PREPARED FOR:

City of Santa Maria, Wastewater Treatment Plant
751 Black Rd, Santa Maria, CA 93458, USA
PREPARED BY:

Tobias Pizot, Staff Professional
Carollo Engineers, [email protected]
3609094857
This proposal has been generated using HOMER Grid, a dynamic software engine that runs complex simulations and sensitivity analyses with your energy data. It evaluates thousands of variables to compare value streams, assess system options, and provide risk-mitigation and cost reduction strategies. Originally developed at the US Department of Energy’s National Renewable Energy Laboratory, the HOMER software is a risk-mitigation tool trusted by over 200,000 project developers and financial institutions to produce informed economic feasibility studies, system design and engineering insight, as well as energy cost savings.

Table of Contents
PREPARED BY:

Tobias Pizot,
Staff Professional, Carollo Engineers,
[email protected],
3609094857

Page 2 of 13 ends

Project Summary......................................................................................3 About Carollo Engineers .........................................................................4 Savings Summary ....................................................................................5 Savings Details.........................................................................................6 Consumption Summary...........................................................................7 Engineering Details..................................................................................8 Cashflow Section ...................................................................................10 Utility Bill Details....................................................................................11 Glossary Section....................................................................................12 HOMER Energy Section.........................................................................13 Carollo Engineers
PREPARED BY:

Tobias Pizot,
Staff Professional, Carollo Engineers,
[email protected],
3609094857

Page 3 of 13 ends

CURRENT SYSTEM
The electric needs of 751 Black Rd, Santa Maria, CA 93458, USA are met with a grid connection and 720 kW of PV. You currently spend $757,101 on your utility bill per year. 41% of your utility bill is demand charges.

PROPOSED SYSTEM
We propose adding 720 kW of PV and 3,421 kWh of battery capacity.

ABOUT CAROLLO ENGINEERS
Carollo Engineers is a consulting firm that specializes in water and wastewater engineering.

We focus on designing and implementing solutions for water treatment, wastewater treatment, water reuse, and infrastructure management.

Our work includes:

Water Treatment – Designing facilities to provide clean drinking water.

Wastewater Treatment – Developing systems to treat and safely discharge wastewater.

Water Reuse & Desalination – Finding ways to recycle water and remove salt for fresh water supply.

Stormwater Management – Controlling and treating runoff to prevent flooding and pollution.

Savings Summary
PREPARED BY:

Tobias Pizot,
Staff Professional, Carollo Engineers,
[email protected],
3609094857

Page 4 of 13 ends

The chart summarizes down your estimated annual savings in the following categories:

1. Demand: Savings from demand charge reduction

2. Energy: Consumption reduction and self-consumption

3. O&M: Operating and maintenance costs of the proposed components

4. Replacements: Cost to replace proposed system components over the project lifetime

5. Other: Cost differences not included in the other categories

6. Total: The total savings (annualized) of the proposed system Savings Details
PREPARED BY:

Tobias Pizot,
Staff Professional, Carollo Engineers,
[email protected],
3609094857

Page 5 of 13 ends

1. Utility Bill Savings
The facility at 751 Black Rd, Santa Maria, CA 93458, USA is served by Pacific Gas & Electric Co. The electricity tariff plan you are currently on is the Large General - Time of Use, Option S (NEM 3).

Your monthly electricity bill has two main parts:
1) Energy charges for the total amount of electricity you consume. 2) Demand charges—for “peak usage.” If your facility tends to use a lot of power over short periods, your demand charges will comprise a larger part of your bill. If you use power at a more consistent rate throughout the month, your demand charges will generally comprise a smaller part of your bill. Demand charges make up a significant portion of commercial and industrial customers’ total electricity costs: typically, between 30 and 70 %.

Your annual utility bills and savings by category:

Consumption
Charge Demand Charge Fixed Rate Total
Base Case $445,138 $307,859 $4,105 $757,101
Proposed Case $445,138 $188,012 $4,105 $637,254
Annual Savings $0.00 $119,846 $0.00 $119,847
Current System: Grid-Connection and Solar
Proposed System: Grid-Connection, Solar, Generator, and Storage Consumption Summary
PREPARED BY:

Tobias Pizot,
Staff Professional, Carollo Engineers,
[email protected],
3609094857

Page 6 of 13 ends

Electric Consumption
This facility uses 12250 kWh/day and has a peak of 946 kW. In the proposed system, the following generation sources serve the electrical load. 0 67
133
200
267
333
400
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Utility
Imported PV
Production (MWh)
Engineering Details
PREPARED BY:

Tobias Pizot,
Staff Professional, Carollo Engineers,
[email protected],
3609094857

Page 7 of 13 ends

PV: Imported PV Production
The Generic PV system has a nominal capacity of 720 kW. The annual production is 1,649,542 kWh/yr.

Rated Capacity 720 kW Total Production 1,649,542 kW
Specific Yield 2,291 kWh/kW LCOE 0 $/kWh
PV Penetration 36.9 %
Hour of Day
Day of Year
kW
Engineering Details
PREPARED BY:

Tobias Pizot,
Staff Professional, Carollo Engineers,
[email protected],
3609094857

Page 8 of 13 ends

Storage: Generic 1kWh Li-Ion [ASM]
The Generic storage system's nominal capacity is 3,421 kWh. The annual throughput is 962,852 kWh/yr.

Rated Capacity 3,421 kWh Expected Life 9.22 yr
Annual Throughput 962,852 kWh/yr Capital Costs $1.74M
Maintenance Cost 34,800 $/yr Losses 82,904 kWh/yr
Autonomy 4.69 hr
The following incentives improve the economics for Storage. Hour of Day Day of Year
%
Engineering Details
PREPARED BY:

Tobias Pizot,
Staff Professional, Carollo Engineers,
[email protected],
3609094857

Page 9 of 13 ends

Converter: System Converter
Capacity 720 kW Hours of Operation 4,352 hrs/yr
Mean Output 176 kW Energy Out 1,541,603 kWh/yr
Minimum Output 0 kW Energy In 1,622,740 kWh/yr
Maximum Output 720 kW Losses 81,137 kWh/yr
Capacity Factor 24.4 %
Hour of Day
Day of Year
kW
Cash Flows
PREPARED BY:

Tobias Pizot,
Staff Professional, Carollo Engineers,
[email protected],
3609094857

Page 10 of 13 ends

Project Lifetime 20 years Expected Inflation Rate 3.7%
Nominal Discount Rate 6.0% Real Interest Rate 2.2%
Year 1 2 3 4 5 6 7 8 9 10
Generic 1kWh Li-Ion [ASM] ($34,800) ($34,800) ($34,800) ($34,800) ($34,800) ($34,800) ($34,800) ($34,800) ($34,800) ($34,800) Investment Tax Credit $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Large General - Time of Use,
Option S (NEM 3)
($528,185) ($528,185) ($528,185) ($528,185) ($528,185) ($528,185) ($528,185) ($528,185) ($528,185) ($528,185) Year 11 12 13 14 15 16 17 18 19 20
Generic 1kWh Li-Ion [ASM] ($34,800) ($34,800) ($34,800) ($34,800) ($34,800) ($34,800) ($34,800) ($34,800) ($34,800) ($34,800) Investment Tax Credit $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Large General - Time of Use,
Option S (NEM 3)
($528,185) ($528,185) ($528,185) ($528,185) ($528,185) ($528,185) ($528,185) ($528,185) ($528,185) ($528,185) Utility Bill Details
PREPARED BY:

Tobias Pizot,
Staff Professional, Carollo Engineers,
[email protected],
3609094857

Page 11 of 13 ends

Utility Monthly Summary - Current System
Month Energy
Purchased
(kWh)
Energy
Sold
(kWh)
Net
Energy
Purchased
(kWh)
Peak
Load
(kW)
Energy
Charge
Demand
Charge
Demand
Response
Fixed
Charge
Minimum
Charge
Taxes Total
January 326,481 0 326,481 946 $27,159 $19,639 $0.0 $348.58 $0.0 $0.0 $47,146 February 288,232 0 288,232 946 $23,990 $19,639 $0.0 $314.85 $0.0 $0.0 $43,943 March 311,317 0 311,317 946 $25,024 $19,639 $0.0 $348.61 $0.0 $0.0 $45,011 April 297,330 0 297,330 946 $23,647 $19,580 $0.0 $337.37 $0.0 $0.0 $43,564 May 302,069 0 302,069 946 $24,027 $19,580 $0.0 $348.61 $0.0 $0.0 $43,956 June 290,501 0 290,501 946 $58,893 $37,731 $0.0 $337.37 $0.0 $0.0 $96,961 July 301,993 0 301,993 946 $60,444 $37,731 $0.0 $348.61 $0.0 $0.0 $98,524 August 305,037 0 305,037 946 $61,804 $37,731 $0.0 $348.60 $0.0 $0.0 $99,884 September 299,062 0 299,062 946 $60,773 $37,731 $0.0 $337.36 $0.0 $0.0 $98,842 October 317,914 0 317,914 946 $25,594 $19,580 $0.0 $348.60 $0.0 $0.0 $45,523 November 313,404 0 313,404 946 $26,204 $19,639 $0.0 $337.35 $0.0 $0.0 $46,180 December 331,387 0 331,387 946 $27,580 $19,639 $0.0 $348.59 $0.0 $0.0 $47,567 Annual 3,684,727 0 3,684,727 946 $445,138 $307,859 $0.0 $4,105 $0.0 $0.0 $757,101 Utility Monthly Summary - Proposed System
Month Energy
Purchased
(kWh)
Energy
Sold
(kWh)
Net
Energy
Purchased
(kWh)
Peak
Load
(kW)
Energy
Charge
Demand
Charge
Demand
Response
Fixed
Charge
Minimum
Charge
Taxes Total
January 326,481 0 326,481 946 $27,159 $11,961 $0.0 $348.58 $0.0 $0.0 $44,285 February 288,232 0 288,232 946 $23,990 $11,947 $0.0 $314.85 $0.0 $0.0 $41,178 March 311,317 0 311,317 946 $25,024 $11,803 $0.0 $348.61 $0.0 $0.0 $40,962 April 297,330 0 297,330 946 $23,647 $11,814 $0.0 $337.37 $0.0 $0.0 $49,886 May 302,069 0 302,069 946 $24,027 $11,765 $0.0 $348.61 $0.0 $0.0 $39,941 June 290,501 0 290,501 946 $58,893 $23,074 $0.0 $337.37 $0.0 $0.0 $74,601 July 301,993 0 301,993 946 $60,444 $23,074 $0.0 $348.61 $0.0 $0.0 $77,616 August 305,037 0 305,037 946 $61,804 $23,095 $0.0 $348.60 $0.0 $0.0 $78,304 September 299,062 0 299,062 946 $60,773 $23,009 $0.0 $337.36 $0.0 $0.0 $78,526 October 317,914 0 317,914 946 $25,594 $12,083 $0.0 $348.60 $0.0 $0.0 $37,611 November 313,404 0 313,404 946 $26,204 $12,179 $0.0 $337.35 $0.0 $0.0 $37,126 December 331,387 0 331,387 946 $27,580 $12,208 $0.0 $348.59 $0.0 $0.0 $37,218 Annual 3,684,727 0 3,684,727 946 $445,138 $188,012 $0.0 $4,105 $0.0 $0.0 $637,254 PREPARED BY:

Tobias Pizot,
Staff Professional, Carollo Engineers,
[email protected],
3609094857

Page 12 of 13 ends

Glossary Section
Annualized Savings
The difference in annualized cost between the base case system and the proposed system.

The annualized cost is the cost that, if it were to repeat in every year of the project lifetime, would give the same net present cost as the actual cash flow sequence.

Capital Investment
The capital investment is the additional installed cost of the proposed system relative to the base case system at the start of the project.

Internal rate of return
Internal rate of return (IRR) is the discount rate at which the base case and proposed system have the same net present cost. HOMER calculates the IRR by determining the discount rate that makes the present value of the difference of the two cash flow sequences equal to zero.

Net Present Cost
The total net present cost (NPC) of a system is the present value of all the costs the system incurs over its lifetime, minus the present value of all the revenue it earns over its lifetime.

Costs include capital costs, replacement costs, O & M costs, fuel costs, emissions penalties, and the costs of buying power from the grid. Revenues include salvage value and grid sales revenue. HOMER calculates the total NPC by summing the total discounted cash flows in each year of the project lifetime.

Net Present Value
Net Present Value (NPV), also referred to as net present worth, is the difference between the net present costs of the base case system and the proposed system.

Return on Investment
Return on Investment (ROI) is the yearly cost savings relative to the initial investment. The ROI is the average yearly difference in nominal cash flows over the project lifetime, divided by the difference in capital cost.

Simple payback
Simple payback is the number of years at which the cumulative cash flow of the difference between the proposed system and base case system switches from negative to positive.

The payback is an indication of how long it would take to recover the difference in investment costs between the proposed system and the base case system.

Total Annualized Cost
Total Annualized Cost is the annualized value of the total net present cost. The annualized cost of a component is the cost that, if it were to occur equally in every year of the project lifetime, would give the same net present cost as the actual cash flow sequence associated with that component. HOMER calculates annualized cost by first calculating the net present cost, then multiplying it by the capital recovery factor.

PREPARED BY:

Tobias Pizot,
Staff Professional, Carollo Engineers,
[email protected],
3609094857

Page 13 of 13 ends

HOMER Energy

ABOUT HOMER ENERGY
HOMER software is used by
more than 200,000 users in
193 different countries.

HOMER Energy is the world’s leading microgrid modeling software company. The Hybrid Optimization of Multiple Energy Resources (HOMER) software helps engineers and project developers navigate the complexities of designing cost-effective and reliable microgrids that combine traditional and renewable generation sources.

HOMER evaluates thousands of variables to compare value streams, assess system options, and provide risk-mitigation and cost reduction strategies. The software includes hundreds of preconfigured components to offer detailed insight, while addressing the modeling requirements of all major microgrid segments.

HOMER software is utilized by over 200,000 users in 193 countries and is trusted by governments, financial institutions, military agencies, utilities, energy systems integrators, and NGOs to design hybrid power systems. In the last decade, HOMER has demonstrated its effectiveness for analyzing complex distributed energy systems, including grid-tied hybrid renewable microgrids and situations where the grid is insufficiently reliable, such as islands and remote communities.

ABOUT HOMER GRID
HOMER Grid is a powerful software solution for modeling hybrid energy systems and evaluating options to reduce electricity expenditures. It is a robust tool that combines engineering and economics information in one comprehensive model while rapidly performing complex calculations to determine the value of self-consumption, demand charge reduction, and energy arbitrage.

HOMER Grid allows users to compare multiple components and design outcomes, identify points at which different technologies become cost-competitive, and consider options for minimizing project risk and determining the most economic design. With integrated access to more than 20k tariffs in the US, Canada, and Mexico, and the ability to model any tariff, HOMER Grid simulates real-world performance to deliver informed choices for system design and optimization.

VOLUME 9 / CHAPTER 1: ENERGY MANAGEMENT
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA

WASTEWATER TREATMENT PLANT MASTER PLAN

APPENDIX C FINANCIAL ASSUMPTIONS AND PROCESS

ASSUMPTIONS

FINANCIAL

ASSUMPTION VALUE UNIT REMARK
Present worth Year 2034end of evaluation 2054Inflation (capital) 3.7%Inflation (electricity) 3.7%Inflation (natural gas) 3.7%Inflation (O&M costs) 2.0% inflation applied once in 10 years due to fixed maintenance contractsGross discount rate 6%Digester Gas LHV, 600 btu/scfEngine availability 88%Turbine availability 88%Parasitic Power 5%O&M cost for gas engine $0.035 $/kWh based on quoted maintenance contracts and Riverside DG Life Cycle CostO&M cost for solar $0.011 $/kWhO&M cost for battery battery O&M cost done by HOMERO&M rate for microturbine $0.030 $/kWh based on quoted maintenance contracts and Riverside DG Life Cycle CostO&M rate for fuel treatment $0.900 $/mmBTU based on Riverside Life Cycle cost analysisO&M rate for flare $85.00 $/cfm based on existing costsO&M rate for fuel treatmentAve Natural gas sale price 0.40 $/therm quoted price from SoCalGas resourcesAve Natural gas sale price $4.0 $/mmBTU PROCESS PROJECTIONS Current Phase 1 End of Phase 1 Remark Year 2024 2034 2054 from Vol. 2Plant Flow (mgd) 7.5 8.5 9.9 from Vol. 2 and vol. 3 TWAS loading increaseGas production (scfd) 162000 227000 267000 accounts for ramp up in flow, switch from trickling filter to Activated Sludge increase production, BioWin Process ModelGas production (scfm) 112.5 157.6 185.4Average plant heat load (mmBTU/hr) 0.888 1.11 1.53 95% boiler efficiency, 2024 values assume 2 digesters in operation, 2054 value assumes all 3 in operation (25.3 mmBTU - 34.8 mmBTU)Peak heat load (mmBTU/hr) 1.136 1.42 1.95 peak heat value of 1.28 derived from existing digester dataAve. Electric usage - no solar (kWh/d) 5624 16440 16440Average electrical demand (kW) 234 685 685 flow weighted, demand remains steady over timePeak.Electrical demand (kW) 300 946 946 1.3x average, demand remains steady over timeAverage solar demand reduction (kW) - 183 183 calculated with NREL and HOMER grid softwareAverage electrical demand w/solar (kW) - 502 502 calculated with NREL and HOMER grid software

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 10: Air Quality and
Emissions Odor Control
FINAL / October 2026

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 10: Air Quality and
Emissions Odor Control
FINAL / October 2026
Digitally signed by Graham J.G. Juby
Contact Info: Carollo Engineers, Inc.

Date: 2026.10.24 11:23:18-07'00'
VOLUME 10 / AIR QUALITY AND EMISSIONS ODOR CONTROL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN i
pw://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/Master Plan/Volume 10/_Cover_TOC_Abbrevs_AppxCovers.docx Contents
CHAPTER 1 AIR QUALITY EMISSIONS

1.1 Introduction 1-1

1.2 Background 1-1

1.2.1 Federal 1-1

1.2.2 State 1-2

1.2.3 Local 1-2

1.3 Facilities Impacting Air Quality 1-3

1.3.1 Existing Facilities Impacting Air Quality 1-3

1.3.2 Future Facilities Impacting Air Quality 1-4

1.4 Facilities Impacting Odor 1-7

1.4.1 Existing Facilities Impacting Odor 1-7

1.4.2 Future Facilities 1-9
CHAPTER 2 PERMITTING PLAN

2.1 Introduction 2-1

2.2 Permits Requiring Modification 2-1

2.2.1 Central Coast Regional Water Quality Control Board 2-1

2.2.2 Biosolids 2-2

2.3 New Permits Required for Future Expansion 2-3

2.3.1 City of Santa Maria Community Development Department 2-3

2.3.2 Santa Barbara County Air Pollution Control District 2-3

2.3.3 Santa Barbara County Environmental Health Services Certified Unified Program Agency 2-5

2.3.4 State Water Resources Control Board 2-5

2.3.5 State of California Department of Industrial Relations Division of Occupational Safety and Health 2-6

2.3.6 Post Construction Additional Permits and Programs 2-6

2.3.7 Pretreatment Program 2-7

2.3.8 SWRCB Environmental Laboratory Accreditation Program 2-7

2.4 Permitting Plan Summary 2-7
Appendices

APPENDIX A EXISTING SANTA MARIA WWTP PERMITS
Tables
Table 1.1 Santa Maria Permit Potential to Emit Limits - Tons Per Year 1-3 Table 1.2 Flares and Boiler No. 1 Permitted Flows 1-4
Table 1.3 City WWTP SBCAPCD Permits Required for Expansion 1-7 VOLUME 10 / AIR QUALITY AND EMISSIONS ODOR CONTROL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN ii
Table 1.4 Planning Level Cost for Odor Control Improvements 1-15 Table 2.1 Permitting Plan for Santa Maria WWTP Expansion Program 2-8 Figures
Figure 1.1 Facilities Impacting Air Quality 1-6
Figure 1.2 Existing Facilities Contributing to Odor 1-8 Figure 1.3 Phase 1 Expansion Odor Control Strategy - Reuse Primary Trickling Filter No. 2 1-11
Figure 1.4 Phase 1 Expansion Odor Control Strategy - Option to Construct a New TF Pump Station 1-12
Figure 1.5 Phase 2 WWTP Facilities Layout 1-14
Figure 2.1 Permitting Schedule for Phase 2-11
VOLUME 10 / AIR QUALITY AND EMISSIONS ODOR CONTROL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN iii
Abbreviations
APCD Air Pollution Control District
ATC Authority to Construct
BACT Best Available Control Technology
BMP Best Management Practices
BOD biochemical oxygen demand
CAA Clean Air Act
CAAQS California Ambient Air Quality Standards
Cal/OSHA California Division of Occupational Safety and Health CARB California Air Resources Board
CBC California Building Code
CEQA California Environmental Quality Act
CERS California Environmental Reporting System
CFR Code of Federal Regulations
CH4 methane
CHP combined heat and power
City City of Santa Maria
CO carbon monoxide
CO2 carbon dioxide
Cogen cogeneration
CUPA Certified Unified Program Agency
E&G Engel & Gray, Inc.

EHS Environmental Health Services
ELAP Environmental Laboratory Accreditation Program
EPA Environmental Protection Agency
H2S hydrogen sulfide
HMBP Hazardous Materials Business Plan
IGP Industrial General Permit
mgd million gallons per day
mmBTU million British Thermal Units
MS4 Municipal Separate Storm Sewer Systems
N/A not applicable
NAAQS National Ambient Air Quality Standards
NESHAP National Emissions Standards for Hazardous Air Pollutants NOx nitrogen oxides
NOA Notice of Applicability
NOI Notice of Intent
PCR Post Construction Requirement
VOLUME 10 / AIR QUALITY AND EMISSIONS ODOR CONTROL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN iv
PM particulate matter
ppmv parts per million as volume
PTO Permit to Operate
ROC reactive organic compounds
ROWD Report of Waste Discharge
RWQCB Regional Water Quality Control Board
SBCAPCD Santa Barbara County Air Pollution Control District scf standard cubic feet
scfm standard cubic feet per minute
SMARTS Stormwater Multiple Application and Report Tracking System SOx sulfur oxides
SWCP Stormwater Control Plan
SWPPP Stormwater Pollution Prevention Plan
SWRCB State Water Resource Control Board
TNI The NELAC Institute
VAR vector attraction reduction
VOC volatile organic compound
WDR Waste Discharge Requirements
WWTP wastewater treatment plant
VOLUME 10 / CHAPTER 1: AIR QUALITY EMISSIONS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-1
CHAPTER 1 AIR QUALITY EMISSIONS

1.1 Introduction
Wastewater treatment plants (WWTPs) contribute significantly to meeting the statewide air quality targets; therefore, it is important for the City of Santa Maria's (City) WWTP to maintain compliance with all applicable air quality regulations. As the WWTP expands, managing air emissions and odors becomes increasingly important to comply with regulatory requirements and maintain positive community relations. This chapter outlines existing and future facilities and processes at the City's WWTP that impact air quality, regulatory context, and expected permitting requirements for the expansion of the WWTP. This chapter will also identify both existing and future odor sources and identify odor control strategies should these be needed as the plant expands in the future.

1.2 Background
The City's WWTP provides wastewater treatment services to residents and commercial dischargers and provides septage receiving services for the community and the surrounding area. The WWTP consists of septage receiving, headworks, primary clarifiers, primary trickling filters, an intermediate clarifier, secondary trickling filters, secondary clarifiers, percolation ponds, thickeners, digesters, and sludge drying beds. The WWTP operates under several environmental permits, including those issued by the Santa Barbara County Air Pollution Control District (SBCAPCD). Existing SBCAPCD permits primarily govern criteria pollutant emissions from combustion equipment and odor control systems. Facility upgrades and expansion efforts may require modifications to existing permits and trigger new permitting requirements based on emissions thresholds and control technologies. The following subsections provide an overview of current regulations on criteria pollutants at the federal, state, and local levels. For additional information regarding regulatory setting and overview, refer to Volume 2, Chapter 4 - Regulatory Considerations.

1.2.1 Federal
At the federal level, the Environmental Protection Agency (EPA) establishes and enforces the federal regulations that govern air emissions generated by the Santa Maria WWTP facilities. Most of the regulations impacting WWTP air emissions are based on the Clean Air Act (CAA). The CAA creates a comprehensive national framework designed to protect ambient air quality by limiting air emissions for both stationary and mobile sources. The CAA primarily regulates six common air pollutants, which are referred to as "criteria air pollutants." Per the CAA, the EPA establishes National Ambient Air Quality Standards (NAAQS) for the six criteria pollutants to protect human health and welfare. These standards are codified in 40 Code of Federal Regulations (CFR) Part 50, National Primary and Secondary Ambient Air Quality Standards, or NAAQS. The six criteria pollutants are:
 Ozone.
 Particulate matter (PM) (PM10 and PM2.5).
 Lead.

VOLUME 10 / CHAPTER 1: AIR QUALITY EMISSIONS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-2
 Carbon monoxide (CO).
 Sulfur oxides (SOx).
 Nitrogen oxides (NOx).

1.2.2 State
At the state level, the California Air Resources Board (CARB) develops statewide policy and regulations for the protection of public health from the effects of air pollution and enforces federal regulations to meet minimum air quality standards. The EPA requires states to adopt and enforce plans to achieve the NAAQS.

As such, CARB has set California Ambient Air Quality Standards (CAAQS) to enforce the NAAQS for the six criteria pollutants as well as four additional pollutants. The four additional pollutants include:
 Hydrogen sulfide (H2S).
 Sulfate.
 Vinyl chloride.
 Visibility-reducing particles (i.e., particles that reduce visibility for airport safety, scenic enjoyment, road safety, etc.).

1.2.3 Local
Air regulations are implemented locally by the SBCAPCD, which ensures compliance to safeguard air quality in the region. The local air districts regulate emissions from factories, industrial facilities, and other stationary sources, such as combustion engines, boilers, and flares at WWTPs. Additionally, the local air districts provide permitting, air quality attainment planning, rulemaking, air quality monitoring, and incentive programs.

There are two primary types of air quality permits applicable to WWTPs: the Permit to Operate (PTO) and the Authority to Construct (ATC). The PTO authorizes the operation of equipment that emits pollutants and requires renewal every three years. For instance, the PTO for the City's WWTP, identified as PTO No. 08390-R11, is reevaluated triennially, with the most recent review conducted in September 2024.

The ATC permits the construction of new equipment or the modification of existing equipment that will emit pollutants and is renewed as needed based on the project's timeline.

The PTO comes with stringent requirements to ensure ongoing compliance with emission standards. This includes specific limits on pollutants such as NOx, CO, SOx, PM10, and PM2.5, which are discussed below.

There are also operational restrictions, including the volume of digester gas and propane that can be burned daily. The permit mandates proper maintenance and operation of equipment, and strictly prohibits the venting of digester gas except under breakdown conditions.

Monitoring and recordkeeping are essential components of compliance. Daily monitoring of digester gas and propane volumes combusted must be conducted using calibrated flow meters. Detailed records must be maintained, including daily volumes of fuel used, maintenance logs, and instances of leaks or H2S alarms. Additionally, annual reports documenting compliance with permit conditions must be submitted by March 1 of each year. These reports include data on emission levels, fuel usage, and any corrective actions taken. Compliance and enforcement mechanisms are in place to ensure adherence to the permit conditions. This includes the implementation of an SBCAPCD-approved Inspection and Maintenance Plan, which details procedures for detecting and repairing leaks, maintaining equipment, and ensuring VOLUME 10 / CHAPTER 1: AIR QUALITY EMISSIONS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-3
compliance with emission thresholds. Biennial source testing of emissions and process parameters is also required to verify compliance with emission standards.

1.3 Facilities Impacting Air Quality
The Santa Maria WWTP has several facilities that impact air quality and require Air Pollution Control District (APCD) PTOs. This section summarizes the existing facilities that impact air quality and the existing APCD permit. Additionally, the expansion of the WWTP will include new and modified facilities that will impact air quality and require new PTOs and ATCs. This section also details future facilities planned as part of the expansion that will impact air quality and require new or modified APCD permits.

1.3.1 Existing Facilities Impacting Air Quality
Existing flares, digesters, and boilers at the City's WWTP impact air quality and require PTOs from the SBCAPCD. The City operates anaerobic digesters to treat its biosolids, generating methane (CH4) and carbon dioxide (CO2) during the digestion process. A portion of the biogas is burned in a boiler to make hot water for heating the digesters, and the remainder of the gas is flared. Boiler No. 1, the primary boiler, burns digester gas with propane gas as a backup, while the standby unit (Boiler No. 2) burns only propane gas and is exempt from regulations. There are two waste flares equipped with a pilot flare and fueled by propane gas as a back-up. An iron sponge scrubber is also a part of the system to remove hydrogen sulfide in the produced gas ahead of the boilers and flares.

The local regulations, enforced by the SBCAPCD, take into account the state and federal rules on criteria and hazardous pollutants. The existing permit to operate the flares, digesters, and boilers onsite is PTO No. 08390-R11. The permit regulates the amount of criteria pollutants and the quantity of fuel that may be burned. Table 1.1 lists the permit potential to emit for recognized air quality pollutants under PTO No. 08390-R11.

Table 1.1 Santa Maria Permit Potential to Emit Limits - Tons Per Year Equipment NOx ROC CO SOx PM PM10 PM2.5 Maximum Fuel Input (mmBTU/hour)
Flare 1 1.38 1.75 7.5 4.55 0.41 0.41 0.41 4.63
Flare 2 3.56 4.52 19.37 11.74 1.05 1.05 1.05 12.0
Flare 1 (pilot) 0.03 0.04 0.15 0.05 0.01 0.01 0.01 0.095 Flare 2 (pilot) 0.03 0.04 0.15 0.05 0.01 0.01 0.01 0.095 Boiler (digester gas) 0.4 0.06 3.26 2.46 0.08 0.08 0.08 2.51 Boiler (propane) 0.4 0.06 3.26 0.18 0.08 0.08 0.08 Exempt Iron Sponge Scrubber - 0.01 - - - - - -
Total 4.02 4.66 22.94 14.30 1.15 1.15 1.15 N/A
Notes:
mmBTU - million British Thermal Units; N/A - not applicable; ROC - reactive organic compounds In addition to the limits, H2S is continuously monitored using an ambient monitoring system. H2S concentrations are reduced because of the iron sponge scrubbing and ferrous chloride injection system.

The current limit for H2S at atmospheric conditions is 796 parts per million as volume (ppmv).

VOLUME 10 / CHAPTER 1: AIR QUALITY EMISSIONS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-4
The typical daily average concentration of H2S in the treated biogas in 2023, downstream of the iron sponge, was well below the limit, at 197 ppmv.

In addition to the maximum fuel input shown, there are maximum volume limits for monthly digester gas production and for propane gas for boilers and flares.

The permit stipulates the maximum biogas flow to each flare and Boiler No. 1, as shown in Table 1.2.

The total average biogas production in 2023 was 161,335 standard cubic feet (scf) per day. Typical biogas usage in Boiler No. 1 in 2023 was 35,400 scf per day. The combined energy that the flares can burn each day is 291.5 mmBTU per day.

Table 1.2 Flares and Boiler No. 1 Permitted Flows
Equipment SCF per Day SCFM
Flare 1 185,200 128.6
Flare 2 293,000 203.5
Flare 1+2 Pilots (propane) 1800 1.25
Boiler 1 Max Flow (digester gas) 100,000 69.4
Boiler 1 Max Flow (propane) 24,000 16.6
Notes:

SCFM - standard cubic feet per minute
Stringent monitoring is required for the system; annual reports are due to the SBCAPCD with information regarding waste gas production, flaring, and H2S concentrations.

1.3.2 Future Facilities Impacting Air Quality
The expansion of the City's WWTP includes modification of existing facilities and new facilities that impact air quality and will require new permits from the SBCAPCD. The Phase 1 Expansion requires a total of three anaerobic digesters. At least one additional anaerobic digester will be constructed as part of the Phase 1 project, and two of the existing digesters, Digester No. 1 and Digester No. 4, will either be rehabilitated and used as an anaerobic digester or converted to a sludge storage tank, depending on their condition. This would mean that biogas flaring and utilization of biogas as a boiler fuel would continue.

However, due to the age of existing components and the potential for stricter criteria pollutant laws, new methane boilers and waste gas flares will be constructed in Phase 1 of the project. As such, the criteria pollutants regulated under the existing permit would remain in effect, but a new SBCAPCD permit would be required.

Also planned as part of the WWTP expansion to meet the plant's proposed power and heating demands is a new co-generation facility. Further detailed in Chapter 1 of Volume 9 of the Master Plan, a combined heat and power combustion engine will be included as part of Phase 1 of the project and will produce heat for use in the anaerobic digesters and electricity for use at the facility. The gas will be treated before entering the system to maintain high engine performance standards and meet APDC requirements for exhaust emissions. The exhaust heat from the gas engines will be recovered and used for anaerobic digesters heating, and a duty-standby flare and a standby boiler will remain as a backup in the case of engine downtime. Permitting a gas engine in Santa Barbara County must follow existing Best Available Control Technology (BACT) guidelines for the APCD. There would be a large degree of monitoring and compliance tasks to maintain compliance with the permits. The gas conditioning skids will be compliant VOLUME 10 / CHAPTER 1: AIR QUALITY EMISSIONS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-5
with current APCD regulations and will have significant monitoring requirements, including annual APCD permits, reports, and calibration. Figure 1.1 highlights existing facilities that impact air quality and will require updates to the existing APCD permit, and new facilities that will require new permits. This information is also detailed in Table 1.3.

VOLUME 10 / CHAPTER 1: AIR QUALITY EMISSIONS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-6
Figure 1.1 Facilities Impacting Air Quality
VOLUME 10 / CHAPTER 1: AIR QUALITY EMISSIONS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-7
Table 1.3 City WWTP SBCAPCD Permits Required for Expansion Facilities Type of APCD Permit Required in Phase 1 Required in Phase 2 Flare 1 PTO Update Update
Flare 2 PTO Update Update
Flare 1 (pilot) PTO Update Update
Flare 2 (pilot) PTO Update Update
New Boiler ATC New Not Required
New Boiler PTO New Update
Iron Sponge Scrubber PTO Update Update
CHP Engine(1) ATC New Not Required
CHP Engine(1) PTO New Update
Waste Gas Flare ATC New Not Required
Waste Gas Flare PTO New Update
Notes:

CHP - combined heat and power
(1) BACT evaluation required.

1.4 Facilities Impacting Odor
Effective odor management is essential to the operation of the City WWTP. Odors generated from various treatment processes can lead to regulatory scrutiny and neighbor complaints if not properly controlled.

This section identifies current and future odor sources at the facility and evaluates future odor control strategies.

1.4.1 Existing Facilities Impacting Odor
Several existing treatment processes at the WWTP are known contributors to odor emissions, particularly during warmer months or periods of high organic loading. The facilities listed below and highlighted in Figure 1.2 are open to the atmosphere, allowing for the release of volatile organic compounds (VOCs), hydrogen sulfide (H2S), and other odorous compounds.
 Septage Receiving Station:
» High-strength loads contribute to strong odors.
 Headworks:
» Raw influent with turbulent flow can release VOCs and H2S.  Grit Chamber:
» Uncovered and allows for escape of odorous compounds.  Primary Clarifiers:
» Uncovered and allows for escape of odorous compounds.  Gravity Sludge Thickeners:
» Uncovered and allows for the escape of odorous compounds from primary sludge.

VOLUME 10 / CHAPTER 1: AIR QUALITY EMISSIONS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-8
Figure 1.2 Existing Facilities Contributing to Odor
VOLUME 10 / CHAPTER 1: AIR QUALITY EMISSIONS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-9
Currently, there are no odor control facilities at the WWTP. The plant is surrounded by agricultural processes and no residential areas, so there has not been a need for odor control facilities.

1.4.2 Future Facilities
As part of the plant's long-term odor management approach, both Phase 1 and Phase 2 expansion efforts will incorporate upgrades to reduce and control odor emissions.

1.4.2.1 Phase 1 Expansion
During Phase 1 of the plant expansion, the grit chamber will be replaced with a covered vortex de-gritting system, which will require foul air ventilation and probably an in-ground biofilter. This will reduce the potential for odor in this area. The existing sludge drying beds will be eliminated to create space for the new aeration basins and replaced by a new mechanical dewatering facility. The septage receiving station, headworks, and primary clarifiers will remain uncovered during Phase 1 of the project, and the primary clarifiers will likely be the largest source of odor.

As part of the Phase 1 expansion, there will be a reduction in the amount of recycled flow to the primary clarifiers because the existing trickling filters will be shut down, making it likely that only one of the two primary clarifiers will need to be operated under normal conditions. In order to mitigate potential odor issues from the operating primary clarifier, one mitigation strategy considered was to keep the existing Primary Trickling Filter No. 2 ( the most recently constructed) to help with odor control. The concept is that by retaining Primary Trickling Filter No. 2, oxygenated flow would be continuously recirculated to the primary clarifier in operation, thereby helping to suppress anaerobic conditions that generate H2S. This concept is shown schematically in Figure 1.3. To make this work, two options were considered for the pumping arrangement.
 Option 1: Rehab of Existing Primary Trickling Filter Pump Station:
» To provide odor mitigation for the existing uncovered primary clarifiers during Phase 1, this option would rehabilitate the existing primary trickling filter pump station so that it can pump primary effluent from the primary clarifier in service to the existing Primary Trickling Filter No. 2.

Rehabilitation of the pump station would include a new concrete liner, piping, pumps, and valves.

The rehabilitated pump station would receive primary effluent from the primary clarifier(s) and pump primary effluent to the primary trickling filter through already existing pipework. The effluent from the primary trickling filter would be circulated back to the primary clarifier feed through new pipework.
 Option 2: New Primary Trickling Filter Pump Station:
» This option would construct a new, smaller primary trickling filter pump station at a location where the primary effluent pipes from the primary clarifiers intersect. The new pump station would use H2S-resistant concrete admixture and would include an overflow weir to send excess primary clarified water to the new aeration basins when flow from the primary clarifiers exceeds the capacity of the primary trickling filter. For this option, because new pipework will be required, the primary trickling filters distributor mechanism would be upgraded to include two additional arms to increase capacity from 7.8 million gallons per day (mgd) to 11.7 mgd or more. Figure 1.4 illustrates this odor mitigation strategy for Phase 1 expansion.

VOLUME 10 / CHAPTER 1: AIR QUALITY EMISSIONS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-10
A possible negative outcome of the approach to keep Primary Trickling Filter No. 2 in operation is that, because of incidental biochemical oxygen demand (BOD) removal in the trickling filter, additional chemicals may be required to accomplish full denitrification in the new aeration basins. This aspect will need to be further evaluated during the preliminary design.

Other options for controlling potential odor from the primary clarifiers during Phase 1 will also be developed and considered during the preliminary design phase so that the City can compare options and select the most suitable approach.

VOLUME 10 / CHAPTER 1: AIR QUALITY EMISSIONS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-11
Figure 1.3 Phase 1 Expansion Odor Control Strategy - Reuse Primary Trickling Filter No. 2 VOLUME 10 / CHAPTER 1: AIR QUALITY EMISSIONS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-12
Figure 1.4 Phase 1 Expansion Odor Control Strategy - Option to Construct a New TF Pump Station VOLUME 10 / CHAPTER 1: AIR QUALITY EMISSIONS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-13

1.4.2.2 Phase 2 Expansion
In Phase 2 of the plant expansion, an odor control facility would be constructed to treat foul air from the septage receiving station, the future headworks and grit removal system, and the updated covered primary clarifiers. Space has been allocated in the Phase 2 layout, shown in Figure 1.5, for a new odor control system utilizing an in-ground biofilter. An in-ground biofilter uses organic media, such as wood chips and compost to biologically degrade odorous compounds, including H2S and VOCs. In-ground systems offer passive treatment with low energy demand and high removal efficiency and are well-suited for continuous odor sources.

VOLUME 10 / CHAPTER 1: AIR QUALITY EMISSIONS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-14
Figure 1.5 Phase 2 WWTP Facilities Layout
VOLUME 10 / CHAPTER 1: AIR QUALITY EMISSIONS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-15

1.4.2.3 Cost Considerations
Odor control improvements for the Santa Maria WWTP will be implemented in a phased approach, balancing operational effectiveness with capital investment. Phase 1 focuses on leveraging existing infrastructure for low-cost odor mitigation, while Phase 2 anticipates construction of a centralized treatment system. Table 1.4 provides high-level planning costs for odor control improvements for both Phases 1 and 2 of the plant expansion. As noted, other mitigation measures for Phase 1 will be considered and evaluated during the preliminary design phase.

Table 1.4 Planning Level Cost for Odor Control Improvements Phase Odor Control Improvement Key Components Estimated Costs 1 Option 1: Primary Trickling
Filter Recirculation w/ Existing
Primary Trickling Filter Pump
Station
 Use of existing trickling filter
and pipework.
 Rehab of primary trickling
filter pump station includes
new concrete liner, piping,
pumps, and valves.
 Controls to adjust
recirculation rate based on
odor conditions.
$2-3 million
1 Option 2: Primary Trickling
Filter Recirculation w/ New
Primary Trickling Filter Pump
Station
 Use of existing trickling filter.
 New pipework and primary
trickling filter pump station.
 New pump station will use
H2S-resistant concrete
admixture and overflow weir.
 Controls to adjust
recirculation rate based on
odor conditions.
 Upgrade Primary Trickling
Filter No. 2 distributor
mechanism to add 2 more
arms.
$5-6 million
2 Biofilter Centralized Odor
Control System
 In-ground biofilter.
 Fiberglass ducting from
process areas.
 Fans/blowers for ventilation.
$3-4 million
VOLUME 10 / CHAPTER 2: PERMITTING PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-1
CHAPTER 2 PERMITTING PLAN

2.1 Introduction
The City of Santa Maria (City) is embarking on a large program to upgrade its existing wastewater treatment plant (WWTP) to meet the new General Permit requirements issued by the Central Coast Regional Water Quality Control Board (RWQCB). The first phase of the program (Phase 1) is expected to be complete by late 2033 or early 2034. Throughout this program, existing permits held by the City's WWTP will require modifications, and additional permits will be required during construction. This chapter provides a permitting plan for the program that includes a list of permits, contact persons, probable requirements, and an anticipated schedule for the permit applications and receipt of permits.

2.2 Permits Requiring Modification
The City's WWTP has several permits that are required under the current plant configuration that will require modification at some point during the Phase 1 program. The subsequent sections describe the existing permits that will need to be modified and the probable requirements for permit modification.

Table 2.1 at the end of the section provides a list of these permits, contact persons, and the anticipated schedule for the permit applications and receipt of permits and current copies of all existing permits are included in Appendix A.

2.2.1 Central Coast Regional Water Quality Control Board The City's WWTP operates under General Waste Discharge Requirements (WDR) Order No. R3-2020-0020, issued by the Central Coast RWQCB. This permit applies to domestic wastewater facilities with flows exceeding 100,000 gallons per day and regulates land-based discharges, including percolation ponds and land application systems. As the City moves forward with its Phase 1 treatment plant expansion, it will be necessary to update the facility's permit coverage under this general order to reflect increased flow capacity, revised treatment processes, and potential changes in discharge characteristics.

An update to the permit is triggered when there is a planned increase in average dry weather flow, modifications to the treatment process that may affect effluent quality, or changes to the discharge location or method. Wastewater system expansions must be made in accordance with the conditions of the General Permit and require re-evaluation of the existing Notice of Applicability (NOA). Pursuant to California Water Code Section 13260, the Discharger must inform the Central Coast Water Board Executive Officer at least 120 days prior to making a material change in the character, location, or volume of discharge.

The expansion project will require submittal of an updated Report of Waste Discharge (ROWD), which must detail both phases of construction, anticipated flow increases, revised treatment train configuration, updated influent and effluent characteristics, and any modifications to disposal methods. The ROWD should also include site plans, process flow diagrams, and environmental documentation under the California Environmental Quality Act (CEQA).

VOLUME 10 / CHAPTER 2: PERMITTING PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-2
The City is also planning one or more near-term projects in preparation for the larger Phase 1 expansion.

One example is the construction of new percolation ponds. This will require a modification of the current permit. The City is planning to meet with the RWQCB regarding this project and other milestone requirements set out in the Time Schedule Compliance Plan, which will provide an opportunity to review the scope and timeline of the program and confirm permitting expectations. Depending on the scale and timing of individual projects, the RWQCB may issue an amended NOA with phase-specific conditions or flow triggers. To ensure regulatory compliance, the updated permit must demonstrate that the facility will continue to meet effluent limitations, avoid degradation of water quality, and incorporate appropriate monitoring and operational controls. The ROWD and associated materials will need to be submitted well in advance of Phase 1 construction, typically six months prior, to allow for adequate regulatory review and coordination with CEQA documentation.

2.2.2 Biosolids
The City's WWTP currently produces Class B biosolids and disposes of them at the City's landfill and the Engel & Gray, Inc. (E&G) composting facility. Any changes to solids production volumes, treatment processes, or end-use locations triggered by the plant expansion will require updates to the facility's biosolids management plan, possible revisions to the waste discharge permit, and applications for new hauling permits.

Phase 1 of the expansion is expected to increase solids digestion capacity. While this phase may not immediately change the final biosolids classification or end-use method, the increased digester volume may alter retention times, volatile solids reduction performance, or pathogen vector attraction reduction (VAR) strategies. Any change in these parameters must be documented and reported in accordance with the 40 Code of Federal Regulations (CFR) Part 503 requirements, including updated sampling and analysis data. Additionally, as detailed in Volume 8 of the Master Plan, the disposal destination for the biosolids produced by the WWTP may change, triggering an update to the biosolids management plan and the application for new land application permits during Phase 1 of the program.

The ultimate expansion of the WWTP around 2045, Phase 2, will introduce further solids processing impacts due to the addition of another digester and new gas handling systems. If biosolids production increases substantially or if operational changes affect stabilization, dewatering, or beneficial use pathways, the City will need to update its Biosolids Management Plan and possibly seek revised land application agreements or permits from receiving counties. Additionally, the RWQCB may request a revised biosolids handling section of the plant's ROWD or require updates under the general WDR order if biosolids storage or discharge to land areas are modified.

To remain in compliance, it is recommended that the City conduct an early review of biosolids treatment and performance projections for both phases and consult with the Central Coast RWQCB and any destination counties for land-applied biosolids. Annual biosolids reports submitted to the United States Environmental Protection Agency (EPA) and RWQCB under Part 503 will need to reflect the updated volumes and characteristics following each expansion phase.

VOLUME 10 / CHAPTER 2: PERMITTING PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-3

2.3 New Permits Required for Future Expansion
This section summarizes the new permits required for both phases of the expansion program at the City's WWTP. Table 2.1 at the end of the section provides a list of these permits, contact persons, and the anticipated schedule for permit applications and receipt of permits.

2.3.1 City of Santa Maria Community Development Department The City's Community Development Department oversees and guides land use, construction, and community planning within the city. The Building Division enforces building codes and inspects projects during construction. It conducts building plan reviews and issues building permits to ensure public health, safety, and structural compliance.

2.3.1.1 Building Permit
A building permit is required for the construction, alteration, or repair of any occupied structure at the WWTP. The permit ensures compliance with the California Building Code (CBC), electrical, mechanical, plumbing, and fire codes. Submittals typically include stamped construction drawings, structural calculations, and architectural layouts. The Building Division of the City's Community Development Department is mandated by State Law 17960 (Health & Safety Code) to be responsible for monitoring construction activity and to determine that any ongoing construction project has the required permits and conforms to the approved plans and any conditions of approval. Building permit applications should be submitted during the final design. The lead time for review/approval is typically four to eight weeks, depending on the complexity. For each phase of the proposed program, it is anticipated that a separate Building Permit will be required.

2.3.2 Santa Barbara County Air Pollution Control District The City's WWTP currently operates under Permit to Operate (PTO) No. 08390-R11, issued by the Santa Barbara County Air Pollution Control District (SBCAPCD). As part of the plant expansion, the PTO will need to be revised to reflect new emission sources and operational changes associated with both phases of the facility's planned expansion. The current permit governs existing digester gas and combustion-related operations, and any physical or operational modification that results in a change in emissions, control equipment, or process throughput requires Air Pollution Control District (APCD) approval through the Authority to Construct (ATC) process.

Phase 1 of the expansion involves the addition of one new anaerobic digester and the modification of an existing digester. These changes are expected to increase biogas generation and alter the load on existing gas-handling systems, thereby affecting emissions from flares, gas conditioning units, and any backup combustion systems. In addition, the Phase 1 project includes the addition of a biogas combustion engine for energy and heat recovery. APCD will require a permit modification to assess these impacts and ensure continued compliance with emission limits for volatile organic compounds (VOCs), methane, hydrogen sulfide, and other constituents.

Phase 2 introduces several new stationary sources, including an additional anaerobic digester, a new digester flare, hot water boilers, and a combined heat and power (CHP) cogeneration (Cogen) facility.

These sources will generate additional emissions of criteria pollutants as well as greenhouse gases. As such, they may be subject to APCD's New Source Review (Rule 370) Best Available Control Technology VOLUME 10 / CHAPTER 2: PERMITTING PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-4
(BACT) requirements and toxic air contaminant evaluation under Rule 802. Emissions modeling and stack parameters for the flare and Cogen system may be required to demonstrate compliance with ambient air quality standards and permit thresholds.

Coordination with APCD should begin early in the design process to confirm regulatory applicability and permitting pathways. For each phase of the program, the project team will need to prepare an ATC application that includes detailed descriptions of the new or modified equipment, manufacturer specifications, projected emissions data, proposed control technologies, and any required air dispersion modeling.

In summary, the Santa Maria WWTP operates and plans to construct several stationary air emissions sources that are subject to permitting through the SBCAPCD. These sources include combustion and gas handling equipment such as standby generators, sludge heating boilers, anaerobic digesters, flares, and Cogen engines. Under SBCAPCD rules, new equipment requires an ATC, and all equipment requires a PTO.

For the ATC permit application, submittal of design specs, emission estimates, fuel types, and operating scenarios must be submitted. ATC must be approved before the equipment installation. After installation and performance validation, an application for PTO can be submitted. Additionally, BACT may be required for new or modified sources emitting above the defined thresholds. The anticipated lead time for obtaining an updated ATC permit is six to twelve months.

2.3.2.1 Construction-Related Permits
For the Santa Maria WWTP two-phase upgrade project, construction activities will trigger several additional SBCAPCD permits. Portable construction equipment rated at 50 brake horsepower or greater (e.g., generators, pumps, compressors) must either be registered in the California Air Resources Board (CARB) Portable Equipment Registration Program or be permitted individually by SBCAPCD.

Additionally, because both phases will include multi-year grading, excavation, and demolition, the project must comply with Rule 345 (Control of Fugitive Dust). This rule applies to any activity associated with the construction or demolition of a structure or structures and includes requirements for visible fugitive dust beyond the property line, truck hauling, carry-out, and demolition. This rule is a standards-based rule with no recordkeeping, permitting, or dust control plant requirements. District Inspectors can issue Notices of Violation for sources that are causing a nuisance or failing to comply with the rule requirements.

Demolition activities also require compliance with the Asbestos National Emissions Standards for Hazardous Air Pollutants (NESHAP) in accordance with the Clean Air Act (CAA). The Asbestos NESHAP specifies work practices to be followed during demolitions and renovations of structures and requires contractors to notify the SBCAPCD before demolitions or renovations of buildings that contain a certain threshold amount of asbestos. The contractor will be required to complete an asbestos survey and submit a notification to the SBCAPCD at least 10 working days before demolition that must include the scheduled starting and completion date of the work, the location of the site, the names of operators or asbestos removal contractors, methods of removal and amount of asbestos, and whether the operation is a demolition or renovation.

VOLUME 10 / CHAPTER 2: PERMITTING PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-5

2.3.3 Santa Barbara County Environmental Health Services Certified Unified Program Agency
The Santa Barbara County Environmental Health Services (EHS) Department, acting as the Certified Unified Program Agency (CUPA), regulates hazardous materials management at the Santa Maria WWTP under California's unified hazardous materials and waste program. Facilities that store or use hazardous substances above threshold quantities, such as sodium hypochlorite, polymers, diesel fuel, and waste oil, are required to maintain a Hazardous Materials Business Plan (HMBP). The HMBP includes a hazardous materials inventory, site map, and a Hazardous Material Release Response Plan to ensure proper notification, containment, and emergency response procedures in the event of a spill or release.

Submittals must be uploaded through the California Environmental Reporting System (CERS) and are subject to periodic review and on-site inspection by EHS. Updates to the HMBP are required annually or when significant changes to chemical use, storage volumes, or site operations occur. The WWTP must also comply with CUPA requirements related to hazardous waste generation, tank integrity, and employee training.

The Phase 1 project will introduce new chemicals to the site that will require regulation under the CUPA.

2.3.4 State Water Resources Control Board
The State Water Resources Control Board (SWRCB) is responsible for ensuring the proper allocation and quality of the state's water resources, and the Central Coast RWQCB is responsible for implementing the state's water resources locally. Stormwater flows and runoff from the site have not yet been determined for the Phase 1 project, but the permits discussed below will need to be considered during the preliminary and final design phases of the project.

2.3.4.1 Construction General Permit
The Construction General Permit is required for any construction activity that disturbs one acre or more of soil. Administered through the SWRCB and the Central Coast RWQCB and implemented locally under the City's Municipal Separate Storm Sewer Systems (MS4) program, the permit is intended to prevent sediment, debris, and other construction-related pollutants from entering local storm drains and receiving waters.

Permit compliance requires preparation of a Stormwater Pollution Prevention Plan (SWPPP), which identifies and implements Best Management Practices (BMPs) to address erosion control, sediment containment, materials storage, waste handling, and stormwater flow management. The permit must be obtained by submitting a Notice of Intent (NOI) through SWRCB's Stormwater Multiple Application and Report Tracking System (SMARTS) portal prior to the start of ground-disturbing activities. The SWPPP must be implemented throughout construction, with regular inspections, monitoring, and recordkeeping as required by the site's risk level classification.

2.3.4.2 MS4 Permit Post-Construction Requirements
City's MS4 Permit Post-Construction Requirements (PCRs) (R3-2013-0032) will need to be evaluated during the building plan submittal and review process. Based on the project scope, footprint, etc., VOLUME 10 / CHAPTER 2: PERMITTING PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-6
a determination will be made as to whether and or how the PCRs will be implemented. Evaluation will be initiated by the submittal of a Stormwater Control Plan (SWCP) with the Building Permit submittals.

The SWCP will document how the project will comply with the PCRs by documenting permanent site design features that retain, infiltrate, and treat stormwater runoff following project completion.

Post-construction BMPs should be finalized during the 90 to 100 percent design.

2.3.4.3 Industrial General Permit
The Santa Maria WWTP is subject to the Statewide Industrial General Permit (IGP) for stormwater discharges, issued by the SWRCB. The IGP applies to wastewater treatment facilities classified under Standard Industrial Classification Code 4952. Under this permit, a WWTP is required to implement a SWPPP specific to industrial operations, conduct quarterly visual observations, and perform annual stormwater sampling and reporting. All documentation, sampling results, and the annual report must be submitted through the SMARTS database. The WWTP must also implement BMPs to prevent industrial pollutants from being exposed to stormwater, including containment, housekeeping, and material handling protocols. The IGP is separate from the Construction General Permit and applies to ongoing operations.

Currently, the WWTP does not need coverage under the IGP because all stormwater is retained on site and there is no industrial discharge. For Phase 1 and Phase 2 of the upgrade project, the requirement for enrollment would need to be evaluated to determine if there are any changes that would require the new WWTP to enroll and be covered under the IGP. If determined that an IGP is required, the SWPPP and site map would need to be updated to reflect the new treatment processes and solids handling.

2.3.5 State of California Department of Industrial Relations Division of Occupational Safety and Health

2.3.5.1 Pressure Vessel Unit Permit to Operate
The WWTP operates certain equipment, such as boilers, propane storage, and may need a digester gas storage vessel in the future, each of which qualifies as a pressure vessel under the California Code of Regulations Title 8. These vessels are regulated by the California Division of Occupational Safety and Health (Cal/OSHA) Pressure Vessel Safety Program, which requires an annual PTO. Vessels must be registered with the state and inspected either by Cal/OSHA or an authorized third-party inspector.

Pressure vessels must comply with design, safety relief, and maintenance standards outlined in Title 8 Sections 450-560. A PTO must be displayed at or near the vessel and reviewed annually. As part of the expansion, any new pressure vessels installed will need to be permitted prior to operation and incorporated into the facility inspection and safety program.

2.3.6 Post Construction Additional Permits and Programs Following the completion and commissioning of the expanded WWTP, several regulatory programs and permits may require updates to reflect changes in treatment capacity, influent characteristics, and operational processes. These updates are critical to maintaining regulatory compliance and ensuring that new facilities are integrated into the plant's broader environmental management framework.

VOLUME 10 / CHAPTER 2: PERMITTING PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-7

2.3.7 Pretreatment Program
One key area requiring attention is the pretreatment program, which is regulated under 40 CFR Part 403 and administered by the Central Coast RWQCB. The City operates an approved pretreatment program to control the discharge of industrial and commercial pollutants that could interfere with treatment processes or pass through to the environment. With changes to plant flow rates, treatment capacity, and solids handling capabilities, a pretreatment program update study will be needed. The study will evaluate whether the plant's local limits remain protective of the upgraded treatment process and effluent quality.

If updates to the local limits are warranted, the City must submit revised calculations, public participation documentation, and a program modification package to the RWQCB for approval. Additionally, any structural or administrative changes to the pretreatment program must be documented and submitted.

2.3.8 SWRCB Environmental Laboratory Accreditation Program Another area requiring post-construction attention is the facility's participation in the Environmental Laboratory Accreditation Program (ELAP), managed by the California SWRCB. If laboratory facilities at the WWTP are expanded or upgraded, or if the analytical scope changes (new instrumentation, new permit-required parameters, etc.), the City must ensure the laboratory ELAP certification is updated accordingly.

Although the program does not directly expand or upgrade the laboratory facilities at the WWTP, there may be analytical scope changes that require an update to the ELAP certification. ELAP requires adherence to The NELAC Institute (TNI) 2016 Standard, including documented quality assurance procedures, staff competency records, and proficiency testing. Any significant changes to laboratory operations, methods, or equipment following construction must be reported to ELAP, and an amended application may be needed to maintain accreditation.

2.4 Permitting Plan Summary
Table 2.1 lists all permits that will be required as part of the two-phase expansion program and includes contact persons, probable requirements, and an anticipated schedule for the permit applications and receipt of permits. Additionally, Figure 2.1 illustrates the relative timing of the various permits listed in Table 2.1.

VOLUME 10 / CHAPTER 2: PERMITTING PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-8
Table 2.1 Permitting Plan for Santa Maria WWTP Expansion Program Permit Agency Contact Persons Probable Requirements Permit Application Schedule
Permit Receipt
Schedule
Permits Requiring Modification
WDR General
Permit (R3-2020-
0020)
Central Coast
RWQCB
Permit Engineer
(WDR Staff)
 Updated ROWD/NOI including phased flow
increases.
 Treatment diagrams.
 New disposal areas.
 CEQA documentation.
 Revised Monitoring and Reporting Program.
 Submit 6-12 months
prior to Phase 1
construction
completion.
 RWQCB review
~6-9 months.
 Amended NOA
issued when
construction is
complete, and the
Phase 1 project is
commissioned.

