SECTION 28 13 00 PHYSICAL ACCESS CONTROL SYSTEM
PHYSICAL ACCESS CONTROL SYSTEM 28 13 00 - 7 of 10
b. Contacts that will make 720 VA at 60A and that will break at 720 VA at 10A.
2. Enclosures: Flush or surface mounting. Push buttons shall be suitable for flush mounting in the switch enclosures.
3. Enclosures shall additionally be suitable for installation in the following locations:
a. Indoors, controlled environment.
b. Indoors, uncontrolled environment.
c. Outdoors.
4. Power: Push-button switches shall be powered from their associated Controller, using dc control.
2.05 INTERFACES
A. Power Supplies:
1. Shall be UL rated and able to adequately power new and existing entry control devices on a continuous basis without failure.
2. Shall meet the following minimum technical characteristics:
INPUT POWER 110 VAC 60 HZ
OUTPUT VOLTAGE 12 VDC Nominal (13.8 VDC)
24 VDC Nominal (27.6 VDC)
Filtered and Regulated
BATTERY Dependent on Output Voltage shall provide up
to 24 hours of unpowered operation
CHARGING CIRCUIT Built-in standard
2.06 WIRES AND CABLES
A. Provide device input cables as required by manufacturer.
PART 3 EXECUTION
3.01 GENERAL
SECTION 28 13 00 PHYSICAL ACCESS CONTROL SYSTEM
PHYSICAL ACCESS CONTROL SYSTEM 28 13 00 - 8 of 10
A. The Contractor shall install all system components and appurtenances in accordance with the manufacturers’ instructions, ANSI C2, and shall furnish all necessary interconnections, services, and adjustments required for a complete and operable system as specified. Control signals, communications, and data transmission lines grounding shall be installed as necessary to preclude ground loops, noise, and surges from affecting system operation. Equipment, materials, installation, workmanship, inspection, and testing shall be in accordance with manufacturers’ recommendations and as modified herein.
B. Consult the manufacturers’ installation manuals for all wiring diagrams, schematics, physical equipment sizes, etc., before beginning system installation. Refer to the Riser/Connection diagram for all schematic system installation/termination/wiring data.
C. All equipment shall be attached to walls and ceiling/floor assemblies and shall be held firmly in place (e.g., sensors shall not be supported solely by suspended ceilings).
Fasteners and supports shall be adequate to support the required load.
3.02 EXAMINATION
A. Examine pathway elements intended for cables. Check raceways, cable trays, and other elements for compliance with space allocations, installation tolerances, hazards to cable installation, and other conditions affecting installation.
B. Examine roughing-in for control cable conduit systems, Controllers, card readers, and other cable-connected devices to verify actual locations of conduit and back boxes before device installation.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.03 CABLING
A. Comply with NECA 1, "Good Workmanship in Electrical Contracting." B. Install cables without damaging conductors, shield, or jacket.
C. Boxes and enclosures containing security system components or cabling, and which are easily accessible to employees or to the public, shall be provided with a lock. Boxes above ceiling level in occupied areas of the building shall not be considered to be accessible. Junction boxes and small device enclosures below ceiling level and easily accessible to employees or the public shall be covered with a suitable cover plate and secured with tamperproof screws.
3.04 CABLE APPLICATION
A. Comply with EIA/TIA-569, "Commercial Building Standard for Telecommunications Pathways and Spaces."
B. Cable application requirements are minimum requirements and shall be exceeded if recommended or required by manufacturer of system hardware.
C. RS-232 Cabling: Install at a maximum distance of 50 feet.
D. RS-485 Cabling: Install at a maximum distance of 4000 feet.
E. Card Readers and Keypads:
SECTION 28 13 00 PHYSICAL ACCESS CONTROL SYSTEM
PHYSICAL ACCESS CONTROL SYSTEM 28 13 00 - 9 of 10
1. Install number of conductor pairs recommended by manufacturer for the functions specified.
2. Unless manufacturer recommends larger conductors, install No. 22 AWG wire if maximum distance from Controller to the reader is 250 feet, and install No. 20 AWG wire if maximum distance is 500 feet.
3. For greater distances, install "extender" or "repeater" modules recommended by manufacturer of the Controller.
4. Install minimum No. 18 AWG shielded cable to readers and keypads that draw 50 mA or more.
F. Install minimum No. 16 AWG cable from Controller to electrically powered locks. Do not exceed 500 feet of cable.
G. Install minimum No. 18 AWG ac power wire from transformer to Controller, with a maximum distance of 25 feet of cable.
3.05 INSTALLATION
A. System installation shall be in accordance with UL 294, manufacturer and related documents and references, for each type of security device installed.
B. Control Panels:
1. Connect power and signal lines to the controller.
2. Program the panel as outlined by the design and per the manufacturer’s programming guidelines.
C. Card Readers:
1. Connect all signal inputs and outputs as shown and specified.
2. Terminate input signals as required.
3. Program and address the reader as per the design package.
4. Readers shall be surface or flushed mounted and all appropriate hardware shall be provided to ensure the unit is installed in an enclosed conduit system.
3.06 FIELD QUALITY CONTROL
A. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust field-assembled components and equipment installation, including connections, and to assist in field testing. Report results in writing.
B. Perform the following field tests and inspections and prepare test reports:
1. Test each circuit and component of each system. Tests shall include, but are not limited to, measurements of power supply output under maximum load, signal loop resistance, and leakage to ground where applicable.
2. Operational Test: After installation of cables and connectors, demonstrate product capability and compliance with requirements. Test each signal path for
SECTION 28 13 00 PHYSICAL ACCESS CONTROL SYSTEM
PHYSICAL ACCESS CONTROL SYSTEM 28 13 00 - 10 of 10
end-to-end performance from each end of all pairs installed. Remove temporary connections when tests have been satisfactorily completed.
END OF SECTION
SECTION 31 23 00 EXCAVATING BACKFILLING AND COMPACTING
EXCAVATING BACKFILLING AND COMPACTING 31 23 00 - 1 of 3 PART 1 GENERAL
1.01 SUMMARY
A. Excavating for footings, slabs-on-grade, trenches, pits, curbs, and paving; backfill and compaction of sub-grade, base and trenches.
B. Excavated materials shall be removed from site and costs for transportation and removal included in Bid.
1.02 RELATED WORK
A. All Related Documents and Sections: Contractor to examine Contract Documents for requirements that directly affect or are affected by Work of this Section. Those Documents and Sections include, but is not limited to, the following:
1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 General Requirements, apply to this Section.
2. All Specification Sections listed in the Table of Contents.
1.03 SUBMITTALS
A. Submit in accordance with Division 01, Submittals, Shop Drawings Product Data and Samples.
B. Submit list and source of materials to be used in the Work.
1.04 QUALITY ASSURANCE
A. Verify that survey benchmark and intended elevations for the Work are as indicated.
B. Comply with State of California Construction Safety Orders (CAL/OSHA)
1.05 UTILITY DISCONNECTS
A. Coordinate directly with County for any utility disconnects.
B. Notify Owner 72 hours prior to any excavation.
PART 2 PRODUCTS
2.01 MATERIALS
A. General: Fill material will be subject to approval of the Geotechnical Engineer.
B. Backfill and Fill Materials: Satisfactory soil materials free of clay, rock or gravel larger than 2 inches in any dimension, debris, waste, vegetation, and other unsuitable materials.
Local and import fill should have less than 15% fines and a plasticity index (PI) of less than 20.
SECTION 31 23 00 EXCAVATING BACKFILLING AND COMPACTING
EXCAVATING BACKFILLING AND COMPACTING 31 23 00 - 2 of 3 C. Aggregate Base: Class 2 conforming to Caltrans Specification Section 26, maximum size 3/4 inches; compact to minimum of 95 percent.
PART 3 EXECUTION
3.01 EXAMINATION
A. Identify required lines, levels, contours, and datum locations.
B. Locate, identify, and protect utilities that remain from damage.
C. Notify utility company to remove and relocate utilities if required.
D. Protect plant life, lawns, and other features remaining as a portion of final landscaping.
E. Protect bench marks, survey control points, existing structures, fences, sidewalks, paving, and curbs from excavating equipment and vehicular traffic.
3.02 EXCAVATION AND COMPACTING
A. Saw cut all cuts into asphalt and/or concrete surfaces.
B. Excavate subsoil to accommodate building foundations, paving and site structures, construction operations, and as indicated on Drawings and/or in attached Project Geotechnical Report.
C. Cover soils stockpiles. Stockpiles shall be covered daily and covers maintained as well as perimeter erosion control.
D. Compact disturbed load-bearing soil in direct contact with foundations to original bearing capacity; perform compaction as directed by Geotechnical Engineer.
E. Support trench excavations in compliance with local codes and safety regulations.
F. Sheet Pile or shore all excavations as required.
G. Do not interfere with 45 degree bearing splay under foundations except at pile foundations or where shoring is designed to resist earth and foundation pressures without permitting any settlements of foundations, slabs, or similar structures.
H. Grade top perimeter of excavation to prevent surface water from draining into excavation.
I. Hand trim excavation. Remove loose matter.
J. Remove lumped subsoil, boulders, and rock larger than 2 inches in diameter.
K. Correct areas over-excavated as directed by Geotechnical Engineer.
L. Do not backfill trenches until tests and inspections have been made.
M. Compact to minimum of 95 percent dry density (ASTM 1557) in planted areas and a minimum of 95 percent dry density (ASTM 1557) in paved areas.
SECTION 31 23 00 EXCAVATING BACKFILLING AND COMPACTING
EXCAVATING BACKFILLING AND COMPACTING 31 23 00 - 3 of 3 N. Footing bottoms should be free of loose debris and should be firm and unyielding as approved by the project Geotechnical Engineer prior to placement of steel and concrete.
END OF SECTION
THIS PAGE INTENTIONALLY LEFT BLANK Page 982 of 1257
SECTION 31 25 00 EROSION AND SEDIMENTATION CONTROL
EROSION AND SEDIMENTATION CONTROL 31 25 00 - 1 of 2
PART 1 GENERAL
1.01 SUMMARY
A. This Section describes the requirements for providing and installing temporary erosion control structures.
1.02 RELATED SECTIONS
A. All Related Documents and Sections: Contractor to examine Contract Documents for requirements that directly affect or are affected by Work of this Section. Those Documents and Sections include, but is not limited to, the following:
1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 General Requirements, apply to this Section.
2. All Specification Sections listed in the Table of Contents.
1.03 QUALITY ASSURANCE
A. Reference Standards
1. California Stormwater Quality Association (CASQA) “Stormwater Best Management Practice Handbook for Construction”.
2. State Water Resources Control Board (SWRCB) standards
3. California Stormwater Quality Association “Stormwater Best Management Practice Handbook” for Construction and Industrial and Commercial Development, latest edition.
4. County of Mendocino, California “Small Construction Site Stormwater Erosion and Sediment Control Plan Template”, latest edition.
1.04 SUBMITTALS
A. Submit in accordance with Division 01, Submittals, Shop Drawings Product Data and Samples.
B. Data, Reports and Certifications:
1. Materials used.
2. Erosion Control Point of Contract
PART 2 PRODUCTS
2.01 MATERIALS
A. Furnish and install the following as specified herein and required to eliminate potential erosion and sedimentation during construction works.
SECTION 31 25 00 EROSION AND SEDIMENTATION CONTROL
EROSION AND SEDIMENTATION CONTROL 31 25 00 - 2 of 2
1. Outlet structure, basins, ditches
2. Filter fabric, and/or mesh
3. Concrete washout
4. Fiber rolls
5. Inlet protection
6. Stabilized construction entrance
7. Straw waddles
PART 3 EXECUTION
3.01 PROCEDURES.
A. Erosion and sedimentation control measures are to be installed in areas as indicated and as directed by governing regulations.
B. Erosion and sedimentation control measures shall be adjusted, relocated or new controls established for each phase of construction and for specific construction activities that may disturb soils and contribute to erosion.
END OF SECTION
SECTION 32 05 23 CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS 32 05 23 - 1 of 11 PART 1 GENERAL
1.01 DESCRIPTION
A. This section shall cover site work concrete constructed upon the prepared subgrade and in conformance with the lines, grades, thickness, and cross sections shown. Construction shall include the following:
1. Curb, gutter, and combination curb and gutter.
2. Pedestrian Pavement: Walks and curb ramps.
3. Transformer and Emergency Generator slabs, walls, and footings.
4. Exterior retaining walls.
5. Exterior stairs and landings.
6. Light, sign and bollard foundations.
7. Site furnishings foundations.
8. Fencing and gate foundations.
9. Vehicle charging equipment foundations.
10. Accessible Parking Stalls
11. Miscellaneous exterior formed and unformed concrete.
1.02 RELATED WORK
A. All Related Documents and Sections: Contractor to examine Contract Documents for requirements that directly affect or are affected by Work of this Section. Those Documents and Sections include, but is not limited to, the following:
1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 General Requirements, apply to this Section.
2. All Specification Sections listed in the Table of Contents.
1.03 DESIGN REQUIREMENTS
A. Design all elements with the latest published version of applicable codes.
1.04 WEATHER LIMITATIONS
A. Placement of concrete shall be in conformance with ACI as specified under Section 03 30 00, CAST-IN-PLACE CONCRETE.
SECTION 32 05 23 CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS 32 05 23 - 2 of 11
1.05 SELECT SUBBASE MATERIAL JOB-MIX
A. The Contractor shall retain and reimburse a testing laboratory to design a select subbase material mixture and submit a job-mix formula to the Owner’s Representative, in writing, for approval. The formula shall include the source of materials, gradation, plasticity index, liquid limit, and laboratory compaction curves indicating maximum density at optimum moisture.
1.06 SUBMITTALS
A. Submit in accordance with Division 01, Submittals, Shop Drawings Product Data and Samples.
B. Manufacturers' Certificates and Data certifying that the following materials conform to the requirements specified.
1. Expansion joint filler
2. Hot poured sealing compound
3. Reinforcement
4. Curing materials
C. Data and Test Reports: Select subbase material.
1. Job-mix formula.
2. Source, gradation, liquid limit, plasticity index, percentage of wear, and other tests as specified and in referenced publications.
1.07 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this specification to the extent referenced.
The publications are referenced in the text by the basic designation only. Refer to the latest edition of all referenced Standards and codes.
B. American Association of State Highway and Transportation Officials (AASHTO):
M031MM031-07-UL ...... Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement (ASTM A615/A615M-09)
M055MM055-09-UL ...... Steel Welded Wire Reinforcement, Plain, for Concrete (ASTM A185)
M147-65-UL .................. Materials for Aggregate and Soil-Aggregate Subbase, Base and Surface Courses (R 2004)
M148-05-UL .................. Liquid Membrane-Forming Compounds for Curing Concrete (ASTM C309)
M171-05-UL .................. Sheet Materials for Curing Concrete (ASTM C171) M182-05-UL .................. Burlap Cloth Made from Jute or Kenaf and Cotton Mats
SECTION 32 05 23 CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS 32 05 23 - 3 of 11 M213-01-UL .................. Preformed Expansion Joint Fillers for Concrete Paving and Structural Construction (Non-extruding and Resilient Bituminous Type) (ASTM D1751)
M233-86-UL .................. Boiled Linseed Oil Mixer for Treatment of Portland Cement Concrete
T099-09-UL ................... Moisture-Density Relations of Soils Using a 2.5 kg. (5.5 lb) Rammer and a 305 mm (12 in.) Drop
T180-09-UL ................... Moisture-Density Relations of Soils Using a 4.54 kg (10 lb.) Rammer and a 457 mm (18 in.) Drop
C. American Society for Testing and Materials (ASTM):
C94/C94M-09 ................ Ready-Mixed Concrete
C143/C143M-09 ............ Slump of Hydraulic Cement Concrete PART 2 PRODUCTS
2.01 GENERAL
A. Concrete shall be Type C, air-entrained as specified in Section 03 30 00, CAST-INPLACE CONCRETE, with the following exceptions:
TYPE MAXIMUM SLUMP*
Curb & Gutter 75 mm (3")
Pedestrian Pavement 75 mm (3")
* For concrete to be vibrated: Slump as determined by ASTM C143.
Tolerances as established by ASTM C94.
2.02 REINFORCEMENT
A. The type, amount, and locations of steel reinforcement shall be as shown on the drawings and in the specifications.
B. Welded wire-fabric shall conform to AASHTO M55.
C. Dowels shall be plain steel bars conforming to AASHTO M31. Tie bars shall be deformed steel bars conforming to AASHTO M31.
2.03 SELECT SUBBASE (WHERE REQUIRED)
A. Subbase material shall conform to Section 31 23 00 “Excavating Backfilling and Compacting” and as shown on the Drawings.
B. Subbase material shall produce a compacted, dense-graded course, meeting the density requirement specified in these specifications and drawings.
SECTION 32 05 23 CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS 32 05 23 - 4 of 11
2.04 FORMS
A. Use metal or wood forms that are straight and suitable in cross-section, depth, and strength to resist springing during depositing and consolidating the concrete, for the work involved.
B. Do not use forms if they vary from a straight line more than 3 mm (1/8 inch) in any 3000 mm (ten foot) long section, in either a horizontal or vertical direction.
C. Wood forms should be at least 50 mm (2 inches) thick (nominal). Wood forms shall also be free from warp, twist, loose knots, splits, or other defects. Use approved flexible or curved forms for forming radii.
2.05 CONCRETE CURING MATERIALS
A. Concrete curing materials shall conform to one of the following:
1. Burlap conforming to AASHTO M182 having a weight of 233 grams (seven ounces) or more per square meter (yard) when dry.
2. Impervious Sheeting conforming to AASHTO M171.
3. Liquid Membrane Curing Compound conforming to AASHTO M148 (ASTM C309), and shall be free of paraffin or petroleum.
2.06 EXPANSION JOINT FILLERS
A. Material shall conform to AASHTO M213.
PART 3 EXECUTION
3.01 SUBGRADE PENETRATION
A. Prepare, construct, and finish the subgrade as specified in Section 31 23 00, Excavating Backfilling and Compacting.
B. Maintain the subgrade in a smooth, compacted condition, in conformance with the required section and established grade until the succeeding operation has been accomplished.
3.02 SELECT SUBBASE (WHERE REQUIRED)
A. Mixing: Proportion the select subbase by weight or by volume in quantities so that the final approved job-mixed formula gradation, liquid limit, and plasticity index requirements will be met after subbase course has been placed and compacted. Add water in approved quantities, measured by weight or volume, in such a manner to produce a uniform blend.
B. Placing:
1. Place the mixed material on the prepared subgrade in a uniform layer to the required contour and grades, and to a loose depth not to exceed 200 mm (8
SECTION 32 05 23 CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS 32 05 23 - 5 of 11 inches), and that when compacted, will produce a layer of the designated thickness.
2. When the designated compacted thickness exceeds 150 mm (6 inches), place the material in layers of equal thickness. Remove unsatisfactory areas and replace with satisfactory mixture, or mix the material in the area.
3. In no case will the addition of thin layers of material be added to the top layer in order to meet grade.
4. If the elevation of the top layer is 13 mm (1/2 inch) or more below the grade, excavate the top layer and replace with new material to a depth of at least 75 mm (3 inches) in compacted thickness.
C. Compaction:
1. Perform compaction with approved equipment (hand or mechanical) well suited to the material being compacted.
2. Moisten or aerate the material as necessary to provide the moisture content that will readily facilitate obtaining the specified compaction with the equipment used.
3. Compact each layer to at least 95 percent or 100 percent of maximum density as determined by AASHTO T180 or AASHTO T99 respectively.
D. Smoothness Test and Thickness Control:
Test the completed subbase for grade and cross section with a straight edge.
1. The surface of each layer shall not show any deviations in excess of 10 mm (3/8 inch).
2. The completed thickness shall be within 13 mm (1/2 inch) of the thickness as shown.
E. Protection:
1. Maintain the finished subbase in a smooth and compacted condition until the concrete has been placed.
2. When Contractor's subsequent operations or adverse weather disturbs the approved compacted subbase, excavate, and reconstruct it with new material meeting the requirements herein specified, at no additional cost to the Owner.
3.03 SETTING FORMS
A. Base Support:
1. Compact the base material under the forms true to grade so that, when set, they will be uniformly supported for their entire length at the grade as shown.
2. Correct imperfections or variations in the base material grade by cutting or filling and compacting.
B. Form Setting:
SECTION 32 05 23 CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS 32 05 23 - 6 of 11
1. Set forms sufficiently in advance of the placing of the concrete to permit the performance and approval of all operations required with and adjacent to the form lines.
2. Set forms to true line and grade and use stakes, clamps, spreaders, and braces to hold them rigidly in place so that the forms and joints are free from play or movement in any direction.
3. Forms shall conform to line and grade with an allowable tolerance of 3 mm (1/8 inch) when checked with a straightedge and shall not deviate from true line by more than 6 mm (1/4 inch) at any point.
4. Do not remove forms until removal will not result in damaged concrete or at such time to facilitate finishing.
5. Clean and oil forms each time they are used.
C. The Contractor’s Registered Professional Land Surveyor shall establish and control the alignment and the grade elevations of the forms or concrete slipforming machine operations.
1. Make necessary corrections to forms immediately before placing concrete.
2. When any form has been disturbed or any subgrade or subbase has become unstable, reset and recheck the form before placing concrete.
3.04 EQUIPMENT
A. The Owner’s Representative shall approve equipment and tools necessary for handling materials and performing all parts of the work prior to commencement of work.
B. Maintain equipment and tools in satisfactory working condition at all times.
3.05 PLACING REINFORCEMENT
A. Reinforcement shall be free from dirt, oil, rust, scale or other substances that prevent the bonding of the concrete to the reinforcement.
B. Before the concrete is placed, the Owner’s Representative shall approve the reinforcement, which shall be accurately and securely fastened in place with suitable supports and ties. The type, amount, and position of the reinforcement shall be as shown.
3.06 PLACING CONCRETE - GENERAL
A. Obtain approval of the Owner’s Representative before placing concrete.
B. Remove debris and other foreign material from between the forms before placing concrete. Obtain approval of the Owner’s Representative before placing concrete.
C. Before the concrete is placed, uniformly moisten the subgrade, base, or subbase appropriately, avoiding puddles of water.
D. Convey concrete from mixer to final place of deposit by a method which will prevent segregation or loss of ingredients. Deposit concrete so that it requires as little handling as possible.
SECTION 32 05 23 CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS 32 05 23 - 7 of 11 E. While being placed, spade or vibrate and compact the concrete with suitable tools to prevent the formation of voids or honeycomb pockets. Vibrate concrete well against forms and along joints. Over-vibration or manipulation causing segregation will not be permitted. Place concrete continuously between joints without bulkheads.
F. Install a construction joint whenever the placing of concrete is suspended for more than 30 minutes and at the end of each day's work.
G. Workmen or construction equipment coated with foreign material shall not be permitted to walk or operate in the concrete during placement and finishing operations.
3.07 PLACING CONCRETE FOR CURB AND GUTTER, PEDESTRIAN PAVEMENT, AND
EQUIPMENT PADS
A. Place concrete in the forms in one layer of such thickness that, when compacted and finished, it will conform to the cross section as shown.
B. Deposit concrete as near to joints as possible without disturbing them but do not dump onto a joint assembly.
C. After the concrete has been placed in the forms, use a strike-off guided by the side forms to bring the surface to the proper section to be compacted.
D. Consolidate the concrete thoroughly by tamping and spading, or with approved mechanical finishing equipment.
E. Finish the surface to grade with a wood or metal float.
F. All Concrete pads and pavements shall be constructed with sufficient slope to drain properly.
3.08 PLACING CONCRETE FOR VEHICULAR PAVEMENT
A. Deposit concrete into the forms as close as possible to its final position.
B. Place concrete rapidly and continuously between construction joints.
C. Strike off concrete and thoroughly consolidate by a finishing machine, vibrating screed, or by hand-finishing.
D. Finish the surface to the elevation and crown as shown.
E. Deposit concrete as near the joints as possible without disturbing them but do not dump onto a joint assembly. Do not place adjacent lanes without approval by the Owner’s Representative.
3.09 CONCRETE FINISHING - GENERAL
A. The sequence of operations, unless otherwise indicated, shall be as follows:
1. Consolidating, floating, straight-edging, troweling, texturing, and edging of joints.
2. Maintain finishing equipment and tools in a clean and approved condition.
SECTION 32 05 23 CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS 32 05 23 - 8 of 11
3.10 CONCRETE FINISHING CURB AND GUTTER
A. Round the edges of the gutter and top of the curb with an edging tool to a radius of 1/4 inch or as otherwise detailed.
B. Float the surfaces and finish with a smooth wood or metal float until true to grade and section and uniform in textures.
C. Finish the surfaces, while still wet, with a bristle type brush with longitudinal strokes.
D. Immediately after removing the front curb form, rub the face of the curb with a wood or concrete rubbing block and water until blemishes, form marks, and tool marks have been removed. Brush the surface, while still wet, in the same manner as the gutter and curb top.
E. Except at grade changes or curves, finished surfaces shall not vary more than 1/8 inch for gutter and 1/4 inch for top and face of curb, when tested with a 10 foot straightedge.
F. Remove and reconstruct irregularities exceeding the above for the full length between regularly scheduled joints.
G. Correct any depressions which will not drain.
H. Visible surfaces and edges of finished curb, gutter, and combination curb and gutter shall be free of blemishes, form marks, and tool marks, and shall be uniform in color, shape, and appearance.
3.11 CONCRETE FINISHING PEDESTRIAN PAVEMENT
A. Walks, Wheelchair Curb Ramps:
1. Finish the surfaces to grade and cross section with a metal float, trowled smooth and finished with a broom moistened with clear water.
2. Medium brooming shall be transverse to the line of traffic.
3. Finish all slab edges, including those at formed joints, carefully with an edger having a radius as shown on the Drawings.
4. Unless otherwise indicated, edge the transverse joints before brooming. The brooming shall eliminate the flat surface left by the surface face of the edger.
Execute the brooming so that the corrugation, thus produced, will be uniform in appearance and not more than 1/16 inch in depth.
5. The completed surface shall be uniform in color and free of surface blemishes, form marks, and tool marks. The finished surface of the pavement shall not vary more than 3/16 inch when tested with a 10 foot straightedge.
6. The thickness of the pavement shall not vary more than 1/4 inch.
7. Remove and reconstruct irregularities exceeding the above for the full length between regularly scheduled joints.
SECTION 32 05 23 CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS 32 05 23 - 9 of 11
3.12 JOINTS - GENERAL
A. Place joints, where shown, conforming to the details as shown, and perpendicular to the finished grade of the concrete surface.
B. Joints shall be straight and continuous from edge to edge of the pavement.
3.13 EXPANSION JOINTS
A. Use a preformed expansion joint filler material of the thickness as shown to form expansion joints.
B. Material shall extend the full depth of concrete, cut and shaped to the cross section as shown, except that top edges of joint filler shall be below the finished concrete surface where shown to allow for sealing.
C. Anchor with approved devices to prevent displacing during placing and finishing operations.
D. Round the edges of joints with an edging tool.
E. Form expansion joints as follows:
1. Without dowels, about structures and features that project through, into, or against any site work concrete construction.
2. Using joint filler of the type, thickness, and width as shown.
3. Installed in such a manner as to form a complete, uniform separation between the structure and the site work concrete item.
3.14 CONSTRUCTION JOINTS
A. Locate longitudinal and transverse construction joints between slabs as shown.
B. Place transverse construction joints of the type shown, where indicated and whenever the placing of concrete is suspended for more than 30 minutes.
C. Use a butt-type joint with dowels in curb and gutter if the joint occurs at the location of a planned joint.
D. Use keyed joints with tiebars if the joint occurs in the middle third of the normal curb and gutter joint interval.
3.15 FORM REMOVAL
A. Forms shall remain in place at least 12 hours after the concrete has been placed.
Remove forms without injuring the concrete.
B. Do not use bars or heavy tools against the concrete in removing the forms. Promptly repair any concrete found defective after form removal.
SECTION 32 05 23 CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS 32 05 23 - 10 of 11
3.16 CURING OF CONCRETE
A. Cure concrete by one of the following methods appropriate to the weather conditions and local construction practices, against loss of moisture, and rapid temperature changes for at least seven days from the beginning of the curing operation. Protect unhardened concrete from rain and flowing water. All equipment needed for adequate curing and protection of the concrete shall be on hand and ready to install before actual concrete placement begins. Provide protection as necessary to prevent cracking of the pavement due to temperature changes during the curing period. If any selected method of curing does not afford the proper curing and protection against concrete cracking, remove and replace the damaged pavement and employ another method of curing as directed by the Owner’s Representative.
B. Burlap Mat: Provide a minimum of two layers kept saturated with water for the curing period. Mats shall overlap each other at least 150 mm (6 inches).
C. Impervious Sheeting: Use waterproof paper, polyethylene-coated burlap, or polyethylene sheeting. Polyethylene shall be at lease 0.1 mm (4 mils) in thickness. Wet the entire exposed concrete surface with a fine spray of water and then cover with the sheeting material. Sheets shall overlap each other at least 300 mm (12 inches). Securely anchor sheeting.
D. Liquid Membrane Curing:
1. Apply pigmented membrane-forming curing compound in two coats at right angles to each other at a rate of 5 m2/L (200 square feet per gallon) for both coats.
2. Do not allow the concrete to dry before the application of the membrane.
3. Cure joints designated to be sealed by inserting moistened paper or fiber rope or covering with waterproof paper prior to application of the curing compound, in a manner to prevent the curing compound entering the joint.
