SUMMARY
Staff recommends approval of a contract purchase agreement with Burns & McDonnell Western Enterprises Inc. in the amount of $985,000 to provide data migration consulting services to migrate the current Geographic Information System Esri data to the Utility Network data structure. Partial funding for planned work in FY2026-27 is included within the Electric - Geographic Information System Upgrade Project budget for FY2026-27. Any future funding necessary will be included in proposed capital improvement project budgets and is contingent on City Council approval.
RECOMMENDATION
Staff recommends that the City Council adopt a resolution to approve Contract Purchase Agreement (3005881) with Burns & McDonnell Western Enterprises, Inc. for data migration consulting services to migrate the current GIS Esri data to the Utility Network data structure and authorize the City Manager to execute it on behalf of the City of Roseville.
BACKGROUND
The Electric Department is initiating a project to update and standardize its Geographic Information System (GIS) by migrating from Esri’s 10.8.1 platform and a legacy geometric network model to Esri’s Utility Network model on version 11.1. This transition reflects the City’s ongoing commitment to maintaining a resilient, scalable, and future-ready GIS infrastructure aligned with industry best practices. As part of the migration to the Utility Network, this project will also be upgrading Schneider Electric’s ArcFM solution to a version supporting Esri’s ArcGIS Enterprise 11.1. The Electric Department uses ArcFM to support designing, editing, and managing workflows.
Roseville Electric solicited proposals through Request for Proposal No. 07-104 GIS Esri Utility Network Data Migration. Eleven (11) vendor proposals were received and evaluated based on qualifications of firm and team, experience, references, project understanding and plan, and required documents. The evaluation team reviewed and scored the vendor proposals, selecting Burns & McDonnell Western Enterprises Inc. as the firm to provide the requested scope of services.
FISCAL IMPACT
The total cost of the agreement will not exceed $985,000. Partial funding for planned work in FY2026-27 is included within the Electric - Geographic Information System Upgrade Project budget for FY2026-27. Any future funding necessary will be included in proposed capital improvement project budgets and is contingent on City Council approval.
ENVIRONMENTAL REVIEW
The California Environmental Quality Act (CEQA) only applies to projects which have the potential to cause a significant effect on the environment. Where it can be seen with certainty that there is no possibility that the activity in question may have a significant effect on the environment, the activity is not subject to CEQA. (CEQA Guidelines §15061(b)(3)). Approval of the Contract Purchase Agreement with Burns & McDonnell Western Enterprises Inc. meets the above criteria and is not subject to CEQA. No additional environmental review is required.
CITY COUNCIL STRATEGIC PLAN/OVERARCHING GOALS
4. Invest in well-planned infrastructure and growth
Respectfully Submitted,
Steve Hancock, Senior Electric Business Analyst
Chris Porter, Assistant Electric Utility Director
Daniel Beans, Electric Utility Director
ATTACHMENTS:
1. Resolution 26-376
2. CPA 3005881
3. Proposal
4. Project Schedule
5. Scope of Work
6. RFP 07-104
7. Master Averaged Score Sheet
8. Notice of Intent to Award
REVIEWERS:
Steve Hancock, Electric Department - Financial & Administrative Created/Initiated - 9/13/2026 Chris Porter, Electric Department - Engineering Approved - 9/17/2026 Shawn Matchim, Electric Department - All Approved - 9/18/2026 Daniel Beans, Electric Department - All Approved - 9/18/2026 Kelly Aye, City Attorney Department Approved - 9/23/2026 Katrina Six, City Clerk Department Approved - 9/24/2026 Ryan DeVore, City Clerk Department Approved - 9/25/2026 Dennis Kauffman, City Manager Department - Assistant City Manager Approved - 9/28/2026 Michelle Sheidenberger, City Attorney Department Approved - 9/28/2026 Dominick Casey, City Clerk Department Approved - 9/28/2026 Katrina Six, City Clerk Department Final Approval - 9/28/2026
RESOLUTION NO. 26-376
APPROVING A CONTRACT PURCHASE AGREEMENT, BY AND BETWEEN THE CITY OF ROSEVILLE AND BURNS & MCDONNELL WESTERN ENTERPRISES, INC., AND
AUTHORIZING THE CITY MANAGER TO EXECUTE IT ON BEHALF OF
THE CITY OF ROSEVILLE
WHEREAS, the Contract Purchase Agreement (3005881) for Geographical Information System (GIS) ESRI Utility Network Data Migration, by and between the City of Roseville and Burns & McDonnell Western Enterprises, Inc., has been reviewed by the City Council; and NOW, THEREFORE, BE IT RESOLVED by the Council of the City of Roseville that said agreement is hereby approved and the City Manager is authorized to execute it on behalf of the City of Roseville.
PASSED AND ADOPTED by the Council of the City of Roseville this ___ day of ______________, 2026, by the following vote on roll call:
AYES COUNCILMEMBERS:
NOES COUNCILMEMBERS:
ABSENT COUNCILMEMBERS:
______________________________
MAYOR
ATTEST:
________________________
City Clerk
Contract Purchase Agreement 3005881
Supplier Details:
Company Burns & McDonnell Western Enterprises Inc
Contact Chad R. Pinarija
Address 145 S State College Blvd Ste 600
Brea, CA 92821
Submit your response to:
Company City of Roseville
Contact Erica Kaminski
Address Purchasing Division
311 Vernon St
Roseville, CA 95678
Phone (916) 746-1108
Fax (916) 746-1115
E-mail [email protected]
This Contract Purchase Agreement is sent for your review and acceptance. Notify the Buyer via email of any needed changes to the company name, address, and contact information. The Buyer will update the agreement prior to you signing the document.
Return signed copies of the agreement to the Buyer noted on the agreement. Alterations or modifications to the agreement are not allowed. Upon receipt of all necessary documents, the City will sign the agreement and return a fully executed copy to you. Receipt of the signed copy will be your notice to proceed with the work in accordance with the terms and conditions of the agreement. Work must not begin until the contract has been fully executed.
The following guidelines must be followed for the signature block on the agreement:
Sole proprietorship - By owner
Partnership - Any general partner
Corporation - Two options:
(1) A signature from the President and the corporate seal; OR (2) One signature from the Chairman of the Board, President, or any Vice President AND one signature from the Secretary, any Assistant Secretary, Chief Financial Officer, or any Treasurer or Assistant Treasurer of the corporation
*General Manager, Office Manager and/or Sales Manager are not corporate officer titles. The agreement will be rejected if not signed in accordance with these guidelines.
Insurance requirements:
The City's insurance requirements are referenced on Attachment A of the agreement. By signing the agreement, you are confirming that your company has the insurance limits required. 1 Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Contract Purchase Agreement 3005881
Agreement 3005881
Agreement Date 04-SEP-2026
Revision 0
Agreement Amount 985,000.00 USD
Invoice To City of Roseville
Accounts Payable
311 Vernon St
ROSEVILLE CA 95678
Supplier Burns & McDonnell Western Enterprises Inc
145 S State College Blvd Ste 600
Brea, CA 92821
Phone:
Fax:
Email:
(916) 774-5488
(916) 784-3796
[email protected]
Phone:
Fax:
Email:
(949) 293-1584
()
[email protected]
Description of
Labor,
equipment
and/or materials
THE VENDOR SHALL PROVIDE THE SERVICES CALLED FOR UNDER THE CITY OF ROSEVILLE REQUEST FOR PROPOSALS (RFP) 07-104 FOR GIS ESRI UTILITY
NETWORK DATA MIGRATION AND CONTRACTOR'S PROPOSAL THERETO TITLED "PROPOSAL FOR GIS ESRI UTILITY NETWORK DATA MIGRATION RFP 07-104" (HEREINAFTER "PROPOSAL") DATED 1/14/26, AS SUPPLEMENTED AND CLARIFIED BY VENDOR'S SUBSEQUENT STATEMENT OF WORK DATED 6/2/26. IN
THE EVENT OF ANY CONFLICT BETWEEN THE PROPOSAL AND THE
STATEMENT OF WORK, THE STATEMENT OF WORK SHALL CONTROL. THE TERMS AND SCOPE OF WORK OF CITY OF ROSEVILLE RFP 07-104,
CONTRACTOR'S PROPOSAL, AND STATEMENT OF WORK ARE HEREIN MADE PART OF THIS AGREEMENT AND FULLY INCORPORATED BY REFERENCE.
START DATE: EXECUTED AGREEMENT
END DATE: ONE YEAR FROM ACCEPTANCE OF PRODUCTION MIGRATION PLEASE CONTACT STEVE HANCOCK IN THE ELECTRIC DEPARTMENT AT (916) 774-5631 OR [email protected] FOR ANY QUESTIONS REGARDING THIS AGREEMENT.
Customer # Supplier # Payment Terms Freight Terms FOB Shipping Method 16921 Net 30 Freight on Board at the destination Destination Best Method Start Date End Date Confirm To
Erica Kaminski Phone 1-916-746-1108
Attention: Total Cost not to exceed the agreement amount without prior approval of the Purchasing office. 2 Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Contract Purchase Agreement 3005881
Contract Terms and Conditions
1. To the fullest extent allowed by law, Consultant shall indemnify (but not defend) City, its officers, and employees from any liabilities, damages, or other losses of third parties arising out of injuries to or death of any person or damage to property, to the extent caused by Consultant's willful misconduct or negligent act or omission while engaged in the performance of obligations or exercise of rights created by this Agreement. City shall be responsible for its proportionate fault to the extent caused by the City's negligence or willful misconduct. Consultant's indemnity obligations shall survive the termination or completion of this Agreement for the full period of time allowed by law.
2. Consultant is an independent contractor, and shall not be considered an officer, agent, or employee of the City.
3. Without the written consent of the City, this Agreement is not assignable by Consultant either in whole or in part.
4. Time is of Material Importance. The parties shall make commercially reasonable efforts to adhere to the timelines specified in the Scope of Services.
5. At any time during the term of this Agreement, the City has the right to terminate this Agreement, provided Consultant is given thirty (30) days written notice. City's termination shall be without further liability to City; however, Consultant shall be entitled to all costs reasonably incurred prior to the date of termination. Consultant acknowledges that City may terminate this Agreement should funds not be appropriated by its governing body to continue services under this Agreement.
6. This Agreement may only be amended or modified in writing. It is integrated and contains the complete understanding of the parties.
7. All services sold to the City of Roseville shall conform to the general safety orders of the State of California.
8. Unless notified to the contrary, in writing, the City assumes that the Consultant has accepted the work and agrees to do the work in compliance with this Agreement. Upon full and final payment in accordance with the terms of this Agreement, any work product created for City pursuant to this Agreement is deemed owned by City. The work product is not intended or represented to be suitable for reuse by City or others on extensions of the project or on any other project. Any reuse without written verification or adaptation by Consultant for the specific purpose intended will be at City's sole risk and without liability or legal exposure to Consultant from and against all claims, damages, losses, and expenses, including attorneys' fees arising out of or resulting therefrom.
Rights to Consultant existing intellectual property developed, utilized or modified in the performance of the services, but not developed initially as part of the work product, shall remain the property of Consultant. Consultant shall have the right to retain and use copies of all deliverables furnished or to be furnished by Consultant and the information contained therein. City shall not acquire any rights under this Agreement to any of Consultant's proprietary computer software that may be used in connection with the services.
9. All prevailing wages and fair employment practices must be adhered to. For prevailing wage contracts over $25,000, copies of certified payroll must be submitted with invoices. Prevailing wage rates may be obtained from the State Department of Industrial Relations and/or the following website address:
http://www.dir.ca.gov/dlsr/DPreWageDetermination.htm . In compliance with 3 Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Contract Purchase Agreement 3005881
Labor Code Section 1773.2, as may be amended from time to time, Contractor shall cause a copy of this website to be posted at each jobsite, as applicable.
10. Consultant agrees to the below insurance requirements:
a. Unless otherwise specified, the Consultant shall maintain the policies of insurance outlined in Attachment A, incorporated herein by this reference, in full force and effect during the term of this Agreement. The City of Roseville retains sole discretion in determining the types and proper levels of insurance coverage. b. Form. Consultant shall submit an ACORD certificate evidencing such coverage for the period covered by this Agreement to Risk Management and the City Attorney, prior to undertaking any work hereunder. Any insurance written on a claims made basis is subject to the reasonable approval of Risk Management and the City Attorney. c. Additional Insureds. Consultant shall also provide a separate endorsement attached to the certificate of insurance including City, its officers, and employees as additional insureds for each type of required coverage, except for Workers' Compensation and Professional Liability. In addition, the additional insured coverage shall be as broad as the Insurance Services Office (ISO) CG 20 10 04 13 Endorsement.
d. Cancellation. Consultant shall provide thirty (30) days written notice to City prior to cancellation or non-renewal of any insurance required by this Agreement. e. Subconsultants. Consultant agrees to use commercially reasonable efforts to include in its contracts with its direct subconsultants the same requirements and provisions of this Agreement, including the indemnity and insurance requirements, to the extent they apply to the scope of the subconsultants work. Furthermore, Consultant shall require its subconsultants to agree to be bound to Consultant and City in the same manner and to the same extent as Consultant is bound to City under this Agreement. Additionally, Consultant shall obligate its subconsultants to comply with these same provisions with respect to any tertiary subconsultant, regardless of tier. A copy of City's indemnity and insurance provisions will be furnished to the subconsultant or tertiary subconsultant upon request.
f. Waiver of Subrogation. Where allowed by law the required Workers Compensation, Commercial General Liability and Automobile Liability policies shall be endorsed with a waiver of subrogation in favor of City, its officers, employees, and volunteers for all worked performed by Consultant, its employees, and sub consultants. CITY and CONSULTANT waive all rights of recovery and subrogation against each other and their officers, directors, agents, or employees for damage covered or coverable by property insurance (including deductibles and self insurance) during and after the completion of CONSULTANT's Services.
g. Liability/Remedies. Insurance coverage in the amounts set forth herein shall not be construed to waive Consultant of liability in excess of such coverage, nor shall it preclude City from taking such other actions as are available to it under any other provisions of this Agreement or law.
11. Consultant shall comply with all federal, state, local laws, ordinances, and policies as may be applicable to the performance of services under this Agreement. Failure to comply with local ordinances may result in monetary fines and cancellation of this Agreement.
12. In the event that the terms of any attachment or exhibit conflict with any terms of this Agreement, the terms of the Statement of Work shall control followed by the provisions of this Agreement.
4 Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Contract Purchase Agreement 3005881
13. This Agreement may be executed in one or more counterparts, each of which shall be deemed an original, but all of which together shall constitute one and the same instrument. In the event that any signature is delivered by facsimile transmission or by e-mail delivery of a ". pdf" format data file, such signature shall create a valid and binding obligation of the party executing (or on whose behalf such signature is executed) with the same force and effect as if such facsimile or ".pdf" signature page were an original thereof.
14. If either party commences any legal action against the other party arising out of this Agreement or the performance thereof, the predominantly prevailing party in such action shall be entitled to recover its reasonable litigation expenses, including but not limited to, court costs, expert witness fees, discovery expenses, and attorneys' fees. Any action arising out of this Agreement shall be brought in Placer County, California, regardless of where else venue may lie. This Agreement shall be governed by and construed in accordance with the laws of the State of California.
15. This Agreement shall be binding upon the heirs, successors, executors, administrators and assigns of the respective parties hereto.
16. If any of the provisions contained in this Agreement are for any reason held invalid or unenforceable, such holding shall not affect the remaining provisions or the validity and enforceability of the Agreement as a whole.
17. For purposes of this Agreement, the terms "Contractor," "Consultant," and "Supplier" are used interchangeably.
18. Consultant agrees that any and all information furnished by City shall be deemed proprietary and confidential. All such information, to the extent previously, presently, or subsequently disclosed to Consultant and/or processed and derived by Consultant services is the property of City and such property shall be deemed and treated as "Confidential Information" of City.
Consultant acknowledges that such Confidential Information may contain information provided and/or generated by third-parties. Consultant agrees that such Confidential Information shall not be disclosed to any third party without written permission from City, except as required by law. Consultant shall not use the Confidential Information except to perform Consultant's services as directed by City. Notwithstanding the foregoing, Confidential Information shall not include information that (a) is or becomes publicly available through no fault of Consultant; (b) was in Consultant's lawful possession prior to disclosure by City; (c) is rightfully received by Consultant from a third party without restriction on disclosure; or (d) is independently developed by Consultant without use of or reference to City's Confidential Information.
19. All facilities, devices, networks, and services used to store, deliver, process, backup or purge Confidential Information will employ administrative, physical, technical, and procedural safeguards and industry practices reasonably designed to protect Confidential Information from unauthorized access, destruction, use, modification, or disclosure. Such measures will be no less protective than those used to secure Consultant's own information of a similar type, and in no event less than reasonable in view of the type and nature of the information involved.
20. Consultant will retain Confidential Information until deleted by City or City-authorized third party, or for a time period mutually agreed upon by the parties to this Agreement, subject to Consultant's standard backup and retention practices.
21. Upon termination or expiration of this Agreement, Consultant will confirm that all Confidential Information is securely transferred to City within thirty (30) calendar days, to the extent technically practicable. Consultant will confirm that any transfer of Confidential Information is accomplished by methods that are compatible with the relevant City systems, and that City will have access to all Confidential Information during any such transfer.
Consultant shall securely dispose of all Confidential Information when requested by City and 5 Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Contract Purchase Agreement 3005881
Consultant will provide written notification to City once all Confidential Information has been securely disposed of. Consultant may retain one archival copy for up to six months after the support and warranty term has ended to accommodate legal, audit, insurance, and contract administration requirements.
22. Consultant shall report to City any data compromise or unauthorized access to Confidential Information within twenty-four (24) hours after Consultant discovers such data compromise or unauthorized access. Consultant will take commercially reasonable measures to address any such data compromise or unauthorized access in a timely manner. Except as otherwise required by law, Consultant will not provide notice to end users or other entities of any such data compromise or unauthorized access without written permission from City. Consultant will promptly reimburse City for all commercially reasonable and documented fees and costs incurred by City in any investigation, remediation or litigation resulting from any such data compromise or unauthorized access, to the extent caused by Consultant's failure to comply with its obligations under this Agreement, including identity protection and restoration services for each person reasonably determined to be impacted by such data compromise or unauthorized access, subject to the limitations of liability set forth in this Agreement.
23. Consultant may not advertise that City is a client, list City as a reference or otherwise use City's name, logos, trademarks, or service marks without prior written permission from City.
24. Consultant acknowledges that services rendered under this agreement (including but not limited to service levels and operational levels) shall be performed in accordance with industry standards ("Standard of Care"). City shall promptly notify Consultant in writing of any failure of Consultant to comply with the Standard of Care or any perceived deficiency in its Services. Should Consultant receive such notice less than one year after performance of such deficient Services, Consultant at its sole option, may (a) reperform the Services to bring the same into conformance with the requirements of the this Agreement and the applicable Standard of Care, or (b) liquidate damages to City by paying to City, as refund or otherwise, that portion of the compensation for that portion of the Services which are found to be deficient, or otherwise were not able to be corrected or brought into conformance with this Agreement requirements by reperformance or replacement after commercially reasonable attempts by Consultant to do so. City's improper operation, maintenance, or unauthorized use of the Services shall relieve Consultant of any liability or damages arising out of such improper or unauthorized use. Consultant shall have the right to rely on information provided by City without independent investigation. The mutually negotiated obligations and representations are Consultant's sole obligation and City's sole and exclusive remedy with respect to defects in the quality of Services or failure to meet the Standard of Care.
25. Reserved.
26. Reserved.
27. Contractor/consultant's duties and services under this agreement shall not include preparing or assisting the public entity with any portion of the public entity's preparation of a request for proposals, request for qualifications, or any other solicitation regarding a subsequent or additional contract with the public entity. The public entity entering this agreement shall at all times retain responsibility for public contracting, including with respect to any subsequent phase of this project. Contractor/consultant's participation in the planning, discussions, or drawing of project plans or specifications, if any, shall be limited to conceptual, preliminary, or initial plans or specifications. Contractor/consultant shall cooperate with the public entity to ensure that all bidders for a subsequent contract on any subsequent phase of this project have access to the same information, including all conceptual, preliminary, or initial plans or specifications prepared by contractor pursuant to this agreement.
28. Consultant certifies that Consultant, its employees, directors, officers, agents, subcontractors, vendors, and volunteers are not presently debarred, excluded, suspended, declared ineligible, 6 Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Contract Purchase Agreement 3005881
voluntarily excluded, or proposed for debarment, exclusion, suspension, or ineligibility by any federal, state, or local department or agency.
29. The Levine Act (Govt. Code, Section 84308) requires a Party (and its agent(s), if any) to a Proceeding before the City of Roseville that involves any action or consideration related to their contract, license, permit, or other entitlement for use, to disclose any campaign contributions made to City elected or appointed officers totaling more than $500 within the twelve (12) months prior to the City decision and while a proceeding is pending, and includes certain prohibitions on contribution activity thereafter. If applicable campaign contributions have been made by Contractor and/or its agent(s), Contractor is responsible for compliance, including for its disclosure obligations, if any, as further described at: https://www.roseville. ca.us/government/departments/city_clerk/transparency/levine_act.
30. This Agreement may be amended via change order, with an appropriate change in compensation and schedule, but only if such change order is made in writing, approved by the City, and signed by both parties.
31. CONSULTANT agrees to defend and indemnify CITY if, despite the parties intent and practice, any venue, agency, or court with competent jurisdiction determines that CONSULTANT and/or any of its agents, officers, employees, independent contractors, or subcontractors, are characterized as employee(s) of CITY.
CONSULTANT and CITY agree that: (a) CONSULTANT is free from the control and direction of CITY in connection with the performance of the work; (b) CONSULTANT is providing services directly to CITY; (c) CONSULTANT has and will maintain at all relevant times a business license; (d) CONSULTANT maintains a business location that is separate from CITY; (e) CONSULTANT is customarily engaged in an independently established business of the same nature as that involved in the work performed hereunder; (f) CONSULTANT actually contracts with other businesses to provide the same or similar services and maintains a clientele without restrictions from CITY; (g) CONSULTANT advertises and holds itself out to the public as available to provide the same or similar services; (h) CONSULTANT provides its own tools, vehicles, and equipment to perform the services; (i) CONSULTANT has negotiated its own rates; (j) CONSULTANT set its own hours and location of work in accomplishing CITY's on-call needs; and (k) CONSULTANT has the right to control the manner and means of accomplishing the result desired and exercises its own expert independent judgement.
32. Reserved.
33. Mutual Waiver of Consequential Damages. Neither party is liable for any special, indirect, incidental, punitive, or consequential damages to the other, including but not limited to, by way of example, loss of profits; loss of savings or revenue, including lost production; loss of use of the equipment, sublicensed software, licensed software, services, or data; cost of capital; cover costs, or cost of any substitute performance or replacement of equipment, facilities or services; increased Project costs; governmental fines or penalties; and claims by customers of CITY.
34. Limitation of Liability. To the fullest extent permissible by law, and notwithstanding any other provision of this Agreement, the total liability, in the aggregate, of Consultant, its officers, directors, shareholders, employees, agents, and consultants, and any of them, to City and anyone claiming by, through or under City, for any and all claims, losses, liabilities, costs or damages whatsoever arising out of, resulting from or in any way related to the Project or this Agreement from any form of negligence, professional errors or omissions (including breach of contract or warranty) of Consultant, its officers, directors, employees, agents or consultants, or any of them, SHALL NOT EXCEED the total amount of this Agreement. The parties agree that specific consideration has been given by Consultant for this limitation and that it is deemed adequate. The parties further agree that the insurance limits required to be 7 Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Contract Purchase Agreement 3005881
maintained by Consultant under this Agreement are not impacted or reduced by this limitation of liability.
35. Consultant may engage or obtain assistance from its affiliates and subsidiaries including, without limitation, Burns & McDonnell Canada Ltd., Burns & McDonnell Global, Inc., Burns & McDonnell Engineering Company, Inc., and Burns & McDonnell India Pvt. Ltd. ("Labor Sources") to fulfill performance obligations of Consultant under this Agreement. The Parties agree that contracts, purchase orders, or similar agreements between Consultant and any Labor Sources are not subcontracts and persons from such Labor Sources shall be billed to Client according to the fee or rate sheet / billing rate defined for the applicable contract, purchase order, or similar agreement. Personnel from Labor Sources shall be considered agents of Consultant and able to act on behalf of Consultant within the scope of the authority granted such personnel according to job function and billing classification.
The supplier named hereon by the acceptance of this order agrees to the provisions of this document titled "Contract Purchase Agreement" and all accompanying terms, conditions, and attachments.
Roseville Business License No. ____________________________________ Contractor License No. ____________________________________________ DIR Registration No. _______________________________________________ Check mark the applicable company type below:
___________ Corporation
___________ Limited Liability Company
___________ Partnership
___________ Sole Proprietor
City reserves the right to withhold any payments to Consultant in the event of noncompliance with insurance requirements or if required by law.
Information Technology T&C (Negotiated for Burns & McDonnell Western Enterprises, Inc.) REV 9/3/26 JM
8 X
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749 00857765
Contract Purchase Agreement 3005881
ATTACHMENT A
HUMAN RESOURCES/RISK MANAGEMENT DIVISION
INSURANCE REQUIREMENTS
AGREEMENT OVER FORMAL BID LIMIT OR INVOLVING HIGH RISK ACTIVITIES Negotiated for Burns & McDonnell Western Enterprises, Inc. rev. 9/3/26 VB General - Required Coverage/Documentation
● General Liability: $1 Million per occurrence /$2 Million aggregate per accident where allowed by law ● Workers' Compensation: Statutory *Must provide a Waiver of subrogation ● Additional Insured Endorsement (AIE) - General Liability policy: CG 20 38 04 13 or an equivalent, attached to the certificate of insurance. Endorsement shall cover the City of Roseville, its officers, and employees as additional insured.
● A 30 day notice of cancellation must be provided
● List certificate holder as: The City of Roseville - Insurance Compliance, PO Box 100085-R1, Duluth, GA 30096
Additional Liability/Insurance Requirements if required by Agreement (and marked below):
Construction:____
General Liability:
$2 Million/occurrence
$4 Million aggregate
Design Professional:____
General Liability:
$2 Million/occurrence
$4 Million aggregate
Professional Liability:
$2 Million/occurrence
Professional Consultant:____
Professional Liability:
$1 Million/occurrence
IT Services:_X___
Professional Liability:
$1 Million/claim and in the aggregate
No auto required
Cyber Liability:
$1 Million/occurrence
Hazardous Materials:____
Pollution Liability:
$1 Million/occurrence
Special Events/Caterers-Vendors:____
No auto required
No workers' comp required
Professional Counseling/ Psychological:____
Professional Liability:
$1 Million/occurrence
No auto required
Pyrotechnics:____
9 Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Contract Purchase Agreement 3005881
General Liability:
$5 Million/occurrence
$10 Million aggregate
Auto - $2 Million/occurrence
Chemical/Environmental:____
General Liability:
$3 Million/occurrence
$6 Million aggregate
Pollution – $2 Million/Occurrence
Auto - $2 Million/Occurrence
Insurance Submission Process
The City of Roseville Human Resources/Risk Management Department uses a service called EBIX to manage our insurance certificate tracking.
How It Works
● The vendor's contact information is entered into EBIX. EBIX will contact the vendor to request proof of insurance.
● The Vendor can forward the request to their Insurance Agent(s) if necessary. ● Vendor/Insurance Agent submits insurance to EBIX by email to [email protected] or by fax to (770) 325-5727. After faxing or emailing the certificate, please DO NOT send the certificate by mail to EBIX. Please do not mail, email or fax any certificates to the City of Roseville. ● Once submitted, EBIX reviews the insurance documentation. If there are deficiencies, EBIX will send a follow up letter or email requesting additional information.