Sludge Management
Plan Update
Central Coast
RWQCB
Permit Engineer
(WDR Staff)
 Update description of biosolids treatment and
disposal.
 Compliance with CFR Part 503.
 Submit with WDR
amendment.
 Prior to digester
commissioning in
Phase 1.

New Permits Required for Phase 1 and Phase 2 of Program Building Permit City's Community
Development
Department Building
Division
Plan Check
Engineer
 Construction documents.
 Energy/mechanical calculations.
 Inspections.
 Fire/life safety compliance.
 Calculations.
 Equipment data.
 Submit 4-6 months
prior to construction.
 Review process
takes ~2-3 months.

Construction
General Permit
(SWPPP)
SWRCB
(via SMARTS)
Stormwater Permit
Engineer
 SWPPP.
 BMP design.
 NOI via SMARTS.
 Submit NOI 30 days
before Phase 1
ground disturbance.
 Coverage ~1 week
post-submittal.

VOLUME 10 / CHAPTER 2: PERMITTING PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-9
Permit Agency Contact Persons Probable Requirements Permit Application Schedule
Permit Receipt
Schedule
MS4 Permit PCRs City of Santa Maria
Community
Development
Department Building
Division
SWCP reviewed by
Public Works
Department
Principal Engineer in
Development as part
of Building Permit
plan check process.
 Site-specific BMP design.
 Hydrology report.
 Operations and maintenance plan.
 After submittal of
Stormwater Control
Plan with the
Building Permit
Submittals.
 Submit during
60-90% design
phase.
 Approved with
grading/building
plan check.

APCD ATC and
PTO Permit
SBCAPCD Engineering and
Permitting
Supervisor
 ATCs for digester modifications (Phase 1).
 ATC for new flare, boilers, and Cogen
(Phase 1).
 Emission estimates.
 BACT.
 CEQA review.
 Modeling.
 ATC Phase 1 due
prior to Phase 1
construction.
 ATC Phase 2 due
prior to Phase 2
construction.
 Receive PTO permit
~6-12 months after
submittal after install
and testing.

Hazardous Materials
Business Plan
Santa Barbara
County EHS CUPA
Hazardous Materials
Coordinator
 Hazardous materials inventory.
 Training plan for gas handling and new
flammable/combustible materials.
 Update site map.
 Emergency response plan.
 CERS upload.
 1-2 months before
chemical delivery.
 Approval in 1-2
weeks, requires
annual updates.

Pressure Vessel
PTO
Cal/OSHA Local Pressure
Vessel Inspector
 Registration of boilers.
 Plan review and inspection of new digesters,
gas piping, and boilers.
 The American Society of Mechanical
Engineers certification.
 Submit 2-3 months
prior to
commissioning
vessels.
 30-60 days
approval.

VOLUME 10 / CHAPTER 2: PERMITTING PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-10
Permit Agency Contact Persons Probable Requirements Permit Application Schedule
Permit Receipt
Schedule
IGP SWRCB (SMARTS) IGP Program Staff  SWPPP.
 Industrial Site Map.
 Visual/annual stormwater sampling.
 BMP implementation.
 Submit before new
processes become
active.
 Permit issued within
2-3 months.

Pretreatment
Program
Central Coast
RWQCB
Permit Engineer
(WDR)
 Local limits update study.
 Update sewer use ordinance.
 Local limits monitoring plan if influent
characteristics or side stream discharges
change.
 Sampling, analysis,
and development of
local limits may take
1-2 years to prepare
and submit after the
Phase 1 facilities
are online.
 Approval takes
3-6 months.

ELAP CA ELAP SWRCB ELAP Program
Manager
 Quality Assurance/Quality Control Manual.
 Staff certification.
 Modify laboratory scope or certification for
new testing methods or analytes.
 Submit 3 months
prior to new permit
compliance testing.
 Review takes
~2-3 months.

Notes:
~ - approximately; % - percent
VOLUME 10 / CHAPTER 2: PERMITTING PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-11
Figure 2.1 Permitting Schedule for Phase
VOLUME 10 / AIR QUALITY AND EMISSIONS ODOR CONTROL
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA

WASTEWATER TREATMENT PLANT MASTER PLAN

APPENDIX A EXISTING SANTA MARIA WWTP PERMITS
Central Coast

SRWQCB WDR
Permit
Central Coast Regional Water Quality Control Board
June 16, 2023 Sent Via Electronic Mail
Shad Springer, Director of Utilities
City of Santa Maria – Utilities Department
2065 E. Main Street
Santa Maria, CA 93454
Email: [email protected]
Dear Shad Springer:

CITY OF SANTA MARIA WASTEWATER TREATMENT PLANT, 601 BLACK ROAD, SANTA MARIA, CA 93458, SANTA BARBARA COUNTY:
• NOTICE OF APPLICABILITY FOR ENROLLMENT IN ORDER NO. R3-2020- 0020, GENERAL WASTE DISCHARGE REQUIREMENTS FOR DISCHARGES

FROM DOMESTIC WASTEWATER SYSTEMS WITH FLOWS GREATER
THAN 100,000 GALLONS PER DAY;
• TRANSMITTAL OF MONITORING AND REPORTING PROGRAM NO. R3- 2023-0032; AND
• TERMINATION OF INDIVIDUAL PERMIT, WASTE DISCHARGE
REQUIREMENTS ORDER NO. R3-2010-0001 FOR THE CITY OF SANTA MARIA WASTEWATER FACILITY, SANTA BARBARA COUNTY.

The Central Coast Regional Water Quality Control Board (Central Coast Water Board) reviewed the August 5, 2022, notice of intent and available documents associated with City of Santa Maria’s domestic wastewater treatment facility (Wastewater System) located at 601 Black Road in Santa Maria, California. The Wastewater System, owned by the City of Santa Maria is currently regulated pursuant to Waste Discharge Requirements Order No. R3-2010-0001 for the City of Santa Maria Wastewater Facility, Santa Barbara County (Order No. R3-2010-0001).

On September 25, 2020, the Central Coast Water Board adopted General Waste Discharge Requirements Order No. R3-2020-0020 for Discharges from Domestic Wastewater Systems with Flows Greater than 100,000 Gallons per Day (General Permit).

This letter serves as a notice of applicability for enrollment in the General Permit. This letter includes: wastewater system operation summary, specific requirements, and City of Santa Maria - 2 - June 16, 2023
City of Santa Maria Wastewater Treatment Plant
limitations (Attachment 1); figures (Attachment 2); and City of Santa Maria’s monitoring and reporting program requirements (Attachment 3).

This letter also serves as a notice of termination of City of Santa Maria’s coverage in existing individual permit, Order No. R3-2010-0001.

City of Santa Maria must comply with the following:

1. General Permit – City of Santa Maria must comply with all conditions and requirements of the General Permit. As described in the General Permit, ongoing operation, maintenance, monitoring, and reporting are required. A copy of the General Permit can be found electronically at the following link:
https://www.waterboards.ca.gov/centralcoast/board_decisions/adopted_orders/2 020/r32020_0020.pdf

2. Monitoring and Reporting Program – City of Santa Maria must comply with the requirements of the monitoring and reporting program enclosed with this letter (monitoring and reporting program no. R3-2023-0032, Attachment 3). City of Santa Maria must start implementing the monitoring on October 1, 2023. The first quarterly monitoring report is due February 1, 2024 and the first annual report is due March 1, 2024. City of Santa Maria is also required to submit an annual pretreatment program report1 due on March 1st and the annual volumetric reporting requirements2 established by the State Water Resources Control Board (State Water Board), due April 30th. Annual reports must be submitted to the GeoTracker database.

Quarterly monitoring reports and annual reports must be provided electronically in searchable PDF with the Central Coast Water Board’s current transmittal sheet found at the link below as the cover page. The transmittal sheet must be signed. https://www.waterboards.ca.gov/centralcoast/water_issues/programs/wastewater _permitting/docs/transmittal_sheet.pdf
All annual reports must be formatted and completed as specified in the annual report template found at the following link:
https://www.waterboards.ca.gov/centralcoast/board_decisions/adopted_orders/2 020/wdr_annual_report_format.pdf
City of Santa Maria must submit all reports/documents and laboratory data (using the transmittal sheet as the cover page) to the publicly accessible State Water 1 California Code of Regulations title 23 section 2233 View Document - California Code of Regulations (westlaw.com)
2 See: Volumetric Annual Reporting | California State Water Resources Control Board City of Santa Maria - 3 - June 16, 2023
City of Santa Maria Wastewater Treatment Plant
Board’s GeoTracker3,4 database with applicable Electronic Submittal of Information (ESI) requirements under the Wastewater System – specific global identification number WDR100029526 over the internet at:
https://geotracker.waterboards.ca.gov/esi/login.asp
The attached monitoring and reporting program outlines the GeoTracker electronic reporting requirements. The Central Coast Water Board may request submittal of some documents on paper, particularly drawings or maps that require a large size to be readable, or in other electronic formats where evaluation of data is required.

3. Fees – City of Santa Maria paid an annual fee of $123,934.00 on January 24, 2023 for coverage in existing individual permit, Order No. R3-2010-0001. This payment covers City of Santa Maria‘s enrollment in the General Permit for the 2022-2023 fiscal year.

City of Santa Maria must pay an annual fee to maintain coverage in the General Permit. Annual fees are determined by the State Water Board’s fee program and cover the state fiscal year of July 1 through June 30. The Central Coast Water Board has lowered your assigned threat and complexity rating to 2A which will result in a reduced annual fee (currently $41,063) starting with the 2023-2024 fiscal year. A copy of the current state fee schedule is available electronically at the following link:
https://www.waterboards.ca.gov/resources/fees/water_quality/#wdr

4. Notification – The Central Coast Water Board will be notified of City of Santa Maria’s enrollment at a regularly scheduled public meeting on August 24-25, 2023. Details about that meeting are available on our website at:
https://www.waterboards.ca.gov/centralcoast/board_info/agendas/

5. Future Discharge Modifications – Pursuant to California Water Code section 13260, City of Santa Maria must inform the Central Coast Water Board at least 120 days prior to modifying your discharge. If there are any significant changes in either treatment or disposal methodologies, or the volume or character of the treated wastewater, City of Santa Maria must notify the Central Coast Water Board immediately of such changes.
3 Information for first-time GeoTracker users is available at:
https://www.waterboards.ca.gov/ust/electronic_submittal/ 4 Additional information available at: http://geotracker.waterboards.ca.gov/ City of Santa Maria - 4 - June 16, 2023
City of Santa Maria Wastewater Treatment Plant
Attachment 1 contains the Central Coast Water Board’s understanding of the Wastewater System located at 601 Black Road, Santa Maria, CA 93458. Please review Attachment 1 to determine if the description is representative of your current system. Pursuant to California Water Code section 13267, City of Santa Maria must notify the Central Coast Water Board if this information is out of date or incorrect. You are required to provide staff with your updated information within 30 days of issuance of this letter.

6. Responsible Party – City of Santa Maria is responsible for the management and disposal of the domestic wastewater in compliance with the conditions of the General Permit. Any noncompliance with this General Permit constitutes a violation of the California Water Code, and subjects City of Santa Maria to enforcement action, and termination of enrollment under this General Permit.

7. Change in Ownership - In the event of any change in control or ownership of the property, City of Santa Maria must notify the succeeding owner or operator of the existence of this General Permit by letter, a copy of which shall be immediately forwarded to the Central Coast Water Board so that the new owner or operator can be enrolled in the General Permit and City of Santa Maria’s enrollment in the General Permit can be terminated.

8. Certified Operator – City of Santa Maria is required to comply with the operator certification requirements5 administered by the State Water Board’s Office of Operator Certification, which currently requires a Grade IV certified operator onsite to maintain and operate the Wastewater System. The City of Santa Maria must:
a. Keep a current Wastewater Treatment Plant Classification Form on file with the Office of Operator Certification and update the form when modifications to the Wastewater System treatment processes occur. b. Provide the Office of Operator Certification with a Chief Plant Operator Acknowledgement Form and update this information within 30 days of a change of Chief Plant Operator.
c. If a contractor operator is used, the contract operator must register with the Office of Operator Certification and obtain a contract operator certificate for the Wastewater System.

Forms are available at the following link:
https://www.waterboards.ca.gov/water_issues/programs/operator_certification/for m.html
5 Title 23 Division 3. Chapter 26 Wastewater Treatment Plant Classification, Operator Certification and Contract Operator Registration.
https://www.waterboards.ca.gov/water_issues/programs/operator_certification/docs/ocr_clean.pdf City of Santa Maria - 5 - June 16, 2023
City of Santa Maria Wastewater Treatment Plant

9. Termination of Permit – The existing individual permit, Order No. R3-2010-0001 is terminated, except for enforcement purposes.6 City of Santa Maria is responsible for compliance with Order No. R3-2010-0001 prior to the date of this letter.

10.Compliance Plan – As required in the attached monitoring and reporting program, City of Santa Maria must, by June 16, 2024, prepare and submit for Central Coast Water Board review and approval a time schedule compliance plan.

If you have any questions, please contact Cecile Blancarte at (805) 542-4782 or by email at [email protected] or Jennifer Epp at (805) 594-6181 or by email at [email protected].

Sincerely,
for Matthew T. Keeling
Executive Officer
Attachments:

Attachment 1: Wastewater System Operation Summary, Specific Requirements, and Limitations
Attachment 2: Figures
Attachment 3: Monitoring and Reporting Program Order No. R3-2023-0032

cc:

Alexandra Griffith, City of Santa Maria, [email protected] Russ Newman, City of Santa Maria, [email protected] Office of Operator Certification, [email protected] Jennifer Epp, Central Coast Water Board, [email protected] Jesse Woodard, Central Coast Water Board, [email protected] Cecile Blancarte, Central Coast Water Board, [email protected] WDR Program, GeoTracker [email protected]
6 The General Permit states “… where a Wastewater System discharge is currently regulated by an individual permit, that permit is terminated upon the enrollment of the Wastewater System into this General Permit.”
City of Santa Maria - 6 - June 16, 2023
City of Santa Maria Wastewater Treatment Plant
ECM/CIWQS = CW-255678
GeoTracker No. = GT- WDR100029526
Rev 12/21/2022
ECM Subject Name = City of Santa Maria Wastewater Treatment Plant NOA for R3- 2020-0020
\\ca.epa.local\rb\rb3\shared\wdr\wdr facilities\santa barbara co\santa maria wwtp\order 2020- 0020\final\santa maria r3-2020-0020 noa_final.docx
ATTACHMENT 1

WASTEWATER SYSTEM OPERATION SUMMARY, SPECIFIC REQUIREMENTS,

AND LIMITATIONS

1. OWNERSHIP AND WASTEWATER SYSTEM INFORMATION
Ownership and wastewater system information submitted by City of Santa Maria to the Central Coast Water Board is shown in Table 1.

Table 1. Ownership and Wastewater System Information
Name City of Santa Maria Wastewater
Treatment Plant
Physical Address 601 Black Road Santa Maria, CA 93458
Lattitude 34°56'54.93"N
Longitude 120°29'49.59"W
Mailing Address 2065 E. Main Street, Santa Maria, CA
93454
Owner City of Santa Maria
Operator
Russ P. Newman
phone: (805) 925-0951 x721
e-mail: [email protected]
Legally Responsible Official
Shad Springer
phone: (805) 925-0951 x7211
e-mail: [email protected]
Raw Wastewater
Characteristics
Sewer Connections: 22,020
Population Served: 107,407
Domestic (%): 91%
Industrial (%): 9%
Permitted Design Flow,
Average Monthly (Million
gallons per day, mgd)

8.0 Baseline Flow (average
annual flow) in mgd

7.2 Threat to Water Quality 2
Complexity B
For Internal Use
Fee Code 58
Primary Place Type Wastewater Treatment Facility
Facility Type Municipal/Domestic
Facility Waste Type Domestic Wastewater
Regulatory measure Type Enrollee - WDR
Reclamation Included No
EPA Approved Pretreatment
Program
Yes
City of Santa Maria - 2 - June 16, 2023
City of Santa Maria Wastewater Treatment Plant

2. WASTEWATER SYSTEM OPERATION SUMMARY
The City of Santa Maria wastewater treatment facility (Wastewater System) is a Class IV wastewater system. City of Santa Maria must staff a Grade IV chief plant operator for proper operation of the Wastewater System. The current chief plant operator is Russ P.

Newman, Grade IV, Operator No. 29543, Certificate No. 28863 (expires 1/18/2026).

The Wastewater System is capable of treating 13.5 million gallons per day (mgd) to a secondary treatment level but is limited in disposal capacity to 8.0 mgd. The Wastewater System consists of the treatment technologies and treatment capabilities shown in Table 2.

Table 2. Treatment Technology and Capacity
Headworks/Preliminary
Treatment
The headworks consists of a Parshall flume flow meter,
three automatic bar screens followed by two aerated grit chambers.

Headworks capacity (mgd): 13.5
Primary Treatment
Clarifiers: Primary treatment consists of two primary
clarifiers that operate in parallel. The volume of each clarifying tank is 1.32 million gallons.

Primary treatment capacity (mgd): 27.92
Secondary Treatment
Trickling Filters: Secondary treatment is performed using two primary and two secondary aerobic trickling filters.

Each of the primary trickling filters has a volume of
543,000 gallons. Each of the secondary trickling filters has a volume of 170,000 gallons.

Secondary treatment capacity (mgd): 17.7
Tertiary Treatment Not Applicable
Tertiary treatment capacity (gpd): 0
Disinfection Not Applicable
Disinfection Capacity (gpd): 0
Wastewater Disposal
Method
Percolation Ponds, 123 acres
Disposal capacity (mgd): 8.0
Biosolids/Sludge
Production and
Handling
Gravity Thickeners (2), Anaerobic Digestors (4), and
Sludge Drying Beds, Offsite Composting, and Landfilling Annual production of biosolids: 1,811 tons
The final destination of biosolids produced is hauled off to Engel and Gray Composting, Inc. located at 468-594 Ray
Road, Santa Maria, California, and the City of Santa Maria Landfill, 2065 E. Main Street, Santa Maria, California
Non-Potable Recycled
Water
Non-potable recycled
water produced onsite: Not Applicable
Recycled water usage
areas: Not Applicable
City of Santa Maria - 3 - June 16, 2023
City of Santa Maria Wastewater Treatment Plant
Enrolled in WQ 2016-
0068-DDW: Not Applicable
Recycled water production
volume (gpd): Not Applicable
A summary of historic and recent average effluent concentrations is included in Table 3, which were reported in City of Santa Maria quarterly monitoring reports. The Central Coast Water Board used reported effluent water quality data to establish the effluent and groundwater limitations in section 3.

Table 3. Effluent Water Quality for Select Constituents Constituents Unit [1][2] Historical
Average[3]
Annual Average
for 2022[4]
Carbonaceous Biochemical
Oxygen Demand, 5-Day[5] mg/L 43 45
Total Suspended Solids mg/L 39 37
Total Dissolved Solids mg/L 844 1,055
Chloride mg/L 156 143
Sodium mg/L 145 140
Sulfate mg/L 196 320
Boron mg/L 0.35 0.41
Total Nitrogen mg/L 43 42
Settleable Solids ml/L[4] <0.1 <0.1
pH Standard
Units 8 7.8
[1] mg/L denotes milligrams per liter.
[2] ml/L denotes milliliters per liter.
[3] Based on water quality data reported by City of Santa Maria in their 2018 to 2022 monitoring reports. [4] Based on water quality data reported by City of Santa Maria in the 2022 Annual Monitoring Report. [5] The City of Santa Maria has been reporting carbonaceous biochemical oxygen demand (CBOD) instead of biochemical oxygen demand (BOD). Monitoring and reporting program no. R3-2023-0032 requires the City of Santa Maria to report BOD.

3. WASTEWATER SYSTEM SPECIFIC REQUIREMENTS AND LIMITATIONS City of Santa Maria must operate the Wastewater System in accordance with the General Permit and this notice of applicability. City of Santa Maria must comply with the wastewater specific limitations specified in Table 4 through Table 8.

Flow limitations are shown in Table 4. Interim effluent limitations shown in Table 5 apply until June 16, 2025. After June 16, 2025, effluent limitations shown in Table 6 and Table 7 apply.

A. Flow Limitations:

Table 4. Flow Limitations
Flow Units Limit Point of
Compliance
Maximum Daily Flow to Disposal Ponds mgd 8.0 Influent IS-1 City of Santa Maria - 4 - June 16, 2023
City of Santa Maria Wastewater Treatment Plant
B. Effluent Limitations:

Based on reported water quality data, effluent water quality for Carbonaceous Biochemical Oxygen Demand and Total Suspended Solids (TSS) (see Table 3) exceed the General Permit effluent limits for a trickling filter treatment system. Therefore, pursuant to the General Permit, City of Santa Maria can comply with their individual permit No. R3-2010-0001 5-day Biochemical Oxygen Demand (BOD5) and TSS limits for two years. After June 16, 2025, trickling filter effluent limitations shown in Table 6 apply.

Table 5. Interim Effluent Limitations: Trickling Filters (Until June 16, 2025) Constituent Units 30-Day
Average
Daily
Maximum
Biochemical Oxygen Demand, 5-Day mg/L 60 100
Total Suspended Solids mg/L 60 100
Settleable Solids mL/L 0.1 0.4
Total Dissolved Solids1 mg/L 1,000 Not Applicable
Sodium1 mg/L 180 Not Applicable
Chloride1 mg/L 180 Not Applicable
pH Standard
Units
Between 6.5
and 8.4
Between 6.5
and 8.4
[1] Compliance shall be based on a three-year running mean.

Table 6. Effluent Limitations[1] (After June 16, 2025)
Constituent Units 30-Day
Average
7-Day
Average
Sample
Maximum
Biochemical Oxygen
Demand, 5-Day mg/L 30 45 Not Applicable
Total Suspended Solids mg/L 30 45 Not Applicable
Settleable Solids mL/L 0.1 0.3 0.5
pH Standard
Units
Between 6.5
and 8.4
Not
Applicable Not Applicable
[1] The Central Coast Water Board understands that the City of Santa Maria will be upgrading the Wastewater System to comply with the new effluent limitations. Pursuant to General Permit Tables 3 through 5, the values in this table will vary depending on the treatment technology chosen. By June 16, 2024, the City of Santa Maria must report to the Central Coast Water Board the treatment technology chosen for the upgrades such that this notice of applicability can be updated as needed.

Table 7. Effluent Limitations (After June 16, 2025)
Based on - Upper Guadalupe Groundwater Basin
Constituents Units 25-Month Rolling Median[1]
Total Dissolved Solids mg/L 1,000
Chloride mg/L 165
Sodium mg/L 105
Sulfate mg/L 500
Boron mg/L 0.5
City of Santa Maria - 5 - June 16, 2023
City of Santa Maria Wastewater Treatment Plant
Constituents Units 25-Month Rolling Median[1]
Total Nitrogen mg/L 10
[1] Rolling Median is the median from all data collected over the most recent 25 months.

C. Groundwater Limitations:

Based on review of historical effluent water quality (see Table 3), City of Santa Maria is currently unable to consistently comply with the General Permit effluent limitations for total nitrogen. The Central Coast Water Board understands that the City of Santa Maria will be designing upgrades to the Wastewater System to comply with the General Permit and will be providing a time schedule compliance plan as described in monitoring and reporting program no. R3-2023-0032. In the time schedule compliance plan, the City of Santa Maria must identify if it chooses General Permit section V.A.2 Option 1 or Option 2 for each constituent. Option 1 is to comply with the effluent limits in Table 7.

Option 2 is to implement a groundwater monitoring program to demonstrate that the discharge does not cause underlying groundwater to exceed the water quality objectives set forth in the Basin Plan including the limitations listed in Table 8.

Table 8. Groundwater Limitations
for Designated Groundwater Basin – Upper Guadalupe Groundwater Basin Constituents Units 25-Month Rolling Median
Total Dissolved Solids mg/L 1,000
Chloride mg/L 165
Sodium mg/L 230
Sulfate mg/L 500
Boron mg/L 0.5
Total Nitrogen mg/L 1.4
City of Santa Maria - 1 - June 16, 2023
City of Santa Maria Wastewater Treatment Plant
ATTACHMENT 2

FIGURES
Figure 1 - Vicinity Map
City of Santa Maria
Wastewater
Treatment Plant
City of Santa Maria - 2 - June 16, 2023
City of Santa Maria Wastewater Treatment Plant
Figure 2- City of Santa Maria Wastewater Treatment Plant Site Map City of Santa Maria - 3 - June 16, 2023
City of Santa Maria Wastewater Treatment Plant
Figure 3 - Process Flow Schematic

CENTRAL COAST REGIONAL WATER QUALITY CONTROL BOARD
MONITORING AND REPORTING PROGRAM NO. R3-2023-0032
June 16, 2023
MODIFICATION OF MONITORING AND REPORTING PROGRAM NO. R3-2020-0020 FOR

CITY OF SANTA MARIA WASTEWATER TREATMENT PLANT

SANTA MARIA, SANTA BARBARA COUNTY
This Monitoring and Reporting Program applies to the monitoring and reporting requirements for the City of Santa Maria Wastewater Treatment Plant (Wastewater System) enrolled in General Waste Discharge Requirements Order No. R3-2020-0020 for Discharges from Domestic Wastewater Systems with Flows Greater than 100,000 Gallons per Day (General Permit).

The City of Santa Maria owns and operates the Wastewater System that is subject to the General Permit and notice of applicability. The City of Santa Maria must not implement any changes to this monitoring and reporting program unless and until a revised monitoring and reporting program is issued by the Central Coast Regional Water Quality Control Board (Central Coast Water Board).

The State Water Resources Control Board (State Water Board) and Regional Water Quality Control Boards are transitioning to the use of the publicly accessible State Water Board’s GeoTracker database for the tracking of environmental and regulatory data for sites that operate under waste discharge requirements. The monitoring and reporting program directs the City of Santa Maria to submit reports (both technical and monitoring reports) and analytical data electronically to the State Water Board’s GeoTracker database (see monitoring and reporting program section VI.C).

I. SAMPLING AND ANALYSIS
The City of Santa Maria must collect representative samples in accordance with the most recently approved sampling and analysis plan contained in the Operations and Maintenance Manual and validate analytical results prior to submittal to the Central Coast Water Board. All samples (e.g., wastewater, groundwater, soil, sludge) must be representative of the volume and nature of the discharge or matrix of materials sampled.

All samples must be collected by a qualified person, trained in proper procedures for collecting the samples. The name of the sampler, sample type (grab or composite), time, date, location, bottle/container type, and any preservative used for each sample must be recorded on the sample chain of custody form. The chain of custody form must also contain all custody information including date, time, and to whom samples were relinquished. If composite samples are collected, the basis for sampling (time or flow weighted) must be included in the sampling and analysis plan contained in the MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
2 Operations and Maintenance Manual for Central Coast Water Board review and approval.

A. Sampling Schedule – Unless otherwise specified below, sampling must be performed in accordance with Table 1.

Table 1. Sampling Schedule
Monitoring Period Sample Collection Time
Quarterly January, April, July, and October
Semiannual April and October
Annual October
Field test instruments (such as those used to evaluate pH, dissolved oxygen, and electrical conductivity) may be used if they are used by a State Water Board Environmental Laboratory Accreditation Program accredited laboratory, or:

1. The user is trained in proper use and maintenance of the instruments;

2. The instruments are field calibrated prior to monitoring events at the frequency recommended by the manufacturer;

3. Instruments are serviced and/or calibrated by the manufacturer at the recommended frequency; and

4. Field calibration reports are maintained and available for at least three years.

B. Monitoring Location Descriptions – All samples including influent samples (IS), effluent samples (ES), and groundwater monitoring wells (MW) must be collected at the locations described in Table 2. These locations must be consistent with the Central Coast Water Board approved sampling and analysis plan. The City of Santa Maria must upload the GeoTracker field point information for each sampling location in the GeoTracker database once, prior to uploading laboratory data (see Table 10).

Table 2. Sample Identification Details
GeoTracker Field
Point Class
GeoTracker Field Point
Name (Sample ID)
GeoTracker Field Point
Description [1][2]
Influent Sample IS-1 Raw wastewater sample collected
at the headworks
Effluent Sample ES-1
Treated wastewater sample
collected downstream of the
secondary clarifiers
MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
3 GeoTracker Field
Point Class
GeoTracker Field Point
Name (Sample ID)
GeoTracker Field Point
Description [1][2]
Effluent Sample
ES-A, ES-1a, ES-2 through
ES-8, ES-11 through ES-15,
and ES-DKC
Treated wastewater sample
collected from the percolation
ponds
Monitoring Well MW-5H
Background Groundwater
Monitoring Well
Top of casing elevation unknown
Perforations 160 to 602 ft bgs
Monitoring Well MW-UMW1
Groundwater Monitoring Well
Top of Casing Elevation 175.6 ft
amsl
Screened elevations unknown
Monitoring Well MW-DMW1
Groundwater Monitoring Well
Top of Casing Elevation 158.16 ft
amsl Screened 87 to 135 ft bgs
Monitoring Well MW-DMW2
Groundwater Monitoring Well
Top of Casing Elevation 157.2 ft
amsl
Screened 82 to 155 ft bgs
Water Supply
Well
WSW-1[3] Representative sample from
potable well serving the city
[1] ft amsl denotes feet above mean sea level.
[2] ft bgs denotes feet below grade surface.
[3] Water supply sample data should be included in the annual report but does not need to be uploaded to GeoTracker if the Central Coast Water Board approves submittal of a Well Identification Number pursuant to the Water Supply Monitoring section below.

II. WATER SUPPLY MONITORING
Representative samples of the City of Santa Maria’s raw water supply (sampled before use or treatment) must be collected and analyzed, at a minimum, for constituents specified in Table 3.

In lieu of the required water supply sampling, the City of Santa Maria may request Central Coast Water Board approval to submit a Well Identification Number and the reporting year’s consumer confidence report (annual water quality report or drinking water quality report), as required by the State Water Board Division of Drinking Water and/or county, provided, at a minimum, all of the required constituents are sampled at the frequency specified in Table 3. The City of Santa Maria must report the results of any constituent monitored more frequently than is required by the monitoring program shown in Table 3. The City of Santa Maria must also report detectable concentrations (above the reporting limit) for any other constituent that has a published maximum contaminant level (MCL).

MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
4 The City of Santa Maria must evaluate and provide a tabular summary of the water supply data with the annual monitoring report.

Table 3. Water Supply Monitoring
Constituent Units[1] Sample Type Sampling Frequency
Nitrate (as N) mg/L Grab Annually
Total Dissolved Solids mg/L Grab Annually
Chloride mg/L Grab Annually
Sodium mg/L Grab Annually
Sulfate mg/L Grab Annually
Boron mg/L Grab Annually
Carbonate mg/L Grab Annually
Bicarbonate mg/L Grab Annually
Calcium mg/L Grab Annually
Potassium mg/L Grab Annually
Magnesium mg/L Grab Annually
[1] mg/L denotes milligrams per liter.

III. INFLUENT AND EFFLUENT MONITORING
A. Influent Flow Monitoring – The City of Santa Maria must monitor and report flow in million gallons per day, as described in Table 4, with each monitoring report. See monitoring and reporting program section VI.A.4 for supplemental volumetric annual reporting requirements established by the State Water Board.

Table 4. Influent Flow Monitoring
Parameter Sample Type Sampling Frequency Sample Location Daily Flow Metered Daily IS-1
Maximum
Daily Flow Metered Monthly IS-1
Mean Daily
Flow Calculated Monthly IS-1
Percent of
Permitted
Flow [1]
Calculated Quarterly IS-1
MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
5 [1] The General Permit notice of applicability specifies the Wastewater System’s maximum permitted flow. In the monitoring reports, the City of Santa Maria must evaluate and provide a comparison of monitored flow to the permitted flow.

B. Wastewater System Monitoring – Representative samples of The City of Santa Maria’s influent (raw wastewater) into the Wastewater System and effluent (treated wastewater) discharged to percolation ponds must be collected and analyzed in accordance with the treatment technology-based monitoring requirements (including sample type and frequency) summarized in the tables below. See Figure 1 for the location of samples and GeoTracker field points.

Figure 1. Process Flow Diagram and Sample Locations Referenced in Table 2 IS-1
ES-1
MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
6 Figure 2. Percolation Pond and Groundwater Monitoring Well Sample Locations Referenced in Table 2
ES-2
ES-3
ES-4
ES-1a
ES-5
ES-6
ES-7
ES-8
ES-DKC
ES-12
ES-11
ES-14
ES-13
ES-15
MW-DMW1
MW-DMW2
MW-UMW1
ES-1
IS-1
MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
7 Figure 3. Water Supply and Groundwater Monitoring Well Sample Locations Referenced in Table 2

1. Pond System Monitoring
i. Required Pond Monitoring – All wastewater treatment and treated wastewater storage/disposal ponds (lined and unlined) must be monitored as specified in Table 5. Sampling for dissolved oxygen must be a grab sample taken from 1 foot below pond surface1.

Observations do not need to be reported in the monitoring reports unless a violation, significant change, or treatment issue is observed. Photos of the pond(s) verifying the observations must be collected annually and included in the annual report, with the date and location of the photo clearly marked. Observations must be noted in a logbook or database and made available to the Central Coast Water Board upon request. Any problems must be promptly corrected and recorded.
1 Pond dissolved oxygen sample collection may be omitted if collection is deemed infeasible or unsafe to perform by the wastewater treatment plant chief plant operator.

MW-5H
MW-DMW2
MW-DMW1
MW-UMW1 MW-5H
MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
8 Table 5. Wastewater Treatment/Storage/Disposal Pond Monitoring Parameter/
Constituent Units Sample Type Sampling/MonitoringFrequency Freeboard 0.1 feet Measured Weekly
Dissolved Oxygen
(in pond)[4] mg/L Grab Monthly
Sludge Depth[1] 0.1 feet Measured Annually
Color Not
applicable Observation Monthly
Vegetation in and
surrounding ponds
Not
Applicable Observation Monthly
Berm condition Not
Applicable Observation Monthly
Precipitation inches/day
and date Measured [2] Each precipitation event [3]
[1] Sludge depth will not be required at disposal ponds if the disposal pond was dried and scarified within the reporting year. The annual report must provide dates of when the disposal ponds have been dried and scarified.
[2] The City of Santa Maria may use a rain gauge or use a National Oceanic and Atmospheric Administration, United States Geological Survey, or California Irrigation Management Information System weather station, such as http://scacis.rcc-acis.org/. [3] A precipitation event is one producing precipitation of ½ inch or more. [4] Pond sample collection may be omitted if collection is deemed infeasible or unsafe to perform by the wastewater treatment plant chief plant operator.

2. Trickling Filter System Monitoring
i. Influent and Effluent Monitoring – At a minimum, influent and effluent constituent monitoring for the trickling filter system must be monitored as specified in Table 6.

Table 6. Influent and Effluent Monitoring for Trickling Filter Systems

INFLUENT
(IS-1)

INFLUENT
(IS-1)

EFFLUENT
(ES-1)

EFFLUENT
(ES-1)
Parameter/
Constituent Units Sample Type
Sampling
Frequency
Sample
Type
Sampling
Frequency
pH units Grab Weekly Grab Weekly
Biochemical
Oxygen Demand,
5-Day
mg/L 24-hour
composite Quarterly 24-hr composite Monthly
Total Suspended
Solids mg/L 24-hour composite Quarterly 24-hr composite Monthly Settleable Solids ml/L Not
Required Not Required Grab Weekly
MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
9 INFLUENT
(IS-1)

INFLUENT
(IS-1)

EFFLUENT
(ES-1)

EFFLUENT
(ES-1)
Parameter/
Constituent Units Sample Type
Sampling
Frequency
Sample
Type
Sampling
Frequency
Total Nitrogen[2] mg/L Calculated Quarterly Calculated Monthly Nitrate (as N) +
Nitrite (as N) mg/L 24-hour composite Quarterly Grab Monthly Total Kjeldahl
Nitrogen (as N) mg/L 24-hour composite Quarterly Grab Monthly Ammonia (as N) mg/L 24-hour
composite Quarterly Grab Monthly
Total Dissolved
Solids mg/L 24-hour composite Quarterly Grab Monthly
Chloride mg/L 24-hour
composite Quarterly Grab Monthly
Sodium mg/L 24-hour
composite Quarterly Grab Monthly
Sulfate mg/L 24-hour
composite Quarterly Grab Monthly
Boron mg/L Not
Required Not Required Grab Monthly
Carbonate mg/L Not
Required Not Required Grab Semiannually
Bicarbonate mg/L Not
Required Not Required Grab Semiannually
Calcium mg/L Not
Required Not Required Grab Semiannually
Potassium mg/L Not
Required Not Required Grab Semiannually
Magnesium mg/L Not
Required Not Required Grab Semiannually
[1] Total nitrogen is the sum of total inorganic nitrogen (nitrate + nitrite + ammonium + ammonia) and organic nitrogen.

IV. SLUDGE/BIOSOLIDS DISPOSAL MONITORING
The City of Santa Maria must report the handling and disposal of all sludge/biosolids generated at the Wastewater System. Records must include the date removed from the Wastewater System, name/contact information for the hauling company, the type and volume of waste transported, the disposal facility name and address, and copies of analytical data required by the entity accepting the waste. These records must be submitted as part of the annual monitoring report.

The City of Santa Maria must also monitor sludge/biosolids consistent with a Central Coast Water Board approved sludge management plan and in accordance with the MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
10 requirements specified by the receiving party, including a regulated landfill and/or regulated composting facility.

If sludge/biosolids are not removed during the year, the City of Santa Maria must explain the absence of this monitoring in the annual report.

V. GROUNDWATER MONITORING
A. General Permit section V.A.2 provides two choices for compliance, effluent limitations, or groundwater monitoring.

In the time schedule compliance plan, the City of Santa Maria must identify if it chooses General Permit section V.A.2 Option 1 or Option 2 for each constituent.

Option 1 is to comply with the effluent limits (refer to notice of applicability Table 7).

Option 2 is to implement a groundwater monitoring program to demonstrate that the discharge does not cause underlying groundwater to exceed the water quality objectives set forth in the Basin Plan (refer to notice of applicability Table 8).

Existing upgradient and downgradient groundwater monitoring wells are located within the percolated effluent mound at the Wastewater System. The current monitoring well network is not adequate for the assessment of upgradient background water quality and/or downgradient water quality trend for the City of Santa Maria Wastewater System (Fugro 2007)2.

By June 16, 2024, (with the time schedule compliance plan) the City of Santa Maria must notify the Central Coast Water Board of the city’s choice for compliance for each constituent pursuant to General Permit section V.A.2 Option 1 or Option 2 (complying with an effluent limit or demonstrating compliance through a groundwater monitoring program).

If the City of Santa Maria chooses Option 2 for any constituent, by October 16, 2024, the City of Santa Maria must:

1. Submit a groundwater monitoring workplan and preliminary hydrogeologic conceptual site model for Central Coast Water Board approval. At a minimum, the workplan must propose the installation of three shallow groundwater monitoring wells to establish groundwater gradient, groundwater flow velocity and direction, and evaluate downgradient groundwater quality influenced by the wastewater disposal. The number and location of the proposed groundwater monitoring well network must be on a scale sufficient to determine potential impacts and be sufficiently representative of groundwater conditions upgradient and downgradient of the permitted disposal/dispersal area. The groundwater 2 Hydrogeologic and Water Quality Review of Groundwater Conditions for the Wastewater Treatment Plant, Santa Maria, California. Fugro West, Inc. September 2007 MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
11 monitoring wells should not be installed prior to Central Coast Water Board approval of the groundwater monitoring workplan and preliminary hydrogeologic conceptual site model.

The groundwater monitoring wells must be installed within first encountered groundwater and in accordance with California Department of Water Resources Bulletin No. 74-81 and Supplement No. 74-90, California Water Code sections 13710 through 13755, and any local permitting requirements. The locations and top-of-casing elevations for the newly installed monitoring wells must be surveyed by a licensed land surveyor. The City of Santa Maria must install3 the Central Coast Water Board approved groundwater monitoring well network within 90 days of receiving Central Coast Water Board approval.

2. Once installed, all monitoring wells designated as part of the monitoring well network must be, at a minimum, sampled and analyzed as specified in Table 7 and the Central Coast Water Board approved sampling and analysis plan (see section VI.A.2.i of the General Permit).

Prior to sampling, depth to groundwater must be measured and groundwater elevations4 must be calculated. The monitoring wells must be purged of at least three well volumes and until measurements of the following parameters have stabilized (i.e., are reproducible within 10 percent): pH, temperature, dissolved oxygen, electrical conductivity, and turbidity. No-purge, low-flow, or other sampling techniques are acceptable only if they are approved in advance by the Central Coast Water Board and described in an approved sampling and analysis plan. Once the groundwater level in each of the wells has recovered sufficiently to ensure the collection of representative groundwater samples, a qualified individual (e.g., consultant, technician) trained in using proper sampling methods must recover samples using approved USEPA methods. Laboratories analyzing groundwater samples must be accredited by the State Water Board Environmental Laboratory Accreditation Program, in accordance with California Water Code section 13176, and must include quality assurance/quality control data with their reports.

The City of Santa Maria must provide monitoring well field sheets and report monitoring data, as described in Table 7, with each monitoring report.

3. Groundwater monitoring must include and must be consistent with Table 7 if Option 2 is chosen. Some constituents in Table 7 may be removed by the Central 3 Well installation must be supervised by a California licensed Civil Engineer or Professional Geologist. 4 The locations and top-of-casing elevations for the existing groundwater monitoring wells must be surveyed by a licensed land surveyor if not already completed at the time of installation.

MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
12 Coast Water Board if compliance for that constituent is chosen by the City of Santa Maria to be an effluent limitation.

Table 7. Groundwater Monitoring if Option 2 is Chosen
Constituent Units Sample
Type
Sampling
Frequency
Groundwater Elevation [1] 0.01 ft amsl Calculated Quarterly Depth to Groundwater [1] 0.01 ft bgs Measurement Quarterly Gradient feet/feet Calculated Quarterly
Groundwater Flow Direction [2] degrees Calculated Quarterly Total Nitrogen[3] mg/L Calculated Quarterly
Nitrate (as N) mg/L Grab Quarterly
Nitrite (as N) mg/L Grab Quarterly
Total Kjeldahl Nitrogen (as N) mg/L Grab Quarterly
Ammonia (as N) mg/L Grab Quarterly
Total Dissolved Solids mg/L Grab Quarterly
Chloride mg/L Grab Quarterly
Sodium mg/L Grab Quarterly
Sulfate mg/L Grab Quarterly
Boron mg/L Grab Quarterly
Carbonate mg/L Grab Semiannually
Bicarbonate mg/L Grab Semiannually
Calcium mg/L Grab Semiannually
Potassium mg/L Grab Semiannually
Magnesium mg/L Grab Semiannually
pH pH Units Metered Quarterly
Dissolved Oxygen mg/L Metered Quarterly
Phenol [4] mg/L Grab Annual
Formaldehyde [4] mg/L Grab Annual
MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
13 Constituent Units Sample
Type
Sampling
Frequency
Zinc [4] mg/L Grab Annual
[1] ft amsl denotes feet above mean sea level and ft bgs denotes feet below ground surface. [2] Calculations must be prepared by, or under the responsible charge of, a California licensed professional.
[3] Total nitrogen is the sum of total inorganic nitrogen (nitrate + nitrite + ammonium + ammonia) and organic nitrogen.
[4] Sampling required once every five years if not detected in initial sample.

4. Groundwater monitoring reports, workplans, and other technical reports that interpret groundwater data must be prepared and stamped by a California licensed civil engineer or professional geologist.

B. GROUNDWATER MONITORING PRIOR TO OCTOBER 16, 2024
Table 8. Groundwater Monitoring Prior to October 16, 2024 Constituent Units Sample
Type
Sampling
Frequency
Groundwater Elevation 0.01 ft amsl Calculated Quarterly Depth to Groundwater 0.01 ft bgs Measurement Quarterly
Total Nitrogen mg/L Calculated Quarterly
Nitrate (as N) mg/L Grab Quarterly
Nitrite (as N) mg/L Grab Quarterly
Total Kjeldahl Nitrogen (as N) mg/L Grab Quarterly
Ammonia (as N) mg/L Grab Quarterly
Chloride mg/L Grab Quarterly
Sodium mg/L Grab Quarterly
Sulfate mg/L Grab Quarterly
Boron mg/L Grab Quarterly
VI. REPORTING REQUIREMENTS
A. QUARTERLY AND ANNUAL MONITORING REPORTS
Quarterly and annual monitoring reports are due as described in Table 9.

MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
14 Table 9. Quarterly and Annual Monitoring Reporting
Report Monitoring Period Report Due Date
First Quarter Monitoring
Report January 1 to March 31 May 1
Second Quarter Monitoring
Report April 1 to June 30 August 1
Third Quarter Monitoring
Report July 1 to September 30 November 1
Fourth Quarter Monitoring
Report October 1 to December 31 February 1
Annual Monitoring Report January 1 to December 31 March 1 Annual Pretreatment
Program Report January 1 to December 31 March 1
State Water Board
Volumetric Annual
Reporting
January 1 to December 31 April 30

1. Quarterly Monitoring Reporting – At a minimum, the quarterly reports must include:
i. Results of all required monitoring in tabular format. ii. The results of any pollutant or parameter monitored more frequently than is required by this monitoring program. Values obtained through additional monitoring must be used in calculations as appropriate. iii. A comparison of monitoring data to the discharge specifications, applicable effluent limitations, disclosure of any violations of the notice of applicability and/or General Permit, and an explanation of any violation of those requirements. The City of Santa Maria must calculate 7-day averages, 30- day averages and 25-month rolling medians for select analytes when comparing monitoring data to applicable effluent limitations specified in the General Permit. Data must be presented in tabular format. iv. Copies of laboratory analytical report(s) and chain of custody form(s). v. An updated hydrogeologic conceptual site model with the groundwater monitoring reporting requirements based on new information generated from the monitoring well boring logs, groundwater elevation data, and water quality data.
vi. Copies of groundwater monitoring well field sheets with purge methods and data.

MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
15 2. Annual Monitoring Reporting – The City of Santa Maria must submit annual reports in compliance with Standard Provisions 20135, (and any updates to the Standard Provisions) Section C, General Reporting Requirements, Item 16 using the most recent annual report template provided by Central Coast Water Board.

The current annual report template can be found here:
https://www.waterboards.ca.gov/centralcoast/board_decisions/adopted_orders/2 020/wdr_annual_report_format.pdf

3. Annual Pretreatment Program Report – Pursuant to California Code of Regulations, title 23, section 2233, subdivision (a), because the City of Santa Maria’s Wastewater System is designed to treat over five million gallons a day, the city must have and enforce an adequate pretreatment program approved by the Central Coast Water Board. The City of Santa Maria’s Pretreatment Program was approved by the Environmental Protection Agency (EPA) in 1982. The Pretreatment Program monitors compliance of permitted facilities and attempts to identify and reduce pollutants to both sanitary and stormwater collection systems.

On occasion, there may be a need to modify an existing pretreatment program, as identified by either the City of Santa Maria or the Central Coast Water Board.

These modifications may be driven by a variety of factors such as, but not limited to, a change in conditions at the Wastewater System, a recalculation of local limits (or reallocation of the maximum allowable industrial loading), changes to federal pretreatment regulations, or a change in the industrial user base discharging to the Wastewater System. Substantial modification is defined in title 40 Code of Federal Regulations (CFR) 403.18(b).

For substantial modifications, the City of Santa Maria must submit in writing to the Central Coast Water Board the rationale for the substantial modification, a detailed description of the proposed modification, and other documents considered necessary by Central Coast Water Board staff.

The City of Santa Maria must submit an annual Pretreatment Program report in accordance with title 40 CFR 403.12(i) that describes the City of Santa Maria’s pretreatment program activities, including activities of all participating agencies, if more than one jurisdiction is involved in the program. The report must include, at a minimum, the applicable required data in appendix A to 40 CFR part 127 which requires the following data to be added or updated annually:
i. Pretreatment program approval or modification date
5 See General Permit Attachment E, Standard Provisions, 2013:
https://www.waterboards.ca.gov/centralcoast/board_decisions/docs/wdr_standard_provi sions_2013.pdf
MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
16 ii. Pretreatment program modification type
iii. Industrial user type
iv. Significant industrial user subject to local limits v. Significant industrial user subject to local limits more stringent than categorical standards
vi. Significant industrial user wastewater flow rate
vii. Industrial user causing problems at the Wastewater System viii. Receiving resource conservation and recovery act (RCRA) waste ix. Receiving remediation waste
The report must also include a summary of changes to the City of Santa Maria’s pretreatment program that have not been previously reported to the Central Coast Water Board and any other relevant information requested by the Central Coast Water Board.

4. State Water Board Volumetric Annual Reporting – The City of Santa Maria must electronically certify and submit a summary of the monthly influent and effluent flow volume by April 30th of each calendar year via the State Water Board’s Internet GeoTracker database.6
The following information is required:
i. Monthly volume of wastewater collected and treated by the wastewater treatment plant (i.e., total monthly influent volume).
ii. Monthly volume of wastewater treated, specifying level of treatment, including treated wastewater discharged.
iii. If applicable, monthly volume of recycled water distributed, and annual volume of treated wastewater distributed for beneficial use in compliance with California Code of Regulations, title 22 use categories.

Additional information about volumetric annual reporting of wastewater and recycled water and the Recycled Water Policy is available at the Recycled Water Policy Volumetric Annual Reporting Website7.
6 See: https://geotracker.waterboards.ca.gov/
7 See: Volumetric Annual Reporting | California State Water Resources Control Board MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
17 B. NON-COMPLIANCE REPORTING:

The City of Santa Maria must notify and report to Central Coast Water Board noncompliance of limits related to pond freeboard, flow rate, bypass or overflow, and wastewater containment failure, pursuant to General Permit section VI.C.2.

C. ELECTRONIC GEOTRACKER SUBMITTAL
All monitoring reports must be provided electronically in a searchable PDF format, with the Central Coast Water Board’s current transmittal sheet found at the link below as the cover page. The transmittal sheet must be signed.
https://www.waterboards.ca.gov/centralcoast/water_issues/programs/wastewater_permi tting/docs/transmittal_sheet.pdf
The City of Santa Maria must submit all reports/documents and laboratory analytical data to the State Water Board’s GeoTracker8,9 database consistent with applicable Electronic Submittal of Information (ESI) requirements under the Wastewater System-specific global identification number WDR100029526 at:
https://geotracker.waterboards.ca.gov/esi/login
For general questions, please contact the GeoTracker Help Desk at:

[email protected].

Table 10 summarizes all the GeoTracker electronic reporting requirements. Central Coast Water Board may request submittal of some documents on paper, particularly drawings or maps that require a large size to be readable, or in other electronic formats where evaluation of data is required.

Table 10. GeoTracker Electronic Submittal Information Data Requirements Electronic
Submittal Description of Action Action Frequency
8 Information for first-time GeoTracker users is available at:
https://www.waterboards.ca.gov/ust/electronic_submittal/docs/beginnerguide2.pdf 9 Additional information available at:
https://geotracker.waterboards.ca.gov/
MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
18 Electronic
Submittal Description of Action Action Frequency
Reports and
Documents
Complete copy of all
documents including
monitoring reports (in
searchable PDF format) and
any other associated
documents related to the
Wastewater System.

Upload directly to
GeoTracker all
monitoring reports (in
searchable PDF
format) and any
other associated
documents.

On or before the due
dates required by this
General Permit and for
other documents when
required by the Central
Coast Water Board.

Laboratory
Data
All analytical data (including
geochemical data) in
electronic deliverable format
(EDF). This includes all
water, soil, and vapor
samples collected when
monitoring a discharge.

Upload, or direct
your California
ELAP-accredited
laboratory staff to
upload, all EDF
laboratory data
directly to
GeoTracker.

On or before the due
date of the required
monitoring report.

Depth to
Groundwater
Monitoring wells must have
the depth-to-water
information reported. Report
data only for wells defined as
permanent sampling points.

Upload depth-to-water information to
the GeoTracker
GEO_WELL file.

On or before the due
date of the required
monitoring report.

Boring Logs
and Well
Screen
Intervals
Boring logs must be prepared
by a registered professional
and submitted in PDF format
separately (not only as
attachments to reports).

Upload boring logs
(in searchable PDF
format) to
GeoTracker
GEO_BORE file
whenever a new
boring is drilled.

Every time a new
boring is drilled.

Field Points,
Location Data
(Geo XY)[1]
Name, classify, and identify
the location (latitude and
longitude) of all sampling
points. Monitoring wells must
be surveyed, influent and
effluent sample locations
must be identified on the
GeoTracker mapping tool
under “non-surveyed data.”
These data points are
required prior to laboratory
data uploads.

Upload the location
data (surveyed and
non-surveyed) to the
GeoTracker Geo_XY
file.

Every time a
permanent monitoring
point is established.

MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
19 Electronic
Submittal Description of Action Action Frequency
Elevation
Data
(Geo Z)[2]
Survey and mark the
elevation at the top of
groundwater well casings for
all permanent groundwater
wells. These points are
required prior to depth-to-water data uploads.

Upload the survey
data to the
GeoTracker GEO_Z
file.

One-time, for all
groundwater
monitoring wells.

Geo Map
Site layout, map of facilities,
Wastewater System including
treatment and disposal
area(s).

Upload the Site
layout PDF to the
GeoTracker site plan
file.

Year one and every
five years thereafter
and when the facilities
are modified.
[1] Geo XY required for all wells. New wells must be surveyed. For existing wells, use original well installation survey data. The City of Santa Maria must also upload sample locations (e.g., influent and effluent samples) that are not defined as a permanent monitoring well and have not been surveyed by a licensed professional.
[2] Geo Z required for all wells. New wells must be surveyed. For existing wells, use original well installation survey data.

VII. TECHNICAL REPORTS
The technical reports are due as described in Table 11.

Table 11. Technical Report Submittal Due Dates
Report Report Due Date
Operations and Maintenance Manual June 16, 2024
Climate Change Adaptation Plan June 16, 2025
Salt and Nutrient Management Plan Not Applicable
Time Schedule Compliance Plan June 16, 2024
Groundwater Monitoring Plan[1] October 16, 2024
[1] Required if the City of Santa Maria chooses Option 2 described in section V.A.

1. Operations and Maintenance Manual – In addition to the required components specified in Standard Provisions10 A.12 and A.28 (and any updates to the 10 See General Permit Attachment E, Standard Provisions, 2013:
https://www.waterboards.ca.gov/centralcoast/board_decisions/do-cs/wdr_standard_provisions_2013.pdf MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
20 Standard Provisions) and General Permit section VI.A.2, the Operations and Maintenance Manual must contain the following components. Each component must contain an implementation schedule and identification of adequate funding to implement the component.
i. Sampling and Analysis Plan – The City of Santa Maria’s Operation and Maintenance Manual must contain a sampling and analysis plan that meets the requirements specified herein. Anyone performing sampling on behalf of the City of Santa Maria must be familiar with the sampling and analysis plan. At a minimum, the sampling and analysis plan must contain the following:
a. A wastewater treatment process flow schematic with the monitoring locations labeled and scaled Wastewater System maps with treatment components, discharge locations (both treated wastewater and non-potable recycled water), monitoring locations, groundwater wells, storage locations (e.g., chemical, sludge, emergency overflow ponds), and buildings. If the City of Santa Maria needs to update Figure 1 to comply with this requirement, a copy of the updated process flow schematic will also be included with the annual report. b. Sample identification details in tabular format. The table must include the sample titles, GeoTracker field point information, sample description(s), and sampling frequencies.
c. Sample chain-of-custody procedures and documentation. d. Sample handling/preservation procedures.
e. A description of the analytical methods.
f. A description of sample containers, preservatives, and holding times. g. For water supply monitoring, a description of the location and method of data collection (e.g., onsite well sampling, use of consumer confidence report).
h. For groundwater monitoring, a description of the well purging and field methods.
ii. Sludge Management Plan – The City of Santa Maria’s Operation and Maintenance Manual must contain a sludge management plan that is sufficient to ensure compliance with the terms of the General Permit and the notice of applicability. At a minimum, the plan must describe the following:

MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
21 a. An estimated volume/amount and quality of sludge and scum that will be generated.
b. How sludge, scum, and supernatant will be stored and disposed of to protect groundwater quality.
c. If sludge will be subject to further treatment, describe the treatment and storage requirements.
d. Procedures for cleaning of digesters or storage vessels and the treatment and disposal of the residuals. If drying of residuals is planned, describe how that will be performed to prevent nuisance odors, prevent vectors, and protect groundwater quality. iii. Wastewater Disposal Management Plan – The City of Santa Maria’s Operation and Maintenance Manual must contain a wastewater disposal management plan that is sufficient to ensure compliance with the terms of the General Permit and the notice of applicability. At a minimum, the wastewater disposal management plan must include:
a. A description of the wastewater disposal area and a map denoting acreage.
b. Loading calculations based on flow volumes, applied acreage, and biochemical oxygen demand, salts (total dissolved solids, sodium, chloride, sulfate, boron), and nitrogen analytical results. c. A description of wastewater disposal and water quality protection practices.
iv. Spill Prevention and Emergency Response Plan –The City of Santa Maria’s Operation and Maintenance Manual must contain a spill prevention and emergency response plan that is sufficient to ensure compliance with the terms of the General Permit and the notice of applicability. The spill prevention and emergency response plan must describe operation and maintenance activities to prevent accidental releases of wastewater and to effectively respond to such releases and minimize the environmental impact. At a minimum, the spill prevention and emergency response plan must address the following:
a. Operation and Control of Wastewater System - A description of the wastewater treatment equipment, operational controls, flow measurement and calibration procedures, and treatment system schematic including valve/gate locations.
b. Sludge Handling - A description of the sludge handling equipment, operational controls, and disposal procedures.
c. Collection System Maintenance - A description of collection system cleaning and maintenance, equipment tests, and alarm functionality tests to minimize the potential for wastewater spills originating in the MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
22 collection system or headworks. For collection systems subject to State Water Board Order WQ 2022-0103-DWQ, Statewide Waste Discharge Requirements General Order for Sanitary Sewer Systems (or its replacement), reports prepared to comply with State Water Board Order WQ 2022-0103-DWQ satisfy this requirement.
d. Emergency Response - A description of emergency response procedures including for emergencies such as power outage, severe weather, flooding, or inadequate freeboard (for systems with wastewater treatment, storage, or disposal ponds or treated non-potable recycled water storage ponds). An equipment and telephone list for contractors/consultants, emergency personnel, and equipment vendors.
e. Finance - At a minimum, discuss current fees, projected fees, current budget for spill prevention and emergency response, projected budget for spill prevention and emergency response.
f. Notification Procedures - Coordination procedures with fire, police, Governor’s Office of Emergency Services (CalOES), Central Coast Water Board, and local county health department personnel. v. Training Records Log – The City of Santa Maria’s Operation and Maintenance Manual must contain updated training records logs that demonstrate the City of Santa Maria is complying with General Permit section VI.B.3.

