PLASTICITY
D110 of 179
LIQUID

PLASTICITY
LIMIT, %
CONTENT, %
% PASSING
LOG OF TEST HOLE NO. T-9
140
PLATE A-10
ALLUVIUM (Qa1)
Poorly-graded SAND (SP): loose, light brown, moist, little to some rounded fine to coarse gravel, trace silt
148
146
144
142
140
138
136
#200 SIEVE
INDEX, %
Qa3
Qa2
Qa1
Disturbed Soils
TD = 8.0 ft
ALLUVIUM (Qa3)
Silty Fine SAND (SM): loose to medium dense, gray to
black, moist, trace Hydrogen Sulfide odor

UNIT WET
WEIGHT, pcf
1 WATER
ALLUVIUM (Qa2)
Fat CLAY (CH): stiff to very stiff, reddish brown, moist Disturbed Soils
Clayey SAND (SC): light brown to greenish brown, moist to wet
4 SAMPLE NO.
2 4
6 8
10 12
14 COMPLETION DEPTH: 8.0 ft
102
ELEVATION, +/- MSL
ELEVATION, ft

MATERIAL DESCRIPTION

UNIT DRY
WEIGHT, pcf

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. T-9
SURFACE EL: 150.0 ft +/- (rel. datum)
LOCATION: West Side of Perc Pond No. 1
EXCAVATION DATE: June 2, 2008
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

Project No. 3019.008
106
142
144
146
148
150
City of Santa Maria
TEST PIT LOG WITH LAB SUMS VENTURA F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\3019.008.GPJ 6/30/08 12:25 p Percolation Pond No. 1
Santa Maria Wastewater Treatment Facility, Santa Maria, California SAMPLES 2 DEPTH TO WATER: Not Encountered SYMBOL MATERIAL
6 SAMPLER
4 UNDRAINED
SHEAR
STRENGTH,Su, ksf

BLOWCOUNT
CONTRACTOR: City of Santa Maria
EXCAVATION METHOD: Backhoe
CHECKED BY: J Blanchard
LOGGED BY: GD Eckrich
DEPTH, ft
0 8
DEPTH, ft
10 D111 of 179
DEPTH TO WATER: 4.0 ft
DEPTH, ft
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. T-10
SURFACE EL: 148.0 ft +/- (rel. datum)
LOCATION: West Side of Perc Pond No. 1
10 % PASSING
146
144
142
140
138
136
134
LOG OF TEST HOLE NO. T-10
#200 SIEVE
LIMIT, %
LOGGED BY: GD Eckrich
CONTENT, %

PLASTICITY

SAMPLER
8 6
4 2
0 DEPTH, ft
SYMBOL
EXCAVATION DATE: June 2, 2008 SAMPLES

UNDRAINED
SHEAR
STRENGTH,Su, ksf

BLOWCOUNT
CONTRACTOR: City of Santa Maria
EXCAVATION METHOD: Backhoe
CHECKED BY: J Blanchard

MATERIAL
COMPLETION DEPTH: 6.0 ft ELEVATION, +/- MSL

MATERIAL DESCRIPTION

UNIT DRY
WEIGHT, pcf
WATER
1 ELEVATION, ft
Disturbed Soils
PLATE A-11

UNIT WET
WEIGHT, pcf
LIQUID
2 4
6 8
10 12
14 SAMPLE NO.

ALLUVIUM (Qa3)
Silty SAND (SM): dark gray to black, moist, Hydrogen
Sulfide odor
Disturbed Soils
Clayey SAND (SC): light brown to greenish brown, moist
SAND with silt (SP-SM): medium dense, reddish brown,
moist
ALLUVIUM (Qa1)
Poorly-graded SAND with gravel (SP): loose, gray to black, moist to wet, water perched at base of unit, rounded
gravel, Hydrogen Sulfide odor
ALLUVIUM (Qa2)
Fat CLAY (CH): stiff to very stiff, reddish brown, moist, fissured
INDEX, %
144
Qa3
Qa2
Qa1
Disturbed Soils
138
142
146
148
Percolation Pond No. 1
Santa Maria Wastewater Treatment Facility, Santa Maria, California City of Santa Maria
Project No. 3019.008
TEST PIT LOG WITH LAB SUMS VENTURA F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\3019.008.GPJ 6/30/08 12:25 p 140
TD = 6.0 ft
1 D112 of 179

MATERIAL
8 6
4 2
0 EXCAVATION METHOD: Backhoe
DEPTH, ft
SYMBOL

SAMPLES

SAMPLER

UNDRAINED
SHEAR
STRENGTH,Su, ksf

BLOWCOUNT
LIMIT, %
10 DEPTH, ft
CHECKED BY: J Blanchard
SAMPLE NO.
2 4
6 8
10 12
14 COMPLETION DEPTH: 6.0 ft
CONTRACTOR: City of Santa Maria

UNIT WET
WEIGHT, pcf
ELEVATION, +/- MSL
ELEVATION, ft
#200 SIEVE
LOGGED BY: GD Eckrich
EXCAVATION DATE: June 2, 2008
INDEX, %
LOG OF TEST HOLE NO. T-11
LIQUID

PLASTICITY
PLATE A-12
146
144
142
140
138
136
134
1 UNIT DRY
WEIGHT, pcf
WATER
146
ALLUVIUM (Qa3)
SAND with silt (SP-SM): medium dense, gray to black,
moist
ALLUVIUM (Qa2)
Fat CLAY (CH): stiff to very stiff, reddish brown, moist, fissured, occasional white chert clasts
CONTENT, %
% PASSING

MATERIAL DESCRIPTION
148
138
140
142
144
Disturbed Soils
Sandy SILT (ML): stiff, greenish brown, moist to wet, water perched at base of unit
TD = 6.0 ft
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. T-11
SURFACE EL: 148.0 ft +/- (rel. datum)
LOCATION: West Side of Perc Pond No. 1
DEPTH TO WATER: 4.0 ft
Project No. 3019.008
Qa3
Qa2
Disturbed Soils
City of Santa Maria
TEST PIT LOG WITH LAB SUMS VENTURA F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\3019.008.GPJ 6/30/08 12:25 p Percolation Pond No. 1
Santa Maria Wastewater Treatment Facility, Santa Maria, California D113 of 179
TD = 9.0 ft
TEST PIT LOG WITH LAB SUMS VENTURA F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\3019.008.GPJ 6/30/08 12:25 p LOG OF TEST PIT NO. T-12
SURFACE EL: 151.0 ft +/- (rel. datum)
LOCATION: Middle of Perc Pond No. 1
DEPTH TO WATER: 3.5 ft
145
Qa2
Qa1
Disturbed Soils
143
147
149
151
Percolation Pond No. 1
Santa Maria Wastewater Treatment Facility, Santa Maria, California City of Santa Maria
Project No. 3019.008
141
Disturbed Soils
Silty SAND (SM): medium dense, light brown to greenish
brown, moist
Lean CLAY (CL): soft, grayish brown, moist
WATER
ALLUVIUM (Qa3)
Poorly-graded SAND with silt (SP-SM): medium dense to
dense, yellowish brown, wet
ALLUVIUM (Qa1)
Poorly-graded SAND with silt and gravel (SP-SM): gray to light brown, wet, water perched at base of unit, rounded gravel
Qa3
ALLUVIUM (Qa2)
Fat CLAY (CH): very stiff to hard, reddish brown, moist, fissured, oxidation mottling
ELEVATION, +/- MSL
ELEVATION, ft

MATERIAL DESCRIPTION

UNIT DRY
WEIGHT, pcf
DEPTH, ft
8 6
4 2
0 CHECKED BY: J Blanchard

MATERIAL

SAMPLES

SAMPLER

UNDRAINED
SHEAR
STRENGTH,Su, ksf
Qa2
CONTRACTOR: City of Santa Maria
SYMBOL
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT GRAPHICAL REPRESENTATION
10 DEPTH, ft
EXCAVATION METHOD: Backhoe INDEX, %
LOGGED BY: GD Eckrich

BLOWCOUNT
PLATE A-13 LIQUID
SAMPLE NO.
2 4
6 8
10 12
14 COMPLETION DEPTH: 9.0 ft

UNIT WET
WEIGHT, pcf
LOG OF TEST HOLE NO. T-12
EXCAVATION DATE: June 2, 2008
150
148
146
144
142
140
138
#200 SIEVE

PLASTICITY
LIMIT, %
CONTENT, %
% PASSING
D114 of 179
TD = 9.0 ft
LOGGED BY: GD Eckrich
PLATE A-14
WATER
5 PLASTICITY
EXCAVATION DATE: June 2, 2008
Qa1
150
148
146
144
142
140
138
#200 SIEVE
1 LIMIT, %
CONTENT, %
% PASSING
LOG OF TEST HOLE NO. T-13
ELEVATION, +/- MSL
ELEVATION, ft

MATERIAL DESCRIPTION

UNIT DRY
WEIGHT, pcf
Disturbed Soils
Silty SAND (SM): medium dense, light brown to greenish
brown, moist
ALLUVIUM (Qa1)
Poorly-graded SAND with silt and gravel (SP-SM): medium dense, black to gray to light brown, moist to wet, water perched at base of unit, lenses of clean sand and silt, oxidation mottling, rounded to subrounded gravel, trace organic odor at base of unit

UNIT WET
WEIGHT, pcf
ALLUVIUM (Qa3)
Poorly-graded SAND with silt (SP-SM): medium dense,
grayish black, wet
Qa3
LIQUID
INDEX, %
SAMPLE NO.
2 4
6 8
10 12
14 COMPLETION DEPTH: 9.0 ft
2 ALLUVIUM (Qa2)
Fat CLAY (CH): stiff, reddish brown, moist, fissured,
oxidation staining, gray staining along fissures,
consistency becomes soft at base of unit
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

LOG OF TEST PIT NO. T-13
CHECKED BY: J Blanchard
LOCATION: Middle of Perc Pond No. 1
DEPTH TO WATER: 4.0 ft
151
Qa2
Disturbed Soils
141
143
145
149
Percolation Pond No. 1
Santa Maria Wastewater Treatment Facility, Santa Maria, California City of Santa Maria
Project No. 3019.008
TEST PIT LOG WITH LAB SUMS VENTURA F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\3019.008.GPJ 6/30/08 12:25 p SURFACE EL: 151.0 ft +/- (rel. datum)
147
DEPTH, ft
8 4

TEST PIT GRAPHICAL REPRESENTATION
0 10

MATERIAL
6 SAMPLES

SAMPLER

UNDRAINED
SHEAR
STRENGTH,Su, ksf

BLOWCOUNT
CONTRACTOR: City of Santa Maria
EXCAVATION METHOD: Backhoe
SYMBOL
2 DEPTH, ft
D115 of 179

PLASTICITY
LIMIT, %
CONTENT, %
% PASSING
LOG OF TEST PIT NO. T-14
PLATE A-15

UNIT WET
WEIGHT, pcf
Qa2
LOCATION: Middle of Perc Pond No. 1
#200 SIEVE
LOG OF TEST HOLE NO. T-14
Sandy SILT (ML): grayish brown, moist, black staining,
trace organic odor
LIQUID
1 62
ALLUVIUM (Qa3)
Silty SAND (SM): yellowish brown to grayish brown, moist ALLUVIUM (Qa2)
Fat CLAY (CH): reddish brown, moist, oxidation mottling Disturbed Soils
Silty SAND (SM): medium dense, light brown to grayish
brown, moist
ELEVATION, +/- MSL
SURFACE EL: 148.0 ft +/- (rel. datum)
SAMPLE NO.
2 4
6 8
10 12
14 COMPLETION DEPTH: 7.0 ft
INDEX, %
ELEVATION, ft

MATERIAL DESCRIPTION

UNIT DRY
WEIGHT, pcf
WATER
EXCAVATION DATE: June 2, 2008 SAMPLES

UNDRAINED
SHEAR
STRENGTH,Su, ksf

BLOWCOUNT
CONTRACTOR: City of Santa Maria
EXCAVATION METHOD: Backhoe
DEPTH, ft
LOGGED BY: GD Eckrich

MATERIAL
DEPTH TO WATER: Not Encountered

TEST PIT GRAPHICAL REPRESENTATION
CHECKED BY: J Blanchard
8 DEPTH, ft

SAMPLER
10 146
144
142
140
138
136
134
6 4
2 0
SYMBOL
TD = 7.0 ft
TEST PIT LOG WITH LAB SUMS VENTURA F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\3019.008.GPJ 6/30/08 12:25 p The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

Disturbed Soils
Qa2
Qa3
Project No. 3019.008
138
140
142
144
146
148
Percolation Pond No. 1
Santa Maria Wastewater Treatment Facility, Santa Maria, California City of Santa Maria
D116 of 179
TEST PIT LOG WITH LAB SUMS VENTURA F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\3019.008.GPJ 6/30/08 12:25 p 141
143
145
147
149
Percolation Pond No. 1
Santa Maria Wastewater Treatment Facility, Santa Maria, California

MATERIAL DESCRIPTION
Project No. 3019.008
City of Santa Maria

UNIT DRY
WEIGHT, pcf
Qa2
151
TD = 7.5 ft
Qa3
Qa2
Qa2
Disturbed Soils
ALLUVIUM (Qa2)
Sandy SILT (ML): stiff, grayish brown, moist, oxidation staining, fissured
ALLUVIUM (Qa3)
Poorly-graded SAND with silt (SP-SM): medium dense to
dense, light yellowish brown, moist
1 Silty CLAY (CL-ML): grayish brown, moist, abundant black staining, organic odor
2 Disturbed Soils
Sandy Lean CLAY (CL): stiff, light brown, moist, occasional rounded gravel
Fat CLAY (CH): reddish brown, moist, fissured
LOG OF TEST PIT NO. T-15
WATER
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT GRAPHICAL REPRESENTATION
SURFACE EL: 151.0 ft +/- (rel. datum)
LOCATION: Middle of Perc Pond No. 1
DEPTH TO WATER: Not Encountered
63 MATERIAL
10 8
6 4
2 0
EXCAVATION METHOD: Backhoe
DEPTH, ft
SYMBOL

SAMPLES
ELEVATION, ft

BLOWCOUNT
CONTRACTOR: City of Santa Maria DEPTH, ft UNDRAINED SHEAR STRENGTH,Su, ksf
SAMPLE NO.

CHECKED BY: J Blanchard
PLATE A-16

SAMPLER
LIQUID
2 4
6 8
10 12
14 COMPLETION DEPTH: 7.5 ft ELEVATION, +/- MSL
INDEX, %
LOGGED BY: GD Eckrich
EXCAVATION DATE: June 2, 2008

UNIT WET
WEIGHT, pcf
150
148
146
144
142
140
138
#200 SIEVE

PLASTICITY
LIMIT, %
CONTENT, %
% PASSING
LOG OF TEST HOLE NO. T-15
D117 of 179

97.0 92.4 5.0
ALLUVIUM (Qa3)
Poorly-graded SAND (SP): light yellowish brown, moist
LOCATION: East Side of Perc Pond No. 1
DEPTH TO WATER: Not Encountered
City of Santa Maria
2 Percolation Pond No. 1
Santa Maria Wastewater Treatment Facility, Santa Maria, California Lean CLAY (CL): soft, grayish brown, moist, fissured
Fat CLAY (CH): stiff to very stiff, reddish brown, moist, fissured
ALLUVIUM (Qa2)
SILT (ML): gray to black, moist, Hydrogen Sulfide odor
Disturbed Soils
Clayey SAND (SC): light brown to grayish brown, moist
TD = 9.0 ft
Qa3
Qa2
Qa2
Qa2
152
142
144
146
148
150
Disturbed Soils
DEPTH, ft
10 8
6 4
2 0
EXCAVATION METHOD: Backhoe
SYMBOL
DEPTH, ft

MATERIAL

SAMPLES

SAMPLER

UNDRAINED
SHEAR
STRENGTH,Su, ksf
1 CONTRACTOR: City of Santa Maria

TEST PIT GRAPHICAL REPRESENTATION
CHECKED BY: J Blanchard
LOGGED BY: GD Eckrich
EXCAVATION DATE: June 2, 2008 BLOWCOUNT
Project No. 3019.008
TEST PIT LOG WITH LAB SUMS VENTURA F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\3019.008.GPJ 6/30/08 12:25 p SURFACE EL: 152.0 ft +/- (rel. datum)
LOG OF TEST PIT NO. T-16
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time. #200 SIEVE
LIQUID
150
148
146
144
142
140
138
INDEX, %
SAMPLE NO.
2 4
6 8
10 12
14 COMPLETION DEPTH: 9.0 ft
LOG OF TEST HOLE NO. T-16

UNIT WET
WEIGHT, pcf
ELEVATION, +/- MSL
ELEVATION, ft

MATERIAL DESCRIPTION

UNIT DRY
WEIGHT, pcf
WATER

PLASTICITY
LIMIT, %
CONTENT, %
% PASSING
PLATE A-17
D118 of 179

8.0 T-14 4.0 1 SILT (ML) 62
2 5
2 T-13
T-10 2.5 1 Poorly-graded SAND (SP) 1
Poorly-graded SAND with silt (SP-SM)
92 T-4

SAMPLE NUMBER

4.2E-2
T-15
5 3.0
T-16 8.5 1 Poorly-graded SAND (SP) 97
SILT (ML) 63
1 2
Poorly-graded SAND with silt (SP-SM)
T-57.6 2.0 1 Poorly-graded SAND (SP) 14107122

7.6E-3

8.1E-2
10 2.7E-2
T-4 7.5 2

0.0 1 Poorly-graded SAND with silt (SP-SM) 8
2 T-9 2.0 1 Poorly-graded SAND (SP) 102106 4
1 T-7 14.5 Poorly-graded SAND with silt (SP-SM)
T-7 7.5 1 Poorly-graded SAND with silt (SP-SM) 8
7 MAX
DD
pcf
Percolation Pond No. 1
Santa Maria Wastewater Treatment Facility, Santa Maria, California ATTERBERG FINES
LIMITS
%
LAB SUMMARY TABLE VENTURA_F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\3019.008.GPJ_ 7/3/08 10:14 AM-cab DEPTH, ft
Project No. 3019.008
Permeability, cm/s
PLATE B-1

CORROSIVITY TESTS
R pH

DRILLDIRECT
SHEAR
HOLE
OPT
MC
%
UWW
pcf
LL Cl

EXPANSION INDEX
UDW
pcf
MC
%
PI C
ksf
Qu,
ksf

COMPACTION
TEST

MATERIAL DESCRIPTION
SU
(Cell Prs.)
ksf
So4
(%)

SUMMARY OF LABORATORY TEST RESULTS
PHI
deg

SAND EQUIVALENT
(SE)

COMPRESSIVE

STRENGTH
TESTS

R-VALUE
City of Santa Maria
D120 of 179
20 10
0 40
50 1 0.1 0.01 0.001

7.5 2.0

8.0 30

100
90 80
70 60

8.5 2.0

GRAIN SIZE IN MILLIMETERS
Coarse Medium Fine

PERCENT FINER BY WEIGHT
Fine Coarse

CLASSIFICATION
PLATE B-2
SILT or CLAY
SAND
10 1.53 3/4 3/8 40 100
GRAVEL

GRAIN SIZE CURVES
10 LEGEND
20 HYDROMETER ANALYSIS
GRAIN SIZE CURVES VENTURA (F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\3019.008.GPJ) 7/2/08 05:00 p-sz Percolation Pond No. 1
Santa Maria Wastewater Treatment Facility, Santa Maria, California City of Santa Maria
Project No. 3019.008
Cc
(location)
Poorly-graded SAND with silt (SP-SM)
Poorly-graded SAND (SP)
Poorly-graded SAND with silt (SP-SM)
Poorly-graded SAND (SP)
T-4
T-5
T-7
T-9
(depth,ft)
T-16

US STD SIEVE SIZE
INCHES
200

US STD SIEVE SIZE

NUMBERS

7.5 4
T-13

4.6 Cu

1.6 0.9

1.4 0.8

1.2 1.2

5.6 Poorly-graded SAND (SP)

5.7 Poorly-graded SAND with silt (SP-SM)

3.2 2.4
100

3.0 D121 of 179
TP-3L2
TP-3-2
TP-3-4
TP-3-3
TP-3-5
TP-3L1
TP-3-1
TP-3-6
TP-4-2
TP-4-1
TP-4-7
TP-4L1
TP-4-6
TP-4-5
TP-4-3
City of Santa Maria
Project No. 04.6111.0048
PLATE 2

FIELD EXPLORATION PLAN
Percolation Ponds Nos. 3 and 4
Santa Maria, California
0 400
FEET
NORTH
All locations and dimensions are approximate
D122 of 179
PLATE A-1
City of Santa Maria
Project No. 04.6111.0048
11 4
Poorly graded SAND (SP)
C
O
A
R
S
E
G
R
A
I
N
E
D

MATERIAL DESCRIPTION
Silty CLAY (CL-ML)
Silty SAND (SM)
Paving and/or Base Materials

SANDSTONE
Poorly graded GRAVEL (GP)

MUDSTONE
SYMBOL

SILTSTONE
Well graded SAND (SW)
Fat CLAY (CH)

MATERIAL
SAMPLE NO.

Hand Auger Sample

ANDESITE BRECCIA
7 9
5 Thin-walled Tube, pushed
10 Symbol for:

CA Liner Sampler, driven
Vibracore Sample
Pitcher Sample
Lexan Sample
BASALT
Sonic Soil Core Sample
No Sample Recovered
CA Liner Sampler, Bagged
13 (25)
6 CONGLOMERATE
3 F
I
N
E
G
R
A
I
N
E
D
R
O
C
K
-12
-14
-16
-18
-20
-22
-24
-26
-28
-30
-32
-34
-36
-38
-40
-42
-44
-46
-48
2 4
6 8
10 12
14 16
18 20
22 24
26 28
30 32
34 36
38 25
Silty, Clayey SAND (SC-SM)
(25)
Elastic SILT (MH)
(25)
(25)
Lean CLAY (CL)
Sampler Driving Resistance
p = Pocket Penetrometer
Q = Unconfined Compression
u = Unconsolidated Undrained Triaxial
Initial or perched water level
Seepages encountered
Final ground water level
Bulk Bag Sample (from cuttings)
Number of blows with 140 lb. hammer, falling
30" to drive sampler 1 ft. after seating
sampler 6"; for example,

CLAYSTONE
LOCATION:

SILT (ML)
2 5
13 9
1 8
7 SAMPLES
Clayey SAND (SC)
The drill hole location referencing local
landmarks or coordinates
Well graded GRAVEL (GW)

BLOW COUNT /
t = Torvane
Blows/ft Description
25 Blow counts for California Liner Sampler
shown in ( )
Geologic Formation noted in bold font at
the top of interpreted interval
Classification of Soils per ASTM D2487
or D2488
Strength Legend
Length of sample symbol approximates
recovery length
Water Level Symbols
SURFACE EL: Using local, MSL, MLLW or other datum

KEY TO TERMS & SYMBOLS USED ON LOGS
12 m = Miniature Vane
Samplers and sampler dimensions
Soil Texture Symbol
General Notes
Sloped line in symbol column indicates
transitional boundary
(unless otherwise noted in report text) are as follows:
3 CA Liner Sampler, disturbed
11 1 SPT Sampler, driven
6 8
2 4
CME Core Sample
12 10
BORING LOG KEY VENTURA F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/2/11 09:36 a 30"/
30"
20"/
24"
DEPTH, ft
REC"/DRIVE"
18"/
30"
20"/
24"
ELEVATION, ft
50 blows drove sampler 3" during
initial 6" seating interval
Ref/3"
50 blows drove sampler 6" after
initial 6" of seating
After driving sampler the initial 6"
of seating, 36 blows drove
sampler through the second 6"
interval, and 50 blows drove the
sampler 5" into the third interval
50/6"
86/11"
25 blows drove sampler 12" after
initial 6" of seating
Rock Quality Designation (RQD) is the
sum of recovered core pieces greater
than 4 inches divided by the length of
the cored interval.
1-3/8" ID, 2" OD
2-3/8" ID, 3" OD
2-3/8" ID, 3" OD
2-7/8" ID, 3" OD
D124 of 179
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

Santa Maria, California
LOCATION: South-central of Pond 3
DEPTH TO WATER: Not Encountered
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 3-1
INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 14.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

1. Poorly graded SAND with silt (SP-SM): pale yellowish brown, moist, fine to medium sand

2. Lean CLAY (CL): reddish brown, moist

3. Poorly graded SAND with silt (SP-SM) to silty SAND
(SM): pale yellowish brown, fine to medium sand
PLATE A-2
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 3-1

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:11 a City of Santa Maria
Percolation Ponds Nos. 3 and 4
0 4
8 12
16 20
DEPTH, ft
DEPTH, ft
0 4
8 12
16 20
1 2
3 Bulk sample Hand driven ring sample
D125 of 179

1. Lean CLAY (CL): reddish brown, moist, minor gravel to 3"

2. Poorly graded SAND (SP): pale yellowish brown, wet,
fine to medium sand
3 WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 14.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
PLATE A-3
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 3-2
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER
LOCATION: Northeast corner of Pond 3
DEPTH TO WATER: Not Encountered
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 3-2
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:31 a City of Santa Maria
Santa Maria, California
Percolation Ponds Nos. 3 and 4
0 4
8 12
16 20
DEPTH, ft
DEPTH, ft
0 4
8 12
16 20
1 2
Bulk sample Hand driven ring sample
D126 of 179

1. Poorly graded SAND with silt (SP-SM): moderate
yellowish brown, fine sand

2. Lean CLAY (CL): reddish brown, moist to wet

3. Poorly graded SAND with silt (SP-SM): pale yellowish brown
WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 6.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
PLATE A-4
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 3-3
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER
LOCATION: East side near center of Pond 3
DEPTH TO WATER: Not Encountered
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 3-3
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:33 a City of Santa Maria
Santa Maria, California
Percolation Ponds Nos. 3 and 4
0 4
8 12
16 20
DEPTH, ft
DEPTH, ft
0 4
8 12
16 20
1 2
3 R3
Bulk sample Hand driven ring sample
D127 of 179

1. Poorly graded SAND with silt (SP-SM): moderate
yellowish brown, fine sand, disturbed material

2. Lean CLAY (CL): reddish brown, pockets of black sand

3. Poorly graded SAND (SP): gray to grayish brown, fine to medium sand
3 WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 5.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
PLATE A-5
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 3-4
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER
LOCATION: Northwest quadrant of Pond 3
DEPTH TO WATER: Not Encountered
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 3-4
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:34 a City of Santa Maria
Santa Maria, California
Percolation Ponds Nos. 3 and 4
0 4
8 12
16 20
DEPTH, ft
DEPTH, ft
0 4
8 12
16 20
1 2
3 Bulk sample Hand driven ring sample
D128 of 179
100.4 9.2 91.9

1. Poorly graded SAND with silt (SP-SM): moderate
yellowish brown

2. Lean CLAY (CL): light olive gray, moist, crumbly

3. Lean CLAY (CL): stiff to very stiff, dark yellowish brown, moist

4. Poorly graded SAND (SP): pale yellowish brown, fine to medium sand
2 WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 5.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
PLATE A-6
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 3-5
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER
LOCATION: Center of Pond 3
DEPTH TO WATER: Not Encountered
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 3-5
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:34 a City of Santa Maria
Santa Maria, California
Percolation Ponds Nos. 3 and 4
0 4
8 12
16 20
DEPTH, ft
DEPTH, ft
0 4
8 12
16 20
1 2
3 4
Bulk sample Hand driven ring sample
D129 of 179

1. Poorly graded SAND with silt (SP-SM): moderate
yellowish brown, wet, fine to medium sand, disturbed
material

2. Lean CLAY (CL): dark gray to dark yellowish brown

3. Poorly graded SAND with silt (SP-SM): pale yellowish brown, fine to medium sand
WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 6.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
PLATE A-7
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 3-6
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER
LOCATION: Southwest quadrant of Pond 3
DEPTH TO WATER: Not Encountered
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 3-6
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:34 a City of Santa Maria
Santa Maria, California
Percolation Ponds Nos. 3 and 4
0 4
8 12
16 20
DEPTH, ft
DEPTH, ft
0 4
8 12
16 20
1 2
3 Bulk sample Hand driven ring sample
D130 of 179

1. Silty SAND (SM): grayish brown, moist, fine sand

2. - dark yellowish brown
WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 6.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
PLATE A-8
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 3-L1
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER
LOCATION: Levee between Ponds 1 and 3
DEPTH TO WATER: Not Encountered
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 3-L1
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:34 a City of Santa Maria
Santa Maria, California
Percolation Ponds Nos. 3 and 4
0 4
8 12
16 20
DEPTH, ft
DEPTH, ft
0 4
8 12
16 20
1 2
Bulk sample Hand driven ring sample
D131 of 179

95.7 6.3 90.0

1. Poorly graded SAND with silt (SP-SM): grayish brown, moist, fine sand
14 11
WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 14.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
PLATE A-9
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 3-L2
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER
LOCATION: North end of levee between Ponds 1 and 3
DEPTH TO WATER: Not Encountered
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 3-L2
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:37 a City of Santa Maria
Santa Maria, California
Percolation Ponds Nos. 3 and 4
0 4
8 12
16 20
DEPTH, ft
DEPTH, ft
0 4
8 12
16 20
1 Bulk sample Hand driven ring sample
D132 of 179

1. SAND with silt (SP-SM): dark yellowish brown to brownish gray, wet to moist, fine to medium pockets of sand
WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 15.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
PLATE A-10
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 4-1
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER
LOCATION: Northeast quadrant of Pond 4
DEPTH TO WATER: Not Encountered
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 4-1
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:37 a City of Santa Maria
Santa Maria, California
Percolation Ponds Nos. 3 and 4
Bulk sample Hand driven ring sample
1 0
4 8
12 16
20 DEPTH, ft
DEPTH, ft
0 4
8 12
16 20
D133 of 179

1. Poorly graded SAND (SP): dark gray to brownish gray, wet - stained dark gray
WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 12.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
PLATE A-11
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 4-2
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER
LOCATION: Northeast corner of Pond 4
DEPTH TO WATER: Not Encountered
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 4-2
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:37 a City of Santa Maria
Santa Maria, California
Percolation Ponds Nos. 3 and 4
0 4
8 12
16 20
DEPTH, ft
DEPTH, ft
0 4
8 12
16 20
1 Dark gray
1 Bulk sample Hand driven ring sample
D134 of 179

1. Poorly graded SAND with silt (SP-SM): moderate
yellowish brown, wet, medium to coarse sand, minor
gravels
1A. Poorly graded SAND with silt (SP-SM): multicolored, coarse sand, rounded, seepage

2. Lean CLAY (CL): dark yellowish brown to moderate
yellowish brown, wet
WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 6.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
PLATE A-12
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 4-3
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER
LOCATION: Southeast quadrant of Pond 4
DEPTH TO WATER: Not Encountered
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 4-3
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:37 a City of Santa Maria
Santa Maria, California
Percolation Ponds Nos. 3 and 4
0 4
8 12
16 20
DEPTH, ft
DEPTH, ft
0 4
8 12
16 20
1 2
1A
Bulk sample Hand driven ring sample
D135 of 179
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 4-4
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER

1. Poorly graded SAND with silt (SP-SM): moderate
yellowish brown, moist, fine to medium sand, some fine
gravel, rounded

2. Poorly graded SAND (SP): moderate yellowish brown,
wet, medium sand

3. Lean CLAY (CL): reddish brown to dark yellowish brown

4. Poorly graded SAND with silt (SP-SM): moderate
yellowish brown, wet, medium sand
10 WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 11.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
PLATE A-13
LOCATION: South-center of Pond 4
DEPTH TO WATER: Not Encountered
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 4-4
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:40 a City of Santa Maria
Santa Maria, California
Percolation Ponds Nos. 3 and 4
0 2
4 6
8 10
DEPTH, ft
DEPTH, ft
0 2
4 6
8 10
1 2
3 4
Bulk sample Hand driven ring sample
D136 of 179

1. Poorly graded SAND (SP): moderate yellowish brown,
moist

2. Poorly graded SAND with gravel (SP): multicolored, wet, fine to coarse sand

3. Lean CLAY (CL): reddish brown, wet, 3' to 4' thick
3 1
WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 15.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
PLATE A-14
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 4-5
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER
LOCATION: South-center of Pond 4
DEPTH TO WATER: Not Encountered
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 4-5
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:40 a City of Santa Maria
Santa Maria, California
Percolation Ponds Nos. 3 and 4
0 3
6 9
12 15
DEPTH, ft
DEPTH, ft
0 3
6 9
12 15
1 2
3 Bulk sample Hand driven ring sample
D137 of 179
109.7 37.6 79.7

1. Silty SAND (SM): moderate yellowish brown, moist to
wet, fine sand

2. Sandy SILT (ML): moderate yellowish brown to
multicolored, medium to coarse sand, seeping

3. Lean CLAY (CL): moderate yellowish brown to dark
yellowish brown, wet, fine to medium sand

4. Poorly graded SAND with silt (SP-SM): moderate
yellowish brown, wet, fine to medium sand
WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 13.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
PLATE A-15
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 4-6
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER
LOCATION: Center of Pond 4
DEPTH TO WATER: Not Encountered
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 4-6
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:43 a City of Santa Maria
Santa Maria, California
Percolation Ponds Nos. 3 and 4
0 4
8 12
16 20
DEPTH, ft
DEPTH, ft
0 4
8 12
16 20
1 2
3 4
Bulk sample Hand driven ring sample
D138 of 179
117.9 17.7 100.2

1. Silty SAND (SM): moderate yellowish brown to brownish gray, moist to wet, medium to coarse sand

2. Lean CLAY (CL): reddish brown to moderate yellowish
brown, wet

3. Poorly graded SAND with silt (SP-SM): moderate
yellowish brown, wet, fine to medium sand
9 WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 9.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
PLATE A-16
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 4-7
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER
LOCATION: North-center of Pond 4
DEPTH TO WATER: Not Encountered
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 4-7
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:43 a City of Santa Maria
Santa Maria, California
Percolation Ponds Nos. 3 and 4
0 4
8 12
16 20
DEPTH, ft
DEPTH, ft
0 4
8 12
16 20
1 2
3 Bulk sample Hand driven ring sample
D139 of 179

1. Silty SAND (SM): moderate yellowish brown, dry

2. Poorly graded SAND with silt (SP-SM): dark yellowish brown, dry, fine to medium sand, fill, gravels occasionally to 3"

3. Poorly graded SAND with silt (SP-SM): pale yellowish brown, dry, fine to medium sand
8 12
WATER

UNIT DRY
WEIGHT, pcf
ELEVATION, ft

MATERIAL DESCRIPTION
COMPLETION DEPTH: 9.0 ft
2 4
6 8
10 12
14 SAMPLE NO.

INDEX, %
LIQUID

UNIT WET
WEIGHT, pcf
PLATE A-17
CONTENT, %
% PASSING
LIMIT, %
#200 SIEVE

PLASTICITY
LOG OF TEST PIT NO. TP 4-L1
EXCAVATION DATE: June 22, 2011
LOGGED BY: T Nicely
CHECKED BY: J Blanchard
EXCAVATION METHOD: Backhoe
CONTRACTOR: Fugro Consultants

BLOWCOUNT

UNDRAINED
SHEAR
STRENGTH,Su, ksf
DEPTH, ft

MATERIAL
SYMBOL

SAMPLES

SAMPLER
LOCATION: Levee between Ponds 2 and 4
DEPTH TO WATER: Not Encountered
SURFACE EL: ft +/- (rel. datum)

TEST PIT GRAPHICAL REPRESENTATION
LOG OF TEST PIT NO. TP 4-L1
The log and data presented are a simplification of actual conditions encountered at the time of exploring at the explored location. Subsurface conditions may differ at other locations and with the passage of time.

TEST PIT LOG WITH LAB SUMS VENTURA
Project No. 04.6111.0048
F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 11:44 a City of Santa Maria
Santa Maria, California
Percolation Ponds Nos. 3 and 4
0 4
8 12
16 20
DEPTH, ft
DEPTH, ft
0 4
8 12
16 20
1 2
3 Bulk sample Hand driven ring sample
D140 of 179
TP 3-1 2.0 Lean CLAY (CL) 106.6 19.6
TP 3-2 14.0 Poorly graded SAND (SP) 3TP 3-4 4.0 Poorly graded SAND (SP) 3TP 3-5 5.0 Poorly graded SAND (SP) 100 92 9 2 3.10E-3TP 3-L2 4.0 Silty SAND (SM) 96 90 6 14 6.90E-4TP 3-L2 5.0 Poorly graded SAND with silt (SP-SM) 11TP 4-2 2.5 Poorly graded SAND (SP) 103.9 17.8TP 4-4 0.0 Poorly graded SAND with silt (SP-SM) 10TP 4-5 3.0 Poorly graded SAND (SP) 3TP 4-5 5.0 Poorly graded SAND with gravel (SP) 1TP 4-6 5.0 Lean CLAY (CL) 110 80 38 7.10E-6TP 4-7 8.0 Poorly graded SAND with silt (SP-SM) 118 100 18 9 6.10E-3TP 4-L1 4.0 Poorly graded SAND with silt (SP-SM) 8TP 4-L1 5.0 Poorly graded SAND with silt (SP-SM) 12

SAMPLE NUMBER

SUMMARY OF LABORATORY TEST RESULTS
So4
(%)
LAB SUMMARY W/ HYDRAULIC CONDUCTIVITY _F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ_ 8/9/11 09:43 AM-cab FINES %
MAX
DD
pcf

ATTERBERG
LIMITS
DEPTH, ft
Percolation Ponds Nos. 3 and 4
Santa Maria, California
DRILL
HOLE

COMPACTION
TEST
SU (Cell Prs.)
ksf
Qu,
ksf
C
ksf PI
MC
%
UDW
pcf

HYDRAULIC
CONDUCTIVITY (cm/s)

SAND EQUIVALENT
(SE)

SPECIFIC GRAVITY

COMPRESSIVE

STRENGTH
TESTS
PHIdeg LL
UWW
pcf
OPT
MC
%
DIRECT
SHEAR
Cl R pH

CORROSIVITY TESTS
PLATE B-1

MATERIAL DESCRIPTION
Project No. 04.6111.0048
City of Santa Maria
D142 of 179
0 10
20 30
40 50
60 70
80 90
100
100 10 1 0.1 0.01 0.001
SAND
SILT or CLAY
Fine Coarse

PERCENT FINER BY WEIGHT
Coarse Medium Fine

GRAIN SIZE IN MILLIMETERS
GRAVEL

GRAIN SIZE CURVES
PLATE B-2
Project No. 04.6111.0048
City of Santa Maria
Percolation Ponds Nos. 3 and 4
Santa Maria, California
GRAIN SIZE CURVES VENTURA (F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ) 8/1/11 10:50 a-sz

HYDROMETER ANALYSIS
20 LEGEND
3 1.5 3/4 3/8 4 10 40 100
(depth,ft)
CLASSIFICATION Cc Cu

2.7 2.9

2.6 5.1

2.8 4.7

4.4 4.9
Poorly graded SAND (SP)
Poorly graded SAND (SP)
Poorly graded SAND (SP)
Poorly graded SAND with silt (SP-SM)
Poorly graded SAND (SP)
Poorly graded SAND with gravel (SP)
Poorly graded SAND with silt (SP-SM)
Poorly graded SAND with silt (SP-SM)
TP 3-2
TP 3-4
TP 3-5
TP 3-L2
TP 4-5
TP 4-5
TP 4-7
TP 4-L1
(location)

US STD SIEVE SIZE
INCHES
200

US STD SIEVE SIZE

NUMBERS

14.0 4.0

5.0 5.0

3.0 5.0

8.0 4.0

1.2 1.2

1.1 1.2

1.2 0.8

1.3 1.2
D143 of 179
100
105
110
115
120
125
130
135
0 5 10 15 20 25

OPTIMUM WATER
CONTENT, %
MOISTURE CONTENT, %
UNIT DRY WEIGHT, pcf

LEGEND MAXIMUM UNIT
DRY WEIGHT, pcf
Test Method: ASTM D1557
(Gs = 2.65 to 2.75)

CLASSIFICATION
106.6 19.6
depth, ft
PLATE B-3a

COMPACTION TEST RESULTS
(location)
Lean CLAY (CL)

ZERO AIR VOIDS CURVES
TP 3-1 2.0
COMPACTION TEST VENTURA F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 10:44 a Project No. 04.6111.0048
City of Santa Maria
Percolation Ponds Nos. 3 and 4
Santa Maria, California
D144 of 179
100
105
110
115
120
125
130
135
0 5 10 15 20 25

OPTIMUM WATER
CONTENT, %
MOISTURE CONTENT, %
UNIT DRY WEIGHT, pcf

LEGEND MAXIMUM UNIT
DRY WEIGHT, pcf
Test Method: ASTM D1557
(Gs = 2.65 to 2.75)

CLASSIFICATION
103.9 17.8
depth, ft
PLATE B-3b

COMPACTION TEST RESULTS
(location)
Poorly graded SAND (SP)

ZERO AIR VOIDS CURVES
TP 4-2 2.5
COMPACTION TEST VENTURA F:\FUGRO SLO GEOTECH DOCUMENTS\GINT\GINT PROJECTS\04.6111.0048.GPJ 8/1/11 10:44 a Project No. 04.6111.0048
City of Santa Maria
Percolation Ponds Nos. 3 and 4
Santa Maria, California
D145 of 179
City of Santa Maria
Project No. 04.6111.0048
Boring Number
Sample Number
Sample Depth, ft
Classification
Estimated Gs

SAMPLE ID
TP 3-5

CLASSIFICATION
Sieve Size

5.00 #4 (4.75mm)

SAMPLE PROPERTIES
Intial
% Passing Other Parameters
--- 3/8-in. (9.5mm) --- Liquid Limit ---
--- Plastic Limit ---
Poorly-graded SAND (SP): olive
brown, moist, fine sand
#
16 (1.18mm) --- Plasticity Index ---
#
30 (0.6mm) --- 2.65
#
100 (0.150mm) ---
Mass, g 363.48 425.55
---
ModCal
Deaired Tap-Water
Final #200 (0.075mm)

91.9 95.1 Permeant TEST SUMMARY
Sample Type

2.93 2.42 2.41
kavg 20ºC, cm/s
Water Content, % 9.2% 27.8%
Void Ratio 0.80 0.74
Saturation, % 30% 100%
Dry Density, pcf
Area, in2
Pipette Area, cm20.971

3.1E-03
Diameter, in Tested By JC
Height, in 3.00

4.60 4.55
Volume, in313.80 13.33

REMARKS
Test Method: ASTM D5084 (Method C)