Questions Regarding Insurance Submission: Contact EBIX at (951) 652-4239 Questions Regarding Insurance Requirements Contact Risk Management at (916) 774-5202 10 Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Contract Purchase Agreement 3005881
Supplier
Signature:______________________________________________ Print Name:_____________________________________________ Title:__________________________________________________ Date: __________________________________________________ Supplier
Signature:______________________________________________ Print Name:_____________________________________________ Title:__________________________________________________ Date: __________________________________________________ City of Roseville, A Municipal Corporation
Signature:______________________________________________ Print Name: Dominick Casey
Title: City Manager
Date:__________________________________________________ 11 Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749 Chief Financial Officer
Vice President
9/9/2026
Stephen Kane
9/10/2026
Jenna Pukach
CONFIDENTIALITY AND NON-DISCLOSURE AGREEMENT
ARTICLE I – GENERAL
_____ _____ _____ _____ (“Consultant”) agrees that information furnished by the City of Roseville (“City”) shall be deemed proprietary and confidential, and all such foregoing information, to the extent previously, presently, or subsequently disclosed to Consultant or processed and derived by Consultant services is hereinafter referred to as “Confidential Information” of City.
Consultant acknowledges that such Confidential Information may contain information provided and/or generated by third parties.
In recognition of the proprietary and confidential nature of such Confidential Information, Consultant agrees to treat the Confidential Information as provided by this Agreement.
ARTICLE II – TREATMENT OF CONFIDENTIAL INFORMATION
Consultant shall, and shall cause each of Consultant’s affiliates, agents, employees, directors, partners, and representatives to safeguard and maintain as confidential all Confidential Information, including, without limitation, information in written, magnetic, electronic or any other form, and take reasonable precautions to protect the Confidential Information (including, without limitation, all precautions Consultant employs with respect to Consultant’s own proprietary and confidential information). Consultant shall not, and Consultant shall cause each of Consultant’s affiliates, agents, employees, directors, partners, and representatives not to:
(a) use the Confidential Information except to perform Consultant’s services as directed by City; (b) do anything to impair the business relationships, intellectual property or other proprietary rights of City; (c) claim, or reverse engineer any of the Confidential Information; or (d) disclose the Confidential Information to anyone unless required to do so by law or with prior written consent of City. Any Consultant employee, affiliate, advisor, agent, director, partner or representative given access to any of the Confidential Information must have undergone and passed City approved criminal background screenings, and have a legitimate “need to know”; and Consultant will notify such employee, affiliate, advisor, director, partner, or representative that they are bound by the same restrictions as Consultant regarding the Confidential Information. No Confidential Information may be stored or transmitted outside the continental United States without prior written consent of City. For Confidential Information that is protected under Federal, State or Local law, including, without limitation, personally identifiable information, health care information and criminal history information, Consultant will use best practices to protect such information in conformity with applicable law.
ARTICLE III – EXCEPTIONS
The foregoing restrictions of confidentiality and non-use will not apply to information that: (a) is or becomes publicly available without breach of this Agreement; (b) is disclosed to Consultant by a third party, provided such information was not obtained by such third party, directly or indirectly, from City on a confidential basis; (c) is already known to Consultant without obligations of confidentiality; (d) is independently developed or discovered by Consultant without access to the Confidential Information as evidenced by the Consultant’s business records; or (e) is the subject of a written permission to disclose provided by City.
ARTICLE IV – PERMITTED DISCLOSURES
Notwithstanding any provisions of this Agreement to the contrary, Consultant may disclose the Confidential Information to applicable regulatory authorities or if required by judicial or administrative process or timely disclosure requirements imposed by law, provided that Consultant first provides to City prompt written notice of such required disclosure, maintains confidentiality to the greatest extent permissible and takes such steps as may be reasonable in the circumstances to allow City to seek a protective order with respect to the confidentiality of the information required to be disclosed. If City receives a legal order or request seeking Confidential Information being held by Consultant, City will supply a copy to Consultant. Consultant will supply City with copies of the Confidential Information within two business days.
ARTICLE V – NO LICENSE
This Agreement shall not be construed as creating, conveying, transferring, granting or conferring upon Consultant any rights, license or authority in or to the Confidential Information. Furthermore and specifically, no license or conveyance of any intellectual property rights is granted or implied by this Agreement.
ARTICLE VI – RETURN OF CONFIDENTIAL INFORMATION
Immediately upon the decision of either party to terminate this Agreement, Consultant shall, and shall cause each of Consultant’s affiliates, agents, employees, directors, partners, and representatives to, return to City all documents, media and data, in any form, containing Confidential Information and any and all copies or extracts in a usable format deemed acceptable by City thereof, within thirty (30) calendar days of such decision. Furthermore, within thirty (30) calendar days of the decision of either party to terminate the Agreement, Consultant shall remove all Confidential Information from any computer system used by Consultant’s agents or business partners.
ARTICLE VII – REQUIRED DISCLOSURES
Consultant must disclose information regarding participation, directly or indirectly, in any arrangement, agreement, investment, or other activity with any vendor, supplier, or other entity, which has resulted or could result in a benefit to Consultant, if said participation creates potential conflicts or competition with this Agreement or other agreements involving City.
ARTICLE VIII – REMEDIES FOR BREACH
Consultant agrees that the limitations contained herein are reasonable and necessary for the protection of City, and given the unique nature of the Confidential Information, the breach of this Agreement cannot be adequately remedied by law. Therefore, in the event of a breach of this Agreement by Consultant, City shall be entitled to pursue equitable remedies, which shall include, but not be limited to, injunctive relief, and recovery of any associated reasonable attorney’s fees and legal costs, along with any other available remedies at law. Consultant will notify City in writing immediately upon discovery of any such unauthorized release or other breach of Confidential Information, or any belief that unauthorized access to Confidential Information has transpired, ARTICLE IX – VALIDITY
Any provision of this Agreement held to be illegal, invalid, or unenforceable by law or rule or regulation shall be fully severable, and the remaining provisions of this Agreement shall remain in full force and effect. Additionally, the parties hereby agree to negotiate in good faith to modify and amend this Agreement to maintain the original intent of the parties with respect to such provisions so severed.
By:________________________________ Print Name:_________________________ Title:_______________________________
Date:______________________________
and
By:________________________________ Print Name:_________________________ Title:_______________________________
Date:______________________________
Burns & McDonnell Western Enterprises, Inc.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749 Chief Financial Officer
Vice President
9/9/2026
Stephen Kane
Jenna Pukach
9/10/2026
!"#$%$$
&'()*+,-./,*-.+01-.+,22)*3456.+/276,8'/*+*36/9.+/,6*+:;34*:206+ &2:4*+:2,*&<::6.=:>/,6*+:[email protected]+2
ABC DBEFG H
IEJC KLM#$%$$#NGOB EG NCO!EPBQRGS!RRTBFUVBKTW!OBI FB PXYX$$ZUI[ B\C F!E\RCEKW!GER!E BRGERBWG]TRR!CEC\\ BRR!GE!E^_ C!EB`aLBUI!R"GKCWBFCW LWWRHbbQQQ`\GO`KC`\GObQXKGEWBEWbT"GCFRb$%$$b%cbc`M`$$X]TRR!CX^_ C!EBXUVBKTW!OBX I FB `Fd`
aLBUIF! BKWRC""C\BEK!BRCEFFBC WSBEWRWLCWC BRTefBKWWGWLBNGOB EG gRCTWLG !Wh WGWC_BKB WC!E!SSBF!CWBRWBR#!EK"TF!E\EGW!dh!E\C""KGEW CKWG RCEF\ CEWBBRGdWLB! Ge"!\CW!GERWGKGS"hQ!WLBV!RW!E\BKGEGS!KRCEKW!GER!SGRBFehWLB^`i`\GOB ESBEW!E BRGERBWG]TRR!CjRCKW!GER!E^_ C!EB#CRQB""CRCEhRCEKW!GER!SGRBFTEFB RWCWB "CQ`
aL!RKG BRGEFBEKBRB OBRCRCEGW!KBTEFB WLBUIWLCWCRCKGEW CKWG G \ CEWBB# KGS"!CEKBQ!WLWLBBKGEGS!KRCEKW!GER!SGRBF!E BRGERBWG]TRR!CgRCKW!GER!E ^_ C!EB!R BkT! BF#!EK"TF!E\Q!WL BRBKWWG#eTWEGW"!S!WBFWG#WLBdBFB C"BVBKTW!OB G FB R!FBEW!d!BF!EWLBUICEFWLBRCEKW!GER!FBEW!d!BFGEWLB^`i`ABC WSBEWGdWLB a BCRT hQBeR!WBZLWWRHbbLGSB`W BCRT h`\GObG"!KhX!RRTBRbd!ECEK!C"XRCEKW!GERbRCEKW!GERX G\ CSRXCEFXKGTEW hX!EdG SCW!GEbT_ C!EBX TRR!CX B"CWBFXRCEKW!GER[`lC!"T BWGKGS"h SCh BRT"W!EWLBWB S!ECW!GEGdKGEW CKWRG \ CEWR#CRC"!KCe"B`
m"BCRBEGWBWLCWdG CEhC\ BBSBEWRG \ CEWROC"TBFCWnoS!""!GEG SG BhGTSTRW BG WWGWLBp!WhGd]GRBO!""BhGT KGS"!CEKBQ!WLBKGEGS!KRCEKW!GER!EK"TF!E\RWBR hGTLCOBWC_BE!E BRGERBWG]TRR!CjRCKW!GER!E^_ C!EB#!EK"TF!E\#eTWEGW"!S!WBFWG# FBR!RW!E\d GSSC_!E\EBQ!EOBRWSBEWR!E#G BE\C\!E\!Ed!ECEK!C"W CERCKW!GERQ!WL# ]TRR!CEBEW!W!BR#EGWW CERdB !E\WBKLEG"G\hWG]TRR!CG ]TRR!CEBEW!W!BR#CEFF! BKW"h GO!F!E\RTG WWGWLB\GOB ESBEWCEFBG"BGd^_ C!EB`
i!EKB B"h#
Mb$ob$%$$
iLCEEGEq!BRW
p!WhGd]GRBO!""B
mT KLCR!E\CEFqC BLGTRBJCEC\B
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
PROPOSAL FOR
GIS ESRI UTILITY NETWORK
DATA MIGRATION
RFP 07-104
SUBMITTED TO
CITY OF ROSEVILLE
January 14, 2026
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
2 January 14, 2026
Steve Hancock | Senior Electric Business Analyst
City of Roseville – Roseville Electric Utility
2090 Hilltop Circle | Roseville, CA 95747
Re: GIS ESRI Utility Network Data Migration | RFP 07-104 Dear Mr. Hancock,
1898 & Co., a part of Burns & McDonnell Western Enterprises Inc., is pleased to submit this proposal to support the City of Roseville in its migration from the Esri ArcGIS 10.8.1 Geometric Network to the ArcGIS Utility Network, alongside the modernization and upgrade of its Schneider Electric ArcFM solution. This initiative is a transformative opportunity for Roseville Electric Utility to strengthen operational efficiency, improve network modeling accuracy, expand enterprise integrations, and support next-generation workflows across engineering, operations, and field teams.
As a consulting practice built within one of the nation’s leading engineering firms, 1898 & Co. brings a combination of deep utility operations knowledge, modern geospatial experience, and hands-on ArcFM XI and Utility Network implementation experience. Our team has delivered successful UN migrations for electric distribution & transmission, water, gas, and fiber systems across public power, IOUs, and municipal utilities nationwide. We understand the business-critical nature of electric network data and how GIS enables planning, outage response, asset management, customer service, and compliance.
What differentiates 1898 & Co. is our ability to serve as a strategic partner throughout the delivery lifecycle, we are more than just a technical implementer. We work closely with clients to confirm their Utility Network transition aligns with operational requirements, long-term modernization goals, system integrations, and staff readiness. Our approach emphasizes strong communication, transparency, knowledge transfer, and a well-managed transition that protects business continuity.
This proposal outlines a fixed-price scope that covers all required tasks outlined in the RFP and provides the City of Roseville cost certainty. We welcome the opportunity to serve as your trusted partner on this transformational journey and look forward to the next steps in support of your vision for a modern, connected utility GIS. 1898 & Co. understands the requirements of this Request for Proposals and commits to performing the services in accordance with the requirements described in RFP No. 07-104, including the Question and Answer (Q&A) issued by the City of Roseville. If you have any questions about our proposal, please contact Chad Pinarija at [email protected] or 1-949-293-1584.
Sincerely,
Chad Pinarija
Director, Technology Consulting
Stephen Kane
Vice President
2175 N. California Blvd. #400
Walnut Creek, CA 94596
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Attachment A
PROPOSER’S CERTIFICATION
I hereby propose to furnish the goods or services specified in the Request for Proposals (“RFP”). I agree that my proposal will remain firm for a period of up to ninety (90) days in order to allow the City of Roseville (“City”) adequate time to evaluate the qualifications submitted.
I have carefully examined the Request for Proposals and any other documents accompanying or made a part of this RFP. The information contained in this proposal is true and correct to the best of my knowledge and is signed under penalty of perjury under the laws of the State of California. I further certify that I am duly authorized to submit this proposal on behalf of the firm as its authorized agent and that the firm is ready, willing and able to perform if awarded the contract.
I further certify that this proposal is made without prior understanding, agreement, connection, discussion, or conspiracy with any other person, firm or corporation submitting a proposal for the same product or service; that this proposal is fair and made without outside control, collusion, fraud or illegal action; that no officer, employee or agent of the City or any other proposer is financially interested in said proposal; that no undue influence or pressure was used against or in concert with any officer, employee or agent of the City in connection with the award or terms of the contract that will be executed as a result of this RFP; and that the undersigned executed this Proposer’s Certification with full knowledge and understanding of the matters therein contained and was duly authorized to do so.
_________________________________________________
NAME OF BUSINESS
_________________________________________________
SIGNATURE
_________________________________________________
NAME & TITLE, TYPED OR PRINTED
_________________________________________________
MAILING ADDRESS
_ _____________________________________
TELEPHONE NUMBER
_________________________________________________
EMAIL
Type of Organization:
____ Sole Proprietorship ____ Corporation ____ State of Incorporation ________ Partnership ____Limited Liability Company
Burns & McDonnell Western Enterprises, Inc.
Stephen Kane, Vice President
145 S. State College Blvd., Suite 600, Brea, CA 92821
+
__
1 (7
___
14 ___
) 264-7333
___
[email protected]
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2025
PAGE 3
Contents
Tab A: Firm Qualifications .............................................................. 4 Tab B: Experience and References .................................................. 11 Tab C: Qualifications of Team ........................................................ 17 Tab D: Project Understanding ........................................................ 21 Tab E: Project and Implementation Overview .................................... 28 Tab F: Cost Proposal.................................................................... 42 Tab G: Required Statements/Documents........................................... 44 Tab H: Exceptions ....................................................................... 45 Tab I: Competency of Proposers ..................................................... 46 Appendix A: Resumes .................................................................. 47 Appendix B: Example Project Log ................................................... 48 Additional Attachments:
Attachment G - Gantt Chart
Project Workbook Example
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 4
Tab A: Firm Qualifications
Corporate Structure & Services
Burns & McDonnell is a family of privately held companies, each providing services based upon supporting a client’s particular needs. We provide a full suite of architecture, engineering, construction and consulting services across all industries, including Water, Power, Telecommunications, Environmental, Transportation, Construction, Governmental, Military &
Municipal, Aviation, Commercial, Retail & Institutional, Manufacturing & Industrial, and Oil, Gas & Chemical. We can provide additional information regarding corporate structure, including international services, upon contract award.
Industry rankings provided by Engineering News-Record (ENR). Click here for the full list of Burns & McDonnell rankings.
About 1898 & Co.
1898 & Co., a part of Burns & McDonnell, is a global business, technology and security consulting firm that serves critical infrastructure industries. As an extension of your team, we plan, secure and optimize your asset-intensive organization, leveraging our trusted advisers with proven track records to uncover and deliver straightforward, actionable insights that can transform your business.
Our firm has been helping organizations engineer and construct electric infrastructure since 1898. By combining our experience working in the electric industry with our business-aligned approach to technology adoption, we apply enterprise system planning, implementation, and customization capabilities to help utility clients maximize their return on investment in people, processes, and technologies. 100%
employee-owned
Backed by
15K+
professionals at
Burns & McDonnell
24 Years as Esri Business
Partner
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 5
California Presence
1898 & Co., part of Burns & McDonnell, is proud to have a strong and growing presence in California. With 321 employee-owners in our California regional offices we bring local knowledge, responsiveness, and a deep commitment to the communities we serve. Burns & McDonnell has consistently been recognized as one of the Best Places to Work in California, reflecting the strength and stability of our local teams.
We understand the unique operational challenges and opportunities facing electric utilities in this region, and we are actively engaged with clients across California on projects involving grid modernization, advanced GIS solutions, and Utility Network implementations.
As part of a global organization of more than 15,000 professionals in more than 75 offices globally, shown in Figure 1, we have access to a wide range of engineering, technology, and consulting disciplines. This depth of resources enables us to respond quickly and effectively to complex challenges while delivering integrated, forward-thinking solutions for City of Roseville.
Figure 1. 1898 & Co. and Burns & McDonnell have more than 75 offices worldwide, bringing City of Roseville a wide network of seasoned experts with extensive Esri design service experience.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 6
What We Do
With more than 100 technology professionals
across the country, many of them specializing in
the usage, planning, implementation, and
extension of Geographic Information Systems
(GIS), 1898 & Co. has the people and tools
necessary to meet your GIS services, GIS
modernization, GIS application (desktop, mobile,
web) development, geodatabase design and
maintenance needs.
We have been an Esri business partner for 24
years, and over the last five years, we have
actively participated in the Business Partner
Advantage Program. In addition to our gold tier
status in the Esri Partner Network and our engagement in the Business Partner Advantage Program, our staff members actively engage with Esri related to existing technology, as well as participating in activities such as beta testing and holistic testing to help guide and mold the future of the GIS tools. 1898 & Co. staff members are certified at the highest levels in Esri Enterprise System Administration and Enterprise System Design. Esri has recognized our experience with cloud, indoor, and utility GIS by awarding us with ArcGIS Online, System Ready, ArcGIS Indoors, and ArcGIS Utility Network specialty business partner designations.
In addition to our Esri experience, 1898 & Co. is also a certified Schneider Electric EcoExpert partner. This certification affirms our specialized ability to implement, configure, and support the Schneider ArcFM XI platform, including ArcFM Editor XI. Our team is well-versed in aligning the ArcFM XI suite with Utility Network schema, rules, and workflows to deliver scalable, enterprise-ready electric design and editing solutions.
Our dual fluency in Esri and Schneider Electric platforms enables us to offer an unmatched level of integration and support for electric utilities seeking to modernize their GIS infrastructure while maintaining operational continuity and advancing toward grid modernization goals.
1. Utility Network Model Advisory
2. Enterprise GIS System Design,
Administration, and Implementation
3. Geospatial Data Curation and Data
Enrichment
4. Spatial Analytics
5. GIS Roadmaps and Assessments
6. Training and Organizational Change
Management Support
7. Field Data Collection & Reporting
Learn more here!
GEOSPATIAL SERVICES WE PROVIDE
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 7
1898 & Co. brings deep experience in delivering successful Esri Utility Network (UN) deployments, with a strong focus on electric utilities. As of the end of 2025, we have led 14 UN design projects, 12 UN full migrations, and have additional measurable UN experience. Our approach combines strategic system architecture design, robust data readiness planning, and phased implementation to minimize risk and disruption. We also specialize in integration analysis, driving seamless connectivity with edge systems and maintaining or improving service levels throughout the transition. Our proven track record reflects a comprehensive understanding of utility operations and the technical demands of UN modernization.
Our relevant project experience, transition experience, and integration experience is summarized in Figure 2 below.
Figure 2. 1898 & Co. offers a depth of relevant project, transition, and integration experience to guide City of Roseville through UN Design.
Relevant Technology Partnership Programs
To deliver maximum value to City of Roseville, our firm brings a robust network of commercial partnerships and industry certifications that enhance our ability to implement leading technology solutions. These partnerships not only reflect our technical depth but also enable us to deliver more efficient, scalable, and future-ready outcomes.
In addition to our Esri Gold Partnership, we maintain key relationships with other technology providers that will directly support the success of the Utility Network Migration project. These programs grant us early access to product updates, dedicated technical support, and advanced training, all of which we will leverage to help City of Roseville achieve its business and operational goals. Below are several of our most relevant partnerships and certifications that will contribute to the success of this engagement.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 8
Schneider EcoXpert Certified Partner
1898 & Co. has earned Schneider Electric’s Smart Grid EcoXpert certification, recognizing its advanced technical capabilities with the EcoStruxure ArcFM Solution XI Series on Esri’s ArcGIS Utility Network platform. This certification reinforces our experience supporting utility grid modernization by integrating siloed workflows, improving efficiency, and enhancing data sharing.
As a certified EcoXpert in the Geographic Information Systems path, 1898 & Co. demonstrates excellence in implementing next-generation ArcFM solutions. The firm maintains strong partnerships with Schneider Electric and Esri, helping utilities adopt modern network management technologies and extend the value of GIS across their organizations.
IBM Business Partner Program
1898 & Co. is part of the IBM Business Partner Program with cross industry capabilities.
This Partner program provides us the ability to partner with the best technical, business and marketing consultants to deliver successful IBM solutions, including IBM’s Enterprise Asset Management (Maximo) software platform, as well as reduced priced training and educational opportunities, access to demo/evaluation software, and remote technical support from IBM. Our IBM Business Partner status has allowed 1898 & Co. to be a trusted advisor, consultant, and system integrator for Maximo upgrades.
FME by Safe Software Partner Program
The FME by Safe Software Partner Program has enhanced our ability to provide solutions for 3D/4D web maps, CAD-GIS, Geomatics, real-time construction/environmental monitoring using FME, FME Server, and data translation & integration ETL best practices. Additionally, this agreement allows 1898 & Co. to purchase and resell FME licenses. This software platform connects applications and transforms data using repeatable workflows that seamlessly connect to spatial and GIS data.
Microsoft Azure Partner Program
The Microsoft Partner Program provides our team with the latest technology, training and certifications required to design and implement solutions using Microsoft Technology and Azure Cloud. 1898 & Co. provides tools, training, and resources to help deliver high-quality products to clients using best practices, tools, and technology. Our long-standing Microsoft relationship enables us to leverage Azure to deploy flexible lasting solutions and to include Microsoft solutioning discussions.
Prosci Change Management Certified
Prosci’s Change Management Certification Program gives you the tools, know-how and support you need to drive successful change going forward. The Prosci method (supported by world-class research and development) is used by utilities, water companies, and companies across all other major sectors. We have adapted Prosci over the course of numerous projects and incorporated aspects of other well-known change Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 9
management methodologies to supplement and tailor our approach for utility clients.
Our firm has a Certified Change Practitioner Community of Practice, comprised of over 100 Prosci-certified change management team members. Our commitment to change management is exemplified by the investment and focus reflected by 1898 & Co.
Sub-contractor Plan and Project Delivery Responsibility As one of a limited number of firms in North America that have gained GIS certification as part of Schneider’s EcoXpert program, 1898 & Co. will engage Schneider Electric as a subconsultant for this project to support specific aspects of the ArcFM XI solution that are best delivered by the product owner.
Schneider Electric is the developer and steward of the ArcFM product suite and is widely recognized as the industry leader in electric utility GIS design, editing, and workflow solutions built on Esri’s ArcGIS platform.
Schneider Electric’s ArcFM solution has been used by electric utilities for decades to support critical design, editing, and data management workflows. ArcFM XI represents the current generation of this platform, purpose-built to operate with Esri’s Utility Network and ArcGIS Pro, and to support modern utility GIS requirements such as rules-based editing, session management, and scalable enterprise deployments.
Schneider Electric’s continued investment in ArcFM confirms alignment with Esri’s Utility Network roadmap and evolving utility operational needs.
As part of this engagement, Schneider Electric will provide targeted, product-specific support related to ArcFM XI, leveraging their direct knowledge of the software architecture, configuration options, and supported workflows. Their participation strengthens our overall delivery by providing authoritative guidance on ArcFM capabilities and supported configurations, while allowing 1898 & Co. to focus on overall project delivery, data migration, Utility Network design, integration coordination, testing, training, and project management.
The division of responsibilities for this project are as follows:
1898 & Co. Responsibilities:
1898 & Co. will serve as the prime consultant and will retain full responsibility for overall project management, delivery coordination, scope management, schedule, quality control, and communication with the City of Roseville. 1898 & Co. will lead the Utility Network data readiness assessment, data model design, migration execution, testing coordination, documentation, training, integration touchpoint coordination, cutover support, and hypercare.
Schneider Electric Responsibilities:
Schneider Electric will provide ArcFM XI product experience, including participation in ArcFM-related workshops, guidance on supported ArcFM XI configurations and workflows, and product-level knowledge transfer to support successful implementation within the City of Roseville’s ArcGIS Utility Network environment. Schneider Electric’s role is focused on ArcFM XI enablement and does not include ownership of overall project delivery or integration implementation.
The use of Schneider Electric as a subconsultant enhances solution quality and reduces implementation risk by confirming that ArcFM XI is applied in a manner consistent with vendor-supported practices, while maintaining a single point of accountability through 1898 & Co.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 10
Firm’s Organizational Chart
Below is the Burns & McDonnell Western Enterprises Inc. organizational structure, including constituent parts.
Staffing Levels
The table below provides the staffing levels for the past five (5) years for the Burns & McDonnell family of companies.
Year Number of Staff
2025 15,629
2024 14,576
2023 13,867
2022 12,703
2021 10,805
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 11
Tab B: Experience and References
1898 & Co. has a deep understanding of the benefits of the Utility Network for electric utilities through our long-time partnership with Esri. As part of Burns & McDonnell, we work closely with all industry-focused departments, including Power and T&D, where Engineering New-Record recognizes us as #1 in Power and #1 in Transmission and Distribution.
By combining our electric utility background with our broad enterprise technology experience working for some of the industry's most important vendors (including former employees of Esri), we bring an unmatched set of end-to-end electric and Esri technology capabilities to this project. In this section, we feature nine total relevant projects. We provide reference information for three projects of similar size and scope to the City of Roseville GIS Data Migration project and an additional three projects to showcase our team’s extensive experience designing and implementing GIS data migration projects. Key data points showing project size and scope for our top 10 projects are summarized in Table 1.
No. Project Esri UN
Migration Similar Scope/Size Timeline CustomerCount
1 FirstEnergy Yes Full UN Migration &
TAMI Redesign
Jan 2025 -
Current 6 million
3 Denton Municipal Electric Yes
Full UN Migration,
EAM, OMS/ADMS
Planning
Multi-year
(five-year
roadmap
started)
64,000
4 Confidential Large
Manufacturing Client Yes Full UN Migration
(7 Utilities Migrated)
Completed
2023 100,000
5 Gainesville Regional Utilities Yes Full UN Migration Aug 2019 – Sept 2020 93,000
6 Greenville Utilities Commission Initialization UN Implementation Initialization
Aug 2025 -
Ongoing 175,000
6 American Transmission Company Assessment UN Assessment Nov 2023 – Dec 2023 5 million
7 Evergy Yes
Full UN Migration and
Implementation
Initialization
Apr 2025 -
Ongoing 1.7 million
8 Hoosier Energy Assessment UN Assessment Oct 2022 –
Feb 2023 760,000
2 Fairfax Water Yes Full UN Migration Aug 2023 -
Dec 2024 2 million
9 KC Water Yes Pilot and Full UN
Migration
Apr 2021 –
June 2022;
Feb 2025 -
Ongoing
172,000
10 Confidential Northern California
National Laboratory Integration GIS and DataSplice Integration Aug 2024 –
Jan 2025 Confidential
Table 1. 1898 & Co. has designed and implemented GIS data migration projects for a number of clients, and brings that experience to City of Roseville’s GIS Data Migration project.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 12
Reference Project 1. Utility Network Implementation and Transmission Asset Mapping Interface (TAMI) Modernization FirstEnergy
Project Overview
1898 & Co. is currently leading a nearly two-year initiative for FirstEnergy, a Fortune 500 electric utility, to modernize its Electric Transmission GIS environment through the implementation of the Esri ArcGIS Utility Network and a full redesign of its Transmission Asset Mapping Interface (TAMI). This effort directly supports FirstEnergy’s Strategic Asset Management Program (SAMP) and plays a critical role in improving data quality, operational efficiency, and asset lifecycle management practices.