2. Climate Change Adaptation –The Climate Change Adaptation Plan must, at a minimum, include the following components:
i. Hazards and Vulnerabilities – Identify climate change hazards, at a minimum accounting for the hazards listed below, applicable to the Wastewater System. Using up-to-date tools, data, and guidance from the State of California (e.g., Cal-Adapt11, Sea-Level Rise Guidance from Ocean Protection Council, reports from the Climate-Safe Infrastructure 11 Cal-Adapt is an online resource with downscaled climate project data. It provides users with projections and more detailed downloadable data supporting a range of needs and array of climate models and emissions scenarios. Cal-Adapt offers climate projections for the major stressors facing California, including the following: temperature averages and extremes, precipitation averages and extremes, sea-level rise, wildfires, and drought. The Governor’s Office of Planning and Research (OPR) recommends agencies use Representative Concentration Pathway (RCP) 8.5 for analyses considering impacts through 2050, because there are minimal differences between emissions scenarios during the first half of the 21st century.

MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
23 Working Group, the Climate Adaptation Planning Guide, and California Climate Assessment Regional Reports), assess the Wastewater System’s vulnerability to identified hazards that could cause reduction, loss, or failure of treatment processes and/or critical structures at the Wastewater System. Identify and justify the resources (e.g., models and tools, design parameters) used to inform identification of these hazards and vulnerabilities.
a. Sea Level Rise – Saltwater intrusion, flooding and inundation, and increased coastal erosion.
b. Precipitation Pattern Changes.

I. Drought – Decreased influent quantity and quality.

II. Peak Events – Flooding and increased influent quantity. c. Temperature fluctuations and extremes.
d. Increased wildfires.
e. Increased power outages.
ii. Resiliency Actions – Identify actions to build Wastewater System and operational resilience to identified vulnerabilities, accounting for options that minimize resource impacts.
iii. Adaptation Strategy – For Wastewater Systems with design flows over 1,000,000 gallons per day, develop and implement a strategy to complete resiliency actions, at a minimum encompassing the following:
a. Prioritization – Prioritized resiliency actions based on risks to water quality, but also accounting for costs and benefits.
b. Schedule and Milestones – Timeframes to complete prioritized resiliency actions and/or climate change hazard triggers to inform when the City of Santa Maria must implement actions. Milestones to complete critical steps for prioritized resiliency actions, designed to demonstrate measurable progress at a steady, or accelerated, completion pace over the established timeframes.
c. Financial Planning – Projected costs necessary to implement and sustain resiliency actions and strategy to procure funds. iv. Recycled Water Feasibility Plan – Dischargers with Wastewater System design flows over 1,000,000 gallons per day must include a recycled water feasibility plan.

The recycled water feasibility plan will assess the viability of using the Wastewater System’s treated wastewater effluent for beneficial reuse including, but not limited to the following:
a. Beneficial Reuse Options – Identification of reuse opportunities for the City of Santa Maria’s treated effluent that would achieve the highest beneficial impact and best uses possible of non-potable recycled MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
24 water. Include assessment of the following non-potable recycled water benefits identified in the State Water Board Recycled Water Policy:
providing safe alternatives to fresh water or potable water for approved uses; supporting sustainable groundwater and surface water uses with the intent of substituting use of treated effluent for use of fresh water or potable water; and diversifying community water supplies and mitigating for the impacts of climate change.12
b. Viable Users – Identification and viability evaluation of all potential users of the Wastewater System’s treated effluent associated with identified beneficial reuse options. The City of Santa Maria must demonstrate it engaged potential water purveyors and customers about the viability of reusing the Wastewater System’s treated effluent. c. Infrastructure Upgrades – Assessment of infrastructure needs to produce non-potable recycled water for identified beneficial reuses and convey non-potable recycled water to beneficial reuse locations. d. Fiscal Analysis – Cost estimates for identified reuse options, at a minimum including project development, construction, and long-term maintenance and lifecycle costs. This analysis shall also include identification and evaluation of the following: 1) funding options, including at a minimum, revenues from recycled water sales, grant and loan funding opportunities, and financing from other benefitting parties and 2) funding limitations.
e. Schedule and Milestones for Next Steps – Timeframes to assess the feasibility of identified beneficial reuse options and to identify proposed beneficial reuse options based on prioritized water recycling and reuse opportunities, feasibility assessments, and other factors identified by the City of Santa Maria.
f. Identification of implementation schedule and adequate funding to implement the plan.

3. Salt and Nutrient Management Plan – The City of Santa Maria is an active cooperating partner of the Santa Barbara County Integrated Regional Water Management (IRWM) Plan’s regional water management group. The regional water management group prepared and submitted an assessment of the Santa Maria Valley Groundwater basin to the Central Coast Water Board. The assessment concluded that the dischargers participating in the workgroup were in balance for salts and nutrients in 2013. A salt and nutrient management plan is 12 Water Quality Control Policy for Recycled Water, State Water Board, adopted December 11, 2018, page 1.

MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
25 currently not required while the City of Santa Maria participates in the Santa Barbara County IRWM regional water management group.

4. Time Schedule Compliance Plan - As set forth in General Permit sections V.A and VI.A.5, if the City of Santa Maria anticipates that additional time is needed to achieve compliance with the effluent limitations, the City of Santa Maria must prepare and submit for Central Coast Water Board review and approval, a time schedule compliance plan. At a minimum, the time schedule compliance plan must address the following:
i. Comparison of the current effluent quality to the effluent and groundwater limitations in General Permit Tables 3-6.
ii. Identification of the City of Santa Maria’s choice for compliance for each constituent pursuant to General Permit section V.A.2 Option 1 or Option 2 (complying with an effluent limit or demonstrating compliance through a groundwater monitoring program).
iii. A detailed description and chronology of efforts, since issuance of the notice of applicability, to reduce wastes.
iv. Justification of the need for additional time to achieve the effluent limitations in General Permit Tables 3-6.
v. A detailed time schedule of specific actions the City of Santa Maria will take to achieve the effluent limitations.
vi. A demonstration that the time schedule requested is as short as possible, considering the technological, operation, and economic factors that affect the design, development, and implementation of the measures that are necessary to comply with the effluent limitation(s).
vii. If the requested time schedule exceeds one year, the proposed schedule shall include interim requirements and the date(s) for their achievement. The interim requirements shall include both of the following:
a. Effluent limitation(s) for the pollutant(s) of concern. b. Actions, measurable milestones, and tangible products leading to compliance with the effluent limitation(s).

VIII. LEGAL REQUIREMENTS
The Central Coast Water Board’s requirements that the City of Santa Maria submit the technical and monitoring reports described in this monitoring and reporting program are made pursuant to section 13267 of the California Water Code. Failure to submit reports in accordance with schedules established by this General Permit and notice of applicability with attachments or failure to submit a report of sufficient technical quality to be acceptable to the Central Coast Water Board may subject the City of Santa Maria to enforcement action pursuant to section 13268 of the California Water Code. Pursuant to section 13268 of the Water Code, a violation of a request made pursuant to section MRP No. R3-2023-0032 June 16, 2023
City of Santa Maria Wastewater Treatment System
26 13267 may subject the City of Santa Maria to civil liability assessment of up to $1,000 per day in which the violation occurs.

The Central Coast Water Board needs the required information to ensure compliance with the notice of applicability and the General Permit. The City of Santa Maria is required to submit this information because it is subject to the General Permit and is responsible for the discharge.

The burden, including costs, of the reports bears a reasonable relationship to their need and the benefits to be obtained. The requirement for the reports is necessary to ensure compliance with the General Permit, notice of applicability, and monitoring and reporting program to protect water quality.

The City of Santa Maria must implement the above monitoring program on October 1, 2023. The Central Coast Water Board may rescind or modify this monitoring and reporting program at any time.

Ordered By:

for Matthew T. Keeling
Executive Officer
\\ca.epa.local\RB\RB3\Shared\WDR\WDR Facilities\Santa Barbara Co\Santa Maria WWTP\Order 2020-0020\final\Santa Maria_MRP_ R3-2023-0032_final.docx Solids Waste
Facility Permit
Facility Number:

SOLID WASTE FACILITY PERMIT 42-AA-0016

1. Name and Street Address of Facility:

Santa Maria Regional Landfill
2065 East Main Street
Santa Maria, CA. 93454

4. Specifications:

2. Name and Mailing Address of Operator:

City of Santa Maria
2065 East Main Street
Santa Maria, CA. 93454

3. Name and Mailing Address of Owner:

City of Santa Maria
2065 East Main Street
Santa Maria, CA. 93454
a. Permitted Operations: Solid Waste Disposal Site D Transformation Facility D Transfer/Processing Facility (MRF) D Composting Facility D Other: __
b. Permitted Hours of Operation:
c. Permitted Maximum Tonnage:
d. Permitted Traffic Volume:
(Receipt of Refuse/Waste) 4:00 a.m. to 7:00 p.m. Sunday to Saturday, closed holidays. (Ancillary Operations/Facility Operating Hours) Agricultural Plastic Baling and the Concrete and Asphalt Recycling operations may operate 24 hours per day Sunday to Saturday, closed holidays.
8,820 Tons per Week (Disposal), (See EA Conditions 17-d). 810 Vehicles per Day
e. Key Design Parameters (Detailed parameters are shown on site plans bearing EA and CalRecycle validations):

Permitted Area (in acres)
Design Capacity ( cu. yds)
Max. Elevation (Ft. MSL) Max. Depth (Ft. MSL)
Estimated Closure Year
Total
290.88
Disposal
247.16
15,278,400
410
265
2034
Transfer/Processing Composting Transformation
Upon a significant change in design or operation from that described herein, this permit is subject to revocation or suspension. The attached permit findings and conditions are integral parts of this permit and supersede the conditions of any previously issued solid waste facility permit.

5. Approval:

Lars Seifert, Director Environmental Health Services
ag ~:tu,e

7. Date Received by CalRecycle:

May 16, 2024

6. Enforcement Agency Name and Address:

Santa Barbara County, Environmental Health Services
225 Camino de! Remedio
Santa Barbara, CA. 93110

8. CalRecyde Concurrence Date:

June 27, 2024

9. Permit Issued Date: 10. Permit Review Due Date: 11. Owner/Operator Transfer Date:

May 7, 2029

Page 1 of 4 ends
Page 2 of 4 ends

SOLID WASTE FACILITY PERMIT
Facility Number:
42-AA-0016

12. Legal Description of Facility:

The legal description of this facility is contained in Section 3.3.4 of the Joint Technical Document dated February 2, 2024.

Legal description of facility: Sections 7, 8, 16, and 17, Township 10 North, Range 33 West, and Sections 1 and 12, Township 10 North, Range 34 West, San Bernardino Baseline and Meridian (SBB&M).

13. Findings:
a. This permit is consistent with the Santa Barbara County Integrated Waste Management Plan, which was approved by the CIWMB on 5/98. The location of the facility is identified in the Countywide Sitting Element, pursuant to Public Resources Code (PRC), Section 50001(a).
b. This permit is consistent with the standards adopted by CalRecycle, pursuant to PRC 44010. c. The design and operation of the facility is consistent with the State Minimum Standards for Solid Waste Handling and Disposal as determined by the enforcement agency, pursuant to PRC 44009. d. The Santa Maria City Fire Department has determined that the facility is in conformance with applicable fire standards, pursuant to PRC, 44151.
e. The 1993 Final Environmental Impact Report (EIR), 1995 Supplement to the EIR, 2001 Addendum to the EIR, 2004 Second Supplemental EIR (SEIR), 2018 Addendum to the Second SEIR, 2021 second Addendum to the Second SEIR, and 2023 Addendum to the Second Final Supplemental EIR were certified or approved by the Santa Maria City Council on 12/93, 9/95, 5/01, 7/04, 5/18, 3/21 and 12/23. The 1993 EIR, 1995 Supplement to the EIR, and 2004 Second SEIR were filed with the State Clearinghouse (SCH #1992031045). A NOE was filed in September 2009 for a Co-gen Plant and to clarify the amount of Agricultural Plastic received. These documents describe and support the design and operation, which will be authorized by the issuance of this permit.

14. Prohibitions:

The permittee is prohibited from accepting the following wastes:

Hazardous, radioactive, medical (as defined in Health and Safety Code Sections 117600-118360), liquid, designated, burning waste, hot ashes, or other wastes requiring special treatment or handling, except as identified in the Joint Technical Document/Report of Facility Information and approved amendments thereto and as approved by the enforcement agency.

15. The following documents describe and/or restrict the operation of this facility:

Date Date
Joint Technical Document & Amendment 2/24 Preliminary and Partial Final Closure and Postclosure Maintenance Plan 02/05/24
Waste Discharge Requirements
Order No. R3-2020-0001
12/22 Closure Financial Assurance Documentation 06/30/23 APCD Permit to Operate #10318-R3 8/17 Operating Liability Certification 09/12/23 EIR, Supplemental EIR, EIR Addendum,
Final Second Supplemental EIR, Addendum
to Final Second SEIR, second Addendum to
Final Second SEIR and 2023 Addendum to
the Second Final Supplemental EIR.
(SCH # 1992031045)
12/93, 9/95,
5/01, 7/04,
5/18, 3/21 and
12/23
Land Use and/or Conditional Use Permit(s) 7/01
Notice of Exemption/Cat. Class 8 & 29 9/09
Static and Seismic Slope Stability Analysis Cell 1
Height Increase
Static and Seismic Slope Stability Analysis Cell 1
Extension
5/18
1/21&
12/23

Page 3 of 4 ends

SOLID WASTE FACILITY PERMIT
Facility Number:
42-AA-0016

16. Self Monitoring:

Unless otherwise specified, the owner/operator shall submit the results of all self monitoring programs to the Enforcement Agency within 30 days of the end of the reporting period (for example, 1st quarter = January – March, the report is due by April 30, etc.. Information required on an annual basis shall be submitted with the 4th quarter monitoring report, unless otherwise stated.)
Program Reporting Frequency
a. The types and quantities (in tons) of waste, including separated or commingled recyclables, entering the facility per day. In addition, the amount of materials used as on-site ADC must be reported.
b. The number and types of vehicles using the facility per day. c. Results of the hazardous waste load checking program, including the quantities and types of hazardous wastes, medical wastes or otherwise prohibited wastes found in the waste stream and the disposition of these materials. Include record of any waste loads rejected. d. Copies of all written complaints regarding this facility and the operator's actions taken to resolve these complaints.
e. Results of landfill gas monitoring program.
f. Wet weather preparedness report/winter operations plan. g. Fill sequencing plan for forthcoming year.
h. Remaining site capacity.
i. Special Occurrences (see condition 17-b)
j. The areas of the site that were used for disposal.
k. A current list of responsible personnel for this facility. This list shall include the name and emergency phone number for the following personnel; the Site Manager, the Duty Supervisor, and any on site Contractors.

Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Annually – due by October 1
Annually
Annually
Daily log maintained on site;
summary provided in quarterly
tonnage report
Quarterly
Annually

Page 4 of 4 ends

SOLID WASTE FACILITY PERMIT
Facility Number:
42-AA-0016

17. Enforcement Agency (EA) Conditions:
a. The operator shall comply with all State Minimum Standards for solid waste handling and disposal as specified in Title 27, California Code of Regulations.
b. The operator shall maintain a log of special/unusual occurrences. This log shall include, but is not limited to, fires, explosions, the discharge and disposition of hazardous or unpermitted wastes, and significant injuries, accidents or property damage. Each log entry shall be accompanied by a summary of any actions taken by the operator to mitigate the occurrence. The log shall be available to site personnel and the EA at all times.
c. Additional information concerning the design and operation of the facility shall be furnished upon request and within the time frame specified by the EA.
d. The maximum permitted throughput for this facility is 17,640 tons per week (TPW) (based on an average of 2,520 tons per day (TPD)) with a 7-day maximum for solid waste disposal of 8,820 TPW of non-hazardous solid waste (based on an average of 1,260 TPD), and a 7-day maximum of 8,820 TPW for recyclables, diversion, and beneficial reuse (based on an average of 1,260 TPD). In addition to the daily limit, agricultural plastic received for recycling is limited to 15,000 tons per year. This facility shall not receive more than the amounts indicated above without a revision of this permit. The tonnage limits indicated above do not apply to clean earthen materials, Non-hazardous Hydrocarbon Impacted Soils (NHIS), biosolids used as final landfill cover soil amendment, biosolids used as erosion control repair material, or materials received ready for use as Alternative Daily Cover (ADC). e. This permit is subject to review by the EA and may be temporarily suspended or revoked at any time by the EA for sufficient cause, in accordance with Division 30 of the Public Resources Code, Part 4, Chapter 4 Article 2, Sections 44305 et seq. f. The EA reserves the right to suspend or modify waste receiving and handling operations when deemed necessary due to an emergency, a potential health hazard, or the creation of a public nuisance. g. Any change that would cause the design or operation of the facility not to conform to the terms and conditions of this permit is prohibited.

Such a change may be considered a significant change, requiring a permit revision. In no case shall the operator implement any change without first submitting a written notice of the proposed change, in the form of an RFI amendment, to the EA at least 180 days in advance of the change.
h. A copy of this permit shall be maintained at the facility. i. Site Elevation: - This site is designed into 4 sections; the Inactive Area, the Closed Active Area, the Active Area (Cell 1), and an Undeveloped Active Area (Cell 2). The Inactive Area has not received waste since the 1960’s. The Inactive Area has been graded and several feet of additional cover has been applied. The City of Santa Maria is currently using Non-Hazardous Impacted Soil (NHIS) as foundation material for closure construction of the Closed Active Area per approval of WDR R3-2020-0001. The Closed Active Area, the Active Area, and Undeveloped Cell 2’s elevations cannot exceed the maximum elevation, as specified in the Approved Preliminary/Partial Final Closure Plan.

The maximum elevation for the Active Area (Cell 1/Cell 1 Extension) will be 410’ MSL. j. The maximum depth for the Undeveloped Active Area (Cell 2) is 265’ MSL or at least 5 feet above the highest recorded groundwater level, whichever is highest.
k. Adequate lighting shall be provided for all operations conducted before sunrise or after sunset as described in the most current JTD. l. Site access shall be granted to the LEA for the purpose of inspection without prior notice from the LEA. m. Storage of baled and un-baled Agricultural Plastic shall be restricted to individual piles which do not exceed 5000 square feet of contiguous area and any pile shall not exceed 50,000 cubic feet nor 10 feet in height as described in the JTD.

Santa Barbara
County Air Pollution
Control District
Permit
Permit to Operate 08390 - R11

Page 1 of 14 ends

EQUIPMENT OWNER:

City of Santa Maria
EQUIPMENT OPERATOR:

City of Santa Maria
EQUIPMENT LOCATION:
601 Black Road, Santa Maria
STATIONARY SOURCE/FACILITY:

EQUIPMENT DESCRIPTION:

The equipment subject to this permit is listed in the table at the end of this permit.

PROJECT/PROCESS DESCRIPTION:

The City of Santa Maria treats its municipal wastewater (sewage) at this plant. Influent is separated by mechanical bar screens and a grit chamber. The wastewater is then sent through primary clarifiers and trickling filters and secondary clarifiers and trickling filters for aerobic treatment. Treated wastewater is then sent to percolation ponds for disposal.

Solids from the aerobic treatment system are sent to sludge thickeners, the sludge is treated anaerobically in the digesters. The anaerobic digesters are each equipped with a pressure and vacuum relief value to avoid under and over-pressurization. Anaerobic decomposition generates methane that is burned in a boiler or two waste gas flares.

Ferrous chloride is injected in the sludge as needed to reduce the concentration of hydrogen sulfide and sulfur compounds in the digester gas. An iron sponge scrubber is used as needed to further reduce hydrogen sulfide concentrations to permitted emission limits. The plant is currently rated for treating 13.5 million gallons per day of raw sewage in a peak month.

SSID: 02077
City of Santa Maria WWTP FID: 02077
Permit to Operate 08390 - R11

Page 2 of 14 ends

CONDITIONS:

1. Emission Limitations. The mass emissions from the equipment permitted herein shall not exceed the values listed in Table 1 and Table 2. Compliance shall be based on the operational, monitoring, recordkeeping and reporting conditions of this permit.

2. Operational Restrictions. The equipment permitted herein is subject to the following operational restrictions:
a. Maximum combined heat input to the waste gas flares and pilots shall not exceed

12.145 MMBtu/hr, 291.480 MMBtu/day, and 106,390.200 MMBtu/year. b. The volume of digester gas burned daily in the waste gas flares shall not exceed 478,200 scf/day (total monthly amount ÷ number of days per month of gas usage). c. The combined volume of propane burned daily in the Waste Gas Flare 1 and Waste Gas Flare 2 pilots shall not exceed 1,800 scf/day (total monthly amount ÷ number of days per month of gas usage).
d. Only digester gas shall be burned in the flares.
e. Only propane shall be used as fuel for the flare pilots. f. When not in operation, Waste Gas Flare 2 shall be maintained in a ready condition for immediate operation upon demand.
g. The flares shall be equipped with a shared, properly functioning flow meter for propane installed upstream the combustion units. This meter shall be calibrated in accordance with the manufacturer’s specifications and recommendations h. Heat Input Limits. The hourly, daily and annual heat input limits to Boiler 1 shall not exceed the values listed in Table 3. These limits are based on the design rating of the unit and the annual heat input value as listed in the permit application. Unless otherwise designated by the District, the following fuel content shall be used for determining compliance: Digester Gas = 600 Btu/scf, Propane = 2,522 Btu/scf. i. The volume of fuel burned daily in Boiler 1 shall not exceed any of the following:
i. 100,400 scf/day of digester gas
ii. 23,885 scf/day of gaseous propane
iii. 652.62 gals/day of liquid propane
Compliance shall be based on the total monthly amount ÷ number of days per month of fuel usage.

Permit to Operate 08390 - R11

Page 3 of 14 ends

j. Boiler 1 shall only combust digester gas or propane. k. Non-resettable totalizing fuel meters shall be used to measure the fuel input to Boiler 1.

This meter shall be calibrated at least annually in accordance with the manufacturer’s specifications and recommendations.
l. Boiler 1’s low emission kit shall be maintained and operated in accordance with the manufacturer’s specifications and requirements.
m. The total sulfur content (calculated as H2S at standard conditions, 60 °F and 14.7 psia) of gaseous fuels for all fuel burning equipment shall not exceed 50 grains per 100 cubic feet (796 ppmv).
n. The facility operator shall maintain a hydrogen sulfide awareness program so that its employees are aware of and are properly trained to respond to any emergency involving the release of hydrogen sulfide.
o. Incineration of sludge is prohibited.
p. Except for breakdown conditions defined in District Rule 505, venting of digester gas is prohibited.
q. Any replacement of the exempt boiler (Device ID: 104101) must comply with the requirements of District Rule 360 (Boilers, Water Heaters, and Process Heaters (0.075 – 2 MMBtu/hr).

3. Monitoring. The equipment permitted herein is subject to the following monitoring requirements:
a. Daily volume of digester gas combusted in the flares shall be monitored. The daily volumes shall be calculated by dividing the total monthly volume (scf) by the number of days per month. Flowmeters for quantifying the total volume (scf) of produced digester gas shall be checked weekly and maintained to ensure proper operation. b. Daily volume of propane combusted in the flares’ pilots shall be monitored. The daily volumes shall be calculated by dividing the total monthly volume (scf) by the number of days per month. Flowmeters for quantifying the total volume (scf) of propane shall be checked weekly and maintained to ensure proper operation.

Permit to Operate 08390 - R11

Page 4 of 14 ends

c. The volume (scf) of digester gas and propane combusted in Boiler 1 used shall be measured through the use of a dedicated District-approved fuel meters. The meters shall be temperature and pressure corrected. The fuel meters shall be accurate to within five percent (5%) of the full-scale reading. The meters shall be calibrated according to manufacturer’s specifications and the calibration records shall be made available to the District upon request. Additionally, flowmeters for quantifying the total volume (scf) of produced digester gas and propane shall be checked weekly and maintained to ensure proper operation.
d. Compliance Determination. The following compliance determinations are applicable to Boiler 1:
i. New/Modified Units Rated Between 2.0 - 5.0 MMBtu/hr – Not Fired on Utility Natural Gas. Any owner or operator of any unit not fired exclusively on utility natural gas shall perform District-approved source testing not less than once every 24 months using the source test methods listed in Section H of Rule 361. After the third required compliance source test, the District may, at its discretion, allow the owner or operator of the unit to perform tune-ups in lieu of source testing per the requirements of Section G.
ii. Rule 361 Non-Operational Test Firing. No tune-up is required during a calendar year for any unit subject to Rule 361 that is not operated during that calendar year.

This unit may be test fired to verify availability of the unit for its intended use but once test firing is completed it shall be shutdown. If test firing exceeds 24 hours per year, then tune-ups shall follow the requirements of Rule 361.G.1. e. Daily checks shall be performed to determine if, and when, the fuel supplied to Boiler 1 is switched to propane.
f. The permittee shall measure the hydrogen sulfide concentration of the digester gas on a daily basis in accordance with current ASTM-D1072 method, colorimetric gas detection tubes, or other District-approved equivalent method.

These measurements shall be taken every day between 4:00 am – 11:00 am. The operator shall record the date and time as well as initial the record to certify when the measurement was taken. These records shall be made available for District inspection upon request.
g. Three ambient H2S monitors shall be in place and operational at all times to detect releases of digester gas.
h. On an annual basis, the heating value (Btu/scf) of the digester gas fuel shall be measured using ASTM D-1945 method, or by a District-approved equivalent method.

Permit to Operate 08390 - R11

Page 5 of 14 ends

i. The daily volume (scf) of digester gas produced shall be monitored with gas totalizers and recorded digitally in accordance with the Emission and Digester Gas Monitoring Plan requirements.
j. The digesters, gas piping, and pressure regulators shall be inspected for leaks daily. The pressure safety valves shall be inspected for leaks quarterly. k. Daily logs detailing inspection and maintenance activities shall be maintained.

4. Recordkeeping. The permittee shall record and maintain the following information. This data shall be maintained for a minimum of three (3) years from the date of each entry and made available to the District upon request:
a. Daily volume (scf/day) of digester gas combusted in the waste gas flares for each month.

The daily volumes shall be calculated by dividing the total monthly volume (scf) by the number of days per month.
b. Daily volumes (scf/day) of propane gas combusted in the waste gas flare pilots for each month. The daily volumes shall be calculated by dividing the total monthly volume (scf) by the number of days per month.
c. Number of days that the waste gas flares operation.
d. The volumes (scf) of digester gas and propane combust each month in Boiler 1. e. The number of days that Boiler 1 operated on digester gas each month. f. The number of days that Boiler 1 operated on propane gas each month. g. The dates and times the fuel supplied to Boiler 1 is switched to propane and returned to digester gas.
h. Tuning Records. For units subject to Rule 361 tuning requirements, copies of all Rule 361 Tune-Up Reports as specified in Step 12 of Procedure A and/or Step 6 of Procedure B of the tuning Attachment to Rule 361.
i. Rule 361 Non-Operational Test Firing. A log that documents the date and number of hours that the unit was test fired in accordance with Rule 361.I.3. j. Measurements of the daily total sulfur content (ppmv) of the digester gas, taken in accordance with Condition 3.f of this permit.
k. The heating value of the digester gas fuel as measured in accordance with Condition 3.h.

Permit to Operate 08390 - R11

Page 6 of 14 ends

l. Records of the date and time of any leaks detected from the digesters, gas piping, pressure regulators, or pressure safety valves. Records of any repair actions taken to stop the leaks and the date and time that the leaks were stopped. m. The dates and times of any ambient H2S alarms, the cause of the alarms, and any corrective actions taken to stop the H2S release.
n. Maintenance and calibration records of Boiler 1, fuel flow meters, and burner (as applicable).
o. Source test reports for all District-required stack emission tests.

5. Reporting. By March 1st of each year, a written report documenting compliance with the terms and conditions of this permit for the previous calendar year shall be provided by the permittee to the District (Attn: Annual Report Coordinator). The report shall contain information necessary to verify compliance with the emission limits and other requirements of this permit.

The report shall be in a format approved by the District. All logs and other basic source data not included in the report shall be made available to the District upon request. The report shall include the following information:
a. The daily and yearly total volume (scf) of digester gas combusted in the waste gas flares. b. The daily and yearly total volume (scf) of propane gas combusted in the waste gas flare pilots.
c. The number of days of waste gas flare operation summarized monthly and annually. d. The monthly and yearly volumes (scf) of digester gas and propane combusted in Boiler 1.
e. The number of days that Boiler 1 operated on digester gas summarized monthly and annually.
f. The number of days that Boiler 1 operated on propane gas summarized monthly and annually.
g. The dates and times the fuel supplied to Boiler 1 is switched to propane and returned to digester gas.
h. Tune-Up Reports. Tuning Records as required in the Recordkeeping Condition above. i. Rule 361 Test Firing Records. A copy of the Rule 361 Non-Operational Test Firing log. j. Records of the daily digester gas sulfur concentration (as H2S) content measurements including the date and time that the sample was taken.

Permit to Operate 08390 - R11

Page 7 of 14 ends

k. The heating value of the digester gas fuel as measured in accordance with Condition 3.h.
l. Records of the date and time of any leaks detected from the digesters, gas piping, pressure regulators, or pressure safety valves. Records of any repair actions taken to stop the leaks and the date and time that the leaks were stopped. m. The dates and times of any ambient H2S alarms, the cause of the alarms, and any corrective actions taken to stop the H2S release.
n. Fuel Meter Calibration Records. Copies of the most recent fuel use meter calibration. o. Source test reports shall be submitted to the District within 45 days of test completion.

6. Source Testing. The following source testing provisions shall apply:
a. The permittee shall conduct source testing of air emissions and process parameters listed in Table 5 of this permit. More frequent source testing may be required if the equipment does not comply with permitted limitations or if other compliance problems, as determined by the District, occur. Source testing shall be performed on a schedule identified in Table 4, using November 16 as the anniversary date.

After the third required compliance source test, the District may, at its discretion, allow the owner or operator of the unit to perform tune-ups in lieu of source testing per the requirements of Section G of Rule 361.
b. The permittee shall submit a written source test plan to the District for approval at least thirty (30) days prior to initiation of each source test. The source test plan shall be prepared consistent with the District's Source Test Procedures Manual (revised May 1990 and any subsequent revisions). The permittee shall obtain written District approval of the source test plan prior to commencement of source testing. The District shall be notified at least ten (10) calendar days prior to the start of source testing activity to arrange for a mutually agreeable source test date when District personnel may observe the test. c. Source test results shall be submitted to the District within forty-five (45) calendar days following the date of source test completion and shall be consistent with the requirements approved within the source test plan. Source test results shall document the permittee’s compliance status with mass emission rates in Table 1 and applicable permit conditions, rules and NSPS (if applicable). For determining compliance with daily emission limits, the applicable pounds per day value in Table 1 shall be divided by 24 to convert to a "pounds per hour equivalent limit". If the source test pounds per hour result for a pollutant exceeds the "pounds per hour equivalent limit", then the source is not in compliance with the pounds per day permitted limit for the applicable pollutant. All District costs associated with the review and approval of all plans and reports and the witnessing of tests shall be paid by the permittee as provided for by District Rule 210.

Permit to Operate 08390 - R11

Page 8 of 14 ends

d. A source test for an item of equipment shall be performed on the scheduled day of testing (the test day mutually agreed to) unless circumstances beyond the control of the operator prevent completion of the test on the scheduled day. Such circumstances include mechanical malfunction of the equipment to be tested, malfunction of the source test equipment, delays in source test contractor arrival and/or set-up, or unsafe conditions on site. Except in cases of an emergency, the operator shall seek and obtain District approval before deferring or discontinuing a scheduled test, or performing maintenance on the equipment item on the scheduled test day. If the test cannot be completed on the scheduled day, then the test shall be rescheduled for another time with prior authorization by the District. Once the sample probe has been inserted into the exhaust stream of the equipment unit to be tested (or extraction of the sample has begun), the test shall proceed in accordance with the approved source test plan. In no case shall a test run be aborted except in the case of an emergency or unless approval is first obtained from the District.

Failing to perform the source test of an equipment item on the scheduled test day without a valid reason and without District's authorization shall constitute a violation of this permit. If a test is postponed due to an emergency, written documentation of the emergency event shall be submitted to the District by the close of the business day following the scheduled test day.

The timelines in a, b, and c above may be extended for good cause provided a written request is submitted to the District at least three (3) days in advance of the deadline, and approval for the extension is granted by the District.

7. Inspection and Maintenance. The permittee shall implement the District-approved Inspection and Maintenance Plan (approved January 29, 2015). The permittee shall maintain the inspection and maintenance program for the pressure regulator vents, the pressure regulator seals, and other digester gas discharge piping, valves and flanges. The contents of the plan shall include, at a minimum, details on:
a. Spare parts to be kept on site.
b. Definition of emission concentration threshold level to be used to trigger repair or replacement.
c. Method of leak detection employed.
d. Time between leak detection and repair for each component. e. Recordkeeping procedure and data reporting format to be used. f. Quality assurance procedures.

Permit to Operate 08390 - R11

Page 9 of 14 ends

8. Emission and Digester Gas Monitoring Plan. The permittee shall implement the District-approved Emission and Digester Gas Monitoring Plan (approved January 29, 2015).

The contents of the District-approved plan shall be implemented and include, at a minimum, details on:
a. The pressure regulator settings for discharging digester gas to the flare(s). b. The pressure regulator settings for atmospheric venting of digester gas. c. The setting for triggering the high gas pressure alarm of the sensor in the digester dome top.
d. The ambient monitors capable of detecting and triggering an audio alarm when H2S concentrations  10 ppmv are detected.
e. The monitoring of atmospheric venting from the digester pressure regulators. f. The methods used to maintain operative gas meters and recorders for each digester gas discharge line.

9. Consistency with Analysis. Operation under this permit shall be conducted consistent with all data, specifications and assumptions included with the application and supplements thereof (as documented in the District's project file) and the District's analyses under which this permit is issued as documented in the Permit Analyses prepared for and issued with the permit.

10. Equipment Maintenance. The equipment listed in this permit shall be properly maintained and kept in good condition at all times. The equipment manufacturer’s maintenance manual, maintenance procedures and/or maintenance checklists (if any) shall be kept on site.

11. Compliance. Nothing contained within this permit shall be construed as allowing the violation of any local, state or federal rules, regulations, air quality standards or increments.

12. Severability. In the event that any condition herein is determined to be invalid, all other conditions shall remain in force.

13. Conflict Between Permits. The requirements or limits that are more protective of air quality shall apply if any conflict arises between the requirements and limits of this permit and any other permitting actions associated with the equipment permitted herein.

14. Access to Records and Facilities. As to any condition that requires for its effective enforcement the inspection of records or facilities by the District or its agents, the permittee shall make such records available or provide access to such facilities upon notice from the District. Access shall mean access consistent with California Health and Safety Code Section 41510 and Clean Air Act Section 114A.

Permit to Operate 08390 - R11

Page 10 of 14 ends

15. Equipment Identification. Identifying tag(s) or name plate(s) shall be displayed on the equipment to show manufacturer, model number, and serial number. The tag(s) or plate(s) shall be affixed to the equipment in a permanent and conspicuous position.

16. Emission Factor Revisions. The District may update the emission factors for any calculation based on USEPA AP-42 or District emission factors at the next permit modification or permit reevaluation to account for USEPA and/or District revisions to the underlying emission factors.

17. Nuisance. Except as otherwise provided in Section 41705 of the California H&SC, no person shall discharge from any source whatsoever such quantities of air contaminants or other material which cause injury, detriment, nuisance, or annoyance to any considerable number of persons or to the public, or which endanger the comfort, repose, health, or safety of any such persons or the public, or which cause, or have a natural tendency to cause, injury or damage to business or property.

18. Grounds for Revocation. Failure to abide by and faithfully comply with this permit or any Rule, Order, or Regulation may constitute grounds for revocation pursuant to California Health & Safety Code Section 42307 et seq.

19. Transfer of Owner/Operator. This permit is only valid for the owner and operator listed on this permit unless a Transfer of Owner/Operator application has been applied for and received by the District. Any transfer of ownership or change in operator shall be done in a manner as specified in District Rule 203. District Form –01T and the appropriate filing fee shall be submitted to the District within 30 days of the transfer.

20. Documents Incorporated by Reference. The documents listed below, including any District-approved updates thereof, are incorporated herein by reference and shall have the full force and effect of a permit condition for this permit. These documents shall be implemented for the life of the Project and shall be made available to District inspection staff upon request. a. Inspection and Maintenance Plan (approved January 29, 2015) b. Emission and Digester Gas Monitoring Plan (approved January 29, 2015)

AIR POLLUTION CONTROL OFFICER
DATE
September 29, 2021
Permit to Operate 08390 - R11

Page 11 of 14 ends

Attachments:
- Table 1 – Permitted Emission Limits
- Table 2 – Emission Standards
- Table 3 – Heat Input Limits
- Table 4 – Device Specific Requirements Summary
- Table 5 – Source Testing Requirements
- Permit Equipment List(s)
- Permit Evaluation for Permit to Operate 08390 - R11
Notes:
- Reevaluation Due Date: September 2024
- Stationary sources are subject to an annual emission fee (see Fee Schedule B-3 of Rule 210). - Annual reports are due by March 1st of each year.
- This permit supersedes Reeval 8390-R10 and PTO Mod 8390-02. \\sbcapcd.org\shares\Groups\ENGR\WP\Landfills & WWT\02077 City of Santa Maria WWTP\Reevals\Reeval 8390-R11\Reeval 08390 R11 - Final Permit - 9-28-2021.docx Permit to Operate 08390 - R11

Page 12 of 14 ends

NOx ROC CO SOx PM PM10 PM2.5

7.56 9.60 41.11 24.91 2.22 2.22 2.22

1.38 1.75 7.50 4.55 0.41 0.41 0.41

19.51 24.78 106.16 64.33 5.74 5.74 5.74

3.56 4.52 19.37 11.74 1.05 1.05 1.05

0.15 0.20 0.84 0.27 0.05 0.05 0.05

0.03 0.04 0.15 0.05 0.01 0.01 0.01

0.15 0.20 0.84 0.27 0.05 0.05 0.05

0.03 0.04 0.15 0.05 0.01 0.01 0.01

2.20 0.33 17.86 13.51 0.45 0.45 0.45

0.40 0.06 3.26 2.46 0.08 0.08 0.08

2.20 0.33 17.86 0.96 0.45 0.45 0.45

0.40 0.06 3.26 0.18 0.08 0.08 0.08

0.24 0.01

22.02 25.74 125.70 78.38 6.28 6.28 6.28

4.02 4.66 22.94 14.30 1.15 1.15 1.15
Notes:

2. Boiler (Propane)'s potential to emit is not included in the permit PTE total because the boiler is either fired on digester gas or propane. The NOx, ROC, CO, SOx, PM, PM10, and PM2.5 potential to emit while fired on digester gas are equal to or greater than when the boiler is fired on propane.

TPY
Boiler (Propane)
lb/day

1. Flare 1's potential to emit is not included in the permit PTE total because the combined heat input limit for the flares is 11.955 MMBtu/hr (Conditions 2.a's limit of 12.145 MMBtu/hr - lb/day
TPY
lb/day
TPY
Totals
lb/day
TPY
Table 1: Permit Potential to Emit
Flare 1
Iron Sponge Scrubber Fugitive Components
Flare 2
lb/day
TPY
Equipment
Flare 1 Pilot
Flare 2 Pilot
Boiler (Digester Gas)
lb/day
TPY
lb/day
TPY
lb/day
TPY
factors for all pollutants.

Flare 1's pilot heat input of 0.095 MMBtu/hr - Flare 2 pilot's heat input of 0.095 MMBtu/hr), which is equal to Flare 2's heat input. While both Flare 1 and Flare 2 are permitted to operation simultaneously, for the ease of emission calculations, only Flare 2's potential to emit was included since the resulting PTE would be identical regardless of how the heat input is divided between Flare 1 and Flare 2. Note that the flares have identical emission Permit to Operate 08390 - R11

Page 13 of 14 ends

TABLE 2. EMISSION STANDARDS
Device
ID # NOx CO Units Basis
104098 30 400 ppmvd @ 3% O2 Rule 361

TABLE 3. HEAT INPUT LIMITS
TABLE 4. DEVICE SPECIFIC REQUIREMENTS SUMMARY
Table Notes:
(a) Units subject to Rule 342 may comply with either the ppmvd or lb/MMBtu standards of the Rule. (b) NOx as NO2, SOx as SO2, lb/day = pounds per day, tpy = tons per year (c) Device ID # from permit equipment list.
(d) Emission data that round down to 0.00 has been set to a default of 0.01.

Device
ID # Fuel MMBtu/hr MMBtu/day MMBtu/yr
104098 Digester Gas, Propane 2.510 60.240 21,987.600
Device
ID #
Applicable
Rule
Source
Testing Tune-Ups Fuel Use Method
Low Use
Exemption BACT
104098 R361 Biennial Conditional Fuel Meter No No
Permit to Operate 08390 - R11

Page 14 of 14 ends

TABLE 5. SOURCE TESTING REQUIREMENTS
Emission &
Limit Test
Points
Pollutants Parameters Test Methods (a)
Boiler 1 Stack
(b)(c)(d)(e)
NOx ppmv, lb/hr EPA Method 7E, CARB 100
CO ppmv, lb/hr EPA Method 10, CARB 100
Sampling Point Det. EPA Method 1
Stack Gas Flow Rate EPA Method 2 or 19
O2, CO2, Dry MW EPA Method 3
Moisture Content EPA Method 4
Stack Temperature oF Calibrated Thermocouple
Fuel Gas Fuel Gas Flow Rate Fuel Gas Meter (f)
Higher Heating Value Btu/lb ASTM D 1826 or 3588
Total Sulfur Content ppmw ASTM D 1072 or 5504 (g)
Gas Composition CHONS%, F-factor ASTM 1945
Notes:
(a) Alternative methods may be acceptable on a case-by-case basis. (b) The emission rates shall be based on EPA Methods 2 and 4, or Method 19 along with the heat input rate. (c) For NOx, CO and O2 a minimum of three 30-minute runs shall be obtained during each test. (d) See Tables 1 and 2 for the emission standards to be measured against during the test. Measured NOx and CO shall not exceed the limit specified in the applicable Rule (e.g., Rule 361, Rule 342). (e) All emission determinations shall be made in the as-found operating condition, at the maximum attainable firing rate to be approved by the source test plan. No determination of compliance shall be established within two hours after a continuous period in which fuel flow to the unit is shut off for 30 minutes or longer.
(f) Fuel meter shall meet the calibration requirements prior to testing. (g) Total sulfur content fuel samples shall be obtained using EPA Method 18 with Tedlar Bags (or equivalent) equipped with Teflon tubing and fittings. Turnaround time for laboratory analysis of these samples shall be no more than 24 hours from sampling.

Equipment List for Permit to Operate 08390 - R11

Page 1 of 5 ends

PERMIT EQUIPMENT LIST - TABLE A
Reeval 08390 R11 / FID: 02077 City of Santa Maria WWTP / SSID: 02077

A PERMITTED EQUIPMENT
1 Anaerobic Digesters

1.1 Anaerobic Digester 1
Device ID # 104084 Device Name Anaerobic Digester 1
Rated Heat Input Physical Size 92,876.00 Cubic Feet
Manufacturer Operator ID
Model Serial Number
Location Note
Device
Description
Standard operating pressure of 5.5 - 10.5" water column, pressure alarm sounds at 12 - 15" water column, equipped with 4" Varec Model 2010B PRV (Serial Number: 15122407) set at pressure of 15" water column and vacuum of 2" water column

1.2 Anaerobic Digester 2
Device ID # 104085 Device Name Anaerobic Digester 2
Rated Heat Input Physical Size 47,112.00 Cubic Feet
Manufacturer Operator ID
Model Serial Number
Location Note
Device
Description
Standard operating pressure of 5.5 - 10.5" water column, pressure alarm sounds at 12 - 15" water column, equipped with 4" Varec Model 2010B PRV (Serial Number: 15122408) set at pressure of 15" water column and vacuum of 2" water column
Equipment List for Permit to Operate 08390 - R11

Page 2 of 5 ends

1.3 Anaerobic Digester 3
Device ID # 104629 Device Name Anaerobic Digester 3
Rated Heat Input Physical Size 47,112.00 Cubic Feet
Manufacturer Operator ID
Model Serial Number
Location Note
Device
Description
Standard operating pressure of 5.5 - 10.5" water column, pressure alarm sounds at 12 - 15" water column, equipped with 4" Varec Model 2010B PRV (Serial Number: 15122409) set at pressure of 15" water column and vacuum of 2" water column

1.4 Anaerobic Digester 4
Device ID # 112446 Device Name Anaerobic Digester 4
Rated Heat Input Physical Size 82,300.00 Cubic Feet
Manufacturer Operator ID
Model Serial Number
Location Note
Device
Description
Standard operating pressure of 5.5 - 10.5" water column, pressure alarm sounds at 12 - 15" water column, equipped with two Varec Model 5810B62 6" PSVs set at 12 inches of water column, equipped with Varec Model 450 6" flame arrestor
2 Waste Gas Flare 1
Device ID # 114679 Device Name Waste Gas Flare 1
Rated Heat Input 4.725 MMBtu/Hour Physical Size 4.725 MMBtu/Hour Manufacturer Varec Operator ID
Model 239-A Serial Number
Location Note
Device
Description
Waste gas design capacity of 4.630 MMBtu/hr (0.1852 MMscf/day of 600 Btu/scf gas), pilot gas design capacity of 0.095 MMBtu/hr (0.00009 MMscf/day of propane), dimensions: 4” D x 11’ H, equipped with an automatic reigniting pilot fired on propane, flare tip equipped with a wind shroud
Equipment List for Permit to Operate 08390 - R11

Page 3 of 5 ends

3 Waste Gas Flare 2
Device ID # 008696 Device Name Waste Gas Flare 2
Rated Heat Input 12.050 MMBtu/Hour Physical Size 12.050 MMBtu/Hour Manufacturer Varec Operator ID
Model 244W Serial Number
Location Note
Device
Description
Waste gas design capacity of 11.955 MMBtu/hr (0.4782 MMscf/day of 600 Btu/scf gas), pilot gas design capacity of 0.095 MMBtu/hr (0.00009 MMscf/day of propane), dimensions: 6” D x 15’ H, equipped with an automatic reigniting pilot fired on propane, flare tip equipped with a wind shroud
4 Hydrogen Sulfide Ambient Monitoring System
Device ID # 104086 Device Name Hydrogen Sulfide
Ambient Monitoring
System
Rated Heat Input Physical Size
Manufacturer Operator ID
Model Serial Number
Location Note
Device
Description
Hydrogen sulfide ambient monitoring system with three remote sensors 5 Iron Sponge Scrubber
Device ID # 104089 Device Name Iron Sponge Scrubber
Rated Heat Input Physical Size
Manufacturer Operator ID
Model Serial Number
Location Note
Device
Description
Dimensions: 10’ D x 7’ H, welded construction with a manway cover and vessel cover bolted in place, contains 5’ of wood shavings impregnated with iron oxide supported on a removable tray
Equipment List for Permit to Operate 08390 - R11

Page 4 of 5 ends

6 Ferrous Chloride Injection System
Device ID # 104087 Device Name Ferrous Chloride
Injection System
Rated Heat Input Physical Size 0.25 Horsepower
(Electric Motor)
Manufacturer Operator ID
Model Serial Number
Location Note
Device
Description
Hydrogen sulfide control system, ferrous chloride injection system equipped with a pump powered by a 0.25 horsepower electric motor 7 Boiler 1
Device ID # 104098 Device Name Boiler 1
Rated Heat Input 2.510 MMBtu/Hour Physical Size 2.510 MMBtu/Hour Manufacturer Cleaver Brooks Operator ID
Model CB 700-60 Serial Number L-103264
Location Note
Device
Description
Fueled by digester gas, propane gas used as backup, equipped with a Cleaver Brooks low emission kit and a fuel meter, complies with the Rule 361 emission requirements of 30 ppmv NOx at 3% oxygen and 400 ppmv CO at 3% oxygen
Equipment List for Permit to Operate 08390 - R11

Page 5 of 5 ends

B EXEMPT EQUIPMENT
1 Aerobic Equipment
Device ID # 104100 Device Name Aerobic Equipment
Rated Heat
Input
Physical Size
Manufacturer Operator ID
Model Serial Number
Part 70 Insig? No District Rule Exemption:
202.L.11 Aerobic Wastewater Treatment Equipment
Location Note
Device
Description
Aerobic equipment not used for digester gas combustion or the control of air emissions
2 Boiler 2
Device ID # 104101 Device Name Boiler 2
Rated Heat
Input

0.960 MMBtu/Hour Physical Size
Manufacturer Operator ID
Model Serial Number
Part 70 Insig? No District Rule Exemption:
202.G.1 Combustion Equipment <= 2 MMBtu/hr
Location Note
Device
Description
Installed prior to October 17, 2003, fired on propane gas

PERMIT EVALUATION FOR
PERMIT TO OPERATE 08390 - R11

Page 1 of 4 ends

1.0 BACKGROUND

1.1 General: This PTO is the triennial reevaluation of the Permit to Operate and contains an updated rule review. This reevaluation incorporates the updated equipment list description and emission calculations found in PTO Mod 8390-02.

1.2 Permit History:

PERMIT FINAL ISSUED PERMIT DESCRIPTION
Reeval 08390 R10 10/16/2018 Permit reevaluation for wastewater treatment plant.

PTO Mod 08390 02 07/05/2019 Modify permit to comply with Rule 361 ATC 15547 01/11/2021 Two 2014 Deutz prime engines rated at 74 bhp each.

Reeval 13046 R4 03/05/2021 Permit reevaluation for E/S diesel-fired IC engine.

1.3 Compliance History:

VIOLATION TYPE NUMBER ISSUE DATE DESCRIPTION OF VIOLATION NOV 11453 01/11/2019 Violation of Rule 206

2.0 ENGINEERING ANALYSIS

2.1 Equipment/Processes: This facility treats wastewater for the City of Santa Maria. The sludge from the biochemical treatment process is anaerobically decomposed in the digesters. The gases produced during this process are burned in a boiler or one of two flares. A ferrous chloride injection system controls hydrogen sulfide production, with an iron sponge scrubber used as necessary for further hydrogen sulfide control.

2.2 Emission Controls: Digester gas is burned in the waste gas flare. A ferrous chloride injection system controls hydrogen sulfide production. An iron sponge scrubber is used in addition to the ferrous chloride injection system if further gas treatment is necessary. Boiler 1 was source tested and certified to meet the 30 ppmv NOx and 400 ppmv CO emissions standards of Rule 361.

2.3 Emission Factors: Emission factors are documented in the Attachment A.

2.4 Reasonable Worst Case Emission Scenario: The operating scenario is summarized as follows:

Worst Case:
• Maximum digester gas flow to Flare 1 = 185,200 scf/day • Maximum digester gas flow to Flare 2 = 478,200 scf/day

PERMIT EVALUATION FOR
PERMIT TO OPERATE 08390 - R11

Page 2 of 4 ends

• Propane pilot gas flow rate to Flares 1 = 900 scf/day • Propane pilot gas flow rate to Flares 2 = 900 scf/day • Flare pilots are continuously operated
• Maximum combined heat input to the waste gas flares and pilots is 12.145 MMBtu/hr, 291.480 Btu/day, and 106,390.200 MMBtu/year
• Maximum heat input to the boiler is 2.510 MMBtu/hr
• Boiler is fired on either digester gas or propane
• Worst-case emissions from the boiler occur when combusting digester gas. • Total sulfur content of digester gas shall not exceed 796 ppmv (as H2S) • High heat value (HHV) of digester gas = 600 Btu/scf
• Total sulfur content of propane gas shall not exceed 239 ppmv (as H2S) • High heat value (HHV) of propane = 2,522 Btu/scf
• Plant operates 24 hours/day, 8,760 hours/year

2.5 Emission Calculations: Detailed emission calculation spreadsheets may be found in the Attachment A. These emissions define the Potential to Emit for the permitted equipment.

2.6 Special Calculations: There are no special calculations.

2.7 BACT Analyses: Best Available Control Technology was not required for this project.

2.8 Enforceable Operational Limits: The permit has enforceable operating conditions that ensure the equipment is operated properly.

2.9 Monitoring Requirements: Monitoring of the equipment’s operational limits is required to ensure that these are enforceable.

2.10 Recordkeeping and Reporting Requirements: The permit requires that the data which is monitored be recorded and reported to the District.

3.0 REEVALUATION REVIEW

3.1 Compliance Summary: Since the last permit reevaluation, this facility has been inspected on November 21, 2019.

3.2 Notes from Inspector: No notes from the inspector.

3.3 Changes to Applicable Rules (or new rules): None.

3.4 Changes/Revisions to Engineering Analysis (EF updates, etc.): There have been no changes to the Engineering Analysis.

3.5 Changes/Revisions to Monitoring, Recordkeeping & Reporting: Monitoring, recordkeeping and reporting requirements from PTO Mod 8390-02 have been incorporated into this permit.

PERMIT EVALUATION FOR
PERMIT TO OPERATE 08390 - R11

Page 3 of 4 ends

3.6 Other Changes/Corrections Made: The permit reflects the most current template.

4.0 REGULATORY REVIEW

4.1 Partial List of Applicable Rules:

Rule 201. Permits Required
Rule 202. Exemptions to Rule 201
Rule 205. Standards for Granting Permits
Rule 301. Circumvention
Rule 302. Visible Emissions
Rule 303. Nuisance
Rule 304. Particulate Matter - Northern Zone
Rule 306. Dust and Fumes - Northern Zone
Rule 311. Sulfur Content of Fuels
Rule 360. Boilers, Water Heaters, and Process Heaters (0.075 – 2 MMBtu/hr) Rule 361. Small Boilers, Steam Generators, and Process Heaters Rule 801. New Source Review- Definitions and General Requirements Rule 802. New Source Review
Rule 809. Federal Minor Source New Source Review
Rule 810. Federal Prevention of Significant Deterioration

4.2 Rules Requiring Review:

4.2.1 Rule 202 - Exemptions to Rule 201: Section G.1.b exempts combustion equipment with a maximum heat input less than 2.000 MMBtu/hour when fired exclusively on liquefied petroleum gas, which meets Gas Processors Association Standards. Boiler 2 fired on propane satisfies this requirement.

4.2.2 Rule 311 - Sulfur Content of Fuels: Section C of this rule limits burning, within the Northern Zone of Santa Barbara County, of any gaseous fuel containing sulfur compounds in excess of 50 grains per 100 cubic feet (calculated as hydrogen sulfide at standard conditions) or any liquid or solid fuel having a sulfur content in excess of 0.5 percent by weight. This rule applies to the digester gas burned in the flares and any other equipment at the facility.

5.0 AQIA
The project is not subject to the Air Quality Impact Analysis requirements of Regulation VIII.

6.0 OFFSETS/ERCs

6.1 Offsets: The emission offset thresholds of Regulation VIII are not exceeded.

6.2 ERCs: This source does not generate emission reduction credits.

PERMIT EVALUATION FOR
PERMIT TO OPERATE 08390 - R11

Page 4 of 4 ends

7.0 AIR TOXICS
An air toxics health risk assessment was not performed for this permitting action.

8.0 CEQA / LEAD AGENCY
This project is exempt from CEQA pursuant to the Environmental Review Guidelines for the Santa Barbara County APCD (revised April 30, 2015). Appendix A (APCD Projects Exempt from CEQA and Equipment or Operations Exempt from CEQA) provides an exemption specifically for permits to operate and reevaluations thereof. No further action is necessary.

9.0 SCHOOL NOTIFICATION
A school notice pursuant to the requirements of Health and Safety Code Section 42301.6 was not required.

10.0 PUBLIC and AGENCY NOTFICATION PROCESS/COMMENTS ON DRAFT PERMIT

10.1 This project was not subject to public notice.

10.2 The permittee had no comments on the draft permit.

11.0 FEE DETERMINATION
Fees for the District’s work efforts are assessed on a fee basis. The Project Code is 520000 (External Combustion). See Attachment C for the fee calculations.