PERMEATION DATA
Trial Date Time, sec TempAvg, ºC σ', ksf μ, ksf ioi
f kt
, cm/s
1 7/5/11 80 25.4 0.4 14.4 0.4 0.1 3.5E-03
2 7/5/11 77 25.4 0.4 14.4 0.4 0.1 3.6E-03
3 7/5/11 79 25.4 0.4 14.4 0.4 0.1 3.5E-03
4 7/5/11 78 25.4 0.4 14.4 0.4 0.1 3.6E-03
5 SAMPLE IMAGES
6 HYDRAULIC CONDUCTIVITY
Percolation Ponds Nos. 3 and 4
Santa Maria, California PLATE B-4a
D146 of 179
City of Santa Maria
Project No. 04.6111.0048
Boring Number
Sample Number
Sample Depth, ft
Classification
Estimated Gs

SAMPLE ID
TP 3-L2

CLASSIFICATION
Sieve Size

4.00 #4 (4.75mm)

SAMPLE PROPERTIES
Intial
% Passing Other Parameters
--- 3/8-in. (9.5mm) --- Liquid Limit ---
--- Plastic Limit ---
Silty SAND (SM): yellowish brown,
moist
#
16 (1.18mm) --- Plasticity Index ---
#
30 (0.6mm) --- 2.65
#
100 (0.150mm) ---
Mass, g 343.80 396.48

13.8 ModCal
Deaired Tap-Water
Final #200 (0.075mm)

90.0 103.3 Permeant TEST SUMMARY
Sample Type

2.83 2.41 2.32
kavg 20ºC, cm/s
Water Content, % 6.3% 22.6%
Void Ratio 0.84 0.60
Saturation, % 20% 100%
Dry Density, pcf
Area, in2
Pipette Area, cm20.971

6.9E-04
Diameter, in Tested By JC
Height, in 3.00

4.56 4.21
Volume, in313.69 11.92

REMARKS
Test Method: ASTM D5084 (Method C)

PERMEATION DATA
Trial Date Time, sec TempAvg, ºC σ', ksf μ, ksf ioi
f kt
, cm/s
1 7/6/11 375 24.9 0.4 14.4 0.4 0.1 7.7E-04
2 7/6/11 377 24.8 0.4 14.4 0.4 0.1 7.7E-04
3 7/6/11 376 24.8 0.4 14.4 0.4 0.1 7.7E-04
4 7/6/11 375 24.8 0.4 14.4 0.4 0.1 7.7E-04
5 SAMPLE IMAGES
6 HYDRAULIC CONDUCTIVITY
Percolation Ponds Nos. 3 and 4
Santa Maria, California PLATE B-4b
D147 of 179
City of Santa Maria
Project No. 04.6111.0048
Boring Number
Sample Number
Sample Depth, ft
Classification
Estimated Gs

4.60 38.5%

SAMPLE ID
TP 4-6
---
5 Lean CLAY (CL): yellowish brown,
moist

1.00 4.46

4.44 100%

1.04 kt σ', ksf μ, ksf , cm/s
Permeant
Pipette Area, cm2
kavg 20ºC, cm/s
Annulus Area, cm2
TempAvg, ºC

2.6 7.8E-06

8.1E-06

7.6E-06
i
f

2.6 2.6

2.6 0.4 13.2 9.8

9.8 13.2 9.8

REMARKS
Void Ratio
Diameter, in
Tested By JC

4.60 Test Method: ASTM D5084 (Method F)

2.38 132.50

0.4 0.4 13.2 7.8E-06
Date Time, sec

SAMPLE PROPERTIES
Intial Final
Mass, g
Water Content, %
Dry Density, pcf
Saturation, %
Height, in
Area, in2
Volume, in3

37.6%

79.7 5
36 7/1/11 37
Trial
7/1/11 37
6 24.0
7/1/11
3 24.0

24.0 SAMPLE IMAGES
2 1 7/1/11 38 9.8

PERMEATION DATA
io
4 24.0

0.4 13.2
#
100 (0.150mm)
Sample Type
#
200 (0.075mm)
---
---

TEST SUMMARY
91%

1.11 2.42

1.00 ModCal
Deaired Tap-Water

0.0314

7.1E-06

0.7671

82.6 3/8-in. (9.5mm) Liquid Limit ---
---
---

2.7 Plastic Limit
Plasticity Index
133.36

CLASSIFICATION
Sieve Size % Passing Other Parameters
#
16 (1.18mm)
#
30 (0.6mm)
---
---
#
4 (4.75mm)
---
---

HYDRAULIC CONDUCTIVITY
Percolation Ponds Nos. 3 and 4
Santa Maria, California PLATE B-4c
D148 of 179
City of Santa Maria
Project No. 04.6111.0048
Boring Number
Sample Number
Sample Depth, ft
Classification
Estimated Gs

SAMPLE ID
TP 4-7

CLASSIFICATION
Sieve Size

8.00 #4 (4.75mm)

SAMPLE PROPERTIES
Intial
% Passing Other Parameters
--- 3/8-in. (9.5mm) --- Liquid Limit ---
--- Plastic Limit ---
Poorly-graded SAND (SP):
yellowish brown, moist
#
16 (1.18mm) --- Plasticity Index ---
#
30 (0.6mm) --- 2.65
#
100 (0.150mm) ---
Mass, g 423.40 439.57
---
Remold
Deaired Tap-Water
Final #200 (0.075mm)
100.2 104.1 Permeant TEST SUMMARY
Sample Type

2.90 2.41 2.41
kavg 20ºC, cm/s
Water Content, % 17.7% 22.2%
Void Ratio 0.65 0.59
Saturation, % 72% 100%
Dry Density, pcf
Area, in2
Pipette Area, cm20.971

6.1E-03
Diameter, in Tested By JC
Height, in 3.00

4.56 4.54
Volume, in313.69 13.16

REMARKS
Test Method: ASTM D5084 (Method C)

PERMEATION DATA
Trial Date Time, sec TempAvg, ºC σ', ksf μ, ksf ioi
f kt
, cm/s
1 7/5/11 38 25.9 0.4 14.4 0.4 0.1 7.3E-03
2 7/5/11 40 25.9 0.4 14.4 0.4 0.1 6.9E-03
3 7/5/11 39 25.8 0.4 14.4 0.4 0.1 7.1E-03
4 7/5/11 40 25.8 0.4 14.4 0.4 0.1 6.9E-03
5 7/5/11 40 25.7 0.4 14.4 0.4 0.1 6.9E-03

6.9E-03

SAMPLE IMAGES
6 7/5/11 40 25.7 0.4 14.4 0.4 0.1

HYDRAULIC CONDUCTIVITY
Percolation Ponds Nos. 3 and 4
Santa Maria, California PLATE B-4d
D149 of 179
summary of the test pit locations with the depth to the top of the clay layer noted is shown in Figure 3.

4.2 SUGGESTED REQUIREMENTS FOR IMPORTED SAND
Imported replacement fill materials should consist of clean sand with a sand equivalent of at least 30 and no more than 3 percent fines. All import fill materials should be reviewed by the geotechnical professional prior to use. The onsite or imported soil should be sand that is free of topsoil, organics, clay and other deleterious material.

4.3 REUSE OF EXCAVATED SOIL
The hydraulic conductivity of the excavated soil should be approximately 1x10-3 centimeters per second (cm/s) or greater (i.e., faster). Relatively high permeability sandy soil excavated from the pond should be suitable for re-use as fill in the pond bottom based on Fugro’s (2008) study and sieve analysis data collected for this study. Fugro (2008) performed hydraulic conductivity testing on alluvium with fines contents of 1, 2 and 10 percent from beneath nearby Pond No. 1.

The Fugro (2008) hydraulic conductivity test results on samples with 1- and 2-percent fines content estimated permeability rates of 8.1x10-2 cm/s and 4.2x10-2 cm/s. The result of the Fugro Figure 3: Field Exploration Plan
D150 of 179
DATE
6/8/2018

PROJECT NAME
Pond No. 12 Rehabilitation
Poorly graded SAND with SILT and GRAVEL
SANDY lean CLAY GRAVELLY lean CLAY
ORGANIC lean CLAY with SAND ORGANIC lean CLAY with GRAVEL SANDY ORGANIC lean CLAY SANDY ORGANIC lean CLAY with GRAVEL
Fat CLAY with SAND
Fat CLAY with GRAVEL SANDY fat CLAY
SANDY fat CLAY with GRAVEL GRAVELLY fat CLAY GRAVELLY fat CLAY with SAND ORGANIC fat CLAY ORGANIC fat CLAY with SAND ORGANIC fat CLAY with GRAVEL SANDY ORGANIC fat CLAY Elastic SILT with SAND
Well-graded GRAVEL
Poorly graded GRAVEL with SILT
GRAVELLY lean CLAY with SAND
Standard California Sampler (2.5" O.D.)
C Consolidation (ASTM D 2435-04)
CL Collapse Potential (ASTM D 5333-03)
CP
CR Corrosion, Sulfates, Chlorides (CTM 643 - 99;
CTM 417 - 06; CTM 422 - 06)
CU Consolidated Undrained Triaxial (ASTM D 4767-02)
Direct Shear (ASTM D 3080-04)
Expansion Index (ASTM D 4829-03)
Moisture Content (ASTM D 2216-05)
Organic Content (ASTM D 2974-07)
Permeability (CTM 220 - 05)
Particle Size Analysis (ASTM D 422-63 [2002])
Liquid Limit, Plastic Limit, Plasticity Index
(AASHTO T 89-02, AASHTO T 90-00)
PP
PM
PL
PI
PA
P
OC
M
EI
DS
SP-SC
SW
SP
Piston Sampler
SW-SM
SILTY, CLAYEY GRAVEL with SAND
CLAYEY GRAVEL with SAND
SILTY GRAVEL with SAND
Compaction Curve (ASTM D1557)
Modified California Sampler (3" O.D.)
GRAVELLY SILT with SAND
SILT
ORGANIC SILT with SAND ORGANIC SILT with GRAVEL
Standard Penetration Test (SPT) (2" O.D.)

GROUP SYMBOLS AND NAMES

DRILLING METHOD SYMBOLS
OL
CH
MH
OH
OL/OH
Rock Core Grab Sample
OL
SC
GW
GW-GM
CL
CL-ML
ML
COBBLES and BOULDERS

BOULDERS
PT

SILTY GRAVEL

CLAYEY GRAVEL

SILTY, CLAYEY GRAVEL

SILTY SAND

CLAYEY SAND

SILTY CLAY
SILTY CLAY with SAND
SILTY CLAY with GRAVEL SANDY SILTY CLAY
SANDY SILTY CLAY with GRAVEL GRAVELLY SILTY CLAY GRAVELLY SILTY CLAY with SAND SILT with SAND
SILT with GRAVEL SANDY SILT SANDY SILT with GRAVEL
SANDY ORGANIC fat CLAY with GRAVEL GRAVELLY ORGANIC fat CLAY GRAVELLY ORGANIC fat CLAY with SAND Elastic SILT
ORGANIC elastic SILT with GRAVEL SANDY elastic ELASTIC SILT SILTY, CLAYEY SAND Group Names
SC-SM
Graphic / Symbol Graphic / Symbol Group Names
GC
GP
GC-GM

SANDY ORGANIC SILT
Lean CLAY with SAND
Lean CLAY with GRAVEL SANDY lean CLAY with GRAVEL
ORGANIC lean CLAY
GRAVELLY ORGANIC lean CLAY GRAVELLY ORGANIC lean CLAY with SAND Fat CLAY
Elastic SILT with GRAVEL SANDY elastic SILT SANDY elastic SILT with GRAVEL GRAVELLY elastic SILT GRAVELLY elastic SILT with SAND ORGANIC elastic SILT
SANDY ORGANIC SILT with GRAVEL GRAVELLY ORGANIC SILT GRAVELLY ORGANIC SILT with SAND

ORGANIC SILT
Well-graded SAND with CLAY and GRAVEL
(or SILTY CLAY and GRAVEL)
SILTY, CLAYEY SAND with GRAVEL
CLAYEY SAND with GRAVEL
SILTY SAND with GRAVEL

COBBLES
Well-graded GRAVEL with SAND
Well-graded GRAVEL with SILT
Well-graded GRAVEL with CLAY and SAND
(or SILTY CLAY and SAND)
Well-graded SAND with CLAY (or SILTY CLAY)
Poorly graded GRAVEL
Poorly graded GRAVEL with CLAY
(or SILTY CLAY)
Poorly graded SAND with SILT
Poorly graded SAND with CLAY (or SILTY CLAY)
Poorly graded SAND with CLAY and GRAVEL
(or SILTY CLAY and GRAVEL)
Lean CLAY
ORGANIC elastic SILT with SAND
SANDY ORGANIC elastic SILT with GRAVEL GRAVELLY ORGANIC elastic SILT GRAVELLY ORGANIC elastic SILT with SAND GW-GC
GP-GM
GP-GC
GM
Well-graded SAND with SILT
SW-SC
SP-SM

GRAVELLY SILT
ORGANIC SOIL ORGANIC SOIL with SAND ORGANIC SOIL with GRAVEL SANDY ORGANIC SOIL SANDY ORGANIC SOIL with GRAVEL GRAVELLY ORGANIC SOIL GRAVELLY ORGANIC SOIL with SAND OH
SM
Auger Drilling

FIELD AND LABORATORY TESTS

WATER LEVEL SYMBOLS
Dynamic Cone
or Hand Driven Rotary Drilling Diamond Core
Static Water Level Reading (long-term)
Shelby Tube
Bulk Sample Other (see remarks)
Static Water Level Reading (short-term)
First Water Level Reading (during drilling)
SHEET
1 of 1

SAMPLER GRAPHIC SYMBOLS
PEAT
Well-graded GRAVEL with SILT and SAND
Well-graded GRAVEL with CLAY (or SILTY CLAY)
Well-graded SAND
Well-graded SAND with GRAVEL
Well-graded SAND with SILT and GRAVEL
Poorly graded GRAVEL with SAND
Poorly graded GRAVEL with SILT and SAND
Poorly graded GRAVEL with CLAY and SAND
(or SILTY CLAY and SAND)
Poorly graded SAND
Poorly graded SAND with GRAVEL
Point Load Index (ASTM D 5731-05)
Pressure Meter
Pocket Penetrometer
R-Value (CTM 301 - 00)
Sand Equivalent (CTM 217 - 99)
Specific Gravity (AASHTO T 100-06)
Shrinkage Limit (ASTM D 427-04)
Swell Potential (ASTM D 4546-03)
Pocket Torvane
Unconfined Compression - Soil (ASTM D 2166-06)
Unconfined Compression - Rock (ASTM D 2938-95)
Unconsolidated Undrained Triaxial
(ASTM D 2850-03)
Unit Weight (ASTM D 4767-04)
Vane Shear (AASHTO T 223-96 [2004])
-200 200 Wash (ASTM D1140-14)
VS
UW
UU
UC
TV
SW
SL
SG
SE
R

REPORT TITLE

BORING RECORD LEGEND
D151 of 179
GB-1
GB-2
-200 (4% G, 88% S, 8% F)
M (15%)
Poorly graded SAND with SILT (SP-SM); trace GRAVEL ; grey-brown, moist, (disturbed).

Poorly graded SAND (SP); grey with black mottling, moist.

SILTY SAND (SM); grey with black, moist.

Lean CLAY (CL); brown, moist, stiff, with white gypsum veins.

Poorly graded SAND (SP); dark grey, moist.

Bottom of test pit at 9.0 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-01

TIME COMPLETED
0830

LOCATION DESCRIPTION
Northwest corner of Pond No. 12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

9.0 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
134
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-01

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
8 9
D152 of 179
GB-1
GB-2
PA (1% G, 89% S, 10% F)
M(13%)
Poorly graded SAND (SP); grey-brown, moist.

Lean CLAY (CL); brown, moist, stiff.

Bottom of test pit at 7.0 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-02

TIME COMPLETED
0850

LOCATION DESCRIPTION
West-center edge of Pond No. 12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

7.0 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-02

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
D153 of 179
GB-1
GB-2
-200 (0% G, 96% S, 4% F)
M (15%)
PI (LL= 45, PL = 23, PI =22)
M (25%)
Poorly graded SAND with SILT (SP-SM); grey-brown with black, moist.

Lean CLAY (CL); brown, moist, stiff.

Poorly graded SAND (SP); grey-brown, moist.

Bottom of test pit at 9.0 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-03

TIME COMPLETED

LOCATION DESCRIPTION
West-center edge of Pond No. 12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

9.0 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
134
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-03

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
8 9
D154 of 179
GB-1
GB-2
-200 (0% G, 95% S, 5% F)
M (17%)
Poorly graded SAND with SILT (SP-SM); brown, moist.

Poorly graded SAND (SP); black, moist.

Lean CLAY (CL); brown, moist, stiff.

Poorly graded SAND (SP); black, moist.

Bottom of test pit at 10.0 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-04

TIME COMPLETED

LOCATION DESCRIPTION
Southwest corner of Pond No. 12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

10.0 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
134
132
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-04

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
8 9
10 D155 of 179
GB-1 PA (2% G, 95% S, 5% F)
M (10%)
Poorly graded SAND with SILT (SP-SM); dark brown, moist.

Poorly graded SAND (SP); grey-black, moist.

Lean CLAY (CL); brown, moist.

Bottom of test pit at 9.0 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-05

TIME COMPLETED

LOCATION DESCRIPTION
South-center edge of Pond No. 12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

9.0 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
134
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-05

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
8 9
D156 of 179
GB-1
GB-2
GB-3
GB-4
-200 (0% G, 97% S, 3% F)
M (14%)
-200 (2% G, 95% S, 3% F)
M (10%)
PA (8% G, 82% S, 10% F)
M (11%)
Poorly graded SAND (SP); dark brown with trace of yellow, moist.

Grey-brown, trace gravel.

Poorly graded SAND with CLAY (SP-SC); brown, moist, trace gravel.

Lean CLAY (CL); brown, moist, stiff.

Bottom of test pit at 9.5 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-06

TIME COMPLETED
1011

LOCATION DESCRIPTION
South-center edge of Pond No.12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

9.5 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
134
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-06

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
8 9
D157 of 179
GB-1
GB-2
-200 (0% G, 94% S, 6% F)
M (14%)
PA (1% G, 94% S, 5% F)
M (13%)
Poorly graded SAND with SILT (SP-SM); grey-brown, moist.

Poorly graded SAND (SP); brown, moist, some gravel.

Seepage at 6.5 feet.

Lean CLAY (CL); brown, wet, soft.

Bottom of test pit at 8.0 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-07

TIME COMPLETED

LOCATION DESCRIPTION
East-center edge of Pond No. 12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

8.0 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
134
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-07

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
8 D158 of 179
GB-1
GB-2
-200 (7% G, 89% S, 4% F)
M (14%)
PA (1% G, 95% S, 4% F)
M (11%)
Poorly graded SAND (SP); dark brown, moist.

Brown, trace fines.

Bottom of test pit at 12.0 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-08

TIME COMPLETED
1155

LOCATION DESCRIPTION
Southeast corner of Pond No. 12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

12.0 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
134
132
130
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-08

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
8 9
10 11
12 D159 of 179
GB-1
GB-2
GB-3
-200 (2% G, 89% S, 9% F)
M (14%)
PA (0% G, 97% S, 3% F)
M (14%)
Poorly graded SAND with SILT (SP-SM); brown, moist.

Poorly graded SAND (SP); light brown, moist, trace gravel.

Lean CLAY (CL); brown with traces of white and grey lines, moist, stiff.

Poorly graded SAND (SP); brown, moist.

Bottom of test pit at 12.0 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-09

TIME COMPLETED
1215

LOCATION DESCRIPTION
East-center edge of Pond No. 12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

12.0 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
134
132
130
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-09

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
8 9
10 11
12 D160 of 179
GB-1
GB-2
-200 (0% G, 90% S, 10% F)
M (14%)
-200 (1% G, 97% S, 2% F)
M (6%)
Poorly graded SAND with SILT (SP-SM); dark brown, moist.

Poorly graded SAND (SP); light brown, moist.

Lean CLAY (CL).

Bottom of test pit at 9.0 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-10

TIME COMPLETED
1230

LOCATION DESCRIPTION
East-center edge of Pond No. 12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

9.0 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
134
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-10

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
8 9
D161 of 179
GB-1
GB-2
-200 (0% G, 97% S, 3% F)
M (10%)
PA (0% G, 93% S, 7% F)
M (9%)
Poorly graded SAND (SP); dark brown, moist.

Poorly graded SAND with SILT (SP-SM); light brown, moist.

Lean CLAY (CL); brown, moist, medium stiff.

Bottom of test pit at 10.0 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-11

TIME COMPLETED
1245

LOCATION DESCRIPTION
Norththeast corner of Pond No. 12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

10.0 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
134
132
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-11

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
8 9
10 D162 of 179
GB-1
GB-2
GB-3
-200 (0% G, 91% S, 9% F)
M (16%)
-200 (0% G, 93% S, 7% F)
M (13%)
PI (LL = 36, PL = 19, PI = 17)
M (24%)
Poorly graded SAND with CLAY (SP-SC); dark brown, moist.

Poorly graded SAND (SP); light brown, moist, trace gravel.

Seepage at 3 feet.

Lean CLAY (CL); brown, moist, soft.

Poorly graded SAND (SP); light brown, moist.

Bottom of test pit at 8.0 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-12

TIME COMPLETED
1310

LOCATION DESCRIPTION
North-center edge of Pond No. 12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

8.0 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
134
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-12

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
8 D163 of 179
GB-1
GB-2
PA (1% G, 95% S, 4% F)
M (9%)
-200 (3% G, 96% S, 1% F)
M (6%)
Poorly graded SAND (SP); grey-black, moist.

Lean CLAY (CL); brown, moist, medium-stiff.

Poorly graded SAND (SP); brown with grey patches, moist.

Encountered CLAY at 8 feet bgs but test pit collapsed and was terminated at 8 feet bgs.

Bottom of test pit at 8.0 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-13

TIME COMPLETED
1330

LOCATION DESCRIPTION
North-center edge of Pond No. 12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

8.0 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
134
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-13

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
8 D164 of 179
GB-1
GB-2
-200 (2% G, 93% S, 6% F)
M (14%)
-200 (0% G, 97% S, 3% F)
M (7%)
Poorly graded SAND with SILT (SP-SM); brown with black patches, moist, trace gravel.

Lean CLAY (CL); brown, moist, medium-stiff.

Poorly graded SAND (SP); brown, moist.

Bottom of test pit at 10.5 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-14

TIME COMPLETED
1345

LOCATION DESCRIPTION
West-center of Pond No. 12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

10.5 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
134
132
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-14

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
8 9
10 D165 of 179
GB-1
GB-2
-200 (0% G, 95% S, 5% F)
M (13%)
PA (1% G, 88% S, 11% F)
M (11%)
Poorly graded SAND with SILT (SP-SM); dark brown, moist.

Grey with black.

Lean CLAY (CL); brown, moist, medium-stiff.

Poorly graded SAND (SP); brown, moist.

Bottom of test pit at 9.0 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-15

TIME COMPLETED
1350

LOCATION DESCRIPTION
West-center of Pond No. 12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

9.0 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
134
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-15

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
8 9
D166 of 179
GB-1
GB-2
-200 (1% G, 92% S, 7% F)
M (15%)
-200 (2% G, 86% S, 12% F)
M (7%)
Poorly graded SAND with SILT (SP-SM); grey with black, moist.

Brown with grey.

Lean CLAY (CL); brown, moist.

Poorly graded SAND (SP); brown, moist.

Lean CLAY (CL); brown, moist.

Poorly graded SAND (SP).

Bottom of test pit at 11.0 ft bgs
This Boring Record was developed in accordance with the Caltrans Soil & Rock Logging, Classification, and Presentation Manual (2010) except as noted on the Soil or Rock Legend or below.

GROUNDWATER

READINGS

LOGGED BY
Alex Limpert

FINAL BY
Nick Simon

TEST PIT NUMBER
18T-16

TIME COMPLETED
1405

LOCATION DESCRIPTION
East-center of Pond No. 12

SURFACE ELEVATION
142.0 ft

CONTRACTOR
City of Santa Maria

EQUIPMENT
John Deere 310 SJ Backhoe

BUCKET WIDTH
24"

DATE STARTED
6-8-18

TIME STARTED

DATE COMPLETED
6-8-18

BACKFILLED WITH
Approved Native Fill

TOTAL DEPTH OF TRENCH

11.0 ft

ORIENTATION
TEST PIT LOCATION (Lat/Long or North/East and Datum) -- DURING EXCAVATION Not EncounteredAFTER EXCAVATION
DATE
6/8/2018
Sample LocationSample Number Moisture Content (%)Dry Unit Weight(pcf)Shear Strength(ksf)

PROJECT NAME
Pond No. 12 Rehabilitation

PROJECT NUMBER
218-244
SHEET
1 of 1
ELEVATION (ft) Material Graphics
140
138
136
134
132
Remarks
DEPTH (ft)

TEST PIT NUMBER
18T-16

DESCRIPTION
TRENCH LOG 244-218_NS.GPJ CALIFORNIA YEH LIBRARY (FEB 2013).GLB 7/30/18 0 1
2 3
4 5
6 7
8 9
10 11
D167 of 179
Project No. Date Checked By N. Simon
Boring No. Sample No. Depth (ft) Sample Type Gravel > #4 (%) Sand (%) Fines < #200 (%) LL PI pH R (ohm- cm) SO42- (mg/kg) Cl- (mg/kg) Max. Unit Weight (pcf) Optimum Water Content (%) 18T-01 1 1 GB 14.8 -- 4 88 8 -- -- -- -- -- -- -- -- -- Poorly-graded SAND with silt (SP-SM)18T-02 1 1 GB 13.4 -- 1 89 10 -- -- -- -- -- -- -- -- -- Poorly-graded SAND with silt (SP-SM)18T-03 1 1 GB 15.2 -- 0 96 4 -- -- -- -- -- -- -- -- -- Poorly-graded SAND (SP)18T-03 2 6.5 GB 25.4 -- -- -- -- 45 22 -- -- -- -- -- -- -- Lean CLAY (CL) 18T-04 1 1 GB 16.8 -- 0 95 5 -- -- -- -- -- -- -- -- -- Poorly-graded SAND with silt (SP-SM) 18T-05 1 3.5 GB 10.3 -- 2 95 3 -- -- -- -- -- -- -- -- -- Poorly-graded SAND (SP)18T-06 1 1 GB 14.4 -- 0 97 3 -- -- -- -- -- -- -- -- -- Poorly-graded SAND (SP)18T-06 2 6 GB 9.5 -- 2 95 3 -- -- -- -- -- -- -- -- -- Poorly-graded SAND (SP)18T-06 3 7.5 GB 11.1 -- 8 82 10 -- -- -- -- -- -- -- -- -- Well-graded SAND with clay (SW-SC)18T-07 1 1 GB 14.2 -- 0 94 6 -- -- -- -- -- -- -- -- -- Poorly-graded SAND with silt (SP-SM)18T-07 2 5 GB 13.1 -- 1 94 5 -- -- -- -- -- -- -- -- -- Poorly-graded SAND (SP)18T-08 1 1 GB 13.6 -- 7 89 4 -- -- -- -- -- -- -- -- -- Poorly-graded SAND (SP)18T-08 2 9 GB 11.4 -- 1 95 4 -- -- -- -- -- -- -- -- -- Poorly-graded SAND (SP)18T-09 1 1 GB 13.7 -- 2 89 9 -- -- -- -- -- -- -- -- -- Poorly-graded SAND with silt (SP-SM)18T-09 2 5 GB 10.0 -- 4 91 5 -- -- -- -- -- -- -- -- -- Poorly-graded SAND (SP)18T-10 1 2 GB 13.5 -- 0 90 10 -- -- -- -- -- -- -- -- -- Poorly-graded SAND with silt (SP-SM)18T-10 2 5 GB 5.9 -- 1 97 2 -- -- -- -- -- -- -- -- -- Poorly-graded SAND (SP)18T-11 1 1 GB 9.8 -- 0 97 3 -- -- -- -- -- -- -- -- -- Poorly-graded SAND (SP)18T-11 2 5 GB 9.2 -- 0 93 7 -- -- -- -- -- -- -- -- -- Poorly-graded SAND with clay (SP-SC) 218-244 6/22/2018
Summary of Laboratory Test Results
R-Value
Project Name Santa Maria WWTP - Pond 12 Rehabilitation Project Manager J. Blanchard Atterberg Corrosion
USCS Classification
Sample Location
Moisture
Content
(%)
Dry Unit
Weight
(pcf)
Gradation Compaction
D169 of 179
Project No. Date Checked By N. Simon
Boring No. Sample No. Depth (ft) Sample Type Gravel > #4 (%) Sand (%) Fines < #200 (%) LL PI pH R (ohm- cm) SO42- (mg/kg) Cl- (mg/kg) Max. Unit Weight (pcf) Optimum Water Content (%) 18T-12 1 1 GB 16.1 -- 0 91 9 -- -- -- -- -- -- -- -- -- Poorly-graded SAND with clay (SP-SC)18T-12 2 3.5 GB 12.9 -- 0 93 7 -- -- -- -- -- -- -- -- -- Poorly-graded SAND with clay (SP-SC)18T-12 3 5 GB 24.3 -- -- -- -- 36 17 -- -- -- -- -- -- -- Lean CLAY (CL) 18T-13 1 5 GB 8.5 -- 1 95 4 -- -- -- -- -- -- -- -- -- Poorly-graded SAND (SP) 18T-13 2 7 GB 5.9 -- 3 96 1 -- -- -- -- -- -- -- -- -- Poorly-graded SAND (SP)18T-14 1 1 GB 14.4 -- 2 93 6 -- -- -- -- -- -- -- -- -- Poorly-graded SAND with silt (SP-SM)18T-14 2 8 GB 7.2 -- 0 97 3 -- -- -- -- -- -- -- -- -- Poorly-graded SAND (SP)18T-15 1 1 GB 13.2 -- 0 95 5 -- -- -- -- -- -- -- -- -- Poorly-graded SAND (SP)18T-15 2 4 GB 11.4 -- 1 88 11 -- -- -- -- -- -- -- -- -- Poorly-graded SAND with silt (SP-SM)18T-16 1 2 GB 14.8 -- 1 92 7 -- -- -- -- -- -- -- -- -- Poorly-graded SAND with clay (SP-SC)18T-16 2 5 GB 6.9 -- 2 86 12 -- -- -- -- -- -- -- -- -- Poorly-graded SAND with clay (SP-SC) Summary of Laboratory Test Results
Project Name Santa Maria WWTP - Pond 12 Rehabilitation 218-244 6/22/2018 Project Manager J. Blanchard Corrosion Compaction
R-Value USCS Classification
Sample Location
Moisture
Content
(%)
Dry Unit
Weight
(pcf)
Gradation Atterberg
D170 of 179
Boring Sample No. Depth (ft) AASHTO Classification Tin ID Tin Mass (g) Tin + Soil (g) Tin + Dry Soil (g) No. 4 Dish ID No. 4 Dish Mass (g) No. 4 Dish + Dry no. 4 (g) Tin + Dry Soil Minus No. 4 Passing No. 4 Passing No. 200 % Gravel % Sand % Fines Water Content (%) 18T-01 1 1 -- 106B 134.7 198.9 190.6 2X 21.0 23.5 183.8 96% 7.7% 4% 88% 8% 14.8%18T-03 1 1 -- 107C 135.0 172.9 167.9 -- 0.0 0.0 166.5 100% 4.3% 0% 96% 4% 15.2%18T-04 1 1 -- 109C 134.7 193.2 184.8 -- 0.0 0.0 182.2 100% 5.2% 0% 95% 5% 16.8%18T-06 1 1 -- 108A 134.7 205.2 196.3 -- 0.0 0.0 194.2 100% 3.4% 0% 97% 3% 14.4%18T-06 2 6 -- 203A 134.9 198.5 193.0 1U 24.1 25.1 190.3 98% 2.9% 2% 95% 3% 9.5%18T-07 1 1 -- 301A 122.9 194.5 185.6 -- 0.0 0.0 181.9 100% 5.9% 0% 94% 6% 14.2%18T-08 1 1 -- 302A 122.8 174.6 168.4 2N 21.2 24.3 163.3 93% 4.4% 7% 89% 4% 13.6%18T-09 1 1 -- 303A 122.5 174.9 168.6 1L 24.3 25.1 163.5 98% 9.3% 2% 89% 9% 13.7%18T-10 1 2 -- 306A 122.9 175.9 169.6 -- 0.0 0.0 164.7 100% 10.5% 0% 90% 10% 13.5%18T-10 2 5 -- 307A 123.0 173.2 170.4 1H 23.9 24.3 168.9 99% 2.3% 1% 97% 2% 5.9%18T-11 1 1 -- 107A 134.8 178.6 174.7 -- 0.0 0.0 173.4 100% 3.3% 0% 97% 3% 9.8%18T-12 1 1 -- 101A 134.8 197.7 189.0 2J 20.8 21.0 183.9 100% 9.0% 0% 91% 9% 16.1%18T-12 2 4 -- 101R 135.3 193.8 187.1 -- 0.0 0.0 183.5 100% 6.9% 0% 93% 7% 12.9% Percent Passing No. 200 Sieve
Test Methods: ASTM D1140, D2487
Poorly-graded SAND (SP),yellow
brown, moist
USCS Classification
& Soil Description
Poorly-graded SAND with silt (SP-SM), dark grey, moist
Poorly-graded SAND (SP), dark grey,
moist
Poorly-graded SAND with silt (SP-SM), dark grey, moist
Poorly-graded SAND (SP), dark
grey, moist
6/15/2018
Project Manager Jon Blanchard

SPECIMEN ID AND MEASUREMENTS
Testing Date
City of Santa Maria WWTP - Pond 12 Rehabilitation
N. Simon
Project Name
Poorly-graded SAND with silt (SP-SM), dark grey, moist
Poorly-graded SAND (SP),
brown, moist, few gravel
Poorly-graded SAND with silt (SP-SM), brown, moist
Poorly-graded SAND with clay
(SP-SC), dark brown, moist
Poorly-graded SAND with clay
(SP-SC), dark brown, moist
Poorly-graded SAND with silt (SP-SM), dark brown, moist Poorly-graded SAND (SP),
brown, moist
Poorly-graded SAND (SP),
brown, moist
Prewash Washed
Tested By R. Atiliano/A. Limpert Checked By
Project No. 218-244
D171 of 179
Boring Sample No. Depth (ft) AASHTO Classification Tin ID Tin Mass (g) Tin + Soil (g) Tin + Dry Soil (g) No. 4 Dish ID No. 4 Dish Mass (g) No. 4 Dish + Dry no. 4 (g) Tin + Dry Soil Minus No. 4 Passing No. 4 Passing No. 200 % Gravel % Sand % Fines Water Content (%) 18T-13 2 7 -- 102R 135.1 204.7 200.8 2H 20.8 23.0 198.1 97% 0.8% 3% 96% 1% 5.9%18T-14 1 1 -- 101B 134.5 220.2 209.4 2R 20.8 22.0 204.0 98% 5.6% 2% 93% 6% 14.4%18T-14 2 8 -- 4A 135.0 203.7 199.1 -- 0.0 0.0 197.0 100% 3.3% 0% 97% 3% 7.2%18T-15 1 1 -- 102A 134.9 223.2 212.9 -- 0.0 0.0 209.1 100% 4.9% 0% 95% 5% 13.2%18T-16 1 2 -- 9B 135.5 188.9 182.0 2I 20.9 21.2 178.5 99% 6.9% 1% 92% 7% 14.8%18T-16 2 5 -- 101B 130.8 180.5 177.3 1Y 24.4 25.5 170.7 98% 11.8% 2% 86% 12% 6.9% Poorly-graded SAND with silt (SP-SM), dark brown, moist, trace gravel
Poorly-graded SAND (SP),
brown, moist
Poorly-graded SAND (SP), dark
brown, moist
Poorly-graded SAND with clay
(SP-SC), dark brown , moist
Poorly-graded SAND with clay
(SP-SC), brown , moist
Poorly-graded SAND (SP),
brown, moist
Tested By R. Atiliano/A. Limpert Checked By N. Simon Testing Date 6/15/2018

SPECIMEN ID AND MEASUREMENTS
Prewash Washed
USCS Classification
& Soil Description
Percent Passing No. 200 Sieve
Test Methods: ASTM D1140, D2487
Project Name City of Santa Maria WWTP - Pond 12 Rehabilitation Project No. 218-244 Project Manager Jon Blanchard D172 of 179
Project Manager
Boring No. Sample
No.

Depth
(ft)
Water
Content
(%)
Gravel
(%)
Sand
(%)
Fines
(%)
D10 (mm) D30 (mm) D50 (mm) D60 (mm) Cu Cc
USCS
Classification
& Soil
Description
AASHTO
Classification
18T-02 1 1 13.4% 1% 89% 10.0% 0.08 0.21 0.32 0.38 5.10 1.60 Poorly-graded
SAND with SILT (SP-SM), brown, moist
--
18T-05 1 3.5 10.3% 3% 95% 2.9% 0.17 0.31 0.42 0.55 3.30 1.00 Poorly graded
SAND (SP), brown,
moist
--
18T-06 3 8 11.1% 8% 82% 10.4% 0.07 0.26 0.38 0.47 6.70 2.10 Well-graded SAND
with CLAY (SW-SC), brown, moist,
trace GRAVEL
--
18T-07 2 5 13.1% 1% 94% 4.6% 0.14 0.27 0.38 0.45 3.20 1.20 Poorly-graded
SAND (SP), brown,
moist, trace clay
fines
--
18T-08 2 9 11.4% 2% 95% 3.7% 0.15 0.29 0.41 0.52 3.50 1.10 Poorly-graded
SAND (SP), brown,
moist, trace fines
--
Mechnical Sieve Analysis
Test Methods: ASTM D6913, D2487, D4718
Project Name
Checked By
218-244

SUMMARY OF RESULTS
Testing Date
City of Santa Maria WWTP-Pond 12 Rehabilitation Project No.

Jon Blanchard Tested By R. Atilano/A. Limpert
N. Simon 6/15/2018
D173 of 179
Boring No. Sample
No.

Depth
(ft)
Water
Content
(%)
Gravel
(%)
Sand
(%)
Fines
(%)
D10 (mm) D30 (mm) D50 (mm) D60 (mm) Cu Cc
USCS
Classification
& Soil
Description
AASHTO
Classification
18T-09 2 5 10.0% 4% 91% 4.9% 0.11 0.22 0.32 0.37 3.30 1.10 Poorly-graded
SAND (SP), brown,
moist, trace fines
and gravel
--
18T-11 2 5 9.2% 1% 93% 6.6% 0.11 0.26 0.36 0.41 3.70 1.40 Poorly-graded
SAND with CLAY
(SP-SC), brown,
moist, clod of
CLAY
--
18T-13 1 5 8.5% 1% 95% 3.9% 0.17 0.33 0.47 0.58 3.40 1.10 Poorly-graded
SAND (SP), brown,
moist, trace SILT
--
18T-15 2 4 11.4% 1% 88% 11.1% 0.08 0.22 0.33 0.38 5.10 1.70 Poorly-graded
SAND with SILT (SP-SM), , dark grey,
moist
--
#DIV/0! ##### ###### ##### ###### ##### ##### ##### ##### #DIV/0! Well-Graded
GRAVEL with Sand
(GW) brown,
moist, subrounded
gravel
0 #DIV/0! ##### ###### ##### ###### ##### ##### ##### ##### #DIV/0! Well-Graded
GRAVEL with Sand
(GW) brown,
moist, subrounded
gravel
0 #DIV/0! ##### ###### ##### ###### ##### ##### ##### ##### #DIV/0! Well-Graded
GRAVEL with Sand
(GW) brown,
moist, subrounded
gravel
0 SUMMARY OF RESULTS
D174 of 179
18T-02
1 Poorly-graded SAND with SILT (SP-SM)
18T-05
1 Poorly graded SAND (SP)
Boring No.:

Sample No.:

Boring No.:

Sample No.:

USCS
Classification:

USCS
Classification:

GRADATION CHARTS
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
100 10 1 0.1 0.01
% Passing
Particle Diameter (mm)
1/2"3/4"1"2"3" 3/8" No. 4 No. 10 No. 20 No. 40 No. 60 No. 100 No. 200 |<-------------- Gravel -------------->| <------------------------- Sand ---------------------->| <--------- Fines --------->| 0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
100 10 1 0.1 0.01
% Passing
Particle Diameter (mm)
1/2"3/4"1"2"3" 3/8" No. 4 No. 10 No. 20 No. 40 No. 60 No. 100 No. 200 |<-------------- Gravel ---------->| <------------------------- Sand -------------------->| <--------- Fines --------->| D175 of 179
18T-06
3 Well-graded SAND with CLAY (SW-SC)
18T-07
2 Poorly-graded SAND (SP)
Boring No.:

GRADATION CHARTS
USCS
Classification:

USCS
Classification:

Boring No.:

Sample No.:

Sample No.:
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
100 10 1 0.1 0.01
% Passing
Particle Diameter (mm)
1/2"3/4"1"2"3" 3/8" No. 4 No. 10 No. 20 No. 40 No. 60 No. 100 No. 200 |<-------------- Gravel -------------->| <------------------------- Sand -------------------->| <--------- Fines ------->| 0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
100 10 1 0.1 0.01
% Passing
Particle Diameter (mm)
1/2"3/4"1"2"3" 3/8" No. 4 No. 10 No. 20 No. 40 No. 60 No. 100 No. 200 |<-------------- Gravel -------------->| <------------------------- Sand --------------------->| <--------- Fines ------->| D176 of 179
18T-08
2 Poorly-graded SAND (SP)
18T-09
2 Poorly-graded SAND (SP)

GRADATION CHARTS
Boring No.:

Sample No.:

USCS
Classification:

Boring No.:

Sample No.:

USCS
Classification:
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
100 10 1 0.1 0.01
% Passing
Particle Diameter (mm)
1/2"3/4"1"2"3" 3/8" No. 4 No. 10 No. 20 No. 40 No. 60 No. 100 No. 200 |<-------------- Gravel -------------->| <------------------------ Sand ---------------------->| <--------- Fines --------->| 0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
100 10 1 0.1 0.01
% Passing
Particle Diameter (mm)
1/2"3/4"1"2"3" 3/8" No. 4 No. 10 No. 20 No. 40 No. 60 No. 100 No. 200 |<-------------- Gravel -------------->| <------------------------- Sand ---------------------->| <--------- Fines ------->| D177 of 179
18T-11
2 Poorly-graded SAND with CLAY (SP-SC)
18T-13
1 Poorly-graded SAND (SP)

GRADATION CHARTS
Boring No.:

Sample No.:

USCS
Classification:

USCS
Classification:

Sample No.:

Boring No.:
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
100 10 1 0.1 0.01
% Passing
Particle Diameter (mm)
1/2"3/4"1"2"3" 3/8" No. 4 No. 10 No. 20 No. 40 No. 60 No. 100 No. 200 |<-------------- Gravel -------------->| <---------------------- Sand ------------------------>| <--------- Fines-------->| 0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
100 10 1 0.1 0.01
% Passing
Particle Diameter (mm)
1/2"3/4"1"2"3" 3/8" No. 4 No. 10 No. 20 No. 40 No. 60 No. 100 No. 200 |<-------------- Gravel -------------->| <------------------------- Sand ---------------------->| <--------- Fines --------->| D178 of 179
18T-15
2 Poorly-graded SAND with SILT (SP-SM)
Boring No.:

Sample No.:

USCS
Classification:

GRADATION CHARTS
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
100 10 1 0.1 0.01
% Passing
Particle Diameter (mm)
1/2"3/4"1"2"3" 3/8" No. 4 No. 10 No. 20 No. 40 No. 60 No. 100 No. 200 |<-------------- Gravel -------------->| <---------------------- Sand ------------------------>| <--------- Fines -------->| D179 of 179
VOLUME 7 / CHAPTER 2: EFFLUENT DISPOSAL
JANUARY 2026 / DRAFT FINAL / CAROLLO

CITY OF SANTA MARIA

SANTA MARIA WWTP PROGRAM MANAGEMENT SERVICES

APPENDIX D GSI WATER SOLUTIONS

PERCOLATION POND PERFORMANCE

EVALUATION
City of Santa Maria
Wastewater Treatment Facility
Percolation Pond Performance Evaluation
April 16, 2024 (Revised June 4, 2024)
Prepared by:

GSI Water Solutions, Inc.
418 Chapala Street, Suite H, Santa Barbara, CA 93101
This page intentionally left blank.

