Brick Masonry
04221-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/04221 (BidSetFinal) SECTION 04221
BRICK MASONRY
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Brick masonry units.
1.02 REFERENCES
A. ASTM International (ASTM):
1. C62 - Standard Specification for Building Brick (Solid Masonry Units Made from Clay or Shale).
2. C67 - Standard Test Methods of Sampling and Testing Brick and Structural Clay Tile.
3. C216 - Standard Specification for Facing Brick (Solid Masonry Units Made from Clay or Shale).
4. C652 - Standard specification for Hollow Brick (Hollow Masonry Units Made from Clay or Shale).
1.03 SUBMITTALS
A. Product data.
B. Shop drawings: Include elevations of each wall indicating type and layout of units.
C. Samples: Include samples of stretcher units in sufficient quantity to illustrate color range.
D. Test reports.
1.04 QUALITY ASSURANCE
A. Continuous inspection:
1. Employ a qualified masonry inspector for continuous inspection of the masonry work.
a. Acceptance by a state or municipality having a program of examining and certifying masonry inspectors will be considered adequate qualifications. b. The masonry inspector shall be at the site during all masonry construction and perform the following duties:
1) Review drawings and specifications and meet with the Contractor to discuss requirements before work commences.
2) Before masonry work commences, Contractor and the Contractor's Quality Control Representative shall attend meeting with Engineer to review the requirements for surveillance and quality control of the masonry work.
3) Check brand and type of cement, lime (if used), and source of sand.
Brick Masonry
04221-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/04221 (BidSetFinal) 4) Ensure that foundation is clean, rough, and ready to receive units. 5) Check reinforcing steel dowels for straightness, proper alignment, spacing, size, and length.
6) Observe field proportioning of mortar. Visually check aggregate to determine uniformity of grading, cleanliness, and moisture. 7) Ensure that joints are full of mortar and kept tight during work. a) Inspect grout cells to ensure that fins will not interfere with grouting.
b) Ensure that masons keep grout cells clean of mortar droppings and inspect to determine compliance.
8) Continuously observe placing of grout.
9) Perform or supervise performance of required sampling and testing.
2. Keep complete record of inspections. Report daily to the Contractor's Quality Control Representative the progress of the masonry inspection.
B. Mock-up:
1. Prior to starting construction of masonry, construct minimum 4-foot square mock-up.
2. Use accepted materials, containing each different kind and color of brick masonry units to illustrate wall design.
3. When not accepted, construct another mock-up.
4. When accepted, mock-up will be standard of comparison for remainder of masonry work.
5. Upon completion of Project, dispose of mock-ups in legal manner at offsite location.
C. Pre-installation conference: Conduct as specified in Section 01312 - Project Meetings.
D. Masonry prism testing: Perform masonry prism testing in accordance with building code.
E. A letter of certification from the supplier of the materials used to verify in accordance with building code, shall be provided at the time of, or prior to, delivery of the materials to the jobsite.
1.05 DELIVERY, STORAGE, AND HANDLING
A. Transport and handle brick masonry units as required to prevent discoloration, chipping, and breakage.
B. Locate storage piles, stacks, and bins to protect materials from heavy traffic.
C. Remove chipped, cracked, and otherwise defective units from jobsite upon discovery.
Brick Masonry
04221-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/04221 (BidSetFinal)
1.06 PROJECT CONDITIONS
A. Cold weather requirements:
1. In accordance with the building code as specified in Section 01410 - Regulatory Requirements.
2. Provide adequate equipment for heating masonry materials when air temperature is below 40 degrees Fahrenheit.
B. Hot weather requirements:
1. When ambient air temperature exceeds 100 degrees Fahrenheit, or when ambient air temperature exceeds 90 degrees Fahrenheit and wind velocity is greater than 8 miles per hour, implement hot weather protection procedures.
2. Wet mortarboard before loading and cover mortar to retard drying when not being used.
3. Do not spread mortar beds more than 48 inches ahead of placing masonry units.
4. Place masonry units within 1 minute of spreading mortar.
1.07 SEQUENCING AND SCHEDULING
A. Order brick masonry units (8 weeks minimum) well before start of installation to ensure adequate time for manufacturing.
PART 2 PRODUCTS
2.01 HOLLOW LOAD BEARING BRICK MASONRY UNITS
A. Manufacturers: One of the following or equal:
1. Interstate Brick Co.
2. General Shale Brick Co.
B. Type: ASTM C652, Grade SW, Type HBS with minimum compressive strength of 2,500 pounds per square inch.
C. Surface texture: To be selected by Engineer from manufacturer’s full range of available textures.
D. Colors:
1. Soldier coursing: “Copperstone,” soldier coursing over windows and doors to be contrasting color as selected by Engineer from standard colors.
E. Size: 8 inches wide, by 4 inches high, by 12 inches long, unless otherwise indicated on the Drawings.
F. Coursing: 4 inches wide, by 8 inches high, by 8 inches deep.
G. Special sizes and shapes: As required for window and door soldier coursing and custom sills where indicated; bond beams, piers, lintels, control joints, and other special applications to minimize cutting.
Brick Masonry
04221-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/04221 (BidSetFinal) PART 3 EXECUTION
3.01 PREPARATION
A. Protect adjacent construction with appropriate means from mortar droppings and other effects of laying of brick masonry units.
B. Thoroughly clean foundations of laitance, grease, oil, mud, dirt, mortar droppings, and other objectionable matter.
3.02 BRICK MASONRY UNITS
A. Provide custom level of quality in accordance with ASTM C62 and C 216.
B. Lay masonry units damp. (Wet bricks with fine spray about 4 hours prior to their use).
C. Lay units in uniform and true courses, level, plumb, and without projections or offset of adjacent units.
D. Lay units to preserve unobstructed vertical continuity of cells to be filled with grout or insulation.
E. Align vertical cells to be filled with grout to maintain clear, unobstructed continuous vertical cell measuring not less than 2 by 3 inches.
F. Place mortar with full coverage of joints at webs of all cells and face shells.
G. Butter vertical head joints for thickness equal to face shell thickness of units, and shove joints tightly together so that mortar bonds to both masonry units.
H. Solidly fill joints from face of units to inside face of cells.
I. Lay units to desired height with joints of uniform thickness.
J. Bond shall be plumb throughout.
K. Lay units to avoid formation of cracks when units are placed. Keep cells of units as free of mortar as possible as masonry wall height increases.
L. Lay masonry plumb, true to line, with courses level. Keep bond pattern plumb throughout. Lay masonry within the following tolerances:
1. Maximum variation from the plumb in the lines and surfaces of columns, walls, and in the flutes and surfaces of fluted or split faced blocks:
a. In adjacent masonry units: 1/8 inch.
b. In 10 feet: 1/4 inch.
c. In any story or 20 feet maximum: 3/8 inch.
d. In 40 feet or more: 1/2 inch.
2. Maximum variations from the plumb for external corners, expansion joints, and other conspicuous lines:
a. In any story or 20 feet maximum: 1/4 inch.
b. In 40 Feet or More: 1/2 inch.
Brick Masonry
04221-5 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/04221 (BidSetFinal)
3. Maximum variations form the level or grades indicated on the Drawings for exposed lintels, sills, parapets, horizontal grooves, and other conspicuous lines:
a. In any bay or 20 feet maximum: 1/4 inch.
b. In 40 feet or more: 1/2 inch.
4. Maximum variations of the linear building lines from established position in plan and related portion of columns, walls, and partitions:
a. In any bay or 20 feet maximum: 1/2 inch.
b. In 40 feet or more: 3/4 inch.
5. Maximum variation in cross sectional dimensions of columns and in thickness of walls:
a. Minus: 1/4 inch.
b. Plus: 1/2 inch.
6. When positions of units shift after mortar has stiffened, bond is broken, or cracks are formed, relay units in new mortar.
M. Remove mortar, mortar droppings, debris, and other obstructions and materials from inside of cell walls.
N. Seal cleanouts after inspection and before grouting or placing insulation.
3.03 LOOSE FILL INSULATION
A. Fill all brick masonry unit cells solidly with grout.
B. Place in lifts of 4 feet maximum when filling brick masonry unit cells.
C. Do not lay units more than 4 feet vertically ahead of units filled with loose insulation.
D. Ensure that no insulation gets into cells which are to be filled with grout.
3.04 MORTAR JOINTS
A. Make joints straight, clean, smooth, and uniform in thickness.
B. Pointing: Tool exposed joints, slightly concave. Strike concealed joints flush.
C. Joint thickness: Make vertical and horizontal joints 3/8-inch thick.
D. Where fresh masonry joins totally or partially set masonry, clean and roughen set masonry before laying new units.
3.05 BOND PATTERN
A. Lay brick masonry units in running bond pattern, unless otherwise indicated on the Drawings.
3.06 GROUTING AND REINFORCEMENT
A. Where horizontal and vertical bars are spliced and adjacent lap splices are separated by more than 3 inches, the lap splice length shall be 72 bar diameters.
Brick Masonry
04221-6 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/04221 (BidSetFinal) B. Where adjacent lap splices are separated by 3 inches or less, the lap splice length shall be increased by 1.3 times or the lap splices shall be staggered at least 24 bar diameters with no increase in length.
C. Hold vertical reinforcing bars in position at top and bottom and at intervals not exceeding 200 bar diameters. Use steel wire bar positioners to position bars and tie reinforcing bars to dowels with wire ties.
D. Obtain acceptance of reinforcement placement before grouting.
E. Fill all spaces and cells solidly with grout.
F. Low-lift grouting:
1. Hollow unit masonry to be grouted by the low lift method shall be constructed and grouted in lifts not exceeding 4 feet.
a. Double wythe masonry which will be grouted by the low-lift method shall be constructed and grouted in lifts not exceeding 8 inches. b. Slushing with mortar will not be permitted.
G. High-lift grouting:
1. If grouting is accomplished by the high-lift method, double wythe masonry shall be allowed to cure at least 72 hours and hollow unit masonry shall be allowed to cure at least 24 hours before grouting.
2. In double wythe construction, vertical grout barriers shall be built across the grout space to the height of the grout lift.
3. Grout barriers shall not be spaced more than 30 feet apart. a. Grout shall be placed in lifts not to exceed 5 feet in depth.
4. Each lift shall be allowed to set for 10 minutes after initial consolidation of grout before successive lift is placed.
5. The full height of each section of wall shall be grouted in 1 day.
H. Grout in cells shall have full contact with surface of concrete footings.
I. When grouting stops for 1 hour or longer, form horizontal construction joints by stopping grout placement 1-1/2 inches below top of uppermost unit containing grout.
J. After placement, consolidate grout using mechanical immersion vibrators designed for consolidating grout.
K. Placement:
1. Use a hand bucket, concrete hopper, or grout pump.
2. Place grout in final position within 1-1/2 hours after mixing.
3. Place grout so as to completely fill the grout spaces without segregation of the aggregates.
4. Do not insert vibrators into lower grout placements that are in a semi-solidified state.
Brick Masonry
04221-7 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/04221 (BidSetFinal)
3.07 BOND BEAMS
A. Place horizontal reinforcement and solidly grout bond beam units in place.
B. Provide wire mesh at openings in bottom of bond beams to support grout where walls are not grouted solid.
3.08 CUTTING BRICK MASONRY UNITS
A. When possible, use full units of the proper size in-lieu of cut units. Cut units as required to form chases, openings, for anchorage, and for other appurtenances.
B. Cut and fit units with power-driven carborundum or diamond disc blade saw.
3.09 CONTROL JOINTS
A. Provide in masonry walls where indicated on the Drawings.
B. Make full height and continuous in appearance.
C. Run bond beams and bond beam-reinforcing bars continuously through control joints.
D. Insert control joint filler in joints as wall is constructed.
E. Apply sealant as specified in Section 07900 - Joint Sealants.
3.10 OPENINGS AND LINTELS
A. Place horizontal reinforcement in fully grouted bond beam units.
B. Use lintel block units where underside of lintel will be exposed.
C. Provide minimum of 8-inch bearing at each end of lintel.
D. Embed reinforcing bars minimum 24 inches or 40 bar diameters, whichever is longer, into wall past edges of openings or as indicated on the Drawings:
1. At corners, provide 90-degree bend with equivalent total embedment.
3.11 STEEL DOOR FRAMES
A. Anchor and fully grout jambs and head of steel doorframes connected to brick unit masonry.
B. Fill frames with grout as each 2 feet of brick unit masonry is laid.
3.12 BEARING PLATES
A. Provide minimum of 12 inches of grouted brick unit masonry below steel bearing plates and beams bearing on masonry walls.
Brick Masonry
04221-8 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/04221 (BidSetFinal)
3.13 ANCHOR BOLTS
A. Hold anchor bolts in place with template during grouting to ensure precise alignment.
B. Do not cut or ream members being anchored or use other means to accommodate misaligned anchor bolts in roof deck support angles.
C. Provide minimum 6-inch wide grouted brick unit masonry entirely around anchor bolts and other attachment devices.
3.14 ENCLOSURES
A. Where brick masonry units enclose conduit, pipes, stacks, ducts, and similar items, construct chases, cavities, and similar spaces as required, whether or not such spaces are indicated on the Drawings.
B. Point openings around flush mounted electrical outlet boxes with mortar, including flush joints above boxes.
C. Do not cover enclosures until inspected and when appropriate, tested.
3.15 OTHER EMBEDDED ITEMS
A. Build in wall plugs, accessories, flashings, pipe sleeves, and other items required to be built-in as the masonry work progresses.
3.16 PATCHING
A. Patch exposed brick masonry units at completion of the Work and in such manner that patching will be indistinguishable from similar surroundings and adjoining construction.
3.17 WATER CURING
A. Protect brick masonry units from drying too rapidly by frequently fogging or sprinkling for minimum 3 days.
3.18 MISCELLANEOUS
A. Build in required items such as anchors, flashings, sleeves, frames, structural steel, lintels, anchor bolts, and metal fabrications as required for complete installation.
3.19 WATER REPELLENT
A. Apply water repellent as specified in Section 07190 - Water Repellents.
3.20 FIELD QUALITY CONTROL
A. Have minimum 3 masonry units of each type proposed for Project tested in accordance with ASTM C67 to verify conformance to specifications.
Brick Masonry
04221-9 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/04221 (BidSetFinal) B. Tests shall include compressive strength, linear shrinkage, total absorption, moisture content as percent of total absorption, and unit weight.
C. Employ and pay acceptable independent testing laboratory to perform testing.
3.21 CLEANING
A. Exercise extreme care to prevent mortar splotches.
B. Do not attach construction supports to masonry walls.
C. Wash off brick scum and grout spills before scum and grout set.
D. Remove grout stains from walls.
E. Clean exposed masonry. Remove scaffolding and equipment. Dispose of debris, refuse, and surplus material offsite legally.
F. Correct efflorescence on exposed surfaces with commercially-prepared cleaning solution acceptable to masonry unit manufacturer:
1. Apply cleaning solution in accordance with cleaning solution manufacturer's printed instructions.
2. Do not use muriatic acid as cleaning solution.
3. Do not use sandblast cleaning equipment.
3.22 FORMS AND SHORES
A. Where required, construct forms to the shapes indicated on the Drawings:
1. Construct forms sufficiently rigid to prevent deflection which may result in cracking or other damage to supported masonry and sufficiently tight to prevent leakage of mortar and grout.
2. Do not remove supporting forms or shores until the supported masonry has acquired sufficient strength to support safely its weight and any construction loads to which it may be subjected:
a. Wait at least 16 hours after grouting masonry columns or walls before applying uniform loads.
b. Wait at least 64 hours before applying concentrated loads.
3.23 PROTECTION
A. Provide temporary protection for exposed masonry corners subject to damage.
B. Bracing:
1. Adequately brace masonry walls over 8 feet in height to prevent overturning and to prevent collapse unless wall is adequately supported by permanent supporting elements so wall will not overturn or collapse.
2. Keep bracing in place until permanent supporting elements of structure are in place.
Brick Masonry
04221-10 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/04221 (BidSetFinal) C. Limited access zone:
1. Establish limited access zone prior to start of masonry wall construction.
2. Zone shall be immediately adjacent to wall and equal to height of wall to be constructed plus 4 feet by entire length of wall on unscaffolded side of wall.
3. Limit access to zone to workers actively engaged in constructing wall. Do not permit other persons to enter zone.
4. Keep zone in place until wall is adequately supported or braced by permanent supporting elements to prevent overturning and collapse.
3.24 GROUTING EQUIPMENT
A. Grout pumps:
1. Do not pump grout through aluminum tubes.
2. Operate pumps to produce a continuous stream of grout without air pockets.
3. Upon completion of each day's pumping, eject grout from pipeline without contamination or segregation of the grout:
a. Remove waste materials and debris from the equipment. b. Dispose of waste materials, debris, and all flushing water outside the masonry.
B. Vibrators:
1. Internal vibrators shall maintain a speed of not less than 5,000 impulses per minute when submerged in the grout.
2. Maintain at least 1 spare vibrator, at the site at all times.
3. Apply vibrators at uniformly spaced points no further apart than the visible effectiveness of the machine.
4. Limit duration of vibration to time necessary to produce satisfactory consolidation without causing segregation.
3.25 EFFLORESCENCE TESTS
A. Perform efflorescence tests on mortar which will be exposed to weathering. Tests shall be scheduled far enough in advance of starting masonry work to permit retesting if necessary.
END OF SECTION
Structural Steel Framing
05120-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05120 (BidSetFinal) SECTION 05120
STRUCTURAL STEEL FRAMING
PART 1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Structural steel shapes and plate.
2. Fasteners and structural hardware:
a. All thread rods.
b. High-strength bolts.
3. Welding.
4. Bolting.
1.02 REFERENCES
A. American Institute of Steel Construction (AISC):
1. 303 - Code of Standard Practice for Steel Buildings and Bridges.
2. 360 - Specification for Structural Steel Buildings.
B. American Iron and Steel Institute (AISI):
1. Steel and stainless steel alloys (“types”) as indicated.
C. American Welding Society (AWS):
1. A5.1 - Specification for Carbon Steel Electrodes for Shielded Metal Arc Welding.
2. A5.17 - Specification for Carbon Steel Electrodes and Fluxes for Submerged Arc Welding.
3. A5.20 - Specification for Carbon Steel Electrodes for Flux Cored Arc Welding.
4. D1.1 - Structural Welding Code - Steel.
5. D1.6 - Structural Welding Code - Stainless Steel.
D. ASTM International (ASTM):
1. A6 - Standard Specification for General Requirements for Rolled Structural Steel Bars, Plates, Shapes, and Sheet Piling.
2. A36 - Standard Specification for Carbon Structural Steel.
3. A123 - Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products.
4. A153 - Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware.
5. A194 - Standard Specification for Carbon and Alloy Steel Nuts for Bolts for High Pressure or High Temperature Service, or Both.
6. A240 - Standard Specification for Chromium and Chromium-Nickel Stainless Steel Plate, Sheet, and Strip for Pressure Vessels and for General Applications.
7. A276 - Standard Specification for Stainless Steel Bars and Shapes.
Structural Steel Framing
05120-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05120 (BidSetFinal)
8. A380 - Standard Practice for Cleaning, Descaling, and Passivation of Stainless Steel Parts, Equipment, and Systems.
9. A489 - Standard Specification for Carbon Steel Lifting Eyes.
10. A500 - Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes.
11. A501 - Standard Specification for Hot-Formed Welded and Seamless Carbon Steel Structural Tubing.
12. A563 - Standard Specification for Carbon and Alloy Steel Nuts.
13. A992 - Standard Specification for Structural Steel Shapes.
14. F436 - Standard Specification for Hardened Steel Washers.
15. F593 - Standard Specification for Stainless Steel Bolts, Hex Cap Screws, and Studs.
16. F594 - Standard Specification for Stainless Steel Nuts.
17. F959 - Standard Specification for Compressible-Washer-Type Direct Tension Indicators for Use with Structural Fasteners.
18. F1554 - Standard Specification for Anchor Bolts, Steel, 36, 55, and 105 ksi Yield Strength.
19. F2329 - Standard Specification for Zinc Coating, Hot-Dip, Requirements for Application to Carbon and Alloy Steel Bolts, Screws, Washers, Nuts, and Special Threaded Fasteners.
20. F3125 - Standard Specification for High Strength Structural Bolts, Steel and Alloy Steel, Heat Treated, 120 ksi and 150 ksi Minimum Tensile Strength.
E. Research Council on Structural Connections (RCSC):
1. Specification for Structural Joints Using High-Strength Bolts (RCSC Specification).
1.03 DEFINITIONS
A. Snug-tight: At bolted joints, the tightness attained with a few impacts of an impact wrench, or by the full effort of an ironworker using a spud wrench to bring the connected plies into firm contact.
B. Stainless steel related terms:
1. Descaling: Removal of heavy, tightly adherent oxide films resulting from hot-forming, heat-treatment, welding, and other high-temperature operations.
2. Pickling: Chemical descaling of stainless steel using aqueous solutions of nitric and hydrofluoric acid, or various proprietary formulations as specified.
3. Passivation: Chemical treatment of stainless steel with a mild oxidant for the purpose of enhancing the spontaneous formation of the steel’s protective passive film.
1.04 SUBMITTALS
A. Product data:
1. Stainless steel: Fabricator name and qualifications, member dimensions and structural section properties, and specifications and procedures used for pickling and passivating members.
B. Shop drawings:
1. Fabrication and erection drawings.
Structural Steel Framing
05120-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05120 (BidSetFinal) C. Quality control submittals:
1. Welding procedure specifications (WPS) in accordance with AWS D1.1 and D1.6:
a. Submit WPS for each type of welded joint used, whether prequalified or qualified by testing:
1) State electrode manufacturer and specific electrodes used. 2) Indicate required AWS qualification for joint.
b. Submit WPS with shop drawings that indicate those welds. c. Submit Procedure Qualification Record (PQR) in accordance with AWS D1.1 and D1.6 for welding procedures qualified by testing.
2. Welder qualifications: For each welding process and position:
a. Welder's qualification certificates.
b. Contractor's statement that certificate will be "in effect" at the time(s) welding will be performed based on the "Period of Effectiveness" provisions of AWS D1.1 and D1.6.
3. Steel fabricator's AISC certification.
D. Test reports:
1. Certified copies of mill tests and analyses made in accordance with applicable ASTM standards, or reports from a recognized commercial laboratory, including chemical and tensile properties of each shipment of structural steel or part thereof having common properties.
1.05 QUALITY ASSURANCE
A. Certification:
1. Steel fabricators shall be certified by the AISC or other certification acceptable to the Engineer and the building official having jurisdiction.
B. Welding:
1. Perform welding of structural metals in accordance with AWS D1.1 and D1.6 using welders who have current AWS qualification certificate for the process, position, and joint configuration to be welded.
2. Make Welding Procedure Specifications available at the locations where welding is performed.
3. Notify Engineer at least 24 hours before starting shop or field welding.
4. Engineer may check materials, equipment, and qualifications of welders.
5. Remove welders performing unsatisfactory Work, or require requalification.
6. Engineer may use gamma ray, magnetic particle, dye penetrant, trepanning, or other aids to visual inspection to examine any part of welds or all welds.
7. Contractor shall bear costs of retests on defective welds.
8. Contractor shall also bear costs in connection with qualifying welders.
1.06 DELIVERY, STORAGE, AND HANDLING
A. Packing and shipping: Deliver structural steel free from mill scale, rust, and pitting.
B. Storage and protection: Until erection and painting, protect from weather items not galvanized or protected by a shop coat of paint.
Structural Steel Framing
05120-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05120 (BidSetFinal) PART 2 PRODUCTS
2.01 MATERIALS
A. Unless otherwise specified or indicated on the Drawings, materials shall conform to the following:
Item ASTM Standard
Class, Grade, Type,
or Alloy Number
Carbon Steel
Plate, bars, rolled shapes (except W and WT
shapes), and miscellaneous items
A36 --
Rolled W and WT shapes A992 Grade 50
Hollow structural sections/HSS: Round,
square, or rectangular
(including “pipe” where indicated for structural
members and supports)
A500 Grade C
Stainless Steel
Plate, sheet, and strip A240 Type 304* or 316**
Bars and shapes A276 Type 304* or 316**
* Use Type 304L (low-carbon stainless steel) if material will be welded. ** Use Type 316L (low carbon stainless steel) if material will be welded.
2.02 FASTENERS AND STRUCTURAL HARDWARE
A. General:
1. Materials: Of domestic manufacture.
2. Where fasteners and hardware are specified to be galvanized, hot-dip galvanize in accordance with ASTM A153 or ASTM F2329, unless otherwise specified.
B. All thread rods:
1. Carbon steel:
a. In accordance with ASTM A36 unless otherwise indicated on the Drawings.
b. Nuts: ASTM A194.
c. Washers: ASTM F436.
2. Galvanized carbon steel:
a. In accordance with ASTM A36 unless otherwise indicated on the Drawings, and hot dip galvanized in accordance with ASTM A153. b. Nuts: ASTM A194, hot-dip galvanized in accordance with ASTM A153. c. Washers: ASTM F436, hot-dip galvanized in accordance with ASTM A153.
3. Stainless steel:
a. Units descaled, pickled, and passivated as specified in “Fabrication” in this Section.
Structural Steel Framing
05120-5 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05120 (BidSetFinal) b. Threaded rods and nuts to be the products of a single manufacturer/fabricator to ensure proper fit without galling. Ship all thread rods with properly fitting nuts attached.
c. Alloy Type 304 or Type 316 as indicated on the Drawings. d. Type 304:
1) Rod: ASTM F593, Group 1, Condition CW, coarse threads. 2) Nuts: ASTM F594. Match alloy of rod (group and UNS designation). 3) Washers: Type 304 stainless steel.
e. Type 316:
1) Rod: ASTM F593, Group 2, Condition CW, coarse threads. 2) Nuts: ASTM F594. Match alloy of rod (group and UNS designation). 3) Washers: Type 316 stainless steel.
C. Anchor bolts, anchor rods, and post-installed steel anchors: As indicated on the Drawings and as specified in Section 05190 - Mechanical Anchoring and Fastening to Concrete and Masonry.
D. Forged steel structural hardware - carbon steel:
1. Clevises and turnbuckles: Forged steel in accordance with AISI C-1035.
2. Eye nuts / Eye bolts: Forged steel in accordance with AISI C-1030. a. Having geometric and strength characteristics (including proof load, breaking strength, tensile strength, bend test, and impact strength) of eyebolts in accordance with ASTM A489, Type 1.
E. High-strength bolts:
1. Provide high-strength bolt assembly, with nuts, hardened flat washers, and compressible-washer-type direct tension indicators. Provide uncoated components unless galvanized coating is indicated on the Drawings.
2. Carbon steel - Uncoated:
a. Bolts: Plain heavy hex structural bolts in accordance with ASTM F3125, Grade A325, Type 1.
b. Nuts: Heavy hex nuts in accordance with ASTM A563, Grade C. c. Washers:
1) Adjacent to normal, oversized, and short-slotted holes: Circular, square, or rectangular beveled, clipped, or extra thick washers in accordance with ASTM F436, Type 1. Flat circular washers unless otherwise indicated on the Drawings.
2) Adjacent to long slotted holes: Fabricated from 5/16-inch-thick plate conforming to ASTM A36.
3. Carbon steel - Galvanized:
a. Bolt and nut assemblies fabricated, galvanized, tested for rotational capacity, and shipped accordance with the provisions ASTM F3125, Grade A325and the RCSC Specification.
b. Bolts, nuts, and washers: Hot-dip galvanized in accordance with ASTM F2329.
c. Bolts: Plain heavy hex structural bolts in accordance with ASTM F3125, Grade A325, Type 1 and galvanized as specified.
d. Nuts: Heavy hex nuts in accordance with ASTM A563, Grade DH, galvanized as specified, and lubricated in accordance with ASTM A563, Supplementary Requirement S1 to minimize galling.
Structural Steel Framing
05120-6 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05120 (BidSetFinal) e. Washers:
1) Adjacent to normal, oversized, and short-slotted holes: Circular, square, or rectangular beveled, clipped, or extra thick washers in accordance with ASTM F436, Type 1 and galvanized as specified.
Flat circular washers unless otherwise indicated on the Drawings. 2) Adjacent to long slotted holes: 5/16-inch thick plate washer fabricated from steel conforming to ASTM A36, and galvanized in accordance with ASTM A123.
f. Load indicator devices: At slip critical connections, provide one of the following devices at each bolt:
1) Compressible washer type direct tension indicators (“DTI”): In accordance with ASTM F959, Type 325-1, with mechanically deposited zinc coating conforming to ASTM B695, Class 55. 2) Twist-off type tension-control bolt assemblies: ASTM F3125, Grade F1852 with mechanically deposited zinc coating conforming to ASTM B695, Class 55.
F. Stainless steel bolts (for use in stainless steel structures):
1. General:
a. Bolts and nuts shall be the products of a single manufacturer/fabricator to ensure proper fit without galling. Ship bolts with properly fitting nuts attached.
b. Units descaled, pickled, and passivated as specified in “Fabrication."
2. Alloy: Type 304 or Type 316 to match alloy of structural members being connected.
3. Type 304:
a. Bolts: ASTM F593, Group 1, Condition CW, coarse threads. b. Nuts: ASTM F594. Match alloy (group and UNS designation) and threads of bolts.
c. Washers: Type 304 stainless steel.
4. Type 316:
a. Bolts: ASTM F593, Group 2, Condition CW, coarse threads. b. Nuts: ASTM F594. Match alloy (group and UNS designation) and threads of bolts.
c. Washers: Type 316 stainless steel.
5. Welded studs: As indicated on the Drawings and as specified in Section 05190 - Mechanical Anchoring and Fastening to Concrete and Masonry.
2.03 ISOLATING SLEEVES AND WASHERS
A. As indicated on the Drawings and as specified in Section 05190 - Mechanical Anchoring and Fastening to Concrete and Masonry.
2.04 GALVANIZED SURFACE REPAIR
A. Manufacturers: The following or equal:
1. Jelt, Galvinox.
Structural Steel Framing
05120-7 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05120 (BidSetFinal)
2.05 THREAD COATING
A. Manufacturers: One of the following or equal:
1. Bostik, Never-Seez.
2. Oil Research, Inc., WLR No. 111.
2.06 SUPPLEMENTARY PARTS
A. Furnish as required for complete structural steel erection, whether or not such parts and Work are specified or indicated on the Drawings.
2.07 FABRICATION
A. Shop assembly:
1. Fabricate structural steel in accordance with AISC 360 and AISC 303 unless otherwise specified or modified by applicable regulatory requirements.