12.0 RECOMMENDATION
It is recommended that this permit be granted with the conditions as specified in the permit.

Kevin Brown September 28, 2021 9/28/2021
AQ Engineer/Technician Date Supervisor Date

13.0 ATTACHMENT(S)
A. Emission Calculations
B. IDS Tables
C. Fee Statement
Permit to Operate 08390 - R11

ATTACHMENT A
Emission Calculations
Attachment: A-1
Permit Number: Reeval 8390-R11
Facility: Santa Maria WWTP
Fuel Information
Data Value Units Reference
Flare Throughput……………………. 0.185 MMscf/day
Gas Heat Content………………….. 600 Btu/scf
Sulfur Content………………………. 796 ppmv as H2S
Heat Input Data
Value Units Reference

4.630 MMBtu/hour Daily divided by 24 hr/day
111.120 MMBtu/day Permit Application
40,558.800 MMBtu/year Daily times 365 days/yr
Emission Factors
Pollutant lb/MMBtu Reference
NOx 0.0680
ROC 0.0864 APCD Emission Factor Guidance (ver 1.1, 7/13/1998) CO 0.3700
SOx 0.2242
PM 0.0200
PM10 0.0200
PM2.5 0.0200
Pollutant lb/day TPY
NOx 7.56 1.38
ROC 9.60 1.75
CO 41.11 7.50
SOx 24.91 4.55
PM 2.22 0.41
PM10 2.22 0.41
PM2.5 2.22 0.41
Processed By: KMB Date: August 10, 2021
FLARE 1 EMISSION CALCULATIONS (Ver. 2.0)
Flare Potential to Emit
Permit Application
Permit Application
Permit Application
AP-42, Table 13.5-1
Mass Balance Calculation

SBCAPCD
AP-42, Chapter 1.4
AP-42, Chapter 1.4
AP-42, Table 13.5-1
Permit to Operate 08390 - R11

ATTACHMENT A
Emission Calculations
Attachment: A-2
Permit Number: Reeval 8390-R11
Facility: Santa Maria WWTP
Fuel Information
Data Value Units Reference
Flare Throughput……………………. 0.478 MMscf/day
Gas Heat Content………………….. 600 Btu/scf
Sulfur Content………………………. 796 ppmv as H2S
Heat Input Data
Value Units Reference

11.955 MMBtu/hour Daily divided by 24 hr/day
286.920 MMBtu/day Permit Application
104,725.800 MMBtu/year Daily times 365 days/yr
Emission Factors
Pollutant lb/MMBtu Reference
NOx 0.0680
ROC 0.0864 APCD Emission Factor Guidance (ver 1.1, 7/13/1998) CO 0.3700
SOx 0.2242
PM 0.0200
PM10 0.0200
PM2.5 0.0200
Pollutant lb/day TPY
NOx 19.51 3.56
ROC 24.78 4.52
CO 106.16 19.37
SOx 64.33 11.74
PM 5.74 1.05
PM10 5.74 1.05
PM2.5 5.74 1.05
Processed By: KMB Date: August 10, 2021
AP-42, Table 13.5-1
FLARE 2 EMISSION CALCULATIONS (Ver. 2.0)
Permit Application
Permit Application
Permit Application
AP-42, Table 13.5-1
Mass Balance Calculation

SBCAPCD
AP-42, Chapter 1.4
AP-42, Chapter 1.4
Flare Potential to Emit
Permit to Operate 08390 - R11

ATTACHMENT A
Emission Calculations
Attachment: A-3
Permit Number: Reeval 8390-R11
Facility: Santa Maria WWTP
Fuel Information
Data Value Units Reference
Flare Throughput……………………. 0.0009 MMscf/day
Gas Heat Content………………….. 2,522 Btu/scf
Sulfur Content………………………. 239 ppmv as H2S
Heat Input Data
Value Units Reference

0.095 MMBtu/hour Daily divided by 24 hr/day

2.270 MMBtu/day Permit Application
828.477 MMBtu/year Daily times 365 days/yr
Emission Factors
Pollutant lb/MMBtu Reference
NOx 0.0680
ROC 0.0864 APCD Emission Factor Guidance (ver 1.1, 7/13/1998) CO 0.3700
SOx 0.1206
PM 0.0200
PM10 0.0200
PM2.5 0.0200
Pollutant lb/day TPY
NOx 0.15 0.03
ROC 0.20 0.04
CO 0.84 0.15
SOx 0.27 0.05
PM 0.05 0.01
PM10 0.05 0.01
PM2.5 0.05 0.01
Processed By: KMB Date: August 10, 2021

SBCAPCD
AP-42, Chapter 1.4
AP-42, Chapter 1.4
Flare Potential to Emit
FLARE 1 PILOT EMISSION CALCULATIONS (Ver. 2.0)
Permit Application
Permit Application
Permit Application
AP-42, Table 13.5-1
AP-42, Table 13.5-1
Mass Balance Calculation
Permit to Operate 08390 - R11

ATTACHMENT A
Emission Calculations
Attachment: A-3
Permit Number: Reeval 8390-R11
Facility: Santa Maria WWTP
Fuel Information
Data Value Units Reference
Flare Throughput……………………. 0.0009 MMscf/day
Gas Heat Content………………….. 2,522 Btu/scf
Sulfur Content………………………. 239 ppmv as H2S
Heat Input Data
Value Units Reference

0.095 MMBtu/hour Daily divided by 24 hr/day

2.270 MMBtu/day Permit Application
828.477 MMBtu/year Daily times 365 days/yr
Emission Factors
Pollutant lb/MMBtu Reference
NOx 0.0680
ROC 0.0864 APCD Emission Factor Guidance (ver 1.1, 7/13/1998) CO 0.3700
SOx 0.1206
PM 0.0200
PM10 0.0200
PM2.5 0.0200
Pollutant lb/day TPY
NOx 0.15 0.03
ROC 0.20 0.04
CO 0.84 0.15
SOx 0.27 0.05
PM 0.05 0.01
PM10 0.05 0.01
PM2.5 0.05 0.01
Processed By: KMB Date: August 10, 2021
Mass Balance Calculation

SBCAPCD
AP-42, Chapter 1.4
AP-42, Chapter 1.4
Flare Potential to Emit
AP-42, Table 13.5-1
FLARE 2 PILOT EMISSION CALCULATIONS (Ver. 2.0)
Permit Application
Permit Application
Permit Application
AP-42, Table 13.5-1
Permit to Operate 08390 - R11

ATTACHMENT A
Emission Calculations
Attachment: A-5
Permit Number: Reeval 8390-R11
Facility: Santa Maria WWTP
Heater Input Data
Information Value Units Reference
Maximum Hourly Heat Input…………… 2.510 MMBtu/hr
Daily Operating Schedule...................... 24 hrs/day Maximum Daily Heat Input……………. 60.240 MMBtu/day Calculated value Yearly Load Factor (%)......................................... 100 % Maximum Annual Heat Input………….. 21,987.600 MMBtu/yr Calculated value Fuel Information
Information Value Units Reference
Fuel........................................................... Digester Gas N/A High Heating Value......................................... 600 Btu/scf Sulfur Content of Fuel.................................... 796.00 ppmvd as H2S Emission Factors
Pollutant Value Units Reference
NOx Emission Factor...................................... 0.0365 lb/MMBtu ROC Emission Factor................................. 0.0054 lb/MMBtu CO Emission Factor............................................ 0.2965 lb/MMBtu SOx Emission Factor..................................... 0.2242 lb/MMBtu PM Emission Factor ........................................... 0.0075 lb/MMBtu PM10 Emission Factor.......................................... 0.0075 lb/MMBtu PM2.5 Emission Factor........................................... 0.0075 lb/MMBtu Pollutant lb/day TPY
NOx 2.20 0.40
ROC 0.33 0.06
CO 17.86 3.26
SOx 13.51 2.46
PM 0.45 0.08
PM10 0.45 0.08
PM2.5 0.45 0.08
Processed By: Date: August 10, 2021
AP-42, Section 1.4
KMB
BOILER FIRED ON DIGESTER GAS EMISSION CALCULATIONS (Ver. 7.0) Boiler/Steam Generator Potential to Emit
Permit Application
Permit Application
Permit Application
Permit Application
Permit Application
Permit Application
Rule 361 (30 ppmv @ 3% O2)
AP-42, Section 1.4
Rule 361 (400 ppmv @ 3% O2)
Mass Balance Calculation
AP-42, Section 1.4
AP-42, Section 1.4
Permit to Operate 08390 - R11

ATTACHMENT A
Emission Calculations
Attachment: A-6
Permit Number: Reeval 8390-R11
Facility: Santa Maria WWTP
Heater Input Data
Information Value Units Reference
Maximum Hourly Heat Input…………… 2.510 MMBtu/hr
Daily Operating Schedule...................... 24 hrs/day Maximum Daily Heat Input……………. 60.240 MMBtu/day Calculated value Yearly Load Factor (%)......................................... 100 % Maximum Annual Heat Input………….. 21,987.600 MMBtu/yr Calculated value Fuel Information
Information Value Units Reference
Fuel........................................................... Propane N/A High Heating Value......................................... 2,522 Btu/scf Sulfur Content of Fuel.................................... 239.00 ppmvd as H2S Emission Factors
Pollutant Value Units Reference
NOx Emission Factor...................................... 0.0365 lb/MMBtu ROC Emission Factor................................. 0.0054 lb/MMBtu CO Emission Factor............................................ 0.2965 lb/MMBtu SOx Emission Factor..................................... 0.0160 lb/MMBtu PM Emission Factor ........................................... 0.0075 lb/MMBtu PM10 Emission Factor.......................................... 0.0075 lb/MMBtu PM2.5 Emission Factor........................................... 0.0075 lb/MMBtu Pollutant lb/day TPY
NOx 2.20 0.40
ROC 0.33 0.06
CO 17.86 3.26
SOx 0.96 0.18
PM 0.45 0.08
PM10 0.45 0.08
PM2.5 0.45 0.08
Processed By: Date: August 10, 2021
AP-42, Section 1.4
AP-42, Section 1.4
Boiler/Steam Generator Potential to Emit
KMB
Permit Application
Rule 361 (30 ppmv @ 3% O2)
AP-42, Section 1.4
Rule 361 (400 ppmv @ 3% O2)
Mass Balance Calculation
AP-42, Section 1.4
Permit Application
BOILER FIRED ON PROPANE EMISSION CALCULATIONS (Ver. 7.0) Permit Application
Permit Application
Permit Application
Permit Application
Permit to Operate 08390 - R11

ATTACHMENT B
IDS Tables

PERMIT POTENTIAL TO EMIT
NOx ROC CO SOx PM PM10 PM2.5
lb/day 22.02 25.74 125.70 78.38 6.28 6.28 6.28
lb/hr
TPQ
TPY 4.02 4.66 22.94 14.30 1.15 1.15 1.15

FACILITY POTENTIAL TO EMIT
NOx ROC CO SOx PM PM10 PM2.5
lb/day 83.88 29.68 179.00 78.47 7.43 7.43 7.43
lb/hr
TPQ
TPY 6.27 4.79 25.26 14.31 1.16 1.16 1.16

STATIONARY SOURCE POTENTIAL TO EMIT
NOx ROC CO SOx PM PM10 PM2.5
lb/day 83.88 29.68 179.00 78.47 7.43 7.43 7.43
lb/hr
TPQ
TPY 6.27 4.79 25.26 14.31 1.16 1.16 1.16
Notes:
(1) Emissions in these tables are from IDS.
(2) Because of rounding, values in these tables shown as 0.00 are less than 0.005, but greater than zero.

Permit to Operate 08390 - R11

ATTACHMENT C
Fee Statement

FEE STATEMENT
PTO No. 08390 - R11
FID: 02077 City of Santa Maria WWTP / SSID: 02077
Device Fee
Device
No. Device Name
Fee
Schedule
Qty of Fee
Units
Fee
per
Unit
Fee
Units
Max or
Min. Fee
Apply?
Number
of Same
Devices
Pro Rate
Factor
Device
Fee
Penalty
Fee?
Fee
Credit
Total Fee
per Device
104084 Anaerobic Digester 1 A6 694.761 4.33
Per 1000
gallons No 1 1.000 3,008.32 0.00 0.00 3,008.32
104085 Anaerobic Digester 2 A6 352.422 4.33
Per 1000
gallons No 1 1.000 1,525.99 0.00 0.00 1,525.99
104629 Anaerobic Digester 3 A6 352.422 4.33
Per 1000
gallons No 1 1.000 1,525.99 0.00 0.00 1,525.99
112446 Anaerobic Digester 4 A6 615.647 4.33
Per 1000
gallons No 1 1.000 2,665.75 0.00 0.00 2,665.75
114679 Waste Gas Flare 1 A3 4.725 566.34
Per 1 million
Btu input No 1 1.000 2,675.96 0.00 0.00 2,675.96
008696 Waste Gas Flare 2 A3 12.050 566.34
Per 1 million
Btu input No 1 1.000 6,824.40 0.00 0.00 6,824.40
104086 Hydrogen Sulfide Ambient Monitoring System A1.a 1.000 75.49 Per equipment No 1 1.000 75.49 0.00 0.00 75.49 104089 Iron Sponge Scrubber A1.a 1.000 75.49 Per equipment No 1 1.000 75.49 0.00 0.00 75.49 104087 Ferrous Chloride Injection System A2 0.250 39.14 Per total rated
hp Min 1 1.000 75.00 0.00 0.00 75.00
104098 Boiler 1 A3 2.510 566.34
Per 1 million
Btu input No 1 1.000 1,421.51 0.00 0.00 1,421.51
Device Fee Sub-Totals = $19,873.89 $0.00 $0.00
Device Fee Total = $19,873.89
Permit Fee
Fee Based on Devices $19,873.89
Fee Statement Grand Total = $19,873
Notes:
(1) Fee Schedule Items are listed in District Rule 210, Fee Schedule "A". (2) The term "Units" refers to the unit of measure defined in the Fee Schedule.

Certified Mail
Return Receipt Requested
Re: Notice of Final Permit to Operate 08390 - R11 Issuance Fee Due: $ 19,873
Dear Ms. Griffith:

Enclosed is the final Permit to Operate (PTO) No. 08390 - R11 for a wastewater treatment plant at 601 Black Road in Santa Maria.

Please carefully review the enclosed documents to ensure that they accurately describe your facility and that the conditions are acceptable to you.

This PTO is for the triennial (every three years) reevaluation of existing air quality permits at your facility, as required by Air Pollution Control District (District) Rule 201. This permit may contain new conditions added to ensure compliance with current laws and updated regulations.

You should become familiar with all District rules pertaining to your facility. This permit does not relieve you of any requirements to obtain authority or permits from other governmental agencies.

This permit requires you to:
• Pay a fee of $19,873, which is due immediately and is considered late after 30 calendar days from the date stamped on the permit. Pursuant to District Rule 210.IV.B, no appeal shall be heard unless all fees have been paid. See the attached invoice for more information. • Follow the conditions listed on your permit. Pay careful attention to the recordkeeping and reporting requirements.
• Ensure that a copy of the enclosed permit is posted or kept readily available near the permitted equipment.
• Promptly report changes in ownership, operator, or your mailing address to the District.

Alexandra Griffith
City of Santa Maria
2065 E. Main Street
Santa Maria, CA 93454
FID: 02077
Permit: P 08390 - R11
SSID: 02077
September 29, 2021 9171 9690 0935 0268 3953 34
If you are not satisfied with the conditions of this permit, you have thirty (30) calendar days from the date of this permit issuance notice to appeal this permit to the Air Pollution Control District Hearing Board (ref: California Health and Safety Code, §42302.1). Any contact, discussions, or meetings with District staff regarding the terms of this permit during or after permit issuance do not constitute an appeal under Rule 209 or the California H&SC and will not stop or alter the 30-day appeal period. Only a formal application to the Hearing Board can initiate an appeal. You may contact the Clerk of the Hearing Board for specific information concerning appeal initiation and procedures.

Please include the facility identification (FID) and permit numbers as shown at the top of this letter on all correspondence regarding this permit. If you have any questions, please contact Kevin Brown of my staff at (805) 961-8826.

Sincerely,
David Harris, Division Manager
Engineering Division
enc: Final PTO 08390 - R11
Final Permit Evaluation
Invoice # R 08390 - R11

cc: City of Santa Maria WWTP 02077 Project File
Engr Chron File
Accounting (Invoice only)
Kevin Brown (Cover letter only)
\\sbcapcd.org\shares\Groups\ENGR\WP\Landfills & WWT\02077 City of Santa Maria WWTP\Reevals\Reeval 8390-R11\Reeval 08390 R11 - Final Letter - 9-28-2021.docx 260 N. San Antonio Rd, Suite A
Santa Barbara, CA 93110-1315
Invoice: R 08390 - R11
Date:

Terms: Net 30 Days
520000/6600/3282
\\sbcapcd.org\shares\Groups\ENGR\WP\Landfills & WWT\02077 City of Santa Maria WWTP\Reevals\Reeval 8390-R11\Reeval 08390 R11 - Invoice - 8-10- 2021.docx District Federal TIN 77-0384167

INVOICE
BILL TO: FACILITY:

Accounts Payable
City of Santa Maria (000361)
2065 E. Main Street
Santa Maria, CA 93454
City of Santa Maria WWTP
02077
601 Black Road
Santa Maria
Permit: Permit to Operate (PTO) No. 08390 - R11
Fee Type: Permit Reevaluation Fee (see the Fee Statement in your permit for a breakdown of the fees) Amount Due: $ 19,873

REMIT PAYMENTS TO THE ABOVE ADDRESS
Please indicate the invoice number R 08390 - R11
on your remittance.

IF YOU HAVE ANY QUESTIONS REGARDING YOUR INVOICE PLEASE CONTACT OUR ADMINISTRATION DIVISION AT (805) 961-8800
The District charges $25 for returned checks. Other penalties/fees may be incurred as a result of returned checks and late payment (see District Rule 210). Failure to pay this Invoice may result in the cancellation or suspension of your permit. Please notify the District regarding any changes to the above information 09/29/2021

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 11: Capital Improvement
Program and Implementation
FINAL / October 2026

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 11: Capital Improvement
Program and Implementation
FINAL / October 2026
Digitally signed by Graham J.G. Juby
Contact Info: Carollo Engineers, Inc.

Date: 2026.10.24 11:25:32-07'00'
VOLUME 11 / CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN i
pw://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/Master Plan/Volume 11/_Cover_TOC_Abbrevs_AppxCovers.docx Contents
CHAPTER 1 CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION

1.1 Purpose 1-1

1.2 Background and Methodology 1-1

1.2.1 Short-Term Projects 1-2

1.2.2 Medium-Term Projects 1-2

1.2.3 Long-Term Projects 1-2

1.3 Project List 1-2

1.3.1 Short-Term Projects 1-2

1.3.2 Medium-Term Projects 1-6

1.3.3 Long-Term Projects 1-6

1.4 Preliminary CIP Schedule 1-8

1.5 Summary of CIP Projects 1-8
CHAPTER 2 PROJECT DELIVERY

2.1 Introduction 2-1

2.1.1 Purpose and Background 2-1

2.1.2 Project Drivers 2-1

2.2 Project Delivery Methods 2-2

2.2.1 Design-Bid-Build 2-3

2.2.2 Construction Manager General Contractor 2-3

2.2.3 Progressive Design-Build 2-4

2.2.4 Fixed-Price Design-Build 2-4

2.3 Delivery Method Evaluation and Recommendations 2-7

2.3.1 Evaluation Criteria 2-7

2.3.2 Recommended Project Delivery Method 2-11
Appendices

APPENDIX A SHORT-TERM CAPITAL IMPROVEMENT PROGRAM PROJECTS TO MAINTAIN EXISTING WWTP
APPENDIX B WORKSHOP NO. 7 - PROJECT DELIVERY
Tables
Table 1.1 Detailed Summary of CIP 1-9
Table 2.1 Project Delivery Methods 2-3
Table 2.2 Advantages and Disadvantages of Delivery Methods 2-5 Table 2.3 Considerations for Alternative Project Delivery 2-7 VOLUME 11 / CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN ii
Figures
Figure 1.1 Preliminary Layout of Proposed Percolation Pond Project 1-3 Figure 1.2 Phase 1 WWTP Facilities Planning Level Layout 1-5 Figure 1.3 Phase 2 WWTP Preliminary Facilities Layout 1-7 Figure 1.4 Planning Level Schedule for First 13 Years of the Proposed CIP 1-8 Figure 1.5 Projected Annual CIP Outlay Through Fiscal Year 2036/2037 1-10 Figure 1.6 Projected Total CIP Through 2060 for all Major Identified Projects 1-11 Figure 2.1 Traditional DBB Approach for Phase 1 Delivery 2-12 Figure 2.2 Option for Refinement of the Project Delivery Approach After 30% Design 2-13 Figure 2.3 At 60% Design, There is Flexibility to Stay With CMGC or Switch Back to DBB 2-14 Figure 2.4 Final Choice to Complete the Project via CMGC or DBB 2-14 VOLUME 11 / CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN iii
Abbreviations
ADWF average dry weather flow
BODR Basis of Design Report
Carollo Carollo Engineers
CIP Capital Improvement Program
City City of Santa Marian
CMAR Construction Manager-At-Risk
CMGC Construction Manager/General Contractor
DB Design-Build
DBB design-bid-build
FPDB Fixed Price Design-Build
FY fiscal year
GMP guaranteed maximum price
mgd million gallons per day
O&M operations and maintenance
PDB Progressive Design-Build
SB Senate Bill
WWTP wastewater treatment plant
VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-1
CHAPTER 1 CAPITAL IMPROVEMENT PROGRAM AND

IMPLEMENTATION

1.1 Purpose
The purpose of this chapter is to present the Capital Improvement Program (CIP) developed from the recommendations identified throughout this Master Plan. The CIP provides an implementation framework for the recommended improvements through 2060. The City of Santa Maria (City) operates on a July 1 to June 30 fiscal year (FY), so for example FY 26/27 begins July 1, 2026 and ends June 30, 2027.

The preceding volumes and chapters of this Master Plan identify project needs, planning-level costs, and technical justifications. This chapter consolidates those recommendations into a prioritized implementation program and identifies anticipated City expenditures by FY.

1.2 Background and Methodology
The CIP was developed using recommendations from the facility planning, process evaluation, condition assessment, capacity evaluation, and regulatory compliance analyses presented throughout this Master Plan. Each project was evaluated based on the following considerations:
 Regulatory compliance requirements.
 Operational reliability.
 Asset condition.
 Treatment capacity needs.
 Long-term growth projections.
 Sequencing and interdependencies with other improvements.

Planning-level project costs were developed in the respective technical chapters where the projects were identified. The basis that was used to develop the planning-level cost estimates is detailed in Volume 2, Chapter 6.

This chapter incorporates those costs into an implementation strategy that supports continued reliable operation of the Santa Maria Wastewater Treatment Plant (WWTP) through 2060, incorporating appropriate plant modifications and improvements to address effluent permitting requirements, growth, and rehabilitation.

To facilitate project prioritization and implementation planning, projects were grouped into the following three implementation periods based on anticipated facility needs, project sequencing, and dependencies between major capital improvements.

VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-2

1.2.1 Short-Term Projects
Short-term projects are recommended to address immediate facility needs, maintain reliable plant operation, and implement the first phase of treatment facility improvements identified in this Master Plan.

Short-term projects are anticipated to begin immediately (FY 26/27) and be completed over the following ten years, by FY 36/37.

This category includes the major Phase 1 Expansion project.

Note that in some Volumes of the Master Plan there were references made to so-called Near-Term projects, in order to differentiate them from longer-term projects. These are now included in the short-term projects.

1.2.2 Medium-Term Projects
Medium-term projects focus on maintaining the performance and reliability of critical wastewater treatment infrastructure following implementation of the Phase 1 improvements. Medium-term projects are anticipated to begin in FY 37/38.

1.2.3 Long-Term Projects
Long-term projects are intended to support future treatment capacity needs, maintain critical infrastructure, and accommodate long-range planning objectives. Long-term projects are anticipated to begin in FY 52/53.

1.3 Project List
Based on recommendations developed throughout this Master Plan, smaller projects were grouped into five “major projects” and recommended for implementation through FY 59/60. These major projects are:
 CIP Projects to Maintain the Existing WWTP
 Percolation Pond Expansion Project
 Phase 1 Expansion Project
 Percolation Pond Rehabilitation Project
 Phase 2 Expansion Project
These five projects were organized according to the implementation periods described in Section 1.2 and are described in more detail below.

1.3.1 Short-Term Projects

1.3.1.1 CIP Projects to Maintain Existing WWTP
Several CIP projects were identified and recommended to maintain plant reliability and support continued operation prior to and during the construction and completion of the Phase 1 facilities. Volume 4 of the Master Plan provided a compiled set of projects to be undertaken in the short-term prior to Phase 1 upgrades. These projects were based on findings from a condition assessment performed on all of the VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-3
facilities at the WWTP. Appendix A lists details and project costs of each individual upgrade/rehabilitation project. These projects are anticipated to occur between FY 26/27 and FY 30/31.

1.3.1.2 Percolation Pond Expansion Project
The Percolation Pond Expansion Project is recommended as a short-term improvement to provide additional percolation capacity and support current and future wastewater flows. This project will construct six additional percolation ponds for a total of 42 acres of percolation ponds and associated facilities on City-owned land east of Black Road. Figure 1.1 shows the preliminary layout of the Percolation Pond Expansion Project. Design and implementation are anticipated between FY 26/27 and FY 29/30. For additional details regarding this project, refer to Volume 6, Chapter 6 of the Master Plan.

Figure 1.1 Preliminary Layout of Proposed Percolation Pond Project VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-4

1.3.1.3 Phase 1 Expansion Project
The Phase 1 Project represents the first major treatment facility expansion recommended by the Master Plan. This project provides the foundation for future treatment improvements and is a key component of the overall implementation strategy to enable the plant to meet the new General Permit effluent limits.

Once completed, the Phase 1 improvements will take the facility through 2052 with 10 million gallons per day (mgd) average dry weather flow (ADWF) of hydraulic capacity at the projected loading rates for this expansion’s horizon.

The project is anticipated to begin advanced planning and design activities in FY 26/27, followed by construction beginning in FY 31/32 and completion in FY 36/37. Figure 1.2 illustrates the facilities that will be upgraded as part of the Phase 1 project. For additional details regarding this project, refer to Volume 6 of the Master Plan.

VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA WASTEWATER TREATMENT PLANT MASTER PLAN 1-5 Figure 1.2 Phase 1 WWTP Facilities Planning Level Layout VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-6

1.3.2 Medium-Term Projects

1.3.2.1 Percolation Pond Rehabilitation Project
The City currently percolates all its secondary effluent into 15 separate percolation ponds. A 2024 soils investigation, further detailed in Volume 7, Chapter 2 of the Master Plan, resulted in several recommendations for rehabilitation of the ponds to improve and sustain performance. The Percolation Pond Rehabilitation Project is recommended to maintain long-term performance and reliability of the percolation pond system.

The rehabilitation work would include removing the top 3 to 5 feet of soil in each of the existing 15 ponds, "cleaning" it to remove unwanted clay and organic matter, and placing it back in the ponds. The operation is expected to take about 5 years to complete, based on completing three ponds per year during the drier summer months, and, for CIP planning purposes, it is anticipated that this work would be repeated periodically as pond percolation rates begin to decline. The actual timeframe for repeating this major pond rehabilitation work will be determined based on performance, and, because the Phase 1 upgrades should result in a much lower solids load to the ponds, it is possible that the timeframe could be extended considerably. For this CIP it was assumed that two rehabilitation projects would be completed within a 15-year period, which is considered to be conservative.

1.3.3 Long-Term Projects

1.3.3.1 Phase 2 Project
The Phase 2 Project represents the final major treatment facility expansion identified in the Master Plan.

Phase 2 construction will provide a total plant capacity of 12-mgd ADWF, to take the City beyond 2060 in terms of the projected flow and loading needs. The project is anticipated to begin planning activities around FY 52/53 and be complete by FY 59/60, and is intended to provide additional treatment capacity required to meet future planning conditions. Figure 1.3 illustrates the facilities that will be upgraded as part of the Phase 2 project.

VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA WASTEWATER TREATMENT PLANT MASTER PLAN 1-7 Figure 1.3 Phase 2 WWTP Preliminary Facilities Layout
VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-8

1.4 Preliminary CIP Schedule
Figure 1.4 presents a planning level schedule for the first 13-years of the proposed CIP and covers the implementation of the Short-Term Projects and the start of the Medium-Term Project. As indicated, the three short term projects are expected to be complete by the end of 2036, which includes the Percolation Pond Expansion Project and the large Phase 1 Expansion Project. The other Short-Term project that is underway is on-going maintenance of the existing WWTP to keep it performing as efficiently as possible.

The Medium-Term project is focused on rehabilitation of the existing percolation ponds, and that is expected to get underway in 2035, although the timing for this will depend on the status of the construction of the Phase 1 Expansion and the performance of the existing and new ponds. The new ponds are expected to be on-line in 2030.

Planning for the future Long-Term Phase 2 Expansion project is not expected to start until about 2052, which is well beyond the timeline shown in Figure 1.4.

Figure 1.4 Planning Level Schedule for First 13 Years of the Proposed CIP

1.5 Summary of CIP Projects
Table 1.1 summarizes the five major recommended CIP projects, covering the short-term, medium-term and long-term implementation periods, and planning-level project costs. Project costs were developed in the corresponding technical chapters of this Master Plan and are presented herein for implementation planning purposes. Actual project costs should be refined during subsequent planning, design, and budgeting efforts. As indicated, the total anticipated expenditure for all major projects identified through FY 59/60 is approximately $935 million. Graphical representations of the values in Table 1.1 are presented below.

VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA WASTEWATER TREATMENT PLANT MASTER PLAN 1-9 Table 1.1 Detailed Summary of CIP
Project Name
CIP Cost
Estimate Total
($)
CIP Cost by FY and Phase ($)
Short-Term Medium-Term Long-Term
WWTP Maintenance; Percolation Pond Expansion; Phase 1 Project Pond Rehabilitation Phase 2 Project FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 FY 31/32 FY 32/33 FY 33/34 FY 34/35 FY 35/36 FY 36/37 FY 37/38 – 41/42 FY 42/43 – 46/47 FY 47/48 – 51/52 FY 52/53 – 59/60 Short-Term Projects to Maintain WWTP Operation(1,2,3)
Project 100 - Septage Station Rehabilitation $27,000 $27,000 Project 200 - Headworks Rehabilitation - Phase 1 $386,000 $279,000 $89,000 $18,000 Project 250 - Headworks Rehabilitation - Phase 2 $112,000 $112,000 Project 300 - Primary Trickling Filter, Pump Station, and Primary Clarifier Rehabilitation $411,000 $107,000 $9,000 $257,000 $38,000 Project 400 - Secondary Trickling Filter Rehabilitation $181,000 $47,000 $134,000 Project 500 - Secondary Clarifier Rehabilitation $144,000 $22,000 $122,000 Project 600 - Digester Rehabilitation - Phase 1 $580,000 $569,000 $11,000 Project 650 - Digester Rehabilitation - Phase 2 $156,000 $156,000 Project 700 - Plant Facilities Projects - Phase 1 $459,000 $450,000 $9,000 Project 750 - Plant Facilities Projects - Phase 2 $118,000 $118,000 Percolation Pond Expansion Project(4,5) $76,209,000 $1,540,000 $12,524,000 $35,745,000 $26,400,000 Phase 1 Expansion Project(4,6,7) $536,000,000 $1,258,000 $5,922,000 $9,945,840 $14,684,680 $14,173,680 $42,065,520 $109,108,720 $118,265,840 $118,265,840 $88,954,880 $19,929,000 Phase 2 Expansion Project(4,8) $274,524,000 $274,524,000 Percolation Pond Rehabilitation $46,000,000 $23,000,000 $23,000,000 TOTAL COST(7) $935,307,000 $3,527,000 $19,289,000 $45,966,840 $41,615,680 $14,368,680 $42,065,520 $109,108,720 $118,265,840 $118,265,840 $88,954,880 $19,929,000 $23,000,000 $0 $23,000,000 $274,524,000 Notes: (1) Project costs are in February 2024 dollars. Los Angeles Engineering News-Record Construction Cost Index for February 2024 is 15,214. (2) Total project cost includes a 30 percent contingency, 10 percent for general conditions, 15 percent for general contractor, and 8.75 percent for sales tax based on 50 percent of the baseline cost plus contingency. (3) Total project cost includes a 30 percent markup of the estimated construction cost that accounts for engineering, management, and legal fees. (4) Total project cost includes a 30 percent contingency; 12.5 percent for general conditions; 15 percent for general contractor; 8.75 percent for sales tax based on 50 percent of the baseline cost plus contingency; 15 percent for engineering support during design, 7 percent for construction management; and 9 percent for legal, administrative, and regulatory fees. (5) Project cost has been escalated to midpoint of construction. The midpoint of construction is 2028. (6) Project cost has been escalated to midpoint of construction. The midpoint of construction is 2034. (7) Project totals may not add up due to rounding. (8) Project cost has been escalated to midpoint of construction. The midpoint of construction is 2057.

VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-10
Figure 1.5 presents the projected annual CIP expenditures for the two major short-term projects, namely the Percolation Pond Expansion Project and the Phase 1 WWTP Expansion Project. All costs for the short-term projects, including the projects to maintain WWTP operations are included, but the latter have not been broken out into individual cost items in the figure. As indicated, fiscal year expenditure is expected to peak at close to $120 million per year at the height of the construction of the Phase 1 Expansion Project in FYs 33/34 and 34/35.

Figure 1.5 Projected Annual CIP Outlay Through Fiscal Year 2036/2037 Figure 1.6 presents the overall CIP based on identified projects through 2060. This includes all projects shown in Figure 1.5 as well as the Percolation Pond Rehabilitation project, projected to begin around FY 37/38, and the future Phase 2 expansion of the WWTP projected to begin around FY 52/53. The total anticipated CIP for major project identified through 2060 is expected to total around $935 million, as noted above in Table 1.1.
$0
$20,000,000
$40,000,000
$60,000,000
$80,000,000
$100,000,000
$120,000,000
$140,000,000
FY
26/27
FY
27/28
FY
28/29
FY
29/30
FY
30/31
FY
31/32
FY
32/33
FY
33/34
FY
34/35
FY
35/36
FY
36/37
CIP Expenditure ($)
Fiscal Year

PROJECTED ANNUAL CIP OUTLAY
Percolation Pond Expansion Project Phase 1 Expansion Project CIP TOTAL PER FY VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-11
Figure 1.6 Projected Total CIP Through 2060 for all Major Identified Projects TOTAL CIP THROUGH 2060 ~ $935 Million
Short-Term Projects to Maintain WWTP Operation Percolation Pond Expansion Project Phase 1 Expansion Project Phase 2 Expansion Project
Percolation Pond Rehabilitation
8 %
29 %
5 %
57 %
<1 %
VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-1
CHAPTER 2 PROJECT DELIVERY

2.1 Introduction

2.1.1 Purpose and Background
Chapter 2 of Volume 11 provides an overview as well as the relative strengths, weaknesses, and applicability of various project delivery methods the City will consider for implementation of the Phase 1 Project. In addition, this chapter describes the evaluation factors the City is considering in selecting the project delivery method, and also recommends the initial direction regarding the selected project delivery approach.

When considering a project delivery method, owners generally follow this structured approach in order to reach a supportable decision:

1. Confirm Project Drivers - Identify and confirm the key project drivers and success factors that the chosen project delivery method must address.

2. Identify Applicable Delivery Methods - Identify traditional and alternative project delivery methods, consider their inherent strengths and weaknesses, and establish the applicability of these methods to the owner's legal requirements, characteristics, values, and needs, as well as their applicability to the project drivers specifically.

3. Develop Evaluation Criteria - Develop and define key project drivers and appropriate considerations to be used in the evaluation.

4. Evaluate Delivery Methods - Compare the project delivery methods based on the key project drivers and evaluation criteria.

2.1.2 Project Drivers
A myriad of potential drivers come into play on any large capital improvement project. Typical examples include:
 Schedule - Does the Project need to be operational to comply with regulatory and/or funding deadlines?
 Cost - Is the owner facing affordability challenges for the Project, requiring minimization of capital and life-cycle costs?
 Innovation - Does the Project require a unique technical approach? Are there construction challenges related to the site?
 Operations and Maintenance (O&M) Coordination - What requirements or constraints need to be addressed from an operational perspective?
 Political - Do the owner's elected officials have particular goals or concerns that must be addressed?  Community - Does the community have concerns regarding cost, aesthetics, odor, noise, etc.?  Risk Transfer - Does the owner wish to allocate Project risk to other parties? VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-2
When considering project delivery approaches, owners need to carefully consider these drivers and weigh their relative importance in order to select the optimal delivery approach, as each methodology possesses certain tradeoffs among its advantages. For example, certain delivery methods can create schedule efficiencies, yet sacrifice owner control. Others can provide a very high level of owner control, yet sacrifice market price competitiveness. As discussed later in this chapter, the evaluation of project delivery methods needs to involve thoughtful criteria that directly reflect project drivers.

2.2 Project Delivery Methods
A range of project delivery methods is available and regularly utilized in the public infrastructure industry for vertical construction and water/wastewater projects. While traditional "design-bid-build" (DBB) has been the preferred delivery method for water/wastewater projects for many decades, owners have been increasingly turning to alternative project delivery approaches that may offer certain owner and project benefits over DBB. To date, the City has used the DBB delivery method exclusively, and the planned Phase 1 Project represents the largest capital project that the City has undertaken to date.

The most common alternative delivery methods in use for water/wastewater projects include Construction Manager At-Risk (CMAR) and two different variants of the Design-Build (DB) method. As described later in this chapter, each method possesses specific advantages and disadvantages that can make it more or less applicable to different organizations and projects. On October 11, 2025, California Governor Gavin Newsom approved Senate Bill (SB) 598, which added Section 22199.5 to the California Public Contract Code that authorizes the use of the Construction Manager/General Contractor (CMGC) project delivery method for water and wastewater infrastructure projects. CMGC is synonymous with CMAR, the latter term now obsolete in California; CMGC will be used for the rest of this chapter.

As such, the following delivery methods for this evaluation were initially deemed the most relevant to the City's Project:
 Design-Bid-Build (DBB).
 Construction Manager/General Contractor (CMGC).
 Progressive Design-Build (PDB).
 Fixed Price Design-Build (FPDB).

Other delivery methods, such as Design-Build-Operate/Finance, Engineer-Procure-Construct, Job Order Contracting, etc., are not considered applicable to the delivery of the Project because the City intends to own, operate, and finance the Phase 1 Project once complete, and so these methods were eliminated from further consideration.

Table 2.1 presents a summary of the delivery methods applicable to the Phase 1 Project and the familiarity of each to the City.

VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-3
Table 2.1 Project Delivery Methods
Delivery Method City Experience General Method Application Design-Bid-Build (DBB) Traditional delivery method,
well understood and used
extensively for City capital
projects.

DBB is the most common delivery method for
construction projects regardless of location and type.

Construction Manager/
General Contractor (CMGC)
None. Less common than DBB. Used for transportation and vertical construction projects when contractor input is required early in design. CMGC is gaining acceptance in the water/wastewater industry, and there are projects
underway in the region using this approach.

Progressive Design-Build
(PDB)
None. Providing similar benefits as CMGC, PDB is becoming more common in the water/wastewater industry.

Fixed-Price Design-Build
(FPDB)
None FPDB was the first alternative project delivery method used in the water/wastewater industry and remains
widely accepted.

Key differences between the project delivery methods lie in the contractual and working relationships employed, and in how and when project costs are established. The following sections provide a brief description of the four delivery methods described in Table 2.1.

2.2.1 Design-Bid-Build
DBB is the most commonly utilized project delivery method. For most projects, the owner and/or its design consultant completes the design and develops construction documents, from which bids are solicited. The selection of the contractor is based on the lowest responsive bid, and the contractor serves as a single point of responsibility for construction. As mentioned, this is the delivery approach that the City has used exclusively to date for completing capital projects.

In the DBB structure, there is no contractual relationship between the designer and the contractor. The engineer typically prepares cost estimates throughout the design of the project, but the construction cost is not established until the lump sum bids are received. Because the design is completed by the owner or its consultants, the owner/engineer retains the design risk for the project. Change orders tend to be more common under DBB than other project delivery variants, as there are no mechanisms built into this delivery method to react to or incorporate necessary project adjustments or deviations without a change order, and also because the design typically does not receive contractor review until the procurement stage. However, owners typically set aside a contingency amount to cover anticipated changes.

2.2.2 Construction Manager General Contractor
The CMGC delivery approach is contractually similar to the DBB method in that the designer and the contractor are contracted as separate entities. Like DBB, the project design may be completed by the owner/owner's consultant, but the model is more commonly administered using a third-party designer.

The primary difference between CMGC and DBB is that the contractor is selected early in the design process based on a best-value selection process that incorporates qualifications, experience, and minimal project cost information. During the preconstruction phase services period, the contractor provides input during the design process to develop more detailed cost estimates as the project progresses. This VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-4
ultimately leads to a negotiated guaranteed maximum price (GMP) generally established between 60 to 90 percent design completion. This delivery method also allows for certain portions of the project to be released for construction (i.e., "early construction packages") before the entire design is complete, which can facilitate a reduction in overall project schedule. While the City still retains the design risk associated with this project delivery method, exposure to change orders is generally reduced due to the contractor's involvement during design. In addition, risks associated with exceeding the construction budget can be shifted to the contractor.

2.2.3 Progressive Design-Build
PDB is essentially identical to the CMGC delivery approach, with the exception being the use of a "single entity" contracting method. While under CMGC, the owner executes separate agreements with the design engineer and the contractor, in PDB, the owner executes a single agreement with the PDB entity (generally a contracting firm or joint venture). Because the design-builder is a single point of responsibility for both design and construction, it assumes both design and construction liability. Like CMGC, under PDB, the design-builder is selected through a qualifications-based, or best-value, selection process.

PDB allows the owner to maintain an influence over the design, similar to CMGC, but in the case of PDB, the design-builder owns the design risk – a key differentiator over CMGC. Similar to CMGC, construction cost estimates are prepared throughout the design process, and a GMP is typically negotiated between the 60 percent to 90 percent design completion.

Early work packages are also possible under this model, facilitating schedule efficiencies, and the contractor's involvement during design reduces owner exposure to change orders. It is worth noting that under the PDB model, the design engineer is working for and being paid by the contractor. So, the typical owner-engineer relationship in which the engineer is looking after the interests of the owner is no longer there.

2.2.4 Fixed-Price Design-Build
FPDB is a "single entity" project delivery method that provides the same design and construction risk transfer benefits as the PDB approach. However, unlike PDB (and CMGC), FPDB is not a collaborative delivery method wherein the design engineer and construction contractor work together to advance the design and construction cost estimate until a GMP can be reached.

Instead, as the name implies, FPDB incorporates a best-value procurement process where the owner provides proposers with technical bridging documents developed to the degree necessary to solicit fixed pricing for the project. Selection of the FPDB team involves a best-value evaluation, which considers the fixed pricing element. While this delivery model offers the owner price certainty, its use requires thorough consideration of the project's technical requirements, particularly those impacting operations, in order to avoid costly change orders. To this end, owners typically produce designs that are at the 10 to 30 percent completion level together with detailed design criteria and "minimum" technical specifications to incorporate as many of the owner's preferences as possible prior to issuing the package for bidding.

A summary of advantages and disadvantages of each of the applicable delivery methods is provided in Table 2.2. In addition, Appendix B includes presentation slides provided to the City during a workshop in August 2025 (Workshop No. 7) in which these delivery methods were discussed in more detail.

VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-5
Table 2.2 Advantages and Disadvantages of Delivery Methods Method Advantages Disadvantages
Design
Bid-Build (DBB)
 Institutional familiarity and well-understood contracting relationships
 High level of control over design elements
 Project scope fully defined at commencement of construction  Competitive bidding environment
 Some control over contractor quality when qualifications based evaluation criteria are used in the bid process
 Owner legal exemption is not needed
 Familiar to local contracting community
 Sequential design-bid-build process typically extends schedule  Owner warrants design to contractor (assumes design risk)  No contractor input during design
 Cost certainty not obtained until after design is complete and the project has been bid
 Increased potential for change orders
 Greater potential for disputes
 Little control of contractor selection (i.e., lowest responsive bid dictates selection)
 Managing multiple contracts (i.e., separate design and construction contracts)
Construction
Manager/General
Contractor
(CMGC)
 Design can be completed by the owner or by a consultant based on resource availability
 Qualifications-based selection of designer and/or contractor  High level of owner design control
 Cost certainty can be established earlier in the project if CMGC procured early in design
 Contractor input during design
 Opportunities for collaboration between parties
 Potentially shortened schedule
 Significant opportunity for owner input/review (control over quality)
 Flexibility to off-ramp if GMP not considered realistic  Design packages must be sufficient to mitigate change orders  Negotiating GMP sometimes difficult
 Managing multiple contracts (i.e., separate design and construction contracts)
 Much of the design risk is still assigned to the owner since the designer is contracted separately from the contractor, although some risk is mitigated by early involvement by the contractor
 May not result in lowest possible cost, but cost competitiveness is gained through "open book" negotiations and bidding of subcontract work  Performance guarantees not available from contractor
 Less familiar to local contracting community and owner's elected officials and stakeholders
 Requires additional owner resources to manage project delivery VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-6
Method Advantages Disadvantages
Progressive
Design-Build
(PDB)
 Qualifications-based selection
 Potentially shortened project schedule
 Increased owner control over project (relative to other design-build variants)  Transfer of design-related risk to design-build team
 Implemented in phases or task orders to save time and keep the project moving
 Single contract between owner and design-builder (single point of accountability)
 Potential for increased competition relative to other project delivery variants due to lower proposal costs
 Innovation from design-build team allows potential cost savings (i.e., works well when the project is complex or lacks definition)  Early cost determination
 Flexibility to design to budget
 Allocation of risk flexibility
 Owner does not hold design contract
 Owner has little control over development of design elements as design engineer now works for the contractor
 Construction costs are unknown when initial contract is signed  Public perception of higher costs since they are negotiated rather than "hard bid"
 Negotiating the GMP can be more difficult if the design-builder is self-performing a significant amount of the work  Less familiar to local contracting community and owner's elected officials and stakeholders
 Requires additional owner resources to manage project delivery Fixed-Price
Design-Build
(FPDB)
 Best-value based selection of contractor
 Has potential for accelerated project schedule
 Provides design-builder with significant flexibility to develop innovative designs, which can result in maximum potential for cost savings
 Early establishment of construction cost and construction schedule
 Transfer of design-related risk to design-builder
 Competitive process at the bidding stage
 Performance guarantees available (i.e., works well when the project can be defined using performance metrics)
 Single contract between owner and design-builder (single point of accountability)
 Owner has little control over development of design elements  Engineer works for the contractor
 Potential for increased life-cycle costs (due to selection of lower capital cost equipment that may have higher O&M costs)
 Determining exactly what the owner expects relative to overall performance is key to obtaining an acceptable product
 Complex procurement process
 Existing conditions and permitting uncertainty prior to design-build contract
 Potential for decreased competition due to cost of preparing proposal (can be offset by providing a stipend to proposers, which adds cost for the owner)
 Less familiar to local contracting community and owner's elected officials and stakeholders
VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-7

2.3 Delivery Method Evaluation and Recommendations

2.3.1 Evaluation Criteria
Table 2.3 presents the more common criteria owners consider when selecting a project delivery method.

The application of these considerations to the various delivery methods is presented in the subsection that follows.

Table 2.3 Considerations for Alternative Project Delivery Consideration Definition
Level of Control
Design The ability of the owner to exercise control of project design.

Project Quality The ability of the owner to exercise control of the contractor's approach towards ensuring quality of the work.

Owner Resources The degree to which the delivery method impacts owner staffing and/or administrative needs.

Schedule
Project Phase Duration The extent to which the delivery method impacts the procurement and project implementation schedule/duration.

Cost
Cost Efficiency The degree to which the delivery method impacts price competitiveness and resulting project cost efficiencies.

Cost Certainty The point at which the delivery method provides cost certainty at contract execution and beyond.

Cost Transparency The degree to which the delivery model allows owner review of the construction procurement process and resulting cost estimates.

Flexibility to Control Costs The extent to which the delivery method allows for flexibility to change scope to control costs.

Risk Allocation
Design and Construction
Risk
The extent to which the delivery method transfers project design risk to the contracting entity.

Project Performance Risk The extent to which the delivery method promotes the transfer of risk for overall project performance.

Political Risk The extent to which the local contracting community and governing bodies are familiar with delivery method (i.e., less familiarity can result in greater political risk).

2.3.1.1 Level of Control
Evaluating the comparative level of control among delivery methods involves considering the owner's control over project design and the ability to mandate specific quality requirements.

VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-8
Design
The DBB approach provides the owner with the largest degree of design control. This is due to the direct contractual relationship with the design engineer, coupled with the advancement of the design via various review submittals to obtain owner input to 100 percent completion.

CMGC provides a similar degree of design control via direct contracting with the designer. Once the GMP is reached and agreed upon, generally around 60 to 90 percent, owner control over the final design product may be reduced.

PDB provides less design control as the design engineer is not under direct contract with the owner and may be influenced by competing objectives of the construction contractor who holds the PDB contract.

Lastly, under FPDB, design control is limited to the content of the procurement's technical bridging documents, which generally includes a design advancement of approximately 30 percent. The FPDB is free to complete the design as it sees fit.

DBB will result in quality materials and equipment being utilized by the contractor since the contract documents (drawings and specifications) are prepared by the owner to reflect quality preferences.

However, the owner's selection of a contractor is based solely on a low bid (pre-qualification of contractors or use of the owner's provision to consider other factors than cost can provide some control).

Additionally, limited opportunity exists for owner involvement in subcontractor procurement through DBB, so poorly qualified subcontractors could potentially affect the quality of construction.

Conversely, both CMGC and PDB allow for the City to control the quality of the contractor by mandating the use of a best-value/qualifications-based selection process, and to potentially be involved in the pre-qualification process for subcontractors. FPDB quality prescription is limited by what is contained in the procurement technical bridging documents.

One criticism of alternative delivery methods, compared to DBB, is the poorer quality of record drawings and general project documentation. Assigning such tasks to a third-party construction manager may be a way to provide higher quality finished products for the owner.

Owner Resources
Level of control and owner resources requirements go hand in hand. CMGC and PDB require additional owner staff resources or a consultant to assist with the procurement and oversight during the preconstruction phase services, as the design is advanced and the cost model is developed. These additional costs are not required for traditional DBB or FPDB methods, where lump sum costs are established without the negotiation step. FPDB requires considerable owner involvement during the procurement process.

VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-9

2.3.1.2 Schedule
In general, no project delivery model is inherently faster or slower than others. The various approaches contain differing opportunities for schedule efficiency during both the procurement and delivery phases, based on the parameters identified below.
 Procurement Duration - The PDB approach can provide the greatest procurement schedule efficiency, as there is usually no need for advanced technical bridging documents, and the owner is soliciting a single contracting entity. CMGC requires an extra procurement step for selection of the separately-contracted design engineer. The procurement under DBB is relatively straightforward, yet the duration is dependent on the required effort in completing the design. Under FPDB, procurement duration is directly related to the level of design completion in the technical bridging documents.

Contract negotiation durations tend to be longest under FPDB, followed by CMGC, PDB, and DBB.  Preconstruction Phase Services - Unique to the CMGC and PDB delivery models, the "preconstruction phase services" consist of the advancement of the project design to approximately 60 percent and the concurrent development of the GMP cost model. It is during this phase that schedule efficiency can vary dramatically. Misalignment between the design engineer and the contractor can lead to time-consuming iterations of work products, delaying the development of the GMP. Additionally, owner-created inefficiencies (e.g., multiple design review efforts, excessive review durations, etc.) during the preconstruction phase can also slow the process.  Construction Phase Services - Both single-entity variants of project delivery options (PDB and FPDB) offer the greatest opportunity for schedule efficiency during construction due to the potential overlap of design and construction activities. Typically, another schedule advantage of CMGC and PDB is the capability to shorten the overall construction schedule through the issuance of early construction packages, which requires accelerating certain design components.

The DBB approach, on the other hand, carries a larger potential risk of schedule delay due to the model's vulnerability to change orders and the requirement of 100 percent design drawings and specifications completion before bidding. However, change orders do provide a mechanism to make adjustments in the field, and owners typically hold some amount of contingency for this. Also, the level of change orders is highly dependent on the quality of the plans and specifications.

2.3.1.3 Cost
Cost considerations can also vary widely among the project delivery methods and fall into the categories discussed below.
 Cost Efficiency - As with the schedule criterion discussed above, it is difficult to draw absolute conclusions regarding the ability of the various project delivery methods to provide cost savings.

Generally speaking, DBB and FPDB provide the best opportunity for cost savings due to the fact that the project cost is competitively procured and influenced by market price competition. Conversely, under the collaborative delivery methods of CMGC and PDB, despite the use of "open book" pricing, true price competition is generally not available. Instead, the owner must require the CMGC/PDB contractor to implement a procurement plan for subcontractors and equipment that facilitates market price competition, for example, requiring a certain number of bids, using standardized bidding forms, etc.

VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-10
 Cost Certainty - Under DBB and FPDB, cost certainty is provided at the procurement stage in the form of a "hard bid" under DBB, or a "fixed DB price" under FPDB. The owner receives the project cost information prior to executing the contract. Under CMGC and PDB, the owner only receives guaranteed pricing for the preconstruction phase services, with the project GMP not being provided until those services are completed (typically at 60 percent design). The owner retains the right to "off ramp" should the GMP be unacceptable, but some owners and/or stakeholders are uncomfortable executing a contract without knowing the ultimate project construction cost.  Cost Transparency - Despite lacking price competition and initial cost certainty, CMGC and PDB provide an extremely transparent project costing approach. Under these collaborative models, the CMGC or PDB team develops a procurement plan for approval by the owner, identifying the approach that will be implemented to secure subcontractor services and equipment purchases. The procurement plan will also address self-performance and provide the owner with the ability to mandate the bidding of any/all project elements. All documents prepared and all pricing information received is shared with the owner, i.e., provided "open book." Additionally, the GMP developed under these models will clearly identify various cost contingency amounts and the assumptions regarding their calculation. DBB and FPDB do not offer cost transparency for either project pricing or contingency. However, most owners typically allocate an internal contingency sum to account for differing site conditions and/or change orders.
 Cost Control - Project delivery methods vary in their ability to provide cost control via their ability to adjust in response to potential budget challenges. Because the collaborative models of CMGC and PDB involve the daylighting of project cost information as early as the Basis of Design Report (BODR) stage, future design efforts at 30 percent and 60 percent can incorporate value engineering, constructability considerations, and/or other project scoping adjustments to reduce project cost prior to GMP. These approaches allow owners to avoid the "bid surprise" which can occur under DBB and FPDB.

2.3.1.4 Risk Allocation
When considering risk allocation under various project delivery methods, industry best practice dictates that risk should be allocated to the party best able to manage the risk. The most common risks, as well as mitigation and pricing considerations, are summarized below.  Design and Construction Risk - Single-entity project delivery models such as PDB and FPDB provide the ability to transfer all design and construction risk to the contracting entity. Under these models, the DB contractor is responsible for any deficiencies in the project design and any associated construction challenges. Conversely, under DBB and CMGC, because the owner owns the design contract, the construction contractors under those two delivery models are insulated from design deficiencies and/or incongruence with construction requirements. However, under these approaches, the owner still retains a contract with the design engineer who would be responsible for errors and omissions.
 Project Performance Risk - Directly related to design and construction risk allocation, under FPDB and PDB, the owner is also able to transfer the risk of the overall ability of the project to meet all operational performance requirements of the project. Again, because DBB and CMGC are not single-entity contract instruments, the owner's ability to transfer performance risk is a little more VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-11
difficult, but as mentioned, a contract will be in place with the design engineer for errors and omissions.
 Political Risk - Political risk is also a consideration when selecting a project delivery method. While collaborative delivery approaches such as CMGC and PDB have been in use for over 20 years, many owners are uncomfortable moving away from their proven use of the DBB model. The application of a new, unfamiliar project delivery approach will inevitably require an owner to dramatically change its contracting and procurement approach and philosophy. Further, as discussed above, CMGC and PDB do not provide project cost certainty at contract execution—a concept some owners and other stakeholders find uncomfortable.

2.3.2 Recommended Project Delivery Method

2.3.2.1 Initial Considerations
During the August 27, 2025, Workshop No. 7, Carollo Engineers (Carollo) facilitated a discussion to apply the evaluation criteria described above and other considerations to the specific objectives and risks of the Phase 1 Project. While the City and Carollo did not conduct a formal, weighted evaluation of the four project delivery methods discussed, the relative importance of the evaluation criteria were discussed, and the following conclusions were reached:
 City legal counsel must opine on state and City legal authorization for CMGC and both DB variants.  The City wishes to possess a high degree of control over Project design.  The individual qualifications and experience of the design engineer and construction contractor should be considered in the procurement processes.
 Involvement by City O&M personnel will be instrumental in the development of the Project design.  The Project construction approach must take into account coordination with the ongoing O&M requirements of those existing plant facilities that will remain in operation during and after Project construction.
 City Council must be educated on the various project delivery approaches and how they differ from the traditional DBB approach historically implemented by the City.  Overall Project schedule duration is not the most important criterion for this Project when considering the delivery method.

The group concluded that, based on the above assessment, the most appropriate project delivery models to consider for the Phase 1 project are DBB and CMGC.

2.3.2.2 Project Delivery Update
As mentioned, SB 598 was approved in October 2025, which authorizes the use of the CMGC project delivery method for water and wastewater infrastructure projects. While the City should seek the opinion of legal counsel, it is highly probable that CMGC can be used by the City to deliver the Project.

2.3.2.3 Proposed Project Delivery Scenario
During a follow-up meeting with the City on May 20, 2026, the City and Carollo again discussed the possible paths forward for selecting the project delivery method. Because the Phase 1 Project is such a VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-12
significant endeavor and will take eight or nine years to design and construct, it is important that the City does not get locked into a delivery method early on that limits flexibility. Accordingly, the focus of the discussion was "how to keep the City moving ahead with the Phase 1 design while retaining flexibility to adjust the project delivery method if and when deemed appropriate". Each of the two preferred delivery methods of DBB and CMGC was discussed, and the following scenario was developed.

Figure 2.1 presents an approximate timeline for delivery of the design portion of the Phase 1 project via the traditional DBB approach, expected to take about three and a half years to complete. As shown, the City would procure a design engineer in 2027 to provide preliminary design services. For the purposes of this discussion, a design level of approximately 30 percent was selected as a reasonable point to potentially refine the delivery method, as discussed below. However, this does not prevent the City from choosing to refine the delivery approach at any point prior to reaching the 30 percent level.

A design level of approximately 30 percent was chosen as a starting point because this would represent a sizable engineering design contract for a project of this magnitude and will take considerable time to complete.

Figure 2.1 Traditional DBB Approach for Phase 1 Delivery Upon completion of the "preliminary design" (30 percent or less), the City would have the flexibility to refine the delivery method. As shown in Figure 2.2, the City would have the choice to continue with the traditional DBB approach, as shown along the bottom of the graphic, or switch to the alternative CMGC delivery method, shown on the top.

If the City decides to continue with the DBB approach, the design engineer (or a new design engineer) would proceed with completing the design to 60 percent, 90 percent, and 100 percent. Alternatively, if the CMGC route is chosen, a general contractor would be selected using a qualifications-based approach to work with the City's design engineer to complete the design to 60 percent. The City would sign a Preconstruction Phase services contract with the selected contractor.

CAROLLO / 7
updatefooter0323.pptx/7 SantaMaria-052026-FlowDiagram-Graphic

PRELIMINARY
DESIGN 30%
C
O
N
S
T
R
U
C
T
I
O
N
2028 2029 2030
Select
Designer
for PDR
DBB
60%
Design
90%
Design
100%
Design
BID
Consider
Offramp
Consider
Offramp
2027 2031 2032
Refine
Delivery
Method
Option
to
Refine
Delivery Method
VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-13
Figure 2.2 Option for Refinement of the Project Delivery Approach After 30% Design If the CMGC route is selected, then, as shown in Figure 2.3, the CMGC contractor will prepare a GMP after completion of the 60 percent Design. At this point, the City can again consider its options:

1. If the GMP submitted by the contractor seems reasonable and the City feels committed to working with the contractor for the duration of the Phase 1 project, then the City could accept the GMP and sign a Construction Phase services Amendment with the contractor, and the CMGC would proceed with finishing the design and move into construction.

2. If, on the other hand, the City is not comfortable with the GMP number, the City could:
a. Tell the CMGC (through a separate contract amendment and additional cost) to advance the design to 90 percent and submit another more competitive GMP, or b. Turn to its designer, who is under a separate contract, and instruct him to complete the design, in which case the project would be finalized and delivered by DBB.

CAROLLO / 8
updatefooter0323.pptx/8 SantaMaria-052026-FlowDiagram-Graphic

PRELIMINARY
DESIGN 30%
C
O
N
S
T
R
U
C
T
I
O
N
2028 2029 2030
Select
Designer
for PDR
DBB
60%
Design
90%
Design
100%
Design
BID
Consider
Offramp
Consider
Offramp
2027 2031 2032
Refine
Delivery
Method
Option
to
Refine
Delivery Method
CMGC
60%
Design
GMP
VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-14
Figure 2.3 At 60% Design, There is Flexibility to Stay With CMGC or Switch Back to DBB If the option to stick with the CMGC is selected, then, as shown in Figure 2.4, there is one more opportunity to adjust the delivery method. Once the CMGC reaches the 90 percent design level and issues its final GMP, the City will have the same choice as before:

1. Accept the updated GMP and sign an Amendment with the contractor for the Construction Phase services to complete the design and construction of the Phase 1 project, or

2. Ask the design engineer to complete the design and switch back to the DBB approach. Once the design is completed, the project will be competitively bid.