4. Immediately re-spray any area covered with curing compound and damaged during the curing period.
3.17 CLEANING
A. After completion of the curing period:
1. Remove the curing material (other than liquid membrane).
2. Sweep the concrete clean.
3. After removal of all foreign matter from the joints, seal joints as herein specified.
4. Clean the entire concrete of all debris and construction equipment as soon as curing and sealing of joints has been completed.
3.18 PROTECTION
A. The contractor shall protect the concrete against all damage prior to final acceptance by the Owner. Remove concrete containing excessive cracking, fractures, spalling, or other defects and reconstruct the entire section between regularly scheduled joints, when
SECTION 32 05 23 CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS 32 05 23 - 11 of 11 directed by the Owner’s Representative, and at no additional cost to the Owner. Exclude traffic from vehicular pavement until the concrete is at least seven days old, or for a longer period of time if so directed by the Owner’s Representative.
3.19 FINAL CLEAN-UP
A. Remove all debris, rubbish and excess material from the site.
END OF SECTION
THIS PAGE INTENTIONALLY LEFT BLANK Page 996 of 1257
SECTION 32 12 16 ASPHALT PAVING
ASPHALT PAVING 32 12 16 - 1 of 5
PART 1 GENERAL
1.01 DESCRIPTION
A. This work shall cover the composition, mixing, construction upon the prepared subgrade, and the protection of hot asphalt concrete pavement. The hot asphalt concrete pavement shall consist of an aggregate or asphalt base course and asphalt surface course constructed in conformity with the lines, grades, thickness, and cross sections as shown.
Each course shall be constructed to the depth, section, or elevation required by the drawings and shall be rolled, finished, and approved before the placement of the next course.
B. This Section includes specifications for constructing new asphalt concrete wearing surface Type A, 1/2-inch maximum with medium grading.
1.02 RELATED WORK
A. All Related Documents and Sections: Contractor to examine Contract Documents for requirements that directly affect or are affected by Work of this Section. Those Documents and Sections include, but is not limited to, the following:
1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 General Requirements, apply to this Section.
2. All Specification Sections listed in the Table of Contents.
1.03 ALIGNMENT AND GRADE CONTROL
A. The Contractor’s Registered Professional Land Surveyor shall establish and control the pavement (aggregate or asphalt base course and asphalt surface course) alignments, grades, elevations, and cross sections as shown on the Drawings.
1.04 SUBMITTALS
A. Submit in accordance with Division 01, Submittals, Shop Drawings Product Data and Samples.
B. Data and Test Reports:
1. Aggregate Base Course: Sources, gradation, liquid limit, plasticity index, percentage of wear, and other tests required by Section 39 of Caltrans Standard Specifications (CTSS).
2. Asphalt Base/Surface Course: Aggregate source, gradation, soundness loss, percentage of wear, and other tests required by Section 39 of CTSS.
3. Job-mix formula.
C. Certifications:
1. Asphalt prime and tack coat material certificate of conformance to Section 39 of CTSS requirements.
SECTION 32 12 16 ASPHALT PAVING
ASPHALT PAVING 32 12 16 - 2 of 5
2. Asphalt cement certificate of conformance to CTSS requirements.
3. Job-mix certification - Submit plant mix certification that mix equals or exceeds Section 39 of CTSS.
4. Prior to starting construction, the Contractor shall submit the asphalt concrete mix design including the amount of asphalt binder to be mixed with the dry aggregate to the Engineer for approval. No resurfacing work will be allowed prior to the approval of the mix design. Asphalt concrete mix design shall conform to Section 39 of CTSS.
5. The Contractor shall submit electronic copies of manufacturer’s literature, specifications, applications and installations for filler and/or sealer material to the Owner’s Representative for approval at least five (5) calendar days in advance of performing the filling and/or sealing work.
1.05 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this specification to the extent referenced.
The publications are referenced in the text by the basic designation only. Refer to the latest edition of all referenced Standards and codes.
B. State of California Department of Transportation (CalTrans):
1. Standard Specifications (CTSS)
PART 2 PRODUCTS
2.01 GENERAL
A. Aggregate base, Asphaltic base and asphalt concrete materials shall conform to the requirements of the following and other appropriate sections of the latest version of Section 39 of CTSS, including amendments, addenda and errata. Where the term "Engineer" is referenced in Section 39 of CTSS, it shall mean the Owner’s Representative.
2.02 MATERIALS
A. Asphalt: In accordance with the requirements of Section 39-2.01 of CTSS, except that asphalt shall be either PG 64-10 or AR-4000.
B. Aggregate: In accordance with the requirements of Section 39-2.02 of CTSS, except that aggregate grading shall be as follows:
Limits of
Proposed Operating Contract
Sieve Sizes Gradation Range Compliance
3/4" ---------- 100 100
1/2" ---------- 95-100 89-100
3/8" ---------- 80-95 75-100
No. 4 59-66 X+5 X+8
SECTION 32 12 16 ASPHALT PAVING
ASPHALT PAVING 32 12 16 - 3 of 5
No. 8 43-49 X+5 X+8
No. 30 22-27 X+5 X+8
No. 200 ---------- 3-8 0-11
C. Minimum Durability Index: When tested in accordance with Caltrans Test Method 229 shall be 50.
D. Tack coat in accordance with Section 39 of CTSS.
2.03 EQUIPMENT
A. Spreading Equipment: In accordance with the requirements of Section 39 of CTSS.
B. Compacting Equipment: In accordance with the requirements of Section 9 of CTSS.
PART 3 EXECUTION
3.01 GENERAL
A. The Asphalt Concrete Paving equipment, weather limitations, job-mix formula, mixing, construction methods, compaction, finishing, tolerance, and protection shall conform to the requirements of the appropriate sections of Section 39 of CTSS for the type of material specified.
3.02 MIXING ASPHALTIC CONCRETE MATERIALS
A. Provide hot plant-mixed asphaltic concrete paving materials.
1. Temperature leaving the plant: 143 degrees C (290 degrees F) minimum, 160 degrees C (320 degrees F) maximum.
2. Temperature at time of placing: 138 degrees C (280 degrees F) minimum.
3.03 SUBGRADE
A. Shape to line and grade and compact with self-propelled rollers.
B. All depressions that develop under rolling shall be filled with acceptable material and the area re-rolled.
C. Soft areas shall be removed and filled with acceptable materials and the area re-rolled.
D. Should the subgrade become rutted or displaced prior to the placing of the subbase, it shall be reworked to bring to line and grade.
E. Proof-roll the subgrade with maximum 50 ton gross weight dump truck as directed by Owner’s Representative. If pumping, pushing, or other movement is observed, rework the area to provide a stable and compacted subgrade.
SECTION 32 12 16 ASPHALT PAVING
ASPHALT PAVING 32 12 16 - 4 of 5
3.04 BASE COURSES
A. Base:
1. Spread and compact to the thickness shown on the drawings.
2. Rolling shall begin at the sides and continue toward the center and shall continue until there is no movement ahead of the roller.
3. After completion of the base rolling there shall be no hauling over the base other than the delivery of material for the top course.
C. Thickness tolerance: Provide the compacted thicknesses shown on the Drawings within a tolerance of minus 0.0mm (0.0") to plus 12.7mm (0.5").
D. Smoothness tolerance: Provide the lines and grades shown on the Drawings within a tolerance of 5mm in 3m (3/16 inch in ten feet).
E. Moisture content: Use only the amount of moisture needed to achieve the specified compaction.
3.05 PLACEMENT OF ASPHALTIC CONCRETE PAVING
A. Remove all loose materials from the compacted base.
B. Apply the specified prime coat, and tack coat where required, and allow to dry in accordance with the manufacturer’s recommendations as approved by the Owner.
C. Receipt of asphaltic concrete materials:
1. Do not accept material unless it is covered with a tarpaulin until unloaded, and unless the material has a temperature of not less than 130 degrees C (280 degrees F).
2. Do not commence placement of asphaltic concrete materials when the atmospheric temperature is below 10 degrees C (50 degrees F), not during fog, rain, or other unsuitable conditions.
D. Spreading:
1. Spread material in a manner that requires the least handling.
2. Where thickness of finished paving will be 76mm (3") or less, spread in one layer.
E. Rolling:
1. After the material has been spread to the proper depth, roll until the surface is hard, smooth, unyielding, and true to the thickness and elevations shown own the drawings.
2. Roll in at least two directions until no roller marks are visible.
3. Finished paving smoothness tolerance:
a. No depressions which will retain standing water.
SECTION 32 12 16 ASPHALT PAVING
ASPHALT PAVING 32 12 16 - 5 of 5
b. No deviation greater than 3mm in 1.8m (1/8" in six feet).
3.06 APPLICATION OF SEAL COAT
A. Prepare the surfaces, mix the seal coat material, and apply in accordance with the manufacturer’s recommendations as approved by the Owner.
B. Apply one coat of the specified sealer.
C. Achieve a finished surface seal which, when dry and thoroughly set, is smooth, tough, resilient, of uniform black color, and free from coarse textured areas, lap marks, ridges, and other surface irregularities.
3.07 PROTECTION
A. Protect the asphaltic concrete paved areas from traffic until the sealer is set and cured and does not pick up under foot or wheeled traffic.
3.08 FINAL CLEAN-UP
A. Remove all debris, rubbish, and excess material from the work area.
END OF SECTION
THIS PAGE INTENTIONALLY LEFT BLANK Page 1002 of 1257
SECTION 32 17 13 WHEEL STOPS
WHEEL STOPS 32 17 13- 1 of 2
PART 1 GENERAL
1.01 DESCRIPTION
A. Section includes specifications for precast concrete wheel stops for vehicular parking stalls in parking structures and parking lots as indicated.
1.02 RELATED WORK
A. All Related Documents and Sections: Contractor to examine Contract Documents for requirements that directly affect or are affected by Work of this Section. Those Documents and Sections include, but is not limited to, the following:
1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 General Requirements, apply to this Section.
2. All Specification Sections listed in the Table of Contents.
1.03 REFERENCE STANDARDS
A. State of California, Department of Transportation Caltrans, Standard Specifications (CTSS)
1.04 SUBMITTALS
A. Submit in accordance with Division 01, Submittals, Shop Drawings Product Data and Samples.
B. Product Data: Submit manufacturers' product data of precast stops and epoxy adhesive for approval.
1.05 QUALITY ASSURANCE:
A. Precast wheel stops shall be manufactured for the intended purpose by a company or firm specializing in the manufacture of precast concrete parking appurtenances.
PART 2 PRODUCTS
2.01 MATERIALS
A. Wheel Stops: Precast, 3.5% minimum air-entrained concrete; 4000 psi minimum compressive strength. Each stop shall be reinforced with two No. 4 deformed steel reinforcing bars, minimum. Provide chamfered corners and drainage slots on underside, and provide holes for dowel-anchoring to substrate. Unless indicated otherwise, provide stops of half octagonal configuration and 30-inch length.
B. Adhesive for Anchoring Stops to Concrete Slabs, At-Grade Concrete Pavements, and AtGrade Asphalt Pavements: Epoxy adhesive manufactured for the purpose, similar and equal to the adhesives specified in Caltrans Standard Specifications, Section 95-2.04 or 95-2.05.
SECTION 32 17 13 WHEEL STOPS
WHEEL STOPS 32 17 13- 2 of 2
C. Adhesive for Bonding Dowel to Wheel Stop: As proposed by Contractor and approved by the Engineer, suitable for application.
D. Steel Bars for Installation: Galvanized 5/8” diameter steel dowels or galvanized PART 3 EXECUTION
3.1 INSTALLATION
A. Securely attach wheel stops into at-grade concrete and at-grade asphalt pavement with not less than two galvanized steel dowels embedded in holes cast into wheel stops.
Firmly bond each dowel to wheel stop and to pavement.
B. At concrete pavement, drill holes in pavement for dowels.
END OF SECTION
SECTION 32 17 23 PAVEMENT MARKINGS
PAVEMENT MARKINGS 32 17 23 - 1 of 3
PART 1 GENERAL
1.01 DESCRIPTION
A. This work shall consist of furnishing and applying paint areas restricted to accessible stalls, crosswalks, energy stalls, and other detail pavement markings, in accordance with the details as shown or as prescribed by the Owner’s Representative. Conform to the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the U.S. Department of Transportation, Federal Highway Administration, CBC 2016, 11B and ADAAG 2010 for details not shown.
1.02 RELATED WORK
A. All Related Documents and Sections: Contractor to examine Contract Documents for requirements that directly affect or are affected by Work of this Section. Those Documents and Sections include, but is not limited to, the following:
1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 General Requirements, apply to this Section.
2. All Specification Sections listed in the Table of Contents.
1.03 SUBMITTALS
A. Submit in accordance with Division 01, Submittals, Shop Drawings Product Data and Samples
B. Furnish Manufacturer's Certificates and Data certifying that the following materials conform to the requirements specified:
1. Paint.
1.04 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this specification to the extent referenced.
The publications are referenced in the text by the basic designation only.
B. Federal Specifications (Fed. Spec.):
TT-B-1325C .................. Beads (Glass Spheres); Retro-Reflective TT-P-1952D .................. Paint, Traffic Black, and Airfield Marking, Waterborne C. Master Painters Institute (MPI):
Approved Product List – 2019
SECTION 32 17 23 PAVEMENT MARKINGS
PAVEMENT MARKINGS 32 17 23 - 2 of 3
PART 2 PRODUCTS
2.01 PAINT
A. Paint for marking pavement (parking lot and zone marking) shall conform to MPI No. 97, color as shown. Paint for obliterating existing markings shall conform to Fed. Spec.
TT-P-1952D. Paint shall be in containers of at least 5 gallons. A certificate shall accompany each batch of paint stating compliance with the applicable publication.
2.02 PAINT APPLICATOR
A. Apply all marking by approved mechanical equipment. The equipment shall provide constant agitation of paint and travel at controlled speeds. Synchronize one or more paint "guns" to automatically begin and cut off paint flow in the case of skip lines. The equipment shall have manual control to apply continuous lines of varying length and marking widths as shown. Provide pneumatic spray guns for hand application of paint in areas where a mobile paint applicator cannot be used. If the equipment does not have a glass bead dispenser, use a separate piece of equipment. An experienced technician that is thoroughly familiar with equipment, materials, and marking layouts shall control all painting equipment and operations.
PART 3 EXECUTION
3.01 SURFACE PREPARATION
A. Allow new pavement surfaces to cure for a period of not less than 14 days before application of marking materials.
B. Thoroughly clean all surfaces to be marked before application of paint. Remove dust, dirt, and other granular surface deposits by sweeping, blowing with compressed air, rinsing with water, or a combination of these methods. Completely remove rubber deposits, existing paint markings, and other coatings adhering to the pavement with scrapers, wire brushings, sandblasting, mechanical abrasion, or approved chemicals as directed by the Owner’s Representative. The application of paint conforming to Fed. Spec. TT-P-1952D is an option to removal of existing paint markings on asphalt pavement. Apply the black paint in as many coats as necessary to completely obliterate the existing markings.
Where oil or grease are present on old pavements to be marked, scrub affected areas with several applications of trisodium phosphate solution or other approved detergent or degreaser, and rinse thoroughly after each application. After cleaning, seal oil-soaked areas with cut shellac to prevent bleeding through the new paint. Pavement marking shall follow as closely as practicable after the surface has been cleaned and dried, but do not begin any marking until the Owner’s Representative has inspected the surface and gives permission to proceed. The Contractor shall establish control points for marking and provide templates to control paint application by type and color at necessary intervals.
The Contractor is responsible to preserve and apply marking in conformance with the established control points.
3.02 APPLICATION
A. Apply uniformly painted and reflective pavement marking of required color(s), length, and width with true, sharp edges and ends on properly cured, prepared, and dried surfaces in conformance with the details as shown and established control points. The length and width of lines shall conform within a tolerance of plus or minus 3 inches and plus or minus
SECTION 32 17 23 PAVEMENT MARKINGS
PAVEMENT MARKINGS 32 17 23 - 3 of 3
1/8 inch, respectively, in the case of skip markings. The length of intervals shall not exceed the line length tolerance. Temperature of the surface to be painted and the atmosphere shall be above 50 degrees F and less than 95 degrees F. Apply the paint at a wet film thickness of 0.015 inch. Disperse reflective glass beads evenly on the wet paint at a rate of 6 pounds per gallon of paint. Apply paint in one coat. At the direction of the Owner’s Representative, markings showing light spots may receive additional coats. The maximum drying time requirements of the paint specifications will be strictly enforced, to prevent undue softening of asphalt, and pick-up, displacement, or discoloration by tires of traffic. If there is a deficiency in drying of the marking, discontinue paint operations until cause of the slow drying is determined and corrected. Remove and replace marking that is applied at less than minimum material rates; deviates from true alignment; exceeds stipulated length and width tolerances; or shows light spots, faulty distribution of beads, smears, or other deficiencies or irregularities. Use carefully controlled sand blasting, approved grinding equipment, or other approved method to remove marking so that the surface to which the marking was applied will not be damaged.
3.03 PROTECTION
A. Conduct operations in such a manner that necessary traffic can move without hindrance.
Protect the newly painted markings so that, insofar as possible, the tires of passing vehicles will not pick up paint. Place warning signs at the beginning of the wet line, and at points well in advance of the marking equipment for alerting approaching traffic from both directions. Place small flags or other similarly effective small objects near freshly applied markings at frequent intervals to reduce crossing by traffic. Efface and replace damaged portions of markings at no additional cost to the Owner.
3.04 DETAIL PAVEMENT MARKING
A. Use Detail Pavement Markings, exclusive of actual traffic lane marking, at exit and entrance islands and turnouts, on curbs, at crosswalks, at parking bays, and at such other locations as shown. Show the International Accessibility Symbol at indicated parking spaces. Color shall be as shown. Apply paint for the symbol using a suitable template that will provide a pavement marking with true, sharp edges and ends. Place detail pavement markings of the color(s), width(s) and length(s), and design pattern at the locations shown.
3.05 FINAL CLEAN-UP
A. Remove all debris, rubbish and excess material from the site.
END OF SECTION
THIS PAGE INTENTIONALLY LEFT BLANK Page 1008 of 1257
SECTION 32 17 26 CAST-IN-PLACE DETECTABLE/TACTILE WARNING SURFACE CAST-IN-PLACE DETECTABLE/TACTILE WARNING SURFACE 32 17 26 - 1 of 6 PART 1 GENERAL
1.01 SUMMARY
A. This Section specifies furnishing and installing Cast In Place Detectable/Tactile Warning Surface Tiles where indicated. Not recommended for asphalt applications.
1.02 RELATED SECTIONS: Section(s) related to this section include:
A. Drawings All Sections listed in the Table of Contents are a Condition of this Section.
1.03 SUBMITTALS
A. Product Data: Submit manufacturer’s literature describing products, installation procedures and routine maintenance.
B. Samples for Verification Purposes: Submit two (2) tile samples minimum 12”x12” of the kind proposed for use.
C. Shop drawings are required for products specified showing fabrication details, composite structural system, tile surface profile, sound on cane contact amplification feature, plans of tile placement including joints, and material to be used as well as outlining installation materials and procedure.
D. Material Test Reports: Submit complete test reports from qualified accredited independent testing laboratories to qualify that materials proposed for use are in compliance with requirements and meet or exceed the properties indicated on the specifications. All tests shall be conducted on a Cast In Place Detectable/Tactile Warning Surface Tile system as certified by a qualified independent testing laboratory.
E. Maintenance Instructions: Submit copies of manufacturer’s specified installation and maintenance practices for each type of Detectable Warning Surface Tile and accessory as required.
1.04 QUALITY ASSURANCE
A. Provide Cast In Place Detectable/Tactile Warning Surface Tiles and accessories as produced by a single manufacturer with a minimum of five (5) years’ experience in the manufacturing of Cast In Place Detectable/Tactile Warning Surface Tiles.
B. Installer’s Qualifications: Engage an experienced Installer certified in writing by Cast In Place Detectable/Tactile Warning Surface Tile manufacturer as qualified for installation, who has successfully completed installations similar in material, design, and extent to that indicated for Project.
C. Americans with Disabilities Act (ADA): Provide Surface Applied Detectable/Tactile Warning Surface Tiles which comply with the detectable warnings on walking surfaces section of the Americans with Disabilities Act (Title III Regulations, 28 CFR Part 36 ADA STANDARDS FOR ACCESSIBLE DESIGN, Appendix A, Section 4.29.2 DETECTABLE WARNINGS ON WALKING SURFACES).
D. California Code of Regulations (CCR): Provide only approved DSAAC detectable warning products as provided in the California Code of Regulations (CCR) Title 24, Chapter 2,
SECTION 32 17 26 CAST-IN-PLACE DETECTABLE/TACTILE WARNING SURFACE CAST-IN-PLACE DETECTABLE/TACTILE WARNING SURFACE 32 17 26 - 2 of 6 Section 202 definition of ”Detectable Warning”. Section 11B-247 and 11B-705 “Detectable Warnings And Detectable Directional Texture”
E. Vitrified Polymer Composite (VPC) Cast in Place Warning tiles shall include continuous strand woven fiberglass sheet matrix embedded within an epoxy polymer composition with a ultra-violet coating employing aluminum oxide particles in the truncated domes. The tile shall incorporate an in-line pattern of truncated domes measuring nominal 0.2” height, 0.9” base diameter, and 0.45” top diameter, spaced center-to-center 2.35” to 2.40 as measured “In Line”. For wheelchair safety the field area shall consist of a non-slip surface with a minimum of 40 - 90° raised points 0.045” high, per square inch.
1. Dimensions: Cast In Place Detectable/Tactile Warning Surface Tiles shall be held within the following dimensions and tolerances:
Length and Width: 36” x 60"
Nominal Depth: 1.375 (1-3/8”) (+/-) 5% max.
Face Thickness: 0.1875 (1 3/8”) (+/-) 5% max.
Warpage of Edge: 0.5% max.
Embedment Flange Spacing: shall be no greater than 3.1"
2. Water Absorption of Tile when tested by ASTM D 570-98 not to exceed 0.05%.
3. Slip Resistance of Tile when tested by ASTM C 1028-96 the combined Wet and Dry Static Co-Efficients of Friction not to be less than 0.80 on top of domes and field area.
4. Compressive Strength of Tile when tested by ASTM D 695-02a not to be less than 28,000 psi.
5. Tensile Strength of Tile when tested by ASTM D 638-03 not to be less than 19,000 psi.
6. Flexural Strength of Tile when tested by ASTM D 790-03 not to be less than 25,000 psi.
7. Chemical Stain Resistance of Tile when tested by ASTM D 543-95 (re approved 2001) to withstand without discoloration or staining - 10% hydrochloric acid, urine, saturated calcium chloride, black stamp pad ink, chewing gum, red aerosol paint, 10% ammonium hydroxide, 1% soap solution, turpentine, Urea 5%, diesel fuel and motor oil.
8. Abrasive Wear of Tile when tested by BYK - Gardner Tester ASTM D 2486-00 with reciprocating linear motion of 37± cycles per minute over a 10” travel. The abrasive medium, a 40 grit Norton Metallite sand paper, to be fixed and leveled to a holder. The combined mass of the sled, weight and wood block is to be
3.2 lb. Average wear depth shall not exceed 0.060 after 1000 abrasion cycles when measured on the top surface of the dome representing the average of three measurement locations per sample.
9. Resistance to Wear of Unglazed Ceramic Tile by Taber Abrasion per ASTM C501-84 (re approved 2002) shall not be less than 500.
10. Gardner Impact to Geometry "GE" of the standard when tested by ASTM D 5420- 04 to have a mean failure energy expressed as a function of specimen thickness of
SECTION 32 17 26 CAST-IN-PLACE DETECTABLE/TACTILE WARNING SURFACE CAST-IN-PLACE DETECTABLE/TACTILE WARNING SURFACE 32 17 26 - 3 of 6 not less than 550 in. lbf/in. A failure is noted when a crack is visible on either surface or when any brittle splitting is observed on the bottom plaque in the specimen.
11. Accelerated Weathering of Tile when tested by ASTM G 155-05a for 3000 hours shall exhibit the following result – ΔE <4.5, as well as no deterioration, fading or chalking of surface of tile color No 33538
12. Accelerated Aging and Freeze Thaw Test of Tile and Adhesive System when tested to ASTM D 1037-99 shall show no evidence of cracking, delamination, warpage, checking, blistering, color change, loosening of tiles or other detrimental defects.
13. Salt and Spray Performance of Tile when tested to ASTM B 117-03 not to show any deterioration or other defects after 200 hours of exposure.
14. AASHTO HB-17 single wheel HS20-44 loading “Standard Specifications for Highways and Bridges”. The Cast In Place Tile shall be mounted on a concrete platform with a ½” airspace at the underside of the tile top plate then subjected to the specified maximum load of 10,400 lbs., corresponding to an 8000 lb individual wheel load and a 30% impact factor. The tile shall exhibit no visible damage at the maximum load of 10,400 lbs.
15. Embedment flange spacing shall be no greater than 3.1” center to center spacing as illustrated on the product Cast In Place drawing.
1.05 DELIVERY, STORAGE AND HANDLING
A. Cast In Place Detectable/Tactile Warning Surface Tiles shall be suitably packaged or crated to prevent damage in shipment or handling. Finished surfaces shall be protected by sturdy plastic wrappings to protect tile from concrete residue during installation and tile type shall be identified by part number.
B. Cast In Place Detectable/Tactile Warning Surface Tiles shall be delivered to location at building site for storage prior to installation.
1.06 SITE CONDITIONS
A. Environmental Conditions and Protection: Maintain minimum temperature of 40°F in spaces to receive Cast In Place Detectable/Tactile Warning Surface Tiles for at least 24 hours prior to installation, during installation, and for not less than 24 hours after installation.
B. The use of water for work, cleaning or dust control, etc. shall be contained and controlled and shall not be allowed to come into contact with the general public. Provide barricades or screens to protect the general public.
1.07 GUARANTEE
A. Cast In Place Detectable/Tactile Warning Surface Tiles shall be guaranteed in writing for a period of five (5) years from date of final completion. The guarantee includes defective work, breakage, deformation, fading and loosening of tiles.
PART 2 PRODUCTS
SECTION 32 17 26 CAST-IN-PLACE DETECTABLE/TACTILE WARNING SURFACE CAST-IN-PLACE DETECTABLE/TACTILE WARNING SURFACE 32 17 26 - 4 of 6
2.01 MANUFACTURERS
A. Basis-Of-Design Manufacturer: ”Armor-Tile” as manufactured by Engineered Plastics Inc., Tel: 800-682-2525, or approved equal.
B. Product: The Vitrified Polymer Composite (VPC) Cast In Place Detectable/Tactile Warning Surface Tile.
C. Color: Yellow conforming to Federal Color No. 33538. Color shall be homogeneous throughout the tile.
PART 3 EXECUTION
3.01 INSTALLATION
A. During Cast In Place Detectable/Tactile Warning Surface Tile installation procedures, ensure adequate safety guidelines are in place and that they are in accordance with the applicable industry and government standards.
B. Prior to placement of the Cast In Place Detectable/Tactile Warning Surface Tile system, review manufacturer and contract drawings with the Contractor prior to the construction and refer any and all discrepancies to the Engineer.
C. The specifications of the structural embedment flange system and related materials shall be in strict accordance with the contract documents and the guidelines set by their respective manufacturers. Not recommended for asphalt applications.
D. The physical characteristics of the concrete shall be consistent with the contract specifications while maintaining a slump range of 4 - 7 to permit solid placement of the Cast In Place Detectable/Tactile Warning Surface Tile system. An overly wet mix will cause the tile to float.
Under these conditions, suitable weights such as 2 concrete blocks or sandbags (25 lb) shall be placed on each tile.
E. The concrete pouring and finishing operations require typical mason’s tools, however, a 4’ long level with electronic slope readout, 25 lb. weights, and a large non-marring rubber mallet are specific to the installation of the Cast In Place Detectable/Tactile Warning Surface Tile system. A vibrating mechanism such as that manufactured by Vibco can be employed, if desired. The vibrating unit should be fixed to a soft base such as wood, at least 1 foot square.
F. The factory-installed plastic sheeting must remain in place during the entire installation process to prevent the splashing of concrete onto the finished surface of the tile.
G. When preparing to set the tile, it is important that no concrete be removed in the area to accept the tile. It is imperative that the installation technique eliminates any air voids under the tile. Holes in the tile perimeter allow air to escape during the installation process.
Concrete will flow through the large holes in each embedment flange on the underside of the tile. This will lock the tile solidly into the cured concrete.
H. The concrete shall be poured and finished true and smooth to the required dimensions and slope prior to the tile placement. Immediately after finishing concrete, the electronic level should be used to check that the required slope is achieved. The tile shall be placed true and square to the curb edge in accordance with the contract drawings. The Cast In Place
SECTION 32 17 26 CAST-IN-PLACE DETECTABLE/TACTILE WARNING SURFACE CAST-IN-PLACE DETECTABLE/TACTILE WARNING SURFACE 32 17 26 - 5 of 6 Detectable/Tactile Warning Surface Tiles shall be tamped (or vibrated) into the fresh concrete to ensure that the field level of the tile is flush to the adjacent concrete surface. The embedment process should not be accomplished by stepping on the tile as this may cause uneven setting which can result in air voids under the tile surface. The contract drawings indicate that the tile field level (base of truncated dome) is flush to adjacent surfaces to permit proper water drainage and eliminate tripping hazards between adjacent finishes.
I. In cold weather climates it is recommended that the Cast In Place Detectable/Tactile Warning Surface Tiles be set deeper such that the top of domes are level to the adjacent concrete on the top and sides of ramp and that the base of domes to allow water drainage. This installation will reduce the possibility of damage due to snow clearing operations.