City of Santa Maria | Wastewater Treatment Facility Percolation Pond Performance Evaluation GSI Water Solutions, Inc. iii
Contents
Introduction ............................................................................................................................................................... 1 Facility Operation ...................................................................................................................................................... 3 Percolation Capacity ................................................................................................................................................. 6 Empirical Flow Testing .......................................................................................................................................... 6 Results7
Water Balance Results ..................................................................................................................................... 7 Discussion ......................................................................................................................................................... 8 Closure and Operational Considerations .............................................................................................................. 12 Tables
Table 1. Santa Maria Wastewater System Percolation Pond Details.................................................................... 3 Table 2. Summary of Flow Testing Results ............................................................................................................. 8 Table 3. Santa Maria Wastewater System Percolation Capacity .......................................................................... 9 Figures
Figure 1. Location Map ............................................................................................................................................ 4 Figure 2. Site Map .................................................................................................................................................... 5 Figure 3. Qualitative Pond Performance ............................................................................................................... 10 Figure 4. Quantitative Pond Performance............................................................................................................. 11 Attachments
Attachment A Percolation Pond Hydrographs
Attachment B Daily Effluent Flow Volumes
City of Santa Maria | Wastewater Treatment Facility Percolation Pond Performance Evaluation GSI Water Solutions, Inc. iv
This page intentionally left blank.

City of Santa Maria | Wastewater Treatment Facility Percolation Pond Performance Evaluation GSI Water Solutions, Inc. 1
Introduction
This report presents the results of a hydrogeologic assessment conducted by GSI Water Solutions, Inc. (GSI) to evaluate the current percolation capacity of ponds at the City of Santa Maria’s (City) Wastewater Treatment Facility (Wastewater System). GSI is collaborating with Yeh & Associates (Yeh) and Carollo Engineers to present a long-term percolation test to quantify the inflow, outflow, evaporation, and percolation of water that is directed into the City’s percolation ponds.

The City has faced ongoing challenges with relatively poor performance of their percolation ponds at the Wastewater System. A series of investigations over the past couple of decades have documented challenges with the percolation capacity of these ponds and identified several problems that have caused reduced infiltration capacity including clay layers at shallow depths beneath the ponds and with a minimal downward hydraulic gradient, as the main reasons for hampered infiltration and percolation.

The City’s Wastewater System is located within the Santa Maria Valley Management Area of the Santa Maria Groundwater Basin1. The site is underlain by
alluvial deposits of gravel, sand, silt and clay.

Percolation of treated wastewater from the site
can be impeded by shallow groundwater
beneath the site and by layers of clay present in
the area. The uppermost material at the site
becomes progressively finer to the west
(towards the coast). Sand and silt from the City
of Santa Maria extends towards the west to a
point approximately halfway to Guadalupe. Clay
and silt are present from this area westward.

Groundwater elevations near the site have
been as high as 30 feet below ground around
the year 2000, which have since declined to
about 110 feet below ground. Relative to the
site location, the percolation capacity is
expected to be relatively better to the east
towards Santa Maria and relatively worse
towards the west.

To document the current percolation capacity of the ponds, GSI developed and conducted flow monitoring within the City’s current percolation ponds. The objective of this flow monitoring was to understand the current wastewater percolation capacity, which involved recording inflow volumes of the treated wastewater directed into the percolation ponds, along with evaporation and rainfall, and from these data, estimating rates of wastewater percolation into the underlying groundwater basin and evaporation rates from pond water surface. The elements quantified in this overall water balance into each of the facility’s 15 percolation ponds are presented in the graphic below. Together, the documentation of these inflow components (effluent and precipitation) and outflow components (percolation and evaporation) provide the overall water budget for these ponds for this assessment.
1 Luhdorff & Scalmanini. 2025. 2024 Annual Report of Hydrogeologic Conditions, Water Requirements, Supplies and Disposition Santa Maria Valley Management Area. April 2025.

Geologic Cross Section (Luhdorff & Scalmanini, 2004)
City of Santa Maria | Wastewater Treatment Facility Percolation Pond Performance Evaluation GSI Water Solutions, Inc. 2
A forthcoming report will document whether the ponds' performance has changed significantly relative to this assessment and several prior studies that focused on the existing percolation ponds. The forthcoming report will also present results of field exploration of the materials below the percolation ponds that is currently underway. GSI will conduct this further assessment to identify the geotechnical and hydrogeological factors affecting percolation capacity and identify any possible operational modifications that could be implemented to address reduced percolation pond capacity.

City of Santa Maria | Wastewater Treatment Facility Percolation Pond Performance Evaluation GSI Water Solutions, Inc. 3
Facility Operation
The City Utilities Department operates the Wastewater System and associated percolation ponds on an approximate 211-acre property in Santa Maria, California on Black Road between W Main Street and W Stowell Road approximately 1.5 miles west of the City. The location of the site is presented on Figure 1 and the respective locations of all percolation ponds within the facility are shown in Figure 2.

The Wastewater System is designed to treat 13.5 million gallons per day (MGD) on a maximum month basis to a secondary treatment level but is limited in disposal capacity to 8 MGD2. The percolation ponds are not currently performing adequately as indicated by percolation pond level measurements and effluent flow as presented in this report. The treatment system does not produce any recycled water, and therefore percolation and evaporation are the only means of disposal of the produced effluent.

Operationally, the treated effluent is directed to one or more ponds at a time by City staff to ponds that are available (not full) at a filling rate that greatly exceeds the percolation rate of an individual pond. Typically, a couple of ponds have been emptied and dried out and are available to receive the effluent. The maximum water depth within the 15 percolation ponds varies between completely dry and a maximum depth of 8 and 16 feet when filled. Water levels are required to be maintained with at least two feet of freeboard.

A summary of the area of the available percolation ponds to accommodate the produced effluent is presented in Table 1. Notably, the area covered by each pond varies with water depth such that water within each pond covers more area when full than when partially filled. The total volume of the ponds is approximately 300 million gallons, as shown, which is equal to 934 acre-feet.

Table 1. Santa Maria Wastewater System Percolation Pond Details Pond Area Empty
(Acres)
Area Full
(Acres) 1
Maximum Pond
Depth (Feet)2
Approximate Volume
(Million gallons)
1 6.3 8 11 26
2 7.2 8 11 27
3 3 4 16 19
4 4.4 4.6 10 11
5 6.2 7 16 36
6 6.6 7 11 25
7 1.5 2 12 4
8 2.9 3.5 9 9
11 6.2 6.3 8 16
12 5.9 7 12 25
13 6.7 8 12 28
14 6.3 7 12 26
15 5.3 7 12 24
DKC 6 7 9 19
Wash Pond 1 1.5 15 6
Total 75.5 87.9 -- 304
1: Acreage shown represent water level when full with approximately 2 feet of freeboard. 2: Maximum pond depth determined based on observed depths measured by City staff. 2 The Central Coast Regional Water Quality Control Board reduced the rated treatment capacity of the wastewater system based on the reduced percolation capacity of the ponds.

City of Santa Maria | Wastewater Treatment Facility Percolation Pond Performance Evaluation GSI Water Solutions, Inc. 4
Figure 1. Location Map
City of Santa Maria | Wastewater Treatment Facility Percolation Pond Performance Evaluation GSI Water Solutions, Inc. 5
Figure 2. Site Map
City of Santa Maria | Wastewater Treatment Facility Percolation Pond Performance Evaluation GSI Water Solutions, Inc. 6
Percolation Capacity
The current percolation capacity of the Wastewater System percolation ponds is described in the following section. A comparison of the historic percolation capacity of the ponds, along with a history of proposed and implemented improvements to the percolation ponds, will be presented in a forthcoming report.

Empirical Flow Testing
To estimate the current
percolation capacity of
the ponds, a water
balance was conducted
by GSI to estimate the
proportions of the
treated wastewater
directed into the
Wastewater System’s
ponds that ultimately
either percolate into the
underlying groundwater
or evaporate. The
analysis took place over
an approximately five-month period between
November 2023 and April 2024. This water balance conducted by GSI consisted of documenting pond level conditions on a daily basis in the course of the normal operation of the facility during this period. The ponds are operated serially through a series of fill, dry, and rest cycles. City staff do not allow percolation to continue until each pond is dry, but instead, when several feet of water remain, the City staff pumps water into another dry pond. The testing period began and ended when a similar number of ponds were completely dry. No diversions of this effluent are directed to any location other than the percolation ponds.

The water level in each pond is
measured and recorded daily
relative to staff gauges (shown
on this photo) by City staff,
which was compiled for this
water balance study. Daily
records of effluent volumes
directed to the 15 percolation
ponds were compiled from City
records. Hydrographs of the
pond water levels during the
testing period are presented as
Attachment A.

Particular attention was
focused on the rates at which effluent was directed to each of the 15 ponds, which all drained from a relatively full state until the wastewater had receded significantly. The daily volumes of effluent directed to the ponds are presented as Attachment B.

City of Santa Maria | Wastewater Treatment Facility Percolation Pond Performance Evaluation GSI Water Solutions, Inc. 7
To estimate evaporation rates from the percolation
ponds, GSI installed a Class A evaporation pan
equipped with a data logger (shown in this photo). The
evaporation pan meets National Weather Service Class
A specifications. It is constructed of low carbon type
304 stainless steel and is fitted with an external
NovaLynx 255-100 Analog Output Evaporation Gauge
automated system. The Analog Output Evaporation
Gauge is designed to accurately measure water level
in the evaporation pan. As water evaporates from the
pan or precipitation fills the pan, a float mechanism
turns a precision potentiometer which was monitored
by a data logger to record the change. Evaporation
data are shown on the hydrographs in Attachment A.

Precipitation data was compiled from records from
nearest rain gauge operated by the California Irrigation Management Information System (CIMIS) station
number 232 near the Santa Maria Airport to the
southwest. Precipitation records for another rainfall
gauge located farther away to the north on the Nipomo
Mesa were evaluated, but not used for this analysis
because of the much greater distance from the site
and relatively higher elevation of the gauge.

Results
During the 5-month duration of the flow testing during the winter of 2023 and spring of 2024, the ponds were partially or entirely full for a majority of the period. On average, the ponds were wetted for 72 percent of the period, which varied from 63 to 79 percent of the days during this period, respectively for ponds 15 and

5. Based on this water balance, the average percolation capacity for the Wastewater Facility was 0.27 feet per day during this period, which is equal to 3.3 inches per day or 9.6x10-5 cm/sec. This percolation rate is representative of sandy silt to clayey sand.

Water Balance Results
The total volume of effluent flow directed to the percolation ponds averaged 6.63 MGD and ranged between

5.20 and 8.42 MGD.

In addition to contributions to the ponds from the effluent, significant precipitation fell during the period between mid-November 2023 and mid-April 2024. During this period, a total of 15.0 inches of precipitation fell on the percolation ponds during a series of winter storms. Rainfall during this period added an additional 33 million gallons of water to the percolation ponds, which was equal to 0.22 MGD on average. This volume added an additional 3% of water relative to the effluent flow. Notably, this 15 inches of rainfall that fell during this period is roughly similar to the 12 inches of evaporation that occurred. During the other warmer and drier times of the year, rainfall will be limited or non-existent and evaporation will be higher.

The total inflow to the percolation ponds totaled 6.85 MGD from these two sources:

City of Santa Maria | Wastewater Treatment Facility Percolation Pond Performance Evaluation GSI Water Solutions, Inc. 8
• 6.63 MGD from effluent flow (97% of total inflow), and • 0.22 MG from precipitation (3% of total inflow).

The percolation ponds accommodated the entire inflow volume due principally to percolation and, to a lesser degree, to evaporation, although some accumulation of pond volume did occur. Of the total volume of inflow to the ponds by effluent and precipitation of 6.85 MGD:
• 6.68 MGD percolated (97% of total), which ranged from 5.4 to 6.7 MGD, and • 0.18 MGD evaporated (3% of total), which ranged from zero during rainy days in the winter to 0.4 MGD during the later spring months.

The results of the testing are summarized on Table 2.

Table 2. Summary of Flow Testing Results
Flow Component Average Volume
MGD
Proportion of
Total Inflow
Inflow
Wastewater
System
Effluent

6.63 97%
Precipitation 0.22 3%
Outflow
Percolation 6.68 97%
Evaporation 0.18 3%
Note: MGD Millions of Gallons per Day
During the other warmer and drier times of the year, rainfall will be much lower, and the proportion of evaporation compared to effluent flow will be higher. Specifically, evaporation during the summer months will be as much as 80 percent higher than evaporation during the study period for an average of 0.32 MGD.

Likewise, during the entire year evaporation should average 30 to 35 percent higher compared to the study period (average of 0.23 to 0.24 MGD, or 85 to 88 million gallons).

Discussion
The City provided estimates of percolation capacity based on data provided by Mr. Russ Newman with the City based on the City’s long-term familiarity with the operation and performance of the ponds. The City’s estimates of the percolation capacity provided a range of percolation rates for each pond, which was based on a longer period than was included in this water balance analysis.

The results of this water balance suggest that the measured percolation capacity during this period closely matched the City’s estimates; the City estimated percolation capacity of 7 to 11 MGD for the Wastewater Facility, while this water balance measured the percolation capacity to be an average of 6.85 MGD, which is near the lower end of the City’s estimate. The water balance did not support the middle and higher end of the City’s range of estimated percolation capacity during the testing period.

The observed water level variation shown on the hydrographs presented as Attachment A show that the required fill, drain, and rest cycles for each pond include several periods when no water is percolating (ponds are dry) while the ponds “rest” to accommodate nitrogen removal. The A summary of the approximate percolation capacity of each of the percolation ponds, along with the relative performance of each, is presented on Table 3.

City of Santa Maria | Wastewater Treatment Facility Percolation Pond Performance Evaluation GSI Water Solutions, Inc. 9
Table 3. Santa Maria Wastewater System Percolation Capacity Pond Name Percolation Capacity
(MGD) Performance
1 0.8 to 1.0 Decent
2 0.6 to 0.7 Medium
3 0.6 to 0.7 Medium
4 0.1 Poor
5 0.8 to 1.0 Medium
6 0.2 Poor
7 0.1 to 0.2 Poor
8 0.1 to 0.2 Poor
11 0.3 Mediocre
12 0.3 to 0.4 Mediocre
13 0.4 to 0.5 Mediocre
14 0.2 to 0.3 Poor
15 0.4 to 0.5 Medium
DKC 0.5 to 0.6 Medium
Wash Pond 0.1 Poor
Total 5.6 to 6.8
The City’s estimate of the percolation pond performance is provided on Figure 3. As shown, the best percolating ponds are estimated to have “decent” performance (ponds 1, 2, and 3) while some ponds are estimated to have “poor” performance (ponds 4, 6, and 7). Notably, no ponds were categorized as having “great” performance.

For comparison, a similar map of the pond performance based on the same criteria, but based on the current testing is provided on Figure 4, along with a comparison of the City’s estimate and the results of this water balance. As shown, the ponds are categorized somewhat similarly, but several ponds perform relatively worse including ponds 8, 14, and the Wash Pond that all perform poorly. Likewise, ponds 3 and 12 do not perform as well as previously presented. Pond 15 appears to be performing better, at “medium” performance than previously presented. As previously, no ponds were categorized as having “great” performance.

City of Santa Maria | Wastewater Treatment Facility Percolation Pond Performance Evaluation GSI Water Solutions, Inc. 10
Figure 3. Qualitative Pond Performance
City of Santa Maria | Wastewater Treatment Facility Percolation Pond Performance Evaluation GSI Water Solutions, Inc. 11

Figure 4. Quantitative Pond Performance

City of Santa Maria | Wastewater Treatment Facility Percolation Pond Performance Evaluation GSI Water Solutions, Inc. 12
Closure and Operational Considerations
The operation of the City’s Wastewater System, as currently configured, is limited by poor percolation capacity due to factors.. The data presented in this water balance suggest that the current performance of the ponds is limited by the current percolation capacity of approximately 6 to 7 MGD.

As presented in all of the hydrographs presented in Attachment A, there are periods where the ponds are empty and not percolating effluent. While the operation of the ponds requires frequent drying, as described, these periods when the ponds are dry decreases the overall percolation capacity proportionally. The ponds were dry for 28 percent of the period of this testing during a wet winter when increased percolation capacity is typically most needed.

A geotechnical data report was prepared by Yeh and Associates for the facility3 which present the operational alternatives that may be effective to regain percolation capacity at the Wastewater System. The preliminary recommendations presented by Yeh were discussed during the project and adequately identify operational improvements that are highly likely to improve percolation capacity including the following tasks.

1. Remove the upper 2 to 4 inches of accumulated organic layer that forms following drying of beds, when possible.

2. Following removal of the shallow organic layer, perform deep ripping of the bottom of each pond when dry.

3. When possible, plan and budget for removal of clayey and silty soil within the upper 5 to 10 feet of the ponds. Yeh suggested that the phased implementation of this task would provide the city to evaluate the effectiveness of this deep soil removal program, which would include soil sampling and testing before and after the removal process.

4. Operationally, Yeh recommends reducing the total suspended solids of the effluent being introduced to the ponds.

5. Yeh mentioned focus on the elevations of the groundwater within the aquifer below the percolation ponds, which may hinder percolation at greater depths. While monitoring of these conditions is important and may affect percolation, we understand that the greatest limitations to percolation within this system are due to the shallow organic layer (2 to 4 inches), deeper (ripping depth), and 5 to 10 feet (remedied by deep removal).

6. Lastly, installation of stilling wells within the ponds would provide improved data upon which to evaluate the effectiveness of the above operational improvements. We understand that the City is installing these stilling wells within many of the percolation ponds along with automated and remote monitoring devices, which will aid in the effective operation of the Wastewater Facility. 3 Yeh and Associates. 2024. Draft Geotechnical Data Report City of Santa Maria Wastewater Treatment Plant Percolation Pond Study. Prepared for Carollo Engineers. October 3, 2024.

ATTACHMENT A
Percolation Pond Hydrographs
Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 0

0.1 0.2

0.3 0.4

0.5 0.6

0.7 0.8

0.91 Evaporation (inches) 02468
10 12
14 16
18 Depth to Water (feet)
Pond 1
FIGURE A-1
Percolation Pond 1 Hydrograph
Santa Maria Wastewater Treatment Facility
Santa Maria, California

0.40 feet
per day

0.25 feet
per day
Average:

0.32 feet per day
Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 0

0.1 0.2

0.3 0.4

0.5 0.6

0.7 0.8

0.91 Evaporation (inches) 02468
10 12
14 16
18 Depth to Water (feet)
Pond 2
FIGURE A-2
Percolation Pond 2 Hydrograph
Santa Maria Wastewater Treatment Facility
Santa Maria, California

0.30 feet
per day

0.15 feet
per day
Average:

0.22 feet per day
Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 0

0.1 0.2

0.3 0.4

0.5 0.6

0.7 0.8

0.91 Evaporation (inches) 02468
10 12
14 16
18 Depth to Water (feet)
Pond 3
FIGURE A-3
Percolation Pond 3 Hydrograph
Santa Maria Wastewater Treatment Facility
Santa Maria, California

0.48 feet
per day

0.38 feet
per day
Average:

0.43 feet per day
Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 0

0.1 0.2

0.3 0.4

0.5 0.6

0.7 0.8

0.91 Evaporation (inches) 02468
10 12
14 16
18 Depth to Water (feet)
Pond 4
FIGURE A-4
Percolation Pond 4 Hydrograph
Santa Maria Wastewater Treatment Facility
Santa Maria, California

0.14 feet
per day
Average:

0.14 feet per day
Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 0

0.1 0.2

0.3 0.4

0.5 0.6

0.7 0.8

0.91 Evaporation (inches) 02468
10 12
14 16
18 Depth to Water (feet)
Pond 5
FIGURE A-5
Percolation Pond 5 Hydrograph
Santa Maria Wastewater Treatment Facility
Santa Maria, California

0.29 feet
per day

0.36 feet
per day
Average:

0.33 feet per day
Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 0

0.1 0.2

0.3 0.4

0.5 0.6

0.7 0.8

0.91 Evaporation (inches) 02468
10 12
14 16
18 Depth to Water (feet)
Pond 6
FIGURE A-6
Percolation Pond 6 Hydrograph
Santa Maria Wastewater Treatment Facility
Santa Maria, California

0.08 feet
per day
Average:

0.08 feet per day
Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 0

0.1 0.2

0.3 0.4

0.5 0.6

0.7 0.8

0.91 Evaporation (inches) 02468
10 12
14 16
18 Depth to Water (feet)
Pond 7
FIGURE A-7
Percolation Pond 7 Hydrograph
Santa Maria Wastewater Treatment Facility
Santa Maria, California

0.19 feet
per day

0.19 feet
per day
Average:

0.19 feet per day
Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 0

0.1 0.2

0.3 0.4

0.5 0.6

0.7 0.8

0.91 Evaporation (inches) 02468
10 12
14 16
18 Depth to Water (feet)
Pond 8
FIGURE A-8
Percolation Pond 8 Hydrograph
Santa Maria Wastewater Treatment Facility
Santa Maria, California

0.22 feet
per day

0.18 feet
per day
Average:

0.20 feet per day
Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 0

0.1 0.2

0.3 0.4

0.5 0.6

0.7 0.8

0.91 Evaporation (inches) 02468
10 12
14 16
18 Depth to Water (feet)
Pond 11
FIGURE A-11
Percolation Pond 11 Hydrograph
Santa Maria Wastewater Treatment Facility
Santa Maria, California

0.14 feet
per day

0.15 feet
per day
Average:

0.15 feet per day
Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 0

0.1 0.2

0.3 0.4

0.5 0.6

0.7 0.8

0.91 Evaporation (inches) 02468
10 12
14 16
18 Depth to Water (feet)
Pond 12
FIGURE A-12
Percolation Pond 12 Hydrograph
Santa Maria Wastewater Treatment Facility
Santa Maria, California

0.08 feet
per day

0.23 feet
per day
Average:

0.15 feet per day
Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 0

0.1 0.2

0.3 0.4

0.5 0.6

0.7 0.8

0.91 Evaporation (inches) 02468
10 12
14 16
18 Depth to Water (feet)
Pond 13
FIGURE A-13
Percolation Pond 13 Hydrograph
Santa Maria Wastewater Treatment Facility
Santa Maria, California

0.15 feet
per day
Average:

0.15 feet per day
Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 0

0.1 0.2

0.3 0.4

0.5 0.6

0.7 0.8

0.91 Evaporation (inches) 02468
10 12
14 16
18 Depth to Water (feet)
Pond 14
FIGURE A-14
Percolation Pond 14 Hydrograph
Santa Maria Wastewater Treatment Facility
Santa Maria, California

0.13 feet
per day

0.09 feet
per day
Average:

0.10 feet per day
Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 0

0.1 0.2

0.3 0.4

0.5 0.6

0.7 0.8

0.91 Evaporation (inches) 02468
10 12
14 16
18 Depth to Water (feet)
Pond 15
FIGURE A-15
Percolation Pond 15 Hydrograph
Santa Maria Wastewater Treatment Facility
Santa Maria, California

0.17 feet
per day

0.21 feet
per day
Average:

0.19 feet per day
Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 0

0.1 0.2

0.3 0.4

0.5 0.6

0.7 0.8

0.91 Evaporation (inches) 02468
10 12
14 16
18 Depth to Water (feet)
Pond DKC

FIGURE A-DKC
Percolation Pond DKC Hydrograph
Santa Maria Wastewater Treatment Facility
Santa Maria, California

0.23 feet
per day

0.17 feet
per day
Average:

0.20 feet per day
Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2024 May 2024 0

0.1 0.2

0.3 0.4

0.5 0.6

0.7 0.8

0.91 Evaporation (inches) 02468
10 12
14 16
18 Depth to Water (feet)
Pond Wash
FIGURE A-Wash
Percolation Pond Wash Hydrograph
Santa Maria Wastewater Treatment Facility
Santa Maria, California

0.22 feet
per day

0.17 feet
per day
Average:

0.19 feet per day
City of Santa Maria Wastewater Treatment Plant Percolation Pond Monitoring Nov 2023
Percolation Pond Height (in")
Day 1 2 3 4 5 6 7 8 11 12 13 14 15 DKC Wash
1 0 23 23 78 136 90 62 88 46 0 43 0 86 26 92
2 0 14 0 73 130 94 70 90 40 0 38 0 96 42 89
3 0 5 0 71 123 98 82 93 36 0 35 0 108 54 89
4 10 0 0 66 118 97 82 88 35 65 22 0 106 54 88
5 23 0 0 65 110 94 78 86 27 76 0 0 98 53 86
6 55 0 0 63 105 90 72 81 18 81 0 0 86 48 85
7 62 0 0 54 106 88 85 78 8 92 0 0 86 60 84
8 76 0 0 10 93 84 103 72 0 96 0 0 81 76 50
9 84 0 0 0 88 81 114 69 0 96 0 0 75 88 0
10 92 0 47 0 83 76 108 66 0 100 0 0 70 80 0
11 97 0 71 0 82 76 97 61 0 108 0 0 64 72 0
12 100 0 89 0 76 72 96 60 0 114 0 0 60 72 0
13 107 0 112 0 70 71 95 58 0 115 0 0 66 68 0
14 105 10 120 0 64 68 90 53 0 108 0 12 60 72 0
15 100 18 131 0 60 60 90 51 0 104 0 26 58 64 0
16 95 30 126 48 57 54 91 48 0 99 0 45 46 66 0
17 84 40 117 59 57 45 93 46 0 94 0 57 34 65 0
18 82 50 110 83 51 37 95 46 0 90 0 71 23 69 0
19 73 60 100 90 47 18 95 46 0 86 0 84 0 69 0
20 68 71 93 96 43 0 92 40 0 84 0 95 0 54 0
21 59 80 103 91 35 0 88 21 0 79 0 108 0 60 40
22 55 89 108 86 24 0 83 10 0 75 0 121 0 56 61
23 47 95 117 83 22 0 78 4 14 71 22 118 0 50 90
24 42 102 121 82 18 0 76 4 22 68 27 116 0 49 112
25 34 106 122 73 0 0 68 4 24 66 30 108 0 46 118
26 29 108 126 72 0 0 69 0 28 59 34 107 0 46 118
27 23 112 128 71 0 0 67 0 30 59 40 104 0 39 117
28 30 113 131 65 0 0 60 0 32 36 48 98 0 35 112
29 36 106 124 66 0 40 56 0 36 12 57 94 0 32 100
30 48 98 115 51 0 57 56 0 39 0 60 93 0 30 117
31 City of Santa Maria Wastewater Treatment Plant Percolation Pond Monitoring Dec 2023
Percolation Pond Height (in")
Day 1 2 3 4 5 6 7 8 11 12 13 14 15 DKC Wash
1 60 93 106 0 0 57 31 0 46 0 65 91 0 23 114
2 68 86 100 0 0 76 0 0 49 0 68 86 0 23 113
3 71 78 92 0 0 85 0 0 52 0 70 83 0 18 100
4 74 72 84 0 0 93 0 0 57 0 72 80 0 14 107
5 79 66 84 0 0 86 0 44 57 0 72 76 0 5 108
6 83 60 90 0 0 87 0 72 60 0 75 72 0 2 106
7 89 55 96 0 0 84 0 90 66 0 80 71 0 0 68
8 89 48 100 0 6 80 0 84 60 0 83 65 24 0 38
9 94 42 99 0 45 80 0 82 55 0 87 66 32 0 0
10 96 36 93 0 44 78 0 80 53 0 90 62 35 0 0
11 97 32 84 0 64 78 0 75 50 0 93 59 40 0 0
12 99 18 78 0 72 78 0 72 48 0 96 53 48 0 0
13 100 6 72 0 80 84 0 70 40 0 90 52 52 0 0
14 96 4 65 0 87 88 60 68 40 0 92 49 60 3 0
15 90 0 60 0 91 84 60 65 36 12 102 37 62 34 0
16 84 0 40 0 102 84 72 64 35 38 96 33 67 42 0
17 75 0 6 0 112 80 86 60 32 48 84 22 70 60 0
18 67 0 0 0 115 79 99 59 32 56 86 0 74 72 0
19 62 0 0 39 120 78 108 43 22 67 86 0 86 80 0
20 56 0 0 48 126 77 114 23 0 73 84 0 99 84 0
21 48 10 0 72 138 76 109 10 0 78 83 0 103 84 0
22 46 33 0 79 126 73 106 0 0 82 76 0 103 79 0
23 41 50 0 83 131 72 102 0 0 85 75 0 106 75 0
24 33 65 0 84 128 70 100 0 0 89 72 6 108 72 0
25 28 80 0 86 124 70 96 0 0 91 68 22 104 69 0
26 21 90 0 85 117 67 92 0 0 92 67 25 96 64 10
27 12 101 31 85 113 66 87 0 0 93 63 36 94 60 10
28 6 102 101 87 108 68 86 0 0 100 50 39 90 55 15
29 0 105 131 86 106 63 83 0 0 111 45 47 90 56 13
30 0 98 142 86 102 62 81 34 19 107 30 61 85 56 17
31 0 94 152 86 96 60 80 55 24 106 0 77 85 40 15
City of Santa Maria Wastewater Treatment Plant Percolation Pond Monitoring Jan 2024
Percolation Pond Height (in")
Day 1 2 3 4 5 6 7 8 11 12 13 14 15 DKC Wash
1 101 86 146 86 90 59 78 58 30 101 0 82 81 50 0
2 18 84 140 89 94 60 87 77 35 96 0 84 80 48 18
3 35 77 132 89 88 57 88 72 38 94 0 88 74 48 20
4 46 74 124 90 90 55 80 92 44 89 0 84 72 48 20
5 60 72 118 88 82 53 60 92 48 87 0 99 72 36 65
6 70 70 112 98 94 56 55 88 52 85 6 96 70 26 96
7 75 66 104 92 106 52 50 86 54 82 24 96 68 12 126
8 83 60 100 91 114 50 49 82 56 80 28 95 64 4 143
9 88 59 96 91 124 48 48 78 59 79 36 92 64 0 160
10 96 52 90 91 133 44 47 76 63 69 46 91 61 0 156
11 104 52 84 91 140 28 47 74 68 52 60 89 61 0 153
12 108 48 82 93 144 31 46 72 71 41 70 90 58 0 150
13 106 46 76 87 146 28 60 70 67 30 76 86 59 10 147
14 100 54 71 86 144 0 64 66 63 0 80 86 60 35 144
15 94 63 66 85 137 0 77 67 65 0 78 85 60 51 143
16 92 72 48 82 132 0 90 54 60 0 82 90 48 62 140
17 83 80 23 79 131 0 100 40 60 0 95 98 37 75 161
18 77 89 8 76 126 0 111 16 60 0 104 106 16 84 163
86 73 97 0 75 122 0 118 12 58 0 109 107 16 86 161
20 71 104 0 73 119 39 115 0 58 34 110 107 0 88 159
21 66 110 0 72 116 50 112 0 56 57 107 106 0 85 156
22 60 102 52 70 112 60 110 0 55 85 105 104 0 83 152
23 60 100 80 70 108 65 107 0 53 95 100 101 0 80 149
24 54 95 104 67 105 73 104 0 53 109 100 101 0 77 146
25 48 91 124 65 100 80 104 0 48 123 97 100 0 77 143
26 44 88 126 64 99 81 102 0 40 123 95 100 38 78 140
27 50 82 130 60 94 80 106 37 33 117 92 97 48 81 134
28 59 80 126 60 91 81 108 61 26 111 91 96 60 81 132
29 70 75 120 58 90 77 108 78 20 108 88 96 79 82 129
30 83 74 117 58 86 76 110 88 0 107 88 96 93 83 127
31 93 71 109 53 83 77 108 94 0 104 87 95 107 77 114
City of Santa Maria Wastewater Treatment Plant Percolation Pond Monitoring Feb 2024
Percolation Pond Height (in")
Day 1 2 3 4 5 6 7 8 11 12 13 14 15 DKC Wash
1 99 68 107 56 108 76 106 94 12 100 86 95 109 27 123
2 105 65 104 54 138 74 105 91 0 99 85 95 110 76 120
3 107 63 98 56 154 72 96 87 12 96 84 93 107 73 116
4 101 72 108 52 149 72 94 84 36 92 83 90 103 71 113
5 96 83 124 52 142 72 94 83 58 90 83 93 102 69 116
6 94 93 126 52 140 71 94 82 79 88 83 94 100 68 114
7 90 102 141 34 134 70 96 80 76 112 68 92 98 69 114
8 85 108 148 0 131 70 96 78 74 131 67 93 96 70 124
9 89 110 152 0 127 68 98 76 72 130 66 100 102 71 123
10 92 110 148 0 136 68 100 74 70 124 63 104 106 72 120
11 94 106 140 0 148 66 100 71 68 120 56 107 108 74 118
12 96 106 136 0 156 64 102 69 66 116 50 112 112 74 117
13 99 104 138 0 159 64 102 67 66 112 46 117 116 75 131
14 104 101 143 0 162 55 104 66 65 109 33 120 118 75 132 15 106 100 148 0 168 43 104 64 64 107 28 122 122 77 168 16 109 100 153 0 170 35 105 75 62 107 24 127 124 78 168 17 106 98 153 40 170 20 108 85 60 106 12 126 120 78 165 18 110 96 154 58 172 8 104 84 58 106 6 130 122 74 162
19 114 96 156 73 174 6 102 84 59 110 6 132 126 72 162
20 116 95 160 81 176 0 98 83 59 114 0 137 131 72 161
21 118 92 162 95 178 0 100 69 55 117 0 136 132 72 158
22 119 89 166 104 183 0 101 52 48 115 0 140 132 73 158
23 121 91 165 109 180 0 101 36 40 115 0 142 132 76 154
24 121 94 168 112 183 0 103 23 34 116 0 142 132 76 153
25 121 96 172 113 184 0 105 10 26 116 0 143 132 76 150
26 120 108 170 108 184 0 106 0 16 112 0 142 131 77 146
27 120 119 168 104 184 0 104 0 0 109 0 136 127 76 144
28 122 124 171 101 186 0 106 0 0 109 0 138 122 77 126
29 124 132 168 103 187 0 108 0 0 105 0 136 112 80 112
30 31
City of Santa Maria Wastewater Treatment Plant Percolation Pond Monitoring Mar 2024
Percolation Pond Height (in")
Day 1 2 3 4 5 6 7 8 11 12 13 14 15 DKC Wash
1 126 130 170 100 188 16 109 0 0 107 16 136 102 82 82
2 128 130 171 104 188 34 108 0 0 108 24 138 96 82 60
3 130 128 173 102 194 44 114 0 0 114 32 134 92 84 30
4 131 117 172 100 192 47 114 0 0 118 36 132 82 88 12
5 131 114 173 100 192 52 116 0 0 120 42 131 72 88 0
6 130 111 174 100 192 56 118 0 0 122 46 131 66 90 0
7 131 102 176 102 193 60 119 0 0 126 53 129 59 92 38
8 130 95 174 104 193 64 119 0 0 129 56 126 50 93 24
9 131 83 174 104 193 70 120 0 0 132 60 130 40 92 0
10 131 76 172 103 193 76 121 0 0 134 64 124 36 92 0
11 131 62 172 105 192 82 122 0 0 137 71 124 29 95 0
12 132 60 175 104 191 84 124 0 0 141 76 122 22 95 0
13 131 48 175 104 192 86 121 0 12 138 79 121 0 92 0
14 131 36 175 104 192 88 116 0 24 134 87 114 0 88 0
15 131 28 168 105 191 94 113 12 31 127 96 108 0 88 0
16 131 20 166 106 192 95 113 25 43 126 104 100 0 86 0
17 131 12 156 106 192 96 111 36 50 120 107 95 0 83 0
18 130 6 152 105 192 96 107 47 58 116 111 88 0 80 0
19 130 0 140 106 192 97 107 52 68 112 115 83 0 78 0
20 130 0 124 106 189 98 104 58 78 108 120 76 0 76 0
21 130 0 120 105 188 98 102 66 78 107 130 68 0 73 0
22 130 0 105 105 189 99 96 74 76 102 133 60 34 74 0
23 130 0 90 106 189 99 98 80 75 99 136 52 50 70 0
24 129 0 72 105 188 99 96 87 70 95 138 42 68 70 0
25 129 0 53 105 188 99 93 90 66 93 140 32 83 64 0
26 128 0 40 105 188 99 95 95 64 88 144 19 98 64 0
27 128 0 21 104 187 99 90 98 61 88 144 8 107 63 0
28 127 0 0 105 188 100 88 95 59 88 145 0 114 61 0
29 124 8 0 104 184 96 85 89 65 73 144 0 113 55 60
30 124 13 0 104 184 93 76 84 69 64 145 0 119 47 94
31 123 25 0 102 183 91 66 82 73 48 145 0 122 40 124
City of Santa Maria Wastewater Treatment Plant Percolation Pond Monitoring Apr 2024
Percolation Pond Height (in")
Day 1 2 3 4 5 6 7 8 11 12 13 14 15 DKC Wash
1 122 42 0 100 180 38 58 76 71 24 141 0 128 32 150
2 120 52 0 100 180 84 52 72 67 0 136 0 130 24 170
3 119 66 0 100 180 81 15 81 66 0 134 0 129 18 170
4 119 76 0 99 180 78 0 86 64 0 132 0 128 12 168
5 119 90 0 102 180 78 0 93 64 0 131 0 128 8 166
6 118 96 0 102 180 75 0 96 60 0 129 0 127 0 163
7 118 106 0 101 180 65 0 91 59 0 127 0 129 0 160
8 118 112 0 100 178 50 0 84 56 0 124 0 130 0 156
9 118 118 0 100 177 46 0 78 44 0 124 0 132 0 157
10 118 122 0 100 177 38 0 75 52 0 124 0 134 0 154
11 119 126 0 100 176 20 0 72 52 0 124 0 136 0 152
12 13
14 15
16 17
18 19
20 21
22 23
24 25
26 27
28 29
30 31

ATTACHMENT B
Daily Effluent Flow Volumes
City of Santa Maria Wastewater Treatment Plant Daily Log 2023 Methane to Boiler Sludge Pump
Dig 1 (ft3
) Dig 2 (ft3) Dig 3 (ft3) Dig 4 (ft3) 1
o 2o 1o
Meter Standby 1
o
Metered (Gallons) Flare Time
1 6.87 5,440 91,445 71,804 1 1 34700 0 0 300 54,235 300 809 2 6.99 5,600 95,615 77,439 1 1 36400 0 0 300 57,212 400 801 3 6.39 4,640 88,220 69,472 1 1 31000 0 0 200 49,502 250 900 4 7.26 5,920 101,513 84,949 1 1 34800 0 0 400 58,432 250 552 5 7.29 5,600 91,881 75,867 1 1 35600 0 0 300 49,549 300 656 6 6.99 5,760 81,476 67,457 1 1 32400 0 0 300 45,631 250 821 7 6.90 5,760 82,411 67,662 1 1 32900 0 0 300 49,919 200 756 8 6.87 5,760 78,461 67,898 1 1 32400 0 0 300 52,432 250 805 9 6.75 5,920 89,145 77,077 1 1 34300 0 0 300 52,785 200 740 10 6.42 5,280 79,252 70,888 1 1 31300 0 0 200 46,537 200 800 11 6.51 5,760 87,236 76,306 1 1 35200 0 0 300 52,393 175 540 12 6.85 6,080 87,669 77,449 1 1 37800 0 0 400 53,930 175 600 13 6.54 5,120 71,244 62,821 1 1 33000 0 0 300 43,870 150 755 14 7.10 6,240 84,095 73,960 1 1 38200 0 0 300 50,361 150 605 15 6.61 5,440 81,631 67,665 1 1 35700 0 0 300 49,492 200 750 16 6.90 5,600 93,042 78,955 1 1 36300 0 0 300 53,857 150 755 17 6.57 4,960 84,259 68,806 1 1 32900 0 0 300 45,556 180 800 18 6.91 5,760 95,196 74,577 1 1 40100 0 0 300 53,200 100 648 19 6.80 5,760 87,413 71,730 1 1 37000 0 0 300 49,631 150 835 20 6.88 5,920 86,607 69,767 1 1 35000 0 0 300 51,628 170 830 21 6.91 5,760 89,244 68,678 1 1 35600 0 0 300 51,003 100 814 22 6.49 5,120 81,241 58,524 1 1 30100 0 0 200 46,296 175 759 23 6.43 5,600 95,302 71,456 1 1 34700 0 0 300 50,767 100 609 24 6.39 6,720 101,733 82,719 1 1 40700 0 0 400 58,930 100 507 25 6.32 5,600 89,684 67,716 1 1 35400 0 0 300 51,521 170 745 26 6.68 6,080 91,753 72,418 1 1 38400 0 0 300 50,136 150 800 27 6.70 5,760 77,621 73,637 1 1 35900 0 0 300 46,821 130 800 28 6.97 6,240 74,691 52,169 1 1 36700 0 0 300 30,618 160 815 29 6.53 5,760 68,231 53,708 1 1 35400 0 0 300 44,902 200 840 30 6.70 5,920 83,463 79,008 1 1 37400 0 0 300 50,678 100 815 AVE. 6.75 5696 86359 71086 35243 50061 186
H2S Readings