2. Where anchors, connections, or other details of structural steel are not specifically indicated on the Drawings or specified, their material, size and form shall be equivalent in quality and workmanship to items specified.
3. Round off sharp and hazardous projections and grind smooth.
4. Take measurements necessary to properly fit work in the field. Take responsibility for and be governed by the measurements and proper working out of all the details.
5. Take responsibility for correct fitting of metalwork.
6. Welded connections:
a. Comply with AWS requirements for the metals to be welded. b. Weld only in accordance with approved Welding Procedure Specifications.
c. Keep Welding Procedure Specifications readily available for welders and inspectors during fabrication processes.
B. Stainless steel shapes and assemblies:
1. For structural members such as W shapes, S shapes, channels, angles, and similar rolled shapes not available in quantity, size, and type of stainless steel specified or indicated on the Drawings:
a. Fabricate shapes using laser-fused, full penetration welds between pieces of plate to attain same or higher section modulus and moment of inertia as that of members indicated on the Drawings.
b. Fabricate shapes from dual grade stainless steel.
c. Fabricate beams and channels to ASTM A6 tolerances.
d. Manufacturers: The following or equal:
1) Stainless Structural, LLC.
2. Cleaning and passivation:
a. Following shop fabrication of stainless steel members and bolts, clean and passivate fabrications at point of manufacture.
b. Finish requirements: Remove free iron, heat tint oxides, weld scale and other impurities, and obtain a bright passive finished surface with no etching, pitting, frosting, or discoloration.
Structural Steel Framing
05120-8 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05120 (BidSetFinal) c. Provide quality control testing to verify effectiveness of cleaning agents and procedures and to confirm that finished surfaces are clean and passivated.
1) Conduct sample runs using test specimens with proposed cleaning agents and procedures as required to avoid adverse effects on surface finishes and base materials.
d. Pre-clean, chemically de-scale (“pickle”), passivate, and final-clean fabrications in accordance with the requirements of ASTM A380. 1) If degreasing is required before cleaning (pickling) to remove scale or iron oxide, cleaning with citric acid treatments is permissible; however, such treatments shall be followed inorganic cleaners. 2) Pickle and passivate stainless steel using a nitric acid solution in accordance with ASTM A380, Annex A2, Table A2.1, Part II. 3) Pickling by citric acid treatment or sulfuric acid treatment is not considered to satisfy the requirements of this Section. e. Inspect after cleaning using methods specified for “gross inspection” in ASTM A380.
f. Improperly or poorly cleaned and passivated materials shall not be shipped and will not be accepted at the site.
C. Galvanized carbon steel:
1. Where galvanizing is required, hot-dip structural steel after fabrication in accordance with ASTM A123:
2. Do not electro-galvanize or mechanically-galvanize unless specified or accepted by Engineer.
3. Re-straighten galvanized items that bend or twist during galvanizing.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verification of conditions: Examine Work in place to verify that it is satisfactory to receive the Work of this Section. If unsatisfactory conditions exist, do not begin this Work until such conditions have been corrected.
3.02 ERECTION
A. General:
1. Fabricate structural and foundry items to true dimensions without warp or twist.
2. Form welded closures neatly, and grind off smooth where weld material interferes with fit or is unsightly.
3. Install structural items accurately and securely, true to level, plumb, in correct alignment and grade, with all parts bearing or fitting structure or equipment for which intended.
4. Do not shift out of alignment, re-drill, re-shape, or force fit fabricated items.
5. Place anchor bolts or other anchoring devices accurately and make surfaces that bear against structural items smooth and level.
6. Rigidly support and brace structural items needing special alignment to preserve straight, level, even, and smooth lines. Keep structural items braced until concrete, grout, or dry pack mortar has hardened for 48 hours minimum.
Structural Steel Framing
05120-9 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05120 (BidSetFinal)
7. Erect structural steel in accordance with AISC 303 unless otherwise specified or modified by applicable regulatory requirements.
8. Where anchors, connections, and other details of structural steel erection are not specifically indicated on the Drawings or specified, form, locate, and attach with equivalent in quality and workmanship to items specified.
9. Round off sharp or hazardous projections and grind smooth.
10. Paint or coat steel items as specified in Sections 09910 - Painting and 09960 - High-Performance Coatings.
B. Stainless steel: Take all necessary precautions to avoid iron contamination of stainless steel during delivery, storage, and handling.
1. Segregate stainless steel from iron.
2. Tools and handling devices:
a. Do not use iron tools clamps, chokes, working surfaces, or brushes when fabricating, handling, and erecting stainless steel.
b. Do not use tools that have been contaminated by contact with iron. c. Use stainless steel, polymer coated, or wood tools and handling equipment. Do not use tools that have been contaminated by contact with iron or steel.
C. Welding: General:
1. Make welds full penetration type, unless otherwise indicated on the Drawings.
2. Remove backing bars and weld tabs after completion of weld. Repair defective welds observed after removal of backing bars and weld tabs.
D. Welding: Carbon steel:
1. General: In accordance with AWS D1.1:
a. Weld ASTM A36 and A992 structural steel, and ASTM A500 and A501 structural tubing with electrodes in accordance with AWS A5.1, using E70XX electrodes; AWS A5.17, using F7X-EXXX electrodes; or AWS A5.20, using E7XT-X electrodes:
b. Field repair cut or otherwise damaged galvanized surfaces to equivalent original condition using a galvanized surface repair.
E. Welding - stainless steel:
1. General: In accordance with AWS D1.6.
2. Field welding of stainless steel will not be permitted.
3. Passivation of field-welded surfaces:
a. Provide cleaning, pickling, and passivating as specified under “Fabrications” of this Section. Clean using Derustit Stainless Steel Cleaner, or equal.
F. Interface with other products:
1. Where steel members and fasteners come in contact with dissimilar metals (aluminum, stainless steel, etc.), separate or isolate the dissimilar metals with isolating sleeves and washers as specified in Section 05190 - Mechanical Anchoring and Fastening to Concrete and Masonry.
Structural Steel Framing
05120-10 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05120 (BidSetFinal) G. Fasteners: General:
1. Install bolts to project 2 threads minimum, but 1/2 inch maximum beyond nut.
2. Anchor bolts and anchor rods: Install as specified in Section 05190 - Mechanical Anchoring and Fastening to Concrete and Masonry. a. Unless otherwise specified, tighten nuts on anchor bolts and anchor rods specified in Section 05190 - Mechanical Anchoring and Fastening to Concrete and Masonry to the "snug-tight" condition.
H. Fasteners: High-strength carbon steel bolts:
1. Connections with high-strength bolts shall in accordance with RCSC Specification for Structural Joints Using High-Strength Bolts.
2. Provide pre-tensioned joints at bolted connections, except where slip-critical or snug-tight connections are indicated on the Drawings.
3. Joints: Snug-tight:
a. Install bolts with washers where required in accordance with RCSC Specification.
b. Tighten bolts to bring the connected plies into firm contact. Tightening shall progress systematically beginning with the most rigid part of the joint.
More than 1 cycle through the bolt pattern may be required to achieve this condition.
c. Verify adequate tightening of bolts by visual observation to confirm that washers have been installed at locations required in accordance with RCSC Specification, and that the plies of the connected parts have been brought into firm contact.
I. Fasteners: High-strength carbon steel bolts:
1. Connections with high-strength bolts shall in accordance with RCSC Specification for Structural Joints Using High-Strength Bolts.
2. Provide pre-tensioned joints at bolted connections, except where slip-critical or snug-tight connections are indicated on the Drawings.
3. Joints: Slip-critical.
a. Confirm that faying surfaces at connections are free of dirt and other foreign material, have been blast cleaned, and are free of coatings and inadvertent overspray in accordance with RCSC Specification. b. Furnish hardened flat washers in accordance with ASTM F436:
1) On outer plies with slotted holes.
2) When 1 or more plies of the connected material has a yield strength less than 40 ksi.
3) Under element, nut, or bolt head, turned in tightening. c. Install tension indicator washers, placed in accordance with ASTM F959 Figure X1, to confirm adequate tightening of bolts.
d. Tighten bolts to full pretension.
4. Joints: Pre-tensioned.
a. Joint preparation, assembly, and tightening shall be as specified for slip-critical connections, except that the requirements for un-coated faying surfaces shall not apply.
5. Joints: Snug-tight:
a. Install bolts with washers where required in accordance with RCSC Specification.
b. Tighten bolts to bring the connected plies into firm contact. Tightening shall progress systematically beginning with the most rigid part of the joint.
Structural Steel Framing
05120-11 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05120 (BidSetFinal) More than 1 cycle through the bolt pattern may be required to achieve this condition.
c. Verify adequate tightening of bolts by visual observation to confirm that washers have been installed at locations required in accordance with RCSC Specification, and that the plies of the connected parts have been brought into firm contact.
J. Fasteners: Stainless steel bolts:
1. Connections shall be snug-tight joints unless otherwise indicated on the Drawings.
2. Prior to installing nuts, coat threads of stainless steel fasteners with thread coating to prevent galling of threads.
3. Rotate nuts using a slow, smooth action without interruptions. Avoid over-tightening.
3.03 FIELD QUALITY CONTROL
A. Provide quality control as specified in Section 01450 - Quality Control.
3.04 FIELD QUALITY ASSURANCE
A. Provide quality assurance as specified in Section 01450 - Quality Control.
B. Special inspections, special tests, and structural observation:
1. Provide as specified in Section 01455 - Regulatory Quality Assurance.
END OF SECTION
Structural Aluminum
05140-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05140 (BidSetFinal) SECTION 05140
STRUCTURAL ALUMINUM
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Structural aluminum products, including sheet, pipe, extrusions, and associated accessories.
1.02 REFERENCES
A. ASTM International (ASTM):
1. B209 - Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate.
2. B221 - Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes.
3. B308 - Standard Specification for Aluminum-Alloy 6061-T6 Standard Structural Profiles.
B. American Welding Society (AWS):
1. A5.10 - Specification for Bare Aluminum and Aluminum-Alloy Welding Electrodes and Rods.
2. D1.2 - Structural Welding Code - Aluminum.
1.03 SUBMITTALS
A. Quality control submittals:
1. Test Reports: Certified copies of mill tests or reports from a recognized commercial laboratory including chemical and tensile properties of each shipment of structural metal or part thereof having common properties. Tests and analyses shall be made in accordance with applicable ASTM Standards.
2. Welder’s certificates.
1.04 QUALITY ASSURANCE
A. Qualifications:
1. Perform welding of structural metals with welders who have current AWS certificate for the type of welding to be performed.
2. Notify Engineer 24 hours minimum before starting shop or field welding.
3. Engineer may check materials, equipment, and qualifications of welders.
4. Remove welders performing unsatisfactory work, or require to requalify.
5. Engineer may use gamma ray, magnetic particle dye penetrant, or other aids to visual inspection to examine any part of welds or all welds.
6. Contractor shall bear costs of retests on defective welds.
7. Contractor shall bear costs in connection with qualifying welders.
Structural Aluminum
05140-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05140 (BidSetFinal) PART 2 PRODUCTS
2.01 MATERIALS
A. Structural sheet aluminum: ASTM B209, Alloy 6061-T6.
B. Structural aluminum: ASTM B308, Alloy 6061-T6.
C. Extruded aluminum: ASTM B221, Alloy 6063-T42.
D. Isolating sleeves and washers:
1. As indicated on the Drawings and as specified in Section 05190 - Mechanical Anchoring and Fastening to Concrete and Masonry.
E. Miscellaneous materials:
1. Furnish supplementary parts necessary to complete each item even where such work is neither definitely indicated on the Drawings nor specified.
2. Size, form, attachment, and location shall conform to the best of current practice.
3. Conform to applicable ASTM Standards for materials not otherwise specified.
2.02 FABRICATION
A. Aluminum layout:
1. Center punch hole centers, and punch or scribe cutoff lines, except where marks would remain on fabricated material.
2. Apply temperature correction where necessary in layout of critical dimensions.
Use a coefficient of expansion of 0.000013 per degree of Fahrenheit.
B. Cutting aluminum:
1. Material 1/2-inch thick or less: Shear, saw, or cut with a router.
2. Material more than 1/2-inch thick: Saw or rout.
3. Make cut edges true and smooth, free from excessive burrs or ragged breaks.
4. Avoid reentrant cuts wherever possible. Where used, fillet by drilling prior to cutting.
5. Do not flame cut aluminum alloys.
6. Punch or drill rivet or bolt holes to finished size before assembly:
a. Make finished diameter of holes for bolts 1/16-inch maximum larger than nominal bolt diameter.
b. Make holes cylindrical and perpendicular to principal surface. c. Do not permit holes to drift in a manner to distort metal.
C. Aluminum forming and assembly:
1. Do not heat structural aluminum, except as follows:
a. Heat aluminum to 400 degrees Fahrenheit for 30 minutes maximum, to facilitate bending or welding.
b. Heat only when proper temperature controls and supervision can ensure that limitations on temperature and time are observed.
Structural Aluminum
05140-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05140 (BidSetFinal) D. Before assembly, remove chips lodged between contacting surfaces.
E. Welding aluminum:
1. Perform welding of aluminum in accordance with AWS D1.2.
2. Weld aluminum in accordance with the following:
a. Preparation:
1) Remove dirt, grease, forming or machining lubricants, and organic materials from areas to be welded by cleaning with a suitable solvent or by vapor degreasing.
2) Additionally, etch or scratch brush to remove oxide coating just prior to welding when inert gas tungsten arc welding method is used. 3) Oxide coating may not need to be removed if welding is performed by automatic or semi-automatic inert gas shielded metal arc. 4) Suitably prepare edges to ensure 100 percent penetration in butt welds by sawing, chipping, machining, or shearing. Do not cut with oxygen.
b. Filler metal: Aluminum alloys conforming to the requirements of AWS A5.10 and AWS classification ER 4043, ER 5654, ER 5554, ER 5183, ER 5356, or ER 5556.
c. Perform welding of structures which are to be anodized using filler alloys which will not discolor when anodized, AWS ER 5654, ER 5554, ER 5183, ER 5356, or ER 5556.
d. Perform welding by using a non-consumable tungsten electrode with filler metal in an inert gas atmosphere (TIG) or using a consumable filler metal electrode in an inert gas atmosphere (MIG).
e. Do not use welding process that requires use of a welding flux. f. Neatly make welded closures.
g. Where weld material interferes with fit or is unsightly in appearance, grind it smooth.
h. Make welds full penetration welds unless otherwise indicated on the Drawings.
2.03 FINISHES
A. Coating for Aluminum in contact with concrete or masonry:
1. Epoxy mastic.
a. Manufacturers: One of the following or equal:
1) Carboline, Carbomastic 15.
2) International Paint, Bar-Rust 231.
3) Tnemec, Series 135.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verification of conditions: Examine Work in place to verify that it is satisfactory to receive the Work of this Section. If unsatisfactory conditions exist, do not begin this Work until such conditions have been corrected.
Structural Aluminum
05140-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05140 (BidSetFinal)
3.02 INSTALLATION
A. Install structural aluminum products as indicated on the Drawings and specified.
B. Install structural aluminum products accurately and securely, true to level, plumb, in correct alignment and grade, with all parts bearing or fitting structure or equipment for which intended.
C. Do not cock out of alignment, redrill, reshape, or force fit fabricated items.
D. Place anchor bolts or other anchoring devices accurately and make surfaces that bear against structural items smooth and true to level.
E. Rigidly support and brace structural products needing special alignment to preserve straight, level, even, smooth lines, and keep braced until concrete, grout, or dry pack mortar has hardened for a minimum 48-hour period.
F. Interface with other products:
1. Where aluminum comes in contact with dissimilar metals, use stainless steel bolts or anchors and separate or isolate the dissimilar metals with isolating sleeves and washers as specified in Section 05190 - Mechanical Anchoring and Fastening to Concrete and Masonry.
2. Coat those parts of aluminum that will be cast into concrete or that will be in contact with concrete, grout, masonry, wood, or other materials that will cause the aluminum to corrode, as specified in Section 09960 - High-Performance Coatings.
END OF SECTION
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal) SECTION 05190
MECHANICAL ANCHORING AND FASTENING TO CONCRETE AND MASONRY PART 1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Cast-in anchors and fasteners:
a. Anchor bolts.
b. Anchor rods.
c. Concrete inserts.
d. Welded studs.
2. Post-installed steel anchors and fasteners:
a. Concrete anchors.
1.02 REFERENCES
A. American Concrete Institute (ACI):
1. 355.2 - Qualification of Post-Installed Mechanical Anchors in Concrete and Commentary.
B. American National Standards Institute (ANSI):
1. B212.15 - Cutting Tools - Carbide-tipped Masonry Drills and Blanks for Carbide-tipped Masonry Drills.
C. American Welding Society (AWS):
1. D1.1 - Structural Welding Code - Steel.
2. D1.6 - Structural Welding Code - Stainless Steel.
D. ASTM International (ASTM):
1. A36 - Standard Specification for Carbon Structural Steel.
2. A53 - Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless.
3. A108 - Standard Specification for Steel Bars, Carbon and Alloy, Cold Finished.
4. A123 - Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products.
5. A153 - Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware.
6. A240 - Standard Specification for Chromium and Chromium Nickel Stainless Steel Plate, Sheet, and Strip for Pressure Vessels and for General Applications.
7. A380 - Standard Practice for Cleaning, Descaling, and Passivation of Stainless Steel Parts, Equipment, and Systems.
8. A563 - Standard Specification for Carbon and Alloy Steel Nuts.
9. B633 - Standard Specification for Electrodeposited Coatings of Zinc on Iron and Steel.
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal)
10. B695 - Standard Specification for Coatings of Zinc Mechanically Deposited on Iron and Steel.
11. E488 - Standard Test Methods for Strength of Anchors in Concrete Elements.
12. F436 - Standard Specification for Hardened Steel Washers.
13. F593 - Standard Specification for Stainless Steel Bolts, Hex Cap Screws and Studs.
14. F594 - Standard Specification for Stainless Steel Nuts.
15. F1554 - Standard Specification for Anchor Bolts, Steel, 36, 55 and 105-ksi Yield Strength.
16. F2329 - Standard Specification for Zinc Coating, Hot-Dip, Requirements for Application to Carbon and Alloy Steel Bolts, Screws, Washers, Nuts, and Special Threaded Fasteners.
E. International Code Council Evaluation Service, Inc. (ICC-ES):
1. AC193 - Acceptance Criteria for Mechanical Anchors in Concrete Elements.
1.03 DEFINITIONS
A. Built-In Anchor: Headed bolt or assembly installed in position before filling surrounding masonry units with grout.
B. Cast-In Anchor: Headed bolt or assembly installed in position before placing plastic concrete around.
C. Overhead Installations: Fasteners installed on overhead surfaces where the longitudinal axis of the fastener is more than 60 degrees above a horizontal line so that the fastener resists sustained tension loads.
D. Passivation: Chemical treatment of stainless steel with a mild oxidant for the purpose of enhancing the spontaneous formation of the steel’s protective passive film.
E. Post-Installed Anchor: Fastener or assembly installed in hardened concrete or finished masonry construction, typically by drilling into the structure and inserting a steel anchor assembly.
F. Terms relating to structures or building environments as used with reference to anchors and fasteners:
1. Corrosive locations: Describes interior and exterior locations as follows:
a. Locations used for delivery, storage, transfer, or containment (including spill containment) of chemicals used for plant treatment processes.
2. Wet and moist locations: Describes locations, other than “corrosive locations,” that are submerged, are immediately above liquid containment structures, or are subject to frequent wetting, splashing, or wash down. Includes:
a. Exterior portions of buildings and structures.
b. Liquid-containing structures:
1) Locations at and below the maximum operating liquid surface elevation.
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal) 2) Locations above the maximum operating liquid surface elevation and:
a) Below the top of the walls containing the liquid.
b) At the inside faces and underside surfaces of a structure enclosing or spanning over the liquid (including walls, roofs, slabs, beams, or walkways enclosing the open top of the structure).
c. Liquid handling equipment:
1) Bases of pumps and other equipment that handles liquids. d. Indoor locations exposed to moisture, splashing, or routine wash down during normal operations, including floors with slopes toward drains or gutters.
e. Other locations indicated on the Drawings.
3. Other locations:
a. Interior dry areas where the surfaces are not exposed to moisture or humidity in excess of typical local environmental conditions.
1.04 SUBMITTALS
A. General:
1. Submit as specified in Section 01330 - Submittal Procedures.
2. Submit information listed for each type of anchor or fastener to be used.
B. Action submittals:
1. Product data:
a. Cast-in anchors:
1) Manufacturer’s data including catalog cuts showing anchor sizes and configuration, materials, and finishes.
b. Post-installed anchors:
1) For each anchor type, manufacturer’s data including catalog cuts showing anchor sizes and construction, materials and finishes, and load ratings.
2. Samples:
a. Samples of each type of anchor, including representative diameters and lengths, if requested by the Engineer.
3. Certificates:
a. Cast-in anchors:
1) Mill certificates for steel anchors that will be supplied to the site. b. Post-installed anchors:
1) Manufacturer’s statement or certified test reports demonstrating that anchors that will be supplied to the site comply with the materials properties specified.
4. Test reports:
a. Post-installed anchors: For each anchor type used for the Work:
1) Current ICC-ES Report (ESR) demonstrating:
a) Acceptance of that anchor for use under the building code specified in Section 01410 - Regulatory Requirements.
b) That testing of the concrete anchor included the simulated seismic tension and shear tests of AC193, and that the anchor is accepted for use in Seismic Design Categories C, D, E, or F and with cracked concrete.
b. Concrete anchor pre-installation test report.
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal)
5. Manufacturer’s instructions:
a. Requirements for storage and handling.
b. Recommended installation procedures including details on drilling, hole size (diameter and depth), hole cleaning and preparation procedures, anchor insertion, and anchor tightening.
c. Requirements for inspection or observation during installation.
6. Qualification statements:
a. Post-installed anchors: Installer qualifications:
1) Submit list of personnel performing installations and include date of manufacturer’s training for each.
1.05 QUALITY ASSURANCE
A. Qualifications:
1. Post installed anchors shall be in accordance with building code specified in Section 01410 - Regulatory Requirements.
B. Special inspection:
1. Provide special inspection of post-installed anchors as specified in Section 01455 - Regulatory Quality Assurance and this Section.
1.06 DELIVERY, STORAGE, AND HANDLING
A. Deliver post-installed anchors in manufacturer’s standard packaging with labels visible and intact. Include manufacturer’s installation instructions.
B. Handle and store anchors and fasteners in accordance with manufacturer’s recommendations and as required to prevent damage.
C. Protect anchors from weather and moisture until installation.
1.07 PROJECT CONDITIONS
A. Seismic Design Category (SDC) for structures is indicated on the Drawings.
PART 2 PRODUCTS
2.01 MANUFACTURED UNITS
A. General:
1. Furnish threaded fasteners with flat washers and hex nuts fabricated from materials corresponding to the material used for threaded portion of the anchor.
a. Cast-in anchors: Provide flat washers and nuts as listed in the ASTM standard for the anchor materials specified.
b. Post-installed anchors: Provide flat washers and nuts supplied for that product by the manufacturer of each anchor.
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-5 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal)
2. Size of anchors and fasteners, including diameter and length or minimum effective embedment depth: As indicated on the Drawings or as specified in this Section. In the event of conflicts, contact Engineer for clarification.
3. Where anchors and connections are not specifically indicated on the Drawings or specified, their material, size and form shall be equivalent in quality and workmanship to items specified.
B. Materials:
1. Provide and install anchors of materials as in this Section.
2.02 CAST-IN ANCHORS AND FASTENERS
A. Anchor bolts:
1. Description:
a. Straight steel rod having one end with an integrally forged head, and one threaded end. Embedded into concrete with the headed end cast into concrete at the effective embedment depth indicated on the Drawings or specified, and with the threaded end left to project clear of concrete face as required for the connection to be made.
b. Furnish anchor bolts with heavy hex forged head or equivalent acceptable to Engineer.
1) Rods or bars with angle bend for embedment in concrete (i.e., “L” or “J” shaped anchor bolts) are not permitted in the Work.
2. Materials:
a. Ship anchor bolts with properly fitting nuts attached. b. Type 316 stainless steel:
1) Surfaces descaled, pickled, and passivated in accordance with ASTM A380.
2) Bolts: ASTM F593, Group 2, Condition CW, coarse threads. 3) Nuts: ASTM F594. Match alloy (group and UNS designation) and threads of bolts.
4) Washers: Type 316 stainless steel.
c. Galvanized steel:
1) Hot-dip galvanized coating in accordance with ASTM F2329. 2) Bolt: ASTM F1554, Grade 36, heavy hex, coarse thread. 3) Nuts: ASTM A563, Grade A, heavy hex, threads to match bolt. 4) Washers: ASTM F436, Type 1.
B. Anchor rods:
1. Description: Straight steel rod having threads on each end. One threaded end is fitted with nuts or plates and embedded in concrete to the effective depth indicated on the Drawings, leaving the opposite threaded end to project clear of the concrete face as required for the connection to be made at that location.
2. Materials:
a. Stainless steel: Type 316:
1) Surfaces descaled, pickled, and passivated in accordance with ASTM A380.
2) Rod: ASTM F593, Group 2, Condition CW, coarse threads. 3) Nuts: ASTM F594. Match alloy (group and UNS designation) and threads of rods.
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-6 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal) 4) Washers: Type 316 stainless steel.
5) Plates (embedded): ASTM A240.
b. Galvanized: steel:
1) Hot-dip galvanized with coating in accordance with ASTM F2329. 2) Rod: ASTM F1554, Grade 36, coarse thread.
3) Nuts: ASTM A563, Grade A, threads to match rod.
4) Washers: ASTM F436, Type 1.
5) Plates (embedded): ASTM A36.
C. Welded studs:
1. Description: Anchor with forged head for embedment into concrete on one end, and welding ferrule for attachment to steel on the other. Welded to steel members or plates to provide anchorage for steel connections to concrete.
2. Acceptance criteria:
a. Welded studs in accordance with AWS D1.1, Type B.
3. Manufacturers: One of the following or equal:
a. Nelson Stud Welding Co., H4L Concrete Anchors or S3L Shear Connectors as indicated on the Drawings.
b. Stud Welding Products, Headed Concrete Anchors (HCA) or Headed Shear Connectors (HSC) as indicated on the Drawings.
4. Materials:
a. Galvanized steel:
1) Hot-dip galvanized after fabrication with coating in accordance with ASTM A123.
2) Steel: Carbon steel in accordance with ASTM A108 with 50,000 pounds per square inch minimum yield strength, and 60,000 pounds per square inch minimum tensile strength.
D. Steel plates or shapes for fabrications including assemblies with welded studs or deformed bar anchors:
1. Stainless steel: Type 316L or Type 304L:
a. Plates (embedded): ASTM A240.
2. Galvanized steel:
a. Hot dip galvanized in accordance with ASTM A123.
b. Steel: ASTM A36.
2.03 POST-INSTALLED ANCHORS AND FASTENERS - ADHESIVE
A. Epoxy bonding of reinforcing bars, all thread rods, and threaded inserts in concrete:
As specified in Section 03055 - Adhesive-Bonded Reinforcing Bars and All Thread Rods in Concrete.
B. Epoxy bonding of reinforcing bars, all thread rods, and threaded inserts in masonry:
As specified in Section 04055 - Adhesive Bonding Reinforcing Bars and All Thread Rods in Masonry.
2.04 POST-INSTALLED ANCHORS AND FASTENERS - MECHANICAL
A. General:
1. Post-installed anchors used for the Work shall hold a current ICC Evaluation Service Report demonstrating acceptance for use under the building code
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-7 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal) specified in Section 01410 - Regulatory Requirements. Reports prepared by other recognized evaluation agencies may be submitted for consideration if acceptable to the Engineer and to the authority having jurisdiction. a. Conditions of use: The acceptance report shall indicate acceptance of the product for use under the following conditions:
1) In regions of concrete where cracking has occurred or may occur. 2) To resist short-term loads due to wind forces.
3) To resist short-term loading due to seismic forces for the Seismic Design Category of the structure where the product will be used.
2. Substitutions: When requesting product substitutions, submit calculations, indicating the diameter, effective embedment depth and spacing of the proposed anchors, and demonstrating that the substituted product will provide load resistance that is equal to or greater than that provided by the anchors listed in this Section.
a. Calculations shall be prepared by and shall bear the signature and seal of a Professional Engineer licensed in the State of California. b. Decisions regarding the acceptability of proposed substitutions shall be at the discretion of the Engineer.
B. Concrete anchors:
1. Description. Post-installed anchor assembly consisting of a threaded stud and a surrounding wedge expansion sleeve that is forced outward by torquing the center stud to transfer loads from the stud to the concrete through bearing, friction, or both. (Sometimes referred to as “expansion anchors” or “wedge anchors.”)
a. Do not use slug-in, lead cinch, and similar systems relying on deformation of lead alloy or similar materials to develop holding power.
2. Concrete anchors for anchorage to concrete:
a. Acceptance criteria:
1) Concrete anchors shall have a current ICC-ES Report demonstrating that the anchors have been tested and qualified for performance in both cracked and un-cracked concrete, and for short-term loading due to wind and seismic forces for Seismic Design Categories A through F in accordance with ACI 355.2 and with ICC-ES AC193 (including all mandatory tests and optional tests for seismic tension and shear in cracked concrete).
2) Concrete anchor performance in the current ICC-ES Report shall be “Category 1” as defined in ACI 355.2.
b. Manufacturers: One of the following or equal:
1) Hilti, Kwik Bolt TZ Expansion Anchor.
2) DEWALT/Powers, PowerStud.
3) Simpson Strong-Tie, Strong Bolt 2 Wedge Anchor.
c. Materials. Integrally threaded stud, wedge, washer, and nut:
1) Stainless steel: Type 316.
2) Galvanized: Carbon steel, zinc plated in accordance with ASTM B633, minimum 5 microns (Fe/Zn 5).
3. Concrete anchors for anchorage to concrete masonry (fully grouted cells):
a. Acceptance criteria: Concrete anchors shall have a current ICC-ES Report demonstrating that the anchors have been tested and qualified in accordance with ICC-ES AC01, including all mandatory tests and optional seismic tests.
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-8 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal) b. Manufacturers: One of the following or equal:
1) Hilti, Kwik Bolt 3 Expansion Anchor.
2) DEWALT/Powers, Power-Stud+ SD1.
3) Simpson Strong-Tie, Wedge-All Anchor.
c. Materials. Integrally threaded stud, wedge, washer, and nut:
1) Stainless steel: Type 316.