Scope of Work
The scope includes a full ArcGIS Utility Network implementation within a threetier ArcGIS Enterprise environment (development, testing, production) to support scalability, redundancy, and controlled deployment. The TAMI application, used by thousands at FirstEnergy, is being redesigned for improved usability, advanced visualization, and integration with systems like Cascade. The project also covers extensive data cleanup to meet Utility Network standards, full system deployment, customized training, and detailed documentation to support long-term sustainability and self-sufficiency.
Project Challenges
A key challenge of this project has been migrating large volumes of mission-critical transmission network data while maintaining continuous availability for operational users. TAMI’s widespread use by thousands of employees added complexity to the redesign, requiring a user-first approach to avoid disruptions.
Additionally, aligning the migration effort with SAMP requires tight coordination with enterprise systems and asset management processes, including integration with legacy applications and evolving data governance models.
Solutions Implemented
To address these challenges, 1898 & Co. deployed a three-tier ArcGIS Enterprise environment to support development, testing, and a safe production rollout. We used ArcGIS Data Reviewer and custom validation workflows to identify and fix data issues before migration. The TAMI interface was rebuilt using modern ArcGIS APIs to enhance usability and integration. We delivered targeted training to GIS editors, admins, and support staff to build internal capability. After deployment, we led an eight-week stabilization period to resolve issues and transition the system to FirstEnergy’s internal team.
Outcomes and Impact
The implementation will result in a fully operational ArcGIS Utility Network designed to support FirstEnergy’s transmission GIS needs, enabling improved modeling, tracing, and asset connectivity. The reimagined TAMI interface is significantly enhancing system usability and staff efficiency, benefiting thousands of users across departments. The utility is now benefiting from more consistent, accurate GIS data and stronger alignment with asset management strategies under SAMP. With comprehensive documentation and targeted knowledge transfer, FirstEnergy’s GIS team is becoming well-positioned to manage and expand the new platform independently.
REFERENCE CONTACT
Justin Bragwell
Manager of Transmission and
Distribution Products
330-472-3384
[email protected]
SERVICES PROVIDED
• UN Migration &
Implementation
• User Training
• Database Design
• Asset Management
Similar in scope
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 13
Reference Project 2. Grid Modernization, Utility Network Model Implementation, and Business Case
Denton Municipal Electric
Project Overview
1898 & Co. is partnering with Denton Municipal Electric (DME) on a large grid modernization initiative aimed at positioning DME as Texas’ leading customercentric utility. This multi-year transformation emphasizes sustainability, reliability, and operational competitiveness, and involves extensive process and technology advancements across the organization. At the heart of this initiative is a strategic move to modernize DME’s GIS through the migration to the Esri ArcGIS Utility Network.
Scope of Work
The work began with the development of a 20-year business case and a fiveyear implementation roadmap, organized into three major phases across several workstreams. These include Utility Network migration and data model validation, EAM and mobile system rollout, network model development, and planning for OMS, ADMS, DERMS, and field automation technologies such as DER, CVR/VVO, and FLISR. 1898 & Co. is supporting the client in an Owner's Engineer role, guiding the migration of DME’s distribution, transmission, and substation GIS data into the ArcGIS Utility Network and Schneider Electric’s ArcFM XI software suite. The project includes data quality assessments, schema mapping, system architecture design, ArcFM XI configuration, and user training. Our team also provides governance, change management, and coordination across workstreams.
Project Challenges
The project involves a broad range of technical and organizational shifts. Key challenges include unifying GIS across multiple voltage levels and legacy systems, preparing data for Utility Network compliance, and coordinating a large, phased rollout across multiple departments. DME is also preparing for system-level changes that include future OMS and ADMS deployment—requiring significant planning and cross-team alignment throughout the process.
Solutions Implemented
1898 & Co. established a phased implementation model that breaks down the program into manageable workstreams, each linked to a specific objective and technical scope. The Utility Network migration is supported by rigorous data validation, a newly designed enterprise architecture, and detailed schema mapping aligned with Esri’s model. ArcFM XI is being deployed with custom configurations tailored to DME’s workflows. Training and change management are delivered as part of each phase to help DME staff adopt and operate the new systems effectively.
Outcomes and Impact
The GIS migration marks the first major milestone in DME’s broader IT/OT modernization strategy, enabling future integration with ADMS, OMS, and IBM Maximo to support connected grid operations and streamlined asset management. It also improves data quality and creates a flexible GIS framework for future planning, operations, and customer service initiatives. Alongside the Utility Network implementation, 1898 & Co. is supporting DME in selecting and deploying new ADMS and OMS systems, enabling alignment across this multi-year modernization effort.
REFERENCE CONTACT
Jerry Looper
Systems Operations Manager
940-349-7676
[email protected]
SERVICES PROVIDED
• Business Case
• UN Migration &
Implementation
• Change Management
• User Training
• System Architecture
• Database Design
• ADMS/OMS Selection &
Implementation
• Asset Management
Similar in size and scope
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 14
Reference Project 3. Utility Network Initialization and Implementation (in progress)
Evergy
Project Overview
Evergy selected 1898 & Co. to execute its Utility Network Initialization Phase for its distribution, transmission, substation and fiber network and assets.
Evergy is interested in migrating its current Esri ArcGIS 10.6.1 GIS along with Schneider Electric ArcFM 10.6.1 system into the Utility Network. The network model and data from the GIS platform provide input into numerous operational support systems and serves many important business processes. The current state of Evergy’s GIS is a product of consolidation of subsidiaries, application updates, customizations and configurations, field updates and integrations built over a number of years.
Scope of Work
1898 & Co. will guide Evergy through a familiarization stage where both core GIS and IT stakeholders and the wider user base will receive education on the change and opportunities the Utility Network can bring to their organization.
High-level presentations, technical workshops, and business-focused workshops will be conducted. Following these efforts and a collaborative project plan development, the project will move into a discovery phase. This phase will endeavor to bring 1898 & Co. up to speed on Evergy’s current state through data requests and collaborative evaluation of existing systems and business processes. We will also gather initial future state expectations from the project team and Evergy stakeholders. Discovery will transition into requirements gathering where focus will be given to both the numerous Evergy stakeholder groups, as well as the approximately 10 integration teams currently in use. An Enterprise Requirements Traceability Matrix and Key Business Decisions will be documented and used to guide an Integration Assessment, Finalized Requirements Report, Hardware & Software Recommendations, and an Initial UN implementation project plan. Extensive data readiness, data remediation, and data modeling will occur throughout the project life cycle, setting up Evergy to roll into the pilot and implementation phase following this engagement.
Project Challenges
Evergy is a very large utility that has operated though decades of consolidation, operations, and customizations of their GIS system. There will be intense focus on incorporating input and desires from a number of internal and external integration stakeholders. Education and change management services will be a common theme throughout the engagement to put Evergy in the best possible place for the implementation phase of the Utility Network migration.
Solutions Implemented
Future state activities to be executed will provide Evergy with a comprehensive Readiness Report, Future State Architecture Design, RICEFW list of artifacts, Organizational Readiness Report, and a UN Project Implementation Plan to execute the pilot and migration & implementation phase.
Outcomes and Impact
1898 & Co. completed the Initialization project successfully, helping Evergy leadership to secure funding for Phase 2, UN Implementation. Furthermore, 1898 & Co. was chosen to lead Evergy’s Phase 2 UN Implementation project which will run from 2026-2028.
REFERENCE CONTACT
Scott Schlageck
Manager – GIS Services
(785) 532-8505
[email protected]
SERVICES PROVIDED
• GIS Current State
• Stakeholder Engagement
• Future State Model &
Strategy
• UN Roadmap
• Integrations Assessments
and Requirements
• Data Remediation
• Budget Planning
• Change Management
Similar in scope
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 15
Experience Integrating Esri Utility Network with Similar Systems to those Used by City of Roseville
1898 & Co. has extensive experience integrating the Esri Utility Network with a wide range of systems similar to those used by City of Roseville, including OMS, SCADA/ADMS, AMI, engineering analysis tools, asset management platforms, and CIS solutions. In this section, we describe specific projects where we have supported similar integrations, demonstrating our ability to connect the Utility Network with critical enterprise systems to drive real-time visibility, data consistency, and operational efficiency.
OMS
1898 & Co. has direct experience integrating with Outage Management Systems used by many electric utilities. For Denton Municipal Electric (DME), the project team supported both the Utility Network migration and the selection and implementation of new ADMS and OMS systems. This included aligning OMS outage tracing and restoration workflows with the Utility Network’s subnetwork and connectivity model, allowing DME to benefit from improved outage visualization and customer impact tracking. The integration plan accounted for changes in network model structure, data availability, and tracing logic to support outage cause identification and restoration dispatching. Matt Seidl, in a former role at Black Hills Energy, has direct experience building an OMS interface between GE Smallworld, Oracle Spatial, and OSI eMap as well as experience working with GE PowerOn’s circuit manager. Matt also worked with GE and the Black Hills IT team to make the business case for purchasing GE’s GIS Data Adapter that leverages CIM, for a productized ADMS interface.
Engineering Analysis Tools
For electric cooperatives and municipalities, 1898 & Co. has supported the integration of Utility Network data with Synergi and similar engineering analysis tools. These integrations involve structuring the Utility Network to accurately reflect conductor phasing, impedance, protective devices, and other electrical characteristics required for system modeling. The team’s work with Evergy and a confidential client included schema design, data translation pipelines, and custom ETL workflows to export Utility Network datasets into analysis environments. Integration allows for accurate topological representation for load flow analysis, fault isolation studies, and contingency planning.
Asset Management Platforms
1898 & Co. has extensive experience integrating Utility Network data with IBM Maximo. At Evergy, the team configured the Utility Network model to facilitate the interaction between the UN and Maximo to support inspection scheduling, work order generation, and asset management. Similarly, at Fairfax Water, integration workflows were developed using Python ETL scripts to synchronize asset IDs and lifecycle states between the Utility Network geodatabase and asset systems, while maintaining inspection history and work order traceability. These integrations are essential to support mobile work execution, field updates, and long-term capital planning.
“My GIS leadership experience
integrating GIS with OMS, AMI,
Engineering Analysis, CIS, and mobile
maps will help the City of Roseville
successfully navigate their transition
to the Utility Network without missing
any critical steps on their journey.”
- Matt Seidl, System Integration
Consultant, 1898 &Co.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 16
CIS Solutions
Integrating Utility Network data with Customer Information Systems enables utilities to visualize customer impacts from outages, improve service connection tracking, and support billing zone validation. At California Water Services, 1898 & Co. configured FME-based integration between Oracle CC&B and ArcGIS Utility Network, allowing real-time updates to customer account locations, service tap records, and outage notification boundaries. These integrations also supported API-based access to spatial data for customer service representatives, enhancing customer response during service interruptions.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 17
Tab C: Qualifications of Team
Our key personnel have decades of experience helping utilities set up and manage geospatial data and systems. They have executed large and complex GIS projects and delivered them on time and on budget while adhering to the standards and procedures outlined by clients across a variety of critical infrastructure sectors. Full resumes for the key personnel can be found in Appendix A.
Staffing Approach
1898 & Co. brings City of Roseville a highly qualified team with deep utility GIS project delivery experience, supported by a structured and scalable staffing approach. With 167 years of combined relevant experience, our proposed team blends technical depth, practical implementation history, and strong working knowledge of both legacy systems and modern Esri Utility Network architecture. More than a vendor, we act as a committed partner, working side by side with your team to drive outcomes, build internal capability, and support long-term success.
Our approach begins by assigning a core team with direct experience in Schneider’s ArcFM XI Suite and Utility Network migration projects, enabling a fast start and reducing onboarding time. This team is further supported by specialized resources, including certified GIS professionals, Schneider EcoExpert Certifications and Esri Utility Network Specialty certifications, providing targeted knowledge when and where it’s needed throughout the project lifecycle. 1898 & Co. employs 12% of all ArcGIS Utility Network Specialty-certified professionals in the U.S. as reported by Esri, and we have included two of these individuals directly on City of Roseville’s project team.
We use a structured staffing model with clear roles, dedicated leadership, and scalable support aligned to project needs. Our team works alongside City of Roseville to transfer knowledge, build internal capability, and align on expectations—supported by clear communication and escalation paths to keep the project moving forward. Our company also provides a local Colorado presence, enabling in-person collaboration and efficient coordination with City of Roseville’s internal teams. Our delivery model is designed to be agile, responsive, and aligned to your organizational goals, balancing quality, speed, and long-term sustainability.
Organizational Chart
Our proposed team will be led by Drew Haney, who will provide a collaborative and innovative project execution methodology for City of Roseville. Drew will manage the 1898 & Co. team to meet the City of Roseville’s project needs. Our team consists of technology and GIS professionals with varied qualifications, including Utility Network Certifications, Schneider EcoXpert certifications, and long-term experience with ArcFM. Our proposed organizational chart is shown on the following page.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 18
Drew Haney, GISP
Project Manager | San Diego, CA | 28 years of experience | 17 years with firm Drew is a Senior Geographic Information Systems specialist with 25 years' experience in geographic information systems and data analysis. Drew has served in many geospatial positions, from his involvement in the geographic programs of Census 2000, to his consultation of Fortune 500 companies and his performance analysis for a large automobile sales force. Since joining 1898 & Co. he has spent the vast majority of his time consulting and managing electric utility GIS projects. His recent responsibilities include managing the geospatial transmission scheduling display for a large California electric utility, GIS fiber feasibility analysis for a California Water District, technical project management, database and customer support using Geographic Information System (GIS) software, automation and data integration.
Ben Stafford, GISP
QA/QC | Kansas City, MO | 18 years of experience | 18 years with firm Ben has 18 years of experience as Project Manager and Senior Geospatial Consultant specializing in projects related to Utility Network, geospatial database design & integrations, Cityworks/AMS configurations & implementations, design & construction program management, siting studies, and roadmapping. Ben is responsible for defining Spatial Platform Modernization offerings, growing and managing the technical teams responsible for successful delivery, and developing technical requirements for the service offerings. He is responsible for project management tasks including scoping, budgeting, scheduling, client communications, invoicing, and project delivery. Ben has recent experience managing complex geospatial model development and implementation for utilities. He has extensively performed data collection, conversion, management and deployment of web and mobile GIS systems. He has performed tasks related to digitizing, spatial analysis, and 3D analysis.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 19
Matt Seidl, P.E.
Process and Requirements Lead | Rapid City, SD | 25 years of experience | 1 year with firm
Matt is a utility industry and engineering professional with over 20 years of experience leading change and modernizing utility technologies and processes. Matt served for 17 years at a combined electric and gas utility operator, managing the GIS department, leading a team of 49 employees supporting GIS, field service, and work management processes and technologies. Matt’s GIS team was recognized by AGA as a best practice in 2023. Matt has enjoyed leading teams for the past 17 years and has developed a great track record of providing vision and leadership as an implementer of enterprise processes and technology solutions. His broad career experience includes leading both business and IT applications teams, building the Utility of the Future vision and strategy, managing the geographic information systems department, managing enterprise projects, selecting solutions, creating business cases, and marketing projects internally. Matt is excited to leverage the latest technologies and data to help employees have the right information at the right time to make great decisions.
Cristin Holmgren, UN Specialty & EcoXpert Certification Utility Network Lead | Kansas City, MO | 24 years of experience | 5 years with firm
Cristin Holmgren is a GIS professional well versed in spatial analysis, linear referencing, modeling, database design & database configuration. Ms. Holmgren started her GIS career in the Oil and Gas industry where she was responsible for designing geospatial databases and implementing GIS solutions for several of the largest pipeline industry companies. She has expanded her geospatial experience to include the energy, telecom, wastewater and water industries. Ms. Holmgren’s can analyze, organize, and process internal and external client data and has worked in renewable energy, electric transmission, water, wastewater/stormwater, electric reconductoring, site/route selection, database design, fiber design & management, and 3D analysis projects. She has knowledge of Esri’s Enterprise environment and the administration of the ArcGIS Online environment as well as experience in the implementation of Esri’s Utility Network Solution. She is also Esri Utility Network and Schneider EcoXpert Certified.
Darris Friend, GISP, UN Specialty
Solutions Architect | Kansas City, MO | 26 years of experience | 2 years with firm Darris is a senior GIS specialist with 25 years of experience using, supporting and administering Esri’s ArcGIS Enterprise platform for the fifth largest municipal utility in Florida. Darris has managed an annual software budget of $450K and has been the project leader for multi-year GIS initiatives valued at $1.2 million. He’s been recognized by Esri as an Electric GIS Hero in 2021 and is a member of Panasonic Utility & Energy Advisory Council. He has presented on Utility GIS related topics at TC Technology PAG, Esri GeoConX, SSP Innovations Illuminate, FMEA 2022 Hurricane Preparedness, Cityworks Innovate 2022, Esri User Conference 2023, Spatial Business Systems' PUG 2023 and the Central Florida GIS Workshop 2023. Darris harbors the ability to communicate and present complex information to technical and nonDocusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 20
technical audiences with experience presenting to City Commissioners, Utility Advisory Board, Executives, Managers, technical staff, End Users and at GIS conferences.
Eva Shafman
Data Lead | San Diego, CA | 3 years of experience | 3 years with firm Eva is a Lead Geospatial Information System (GIS) Analyst with 1898 & Co. located in San Diego, California. She has provided GIS Data Solutions to San Diego Gas & Electric, Hawaiian Electric, Arizona Public Services, Public Services of New Mexico, Evergy, Duke Energy, Southern California Gas, and Denver International Airport utilizing her ArcGIS Pro and ArcGIS Online experience. She has utilized Feature Manipulation Engine (FME) to automate data processes and conduct spatial analysis. Eva has also worked with clients to set up field applications in ArcGIS Collector and Field Maps.
Chad Pinarija
Regional Engagement Lead | Orange County, CA | 13 years of experience | 5 years with firm
Chad is the Technology Consulting Director at 1898 & Co. for the California region and will serve as the client engagement lead for this project. His responsibilities include maintaining client relations, account management, and advising on client engagements. As the Client Engagement Director, Chad will work with the Project Manager and City of Roseville leadership throughout the duration of the contract to drive client success in all aspects of the engagement. He received his degree in Managerial Economics from the University of California, Davis and brings a wealth of knowledge serving California utility clients.
Brian Hiller, MBA, PCCM, UN Specialty
Senior Managing Director | Kansas City, MO | 20 years of experience | 12 years with firm
Brian is the national Managing Director of Geospatial Technologies in 1898 & Co. He holds multiple technical certifications with Esri’s ArcGIS Platform including the ArcGIS Utility Network certification and Enterprise System Design and Enterprise System Administration. Brian has experience managing and working on a range of IT/GIS projects. Brian is heavily involved in the implementation of GIS technology across water / wastewater and electric utilities. Brian is a Prosci Certified Change Management Practitioner and works with organizations to help them realize a greater Return On their Investment in technology solutions. Prior to joining 1898 & Co., Brian worked for Esri; the global leader in enterprise GIS software helping organizations leverage the ArcGIS platform.
Schneider Electric
Schneider Electric is the developer of the ArcFM GIS product suite and will serve as the ArcFM XI product support subconsultant for this project. Schneider Electric will provide product-level guidance on supported ArcFM XI configurations, workflows, and implementation considerations aligned with the Esri Utility Network. All ArcFM-related activities will be coordinated through 1898 & Co.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 21
Tab D: Project Understanding
City of Roseville’s transition from an Esri geometric network to the Esri Utility Network (UN) and the Schneider ArcFM XI series represents a critical step toward modernizing its electric distribution GIS and enabling enterprise-wide integration, analysis, and scalability. 1898 & Co., a part of Burns & McDonnell, is uniquely positioned to guide City of Roseville through this transformation with the strategic insight, technical depth, and utility experience required for long-term success.
As a consulting and solutions firm built by utility engineers and GIS professionals, 1898 & Co. brings a rare blend of deep domain experience and technology leadership. We have successfully delivered Esri Utility Network projects for municipalities, electric cooperatives, and investor-owned utilities across the country, translating complex technical shifts into operational advantages.
We also have hands-on experience with many of the systems in use at City of Roseville, including ArcFM Editor XI, Synergi OS, Maximo (DataSplice), and CIS, positioning us to support seamless integration and interoperability across your enterprise environment.
Why 1898 & Co. is the Right Partner for City of Roseville Utility Native, Not Just Integration Experts: We deliver end-to-end integrations across IOUs, public power, and municipal utilities, bridging technical and operational workflows with a clear focus on minimizing business and customer impact.
Depth Across Systems, Not Silos: Few firms match our cross-system depth spanning Esri, Schneider Electric and IBM Maximo which allows us to identify edge cases and connect data logic across IT and OT.
Field-to-Enterprise Understanding: We understand how integrations impact daily performance across outage response, planning, and asset health.
Collaborative Execution Model: City of Roseville seeks a partner, not just a vendor. Our approach emphasizes effective communication strategies, joint planning, knowledge sharing, and full team alignment. We demonstrate this partnership mindset through shared planning, documented decision points, transparent risk management, and clear delineation of responsibilities, allowing City staff to maintain control and confidence throughout the project. 1898 & Co.
is a partner, not
just a vendor.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 22
Our Understanding of Your Objectives
1898 & Co. recognizes that City of Roseville is undertaking a significant and strategic transformation of its electric distribution GIS by migrating from the existing Geometric Network model to the Esri Utility Network and ArcFM Editor XI. We recognize the limitations of the legacy system, including performance constraints, integration challenges, and the approaching end of ArcGIS Desktop support, and we will lead this transition to a more scalable, modern, and interoperable GIS platform.
We understand that this transition must occur while City of Roseville continues to support daily outage response, engineering design, asset maintenance, and customer service activities that depend on GIS accuracy and availability. The City of Roseville’s electric GIS is deeply embedded in downstream systems and established workflows, which means this migration must be carefully sequenced, well governed, and validated to avoid operational disruption.
Based on our understanding of the City of Roseville GIS environment and our experience with similar municipal electric utilities, success for this project requires balancing technical rigor with operational continuity and staff adoption.
Our general approach follows a disciplined, phased delivery model that emphasizes early risk identification, City validated decision points, iterative testing, and controlled progression to production. This approach is designed to reduce uncertainty, protect operational continuity, and provide City of Roseville with clear visibility into progress, risks, and upcoming decisions throughout the migration.
Our approach is designed to:
• Migrate City of Roseville’s electric GIS data into the Utility Network model • Preserve data integrity and accuracy through rigorous QA/QC and validation workflows • Implement key Utility Network capabilities including subnetworks, tracing, and associations tailored to your operational requirements
• Implement ArcFM Editor XI, GDBM XI
• Equip City of Roseville staff with the tools, training, and documentation needed to confidently manage and evolve the Utility Network in-house
• Deliver a fully documented, production-ready Utility Network that meets both current needs and future scalability goals
These objectives are designed to support not only a successful migration, but a system that Roseville staff can confidently operate, maintain, and evolve after project closeout.
By combining deep utility GIS delivery experience with a structured, client-focused methodology, 1898 & Co. is committed to helping City of Roseville modernize its electric distribution GIS and maximize long-term value from the Esri Utility Network and ArcFM XI.
As illustrated in Figure 3 below, we understand that the GIS geodatabase functions as an authoritative hub for multiple operational and planning systems, which reinforces the need for accuracy, stability, and disciplined change management throughout the utility network data migration.
Did you know?
Utility Network migrations
are a core offering of the
1898 & Co. team, and we
regularly customize them for
municipal electric utilities
like City of Roseville. This is
what we do, and we do it
with focus, precision, and
results.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 23
This understanding directly reflects the scope, sequencing, and evaluation priorities outlined in the City of Roseville RFP for Utility Network Data Migration.
Potential Challenges and Special Considerations
Based on our experience with similar municipal Utility Network projects, we have identified several key challenges that require deliberate planning and focused execution to achieve the City of Roseville’s stated goals.
1. Data Quality and Readiness
Data readiness is one of the most significant risk factors in any Utility Network migration. Legacy geometric networks often contain accumulated issues related to geometry integrity, orphaned features, inconsistent attribution, and domain drift that do not prevent day to day operations today but can surface as blocking errors during Utility Network validation.
For City of Roseville, the scale of the electric system, the number of asset classes, and the presence of long-standing editing workflows increase the importance of identifying and prioritizing data issues early. A structured readiness assessment, paired with severity-based remediation guidance and City review checkpoints, is critical to maintaining schedule control and avoiding downstream rework.
Special consideration is required to distinguish between issues that must be resolved prior to migration and those that can be addressed post migration without impacting network functionality.
2. Licensing and Platform Alignment
The transition to ArcGIS Enterprise 11.1, ArcGIS Pro, Utility Network, and ArcFM XI introduces dependencies across Esri and Schneider Electric platforms. Aligning versions, permissions, and deployment sequencing is a common challenge, particularly when multiple environments are involved.
Figure 3. A modernized electric distribution GIS gives City of Roseville long-term value.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 24
We recognize that the City will provide required licensing and infrastructure. However, careful coordination is required to confirm compatibility, avoid configuration drift between environments, and support stable testing and production cutover. Early validation of platform readiness and clear delineation of responsibilities between the City, Esri, Schneider Electric, and third-party vendors is essential.
3. Third-Party Systems and Integration Touchpoints
City of Roseville’s GIS supports multiple enterprise systems, including outage management, engineering analysis, asset management, and customer systems. While third-party vendors will manage changes on their respective platforms, the Utility Network migration will alter schemas, connectivity models, and service endpoints that these systems rely upon.
A common challenge in Utility Network projects is underestimating the coordination effort required to align assumptions, testing timelines, and data dependencies across vendors. Special consideration is required to manage these touchpoints without expanding scope or introducing ownership ambiguity.
Successful projects treat integrations as coordinated validation efforts rather than parallel implementations, with defined roles, shared test scenarios, and clear escalation paths.
4. User Adoption and Change Management
This project is not simply a technology upgrade driven by platform obsolescence. It is an opportunity for City of Roseville to modernize how GIS supports engineering, operations, and data governance.
Utility Network introduces new concepts such as associations, subnetworks, dirty areas, and ArcGIS Pro based editing that change how users interact with GIS. Without deliberate attention to adoption, these changes can create friction even when the underlying system is technically sound.
Special consideration must be given to:
• Role based training tailored to editors, administrators, and power users • Clear documentation of revised workflows and editing practices • Adequate stabilization time following cutover to build user confidence • Change management plan
5. Testing Capacity and Resource Constraints
The City has identified limited internal testing resources, which is common for municipal utilities. This constraint requires a testing strategy that is efficient, well scoped, and supported by clear test cases and defect tracking processes.
A key challenge is balancing thorough validation with realistic demands on City staff. Consultant-led testing preparation, combined with City executed validation at defined milestones, supports quality outcomes without overburdening internal resources.
6. Schedule Discipline and Decision Management
Utility Network projects often encounter delays not due to technical complexity, but due to unresolved decisions related to data modeling, asset classification, or workflow expectations. Without structured decision management, these issues can accumulate and impact schedule and cost.
Special consideration must be given to documenting decisions, confirming City approvals at key milestones, and maintaining alignment across stakeholders throughout the project lifecycle.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 25
Project Management Approach
1898 & Co. understands that the City of Roseville’s Project Manager and GIS Manager require a project manager with a proven track record of successfully delivering GIS projects and providing clear, transparent communication throughout the engagement, which is a critical driver of project success.
