upgrading and training. b. Otherwise implement an affirmative anti-discrimination program in terms of the unions' specific areas of skill and geography to the end that qualified minority workers will be available and given and equal opportunity for employment.
(5) The Contractor shall notify the City of opposition to the anti-discrimination clause by individuals, firms or organizations during the period of its pre-qualification. (h) The Contractor will include the provisions of the foregoing paragraphs 1 through 5 in every first tier subcontract so that such provisions will be binding upon each such subcontractor. (i) The "Fair Employment Practices Certification" must be completed and signed prior to the time of submitting the bid.

Page 311 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 46 Spec. No. 25-04
Article IV. Parts of the Contract.

That the complete contract consists of the following documents, all of which shall be considered a part of this agreement.

1. Notice to Bidders

2. Wage Rates

3. General Conditions

4. Technical Specifications

5. Proposal

6. Fair Employment Practices Certification

7. Agreement

8. Contract Bonds

9. Contract Drawings and Construction Details

10. Standard Drawings

11. Indemnification Agreement
IN WITNESS WHEREOF, this contract being executed in duplicate and the parties having caused their names to be signed by authority of their duly authorized office this _____ day of _____________, 20____.

CITY OF UKIAH, MENDOCINO COUNTY, CALIFORNIA
By: ______________________________________________________________

CITY MANAGER, CITY OF UKIAH
Attest: ______________________________________________________________

CITY CLERK, CITY OF UKIAH
By: ______________________________________________________________

CONTRACTOR
Attest: ______________________________________________________________ Title: ______________________________________________________________ The foregoing contract is approved as to form and legality this ______ day of ______________, 20 ____. __________________________________________________

CITY ATTORNEY, CITY OF UKIAH

Page 312 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 47 Spec. No. 25-04

INDEMNIFICATION AGREEMENT
This Indemnification Agreement is made and entered in Ukiah, California, on _________________, 20____, by and between the City of Ukiah (Ukiah) and ______________________________________ (Contractor).

Contractor is
_________________________________________________________________________________ ___________________________________________ for Ukiah.

As a condition of issuing the work order, attached hereto, Ukiah requires assurance that Contractor will protect Ukiah from damage or damage claims which arise from its performance of the work.

Accordingly, Contractor agrees as follows:

1. Indemnification. Contractor shall indemnify and hold harmless Ukiah and its officers, agents, and employees from and against any claim, loss, or damage, including the legal and other costs of defending against any claim of damage or loss which arises out of the Contractor’s negligent or wrongful performance under the work order attached hereto, except for claims, losses, or damages resulting from the sole and exclusive negligence or other wrongful conduct of Ukiah or its officers, agents and employees.

CONTRACTOR
BY: _______________________________________________
TITLE: _______________________________________________

Page 313 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 48 Spec. No. 25-04

CITY OF UKIAH
Mendocino County, California

PERFORMANCE BOND
BOND No._____________________
KNOW ALL PERSONS BY THESE PREESNTS:

THAT WHEREAS, the City of Ukiah, organized and operating under the laws of the State of California, (hereinafter referred to as the “City”) has awarded to ______________________________, (hereinafter referred to as the “Contractor”) an agreement for Contract No. _______________ (hereinafter referred to as the “Project”).

WHEREAS, the work to be performed by the Contractor is more particularly set forth in the Contract for the Project dated _______________________, (hereinafter referred to, together with all attachments and exhibits thereto, as “Contract Documents”), the terms and conditions of which are expressly incorporated herein by reference; and WHEREAS, the Contractor is required by the Contract Documents to perform the terms thereof and to furnish a bond for the faithful performance of said Contract Documents.

NOW, THEREFORE, we, __________________________, the undersigned Contractor and _________________________, as Surety, a corporation organized and duly authorized to transact business under the laws of the State of California, are held firmly bound until the City in the sum of ______________________________ ($_________________), for which amount well and truly to be made, we bind ourselves, our heirs ,executors and administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH that, if the Contractor, his or its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions and agreements in the Contract Documents and any alteration thereof made as therein provided, on its part, to be kept and performed at the time and in the manner therein specified, and in all respects according to their intent and meaning; and shall faithfully fulfill all obligations; and shall indemnify and save harmless the City, its officials, officers, employees, and authorized volunteers, as stipulated in said Contract Documents, then this obligation shall become null and void; otherwise it shall be and remain in full force and effect.

As part of the obligation secured hereby and in addition to the face amount specified therefore, there shall be included costs and reasonable expenses and fees including reasonable attorneys’ fees, incurred by the City in enforcing such obligation.

As a condition precedent to the satisfactory completion of the Contract Documents, unless otherwise provided for in the Contract Documents, the above obligation shall hold good for a period of one (1) year after the acceptance of the work by the City, during which time if Contractor shall fail to make full, complete, and satisfactory repair and replacements and totally protect the City from loss or damage resulting from or caused by defective materials or faulty workmanship. The obligations of Surety hereunder shall continue so long as any obligation of Contractor remains. Nothing herein shall limit the City’s rights or the Contractor or Surety’s obligations under the Contract Documents, law or equity, including, but not limited to, California Code of Civil Procedure Section 337.15.

Whenever Contractor shall be, and is declared by the City to be, in default under the Contract Documents, the Surety shall remedy the default pursuant to the Contract Documents, or shall promptly, at the City’s option:
i. Take over and complete the Project in accordance with all terms and conditions in the Contract Documents; or
ii. Obtain a bid or bids for completing the Project in accordance with all terms and conditions in the Contract Documents and upon determination by Surety of the lowest responsive and responsible bidder, arrange for a contract between such bidder, the Surety and the City, and make available as work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the contract

Page 314 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 49 Spec. No. 25-04
price, including other costs and damages for which Surety may be liable. The term “balance of the contract price” as used in this paragraph shall mean the total amount payable to Contractor by the City under the Contract and any modification thereto, less any amount previously paid by the City to the Contractor and any other set offs pursuant to the Contract Documents.
iii. Permit the City to complete the Project in any manner consistent with California law and make available as work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the contract price, including other costs and damages for which Surety may be liable. The term “balance of the contract price” as used in this paragraph shall mean the total amount payable to Contractor by the City under the Contract and any modification thereto, less any amount previously paid by the City to the Contractor and any other set offs by the City pursuant to the Contract Documents.

Surety expressly agrees that the City may reject any contractor or subcontractor which may be proposed by Surety in fulfillment of its obligations in the event of default by the Contractor.

Surety shall not utilize Contractor in completing the Project nor shall Surety accept a bid from Contractor for completion of the Project if the City, when declaring the Contractor in default, notifies Surety of the City’s objection to Contractor’s further participation in the completion of the Project.

The Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project to be performed thereunder shall in any way affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project. [REMAINDER OF PAGE LEFT INTENTIONALLY BLANK]

Page 315 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 50 Spec. No. 25-04
IN WITNESS WHEREOF, we have hereunto set our hands and seals this ____ day of ___________________, 2022.
(Corporate Seal) ________________________________
Contractor/Principal
By______________________________

Title_____________________________
(Corporate Seal) _________________________________
Surety
By_______________________________
Attorney-in-Fact
(Attach Attorney-in Fact Certificate) Title______________________________ The rate of premium on this bond is __________________ per thousand. The total amount of premium charges is $_________________________.
(The above must be filled in by corporate attorney.)
THIS IS A REQUIRED FORM.

Any claims under this bond may be addressed to:
(Name and Address of Surety) ________________________________ ________________________________
________________________________
(Name and Address of Agent or ________________________________ Representative for service of process in ________________________________ California, if different from above) ________________________________ (Telephone number of Surety and Agent _______________________________ or Representative for service of process in California)

Page 316 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 51 Spec. No. 25-04

CITY OF UKIAH
Mendocino County, California

PAYMENT BOND
BOND No. ____________________
KNOW ALL PERSONS BY THESE PRESENTS:

WHEREAS, the City of Ukiah (“City”) has awarded to _______________________ (“Contractor/Principal”) a contract (City Agreement No. _____________, dated _________________, ___________, referred to as the “Agreement”) for the work described as _______________________. The Agreement is incorporated by this reference into this Payment Bond (“Bond”); and
WHEREAS, Contractor/Principal is required to furnish a bond in connection with the Agreement and pursuant to California Civil Code section 9550;
NOW, THEREFORE, we ____________________________________________, the undersigned Contractor/Principal, and _____________________ (“Surety”), a corporation organized and existing under the laws of the State of _____________________, and duly authorized to transact business under the laws of the State of California, as Surety, are held firmly bound until the City, and to any and all persons, companies, or corporations entitled by law to file stop payment notices under California Civil Code Section 9100, or any person, company, or corporation entitled to make a claim on this bond, in the sum of $_________________________, for which payment will and truly be made, we bind ourselves, our heirs, executors and administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH that if Contractor/Principal, its heirs, executors, administrators, successors, or assigns, or subcontractor, shall fail to pay any person or persons named in Civil Code section 9100; or fail to pay for any materials, provisions, or other supplies, used in, upon, for , or about the performance of the work contracted to be done, or for any work or labor thereon of any kind, or for amounts due under the Unemployment Insurance Code, with respect to work or labor thereon of any kind; or shall fail to deduct, withhold, and pay over to the Employment Development Department, any amounts required to be deducted, withheld, and paid over by Unemployment Insurance Code Section 13020 with respect to work and labor thereon of any kind, then Surety will pay for the same, in an amount not exceeding the amount herein above set forth, and in the event suit is brought upon this bond, also will pay such reasonable attorneys’ fees as shall be fixed by the court, awarded and taxed as provided in California Civil Code Section 9550, et seq.

It is further stipulated and agreed that the Surety of this bond shall not be exonerated or released from the obligation of the bond by any change, extension of time for performance, addition, alteration or modification in, to, or of any contract, plans, or specifications, or agreement pertaining or relating to any scheme or work of improvement herein above described; or pertaining or relating to the furnishing of labor, materials, or equipment therefor; nor by any change or modification of any terms of payment or extension of time for payment pertaining or relating to any scheme or work of improvement herein above described; nor by any rescissions or attempted rescission of the contract, agreement or bond; nor by any conditions precedent or subsequent in the bond attempting to limit the right of recovery of claimants otherwise entitled to recover under any such contract or agreement or under the bond; nor by any fraud practiced by any person other than the claimant seeking to recover on the bond; and that this bond be construed most strongly against the Surety and in favor of all persons for whose benefit such bond is give; and under no circumstances shall the Surety be released from liability to those for whose benefit such bond has been given, by reason of any breach of contract between the Owner and Contractor/Principal or on the part of any oblige named in such bond; that the sole condition of recovery shall be that the claimant is a person described in California Civil Code section 9100, and who has not been paid the full amount of his or her claim; and that the Surety does hereby waive notice of any such change, extension of time, addition, alteration or modification herein mentioned, including but not limited to the provisions of section 2819 and 2845 of the California Civil Code.

Page 317 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 52 Spec. No. 25-04
Any notice to Surety may be given in the manner specified in the Agreement and delivered or transmitted to Surety as follows:

Attn:__________________________________________
Address:_______________________________________
City/State/Zip:___________________________________
Phone:_________________________________________
Fax:___________________________________________
Email:__________________________________________

IN WITNESS WHEREO, two identical counterparts of this Bond, each of which shall for all purposes be deemed an original thereof, have been duly executed by Contractor/Principal and Surety above named, on the __ day of ____________________, 202__.
__________________________________ (SEAL)
Contractor/Principal
By_____________________________________
Contractor’s Representative
______________________________________
Contractor/Principal’s Address
______________________________________
City,State,Zip
_________________________________(SEAL)
Surety
By_____________________________________
Surety’s Representative
______________________________________
Surety’s Address
______________________________________
City,State,Zip
______________________________________
Telephone Number
NOTE: Signatures of those executing for Surety must be properly acknowledged, The bond must be accompanied by a properly acknowledged Power of Attorney from the Surety authorizing its agent to bind it to this bond. A copy of such Power of Attorney must be in file with the City.

Page 318 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 53 Spec. No. 25-04

DIRECTIONS FOR PREPARATION OF PERFORMANCE AND MATERIAL AND LABOR BOND

1. Individual sureties, partnerships, or corporations not in the surety business will not be acceptable.

2. The name of the Principal shall be shown exactly as it appears in the Contract.

3. The penal sum shall not be less than required by the Specifications.

4. If the Principals are partners or joint venturers, each member shall execute the bond as an individual and state his place of residence.

5. If the Principal is a corporation, the bond shall be executed under its corporate seal.

If the corporation has no corporate seal, it shall so state and affix a scroll or adhesive seal following the corporate name.

6. The official character and authority of the person(s) executing the bond for the Principal, if a corporation, shall be certified by the Secretary or Assistant Secretary thereof under the corporate seal, or copies attached to such records of the corporation as will evidence the official character and authority of the officer signing, duly certified by the Secretary or Assistant Secretary, under the corporate seal, to be true copies.

7. The current power-of-attorney of the person signing for the surety company must be attached to the bond.

8. The date of the bond must not be prior to the date of the Contract.

9. The following information must be placed on the bond by the surety company:
a. The rate of premium in dollars per thousand; and
b. The total dollar amount of premium charged.

10. The signature of a witness shall appear in the appropriate place attending to the signature of each party of the bond.

11. Type or print the name underneath each signature appearing on the bond.

12. An executed copy of the bond must be attached to each copy of the Contract (original counterpart) intended for signing.

Page 319 of 1257 ends

Draft
REMODEL OF 501 SOUTH STATE STREET 54 Spec. No. 25-04

CITY OF UKIAH
Mendocino County, California

DEFECTIVE MATERIAL AND WORKMANSHIP (MAINTENANCE) BOND

KNOW ALL MEN BY THESE PRESENTS,
That we, _____________________________________________________________________ __________________________________________________________________, as PRINCIPAL and__________________________________________________________________________ ___________________________________________________________________, as SURETY, are held and firmly bound unto the City of Ukiah as Obligee, in the penal sum of ___________________________________________________________________________________ _________________________________________________________($____________________), (5 PERCENT OF THE FINAL CONTRACT AMOUNT)
to which payment well and truly to be made, we do bind ourselves, our and each of our heirs, executors, administrators successors and assigns jointly and severally, firmly by these presents.