J. Immediately after placement, the tile elevation is to be checked to adjacent concrete. The elevation and slope should be set consistent with contract drawings to permit water drainage to curb as the design dictates. Ensure that the field surface of the tile is flush with the surrounding concrete and back of curb so that no ponding is possible on the tile at the back side of curb.
K. While concrete is workable, a 3/8" radius edging tool shall be used to create a finished edge of concrete, then a steel trowel shall be used to finish the concrete around the tile’s perimeter, flush to the field level of the tile.
L. During and after the tile installation and the concrete curing stage, it is imperative that there is no walking, leaning or external forces placed on the tile that may rock the tile causing a void between the underside of tile and concrete.
M. Following tile placement, review installation tolerances to contract drawings and adjust tile before the concrete sets. Two suitable weights of 25 lb each may be required to be placed on each tile as necessary to ensure solid contact of the underside of tile to concrete.
N. Following the concrete curing stage, protective plastic wrap is to be removed from the tile surface by cutting the plastic with a sharp knife, tight to the concrete/tile interface. If concrete bled under the plastic, a soft brass wire brush will clean the residue without damage to the tile surface.
O. If desired, individual tiles can be bolted together using ¼ inch or equivalent hardware. This can help to ensure that adjacent tiles are flush to each other during the installation process.
Tape or caulking can be placed on the underside of the bolted butt joint to ensure that concrete does not rise up between the tiles during installation. Any protective plastic wrap which was peeled back to facilitate bolting or cutting, should be replaced and taped to ensure that the tile surface remains free of concrete during the installation process.
P. Tiles can be cut to custom sizes, or to make a radius, using a continuous rim diamond blade in a circular saw or mini-grinder. Use of a straightedge to guide the cut is advisable where appropriate.
Q. Any sound-amplifying plates on the underside of the tile, which are dislodged during handling or cutting, should be replaced and secured with construction adhesive. The air gap created between these plates and the bottom of the tile is important in preserving the sound on cane audible properties of the Armor-Tile system as required in various jurisdictions.
3.02 CLEANING, PROTECTING AND MAINTENANCE
A. Protect tiles against damage during construction period to comply with Tactile Tile
SECTION 32 17 26 CAST-IN-PLACE DETECTABLE/TACTILE WARNING SURFACE CAST-IN-PLACE DETECTABLE/TACTILE WARNING SURFACE 32 17 26 - 6 of 6 manufacturer’s specification.
B. Protect tiles against damage from rolling loads following installation by covering with plywood or hardwood.
C. Clean Tactile Tiles not more than four days prior to date scheduled for inspection intended to establish date of substantial completion in each area of project. Clean Tactile Tile by method specified by Tactile Tile manufacturer.
D. Comply with manufacturers maintenance manual for cleaning and maintaining tile surface and it is recommended to perform annual inspections for safety and tile integrity.
END OF SECTION
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 1 of 26
***************************ATTENTION: This section contains multiple sections************************************* SECTION 33 05 31.11 - POLYVINYL CHLORIDE (PVC) GRAVITY PIPE PART 1 – GENERAL
1. 01 THE REQUIREMENT:
The Contractor shall furnish and install PVC pipe and all appurtenances as specified, complete and in place, as shown on the Plans, as specified in this Section and Section 33 31 00 - Sanitary Sewerage Piping and Section 33 31 16 - Sanitary Sewer Gravity Service Laterals.
1.02 RELATED WORK SPECIFIED ELSEWHERE:
A. All Related Documents and Sections: Contractor to examine Contract Documents for requirements that directly affect or are affected by Work of this Section. Those Documents and Sections include, but is not limited to, the following:
1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 General Requirements, apply to this Section.
2. All Specification Sections listed in the Table of Contents.
1.03 REFERENCE SPECIFICATIONS, CODES AND STANDARDS:
A. Commercial Standards:
AWWA C900-07: Standard for Polyvinyl Chloride (PVC) Pressure Pipe and Fabricated Fittings, 4 In. Through 12 In. (100 mm through 300 mm), for Water Transmission and Distribution
AWWA C905-08: Polyvinyl Chloride (PVC) Pressure Pipe and Fabricated Fittings, 14 In.
Through 48 In. (350 mm Through 1,200 mm), for Water Transmission and Distribution ASTM D 1784: Specification for Rigid Poly (Vinyl Chloride) (PVC) Compounds and Chlorinated Poly (Vinyl Chloride) (CPVC) Compounds.
ASTM D 2241: Specification for Poly (Vinyl Chloride) (PVC) Pressure-Rated Pipe (SDRSeries) ASTM D 2321: Practice for Underground Installation of Thermoplastic Sewer Pipe for Sewers and Other Gravity-Flow Applications
ASTM D 3034: Specification for Type PSM Poly (Vinyl Chloride) (PVC) Sewer Pipe and Fittings
ASTM F 477: Standard Specification for Elastomeric Seals (Gaskets) for Joining Plastic Pipe
ASTM F 1674: Test Method for Joint Restraint Products
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 2 of 26
1.04 QUALITY ASSURANCE:
A. Except as modified in this Section, all materials used in the manufacture or installation of the pipe shall be tested in accordance with the requirements of the referenced standards.
B. Submittals and testing shall be done in compliance with Section 33 01 30.11 - Inspection of Sewers.
PART 2 – PRODUCTS
2.01 GENERAL:
All PVC pipe shall be continuously and permanently marked with the manufacturer's name, pipe size and pressure rating in psi.
2.02 PIPE:
A. All PVC pipe shall be joined by compression, solvent-welded, thermo-fusion welded or mechanical restrained joints as shown on the Plans.
B. Polyvinyl chloride pipe (PVC) shall conform to the requirements of ASTM D 3034, SDR26, or AWWA C900 or C905, Class 100, 150, 165, 200, 253, or 305. Material for PVC pipe shall conform to the requirements of ASTM D 1784 for Class 12454-B or 12454-C as defined therein.
C. Flexible rubber rings for compression type joints for PVC pipe and fittings shall conform to the requirements of ASTM F 477.
D. All sun-faded pipe or pipe with noticeable surface defects will be rejected and shall be replaced by the Contractor.
2.03 COUPLINGS AND FITTINGS:
A. Couplings shall be as listed in the Approved Materials List.
B. All fittings for PVC pipe shall conform to the requirements of ASTM D 2241. The ring groove and gasket ring shall be compatible with PVC pipe ends.
C. The strength class of fittings shall be no less than the strength class of any adjoining pipe.
D. PVC fittings shall, at a minimum, conform to the requirements of ASTM D 3034 as they apply to type SDR-26 PVC Sewer Pipe using an Elastomeric Gasket Joint in a bell and spigot assembly system. Rubber sealing gaskets shall meet the requirements of ASTM F 477.
E. All PVC pipe entering or leaving a concrete structure shall have a rubber sealing gasket, as supplied by the pipe manufacturer, firmly seated perpendicular to the pipe axis, around the pipe banded and cast into the structure base or near the structure wall center as a water stop. Said water stop may also consist of a manhole coupling with rubber sealing rings cast into the structure base (see DWG 20-05).
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 3 of 26
2.04 RESTRAINED JOINTS FOR C900 PVC PIPE:
All restrained joints used in sanitary sewer applications shall meet or exceed the requirements of ASTM F 1674. All restrained joints shall be per the Approved Materials List.
PART 3 – EXECUTION
3.01 GENERAL:
A. Sewer pipelines shall be constructed in compliance with the requirements of this Section and Section 33 31 00 - Sanitary Sewerage Piping and Section 33 31 16 - Sanitary Sewer Gravity Service Laterals.
B. Work shall meet the specified requirements of these Specifications unless the requirements of the local agency having jurisdiction are greater, in which case the greater requirements shall govern.
3.02 INSTALLATION:
PVC pipe shall be installed in accordance with the requirements of ASTM D 2321; as specified herein and shown on the Plans
3.03 HORIZONTAL CURVES:
Horizontal curves shall be installed using straight pipe segments, each a minimum of five feet in length and joint deflections or fittings in accordance with the requirements of DWG 21-01, or with forced bends where the radius of the curve exceeds the minimums specified in the table below:
3.04 FIELD JOINTING:
A. Each pipe compression-type joint shall be joined with a lock-in rubber ring and a ring groove that is designed to resist displacement during pipe insertion.
B. The ring and the ring seat inside the bell shall be wiped clean before the gasket is inserted. A thin film of lubricant shall be applied to the exposed surface of the ring and to the outside of the clean pipe end. Lubricant other than that furnished with the pipe shall not be used.
C. Joints shall not be deflected either vertically or horizontally in excess of the printed recommendations of the pipe manufacturer.
END OF SECTION
*****************************************************************************************************************************
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 4 of 26
SECTION 33 05 19 - DUCTILE IRON PIPE (DIP)
PART 1 – GENERAL
1.01 THE REQUIREMENT:
The Contractor shall furnish and install ductile iron pipe (DIP) and all appurtenances as specified, complete and in place, as shown on the Plans, as specified in this Section and in Section 33 31 00 - Sanitary Sewerage Piping and Section 33 31 16 - Sanitary Sewer Gravity Service Laterals.
1.02 RELATED WORK SPECIFIED ELSEWHERE:
A. All Related Documents and Sections: Contractor to examine Contract Documents for requirements that directly affect or are affected by Work of this Section. Those Documents and Sections include, but is not limited to, the following:
1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 General Requirements, apply to this Section.
2. All Specification Sections listed in the Table of Contents.
1.03 REFERENCE SPECIFICATIONS, CODES AND STANDARDS:
A. Commercial Standards:
ANSI/AWWA C110/A21.10: Ductile-Iron and Gray-Iron Fittings, 3 in. through 48 in. for Water and Other Liquids
ANSI/AWWA C111/A21.11: Rubber-Gasket Joints for Ductile-Iron and Gray-Iron Pressure Pipe and Fittings
ANSI/AWWA C115/A21.15: Flanged Ductile-Iron and Gray-Iron Pipe with Threaded Flanges
ANSI/AWWA C150/A21.50: Thickness Design of Ductile-Iron Pipe ANSI/AWWA C151/A21.51: Ductile-Iron Pipe, Centrifugally Cast ANSI/AWWA C153/A21.53: Ductile-Iron Compact Fittings, 3 in. through 12 in. for Water and Other Liquids
AWWA C600: Installation of Ductile-Iron Water Mains and Their Appurtenances
1.05 QUALITY ASSURANCE:
A. Except as modified in this Section, all materials used in the manufacture or installation of the pipe shall be tested in accordance with the requirements of the referenced standards.
B. Submittals and testing shall be done in compliance with Section 33 01 30.11 - Inspection of Sewers.
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 5 of 26
PART 2 – PRODUCTS
2.01 GENERAL:
A. Ductile-iron pipe (DIP) shall conform to the latest revision of ANSI/AWWA C150/A21.50 subject to the following supplemental requirements. The pipe shall be furnished complete with rubber gaskets, and all special fittings shall be provided as shown on the Plans.
B. Bell and spigot joints and mechanical joints are acceptable for underground applications.
As an alternative to bell and spigot joints the use of mechanical and flanged joints will be permitted for above ground applications only.
2.02 PIPE:
Ductile iron pipe shall be of the diameter indicated at a minimum Class 52 and shall be manufactured with standard bell and spigot joints in accordance with the latest revision of ANSI/AWWA C151/A21.51.
2.03 LINING AND COATING:
Pipe shall have standard asphaltic coating on the exterior and be epoxy lined on the interior with Protecto 401™ ceramic epoxy lining as manufactured by U.S. Pipe, or approved equal.
2.04 FITTINGS:
A. Fittings shall be ductile iron at a minimum of Class 52. Fittings shall conform to the latest revision of either ANSI/AWWA C110/A21.10 or ANSI/AWWA C153/A21.53. Fittings and accessories shall be furnished with either Push-on or Mechanical Type Joints in accordance with ANSI/AWWA C111/A21.11.
B. Ductile-iron pipe and fittings shall be furnished with mechanical joints, push-on joints, flanged joints, and/or restrained joints, as required. Bolted joints shall not be used for underground installations.
1. Mechanical and push-on bell and spigot joints shall conform to ANSI/AWWA C111/A21.11 and be furnished complete with all necessary accessories.
2. Flanged joints shall conform to ANSI/AWWA C115/A21.15.
3. Restrained joints shall be per the Approved Materials List.
PART 3 – EXECUTION
3.01 GENERAL:
A. Sewer pipelines shall be constructed in compliance with the requirements of this Section and Section 33 31 00 - Sanitary Sewerage Piping and Section 33 31 16 - Sanitary Sewer Gravity Service Laterals.
B. Work shall meet or exceed the requirements of these Specifications unless applicable requirements of an agency having jurisdiction (including the terms and conditions of an encroachment permit issued by a city or county) are greater, in which case the greater requirements shall govern.
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 6 of 26
3.02 INSTALLATION OF PIPE:
A. All pipe shall be installed in accordance with ANSI/AWWA C600.
3.03 RUBBER-GASKETED JOINTS:
A. Immediately before jointing pipe, the bell end of the pipe shall be thoroughly cleaned, and a clean rubber gasket, lubricated with an approved vegetable-based lubricant, shall be placed in the bell groove. The spigot end of the pipe shall be carefully cleaned and lubricated with a vegetable-based lubricant. The spigot end of the pipe section shall then be inserted into the bell of the previously laid joint and pushed into its proper position.
Tilting of the pipe to insert the spigot into the bell will not be permitted.
END OF SECTION
***************************************************************************** SECTION 31 23 16 - EXCAVATION, BEDDING AND BACKFILL
PART 1 – GENERAL
1.01 THE REQUIREMENT:
The Contractor shall provide all labor, materials, and equipment necessary to perform all excavation, bedding, backfill and grading operations required for construction of the work.
1.02 RELATED WORK SPECIFIED ELSEWHERE:
A. All Related Documents and Sections: Contractor to examine Contract Documents for requirements that directly affect or are affected by Work of this Section. Those Documents and Sections include, but is not limited to, the following:
1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 General Requirements, apply to this Section.
2. All Specification Sections listed in the Table of Contents.
1.03 REFERENCE SPECIFICATIONS, CODES AND STANDARDS:
A. Commercial Standards:
ASTM D 1556: Test Method for Density and Unit Weight of Soil in Place by Sand-Cone Method
ASTM D 1557: Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kNm/m3))
ASTM D 2419: Standard Test Method for Sand Equivalent Value of Soils and Fine Aggregates
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 7 of 26
ASTM D 2487: Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)
ASTM D 6938: Test Methods for In-Place Density and Water Content of Soil and SoilAggregate by Nuclear Methods (Shallow Depth) ASTM D 4253: Test Methods for Maximum Index Density and Unit Weight of Soils Using a Vibratory Table
ASTM D 4254 Test Methods for Minimum Index Density and Unit Weight of Soils and Calculation of Relative Density
1.04 CONTRACTOR SUBMITTALS:
A. Compaction testing of bedding and backfill materials shall be required for all main sewer extensions and laterals in public streets.
B. Compaction testing of bedding and backfill for side sewer work on private property may be required at the discretion of the Inspector.
C. The required compaction testing shall be conducted under the direction of a Civil or Geotechnical Engineer licensed by the State of California. As a condition of Central San’s Final Inspection, a Certification Report indicating that compaction results meet or exceed the requirements of these Specifications shall be submitted by the engineer in responsible charge of the compaction testing with a cover letter bearing the engineer’s professional stamp.
D. Compaction testing shall be completed prior to the acceptance televising of the sewer and installation of final paving.
1.05 QUALITY ASSURANCE:
A. Where soil material is required to be compacted to a percentage of maximum density, the maximum density at optimum moisture content will be determined in accordance with ASTM D 1557. Where cohesionless, free draining soil material is required to be compacted to a percentage of relative density, the calculation of relative density will be determined in accordance with ASTM D 4253 and D 4254. Field density in-place tests will be performed in accordance with ASTM D 1556, ASTM D 6938, or by such other means acceptable to Central San. At a minimum, compaction tests shall be conducted for each 50 feet of trench and for each 2 feet of trench depth, unless otherwise specified by the agency with jurisdiction for the roadway.
B. If a first test and a subsequent re-test of the bedding or backfill show noncompliance with the density required under this Section, the Contractor shall remove and re-compact the material represented by the test/retest as necessary to ensure compliance.
C. The Contractor shall provide access in the excavation for the soil compaction testing technician or Inspector. This shall include providing site-specific safety equipment and temporary shoring to enable compaction testing at each required level within the excavation. Should the Contractor have backfilled to an elevation above that required to be tested, he shall excavate the backfill down to the necessary level for testing and provide shoring at his cost. Subsequent backfilling shall also be at the Contractor’s cost.
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 8 of 26
PART 2 – PRODUCTS
2.01 SUITABLE BEDDING AND BACKFILL MATERIAL:
A. Bedding and backfill material shall be selected or processed clean, free from grass, roots, brush, other vegetation, debris, refuse or other deleterious material of any kind.
B. The following types of bedding and backfill materials are designated and defined as follows:
1. Type I Bedding and Backfill Material (Class 2 Aggregate Base): Shall be newly quarried or recycled material (not mined alluvial material), and shall be certified by the quarry or recycler as complying with the provisions of Caltrans Specifications Section 26 (Class 2 Aggregate Base) for 3/4” maximum grading.
2. Type III Bedding and Backfill Material (native material from trench excavation): Shall be free from vegetable matter, debris and refuse, shall contain no concrete, stones or clods larger than 3” in any dimension and shall contain sufficient fines so that all voids will be filled when compacted, and shall be so constituted that compaction requirements can be met.
3. Select Type III Bedding and Backfill Material (native material from trench excavation):
Shall meet all requirements of the above described Type III Bedding and Backfill Material with the additional requirement that the maximum particle size shall be 3/4” in diameter.
4. Coarse Bedding Material (Drain Rock/Foundation Rock): Shall be crushed stone or gravel (not mined alluvial material), with a minimum of 95% crushed particles per CTM 205, durable and free from slaking or decomposition under action of alternate wetting and drying with minimum Durability Index of 40 per CTM 229. The material shall meet the following gradation requirements:
C. Controlled Low Strength Material shall conform to the requirements of Section 03 34 13 - Controlled Low-Strength Material (CLSM).
2.02 UNSUITABLE MATERIAL:
A. Unsuitable materials for bedding and backfill shall include soils, which when classified under ASTM D 2487 fall in the classifications of PT, OH, CH, MH, or OL. In addition, any soil that cannot be sufficiently compacted to achieve the percentage of maximum density specified for the intended use shall be considered unsuitable.
B. Chemical testing for corrosivity shall be performed for all materials proposed for use as bedding and backfill for metallic or reinforced concrete pipe. The testing shall be in accordance with the requirements of CTM 417, CTM 422 and CTM 643. Bedding and backfill materials shall be considered unsuitable when the chloride concentration exceeds 500 ppm, sulfate concentration exceeds 1,500 ppm, resistivity is less than 2,000 ohm-cm
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 9 of 26
or pH is less than 6.5. Testing shall be performed by a qualified laboratory approved by Central San, and the data shall be submitted to the Inspector for acceptance prior to use of the material in the work.
C. Type III materials which are too wet to be compacted to specified compaction shall not be rejected solely because they are too wet for proper compaction. The Contractor may at its option, dry these materials in accordance with Paragraph 3.8.G of this section prior to compaction. Alternatively, the Contractor may remove the Type III materials and provide imported backfill material.
D. Backfill placed within 6” of any structure or pipe shall be free of rocks or unbroken clods of earth larger than 3” in any dimension.
E. All material that is determined to be unsuitable for use as bedding and backfill or that is in excess of the amount required shall be removed immediately and disposed of properly by the Contractor.
2.03 USE OF SUITABLE BEDDING AND BACKFILL MATERIAL:
Backfill types shall be used in accordance with the following provisions:
A. Pipe zone backfill (bedding, haunching and shading), as defined under paragraph 3.6 Bedding and Backfill herein, shall be Type I Bedding and Backfill Material (Class 2 Aggregate Base) unless otherwise specified on the Plans.
B. Trench zone backfill, as defined under paragraph 3.6 Bedding and Backfill herein, for pipelines in public and private streets and other paved areas shall be Type I Bedding and Backfill Material (Class 2 Aggregate Base).
C. Trench zone backfill in future roadway or street rights-of-way or in off road locations (e.g., easements) may be Type III Bedding and Backfill Material (native trench soil) so long as specified compaction is achieved.
D. Final Backfill as defined under "Pipe and Utility Trench Backfill herein, for pipelines in public and private streets and other paved areas shall be Type I Bedding and Backfill Material (Class 2 Aggregate Base).
E. Backfill around structures, vaults, and valve boxes shall be Type I Bedding and Backfill Material (Class 2 Aggregate Base).
F. Backfill used to replace structure and pipeline trench over-excavation of wet or soft trench bottom conditions shall be Coarse Bedding and Backfill Material (Drain Rock/Foundation Rock) with a geotextile envelope (minimum one-foot overlap) around the rock to prevent migration of fines.
G. Controlled Low Strength Material may be used for pipe zone backfill and trench zone backfill whenever pre-approved in writing by Central San or shown on the Plans.
H. Trenches in landscaped or cultivated areas shall have the top 12” inches backfilled with topsoil.
2.04 FILTER FABRIC:
Filter fabric shall be as specified in Section 31 05 19 - Geosynthetics for Earthwork.
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 10 of 26
2.05 TRENCH DAMS, AND PIPE ANCHORS:
Trench Dams and Pipe Anchors shall be provided at the locations shown on the Plans and shall be constructed as shown in the Standard Drawings as follows:
• DWG 20-05 Trench Dams
• DWG 21-03 Pipe Anchor Detail
Trench dams shall be of the length and width dimensions shown in the detail, shall extend below finished grade as shown in the detail, and shall be constructed of controlled low strength material (CLSM) as specified in Section 03 34 13 - Controlled Low-Strength Material (CLSM).
PART 3 – EXECUTION
3.01 GENERAL:
A. Work shall meet or exceed the requirements of these Specifications unless applicable requirements of an agency having jurisdiction (including the terms and conditions of an encroachment permit issued by a city or county) are greater, in which case the greater requirements shall govern.
B. Prior to any excavation and backfill work, the Contractor shall obtain and provide Central San with copies or other evidence of acquisition thereof, all required permits for the work, including but not limited to: County and/or City encroachment permits, Central San permits, Cal OSHA Excavation Permit, and Competent Person certification.
C. Material to be used for backfill shall be laid alongside of the trench and kept trimmed so as to cause as little inconvenience as possible to public travel and the normal use of adjacent properties. However, stockpiled material shall be kept a minimum of two feet from the edge of the trench and the face of the stockpile shall be sloped as needed. Free access shall be provided to all fire hydrants, water gates, meters, and private drives.
Gutters or other drainage ways shall be kept clear unless other temporary provisions are made for maintaining drainage.
D. In advance of placing sewer pipe or structures, material within the area where such pipe or structures are to be placed, which in the opinion of the Inspector is unsuitable including, but not limited to vegetable matter, garbage, and junk piles, either on the surface or buried, shall be removed and disposed of.
E. Water to control dust resulting from grading operations, excavation, backfill, and the passage of traffic through the work area shall be applied by means that will ensure a uniform application of water with no runoff.
F. The Contractor shall remove and dispose of all excess excavated material at a suitable preferred site(s). The Contractor shall obtain all necessary fill and grading permits and a written release from property owners upon completion of use of said sites.
3.02 STRUCTURE EXCAVATION:
A. Except when specifically provided to the contrary, excavation shall include the removal of all materials of whatever nature encountered, including all obstructions of any nature that would interfere with the proper execution and completion of the work. The removal of
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 11 of 26
these materials shall conform to the lines and grades shown on the Plans or as directed by the Inspector Unless otherwise provided, the entire construction site shall be stripped of all vegetation and debris, and such material shall be removed from the site prior to performing any excavation or placing any fill. The Contractor shall furnish, place, and maintain all supports and shoring that may be required for the sides of the excavations, and all pumping, ditching, or other measures required for the removal or exclusion of water, including storm water, groundwater, and wastewater reaching the site of the work from any source so as to provide dry working conditions and to prevent damage to the work or adjoining property. Excavations shall be benched, sloped, shored or otherwise supported in a safe manner in accordance with applicable State safety requirements and the requirements of OSHA Safety and Health Standards for Construction (29CFR1926).
F. Excavation under structures, manholes, vaults and others: Except where otherwise specified for a particular structure or directed by the Inspector, excavation shall be carried to the grade of the bottom of the bedding. Where shown on the Plans or directed by the Inspector, areas beneath structures shall be over-excavated. The exposed surface shall be scarified to a depth of 6”, brought to optimum moisture content, and compacted to 95% relative compaction. Where over-excavation is directed by the Inspector to provide for the placement of foundation rock over wet or soft soils, scarification and recompaction shall not be performed.
3.03 TRENCH EXCAVATION:
A. Excavation for sewers shall be made only after pipe and other necessary materials are delivered on the site of the work. After such delivery, trench excavation shall proceed as rapidly as possible, and the pipe installed and the trench backfilled without undue delay.
In public street areas, excavation and pipe installation shall be coordinated to the end that a minimum of interference with traffic will result.
B. Refer to table below for required trench widths according to nominal pipe size.
C. The pipe bedding shall be given a final trim, using a laser for establishing grade, such that each pipe section when first laid will be continually in contact with the bedding along the bottom of the pipe. The Contractor shall excavate bell holes at pipe joints.
D. For trenching in existing streets, excavation and pipe installation shall be coordinated so that no more than 100 linear feet of trench shall be open at any time. Backfilling operations shall closely follow pipe installation. In new subdivisions more than 100 feet of trench may be opened if allowed by the Inspector and if the excavation is properly shored, sloped or benched. All trenches shall be fully backfilled at the end of each day or, properly shored and covered by heavy steel plates adequately braced and capable of supporting H-20 vehicle loads in those locations subject to traffic and with 1- 1/8” plywood in off road locations where it is impractical to backfill at the end of each day. Use of steel traffic plates is subject to the prior approval of the agency issuing the encroachment permit. Traffic plates shall be staked in place, with adjacent plates tack-welded together, and shall be provided with non-skid coating. Compacted cold mix asphalt shall be placed around the plate perimeter to provide a smooth transition from adjacent pavement.
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 12 of 26
E. Where the bottom of the trench becomes soft or is unstable due to groundwater and/or movement of construction equipment, the Contractor shall over-excavate unsuitable material to a minimum depth of 9” below the base elevation to establish a stable foundation for the bedding or to a depth as otherwise directed by the Inspector.
Geotextile shall be placed on the overexcavated trench bottom and staked to the trench walls, coarse bedding material in conformance with these specifications shall be placed on the fabric, and the fabric shall then be un-staked from the trench wall and wrapped over the coarse bedding material forming a closed envelope with a minimum 1-foot overlap at the top edges of the fabric.
F. Any over-excavation carried below the grade ordered, specified, or shown, shall be backfilled and compacted to the required grade with the specified material.
3.04 EMBANKMENT EXCAVATION:
A. The relative compaction of the natural ground area upon which embankments are to be constructed, for a depth of not less than 2 feet below finished grade, shall be not less than 90% relative compaction.
B. If finished grade is less than 3 feet, above natural ground, the natural ground shall be excavated to a depth of not less than 3 feet below finished grade and re-compacted to a relative compaction of not less than 90%.
C. When embankments are to be made and compacted on hillsides, or where new fill is to be compacted against existing embankments, the slopes of the original hillside, old or new fill, shall be cut into a minimum of 6 feet horizontally as the work is brought up in layers. Material thus cut out shall be re-compacted along with the new fill. Fill shall be compacted to a relative compaction of not less than 90%.
3.05 BEDDING AND BACKFILL:
A. Except for required foundation material (in an envelope of geotextile) coarse bedding material being placed in over-excavated areas, where water or soft ground is present, backfill shall not be placed until after all water is removed from the excavation.
B. Pipe zone bedding and backfill operations shall be performed in accordance with the following requirements:
1. Type I Bedding and Backfill Material (Class 2 Aggregate Base) shall be placed and properly compacted in the pipe zone. The pipe zone is defined as that portion of the vertical trench cross-section lying between a plane 4 to 6” below the bottom surface of the pipe, i.e., the trench sub-grade, and a plane at a point 12” above the top outside surface of the pipe. The subzones of the pipe zone are defined as follows:
a) "Bedding is that portion of the Pipe Zone between the bottom of the trench or the top of required foundation material and the lowest point on the outside surface of the pipe barrel excepting bells;
b) "Haunching" is that portion of the Pipe Zone between the top of the Bedding and the horizontal centerline of the pipe;
c) "Shading" is that portion of the Pipe Zone between the top of the Haunching and a horizontal plane 12” above the highest point on the outside surface of the pipe barrel excepting bells.
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 13 of 26
2. Controlled Low Strength Material (CLSM) shall be provided in lieu of Type I Bedding and Backfill Material where indicated on the Plans Contractor shall provide a method to prevent pipe from floating during backfill. (The remaining portions of the trench shall be backfilled as specified elsewhere in this Section.)
3. After compacting the bedding, the Contractor shall perform a final trim using a laser for establishing grade, such that each pipe section when laid will be continually in contact with the bedding along the bottom of the pipe. The Contractor shall provide bell holes at each pipe joint.
4. Backfill in trenches shall be placed uniformly on each side of the pipe to prevent displacement. The Contractor shall exercise care to prevent damage to the pipeline coating, cathodic bonds, or the pipe itself during the installation and backfill operations. The Contractor shall hand shovel slice the bedding along the sides of the pipe in order to ensure filling any voids under the pipe haunches.
C. Warning Tape: A colored detectable metallic foil core plastic tape, at least 3” in width, shall be placed on top of the pipe zone backfill wherever sewers are installed. The tape shall have printed on it the words “Caution: Sewer Buried Below.” The warning tape shall be utilized for all pipes (mains and laterals).
