Extracted automatically — check the source. These rows were read out of the cities' own agendas, staff reports and minutes by a language model (claude-haiku-5-5/v5) on 2026-10-20. Each amount links to the passage it came from and each row to the city's original file, which is the official record. Rows marked check had a problem the checks caught.
11actions
6vendors
$13,315,390approved (recorded vote)
$12,454,457proposed, no vote in the index
Dollar totals add the amount each action states: an amendment's new total can repeat an earlier award, and annual amounts are counted once. Use them as a rough size, the rows for detail.
Actions
| Date | Vendor | Item | Action | Amount | Size · price · savings | Outcome | Sources |
|---|---|---|---|---|---|---|---|
| 2025-09-23 | Willdan | Amendment No. 1 to the Energy and Water Savings Performance Contract with Willdan Energy Solutions, Inc. (WES) for the Energy Efficiency and Infrastructure Impr Efficiency retrofits and ESPCs | Renewal / extension | $12,320,387 | Annual savings from AMI meters anticipated to exceed annual lease paym… | No vote recorded | packet · city original |
| 2025-02-11 | ChargePoint | CHARGEPOINT EV CHARGING STATION MAINTENANCE/SERVICE AGREEMENT AND EQUIPMENT PROCUREMENT FOR DILLS PARK check EV charging | Award | $86,421 | four (4) dual EV charging stations at Dills Park; 12 stations (22 port… $0.20/kWh usage rate | Approved AYES: Councilmembers Aguayo, Olmos, Cuellar Stallings; Vice Mayor Lemons; and… | agenda · minutes · packet · packet · city original |
| 2024-06-25 | AMTEK Construction | ACCEPTANCE OF WORK – LED LIGHTING CONVERSION (CITY PROJECT NO. 9490) Efficiency retrofits and ESPCs | Other | $84,070 | No vote recorded | packet · city original | |
| 2024-03-12 | AMTEK Construction | AWARD OF CONTRACT LED LIGHTING CONVERSION (CITY PROJECT NO. 9490) LED streetlights | Award | $79,933 | Approved AYES: Councilmembers Lemons, Cuellar Stallings; Vice Mayor Delgadillo and… | agenda · minutes · packet · packet · city original | |
| 2023-12-12 | Willdan | Resolution No. 23:037 Adopting certain findings and approving the Energy Service Contract for energy related improvements to City facilities and infrastructure check Bundles | Award | $12,724,773 | Approved AYES: Councilmembers Lemons, Olmos, Cuellar Stallings; and Mayor Aguayo; NOES:… | packet · packet · city original | |
| 2023-12-12 | Willdan | Energy and Water Savings Performance Contract with Willdan Energy Solutions (Two-Phase ESPC, Resolution No. 23-037) check Efficiency retrofits and ESPCs | Award | — | Approved | packet · city original | |
| 2023-03-28 | Willdan | Approval of Contingent Design and Engineering Services Agreement with Willdan Energy Solutions for Efficiency and Infrastructure Improvement Projects and Consid Efficiency retrofits and ESPCs | Award | $50,000 | No vote recorded | packet · city original | |
| 2022-09-06 | ChargePoint | Authorization to Purchase Electric Vehicle Charging Stations for Charge Ready Program EV charging | Purchase order | $164,595 | Approved AYES: Councilmembers Delgadillo, Lemons, Olmos; Vice Mayor Aguayo; and Mayor… | minutes · packet · city original | |
| 2022-07-12 | Smart City Electric | AWARD OF CONTRACT FOR ELECTRIC VEHICLE CHARGING STATIONS (CITY PROJECT NO. 9290) EV charging | Award | $162,000 not to exceed | three additional EVCS at City Hall, Substation, and City Yard | Approved AYES: Councilmembers Delgadillo, Lemons, Olmos; Vice Mayor Aguayo; and Mayor… | minutes · packet · packet · city original |
| 2022-06-21 | Southern California Edison | Resolution No. 22:039 Authorizing the City Manager to execute all agreements with Southern California Edison for the Charge Ready Program EV charging | Award | — | 12 charging ports at Paramount Park and 12 charging ports at Progress … | No vote recorded | packet · city original |
| 2022-05-03 | Junior’s Construction | AWARD OF CONTRACT City Hall LED Retrofit Lighting (City Project No. 9293) Efficiency retrofits and ESPCs | Award | $97,668 | Approved AYES: Councilmembers Guillen, Lemons, Olmos; Vice Mayor Aguayo; and Mayor… | minutes · packet · packet · city original |