NOV WWTP
(MGD)
Elec. Usage
(kwh)
Digester Gas Production Gas Flares Propane to Boiler Flare Propane
City of Santa Maria Wastewater Treatment Plant Daily Log 2023 Methane to Boiler Sludge Pump
Dig 1 (ft3
) Dig 2 (ft3) Dig 3 (ft3) Dig 4 (ft3) 1
o 2o 1o
Meter Standby 1
o
Metered (Gallons) Flare Time
1 6.35 5440 79220 66,476 1 1 32700 0 0 300 47,278 150 810 2 6.49 6240 96219 83,326 1 1 42700 0 0 300 55,053 125 559 3 6.66 6080 96256 81,087 1 1 40700 0 0 300 54,156 200 751 4 6.75 5920 88475 72,182 1 1 37100 0 0 300 51,231 200 839 5 6.88 6080 92759 78,493 1 1 39400 0 0 300 54,540 200 730 6 6.53 5600 87578 71,042 1 1 37200 0 100 300 53,495 200 801 7 6.60 5920 95320 74,351 1 1 38900 0 0 300 55,960 200 755 8 6.34 5600 89026 70,799 1 1 38000 0 0 300 52,648 175 801 9 6.23 5920 96540 72,143 1 1 36900 0 0 300 57,078 200 734 10 6.58 6080 90160 76,975 1 1 40300 0 0 300 54,199 200 800 11 6.60 5600 77708 65,910 1 1 39300 0 0 300 48,854 150 823 12 6.74 6080 81800 68,094 1 1 39200 0 0 300 55,955 100 819 13 6.43 5280 83586 71,025 1 1 39900 0 0 300 55,282 200 802 14 6.59 5600 88668 70,876 1 1 39600 0 0 300 52,106 150 811 15 6.11 4960 78549 66,643 1 1 34600 0 0 200 44,882 125 820 16 6.21 5600 90728 77,356 1 1 40700 0 0 400 52,266 100 530 17 7.69 5920 89109 76,340 1 1 42100 0 0 300 55,706 125 632 18 6.71 5440 79680 65,641 1 1 35100 0 0 300 46,287 120 820 19 6.67 5440 86860 66,442 1 1 31700 0 0 300 52,178 150 805 20 8.16 5600 53123 64,524 1 1 38500 0 0 300 52,950 150 800 21 8.07 5760 89700 76,600 1 1 33100 0 0 300 53,558 200 744 22 6.63 5280 85021 70,333 1 1 36600 0 0 200 48,597 150 813 23 6.32 5440 87441 68,117 1 1 37400 0 0 300 49,367 150 646 24 6.14 5600 82281 72,158 1 1 37600 0 0 300 51,021 150 626 25 5.70 5920 86564 76,788 1 1 41200 0 0 300 56,110 150 640 26 6.20 5600 84821 65,316 1 1 35600 0 0 300 50,351 140 800 27 6.20 5920 77443 65,046 1 1 38000 0 0 300 49,776 200 815 28 5.60 6080 93370 80,599 1 1 38700 0 0 300 54,001 160 840 29 7.40 5760 88503 75,399 1 1 31800 600 0 200 54,844 170 810 30 6.70 8640 85220 74,837 1 1 0 7500 0 300 51,430 150 745 31 6.40 3360 84753 73,893 1 1 0 7800 0 300 50,758 150 755 AVE. 6.60 5734 86016 72220 35310 52320 161
H2S Readings

DEC WWTP
(MGD)
Elec. Usage
(kwh)
Digester Gas Production Gas Flares Propane to Boiler Flare Propane
City of Santa Maria Wastewater Treatment Plant Daily Log 2024 Methane to Boiler Sludge Pump
Dig 1 (ft3
) Dig 3 (ft3) Dig 4 (ft3) 1
o 2o 1o
Meter Standby 1
o
Metered (Gallons) Flare ppm Time
1 5.40 35 76,667 65,443 1 1 0 7200 0 300 47,278 150 745 101 2 6.50 34 80,426 65,770 1 1 0 6800 0 300 50,062 180 800 101 3 6.30 36 79,214 61,574 1 1 0 6400 0 300 49,523 215 815 109 4 6.12 33 86,260 69,653 1 1 0 7000 0 200 52,155 175 800 109 5 5.88 30 76,468 65,000 1 1 24,900 1600 0 300 68,683 175 821 124 6 5.20 37 92,062 76,249 1 1 38,200 0 0 300 29,299 200 532 101 7 6.94 38 91,618 76,247 1 1 40,100 0 0 300 56,441 180 635 109 8 6.33 38 81,909 68,138 1 1 36,400 0 0 300 46,111 150 850 117 9 6.21 38 83,470 67,966 1 1 38,100 0 0 300 49,323 180 811 94 10 6.23 37 79,218 67,711 1 1 39,800 0 0 300 52,785 200 813 104 11 6.08 38 82,586 76,238 1 1 35,500 0 0 200 49,576 200 854 109 12 5.99 38 84,315 72,155 1 1 35,300 0 0 300 48,935 200 820 109 13 6.10 36 76,010 62,637 1 1 35,400 0 0 300 43,015 200 810 101 14 5.98 37 72,704 62,712 1 1 37,000 0 0 300 52,953 140 810 109 15 6.55 35 83,110 67,344 1 1 39,100 0 0 300 54,625 150 820 109 16 6.32 36 81,921 63,921 1 1 37,800 0 0 200 37,858 200 820 125 17 6.04 36 76,531 61,723 1 1 38,000 0 0 300 52,720 200 755 72 18 6.06 36 89,864 76,480 1 1 41,100 0 0 300 56,417 100 735 109 19 5.96 33 87,026 73,669 1 1 38,500 0 0 300 54,765 150 805 121 20 6.31 34 92,985 76,024 1 1 40,200 0 0 300 58,932 175 722 115 21 6.76 36 90,465 75,262 1 1 40,900 0 0 200 61,646 125 743 125 22 6.48 33 77,271 65,482 1 1 37,600 0 0 300 51,924 175 831 127 23 6.53 37 66,329 52,622 1 1 39,400 0 0 300 51,474 150 608 109 24 6.89 44 82,261 64,305 1 1 43,500 0 0 300 60,812 150 613 101 25 6.17 36 63,675 56,881 1 1 37,800 0 0 300 55,421 125 850 125 26 6.21 36 88,028 68,836 1 1 38,900 0 0 300 56,073 100 812 117 27 6.17 37 95,932 75,059 1 1 38,500 0 0 300 56,399 125 813 121 28 6.53 37 85,129 68,813 1 1 11,100 500 0 300 56,416 150 825 121 29 6.48 35 90,349 68,403 1 1 34,400 1400 0 200 57,360 175 825 119 30 6.08 39 88,568 78,729 1 1 45,300 0 0 300 60,306 200 844 121 31 7.28 38 79,656 72,285 1 1 31,600 400 0 300 47,126 150 834 125 AVE. 6.26 36 82646 68495 32077 52465 112
Ferrous
Chloride
Gal
Digester Gas Production H2S Readings JAN WWTP
(MGD)
Elec. Usage
(kwh)
Gas Flares Propane to Boiler Flare
Propane
City of Santa Maria Wastewater Treatment Plant Daily Log 2024 Methane to Boiler Sludge Pump
Dig 1 (ft3
) Dig 3 (ft3) Dig 4 (ft3) 1
o 2o 1o
Meter Standby 1
o
Metered (Gallons) Flare ppm Time
1 6.26 31 77,360 53,017 1 1 39300 300 0 300 45,121 175 830 94 2 6.45 41 91,213 68,239 1 1 11200 5300 0 300 50,013 150 745 94 3 6.51 28 94,347 75,702 1 1 0 8500 0 300 53,384 125 700 109 4 7.11 37 102,227 79,069 1 1 0 9500 0 300 56,252 100 720 113 5 7.63 37 82,136 66,425 1 1 34800 1400 0 200 51,372 150 845 117 6 6.78 34 84,032 64,027 1 1 36800 0 0 300 46,713 125 827 101 7 7.74 42 106,184 75,311 1 1 45800 0 0 300 57,862 175 543 101 8 6.96 39 94,016 73,403 1 1 38000 0 0 300 53,611 150 800 125 9 6.30 39 84,217 60,732 1 1 32500 0 0 300 46,303 125 801 113 10 6.95 38 87,230 68,430 1 1 36200 0 0 300 52,476 125 543 101 11 7.15 42 97,308 74,139 1 1 38300 0 0 300 54,616 100 629 109 12 6.35 32 78,866 62,888 1 1 32500 0 0 300 48,430 125 800 109 13 7.10 41 97,164 73,438 1 1 37900 0 0 300 55,031 200 624 98 14 6.39 35 81,373 70,704 1 1 36800 100 0 300 47,912 175 839 105 15 6.62 36 81,926 70,584 1 1 38500 0 0 300 48,620 150 820 98 16 6.32 31 71,619 62,298 1 1 32900 0 0 200 41,865 150 802 99 17 6.84 35 82,229 67,133 1 1 36300 0 0 300 47,856 175 508 86 18 8.42 40 95,449 77,874 1 1 38300 0 0 400 60,362 200 953 96 19 7.74 37 79,769 68,812 1 1 36400 0 0 300 51,567 175 826 121 20 7.02 38 91,859 69,021 1 1 38900 0 0 300 49,780 200 756 101 21 7.02 38 88,947 75,705 1 1 38800 0 0 300 53,228 200 801 101 22 6.64 37 93,245 70,909 1 1 37400 0 0 300 56,362 200 759 109 23 6.53 38 89,989 79,544 1 1 37400 0 0 300 60,934 225 809 117 24 6.64 35 93,548 78,967 1 1 37600 0 0 300 60,893 225 739 121 25 6.79 39 97,901 81,304 1 1 42700 0 0 300 67,660 225 702 125 26 6.89 36 88,813 78,702 1 1 40300 0 0 300 62,730 250 802 137 27 6.85 37 93,629 75,002 1 1 45000 0 0 300 60,437 250 802 125 28 6.71 35 85,107 72,530 1 1 43800 0 0 300 58,062 300 811 119 29 6.63 35 88,761 74,067 1 1 34600 0 0 300 54,769 250 811 113 AVE. 6.87 37 88982 71310 34448 53594 109
Ferrous
Chloride
Gal
H2S Readings

FEB WWTP
(MGD)
Elec. Usage
(kwh)
Digester Gas Production Gas Flares Propane to Boiler Flare Propane
City of Santa Maria Wastewater Treatment Plant Daily Log 2024 Methane to Boiler Sludge Pump
Dig 1 (ft3
) Dig 3 (ft3) Dig 4 (ft3) 1
o 2o 1o
Meter Standby 1
o
Metered (Gallons) Flare ppm Time
1 7.00 32 77,406 59,390 1 1 30400 0 0 300 47,469 225 746 113.1 2 7.12 36 92,389 70,938 1 1 37800 0 0 300 53,059 175 445 101.4 3 7.11 38 108,466 86,091 1 1 42300 0 0 300 62,385 225 500 109.2 4 6.92 39 87,441 72,806 1 1 35700 0 0 300 44,623 225 844 124.8 5 6.71 37 82,911 70,089 1 1 35500 0 0 300 47,190 200 820 97.5 6 7.28 39 81,464 69,546 1 1 36900 0 0 300 55,573 300 751 101.4 7 6.71 38 95,353 78,706 1 1 36100 0 0 300 56,433 250 828 117 8 6.58 37 86,607 72,250 1 1 34000 0 0 300 50,780 225 815 120.9 9 6.55 36 90,095 70,583 1 1 34900 0 0 300 50,629 250 700 109.2 10 6.57 39 92,762 78,175 1 1 37000 0 0 300 54,213 200 730 109.2 11 6.53 32 84,528 66,157 1 1 32100 0 0 200 46,524 300 820 117 12 6.77 37 88,079 74,371 1 1 37800 0 0 400 55,552 300 517 101.4 13 7.05 39 86,963 77,523 1 1 40800 0 0 300 59,770 300 558 124.8 14 6.49 34 83,363 71,758 1 1 33100 0 0 200 50,128 225 825 127.5 15 6.59 34 90,529 73,203 1 1 35400 0 0 300 54,133 200 550 113.1 16 6.57 36 94,953 80,193 1 1 37700 0 0 300 56,934 225 549 124.8 17 7.18 38 93,850 80,017 1 1 38900 0 0 300 56,172 225 639 128.7 18 6.20 34 75,392 65,863 1 1 31600 0 0 200 45,030 225 833 120.9 19 6.85 38 86,470 71,224 1 1 35800 0 0 300 53,830 200 554 101.4 20 7.07 41 94,277 74,653 1 1 36800 0 0 400 65,192 300 609 120.9 21 6.77 37 100,184 82,824 1 1 33300 0 0 200 58,277 200 809 144.3 22 6.49 34 91,467 71,140 1 1 28800 0 0 300 53,495 300 759 132.6 23 6.83 37 100,710 80,652 1 1 34700 0 0 300 62,355 225 555 117 24 6.67 37 86,452 73,169 1 1 34500 0 0 300 58,128 300 620 132.6 25 6.63 38 82,204 70,329 1 1 36900 0 0 300 55,892 300 620 128.7 26 6.63 40 81,427 67,580 1 1 36600 0 0 300 51,804 250 610 117 27 6.53 36 79,464 63,000 1 1 36900 0 0 300 51,593 320 543 117 28 6.73 41 93,866 81,485 1 1 37600 0 0 300 52,333 275 600 113.1 29 6.75 35 76,184 61,746 1 1 30900 0 100 300 46,896 250 753 117 30 6.94 37 82,976 66,959 1 1 32800 100 0 300 49,898 290 646 105.3 31 6.94 39 84,060 71,076 1 1 35900 0 0 300 50,222 290 714 111.15 AVE. 6.77 37 88138 72693 35468 53436 117
Ferrous
Chloride
Gal
H2S Readings

MAR WWTP
(MGD)
Elec. Usage
(kwh)
Digester Gas Production Gas Flares Propane to Boiler Flare Propane
City of Santa Maria Wastewater Treatment Plant Daily Log 2024 Methane to Boiler Sludge Pump
Dig 1 (ft3
) Dig 3 (ft3) Dig 4 (ft3) 1
o 2o 1o
Meter Standby 1
o
Metered (Gallons) Flare ppm Time
1 6.65 36 87,914 71,051 1 1 34,400 0 0 300 51,128 310 756 111.15 2 6.52 34 81,040 67,798 1 1 31,500 0 0 300 43,735 300 752 120.9 3 6.46 33 87,646 68,117 1 1 35,500 0 0 300 52,557 350 551 105.3 4 6.19 39 100,998 81,657 1 1 36,900 0 0 300 60,025 275 619 117 5 7.70 34 81,025 70,467 1 1 31,900 0 0 300 54,636 275 812 140.4 6 6.71 42 89,100 77,400 1 1 34,300 0 0 200 57,972 225 620 121 7 6.73 31 93,345 76,937 1 1 35,100 0 0 400 53,860 225 615 132.6 8 6.61 38 83,228 69,145 1 1 32,000 0 0 200 51,718 200 745 124.8 9 6.42 36 84,075 66,648 1 1 30,800 0 0 300 50,614 225 735 109.2 10 6.50 36 90,898 69,340 1 1 35,300 0 0 300 55,484 300 554 113.1 11 6.90 42 98,733 80,272 1 1 38,500 0 0 300 60,534 300 530 124.8 12 6.37 37 78,603 63,119 1 1 34,300 0 0 300 56,319 225 805 132.6 13 7.68 35 85,308 64,956 1 1 33,900 0 0 300 54,273 200 740 124.8 14 15
16 17
18 19
20 21
22 23
24 25
26 27
28 29
30 AVE. 6.73 36 87839 71301 34185 54066 121
Ferrous
Chloride
Gal
H2S Readings

APR WWTP
(MGD)
Elec. Usage
(kwh)
Digester Gas Production Gas Flares Propane to Boiler Flare Propane
VOLUME 7 / CHAPTER 2: EFFLUENT DISPOSAL
JANUARY 2026 / DRAFT FINAL / CAROLLO

CITY OF SANTA MARIA

SANTA MARIA WWTP PROGRAM MANAGEMENT SERVICES

APPENDIX E SUMMARY OF PRIOR POND

REHABILITATION WORK AND

COST ESTIMATES FOR SOIL CLEANING
1 Summary of Prior Pond Rehabiliation Work and Cost Estimates for Soil Cleaning 2 The following assumptions were used to develop the budget costs shown in the table above:

1. Process water for the screening/cleaning operation will be provided to the contractor by the City.

2. The City will identify a laydown and decanting/sludge pond area that can be used.

3. Sludge/ fines can be disposed of on-site and no offsite hauling is anticipated.

4. The contractor would be working at Prevailing Wage rates.

5. The City will have pond(s) dried out so that equipment can traverse bottom of ponds.

6. Mobilization/Demobilization and Set up of screening/cleaning plant estimated at $200,000. Note that this amount has been added to the cost for each pond to provide a conservative cost.

7. Upper 5 feet of pond soil to be processed and placed back in the same pond after screening.

VOLUME 7 / WATER REUSE AND LIQUID DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA

WASTEWATER TREATMENT PLANT MASTER PLAN

APPENDIX F SUMMARY OF PRIOR POND

REHABILITATION WORK AND

COST ESTIMATES FOR SOIL CLEANING
1 Summary of Prior Pond Rehabiliation Work and Cost Estimates for Soil Cleaning 2 The following assumptions were used to develop the budget costs shown in the table above: 1. Process water for the screening/cleaning operation will be provided to the contractor by the City. 2. The City will identify a laydown and decanting/sludge pond area that can be used.

3. Sludge/
fines can be disposed of on-site and no o
Ưsite hauling is anticipated.

4. The contractor would be working at Prevailing Wage rates. 5. The City will have pond(s) dried out so that equipment can traverse bottom of ponds. 6. Mobilization/Demobilization and Set up of screening/cleaning plant estimated at $200,000. Note that this amount has been added to the cost for each pond to provide a conservative cost. 7. Upper 5 feet of pond soil to be processed and placed back in the same pond after screening.

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 8: Biosolids Handling
and Disposal
FINAL / October 2026

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 8: Biosolids Handling
and Disposal
FINAL / October 2026
Digitally signed by Graham J.G. Juby
Contact Info: Carollo Engineers, Inc.

Date: 2026.10.24 11:21:00-07'00'
Digitally signed by Daniel L. Meacham
Contact Info: Carollo Engineers, Inc.

Date: 2026.10.25 08:39:03-05'00'
VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN i
pw://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/Master Plan/Volume 8/Ch01 Contents
CHAPTER 1 BIOSOLIDS HANDLING AND DISPOSAL

1.1 Introduction 1-1

1.2 Background 1-1

1.3 Current and Future Regulations 1-2

1.3.1 Wastewater Solids Regulations 1-2

1.3.2 Future Trends 1-9

1.3.3 Treatment Implications 1-10

1.4 Biosolids Production by Treatment Alternative 1-10

1.4.2 Comparison of Alternatives 1-12

1.5 Hauling and Disposal Alternatives 1-12

1.5.1 Current Co-Disposal 1-13

1.5.2 E&G Only 1-13

1.5.3 Additional Disposal Options 1-14

1.5.4 Additional Considerations 1-14

1.6 Conclusions and Findings 1-16
Appendices
APPENDIX A TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES

APPENDIX B ISHIGAKI PILOT TESTING REPORT
Tables
Table 1.1 Summary of City's Biosolids Reporting Data (2018-2023) 1-1 Table 1.2 EPA 40 CFR 503 Pathogen Reduction Requirements for Class A and Class B Biosolids 1-4
Table 1.3 EPA 40 CFR 503 Vector Attraction Reduction Requirements for Biosolids 1-4 Table 1.4 EPA 40 CFR 503 Metal Concentration Limits for Beneficial Use of Biosolids 1-5 Table 1.5 Treatment Technologies Considered and the Defined PSRP to Meet Class B 1-6 Table 1.6 Estimated Biosolids Production for Alternatives Producing Sub-Class B Biosolids 1-11
Table 1.7 Estimated Biosolids Production for Alternatives Producing Class B Biosolids 1-11 Table 1.8 Comparison of Biosolid Production of Alternatives 1-12 Table 1.9 Cost of Co-Disposal of Biosolids 1-13
Table 1.10 Cost of E&G Only Disposal of Biosolids 1-13
Table 1.11 Cost of Biosolids Disposal at Synagro Facilities 1-14 Table 1.12 Summary of Biosolids Handling and Disposal Alternatives 1-17 Figures
Figure 1.1 Current Status of County Ordinances Affecting the Use of Biosolids 1-9 VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN ii
Abbreviations
ADC alternative daily cover
C Celsius
CCL ceiling concentration limits
CFU colony forming unit
City City of Santa Maria
CPLR cumulative pollutant loading rate
CWEA California Water Environment Association
DWQ Division of Water Quality
E&G Engel and Gray
EPA Environmental Protection Agency
FOG fats, oils, and grease
gpm gallons per minute
kg kilogram
lb/day pounds per day
M million
mg/kg milligram per kilogram
mg/l milligrams per liter
mgd million gallons per day
MLE Modified Ludzak-Ettinger
MMBTU million British thermal units
MPN most probable number
N/A not applicable
O&M operations and maintenance
PCL pollutant concentration limits
PFAS per- and polyfluoroalkyl substances
PFRP processes to further reduce pathogens
PFU plaque forming unit
PR pathogen reduction
PS primary sludge
PSRP processes to significantly reduce pathogens
RWQCB Regional Water Quality Control Board
SB Senate Bill
SKIC Synagro Kern Industrial Center
SRT solids retention time
SWRCB State Water Resources Control Board
TM Technical Memo
TN total nitrogen
VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN iii
TS total solids
VAR vector attraction reduction
WAS waste activated sludge
WDR waste discharge requirement
WWTP wastewater treatment plant
VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-1
CHAPTER 1 BIOSOLIDS HANDLING AND DISPOSAL

1.1 Introduction
The City of Santa Maria (City) wastewater treatment plant (WWTP) produces over 3,500 wet tons of Class B biosolids annually, resulting from its existing solids treatment processes. As part of the Phase 1 WWTP expansion project, the City is evaluating several solids treatment configurations to bring the plant into compliance with the new effluent discharge requirements that include reducing the total nitrogen (TN) concentration to below 10 milligrams per liter (mg/L). This chapter provides an overview of biosolids as a byproduct of wastewater treatment and assesses existing and potential future biosolids-related practices and regulations to identify drivers for various solids management approaches. Biosolids handling and disposal methods will be evaluated for each of the liquid treatment alternatives presented in Chapter 1 of Volume 6 in the Master Plan based on its sustainability, cost-effectiveness, and regulation-compliant disposal methods. Technical Memorandum (TM) 2 - Energy and Solids Evaluation for Bardenpho Alternatives (Appendix A) includes detailed assumptions and cost estimates that are referenced in this chapter.

1.2 Background
The existing sludge processing system at the City's WWTP includes gravity thickening, anaerobic digestion, and sludge drying beds. The current anaerobic digestion treatment meets a minimum solids retention time (SRT) of 15 days, which produces a Class B solids product.

Currently, the City disposes of its biosolids at the City's landfill and the Engel and Grey (E&G) composting facility, which are licensed to accept Class B solids for disposal. E&G's composting facility is adjacent to the treatment plant and provides a convenient and economical solution to biosolids disposal. With the exception of E&G, the City's landfill is closer than any current alternative for disposal and has significant cost savings for the City. The City's annual biosolids reporting data from 2018 to 2023 includes the average biosolids production, disposal location, and hauling and tipping fees. In 2023, about 30 percent of the biosolids went to the City landfill, and the remainder was composted. This information is summarized in Table 1.1 together with the annual costs.

Table 1.1 Summary of City's Biosolids Reporting Data (2018-2023) Year
E&G City Landfill
Total Annual
Cost (USD)
Fee
(USD/
Wet Ton)
Annual Cake
Processed
(Wet Tons)
Annual Cost
(USD)
Fee
(USD/
Wet Ton)
Annual Cake
Processed
(Wet Tons)
Annual Cost
(USD)
2019 $33.91 2295.09 $77,826.50 $26.6 1027.21 $27,354.60 $105,181.10 2020 $33.91 2036.26 $69,049.58 $26.63 652.67 $17,380.60 $86,430.18 2021 $33.91 2269.82 $76,969.60 $26.63 316.5 $8,428.40 $85,397.99 2022 $33.91 3320.46 $112,596.80 $26.63 1352.47 $36,016.28 $148,613.07 2023 $33.91 2530.22 $85,799.76 $26.63 996.54 $26,537.86 $112,337.62 Average Annual Cost $110,706.07
VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-2
The wet tonnage of biosolids shown in Table 1.1 is an estimate provided in the City's annual anaerobic digester analysis summary, which assumes a 30 percent moisture content when calculating wet tonnage of biosolids. Due to the favorable weather in Santa Maria, the existing sludge drying beds are able to achieve 70 percent total solids content in dewatered cake.

Looking to the future, several of the liquid treatment alternatives evaluated in Volume 6 of the Master Plan shift biosolids quantity and quality to produce sub-Class B biosolids. Because E&G operates under the General Waste Discharge Requirements for Commercial Composting Operations (Order WQ 2020- 0012-DWQ) by the State Water Resources Control Board (SWRCB), their permit requires that biosolids are treated to a minimum of Class B standards prior to acceptance at the composting facility. The same constraint is true for the City's landfill, requiring the ability to produce a Class B biosolid as a key constraint when evaluating treatment alternatives. Additionally, there is uncertainty regarding the long-term availability of the existing composting facility and landfill as disposal options for the City.

Refer to Appendix A for a detailed summary of current operational practices, historical biosolids volumes, and existing conditions.

1.3 Current and Future Regulations
Assessment of both current and anticipated future regulatory requirements is critical for the development of effective long-term biosolids management alternatives. This section summarizes current regulatory requirements and considerations that impact the operation of the City's WWTP solids processing today, as well as proposed regulations that will impact the facility operations within the planning horizon of the Master Plan. The regulatory summary includes a comprehensive review of the current regulations governing solids treatment and end use. Potential impacts of future regulations are also considered.

1.3.1 Wastewater Solids Regulations
 Federal, state, and local regulations determine whether biosolids from wastewater treatment plants can be beneficially used or must be disposed of. At the federal level, biosolids regulations are well established, with few changes anticipated in the planning horizon. In contrast, at the state level, anticipated changes to California's biosolids regulations will influence biosolids management options, making the development and execution of a flexible management program essential.  A summary of relevant federal, state, and local regulations is provided in the following sections. The specific relevance of regulations depends on the intended beneficial end use or disposal method, which dictates the level of treatment required and the resulting product classification (Class A, Class B, or Sub-Class B).

1.3.1.1 Federal
Federal, state, and local agencies are responsible for regulating beneficial use/disposal of biosolids. Each agency's required level of treatment varies based on the beneficial use/disposal methods employed.

However, key minimum guidelines are established by the Environmental Protection Agency (EPA) that must be implemented by state and local governments. In California, state and local agencies have developed additional rules, guidelines, and criteria for biosolids management.

In order to implement a long-term biosolids program required by the Water Quality Act of 1987, EPA initiated two rulemakings resulting in the promulgation of 40 CFR 503 (the Rule or Regulation), Standards VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-3
for the Use or Disposal of Sewage Sludge. The regulation establishes requirements, procedures, operational standards, and management practices for:
 Biosolids management in waste discharge requirement (WDR) permits.  Implementing federal biosolids permit programs, if a state so chooses.  Granting state biosolids management programs primacy over federal program.  Land application of sewage sludge (which is biosolids in this context) for beneficial use.  Surface disposal in a monofill, surface impoundment, or other dedicated site.  Incineration of sewage sludge with or without auxiliary fuel.  For additional details on federal regulations that impact treatment and disposal of biosolids generated at Santa Maria WWTP, refer to Chapter 4 of Volume 2 in the Master Plan.

EPA 40 CFR 503 Regulations
The EPA's 40 CFR 503 regulations establish biosolids quality standards based on three parameters:
pathogen reduction (PR), vector attraction reduction (VAR), and pollutant (metals) concentration. The regulation applies to non-hazardous wastewater solids that are applied to land, fired in a sewage sludge incinerator, or placed on a surface disposal site. Based on the three parameters, the EPA classifies biosolids into Class B, Class A, and Exceptional Quality Biosolids.

Pathogen reduction alternatives are designed to reduce the concentration of pathogens (organisms capable of causing diseases pathogens) in biosolids. The 40 CFR 503 Class A and Class B PR requirements for land-applied biosolids are summarized in Table 1.2. For a product to be classified as Class A or Class B, it must meet each of the major bullets outlined in Table 1.2. Sub-Class B biosolids are those that do not meet the minimum requirements of the Class B designation. This can include biosolids that range from untreated to insufficiently treated to meet these minimum requirements. The City's WWTP currently meets PR requirements through anaerobic digestion to produce Class B biosolids.

VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-4
Table 1.2 EPA 40 CFR 503 Pathogen Reduction Requirements for Class A and Class B Biosolids Class A Class B
Either fecal coliform density in the sewage sludge is less than 1,000 MPN/gram of total solids (dry weight basis). Or the density of Salmonella species bacteria in the sewage sludge is less than 3 MPN/4 grams of total solids (dry
weight basis).

Sewage sludge must be treated and/or meet one of the
following alternatives before us or disposal. For more
details on each treatment alternative, refer to
40 CFR 503.32(a):

1. Thermally treated.

2. High pH-high temperature treatment.

3. Treatment to reduce enteric virus to less than 1 PFU per 4 grams of total dry solids and viable helminth ova to less than one per four grams of total dry solids.

4. Processes to further reduce pathogens (PFRP) include treatment by composting, heat drying, heat treatment,
thermophilic aerobic digestion, beta ray irradiation,
gamma ray irradiation, or pasteurization. Specific
operating conditions for each process have been
specified in 40 CFR 503.32(a).

5. Use of processes equivalent to the above (subject to authority approval).

Comply with site restrictions of land application as specified in 40 CFR 503.32(b)(2), (b)(3), or (b)(4). In summary, these restrictions limit access to animals and the public on sites where Class B material was applied.

Sewage sludge must be treated and/or meet one of the
following alternatives before use or disposal. For more details on each treatment alternative, refer to
40 CFR 503.32(b):

1. Geometric mean of seven samples of treated sewage
sludge collected at the time of use or disposal shall
meet a fecal coliform density of 2 million CFU or
MPN/gram of total solids (dry weight basis).

2. Processes to significantly reduce pathogens (PSRP),
which include aerobic digestion, air drying, anaerobic
digestion, composting, or lime stabilization. Specific
operating conditions for each process have been
specified in 40 CFR 503.32(b).

3. Use of processes equivalent to the above (subject to authority approval).

Notes:

CFU - colony forming unit; MPN - most probable number; PFRP - processes to further reduce pathogens; PFU - plaque forming unit; PSRP - processes to significantly reduce pathogens Vector attraction reduction options are designed to reduce the transport of pathogens by vectors (i.e., flies, mosquitoes, fleas, rodents, and birds) from biosolids to other animals or humans. VAR requirements are summarized in Table 1.3 and include process methods (i.e., chemical or biological reduction [Options 1-8]) or barrier methods (i.e., physically blocking biosolids from vectors [Options 9-10]). The City's WWTP currently meets VAR requirements through Alternative 1 in Table 1.3.

Table 1.3 EPA 40 CFR 503 Vector Attraction Reduction Requirements for Biosolids Alternative No. in
40 CFR 503.33(b) Description
1 Meet 38 percent reduction in volatile solids content. 2 Demonstrate vector attraction reduction with additional anaerobic digestion in a bench-scale unit.
3 Demonstrate vector attraction reduction with additional aerobic digestion in a bench-scale unit. 4 Meet a specific oxygen uptake rate for aerobically digested biosolids. 5 Use aerobic processes at greater than 40 degrees C for 14 days or longer. 6 Alkali addition under specified conditions.
7 Dry biosolids (with no unstabilized solids) to at least 75 percent solids. 8 Dry biosolids (with unstabilized solids) to at least 90 percent solids.

VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-5
Alternative No. in
40 CFR 503.33(b) Description
9 Inject biosolids beneath the soil surface.
10 Incorporate biosolids into the soil within six hours of application to or placement on the land. 11 Cover biosolids placed on a surface disposal site with soil or other material at the end of each operating day. (Note: only for surface disposal).
12 Alkaline treatment of domestic septage to pH 12 or above for 30 minutes without adding more alkaline material.

Notes:

C - Celsius
Currently, biosolids from the Santa Maria WWTP are not required to be tested for metals for disposal at a composting facility or the City's landfill; however, if alternative disposal options are pursued, metal testing may become required. If required, biosolids must, at a minimum, meet metal concentration limits, referred to as ceiling concentration limits (CCL), to be beneficially used. If land applying, the biosolids must meet either the pollutant concentration limits (PCL) or the cumulative pollutant loading rate (CPLR) limits.

Table 1.4 summarizes the pollutant limits required by 40 CFR 503 to beneficially use biosolids.

Table 1.4 EPA 40 CFR 503 Metal Concentration Limits for Beneficial Use of Biosolids Pollutant EPA CCL mg/kg
Dry Weight Basis
EPA PCL, mg/kg
Dry Weight Basis
EPA CPLR Limit,
kg per hectare
Arsenic 75 41 41
Cadmium 85 39 39
Copper 4,300 1,500 1,500
Lead 840 300 300
Mercury 57 17 17
Molybdenum 75 - -
Nickel 420 420 420
Selenium 100 100 100
Zinc 7,500 2,800 2,800
Applicable to: Land applied material Bulk and bagged material Bulk material Notes:
kg - kilogram; mg/km - milligram per kilogram
In addition to the requirements above, 40 CFR 503 provides guidance on best practices for land application of biosolids, provides site restrictions for each type of biosolids, and sets the requirements for monitoring, recordkeeping, and reporting. These apply to both the supplier and application of biosolids (which could be a third party).

Class B Biosolids
Class B biosolids are treated with processes intended to significantly reduce, but not eliminate, pathogens.

As such, biosolids may be land applied, but land appliers must also follow application restrictions for Class B biosolids with regard to public contact, animal forage, and production of crops for human VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-6
consumption. The waiting periods are intended to further reduce pathogens such that they are comparable to Class A. In short, Class B + Management practices = Class A. For example:
 Class B biosolids may only be applied to sites where there is no possibility of contact with the general public for a period of one year. These sites include specific types of agriculture, land reclamation, landfills, etc.
 Crop harvesting, animal grazing, and public access are restricted for a defined period of time until environmental conditions have further reduced pathogens.

Class B biosolids can be produced through the three Alternatives defined in Table 1.2, and in order to be land applied, must also meet VAR and pollutant standards previously defined. As mentioned above, the City's WWTP currently meets Class B through anaerobic digestion. Additionally, the alternatives considered in the Master Plan include several PSRPs as listed in Table 1.2: mesophilic anaerobic digestion, aerobic digestion, and sludge drying beds. Table 1.5 summarizes the requirements of these PSRPs to meet Class B requirements for biosolids.

Table 1.5 Treatment Technologies Considered and the Defined PSRP to Meet Class B Treatment Technology Requirements for Class B
Aerobic Digestion
The process must be operated for at least 40 days at 20 degrees C or at least 60 days at 15 degrees C for single-stage aerobic digestion to meet Class B standards. These times and temperatures can be reduced with staged aerobic digestion.

Mesophilic Anaerobic Digestion The process must be operated between 15 days at 35 to 55 degrees C and 60 days at 20 degrees C to meet Class B standards.

Sludge Drying Beds
The process is required to retain sludge for a minimum of 3 months, where the final month must have an average daily temperature above 0 degrees C.

Sub-Class B Biosolids
Under the 40 CFR 503 rule, Class B is the minimum standard for any land application of biosolids.

Sub-Class B biosolids refers to sludge that has not undergone sufficient treatment to meet Class B standards and may contain high levels of pathogens and VAR potential, therefore making the biosolids not permitted for land application.

One alternative for dealing with sub-Class B biosolids would be to haul it to a facility which can accept and further treat sub-Class B solids through composting. A few of these facilities exist both within California and Arizona, operated under site-specific permits which limit the type and amount of biosolids accepted by each location. Some other Southern California agencies are using this approach, including hauling biosolids to Arizona. However, there are concerns that the new ordinances in both California and Arizona may also prevent acceptance of sub-Class B material at these locations in future. Many composting facilities, including E&G, though they use composting to further treat biosolids, are not specifically permitted to accept sub-Class B biosolids. E&G's operation falls under the General Waste Discharge Requirements for Composting Operations, Order WQ 2015-0121-DWQ, that stipulates Class A, B, and/or Exceptional quality biosolids as a Tier II allowable feedstock - see Appendix 4H in Volume 2, Chapter 4.

VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-7
Class A Biosolids
Class A biosolids are produced with technologies designed to reduce pathogens to undetectable levels and, therefore, may be beneficially used where contact with the general public is possible (i.e., nurseries, gardens, golf courses, etc.). Class A biosolids can be produced through any of the six defined Alternatives in 40 CFR 503 (Table 8.2). No alternatives were considered within the Master Plan to meet Class A requirements.

1.3.1.2 State
The beneficial use or disposal of biosolids is primarily regulated by California's SWRCB Division of Water Quality (DWQ), and the nine Regional Water Quality Control Boards (RWQCBs or Regional Water Boards).

As required under the Porter-Cologne Act, the SWRCB, along with its nine Regional Water Boards, is principally concerned with protecting existing and future beneficial uses of water, but also addresses the use or disposal of sewage sludge (and biosolids). The City's WWTP is regulated under the Central Coast Regional Water Board.

The treatment and disposal of Santa Maria WWTP biosolids must comply with the SWRCB Order No. 2004-0012-DWQ, General WDRs for the Discharge of Biosolids to Land for Use as a Soil Amendment in Agriculture, Silviculture, Horticulture, and Land Reclamation Activities (2004 General Order). Currently, the City does not land apply biosolids, but if this were to change in the future, then the City would need to comply. The 2004 General Order applies to Class B land application sites of all sizes and Class A Exceptional Quality sites where biosolids will be applied at rates greater than 10 dry tons per acre per year to a field that is larger than 20 acres in size.

The 2004 General Order goes beyond the requirements of 40 CFR Part 503 by requiring additional biosolids testing, soil testing, and groundwater sampling. For such a discharge to be allowed, the biosolids must meet these treatment and testing requirements and must demonstrate capability to be beneficially used as a soil amendment as specified under 40 CFR Part 503. The General Order requires the same pathogen reduction and vector attraction reduction requirements as in 40 CFR Part 503. Refer to Chapter 4 of Volume 2 of the Master Plan for details on the 2004 General Order permit.

CalRecycle oversees and regulates California's solid waste disposal, including the disposal of biosolids with municipal solid waste and the use of biosolids as alternative daily cover (ADC) material at landfills.

Per the existing permits, Santa Maria WWTP is exempt from the requirements of Consolidated Regulations for Treatment, Storage, Processing, or Disposal of Solid Waste in CCR, Title 27, Division 2, Subdivision 1, Section 20005, et seq. The Title 27 exemption is in effect so long as Santa Maria WWTP meets the preconditions for Sewage, Wastewater, Underground Injection, Soil Amendments, and Fully Enclosed Units categories. Biosolids that are land-discharged (disposed), including incineration ash, must also comply with the following regulations:
 CCR Title 23, Division 3, Chapter 15.
 Title 22, Division 4.5, Chapter 11; California Water Environment Association (CWEA) Manual of Good Practice for Agricultural Land Application of Biosolids.

PFAS Sampling
The state issued Order DW 2020-0015-DWQ in July 2020, which requires WWTPs across the state to conduct per- and polyfluoroalkyl substances (PFAS) sampling of their effluent and biosolids. Per this VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-8
order, WWTPs must conduct a one-year-long sampling of 31 PFAS analytes in the influent and effluent.

Further, biosolids must be sampled for PFAS and moisture content once during the same year-long sampling period. As of now, Santa Maria has completed a year-long sampling baseline for PFAS constituents.

Senate Bill 1383
CalRecycle Senate Bill (SB) 1383, which became effective on January 1, 2022, requires 50 percent diversion of organics (including wastewater solids and biosolids) from landfills by 2020 relative to 2014 levels and 75 percent diversion by 2025. Historically, both use of wastewater solids as ADC in landfills and land application were considered landfill diversion. However, with the enactment of SB 1383, use of wastewater solids as ADC no longer qualifies as diversion and is considered disposal. This could drive wastewater agencies that currently landfill their biosolids to investigate land application options, development of more anaerobic digestion and composting facilities (both in the public and private sector), increased co-digestion of organics at WWTP having excess anaerobic digestion capacity, and an increase in compost and biosolids products in the market. Furthermore, SB 1383 is expected to overturn county ordinances that overly restrict land application and expand the number of land application sites.

1.3.1.3 Local
At the local level, the Central Coast RWQCB (Region 3) is responsible for rulemaking, permitting, and enforcement of federal and state requirements at the Santa Maria WWTP. As noted in Volume 2, Chapter 4 of the Master Plan, counties across California have developed, or are developing, ordinances governing biosolids land application. This can range from unrestricted land application to banning biosolids completely. Figure 1.1, taken from Volume 2, Chapter 3, shows the current status of county ordinances affecting the use of biosolids. Of significance for this discussion is that currently, there are no regulations/ordinances enacted in Santa Barbara County. This is only one of two counties in Southern California with no regulations. However, the neighboring counties of Kern and San Luis Obispo have a ban on land application of Class B biosolids, and Ventura County requires a conditional use permit. In the future, it is likely to become more and more difficult to apply sub-Class B biosolids that Alternatives 1, 3, and 5 would produce, and potentially even Class B biosolids in and around the Santa Maria area.

VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-9
Figure 1.1 Current Status of County Ordinances Affecting the Use of Biosolids To comply with current restrictions, the Master Plan considers alternative biosolids use and/or disposal scenarios that are cost-effective and can operate within the existing WWTP facilities.