WHEREAS, the said Principal entered into a Contract with the City of Ukiah dated_________________________
for _________________________________________________________________________________ ____________________________________________________________________________________ WHEREAS, said Contract has been completed, and was approved on the ______ day of ___________, _________,
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal shall guarantee that the work will be free of any defective materials or workmanship which become apparent during the period of one (1) year following completion of the Contract, then this obligation shall be void, otherwise to remain in full force and effect, provided however, any additional warranty or guarantee whether expressed or implied is extended by the Principal or Manufacturer only, and the surety assumes no liability for such a guarantee.

Signed, sealed, and dated this __________ day of ____________, 20_____. __________________________________________________(Seal) BY:_______________________________________________(Seal) __________________________________________________(Seal) Principal
__________________________________________________(Seal) BY:_______________________________________________(Seal)

Page 320 of 1257 ends

Draft
__________________________________________________(Seal) Surety

Page 321 of 1257 ends

THIS PAGE INTENTIONALLY LEFT BLANK
Attachment 2

Page 322 of 1257 ends

TABLE OF CONTENTS
TABLE OF CONTENTS 1 of 3
VOLUME 1 of 1
Table of Contents
DIVISION 0 – PROCUREMENT AND CONTRACTING REQUIREMENTS
*See Special Provisions document
DIVISION 1 – GENERAL REQUIREMENTS
01 25 13 Substitutions
01 31 00 Project Management and Coordination
01 32 19 Submittal Schedules, Daily Reports, & Field Reports 01 33 00 Submittal Procedures
01 40 00 Quality Requirements
01 43 39 Mock-ups
01 50 00 Temporary Facilities and Controls
01 73 00 Execution Requirements
01 73 29 Cutting and Patching
01 74 19 Construction Waste Management
01 74 20 Cleaning
01 77 00 Closeout Procedures
01 91 00 General Commissioning Requirements
*See also Special Provisions document
DIVISION 2 – EXISTING CONDITIONS
02 41 00 Demolition
DIVISION 3 – CONCRETE
03 05 00 Concrete Tests and Inspections
03 11 13 Concrete Formwork
03 20 00 Concrete Reinforcement
03 30 00 Cast-in-Place Concrete
03 37 13 Shotcrete
03 54 16 Hydraulic Cement Underlayment
DIVISION 4 – MASONRY
Not Used

DIVISION 5 – METALS
05 12 00 Structural Steel Framing
05 50 00 Metal Fabrications
DIVISION 6 – WOOD AND PLASTICS
06 10 00 Rough & Finish Carpentry
06 40 23 Interior Architectural Woodwork
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
07 14 16 Cold Fluid-Applied Waterproofing
07 21 00 Building Insulation
07 22 00 Roof and Deck Insulation
07 24 00 Insulation & Finish System (EIFS)
07 26 16 Underslab Vapor Retarder
07 27 26 Fluid-Applied Membrane Air Barriers
07 54 23 Thermoplastic Polyolefin (TPO) Roofing
07 62 00 Sheet Metal Flashing and Trim
07 71 00 Roof Specialties

Page 323 of 1257 ends

TABLE OF CONTENTS
TABLE OF CONTENTS 2 of 3
07 84 00 Firestopping Systems
07 90 00 Joint Sealants
DIVISION 8 – DOORS AND WINDOWS
08 11 13 Hollow Metal Doors and Frames
08 14 00 Wood Doors
08 31 00 Access Doors and Frames
08 41 13 Aluminum-Framed Entrances and Storefronts
08 42 29 Sliding Aluminum Entrances
08 45 23 Fiberglass Sandwich Panel Skylights
08 71 00 Door Hardware
08 80 00 Glazing
DIVISION 9 – FINISHES
09 06 00 Schedule for Finishes
09 22 16 Non-Structural Metal Framing
09 25 00 Gypsum Board
09 30 13 Porcelain Tile
09 51 00 Acoustical Ceilings
09 65 00 Resilient Flooring and Base
09 65 19 Static Dissipative Resilient Flooring
09 68 13 Carpet Tile
09 90 00 Painting
DIVISION 10 – SPECIALTIES
10 14 00 Signage
10 22 39 Folding Glass Partitions
10 26 00 Wall Protection
10 28 00 Toilet Accessories
10 44 13 Fire Extinguisher Cabinets
DIVISION 11 – EQUIPMENT
Not Used
DIVISION 12 – FURNISHINGS
Not Used
DIVISION 13 – SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint for Non-Structural Components DIVISION 14 – CONVEYING SYSTEMS
14 24 00 Hydraulic Elevator
DIVISION 21 – FIRE SUPPRESSION
21 05 11 Common Work for Fire Suppression
21 13 13 Wet-Pipe Sprinkler Systems
DIVISION 22 – PLUMBING
22 00 00 General Requirements of Plumbing and HVAC
22 05 00 General Provision of Plumbing and HVAC
22 05 23 General Duty Valves for Plumbing and HVAC
22 05 29 Hangars and Supports for Plumbing and HVAC Piping and Equipment 22 05 48 Vibration and Seismic Controls for Plumbing and HVAC Piping and Equipment 22 05 53 Identification for Plumbing and HVAC Piping and Equipment 22 07 16 Plumbing and HVAC Equipment and Piping Insulation

Page 324 of 1257 ends

TABLE OF CONTENTS
TABLE OF CONTENTS 3 of 3
22 11 16 Domestic Water Piping
22 11 19 Domestic Water Piping Specialties
22 13 16 Sanitary Waste and Vent Piping
22 13 19 Sanitary Waste Piping Specialties
22 33 00 Electric, Domestic-Water Heaters
22 41 00 Plumbing Fixtures
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) 23 05 93 Testing, Adjusting, and Balancing for HVAC
23 07 13 Duct Insulation
23 23 00 Refrigerant Piping
23 31 13 Metal Ducts
23 33 00 Air Duct Accessories
23 33 46 Flexible Ducts
23 37 13 Grilles, Registers and Diffusers
23 81 26 Split-System Air-Conditioners
DIVISION 26 – ELECTRICAL
26 05 00 Common Work Results for Electrical
26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems
26 05 29 Hangers and Supports for Electrical Systems
26 05 33 Raceways and Boxes for Electrical Systems
26 05 53 Identification for Electrical Systems
26 09 23 Lighting Control Devices
26 24 16 Panelboards
26 27 26 Wiring Devices
26 28 16 Enclosed Switches and Circuit Breakers
26 32 13.13 Diesel-Engine-Driven Generator Sets
26 36 23 Automatic Transfer Switch
26 51 00 Interior Lighting
26 56 00 Exterior Lighting
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 13 00 Physical Access Control System
DIVISION 31 – EARTHWORK
31 23 00 Excavating Backfilling and Compacting
31 25 00 Erosion and Sedimentation Control
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements
32 12 16 Asphalt Paving
32 17 13 Wheel Stop
32 17 23 Pavement Markings
32 17 26 Cast-In-Place Tactile Warning Surface
DIVISION 33 – WATER UTILITIES
33 30 00 Sanitary Sewer Utilities
APPENDIX A – Hydrant Flow Test Report

Page 325 of 1257 ends

THIS PAGE INTENTIONALLY LEFT BLANK Page 326 of 1257
SUBSTITUTIONS 01 25 13 - 1 of 6
SECTION 01 25 13 SUBSTITUTIONS
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General Conditions and Supplemental General Conditions and other Division 01 General Requirements, apply to this Section.

1.2 SUMMARY
A. This Section specifies administrative and procedural requirements for handling requests for Substitutions.

B. Pre-bid substitutions will not be considered. No Substitution request will be accepted or considered by City prior to bid.

C. Procedural requirements governing the Contractor’s selection of products and product options are included under General Requirements - Product Requirements.

1.3 DEFINITIONS
A. Definitions used in this Section are not intended to change or modify the meaning of other terms used in the Contract Documents.

B. Substitutions: Requests for changes in products, materials, equipment, and methods of construction required by Contract Documents are considered requests for "substitutions." Where phrases such as "or equal" or "or equal as approved by the Architect" occurs in the Contract Documents, do not assume that materials or equipment will be approved as equal unless the item has been specifically approved for this work by the Architect prior to Bid Opening Date, or as otherwise allowed in these Contract Documents.

The following are not considered substitutions:

1. Revisions to Contract Documents requested by the Owner or Architect.

2. Specified options of products and construction methods included in Contract Documents.

3. The Contractor's determination of and compliance with governing regulations and orders issued by governing authorities.

1.4 SUBMITTALS
A. If the Contractor desires to use material or equipment other than that specified, they shall submit a request for approval of such substitution, in writing, to the Construction Manager.

Product Substitutions for all Specification Sections must be requested within the time period specified in the general conditions. Substitution Request Form: Use CSI Form

13.1A.

B. Submit Substitution Request packages using the form provided and in a quantity to be returned to the Contractor plus four (4) copies of each request for substitution for review by the Architect.

Page 327 of 1257 ends

SUBSTITUTIONS 01 25 13 - 2 of 6
SECTION 01 25 13 SUBSTITUTIONS
C. Identify the product, or the fabrication or installation method to be replaced in each request. Include related Specification Section and Drawing numbers. Provide complete documentation showing compliance with the requirements for substitutions, and the following information, as appropriate:

1. Product Data, including Drawings and descriptions of products, fabrication and installation procedures.

2. Samples where applicable or requested.

3. A detailed, side-by-side comparison of the significant qualities of the proposed substitution with those of the Work specified. Significant qualities may include but is not necessarily limited to elements such as size, weight, durability, performance and visual effect.

4. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by the Owner and separate Contractors will become necessary to accommodate the proposed substitution.

5. A statement indicating the substitution's effect on the Contractor's Construction Schedule compared to the schedule without approval of the substitution. Indicate the effect of the proposed substitution on overall Contract Time.

6. Cost information, including a proposal of the net change, if any, in the Contract Sum.

7. Certification by the Contractor that the substitution proposed is equal-to or better in every significant respect to that required by the Contract Documents, and that it will perform adequately in the application indicated. Include the Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of the failure of the substitution to perform adequately

8. The Contractor warrants that they have investigated the proposed product and determined that it is equal to or superior in all respects to that indicated or specified.

9. The Contractor waives claim for additional costs and time associated with the proposed product, which may subsequently become apparent.

10. The Contractor shall provide a signed statement that the proposed product is in full compliance with the Contract Documents, and applicable regulatory requirements, requires no changes to specified controls and monitoring systems that may be specified in other Sections, and Certify that the Contractor will be responsible for coordination at no additional expense to the Owner

11. The Contractor shall provide information on availability of maintenance service, and source of replacement materials, and provide a sample of Manufacturer’s standard form of guarantee or warranty for proposed product.

Page 328 of 1257 ends

SUBSTITUTIONS 01 25 13 - 3 of 6
SECTION 01 25 13 SUBSTITUTIONS

1.5 CONSTRUCTION MANAGER’S ACTION
A. Within ten (10) days of receipt of the request, the Construction Manager will notify the Contractor of acceptance or rejection of the proposed substitution. The Architect at their sole discretion will determine the acceptability of proposed products and their determination shall be final. If a decision on use of a proposed substitution cannot be made or obtained within the time allocated, use the product specified by name in the Contract Documents.

B. No consideration will be given to a substitute product unless, in the Architect’s judgment, it complies with the following conditions.

1. Substitution Request is complete.

2. It is equal in quality, performance and serviceability.

3. Its use does not entail changes in details or related construction.

4. It is acceptable in regards to design and aesthetic effect.

5. There is a cost and/or time advantage to the Owner.

C. Acceptance of a product shall not relieve the Contractor from responsibility for the proper execution of the Work and any other requirements of the Contract Documents.

D. If a proposed product is not accepted, use the product originally specified or indicated in the Contract Documents.

E. No products other than those indicated or specified in the Contract Documents shall be purchased or incorporated in the Work without the Architect’s prior written acceptance.

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS
A. Conditions: The Contractor's substitution request will be received and considered by the Architect when one (1) or more of the following conditions are satisfied, as determined by the Architect; otherwise requests will be returned without action except to record noncompliance with these requirements.

1. Extensive revisions to Contract Documents are not required.

2. Proposed changes are in keeping with the general intent of the Contract Documents.

3. The request is timely, fully documented and properly submitted.

4. The request is directly related to an "or equal" clause or similar language in the Contract Documents.

5. The Specified product or method of construction cannot be provided within the Contract Time. The request will not be considered if the product or method

Page 329 of 1257 ends

SUBSTITUTIONS 01 25 13 - 4 of 6
SECTION 01 25 13 SUBSTITUTIONS
cannot be provided as a result of failure to pursue the Work promptly or coordinate activities properly.

6. The specified product or method of construction cannot receive necessary approval by a governing authority, and the requested substitution can be approved.

7. A substantial advantage is offered the Owner, in terms of cost, time, energy conservation or other considerations of merit, after deducting offsetting responsibilities the Owner may be required to bear. Additional responsibilities for the Owner may include additional compensation to the Architect for redesign and evaluation services, increased cost of other construction by the Owner or Separate Contractors, and similar considerations.

8. The specified product or method of construction cannot be provided in a manner that is compatible with other materials, and where the Contractor certifies that the substitution will overcome the incompatibility.

9. The specified product or method of construction cannot be coordinated with other materials, and where the Contractor certifies that the proposed substitution can be coordinated.

10. The specified product or method of construction cannot provide a warranty required by the Contract Documents and where the Contractor certifies that the proposed substitution provides the required warranty.

B. The Contractor's submittal and Architect's acceptance of Shop Drawings, Product Data or Samples that relate to construction activities not complying with the Contract Documents, does not constitute an acceptable or valid request for substitution, nor does it constitute approval.

PART 3 - EXECUTION (not used)

END OF SECTION

Page 330 of 1257 ends

SUBSTTUTION REQUEST 01 25 13 – 5 of 6

SUBSTITUTION

REQUEST
(After the Bidding Phase)
Project: Insert project name Substitution Request Number: For the Architect to fill in.

From: Insert your name and company name
To: Insert name of Architect, Engineer or GC
.