As part of our commitment to delivering a successful GIS data migration project for City of Roseville, 1898 & Co. fully complies with all project management requirements outlined in the RFQ. We have assigned a dedicated Project Manager, Drew Haney, who is located in California and will serve as the primary point of contact throughout the engagement, maintaining clear and consistent communication with City of Roseville’s project manager and stakeholders. Our team will conduct weekly status meetings and provide ongoing progress reports to maintain transparency and alignment. We will proactively manage risks through the development and maintenance of a comprehensive Risk and Mitigation Plan, identifying potential issues early and outlining strategies to address them.
Additionally, we will implement a formal change management process that includes procedures for submitting, evaluating, approving, and documenting changes to the scope of work, so all adjustments are well-coordinated and traceable. Drew will work together with the City of Roseville to:
• Jointly define expectations
• Create detailed work plans
• Manage progress against plans
• Complete deliverables as efficiently and
effectively as possible
• Manage Deliverables quality
• Identify and mitigate project issues and risks
• Manage scope and schedule
• Achieve the expected business outcomes
within the allocated budget and schedule
Drew’s project management approach is based on the Project Management Institute’s (PMI) industry standard project management framework with a focus on an iterative approach. PMI’s project management lifecycle is a framework of processes and methodologies that can be deployed on an iterative, incremental process of managing a project. Key to this effort will be constant reassessment to verify all stakeholders are engaged and understand all that is taking place at a given time.
Project Management Expectations:
• Project plan and schedule
• Organize and attend regular project status meetings
• Develop meeting agenda and compile meeting notes
Drew Haney, GISP
PROJECT MANAGER
Drew comes with more than 25 years of experience making clients successful. His proven track record of managing utility projects, with clients like SDG&E and California Water, will be invaluable to making the Utility Network Migration a success.
His project management skills include scoping, budgeting, scheduling, client communications, invoicing, and project delivery.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 26
• Proactive and effective communications with City of Roseville project manager and stakeholders • Provide City of Roseville stakeholders with regular progress reports • Monitor scope/schedule/budget throughout the project
• Deliver the Work Plan for the initial set-up and ongoing delivery of services that addresses all tasks and proposed deliverables, and Change Management Plan to address and changes to SOW or project scope • Project Risk and Mitigation Plan that outlines project risks and mitigation strategies • Quality assurance/quality control (QA/QC) program for project deliverables Communication and Coordination Approach
Clear, consistent, and disciplined communication is essential to the success of a Utility Network migration, particularly when multiple City stakeholders, limited testing resources, and third-party vendors are involved. Our communication approach is designed to support transparency, timely decision-making, and predictable execution throughout the project lifecycle.
1898 & Co. will establish a structured communication framework at project initiation that defines meeting cadence, roles, decision points, and escalation paths. This framework is designed to keep City of Roseville leadership informed without overburdening staff, while maintaining alignment across technical and operational teams.
Key elements of our communication approach include:
Defined Meeting Cadence
We will facilitate recurring meetings aligned to project phase and need, including:
• Project kickoff and phase initiation meetings
• Weekly project status meetings focused on progress, risks, and upcoming decisions • Targeted workshops for data modeling, integrations, testing, and training • Ad hoc working sessions as required to resolve issues or support decisions Clear Documentation and Decision Tracking
All meetings will be supported by documented agendas, meeting notes, and action items. Key technical and business decisions will be recorded and tracked to support clarity, accountability, and schedule control. This approach reduces rework and helps maintain alignment as the project progresses.
Risk, Issue, and Change Communication
Risks, issues, and potential scope changes will be identified early and communicated clearly, along with recommended mitigation strategies. Our team will maintain visibility into these items and support City led decisions at defined checkpoints.
Collaboration Tools and Information Access
A shared project workspace will be used to provide controlled access to project documentation, schedules, deliverables, and meeting records. This supports version control, visibility, and efficient collaboration across City staff and project participants.
Escalation and Governance
An agreed escalation path will be established at project kickoff to support timely resolution of issues. This governance structure promotes efficient decision-making, minimizes delays, and aligns day-to-day execution with City priorities.
Figure 4 illustrates our proposed project escalation path and governance structure, showing how communication and decision-making flow between different organizational levels. Team Members raise issues and report progress to Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 27
Team Leads, who coordinate with Project Leadership. Project Leadership then engages the Steering Committee for higher-level input and direction. The left-hand arrow represents the upward flow of communications, such as status updates and risks. The right-hand arrow shows how decisions and issue resolutions move back down through the organization. For City of Roseville, this structure adds value by promoting transparency, reducing delays in resolving issues, and aligning decisions with both day to day operations and strategic goals. It helps maintain momentum, minimizes risk, and supports effective coordination across all project roles. This communication approach supports City staff by providing predictability, transparency, and clear lines of responsibility throughout the Utility Network migration.
Project Understanding Summary
1898 & Co. understands that the City of Roseville’s Utility Network migration is a complex, high impact initiative that extends beyond technology conversion. Success depends on disciplined data preparation, thoughtful system design, coordinated integration touchpoints, realistic testing strategies, and strong staff adoption. Our approach reflects a clear understanding of the City of Roseville’s operational environment, resource constraints, and long-term modernization goals. By combining proven Utility Network delivery experience with structured project management, transparent communication, and a collaborative execution model, 1898 & Co. is prepared to support the City of Roseville through a controlled transition that positions the electric GIS for sustained value well beyond project completion.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 28
Tab E: Project and Implementation Overview
Approach and Methodology
1898 & Co. views City of Roseville’s transition to Esri’s ArcGIS Utility Network as a foundational opportunity to advance operational performance, increase system reliability, and support enterprise-wide collaboration. We will work collaboratively with City of Roseville throughout this project to enable the transition to be successful and aligned with their strategic goals. This is not simply a technical upgrade; it is a strategic initiative that positions City of Roseville to meet the evolving demands of electric utility operations.
To successfully migrate to the Utility Network and move to the ArcFM XI Solution, City of Roseville will need a strategy that aligns technical execution with organizational readiness, combining data assessment, a utility-specific data model, and a migration framework that integrates with OMS, Synergi, FME, and Maximo. Just as critical are training and change management to equip staff across GIS, operations, and engineering to excel in the future state environments and processes. With these in place, City of Roseville can fully unlock the Utility Network’s potential to improve reliability, streamline workflows, and support real-time decisions.
To support City of Roseville’s strategic transition to the Esri Utility Network and ArcFM XI, 1898 & Co. proposes a structured and phased approach that aligns technical delivery with organizational goals. This methodology supports a smooth migration while strengthening system integration, data quality, and long-term operational capability. Our overall approach is shown in Figure 5.
Figure 5. Our approach to City of Roseville’s transition to Esri’s ArcGIS Utility Network & ArcFM XI will advance performance, increase system reliability, and support enterprise-wide collaboration.
Project Management Across the Delivery Lifecycle
Project management is applied consistently across all phases of the delivery lifecycle illustrated above, from Initialization through Hypercare. 1898 & Co.’s Project Manager maintains responsibility for coordinating scope, schedule, quality, and communication as the project progresses through design, pilot, build, testing, documentation, training, and cutover activities. This approach aligns with the project management framework described in Tab D and is designed to provide the City of Roseville with clear visibility into progress, risks, decisions, and upcoming activities at each phase transition. To support disciplined execution and transparency, 1898 & Co. maintains a structured project workbook that includes standard project-level logs such as the Risk Log, Issue Log, Action Item Log, Change Order Log, and Key Decision Log. These logs are actively maintained throughout the project to support Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 29
accountability, timely decision-making, and effective coordination. Examples of these project workbook logs are provided in Appendix B to demonstrate how they are used to contribute to successful project delivery.
Task 1: Initialization
Esri’s ArcGIS Utility Network combined with ArcFM XI offers City of Roseville a modern, scalable foundation for advancing network management across the organization. However, the true impact of the modernization depends on how well it aligns with City of Roseville’s operational goals, business processes, and technology environment. 1898 & Co. combines decades of utility experience with deep knowledge of GIS modernization and the ArcGIS Utility Network. Our team includes certified Utility Network and Schneider EcoExpert professionals who have applied this technology within electric distribution environments to support real-world operations.
Through stakeholder discovery sessions and a comprehensive review of City of Roseville’s GIS configurations, workflows, customizations, and integrations, we will identify how current systems operate and where improvements can be made. This collaboration will guide the development of a Current State and Future Vision Report, connecting City of Roseville’s organizational needs with the capabilities of the Utility Network.
The insights gathered will lead to actionable recommendations that adapt and strengthen City of Roseville’s workflows, helping the organization fully leverage the Utility Network to advance reliability, efficiency, and operational visibility.
1.1 Kickoff Meeting (Onsite)
1898 & Co. will lead an onsite kickoff meeting with the City of Roseville following contract award to formally initiate the project and establish a shared understanding of objectives, scope, roles, and expectations. The kickoff meeting will review the overall implementation approach for the Utility Network data migration, confirm key assumptions, and align on the project schedule and milestone structure.
These sessions will also be used to identify potential risks, constraints, and dependencies early, and to confirm the communication framework, stakeholder roles, and decision-making processes that will govern the project. The kickoff will establish the agreed project governance structure, identify primary and secondary stakeholders, and confirm the cadence and format of ongoing project meetings to support effective coordination throughout the engagement.
Deliverables
• Kickoff Meeting Minutes
o Confirmed project scope, objectives, and success criteria o Validated project schedule, milestones, and key assumptions o Defined roles, responsibilities, and escalation paths o Agreed communication plan and meeting cadence
o Initial risk and dependency identification
1.2 Requirements Gathering
Following the project kickoff meeting and initial data collection, 1898 & Co. will conduct in-person workshops to familiarize City of Roseville project resources with the foundational concepts of the ArcGIS UN. These sessions will help provide an improved understanding of the Utility Network and the functional differences between the Utility Network platform and City of Roseville’s existing ArcFM GIS environment. These sessions will provide essential knowledge to City of Roseville stakeholders regarding the UN and provide useful information for the later phases of the project.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 30
We will request and review existing documentation and conduct interviews with City of Roseville GIS and IT stakeholders to confirm available information and address information gaps. As part of the interviews, we will ask stakeholders to share their thoughts on expectations for the future state. 1898 & Co. will review City of Roseville’s current state business processes for managing its electric distribution assets, including: GIS data management processes, OMS/ADMS daily circuit builds, construction estimating processes, as-building processes, etc. We will document key pain points and stakeholder priorities for desired improvements.
These in-person workshops are designed to identify and document requirements from both business and technical perspectives. Following the workshops, we will leverage our experience with other clients as input and work with the City of Roseville team to complete an analysis of the requirements to confirm alignment with business needs and leading practices. We will also evaluate the documented current state GIS ecosystem and build out the requirements and specifications for the design and implementation. This evaluation will utilized in the data model design and migration plans. Once the analysis is complete, we will create a summary of requirements for review/confirmation with City of Roseville stakeholders.
1.3 Data Readiness Assessment
Establishing data readiness early is critical to the success of any Utility Network migration. Data cleanup can be time-intensive, and addressing issues later in the project can cause delays. By performing a comprehensive data assessment at the start, City of Roseville will gain early visibility into potential data quality or data modeling concerns and thus have the necessary time to resolve them well before full migration begins. This proactive approach reduces risk, improves migration efficiency, and enables a smoother transition to the Utility Network. 1898 & Co. will conduct a data discovery and requirements gathering session to collect the data required to complete the data readiness assessment. We will use City of Roseville’s source data to perform multiple types of data reviews, including geometry, domain and subtype checks. The data readiness assessment is intended to thoroughly assess existing network data using automated checks and visual spot checks. The results from this report and the remediation actions that are taken will help mitigate data-related issues in the migration to the Utility Network.
Figure 6. Our proposed data assessment will utilize Our proposed data assessment will utilize UN rules to help mitigate data UN rules to help mitigate data-related issues. related issues.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 31
Our experienced 1898 & Co. team will utilize the out of the box rules from the Utility Network and perform a draft migration, which we term Rapid Test, to the Commercial Off The Shelf (COTS) Schneider Electric UN file geodatabase for the electric utility types being migrated and provide a summary of the ArcGIS Utility Network dirty areas present after the draft migration. The high-level Rapid Test push helps to identify other errors based on the OOTB Utility Network rules themselves.
The data quality checks will focus on three key areas: basic integrity, attribute integrity, and spatial integrity.
The primary focus of this assessment is to analyze the source data’s readiness for a Utility Network data migration.
We will assign each result a severity code of 1, 2, or 3, shown in Figure 7. These severity codes are based on the potential impact of the data issue on migration to the Utility Network and are classified based on our team’s lessons learned on similar projects.
Severity
Code Description
1 Must be resolved in existing geodatabase instance prior to UN migration (geometry errors: self-intersecting lines, null geometry, out of bounds features, stacked verticies…) 2 Recommended to resolve issues in existing geodatabase instance prior to UN migration (stacked points, orphaned records or unsnapped geometry…) 3 Not critical for UN migration. However, addressing these issues prior to UN migration may result in a better migration experience
(non-Asset Group/Asset Type or migration related domain errors) Figure 7. Each severity code is based on the potential impact of the data issue when migrating to the Utility Network.
1898 & Co. highly recommends that City of Roseville address all Severity 1 type errors in the current production geodatabase before the Utility Network data migration as Severity 1 errors can compromise network functionality. A data readiness report will be provided to give an overview of the Rapid Test results and recommendations for resolving data quality errors. This will allow City of Roseville time to address the Severity 1 items required for allowing the migration of data from the Geometric Network to the Utility Network to occur, as well as supporting the goal of no data loss. The report will also identify issues that, if addressed, may improve the overall data quality in the GIS database. At this stage, errors related to ‘missing’ UN Rules will exist but will decrease in number after Data Modeling workshops are held and the UN model and migration scripts are updated per the City’s requirements.
1.4 Data Cleanup
1898 & Co. is also well-equipped to support City of Roseville through the data remediation process if requested.
Once the data readiness report is complete, we will provide an estimate for the level of effort and associated remediation steps required to address the identified issues to prepare the data for Utility Network migration. Based upon the RFP Q&A, we assume data cleanup will be performed by the City of Roseville, but 1898 & Co. can additionally provide support through a negotiated change order if needed.
Activities:
• Work with City of Roseville to schedule familiarization and requirements gathering workshops • Create information requests for City of Roseville to review and collect documentation prior to 1898 & Co. engagement.
• Review provided documentation on current state
• Conduct in-person workshops and create requirements inventory • Work with City of Roseville to design preferred migration strategy • Strategic consulting on System Architecture and Integration Assessment • Review requirements inventory with City of Roseville stakeholders for confirmation Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 32
Deliverables:
• Onsite workshops at City of Roseville’s with 1898 & Co.: Facilitate in-person sessions with stakeholders across GIS, Engineering, IT, and Operations to review current systems, gather business and technical requirements, and document migration needs.
• Current State and Future Vision Report: Provide a detailed report capturing City of Roseville’s existing GIS environment, key challenges, and a future-state Utility Network vision aligned with business and operational goals.
• Data Readiness Report: List of the data quality issues identified and prioritized based on severity. The report will provide examples of data quality issues along with recommendations for addressing identified data quality issues.
• Utility Network Dirty Area Rapid Test results in a file geodatabase Task 2: Design Architecture
2.1 System & ArcFM XI Solution Architecture
To confirm City of Roseville’s enterprise GIS system is architected and sized appropriately to meet the functional and technical needs of the organization and the ArcGIS Utility Network, 1898 & Co. will perform a high-level architecture review. The review shall evaluate City of Roseville’s current enterprise GIS configuration along with the future needs of the ArcGIS Utility Network and ArcFM Editor XI to provide recommendations for system architecture design.
Results from the assessment shall be summarized in a report and provided to City of Roseville as recommendations for future system architecture design.
1898 & Co. will additionally conduct a remote in-depth exploration for the current system architecture as it pertains to the implementation of ArcFM Editor XI and Session Manager and GDBM XI. This discussion will also include prerequisites and considerations for the ArcFM XI Suite.
2.2 ArcFM Editor XI (EXI) – Apps and Services
1898 & Co. will include an in-depth exploration of the overall system architecture and landscape for the implementation of ArcFM Editor XI, Session Manager and GDBM XI.
2.3 Systems Integration Assessment
There are several integrations that will need to be updated because of the change to the Utility Network. The table below lists the identified integrations from the RFP and a high-level assumption regarding the integration. As part of this phase, 1898 & Co. will capture current state requirements for the integrations for the Utility Network, shown in Table 2.
Interface Assumptions
Survalent SCADA/ADMS/OMS Grid operations need a full network model and connectivity.
CIS Meter and/or service point synchronization.
Leidos/Honeywell AMI/MDM Meter and/or service point synchronization.
Maximo Asset maintenance/asset lifecycle integration.
Milsoft WindMil 23.2.4 Engineering analysis needs a full network model and connectivity.
Table 2. We will capture current state requirements for UN integrations.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 33
2.4 Data Model Development & Workshop
1898 & Co. will conduct an initial detailed mapping of City of Roseville’s existing Electric Geometric Network (GN) data model against the ArcFM XI Electric Commercial-Off-The-Shelf (COTS) Utility Network data model. This effort will ultimately establish the foundation for a modified Utility Network asset package that aligns with City of Roseville’s operational and business needs.
The work will begin with a thorough data discovery process, during which our team will review City of Roseville’s current GIS data model, focusing on feature classes, attributes, domains, and established relationships. This review will identify any gaps between the existing GN schema and the ArcFM XI Electric Utility Network model, including missing asset types, required fields, or domain structures necessary for successful migration.
After our initial efforts, we will engage City of Roseville in a remote, collaborative data model design workshop to validate our work and to complete the build out of the future data model with primary stakeholders.
Building on the results of the mapping workshops, our team will then configure a customized Utility Network asset package tailored to City of Roseville’s electric distribution operations. During this effort, we will have touchpoints with key UN stakeholders to maintain visibility, promote collaboration, and allow for adjustments to be made to the Asset Package as they arise. The asset package will define the structure and behavior of critical system components, including:
• Asset groups and asset types for primary, secondary, and service-level assets. • Customized network rules and domain values to match operational and engineering standards. • Subnetwork definitions to support feeder management, outage isolation, and system tracing.
Throughout this configuration process, 1898 & Co. will maintain compatibility with Schneider Electric’s ArcFM XI environment, building an asset package that fully supports design workflows, editing environments, and Utility Network management practices.
Version alignment and platform compatibility will remain a top priority during Phase 2. Our team will identify, validate, and document the required versions of ArcGIS Enterprise, ArcGIS Pro, ArcFM XI and SQL Server needed to support Utility Network deployment and maintain a stable operational environment.
We will build internal quality assurance and quality control (QA/QC) checkpoints into each step of Task 2 to validate schema mapping and asset package design. After completing the initial versions, 1898 & Co. will lead a review session with City of Roseville stakeholders to confirm finalized structure before advancing to the pilot migration and full system rollout.
Activities
• Schema Mapping Document/Crosswalk (.xls) – Review City of Roseville’s existing GN GIS data model and align feature classes, fields, domain values, and subtypes with the corresponding Utility Network asset groups, asset types, and schema requirements. This foundational step supports an accurate and efficient migration into the Utility Network model.
• Build Asset Package – Based on Data Modeling Workshop results and crosswalk development, we will develop a customized Asset Package (.gdb) for City of Roseville. We will also convert this into a Utility Network (.gdb).
• Create Migration Workflow & Tools – Configuration of migration tool using Safe Software’s FME and/or ArcGIS Data Loader Tools. Implementing defined attribute transformations or reclassifications to meet the Utility Network’s data integrity, classification, and connectivity standards. This process will enable control Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 34
and consistency across iterative migration activities. Per the City’s request, we will also remove unused domains during the migration.
Deliverables:
• Schema Mapping Document/Crosswalk: A detailed spreadsheet resulting from on-site workshops, mapping City of Roseville’s GN GIS data model to the ArcFM XI Utility Network schema, including feature classes, subtypes, attributes, and domain translation rules.
• Customized Utility Network (converted from an Asset Package): A schema only Utility Network (file geodatabase) tailored to City of Roseville’s electric distribution system, including configured asset groups, asset types, domains, and network rules.
• HTML Data Dictionary: A web-based version of the UN database design. • Subnetwork Documentation: A plan outlining the subnetwork creation and updates aligned with City of Roseville’s operational practices.
• System Architecture and Integration Assessment: Perform high level evaluation of system architecture and current integrations with third-party systems (OMS, SCADA/ADMS, AMI, Asset Management, CIS) and outline the impacts, risks, and considerations for Utility Network migration.
Task 3: Design Requirements
For design requirements, 1898 & Co. and Schneider Electric will hold a remote (1) day workshop that will present the workflows, prerequisites and configuration for the successful implementation of Editor XI, Session Manager & GDBM XI.
3.1 ArcFM Editor (EXI): Editing Workflow and Tools
1898 & Co. and Schneider Electric will conduct a remote workshop for a maximum of one (1) business days to review the COTS Schneider Electric GIS application workflows for ArcFM Editor XI, GDBM XI and Session Manager.
3.2 System Integration Workshop – With GIS System
1898 & Co. and Schneider Electric will lead an integration design remote workshop of up to 40 hours to define the following integrations with the GIS system.
• Synergi
• OMS (Data Voice)
• Maximo (DataSplice)
• FME
• Attribute Assistant Add-on
3.3 ArcFM Editor XI (EXI): Configuration
1898 & Co. and Schneider Electric will lead a one (1) business day remote workshop with the customer to review the available configurations in the ArcFM Editor applications (EXI). The workshops will be conducted in knowledge transfer format and will serve as enablement for the customer to perform any configurations available in the applications.
Deliverables:
• EXI/Session Manager/GDBM Workflow Document: A summary of workshop content and findings. • EXI/Session Manager/GDBM Configuration Document: A requirements summary of workshop details.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 35
• System Integration Document: A summary of workshop findings.
Task 4: Pilot Area Migration and UN Testing
Using a system-wide data pull (.gdb) from City of Roseville, our team will execute a complete migration to the Utility Network in a test environment. We will enable network topology and publish services to confirm edit, and trace capabilities. This allows early validation of assumptions and mitigates risks before system-wide rollout. It will also allow City of Roseville staff the first opportunity to interact with the Utility Network, familiarize with ArcGIS Pro processes, perform tracing, and test out integrations with the Utility Network schema and services.
The pilot migration process includes:
• Preliminary Data Migration: System-wide GN data will be migrated to the ArcGIS Utility Network in a file or mobile geodatabase and pasted into SDE. Using ArcGIS Pro & Portal – services will be published. This will allow for the validation of schema mapping, domain configuration, and test subnetwork creation. • Dirty Area Identification: After migration, the Utility Network Dirty Area layer will be auto-populated and can be used to identify rule violations and inconsistencies. These Dirty Areas represent issues where network rules are not being met and must be corrected for accurate tracing and network validation. • Topology and Subnetwork Testing: The pilot dataset will be used to validate network topology and test subnetwork management.
4.1 Pilot Data and Migration Iterations
Migration iterations (.gdb) and final Pilot Migration (.gdb to SDE) will be used to continuously refine the migration process and additionally identify status of error resolution identified in the initial Data Readiness exercise. We propose data issues identified during pilot testing should be addressed in the current Production GN Throughout these migrations processes, 1898 & Co. will closely track observations, lessons learned, and refinements needed to improve the migration methodology. Insights gained during the test migrations and pilot will directly inform and optimize the strategy for the production migration in Phase 9, helping to mitigate risk and support a smooth rollout.
Deliverables
• A Pilot Area Data Migration Report summarizing findings and refinements to be applied to the full migration.
• Documented Dirty Area classifications observed in the pilot environment. • Functional validation of trace tools, editing workflows, and web service operation. • A refined migration and configuration approach based on observed behavior and feedback.
Task 5: Build
During this phase, 1898 & Co. will perform the configuration and setup activities required to prepare the Esri ArcGIS Enterprise environment and ArcFM XI platform for operational use. This task transitions the project from design and planning into a functional system state that supports ArcFM editing, Utility Network operations, and GIS-side interfaces. Activities focus on configuring supported components, publishing required services, and validating that the environment is ready for testing and user interaction.
All build activities will leverage requirements, decisions, and configurations defined during prior design and workshop phases. Configuration will follow vendor-supported, out-of-the-box practices to promote system stability, maintainability, and long-term sustainability.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 36
5.1 ArcGIS Enterprise and Portal Configuration
1898 & Co. will work with City of Roseville to configure the ArcGIS Enterprise environment required to support ArcFM XI and the Utility Network implementation. This includes validating Portal configuration, establishing required user roles and groups, and preparing the environment for service publication and access by ArcFM XI tools.
As part of this effort, 1898 & Co. will configure Portal groups and access controls to support editing workflows, service consumption, and interface needs, consistent with City security and governance practices.
5.2 Publish Utility Network and Supporting Services
1898 & Co. will publish the required Utility Network and supporting feature services from the configured geodatabase to ArcGIS Enterprise. These services will be configured to support ArcFM XI editing, tracing, subnetwork management, and GIS-side integration touchpoints. Service configuration will include validation of permissions, access patterns, and operational behavior necessary to support ArcFM workflows and downstream system interfaces, as defined during prior integration and design workshops. 5.3 Setup ArcFM Tenant 1898 & Co. will coordinate with Schneider Electric’s infrastructure team and City of Roseville to establish the required ArcFM tenant(s) as part of the ArcFM XI Suite. This includes confirming connectivity, authentication, and prerequisite configurations necessary to enable ArcFM XI tools within the City’s ArcGIS Enterprise environment.
5.4 Configure EXI Tools
1898 & Co. will install and configure ArcFM Editor XI (EXI) components, including Session Manager and GDBM XI, using the ArcFM Solution Center application. Configuration settings will be based on outcomes from prior ArcFM XI workshops and will align with supported out-of-the-box workflows. This effort establishes the core editing environment used by City of Roseville staff for Utility Network data maintenance and management.
5.5 Configure Out-of-the-Box AutoUpdaters
1898 & Co. will configure supported out-of-the-box AutoUpdaters to operate within the City of Roseville’s EXI environment. These AutoUpdaters support standard data maintenance and validation behaviors consistent with ArcFM XI and Utility Network requirements. Development of custom AutoUpdaters is not included in this scope and would require a separately negotiated change.
Deliverables
• Configured ArcGIS Enterprise and Portal environment to support ArcFM XI and Utility Network operations • Published Utility Network and supporting feature services with validated permissions and access • Configured ArcFM XI tenant and EXI components
• Validation of out-of-the-box AutoUpdaters and supported editing workflows • Environment validation results confirming readiness for testing and interface consumption Task 6: Testing
Testing of the ArcFM Utility Network model will be performed by creating a test plan that includes a variety of scenarios that the City performs today. This involves test cases for data validation, editing, and tracing. ArcFM Editor XI testing will focus on the functionality of the editing tools, ensuring that they are working as expected and that they are properly interacting with the utility network model. This testing includes scenarios for creating, editing, and deleting features, as well as testing the undo and redo functionality.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 37
6.1 EXI: Factory Acceptance Testing (FAT)
Confirms the GIS editing solution meets all utility-specific requirements before it is deployed into the production environment. This process involves simulating the entire operational workflow, from data editing and validation to network analysis, to identify and resolve any issues before the system goes live.
6.2 EXI: Site/User Acceptance Testing (SIT/UAT)
Testing is performed by the end-users of the software to validate that it meets their business requirements in a realworld context. This phase involves users executing their daily editing and data management workflows, such as creating and updating features, running validation rules, and performing network traces, to confirm the system functions as expected before it is approved for release into the production environment.
Deliverables
Documentation of testing results, bug tracking and fixes for each round of testing listed above.