1.3.2 Future Trends
Currently, legislation allows for some facilities to accept sub-Class B solids for disposal and composting within California. However, it is important to note that E&G is not one of these facilities. This is a key constraint as it precludes the continued use of E&G for biosolids disposal for several of the evaluated liquid treatment alternatives, which would produce sub-Class B solids.

In addition to E&G, the City has the option to send biosolids to the City's landfill. Though this offers a near-term solution for disposal, legislative initiatives such as SB 1383 and Santa Barbara's Climate Action Plan aim to reduce the portion of biosolids sent to landfills. Over the course of the planning period for this Master Plan, disposal at the landfill may be significantly reduced if not ceased.

VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-10
Lastly, PFAS chemicals are an emerging concern in both liquid and solids treatment for wastewater.

Although legislation has not been written for PFAS in biosolids, discussion of future regulations has begun at both the state and national level. For the purposes of this Master Plan, it would not be practical to invest in and operate an advanced solids treatment process without knowing whether or not it will meet future unknown regulations. However, it is prudent to plan for adequate space availability on-site near the solids handling facilities to more easily implement a new technology to further process solids to destroy or eliminate PFAS prior to disposal.

1.3.3 Treatment Implications
From a treatment perspective, the legislative trends described above may have a significant impact on the current biosolids regime. Once the implementation of the laws proceed (in particular SB 1383 that requires 75 percent diversion of organics from landfills by 2025 relative to 2014, and the Santa Barbara County Climate Action Plan that targets 85 percent reduction of organic waste by 2035), the City may face a situation where the Santa Maria landfill that receives some WWTP biosolids may no longer accept them for disposal. Further, increased demand for organics diversion by other businesses and individuals may cause strain on the capacity of the existing composting facilities in Santa Maria (such as E&G, the existing composting facility). This may further reduce the ability of Santa Maria to send their biosolids to the local composting operation.

As a result of both previous changes and expected future changes to wastewater solids regulations, the Master plan considered several different alternatives for long-term disposal of biosolids, further described in Section 1.4.

1.4 Biosolids Production by Treatment Alternative
This section provides a brief overview of solids handling for each of the alternatives presented in Chapter 1 of Volume 6 of the Master Plan and the additional alternatives presented in TM 2.

1.4.1.1 Alternatives Producing Sub-Class B Biosolids
The following liquid process alternatives do not include primary clarifiers or digesters and will produce Sub-Class B Biosolids:
 Alternative 1: Modified Ludzak-Ettinger (MLE) without Primary Clarifiers.  Alternative 3: Oxidation Ditch without Primary Clarifiers.  Alternative 5: 4-Stage Bardenpho without Primary Clarifiers.  Each of these alternatives includes the following two solids waste streams:
» Waste Activated Sludge (WAS): The excess biomass produced during the secondary treatment process. Largely composed of microorganisms and biological floc with 0.5 percent to 1 percent total solids (TS).
» Secondary scum: floatable solid waste from the secondary clarifiers, including filamentous organisms, foam, and grease.

For these alternatives, only secondary sludge (WAS) is produced, which is then sent to aerated sludge holding tanks for storage prior to dewatering. These treatment alternatives would not reach a Class B level VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-11
of treatment for the biosolids and would therefore be considered sub-Class B biosolid. Based on the process model, the estimated production of solids for each of these alternatives is shown in Table 1.6.

Table 1.6 Estimated Biosolids Production for Alternatives Producing Sub-Class B Biosolids Alternative 1 Alternative 3 Alternative 5
Primary Sludge Flow, mgd N/A N/A N/A
WAS Flow, mgd(1,2) 0.43 0.48 0.44
WAS Solids Concentration, (%TS)(1,2) 0.60 0.61 0.61
Thickened WAS Flow, mgd N/A N/A N/A
Digested Sludge Flow, mgd N/A N/A N/A
Dewatered Cake, wet tons/day(1) 68 77 70
Dewatered Cake Solids Concentration(%TS)(1) 15 15 15
Notes:
mgd - million gallons per day; N/A - not applicable
(1) Flow and loads based on modeling results for all treatment alternatives presented in Chapter 1 of Volume 3. (2) The WAS flows and loads are based on the modeling results for average daily loading.

1.4.1.2 Alternatives Producing Class B Biosolids
The following liquid process alternatives produce Class B biosolids using one of the methods detailed in Table 1.5:
 Alternative 2: Oxidation Ditch with Primary Clarifiers.  Alternative 4: 4-Stage Bardenpho with Primary Clarifiers.  Alternative 5a: 4-Stage Bardenpho with Aerobic Digestion.  Alternative 5b: 4-Stage Bardenpho with Sludge Drying Beds.

Each of these alternatives includes the two solid waste streams listed in Section 1.4.1.1. In addition to WAS and secondary scum, both Alternatives 2 and 4 include:

1. Primary Sludge (PS): The solid materials that settle out of raw wastewater during primary clarification.

This waste stream is largely composed of organic material, fecal solids, and grit with 1 percent to

3.5 percent TS.

2. Primary Scum: Primary scum is similar in nature to secondary scum and consists of a floatable solid waste stream comprised of fats, oils, and grease (FOG) and other buoyant materials poorly suited for settling.

Based on the process model developed as a part of Volume 3 of the Master Plan, the estimated production of solids is shown in Table 1.7.

Table 1.7 Estimated Biosolids Production for Alternatives Producing Class B Biosolids Alternative 2 Alternative 4 Alternative 5a Alternative 5b Primary Sludge Flow, mgd(1) 0.07 0.07 N/A N/A
Primary Sludge Solids Concentration (%TS)(1,2) 3.6 3.5 N/A N/A WAS Flow, mgd(1) 0.20 0.28 0.44 0.44
WAS Solids Concentration, (%TS)(1) 0.61 0.60 0.61 0.61
VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-12
Alternative 2 Alternative 4 Alternative 5a Alternative 5b Thickened Sludge Flow, mgd(3) 0.06 0.07 0.04 0.085
Thickened WAS Solids Concentration (%TS) 6 6.0 6 3
Digested Sludge Flow, mgd(3) 0.06 0.07 0.04 N/A
Digested Sludge Solids Concentration (%TS)(3) 3.2 3.2 3.4(4) N/A Dewatered Cake, wet tons/day 38 42 38 15
Dewatered Cake Solids Concentration (%TS) 20 20 15 70(5) Notes:
(1) Flow and loads based on modeling results for all treatment alternatives presented in Chapter 1 of Volume 3. (2) Although design parameters for the primary clarifiers are the same for both Alternatives 2 and 4, the recycle streams for the overall system are not the same, leading to some variance in primary sludge solids content. (3) The digested sludge loads are based on model results (thickened primary sludge and thickened WAS). (4) Assumes 50 percent reduction in volatile solids during aerobic digestion with 15 percent solids cake. (5) Assumes 70 percent TS cake based on existing data from the Santa Maria WWTP.

1.4.2 Comparison of Alternatives
Table 1.8 provides a summary and comparison of biosolids production for each of the evaluated alternatives with consideration of biosolids quantity, solids content, solids reduction, hauling volume, and dryness level.

Table 1.8 Comparison of Biosolid Production of Alternatives Alternative
1 Alternative
2 Alternative
3 Alternative
4 Alternative
5 Alternative
5a(1)
Alternative
5b
Dewatered Cake, dry lb/d 20,403 15,281 23,124 16,867 21,105 11,324 21,105 Hauling Volume, wet tons/year 24,824 13,944 28,134 15,391 25,677 13,777 5,502 Dryness Level 15% total
solids
20% total
solids
15% total
solids
20% total
solids
15% total
solids
15% total
solids
70% total
solids
Notes:
lb/d - pounds per day
(1) WAS from the Bardenpho process is sent to aerobic digesters prior to dewatering.

1.5 Hauling and Disposal Alternatives
This section evaluates the logistical, economic, and regulatory feasibility of disposal options for the City's solids handling process at the WWTP. The following solutions for disposal of the dewatered cake, based on the quality of biosolids produced, were evaluated for each of the evaluated alternatives:

1. Continued disposal at both E&G and the City's Landfill, based on a 70:30 percent split, respectively, for biosolids disposal destination based on data from 2018-2023.

2. Disposal of all biosolids at E&G.

3. Disposal of biosolids with a third-party processing facility like Synagro at either their South Kern Industrial Center (SKIC) or Liberty Composting facilities in California, both of which have capacity to accept 100 percent of the City's projected biosolids.

VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-13

1.5.1 Current Co-Disposal
The City currently operates a series of gravity thickeners, anaerobic digestors, and sludge drying beds to produce Class B solids. Approximately 75 percent of the dried solids are then sent to an off-site composting facility, and the remainder is sent to the Santa Maria landfill. In order to continue the method of co-disposal of biosolids, the solids processing facilities must produce a Class B biosolid to be accepted at E&G. Therefore, only Alternatives 2, 4, 5a, and 5b were considered for continuing this disposal alternative. Table 1.9 summarizes the estimated costs associated with disposal of Class B biosolids for these alternatives.

Table 1.9 Cost of Co-Disposal of Biosolids
Current Co-Disposal (2023)Alternative
2 Alternative
4 Alternative
5a
Alternative
5b
E&G Annual Cake Disposal (Wet Tons) 2,530 9,760 10,774 9,644 3,852 E&G Annual Cost(1) $85,800 $330,977 $365,340 $327,031 $174,564 City Landfill Annual Cake Disposal (Wet Tons) 997 4,183 4,617 4,133 1,651 City Landfill Annual Cost(2) $26,538 $111,395 $122,960 $110,066 $43,957 Total Annual Cost $110,707 $442,372 $488,300 $437,097 $174,564 Notes:
(1) Fee derived from current City rates at E&G. Fee = $33.61 USD/Wet Ton. (2) Fee derived from current City rates at Landfill. Fee = $26.63 USD/Wet Ton.

Maintaining the use of both the Landfill and E&G for Class B biosolids disposal will provide the lowest annual cost. Though this offers a near-term solution for disposal, legislative initiatives such as SB 1383 and Santa Barbara's Climate Action Plan aim to reduce the portion of biosolids sent to landfills. Over the course of the planning period for this Master Plan, disposal at the landfill may be significantly reduced, if not ceased.

1.5.2 E&G Only
In order for Santa Maria's WWTP to only use the E&G composting facility for disposal of biosolids, Class B biosolids or higher must be produced. Like the Co-Disposal options, only Alternatives 2, 4, 5a, and 5b have the ability to use this alternative, as they use anaerobic digestion to produce Class B biosolids.

Table 1.10 summarizes the estimated costs associated with disposal of Class B biosolids to E&G only for each of the alternatives.

Table 1.10 Cost of E&G Only Disposal of Biosolids
Alternative 2 Alternative 4 Alternative 5a Alternative 5b E&G Annual Cake Disposal (Wet Tons) 13,944 15,391 13,777 5,502 E&G Annual Cost(1) $472,824 $521,914 $467,187 $186,581
Notes:
(1) Fee derived from current City rates at E&G. Fee = $33.61 USD/Wet Ton.

When compared to disposal of biosolids at E&G as well as the City's landfill, similar to current operations, the disposal of all Class B biosolids at E&G would result in a slightly higher annual disposal cost across all alternatives. With only one location for the disposal of biosolid, operations are simplified; however, VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-14
because E&G is privately owned and operated, there is some uncertainty regarding the longevity of E&G as a disposal option.

1.5.3 Additional Disposal Options
Additional biosolids disposal methods are available and were considered as part of the Master Plan.

However, most options require additional biosolids treatment to produce Class A biosolids. The higher cost to achieve Class A biosolids is not practical for the City to pursue, so only disposal options for Class B or sub-Class B biosolids were considered.
 Many large wastewater treatment plants send biosolids to a third-party facility for further processing.

Synagro, a nationwide biosolids and residuals management company, is a third-party processing facility that accepts sub-Class B biosolids. They have two locations, Liberty and SKIC, that are close to the City's service area and can accept 100 percent of the City's projected biosolids. Synagro further processes the biosolids and land applies it on a number of Synagro-owned sites. Because third-party processing facilities can accept sub-Class B biosolids, the option to dispose of biosolids at a Synagro facility was considered for all the evaluated alternatives. Table 1.11 summarizes the estimated cost associated with the disposal of biosolids at Synagro.
 Hauling sub-class B biosolids to a Synagro facility, which is the only location that will accept sub-class B currently, will have the highest annual cost.

Table 1.11 Cost of Biosolids Disposal at Synagro Facilities Alternative
1 Alternative
2 Alternative
3 Alternative
4 Alternative
5 Alternative
5a
Alternative
5b
Synagro Annual Cake Disposal
(Wet Tons) 24,824 13,944 28,134 15,391 25,677 13,777 5,502 Synagro Annual Cost(1) $1,823,295 $1,024,151 $2,066,454 $1,130,480 $1,885,988 $1,011,939 $404,140 Notes:
(1) Synagro provided budgetary costs for hauling and composting, which is the same unit cost for both proposed facilities.

Fee = $73.45 USD/Wet Ton.

1.5.4 Additional Considerations
Santa Maria WWTP solids processing facilities include sludge drying beds that receive solids flow from the existing anaerobic digesters and assist in producing Class B biosolids. Due to the favorable weather in Santa Maria, the existing sludge drying beds can be used seasonally for post-mechanical dewatering. For the alternatives evaluated that produce Class B biosolids, the existing sludge drying beds can provide 6 weeks of cake storage for times when the composting facility cannot take the biosolids right away and can provide additional drying in the dry season, offsetting hauling costs.

For the alternatives that produce sub-Class B biosolids, the existing sludge drying beds can be used to produce Class B biosolids by requiring a minimum 3-month retention time. Alternative 5b, further described in TM 2, evaluated the option of using sludge drying beds to produce Class B biosolids. The minimum number of sludge drying beds will require eliminating approximately 29 acres of existing percolation ponds, making this option undesirable and was not further considered.

VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-15

1.5.4.1 Screw Press Pilot Testing
The City pursued pilot testing of an Ishigaki screw press from September 8th through September 12th of 2025. Overall, the testing went well, and the dewatered cake achieved exceptional dryness with the existing digested sludge. Below is a summary of the overall findings and considerations for this pilot testing effort.

Summary of Pilot Testing:
 Dewatering Unit: Ishigaki Mobile Pilot Testing Unit:
» Ishigaki ISGK-A-0305 dewatering screw press.
» Netzch progressive cavity pump.
» Velodyne Liquid Polymer Blending Unit.
» Endress+Hauser Magnetic Flowmeter.
» Ishigaki conditioning tank, control panel, and 3 polymer injection points. » Capacity: 5-17 gallons per minute (gpm), with a maximum solids loading of 150 lbs dry solids per hour.
 Digested Sludge Feed:
» Anaerobically digested sludge from trickling filter process:
 69.55 percent volatile solids content (average from lab data).  2.2 percent TS (average from lab data).
 Jar testing was initially performed on sludge samples from the Santa Maria WWTP, which showed the C-6285 as the best-performing polymer for the City's current sludge makeup.

This polymer was used for pilot testing the screw press at the WWTP. Polymer dosage ranged from 22 to 35 lbs active/dry ton of digested solids, with cake solids concentrations averaging

27.9 percent. These results are in line with expected performance with easily dewaterable trickling filter sludge. The full report is included as Appendix B - Ishigaki Pilot Testing Report.  Pilot Testing Observations and Considerations:
» At a sludge feed rate of 5-17 gpm, the pilot unit was fairly small compared to the units that would be required for permanent installation. Larger units may not provide the same level of efficiency as the smaller unit tested, which would impact performance. » Trickling filter solids are fairly easy to dewater after digestion, so it should not be assumed that the same high-level performance would be achieved with the future digested sludge makeup of the facility once Phase 1 is complete. The combination of primary sludge and waste activated sludge would likely demand higher polymer usage and provide lower cake dryness. The assumed solids concentrations presented previously in this chapter for mechanical dewatering are still recommended values for planning and design purposes.
» Screw presses have limited throughput, so sizing with a factor of safety built into the design capacity of each unit is recommended. Based on our experience, an assumed performance of 65 percent to 75 percent of the manufacturer's stated maximum capacity is recommended to ensure sufficient system capacity is provided.
» For a permanent screw press system, a unit may at times "lose the plug" and no longer be water-tight at the back of the machine. Curbing, drainage, and housekeeping provisions should be provided to account for these occurrences.

VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-16
» Where possible, specify 316 stainless steel construction as the equipment will be subject to corrosion from hydrogen sulfide or other compounds naturally present in the dewatering process. » Provide positive odor control/ventilation out of the unit, if possible. » Provide locations for polymer injection ahead of the screw press and the floc tank, in addition to those provided by the manufacturer.
» In general, dewatering screw press technology is still a viable selection for mechanical dewatering at the Santa Maria WWTP and can be considered further alongside other technologies, such as belt filter presses, for final selection during preliminary design. It would be good to obtain feedback from agencies that use this technology before making a final decision on the selection of dewatering technology.

1.6 Conclusions and Findings
The following is a summary of key findings from cost, regulatory, and operational standpoints:
 Alternatives 1 (MLE with extended aeration, no Primary Clarification or Digestion) and Alternative 3 (Oxidation Ditch without Primary Clarification or Digestion) will produce sub-Class B biosolids that can only be disposed of at a third-party processing facility like Synagro. These alternatives offer limited disposal flexibility and a high annual cost that is more than the City's current costs for biosolids disposal.
 Alternative 2 (Oxidation Ditch with Primary Clarification and Anaerobic Digestion) will produce Class B biosolids that can be disposed of using the current co-disposal methods.  Alternative 4 (Bardenpho Activated Sludge with Primary Clarification and Anaerobic Digestion) will produce Class B biosolids that can be disposed of using the current co-disposal methods. Such biosolids can be used as a feed to additional solids processing systems to produce a higher class of biosolids and/or treatment to achieve future PFAS regulations. This alternative provides the best balance of cost, compliance, and flexibility.
 Alternative 5 (Bardenpho Activated Sludge without Primary Clarification and Digestion) offers limited disposal flexibility as it will produce a sub-Class B biosolid that will have to be disposed of by hauling to a Synagro facility for third-party processing. The annual cost for this option would be $1.9 million, which is more than one million per year more than the City's current costs for biosolids disposal.
 Alternative 5a (Alt 5 with use of Aerobic Digestion) will produce a Class B biosolid to provide more flexibility in biosolid disposal options. The construction capital cost impact of producing Class B solids as part of Alternative 5a is approximately $59 million to add sufficient thickening and digestion capacity. This alternative will have greater capital costs than both Alternatives 4 and 5, in addition to higher solids disposal costs than Alternative 4. This solution to produce Class B solids is sub-optimal and does not merit further consideration unless other non-economic factors rule out Alternatives 4 and 5.
 Alternative 5b (Alt 5 with use of Drying Beds) will produce a Class B biosolid by using sludge drying beds as the sole means of dewatering. Currently, there is a desire from the City to move away from drying beds as the sole means of dewatering due to capacity issues during wet weather months and to provide site space for the new wastewater treatment facilities. Alternative 5b exacerbates this issue by requiring an additional 29 acres of sludge drying bed area. Although this alternative would VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-17
result in the lowest biosolids disposal cost, it is considered to be impractical based on the significant area required, the need to relocate existing percolation ponds to accommodate sufficient drying beds, and the significant operations and maintenance (O&M) costs in operating the drying beds.

Accordingly, Alternative 5b was not considered further.

Table 1.12 summarizes the biosolids handling and disposal alternatives presented in this chapter.

Table 1.12 Summary of Biosolids Handling and Disposal Alternatives Alternative Biosolid Quality Available
Disposal Option
Estimated Annual Biosolids Disposal Cost
($ 000)(1)
Estimated
Project Cost
($ M)
1 Sub-Class B Synagro $1,823 $501M
2 Class B
Co-Disposal
E&G Only
Synagro
$442 - $1,024 $516M
3 Sub-Class B Synagro $2,066 $515M
4 Class B
Co-Disposal
E&G Only
Synagro
$488 - $1,130 $483M
5 Sub-Class B Synagro $1,886 $516M
5a Class B
Co-Disposal
E&G Only
Synagro
$437 - $1,012 $575M
Notes:

M - million
(1) Fees derived from current City rates (hauling and disposal) at the City's landfill and E&G. Synagro provided budgetary costs for hauling and composting, which is the same unit cost for both proposed facilities (SKIC or Liberty Composting).

Based on the evaluation of biosolids production by treatment alternative described in this chapter, maintaining Class B production capability to preserve low-cost, local disposal options is recommended.

Alternative 4, which features a 4-stage Bardenpho activated sludge process with primary clarifiers and anaerobic digesters, is expected to have the lowest long-term O&M cost and provides the best balance of cost, compliance, and flexibility.

VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA

WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX A TM 2 - ENERGY AND SOLIDS EVALUATION

FOR BARDENPHO ALTERNATIVES

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
TECHNICAL MEMORANDUM 2
Energy and Solids Evaluation for Bardenpho
Alternatives
FINAL / October 2026

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
TECHNICAL MEMORANDUM 2
Energy and Solids Evaluation for
Bardenpho Alternatives
FINAL / October 2026
Digitally signed by Graham J.G. Juby
Contact Info: Carollo Engineers, Inc.

Date: 2026.10.23 07:52:53-07'00'
Digitally signed by Daniel L. Meacham
Contact Info: Carollo Engineers, Inc.

Date: 2026.10.23 09:56:56-05'00'
TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN i
pw://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/TM02/TM02 Contents
TM 2 ENERGY AND SOLIDS EVALUATION FOR BARDENPHO

ALTERNATIVES

2.1 Overview 2-1

2.1.1 Background and Purpose 2-1

2.1.2 Alternative 4 Overview: 4-Stage Bardenpho With Primary Clarifiers and Anaerobic Digesters 2-1

2.1.3 Alternative 5 Overview: 4-Stage Bardenpho Without Primary Clarifiers 2-2

2.2 Addressing Question 1: Energy Recovery Analysis 2-4

2.2.1 Existing Digester Gas System 2-4

2.2.2 Historical and Future Digester Gas Production 2-5

2.2.3 Cogeneration and Energy Estimates 2-6

2.2.4 Operations and Maintenance Cost Summary 2-8

2.2.5 Capital Cost Impacts 2-9

2.2.6 Biogas Beneficial Use Considerations 2-9

2.3 Question 2: Biosolids Disposal Options for Sub-Class B 2-10

2.3.1 Regulatory Constraints 2-10

2.3.2 Existing Solids Treatment 2-11

2.3.3 Alternative 4 - Bardenpho With Anaerobic Digestion 2-12

2.3.4 Alternative 5: Bardenpho Without Anaerobic Digestion 2-13

2.3.5 Alternative 5a: Bardenpho With Aerobic Digestion 2-13

2.3.6 Alternative 5b: Bardenpho With Sludge Drying Beds 2-14

2.3.7 Capital Cost Impacts 2-16

2.3.8 Biosolids Disposal Considerations 2-18

2.4 Overall Summary and Conclusions 2-18
Tables
Table 2.1 Average Monthly Digester Gas Production and Yield (2018-2024)(1) 2-5 Table 2.2 Phase 1 Expansion Anaerobic Digester Design Criteria 2-5 Table 2.3 Flaring and Boiler Heat Recovery Using Biogas to Replace Propane Heating 2-7 Table 2.4 Gas Engine Specifications Used for Analysis 2-7 Table 2.5 Savings from Electrical Power 2-8
Table 2.6 Thermal Power Savings 2-8
Table 2.7 Gas Flared and Utilized under Each Scenario 2-8 Table 2.8 O&M Cost Comparisons 2-9
Table 2.9 Summary of City's Biosolids Reporting Data (2018-2023) 2-11 Table 2.10 Estimated Biosolids Production for Alternative 4 2-12 Table 2.11 Comparison of Class B Biosolids Disposal Costs for Alternative 4 2-12 Table 2.12 Estimated Biosolids Production for Alternative 5 2-13 Table 2.13 Anticipated Annual Cost for Disposal of Sub-Class B Biosolids to Synagro 2-13 TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN ii
Table 2.14 Summary of Biosolid Production for Alternative 5a(1) 2-13 Table 2.15 Summary Estimated Annual Class B Biosolids Disposal Costs for Alternative 5a 2-14 Table 2.16 Summary of Biosolid Production for Alternative 5b(1) 2-14 Table 2.17 Summary Estimated Annual Class B Biosolids Disposal Costs for Alternative 5b 2-16
Table 2.18 O&M and Capital Cost Summary and NPV 2-20
Figures
Figure 2.1 Alternative 4 With Primary Clarifier Process Schematic 2-2 Figure 2.2 Alternative 5 Without Primary Clarifiers Process Schematic 2-3 Figure 2.3 Current Status of County Ordinances Affecting the Use of Biosolids 2-3 Figure 2.4 Alternative 5b Would Require Eliminating About 29 Acres of Existing Percolation Pond Area 2-15
Figure 2.5 Impact of Alternative 5b on the Additional Pond Area (Purple) Required East of Black Road 2-17
TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-1
TM 2 ENERGY AND SOLIDS EVALUATION FOR

BARDENPHO ALTERNATIVES

2.1 Overview

2.1.1 Background and Purpose
The City of Santa Maria (City) is in the process of selecting the preferred treatment configuration for the upcoming Phase 1 wastewater treatment plant (WWTP) expansion to bring the plant into compliance with the new effluent discharge requirements that include reducing the total nitrogen concentration to below 10 milligrams per liter (mg/L). In a workshop with the City on November 6, 2024, the liquid stream treatment alternatives were narrowed down to two configurations that incorporate the Bardenpho activated sludge process for achieving nitrogen removal. One configuration includes the use of primary treatment and anaerobic digestion (Alternative 4) and the other does not include either primary treatment or anaerobic digestion (Alternative 5).

The purpose of this Technical Memorandum (TM) is to evaluate the two Bardenpho process alternatives from an energy and biosolids perspective, and to provide technical justification for selection of one of the process treatment alternatives for the Phase 1 project. This TM will consider operations and maintenance (O&M) costs, regulatory requirements, and project feasibility.

In particular, this memorandum will be divided into two areas of discussion, Energy and Biosolids. The overarching questions to be addressed are:
 Question 1: What energy cost savings are possible with Alternative 4 when utilizing a cogeneration (cogen) system?
 Question 2: What are the options for biosolids disposal available with Alternative 5 which does not include anaerobic digestion?
Before addressing these questions, an overview for the two process alternatives is provided as background.

2.1.2 Alternative 4 Overview: 4-Stage Bardenpho With Primary Clarifiers and Anaerobic Digesters
Alternative 4 includes a Bardenpho aeration basin process that incorporates upstream primary clarifiers and solids stabilization in anaerobic digesters. As can be seen in the simplified process schematic in Figure 2.1, primary and secondary sludge is generated and sent to a solids processing system. For solids processing, this alternative includes co-thickening of both primary sludge and waste activated sludge (WAS), anaerobic digestion of thickened sludge, and mechanical dewatering of the digested sludge to produce Class B material for disposal.

This approach is similar to the existing process at the WWTP which produces Class B Biosolids through use of gravity thickening, anaerobic digestion and sludge drying beds. Currently, final disposal of the TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-2
majority of the Class B material is to the nearby composting facility (operated by Engel and Gray, Inc. [E&G]), with about a quarter of the biosolids going to the City's landfill operation.

Figure 2.1 Alternative 4 With Primary Clarifier Process Schematic

2.1.3 Alternative 5 Overview: 4-Stage Bardenpho Without Primary Clarifiers Alternative 5 includes a Bardenpho aeration basin process that does not incorporate upstream primary clarifiers or downstream anaerobic digesters. In this alternative, as can be seen in the simplified process schematic in Figure 2.2, only secondary sludge is produced, which is then sent to aerated sludge holding tanks for storage prior to dewatering. The sludge storage tank volume for this alternative provides only sufficient capacity to accommodate three days of storage, allowing for holiday weekends without the need for dewatering operations. This treatment approach would not reach a Class B level of treatment for the biosolids.

As noted in Volume 2, Chapter 4 of the Master Plan, counties across California have developed, or are developing, ordinances governing biosolids land application. This can range from unrestricted land application to banning biosolids completely. Figure 2.3, taken from Volume 2, Chapter 3, shows the current status of county ordinances affecting the use of biosolids. Of significance for this discussion is that currently, there are no regulations/ordinances enacted in Santa Barbara County. This is only one of two counties in Southern California with no regulations. However, the neighboring counties of Kern and San Luis Obispo have a ban on land application of Class B biosolids, and Ventura County requires a conditional use permit. In the future, it is likely to become more and more difficult to apply sub-Class B biosolids that Alternative 5 would produce, and potentially even Class B biosolids in and around the Santa Maria area.

TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-3
Figure 2.2 Alternative 5 Without Primary Clarifiers Process Schematic Figure 2.3 Current Status of County Ordinances Affecting the Use of Biosolids TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-4
One alternative for dealing with sub-Class B biosolids would be to haul it to a facility which can accept and further treat sub-Class B solids through composting. A few of these facilities exist both within California and Arizona, operated under site-specific permits which limit the type and amount of biosolids accepted by each location. Some other Southern California agencies are using this approach, including hauling biosolids to Arizona. However, there are concerns that the new ordinances in both California and Arizona may also prevent acceptance of sub-Class B material at these locations in future. Another alternative would be to add additional solids processing to the Alternative 5 treatment train to produce Class B biosolids, as discussed below.

2.1.3.1 Alternative 5a and 5b: Class B Solids Without Anaerobic Digestion Alternative 5a follows the same treatment approach as Alternative 5, however the waste solids from the aeration basins would be mechanically thickened and then processed in open aerobic digesters prior to dewatering. Aerobic digesters are essentially large aeration basins which allow the sludge to age over a long detention time. To meet Class B, sufficient aerobic digester volume that allows for a minimum 40-day retention time with one of the largest aerobic digester tanks out of service is required. This will produce Class B biosolids without the need for anaerobic digesters.

A second alternative (Alternative 5b) would be to use sludge drying beds to retain the solids long enough to reach a Class B biosolids.

Further discussion on these sub-alternatives is presented later in this TM.

2.2 Addressing Question 1: Energy Recovery Analysis
Question 1: What energy cost savings are possible with Alternative 4 when utilizing a cogen system?
As noted, Alternative 4 includes anaerobic digesters, which will produce biogas. A cogen system using internal combustion engines (IC Engines) to generate heat and electrical power was used for this preliminary analysis. The evaluation considered the anticipated biogas production, digester heating requirements, the WWTP power consumption, and monthly O&M costs.

The analysis also compares the costs/savings for the scenario where the City continues to flare excess digester gas, which is not used in the hot water boilers.

2.2.1 Existing Digester Gas System
The City currently operates a gas flaring and boiler system. There are two hot water boilers on-site, the primary boiler, Boiler No. 1, burns digester gas with propane gas as a backup while the standby unit burns only propane. Gas produced by the anaerobic digesters is sent to Boiler No. 1 as the primary heat source for the hot water system which heats the anaerobic digesters to 35°C. The standby propane boiler (Boiler No. 2) is only utilized when Boiler No. 1 is out of service. The boilers typically do not operate simultaneously, except during digester startup. Any excess gas not used by the boilers to maintain the temperature is flared. Waste Gas Flare 1 and 2 burn excess digester gas and are ignited by a propane pilot. Currently, approximately 22 percent of the gas, about 24.6 standard cubic feet per minute [scfm], is sent to the boiler, and the remaining 78 percent is flared. This means there is significant potential for energy recovery using a cogen system.

TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-5
In addition to purchasing propane used for heating, the City purchases electricity to power the facility from Pacific Gas and Electric (PG&E). The costs associated with electric delivery are based on demand and energy charges. The demand charge is set by the peak amount of instantaneous power required by the City (all the lights are turned on at once), whereas the energy charge describes the total amount of electricity utilized over time (leaving the lights on all day). The City can reduce the power costs by both reducing the peak demand required by the facilities, or by reducing overall energy consumption over time. There are time-of-use considerations as well. Winter purchases at night are cheaper than summer purchases during the afternoon. As such, when comparing cogen and flaring alternatives, understanding how the costs are reduced is directly linked to how facility demand and energy consumption is reduced.

2.2.2 Historical and Future Digester Gas Production
The City tracks the performance of its anaerobic digesters on a monthly basis. The City also tracks the amount of biogas produced, the inflow of solids, and the amount of volatile solids reduced by the process. There are three operational digesters at the City of Santa Maria's WWTP, one of which is a standby.

Table 2.1 summarizes the average amount of gas produced on a monthly basis, and the average specific yield (gas CH3 produced/pound of volatile suspended solids [VSS] removed) of the digesters since 2018.

Table 2.1 Average Monthly Digester Gas Production and Yield (2018-2024)(1) Digester VSS Removal Efficiency Monthly Biogas Produced (ft3) [cfm]
Biogas Yield
(ft3 of Gas Produced/lb VSS removed)
Digester No. 1 57% 2,461,000 [57.0 cfm] 12.9
Digester No. 3 56% 2,040,000 [47.2 cfm] 19.3
Notes:
cfm - cubic feet per minute; ft3 - cubic feet; lb - pound (1) Includes 2024 data to September 2024.

Using historically observed yields and the currently developed preliminary design criteria for Alternative 4, the amount of VSS destruction and the future digester gas production can be estimated.

Table 2.2 highlights the design criteria of the future Phase 1 digestion facilities for Alternative 4 derived from the process model presented in TM 1.

Table 2.2 Phase 1 Expansion Anaerobic Digester Design Criteria Design Criteria Estimated VSS Loading From PS and
Thickened WAS (lb/day)
Future Digester Volume
(ft3)
Anticipated Biogas Production
(cfd) [cfm]
Digestion System 32,225 173,780 192,000 to 275,000
[133 to 190 cfm]
Notes:
cfd - cubic feet per day
Using the yield values from Table 2.1, and the volatile solids loading values in Table 2.2, the future amount of gas produced by the Alternative 4 digesters may be estimated.

The projected amount of biogas produced for Alternative 4 under Phase 1 conditions is estimated to be between 192,000 and 275,000 cfd [190 cfm], at the start and end of Phase 1, respectively. Assuming a TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-6
60 percent methane concentration and standard conditions (600 BTU/scf), the energy content inherent in that quantity of gas is between 116 and 165 million British thermal units (MMBTU)/day.

2.2.3 Cogeneration and Energy Estimates
Given the future energy available for digester gas and energy recovery activities, it is possible to estimate the energy that can be re-used thermally (to reheat the digesters), and electrically (for sale or for use elsewhere in the plant).

For this analysis, two scenarios were compared. The first considers a "no biogas utilization" approach that would use a boiler system with propane as the primary fuel source. Note that in the Phase 1 project, the existing boiler (around 20 years old now) would be replaced under this scenario. This would set a baseline cost for digester heating without biogas use. The second scenario analyzes a modular IC Engine approach.

The gas engine manufacturer used for the analysis was JenBacher, and specifically their model J312 Modular Gas Engine.

The existing boiler system is sticker-rated at 88 percent efficiency, but was down-rated for the purposes of this assessment to 85 percent efficiency.

It is assumed that any excess biogas not utilized by the alternatives will need to be flared.

2.2.3.1 Boiler and Flaring System Analysis
This scenario assumes that a boiler and flaring system will be provided as part of the Phase 1 expansion to replace the aging boiler and flares. The scenario compares the cost savings of reusing the biogas compared with utilizing propane as fuel for the boilers. This scenario attempts to quantify the effect of keeping the existing infrastructure configuration (with new equipment) while flaring the remainder of the gas. The difference in operational cost savings will be developed based on the cost of propane.

Based on the heating projections for two digesters, it is estimated that 27 MMBTU/day of heating is required at the design flows in the Phase 1 expansion. A third digester would be provided as standby, but would not be heated until put into service. This corresponds to a requirement of 45,000 cfd of digester biogas.

As such, the comparison will compare the cost of re-using the digester biogas vs heating the digesters with propane only.

It is important to note that the Air Pollution Control District (APCD) permit currently allows for 478,000 cfd of flaring. This is allowable under the current air pollution permit. The permit is re-evaluated triennially.

The plant currently flares between 115,00 and 135,000 cfd, well within the permit limit.

In this case, the actual heating requirements for the system are needed. The monthly heating requirement for the digesters in 2023 averaged 19.2 MMBTU/day. As mentioned, the future heating requirements at the Phase 1 design conditions are estimated at 27 MMBTU/day.

TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-7
Table 2.3 summarizes the potential cost savings by utilizing biogas rather than propane for heating the digesters.

Table 2.3 Flaring and Boiler Heat Recovery Using Biogas to Replace Propane Heating System
Anaerobic Digester Heating
Requirement
(MMBTU/day)
Quantity of Propane Gas
Saved by using Biogas
(cfd)
Monthly Cost Benefit for Using
Digester Gas(1,2)
Current System 19.2 MMBTU/day 213 cfd $22,700
Future System 27 MMBTU/day 303 cfd $32,400
Notes:
(1) Propane costs, including purchase and delivery, is $3.50 per gallon. (2) The cost-benefit for reusing digester gas for the future is based on reducing the propane costs.

As shown in Table 2.3, using digester biogas rather than propane for digester heating would provide significant monthly cost savings. Continual maintenance and reporting requirements detailed under the existing permit would remain.

2.2.3.2 Internal Combustion Engine Analysis
This section analyzes the energy savings that can be achieved with cogen. Discussion of the possible gas systems and the operational and maintenance burden of engines and other alternatives will be provided in Volume 9.

As noted earlier, a JenBacher IC Engine was used for this analysis. The specifications for the engine are shown in Table 1.4.

Table 2.4 Gas Engine Specifications Used for Analysis
Electrical Biogas Consumption
(cfd)
Electrical
Output
(kW)
Thermal
Output
(kW)
Electrical
Efficiency
Thermal
Efficiency
JenBacher J312 248,000(1) 635 kW(1) 752-855 kW 39%(2) 50%(2) Notes:
kW - kilowatt
(1) Assumes 24-hour operation.
(2) To be conservative these values were reduced to 35 percent and 47 percent, respectively in the calculations.

Despite the efficiencies shown in the table, in order to be conservative, this analysis assumed that electrical efficiencies would be 4 percent less than indicated, and thermal efficiencies would be 3 percent less than indicated; that is 35 percent and 47 percent, respectively.

The cost savings analysis relies on two sources:

1. Thermal: The cost savings of not purchasing an equivalent amount of propane to heat the anaerobic digesters (see Table 2.3).

2. Electrical: The cost savings from not purchasing electricity from the grid at purchased rates.

Table 2.5 indicates the electrical power production of the IC engine. It was assumed that the engine would operate for 20 hours a day, to allow for some down-time for maintenance, and that all the energy would be re-used at the plant. The initial estimate of the Phase 1 WWTP electrical power demand for Alternative 4 is approximately 1.2 megawatt (MW).

TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-8
Table 2.5 Savings from Electrical Power
Electrical Power Generated(1) Energy Produced per Day Monthly Cost Savings(2) Annual Energy Saving(3) JenBacher 0.635 MW 12.70 MWh(2) $83,800 $1,005,600
Notes:
(1) The instantaneous power generated is the rated capacity provided by the manufacturer. (2) Summarizes the existing average monthly 2023/24 consumption by the City of Santa Maria WWTP, and assuming 20-hours of engine operation per day.
(3) Cost savings generated by re-using electricity at 23/24 rates, which average $0.22/kWh including delivery and generation costs.

The thermal energy recovered is equivalent to the amount of energy required by the anaerobic digesters (~27 MMBTU). As such, the savings will be the same as shown in Table 2.3 above. In both cases, however, there is excess thermal energy that is generated and must be accounted for. Table 2.6 summarizes the thermal energy generated from the IC engine.

Table 2.6 Thermal Power Savings
Thermal Thermal Power
Generated
Heating Energy
Required for Digesters Excess Heat Annual Cost Savings(1) JenBacher 69.8 MMBTU/day ~ 27 MMBTU/day 42.8 MMBTU/day $388,800 Notes:
(1) Based on monthly saving of $32,400 from Table 2.3.

As shown in Table 2.6, the excess heat also provides significant savings. Implementation of the gas engine system will likely need to provide an additional cooler/boiler as an outlet for excess heat.

Table 2.7 indicates the amount of gas that would be flared or utilized in either the gas boiler approach or the IC engine approach. The maximum biogas anticipated under the Phase 1 design conditions would be 275,000 cfd. At the start of Phase 1 the anticipated gas production would be 192,000 cfd. As mentioned, the existing APCD permit for the City allows for 478,000 cubic feet of flaring a day. Note that APCD regulates emissions from all sources where biogas is burned. Thus, directing gas to be combusted in an engine rather than the flare still counts towards the total emissions. But, in each scenario, the total amount of biogas to be burned is within the existing permit amount.

Table 2.7 Gas Flared and Utilized under Each Scenario
System Alternative Biogas Utilized (cfd) Biogas Flared (cfd) Boiler and Flaring System 45,000 230,000
JenBacher IC Engine 248,0001 27,000
In each alternative, reducing the quantity of biogas flaring is important to maximize the energy that can be saved.

2.2.4 Operations and Maintenance Cost Summary
For the cogen to be viable, the cost savings should be significant enough to offset the increased operations and maintenance burden that would be placed on the plant and their facilities. It would also need to be significant enough to pay off any capital cost requirements on the system.

TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-9
The projected monthly O&M cost for Alternative 4 after the Phase 1 expansion, including Class B solids disposal but without co-generation, is $347,500. The additional monthly cost to operate an IC Engine is estimated to be $52,000.

The following Table 2.8 estimates the added monthly O&M cost for operation for each energy recovery system.

Table 2.8 O&M Cost Comparisons
Estimated Additional Monthly O&M
Cost for Alternative 4(1) ($)
Estimated Monthly Cost Savings
from Energy Recovery
Net Monthly Cost
Savings
Boiler + Flaring $21,300 $32,400 $11,100
JenBacher Gas Engine $52,000 $117,600 $65,600
Notes:
(1) Gas Engine O&M cost is 0.054 $/kWh based on existing maintenance contracts, and other fuel treatment costs.

The results from this analysis indicate that the energy recovery savings are significant enough to offset the added maintenance burdens that result from operating cogen equipment, and result in a net overall monthly cost saving.

Further, there is potential for the equipment supplier to provide maintenance services on the cogen system and reduce the operational burdens for the City.

2.2.5 Capital Cost Impacts
The construction capital cost impact of including a cogen system as part of Alternative 4 is approximately $20 million. If cogeneration is not implemented there would still be the cost of providing a new boiler to provide redundancy.

Details of the capital cost impacts will be included in Volume 9. However, given the net monthly O&M cost savings shown in Table 2.8, there would be the opportunity to apply such savings towards paying back the capital costs incurred for either approach.