Re: Substitution request
Date: Insert the current date
A/E Project Number: Fill in if you know the number
Contract For: Insert your contract scope (in general)
Specification Title: Insert spec title from specification book Description: Copy section title from specification Section: Copy from spec book Page: insert page Article/Paragraph: insert para Proposed Substitution:

Manufacturer:

Address: Phone: insert plant phone number
Trade Name: Model No.: )
Installer: insert subs company Address: insert subs address Phone: insert subs phone number History: New product 2-5 years old X 5-10 years old More than 10 years old Differences between proposed substitution and specified product:

X Point-by-point comparative data attached - REQUIRED BY A/E.

Reason for not providing specified item:

Similar Installation:

Project: List a completed project Architect: Insert name of Architect on completed project Address: Insert project address Owner: Insert name of Owner on completed project Date Installed:

Proposed substitution affects other parts of Work: X No Yes; explain Savings to Owner for accepting substitution: ($ ).

Proposed substitution changes Contract Time: No Yes [Add] [Deduct] days.

Supporting Data Attached: Drawings Product Data Samples Tests Reports © Copyright 1996, Construction Specification Institute, 99 Canal Center Plaza, Suite 300 Alexandria, VA 22314
Page of September 1996
CSI Form 13.1A

Page 331 of 1257 ends

SUBSTITUTION REQUEST 01 25 13 – 6 of 6

SUBSTITUTION

REQUEST
(Continued)
The Undersigned certifies:
• Proposed substitution has been fully investigated and determined to be equal or superior in all respects to specified product. • Same warranty will be furnished for proposed substitution as for specified product. • Same maintenance service and source of replacement parts, as applicable, is available. • Proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule. • Cost data as stated above is complete. Claims for additional costs related to accepted substitution which may subsequently become apparent are to be waived.
• Proposed substitution does not affect dimensions and functional clearances. • Payment will be made for changes to building design, including A/E design, detailing, and construction costs caused by the substitution.
• Coordination, installation, and changes in the Work as necessary for accepted substitution will be complete in all respects.

Submitted by: Insert submitters name, normally project manager for sub Signed by: Submitter to sign
Firm: Insert Submitters company name
Address: Insert
Telephone: Insert company phone number
Attachments: List name of attachments
A/E’s REVIEW AND ACTION
Substitution approved - Make submittals in accordance with Specification Section 01330.

Substitution approved as noted - Make submittals in accordance with Specification Section 01330.

Substitution rejected - Use specified materials.

Substitution Request received too late - Use specified materials.

Signed by: Date:

Additional Comments: Contractor Subcontractor Supplier Manufacturer A/E Copyright 1996, Construction Specification Institute,
99 Canal Center Plaza, Suite 300 Alexandria, VA 22314
Page of September 1996
CSI Form 13.1A

Page 332 of 1257 ends

PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 1 of 6
SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL

1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Coordination Drawings.

2. Project meetings.

3. Requests for Interpretation (RFIs).

1.2 DEFINITIONS
A. RFI: Request For Information from Contractor seeking interpretation or clarification of the Contract Documents.

1.3 WEB-BASED PROJECT MANAGEMENT SOFTWARE – NOT USED

1.4 COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work.

Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.

Page 333 of 1257 ends

PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 2 of 6
SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Pre-installation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

9. Project closeout activities.

1.5 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.

1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Architect for resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

Page 334 of 1257 ends

PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 3 of 6
SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION

2. Sheet Size: At least 8-1/2 by 11 inches (215 by 279 mm) but no larger than 30 by 42 inches (750 by 1067 mm).

3. Number of Copies: Submit electronic files for each submittal and produce hard copies as required by the Architect.

4. Refer to individual Sections for Coordination Drawing requirements for Work in those Sections.

1.6 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner, Construction Manager and Architect of scheduled meeting dates and times.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

3. Minutes: Record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner, Construction Manager and Architect, within three (3) days of the meeting.

B. Preconstruction Conference: Schedule a preconstruction conference before starting construction, at a time convenient to Owner and Kitchell, but no later than fifteen (15) days after execution of the Agreement. Hold the conference at Project site or another convenient location. Conduct the meeting to review responsibilities and personnel assignments.

1. Attendees: Authorized representatives of Owner, Construction Manager, Architect, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Tentative construction schedule.
b. Phasing.
c. Critical work sequencing and long-lead items.
d. Designation of key personnel and their duties.
e. Procedures for processing field decisions and Change Orders. f. Procedures for RFIs.
g. Procedures for testing and inspecting.
h. Procedures for processing Applications for Payment.
i. Distribution of the Contract Documents.
j. Submittal procedures.
k. LEED requirements.
l. Preparation of Record Documents.
m. Use of the premises and existing buildings.
n. Work restrictions.
o. Owner's occupancy requirements.

Page 335 of 1257 ends

PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 4 of 6
SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION
p. Responsibility for temporary facilities and controls. q. Construction waste management and recycling.
r. Parking availability.
s. Office, work, and storage areas.
t. Equipment deliveries and priorities.
u. First aid.
v. Security.
w. Progress cleaning.
x. Working hours.

3. Notes: Construction Manager or Architect will record and distribute meeting notes.

C. Progress Meetings: Construction Manager will conduct progress meetings at weekly intervals. Coordinate dates of meetings with preparation of payment requests.

1. Attendees: In addition to representatives of Owner, Construction Manager and Architect, each subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. General Contractor’s designated Project Manager and Superintendent must attend all Progress Meetings in addition to all other project related meetings. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve notes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting.

Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time. 1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site utilization.
8) Temporary facilities and controls.
9) Work hours.
10) Hazards and risks.
11) Progress cleaning.
12) Quality and work standards.
13) Status of correction of deficient items.

Page 336 of 1257 ends

PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 5 of 6
SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION
14) Field observations.
15) Status of RFIs.
16) Status of proposal requests.
17) Pending changes.
18) Status of Change Orders.
19) Pending claims and disputes.
20) Documentation of information for payment requests.

3. Notes: Construction Manager will conduct the meeting will record and distribute meeting notes to Owner, Architect and Contractor.

4. Reporting: Distribute notes of the meeting to each party present and to parties who should have been present.
a. Schedule Updating: Contractor shall update the Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized.

1.7 REQUESTS FOR INTERPRETATION (RFIs)
A. Procedure: Immediately on discovery of the need for interpretation of the Contract Documents, and if not possible to request interpretation at Project meeting, prepare and submit an RFI via the web-based project management software.

1. RFIs shall originate with Contractor. RFIs submitted by entities other than Contractor will be returned with no response.

2. RFIs shall be submitted to the Construction Manager in the specified format.

3. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing interpretation and the following:

1. Project name.

2. Project number

3. Date.

4. Name of Contractor.

5. Name of Architect and Construction Manager.

6. RFI number, numbered sequentially.

7. Specification Section number and title and related paragraphs, as appropriate.

8. Drawing number and detail references, as appropriate.

9. Field dimensions and conditions, as appropriate.

10. Contractor's suggested solution(s). If Contractor's solution(s) impact the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

11. Contractor's signature.

12. Attachments: Include drawings, descriptions, measurements, photos, Product Data, Shop Drawings, and other information necessary to fully describe items needing interpretation.

C. Architect's Action: Architect will review each RFI, determine action required, and return it.

Allow fourteen (14) working days for Architect's response for each RFI. RFIs received after 1:00 p.m. will be considered as received the following working day.

Page 337 of 1257 ends

PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 6 of 6
SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION

1. The following RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for coordination information already indicated in the Contract Documents.
d. Requests for adjustments in the Contract Time or the Contract Sum. e. Requests for interpretation of Architect's actions on submittals. f. Incomplete RFIs or RFIs with numerous errors.

2. Architect's action may include a request for additional information, in which case Architect's time for response will start again.

3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to procedures defined in the Contract Documents including Division F, Section 21. a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Architect in writing within ten (10) days of receipt of the RFI response.

D. On receipt of Architect's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect within seven (7) days if Contractor disagrees with response.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.

Submit log (CSI Log Form 13.2B) weekly. Include the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Architect.

4. RFI number including RFIs that were dropped and not submitted.

5. RFI description.

6. Date the RFI was submitted.

7. Date Architect's response was received.

8. Identification of related Minor Change in the Work, Construction Change Directive, and Proposal Request, as appropriate.

9. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.

PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)

END OF SECTION

Page 338 of 1257 ends

SUBMITTAL SCHEDULES

DAILY REPORTS AND FIELD REPORTS
01 32 19 - 1 of 2
SECTION 01 32 19 SUBMITTAL SCHEDULES / DAILY REPORTS / FIELD REPORTS PART 1 - GENERAL

1.1 SUMMARY
A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Submittals Schedule.

2. Daily construction reports.

3. Field condition reports.

1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

C. Major Area: A story of construction, a separate building, or a similar significant construction element.

1.3 SUBMITTALS
A. Submittals Schedule: Submit via the web-based project management software. Arrange the following information in a tabular format:

1. Scheduled date for first submittal.

2. Specification Section number and title.

3. Submittal category (action or informational).

4. Name of subcontractor.

5. Description of the Work covered.

6. Scheduled date for Architect's final release or approval.

B. Daily Construction Reports: Submit PDF file via the web-based project management software prior to close-of-business on the day covered by the report.

Page 339 of 1257 ends

SUBMITTAL SCHEDULES

DAILY REPORTS AND FIELD REPORTS
01 32 19 - 2 of 2
SECTION 01 32 19 SUBMITTAL SCHEDULES / DAILY REPORTS / FIELD REPORTS C. Field Condition Reports: Submit PDF file via the web-based project management software at time of discovery of differing conditions.

1.4 COORDINATION
A. Coordinate preparation and processing of reports with performance of construction activities and with scheduling and reporting of separate contractors.

PART 2 - PRODUCTS

2.1 SUBMITTALS SCHEDULE
A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, re-submittal, ordering, manufacturing, fabrication, and delivery when establishing dates.

1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and Contractor's Construction Schedule.

2. Submit concurrently with the first complete submittal of Contractor's Construction Schedule.

2.2 REPORTS
A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:

1. List of subcontractors at Project site and quantities relating to labor force.

2. Equipment at Project site.

3. Material deliveries.

4. High and low temperatures and general weather conditions.

5. Accidents.

6. Stoppages, delays, shortages, and losses.

7. Meter readings and similar recordings.

8. Orders and requests of authorities having jurisdiction.

9. Services connected and disconnected.

10. Equipment or system tests and startups.

11. Progress on any schedule activity, including all related activity IDs.

B. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare and submit a detailed report. Submit with a request for interpretation [on CSI Form 13.2A]. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.

PART 3 - EXECUTION – (Not Used)
- END OF SECTIONPage 340 of 1257
SUBMITTAL PROCEDURES 01 33 00 – 1 of 12
SECTION 01 33 00 SUBMITTAL PROCEDURES
PART 1 - GENERAL

1.1 SUMMARY
A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

1.2 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that require Architect's and Construction Manager’s responsive action.

B. Informational Submittals: Written and graphic information and physical samples that do not require Architect's and Construction Manager’s responsive action. Submittals may be rejected for not complying with requirements.

1.3 ACTION SUBMITTALS
A. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or modifications to submittals noted by the Architect and Construction Manager and additional time for handling and reviewing submittals required by those corrections.

1.4 SUBMITTAL ADMINISTRATIVE REQUIREMENTS
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Architect and Construction Manager reserve the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

B. Processing Time: Allow time for submittal review, including time for re-submittals, as follows.

Time for review shall commence on Architect’s receipt of submittal. Contractor is to notify the Architect and Construction Manager when new materials for review have been posted to the designated web-based project management software. Time will begin upon successful download of that information. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.

1. Initial Review: Allow fourteen (14) calendar days for initial review of each submittal.

Allow additional time if coordination with subsequent submittals is required.

Construction Manager will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

Page 341 of 1257 ends

SUBMITTAL PROCEDURES 01 33 00 – 2 of 12
SECTION 01 33 00 SUBMITTAL PROCEDURES

3. Resubmittal Review: Allow fourteen (14) calendar days for review of each resubmittal.

C. Architect’s Digital Data Files: Electronic copies of digital data files of the Contract Drawings will be provided by Architect for Contractor's use in preparing submittals.

1. Architect will furnish Contractor one set of digital data drawing files of the Contract Drawings for use in preparing Shop Drawings and Project record drawings. a. Architect makes no representations as to the accuracy or completeness of digital data drawing files as they relate to the Contract Drawings. b. Contractor shall execute a data licensing agreement in the form of AIA Document C106, Digital Data Licensing Agreement as well as any further waivers required by the Architect.

D. Submittals are to be submitted electronically via the web-based project management software.

1. The following submittals are to be submitted electronically:
a. Product Data
b. Shop Drawings
c. Certifications
d. Test Data
e. Schedules

2. Samples shall not be submitted electronically but a transmittal should be to document delivery of such samples.

E. Identification and Information: Place a permanent label or title block on each cover of submittal item for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space approximately 6x8 inches on label or beside title block to record Contractor's review and approval markings and action taken by Architect and Construction Manager.

3. Include the following information for processing and recording action taken:
a. Project name.
b. Date.
c. Name of Architect.
d. Name of Construction Manager.
e. Name of Contractor.

Page 342 of 1257 ends

SUBMITTAL PROCEDURES 01 33 00 – 3 of 12
SECTION 01 33 00 SUBMITTAL PROCEDURES
f. Name of subcontractor.
g. Name of supplier.
h. Name of manufacturer.
i. Submittal number or other unique identifier, including revision identifier. 1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 061000.01). Resubmittals shall include an alphabetic suffix after another decimal point (e.g., 061000.01.A).
j. Number and title of appropriate Specification Section. k. Drawing number and detail references, as appropriate. l. Location(s) where product is to be installed, as appropriate. m. Other necessary identification.

F. Identification and Information: Identify and incorporate information in each electronic submittal file as follows:

1. Assemble complete submittal package into a single indexed file with links enabling navigation to each item.

2. Name file with submittal number or other unique identifier, including revision identifier. a. File name shall use project identifier and Specification Section number followed by a decimal point and then a sequential number (e.g., 061000.01- LNHS). Re-submittals shall include an alphabetic suffix after another decimal point (e.g., 061000.01.A-LNHS).

3. Provide means for insertion to permanently record Contractor's review and approval markings and action taken by Architect and Construction Manager.