Task 7: Training
Our team will deliver end-user and admin training, tailored documentation, editing guides, and subnetwork updating workflows. We will also provide post-go-live stabilization support, enabling a confident transition. As City of Roseville prepares to transition fully to the ArcGIS Utility Network, 1898 & Co. will focus on equipping your staff with the knowledge, tools, and support needed to operate and sustain the new system with confidence. This phase centers on workforce readiness, system handoff, and a seamless go-live experience.
Activities
• Tailored Training Sessions – 1898 & Co. will lead hands-on, role-based training for system administrators, GIS editors, power users, and other identified stakeholders. Training will be purpose-built for the City of Roseville and aligned with actual workflows, operational priorities, and Utility Network responsibilities rather than generic product instruction. A comprehensive Training Plan will be developed early in the project in partnership with the City of Roseville and will define training options, delivery approach, staffing expectations, class size and skill level by audience, training materials, and the functional responsibilities addressed in each session to prepare users for their day-to-day tasks within the Utility Network environment. • Custom Documentation – We will develop comprehensive user and administrative guides, including editing instructions, subnetwork management practices, and trace configuration documentation. These materials will serve as long-term references for staff and support future onboarding efforts. • Configuration Tools and Editing Support – As part of the go-live preparation, we will deliver tools and best practices to manage trace rules, maintain network topology, and troubleshoot common issues in real-time.
This includes guidance on editing workflows, versioning, and maintaining system health. • Cutover Planning and Execution – Working closely with City of Roseville’s team, we will execute the final cutover to the production Utility Network environment based on an agreed-upon schedule. This includes final data loads, service validation, and system readiness checks. This effort will also include the • Post-Cutover Stabilization – Following cutover, 1898 & Co. will remain engaged for a 60-day stabilization period. During this time, our team will assist with issue resolution, performance monitoring, and any final adjustments needed to optimize day-to-day operations in the new environment.
Deliverables
• Training Plan, Training sessions, and user onboarding • Complete set of tailored documentation and configuration guides Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 38
• Final system cutover and production launch
• Post-go-live support to reinforce adoption and address emerging needs Task 8: Full System Migration and Configuration to UN Production Environment With lessons learned from the pilot, we will execute the full migration of City of Roseville’s electric network, publish Utility Network services and web maps and test third-party system touchpoints. This phase represents the transition from isolated testing to enterprise deployment, with a strong focus on configuration accuracy, system integrity, and cross-platform integration, as determined by City of Roseville.
The full system migration includes:
• Comprehensive Data Migration – All relevant electric distribution system data will be migrated from the Geometric Network into the Utility Network using the finalized schema asset package developed earlier in the project with City of Roseville. Migration processes will follow the tested methodology proven during the pilot.
These migration efforts only include data directly participating in the Utility Network itself. • Utility Network Services Configuration – Core Utility Network services will be published, allowing for network validation, subnetwork management, network topology, and tracing. • Validation and Testing – The Utility Network implementation will undergo full-scale testing for performance, accuracy, and usability. Dirty Area layers, trace operations, editing capabilities, and security settings will be reviewed to confirm system readiness.
• Configure Production ArcFM Tenant and tools – This effort assumes existing configuration from the test environment will be transferred over to production.
Deliverables
• A fully migrated and configured Utility Network for City of Roseville’s electric distribution system. • Final documentation of the migration process, configuration settings, and system architecture Task 9: Hypercare
Following production cutover, 1898 & Co. will provide a structured 60-day hypercare period to support the City of Roseville as the Utility Network and ArcFM XI environment transitions into day-to-day operations. The purpose of hypercare is to stabilize the production environment, support City of Roseville staff during early adoption, and address issues directly related to the implementation and migration activities performed under this project. This hypercare model reflects industry-standard practice for post–go-live support following major GIS and Utility Network implementations and is widely used to provide focused stabilization while controlling overall project cost.
During the hypercare period, 1898 & Co. will support the production environment by identifying, tracking, and assisting with the resolution of post–go-live issues and defects associated with the Utility Network and ArcFM XI configuration. Issues will be logged, reviewed, and prioritized in coordination with City of Roseville staff using agreed severity levels to support effective triage and resolution sequencing.
At the conclusion of the hypercare period, 1898 & Co. will support transition to steady-state operations by documenting outstanding items and coordinating handoff of unresolved lower-priority issues. Any work requested beyond the defined hypercare scope, such as extended operational support, may be addressed through a separately negotiated change. While the City of Roseville’s RFP references a longer-term support duration, separating post–golive stabilization from ongoing support services allows the City of Roseville to procure extended support in a more targeted and cost-effective manner, aligned with actual operational needs following system adoption.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 39
Hypercare Assumptions
The hypercare services described above are based on the following assumptions:
• Hypercare support applies to issues and defects directly related to the Utility Network migration, ArcFM XI configuration, and implementation activities performed under this scope of work. • Defects inherent to third-party software platforms are excluded. • Issues associated with legacy systems or legacy-side integrations are excluded. • Middleware or integration components not configured by 1898 & Co. are excluded. • Data quality issues unrelated to the migration or conversion process are excluded.
Project Schedule
A detailed Gantt chart documenting the project phases, durations, and dependencies is provided separately in Attachment G in the required formats. The task-level project schedule below highlights the major activities and sequencing associated with our implementation approach. 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Task Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Task 1 - Initialization
Task 2 - Design Architecture
Task 3 - Design Requirements
Task 4 - Pilot Area Migration and UN Testing
Task 5 - Build
Task 6 - Testing
Task 7 - Training
Task 8 - Go Live
Task 9 - Hypercare
2026 2027
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 40
General Assumptions and Project Clarifications
All information presented in this proposal has been provided for informational and evaluation purposes only. This proposal is not intended to constitute a binding offer. Any binding agreement is subject to incorporating a mutually executed Agreement consisting of negotiated terms and conditions and a statement of work with a defined scope, deliverables, schedule, and fees.
• Pricing Structure and Billing
This proposal is submitted on a fixed-price, milestone-based basis. The fixed fee includes professional services and travel associated with two onsite visits for Project Kickoff and Training, with hypercare billed at initiation of the post–go-live period.
• Onsite Commitment
The proposed scope includes two onsite visits to the City of Roseville with an average of three 1898 & Co. team members per visit. The City of Roseville will provide reasonable onsite support, including meeting space and IT connectivity as needed.
• ArcFM XI and Utility Network Implementation Approach
The implementation will use the ArcFM Electric Utility Network Commercial-Off-The-Shelf model, out-ofthe-box AutoUpdaters, and supported ArcFM XI workflows. Custom ArcFM development, custom AutoUpdaters, ADMS feeder service modification, and Conduit Manager configuration are excluded unless explicitly stated.
• Licensing, Infrastructure, and System Access
The City of Roseville will provide required Esri and Schneider Electric licenses, infrastructure, environments, and system access necessary to support ArcGIS Enterprise, Utility Network, and ArcFM XI activities. • Utility Network and Platform Version Alignment
Target versions for ArcGIS Enterprise, ArcGIS Pro, Utility Network, ArcFM XI, and supporting platforms will align with vendor-supported versions mutually agreed at project initiation. Our standard approach and working assumption is to leverage a Network Management Release version (the latest being ArcGIS Enterprise
11.5 and ArcGIS Pro 3.5). Version changes after design approval may affect scope, schedule, or fees. • Integrations and Third-Party Systems
Integrations are coordinated and validated on the GIS side only, and third-party systems remain City and vendor owned. Configuration or modification of third-party systems, middleware, or vendor-managed integrations is excluded unless explicitly defined.
• Third-Party Vendor Responsibility
1898 & Co. does not assume responsibility for inherent defects, limitations, or behavior of third-party software platforms. Vendor product issues, platform changes, or legacy system behavior are excluded from scope.
• Data Access, Quality, and Remediation
The City of Roseville will provide timely access to GIS data and documentation required for assessment and migration activities. Data quality issues unrelated to conversion or migration, including legacy data not previously cleansed, are excluded unless otherwise agreed. • Data Remediation Responsibility
Resolution of Severity 1 data issues identified during the Data Readiness Assessment is assumed to be performed by the City of Roseville in a timely manner that aligns with 1898 & Co.’s project plan. Assistance from 1898 & Co. beyond assessment and guidance may be provided through a separately negotiated change. • Stakeholder Participation and Scheduling
The scope assumes participation in approximately five to ten cross-functional stakeholder workshops over a two-week period. Delays in stakeholder availability or scheduling may impact the project timeline. • City Coordination and Decision-Making
The City of Roseville will designate a primary project contact to support coordination, scheduling, and decision-making. Timely review and approval of deliverables are required to maintain the proposed schedule.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 41
• Feedback and Review Timelines
Deliverable reviews are assumed to occur within five business days unless otherwise agreed. Additional review cycles or expanded feedback beyond scope may require schedule or fee adjustments. • Testing Scope and Acceptance
Testing is limited to validation of Utility Network migration, ArcFM XI configuration, and GIS-side services described in this proposal. Final system acceptance is performed by the City of Roseville with support from 1898 & Co.
• Change in Business Processes or Requirements
Core business processes and requirements identified during design are assumed to remain materially consistent. Significant changes to workflows, asset modeling, or operational requirements may impact scope, schedule, and fees.
• Regulatory, Security, or Policy Changes
Changes to regulatory requirements, cybersecurity standards, or City security policies occurring after project initiation that materially affect system design may require scope or schedule adjustments. • Warranty and Post–Go-Live Support
Consistent with the RFP Q&A, the warranty functions as extended post–go-live implementation support similar to hypercare, and applies only to issues attributable to migration and configuration activities performed by 1898 & Co. It is not a product warranty and excludes third-party software defects, legacy system behavior, and post–go-live operational changes.
• Out-of-Scope Changes
Requests for additional services; extended support beyond hypercare, expanded integration responsibilities, or evaluations beyond those described require a written amendment and may impact fees and schedule. • Proposal Validity
This proposal and fee shall remain valid for a period of ninety (90) days from the proposal submission deadline.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 42
Tab F: Cost Proposal
1898 & Co., part of Burns & McDonnell, is submitting this cost proposal on a fixed-price basis in the amount of $935,000, subject to the scope of services and corresponding assumptions outlined in this proposal. The proposed fixed fee includes all travel expenses associated with the engagement, including two onsite trips for the Project Kickoff and Training activities. Pricing is structured around defined project milestones, with billing aligned to the delivery of milestones. The key project milestones and associated fees are presented below.
Milestone Milestone Name (Task) Milestone Description Billing Trigger Fee Milestone 1 Project Kickoff (Task 1 –
Initialization) Completion of onsite project kickoff Project Kickoff Meeting $50,000 Milestone 2 Data Readiness and Migration
Planning (Task 1.3, Task 1.4)
Data Readiness Assessment, Rapid
Test migration results, severity
classification, and delivery of Data
Readiness Report
Delivery of data
readiness
deliverables
$90,000
Milestone 3
Architecture and Data Model
Design (Task 2 – Design
Architecture)
Completion of system and ArcFM XI
architecture review, integration
assessment, schema mapping, asset
package design, and delivery of
associated documentation
Delivery of Task 2
deliverables $175,000
Milestone 4
ArcFM XI Design and
Integration Definition (Task 3 –
Design Requirements)
Completion of ArcFM XI workflow
workshops, integration design
workshops, and delivery of EXI,
Session Manager, GDBM, and
integration documentation
Delivery of Task 3
deliverables $180,000
Milestone 5
Pilot Migration and Validation
(Task 4 – Pilot Area Migration
and UN Testing)
Completion of pilot migration,
topology and subnetwork validation,
Dirty Area analysis, and Pilot
Migration Report
Delivery of pilot
migration results $100,000
Milestone 6 Platform Build and Service
Enablement (Task 5 – Build)
Configuration of ArcGIS Enterprise
and Portal environment, publication
of Utility Network and supporting
services, ArcFM tenant setup, EXI,
Session Manager, and GDBM
configuration, and environment
readiness confirmation for testing and
interfaces
Delivery of Task 5
deliverables $100,000
Milestone 7 Testing and User Acceptance
(Task 6 – Testing)
Completion of Factory Acceptance
Testing and Site/User Acceptance
Testing
Delivery of testing
results $100,000
Milestone 8 Training and Production
Migration (Task 7, Task 8)
Completion of training delivery,
documentation, full system migration
to production Utility Network, service
publication, and system cutover
Acceptance of
production
migration
$100,000
Milestone 9 Hypercare Initiation (Task 9 –
Hypercare)
Initiation of post–go-live hypercare
support
Start of hypercare
period $40,000
TOTAL $935,000
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 43
Hourly Rates Statement and Level of Effort
The RFP requests a schedule of hourly rates and the estimated amount of time each proposed staff member will be devoted to the project. 1898 & Co. respectfully notes that this proposal is submitted on a fixed-fee basis, rather than a time-and-expense/time-and-material delivery model.
Under a fixed-fee structure, 1898 & Co. assumes responsibility and risk for managing labor mix, staffing levels, subconsultant and internal effort required to complete the defined scope of work for the agreed price. As such, the project fee is based on overall scope, complexity, risk allocation, and delivery outcomes, rather than a rate-based build-up tied to individual personnel hours. Providing estimated hours and individual billing rates would not accurately reflect how work is planned, staffed, or managed under a fixed-fee engagement and could be misleading when interpreted outside of a time-and-expense framework.
This fixed-fee structure applies not only to 1898 & Co.’s internal delivery effort, but also to any subconsultant services included within the proposed scope, along with the risks of managing the subconsultant. All subconsultant support has been secured on a fixed-fee basis and is fully incorporated into the total proposed price. This approach further reinforces cost predictability for the City of Roseville and avoids the administrative complexity and variability associated with rate-based or time-and-expense arrangements.
The proposed fixed fee represents the full cost for delivering the services described in this proposal, including project management, technical delivery, quality control, coordination, documentation, and travel, regardless of actual internal labor hours expended. This approach provides the City of Roseville with cost predictability, budget certainty, and reduced administrative burden, which aligns with the City’s stated preference for fixed pricing.
If requested during contract negotiations, 1898 & Co. is willing to further discuss high-level staffing assumptions, role responsibilities, and relative allocation of effort to support transparency. To that end, and in good-faith response to the RFP Section 6.8 Cost Proposal requirements, a Resource Allocation Summary table is provided below to illustrate the approximate distribution of the total project fee across key project roles, including subconsultant support, for informational purposes only. This summary is not intended to represent billable rates, hours, or a time-and-expense pricing model, and the fixed-fee commercial structure will remain unchanged.
Resource Name Project Role Title Percentage (%) of
Total Project Fee
Drew Haney, GISP Project Manager and GIS Consultant 20% Ben Stafford, GISP QA/QC Lead 5%
Matt Seidl, P.E. Process and Requirements Lead 14%
Cristin Holmgren Utility Network Lead 25%
Darris Friend Solution Architect 15%
Eva Shafman Data Lead 10%
Schneider Electric ArcFM XI Product Support Subconsultant 11% Chad Pinarija Engagement Lead No Charge
Brian Hiller GIS Managing Director No Charge
Percentages shown are approximate allocations for informational purposes only and do not represent billable rates, hours, or a time-and-expense pricing model.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 44
Tab G: Required Statements/Documents
Non-substitution for the designated members of the team without approval by City staff (Section 5.0) • Substitution of designated members of the team will not be made without approval by City staff.
The absence of a conflict of interest (Section 10.4)
• There is no conflict of interest as per Section 10.4.
Indicate your ability and agreement to fulfill the indemnification and insurance requirements contained in the sample contract (Section 10.7). (Please note that actual certificates of insurance are not required as part of your submittal.)
• We are able and agree to fulfill the indemnification and insurance requirements contained in the sample contract upon discussions and mutual negotiation as described in Tab H.
A statement that nothing contained in the submitted proposal will be proprietary. (Section 10.23) • Nothing contained in this proposal is proprietary.
Proof of registration with California Secretary of State. Note: All proposers must be registered with the Secretary of State or have a valid exemption by the time of award.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Attachment A
PROPOSER’S CERTIFICATION
I hereby propose to furnish the goods or services specified in the Request for Proposals (“RFP”). I agree that my proposal will remain firm for a period of up to ninety (90) days in order to allow the City of Roseville (“City”) adequate time to evaluate the qualifications submitted.
I have carefully examined the Request for Proposals and any other documents accompanying or made a part of this RFP. The information contained in this proposal is true and correct to the best of my knowledge and is signed under penalty of perjury under the laws of the State of California. I further certify that I am duly authorized to submit this proposal on behalf of the firm as its authorized agent and that the firm is ready, willing and able to perform if awarded the contract.
I further certify that this proposal is made without prior understanding, agreement, connection, discussion, or conspiracy with any other person, firm or corporation submitting a proposal for the same product or service; that this proposal is fair and made without outside control, collusion, fraud or illegal action; that no officer, employee or agent of the City or any other proposer is financially interested in said proposal; that no undue influence or pressure was used against or in concert with any officer, employee or agent of the City in connection with the award or terms of the contract that will be executed as a result of this RFP; and that the undersigned executed this Proposer’s Certification with full knowledge and understanding of the matters therein contained and was duly authorized to do so.
_________________________________________________
NAME OF BUSINESS
_________________________________________________
SIGNATURE
_________________________________________________
NAME & TITLE, TYPED OR PRINTED
_________________________________________________
MAILING ADDRESS
_ _____________________________________
TELEPHONE NUMBER
_________________________________________________
EMAIL
Type of Organization:
____ Sole Proprietorship ____ Corporation ____ State of Incorporation ________ Partnership ____Limited Liability Company
Burns & McDonnell Western Enterprises, Inc.
Stephen Kane, Vice President
145 S. State College Blvd., Suite 600, Brea, CA 92821
+
__
1 (7
___
14 ___
) 264-7333
___
[email protected]
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Attachment B
LEVINE ACT DISCLOSURE STATEMENT
(The completed form submitted to the City of Roseville is a public record.) California Government Code Section 84308, commonly referred to as the "Levine Act," prohibits any “Officer” (elected or appointed officer, any alternate thereto, and any candidate for elective office) from participating in any consideration or action related to a proceeding if they receive political contribution(s) from a party, or its agent(s), totaling more than $250 within the previous twelve (12) months, while a proceeding is pending, and for twelve (12) months following the date of a final decision in a proceeding concerning a license, permit, other entitlement for use, franchise, or contract (collectively “license, permit, or contract”). For additional information:
https://www.roseville.ca.us/government/departments/city_clerk/transparency/levine_act.
City Officers are listed at the following sites:
• The Members of City Council - https://www.roseville.ca.us/government/city_council/meet_council • Boards & Commission Members - https://www.roseville.ca.us/government/boards_commissions Parties and their Agents are responsible for reviewing and disclosing their applicable contributions to City Officers on the record of a proceeding.
1. Have you or your entity, or any agent on behalf of youor your entity, made any political contribution(s) totaling more than $250 to any City Officer in the twelve (12) months preceding the date of the submission of your license, permit, or contract, or the anticipated date of any City Council, Board, or Commission consideration or action related to this license, permit, or contract? YES _____ NO _____
If yes, please identify the City Officer(s):________________________________________________________________________________
2. Do you or your entity, or any agent on behalf of you or your entity, anticipate orplan to make any political contribution(s) totaling more than $250 to any City Officer in the twelve (12) months following any City Council, Board, or Commission consideration or action related to this license, permit, or contract?
YES _____ NO _____
If yes, please identify the City Officer(s):_______________________________________________________________________________ Answering yes to either of the two questions above does not preclude the City of Roseville from considering and/or taking action on a license, permit, or contract. It does, however, potentially preclude the identified City Officers from participating in consideration of and in taking any actions related to the license, permit, or contract. Please accurately complete and sign this form, under the penalty of perjury:
____________ ___________________________________________ _______________________________________ (Date) (Printed Name/Title of Authorized Representative) (Name of business/legal entity) ___________________________________
(Signature)
You must submit a supplemental form if you make any new reportable contribution(s) while the contract, license, permit, or other entitlement is being considered. If this form has not previously been submitted in connection with a contracting, licensing, entitlement or permitting process, please provide the completed form to the Office of the City Clerk for appropriate departmental routing, at: City Clerk, 311 Vernon St., Roseville, CA 95678, [email protected] 1/14/2026 Stephen Kane, Vice President Burns & McDonnell, Western Enterprises, Inc.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
LEVINE ACT DISCLOSURE STATEMENT
(The completed form submitted to the City of Roseville is a public record.) Term Definition Law
Covered
"proceedings"
A proceeding to grant, deny, revoke, restrict, or modify a license, permit or other entitlement for use, that does not solely involve purely ministerial decisions and is:
(1) Applied for by the party;
(2) Formally or informally requested by the party; or
(3) A contract between the agency and the party or a
franchisee granted by the agency to the party, other than a contract that is competitively bid, a labor contract, or a personal employment contract.
FPPC Reg 18438.2(a)
Party
Any person who files an application for, or is the subject of, a proceeding involving a license, permit, or other entitlement for use.
Gov. Code 84308(a)(1)
Participant
Any person who is not a party but who actively supports or opposes a particular decision in a proceeding involving a license, permit, or other entitlement for use and who has a financial interest in the decision. A person actively supports or opposes a particular decision in a proceeding if that person lobbies in person the officers or employees of the agency, testifies in person before the agency, or otherwise acts to influence officers of the agency.
Gov. Code 84308(a)(2)
FPPC Reg 18438.4
Agent
A person who represents a party or participant for
compensation and appears before or otherwise communicates with the governmental agency for the purpose of influencing the pending proceeding. See FPPC Reg 18438.3 for exceptions for certain consultants.
FPPC Reg 18438.3
Competitively Bid
A contract required by law to be awarded to the lowest
responsible bidder with a responsive bid, or, if the successful bidder refuses or fails to execute the contract, to the next lowest bidder with a responsive bid.
FPPC Reg 18438.2(a)(3)(A)
Labor Contract
A contract or agreement reached through collective bargaining or with a representative group regarding the salary, benefits, or terms and conditions under an employment or retirement
policy for employees or retirees, including a project labor agreement entered under Public Contract Code Section 2500.
FPPC Reg 18438.2(a)(3)(B)
Personal Employment
Contract
A contract for employment, including the terms and conditions of employment, between the agency and an agency employee.
A contract with an independent contractor is NOT a personal employment contract.
FPPC Reg 18438.2(a)(3)(C)-
(D)
A party to a proceeding before an agency involving a license, permit, or other entitlement for use shall disclose on the record of the proceeding any contribution in an amount of more than two hundred fifty dollars ($250) made within the preceding 12 months by the party or the party's agent.
A party, or agent to a party, to a proceeding involving a license, permit, or other entitlement for use pending before any agency or a participant, or agent to a participant, in the proceeding shall not make a contribution of more than two hundred fifty dollars ($250) to any officer of that agency during the proceeding and for 12 months following the date a final decision is rendered by the agency in the proceeding.
(Gov. Code, § 84308, emphasis added.)
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Attachment D
NONCOLLUSION DECLARATION TO BE EXECUTED BY
BIDDER AND SUBMITTED WITH BID
The undersigned declares:
I am the _________________ of ______________________, the party making the foregoing bid.
The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on _______________________ [date], at _____________________ [city], ________________ [state].
____________________________________
(Signature of Declarant)
Vice President
Burns & McDonnell Western
Enterprises, Inc.
1/14/2026 Brea
California
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 45
Tab H: Exceptions
1898 & Co., part of Burns & McDonnell Western Enterprises Inc. (“1898 & Co.”), has reviewed the City of Roseville (“City”) GIS ESRI Utility Network Data Migration Request for Proposal (RFP #07-104) and all supplemental documents, including the Sample Contract (Attachment C). We agree that upon the award of this project to 1898 & Co. such terms and conditions, subject to final negotiation, can be the basis for mutual agreement.
In general, 1898 & Co. seeks a fair and mutually beneficial Agreement which embodies the following concepts and would propose to discuss modifications to the contract to meet these mutually beneficial objectives.
• A standard of care which is insurable and consistent with industry practices for similar work or services in the location of the Project.
• Standard industry warranties that define the basis of defective work and remedies to correct such defects discovered within a reasonable timeframe.
• Indemnity for third-party claims based upon a party’s fault. • Insurance types and limits appropriate for the scope of work, along with a mutual waiver of subrogation with respect to property insurance.
• Intellectual property terms that allow the City to fully utilize the deliverables for the Project, but also allow 1898 & Co. to retain its rights in pre-existing IP and proprietary software and protects 1898 & Co. from the City’s future reuse of 1898 & Co.’s work product. • Protection on the reliance of information and data provided to 1898 & Co. by the City. • An appropriate aggregate monetary cap on 1898 & Co.’s liability to the City and a mutual waiver of consequential damages.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 46
Tab I: Competency of Proposers
1898 & Co., part of Burns & McDonnell Western Enterprises Inc., confirms that we have the necessary facilities, ability, experience, and financial resources to provide the services specified herein in a satisfactory and timely manner which has been thoroughly demonstrated in the previous sections.
Please list and explain any pending bankruptcies, liens, stop payment notices, judgments, lawsuits, arbitrations, mediations, foreclosures, and any similar actions filed or resolved in the past seven (7) years. • Burns & McDonnell Western Enterprises Inc. does not have any pending bankruptcies, liens, stop payment notices, judgments, lawsuits, arbitrations, mediations, foreclosures, and any similar actions filed or resolved in the past seven (7) years.
Please indicate whether a client has ever terminated a contract with your firm for breach, and if so, please explain.
• Burns & McDonnell Western Enterprises Inc. has never had a client terminate a contract with the firm for breach.
Also, furnish a statement of financial resources demonstrating that the Consultant has the ability to maintain a staff of regular employees, sub-consultants or sub-contractors adequate to ensure continuous performance of work, and demonstrating that the equipment for the work contemplated is sufficient, adequate and suitable.
• Burns & McDonnell is a financially strong, 100 percent employee owned engineering, architecture, construction, environmental, and consulting firm with the resources, experience, and organizational depth necessary to successfully perform the services contemplated. The firm’s strong financial performance is demonstrated by sustained growth and long term stability, with annual revenues of $3.8 billion in 2019, $3.6 billion in 2020, $4.62 billion in 2021, $6.5 billion in 2022, $6.4 billion in 2023, and $6.5 billion in 2024. Burns & McDonnell maintains a confidential amount of cash and investment balances, has no current or long term bank borrowings, consistently achieves positive net income, and maintains backlog levels exceeding $3 billion. As sales and revenues have grown, the firm has expanded its professional staff from approximately 7,600 employees in 2021 to more than 15,000 in 2026, ensuring adequate staffing to support uninterrupted and timely project delivery. Since its founding in 1898, the company has completed only three acquisitions, most recently in 2018, demonstrating a disciplined approach to growth and long term stability. The firm’s robust financial position supports continuous operations, sustained staffing, and ongoing investment in advanced technologies, equipment, software, and quality control systems, enabling effective coordination, documentation, and delivery of high quality services.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 47
Appendix A: Resumes
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Drew Haney, GISP
Project Manager
EDUCATION
Masters, Geography
Bachelors, Geography
CERTIFICATIONS
Certified GIS Professional
(GISP)
EXPERIENCE
28 years of experience
Based in San Diego, Drew is a Project Manager and Senior Geographic Information Systems specialist with 28 years' experience in geographic information systems and data analysis, including 17 at 1898 & Co., part of Burns & McDonnell. This experience includes data analysis and support for several California electric utilities, water utilities and ports in their water, transmission and electrical operations. His current responsibilities include managing the geospatial transmission scheduling display for a large California electric utility, GIS project management for a California Water District, technical project management, database and customer support using Geographic Information System (GIS) software, automation, and data integration.