D. After the pipe zone backfill has been placed as specified above, and after all excess water has completely drained from the trench, backfilling of the trench zone may proceed.
The trench zone is defined as that portion of the trench excavation between the top of the shading and the ground surface in unpaved areas, and the horizontal plane at lowest point of the pavement structural section in paved areas.
E. "Final Backfill" is that portion of the Trench Zone in paved areas between the top of the trench backfill and the lowest point of the pavement structural section.
F. Joint utility trench excavations shall conform to the requirements shown on DWG 20-06.
3.06 PLACING AND SPREADING OF BACKFILL AND EMBANKMENT MATERIALS:
A. Backfill materials shall be placed and spread evenly in layers. The backfill layers shall be evenly spread so that each layer shall not exceed 8” in uncompacted thickness. Backfill layers greater than 8” but no more than 24” may be used after the Contractor demonstrates by compaction testing as specified in 3.8 below, that required compaction levels will be achieved.
B. During spreading, each layer shall be thoroughly mixed as necessary to promote uniformity of material in each layer. Pipe zone backfill materials shall be manually spread around the pipe so that when compacted, the pipe zone backfill will provide uniform bearing and side support.
C. Where the backfill material moisture content is below the optimum moisture content, water shall be added before or during spreading until the proper moisture content is within the range where the specified compaction can be achieved.
D. Where the backfill material moisture content is too high to permit the specified degree of compaction, the material shall be bladed, aerated or dried and/or mixed with dryer material until the moisture content is satisfactory.
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 14 of 26
E. Whenever selection is possible, embankment material having a sand equivalent value of less than 10 shall be deposited in the lower portions of embankments and no such material shall be placed within 3 feet of planned finished grade.
F. When the embankment material consists of large rocky material, or hard lumps such as hardpan or cemented gravel which cannot be broken readily, such material shall be well distributed throughout the embankment, and sufficient earth or other fine material shall be placed around the large material as it is deposited so as to fill the interstices and produce a dense compact embankment, but in no case shall any material exceed 24” in any dimension.
3.07 COMPACTION OF BACKFILL AND EMBANKMENT MATERIALS:
A. The Contractor shall provide a minimum of one compaction test per day, and an additional compaction test for each 500 sf completed and at each structure (e.g. manholes), and as required on the Plans or at the direction of the Central San Inspector.
B. Each layer of backfill material as defined herein, shall be mechanically compacted to the specified percentage of maximum density. Equipment that is consistently capable of achieving the required degree of compaction shall be used and each layer shall be compacted over its entire area while the material is at the required moisture content.
Compaction at the top of the pipe zone shall be done using a plate compactor.
C. Flooding, ponding, or jetting shall not be used.
D. Equipment weighing more than 10,000 pounds shall not be used within a horizontal distance equal to the depth of the trench. Hand operated power compaction equipment shall be used where use of heavier equipment is impractical or restricted due to weight limitations.
E. The following compaction requirements shall be in accordance with ASTM D 1557 except for free draining materials (i.e., Coarse Bedding Material/Drain Rock/Foundation Material), which shall be in accordance with ASTM D 4253 and D 4254 for cohesionless free draining type materials. Where other public agency, utility company or encroachment permit requirements govern, the highest compaction standards shall apply.
F. The Contractor shall maintain the indicated trench cross section at a minimum of 12” above the top of the pipe (the top of the “pipe zone”).
G. Embankments shall be constructed as recommended by the geotechnical engineer in compacted layers of uniform thickness.
H. At the time of compaction, the moisture content of embankment material shall be such that the relative compactions specified will be obtained and the embankment will be in a
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 15 of 26
firm and stable condition. Embankment material which contains less than the required moisture content shall be watered and material which contains excessive moisture shall not be compacted until the material is dry enough to obtain the required compaction.
3.08 TEMPORARY PAVING:
A minimum of 2” of cold or hot mix temporary asphalt shall be placed in finished trenches and rolled to a smooth surface at the end of each day unless final paving can be completed, or steel plates are used to cover trenches in paved streets. Traffic plates shall be subject to the requirements of 3.3 above. The temporary asphalt shall be placed within ¼” of finished pavement grade.
END OF SECTION
***************************************************************************************************************************** SECTION 33 01 30.11 - INSPECTION OF SEWERS
PART 1 – GENERAL
1. 01 THE REQUIREMENT:
A. The Contractor shall furnish all labor, materials, tools, and equipment necessary to clean, perform testing, and provide for televising of completed sewer pipelines.
B. The Contractor shall call the Central San Inspection Office at least one business day in advance to arrange for an Inspector to be present for the preinstallation CCTV inspection.
C. The Contractor shall notify the Inspector at least one business day prior to any cleaning, testing, or televising work. All final testing and cleaning of sewer lines shall be done in the presence of the Inspector.
D. The Contractor shall complete cleaning and testing of sewer lines as required in this Section prior to requesting CCTV inspection.
E. No testing will be allowed until all utilities have been installed.
F. If deficiencies are identified during testing, the Contractor shall re-test after the deficiencies have been corrected.
1.02 REFERENCE SPECIFICATIONS, CODES AND STANDARDS:
A. Commercial Standards:
ASTM C 969: Standard Practice for Infiltration and Exfiltration Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines
ASTM C 1091-03a: Test Method for Hydrostatic Infiltration Testing of Vitrified Clay Pipe Lines
AWWA C600-54T: Installation of Ductile-Iron Water Mains and Their Appurtenances
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 16 of 26
ASTM D 3034: Specification for Type PSM Poly (Vinyl Chloride) (PVC) Sewer Pipe and Fittings
ASTM F 679: Specification for Poly (Vinyl Chloride) (PVC) Large-Diameter Plastic Gravity Sewer Pipe and Fittings
PART 2 – PRODUCTS
2.01 MATERIAL REQUIREMENTS:
A. Mandrels, temporary plugs, low-pressure testing equipment and all other necessary materials shall be provided by the Contractor, subject to the Inspector’s approval.
B. No materials shall be used which would be injurious to the public, personnel, adjacent improvements or the pipeline.
C. Air test gauges shall be laboratory-calibrated test gauges and shall be recalibrated by a certified laboratory prior to the leakage test. Gauge shall be easy to read in no more than 1 psi per increment and have a maximum full-scale range of 5 psi.
PART 3 – EXECUTION
3.01 GENERAL:
A. The Contractor shall clean pipelines by balling and flushing or hydroflushing prior to deflection and pressure testing.
B. The Contractor shall perform deflection and pressure tests after submittal of compaction reports demonstrating compliance with the backfill compaction requirements and before CCTV inspections.
C. Work shall meet or exceed the requirements of these Specifications unless applicable requirements of an agency having jurisdiction (including the terms and conditions of an encroachment permit issued by a city or county) are greater, in which case the greater requirements shall govern.
3.02 CLEANING:
A. After the pipeline installation has been completed to the satisfaction of Central San, the Contractor shall clean the pipe in the presence of the Inspector.
B. The Contractor shall clean all sewer installations, deemed necessary by the Inspector, with a cleaning ball or device in accordance with the device manufacturer's instructions or recommendations and flushed. Hydroflush-pressure shall be maintained below 2,000 psi.
Traps with screens in accordance with DWG 21-08 shall be used to trap debris. The Contractor shall remove all debris from the manhole prior to removing the trap.
C. Release of water during and/or after cleaning and testing has been completed, shall be performed in a manner approved by the Inspector. The Contractor shall be responsible for the proper disposal of water released.
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 17 of 26
D. The Contractor shall perform an additional cleaning of the pipeline after the installation of final paving, top block, frames and covers, and after all other required inspections, if required by the Inspector due to a reasonable determination that additional debris may have accumulated in the pipeline after initial cleaning.
3.03 PIPELINE DEFLECTION TESTING:
PVC and HDPE pipe 8” in diameter or larger shall be tested for deflection, joint displacement, or other obstruction by passing a rigid mandrel through the pipe. Deflection shall be tested after submittal of daily compaction reports demonstrating compliance with, but prior to, permanent resurfacing. The mandrel shall be a full circle, rigid, non-adjustable, an odd-numbered leg (9 leg minimum), acceptable to the Inspector as to design and manufacturer. Mandrel size shall meet the minimum requirements set forth in ASTM D 3034 and ASTM F 679. The circular cross section of the mandrel shall have a diameter of at least 95% of the specified average inside diameter of the pipe and the minimum length of the circular portion of the mandrel shall be equal to the nominal diameter of the pipe. Where obstructions and excessive deflection encountered by the mandrel, the Contractor shall remove, replace and retest the deficient section. Re-rounding will not be allowed.
3.04 PIPELINE LEAKAGE TESTING:
A. Repaired pipelines shall be re-tested as follows:
B. Air Testing
1. Each section of main sewer and its appurtenant connected laterals shall be tested between successive manholes by plugging and bracing all openings in the sewer lines. If any leaks are found, the air pressure shall be released, the leaks eliminated, and the test procedure started over again.
2. Air tests shall be conducted in accordance with the following procedure and the table below:
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 18 of 26
All necessary test equipment shall be in proper working order and tests shall be made in the presence of the Inspector. Test plugs shall be carefully placed at each end of the section of line to be tested. When all necessary test equipment is in place, a compressed air supply shall be attached to the air fitting on the test equipment and the air pressure within the line increased to 4 psi. After the air supply is securely turned off or disconnected, there shall be a 2-minute waiting period to allow stabilization of air within the sewer line before the actual test period begins. In no case shall the air pressure within the line be less than 3-1/2 psi at the beginning of the test period. The allowable air pressure loss shall not exceed 1 psi. When testing side sewers, or portions thereof, the test period shall be 4 minutes and the allowable loss shall not exceed 1 psi. After completion of a test, the air pressure shall be released slowly through the valve, which is incorporated in the test equipment. Air test plugs shall not be removed until the air pressure is no longer measurable.
C. New sewers larger than 16” diameter shall be hydrostatically tested in accordance with the following procedure:
1. After installation, all new trunk sewer pipelines shall be thoroughly cleaned prior to pressure testing. A section of trunk sewer shall be prepared for testing between two structures by plugging the inlet side of the discharge manhole and all openings in the upstream manhole except the discharge opening. All plugs shall be properly braced against the manhole wall to withstand the forces of the test in order to prevent loss in the event of a failure.
2. A section of the trunk sewer prepared as above shall be tested by filling it with water to an elevation 5 feet above the top of pipe at the upstream end of the test section, or 5 feet above the existing groundwater elevation, whichever is greater. The water shall be introduced into the test section at least one hour in advance of the test period and refilled as necessary prior to commencement of the test period to allow the pipe and joint material to become saturated. The loss in water may be determined by measuring the rate of fall of the water level, but the level shall not be allowed to fall more than one foot below the specified head during the test period.
3. For RCP, the pressure shall be maintained for not less than 4 hours and the leakage rate shall not exceed 200 gallons per inch of diameter per mile of pipe for 24 hours (ASTM C 969-02). For VCP, the pressure shall be maintained for not less than one hour and the leakage rate shall not exceed 200 gallons per inch diameter per mile for 24 hours (ASTM C 1091-03a). For DIP, the pressure shall be maintained for not less than one hour and the leakage rate shall not exceed 70 gallons per inch diameter per mile of pipe of 24 hours (AWWA C600-54T).
D. When leakage exceeds the amount allowed by the specifications, the Contractor shall locate the leaks, submit a repair procedure for the Inspector’s review, and make the necessary repairs.
3.05 MANHOLE TESTING:
A. Hydrostatic Testing: Central San may require hydrostatic testing for leakage after installation and prior to backfilling. Prior to hydrostatic testing, all manholes shall be visually inspected. All defects shall be repaired by the Contractor, with non-shrink grout, to the satisfaction of the Inspector. All pipes entering the manhole shall be sealed at a point outside the manhole walls to include testing of the pipe/manhole joints. Safety lines shall be secured to all plugs utilized. The manhole shall be filled with water to a level 2” below the top of the frame. After a period of at least one hour to allow the water level to stabilize, the manhole shall be refilled and the water level shall be checked. The water level shall again be checked after a period of 4 hours. If the water level drops by more
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 19 of 26
than 1”, the leakage shall be considered excessive, and the Contractor shall make necessary repairs and retest the manhole.
B. Vacuum Testing: As an alternative to manhole hydrostatic testing, the Inspector may allow the use of vacuum testing. A vacuum of 10” of mercury shall be drawn on the manhole, the valve on the vacuum line of the test hood closed and the vacuum pump shut off. The manhole shall be deemed to have passed the test if the vacuum drop is less than 1” of mercury during a one-minute test period.
3.06 CCTV INSPECTION:
A. Central San will perform a CCTV inspection of the sanitary sewer upon substantial completion of the work.
1. The Contractor shall coordinate with the Inspector to arrange for an acceptable time to conduct the inspection.
2. Defects discovered by the CCTV inspection shall be corrected and the line reinspected at the Contractor’s cost.
3. If a portion of an entire job is to be CCTV inspected, a separate fee will be due as established by Central San. Inspection fees are payable prior to the date of the partial CCTV inspection.
4. The Contractor shall request CCTV inspection once the following have been completed:
a) Sewer pipelines are installed, backfilled, and compacted. b) Structures are in place, channeling is complete, and pipelines are accessible from structures.
c) All other underground facilities, utility piping, and conduits in the vicinity are installed.
d) For street locations, placement of aggregate base has been completed. e) Pipelines to be inspected have been cleaned and flushed. f) Final pressure test has been completed.
g) Mandrel testing is complete.
B. The procedure outlined below will be repeated until all deficiencies observed by CCTV inspection have been corrected to the satisfaction of Central San.
1. The Contractor shall request Central San to schedule the CCTV inspection. a) If Central San's CCTV crew arrives at the jobsite and the work is not ready or accessible, the Contractor will be billed the cancellation fee payable to Central San prior to the date of rescheduled CCTV inspection. The Contractor shall reschedule CCTV inspection as outlined above.
2. Central San will televise the job.
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 20 of 26
a) If no deficiencies are observed, the work will be considered satisfactory. b) If deficiencies are observed, a recording will be made and defects serious enough to require correction will be identified by the Inspector who will provide written notification. If corrective work is indicated and viewing of the recording is desired, the Contractor shall contact the Inspector to set a time for the viewing.
All corrective work will be subject to approval by Central San. Central San reserves the right to require cleaning and additional leak testing of the repaired pipeline. Those portions of the pipeline where deficiencies have been corrected shall be re-televised. Payment of re-television inspection fees shall be paid to Central San prior to the scheduled date of the inspection.
C. The following observations from CCTV inspections will require correction:
1. Low spot 0.0625 x diameter of pipe or greater (e.g., 0.5” for an 8” pipe).
2. Joint separations (3/4” or greater opening between pipe sections).
3. Cocked joints present in straight runs or on the inside of pipe curves.
4. Chips in pipe ends.
5. Cracked or damaged pipe.
6. Offset joints.
7. Infiltration.
8. Debris or other foreign objects.
9. Other obvious deficiencies.
D. CCTV inspection of the work and the correction of observed defects shall not relieve the Contractor of its responsibility for the warranty period.
END OF SECTION
************************************************************************************************************************ SECTION 33 05 13 - MANHOLES AND STRUCTURES
PART 1 – GENERAL
1. 01 THE REQUIREMENT:
The Contractor shall furnish and install manholes and structures, complete with precast manhole bases or cast-in-place (if approved during Plan Review), pipe connections, barrel and cone components, preformed joint sealant, grade rings, frames, covers and other appurtenances shown on the Plans or specified in this Section.
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 21 of 26
1.02 RELATED WORK SPECIFIED ELSEWHERE:
A. All Related Documents and Sections: Contractor to examine Contract Documents for requirements that directly affect or are affected by Work of this Section. Those Documents and Sections include, but is not limited to, the following:
1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 General Requirements, apply to this Section.
2. All Specification Sections listed in the Table of Contents.
1.03 REFERENCE SPECIFICATIONS, CODES AND STANDARDS:
A. Commercial Standards:
ASTM C 150: Specification for Portland Cement
ASTM C 478: Specification for Precast Reinforced Manhole Sections
1.04 CONTRACTOR SUBMITTALS:
Upon request by Central San, the Contractor shall submit complete shop drawings for all precast manhole bases to Central San and shall receive favorable review prior to ordering the bases.
1.05 QUALITY ASSURANCE:
After installation, the Contractor shall demonstrate that all manholes have been properly installed, level, with tight joints, at the correct elevations and orientations and that the backfilling has been carried out in accordance with the Plans and these Specifications. Vacuum testing of manholes may be required at Central San’s sole discretion.
PART 2 – PRODUCTS
2.01 MATERIALS:
A. Manhole bases may be either cast-in-place or precast. Channels and shelves shall conform to the requirements DWG 19-01 through 19-07. Manhole channels shall be shaped to form a smooth transition of uniform cross-section from inlet pipes to the outlet pipe, both horizontally and vertically.
B. Precast Concrete Components: Only components listed in the Approved Materials List shall be used in the construction of manholes.
1. Precast manhole bases, and barrel and cone sections shall be manufactured by a process that will produce dense homogeneous reinforced concrete of high quality in conformance with ASTM C 478. Cement shall be Type V Portland Cement as specified in ASTM C 150.
2. Precast manhole components shall be designed to support vertical AASHTO H-20 truck loading, plus the weight of soil above the cone section.
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 22 of 26
3. Pipe connections at precast bases shall be pipe bells of the size, material and class of inlet and outlet pipes, integrally cast into the base by the manufacturer.
4. The minimum wall thickness for barrel and cone sections (in inches) shall be calculated by dividing the nominal diameter of the barrel (in inches) by twelve (i.e., D/12).
5. Manhole throats shall be constructed of reinforced concrete grade rings.
C. Preformed plastic sealing gasket for sealing joints between the manhole base, barrel and cone sections shall be as listed in the Approved Materials List.
D. Non-shrink grout shall conform to the requirements Section 03 60 00 – Grout.
E. Castings for manhole frames and covers shall conform to the requirements of Section 05 50 00 - Miscellaneous Metal Work.
F. Primer and sealant tape for sealing exterior joints between precast components shall be as listed in the Approved Materials List.
G. Concrete for cast-in-place manhole and rodding inlet components (bases and top blocks) shall conform to Section 03 30 00 - Cast-In-Place Concrete.
2.02 TEMPORARY COVERS:
Temporary covers for new construction or reconstruction of manholes shall be fabricated as detailed in DWG 19-12.
2.03 TEMPORARY PLUGS:
Temporary plugs shall be of the mechanical expanding type. Pneumatic are not acceptable.
PART 3 – EXECUTION
3.01 GENERAL:
A. Work shall meet or exceed the requirements of these Specifications unless applicable requirements of an agency having jurisdiction (including the terms and conditions of an encroachment permit issued by a city or county) are greater, in which case the greater requirements shall govern.
B. An All-Weather Access Road as specified in this Section is required for access to all structures in off-road locations (e.g., easements).
3.02 INSTALLATION:
A. Temporary Plugs
1. Mechanical expanding-type temporary plugs shall be installed and removed, as specified below, in the presence of an Inspector. Plugs shall be secured by tethering with a ¼” nylon rope attached to the top of a wood 2’x4’ of sufficient length to extend from the shelf to a point in the throat within 6” of the underside of the cover.
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 23 of 26
a) When a manhole exists or a new manhole is constructed at the beginning of a new main extension, a temporary plug shall be installed at the inlet of the new pipe at the existing manhole or new manhole.
b) When a new main extension begins at an existing rodding inlet or stub, a temporary plug shall be installed on the outlet of the first manhole upstream from the beginning of the new main extension.
B. Cast-in-Place Manhole Bases
1. Cast-in-place manhole bases over existing sewers shall be poured against undisturbed native soil, which has been excavated to the dimensions shown on the Plans. For new sewer installations, the cast-in-place manhole base shall be poured over 6” Type 1 Backfill. See DWG 19-01 through 19-08. If the excavation extends beyond the dimensions shown on the Standard Drawings, the Contractor shall construct forms and pour the base to the specified dimensions.
2. If water or soft ground is encountered at the bottom of the excavation, a minimum lift of 9” of coarse-bedding material in a geotextile wrap shall be used as shown on DWG 19-01.
3. A joint forming ring shall be used to form a level joint groove in the manhole base while the concrete is fresh to receive the first precast barrel section. The metal forming ring may be removed as soon as the concrete has set sufficiently to eliminate any slump in the joint groove.
4. Manhole channels shall be shaped to form a smooth transition from inlet pipes to the outlet pipe, both horizontally and vertically.
C. Precast Manhole Bases (on all new main sewer extensions)
1. Precast manhole bases shall be placed to the lines and grades shown on the Plans as an integral part of the pipe laying operation on a minimum thickness of 6” of Type I Bedding and Backfill Material compacted to 95% relative compaction. Where soft ground or water is present, a minimum thickness of 9“ of Coarse Bedding Material in a wrap of geotextile, per the requirements of Section 31 05 19 - Geosynthetics for Earthwork, shall be placed below the course of Type I Bedding and Backfill Material.
2. Inlet and outlet pipe connections at precast bases shall be pipe bells cast into the base by the manufacturer.
3. All precast concrete manholes shall be installed in strict conformance with the manufacturer's written instructions on a well-compacted foundation.
D. Setting Precast Barrel and Cone Sections
1. All joint surfaces of precast manhole bases, barrel and cone sections shall be thoroughly cleaned and dried prior to setting, and shall be sealed with a preformed plastic sealing gasket listed in the Approved Materials List at each joint as follows:
a) Remove the paper wrapper from one side of the gasket, retaining the outside paper in place to protect the gasket and assure against stretching. b) Place the plastic gasket strip in the joint, forming a continuous gasket around the entire circumference of the manhole joint.
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 24 of 26
c) Remove the paper wrapper from the exposed side of the gasket and place the next manhole component.
d) Care shall be taken in the handling of barrel and cone sections after the plastic gasket has been affixed to avoid displacing the gasket or contaminating the joint or gasket with dirt or other foreign material. Any displaced or soiled gaskets shall be removed and replaced.
e) Care shall be taken to properly align the manhole section with the previously set section before it is lowered into position.
f) During cold or wet weather, the joint surfaces shall be heated with hot air until ice, frost, and moisture are removed and surface to be primed is dry and warm.
Hot air shall also be passed over plastic gasket strips immediately prior to attaching them to joint surfaces and immediately prior to setting the section.
E. Manhole frames and covers shall not be set to final grade until the pavement has been completed, unless otherwise approved by Central San. Precast concrete grade rings shall be installed as shown in the Standard Drawings. Paving around the manhole shall be in accordance with local jurisdiction requirements. Openings in manholes shall be protected from construction loads, debris and unauthorized entry.
F. When new piping is installed in existing structures, the Contractor shall accurately position core-drilled openings in the concrete as shown on the job Plans and Standard Drawings or otherwise directed by the Inspector. Openings shall be of sufficient size to permit a final alignment of pipelines and fittings without deflection of any part and to allow adequate space for satisfactory placement of mechanical seals or packing with nonshrink grout where the pipe passes through the wall to ensure the resulting structure is watertight. Before placing the non-shrink grout, concrete surfaces shall be sandblasted, thoroughly cleaned of sand and any other foreign matter, and coated with epoxy bonding compound. After connection of the new inlet pipe, the Contractor shall re-channel the inside of the existing manhole base to provide a smooth flow channel to the new exit pipe.
G. The throat shall be constructed using appropriately sized reinforced concrete grade rings to bring the manhole cover to finished grade surface. No plastic sealing gaskets shall be used for jointing grade or extension rings.
H. Manhole top blocks shall be poured against forms constructed to the specified dimensions shown on DWG 19-01.
I. All manholes located on slopes steeper than 3:1 (horizontal to vertical) in easement areas shall be constructed with a reinforced concrete, reinforced concrete masonry unit or interlocking masonry unit retaining wall as shown on DWG 19-11.
J. All manholes shall be tested in accordance with Section 33 01 30.11 - Inspection of Sewers.
K. Temporary covers shall be used during construction until permanent frames and covers are installed.
3.03 RECONSTRUCTION OF EXISTING STRUCTURES:
A. General
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 25 of 26
1. Reconstruction work on any particular structure shall be diligently prosecuted so as to be completed within 3 calendar days after work is begun on that particular structure.
The Contractor shall provide continuous access for Central San maintenance forces to the structure at all times.
2. When removing existing structures, the Contractor shall take precautions to ensure that no foreign material enters the structure or the downstream system. Before any work is started, the base shall be covered with a plywood (“false bottom”) as shown on DWG 19-13, and then the false bottom shall be covered with a drop cloth of heavy canvas. The drop cloth and false bottom shall be kept in place during the work to catch debris, and upon completion, shall be removed with the collected debris. No debris shall enter the downstream system or be allowed to remain in the manhole.
B. Structure Adjustments and Repairs
1. All workmanship and materials for structure adjustments shall conform to the requirements of these Specifications. In the case of existing brick or cast-in-place concrete structures, repair or adjustments shall be accomplished with materials in-kind or with precast elements as detailed on the Plans.
2. Existing structure precast elements, adjustment rings, frames, and covers removed for adjustments and/or repairs may be reinstalled only when such undamaged items are permitted by the Inspector for reuse.
3. Manhole adjustments shall be accomplished by one of the methods specified below or as shown on the Plans:
a) Upward adjustments of manholes to finish grade surface may be accomplished with reinforced concrete grade rings, formed concrete and/or a single cast iron extension ring when the adjusted manhole throat will not exceed 12” in height. In no case shall multiple cast iron extension rings be used in adjustments. When adjustments are made that position the bottom of the cast iron manhole frame above the existing concrete top block, the top block shall be reconstructed in accordance with the requirements of DWG 19-01 through 19-08. b) Whenever upward adjustment of manholes would result in a completed manhole throat section exceeding 12” in height, the upper manhole section, including the top block and cone section, shall be removed and the adjustment shall be made by reconstructing the structure using manhole barrel and cone sections, grade rings and frames and covers in accordance with the requirements of these Specifications and DWG 19-01 through 19-08.
c) Downward adjustments of manholes shall be accomplished by removal of existing grade or extension rings and cone and barrel sections as required, and reconstructing the structure using manhole barrel and cone sections, grade rings and frames and covers in accordance with the requirements of these Specifications and DWG 19-01 through 19- 08.
4. Rodding inlet adjustments shall be accomplished by one of the methods specified below or as detailed on the Plans:
a) Upward adjustments of rodding inlets shall be accomplished with formed concrete or cast-iron extension rings where the extension will not exceed 8”, including any previous adjustments. When adjustments are made that position the bottom of the cast iron frame above the existing concrete top block, the top
SECTION 33 30 00 SANITARY SEWER UTILITIES
SANITARY SEWER UTILITIES 33 30 00 - 26 of 26
block shall be reconstructed in accordance with the requirements of these Specifications and DWG 19-14.
b) Upward adjustments of rodding inlets exceeding 8” shall be accomplished by removing the structure’s frame, cover, and top block, and reconstructing the structure in accordance with the requirements of these Specifications and DWG 19-14. Pipe used for such adjustments shall be as required for pipeline repair and shall be installed to extend the line and grade of the existing pipe. c) Downward adjustments of rodding inlets shall be accomplished by removal and reconstructions of the entire upper section of the structure including the top block.