2) Galvanized: Carbon steel, zinc plated in accordance with ASTM B633, minimum 5 microns (Fe/Zn 5) or mechanically
galvanized in accordance with ASTM B695, Class 55, Type 1.
C. Flush shells:
1. Description: Post-installed anchor assembly consisting of an internally threaded mandrel that is forced into a pre-drilled concrete hole with a setting tool until the top of the anchor is flush with the face of the concrete. Once installed, a removable threaded bolt is installed in the mandrel.
2. Flush shell anchors are not permitted in the Work.
2.05 APPURTENANCES FOR ANCHORING AND FASTENING
A. Anchor bolt sleeves:
1. Having inside diameter approximately 2 inches greater than bolt diameter and minimum 10-bolt diameters long.
2. Plastic sleeves:
a. High-density polyethylene, corrugated sleeve, threaded to provide adjustment of location on the anchor bolt.
b. Manufacturers: The following or equal:
1) Portland Bolt & Manufacturing Co.
B. Isolating sleeves and washers:
1. Manufacturers: One of the following or equal:
a. Central Plastics Co.
b. Allied Corrosion Industries.
2. Sleeves: Mylar, 1/32-inch thick, 4,000 volts per mil dielectric strength, of proper size to fit bolts and extending half way into both steel washers.
3. One sleeve required for each bolt.
4. Washers: The inside diameter of all washers shall fit over the isolating sleeve, and both the steel and isolating washers shall have the same inside diameter and outside diameter.
a. Proper size to fit bolts.
b. Two 1/8-inch thick steel washers for each bolt.
c. G3 Phenolic: 2 insulating washers are required for each bolt:
1) Thickness: 1/8 inch.
2) Base material: Glass.
3) Resin: Phenolic.
4) Water absorption: 2 percent.
5) Hardness (Rockwell): 100.
6) Dielectric strength: 450 volts per mil.
7) Compression strength: 50,000 pounds per square inch. 8) Tensile strength: 20,000 pounds per square inch.
9) Maximum operating temperature: 350 degrees Fahrenheit.
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-9 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal) C. Coating for repair of galvanized surfaces:
1. Manufacturers: The following or equal:
a. Jelt, Galvinox.
D. Thread coating: For use with threaded stainless steel fasteners:
1. Manufacturers: One of the following or equal:
a. Bostik, Never-Seez.
b. Oil Research, Inc., WLR No. 111.
PART 3 EXECUTION
3.01 EXAMINATION
A. Examine Work in place to verify that it is satisfactory to receive the Work of this Section. If unsatisfactory conditions exist, do not begin this Work until such conditions have been corrected.
3.02 INSTALLATION: GENERAL
A. Where anchors and fasteners are not specifically indicated on the Drawings or specified, make attachments with materials specified in this Section.
B. Substitution of anchor types:
1. Post-installed anchors may not be used as an alternative to cast-in/built-in anchors at locations where the latter are indicated on the Drawings.
2. Cast-in/built-in anchors may be used as an alternative to post-installed mechanical anchors at locations where the latter are indicated on the Drawings.
C. Protect products from damage during installation. Take special care to protect threads and threaded ends.
D. Accurately locate and position anchors and fasteners:
1. Unless otherwise indicated on the Drawings, install anchors perpendicular to the surfaces from which they project.
2. Install anchors so that at least 2 threads, but not more than 1/2 inch of threaded rod, projects past the top nut.
E. Interface with other products:
1. Where steel anchors come in contact with dissimilar metals (aluminum, stainless steel, etc.), use stainless steel anchors and separate or isolate dissimilar metals using isolating sleeves and washers.
2. Prior to installing nuts, coat threads of stainless steel fasteners with thread coating to prevent galling of threads.
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-10 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal)
3.03 INSTALLATION: CAST-IN ANCHORS
A. General:
1. Accurately locate cast-in and built-in anchors.
a. Provide anchor setting templates to locate anchor bolts and anchor rods.
Secure templates to formwork.
b. Brace or tie off embedments as necessary to prevent displacement during placement of plastic concrete or of surrounding masonry construction. c. Position and tie cast-in and built-in anchors in place before beginning placement of concrete or grout. Do not “stab” anchors into plastic concrete, mortar, or grout.
d. Do not allow cast-in anchors to touch reinforcing steel. Where cast-in anchors are within 1/4 inch of reinforcing steel, isolate the metals by wrapping the anchors with a minimum of 4 wraps of 10-mil polyvinyl chloride tape in area adjacent to reinforcing steel.
2. For anchoring at machinery bases subject to vibration, use 2 nuts, with 1 serving as a locknut.
3. Where anchor bolts or anchor rods are indicated on the Drawings as being for future use, thoroughly coat exposed surfaces that project from concrete or masonry with non-oxidizing wax. Turn nuts down full length of the threads, and neatly wrap the exposed thread and nut with a minimum of 4 wraps of 10-mil waterproof polyvinyl tape.
B. Anchor bolts:
1. Minimum effective embedment: 10-bolt diameters, unless a longer embedment is indicated on the Drawings.
2. Where indicated on the Drawings, set anchor bolts in plastic, galvanized steel or stainless steel sleeves to allow for adjustment.
C. Welded studs:
1. Butt weld to steel fabrications with automatic stud welding gun as recommended by the manufacturer.
2. Ensure that butt weld develops full strength of the stud.
3.04 INSTALLATION: POST-INSTALLED ADHESIVE ANCHORS
A. Epoxy and acrylic adhesive bonding of reinforcing bars, all thread rods, and internally threaded inserts in concrete: As specified in Section 03055 - Adhesive-Bonded Reinforcing Bars and All Thread Rods in Concrete.
B. Epoxy and acrylic adhesive bonding of reinforcing bars, all thread rods, and internally threaded inserts in masonry: As specified in Section 04055 - Adhesive Bonding Reinforcing Bars and All Thread Rods in Masonry.
3.05 INSTALLATION: POST-INSTALLED MECHANICAL ANCHORS
A. General:
1. Install anchors in accordance with the manufacturer’s instructions, ACI 355.2, the anchor’s ICC-ES Report. Where conflict exists between the ICC-ES Report and the requirements in this Section, the requirements of the ICC-ES Report shall control.
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-11 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal)
2. Where anchor manufacturer recommends the use of special tools and/or specific drill bits for installation, provide and use such tools.
3. After anchors have been positioned and inserted into concrete or masonry, do not:
a. Remove and reuse/reinstall anchors.
b. Loosen or remove bolts or studs.
B. Holes drilled into concrete and masonry:
1. Do not drill holes in concrete or masonry until the material has achieved its minimum specified compression strength (f’c or f’m).
2. Accurately locate holes:
a. Before drilling holes, use a reinforcing bar locator to identify the position of all reinforcing steel, conduit, and other embedded items within a 6-inch radius of each proposed hole.
b. If the hole depth exceeds the range of detection for the rebar locator, the Engineer may require radiographs of the area designated for investigation before drilling commences.
3. Exercise care to avoid damaging existing reinforcement and other items embedded in concrete and masonry.
a. If embedments are encountered during drilling, immediately stop work and notify the Engineer. Await Engineer’s instructions before proceeding.
4. Unless otherwise indicated on the Drawings, drill holes perpendicular to the concrete surface into which they are placed.
5. Drill using anchor manufacturer’s recommended equipment and procedures:
a. Unless otherwise recommended by the manufacturer, drill in accordance with the following:
1) Drilling equipment: Electric or pneumatic rotary type with light or medium impact. Where edge distances are less than 2 inches, use lighter impact equipment to prevent micro-cracking and concrete spalling during drilling process.
2) Drill bits: Carbide-tipped in accordance with ANSI B212-15. Hollow drills with flushing air systems are preferred.
6. Drill holes at manufacturer’s recommended diameter and to depth required to provide the effective embedment indicated.
7. Clean and prepare holes as recommended by the manufacturer and as required by the ICC-ES Report for that anchor.
a. Unless otherwise recommended by anchor manufacturer, remove dust and debris using brushes and clean compressed air.
b. Repeat cleaning process as required by the manufacturer’s installation instructions.
c. When cleaning holes for stainless steel anchors, use only stainless steel or non-metallic brushes.
C. Insert and tighten (or torque) anchors in full compliance with the manufacturer’s installation instructions.
1. Once anchor is tightened (torque), do not attempt to loosen or remove its bolt or stud.
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-12 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal) D. Concrete anchors: Minimum effective embedment lengths unless otherwise indicated on the Drawings:
Concrete Anchors
Nominal
Diameter
Minimum Effective Embedment Length Minimum Member
In Concrete In Grouted Masonry Thickness
3/8 inch 2 1/2 inch 2 5/8 inch 8 inch
1/2 inch 3 1/2 inch 3 1/2 inch 8 inch
5/8 inch 4 1/2 inch 4 1/2 inch 10 inch
3/4 inch 5 inch 5 1/4 inch 12 inch
E. Flush shell anchors:
1. Flush shell anchors are not permitted in the Work.
2. If equipment manufacturer’s installation instructions recommend the use of flush shell anchors, contact Engineer for instructions before proceeding.
F. Sleeve anchors:
1. Minimum effective embedment lengths unless otherwise indicated on the Drawings:
Sleeve Anchors
Nominal Diameter
Minimum Effective
Embedment Length Minimum Member
In Concrete In Grouted Masonry Thickness
M8 (1/2 inch) 70 mm (2 3/4 inch) Not accepted 100 mm (8 inch) M10 (5/8 inch) 76 mm (3 inch) Not accepted 250 mm (10 inch) M12 (3/4 inch) 80 mm (3 1/4 inch) Not accepted 300 mm (12 inch)
2. Install with the sleeve fully engaged in the base material.
G. Screw anchors:
1. Minimum effective embedment lengths unless otherwise indicated on the Drawings:
Screw Anchors
Nominal Diameter
Minimum Effective
Embedment Length Minimum Member
In Concrete In Grouted Masonry Thickness
3/8 inch 2 1/2 inch 3 1/4 inch 8 inch
1/2 inch 3 1/4 inch 4 1/2 inch 8 inch
5/8 inch 4 inch 5 inch 10 inch
3/4 inch 5 1/2 inch 6 1/4 inch 12 inch
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-13 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal)
2. Install screw anchors using equipment and methods recommended by the manufacturer. Continue driving into hole until the washer head is flush against the item being fastened.
H. Undercut concrete anchors:
1. Minimum effective embedment lengths unless otherwise indicated on the Drawings:
Undercut Anchors
Nominal
Diameter
(bolt)
Minimum Effective
Embedment Length Minimum Member
Thickness(1) In Concrete In Grouted Masonry
M10 (3/8 inch) 100 mm (4 inch) Not accepted 200 mm (8 inch) M12 (1/2 inch) 125 mm (5 inch) Not accepted 350 mm (14 inch) M16 (5/8 inch) 190 mm (7 1/2 inch) Not accepted 460 mm (18 inch) M20 (7/8 inch) 250 mm (10 inch) Not accepted 510 mm (20 inch) Notes:
(1) Thickness indicated is for pre-set units. If through-set units are accepted, obtain minimum member thickness requirements from the Engineer.
2. Installations of undercut anchors shall not be allowed where edge distances are less than 12 times the nominal diameter of the anchor stud.
3. Undercut bottom of hole using cutting tools manufactured for this purpose by the manufacturer of the undercut anchors being placed.
3.06 FIELD QUALITY CONTROL
A. Contractor shall provide quality control over the Work of this Section as specified in Section 01450 - Quality Control.
1. Expenses associated with work described by the following paragraphs shall be paid by the Contractor.
B. Post-installed anchors:
1. Review anchor manufacturer’s installation instructions and requirements of the Evaluation Service Report (hereafter referred to as “installation documents”) for each anchor type and material.
2. Observe hole-drilling and cleaning operations for conformance with the installation documents.
3. Certify in writing to the Engineer that the depth and location of anchor holes, and the torque applied for setting the anchors conforms to the requirements of the installation documents.
3.07 FIELD QUALITY ASSURANCE
A. Owner’s Representative will provide on-site observation and field quality assurance for the Work of this Section.
1. Expenses associated with work described by the following paragraphs shall be paid by the Owner.
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-14 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal) B. Field inspections and special inspections:
1. Required inspections: Observe construction for conformance to the approved Contract Documents, the accepted submittals, and manufacturer’s installation instructions for the products used.
2. Record of inspections:
a. Maintain record of each inspection.
b. Submit copies to Engineer upon request.
3. Statement of special inspections: At the end of the project, prepare and submit to the Engineer and the authority having jurisdiction inspector’s statement that the Work was constructed in general conformance with the approved Contract Documents, and that deficiencies observed during construction were resolved.
C. Special inspections: Anchors cast into concrete and built into masonry.
1. Provide special inspection during positioning of anchors and placement of concrete or masonry (including mortar and grout) around the following anchors:
a. Anchor bolts.
2. During placement, provide continuous special inspection at each anchor location to verify that the following elements of the installation conform to the requirements of the Contract Documents.
a. Anchor:
1) Type and dimensions.
2) Material: Galvanized steel, Type 304 stainless steel, or Type 316 stainless steel as specified in this Section or indicated on the Drawings.
3) Positioning: Spacing, edge distances, effective embedment, and projection beyond the surface of the construction.
4) Reinforcement at anchor: Presence, positioning, and size of additional reinforcement at anchors indicated on the Drawings.
3. Following hardening and curing of the concrete or masonry surrounding the anchors, provide periodic special inspection to observe and confirm the following:
a. Base material (concrete or grouted masonry):
1) Solid and dense concrete or grouted masonry material within required distances surrounding anchor.
2) Material encapsulating embedment is dense and well-consolidated.
D. Special Inspections: Post-installed mechanical anchors placed in hardened concrete and in grouted masonry.
1. Provide special inspection during installation of the following anchors:
a. Concrete anchors.
2. Unless otherwise noted, provide periodic special inspection during positioning, drilling, placing, and torquing of anchors.
a. Provide continuous special inspection for post-installed anchors in “overhead installations” as defined in this Section.
3. Requirements for periodic special inspection:
a. Verify items listed in the following paragraphs for conformance to the requirements of the Contract Documents and the Evaluation Report for the anchor being used. Observe the initial installation of each type and
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-15 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal) size of anchor, and subsequent installation of the same anchor at intervals of not more than 4 hours.
1) Any change in the anchors used, in the personnel performing the installation, or in procedures used to install a given type of anchor shall require a new “initial inspection.”
b. Substrate: Concrete or masonry surfaces receiving the anchor are sound and of a condition that will develop the anchor’s rated strength. c. Anchor:
1) Manufacturer, type, and dimensions (diameter and length). 2) Material (galvanized, Type 304 stainless steel, or Type 316 stainless steel).
d. Hole:
1) Positioning: Spacing and edge distances.
2) Drill bit type and diameter.
3) Diameter, and depth.
4) Hole cleaned in accordance with manufacturer’s required procedures. Confirm multiple repetitions of cleaning when recommended by the manufacturer.
5) Anchor’s minimum effective embedment.
6) Anchor tightening/installation torque.
4. Requirements for continuous special inspection:
a. The special inspector shall observe all aspects of anchor installation, except that holes may be drilled in his/her absence provided that he/she confirms the use of acceptable drill bits before drilling, and later confirms the diameter, depth, and cleaning of drilled holes.
E. Field tests:
1. Engineer may, at any time, request testing to confirm that materials being delivered and installed conform to the requirements of the Specifications. a. If such additional testing shows that the materials do not conform to the specified requirements, the Contractor shall pay the costs of these tests. b. If such additional testing shows that the materials do conform to the specified requirements, the Owner shall pay the costs of these tests.
3.08 NON-CONFORMING WORK
A. Remove misaligned or non-performing anchors.
B. Fill empty anchor holes and repair failed anchor locations as specified in Section 03600 using high-strength, non-shrink, non-metallic grout.
C. If more than 10 percent of all tested anchors of a given diameter and type fail to achieve their specified torque or proof load, the Engineer will provide directions for required modifications. Make such modifications, up to and including replacement of all anchors, at no additional cost to the Owner.
3.09 SCHEDULES
A. Stainless steel. Provide and install stainless steel anchors at the following locations:
1. “Corrosive locations” as defined in this Section: Type 316 stainless steel.
2. “Wet and moist locations” as defined in this Section: Type 316 stainless steel.
Mechanical Anchoring and Fastening to Concrete and Masonry 05190-16 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05190 (BidSetFinal)
3. “Other locations:”
a. For connecting stainless steel members to concrete or masonry: Type 304 stainless steel.
b. For connecting aluminum members to concrete or masonry. c. For connecting fiber-reinforced plastic (FRP) members to concrete or masonry.
4. At locations indicated on the Drawings.
B. Galvanized: Provide and install galvanized carbon steel anchors at the following locations:
1. Locations not requiring stainless steel.
2. At locations indicated on the Drawings.
C. Provide and install anchor materials as scheduled in the following Table.
Table - Required Anchoring Materials by Location
Location/Exposure Materials Notes
1. Anchors into concrete and grouted masonry for attachment of carbon steel, including structural steel and other steel fabrications:
a) Interior dry areas Carbon steel - galvanized
b) Locations with galvanized
steel structures or fabrications
Stainless steel - Type 304 or 316 1
c) Exterior and interior wet and
moist locations
Stainless steel - Type 316 1
d) Corrosive locations Stainless steel - Type 316 1
2. Anchors into concrete and grouted masonry for attachment of aluminum, stainless steel, or fiber-reinforced plastic (FRP) shapes and fabrications:
a) Interior dry areas Stainless steel - Type 304 or 316 1 b) Exterior and interior wet and
moist locations
Stainless steel - Type 316 1
c) Corrosive locations Stainless steel - Type 316 1
3. Anchors for attaching equipment and its appurtenances:
a) All locations Stainless steel - Type 316 (unless
Type 304 is specifically indicated in
the specifications for the equipment.)
1 Notes:
(1) Where anchors are in contact with a metal that differs from that of the anchor, provide isolation sleeves and washers.
END OF SECTION
Steel Decking
05310-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05310 (BidSetFinal) SECTION 05310
STEEL DECKING
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Steel deck for floors and roofs, and associated accessories.
1.02 REFERENCES
A. ASTM International (ASTM):
1. A653 - Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process.
B. American Welding Society (AWS):
1. D1.3 - Structural Welding Code - Sheet Steel.
1.03 SUBMITTALS
A. Product data.
B. Shop drawings.
1.04 DELIVERY, STORAGE, AND HANDLING
A. Storage and protection:
1. Store steel deck at the site stacked on platforms or pallets and covered with tarpaulins or other suitable weathertight covering.
2. Do not use steel deck for storage or working platform.
3. Remove damaged, unlabeled, untagged, rusty, and deteriorated steel deck material from the job site.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. One of the following or equal:
1. ASC Profiles.
2. Verco Manufacturing Co.
3. Canam Steel Corp.
2.02 MATERIALS
A. Sheet steel: ASTM A653, G 90 minimum coating designation.
Steel Decking
05310-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05310 (BidSetFinal)
2.03 FABRICATION
A. Steel deck shall be formed:
1. So every sheet is identical and will register perfectly with adjacent sheets.
2. In accordance with building code as specified in Section 01410- Regulatory Requirements.
B. Decking used with concrete fill shall be deformed to develop composite action between the deck and the concrete.
C. Furnish minimum gauge, deck thickness, section modulus, moment of inertia, and allowable diaphragm shear per foot of deck width that is not less than for type deck sections indicated on the Drawings.
D. Treat exposed roof deck with phosphate.
E. Furnish roof deck ready to receive field painting without further pretreatment. Paint exposed roof deck in accordance with Contract Documents.
F. Accessories:
1. Furnish all accessories indicated on the Drawings or needed to completed work.
2. Minimum required gauges:
a. Sump pans: 14 gauge.
b. All other accessories: 20 gauge unless otherwise indicated on the Drawings.
G. Welding and electrodes: In accordance with AWS D1.3.
H. Furnish roof decking in lengths to minimize number of splices.
I. Furnish steel deck complete, including cutting, shaping, fitting, drilling, welding, ridge plates, valley plates, reinforcing plates for openings, and miscellaneous pieces necessary for proper installation.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verification of conditions: Examine work in place to verify that it is satisfactory to receive the work of this Section. If unsatisfactory conditions exist, do not begin this work until such conditions have been corrected.
3.02 INSTALLATION
A. Decking shall span over at least 3 spans wherever possible.
B. Do not damage or overload roof deck during installation.
C. Do not use steel deck for storage or as a working platform until sheets have been welded in position.
Steel Decking
05310-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05310 (BidSetFinal) D. Do not exceed maximum uniformly distributed load of 20 pounds per square foot.
E. Install decking in straight and continuous rows as far as practicable, with ribs at right angles to supporting members.
F. For each end of deck section, provide 3 inches minimum bearing on supports. For sections that abut each other, each piece shall bear a minimum of 3 inches on the support. This requires a 6 inch minimum flange width. For cases where the minimum bearing cannot be obtained, notify the Engineer.
G. Electric arc weld deck sections to bearing plates, supports at butt joints, at intermediate supports, side supports, and at end supports as indicated on the Drawings. Do not burn through the deck. Remove all slag.
H. Fasten the longitudinal joints between deck sections together by the method indicated on the Drawings.
I. Neatly cut and fit openings in roof deck, and reinforce with structural steel members as indicated on the Drawings.
J. Paint welds as specified.
K. Install roof deck free of dents and bent members.
L. Reinforce all holes and openings in steel deck as indicated on the Drawings.
M. Piping, conduit, equipment, and other services: Do not hang from decking.
N. Install all accessories required to complete work.
O. Suspended items:
1. Ceilings and ductwork:
a. Do not attach hangers to deck within the center 1/3 of span. b. Only 1 hanger may be attached to any 1 rib within 1 span. c. Attach wire hangers to decking with clips through hanger tabs.
3.03 REPAIR OF GALVANIZING AND COATING
A. Touch-up damage to galvanized surfaces, including cut edges and holes, with zinc rich primer.
B. Repair damage to factory-applied coating system in accordance with the manufacturer's printed recommendations.
3.04 CLEANUP
A. After erection, remove weld spatter, grease, and oil from decking.
END OF SECTION
Metal Fabrications
05500-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05500 (BidSetFinal) SECTION 05500
METAL FABRICATIONS
PART 1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Ladders.
2. Manhole frames and covers.
3. Miscellaneous metals.
4. Associated accessories to the above items.
1.02 REFERENCES
A. Aluminum Association (AA):
1. DAF-45: Designations from Start to Finish.
a. M12-C22-A41.
B. American Association of State Highway and Transportation Officials (AASHTO):
1. Standard Specifications for Highway Bridges.
C. ASTM International (ASTM):
1. A36 - Standard Specification for Carbon Structural Steel.
2. A48 - Standard Specification for Gray Iron Castings.
3. A53 - Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded, and Seamless.
4. A123 - Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products.
5. A240 - Standard Specification for Chromium and Chromium-Nickel Stainless Steel Plate, Sheet, and Strip for Pressure Vessels for General Applications.
6. A276 - Standard Specification for Stainless Steel Bars and Shapes.
7. A307 - Standard Specification for Carbon Steel Bolts and Studs, 60,000 PSI Tensile Strength.
8. A380 - Standard Practice for Cleaning, Descaling, and Passivation of Stainless Steel Parts, Equipment, and Systems.
9. A489 - Standard Specification for Carbon Steel Lifting Eyes.
10. A500 - Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes.
11. A501 - Standard Specification for Hot-Formed Welded and Seamless Carbon Steel Structural Tubing.
12. A635 - Standard Specification for Steel, Sheet and Strip, Heavy-Thickness Coils, Hot-Rolled, Alloy, Carbon, Structural, High-Strength Low-Alloy, and High-Strength Low-Alloy with Improved Formability, General Requirements for.
13. A653 - Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process.
14. A992 - Standard Specification for Structural Steel Shapes.
Metal Fabrications
05500-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05500 (BidSetFinal)
15. B209 - Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate.
16. B221 - Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes.
17. B308 - Standard Specification for Aluminum-Alloy 6061-T6 Standard Structural Profiles.
18. B429 - Standard Specification for Aluminum-Alloy Extruded Structural Pipe and Tube.
19. F593 - Standard Specification for Stainless Steel Bolts, Hex Cap Screws and Studs.
20. F3125 - Standard Specification for High Strength Structural Bolts, Steel and Alloy Steel, Heat Treated, 120 ksi and 150 ksi Minimum Tensile Strength.
D. American Welding Society (AWS):
1. A2.4 - Standard Symbols for Welding, Brazing, and Nondestructive Examination.
E. Occupational Safety and Health Administration (OSHA).
1.03 DEFINITIONS
A. Passivation: Removal of exogenous iron or iron compounds from the surface of a stainless steel by means of chemical dissolution resulting from treatment with an acid solution that removes the surface contamination but does not significantly affect the stainless steel itself.
1.04 SUBMITTALS
A. Shop drawings:
1. Ladders.
2. Manhole frames and covers.
3. Miscellaneous metals.
4. Associated accessories to the above items.
B. Quality control submittals:
1. Design data.
Metal Fabrications
05500-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05500 (BidSetFinal) PART 2 PRODUCTS
2.01 MATERIALS
A. General: Unless otherwise specified or indicated on the Drawings, structural and miscellaneous metals in accordance with the standards of the ASTM, including the following:
Item
ASTM
Standard No.
Class, Grade
Type or Alloy No.
Cast Iron
Cast Iron A48 Class 40B
Steel
Galvanized sheet iron or steel A653 Coating G90
Coil (plate) A635 --
Structural plate, bars, rolled shapes, and
miscellaneous items (except W shapes).
A36 --
Rolled W shapes A992 Grade 50
Standard bolts, nuts, and washers A307 --
High strength bolts, nuts, and hardened
flat washers
F3125, Grade A325 --
Eyebolts A489 Type 1
Tubing, cold-formed A500 --
Tubing, hot-formed A501 --
Steel pipe A53 Grade B
Stainless Steel
Plate, sheet, and strip A240 Type 304* or 316**
Bars and shapes A276 Type 304* or 316**
Bolts (Type 304) F593 Group 1 Condition CW
Bolts (Type 316) F593 Group 2 Condition CW
Aluminum
Flashing sheet aluminum B209 Alloy 5005-H14,
0.032 inches minimum
thickness
Structural sheet aluminum- B209 Alloy 6061-T6
Metal Fabrications
05500-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05500 (BidSetFinal) Item
ASTM
Standard No.
Class, Grade
Type or Alloy No.
Structural aluminum B209
B308
Alloy 6061-T6
Extruded aluminum B221 Alloy 6063-T42
* Use Type 304L if material will be welded.
** Use Type 316L if material will be welded.
1. Stainless steels are designated by type or series defined by ASTM.
2. Where stainless steel is welded, use low-carbon stainless steel.
2.02 MANUFACTURED UNITS
A. Ladders:
1. General:
a. Type: Safety type conforming to local, State, and OSHA standards as minimum. Furnish guards for ladder wells.
b. Size: 18 inches wide between side rails of length, size, shape, detail, and location indicated on the Drawings.
2. Aluminum ladders:
a. Materials: 6063-T5 aluminum alloy.
b. Rungs:
1) 1-inch minimum solid square bar with 1/8-inch grooves in top and deeply serrated on all sides.
2) Capable of withstanding 1,000 pound load without failure. c. Side rails: Minimum 4-inch by 1/2-inch flat bars.
d. Finish of aluminum components:
1) Anodized finish, 0.7 mil thick, applied to exposed surfaces after cutting. Aluminum Association Specification M12-C22-A41, mechanical finish non specular as fabricated, chemical finish-medium matte, anodic coating-clear Class I Architectural.
2) Pretreat aluminum for cleaning and removing markings before anodizing.
e. Fabrication:
1) Welded construction, of size, shape, location, and details indicated on the Drawings.
2) For ladders over 20 feet high, furnish standard ladder cages or fall prevention system designed in accordance with State and OSHA requirements.
f. Fall prevention system: Include but not limit to railing, brackets, clamps, 2 sleeves, and 2 belts, satisfying OSHA safe climbing requirements:
1) Manufacturers: One of the following or equal:
a) North Consumer Products, Saf-T-Climb.
b) Swager Communications, Climbers Buddy System.
B. Manhole frames and covers:
1. Material: Gray iron castings, in accordance with ASTM A48, Class 30-B.
2. Type: Heavy-duty traffic type, with combined minimum set weight of 265 pounds.
Metal Fabrications
05500-5 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05500 (BidSetFinal)
3. Machine horizontal and vertical bearing surfaces to fit neatly, with easily removable cover bearing firmly in frame without rocking.
4. Frame:
a. Bottom flange type.
b. Approximately 4-1/2 inches frame height.
c. Dimensions as indicated on the Drawings.
1) Minimum inside clear dimension may not be smaller than nominal diameter minus 2 inches.
5. Cover:
a. Skid-resistant grid pattern design stamped with name of utility service provided by manhole, such as "ELECTRICAL," "SEWER,"
"TELEPHONE," or "WATER."
b. Solid type without ventilation holes.
6. Finish: Unpainted.
C. Miscellaneous aluminum:
1. Fabricate aluminum products, not covered separately in this Section, in accordance with the best practices of the trade and field assemble by riveting or bolting.
2. Do not weld or flame cut.
D. Miscellaneous cast iron:
1. General:
a. Tough, gray iron, free from cracks, holes, swells, and cold shuts. b. Quality such that hammer blow will produce indentation on rectangular edge of casting without flaking metal.
c. Before leaving the foundry, clean castings and apply 16-mil dry film thickness coating of coal-tar epoxy, unless otherwise specified or indicated on the Drawings.
E. Miscellaneous stainless steel:
1. Provide miscellaneous stainless steel items not specified in this Section as indicated on the Drawings or specified elsewhere.
a. Fabricate and install in accordance with the best practices of the trade.
2. Cleaning and passivation:
a. Following shop fabrication of stainless steel members, clean and passivate fabrications.
b. Finish requirements: Remove free iron, heat tint oxides, weld scale and other impurities, and obtain a passive finished surface. c. Provide quality control testing to verify effectiveness of cleaning agents and procedures and to confirm that finished surfaces are clean and passivated.
1) Conduct sample runs using test specimens with proposed cleaning agents and procedures as required to avoid adverse effects on surface finishes and base materials.
d. Pre-clean, chemically descale (pickle), and final clean fabrications in accordance with the requirements of ASTM A380 to remove deposited contaminants before shipping.