4. Include the following information on an inserted cover sheet:
a. Project name.
b. Date.
c. Name and address of Architect.
d. Name of Construction Manager.
e. Name of Contractor.
f. Name of firm or entity that prepared submittal.
g. Name of subcontractor.
h. Name of supplier.

Page 343 of 1257 ends

SUBMITTAL PROCEDURES 01 33 00 – 4 of 12
SECTION 01 33 00 SUBMITTAL PROCEDURES
i. Name of Manufacturer
j. Number and title of appropriate Specification Section. k. Drawing number and detail references, as appropriate. l. Location(s) where product is to be installed, as appropriate. m. Related physical samples submitted directly.
n. Other necessary identification.

G. Options: Identify options requiring selection by the Architect.

H. Deviations: Highlight, encircle, and otherwise specifically identify deviations from the Contract Documents on submittals.

I. Additional Paper Copies: Unless additional copies are required for final submittal, and unless Architect or Construction Manager observes noncompliance with provisions in the Contract Documents, initial electronic submittal may serve as final submittal.

J. Transmittal: Assemble each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form. Architect and Construction Manager will return submittals, without review, received from sources other than Contractor.

1. On an attached separate sheet, prepared on Contractor's letterhead, record relevant information, requests for data, revisions other than those requested by Architect and Construction Manager on previous submittals, and deviations from requirements in the Contract Documents, including minor variations and limitations. Include same identification information as related submittal.

K. Re-submittals: Make re-submittals in same form as initial submittal.

1. Note date and content of previous submittal.

2. Note date and content of revision in label or title block and clearly indicate extent of revision.

3. Resubmit submittals until they are marked with approval notation from Architect's and Construction Manager's action stamp.

L. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

M. Use for Construction: Retain complete set of paper copies of submittals on Project site. Use only final submittals that are marked with approval notation from Architect's and Construction Manager's action stamp.

1.5 CONTRACTOR'S USE OF ARCHITECT'S CAD FILES
A. At Contractor's written request, copies of Architect's CAD files of select plans will be provided to Contractor for Contractor's use in connection with Project, subject to the following conditions.

1. Only major site/floor/ceiling/roof plans, or building elevations/sections will be provided.

2. Wall section, details, schedules will not be provided.

Page 344 of 1257 ends

SUBMITTAL PROCEDURES 01 33 00 – 5 of 12
SECTION 01 33 00 SUBMITTAL PROCEDURES

3. Title blocks will be removed from the file.

4. Notes and dimensions may be removed from the file.

5. Compliance of the requests for consultant files is at the discretion of the consultant.

6. The following disclaimer will be added to the file:

DISCLAIMER AND INDEMNIFICATION AGREEMENT FOR

COMPUTER-BASED INFORMATION
The attached computer-based information for the Construction of Fire Station 86 are provided to (The User) as a courtesy for their sole convenience. The User recognizes that computerbased information is easily changeable, that changes are difficult to detect and that use or conversion of the information provided may introduce errors, inaccuracies or anomalies that the Architect and their consultants can neither predict nor control. The delivery of this electronic data does not constitute the delivery of the professional work product of the Architect shall not be responsible for any modifications made to the electronic files or any products derived from the electronic files which are not prepared by us. By accepting and utilizing this electronic data in lieu of the corresponding drawings and specifications prepared by the Architect, the User agrees that such data is an instrument of service of the Architect, who shall be deemed to be the author of the drawings and data, and shall retain all common law, statutory law and other rights, including copyrights. The User, by accepting the electronic files, agrees to assume all risk and liabilities associated with the use of the information provided by the Architect and understand the Architect makes no claim or warranty as to the suitability or usefulness of the information for any purpose.

The User also agrees, to the fullest extent permitted by law, to hold harmless and indemnify the Architect from and against any and all claims, liabilities, losses, damages and costs, including but not limited to attorney’s fees, arising from or in connection with the use, misuse, modification, or misinterpretation of the electronic data provided by the Architect. Use of the attached computerbased information indicates acceptance and constitutes agreement to abide by the terms and conditions of this agreement.

PART 2 - PRODUCTS

2.1 SUBMITTAL PROCEDURES
A. General Submittal Procedure Requirements:

1. Post electronic submittals as PDF electronic files directly to the web-based project management software (Prolog Converge). Notify the Architect and Construction Manager of the presence of the submittal(s) via email with identification of the specific materials posted. In web-based project management software, include link for all submittal register items associated with the submittal package. Where possible, endeavor to include all required action submittals for that specification section. a. Architect, through Construction Manager, will return annotated file. Annotate and retain one copy of file as an electronic Project record document file.

Page 345 of 1257 ends

SUBMITTAL PROCEDURES 01 33 00 – 6 of 12
SECTION 01 33 00 SUBMITTAL PROCEDURES

2. Submit electronic submittals via email as PDF files. a. Architect will return annotated file. Annotate and retain one copy of file as an electronic Project record document file.

3. Closeout Submittals and Maintenance Material Submittals: Comply with requirements specified "Closeout Procedures."

4. Certificates and Certifications Submittals: Provide a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
a. Provide a digital signature with digital certificate on electronicallysubmitted certificates and certifications where indicated. b. Provide a notarized statement on original paper copy certificates and certifications where indicated.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards. e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:
a. Wiring diagrams showing factory-installed wiring.
b. Printed performance curves.
c. Operational range diagrams.
d. Clearances required to other construction, if not indicated on accompanying Shop Drawings.

5. Submit Product Data before or concurrent with Samples.

6. Submit Product Data in the following format:
a. PDF electronic file with transmittal as noted above.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data. Submittals based upon Architect's digital data drawing files will be permitted.

Page 346 of 1257 ends

SUBMITTAL PROCEDURES 01 33 00 – 7 of 12
SECTION 01 33 00 SUBMITTAL PROCEDURES

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement. f. Relationship and attachment to adjoining construction clearly indicated. g. Seal and signature of professional engineer if specified.

2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 30 by 42 inches.

Provide hard copies as required by the Architect and Construction Manager

3. Submit Shop Drawings in the following format:
a. PDF electronic file.

D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package. Provide transmittal listing all samples submitted along with quantities.

2. Identification: Attach label on unexposed side of Samples that includes the following:
a. Generic description of Sample.
b. Product name and name of manufacturer.
c. Sample source.
d. Number and title of applicable Specification Section.

3. Disposition: Maintain sets of approved Samples at Project site, available for qualitycontrol comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set. a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use.
b. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the property of Contractor.

4. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available. a. Number of Samples: Submit one (1) full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Architect will return submittal, through Construction Manager, with options selected.

5. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for

Page 347 of 1257 ends

SUBMITTAL PROCEDURES 01 33 00 – 8 of 12
SECTION 01 33 00 SUBMITTAL PROCEDURES
use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection. a. Number of Samples: Submit three (3) sets of Samples. Architect will retain two (2) Sample sets; remainder will be returned. Mark up and retain one returned sample set as a project record sample.
1) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least three (3) sets of paired units that show approximate limits of variations.

E. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:

1. Submit product schedule in the following format:
a. PDF electronic file.

F. Contractor's Construction Schedule: Comply with requirements specified in Section 01 32 16 "Construction Progress Document."
G. Application for Payment: Comply with requirements specified in Section 01 29 00 “Payment Procedures."
H. Schedule of Values: Comply with requirements specified in Section 01 29 00 "Payment Procedures."
I. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Wherever possible, including CSI numbers with description of work being completed. Also, provide DIR numbers for all subcontractors and vendors listed. Provide an updated list when any changes take place along with and explanation of what changed and why.

1. Submit subcontract list in the following format:
a. PDF electronic file.

J. Coordination Drawings: Comply with requirements specified in Section 01 31 00 "Project Management and Coordination."
K. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of architects and owners, and other information specified.

L. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on American Welding Society (AWS) forms. Include names of firms and personnel certified.

Page 348 of 1257 ends

SUBMITTAL PROCEDURES 01 33 00 – 9 of 12
SECTION 01 33 00 SUBMITTAL PROCEDURES
M. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

N. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.

O. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

P. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

Q. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

R. Product Test Reports: Submit written reports indicating current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

S. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project.

T. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.

U. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

V. Field Test Reports: Submit reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

Page 349 of 1257 ends

SUBMITTAL PROCEDURES 01 33 00 – 10 of 12
SECTION 01 33 00 SUBMITTAL PROCEDURES
W. Design Data: Prepare and submit written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations.

Include list of assumptions and other performance and design criteria and a summary of loads.

Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.

2.2 DELEGATED-DESIGN SERVICES (Including DEFERRED APPROVALS) A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.

1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Architect.

B. Delegated-Design Services Certification: In addition to Shop Drawings, Product Data, and other required submittals, submit digitally-signed PDF electronic file and three (3) paper copies of certificate, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.

1. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services.

PART 3 - EXECUTION

3.1 CONTRACTOR'S REVIEW
A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Architect and Construction Manager.

B. Project Closeout and Maintenance/Material Submittals: Refer to requirements in Section 01 77 00 "Closeout Procedures."
C. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

3.2 ARCHITECT'S AND CONSTRUCTION MANAGER'S ACTION
A. General: Construction Manager will not review submittals that do not bear Contractor's approval stamp and will return them without action.

Page 350 of 1257 ends

SUBMITTAL PROCEDURES 01 33 00 – 11 of 12
SECTION 01 33 00 SUBMITTAL PROCEDURES
B. Action Submittals: Architect and Construction Manager will review each submittal, make marks to indicate corrections or modifications required, and return it. Architect will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action taken, as follows:

1. Final Unrestricted Release: Where the submittal is marked "No Exceptions Taken," the Work covered by the submittal may proceed provided it complies with the Contract Documents. Final acceptance will depend on that compliance.

2. Final-but-Restricted Release: Where the submittal is marked "Reviewed with Exceptions as Noted," the Work covered by the submittal may proceed provided it complies with both Architect’s notations and corrections on the submittal and the Contract Documents. Final acceptance will depend on that compliance.

3. Returned for Resubmittal: Where the submittal is marked "Revise and Resubmit," do not proceed with the Work covered by the submittal, including purchasing, fabrication, delivery, or other activity for the product submitted. Revise or prepare a new submittal according to Architect’s notations and corrections.

4. Rejected: Where the submittal is marked "Rejected," do not proceed with the Work covered by the submittal. Prepare a new submittal for a product that complies with the Contract Documents.

5. Incomplete: Where the submittal is marked "Submit Specified Item," do not proceed with the Work covered by the submittal. Prepare additional information requested, or required by the Contract Documents, that indicates compliance with requirements.

C. Informational Submittals: Architect and Construction Manager will review each submittal and will not return it or will return it if it does not comply with requirements. Construction Manager will forward each submittal to appropriate party.

D. Incomplete submittals are not acceptable, will be considered nonresponsive, and will be returned without review.

E. Submittals not required by the Contract Documents may not be reviewed and may be discarded.

END OF SECTION

Page 351 of 1257 ends

SUBMITTAL PROCEDURES 01 33 00 – 12 of 12
SECTION 01 33 00 SUBMITTAL PROCEDURES

PAGE INTENTIONALLY LEFT BLANK

Page 352 of 1257 ends

STORM WATER POLLUTION PREVENTION 01 35 44 - 1 of 10
SECTION 01 35 44 STORM WATER POLLUTION PREVENTION
PART 1 - GENERAL

1.1 DESCRIPTION
A. The work of this section consists of implementing measures to prevent Storm Water Pollution during construction activities, in accordance with Federal, State, and local regulations, and in accordance with the Storm Water Pollution Prevention Plan (SWPPP) to be prepared for this project.

1.2 SUBMITTALS
A. Submit SWPPP to Owner after contract award and before the preconstruction conference.

B. Plans showing proposed arrangements and methods for control of erosion, sedimentation, and pollutant conveyance in storm water resulting from construction activities (Sheet C-7.2).The contractor shall provide final arrangement, methods of control and conveyance in the Storm Water Pollution Prevention Plan that satisfies all State NPDES permit requirements.

C. Provide sufficient information for evaluation of the following:

1. Erosion protection measures and products

2. Drainage management strategies

3. Surface restoration
D. Submit schedules for inspection and monitoring of all SWPPP measures.

E. Submit manufacturer’s product information and installation recommendations for silt fence, filter fabric and erosion control blanket, straw bales, and any other materials proposed for use on this project.

F. Contractor shall register on the State Water Resources Control Board (SWRCB) on- line Storm Water Multiple Application and Report Tracking System (SMARTS) database and submit the User Identification (ID) to the Owner. Owner will file a Notice of Intent (NOI) and link the Contractor User ID as a Data Entry Person for required entries (i.e., SWPPP, Annual Reports, Ad Hoc Reports) in accordance with the determined Risk Level monitoring and sampling requirements.

1.3 QUALITY ASSURANCE
A. Before commencing construction activities, such as grading, excavation or filling in any part of the site, Contractor shall plan for temporary structures to guide runoff away from the work area and to capture eroded material before it reaches natural water courses. The measures shall be in accordance with reviewed and approved SWPPP.

Page 353 of 1257 ends

STORM WATER POLLUTION PREVENTION 01 35 44 - 2 of 10
SECTION 01 35 44 STORM WATER POLLUTION PREVENTION
B. Arrange construction activities to minimize erosion to the maximum practical extent.

Clearing, excavation, and grading shall be limited to those areas of the project site necessary for construction. Minimize the area exposed and unprotected.

C. Clearly mark and delineate the limits of work activities. Do not allow equipment to operate outside the limits of work or to disturb existing vegetation. Complete excavation and grading during the dry season to the maximum extent possible.

1.4 REGULATORY REQUIREMENTS
A. The Contractor shall comply with provisions of Federal, State, and local regulations and requirements that govern the Contractor's operations and storm water and non- storm water discharges from the project site and areas outside the project limits during construction.

B. The project site is more than one acre and therefore requires compliance with the State Water Resources Control Board statewide general permit entitled "Order No. 2009-0009– DWQ (as amended by Order No. 2010-0014-DWQ), National Pollutant Discharge Elimination System General Permit No. CAS000002, Waste Discharge Requirements for Discharges of Storm Water Runoff Associated with Construction and Land Disturbance Activities" (Construction General Permit) that regulates discharges of storm water and nonstorm water from construction activities disturbing one acre or more of land surface, or that are part of a common plan of development. The Construction General Permit is available for review at:
http://www.waterboards.ca.gov/water_issues/programs/stormwater/ This project shall conform to applicable provisions of this Permit and modifications thereto.