2.2.6 Biogas Beneficial Use Considerations
Based on the above analysis the following conclusions can be made:

1. Alternative 4 is expected to produce between 192,000 and 274,000 cfd of biogas when operating at the start and end of the Phase 1 design conditions, respectively and there are two approaches for making use of the biogas; one utilizes the biogas for digester heating only, and the other would implement a cogen (or similar) system that would produce heat for the digesters as well as renewable electrical power to offset the plant electrical power costs.

2. Under Phase 1 conditions, a daily average of about 530 kW of electrical power could be generated from a combustion engine cogen system, together with more than enough residual heat to heat the digesters.

3. Under Phase 1 conditions, the electrical energy produced by a cogen system would off-set electrical energy purchases from PG&E. The analysis shows that the cost savings from producing electrical energy (530 kW) and heat would be almost $1.4 million annually. This is expected to be greater than the O&M costs ($624,000) associated with operating and maintaining the cogen equipment, resulting in a net positive savings.

TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-10

4. Utilizing power and heat from a cogen system offers the following benefits:
a. More sustainable than flaring biogas.
b. Reduces reliance on PG&E for electrical power for a portion of the plant needs. c. Provides an opportunity to receive funding for GHG reduction, as well as tax credits.

5. Adding cogen facilities to Alternative 4 will increase the construction capital cost by approximately $20 million. For Alternative 4 without the cogen approach, the capital cost would increase to cover the cost of providing a redundant boiler. The cost for a new gas flare system is already included in the Alternative 4 cost.

2.3 Question 2: Biosolids Disposal Options for Sub-Class B Question 2: What are the options for biosolids disposal available with Alternative 5 which does not include anaerobic digestion?
Currently, the City disposes of its biosolids at the City's landfill and the E&G composting facility which is licensed to accept Class B solids for composting. This facility is adjacent to the treatment plant and provides a convenient and economical solution to biosolids disposal. However, changing regulatory landscapes and disposal site availability merit consideration when selecting a long-term biosolids treatment approach. Additionally, there is uncertainty regarding the long-term availability of the existing composting facility that receives Class B biosolids from Santa Maria. This evaluation will consider both the existing disposal site and secondary options for disposal for treatment Alternatives 4, 5, and 5a, which can be defined as:

1. Alternative 4: Anaerobic digestion which produces Class B solids.

2. Alternative 5: No digestion which produces sub-Class B solids.

3. Alternative 5a: Aerobic digestion/sludge storage which produces Class B solids.

2.3.1 Regulatory Constraints
Regulations are further discussed in Volume 2, Chapter 4 of the Master Plan, however biosolids quality has a direct impact on where solids can be disposed of which may influence the City's ultimate decision on solids treatment.

Currently, legislation allows for some facilities to accept sub-Class B solids for disposal and composting within California. However, it is important to note that E&G is not one of these facilities. E&G operates under the General Waste Discharge Requirements for Commercial Composting Operations (Order WQ 2020-0012-DWQ) by the State Water Resources Control Board (SWRCB). Their permit requires that biosolids are treated to a minimum of Class B standards prior to acceptance at the composting facility.

This is a key constraint as it precludes the continued use of E&G for biosolids disposal for Alternative 5, which would produce sub-Class B solids.

In addition to E&G, the City has the option to send biosolids to the City's landfill. Though this offers a near-term solution for disposal, legislative initiatives such as SB 1383 and Santa Barbara's Climate Action Plan aim to reduce the portion of biosolids sent to landfills. Over the course of the planning period for this Master Plan, disposal at the landfill may be significantly reduced if not ceased.

TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-11
Lastly, PFAS chemicals are an emerging concern in both liquid and solids treatment for wastewater.

Although legislation has not been written for per- and polyfluoroalkyl substances (PFAS) in biosolids, discussion of future regulations has begun at both the state and national level. For the purposes of this Master Plan, it would not be practical to invest in and operate an advanced solids treatment process without knowing whether or not it will meet future unknown regulations. However, it is prudent to plan for adequate space availability on-site near the solids handling facilities to more easily implement a new technology to further process solids to destroy or eliminate PFAS prior to disposal.

2.3.2 Existing Solids Treatment
The existing sludge processing system at the Santa Maria WWTP includes gravity thickening, anaerobic digestion, and sludge drying beds. The current anaerobic digestion treatment meets a minimum solids retention time (SRT) of 15 days, which produces a Class B solids product.

The City's annual biosolids reporting data from 2018 to 2023 includes the average biosolids production, disposal location, and hauling and tipping fees. In 2023, about 30 percent of the biosolids went to the City Landfill and the remainder was composted. This information is summarized in Table 2.9.

Table 2.9 Summary of City's Biosolids Reporting Data (2018-2023) Year
E&G City Landfill
Total Annual
Cost (USD)
Fee
(USD/
Wet Ton)
Annual Cake
Production
(Wet Tons)
Annual Cost
(USD)
Fee
(USD/
Wet Ton)
Annual Cake
Production
(Wet Tons)
Annual Cost
(USD)
2019 $33.91 2295.09 $77,826.50 $26.6 1027.21 $27,354.60 $105,181.10 2020 $33.91 2036.26 $69,049.58 $26.63 652.67 $17,380.60 $86,430.18 2021 $33.91 2269.82 $76,969.60 $26.63 316.5 $8,428.40 $85,397.99 2022 $33.91 3320.46 $112,596.80 $26.63 1352.47 $36,016.28 $148,613.07 2023 $33.91 2530.22 $85,799.76 $26.63 996.54 $26,537.86 $112,337.62 Average Annual Cost $110,706.07
The wet tonnage of biosolids shown in the table above are estimates provided in the City's annual anaerobic digester analysis summary, which assumes a 30 percent moisture content when calculating wet tonnage of biosolids. Due to the favorable weather in Santa Maria, it is possible to achieve this high solids content in dewatered cake, which will contrast with the mechanical dewatering processes in the alternatives discussed herein. If the City chooses to do so, existing sludge drying beds that remain onsite once the new facilities are complete may be used to further dewater cake post-mechanical dewatering.

This benefit may allow for significant financial savings during dry months when the City can store mechanically dewatered cake outside in the drying beds.

TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-12

2.3.3 Alternative 4 - Bardenpho With Anaerobic Digestion As noted earlier, this alternative includes primary sludge and WAS, both co-thickened and then sent to anaerobic digesters prior to sludge storage and dewatering. This process produces Class B biosolids.

Based on the process model, developed as a part of Volume 3 of the Master Plan, the estimated production of solids is shown in Table 2.10.

Table 2.10 Estimated Biosolids Production for Alternative 4 Units Primary
Sludge
Thickened Primary
Sludge
WAS Thickened
WAS
Digested
Sludge(2)
Dewatered
Cake
Flow mgd 0.07 0.04 0.28 0.03 0.07 0.01
Daily Solids
Production(1)
dry
lbs/day 20,586 19,556 14,005 13,305 17,755 16,867
Percent solids % 3.53 6 0.60 6 3.24 20
Daily Cake Hauling
Weight
wet
tons/day - - - - - 42.2
Cake Volume cu. ft./day - - - - - 1,352
Notes:
mgd - million gallons per day
(1) It is assumed that the mechanical thickening and the mechanical dewatering processes each have a 95 percent solids capture.
(2) It is assumed that the anaerobic digestion process has a 50 percent destruction of volatile solids for both primary sludge and WAS. Primary sludge is assumed to contain approximately 95 percent volatile solids, and WAS is assumed to have approximately 88 percent volatile solids based on the calibrated model.

Multiple solutions for disposal of the dewatered cake exist for this alternative and will be further discussed in Volume 8 of the Master Plan. For the purpose of this evaluation, three alternatives will be compared:

1. Continued disposal at both E&G and the City's Landfill, based on a 70:30 percent split, respectively, for biosolids disposal destination based on data from 2018-2023.

2. Disposal of all biosolids at E&G.

3. Disposal of biosolids with Synagro at either their South Kern (SKIC) or Liberty Composting facilities in California, both of which have capacity to accept 100 percent of the City's projected biosolids.

The following table summarizes the estimated costs associated with disposal of Class B biosolids at 20 percent solids concentration for Alternative 4.

Table 2.11 Comparison of Class B Biosolids Disposal Costs for Alternative 4 No. Disposal Location Fee
(USD/Wet Ton)(1)
Annual Cake Disposal
(Wet Tons)
Subtotal Cost
(USD) Total Annual Cost (USD)
1 E&G $33.91 9,490 $321,803 $488,300 City Landfill $26.63 4,067 $108,307 2 E&G $33.91 13,557 $459,718 $521,914
3 Synagro $73.45 13,557 $995,762 $1,130,480
Notes:
(1) Fees derived from current City rates (hauling and disposal) at the City's landfill and E&G. Synagro provided budgetary costs for hauling and composting, which is the same unit cost for both proposed facilities (SKIC or Liberty Composting).

TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-13

2.3.4 Alternative 5: Bardenpho Without Anaerobic Digestion This alternative includes only WAS which is sent directly to sludge storage without thickening or digestion, prior to dewatering. This process produces sub-Class B biosolids. Based on the process model, the estimated production of solids is shown in Table 2.12.

Table 2.12 Estimated Biosolids Production for Alternative 5 Units WAS Dewatered Cake
Flow mgd 0.44 0.017
Daily Solids Production(1) dry lbs/day 22,215 21,105
Percent solids % 0.61 15
Daily Cake Hauling Weight wet tons/day - 70.4
Cake Volume cu. ft./day - 2,255
Notes:
(1) It is assumed that the mechanical dewatering processes has a 95 percent solids capture.

Disposal of sub-Class B solids is limited to composting facilities that will accept this product, or further treatment could be provided in order to achieve Class B or better. In order to evaluate Alternative 5 as presented in the November 6th, 2024 workshop, the only disposal alternative applicable for Alternative 5 is disposal with Synagro. Both their SKIC and Liberty Composting locations can accept sub-Class B biosolids in the projected quantity for this alternative.

Table 1.13 summarizes the estimated costs associated with disposal of sub-Class B biosolids at 15 percent solids concentration for Alternative 5.

Table 2.13 Anticipated Annual Cost for Disposal of Sub-Class B Biosolids to Synagro No. Disposal Location Fee
(USD/Wet Ton)(1)
Annual Cake Disposal
(Wet Tons) Total Annual Cost (USD)
1 Synagro $73.45 25,677 $1,885,998
Notes:
(1) Synagro provided budgetary costs for hauling and composting, which is the same unit cost for both proposed facilities (SKIC or Liberty Composting).

2.3.5 Alternative 5a: Bardenpho With Aerobic Digestion
Alternative 5a is the same as Alternative 5, with the addition of aerobic digesters. WAS from the Bardenpho process would be sent to aerobic digesters, prior to dewatering. This process produces Class B biosolids by extending the SRT within the aerobic digesters to a minimum of 40 days. This alternative is presented as a compromise by excluding primary clarifiers and anaerobic digesters from the treatment train, while still producing a Class B biosolid which provides greater options for disposal. The estimated solids generation for this alternative are shown in Table 2.14.

Table 2.14 Summary of Biosolid Production for Alternative 5a(1) Units WAS Thickened WAS Digested Sludge Dewatered Cake
Flow mgd 0.44 0.04 0.04 0.01
Daily Solids Production(1) dry lbs/day 22,215 21,105 11,920 11,324 Percent solids % 0.61 6 3.39 15
TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-14
Units WAS Thickened WAS Digested Sludge Dewatered Cake
Daily Cake Hauling Weight wet tons/day - - - 37.8
Cake Volume cu. ft./day - - - 1,210
Notes:
(1) Alternative 5a assumes a 50 percent reduction in volatile solids during aerobic digestion with 15 percent solids cake.

With aerated digestion and a Class B biosolids, multiple solutions for disposal of the dewatered cake are once again available for this alternative. For the purpose of this evaluation, three alternatives will be compared:

1. Continued disposal at both E&G and the City's Landfill, based on the same 70:30 percent split respectively for biosolids disposal destination based on data from 2018-2023.

2. Disposal of all biosolids at E&G.

3. Disposal of biosolids with Synagro at either their SKIC or Liberty Composting facilities in California, both of which have capacity to accept 100 percent of the City's projected biosolids.

Table 2.15 summarizes the estimated costs associated with disposal of Class B biosolids at 15 percent solids concentration for Alternative 5a. Costs are higher than for Alternative 5 due to the greater quantity of biosolids requiring disposal.

Table 2.15 Summary Estimated Annual Class B Biosolids Disposal Costs for Alternative 5a No. Disposal Location Fee
(USD/Wet Ton)(1)
Annual Cake Disposal
(Wet Tons)
Subtotal Cost
(USD)
Total Annual
Cost (USD)
1 E&G $33.91 9,644 $327,031 $437,097
City Landfill $26.63 4,133 $110,066
2 E&G $33.91 13,777 $467,187 $467,187
3 Synagro $73.45 13,777 $1,011,939 $1,011,939
Notes:
(1) Fees derived from current City rates (hauling and disposal) at the City's landfill and E&G. Synagro provided budgetary costs for hauling and composting, which is the same unit cost for both proposed facilities (SKIC or Liberty Composting).

2.3.6 Alternative 5b: Bardenpho With Sludge Drying Beds Alternative 5b is the same as Alternative 5, except sludge drying beds are used in addition to mechanical dewatering, which allows for the production of Class B biosolids. WAS from the Bardenpho process would be sent to a mechanical dewatering process, prior to further dewatering and a minimum 3-month retention within the sludge drying beds to reduce the water volume removed via evaporation. Similar to Alternative 5a, this alternative is presented as a compromise by excluding primary clarifiers and anaerobic digesters from the treatment train, while still producing a Class B biosolid which provides greater options for disposal. The estimated solids generation for this alternative are shown in Table 2.16.

Table 2.16 Summary of Biosolid Production for Alternative 5b(1) Units WAS Dewatered Cake
Flow mgd 0.44 0.004
Daily Solids Production(1) dry lbs/day 22,215.28 21,105 Percent solids % 0.61 70
TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-15
Units WAS Dewatered Cake
Daily Cake Hauling Weight wet tons/day - 15.1
Cake Volume cu. ft./day - 483
Notes:
(1) Alternative 5b assumes a 70 percent TS cake based on existing data from the Santa Maria WWTP.

The area of drying beds required for the minimum 3-month retention time would be greater than the space available on-site when considering the replacement of impacted percolation ponds. Because of this, Alternative 5b assumes that the WAS is thickened in a mechanical dewatering process prior to transfer to the sludge drying beds. This would minimize the sludge drying bed area to about 29 acres. The mechanically thickened sludge is estimated to have 15 percent solids, which would be difficult to pump.

Hauling vehicles would therefore be needed for routine transportation of solids from the mechanical dewatering facility to the drying beds in addition to heavy equipment to spread the sludge within the drying beds. The hauling and spreading equipment would not only increase capital investment, but significantly impact labor demand at the facility to accommodate this treatment approach. Figure 2.4 illustrates the area required for the sludge drying beds under this alternative in comparison to the Phase II facilities, showing that the large area required for sludge drying beds cannot be accommodated without impacting existing percolation ponds. Accordingly, additional percolation pond area would also need to be constructed east of Black Road.

Figure 2.4 Alternative 5b Would Require Eliminating About 29 Acres of Existing Percolation Pond Area TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-16
With the use of sludge drying beds to produce a Class B biosolid, multiple solutions for disposal of the dewatered cake are once again available for this alternative. For the purpose of this evaluation, three alternatives will be compared:

1. Continued disposal at both E&G and the City's Landfill, based on the same 70:30 percent split respectively for biosolids disposal destination based on data from 2018-2023.

2. Disposal of all biosolids at E&G.

3. Disposal of biosolids with Synagro at either their SKIC or Liberty Composting facilities in California, both of which have capacity to accept 100 percent of the City's projected biosolids.

Table 2.17 summarizes the estimated costs associated with disposal of Class B biosolids at 70 percent solids concentration for Alternative 5b. Costs are lower than for Alternative 5a due to the lower quantity of biosolids requiring disposal.

Table 2.17 Summary Estimated Annual Class B Biosolids Disposal Costs for Alternative 5b No. Disposal Location Fee
(USD/Wet Ton)(1)
Annual Cake Disposal
(Wet Tons)
Subtotal Cost
(USD)
Total Annual Cost
(USD)
1 E&G $33.91 3,852 $130,607 $174,564 City Landfill $26.63 1,651 $43,957 2 E&G $33.91 5,502 $186,581 $186,581
3 Synagro $73.45 5,502 $404,140 $404,140
Notes:
(1) Fees derived from current City rates (hauling and disposal) at the City's landfill and E&G. Synagro provided budgetary costs for hauling and composting, which is the same unit cost for both proposed facilities (SKIC or Liberty Composting).

2.3.7 Capital Cost Impacts
The construction capital cost impact of producing Class B solids as part of Alternative 5a is approximately $59 million to add sufficient thickening and digestion capacity. This alternative will have greater capital costs than both Alternatives 4 and 5 in addition to higher solids disposal costs than Alternative 4. This solution to producing Class B solids is sub-optimal and does not merit further consideration unless other non-economic factors rule out Alternatives 4 and 5.

Concerning Alternative 5b, the minimum number of sludge drying beds will require eliminating approximately 29 acres of existing percolation ponds, which will require reestablishment on the east side of Black Road. This effectively takes up the vast majority of all the remaining space on this property north of Stowell Road when included with the 6 new ponds already planned for construction during Phase 1.

This also requires construction of the replacement ponds within an area outside of the "favorable area" for percolation, which may require more than 29 acres of land to provide sufficient percolation. Assuming uniform pond size of 7 acres, to achieve the 29-acre minimum replacement, an additional 34 acres of pond area is shown in Figure 2.5 to illustrate the impact of the additional drying beds and associated new percolation ponds. Space limitations would likely become worse during Phase 2 if the same sludge disposal strategy is being applied.

TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-17
Figure 2.5 Impact of Alternative 5b on the Additional Pond Area (Purple) Required East of Black Road TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-18

2.3.8 Biosolids Disposal Considerations
It's clear that it would be advantageous for the City to continue using both the landfill and E&G for biosolids disposal. However, these may not be long-term options, and the City may be forced to use disposal options located farther from the treatment facility at a much higher disposal cost either within or beyond the current planning horizon of the Master Plan.

Based on the analysis presented, the following conclusions can be made regarding biosolids disposal:

1. Maintaining the use of both the Landfill and E&G for Class B biosolids disposal, or even switching to 100 percent disposal of biosolids to E&G will provide the lowest disposal annual cost ($488,000 to $522,000). This would be achievable with Alternative 4.

2. Hauling sub-Class B biosolids (Alternative 5) to a Synagro facility (the only location that will accept sub-Class B currently) will have the highest annual cost (almost $1.9 million); more than four times higher than the costs associated with Alternative 4.

3. Treating sub-Class B solids to Class B on site with aerobic digestion (Alternative 5a) will have the next highest biosolids disposal cost, but will also incur added costs for power for aeration air required for the aerobic digesters. In addition, there will considerable capital cost (estimated to be >$59 million) associated with providing sufficient aerobic digester volume to achieve the minimum 40-day detention time. Overall, Alternative 5a is expected to have the highest cost.

4. Using sludge drying beds to produce Class B biosolids, Alternative 5b, is challenged by the area required for the sludge drying beds. Currently, there is a desire to move away from drying beds as the sole means of dewatering due to capacity issues during wet weather months. Alternative 5b exacerbates this issue by requiring an additional 29 acres of sludge drying bed area. Although this alternative would result in the lowest biosolids disposal cost, it is considered to be impractical based on the significant area required and the need to relocate existing percolation ponds to accommodate sufficient drying beds. Accordingly, Alternative 5b was not considered further.

2.4 Overall Summary and Conclusions
This TM evaluated the two Bardenpho process alternatives from an energy and biosolids perspective, with the goal to provide technical information to support justification for selection of one of the process treatment alternatives for the Phase 1 project. The two treatment alternatives under consideration are:
 Alternative 4 - 4-Stage Bardenpho with Primary Clarifiers and Anaerobic Digesters.  Alternative 5 - 4-Stage Bardenpho without Primary Clarifiers and Anaerobic Digesters.

Based on the evaluation presented above, which considered O&M costs, regulatory requirements, and capital cost impacts, the following conclusions can be made:

1. With respect to Alternative 4:
a. Alternative 4 is expected to produce sufficient biogas to support the operation of boiler system to generate hot water to heat the digesters, similar to the existing system, or a cogen system that will produce more than enough heat to heat the anaerobic digesters, and sufficient electrical power to meet about 40 percent of the expected plant electrical load. b. The savings in electrical energy for Alternative 4 with a cogen system is expected to total nearly $800,000 per year and will help to off-set the capital cost of the Phase 1 project.

TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-19
c. Alternative 4 will produce Class B biosolids that can be disposed of via the current methods. Such biosolids can be used as a feed to additional solids processing systems to produce a higher class of biosolids and/or treatment to achieve future PFAS regulations. d. A cogen system is expected to add about $20 million to the construction cost estimate of Alternative 4 presented at November 6th, 2024 workshop. The non-cogen approach will add $6 million to the construction cost for the inclusion of a replacement boiler.

2. With respect to Alternative 5:
a. Alternative 5 would not produce biogas and therefore recovery of reusable energy would not be an option.
b. Alternative 5 would produce a sub-Class B biosolids. The only option for disposal of this sludge would be hauling it to Synagro with an annual cost of $1.9 million; at least $1.0 million per year more than the City's current costs for biosolids disposal. c. Producing Class B biosolids with Alternative 5 would require the addition of large aerobic digester tanks, Alternative 5a. Such tanks are expected to add almost $60 million to the construction cost and increase the energy demand for the process.

3. Summary of O&M and Capital Costs:
a. Table 2.16 presents a summary of the anticipated annual cost savings, biosolids disposal costs, total O&M costs and updated construction cost estimate for Alternative 4 (with and without cogen), and Alternative 5 and 5a, as well as the 20-year Net Present Value (NPV). b. Alternatives 5 has the highest biosolids disposal costs, followed by Alternative 5a. Alternative 5a has higher biosolids disposal costs than Alternative 4 because the amount of biosolids produced would be greater.
c. Alternatives 5 and 5a have the highest estimated annual O&M cost. d. Alternative 5a has the highest expected construction cost. Alternative 5 has the next highest construction cost.
e. Alternative 4 (without cogen) is expected to have the lowest 20-year NPV, slightly lower than Alternative 4 (with cogen). For the 20-year evaluation it was assumed that the mechanical equipment would be maintained regularly, as part of the O&M cost, but that the boilers and cogen equipment would last for the 20-year period. Alternatives 5 and 5a would have significantly greater NPVs.

4. Alternative 4, either with or without cogen, appears to be a better choice than Alternative 5 or 5a for the Phase 1 project because of the additional energy savings associated with Alternative 4 with cogen.

This alternative is expected to have the lowest long-term O&M cost. However, the higher capital cost of the cogen equipment pushes the 20-year NPV of this alternative higher than the "without cogen" alternative. Potential opportunities to receive funding for greenhouse gas reduction, as well as tax credits could further improve the economic advantage of Alternative 4 with cogen. Designing a system with flexibility to accept a future cogen system, and operating without one in Phase 1, would allow the investment in biogas utilization to be phased and not lock the City into a cogen system that might impact the long-term O&M costs if there are operational issues, or if sufficient tax credits/incentives are not forthcoming.

TM 2 - ENERGY AND SOLIDS EVALUATION FOR BARDENPHO ALTERNATIVES OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-20
Table 2.18 O&M and Capital Cost Summary and NPV
Alternative
Estimated Annual
Biogas Beneficial
Savings
($ 000)
Estimated Annual
Biosolids Disposal Cost
($ 000)(1)
Estimated Annual
O&M Cost
($ 000) (6)
Estimated
Project Cost
($ M)
20-year Net
Present Value
($ M) (7)
4 (w/o cogen) $133(3) $488 - $1,130(4) $4,054 - $4,696 $489M(2) $570M 4 (with cogen) $788 $488 - $1,130(4) $3,398 - $4,041 $507M $575M 5 (sub-Class B) - $1,886(5) $5,324 $516M $585M
5a (Class B) - $437 - $1,012 $4,569 - $5,329 $575M $666M Notes:

M - million
(1) Fees derived from current City rates (hauling and disposal) at the City's landfill and E&G. Synagro provided budgetary costs for hauling and composting, which is the same unit cost for both proposed facilities (SKIC or Liberty Composting). (2) Capital cost does not include capital investment required for resource recovery through full beneficial use of biogas, but assumes utilization of biogas for digester heating. Includes the cost of a new boiler. Further modifications has been made to Alternative 4, detailed in Volume 6, Chapter 6, which are not included here to provide an apples to apples comparison regarding level of treatment between alternatives discussed herein. (3) Digester heating only.
(4) The higher cost ($1,130,480) is for hauling to a Synagro facility. (5) Sub-Class B hauled to Synagro.
(6) Includes the benefit of cost savings due to biogas utilization shown in second column. (7) Assuming the lowest annual operation cost, an annual inflation rate of 3 percent, and a discount rate of 3 percent.

VOLUME 8 / CHAPTER 1: BIOSOLIDS HANDLING AND DISPOSAL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA

WASTEWATER TREATMENT PLANT MASTER PLAN

APPENDIX B ISHIGAKI PILOT TESTING REPORT
Pilot Test Report Santa Maria WWTF
280 Heritage Ave • Portsmouth, NH 03801 • (603) 433-3334 • Fax (603) 433-3348

Page 1 of 12 ends

PILOT TEST REPORT
TEST LOCATION: SANTA MARIA WWTF
PILOT TEST FOR: BIOSOLIDS DEWATERING TRIAL
PILOT TEST DATE: SEPTEMBER 08 – SEPTEMBER 12, 2025
ISHIGAKI USA LTD.
280 HERITAGE AVE. UNIT #J
PORTSMOUTH, NH 03801
Pilot Test Report Santa Maria WWTF
280 Heritage Ave • Portsmouth, NH 03801 • (603) 433-3334 • Fax (603) 433-3348

Page 2 of 12 ends

TABLE OF CONTENTS

1. Ishigaki’s Mobile Testing System Summary ........................................................................ 3

2. Facility Details..................................................................................................................... 3

3. Tested Treatment Process.................................................................................................. 4

4. Current Wastewater Treatment Details ............................................................................... 5

5. Polymer Jar Testing Results ............................................................................................... 5

6. Pilot Test Goals................................................................................................................... 5

7. Methods to Achieve Pilot Test Goals................................................................................... 6

8. Detailed Sludge Characteristics .......................................................................................... 6

9. Results................................................................................................................................ 7 a) Summary Plot ............................................................................................................ 7 b) Table.......................................................................................................................... 9

10. Observations and Conclusions...........................................................................................10

11. Test Pictures......................................................................................................................11 Pilot Test Report Santa Maria WWTF
280 Heritage Ave • Portsmouth, NH 03801 • (603) 433-3334 • Fax (603) 433-3348

Page 3 of 12 ends

1. ISHIGAKI’S MOBILE TESTING SYSTEM SUMMARY
The Ishigaki Mobile Pilot Testing System is a self-contained screw press dewatering system, which can typically test 5 – 17 gallons per min and up to 150 pounds of dry solids per hour.

The mobile testing system is specifically designed for on-site evaluation to accurately determine the dewatering performance of a particular slurry, as well as appropriate sizing for a particular application. The system includes Ishigaki’s ISGK-A-0305 dewatering screw press, NETZCH progressive cavity sludge pump, Velodyne Liquid Polymer Blending Unit, Endress+Hauser Magnetic flow meter, Ishigaki’s Conditioning Tank, control panel, and 3 polymer injection points. Additionally, there are specific ports within the system to monitor the slurry condition.

2. FACILITY DETAILS
Facility: City of Santa Maria WWTF
Location: 601 Black Rd.

Santa Maria, CA 93458
Project Summary: Biosolids Facility Upgrade
Facility Contact Name: Russ Newman
Facility Contact Position: Wastewater Supervisor
Facility Contact Email: [email protected]
Facility Contact Phone: (805) 266-1617
Performed by: Ishigaki USA Ltd.

Test Lead: Nicholas Hall, Ishigaki USA Ltd.

Pilot Test Report Santa Maria WWTF
280 Heritage Ave • Portsmouth, NH 03801 • (603) 433-3334 • Fax (603) 433-3348

Page 4 of 12 ends

3. TESTED TREATMENT PROCESS
Trickling
Filters
Additional
Treatment
Anaerobic
Digesters
Primary
Influent Clarifiers
Sludge
Drying Beds
Screens
Grit
Removal

= Raw Sludge Sample Location
Pilot Test Report Santa Maria WWTF
280 Heritage Ave • Portsmouth, NH 03801 • (603) 433-3334 • Fax (603) 433-3348

Page 5 of 12 ends

4. CURRENT WASTEWATER TREATMENT DETAILS
Sludge Type: Anaerobically Digested Sludge
Thickening Method: Gravity, in digester
Facility Daily Flow (MGD): ~7.5 MGD influent per 2024 Plant Flow Schematic Volatile Solids (%): 69.55% (Average from Lab Data)
Sludge Solids Content (%): 2.2% (Average during testing) Dewatering Equipment: Natural Effects; Sludge Drying Beds Polymer Type: C-6285/FB-808
Current Dewatered Cake Solids As needed / as natural effects allow Requested for testing: ~20% Total Solids or better

5. POLYMER JAR TESTING RESULTS
Prior to the pilot testing, Ishigaki USA Ltd. jar tested multiple polymers to determine which created the most effective flocs with the feed sludge. Jar testing indicated that the Clarifloc C-6285 was the most effective polymer for this application.

6. PILOT TEST GOALS
1) To demonstrate the operational and performance benefits of the Ishigaki Screw Press for this application.
2) To provide relevant data used to scale up this specific Ishigaki Screw Press to a full-size design for this application.
3) To verify that the Ishigaki Screw Press technology, in this application, is capable of adequately dewatering the test sludge.

Pilot Test Report Santa Maria WWTF
280 Heritage Ave • Portsmouth, NH 03801 • (603) 433-3334 • Fax (603) 433-3348

Page 6 of 12 ends

7. METHODS TO ACHIEVE PILOT TEST GOALS
The press was operated with the objective of minimizing polymer dosage and maximizing throughput, cake solids dryness and solids capture efficiency. Optimization occurred by varying sludge feed rate, polymer feed rate, and screw speed. Based on those objectives, the most important testing parameters were determined to be:
1) Feed sludge concentration (% DS)
2) Flow rate of feed sludge (GPM)
3) Active polymer dosage (lbs / ton DS)
4) Cake solids concentration (% DS)
5) Solids loading capacity (lbs DS/hr)
6) Solids capture Efficiency
The optimal choice of polymer(s) is discussed in section 5, “Polymer Jar Testing Results.” For your reference, a schematic of the system can be seen below.

8. DETAILED SLUDGE CHARACTERISTICS
Date TS% TVS%
09/9/2025 2.2% ~70*%
* Based on cake solids volatile data.

Pilot Test Report
Palm Beach County WWTF
280 Heritage Ave • Portsmouth, NH 03801 • (603) 433-3334 • Fax (603) 433-3348

Page 7 of 12 ends

9. RESULTS
a) Summary Plot
0%
10%
20%
30%
40%
50%
60%
70%
80%
0 5
10 15
20 25
30 35
40 0 2 4 6 8 10 12 14
Screw Speed (% of 60 Hz)
Cake Solids (% DS)
Polymer Dosage (lbs Active / Ton DS)
Hydraulic Loading (GPM)
Test Number
Summary (Field Data)
Polymer Dosage Hydraulic Loading Screw Speed Cake Solids

22.0%

24.0%

26.0%

28.0%

30.0%

32.0%

34.0%
20 22 24 26 28 30 32 34 36
CAKE SOLIDS (%)

POLYMER DOSAGE (LBS ACTIVE / DT)
CAKE SOLIDS VS. POLYMER DOSAGE
Pilot Test Report
Palm Beach County WWTF
280 Heritage Ave • Portsmouth, NH 03801 • (603) 433-3334 • Fax (603) 433-3348

Page 8 of 12 ends

0.0 10.0

20.0 30.0

40.0 50.0

60.0 70.0

80.0 90.0

0.150 0.200 0.250 0.300 0.350 0.400

SOLIDS LOADING (LBS DS / HR)

SPEED SCREW PRESS (RPM)
SOLIDS LOADING VS. SCREW SPEED

20.0%

22.0%

24.0%

26.0%

28.0%

30.0%

32.0%

34.0%

0.150 0.200 0.250 0.300 0.350 0.400
CAKE SOLIDS (%)

SPEED SCREW PRESS (RPM)
CAKE SOLIDS VS. SCREW SPEED
Pilot Test Report
Palm Beach County WWTF
280 Heritage Ave • Portsmouth, NH 03801 • (603) 433-3334 • Fax (603) 433-3348

Page 9 of 12 ends

b) Table

Pilot Test Report
Palm Beach County WWTF
280 Heritage Ave • Portsmouth, NH 03801 • (603) 433-3334 • Fax (603) 433-3348

Page 10 of 12 ends

10.OBSERVATIONS AND CONCLUSIONS
• Operational and performance benefits were demonstrated to key staff members during this plant’s specific application.
• Relevant data was acquired during the pilot test. This data will be analyzed by Ishigaki’s leading team of design engineers to properly scale up the pilot unit to a full-size unit for your operation.
• The pilot test proved the advanced technology of the ISGK-A screw press technology would be an excellent choice to successfully dewater this slurry. o Polymer dosage ranged from 22 – 35 lbs. active / ton DS. Polymer dosage throughout the entire range resulted in good performance. o Cake solids concentration throughout the pilot test ranged from 23.9 to 33.5% throughout the testing, averaging 27.9%. Screw speed (throughput) and polymer dosage effected cake solids as anticipated.
o Solids feed capacity in this ISGK-A-0305 unit, specifically sized for pilot testing, ranged from 41.8 – 77.1 lbs DS / hr.
o Capture efficiencies averaged 99.08% and ranged up to 99.77%.

Ishigaki USA Ltd. would like to thank you for the opportunity to present our screw press model ISGK-A-0305 at the City of Santa Maria WWTP. We appreciate all the help provided by the plant personnel to make this a successful test.

Pilot Test Report
Palm Beach County WWTF
280 Heritage Ave • Portsmouth, NH 03801 • (603) 433-3334 • Fax (603) 433-3348

Page 11 of 12 ends

11.TEST PICTURES

1. Flocculated Sludge 2. Filtrate

Pilot Test Report
Palm Beach County WWTF
280 Heritage Ave • Portsmouth, NH 03801 • (603) 433-3334 • Fax (603) 433-3348

Page 12 of 12 ends

3. Cake Solids 4. Naturally Dried Cake

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 9: Energy Management
FINAL / October 2026

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 9: Energy Management
FINAL / October 2026
Digitally signed by Graham J.G. Juby
Contact Info: Carollo Engineers, Inc.

Date: 2026.10.24 11:22:15-07'00'
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN i
pw://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/Master Plan/Volume 9/Ch01 Contents
CHAPTER 1 ENERGY MANAGEMENT

1.1 Introduction 1-1

1.2 Data Gathering 1-2

1.2.1 Current Electrical Demand and Charges 1-2

1.2.2 Projected Electrical and Heating Demand for New/Modified WWTP 1-4

1.2.3 Current and Projected Digester Gas Production 1-7

1.3 Power/Heating Generation and Management Technologies 1-9

1.3.1 Emissions Regulation 1-9

1.3.2 Gas Engines 1-9

1.3.3 Microturbines 1-10

1.3.4 Pipeline Injection 1-11

1.3.5 Boilers 1-12

1.3.6 Microgrid 1-13

1.3.7 Wind Energy 1-15

1.3.8 Fuel Cells 1-16

1.4 Site Layouts 1-17

1.5 Digester Gas Beneficial Use Alternatives 1-18

1.5.1 Alternatives Evaluation Basis 1-19

1.5.2 Alternative 1 (Base Case and Current Operation): Heat Recovery With Boilers and Flare Remaining DG 1-20

1.5.3 Alternative 2: Alternative 1 + Power Management Using Microgrid and Battery 1-23

1.5.4 Alternative 3: Power and Heat Generation Using 635 kW Gas Engine + Power Management Using Microgrid and Battery 1-27

1.5.5 Alternative 4: Power and Heat Generation Using 400 kW Microturbine + Power Management Using Microgrid and Battery 1-33

1.5.6 Alternative 5: Power and Heat Generation Using 600 kW Microturbine + Power Management Using Microgrid and Battery 1-40

1.5.7 Alternative 6: Heat Recovery With Boilers + Compression of Remaining Biogas to CNG for Pipeline Injection + Power Management Using Microgrid and Battery 1-45

1.6 Alternative Analysis 1-50

1.6.1 Conclusions and Recommendations 1-52
Appendices

APPENDIX A ELECTRICAL POWER DRAW CALCULATIONS

APPENDIX B HOMER REPORT

APPENDIX C FINANCIAL ASSUMPTIONS AND PROCESS ASSUMPTIONS VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN ii
Tables
Table 1.1 Projected Daily Demand Based on Normal Operation 1-4 Table 1.2 Projected Average Daily Demand Based on Normal Operation 1-6 Table 1.3 WWTP Expansion Anaerobic Digester Heating Requirements 1-6 Table 1.4 Average Monthly Digester Gas Production and Yield (2018-2024)(1) 1-7 Table 1.5 Phase 1 Expansion Anaerobic Digester Design Criteria 1-7 Table 1.6 Gas Engine Specifications 1-9
Table 1.7 Microturbine Specifications 1-10
Table 1.8 Boiler Specifications 1-12
Table 1.9 Case 1 - Homer Software Results - Grid and Solar Only 1-14 Table 1.10 Case 2 - Homer Software Results - Grid, Solar, and Battery 1-15 Table 1.11 Financial Incentives for DG Beneficial Use Alternatives(1) 1-20 Table 1.12 Life Cycle Analysis Criteria - Alternative 1 1-21 Table 1.13 Life Cycle Cost Analysis - Alternative 1 (Base Case) 1-23 Table 1.14 Life Cycle Analysis Criteria - Alternative 2 1-24 Table 1.15 Financial Incentives for Alternative 2 1-25
Table 1.16 Life Cycle Cost Analysis – Alternative 2 (Base Case + Boiler, Battery, and Solar) 1-26 Table 1.17 Gas Conditioning Skid Specifications 1-28
Table 1.18 Life Cycle Analysis Criteria - Alternative 3 1-29 Table 1.19 Financial Incentives for Gas Engines 1-30
Table 1.20 Life Cycle Cost Analysis - Alternative 3 (Gas Engine) 1-33 Table 1.21 Gas Conditioning Skid Specifications 1-34
Table 1.22 Life Cycle Analysis Criteria - Alternative 4 1-35 Table 1.23 Financial Incentives for Microturbines 1-36
Table 1.24 Life Cycle Cost Analysis - Alternative 4 (400 kW Microturbine) 1-39 Table 1.25 Gas Conditioning Skid Specifications 1-40
Table 1.26 Life Cycle Analysis Criteria - Alternative 5 1-41 Table 1.27 Financial Incentives for Microturbines 1-42
Table 1.28 Life Cycle Cost Analysis – Alternative 5 (600 kW Microturbine) 1-45 Table 1.29 Life Cycle Analysis Criteria - Alternative 6 1-46 Table 1.30 Financial Incentives for Pipeline Injection 1-47 Table 1.31 Life Cycle Cost Analysis - Alternative 6 (Conversion to CNG for Pipeline Injection) 1-49
Table 1.32 Alternatives Analysis 1-51
Figures
Figure 1.1 Selected Treatment Alternative for Santa Maria WWTP 1-1 Figure 1.2 WWTP Average Monthly Usage (September 2023 - August 2024) 1-2 Figure 1.3 WWTP Peak Demand by Month (September 2023 - August 2024) 1-3 Figure 1.4 WWTP Cost per Kilowatt-Hour (September 2023 - August 2024) 1-4 Figure 1.5 WWTP Projected Hourly Demand 1-5
Figure 1.6 WWTP Projected Hourly Net Demand With Solar Output 1-6 Figure 1.7 Jenbacher J312 Gas Engine 1-10
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN iii
Figure 1.8 Capstone C600S Enclosure 1-11
Figure 1.9 Proximity of WWTP to SoCalGas Pipeline 1-12
Figure 1.10 Cleaver Brooks CBJT Boiler 1-13
Figure 1.11 Example Representation of a Microgrid 1-14
Figure 1.12 Available Space for Cogeneration Alternatives 1-17 Figure 1.13 Proposed Locations of the Power Management Systems at Santa Maria WWTP 1-18
Figure 1.14 Alternative 1 - Electrical Process Schematic 1-21 Figure 1.15 Alternative 1 - Biogas Process Schematic 1-21 Figure 1.16 Alternative 1 - Digester Gas End Uses 1-22
Figure 1.17 Alternative 1 - Annual O&M Costs 1-23
Figure 1.18 Alternative 2 - Electrical Process Schematic 1-24 Figure 1.19 Alternative 2 - Biogas Process Schematic 1-24 Figure 1.20 Alternative 2 - Digester Gas End Uses 1-25
Figure 1.21 Alternative 2 - Annual O&M Costs 1-26
Figure 1.22 Alternative 3 - Process Flow Schematic 1-27 Figure 1.23 Alternative 3 - Proposed Layout 1-28
Figure 1.24 Alternative 3 - Projected Electrical Consumption 1-31 Figure 1.25 Alternative 3 - Digester Gas End Uses 1-32
Figure 1.26 Alternative 3 - Annual O&M Costs 1-32
Figure 1.27 Alternative 4 - Process Flow Schematic 1-34 Figure 1.28 Alternative 4 - Proposed Layout 1-35
Figure 1.29 Alternative 4 - Projected Electrical Consumption 1-37 Figure 1.30 Alternative 4 - Digester Gas End Uses 1-38
Figure 1.31 Alternative 4 - Annual O&M Costs 1-39
Figure 1.32 Alternative 5 - Process Flow Schematic 1-40 Figure 1.33 Alternative 5 - Proposed Layout 1-41
Figure 1.34 Alternative 5 - Projected Electrical Consumption 1-43 Figure 1.35 Alternative 5 - Digester Gas End Uses 1-44
Figure 1.36 Alternative 5 - Annual O&M Costs 1-44
Figure 1.37 Alternative 6 - Electrical Process Schematic 1-46 Figure 1.38 Alternative 6 - Biogas Process Schematic 1-46 Figure 1.39 Alternative 6 - Digester Gas End Uses 1-48
Figure 1.40 Alternative 6 - Annual O&M Costs 1-49
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN iv
Abbreviations
APCD Air Pollution Control District
BACT Best Available Control Technology
BTU/scf British thermal units per standard cubic foot
C Celsius
CEQA California Environmental Quality Act
cfd cubic feet per day
cfm cubic feet per minute
cfs cubic feet per second
City City of Santa Maria
CNG compressed natural gas
CO2e carbon dioxide equivalent
DG digester gas
FCE fuel cell energy
FOG fats, oils, and grease
ft foot or feet
ft3 cubic feet
H height
H2S hydrogen sulfide
hp horsepower
IRA Inflation Reduction Act
ITC Investment Tax Credit
kWh kilo-watt hour
L length
lb pound
LCFS Low Carbon Fuel Standard
LHV lower heating value
MG million gallons
mgd million gallons per day
MMBTU million British thermal units
MW megawatt
MWh megawatt hour
N/A not applicable
NOx nitrogen oxides
NREL National Renewable Energy Laboratory
O&M operations and maintenance
PG&E Pacific Gas and Electric
PPA Power Purchase Agreement
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN v
ppd pounds per day
ppm parts per million
PS primary sludge
PV photo-voltaic
RFS Renewable Fuel Standard
SB Senate Bill
scfm standard cubic feet per minute
SGIP Self-Generation Incentive Program
TOU Time of Use
VFD variable frequency drive
VOC volatile organic compounds
VSS volatile suspended solids
W width
WAS waste activated sludge
WWTP wastewater treatment plant
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-1
CHAPTER 1 ENERGY MANAGEMENT

1.1 Introduction
The City of Santa Maria (City) runs a comprehensive liquid and solid wastewater treatment plant (WWTP) that treats flows of about 6.5 million gallons per day (mgd) on average in 2024. The liquid stream facilities consist of headworks, clarifiers, trickling filters, and percolation ponds. The solid stream facilities consist of thickeners, digesters, and sludge drying beds. A laboratory, an operations building, a modular building, and an administration building on-site house staff and permit management of the site. Per Volume 6 of this Master Plan, the City has selected the following treatment process for the Phase 1 expansion project:
 4-Stage Bardenpho Activated Sludge Process with Primary Clarifiers and Digesters.