PROJECT EXPERIENCE
CAL WATER FME SUPPORT | California Water Service Group
La Jolla, California | Jan 2024 - current
Project Manager. Drew provided configuration and development of Safe Software Feature Manipulation Engine (FME) translations, workflows, and documentation. Documentation focused on specific areas where FME may need to be adjusted at later dates for Application Programming Interface (API) locations from Google and MuleSoft and other data transformations occurring within the automation. Project management meetings were scheduled to knowledge transfer the FME creation and workflows to internal Cal Water project management personnel. Drew currently manages the client for additional FME processes that are identified.
FAIRFAX WATER UTILITY NETWORK | Fairfax County Water
Authority
Fairfax, Virginia | Oct 2023 - Apr 2024
Senior GIS Consultant. 1898 & Co. is migrating Fairfax Water's GIS asset network into the water distribution ArcGIS Utility Network model. We are conducting a full production deployment in an 11.1 ArcGIS Enterprise cloud environment. 1898 & Co. is conducting an organization-wide stakeholder assessment and requirements gathering report, system architecture design & documentation, and a 3rd-party software impact assessment prior to initiating a data readiness assessment. Following a collaborative data model design Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
process, we will deploy the Utility Network into a staging environment and a pilot project instance. Following sufficient testing, data cleanup, application migration and dirty area resolution, the Utility Network will be migrated into production. We will also be leveraging our partner, ROK Technologies, to migrate Fairfax Waters ArcGIS Enterprise environment into an Azure managed cloud. Additionally, we will provide Fairfax Water with Change Management services and hydraulic modeling consulting services. 1898 & Co. is migrating Fairfax Water's GIS asset network into the water distribution ArcGIS Utility Network model. We conducted a full production deployment in an
11.1 ArcGIS Enterprise cloud environment. 1898 & Co. conducted a preliminary organization-wide stakeholder assessment and requirements gathering report, system architecture design & documentation, and a 3rd-party software impact assessment prior to initiating the data readiness assessment.
GIS Asset Aggregation to Maximo | Northern California Federal Laboratory Bay Area, California | Jan 2025 – July 2025
GIS Project Manager. Drew consulted with Federal stakeholders to identify disparate data sources of asset information in electric utilities and compile the information and location into Maximo. Automation was used to capture asset information from Single Line Diagrams, pdf’s, and CAD dwg files. The acquired data output was converted to Maximo format that could be consumed in DataSplice to be utilized in field verification.
HUMBOLDT COLLINSVILLE ROUTE SITING GIS | VIRIDON
Humboldt, California | Jul 2024 - ongoing
GIS Project Manager. Drew consulted with Viridon stakeholders to identify and publish GIS data layers needed for route siting analysis for a potential transmission line. Publicly available data services, subscription data sets and project specific data items were all identified and categorized in ArcGIS Online. Data submissions from internal transmission teams were consumed so the Viridon team could identify potential jurisdiction and environmental issues with route crossings. Drew also provided automated tools to calculate disturbance areas and mileage lengths within various jurisdictions for the potential transmission line. Following CAISO award of the project to Viridon, Drew has continued manging route siting updates and structure distance anlaysis for the client.
DIAR Program | SAN DIEGO GAS & ELECTRIC
La Jolla, California | 2019 - 2024
GIS Lead. Burns & McDonnell served as the program manager for the DIAR Program. The firm’s services included preparation of the program execution plan (PEP), planning and execution of drone operations, public outreach, design/engineering for necessary repairs, coordination with various departments, cost management, and oversight for various components of the program. In addition, Burns & McDonnell also provided support for various IT initiatives including the preparation of business requirements, software assessments, and implementation of tools. The development and setup of the DIAR Program occurred simultaneously with the execution of the drone operations, assessments, and design.
SDGE DCRI OTPM | SAN DIEGO GAS & ELECTRIC
San Diego, California | Jun 2018 - Apr 2023
GIS and Automation Lead. GIS Lead for the Distribution Communications Reliability Improvement (DCRI) project, which will improve telecommunications reliability, enhance wildfire protection and improve network availability, reliability and coverage by expanding the use of Falling Conductor Protection (FCP) technology. Primavera P6 schedules and infrastructure locations integrated into the OneTouchPM geospatial portal location, GIS Lead for the Distribution Communications Reliability Improvement (DCRI) project, which will improve telecommunications reliability, enhance wildfire protection and improve network availability, reliability and coverage by expanding the use of Falling Conductor Protection (FCP) technology. Primavera P6 schedules and infrastructure locations integrated into the OneTouchPM geospatial portal location
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Ben Stafford, GISP
QA/QC
Ben is a Project Delivery Director at 1898 & Co. and has 18 years of experience as Project Manager and Senior Geospatial Consultant specializing in projects related to Utility Network, geospatial database design & integrations, Cityworks/AMS configurations & implementations, design & construction program management, siting studies, and EV charging spatial analysis. Ben is responsible for defining Spatial Platform Modernization offerings, growing and managing the technical teams responsible for successful delivery, and developing technical requirements for the service offerings. He is responsible for project management tasks including scoping, budgeting, scheduling, client communications, invoicing, and project delivery. Ben has recent experience managing complex geospatial model development and implementation for utilities. He has extensively performed data collection, conversion, management and deployment of web and mobile GIS systems. He has performed tasks related to digitizing, spatial analysis, and 3D analysis. Ben also has experience in application development and requirements testing for mobile and web-based solutions. He is certified in both Esri ArcGIS and as a GIS Professional.
PROJECT EXPERIENCE
Utility Network Model Migration | Fairfax County Water
Authority | Fairfax, Virginia
Project Manager | 1898 & Co. is migrating Fairfax Waters GIS asset network into the water distribution ArcGIS Utility Network model. We conducted a full production deployment in an 11.3 ArcGIS Enterprise cloud environment. 1898 & Co. conducted an organization-wide stakeholder assessment and requirements gathering report, system architecture design & documentation, and a 3rd party software impact assessment prior to initiating a data readiness assessment. Following a collaborative data model design process, we deployed the Utility Network into a staging environment and then a pilot project instance.
Following sufficient testing, data cleanup, application migration and dirty area resolution, the Utility Network was migrated into production.
Migrated Fairfax Water’s ArcGIS Enterprise environment into an Azure managed cloud. Additionally, we will provide Fairfax Water with Change Management services and hydraulic modeling consulting services.
EDUCATION
Bachelors, Geography
CERTIFICATIONS
Certified GIS
Professional;
Esri Certification -
Desktop
EXPERIENCE
18 years of experience
-------------------------------
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
KC Water ArcGIS Utility Network Assessment & Pilot | Kansas City, Missouri | Kansas City, Missouri
Project Manager | 1898 & Co. assisted KC Water with an ArcGIS Utility Network readiness assessment and pilot project. The goal of the project was to help KC Water take the first steps toward migrating their existing Sewer, Water, and Stormwater GIS databases to the ArcGIS Utility Network. 1898 & Co. staff performed a variety of tasks to help KC Water prepare to migrate to the ArcGIS Utility Network including:
Review of the existing GIS data schema and mapping it to the Utility Network data models for wastewater and stormwater. Creation of an asset package that includes KC Water specific requirements including combined sewer asset types. Sewer data quality review using the ArcGIS Data Reviewer Data cleanup to assist with resolving sewer system type issues identified during the data quality review Third-party software integration assessment to determine the level of impact migration to the ArcGIS Utility Network would have on KC Waters Infor Public Sector CMMS, Innovyze hydraulic modeling and asset management analytics, as well as the organizations Wincan CCTV management system. A preliminary data migration from the Geometric Network to the Utility Network. The sewer database was migrated to the newly created KC Water sewer asset database.
Ben provided project Management and GIS consulting services to the KC Water Department’s initiative of converting their existing Esri Geometric Network-based combined sewer GIS to the new Esri Utility Network model. Actively engaged the client in data workshops to evaluate existing wastewater and stormwater GIS data, Hansen Asset Management System (AMS) data, and integrations with other external business systems, in order to provide strategic recommendations on how the data should be loaded to the Esri UN. Authored AM/CMMS Risk Register and documentation. Actively built out a database schema that uses Esri's Sewer UN model as a base, and incorporated elements from the Stormwater UN model to address the combined sewer infrastructure in a single cohesive model. Managed subconsultants that performed data cleanup tasks.
Established development UN and sandbox UN in client environment with GN to UN syncing configuration.
Authored a Closeout & Next Steps document recommending a path to full deployment.
ArcGIS Utility Network Readiness Assessment & Roadmap | Unified Government of Wyandotte Co. KCK | Kansas City, Kansas
Project Manager | 1898 & Co. completed an ArcGIS Utility Network Readiness Assessment & Roadmap with the Unified Government of Kansas City Kansas and Wyandotte County. During the assessment staff performed a review of the existing data schema and mapped it to the ArcGIS Utility Network data models for wastewater and stormwater. 1898 & Co. reviewed existing GIS editing extensions and outlined which tools would and would not be able to be replicated out of the box with ArcGIS Pro Attribute Rules and Dynamic Values. Staff reviewed third-party software integrations to determine the level of impact migration to the ArcGIS Utility Network would have on the third-party systems integrated with the GIS, including any schema requirements for Lucity integration. 1898 & Co. performed a pilot area data migration from the Geometric Network to the Utility Network. The pilot area was then exported and delivered to the client as an Asset Package. Ben served as project manager for an ArcGIS Utility Network Readiness Assessment & Roadmap with the Unified Government of Kansas City Kansas and Wyandotte County. During the assessment staff performed a review of the existing data schema and mapped it to the ArcGIS Utility Network data models for wastewater and stormwater. 1898 & Co. reviewed existing GIS editing extensions and outlined which tools would and would not be able to be replicated out of the box with ArcGIS Pro Attribute Rules and Dynamic Values.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Matt Seidl, PE
Process and Requirements Lead
Matt is a utility industry and engineering professional with over 20 years of experience leading change and modernizing utility technologies and processes. Matt has enjoyed leading teams for the past 17 years and has developed a great track record of providing vision and leadership as an implementer of enterprise processes and technology solutions. His broad career experience includes leading both business and IT applications teams, building Utility of the Future vision and strategy, managing the geographic information systems department, managing enterprise projects, selecting solutions, creating businesses cases, and marketing projects internally. Matt is excited to leverage the latest technologies and data to insure employees have the right information at the right time to make great decisions.
PROJECT EXPERIENCE
GUC – UTILITY NETWORK DESIGN | GREENVILLE
UTILITIES COMMISSION | Greenville, North Carolina | July 2025 - Jan 2026
Ancillary Systems & Integration Lead | Lead Discovery workshops with electric utility and natural gas stakeholders. Analyzed and documented current state business processes. Wrote current state assessment document. Assessed and documented GIS Interfaces for current and future state. Assessed and documented GUC's Esri portal components. Performed financial sensitivity analysis for program cost estimates. Collaborated with project team on deliverables.
Contributed to project deliverables * Current State Assessment - Lead and Primary Writer * Future State Assessment - Lead and Primary Writer * Implementation Roadmap - Contributor and Primary Editor
EVERGY ARCGIS UTILITY NETWORK INITIALIZATION AND
IMPLEMENTATION ROADMAP | EVERGY KANSAS CENTRAL
INC | Kansas City, Missouri | April 2025 - Nov 2025
Discovery and Requirements Workstream Lead | Discovery Lead Discovery Lead -Lead Discovery workshops with electric utility stakeholders. -Analyzed and documented current state business
EDUCATION
Masters, Agricultural
Engineering
Bachelors, Agricultural
Engineering, Soil and
Water Emphasis
CERTIFICATIONS
Professional Engineer,
Civil, State of Nevada
EXPERIENCE
20+ Years of experience
-------------------------------
LinkedIn
Matt Seidl | LinkedIn
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
processes. -Wrote current state assessment document. Requirements Lead -Lead Requirements gathering workshops with 18 electric utility stakeholder groups. -Analyzed 150 existing documents and extracted requirements. -Developed Requirements Traceability Matrix and prioritization methodology for 425 highlevel requirements. Collaborated with project team on project deliverables. * Current State Assessment - Lead and Primary Writer * High-Level Requirements Traceability Matrix - Lead and Primary Writer * Future State Architecture Analysis - Contributor and Primary Editor * Solution Validation Confirmation Presentation - Contributor and Presenter
PRIOR EXPERIENCE
Black Hills Energy
Director, Utility Technology Systems
• Led a team of 49 full-time employees supporting our GIS, field service, and work management processes and technologies with an annual budget of $12 million. • Successfully delivered a multi-year enterprise-wide Field Service. Management project serving over 1400 field and back-office employees with a budget above $20 million. Project was completed within 2% of estimate with 99.5% of requirements delivered.
• Guided our GIS teams to reduce distribution gas and electric backlogs from years down to 30 days.
BHE’s GIS team was recognized by AGA as a best practice in 2023. • Directed our $10 million annual data improvement program.
Director, Enterprise Data and Analytics
• Centralized analytics teams from across the Black Hills Energy organization. • Developed BHE’s first ED&A strategy and managed ED&A program. • Leveraged analytics tools and methodologies in support of enterprise jurisdictional simplification project.
Director, IT Business Applications
• Led a team of 70+ full-time IT employees and managed a $14 million budget supporting the majority of business applications including CIS, ERP, GIS, OMS, mobile dispatch, web, etc. • Developed support and business case for the Customer Usage data lake, BHE’s largest enterprise-grade investment in Analytics.
• Led the analysis and creation of CIS University, a strategic initiative to build continuing support for our aging customer information system.
• Developed support for our enterprise Technology Evolution strategic initiative to quantify and address gaps across our technology functions including planning and prioritization.
Utility of the Future Strategy Lead, Stretch Assignment • Developed company’s Utility of the Future strategy for transformation and modernization of operations aimed to improve of the lives of our employees and customers. • Led multi-year enterprise projects implementing the company’s first iOS mobile devices, field service management technology, enterprise-wide schedule optimization and asset management technologies.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Cristin Holmgren, UN Specialty
Utility Network Lead
Cristin Holmgren is a GIS professional well versed in spatial analysis, linear referencing, modeling, database design & database configuration.
Ms. Holmgren started her GIS career in the Oil and Gas industry where she was responsible for designing geospatial databases and implementing GIS solutions for several of the largest pipeline industry companies. She has expanded her geospatial expertise to include the energy, telecom, wastewater and water industries. Ms. Holmgren’s can analyze, organize, and process internal and external client data and has worked in renewable energy, electric transmission, water,
wastewater/stormwater, electric reconductoring, site/route selection, database design, fiber design & management, and 3D analysis projects.
She has knowledge of Esri’s Enterprise environment and the administration of the ArcGIS Online environment as well as experience in the implementation of Esri’s Utility Network Solution. She is also Esri Utility Network Specialty and Schneider Electric EcoXpert Certified.
PROJECT EXPERIENCE
Evergy Utility Network Initialization | Evergy | Topeka, Kansas | April 2025 – December 2025
UN Consultant | Cristin assisted Evergy with an ArcGIS Utility Network readiness assessment, mapping workshop, pilot and POC
implementation. The goal of the project was to help Evergy create a 90% Utility Network model to help facilitate a future migration to the UN.
She performed the following tasks to help the client prepare for migration: Review of the existing GIS data schema and leading collaborative workshops to facilitate mapping to the ArcFM Electric Distribution Utility Network model. Creation of an asset package that includes Evergy specific requirements including field additions for asset management, ADMS and other internal stakeholders. Data quality review using the ArcGIS Data Reviewer in both ArcMap and ArcPro was conducted. Conducted a preliminary data migration from the current state to the Utility Network. Deployed Utility Network to a new clientside POC environment. Cristin led the technical side of the effort in the creation, migration and POC implementation of the Utility Network developed in this project.
EDUCATION
General Studies, 2001
EXPERIENCE
24 years of experience
CERTIFICATIONS
Esri Utility Network
Specialty
Schneider Electric
EcoXpert
-------------------------------
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
First Energy Transmission Utility Network | First Energy | Akron, Ohio | July 2024 – Jan 2026
UN Consultant | Facilitated data mapping meetings with shareholders to plan for the migration of electric transmission assets to the Utility Network. Customized the OOTB Esri UN Transmission model to align with First Energy's business processes where possible and provided training on new modernized solutions for legacy workflows. Performed data migration of sample dataset to assist First Energy staff in familiarizing themselves with new model prior to go-live. Performed many iterations of whole system migrations to test and update model as needed.
Fairfax Water- Utility Network | Fairfax County Water Authority | Fairfax, Virginia | July 2023 – Jan 2025
UN Consultant | Cristin assisted Fairfax Water with an ArcGIS Utility Network readiness assessment and implementation. The goal of the project was to help Fairfax Water migrate their existing On-Prem Water Network to the ArcGIS Utility Network in the cloud. She performed the following tasks to help the client prepare for migration: Review of the existing GIS data schema and leading collaborative workshops to facilitate mapping to the Water Distribution Utility Network Foundation Solution. Creation of an asset package that includes Fairfax Water specific requirements including field additions for hydraulic modeling and other internal stakeholders. Water data quality review using the ArcGIS Data Reviewer in both ArcMap and ArcPro. Data cleanup of errors identified during the data quality review for Pilot Area. Conducted a preliminary data migration from the current state to the Utility Network. Deployed Utility Network to a new Managed Cloud Solution test environment. Cristin also led knowledge transfer training sessions for the Fairfax team on how to edit & manage the Utility Network. Cristin led the technical side of the effort in the creation, migration and implementation of the Water Utility Network developed in this project. She also created and implemented new rules to support Fairfax Water's use case. She created and updated the data dictionary. Cristin also stood up and implemented the production UN in the cloud environment.
KC Water ArcGIS Utility Network Assesment | Kansas City Missouri | Kansas City, Missouri | June 2021 - Aug 2021
GIS analyst | 1898 & Co. assisted KC Water with an ArcGIS Utility Network readiness assessment and pilot project. The goal of the project was to help KC Water take the first steps toward migrating their existing Sewer, Water, and Stormwater GIS databases to the ArcGIS Utility Network. 1898 & Co. staff performed a variety of tasks to help KC Water prepare to migrate to the ArcGIS Utility Network including: Review of the existing GIS data schema and mapping it to the Utility Network data models for wastewater and stormwater.
Creation of an asset package that includes KC Water specific requirements including combined sewer asset types. Sewer data quality review using the ArcGIS Data Reviewer. Data cleanup to assist with resolving sewer system type issues identified during the data quality review.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Darris Friend, GISP, UN Specialty
Solution Architect
Darris is a senior GIS specialist with 25 years of experience using, supporting and administering Esri’s ArcGIS Enterprise platform for the fifth largest municipal utility in Florida. He is certified by Esri as an ArcGIS Utility Network Associate. Darris was recognized by Esri as an Electric GIS Hero in 2021. He is a member of Panasonic Utility & Energy Advisory Council and volunteers on the Central Florida GIS Workshop Committee. He has presented Utility GIS related topics at TC Technology PAG, Esri GeoConX, SSP Innovations Illuminate, FMEA 2022 Hurricane Preparedness, Cityworks Innovate 2022, Esri User Conference 2023, Spatial Business Systems' PUG 2023 and the Central Florida GIS Workshop 2025. Darris harbors the ability to communicate and present complex information to technical and non-technical audiences with experience presenting to City Commissioners, Utility Advisory Board, Executives, Managers, technical staff, End Users and at GIS conferences.
PROJECT EXPERIENCE
Esri Utility Network Design Services | Greenville
Utilities Commission
Senior UN Consultant | As the technical lead for Greenville Utilities Commission’s Esri Utility Network Design initiative, Darris spearheaded the future-state design of the organization’s Electric and Gas Utility Network data models. He assessed the existing Electric and Gas GIS architecture, documenting how data flows among OMS, SCADA, CIS, and GIS. As part of the team effort, he assisted in developing a high-level roadmap with timelines, risks, impacts and key decision points such as consideration facilities design application and OMS replacements, Darris also conducted the Utility Network Data Readiness assessment for GUC’s current GIS data and transitioned each model into a pilot Utility Network environment.
Utility Network Initialization Phase | Evergy
Project team | As part of the project team supporting Evergy’s Esri Utility Network Initialization, Darris contributed to multiple phases of the project including Discovery, Requirements Gathering, Data Readiness and Future State Readiness activities and deliverables.
EDUCATION
A.S., Engineering
LICENSES/
CERTIFICATIONS
Certified GIS
Professional,
Esri ArcGIS Utility
Network Specialty
Associate 2024
EXPERIENCE
25 years of relevant
experience
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Esri Utility Network Discovery | American Transmission Company Project team | As part of the project team supporting American Transmission Company’s Esri Utility Network Discovery initiative, Darris contributed to both the current-state assessment and future-state design of the organization's GIS workflows. He helped evaluate how GIS was being used across the enterprise, identified opportunities to improve data quality and operational efficiency, and supported the development of a Utility Network implementation roadmap. Darris also assisted in strengthening data governance practices related to transmission line information managed in PLS-CADD and Esri GIS, helping ATC establish a clearer path toward a modernized and more integrated geospatial environment.
GIS Data Governance | NextEra Energy Resources
Senior GIS Consultant | As a Senior GIS Consultant, Darris supported NextEra Energy Resources in evaluating and improving the governance and use of geospatial data across key business processes and departments. He helped assess existing workflows, data practices, and outputs, contributing to recommendations that strengthened process standardization and improved the consistency and quality of geospatial information.
Darris assisted in prioritizing NEER’s internal datasets, developing organizational and process enhancements, and supporting the creation of a proof-of-concept Geospatial Project Viewer that demonstrated recommended improvements in practice. He also contributed to the development of a GIS data governance roadmap to guide NEER’s future modernization efforts.
Strategic Asset Management Advisor and Pilot | Port Of Corpus Christi Authority Project team | As part of the project team supporting the Port of Corpus Christi Authority, Darris served as a technical lead in implementing a pilot Enterprise Asset Management (EAM) system aligned with ISO 55001 and the Port’s Strategic Asset Management Plan. He configured Trimble Cityworks to reflect the Port’s defined business processes, building workflows for service requests, inspections, and work orders that capture essential equipment, labor, material, and asset condition information. Darris developed dashboards to provide insight into maintenance costs and asset condition, enabling more informed capital planning and risk management. He also documented standard operating procedures for key Cityworks user roles: office staff, field personnel, and system administrators—and provided training to support effective system adoption and ongoing use.
GIS SUPPORT | City of Alachua, FL
Project team | As part of the GIS support team for the City of Alachua, Darris provides both onsite and remote assistance to the City’s IT/GIS staff, supporting the administration of ArcGIS, map digitization efforts, and comprehensive GIS data cleanup. Serving as Technical Lead, he oversees data quality improvements, guides the upgrade of the City’s ArcGIS Enterprise environment, and leads the enhancement of the Trimble Cityworks Asset Management system. Darris also configures ArcGIS Field Maps to support the City’s as-built workflows and is developing a three-year GIS strategy roadmap to guide future modernization, system improvements, and operational alignment.
ARCFM/GIS | Beaches Energy Services
Senior GIS Specialist | As a Senior GIS Specialist supporting Beaches Energy Services, Darris serves as the technical lead for installing and configuring ArcGIS Enterprise and implementing ArcFM Mobile. His work enables key utility workflows, including the management of as-built designs produced using Spatial Business Systems’ Automated Utility Design, and supports the organization’s broader efforts to modernize and integrate its GIS and mobile field operations platforms.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Eva Shafman
GIS Data Lead
Eva is a Lead Geospatial Information System (GIS) Analyst at 1898 & Co., where she provides expert geospatial and data management solutions for large-scale utility modernization projects. She is adept at driving project success by gathering and translating complex GISspecific requirements into comprehensive design documentation and technical support. Eva is instrumental in GIS build efforts, which includes implementing ArcFM XI tools and workflows to support longterm team enablement. She also assists in quality assurance by developing and executing detailed test cases and scripts for critical system integrations supporting major utility go-lives. Throughout her roles, she utilizes her expertise in ArcGIS Pro, ArcGIS Online, and Feature Manipulation Engine (FME) to automate data processes, conduct spatial analysis, and set up field applications like ArcGIS Field Maps for real-time data management.
PROJECT EXPERIENCE
FME Support Services | California Water Services
FME support | Eva helped with the development of automated data processes using FME. She configured translations and workflows using logic and data from Application Programming Interfaces (APIs) for additional functionality and transformation of the Supervisory Control and Data Acquisition (SCADA) system.
GIS Utility Network Implementation| Evergy
GIS Design & Business Analyst | Eva serves as a key analyst on a utility network modernization and system implementation project, contributing across the full project lifecycle. She is responsible for gathering GIS-specific business requirements and executing these findings by designing comprehensive test cases and scripts for high-level system integration and quality assurance. She also supports the GIS build effort by creating workflows of the implementation of ArcFM XI tools to ensure long-term success for both fiber and electric networks.
GIS Work Order Support | Evergy
GIS Analyst | This project aims to support ageing electric distribution workorders through GIS data entry. Eva helps in reviewing as-builts and verifying that all design types and materials are correctly submitted by designers in Mas 8. She translates these jobs into an ArcFM Designer environment for a complete operational system.
EDUCATION
Bachelor of Science,
GeoDesign from University
of Southern California
EXPERIENCE
3 years of experience
-------------------------------
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
GIS Data Design Support | Arizona Public Safety (APS)
GIS Analyst | This project works to meet a compressed project timeline for electric distribution service ticket entries. Eva helps to energize certain areas through GIS service ticket entry within an ArcFM Designer environment.
Real Estate Data Management | Southern California Edison GIS support | This project analyzes various Southern California land data for transmission line siting. Eva assisted in creating layers of potential disturbance areas for the implemented structures using spatial analysis tools and automating the tabulation of road and work area disturbances.
Electric Vehicle Resiliency Study | Pacific Gas & Electric (PG&E) GIS Analysis | This comparative assessment of resiliency technology options for PG&E’s future electric fleet included a high-level GIS exercise. Eva created a GIS model of PG&E’s facilities that host fleet vehicles, analyzing the spatial relationships between them. This provided various optimal solutions for PG&E’s decision-making process.
Catalina Island Inventory | Southern California Edison (SCE) GIS support | Eva geocoded existing water service addresses in the Catalina Island area for field assessment. She helped configure the field application in ArcGIS Field Maps for inventory assessment of SCE’s services to stay in compliance with the Division of Drinking Water (DDW). She compiled all field mapping edits and photos into a geodatabase.
Angeles Hydrogen Project Data Manipulation | Southern California Gas GIS Support | Southern California Gas (SCG) is implementing what could be the nation’s largest clean, renewable hydrogen energy pipeline system. Eva has assisted with compiling and manipulating data needed to support SCG’s efforts.
Distribution Communications Reliability Improvement | San Diego Gas & Electric Support | Automation GIS Lead for the Distribution Communications Reliability Improvement (DCRI) project, which will improve telecommunications reliability, enhance wildfire protection and improve network availability by expanding the use of Galling Conductor Protection (FCP) technology. Primavera P6 schedules, infrastructure locations were integrated into the OneTouchPM™ geospatial portal location.
Transmission Engineering Department Projects | San Diego Gas & Electric GIS support | This consultation utilizes multiple spatial data and imagery in the OneTouchPM™ implementation for the transmission projects. Eva assisted in updating the geospatial view with new data and working with the client to ensure all projects and schedules were displayed correctly.
Drone Investigation, Assessment, and Repair (DIAR) Program | San Diego Gas & Electric
GIS Analyst | Our firm provided San Diego Gas & Electric Company with services to support the company's Drone Investigation, Assessment & Repair (DIAR) program, which was one of their key fire mitigation efforts.
Eva created map figures and conducted analysis on poles within the High Fire Threat Districts.
Reconductoring | Hawaiian Electric Company (HECO)
GIS support | Eva helped with updating symbology, changing domain values, and editing tools within an ArcGIS Online map for the client’s need to manipulate and visualize the next phase of distribution projects.
Data Compilation | Arizona Public Safety (APS)
GIS support | Eva worked with internal project manager to create an ArcGIS Online display of 30 datasets.