1) Passivation by citric acid treatment is not allowed. a) If degreasing is required before cleaning to remove scale or iron oxide, cleaning (pickling) treatments with citric acid are
Metal Fabrications
05500-6 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05500 (BidSetFinal) permissible; however, these treatments shall be followed by inorganic cleaners such as nitric-hydrofluoric acid.
2) Provide acid descaling (pickling) in accordance with Table A1.1 of Annex A1 of ASTM A380.
3) After pickling, final cleaning of stainless steel shall conform to Part II of Table A2.1 of Annex A2 of ASTM A380.
e. After cleaning, inspect using methods specified for “gross inspection” in ASTM A380.
f. Improperly or poorly cleaned and passivated materials shall not be shipped and will not be accepted at the job site.
F. Miscellaneous structural steel:
1. Provide miscellaneous steel items not specified in this Section as indicated on the Drawings or specified elsewhere.
a. Fabricate and install in accordance with the best practices of the trade.
G. Isolating sleeves and washers:
1. As indicated on the Drawings and as specified in Section 05190 - Mechanical Anchoring and Fastening to Concrete and Masonry.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verification of conditions:
1. Examine work in place to verify that it is satisfactory to receive the work of this Section.
2. If unsatisfactory conditions exist, do not begin this work until such conditions have been corrected.
3.02 INSTALLATION
A. General:
1. Install products as indicated on the Drawings, and in accordance with shop drawings and manufacturer's printed instructions, as applicable except where specified otherwise.
2. Interface between materials:
a. Dissimilar metals: Where steel comes in contact with dissimilar metals (aluminum, stainless steel, etc.), separate or isolate the dissimilar metals. 1) Make application so that the isolating or protective barrier is not visible in the completed construction.
2) Isolating sleeves and washers: As specified in Section 05190 - Mechanical Anchoring and Fastening to Concrete and Masonry. b. Aluminum in contact with concrete or masonry: Coat aluminum surfaces as specified in Section 09960 - High Performance Coatings. c. Aluminum in contact with concrete or masonry.
B. Ladders:
1. Secure to supporting surface with bent plate clips providing minimum 8 inches between supporting surface and center of rungs.
Metal Fabrications
05500-7 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/05500 (BidSetFinal)
2. Where exit from ladder is forward over top rung, extend side rails 3 feet 3 inches minimum above landing, and return the rails with a radius bend to the landing.
3. Where exit from ladder is to side, extend ladder 5 feet 6 inches minimum above landing and rigidly secure at top.
4. Erect rail straight, level, plumb, and true to position indicated on the Drawings:
a. Correct deviations from true line or grade which are visible to the eye.
C. Stainless Steel:
1. Welding:
a. Passivate field-welded surfaces:
1) Provide cleaning, pickling, and passivating as specified in this Section.
2) Clean using Derustit Stainless Steel Cleaner, or equal.
END OF SECTION
Dampproofing
07110-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07110 (BidSetFinal) SECTION 07110
DAMPPROOFING
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Dampproofing.
1.02 REFERENCES
A. ASTM International (ASTM):
1. D1227 - Standard Specification for Emulsified Asphalt Used as a Protective Coating for Roofing.
B. California Air Resources Board (ARB):
1. Architectural Coatings Suggested Control Measure.
1.03 SUBMITTALS
A. Product data.
B. Shop drawings.
C. Manufacturer's Installation Instructions.
D. Warranty.
1.04 DELIVERY, STORAGE, AND HANDLING
A. Store materials in original, unopened containers in compliance with manufacturer's printed instructions.
1.05 ENVIRONMENTAL REQUIREMENTS
A. Conform to volatile organic compound limits specified in Table 1 of the California ARB Architectural Coatings Suggested Control Measure.
B. Do not apply bituminous dampproofing when temperatures are 40 degrees Fahrenheit or lower or when rain is forecast for the 24 hours following application.
Dampproofing
07110-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07110 (BidSetFinal) PART 2 PRODUCTS
2.01 MATERIALS
A. Dampproofing: ASTM D1227, Asbestos Free, Emulsified Asphalt Coatings:
1. Manufacturers: One of the following or equal:
a. Karnak Corp., Karnak 220 AF.
b. W.R. Meadows, Inc., Sealmastic Type 2 Asphalt Emulsion Dampproofing.
B. Sealing mastic: Type compatible with dampproofing and free of toxic solvents with thick mastic consistency and smooth and uniform in composition product as recommended by dampproofing manufacturer.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that conditions are satisfactory for application of products in accordance with manufacturer's recommendations.
B. Verify that surfaces to receive dampproofing are clean, dry, reasonably smooth, free of dust, dirt, voids, cracks, or sharp projections.
3.02 APPLICATION
A. Completely cover surfaces to receive dampproofing with 2 coats:
1. Applied by brush or spray.
2. Apply dampproofing at manufacturer's recommended rate of application or minimum 2 gallons per 100 square feet, whichever is greater.
B. Extend dampproofing to 6 inches above finish grade.
C. Apply each coat evenly so surfaces have uniform black appearance.
D. Apply second coat at right angles to first, allowing not less than 24 hours between coats.
E. Seal around items and services projecting through dampproofing surfaces in accordance with manufacturer's recommendations.
F. Ensure sealed areas are moisture tight.
G. Backfill completely against dampproofing application within time recommended by manufacturer.
END OF SECTION
Water Repellents
07190-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07190 (BidSetFinal) SECTION 07190
WATER REPELLENTS
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Water repellent for concrete masonry.
1.02 REFERENCES
A. International Union of Testing and Research Laboratories for Materials and Structures:
1. RILEM Test Method No. 11.4 - Measurement of Water Absorption Under Low Pressure.
B. South Coast Air Quality Management District (SCAQMD):
1. Rule 1168 - Adhesive and Sealant Applications.
1.03 DEFINITIONS
A. Water Repellent: Resistance to penetration of water from rainfall.
1.04 SUBMITTALS
A. Product Data.
B. Samples: Water repellent applied on 8-inch by 8-inch substrates to receive water repellent, marked with application date and application rate.
C. Manufacturer's Application Instructions.
1.05 QUALITY ASSURANCE
A. Manufacturer qualifications: Manufacturer of water repellents for minimum of 5 years with satisfactory performance record.
B. Applicator qualifications: Trained, approved, and accepted by water repellent manufacturer.
C. Spray personnel qualifications: Minimum 2 years of experience spraying exotic coatings.
D. Regulatory requirements: Comply with volatile organic compound regulations.
Water Repellents
07190-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07190 (BidSetFinal)
1.06 DELIVERY, STORAGE, AND HANDLING
A. Deliver materials to site in manufacturer's original containers with seals unbroken and labeled with manufacturer's batch number.
B. Store materials in original, unopened containers in compliance with manufacturer's printed instructions.
1.07 ENVIRONMENTAL REQUIREMENTS
A. Sealants in compliance with SCAQMD Rule 1168.
B. Apply water repellent under temperature and relative humidity conditions before, during, and after application in accordance with manufacturer's instructions.
C. Allow surfaces to dry for minimum 5 days after rains.
1.08 PROJECT CONDITIONS
A. Make proper material allowance based upon substrate material and surface configuration when determining quantities of material.
1.09 WARRANTY
A. Warrant to furnish and apply water repellent on walls that experience water penetration because of failure of water repellent for minimum 5 years.
1.10 MAINTENANCE
A. Extra materials: Deliver water repellent in manufacturer's original unopened containers to Owner that equals minimum 1 percent of material supplied.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Water repellent sealer:
1. One of the following or equal:
a. Rainguard Products.
b. ProSoCo, Inc.
2.02 DESIGN AND PERFORMANCE CRITERIA
A. Performance requirements: Surfaces with water repellent shall be uniform in color with unaltered texture.
Water Repellents
07190-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07190 (BidSetFinal)
2.03 MATERIALS
A. Water repellent sealer for concrete and concrete masonry: Silane/siloxane; volatile organic compound compliant; free of silicone oils, paraffin wax, or urethanes.
1. Manufacturers: The following or equal:
a. Rainguard, Blok-Lok™.
2.04 EQUIPMENT
A. Spray equipment: High-volume, low-pressure, airless, with maximum 60 pounds per square inch pressure:
1. Pump: Non-atomizing, able to flow material on walls at minimum 1 to 1-1/2 gallons per minute.
2. Orifice size for concrete, slump block, exposed concrete aggregate, and cement plaster: 0.060 to 0.110 inches.
3. Orifice size for brick, clay brick tile, brick veneer, stone, and wood:
0.060 inches.
PART 3 EXECUTION
3.01 EXAMINATION
A. Carefully inspect installed construction. Verify that construction is ready for repellent application.
B. Require manufacturer's representative to verify that water repellent may be installed.
3.02 PREPARATION
A. Allow concrete or masonry walls to cure at least 30 days before applying water repellent.
B. Clean wall surfaces of soil, mud, efflorescence, or other detrimental materials.
C. Tuck-point or caulk cracks, other than hairline cracks.
D. Route out defective mortar joints, point with mortar and tool.
E. Moisture content: Apply water repellent sealer when moisture content of substrate is 15 percent or less.
3.03 APPLICATION ON CONCRETE, CONCRETE MASONRY, EXPOSED CONCRETE
AGGREGATE, AND CEMENT PLASTER
A. Apply water repellent in accordance with manufacturer's printed instructions.
B. Apply flood coat using low-pressure spray equipment.
C. Start at top of wall and work down using overlapping horizontal passes.
Water Repellents
07190-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07190 (BidSetFinal) D. Hold spray head 8 to 10 inches from surface so saturation coat runs freely down wall 6 to 10 inches below point of application on most substrates.
E. Spray by traveling horizontally to ensure uniform coverage.
F. Overlap each following pass by centering spray head on bottom line of the previous pass.
G. Trigger gun off at end of each pass to avoid applying excessive amount of material.
Do not over apply.
H. Avoid application in hot or windy weather as premature drying can cause whitish residue on walls.
3.04 APPLICATION ON BRICK, CLAY BRICK TILE, BRICK VENEER, STONE, AND WOOD
A. Apply water repellent in accordance with manufacturer's printed instructions.
B. Apply wet coat in horizontal passes using low-pressure spray equipment with or without rundown.
C. Overlap each following pass by approximately 50 percent.
D. Trigger gun off at the end of each pass to avoid an excessive amount of material being applied.
E. Keep surface wet for 5 to 10 minutes and damp for over 1 hour.
F. Do not apply in hot or windy weather. Over-application can result in whitish residue on surface.
3.05 FIELD QUALITY CONTROL
A. 20 days after application, test water repellent on CMU surfaces using RILEM Test Method No. 11.4:
1. Contractor shall perform a 20-minute RILEM baseline test on dry untreated CMU units of each type to receive water repellent. Test results (water loss in milliliter) shall be compared to CMU units in walls after water repellent application.
2. On water repellant coated CMU, a RILEM tube test resulting in 5 milliliter or less after 20 minutes is necessary to qualify for 5-year warranty.
B. Notify the Engineer and manufacturer at least 72 hours in advance of test.
C. Where tested wall areas fail to pass RILEM tube test, apply additional coat of water repellent on entire wall from corner to corner.
D. Test all locations where directed by the Engineer.
Water Repellents
07190-5 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07190 (BidSetFinal)
3.06 CLEANING
A. Concrete, concrete masonry, exposed concrete aggregate, and cement plaster:
Clean drips, runs, and overspray residue while still wet, using detergent and water.
Clean application and spray equipment with detergent and water immediately following use.
B. Brick, clay brick tile, brick veneer, stone, and wood: Clean drips, runs, and overspray residue with petroleum type thinner following application.
C. Clean application and spray equipment according to the manufacturer's recommendations.
D. Remove excess materials, equipment, and debris incidental to water repellent application upon completion.
3.07 PROTECTION
A. During application, protect water repellent treated and adjacent surfaces from damage.
B. Protect glass, aluminum, and other surfaces from overspray.
C. Protect concrete sidewalks from runoff. Soak with water immediately prior to application on adjacent walls.
D. Repair damaged areas promptly.
END OF SECTION
Roof and Deck Insulation
07220-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07220 (BidSetFinal) SECTION 07220
ROOF AND DECK INSULATION
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Roof and deck insulation and associated accessories.
1.02 REFERENCES
A. ASTM International (ASTM):
1. A123 - Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products.
2. D41- Standard Specification for Asphalt Primer Used in Roofing, Dampproofing, and Waterproofing.
3. D312 - Standard Specification for Asphalt Used in Roofing.
B. National Roofing Contractors Association (NRCA).
C. Underwriters Laboratories, Inc. (UL).
1.03 SUBMITTALS
A. Product data.
B. Samples. Include 6-inch square samples of each type and thickness of insulation required.
C. State thickness and R-value of insulation to be provided at each building.
D. Manufacturer's installation instructions: Include the following:
1. Indicate special environmental conditions required for installation.
2. Indicate adhesive recommendations.
3. Indicate fastener recommendations and attachment pattern to meet specified FM 1-90 requirements.
4. Indicate installation techniques.
E. Certificates:
1. Certify that products meet or exceed specified requirements.
2. Certify that insulation is approved by manufacturer for use with specified roofing materials.
F. Manufacturer's field reports.
G. Warranty.
Roof and Deck Insulation
07220-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07220 (BidSetFinal)
1.04 QUALITY ASSURANCE
A. Manufacturer qualifications: Manufacturer of proposed product for minimum 5 years with satisfactory performance record.
B. Installer qualifications:
1. Manufacturer-approved installer of products similar to specified products on minimum 5 projects of similar scope as Project with satisfactory performance record.
2. Committed to complying with manufacturer's specifications and NRCA recommendations.
3. Committed to assuming undivided responsibility for roof insulation, roofing membrane and sheet metal flashing, and trim associated with roofing.
C. Product compatibility: Provide roofing manufacturer approved roof insulation.
D. Pre-installation conference: Conduct as specified in Section 01312 - Project Meetings.
1.05 DELIVERY, STORAGE, AND HANDLING
A. Deliver, store, and handle products in accordance with manufacturer's instructions.
B. Label asphalt containers with certification of full compliance with requirements of ASTM D312, Table 1, and indicating equiviscous temperature, finished flowing temperature, and flash point.
C. Store roof system materials on pallets or dunnage at least 4 inches above ground and suitably covered to protect from weather.
1.06 SEQUENCING AND SCHEDULING
A. Apply no more insulation than can be completely covered with roofing membrane on the same day.
B. When installation of insulation and roof membrane cannot be completed within same day, install temporary water cutoffs at end of day's work and remove cutoffs prior to resumption of work.
1.07 WARRANTY
A. Furnished by roof membrane manufacturer, as specified in Section 07540 - Thermoplastic Polyolefin Roofing
Roof and Deck Insulation
07220-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07220 (BidSetFinal) PART 2 PRODUCTS
2.01 DESIGN AND PERFORMANCE CRITERIA
A. Roof insulation system: As follows with UL Class A and FM Class 1A fire classification and meeting FM 1-90 wind up-lift requirements.
1. Where tapered rigid foam insulation is indicated on the Drawings, insulation shall be as follows:
a. Multiple layer insulation, comprised of layers of flat and tapered rigid foam roof insulation, built up to provide a taper, sloped to drains, of 1/4-inch per foot minimum.
b. Minimum insulation thickness at roof drains shall be 1-1/2 inches. c. Provide drainage pattern as indicated on the Drawings.
2.02 MATERIALS
A. Tapered foam roof insulation:
1. Closed cell polyisocyanurate foam core bonded to universal fiberglass reinforced facers.
2. Utilizing environmentally compliant blowing agent.
3. Manufacturers: One of the following or equal:
a. Johns Manville, Inc., Tapered ENRGY 3.
b. Atlas Roofing Corp., Tapered ACFoam II.
B. Roof crickets and saddles: Tapered Perlite Roof Insulation or as otherwise recommended by roofing manufacturer to meet warranty requirements.
C. Primer: ASTM D41, asphalt primer.
D. Bitumen: ASTM D312, Type II, III, or IV petroleum asphalt, free from inorganic matter; as recommended by manufacturer for interply moppings to suit particular slope limitations.
2.03 ACCESSORIES
A. Screw fastener system for steel decks:
1. Self-drilling and self-tapping, zinc plated or stainless steel screws, sized for 1/2- to 3/4-inch exposure on exposed to view underside of deck, with minimum 3-inch square or diameter ribbed steel stress plates, hot-dip galvanized with minimum G-60 coating in accordance with ASTM A123.
2. Manufacturers: One of the following or equal:
a. Tru Fast.
b. TW Buildex.
Roof and Deck Insulation
07220-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07220 (BidSetFinal) PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that deck is properly graded to outlets.
B. Verify that deck surfaces are clean, dry, and where required, coated with primer.
3.02 PREPARATION
A. Embed 1 ply of roofing felt over roof drains and minimum 6 inches over adjacent surface in solid uniform layer of plastic cement.
3.03 HEATING OF ASPHALT AND APPLICATION TEMPERATURES
A. Equip kettles and tankers with accurate, fully readable thermometers.
B. Do not heat asphalt to or above their flash points.
C. Avoid heating at or above finished flowing temperature.
D. When accepted, heat above finished flowing temperature for no more than 4 hours.
E. Apply asphalt at maximum 25 degrees Fahrenheit below finished flowing temperature or above equiviscous temperature.
F. Do not cut or alter bitumens.
3.04 INSTALLATION OVER STEEL DECK
A. Install roof insulation in accordance with manufacturer's specifications.
B. Secure wood nailers to roof deck adjoining eaves, at roof curbs for attachment of flashing and counterflashing, and at other locations indicated on the Drawings.
1. Nailers shall be built up of pressure treated wood to match the thickness of the insulation.
C. Apply first layer of roof insulation with long joints continuous, either parallel or at right angles to ribs of deck.
D. Form joints parallel to ribs over solid bearing.
E. Stagger end joints.
F. Secure with approved mechanical fasteners in FM I-90 pattern:
1. Space fasteners as recommended by insulation manufacturer.
2. Drive fasteners through tin caps or plastic fastener/cap assemblies, unless they are provided with integral flat cap not less than 1 inch across.
3. Install screw fastener system in top rib of steel deck in accordance with manufacturer's instructions. Where underside of metal deck is exposed to view, size fasteners to penetrate deck from 1/2- to 3/4-inch, unless otherwise recommended by fastener manufacturer.
Roof and Deck Insulation
07220-5 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07220 (BidSetFinal) G. Install cant strips at curbs, parapets, and intersections of roofs and vertical walls, when recommended by membrane manufacturer. Place on top of insulation and set in solid mopping of asphalt.
H. Roof crickets:
1. Install as required to achieve drainage pattern indicated on the Drawings, and as otherwise required to obtain roof warranty. Set in full mopping of hot asphalt. Feathered edges of crickets and tapered insulation shall be formed of perlite or fiber board.
2. Mop 12-inch wide felt strip into solid asphalt at valley formed by installation of roof crickets to provide additional membrane reinforcement.
I. Before application of roofing, turn over and solidly mop projecting felt to insulation at vertical surfaces and edges.
J. Do not leave insulation exposed to weather.
3.05 FIELD QUALITY CONTROL
A. Roof insulation which becomes wet or damaged shall be removed and replaced with solid, dry insulation, unless installer provides written acceptance of the damaged insulation from the roofing manufacturer, whose warranty shall cover the system.
B. Inspections: Roof membrane manufacturer, whose warranty shall cover complete roof assembly, shall provide supervision and inspection necessary to secure warranty.
END OF SECTION
Elastomeric Membrane Roofing
07530-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07530 (BidSetFinal) SECTION 07530
ELASTOMERIC MEMBRANE ROOFING
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Single-ply elastomeric membrane roofing system.
1.02 REFERENCES
A. American Society of Civil Engineers (ASCE):
1. 7 - Hazard Tool.
B. ASTM International (ASTM):
1. D751 - Standard Test Methods for Coated Fabrics.
2. D573 - Standard Test Method for Rubber-Deterioration in an Air Oven.
3. D1149 - Standard Test Method for Rubber Deterioration-Surface Ozone Cracking in an Ozone Controlled Environment.
4. D2136 - Standard Test Method for Coated Fabrics-Low-Temperature Bend Test.
5. D2240 - Standard Test Method for Rubber Property-Durometer Hardness.
6. E108 - Standard Test Methods for Fire Tests of Roof Coverings.
C. California Air Resources Board (ARB):
1. Architectural Coatings Suggested Control Measure.
D. Underwriters Laboratories, Inc. (UL).
1.03 SUBMITTALS
A. Product data: Include specifications and flashing details.
B. Detail drawings: Provide roofing system plans, elevations, sections, details, and details of attachment to other Work, including:
1. Base flashings and membrane terminations.
2. Tapered insulation, including slopes.
3. Crickets, saddles, and tapered edge strips, including slopes.
4. Insulation fastening and adhesive patterns.
5. Mechanical equipment, skylights, conduit, and other penetrations.
C. Samples:
1. For each product specified.
2. Each type of felt: 8 inches square.
D. Manufacturer's Installation Instructions.
E. Certificates: UL listings.
Elastomeric Membrane Roofing
07530-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07530 (BidSetFinal) F. Installer Authorization: Letter or certificate signed by roofing system manufacturer certifying that installer is approved, authorized, or licensed by manufacturer to install roofing system.
G. Maintenance manual: Include repair instructions.
H. Prior to beginning the Work of this Section:
1. Submit sample warranties.
2. Submit the final System Assembly Letter issued by manufacturer indicating that the products and system to be installed shall be eligible to receive the specified manufacturer's guarantee when installed by a certified contractor in accordance with manufacturer application requirements, inspected and approved by an authorized manufacturer representative.
3. Submit the Guarantee Application Confirmation document issued by manufacturer indicating that the project has been reviewed for eligibility to receive the specified guarantee/warranty and that the project is registered.
I. Upon substantial completion:
1. Submit final warranties.
1.04 QUALITY ASSURANCE
A. Manufacturer qualifications: Manufacturer of proposed product for minimum 5 years with satisfactory performance record.
B. Installer qualifications: Qualified firm that is approved, authorized, or licensed by roofing system manufacturer to install manufacturer’s product and that is eligible to receive the specified manufacturer’s guarantee/warranty.
C. Source Limitations:
1. Obtain all components from the single source roofing manufacturer guaranteeing the roofing system.
2. All products used in the system shall be labeled by the single source roofing manufacturer issuing the guarantee.
D. Pre-installation conference: Conduct as specified in Section 01312 - Project Meetings.
E. Verify roof and deck insulation in Section 07220 - Roof and Deck Insulation, and flashing and sheet metal in Section 07600 - Flashing and Sheet Metal are compatible with membrane roofing.
1.05 DELIVERY, STORAGE, AND HANDLING
A. Deliver, store, and handle products in accordance with manufacturer's recommendations.
B. Deliver materials with appropriate labels indicating warnings, storage conditions, lot numbers, and usage instructions.
C. Deliver materials in original unopened containers.
Elastomeric Membrane Roofing
07530-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07530 (BidSetFinal) D. Label containers with manufacturer's name, brand name, installation instructions, and identification of items.
E. Each container or bulk shipping ticket for asphalt shall indicate the equiviscous temperature, finished blowing temperature, and the flash point.
F. Store materials out of direct exposure to the elements.
G. Store roll goods on end on a clean flat surface.
H. Protect materials against moisture.
1.06 ENVIRONMENTAL REQUIREMENTS
A. Conform to volatile organic compound (VOC) limits specified in Table 1 of the California ARB Architectural Coatings Suggested Control Measure.
B. Do not apply roofing membrane during inclement weather or when air temperature may fall below 40 degrees Fahrenheit.
C. Do not apply roofing membrane to damp or frozen deck surface.
D. Do not expose materials vulnerable to water or sun damage in quantities greater than can be weatherproofed during same day.
1.07 WARRANTIES
A. As specified in Section 01783 - Warranties and Bonds.
B. Special warranty:
1. Manufacturer's warranty: Minimum 10 years to correct defective roofing materials, including installation.
2. Roofer's warranty: Minimum 2 years to correct defective workmanship.
3. Warranty rider for hail enhancement:
a. Hail: For hail up to 1 inches.
b. Moderate hail: 1.5.
c. Severe hail: For hail up to 2 inches.
4. Warranty rider for punctures:
a. Provides 8 hours per year for repair of punctures.
b. Provides 16 hours per year for repair of punctures.
c. Provides 32 hours per year for repair of punctures.
5. Warranty rider for ponding water.
6. Warranty rider for overburden.
PART 2 PRODUCTS
2.01 DESIGN AND PERFORMANCE CRITERIA
A. General: Installed roofing membrane system shall remain watertight; and resist specified wind uplift pressures, thermally induced movement, and exposure to weather without failure.
Elastomeric Membrane Roofing
07530-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07530 (BidSetFinal) B. Material compatibility: Roofing materials shall be compatible with one another under conditions of service and application required, as demonstrated by roofing system manufacturer based on testing and field experience.
C. Installer shall comply with current code requirements based on authority having jurisdiction.
D. Wind uplift performance: As specified in Section 01850 - Wind Design Criteria.
1. Roofing system shall be identical to systems that have been successfully tested by a qualified testing and inspecting agency to resist wind uplift pressure calculated in accordance with ASCE 7.
E. Roof live load, roof dead loads and snow load: As indicated on the structural Drawings.
F. Fire-test-response characteristics:
1. Provide roofing materials with the fire-test-response characteristics indicated as determined by testing identical products per test method below by UL, FMG, or another testing and inspecting agency acceptable to authorities having jurisdiction.
2. Materials shall be identified with appropriate markings of applicable testing and inspecting agency.
G. Fire hazard classification:
1. UL Class C.
H. Exterior fire-test exposure:
1. ASTM E108, Class C for application and roof slopes indicated.
2.02 ROOFING SYSTEMS
A. Type: Mechanically attached, 60-mil reinforced membrane assemblies.
B. Membrane color: Black.
2.03 MANUFACTURERS
A. One of the following or equal:
1. Carlisle Corp., Sure-Weld.
2. Johns Manville, EPDM R.
2.04 COMPONENTS
A. Membrane: 60 mil, scrim-reinforced, white, uncured polyolefin based rubber sheet approximately 75 inches wide by appropriate length conforming to following minimum physical properties:
1. Breaking strength: Minimum 225 pounds when tested in accordance with ASTM D751, Grab Method.
2. Tear strength: Minimum 55 pounds when tested in accordance with ASTM D751, Tongue Tear.
Elastomeric Membrane Roofing
07530-5 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07530 (BidSetFinal)
3. Brittleness: Passes bending around 1.8 inch mandrel at minus 45 degrees Celsius in accordance with ASTM D2136.
4. Shore A hardness: From 75 to 85 when tested in accordance with ASTM D2240.
5. Heat aging: Maintains 100 percent of original breaking strength after 28 days at 212 degrees Fahrenheit in accordance with ASTM D573.
6. Ozone resistance: No effect when subjected in 3 parts per million ozone and 30 percent strain at 104 degrees Fahrenheit for 72 hours and 25,000 hours in accordance with ASTM D1149.
7. Puncture resistance: Minimum 250 pounds when tested in accordance with FTM 191 B, Method 2031.
B. Roof walkway:
1. Provide roofing system manufacturer standard roof walkway.
2. Placement location requirements:
a. Traffic concentration points.
b. Regular maintenance access areas.
c. Coordinate roof access landing to connect with traffic concentration points and regular maintenance access areas.
C. Flashing, bonding adhesive, sealant, primer, seam caulk, and mechanical fasteners:
Membrane manufacturer approved.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verification the following:
1. Proper installation of treated curbs, wood nailers, insulation, cants, and crickets.
2. Deck is properly graded to outlets. Build up potential birdbaths.
3. Deck surfaces are dry, clean, smooth, and free of sharp edges and debris.
3.02 PREPARATION
A. Prepare substrate to receive roofing system in accordance with roofing manufacturer's instructions.
B. Install flashings and similar accessory items in accordance with manufacturer's instructions.
C. Sweep surface to be covered clean of debris, dirt, or other sharp objects.
D. Prime metal flanges, concrete and masonry surface, and concrete roof deck to receive membrane roofing with a uniform coating of asphalt primer.
Elastomeric Membrane Roofing
07530-6 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07530 (BidSetFinal)
3.03 INSTALLATION
A. Install roofing in accordance with manufacturer's instructions and warranty.
B. Install perimeter sheets.
C. Lay field sheets with long edges perpendicular to roof slope, with edge of roll aligned with perimeter sheets.
D. Install screw fasteners, spaced in accordance with manufacturer's recommendations, along leading edge of membrane, through insulation, and into roof deck.
E. Overlap fastened edges of installed membrane by approximately 4-1/2 inches. Hot air weld edges with manufacture approved automatic hot air welder.
F. Prime cured material as required before hot air welding.
G. Seal cut edges with seam caulk.
H. Install metal flashing as specified in Section 07600 - Flashing and Sheet Metal and as indicated on the Drawings.
I. Fasten and finish perimeter in accordance with membrane manufacturer's standard details.
J. Where underside of metal deck is exposed to view, size fasteners to penetrate deck not more than 3/4 inch.
K. Cut walkway material into sections (maximum 36 inch). Heat weld in place with 6-inch gap between sections to allow proper drainage.
3.04 FIELD QUALITY CONTROL
A. Arrange for manufacturer's inspection of completed installation in the presence of the Engineer and the Owner.
3.05 PROTECTION
A. Before the end of each working day or before application is interrupted by precipitation, seal exposed sheet edges along laps and around drains, projections, and upstands.
B. Build cutoffs using asphalt or plastic cement and roofing felts, constructed to withstand protracted periods of service. Completely remove cutoffs prior to the resumption of roofing.
END OF SECTION
Thermoplastic Polyolefin (TPO) Membrane Roofing
07540-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07540 (BidSetFinal) SECTION 07540
THERMOPLASTIC POLYOLEFIN (TPO) MEMBRANE ROOFING
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Fully-adhered, 60 mil thermoplastic polyolefin membrane, white, scrim-reinforced roofing system.
1.02 REFERENCES
A. American Society of Civil Engineers (ASCE):
1. 7 – Hazard Tool.