C. This project lies within the boundaries of the San Francisco Bay Region (2) Regional Water Quality Control Board (SFRWQCB). The SFRWQCB has issued Waste Discharge Requirements and National Pollutant Discharge Elimination System (NPDES) Permit for the discharge of stormwater runoff from the municipal separate storm sewer systems (MS4s) including construction sites (San Francisco Bay Region Municipal Regional Stormwater NPDES Permit Order No. R2-2015-0049 NPDES Permit No. CAS612008 November 19, 2015). The MS4 Regional Stormwater NPDES Permit is available to review at:
https://www.waterboards.ca.gov/sanfranciscobay/water_issues/programs/stormwater /Municipal/R2_2015_0049_amended.pdf
This project shall conform to applicable provisions of this Permit and modifications thereto.

D. Storm Water Pollution Prevention Plan (SWPPP)

1. The SWPPP will include a description of best management practices (BMPs) that will be implemented to reduce the pollutants in stormwater and non-stormwater discharges to assure compliance with the terms and conditions of the Construction

Page 354 of 1257 ends

STORM WATER POLLUTION PREVENTION 01 35 44 - 3 of 10
SECTION 01 35 44 STORM WATER POLLUTION PREVENTION
General Permit.

2. A Qualified Stormwater Developer (QSD) shall prepare the SWPPP and a Qualified Stormwater Practitioner shall ensure implementation of the SWPPP.

3. The SWPPP shall include the following information and forms:
a. Site description
b. Expected sequencing of operations and construction schedule c. Weather monitoring procedure
d. Descriptions and details of erosion controls, including dust control e. Erosion control plans
f. Controls for other potential onsite storm water pollutants g. Applicable specifications
h. Maintenance and inspection procedures and forms
i. Description of potential non-storm water discharges at site j. Notice of Intent (NOI) form
k. Notice of Termination (NOT) form
l. QSD/QSP Certification forms
m. Other record keeping forms and procedures
n. Good housekeeping practices and procedures, including vehicle washdown areas, protection of equipment storage and maintenance areas, and sweeping of roadways related to hauling activities

4. The Owner will review the draft SWPPP. Contractor QSD will address Owner review comments and submit revised SWPPP for Owner approval. Upon Owner approval, Contractor QSD and Owner representative will sign the approved SWPPP.

5. Contractor will upload approved SWPPP onto SMARTS database for Notice of Intent (NOI) submittal.

6. When the SWRCB approves the NOI, the SWPPP will be the document in force on the project.

7. Place the SWPPP and all updates in a three-ring binder so that completed inspection forms and other records may be inserted. The Contractor shall maintain a copy of the SWPPP and all associated records and forms on site throughout the construction period.

8. The SWPPP shall be available for public inspection. The Contractor shall notify the Owner immediately upon request from the regulatory agencies to enter, inspect, sample, monitor, or otherwise access the project site or the Contractor's records pertaining to water pollution control work. The Contractor and the Owner shall provide copies of correspondence, notices of violation, enforcement actions, or proposed fines by regulatory agencies to the requesting regulatory agency.

9. Implement the SWPPP as required throughout the construction period and maintain all erosion control elements in proper working order until final acceptance of project.

Page 355 of 1257 ends

STORM WATER POLLUTION PREVENTION 01 35 44 - 4 of 10
SECTION 01 35 44 STORM WATER POLLUTION PREVENTION

10. Do not perform clearing and grubbing or earthwork until applicable BMPs have been installed.

11. Prior to construction, the Contractor and all subcontractors shall sign certifications (included in the SWPPP) that they understand the requirements of the Construction General Permit and SWPPP. All Contractor and subcontractor crews shall comply with the requirements of the Construction General Permit under the supervision of the Contractor QSP who will be responsible for implementing the SWPPP. The Contractor QSP shall ensure that emergency procedures and the SWPPP are updated as needed and available for inspection. The SWPPP (including inspection forms) and all data used to complete the NOI shall be provided to the Owner at the completion of the project.

12. SWPPP Inspections and Amendments
a. The Contractor QSP and/or trained crew under QSP supervision will perform weekly inspections of the project site in accordance with the SWPPP. Inspections shall be documented on forms provided in the SWPPP binder. b. It may be necessary to revise the SWPPP during construction to make necessary improvements or to respond to unforeseen conditions noted during construction or site inspections. For that purpose, the SWPPP shall specify the mechanism whereby revisions may be proposed by the Contractor or the Owner and incorporated into the SWPPP, including review and acceptance of minor changes. The Contractor and the Owner will jointly accept and sign each revision to the SWPPP before implementation. Accepted modifications will be implemented within 7 calendar days following the date of the inspection when deficiencies or necessary corrections are first noted.
c. Temporary erosion and pollution control measures shall be used to correct conditions that develop during construction that were not foreseen during design, that are needed prior to installation of permanent control features, or that are needed temporarily to control erosion that developed during normal construction practices but are not associated with permanent control features on the project.
d. Provide additional temporary erosion and pollution controls made necessary by Contractor’s errors or negligence at no additional cost to the Owner.

E. Notice of Intent (NOI)

1. Owner will complete NOI form on SMARTS and submit to SWRCB after accepted SWPPP has been uploaded by Contractor.

2. Annual Reports are due to the SWRCB SMARTS by September 1 of each year. Contractor shall submit Annual Reports and any Ad Hoc Reports onto SMARTS by August 15 for Owner review.

F. Notice of Termination (NOT)
G. Upon final acceptance, the Owner will file the NOT.

Page 356 of 1257 ends

STORM WATER POLLUTION PREVENTION 01 35 44 - 5 of 10
SECTION 01 35 44 STORM WATER POLLUTION PREVENTION

1.5 PROJECT CONDITIONS
A. The Contractor shall maintain records of work performed on the sediment control structures.

B. The Contractor shall not remove any erosion or sediment control measure without prior permission from the Owner.

C. The Contractor shall obtain approval from the Owner prior to making changes to erosion control plans.

1.6 SEQUENCE OF CONSTRUCTION
A. The Contractor shall be responsible for arranging and conducting an Erosion and Sediment Control meeting/briefing to inform all parties scheduled to be on-site during the project of the measures to be implemented for proper erosion and sediment control (may be included as part of the preconstruction meeting).

1. Installation of silt fences, storm drain protection, and all other forms of erosion and sediment control shall not begin until after this meeting has occurred.

B. The Contractor shall notify the Owner in writing and by telephone of the following events:

1. The required erosion and sediment control meeting/briefing.

2. Following installation of required sediment control structures.

3. Prior to removal of or modification to sediment control structures.

4. Prior to removal of all sediment control structures.

C. Silt fences, storm drain protection, and all other forms of erosion and sediment control shall be installed, inspected, and accepted by the Contractor before beginning any utility excavation.

D. Temporary silt fences shall be installed around any stockpiles and/or excavated material that cannot be backfilled during the same day in which it was excavated.

Temporary silt fences shall also be placed immediately downstream of any utility trench that has not been backfilled at the end of the working day. Temporary silt fences shall be installed prior to leaving the work site for the day.

E. Silt fences and storm drain protection shall be inspected by the Contractor weekly.

Repairs to these devices shall be completed prior to leaving the work site for the day.

F. The Contractor shall prevent the deposition of materials onto paved areas. The Contractor shall inspect the paved areas for deposited materials weekly and remove the materials immediately.

G. Silt fences shall be removed with permission of the Owner within 20 working days

Page 357 of 1257 ends

STORM WATER POLLUTION PREVENTION 01 35 44 - 6 of 10
SECTION 01 35 44 STORM WATER POLLUTION PREVENTION
after final acceptance of the project and/or after the establishment of permanent stabilization of all excavations and fill areas.

PART 2 - PRODUCTS

2.1 EQUIPMENT
A. Before the work begins, sufficient equipment shall be available on the site to assure that the operation and adequacy of the erosion control plans can be continuously maintained.

2.2 EROSION CONTROL MEASURES
A. Erosion control measures shall consist of silt fencing or equivalent (eg. wattles, etc.), barrier protectors, straw bales, temporary soil retention blankets, excelsior drainage filters, sediment traps and berms.

B. Berms and excelsior drainage filters shall be used to form sediment traps and to control run- on and run-off into other areas, including creeks, streams, marshes, access roads, well areas, and the staging areas.

C. Erosion control measures shall be used to contain only direct precipitation in the construction zone. The contained water shall be allowed to percolate into the ground or drain slowly through the drainage filter sediment traps.

D. Earthen sediment traps or holding ponds shall not be used unless accepted by the Owner.

PART 3 - EXECUTION

3.1 GENERAL DESCRIPTION
A. Furnish, install, maintain, and operate necessary control measures and other equipment necessary to prevent erosion to the maximum extent practical, including implementation of Best Management Practices (BMPs).

1. Temporary measures shall be to Contractor's own design and Contractor shall be solely responsible for risks related to the management of erosion control during construction.

B. Effective measures shall be initiated prior to the commencement of clearing, grading, excavation, or other operations that will disturb the natural erosion protection.

C. Schedule work to expose areas subject to erosion for the shortest possible time, and preserve natural vegetation to the greatest extent practicable. Temporary storage and construction buildings shall be located, and construction traffic routed, to minimize erosion.

Temporary fast-growing vegetation or other suitable ground cover shall be provided as necessary to control runoff.

Page 358 of 1257 ends

STORM WATER POLLUTION PREVENTION 01 35 44 - 7 of 10
SECTION 01 35 44 STORM WATER POLLUTION PREVENTION

3.2 METHODS
A. Construct berms to reduce runoff velocity as well as direct surface runoff around and away from all fuel containment, storage, and borrow areas.

B. Divert surface runoff around and away from cut and fill slopes by constructing berms or ditches at the base of disturbed slopes. Provide conveyance for the runoff in temporary pipes or protected channels to temporary sediment traps.

C. Place drainage filters around all catch basins to create sediment traps to control run- off from the construction area.

D. Excess water used for dust control shall be contained within the demolition areas by the erosion control measures.

3.3 MAINTENANCE OF TEMPORARY FACILITIES
A. Inspect erosion and sediment control structures weekly. Ensure erosion and sediment control structures remain effective throughout excavation and grading operations.

Relocate structures as necessary.

B. Inspect control structures after each significant rainfall. Promptly repair breaches which occur.

C. The Contractor shall remove entrapped sediment from behind excelsior drainage filter after each storm.

3.4 DISPOSAL OF SEDIMENT FROM STORM WATER POLLUTION CONTROL

STRUCTURES
A. Sediment excavated from temporary sediment control structures shall be disposed on the site with general fill, or with topsoil. Sediment shall be allowed to dry out as required before reuse.

B. Contractor shall place the sediment removed from traps and other structures where it will not enter a storm drain or watercourse and where it will not immediately reenter the basin.

3.5 REMOVAL OF TEMPORARY STORM WATER POLLUTION CONTROL

MEASURES
A. All temporary control measures shall be removed with permission of the Owner within 20 working days after final acceptance of the Project or once grading is completed and slopes have stabilized.

Page 359 of 1257 ends

STORM WATER POLLUTION PREVENTION 01 35 44 - 8 of 10
SECTION 01 35 44 STORM WATER POLLUTION PREVENTION
SWPPP Contents
a. SWPPP Certifications and Approval
b. Risk Level
c. Table of Contents
d. Qualified SWPPP Developer
e. Legally Responsible Person
f. Amendment Log
g. SWPPP Requirements
• Permit registration documents
• SWPPP availability and implementation
• SWPPP amendments
• Retention of records
• Required non-compliance reporting
• Annual report
• Changes to permit coverage
• Notice of Termination
h. Project Information
• Site description
• Existing conditions
• Existing drainage
• Geology and groundwater
• Project description
• Developed condition
• Permits and governing documents
• Stormwater run-on from off-site areas
• Findings of the construction site sediment and receiving water risk determination
• Construction schedule
• Potential construction activity and pollutant sources • Identification of non-stormwater discharges
• Required site map information
i. Best Management Practices
• Schedule for BMP implementation
• Erosion and sediment control
• Non-stormwater controls and waste and materials management • Post-construction stormwater management measures
j. BMP inspection and maintenance
• Rain Event Action Plans
k. Training
l. Responsible parties and operators
• Responsible parties

Page 360 of 1257 ends

STORM WATER POLLUTION PREVENTION 01 35 44 - 9 of 10
SECTION 01 35 44 STORM WATER POLLUTION PREVENTION
• Contractor list
m. Construction Monitoring Program
• Weather and rain event tracking
• Monitoring locations
• Safety and monitoring exemptions
• Visual monitoring
• Routine observations and inspections: Routine BMP inspections, Nonstormwater discharge observations • Rain-event triggered observations and inspections: Visual observations prior to a forecasted qualifying rain event, BMP inspections during an extended storm event, Visual observations following a qualifying rain event • Visual monitoring procedures
• Visual monitoring follow-up and reporting
• Visual monitoring locations
• Water quality sampling and analysis
• Sampling and analysis plan for non-visible pollutants in stormwater runoff discharges: Sampling scheduled, sampling locations, monitoring preparation, analytical constituents, sample collection, sample analysis, data evaluation and reporting
• Sampling and analysis plan for pH and turbidity and stormwater runoff discharges: Sampling schedule, sampling locations, monitoring preparation, field parameters, sample collection, field measurements, data evaluation and reporting
• Sampling and analysis plan for non-stormwater discharges: Sampling schedule, sampling locations, monitoring preparation, analytical constituents, sample collection, sample analysis, data evaluation and reporting
• Additional monitoring following an NEL exceedance
• Training of sampling personnel
• Sample collection and handling
• Sample documentation procedures
• Records retention
n. Attachments
• Construction General Permit
• Risk Level calculations
• Water Pollution Control Drawings
• Permit Registration Documents/Amendments
• QSD/QSP Certifications
• SWPPP Amendment Certifications
• Construction Schedule

Page 361 of 1257 ends

STORM WATER POLLUTION PREVENTION 01 35 44 - 10 of 10
SECTION 01 35 44 STORM WATER POLLUTION PREVENTION
• Construction Activities, Materials Used, and Associated Pollutants • CASQA Stormwater BMP Handbook Portal: Construction Fact Sheets • BMP Inspection Form
• Training Reporting Form
• Weather forecast reports
• Monitoring records
• Field meter instructions

END OF SECTION

Page 362 of 1257 ends

QUALITY REQUIREMENTS 01 40 00 - 1 of 8
SECTION 01 40 00 QUALITY REQUIREMENTS
PART 1 - GENERAL

1.1 SUMMARY
A. This Section includes administrative and procedural requirements for quality assurance and quality control.