Figure 2.4 Final Choice to Complete the Project via CMGC or DBB CAROLLO / 9
updatefooter0323.pptx/9 SantaMaria-052026-FlowDiagram-Graphic

PRELIMINARY
DESIGN 30%
C
O
N
S
T
R
U
C
T
I
O
N
2028 2029 2030
Select
Designer
for PDR
DBB
90%
Design
100%
Design
BID
Consider
Offramp
Consider
Offramp
2027 2031 2032
Refine
Delivery
Method
Consider
Offramp
CMGC
60%
Design
GMP
VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-15

2.3.2.4 Discussion
The above scenario may be a little cumbersome with the back and forth between delivery methods and the associated additional project costs, but the purpose is to illustrate an approach that the City could use to deliver the Phase 1 Project. The benefit would be a highly flexible approach that does not limit the City's ability to make adjustments to the delivery approach if certain conditions present themselves. The design process itself, irrespective of delivery method, is expected to take about three and a half years to complete. Much can change in the water/wastewater construction market during this period, hence the proposed methodology to keep the delivery approach flexible.

Based on the delivery scenario presented above, the following concluding points can be made:

1. The City can begin the procurement for design services for the Phase 1 project and complete the design to about a 30 percent level and still retain final project delivery flexibility.

2. Once the 30 percent design level is reached, the City will have the flexibility to switch to the CMGC alternative delivery approach or continue on with the traditional DBB approach and competitively bid the project. By reassessing the delivery method after completion of the preliminary design, the City would be able to gather more information regarding the relative strengths and weaknesses of the chosen approach based on project-specific considerations.

Note that once the design gets beyond the 30 percent level, the benefits of switching to CMGC diminish, so this would likely be the final opportunity to switch to CMGC. But the flexibility to switch back to DBB from CMGC would remain until a GMP is accepted.

3. If at the 30 percent design level a switch is made to the CMGC approach, then the design will proceed to the 60 percent level with two contracts in place: one with the design engineer and the other with the selected contractor.

4. At the 60 percent level and assuming the CMGC delivery method, the contractor would issue a GMP to the City. If this is acceptable, the City will sign the Construction Phase services agreement with the Contractor, and the CMGC will continue to complete the design and construction.

5. If, at 60 percent design, the GMP is not acceptable, then the City can either ask the CMGC to proceed to 90 percent completion and issue another GMP, by issuing an amendment, or the City could retain the design engineer to complete the design via the DBB approach.

6. If the CMGC is asked to proceed to 90 percent and submit another GMP, then, based on the outcome of the updated GMP, the City can again either elect to complete the project via the CMGC approach or retain the design engineer to complete the design, and the project would be competitively bid and delivered by DBB.

Finally, this approach allows the City to begin the design of the Phase 1 project using the familiar approach of DBB but offers the flexibility to change the delivery method if that is seen to be in the best interests of the City.

VOLUME 11 / CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA

WASTEWATER TREATMENT PLANT MASTER PLAN

APPENDIX A SHORT-TERM CAPITAL IMPROVEMENT

PROGRAM PROJECTS TO MAINTAIN

EXISTING WWTP
FY 2024-2028 FY 2029-2031 Notes
Priority
100 Area 1 3 Septage Station Rehabilitation $ 27,000 $ - $ 27,000 Low priority 200 Area 2- 1A, Area 2- 1B, Area 2- 1C, Area 2-1E 1 Headworks Rehabilitation - Phase 1 $ 386,000 $ 18,000 $ 368,000250 Area 2-1D 3 Headworks Rehabilitation - Phase 2 $ 112,000 $ - $ - $ 112,000 May defer to Phase 1 Contractor's Scope 300 Area 3- 1A, Area 3-1B, Area 3-1C, Area 3-1D, Area 4-1A, Area 4-1B, Area 4- 1C 2 Primary Trickling Filter, Pump Station, and Primary Clarifier Rehabilitation $ 411,000 $ 154,000 $ - $ 257,000 400 Area 5-1A, Area 5-1B, Area 5-1C, Area 5-1D 1 Secondary Trickling Filter Rehabilitation $ 181,000 $ - $ 181,000 $ - 500 Area 6-1A, Area 6-1B, Area 6-1C 2 Secondary Clarifier Rehabilitation $ 144,000 $ - $ 144,000 $ - 600 Area 7-1A, Area-7-1D 2 Digester Rehabilitation - Phase 1 $ 580,000 $ 11,000 $ 569,000 $ - 650 Area 7-1B, Area 7-1C 3 Digester Rehabilitation - Phase 2 $ 156,000 $ - $ - $ 156,000 700 Area 8-1A, Area 8-1D 2 Plant Facilities Projects - Phase 1 $ 459,000 $ 9,000 $ 450,000 $ - 750 Area 8-1B, Area 8-1C 3 Plant Facilities Projects - Phase 2 $ 118,000 $ - $ - $ 118,000 Area 1 Area 1 3 Septage Station - Clean and coat Columns $ 27,000 $ - $ - $ 27,000 Area 2 - 1A Area 2 - 1A 1 Headworks - Repairs to slab and provide backfill $ 234,000 $ - $ 234,000 $ - Area 2 - 1B Area 2 - 1B 1 Grit Chamber Structure - Repairs to expansion joints $ 89,000 $ - $ 89,000 $ - Area 2 - 1C Area 2 - 1C See O&M Clean and Replace Sump Pump #1 $ 18,000 $ - budget incorporated into routine O&M Area 2 - 1D Area 2 - 1D 2 Clean and Replace Proportional Butterfly Valve $ 112,000 $ - $ - $ 112,000 Maintain until Phase 1 expansion Area 2 - 1E Area 2 - 1E 2 Proportional Valve Actuator $ 45,000 $ - $ 45,000 $ - Area 3- 1A Area 3- 1A 3 Intermediate Clarifier Structure $ 45,000 $ - $ - $ 45,000 Changed to Low Priority Area 3 - 1B Area 3 - 1B 3 Intermediate Clarifier Drive $ 20,000 $ - $ - $ 20,000 Changed to Low PriorityArea 3 - 1C Area 3 - 1C See O&M Primary Sludge Building Blowers $ 47,000 budget incorporated into routine O&M Area 3 - 1D Area 3 - 1D 3 Primary Sludge Building Structure $ 27,000 $ - $ - $ 27,000 Area 3- 1E Area 3- 1E - Primary Sludge Pump #1 $ - $ - $ - $ - Project complete Area 4 - 1A Area 4 - 1A 3 PTF #1 Structure $ 89,000 $ - $ - $ 89,000 Monitor, reassess biannually. Area 4 - 1B Area 4 - 1B 1 PTF Pump Station Structure $ 76,000 $ - $ - $ 76,000Area 4 - 1C Area 4 - 1C See O&M PTF Pump Station Operators $ 107,000 $ - budget incorporated into routine O&M Area 4- 1D Area 4- 1D - PTF #1 Rotary Distributor $ - $ - $ - $ - Project complete Area 5 -1A Area 5 -1A 1 STF #1 Structure $ 67,000 $ - $ 67,000 $ - Area 5-1B Area 5-1B 1 STF #2 Structure $ 67,000 $ - $ 67,000 $ - Area 5 - 1C Area 5 - 1C 1 STF Pump Station Structure $ 27,000 $ - $ 27,000 $ - Area 5 - 1D Area 5 - 1D 1 STF Pump Pipe Supports $ 20,000 $ - $ 20,000 $ - Change to High Priority for grouping Area 5-1E Area 5-1E - Secondary Sludge Pumps 1 and 3 $ - $ - $ - $ - Project complete Area 5-1F Area 5-1F - Secondary Sludge Pump 2 $ - $ - $ - $ - Project complete Area 6 - 1A Area 6 - 1A 1 Secondary Clarifier #1 Structure $ 22,000 $ - $ 22,000 $ - Area 6 -1B Area 6 -1B 1 Secondary Clarifier #2 Structure $ 22,000 $ - $ 22,000 $ - Area 6 - 1C Area 6 - 1C 2 Mechanical Pumps and Drives $ 100,000 $ - $ 100,000 $ - Area 7-1A Area 7-1A 1 Digester #1 and 3 Structures $ 569,000 $ - $ 569,000 $ - Minimized expenditure on Dig #3 Area 7-1B Area 7-1B 3 Sludge Thickener #1 Structure and Catwalk $ 78,000 $ - $ - $ 78,000 ST #1 is from 1961 Area 7-1C Area 7-1C 3 Sludge Thickener #2 Structure and Catwalk $ 78,000 $ - $ - $ 78,000 Area 7-1D Area 7-1D See O&M Digester Control Building $ 11,000 $ - budget incorporated into routine O&M Area 8-1A Area 8-1A 2 Storage Building Structure $ 450,000 $ - $ 450,000 $ - Area 8-1B Area 8-1B 3 Maintenance Shop Structure $ 31,000 $ - $ - $ 31,000 Area 8-1C Area 8-1C 3 Maintenance Shop Structure $ 87,000 $ - $ - $ 87,000 Area 8-1D Area 8-1D See O&M Facility Drainage Sump Pumps $ 9,000 $ - budget incorporated into routine O&M CIP Total $ 2,574,000 $ 192,000 $ 1,712,000 $ 670,000
O&M costs $ 192,000
Phase Totals $ 2,382,000 -- $ 1,712,000 $ 670,000
Table Detailed Capital Improvement Program
City of Santa Maria
Short-Term Improvements for WWTP

WASTEWATER TREATMENT PLANT PROGRAM
Proposed CIP Project Number Individual Project Identifiers CIP Cost Estimate(1, 2,3) ($) Cost to O&M budget CIP Cost by Fiscal Year and Phase ($) List of Individual Projects
Notes:(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 4.375% for sales tax of the baseline cost. (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Priority (1 (high)
to 3 (low) scale) Project Name
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 1
Project Name: Septage Station - Clean and coat ColumnsSystem Type: WastewaterProject Description:
$ 12,000 $ 21,000 $ 27,000 2030
Project Detail:

Percent Cost ($)
100% 27,000$
0% $ - 100% 27,000$
Notes on Cost Estimation:Reimbursement Category
Existing Users
Total
Future UsersCoat columns of existing Overhang structure. Place protective curb around the base to prevent water infiltration.Project Details:

Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
Project Element ($/ft)
Project Cost Allocation:

Notes:(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project
Schedule
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Miscellaneous
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 2 - 1A
Project Name: Headworks - Repairs to slab and provide backfillSystem Type: WastewaterProject Description:
$ 105,000 $ 180,000 $ 234,000 2026
Project Detail:

Percent Cost ($)
100% 234,000$
0% $ - 100% 234,000$
Notes on Cost Estimation:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 This project involves sealing cracks in the top slab. Restore grouting for bar screen supports at the deck.

Backfill the subgrade of the headworks structure on the south end with pumped slurry. Stabilization of the slope with a retaining wall may be necessary. Add coating to headworks automatic valve actuators.

Project Details:Project Element
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Miscelaneous Repairs
Notes:

Existing Users
Future UsersTotal
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 2 - 1B
Project Name: Grit Chamber Structure - Repairs to expansion jointsSystem Type: WastewaterProject Description:
$ 40,000 $ 69,000 $ 89,000 2027
Project Detail:

Percent Cost ($)
100% 89,000$
0% $ - 100% 89,000$
Notes on Cost Estimation: Future UsersTotal
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
Existing Users
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Reseal all expansion joints along the east and south side of the structure. The east and south side between the slab on grade and the retaining wall have failed sealants. Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Miscelaneous Repairs
Notes:

Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 2 - 1C
Project Name: Clean and Replace Sump Pump #1System Type: WastewaterProject Description:

Replace 1 $ 8,000 $ 14,000 $ 18,000 2030
Project Detail:

Percent Cost ($)
100% 18,000$
0% $ - 100% 18,000$
Notes on Cost Estimation:

Notes:

Exterior of Sump Pump #1 needs to be cleaned. Included cost assumes full replacement by the project date.CProject Element Proposed
Power
(hp)
Proposed
Capacity
(gpm)
Replace/
New
Proposed
Number
of Pumps Unit Cost(1)
($/gpm)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Pump
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Cost from Santa Maria provided Cost tables. Previous cost based on 2013 estimate. Replacement should occur by 2030 Project Cost Allocation:

Reimbursement Category
Existing Users
Future Users
Total
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 2 - 1D
Project Name: Clean and Replace Proportional Butterfly Valve System Type: WastewaterProject Description:
$ 50,000 $ 86,000 $ 112,000 2030
Percent Cost ($)
100% 112,000$
0% $ - 100% 112,000$
Notes on Cost Estimation:Clean exterior and monitor performance. Replace at failure, expected in 2030. Butterfly valve is 36". Will require a complete shutdown to replace. May defer to Phase 1 contractor scope. Project Element Notes:

Project Details:

Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Butterfly Valve
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation: Project Detail:

Reimbursement Category
Existing Users
Future Users
Total
https://www.ferguson.com/category/valves/butterfly-valves/?customsort=sku_sales_i%20desc&prefn1=sku_Valve_Size_ss&prefv1=36%2Bin&srsltid=AfmBOoqvxNvT6vzuGV7WwVRRCSjIohD96a2dK9o9aPJbWNtcmvWyPqK- Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 2 - 1E
Project Name: Proportional Valve Actuator
System Type: WastewaterProject Description:
$ 20,000 $ 34,000 $ 45,000 2026
Project Detail:

Percent Cost ($)
100% 45,000 $
0% $ - 100% 45,000 $
Notes on Cost Estimation:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Due to age, clean exterior and monitor frequently for performance. Replace if failure occurs.Project Details:

Project Element
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Miscallenous
Notes:

Future UsersTotal
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
Existing Users
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 3 - 1A
Project Name: Intermediate Clarifier StructureSystem Type: WastewaterProject Description:
$ 20,000 $ 34,000 $ 45,000 2029
Project Detail:

Percent Cost ($)
100% 45,000 $
0% $ - 100% 45,000 $
Notes on Cost Estimation:

Seal cracks along concrete exterior to prevent moisture ingress. Monitor concrete condition and repair with high strength mortar as needed.

Concrete Repairs
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Details:

Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Project Element Schedule
Notes:

Total
Project Cost Allocation:

Reimbursement Category
Existing Users
Future Users
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 3 - 1B
Project Name: Intermediate Clarifier DriveSystem Type: WastewaterProject Description:
$ 9,000 $ 15,000 $ 20,000 2029
Percent Cost ($)
100% 20,000 $
0% $ - 100% 20,000 $
Notes on Cost Estimation:Project Element
Notes:

Clean rust on the exteror and epoxy coat the drive. Monitor performance due to ageProject Details:

Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Miscallenous repairs
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation: Project Detail:

Reimbursement Category
Existing Users
Future Users
Total
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 3 - 1C
Project Name: Primary Sludge Building BlowersSystem Type: WastewaterProject Description:
$ 4,000 $ 7,000 $ 9,000 2028
$ 17,000 $ 29,000 $ 38,000 2030
Percent Cost ($)
100% 47,000$
0% $ - 100% 47,000$
Notes on Cost Estimation:Project Element
Notes:

Blowers leak oil and experience frequent downtime. Repair blowers per O&M methods manual requirements if downtime issues persist. Monitor performance consistently.Project Details:

Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Mechanical repairsReplacement
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation: Project Detail:

Reimbursement Category
Existing Users
Future Users
Total
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 3 - 1D
Project Name: Primary Sludge Building Structure
System Type: WastewaterProject Description:
$ 12,000 $ 21,000 $ 27,000 2029
Project Detail:

Percent Cost ($)
100% 27,000 $
0% $ - 100% 27,000 $
Notes on Cost Estimation:

Project
Project Element Schedule
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Notes:

Joints sealants on the sidewalk have failed. Provide new joint sealants and adjust sidewalk to slab interface. Address basement vent fan, access hatch and eave issues Miscallenous
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
Existing Users
Future Users
TotalProject Details:

Proposed
Diameter
(in)
Replace/
New
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 3 - 1E
Project Name: Primary Sludge Pump #1System Type: WastewaterProject Description:
$ 11,000 $ 19,000 $ 25,000 2029
Percent Cost ($)
100% 25,000$
0% $ - 100% 25,000$
Notes on Cost Estimation:Project Element
Notes:

Clean exterior and monitor the corrosion. The advanced age of this pump may result in a failure; monitor frequently for performance. Project complete in 2024. Project Details:

Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Miscallenous Repairs
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation: Project Detail:

Reimbursement Category
Existing Users
Future Users
Total
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 4 - 1A
Project Name: PTF #1 StructureSystem Type: WastewaterProject Description:
$ 40,000 $ 69,000 $ 89,000 2029
Project Detail:

Percent Cost ($)
100% 89,000 $
0% $ - 100% 89,000 $
Notes on Cost Estimation: Future UsersTotal
assumes 50$/SF per Carollo projects. About 1780 SF would be repaired in this scenario from 7918 SF of structure (2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
Notes:

Repair spalls and cracks on exterior. Rebuild exterior and interior parapet wall surface with high-strength mortar and protective coating. Assumes half surface is covered at 50$/SF. Structure is 60ft in diameter with 12ft media height. Full replacement may not be required at current level of severity .

Monitor and reassess biannually.

Concrete Repairs
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Existing Users
Capital
Improvement
Cost(3)
($)
Project
Project Element Schedule
Replace/
New
Project Details:

Proposed
Capacity
(gpm)
Unit Cost(1)
($)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 4 - 1B
Project Name: PTF Pump Station Structure
System Type: WastewaterProject Description:
$ 34,000 $ 58,000 $ 76,000 2029
Project Detail:

Percent Cost ($)
100% 76,000 $
0% $ - 100% 76,000 $
Notes on Cost Estimation:

Existing Users
Future Users
Total
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Examine interior concrete for corrosion and coatings. Repair interior with high-strength mortar and apply protective coatings. Interior is badly corroded. Will require bypass and coordination. Reapirs of inside concrete walls will require reinstallation of all media. Monitor and re-assess. Replacement of media may not be justified considering structure to be demolished in Phase 1Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete repairs
Notes:

Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 4 - 1C
Project Name: PTF Pump Station Operators
System Type: WastewaterProject Description:
$ 48,000 $ 82,000 $ 107,000 2027
Project Detail:

Percent Cost ($)
100% 107,000 $
0% $ - 100% 107,000 $
Notes on Cost Estimation:Clean exterior and monitor the corrosion. Moderate corrosion observed on the operators. Replace in the near-term. 3 repairs needed. Cost reflects rehab of some operators and pump replacement.Project Details:

Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
Project Element ($/ft)
Project Cost Allocation:

Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Miscallenous
Notes:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project
Schedule
Reimbursement Category
Existing Users
Future Users
Total
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 4 - 1D
Project Name: PTF #1 Rotary DistributorSystem Type: WastewaterProject Description:
$ 112,000 $ 192,000 $ 250,000 2025
Percent Cost ($)
100% 250,000$
0% $ - 100% 250,000$
Notes on Cost Estimation:Project Element
Notes:

The City has begun replacing this. Severe corrosion and welding failures. Parts have been ordered and cost reflects actual price. Project complete in 2024/2025Project Details:

Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Distributor
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
Existing Users
Future Users
Total actual cost provided by City.

Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 5- 1A
Project Name: STF #1 Structure
System Type: WastewaterProject Description:
$ 30,000 $ 51,000 $ 67,000 2028
Project Detail:

Percent Cost ($)
100% 67,000 $
0% $ - 100% 67,000 $
Notes on Cost Estimation:Repair cracks and spalls along STF Structures #1 and #2 with high-strength mortar. Monitor and track water penetration occurring on the perimeter of each structure. Repair and rebuild interior surfaces of the effluent boxes exiting from each structure with protective coatings and high-strength mortar. Coat bypass manhole structures.Project Details:

Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
Project Element ($/ft)
Project Cost Allocation:

Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Concrete Repairs
Notes:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project
Schedule
Reimbursement Category
Existing Users
Future Users
TotalAssumes 50$/SF. The size of the STF is 180 ft diameter with 3.3 ft of height. Assumes about 1800 SF of repairs required.

Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 5- 1B
Project Name: STF #2 StructureSystem Type: WastewaterProject Description:
$ 30,000 $ 51,000 $ 67,000 2028
Project Detail:

Percent Cost ($)
100% 67,000$
0% $ - 100% 67,000$
Notes on Cost Estimation:

Capital
Improvement
Cost(3)
($)
Project
Schedule
Repair cracks and spalls along STF Structures #1 and #2 with high-strength mortar. Monitor and track water penetration occurring on the perimeter of each structure. Repair and rebuild interior surfaces of the effluent boxes exiting from each structure with protective coatings and high-strength mortar.Project Details:Project Element Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
STF #2 Structure
Notes:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
Existing Users
Future Users
Total
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 5 - 1C
Project Name: STF Pump Station Structure
System Type: WastewaterProject Description:
$ 12,000 $ 21,000 $ 27,000 2027
Project Detail:

Percent Cost ($)
100% 27,000 $
0% $ - 100% 27,000 $
Notes on Cost Estimation:Repairs cracking on top deck.Inspect interior of pump station for coatings. Flow cannot be shut down to the effluent box - shutdown would send untreated water to disposal ponds. Will need to assess work sequence when this work is scheduled.Project Details:

Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
Project Element ($/ft)
Project Cost Allocation:

Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Concrete
Notes:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project
Schedule
Reimbursement Category
Existing Users
Future Users
Total
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 5 - 1D
Project Name: STF Pump Pipe Supports
System Type: WastewaterProject Description:
$ 9,000 $ 15,000 $ 20,000 2027
Project Detail:

Percent Cost ($)
100% 20,000 $
0% $ - 100% 20,000 $
Notes on Cost Estimation:Corrosion has begun to occur. Clean exterior and coat supports with protective coatings.

Project
Schedule
Project Cost Allocation:

Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Miscallenous
Notes:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Details:

Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Total
Unit Cost(1)
Project Element ($/ft)Reimbursement Category
Existing Users
Future Users
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 5 - 1E
Project Name: Secondary Sludge Pumps 1 and 3System Type: WastewaterProject Description:
$ 11,000 $ 19,000 $ 25,000 2030
Project Detail:

Percent Cost ($)
100% 25,000 $
0% $ - 100% 25,000 $
Notes on Cost Estimation:Project Element
Notes:

Clean exterior and monitor the corrosion. 2 pumps. Project completed in 2024/2025. Removed from O&M budget.Project Details:

Capacity (MG)
Replace/
New
Capacity
(MG)
Unit Cost(1)
($/gallon)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Replacement
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
Existing Users
Future Users
Total25k provided by City
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 5 - 1F
Project Name: Secondary Sludge Pumps 2System Type: WastewaterProject Description:
$ 9,000 $ 15,000 $ 20,000
Percent Cost ($)
100% 20,000 $
0% $ - 100% 20,000 $
Notes on Cost Estimation:
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost).

Replace secondary sluge pump #2. Project completed in 2024/2025. Removed from O&M budget.Project Details:

Project Element Capacity (MG)
Replace/
New
Capacity
(MG)
Unit Cost(1)
($/gallon)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Replacement
Notes:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Total25k provided by City
(3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
Existing Users
Future Users
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 6 - 1A
Project Name: Secondary Clarifier #1 StructureSystem Type: WastewaterProject Description:
$ 10,000 $ 17,000 $ 22,000 2027
Project Detail:

Percent Cost ($)
100% 22,000 $
0% $ - 100% 22,000 $
Notes on Cost Estimation:Repair cracks and spalls along Secondary Clarifier Structures #1 and #2 with high-strength mortar. Install kickplates on the access guardrail
Project
Schedule
Project Cost Allocation:

Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
miscallenous
Notes:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Details:

Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Total
Unit
Cost(1)
Project Element ($/ft)Reimbursement Category
Existing Users
Future Users
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 6 - 1B
Project Name: Secondary Clarifier #2 StructureSystem Type: WastewaterProject Description:
$ 10,000 $ 17,000 $ 22,000 2028
Project Detail:

Percent Cost ($)
100% 22,000 $
0% $ - 100% 22,000 $
Notes on Cost Estimation:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Repair cracks and spalls along STF Structures #1 and #2 with high-strength mortar. Install kickplates on the access guardrail Project Details:Project Element
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit
Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
concrete repairs
Notes:

Future UsersTotal
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
Existing Users
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 6 - 1C
Project Name: Mechanical Pumps and DrivesSystem Type: WastewaterProject Description:
$ 45,000 $ 77,000 $ 100,000 2028
Project Detail:

Percent Cost ($)
100% 100,000 $
0% $ - 100% 100,000 $
Notes on Cost Estimation: Future UsersTotal
(3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
Existing Users
Notes:

Clean exterior and monitor/replace coatings. Annual maintenance required. Rehab of pumps required in next few years.

Miscallenous
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost).

Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Project Element Schedule
Project Details:

Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 7-1A
Project Name: Digester #1 and 3 StructuresSystem Type: WastewaterProject Description:
$ 255,000 $ 438,000 $ 569,000 2027
Project Detail:

Percent Cost ($)
100% 569,000 $
0% $ - 100% 569,000 $
Notes on Cost Estimation:

Existing Users
Future Users
TotalDigester #1 is in worse condition and thus it is assumed 20% of the surface will need coating (2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Repair exterior, spalls and cracks with high-strength mortar. Inspect the interior of Digester #1 and #3 during an offline period. Apply protective coatings to the interior. Monitor for leaks when in service.

Includes gas valve, sludge valving, feed piping and gas handling maintenance.

Project requires repair of Digester 3 first to allow for Digester 1 repair, and Digester 3 operation. Then, once Digester 1 is maintained, Digester 3 will ramp down and be demolished in Phase 1. Limit expenditure on Digester #3. Digester 1 to be converted a sludge holding tank as part of Phase 1. Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Demolition
Notes:

Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 7-1B
Project Name: Sludge Thickener #1 Structure and CatwalkSystem Type: WastewaterProject Description:
$ 35,000 $ 60,000 $ 78,000 2029
Project Detail:

Percent Cost ($)
100% 78,000 $
0% $ - 100% 78,000 $
Notes on Cost Estimation:

Existing Users
Future Users
Totalcost includes coating and some potential valve replacement (2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Clean exterior, replace corroded bolts or anchors, and monitor corrosion. Repair exterior, spalls and cracks with high-strength mortar. Replace 6 valves in sludge thickenerProject Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete
Notes:

Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 7-1C
Project Name: Sludge Thickener #2 Structure and CatwalkSystem Type: WastewaterProject Description:
$ 35,000 $ 60,000 $ 78,000 2029
Project Detail:

Percent Cost ($)
100% 78,000 $
0% $ - 100% 78,000 $
Notes on Cost Estimation:

Existing Users
Future Users
Totalcost includes coating and some potential valve replacement (1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement CategoryClean exterior, replace corroded bolts or anchors, and monitor corrosion. Repair exterior, spalls and cracks with high-strength mortar.Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Notes:

Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 7-1D
Project Name: Digester Control BuildingSystem Type: WastewaterProject Description:
$ 5,000 $ 9,000 $ 11,000 2028
Project Detail:

Percent Cost ($)
100% 11,000 $
0% $ - 100% 11,000 $
Notes on Cost Estimation:

Existing Users
Future Users
Total
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category Replace anchors, bolts and other components with stainless steel.

Project Details:Project Element
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Notes:

Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 8-1A
Project Name: Storage Building StructureSystem Type: WastewaterProject Description:
$ 201,500 $ 346,000 $ 450,000 2026
Project Detail:

Percent Cost ($)
100% 450,000 $
0% $ - 100% 450,000 $
Notes on Cost Estimation:

Existing Users
Future Users
Total
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement CategoryFull roof replacement required. Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Notes:

Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 8-1B
Project Name: Maintenance Shop StructureSystem Type: WastewaterProject Description:
$ 14,000 $ 24,000 $ 31,000 2029
Project Detail:

Percent Cost ($)
100% 31,000 $
0% $ - 100% 31,000 $
Notes on Cost Estimation:

Existing Users
Future Users
Total
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Southern half of the roof has no roof drain. Add roof drain and replace corroded scuppers. Repair mid-span of the lintel above the roll-up door. Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete
Notes:

Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 8-1C
Project Name: Maintenance Shop StructureSystem Type: WastewaterProject Description:
$ 39,000 $ 67,000 $ 87,000 2029
Project Detail:

Percent Cost ($)
100% 87,000 $
0% $ - 100% 87,000 $
Notes on Cost Estimation:

Existing Users
Future Users
Total
system is 30 x 60 ft - 180 ft of perimeter, with pipe supports and 4 columns to have corrosion repair. pipe support replacement estimated at 175$ per ft (direct cost, labor and materials only). 15ft tall column repair estimated at 125$/ft (4 columns) (2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Replace corroded pipe supports of metal structure over the boiler. Provide structural bracing on the exhaust stack. Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete
Notes:

Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 8-1D
Project Name: Facility Drainage Sump PumpsSystem Type: WastewaterProject Description:
$ 4,000 $ 7,000 $ 9,000 2027
Project Detail:

Percent Cost ($)
100% $ 9,000
0% $ - 100% $ 9,000
Notes on Cost Estimation:

Existing Users
Future Users
Total
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.

Project Cost Allocation:

Reimbursement Category
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Clean exterior, replace corroded bolts or anchors, and monitor corrosion. Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete
Notes:

VOLUME 11 / CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA

WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX B WORKSHOP NO. 7 - PROJECT DELIVERY
6/1/2026
1 WORKSHOP No. 7 / AUGUST 27, 2025
City of Santa Maria
Workshop No. 7
Wastewater Treatment Plant
Goals for Workshop No. 7
1 2
6/1/2026
2 C A R O L L O / 3
updatefooter0323.pptx/3 86STM0623i1.pptx/3
Goals for Workshop No. 7
• Gain a general understanding of project delivery approaches • Identify project-specific criteria to apply to project delivery decision • Achieve general agreement on best delivery method(s) to apply to project(s) • Identify next steps necessary for confirming delivery method(s) decision Volume 11 – CIP and
Implementation Plan
Project Delivery
3 4
6/1/2026
3 C A R O L L O / 5
updatefooter0323.pptx/5 86STM0623i1.pptx/5
Project Delivery Methods
C A R O L L O / 6
updatefooter0323.pptx/6 86STM0623i1.pptx/6
Project Delivery Approaches
Owner
Design/
Builder
Design-Bid-Build
(DBB)
Construction
Manager-at-Risk
(CMAR)
Fixed-Price
Design-Build
(FPDB)
“Progressive”
Design-Build
(PDB)
Design-Build-Operate/
Finance, etc.

Traditional Delivery Alternative or Collaborative Delivery Owner
Design/
Builder
Owner
Designer Contractor
Owner
Designer Contractor
Owner
Design/
Builder/
Operator
Design/
Builder Operator
Working Relationship
Contractual Relationship
Work & Service Contracts Public-Private
Partnerships
5 6
6/1/2026
4 C A R O L L O / 7
updatefooter0323.pptx/7 86STM0623i1.pptx/7
Project Delivery Approaches
Owner
Design/
Builder
Design-Bid-Build
(DBB)
Construction
Manager-at-Risk
(CMAR)
Fixed-Price
Design-Build
(FPDB)
“Progressive”
Design-Build
(PDB)
Design-Build-Operate/
Finance, etc.

Traditional Delivery Alternative or Collaborative Delivery Owner
Design/
Builder
Owner
Designer CM
Owner
Designer Contractor
Owner
Design/
Builder/
Operator
Design/
Builder Operator
Working Relationship
Contractual Relationship
Work & Service Contracts Public-Private
Partnerships
C A R O L L O / 8
updatefooter0323.pptx/8 86STM0623i1.pptx/8
Design-Bid-Build
Contracting Process
8 Procurement
• 100% drawings/specs
• Standard front-ends
• Construction contract
• Lowest responsible bid
• Contract negotiations
Construction
• Construct to drawings/specs
• Project Commissioning
• Project Start-up / Acceptance
7 8
6/1/2026
5 C A R O L L O / 9
updatefooter0323.pptx/9 86STM0623i1.pptx/9
Design-Bid-Build
Pricing Process
Design Engineer
0% 30% 60% 90% 100%
Cost
Estimate
Cost
Update
Cost
Update
Bid
Estimate
Contractor
Bid
Design Definition
BODR
C A R O L L O / 1 0
updatefooter0323.pptx/10 86STM0623i1.pptx/10
Design-Bid-Build
Advantages Disadvantages
Level of Control
• Owner & Contractor familiarity
• High level of Owner control over design elements
• Project scope fully defined at construction
commencement
Cost
• Construction cost determined at bid time (Engineer’s
estimate along the way)
• Selection based on low-bid contractor (qualified?)
• Greater potential for disputes and change orders
• Competitive bidding environment
Schedule
• Sequential schedule
Risk Allocation
• No contractor input during design
• Owner warrants design to Contractor
9 10
6/1/2026
6 C A R O L L O / 1 1
updatefooter0323.pptx/11 86STM0623i1.pptx/11
Project Delivery Approaches
Owner
Design/
Builder
Design-Bid-Build
(DBB)
Construction
Manager-at-Risk
(CMAR)
Fixed-Price
Design-Build
(FPDB)
“Progressive”
Design-Build
(PDB)
Design-Build-Operate/
Finance, etc.

Traditional Delivery Alternative or Collaborative Delivery Owner
Design/
Builder
Owner
Designer Contractor
Owner
Designer Builder
Owner
Design/
Builder/
Operator
Design/
Builder Operator
Working Relationship
Contractual Relationship
Work & Service Contracts Public-Private
Partnerships
C A R O L L O / 1 2
updatefooter0323.pptx/12 86STM0623i1.pptx/12
Construction Manager At-Risk
Contracting Process
12 Construction
Phase
Preconstruction
Phase
Procurement
• Design Engineer Procurement (single stage)
• CMAR Contractor Request for Qualifications (optional) • Statements of Qualification Evaluation/ Shortlisting (optional) • CMAR Contractor Request for Proposals
• Draft CMAR Contract
• Proposal Evaluation
• CMAR Team Interviews
• CMAR Selection
• CMAR Contract Negotiation (Preconstruction Phase Services) 11 12
6/1/2026
7 C A R O L L O / 1 3
updatefooter0323.pptx/13 86STM0623i1.pptx/13
Construction Manager At-Risk
Contracting Process
13 Construction
Phase
Preconstruction
Phase
Procurement
• BODR Development
• 30% Design Development
• 60% Design Development
• Value Engineering (continuous)
• Constructability Review (continuous)
• Cost Model Development (BODR/30%/60%)
• Guaranteed Maximum Pricing
C A R O L L O / 1 4
updatefooter0323.pptx/14 86STM0623i1.pptx/14
Construction Manager At-Risk
Contracting Process
14 Construction
Phase
Preconstruction
Phase
Procurement
• Early Works Construction (TBD)
• Design Finalization
• Project Construction
• Project Commissioning
• Project Start-up / Acceptance
13 14
6/1/2026
8 C A R O L L O / 1 5
updatefooter0323.pptx/15 86STM0623i1.pptx/15
Construction Manager At-Risk
Pricing Process
CMAR Contractor
Design Engineer
0% 30% 60% 90% 100%
Design Definition
Design Development / Review / Value Engineering
75%
Cost Model Development
Guaranteed Maximum Price
BODR
C A R O L L O / 1 6
updatefooter0323.pptx/16 86STM0623i1.pptx/16
Construction Manager At-Risk
Advantages Disadvantages
Level of Control
• Qualifications-based designer and contractor selection • Owner manages multiple contracts** • Owner substantially involved in design phase
• Traditional owner-designer relationship**
Cost
• CMAR contract price established after contract award
eliminating market price competition
• Negotiating GMP sometimes difficult due to “us vs.
them” relationship**
• Cost model developed by CMAR early in project
• Ability to design and deliver project to fixed budget Schedule
• Extended schedule potential depending on degree of
design advancement for GMP
• Dual contract model can be less efficient**
• Shortened schedule potential depending on degree of
design advancement for GMP
Risk Allocation
• Involvement of CMAR during design does not relieve
owner of design risk**
• Performance guarantees generally not available**
• Collaborative relationship
• High degree of Contractor input into design
**Key differentiator from PDB
15 16
6/1/2026
9 C A R O L L O / 1 7
updatefooter0323.pptx/17 86STM0623i1.pptx/17
Project Delivery Approaches
Owner
Design/
Builder
Design-Bid-Build
(DBB)
Construction
Manager-at-Risk
(CMAR)
Fixed-Price
Design-Build
(FPDB)
“Progressive”
Design-Build
(PDB)
Design-Build-Operate/
Finance, etc.

Traditional Delivery Alternative or Collaborative Delivery Owner
Design/
Builder
Owner
Designer CM
Owner
Designer Builder
Owner
Design/
Builder/
Operator
Design/
Builder Operator
Working Relationship
Contractual Relationship
Work & Service Contracts Public-Private
Partnerships
C A R O L L O / 1 8
updatefooter0323.pptx/18 86STM0623i1.pptx/18
Progressive Design-Build
Contracting Process
18 Construction
Phase
Preconstruction
Phase
Procurement
• Request for Qualifications (optional)
• Statements of Qualification Evaluation / Shortlisting (optional) • Request for Proposals
• Draft PDB Contract
• Proposal Evaluation
• PDB Team Interviews
• PDB Selection
• PDB Contract Negotiation (Preconstruction Phase Services) 17 18
6/1/2026
10 C A R O L L O / 1 9
updatefooter0323.pptx/19 86STM0623i1.pptx/19
Progressive Design-Build
Contracting Process
19 Construction
Phase
Preconstruction
Phase
Procurement
• BODR Development
• 30% Design Development
• 60% Design Development
• Value Engineering (continuous)
• Constructability Review (continuous)
• Cost Model Development (BODR/30%/60%)
• Guaranteed Maximum Pricing
C A R O L L O / 2 0
updatefooter0323.pptx/20 86STM0623i1.pptx/20
Progressive Design-Build
Contracting Process
20 Construction
Phase
Preconstruction
Phase
Procurement
• Early Works Construction (TBD)
• Design Finalization
• Project Construction
• Project Commissioning
• Project Start-up / Acceptance
19 20
6/1/2026
11 C A R O L L O / 2 1
updatefooter0323.pptx/21 86STM0623i1.pptx/21
Progressive Design-Build
Pricing Process
PDB Contractor
PDB
Design Engineer
0% 30% 60% 90% 100%
Design Definition
Design Development / Review / Value Engineering
75%
Cost Model Development
Guaranteed Maximum Price
BODR
C A R O L L O / 2 2
updatefooter0323.pptx/22 86STM0623i1.pptx/22
Progressive Design-Build
Advantages Disadvantages
Level of Control
• Inability to separately select designer or contractor (single entity contract)**
• Owner does not hold design contract**
• Qualifications-based designer and contractor selection • Single contract to manage**
• Owner substantially involved in design phase
Cost
• PDB contract price established after contract award
eliminating market price competition
• Establishing GMP sometimes difficult due to internal
misalignment of PDB team**
• Cost model developed by PDB early in project
• Innovation from PDB allows potential cost savings**
• Ability to design and deliver project to fixed budget • Efficient procurement process
Schedule
• Extended schedule potential depending on degree of
design advancement for GMP
• Shortened schedule potential depending on degree of
design advancement for GMP
Risk Allocation
• Existing conditions and permitting uncertainty prior to PDB contract**
• Collaborative relationship
• Transfer of design-related risk to PDB**
• Single point of responsibility**
• Performance guarantees available**
**Key differentiator from CMAR
21 22
6/1/2026
12 C A R O L L O / 2 3
updatefooter0323.pptx/23 86STM0623i1.pptx/23
Project Delivery Approaches
Owner
Design/
Builder
Design-Bid-Build
(DBB)
Construction
Manager-at-Risk
(CMAR)
Fixed-Price
Design-Build
(FPDB)
“Progressive”
Design-Build
(PDB)
Design-Build-Operate/
Finance, etc.

Traditional Delivery Alternative or Collaborative Delivery Owner
Design/
Builder
Owner
Designer CM
Owner
Designer Builder
Owner
Design/
Builder/
Operator
Design/
Builder Operator
Working Relationship
Contractual Relationship
Work & Service Contracts Public-Private
Partnerships
C A R O L L O / 2 4
updatefooter0323.pptx/24 86STM0623i1.pptx/24
Fixed-Price Design-Build
Contracting Process
24 Design /
Construction
Phase
Procurement
• Request for Qualifications
• Statements of Qualification
Evaluation / Shortlisting
• Request for Proposals
• Draft FPDB Contract
• Proposal Evaluation
• FPDB Team Interviews
• FPDB Selection
• FPDB Contract Negotiation
• Design Completion / Finalization
• Early Works Construction (TBD)
• Project Construction
• Project Commissioning
• Project Start-up / Acceptance
23 24
6/1/2026
13 C A R O L L O / 2 5
updatefooter0323.pptx/25 86STM0623i1.pptx/25
Fixed Price Design-Build
Pricing Process
Owner Advisor
0% 30% 60% 90%
Cost
Estimate
Cost
Estimate
Cost
Estimate
DB Team Provides Fixed Price Proposal
Design Definition (Bridging Documents)
BODR
C A R O L L O / 2 6
updatefooter0323.pptx/26 86STM0623i1.pptx/26
Fixed-Price Design-Build
Advantages Disadvantages
Level of Control
• Owner does not hold design contract
• Procurement/selection of DB more complicated than
DBB
• Design control limited to specificity of technical bridging documents
• Qualifications inclusion selection
• Single contract to manage
Cost
• Design-Builder contract price established prior to design completion necessitating pricing of some risks
• Innovation from Design-Builder allows potential cost
savings
• Early cost determination
Schedule
• Shortened schedule potential
Risk Allocation
• Existing conditions and permitting uncertainty prior to DB contract
• Transfer of design-related risk to Design-Builder
• Single point of responsibility
• Performance guarantees available
25 26
6/1/2026
14 C A R O L L O / 2 7
updatefooter0323.pptx/27 86STM0623i1.pptx/27
Summary Comparison

DBB CMAR PDB FPDB
Level of Control
• Reduced level of owner
control over design elements
for non-specified items
• Inability to separately select
designer or construction
contractor (single-entity
contract)
• Slightly reduced level of
owner control over design
elements
• Inability to separately select
designer or construction
contractor (single-entity
contract)
• High level of Owner control
over design elements
• Traditional owner-designer
relationship
• Qualifications-based
designer and contractor
selection (dual contracts)
• High level of owner control
over design elements
• Traditional owner-designer
relationship
• Little or no ability to select
based on contractor
quals/experience
Cost
• Early cost certainty through
fixed-pricing during
procurement
• PDB team generally
determines design
advancement for negotiated
GMP
• Owner directs design
advancement for negotiated
GMP
• Market price competition
Schedule
• Sequential approach • Schedule efficiencies vary • Schedule efficiencies vary • Schedule efficiencies likely Risk Allocation
• FPDB assumes design and
non-inflation price risk
• Potential for performance
guarantees
• PDB assumes design risk
• Potential for performance
guarantees
• Involvement of CMAR during
design does not relieve
owner of design risk
• Owner assumes design risk
C A R O L L O / 2 8
updatefooter0323.pptx/28 86STM0623i1.pptx/28
Delivery Model Schedule Comparison
(Hypothetical Project)
28 27
28 6/1/2026
15 C A R O L L O / 2 9
updatefooter0323.pptx/29 86STM0623i1.pptx/29
• No delivery method procurement process is inherently faster than another • Design-Bid-Build schedule impacted by:
»Extended design period
»Bid protests
• Progressive Design-Build and CMAR schedules impacted by:
»Extended preconstruction phase and GMP negotiations
»Inefficient coordination among designer/contractor/owner • Fixed Price Design-Build schedule impacted by:
»Degree of design prescription in bridging documents
Delivery Model Procurement Schedule
Considerations
Break
29 30
6/1/2026
16 C A R O L L O / 3 1
updatefooter0323.pptx/31 86STM0623i1.pptx/31
Meeting Agenda
Discussion
Lead
Item Description Approx. Time

1.0 Welcome and Introductions 8:30 – 8:32 Graham

2.0 Project Management – Action Items and Schedule 8:32 – 8:43 Graham

3.0 Goals for Workshop No. 7 8:43 – 8:45 Graham

4.0 Volume 11 – Project Delivery 8:45 – 10:15 Kyle
Break 10:15 – 10:30

5.0 Volume 11 – Project Delivery….continued 10:30 – 11:30 Kyle

6.0 Discussion 11:30 – 12:00 All
Wrap up and Next Steps 12:00 – 12:05 Graham
- Lunch

7.0 C A R O L L O / 3 2
updatefooter0323.pptx/32 86STM0623i1.pptx/32
Project Delivery Evaluation
31 32
6/1/2026
17 C A R O L L O / 3 3
updatefooter0323.pptx/33 86STM0623i1.pptx/33
Project Delivery Method Evaluation Criteria
• Legal authority for delivery method
• Project schedule
» Procurement
» Design and construction
• Degree of design control
• Transfer of risk
• Project cost considerations
» Efficiency
» Certainty
» Transparency
• Technical innovation
• Designer / contractor qualifications
• Other…?
C A R O L L O / 3 4
updatefooter0323.pptx/34 86STM0623i1.pptx/34
Project Delivery Method Evaluation Criteria
Weighting
Criterion (High / Med/ Low)
Procurement schedule
Project schedule (design and construction)
Design control
Transfer of risk
Cost efficiency
Cost certainty
Cost transparency
Technical innovation
Designer/contractor qualifications and experience
Other…?
33 34
6/1/2026
18 C A R O L L O / 3 5
updatefooter0323.pptx/35 86STM0623i1.pptx/35
Initial Thoughts? - Project Delivery Approaches
Owner
Design/
Builder
Design-Bid-Build
(DBB)
Construction
Manager-at-Risk
(CMAR)
Fixed-Price
Design-Build
(FPDB)
“Progressive”
Design-Build
(PDB)
Design-Build-Operate/
Finance, etc.

Traditional Delivery Alternative or Collaborative Delivery Owner
Design/
Builder
Owner
Designer CM
Owner
Designer Builder
Owner
Design/
Builder/
Operator
Design/
Builder Operator
Working Relationship
Contractual Relationship
Work & Service Contracts Public-Private
Partnerships
C A R O L L O / 3 6
updatefooter0323.pptx/36 86STM0623i1.pptx/36
Summary Comparison

DBB CMAR PDB FPDB
Level of Control
• Reduced level of owner
control over design elements
for non-specified items
• Inability to separately select
designer or construction
contractor (single-entity
contract)
• Slightly reduced level of
owner control over design
elements
• Inability to separately select
designer or construction
contractor (single-entity
contract)
• High level of Owner control
over design elements
• Traditional owner-designer
relationship
• Qualifications-based
designer and contractor
selection (dual contracts)
• High level of owner control
over design elements
• Traditional owner-designer
relationship
• Little or no ability to select
based on contractor
quals/experience
Cost
• Early cost certainty through
fixed-pricing during
procurement
• PDB team generally
determines design
advancement for negotiated
GMP
• Owner directs design
advancement for negotiated
GMP
• Market price competition
Schedule
• Sequential approach • Schedule efficiencies vary • Schedule efficiencies vary • Schedule efficiencies likely Risk Allocation
• FPDB assumes design and
non-inflation price risk
• Potential for performance
guarantees
• PDB assumes design risk
• Potential for performance
guarantees
• Involvement of CMAR during
design does not relieve
owner of design risk
• Owner assumes design risk
35 36
6/1/2026
19 C A R O L L O / 3 7
updatefooter0323.pptx/37 86STM0623i1.pptx/37
Typical Roles and Responsibilities

DBB CMAR PDB FPDB
City / Owner
• Administers PM/OA services
contract
• Administers design-build contract
• May administer construction
management contract
• Administers PM/OA services
contract
• Administers design-build contract
• May administer construction
management contract
• Administers PM/OA services
contract
• Administers design contract
• Administers CMAR construction
contract
• May administer construction
management contract
• Administers design contract
• Administers construction contract
• Administers construction
management contract
Owner’s Advisor
• Develops preliminary to advanced
design for bridging documents
• Implements design-build
procurement
• Provides project controls support
• May provide construction
management services
• Develops preliminary design
• Implements design-build
procurement
• Provides project controls support
• May provide construction
management services
• Develops preliminary design
• Implements designer and CMAR
contractor procurements
• Provides project controls support
• May provide construction
management services
• May provide program
management support for
procurement and controls
Design Engineer
• Advances design from bridging
level to facilitate fixed pricing
• Completes design after contract
execution
• Completes design to +/- 60% for
CMAR guaranteed maximum
pricing (Phase 1)
• Completes design (Phase 2)
• Completes design to +/- 60% for
CMAR guaranteed maximum
pricing (GMP) (Phase 1)
• Completes design (Phase 2)
• Completes 100% design
• Supports bidding process
• May provide construction
management services
Construction Contractor
• Contractor arm of DB team
constructs project in accordance
with design
• Contractor entity of DB team
develops GMP (Phase 1)
• Contractor entity of DB team
constructs project (Phase 2)
• CMAR contractor develops GMP
(Phase 1)
• CMAR contractor constructs
project (Phase 2)
• Constructs project in accordance
with 100% design
Discussion
37 38

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 12: Funding Opportunities
FINAL / October 2026

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 12: Funding Opportunities
FINAL / October 2026
Digitally signed by Graham J.G. Juby
Contact Info: Carollo Engineers, Inc.

Date: 2026.10.24 11:26:39-07'00'
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN i
p6w://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/Master Plan/Volume 12/Ch01.docx Contents
CHAPTER 1 FUNDING

1.1 Federal and State Funding 1-1

1.2 Funding Considerations 1-1

1.3 Funding Opportunities 1-3

1.4 Recommendations 1-6

1.4.1 Timing 1-6

1.4.2 Application and Costs to Apply 1-7

1.4.3 Reporting Requirements 1-8

1.5 Other Funding Programs Considered 1-8

1.6 Summary and Conclusion 1-9
Appendices

APPENDIX A CALIFORNIA CWSRF PRIORITY SCORING
Tables
Table 1.1 Federal Funding Programs 1-3
Table 1.2 State Funding Programs 1-5
Figures
Figure 1.1 General Loan Program Application Timelines 1-6 Figure 1.2 Loan Application Timeline and Project Schedule 1-7 VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN ii
Abbreviations
AIS American Iron and Steel
BABA Build America, Buy America
CDS Congressional Direct Spending
CEDS Comprehensive Economic Development Strategy
CPF Community Project Funding
CWSRF Clean Water State Revolving Fund
DAC Disadvantaged Community
DB Davis Bacon
DBE Disadvantaged Business Enterprise
EAA Economic Adjustment Assistance
EDA Economic Development Administration
EPA Environmental Protection Agency
FY fiscal year
GO General Obligation
M million
MHI median household income
NOFO Notice of Funding Opportunity
NPDES National Pollutant Discharge Elimination System
OSHA Occupational Safety and Health Act
PF principal forgiveness
Q quarter
SRF State Revolving Fund
USACE United State
USBR United States Bureau
USDA United States Department of Agriculture
WIFIA Water Infrastructure Finance and Innovation Act
WRDA Water Resources Development Act
WWTP wastewater treatment plant
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-1
CHAPTER 1 FUNDING

1.1 Federal and State Funding
Federal, state, and local grant and low-interest loan sources are available for the planning, design, and construction of water, wastewater, stormwater, and other public infrastructure projects. These programs have become more competitive due to an overall increased interest in alternate funding options and federal/state budget constraints, coupled with a nationwide, consistent increase in construction costs.

Many programs have challenging qualification processes, specific timeframes in which funds can be used, and eligibility restrictions. For example, funding sources often exclude standard maintenance projects from being eligible in order to focus on improvement projects.

With the new federal administration in 2025, there is uncertainty about the future of federal funding opportunities for water, wastewater, stormwater, and other water-related infrastructure projects. As federal agencies and departments conduct reviews to ensure grant and loan funding align with the current administration's priorities, delays in project award processing are anticipated. At this time, it is assumed that the funding opportunities highlighted in this funding matrix will continue to be available.

1.2 Funding Considerations
Examples of federal and state agencies that provide funding opportunities include the Environmental Protection Agency (EPA), Economic Development Administration (EDA), United States Bureau of Reclamation (USBR), Department of Energy, United States Army Corps of Engineers (USACE), United States Department of Agriculture, Department of Housing and Urban Development, State Revolving Funds (SRFs), and Congress, among others. Locally, the State of California's SRF program provides one of the best avenues for securing a large source of loan funding. Programs under the EPA, EDA, USACE, and others can provide sources of grant funding. Grant funding has the obvious advantage over loans in that it does not require repayment. However, these programs also typically require matching funds and are more competitive to secure.

Because of the constraints of federal and state grant and loan programs, many agencies begin by securing low-interest loan financing for the majority of the project from programs like the Water Infrastructure Finance and Innovation Act (WIFIA) and SRF. This allows the project to proceed with certainty in its financing while pursuing grants that will either provide additional funding or offset loan funding. In addition, loan funding can sometimes be used to satisfy matching fund requirements (with attention to federal funding limits). Smaller grants can also be pursued as they are helpful in building relationships with funding agencies and reducing the overall financial burden. There are numerous factors that should be considered in the pursuit of external low-interest loans and grant funding, including:
 Specific Project Priorities: Most low-interest loan and grant programs target a specific type of project or have clear purposes, priorities, and goals for their funds to be awarded. Therefore, a project should be aligned with these to be competitive. Common program goals that many grant programs focus on are that the project should:
» Build regional partnerships.

VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-2
» Enhance water conservation or efficiency.
» Protect groundwater resources.
» Provide renewable energy improvements or energy efficiency. » Address risk and resiliency.
» Demonstrate consistency with the state and regional policies and objectives. » Demonstrate regional cooperation and partnerships with partners and stakeholders. » Serve a Disadvantaged Community (DAC).
» Help create both construction and post-construction related employment.  Does Not Cover Full Project Cost: Most grant programs do not cover the full cost of the project, requiring the sponsoring agency to provide a cost share ranging from 25 to 75 percent (in-kind donations are applicable matches).
 Demonstration of Ability to Pay for Ongoing Project Expenses: Funding agencies typically require the proposed grant applicant to demonstrate the ability to operate and maintain the project without external funding.
 Funding Restrictions: Few programs allow for the retroactive funding of design and construction work, and some programs will only fund activities that are conducted post-selection for award or even require entering into an agreement prior to starting work activities.  Application Timelines: Application timing is critical for most grant and loan programs. Typically, grant programs release funding announcements once per year with a 45- to 60-day window to apply, and available funding varies from year to year pending Congressional appropriations. Low-interest loan programs typically accept applications on a rolling basis (e.g., WIFIA, SRF); however, they may require submission of pre-application materials by a prescribed date.  Award Timing: With the increased interest in external funding and limited funding agency staff availability, the review, selection, and execution of a funding agreement can take an average of 12 months (sometimes longer). In general, agencies should plan on submitting a loan application 6 to 12 months in advance of when funding will be needed and prior to construction start.  Project and Documentation Readiness: Applications may require multiple documents (e.g., engineering, environmental, and financial) to show the readiness level of the project. Assessing project document readiness early on is important to ensure the appropriate level of documentation is available to support the funding application.
 Grant Reimbursement: Most grants are reimbursements, not upfront cash. This may require that a separate source of funding (i.e., bridge loan) be available as an entity awaits reimbursement of submitted payment receipts if they do not have the cash flow to support the project. Grant reimbursements are subject to annual budget and appropriations processes and thus disbursement of grant funds on schedule is not guaranteed.
 Federal Compliance Requirements: Federal funding sources require compliance with federal requirements (also called cross cutters) including, but not limited to, American Iron and Steel (AIS), Davis Bacon (DB) Wage Determinations, anti-lobbying, Disadvantaged Business Enterprise (DBE), Build America, Buy America (BABA), Williams-Steiger Occupational Safety and Health Act (OSHA), and environmental, archeological, procurement, and reporting requirements. These conditions may add to the project's overall cost, influence project schedules, and increase the administrative burden on the borrower.

VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-3

1.3 Funding Opportunities
Tables 1.1 and 1.2 below detail several federal and state funding programs that are a possible fit for the City of Santa Maria's (City) Phase 1 Wastewater Treatment Plant Upgrade.

Table 1.1 Federal Funding Programs
Program Agency Type Description Deadlines/Next Steps Constraints Priority WIFIA EPA Loan WIFIA provides low-cost, flexible loans for water infrastructure projects, supports most aspects of project design, planning, construction, land and equipment acquisition, and more. The program provides loan funds for investments in water and wastewater infrastructure of national and regional significance by offering loans to creditworthy borrowers for up to 49 percent of eligible project costs.

Project eligibility is divided into two categories: small and large communities. A population of over 25,000 is considered a large community, and eligible projects are those that cost more than $20 million (M). Projects can be combined and submitted as a group of projects and funded under one loan if they serve a similar purpose and will be repaid from the same revenue stream. The maximum loan term is 35 years (including 5-year repayment deferment).

The interest rate is equal to the United States Treasury rate of a similar maturity, which is about 4.2 percent as of Q2 2025. Application fees apply (average $200,000 - $300,000 pending reviews and legal negotiations). The most recent notice of funding opportunity was published in Sept. 2024; it stated a funding capacity of $6.5 billion.

Applications are accepted on a rolling
basis until funding is depleted, or a
new announcement of funding ability is
announced. Begin by submitting a
letter of inquiry.

WIFIA Website
There are no direct grant
opportunities through WIFIA, but
grants can be used as match
funding as long as no more than
80 percent of the project costs
are covered by federal funds.

High
WIFIA is one of the best options for
low-interest loan funding for a
wastewater project of this size.

Community Project
Funding (CPF) and
Congressional Direct
Spending (CDS)
U.S. Congress Grant CPF and CDS are mechanisms by which members of Congress can request funding for specific projects in their home state that directly serve the public and have been submitted for consideration by state and local government entities and nonprofits to their respective congressmember or senators. Congressional District Representatives may request funding for up to 15 projects in their community under CPF, and Senators have more flexibility in the number of CDS requests, although only a handful may be funded overall. Projects with demonstrated community support are typically considered. Overall, earmarked funds are limited to no more than 1 percent of discretionary spending.

State/local match may be required.

Congressman Carbajal participates in the CPF program and has submitted large requests for regional projects, including the nearby City of Solvang's Wastewater Treatment Plan Upgrade Project in FY25 (among other programs). Senator Alex Padila has a long history of submitting Congressional Direct Spending requests. Senator Adam Schiff made CDS requests during his first term, which began in 2024.

Projects are ultimately selected by the House and Senate. If approved, the budgetary entity funding the program may request submission of an application or submission of other project information, and funds are then distributed as part of the federal appropriations process the next FY (October through September). Funds are to be spent within 1 year. Water and wastewater projects typically have a 20 percent match requirement, and municipal and private non-profit systems are eligible. Compliance with federal requirements applies.

As the FY26 opportunity has closed,
there is currently no application
available. Senators and
representatives typically post
information about the opportunities in
the first quarter of each year, and
deadlines are generally in late April.

If interested in this avenue of funding,
the City should reach out to their
congressional representative or
senators to begin soliciting support for
their project.

Link to Senate Appropriations
Link to House Appropriations
1+ year process to get
recommendation, then
dependent upon congressional
decision, which could be
improved through lobbying
efforts.

Funds must be spent within
1 year of receipt.

Federal requirements apply.

Low
All local representatives participate
in these programs.

Appropriations Requests &
Community Project Funding | U.S.