She converted data from kmz, excel, and shapefile to create and maintain the project geospatial view.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Chad Pinarija
Client Engagement Director
Chad is the Client Engagement Director at 1898 & Co. for the California region and will serve as the client liaison for this projects. His responsibilities include maintaining client relations, account management, and advising on client engagements. As the Client Engagement Director, Chad will work with the Project Manager and client leadership throughout the duration of the contract to drive client success in all aspects of the engagement. He received his degree in Managerial Economics from the University of California, Davis and brings a wealth of knowledge serving regional clients.
PROJECT EXPERIENCE
ENTERPRISE DATA STRATEGY, ROADMAP, AND
IMPLEMENTATION / PUBLIC UTILITY DISTRICT NO 1 OF
COWLITZ COUNTY
Longview, Washington / May 2023 - Current
Client Engagement Manager Establish a vision, strategy, and roadmap to better utilize data to improve current processes, solve business challenges, and create new capabilities. The project consists of initial workshops with leadership to establish vision and subsequent workshops with each business unit to understand their unique challenges and needs. Final deliverables will include a vision statement, a strategy document covering topics around
organizational approach, staffing, projects, technology considerations, prioritized user cases and a detailed roadmap outlining next steps for implementation. A As a result of this project, Cowlitz PUD now has a clear understanding of what the concept of data-driven means for their organization and how they can achieve their vision through people, process, and technology.
Upon completion of the data strategy and roadmap, we have implemented a data warehouse solution, currently managing the roadmap and backlog, and delivering use cases to enable a datadriven organization.
FME SUPPORT / CALIFORNIA WATER SERVICES COMPANY
San Jose, California / Dec 2023 - Current
Engagement Manager Providing configuration and development of Safe Software Feature Manipulation Engine (FME) translations, workflows, and documentation for Cal Water. Documentation was
EDUCATION
Bachelors, Managerial
Economics
EXPERIENCE
13 years of experience
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
provided to the client focused on specific areas where FME may need to be adjusted at later dates for Application Programming Interface (API) locations and other data transformations occurring within the automation. Following these translations being placed into production, written documents and training are provided to the client for ongoing internal maintenance of the translations.
GENERATION IT PROGRAM / SOUTHERN CALIFORNIA EDISON
Rosemead, California / June 2022 - Current
Client Engagement Manager Our team provides program and product management support to help deliver generation IT solutions in a scalable, outcomes-oriented manner to Southern California Edison (SCE). The team is working to enhance the ability to deliver projects more quickly, predictably, and considering prioritization of business value through our strategic partnership alongside the SCE team.
This program includes projects delivering integration for 500+ MW battery power across 3 plants, designing solution to support integration of multiple power sources including additional batteries in one control center, and providing support across hydro plants including control upgrades, warning systems and telecom improvements. In addition, the team is increasing the overall value to the SCE generation business unit by helping enable agile delivery concepts that support a Product Team structure that focuses on delivering business outcomes.
RATE CASE SUPPORT - PROJECT MANAGEMENT INFORMATION SYSTEMS / GOLDEN STATE
WATER COMPANY
San Dimas, California / December 2022 – May 2023
Owner’s Advisor Provided comprehensive owner's advisor support to assist in navigating and optimizing their rate case for a Project Management Information System (PMIS) implementation. Through strategic guidance, the goal is to ensure our client's rate case accurately reflects the value and benefits of procuring a PMIS. This engagement empowered the client to secure necessary funding while showcasing the system's potential to enhance project efficiency, transparency, and overall organizational success.
CAPITAL PROGRAM DELIVERY ASSESSMENT/ GOLDEN STATE WATER COMPANY San Dimas, California / March 2022 - November 2022
Project team Our team provided a comprehensive review and analysis of the clients’ approach to leading Capital Program Delivery. Analysis was performed in nine program execution steps - from budgeting, to prioritization, all the way through design, procurement, construction, and closeout.
Activities included interviews with key staff, analysis of project outcomes, design and specification review, comparison to best practices, and recommendations for improvements. We provided GSWC with over 20 different recommendations, focusing on higher capital program output, improving project delivery success, minimizing errors and rework, and allowing staff to "do more with the same".
Enterprise BI Roadmap
Port of Portland / November 2021 – January 2022
Engagement Lead | Developed a strategy to evolve their Enterprise Business Intelligence (BI) practice from a low state of maturity to an enhanced state able to leverage valuable information to make informed decisions. The project team worked with stakeholders to understand expectations then developed an architecture and supported roadmap for delivery. The roadmap included people, process and technology needs laid out on a timeline supported by a budgetary estimate.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
Brian Hiller, UN Specialty, MBA, PCCM
Senior Managing Director / GIS Solutions
Brian is the National Senior Managing Director of GIS Solutions at 1898 & Co. and has nearly two decades of experience helping electric, water and wastewater utilities leverage GIS and asset management systems.
He has led multiple Cityworks AMS, Cityworks PLL, and Cityworks Online implementations and assisted with enterprise GIS deployments including implementation of the ArcGIS Utility Network for water utilities. Brian started his career with a water and sewer utility, worked on Esri’s global water team, and he leads 1898 & Co.’s GIS business. He is Esri ArcGIS Utility Network certified, and also a Prosci Certified Change Manager.
PROJECT EXPERIENCE
Utility Network Model Migration | Fairfax County Water
Authority
Principal-in-Charge | 1898 & Co. is migrating Fairfax Waters GIS asset network into the water distribution ArcGIS Utility Network model. We are conducting a full production deployment in an 11.1 ArcGIS Enterprise cloud environment. 1898 & Co. is conducting an organizationwide stakeholder assessment and requirements gathering report, system architecture design & documentation, and a 3rd party software impact assessment prior to initiating a data readiness assessment. Following a collaborative data model design process, we will deploy the Utility Network into a staging environment and then a pilot project instance.
Following sufficient testing, data cleanup, application migration and dirty area resolution, the Utility Network will be migrated into production. Migrated Fairfax Water’s ArcGIS Enterprise environment into an Azure managed cloud. Additionally, we will provide Fairfax Water with Change Management services and hydraulic modeling consulting services.
KC Water ArcGIS Utility Network Assessment | Kansas
City, Missouri
Technical lead | 1898 & Co. assisted KC Water with an ArcGIS Utility Network readiness assessment and pilot project. The goal of the project was to help KC Water take the first steps toward migrating their existing Sewer, Water, and Stormwater GIS databases to the ArcGIS Utility Network. 1898 & Co. staff performed a variety of tasks to help
EDUCATION
Masters, Business
Administration
Bachelors, Geography
CERTIFICATIONS
Esri ArcGIS Utility
Network Specialty
Prosci Certified
Change Manager
EXPERIENCE
18 years of experience
-------------------------------
LinkedIn
Brian Hiller | LinkedIn
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
KC Water prepare to migrate to the ArcGIS Utility Network including: Review of the existing GIS data schema and mapping it to the Utility Network data models for wastewater and stormwater. Creation of an asset package that includes KC Water specific requirements including combined sewer asset types. Sewer data quality review using the ArcGIS Data Reviewer. Data cleanup to assist with resolving sewer system type issues identified during the data quality review. Third-party software integration assessment to determine the level of impact migration to the ArcGIS Utility Network would have on KC Waters Infor Public Sector CMMS, Innovyze hydraulic modeling and asset management analytics, as well as the organizations Wincan CCTV management system. A preliminary data migration from the Geometric Network to the Utility Network.
The sewer database was migrated to the newly created KC Water sewer asset database. Development of a test environment that KC Water can work with and test the ArcGIS Utility Network Setup of a toolset that synchronizes content from the Geometric Network to the Utility Network.
ArcGIS Utility Network Services | Confidential Client
Project Manager | Developed CADD to GIS automated ETL solution with FME Server to update ArcGIS Utilities datasets from CADD (.dwg,. dgn) data sources stored in Project Wise. Brian is project manager for a GIS implementation project with a large defense contractor that owns and operates hundreds of buildings on campuses throughout the United States and around the world. The project involves ArcGIS system implementation and configuration, ArcGIS Enterprise Geodatabase (SDE) design, CAD (MicroStation and AutoCAD) to GIS conversion using the Safe Software FME platform, integration with facility management data from IBM Tririga, systems integration, development of an Unmanned Aerial Vehicle (UAV) program to perform inspections using high resolution traditional imagery and thermal imagery, and an ArcGIS Utility Network pilot.
Utility Network Readiness Assessment | Omaha, Nebraska
Project Manager | 1898 & Co. conducted an ArcGIS Utility Network readiness assessment for the City of Omaha Public Works Department to evaluate organizational readiness and identify tasks required to migrate from the existing GIS environment. The effort included reviewing and mapping the current GIS data schema to Utility Network models for wastewater and stormwater, assessing third-party integrations (Cityworks and GraniteXP), evaluating existing Attribute Assistant tools against ArcGIS Pro Attribute Rules and Dynamic Values, and executing a pilot migration from the Geometric Network to the Utility Network delivered as an Asset Package. The team also established a Microsoft Azure sandbox for testing. Brian served as project manager, leading the assessment and migration planning effort.
Cityworks Implementation | City of Shreveport, LA Water & Sewerage Department GIS and Cityworks Lead| 1898 & Co. implemented Cityworks Online with the City of Shreveport Department of Water & Sewerage and the SPAR departments. The implementation supported over 250 staff from the Water and Wastewater Treatment Divisions, Field Operations (responsible for maintaining the water distribution network and the sanitary sewer collections network), customer service, and the SPAR Department (Parks and Recreation, Grounds Maintenance, Events, and Warehouse). In addition to migrating the legacy on-premises system to Cityworks Online environment, 1898 & Co. helped to optimize legacy workflows, performing data migration, and integrating Cityworks Online with SewerAI CCTV (sewer main pipe inspection software), QAlert (citizen service request application), and UMBS (the CIS/Water & Sewerage Utility billing system). 1898 & Co. team also provided GIS system updates to improve the quality of data in the GIS and user training and organizational change management support to improve the adoption of the new technology.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 48
Appendix B: Example Project Log
To support disciplined project management, transparency, and effective coordination, 1898 & Co. will utilize its standard Project Workbook, a structured, living set of project management tools maintained throughout the engagement. This workbook consolidates the project-level logs requested in the RFP and is actively used by the Project Manager to track progress, decisions, risks, and changes across all phases of the project lifecycle.
The Project Workbook is maintained as a working document and updated regularly to support status reporting, issue resolution, and decision-making.
Screenshots of the Project Workbook is included in this appendix B and the excel file is attached separately.
Action Items
The image below illustrates the Action Item Log used by 1898 & Co. to capture, assign, and track action items arising from project meetings, workshops, testing activities, and decision points. This log supports the RFP requirement for an Action Item Log and is used to maintain accountability, track ownership, and confirm timely resolution of project actions throughout the delivery lifecycle.
RFP mapping:
✔ Action Item Log
✔ Action Item Log
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 49
Change Log
The image below illustrates the Change Log used by 1898 & Co. to document scope-related changes, potential change orders, and key project decisions.
The log captures the reason for change, impact considerations, approval status, and implementation tracking, supporting the RFP requirement for a Change Order Log and Key Decision Log while maintaining a clear audit trail.
RFP mapping:
✔ Change Order Log
✔ Key Decision Log
✔ Risk Log
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 50
Deliverables Tracker and RACI Matrix
The image below illustrates the Deliverables Tracker and RACI Matrix used to define roles, responsibilities, and accountability across project activities and deliverables. This matrix supports effective governance, escalation, and coordination between 1898 & Co., the City of Roseville, and subconsultants, and aligns with the RFP’s expectations for clear project team roles and responsibilities. The Deliverables Tracker will be used to track and monitor both City of Roseville deliverables and internal 1898 & Co. project team deliverables across the project lifecycle.
RFP mapping:
✔ Project deliverable tracking
✔ Project governance and role clarity
✔ Assurance of designated project team
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 51
Submittal Log
The image below illustrates the Submittal Log used to track formal deliverables, submission dates, review cycles, feedback status, and acceptance milestones. This log supports schedule control, review management, and compliance with agreed deliverable timelines, and contributes to disciplined project execution.
RFP mapping:
✔ Project deliverable tracking
✔ Issue Log
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
PAGE 52
Schedule
The image below illustrates the Schedule Tracking tab used by 1898 & Co. to monitor task-level activities, milestone progress, and dependencies. This log supports the RFP requirement for effective project scheduling and is used to identify potential impacts to the critical path and inform schedule-related decision-making.
RFP mapping:
✔ Project schedule management
✔ Progress tracking and reporting
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
City of Roseville | 2026
Attachment G: Project Schedule
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
ID Task Name Duration Start Finish
1 Task 1: Initialization 15 days Mon 6/15/26 Fri 7/3/26 2 1.01 Kickoff Onsite 5 days Mon 6/15/26 Fri 6/19/26
3 1.02 Data Readiness Assessment 10 days Mon 6/22/26 Fri 7/3/26 4 Task 2: Design Architecture 44 days Wed 7/1/26 Mon 8/31/26 5 2.01 ArcFM XI Solution Architecture Workshop 3 days Wed 7/1/26 Fri 7/3/26 6 2.02 ArcFM XI Apps & Services - Header Only 43 days Wed 7/1/26 Fri 8/28/26 7 2.03 EXI - Apps and Services 5 days Mon 7/6/26 Fri 7/10/26 8 2.04 System Integration Overview 1 day Mon 7/13/26 Mon 7/13/26 9 2.05 Architecture Documentation and Review 6 days Tue 7/14/26 Tue 7/21/26 10 2.06 Document Approval 1 day Wed 7/22/26 Wed 7/22/26 11 2.07 ArcFM UN Data Model Workshop 3 days Thu 7/23/26 Mon 7/27/26 12 2.08 ArcFM UN Data Modeling and Review 5 days Tue 7/28/26 Mon 8/3/26 13 2.09 Document Approval 3 days Tue 8/4/26 Thu 8/6/26
14 2.10 Asset Maintenance Lifecycle Workshops - HEADER ONLY 2 days Wed 7/1/26 Thu 7/2/26 15 2.11 Business Process Review Workshop 6 days Fri 8/7/26 Fri 8/14/26 16 2.12 Business Process Documentation 12 days Thu 8/6/26 Fri 8/21/26 17 2.13 Document Approval 6 days Mon 8/24/26 Mon 8/31/26 18 Task 3: Design Requirements 88 days Tue 9/1/26 Thu 12/31/26 19 3.01 Editor XI | Asset Maintenance Lifecycle - HEADER ONLY 88 days Tue 9/1/26 Thu 12/31/26 20 3.02 GIS Editing Workflow and Tools 7 days Wed 9/2/26 Thu 9/10/26 21 3.03 GIS Editing workflow Documentation 6 days Wed 9/16/26 Wed 9/23/26 22 3.04 Document Approval 56 days Thu 9/24/26 Thu 12/10/26 23 3.05 Editor | Asset Maintenance Lifecycle 51 days Thu 10/1/26 Thu 12/10/26 24 3.06 System Integration Workshop - With GIS System 12 days Fri 12/11/26 Mon 12/28/26 25 3.07 System Integration Requirement Documentation 37 days Tue 12/29/26 Wed 2/17/27 26 3.08 Document Approval 15 days Thu 2/18/27 Wed 3/10/27 27 3.09 Configuration Workshop 15 days Thu 2/18/27 Wed 3/10/27 28 3.10 Asset Maintenance Lifecycle - EXI Configuration 5 days Thu 3/11/27 Wed 3/17/27 29 3.11 Configuration Requirement Documentation 4 days Thu 3/18/27 Tue 3/23/27 30 3.12 Document Approval 3 days Tue 12/29/26 Thu 12/31/26 31 Task 4: Pilot Area Migration and UN Testing 20 days Mon 1/4/27 Fri 1/29/27 32 4.01 Migration Scripts 10 days Mon 1/4/27 Fri 1/15/27 33 4.02 Pilot Migration 7 days Mon 1/18/27 Tue 1/26/27
34 4.03 Publish Services 3 days Wed 1/27/27 Fri 1/29/27 35 Task 5: Build 41 days Fri 1/1/27 Fri 2/26/27
36 5.01 Build ArcFM XI Development Environment (CLIENT Env) 5 days Mon 1/4/27 Fri 1/8/27 37 5.02 Configure EXI Tools 5 days Mon 1/11/27 Fri 1/15/27 38 5.03 Configure Session Manager 5 days Mon 1/18/27 Fri 1/22/27 39 5.04 Configure Geodatabase Manager 5 days Mon 1/25/27 Fri 1/29/27 May June July August SeptemberOctober NovemberDecemberJanuary February March April May June July August Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: Attachment G - Project
Date: Wed 1/14/26
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
ID Task Name Duration Start Finish
40 5.05 Custom Workflows, Tasks, AUs 10 days Mon 2/1/27 Fri 2/12/27 41 5.06 Integrations - HEADER ONLY 41 days Fri 1/1/27 Fri 2/26/27 42 5.07 Custom Integrations Build 10 days Mon 2/15/27 Fri 2/26/27 43 Task 6: Testing 45 days Mon 3/1/27 Fri 4/30/27
44 6.01 Quality assurance and Testing (Scripts and test plan) 15 days Mon 3/1/27 Fri 3/19/27 45 6.02 FAT 15 days Mon 3/22/27 Fri 4/9/27
46 6.03 SAT 15 days Mon 4/12/27 Fri 4/30/27
47 Task 7: Training 5 days Mon 4/5/27 Fri 4/9/27
48 7.01 Training 5 days Mon 4/5/27 Fri 4/9/27
49 Task 8: Go Live 36 days Mon 4/12/27 Mon 5/31/27
50 8.01 Production Migration and Configuration 15 days Mon 4/12/27 Fri 4/30/27 51 8.02 Go Live Support 21 days Mon 5/3/27 Mon 5/31/27
52 Task 9: Hypercare 44 days Tue 6/1/27 Fri 7/30/27
May June July August SeptemberOctober NovemberDecemberJanuary February March April May June July August Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: Attachment G - Project
Date: Wed 1/14/26
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
1898andco.com
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
GIS ESRI UTILITY NETWORK
DATA MIGRATION
FOR CITY OF ROSEVILLE
STATEMENT OF WORK
RFP 07-104
June 2, 2026
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
1 City of Roseville
Table of Contents
List of Tables ......................................................................................1
1.0 Scope Activities ...........................................................................2 Phase 1: Initialization ...................................................................................... 2 Phase 2: Utility Network Migration Roadmap & Master Plan........................................ 3 Phase 3: Design Requirements............................................................................ 5 Phase 4: Pilot Area Migration and UN Testing ......................................................... 5 Phase 5: Build................................................................................................ 6 Phase 6: Testing............................................................................................. 8 Phase 7: Training............................................................................................ 8 Phase 8: Full System Migration and Configuration to UN Production Environment............. 9 Phase 9: Hypercare and Continued Support ..........................................................11
2.0 Project Assumptions ................................................................... 11
3.0 Deliverable Acceptance Process ..................................................... 13
4.0 Project Schedule........................................................................ 13
5.0 Pricing and Invoicing ................................................................... 14
6.0 Document History....................................................................... 15
7.0 Appendix 1 ............................................................................... 16 List of Tables
Table 1: Tasks in Phase 1......................................................................... 2 Table 2: Deliverables Phase 1 ................................................................... 3 Table 3: Tasks in Phase 2......................................................................... 4 Table 4: Deliverables in Phase 2 ................................................................ 4 Table 5: Tasks in Phase 3......................................................................... 5 Table 6: Deliverables in Phase 3 ................................................................ 5 Table 7: Tasks in Phase 4......................................................................... 6 Table 8: Deliverables in Phase 4 ................................................................ 6 Table 9: Tasks in Phase 5......................................................................... 6 Table 10: Deliverables in Phase 5 ............................................................... 7 Table 11: Tasks in Phase 6 ....................................................................... 8 Table 12: Deliverables in Phase 6 ............................................................... 8 Table 13: Tasks in Phase 7 ....................................................................... 9 Table 14: Deliverables in Phase 7 ............................................................... 9 Table 15: Tasks in Phase 8 ....................................................................... 9 Table 16: Deliverables in Phase 8 .............................................................. 10 Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
2 City of Roseville
1.0 Scope Activities
1898 & Co. proposes to perform this statement of work using the terms and conditions agreed to in the Contract Purchase agreement herein between City of Roseville and 1898 & Co., a part of Burns & McDonnell Western Enterprises, Inc (1898 & Co.). The activities and deliverables in scope for each phase are defined herein.
RACI Matrix
To clarify City of Roseville and 1898 & Co.’s responsibilities relative to the proposed project activities, a RACI matrix has been included with the proposed tasks below. City of Roseville and 1898 & Co. will review and confirm jointly prior to the start of the engagement.
Definitions:
Key RACI Roles
Responsible (R): The organization executing the task.
Accountable (A): The organization ultimately answerable for the task's completion and quality; only one "A" per task.
Consulted (C): The organization whose experts whose opinions are sought before action.
Informed (I): The organization that is updated on progress after actions are taken COR - City of Roseville, Roseville Electric Utility
SE - Schneider Electric
Phase 1: Initialization
In this phase, 1898 & Co. will conduct a comprehensive review of COR’s existing GIS environment, electric data models, integrations, workflows, and system architecture. The phase will begin with an onsite kickoff meeting with 1898 & Co. and COR stakeholders. We will identify areas that pose risk to the migration and opportunities to work with COR stakeholders to define a clear, achievable vision for the future-state Utility Network.
Through stakeholder discovery sessions and a comprehensive review of COR’s GIS configurations, workflows, customizations, and integrations, 1898 & Co. will identify how current systems operate and where improvements can be made. Timelines when to have a dev environment created and accessible by 1898 & Co will be provided to COR. This collaboration will guide the development of a Current State and Future Vision Report, connecting COR’s organizational needs with the capabilities of the Utility Network.
Table 1: Tasks in Phase 1
Task # Task Description (Activities) 1898 COR
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
3 City of Roseville
The outcome of Phase 1 will be a comprehensive Current State Assessment report and a Future State Model summary that clearly articulates where COR is today and what foundational changes are needed to successfully transition to the Utility Network. These findings will feed directly into the Phase 2 planning and roadmap development.
Table 2: Deliverables Phase 1
Deliverable
#
Corresponding
Task
Description
1a 1.1, 1.2, 1.3,
1.4, 1.6, 1.7
Current State and Future Vision Report: Provide a detailed report document capturing COR’s existing GIS environment, key challenges, and a future-state Utility Network vision aligned with business and operational goals in MS Word (Draft) and PDF format (final) 1b 1.5 Data Readiness Report: List of the data quality issues identified and prioritized based on severity. The report will provide examples of data quality issues along with recommendations for addressing identified data quality issues. (Format: Microsoft Word document) 1c 1.5 Utility Network Dirty Area Rapid Test results in a file geodatabase Phase 2: Utility Network Migration Roadmap & Master Plan This phase focuses on transforming the findings of Phase 1 into a detailed implementation strategy. We will define implementation programs, prioritize activities and level of effort required to execute the migration to the Utility Network.
Phase 2 builds on the findings of Phase 1 and transitions the engagement from assessment into actionable planning. The objective is to define the scope, timeline, and identify resources associated with transitioning COR’s electric systems to the Esri Utility Network. This phase includes roadmap development, program definition, and stakeholder alignment around priorities, risks, and interdependencies.
& Co.
1.1 Work with COR to schedule an on-site kickoff meeting, familiarization workshop and requirements gathering
workshop
R R, A
1.2 Create information requests for COR to review and
collect documentation prior to 1898 & Co. engagement
R, A R
1.3 Review provided documentation on current state R, A C
1.4 Conduct kickoff, familiarization, and requirements
workshops and create requirements inventory
R, A R
1.5 Work with COR to design the preferred migration
strategy
R, A R
1.6 Consult on System Architecture and Integration
Assessment
R, A R
1.7 Review requirements inventory with COR stakeholders for confirmation
R, A R
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
4 City of Roseville
Table 3: Tasks in Phase 2
Task # Task Description 1898 &
Co.
COR
2.1 Conduct high-level architecture review to evaluate COR current enterprise GIS configuration along with the future needs of the ArcGIS Utility Network and ArcFM Editor XI
R, A C, I
2.2 Conduct in-depth exploration of the overall system architecture and landscape for the implementation of ArcFM Editor XI, Session Manager and GDBM XI.
R, A C, I
2.3 Capture current state requirements for the integrations for the Utility Network including: Synergi, OMS (Data Voice), Maximo (DataSplice), FME, and Attribute Assistant Add-on
R, A R
2.4 Data Model Development & Workshop - conduct an initial detailed mapping of City of Roseville’s existing Electric Geometric Network (GN) data model against the ArcFM XI
Electric Commercial-Off-The-Shelf (COTS) Utility Network data model. Engage COR in a remote, collaborative data model design workshop to validate our work and to complete the build out of the future data model with primary stakeholders
R, A R
2.5 Build Asset Package – Based on Data Modeling Workshop results and crosswalk development, we will develop a customized Asset Package (.gdb) for COR. We will also convert this into a Utility Network (.gdb).
R, A C, I
2.6 Create Migration Workflow & Tools – Configuration of migration tool using Safe Software’s FME and/or ArcGIS Data Loader Tools.
Implementing defined attribute transformations or
reclassifications to meet the Utility Network’s data integrity, classification, and connectivity standards.
R, A C, I
The result of Phase 2 will be a clear and practical roadmap that COR can use to plan for implementation planning, procurement, resource allocation, and organizational readiness. It will also help COR compare technology toolsets and workflows and set realistic expectations for execution.
Table 4: Deliverables in Phase 2
Deliverable
#
Corresponding
Task
Description
2a 2.1,2,2,2.3 System Architecture and Integration Assessment Document: Perform high level evaluation of system architecture and current integrations with third-party systems which includes Synergi, OMS (Data Voice), Maximo (DataSplice), FME, Attribute Assistant Add-on. Outline the impacts, risks, and considerations for Utility Network migration. 2b 2.4 Schema Mapping Document/Crosswalk: A detailed spreadsheet resulting from workshops, mapping COR’s GN GIS data model to the ArcFM XI Utility Network schema, including feature classes, subtypes, attributes, and domain translation Rules.
2c 2.5 Customized Utility Network (converted from an Asset Package): A schema only Utility Network (file geodatabase) tailored to COR’s electric distribution system, including configured asset groups, asset types, domains, and network Rules.
2d 2.5 HTML Data Dictionary: A web-based version of UN database design. 2e 2.5 Subnetwork Documentation Document: A plan outlining the subnetwork creation and updates aligned with COR’s operational practices.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
5 City of Roseville
Phase 3: Design Requirements
For design requirements, 1898 & Co. and Schneider Electric will hold a remote (1) day workshop that will present the workflows, prerequisites, and configuration for the successful implementation of Editor XI, Session Manager & GDBM XI.
Table 5: Tasks in Phase 3
Task # Task Description 1898 &
Co.
COR
3.1 ArcFM Editor (EXI) Editing Workflow and Tools - Conduct a remote workshop with COR for a maximum of one (1) business days to review the COTS Schneider Electric GIS application workflows for ArcFM Editor XI, GDBM XI and Session Manager.
R, A R
3.2 System Integration Workshop - Lead an integration design remote workshop of up to 40 hours with COR to define the following integrations with the GIS system.
• Synergi
• OMS (Data Voice)
• Maximo (DataSplice)
• FME
• Attribute Assistant Add-on
R, A R
3.3 ArcFM Editor XI (EXI): Configuration- Lead a one (1) business day remote workshop with COR to review the available
configurations in the ArcFM Editor applications (EXI).
R, A R
Deliverables within Phase 3 are shown in Table 6.
Table 6: Deliverables in Phase 3
Deliverable
#
Corresponding
Task
Description
3a 3.1 EXI/Session Manager/GDBM Workflow Document: A summary of workshop content and findings.