B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.

1. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and control procedures that facilitate compliance with the Contract Document requirements.

2. Requirements for Contractor to provide quality-assurance and control services required by Architect, Owner, or authorities having jurisdiction are not limited by provisions of this Section.

3. Specific test and inspection requirements are not specified in this Section.

1.2 DEFINITIONS
A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.

B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Services do not include contract enforcement activities performed by Architect.

C. Mockups: Full-size, physical assemblies that are constructed on-site. Mockups are used to verify selections made under sample submittals, to demonstrate aesthetic effects and, where indicated, qualities of materials and execution, and to review construction, coordination, testing, or operation; they are not Samples. Approved mockups establish the standard by which the Work will be judged.

D. Laboratory Mockups: Full-size, physical assemblies that are constructed at testing facility to verify performance characteristics.

E. Preconstruction Testing: Tests and inspections that are performed specifically for the Project before products and materials are incorporated into the Work to verify performance or compliance with specified criteria.

F. Product Testing: Tests and inspections that are performed by an NRTL, an NVLAP, or a testing agency qualified to conduct product testing and acceptable to authorities

Page 363 of 1257 ends

QUALITY REQUIREMENTS 01 40 00 - 2 of 8
SECTION 01 40 00 QUALITY REQUIREMENTS
having jurisdiction, to establish product performance and compliance with industry standards.

G. Source Quality-Control Testing: Tests and inspections that are performed at the source, i.e., plant, mill, factory, or shop.

H. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work.

I. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.

J. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.

1. Using a term such as "carpentry" does not imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter." It also does not imply that requirements specified apply exclusively to Tradespeople of the corresponding generic name.

K. Experienced: When used with an entity, "experienced" means having successfully completed a minimum of five previous projects similar in size and scope to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction. See specific specification sections for additional experience requirements.

1.3 CONFLICTING REQUIREMENTS
A. General: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement as defined in the General Conditions. Refer uncertainties and requirements that are different, but apparently equal, to Architect for a decision before proceeding.

B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits.

To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Architect for a decision before proceeding.

1.4 SUBMITTALS
A. Qualification Data: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.

Page 364 of 1257 ends

QUALITY REQUIREMENTS 01 40 00 - 3 of 8
SECTION 01 40 00 QUALITY REQUIREMENTS
B. Reports: Prepare and submit certified written reports that include the following:

1. Date of issue.

2. Project title and number.

3. Name, address, and telephone number of testing agency.

4. Dates and locations of samples and tests or inspections.

5. Names of individuals making tests and inspections.

6. Description of the Work and test and inspection method.

7. Identification of product and Specification Section.

8. Complete test or inspection data.

9. Test and inspection results and an interpretation of test results.

10. Record of temperature and weather conditions at time of sample taking and testing and inspecting.

11. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements.

12. Name and signature of laboratory inspector.

13. Recommendations on retesting and re-inspecting.

C. Permits, Licenses, and Certificates: For Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.

1.5 QUALITY ASSURANCE
A. General: Qualifications paragraphs in this Article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.

B. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.

C. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

D. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or products that are similar to those indicated for this Project in material, design, and extent.

Page 365 of 1257 ends

QUALITY REQUIREMENTS 01 40 00 - 4 of 8
SECTION 01 40 00 QUALITY REQUIREMENTS
F. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.

1. Requirement for specialists shall not supersede building codes and regulations governing the Work.

G. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspecting indicated, as documented according to ASTM E 548; and with additional qualifications specified in individual Sections; and where required by authorities having jurisdiction, that is acceptable to authorities.

1. NRTL: A nationally recognized testing laboratory according to 29 CFR 1910.7.

2. NVLAP: A testing agency accredited according to NIST's National Voluntary Laboratory Accreditation Program.

H. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.

I. Mockups: Before installing portions of the Work requiring mockups, build mockups for each form of construction and finish required to comply with the following requirements, using materials indicated for the completed Work:

1. Build mockups in location and of size indicated or, if not indicated, as directed by Architect.

2. Notify Construction Manager seven (7) days in advance of dates and times when mockups will be constructed.

3. Demonstrate the proposed range of aesthetic effects and workmanship.

4. Obtain Architect's approval of mockups before starting work, fabrication, or construction.

5. Maintain mockups during construction in an undisturbed condition as a standard for judging the completed Work.

6. Demolish and remove mockups when directed, unless otherwise indicated.

J. Laboratory Mockups: Comply with requirements of preconstruction testing and those specified in individual Sections in Divisions 02 through 48.

1.6 QUALITY CONTROL
A. Owner Responsibilities: Where quality-control services are indicated as Owner's responsibility, Owner will engage a qualified testing agency to perform these services.

1. Owner will furnish Contractor with names, addresses, and telephone numbers of testing agencies engaged and a description of types of testing and inspecting they are engaged to perform.

Page 366 of 1257 ends

QUALITY REQUIREMENTS 01 40 00 - 5 of 8
SECTION 01 40 00 QUALITY REQUIREMENTS

2. Costs for retesting and reinspecting construction that replaces or is necessitated by work that failed to comply with the Contract Documents will be charged to Contractor (contract sum adjusted through change order procedures).

B. Tests and inspections not explicitly assigned to Owner are Contractor's responsibility. Unless otherwise indicated, provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not.

1. Where services are indicated as Contractor's responsibility, engage a qualified testing agency to perform these quality-control services. a. Contractor shall not employ same entity engaged by Owner, unless agreed to in writing by Owner.

2. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspecting will be performed.

3. Where quality-control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality-control service.

4. Testing and inspecting requested by Contractor and not required by the Contract Documents are Contractor's responsibility.

5. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.

C. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections.

D. Retesting/Re-inspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that replaced Work that failed to comply with the Contract Documents.

E. Testing Agency Responsibilities: Cooperate with Architect and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.

1. Notify Architect and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.

2. Determine the location from which test samples will be taken and in which in-situ tests are conducted.

3. Conduct and interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.

4. Submit a certified written report, in duplicate, of each test, inspection, and similar qualitycontrol service through Contractor.

5. Does not release, revoke, alter, or increase the Contract Document requirements or approve or accept any portion of the Work.

6. Do not perform any duties of Contractor.

Page 367 of 1257 ends

QUALITY REQUIREMENTS 01 40 00 - 6 of 8
SECTION 01 40 00 QUALITY REQUIREMENTS
F. Associated Services: Cooperate with agencies performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:

1. Access to the Work.

2. Incidental labor and facilities necessary to facilitate tests and inspections.

3. Adequate quantities of representative samples of materials that require testing and inspecting. Assist agency in obtaining samples.

4. Facilities for storage and field curing of test samples.

5. Delivery of samples to testing agencies.

6. Preliminary design mix proposed for use for material mixes that require control by testing agency.

7. Security and protection for samples and for testing and inspecting equipment at Project site.

G. Coordination: Coordinate sequence of activities to accommodate required qualityassurance and -control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.

1. Schedule times for tests, inspections, obtaining samples, and similar activities.

1.7 SPECIAL TESTS AND INSPECTIONS
A. Special Tests and Inspections: Owner will engage a qualified testing agency, special inspector and/or Essential Services Inspector to conduct special tests and inspections required by authorities having jurisdiction as the responsibility of Owner, and as follows:

1. Verifying that manufacturer maintains detailed fabrication and quality-control procedures and reviewing the completeness and adequacy of those procedures to perform the Work.

2. Notifying Architect and Contractor promptly of irregularities and deficiencies observed in the Work during performance of its services.

3. Submitting a certified written report of each test, inspection, and similar quality- control service to Architect with copy to Contractor and to authorities having jurisdiction.

4. Submitting a final report of special tests and inspections at Substantial Completion, this includes a list of unresolved deficiencies.

5. Interpreting tests and inspections and stating in each report whether tested and inspected work complies with or deviates from the Contract Documents.

6. Retesting and reinspecting corrected work.

PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION

3.1 TEST AND INSPECTION LOG
A. Test and Inspection Log: Prepare a record of tests and inspections. Include the

Page 368 of 1257 ends

QUALITY REQUIREMENTS 01 40 00 - 7 of 8
SECTION 01 40 00 QUALITY REQUIREMENTS
following:

1. Date test or inspection was conducted.

2. Description of the Work tested or inspected.

3. Date test or inspection results were transmitted to Architect.

4. Identification of testing agency or special inspector conducting test or inspection.

B. Maintain log at Project site. Post changes and revisions as they occur. Provide access to test and inspection log for Architect's and Construction Manager's reference during normal working hours.

3.2 REPAIR AND PROTECTION
A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.

1. Provide materials and comply with installation requirements specified in other Specification Sections. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible.

2. Comply with the Contract Document requirements for "Cutting and Patching." B. Protect construction exposed by or for quality-control service activities.

C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.

END OF SECTION

Page 369 of 1257 ends

QUALITY REQUIREMENTS 01 40 00 - 8 of 8
SECTION 01 40 00 QUALITY REQUIREMENTS

PAGE INTENTIONALLY LEFT BLANK

Page 370 of 1257 ends

MOCK-UPS 01 43 39 - 1 of 2
SECTION 01 43 39 MOCK-UPS
2 PART 1 – GENERAL

1.1 MOCK-UP SUMMARY
A. Mock-ups will be used to review of appearance, quality of workmanship, coordination, compatibility, and relationships with adjacent materials. Unless otherwise specifically indicated mock-ups shall be constructed in place at location directed by Architect.

Approved mock ups may remain as part of the work.

1.2 SUBMITTALS
A. Mock-ups shall not be fabricated until after acceptance of required submittals for all materials to be incorporated into the mock-ups. This means that the Project schedule shall take into account early submittal of these components to the Architect.

B. Samples: Prior to construction of mock-ups, provide samples as specified in the respective Specification Sections included as part of the mock-ups.

1.3 QUALITY ASSURANCE
A. Design Concept: Mock-up requirements are intended to establish function, workmanship, finish, and color for conformance with the architectural design intent.

B. Purpose: To verify suitability of colors, finishes, and satisfactory integration of building materials and components indicated and required.

C. Performance: Mock-ups shall be constructed for the Architect’s review for compliance with the Contract Documents and shall be used as a standard for the final installation.

D. Make necessary additions and modifications to mock-ups as directed by the Architect.

E. Modify mock-ups, or construct or install new components if requested by the Architect, until final acceptance is obtained.

F. Mock-ups shall serve as the standard for subsequent work of like kind after approval by the Architect. Be prepared, at no additional cost to the Owner, to make as many modifications as required to achieve mock-ups that are acceptable to the Architect and of sufficient quality to serve as the standard for the complete Project.

G. Following acceptance, mock-ups shall serve as a performance standard of quality and appearance of the work it represents, including the interface with adjacent

Page 371 of 1257 ends

MOCK-UPS 01 43 39 - 2 of 2
SECTION 01 43 39 MOCK-UPS
2 materials and components as applicable.

H. Coordinate fabrication, delivery, assembly, and installation with related materials to be included in the mock-ups. Construction of the mock-up assemblies shall be under the supervision of the same personnel who will be employed for the subsequent work.

I. Maintain mock-ups in neat, clean condition until removal or final acceptance. Repair damage as required to maintain in condition suitable for review and approval.

J. Scheduling:

1. Construct mock-ups in a timely manner to permit review and modifications such that the work is not delayed.

2. Do not proceed with ordering of components or construction subject to mockup approval until after approvals have been obtained.

3. Provide the Architect not less than 10 working days notice of the time each component is ready for review.

4. Include line item in the construction schedule for the building section mockup, showing submittals, construction, review, and approval periods.

PART 2 – PRODUCTS

2.1 MATERIALS
A. As specified in the respective Sections of the Specifications.

PART 3 – EXECUTION

3.1 EXTERIOR BUILDING MOCK-UP
A. Provide building mock-up of building area indicated where directed by the Architect.

B. Purpose: Establish standards for work indicated and specified to be included in mockups to demonstrate quality of workmanship, materials, colors, and textures required by the Contract Documents. Include roof, roof overhang, soffits, windows, doors, glazing, sealants, siding and cladding, flashings, and other exterior materials.

1. Mock-up will be used by the Architect to test color and material alternatives and to approve final colors, textures, and workmanship.

2. Interior finishes will not be required to be installed on the interior side of the exterior building mock-up.

END OF SECTION

Page 372 of 1257 ends

TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 1 of 8
SECTION 01 50 00 TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL

1.1 SUMMARY
A. This Section includes requirements for temporary fencing, utilities, support facilities, and security and protection facilities.

1.2 DEFINITIONS
A. Permanent Enclosure: As determined by Architect, permanent or temporary roofing is complete, insulated, and weather tight; exterior walls are insulated and weather tight; and all openings are closed with permanent construction or substantial temporary closures.

1.3 USE CHARGES
A. General: Cost or use charges for temporary facilities shall be included in the Contract Sum.

Allow other entities to use temporary services and facilities without cost, including, but not limited to, Owner's construction forces, Construction Manager, Architect, occupants of Project, testing agencies, and authorities having jurisdiction.

B. Water Service: Water from Owner's existing water system is not available for use without metering and without payment of use charges. Contractor is responsible for coordination of this activity with the local municipality.

C. Electric Power Service: Contractor to provide connections and extensions of services as required for construction operations including the office trailers. Contractor will be responsible to coordinate and make arrangements with PG&E to provide temporary power to the construction site. Contractor will be responsible for all costs associated with the installation of temporary power and any and all use charges for the duration of the contract.

Contractor shall provide temporary power as required to allow for operation of office trailers, construction power and new modular building. Temporary power from PG&E is available in the immediate area of the site, contractor shall pursue engineering and installation of temporary power at their own cost.