Representative Salud Carbajal
Appropriations - Senator Schiff
Appropriations - Senator Alex
Padilla
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-4
Program Agency Type Description Deadlines/Next Steps Constraints Priority Public Works and EAA
Programs
EDA Grant The program promotes long-term economic development through assistance in the construction of public works and the development of facilities needed to initiate and support the creation or retention of permanent private sector jobs in areas experiencing long-term economic deterioration and distress. The program provides funding for the construction and/or design of infrastructure to enable them to become more economically competitive. Water and sewer system improvements have historically been funded through this program.

Eligible projects must: be consistent with the region's current Comprehensive Economic Development Strategy (CEDS) or equivalent EDA-accepted regional economic development strategy, be consistent with at least one of EDA's investment priorities, lead to the creation or retention of long-term jobs that provide living wages (preferably, not seasonal), and be located in areas that meet at least one of the following criteria: low per-capita income, unemployment above the national average, or "special need" as determined by EDA.

The City's Wastewater Treatment Plant (WWTP) project would fall into the Public Works grants category, for which the average grant awards have been approximately $1.4M, with an award ceiling of $30M. Although not a defined rule, applicants may receive $15,000 per job created. Federal/non-federal cost share is 50/50 or 80/20 based on unemployment or criteria alignment. Federal requirements apply. Funding is typically awarded 6 months after a complete application is submitted.

The President's proposed FY2026 budget proposed funding cuts to EDA programs, so the future of the program is uncertain.

Applications are accepted on an
ongoing basis, if funding is available.

The FY24 Notice of Funding
Opportunity (NOFO) is the most
current, and applications are still
accepted under this NOFO.

Reach out to EDA regional
representative to discuss project and
confirm applicability.

Contact: Jeff Hays at [email protected],
(206)999-2079
Public Works and EAA Program
Website
Link to 2024 NOFO
Funded projects must be part of
an EDA-certified CEDS or
equivalent EDA-accepted
regional economic development
strategy.

Projects must be able to provide
measurable business/job growth
in the area.

The area must be considered a
low per-capita income, less than
80 percent of the national
average. The unemployment rate
must be 1 percent higher than
the national average. The City
currently meets both criteria.

Low
While the City meets the EDA's
distress criteria, the project must
show that it creates measurable
business/job growth. If the project
or a specific portion of the project
can show that, this could be a good
fit for additional grant funding.

Section 219:

Environmental
Infrastructure Program
U.S. Army Corps of
Engineers
Grant Section 219 authorizes the USACE to provide assistance to non-federal interests (e.g., local communities, water districts, sanitation districts, etc.) for carrying out water and sewer-related environmental infrastructure and resource protection and development projects. This includes projects that address emerging contaminants.

The program requires a minimum cost share of 25 percent non-federal funds. Federal funding ranges based on project type and priority, up to 75 percent federal funding. The application is a two-step process, with Congressional authorization through the Water Resources Development Act (WRDA) processed bi-annually, followed by appropriation of funds through the USACE budgetary process which requires the submission of a letter of interest, financial certification, and workplan.

This program authorized USACE to design and construct the listed project with the funding identified in the WRDA Act. The non-federal entity would not bid or complete the project construction. Rather, USACE would design and/or construct the project identified by the entity, and USACE would be in charge of managing the funding to pay for contractors and/or staff to complete the project.

The Corps must have authorization
from Congress to begin a project or
study. Must contact Regional Army
Corps representative for more
information.

Contact:

[email protected]
.mi
The City would need to work with
a Congressperson to secure
congressional authorization for
USACE to work on the project
through the next WRDA bill.

Low
Securing funding through WRDA is
a lengthy process, and the City
would give control of the portion of
the project funded to the USACE.

Notes:

CDS - Congressional Direct Spending; CEDS - Comprehensive Economic Development Strategy; CPF - Community Project Funding; EAA - Economic Adjustment Assistance; FY - fiscal year; M - million; NOFO - Notice of Funding Opportunity; Q - quarter; WRDA - Water Resources Development Act; WWTP - wastewater treatment plant
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-5
Table 1.2 State Funding Programs
Program Agency Type Description Deadlines/Next steps Constraints Priority Clean Water State Revolving Fund
(CWSRF)
California State
Water Resources
Control Board
Loan CWSRF provides low-interest loans that can also include loan forgiveness for eligible borrowers. Projects funded by the CWSRF include the construction, repair, or replacement of wastewater treatment facilities, stormwater management systems, and wastewater recycling systems. Priority is given to projects that address violations of waste discharge requirements or National Pollutant Discharge Elimination System (NPDES) permits, and projects that connect previously unsewered areas or join communities to regionalize wastewater treatment works. CWSRF also supports projects that reduce energy consumption, increase security at publicly owned treatment works, and otherwise help conservation efforts.

CWSRF loans are capped at $50M per project, but there is no limit to the percentage of project costs they can cover.

The loan rate is one-half of the most recent State General Obligation (GO) Bond Rate at the time of approval. Terms are available for up to 30 years. Principal forgiveness (PF) for a portion of the loan may be available to disadvantaged borrowers or borrowers that incorporate sustainability into projects. PF is also available for public health projects, estuary projects, water recycling, and stormwater projects.

Projects will be scored and prioritized based in part on the project's readiness to begin construction. If plans are greater than 49 percent complete on December 31, then the project will receive 1 "construction readiness point." If greater than 89 percent complete on December 31, then 2 points are given. If plans are less than 50 percent, no points are given.

Applications should be submitted by
December 31st each year to be
reviewed for inclusion on the fundable
list in the following year's Intended Use
Plan.

Review the project's priority score
based on the guidelines in Section IV.C.
of the Policy for Implementing the Clean
Water State Revolving Fund.

Competitive projects are generally
those that score a 13 or above. See
appendix A for an estimated priority
score for this project.

CWSRF Website
All federal requirements (such
as BABA) apply to this funding.

More funding is focused on
areas with low to moderate
income communities and/or
small communities.

Projects that are primarily for
growth are generally ineligible.

High
CWSRF is one of the
few funding programs
focused on wastewater
improvements and can
provide up to $50M in
funding per project.

Notes:

CWSRF - Clean Water State Revolving Fund; GO - General Obligation; National Pollutant Discharge Elimination System; PF - principal forgiveness VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-6

1.4 Recommendations
Based on the size of the project and the available funding sources, seeking low-interest loan funding for this project through the CWSRF and WIFIA program is the strategy with the highest likelihood of success.

The WIFIA program is a flexible source of low-interest loan funding and will provide up to 49 percent of the project's cost as a low-interest loan. The CWSRF program is also a low-interest loan; however, the program is capped at $50M per project. If the City decides to pursue these two programs, the City could receive up to $311M in low-interest loan funding.

1.4.1 Timing
The general application timelines of the primary recommended funding sources for this project, CWSRF and WIFIA, are included in Figure 1.1.

As shown in the figure below, the funding process for CWSRF takes about a year and a half (dates are not specific to this project; they are meant to provide a clearer idea of the timeline with a requirement to submit applications by December each year).

The WIFIA process can take up to two years, depending on how long the negotiation of loan terms takes.

The following are a few examples of factors that will speed up the WIFIA loan closing process:
 Projects for WIFIA loans are established at 30-90 percent design (either preliminary or final design stage).
 Borrower is highly rated and familiar with using debt.  Environmental studies and consultations are complete or currently underway.  Borrower has dedicated person(s) to spearhead the WIFIA process and make decisions.  Borrower largely agrees to template loan terms.

Figure 1.1 General Loan Program Application Timelines
With those timelines in mind, Figure 1.2 shows the approximate timing of loan applications in comparison to the project schedule.

VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-7
Figure 1.2 Loan Application Timeline and Project Schedule The WIFIA program recommends beginning the application process when the project is at 30 percent preliminary design. The flexibility of the WIFIA program makes it an ideal first funding source for a large project. For example, if interest rates fall, WIFIA allows for a one-time realignment of the interest rate on the loan. The program also allows for custom repayment schedules that can work around rate increases and other financial realities.

For CWSRF however, the City should wait to apply until the project final design reaches 90 percent completion to obtain the highest possible score on the priority scoring worksheet. See Appendix A for an estimate of where the project will score. In an ideal scenario, the project would be reaching 90 percent of final design near the end of the calendar year since applications are due by December 31st to be included in the following year's intended use plan. In Figure 1.2, the timeline assumes a December 2028 application date with the final design at 90 percent.

1.4.2 Application and Costs to Apply
Budgeting for both the time and cost of applying to these programs and accounting for closing costs on loan funds is important in this process. Applications for both the CWSRF and WIFIA are extensive and will require significant time to prepare. It is estimated that an experienced funding team would need around 300 to 350 labor hours to complete a full application. It is proposed that the City budget approximately $110,000 for this effort for each loan application.

Closing costs and administrative fees are also important to budget for when applying to these programs.

For the CWSRF program in California, there is an administrative service charge of up to 1 percent of the outstanding loan balance. This fee is pulled from the interest rate payments and does not add an additional fee to the loan.

The WIFIA program requires a down payment of $100,000 at the time of application submission. The application will not be evaluated until the down payment has been paid. The down payment goes toward any external counsel used to assess the project and loan conditions and is credited to the credit processing fee. The credit processing fee reimburses EPA for its costs to provide a loan. The credit processing fee varies for each transaction and is determined by a variety of factors, including the complexity of the transaction, borrower history with the WIFIA program, and the extent of legal negotiations. After the application down payment, the WIFIA program estimates the remaining costs due after loan closing to be between $50,000 to $150,000 per applicant. Therefore, the application down payment and credit processing fee could cost up to $250,000.

The WIFIA program also charges borrowers an annual loan servicing fee that accounts for activities such as credit accounting, collections, maintenance of documents, financial reporting, and construction VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-8
monitoring. In the period prior to substantial completion of the project, the annual loan servicing fee will range from $10,000 to $25,000. After substantial completion, the annual loan servicing fee is typically under $10,000 for all borrowers.

1.4.3 Reporting Requirements
CWSRF Reporting Requirements
If awarded a loan through CWSRF, the recipient must submit progress reports at least quarterly. The reports should detail the status of project activities, starting with the issuance of the executed Financing Agreement and ending on final reimbursement, and must contain at least the following information:
 A summary of progress to date, including a description of progress since the last report, percent complete, percent invoiced, and percent schedule elapsed.  A listing of Change Orders, including amount, description of work, and change in contract amount and schedule.
 Any problems encountered, proposed resolutions, schedule for resolutions, and status of previous problem resolutions.
 A summary of compliance with environmental conditions, if applicable.

WIFIA Reporting Requirements
The WIFIA program requires that borrowers submit financial condition reports to:
 Provide an oversight tool for ensuring each borrower's compliance with the provisions of the loan agreement.
 Monitor the overall status of the project and the WIFIA program.  Assist it in identifying any changes to the credit risk posed to the federal government under individual loan agreements.

WIFIA loan agreements will specify scheduled (e.g., monthly, quarterly, annual, or project milestone) reporting requirements, as well as any other periodic reporting requirements. These reporting requirements are included in the loan agreement and are tailored to the characteristics and risks of the project and the borrower. Disbursement requests may be made as frequently as once per month.

1.5 Other Funding Programs Considered
In addition to the list of funding opportunities discussed above, Carollo Engineers' (Carollo) funding team conducted research into many other funding programs and agencies. A few main factors precluded the City's project from being eligible for many of these funding programs.

The City's population is about 109,000 people, which therefore precludes the project from being eligible for any program that focuses on small communities. For example, the United States Department of Agriculture (USDA) Water and Waste Disposal Loan and Grant Program provides funding to rural communities of less than 10,000 people.

A second factor is the median income in the area, which is low enough to qualify for some programs like the Public Works and EAA Programs, but too high to be considered disadvantaged/low income for other VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-9
programs. For example, the City does not qualify for principal forgiveness through the CWSRF because the median income of the City is higher than 80 percent of the state median income (which is around $77,000).

The focus of the project also makes it difficult to qualify for funding. Most funding programs that fund wastewater projects are generally geared towards supporting water recycling efforts. The lack of a water recycling program rules out many programs, including most funding opportunities, though the United States Bureau of Reclamation and other large grant programs, such as the Water Recycling Funding Program through the State of California.

1.6 Summary and Conclusion
Pursuing low interest loans for this project has the highest likelihood of successfully securing the funding needed.
 WIFIA:
» The WIFIA program is the funding opportunity with the highest chance of success for obtaining a large low-interest rate loan for this project. The City held a virtual meeting with a WIFIA program representative in September 2025 to discuss the best way to move forward with seeking funding and support from the WIFIA program. WIFIA likes to see funded projects completed within 5 to 7 years.
» The program will fund up to 49 percent of the project costs. Santa Maria could receive up to $261M in low-interest loan funding for this project if approved by the WIFIA program. » The City should begin the application process when the project's preliminary design is at 30 percent.
» Fees for applying for a WIFIA loan could be up to $250,000. » The City should budget to spend about $110,000 for the loan application process.  California CWSRF:
» In early 2026, a general application (the first step in the application process) was submitted to the CWSRF program for the Percolation Ponds Project. The estimated score will be 13 if at least 50 percent of the design has been completed by December 2026 (see Appendix A for the estimated score).
» The California CWSRF is focused on funding wastewater and stormwater projects and is the next best option for additional loan funding for this project. » To be competitive, the project should score at least a 13 on the priority scoring system found within the Policy for Implementing the Clean Water State Revolving Fund. » The program caps all loans at $50M, regardless of the project costs. » The City should budget to spend about $110,000 for the loan application process.

If approved for the maximum loan amounts, the City of Santa Maria could obtain up to $311M in low-interest loan funding to complete the necessary upgrades for the Phase 1 Project.

VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA

WASTEWATER TREATMENT PLANT MASTER PLAN

APPENDIX A CALIFORNIA CWSRF PRIORITY SCORING
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN A-1
Priority Scoring Estimation
The California Clean Water State Revolving Fund (CWSRF) is a promising funding opportunity for the project. However, the project must score high enough on the CWSRF priority scoring worksheet to present a competitive application for this program. The estimated priority score for the percolation pond project is discussed below. Carollo assisted the City in submitting the general application package in the spring of 2026; the following estimated score information reflects what was submitted.

Table A.1 Project Score
Resource or Impact Purpose
Corrective Preventive Improvement
Drinking Water Source 10 9 6
Nutrient Removal 8 6
Water Recycling - - 8
Water Quality Control Plan or Permit, or Impaired Water Body 8 7 4 The estimated score for Santa Maria's percolation ponds project is an 8 because the project will prevent future violations of the plant’s permit related to the capacity of the ponds.

Table A.2 Secondary Score (Maximum Score of 3)
Secondary Score Score
Applicant volunteers this project to meet SRF's equivalency requirements, meaning all federal crosscutting requirements will apply. (Projects may be selected to meet necessary equivalency requirements associated with the funding source, regardless of whether the applicant volunteers.) 3 Project eliminates a discharge of waste regulated by a Regional Water Board or the State Water Board (e.g., regionalization, consolidation, or septic-to-sewer projects). 2 Project is cited in a multi-agency regional environmental management plan or has multi-media environmental benefits.
2 The applicant agrees to provide funds to match federal capitalization grants by agreeing to the match financing option.
2 The estimated score for Table A.2 is a 3, as the City of Santa Maria (City) will need to meet the State Revolving Fund's (SRF's) equivalency requirements (meaning all federal crosscutting requirements, such as Build America, Buy America (BABA), will apply to the project).

VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN A-2
Table A.3 Affordability Score (Maximum Score of 5)
Secondary Characteristics
<80% of State MHI ≥80% and <100% of State MHI ≥100% and ≤150% of State MHI Small (≤20,000) Not subject to scoring 2 2
Medium (>20,000 and
≤100,000)
2 1 0
Large (>100,000) 1 0 0
Sewer Rates as a Percentage of MHI:
 <1% of MHI
 ≥1% and <1.5% of MHI
 ≥1.5% of MHI
0
1
2
Offers Rate Assistance 1
Notes:

MHI - median household income
According to the U.S. Census Bureau, the state of California's MHI is $100,149. Based on this data, 80 percent of the state MHI is $80,119. The median household income in the City is $74,986 with a 2020 census population of 109,707 people (according to the U.S. Census Bureau). This places the City in the chart above as a large community with an MHI of less than 80 percent of the state MHI and awards a score of one for this item.

Based on the "Notice of Proposed Rate Increases to Water and Sewer Rates for 2024-2027," the current monthly sewer rate for a single-family residential household is $36.40 per month, or $436.80 annually.

This annual rate represents approximately 0.5 percent of the local MHI, which awards the City a score of zero for this item. Lastly, as the City does not offer rate assistance, the score for this item is also zero.

Overall, the City scores an affordability score of one.

Table A.4 Readiness Score (Maximum Score of 2)
Application or Design Status Score
Plans and Specifications:
 ≥90% as verified by Division staff
 ≥50% as verified by Division staff
2 1
Consent to use of a funding agreement template as posted on the Division's website
(Requires a satisfactory certification form submitted with application documents) Remaining Capacity Process-eligible
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN A-3
The current project schedule shows that design of the percolation pond will be at least 50 percent by December 2026, therefore, the City would receive 1 point for their readiness score. The priority score estimated worksheet that was submitted noted this score as zero. This can be resubmitted later in the process to note this change to the project schedule.

Table A.5 Total Estimated Priority Score
Scoring Element Estimated Score for the Project
Project Score 8
Secondary Score 3
Affordability Score 1
Readiness Score 1
Total Estimated Priority Score 13
While the priority score needed to get on the fundable list varies from year to year, the score needed on the most recent intended use plan for 2026-2027 is 13. This project scores an estimated 13 points and could be a competitive project for CWSRF funding.

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 13: Support Facilities
FINAL / October 2026

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 13: Support Facilities
FINAL / October 2026
Digitally signed by Graham J.G. Juby
Contact Info: Carollo Engineers, Inc.

Date: 2026.10.24 11:27:44-07'00'
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN i
pw://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/Master Plan/Volume 13/_Cover_TOC_Abbrevs_AppxCovers.docx Contents
CHAPTER 1 PLANT WATER SYSTEMS

1.1 Purpose/Background 1-1

1.2 City Water System 1-1

1.2.1 Fire Suppression 1-4

1.3 Softened Water System 1-6

1.4 Utility Water System 1-8

1.4.1 Utility Water Quality 1-8

1.4.2 Projected Utility Water Demand 1-10

1.4.3 Tertiary Filtration System Capacity 1-11

1.4.4 Layout Considerations 1-12

1.4.5 Comparison of Alternatives 1-22

1.4.6 Other Tertiary Filtration Considerations 1-23
CHAPTER 2 PLANT DRAINAGE AND STORMWATER

2.1 Introduction 2-1

2.2 Plant Drainage System 2-1

2.2.1 Phase 1 Plant Drainage Considerations 2-2

2.3 Stormwater System 2-3

2.3.1 Phase 1 Plant Stormwater Considerations 2-5
CHAPTER 3 INSTRUMENT AIR AND PROPANE

3.1 Introduction 3-1

3.2 Instrument Air 3-1

3.2.1 Phase 1 Considerations 3-1

3.3 Propane System 3-3

3.3.1 Phase 1 Considerations 3-3
CHAPTER 4 UTILITY BUILDING, MAINTENANCE, AND LABORATORY

4.1 Introduction 4-1

4.2 Utility Building 4-2

4.2.1 Phase 1 Utility Building Considerations 4-2

4.3 Maintenance Building 4-4

4.3.1 Phase 1 Maintenance Building Considerations 4-4

4.4 Storage Building 4-4

4.4.1 Phase 1 Storage Building Considerations 4-4

4.5 Laboratory 4-5

4.5.1 Phase 1 Laboratory Considerations 4-5

4.6 City Yard 4-5

4.6.1 Phase 1 City Yard Considerations 4-5
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN ii
CHAPTER 5 SEPTAGE HANDLING

5.1 Septage Overview 5-1

5.2 Septage Sampling Results 5-3

5.2.1 First Sampling Event - September 2024 5-3

5.2.2 Second Sampling Event - Major Haulers - March/April 2025 5-5

5.2.3 Third Sampling Event - June 2025 5-8

5.2.4 Fourth Sampling Event - July to August 2025 5-9

5.2.5 Comparison of Sampling Events 5-10

5.2.6 Impact of Current Septage Loads on Effluent Quality 5-12

5.3 Proposed Modifications to the Septage Receiving Area 5-12

5.3.1 Debris Removal 5-12

5.3.2 Septage Equalization Basin for Influent Metering 5-18

5.3.3 Return Activated Sludge Treatment of Septage 5-18

5.3.4 Conceptual Layouts 5-19

5.3.5 Planning Level Cost Estimates 5-22

5.4 Conclusion 5-27
Appendices

APPENDIX A TERTIARY FILTER PILOT STUDY REPORT
APPENDIX B HEADWORKS SAMPLING RESULTS - SEPTEMBER 2024
APPENDIX C PFAS SAMPLING RESULTS - SEPTEMBER 2024

APPENDIX D SUMMARY OF CONSTITUENTS IN MAJOR HAULER SAMPLING

APPENDIX E RESULTS FROM MAJOR HAULER SAMPLING
APPENDIX F HEADWORKS SAMPLING RESULTS - JUNE 2025

APPENDIX G COMPARISON OF LOADING EVENTS
Tables
Table 1.1 Treated Effluent Re-use Regulations 1-9
Table 1.2 Projected Utility Water Demands for Each Facility After Phase 1 Expansion 1-10 Table 1.3 Layout Alternative 1 Cost Estimate 1-17
Table 1.4 Layout Alternative 2 Cost Estimate 1-19
Table 1.5 Layout Alternative 3 Cost Estimate 1-20
Table 4.1 New Utility Building Features 4-3
Table 5.1 Summary of Septage as Percentage of Influent Flow for Various WWTPs 5-1 Table 5.2 Summary of September 2024 Sampling Event - Flows 5-3 Table 5.3 Summary of Results From First Sampling Event - September 2024 - BOD5, TKN, and NH3(1) 5-4
Table 5.4 Contribution of Septage to Influent BOD, NH3, and TKN Load - September 2024 (Adjusted for 24-Hour Period) 5-4
Table 5.5 List of the Eight Septage Haulers and Their Annual Flow Contribution 5-5 VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN iii
Table 5.6 Average Concentrations for Constituents Sampled for Each Major Hauler 5-7 Table 5.7 June 2025 Sampling Event Results 5-8
Table 5.8 July/August 2025 Sampling Event Results 5-10
Table 5.9 Summary of Septage Loading Contributions and Planning Range 5-11 Table 5.10 Preliminary Sizing for Huber RotaShield Units 5-17 Table 5.11 Preliminary Design Criteria - Booster Pump Station 5-22 Table 5.12 Septage Station Improvements Cost Estimate - Level 1 - Improved Screening Only 5-23
Table 5.13 Equalization Basin and Metering Cost Estimate - Level 2 - Small Equalization and Return to Headworks 5-23
Table 5.14 Septage Treatment Cost Estimate - Level 3 - Full Treatment 5-24 Table 5.15 Preliminary O&M Costs for Septage Treatment - Based on Level 3 5-25 Table 5.16 Preliminary Unit Cost for Septage Treatment - Based on Full Treatment - Level 3 5-25
Figures
Figure 1.1 Existing Utility Water Tank Configuration 1-2 Figure 1.2 City Water Tie-In Connection Points As-Builts - Sourced Courtesy of City of Santa Maria 1-3
Figure 1.3 Existing Plant Water Distribution Schematic 1-5 Figure 1.4 Approximate Location of Existing Fire Hydrants 1-6 Figure 1.5 Existing Softened Water Distribution Schematic - Phased Out 1-7 Figure 1.6 Layout Alternative 1 - Chlorine Contact Tank With Tertiary Filters in the South 1-14 Figure 1.7 Example of Tertiary Filter Installation 1-15 Figure 1.8 Layout Alternative 2 - Intermediate Clarifier With Tertiary Filters Located Centrally 1-18
Figure 1.9 Layout Alternative 3 - Tertiary Filters South of Facility with Intermediate Clarifier Storage 1-21
Figure 2.1 High-Level Drainage Pattern for Plant Drain System 2-1 Figure 2.2 Plant Drainage Pump Station 2-2
Figure 2.3 High-Level Surface Water Stormwater Drainage Pattern 2-3 Figure 2.4 High-Level Stormwater Pumping Schematic 2-4
Figure 2.5 East Supernatant Pit Pump Station 2-5
Figure 3.1 High-Pressure Air (Instrument Air) Schematic 3-2 Figure 3.2 Propane Storage Cylinder 3-3
Figure 4.1 Plant Operations and Maintenance Support Buildings 4-1 Figure 4.2 Utility (Left Portion - 1961) and Maintenance (Right Portion - 1979) Buildings 4-2 Figure 4.3 Preliminary Location of New Utility Building and Other Facilities 4-4 Figure 5.1 Existing Septage Receiving Area at Entrance to WWTP 5-2 Figure 5.2 Existing Septage Receiving Area at Entrance to WWTP 5-2 Figure 5.3 Septage Contributions From Major Haulers - November 2023 to November 2024 5-6
Figure 5.4 Septage Loading From Major Haulers 5-7
Figure 5.5 Influent Area Piping Elevations 5-9
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN iv
Figure 5.6 Septage Loading Comparison Between Sampling Events 3 and 4 - TSS and TDS 5-10
Figure 5.7 Septage Loading Comparison Between Sampling Events 3 and 4 - NH3 and Total Nitrogen 5-11
Figure 5.8 Examples of Septage Station Improvement Features Utilizing Manually Cleaned Screens 5-13
Figure 5.9 Huber RotaShield Septage Acceptance Units 5-15 Figure 5.10 Huber RotaShield Field Trial - November 2025 5-16 Figure 5.11 Existing Pipe Orientation at the Septage Receiving Station With the Canopy 5-18 Figure 5.12 Proposed Septage Improvements for Equalization and Return to Headworks 5-20 Figure 5.13 Proposed Septage Improvements for Full Treatment Showing Three Alternative Locations 5-21
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN v
Abbreviations
µg/L micrograms per liter
BOD biochemical oxygen demand
BOD5 5-day biochemical oxygen demand test
City City of Santa Maria
COD chemical oxygen demand
DI ductile iron
F Fahrenheit
gpcd gallons per capita day
gpd gallons per day
gpd/ac gallons per day per acre
gpm gallons per minute
hp horsepower
kWh kilowatt-hour
lb/day pounds per day
M million
MCL maximum contaminant level
MG million gallons
mg/L milligrams per liter
mgd million gallons per day
mg-min/L milligrams per minute per liter
mL milliliter
MPN most probable number
msl mean sea level
N/A not applicable
ND not detected
NH3 ammonia
NH3-N ammonia-nitrogen
NL notification level
NTU nephelometric turbidity unit
O&M operations and maintenance
OSHA Occupational Safety and Health Administration
PFAS per- and polyfluoroalkyl substances
PFBS perfluorobutanesulfonic acid
PFHxA perfluorohexanoic acid
PFHxS perfluorohexanesulfonic acid
PFOA perfluorooctanoic acid
PFOS perfluorooctanesulfonic acid
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN vi
PS primary sludge
psi pounds per square inch
PTF primary trickling filter
PVC polyvinyl chloride
RAS return activated sludge
RL response level
ROC reactive organic compound
RUL remaining useful life
RV recreational vehicle
RWQCP regional water quality control plant
RWRF regional water reclamation facility
SCADA supervisory control and data acquisition
scf standard cubic feet
scfm standard cubic feet per minute
STF Secondary Trickling Filter
TDS total dissolved solids
TKN total Kjeldahl nitrogen
TSS total suspended solids
UV ultraviolet
UW utility water
V volt
VFD variable frequency drive
VOC volatile organic compound
VSS volatile suspended solids
WAP Wash and Press
WAS waste activated sludge
WRF water reclamation facility
WTP water treatment plant
WWTP wastewater treatment plant
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-1
CHAPTER 1 PLANT WATER SYSTEMS

1.1 Purpose/Background
This chapter discusses the existing and proposed water systems at the City of Santa Maria's (City) Wastewater Treatment Plant (WWTP), including City-supplied water and a proposed utility water system.

The plant currently uses City-supplied water for washing down equipment, and other utility uses to support liquid and solid treatment processes. Historically, these functions were fulfilled by an on-site well prior to the City supply becoming available. The on-site well is still operable as a standby source. There was also a separate softened-water system, but it was decommissioned as of 2024.

The planned expansions and modifications to the existing WWTP as part of the Phase 1 improvements project, presented in the other Volumes of this Master Plan, will significantly alter the treatment process and require a much larger volume of utility water to support operation. Purchasing City water to meet these higher demands will substantially increase the cost and also add to the total volume of water requiring disposal in the percolation ponds. For these reasons, a new utility water system that uses treated effluent for plant water is being evaluated. The analysis of this system is presented in this chapter.

Other WWTP support systems are discussed in Volume 13, Chapters 2, 3, and 4. The septage receiving system is discussed in Chapter 5.

1.2 City Water System
As mentioned, the WWTP was previously served by water from a local well. The City water distribution system now connects to the well header, which incorporates a small hydropneumatic tank to provide a buffer volume and a pressure regulator that controls pressure at 72 pounds per square inch (psi).

A pressure blowoff, set at 75 psi, is provided as a safety measure. An air release valve is also included.

Figure 1.1 shows a schematic of the previous well system, which now serves as the backup to City water.

VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-2
Figure 1.1 Existing Utility Water Tank Configuration
The City water connection point into the system was made in 2024. The new connection is made at the indicated pad in Figure 1.2. A 6-inch pipeline comes in from the 12-inch distribution pipe located on Black Road to connect to the valving and pump system on the pad. From that system, a 4-inch water distribution line sends flow to the site. An 8-inch fire line from the 12-inch distribution line on Black Road connects to the hydrant to provide fire suppression. The pipeline then connects with a series of valves and regulators that furnish the required pressure for the plant system.

Figure 1.2 illustrates the locations of the new connection point and highlights where the 6-inch City water line ties in with the plant distribution system. Figure 1.2 also indicates the water connection point to the fire hydrant located adjacent to the plant water distribution system.

VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-3
Figure 1.2 City Water Tie-In Connection Points As-Builts - Sourced Courtesy of City of Santa Maria VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-4
Because the City water is currently the only high-pressure water source at the treatment plant, it must be used for the pump seal water systems (although the plant has moved away from using flushed seals for pumps in recent years), supply for the boiler makeup water, and for all hose bibbs.

There are two City water connections to the plant: one 4-inch line that provides water to the Operations Building and a separate 4-inch line that provides water to the various plant areas for uses such as washdown, boiler water makeup, etc. A schematic showing the distribution lines servicing the plant facilities, taken from the Operation and Maintenance Manual, is shown in Figure 1.3. Note that Figure 1.3 does not reflect the updated connection points highlighted in Figure 1.2 but indicates the existing distribution lines from that point to the remainder of the plant.

As shown in Figure 1.3, the distribution system for water is extensive. This will need to be modified when the plant moves to a separate utility water system, discussed later.

1.2.1 Fire Suppression
Currently, the WWTP has four fire hydrants that are connected to the City water distribution system. The approximate locations are shown by the yellow placemarks in Figure 1.4. The fire hydrants are currently rated to deliver 85 psi of static pressure. In addition, there are approximately 13 hand-held fire extinguishers located around the plant. As part of the Phase 1 project, the fire suppression system will remain on City water.

Additional fire hydrants, probably two, may need to be added in the area of the plant that will house the new activated sludge system and blower building, and serve the solids thickening and dewatering areas.

The location of these hydrants will be confirmed during preliminary design.

VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-5
Figure 1.3 Existing Plant Water Distribution Schematic
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-6
Figure 1.4 Approximate Location of Existing Fire Hydrants

1.3 Softened Water System
In the past, potable water supplied to the Laboratory and Operations Building was treated for hardness by passing it through a water softener. The soft water system was eliminated when City water was connected to the plant in 2024, and the old soft water supply header line was used to supply "potable" water to the offices. The soft water distribution system within the WWTP yard is still underground (see Figure 1.5) but not in use and has been disconnected near the office buildings to avoid any cross-connections with water used in the WWTP processes.

This system is used to distribute softened water from the water softeners located in the Storage Building to the Laboratory, the Utility Building, the Primary Sludge Pump Station, the Secondary Sludge Pump Station, and the Digester No. 1 Control Building.

For the Phase 1 project, it is not anticipated that softened water will be needed. This will be confirmed during the Preliminary Design phase, at which time a decision can be made on whether to keep or remove the existing distribution system piping.

VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-7
Figure 1.5 Existing Softened Water Distribution Schematic - Phased Out VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-8

1.4 Utility Water System
This section presents an evaluation of a new utility water system to support the anticipated plant water demands associated with the operation of the future Phase 1 liquids and solids treatment processes. It summarizes existing treated effluent regulations and provides regulatory justification for the choice of utility water quality. The evaluation also considers alternative locations for the chosen treatment system, preliminary layouts for the major utility water pipework, and the estimated cost.

1.4.1 Utility Water Quality
Utility water systems at municipal WWTPs in California typically utilize treated wastewater effluent as the plant process water. Some systems combine the fire water system as part of the utility water system or have a separate potable water system that provides potable water uses and fire suppression. As discussed, it has been assumed that, for the Phase 1 expansion, the existing and any new fire hydrants would remain on potable City water.

Because of the volume of water required for the Phase 1 Utility Water System, using City water would be both cost-prohibitive and add significant water to the system, increasing loading for the percolation ponds. Accordingly, the City is evaluating the use of treated effluent for the washdown and maintenance operations required under the Phase 1 improvements.

1.4.1.1 Worker Health and Title 22 Requirements
Recycled water is typically subject to strict treatment requirements, as specified in Title 22 of the California Code of Regulations. Title 22 provides guidelines for the quality of recycled water that is to be used for processes, which are presented in Table 1.1. Three qualities of treated wastewater effluent are permitted for reuse under Title 22, namely: Disinfected Secondary - 23, Disinfected Secondary - 2.2, and Disinfected Tertiary. These are listed in order of increasing quality, with Disinfected Tertiary being the highest quality.

The first two only differ in the level of disinfection that is required.

However, pursuant to an exception noted in Section 60303 of Title 22 of the California Code of Regulations, the regulations do not apply to recycled water used on-site at a water recycling plant or wastewater treatment plant if public access is restricted. The City restricts public access to the wastewater facility and, therefore, will not be required to hold a Title 22 permit for the re-use of treated effluent within the plant.

The treatment regulations under Title 22 are noted in Table 1.1. However, these are informative only, as the City will not be subject to the allowable uses and monitoring requirements indicated therein.

VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-9
Table 1.1 Treated Effluent Re-use Regulations
Title 22 Regulatory Standard Treatment Requirements Allowable Uses Disinfected Secondary - 23 Disinfection that reaches:
 7-day median total coliform < 23 MPN/100 mL.
 One sample per 30 days > 240 MPN/100 mL.
 Industrial cooling without mist
generation.
 Boiler feedwater.
 Industrial process water that
does not contact humans.

Disinfected Secondary - 2.2 Disinfection that reaches:
 7-day median total coliform < 2.2 MPN/100 mL.
 One sample per 30 days > 23 MPN/100 mL.
 Industrial cooling without mist
generation.
 Boiler feedwater.
 Industrial process water that
does not contact humans.

Disinfected Tertiary(1) Disinfection that reaches:
 7-day median total coliform < 2.2 MPN/100 mL.
 One sample per 30 days > 23 MPN/100 mL.
 > 450 mg-min/L Contact Time with > 90-minute
overall contact time.

Media filtration that reaches:
 24-hour average Turbidity < 2 NTU.
 Max Turbidity no more than 5% of time: < 5 NTU.
 Landscape irrigation in public
access areas.
 Food crop irrigation.
 Recreational impoundments.
 Dual-plumbed systems (e.g.,
building reuse).
 Industrial processes where
worker contact may occur.

Notes:
mg-min/L - milligrams per minute per liter; mL - milliliter; MPN - most probable number; NTU - nephelometric turbidity unit (1) A Title 22 permit will not be required unless the tertiary effluent is used for off-site recycled water purposes, which is not the intention.

Although the City is not required to comply with the regulations, worker health should be considered. The future utility water system will include hose bibbs for general washdown, spray systems in the aeration basins, and the solids thickening and dewatering areas, which can create mist, among other uses.

Accordingly, there is a high likelihood that there will be human contact with the water. Only Disinfected Tertiary effluent meets the quality requirements for these uses. Accordingly, Disinfected Tertiary effluent is recommended as the water supply for the proposed future utility water system to protect worker health.

The related requirements and monitoring noted in Table 1.1 will not apply, allowing the City to preserve worker health without the stringent monitoring that would be required under typical Title 22 permits.

1.4.1.2 Suspended Solids Considerations
An additional key consideration in evaluating the water quality for the utility water system is ensuring a system that reliably conveys flow without causing obstructions or blockages. Disinfected Secondary - 23 and 2.2 will contain more suspended solids than Disinfected Tertiary, and may lead to regrowth within the distribution network and sloughing of solids, which could block small orifices, including valves, seals, and sprays.

Operators at a plant with both tertiary- and secondary-treated utility water systems report that disinfected secondary effluent has led to higher biomass growth and operational issues in the plant's water system.

VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-10

1.4.1.3 Disinfection Efficacy Considerations
A third consideration related to the plant water quality is the ability of a new disinfection system to achieve worker safety protection and regulatory standards. The three primary disinfection systems utilized in municipal WWTPs are chlorination, ultraviolet (UV) irradiation, and ozonation. Design manuals and observational evidence indicate that the disinfection efficiency for each disinfection approach improves with increasing water quality, which is lower turbidity and lower organic content. Accordingly, tertiary filtered water will be easier to disinfect compared to the other qualities.

1.4.1.4 Water Quality Recommendation
Considering the three key factors governing the utility water system, it is recommended that a tertiary filtration and disinfection system be provided for the plant water supply. Disinfected tertiary effluent will allow the WWTP to preserve worker health, reduce the likelihood of biomass growth in the plant water distribution system, and allow the disinfectant residual to last longer. This filtration standard and recycled water use will not require a Title 22 permit.

1.4.2 Projected Utility Water Demand
Preliminary estimates of the projected utility water demand for the new Phase 1 Improvements are shown in Table 1.2. These values will need to be updated/revised during the preliminary design phase. The average utility and peak utility water demands are depicted in gallons per minute (gpm). Note that safety shower and emergency eye-wash facilities will all be provided with potable water.

Table 1.2 Projected Utility Water Demands for Each Facility After Phase 1 Expansion Facility Reclaimed Water Utilities Included
Average Daily
Demand (gpm)
Peak Hourly
Demand (gpm)
Septage Station 9 50 1 Hose Bibb in service 10 hours/day Screening/ Headworks 5 20 Hose Bibb
Grit Chambers 5 60 Hose Bibb and Grit Flushing
Primary Clarifiers 10 40 Hose Bibb and Scum Spray
Primary Effluent Pump Station 5 20 Hose Bibb
Bardenpho - Aeration Basins 225 1,500 Spray Water and Hose Bibbs Secondary Clarifiers 20 40 Hose Bibb and Scum Spray
Tertiary Filter Feed Pumps 5 20 Hose Bibb
Tertiary Filter Backwashing System 5 20 Polymer, Hose Bibb Effluent Pump Station 5 40 Hose Bibb
PS Thickening 25 120 Polymer, Hose Bibb, Spray Water
WAS Thickening 60 120 Polymer, Hose Bibb, Spray Water
Anaerobic Digesters 15 40 Hose Bibb
Sludge Storage 5 40 Hose Bibb
Dewatering (screw press) 80 1,150 Polymer, Hose Bibb, Spray Water Cake Storage Area 5 20 Hose Bibb
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-11
Facility Reclaimed Water Utilities Included
Average Daily
Demand (gpm)
Peak Hourly
Demand (gpm)
Blower Building 5 40 Hose Bibb
Boilers 5 30 Make Up Water and Hose Bibb
Irrigation 25 100 General Irrigation
Ponds 5 20 Hose Bibb
Electrical Building 2 20 Hose Bibb
Admin Building 0 0 Potable Water Only
Maintenance Building 0 0 Potable Water Only
Sum 526 3,500
Safety Factor 1.2 -
Design Flow (gpm) 632 3,500
Design Flow (mgd) 0.91 5.0
Notes:
mgd - million gallons per day; PS - primary sludge; WAS - waste activated sludge Table 1.2 indicates that the most significant contributors to the utility water system will be the aeration basins and the solids thickening and dewatering processes. The large peaks reflect the washdown periods and scum spraying that are typically required for these processes based on existing flows. As indicated, the anticipated daily average flow is expected to be close to 1.0 mgd, including a 20 percent safety factor.

This would equate to about 10 percent of the Phase 1 treatment plant design flow, which is a reasonable estimate for planning purposes. The actual utility water uses should be confirmed during the preliminary design phase of the project once equipment selections have been made.

1.4.3 Tertiary Filtration System Capacity
In order to size the tertiary filtration system, the average daily demand flow shown in Table 1.2, together with the 20 percent safety factor, was used as the basis, which is approximately 1 mgd.

The peak-hour flow could be as high as 3,500 gpm (5.0 mgd) and would be provided from a suitable storage tank. Historical influent flow data indicates that effluent flow, even during low diurnal periods, does not decrease below about 2 mgd. Therefore, it is anticipated that there will be sufficient effluent flow to allow the average daily utility water demand to be met at all times.

1.4.3.1 Peak Storage
Utility water systems require peak storage to meet demand instantaneously. The peak storage will be sized to accommodate one hour of demand flow as indicated in Table 1.2, that is, 3,500 gpm, 5.0 mgd, or 210,000 gallons.

There are two potential options for peak storage. The first is the construction of a new aboveground or belowground tank. This will address any fluctuations in flow and serve demand when it is required. It will also provide contact time for disinfection with chlorine.

VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-12
The second is the utilization of the existing intermediate clarifier. According to Volume 4 of this Master Plan, the condition assessment of the intermediate clarifier assessed a remaining useful life of up to 20 years. The assessment noted that some spalling and wear in the concrete had been observed.

However, this can be repaired, and the reclaimed tertiary effluent is less corrosive than the wastewater the clarifier currently receives, allowing for potential reuse of this structure. This would reduce the cost of providing storage volume.

According to the 2008 Expansion Record Drawings, the intermediate clarifier is sized for 1.92 hours of detention time at a flow of 3.6 mgd. This corresponds to a volume of 288,000 gallons, which is sufficient to provide up to 4,800 gpm of flow for one hour of peak utility demand, more than is needed. The tank would need to be recoated, and a new covering would likely need to be installed to maintain chlorine residuals and reduce algal growth.

1.4.4 Layout Considerations
Three layout alternatives were evaluated for a tertiary filtration and peak storage facility that will initially serve the plant's disinfected utility water demands while preserving the ability to expand to full tertiary treatment of the plant effluent in the future, should the City elect to do so. Each alternative below illustrates the site area required to accommodate a total of four filters. However, the planning-level cost estimates within this chapter assume that only two filters will be installed initially (one duty and one standby) during Phase 1 to meet the immediate utility water demand. The allocated space can accommodate individual filters up to 2.5 mgd average flow in size, but equipment costs assume use of two 1 mgd filters to match the utility water needs. This phased approach minimizes initial capital costs while providing infrastructure capable of expanding to approximately 10 mgd of filtration capacity within the initial structure before additional structural expansion is required. For each alternative, the layout, tertiary filtration and peak storage facilities, major piping requirements, and planning-level cost estimate are presented. Final layout and costs for the tertiary filtration and utility water system are presented in Volume 6, Chapter 5 with the final project selection.

Alternative 1 locates the filters south of the Percolation Pond pump station and incorporates the construction of a new peak storage demand tank and chlorine contact facility to attenuate peak demand.

Alternative 2 places the filters closer to the intermediate clarifier, to the north of the Percolation Pond pump station. Alternative 3 locates the filters in the same place as Alternative 1, but also uses the intermediate clarifier for storage.

It has been assumed that the disinfection approach will be to use sodium hypochlorite solution, which will be dosed in two locations: directly downstream of the filter(s) to provide a residual entering the storage tank, and then downstream of the utility water pumps using an inline injector and static mixer to provide a residual in the plant distribution system.

Each alternative considers the size of the required piping and pumping for the facilities. Each layout alternative is considered in more detail below.

1.4.4.1 Alternative 1 - Tertiary Filters and Construction of Contact Tank This alternative includes the construction of a chlorine contact tank that will serve as a peak storage buffer to supply the utility water system during peak demand. Secondary effluent from the Percolation Ponds Pump Station influent box will be pumped to the tertiary filters, located south of the Percolation Ponds VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-13
Pump Station. This location keeps the filter system away from other areas of the plant where Phase 1 construction activities are anticipated. Filtered effluent will gravitate to a below-grade storage tank. From the tank, the average demand for the utility water system will be provided by a new utility water pump station that would discharge into the utility water distribution system.

Any excess filtered water will overflow from the storage tank to the Percolation Pond Pump Station for discharge to the percolation ponds. Tertiary filter backwash will be pumped to either the headworks or directly to the primary clarifier influent splitter box. The layout for this alternative is shown in Figure 1.6, which shows the preliminary layout of the Phase 1 facilities and location of the tertiary filters, and includes a preliminary layout of the utility water distribution system, shown in red. As indicated, there would be two loops within the plant: one incorporating the septage receiving area in the north, and a second incorporating the activated sludge process and the solids treatment area to the west.

VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-14
Figure 1.6 Layout Alternative 1 - Chlorine Contact Tank With Tertiary Filters in the South VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-15
Tertiary Filter Footprint
It is anticipated that the tertiary filtration facility will include a chemical containment facility for chlorine solution storage and addition located adjacent to the tertiary filters. Chlorine will be dosed immediately downstream of the filter and also in the discharge of the utility water pumps. It is anticipated that the system will be constructed with a metal canopy, similar to that shown in Figure 1.7, which the City may wish to enclose.

Figure 1.7 Example of Tertiary Filter Installation
The tertiary filter system is expected to have a footprint of 72 feet by 25 feet, corresponding to a space footprint of 1,800 square feet, and will include duty and standby filters, each sized for a production rate of

1.0 mgd.

The peak volume storage tank will be sized with the following parameters:
 0.3 million gallons (MG; one hour of peak flow).
 70 feet long by 38 feet wide by 17 feet high.
» 2,660 square feet of space required.

The anticipated sodium hypochlorite dosing rate will be between 2 and 5 milligrams per liter (mg/L).

Piping and Pumping
The primary utility water pipeline will be a 14-inch C900 polyvinyl chloride (PVC) line that is sized for the peak flow of 5.0 mgd at a maximum velocity of not more than 6 feet per second. A 14-inch pipe will be able to accommodate the peak flows while also reaching minimum velocities for average flows. A 12-inch C900 pipe with a parallel bypass from the chlorine tank may be necessary to handle peak flows from the VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-16
utility water pumps. In this Alternative 1 layout, the pipe will be connected to a wet well at the edge of the storage tank. The pumps required to service this flow will be sized with the following parameters:
 15 percent minor losses.
 Approximately 4,400 feet of pipeline (14-inch C900 pipe).  10 feet of static head.
 5.5 mgd of peak flow.
 Delivering 72 psi to match the existing potable water system.  The pumps will be sized to accommodate both average flow and peak flows while maintaining high pump efficiency.
» Two 700-gpm pumps in a duty-standby configuration will be installed to accommodate the average flows during regular operation, with a control panel to allow switching of the duty pump to reduce wear on individual pumps.
» When demand cannot be met from the smaller pumps, larger 1,400-gpm pumps in a 2-duty-1-standby configuration will progressively be brought into service to meet the peak flow.

The pumps will be able to handle 166 feet of head.
» Pumps will be fitted with variable frequency drives (VFDs) to adjust flow to meet demand. At average flow, the VFD can ramp down to around 30 to 50 percent of standard flow to accommodate average demands.

The power demand for the pumps is anticipated to be 42 horsepower (hp) and 84 hp for the 700 and 1,400 gpm pumps, respectively. The pumps could be vertical turbine or submersible types and will be connected to the storage tank outlet and the utility water system. Details would be established during preliminary design.

Flow from the tertiary filters will gravitate to the peak storage basin. When the storage tank is full, there will be an overflow weir that will convey excess filtered effluent by gravity to the Percolation Pond Pump Station.

The elevations and heads for this alternative are:
 Grade elevation at tertiary filters: 158 feet (18-inch slab on grade).  Outlet elevation tertiary filters: 163.8 feet.
 Inlet elevation for contact tank: 162.0 feet.
 Utility Water Pump Station Inlet: ranges from 144.8 to 160.2 feet.

There is sufficient head to gravitate from the tertiary filters to the storage tank and from the storage tank to the Percolation Pond pump station.

Cost Estimate (Alternative 1)
The anticipated cost for this alternative (Class 5 estimate) is shown in Table 1.3 and includes the costs of the tertiary filters, the shade structure, disinfection, piping, the peak flow storage tank, and the utility water pumps. The total project cost is estimated at $10.9 million.

VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-17
Table 1.3 Layout Alternative 1 Cost Estimate
Item Description Amount
1 Tertiary Cloth Filters and Storage Basin
 Site Construction. $565,000
 Structural Work. $911,400
 Cloth Filters, Pumps, Backwash Chemicals, Equipment, etc. (1+1 Duty/Standby, 1.0 mgd each).
$1,150,000
2 Utility Water System Piping $1,410,000
3 Electrical (15%) $610,000
4 Instrumentation and Controls (10%) $350,000
Subtotal - Direct Costs $4,990,000
5 Contingency (30%) $1,496,000
6 Contractor Mark-ups (General Conditions, Overhead and Profit) (30%) $2,182,000 7 Sales Tax (Based on 50% of the Direct Costs at 8.75%) $284,000 Estimated Construction Cost $8,950,000
8 Engineering and Construction Management (17%) $1,520,000 9 Legal Admin and Regulatory Costs (5%) $450,000
Total Project Cost $10,915,000

1.4.4.2 Alternative 2 - Tertiary Filters and Re-use of Intermediate Clarifier Alternative 2 will utilize the existing intermediate clarifier as the storage tank to supply peak demand. As noted above, the structure for the intermediate clarifier could be rehabilitated and reused for the storage of disinfected filtered effluent. In this case, the tertiary filters will be located north of the Percolation Pond pump station. This location was selected to allow tertiary filters' effluent to easily flow by gravity to the intermediate clarifier.

This location is more central within the existing plant and is more likely to impact construction sequencing and construction of new anaerobic digesters for the Phase 1 project, but would reduce the overall cost of the proposed system by reusing the existing structure.

Tertiary Filter Footprint
The footprint requirements and arrangement of equipment would be similar to Alternative 1.

Secondary effluent would be sent to the filters from the Percolation Pond Pump Station Influent Box. The filter backwash would be returned to the headworks or directly to the primary clarifiers, similar to Alternative 1. The layout for Alternative 2 is shown in Figure 1.8.

VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-18
Figure 1.8 Layout Alternative 2 - Intermediate Clarifier With Tertiary Filters Located Centrally VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-19
Piping and Pumping
The piping and pumping system configuration would be similar to Alternative 1.

There would be about 60 feet between the tertiary filter and the intermediate clarifier. Based on anticipated levels, there would be sufficient head to gravitate to the intermediate clarifier from the indicated location.

Cost Estimate (Alternative 2)
The cost for this alternative (Class 5 estimate) includes the costs of the tertiary filters, an overhang, pumping, disinfection, piping, and the rehabilitation of the intermediate clarifier. Table 1.4 highlights the cost estimate for this alternative.

Table 1.4 Layout Alternative 2 Cost Estimate
Item Description Amount
1 Tertiary Cloth Filters and Intermediate Clarifier
 Site Construction. $276,000
 Structural Work and Intermediate Clarifier Rehab. $615,000  Cloth Filters, Pumps, Backwash Chemicals, Equipment, etc. (1+1 Duty/Standby, 1.0 mgd each).
$1,177,000
2 Utility Water System Piping $1,306,000
3 Electrical (15%) $506,000
4 Instrumentation and Controls (10%) $310,000
Subtotal - Direct Costs $4,190,000
5 Contingency (30%) $1,260,000
6 Contractor Mark-ups (General Conditions, Overhead and Profit, 30%) $1,833,000 7 Sales Tax (Based on 50% of the Direct Costs at 8.75%) $266,000 Estimated Construction Cost $7,516,000
8 Engineering (17%) $1,280,000
9 Legal Admin and Regulatory Costs (5%) $380,000
Total Project Cost $9,170,000

1.4.4.3 Layout 3 - Tertiary Filters and Re-use of Intermediate Clarifiers at South Location
The next alternative utilizes the same location for the filters as Alternative 1, south of the Percolation Pond pump station, but in this case, the existing intermediate clarifier would be used as the storage tank to supply peak demand, similar to Alternative 2. As noted, the structure for the intermediate clarifier could be rehabilitated and reused for the storage of disinfected filtered effluent. It is anticipated that this location will still allow the filtered effluent to flow by gravity to the intermediate clarifier; however, the filter slab will need to be raised to accomplish this.

Similar to Alternative 1, this location for the filters would keep the bulk of the activities away from where the Phase 1 contractor would be doing most of the work. Reusing the intermediate clarifier would take up VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-20
space originally allocated to new anaerobic digesters, but a preliminary analysis has shown that there would still be adequate space to locate both new digesters in the remaining area.

Tertiary Filter Footprint
The layout of the equipment and the required footprint for Alternative 3 would be the same as the previous alternatives, and backwash water would be directed to the headworks or the primary clarifiers.

Figure 1.9 shows the preliminary layout.

Piping and Pumping
The piping and pumping requirements for this alternative would be the same as for Alternative 2, with a new utility water pump station located adjacent to the existing intermediate clarifier.

There would be about 500 feet between the tertiary filter and the intermediate clarifier. To allow for flow by gravity from the filters to the intermediate clarifier, the filters would need to be raised about 42 inches.

Cost Estimate (Alternative 3)
The cost for this alternative (Class 5 estimate) includes the costs of the tertiary filters, an overhang, pumping, disinfection, piping, and the rehabilitation of the intermediate clarifier. Table 1.5 provides the details of the items included in the cost estimate for Alternative 3.

Table 1.5 Layout Alternative 3 Cost Estimate
Item Description Amount
1 Tertiary Cloth Filters and Intermediate Clarifier
 Site Construction. $283,000
 Structural Work and Intermediate Clarifier Rehab. $750,000  Cloth Filters, Pumps, Backwash Chemicals, Equipment, etc. (1+1 Duty/Standby, 1.0 mgd each).
$1,177,000
2 Utility Water System Piping $1,378,000
3 Electrical (15%) $540,000
4 Instrumentation and Controls (10%) $331,000
Subtotal - Direct Costs $4,450,000
5 Contingency (30%) $1,340,000
6 Contractor Mark-ups (General Conditions, Overhead and Profit, 30%) $1,950,000 7 Sales Tax (Based on 50% of the Direct Costs at 8.75%) $255,000 Estimated Construction Cost $7,992,0000
8 Engineering (17%) $1,360,000
9 Legal Admin and Regulatory Costs (5%) $400,000
Total Project Cost $9,750,000
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-21
Figure 1.9 Layout Alternative 3 - Tertiary Filters South of Facility with Intermediate Clarifier Storage VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-22

1.4.5 Comparison of Alternatives
Three potential layout options for implementing tertiary filters and supplying utility water as part of the Phase 1 upgrades were evaluated. The first alternative (Alternative 1), while more expensive (at $10.9 million) due to the construction of an additional peak volume storage tank, offers significant advantages in terms of construction sequencing and spatial availability. The filter system location south of the Percolation Pond pump station facilitates easier access, allows for future expandability, and keeps the filters out of the area where a majority of the Phase 1 construction work is anticipated.

Alternative 2 proposes reusing the existing intermediate clarifier, saves about $1.7 million, and results in the lowest project cost estimate ($9.2 million). This approach, however, introduces the potential for spatial congestion near the solids dewatering area and anaerobic digesters, which could complicate future construction during the Phase 1 upgrades as well as daily operations.

Alternative 3, which places the tertiary filters in the same location as Alternative 1, is about $0.5 million more than Alternative 2 (at $9.75 million). It remains a lower-cost alternative with the re-use and rehabilitation of the intermediate clarifier for storage while reducing the spatial congestion and removing some construction sequencing constraints. This alternative will require the filters to be installed above grade for gravitational hydraulics from the filters to the intermediate clarifier, but that is a minor cost addition. Further, if the intermediate clarifier must be decommissioned for some reason in the future, the layout provides adequate space in the adjacent area to construct a new peak storage tank, similar to Alternative 1.

Reusing the intermediate clarifier to provide peak flow storage and disinfection volume presents a cost-effective and functionally viable solution for achieving Phase 1 goals. Accordingly, the preferred option is to proceed with using tertiary filtration and disinfection, and the use of the intermediate clarifier for storage as part of the planned initial phase of upgrades. Due to Phase 1 construction and sequencing activities, it would seem that Alternative 3 would be the preferred approach, but a closer look at the construction sequencing and potential conflicts associated with Alternatives 2 and 3 might show that Alternative 1 is the better choice. This can be done as part of the preliminary design.

Conclusion
A separate new utility water system utilizing an average of 1.0 mgd of tertiary filtered secondary effluent from the new Phase 1 activated sludge treatment process was evaluated as an approach to replace potable water for plant process water needs. Three alternatives were considered to provide an average flow of 1.0 mgd and a peak hour flow of 5.0 mgd. The cost of the new system is expected to range between $9.2 million on the low end if the filters are located closer to Digester 4 and the existing intermediate clarifier is utilized for storage and disinfection volume (Alternative 2), and up to $10.9 million if the filters are located south of the existing Percolation Pond pump station and a new storage/disinfection tank is constructed (Alternative 1). Alternative 3, which locates the filters to the south (like Alternative 1) but also makes use of the intermediate clarifier for storage, has an estimated project cost of $9.75 million and seems to be the most favorable approach because it keeps the filters out of the way of future Phase 1 construction activities. The location associated with Alternative 2 could be investigated further during preliminary design.

VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-23

1.4.6 Other Tertiary Filtration Considerations

1.4.6.1 Use of Tertiary Filters as Part of Phase 1 Treatment Geotechnical investigations of the soils in the existing percolation ponds in 2024 showed that the top layers of the existing soil contained a lot of fine organic material. These are presumably solids from the secondary effluent that have settled and built up over a long period of time, contributing to the gradual reduction in percolation rate observed by the City. This is reported in more detail in Volume 7, Chapter 2, together with strategies to periodically remove the fine organic solids layer from the bottom of the ponds.

Due to the observed effects on percolation pond capacities by the accumulation of organic material, the City recognized the benefits that percolation of tertiary filtered effluent, rather than secondary effluent, would have for long-term maintenance of the ponds. Because of this, the City would like to approach tertiary filtration with the near-term goal of providing equipment capacity to produce the necessary utility water to serve the WWTP, with the ability to expand the facility in the future to provide partial or full treatment of the plant effluent prior to discharge in the percolation ponds. Details are provided in Volume 6, Chapter 5, which shows a larger tertiary filtration facility located in the same location as shown for Alternative 3 above. The remainder of the Utility Water system, including the use of the intermediate clarifier, would be operated as discussed above.