END OF SECTION
300 Seminary Avenue • Ukiah • CA • 95482-5400
Phone: (707)463-6200 · Fax: (707)463-6204 ·www.cityofukiah.com 300 Seminary Av., Ukiah CA 95482
Hydrant Flow Test Report
Name: Corner of Clay/Main
Address:
Tested by: Robby Hulbert Date: 8/8/2023
Requested By: Daniel Flores Time: 7:00 AM
Location of test: Clay/Main
Hydrant ID Number: 287
Residual hydrant location: 506 Main St
Flow hydrant(s) Location: SW Corner of Clay/Main
Static pressure (residual hydrant): 100 psi Hydrant 288 Residual pressure (residual hydrant): 96 psi
Nozzle size (flow hydrant): 2 1/2
Hydrant pressure (flow hydrant): 75 psi
Projected hydrant flow: 1455 GPM
Remarks and comments:
Project: Ukiah B of A Remodel Client: City of Ukiah
City: Ukiah, CA
Project No.: Date: December 13, 2024
Building Size: 9,201 SF
CSI DESCRIPTION UNIT PRICE QTY COST
Division 2 - Site Construction
Temporary Controls, Fencing & Signage ls $5,000.00 1 $5,000 Site demolition - Asphalt Pavement sf $7.00 2400 $16,800 Site demolition - Ramp sf $13.00 340 $4,420
Site demolition - Concrete Sidewalk sf $12.00 390 $4,680 Site demolition - Utility trench lf $40.00 300 $12,000
Site demolition - Landscape ls $2,500.00 1 $2,500
Site demolition - Electrical Handhole ls $1,000.00 1 $1,000 Site demolition - Subgrade water valve ls $1,000.00 1 $1,000 Site demolition - ramp landing & stair ls $3,500.00 1 $3,500 Site demolition - generator pad sf $8.00 250 $2,000
Site demolition - Misc ls $2,000.00 1 $2,000
SUBTOTAL $54,900
Division 3 - Concrete
Concrete Reinforcement - Elevator Pit ls $1,000.00 1 $1,000 Concrete Reinforcement - Slab-on-Gade ls $12,500.00 1 $12,500 Concrete - Elevator Pit sf $50.00 100 $5,000
SUBTOTAL $18,500
Division 5 - Metals
Metal Fabrications - Misc. ls $3,000.00 1 $3,000
Metal Fabrications - Stair Handrails lf $110.00 76 $8,360 SUBTOTAL $11,360
Division 6 - Wood & Plastics
Structural Framing - Posts 6x6 ea $500.00 9 $4,500
Structural Framing - PSL Headers ls $15,000.00 1 $15,000 Structural Framing - Standard Headers ls $3,000.00 1 $3,000 Structural Framing - Wall attachments ea $1,850.00 12 $22,200 Rough & Finish Carpentry - Partitions/Framing ls $13,500.00 1 $13,500 Rough & Finish Carpentry - Misc ls $13,500.00 1 $13,500 Interior Architectural Woodwork - Counter lf $725.00 94 $68,150 Interior Architectural Woodwork - Lactation Rm ls $3,500.00 1 $3,500 Interior Architectural Woodwork - Break Rm ls $7,500.00 1 $7,500 SUBTOTAL $150,850
Division 7 - Thermal & Moisture Protection
Roof Patch - penthouse ls $7,500.00 1 $7,500
Interior Acoustical Insulation sf $3.75 9201 $34,504
Roof and Deck Insulation ls $1,250.00 1 $1,250
Sealants ls $5,000.00 1 $5,000
SUBTOTAL $48,254
Attachment 3
Project: Ukiah B of A Remodel Client: City of Ukiah
City: Ukiah, CA
Project No.: Date: December 13, 2024
Building Size: 9,201 SF
CSI DESCRIPTION UNIT PRICE QTY COST
Division 8 - Doors & Windows
Wood Door & HM Frame & Hardware ea $3,800.00 18 $68,400 Wood Door & Aluminum Frame & Hardware ea $4,250.00 13 $55,250 HM Door & HM Frame & Hardware ea $3,300.00 3 $9,900
Wood Door & Other Frame & Hardware ea $4,000.00 4 $16,000 Storefront Misc - Interior ls $5,000.00 1 $5,000
Storefront Misc - Exterior ls $2,500.00 1 $2,500
Access Doors and Frames ea $3,800.00 3 $11,400
Aluminum Door & Frame & Hardware ea $5,000.00 3 $15,000 Windows ea $8,000.00 7 $56,000
Sliding Automatic Entrances ea $17,500.00 1 $17,500
Fiberglass Sandwich Panel Skylights sf $140.00 400 $56,000 SUBTOTAL $312,950
Division 9 - Finishes
Non-Structural Metal Framing - Misc. ls $10,000.00 1 $10,000 New partitions - Gyp board lf $330.00 275 $90,750
New partitions - Insulation lf $24.00 275 $6,600
Gypsum Board - interior outside walls lf $40.00 160 $6,400 Gypsum Board - Ceilings sf $14.00 1440 $20,160
Porcelain Tile - Unisex Tlts & Vestibule sf $36.00 3360 $120,960 Acoustical Ceilings sf $17.00 6981 $118,677
Resilient Flooring sf $13.00 4100 $53,300
Resilient Base lf $3.50 1800 $6,300
Static Dissipative Resilient Flooring - IT Room sf $28.00 207 $5,796 Carpet Tile sf $15.00 2680 $40,200
Painting,Interior Walls sf $6.50 8000 $52,000
Painting, Doors and Frames ea $225.00 38 $8,550
Painting, Misc ls $2,500.00 1 $2,500
SUBTOTAL $542,193
Division 10 - Specialties
Signage Interior ls $17,500.00 1 $17,500
Signage Exterior ls $4,000.00 1 $4,000
Folding Glass Partitions ls $60,000.00 1 $60,000
Wall Protection - Corner Guards ls $2,500.00 1 $2,500
Fire Extinguisher Cabinet w/Extinguisher ea $1,500.00 6 $9,000 Grab Bars ea $400.00 12 $4,800
Mirrors ea $750.00 6 $4,500
Soap Dispenser ea $300.00 6 $1,800
Sanitary Napkin Disposal ea $300.00 6 $1,800
Toilet Seat Cover Dispenser ea $300.00 6 $1,800
Toilet Tissue Dispenser ea $300.00 6 $1,800
Towel dispenser waste receptacle ea $350.00 6 $2,100
Robe HooK ea $100.00 6 $600
Diaper Changing Station ea $3,500.00 2 $7,000
SUBTOTAL $119,200
Project: Ukiah B of A Remodel Client: City of Ukiah
City: Ukiah, CA
Project No.: Date: December 13, 2024
Building Size: 9,201 SF
CSI DESCRIPTION UNIT PRICE QTY COST
Division 13 - Special Construction
Seismic Restraint for Piping and Equipment sf $3.00 9201 $27,603 SUBTOTAL $27,603
Division 14 - Conveying Systems
Hydraulic Elevator ls $410,000.00 1 $410,000
Elevator penthouse ls $12,500.00 1 $12,500
SUBTOTAL $410,000
Division 21 - Fire Suppression
Fire Riser ls $13,500.00 1 $13,500
Wet-Pipe Sprinkler Systems sf $10.00 9201 $92,010
Total $105,510
Division 22 - Plumbing
General Requirements of Plumbing and HVAC ls $10,000.00 1 $10,000 Siesmic Controls ls $5,000.00 1 $5,000
Demo - Existing plumbing fixtures ls $8,500.00 1 $8,500 Sanitary Sewer - Floor trench ls $9,000.00 1 $9,000
3" Sanitary Line lf $130.00 50 $6,500
2" Sanitary line lf $110.00 128 $14,080
4" Sanitary line lf $150.00 110 $16,500
Plumbing Valves ls $9,000.00 1 $9,000
Domestic Water Piping lf $75.00 780 $58,500
Vent piping ls $17,500.00 1 $17,500
Water Closets ea $2,800.00 6 $16,800
Lavatories ea $1,695.00 6 $10,170
Lactation Rm Sinks (Single) ea $1,375.00 1 $1,375
Break Room Sinks (Double) ea $1,375.00 1 $1,375
Drinking Fountain (Dual Height Bottle Fill) ea $2,000.00 2 $4,000 Floor Drains at Toilets ea $800.00 6 $4,800
Mop Sink ea $1,770.00 1 $1,770
Urinals ea $2,800.00 2 $5,600
SUBTOTAL $200,470
Division 23 - Mechanical
Testing & Balancing ls $10,000.00 1 $10,000
Ductwork - large lf $95.00 445 $42,275
Ductwork - small lf $68.00 830 $56,440
Refrigerant Piping ls $6,500.00 1 $6,500
New ductless condenser unit ls $7,000.00 1 $7,000
Minisplit unit at IT ls $8,500.00 1 $8,500
Air Duct Accessories ls $7,500.00 1 $7,500
Grilles, Registers and Diffusers ls $15,000.00 1 $15,000 SUBTOTAL $153,215
Project: Ukiah B of A Remodel Client: City of Ukiah
City: Ukiah, CA
Project No.: Date: December 13, 2024
Building Size: 9,201 SF
CSI DESCRIPTION UNIT PRICE QTY COST
Division 26 - Electrical
Common Work Results for Electrical ls $15,000.00 1 $15,000 Low Voltage ls $5,000.00 1 $5,000
Grounding & Bonding ls $8,000.00 1 $8,000
Hangers & Supports ls $12,500.00 1 $12,500
Raceways & Boxes sf $3.50 9201 $32,204
HVAC and Control Wiring ls $25,000.00 1 $25,000
Wiring - general ls $60,000.00 1 $60,000
Lighting Controls ls $15,000.00 1 $15,000
Panelboards - New ea $4,000.00 3 $12,000
Automatic Transfer Switch ls $40,000.00 1 $40,000
Interior Lighting sf $17.00 9201 $156,417
Exterior Lighting ls $5,000.00 1 $5,000
SUBTOTAL $386,121
Division 28 - Electronic Safety and Security
Physical Access Control System ls $35,000.00 1 $35,000
Access Control - Card Readers ea $2,000.00 10 $20,000
Access Control - System wiring ls $55,000.00 1 $55,000
SUBTOTAL $110,000
Division 31 - Earthwork
Site Grading ls $8,500.00 1 $8,500
SUBTOTAL $8,500
Division 32 - Exterior Improvements
Site Improvements - Concrete Curbs lf $90.00 200 $18,000 Handrails/Guardrails lf $115.00 81 $9,315
Sign Posts ea $3,000.00 3 $9,000
Signage ls $1,500.00 1 $1,500
Truncated Domes ls $1,000.00 1 $1,000
Site Improvements - Generator Pad sf $15.00 250 $3,750
Site Improvements - Concrete ADA Stalls sf $50.00 470 $23,500 Site Improvements - Concrete - Sidewalk sf $50.00 981 $49,050 Site Improvements - Asphalt Paving sf $15.00 760 $11,400 Site Improvements - Asphalt Utility Trench sf $15.00 800 $12,000 Site Improvements - Wheel Stops ea $1,500.00 6 $9,000
Site Improvements - Pavement Markings ls $2,000.00 1 $2,000 Site Improvements - Landscape ls $2,000.00 1 $2,000
SUBTOTAL $151,515
Project: Ukiah B of A Remodel Client: City of Ukiah
City: Ukiah, CA
Project No.: Date: December 13, 2024
Building Size: 9,201 SF
CSI DESCRIPTION UNIT PRICE QTY COST
Division 33 - Utility
Utility Trench - New Handhole ea $5,000.00 1 $5,000
Demo - Light and Pole ea $2,500.00 1 $2,500
Exterior Site Lighting - replace ea $3,000.00 2 $6,000
Exterior Site Lighting - new with pole ea $18,500.00 1 $18,500 Exterior Site Lighting - new with pole at ADA ea $11,500.00 1 $11,500 Utility Trench lf $125.00 300 $37,500
Utility Trench - Sanitary Sewer pipe lf $105.00 200 $21,000 Primary service connection ls $40,000.00 1 $40,000
Generator ls $125,000.00 1 $125,000
Generator feeder lf $120.00 100 $12,000
Utilities - Sewer - Coupling & Fittings ls $5,000.00 1 $5,000 SUBTOTAL $284,000
Construction Cost Subtotal $3,095,140
Division 1 - General Requirements & Fees
General Conditions % 10.00% $309,514
Bond, Insurance & Permit % 2.00% $61,903
Contingency % 10.00% $309,514
SUBTOTAL $680,931
Construction Cost Total $3,776,071
Summary Subtotal
Division 1 - General Requirements & Fees $680,931 74.01 Division 2 - Site Construction $54,900 5.97
Division 3 - Concrete $18,500 2.01
Division 5 - Metals $11,360 1.23
Division 6 - Wood & Plastics $150,850 16.39
Division 7 - Thermal & Moisture Protection $48,254 5.24 Division 8 - Doors & Windows $312,950 34.01
Division 9 - Finishes $542,193 58.93
Division 10 - Specialties $119,200 12.96
Division 13 - Special Construction $27,603 3.00
Division 14 - Conveying Systems $410,000 44.56
Division 21 - Fire Suppression $105,510 11.47
Division 22 - Plumbing $200,470 21.79
Division 23 - Mechanical $153,215 16.65
Division 26 - Electrical $386,121 41.97
Division 28 - Electronic Safety and Security $110,000 11.96 Division 31 - Earthwork $8,500 0.92
Division 32 - Exterior Improvements $151,515 16.47
Division 33 - Utility $284,000 30.87
TOTAL $3,776,071 $ 410.40 per SF
Agenda Item No: 8.f.
MEETING DATE/TIME: 7/16/2025
ITEM NO: 2025-822
AGENDA SUMMARY REPORT
SUBJECT: Adoption of a Resolution Authorizing an Application to the California Climate Investments and Proposition 4 Department of Forestry and Fire Protection (CAL FIRE) Wildfire Prevention Program.
DEPARTMENT: City Manager /
Admin PREPARED BY: Traci Boyl, Senior Management Analyst PRESENTER: Traci Boyl, Sr. Management Analyst
ATTACHMENTS:
1. FY 2526 Wildfire Prevention Grants GUIDELINES CCI-Prop4
2. Resolution Cal Fire Wildfire Prevention Program
Summary: The City Council will consider authorizing a grant application to the California Climate Investments and Proposition 4 Department of Forestry and Fire Protection (CAL FIRE) Wildfire Prevention Grant Program for hazardous fuels reduction work within the Ukiah Valley Fire District.
Background: The CAL FIRE Community Wildfire Defense Grant (Attachment 1) provides funding to help communities plan for and mitigate wildfire risks. The grant offers up to $950,000 with no local match requirement and includes a three-year period of performance. The application deadline is August 6, 2025.
This grant complements the existing USDA grant that funded the hiring of a dedicated fuels crew by providing the additional necessary equipment, planning documents to prioritize and coordinate ongoing projects, related CEQA, and providing important education and outreach pieces.
Discussion: This funding will allow the City to maintain and expand wildfire hazard mitigation efforts. Priority activities include maintaining the existing fire break in the western hills area now within city limits, supporting work beyond the original scope of the fuels crew grant, and filling operational gaps. The grant will also fund the purchase of a masticator, truck, trailer, and additional crew equipment. Planning efforts will include updates to the Community Wildfire Protection Plan (CWPP), necessary CEQA compliance, and community education and outreach initiatives.
Staff recommends Council adopt the resolution (Attachment 2) to participate in the Community Wildfire Defense Grant application. This is a competitive grant application, but it requires no matching funds. Therefore, there is no fiscal impact from the application, and the Council would have an opportunity to provide direction before accepting any potential grant award.
Recommended Action: Adopt a resolution authorizing an application to the California Climate Investments and Proposition 4 Department of Forestry and Fire Protection (CAL FIRE) Wildfire Prevention Program.
BUDGET AMENDMENT REQUIRED: N/A
CURRENT BUDGET AMOUNT: N/A
PROPOSED BUDGET AMOUNT: N/A
FINANCING SOURCE: N/A
REVENUE: Yes/No GRANT: Yes/No
PREVIOUS CONTRACT/PURCHASE ORDER NO.: N/A
COORDINATED WITH: Doug Hutchison, Fire Chief; Justin Buckingham, Battalion Chief; Jim Robbins, Housing and Grants Manager
STRATEGIC PLAN (SP):SP 1B - Provide services that support a high quality of life for all residents, including fostering diverse, inclusive, sustainable, and accessible neighborhoods.
CLIMATE INITIATIVES (CI): 10a – Protect from dangerous emission by preventing fires.
GENERAL PLAN ELEMENTS (GP): GP-A6 - Safety Element
California Climate Investments
And Proposition 4
Department of Forestry and Fire Protection
(CAL FIRE)
Wildfire Prevention Program
Grant Guidelines
FY 2025-2026
June 25, 2025
Attachment 1
pg. 2
Table of Contents
I. Introduction..................................................................................................................................................4 Wildfire Prevention GrantsProgram Summary ........................................................................................4 Qualifying Project Types and Activities................................................................................................5 Hazardous Fuels Reduction...................................................................................................................6 Wildfire Prevention Planning......................................................................................................................6 Wildfire Prevention Education..............................................................................................................6 II. Eligibility, Conditions, andImportant Points...............................................................................................7 Conditions and Important points................................................................................................................. 10 Prevailing Wage Requirements............................................................................................................... 16 Greenhouse Gas (GHG)Emissions Requirements.................................................................................. 16 Prop 4 Reporting Requirements.........................................................................................................17 California Climate Investments (CCI)Reporting Requirements................................................................ 18 III. Grant Application Review and Evaluation Factors................................................................................18 Review Process ........................................................................................................................................ 18 Evaluation Factors(Ranking Criteria)...................................................................................................... 19 Application Process andProject Administration.................................................................................... 21 Stage 1 - Project Application ................................................................................................................... 21 Stage 2 - Grant Application Reviewand Selection ..................................................................................... 23 Stage 3 - Grants Awarded........................................................................................................................ 23 Stage 4 – CompletedGrant Agreements................................................................................................ 24 Project Amendments, Modifications,and Terminations........................................................................... 24 Accounting Requirements.................................................................................................................. 25 Loss of Funding.......................................................................................................................................... 25 Prop 4 Indirect Cost Rates............................................................................................................ 26 Project Costs....................................................................................................................................... 27 Payment of Grant Funds.................................................................................................................................30
pg. 3
State Conflict of Interest Laws................................................................................................................. 30 Advance Payments............................................................................................................................. 32 State Audit.......................................................................................................................................... 32 Explanation of Terms.............................................................................................................................................33 Appendix A – Environmental Compliance for CAL FIRE Projects ................................................................37 Appendix B – Sample Resolution...............................................................................................................40 Appendix C – Invoice .......................................................................................................................................41 Appendix D – State of California Standard Required Forms...........................................................................42 Appendix E – CalMAPPER (AwardedGrants Only) .........................................................................................42 Appendix F – Low-Income andDisadvantaged Communities.....................................................................42 Appendix G – PDFProject Map....................................................................................................................................45 Appendix H – Justification for indirect cost rate above 12%..............................................................................45 Appendix I –Application Package ...................................................................................................................46 Appendix J – Additional Resources............................................................................................................47 Appendix K – Calculating Interest onAdvance Payments..............................................................................48
pg. 4
I. INTRODUCTION
This grant guideline includes information about the California Department of Forestry and Fire Protection (CAL FIRE) Wildfire Prevention (WP) Grants Program. The Program is funded by Capand-Trade auction proceeds appropriated by the California Legislature to agencies that administer California Climate Investments (CCI).
Up to $135 million is being allocated to CAL FIRE’s WP Grants Program in Fiscal Year 2025- 2026 from the CCI Greenhouse Gas Reduction Fund (GGRF) and the Safe Drinking Water, Wildfire Prevention, Drought Preparedness, and Clean Air Bond Act of 2024 (Proposition 4).
For information about CAL FIRE’s other CCI programs, please visit CAL FIRE Grants.
WILDFIRE PREVENTION GRANTS PROGRAM SUMMARY
CAL FIRE’s WP Grants Program provides funding for wildfire prevention projects and activities in and near wildfire-threatened communities that focus on increasing the protection of people, structures, and communities. Funded activities include Hazardous Fuels Reduction, Wildfire Prevention Planning, and Wildfire Prevention Education with an emphasis on improving public health and safety while reducing greenhouse gas emissions.
California’s Strategic Fire Plan serves as a roadmap for project development. Projects are evaluated based on the overall benefit to reduce the threat of wildfires to people, structures, and communities. CAL FIRE will consider the wildfire hazards and risks to an area, the geographic balance of projects, and whether the project is complementary to other wildfire prevention or forest health activities when awarding grants. Projects benefiting disadvantaged communities or low-income communities, as defined by Health and Safety Code section 39713, projects that demonstrate a carbon benefit by reducing greenhouse gas emissions, and projects that contain matching funds will receive additional priority. Projects are selected on a competitive basis, and consecutive awards are not guaranteed. Disadvantaged and low-income communities can be determined using the process in Appendix F. Projects that demonstrate that they are providing maintenance of existing fuels reduction projects paid for by CAL FIRE or any other funding sources (i.e., other state funds, federal funds, or private funds) will also receive priority. Projects conducted by any local governmental entity qualified to perform defensible space assessments pursuant to Section 4291.5 in very high and high fire hazard severity zones, as identified by the State Fire Marshal pursuant to Section 51178 of the Government Code or Article 9 (commencing with Section 4201) of this chapter or by a local agency pursuant to Section 51179 of the Government Code, will receive priority if they utilize the common reporting platform created pursuant to subdivision (c) of Section 4291.5 to report that information.
CAL FIRE will provide technical expertise and management oversight of grants but may not be the primary agency or applicant for a project. CAL FIRE reserves the right to fund projects in
pg. 5
total or in part, whichever best serves the objectives of the Wildfire Prevention Grants Program. Project applicants that are selected to receive partial funding will be provided with additional information on their revised funding amount, project performance period, and any other changes to their application, as needed.
PROPOSITION 4 BACKGROUND
In November of 2024, California voters approved Proposition 4, a law proposed by Senate Bill 867, to fund water, climate, wildfire, and natural resource projects across the state of California. Proposition 4, among other things, will allocate $1.5 billion for wildfire prevention, including reducing community wildfire risk and restoring the health and resilience of forests and landscapes. (Pub. Resources Code, section 91500, et seq.) Of this amount, $185 million was made available to CAL FIRE Wildfire Prevention Grants as follows: “for projects that prevent wildfires, increase resilience, maintain existing wildfire risk reduction projects, reduce the risk of wildfires to communities, or increase home or community hardening.” (Pub. Resources Code, section 91520, subd. (h).) Projects shall benefit disadvantaged communities, severely disadvantaged communities, or vulnerable populations. To the extent feasible, a project whose application includes the use of services of the California Conservation Corps or certified community conservation corps, as defined in Section 14507.5, shall be given preference for receipt of a grant under this division (Pub. Resources Code, section 91500, et seq.). In addition, projects that leverage private, federal, and local funding or produce the greatest public benefit will also receive priority (Pub. Resources Code, section 90050, et seq.). Proposition 4 requires that at least 40 percent of the total funds available shall be allocated for projects that provide meaningful and direct benefits to vulnerable populations or disadvantaged communities. Of this 40 percent, at least 10 percent of the total funds available shall be allocated for projects that provide meaningful and direct benefits to severely disadvantaged communities.
GOVERNOR’ S EXECUTIVE ORDER N-25-25
In addition, on March 1, 2025, Governor Newsom signed Executive Order N-25-25 to ensure that wildfire-safety projects funded under Assembly Bill 100 benefit from streamlining under the Statewide Fuels Reduction Environmental Protection Plan (EPP) created in response to the Emergency Proclamation issued on March 1, 2025. The Governor’s Forest Management Task Force identified these priorities in California’s Wildfire and Forest Resilience Action Plan.
QUALIFYING PROJECT TYPES AND ACTIVITIES FOR PROPOSITION 4 The WP Grants Program can only fund Hazardous Fuels Reduction projects for Proposition 4.
Please see the Hazardous Fuels Reduction project and activities below for examples.
pg. 6
QUALIFYING PROJECT TYPES AND ACTIVITIES FOR CCI
The WP Grants Program funds three types of activities: Hazardous Fuels Reduction, Wildfire Prevention Planning, and Wildfire Prevention Education. Below are some examples of qualifying projects and activities:
HAZARDOUS FUELS REDUCTION
• Vegetation clearance in critical locationsto reduce wildfire intensity and rate of spread.
• Creation or maintenance of fuel breaks in strategic locations, as identified in CAL FIRE Unit Fire Plans, a Community Wildfire Protection Plan, or similar strategic planning document.
• Maintenance of existing fuels reduction projects paid for by CAL FIRE or any other funding sources (i.e., other state funds, federal funds, or private funds). • Removal of ladder fuels to reduce the risk of crown fires. • Creation of community-level wildfire prevention programs,such as community chipping days, roadside chipping, and green waste bin programs. • Selective tree removal (thinning) to improveforest health to withstand wildfire. • Modification of vegetation adjacent to roadsto improve public safety for egress of evacuating residents and ingress of responding emergency personnel. • Reduction of fuel loading around critical infrastructure to maintain continuity of government and other critical services.
• Projects to improve compliance with defensible space requirements as required by Public Resources Code Section 4291 (Projects eligible for CCI funds are low-income, disabled, or elderly households per CA requirements).
• Seasonal and temporary prescribed grazing using temporary infrastructure consistent with increasing the protection of people, structures, and communities.
WILDFIRE PREVENTION PLANNING
• Wildfire risk or related mapping
• Creation or update of strategic wildfire planning documents, suchas:
o Evacuation plans
o Community Wildfire Protection Plans(CWPP)
o Local Hazard Mitigation Plans
o Safety Elements
o Wildfire Prevention or Mitigation Plans
WILDFIRE PREVENTION EDUCATION
• Development and implementation of public education and outreachprograms.
pg. 7
• Workshops, meetings, materials creation, and other educational activities with the purpose of increasing knowledge and awareness of information that could be used to reduce the total number of wildfires, acres burned, and structureslost. • To educate the public on making homes and communities more wildfire resilient, including defensible space training.
Activities are subject to CAL FIRE approval.
II. ELIGIBILITY, CONDITIONS, AND IMPORTANT POINTS
ELIGIBILITY FOR PROPOSITION 4
• State Agencies
• Native American Tribes
• Joint Powers Authorities (JPAs) if the entities involved areeligible applicants. • Special districts
o Fire protection districts.
o Community services districts
o Water districts
o Resource conservation districts
• Local agencies, including:
o City, county, or city and county
• Fire Safe Councils with a 501(c)(3) designation.
• Other qualified non-profit organizations with a 501(c)(3)designation
ELIGIBILITY FOR CCI FUNDS
• State Agencies
• Federal Agencies
• Native American Tribes
• Joint Powers Authorities (JPAs) if the entities involved areeligible applicants. • Special districts
o Fire protection districts.
o Community services districts
o Water districts
o Resource conservation districts
• Local agencies, including:
o City, county, or city and county
• Certified local conservation corps
pg. 8
• Fire Safe Councils with a 501(c)(3) designation.
• Other qualified non-profit organizations with a 501(c)(3)designation In situations where a local government has contracted with CAL FIRE for fire protection services, CAL FIRE is considered a local government for purposes of this grant program.
If an applicant has applied for a 501(c)(3) status at the time of application, that is sufficient.
Applicants will have to provide the official 501(c)(3) status prior to execution of the grant agreement.
LIMITEDWAIVERSOF SOVEREIGN IMMUNITY FORNATIVE AMERICAN TRIBES Federally recognized tribes are sovereign nations with special legal status. These projects may require limited waivers of sovereign immunity when the primary grantee (who signs the grant agreement contract) is a federally recognized tribe. This will be determined on a case-by-case basis and dependent on the type and scope of the project. The grant agreement will identify these important terms and conditions, including the potential limited waiver of sovereign immunity, to ensure the grant agreement may be enforced in case of default.
CAL FIRE will avoid seeking a limited waiver of sovereign immunity when possible and will strive to notify applicants early in the grant application review process if it is anticipated a limited waiver of sovereign immunity will be necessary. CAL FIRE is committed to working collaboratively with California Native American tribes on tailoring limited waiver of sovereign immunity terms to support tribal priorities while also meeting the state’s legal obligations.
CAL FIRE will conduct a risk analysis of all projects that may involve limited waivers of sovereign immunity. In general, limited waivers of sovereign immunity will be required for projects with:
• Advance funds
• High-risk implementation projects, which may include fuels reduction, prescribed burning, cultural burning, ceremonial or other use of fire
• Organizations without demonstrated reliability in sound financial management For questions regarding sovereign immunity, please reach out to program by emailing [email protected], who may refer you to discuss specifics with the appropriate person at CAL FIRE Legal.
Applicants may not be one of the following:
• A privately held for-profit company or corporation.
• Individual or private landowners.
• Homeowners’ associations or other associations unlessthey have 501(c)(3) non- profit status.
pg. 9
ELIGIBLE COSTS INCLUDE, BUT ARE NOT LIMITED TO:
• Removal of dead, dying, diseased, or otherwise hazardous trees posing an imminent threat to public rights-of-way and public infrastructure, which may include trees on private property.
• Contracted tree removal, transportation, holding site fees, anddisposal. • Costs that are necessary and prudent to the accomplishment of the project,e.g., o Project equipment not to exceed a cumulative total of $750,000. o Project supplies (supplies include items under $5,000 per unit cost).
Chainsaws are an example of a supply item and are not considered equipment.
o Fuel and Maintenance
o CEQA/NEPA Costs
• All equipment purchases must be pre-approved. All pre-approved equipment purchases are owned by the grantee. Equipment cannot be purchased by subcontractors and billed to the grantee for reimbursement.
INELIGIBLE COSTS INCLUDE, BUT ARE NOT LIMITED TO:
• Removal of non-hazardous trees that do not pose an imminent threat topublic health and safety.
• Costs associated with the improvement of landscaping, includingplanting. • Costs that are not directly associated with the project. • Costs already funded or budgeted through another source (i.e.,supplanting) • Income, fees, revenues, or wages lost or voluntarily waived by a local agency. • Activities or costs associated with permanentinfrastructure. • Costs incurred before or after the project performanceperiod. • Cost of preparing a grant and application.
• Late fees, penalties, and bank fees.
• Gifts or gift cards. If uncertain, contact your Region.
NON-QUALIFYING PROJECT TYPES AND ACTIVITIES INCLUDE, BUT ARE NOT LIMITED TO:
• Purchase of capital equipment with a cumulative total of more than$750,000 • Purchase of capital equipment without demonstrating how the equipment will be utilized.
All equipment purchases must be pre-approved. All pre-approved equipment purchases are owned by the grantee. Equipment cannot be purchased by subcontractors and billed to the grantee for reimbursement.
• Installation, creation, upgrade, or maintenance of fire protection features,such as roads, bridges, structures, water storage facilities, or other permanent infrastructure. • Projects or activities utilizing CAL FIRE staff without corresponding reimbursements or requests seeking funding for services already provided by CAL FIRE.
pg. 10
CONDITIONS AND IMPORTANT POINTS
1. The recommended funding amount is $950,000 orless.
2. Grants can be made only to “eligible” applicants.
3. Projects must provide benefits to habitable structures and people in and near wildfire threatened communities.
4. Projects utilizing partners must provide a letter of commitment from the partner entity as proof that they have contacted the entity, the entity has the required resources (if needed) to commit toward the project, and the entity supports theproject.
5. Qualifying projects and activities are limited to those where the proposed project or activity addresses the hazards and risks to wildfire threatened communities that focus on increasing the protection of people, structures, and communities.
6. Applicants must consider greenhouse gas emissions of project activities and plan to reduce emissions as much as possible during project activities.
7. Grantees must have and demonstrate to CAL FIRE the ability to plan, administer, and complete the grant project.
8. For some projects, the grantee may be required to prepare a California Environmental Quality Act (CEQA) or National Environmental Policy Act (NEPA) document. Projects requiring CEQA/NEPA review are required to provide documented compliance within 12 months from the grant execution. CEQA/NEPA compliance must begin immediately after grant execution. Documented CEQA/NEPA compliance is required prior to commencing any ground disturbing activity.