B. ASTM International (ASTM):
1. D751 – Standard Test Methods for Coated Fabrics.
2. E108 – Standard Test Methods for Fire Tests of Roof Coverings.
C. California Air Resources Board (ARB):
1. Architectural Coatings Suggested Control Measure.
D. Single Ply Roofing Industry (SPRI):
1. SPRI WD-1 - Wind Design Standard Practice for Roofing Assemblies.
E. Underwriters Laboratories, Inc.(UL).
1.03 SUBMITTALS
A. Product data: Include specifications and flashing details.
B. Detail drawings: Provide roofing system plans, elevations, sections, details, and details of attachment to other Work, including:
1. Base flashings and membrane terminations.
2. Tapered insulation, including slopes.
3. Crickets, saddles, and tapered edge strips, including slopes.
4. Insulation fastening and adhesive patterns.
5. Mechanical equipment, skylights, conduit, and other penetrations.
C. Samples:
1. For each product specified.
2. Each type of felt: 8 inches square.
D. Manufacturer's Installation Instructions.
Thermoplastic Polyolefin (TPO) Membrane Roofing
07540-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07540 (BidSetFinal) E. Certificates:
1. UL listings.
2. Letter of certification from the manufacturer certifying the roofing contractor is authorized to install the manufacturer's roofing system, include certified foreman and training dates.
3. Indicating membrane thickness from the membrane manufacturer.
F. Installer Authorization: Letter or certificate signed by roofing system manufacturer certifying that installer is approved, authorized, or licensed by manufacturer to install roofing system.
G. Maintenance manual: Include repair instructions.
H. Prior to beginning the Work of this Section:
1. Submit sample warranties.
2. Submit the final System Assembly Letter issued by manufacturer indicating that the products and system to be installed shall be eligible to receive the specified manufacturer's guarantee when installed by a certified contractor in accordance with manufacturer application requirements, inspected and approved by an authorized manufacturer representative.
3. Submit the Guarantee Application Confirmation document issued by manufacturer indicating that the project has been reviewed for eligibility to receive the specified guarantee/warranty and that the project is registered.
I. Upon substantial completion:
1. Submit final warranties.
1.04 QUALITY ASSURANCE
A. Manufacturer qualifications: Manufacturer of proposed product for minimum 5 years with satisfactory performance record.
B. Installer qualifications: Qualified firm that is approved, authorized, or licensed by roofing system manufacturer to install manufacturer’s product and that is eligible to receive the specified manufacturer’s guarantee/warranty.
C. Source Limitations:
1. Obtain all components from the single source roofing manufacturer guaranteeing the roofing system.
2. All products used in the system shall be labeled by the single source roofing manufacturer issuing the guarantee.
D. Pre-installation conference: Conduct as specified in Section 01312 - Project Meetings.
E. Verify existing roof, deck insulation, and roof specialties and accessories in Section 07700 - Roof Specialties are compatible with membrane roofing.
Thermoplastic Polyolefin (TPO) Membrane Roofing
07540-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07540 (BidSetFinal)
1.05 DELIVERY, STORAGE, AND HANDLING
A. Deliver materials in original unopened containers.
B. Label containers with manufacturer's name, brand name, installation instructions, and identification of items.
C. Each container or bulk shipping ticket for asphalt shall indicate the equiviscous temperature, finished blowing temperature, and the flash point.
D. Store materials out of direct exposure to the elements.
E. Store roll goods on end on a clean flat surface.
F. Protect materials against moisture.
1.06 ENVIRONMENTAL REQUIREMENTS
A. Conform to volatile organic compound (VOC) limits specified in Table 1 of the California ARB Architectural Coatings Suggested Control Measure.
B. Do not apply roofing membrane during inclement weather or when air temperature may fall below 40 degrees Fahrenheit.
C. Do not apply roofing membrane to damp or frozen deck surface.
D. Do not expose materials vulnerable to water or sun damage in quantities greater than can be weatherproofed during same day.
1.07 WARRANTY
A. As specified in Section 01783 - Warranties and Bonds.
B. Special warranty:
1. Manufacturer's warranty:
a. Minimum 20 years to correct defective roofing materials, including installation.
2. Roof Installer's warranty: Minimum 2 years to correct defective workmanship.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. One of the following or equal:
1. Carlisle Corp., Sure-Weld Roofing System.
2. Johns Manville, JM TPO Roofing Systems.
Thermoplastic Polyolefin (TPO) Membrane Roofing
07540-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07540 (BidSetFinal)
2.02 D TYPE
A. Type: Fully-adhered, 60 mil, reinforced thermoplastic polyolefin (TPO) membrane assemblies.
B. Membrane color: White.
2.03 DESIGN AND PERFORMANCE CRITERIA
A. General: Installed roofing membrane system shall remain watertight; and resist specified wind uplift pressures, thermally induced movement, and exposure to weather without failure.
B. Material compatibility: Roofing materials shall be compatible with one another under conditions of service and application required, as demonstrated by roofing system manufacturer based on testing and field experience.
C. Installer shall comply with current code requirements based on authority having jurisdiction.
D. Design uplift pressures:
1. In accordance with building code: As specified in Section 01410 - Regulatory Requirements.
2. In accordance with SPRI WD-1.
3. In accordance with ASCE 7 – Minimum Design Loads and Associated Criteria for Buildings and Other Structures (ASCE.SEI 7-16).
E. Wind uplift performance:
1. As specified in Section 01850 - Design Criteria.
2. Roofing system shall be identical to systems that have been successfully tested by a qualified testing and inspecting agency to resist wind uplift pressure calculated in accordance with ASCE 7.
F. Wind pressure at each element: As indicated on the structural Drawings.
G. Roof live load, roof dead loads and snow load: As indicated on the structural Drawings.
H. Fire-test-response characteristics:
1. Provide roofing materials with the fire-test-response characteristics indicated as determined by testing identical products per test method below by UL, FMG, or another testing and inspecting agency acceptable to authorities having jurisdiction.
2. Materials shall be identified with appropriate markings of applicable testing and inspecting agency.
I. Fire hazard classification:
1. UL Class C.
J. Exterior fire-test exposure:
1. ASTM E108, Class C for application and roof slopes indicated.
Thermoplastic Polyolefin (TPO) Membrane Roofing
07540-5 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07540 (BidSetFinal)
2.04 COMPONENTS
A. Scrim-Reinforced Thermoplastic Polyolefin (TPO) Sheet: 60 mil, scrim-reinforced, white, membrane 10-feet wide maximum by appropriate length conforming to following minimum physical properties:
1. Tensile strength: Minimum of 300 pounds per foot as tested in accordance with ASTM D751.
2. Tear strength: Minimum 45-60 pounds when tested in accordance with ASTM D751.
B. Flashing, bonding adhesive, sealant, primer, seam caulk, insulation replacement, and fasteners: Membrane manufacturer approved.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verification the following:
1. Proper installation of treated curbs, wood nailers, insulation, cants, and crickets.
2. Deck is properly graded to outlets. Build up potential birdbaths.
3. Deck surfaces are dry, clean, smooth, and free of sharp edges and debris.
3.02 PREPARATION
A. Prepare substrate to receive roofing system in accordance with roofing manufacturer's instructions.
B. Install flashings and similar accessory items in accordance with manufacturer's instructions.
C. Sweep surface to be covered clean of debris, dirt, or other sharp objects.
D. Prime metal flanges, concrete and masonry surface, and concrete roof deck to receive membrane roofing with a uniform coating of asphalt primer.
3.03 INSTALLATION
A. Install roofing in accordance with manufacturer's instructions and warranty.
B. Install perimeter sheets.
C. Lay field sheets with long edges perpendicular to roof slope, with edge of roll aligned with perimeter sheets.
D. Fully adhered membrane shall be bonded to the substrate with manufacturer's approved adhesives. Overlap fastened edges of installed membrane by approximately 5-1/2 inches at fastening plates and 2 inches at end roll sections.
Thermoplastic Polyolefin (TPO) Membrane Roofing
07540-6 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07540 (BidSetFinal) E. Seal non-factory cut edges with seam caulk.
F. Fasten and finish perimeter in accordance with membrane manufacturer's standard termination details.
3.04 FIELD QUALITY CONTROL
A. Arrange for manufacturer's inspection of completed installation in the presence of the Engineer and the Owner.
3.05 PROTECTION
A. Before the end of each working day or before application is interrupted by precipitation, seal exposed sheet edges along laps and around drains, projections, and upstands.
B. Build cutoffs using asphalt or plastic cement and roofing felts, constructed to withstand protracted periods of service. Completely remove cutoffs prior to the resumption of roofing.
END OF SECTION
Flashing and Sheet Metal
07600-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07600 (BidSetFinal) SECTION 07600
FLASHING AND SHEET METAL
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: flashing, sheet metal, and associated accessories.
1.02 REFERENCES
A. Aluminum Association (AA).
B. ASTM International (ASTM):
1. A240 - Standard Specification for Chromium and Chromium-nickel Stainless Steel Plate, Sheet, and Strip For Pressure Vessels and General Applications.
2. A653 - Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process.
3. B32 - Standard Specification for Solder Metal.
4. B209 - Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate.
5. B221 - Standard Specification for Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes.
6. B224 - Standard Classification of Coppers.
7. B370 - Standard Specification for Copper Sheet and Strip for Building Construction.
8. B749 - Standard Specification for Lead and Lead Alloy Strip, Sheet, and Plate Products.
9. D226 - Standard Specification for Asphalt-Saturated Organic Felt Used in Roofing and Waterproofing.
10. D4586 - Standard Specification for Asphalt Roof Cement, Asbestos-Free.
C. Sheet Metal and Air Conditioning Contractors National Association, Inc. (SMACNA).
1.03 SUBMITTALS
A. Product data.
B. Shop drawings: Show fabrication details, material profiles, connections, jointing pattern, jointing details, fastening methods, isolation methods, and installation details.
C. Manufacturer's Installation Instructions.
1.04 SEQUENCING AND SCHEDULING
A. Coordinate sheet metal installation with installation of materials specified in Sections 07530 - Elastomeric Membrane Roofing, 07700 - Roof Specialties, 07900 - Joint Sealants, 15050 - Common Work Results for Mechanical Equipment.
Flashing and Sheet Metal
07600-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07600 (BidSetFinal)
1.05 DELIVERY, STORAGE, AND HANDLING
A. Stack preformed material to prevent twisting, bending, or abrasion, and to provide ventilation.
B. Prevent contact with materials during storage which may cause discoloration, staining, or damage.
PART 2 PRODUCTS
2.01 MATERIALS
A. Aluminum extrusions: ASTM B221, alloy 6063-T42.
B. Aluminum sheet: ASTM B209, 5005-H14 alloy and temper; minimum 32 mils thick.
2.02 ACCESSORIES
A. Fasteners and metal washers: Types best suited for purpose, of same material as sheet metal being fastened or of composition that will not support electrolysis, such as Type 18-8 stainless steel for fastening aluminum.
B. Sealer washers: Rubber type, minimum 0.040 inch thick.
C. Underlayment: ASTM D226; Number 30 asphalt saturated roofing felt. Polyethylene, 6 mil thick.
D. Protective backing paint: Bituminous.
E. Slip sheet: Rosin sized building paper.
F. Bedding compound: Rubber-asphalt type.
G. Roof cement: ASTM D4586, plastic asphaltic cement.
H. Solder: ASTM B32.
2.03 FABRICATION
A. Form sheet metal true to shape, accurate in size, square, and free from distortion or defects.
B. Form rises and angles into flashing true and straight, with exposed surfaces free from waves and buckles.
C. Fabricate cleats and starter strips of same material as sheet, minimum 3 inches wide, interlockable with sheet.
D. Form pieces in longest practical lengths. Size and space joints to provide adequate movement for thermal expansion and contraction.
Flashing and Sheet Metal
07600-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07600 (BidSetFinal) E. Hem exposed edges on underside 1/2 inch; miter and seam corners.
F. Form material with standing seams.
G. Solder and seal metal joints. After soldering, remove flux. Wipe and wash solder joints clean.
H. Fabricate corners from 1 piece with minimum 18 inch long legs; seam for rigidity, seal with sealant.
I. Fabricate vertical faces with bottom edge formed outward 1/4 inch and hemmed to form drip.
J. Fabricate flashings to allow toe to extend a minimum 2 inches over roofing. Return and break edges.
2.04 FINISH
A. Backpaint concealed metal surfaces with protective backing paint to minimum dry film thickness of 15 mil.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify roof openings, curbs, pipes, sleeves, ducts, or vents through roof are solidly set, cant strips and reglets in place, and nailing strips located.
B. Verify membrane termination and base flashings are in place, sealed, and secure.
3.02 INSTALLATION
A. Install flashing and sheet metal in accordance with AA and SMACNA references, and when in connection with roofing, roofing manufacturer's specifications.
B. Install sheet metal to even smooth, sound, thoroughly clean and dry surfaces, free from defects that could affect installation.
C. Install flashings where necessary to provide leakproof conditions.
D. Isolate dissimilar metals from direct contact with protective backing paint.
E. Install starter, edge strips, and cleats before starting installation.
F. Perform cutting, fitting, drilling, and other operations in connection with sheet metal required to accommodate work of other sections.
G. Install sealer washers under metal washers or fastener heads where weathertightness is required.
Flashing and Sheet Metal
07600-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07600 (BidSetFinal) H. Install surface mounted reglets true to lines and levels. Seal top of reglets with sealant.
I. Insert counterflashings into reglets to form tight fit.
J. Secure flashings in place using concealed fasteners. Use exposed fasteners only in locations acceptable to the Engineer.
K. Lap and seal joints. Make connections watertight and weathertight.
L. Apply roof cement compound between metal flashings and felt flashings.
1. Fit flashings tight in place.
2. Make corners square, surfaces true and straight in planes, and line accurate to profiles.
M. Seal metal joints watertight.
END OF SECTION
Roof Specialties
07700-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07700 (BidSetFinal) SECTION 07700
ROOF SPECIALTIES
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Manufactured roof specialties and accessories, including the following:
1. Metal coping.
2. Metal gravel stop fascia.
3. Expansion joint covers.
4. Equipment curbs and supports, and associated accessories.
5. Reglet and counterflashing systems.
1.02 REFERENCES
A. Single Ply Roofing Industry (SPRI):
1. ES-1 - Test Standard for Edge Systems Used with Low Slope Roofing Systems.
1.03 SUBMITTALS
A. Product data: Include finish and color options.
B. Shop drawings. Include equipment curbs and supports details.
C. Certifications: Certify that curbs are capable of supporting the specified equipment including loads specified in Section 01850 - Design Criteria.
D. Samples: Include finish and color samples.
E. Manufacturer's Installation Instructions.
F. Warranties.
1.04 QUALITY ASSURANCE
A. Manufacturer qualifications: Manufacturer of proposed product for minimum 5 years with satisfactory performance record.
B. Installer qualifications: Installer of products similar to specified products on minimum 5 projects of similar scope as Project with satisfactory performance record.
1.05 DELIVERY, STORAGE, AND HANDLING
A. Deliver, store, and handle products in accordance with manufacturer's recommendations.
Roof Specialties
07700-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07700 (BidSetFinal)
1.06 WARRANTY
A. Provide manufacturers' standard warranties that warranty against defects for longer than 1 year.
PART 2 PRODUCTS
2.01 METAL COPINGS
A. Manufacturers: One of following or equal:
1. Peterson Aluminum Corp., Pac-Lok.
2. MM Systems Corp., Snap-Lok.
3. OMG Roofing Products, Permasnap.
B. Characteristics:
1. Capable of direct attachment to top of masonry walls.
2. In accordance with SPRI ES-1.
3. In accordance with codes as specified in Section 01410 - Regulatory Requirements.
4. Capable of counterflashing roofing.
C. Copings:
1. Material: Aluminum, minimum 0.063 inch thick.
2. Width: To suit wall thickness.
3. Length: 144 inches.
4. Face heights: Sufficient to conceal nailers or roof decking.
5. Corners: Mitered and welded with minimum 24-inch legs.
6. Finish: Kynar® 500, resin-base color coating. Color as selected from manufacturer's standard color line.
D. Splice plates: Same materials, width, face heights, and finish as coping, 6 inches long.
E. Seal strips: Extruded Butyl with protective paper.
F. Anchor plate: Galvanized steel. Same width, face height as coping, approximately 12 inches long.
G. Fasteners and anchors: Manufacturer's recommendation.
2.02 GRAVEL STOPS FASCIA FOR SINGLE PLY ROOFING
A. Manufacturers: One of the following or equal:
1. Peterson Aluminum Corp., Pac-1-Ply.
2. MM Systems Corp., SLF- Series II.
3. OMG Roofing Products, TerminEdge.
B. Fascia up to 8 inches high:
1. Material: Aluminum, minimum 0.040-inch thick.
2. Length: Maximum practical.
Roof Specialties
07700-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07700 (BidSetFinal)
3. Face height: Sufficient to conceal edges of nailers or roof decking.
4. Corners: Mitered and welded with minimum 24-inch legs.
5. Finish: Kynar® 500, resin-base color coating. Color as selected from manufacturer's standard color line.
C. Splice plates: Same materials, width, face heights, and finish as coping.
D. Cant dams and hold-down clips: Galvanized steel, minimum 24 gauge, continuous.
E. Screws: Stainless steel.
2.03 EQUIPMENT CURBS
A. Definition:
1. 4-sided curb supporting the footprint (outline) of the roof-mounted equipment.
2. It may surround a full deck opening as at a duct or skylight, a partial deck opening as at supply and return ducts below an A/C unit, or there may be no deck opening within the curb as at a side discharge A/C unit.
B. Manufacturers: One of following or equal:
1. Equipment curbs provided by the equipment manufacturer as specified in the equipment sections.
C. Design requirements:
1. Capable of supporting equipment loads.
2. Size: Curb width as indicated on the Drawings or as otherwise recommended by the equipment manufacturer.
3. Curb manufacturer to coordinate curb capacity and width with the equipment supplier.
D. Material and fabrication:
1. Metal: Galvanized steel; gauge as required to suit equipment loads, minimum 18 gauge.
2. Rail profile: Straight, without cant.
3. Rail height: Minimum 12 inches at uniform thickness insulation and 15 inches at tapered insulation, including nailer.
4. Rail top: Level within 1/8 inch in 10 feet (adjust for roof slope).
5. Rail width: Width of nailer.
6. Rail reinforcement: Rolled tee bar at 24 inches on center.
7. Rail infill: Insulation, 3-pound density.
8. Nailer: Nominal 2 inch by width to suit equipment supported, pressure preservative treated wood, and manufacturer recommended species.
9. Base: Adequately sized to ensure proper anchoring.
10. Corners: Mitered and continuously welded with minimum 24-inch legs.
E. Accessories:
1. Curb liner: Minimum 22 gauge galvanized steel, spot welded to curb, to finish inside of curbs exposed to view from below.
2. Curb platform: Minimum 3/4-inch thick plywood platform over top of curb, capped with 20-gauge galvanized metal welded watertight to support open
Roof Specialties
07700-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07700 (BidSetFinal) sled-based roof equipment, or as watertight closure over curbed opening for future equipment.
3. Metal roofing adapters: Fabricated to conform to exposed metal roofing profile, overlapping deck by minimum 3 inches, with water diverters on flat area; watertight, continuous welds.
2.04 EQUIPMENT SUPPORTS
A. Definition: A linear rail or rails for mounting horizontal piping across the top of roof or for supporting roof equipment on legs.
B. Linear rails:
1. Manufacturers: One of the following or equal:
a. Pate Co., Model ES-2.
b. ThyCurb, Model TEMS.
c. Roof Products, Inc., Model RPES-3.
C. Material and fabrication:
1. Material: 14 gauge galvanized.
2. Rail profile: Straight, without cant profile.
3. Rail height: Minimum 12 inches including nailer at uniform thickness insulation and 15 inches at tapered insulation, including nailer.
4. Rail top: Level within 1/8 inch in 10 feet (adjust for slope of roof).
5. Rail width: Width of nailer.
6. Rail reinforcement: Rolled tee bar at 24 inches on center.
7. Rail infill: None.
8. Nailer: Nominal 2- by 4-inch pressure preservative treated wood, manufacturer recommended species.
9. Base: Adequately sized to ensure proper anchoring.
2.05 REGLET AND COUNTERFLASHING SYSTEMS
A. Manufacturers: One of the following or equal:
1. Fry Corp.
2. Cheney Flashing Co.
B. Metal reglet and counterflashing system:
1. Material: Aluminum, minimum 0.025-inch thick.
2. Reglet: Type for embedding in masonry with 1-1/2-inch wide top flange.
3. Counterflashing: Formed with snap lock flange to engage reglet receive and to provide spring action at bottom edge against roofing base flashing.
4. Hold-down clips: Type 302 stainless steel, with fasteners.
5. Sealant: As specified in Section 07900.
C. Retainer system for flexible counterflashing:
1. Retainer: Type for embedding in masonry.
2. Locking gasket: Vinyl rope capable of locking into reglet and firmly holding flashing.
3. Flashing: As specified in Section 07530 - Elastomeric Membrane Roofing.
4. Sealant: As specified in Section 07900 - Joint Sealants.
Roof Specialties
07700-5 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07700 (BidSetFinal) D. Reglet system for non-proprietary counterflashing:
1. Reglet: Original with spacer channel and vinyl rope.
2. Flashing: As specified in Section 07600 - Flashing and Sheet Metal.
3. Sealant: As specified in Section 07900 - Joint Sealants.
E. Lengths: Longest possible.
F. Joints: With alignment splines.
G. Corners: Prefabricated, watertight.
PART 3 EXECUTION
3.01 INSTALLATION
A. Install roof accessories and specialties accordance with manufacturers' instructions.
3.02 INSTALLATION OF METAL COPINGS
A. Accurately align and install metal copings with uniformly smooth vertical faces.
B. Attach anchor plate to top of wall at 72 inches on center.
C. Install splice plates on anchor plates at splice joints of coping. Install seal strips on top of plate and down face approximately 1/2 inch. Apply slight pressure on sealant to incur adherence to clean, dry splice plate. Remove protective paper from sealant.
D. Fully engage hook on front face of coping with front leg of anchor plates, pivot coping into position pressing firmly at rear over each anchor plate until hook on rear face of coping snaps into place.
E. Leave 1/4-inch joint between abutting ends at splice plates.
3.03 INSTALLATION OF GRAVEL STOPS
A. Locate joints in balanced pattern along each run, from end to end.
B. Overlap cant dams 1 inch. Nail to top of nailer at maximum 12 inches on center and face of nailer at maximum 24 inches on center, unless otherwise specified by roofing manufacturer.
C. Accurately align and install gravel stops with uniformly smooth vertical faces.
3.04 INSTALLATION OF EXPANSION JOINT COVERS
A. Nail longitudinal nailing strips to wood nailer at 2 inch centers.
B. Strip flanges as specified in Section 07540 - Thermoplastic Polyolefin (TPO) Membrane Roofing.
Roof Specialties
07700-6 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07700 (BidSetFinal)
3.05 INSTALLATION OF EQUIPMENT CURBS AND SUPPORTS
A. Curbs: Install at roof mounted equipment where specified or indicated.
B. Supports: Install where indicated on the Drawings.
3.06 INSTALLATION OF METAL REGLET AND COUNTERFLASHING SYSTEM A. Verify that reglets have been installed properly with minimum 3-inch overlaps.
B. Apply sealant on back of surface mounted reglets. Fasten reglets to wall with minimum 3-inch overlaps.
C. Install hold-down clips at minimum 30 inches on center. Insert counterflashings in reglets. Ensure spring action of counterflashing over roofing base flashings. Turn hold-down clips over counterflashings.
D. Apply sealant on tops of surface mounted reglets in accordance with Section 07900 - Joint Sealants.
END OF SECTION
Roof Hatches
07722-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07722 (BidSetFinal) SECTION 07722
ROOF HATCHES
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Roof hatches.
1.02 REFERENCES
A. American National Standards Institute (ANSI).
1.03 SUBMITTALS
A. Product data: Indicate general construction, configurations, and jointing methods.
B. Shop drawings: Show locations, sizes, fastening methods, and installation details.
C. Manufacturer's Installation Instructions.
1.04 WARRANTY
A. As specified in Section 01783 - Warranties and Bonds.
B. Special warranty:
1. Duration: 5 years warranty on product defects.
PART 2 PRODUCTS
2.01 ROOF HATCHES
A. Manufacturers: One of the following or equal:
1. The Bilco Co.
2. Nystrom.
2.02 SINGLE LEAF FOR LADDER ACCESS
A. Size:
1. Ladder applications:
a. Nominal size: 42-inches by 30-inches.
b. Cover opening angle minimum: 70 degrees.
B. Cover and curb:
1. Material:
a. Exterior surface and curb material:
1) Minimum 14-gauge galvanized galvanneal steel.
Roof Hatches
07722-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07722 (BidSetFinal) b. Interior surface material:
1) Minimum 22-gauge galvanized steel liner.
2) Fully covering cover insulation.
2. Cover:
a. Corners:
1) 3-inch beaded flange and welded.
2) Weathertight corners.
b. Insulation:
1) Nominal 1-inch thick fiberglass.
3. Curb:
a. Height: Minimum 12 inches.
b. Insulation: 1-inch thick fiberboard on outside.
c. Flange: Minimum 3-1/2-inch with holes for fasteners, and welded, weathertight corners.
4. Safety guardrail:
a. Manufacturers: One of the following or equal:
1) The Bilco Co., Model RL2.
2) Nystrom, SRCAY.
b. Rail material: Aluminum or galvanized steel.
c. Finish: Safety yellow powder coating.
d. Gate: Spring hinged and latched.
5. Curb and roofing interface:
a. Non-metal roofing:
1) Integral metal cap flashing.
C. Finish:
1. Steel hatches: Red oxide primer paint.
D. Hardware:
1. Heavy pintle hinges.
2. Compression spring operators enclosed in telescopic tubes.
3. Positive snap latch with turn handles, both inside and outside.
4. Padlock hasps, both inside and outside.
5. Gasket:
a. EPDM rubber gasket adhered to the liner.
6. Automatic hold-open arm with red vinyl grip handle capable of 1-hand release.
7. Enclosed 2-point spring latch as recommended by manufacturer.
E. Latch hardware:
1. Hardware including latch assembly, inside and outside padlock hasps, arm guide bracket, lifting mechanism bracket, hinges, hinge pins, hold open arm, lock strike casting, springs, spring tubes, shoe castings, and fasteners.
2. Zinc chromate plated.
F. Fall prevention system:
1. As specified in Section 05500 - Metal Fabrications.
Roof Hatches
07722-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07722 (BidSetFinal)
2.03 SINGLE LEAF
A. Size:
1. Equipment access applications:
a. Nominal size: 42-inches by 38-inches.
b. Cover opening angle minimum: 90 degrees.
B. Cover and curb:
1. Material:
a. Exterior surface and curb material:
1) Minimum 14-gauge galvanized galvanneal steel.
b. Interior surface material:
1) Minimum 22-gauge galvanized steel liner.
2) Fully covering cover insulation.
2. Cover:
a. Corners:
1) 3-inch beaded flange and welded.
2) Weathertight corners.
b. Insulation:
1) Nominal 1-inch thick fiberglass. Nominal 2-inch polyiso in cover.
3. Curb:
a. Height: Minimum 12 inches.
b. Insulation: 1-inch thick fiberboard on outside.
c. Flange: Minimum 3-1/2-inch with holes for fasteners, and welded, weathertight corners.
4. Safety guardrail:
a. Rail material: Aluminum or galvanized steel.
b. Finish: Safety yellow powder coating.
c. Gate: Spring hinged and latched.
5. Curb and roofing interface:
a. Non-metal roofing:
1) Integral metal cap flashing.
C. Finish:
1. Steel hatches: Red oxide primer paint.
D. Hardware:
1. Heavy pintle hinges.
2. Compression spring operators enclosed in telescopic tubes.
3. Positive snap latch with turn handles, both inside and outside.
4. Padlock hasps, both inside and outside.
5. Gasket:
a. EPDM rubber gasket adhered to the liner.
6. Automatic hold-open arm with red vinyl grip handle capable of 1-hand release.
7. Enclosed 2-point spring latch as recommended by manufacturer.
E. Latch hardware:
1. Hardware including latch assembly, inside and outside padlock hasps, arm guide bracket, lifting mechanism bracket, hinges, hinge pins, hold open arm, lock strike casting, springs, spring tubes, shoe castings, and fasteners.
2. Zinc chromate plated.
Roof Hatches
07722-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07722 (BidSetFinal)
2.04 DOUBLE LEAF FOR EQUIPMENT ACCESS
A. Size:
1. Equipment access applications:
a. Nominal size: 42-inches by 38-inches.
b. Cover opening angle minimum: 90 degrees.
c. Cover and curb:
2. Material:
a. Exterior surface and curb material:
1) Minimum 14-gauge galvanized galvanneal steel.
b. Interior surface material:
1) Minimum 22-gauge galvanized steel liner.
2) Fully covering cover insulation.
3. Cover:
a. Corners:
1) 3-inch beaded flange and welded.
2) Weathertight corners.
b. Insulation:
1) Nominal 1-inch thick fiberglass.
4. Curb:
a. Height: Minimum 12 inches.
b. Insulation: 1-inch thick fiberboard on outside.
c. Flange: Minimum 3-1/2-inch with holes for fasteners, and welded, weathertight corners.
5. Safety guardrail:
a. Rail material: Aluminum or galvanized steel.
b. Finish: Safety yellow powder coating.
c. Gate: Spring hinged and latched.
6. Curb and roofing interface:
a. Non-metal roofing:
1) Integral metal cap flashing.
B. Finish:
1. Steel hatches: Red oxide primer paint.
C. Hardware:
1. Heavy pintle hinges.
2. Compression spring operators enclosed in telescopic tubes.
3. Positive snap latch with turn handles, both inside and outside.
4. Padlock hasps, both inside and outside.
5. Gasket:
a. EPDM rubber gasket adhered to the liner.
6. Automatic hold-open arm with red vinyl grip handle capable of 1-hand release.
7. Enclosed 2-point spring latch as recommended by manufacturer.
D. Latch hardware:
1. Hardware including latch assembly, inside and outside padlock hasps, arm guide bracket, lifting mechanism bracket, hinges, hinge pins, hold open arm, lock strike casting, springs, spring tubes, shoe castings, and fasteners.
2. Zinc chromate plated.
Roof Hatches
07722-5 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07722 (BidSetFinal) PART 3 EXECUTION
3.01 INSTALLATION
A. Hatch quantities and locations shall be as indicated on the Drawings.
B. Install roof hatches in accordance with manufacturer's instructions.
1. Coordinate with installation of roofing system and related flashing.
2. Provide weathertight installation.
C. Paint hatch as specified in Section 09960 - High-Performance Coatings.
END OF SECTION
Steel Roofing Walkways
07723-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07723 (BidSetFinal) SECTION 07723
STEEL ROOFING WALKWAYS
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Galvanized steel, roof-mounted walkway.