D. Internet Service/Data: Temporary hardwired service is not currently available in the immediate area of the site, but contractor may pursue engineering and installation of temporary hardwired service at their own cost. Contractor may need to pursue other options to meet the contractual temporary service requirements (satellite, etc.).

E. Temporary Fencing: Contractor to provide temporary fencing at the perimeter of the project site with adequate protection provided to pedestrians outside of the project site. If there is any exposure to falling objects outside of the project site then the Contractor must provide a covered walkway. Contractor shall comply with FAA Orders and Standards for temporary fencing installed at airside (aircraft parking areas). Contractor shall install fencing to secure FAA Parking areas near ATCT during work at ATCT parking lots.

1.4 SUBMITTALS
A. Site Plan: Show temporary facilities, utility hookups, staging areas, and parking areas for construction personnel and Construction Managers.

B. Erosion- and Sedimentation-Control Plan: Show compliance with requirements of EPA

Page 373 of 1257 ends

TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 2 of 8
SECTION 01 50 00 TEMPORARY FACILITIES AND CONTROLS
Construction General Permit or authorities having jurisdiction, whichever is more stringent.

C. Fire-Safety Program: Show compliance with requirements of NFPA 241 and authorities having jurisdiction. Indicate Contractor personnel responsible for management of fire prevention program.

1.5 QUALITY ASSURANCE
A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.

B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.

1.6 PROJECT CONDITIONS
A. Temporary Use of Permanent Facilities: Installer of each permanent service shall assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Owner’s acceptance, regardless of previously assigned responsibility.

PART 2 - PRODUCTS

2.1 MATERIALS
A. Temporary Chain-Link Fencing: Minimum 2-inch, 9-gage, galvanized steel, chain-link fence with privacy screening fabric mesh; minimum 6 feet high (8 feet at airside) with galvanized steel pipe posts; minimum 2-3/8-inch- OD line posts and 2-7/8-inch- OD corner and pull posts, with 1-5/8-inch- OD top and bottom rails. Galvanized Steel posts will be required to be driven into the ground for support and stability or portable fencing, if appropriate, with sufficient hold down weight to prevent overturning.

2.2 TEMPORARY FACILITIES FOR PROJECT SITE
A. Field Offices for each site, General: Prefabricated or mobile units with serviceable finishes, temperature controls, and foundations adequate for normal loading.

B. Field Offices: Provide and maintain for the duration of the Work temporary offices on site for use by the Contractor and a separate onsite trailer for use by the Owner’s representatives (including Owner, Construction Manager and the Architect).

1. Owner’s Representative. This office shall be a self-contained construction trailer, minimum size 10’ X 44’, and shall be set up with an office at one end and an area for plans. The office will include a desk (minimum size of 30” X 60”), a rolling office chair and two (2) guest chairs. The plan area furnishings will include a 30” X 72” folding table, a small table with a coffee maker, (1) microwave, (1) mini refrigerator, (4) folding chairs, a plan table, a rolling plan rack, two trashcans, three (3) lockable 4 drawer filing cabinets, water cooler, fire extinguisher, smoke detector, and a complete set of unmarked Contract Documents for the Owner’s Representative’s use. The office shall also be equipped with a scanner/copier/printer and a dedicated data line. Two (2) dedicated parking spaces will be provided for use by the Construction Manager’s staff.

2. Offices shall be equipped with secure wireless internet capabilities to allow for onsite users access to email and the internet.

Page 374 of 1257 ends

TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 3 of 8
SECTION 01 50 00 TEMPORARY FACILITIES AND CONTROLS

3. Offices shall be provided with a door and lock with security bar and a window with a minimum size of 4 feet x 3 feet and security screen. Provide and maintain an electric heater and air conditioning along with adequate electric lighting for each office.

C. Office Supplies: The Contractor shall supply the field office of the Owner’s Representative with (2) cases of 8-1/2 x 11 paper, (1) case of 11 x 17 paper, (1) box post-it notes, (1) box white-out tape, (1) stapler with staples, (1) box assorted binder clips, (1) box paperclips, (1) box of pens, (1) box of pencils, Printer/Copier Toner or Ink, (2) surge protectors, (1) 24’ extension cord, (2) water cooler bottles, (1) box coffee cups, coffee, (3) rolls paper towels.

Supplies shall be restocked monthly and/or on an as-needed basis.

D. Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to accommodate materials and equipment for construction operations.

E. Temporary Field Fencing: Provide fence size, material and privacy screen fabric mesh to encompass each site, furnish and installed, equipped for entrance of utility trucks (16- foot gates) and man gates for easy access.

F. Network Setup: The network shall have the following requirements:

1. The internet connection must be separate service and independent of the Contractor’s and shall be the fastest speed available in the area with a minimum a 20- Meg upload / 20-Meg download speed. This should be accomplished via a hardwired connection. a. Wired network connections must be provided at
1) The Office, Planroom, and the Printer/Scanner.
b. Reasonable access to power for the equipment must be provided.

2. If it is necessary to “piggyback” off of an existing hard-wired line, the line provided to the Owner’s Representative shall be an unfiltered line, with no limitations set by the main line holder, such as access restrictions or DNS port blocking.

3. In the cases where a hard-wired connection is not available, the wireless connection provided must meet the same speed needs of 20-Meg upload / 20-Meg download. It shall also be of sufficient bandwidth to meet the needs of the staff.

4. In the case of sites where the internet speeds do not meet the above requirements, a cellular “hot-spot” is to be provided if resulting in a faster connection, along with a local storage device must be provided for the location to save the project data. The local storage device will be connected to the Kitchell network, and backed up during non-business hours to the Kitchell network server.

2.3 EQUIPMENT
A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.

B. HVAC Equipment: Unless Owner authorizes use of permanent HVAC system, provide vented, self-contained, liquid-propane-gas or fuel-oil heaters with individual space thermostatic control.

1. Use of gasoline-burning space heaters, open-flame heaters, or salamander-type heating units is prohibited.

2. Heating Units: Listed and labeled for type of fuel being consumed, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.

3. Permanent HVAC System: If Owner authorizes use of permanent HVAC system for temporary use during construction, provide filter with MERV of 8 at each return air grille in system and remove at end of construction.

Page 375 of 1257 ends

TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 4 of 8
SECTION 01 50 00 TEMPORARY FACILITIES AND CONTROLS
PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL
A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.

B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.

3.2 TEMPORARY UTILITY INSTALLATION FOR PROJECT SITE
A. General: Install temporary service or connect to existing service.

1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.

B. Electrical Power and Lighting:

1. Contractor will furnish and pay for power during the course of the work to the extent power is not in the building(s) or on the Site. Contractor shall be responsible for providing temporary facilities required on the Site to point of intended use.

2. Contractor shall furnish, wire for, install and maintain temporary electrical lights wherever it is necessary to provide illumination for the proper performance and/ or observe of the Work: a minimum of 20 foot-candles for rough work and 50 footcandles for finish work.

3. Contractor shall be responsible for maintaining existing lighting levels in the Project vicinity should temporary outage or service interruptions occur.

C. Sewers and Drainage: Provide temporary utilities to remove effluent lawfully.

1. Connect temporary sewers to municipal system as directed by authorities having jurisdiction. Coordination is the responsibility of the Contractor.

D. Water Service: Install water service and distribution piping in sizes and pressures adequate for construction and modular passenger terminal.

E. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of construction personnel. Comply with authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities. Provide connection to existing sanitary sewer for temporary passenger terminal modular.

F. Heating and Cooling: Provide temporary heating and cooling required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of low temperatures or high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed.

G. Ventilation and Humidity Control: Provide temporary ventilation required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed. Coordinate ventilation requirements to produce ambient condition required and minimize energy consumption.

H. Electric Power Service: It is the Contractor’s responsibility to coordinate with PG&E to obtain the temporary electrical service, including submission of services applications, load calculation, and single line diagrams. The Contractor will also be responsible for payment of

Page 376 of 1257 ends

TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 5 of 8
SECTION 01 50 00 TEMPORARY FACILITIES AND CONTROLS
the monthly PG&E invoices and all other temporary requirements as outlined within the specification section.

Contractor shall provide electric power service and distribution system of sufficient size, capacity, and power characteristics required for construction operations including office trailers.

1. See Section 1.3.C
I. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions.

1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system.

3.3 Temporary Controls
A. Noise Control

1. Contractor acknowledges that adjacent facilities may remain in operation during all or a portion of the Work, and it shall take all reasonable precaution to minimize noise as required by applicable lass and the Contract Documents.

2. Notices of proposed noisy operations, including without limitation, operation of pneumatic demolition tools, concrete saws, and other equipment, shall be submitted to the City a minimum of forty-eight (48) hours in advance of their performance.

Contractor responsible for obtaining all permits required for construction noise outside of the times allowable within the noise ordinance.

3. Contractor to meet the Conditions of Approval related to Noise Control as defined in the Contract Documents.

B. Noise and Vibration

1. Equipment and impact tools shall have intake and exhaust mufflers.

2. Contractor shall cooperate with the City to minimize and /or cease the use of noisy and vibratory equipment if that equipment becomes objectionable by its longevity.

3. Contractor to meet the Conditions of Approval related to noise and vibration as defined in the Contract Documents.

C. Dust and Dirt

1. Contractor shall conduct demolition and construction operations to minimize the generation of dust & dirt, and prevent dust and dirt from interfering with the progress of the Work and from accumulating in the Work and adjacent areas including, without limitation, occupied facilities.

2. Contractor shall periodically water exterior demolition and construction areas to minimize the generation of dust and dirt.

3. Contractor shall ensure that all hauling equipment and trucks carrying loads of soil and debris shall have their loads sprayed with water or covered with tarpaulins, and as otherwise required by local and state ordinance.

4. Contractor shall prevent dust and dirt from accumulating on walks, roadways, parking areas, and planting, and from washing into sewer and storm drain lines.

5. Contractor to meet the Conditions of Approval related to dust and dirt as defined in the Contract Documents.

6. Comply with FAA Orders and Standards.

3.4 SUPPORT FACILITIES INSTALLATION
A. General: Comply with the following:

1. Provide incombustible construction for offices, shops, and sheds located within

Page 377 of 1257 ends

TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 6 of 8
SECTION 01 50 00 TEMPORARY FACILITIES AND CONTROLS
construction area or within thirty (30) feet of building lines. Comply with NFPA 241.

2. Maintain support facilities until near Substantial Completion. Remove before Substantial Completion. Personnel remaining after Substantial Completion will be permitted to use permanent facilities, under conditions acceptable to Owner.

B. Temporary Roads and Paved Areas: Construct and maintain temporary roads and paved areas adequate for construction operations. Locate temporary roads and paved areas within construction limits indicated on Drawings.

1. Provide dust-control treatment that is nonpolluting and non-tracking. Reapply treatment as required to minimize dust.

C. Temporary Roads and Paved Areas: All areas are currently paved.

D. Traffic Controls: Comply with requirements of authorities having jurisdiction.

1. Protect existing site improvements to remain including curbs, pavement, and utilities.

2. Maintain access for fire-fighting equipment and access to fire hydrants.

E. Parking: Contractor is to provide temporary parking for construction personnel within confines of the designated construction site. If parking within the designated construction site becomes unavailable due to number of Trades, Subcontractors and Vendors, Contractor shall be responsible for coordinating with the City, or local jurisdiction for parking requirements, locations, permits, shuttle services, etc. Contractor is to review and follow all related Conditions of Approval, Laws and Regulations from the City of Ukiah.

F. Dewatering Facilities and Drains: Comply with requirements of authorities having jurisdiction. Maintain Project site, excavations, and construction free of water. (refer to demolition drawings for specifics)

1. Dispose of rainwater in a lawful manner that will not result in flooding Project or adjoining properties nor endanger permanent Work or temporary facilities.

G. Project Identification and Temporary Signs: Provide Project identification and other signs as indicated on drawings or required by the County or the City. Install signs where indicated to inform public and individuals seeking entrance to Project. Unauthorized signs are not permitted.

1. Provide temporary, directional signs for construction personnel and visitors.

2. Maintain and touchup signs so they are legible at all times.

H. Lifts and Hoists: Provide facilities necessary for hoisting materials and personnel.

1. Truck cranes and similar devices used for hoisting materials are considered "tools and equipment" and not temporary facilities.

3.5 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

B. Temporary Erosion and Sedimentation Control: Provide measures to prevent soil erosion and discharge of soil-bearing water runoff and airborne dust to adjacent properties and walkways, according to requirements of authorities having jurisdiction.

C. Stormwater Control: Comply with authorities having jurisdiction. Provide barriers in and around excavations and subgrade construction to prevent flooding by runoff of stormwater

Page 378 of 1257 ends

TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 7 of 8
SECTION 01 50 00 TEMPORARY FACILITIES AND CONTROLS
from heavy rains.

D. Pest Control: Engage pest-control service to recommend practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at Substantial Completion. Obtain extended warranty for Owner. Perform control operations lawfully, using environmentally safe materials.

E. Temporary Site Enclosure Fence: All costs associated with the install, monthly fencing rental fees and demobilization of the fencing will be the responsibility of the contractor. Furnish and install any additional site enclosure fence panels in a manner that will prevent people and animals from easily entering site except by entrance gates.

1. Temporary Fence: As required to enclose entire Project site or portion determined sufficient to accommodate construction operations and protection of the public.

Operations include temporary offices, parking, staging areas, actual construction site.

F. Security Enclosure and Lockup: Install substantial temporary enclosure around partially completed areas of construction. Contractor is responsible to ensure that the fencing and all gates are secured and locked prior to leaving the site on a daily basis to prevent unauthorized entrance, vandalism, theft, and similar violations of security.

G. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.

H. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weather-tight enclosure for building exterior.

1. Where heating or cooling is needed and permanent enclosure is not complete, insulate temporary enclosures.

2. Insulate partitions to provide noise protection to occupied areas.

3. Seal joints and perimeter. Equip partitions with dustproof doors and security locks.

4. Protect air-handling equipment.

5. Weather strip openings.

6. Provide walk-off mats at each entrance through temporary partition.

I. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with NFPA 241.

1. Smoking is prohibited in all construction areas.

2. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition according to requirements of authorities having jurisdiction.