9. A Registered Professional Forester (RPF) must design and oversee any fuel “forestry” projects, as defined in Public Resources Code (PRC) § 753, proposed on a “forested landscape,” as defined in PRC § 754. The RPF must conduct at least one site visit during active project operations to ensure vegetation removal is being conducted according to the prescription. An RPF is not required to provide the general project information required in the Scope of Work during the grant application phase, but the applicant must explain how CEQA or NEPA compliance will be met and describe RPF involvement in the Project Scope of Work and include this cost in the budget, if applicable. a) PRC §753 - “Forestry,” as used in this article, refers to the science and practice of managing forested landscapes and the treatment of the forest cover in general, and includes, among other things, the application of scientific knowledge and forestry principles in the fields of fuels management and forest protection, timber growing and utilization, forest inventories, forest economics, forest valuation and
pg. 11
finance, and the evaluation and mitigation of impacts from forestry activities on watershed and scenic values, to achieve the purposes of this article. The practice of forestry applies only to those activities undertaken on forested landscapes.
The professions specified in Section 772 are not practicing forestry when mitigating or recommending mitigation of impacts from previous forestry activities on related watershed or ecological values within their area of professional expertise or when recommending those mitigations for proposed timber operations. However, public, and private foresters are required to be licensed pursuant to this article when making evaluations and determinations of the appropriate overall combination of mitigations of impacts from forestry activities necessary to protect all forest resources.
b) PRC §754 - “Forested landscapes” means those trees dominated landscapes and their associated vegetation types on which there is growing a significant stand of tree species, or which are naturally capable of growing a significant stand of native trees in perpetuity, and is not otherwise devoted to non-forestry commercial, urban, or farming uses.
10. Projects outside of a “forested landscape” should consider the use of a professional ecologist, biologist, certified rangeland manager, arborist, RPF, or other professional with knowledge of local ecosystem processes to develop an appropriate fuel hazard reduction removal project.
11. CAL FIRE has the discretion to specify an earlier project completion date at the time of award based on the funds associated with the grant award. CAL FIRE will work with the grantees to ensure projects will still be achievable within the earliertimeframe.
12. Fuel reduction vegetation treatment prescriptions shall focus on increasing safety for the public and first responders, as well as reducing fire hazards to improve the protection of lives, structures, and communities. Treatments shall eliminate the vertical and horizontal continuity of vegetative fuels for the purpose of reducing the rate of fire spread, duration and intensity of fire, fuel ignitability, and the ignition of tree crowns or structures.
13. Required project deliverables to be included in the Project Scope ofWork:
a) Pre- and post-treatment description of: (1) site conditions and project results relative to hazardous tree or vegetative conditions; (2) wildfire hazard reduction goal accomplishments, or (3) another measurable metric for evaluation of the project. This includes, but is not limited to, number of acres treated, number of parcels treated for fuel reduction for defensible space compliance, number of prevention plans created, and number of people reached in a public education project. CAL FIRE reserves the right to retain copies of these descriptions and publicly disseminate the information for its own purposes. b) GIS data files supporting the project map to allow CAL FIRE to accurately document the spatial extent of the project for the duration of the grant.
pg. 12
• For projects and activities involving on-the-groundwork, CAL FIRE requires shapefiles to be submitted with the signed agreement and on a quarterly basis throughout the duration of the grant. (See Progress report quarterly calendar, pg. XX).
c) Documented CEQA or NEPA compliance within 12 months of grant execution, unless a longer period of time is approved by CAL FIRE. This includes the approval of a Negative Declaration, Mitigated Negative Declaration, or Environmental Impact Report, or the filing of a Notice of Exemption. If compliance is not achieved or if reasonable articulation of non-compliance is not made, the grant could be subject to termination. Documented CEQA/NEPA compliance must be completed before commencing any ground disturbing activity.
14. Financial reports are required for reimbursement. Please see Appendix C for guidelines for the invoice that must be submitted with the financial report. The invoice template is found on the CAL FIRE website.
15. A Quarterly Progress Report form must be submitted under the Pending tasks “Activities report request” in the Grants Portal utilizing the required CAL FIRE Wildfire Prevention Grants Template. Grantee shall provide data reporting to CAL FIRE, including but not limited to, number of acres treated, number of parcels treated for fuel reduction for defensible space compliance, number of prevention plans created, and number of people reached in a public education project. CAL FIRE will provide grantees with the specific metrics and the reporting process. The quarterly progress report is due within 30 days of the end of every calendar quarter, even if no fiscal activity has occurred:
Quarter Progress Report Covering Due Date
1st Quarter January 1 – March 31 April 30
2nd Quarter April 1 – June 30 July 31
3rd Quarter July 1 – September 30 October 31
4th Quarter October 1 – December 31 January 31
16. For all Proposition 4 funded grant projects, grantees will provide CAL FIRE with updated cash flow projections. Cash flow projections will be utilized aggregately for monthly projections and semi-annually for individual projects.
17. Final financial reports for grant-related work must be submitted to CAL FIRE no later than 30 days after the project completion date.
pg. 13
18. A Wildfire Prevention Grants Program Final report (found on the CAL FIRE website) must be submitted simultaneously with the final financialreport. a) Pre-implementation and post-implementation pictures must be submitted with the Final Report, along with updated GIS data files.
19. Projects must demonstrate all efforts to reduce greenhouse gas emissions. Projects that demonstrate significant greenhouse gas emissionsreductions will be favored.
20. All Wildfire Prevention Grants projects must clearly display, identify, and label themselves as being funded by CAL FIRE. Acknowledgments must contain the CAL FIRE logo as well as the following statement: Funding for this project provided by CAL FIRE’s Wildfire Prevention Grants Program. Grantees must include the California Climate Investments (CCI) funding boilerplate and logo, available in the CCI Media & Communications Style Guide, or the Proposition 4 logo and boilerplate language (link to be added here), along with the CAL FIRE logo on all outreach and public-facing materials including but not limited to press releases, media advisories, printed collateral, event invitations, signs, and project/programwebsites.
21. Each application should focus on one or more of the following major activities:
a) Hazardous Fuels Reduction
b) Wildfire Prevention Planning
c) Wildfire Prevention Education
Entities with more than one application should consider consolidating into just one application, especially if proposed project(s) are similar or share geographic locations.
For additional assistance work with your local CAL FIRE Unit coordinator or your region representatives.
22. Applications must be submitted in the CAL FIRE Grants Portal by August 06, 2025, at 3:00 PM Pacific Time. It is highly recommended you submit your application beforethe deadline as CAL FIRE will not accept any late applications due to technical issues.
23. No reimbursable work on proposed Wildfire Prevention Grants projects may commence until there is a fully executed agreement between CAL FIRE and the grantee. An agreement is considered fully executed upon signature and approval by the State Fire Marshal or designee.
24. All project and activity work related to grants must be completed by final expiration date located in the executed Grant Agreement.
25. No ground disturbing work may commence until the requirements of CEQA or NEPA have been satisfied. For more details see Appendix A: Environmental Compliance for CAL FIRE Projects (CEQA).
pg. 14
26. Agreements must be executed by the date specified in theAgreement.
27. Reimbursement payments are expected to be issued 45 calendar days from the time of an undisputed financial report. Payments are sent via U.S. Mail; electronic payment is not available. The financial report approval process is as follows:
a) Financial report submitted to the Region for review and approval using Grants Portal.
b) Unit reviews the financial report and performs a project site inspection, if applicable, to verify that invoiced work has been satisfactorily completed according to the deliverable items described in the grant documentation. c) Grants Management Unit reviews and submits the financial report to the Business Service Office for payment.
28. When a Contract County is the grantee, the Contract County must contact the CAL FIRE Administrative Unit to conduct an inspection of the modification efforts prior to submitting a Financial Report in Grants Portal for completed work. The CAL FIRE Administrative Unit or designee will conduct an inspection to verify that work to be invoiced has been satisfactorily completed according to the deliverable items described in the grant documentation.
29. A resolution or attesting document may be requested for Wildfire Prevention Grants.
The attestee cannot be the same individual designated to sign the agreement. Please refer to the sample resolution (Appendix B). A board resolution template is available on the CAL FIRE WP Grants website.
Note: Where the line indicates ‘whereas the Board designates (designee’s title)’, it is recommended the applicant list the title rather than an individual’s name. In the event the individual retires or leaves the organization, a new resolution designating a replacement will be required if a name is listed rather than the working title. The resolution should name the designee for entering into agreements on behalf of the board and the authorized signatory for financial reports.
30. Wildfire Prevention Grants are neither designed nor intended to create or substantially support ongoing administrative positions.
31. The inclusion of indirect costs is acceptable for Wildfire Prevention Grants funded by CCI projects up to 12% of the total amount of direct grant funds provided to the grantee, minus equipment. Applicants may request from CAL FIRE a higher indirect cost rate by providing additional justification as to why a higher indirect rate is needed as well as including appropriate documentation substantiating the basis of the higher indirect rate (e.g. a copy of a federally approved Negotiated Indirect Cost Rate Agreement, etc.). In no instances may the request exceed 20%. This shall apply to all entities, including University of California (UC) and California State University (CSU) entities. Grantee must retain documentation related to the determination ofthe
pg. 15
grantee’s indirect cost rate for audit purposes. Approval of the higher indirect rate is solely at CAL FIRE’s discretion. Please refer to Appendix H.
32. The inclusion of indirect costs is acceptable for Wildfire Prevention Grants funded by Proposition 4 projects. The grantee may request one of the following indirect costrates:
a) The grantee’s federal negotiated indirect cost rate, pursuant to its Negotiated Indirect Cost Rate Agreement (NICRA).
b) The 15 percent de minimis indirect cost rate specified in Part 200 of Title 2 of the Code of Federal Regulations.
c) A rate negotiated by the grantee with another state agency within the lastfive years.
d) A rate proposed by the grantee in the grantee’s program application with the administering state agency if the grantee does not have an existing state rate. e) Grantee can request an indirect cost rate of 12% to 20%. f) up to 12% of the total amount of direct grant funds provided to the grantee, minus equipment. Applicants may request from CAL FIRE a higher indirect cost rate by providing additional justification as to why a higher indirect rate is needed as well as including appropriate documentation substantiating the basis of the higher indirect rate (e.g. a copy of a federally approved Negotiated Indirect Cost Rate Agreement, etc.). In no instances may the request exceed 20%. This shall apply to all entities, including University of California (UC) and California State University (CSU) entities. Grantee must retain documentation related to the determination of the grantee’s indirect cost rate for audit purposes. Approval of the higher indirect rate is solely at CAL FIRE’s discretion.
Please refer to Appendix H
33. All educational materials and planning documents created and used for a Wildfire Prevention Grant project must be submitted to CAL FIRE. CAL FIRE may retain copies of these materials and utilize them for CAL FIRE’s own purposes. Similarly, any Wildfire Prevention Grant project photos, videos, testimonials, or other similar information submitted to CAL FIRE throughout the performance of the project may be retained by CAL FIRE and utilized for CAL FIRE’s own purposes.
34. Records in CAL FIRE’s possession, including but not limited to applicationpackages, Agreements, and grant project financial records, may be subject to public inspection or disclosure pursuant to the California Public Records Act.
35. Grantees should note that CAL FIRE will only serve in a lead agency capacity for activities related to its discretionary approval (i.e., grant-funded activities). In the circumstance where another public agency subsequently seeks to use a CAL FIREled Project Specific Analysis under the California Vegetation Treatment Program for CEQA compliance and there is no related discretionary approval required of CAL
pg. 16
FIRE, CAL FIRE would have no involvement, oversight, or other obligation in the approval, implementation, or documentation of that agency’s actions.
PREVAILING WAGE REQUIREMENTS
CAL FIRE provides no opinion as to whether projects may be subject to prevailing wages. For determination for prevailing wages, please contact the Department of Industrial Relations (DIR) at DIR Prevailing Wage. It is the applicant’s responsibility to budget for prevailing wages in their project cost when applicable.
Please Note: Beginning July 1, 2026, certain fuel reduction work, including but not limited to residential chipping, rural road fuel breaks, and fire breaks funded by the State will be subject to prevailing wage, record keeping, and registration requirements. (California Public Resources Code section 80200 et seq.). While the requirements do not apply to any contract, subcontract, or grant agreement that is fully executed before July 1, 2026, the requirements will apply if a contract, subcontract, or grant agreement is renewed and/or amended after July 1, 2026.
GREENHOUSE GAS (GHG) EMISSIONS REQUIREMENTS
California Climate Investments (CCI) administered by CAL FIRE through the Forest Health, Wildfire Prevention, and Urban and Community Forestry Programs contribute to California’s climate goals by reducing GHG emissions from wildfires, stabilizing long- term storage of carbon in biomass, and improving carbon sequestration in California’s natural and working forests.
In terms of direct emissions benefits, the objectives of the WP Grants Program are to:
• Reduce GHG emissionsfrom wildfire and prevent the need for cleanup and rebuilding of communities following destructive wildfire events • Provide fire personnel with more opportunities to access the fire perimeter to extinguish fires more quickly, thereby reducing GHG emissions • Encourage projectsthat result in smaller scale fires to reduce GHG emissions and reduce the carbon impact
• Improve health and resilience of treated areasfor increased carbon sequestration
• Improve public awareness and reduce human caused wildfireignitions • Promote orderly growth and development through land use planning which helps to reduce GHG emissions
Eliminating wildfire starts, mitigating wildfires before they progress into wildland areas and communities, and facilitating firefighting efforts and safety all contribute to reduced wildfire emissions over time. The WP Grants Program also includes support for planning, such as
pg. 17
development of Community Wildfire Protection Plans, and education programs that promote fire- safe communities to capture the benefits and synergy of collective, community-wide efforts.
However, fuel reduction activities also release GHG emissions at the time of treatment, and CAL FIRE must balance emissions costs and benefits of the Wildfire Prevention and Forest Health Programs to comply with the law. Minimizing emissions of fuel treatment activities, using disposal methods other than open burning, and optimizing vegetation health options in the development of treatment prescriptions are important steps in project development to achieve balanced emissions costs and benefits.
Grantees must submit information about project size, vegetation type, location, and treatment area so that CAL FIRE staff may complete emissions calculations for the project. Calculations will be completed using an existing methodology produced by CAL FIRE and the California Air Resources Board for the Wildfire Prevention Grants Program. Emissions effects of activities that do not fit the existing methodology will be described in detail. The grant application review process will include consideration of project activities with emissions benefits.
PROPOSITION 4 REPORTING REQUIREMENTS
Wildfire Prevention Grants are funded by Proposition 4 from the Safe Drinking Water, Wildfire Prevention, Drought Preparedness, and Clean Air Bond Act of 2024. The funds are appropriated by the California Legislature to CAL FIRE, who is responsible for administering the funds.
Accountability and transparency are essential elements for Proposition 4. Full public disclosure is required to provide information on how administering agencies are investing appropriations and what benefits are being achieved from those investments. CAL FIRE is responsible for collecting project information and reporting.
For each grant project, grantees must submit reporting data to CAL FIRE on a quarterly basis.
pg. 18
III. GRANT APPLICATION REVIEW AND EVALUATION FACTORS
CALIFORNIA CLIMATE INVESTMENTS (CCI) REPORTING REQUIREMENTS Wildfire Prevention Grants are funded in whole or part by Cap-and-Trade auction proceeds appropriated by the California Legislature to CAL FIRE, who is responsible for administering funds allocated from the CCI Program.
Accountability and transparency are essential elements for CCI. Full public disclosure is required to provide information on how administering agencies are investing appropriations from the GGRF and what benefits are being achieved from those investments. CAL FIRE is responsible for collecting project information and reporting.
For each grant project with a total project cost of greater than $1,000,000.00, grantees must submit jobs reporting data to CAL FIRE on a semi-annual basis in June and December. The reporting cycles cover information for the following periods: December 1 – May 31, June 1 – November 30. All grant projects meeting that criteria will be notified of the reporting dates and the data requirements.
REVIEW PROCESS
Applications will be reviewed by CAL FIRE. The application review involves three levels:
• Local – CAL FIRE Units and Contract Counties
• Regional – CAL FIRE Northern and Southern RegionalOffices • Statewide – Statewide review team. The statewide review team will prepare a list of recommended projects and activities for consideration by the Director of CAL FIRE. The Director will make decisions on approved projects and activities taking into consideration the recommendations of the statewide review team.
Emphasis at each level will be placed on projects and activities that address hazards that reduce potential risk from wildfire in and near communities. The department shall consider the fire risk of an area, the geographic balance of projects, and whether the project is complementary to other wildfire prevention or forest health activities when awarding local assistance grants. Additionally, to the extent possible, a project or activity will not be selected if it conflicts or competes with another proposed or approvedproject.
pg. 19
EVALUATION FACTORS (RANKING CRITERIA)
In evaluating applications, CAL FIRE is seeking information that allows it to consider the following factors:
1. The grant application clearly identifies the focus of the grant as Hazardous Fuels Reduction, Wildfire Prevention Planning, or Wildfire Prevention Education.
2. The project addresses hazards and risks fromwildfire. a. The project includes Fire Hazard Severity Zone rankings and indicates areas and their relative proportion of Very High, High, and Moderate Fire Hazard Severity Zones as adopted by the State Fire Marshal and identified in the CAL FIRE map located at Fire Hazard Severity Zones.
b. The proposed project is in or near a wildfire threatened community and adequately describes how it will address the hazards and risks fromwildfire. c. The project protects other assets of wildfire threatened communities to maintain continuity of government operations and critical services. This includes, but is not limited to, fire, police, power, water, sewer, roads, or other critical facilities. If the project involves community infrastructure, it must explain how it will address the hazards and risks from wildfire to these assets.
3. The project is related to or part of one or more strategic plans or tree removal plan:
a. The project is included in or consistent with one or more of the following plans:
i. CAL FIRE Unit Fire Plan, Contract County Fire Plan, Local Fire Plan, a CWPP, Community Evacuation Plan, tree removal plan, Fire Safe Council Action Plan, Firewise USA Community Wildfire Risk Assessment, Local Hazard Mitigation Plan, Safety Element plan, or other local plan (identified in Scope of Work) that addresses the hazards and risks from wildfire. b. The project proposes to create, or update, a long-term fire hazard reduction planning document affecting or involving wildfire threatened communities, such as, but not limited to, a CWPP or Community Evacuation Plan. Astrategic planning document would include a Safety Element of a General Plan and a Local Hazard Mitigation Plan with elements for increasing safety for the public and first responders.
c. The project removes hazardoustrees in collaboration with other entities, other funding sources, or as part of a larger tree mortality project. d. The project considers other projects, pending or past, in the Unit/Contract County.
e. The project strategically advancesthe protection and preparedness of wildfire threatened communities across a region or the state, while increasing safety for the public and first responders.
4. The applicant has taken steps to reduce GHG emissions as much as possible, such as chipping or mulching removed vegetation, or disposing of material throughbiomass
pg. 20
markets. The applicant is willing and able to provide project data as requested to calculate project emissions.
5. Community support/ meaningful and direct benefits exists. a. The project includes plans for external communications, such as planned press releases, project signage, community meetings or field tours that all, or in part, reach owners and residents in the project area.
b. Letters of Support have been obtained.
c. Letters of Commitment from partnering entities are submitted with the application. Letters of commitment are required if grantee is utilizing the California or Certified Community Conservation Corps.
d. Please note that although matching funds are not required, the existence of matching funds is a positive factor for CCI funds.
e. The degree to which a project provides in-kind services and/or secured federal, state, private, or local cost share funding. Have non-monetary and/or funding resources of agencies and organizations that have been identified and secured.
6. There is an implementation plan in place.
a. The project includes a detailed timeline that addresses potential limitations and includes specific tasks and milestones to measure progress during implementation of the project.
b. The project includes an accurate set of deliverables that are measurable and attainable.
c. The project is fully defined with metrics to measure progress and completion.
This includes, but is not limited to, number of acres treated, number of parcels treated for fuel reduction for defensible space compliance, number of prevention plans created, or number of people reached in a public education project.
7. The project budget and narrative are clear and reasonable. a. The proposed budget shows how grant funds will be spent bycategory. b. Indirect costs are reasonable for the project proposed and should generally not exceed 12% of the total direct grant request, minus equipment costs, unless a higher indirect rate is approved by CAL FIRE for CCI funds. c. Costs and indirect costs are reasonable for the size, scope, and anticipated benefit of the proposed project.
d. For hazardousfuel reduction projects, the actual number of acres being treated is clearly defined.
8. There is demonstrated capacity to administer thegrant. a. The applicant shows an acceptable amount of experience in administering grants. This is largely based on successfully administering other grant- funded projects/activities over the past five years. Project proponents having no previous experience with similar projects should discuss any past experiences that may help show capacity to successfully complete the proposed project. This may include partnering with a more experienced organization that can provide project support.
pg. 21
b. Discuss successes and administration of previously awarded CAL FIRE grantsor grants administered by the applicant for other granting entities.
9. Fire Risk Reduction Community List per Public Resources Code4290.1 a. Public Resources Code 4124.7 requires CAL FIRE to “prioritize local assistance grant funding applications” from local agencies based on the “Fire Risk Reduction Community List.”
b. The prioritization required in subdivision (a) of Public Resources Code 4124.7 shall not affect applications from entities that are not localagencies. c. Wildfire Prevention Grant applicants will receive priority for utilizing the funding to meet the List eligibility requirements.
d. Wildfire Prevention Grant applicants will also receive priority if the applicant is already on the List.
e. Projects are selected on a competitive basis and consecutive awards are not guaranteed.
f. Applicants not eligible for the List are not precluded from receiving grant funds.
For more information about the Fire Risk Reduction Community List, please visit the Board of Forestry website
APPLICATION PROCESS AND PROJECT ADMINISTRATION
Applicants should work with the local CAL FIRE Unit for guidance in developing project plans for your application. Find your local CAL FIRE Unit contact as listed by county. Building a relationship with the local CAL FIRE Unit enhances the potential for a successful application and grant award.
Applications not received by the deadline, not submitted in the CAL FIRE Grants Portal, or that do not adhere to the procedures in this guide, will not be accepted or considered.
STAGE 1 - PROJECT APPLICATION
Due August 06, 2025, at 3:00 PM Pacific Time
ELECTRONIC APPLICATION SUBMISSION IN THE CAL FIRE GRANTS PORTAL SOLICITATION LINK ON THE WP GRANTS WEBSITE AND IN THE WP GRANTS MAPPING CENTER PROJECT MAPPING PROGRAM:
The Grants Portal WP Grants solicitation link and a Grants Portal user guide can be found on the Wildfire Prevention Grants website.
pg. 22
Entities with more than one application should consider consolidating into just one application, especially if proposed project(s) are similar or share geographic locations. For additional assistance, work with your local CAL FIRE Unit coordinator or your region representatives.
Upload all documents related to your application to the Grants Portal no later than 3:00 PM Pacific Time on August 06, 2025. Instructions on how to apply through the Grants Portal can be found in the Grants Portal Application Submittal User Guide.
The Grants Portal will issue a Project Tracking Number for each application.
Please use this file naming structure (Project Tracking Number plus document name) for attachments (if you have multiples of one file, please make it into a zip file) uploaded in the Grants Portal. Below is an example (the Grants Portal will assign the actual Project Tracking number that you will use):
• 25-WP-UUU-XXXXXXXX-STD 204.pdf
• 25-WP-UUU- XXXXXXXX-Letter of Support.pdf
• 25-WP-UUU- XXXXXXXX-Letter of Commitment.pdf
PROJECT MAPPING PROGRAM
In addition to the CAL FIRE Grants Portal application package, each applicant must submit online mapping in our WP Grants Mapping Center Project Mapping Program database. Submit your application in the Grants Portal first to obtain the auto-generated Project Tracking Number, which you will need for the mapping program. The online mapping submission consists of submitting a Geopoint for all project types. For Hazardous Fuels Reduction projects, you also will need to submit treatment area polygon(s). The instructions on how to draw and submit a Geopoint and Polygon in the Project Mapping Program can also be found at CAL FIRE WP Grants.
There is a video and a quick reference guide with screenshots of the online mapping program. •Applications for Hazardous Fuel Reduction that do not include Treatment Area Polygon(s) in the Project Mapping Program will not be accepted. •Applications for Wildfire Prevention Planning and Wildfire Prevention Education projects will submit a Geopoint only.
Complete all documents accurately to avoid delays due to corrections and revisions prior to final approval. If revisions are necessary during Stage 2, then the revised documents will be used in the final grant agreement between the State and the grantee. • Late submissions will be rejected. No exceptions. Late is defined as: after 3:00 PM Pacific Time on the due date according to the date stamp on the CAL FIRE Grants Portal. To avoid possible issues with the Grants Portal (such as internet connectivity and internet speed), applicants are highly encouraged to apply as early aspossible.
pg. 23
• Please retain a copy of all documents uploaded to the CAL FIRE Grants Portal for your own records.
DISQUALIFICATION OF APPLICATION
CAL FIRE may consider an application inadequate and, therefore, disqualified from the selection process for several reasons. These may include, but are not limited to, the following:
• Application is not complete.
• Application contains significant inconsistencies with spatial data or project acresproposed for treatment.
• The application is not submitted by an eligible applicant in the Grants Portal. • The project does not meet any of the other eligibility criteria outlined in the Grant Guidelines.
STAGE 2 - GRANT APPLICATION REVIEW AND SELECTION
Sacramento staff will review the project application packages for completeness and determine if the project meets the objectives of the program. Applications found to meet the initial criteria will continue in the multi-level review and selection process.
Incomplete applications will be disqualified.
Notification of grants selected for funding will be sent to the applicant. The grant agreement package for successful grant applicants will be emailed after selection and will include any required grant agreement forms and instructions to proceed to Stage 3. The grant agreement template can be found online, but may be subject to change prior to the execution of a final agreement.
2024 Standard Grant Terms and Conditions
STAGE 3 - GRANTS AWARDED
Awarded grant applicants shall review and return original signed agreements, and any additional information required, following the instructions provided in the correspondence.
Grant agreement packages not completed or received by the agreement deadline may not be eligible for funding.
pg. 24
PROJECT AMENDMENTS, MODIFICATIONS, AND TERMINATIONS
STAGE 4 – COMPLETED GRANT AGREEMENTS
Once the grant agreement is received and signed by the State Fire Marshal or designee, the approval process is complete. All agreements must be signed and submitted per deadlines established by CAL FIRE.
A CAL FIRE designee will be named as the designated contact. The CAL FIRE designee will work with the Region Program Manager on any grant project issues.
The CAL FIRE designee will conduct periodic and final inspections to ensure compliance with the project plan and environmental rules and regulations. All project messaging and documents must be approved by CAL FIRE.
CAL FIRE may perform an audit at any time during or upon completion of the project as described in this guide under “State Audit.”
Grant Termination Date: All project and activity work related to the grant must be completed by the project completion date identified in the executed grant agreement.
Before work on the project begins, a Grant Agreement may be terminated by CAL FIRE or the grantee upon 30 days advanced written notice to the other party. After work begins on the Project, termination may occur: (1) if CAL FIRE and the grantee mutually agree to terminate the agreement; (2) if the State determines Grantee has made a material misrepresentation, violated this Agreement, failed to fulfill its obligations under this Agreement, or otherwise determines there is cause to do so; or (3) if the State gives 30-days written notice of termination to Grantee.
Once a Grant Agreement has been signed, it may only be amended with advanced written consent of both CAL FIRE and the grantee. Any amendment requests including the ability to extend the project timeline, where permissible, must be submitted to CAL FIRE sixty (60) days before the agreement end date using the Grants Portal system. CAL FIRE reserves the right to waive the sixty (60) days in extenuating circumstances.
A grantee wishing to change the scope or budget of an approved project at any stage shall submit the proposed change in writing, on entity letterhead, to CAL FIRE for review. Any change must be consistent with the need cited in the original application and authorizing legislation. Any modification or alteration to the grant agreement on file must be submitted to the State for review and may require a new signed amended agreement. Any reduction in the actual number of acres being treated in a hazardous fuel reduction grant may result in a corresponding reduction of the grant award.
pg. 25
ACCOUNTING REQUIREMENTS
The grantee shall maintain an accounting system that follows Generally Accepted Accounting Principles. The accounting system must accurately reflect fiscal transactions, using the necessary controls and safeguards. This system shall provide an adequate audit trail, including original source documents such as receipts, progress payments, invoices, purchase orders, timecards, canceled checks, etc. Please redact account numbers and personal identifying information before submitting invoices. The system shall also provide accounting data so the total cost of each individual project can be readily determined. CAL FIRE may request records and documentation at any time. These records shall be retained by the grantee for a period of three years after final payment is made by the State or one year after final disposition of any disputed audit findings, whichever occurs later, unless it is the grantee’s policy to retain records for a longer duration. Avoid audit exceptions – keep accurate records.
LOSS OF FUNDING
The following are examples of actions that may result in a grantee’s loss of funding:
• Grantee withdrawsfrom or fails to complete the funded project (in substantial conformance with the Agreement).
• Grantee failsto submit all required documentation within the time periods specified in the grant agreement.
• Grantee failsto submit evidence of CEQA or NEPA compliance within 12 months of the execution of the agreement as specified by the grant agreement. • Grantee changes the project scope without the approval of theState. • Grantee or the State terminatesthe project in accordance with the terms and conditions in the grant agreement.
• Grantee engages in activities that would lead to the project not achieving GHG emissions reductions.
• Grantee or anyone acting on behalf of Grantee shall not engage in fraud, waste, or the abuse of Grant Funds in violation of California Penal Code section 424 et seq.