3b 3.3 EXI/Session Manager/GDBM Configuration Document: A requirements summary of workshop details.
3c 3.2 System Integration Document: A summary of workshop findings.
Phase 4: Pilot Area Migration and UN Testing
Using a system-wide data pull (.gdb) from COR, our team will execute a complete migration to the Utility Network in a test environment. We will enable network topology and publish services to confirm editing and trace capabilities. This allows early validation of assumptions and mitigates risks before system-wide rollout. It will also allow COR staff the first opportunity to interact with the Utility Network, familiarize with ArcGIS Pro processes, perform tracing, and test out integrations with the Utility Network schema and services.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
6 City of Roseville
Table 7: Tasks in Phase 4
Task # Task Description 1898 &
Co.
COR
4.1 Preliminary Data Migration: System-wide GN data will be migrated to the ArcGIS Utility Network in a file or mobile geodatabase and pasted into SDE. Using ArcGIS Pro & Portal - services will be published. This will allow for the validation of schema mapping, domain configuration, and test subnetwork creation.
R, A R, C, I
4.2 Dirty Area Identification: After migration, the Utility Network Dirty Area layer will be auto-populated and can be used to identify Rule violations and inconsistencies. These Dirty Areas represent issues where network Rules are not being met and must be corrected for accurate tracing and network validation.
R, A R, C, I
4.3 Topology and Subnetwork Testing: The pilot dataset will be used to validate network topology and test subnetwork management.
R, A R, C, I
1898 will deliver the following reports and documentation in Phase 4.
Table 8: Deliverables in Phase 4
Deliverable
#
Corresponding
Task
Description
4a 4.1, 4.2, 4.3 A Pilot Area Data Migration Report document summarizing findings and refinements to be applied to the full migration.
4b 4.2 Dirty Area classification Document observed in the pilot environment.
4c 4.3 Functional validation of trace tools, editing workflows, and web service operation.
4d 4.1, 4.2, 4.3 A refined migration and configuration approach based on observed behavior and feedback.
Phase 5: Build
During this phase, 1898 & Co. will perform the configuration and setup activities required to prepare the Esri ArcGIS Enterprise environment and ArcFM XI platform for operational use. This task transitions the project from design and planning into a functional system state that supports ArcFM editing, Utility Network operations, and GIS-side interfaces. Activities focus on configuring supported components, publishing required services and validating that the environment is ready for testing and user interaction.
Table 9: Tasks in Phase 5
Task # Task Description 1898 &
Co.
COR
5.1 ArcGIS Enterprise and Portal Configuration
1898 & Co. will work with COR to configure the ArcGIS Enterprise environment required to support ArcFM XI and the Utility Network implementation. This includes validating Portal
R, A R, C, I
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
7 City of Roseville
configuration, establishing required user roles and groups, and preparing the environment for service publication and access by ArcFM XI tools.
5.2 Publish Utility Network and Supporting Services
1898 & Co. will publish the required Utility Network and supporting feature services from the configured geodatabase to ArcGIS Enterprise. These services will be configured to support ArcFM XI editing, tracing, subnetwork management, and GIS-side integration touchpoints.
R, A R, C, I
5.3 Setup ArcFM Tenant
1898 & Co. will coordinate with Schneider Electric’s
infrastructure team and COR to establish the required ArcFM tenant(s) as part of the ArcFM XI Suite.
R, A R, C, I
5.4 Configure EXI Tools
1898 & Co. will install and configure ArcFM Editor XI (EXI) components, including Session Manager and GDBM XI, using the ArcFM Solution Center application.
R, A R, C, I
5.5 Configure Out-of-the-Box AutoUpdaters
1898 & Co. will configure supported out-of-the-box AutoUpdaters to operate within the COR’s EXI environment. These
AutoUpdaters support standard data maintenance and validation behaviors consistent with ArcFM XI and Utility Network
requirements.
R, A R, C, I
All build activities will leverage requirements, decisions, and configurations defined during prior design and workshop phases. Configuration will follow vendor-supported, out-of-the-box practices to promote system stability, maintainability, and long-term sustainability.
Specific deliverables include:
Table 10: Deliverables in Phase 5
Deliverable
#
Corresponding
Task
Description
5a 5.1 Configured ArcGIS Enterprise and Portal environment to support ArcFM XI and Utility Network operations
5b 5.2 Published Utility Network and supporting feature services with validated permissions and access
5c 5.3, 5.4 Configured ArcFM XI tenant and EXI components 5d 5.5 Validation of out-of-the-box AutoUpdaters and supported editing workflows
5e 5.4, 5.5 Environment validation results confirming readiness for testing and interface consumption
5f 5.1 – 5.5 Attribute assistant, maps, system preferences, model builder, reports and output. Full listing of additional configurations are located in Appendix 1.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
8 City of Roseville
Phase 6: Testing
Testing of the ArcFM Utility Network model will be performed by creating a test plan that includes a variety of scenarios that COR performs today. This involves test cases for data validation, editing, and tracing. ArcFM Editor XI testing will focus on the functionality of the editing tools, confirming that they are working as expected and that they are properly interacting with the utility network model. This testing includes scenarios for creating, editing, and deleting features, as well as testing the undo and redo functionality.
Table 11: Tasks in Phase 6
Task # Task Description 1898 &
Co.
COR
6.1 EXI: Factory Acceptance Testing (FAT)
Confirms the GIS editing solution meets all utility-specific requirements before it is deployed into the production
environment. This process involves simulating the entire operational workflow, from data editing and validation to network analysis, to identify and resolve any issues before the system goes live.
R, A C, I
6.2 EXI: Site/User Acceptance Testing (SIT/UAT)
Testing is performed by the end-users of the software to validate that it meets their business requirements in a real-world context. This phase involves users executing their daily editing and data management workflows, such as creating and updating features, Running validation Rules, and performing network traces, to confirm the system functions as expected before it is approved for release into the production environment.
R R, A
1898 & Co. will provide the following deliverable as part of the testing phase in phase 6.
Table 12: Deliverables in Phase 6
Deliverable
#
Corresponding
Task
Description
6a 6.1, 6.2 Documentation of testing results, bug tracking and fixes for each round of testing listed above.
Phase 7: Training
Our team will deliver end-user and admin training, tailored documentation, editing guides, and subnetwork updating workflows. We will also provide post-go-live stabilization support, enabling a confident transition.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
9 City of Roseville
Table 13: Tasks in Phase 7
Task # Task Description 1898 &
Co.
COR
7.1 Tailored Training Sessions - 1898 & Co. will lead hands-on, rolebased training for system administrators, GIS editors, power users, and other identified stakeholders. Training will be purpose-built for COR and aligned with actual workflows, operational priorities, and Utility Network responsibilities rather than generic product instruction. A comprehensive Training Plan will be developed early in the project in partnership with COR and will define training options, delivery approach, staffing expectations, class size and skill level by audience, training materials, and the functional responsibilities addressed in each session to prepare users for their day-to-day tasks within the Utility Network environment
R, A R
7.2 Custom Documentation - We will develop comprehensive user and administrative guides, including editing instructions, subnetwork management practices, and trace configuration documentation. These materials will serve as long-term
references for staff and support future onboarding efforts.
R, A C, I
7.3 Configuration Tools and Editing Support - As part of the go-live preparation, we will deliver tools and best practices to manage trace Rules, maintain network topology, and troubleshoot common issues in real-time. This includes guidance on editing workflows, versioning, and maintaining system health.
R, A C, I
Deliverables from the Training phase include:
Table 14: Deliverables in Phase 7
Deliverable
#
Corresponding
Task
Description
7a 7.1 Training Plan, Training sessions, and user onboarding 7b 7.2, 7.3 Complete set of tailored documentation and configuration guides
Phase 8: Full System Migration and Configuration to UN Production Environment With lessons learned from the pilot, we will execute the full migration of COR’s electric network, publish Utility Network services and web maps and test third-party system touchpoints. This phase represents the transition from isolated testing to enterprise deployment, with a strong focus on configuration accuracy, system integrity, and cross-platform integration, as determined by COR.
Table 15: Tasks in Phase 8
Task # Task Description 1898 &
Co.
COR
8.1 Comprehensive Data Migration – All relevant electric distribution system data will be migrated from the Geometric Network into the Utility Network using the finalized schema asset package
R, A R, C, I
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
10 City of Roseville
developed earlier in the project with COR. Migration processes will follow the tested methodology proven during the pilot.
These migration efforts only include data directly participating in the Utility Network itself.
8.2 Utility Network Services Configuration – Core Utility Network services will be published, allowing for network validation, subnetwork management, network topology, and tracing.
R, A R
8.3 Validation and Testing – The Utility Network implementation will undergo full-scale testing for performance, accuracy, and usability. Dirty Area layers, trace operations, editing capabilities, and security settings will be reviewed to confirm system readiness.
R, A R
8.4 Configure Production ArcFM Tenant and tools – This effort assumes existing configuration from the test environment will be transferred over to production.
R, A R
8.5 Cutover Planning and Execution - Working closely with COR’s team, we will execute the final cutover to the production Utility Network environment based on an agreed-upon schedule. This includes final data loads, service validation, and system readiness checks.
R, A R
8.6 Post-Cutover Stabilization – Following cutover, 1898 & Co. will remain engaged for a 60-day stabilization period. During this time, our team will assist with issue resolution, performance monitoring, and any final adjustments needed to optimize dayto-day operations in the new environment.
R, A C, I
Items that will be provided within phase 8 deliverables include:
Table 16: Deliverables in Phase 8
Deliverable
#
Corresponding
Task
Description
8a 8.1 A fully migrated and configured Utility Network for COR’s electric distribution system. Migration will be conducted via Screenshare such as Teams.
8b 8.2, 8.3, 8.4 Final documentation of the migration process, configuration settings, and system architecture
8c 8.5 Final system cutover and production launch
8d 8.6 Post-go-live support to reinforce adoption and address emerging needs
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
11 City of Roseville
Phase 9: Hypercare and Continued Support
Following production cutover, 1898 & Co. will provide a structured 60-day hypercare period to support COR as the Utility Network and ArcFM XI environment transitions into day-to-day operations. Following the 60-day hypercare period, 1898 & Co. will provide and additional 305 days (approximately 10 months) of extended support, consisting of 164 total hours, or roughly 4 hours per week. This support could include areas such as integration product changes or incorrectly configured from the implementation. The project manager will notify COR when 1898 & Co. has utilized 80% of the budgeted hours allocated for extended support. Total support coverage will extend up to 365 days to provide a full year of coverage, or until the 164 hours for extended support have been exhausted, whichever occurs first.
2.0 Project Assumptions
This Statement of Work (SOW) has been developed in accordance with the project assumptions below. • Pricing Structure and Billing This proposal is submitted on a fixed-price, milestone-based basis. The fixed fee includes professional services and travel associated with two onsite visits for Project Kickoff and Training, with hypercare and extended support billed at initiation of support periods. • Onsite Commitment The proposed scope includes two onsite visits to the COR with an average of three 1898 & Co. team members per visit. COR will provide reasonable onsite support, including meeting space and IT connectivity as needed.
• ArcFM XI and Utility Network Implementation Approach The implementation will use the ArcFM Electric Utility Network Commercial-Off-The-Shelf model, out-of-the-box AutoUpdaters, and supported ArcFM XI workflows. Custom ArcFM development, custom AutoUpdaters, ADMS feeder service modification, and Conduit Manager configuration are excluded unless explicitly stated. • Licensing, Infrastructure, and System Access COR will provide required Esri and Schneider Electric licenses, infrastructure, environments, and system access necessary to support ArcGIS Enterprise, Utility Network, and ArcFM XI activities.
• Utility Network and Platform Version Alignment Target versions for ArcGIS Enterprise, ArcGIS Pro, Utility Network, ArcFM XI, and supporting platforms will align with vendor-supported versions mutually agreed at project initiation. Our standard approach and working assumption is to leverage a Network Management Release version (the latest being ArcGIS Enterprise 11.5 and ArcGIS Pro 3.5).
Version changes after design approval may affect scope, schedule, or fees. • Integrations and Third-Party Systems Integrations are coordinated and validated on the GIS side only, and third-party systems remain City and vendor owned. Configuration or modification of thirdparty systems, middleware, or vendor-managed integrations is excluded unless explicitly defined. • Third-Party Vendor Responsibility 1898 & Co. does not assume responsibility for inherent defects, limitations, or behavior of third-party software platforms. Vendor product issues, platform changes, or legacy system behavior are excluded from scope.
• Data Access, Quality, and Remediation COR will provide timely access to GIS data and documentation required for assessment and migration activities. Data quality issues unrelated to conversion or migration, including legacy data not previously cleansed, are excluded unless otherwise agreed.
• Data Remediation Responsibility Resolution of Severity 1 data issues identified during the Data Readiness Assessment is assumed to be performed by the COR in a timely manner that aligns with Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
12 City of Roseville
1898 & Co.’s project plan. Assistance from 1898 & Co. beyond assessment and guidance may be provided through a separately negotiated change.
• Stakeholder Participation and Scheduling The scope assumes participation in approximately five to ten cross-functional stakeholder workshops over a two-week period. Delays in stakeholder availability or scheduling may impact the project timeline. • City Coordination and Decision-Making COR will designate a primary project contact to support coordination, scheduling, and decision-making. Timely review and approval of deliverables are required to maintain the proposed schedule.
• Feedback and Review Timelines Deliverable reviews are assumed to occur within five business days unless otherwise agreed. Additional review cycles or expanded feedback beyond scope may require schedule or fee adjustments.
• Testing Scope and Acceptance Testing is limited to validation of Utility Network migration, ArcFM XI configuration, and GIS-side services described in this proposal. Final system acceptance is performed by the COR with support from 1898 & Co.
• Change in Business Processes or Requirements Core business processes and requirements identified during design are assumed to remain materially consistent. Significant changes to workflows, asset modeling, or operational requirements may impact scope, schedule, and fees. • Regulatory, Security, or Policy Changes to regulatory requirements, cybersecurity standards, or City security policies occurring after project initiation that materially affect system design may require scope or schedule adjustments.
• Out-of-Scope Changes Requests for additional services; extended support beyond hypercare and the 305-day support extension, expanded integration responsibilities, or evaluations beyond those described require a written amendment and may impact fees and schedule.
Travel & Meetings
• Two onsite trips are included, one during the project kickoff and one during the training. • Additional travel, if requested by COR, will be handled through a change order. • Remaining workshops and meetings will be conducted remotely via Microsoft Teams or a COR-approved platform.
Optional Architecture Design Assumptions
• COR currently operates in a high-availability, on-premises environment using SQL Server. • COR is open to cloud-hosted and hybrid solutions. Recommendations will reflect COR’s existing infrastructure, cost sensitivity, and security requirements. • One remote workshop will be held to gather IT input and inform system architecture.
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
13 City of Roseville
3.0 Deliverable Acceptance Process
All deliverables listed in this proposal will be the responsibility of 1898 & Co. Each deliverable will undergo the following review steps. Where necessary, additional activities may be required for certain document deliverables as agreed upon by both COR and 1898 & Co. All deliverables, reviews, issues, and sign-off shall be provided electronically.
• Submission: Upon completion of a deliverable, 1898 & Co. will submit the deliverable to the COR Project Manager.
• Review: The COR Project Manager will be responsible for distributing the draft deliverable to the appropriate COR team members for review. The standard review period will be five (5) business days, or a duration mutually agreed upon, in writing, by the COR Project Manager and 1898 & Co. If after this period there are no unresolved open issues, the deliverable will be sent to the COR Project Manager for final acceptance and sign-off.
• Rework and Review: If COR has open issue(s) on a draft deliverable, 1898 & Co. and COR will collaboratively review the open issues, incorporate address, and close all such open issues. The collaborative review process shall be completed within ten (10) business days, or a duration mutually agreed upon, in writing, by the COR Project Manager and 1898 & Co. to minimize impact on the project schedule. Upon 1898 & Co.’s submission of the Revised Deliverable, COR’s five business day review period identified above will re-commence. After the ten (10) business days, or the agreedupon period, and provided COR and 1898 & Co. have reached a mutually agreeable resolution, the deliverable will move to formal acceptance and sign-off. If the 1898 & Co. project lead and the COR Officer are unable to come to a resolution on a deliverable, the item may by escalated for issue resolution to the 1898 & Co. executive sponsor and the COR steering committee or executive sponsor, or those COR members of the steering committee that have specific knowledge and information regarding the deliverable at issue and will follow the Escalation Process defined in this Statement of Work.
4.0 Project Schedule
1898 & Co. anticipates completion of the scope of work and will provide the go-live deliverables outlined prior to December 31, 2027. 1898 & Co. and COR will develop together a structured project plan in Phase 1 of this scope of work and anticipates an approximately 12-month project timeline from project kickoff to go-live and additional 12-months for hypercare and extended support.
An initial outline is listed below and is constructed with August 2026 being when the project initializes:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Task Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Task 1 - Initialization
Task 2 - Design Architecture
Task 3 - Design Requirements
Task 4 - Pilot Area Migration and UN Testing
Task 5 - Build
Task 6 - Testing
Task 7 - Training
Task 8 - Go Live
Task 9 - Hypercare
Monthly Extended Support
2026 2027 2027 Quarter 4 2028 Quarter 1 2028 Quarter 2
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
14 City of Roseville
5.0 Pricing and Invoicing
COR will compensate 1898 & Co. the fixed fee of $985,000 for the services described in this SOW. The fixed fee includes the scope described herein and travel expenses. Optional tasks may be added at COR’s discretion. 1898 & Co. will deliver the Utility Network Design Services engagement in structured phases with clear milestones tied to tangible deliverables. Each milestone will be invoiced in accordance with the Milestone Payment Schedule Table below.
Milestone Payment Schedule Table
Milestone Milestone Name (Phase) Description Billing Trigger Fee ($) 1 Project Kickoff (Phase 1
– Initialization)
Onsite project kickoff meeting Delivery of
Project Kickoff
Meeting
$50,000
2 Data Readiness and
Migration Planning
(Phase 1 - Initialization)
Data Readiness Assessment, Rapid Test
migration results, severity classification, and
delivery of Data Readiness Report
Delivery of data
readiness
deliverables
$90,000
3 Architecture and Data
Model Design (Phase 2 –
Utility Network Migration
Roadmap & Master Plan)
Completion of system and ArcFM XI
architecture review, integration assessment,
schema mapping, asset package design, and
delivery of associated documentation
Delivery of Phase
2 deliverables
$175,000
4 ArcFM XI Design and
Integration Definition
(Phase 3 – Design
Requirements)
Completion of ArcFM XI workflow workshops,
integration design workshops, and delivery
of EXI, Session Manager, GDBM, and
integration documentation
Delivery of Phase
3 deliverables
$180,000
5 Pilot Migration and
Validation (Phase 4 –
Pilot Area Migration and
UN Testing)
Completion of pilot migration, topology and
subnetwork validation, Dirty Area analysis,
and Pilot Migration Report
Delivery of pilot
migration results
$100,000
6 Platform Build and
Service Enablement
(Phase 5 – Build)
Configuration of ArcGIS Enterprise and
Portal environment, publication of Utility
Network and supporting services, ArcFM
tenant setup, EXI, Session Manager, and
GDBM configuration, and environment
readiness confirmation for testing and
interfaces
Delivery of Phase
5 deliverables
$100,000
7 Testing and User
Acceptance (Phase 6 –
Testing)
Completion of Factory Acceptance Testing
and Site/User Acceptance Testing
Delivery of
testing results
$100,000
8 Training and Production
Migration (Phase 7 -
Training, Phase 8 – Full
System Migration and
Configuration to UN
Production Environment)
Completion of training delivery,
documentation, full system migration to
production Utility Network, service
publication, and system cutover
Acceptance of
production
migration
$100,000
9 Hypercare Initiation
(Phase 9 – Hypercare
and Continued Support)
60-day post–go-live hypercare support Commencement
of hypercare
period
$40,000
10 Extended Support
Initiation (Phase 9 –
Hypercare and
Continued Support)
305-day extended support Commencement
of extended
support period
$50,000
Total $985,000
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
15 City of Roseville
6.0 Document History
Version: Date: Author(s): Lead Reviewer: Approved by: Reason for Revision
1.0 05/08/2026 Drew Haney Matt Seidl Chad Pinarija Initial Draft of SOW
2.0 05/18/2026 Drew Haney Chad Pinarija Chad Pinarija Comments from COR
3.0 06/02/2026 Steve Hancock Drew Haney Drew Haney Adjustment to 1.0 verbiage “contract Purchase Agreement” and change of
“RASCI” to “RACI”
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
16 City of Roseville
7.0 Appendix 1
List of additional configurations for Phase 5 – Build.
GIS Application:
• Attribute Assistant Add-on
• ArcFM
• ArcPro
Maps:
• Symbology shall match current state system.
• Define attribute rules
• Facilities Request MXD Template
• ArcFM Stored Displays:
• Composite
o PRINT – Distribution
o PRINT – Streetlights
o PRINT – Fiber
o PRINT – 60kV
o Feeder Info
o Phase Audit
System Preferences:
• Res 2 Phase Transformers
• Com 3 Phase Transformers
• DF9B
• DF11B
• DF10
• VF15
• DF3W
• DF4W
• 30 Box with 2 Services
• 36 Box with 2 Services
ModelBuilder:
• Assigns address and ADDRID to Service Location FC
• ModelBuilder FindSvcLocAddress.pdf
Reports and Outputs:
• ArcFM Map Book Explorer
o PRINT – Distribution
o PRINT – Streetlights
o PRINT – Fiber
o PRINT – 60kV
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
1898andco.com
Docusign Envelope ID: ECD7075E-7800-8F2D-809F-AB017A9D5749
PROPOSAL FOR
GIS ESRI UTILITY NETWORK
DATA MIGRATION
RFP 07-104
SUBMITTED TO
CITY OF ROSEVILLE
January 14, 2026
2 January 14, 2026
Steve Hancock | Senior Electric Business Analyst
City of Roseville – Roseville Electric Utility
2090 Hilltop Circle | Roseville, CA 95747
Re: GIS ESRI Utility Network Data Migration | RFP 07-104 Dear Mr. Hancock,
1898 & Co., a part of Burns & McDonnell Western Enterprises Inc., is pleased to submit this proposal to support the City of Roseville in its migration from the Esri ArcGIS 10.8.1 Geometric Network to the ArcGIS Utility Network, alongside the modernization and upgrade of its Schneider Electric ArcFM solution. This initiative is a transformative opportunity for Roseville Electric Utility to strengthen operational efficiency, improve network modeling accuracy, expand enterprise integrations, and support next-generation workflows across engineering, operations, and field teams.
As a consulting practice built within one of the nation’s leading engineering firms, 1898 & Co. brings a combination of deep utility operations knowledge, modern geospatial experience, and hands-on ArcFM XI and Utility Network implementation experience. Our team has delivered successful UN migrations for electric distribution & transmission, water, gas, and fiber systems across public power, IOUs, and municipal utilities nationwide. We understand the business-critical nature of electric network data and how GIS enables planning, outage response, asset management, customer service, and compliance.
What differentiates 1898 & Co. is our ability to serve as a strategic partner throughout the delivery lifecycle, we are more than just a technical implementer. We work closely with clients to confirm their Utility Network transition aligns with operational requirements, long-term modernization goals, system integrations, and staff readiness. Our approach emphasizes strong communication, transparency, knowledge transfer, and a well-managed transition that protects business continuity.
This proposal outlines a fixed-price scope that covers all required tasks outlined in the RFP and provides the City of Roseville cost certainty. We welcome the opportunity to serve as your trusted partner on this transformational journey and look forward to the next steps in support of your vision for a modern, connected utility GIS. 1898 & Co. understands the requirements of this Request for Proposals and commits to performing the services in accordance with the requirements described in RFP No. 07-104, including the Question and Answer (Q&A) issued by the City of Roseville. If you have any questions about our proposal, please contact Chad Pinarija at [email protected] or 1-949-293-1584.
Sincerely,
Chad Pinarija
Director, Technology Consulting
Stephen Kane
Vice President
2175 N. California Blvd. #400
Walnut Creek, CA 94596
Attachment A
PROPOSER’S CERTIFICATION
I hereby propose to furnish the goods or services specified in the Request for Proposals (“RFP”). I agree that my proposal will remain firm for a period of up to ninety (90) days in order to allow the City of Roseville (“City”) adequate time to evaluate the qualifications submitted.
I have carefully examined the Request for Proposals and any other documents accompanying or made a part of this RFP. The information contained in this proposal is true and correct to the best of my knowledge and is signed under penalty of perjury under the laws of the State of California. I further certify that I am duly authorized to submit this proposal on behalf of the firm as its authorized agent and that the firm is ready, willing and able to perform if awarded the contract.
I further certify that this proposal is made without prior understanding, agreement, connection, discussion, or conspiracy with any other person, firm or corporation submitting a proposal for the same product or service; that this proposal is fair and made without outside control, collusion, fraud or illegal action; that no officer, employee or agent of the City or any other proposer is financially interested in said proposal; that no undue influence or pressure was used against or in concert with any officer, employee or agent of the City in connection with the award or terms of the contract that will be executed as a result of this RFP; and that the undersigned executed this Proposer’s Certification with full knowledge and understanding of the matters therein contained and was duly authorized to do so.
_________________________________________________
NAME OF BUSINESS
_________________________________________________
SIGNATURE
_________________________________________________
NAME & TITLE, TYPED OR PRINTED
_________________________________________________
MAILING ADDRESS
_ _____________________________________
TELEPHONE NUMBER
_________________________________________________
EMAIL
Type of Organization:
____ Sole Proprietorship ____ Corporation ____ State of Incorporation ________ Partnership ____Limited Liability Company
Burns & McDonnell Western Enterprises, Inc.
Stephen Kane, Vice President
145 S. State College Blvd., Suite 600, Brea, CA 92821
+
__
1 (7
___
14 ___
) 264-7333
___
[email protected]
City of Roseville | 2025
PAGE 3
Contents
Tab A: Firm Qualifications .............................................................. 4 Tab B: Experience and References .................................................. 11 Tab C: Qualifications of Team ........................................................ 17 Tab D: Project Understanding ........................................................ 21 Tab E: Project and Implementation Overview .................................... 28 Tab F: Cost Proposal.................................................................... 42 Tab G: Required Statements/Documents........................................... 44 Tab H: Exceptions ....................................................................... 45 Tab I: Competency of Proposers ..................................................... 46 Appendix A: Resumes .................................................................. 47 Appendix B: Example Project Log ................................................... 48 Additional Attachments:
Attachment G - Gantt Chart
Project Workbook Example
City of Roseville | 2026
PAGE 4
Tab A: Firm Qualifications
Corporate Structure & Services
Burns & McDonnell is a family of privately held companies, each providing services based upon supporting a client’s particular needs. We provide a full suite of architecture, engineering, construction and consulting services across all industries, including Water, Power, Telecommunications, Environmental, Transportation, Construction, Governmental, Military &
Municipal, Aviation, Commercial, Retail & Institutional, Manufacturing & Industrial, and Oil, Gas & Chemical. We can provide additional information regarding corporate structure, including international services, upon contract award.
Industry rankings provided by Engineering News-Record (ENR). Click here for the full list of Burns & McDonnell rankings.
About 1898 & Co.
1898 & Co., a part of Burns & McDonnell, is a global business, technology and security consulting firm that serves critical infrastructure industries. As an extension of your team, we plan, secure and optimize your asset-intensive organization, leveraging our trusted advisers with proven track records to uncover and deliver straightforward, actionable insights that can transform your business.
Our firm has been helping organizations engineer and construct electric infrastructure since 1898. By combining our experience working in the electric industry with our business-aligned approach to technology adoption, we apply enterprise system planning, implementation, and customization capabilities to help utility clients maximize their return on investment in people, processes, and technologies. 100%
employee-owned
Backed by
15K+
professionals at
Burns & McDonnell
24 Years as Esri Business
Partner