1.02 REFERENCES
A. American Iron and Steel Institute (AISI):
1. Cold-Formed Steel Design Manual.
B. ASTM International (ASTM):
1. A653 - Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process.
1.03 DEFINITIONS
A. Clips: Attachments between planks, support plates, and roof deck ribs.
B. Planks: The walkway surface elements which may span parallel or perpendicular to the ribs of the roof deck.
C. Support Plates: Plates that span between roof deck ribs to support planks that are parallel to the roof deck ribs.
1.04 SUBMITTALS
A. Product data.
B. Shop drawings and calculations:
1. Shop drawings: For roof walkway system, including details on connections to roof.
2. Calculations:
a. Complete test reports indicating maximum allowable loading, both uniform and concentrated, and the associated deflections.
b. Use methods outlined in the AISI Cold-Formed Steel Design Manual. c. Use a live load safety factor of 2.
1.05 DELIVERY, STORAGE, AND HANDLING
A. Storage and protection:
1. Store planks and accessories at the site stacked on platforms or pallets and covered with tarpaulins or other suitable weathertight covering.
2. Remove damaged, unlabeled, untagged, rusty, and deteriorated material from the job site.
Steel Roofing Walkways
07723-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07723 (BidSetFinal) PART 2 PRODUCTS
2.01 MANUFACTURERS
A. The following or equal:
1. Unistrut Corp., Roofwalks.
2.02 DESIGN AND PERFORMANCE CRITERIA
A. Design requirements:
1. Design roof walkway to support a uniform live load of 180 pounds per square foot and a concentrated load of 426 pounds per plank.
2. Design of attachment assembly to roof shall not penetrate roof deck.
B. Performance requirements:
1. Top of planks shall have an anti-skid surface that provides 360-degree positive traction.
2.03 MATERIALS
A. Planks, supporting plates, and clips shall have G90 coating in accordance with ASTM A653.
B. Planks shall be a minimum of 18 gauge roll-formed sheet steel:
1. Supporting plates shall be a minimum of 14 gauge sheet steel.
2. Clips shall be a minimum of 16 gauge sheet steel.
PART 3 EXECUTION
3.01 INSTALLATION
A. Install products as indicated on the Drawings and in accordance with shop drawings and manufacturer's printed instructions, applicable except where specified otherwise.
END OF SECTION
Joint Sealants
07900-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07900 (BidSetFinal) SECTION 07900
JOINT SEALANTS
PART 1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Acrylic-Latex sealant.
2. Precast concrete joint sealant.
3. Silicone sealant.
4. Synthetic rubber sealing compound.
5. Synthetic sponge rubber filler.
6. Related materials.
1.02 REFERENCES
A. American Association of State Highway and Transportation Officials (AASHTO):
1. M198 - Standard Specification for Joints for Concrete Pipe, Manholes, and Precast Box Sections Using Preformed Flexible Joint Sealants.
B. ASTM International (ASTM):
1. C920 - Standard Specification for Elastomeric Joint Sealants.
2. C990 - Standard Specification for Joints for Concrete Pipe, Manholes, and Precast Box Sections Using Preformed Flexible Joint Sealants.
3. C1330 - Standard Specification for Cylindrical Sealant Backing for Use with Cold Liquid-Applied Sealants.
4. C1521 - Standard Practice for Evaluating Adhesion of Installed Weatherproofing Sealant Joints.
5. D412 - Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension.
6. D624 - Standard Test Method for Tear Strength of Conventional Vulcanized Rubber and Thermoplastic Elastomer.
1.03 SUBMITTALS
A. Product data.
B. Samples, include color selections.
C. Manufacturer's Installation Instructions.
D. Warranty.
Joint Sealants
07900-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07900 (BidSetFinal)
1.04 QUALITY ASSURANCE
A. Manufacturer qualifications: Manufacturer of proposed product for minimum 5 years with satisfactory performance record.
B. Installer qualifications: Manufacturer approved installer of products similar to specified products on minimum 5 projects of similar scope as Project with satisfactory performance record.
1.05 PROJECT/SITE CONDITIONS
A. Environmental requirements: Do not apply sealant on wet or frosty surfaces or when surface temperature is higher than 100 degrees Fahrenheit or lower than recommended by the manufacturer.
1.06 DELIVERY, STORAGE, AND HANDLING
A. Deliver, store, and handle products in accordance with manufacturer's recommendations.
B. Code date packages. Do not use material older than manufacturer’s published shelf life. Store materials at temperatures lower than 80 degrees Fahrenheit. Condition materials in accordance with manufacturer’s instructions prior to installation.
1.07 SEQUENCING AND SCHEDULING
A. Caulk joints prior to painting.
1.08 WARRANTY
A. Warrant to correct defective products for minimum 1 year in accordance with manufacturer's standard warranty.
PART 2 PRODUCTS
2.01 SEALANTS
A. General:
1. Provide colors matching materials being sealed.
2. Where compound is not exposed to view in finished work, provide manufacturer's color which has best performance.
3. Nonsagging sealant for vertical and overhead horizontal joints.
4. Sealants for horizontal joints: Self-leveling pedestrian/traffic grade.
5. Joint cleaner, primer, bond breaker: As recommended by sealant manufacturer.
6. Sealant backer rod and/or compressible filler made from closed cell polyethylene, polyethylene jacketed polyurethane foam, or other flexible, nonabsorbent, non-bituminous material recommended by sealant manufacturer to:
a. Control joint depth.
Joint Sealants
07900-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07900 (BidSetFinal) b. Break bond of sealant at bottom of joint.
c. Provide proper shape of sealant bead.
d. Serve as expansion joint filler.
2.02 ACRYLIC-LATEX SEALANT
A. Permanently flexible, nonstaining, and nonbleeding latex modified acrylic sealant compound, colors as selected by Engineer from manufacturer's standard options:
1. Manufacturers: One of the following or equal:
a. Tremco, Tremflex 834.
b. Pecora Corp., Number AC-20.
c. Sonneborn, Sonolac.
2.03 PRECAST CONCRETE JOINT SEALANT
A. Preformed, cold-applied, ready-to-use, flexible joint sealant in accordance with ASTM C990 and AASHTO M 198:
1. Manufacturers: One of the following or equal.
a. Henry Corp., Ram-Nek.
b. Concrete Sealants Division, ConSeal.
2.04 SILICONE SEALANT
A. ASTM C920, Type S, Grade NS, Class 25, single component silicone sealant:
1. Manufacturers: One of the following or equal:
a. Tremco, Proglaze.
b. Pecora Corp., Number 864.
c. Dow Corning, Number 795.
d. General Electric, Number 1200 Series.
2.05 SYNTHETIC RUBBER SEALING COMPOUND
A. Manufacturer: One of the following or equal:
1. Sika Corporation, Sikaflex 2c NS or SL
2. Sika Corporation, Sikaflex 2c NS EZ Mix.
3. Pacific Polymers, Elastothane 227R.
B. Material: In accordance with ASTM C920 Type M, Grade P (pourable), Class 25 and Type M, Grade NS (non-sag), Class 25; multi-part polyurethane; able to cure at room temperature to firm, highly resilient polymer; able to perform satisfactory when continuously submerged in water or sewage and exposed to direct sunlight in dry condition; with the following properties determined at 75 degrees Fahrenheit and 50 percent relative humidity:
1. Base: Polyurethane rubber.
2. Application time: Minimum 2 hours.
3. Cure time: Maximum 3 days.
4. Tack free time: Maximum 24 hours.
5. Ultimate hardness: Non-sag 25, Pourable/SL 40, within 5 Shore A.
6. Tensile strength: Non-sag 95 pounds per square inch minimum and self-leveling minimum 170 pounds per square inch when tested in accordance with ASTM D412.
Joint Sealants
07900-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07900 (BidSetFinal)
7. Ultimate elongation: Minimum 340 percent when tested in accordance with ASTM D412.
8. Tear resistance: Non-sag 45 pounds per inch minimum and self-leveling minimum 85 pounds per inch when tested in accordance with ASTM D624, Die C.
9. Service temperature range: Minus 25 degrees to 158 degrees Fahrenheit.
C. Color: Gray to match concrete, unless indicated on the Drawings.
2.06 SYNTHETIC SPONGE RUBBER FILLER
A. Closed-cell expanded sponge rubber manufactured from synthetic polymer neoprene base, or resilient polyethylene foam backer rod. In accordance with ASTM C1330, Type C:
1. Manufacturers: The following or equal:
a. Presstite, No. 750.3 Ropax Rod Stock.
B. Characteristics:
1. Suitable for application intended.
2. Strength: As necessary for supporting sealing compound during application.
3. Resiliency: Resistance to environmental conditions of installation.
4. Bonding: No bonding to the sealing compound.
5. Structure: Cellular, prevents absorption of water.
6. Compatibility with other materials in joint and acceptance by manufacturer of sealing compound.
7. Size: Minimum 25 percent greater than nominal joint width.
2.07 RELATED MATERIALS
A. Primer: Nonstaining type, recommended by sealant manufacturer to suit application.
B. Joint cleaner: Noncorrosive, nonstaining, compatible with joint forming materials and as recommended by sealant manufacturer.
C. Bond breaker tape: Pressure-sensitive tape recommended by sealant manufacturer to suit application.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify acceptability of joint dimensions, physical, and environmental conditions.
B. Verify that surfaces are dry, clean, and free of dirt, grease, curing compound, and other residue which might interfere with adhesion of sealants.
Joint Sealants
07900-5 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07900 (BidSetFinal)
3.02 PREPARATION
A. Allow concrete to cure thoroughly before caulking.
B. Synthetic sponge rubber filler:
1. Prepare surfaces designated to receive filler in accordance with manufacturer's installation instructions.
2. Do not stretch filler beyond its normal length during installation.
C. Caulking:
1. Verify that surfaces are dry, clean, and free of dirt, grease, curing compounds, and other residue that might interfere with adhesion of sealant.
2. Concrete, masonry, wood, and steel surfaces: Clean and prime in accordance with manufacturer's instructions prior to caulking.
D. Synthetic rubber sealing compound:
1. Ensure surfaces to which synthetic rubber must bond are dry and free of dust, dirt, and other foreign residue.
2. Heavy sandblasted caulking groove to sound surface, and prime with manufacturer's recommended primer for particular surface.
E. For sidewalks, pavements, and similar joints sealed with elastomeric sealants and subject to traffic and other abrasion and indentation exposures, fill joints to depth equal to 75 percent of joint width, but neither more than 5/8 inches deep nor less than 3/8 inches deep.
F. For normal moving building joints sealed with elastomeric sealants not subject to traffic, fill joints to depth equal to 50 percent of joint width, but neither more than 1/2 inch deep nor less than 1/4 inch deep.
G. For joints sealed with acrylic-latex sealants, fill joints to depth in range of 75 percent to 125 percent of joint width.
H. Use joint filler to achieve required joint depths, to allow sealants to perform properly.
I. Prepare surfaces and install synthetic sponge rubber filler in accordance with manufacturer's recommendations.
J. Do not stretch filler beyond normal length during installation.
K. Apply bond breaker when recommended by joint sealer manufacturer.
3.03 INSTALLATION
A. Synthetic sponge rubber filler: Install filler in accordance with manufacturer's installation instructions.
B. Caulking, joints, and sealing:
1. Construct expansion, contraction, and construction joints as indicated on the Drawings.
2. Install pipe and conduit in structures as indicated on the Drawings.
Joint Sealants
07900-6 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07900 (BidSetFinal)
3. Caulk doors, windows, louvers, and other items installed in or over concrete openings inside and out.
4. Use synthetic rubber sealing compound for caulking where indicated on the Drawings or as specified, except for masonry construction and where specified otherwise.
5. Complete caulking prior to painting.
6. Verify that concrete is thoroughly cured prior to caulking.
7. When filler compressible material is used, use untreated type.
8. Apply caulking with pneumatic caulking gun.
9. Use nozzles of proper shape and size for application intended.
10. Maintain continuous bond between caulking and sides of joint to eliminate gaps, bubbles, or voids and fill joint in continuous operation without layering of compound.
11. Employ experienced applicators to caulk joints and seams in neat workmanlike manner.
12. To hasten curing of compound when used on wide joints subject to movement, apply heat with infrared lamps or other convenient means.
13. Apply synthetic rubber sealing compound with pneumatic caulking tool or other acceptable method.
3.04 CLEANING
A. Clean surfaces adjacent to sealant as work progresses.
B. Remove excess uncured sealant by soaking and scrubbing with sealant cleaning solvent.
C. Remove excess cured sealant by sanding with Number 80 grit sandpaper.
D. Leave finished work in neat, clean condition.
3.05 SCHEDULE
A. Acrylic latex:
1. Use where indicated on the Drawings.
2. Interior joints with movement less than 7.5 percent and not subject to wet conditions.
B. Silicone:
1. Use where indicated on the Drawings.
2. Joints and recesses formed where window, door, louver and vent frames, and sill adjoin masonry, concrete, stucco, or metal surfaces.
3. Door threshold bedding.
4. Moist or wet locations, including joints around plumbing fixtures.
5. Stainless steel doors and frames, including joints between applied stops and frames, and around anchor bolts.
6. Plenum joints.
C. Synthetic rubber sealing compound, non-sag Type II:
1. Use where indicated on the Drawings.
2. Water-bearing and earth-bearing concrete structures.
Joint Sealants
07900-7 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/07900 (BidSetFinal)
3. Joints in masonry, concrete vertical surfaces, and metal-faced panels in vertical surfaces.
4. Joints between sheet metal flashing and trim.
5. Joints between sheet metal flashing and trim, and vertical wall surfaces.
6. Small voids between materials requiring filling for weathertight performance in vertical surfaces.
7. Perimeters of frames of doors, windows, louvers, and other openings where bonding is critical to airtight performance.
8. Expansion and control joints in masonry vertical surfaces.
D. Synthetic rubber sealing compound, self-leveling Type I:
1. Use where indicated on the Drawings.
2. Expansion and control joints in masonry, concrete horizontal surfaces, and metal panels in horizontal surfaces.
3. Small voids between materials requiring filling for weathertight performance in horizontal surfaces.
4. Pavement joints.
5. Perimeters of frames of doors, windows, louvers, and other openings in horizontal surfaces where bonding is critical to airtight performance.
3.06 FIELD QUALITY CONTROL
A. Adhesion testing:
1. Perform adhesion tests in accordance with ASTM C1521 per the following criteria:
a. Water bearing structures: 1 test per every 1,000 LF of joint sealed. b. Exterior precast concrete wall panels: 1 test per every 2,000 LF of joint sealed.
c. Chemical containment areas: 1 test per every 1,000 LF of joint sealed. d. Building expansion joints: 1 test per every 500 LF of joint sealed. e. All other type of joints except butt glazing joints: 1 test per every 3,000 LF of joint sealed.
f. Manufacturer's authorized factory representative provide written recommendations for remedial measures on failing tests.
END OF SECTION
Hollow Metal Doors and Frames
08110-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08110 (BidSetFinal) SECTION 08110
HOLLOW METAL DOORS AND FRAMES
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Steel Fire Resistive Rated and Non-Fire Resistive Rated:
1. Doors.
2. Door frames.
3. Combination door frames and window frames with mullions, muntins, and transom bars.
1.02 REFERENCES
A. American National Standards Institute (ANSI):
1. A250.6 - Hardware on Steel Doors (Reinforcement Application).
2. A250.8 - Recommended Specification for Standard Steel Doors and Frames.
B. ASTM International (ASTM):
1. A653 - Standard Specification for Sheet Steel, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process.
2. A924 - Standard Specification for General Requirements for Steel Sheet, Metallic-Coated by the Hot-Dip Process.
3. A1008 - Standard Specification for Steel, Sheet, Cold-Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength Low-Alloy With Improved Formability, Solution Hardened, and Bake Hardenable.
4. A1011 - Standard Specification for Steel, Sheet and Strip, Hot-Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength Low-Alloy With Improved Formability, and Ultra-High Strength.
5. E413 - Classification for Rating Sound Insulation.
C. National Association of Architectural Metal Manufacturers (NAAMM)/Hollow Metal Manufacturers Association (HMMA):
1. HMMA 861 - Guide Specifications for Commercial Hollow Metal Doors and Frames.
D. National Fire Protection Association (NFPA):
1. 80 - Standard for Fire Doors and Other Opening Protectives.
2. 252 - Standard Methods of Fire Tests of Door Assemblies.
E. Steel Door Institute (SDI):
1. SDI-111 - Recommended Details for Standard Steel Doors, Frame, Accessories and Related Components.
2. SDI-117 - Manufacturing Tolerances Standard Steel Doors and Frames.
Hollow Metal Doors and Frames
08110-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08110 (BidSetFinal) F. Underwriters’ Laboratories, Inc., (UL):
1. UL 10C - Positive Pressure Fire Tests of Door Assemblies.
2. UL 102 - Sustainability Assessment for Swinging Door Leafs.
1.03 SUBMITTALS
A. Product data.
B. Shop drawings: Show the following with references to the Engineer's door marks and hardware groups:
1. Location of door and frame types.
2. Details of fabrication, including core construction, glass lights, louvers, weatherstripping, and factory finish for each door.
3. Cutouts and reinforcements for hardware.
4. Methods of installation and anchorage to adjacent construction.
C. Certificates documenting:
1. Fire-rated units have been successfully tested as specified in this Section.
D. Manufacturer's instructions: Submit manufacturer's installation instructions.
E. Pre-Submittal Conference:
1. Conduct conference in compliance with requirements in Section 01312 - Project Meetings with attendance by representatives of Supplier, Installer.
2. Contractor to review proper methods and procedures for installing hollow metal doors and frames.
1.04 QUALITY ASSURANCE
A. Testing agency qualifications: Approved by ultimate enforcing authority for the Project; regularly engaged in inspection of materials and workmanship at factory.
1.05 DELIVERY, STORAGE, AND HANDLING
A. Before delivery, identify type and size of each door and frame in such a way that markings will not damage finish.
B. Preassemble doorframes in shop and deliver to Project site with spreader bar at sill or tie them in pairs to form box.
C. Protect doors and frames with resilient packaging sealed with heat shrunk plastic.
Break seal on-site to permit ventilation.
D. Protect doors and frames during shipment and storage to prevent warping, bending, and corrosion.
1.06 SEQUENCING AND SCHEDULING
A. Ensure timely delivery of reviewed hardware schedule and hardware templates such that no delay occurs in the work of the Contract.
Hollow Metal Doors and Frames
08110-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08110 (BidSetFinal) PART 2 PRODUCTS
2.01 MATERIALS
A. Sheet steel: ASTM A1008, commercial quality, level, cold rolled steel, or ASTM A1011, hot rolled, pickled and oil rolled steel. Galvanize by hot-dip process with zinc-coating in accordance with ASTM A924 or with ASTM A653 and the coating designation A60 or G60.
B. Clips, bolts, screws, and rivets: sized as recommended by manufacturer.
C. Primer: Rust- inhibitive epoxy primer compatible with high-solids epoxy finish coating system as specified in Section 09960 - High-Performance Coatings.
D. Touch-up materials: Primer as recommended by manufacturer.
E. Door hardware: As specified in Section 08710 - Door Hardware.
F. Grout: As specified in Section 04220 - Concrete Unit Masonry.
2.02 DOOR AND FRAME TYPES
A. Interior doors: ANSI 250.8, Grade III, Model 3 or NAAMM HMMA 810 Type A and NAAMM HMMA 861, flush steel rib-stiffened, minimum 18-gauge face sheets.
B. Exterior doors: ANSI 250.8, Grade III, Model 3, or NAAMM HMMA 810 Type A and NAAMM HMMA 861, flush steel rib-stiffened, minimum 16-gauge face sheets.
C. Interior frames: ANSI 250.8 or NAAMM HMMA 861, fully welded frames, minimum 16-gauge, sizes and shapes as indicated on the Drawings.
D. Exterior frames: ANSI 250.8 or NAAMM HMMA 861, fully welded frames HMMA 861, except minimum 14-gauge sizes and shapes as indicated on the Drawings.
2.03 FABRICATION OF FRAMES
A. Galvanize all frames installed in exterior openings.
B. Frames: Sheet steel, integral type, welded continuous to full depth of frames with minimum 5/8-inch deep stops, unless otherwise indicated on the Drawings.
C. Hardware reinforcements: Fabricate according to SDI A250.6 with reinforcing plates from same material as door face sheets.
D. Jamb Anchors: As required for adjacent wall construction, minimum 3 per jamb, unless otherwise indicated on the Drawings.
E. Floor anchors: Fixed type, except where adjustable anchors are indicated on the Drawings, 1 per jamb, with minimum 2 holes for anchorage. Where floor fill occurs,
Hollow Metal Doors and Frames
08110-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08110 (BidSetFinal) terminate bottom of frames at indicated finished floor level and support by adjustable extension clips resting on and anchored to structural slabs.
F. Anchors at masonry: Adjustable strap and stirrup, minimum 16-gauge corrugated or perforated steel at maximum of 30 inches on center and extending minimum 8 inches into masonry.
G. Anchors at previously placed concrete: Countersink machine screws through the frame into expansion devices spaced at maximum 30 inches on center.
H. Anchors at structural steel framing: Welded or otherwise securely fastened with stainless steel screws.
I. Anchors for fire resistive frames: Conform to requirements of labeling authority having jurisdiction.
J. Masonry angle stiffeners: Factory welded into heads of frames for installation in openings more than 48 inches wide.
K. Mullions, muntins, and transom bars: Minimum 18-gauge, tubular sheet steel matching, and butt-welded to head and jamb members.
L. Removable stops: Fasten at approximately 12 to 16 inches on center.
2.04 FABRICATION OF DOORS
A. Galvanize all doors installed in exterior openings.
B. Reinforce face sheets with steel rib stiffeners, spaced at maximum 6 inches apart, and securely attached to face sheets by spot welds at maximum 5 inches on center.
C. Fill voids between face sheets and stiffeners with fiberglass insulation having a minimum density of 0.8 pounds per cubic foot.
D. Edges: Full weld without visible joints. Bevel striking edge 1/8 inch in 2 inches.
E. Door cores:
1. Stiffeners: Vertical steel ribs formed from minimum 22-gauge plain sheet steel, spaced at maximum 6 inches apart and securely attached to face sheets by spot welds at maximum 5 inches on center.
2. Core fillers: Insulation, minimum 0.60 pound density noncombustible type, installed in spaces between stiffeners for full height of door; labeled door core material shall conform to requirements of labeling authority.
F. Tops and bottoms of doors: Close with continuous recess steel channel of minimum 16-gauge, extending full width of door and spot welded to both faces.
G. Tops and bottoms of exterior doors: Flush closing channels welded to make tops and bottoms waterproof with weep holes for escape of moisture.
H. Hardware reinforcements: Fabricate according to SDI A250.6 with reinforcing plates from same material as door face sheets.
Hollow Metal Doors and Frames
08110-5 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08110 (BidSetFinal) I. Astragals:
1. Install on active leaf of double doors in accordance with UL listing requirements for fire resistive ratings as indicated on the Drawings, and for exterior pairs of doors.
2. Do not install on doors swinging in pairs with rating of 90 minutes or less in means of egress where both leaves are required to provide building code required exiting widths.
3. Do not provide astragal cutouts for hardware operations.
J. Astragal clearances for fire resistive rated doors:
1. Door bottoms at doors designated to receive non-combustible threshold: Not to exceed 3/8 inch between threshold and door bottom.
2. Door bottoms where there is no threshold: Maximum clearance between door and floor not to exceed 1/2 inch.
3. Door bottoms at doors designated to receive combustible floor coverings: Not to exceed 1/2 inch between floor covering and door bottom.
4. Clearance between door and frame and between meeting edges of pairs of doors: Not to exceed 1/8 inch.
K. Astragal clearances for non-fire resistive rated doors: Same as fire resistive rated doors, unless otherwise indicated on the Drawings.
2.05 FABRICATION OF FIRE RATED DOORS AND FRAMES
A. Fabricate to meet requirements of the building code as specified in Section 01410 - Regulatory Requirements, UL 10C, UL 102, and NFPA 252, except hose stream test shall not be required for opposite swing double egress exit doors and for doors of fire endurance rating of less than 45 minutes with or without approved glass lites.
B. Temperature rise requirements of doors at exit enclosures and exit passageways:
Maximum transmitted temperature end point of less than 450 degrees Fahrenheit above ambient at end of 30 minutes when tested in accordance with the building code as specified in Section 01410 - Regulatory Requirements.
C. Apply approved testing agency labels on fire rated doors and frames.
D. Fabricate oversized fire rated doors in accordance with requirements for ratings indicated on the Drawings.
2.06 ACCESSORIES
A. Mullions and transom bars: Join to adjacent members by welding or rigid mechanical anchors.
B. Grout guards: Formed from same material as frames, not less than 0.016 inches thick.
C. Silencers:
1. Drill single leaf doorframe jamb stops for minimum 3 silencers.
2. Drill double-leaf doorframe head stops for minimum 2 silencers.
3. Do not drill doorframes for silencers when weatherstripping is to be installed.
Hollow Metal Doors and Frames
08110-6 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08110 (BidSetFinal)
2.07 FINISHING
A. Thoroughly clean surfaces of oil, grease, and other impurities; touch-up abraded galvanizing; and chemically etch.
B. Fill irregularities and sand smooth finish surface. Apply 1 coat of manufacturer's standard rust inhibitive baked-on primer.
C. Finish painting: High solids epoxy polyurethane system:
1. Interior doors in non-corrosive environment: As specified in Section 09910 - Painting.
2. Exterior doors and interior doors in corrosive environments: As specified in Section 09960 - High-Performance Coatings.
PART 3 EXECUTION
3.01 EXAMINATION
A. Examine reviewed hardware schedules and verify proper coordination of hardware and doors and frames.
B. Examine opening locations and verify the following:
1. Correctness of dimensions, backing, or support conditions.
2. Absence of defects that would adversely affect frame or door installation.
3.02 INSTALLATION
A. Install doors and frames in accordance with approved shop drawings and manufacturer's instructions.
B. Frames:
1. Set accurately in position, plumb, align, and attach securely to structure.
2. Set in place before construction of adjacent masonry or framed walls.
3. Anchor frames to previously placed concrete.
4. Set frames before removing spreader bars.
5. Fully grout frames in masonry as the Work progresses.
6. Grout frames at concrete through keyways provided at head and jambs.
C. Doors:
1. Install at correct openings, ensure smooth swing and proper closure with frame.
D. Fire resistive frames and doors:
1. Install to conform to NFPA 80 for fire resistive rated class as indicated on the Drawings.
Hollow Metal Doors and Frames
08110-7 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08110 (BidSetFinal) E. Door hardware:
1. Install in accordance with Section 08710 - Door Hardware.
2. Drill and tap doors and frames to receive non-template, mortised, and surface-mounted door hardware.
F. Separate or isolate dissimilar metals with neoprene gaskets, sleeves, and washers, or with coatings acceptable to the Engineer.
3.03 TOLERANCES
A. Manufacturing and installation tolerances: As indicated on the Drawings or in conformance to SDI 117 as minimum.
3.04 ADJUSTING AND CLEANING
A. Prime coat touch-up: Immediately after installation, sand smooth and touch-up rust areas, and other areas where primer has been damaged, with prime touch-up paint.
B. Make adjustments as required for correct, proper, and free function and smooth operation without binding of hardware or doors and frames.
C. Protect doors and frames from damage to surface or profile.
END OF SECTION
Floor Access Doors
08320-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08320 (BidSetFinal) SECTION 08320
FLOOR ACCESS DOORS
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Non-fire-rated floor access doors.
1.02 REFERENCES
A. American Association of State Highway and Transportation Officials (AASHTO):
1. Standard Specifications for Highway Bridges.
B. Occupational Safety and Health Administration (OSHA):
1. 29 CFR 1910-Occupational Safety and Health Standards.
1.03 SUBMITTALS
A. Product data.
B. Shop drawings that include the following:
1. Floor access door installation recommendations.
2. Locations of floor access doors.
3. Door size and configuration.
4. Live load capacity.
5. Materials of construction and finishes provided.
1.04 DELIVERY, STORAGE, AND HANDLING
A. Identify type and size of each floor access door in way not to damage finish prior to delivery.
B. Deliver products only after proper facilities are available.
C. Deliver and store packaged products in original containers with seals unbroken and labels intact until time of use.
D. Handle carefully to prevent damage and store on clean concrete surface or raised platform in safe, dry area.
1. Do not dump onto ground.
E. Protect floor access doors during shipment and storage to prevent warping, bending, and corrosion.
1.05 WARRANTY
A. Provide manufacturer’s warranty against defects in material and workmanship for a period of 5 years.
Floor Access Doors
08320-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08320 (BidSetFinal)
1.06 MAINTENANCE
A. Deliver 2 keys for each cylinder lock to Owner.
PART 2 PRODUCTS
2.01 MEDIUM-DUTY FLOOR ACCESS DOORS
A. Manufacturers: One of the following or equal:
1. The Bilco Co., Model J or JD (double leaf).
2. Babcock Davis Associates, Inc., Model BFDDP-SAL or BFDDP-DAL (double leaf).
B. Style: Single leaf or double leaf as indicated on the Drawings, steel, capable of withstanding minimum live load of 300 pounds per square foot, channel frame, with drainage couplings.
C. Door leaf: Minimum 1/4-inch, diamond-pattern plate reinforced with stiffeners as required to meet specified live load.
D. Frame: 1/4-inch channel with anchor flange around perimeter.
E. Hardware:
1. Hinges: Each leaf equipped with a minimum of 2 heavy forged-brass hinges with stainless steel pins.
2. Lock: Snap lock with removable handle mounted on door leaf.
3. Grip handle: Provide vinyl grip handle designed to release cover for closing.
4. Operating mechanism: Spring operators designed for ease of operation and automatic hold-open arm with release handle.
5. Drainage assembly: Provide 1-1/2-inch drainage coupling located in corner of the channel frame.
2.02 FINISHES
A. Floor access door finishes:
1. Aluminum: Manufacturer's standard mill finish.
2. Aluminum in contact with dissimilar metals and concrete: Manufacturer's standard bituminous coating.
3. Steel: Manufacturer's standard red oxide primer.
B. Hardware finishes:
1. Provide optional Type 316 stainless steel hardware throughout, including parts of the latch and lifting mechanism assemblies, hold-open arms, and all brackets, hinges, pins, and fasteners.
Floor Access Doors
08320-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08320 (BidSetFinal) PART 3 EXECUTION
3.01 EXAMINATION
A. Examine construction to receive floor access door and verify correctness of dimensions and other supporting or adjoining conditions.