1.4.6.2 Tertiary Filtration of Trickling Filter Secondary Effluent In 2024, the City began a pilot study to evaluate whether tertiary filtration of the existing trickling filter secondary effluent would be effective at reducing both 5-day biochemical oxygen demand test (BOD5) and total suspended solids (TSS) concentrations to below the interim effluent limits defined by the new General Permit. The study was a requirement stipulated by the Regional Water Board, the intention being that temporary treatment facilities be provided to meet the interim effluent limits until such time as the new Phase 1 facilities were constructed.

The pilot study demonstration that some reduction in the BOD5 and TSS concentrations was achievable, but ultimately implementation of temporary facilities would take considerable time to design and construct, therefore providing limited effluent quality benefits for the capital and operating cost, while introducing complications to the treatment plant and the plant expansion process. Therefore, the Regional Water Board agreed that the studies to be performed by the City for interim BOD5 and TSS compliance were complete, and a temporary filtration system would not be required. Appendix A includes the Tertiary Filter Pilot Study Report.

VOLUME 13 / CHAPTER 2: PLANT DRAINAGE AND STORMWATER
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-1
CHAPTER 2 PLANT DRAINAGE AND STORMWATER

2.1 Introduction
This chapter describes the existing plant drainage and stormwater systems. Both systems will need to be modified and upgraded as part of the Phase 1 Project, but their overall functionality is expected to remain similar to the existing systems.

2.2 Plant Drainage System
Figure 2.1 provides an aerial view of the wastewater treatment plant (WWTP) and indicates the approximate drainage pattern for the plant drains. Currently, there are two plant drainage pump stations in the WWTP. The majority of office bathrooms, digester emergency overflows, and plant drains within the WWTP gravitate to a submersible pump station located near the boiler area, a photograph of which is shown in Figure 2.2. This pump station is equipped with two 3.4-horsepower (hp) submersible pumps, which return flow to the grit basins.

Figure 2.1 High-Level Drainage Pattern for Plant Drain System VOLUME 13 / CHAPTER 2: PLANT DRAINAGE AND STORMWATER
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-2
Figure 2.2 Plant Drainage Pump Station
A second pump station collects drainage from the Digester No. 4 Building and Digester No. 4 overflow box and pumps it into the Plant Drainage discharge line that transfers flow to the first pump station. This pump station is equipped with two 1.5-hp submersible pumps.

In addition, a catch basin at the 1961 headworks north of the grit chamber conveys flow to the Primary Trickling Filter (PTF) Pump Station.

The Primary Building and the Grit Chambers have independent drainage systems that discharge flow into the grit chamber overflow box.

In addition, the Secondary Clarifier Sludge basement area has its own sump and pump. It discharges to the Secondary Clarifier No. 2 launder recirculation box.

2.2.1 Phase 1 Plant Drainage Considerations
The new Phase 1 facilities will require an expansion of the plant drainage system, details of which will be developed during the preliminary design. Overall, the concept will be to continue to use the existing plant drainage pump station located near the boiler area and return plant drainage water to the grit basins. The rehabilitation could either be a full rehabilitation of the existing plant drainage pump, with new pumps, guide rails, controls, and piping, or the construction of a new plant drainage pump station adjacent to the one shown. In addition, new plant drain pump station (s) will either pump to the existing pump station or transfer flow directly to the grit basins.

VOLUME 13 / CHAPTER 2: PLANT DRAINAGE AND STORMWATER
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-3

2.3 Stormwater System
The existing stormwater system at the WWTP is primarily based on surface water drainage. Most of the runoff is conveyed through concrete gutters or the existing slopes to the east supernatant pit or to the asphalt-lined sludge beds. The East Supernatant Pit occasionally drains to the West Supernatant Pit when there is excess flow from both surface runoff and sludge bed drainage. From the beds, the stormwater is decanted to the supernatant pump, which rejoins other drainage lines and sends collected runoff to the head of the plant. In addition, as much of the site is gravel, a large portion of the stormwater directly percolates into the soil.

There are three areas where the surface water slopes do not convey runoff to the sludge beds or supernatant pit: the Grit Chamber Ramp, the PTF Pump Station, and the Secondary Trickling Filter (STF) Area. At the Grit Chamber Ramp, runoff falls into a sump and is pumped into the Grit Chamber Effluent Box. At the PTF Pump Station, there is a gravity line that runs north, connects with the floor drain at the 1961 headworks, and drains to the PTF Pump Station. At the STF Area, water flows to a sump in the Secondary Sludge basement, then to the STF Pump Station, and is returned to the headworks.

Figures 2.3 and 2.4 illustrate the existing stormwater drainage patterns that constitute the stormwater system.

Figure 2.3 High-Level Surface Water Stormwater Drainage Pattern VOLUME 13 / CHAPTER 2: PLANT DRAINAGE AND STORMWATER
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-4
Figure 2.4 High-Level Stormwater Pumping Schematic
The East Supernatant Pit contains a 3-inch, 5-hp self-priming pump that connects to the 6-inch supernatant line that returns runoff and sludge bed supernatant to the Grit Chamber. The supernatant pit, shown in Figure 2.5, is in poor condition and will likely need to be rehabilitated ahead of the Phase 1 construction to continue receiving stormwater. Duty/standby pumps, new discharge/collection piping, and concrete rehabilitation will be included as part of that pit rehabilitation.

VOLUME 13 / CHAPTER 2: PLANT DRAINAGE AND STORMWATER
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-5
Figure 2.5 East Supernatant Pit Pump Station

2.3.1 Phase 1 Plant Stormwater Considerations
For the Phase 1 project, most of the sludge drying beds are to be demolished and replaced with aeration basins and secondary clarifiers. Once Phase 1 processes are operational, the existing primary and secondary trickling filter systems will be demolished. Overall, once the Phase 1 project is complete, the impervious surface area will be similar to the current WWTP or somewhat less, depending on the final sizing and layout of new facilities. Nevertheless, it is anticipated that additional stormwater conveyance and pump stations will need to be constructed.

As mentioned, the concrete in the supernatant pit is in poor condition, but once that structure has been rehabilitated, it can continue to serve as a basin for future stormwater collection. Captured storm flow from future pump sumps that are installed for surface water drainage could be routed to this pit for transfer to the head of the plant for treatment. No stormwater will drain from the site; it will all be contained and treated through the WWTP.

VOLUME 13 / CHAPTER 3: INSTRUMENT AIR AND PROPANE
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 3-1
CHAPTER 3 INSTRUMENT AIR AND PROPANE

3.1 Introduction
This chapter describes the existing instrument air and propane gas systems at the City of Santa Maria's (City) wastewater treatment plant (WWTP). Both of these systems will remain in place for the Phase 1 Project, but both may need to be modified and potentially upgraded as part of the expansion.

3.2 Instrument Air
The purpose of the instrument air supply is to provide filtered, dry, high-pressure air to treatment plant instrumentation and to air tool connectors throughout the plant. The distribution of high-pressure air is shown in Figure 3.1. Individual compressors have been installed at the headworks, primary sludge pump station building, the digester building, and the 2009 Digester Control 4 Building to supply air to the local systems, which use it for control purposes. The plant's high-pressure air supply is still also available at those locations. The local compressors increase the reliability of the air supply to the equipment.

Two tank-mounted, two-stage reciprocating piston air compressors provide clean, filtered air at between 98 and 140-145 psi to each dedicated air receiver (tank). The compressors are equipped with pressure switches to automatically start and stop the units at set pressures.

There are isolation valves at the old digester control building, the primary sludge building, secondary sludge pump station, new Digester 4 Control Building, and headworks to allow isolation of the main air system and local connection of portable compressors to keep these systems in operation in case the main air system must be taken out of service. High-pressure air is necessary for operating the bubblers at the headworks in order to control the screen cleaning cycles and also for operating the heat control and digester control valves. Portable compressors can be connected to the quick-connect couplings near these locations.

The air compressors and receivers are located in the Maintenance Building. For details, refer to Figure 3.1.

3.2.1 Phase 1 Considerations
The City has decided to move away from air-operated actuators, so all actuators provided as part of the Phase 1 Project will be electric. However, the existing instrument air system will need to be retained to support existing instruments that still use air. In addition, the City may wish to have high-pressure air connections at other parts of the plant associated with the new Phase 1 facilities for powering air tools.

These requirements and the impacts on the high-pressure air compressor sizing and distribution system will be finalized during the preliminary design phase of the project.

VOLUME 13 / CHAPTER 3: INSTRUMENT AIR AND PROPANE
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 3-2
Figure 3.1 High-Pressure Air (Instrument Air) Schematic VOLUME 13 / CHAPTER 3: INSTRUMENT AIR AND PROPANE
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 3-3

3.3 Propane System
The WWTP does not have a supply of natural gas piped to the site; instead, it uses propane. Liquid propane gas is stored on the treatment plant grounds and provides a pilot flame for the sludge heating hot water boiler and for the waste digester gas burner. The potable water heater is fueled with propane.

Propane gas can also be piped to the boiler as a standby fuel source, or the propane-powered standby boiler in the digester building can be used. The City receives deliveries of 550 gallons of propane every 3 weeks if the propane standby boiler isn't running. If the standby boiler is running, a propane delivery is required every two to three days. A photograph showing the location of the propane storage cylinder is shown in Figure 3.2.

Figure 3.2 Propane Storage Cylinder

3.3.1 Phase 1 Considerations
The existing propane gas system will need to be maintained during and after the Phase 1 expansion project in order to support critical plant operations, including the sludge heating via the hot water boiler, waste gas digester gas burner, potable water heater, and the standby boiler. Careful planning during the project's preliminary design phase will be required to maintain an uninterrupted propane supply and ensure safe system operation while construction activities are underway. Key considerations include protecting the existing liquid propane storage tank and distribution piping from potential damage, ensuring adequate access for refueling, and coordinating tie-ins or modifications to avoid service disruptions. Any expansion of heating or standby fuel demands will also need to be evaluated against current storage and supply capacity to determine whether system upgrades or additional redundancy are warranted. Safety compliance, including adherence to fire code clearances, separation distances, and pressure regulation requirements, must be maintained throughout Phase 1 construction. These items will all be addressed as part of the preliminary design.

VOLUME 13 / CHAPTER 4: UTILITY BUILDING, MAINTENANCE, AND LABORATORY OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 4-1
CHAPTER 4 UTILITY BUILDING, MAINTENANCE, AND

LABORATORY

4.1 Introduction
This chapter describes the existing utility, maintenance, and laboratory buildings at the plant and the proposed upgrades and modifications required as part of the Phase 1 Project. It is anticipated that this chapter will be updated as the design progresses and the need for modified and/or additional facilities to support the operation of the expanded treatment facility becomes clearer.

The locations of the major buildings on the site that provide support for plant operations and maintenance are shown in Figure 4.1. The City of Santa Maria (City) does not have a separate Corporate Yard, and the existing wastewater treatment plant (WWTP) serves that role too.

Figure 4.1 Plant Operations and Maintenance Support Buildings VOLUME 13 / CHAPTER 4: UTILITY BUILDING, MAINTENANCE, AND LABORATORY OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 4-2

4.2 Utility Building
It is not clear exactly when the existing Utility Building was constructed, but the 1961 Plans show either an expansion or modification of an existing structure, which is still present today. In 1979, the building was expanded to the north to create a Maintenance portion, which also still exists. Figure 4.2 shows a photograph of the two buildings, with the 1961 Utility Building on the left portion of the photograph and the Maintenance Building on the right portion.

Figure 4.2 Utility (Left Portion - 1961) and Maintenance (Right Portion - 1979) Buildings

4.2.1 Phase 1 Utility Building Considerations
A new utility building will be constructed as part of Phase 1 of the project. It is currently envisioned that the new utility building will be approximately 3,000 square feet and will include a workspace area and a storage area. The utility building will include a restroom equipped with hot and cold water, windows, and skylights for natural light, and outdoor light fixtures. Hose bibs will be located both inside and outside of the utility building, and access to the building will be monitored using outdoor security cameras and an alarm system. Table 4.1 lists the features that will be included in the new utility building.

VOLUME 13 / CHAPTER 4: UTILITY BUILDING, MAINTENANCE, AND LABORATORY OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 4-3
Table 4.1 New Utility Building Features
Proposed New Utility Building Features/Facilities
Workspace Area
Air conditioning to meet OSHA indoor requirements.

Industrial or shop-grade wash sink for hand washing.

Floor drains.

Workbench space along walls with tool storage drawers and shelves underneath.

Movable workbench island (4 feet by 8 feet) to work on larger items.

Welding bench/area.

Industrial-grade shelving on walls.
120V, 240V, and 480V available to supply power for hand tools, welders, and to accommodate bench testing of 480V equipment.

Compressed air.

Bench grinder.

Chop saw.

Vise.

Drill press.

Ventilation system to allow for indoor welding or painting.

Pipe storage on rack on wall.

Fire protection system.

Roll up door to access workshop area.
2-ton minimum shop/bridge crane.

Roll-up door access to adjacent parts/vehicle storage.

At least one man door to access the shop.

Storage Area
Vehicle storage area that is tall enough to house a vactor truck or loader.

At least one man door to access the vehicle storage area.

Notes:

OSHA - Occupational Safety and Health Administration; V - volt Figure 4.3 shows a preliminary location for the new Utility Building. The existing structure will need to be demolished, and the new building will be located to the south. This will create some space to the north of the existing building to allow the road to be widened to increase the turning radius to accommodate dewatered sludge hauling trucks. Existing Digesters 2 and 3, as well as the existing Gravity Thickener No. 1, would also be demolished. The area shown in Figure 4.3 would allow for about a 3,000-square-foot Utility Building with space for the new Anaerobic Digesters. The final location, size, and internal division of space within the building will be determined during the Preliminary Design phase.

VOLUME 13 / CHAPTER 4: UTILITY BUILDING, MAINTENANCE, AND LABORATORY OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 4-4
Figure 4.3 Preliminary Location of New Utility Building and Other Facilities

4.3 Maintenance Building
The Maintenance Building is currently connected to the Utility Building, as described above.

4.3.1 Phase 1 Maintenance Building Considerations
A separate Maintenance Building is not planned as part of the Phase 1 project. Rather, the proposed new Utility Building will incorporate a portion dedicated to maintenance activities, similar to the current arrangement. The features/facilities to be incorporated in the new Utility Building are presented in Table 4.1.

4.4 Storage Building
The Storage Building was constructed in 1996, and its condition was evaluated during the plantwide condition assessment (see Volume 4 for details). The structure was assessed to have about 20 years of remaining useful life (RUL). The northern portion of the building houses general storage, and the southern portion houses office space, a large meeting room, and ablution facilities. The ablution facilities do not include separate male and female facilities.

4.4.1 Phase 1 Storage Building Considerations
Since the building has a RUL of about 20 years, it will remain in place for the Phase 1 project and may be considered for replacement during a future plant expansion. The building does require some ongoing maintenance, but these repairs will be taken care of as part of a separate project to the Phase 1 project.

VOLUME 13 / CHAPTER 4: UTILITY BUILDING, MAINTENANCE, AND LABORATORY OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 4-5

4.5 Laboratory
The laboratory at the City's WWTP conducts water and solids analyses to keep the operators informed of plant efficiencies, and to help predict problems that are developing in the process, and to comply with the current permit requirements for the WWTP. Laboratory test results are a record of plant performance and are evaluated by governing, regulatory, and private consulting agencies.

The Laboratory was constructed as part of the Operations Building in 1982. It is well equipped and expected to have more than 20 years of RUL.

4.5.1 Phase 1 Laboratory Considerations
Because the Phase 1 treatment process will be significantly different to the current treatment plant and because the new permit now requires analysis for total nitrogen, in addition to a BOD5 and TSS, it is likely that some upgrading of the existing laboratory will be included in the Phase 1 project. The details of what upgrades will be required will be developed during the Phase 1 design process.

4.6 City Yard
As noted above, the City does not have a dedicated City Yard and currently makes use of the WWTP facilities for this purpose, for example, to hold all-hands meetings or staff training events.

4.6.1 Phase 1 City Yard Considerations
As the design of the Phase 1 facilities develops, and there is more definitive information on the sizing and location of new buildings and structures, the City will be in a better position to decide what additional modifications will be required to accommodate its needs for a City Yard. It is anticipated that these modifications could include additional vehicle parking spaces, additional maintenance facilities, and potentially larger meeting room space.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-1
CHAPTER 5 SEPTAGE HANDLING

5.1 Septage Overview
The City WWTP accepts septage from industrial, commercial, and domestic customers. It is one of the few locations in the region (Santa Barbara and San Luis Obispo Counties) where septage haulers may dump.

Most of the other WWTPs in the area do not have septage receiving facilities. As a result, the City receives significantly more septage flow compared to other WWTPs of similar size. The City's WWTP typically receives septage from 54 different septage haulers. The gate to the WWTP is open for septage receiving between 7:00 a.m. and 3:30 p.m. Monday-Thursday and from 7:00 a.m. to 1:30 p.m. on Fridays.

In the one-year period between November 2023 and November 2024, a total of 11.5 million gallons (MG) of septage was received at the WWTP. An informal survey of selected Southern California WWTPs that receive septage was conducted in 2024 and 2026. Table 5.1 shows a summary of the information obtained for the WWTPs and City, and presents the septage flow as a percentage of the average WWTP influent flow rate. As shown, the City's contribution from septage haulers is significantly greater than all the other WWTPs surveyed, at around 0.7 percent of the influent flow, which is between 1.7 to about five times greater than the others. In addition, all WWTPs listed in Table 5.1 operate activated sludge processes, except for Santa Maria, which operates a trickling filter process.

Table 5.1 Summary of Septage as Percentage of Influent Flow for Various WWTPs Treatment Plant Average Influent Flow
Rate to WWTP (mgd)
Total Daily Septage Flow
(gallons)
Percentage Contribution
of Septage to Average
Influent Flow
City of Riverside - RWQCP 26.9 33,000 0.12%
Eastern Municipal Water District -
San Jacinto Valley RWRF

8.0 12,000 0.15%
Eastern Municipal Water District -
Perris Valley RWRF

14.0 35,000 0.25%
Inland Empire Utilities Agency -
Regional Plant No. 1

26.0 30,000 - 35,000 0.14%
City of Fresno WWTP(1) 54.0 210,000 0.39%
City of Santa Maria WWTP 6.6(2) 44,000(3) 0.67%
Notes:
mgd - million gallons per day; RWQCP - regional water quality control plant; RWRF - regional water reclamation facility (1) Information obtained during a visit on April 21, 2026. Typically receive 50 - 60 trucks per day. The station is open 7-days per week (5 a.m. to 5 p.m.) but typically only receives 20 - 30 loads on Saturdays and <15 loads on Sundays. (2) Based on monthly average influent flow for 12 months starting November 2023 from self-monitoring reports. (3) Based on one year of data, November 2023 to November 2024; 11.4 MG and 260 days available for dumping.

In addition to the disproportionately high septage contribution at Santa Maria, observations from operational staff and from previously recorded data suggest that septage can produce slug loads on the plant and affect effluent biochemical oxygen demand (BOD) and total suspended solids (TSS) concentrations. As such, the City conducted sampling to determine the significance of the septage on the organic and nitrogen loads entering the plant.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-2
Figures 5.1 and 5.2 highlight one of two septage receiving areas at the WWTP. The other receiving area is designated for septage that may contain large debris and rags, and haulers are required to discharge the septage through an in-ground screen/grating, which is later manually raked to remove captured material.

Material removed from the screen/grating is manually placed into a dumpster. Both receiving areas connect directly to a 48-inch manhole, which then diverts flow to one of two incoming 48-inch influent pipes through a 60-inch diversion manhole.

Figure 5.1 Existing Septage Receiving Area at Entrance to WWTP Figure 5.2 Existing Septage Receiving Area at Entrance to WWTP VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-3

5.2 Septage Sampling Results
To obtain additional information on the quality of septage being received, the City conducted four separate sampling events between September 2024 and August 2025. Each sampling effort aimed to quantify the organic and nitrogen loading entering the plant from septage haulers.

5.2.1 First Sampling Event - September 2024
In September 2024, the City collected composite samples upstream and downstream of the septage receiving station in order to assess the impact of septage dumping on the concentrations and loads of BOD, ammonia (NH3), and total Kjeldahl nitrogen (TKN) entering the WWTP.

Three separate 8-hour composite samples, coinciding with the septage receiving period, were collected a week apart and analyzed for NH3, TKN, and BOD. Automatic samplers were set up to collect a sample every 15 minutes and sampling began at 8:00 a.m. prior to the first septage haulers entering the plant.

Two samples were collected upstream of the septage dumping locations, from the north and the south trunk mains at Junction Box A', and the third sample was collected downstream of the septage dumping locations at the headworks. The volume of septage dumped on each of the sampling days was recorded, as well as the influent flow.

Table 5.2 shows a summary of the influent and septage flows, and the flows in the North and South trunks during the sampling. The data indicates that an average of almost 30,000 gallons of septage was dumped for the three sampling dates. This contributed an average of 1.5 percent of the incoming flow for the 8-hour period on those days.

Table 5.2 Summary of September 2024 Sampling Event - Flows Sampling
Date(1)
Influent Flow to WWTP
During Sampling Period
(gallons)
Total Daily
Septage Flow
(gallons)
Flows (MG) Percent Contribution of
Septage to Average North Trunk South Trunk Influent Flow(1,2) 9/16/2024 2,258,333 34,099 1.35 0.91 1.5%
9/23/2024 2,295,833 20,349 1.37 0.92 0.9%
9/30/2024 2,312,500 35,443 1.38 0.93 1.5%
Average 2,288,889 29,964 1.37 0.92 1.5%
Notes:
(1) Sampling period lasted from 8:00 a.m. to 4:00 p.m.
(2) Percentage is based on eight hours of influent flow.

Table 5.3 summarizes the concentration of BOD, NH3, and TKN upstream and downstream of the septage station. The influent BOD sample was collected as a single combined sample. As indicated, the BOD concentration was significantly higher at the headworks compared with the combined sample collected upstream of the septage station. The average BOD concentration increase was almost 38 percent. The North trunk consistently showed higher concentrations of NH3 than the South trunk. TKN concentrations showed similar trends for the North and South trunks. Accounting for the average flow split between the North and South trunks during the sampling period yields an average upstream NH3 concentration of

71.6 milligrams per liter (mg/L), compared to 76 mg/L after septage addition, a 6 percent increase.

Similarly, for TKN, the combined stream had an average concentration of 99.4 mg/L compared to 111 mg/L after septage, an increase of almost 12 percent.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-4
Note that the percent changes indicated above were only for the 8-hour period during which septage was received at the WWTP. The actual percent contribution by septage over the entire day would be lower, but the higher values represent the concentration of the slug of influent flow that the treatment process would experience during weekdays when septage is accepted at the plant.

Table 5.3 Summary of Results From First Sampling Event - September 2024 - BOD5, TKN, and NH3 (1)
Sampling
Date
BOD5 (mg/L)(1) TKN (mg/L)(1) NH3-N (mg/L)(1)
Upstream of
Headworks
(Pre-Septage)
Headworks
(Post-Septage)
Upstream of
Headworks
(North
Trunk)
Upstream
of Septage
(South
Trunk)
Headworks
(Post-Septage)
Upstream of
Headworks
(North
Trunk)
Upstream
of Septage
(South
Trunk)
Headworks
(Post-Septage)
9/16/2024 340 388 110 84 93 97 66 65
9/23/2024 376 533 94 93 120 69 56 77
9/30/2024 424 650 110 95 120 74 56 86
Average 380 524 105 91 111 80 59 76
Notes:

NH3-N - nitrogen component of ammonia
(1) Samples were collected from 8:00 a.m. to 4:00 p.m. to coincide with septage dumping.

In addition to the three major constituents listed above (BOD, TKN, and NH3), the sample collected at the headworks was also analyzed for several metals, priority pollutants, and per- and polyfluoroalkyl substances (PFAS) compounds. Because there was no “before septage” sample to compare with, the measured concentrations cannot be attributed to septage only. Therefore, these results are not presented here, but have been included in Appendices A and B for information.

Using the flow information and the concentration data, the load of BOD, NH3, and TKN from the septage was calculated and compared to the incoming wastewater load. The loading was flow-adjusted to a 24-hour basis by utilizing the observed average daily flow from the sampling event. The results in Table 5.5 show that when adjusted for a 24-hour composite, the septage contributed about 6.9 percent of the NH3 load, 11.9 percent of the TKN load, and over 28 percent of the BOD load.

A BOD load of 2,873 pounds per day (lb/day) is equivalent to a concentration of 55 mg/L based on the average influent flow of 6.26 mgd for the three sample days, including septage flow.

Table 5.4 Contribution of Septage to Influent BOD, NH3, and TKN Load - September 2024 (Adjusted for 24-Hour Period)
Description NH3
(lb/day)(1)
TKN
(lb/day)(1)
BOD
(lb/day)(1)
Average Load Upstream of Septage(2) 1,369 1,891 7,254
Average Load at Headworks 1,470 2,147 10,127
Average Contribution of Septage(3) 101 256 2,873
Notes:
(1) Load measured over an 8-hour sampling period when septage received, equivalent to daily load for septage flows. (2) Upstream loads based on concentrations in influent wastewater collected over 8 hours and adjusted to a 24-hour value based on average monthly reported concentrations.
(3) Based on measured concentrations and flow for an eight-hour sampling period.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-5

5.2.2 Second Sampling Event - Major Haulers - March/April 2025 Due to the findings from the September 2024 sampling event that the septage appeared to be contributing significantly to the incoming plant load, a second sampling event was carried out in March and April 2025. This event focused on the major septage haulers. Information gathered by the City showed that of the 54 septage haulers, eight each contributed more than 380,000 gallons per year to the plant. Figure 5.3 shows graphically the volumetric contribution of each septage hauler for the period of November 2023 through November 2024. The goal of the second sampling event was to collect four separate samples from the eight identified haulers to determine whether one or more are significant contributors to the incoming plant loads.

Table 5.5 lists each of the eight haulers and the volume they contributed to the plant during the November 2023 to November 2024 period. The total contributed by the eight major haulers was a little over 6.5 MG, or about 57 percent of the total volume dumped. There were two additional haulers that fell into the “major hauler” category [Frank's Underground Utilities (415,500 gallons) and North County Septic (409,200)], which were not included in the sampling exercise. Frank's Underground Utilities is no longer in business.

Table 5.5 List of the Eight Septage Haulers and Their Annual Flow Contribution Septage Hauler
Volume Dumped
(November 2023-November 2024)
(gallons)
Average Volume per Day
(gpd)(1)
Al's Septic Service 1,391,400 5,352
Harvey's Honey Huts 572,500 2,202
I&G 681,300 2,620
Marborg Industries, Inc. 1,379,489 5,306
Pacific Petroleum Company 449,693 1,730
Portable Johns 387,500 1,490
United Site Services 1,051,200 4,043
Valley Septic Service 599,109 2,304
Total 6,512,242 25,047
Percentage of Total Septage Volume(2) 57.1%
Notes:
gpd - gallons per day; I&G - Ingram and Greene
(1) Septage dumping takes place 5 days per week; 260 days per year. (2) Based on total volume dumped of 11.4 MG (November 2023 to November 2024).

More than 20 parameters were analyzed for in the samples collected from the major septage hauler loads.

The list of parameters is included in Appendix D.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-6
Figure 5.3 Septage Contributions From Major Haulers - November 2023 to November 2024 VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-7
Table 5.6 shows the results for the major wastewater constituents. Each septage hauler was sampled between two and four times over the sampling period. Appendix E provides a summary of all laboratory data for all parameters over the sampling period from each hauler.

Table 5.6 Average Concentrations for Constituents Sampled for Each Major Hauler Septage Hauler COD
(mg/L)
BOD5
(mg/L)
TSS
(mg/L)
VSS
(mg/L)
TKN
(mg/L)
NH3
(mg/L)
I&G 8,750 1485 6,200 4,650 425 129.5
Al's Septic Service 16,850 1,463 16,725 12,128 588 138
Harvey's Honey Huts 9,800 3,775 3,220 2,820 778 898
Marborg Industries, Inc. 27,675 5,543 19,228 12,033 1032.5 1100 Portable Johns 11,175 4,100 4,450 3,900 723 1,120
Pacific Petroleum Company 5,767 1,970 1,343 1,128 617 708 Valley Septic Service 10,925 1,485 9,275 7,025 428 145
United Site Services 8,325 2,725 3,900 3,175 618 793
Notes:

COD - chemical oxygen demand; VSS - volatile suspended solids Note that the concentrations of each constituent from the major haulers are large. This produces a slug load effect on the plant as the concentrated flows enter the facility. As shown, the largest concentrations of all constituents tested were in septage from Marborg Industries, with the exception of VSS, which was slightly lower than the concentration from Harvey’s Honey Huts. The TSS, BOD, and TKN loading in lb/day from each major hauler is shown in Figure 5.4.

Figure 5.4 Septage Loading From Major Haulers
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-8

5.2.3 Third Sampling Event - June 2025
A third sampling event was conducted in June 2025. It included sampling upstream and downstream of the septage receiving station, similar to the first sampling event, except that there was one combined composite sample upstream and one downstream, and sampling was conducted over a full 24-hour period on each day for seven selected days in the month. The goal was to capture data for periods when septage dumping was taking place and also for when septage dumping was not taking place, i.e., over the weekend. It was not possible to sample for seven consecutive days, but all seven days of a week were captured over a four-week period.

In this sampling event, TSS, total dissolved solids (TDS), NH3-N, and total nitrogen were sampled.

Table 5.7 lists the average concentrations and load contributions for each constituent upstream and downstream of the septage receiving station, for the days on which septage was accepted at the plant, excluding the weekends. Appendix F presents the summarized concentrations observed during this sampling event.

Table 5.7 June 2025 Sampling Event Results
Description TSS TDS NH3-N Total
Nitrogen TKN(1)
Average Concentration Upstream of Septage (mg/L) 320 1084 48 67 66 Average Load Upstream of Septage (lb/day)(2) 16,900 57,100 2,600 3,600 3,500 Average Concentration Downstream of Septage (mg/L) 453 1,111 55 75 76 Average Load Downstream of Septage (lb/day) 24,100 59,100 2,900 4,100 4,050 Average Contribution of Septage (lb/day) 7,230 1,990 340 410 560 Average Septage Contribution (%)(2) 30% 3% 12% 10% 14%
Notes:
(1) TKN was only sampled on three out of seven days during this event. (2) Average septage contribution to the plant when excluding the days on which no septage was received.

Table 5.7 indicates that septage does contribute a significant load to the plant: 30 percent for TSS and between 10 and 14 percent for the nitrogen parameters. As the plant receives septage, the influent stream experiences an increase in both organic and nitrogen loading. The large contributions from the septage stream may affect the ability of downstream processes to treat wastewater.

There are some confounding variables. On the days that the City did not accept septage (Saturday and Sunday), the data showed that TSS loading increased by 2,430 lb/day downstream of the septage receiving station, representing 13 percent of the average loading observed during that time period. This suggests that influent TSS may still increase, regardless of additional contributions from septage.

The increase over the weekends may be partially explained by the piping orientation feeding the headworks, shown in Figure 5.5. The parallel 48-inch sewers (see Volume 5, Chapter 1) that connect to Box B are relatively flat. Therefore, solids can settle in these pipes during low-flow periods and may be resuspended during high-flow periods, regardless of additional contributions from septage.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-9
Figure 5.5 Influent Area Piping Elevations

5.2.4 Fourth Sampling Event - July to August 2025
A fourth and final sampling event was conducted from July to August 2025. Sampling was conducted upstream and downstream of the septage receiving station. This sampling event was carried out in order to specifically track BOD data and develop a more comprehensive understanding of septage loads. As in the previous sampling events, a composite sample was collected over 24 hours and once for every day of the week. In this sampling event, TSS, TDS, BOD5, NH3-N, and total nitrogen were collected. The daily flow of septage over the corresponding week was also provided during this sampling period.

The average concentrations and calculated loads for the five parameters from the fourth sampling event are shown in Table 5.8. In this case, the TSS again showed the highest contribution at 30 percent.

Ammonia and total nitrogen contributions from septage were in a similar range to the third sampling event (14 to 16 percent), and the contribution of BOD was measured at 17 percent.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-10
Table 5.8 July/August 2025 Sampling Event Results
Description TSS TDS BOD5 NH3-N Total
Nitrogen
Average Concentration Upstream of Septage (mg/L) 310 920 393 49 69 Average Load Upstream of Septage(1) (lb/day) 16,662 49,196 21,030 2,623 3,684 Average Concentration Downstream of Septage (mg/L) 442 922 457 55 76 Average Load Downstream of Septage (lb/day) 23,796 49,530 25,200 3,122 4,283 Average Contribution of Septage (lb/day) 7,134 334 4,170 499 599 Average Septage Contribution (%) 30% 0.7% 17% 16% 14%
Notes:
% - percent
(1) The days in which no septage was received are not included in the loading average.

5.2.5 Comparison of Sampling Events
This section compares the results from each septage event to establish if there are any correlations between septage constituents. The third and fourth sampling events provide a strong point of comparison because the sampling methodology was the same in both. The results from either event provide a reasonable estimate of the loading the plant receives from septage and provides a comparison of the accuracy of sampling. Figures 5.6 and 5.7 illustrate the comparison of the loading from both sampling periods. BOD was not analyzed during the third sampling event and is therefore not included in the comparison in the figures. However, in the first sampling event, the BOD load was measured at 2,873 lb/day, which is about 69 percent of the load measured in the fourth sampling event (4,170 lb/day).

Figure 5.6 Septage Loading Comparison Between Sampling Events 3 and 4 - TSS and TDS VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-11
Figure 5.7 Septage Loading Comparison Between Sampling Events 3 and 4 - NH3 and Total Nitrogen The results indicate that septage continues to contribute a significant amount of loading to the plant. As expected, the loading of the major constituents varies from day to day depending on the mix of septage haulers that visit the site. The results have shown that TSS loading can reach up to 7,000 lb/day of additional loading, and between 350 and 500 lb/day of ammonia, and between about 400 and 600 lb/day of total nitrogen. This information is reported in tabular form in Appendix G.

Table 5.9 summarizes the loading of major constituents for the four sampling events, where available, and then provides a range of loading that can be used for planning purposes.

Table 5.9 Summary of Septage Loading Contributions and Planning Range Average Contribution From Septage for
Each Sampling Event
BOD5
(lb/day)
TSS
(lb/day)
NH3-N
(lb/day)
TKN
(lb/day)
Event #1 2,873 Not Measured 101 256
Event #2(1) 612 2,176 128 142
Event #3 Not Measured 7,231 344 564
Event #4 4,179 7,134 499 Not Measured
Anticipated Loading Range (lb/day) 2,800 - 4,200 3,500 - 7,300 100 - 500 250 - 560 Notes:
(1) Eight major haulers only, data just for comparison.

Clearly, the results of the sampling events confirm that the septage received at the City's WWTP is contributing significantly to the loads that the plant is required to treat. Also, because septage is only accepted five days per week, it induces an additional diurnal load to the plant during the weekdays, meaning that the plant experiences more variation in BOD5 and nitrogen load than would be experienced by other WWTPs that either do not accept septage or ones that receive a more typical volume of septage.

Accordingly, managing septage and its associated load will be important in order to manage effluent quality and preserve the biological processes downstream of the headworks.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-12

5.2.6 Impact of Current Septage Loads on Effluent Quality Currently, the Secondary Trickling Filter process is not able to meet the Interim Discharge limit of 60 mg/L for BOD5 set by the new General Permit (see Volume 2, Chapter 4) for more information. The City has been evaluating approaches to reduce the effluent BOD5 concentration to meet the interim limit that include tertiary filtration and chemical addition (see Volume 13, Chapter 1 for more information).

The sampling events have provided valuable information about the contribution of septage to the incoming organic and nutrient load at the plant. Another way to reduce the effluent BOD5 concentration is to lower the incoming BOD5 load. From the values shown in Table 5.9, septage is estimated to add between 2,800 and 4,200 lb/day of BOD to the treatment plant load. At an average daily plant flow rate of

6.5 mgd, this is equivalent to increasing the influent wastewater BOD5 concentration by between 52 and 77 mg/L. Therefore, significantly reducing or potentially eliminating septage dumping at the City's WWTP would be expected to lower the effluent BOD5 concentration under the current treatment plant configuration.

5.3 Proposed Modifications to the Septage Receiving Area Based on the sampling results reported above, septage contributes a significant loading to the treatment plant. If the City continues to accept septage at the plant, then improvement should be considered to help with operations and reduce the impacts of the high-strength slugs entering the treatment process.

Improvements could include customer access to septage receiving, equalization basins for metering and pre-treatment prior to returning to the treatment process, and even standalone treatment. Some proposed improvements to the septage process are discussed in the following sections.

5.3.1 Debris Removal
The septage haulers coming to the WWTP are divided into two groups: those with high solids loads containing a lot of rags, and those with more conventional septic waste. The high-load group discharges in the northern area, near the grease receiving area, and the second group discharges under the canopy area (shown earlier in Figures 5.1 and 5.2).

In the northern area, the discharge point is equipped with a bar screen, but the spacing is fairly large, and some debris, rags, rocks, and other solids get through to the influent sewers. Accordingly, dischargers need to manually rake and remove larger debris from the area as they are dumping.

In the canopy area, the grade of the influent pipes that receive this septage is fairly flat, and therefore sand and rocks entering at the septage station (both locations) settle out in the large 48-inch lines downstream. These solids continue to build up in the influent pipes until they are flushed out during high-flow events, which is an operational issue for plant staff and may explain some of the TSS values measured at the headworks, even when septage was not being dumped.

Moving forward, the City would like to see a more robust system for the removal of rocks and rags. One example arrangement is where the septage hauler connects to a camlock fitting and discharges into a line (see the top image in Figure 5.8) that feeds a downstream box, where rocks and some grit become trapped. These are removed manually after each septage load by opening the wing nuts on the box's front plate. This approach would be very labor-intensive and probably not suitable for Santa Maria, given the high number of septage discharges each day.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-13
Figure 5.8 Examples of Septage Station Improvement Features Utilizing Manually Cleaned Screens VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-14
Another approach (lower image in Figure 5.8) shows a different arrangement in which the septage hauler discharges to an open steel container that has a V-shaped bar screen built into the base. The screen captures rocks and rags, which are then manually raked out by the septage hauler into an adjacent dumpster. Screened flow from the base of the tank can then be directed into the headworks or a holding tank. Both examples above are simple systems with minimal automated or moving parts. However, both require manual removal of the trapped screenings and rocks, which may be cumbersome given the large number of septage loads that the City receives.

A third alternative is a more automated approach, for example, using a Huber RotaShield unit, as shown in Figure 5.9. The RotaShield is a septage acceptance unit designed to screen and separate coarse material such as rags, plastics, stones, and other debris from septic or sludge deliveries before further treatment.

Incoming septage is fed into a rotating perforated drum, where large solids are retained while fine material passes through. As the drum rotates, solids are slowly moved out of the rotating drum and discharged into a washer compactor, where it is washed, dewatered, and discharged to a bin for disposal.

The unit features forced material guidance and spray water to prevent blockages in the drum perforations, enclosed operation with the ability to connect to an odor control system, and high solids-handling capacity. Each unit can be configured with two 4-inch male camlock inlet connections for simultaneous offloading of two trucks into the same RotaShield unit. Huber also offers a hauler access station that uses a card reader to record the date, time, and hauler information, as well as providing secure access and operation for approved haulers. Figure 5.9 shows a typical installation of two units.

The City would like to see the existing two septage dumping areas consolidated into one area. This consolidation can be achieved with the RotaShield Units by installing them underneath the existing canopy. Special consideration will be required for recreational vehicles (RVs) and other select users that are not equipped to discharge through the Huber RotaShield units. Typical RVs utilize a gravity drain connection with minimal available discharge head, making it impractical to route flow directly into the elevated Huber RotaShield inlet without a separate below-grade receiving tank and pump system. Such a system would add complexity and require periodic O&M activities by the City.

Because RV wastewater is not expected to contain the same quantity of rags, rocks, and other irregular debris often found in commercial septic loads, the City may instead provide a separate grade-level gravity connection for RVs and other select haulers, similar to those commonly found at RV parks. This connection could discharge directly to the influent sewer and headworks, while the remaining haulers will be required to discharge into the Huber RotaShield system. The final configuration, including whether RVs and other select haulers are provided with a separate discharge connection should be evaluated during preliminary design.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-15
Figure 5.9 Huber RotaShield Septage Acceptance Units
Huber RotaShield Field Test
Based on the proposed capabilities of the RotaShield system, the City decided to conduct a one-week field trial. A unit was brought to the treatment plant and installed on November 3, 2025, and operated for three days. Figure 5.10 shows some photographs taken during the operating period. The top left image shows the unit in position, treating the septage from a hauler. The unit was able to unload a 4,500-gallon truck in 6 or 7 minutes and was efficient at removing rags and larger rock material. Haulers were able to pressurize their tanks to lift the septage up to the screen inlet point.

A significant amount of small rock and grit is introduced with septage, as depicted in Figure 5.10 (top right-hand photograph). Because these solids pass through the unit's screen, an additional grit-removal process, such as a dedicated grit trap or chamber, would be necessary. The material discharged from the unit was thoroughly washed and dewatered, making it substantially less objectionable and more visually appealing compared to the material in the current septage scrapings dumpsters. An additional operational benefit observed by the plant operators was a significant improvement in the headworks bar screen run times after implementing septage pretreatment with the RotaShield unit.

The City found the unit's maintenance requirements reasonable, provided operators perform daily rounds and bi-weekly pressure washing to ensure optimal screen permeability. Periodic checks and replacement of wear parts are also necessary with a frequency dependent on grit accumulation.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-16
Figure 5.10 Huber RotaShield Field Trial - November 2025 Based on the successful field trial, the City would like to include Huber RotaShield units as part of the improvements to be made for the septage receiving system.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-17
Huber RotaShield Criteria
The proposed equipment for the screening of septage is the Huber Sludge RotaShield and Wash and Press (WAP). This unit is a screening drum that separates coarse solids (less than 10 millimeters) and liquid streams. The solids are washed, compacted, and discharged into a bin. Septage trucks may be connected to either unit using a 4-inch connection. In addition, these units may be configured with connections on both sides such that one unit can accommodate two haulers simultaneously.

As noted above, the characteristics of the septage indicate a significant amount of debris, rocks and rags.

This level of debris could impact the lifetime of the units and lead to more extensive wear and maintenance than anticipated. As a result, it is recommended that three units be installed (two duty, one standby) to allow for one unit to be out-of-service for maintenance. These units would be installed under the existing canopy to provide some protection from the elements (the existing canopy is shown in Figure 5.1).

The preliminary sizing criteria for the units are shown in Table 5.10.

Table 5.10 Preliminary Sizing for Huber RotaShield Units Item Units Value
RotaShield
Septage Acceptance Capacity gpd 44,000
Units duty x standby x maintenance 2 + 1
Maximum Flow Rate gpm 400
Sizing feet, length x width x height 12 x 8 x 8
Weight pounds 2,976
Wash Water Consumption (RotaShield) gpm 23
Washer Compactor (WAP)
Maximum Screening Capacity cubic feet/hour 140
Wash Water Consumption gpm 16
Weight pounds 750
Notes:
gpm - gallons per minute
Site Modifications
The City would prefer the two septage dumping areas described above consolidated into one area. The high-load dischargers and the more conventional septic waste dischargers would both be able to connect to the RotaShield units.

In addition, the RotaShield units will reduce the amount of solids that accumulate in the 48-inch influent pipes by removing solids from septage before it enters the incoming sewer to the headworks. Figure 5.11 indicates the existing pipe orientation at the septage receiving station under the canopy. In the new configuration, the RotaShield units will still connect to the existing underground pipes and to the diversion manhole.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-18
Additional grit screens may be added at the inlets and in the pipe connections as needed. A slight expansion of the existing slab will be necessary to accommodate the third unit and to permit haulers to attach on both sides of the overhang.

Figure 5.11 Existing Pipe Orientation at the Septage Receiving Station With the Canopy

5.3.2 Septage Equalization Basin for Influent Metering
As discussed previously, the BOD, TSS, and NH3 loadings from the septage station are significant and can result in adverse impacts to the proposed activated sludge secondary treatment facilities. To address this concern, the City is also considering a holding tank to accept screened septage. The idea would be to meter the flow from the tank into the plant over a period of hours to even out the septage load and avoid high load variations. The need for a tank will be assessed further during preliminary design based on the expected loads from septage haulers.

This option would include a storage facility sized for no more than 2 days of septage, roughly 0.12 MG.

This will be achieved with two 25-square-foot basins with 14 feet of depth each. Each basin will be about 60,000 gallons and will accommodate one full day of septage flow for metering into the WWTP. The basin will be located near the existing septage overhang and connect to the existing 60-inch diversion manhole.

The septage flow may be able to gravitate to Box B. The ground elevation at the septage station is 173.5 feet, and the current water elevation at Box B is 170.63 feet at peak wet weather flow. However, it will be equipped with recessed impeller standby pumps with variable speed controllers in case of overflow.

5.3.3 Return Activated Sludge Treatment of Septage
Due to the high-strength nature of septage and the daily volume received at the treatment plant, it may be beneficial to treat it in a separate biological process, similar to the approach used for treating dewatering liquor. And, because the Phase 1 treatment system will include new mechanical dewatering equipment, there may be an opportunity to combine treatment of dewatering liquor with septage.

In order to develop a preliminary cost estimate for a standalone septage treatment system, a recent dewatering liquor side-stream treatment project in Moreno Valley, California was used as a basis for sizing and costing. The project included the construction of equalization basins and return activated sludge (RAS) treatment of dewatering liquor containing high concentrations of NH3, orthophosphate, and COD.

The Moreno Valley facility treats up to 192,600 gpd of flow with a total NH3 load of about 1,700 lb/day.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-19
The size of the facility was adjusted based on projected septage flows and loads appropriate for Santa Maria. It was assumed that future septage flows will average around 44,000 gpd with a future buildout at 60,000 gpd. NH3 and BOD5 loads were assumed to be in the range of 100 to 500 lb/day and 2,800 to 4,200 lb/day, respectively (Table 5.9).

In addition, the equalization basin would be sized to hold a total of 0.18 MG of flow, configured in three separate basins of 0.06 MG each. The basins would be operated in a duty standby mode, with one basin offline for cleaning/maintenance. The equalization basins would be directly connected to aeration basins sized to treat the daily septage load. The sizing of the aeration basins would be suited to accommodate projected septage loads as well as any potential centrate or dewatering flows. The unique feature of this aeration basin system is that, in addition to the septage flow, it would receive a portion of the RAS from the Phase 1 activated sludge secondary clarifiers. Aeration air would be provided to assist with the breakdown of BOD and nitrification of ammonia. The high-nitrate, low BOD stream from the septage aeration basins would be blended with the remaining RAS flow and be recycled to the Phase 1 anoxic zones as normal. The lower ammonia load and higher nitrate load from the septage treatment system would provide additional nitrate for denitrification and reduce the overall ammonia load on the Phase 1 activated sludge system.

It is anticipated that the new septage treatment system will be located at the southern edge of the site property, near the future Phase 1 secondary clarifiers and aeration basins. Coupling the equalization and aeration basins will reduce the slug-loading effects of septage and improve the overall effluent quality of the treatment system.

5.3.4 Conceptual Layouts
There are two possible layouts depending on the level of septage treatment that is provided.

Figure 5.12 illustrates the conceptual layout for potential smaller-scale improvements for the septage receiving area and the construction of an equalization tank for holding and metering flow back to the headworks. The RotaShield units would be installed beneath the existing overhang. As mentioned, the three units will be installed such that pumper trucks may connect to each unit on either side of the unit.

For dumpers that do not have the ability to pressurize their septage tanks for discharge, such as recreational vehicles and the like, an alternative arrangement will be needed. Initial thoughts include providing a relatively small self-cleaning sump into which “non-pumping” haulers would dump.

A self-priming pump would transfer the contents of the sump to the RotaShield unit for processing. At the end of each day, the sump will be flushed to clean out any remaining debris. This concept or alternatives will need to be developed further during the preliminary design phase.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-20
Figure 5.12 Proposed Septage Improvements for Equalization and Return to Headworks Figure 5.13 illustrates the conceptual layout and possible locations for the full septage treatment option, which includes septage upgrades, a septage pump station, and the equalization and aeration basins.

Three different locations for the treatment tanks (equalization and aeration basins) are shown. The southernmost location may not be preferred because it is close to the property line, and odor from the septage may become a future concern. Also, if the dewatering liquor is combined with the septage for treatment, then this location is relatively far from the dewatering building. The location to the northeast of the tertiary filters will be open after demolition of the existing facilities, and may be a good location.

However, this area would only be available after demolition of the existing facilities, which may be a disadvantage. It is also relatively far from the dewatering building if dewatering liquor is to be combined with septage for treatment. The third location is to the north of the new secondary clarifiers, adjacent to the proposed cake storage area. This location is far from the property line, so odor is not expected to be a concern and is close to the dewatering building if septage and dewatering liquor treatment is to be combined. Its disadvantage is that it would be furthest from the septage receiving area and, therefore, require the longest pipe run. The most suitable location for the septage treatment facility can be evaluated further during the preliminary design. The RotaShield units would be located underneath the existing overhang near the plant entrance, as before.

Note that for each layout and alternative, the septage overhang and slab will need to be expanded slightly in order to accommodate trucks and haulers.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-21
Figure 5.13 Proposed Septage Improvements for Full Treatment Showing Three Alternative Locations VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-22
Septage Transfer Pump Station
In each case, a septage transfer pump station would be required to transfer flow from the septage receiving station to the equalization tanks, and then either metering it to the headworks or transferring it to the aeration basins, in the case of the full treatment approach. The station will connect to the existing 60-inch fiberglass-reinforced plastic diversion manhole installed as part of the 2019 improvements to the Septage Receiving Station. Pumps would be housed in a sump. The pumps will be able to convey flow to the other side of the site or to meter back into the existing influent lines.

The preliminary design criteria for the septage transfer pump station are shown in Table 5.11.

Table 5.11 Preliminary Design Criteria - Booster Pump Station Item Units Value
Sump Diameter feet, length x width x height 6 x 9 x 6
Operating Depth feet 5
Sump Liner - PVC
Pump Type - Recessed Impeller
Number of Pumps Duty + Standby 1 + 1
Rated Capacity gpm 350
Head feet 35
Motor Size hp 10
Speed Control - Variable Speed

5.3.5 Planning Level Cost Estimates
Three separate cost estimates were developed for potential upgrades of the septage system:

1. Septage station modifications only - which would only include the addition of Huber screening units and consolidation of the two existing septage areas.

2. Septage station modifications and equalization basins for metering - which would include the addition of Huber screening units, consolidation of the two existing septage areas, and the provision of holding tanks for daily metering of septage flow to the headworks.

3. Full septage treatment and septage station modifications - which would include the addition of Huber screening units, consolidation of the two existing septage areas, provision of a new transfer pump station, and RAS aeration basin treatment of the septage.

Level 1 Modifications
Table 5.12 lists the preliminary planning level construction cost estimate for adding Huber RotaShield units and consolidation of the two septage receiving areas. There would be no major piping or equalization in this alternative.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-23
Table 5.12 Septage Station Improvements Cost Estimate - Level 1 - Improved Screening Only Item Description Amount
1 Septage Station Modifications
 Site and Piping Modifications. $324,000
 Construct Three (3x) Huber RotaShield Units. $1,950,000 Subtotal - Direct Costs $2,274,000
2 Contingency (30%) $684,000
3 Contractor Markups (General Conditions, Overhead and Profit) (28%) $871,000 4 Sales Tax (Based on 50% of the Direct Costs at 8.75%) $131,000 Estimated Construction Cost $3,960,000
Level 2 Modifications
Table 5.13 lists the preliminary planning-level construction cost estimate for improving the septage station with Huber units, along with the construction of an equalization basin that holds up to two days of septage flow, separated into two compartments, to be metered slowly into the plant each day.

Table 5.13 Equalization Basin and Metering Cost Estimate - Level 2 - Small Equalization and Return to Headworks Item Description Amount
1 Septage Station Modifications
 Site and Piping Modifications $324,000
 Construct Three (3x) Huber RotaShield Units $1,950,000 2 Metering Pump Station and Small Equalization Basins (2 x 60,000 gal) $$474,000 Subtotal - Direct Costs $2,751,000
3 Contingency (30%) $829,000
4 Contractor Markups (General Conditions, Overhead and Profit) (28%) $1,052,000 5 Sales Tax (Based on 50% of the Direct Costs at 8.75%) $$158,000 Estimated Construction Cost $4,790,000
Level 3 Modifications
For the full treatment alternative, the costs were primarily based on the cost estimates developed for a side-stream dewatering liquor treatment system recently constructed in Moreno Valley, California. The direct costs listed for that project were escalated for inflation and subsequently factored down for sizing.

Typical civil and electrical direct cost factors were added.

It is anticipated that the Santa Maria system would be roughly a third of the size of the Moreno Valley installation, but due to the embedded costs of construction, a 55 percent direct cost factor was utilized. In addition, the direct costs for the transfer pump station were estimated as half the direct cost of the larger-scale pump station for the full septage treatment as a result of the reduced flows required.

Table 5.14 lists the preliminary planning-level construction cost estimate for full septage treatment, including construction of aeration and equalization basins for septage treatment only (excluding the addition of dewatering liquor), and the expansion/modification of the existing septage receiving area to include the removal of rags and debris.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-24
Table 5.14 Septage Treatment Cost Estimate - Level 3 - Full Treatment Item Description Amount
1 Septage Station Modifications
 Site and Piping Modifications $324,000
 Construct Three (3x) Huber RotaShield Units $1,950,000 2 Septage Transfer Pump Station and Piping $827,600
3 Septage Equalization and Aeration Basins $5,190,000
Subtotal - Direct Costs $8,295,000
4 Contingency (30%) $2,490,000
5 Contractor Markups (General Conditions, Overhead and Profit) (28%) $3,170,000 6 Sales Tax (Based on 50% of the Direct Costs at 8.75%) $475,000 Estimated Construction Cost $14,430,000
If the City decides to continue to accept septage moving forward, then partial or full septage treatment can be implemented as part of the final project completed under Phase 1.

Operating Cost Estimate
In addition to the planning level capital cost estimates, projected annual operations and maintenance (O&M) costs were developed for the Level 3 - full treatment scenario, which includes all the upgrades outlined above. O&M would include power, labor, and an allowance for equipment replacement. The following assumptions were used to develop the annual O&M cost estimate:
 $0.25 per kilowatt-hour (kWh) power cost.
 550 annual labor hours, $80 per hour.
» Labor hours were included for the additional O&M hours dedicated to the RotaShield units. It was assumed that labor costs for the septage treatment aeration basins would be included in the operating costs of the Phase 1 activated sludge system.  Annual equipment replacement costs are 2 percent of the direct capital cost.

The electrical power cost was based on estimates for the power required to operate one RotaShield unit for eight hours per day and one unit for four hours per day, five days per week, plus pumping energy to transfer septage to the equalization and tanks and then to the aeration basins, and blower power to provide aeration air. The total power demand was estimated to be a continuous draw of 20 kWh.

Estimates of the annual O&M costs for the full septage treatment approach (Level 3) are summarized in Table 5.15.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-25
Table 5.15 Preliminary O&M Costs for Septage Treatment - Based on Level 3 Item Annual Cost
Power(1) $45,200
Labor(2) $44,000
Replacement/ Maintenance(3) $64,000
Total $152,200
Notes:
(1) Power estimates for operating Huber RotaShield units, pumping, and aeration basins totaling 20 kWh per hour. (2) Labor hours include the additional labor required for the Huber RotaShield units. Total labor costs for the operation of the full Level 3 facility will be encompassed in Phase 1 expansion operating budgets. (3) Replacement and maintenance costs based on 2 percent of the capital costs of the operating equipment.

Unit Cost Estimate for Septage Treatment
The estimated capital cost for the full treatment approach (Level 3) and the annual O&M cost from Table 5.15 were used to estimate the unit cost of septage treatment. The capital cost estimate from Table 5.14 was amortized over 20 years using an interest rate of 6 percent to obtain the annual payment amount. This value, together with the annual O&M cost, provides an estimate of the annual cost of treatment. The unit cost for treatment was based on a total volume of 11.4 MG of septage, the amount received during the 12-month period of November 2023 to November 2024. This resulted in a unit cost of $0.12 per gallon, as shown in Table 5.16. It should be noted that this cost excludes any further costs associated with septage treatment and handling, such as the cost for final treatment in the activated sludge process for nitrogen removal and a portion of the solids treatment and disposal cost. These costs still need to be developed.

Currently, the City is charging a septage tipping fee of $0.134 per gallon, which is close to the preliminary estimate developed above, and suggests that the City would have to increase the tipping fee to be able to recover sufficient funds from septage receiving to offset the cost of full septage treatment, as long as the annual volume of septage remains about the same as it is currently. In addition, it should be noted that a flat rate of $0.02 per gallon of the septage tipping fee is paid directly to the General Fund, reducing the amount that goes to the Wastewater Fund to cover the cost of treatment. A more detailed analysis of the costs for complete septage treatment will be needed before arriving at a realistic septage tipping fee to cover future treatment costs.

Table 5.16 Preliminary Unit Cost for Septage Treatment - Based on Full Treatment - Level 3 Item Annual Cost
Annual Cost of Capital(1) $1,258,073
Annual O&M Cost(2) $152,200
Total Annual Cost for Septage Treatment $1,410,273
Total Volume of Septage Received per year, MG(3) 11.4
Cost per Gallon to Treat Septage, $/gallon 0.12
Notes:
(1) $14.4 million capital cost estimate for full septage treatment, amortized over 20 years at a fixed interest rate of 6 percent. (2) Includes estimates for power, labor, and maintenance. (3) Based on the annual volume received for November 2023 to November 2024.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-26
No Septage Option
As noted above, the City is considering its options for septage receiving. One option is the “no septage” approach, in which the City would no longer accept septage at the WWTP. Some impacts associated with the “no septage” approach are briefly discussed below.

1. Impacts to the General Fund – The General Fund currently receives $0.02 per gallon for all septage received by the City. If septage dumping ceases, then the General Fund would lose about $228,000 per year based on the current volume of septage received at the WWTP.

2. Impacts to Phase 1 Capital Cost – If septage is no longer received at the WWTP, then there would be no need for the planned improvements in the septage receiving area or the proposed separate treatment system discussed as part of the Level 3 treatment approach. This would reduce the Phase 1 construction cost estimate by about $14.4 million for this single item. In addition, there could be reductions in other areas impacted by the septage load.

3. Impacts to Plant O&M Cost – There would be a reduction in the overall plant O&M cost if septage is no longer received at the plant. The full extent of this has not yet been quantified, but if septage contributes up to 17 percent of BOD5 load, up to 30 percent of the TSS load, and up to 14 percent of the TKN load, as indicated by the septage sampling events discussed earlier, there will be noticeable reductions in O&M costs, specifically in the primary and secondary treatment and solids handling processes.