3. Develop and supervise an overall fire-prevention and -protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings and information.

4. Provide temporary standpipes and hoses for fire protection. Hang hoses with a warning sign stating that hoses are for fire-protection purposes only and are not to be removed. Match hose size with outlet size and equip with suitable nozzles.

3.6 OPERATION, TERMINATION, AND REMOVAL
A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and

Page 379 of 1257 ends

TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 8 of 8
SECTION 01 50 00 TEMPORARY FACILITIES AND CONTROLS
abuse, limit availability of temporary facilities to essential and intended uses.

B. Maintenance: Maintain facilities in good operating condition until removal.

1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.

C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.

D. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.

1. Materials and facilities that constitute temporary facilities are property of Contractor.

Owner reserves right to take possession of Project identification signs.

2. At Substantial Completion, clean and renovate permanent facilities used during construction period. Comply with final cleaning requirements specified in Division 01 Section "Closeout Procedures."

END OF SECTION

Page 380 of 1257 ends

EXECUTION REQUIREMENTS 01 73 00 - 1 of 8
SECTION 01 73 00 EXECUTION REQUIREMENTS
PART 1 - GENERAL

1.1 SUMMARY
A. This Section includes general procedural requirements governing execution of the Work including, but not limited to, the following:

1. Construction layout.

2. Field engineering and surveying.

3. General installation of products.

4. Cutting and patching.

5. Progress cleaning.

6. Starting and adjusting.

7. Protection of installed construction.

8. Correction of the Work.

1.2 SUBMITTALS
A. Landfill Receipts: Submit copy of receipts issued by a landfill facility, licensed to accept hazardous materials, for hazardous waste disposal.

B. Certificates: Submit certificate signed by land surveyor certifying that location and elevation of improvements comply with requirements.

C. Survey reports and plots as detailed below.

1.3 QUALITY ASSURANCE
A. Land Surveyor Qualifications: A professional land surveyor who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing land-surveying services of the kind indicated.

B. Cutting and Patching: Comply with requirements for and limitations on cutting and patching of construction elements.

1. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as

Page 381 of 1257 ends

EXECUTION REQUIREMENTS 01 73 00 - 2 of 8
SECTION 01 73 00 EXECUTION REQUIREMENTS
intended or that results in increased maintenance or decreased operational life or safety.

1.4 EXAMINATION
A. Existing Utilities: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning sitework, investigate and verify the existence and location of underground utilities and other construction affecting the Work.

1. Before construction, verify the location and invert elevation at points of connection of sanitary sewer, storm sewer, and water-service piping; and underground electrical services.

2. Furnish location data for work related to Project that must be performed by public utilities serving Project site.

B. Acceptance of Conditions: Examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations.

1. Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers.

2. Examine roughing-in for mechanical and electrical systems to verify actual locations of connections before equipment and fixture installation.

3. Examine walls, floors, and roofs for suitable conditions where products and systems are to be installed.

4. Proceed with installation only after unsatisfactory conditions have been corrected.

Proceeding with the Work indicates acceptance of surfaces and conditions.

1.5 PREPARATION
A. Existing Utility Information: Furnish information to local utility that is necessary to adjust, move, or relocate existing utility structures, utility poles, lines, services, or other utility appurtenances located in or affected by construction. Coordinate with authorities having jurisdiction.

B. Field Measurements: Take field measurements as required to fit the Work properly.

Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work.

C. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.

D. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to Architect. Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.

Page 382 of 1257 ends

EXECUTION REQUIREMENTS 01 73 00 - 3 of 8
SECTION 01 73 00 EXECUTION REQUIREMENTS

1.6 CONSTRUCTION LAYOUT
A. Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify Architect promptly.

B. General: Engage a land surveyor to lay out the Work using accepted surveying practices.

1. Establish benchmarks and control points to set lines and levels at each story of construction and elsewhere as needed to locate each element of Project.

2. Establish limits on use of Project site.

3. Establish dimensions within tolerances indicated. Do not scale Drawings to obtain required dimensions.

4. Inform installers of lines and levels to which they must comply.

5. Check the location, level and plumb, of every major element as the Work progresses.

6. Notify Architect when deviations from required lines and levels exceed allowable tolerances.

7. Close site surveys with an error of closure equal to or less than the standard established by authorities having jurisdiction.

C. Site Improvements: Locate and lay out site improvements, including pavements, grading, fill and topsoil placement, utility slopes, and invert elevations.

D. Building Lines and Levels: Locate and lay out control lines and levels for structures, building foundations, column grids, and floor levels, including those required for mechanical and electrical work. Transfer survey markings and elevations for use with control lines and levels.

Level foundations and piers from two or more locations.

E. Record Log: Maintain a log of layout control work. Record deviations from required lines and levels. Include beginning and ending dates and times of surveys, weather conditions, name and duty of each survey party member, and types of instruments and tapes used. Make the log available for reference by Architect.

1.7 FIELD ENGINEERING
A. Reference Points: Locate existing permanent benchmarks, control points, and similar reference points before beginning the Work. Preserve and protect permanent benchmarks and control points during construction operations.

B. Benchmarks: Establish and maintain a minimum of two permanent benchmarks on Project site, referenced to data established by survey control points. Comply with authorities having jurisdiction for type and size of benchmark.

1. Record benchmark locations, with horizontal and vertical data, on Project Record Documents.

Page 383 of 1257 ends

EXECUTION REQUIREMENTS 01 73 00 - 4 of 8
SECTION 01 73 00 EXECUTION REQUIREMENTS
C. Certified Survey: On completion of foundation walls, major site improvements, and other work requiring field-engineering services, prepare a certified survey showing dimensions, locations, angles, and elevations of construction and sitework.

D. Final Property Survey: Prepare a final property survey showing significant features (real property) for Project. Include on the survey a certification, signed by land surveyor, that principal metes, bounds, lines, and levels of Project are accurately positioned as shown on the survey.

1. Recording: At Substantial Completion, have the final property survey recorded by or with authorities having jurisdiction as the official "property survey."

1.8 INSTALLATION
A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

1. Make vertical work plumb and make horizontal work level.

2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.

3. Conceal pipes, ducts, and wiring in finished areas, unless otherwise indicated.

B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.

C. Install products at the time and under conditions that will ensure the best possible results. Maintain conditions required for product performance until Substantial Completion.

D. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy.

E. Tools and Equipment: Do not use tools or equipment that produce harmful noise levels.

F. Templates: Obtain and distribute to the parties involved templates for work specified to be factory prepared and field installed. Check Shop Drawings of other work to confirm that adequate provisions are made for locating and installing products to comply with indicated requirements.

G. Anchors and Fasteners: Provide anchors and fasteners as required to anchor each component securely in place, accurately located and aligned with other portions of the Work.

1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by Architect.

2. Allow for building movement, including thermal expansion and contraction.

3. Coordinate installation of anchorages. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry.

Deliver such items to Project site in time for installation.

Page 384 of 1257 ends

EXECUTION REQUIREMENTS 01 73 00 - 5 of 8
SECTION 01 73 00 EXECUTION REQUIREMENTS
H. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.

I. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.

1.9 CUTTING AND PATCHING
A. Cutting and Patching, General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay.

1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.

B. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during installation or cutting and patching operations, by methods and with materials so as not to void existing warranties
C. Temporary Support: Provide temporary support of work to be cut.

D. Protection: Protect in-place construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.

E. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other work. Patch with durable seams that are as invisible as practicable. Provide materials and comply with installation requirements specified in other Sections, where applicable

1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate physical integrity of installation.

2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will minimize evidence of patching and refinishing.

F. Cleaning: Clean areas and spaces where cutting and patching are performed. Remove paint, mortar, oils, putty, and similar materials from adjacent finished surfaces.

1.10 PROGRESS CLEANING
A. General: Clean Project site and work areas daily, including common areas. Coordinate progress cleaning for joint-use areas where more than one installer has worked. Enforce requirements strictly. Dispose of materials lawfully.

1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.

2. Do not hold materials more than seven (7) days during normal weather or three (3) days if the temperature is expected to rise above 80 deg F.

Page 385 of 1257 ends

EXECUTION REQUIREMENTS 01 73 00 - 6 of 8
SECTION 01 73 00 EXECUTION REQUIREMENTS

3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.

B. Site: Maintain Project site free of waste materials and debris.

C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.

1. Remove liquid spills promptly.

2. Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area, as appropriate.

D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.

E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space.

F. Exposed Surfaces in Finished Areas: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.

G. Waste Disposal: Burying or burning waste materials on-site will not be permitted. Washing waste materials down sewers or into waterways will not be permitted.

H. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.

I. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

J. Limiting Exposures: Supervise construction operations to assure that no part of the construction completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.

1.11 STARTING AND ADJUSTING
A. Start equipment and operating components to confirm proper operation. Remove malfunctioning units, replace with new units, and retest.

B. Adjust operating components for proper operation without binding. Adjust equipment for proper operation.

C. Test each piece of equipment to verify proper operation. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.

Page 386 of 1257 ends

EXECUTION REQUIREMENTS 01 73 00 - 7 of 8
SECTION 01 73 00 EXECUTION REQUIREMENTS

1.12 PROTECTION OF INSTALLED CONSTRUCTION
A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.

B. Comply with manufacturer's written instructions for temperature and relative humidity.

1.13 CORRECTION OF THE WORK
A. Repair or remove and replace defective construction. Restore damaged substrates and finishes. Comply with requirements "Cutting and Patching."

1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

B. Restore permanent facilities used during construction to their specified condition.

C. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair.

D. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired.

E. Remove and replace chipped, scratched, and broken glass or reflective surfaces.

PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)

END OF SECTION

Page 387 of 1257 ends

EXECUTION REQUIREMENTS 01 73 00 - 8 of 8
SECTION 01 73 00 EXECUTION REQUIREMENTS

PAGE INTENTIONALLY LEFT BLANK

Page 388 of 1257 ends

CUTTING AND PATCHING 01 73 29 – 1 of 4
SECTION 01 73 29 CUTTING AND PATCHING
PART 1 - GENERAL

1.1 SUMMARY
A. This Section includes procedural requirements for cutting and patching.

B. See Divisions 2 through 48 Sections for specific requirements and limitations applicable to cutting and patching individual parts of the Work.

1.2 SUBMITTALS
A. Cutting and Patching Proposal: Submit a proposal describing procedures at least 10 days before the time cutting and patching will be performed, requesting approval to proceed.

Include the following information:

1. Extent: Describe cutting and patching, show how they will be performed, and indicate why they cannot be avoided.

2. Changes to In-Place Construction: Describe anticipated results. Include changes to structural elements and operating components as well as changes in building's appearance and other significant visual elements.

3. Products: List products to be used and firms or entities that will perform the Work.

4. Dates: Indicate when cutting and patching will be performed.

5. Utility Services and Mechanical/Electrical Systems: List services/systems that cutting and patching procedures will disturb or affect. List services/systems that will be relocated and those that will be temporarily out of service. Indicate how long services/systems will be disrupted.

6. Structural Elements: Where cutting and patching involve adding reinforcement to structural elements, submit details and engineering calculations showing integration of reinforcement with original structure.

7. Architect's Approval: Obtain approval of cutting and patching proposal before cutting and patching. Approval does not waive right to later require removal and replacement of unsatisfactory work.

1.3 QUALITY ASSURANCE
A. Structural Elements: Do not cut and patch structural elements in a manner that could change their load-carrying capacity or load-deflection ratio.

B. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as intended or that result in increased maintenance or decreased operational life or safety.

C. Miscellaneous Elements: Do not cut and patch miscellaneous elements or related components in a manner that could change their load-carrying capacity, and result in

Page 389 of 1257 ends

CUTTING AND PATCHING 01 73 29 – 2 of 4
SECTION 01 73 29 CUTTING AND PATCHING
reducing their capacity to perform as intended, or that result in increased maintenance or decreased operational life or safety.

D. Visual Requirements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch construction exposed on the exterior or in occupied spaces in a manner that would, in Architect's opinion, reduce the building's aesthetic qualities. Remove and replace construction that has been cut and patched in a visually unsatisfactory manner.

PART 2 - PRODUCTS

2.1 MATERIALS
A. General: Comply with requirements specified in other Sections.

B. In-Place Materials: Use materials identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible.

1. If identical materials are unavailable or cannot be used, use materials that, when installed, will match the visual and functional performance of in-place materials.

PART 3 - EXECUTION

3.1 EXAMINATION
A. Examine surfaces to be cut and patched and conditions under which cutting and patching are to be performed.

1. Compatibility: Before patching, verify compatibility with and suitability of substrates, including compatibility with in-place finishes or primers.

2. Proceed with installation only after unsafe or unsatisfactory conditions have been corrected.

3.2 PREPARATION
A. Temporary Support: Provide temporary support of Work to be cut.

B. Protection: Protect in-place construction during cutting and patching to prevent damage.

Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.

C. Adjoining Areas: Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.

D. Existing Utility Services and Mechanical/Electrical Systems: Where existing services/systems are required to be removed relocated, or abandoned, bypass such services/systems before cutting to minimize interruption to occupied areas.

Page 390 of 1257 ends

CUTTING AND PATCHING 01 73 29 – 3 of 4
SECTION 01 73 29 CUTTING AND PATCHING

3.3 PERFORMANCE
A. General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay.

1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.

B. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations.

1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots as small as possible, neatly to size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.

2. Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces.

3. Concrete and Masonry: Cut using a cutting machine, such as an abrasive saw or a diamond-core drill.

4. Excavating and Backfilling: Comply with requirements in applicable Division 31 Sections where required by cutting and patching operations.

5. Mechanical and Electrical Services: Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after cutting.

6. Proceed with patching after construction operations requiring cutting are complete.

C. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other Work. Patch with durable seams that are as invisible as possible. Provide materials and comply with installation requirements specified in other Sections.

1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate integrity of installation.

2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.

3. Floors and Walls: Where walls or partitions that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish, color, texture, and appearance. Remove in-place floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.

4. Ceilings: Patch, repair, or re-hang in-place ceilings as necessary to provide an evenplane surface of uniform appearance.

5. Exterior Building Enclosure: Patch components in a manner that restores enclosure to a weathertight condition.