3.02 PREPARATION
A. Coordinate details with other work supporting, adjoining, or requiring floor access doors.
B. Verify dimensions and profiles for each opening.
C. Verify that location will serve portion of work to which access is required.
1. Where proposed functional location conflicts with other work, notify the Engineer before installation.
D. Apply coating to aluminum surfaces that will be in contact with dissimilar metals or concrete when there is none.
3.03 INSTALLATION
A. Install floor access doors in accordance with manufacturer's instructions.
B. Ensure correct types and adequate sizes at proper locations.
C. Securely attach frames to supporting work and ensure doors, frames, and hardware operate smoothly and are free from warp, twist, and distortion.
3.04 ADJUSTING
A. Adjust doors, frames, and hardware to operate smoothly, freely, and properly without binding.
3.05 CLEANING
A. Thoroughly clean surfaces of grease, oil, or other impurities; touch up abraded prime coat where applicable.
END OF SECTION
Door Hardware
08710-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08710 (BidSetFinal) SECTION 08710
DOOR HARDWARE
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Door hardware.
1.02 REFERENCES
A. Builders Hardware Manufacturers Association (BHMA):
1. A156.1 - Butts and Hinges.156.2 - Bored and Preassembled Locks and Latches.
2. A156.3 - Exit Devices.
3. A156.4 - Door Controls.
4. A156.13 - Mortise Locks and Latches.
5. A156.14 - Sliding and Folding Door Hardware.
6. A156.16 - Auxiliary Hardware.
7. A156.18 - Materials and Finishes.
8. A156.23 - Electromagnetic Locks.
9. A156.26 - Continuous Hinges.
10. A156.31 - Electric Strikes and Frame Mounted Actuators.
11. A156.36 - Auxiliary Locks.
B. International Building Code (ICC):
1. A117.1 - Accessible and Usable Buildings and Facilities.
C. National Fire Protection Association (NFPA):
1. 80 - Fire Doors and Windows.
2. 105 - Installation of Smoke Door Assemblies.
3. 252 - Standard Methods of Fire Tests of Door Assemblies.
D. Underwriters Laboratories, Inc. (UL):
1. 10C - Positive Pressure Fire Tests of Door Assemblies.
2. 1784 - Standard for Air Leakage Tests of Door Assemblies and Other Opening Protectives.
1.03 SUBMITTALS
A. Product data:
1. Manufacturer's product data sheets including installation details, material descriptions, dimensions of individual components and profiles, operational descriptions and finishes.
2. Product Test Reports: Indicating compliance with cycle testing requirements, based on evaluation of comprehensive tests performed by manufacturer and witnessed by a qualified independent testing agency.
Door Hardware
08710-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08710 (BidSetFinal) B. Hardware schedule:
1. Include references to Engineer's hardware group number, door type designations, locations, other pertinent data, and manufacturer names or suitable abbreviation opposite items scheduled.
2. Prepared by or under the supervision of supplier, detailing fabrication and assembly of door hardware, as well as procedures and diagrams. Coordinate the final Door Hardware Schedule with doors, frames, and related work to ensure proper size, thickness, hand, function, and finish of door hardware. a. Format: Comply with scheduling sequence and vertical format in DHI's "Sequence and Format for the Hardware Schedule."
b. Organization:
1) Organize the Door Hardware Schedule into door hardware sets indicating complete designations of every item required for each door or opening.
2) Organize door hardware sets in same order as in the Door Hardware Sets at the end of this Section.
3) Submittals that do not follow the same format and order as the Door Hardware Sets will be rejected and subject to resubmission. c. Content: Include the following information:
1) Type, style, function, size, label, hand, and finish of each door hardware item.
2) Manufacturer of each item.
3) Fastenings and other pertinent information.
4) Location of door hardware set, cross-referenced to Drawings, both on floor plans and in door and frame schedule.
5) Explanation of abbreviations, symbols, and codes contained in schedule.
6) Mounting locations for door hardware.
7) Door and frame sizes and materials.
8) Warranty information for each product.
d. Submittal Sequence:
1) Submit the final Door Hardware Schedule at earliest possible date, particularly where approval of the Door Hardware Schedule must precede fabrication of other work that is critical in the Project construction schedule.
2) Include Product Data, Samples, Shop Drawings of other work affected by door hardware, and other information essential to the coordinated review of the Door Hardware Schedule.
C. Keying schedule:
1. After a keying meeting with the owner has taken place prepare a separate keying schedule detailing the final instructions.
2. Submit the keying schedule in electronic format.
3. Include keying system explanation, door numbers, key set symbols, hardware set numbers and special instructions.
4. Owner must approve submitted keying schedule prior to the ordering of permanent cylinders/cores.
D. Samples: Include for each different type and manufacturer for review of finish.
E. Construction key distribution list: Submit upon Owner's request.
Door Hardware
08710-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08710 (BidSetFinal) F. Templates:
1. Furnish hardware templates to fabricators of doors, frames, and other work to be factory-prepared for hardware.
2. Check shop drawings of other work to confirm that adequate hardware backing is available.
G. Project record documents: Include corrected hardware schedule.
H. Operating and Maintenance Manuals:
1. Provide manufacturers operating and maintenance manuals for each item comprising the complete door hardware installation.
2. As specified in Section 01782 - Operation and Maintenance Manuals.
1.04 REGULATORY REQUIREMENTS
A. Provide hardware for fire-resistive rated openings that complies with UL and listed by UL.
1.05 DELIVERY, STORAGE, AND HANDLING
A. Deliver hardware where directed in unopened packages with items packed separately, complete and ready for installation with necessary fittings, trim, fasteners, and accessories.
B. Provide packages bearing the manufacturers' labels with each item or group of items identified according to the accepted hardware schedule.
1.06 QUALITY ASSURANCE
A. Certified products: Where specified, products must maintain a current listing in the Builders Hardware Manufacturers Association (BHMA) Certified Products Directory (CPD).
B. Installer qualifications: A minimum 3 years documented experience installing both standard and electrified door hardware similar in material, design, and extent to that indicated for this Project and whose work has resulted in construction with a record of successful in-service performance.
C. Door hardware supplier qualifications:
1. Experienced commercial door hardware distributors with a minimum 5 years documented experience supplying both mechanical and electromechanical hardware installations comparable in material, design, and extent to that indicated for this Project.
2. Supplier recognized as a factory direct distributor by the manufacturers of the primary materials with a warehousing facility in Project's vicinity.
3. Supplier to have on staff a certified Architectural Hardware Consultant (AHC) available during the course of the Work to consult with Contractor, Architect, and Owner concerning both standard and electromechanical door hardware and keying.
Door Hardware
08710-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08710 (BidSetFinal) D. Source limitations: Obtain each type and variety of door hardware specified in this section from a single source unless otherwise indicated.
1. Electrified modifications or enhancements made to a source manufacturer's product line by a secondary or third party source will not be accepted.
E. Each unit to bear third party permanent label demonstrating compliance with the referenced standards.
F. Pre-submittal conference:
1. Conduct coordination conference in compliance with requirements in Section 01312 - Project Meetings with attendance by representatives of Supplier(s), Installer(s), and Contractor(s) to review proper methods and the procedures for receiving, handling, and installing door hardware.
2. Prior to installation of door hardware, conduct a project specific training meeting to instruct the installing contractors' personnel on the proper installation and adjustment of their respective products.
3. Product training to be attended by installers of door hardware (including electromechanical hardware) for aluminum, hollow metal and wood doors.
Training will include the use of installation manuals, hardware schedules, templates and physical product samples as required.
4. Inspect and discuss electrical roughing-in, power supply connections, and other preparatory work performed by other trades.
5. Review sequence of operation narratives for each unique access controlled opening.
6. Review and finalize construction schedule and verify availability of materials.
7. Review the required inspecting, testing, commissioning, and demonstration procedures.
1.07 MAINTENANCE
A. Require lockset manufacturers to deliver permanent removable cylinder cores and keys and minimum 2 extractor keys to Owner directly.
1.08 SCHEDULING AND SEQUENCING
A. Upon receipt of accepted hardware schedule, coordinate accepted hardware schedule, templates, reinforcing units, and template instructions to door and frame sections.
B. Restrict distribution of construction keys to superintendents and foremen. Maintain record of persons who have received keys on construction distribution list.
1.09 MAINTENANCE TOOLS AND INSTRUCTIONS
A. Furnish a complete set of specialized tools and maintenance instructions as needed for Owner's continued adjustment, maintenance, and removal and replacement of door hardware.
Door Hardware
08710-5 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08710 (BidSetFinal)
1.10 WARRANTY
A. Provide warranty as specified in Section 01783 - Warranties and Bonds.
1. Written warranty, executed by manufacturer(s), agreeing to repair or replace components of standard and electrified door hardware that fails in materials or workmanship within specified warranty period after final acceptance by the Owner. Failures include, but are not limited to, the following:
a. Structural failures including excessive deflection, cracking, or breakage. b. Faulty operation of the hardware.
c. Deterioration of metals, metal finishes, and other materials beyond normal weathering.
d. Electrical component defects and failures within the systems operation.
B. Special warranty:
1. Duration for electromechanical door hardware: 2 years.
2. Duration for standard duty cylindrical (bored) locks and latches: 5 years.
3. Duration for exit hardware: 5 years.
4. Duration for mortise locks and latches: 10 years.
5. Duration for manual overhead door closer bodies: 10 years.
6. Duration for heavy duty floor closers: 10 years.
PART 2 PRODUCTS
2.01 GENERAL
A. Door hardware includes, but is not necessarily limited to, the following:
1. Mechanical door hardware.
2. Electromechanical door hardware.
3. Automatic operators.
4. Cylinders.
2.02 FASTENERS
A. Types:
1. To concrete, marble, or masonry: Machine screws and flush shells.
2. To wood: Wood screws.
3. On gypsum board or plaster: Screws of sufficient length to provide solid connection to framing or backing behind gypsum board or plaster.
4. To mineral and hollow core doors: Hex bolts.
5. Of exit devices to doors: Thru-bolts, unless otherwise specified.
B. Screws exposed: Phillips-head type, full-threaded screws, not combination type.
C. Sizes: Suitable for heavy use.
D. Finish: Stainless steel, unless otherwise required to match material and hardware finish.
Door Hardware
08710-6 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08710 (BidSetFinal)
2.03 HANGING DEVICES
A. Hinges: BHMA A156.1 certified butt hinges with number of hinge knuckles and other options as specified in the Door Hardware Sets.
1. Quantity: Provide the following hinge quantity:
a. 2 Hinges: For doors with heights up to 60 inches.
b. 3 Hinges: For doors with heights 61 to 90 inches.
c. 4 Hinges: For doors with heights 91 to 120 inches.
d. For doors with heights more than 120 inches, provide 4 hinges, plus 1 hinge for every 30 inches of door height greater than 120 inches. e. Hinge size: Provide the following, unless otherwise indicated, with hinge widths sized for door thickness and clearances required:
1) Widths up to 3 feet 0 inches: 4-1/2 inches standard or heavy weight as specified.
2) Sizes from 3 feet 1inch to 4 feet 0 inches: 5 inches standard or heavy weight as specified.
f. Hinge weight and base material: Unless otherwise indicated, provide the following:
1) Exterior doors: Heavy weight, non-ferrous, ball bearing or oil impregnated bearing hinges unless Hardware Sets indicate standard weight.
2) Interior doors: Standard weight, steel, ball bearing or oil impregnated bearing hinges unless Hardware Sets indicate heavy weight. g. Hinge options: Comply with the following:
1) Non-removable pins: Provide set screw in hinge barrel that, when tightened into a groove in hinge pin, prevents removal of pin while door is closed; for the all out-swinging lockable doors. h. Manufacturers: One of the following or equal:
1) Hager Companies (HA).
2) Ives (IV).
3) McKinney Products; ASSA ABLOY Architectural Door Accessories (MK).
2.04 MECHANICAL LOCKS AND LATCHING DEVICES
A. Mortise Locksets, Grade 1 (Heavy Duty): BHMA A156.13, Series 1000, Operational Grade 1 Certified Products Directory (CPD) listed. Locksets are to be manufactured with a corrosion resistant steel case and be field-reversible for handing without disassembly of the lock body.
1. Manufacturers: One of the following or equal:
a. Corbin Russwin Hardware (RU) – ML2000 Series.
b. Sargent Manufacturing (SA) – 8200 Series.
c. Schlage (SC) – L9000 Series.
B. Cylindrical Locksets, Grade 1 (Heavy Duty): BHMA A156.2, Series 4000, Operational Grade 1 Certified Products Directory (CPD) listed.
1. Furnish with solid cast levers, standard 2-3/4 inch backset, and 1/2 inch (3/4 inch at rated paired openings) throw brass or stainless steel latchbolt.
2. Locks are to be non-handed and fully field reversible.
Door Hardware
08710-7 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08710 (BidSetFinal)
3. Manufacturers: One of the following or equal:
a. Corbin Russwin Hardware (RU) - CL3300 Series.
b. Sargent Manufacturing (SA) - 10 Line.
c. Schlage (SC) - ND Series.
2.05 LOCK AND LATCH STRIKES
A. Strikes: Provide manufacturer's standard strike with strike box for each latch or lock bolt, with curved lip extended to protect frame, finished to match door hardware set, unless otherwise indicated, and as follows:
1. Flat-lip strikes: For locks with 3-piece antifriction latch-bolts, as recommended by manufacturer.
2. Extra-long-lip strikes: For locks used on frames with applied wood casing trim.
3. Aluminum-frame strike box: Provide manufacturer's special strike box fabricated for aluminum framing.
4. Double-lipped strikes:
a. For locks at double acting doors.
b. Furnish with retractable stop for rescue hardware applications.
B. Standards: Comply with the following:
1. Strikes for Mortise Locks and Latches: BHMA A156.13.
2. Strikes for Bored Locks and Latches: BHMA A156.2.
3. Strikes for Auxiliary Deadlocks: BHMA A156.36.
4. Dustproof Strikes: BHMA A156.16.
2.06 CONSTRUCTION KEYING
A. Type: Removable core system.
2.07 PERMANENT CYLINDERS AND KEYING
A. Manufacturers: One of the following or equal:
1. Corbin Russwin Hardware (RU).
2. Sargent Manufacturing (SA).
3. Schlage (SC).
B. Cylinders: Original manufacturer cylinders complying with the following:
1. Mortise type: Threaded cylinders with rings and cams to suit hardware application.
2. Rim type: Cylinders with back plate, flat-type vertical or horizontal tailpiece, and raised trim ring.
3. Bored-lock type: Cylinders with tailpieces to suit locks.
4. Mortise and rim cylinder collars to be solid and recessed to allow the cylinder face to be flush and be free spinning with matching finishes.
5. Keyway: Manufacturer’s Standard. Match Facility Standard.
C. Removable cores: Provide removable cores as specified, core insert, removable by use of a special key, and for use with only the core manufacturer's cylinder and door hardware.
Door Hardware
08710-8 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08710 (BidSetFinal) D. Keying system: Each type of lock and cylinders to be factory keyed.
1. Supplier shall conduct a "Keying Conference" to define and document keying system instructions and requirements.
2. Furnish factory cut, nickel-silver large bow permanently inscribed with a visual key control number as directed by Owner.
3. New system: Key locks to a new key system as directed by the Owner.
E. Key quantity: Provide the following minimum number of keys:
1. Change keys per cylinder: 2.
2. Master keys (per master key level/group): 5.
3. Construction control keys (where required): 2.
4. Permanent control keys (where required): 2.
F. Construction keying: Provide temporary keyed construction cores.
G. Key registration list (biting list):
1. Provide keying transcript list to Owner's representative in the proper format for importing into key control software.
2. Provide transcript list in writing or electronic file as directed by the Owner.
2.08 PUSH/PULL PLATES
A. Manufacturers: One of the following or equal:
1. Ives.
2. Trimco.
3. Rockwood.
B. Pulls:
1. Material: As scheduled.
2. Size: Minimum 8 inches center to center, minimum grip diameter of 3/4 inch, minimum projection of 2-1/4 inch.
C. Pull plates:
1. Material: As scheduled.
2. Plate size: Minimum 3 by 12 inches by 0.050-inch thick, with beveled edges on 4 sides with pull.
3. Pull size: Minimum 8 inches center to center, minimum grip diameter of 3/4 inch, minimum projection of 2-1/4 inch.
D. Push plates:
1. Material: As scheduled.
2. Size: Minimum 3 by 12 inches by 0.050-inch thick, with beveled edges on 4 sides.
2.09 CLOSERS
A. Manufacturers:
1. Features:
a. Heavy-duty.
b. Non-handed and non-sized.
c. Adjustable spring power from size 1 through 4.
Door Hardware
08710-9 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08710 (BidSetFinal)
2. One of the following or equal:
a. Sargent, 351 Series.
b. LCN, Super Smoothee Model 4041 Series.
c. Norton Door Controls, Multi-Size Door Closers Model 7500BF Series.
B. Type: Full rack and pinion type with steel spring and non-gumming, non-freezing hydraulic fluid.
C. Controls: Separate set for regulating sweep speed, latch speed, backcheck and backcheck positioning, or where schedules, spring power.
D. Sizes: As recommended by accepted manufacturer.
E. Covers: Metal, capable of receiving finishes to match adjacent hardware finishes, unless otherwise specified.
F. Narrow frame provisions: Drop plates.
G. Effort to operate: As follows:
1. Exterior: Maximum 8-1/2 pounds.
2. Interior: Maximum 5 pounds.
3. Fire-resistive rated doors: Maximum 15 pounds.
H. Adjust closers in accordance with manufacturer's directions for size of door.
2.10 EXIT DEVICES
A. Lever design:
1. Manufacturers: The following or equal:
a. Von Duprin, Lever Model 06.
B. Rim device, non-fire resistive rated:
1. Manufacturers: One of the following or equal:
a. Von Duprin Inc., Model Series 98.
b. Sargent Essex Ind., Model Series 8800.
C. Rim device, fire-resistive rated:
1. Manufacturers: One of the following or equal:
a. Von Duprin Inc., Model Series 98-F.
b. Sargent Essex Ind., Model Series 12-8800.
D. Mortise lock device, non-fire-resistive rated:
1. Manufacturers: The following or equal:
a. Von Duprin Inc., Model Series 9875L.
E. Mortise lock device, fire-resistive rated:
1. Manufacturers: The following or equal:
a. Von Duprin Inc., Model Series 9875L-F.
Door Hardware
08710-10 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08710 (BidSetFinal) F. Material: As scheduled.
G. Corrosive environment provisions: Zinc dichromate coated internal parts.
2.11 MISCELLANEOUS DOOR HARDWARE
A. Wall stops: As scheduled.
1. Manufacturers: One of the following or equal:
a. Ives.
b. Trimco.
c. Rockwood.
B. Floor stops: As scheduled with strike of suitable height to compensate for clearance between door and floor.
1. Manufacturers: One of the following or equal:
a. Ives.
b. Trimco.
c. Rockwood.
C. Mechanical holders: Foot-operated plunger with instant release by touch of toe and integral spring to keep constant shoe pressure against floor; brass.
1. Manufacturers: The following or equal:
a. Glynn-Johnson.
D. Electromagnetic holders: Electromagnetic hold open device; able to be connected to smoke alarm system; UL BHMA listed; consisting of completely flush wall-mounted electro-magnetic holder and door thru-bolted contact plate; depth as required; with minimum holding force of 25 and maximum of 40 pounds; voltage and mounting height as indicated on the Drawings; steel.
1. Manufacturers: One of the following or equal:
a. Rixson-Firemark Inc., Electromagnetic Door Release Model 990 Series. b. LCN Electromagnetic Door Release Model SEM 7800 Series. c. Dorma Door Controls Inc., Electromagnetic Door Holder Model Series EM.
E. Flush bolts and surface bolts:
1. BHMA A156.3 and A156.16, Grade 1, certified.
a. Flush bolts to be furnished with top rod of sufficient length to allow bolt retraction device location approximately 6 feet from the floor. b. Furnish dust proof strikes for bottom bolts.
c. Surface bolts to be minimum 8 inches in length, UL listed for labeled fire doors, and UL listed for windstorm components where applicable. d. Provide related accessories (mounting brackets, strikes, coordinators, etc.) as required for appropriate installation and operation. e. Manufacturers: One of the following or equal:
1) Ives (IV).
2) Rockwood Products; ASSA ABLOY Architectural Door Accessories (RO).
3) Trimco (TC).
Door Hardware
08710-11 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08710 (BidSetFinal) F. Kick plates:
1. As scheduled, 0.050-inch thick, beveled edges, 10 inches high, 1-1/2 inches narrower than single doors, 1 inch narrower than leaf of door pairs.
2. Manufacturers: One of the following or equal:
a. Ives.
b. Trimco.
G. Architectural seals:
1. General:
a. Thresholds, weatherstripping, and gasket seals to be of type and design as specified below or in the Hardware Sets.
b. Provide continuous weatherstrip gasketing on exterior doors and provide smoke, light, or sound gasketing on interior doors where indicated. c. At exterior applications provide non-corrosive fasteners and elsewhere where indicated.
2. Smoke labeled gasketing:
a. Assemblies in accordance with NFPA 105 that are listed and labeled by a testing and inspecting agency acceptable to authorities having jurisdiction, for smoke control ratings indicated, based on testing in accordance with UL 1784.
b. Provide smoke labeled perimeter gasketing at all smoke labeled openings.
3. Fire labeled gasketing:
a. Assemblies in accordance with NFPA 80 that are listed and labeled by a testing and inspecting agency acceptable to authorities having jurisdiction, for fire ratings indicated, based on testing in accordance with UL 10C. b. Provide intumescent seals as indicated to meet UL 10C, and NFPA 252.
4. Sound-rated gasketing:
a. Assemblies that are listed and labeled by a testing and inspecting agency, for sound ratings indicated.
5. Replaceable seal strips:
a. Provide only those units where resilient or flexible seal strips are easily replaceable and readily available from stocks maintained by manufacturer.
6. Manufacturers: One of the following or equal:
a. National Guard Products (NG).
b. Pemko Products; ASSA ABLOY Architectural Door Accessories (PE). c. Zero (ZE).
H. Thresholds:
1. As scheduled, extruded aluminum, maximum 1/2-inch high, maximum slope of 1 foot in 2 feet.
2. Manufacturers: One of the following or equal:
a. National Guard Products Inc.
b. Pemko Mfg. Co.
I. Dustproof strike:
1. As scheduled.
2. Manufacturers: One of the following or equal:
a. Ives.
b. Trimco.
Door Hardware
08710-12 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08710 (BidSetFinal) J. Coordinator with filler bar:
1. As scheduled, non-handed, series type length as required for door sizes indicated, complete with filer lengths as required, with mounting brackets and carry bars when required for proper operation; steel with manufacturer's standard prime finish capable of receiving painted finish.
2. Manufacturers: One of the following or equal:
a. Glynn-Johnson Coordinators, Model COR Series.
b. Ives, Door Co-Ordinator, Model 900 Series.
K. Door bottoms:
1. As scheduled, extruded aluminum with vinyl insert, surface mounted, length equal to door width minus 2 inches, automatic, recessed in bottom of door.
2. Manufacturers: One of the following or equal:
a. Pemko.
b. Reese.
L. Astragals:
1. As specified in Sections 08110 - Hollow Metal Doors and Frames.
M. Silencers:
1. As scheduled, pneumatic gray rubber.
2. Manufacturers: One of the following or equal:
a. Trimco.
b. Ives.
c. Rockwood.
2.12 FINISHES
A. Brass and bronze: BHMA A156.18 626 (US26D), satin chrome.
B. Steel: BHMA A156.18 652 (US26D), satin chrome.
C. Stainless steel: BHMA A156.18 630 (US32D), satin stainless steel.
D. Aluminum: BHMA A156.18 628 (US28).
E. Plastic closer covers: Spray paint to match typical door hardware finish.
F. Metal closer covers: Plate covers to match typical door hardware finish.
G. Electromagnetic hold open devices: Manufacturer's standard brushed zinc finish.
PART 3 EXECUTION
3.01 EXAMINATION
A. Inspect doors and door frames for damage or defects and examine hardware for compatibility with receiving conditions and suitable to intended use.
B. Verify that required wall backing has been installed.
Door Hardware
08710-13 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08710 (BidSetFinal)
3.02 INSTALLATION
A. Install finish hardware in accordance with manufacturer's templates and instructions.
1. Install each item of mechanical and electromechanical hardware and access control equipment to comply with manufacturer's written instructions and according to specifications.
2. Installers are to be trained and certified by the manufacturer on the proper installation and adjustment of fire, life safety, and security products including:
Hanging devices; locking devices; closing devices; and seals.
B. Accurately and properly fit hardware.
C. Securely fasten fixed parts for smooth, trouble-free, non-binding operation.
D. Fit faces of mortise parts snug and flush.
E. Ensure that operating parts move freely and smoothly without binding, sticking, or excessive clearance.
F. Mounting heights:
1. Mount door hardware units at heights indicated in following applicable publications, unless specifically indicated or required to comply with governing regulations:
2. Standard steel doors and frames: DHI's "Recommended Locations for Architectural Hardware for Standard Steel Doors and Frames."
3. Wood doors: DHI WDHS.3, "Recommended Locations for Architectural Hardware for Wood Flush Doors."
4. Where indicated to comply with accessibility requirements, in accordance with ICC A117.1 "Accessibility Guidelines for Buildings and Facilities."
5. Provide blocking in drywall partitions where wall stops or other wall mounted hardware is located.
G. Retrofitting:
1. Install door hardware to comply with manufacturer's published templates and written instructions.
2. Where cutting and fitting are required to install door hardware onto or into surfaces that are later to be painted or finished in another way, coordinate removal, storage, and reinstallation of surface protective trim units with finishing work specified in Section 09910 - Painting.
3. Do not install surface-mounted items until finishes have been completed on substrates involved.
H. Protection:
1. Protect door hardware from damage or marring of finish during construction, use strippable coatings, removable tapes, or other acceptable means.
2. Ensure door hardware displays no evidence of finish paint after final building cleanup.
I. Latch guard and dead bolts: Install so that bolts automatically engage in keeper, whether activated by closer or by manual pressure.
Door Hardware
08710-14 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08710 (BidSetFinal) J. Closers:
1. Mount on opposite sides of corridors or vestibules, except at exterior doors.
2. Mount for 180-degree swing wherever possible.
3. Mount with drop plates at narrow top rail doors.
4. Adjust to operate noiselessly and evenly.
5. Have closer manufacturer regulate closers prior to final acceptance of project.
K. Kick plates: Screw on push side of doors, unless otherwise indicated on the Drawings.
L. Gasketing: Mount to provide complete contact between door and frame, finished floor, or both; and weathertight enclosure.
M. Thresholds:
1. Install immediately before inspection for Substantial Completion or protect from heavy traffic damage during construction.
2. Cope to fit door frame profile and drill to suit required flush bolts and panic bolts.
3. Unless indicated on the Drawings to be set in grout, set in double bead of sealant, tightly fit at jambs, and make waterproof.
4. Set thresholds for exterior and acoustical doors in full bed of sealant complying with requirements specified in Section 07900 - Joint Sealants.
5. Fasten to concrete slab with 5/16-inch stainless steel flat head countersunk machine screws and concrete anchors at 8-inch centers.
N. Silencers:
1. Insert into predrilled holes in frames.
O. Storage:
1. Provide a secure lock up for hardware delivered to the project but not yet installed.
2. Control the handling and installation of hardware items so that the completion of the work will not be delayed by hardware losses before and after installation.
3.03 DOOR HARDWARE SETS
A. They are a guideline only and should not be considered a detailed hardware schedule.
B. Omitted items not included in a hardware set should be scheduled with the appropriate additional hardware required for proper application and functionality.
C. Quantities listed are for each pair of doors, or for each single door.
D. The Supplier is responsible for handing and sizing all products.
E. Where multiple options for a piece of hardware are given in a single line item, the Supplier shall provide the appropriate application for the opening.
F. Provide a list of Manufacturer’s Abbreviations.
Door Hardware
08710-15 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/08710 (BidSetFinal)
3.04 CONSTRUCTION KEYING
A. Insert construction inserts in cylinder cores of exterior doors, and doors requiring security and access for workman, unless otherwise directed by the Engineer.
3.05 ADJUSTING
A. Examine hardware in place for complete and proper installation. Lubricate bearing surfaces for proper function.
B. Replace, rework, or otherwise correct defective door hardware, including incorrect hand or function.
3.06 CLEANING
A. Remove protective materials and devices and thoroughly clean exposed surfaces of hardware.
B. Check for surface damage prior to final cleaning for acceptance of project.
END OF SECTION
Painting
09910-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09910 (BidSetFinal) SECTION 09910
PAINTING
PART 1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Field applied paints and coatings for normal exposures.
2. Painting Accessories.
1.02 DEFINITIONS
A. Paints: Manufacturer's best ready-mixed coatings, except when field catalyzed, with fully ground pigments having soft paste consistency and capable of being readily and uniformly dispersed to complete homogeneous mixture, having good flowing and brushing properties, and capable of drying or curing free of streaks or sags.
B. Volatile Organic Compound (VOC): Content of air polluting hydrocarbons in uncured coating product measured in units of grams per liter or pounds per gallon.
1.03 SUBMITTALS
A. General: Submit as specified in Section 01330 - Submittal Procedures.
B. Shop drawings: Include schedule of where and for what use coating materials are proposed in accordance with requirements for Product Data.
C. Product data: Include description of physical properties of coatings including solids content and ingredient analysis, VOC content, temperature resistance, typical exposures and limitations, and manufacturer's standard color chips.
D. Samples: Include 8-inch square draw-downs or brush-outs of topcoat finish when requested. Identify each sample as to finish, formula, color name and number and sheen name and gloss units.
E. Manufacturer's instructions: Submit in accordance with requirements for Product Data. Include:
1. Special requirements for transportation and storage.
2. Mixing instructions.
3. Shelf life.
4. Pot life of material.
5. Precautions for applications free of defects.
6. Surface preparation.
7. Method of application.
8. Recommended number of coats.
9. Recommended thickness of each coat.
10. Recommended total thickness.
Painting
09910-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09910 (BidSetFinal)
11. Drying time of each coat, including prime coat.
12. Required prime coat.
13. Compatible and non-compatible prime coats.
14. Recommended thinners, when recommended.
15. Limits of ambient conditions during and after application.
16. Time allowed between coats.
17. Required protection from sun, wind, and other conditions.
18. Touch-up requirements and limitations.
F. Submit notarized certificate that:
1. All paints and coatings to be used on this project comply with the State of California Air Resources Board Rule 1113 VOC Regulations effective as of January 1, 2004; and that
2. All paints and coatings to be used on this project comply with the VOC regulations of the State of California Air Management District in which the coatings will be used, effective January 1, 2004.