Grantee shall cooperate in any investigation of such activities that are suspected in connection with this Agreement.
• Recipients of Grant Funds shall receive no more than the fair market value of an arm’s length transaction for any goods or services provided under this Agreement.
Grantee shall provide evidence to the State upon request of compliance with this Section 11.e. Violation of this Section 11.e. will result in a violation of CaliforniaPenal Code section 424, subd. a.
pg. 26
PROPOSITION 4 INDIRECT COST RATES
For grants awarded for projects under Proposition 4, Wildfire Prevention Grants will reimburse the grantee’s indirect costs. The grantee may request one of the following indirect cost rates:
• The grantee’s federal negotiated indirect cost rate, pursuant to its Negotiated Indirect Cost Rate Agreement (NICRA).
• The 15 percent de minimis indirect cost rate specified in Part 200 of Title 2 of the Code of Federal Regulations.
• A rate negotiated by the grantee with another state agency within the last five years. • A rate proposed by the grantee in the grantee’s program application with the administering state agency if the grantee does not have an existing state rate. • Grantee can request an indirect cost rate of 12% to 20%.
In the event of an audit, projects with budgets that include administrative costs must be able to document the appropriateness of these expenses. If the applicant does not have an existing NICRA, a typical method for documentation of administrative overhead expenses is a Cost Allocation Plan (CAP). A CAP is a formal accounting plan used to calculate and document the method for recovering overhead costs. The CAL FIRE strongly recommends that grantees consult with an accounting professional to develop an appropriate method for calculating the overhead rate and prepare a CAP.
pg. 27
PROJECT COSTS
Project costs must be consistent with the approved project and incurred during the performance period as specified in the grant agreement.
Budget Item Eligible Cost Required Documentation
Salaries and Wages
(Grantee Only)
Salaries and wages of employees employed by the grantee who are DIRECTLY engaged in the execution of the grant
project. Limited to actual time spent on the grant project.
Leave benefits (i.e., sick leave, vacation, etc.) that are consistent with the grantee’s leave benefit policy may be charged to the grant in proportion to the percentage of time worked on the grant within the pay period. Examples of expenditures include time-related to site visits and project monitoring and completion of reporting related to the grant project. Staff time related to accounting,
business services, etc. are allowed only if those functions are not included in the grantee's overhead cost.
A payroll summary of all employees’ time spent
on the project must be provided with invoices
requesting salary/wage reimbursement. Payroll
documentation should show a nexus between
time worked on the project and wages paid to
the employee after the fact. Timesheets or
similar documentation detailing days and hours
worked on the project must be maintained and
retained by the grantee for audit purposes but
should not be submitted to CAL FIRE unless
otherwise instructed. Any leave charged to the
grant must reflect the calculation of time spent
on the grant compared to overall time worked.
A statement certifying that leave charged to the
grant is in proportion to employee’s time spent
must be included as part of the supporting
documentation. All salary and wages charged to
the grant must tie back to the grantee’s
accounting records.
Benefits (Grantee
Only)
Employer contribution share of fringe benefits associated with employees (paid from salaries and wages Budget
Item) who are directly engaged in the execution of the
grant project. This will include Social Security, Medicare, Health Insurance, Pension Plan costs, Payroll taxes, etc. as applicable for the specific employee.
Same documentation as Salaries and Wages.
Payroll summary documentation showing wages
and hours paid to employee and associated
fringe benefits. Back-up documentation to be
retained by grantee for audit records.
Contractual Direct consultant and contractual services necessary to achieve the objectives of the grant. Examples of
contractual costs will be RPF supervision/certification, professional/consultant services (the costs of consultant services necessary for project planning and
implementation), Wildfire Prevention contractor, etc.
Procurement of contractual services should be
documented to ensure selection on a competitive basis
and documentation of price analysis.
Invoices from Consultant/Contractor identifying
expenditure, services performed, and period of
services. When reporting acres, contractor
invoices must identify when and where the
acres were treated. Documents related to
consultant/contractor selection analysis must be
kept by the grantee and made available for
audit purposes, upon request. Use of California
Conservation Corps or certified community
conservation corps is exempt from competitive
selection.
Travel (Grantee
Only)
Travel costs associated with travel to and from project sites, meetings, etc. directly related to the grant project and must be considered reasonable and necessary for the completion of the project. Absent a written policy, per diem shall not exceed the California Standard Per Diem
Rate allowable by the U.S. General Services
Administration. Mileage rates shall not exceed the rates allowable by the IRS. If not using the per diem rate by the U.S. General Services, the Grantees' travel policy must be submitted and approved by CAL FIRE and must be submitted with the application.
Receipts identifying travel costs (i.e., lodging,
rental cars). Mileage must be documented by
either employee travel claims that are signed by
the employee or vehicle mileage logs for
vehicles owned by the grantee. Per Diem must
be documented by employee travel claims.
pg. 28
Budget Item Eligible Cost Required Documentation
Supplies (Grantee
Only)
Supplies that are used in the direct support of the project are allowable. Supplies exceeding. $500 per unit cost shall be documented to ensure procurement of supplies on a
competitive basis and documentation of price analysis.
Any technology must be identified and pre-approved by
CAL FIRE. Supplies include items under $5,000 per unit
cost. (e.g., chainsaws etc.) All food costs must be preapproved and explicitly listed in the Scope of Work, Budget, and Budget narrative in order to be considered an eligible cost.
Receipts identifying item purchased, cost, and
date of purchase. Documentation related to
price analysis of procurement of supplies
exceeding $500 must be kept by the grantee
and made available for audit purposes upon
request.
Equipment (Grantee
Only)
Equipment is an item of $5,000 or more per unit cost and has a tangible useful life of more than one year. Purchase of equipment may not exceed $750,000 and must be
owned by the grantee. The cost to lease equipment to use in the grant project may be charged to the grant but listed under the ‘Other’ budget category. A cost-benefit analysis to justify the cost of purchasing equipment versus leasing, must be identified in the scope of work. Procurement of equipment must be done on a competitive basis and
include documentation of price analysis.
The grantee must include in the application package the proposed use and maintenance plans for equipment after
the performance period of the grant. Disposition of
equipment beyond the project performance period is
subject to CAL FIRE approval. If grantee fails to complete grant or dissolves during grant, grantee must dispose of the equipment in accordance with an equipment
disposition plan that is approved by CAL FIRE in advance.
Equipment purchased using grant funds can not be used as collateral, financed, or sold without written approval from the State at its discretion.
Cost of equipment purchased shall be
substantiated by purchase receipt and a bid
quote worksheet at the time of invoicing. All
documentation related to price analysis of
procurement of equipment must be kept by the
grantee and made available for audit purposes,
upon request. Disposition of the equipment
must be submitted and approved by CAL FIRE
every two years upon completion of the project
until notified in writing by CAL FIRE that
reporting is no longer required.
Other (Grantee
Only)
Other costs that do not fit in any of the above categories.
The cost must be directly related to the grant project. A cost (such as rent, utilities, phones, general office supplies, etc.) that must be apportioned to the grant is considered indirect cost unless written justification is submitted and approved by CAL FIRE. Use of equipment owned by the
grantee may be charged to the grant at a rate set by the California Department of Transportation Labor Surcharge and Equipment Rental Rate Guide. Example, grantee has a rental rate in Other for equipment and Fuel in Supplies for said equipment. As per the Cal-Trans guideline, fuel is calculated and accounted for in the rate.
Invoices or receipts identifying the item and cost
charged to the grant. Cost of leased equipment
charged to the grant must be substantiated with
receipts identifying equipment leased, dates
equipment was leased, lease rate and total cost.
Use of grantee equipment must be
substantiated with an equipment usage log that
identifies the equipment used, rate, and total
rental cost.
pg. 29
Budget Item Eligible Cost Required Documentation
Indirect Costs
(Grantee Only)
Indirect Costs are costs associated with doing
business that are of a general nature and are incurred to benefit two or more functions within the grantee
organization. These costs are not usually identified
specifically in the grant agreement, project, or activity, but are necessary for the general operation of the
organization. Examples include salaries and benefits of employees not directly assigned to a project; functions such as personnel, accounting, budgeting, audits, business services, information technology, janitorial, and rent, utilities, supplies, etc. Functions included as direct versus indirect costs must be applied consistently for all activities within the Grantee organization, regardless of fund
source. The maximum allowable indirect charge for this
grant program for all entities including UC’s and CSUs
should generally not exceed 12%, unless an exemption is approved by CAL FIRE (see Indirect Rate Exemption). For grants awarded for projects under Proposition 4, Wildfire Prevention Grants will reimburse the grantee’s indirect costs. The grantee may request one of the following
indirect cost rates:
The grantee’s federal negotiated indirect cost rate,
pursuant to its Negotiated Indirect Cost Rate Agreement (NICRA).
• The 15 percent de minimis indirect cost rate
specified in Part 200 of Title 2 of the Code of
Federal Regulations.
• A rate negotiated by the grantee withanother
state agency within the last five years.
• A rate proposed by the grantee in the grantee’s
program application with the administering
state agency if the grantee does not have an
existing state rate.
• Grantee can request an indirect cost rate of 12%
to 20%.
Applied on a percentage (%) basis on direct costs
except for equipment. Documentation related
to the determination of the grantee’s indirect
cost rate must be retained by the grantee and
made available upon request for audit purposes.
pg. 30
PAYMENT OF GRANT FUNDS
Funds will be disbursed only when there is a fully executed grant agreement between CAL FIRE and the grantee. An agreement is considered fully executed upon signature and approval by the State Fire Marshal or designee. All payments are made on a reimbursement basis, except in cases where CAL FIRE authorizes advance payments. (i.e., the grantee is invoiced for services, products, or supplies; invoices CAL FIRE for same; and is reimbursed by the State upon approval of the invoice). No work prior to or after the grant period will be reimbursable.
CAL FIRE has the legal right to conduct a spot inspection to verify that work invoiced has been satisfactorily completed. If a financial report is incomplete or non- reimbursable, it will be returned to the grantee.
STATE CONFLICT OF INTEREST LAWS
All applicants, individuals who participate in the review of submitted Project Proposals, and grantees are subject to state and federal conflict-of-interest laws. Applicable statutes include, but are not limited to, California Government Code section 1090 and Public Contract Code sections 10365.5, 10410, and 10411. These statutes include, but are not limited to, prohibitions on the following conduct:
1. Current State Officers or Employees: No State officer or employee shall engage in any employment, activity, or enterprise from which the officer or employee receives compensation or has a financial interest, and which is sponsored or funded by any State agency, unless the employment, activity, or enterprise is required as a condition of regular State employment. No State officer or employee shall contract on his or her own behalf as an independent contractor with any State agency to provide goods orservices.
2. Former State Officers or Employees: For the two-year period from the date he or she left State employment, no former State officer or employee may enter into a contract in which he or she engaged in any of the negotiations, transactions, planning, arrangements, or any part of the decision-making process relevant to the contract while employed in any capacity by any State agency. For the twelve-month period from the date he or she left State employment, no former State officer or employee may enter into a contract with any State agency if he or she was employed by that State agency in a policy-making position in the same general subject area as the proposed contract within the twelve-month period prior to his or her leaving State service.
Any individual who has participated in planning or setting priorities for a specific grant solicitation over and above the public comment process or who will participate in any part of the grant development and negotiation process on behalf of the State is ineligible to receive funds or personally benefit from funds through that solicitation. Failure to comply with conflict-of-interest laws, including business and financial disclosure provisions, will result in the Project Proposal being rejected or any grant agreement made in violation of the conflict-of-interest laws being
pg. 31
declared void. CAL FIRE may request additional documentation during the performance of the grant, including review of financial progress reporting, or during State Audit to verify that a conflict of interest does not exist. Other legal actions may also be taken.
If an applicant has any questions about compliance with conflicts of interest laws, the applicant should consult the California Fair Political Practices Commission or a qualified attorney.
CAL FIRE may require Grantee to establish conflict-of-interest policies and procedures and maintain adequate controls to ensure that the grantee or anyone acting on behalf of the grantee does not have any conflicting personal or financial interest associated with activities funded by the grant project. CAL FIRE may request additional documentation during the performance of the grant, including during review of financial or progress reporting, or during State Audit to verify that a conflict of interest does not exist.
Private Benefit Prohibited
Grantee will not be reimbursed for any costs that exceed the fair market value of an “arm’s length” transaction for goods or services rendered in furtherance of the grant project.
An “arm’s length” transaction exists where the parties have an adverse (or opposing) interest. For example, a seller wants to sell his goods at the highest possible price, while a buyer wants to buy at the lowest possible price. These are adverse interests. In negotiating with a person, an adverse interest is assumed if that person is otherwise unrelated to you in the sense of not being in a position to exercise substantial influence over you or your affairs. If the person is in a position to exercise substantial influence over your affairs, then an arm’s length standard requires additional precautions to eliminate the effect of the relationship. Using a conflict-of-interest policy, information about comparable transactions between unrelated parties, and reliable methods for evaluating the transaction, are examples of precautions that would help make the negotiation process equivalent to one between unrelated persons.
Fair market value is the price at which goods, services, or property would change hands between a willing buyer and a willing seller, neither being under any compulsion to buy, sell, or transfer the goods, services, or property, and both having reasonable knowledge of relevant facts.
Grant recipients must avoid or scrutinize transactions that exhibit signs of actual or possible conflicts-of-interests and should avoid even the appearance of conflicts. The appearance of a conflict of interest occurs when a person in a position of authority over an organization, such as a director, officer, or manager, may benefit personally from a decision he or she could make.
Conflict-of-interest red flags may also include organizations that engage in transactions that are less than “arm’s length” indicating there may be a bargain or gift element, such as transactions with friends and relatives, or receiving gifts from contractors. In addition, transactions with organizations that have several employees or Board members who are personally or professionally related should be highly scrutinized.
pg. 32
ADVANCE PAYMENTS
In accordance with Public Resources Code section 4124.5, or other applicable statutory authority, advance payments may be considered for non-profit organizations, local agencies, Resource Conservation Districts, special districts, and Native American tribes. Advance payments are solely at CAL FIRE’s discretion and eligibility and may be subject to change. An advance request form must be submitted identifying how funds may be used over a six-month period.
Advance payments must be deposited into a federally insured, interest-bearing account that provides the ability to track interest earned and withdrawals. Any interest earned on advance payment funds must be accounted for as project income and used toward offsetting the project cost or returned to the STATE. Refer to Appendix K on calculations and supporting documentation for interest income. All other advance payment requests shall not exceed 25% of the total grant award.
Advances must be fully utilized within a six-month period unless additional time has been requested and is approved by CAL FIRE. Any Advance Payment, or portion thereof, that is not spent within the later of six months or the spending timeline approved by the CAL FIRE must be returned to the State and will be returned to the grant balance.
Additional advances may not be requested until acceptable documentation is received that the previous advance has been fully liquidated on eligible expenses. In addition, an accountability report must be submitted to CAL FIRE every four months upon receipt of funds until funds have been fully liquidated.
CAL FIRE processes for approving and managing grant advances are subject to change.
STATE AUDIT
Projects may be subject to an audit at any time during the Project Performance Period and for three years following Project completion. The purpose of the audit is to verify that project expenditures were properly documented.
If your project is selected for audit, you should include all books, papers, accounts, documents, or other records of the grantee, as they relate to the project for which state funds were granted.
• To expedite the audit, the grantee must have the project records readily available, including the source documents, and canceled warrants. The grantee must also make an employee who has knowledge of the project and the accounting procedure or system available to assist the state auditor. The grantee must provide a copy of any document, paper, record, or the like as requested by the auditor. • Projects may be suspended if the audit reveals discrepancies, or if CAL FIRE believes there are improprieties or issues with the project.
pg. 33
Agreement A legally binding agreement between the State and another entity.
TERM EXPLANATION
Applicant The entity who has applied, requesting grantfunds.
A Legislative budget authorization from a specific fund to a specific agency or program to make expenditures or incur obligations for a specific purpose and period.
Appropriation
Employee Individuals employed directly by the grantee and who generally receive a W-2 for tax purposes.
Grantees must keep source documents for all expenditures related to each grant for at least three (3) years following project completion or one year following an audit, whichever occurs later, unless the grantee has a longer retention policy.
EXPLANATION OF TERMS
Amendment A formal modification or a material change of the Agreement, such as terms, cost, budget, or scope of work.
Application The form identified by CAL FIRE as the document to be submitted by an applicant requesting grant funds, and its required supporting attachments, as required by the enabling legislation or program.
Authorized
Representative
The designated person or position identified by the Grantee as the agent to sign all required grant documents including, but not limited to, grant agreements, Application forms, and payment requests.
Consultant
Services
Services which provide a recommended course of action or personal expertise, such as accounting or a Registered Professional Forester (RPF).
Direct Costs Expenses of doing business that are directly attributable to the Project. Examples of direct costs are salaries and benefits of employees directly associated with a Project or expenses of items used directly by the Project.
Encumbrance A commitment of funds guaranteeing a source of payment for a specific Agreement.
An entity contracting with the grantee forservices and generally receives a form 1099 for tax purposes.
Contractor
The California Environmental Quality Act as stated in the PRC § 21000 et seq.; Title 14 California Code of Regulations (CCR) §15000 et seq. CEQA is a law establishing policies and procedures that require agencies to identify, disclose to decision makers and the public, and attempt to lessen significant impacts to environmental and historical resources that may occur because of the agency’s proposed Project.
CEQA
pg. 34
Expenses of doing business that are of a general nature and are incurred to benefit at least two or more functions within an organization. These costs are not usually identified specifically with a grant, grant agreement, Project, or activity, but are necessary for the general operation of the organization. Examples of Indirect Costs include salaries and benefits of employees not directly assigned to a Project; functions, such as personnel, business services, information technology, janitorial; and rent, utilities, supplies, etc. Indirect Costs may be referred to as overhead or administrative costs.
Indirect Costs
Any California corporation organized under Sections 501(c)(3) of the Federal Internal Revenue Code. A letter of determination certifying non-profit status will be required prior to Project approval.
Non-profit
Organization
Program Income Income that is generated directly by Grantee’s performance of the Project, including any interest earned on AdvancePayments.
Grantee The entity that has an executed grant agreement for the award of grant funds.
Modification An agreement modification is an informal agreement that moves dollars in the line item and task budgets not to exceed 10% of total grant amount; changes deliverable due dates or makes a minor change in the work in accordance with the intent of the legislation. It does not require a formal amendment of the grant agreement. See the modifications section for further requirements.
Operating
Expenses (Direct Costs)
Any cost that can be specifically identified as generated by and in accordance with the provisions or activity requirements of the grant agreement.
Personnel Services This budgeted amount includes salaries and benefits for wage-earning personnel employed bythe grantee/contractor (not a subcontractor) and working on the Project.
Project
Performance Period
The period during which the Project Scope of Work costs may be incurred, and the work described in the Project Scope of Work must be completed, billed, and paid for by the State. Only eligible costs incurred during the Project Performance Period will be paid.
Project The term “Project” means the activity or work to be accomplished utilizing grant funds and match (if applicable).
Project Scope of
Work
The term “Project Scope of Work” defines the individual scope of work or activity describing in detail the proposed tasks identified, as described in enabling legislation and in the grant agreement.
Project Budget
Narrative
The term “Project Budget Narrative” defines the proposed detailed budget plan.
Form Std. 204, “Payee Data Record” is required for all grant recipients. The form must be submitted to establish a vendor number for payment and to have funds encumbered.
Payee DataRecord
(Std. 204)
The act ofsigning an Agreement, which provides a legal basis for required performance by parties to the Agreement.
Execution ofan
Agreement
Resolution The purpose of a resolution by a grantee’s governing body is to allow the entity to sign Agreements and amendments for a specific project, i.e., it allows the designated entity to enter into an agreement with the State of California, and it designates someone to sign on behalf of the grantee’s governing board. A signed resolution can be submitted at the time the signed grant agreements are returned to CAL FIRE’s Grants Management Unit, Sacramento Headquarters.
Severely disadvantaged
community
A community with a median household income of less than 60 percent of the area average or less than 60 percent of statewide median household income.
Vulnerable population A subgroup of the population within a region or community that faces a disproportionately heightened risk or increased sensitivity to the impacts of climate change and that lacks adequate resources to cope with, adapt to, or recover from such impacts. pg. 35
pg. 36
APPENDICES
Appendix A: Environmental Compliance for CAL FIRE Projects (CEQA) Appendix B: Sample Resolution (not required)
Appendix C: Invoice
Appendix D: State of California Standard Required Forms Appendix E: CalMAPPER (Awarded Grants Only)
Appendix F: Low-Income and Disadvantaged Communities
Appendix G: PDF Project Map
Appendix H: Justification for indirect rate above 12% and supporting documentation Appendix I: Application Package
Appendix J: Additional Resources
pg. 37
APPENDIX A – ENVIRONMENTAL COMPLIANCE FOR CAL FIRE PROJECTS NOTE: Grantee must submit proof of California Environmental Quality Act (CEQA) or National Environmental Policy Act (NEPA) compliance within one year of the execution of the grant agreement, unless a longer period is approved by CAL FIRE. To ensure this occurs in a timely manner, the grantee should contact the Department of Forestry and Fire Protection (CAL FIRE) Local Unit Contact as soon as possible after receiving the executed Grant Agreement.
NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) COMPLIANCE
Project work involving Federal actions must comply with NEPA.
Regardless of jurisdiction, CEQA Compliance is required when using Wildfire Prevention grant funds. For Federal jurisdictions that meet the requirements of Public Resources Code (PRC) section 4799.05(d)(1), a CEQA notice of exemption will need to be filed. This means that prescribed fire, reforestation, habitat restoration, thinning, or fuel reduction projects undertaken, in whole or in part, on federal lands to reduce the risk of high-severity wildfire that have been reviewed under NEPA may not need additional analysis and would be statutorily exempt from CEQA. See Item #5 below.
CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA)
Within one year of the execution of the grant agreement and prior to commencing any work that could impact the environment, CAL FIRE requires proof of adequate compliance with CEQA.
This may be accomplished by one or more of the following methods:
1. Notice of exemption filed with the State Clearinghouse and the county clerk in the manner specified in subdivisions (b) and (c) of Section 21108 or subdivisions (b) and (c)of Section 21152.
2. Initial study and negative declaration or mitigated negative declaration and all associated noticing documents filed with the State Clearinghouse and the county clerk.
3. Draft and final environmental impact report and all associated noticing documents filed with the State Clearinghouse and the county clerk.
4. Including shapefiles identifying the “treatment” area surveyed where activities will be conducted during the grant period.
5. Timber harvesting permit or notice in compliance with the California Forest Practice Act and Rules for projects that undertake timber operations per PRC § 4527. Note that use of timber harvest documents for CEQA compliance in the absence of timber operations is not appropriate, as the Forest Practice Act and Rules do not apply in these circumstances.
Applicants that will be utilizing timber harvest documents for CEQA compliance should identify within the harvest documents that they are receiving CAL FIRE grantfunding.
6. Finding of no significant impact-decision notice, categorical exclusion- decision memo, or environmental impact statement-record of decision prepared in compliance with the
pg. 38
NEPA for projects that are exempt from CEQA pursuant to PRC § 4799.05(d)(1). When using a NEPA document, per PRC § 4799.05(d)(4)(A), a CEQA notice of exemption needs to be filed with the State Clearinghouse and with the county clerk in the county in which the project will be located in the manner specified in subdivisions (b) and (c) of Section 21108 or subdivisions (b) and (c) of Section 21152. The lead agency will also need to post the notice of exemption on its internet website together with a description of where the documents analyzing the environmental impacts of the project under the federal National Environmental Policy Act of 1969 are available for public review.
7. Completed and accepted project-specific analysis under the CalVTP (California Vegetation Treatment Program) and all associatednoticing documents filed withthe State Clearinghouse and the countyclerk.
1 For exempt projects where the grantee is a public agency , the grantee must prepare and file the notice of exemption for an exempt project. For exempt projects where the grantee is not a public agency (e.g., Fire Safe Council), CAL FIRE or another public agency will be responsible for preparing and filing the notice of exemption.
For non-exempt projects where the grantee is a public agency, the grantee will assume the role of lead agency. For non-exempt projects where the grantee is not a public agency (e.g., fire safe council), CAL FIRE or another public agency will need to assume the role of lead agency. The lead agency is responsible for: (a) performing the necessary environmental effects analysis; (b) preparing environmental documents; and (c) filing associated notices.
The lead agency may require the grantee to prepare, or retain a consultant to prepare, the environmental documents required for demonstrating adequate compliance with CEQA. When CAL FIRE is the lead agency, the grantee must work closely with CAL FIRE staff to ensure the environmental documents reflect CAL FIRE’s independent judgement. 1 “Public agency” includes the following:
PRC § 21062. “Local agency” means any public agency other than a state agency, board, or commission. For purposes of this division a
pg. 39
Grantees should ensure they ask for adequate funds for environmental work when applying for grants. When preparing their budgets, grantees should consider the need to contract with appropriate resource professionals to do the necessary environmental effects assessment and document preparation work. This may include biologists, professional archaeologists, air quality experts, registered professional foresters, environmental planners, etc.
For all environmental documents where CAL FIRE is the lead agency, except timber harvesting permits or notices, cultural resources must be assessed per the procedures outlined in Cultural Resources Review Procedures for CAL FIRE Projects. This may require the grantee to consult with the appropriate CAL FIRE archaeologist to determine if impacts to cultural resources are possible and what, if any, assessment or mitigation work will have to be done. This consultation should be done as early in the planning process as possible.
CAL FIRE must review all environmental documents and associated notices for adequate compliance with applicable procedures and CEQA.
redevelopment agency and a local agency formation commission are local agencies, and neither is a state agency, board, or commission.
PRC § 21063. “Public agency” includes any state agency, board, or commission, any county, city and county, city, regional agency, public district, redevelopment agency, or other political subdivision.
14 CCR § 15368 “Local agency” means any public agency other than a state agency, board, or commission. Local agency includes but is not limited to cities, counties, charter cities and counties, districts, school districts, special districts, redevelopment agencies, local agency formation commissions, and any board, commission, or organizational subdivision of a local agency when so designated by order or resolution of the governing legislative body of the local agency.
14 CCR § 15379 “Public agency” includes any state agency, board, or commission and any local or regional agency, as defined in these Guidelines. It does not include the courts of the state. This term does not include agencies of the federal government.
pg. 40
APPENDIX B – SAMPLE RESOLUTION (NOT REQUIRED)
pg. 41
APPENDIX C – INVOICE
INVOICE GUIDELINES
It is preferred, but is not required, that grantees use the invoice template posted on the CAL FIRE Grants website. Due to differences in accounting systems used by the grantee, the grantee must include the following elements when submitting a payment request, either on the grantee’s invoice or as an attachment to the invoice. If a grantee chooses to use their invoice in lieu of the invoice template provided, the invoice must be put on grantee’s official letterhead.
1. The word “Invoice” shall appear at the top of thepage.
2. Grantee Information – Includes the grantee name and address which shall match the Std. 204 - Payee Data Record submitted with the grant agreement. Payment will be submitted to this address after the financial report has been approved. Grantee shall notify CAL FIRE in writing regarding address changes and effectivedates.
3. Invoice Date and Number – Date invoice was issued and unique invoice number to be determined by the grantee for reference.
4. Grant Identification – Grant Number, Grant Performance Period, and Project Name as identified in the Grant Agreement.
5. Invoice reporting period – Performance start and end dates for which grantee is invoicing CAL FIRE. Under no circumstances will an invoice period outside of the grant performance period be accepted.
6. Payment Type – Indicate whether the invoice isto request an advance payment, interim payment, or final payment.
7. Cost breakdown – Grantee costs must be broken down by the budget item consistent with the approved budget in the Grant Agreement. The grantee must identify the amount for which CAL FIRE is being billed in the invoice period and the total amount spent and match (if applicable) from the beginning of the grant performance period through the invoice period. Advance requests should still include a breakdown of the budget items for which the grantee is planning to expend the funds.
8. Offset to current cost – Include the balance of advance funds given to grantee as well as program income earned from the grant if applicable.
9. The total amount for which grantee is requesting reimbursement from CAL FIRE.
10. Grantee contact name, phone number, and email addressfor questions related to the invoice.
11. All backup documentation to support the invoice (see Project Costssection).
12. Certification and signature of authorized representative - Please see sample invoice for certification language.
pg. 42
APPENDIX D – STATE OF CALIFORNIA STANDARD REQUIRED FORMS THESE STANDARD FORMS MUST BE SUBMITTED IN THE GRANTS PORTAL WITH THE PROJECT APPLICATION. THE STANDARD FORMS BELOW ARE ALSO LINKED IN THE GRANTS PORTAL.
Payee Data Record form (STD. 204) – CAL FIRE utilizes this form internally for all grantees. This form is required for all applicants, including local governments, despite the language on the form. Payee Data Record STD. 204
APPENDIX E – CALMAPPER (AWARDED GRANTS ONLY)
All California Climate Investments (CCI) and Prop 4 funded projects will be recorded in CAL FIRE’s Management Activity Project Planning & Event Reporter (CalMAPPER). To achieve this, grantees must provide spatial information via shapefiles about where the project occurs on the landscape, identify treatments for their project, and identify what activities occurred.
Submission of all activities completed must be submitted with invoices or other methods identified by the Grants Program. This may be requested as often as ground-disturbing work is performed.
APPENDIX F – LOW-INCOME AND DISADVANTAGED COMMUNITIES
California Climate Investments must meet minimum levels of investments to projects that benefit residents of disadvantaged communities, low-income communities, and low- income households collectively referred to as “priority populations” and defined by Health and Safety Code section 39713.