Figure 1.1 shows the proposed process treatment layout for this alternative.

Figure 1.1 Selected Treatment Alternative for Santa Maria WWTP The expansion of the WWTP per the selected alternative will require a significant increase in electrical power demand, up to approximately 668 kilowatts (kW). The selected treatment alternative also includes upgrading the existing anaerobic digesters that will produce digester gas for beneficial use. As such, this Volume of the Master Plan will discuss alternatives for beneficial use of the digester gas, and develop process schematics, layouts, and cost estimates for each.

The City has identified and scoped a 720-kW solar array for use on its existing property adjacent to the WWTP. The energy alternatives considered in this Volume will proceed with the inclusion of that solar array. This means that each alternative will account for a corresponding reduction in electrical demand resulting from the solar array.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-2
The alternatives for beneficial use of biogas to be evaluated are as follows:

1. Alternative 1 (Base Case and current operation): Heat Recovery with Boilers and flare remaining digester gas (DG).

2. Alternative 2: Alternative 1 + Power Management using Microgrid and Battery.

3. Alternative 3: Power and Heat Generation using 635 kW Gas Engine + Power Management using Microgrid and Battery.

4. Alternative 4: Power and Heat Generation using 400 kW Microturbine + Power Management using Microgrid and Battery.

5. Alternative 5: Power and Heat Generation using 400 kW Microturbine + Power Management using Microgrid and Battery.

6. Alternative 6: Heat Recovery with Boilers + Compression of remaining biogas to Compressed Natural Gas (CNG) for Pipeline Injection + Power Management using Microgrid and Battery.

The goal is to evaluate the most feasible and cost-effective alternative for the beneficial re-use of biogas and energy recovery.

1.2 Data Gathering

1.2.1 Current Electrical Demand and Charges
To supply power to the site, the City is serviced by Pacific Gas and Electric (PG&E). A 1-megawatt (MW) backup generator is also available to provide standby power when needed. PG&E works with Central Coast Community Energy to procure and deliver the required electricity.

The historical energy use by month for the period of September 2023 to August 2024 for the Santa Maria WWTP is shown in Figure 1.2. As indicated, the highest power use occurred in the colder winter months, reaching an average of 185,000 kilowatt-hours (kWh) in January 2024.

Figure 1.2 WWTP Average Monthly Usage (September 2023 - August 2024) VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-3
The daily power usage averaged 5,600 kWh in 2023 to 2024; approximately 233 kW of continuous load. As noted, higher usage was seen in the winter months, but there is a lot of variation at the site.

Peak demand to the site provides insight into the maximum electrical loads required for the site. The peak demands are shown over the same period in Figure 1.3. Peak demand in this case is the highest instantaneous load provided to the site during the entire billing period.

Figure 1.3 WWTP Peak Demand by Month (September 2023 - August 2024) The peak demand per month showed less variation, reaching a maximum of 320 kW, with slightly lower peaks observed during the summer months.

1.2.1.1 Current Electrical Costs
The City is currently on a BS19-S Medium High Use plan. This "Medium-High" Use indicates demand consistently between 500-1,000 kW. The "S" option in the BS19 plan indicates the City has storage of a rated capacity of 10 percent of the peak demand. This is a Time-of-Use (TOU) plan, which states that the prices for each unit of energy delivered and utilized are dependent on the time of day and season.

Depending on the required electrical demands of the facilities after Phase 1 construction, and the potential for storage and renewable generation on-site, the City may need to enroll in a B20 High Use Plan, which is suited for sites that have peak demands greater than 1 MW over three consecutive months in a year. For the purposes of this evaluation, it will be assumed that the B19-S plan will remain in effect due to the potential demand reductions resulting from the new solar facility and energy management systems to be evaluated.

Monthly average rates for WWTP for year 2024 are presented in Figure 1.4. As shown, the average electricity cost per kWh on a monthly basis ranges from $0.18/kWh to $0.26/kWh.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-4
Figure 1.4 WWTP Cost per Kilowatt-Hour (September 2023 - August 2024) The electric plan also charges peak and maximum demand fees, based on the demand required to be supplied by the plant. This cost depends on the time of day, and on the max amount of power delivered to the plant (kW) in a time period. The peak demand cost varies from $2.5/kW to $53/kW.

1.2.2 Projected Electrical and Heating Demand for New/Modified WWTP The future WWTP peak electrical demand is based on the sum of equipment power demands in each process area. The loads for each pump and piece of mechanical equipment were estimated using a variety of methods, including pump power equations, similarly sized operating facilities, and other electrical loading estimators.

Based on the process units at each treatment area (included in Appendix A), the total connected load estimated for the Phase 1 treatment facilities is 1,670 kW, based on the design flow rates and loading.

Recently, due to the standardization of variable frequency drives (VFD's) and improved equipment efficiencies, demand factors are utilized to provide an accurate estimation of the power draw at the plant.

Demand factors are applied to the potential connected load, and provide an estimate of the average electrical load for a facility.

For normal operation, a 40 percent demand factor was applied. This further helps to temper the differences in electrical demand during the ramping up of equipment. As such, the projected electrical demand for the new upgraded WWTP are shown in Table 1.1.

Table 1.1 Projected Daily Demand Based on Normal Operation Connected Load (kW)(1) Expected Average Daily Demand (kW)(2,3) 1,670 668
Notes:
(1) Connected load is the sum of all the loads connected to a power source. (2) Maximum Demand is the loading after a 40 percent demand factor is applied, and represents the electrical demand for the site.
(3) Demand factors are typically 40 percent for WWTP plants.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-5
As illustrated above, the average demand of the site under normal operation is anticipated to reach 668 kW. This is approximately three times the existing usage at the facility.

In order to analyze the effect of energy alternatives on site power, the daily electrical demand was normalized to flow. The projected electrical demand curve for the site is illustrated in Figure 1.5.

Figure 1.5 WWTP Projected Hourly Demand
Using this projected daily demand curve, the impacts of renewable and cogeneration alternatives can be evaluated on an hourly basis.

1.2.2.1 Solar Array
The City has contracted with Forefront Power to design a solar array located on City property east of Black Road. Power generated by the new photo-voltaic (PV) solar array will be connected by an overhead line to the existing plant's electrical power supply. The power from the solar array will be connected downstream of the utility connection from Pacific Gas and Electric (PG&E) and directly feed the plant. The current design AC output of the solar array is 720 kW.

The solar will offset a significant portion of the daily electrical demand of the site. According to the National Renewable Energy Laboratory (NREL) PV Watts Calculator, which incorporates a site's weather patterns and array characteristics, a daily power output curve for the site can be produced. Using the relationship of electrical demand, as shown above, and the calculated PV output, the net demand can be determined, which is shown as the orange curve in Figure 1.6. During the daylight hours the net demand drops as a result of the output from the solar system, which is shown in the blue curve.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-6
Figure 1.6 WWTP Projected Hourly Net Demand With Solar Output As indicated in Figure 1.6, the net demand from 7 p.m. to 6 a.m. (night-time) is the highest at a little over 900 kW and then decreases to about 300 kW. The net demand during the day (7 a.m. to 6 p.m.), starts low due to the PV output and then begins to increase in the early evening when the plant electrical loads are expected to be the highest. The average solar production and net demand for the plant are shown in Table 1.2.

Table 1.2 Projected Average Daily Demand Based on Normal Operation Average Solar Production (kW) Average Net WWTP Demand (kW) 183 502

1.2.2.2 Projected Heating Demand for Solids Treatment
The Phase 1 Expansion will include the construction of an additional anaerobic digester. Based on design criteria highlighted in Volumes 3 and 6, there will be a total of 1.3 million gallons (MG) of anaerobic digestion constructed. This constitutes an increase of 0.25 MG of digester volume relative to current operation. The heating requirements corresponding to the expansion in volume and thickened sludge are shown in Table 1.3.

Table 1.3 WWTP Expansion Anaerobic Digester Heating Requirements System Anaerobic Digester Heating Requirement (MMBTU/day)(4) Current System 19.2 MMBTU/day(1)
Future System 26 MMBTU/day(2) - 34 MMTBU/day(3)
Notes:
(1) Digester 1 and 3 in operation. City staff have noted this may be over-rated for the heat capacity currently. Future heating load requirements may differ after Phase 1 expansion.
(2) Digester 4 and new digester in operation.
(3) All three digesters in operation.
(4) Assumed 94 percent boiler efficiency.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-7

1.2.3 Current and Projected Digester Gas Production
The City currently uses digester gas in boilers for heating the digesters. Any excess gas not used by the boilers is flared. There are two hot water boilers on-site: the primary boiler (Boiler No. 1) burns digester gas with propane gas as a backup, while the standby unit (Boiler No. 2) burns only propane. Gas produced by the anaerobic digesters is sent to Boiler No. 1 as the primary heat source for the hot water system, which heats the anaerobic digesters to 35 degrees Celsius (C). The standby propane boiler (Boiler No. 2) is only utilized when Boiler No. 1 cannot keep up with the heat demand of the digesters or when it is out of service. Any excess gas not used by the boilers to maintain the temperature is flared. Waste Gas Flare 1 and 2 burn excess digester gas and are ignited by a propane pilot. Currently, approximately 22 percent of the gas (about 24.6 standard cubic feet per minute [scfm]) is sent to the boiler, and the remaining 78 percent is flared.

Table 1.4 summarizes the average amount of gas produced on a monthly basis and the average specific yield (gas CH3 produced/pound of volatile suspended solids [VSS] removed) of the digesters since 2018.

Table 1.4 Average Monthly Digester Gas Production and Yield (2018-2024)(1) Digester VSS Removal
Efficiency
Monthly Biogas Produced
(ft3) [cfm]
Biogas Yield
(ft3 of Gas Produced / lb VSS removed)
Biogas CH4
Content
Digester No. 1 57% 2,461,000 [57.0 cfm] 12.9 ~60%
Digester No. 3 56% 2,040,000 [47.2 cfm] 19.3 ~60%
Notes:
cfm - cubic feet per minute; ft3 - cubic feet; lb - pound (1) Includes 2024 data to September 2024.

Using historically observed yields and the currently developed preliminary design criteria for the 4-Stage Bardenpho with Primary Clarifiers, the amount of VSS destruction and the future digester gas production can be estimated.

Table 1.5 highlights the design criteria of the future Phase 1 digestion facilities derived from the BioWin process model presented in Technical Memo 01 and Volume 6.

Table 1.5 Phase 1 Expansion Anaerobic Digester Design Criteria Design Criteria
Estimated VSS Loading From PS
and Thickened WAS(1)
(lb/day)
Future Digester
Volume(2)
(ft3)
Anticipated Biogas
Production(3)
(cfd) [cfm]
Digestion System 32,225 173,780 227,000 to 258,000
[158 to 180 cfm]
Notes:
cfd - cubic feet per day
(1) Design estimates from Volume 6 of the Master Plan.
(2) Future Digester Volume from Volume 6 of the Master Plan, new digester to be built in Phase 1. (3) Biogas Production modelled in BioWin software based on design flow rates.

The projected amount of biogas produced for Alternative 4 under Phase 1 conditions is estimated to be between 227,000 and 258,000 cfd [158 and 180 cfm], in 2034 and 2054, respectively. Assuming a 60 percent methane concentration and 600 British Thermal Units per standard cubic feet (BTU/scf), the energy content inherent in that quantity of gas is between 136 and 155 million British thermal units (MMBTU)/day.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-8
For the purposes of evaluating the biogas reuse alternatives, the future amount of projected biogas will utilize the values indicated in this section.

1.2.3.1 Food Waste and Fats, Oil and Grease
Fats, oils, and grease (FOG) is a global term to describe the waste typically discarded from kitchens during cooking, food preparation, or cleaning. Most industrial kitchens have grease traps to prevent grease from being discharged to the sewers. FOG can harden in pipes and cause clogging and sewer flow backups.

Most cities, including the City of Santa Maria, have programs to educate residents and businesses about proper disposal practices. The City of Santa Maria’s FOG program includes grease trap inspections and enforcement measures for commercial establishments. Any captured grease under their existing program is cleaned by grease haulers and disposed outside of the City’s service area. Historically, FOG may be considered as a metered component of the feed stream to anaerobic digesters to enhance biogas production, but this impact may be minimal for the City’s operations.

The State of California introduced a food waste program via Senate Bill (SB) 1383, which was approved in 2016. SB 1383 is aimed at reducing landfill disposal and methane emissions from landfills, as well as diverting edible food to those in need. It mandates a 50 percent reduction in organic waste disposal by 2020 and a 75 percent reduction by 2025. Some agencies also choose to add pretreated and blended food waste to their anaerobic digesters in order to further enhance biogas production.

The City currently operates a Food Disposal program focused on reducing the quantity of food disposed in trash bins and promotes the disposal of food waste to yellow bins for composting. This waste is currently diverted along with other green waste to the Engel and Gray composting facility.

For the following reasons, food waste addition into the anaerobic digesters at the WWTP was not considered:
 Chemical Imbalances in Anaerobic Digesters:
» FOG primarily consists of lipids. At high concentrations, the increased loading of lipids into the digester can disrupt the existing bacteria present in the digesters and cause upsets to normal operation and gas production.
 Existing Composting Facility - Engel and Gray:
» Engel and Gray is an existing composting facility located adjacent to the WWTP. The facility currently processes the biosolids from the anaerobic digesters along with biosolids from many wastewater agencies on the Central Coast. Additionally, Engel and Gray also receives and processes green waste from the City and other various agencies and commercial businesses. » It is expected that food waste will continue to be treated by Engel and Gray or at the landfill well into the future. Therefore, an alternative disposal method is not needed.  Biogas Production:
» The projected rates of biogas production from plant primary sludge (PS) and waste activated sludge (WAS) are expected to be sufficient to meet projected plant electrical and heating demands. Therefore, enhancing biogas production via a FOG or food waste treatment program would not provide benefits as the additional gas would need to be flared.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-9

1.3 Power/Heating Generation and Management Technologies This section summarizes the various technologies that were evaluated and considered to meet the plant's proposed power and heating demands.

1.3.1 Emissions Regulation
The technologies proposed are intended to remain in compliance with California climate legislation. As noted in Volume 2 Chapter 4 of the Master Plan, wastewater facilities are required to report greenhouse gas emissions to the California Air Resource Board if they produce greater than 10,000 metric tons of carbon dioxide equivalent (CO2e) per year. The City of Santa Maria WWTP currently does not produce that number of emissions under current operations.

The emissions potential for each of the technologies proposed under this section are considered for any net increase in CO2e emissions compared to existing conditions. The City currently utilizes flares and boilers to re-use biogas. Since combustion of biogas will proceed under existing conditions, the net increase of emissions from the implementation of cogeneration units like microturbines, boilers, fuel cells, and gas engines will be minimal. The largest net increase of emissions would result from higher amounts of methane slippage into the atmosphere, but this may be mitigated by keeping the existing flares as standby.

In addition, the other power generation technologies evaluated, including wind energy and a microgrid, both would reduce the overall emissions potential at the facility.

The final selected alternative for power management and generation will need to be incorporated into the CEQA process.

1.3.2 Gas Engines
The selected systems for this analysis are Jenbacher gas engines. Jenbacher is an international supplier of gas engines for the re-utilization of biogas. The product and its rated specifications are shown in Table 1.6. As shown, two alternatives were considered to meet the net demand.

Table 1.6 Gas Engine Specifications
Gas Engine
Model
Maximum
DG Usage
(cfm)
Electrical
Output
(kW)
Thermal Output
(MMBtu/
day)
Electrical
Efficiency
Thermal
Efficiency
Dimensions
(ft, L x W
x H)
Filled Weight
(lbs)
JenBacher
J208 87 335 kW 33.9 36.3%(1) 42.3%(1) 17 x 6.7 x 5.7 11,700 JenBacher
J312 164 635 kW 63.2 39.7%(2) 49.9%(2) 16 x 9 x 9 18,800 Notes:
ft - foot/feet; H - height; L - length; W - weight
(1) Efficiency percentages as reported by the manufacturer. To be conservative, efficiency values were reduced to 33 percent and 39 percent, respectively, in the calculations.
(2) Efficiency percentages as reported by the manufacturer. To be conservative, efficiency values were reduced to 33 percent and 43 percent, respectively, in the calculations.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-10
Ultimately, after receiving quotations from the vendor for the engines, the Jenbacher J208 analysis was discontinued - the quotation received for this smaller-sized engine had a larger capital cost than the larger engine. The smaller engine provides less electrical output and thus would recoup less cost than the larger engine.

An image of the Jenbacher J312 Gas Engine Unit is shown in Figure 1.7. The J312 model is a gas engine which combusts biogas for both heat and electricity. The J312 features a 12-cylinder V-engine configuration. The exhaust heat produced from this process can be captured using the internal heat exchangers, economizers, and radiators on the unit. The existing WWTP utilizes a hot water loop that is used to heat the thickened digester sludge; the exhaust heat from the engine could be configured to supply heat to the existing hot water loops to maintain current operational practices.

Figure 1.7 Jenbacher J312 Gas Engine

1.3.3 Microturbines
The selected systems for this analysis are Capstone microturbines. Capstone microturbines are an international supplier of microturbines for the re-utilization of biogas.

The manufacturer, Capstone Turbine Corporation, provides heat recovery modules and microturbines. The microturbines are provided within an enclosure that houses multiple modular microturbines. The following Table 1.7 indicates the rated specifications for the microturbines.

Table 1.7 Microturbine Specifications
Microturbine
Model
Electrical Output
(kW)
Thermal Output
(kW) Electrical Efficiency Thermal Efficiency Dimensions(ft, L x W x H) Capstone C400S 400 kW 414 kW 33% 42% 20 x 10 x 10
Capstone C600S 600 kW 760 kW 33% 42% 20 x 10 x 10
Notes:
(1) Efficiency values are rated values provided by the manufacturer. Efficiency values were reduced to 28 percent and 39 percent, respectively, in the calculations.

Figure 1.8 shows the enclosure that houses the turbines. The enclosure size for both the C400S and the C600S options is the same. The only difference between the two is that the C600 option includes 3x200 kW microturbines within the enclosure, whereas the C400 option includes the 2x200 kW microturbines within the same enclosure. Microturbines integrate turbine engines and magnetic generators to generate electricity. The exhaust heat is in the form of hot gas that can be sent to heat VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-11
recovery modules to reheat digester sludge streams. Similarly to the gas engine, this exhaust heat can be captured and subsequently exchanged with the existing closed hot water loop that currently heats the digesters. This permits existing WWTP process and operation to be preserved.

Figure 1.8 Capstone C600S Enclosure

1.3.4 Pipeline Injection
Pipeline injection refers to the cleaning and compression of biogas into CNG. CNG can be then injected back into existing SoCalGas distribution pipelines.

The nearest natural gas pipeline to the Santa Maria WWTP is illustrated in Figure 1.9. The SoCalGas distribution gas line reaches a terminus at Betteravia Road, about 2-miles from the WWTP, and may have capacity to accept additional compressed natural gas from the WWTP. Further, there is a CNG fuel station located about 0.6-miles from the proposed pipeline injection site. The proximity of the CNG fuel station and the pipeline to the plant provides a potential opportunity for this technology.

However, there are stringent requirements that are necessary for pipeline injection to proceed. To initiate a pipeline injection project, the following interconnection studies are needed:

1. Rule 45: Interconnection Studies:
a. Interconnection Screening Study: Evaluation of the closest pipeline's capacities and their corresponding injection volumes. This is completed by SoCalGas free of charge. b. Preliminary Engineering Study: A preliminary study to evaluate the feasibility and the constructability requirements for pipeline injection. This study has an estimated cost of $100,000. c. Detailed Engineering Study: A comprehensive study that provides engineering reports and recommendations for construction and injection. These studies are expected to cost $1.64 million. d. There must be sufficient demand for CNG at the Interconnection point for SoCalGas to permit the project.

2. Rule 30: Gas Specifications:
a. In order to be utilized, the gas must be conditioned prior to entry into the pipeline system. Water content, heating values, inert chemicals, and hydrogen sulfide levels are all carefully monitored by an online monitoring system. If the gas does not meet the on-line quality requirements a valve in the pipeline will automatically close and the gas will need to be flared.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-12
Figure 1.9 Proximity of WWTP to SoCalGas Pipeline
Pipeline injection would require the construction of a natural gas pipeline that can send any produced biogas to existing SoCalGas distribution lines.

1.3.5 Boilers
Boilers are the current form of heat recovery utilized by the site. The local distributor for firetube boilers in the region is RF Macdonald, which provides boilers from Cleaver Brooks. The model currently utilized by the City is a CB-700-60 firetube boiler with a rated heat input of 2.51 MMTBU/hour. The selected model for this analysis is the CBJT firetube boiler, shown in Figure 1.10. This firetube boiler runs on both natural gas and propane and achieves <30 parts per million (ppm) nitrogen oxides (NOx) in the exhaust.

The specifications for this boiler are indicated in Table 1.8.

Table 1.8 Boiler Specifications
Boiler Model Fuel Source Boiler Horsepower
(hp)
Possible Heat Output(1)
(MMBtu/hour)
Dimensions(1)
(ft, L x W x H)
CBJT-2D Natural gas, propane 50-200 2.01 13 x 5 x 4.5
Notes:
hp - horsepower
(1) 60-hp boiler dimension shown.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-13
Figure 1.10 Cleaver Brooks CBJT Boiler
Firetube boilers combust biogas or propane to heat flue gases. The hot flue gas transmits heat to water within the boiler shell. As the heat is transferred from combustion to the water within the shell, the hot water/steam can subsequently transfer heat to any adjacent hot water loops that can heat the thickened sludge lines feeding the digesters.

1.3.6 Microgrid
For the purposes of this analysis, microgrids are considered as part of the energy management solutions.

A microgrid consists of battery storage and a control system that regulates on-site electrical generation and electrical demands from the treatment facility. A microgrid at the Santa Maria WWTP would include the new solar array and a battery system, which would store electricity generated by the solar panels and supply it to help meet the facility's energy demands. The microgrid would also match instantaneous plant demands with the generation of electrical power from a biogas beneficial reuse system.

Further, the City currently has a 1 MW standby generator that would remain and be connected to the microgrid system to provide backup power in the event of a failure. It is anticipated that a larger standby generator will be installed.

A microgrid combined with different alternatives for beneficial reuse of biogas would provide cost savings from the offset of peak purchase prices. It may also provide resilience in the case of blackouts. It is also considered for the analysis because of the net demand; it is optimal to recover and charge a battery with energy produced from biogas rather than returning energy back to the grid via a net metering program.

To evaluate the microgrid and its cost savings, the HOMER grid software was used. This software optimizes the cost savings that can be generated from a microgrid. More information on the HOMER software is be provided below.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-14
Figure 1.11 provides a representation of a microgrid.

Source: DVL Group, 2024, https://www.dvlnet.com/blog/microgrids-part-1.

Figure 1.11 Example Representation of a Microgrid

1.3.6.1 HOMER Software
HOMER Grid is a simulation and optimization tool designed to help engineers, project developers, and energy planners design and analyze distributed energy systems. In this case, HOMER provided the optimal sizing of the battery for the site based on energy requirements and generated average cost reductions from peak load shaving. By using the electric inputs discussed above, an accurate representation of the cost savings from the battery and the microgrid can be developed.

Using the projected PV output, the existing BS-19S tariff structure, and the projected electrical demand as inputs, the software compared the costs and electrical production of the WWTP for two cases:

1. Purchasing electricity from PG&E and using the solar array.

2. Purchasing electricity from PG&E, using the solar array, and load shaving with a battery and microgrid.

Using the inputs, the software estimated a battery storage requirement of 3.5 MWh, with 4 hours of autonomy. This storage requirement corresponds to roughly a 1 MW battery, as a cost-optimal size for the electrical demand of the WWTP.

In Case 1, evaluating the grid and the solar array, HOMER produced the following average annual cost and electrical production in Table 1.9 (averaged over 20 years).

Table 1.9 Case 1 - Homer Software Results - Grid and Solar Only Rated Battery
Size
(kWh)
Electricity Purchased
From Grid
(kWh)
Consumption
Charge(1)
($)
Demand Charge(1)
($)
Fixed Cost(1)
($)
Total(1)
($)
N/A 3,684,727 445,138 307,859 4,105 757,101
Notes:

N/A - not applicable
(1) Average annual cost, 2025 dollars.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-15
Based on the provided metrics from the software, the average annual cost per kWh may be determined.

By dividing the total cost by electrical production, the resultant cost per kWh is equal to $0.21/kWh.

In Case 2, evaluating the grid, the solar array, and a battery, HOMER produced the following average annual cost and electrical production in Table 1.10 (averaged over 20 years).

Table 1.10 Case 2 - Homer Software Results - Grid, Solar, and Battery Rated Battery
Size
(kWh)
Electricity Purchased
From Grid
(kWh)
Consumption
Charge(1)
($)
Demand Charge(1)
($)
Fixed Cost(1)
($)
Total(1)
($)
3,450 3,684,727 445,138 188,012 4,105 637,254
Notes:
(1) Average annual cost, 2025 dollars.

Based on the provided metrics from the software, the average annual cost per kWh may be determined.

By dividing the total cost by electrical production, the resultant cost per kWh is equal to $0.17/kWh.

As such, by comparing Case 1 and Case 2, the average cost savings from load shaving and battery storage are equal to $0.04/kWh. This value is applied to each alternative' electric consumption after cogeneration to evaluate the benefit of the battery system.

HOMER grid software also provided values for the operations and maintenance (O&M) cost of the batteries, their replacement cost, and their capital cost annualized over the lifespan. These values are provided in each individual section.

1.3.7 Wind Energy
For the purposes of this analysis, wind energy was considered as a possible power source. The WWTP is located about 9 miles from the ocean and regularly receives ocean breezes. However, after investigation, it was determined that wind energy will not provide sufficient value to justify its installation. This is due to multiple factors, including stringent siting requirements, available power demand, permitting challenges, and size constraints. Further, with the utilization of solar and the potential beneficial reuse of digester gas, the energy recovery from a wind turbine will not yield the necessary payback required for the system.

Some of the constraints associated with wind turbine systems are:
 Siting Requirements:
» Wind turbines occupy more vertical space than other renewable energy systems, such as solar, for example, making them subject to height and aesthetic restrictions that other systems may not be subject to.
» Wind turbines cause noise pollution that will require additional permitting notifications under California Environmental Quality Act (CEQA).
» Wind turbines at the size appropriate for the WWTP could become a hazard for the large number of birds that migrate to and from the site.
 Available Power Demand and Capital Cost:
» As mentioned above, the net power requirements for the facility are projected to range from 100-900 kW. As such, the wind turbine for this site would likely be sized around 600 kW. However, according to the Department of Energy, average wind turbine sizes range much larger in the VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-16
2,500-3,000 kW range. Due to the significant capital cost required, the 600 kW wind turbine required for the site would be less likely to provide sufficient value to recoup the capital cost.  Smaller-sized wind turbines are less efficient due to less wind capture and sweep area.  The variability of wind speed would decrease the efficiency of the turbines, further reducing the value of its investment.

1.3.8 Fuel Cells
Power and heat recovery by using biogas in Fuel Cells was also evaluated. After discussions with Fuel Cell Energy (FCE), a manufacturer of fuel cell systems in Southern California, internal experts, and with Power Purchase Agreement (PPA) purveyors, it was determined that this technology is not a feasible alternative.

The reasons for this are:

1. There would be insufficient biogas flow and associated energy savings for the energy provider to recoup the required capital. There are no known installations in WWTPs of small fuel cell systems of the size that would be applicable for this facility. Most systems in operation that have a reasonable track record are significantly larger.
a. Examples of fuel cell systems in operation at WWTPs in California include:
i. City of Sacramento - 2.8 MW.
ii. City of San Bernardino - 1.4 MW.
iii. City of Chino WWTP - 2.8 MW.
iv. City of San Diego South Bay - 1.4 MW.
v. City of Riverside - 1.4 MW.

2. Fuel cells are sensitive to fluctuations of biogas flows, more so than other alternatives, and fuel cells are sensitive to the quality of the biogas. This may develop into significant process challenges later on, particularly if any provider is not involved in the design process.

Based on this evaluation, it was concluded that suitably sized fuel cells with a good operational track record in WWTPs were not currently available. For these reasons, fuel cells were not considered any further.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-17

1.4 Site Layouts
On the existing WWTP, northwest of the digester control building, and southeast of the operations warehouse, there is space that would be available for the construction and development of Digester Gas Beneficial Use facilities. This space spans roughly 100 ft by 160 ft and is located just northwest of the digesters, with existing underground gas piping that can connect to the proposed treatment trains.

The available space is indicated in the following Figure 1.12.

Figure 1.12 Available Space for Cogeneration Alternatives VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-18
On the existing WWTP, there is also space to house the future battery storage and microgrid system. The microgrid and battery will be located on the existing site to facilitate connection to the CHP system and the PG&E interconnection point located in the administration building. The location of the solar array is located in the parcel of land east of Black Road and will be connected to the microgrid and the primary switchboard with transmission lines.

The locations are illustrated on Figure 1.13.

Figure 1.13 Proposed Locations of the Power Management Systems at Santa Maria WWTP

1.5 Digester Gas Beneficial Use Alternatives
As presented above, the following alternatives are evaluated for beneficial use of the digester gas:

1. Alternative 1 (Base Case and current operation): Heat Recovery with Boilers and flare remaining DG.

2. Alternative 2: Alternative 1 + Power Management using Microgrid and Battery.

3. Alternative 3: Power and Heat Generation using 635 kW Gas Engine + Power Management using Microgrid and Battery.

4. Alternative 4: Power and Heat Generation using 400 kW Microturbine + Power Management using Microgrid and Battery.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-19

5. Alternative 5: Power and Heat Generation using 600 kW Microturbine + Power Management using Microgrid and Battery.

6. Alternative 6: Heat Recovery with Boilers + Compression of remaining biogas to CNG for Pipeline Injection + Power Management using Microgrid and Battery.

1.5.1 Alternatives Evaluation Basis
For each alternative, the following will be developed:
 Preliminary treatment process layout.
 Preliminary sizing of equipment.
 Life Cycle Cost Estimate:
» Includes construction cost and O&M costs normalized over 20 years. » Net Present Cost and Compound Payback used as financial metrics.

The alternatives were compared based on cost, feasibility, and O&M implementation. The life-cycle costs of the cogeneration alternatives will utilize financial assumptions based on the values represented in Chapter 2 of this Master Plan. The starting point of the analysis is 2034, when construction of Phase 1 is expected to be completed.

The analysis will proceed using HOMER Grid software and Excel modeling that optimizes the electrical savings that can be generated from hybrid electrical systems. HOMER Grid software determines the optimal battery size for the required electrical output and calculates the annual cost savings of each option compared to using only the solar array and the grid. These savings are reflected as an average cost per kilowatt-hour ($/kWh) for either scenario.

To fully capture the utility of each cogeneration alternative, a 20-year life cycle analysis was completed in conjunction with the HOMER software reports. The following assumptions were used to guide the analysis:

1. All alternative savings are compared to the existing system, consisting of a solar array and purchasing from the grid.

2. Any excess gas flow not recovered by each system is flared or sent to a pipeline.

Appendix B provides details of the life cycle cost analysis tables and HOMER Grid reports developed for this section.

1.5.1.1 Grants and Power Purchase Agreements
Grants and financial aid were considered in the analysis. California and the federal government offer incentives for energy recovery. This applies to multiple forms of generation.

Although grants and financial aid are reported in this analysis, it is important to consider that the grants are not necessarily permanent. Subsidies may change and are reliant on continued funding from the California State Legislature. For example, the Biomethane Monetary Incentive Program is currently funded until 2026, well before the scope of the project, and the Self Generation Incentive Program (SGIP) is currently funded through 2025.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-20
Federal programs include the Renewable Fuel Standard (RFS) that mandates renewable fuels to be blended into the Nation's fuel supply and thus provides incentives for renewable fuel production. It also includes the Investment Tax Credit (ITC), which provides tax credits for the capital costs of battery storage systems. ITC funding is currently available until December 31, 2032, under provisions of the Inflation Reduction Act (IRA).

The following credits and incentives were considered for each alternative and are shown in Table 1.11.

Table 1.11 Financial Incentives for DG Beneficial Use Alternatives(1) Alternative Available Incentive
1 - CHP Gas Engine  SGIP
2 - Microturbines  SGIP
4 - Pipeline Injection  California's Low Carbon Fuel Standard (LCFS)  RFS
 BioMethane Monetary Incentive Program
5 - Solar and Batteries Microgrid  ITC
Notes:
(1) Refer to Alternative 3 Section Below.

In order for any generation technology to receive an SGIP grant, the project must be a local governmental agency wherein at least 50 percent of the census tracts that are served are disadvantaged, tribal, or low-income. According to the CPUC Non-Residential Eligibility Map that tracks the status of those criteria, the Santa Maria WWTP expansion qualifies for this program. As such, each alternative was evaluated for the benefits and grants provided under this program. The details of each incentive and whether the proposed technology or alternative would apply are discussed in each section.

It is important to note that the qualification of the incentives also requires an increase in the monitoring and reporting requirements of each alternative.

PPA's were also considered. In PPA's, a company provides the upfront cost, maintains the system, and owns the energy system, in exchange for higher fees and electrical costs from the utility (in this case, Santa Maria). However, discussions with various PPA vendors and cogeneration technology suppliers indicated there was not enough demand at this time for those companies to provide this service. PPA's may be a potential option moving forward, however the establishment of PPA's will require increased interest and continued discussions between a financial provider and City representatives.

1.5.2 Alternative 1 (Base Case and Current Operation): Heat Recovery With Boilers and Flare Remaining DG
This alternative represents a "no change" alternative to current operations with regards to heat recovery; a new boiler and flaring system will be installed as a direct replacement to the existing system. The boiler and flaring system will both be configured in a duty-standby system. There will be a minor fuel treatment system, including H2S and moisture removal, installed prior to the boilers to extend the operational life of the boilers, consisting of a single vessel, gas blower, and particulate filter.

Electrically, a solar array and purchase from the grid will power the plant. This alternative would not include a microgrid control system or batteries.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-21
The following process schematic for this alternative is illustrated in Figures 1.14 and 1.15.

Figure 1.14 Alternative 1 - Electrical Process Schematic Figure 1.15 Alternative 1 - Biogas Process Schematic

1.5.2.1 Life Cycle Cost Analysis
The following design parameters were modelled over a 20-year period. The annual life cycle assumptions utilized for the system were developed using the following baseline criteria in Table 1.12.

Table 1.12 Life Cycle Analysis Criteria - Alternative 1 Parameters Units Values
Estimated Average Biogas Production(1) cfm 158 - 180
Available Energy From Biogas MMBTU/hr 5.7 - 6.4
Boiler Heat Recovered(2) MMBTU/hr 1.1 - 1.4
Boiler Efficiency % 94
Gas Flared cfm 102 - 139
Notes:
(1) Range of values represents start of 20-year period to end of 20-year period, comment typical for every range illustrated. (2) Heating requirement of anaerobic digesters.

The capital cost for the new duty-standby boilers, gas conditioning and flares was developed using a budgetary cost estimate of the equipment. Indirect cost factors, contingencies and financial factors VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-22
presented in Volume 2 of this master plan were applied. The capital cost was escalated to 2034 dollars, the starting point of the analysis. The cost analysis did not include cost for the solar array as that system will be the same for all alternatives.

The power cost modeled in this scenario was based on Section 1.3.2 above. The net demand of 502 kW was averaged out over a 20-year period. Then, the 0.21$/kWh power cost was applied.

Financial Grants and Incentives
There were no financial grants and incentives considered because no energy generation or storage technologies are included in this alternative.

1.5.2.2 Results
The net demand for this alternative is 502 kW. This corresponds to an annual consumption of ~4,400 MWh per year based on net demand. The quantity of gas flared and re-used is illustrated in the following Figure 1.16.

Figure 1.16 Alternative 1 - Digester Gas End Uses
The Annual O&M costs for this alternative in 2034 are presented in Figure 1.17.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-23
Figure 1.17 Alternative 1 - Annual O&M Costs
Based on the project costs, and the annualized life cycle O&M costs, the Net Present Cost is determined and presented in Table 1.13. The Net Present Cost indicates the current cost of the alternative, represented as a lump sum to be paid at the outset.

Table 1.13 Life Cycle Cost Analysis - Alternative 1 (Base Case) Boiler and Solar 20-Year Average Annual Cost, 2025 Dollars Estimated Project Cost $13,300,000
20-year Life Cycle O&M Costs $13,200,000
Net Present Cost $26,500,000

1.5.2.3 Operational, Regulatory and Maintenance Considerations The operational requirements of this system are primarily based on the continued usage of the waste gas flare and the boiler. This system is familiar to current operational staff and thus would cause a minimal burden to continue to maintain.

The reporting and monitoring requirements of flaring would continue to be necessary. The current Air Pollution Control District (APCD) permitting process is typically renewed every 3 years. The current permitted flaring limit is about 335 cfm; this alternative would flare around 126 cfm in 2034.

1.5.3 Alternative 2: Alternative 1 + Power Management Using Microgrid and Battery
This alternative represents a "no change" alternative with regards to heat recovery; a new boiler and flaring system will be installed as a direct replacement to the existing system. There will be a minor fuel treatment system, including H2S and moisture removal, installed prior to the boilers to extend the operational life of the boilers, consisting of a single vessel, gas blower, and particulate filter. Electrically, a $1,350,000
$-
$1,260,000
$24,000
$42,000
$18,000
$3,000
Net Annual Cost
Power Cost
O&M costs for fuel treatment
O&M costs for boiler
O&M costs for solar
O&M costs for flare
Annual O&M Costs, 2034 dollars
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-24
battery and microgrid system will be installed in addition to the existing solar array. The following schematics depict the electrical and biogas process flows for this alternative (Figures 1.18 and 1.19).

Figure 1.18 Alternative 2 - Electrical Process Schematic Figure 1.19 Alternative 2 - Biogas Process Schematic

1.5.3.1 Life Cycle Cost Analysis
The following design parameters were modelled over a 20-year period. The annual electricity production generated for each system was developed using the following baseline criteria in Table 1.14.

Table 1.14 Life Cycle Analysis Criteria - Alternative 2 Parameters Units Values
Estimated Average Biogas Production(1) cfm 158 - 180
Available Energy From Biogas MMBTU/hr 5.7 - 6.4
Boiler Heat Recovered(2) MMBTU/hr 1.1 - 1.4
Boiler Efficiency % 94
Gas Flared cfm 102 - 139
Battery Size MWh 3.5
Notes:
(1) Range of values represents start of 20-year period to end of 20-year period, comment typical for every range illustrated. (2) Heating requirement of anaerobic digesters.

The capital cost for the battery system, with new duty-standby boilers and duty-standby flares, was developed using a budgetary cost estimate of the equipment. The cost of the batteries was developed from HOMER software. A small gas conditioning system installed prior to the boiler and its capital cost was developed similarly.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-25
Financial Grants and Incentives
Other assumptions incorporated into this analysis include the incorporation of incentives. The following Table 1.15 lists the incentives available for deployment of the battery system.

Table 1.15 Financial Incentives for Alternative 2
Selected Treatment Incentive Qualification? Current Rate(1,2) Projected Benefit Battery Storage  SGIP
» Large Scale Storage (>10
kW)
» Currently in Step 5
» Applied to capital cost
Yes -

3.5 MWh
system, 4-hour
duration
$ .25 / Watt-hour,
100% for first
2 hours of storage,
50% for hours 2-4
of storage
Not Applied - SGIP
funds not likely to be
available in the 2030s
Battery Storage  ITC
» 6% base credit
» Prevailing wage, low-income
community and domestic
content adders raise the
percentage by 10% each
» Applied to capital cost
Yes - federal
benefit
applicable to all
battery storage
projects

0.18% of capital
cost(3)
$316,000 - funds
expected to be
available until 2033
Notes:
(1) Current rates are subject to state subsidies and incentive programs and may not be applicable in the future. (2) Incentives based on continued compliance performance-based requirements, including efficiency and discharge. (3) Assumes domestic content and prevailing wage adders; 26 percent of the capital cost, available for ~70 percent of the total.

1.5.3.2 Results
The HOMER software sized the battery at 3.5 MWh of storage and an autonomy of 4.6 hours. As indicated in the site layout above, this sizing will be sufficient to manage the electrical loads into the site and provide peak shaving to reduce demand costs. The net demand for this alternative is the same as Alternative 1 at 502 kW. This corresponds to an annual consumption of ~4,400 MWh per year based on net demand.