1.04 QUALITY ASSURANCE
A. Products: First line or best grade.
B. Materials for each paint system: By single manufacturer.
C. Applicator qualifications: Applicator of products similar to specified products with minimum 3 years of experience.
D. Regulatory requirements: Comply with by using paints that do not exceed governing agency's VOC limits or do not contain lead.
E. Field samples:
1. Paint 1 complete surface of each color scheme to show colors, finish texture, materials, and workmanship.
2. Obtain approval before painting other surfaces.
1.05 PRODUCT DELIVERY, STORAGE, AND HANDLING
A. Deliver, store, and handle products as specified in Section 01600 - Product Requirements.
B. Remove unspecified and unapproved paints from Project site immediately.
C. Deliver containers with labels identifying:
1. Manufacturer's name.
2. Brand name.
3. Product type.
4. Batch number.
5. Date of manufacturer.
6. Expiration date or shelf life.
7. Color.
8. Mixing and reducing instructions.
Painting
09910-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09910 (BidSetFinal) D. Store coatings in well-ventilated facility that provides protection from the sun weather, and fire hazards.
1. Maintain ambient storage temperature between 45 and 90 degrees Fahrenheit, unless otherwise recommended by the manufacturer.
E. Take precautions to prevent fire and spontaneous combustion.
1.06 ENVIRONMENTAL CONDITIONS
A. Surface moisture contents: Do not paint surfaces that exceed manufacturer specified moisture contents, or when not specified by the manufacturer, the following moisture contents:
1. Plaster and gypsum wallboard: 12 percent.
2. Masonry, concrete, and concrete block: 12 percent.
3. Interior located wood: 15 percent.
4. Concrete floors: 7 percent.
B. Do not paint or coat:
1. Under dusty conditions.
2. When light on surfaces measures less than 15 foot-candles.
3. When ambient or surface temperature is less than 50 degrees Fahrenheit or unless manufacturer allow a lower temperature.
4. When relative humidity is higher than 85 percent, unless manufacturer allows a higher relative humidity.
5. When surface temperature is less than 5 degrees Fahrenheit above dew point.
6. When surface temperature exceeds the manufacturer's recommendation.
7. When ambient temperature exceeds 90 degrees Fahrenheit, unless manufacturer allows a higher temperature.
8. Apply clear finishes at minimum 65 degrees Fahrenheit.
C. Provide fans, heating devices, or other means recommended by coating manufacturer to prevent formation of condensate or dew on surface of substrate, coating between coats and within curing time following application of last coat.
D. Provide adequate continuous ventilation and sufficient heating facilities to maintain minimum 50 degrees Fahrenheit for 24 hours before, during and 48 hours after application of finishes.
1.07 PROTECTION
A. Protect adjacent surfaces from paint and damage. Repair damage resulting from inadequate or unsuitable protection.
B. Furnish sufficient drop cloths, shields, and protective equipment to prevent spray or droppings from fouling surfaces not being painted and in particular, surfaces within storage and preparation area.
C. Place cotton waste, cloths, and material that may constitute fire hazard in closed metal containers and remove daily from site.
Painting
09910-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09910 (BidSetFinal) D. Remove electrical plates, surface hardware, fittings and fastenings, prior to painting operations.
1. Carefully store, clean and replace on completion of painting in each area.
2. Do not use solvent or degreasers to clean hardware that may remove permanent lacquer finish.
1.08 EXTRA MATERIALS
A. Extra materials: Deliver as specified in Section 01770 - Closeout Procedures.
Include minimum 1 gallon of each type and color of coating applied:
1. When manufacturer packages material in gallon cans, deliver unopened labeled cans as comes from factory.
2. When manufacturer does not package material in gallon cans, deliver material in new gallon containers, properly sealed and identified with typed labels indicating brand, type, and color.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Paints: One of the following or equal:
1. Carboline: Carboline.
2. PPG Paints/PMC.
3. S/W: Sherwin-Williams Co.
4. Tnemec: Tnemec Co.
B. Submit requests for substitutions as specified in Section 01600 - Product Requirements:
1. Include certified ingredient analyses.
2. Provide colors that match specified colors.
2.02 PRETREATMENT, PRIMERS, PRIMER-SEALERS, AND WOOD STAIN A. Aluminum primer:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Carbocrylic 120.
b. PPG: Pitt-Tech® Plus 4020 PF Interior/Exterior Primer/Finish, 4020PF. c. Sherwin-Williams Co.: DTM Wash Primer.
B. Concrete masonry filler/primer:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Sanitile 100.
b. PPG: Perma-Crete® Interior/Exterior Block and Masonry Surfacer/Filler, 4-100XI.
c. Sherwin-Williams Co.: HD Block Filler, B42W46.
d. Tnemec:
1) Series 130, Envirofill.
2) Series 180, Tneme-crete.
Painting
09910-5 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09910 (BidSetFinal) C. Concrete, porous, filler/primer:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Sanitile 100.
b. PPG: Perma-Crete® Interior/Exterior Block and Masonry Surfacer/Filler, 4-100XI.
c. Sherwin-Williams Co.: HD Block Filler, B42W46.
d. Tnemec:
1) Series 130, Envirofill.
2) Series 180, Tneme-crete.
D. Concrete, smooth, filler/primer:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Sanitile 100.
b. Carboline Co.: Carbocrylic 120.
c. PPG:
1) Perma-Crete® Interior/Exterior Block and Masonry Surfacer/Filler, 4-100XI.
2) Seal Grip® Hydrosealer Exterior Bonding Primer/Sealer, 17-6001. d. Sherwin-Williams Co.:
1) HD Block Filler, B42W46.
2) Epoxy Masonry Tilt Primer White B42WW49.
e. Tnemec: Series 180, Tneme-Crete.
E. Ferrous metal primer:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Carboguard 890.
b. PPG: PITT-GUARD® Rapid-Coat Direct-to-Rust Epoxy Mastic Coating, 95-245 Series.
c. Sherwin-Williams Co.: Macropoxy 646.
d. Tnemec: Series 104.
F. Galvanized metal surface pretreatment materials:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Surface Cleaner 3.
b. PPG: Duraprep® Concentrated Degreaser, Prep125.
G. Galvanized metal surface primer:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Carboguard 890.
b. PPG: PITT-GUARD® Rapid-Coat Direct-to-Rust Epoxy Mastic Coating, 95-245 Series Sherwin-Williams Co.: Macropoxy 646.
c. Tnemec: Series 104.
H. Plaster sealer:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Sanitile 120.
b. PPG: Seal Grip® Gripper® Universal Interior/Exterior Primer/Sealer, 17-921XI.
c. Sherwin-Williams Co.:
1) Promar 200 Primer B28W8200.
2) Loxon Masonry Primer A24W300.
Painting
09910-6 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09910 (BidSetFinal) I. Plywood, latex finishes:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Sanitile 120.
b. PPG:
1) Exterior: Seal Grip® Hydrosealer Exterior Bonding Primer/Sealer, 17-6001.
2) Interior: PPG Seal Grip Gripper Interior/Exterior 100 percent Acrylic Latex Primer, 17-921XI Series.
c. Sherwin-Williams Co.: A100 Latex Primer B42W8041.
J. Wood primer for opaque finish paint, interior exposure:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Sanitile 120.
b. PPG: PPG Seal Grip Gripper Interior/Exterior 100 percent Acrylic Latex Primer, 17-921XI Series.
c. Sherwin-Williams Co.: PrepRite Latex Primer B28W111.
K. Wood primer for opaque finish paint, exterior exposure:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Sanitile 120.
b. Sherwin-Williams Co.: A-100 Primer B42W.
c. PPG: Seal Grip® Hydrosealer Exterior Bonding Primer/Sealer, 17-6001.
L. Wood stain:
1. Manufacturers: One of following or equal:
a. Sherwin-Williams Co.:
1) Interior: Wood Classic.
2) Exterior: Woodscapes.
b. PPG:
1) Interior: DEFT.
2) Exterior: PROLUXE.
2.03 PAINTS, INTERIOR EXPOSURE
A. Latex, flat:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Carbocrylic 3359 MC flat.
b. PPG:
1) Speedhide® Zero Interior Flat, 6-5110 Series.
2) Ultralast Interior Matte, 13-210 Series.
c. Sherwin-Williams Co.: Promar 200, B30W200.
B. Latex, semi-gloss:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Carbocrylic 3359 MC.
b. PPG:
1) Speedhide® Zero Interior Semi-Gloss, 6-5510 Series.
2) Copper Armor Interior Latex Paint + Primer Semi-Gloss, 29-1510. c. Sherwin-Williams Co.: Promar 200, B77W3402D.
Painting
09910-7 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09910 (BidSetFinal) C. Acrylic, semi-gloss:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Carbocrylic 3359 MC.
b. PPG:
1) Speedhide® Zero Interior Semi-Gloss, 6-5510 Series.
2) Copper Armor Interior Latex Paint + Primer Semi-Gloss, 29-1510. c. Sherwin-Williams Co.: Promar 200, B77W3402D.
d. Tnemec: Series 1029, Enduratone.
2.04 PAINTS, EXTERIOR EXPOSURE
A. Latex, flat:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Carbocrylic 3359 MC flat.
b. PPG:
1) Speedhide® Exterior Flat, 6-6510XI.
c. Sherwin-Williams Co.: A-100, Flat Exterior Latex A6-100. d. Tnemec: 1028 Enduratone.
B. Acrylic latex, semi-gloss:
1. Manufacturers: One of following or equal:
a. Carboline Co.: Carbocrylic 3359 MC flat.
b. PPG:
1) Speedhide® Exterior Semi-Gloss, 6-901XI.Sherwin-Williams Co.:
A-100, Flat Exterior Latex A6-100.
c. Tnemec: 1028 Enduratone.
PART 3 EXECUTION
3.01 INSPECTION
A. Thoroughly examine surfaces scheduled to be painted before starting work.
B. Start painting when unsatisfactory conditions have been corrected.
3.02 SURFACE PREPARATION
A. Prepare surfaces in accordance with paint manufacturer's instructions or when none, the following:
1. Aluminum:
a. Remove surface contamination by steam, high-pressure water, or degreasers.
b. Abrade surface by abrasive blasting, power tool cleaning or hand tool cleaning.
c. Apply etching primer.
2. Reinforced concrete panels:
a. Remove dirt, powdery residue, and foreign matter.
b. Paint immediately; both sides when applicable.
3. Canvas and cotton insulation coverings: Remove dirt, grease, and oil.
Painting
09910-8 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09910 (BidSetFinal)
4. Concrete floors:
a. Remove contamination, abrasive blast or acid etch and rinse with clear water.
b. Ensure required acid-alkali balance is achieved. Allow to dry thoroughly.
5. Copper for paint finish:
a. Remove contamination by steam, high-pressure water, or degreasers. b. Abrade surface by abrasive blasting, power tool cleaning or hand tool cleaning.
c. Apply vinyl etch primer.
6. Copper for oxidized finish:
a. Remove contamination.
b. Apply oxidizing solution of copper acetate and ammonium chloride in acetic acid.
c. Rub on repeatedly for correct effect.
d. Once attained rinse surfaces well with clear water and allow to dry.
7. Gypsum wallboard:
a. Remove contamination and prime to show defects.
b. Repair and prime defects.
8. Galvanized surfaces:
a. Remove surface contamination and oils and wash with degreasers. b. Apply coat of etching type primer.
9. Zinc coated surfaces: Remove surface contamination and oils and prepare for priming in accordance with metal manufacturer's recommendations.
10. Concrete and concrete masonry:
a. Remove dirt, loose mortar, scale, powder, and other foreign matter. b. Remove oil and grease with solution of tri-sodium phosphate. c. Remove stains caused by weathering of corroding metals with solution of sodium metasilicate.
d. Rinse well and allow to thoroughly dry.
e. Spot prime exposed metal with alkyd primer.
11. Plaster:
a. Fill hairline cracks, small holes and imperfections with patching plaster. b. Smooth off to match adjacent surfaces.
c. Wash and neutralize high alkali surfaces where they occur.
12. Unprimed steel and iron: Remove grease, rust, scale, dirt, and dust by wire brushing, sandblasting or other necessary method.
13. Shop primed steel:
a. Sand and scrape to remove loose primer and rust.
b. Feather out edges to make touch-up patches inconspicuous. c. Clean surfaces.
d. Prime bare steel surfaces.
14. Wood and millwork:
a. Sandpaper to smooth even surface.
b. Wipe off dust and grit prior to priming.
c. Spot coat knots, pitch streaks, and sappy sections with sealer. d. Fill nail holes and cracks after primer has dried and sand between coats.
15. Exterior wood siding:
a. Remove dust, grit, and foreign matter.
b. Seal knots, pitch streak, and sappy sections.
c. Fill nail holes with exterior caulking compound after prime coat has been applied.
Painting
09910-9 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09910 (BidSetFinal)
16. Mildew:
a. Remove by scrubbing with solution of tri-sodium phosphate and chlorine bleach.
b. Rinse with clean water and allow surface to dry completely.
17. Glue laminated woods:
a. Remove grease and dirt.
b. Wash down surfaces with degreasers.
3.03 APPLICATION
A. Apply each coat at proper consistency.
B. Tint each coat of paint slightly darker than preceding coat.
C. Sand lightly between coats to achieve required finish.
D. Do not apply finishes on surfaces that are not sufficiently dry.
E. Allow each coat of finish to dry before following coat is applied, unless directed otherwise by manufacturer.
F. Where clear finishes are required ensure tint fillers match wood.
1. Work fillers well into grain before set.
2. Wipe excess from surface.
G. Backprime exterior woodwork, which is to receive paint finish, with exterior primer paint.
H. Backprime interior woodwork, which is to receive paint or enamel finish, with enamel undercoat paint.
I. Backprime interior and exterior woodwork, which is to receive stain or varnish finish, with gloss varnish reduced 25 percent with mineral spirits.
J. Prime top and bottom edges of wood and metal doors with enamel undercoat when they are to be painted.
K. Prime top and bottom edges of wood doors with gloss varnish when they are to receive stain or clear finish.
3.04 MECHANICAL AND ELECTRICAL EQUIPMENT
A. Identify equipment, ducting, piping, and conduit in accordance with Related Sections.
B. Remove grilles, covers, and access panels for mechanical and electrical system from location and paint separately.
C. Finish paint primed equipment with color selected by the Engineer.
Painting
09910-10 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09910 (BidSetFinal) D. Prime and paint insulated and bare pipes, conduits, boxes, insulated and bare ducts, hangers, brackets, collars, and supports, except where items are plated or covered with prefinished coating.
E. Replace identification markings on mechanical or electrical equipment when painted over or spattered.
F. Paint interior surfaces of air ducts, convector, and baseboard heating cabinets that are visible through grilles and louvers with 1 coat of flat black paint, to limit of sight line.
G. Paint dampers exposed immediately behind louvers, grilles, convector, and baseboard cabinets to match face panels.
H. Paint exposed conduit and electrical equipment occurring in finished areas with color and texture to match adjacent surfaces.
I. Paint both sides and edges of plywood backboards for electrical equipment before installing backboards and mounting equipment on them.
J. Color code equipment, piping, conduit, exposed ductwork, and apply color banding and identification, such as flow arrows, naming and numbering, in accordance with the Contract Documents.
3.05 SURFACES NOT REQUIRING FINISHING
A. Stainless steel, brass, bronze, copper, Monel®, chromium, anodized aluminum:
Specially finished articles such as porcelain enamel, plastic coated fabrics, and baked enamel.
B. Finished products such as ceramic tile, windows, glass, brick, resilient flooring, acoustical tiles, board and metal tees; other architectural features, such as finish hardware, furnished in aluminum, bronze or plated ferrous metal, prefinished panels, or other items that are installed prefinished.
C. Items completely finished at factory, such as preformed metal roof and wall panels, aluminum frames, toilet compartments, sound control panels, acoustical tiles, shower compartments, folding partition, and flagpole.
3.06 CLEANING
A. As work proceeds and upon completion, promptly remove paint where spilled, splashed, or spattered.
B. During progress of work, keep premises free from unnecessary accumulation of tools, equipment, surplus materials, and debris.
C. Upon completion of work, leave premises neat and clean.
Painting
09910-11 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09910 (BidSetFinal)
3.07 INTERIOR PAINT SCHEDULE
A. Aluminum: 2 coats of following finish paints over specified primer:
1. Acrylic, semi-gloss:
a. Surfaces not scheduled otherwise.
B. Concrete masonry: 2 coats of following finish paints over block filler:
1. Latex, semi-gloss:
a. Walls.
C. Concrete, smooth: 2 coats of following finish paints over specified sealer:
1. Latex, flat:
a. Surfaces not scheduled otherwise.
D. Metal, non-galvanized ferrous: 2 coats of following finish paints over specified primer:
1. Acrylic, semi-gloss:
a. Surfaces not scheduled otherwise.
3.08 EXTERIOR PAINT SCHEDULE
A. Aluminum: 2 coats of following finish paints over specified primer:
1. Acrylic, semi-gloss:
a. Surfaces not scheduled otherwise.
B. Concrete masonry: 2 coats of following finish paints over specified block filler:
1. Latex, flat:
a. Surface not scheduled otherwise.
C. Concrete, smooth: 2 coats of following finish paints over specified primer:
1. Latex, flat:
a. Surface not scheduled otherwise.
D. Metal, ferrous: Following finish coat over specified primer:
1. Acrylic, semi-gloss:
a. Surface not scheduled otherwise.
E. Metal, galvanized: 2 coats of following finish paints over pretreatment and specified primer:
1. Acrylic, semi-gloss:
a. Surface not scheduled otherwise.
END OF SECTION
High-Performance Coatings
09960-1 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09960 (BidSetFinal) SECTION 09960
HIGH-PERFORMANCE COATINGS
TABLE OF CONTENTS
PART 1 GENERAL ................................................................................................................. 2
1.01 SUMMARY ................................................................................................................... 2
1.02 REFERENCES ............................................................................................................. 2
1.03 DEFINITIONS ............................................................................................................... 3
1.04 ABBREVIATIONS ......................................................................................................... 5
1.05 SUBMITTALS ............................................................................................................... 6
1.06 QUALITY ASSURANCE ............................................................................................... 8
1.07 PRODUCT DELIVERY, STORAGE, AND HANDLING .............................................. 10
1.08 PROJECT CONDITIONS ........................................................................................... 11
1.09 MAINTENANCE ......................................................................................................... 13
1.10 CTR RESPONSIBILITIES .......................................................................................... 13 PART 2 PRODUCTS ............................................................................................................ 15
2.01 DESIGN AND PERFORMANCE CRITERIA .............................................................. 15
2.02 MATERIALS ............................................................................................................... 15
2.03 COATING SYSTEMS IDENTIFICATION ................................................................... 15
2.04 PRODUCTS FOR COATING SYSTEMS ................................................................... 16 PART 3 EXECUTION ........................................................................................................... 16
3.01 GENERAL PROTECTION REQUIREMENTS ............................................................ 16
3.02 GENERAL SURFACE PREPARATION REQUIREMENTS ....................................... 17
3.03 MECHANICAL AND ELECTRICAL EQUIPMENT PREPARATION ........................... 18
3.04 CLEANING OF NEW AND PREVIOUSLY COATED OR NEW SURFACES ............. 18
3.05 BLAST CLEANING ..................................................................................................... 19
3.06 PREPARATION REQUIREMENTS FOR CONCRETE SURFACES ......................... 20
3.07 GENERAL PREPARATION REQUIREMENTS FOR METALLIC SURFACES .......... 21
3.08 PREPARATION REQUIREMENTS BY SURFACE TYPE ......................................... 22
3.09 APPLICATION REQUIREMENTS .............................................................................. 23
3.10 APPLICATION REQUIREMENTS FOR CONCRETE COATING SYSTEMS ............ 27
3.11 COATING SYSTEM SCHEDULE ............................................................................... 28
3.12 SURFACES NOT REQUIRING COATING ................................................................. 28
3.13 QUALITY CONTROL .................................................................................................. 29
3.14 CORRECTIVE MEASURES ....................................................................................... 30
3.15 CLEANUP ................................................................................................................... 30
3.16 FINAL INSPECTION .................................................................................................. 30
ATTACHMENT A - SCHEDULE OF SURFACES TO BE COATED
ATTACHMENT B - COATING DETAIL SHEETS
High-Performance Coatings
09960-2 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09960 (BidSetFinal) PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Coatings, including coating systems, surface preparation, application requirements, and quality control requirements.
1.02 REFERENCES
A. ASTM International (ASTM):
1. D16 - Standard Terminology for Paint, Related Coatings, Materials, and Applications.
2. D2200 - Standard Practice for Use of Pictorial Surface Preparation Standards and Guides for Painting Steel Surfaces.
3. D3359 - Standard Test Methods for Rating Adhesion by Tape Test.
4. D3960 - Standard Practice for Determining Volatile Organic Compound (VOC) Content of Paints and Related Coatings.
5. D4262 - Standard Test Method for pH of Chemically Cleaned or Etched Concrete Surfaces.
6. D4263 - Standard Test Method for Indicating Moisture in Concrete by the Plastic Sheet Method.
7. D4285 - Standard Test Method for Indicating Oil or Water in Compressed Air.
8. D4414 - Standard Practice for Measurement of Wet Film Thickness by Notch Gages.
9. D4417 - Standard Test Methods for Field Measurement of Surface Profile of Blast-Cleaned Steel.
10. D4541 - Standard Test Methods for Pull-Off Strength of Coatings Using Portable Adhesion Testers.
11. D4787 - Standard Practice for Continuity Verification of Liquid or Sheet Linings Applied to Concrete Substrates.
12. D5162 - Standard Practice for Discontinuity (Holiday) Testing of Nonconductive Protective Coating on Metallic Substrates.
13. D7234 - Standard Test Method for Pull-Off Adhesion Strength of Coatings on Concrete Using Portable Pull-Off Adhesion Testers.
14. E337 - Standard Test Method for Measuring Humidity with a Psychrometer (the Measurement of Wet- and Dry-Bulb Temperatures).
15. F1869 - Standard Test Method for Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride.
16. F2170 - Standard Test Method for Determining Relative Humidity in Concrete Floor Slabs Using In-situ Probes.
B. International Concrete Repair Institute (ICRI):
1. 310.2 - Guideline for Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings, Polymer Overlays, and Concrete Repair.
C. NACE International (NACE):
1. SP0178 - Design, Fabrication, and Surface Finish Practices for Tanks and Vessels to Be Lined for Immersion Service.
2. SP0188 - Discontinuity (Holiday) Testing of New Protective Coatings on Conductive Substrates.
High-Performance Coatings
09960-3 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09960 (BidSetFinal) D. National Association of Pipe Fabricators (NAPF):
1. 500-03 - Surface Preparation Standard for Ductile Iron Pipe and Fittings in Exposed Locations Receiving Special External Coatings and/or Special Internal Linings.
E. NSF International (NSF):
1. 61 - Drinking Water System Components - Health Effects.
F. Occupational Safety and Health Administration (OSHA).
G. Society of Protective Coatings (SSPC):
1. Glossary - SSPC Protective Coatings Glossary.
2. Guide 6 - Guide for Containing Surface Preparation Debris Generated during Paint Removal Operations.
3. Guide 15 - Field Methods for Retrieval and Analysis of Soluble Salts on Steel and Other Nonporous Substrates.
4. PA 1 - Shop, Field, and Maintenance Painting of Steel.
5. PA 2 - Procedure for Determining Conformance to Dry Coating Thickness Requirements.
6. PA 9 - Measurement of Dry Coating Thickness Using Ultrasonic Gages.
7. QP 1 - Standard Procedure for Evaluating the Qualifications of Industrial/Marine Painting Contractors.
8. SP 1 - Solvent Cleaning.
9. SP 3 - Power Tool Cleaning.
10. SP 5 - White Metal Blast Cleaning.
11. SP 10 - Near-White Metal Blast Cleaning.
12. SP 11 – Power Tools Cleaning to Bare Metal.
13. SP 13 - Surface Preparation of Concrete.
14. SP 16 - Brush-Off Blast Cleaning of Coated and Uncoated Galvanized Steel, Stainless Steels, and Non-Ferrous Metals.
15. SP COM - Surface Preparation Commentary.
16. SP VIS 1 - Guide and Reference Photographs for Steel Surfaces Prepared by Dry Abrasive Blast Cleaning.
17. SP WJ-1 - Waterjet Cleaning of Metals - Clean to Bare Substrate.
18. SP WJ-2 - Waterjet Cleaning of Metals - Very Thorough Cleaning.
19. SP WJ-3 - Waterjet Cleaning of Metals - Thorough Cleaning.
20. SP WJ-4 - Waterjet Cleaning of Metals - Light Cleaning.
1.03 DEFINITIONS
A. Definitions used in this Section are in accordance with definitions referenced in ASTM D16, ASTM D3960, and SSPC Glossary of Definitions.
B. Specific definitions:
1. Abrasive: Material used for blast cleaning, such as sand, grit, or shot.
2. Abrasive Blast Cleaning: Cleaning/surface preparation by abrasive propelled at high speed.
3. Anchor Pattern: Profile or texture of prepared surface(s).
4. Biogenic Sulfide Corrosion: Corrosion caused by sulfuric acid formed when Thiobacillus bacteria metabolizes hydrogen sulfide.
High-Performance Coatings
09960-4 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09960 (BidSetFinal)
5. Bug Holes: Small cavities resulting when air bubbles are entrapped in the surface of formed concrete during placement and consolidation.
6. System: Protective film with 1 or more coats applied in a predetermined order, including surface preparation and quality control requirements.
7. Coating/Paint/Lining Thickness: Total thickness of primer, intermediate, and/or finish coats after drying or curing.
8. Dew point: Temperature a given air/water vapor mixture starts to condense.
9. Drying Time: Time interval between application and material curing.
10. Dry to Recoat: Time interval between material application and its ability to receive the next coat.
11. Dry to Touch: Time interval between material application and its ability to tolerate a light ouch without coating damage.
12. Exposed Surface: Any indoor or outdoor surface not buried or encased.
13. Feather Edging: Reducing coating thickness at its edge to blend with existing surrounding coating.
14. Feathering: Tapering off a wet edge with a comparatively dry brush.
15. Ferrous: Cast iron, ductile iron, wrought iron, and all steel alloys except stainless steel.
16. Field Coat: Application of a surface coating system at the work site.
17. Finish Coat: Final coat in a paint system, including texture, color, smoothness of surface, and other properties affecting appearance.
18. Hold Point: A defined point, specified in this Section, at which work shall be halted for inspection.
19. Holiday: A discontinuity, skip, void, or pinhole in coating or coating system film that exposes the substrate.
20. Honeycomb: Segregated and porous surface of hardened concrete due to insufficient consolidation.
21. Hydroblast: High or ultra-high-pressure water jet surface preparation.
22. Incompatibility: One coating's inability to overlay another coating or surface as evidenced by bleeding, poor bonding, or lifting of old coating; inability of a coating to bond to a substrate.
23. Immersed/Immersion: A service condition in which substrate is submerged, is immediately above liquids, or is subject to frequent wetting, splashing, or washdown.
24. Laitance: A thin, weak, brittle layer of cement and aggregate fines on a concrete surface.
25. Mil: 0.001 inch.
26. Overspray: Dry spray, particularly paint bonded to an unintended surface.
27. Pinhole: A small diameter discontinuity in a coating or coating system film, created by offgassing from a void in a concrete or masonry substrate causing a void between coats or exposing the substrate. Usually caused by coating application while temperature is rising.
28. Pot Life: Time interval after components are mixed and coating can be satisfactorily applied.
29. Prime Coat: First full paint coat applied to a surface when using a multicoat system. Primers adhere to a new substrate, protect the substrate, and promote adhesion of subsequent coats of paint. The prime coat on metal surfaces is the first full coat and does not include solvent wash, grease emulsifiers, or other pretreatment applications.
High-Performance Coatings
09960-5 8660F10 April 2023
pw://Carollo/Documents/Client/CA/Ukiah/8660F10/Specifications/New Scope/09960 (BidSetFinal)
30. Resurfacer/Resurfacing Material: A layer of cementitious and/or resin-based material used to fill or otherwise restore surface continuity to worn or damaged concrete surfaces.
31. Shelf Life: Maximum storage time a material may be stored without losing its usefulness.
32. Shop Coat: 1 or more coats applied in an off-site shop or plant before shipment to work site where field or finishing coat(s) are applied.
33. Spreading Rate: Area covered by a unit volume of paint at a specific thickness.
34. Stripe Coat: A separate brush coat of paint applied to all weld seams, pits, nuts/bolts/washers, and edges. This coat shall not be applied until previous coats have cured. Once applied, the coat shall be allowed to cure before subsequent coats are applied.
35. Tie Coat: An intermediate coat that bonds different types of paint material, improving succeeding coat adhesion.
36. Thick Film Coating System: A coating system applied with a minimum dry film thickness of 25 mils.
37. Touch-Up Painting: Application of paint on previously painted surfaces to repair marks, scratches, and deteriorated or damaged areas to restore the appearance and performance of the coating.
38. Water Blast: An alternative to air abrasive blast cleaning that can be used with or without abrasive injection. Water cleaning at pressures up to 5,000 pounds per square inch is called low-pressure water cleaning or power washing.
High-pressure water cleaning uses water pressures between 5,000 and 10,000 pounds per square inch. Water jetting is water blasting with added abrasive at pressures between 10,000 and 25,000 pounds per square inch.
Ultra-high-pressure water jetting is water blasting at pressures above 25,000 pounds per square inch.
39. Weld Splatter: Beads of non-structural weld metal that adhere to the surrounding surface, removed as part of surface preparation.
1.04 ABBREVIATIONS
A. CSM - Coating System Manufacturer.
B. CMU - Concrete Masonry Units.
C. CSA - Coating System Applicator. Specialty subcontractor retained by the Contractor to install the coating systems specified in this Section.
D. CTR - Coating System Manufacturer's Technical Representative.
E. DFT - Dry-Film Thickness. Thickness of cured film, usually expressed in mils (0.001 inch).
F. SSD - Surface Saturated Dry. Refers to concrete surface condition where the surface is saturated (damp) without the presence of standing water.
G. TPC - Technical Practice Committee.