CAL FIRE’s Wildfire Prevention Grants Program and Forest Health Program has a goal of funding a percentage of projects that benefit Low-Income Communities or Households. This is not a requirement for eligibility, but preference will be given to projects that benefit a priority population.
Achieving “Low-Income Community or Household” designation requires three steps:
Step 1: Identify the Priority Population(s). Located within a census tract identified as a disadvantaged community or low-income community, or directly benefit residents of a lowincome household. California Air Resource Board’s Community Investments webpage may be used to identify the census tract.
Step 2: Address a Need. Meaningfully address an important community or household need for priority populations; and
Step 3: Provide a Benefit. Using the evaluation criteria, identify at least one direct, meaningful, and assured benefit that the project provides to priority populations.
The following tables will assist you in achieving the designation and can be found on the California Air Resources Board CCI Quantification, Benefits, and Reporting Materials webpage.
pg. 43
pg. 44
pg. 45
APPENDIX G – PDF PROJECT MAP
In addition to the online WP Grants Mapping Center project mapping program Geopoint and polygons, include a pdf map(s) of the project with the project application. The map(s) shall meet the following requirements:
• Electronic format of PDF.
• Printed format(s) should measure 8 ½ by 11 inches.
• The scale should be 1:24,000 scale or finer. The maps should show enough of the surrounding area so that the application review team can get a sense of the relationship of the project to the surrounding area.
• The map(s) should clearly show:
o Project boundaries
o Treatment area(s) by type
o Roads
o Watercourses
o Parcels
o City/County/Unit
o Proximity to wildfire threatened communities
o Other necessary information
• Legend: Include a map legend that identifies:
o The features on the map
o The project tracking number
o Project name
o Project proponent
APPENDIX H – JUSTIFICATION FOR INDIRECT COST RATE ABOVE 12% Applicants that utilize a higher indirect rate on non-CAL FIRE grants and agreements may request to apply an indirect cost rate in excess of 12% as part of their application. The request shall include a detailed justification as a separate attachment to the grant application indicating why a higher rate is needed for the grant project along with supporting documentation as to how the higher indirect rate is determined. Supporting documentation may include, but is not limited to, the entity’s Federally approved Negotiated Indirect Cost Rate Proposal. Under no circumstances will CAL FIRE approve an indirect rate exceeding 20% for CCI funded projects. Submittal of the justification and supporting documentation does not guarantee approval of the higher rate which is solely at CAL FIRE’s discretion.
Applicants requesting the higher rate may include the higher rate within the total application request and within the budget breakdown. CAL FIRE will evaluate the request for a higher indirect rate concurrently with the grant application. If the project is approved, but the higher indirect rate is not, CAL FIRE will notify the Grantee of the reduced award amount and request changes to the budget, if needed.
pg. 46
For grants awarded for projects under Proposition 4, Wildfire Prevention Grants will reimburse the grantee’s indirect costs. The grantee may request one of the following indirect cost rates:
• The grantee’s federal negotiated indirect cost rate, pursuant to its Negotiated Indirect Cost Rate Agreement (NICRA).
• The 15 percent de minimis indirect cost rate specified in Part 200 of Title 2 of the Code of Federal Regulations.
• A rate negotiated by the grantee with another state agency within the last five years. • A rate proposed by the grantee in the grantee’s program application with the administering state agency if the grantee does not have an existing state rate. • Grantee can request an indirect cost rate of 12% to 20%.
APPENDIX I – APPLICATION PACKAGE
A COMPLETE APPLICATION PACKAGE INCLUDES AND IS REQUIRED TO BE CONSIDERED:
Grants Portal (Solicitation Link on WP Grants website):
• Application
• Scope of Work
• Budget
• Goals
• File Uploads*
• Online submission of Geopoint or polygons in the Project MappingProgram *File uploads to Grants Portal:
• PDF version of Project Map(s) (formatted to 8 ½” x11”) • Articles of Incorporation, including document w/seal from Secretary of State (non- profit applicants)
• State of California Payee Data Record form (Std. 204) – see Appendix D • Letter(s) of Commitment if matching funds or services are included • Letter(s) of Support (not required)
• UC/CSU Model Agreement Template (Required for UC/CSU and associated auxiliary entities)
Board Resolution granting authority to sign if non-profit or local government, a signed resolution may be requested if necessary.
ZIP MULTIPLE FILES OF ONE TYPE, I.E., MULTIPLE LETTERS OF SUPPORT, TRAVEL POLICY (IF TRAVEL IS INCLUDED), FOR FUELS REDUCTION WORK; SHAPE FILES ARE REQUIRED, AND UPLOAD AS A SINGLE ZIP FILE.
pg. 47
APPENDIX J – ADDITIONAL RESOURCES
Local CAL FIRE Unit (Vegetation Management Foresters and Local Wildfire Prevention Grants Resources)
[email protected] (Southern Region Contact) [email protected] (Northern Region Contact)
[email protected] (Wildfire Prevention Grants Program Analysts) [email protected] (Grants Administration)
Subscribe to CAL FIRE grant email notifications to be notified when our workshops are scheduled and to receive solicitation announcements.
pg. 48
APPENDIX K – CALCULATING INTEREST ON ADVANCE PAYMENTS
Interest on Advance Payments must be reported on invoices as Program Income no less frequently than quarterly, unless otherwise waived by CAL FIRE. Documentation to be provided with the invoice should include a copy of the statement showing the grantee’s name, initial deposit of the advance funds into the account and the interest rate earned for each statement period associated with the invoice period reported until the advance funds have been fully liquidated. It is advised that the account number and other sensitive information be redacted from the bank statement.
Separate Account for Advance Payments: Advance funds deposited in a separate interestbearing account that is not comingled with any other funds should provide a copy of the statement showing the interest earned for each statement period. The amount reflected as interest earned on each statement should tie to the Program Income reported on the invoice, unless there is additional program income earned.
Co-mingled Advance Payments: Advance funds that are co-mingled with other funds shall include a copy of the statement for each statement period associated with the advance funds.
The calculation for the invoice period must be included and the total interest should tie to the Program Income reported on the invoice, unless there is additional program income earned. The interest earned can be calculated as:
Formula:
Remaining advance funds x interest rate % = Annual Interest.
Annual Interest/365 days =Daily Rate.
Daily Rate x number of days = Interest/Program Income
Use of an alternative calculation method based on the grantee’s accounting process may be accepted at CAL FIRE’s discretion.
RESOLUTION NO. 2025-
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF UKIAH AUTHORIZING AN APPLICATION TO THE CALIFORNIA CLIMATE INVESTMENTS AND PROPOSITION 4 DEPARTMENT OF FORESTRY AND
FIRE PROTECTION (CAL FIRE) WILDFIRE PREVENTION PROGRAM
WHEREAS, the CAL FIRE Community Wildfire Defense Grant provides funding up to $950,000 for a threeyear period of performance with no local match requirement to help communities plan for and mitigate wildfire risks; and
WHEREAS, this grant complements the existing USDA grant that funded the hiring of a dedicated fuels crew by providing the additional necessary equipment, planning documents to prioritize and coordinate ongoing projects, related CEQA, and providing important education and outreach pieces; and WHEREAS, this funding will allow the City to maintain and expand wildfire hazard mitigation efforts within the Ukiah Valley Fire District; and
WHEREAS, priority activities include maintaining the existing fire break in the western hills area now within city limits; supporting work beyond the original scope of the fuels crew grant; filling operational gaps; planning efforts, and community education and outreach initiatives.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Ukiah hereby:
1. Approves the filing of an application for the Community Wildfire Defense Grant; and
2. Certifies that applicant understands the assurances and certification in the application; and
3. Certifies that applicant or title holder will have sufficient funds to operate and maintain the project consistent with the grant requirements; or will secure the resources to do so; and
4. If applicable, certifies that the project will comply with any laws and regulations including, but not limited to, legal requirements for building codes, health and safety codes, disabled access laws, environmental laws; and
5. Certifies that applicant will work towards the Wildfire Prevention Program Grant Guidelines and Priorities intended to increase protection of people, structures, and communities through hazardous fuels reductions, wildfire prevention planning and education, and improving public health and safety while reducing greenhouse gas emissions; and
6. Appoints the City Manager, or designee, as agent to conduct all negotiations, execute and submit all documents including, but not limited to applications, agreements, payment requests and so on, which may be necessary for the completion of the aforementioned project(s).
PASSED AND ADOPTED this 16th day of July, 2025, by the following roll call vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
Douglas F. Crane, Mayor
ATTEST:
Kristine Lawler, City Clerk
Attachment 2
Agenda Item No: 8.g.
MEETING DATE/TIME: 7/16/2025
ITEM NO: 2025-823
AGENDA SUMMARY REPORT
SUBJECT: Adoption of Resolution Reappointing Gregory Andronaco to the Airport Commission.
DEPARTMENT: City Clerk PREPARED BY: Araceli Sandoval, Deputy City Clerk PRESENTER: Consent Calendar
ATTACHMENTS:
1. Resolution 2014-48
2. Andronaco - Application and Nomination
3. Proposed Resolution
Summary: The City Council will consider adopting a resolution reappointing Gregory Andronaco to the Airport Commission in the 'County Resident' position, term ending July 16, 2028.
Background: The Airport Commission serves in an advisory capacity to the City Council on all matters pertaining to the operations of the municipal airport. The commission aids and advises the City Manager in the selection of personnel for the operation of the municipal airport in accordance with the civil service ordinance.
Pursuant to Resolution 2014-48 (Attachment 1), the Airport Commission has had a vacancy that has been noticed since May 2025, following the expiration of Gregory Andronaco's term. As no applications were received for the position, Mr. Andronaco expressed interest in reapplying for the “County Resident” seat (Attachment 2 – Application and Nomination).
In accordance with Resolution 2014-48, the right to nominate a candidate rotates among the Councilmembers.
Councilmember Criss, as the next Councilmember eligible to nominate, has nominated Mr. Andronaco for reappointment to the Airport Commission (Attachment 2).
Discussion: Staff recommends Council adopt the resolution (Attachment 3) reappointing Gregory Andronaco to 'County Resident' position on the Airport Commission, term ending July 16, 2028.
Recommended Action: Adopt resolution reappointing Gregory Andronaco to the 'County Resident' position on the Airport Commission, term to expire July 16, 2028.
BUDGET AMENDMENT REQUIRED: N/A
CURRENT BUDGET AMOUNT: N/A
PROPOSED BUDGET AMOUNT: N/A
FINANCING SOURCE: N/A
REVENUE: No GRANT: No
PREVIOUS CONTRACT/PURCHASE ORDER NO.: N/A
COORDINATED WITH: N/A
STRATEGIC PLAN (SP): N/A
CLIMATE INITIATIVES (CI): N/A
GENERAL PLAN ELEMENTS (GP): N/A
ATTACHMENT 1
Attachment 2
Original application from 2022
1. Why are you applying to serve on the City of Ukiah’s Airport Commission? I have a business at KUKI on the flight line just north of FedEx. I would like to get more involved with the airport and help with planning.
2. What is your understanding of the purpose, role, and responsibility of the Airport Commission? I am assuming it is an advisory roll to help the BOS and City Council.
3. What do you believe are the three most important Airport related issues facing our community and why?
1) Calfire – They saved my farm during the Mendo Complex fire 2) Reach/Calstar - Moving helicopters away from other work areas 3) More hangar space
4. In your opinion, what type of Airport programs or Airport development should the City encourage? I’d like to see more involvement with younger people in high school and community college. It is sad the programs at Mendocino College have been canceled. I currently have an intern from South Valley. I guess because of the pandemic, the airport day we used to have needed to be canceled. I would like to see this happen again when feasible. More community outreach to let folks know that KUKI is not like a golf course. It is a viable city asset.
5. In your opinion, what type of Airport programs or Airport development should the City discourage? Homeless encampments.
6. What kind of ideal community do you envision for Ukiah? Ukiah is pretty ideal. This is why I moved here from the bay area. I do worry about her getting gentrified. I am glad to see more housing being built. We own three house rentals in the city. Housing prices and rent are unreal. We keep a small studio in one of the houses to have a place to stay without driving back out to RWV, after dinner out or a concert in the park.
7. Do you have any known projects or conflict of interest related to this Commission (business and/or personal)?
I do have a business at KUKI, yet I don’t see that as a conflict. Also, I have a private pilot’s license and love to fly. I don’t see this as a conflict either. I view these as enhancements to perspective. I learned about this area from hang gliding. This is how I started out flying. As I got older, and don’t heal as well, I transitioned to airplanes.
8. How do you believe your own skills, experience, expertise and perspectives will be beneficial to the work of the Airport Commission?
I have lived many places and worked at many different occupations. I have a pretty broad perspective and experience with many different people and ideas. I like people and like working together to accomplish common goals and have fun at the same time. I like the whole aviation community. Below is a link to a portfolio of work and resumes of previous occupations. https://www.dropbox.com/sh/hyipbd7hq74gzv4/AAAGHadqg75J 5W8B6eATu5Ia?dl=0
9. Are there any other City of Ukiah Committees/Commissions in which you are interested and on which you would be willing to serve?
Give me a chance to serve on this one first...
MEMORANDUM
Date: July 7, 2025
To: Kristine Lawler, City Clerk
From: Heather Criss, Councilmember
Subject: Nomination for Airport Commission
I nominate Gregory Andronaco for the Airport Commission as County Resident Representative, to be considered at the July 16, 2025, Regular City Council meeting.
Signature ______________________________
Heather Criss (Jul 7, 2025 15:38 PDT) Page 1106 of 1257
RESOLUTION NO. 2025-X
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF UKIAH REAPPOINTING GREGORY
ANDRONACO TO THE AIRPORT COMMISSION
WHEREAS, a list of current vacancies along with the full roster of Boards and Commissions is updated with each appointment and posted throughout the year online, in the glass case in front of Civic Hall, and at the County Library; and
WHEREAS, there is currently a vacant seat designated for either a City or County Resident Representative due to a term expiration, which has been noticed since May of 2025; and WHEREAS, an application has been received from Gregory Andronaco seeking reappointment, with no other applications having been received; and
WHEREAS, in respect to the Airport Commission, Resolution 2014-48, which amends the procedures for filling vacancies on City Boards and Commissions, states that the right to nominate a candidate from the available pool shall rotate among the Councilmembers; and WHEREAS, Councilmember Criss, being next in line to make nominations to the Airport Commission, has nominated Gregory Andronaco to the County Resident position; and WHEREAS, the City Council met on July 16, 2025, and reviewed the application.
NOW, THEREFORE, BE IT RESOLVED, that the Ukiah City Council approves the nomination, and does hereby appoint the following individual and term:
BOARD/
COMMISSION
NAME POSITION NOMINATED BY
COUNCILMEMBER
TERM
EXPIRATION
Airport Commission Gregory
Andronaco County Resident Criss July 16, 2028
PASSED AND ADOPTED this 16th day of July, 2025, by the following roll call vote:
AYES:
NOES:
ABSTAIN:
ABSENT:
Douglas F. Crane, Mayor
ATTEST:
Kristine Lawler, City Clerk
Attachment 3
Agenda Item No: 8.h.
MEETING DATE/TIME: 7/16/2025
ITEM NO: 2025-828
AGENDA SUMMARY REPORT
SUBJECT: Authorize the City Manager to Negotiate and Execute a One-Year Extension to the Cooperative Agreement for Dispatch Services with the California Department of Forestry and Fire Protection.
DEPARTMENT: Fire PREPARED BY: Traci Boyl, Senior Management Analyst PRESENTER: Doug Hutchison, Fire Chief
ATTACHMENTS:
1. Current Dispatch Agreement
2. Ukiah last agreement Calculator (003)
Summary: Council will consider authorizing the City Manager to negotiate and execute a one-year extension to the cooperative agreement for dispatch services with the California Department of Forestry and Fire Protection.
Background: Since 2012, the City of Ukiah has contracted with the California Department of Forestry and Fire Protection (CAL FIRE) for dispatching fire and emergency medical services within the city. The current cooperative agreement (Attachment 1) expired June 30, 2025.
Discussion: Dispatch services for fire and emergency medical response are currently provided by the California Department of Forestry and Fire Protection (CAL FIRE). City staff are actively working with CAL FIRE to finalize a one-year extension of the existing agreement. The goal is to align the City's contract with the County’s dispatch agreement, promoting a more coordinated and efficient emergency response countywide.
The draft agreement is expected within the next few weeks and will reflect updated salary and benefit rates for two Communications Operators (Attachment 2). Actual expenses for the two Communications Operators in FY 25 were $287,474. Funding for this agreement has been included in the proposed FY26 budget as follows:10521210.52100: $210,000; 71021100.52100; $241,000.00: 71021150.52100: $30,000 Staff requests Council authorize the City Manager to negotiate and execute a one-year extension to the cooperative agreement for dispatch services with the California Department of Forestry and Fire Protection.
Recommended Action: Authorize the City Manager to negotiate and execute a one-year extension to the agreement for dispatch services with the California Department of Forestry and Fire Protection.
BUDGET AMENDMENT REQUIRED: No.
CURRENT BUDGET AMOUNT: 10521210.52100: $210,000; 71021100.52100; $241,000.00:
71021150.52100: $30,000
PROPOSED BUDGET AMOUNT: N/A
FINANCING SOURCE: Cost share with Ukiah Valley Fire District.
REVENUE: Yes/No GRANT: Yes/No
PREVIOUS CONTRACT/PURCHASE ORDER NO.: N/A
COORDINATED WITH: Doug Hutchison- Fire Chief; Justin Buckingham, Battalion Chief STRATEGIC PLAN (SP): SP 1A - Build neighborhoods that provide access for all to a compatible balance of housing, employment, commercial, medical, education, and recreational resources.
CLIMATE INITIATIVES (CI):
GENERAL PLAN ELEMENTS (GP): GP-A6 - Safety Element
COOPERATIVE FIRE PROGRAMS
FIRE PROTECTION REIMBURSEMENT AGREEMENT
LG-1 REV. 11/2020
AGREEMENT NUMBER 1CA05265
REGISTRATION NUMBER:
1. This Agreement is entered into between the State Agency and the Local Agency named below:
STATE AGENCY'S NAME
California Department of Forestry and Fire Protection – (CAL FIRE) LOCAL AGENCY’S NAME
City of Ukiah
2. The term of this Agreement is: July 1, 2021 through June 30, 2025
3. The maximum amount of this
Agreement is:
$ 1,540,822.00
One million, five hundred forty thousand, eight hundred twenty two dollars and zero cents
4. The parties agree to comply with the terms and conditions of the following exhibits which are by this reference made a part of the Agreement.
Exhibit A – Scope of Work – Includes page 2 (contact page) in count for Exhibit A 4 pages Exhibit B – Budget Detail and Payment Provisions 2 pages Exhibit C – General Terms and Conditions 7 pages
Exhibit D – Additional Provisions 5 pages
Exhibit E – Description of Other Services 3 pages
IN WITNESS WHEREOF, this Agreement has been executed by the parties hereto.
LOCAL AGENCY California Department of General
Services Use Only LOCAL AGENCY’S NAME
City of Ukiah
BY (Authorized Signature) DATE SIGNED(Do not type)
PRINTED NAME AND TITLE OF PERSON SIGNING
Sage Sangiacomo, City Manager
ADDRESS
300 Seminary Avenue, Ukiah, CA 95482
STATE OF CALIFORNIA
AGENCY NAME
California Department of Forestry and Fire Protection
BY (Authorized Signature) DATE SIGNED(Do not type)
PRINTED NAME AND TITLE OF PERSON SIGNING
Chris Anthony, Assistant Deputy Director, Cooperative Fire Protection, Training & Safety ADDRESS P.O. Box 944246, Sacramento, CA 94244-2460
ATTACHMENT 1
Contractor Name: City of Ukiah
Contract No.: 1CA05265
Page No.: 2
EXHIBIT A
COOPERATIVE FIRE PROGRAMS
FIRE PROTECTION REIMBURSEMENT AGREEMENT
The project representatives during the term of this agreement will be:
CAL FIRE Unit Chief: Mendocino Unit Local Agency: City of Ukiah Name: George Gonzalez Name: Doug Hutchinson
Phone: (707) 459-7400 Phone: (707) 462-7921
Fax: (707) 459-3041 Fax: (707) 462-2938
All required correspondence shall be sent through U.S. Postal Service by certified mail and directed to:
CAL FIRE Unit Chief: George Gonzalez Local Agency: City of Ukiah Section/Unit: Mendocino Unit Section/Unit: City of Ukiah Attention: Brandon Gunn Attention: Sage Sangiacomo
Address: 17501 N. Hwy 101
Willits, CA 95490
Address: 300 Seminary Ave
Ukiah, CA 95482
Phone: (707) 459-7402 Phone: (707) 463-6221
Fax: (707) 459-3041 Fax:
Send an additional copy of all correspondence to:
CAL FIRE
Cooperative Fire Services
P.O. Box 944246
Sacramento, CA 94244-2460
AUTHORIZATION
As used herein, Director shall mean Director of CAL FIRE. This agreement, its terms and conditions are authorized under the Public Resources Code Sections 4141, 4142, 4143 and 4144, as applicable.
Contractor Name: City of Ukiah
Contract No.: 1CA05265
Page No.: 3
EXHIBIT A
SCOPE OF WORK
Under Public Resources Code Section 4114 and other provisions of law, STATE maintains fire prevention and fire suppression forces including the necessary equipment, personnel, and facilities required to prevent and extinguish forest fires.
The purpose of this agreement is to provide mutually advantageous fire and emergency services through an effective consolidated organization, wherein the STATE is primarily financially responsible for protecting natural resources from vegetation fires and the LOCAL AGENCY is primarily financially responsible for protecting life and property from fires and other emergencies. The LOCAL AGENCY shall have sole authority to establish the fire protection organization and structure needed to meet the determined level of service. This level of service may be based on the LOCAL AGENCY governing board’s established fiscal parameters and assessment of risks and hazards. LOCAL AGENCY personnel providing services under this agreement may include any one or a combination of the following: regular employees, persons temporarily employed and commonly known as volunteers, paid-call firefighters, or others temporarily employed to perform any emergency work or emergency service including, but not limited to fire prevention, fire suppression and emergency medical response.
To comply with the STATE’s mandate for full cost recovery of goods and services provided for others, the LOCAL AGENCY shall be responsible for all STATE costs, both direct and indirect, required to execute the terms of this agreement. These costs shall include, but not be limited to: required training and associated post coverage, employee uniform and Personal Protective Equipment (PPE) costs.
1. FIRE PROTECTION SERVICES TO BE PROVIDED BY THE STATE STATE provides a modern, full service fire protection and emergency incident management agency that provides comprehensive fire protection and other emergency incident response. STATE designs regional fire protection solutions for urban and rural communities by efficiently utilizing all emergency protection resources. Regional solutions provide the most effective method of protecting the citizens of California at local, county and state levels.
Fire protection services to be provided by STATE under this agreement shall include the following:
(check boxes below that apply)
1) Emergency Fire Protection, Medical and Rescue Response: services include commercial, residential, and wildland fire protection, prevention and investigation; hazardous materials incident response; emergency vehicle extrication; hazardous conditions response (flooding, downed power lines, earthquake, terrorist incident, etc.); emergency medical and rescue response; and public service assistance. Also included are management support services that include fire department administration, training and safety, personnel, finance and logistical support.
2) Basic Life Support Services: emergency medical technician (EMT) level emergency medical response providing first aid, basic life support (BLS), airway management, administration of oxygen, bleeding control, and life support system stabilization until patients are transported to the nearest emergency care facility.
3) Advanced Life Support Services: paramedic level emergency medical response providing early advanced airway management, intravenous drug therapy, and life support system stabilization until patients are transported to the nearest emergency care facility. 4) Dispatch Services: provide fire department 9-1-1 emergency dispatch by CAL FIRE Fire/Emergency Command Center (ECC). CAL FIRE will be responsible for fire/emergency
Contractor Name: City of Ukiah
Contract No.: 1CA05265
Page No.: 4
dispatching emergency resource units covered under this agreement. The CAL FIRE ECC is staffed with a Battalion Chief, three or more Fire Captains and Communications Operators to provide 24/7 year-round coverage. There is always an officer of Captain rank or higher to serve as the shift supervisor and command officer. CAL FIRE uses an integrated Computer Aided Dispatch (CAD) system using the latest technology, to direct the closest available resources to all emergency incidents.
5) Fire Code Inspection, Prevention and Enforcement Services: CAL FIRE has staff Fire Inspectors serving under the direction of the LOCAL AGENCY Fire Marshal to provide services to the area covered by this agreement. Fire Code Enforcement will normally be available five days per week, with emergency or scheduled enforcement inspections available seven days per week.
Fire Prevention and Investigation services will be provided by CAL FIRE Prevention Officers trained in arson, commercial, and wildland fire investigation. Officers are available by appointment for site visits and consultations. Officers are trained at CAL FIRE’s Peace Officer Standard Training (POST) certified law enforcement training academy and they cooperate effectively with all local, state and federal law enforcement agencies.
6) Land Use/ Pre-Fire Planning Services – CAL FIRE staff will provide community land use planning, administration of Pre-Fire project work, including community outreach, development of community education programs, project quality control, maintenance of project records and submittal of progress reports, completion of required environmental documentation, acquisition of required permits and completion of other associated administrative duties. 7) Disaster planning services (listed in Exhibit E, Description of Other Services, attached hereto and made a part of this agreement)
8) Specific service descriptions and staffing coverage, by station (listed in Exhibit E, Description of Other Services, attached hereto and made a part of this agreement) 9) Extended Fire Protection Service Availability (Amador)
2. ADMINISTRATION
Under the requirements of California Public Resources Code Section 4114 and other provisions of law, STATE maintains fire prevention and firefighting services as outlined in Exhibit D, Schedule B of this agreement.
A. Director shall select and employ a Region Chief who shall, under the direction of the Director/Chief Deputy Director, manage all aspects of fire prevention and fire protection services and forestry-related programs.
B. Director will select and employ a Unit Chief who shall, under the supervision and direction of Director/Region Chief or a lawful representative, have charge of the organization described in Exhibit D, Schedules A, B and C included hereto and made a part of this agreement.
C. LOCAL AGENCY shall appoint the Unit Chief as the LOCAL AGENCY Fire Chief for all Emergency Fire Protection, Medical and Rescue Response Agreements, pursuant to applicable statutory authority. The Unit Chief may delegate this responsibility to qualified staff.
D. The Unit Chief may dispatch personnel and equipment listed in Exhibit D, Schedules A, B and C from the assigned station or location under guidelines established by LOCAL AGENCY and approved by STATE. Personnel and/or equipment listed in Exhibit D, Schedule B may be dispatched at the sole discretion of STATE.
Contractor Name: City of Ukiah
Contract No.: 1CA05265
Page No.: 5
E. The Unit Chief shall exercise professional judgment consistent with STATE policy and his or her employment by STATE in authorizing or making any assignments to emergencies and other responses, including assignments made in response to requests for mutual aid.
F. Except as may be otherwise provided for in this agreement, STATE shall not incur any obligation on the part of LOCAL AGENCY to pay for any labor, materials, supplies or services beyond the total set forth in the respective Exhibit D, Schedules A and C, as to the services to be rendered pursuant to each Schedule.
G. Nothing herein shall alter or amend or be construed to alter or amend any Collective Bargaining Agreement or Memorandum of Understanding between the State of California and its employees under the State Employer-Employee Relations Act.
3. SUPPRESSION COST RECOVERY
As provided in Health and Safety Code (H&SC) Section 13009, STATE may bring an action for collection of suppression costs of any fire caused by negligence, violation of law, or failure to correct noticed fire safety violations. When using LOCAL AGENCY equipment and personnel under the terms of this agreement, STATE may, at the request of LOCAL AGENCY, bring such an action for collection of costs incurred by LOCAL AGENCY. In such a case LOCAL AGENCY appoints and designates STATE as its agent in said collection proceedings. In the event of recovery, STATE shall deduct fees and litigation costs in a proportional percentage amount based on verifiable and justifiable suppression costs for the fire at issue. These recovery costs are for services provided which are beyond the scope of those covered by the local government administrative fee.
In all such instances, STATE shall give timely notice of the possible application of H&SC Section 13009 to the representative designated by LOCAL AGENCY.
4. MUTUAL AID
When rendering mutual aid or assistance as authorized in H&SC Sections 13050 and 13054, STATE may, at the request of LOCAL AGENCY, demand payment of charges and seek reimbursement of LOCAL AGENCY costs for personnel, equipment and operating expenses as funded herein, under authority given by H&SC Sections 13051 and 13054. STATE, in seeking said reimbursement pursuant to such request of LOCAL AGENCY, shall represent LOCAL AGENCY by following the procedures set forth in H&SC Section 13052. Any recovery of LOCAL AGENCY costs, less expenses, shall be paid or credited to LOCAL AGENCY, as directed by LOCAL AGENCY.
In all such instances, STATE shall give timely notice of the possible application of H&SC Sections 13051 and 13054 to the officer designated by LOCAL AGENCY.
5. PROPERTY PURCHASE AND ACCOUNTING
LOCAL AGENCY shall be responsible for all costs associated with property required by personnel to carry out this agreement. Employee uniform costs will be assessed to the LOCAL AGENCY through the agreement billing process. Personal Protective Equipment (PPE) costs shall be the responsibility of the LOCAL AGENCY. By mutual agreement, PPE meeting the minimum specifications established by the STATE may be purchased directly by the LOCAL AGENCY. Alternately, the STATE will supply all PPE and the LOCAL AGENCY will be billed for costs incurred.
All property provided by LOCAL AGENCY and by STATE for the purpose of providing fire protection services shall be marked and accounted for by the Unit Chief in such a manner as to conform to the regulations, if any, established by the parties for the segregation, care, and use of the respective properties.