The quantity of gas flared and reused is illustrated in Figure 1.20.

Figure 1.20 Alternative 2 - Digester Gas End Uses
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-26
The Life Cycle cost for this alternative was calculated utilizing multiple factors, including the cost of electricity saved by using load shaving from peak hours, the peak demand saved, and the cost O&M on the maintenance of the system. The annual O&M costs in the first year of operation are shown in Figure 1.21.

Figure 1.21 Alternative 2 - Annual O&M Costs
Based on the project costs, and the annualized life cycle O&M costs, the Net Present Cost is determined. and presented in Table 1.16.

Table 1.16 Life Cycle Cost Analysis – Alternative 2 (Base Case + Boiler, Battery, and Solar) Boiler, Battery and Solar 20-Year Average Annual Cost, 2025 Dollars Estimated Project Cost $15,100,000
20-Year Life Cycle O&M Costs $12,200,000
Net Present Cost $$27,300,000

1.5.3.3 Operational, Regulatory, and Maintenance Considerations The operational requirements of this system are primarily based on the continued usage of the waste gas flare and the boiler. This system is familiar to current operational staff and thus would cause a minimal burden to continue to maintain.

The reporting and monitoring requirements of flaring would continue to be necessary. The current APCD permitting process typically is renewed every 3 years. The current permitted flaring limit is about 335 cfm; This alternative would flare about 126 cfm of flaring in 2034.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-27
The maintenance of batteries requires battery management software and monitoring. The maintenance may also be outsourced to companies that specialize in battery management systems. However, it is important to consider that a battery will require additional monitoring.

Further, there is sufficient space, both in the facility, or near the solar array, to place the battery. Its small size and modularity allow for convenient installation.

1.5.4 Alternative 3: Power and Heat Generation Using 635 kW Gas Engine + Power Management Using Microgrid and Battery
Combined Heat and Power engines produce heat for re-use in anaerobic digesters, and electricity for re-use at the facility. Figure 1.22 presents the process flow diagram for this alternative.

The gas will be treated before entering the system to maintain high engine performance standards and meet APCD requirements for exhaust emissions. The proposed gas treatment system will include hydrogen sulfide (H2S), siloxane, and moisture removal. The specific technologies for each stage of the gas treatment shown are shown in the following list:
 Moisture Removal: knockout vessel that provides separation of gas and liquid phases of biogas.  H2S Removal: Iron sponge scrubber to remove excess H2S.  Siloxane and volatile organic compounds (VOC) Removal: Activated Carbon media vessels to remove siloxanes and VOCs in the gas that reduce longevity of the engines.  Gas Storage: In-line pressure-controlled tanks sized with 30-minute ramp down of flow (1,500 ft3).

There are other items that constitute the gas conditioning skid, including control systems, pressure regulators, temp and heat exchangers. These are considered to be integrated within the gas conditioning skid and CHP module.

The exhaust heat from the gas engines will be recovered through a series of hot water loops and used for anaerobic digesters heating. A duty-standby flare and a standby boiler will remain as a backup in the case of engine downtime.

Figure 1.22 Alternative 3 - Process Flow Schematic
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-28
The specifications for the biogas conditioning skid and their dimensions are indicated in the following Table 1.17. The conditioning skid and its dimensions are sufficient to handle the estimated biogas production.

Table 1.17 Gas Conditioning Skid Specifications
Conditioning Stage System Quantity Flow Rate
(cfm) Media Dimensions(ft, L x W x H)
Moisture Removal Knockout Vessel 1 50-350 N/A 5.5 x 3 x 5 Compression Blowers 3 15-300 N/A 10 x 5 x 5
H2S Removal Lead-Lag Vessels 2 up to 780 FerroSorp 8 x 8 x 7 Siloxane Removal GAC Vessels 2 up to 780 Calgon VPR 8 x 8 x 12 Gas Storage Pressurized Buffer Tanks 9 N/A N/A 16 x 4 x 7 Proposed site layout for this alternative is shown in Figure 1.23.

Figure 1.23 Alternative 3 - Proposed Layout
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-29

1.5.4.1 Life Cycle Cost Analysis
The following design parameters were modeled over a 20-year period. The annual electricity production generated for each system was developed using the following baseline criteria in Table 1.18.

Table 1.18 Life Cycle Analysis Criteria - Alternative 3 Parameters Units Values
Estimated Average Biogas Production(1) (cfm) 158 - 180
Available Energy Input(1) (MMBTU/hr) 5.7 - 6.4
1 x Jenbacher J312 series (kW) 635
Required Energy Input (at 100% capacity) (MMBTU/hr) 5.9 Required Input DG flow(at 100% capacity) (cfm) 164
Assumed Uptime (%) 88%
Electrical Efficiency % 33%
Power Produced (at 100% capacity) kW 615
Parasitic Electric Power kW 20
Heat Energy Recovered(2) (MMBTU/day) 26-34
Battery Size MWh 3.5
Notes:
(1) Range of values represents start of 20-year period to end of 20-year period. (2) Based on heat sent to anaerobic digester.

The capital cost for the gas engine, with a gas conditioning system, a microgrid, and a duty-standby flare, and a standby boiler was developed using a budgetary cost estimate of the equipment. The cost of the batteries and microgrid were developed from HOMER software. Indirect costs, contingencies and financial factors presented in Volume 2 of this master plan were applied. The capital cost was escalated to 2034 dollars, the starting point of the analysis.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-30
Grants and Incentives
Other assumptions incorporated into this analysis include the incorporation of incentives. The following Table 1.19 lists the incentives currently available for deployment of gas engines.

Table 1.19 Financial Incentives for Gas Engines
Selected Treatment Incentive Qualification? Current Rate(1) Projected Benefit CHP Gas Engines  SGIP
» Base Incentive
» Applied to capital cost of
equipment
Yes 2$ / Watt Not Applied - current
California funding
levels to expire by
2025
CHP Gas Engines  SGIP
» Resiliency Adder
» Applied to capital cost of
equipment
No - City does not
qualify

2.5$ / Watt Not Applied - current
California funding
levels to expire by
2025
Battery Storage  SGIP
» Large Scale Storage
(>10 kW)
» Currently in Step 5
» Applied to capital cost
Yes -

3.5 MWh system,
4 hour duration
$ .25 / Watt-hour,
100% for first
2 hours of storage,
50% for hours 2-4
of storage
Not Applied - SGIP
funds not likely to be
available in the 2030s
Battery Storage  ITC
» 6% base credit
» Prevailing wage, low-income community and
domestic content adders
raise the percentage by
10% each
» Applied to capital cost of
equipment
Yes - federal
benefit applicable
to all battery
storage projects

0.18% of capital
cost(3)
$316,000 - funds
expected to be
available until 2033
Notes:
(1) Current rates are subject to state subsidies and incentive programs and may not be applicable in the future. (2) Incentives based on continued compliance performance-based requirements, including efficiency and discharge. (3) Assumes domestic content and prevailing wage adders; 26 percent of the capital cost, available for ~70 percent of the total.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-31

1.5.4.2 Results
Figure 1.24 reflects the electrical consumption on the site over the time period. The figure illustrates the net utility purchase required based on net demand, the available electricity produced by the cogeneration, and the net utility purchase required after cogeneration. In this case, the 635 kW gas engine produces sufficient electricity to power the plant entirely from its first year of operation.

Figure 1.24 Alternative 3 - Projected Electrical Consumption VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-32
The electrical production above accounts for the following availability of biogas. In this scenario, there will be insufficient biogas for the engine to run at maximum capacity for the whole life cycle. The maximum capacity of the gas engine will be reached by 2044.

The amount of biogas and the flaring rates for this scenario over twenty years are shown in Figure 1.25.

Figure 1.25 Alternative 3 - Digester Gas End Uses
By the end of the 20 years, there will be excess biogas that needs to be flared. Based on the chart, roughly 21 cfm will need to be flared at the end of the 20-year period.

The Life Cycle cost for this alternative were calculated mainly including the cost of O&M of the equipment. Figure 1.26 describes the O&M costs for the first year of operation in 2034 dollars.

Figure 1.26 Alternative 3 - Annual O&M Costs
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-33
Based on the project costs, and the annualized life cycle O&M costs, the Net Present Cost is determined and presented in Table 1.20.

Table 1.20 Life Cycle Cost Analysis - Alternative 3 (Gas Engine) Gas Engine 20-Year Average Annual Cost, 2025 Dollars
Estimated Project Cost $21,800,000
20-year Life Cycle O&M Costs $3,100,000
Net Present Cost $24,900,000

1.5.4.3 Construction, Operational, and Regulatory Challenges Operationally, the manufacturer Jenbacher offers a renewable 10-year service agreement for the gas engines. The agreement will require City staff to monitor the system, provide daily inspections of its operation, and perform maintenance on standardized components of the system. However, any large repairs, work orders, and general maintenance of specialized tools will be conducted by the manufacturer through this agreement. The maintenance agreement will serve to minimize O&M needs for this alternative.

From a regulatory perspective, permitting a gas engine in Santa Barbara County must follow existing Best Available Control Technology (BACT) guidelines for the APCD. The Jenbacher gas engine, along with the gas conditioning skid, was selected to comply with these BACT guidelines. Regardless, the regulatory requirements of installing cogeneration under an APCD grant are stringent. There would also be a large degree of monitoring and compliance tasks to maintain compliance with the permits.

From a construction standpoint, there are benefits to this alternative. There is existing space onsite for construction, near to the existing digesters and gas systems. There is also sufficient space for the construction of the microgrid. Given the proximity to the source of the biogas (anaerobic digesters), there will be a minimal impact on construction.

1.5.5 Alternative 4: Power and Heat Generation Using 400 kW Microturbine + Power Management Using Microgrid and Battery
Combined Heat and Power microturbines produce heat for re-use in anaerobic digesters, and electricity for re-use at the facility. The following process flow diagram indicates the standard flow path of digester gas with a digester system (Figure 1.27).

The gas will be treated before entering the system to maintain high microturbine performance standards and meet APCD requirements for exhaust emissions. The proposed gas treatment system will include H2S, siloxane, and moisture removal. The specific technologies for each stage of the gas treatment shown are shown in the following list:
 Moisture Removal: knockout vessel that provides separation of gas and liquid phases of biogas.  H2S Removal: Iron sponge scrubber to remove excess H2S.  Siloxane and VOC Removal: Activated carbon media vessels to remove siloxanes and VOCs in the gas that reduce longevity of the engines.
 Gas Storage: In-line pressured controlled tanks sized with 30-minute ramp down of flow (1,500 ft3).

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-34
There are other items that constitute the gas conditioning skid, including control systems, pressure regulators, temp and heat exchangers. These are considered to be integrated within the gas conditioning skid and CHP module.

The exhaust heat will be recovered and used for anaerobic digesters heating. A backup flare will remain as a backup in the case of engine downtime.

Figure 1.27 Alternative 4 - Process Flow Schematic
The specifications for the biogas conditioning skid and their dimensions are indicated in the following Table 1.21.

Table 1.21 Gas Conditioning Skid Specifications
Conditioning Stage System Quantity Flow Rate
(cfm) Media Dimensions(ft, L x W x H)
Moisture Removal Knockout Vessel 1 50-350 N/A 5.5 x 3 x 5 Compression Blowers 3 15-300 N/A 10 x 5 x 5
H2S Removal Lead-Lag Vessels 2 up to 780 FerroSorp 8 x 8 x 7 Siloxane Removal GAC Vessels 2 up to 780 Calgon VPR 8 x 8 x 12 Gas Storage Pressurized Buffer Tanks 9 N/A N/A 16 x 4 x 7 The proposed layout and dimension of the system on-site is as shown in Figure 1.28.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-35
Figure 1.28 Alternative 4 - Proposed Layout

1.5.5.1 Life Cycle Design Criteria
The following design parameters were modelled over a 20-year period. The annual electricity generated was developed using the following baseline criteria in Table 1.22.

Table 1.22 Life Cycle Analysis Criteria - Alternative 4 Parameters Units Values
Estimated Average Biogas Production(1) scfm 158-180
Available Energy Input1 MMBTU/hr 5.7 - 6.4
2 x Capstone 200kW Microturbines (kW) 400
Required Energy Input (at 100% capacity)(1) (MMBTU/hr) 4.9 Required Input DG flow (at 100% capacity) (cfm) 135
Assumed Uptime (%) 88%
Electrical efficiency % 28
Power Produced kW 380
Parasitic Electrical Power kW 20
Heat Energy Recovered (MMBTU/day) 26-34
Battery Size MWh 3.5
Notes:
ppd – pounds per day; LHV - lower heating value
(1) Range of values indicates from start of 20-yr period to end of 20-yr period.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-36
The capital cost for the microturbines, with a gas conditioning system, a standby boiler, and a new duty-standby flare system, was developed using a budgetary cost estimate of the equipment. The cost of the batteries was developed from HOMER software. Indirect costs, contingencies, and financial factors presented in Volume 2 of this master plan were applied. The capital cost was escalated to 2034 dollars, the starting point of the analysis.

Grants and Incentives
Table 1.23 lists the incentives available for deployment of microturbines.

Table 1.23 Financial Incentives for Microturbines
Selected Treatment Incentive Qualification? Current Rate(1,2,3) Projected Benefit Microturbines  SGIP
» Base Incentive
» Applied to capital cost of
equipment
Yes 2$ / Watt Not Applied - current
California funding
levels to expire by
2025
Microturbines  SGIP
» Resiliency Adder
» Applied to capital cost of
equipment
No 2.5$ / Watt Not Applied - current
California funding
levels to expire by
2025
Battery Storage  SGIP
» Large Scale Storage
(>10 kW)
» Currently in Step 5
 Applied to capital cost
Yes -

3.5 MWh system,
4 hour duration
$ .25 / Watt-hour,
100% for first
2 hours of storage,
50% for hours 2-4
of storage
Not Applied - SGIP
funds not likely to be
available in the 2030s
Battery Storage  ITC
» 6% base credit
» Prevailing wage,
low-income community
and domestic content
adders raise the
percentage by 10% each
» Applied to capital cost of
equipment
Yes -
Federal benefit
applicable to all
battery storage
projects

0.18% of capital
cost(4)
$316,000 - funds
expected to be
available until 2033
Notes:
(1) Current rates are subject to state subsidies and incentive programs and may not be applicable in the future. (2) Incentives based on continued compliance performance-based requirements, including efficiency and emissions rates. (3) Incentives based on continued compliance with reporting and monitoring requirements. (4) Assumes domestic content and prevailing wage adders; 26 percent of the capital cost, available for ~70 percent of the total.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-37

1.5.5.2 Results
Figure 1.29 reflects the electrical consumption on the site over the time period. The figure illustrates the net utility purchase required based on net demand, the available electricity produced by the cogeneration, and the net utility purchase required after cogeneration. In this case, the 400 kW microturbine will never produce sufficient electricity to make the WWTP self-sufficient. The WWTP will continue to purchase utility power with this alternative.

Figure 1.29 Alternative 4 - Projected Electrical Consumption VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-38
In this scenario, there will be enough biogas for the engine to run at maximum capacity for the whole life cycle. This means that the biogas will continue to be flared despite full operation of this microturbine. The amount of biogas and the flaring rates for this scenario over twenty years are shown in Figure 1.30.

Figure 1.30 Alternative 4 - Digester Gas End Uses
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-39
There will be a consistent amount of flaring required for this alternative, starting from 43 cfm in 2034 to around 68 cfm in 2054.

The Life Cycle cost for this alternative was calculated mainly including the cost of O&M of the equipment.

Figure 1.31 describes the O&M costs for the first year of operation in 2034 dollars.

Figure 1.31 Alternative 4 - Annual O&M Costs
Based on the project costs, and the annualized life cycle O&M costs, the Net Present Cost is determined and presented in Table 1.24.

Table 1.24 Life Cycle Cost Analysis - Alternative 4 (400 kW Microturbine) 400kW Microturbine 20-Year Average Annual Cost, 2025 Dollars Estimated Project Cost $23,100,000
20-year Life Cycle O&M Costs $5,700,000
Net Present Cost $28,800,000

1.5.5.3 Construction, Operational, and Regulatory Considerations Operationally, the manufacturer Capstone offers a renewable 10-year agreement for the microturbines.

The agreement will still require City staff to monitor the system, provide daily inspections of its operation, and perform maintenance on standardized components of the system. However, it excludes City staff from performing planned and corrective maintenance of more integral parts over the span of the agreement. This reduces the burden on City staff.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-40
From a regulatory perspective, microturbines must follow existing BACT guidelines for the APCD. The technologies presented in this analysis were selected to comply with these BACT guidelines. However, the regulatory requirements of installing cogeneration are stringent. It will require significant monitoring and reporting requirements to both state and local agencies. Fuel treatment will be a significant driver of O&M and operational man-hours. Ensuring quality biogas will be essential for the operation of the plant, but may be reduced in reliability.

From a construction standpoint, there is existing space onsite for construction, near to the existing digesters and gas systems. Further, the size of the microturbine system is small and containerized, allowing for smooth integration into the existing system.

1.5.6 Alternative 5: Power and Heat Generation Using 600 kW Microturbine + Power Management Using Microgrid and Battery
This alternative will be the same as Alternative 4, but with three 200kW microturbines to ensure that all the biogas produced is beneficially used for power and heat generation. A duty-standby flare system and a standby boiler will remain as a backup in the case of engine downtime. Figure 1.32 shows the process flow schematic for this alternative.

Figure 1.32 Alternative 5 - Process Flow Schematic
The specifications for the biogas conditioning skid and their dimensions are indicated in the following Table 1.25.

Table 1.25 Gas Conditioning Skid Specifications
Conditioning
Stage System Quantity Flow Rate(cfm) Media Dimensions(ft, L x W x H) Moisture Removal Knockout Vessel 1 50-350 N/A 5.5 x 3 x 5 Compression Blowers 3 15-300 N/A 10 x 5 x 5
H2S Removal Lead-Lag Vessels 2 up to 780 FerroSorp 8 x 8 x 7 VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-41
Conditioning
Stage System Quantity Flow Rate(cfm) Media Dimensions(ft, L x W x H) Siloxane Removal GAC Vessels 2 up to 780 Calgon VPR 8 x 8 x 12 Gas Storage Pressurized Buffer
Tanks
9 N/A N/A 16 x 4 x 7
The proposed layout and dimension of the system on-site is shown in Figure 1.33.

Figure 1.33 Alternative 5 - Proposed Layout

1.5.6.1 Life Cycle Cost Analysis
The following design parameters were modelled over a 20-year period. The annual electricity production generated for each system was developed using the following baseline criteria in Table 1.26.

Table 1.26 Life Cycle Analysis Criteria - Alternative 5 Parameters Units Values
Estimated Average Biogas Production(1) scfm 158 - 180
Available Energy Input(1) MMBTU/hr 5.7 - 6.4
3 x Capstone 200kW Microturbines (kW) 600
Required Energy Input (at 100% capacity)(1) (MMBTU/hr) 6.4 Required Input DG Flow (at 100% capacity) (cfm) 179
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-42
Parameters Units Values
Electrical Efficiency % 28
Maximum Power Produced kW 580
Parasitic Electrical Power kW 20
Heat Energy Recovered (MMBTU/day) 26-34
Battery Size MWh 3.5
Notes:
(1) A range of values indicates from start of 20-yr period to end of 20-yr period.

As illustrated by the selected parameters and the net demand required by the site (Section 1.2), a sizing of 600 kW is more than the maximum power demand. However, the biogas generated is not sufficient to run this generator at 100 percent capacity.

The capital cost for the microturbines, with a gas conditioning system, a new duty-standby flare system, and a standby boiler was developed using a budgetary cost estimate of the equipment. The cost of the batteries were developed from HOMER software. Indirect costs, contingencies and financial factors presented in Volume 2 of this Master Plan were applied. The capital cost was escalated to 2034 dollars, the starting point of the analysis.

Grants and Incentives
Other assumptions incorporated into this analysis include the incorporation of incentives. The following Table 1.27 lists the incentives available for deployment of microturbines.

Table 1.27 Financial Incentives for Microturbines
Selected Treatment Incentive Qualification? Current Rate(1,2,3) Projected Benefit Microturbines  SGIP
» Base Incentive
» Applied to capital cost of
equipment
Yes 2$ / Watt Not Applied - current
California funding
levels to expire by
2025
Microturbines  SGIP
» Resiliency Adder
» Applied to capital cost of
equipment
No 2.5$ / Watt Not Applied - current
California funding
levels to expire by
2025
Battery Storage  SGIP
» Large Scale Storage
(>10 kW)
» Currently in Step 5
» Applied to capital cost
Yes - 3.5 MWh
system, 4 hour
duration
$ .25 / Watt-hour,
100% for first
2 hours of storage,
50% for hours 2-4
of storage
Not Applied - SGIP
funds not likely to be
available in the 2030s
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-43
Selected Treatment Incentive Qualification? Current Rate(1,2,3) Projected Benefit Battery Storage  ITC
» 6% base credit
» Prevailing wage, low-income community and
domestic content adders
raise the percentage by
10% each
» Applied to capital cost of
equipment
Yes - federal
benefit applicable
to all battery
storage projects

0.18% of capital
cost(4)
$316,000 - funds
expected to be
available until 2033
Notes:
(1) Current rates are subject to state subsidies and incentive programs and may not be applicable in the future. (2) Incentives based on continued compliance performance-based requirements, including efficiency and emissions rates. (3) Incentives based on continued compliance with reporting and monitoring requirements. (4) Assumes domestic content and prevailing wage adders; 26 percent of the capital cost, available for ~70 percent of the total.

1.5.6.2 Results
Figure 1.34 reflects the electrical consumption on the site over the time period. The figure illustrates the net utility purchase required based on net demand, the available electricity produced by the cogeneration, and the net utility purchase required after cogeneration. In this case, the 600 kW microturbine will produce sufficient electricity to make the WWTP self-sufficient by 2054. The WWTP will continue to purchase utility power with this alternative.

Figure 1.34 Alternative 5 - Projected Electrical Consumption VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-44
The available biogas for the microturbine operation is shown. The available biogas under current conditions will never be sufficient for continued utilization of the microturbine. There will be no flaring in this alternative. The amount of available biogas and the corresponding flaring rates for this scenario over twenty years are shown in Figure 1.35.

Figure 1.35 Alternative 5 - Digester Gas End Uses
The Life Cycle cost for this alternative was calculated mainly including the cost of O&M of the equipment.

Figure 1.36 describes the O&M costs for the first year of operation in 2034 dollars.

Figure 1.36 Alternative 5 - Annual O&M Costs
$432,000
$888,000
$80,000
$162,000
$45,000
$79,000
$48,000
$6,000
$18,000
$3,000
$0 $200,000 $400,000 $600,000 $800,000 $1,000,000
Net Annual Cost
Savings from Base Case
Power Cost
O&M costs for microturbine
O&M costs for fuel treatment
Annualized replacement cost for battery
O&M costs for battery
O&M costs for standby boiler
O&M costs for solar
O&M costs for flare
Annual O&M Costs, 2034 dollars
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-45
Based on the project costs, and the annualized life cycle O&M costs, the Net Present Cost is determined and presented in Table 1.28.

Table 1.28 Life Cycle Cost Analysis – Alternative 5 (600 kW Microturbine) 600kW Microturbine 20-Year Average Annual Cost, 2025 Dollars Estimated Project Cost $24,700,000
20-year Life Cycle O&M Costs $3,100,000
Net Present Cost $27,800,000

1.5.6.3 Construction, Operational, and Regulatory Considerations Operationally, the manufacturer Capstone, offers a renewable 10-year agreement for the microturbines.

The agreement will still require City staff to monitor the system, provide daily inspections of its operation, and perform maintenance on standardized components of the system. However, it excludes City staff from performing planned and corrective maintenance of more integral parts over the span of the agreement. This reduces the burden on City staff.

From a regulatory perspective, microturbines must follow existing BACT guidelines for the APCD. The technologies presented in this analysis were selected to comply with these BACT guidelines. However, the regulatory requirements of installing cogeneration are stringent. It will require significant monitoring and reporting requirements to both state and local agencies. Fuel treatment will be a significant driver of O&M and operational man-hours. Ensuring quality biogas will be essential for the operation of the plant, but may be reduced in reliability.

From a construction standpoint, there is existing space onsite for construction, near to the existing digesters and gas systems. Further, the size of the microturbine system is small and containerized, allowing for smooth integration into the existing system.

1.5.7 Alternative 6: Heat Recovery With Boilers + Compression of Remaining Biogas to CNG for Pipeline Injection + Power Management Using Microgrid and Battery
This alternative evaluates the potential for upgrading excess biogas to pipeline-quality natural gas that can be injected into the closest SoCalGas pipeline. It assumes that the digester biogas will first provide fuel to a new boiler for re-heating the digesters, and then the remainder of the biogas would be utilized for compression and injection into a natural gas pipeline. A new pipeline would be constructed from the WWTP to connect to an existing SoCalGas gas pipeline, and the gas would be sold. A microgrid system connected to the new solar array would remain to manage energy use.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-46
The following process flow schematics indicates the process layout of the proposed alternative (Figures 1.37 and 1.38).

A new waste gas flare would be provided as a backup in case the compressed natural gas does not meet the quality requirements for acceptance into the SoCalGas pipeline.

Figure 1.37 Alternative 6 - Electrical Process Schematic Figure 1.38 Alternative 6 - Biogas Process Schematic

1.5.7.1 Life Cycle Cost Analysis
The assumptions of this analysis are heavily based on shifting market dynamics and the continuation of subsidies and incentives provided to natural gas projects. The assumptions may not remain consistent in the long run.

It is assumed that SoCalGas will purchase the compressed biogas at their procurement price, which changes every month. An average value for CNG sale price is assumed.

The design criteria utilized for this process is shown in Table 1.29.

Table 1.29 Life Cycle Analysis Criteria - Alternative 6 Parameters Units Values
Estimated Average Biogas Production scfm 158 - 180
Available Energy Input MMBTU/hr 4.8 - 6.4
Boiler Heat Recovered MMBTU/hr 1.1 - 1.4
Heat Sent to Pipeline MMBTU/hr 4.56 - 5
Average CNG Sale Price ($/MMBtu) $4
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-47
Parameters Units Values
Gas Sent to Pipeline(1) cfm 127 - 139
Battery Size MWh 3.5
Notes:
(1) Dependent on available pipeline capacity and demand.

Electrically, there is no marginal benefit to this alternative, besides the existing solar array and battery.

Duty and standby boilers will be sufficiently sized to recover the necessary heat for the anaerobic digesters.

The capital cost for the pipeline injection, with a gas conditioning system, and new duty-standby boilers and flares, was developed using a budgetary cost estimate of the equipment. Indirect costs, contingencies and financial factors presented in Volume 2 of this Master Plan were applied. The capital cost was escalated to 2034 dollars, the starting point of the analysis.

Grants and Incentives
Other assumptions incorporated into this analysis include the incorporation of incentives. The following Table 1.30 lists the incentives available for deployment of a pipeline injection.

Table 1.30 Financial Incentives for Pipeline Injection
Selected
Treatment Incentive Qualification? Current Rate(1,2,3) Projected Benefit Pipeline
Injection
 Biomethane Monetary Incentive
Program
» Provides assistance with
interconnection costs and studies
» Provides assistance with some
compression equipment
Yes 50% of estimated
interconnection cost
(~1.925 million)
$965,000
Pipeline
Injection
 SoCalGas Procurement Price
» Purchase price of SoCalGas from
CNG suppliers
Yes $.4/therm or 4$/MMBtu Applied in Life
Cycle Cost
Analysis
Pipeline
Injection
 RFS
» Increased credits for biogas injection
when the end use is transportation
Yes - if CNG fuel
station is the
source of the
biogas

3.4$/RIN Not Applied -
federal benefits
uncertain
Pipeline
Injection
 California LCFS
» Increased credits for biogas injection
when the end use is transportation
Yes - if CNG fuel
station is the
source of the
biogas
60$/MTCO2e Not Applied -
federal benefits
uncertain
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-48
Selected
Treatment Incentive Qualification? Current Rate(1,2,3) Projected Benefit Battery
Storage
 SGIP
» Large Scale Storage (>10 kW)
» Currently in Step 5
» Applied to capital cost
Yes

3.5 MWh system,
4 hour duration
$ .25 / Watt-hour,
100% for first 2 hours of
storage,
50% for hours 2-4 of
storage
Not Applied -
SGIP funds not
likely to be
available in the
2030s
Battery
Storage
 ITC
» 6% base credit
» Prevailing wage, low-income
community and domestic content
adders raise the percentage by 10%
each
» Applied to capital cost of equipment
Yes - federal
benefit applicable
to all battery
storage projects

0.18% of capital cost(4) $316,000 - funds
expected to be
available until
2033
Notes:
(1) Current rates are subject to state subsidies and incentive programs and may not be applicable in the future. (2) Current rate values estimated to be steady and not escalate with inflation to account for market fluctuations. (3) Incentives based on continued compliance with reporting and monitoring requirements. (4) Assumes domestic content and prevailing wage adders; 26 percent of the capital cost, available for ~70 percent of the total.

1.5.7.2 Results
Since this alternative utilizes a battery, the cost per kWh determined by the HOMER section provide the basis of the electrical savings for this alternative.

The net demand for this alternative is based on 502 kW. This corresponds to an annual consumption of ~4,400 MWh per year. Based on the previous determination of battery cost savings per kilowatt-hour with HOMER software, the electrical utility costs were developed.

The average sale price per unit of gas was utilized to calculate the annual revenues of CNG sales to the system. As such, the revenues for the system are based on the core SoCalGas sale price described in Table 1.30 above.

The amount of gas available over the time period for compression is illustrated in Figure 1.39.

Figure 1.39 Alternative 6 - Digester Gas End Uses
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-49
The quantity of gas available for compression ranges from 127 to 139 cfm, based on the standard heating value of methane. Based on the current SoCalGas procurement price of approximately ~$4/MMBtu, the sale revenues can be developed for this alternative.

The Life Cycle cost for this alternative was calculated, including O&M cost of the equipment and power purchase from PG&E. Figure 1.40 describes the O&M costs for the first year of operation in 2034 dollars.

Figure 1.40 Alternative 6 - Annual O&M Costs
Based on the project costs, and the annualized life cycle O&M costs, the Net Present Cost is determined and presented in Table 1.31.

Table 1.31 Life Cycle Cost Analysis - Alternative 6 (Conversion to CNG for Pipeline Injection) Pipeline Injection 20-Year Average Annual Cost, 2025 Dollars Estimated Project Cost $30,000,000
20-year Life Cycle O&M Costs $11,100,000
Net Present Cost $41,100,000
The viability of the Net Present Cost is dependent on multiple factors. First, there must be sufficient demand from both SoCalGas to accept the CNG flow provided by WWTP. Second, it is also dependent on State market pricing for gas, which may not remain at current levels.

1.5.7.3 Operational and Regulatory Considerations
The primary operational consideration for this alternative would be the continued operation of the boiler/flare system in conjunction with an advanced fuel treatment system. This would result in an increase in the operational burden for City staff. There may be opportunities for an external company to VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-50
provide maintenance on the fuel treatment, but that has not yet been considered and may be unlikely without a corresponding recovery benefit.

Further, the natural gas quality limits highlighted under Rule 30 above will necessitate a significant upgrade of the fuel treatment system. If the biogas doesn't reach those standards at any point, the CNG will need to be flared. In addition, gasoline markets for sale in vehicles are tightly regulated, and the monitoring and reporting requirements would correspondingly increase.

For the constructability, there would be significant challenges in constructing a pipeline along Black Road.

The City does not own all the property extending from Black Road to the CNG injection point , and thus would need to acquire property and easement rights. This may pose challenges, considering there are existing utility easements from multiple stakeholders along Black Road, including a State Water Project water pipeline.

Integration of the pipeline within the CNG fuel station is also predicated on the acceptance of the natural gas. If SoCalGas deems there is insufficient demand for CNG, they would be unable to sell the gas at the listed credits. As such, the uncertainty of the markets may make this alternative infeasible.

1.6 Alternative Analysis
The analysis of the alternatives is summarized in Table 1.32. As indicated, Alternative 3 (Gas Engine + Boiler + Solar + Battery) is the only alternative that has a lower Net Present Cost than the Base Case alternative (Alternative 1). Thus, Alternative 3 is the only alternative that shows a financial payback, based on the capital investment and the anticipated savings due to significantly reduced energy purchases from the grid. It is important to note that none of the alternatives include any credit for potential incentive programs. Incentive programs are available, as discussed above during the analysis of each alternative, but have not been included in the financial analysis because such programs come and go, and it is not possible to ascertain what programs might be available if/when one of the alternatives is implemented.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-51
Table 1.32 Alternatives Analysis
Metric Alternative 1 (Base
Case)
Boiler + Solar
Alternative 2
Boiler + Solar +
Battery
Alternative 3
Alt 2 + Gas Engine
Alternative 4
Alt 2 + 400kW-Microturbine
Alternative 5
Alt 2 + 600kW-Microturbine
Alternative 6
Alt 2 + Pipeline
Injection
Capital Cost(1) $13,300,000 $15,100,000 $21,800,000 $23,100,000 $24,700,000 $30,000,000 Net Present Cost(2) $26,500,000 $27,300,000 $24,900,000 $28,800,000 $27,800,000 $41,100,000 Payback Period - - 14 - - -
Flaring Rates 126-139 cfm 126-139 cfm 0-21 cfm 43-68 cfm - 126-139 cfm Notes:
(1) Project Cost, 2025 dollars.
(2) 20-yr average annualized project costs discounted to 2025.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-52

1.6.1 Conclusions and Recommendations

1.6.1.1 Financial
The Net Present Cost gives a direct snapshot about how much each alternative will cost the City to run and operate over the course of the assumed 20-year project lifespan. For this analysis, the comparison of the Net Present Cost shows that the Gas Engine with the battery and microgrid (Alternative 3) is the most financially attractive alternative. Due to its higher efficiency and lower capital cost than the microturbines, it can recoup its capital investment quicker than the microturbine alternatives. Alternative 3 is the only alternative that is more financially viable than the "Boiler and Solar" base case (Alternative 1).

As such, the gas engine is the most financially viable option. The gas engine payback period ultimately means that the savings gained from the reduced power costs will recoup the capital cost after 14 years. As noted earlier, the alternatives do not include any credit for potential incentive programs. Therefore, assuming that some type of incentive program is still available when/if Alternative 3 is implemented, the payback period can be expected to be shorter, making this alternative more attractive.

1.6.1.2 Operational Considerations
To assist with the operational requirements of gas engines or microturbines, maintenance agreements with the equipment manufacturers are available, which would reduce the burden on City staff. Such agreements cover significant engine repairs, but the City will still be required to monitor and repair standard components. The terms for these agreements are typically 10 years and are renewable.

From a regulatory perspective, the gas conditioning skids will be compliant with current ACPD regulations.

However, there will continue to be significant monitoring requirements for each, including annual APCD permits, reports, and calibration. City staff would be expected to monitor and maintain the gas treatment systems surrounding the cogeneration options. This means that the City will be responsible for operational requirements compared to the base case alternative (Alternative 1) or Alternative 2.

The gas engine approach (Alternative 3) will begin to flare about four years into its operation, whereas the 600 kW microturbine will consume all available gas throughout the 20-year life cycle. Changes in biogas production can be accommodated by either system. This allows for ramp-up in energy production in the early years if there is more biogas than projected.

If the City is concerned about the operational burden of either option, the Base Case would reduce those stringent requirements. Although there would be an increased reliance on the grid for providing the bulk of electrical power, minimizing the operational requirements to run the gas conditioning skid and monitoring the cogeneration systems may be more beneficial to the City than the cost savings that can be achieved with a cogeneration alternative.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-53

1.6.1.3 Recommendations
The above analysis was presented to the City during Workshop No. 6 on April 30, 2025. After some discussion, the City felt that there would be significant environmental benefits to utilizing the biogas produced by the future WWTP once the Phase 1 expansion project is complete, thereby significantly reducing the reliance on the electrical grid for plant power needs. Also, based on the financial analysis, Alternative 3 would be the preferred approach.

Therefore, it was recommended that Alternative 3 (635 kW CHP Gas Engine with solar, battery and microgrid) is the preferred alternative and that it should be included as part of the Phase 1 project.

Appropriate incentive programs to reduce the financial burden will be investigated closer to the implementation time.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA

WASTEWATER TREATMENT PLANT MASTER PLAN

APPENDIX A ELECTRICAL POWER DRAW

CALCULATIONS
Power Draw Calcs
Phase 1
Phase 1 Power (hp) Remark
Headworks
Screens
conveyor 2 existing size
washer 5
pump 3
Grit Removal
grit pump 8
grit mixer 5 laguna
grit classifier 5 laguna
Primary Clarifiers
Flight drives 3
Skimmer drives 3
Sludge pumps 7.5 added
Aeration Tanks
AB Pump Station
flow, mgd 6.5
flow, gpm 4,514
head, ft 15
efficiency, % 0.7
power, hp 24
Drain pumps 30
Mixers 15
Blowers
average process air, scfm 8,500 based on volume 6 estimation discharge pressure, psig 7
efficiency, % 0.75
power, hp 330
Mech Aerators
power, hp
MLR pumping
flow, mgd 13
flow, gpm 9,259
head, ft 5
efficiency, % 0.7
power, hp 20
Secondary Clarifiers
Flight drives 2 given
Drain pumps 5
RAS pumping
For the following,standard motor sizes are utilized.

As such, the results are rounded up.
flow, mgd 10.0
flow, gpm 6,944
head, ft 30
efficiency, % 0.7
power, hp 75
WAS Pumping
flow, mgd 0.28
flow, gpm 194
head, ft 30
efficiency, % 0.7
power, hp 2
Filters
Filter Influent Pumps
flow, mgd 10
flow, gpm 6,944
head, ft 15
efficiency, % 0.7
power, hp 40
Filter effluent pumps
flow, mgd 10
flow, gpm 6,944
head, ft 30
efficiency, % 0.7
power, hp 75
Filter backwash pumping
flow, mgd 5
flow, gpm 3,472
head, ft 30
efficiency, % 0.7
power, hp 40
Sludge Thickeners
Thickeners 2.55 values based on similarly sized projects Thickened Sludge Pumps 10 values based on existing pumps Polymer Pumps 4 values based on similarly sized projects Drain Pumps 10 values based on similarly sized projects Sludge grinders 2
Anaerobic Digesters
Mixing Pumps 40 values based on similarly sized projects Sludge Transfer Pumps 11 values based on similarly sized projects Recirculation Pump 7.5 based on existing pumps
Sludge Storage
Sludge Transfer Pumps 12 values based on similarly sized projects Recirculation/Hot Water/Gas Mixing
hot water recirculation pumps 5 based on existing pumps, digester 4 gas mixing compressor 30 based on existing compressors
gas chillers/moisture removal 5
Dewatering Building
Screw Press 2.5 values based on similarly sized projects Polymer Metering Pump 1 values based on similarly sized projects Filtrate Pump 20 values based on similarly sized projects Cake Conveyor 10 values based on similarly sized projects Effluent Pump Station to percolation ponds
Effluent Pump Station
Flow, MGD 10 average
Flow, GPM 6940
Head, ft 25
efficiency 0.7
power (hp) 70
Utility Water Pump Station
Flow, MGD 1.5
Flow, GPM 1041
Head, ft 275
efficiency 0.7
power (hp) 110
PROJECT : Santa Maria WWTP Program Management Services
CLIENT: City of Santa Maria
ELEMENT #: 4
DESCRIPTION : Phase 1 Upgrade Electrical Projection
JOB # :

ASSUMPTIONS
Rated Capacity 0.75
1 hp= 0.7457 kW
Safety Factor 1.2
Future Electricity Consumption
No. of
Operating
Units
No. of
Standby
Units
Motor Power
(hp) per unit
Total
Operating
Motor Power
(hP)
Power Input
(KW)
Operation
Time (hr/day)
1 Headworks
Screens 2 1 10 20 15 24
Grit pumps 2 0 8 15 11 12
grit mixer 1 1 5 5 4 24
grit classifier 1 0 5 5 4 24
2 Primary Clarifiers
Flight drives 2 1 2 4 3 24
Skimmer drives 2 1 2 4 3 24
Sludge pumps 2 1 7.5 15 11 24
3 Aeration Basin
AB influent Pumps 3 1 24 73 55 24
Mixers 6 0 15 90 67 24
Blowers 2 1 330 660 492 24
Drain Pumps 1 0 30 30 22 1
MLR Pumping 3 0 20 60 45 24
4 Secondary Clarifiers
RAS pumping 2 1 75 150 112 24
WAS pumping 2 0 2 4 3 5
mechanism drives 2 0 2 4 3 5
5 Tertiary Filters
Filter influent pumps 1 1 40 40 30 24
Filter backwash pumping 1 1 40 40 30 2
6 Primary Scum
Scum Pumps 2 1 15 30 22 0.1
8 Secondary Scum
Process Normal Operations
Scum Pumps 2 1 10 20 15 0.1
9 Sludge Thickening
Thickeners 3 1 3 9 7 7
Thickened Sludge Pumps 2 1 10 20 15 7
Polymer Pumps 3 1 4 12 9 7
Drain Pumps 1 1 10 10 7 7
Sludge grinders 1 1 2 2 1 8
10 Anaerobic Digestion
Mixing Pumps 2 2 20 40 30 24
Sludge Transfer Pumps 2 1 11 22 16 7
Reciculation Pump 2 1 7.5 15 11 8
11 Sludge Storage
Sludge Transfer Pumps 1 1 12 12 9 7
Sludge mixing Pump 1 1 40 40 30 24
12 Dewatering Building
Screw Press 3 1 2.5 8 6 7
Polymer Metering Pump 3 1 1 3 2 7
Filtrate Pump 1 1 20 20 15 7
Cake Conveyor 3 0 10 30 22 7
13) Gas Mixing/Boilers
hot Water recirculation pumps 2 2 5 10 7 8
gas chillers/moisture removal 1 1 5 5 4 8
14) Effluent Pump Station
Finish water pump 1 1 70 70 52 24
15) Utility Water Pump Station 1 1 110 110 82 24
16) HVAC/Process/Misc 396.63 18
Connected Load (kW) 1670
AVERAGE DEMAND FACTOR 40%
Expected Average Daily Demand (kW) 668
Annual Consumption (MWh) 5851
VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA

WASTEWATER TREATMENT PLANT MASTER PLAN

APPENDIX B HOMER REPORT
PREPARED BY:

Tobias Pizot,
Staff Professional, Carollo Engineers,
[email protected],
3609094857

Page 1 of 13 ends