4. Impacts to Septage Haulers – the City held discussions with some of the major haulers regarding where they might go if the City were to stop accepting septage at the plant. None of the haulers contacted are currently permitted to discharge elsewhere, and the closest alternative would be Bakersfield. Some haulers mentioned they have been unsuccessful in obtaining permission to discharge to WWTPs in the areas where the waste is generated, and if the City closed its gates to septage receiving they would have to either close their operation or raise their rates significantly to deal with longer haulage distances. Overall, the sentiment from the sample of haulers contacted was that if the City did not accept their waste, they would not have a feasible alternative without causing service interruption, significant rate increases for their customers, extreme hardship, or ending operations.

5. Impact on City’s Pretreatment Program – The City spends staff time administering the current septage receiving program associated with reviewing wastewater discharge permit applications and issuing and renewing individual liquid waste hauler discharge permits, assigning and issuing access cards for each permitted vehicle, tracking and managing each discharge event, performing the monthly commercial invoicing, and other administrative and regulatory tasks associated with the program. User Fees are collected for the regulatory administrative tasks associated with the Septage Receiving Program, so revenue would not be collected for those tasks if septage is no longer received at the WWTP. However, this would lessen the burden on the pretreatment program staff by reducing administrative time, allowing them to focus on other pretreatment activities for the City.

Overall, no longer accepting septage at the WWTP is likely to have a positive impact on the performance and stability of the current and future Phase 1 wastewater treatment processes and will reduce the operating costs. However, there would be a negative impact to the haulers themselves, as they might be forced out of business, and there would be a loss of revenue to the General Fund.

VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-27

5.4 Conclusion
This chapter provided an overview and analysis of the sources, quality, and type of septage received by the City at the WWTP. The City is the largest acceptor of septage in Santa Barbara and San Luis Obispo Counties and receives septage from both industrial and domestic haulers.

Four separate sampling events were conducted from September 2024 to August 2025. The results from the sampling events suggest multiple conclusions, including:
 Septage constitutes a small portion of total influent flow (around 1.5 percent), but this is a significantly higher percentage than for other typical treatment plants that accept septage.  Septage appears to contribute up to 17 percent of influent BOD, up to 30 percent of influent TSS, and up to 14 percent of influent TKN.
 The sampling indicates that the anticipated loading from each constituent can be up to 4,200 lb/day of BOD5, up to 7,300 lb/day of TSS, up to 500 lb/day of NH3, and up to 650 lb/day of TKN.  Eight major haulers contribute a significant portion of the septage flow and loading into the facility (about 57 percent).

If it is decided to continue accepting septage, then modifications to the existing facilities should be made.

As a part of this process, the City conducted a successful trial of a Huber RotaShield septage screening unit. After this successful trial, an evaluation of alternatives was performed based on this equipment, and cost estimates were developed for three levels of improvement:
 Level 1 would improve septage receiving through installation of the Huber RotaShield units, consolidation of the existing receiving areas, and improved removal of rags and coarse debris.  Level 2 would incorporate the Alternative 1 improvements and add equalization storage and controlled metering of septage back to the headworks, reducing the magnitude of the short-duration slug loads currently experienced by the treatment process.  Level 3 would incorporate the receiving and equalization improvements and provide a dedicated biological treatment process for the high-strength septage prior to returning the treated flow to the Phase 1 activated sludge process.

Based on the historical septage sampling results, the relatively high concentrations of BOD, suspended solids, and nitrogen in the septage stream, and the significant variability associated with individual loads, the City should plan to implement at least Alternative 2. Improved screening under Alternative 1 would provide substantial operational benefits and reduce the amount of coarse material entering the plant, but screening alone would not address the high-strength organic, solids, and nutrient loads associated with the septage. Equalization and controlled metering under Alternative 2 would provide an important minimum level of protection by reducing peak loading and allowing the downstream treatment process to receive the septage load more gradually.

For long-term septage handling and for the planning purposes of this Master Plan, Alternative 3 is recommended. Providing dedicated equalization and biological treatment would give the City greater control over the high-strength septage load, reduce its direct impact on the Phase 1 activated sludge process, and provide greater flexibility to accommodate the variability in septage quantity and quality observed during the sampling program. The proposed system could also be configured to treat other high-strength sidestreams, including centrate or liquor from the solids dewatering process, providing VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-28
additional long-term operational flexibility. Although Alternative 3 has the highest capital cost, it provides the most complete approach for continued septage acceptance and is considered the alternative that best meets the City's long-term goals for reliable septage handling, protection of the downstream treatment processes, and improved control of influent loading.

The planning-level capital cost estimates range from about $4 million to $14.4 million for the three levels of treatment.

Based on preliminary planning-level capital and O&M cost estimates for the full treatment approach (Alternative 3), the unit cost of septage treatment was estimated to be $0.12 per gallon. This cost is similar to the $0.134 per gallon tipping fee the City currently charges for septage, but excludes any further costs associated with final treatment in the Phase 1 activated sludge process for nitrogen removal, as well as a portion of the solids treatment and disposal costs. These costs still need to be developed and accounted for, but the indications are that the City would need to increase the septage tipping fee to cover the cost of treatment in the Phase 1 process, and cover the $0.02 per gallon, which goes directly to the General Fund.

Should the City decide not to accept septage in the future, this is likely to have a positive impact on the performance and stability of the current and future Phase 1 wastewater treatment processes, and will reduce the operating costs. However, based on preliminary discussions with some of the septage haulers there would be a negative impact on their businesses, as the closest alternative would be Bakerfield which might force them to shut down. An additional negative impact will be the loss of revenue to the General Fund, currently around $228,000 per year.

VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA

WASTEWATER TREATMENT PLANT MASTER PLAN

APPENDIX A TERTIARY FILTER PILOT STUDY REPORT

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Tertiary Filter Pilot Study
FINAL / October 2026

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Tertiary Filter Pilot Study
FINAL / October 2026
Digitally signed by Graham J.G. Juby
Contact Info: Carollo Engineers, Inc.

Date: 2026.10.23 07:55:26-07'00'

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN i
pw://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/WWTP Tertiary Filter Pilot/Report/Tertiary Filter Pilot Report.docx Contents
SECTION 1 INTRODUCTION 1
SECTION 2 INITIAL STUDIES 1
SECTION 3 PILOT PLANT SETUP AND EQUIPMENT 2
SECTION 4 PILOT TESTING APPROACH 3
SECTION 5 RESULTS 4

5.1 Historical Effluent Quality 4

5.2 Pilot Results 4

5.2.1 Filter Flow and Loading Rate 4

5.2.2 Solids Removal Performance 5

5.2.3 Biochemical Oxygen Demand Removal Performance 7

5.2.4 Backwash Interval and Recovery 7

5.2.5 Impact of Polymer Addition 8

5.2.6 Evaluation of Backwash Water 10
SECTION 6 FILTER SIZING AND COST ESTIMATE 12

6.1 Cost Estimate 13

6.1.1 Planning Level Capital Cost 13

6.1.2 Planning Level O&M Cost 15
SECTION 7 DISCUSSION 15

7.1 Meeting with the Regional Water Board 16

7.1.1 Reduced Solids Loading on the Percolation Ponds 16

7.1.2 A source of Water for In-Plant Use 17
SECTION 8 CONCLUSIONS 18
Attachments

ATTACHMENT A TERTIARY FILTER PILOT TEST PLAN

ATTACHMENT B SANTA MARIA TEMP TERTIARY FILTRATION COST ESTIMATE Tables
Table 1 City of Santa Maria General Order Interim Wastewater Treatment Plant (WWTP) Effluent Limits 1
Table 2 Nexom Pilot Filter Design Criteria 3
Table 3 Full-Scale Tertiary Filter Design Criteria 12
Table 4 Planning Level Cost Estimate for Tertiary Filters 14 Table 5 Planning Level Annual O&M Cost Estimate for Tertiary Filters 15

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN ii
Figures
Figure 1 Proposed Site Layout and Backwash Flow Paths for Nexom Filter 2 Figure 2 Nexom Cloth Media Tertiary Pilot Filter 3
Figure 3 Historical Secondary Effluent BOD5 Concentration 4 Figure 4 Variation in Filter Feed Flow Rate 5
Figure 5 Variation in Filter Hydraulic Loading Rate 5
Figure 6 Filtered Effluent TSS and Filter Loading Rate 6 Figure 7 Filter Feed and Effluent Turbidity Variation 6 Figure 8 Feed and Effluent Turbidity Variation 7
Figure 9 Variation in Backwash Interval 8
Figure 10 Variation in Overall Recovery 8
Figure 11 Variation of TSS Removal Before, During, and After ACH Addition 9 Figure 12 Variation of COD Removal by Cloth Filter During Addition of ACH 10 Figure 13 Impact of ACH on Percent Solids Remaining in Backwash Water 11 Figure 14 Visual Impact of High Doses of ACH to Backwash Water After 2 Minutes (Top) and 90 Minutes (Bottom) Settling 11
Figure 15 Impact of Filter Capacity on Effluent BOD5 Concentration 12 Figure 16 Simplified Process Flow Diagram and Preliminary Layout for Tertiary Filters 13 Figure 17 Example Tertiary Filter Installation With Shade Cover 14 Figure 18 Impact of TSS (Cs) on Total Infiltration (S) - from Rice 1974 17

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN iii
Abbreviations
ACH aluminum chlorohydrate
amps amperes
BOD5 biochemical oxygen demand (5-day test)
Carollo Carollo Engineers
City City of Santa Maria
COD chemical oxygen demand
ft feet
ft2 square feet
gpm gallons per minute
gpm/ft2 gallons per minute per square foot
hp horsepower
kWh kilowatt-hour
lb/ft2 pounds per square foot
mg/L milligrams per liter
O&M operations and maintenance
TN total nitrogen
TSS total suspended solids
WWTP wastewater treatment plant

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1
SECTION 1 INTRODUCTION
The City of Santa Maria (City) has been investigating ways to reduce the biochemical oxygen demand (BOD5) and total suspended solids (TSS) of the secondary trickling filter effluent to achieve the interim discharge limits established by its new 2023 General Order. These limits are shown in Table 1, and both BOD5 and TSS are required to meet a 30-day average of 60 milligrams per liter (mg/L) or less. In response to the requirements of the General Order, the City prepared a Time Schedule Compliance Plan (see Volume 2, which includes a copy of the Plan) in June 2024 and requested that the interim limits be extended until June 2033. By this time, it was anticipated that the upgraded treatment facilities would be in operation. If not extended, the new effluent limits of 30 mg/L for both BOD5 and TSS would come into effect after June 16, 2025.

Table 1 City of Santa Maria General Order Interim Wastewater Treatment Plant (WWTP) Effluent Limits Constituent Units Interim Limit per General Order Proposed Interim Dates per Time Schedule Compliance Plan
BOD₅ mg/L 100 (daily maximum)
60 (30-day average)
Until June 2033
TSS mg/L 100 (daily maximum)
60 (30-day average)
Until June 2033
At the time this work was undertaken, the City was investigating methods to achieve or get close to achieving the proposed interim effluent limits, based on direction from the Regional Water Board.

SECTION 2 INITIAL STUDIES
In 2023 and 2024, Carollo Engineers (Carollo) conducted some bench-scale testing on the primary influent stream to assess the effectiveness of various coagulants to reduce the BOD5 concentration in the primary effluent. This testing showed that ferric chloride would be most effective, but the dosage and associated cost would be significant.

Following this work, in March 2024, Carollo investigated adding a coagulant to the secondary trickling filter effluent to determine whether a coagulant could increase the settleability of the solids and improve TSS and BOD5 removal efficiency. Only one coagulant provided some improvement in settleability. To confirm its efficiency, a full-scale trial would be needed, which would be costly, challenging to implement, and could have unintended consequences resulting from the recycling of excess coagulant.

Earlier sampling in December 2023 had shown that a significant portion of the BOD5 in the secondary effluent was associated with solids and that there was quite a lot of soluble BOD5 present. 24-hour composite samples showed an average effluent BOD5 value of 66 mg/L, with an average soluble BOD5 concentration of 18 mg/L, indicating about 73 percent of the BOD5 was associated with the solids fraction.

Laboratory filtration of secondary effluent samples suggested that tertiary filtration may be a suitable approach to further reduce the TSS concentration and, consequently, the BOD₅ concentration. The testing indicated that tertiary filtration of the secondary effluent might be sufficient to reduce the BOD5 to less than 60 mg/L. A detailed evaluation of the performance of the existing plant showed that the trickling

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2
filters are performing as well as can be expected, and although the secondary effluent has an average TSS concentration of 38.6 mg/L (2018 to 2023), the BOD₅ concentration has been above 60 mg/L.

These initial investigations were included in the City's Time Schedule Compliance Plan, which established a milestone (Milestone 1) for the City to meet with the Regional Water Board to discuss the results of tertiary effluent pilot testing to establish whether the BOD5 limit of 60 mg/L could be achieved. This report presents the findings of the pilot testing.

SECTION 3 PILOT PLANT SETUP AND EQUIPMENT
In July 2024, Carollo developed a Tertiary Filter Pilot Test Plan that outlined an approach to testing to assist the City in conducting the pilot. The Test Plan is included in Attachment A.

Figure 1 presents an overview of the site arrangement for the pilot testing. The City contracted with Nexom US (Nexom) to provide the tertiary filter pilot unit.

Figure 1 Proposed Site Layout and Backwash Flow Paths for Nexom Filter

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 3
Table 2 presents the performance design criteria for the cloth filter unit.

Table 2 Nexom Pilot Filter Design Criteria
Description Value Units
Influent Flow 600-800 gpm at 20 ft of head
Filter Head Loss 24 inches
Maximum Filter Area 108 ft2
Cloth Media Pore Size 10 micron
Backwash Flow 80 gpm
Backwash Cycle 5-15 minutes
Max Hydraulic Loading 3.5 - 4.5 gpm/ft2
Max Solids Loading 3 lb/ft2.d
Notes:
amps - amperes; ft - feet; ft2 - square feet; gpm - gallons per minute; gpm/ft2 - gallons per minute per square foot; lb/ft2.d- pounds per square foot per day
SECTION 4 PILOT TESTING APPROACH
Nexom delivered the pilot filter to the site and provided the mechanical and electrical hook-up required.

Once the pilot unit was operational, the City took over the day-to-day operation. The pilot filter operated from December 2024 through April 2025. Figure 2 shows a photograph of the trailer-mounted unit.

Figure 2 Nexom Cloth Media Tertiary Pilot Filter

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 4
SECTION 5 RESULTS

5.1 Historical Effluent Quality
Figure 3 shows the WWTP effluent BOD5 concentration variation from October 2023 through December 2024, indicated as individual data points sampled weekly, as well as the running average. The figure also shows the 30-day average limit (60 mg/L) and the maximum daily limit (100 mg/L), per the Interim Discharge Limits presented in Table 1. As shown, historically, the effluent BOD5 has remained in the range of 60 to 100 mg/L. A few samples have been recorded below 60 mg/L, and three individual samples have been above 100 mg/L.

Figure 3 Historical Secondary Effluent BOD5 Concentration

5.2 Pilot Results

5.2.1 Filter Flow and Loading Rate
Figure 4 presents the variation in filter flow rate for the pilot testing period. As shown, the feed flow ranged from 370 gpm to 470 gpm. This corresponded to filter hydraulic loading rates of between 3.5 and

4.5 gpm/square foot, as shown in Figure 5.

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5
Figure 4 Variation in Filter Feed Flow Rate
Figure 5 Variation in Filter Hydraulic Loading Rate

5.2.2 Solids Removal Performance
The 10-micron cloth filter achieved an average of 38 percent removal of TSS and produced a filtered effluent with an average TSS concentration of around 17 mg/L, well below the interim limit. Figure 6 presents the TSS data plotted together with the filter solids loading rate. The influent stream to the filter had average TSS concentrations of 30.9 mg/L with minimum and maximum values of 8.4 and 57.2 mg/L, respectively. As shown in Figure 6, the TSS removal efficiency did not seem to be significantly impacted by the filter loading rate. The TSS removal efficiency was 38 percent, and effluent TSS ranged between 14 and 28 mg/L for the composite samples.

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 6
Figure 6 Filtered Effluent TSS and Filter Loading Rate
Turbidity measurements of the influent and effluent were made regularly throughout the pilot period.

These are plotted in Figure 7 and show that generally the filter was able to reduce the turbidity to about half of the feed value. The trend lines indicated a general increasing trend in the filter feed effluent, and a corresponding increase in the effluent turbidity. Again, there does not appear to be a relationship between effluent turbidity and filter loading rate.

Figure 7 Filter Feed and Effluent Turbidity Variation

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 7

5.2.3 Biochemical Oxygen Demand Removal Performance
A filtered effluent BOD5 of less than 60 mg/L was generally achieved. Figure 8 shows both grab samples (on the left) and 24-hour composite samples (on the right). Grab samples were collected during the daytime and generally resulted in lower concentrations, particularly for the feed stream. Since the composite samples are more representative of what the filter effluent would be, these values were used in the analysis. The composite samples indicate that the filter feed BOD5 varied between a minimum of 51.5 and a maximum of 90 mg/L, while the filter effluent BOD5 was in the range of 31.1 to 71 mg/L, but the majority of samples showed BOD5 of less than 60 mg/L. The average filter feed BOD5 for the composite samples was 74 mg/L, and the effluent was 48 mg/L. The average BOD5 removal efficiency was around 35 percent, but there was wide variability, ranging between 4 and 63 percent.

Figure 8 Feed and Effluent Turbidity Variation

5.2.4 Backwash Interval and Recovery
The backwash frequency impacts the overall recovery of the filter. The backwash interval was typically in the 5 to 15-minute range, but it varied throughout the testing period, as shown in Figure 9. However, even when the unit was backwashing every 5 minutes, the overall recovery was still high, well above 90 percent, as shown in Figure 10.

Grab Samples Composite Samples
Average
Average

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 8
Figure 9 Variation in Backwash Interval
Figure 10 Variation in Overall Recovery

5.2.5 Impact of Polymer Addition
To assess the impact of polymer addition on TSS and BOD5 removal, aluminum chlorohydrate (ACH) was dosed at concentrations of 1, 5, and 10 mg/L to the filter feed stream. This polymer was tested during the bench-scale work that was mentioned earlier and was found to be the only one that appeared to have the ability to coagulate the trickling filter effluent solids. Figure 11 shows the variation of the percentage TSS removal before, during, and after the addition of the coagulant. The figure also illustrates the variation in

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 9
filter loading rate. Each dose of the ACH was continued for one week. As shown in the figure, the TSS removal varied between about 20 and 70 percent in the period before polymer addition, and this variation continued during the polymer addition at all three dosages tested. Overall, there was no noticeable improvement in TSS removal with the addition of ACH.

Figure 11 Variation of TSS Removal Before, During, and After ACH Addition To assess the change in BOD5 before, during, and after ACH addition, chemical oxygen demand (COD) measurements were used. The results are shown in Figure 12, and as indicated, the addition of ACH at the three dosages had no noticeable impact on COD removal either, which stayed constant at around 10 percent for the entire period.

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 10
Figure 12 Variation of COD Removal by Cloth Filter During Addition of ACH

5.2.6 Evaluation of Backwash Water
An important consideration for the pilot testing was the quality and quantity of backwash water that would be produced by the filter, and where in the WWTP such a stream would be directed if a full-scale project were implemented.

As mentioned above (Figure 10), the recovery level for the pilot filter was high, typically between 92 and 97 percent. Thus, the flow rate of backwash water would not be expected to be significant. However, if the solids in the backwash water cannot be removed from the system, they will circulate back to the trickling filters and gradually build up over time, potentially creating operational issues and leading to higher effluent TSS concentrations. To evaluate the settleability of the solids in the backwash, the City conducted some further bench tests using ACH.

The testing determined that without the addition of ACH, only about 60 to 65 percent of the solids settled, leaving a large portion that does not settle and could potentially recirculate. When ACH was dosed at up to 50 mg/L to the backwash water, there was little to no improvement in the percentage of solids that settled. However, at a dose of 100 mg/L, more than 85 percent of the solids settled. This increased to more than 95 percent, settling at a very high dose of 300 mg/L. The results are summarized in Figure 13.

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 11
Figure 13 Impact of ACH on Percent Solids Remaining in Backwash Water Figure 14 shows a photograph of the settling tests in the laboratory for the high ACH doses, indicating the improvement after 2 minutes (top) and 90 minutes (bottom) of settling. Clearly, these results indicate that ACH addition can help with settling the solids in the backwash water, although the dosages are high.

Figure 14 Visual Impact of High Doses of ACH to Backwash Water After 2 Minutes (Top) and 90 Minutes (Bottom) Settling

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 12
SECTION 6 FILTER SIZING AND COST ESTIMATE
The pilot testing has determined that removal of around 30 percent of the BOD5 in trickling filter effluent can be achieved with a nominal 10-micron tertiary cloth filter. To establish the capacity of a full-scale installation that would be needed to reduce the effluent BOD5 to less than 60 mg/L, some design criteria were established from the pilot testing. These are shown in Table 3.

Table 3 Full-Scale Tertiary Filter Design Criteria
Description Value
WWTP Effluent Flow, mgd 6 - 7
Filter Influent BOD5, mg/L 74
Filter Effluent BOD5, mg/L 48
ACH Addition to Filter Influent No
ACH Addition to Backwash Water Yes - 100 - 150 mg/L
Backwash Cycle, min 5
Max Hydraulic Loading, gpm/ft2 3.5
Max Solids Loading, lb/ft2.d 3
The pilot results show that if all the flow leaving the trickling filters is filtered, the resulting BOD5 concentration would be below 50 mg/L. However, if a partial-treatment approach were used, where most of the flow is filtered and the unfiltered portion of the flow is blended with the filtered portion, then it should still be possible to achieve the desired 60 mg/L for BOD5. Figure 15 illustrates the partial treatment approach for a scenario in which the plant effluent flow rate is 6.5 mgd. If, for example, the filter capacity is 3.5 mgd, and 3.0 mgd bypasses the filter, the effluent BOD5 of 60 mg/L should be met, but there would be no safety factor.

Figure 15 Impact of Filter Capacity on Effluent BOD5 Concentration

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 13
On the other hand, treating 5.0 mgd through the filter should produce a combined effluent BOD5 concentration of around 54 mg/L, which provides a 10 percent safety factor to account for variations in flow and concentration. The combined effluent would be expected to have a TSS value of around 20 mg/L.

6.1 Cost Estimate
Based on the above, a capital and operations and maintenance (O&M) cost estimate was developed for the construction and operation of a partial-filtration system with a nominal capacity of 5.0 mgd. Figure 16 presents a simplified process flow diagram and a preliminary layout showing the proposed location of the tertiary filters and arrangement of the major piping runs.

Figure 16 Simplified Process Flow Diagram and Preliminary Layout for Tertiary Filters

6.1.1 Planning Level Capital Cost
The new filters would be located just south of the existing Percolation Pond Pump Station structure and would receive flow from the distribution box just upstream. New transfer pumps would be provided to lift the effluent to the filters, which would be located on a concrete slab under a shade canopy. An example installation is shown in Figure 17. Filtrate from the filters would be returned to the Percolation Pond Pump Station, from where it would be distributed to the existing and proposed new percolation ponds. The backwash water from the filter, up to 280 gpm, would be directed to just downstream of the existing grit chamber, where the flow distribution to the primary clarifiers occurs. This stream would receive a dose of ACH in a mixing tank located near the filters before being pumped to the grit chamber area. Settled solids would be captured in the primary clarifiers and pumped to the anaerobic digesters.

Quotations were obtained from two cloth filter manufacturers, Nexom and Aqua-Aerobics, for the equipment that would be needed. The cost includes installing two filters, each 2.5 mgd capacity, on a concrete slab under a shade canopy (Figure 17). Although the tertiary filters would be a "temporary" facility and not needed once the Phase 1 project is completed, the installation would need to operate until

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 14
the end of 2033, approximately 8 years from now. For the cost estimate it was therefore assumed that this would be a fully functional tertiary filter installation.

Figure 17 Example Tertiary Filter Installation With Shade Cover A summary of the planning level cost estimate (Class 5) is shown in Table 4. A more detailed table showing the breakdown of the Direct Costs is included in Attachment B. As indicated in Table 4, the construction cost is estimated to be a little over $7 million, with a total project cost, including engineering design and construction support etc., of almost $9 million.

Table 4 Planning Level Cost Estimate for Tertiary Filters Item Description Amount
1 Tertiary Cloth Filters
- Site Construction $264,000
- Concrete Work $196,000
- Steel Canopy Structure $281,000
- Cloth Filters, Pumps, Backwash Chemicals, etc. $2,031,000 - Mechanical $361,000
Subtotal $3,133,000
2 Electrical (20%) $627,000
3 Instrumentation and Controls (10%) $313,00
Subtotal - Direct Costs $4,073,000
4 Contingency (30%) $1,222,000
5 Contractor Mark-ups (General Conditions, Overhead and Profit) $1,556,000 6 Sales Tax $232,000
Estimated Construction Cost $7,083,000

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 15
Item Description Amount
7 Engineering (Design and Construction Support) (17%) $1,204,000 8 Legal, Admin, and Regulatory Costs $637,000
Total Project Cost Estimate $8,924,000

6.1.2 Planning Level O&M Cost
To estimate the anticipated O&M costs for a new tertiary filtration facility, estimates were made for electrical power use and chemical use. For electrical power, the major areas would be for the new filter feed pumps, which were assumed to require 15 feet of lift, and the backwash water return pumps, which would require about 10 feet of lift. Electrical power costs were assumed to be $0.25/kilowatt-hour (kWh).

The major chemical cost would be for ACH to be added to the backwash water to help with coagulation and settling. There will also be added O&M associated with the additional solids that will settle in the primary clarifiers and be processed in the anaerobic digesters. These solids will add to the load on the sludge drying beds and the mass of solids hauled from the site. Solids disposal costs were based on the values presented in Volume 8 and assume 70 percent solids and a 75:25 percent split between disposal to Engle and Grey and the City's landfill. Table 5 presents a summary of the O&M cost.

Table 5 Planning Level Annual O&M Cost Estimate for Tertiary Filters Item Description Amount
Annual Cost
Comments
1 Electrical Cost(1)
- Filter Feed Pumps $33,800 3,500 gpm @ 15 ft
- Backwash Transfer Pumps $1,800 280 gpm @ 10 ft
- Tertiary Filters (drive and backwash pump) $9,800 About 5 hp combined 2 Chemicals
- ACH in Backwash(2) $137,000 100 mg/L dosage
3 Solids
Estimate for additional Solids Disposal (11 wet tons/month)(3) $4,200 Assumes 15,600 lb/month DS Total O&M Cost Estimate $186,600
Notes:
hp - horsepower
(1) Assuming $0.25/kWh.
(2) 100 mg/L and 150 mg/L almost provide the same performance, and lower dose saves $60,000. (3) Based on 75:25 split at $33.61 and $26.63 per wet ton (=>$31.9).

SECTION 7 DISCUSSION
Construction of a new $9 million tertiary filtration facility that does not have a need once the Phase 1 construction is completed in 2033 seems like an additional unnecessary burden that the City will need to carry should the Regional Water Board request that the tertiary facilities be constructed.

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 16

7.1 Meeting with the Regional Water Board
At a meeting held with the Regional Water Board on November 19, 2025, the results from the pilot testing were presented and discussed. It was noted that based on the results, the City would need to filter about 80 percent of the secondary trickling filter effluent (~ 5 mgd) and blend it with the remaining flow to produce a combined effluent BOD5 less than 60 mg/L.

The City had looked into long-term rental of tertiary filter equipment and it was determined that this approach would probably not be feasible since the City would pay for the equipment several times over.

The planning level cost estimate to purchase and install a 5-mgd tertiary filtration system was noted as being $9 million (2025). And the annual electrical, chemical, and solids disposal costs were expected to total around $190,000.

In addition, it was noted that the City was concerned about potential unintended consequences associated with adding a new process (partial tertiary filtration) to the treatment train. For example, it was not clear what the long-term impact of adding polymer to the backwash water might be, given the high recirculation rates associated with the current trickling filter treatment process. Also, allowing time for design and construction and the supply chain issues with electrical equipment it was estimated that a new tertiary filtration system would only be expected to be in operation in 2029, which means there would be limited effluent quality benefits prior to the upgraded plant coming into operation. Furthermore, the $9 million (2025) cost was an unplanned capital expenditure for the City, which is already having to find funds to pay for the approximately $500 M main project.

The Regional Water Board acknowledged that the $9 M cost estimate was significant.

It was also pointed out that during the course of the pilot work and development of materials for the master plan, the City had recognized the long-term benefit of incorporating tertiary filtration for the main project, for two main purposes:
 As a means to protect/enhance the performance of the percolation ponds, by minimizing the amount of solids discharged to the ponds. The City will be undertaking maintenance work on all of the ponds to remove fine material that has built up over many years of operation, and this is a costly exercise.  To provide a source of recycled water that can be used for in-plant use, thereby avoiding the additional of an external water source that would need to be percolated.

Each of the above is discussed in more detail in the following sections.

Despite the above long-term benefits, the City was of the opinion that a temporary filtration solution to address BOD5 introduces complications within the plant with parallel projects and sequencing of work and hinders progress and dilutes the focus on the main larger project. The Regional Water Board acknowledged the work that had been done and agreed that the task set out in the Time Schedule Compliance Plan that included studies by the City for interim BOD5 and TSS compliance was complete.

7.1.1 Reduced Solids Loading on the Percolation Ponds
During the pilot testing, the secondary treated trickling filter effluent had an average TSS concentration of around 30 to 35 mg/L. At an effluent flow rate of 6.5 mgd, this represents a load of about 52,000 lb/month of solids to the ponds, or almost 310 tons per year. Cleaning the ponds by removing, washing, and replacing the sand is a costly operation. Volume 7, Chapter 2 of the Master Plan

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 17
recommended that the City budget to spend $23 million over a 5-year period to rehabilitate the ponds and that this be repeated every 10 to 15 years as percolation rates decline.

Yeh and Associates noted the impact of suspended solids on infiltration in their geotechnical analysis of the ponds. Figure 18 is taken from their report that shows a curve developed by Rice in 1974, and indicates the low infiltration rate, indicated by the pink arrow, at a TSS value of 41 mg/L, which was the average effluent TSS reported by the City in 2023. The figure also includes a black arrow at 20 mg/L (point "A"), which would be the anticipated TSS blend downstream of the filters, and the arrow at point "B" is the anticipated TSS in the effluent from the secondary clarifiers after Phase 1 is complete, between 5 and 10 mg/L. Based on the curve in Figure 18, a change in TSS from 41 to 20 mg/L would more than double the infiltration value. And the water quality from the Phase 1 facility would more than triple the infiltration value compared to point "A".

Figure 18 Impact of TSS (Cs) on Total Infiltration (S) - from Rice 1974 In terms of mass of solids, the tertiary filters, with a TSS concentration of about 20 mg/L, would reduce the solids load by about 30 percent, to 200 tons per year. And when the Phase 1 project comes online, the solids load on the ponds would be halved to less than 100 tons per year.

The City is planning to construct new percolation ponds, which are expected to be operational in about 3 years. These ponds will receive effluent from the existing WWTP for about 6 years before the Phase 1 process is fully operational. Providing tertiary-treated effluent to the new ponds would be expected to provide a benefit in terms of the reduced solids load and any impacts on percolation caused by fine organic solids. The financial benefit has not been determined.

7.1.2 A source of Water for In-Plant Use
Recently, the City completed a project to bring City water to the WWTP, which is now used as in-plant utility water. Prior to that, the WWTP used a local on-site groundwater well to provide utility water.

B
A

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 18
Approximately 800,000 gallons per month are currently being used; 18.5 gpm on average. When the Phase 1 project comes online, the plant's water use is expected to be significantly greater. Major usage will occur in the new aeration basins for foam/scum control, and in the solids thickening and dewatering steps for removing solids from the drums or belts, together with other minor use around the plant. This is discussed in more detail in Volume 13, Chapter 1.

The tertiary filters can be used to provide flow for a new utility water system. This would consist of a disinfection step, likely using chlorine, some storage capacity, a pump station, and a utility water distribution system. Based on the initial estimates, not all of the anticipated 5 mgd filtration capacity would be needed.

SECTION 8 CONCLUSIONS
The City completed a five-month tertiary filter pilot test, and based on the analysis of the data, the following conclusions can be made:

1. Tertiary cloth filters with a 10-micron nominal pore size can effectively treat the secondary trickling filter effluent and reduce the BOD5 and TSS concentrations.

2. The pilot filter, operating at a flowrate of between 370 and 470 gpm was able to achieve an overall recovery of between 92 and 97 percent.

3. The filter operated at hydraulic loading rates of between 3.5 and 4.5 gpm/sf, and the loading rate did not seem to impact either BOD5 or TSS removal efficiency.

4. Thirteen 24-hour composite samples of the filtered effluent collected between February and April 2025 showed that the BOD5 concentration could be reduced to less than 60 mg/L.

5. An aluminum-based polymer (ACH) added to the filter feed stream at dosages of 1, 5, and 10 mg/L did not improve either BOD5 or TSS removal efficiency.

6. Dosages of ACH of up to 50 mg/L could not increase the solids settleability in the filter backwash water. However, above 100 mg/L, good improvement in settleability was observed.

7. An analysis showed that filtering 5 mgd of the secondary trickling filter effluent and blending the remaining untreated flow (1.5 mgd) would produce an effluent with a BOD5 concentration of approximately 54 mg/L, providing about a 10-percent safety factor below the 60 mg/L interim limit to allow for flow and water quality variations.

8. The planning level total project cost estimate (Class 5) for a 5 mgd tertiary filtration system is $8.9 million (2025).

9. Operationally, the 5 mgd tertiary filtration system is expected to cost about $187,000 per year to operate. This cost includes the expected electricity use, additional solids disposal, and more than 70 percent of the cost would be for polymer addition to the backwash water. The polymer dose could potentially be lowered during actual operation given the long detention time in the primary clarifiers, which would reduce the anticipated O&M costs. The O&M costs do not include typical wear and tear costs for the filtration system.

10. In addition to providing the filtration system to meet the interim BOD5 effluent limit, the filters would offer additional benefits. First, they would reduce the organic solids load on the new and existing

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 19
ponds, thereby preserving the percolation rate (particularly for the new ponds). Second, once Phase 1 is in operation, a portion of the filter capacity could be retained for providing flow for a new utility water system for the WWTP.

11. The City sees the value in long-term use of tertiary filtration for the main project, but installing a temporary filtration system introduces complications and only provides limited effluent quality benefits for the cost. Therefore, the best use of resources would be to build filtration into the main Phase 1 project rather than provide an interim solution.

12. The Regional Water Board agreed that the studies to be performed by the City for interim BOD5 and TSS compliance (Task 1) were complete. Therefore, a temporary filtration system to reduce BOD5 and TSS would not be needed.

TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA

WASTEWATER TREATMENT PLANT MASTER PLAN

ATTACHMENT A TERTIARY FILTER PILOT TEST PLAN

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan

TECHNICAL MEMORANDUM
Tertiary Filter Pilot Test Plan
FINAL / October 2026

CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan

TECHNICAL MEMORANDUM
Tertiary Filter Pilot Test Plan
FINAL / October 2026
Digitally signed by Graham J.G. Juby
Contact Info: Carollo Engineers, Inc.

Date: 2026.10.21 18:23:23-07'00'

TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN i
pw://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/WWTP Tertiary Filter Pilot Sampling Plan/TM_TertiaryFilterPilotTestPlan.docx Contents
SECTION 1 PURPOSE AND OBJECTIVES 1

1.1 Project Team 1

1.2 Project Goals 1
SECTION 2 BACKGROUND 2
SECTION 3 DESCRIPTION OF WORK TASKS 2

3.1 Coordination of Rental Unit and Set Up 2

3.1.1 Electrical Requirements 3

3.1.2 Grading/Site Requirements 3

3.1.3 Pumping/Piping Requirements 3

3.2 Pilot Plant Operation 5

3.2.1 Commissioning and Start-up 5

3.2.2 Phase 1 Operation – Initial Filter Loading Tests 5

3.2.3 Phase 2 Operation – Continuous Operation (No Chemicals) 6

3.2.4 Phase 3 Operation – Filtration Optimization (With Chemicals) 7

3.3 Sampling Plan 8
SECTION 4 MONITORING AND SAMPLING PLAN 9
Appendices
APPENDIX 1 NEXOM UNIT DRAWINGS
APPENDIX 2 DAILY LOG SHEET
APPENDIX 3 NEXOM EXAMPLE BROCHURE FOR TRAILER PILOT UNIT Tables
Table 1 Nexom Package Filter Specifications 4
Table 2 Filter Loading Rate Evaluation 6
Table 3 Preliminary Approach for Backwash Water Jar Testing 7 Table 4 Monitoring and Sampling Plan 9
Figures
Figure 1 Proposed Site Layout and Backwash Flow Paths for Nexom Filter 4

TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN ii
Abbreviations
ACH aluminum chloralhydrate
amps amperes
BOD5 5-day biochemical oxygen demand test
Carollo Carollo Engineers
City City of Santa Maria
COD chemical oxygen demand
ft feet
ft2 square feet
gpm gallons per minute
gpm/ft2 gallons per minute per square foot
lb/ft2 pounds per square foot
mg/L milligrams per liter
N/A not applicable
NTU nephelometric turbidity unit
PLC programmable logic controller
Title 22 California Code of Regulations Title 22
TOC total organic carbon
TSCP Time Schedule Compliance Plan
TSS total suspended solids
Water Board Central Coast Regional Water Quality Control Board WWTP wastewater treatment plant

TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1
SECTION 1 PURPOSE AND OBJECTIVES
This technical memorandum outlines the recommended tertiary filter pilot test plan for the City of Santa Maria (City) Wastewater Treatment Plant (WWTP). The pilot test plan sets out the proposed testing phases to gather data to assess the performance of the cloth filter on the secondary trickling filter effluent. The City is working towards reducing the 5-day biochemical oxygen demand test (BOD₅) concentration in the WWTP effluent to below 60 milligrams per liter (mg/L) which is the current interim discharge limit.

Currently the trickling filter effluent is not able to meet the 60 mg/L limit. Data collected during the pilot study will be used to assess the feasibility of using a tertiary filtration step as a tool for the City to reach its permitted discharge requirements.

The pilot testing will be conducted over three months, beginning around August 1, 2024.

1.1 Project Team
The team of engineers and companies for this pilot project is as follows:
 Project manager - Carollo Engineers (Carollo).
 Host agency – City of Santa Maria.
 Vendor equipment providers:
» Nexom – cloth filter and required accessories.

1.2 Project Goals
The project aims to operate a package cloth filter furnished by Nexom Inc, downstream of the existing secondary trickling filter system to achieve the following goals: The overarching objective is to reduce total suspended solids (TSS) and BOD₅ concentrations to the new discharge limits provided by the Central Coast Regional Water Quality Control Board (Water Board) as part of the ongoing Time Schedule Compliance Plan (TSCP). Other objectives for this project include:

1. Establish appropriate operating criteria for the tertiary filter:
a. Filter loading rate.
b. Backwash frequency.
c. Overall recovery.

2. Establish the TSS and BOD₅ removal efficiency achieved by the tertiary filter. Understand how the TSS and BOD₅ removal efficiency is impacted by the filter loading rate.

3. Establish the most appropriate method to deal with backwash water from the filter:
a. Return to the grit basins.
b. Return to the secondary trickling filter system.
c. Return to the intermediate clarifier for settling.

4. Establish whether coagulants are needed to assist with the filtration process.

TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2
SECTION 2 BACKGROUND
The City is currently undergoing a master planning effort to upgrade its existing WWTP in order to comply with updated permit requirements. Currently, the treatment plant utilizes trickling filters as the secondary treatment process. A detailed evaluation of the performance of the existing plant has shown that the trickling filters are performing as well as can be expected, and although the secondary effluent has an average TSS concentration of 38.6 mg/L (2018 to 2023), the BOD₅ concentration has been above 60 mg/L.

The Water Board has encouraged the City to explore alternatives to improve the secondary effluent quality and reduce the BOD₅ to below the interim limit of 60 mg/L.

Laboratory filtration of secondary effluent samples indicated that tertiary filtration may be a suitable approach to reduce the TSS concentration further and thereby reduce the BOD₅ concentration.

In June, 2024, per the requirements of the City’s new General Order, the City submitted a TSCP to the Water Board. The TSCP sets out a phased approach to reducing the BOD₅ concentration to below the interim limit of 60 mg/L. Conducting a tertiary filter pilot test and assessing the suitability of tertiary filtration to achieve the BOD₅ limit is the first step. Per the TSCP, the City is required to meet with the Water Board in December 2024 to discuss the results of the tertiary filter pilot study. If the results are found to be satisfactory then the City could implement a larger scale tertiary filtration process.

The implementation of a tertiary cloth filter downstream of existing secondary treatment processes is anticipated to improve TSS and BOD₅ effluent quality. Cloth filters utilized as a tertiary polishing step have been a reliable technology for removal of BOD₅ and TSS wastewater treatment plants around the world.

Nexom Inc, is the selected manufacturer for the pilot filter; they provide rental units that can be installed on a temporary basis to assess the treatment outcomes on City effluent.

The rental filter unit, in conjunction with this sampling and testing plan, may result in improved outcomes, and allow for compliance with the new interim effluent discharge limits.

SECTION 3 DESCRIPTION OF WORK TASKS
There are four major tasks in this project, each of which are described in this section.

3.1 Coordination of Rental Unit and Set Up
The goal of this task is to set up the pilot equipment at the City's WWTP. The City, Carollo, and Nexom Inc, are currently coordinating electrical, grading, power, and piping requirements for the package cloth filter pilot. The City has received a proposal and price quotation from Nexom for a fully integrated pilot skid that can treat up to about 800 gallons per minute (gpm). The City will contract with Nexom for the pilot equipment and the sampling work to FGL laboratories. Wastewater operators onsite will assist in collection and distribution of samples to the laboratory.

TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 3

3.1.1 Electrical Requirements
The City has identified existing conduits that can be used to provide the required power to the area that the pilot filter will be located; close to one of the existing secondary clarifiers. The City will take care of providing any additional breakers in the motor control center and the cable for the power supply.

3.1.2 Grading/Site Requirements
Some slight grading will be needed to level that area where the 40-foot package pilot unit will be located.

There is sufficient space near one of the secondary clarifiers to locate the unit.

3.1.3 Pumping/Piping Requirements
Feed pumps (three) for the secondary effluent will be located in the secondary clarifier effluent launder.

Nexom will provide the pumps and the piping needed to convey the feed water to the tertiary filter.

Filtered effluent from the pilot will be directed to the percolation ponds with the rest of the secondary effluent. Backwash from the pilot filter will be initially directed to the secondary trickling filter pump station. The best location for the backwash water will be investigated as part of the study. The other locations to be investigated are:

1. Sludge drying bed, from where the flow can be returned to the grit chamber.

2. Primary trickling filter pump station.

3. Intermediate clarifier.

Appendices 1 and 3 show the pilot unit drawings and the associated brochure.

The cloth filter itself is fitted with on-line turbidimeters that continuously record the nephelometric turbidity unit (NTU) of the feed and filtrate. Data from the on-line analyzers will be stored in the pilot programmable logic controller (PLC). The effluent/filtrate line is fitted with a low range turbidimeter that is a self-cleaning unit. On the feed water side where the turbidity is higher, there will be a higher range probe type analyzer that has a range of 4 NTU to 100 NTU.

The pilot rental package includes submersible pumps, backwash pumps, and chemical pumps for the addition of coagulants. Coagulant testing may be tested, depending on the Baseline filter performance, discussed further below. The existing chemical day tanks in the pilot filter will be filled with sufficient chemical for testing, as needed.

It is anticipated that the pilot unit will be set up and commissioned by Nexom in late July 2024.

TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 4
Figure 1 Proposed Site Layout and Backwash Flow Paths for Nexom Filter The Nexom filter has the following performance criteria:

Table 1 Nexom Package Filter Specifications
Description Value Units
Influent Flow 600-800 gpm at 20 ft of head
Filter Head loss 24 inches
Maximum Filter Area 108 ft2
Cloth media pore size 5 or 10 micron
Backwash Flow 80 gpm
Backwash Cycle 5-15 minutes
Max hydraulic loading up to 10 gpm/ft2
Max Solids Loading 3 lb/ft2.d
Electrical Requirements 40-50 amps
Notes:
amps - amperes; ft - feet; ft2 - square feet; gpm/ft2 - gallons per minute per square foot; lb/ft2 - pounds per square foot

TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5

3.2 Pilot Plant Operation
The pilot testing is anticipated to last for three months: August, September and October 2024.

The operational sequencing of the pilot filter will be critical to ensure applicable results. Float switches in the filter unit will determine when the filter is backwashed and the feed pumping rate based on filterability.

The WWTP’s regular working hours are from 7:30 a.m. to 4:30 p.m. Monday through Friday. During the initial set up the pilot filter will be operated during regular working hours, but once the City has confidence in the equipment it will be set to run continuously. An integrated control system and human machine interface panel will be used to set the operating parameters. Operators will record the daily set points for feed flow and backwash rate on a Daily Log Sheet – see Appendix 2. The Daily Log Sheet will also record values for feed and effluent turbidity, flow rates, head loss, and backwash intervals. This information will be tracked and consolidated in a reporting matrix.

Sample collection and analysis of the liquid streams will occur regularly throughout the pilot testing period, as outlined below and in Section 4.

The following phased operation of the pilot filter is planned.

3.2.1 Commissioning and Start-up
Nexom will be on-site for the commissioning and start-up of the pilot unit once it has been mechanically plumbed and the power supply provided.

It is anticipated that this period will last approximately including time for troubleshooting, if needed.

3.2.2 Phase 1 Operation – Initial Filter Loading Tests
The Phase 1 Initial Filter Loading tests are anticipated to last for 1 week. The purpose of this phase of the study is to determine what a reasonable feed flowrate and backwash frequency is for the secondary trickling filter effluent. Trickling filter secondary effluent tends to perform differently, in terms of filterability, compared with typical activated sludge secondary effluent. The California Code of Regulations Title 22 (Title 22) requirements for the Nexom tertiary cloth filters show a maximum loading rate of

10.0 gpm/ft2. The Santa Maria plant is not aiming to produce Title 22 quality effluent for reuse, but the Title 22 loading rate provides an indication of a rate that the State of California feels is sustainable. The purpose of this phase of testing is to determine an initial loading rate for the filter.

The pilot filter will be operated at a series of “conditions” outlined in Table 2, to determine which set of conditions works most favorably. For each “condition” a filter loading rate has been selected. Each loading rate corresponds to a specific feed flow rate. It is anticipated that as the filter loading rate increases (from Condition 1 to Condition 3), so the backwash frequency may increase. Condition 1 is set with a low loading rate (4.0 gpm/ft2) as an initial check to confirm that such a rate is achievable with the plant effluent quality. The most favorable conditions will be those at which the filtration rate can be as high as possible and the backwash frequency can be as low as possible; that is the maximum time of 15 minutes which is the current limit set by Nexom. This will minimize the backwash volume that the plant has to deal with.

TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 6
For this testing the filter will be operated on a daytime basis only. For each “condition” the filter will begin operation at the start of the day (say around 8:00 a.m.) and the objective will be to keep the filter operating at the selected operating condition for the remainder of the day (until around 4:00p.m.). Once the pilot is operating the PLC will record the feed and filtrate flowrate and turbidity and the filter head loss. One grab sample of the feed and filtrate stream will be collected each day for analysis in the plant laboratory for TSS and chemical oxygen demand (COD) or total organic carbon (TOC), if possible.

Table 2 Filter Loading Rate Evaluation
Description
Filter Hydraulic
Loading Rate
(gpm/ft2)
Feed Flow
(gpm)
Backwash
Frequency
(minutes)
Comments
Condition 1 4.0 432 Can 15 min be
achieved?
Record Filter Headloss with time; record feed and
filtrate flow and NTU continuously; take one sample
for COD and TSS.

Condition 2 5.0 540 Can 15 min be
achieved?
Record Filter Headloss with time; record feed and
filtrate flow and NTU continuously; take one sample
for COD and TSS.

Condition 3 7.0 756 Can 15 min be
achieved?
Record Filter Headloss with time; record feed and
filtrate flow and NTU continuously; take one sample
for COD and TSS.

Condition 4 TBD TBD TBD Record Filter Headloss with time; record feed and filtrate flow and NTU continuously; take one sample
for COD and TSS.

Notes:

TBD - to be determined
After completion of Condition 3, the performance results for all three Conditions will be assessed. Based on the results a filter loading rate and a target backwash frequency will be selected for Condition 4. The filter will be operated at Condition 4 to confirm that performance can be met.

3.2.3 Phase 2 Operation – Continuous Operation (No Chemicals) Phase 2 is anticipated to last for a minimum of 2 weeks and will build on the results/performance of Phase 1. If the filter met the performance criteria during the Condition 4 from Phase 1 testing and performed well, the pilot filter filtration system will be set up to operate at similar conditions during Phase 2 testing. During Phase 2 the filter will be switched to 24-hour operation. The objective will be to keep the filter operating and confirm that the chosen loading rate and backwash frequency is sustainable.

Samples of feed and filtrate will be collected daily for BOD₅ and TSS analysis. Turbidity will continue to be recorded automatically. The feed and filtrate flows and the backwash frequency will be recorded by the PLC.

At the end of Phase 2 the performance data will be evaluated to confirm whether or not the filter loading used during Phase 2 was suitable for long term operation. If it is decided to adjust the filter loading conditions, then the filter will be operated for an additional week at the new loading conditions, until the team is comfortable with the filter performance.

TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 7

3.2.3.1 Backwash Water
One concern is whether the backwash solids will settle readily so that they can be thickened and then pumped to the anaerobic digesters and removed from the system. During this period the backwash water will be directed to the secondary trickling filter pump station and will be returned to the secondary trickling filters. Samples of backwash water can be collected for conducting some initial settling tests in the laboratory at the WWTP. The purpose of the jar testing will be to understand the settleability of the backwash water to gauge how it might impact the downstream processes.

Carollo’s jar testing equipment can be used for this purpose. Table 3 presents a preliminary approach to conducting initial screening of coagulants to identify whether any show improved settling of the solids in the backwash. All six coagulants shown in Table 4 have been used in previous jar testing. The idea would be to run a series of initial screening jar tests using one coagulant at a time and using constant mixing and settling times to determine which chemicals work best. The determining factor will be a visual assessment of which dose provides the most solids accumulation and the best visual clarity. Turbidity measurements of the supernatant can be performed in the laboratory to assist with the assessment. Based on the findings from the initial screening it is anticipated that several of the chemicals and dosages will be eliminated. Depending on the results additional testing of the “best performing” chemical(s) may be carried out to refine the analysis further to determine whether chemical addition should be applied to the backwash stream as part of the pilot testing.

Table 3 Preliminary Approach for Backwash Water Jar Testing Test Number and Description
Jar Number and Dose (1)
Comment
1 2 3 4
Test 1-Ferrous chloride Control 2 5 10
Test 2-Ferric chloride Control 2 5 10
Test 3-ACH Control 2 5 10
Test 4-Brennfloc RE 5000 Control 5 10 20
Test 5-Alum Control 2 5 10
Test 6-Clarifloc Control 2 4 6
Notes:

ACH - aluminum chloralhydrate
(1) Number = dose in mg/L of metal salt (iron or aluminum) or polymer.

3.2.4 Phase 3 Operation – Filtration Optimization (With Chemicals) The purpose of Phase 3 will be to try to improve the performance of the filter (under the conditions tested in Phase 2) by the addition of a coagulant to the filter feed stream. The filter loading conditions established during Phase 2 will be maintained for Phase 3. The following chemicals will be tested sequentially during Phase 3:
 Ferrous chloride – this chemical is already available on site and will be tested first.  Ferric chloride.
 ACH.

TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 8
For the initial testing, ferrous chloride will be added to one of the day tanks in the pilot filter skid. Before setting the initial dose a set of jar tests will be performed to establish a starting point. The jar testing will be run with doses of 2, 4 and 6 mg/L as iron. Based on the results of the jar testing the initial dosing rate will be set and the filter will be operated continuously. The performance of the filter will be assessed over a one or two day period to determine whether there is any improvement in performance. Since the feed rate will be fixed, to provide a given filter hydraulic loading rate, the performance will be assessed based on the clarity (turbidity) of the filtrate, the TSS of the filtrate and the required backwash rate. If no improvement is seen, the chemical dose will be increased to based on the initial jar testing and the exercise repeated. At the end of the one or two day operating period the chemical will be switched to ferric chloride and the process will be repeated. Again, initial jar testing will be performed to establish the starting point for chemical addition.

Similarly, the exercise will be repeated using ACH as the coagulant.

This phase is expected to take about 3 weeks to complete; one week per chemical.

The test protocol is flexible and will be adjusted depending on the results that are obtained. If good performance is obtained with ferrous chloride then there may not be a need for further testing.

3.2.4.1 Longer-term Performance
After assessing the benefits of adding a coagulant to the feed stream, the pilot unit will be operated under the conditions determined to provide the best filter performance. Sample collection for laboratory analysis will be conducted during this period (see next section), which is expected to last a minimum of 2 weeks.

3.3 Sampling Plan
The proposed sampling plan/matrix for the pilot study is included in Table 4. As shown, it is anticipated that some samples will be analyzed on-site, either through instruments installed in the various pilot units, or by handheld meters used by the pilot plant operator. Other samples will be collected on a daily basis from Monday to Friday during working hours and analyzed at FGL laboratories. FGL can coordinate pickup of the cooled samples. It is recommended that TSS grab samples are taken once a week concurrently with the automatic readings.

TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 9
SECTION 4 MONITORING AND SAMPLING PLAN
Daily samples of the cloth filter influent, effluent and backwash flows shall be taken and refrigerated. It is expected that about 4 L of sample shall be collected at each stream for BOD₅ and TSS analysis. The following table indicates at what location each constituent should be sampled from.

Table 4 Monitoring and Sampling Plan
Parameter
Analytical
Method
Sampling Locations Phase 1 Phase 2 Phase 3
Cloth Filter
Feed
Cloth Filter
Effluent
Backwash Daytime Only 24 Hours/Day 24 Hours/Day
Flow, gpm N/A FIT-101 FIT-103 FIT-102 Continuous Continuous Continuous Turbidity, NTU On-line
Analyzer
AT-101 AT-??? - Continuous Continuous Continuous
Laboratory Samples
pH   Twice daily(1) Twice daily(1)
TOC   Twice daily(1) Twice daily(1)
COD   Two per run(1) Twice daily(1) Twice daily(1)
BOD5 SM 5210 B   Twice daily(1) Twice daily(1)
TSS SM 2540 D    Two per run(1) Twice daily(1) Twice daily(1) Notes:

N/A - not applicable
(1) Correlate with daily high and low NTU diurnal pattern.

TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA

WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX 1 NEXOM UNIT DRAWINGS
A
B
8 0.1

0.2 0.3

0.4 0.7

0.6 0.5

0.8 0.9
±
2 9
16 3
4 8
13 5
7 12
12 15
10 1

0.1 0.2

0.3 0.4

0.7 0.6

0.5 0.8

0.9 0.1

0.2 0.3

0.4 0.7

0.6 0.5

0.8 0.9
Free space
for discs
maintenance
VIEW FROM "A" SECT. "C-C" VIEW FROM "B"
01020304
nome file:
05 ClienteCustomer
Subject
Oggetto
Description
Descrizione
Revision
Revisione
Date
Data Modificato da
Revised by Checked by Approved by
Controllato da Approvato da
Customer approvalApprovazione da cliente
DateData
Disegnato
Drawn by Approved
Approvato
Drawing N°
ScalaScale
N° Disegno
Dim.

Dim.

SheetFoglio
NEXOM, INC.
888-426-8180
www.nexom.com
E-mail: [email protected]

CLOTH DISC FILTER IN METALLIC TANK
MSF 6/30 PEC VVM

STANDARD ASSEMBLY

VERTICAL FILTER
MDA-MSF630PECVVM-12070R06
VAGHI
26-03-12 1di1 1:25 A2
MDAMSF630PECVVM12070R06 Assieme commerciale 6-30 23-06-2020 CHANGED POSITION OF BOTTOM SLUDGE PUMP REINA 14 6
14 300 2
300 2
300 2
Free space
for discs
maintenance
01020304
nome file:
05 ClienteCustomer
Subject
Oggetto
Description
Descrizione
Revision
Revisione
Date
Data Modificato da
Revised by Checked by Approved by
Controllato da Approvato da
Customer approvalApprovazione da cliente
DateData
Disegnato
Drawn by Approved
Approvato
Drawing N°
ScalaScale
N° Disegno
Dim.Dim.

SheetFoglio
NEXOM, INC.
888-426-8180
www.nexom.com
E-mail: [email protected]

CLOTH DISC FILTER IN METALLIC TANK
MSF 6/30 PEC VVM

PROPOSAL LAYOUT
Layout proposal
Donati
07-02-2024 1di1 1:25 A2
Layout proposal Fort Saint John 6-30 PECV VM
11 1
6 7
8 B
A
Free space
for discs
maintenance
11 1
6 7
B

TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA

WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX 2 DAILY LOG SHEET
Record Current Setpoints Programmed in PLC
Record the following values from PLC:

Feed (from Secondary Clarifiers) Filtrate (to Percolation Ponds) Backwash Feed
Flow
(gpm)
NTU Filter Headloss Time Recorded 4L Sample Taken? Filtrate flow (gpm) NTU Filter Headloss Time Recorded 4L Sample Taken? Backwash Flow (gpm) Backwash Frequenc y (minutes) Time Recorded 4L Sample Taken? Morning
YES
NO
YES
NO
YES
NO
Afternoon
YES
NO
YES
NO
YES
NO
Evening
YES
NO
YES
NO
YES
NO
Record the Amount of Chemical Dosing (if no chemical dosed, leave blank) General Observations (include information on clarity of effluent/influent/backwash) Coagulant Dosed Time of Initial Dose Dose amount (mg/L) Filter Loading Rate: gpm/ft2
Feed Flow: gpm
Backwash Flow: gpm
Backwash Interval: minutes
Daily Log Sheet City of Santa Maria Tertiary Filter Pilot Date: Operating Condition (circle one): Operator Initials:
1 2 3 4

TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO

CITY OF SANTA MARIA

WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX 3 NEXOM EXAMPLE BROCHURE FOR

TRAILER PILOT UNIT
Pilot Project Study
Nexom’s Pile Cloth Filter
March 15th , 2024

KAUFMAN, TX

PILOT PROJECT
Example Only
CD25771.01 KAUFMAN TX 2
Project Overview
The Nexom Mita pile cloth filter (PCF) will be piloted for Kaufman in Texas. The pilot will be conducted to:
• Treat secondary effluent wastewater, measuring efficiencies for turbidity and TSS reduction.
• Validate hydraulic and surface solids loading limits of the cloth media technology • Provide engineers the opportunities to observe standard O&M for Mita pile cloth disk filter equipment
• Provide the owner with the opportunity to interface with the Mita pile cloth disk filter, experience and provide feedback on system controls, and validate its performance The Mita pilot filter system is a turnkey system designed for continuous discharge. 1000+ Mita filters worldwide minimize the owners expense and effort in maintaining wastewater treatment standards. The Mita filter consumes the smallest footprint in the lowest available hydraulic profile. Nexom delivers with factory-installed backwash systems and access platforms, leading the industry in quality and safety features.